Office Of Water
                                                    iT  ., ...........
                                        ,ici*:1 * itii1"v.i's*.1 i
-------

-------
                         ACKNOWLEDGEMENTS


This document was prepared by James Montgomery Consulting

Engineers, Pasadena, California, under EPA Contract 68-03-3429.

Arthur Condren was the Project Manager.  Charles Vanderlyn was

the EPA Project Officer.  Technical direction for the study was

provided by Lam Lim and Randy Revetta of the EPA Office of

Municipal Pollution Control and the members of the Rainfall

Induced Infiltration Study Workgroup.  Their time and      ;

contributions are gratefully acknowledged.
                        ,      NOTICE


This report has been reviewed by the U.S. Environmental
Protection Agency and approved for publication.  Mention of.trade
names or commercial products does not constitute endorsement or
recommendations for use.

-------

-------
RAINFALL INDUCED INFILTRATION

      INTO SEWER SYSTEMS



      REPORT TO CONGRESS
                       " /

          August 1990

-------

-------
                         TABLE OF CONTENTS            ,

      ..'"•.  •'..."   •   •  •, •  '  •      •  •    •     .   '"   .  . Page

EXECUTIVE  SUMMARY

    Study Authorization and Objectives                          i
    Background                                           > '  '   i
  .  Findings and. Conclusions               '         >      •    ii
    Recommendations                                    ,     ,   iv

DEFINITION                                                   vi?

CHAPTER 1  - INTRODUCTION

    Study Authorization and Objectives                        1-1
    Study Approach           .     ,                            .1-1
    Report Organization  , •                                    1-1

CHAPTER 2  - PROBLEM ASSESSMENT

    Background                .     '                        ,  2-1
    Definition of RII                                          2-3
    Problems Associated with RII                               2-4
    Possible RII Pathways and Flow Response                   2-5
    Entry Points of RII into Sanitary Sewer Systems            2-9,
    Factors Affecting  RII                              ..       2-10
    Case Studies                 \                            2-14
    Summary   '                     :                          , 2-27

CHAPTER 3  - CONTROL METHODS

    RII  Field Investigation Techniques                        3-1
    Sewer Rehabilitation Methods                               3-5
    Design Standards and Construction Practices               3-9
    RII  Control  Program Approaches                            3-10
    Cost Evaluation                                        -   3-12
    Institutional and  Regulatory  Approaches                   3-15
    Example RII  Control Program - EBMUD               .        3-17
    Summary                         /.'•-.'                  '  3-20
    Recommendations                                           3-21

Appendix A - List of  Abbreviations

Appendix B - References-
                                        i ••.,',     "             "
Appendix C - Case Studies
Appendix D - •

Sewer System Rehabilitation Methods
Appendix E —

Design and Construction  Standards

Appendix F - Cost Evaluation

-------

-------
                        Executive Summary ,
STUDY AUTHORIZATION AND OBJECTIVES

This Report to  Congress,  required by Section 523  of  the Federal
Water Quality Act of 1987  (Public Law 100-4), presents the results
of  an  Environmental Protection  Agency  (EPA)  study  of  rainfall
induced  infiltration  (RID  into  municipal  sanitary  sewerage
systems.  The following are .the objectives of the study:

    o    Study problems associated with RII.            -

 -.',' o    Study appropriate methods to control RII  into municipal
         sanitary sewerage systems,  including that  of the East Bay
         Municipal Utility District, California.

    o    Develop recommendations on, reasonable methods to reduce
                            '
BACKGROUND

The Clean Water Act  (CWA) of  1972  clearly established the intent
of  Congress  to  address  problems  associated with  the  entry  of
extraneous    storm    water    and    ground    water    ( termed
infiltration/inflow, or I/I)  into sanitary sewer systems.  The CWA
mandated that all "excessive"  I /I , be removed from a sanitary sewer
system  as  a  condition for  award of  a  construction grant  for
wastewater treatment facility improvements.  "Excessive" flow was
defined as that portion of the total extraneous flow that could be
cost-effectively  removed.   That  is,  the  cost  to  eliminate  the
excessive flow would be less than the cost to transport it in the
sewer system and provide wastewater treatment.                .

Based on the requirements of the CWA, EPA developed guidelines, for
identifying extraneous flow, and specifically for determining what
portion of the  extraneous  flow  was excessive.  A key concept  in
these guidelines  was the distinction between  "infiltration"  and
"inflow."  In general, infiltration was used to describe the long
term seepage of water  into sewers  through underground defects  in
the system.   Such  seepage was not considered to be directly related
to  recent  storm  events.   Inflow was  defined as water  entering
sewers  through direct connections',  such,  as  cooling  water  from
commercial and industrial buildings, cellar or yard drains, or roof
downspouts connected to sanitary sewers .

In. the years following the enactment of the 1972 law, communities
throughout  the  country  undertook sewer  system  rehabilitation
programs to remove the  flow that had been categorized as excessive.
Flows were reduced in: a number of such systems, while in others the
anticipated flow decreases did not occur.   One explanation of why
these programs  failed to  achieve the expected results  is  that

-------
                        Executive  Summary


infiltration   (which  is  generally  difficult  and  expensive  to
correct) may have been incorrectly identified as inflow, resulting
in an invalid or substantially overestimated assessment of the cost
effectiveness  of  correction.   Such  situations  can  occur  when
extraneous  flows  enter  the  sewer  system  through  traditional
infiltration points,  but  produce a peak flow response similar to
that of inflow.                            •

In  1987,  Congress  asked EPA to  investigate  this  problem.    We
conducted case studies in  10 cities or sewer  districts.   These
studies  attempted  to  gather   information  on:  an  appropriate
definition   of   rainfall   induced   infiltration    (RII);   the
characteristics  of RII;  the problems  associated with RII;  the
pathways and  entry points  into  the sewer system;  and the major
factors which influence the occurrence of RII.   Data on methods to
control or correct RII were obtained from the 10 case studies and
augmented through a review of the pertinent  literature.

FINDINGS AND CONCLUSIONS

The findings  and conclusions of the study  are grouped  into  two
sections, corresponding to  the  first  two  study objectives:  to
assess the problems associated with RII, arid to study methods of
RII control.                                                ,

Problem Assessment

The major findings  and conclusions of  the  study  with respect to
the characteristics  of,  and problems  associated with, RII  are
listed below:
 *                 '                                            *
    o    RII is  a type  of  infiltration since it enters the sewer
         system through defects.  However, its flow characteristics
         resemble those of inflow i.e., there is a rapid increase
         in flow which  mirrors  the rainfall  event  followed by a
         decrease as the rain stops.

    o    Because  of  its  flow  characteristics,   RII  has  been
         misidentified  as  inflow  in  many  cases.    Consequently,
         rehabilitation programs  have not achieved the anticipated
         reductions in extraneous flows.

    o    RII appears to  represent a significant portion of the flow
         to  sewage treatment plants during wet weather  periods.  In
         the 10 case studies  the  peak wet weather flow ranged from
         3.5 to 20 times the  a.verage  dry  weather  flow.    The
         contribution from RII was  estimated to be  between 60-90
         percent of  the  wet weather  flows.   The  remainder  is
         "traditional" groundwater infiltration and inflow.

    o    Collection and treatment  systems  typically  do not  have
         the capacity  to handle peak wet 'weather  flows.    Peak
         flows,  therefore,   can  cause   backups  into  buildings,-

                               ii

-------
                         Executive Summary


          overflows ;and treatment system bypasses.  . Such occurrences
          -are  a  hazard  to  public health  or a  violation of  the
          municipality's discharge permit.    .   >

     o    Sewer.trenches act as collectors of rainfall percolating
          into the  soil.   The trenches channel,  the water,  thus
          providing multiple  opportunities  for.the water  to  seep
          into the collection system at defectiye points.

     o    The  shallow  portions of a collection  system  (building
          laterals  and  their  connections,   sewer mains,  manhole
          defects and foundation drains) are  more vulnerable to RII.
          Interceptors, which are typically deeper, do not appear to
       •'  be a significant, entry point.

     o    The extent of RlI in a sanitary sewer .system  is  related
          to design, construction, climate,   geology and degree of
          maintenance.                '                              ;

 RII Control Methods

 RII control means the 'implementation of measures to reduce existing
 RII flows or limit  future RII into a  sewer system.  RII control can
 be  accomplished   through   various   means,  including  physical
 rehabilitation of the  sewer system,  improved design  standards  and
 construction practices, preventive maintenance,  and  institutional
.and regulatory approaches.   The major  findings and conclusions of
 the study with respect to the various methods and approaches  for
 RII control are:                                   •:',:'

     o    Accurate  field ,investigations  and  data .analyses   are
        ,  important for developing an effective RII control program.

          The first  step in developing an effective control  program
          is to accurately identify and quantify RII in the sewer
          system,  and to distinguish RII from other I/I components.
          The   traditional  I/I  field data  collection techniques.
          commonly  in   use   can be  successfully used  for   RII
          investigation  as  long as  the techniques  are properly
          applied and the data correctly interpreted.  For example,
;         flow  monitoring sites  should  not be influenced by severe
          pipe  constrictions,  and hydraulic_ conditions must  be
          considered in interpreting  flow monitoring results.

     o    Many  methods  -are  available for  rehabilitation of sewer
          systems  to reduce  RII.               -          '

          Pipeline    rehabilitation  methods 'include   in-place
          techniques,,  such  as grouting  and  lining,  as well  as
          replacement  by excavation  or, trenchless  installation
          methods.    The  suitability  of different  methods   for
          correcting RII. problems  depends  upon  cost,  extent  of
                                111

-------
                    Executive Summary


     problem, arid site-specific physical conditions, including
     the condition of the existing pipes.

     Manhole rehabilitation techniques  include  both interior
     and exterior repair methods.  Many of  these methods are
     specifically designed to eliminate RII which seeps into
     pavement  cracks and  enters  the  sewer  system  through
     manhole frame and chimney defects.

     .The  traditional   approach   to  determining   the   cost
     effectiveness of sewer  system rehabilitation  to  reduce
     extraneous flows evaluates each inflow source or defective
     sewer component on  an individual basis.  This traditional
     approach can overestimate the amount of flow reduction
     achievable from rehabilitation because it fails to acc.ount
     for the  migration  of  water  to  defects that are  left
     unrepaired.

     A comprehensive program  of  sewer  system  rehabilitation
     that includes both  the public and private portions of the
     system  can  be  effective  in  reducing  RII,  although
     sometimes at considerable cost.  If  the private  portion
     is not included, a  significant portion of the RII may not
     be  addressed.   Water  may  also migrate  to  unrepaired
     defects in public portions of the system, thereby reducing
     the effectiveness  of the  rehabilitation effort.
RECOMMENDATIONS

o    The specific analysis of RII should be  included  as part
     of  overall  I/I  evaluations.     Guidelines  should  be
     developed  to  ensure  the  proper  application  of  field
     techniques and  interpretation  of data  to  identify  and
     evaluate RII.

o    The following considerations should  be incorporated into
     the development of sewer system rehabilitation programs
     and   evaluation   of   the   cost    effectiveness   of
     rehabilitation:

     -   Addressing  entire  areas of the sewer  system versus
         repair of individual defects only.      .

     -   Including both the public and  private portions  of
         the  sewer system versus only the public portion.

o    Long-term  control  of  RII  should  be  ensured  through
     implementation  of  an  effective  preventive maintenance
     program that  includes:

     -^   Periodic  flow  monitoring in the system to identify
         areas with  increases in RII levels.

                           iv

-------
               Executive Summary
-    A routine program of cleaning and root removal;

     A cyclic program of testing and  inspection .of the
    , sewers throughout the  system to  identify the need
     for repairs and replacement.      '

Sewer design  standards should be modified to provide a
cost-effective means  to  minimize  future RII into new or
rehabilitated sewers  by controlling  the development of
extraneous water in sewer trenches.

Effective sewer construction practices should be  followed
by:     '   •     '   •.'/.•   '      .      - ;  '   '..-'"•-.•.'••

-    Rigorous  construction inspection.

     Effective performance testing for public sewer mains
     as  well as  private laterals.       ,        ..-'•=•

The institutional and regulatory framework governing the
construction  and  maintenance  of house  laterals  (the
connection between the house or building and the collector
sewer in the street .or other public right-of-way) should
be re-examined.   Possible options include:

     Shifting   responsibility  for  construction  and/or
     maintenance of house laterals from  the home owners
     to  the municipality.

-.    Municipal programs  to  help  home  owners  pay  for
     maintenance and repairs  of house  laterals.

     State  or municipal ordinances,  with  appropriate
     enforcement provisions/governing inspection, testing
     and repair  of  house  laterals.

- \_  Public education programs to  inform citizens of the
     importance  of  excluding  extraneous flows from . the
   •  municipal sanitary sewerage systems.

-------
                            DEFINITION
     A   number  of  closely   related   phenomena  are  discussed
throughout this report.  For the convenience of the reader, short
definitions of these phenomena and the acronyms used in the report
are  included below.   Also  included are  schematic  drawings and
graphs to help the reader visualize  these  phenomena.

Inf litration
     Water  other  than  wastewater  that  enters  a sewer  system
(including sewer  service connections and foundation drains) from
the  ground  through such means as defective pipes,  pipe joints,
connections,   or   manholes.     Infiltration   is  typically  not
intentional and occurs by seepage through defects in the system.
The contribution of foundation  drains is considered as infiltration
due to its rate and duration characteristics even though it is an
intentional  contribution to the  system.   Total  infiltration is
composed  of   Rainfall  Induced  Infiltration  and  Ground-Water
Infiltration.

Rainfall Induced Infiltration  (RID
     RII is a  particular form  of  infiltration which behaves like
and is sometimes confused with storm water inflow.  RII generally
occurs  during  and  immediately after  rainfall events and  it is
believed to be caused by the  seepage  of percolating rainwater into
defective pipes  (in many cases service connections  or laterals)
which lie near the ground surface.   These circumstances cause a
large portion  of  the  rainfall  to  enter  the system relatively
quickly and the extraneous flow lasts only a short time after the
rainfall episode is over.  The  combination  of these factors causes
RII  to  be of  relatively  short duration  and  high  intensity as
compared with typical  infiltration which is generally constant in
intensity and of longer  duration.

Ground-Water Infiltration (GWI)
     GWI results from the movement of ground water in the saturated
zone into the sewerage system through defects in the components of
the sewer system located below  the water table.  GWI is relatively
constant and is generally not  significantly affected by rainfall
events (except, where the ground-water is near the sewer pipe).

Inflow
     Water  other  than  wastewater   that  enters   a sewer  system
(including sewer  service connections)  from sources  such as roof
leaders, cellar drains, yard drains,  drains from springs and swampy
areas, manhole covers,, cross connections between storm sewers and
sanitary  sewers,   catch basins,  cooling  towers,  storm  waters,
surface runoff, street washwaters or  drainage.   Inflow  is generally
easier to locate and eliminate from  the system than infiltration
because it enters from specific points that can be identified and
closed off.
                                vi

-------
                            DEFINITION

Storm Water Inflow (SWI)
     SWI is generally the result of intentional diversion of storm
water into sanitary sewers.   These connections are usually easy to
identify and correct.   The pattern that they follow is a prompt
response which  mirrors the  rainfall  event, followed by  a quick
decrease as the event stops.  An example of  SWI is roof downspouts
which are connected to a sanitary sewer line.

Dry Weather Inflow (DWI)
     DWI is the result of extraneous contributions to the flow of
the sewer, /which are not caused by rain.   Some examples are water
from street washing that enters manholes through the holes in the
covers, cooling water for industrial and commercial applications,
and some car washing activities.                        ,
                  • .  '! .                '          . .          .  . -

Inf i Itrat ion/inflow if I/I)
     This is the combination of all the  extraneous contributions
to the sewer system.  I/I is equal  to RII  + GWI  +  SWI + DWI (see
graph).          ,,  •
                               VI1

-------

-------
a.
s
     ~1      PRECIPITATION
                                             INFLOW (SWI)
o
                                  INFILTRATION (Rll
              RAPID Rll RESPONSE
                             LESS RAPID Rll RESPONSE



                             X- •
TOTAL I/I (SWI
                                                Rll  + GWI)
              TOTAL I/I WITH

              RAPID Rll RESPONSE
                              TOTAL I/I WITH

                              LESS RAPID Rll RESPONSE
                        TIME
        TYPICAL EXTRANEOUS FLOW HYDROGRAPHS

-------

-------
SCHEMATIC FOR SEVERAL
TYPES
OF EXTRANEOUS
WATER INTO
SEWERS
                       Rl
EXTRANEOUS WATER
               INFILTRATION
                        •GWI-
              INFLOW
                        SWI
                        DWI

-------

-------

-------

-------
                             CHAPTER 1

                           INTRODUCTION
STUDY AUTHORIZATION AND OBJECTIVES

Section  523  of the Federal Water Quality Act of 1987  (PL  100-4)
requires  that  the U.S.  Environmental  Protection  Agency  (EPA)
conduct a study and submit a report to Congress concerning rainfall
induced  infiltration  (.RID  into  sanitary  sewer systems.   The
specific requirements of  Section 523 were to:
  .         -         \ '•.'•'     '   "     ' •                  •    • • :
     o    Study problems associated with  RII.

     o    Study  appropriate  methods to control RII into  sanitary
       ,  sewer  systems,  including  that of the East Bay Municipal
         Utility District (EBMUD), California.

     o    Develop recommendations on reasonable methods  to  reduce
         RII.             ;   . . '  '     .   ' '         - \      '.''"'

STUDY APPROACH                                                   !

An approach was developed to accomplish the goals of  the study,, as
follows:   '   '    .  .'• •   •     ,   •',:-"    '    /    •  •   ••'.•',.•-.

     o    Establish a definition of RII.   .•_."'.'•

     b    Identify  sewer  systems  in  the  United  States  which
      ,   experience RII,  and  document the characteristics of and
         problems associated with RII in those systems.

     b    Conduct a literature search of  applicable  methods for
         controlling the entry of RII  into sanitary sewer systems.

     o    Conduct an evaluation of the costs of various  approaches
         to control RII.                                        .

     o    Develop   recommendations   on  appropriate  methods  and
         approaches for RII control.

REPORT ORGANIZATION

The report is divided into several chapters and  appendices.  This
chapter  briefly describes  the  study  objectives and   approach.
Chapter 2 presents  an  assessment  of  the RII problem, including the
definition and characteristics of RII,, a discussion of the problems
associated with RII, and  the presentation of ten case  studies of
sanitary sewer systems identified as experiencing RII.   Chapter 3
discusses  methods   and  approaches for   controlling RII.    The
                               1-1

-------
                           introduction


appendices contain more detailed descriptions of the case studies,
further information on rehabilitation methods and design standards
for  RII control,  and  a  detailed  discussion  of the  RII  cost
evaluation conducted for this study.
                               1-2

-------
                      1      CHAPTER 2

                        PROBLEM ASSESSMENT


This  chapter  discusses  the  characteristics  of  and  problems
associated with  rainfall  induced infiltration  (RII) into sanitary
"sewer systems.   Included  are a definition of RII; a discussion of
the typical problems associated with RII; a description of possible
pathways by which  rain can be rapidly transported from the ground
surface to where It enters  a sanitary sewer system; a discussion
of the types of defects and connections through which Rll'may enter
a  sewer  system; an assessment of the  key factors which  may be
important  for explaining the  potential for  RII  occurrence in
specific sewer .systems; and a summary of RII case studies.

BACKGROUND

The entry of extraneous water into  sanitary  sewer systems has been
recognized for many years as a significant problem in communities
throughout the cpuntry.  This ^extraneous water,  termed infiltration
and  inflow  (I/I),  consists of groundwater  and'storm  water which
enter the sewer  system  through defects  in pipes and manholes and
through direct connections to  the  sewer system.   When present in
excessive amounts, I/I can cause wastewater, overflows and bypasses
from  manholes  and pump  stations,  bypassing and/or  inadequate
processing  of wastewater at treatment  plants,  and  flooding of
building basements  with wastewater.  •

The need to address excessive I/I was dictated in the Federal Water
Pollution Control Act Amendments of 1972 (PL.92-500).   Under this
law, Congress mandated that all "excessive" I/I be removed from a
sariitary  sewer  system before a construction grant for wastewater
treatment  facility  improvements   could be  awarded.    EPA  has
interpreted "Excessive" I/I  as that portion  of  the total I/I which
could be cost-effectively removed,  i.e. , the cost for removal would
be  less  than  the  cost for   transport  and  treatment  of  the
"excessive" I/I  flows.
                          ,          ":  •     '     '           - '   '
In the years immediately following the enactment of the 1972 law,
the EPA developed guidelines  for conducting I/I cost-effectiveness
analyses and sewer system evaluation  surveys  (SSESs)  to. identify
excessive I/I  (Appendix B).   EPA  regulations at 40  CFR  Part 35
define, the terms "infiltration" and "inflow" as.follows:

     Infiltration.   Water other than wastewater that enters a sewer
     system (including  sewer  service connections and foundation
    .drains)  from the ground through such means  as defective pipes,
     pipe joints, connections, or manholes.  Infiltration does -not
     include,  and is distinguished  from, inflow.               .
                               2-1,

-------
                        Problem Assessment


     Inflow.   Water  other than  wastewater that  enters a  sewer
     system (including sewer service connections) from such sources
     as,  but  not limited  to,  roof leaders,  cellar drains,  yard
     drains,  area  drains,  drains  from  springs and swampy  areas,
     manhole  covers,  cross connections  between storm sewers  and
     sanitary sewers, catch basins, cooling towers, storm waters,
     surface runoff, street wash waters, or drainage,   inflow does
     not include, and is distinguished from, infiltration.

 In general, the  understanding of  infiltration  was  that it entered
 the  sewer  system   indirectly   via   groundwater  seepage   into
 underground  sewer   defects,  whereas  inflow was rainfall  runoff
 entering   through  direct  connections.     An  exception   to  this
 generalization was  later made when directly connected foundation
 drains were reclassified as  infiltration rather than  inflow,  thus
 recognizing the  sustained  flow contribution of  foundation  drains
 in areas of high groundwater.

 The EPA   guidelines  described   procedures for  separating   and
 quantifying   infiltration   and   inflow   by  use  of   flow  data.
 Specifically, infiltration was calculated as the difference between
 total  flow and estimated wastewater  input  on  non-rainfall days.
 Inflow was calculated as  the difference between  the total  flow
 during a large storm  event and the total  flow  on the nearest non-
 rainfall  day.   Thus,, in practice,  the  term "inflow"  came  to be
 synonymous with  short-term, rain-induced  I/I.   The EPA guidelines
 acknowledged  that  both infiltration  and inflow are  affected by
 rainfall,  but that  it was  not  possible to  precisely   quantify
 infiltration  and   inflow  in  accordance  with  their   literal
 definitions.   As a  result, it was  concluded  that the   accuracy
 levels of the calculated values were adequate  for estimating that
 portion of the I/I which might be considered excessive.

 Subsequently, communities  throughout the country  conducted  I/I
 analyses and  SSESs  using the EPA  guidelines,  and  many undertook
 sewer system  rehabilitation programs  to  remove the I/I  that had
 been categorized as excessive.  While I/I flows were reduced in a
 number of such systems, in others, the anticipated flow decreases
 did not  occur.   One  possible  explanation  of  why  these  programs
 failed is  that infiltration may have  been incorrectly identified
 as inflow.  This can happen when water infiltrates into the sewer
 system through pipe and manhole defects, but produces  a peak flow
 response similar  to that of inflow from direct connections.  Inflow
 connections can typically be eliminated at a lower cost  (per unit
of  flow  removed)   than  can  defects  in  pipes  and  manholes.
Therefore, if flows due to infiltration are  incorrectly identified
as being due to inflow, an invalid or substantially overestimated
assessment of  the cost effectiveness of I/I correction may result.
                               2-2

-------
                        Problem Assessment


One wastewater .system with extremely high rain induced extraneous
flows  is  the East  Bay  Municipal .Utility  District  (EBMUD)  in
California, which includes the City of  Oakland  and six adjacent"
communities.  During  large rainfall events,  the EBMUD system can
experience  flows as high as twenty  (20)  times the  average dry
weather  flow.   As a  result,, peak flows exceed  the conveyance
capacity of the  sewer system, causing overflows onto city streets
and bypasses  of  untreated wastewater to  San Francisco Bay.

To  address these problems,  EBMUD  and  its  tributary communities
undertook extensive studies to identify  and quantify the.rainfall
induced extraneous flows in their sewer system.  The goal of these
studies was to develop a regional plan to eliminate  peak flows that
could cost-effectively be reduced,  and then-to adequately process
the remaining volume of wet weather wastewater.

The comprehensive I/I  study  conducted by the  EBMUD communities
coneluded  that   only  a small fraction  of the  high peak  flows
occurring  during rainfall events  could be attributed  to direct
inflow.  The  majority of the rainfall induced flow was .attributed
to infiltration, and was called "rainfall dependent infiltration"
in the EBMUD studies.  Thus, EBMUD became the impetus for the study
on rainfall induced infiltration  called for  under  the 1987 Water
Quality Act.                        .         ' >

DEFINITION OF RII

For 1the purpose  of this report,  we have defined rainfall induced
infiltration,(RII) as follows:,

    Rainfall Induced,Infiltration.  RII is a particular  form of
     infiltration which  behaves like and is spmetimes confused with
    storm  water  inflow.    RII   generally  occurs  during  and
     immediately after  rainfall .events  and it is  believed  to be
    caused by the seepage of percolating rainwater  into  defective
    pipes (in many cases  service  connections  or  laterals)  which
     lie near, the ground surface.   These circumstances  cause a
     large portion of  the  rainfall to enter the system relatively
    quickly and the extraneous  flow lasts only a short time after
    the rainfall  episode  is over.   The  combination of  these
    factors causes RII to be of relatively short duration and high
    intensity as  compared  with   typical  infiltration which is
    generally constant  in intensity and of longer  duration.

Rainfall induced infiltration can be distinguished from "classical"
infiltration because it  results in  a peak flow response in sanitary
sewer systems which may be'indistinguishable from  that of direct
storm water inflow.   For  the purposes of  the  discussion in this
report, the  long-term,  sustained  classical  type of infiltration
will be  described by  the term  "groundwater  infiltration" (GWI).
"Storm water  inflow"  (SWI) will be used as the term for direct
                               2-3

-------
                        Problem Assessment


 inflow as  defined  by  EPA.    Both  GWI  and  RII  are  forms of
 infiltration,  as  described by  the  EPA definition,  but differ
 primarily in their flow response.

 The  distinctions  between SWI,  GWI,  and RII are illustrated by the
 hydrographs  in Figure 2-1.   As shown in the figure, SWI produces
 a rapid, peak flow response  to  rainfall which recedes quickly after
 the  rainfall stops.   Rainfall may also produce a net increase in
 the  sustained  GWI  flow rate, as shown in the  figure.  RII response
 may  be as rapid as that  of  SWI, or  may include a delayed response
 which  lags the peak rainfall intensity by several hours and  then
 recedes slowly.  In most sewer systems,  the RII response is likely
 a continuum  from a rapid peak flow to  a more gradual, prolonged
 response  similar to GWI.   Therefore, the separation between the.RII
 and  GWI portions  of the  hydrograph  may not be well-defined.   RII
 becomes most significant when the  type  of  flow  response is  more
 like inflow, i.e., it results in a rapid and  high peak flow in the
 sanitary  sewer system.

 PROBLEMS  ASSOCIATED WITH RII

 The  problems associated with RII are those  due to the high  peak
 flows  which  occur during  and  immediately following  rainfall.
 Typical RII problems include wastewater overflows and bypasses  from
 manholes  and pump stations  in the  sewer system,  and flooding of
 building   basements.     Wastewater   backing   up   into  homes  or
 overflowing  into city streets is a hazard to  public health and, in
 most cases,  is a  clear, violation of the  discharge requirements of
 the sewerage agency.  Additionally, wastewater bypassed to drainage
 channels  may result  in  water quality degradation  in downstream
 surface waters.   If the  flows reaching  the  wastewater treatment
 plant  are much  higher  than  the  plant's  capacity,  deliberate
 bypassing may be necessary to  avoid hydraulically overloading the
 plant.  At very high plant flows, inadequate wastewater treatment
 and  inability to meet discharge requirements may result.   In  all
 cases,  excessive  RII  flows  result  in  increased  operation  and
maintenance costs  for transport and treatment.

An ancillary problem  associated  with RII is  that  there  is  the
potential for exfiltration of untreated  sewage at these same pipe
 and manhole defects.  This problem is especially likely to manifest
 itself  when  the sewer pipe  is above the  water  table.   In  -some
cases,  discharged  sewage may cause ground-water contamination; in
other cases it might be channelled by sewer trenches to potential
points  of direct human exposure.

The peak  nature  of flows due to RII, and  the magnitude  of these
flows in some systems, means that wastewater collection, transport,
and  treatment  facilities must be  designed  for capacities  that
greatly exceed normal  peak  dry weather  flows.  Thus,  very large
capital expenditures may be required to construct, facilities that
                               2-4

-------
 a.
 ui
 o
      n      PRECIPITATION
                                               INFLOW (SWI)
 O
 o
o
                                   INFILTRATION (Rll,+ GWI)
               RAPID Rll RESPONSE
                               LESS RAPID Rll RESPONSE
                                TOTAL I/I  (SWI •+.- Rll -i- QWI)
              TOTAL 1/1 WITH

              RAPID Rll RESPONSE
TOTAL I/I WITH

LESS RAPID Rll RESPONSE
                         TIME
                           FIGURE 2-1


         TYPICAL EXTRANEOUS FLOW HYDROGRAPHS

-------

-------
                       , Problem Assessment:


 can handle the RII flows.   Funding for such construction may  be
 difficult,  if  not  impossible,   to obtain.    Similarly,  system
 capacity that might otherwise be available  for  future growth must
 be  used for RII.   In  systems with severe capacity limitations and
 problems due to  RII, building  moratoriums may  be necessary  to
 restrict further  increases  in wastewater flows.
  ' >             /       ',       •-•".••'   • •           •       ,i
 The alternative to providing excess system capacity to handle high
 RII flows is to reduce  RII through sewer  system rehabilitation.
 However, as will be discussed in more detail later in this report,
 achieving substantial RII flow reductions  throu'gh rehabilitation
 can be  very difficult and costly.   Part of  this problem is  due  to
 the fact that  in many  areas,  a significant portion of RII may
 originate  on   private  property   (from  building  laterals and
 foundation drains).   Many communities  have  invested considerable
 sums of money (both under local programs and with state and federal
 funding)  in rehabilitation  programs that have proven ineffective
 in  reducing I/I flows.   The failure of  many of these programs has
 been due in part to  the  failure to properly, identify RII as the
 major component of I/I,  and to implement an adequate  program for
 RII control. .'.-..               .-.'';•

 As  noted previously,  RII  has been identified as the primary  cause
 of  wet  weather problems  in  the  EBMUD  wastewater  system.  During
 large storms, overflows  occurred at over 175 locations within the
 community collection systems and about ten times each year from one
 or  more of seven  shoreline  bypass points on the  District's  major
 interceptor  sewer along  San Francisco Bay.   To  eliminate  these
 problems and comply  with discharge requirements,  EBMUD and its
 tributary communities have had to initiate a major program of  sewer
 system  rehabilitation and construction of facilities, to handle wet,
 weather f lows,'at a cost  of  over  $600 million.  The section on Case
 Studies, presented later  in  this  chapter  describe the  problems
 associated  with RII  in  nine other  sewer  systems throughout the
.country.                                        .,,  ;

 POSSIBLE RII,PATHWAYS AND FLOW RESPONSE

 Storm, water may  reach  sewer  system openings  through  different
 pathways/from the ground surface.  The  resulting RII flow response
 will vary depending upon the type and  length of  the  pathway that
 the water follows.   Factors.such  as the  characteristics of the
 soils,   geology,  groundwater,  topography,   and  trench  backfill
 materials will  influence the speed of  the flow response.  A very,
 rapid response  would  bejexpected  in situations  in which the RII
 pathway is  more like  a direct channel  to the sewer  entry point.
 A slower response would  be  expected in cases where  the  permeable"
 backfill material in the  sewer trench acts as a drain for the  water
 in  the  surrounding soil.                                 '',':
                               2-5

-------
                        Problem Assessment


 Some possible pathways scenarios which may help explain how and why
 RII  occurs  are described  below.   While  these pathways  present
 different conceptual  models  of  RII,  they are  not necessarily
 mutually exclusive.  RII  in any particular sewer system  may result
 from a combination of  several different scenarios.

 Soil Channels

 Storm water may reach sewer defects through "channels" in the soil,
 as illustrated  in  Figure  2-2.  The channels may be large enough to
 be called "holes," or may  simply be continuous "macropores"  from
 the ground surface  to the system  defect.   The  channels may be
 created by soil fauna such as worms  or rodents,  or by plant  and
 tree roots.    In  clay  soils  with high shrink/swell capacities,
 surface_cracks  may open  which extend  to the sewer trench.   With
 each rain,  the  percolating water may gradually enlarge the  above
 described holes, macropores,  or cracks.

 It is also  likely that soil channels within the pipe trench  form
 via a similar erosion process  by water which exfiltrates  from leaky
 pipe joints and defects,  and then infiltrates back into  the  system
 during low  flow periods.    Such joint-to-joint channels have been
 observed  around excavated pipes, and also are evident where grout
 injected  into a pipe joint  reappears at  another nearby  joint.

 Flow response in the sewer system due to water movement through
 soil channels would vary  depending upon  the  size of the channels,
 the distance the  water  must  travel to  a sewer  defect,  and the
 surface characteristics of  the ground.   In particular, for a rapid
 response  to occur  (i.e.,  faster than the natural transmission rate
 of water  through the soil),- the soil channels qr pores would have
 to be large  enough to  overcome capillarity  (pore diameters of at
 least 3 to 4  mm).   The length of the soil channel (distance from
 the ground surface to  the RII entry point)  would also impact the
 speed of  the RII response, with shorter channels,  such as  those to
 shallower sewers,  producing  faster  response  times.    Where the
 surface characteristics are such that the ground over the channel
 forms a natural depression for surface  runoff collection,  the soil
 channels  would  act like  direct  inflow connections,  conveying
 surface water rapidly to  defects in the pipe.

 Shallow Impermeable Strata

Where  a  shallow,  relatively  impermeable  soil  layer or bedrock
 exists, rainfall percolating  into  the soil  may create'a perched
water table, as shown in Figure 2-3,  and may  be carried rapidly to
 sewer  trenches  as  the groundwater  level rises  in response to
rainfall.  RII  response under this scenario may  vary  from rapid
 (i.e., similar to SWI) to  gradual (i.e., similar to GWI), depending
upon the  depth  and permeability of the overlying  soil,  the slope
                               2-6

-------

-------

-------
                  o
                  til
                  CO
                  CO
                  cc
                  o
111
                                  «?
                                  CM
                                  m
                                 •tr
                                  =>•
                                  C5
I
 oc
 fe
 IU
   -
                IU
                >
                IU
                9
                CO

-------

-------
                         Problem Assessment


 of the  impermeable  strata,  and/or the extent to which  the sewer
 trenches penetrate the impermeable material.

 French Drain Effect

 In some situations,  a sewer  trench may act like a French drain, an
 underground passage  for water  constructed of  material that  is
 "looser"  (more  permeable)   than the  surrounding  soil.    This
 condition would occur where the sewer'trench  bedding and backfill
 is  composed of  granular  material  (sand  and/or  gravel).    As
 illustrated in Figure 2-4, the  sewer trench would thus  provide a
 conduit for water from the  surrounding .soil.  If the surrounding
 soil becomes saturated because  of rainfall, the sewer trench may
 drain the water,  resulting in a rise in the transient water level
 in the  trench.   As  the static... water  pressure  over  the  pipe
 increases, the rate of RII  into  pipe defects will also  increase.
.The RII response, will typically  be more gradual than that  of SWI
 or "rapid" RII from soil channels.  The French drain effect  in a
 sewer trench may  be accentuated by other pipe  trenches crossing or
 intersecting the  sewer trench1                    , .   , .  • •

 Entry from Ground Surface into Sewer Trench Backfill  >

 If trench backfill material  is more permeable  than the surrounding
 soil  and extends  to the ground surface, it may provide an area for
 rainwater, on the ground surface to more  easily  infiltrate  the
 trench,   as  illustrated  in  Figure  2-5.     Any   network   of
 interconnected  utility  trenches  can convey  the water to   the
 sanitary sewer trenches,  typically  the deepest utility, and  to
 defects  in the  sewers.   The  RII  flow response under this  scenario
 would depend  upon the  runoff  characteristics  of  the   surface,
 surface  topography, adequacy of existing storm drainage facilities,
 extent of the underlying trench  network, depth of pipes,  and,  type
 of trench backfill materials.  Where slopes  are steep  and  trenches
 are  located  in  natural  depressions  (as  is common for  sewer
.trenches),  RII  flow response  in the system could be rapid.    in
 other situations, the  response time  could be more gradual.

A  similar phenomenon  may occur in cases where the sanitary sewer
pipe  parallels  or crosses under surface drainage ditches.  Storm
water quickly  co.llects  and  fills  the  ditches  and  infiltrates
downward to the sewer  pipe.   In the extreme case,  the sewer pipe
may be installed  directly under  the  entire length of a  drainage
ditch, resulting in rapid infiltration into the backfilled trench.*

Storm Drain Exfiltration                 '     -
 \                                    _         -             .
Where  sanitary  sewer mains  or laterals parallel or  cross  under
storm drain trenches, water may exfiltfate from leaky  storm sewers
or storm laterals  and then infiltrate into the  sanitary sewer pipe.

-------

-------
  g-
  UJ
  CO
  CO

 -8
  tr
  o
UJ

>

UJ
Q

CO
                    1
                uu   =
                cc   <
                ^   DC
                £5   Q

                "••  X
                    O

                    111
                    cc
                    u.

-------

-------
      (0
      Ul

      I
      UJ
     I
     p
     Q
     O
in   IU
cvi   Z
uj   Z
5   O
^)   O
cs   a-
u_   uj
    (0
    o
   'Z

    o
    DC
    O

-------
CM
111
CC
     g
     <
X
UJ
     DC
     Q


     OC

-------
                         Problem Assessment:
 as shown in Figure 2-6.  Channels through the soil will gradually
 form between defects  (exfiltratiqn points) in the storm drain and
 defects  (RII  entry  points)  in  the  sanitary  sewer.    Since the
 stormwater  would  initially  be  conveyed very  quickly  from the
 surface  to the  exfiltration points  in a ' storm drain,  the RII
 response .could be  fairly rapid.   In the extreme case, the storm
 drain  or. lateral may  be installed in  a common trench  with the
 sanitary  sewer  pipe  and  backfilled  with  permeable  material,
 resulting in a very short indirect cross-connection between the two
 pipes.                           .                  .

.Subsurface Seepage

 When  streets  are  flooded  during rainfall,  water can  seep into
 cracks in the pavement and travel laterally underneath the pavement
 to the upper portions  of manholes,  as shown in  Figure 2-7.  The
 water can enter the manholes through defects,  typically between the
 manhole  frame and   chimney.     Subsidence  of  trench  backfill
'materials  may  cause channels  to form  between the pavement and
 street subbase.   The street subbase,  which is  typically highly
 permeable material,: could  also function as a  horizontal  lens  to
 direct the  flow of water.  Channels between the pavement cracks and
 manholes would  gradually  form through  erosion.    The RII flow
 response would be  fairly rapid  because the defects are  located
 close  to  the  ground  surface,  and horizontal  water movement  is
 prompted by street subbase material or channels.   This  pathway
 appears to be more common where  freeze/thaw  cycles  occur in cold
 climates; both the  cracks in the pavement and the openings between
 the manhole frame and chimney may be caused  by such freezing and'
 thawing of  the ground.

 Foundation Drains                                            -

 Where foundation  drains are used to lower the permanent or seasonal
 groundwater  level  from  around  building   foundations,   direct
 connections of  the  drains  to  the  sewer  system may  exist,  as
 illustrated in Figure 2-8;   The  foundation drains may  contribute
 GWI during non-rainfall  periods,  but  flow response may  increase
 significantly  during  periods of-,rainfall.  The magnitude and speed
 of the response  would  depend on lot  slope, direction  of  surface
 drainage in  relation  to  the  building,  location  of   downspout
 discharges, arid permeability of the backfill materials next to the
 basement walls and  drains.  ,             •

 tee and Molzahn utilized a  computer groundwater model to simulate
 the flow response in foundation drains from  rainfall.  .The  model
 demonstrated that  foundation drains could produce a  peak flow
 response that  correlated more to  total  storm  rainfall volume than
 to rainfall intensity.   Rainfall simulation and wet weather flow
 measurements   for  foundation   drains   from  other   studies   also
                                2-8

-------

-------

 (0
DC
O
UR

GH PAVEME
E 2-7
FIG
O
DC



LU
O

Q.
LU
LU
CO

-------

-------
    I
    g
o>
a  —-
u.  DC
    o
    a

-------

-------
                        Problem Assessment


 indicated  that  foundation drains  can produce  a peak  flow  response
 within  one hour of  rainfall.


 ENTRY POINTS OF RII INTO  SANITARY SEWER SYSTEMS

 Extraneous water enters  a  sanitary  sewer system through various
 types of openings.   Infiltration entry points include defects  in
 pipes and  service laterals  (cracks>  holes, open or offset joints,
 defective  pipe  connections;  etc.)  and  similar defects  in. other
 structures such  as manholes  and cleanouts.    Foundation drain
 connections to  sanitary sewer building laterals are also defined
 as  infiltration entry  points.   Infiltration entry points are RII
 entry points whenever  rainfall produces  a significant, short-term
 increase in the 'flow of .extraneous water.  The various types  of RII
 entry points are illustrated, in Figure  2-9. ,.     •

 RII should not exist in a water-tight sewer system, i.e., a  system
 where there  are.no  openings  for  extraneous water to  enter.   No
 sewer system, is expected to be completely  water-tight;  even new
 systems  today   are  designed  with  a  minimal   allowance  for
 infiltration.   However,  .many; systems,  both  old  and new, have
 developed  numerous  defects  which  allow .excessive amounts  of
 extraneous water to enter.  Typical RII entry  points  are described
 below.,

 Pipe Defects                                              '

 Sewer systems.installed in this country prior to about 1960 often
 have   numerous  defects.    These  defects are due  to both poor
 construction  practices  and  the  materials  that were used  for
 construction. The short pipe lengths  (two to three feet) Installed
 in  most older  sewers  resulted   in  many joints  in  the  sewers.
 Specific problems have  resulted because of:

     o    Low tensile strength of  the pipe.
     O    High porosity of pipe materials.
     o    Hydrogen sulfide corrosion  damage to  concrete pipes.
     o    Cracking around  the pipe bells due .to the joint rigidity.
     o    Deterioration of the joint  materials.

Better quality pipe and joint materials have come into widespread
use since  the 1960s.   These include  less porous,  higher strength
pipe, which is installed with flexible joints,  as well as flexible
pipe materials  which  come  in longer pipe,  lengths  ,(hence  fewer
 joints).   -Use  of low  pressure air  testing  for determining  the
acceptability of newly constructed   sewers .has accelerated  the
transition to use of better pipe materials and has helped improve
the quality of sewer construction.             ,.
                               2-9

-------
                      .  Problem Assessment


Poor   construction  practices,   both  in   old   and  new   pipe
installations,  have  also  contributed  to  pipe  defects.    These
include:


     o    Inadequate  pipe  bedding  and  poor  backfill  material
          compaction.
     o    Damage caused during construction of crossing utilities.
     o    Service  lateral "hammer  tap" connections.
     o    Unused,  unplugged  wye  connections  installed with  the
          original sewer main.

In  addition,  external  forces such  as  traffic  loads,  ground
movement,  and root intrusion  also  generate defects  that become
points of entry   for RII.

Service laterals  typically suffer from  the  same  types of defects
as sewer  mains.   However, the  problems  may  be  accentuated by the
fact that the laterals are typically shallower, have shorter pipe
lengths,  are more subject to  root  intrusion,  and  are generally
installed by less experienced  contractors and  subject to minimal
testing  or  inspection.   Often,  laterals  are  broken into  for
cleaning purposes  and not properly  repaired ,or backfilled.   Weak
spots in laterals typically occur  under .the  curb  line, at the bend
or vertical  drop  down to the  sewer main connection,  and at  the
sewer main connection.   Service  laterals may  comprise more than
half of  the  total pipe footage in  a sewer  system, hence may be
significant  contributors to RII.

Manhole Defects

Defects  in  manholes  occur  in  the  walls   and  joints,  at  the
connections  to the sewer pipes, and underneath the manhole frame.
The joint between the manhole frame and chimney  (corbel)  may also
be an entry  point of RII when the frame is displaced or the joint
seal is  deteriorated>  broken,  or improperly installed.   As with
sewer pipes,  manhole defects may also be created by external forces
such as traffic loads, frost heave,  and/or root intrusion.

Foundation Drains

Foundation or  footing drains connected to  building  laterals  are
direct  entry points  for infiltration.    Foundation  drains  are
designed to  drain the groundwater from around a building or house
foundation to prevent seepage  into  the  basement.  The foundation
drain  may discharge  by  gravity  or  through a sump pump  to  the
lateral.   In some buildings   without  foundation  drains,  water
seeping into the  basement may  be  collected  by  the basement drain
and similarly discharged to the sanitary sewer lateral.
                               2-10

-------
                        Problem Assessment
FACTORS AFFECTING RII

In any particular sewer system, a variety of  factors may  influence
how RII .occurs and the magnitude and  type  of RII flow  response.
These  factors  relate to the construction and maintenance of the
sewer system and the natural characteristics of the service  area.
Sewer system construction and maintenance affect the number,  size,
type,  and location.; of  openings  through which RII  can enter the
system  and the  pathways by which water  reaches the  RII  entry
points.   Natural characteristics  of the service  area  primarily
influence  the  pathways  by  which the rain water reaches  the  sewer
system and the characteristics  o.f-;the flow response .pattern.  Each
of these  various factors , is  discussed briefly in  the  following
paragraphs.             .                                 .

System Age and Construction
                  - • .      ,- .      .'•'•-.   '            *  -
Age is often an indicator of the type of sewer system construction
and the types, severity, and relative  number of defects that can
be expected.  As  discussed previously,  older systems, particularly
those constructed before the 1960's,  are often  characterized by
widespread defects due  to  the  poor  quality  of the pipe  and  joint
materials  and  methods  used at  the  time  of  construction.    These
systems can  be, expected to  contribute more  RII  than comparable
newer  systems  under  similar  conditions  of  rainfall,  soils,
groundwater, etc. RII can also be expected to be higher in systems
known to  contain common- trench   storm drain  and  sanitary  sewer
installations.                                      ;

Construction of  houses  with foundation  drains connected  to the
sanitary sewer system was common in  many areas during certain time
periods.  Relatively greater  RII.  contributions  from' foundation
drains would be_expected in areas  developed during these periods
than in areas developed after direct foundation drain connections
we're prohibited.                     ;  ..•','*

Density

The magnitude of  RII may be directly related to the amount of pipe
within an area. Areas with denser development have more sewer main
and lateral pipe  footage, with  a correspondingly greater  number of
potential RII  points of  entry.•'  Hence, higher RII rates might be
expected in areas rwith denser .development.               ,       '-...
             ' n.         '•-'.--    -       •   'I..''     .-       '•'••!
Sewer Depth          •

The depth of sewers and  laterals may influence the amount rof RII
and the speed  in which  it enters  the  sewer system.   Where soil
channeling or permeable trench backfill material extending to the
ground surface are  the  pathways of RII  entry into  the system,
                               2-11

-------
                        Problem Assessment


shallower  pipes  can be  expected to  exhibit  a more  rapid RII
response.                                 ,

Groundwater

In areas with  high groundwater, an increase in groundwater  level
due to  rainfall may increase the  submergence  of the sewer.   The
greater  hydrostatic  pressure   on   the  pipe   may  result  in
significantly  higher rates of  groundwater  infiltration into the
sewer, which  in such cases could realistically be classified as
RII.

Soils and Geology

The characteristics of the soils and geology of a service area will
affect the rates of rainfall infiltration and percolation, and the
occurrence of saturated soil zones.  Permeable  soils  such as  sands
can transmit  water  rapidly;  clay soils  with  large shrink-swell
capacities can develop large channels.  Hydraulically restrictive
horizons or bedrock at or above the sewer trench bottom  can create
perched  water  table conditions  during  rainfall which  greatly
enhance  water transfer  to sewer defects.   In soils subject  to
differential settlement,  such  as  fills and  bay muds, or in  areas
subject to earth movement  from  seismic activity, a greater number
of pipe defects may develop, subsequently increasing  the amount of
RII which can enter  the system.

Topography    .

Both water movement  through the soil mantle and sewer flow  rates
are affected by topography.  Sloped bedrock or impermeable  soil
layers will tend to cause perched groundwater to drain to  sewer
trenches.   Sewers constructed  on steep  slopes  carry  flows  more
rapidly, resulting in higher  peak flows in the system.    These
higher peaks  may  cause  surcharging, and  overflows  downstream in
flatter portions of  the  system.  Sewers and laterals constructed
on steep slopes  may be subject to earth movement,  causing  joint
separation and other damage to the pipes.  Topographic factors may
also result in depressions or  low areas  over  sewers,  as  well as
close proximity of storm drains and drainage channels to sanitary
sewers, a situation  which can  increase RII  due to storm drainage
exfiltration.

Roots

Root intrusion  is a major cause  of  pipe defects  in many areas.
Roots enter sewer  pipes  through very  small  cracks  and openings,
enlarging  these defects  as root  growth continues.   Particularly
in residential areas, private  service  laterals are often subject,
to root intrusion  from plants  and trees; trees lining the street
                               2-12

-------
                        Problem Assessment


may result In root penetration into both laterals and sewer mains.
Root growth may also create channeling  effects in the soil.

Rainfall Patterns             .                               '*.  ' '

The magnitude and pattern of rainfall impacts''the'volume, of RII and
the type of response.  Inmost systems  that  experience RII, it has
been found that extended periods of rain produce larger volumes and
higher  peak RII  flows  than  do  isolated,  short  duration,  high
intensity  storms.   Highly  seasonal  rainfall  patterns  (i.e.,
prolonged  periods without rain),  as  occur  in  the  far western
portions  of the  country, may create  conditions  that  are  more
conducive to RII, e.g.,  creation of soil cracks and channels from
the drying out of the soil during the prolonged dry season.

Cold Weather

Cold  climate  areas  with substantial  snowfall  during-  winter
experience  higher RII   flows  when rainfall  and  snowmelt  occur
simultaneously.   Peak   flow  patterns   may._ also  be produced  by
snowmelt  alone.    Frost  heave may  damage  street  pavements and
manholes, creating openings  for the rainfall  and/or  snowmelt to
seep underneath the  pavement  and  enter manholes below the ground
surface/•   - ...  -\  .  .''• •   •    , > '; '••. :       -'   '.      -  ••

Maintenance Practices

The number  of new sewer defects  through which  RII may enter  a
system  can  be minimized by  an effective preventive  maintenance
program.    A   system   that   has   undergone  routine  preventive
maintenance  throughout   its    lifetime  would  be  expected  to
contribute less RII  than a system which lacks such a maintenance
program.  In.general, very few sewer systems have been adequately
maintained.    '

Typically, private building laterals are the  most poorly maintained
components of a sewer system.   This  situation  is compounded by the
fact that laterals are generally of originally poor, construction.
Most laterals  have never been inspected,-  repaired,  or replaced
since original construction.                       «  >

Ordinance Enforcement

Sewer ordinances may provide the institutional means for agencies
to ensure the proper installation and  maintenance of  the private
portions of their sewer systems.    Examples are  requirements for
lateral  installation  by a   licensed  plumber  or  contractor,
inspection prior to backfilling/ requiring that connections to the
sewer main be properly constructed and that abandoned or unused
                               2-13

-------
                        Problem Assessment:
service laterals be plugged, to prevent entry of extraneous water,
and prohibitions against the direct connection of foundation drains
to the sanitary sewer  system.   Where ordinances  are not strictly
enforced,  RII  can be  expected  to be  greater  due to  illegal
connections or  major defects  in service laterals left undetected
and unrepaired.

CASE STUDIES

Ten case studies were documented for this study, including that of
EBMUD and nine other systems that were selected through a candidate
system search.  Candidate systems were identified through contacts
with EPA regional offices, regulatory agencies of each state, and
major consulting engineering firms throughout the country.  A list
of  approximately 350  possible  candidate  systems  was  initially
compiled.   After screening of preliminary  information,  over  65
telephone  contacts were made  to  ascertain the  likelihood of RII
occurrence  in  candidate sewer   systems  and to  determine  what
documentation was available.  The general characteristics of RII,
as defined under this  study,  were  described, and  each contacted
agency was questioned  as to  the relative magnitude .of .peak wet
weather  flows,  the  .known  or  likely  sources  of  RII,  and  the
availability of  data from past  studies.   In  general, most of the
agencies  contacted  responded  affirmatively when   asked  if  it
appeared that they had RII in their sanitary sewer systems.

Reports  from  approximately  40  systems  were  received.    Most
documented I/I analyses and SSESs completed in the late 1970s and
early  1980s under various  EPA  projects.   Therefore, the study
methodologies  and analyses  employed  largely conformed  to  EPA
guidelines which were, in effect during that period for identifying
"excessive" I/I.  The reports received were fairly representative
of  I/I studies  .completed  over  the  past 15  years.   The  best
candidates for case studies were  considered to  be those agencies
which had  documented potential  pathways and  entry points  of RII,
or could with reasonable certainty be assumed to have RII because
of high  peak  flows  with little or no known sources of direct
inflow.  However,  only a very  few  had  specifically addressed or
attempted  to quantify  RII,  or initiated programs designed solely
to control RII.

Based on contacts made  and documentation received, nine candidates
for RII case studies were identified, as listed below:

     o   City of Springfield, Oregon
     o   Milwaukee Metropolitan Sewerage District, Wisconsin
     o   Northeast Ohio  Regional Sewer District, Ohio
     o   City of Baton Rouge, Louisiana
     o   City of Springfield, Missouri
                               2-14

-------
                        Problem Assessment


     o    North  and  South  ShenangO  Joint  Municipal  Authority,
          Pennsylvania
     o    City of Ames,  Iqw'a
     o.    City of Coos  Bay,  Oregon           ;
     o    City of Tulsa, Oklahoma

Further information was obtained from site"visits to the first four
systems and through written and telephone contacts with the others.

Detailed  discussions of these case studies, including  EBMUD,  are
included  in Appendix C.   Brief descriptions of the findings of each
with respect to RI-I are presented below and summarized in Table 2-
1.         • .•  .  •         •    '    •.   "  •  '  • "  '' '  ' ' ''    -•.'..

East Bay  Municipal Utility  District,  California

The EBMUD wastewater service  area is  located on the  eastern  shore
~of  San Francisco  Bay,  and includes  seven  community  wastewater
collection  agencies.   EBMUD  operates the interceptor  system  and
treatment facilities which transport  and treat  the  wastewater
generated from, the  'seven  communities.   The collection  systems,
which  include about  1,500 m;Lles of  sewer  main, are  owned-  and
operated  by the'individual  communities.

The community collection systems, as well as  the EBMUD interceptor
and treatment  facilities, do  not  have adequate capacity to handle
peak Flows which occur during wet weather. As a result, overflows
Onto city streets and bypasses tb local watercourses  have  occurred-
within.the community systems and at seven locations along the  EBMUD
Interceptor,                                          ,

Findings  documented from field investigations were:

     o    High peak flows occurred  in response to rainfall.    The
          ratio of peak wet  weather  flow (PWWF)  to average  dry
          weather flow  (ADWF)  was  estimated to be  about 20 to  1  for
          a five-year design storm.

     o    Identified direct inflow (i.e., SWI)  accounted  for less
          than five percent of the  total rain induced  extraneous
          flows.        ',           .      ;            .'.'-. -'.-•;

     o    From smoke  testing programs, numerous pipe  defects were
          detected in building laterals.

     o    Numerous defects  were  observed   in  sewer  mains  and
          laterals through TV  inspection programs.

     o    Very    few    direct    storm    drain/sanitary    sewer
          interconnections were  found..  ,Mpst  of  the potential
                               2-15

-------
                        Problem Assessment


          interconnections  detected  through  smoke  testing  were
          found to  be  indirect  (i.e.,  through  pipe  defects).
                 /                •  . •     .        .        '
     o    Laterals  exhibited peak flow responses to  actual rainfall
          and  to simulated  rainfall tests.

     o    Most laterals given  air  or water  leakage  tests failed
          such tests.

The high  rain induced flow response, the absence  of significant
direct  inflow connections to account for any substantial portion
of the peak flows,  and the prevalence of defects in  sewer mains and
laterals indicated that RII is  a significant component of peak wet
weather flows in the EBMUD sanitary sewer system.   The key factors
affecting RII  entry points appear  to  be the  age and condition of
the sewer system and  the  relatively  high density of  sewers and
laterals.  The poor condition of the pipes is  primarily due to age
and lack of maintenance, but is also affected by physical factors
such  as  earth movement due  to seismic  activity.   Other factors
which contribute to the very rapid, high peak  flows  are the shallow
depth of  mains and laterals, clay soils,  and steep  slopes which
characterize the service area.

The EBMUD communities  have initiated a 20-year program to eliminate
overflows  and  reduce  RII in  the sanitary   sewer system.    The
recommended program consists  of  "comprehensive"  rehabilitation
(including sewer mains and the entire  portion of building laterals)
in approximately one-half of the subbasins in the  system, coupled
with construction  of  relief  sewers to transport the  excess flows
not  removed by  rehabilitation.   Rehabilitation  work  conducted
during the  initial phases  of the program has consisted primarily
of slip-lining  and replacement  of  sewer mains and  the portion of
the  building   laterals within  the  public  right-of way  (lower
laterals).  One of the EBMUD communities has  included the private
(upper) laterals  in the public construction project,  and  other
communities are considering this  approach for  subsequent projects,
as  well  as  other  options  for  implementing  private  lateral
rehabilitation.  Analyses of the flow reductions achieved through
the initial rehabilitation projects are not yet complete.

City of Springfield, Oregon

Springfield is located in central western Oregon at the confluence
of the McKenzie and Willamette Rivers.  The.City's sanitary sewer
system is  tributary to  a regional wastewater treatment plant (WWTP)
constructed  in  1984,  which  serves  the  Cities  of Eugene  and
Springfield.  The Springfield sewer system serves  a population of
about 40,000 and includes approximately 165 miles of sanitary sewer
                               2-16

-------
                       Problem Assessment
mains.  Problems in Springfield caused by rain induced flows have
been  reported  to  include  system  surcharging,  overflows,  and'
bypassing  of  partially  treated  wastewater   from  the  former
Springfield treatment plant  (almost continuously during the months
of December and January).

Findings documented from field investigations were:

     o   High flows  occurred  in  response to rainfall.  .The ratio
         of PWWF to ADWF was projected to be about  11 to l. .-•

     o   Identified  direct  inflow  accounted  for  less  than  20>'
         percent of the projected rain induced extraneous flow.

     o   Numerous pipe  defects were detected in  sewer mains and
         building laterals from smoke testing studies.

     o   TV inspection detected numerous defects in sewer mains.

     o   Dye flooding tests confirmed that over 90 percent of the
         potential   storm   drain/sanitary   sewer   connections
         identified by  smoke  testing were through defects in the
         sewers rather than direct connections.

The ,high rain induced flow response, the fact  that direct inflow
connections accounted for  less than 20 .percent of  the peak';rain
induced extraneous flows, and  the prevalence of  defects  in sewer
mains and laterals indicated  that RII  is a significant component
of peak wet weather flows in the Springfield sanitary sewer system.
The key factors affecting  RII appear to .'./be the  condition^ of the
sewer mains  and laterals, groundwater  conditions> and  the high
seasonal rainfall in the service area.

The City has conducted rehabilitation of  the sewer mains and lower
laterals in four areas of the  system, utilizing primarily grouting
and replacement.  Rehabilitation of private  laterals has also been
done in several small special  project areas.  Analyses of the flow
reductions achieved by  these  rehabilitation projects  are not yet
complete.        •

Milwaukee Metropolitan Sewerage District

The Milwaukee Metropolitan Sewerage District serves  28 communities
in the southeastern portion of Wisconsin, the largest of which is
the City of Milwaukee.   The total service area includes over 2,800
miles of sewer mains, of which approximately 20 percent are of the
combined storm/sanitary type,  mostly located within the City of
Milwaukee.   The remaining 80 percent of the District is served by
separate  sanitary  sewer  systems,  which  were  studied  under  a
comprehensive  SSES.    Problems  caused  by , high  rain  induced
                               2-17

-------
                        Problem Assessment


extraneous  flows have  included overflows and  bypasses  from the
interceptor  and  collection systems,  wastewater    back-ups into
building  basements,   and  discharges  of  inadequately  treated
wastewater to Lake Michigan.

The field investigations  conducted  in  the separate portion of the
sewer system documented the following:

     o   High peak -flows  occur  in the  system, of which 76 percent
         could  be contributed  to  rain induced I/I  (RII  + SWI).
         The ratio of PWWF to 2^DWF was projected to be about 7.5
         to 1.'

     o   Numerous defects  were  found  in manholes from  smoke
         testing and  physical  inspection  programs.

     o   Manhole frame/chimney defects were  found to contribute
         significant  flows based  on  street  flooding  studies  to
         simulate rainfall  conditions.

     o   Numerous  direct  foundation drain  connections  were
         identified through building inspections.

     o   Indirect connections between storm  drains  and sanitary
         sewers  were  found by  smoke testing  and  dye  flooding
         programs.                                   ''

     o   Foundation  drains and building  laterals  exhibited peak
         flow responses  to rainfall and to experimental rainfall
         simulation.

     o   Approximately 60  percent  of peak  extraneous  flow  was
         attributed   to  RII,   including  40  percent   through
         foundation   drains  and   12  percent   through  manhole
         frame/chimney joints.

The high  rain induced flow response  and the presence  of sewer
system defects and foundation drain connections that  accounted for
60  percent  of   peak  extraneous  flows indicate  that  RII  is  a
significant problem in the  system.  The key factors  affecting RII
appear to be the prevalence of  foundation  drain connections, storm
and sanitary sewer laterals constructed in the same trench in many
areas of  the  system,  high  groundwater,  and frost heave.   Frost
heave, or  lifting and distortion of  the ground  surface  due  to
subsurface ice formation, is believed  to be a major  factor in the
formation of  manhole frame/chimney  defects  and  the cracks  in
concrete pavements that generate pathways to these defects.
                               2-18

-------
                        Problem Assessment,


As a result "of .its SSES, the District has conducted, I/I correction
work, primarily aimed at eliminating direct inflow through manhole
covers and RII from manhole, frame/chimney interfaces.  The District
conducted  a  manhole rehabilitation  pilot  project  to  evaluate
different methods-of  correcting manhole frame/chimney leakage.  Two
of   the   District  communities   have   successfully  implemented
foundation drain  disconnection  programs.   A permanent monitoring
system is  being  installed for  long-term monitoring  of  I/I flows
throughout the District.
           h   '       '                             '            "
Nortneast Ohio Regional Sewer District

The Northeast Ohio Regional  Sewer District  includes .41 communities
in the Cleveland*  Ohio,  metropolitan area.  The District is divided
into two major subdistricts: The City of  Cleveland, which has  a
combined  sewer system;  and the surrounding  communities,  which
primarily have separate systems.   Most of  the separated portions
of the system are  contained within two major planning areas, the
Easterly Separate  Sewer Area and the  Southwest  Interceptor Area
which together contain approximately 1,200 miles of sanitary sewers
serving a population of about 500,000,     >     .

Overflows arid bypasses occur at over 200 locations in the separated
sewer  systems,  most  initiated  by  rain  events of  less  than 0.2
inches per hour.    Pump stations  and  regulator chambers  in the
interceptor  system  are". used  to  restrict,  flow to  the  WWTPs.
Basement back-ups are a major problem during wet weather.

Field  investigations  in the. separate  sewer  areas  documented the
following:                    .    '     .                        ,

     o   High flows  occurred   in  the  system  in  response  to
         rainfall.  The ratios of PWWF to ADWF was projected to be
        .about 12  to 1  in the  Southwest Area and over  20 to 1 in
         the  Easterly Area.  •                    '             .

     o   Identified  direct  inflow accounted  for , only  5  to  15
         percent of  the peak extraneous flow.

     o   Sanitary - and  storm sewers and  building laterals  were,
         constructed  in common trenches in over 50 percent of the
         separate  system.                ,

     o ;  Indirect  flow  transfer  from storm to  sanitary sewers was
         found  to be very  rapid,  as  documented by  dye flooding
         tests.
These findings indicated that RII is a significant problem in the
sewer system.  The most  significant factors affecting RII appear
                               2-19

-------
                         Problem Assessment


 to be ^the  poor  condition  of the  sewers  and  laterals  and  the
 extensive common trench storm/sanitary system.   Therefore,  storm
 drain exfiltration appears to be the primary pathway for  Rll into
 this  system.

 RII correction efforts  in the District have primarily concentrated
 on rehabilitation and flow regulation in the  storm  sewer system,
 with  some   sanitary  sewer  rehabilitation.    Work . has  included
 construction  of   new  storm  sewers  to   replace common trench
 facilities   and  provide  additional  storm   drainage  capacity;
 rehabilitation of common trench storm/sanitary sewer manholes; and
 installation o'f vortex  regulators to restrict flow into the  storm
 drain system  and thereby  reduce  the transfer  of   flow to  the
 sanitary system.

 City  of  Baton Rouge,  Louisiana

 The City of Baton Rouge is located  in the southeast portion of
 Louisiana along the Mississippi River.  Its  sewer system  serves a
 population of  about 450,000 and includes approximately 1,500  miles
 of mains.   The system is divided into four major areas,  three of
 which comprise the original Consolidated  Sewer  District  and the
 fourth,  the suburban area.  Each of the three original Consolidated
 Sewer District areas  is  served by its  own WWTP; the  suburban area
 includes 144 local wastewater treatment facilities.   Overflows and
 bypasses have occurred  throughput the sewer  system during high
 intensity storm events.

 Findings of  field investigations  were  as follows:

     o    High peak flows occurred in the system in response to
          rainfall. The  overall ratio of PWWF to ADWF  is estimated
          to  be about  3.5 to  1.

    o    Numerous defects were detected in sewer mains, manholes,
          •and building laterals through smoke  testing programs.

    o    Most  potential transfers of  water  from  storm  drains to
          sanitary sewers were  found to be through defects in the
          sewers.

    o    In  four  special  study areas, building  lateral  defects
          were  found  to  account for 32 percent of the  potential
          peak  rain induced  extraneous flow,  with the  remainder
          coming from .sewer mains  and manholes.

The high rain  induced flow response, the absence of direct inflow
connections  to account  for  any substantial portion* of. the  peak
flows", and the prevalence of defects in sewer mains  and  laterals
indicated that RII is a significant component of peak wet weather
flows  in the Baton Rouge sanitary sewer system.   The key factors
                               2-20

-------
                       Problem Assessment
                                                         \   - - '  '


affecting  RII  appear  to be  the poor  condition,  of sewers  and
laterals,  due  to  both   age  and  lack  of  system  maintenance ;
construction of sewer trenches in drainage ditches;  and the shallow
depth of building laterals.         '•

The City is  implementing  a  rehabilitation  program  to correct all
main  line  defects  identified during field  testing in  the four
special study areas.  Rehabilitation techniques will include spot
repair, pipe replacement, slip-lining, and manhole sealing.

City of Springfield, Missouri

Springfield  is  located in southwestern Missouri.   The wastewater
service area is divided into two main drainage basins, each served
by a separate WWTP.  The  larger of the two basins is the Southwest
area, which  includes approximately 80 percent  of  the City.  This
area  includes  over  500  miles  of  sanitary  sewers, which serve
approximately 160,000 people.

Identified  problems due to  rainfall induced extraneous  flows
include  surcharging of and  overflows from  the collection system,
as well  as   basement flooding.   Overflows  occur at approximately
ten sites during any good-sized storm, and at 100 or more locations
during  large rainfall  events.   I/I  correction efforts  aimed at
eliminating  direct  inflow and the repairing  of isolated problem
sewer reaches did not have a noticeable impact on peak wet weather
flows.

Findings "of  limited field investigations included:

     o   High  flows occurred in  response  to  rainfall,  with the
         ratio of  PWWF  to  ADWF estimated to  be  about 8  to 1.
         Larger,  longer  duration storms  produced higher and more
         sustained  peak flows than  short-duration, thunderstorm-
         type  events.

     o   Relatively few direct  inflow connections were found
         through smoke^testing programs.

     o   Evidence  of   infiltration  through manhole  walls  and
          inverts was observed during physical  inspections.

     o   Clear water discharges from laterals were  observed during
         TV inspection work.             •  >

     o   Many  sewers  were  installed in  the  shallow  limestone
         bedrock, which  supports a  perched grbundwater table  in
         much of the area.

The  high rain  induced  flow  response  and  the  failure of the inflow
correction  program to   reduce  rain  induced  extraneous  flows
                               2-21

-------
                        Problem Assessment


indicated that RII is probably a significant component of peak wet
weather flows in the system.   The key factors affecting RII appear
to  be  the  age  and  poor  condition  of  the  sewers  and  the
hydrogeologic conditions characteristic of the service area, which
are conducive to rapid transport of water to sewer defects.

The City has  conducted sewer grouting  in the  system since 1972,'
primarily concentrated in older areas.   A  pilot project in a newer
area was  also conducted,  with  sewer  main  grouting  and manhole
sealing.   No significant  flow reductions were  achieved through
these efforts.   The City has  implemented a  long-term correction
program involving routine TV inspection and rehabilitation of sewer
mains on a priority basis, primarily by slip-lining.

North and South Shenango Joint Municipal Authority, Pennsylvania

The North and South Shenango Joint Municipal Authority includes the
Townships of North and South  Shenango,  which are  located along the
shoreline of  Pymatuning Reservoir  in  northwestern Pennsylvania.
The Authority  operates a collection system and  treatment  plant,
which serve  a permanent population of about 1,200  and  a  summer
population of approximately 6,000.   The collection system includes
approximately 90 miles of sewer mains and several pump stations.

The sanitary sewer  system was •originally  constructed  in 1978.
Although the contract specifications for the sewer system included
strict criteria  for maximum allowable  infiltration,  wet weather
flows in the  system have far exceeded design capacity, resulting
in overflows at the  pump stations and hydraulic  overloads  of the
WWTP.   Major wet weather problems have occurred  in four areas of
the system that were installed under one construction contract and
with clay pipe made by a different manufacturer than that installed
in other portions of the system.                       .

Findings of field investigations were:

    o    High  flows   occurred   in  response  to  rainfall,  with
         sustained  peak ' flows  after  the end  of rainfall.   The
         estimated  ratio of  PWWF to ADWF  is about 7  to 1.

    o    High grpundwater exists in much of the area, and a large
         portion of  the  sewer  system is submerged.

    o    Rapid  increases in  water  levels in  sewer trenches .from
         rainfall occurrences were noted through monitoring water
         levels in the trenches.

    o    The rate of infiltration into  individual pipe joints was
         found to  increase directly with the depth of water over
         the pipe.
                               2^22

-------
                        Problem Assessment:


     o    Many sewers were constructed directly under area drainage
  '  .      ditches.;              .'"•/'    .

     o    Limited  smoke  testing  detected  no significant  direct
          inflow connections. '

     o    Very little extraneous  flows  from building  laterals was
          observed during TV inspection of sewer mains.

 Sewer  flow and trench water level  responses  to  rainfall, .as well
 as the absence of direct inflow connections  confirmed that the high
 rain induced extraneous flows in the North and South Shenango sewer
 system are due to RII.  Entry points of RII appear to be primarily
 through defective pipe, joints.  The other key factors which affect
 RII are the construction  of sewer trenches in drainage ditches and
 the high groundwater level in the service area.

 To correct the RII problem, the Authority is slip-lining all of the
 sewer  mains and slip-lining or  replacing the lower laterals in the
 four problem contract areas  (the upper laterals are constructed of
 PVC pipe   and  are  not  believed  to  contribute RII) . .   Limited
 rehabilitation    work   conducted   prior   to   the    full-scale
 rehabilitation   effort   indicated  that  grouting  would  not  be
 effective in  eliminating infiltration through the pipe joints.   A
 pilot  slip-lining project, however, appeared to  achieve virtually
 complete elimination of extraneous flows.  '

 City of Ames, Iowa

 Ames is  located in central Iowa along the Skunk  River.    The
 collection  system,  containing approximately 135 miles of  sewer
 mains,  serves a population of approximately 45,000, almost half of
 which  comprise  the Iowa State University campus.\

 During-wet weather periods,  the WWTP cannot treat all of the peak
 flows  in the  system.. sAn influent .sluice gate must be throttled,
 often  for  as  long  as  several  days, to  limit flow entering .the
„plant.   Several times each year  during  extremely wet-conditions,
 bypassing of raw wastewater occurs both at the plant and at several
 points in  the  collection system.   Basement .backups during  wet
 weatlier also  occur as a result  of high wet  weather flows.

 Findings of field investigations  were as follows:

     o,   High peak  flows occurred in response .to rainfall.   The
          ratio  of PWWF to ADWF is estimated to be about 6 to l.

     o    Identified direct inflow  accounted  for about 40  percent
          of the peak extraneous flow.
                               2-23

-------
                         Problem Assessment:


      o ,  A   survey  identified  1,800   direct  foundation  drain
          connections   to  the  sanitary  sewer  system.     Many
          additional potential connections, where foundation drains
          incorporated valving to divert flow to the sanitary sewer
          during freezing conditions, were also identified.

      o   Foundation  drains  were  found  to  exhibit  peak  flow
          responses based on a  study of the  impact  of  simulated
          rainfall on foundation drain sump pump operating times.

      o   The flow from foundation drains was estimated to account
          for  about 50 percent  of peak  extraneous  flows  in  the
          system.

 The high  rain induced flow response, the existence of many directly
 connected foundation drains,  and documentation of the peak  flow
 response  from foundation drain  discharges to  rainfall,  indicated
 that RII  is a significant component of peak wet weather  flows  in
 the Ames  sanitary sewer system.   High groundwater  appears to  be a
 key  factor  affecting the  occurrence of RII, through  foundation
 drains.

 As part  of  its  overall  I/I correction program,  the  City has
 implemented a foundation drain  disconnection  program targeted  at
 eliminating  768  foundation  drain  connections  over  a  ten-year
 period.   The program  involves  a  public information effort and
 includes  provisions to reimburse a large portion of the homeowners'
 disconnections costs.  Over 300 disconnections were achieved in the
 initial two years of the program on an  entirely voluntary basis.
 The City anticipates  that  the  program  will  continue beyond the
 required  768 disconnections.

 City of Coos Bay,  Oregon

 Coos  Bay  is  located on  the  southwest  coast of  Oregon.   The
 wastewater system serves a population of about  15,000  and  contains
 approximately 60  miles of sanitary sewers.   The  sewer system  is
 primarily a  separate  system,  although a small  portion is  believed
• to be partially combined.  The City is divided  into two main sewer
 service  areas, each  served  by  a  separate  WWTP.   The  major wet
 weather  flow problems are concentrated in  the collection  system
 which serves  the  eastern portion  of  the  City and  an  adjacent
 sanitary  district.   Problems due to  high peak wet weather flows
 have  included bypassing and  overflows  in the collection  system,
 as well  as bypasses  of  untreated   wastewater  and  discharge
 requirement  violations  at the WWTP.

 The occurrence of RII  in the Coos Bay sanitary  sewer system  is
 indicated by the following:
                               2--2 4

-------
                        Problem Assessment:


     o    From the  early 1970's through 1982, field investigations
          and  rehabllitatio^ work to reduce extraneous flows were-
          conducted, including disconnection of known, direct inflow
          connections  (downspouts and cross  connections  with the
          storm  drain  system)   and  a  sewer main . rehabilitation
          program.                '
  c                  \       -        '       .'       . <      .       .
     o    Smoke  testing  conducted  after  the  rehabilitation work
          confirmed,that almost all direct inflow connections had
          been eliminated from  the system.

     o    High peak wet  weather flows still occurred in the system
          after  completion  of  the  rehabilitation  program.   The
          ratio  of  PWWF  to ADWF was projected to be  about 8 to 1.

This  evidence indicates that the peak rain  induced  flows in the
sanitary sewer system appear to be due primarily to RII.  The key
factors affecting RII  are the poor, condition of the sewers, due in
part  to ground  settlement in the bay,mud which underlies"much of
the older portions of the system; the shallow depth .of building
laterals; and.the high groundwater which characterizes the service
area.   "      .,     -   "••••'.   •.->..'••         •   ...'••   .-'.-••   ...
                  . -     ' .   .     ''      •  ••.-,      - •        *
In previous  years,  the city has  conducted rehabilitation (primarily
grouting and  some replacement)  of sewer mains with major problems
identified  through TV  inspection  and- smoke  testing.    As noted
above, these  efforts did not result in any significant reductions
in wet weather flows.  However,  a program of routine TV inspection
has been  initiated to  identify specific  areas in need of repair
or replacement'.

City of Tulsa, Oklahoma

Tulsa is  located in,northeast  Oklahoma along the Arkansas River.
Total service area population  is approximately  400,000,  and the
collection system  includes  over  1,400 miles of sewer mains.   The
City has conducted field  investigations and rehabilitation of the
sewer  system  since  1982,  both as  part  of  overall  facilities
planning efforts to reduce sanitary sewer  surcharging and overflows
during rainfall.    •       ,

Field investigations documented that:     ,                ,   .

     o    High peak flows occurred in response to rainfall.   The
          ratio of PWWF to. ADWF  is estimated to  be about 3.5 to 1.

     o   Numerous defects were  found in sewer mains, manholes, and
          service laterals  from smoke testing programs.

     o   Defects   were   observed  in  sewer   mains   through  TV
    .      inspection efforts. ,            -  ,
                               2-25

-------
                        Problem Assessment.
     o   Direct  inflow connections detected through smoke testing
         accounted  for  30  percent  of  the  estimated extraneous
         flows.  RII accounted for the remaining 70 percent.

     o   Of the potential flow contribution from RII entry points
         detected  during  smoke . testing,  about  45   percent  Was
         estimated  to  be from service laterals,  35  percent from
         sewer mains, and 20 percent from manholes.

     o   The  estimated  flow  contributions   from  direct  inflow
         connections and sewer system defects identified through
         smoke  testing  could  not account  for all  of  the  rain
         induced extraneous flows.

The  high  rain  induced  flows,   the  fact  that'  direct  inflow
connections   accounted  for less  than  30  percent  of  the  peak
extraneous flows, and  the prevalence of defects  in  sewer mains,
manholes, and service laterals  indicated  that RII is a significant
component of peak wet  weather  flows  in  the  Tulsa  sanitary sewer
system.  The key factors  affecting the occurrence of RII appear to
be the poor condition  of  the  sewers system,  shallow  depth  of
laterals,  granular  trench  backfill, and  the  shallow  limestone
bedrock that characterizes the service area.

Rehabilitation was  performed as part of the  City's SSES.   The
rehabilitation work consisted primarily of slip-lining, inversion
lining, pipe replacement, manhole sealing, and spot repairs of the
public  portions  of  the  system  (mains,  manholes,  and  lower
laterals), as well as disconnection of direct inflow sources.   In
general, only  those specific defects detected through  the  SSES
field work and determined to be-cost-effective f,or correction were
addressed.   Voluntary  repair  of  leaking private  laterals  and
cleanouts was encouraged through a public relations program.  For
eight subbasins in which  rehabilitation was performed, the initial
reductions  in  peak wet  weather  flows were  reported  to average
approximately 50 percent.

SUMMARY

     o   RII is a form of infiltration into sanitary sewer systems
         characterized by a significant, short-term increase in
         flow in direct  response to  rainfall.

     o   RII  enters the sewer system   from  the  ground through
         defective  pipes  and manholes   and through foundation
         drains.    RII  entry  points are  similar  to  those  of
         "classical"  infiltration,  or   groundwater   infiltration
          (GWI).
                               2-26

-------
                Problem Assessment
 The RII  flow response may be indistinguishable from that
 of direct storm water inflow  (SWI)  if  it is very rapid
 and short-termed:

 The RII  flow  response  is likely a continuum from a very
 gradually changing flow, similar to GWI,  to a rapid peak,
 similar  to: SWI.

 The  traditional  methodology  for  analysis  of  I/I' has
- resulted in RII being incorrectly identified as inflow in
 many sewer  systems*  ,                              .

 Peak wet weather flows due to RII can cause overflows and
 bypasses in  sanitary  sewer, systems and  at wastewater
 treatment plants,  as well as backups of wastewater into
 building basements.  Peak wet weather flows  include base
 wastewater  flow plus GWI plus rain induced  infiltration
 and inflow.                      ;
                      *•         "       •          -        -
 To handle RII flows, sewer  pipelines and pump stations
 and  wastewater treatment  plants must be designed with
 considerable  additional  capacity to convey  and treat
 relatively  infrequent, but  large peak flows.

 Estimated RII  ranged from over 50 to nearly iOO percent
 of total peak rain  induced  extraneous  flow for the ten
 case  studies  documented in this  investigation.   Rain
 induced    extraneous  flow    includes    only   ra'infall
 - infiltration  and  inflow.

- Possible pathways of storm water flow  from the ground
 surface  to  the sanitary  sewers may  include:

 -    Soil  channels  from the  ground  surface to sewer
      defects.      «

      Exfiltration out'of leaky storm drains through the
      soil to defects-in sanitary sewer pipes.

 -    Seepage  through  pavement  cracks   with horizontal
      movement  along the street subbase  -to  the upper
      portions of sanitary sewer  system manholes^

 -    Percolation into permeable trench backfill materials
      and along pipe  trenches to  defects  in sewer pipes.

 RII  was found to  enter  sanitary  sewers through pipe
 defects  in sewer  mains and building laterals,  manhole
, defects, and  foundation  drains directly connected to
 service  laterals.                    .
                       2-27

-------
                    Problem Assessment
 o    Several factors were found to be significant in the
     formation of RII entry points.

          Age of the sewer system.
     -    Type of pipe and joint  materials.
     -    Construction practices.
     -    Lack of proper maintenance.
     -    Freeze/thaw conditions.
     -    Earth movement.
          Root intrusion.                            .
          Lack of ordinance enforcement prohibiting foundation
          drain connections.

o    Defective   building  laterals   and  foundation  .drain
     connections   on   private   property   can   contribute
     significant RII'  flows,  and  even the majority of RII  in
     some systems.

o    Different types of RII entry points appear to predominate
     in various geographical areas of the U.S.

     In areas where foundation drains are common, such as the
     midwest, foundation  drain connections  can .contribute a
     major portion of the RII.  Where sewer mains and  laterals
     are  relatively  shallow,  such  as   in  the  western and
     southern portions  of the  .U.S. ,  pipe defects may be the
     predominant RII entry points.

o    For the  systems reviewed in  this  study,  the projected
     overall system peak  wet  weather flow (PWWF) to average
     dry weather flow (ADWF) values ranged from  about 3.5  to
     over 20.

     However,  projected  peak  flows  are  not   necessarily
     directly comparable  because they  are  based on design
     storm criteria specific to each system and  also because
     they typically include at  least some component of SWI and
     GWI.

o    It is  likely  that  RII  can occur to some  extent in any
     sewer system and can be  a significant  component of wet
     weather flows.

     While the sample of  RII  case  studies evaluated was not
     large  enough  to   conclusively  determine  the national
     significance  of  the  RII  problem, sewer   system and
     environmental  factors  which  appear to  influence the
     occurrence of RII can be  found in systems throughout the
     country.
                          2-28

-------
              Problem Assessment
Problems associated  with defective sewer pipes  are not
limited to RII-.   Exfiltration of untreated sewage through
these defective pipes may contaminate ground-water.  This
problem is likely to manifest itself when the sewer:pipe
is above the' water table.
                      2-29

-------
                   Problem Assessment
C
          S1


          a.
T  u
*"*  <
td  y

=  u.

s  s
   ee
          I

          1
Fulfill of Rll Entr
        Iv"?
        •aSts
         -"3
I
C

ar

ili

to
       i»|.

       ill
                          a
                          T9

Condition of sc
                  a
                  2
                                                     i$ii
                                                     &1 «I «

                                                     I 141 f

                                                     •s te S s
                                                     g t* -8 3

                                                     ll'.ll
                                                     S S. » 6 js
                                                     •A  > •— w =C
                                                    " s a s g §
                                                     « K e g i
                                                     ai ™ M a —
                                          1 i
                                            s
                                                    S Q £

                                                    HI
              -S a

              ?!
      fi
o


i
                        s-

                                 Q




                                 1
                                           Q
                                           en


-------
                   Problem Assessment
<






' ^ ;

••


S
z
1
'•S
w
5
£
MARV OF CASE
S.
5«












i
u
i
e
' : y
1
~ e
|i
*

*
i
j
«
]
s
*
£
1
^f
•s
i
§
,


Point! of Rll Entry
fxf
£•35 "S
** •««•
I*
5
§
•s.
. • ft _

•ifi

alt
• in
_- u a.
Ili
op s a


•"• '..'" ''



• ' s
.5 .
.* S
S 1
. '.lei



•3
-':-*!
•-

' .. 2
• Sewer main defects
• Service lateral defec
• Foundation drain
connections
'UK
10

' o - ' •
s.
• ~3
T*
ts
00

'5
CO
l' •'•*'•• -sift
= j{ . • 3= --S
>«i '" 'S SS=">^
'•*.! ll ! -sl^i
•«?'- 1| II 'lf^ •
.&^ § 'S * -''I 2 55 — ^^
* 1 '£1; If . Sl-fll
' •'"'•",'

r> • « ae .*> ' -
<*1

•' ' •' ' ' "" "/-
1 ' ' 3s -£H
SO ^ ^*
2 ' w • • i. • ._ e ra
.= S 5 • S S
| ? | ' |1 ||l
f-^s £ gs g g-o


«s '
s. ' '. e s .
3. .s " SS ^
tC 8 § 8
, -o . -^ _
eg ° — O
™ 55 ~ ^? -5
•S' ll ll i
V K 5 ' * 2 35 '
a £ S C 3 . <3

* * * ^ *
•J> at
t3 S
M w «« g
I -'a* SSa
' ,-i "Sl '«lS
, I g§ -IS -12*
;s a g f 8 f 8 f •
= '• ii II lls
s- s s • s . :
~, *- •
< / ~ . '
i . . *
§• -. °
1 -•• -.-•• 1 ,P •; • • ;
«5 S at  i
if

:r FlowPWWF ma)
ly comparable bell
x -e
^ i
£.i ,
ly combined system.
w; ADWF = Average D
WF/ADWF ratios are iwi
III-
^ — "2
o u r»
i-sjj •
£.
l&a

&^ o
<• f •

-------
                             CHAPTER 3

                          CONTROL METHODS

 This  chapter  discusses  different  methods  and  approaches   for
 controlling rainfall  induced  infiltration into  sanitary sewer
 systems.   The  basis of the  discussions was  a literature search to
 identify   sewer  system  rehabilitation  methods  currently being
 practiced both in the U.S.  and  in other parts of the world.   In
 addition,  the  discussions draw upon information .collected  as part
 of  the RII candidate  system search and case  study documentation
 presented in Chapter 2.  A description of an "example" RII  control
 program,  that  of EBMUD,  is  also  presented.

 "Control"  means  the implementation of methods to  reduce existing
 RII  flows or limit future RII into a sewer system.  RII control  can
 be accomplished through physical rehabilitation of existing sewers
 and    application  of  proper  design  standards  and construction
 practices  for new sewers.  Institutional and regulatory approaches
 and  preventive maintenance programs  are means  of facilitating
 implementation and  ensuring  the  effectiveness  of RII   control
 programs.   The success of an RII  control program  is dependent not
 only on the application of appropriate engineering techniques, but
 also on the overall  implementation approach  used.

 Typically, control methods are aimed at correcting the entry points
 of extraneous  flows into, the  sewer system.  • physical  methods to
 rehabilitate   sewers  are  largely  applicable  to  all  types  of
 infiltration (GWI and RII).   However, RII control  differs from GWI
 control in the approaches used  to quantify flows and identify entry
 points, and the  relative importance that is placed on correction
 of particular  components  of the  sewer system  (e.g., mains versus
 laterals).    For  this  reason,   this  chapter also  includes  a
 discussion  on  field  investigation techniques  to quantify  and
 identify RII,  as well  as various approaches for implementing RII
 control programs.

RII  FIELD INVESTIGATION TECHNIQUES

 In general, the same traditional methods that have been used for
conventional I/I  investigations  and  SSESs  can be used  as field
techniques  for RII investigation.    However,  to identify  and
quantify   RII,   it   is  critical   that   the  field  methods   be
appropriately  applied  and the  data be properly interpreted.   The
 field  techniques  and  methods of  data  interpretation,  as  they
specifically apply to RII, are discussed below.
                               '3-1

-------
                         Control Methods
Flow Monitoring                                    '

Flow monitoring is commonly used to quantify I/I flows in different
portions of a  sewer  system.   To obtain  accurate  and  useful flow
data, no hydraulic constrictions should  exist in  the  vicinity of
the flow monitor, and the sewers upstream  and downstream of the
monitoring site  should be cleaned prior to monitoring to remove
major root .intrusion and sediment buildup.   The monitoring manhole
ideally should have  smooth  transitions  and no .side  streams or
changes in flow direction. Collection of useable  flow  data can be
better assured by appropriate choice of monitoring  equipment (e.g.,
depth-velocity  meters versus  level-only recorders),   as  well as
suitable monitor  location.   Surcharging  or  backwater effects must
be carefully evaluated in interpreting flow monitoring results.

The traditional approach for  analyzing  wet weather  flows  is to
subtract the non-rainfall base flow (base sanitary flow plus GWI)
during  the period, immediately preceding a  storm  event  from the
total  flow during  and  immediately  following the  storm.    The
difference  is, the   rainfall  induced   infiltration  and  inflow
(RII+SWI).  An adjustment can be made to  account for the higher
sustained  GWI  rate  at the  end  of the. storm  (see Figure 2-1).
However, it is generally impossible to distinguish SWI  from RII on
the basis of this hydrography alone.

One  approach  to interpreting  the  (RII+SWI)  hydrography  is to
separate.it  into component parts,  each  representing  a different
response time  to rainfall.   This  type of analysis-can be used to
identify the relative significance  of  different types of RII by the
relative magnitude of each hydrography component.  The most rapid
component  (shortest time  to peak) will include the SWI portion of
the  flow,  as  , well  as  some portion of  the RII.    The slower
components will  typically consist of  RII only.

If the  flow monitoring period  is long enough to include different
types of storms  (e.g., short, intense storms and extended  duration
storms),  then  a comparison  of  (RII+SWI)  hydrographs  may  also
indicate the relative significance  of RII  in the  system.  In  some
systems, it has been found that longer-duration storms  and/or those
characterized   by considerable antecedent  rainfall'produce higher
peaks  and  larger  RII' volumes  than  comparable  isolated, short-
duration storms.
                                3-2

-------
                          Control Methods


 Flow Isolation

 Flow isolation  or flow mapping  is  a technique commonly used  to
 determine the relative I/I contribution from different "minibasins"
 or reaches of sewer within a subsystem.  The procedure consists  of
 taking  instantaneous>  manual  flow  measurements  at  successive
 manholes.   For RII  isolation,  flow  measurements  are  taken  during
 and immediately after rainfall.

 Since the  objective of RII  flow isolation is to determine the peak
 RII contribution at different locations in the sewer  system, care
 must be taken in  comparing measurements  from  different locations
 taken at  different  times  during the  rainfall.   One  way to help
 overcome this difficulty is to place a continuously recording flow
 monitor  at  a  location   downstream   in  the  subsystem.    The
 instantaneous measurements taken within the subsystem  at various
 times during and after the  rainfall are then projected to  a peak
 flow (assumed  to  occur at  the  same  time  as  the  peak  of the
 downstream monitor hydrograph).  The  projection  is based  on the
 ratio of the monitor flow  at the measurement time to the monitor
 peak flow,  if flow  isolation is conducted several hours after the
 peak rain  period  but still  while  the flows  are elevated  above
 normal  levels,  the measured flow  can reasonably be assumed  to
 consist primarily of RII  because the SWI flow hydrograph  should
 already have  receded.

 Flow isolation during rainfall is  an  effective way to determine the
 distribution  of  RII in the subsystem.   This allows rehabilitation
 efforts to be concentrated in those  minibasins  with  relatively
 higher  RII contributions.   Equally important,  any losses in flow.
 between successive manholes indicate exfiltration and  therefore,
 appropriate  corrective  measures  for  the  problem   should   be
 considered.

 Groundwater Monitoring

 Groundwater monitoring  is  used to determine the elevation of the
 groundwater with respect to that of  the sewer system and its  long-
 term or short-term variations.  Groundwater monitors placed within
 a  sewer. trench provide  a  direct measurement  of  the  hydrostatic
 pressure on defects in  the sewer pipe.   Continuously  recording
monitors can be used to determine short-term responses  to rainfall,
which can then be correlated with  flow measurements in the sewers.
 Ground-water monitoring can also be  used to monitor the  quality of
ground-water  when  exfiltration is  determined to  be  a serious
problem.

Smoke Testing   .

Smoke testing is  the traditional field method used to detect direct
inflbw  entry  points.   Under appropriate conditions,  it can also
                               3-3

-------
                           Control Methods


  identify some types of RII entry points.   Specificariy,  for  smoke
  testing to be an effective RII investigation  technique,  the  sewer
  must be above the groundwater level and the soil must be relatively
  dry.   Under these  conditions, smoke will be transmitted  through
  channels in the  soil and be detected as visible emissions from the
  ground over defective  sewer pipes,  laterals, and manholes,  or from
  storm   drains  or  catch   basins  .(in  the.  case  of  RII  due  to
  exfiItration from storm drains).      ,

  In general, detection  of RII entry points by smoke testing will be
  most successful  in  cases where most of the defects aire close to the
  ground surface (i.e.,  shallow mains and  laterals)  and where  there
  are relatively few direct inflow connections  (since these  sources
  would  tend to draw most of the smoke).  ,The absence of smoke from
  potential RII entry points does not mean that they do not exist;
  some pipes  may have  traps or  sags that  prevent smoke  travel.
  However, the defects that do emit smoke are  likely to be those with.
  the most rapid flow response to rainfall.           ,             ,

  Dye Flooding

  Dye flooding  is generally  used  to verify  direct and  indirect
  connections between storm drains and sanitary  sewers.    A  storm
 1 drain  or ditch is flooded with dyed water,  arid the sanitary sewer
  is observed for  appearance of the dye in the flow stream.,   The flow
  rate and concentration of the dye  gives an indication of  whether
  the- connection  is  direct or  indirect.    TV  inspection  of  the
  sanitary  sewer   concurrent  with  dye  flooding  provides, direct
  evidence of specific locations where RII enters the sewer.   If the
  storm   sewer  is completely  flooded  (surcharged)  during the  dye
  flooding,  the  rate of flow  into  the  sanitary  sewer  (or  into
'• individual defects) may  approximate the peak  RII flow during  a
 .large  storm.

  Street Flooding            .

  Street flooding  can be used to; identify and quantify RII flows into
  such entry points as manhole frame/chimney defectSi  Surface water
  is prevented from  entering  the manhole  by placement  of an  inner
  tube in the frame opening, which still permits visual observation
  of the flow entering from the  ground, below the frame.  The ..leakage
  rate  through  the  manhole frame/chimney  defect  is measured  or
  estimated  based   on  observation.    Leakage   rate  under   this
  "simulated" rainfall condition is  assumed  to  approximate  the RII
  flow.   ,           .

  Rainfall Simulation

  Rainfall  simulation  consists  of applying water  to  an  area  of
  suspected  RII  and observing or  measuring  the resulting  flow.
                                 3^4

-------
                          Control Methods


 Rainfall  simulation  is  typically  used  on  a  limited  basis to
 estimate  flows  from foundation  drain  connections or defective
 building  laterals.    The results of  rainfall simulation provide
 evidence  as  to the  potential  magnitude and speed of  the  flow
 response  to  rainfall  from these system  components.  Note that RII
 flows  during  actual  rainfall  events  can also  be .observed or
 measured  in  a similar manner.

 Manhole and  TV  Inspection

 Physical  inspection of manholes and internal television inspection
 of sewers are used to identify defects in sewer pipes and manholes
 which can be potential entry points for extraneous flows.  Material
 deposits  and stains, often indiceitors of infiltration, can also be
 observed.  If conducted during rsiinfall, manhole  and TV inspection
 can identify specific entry points of RII.  TV inspection as  a RII
 detection technique   is  limited  because  many  sewers  become
 surcharged   during   rainfall   conditions,   thereby   preventing
 observation  of  RII  entry to the system.   Also, an apparently good
 sewer  (no observed defects)  does  not  necessarily mean  that RII
 entry points do not exist.  Quite  often, infiltration occurs  below
 the wastewater flow line or  at joints in the sewer pipe that cannot
 be seen by the  camera.

 TV inspection is relatively expensive and generally should be used
 only after a specific sewer reach  has  been identified through flow
 isolation or dye  flooding as  contributing significant RII flows.
 Its use for inspection of building laterals  provides the same type
 of  information,  but  lateral  TV  inspection  generally  requires
 special "mini-cameras" which can crawl or be pushed up the lateral.
 Lateral TV inspection is also limited by the availability of access
 points (cleanouts).

 Building Inspection

 Physical  inspection of  building  basements is  used to  identify
 direct foundation drain  connections to the sanitary sewer system.
 Floor drains  are  inspected  for  evidence of  a  connection with the
 foundation drain (via a Palmer valve or drain tile receiver).  Sump
pump  discharge  points  are   also   determined   during  building
 inspections.

 SEWER REHABILITATION METHODS

Rehabilitation  refers  to  physical repairs  or   modifications to
sanitary sewer system components which can reduce  the amount of RII
entering the system.  Sewer  rehabilitation as  a RII control method
 is generally aimed at eliminating RII entry points,  specifically,
pipe and  manhole  defects and foundation  drain connections.   The
selection of an appropriate  rehabilitation technique to repair any
specific sewer pipe, lateral,  or manhole is a  design decision that
                               3-5

-------
                          ControlMethods


 must be based on/existing  structural  conditioiy,  type of defects,
 site  constraints,   and  cost   considerations.     All   of  the
 rehabilitation methods described  in this section are applicable for
 RII control; the  "best" method for  any particular situation will
 depend upon the factors listed above.

 The effectiveness of sewer rehabilitation in reducing RII depends
 not only on the proper selection  and application of rehabilitation
 technique, but also,.and primarily,  on the overall rehabilitation
 program   approach.     As  discussed   later   in   this  chapter,
 rehabilitation programs which address  only isolated, large defects
 or only the public portion of the'sewer system may be ineffective
 in reducing RII.  Area-wide  rehabilitation,  including private as
 well  as  public .facilities,   is  generally  necessary  to  achieve
 significant RII reductions.

 Sewer rehabilitation methods range  from complete replacement- or
 construction of new facilities  to repairs of  individual defects
 that  can  be accomplished  in place.   In  general, the  costs for
 complete replacement are significant,  .especially when based on not
 only the cost of construction but also  the indirect costs resulting
 from construction.  These indirect costs have been a driving force
 for the  development of less  expensive,  less physically disruptive
 techniques for in-place; rehabilitation.  The following paragraphs
 •briefly review the  various techniques available  for sewer system
 rehabilitation to reduce  RII.   More detailed  descriptions and
 discussions of these methods are included" in Appendix D.

 Pipeline Rehabilitation

 Rehabilitation methods for  sewer pipelines include conventional and
 trenchless  replacement, grouting,  arid several  different lining
 techniques.  The  rehabilitation techniques listed  below are not
' all-inclusive; other techniques are currently being developed.

 The; focus  in  pipeline   rehabilitation  today   is  on  in-place
 techniques  such  as lining  and  trenchless  replacement.   These
 methods  minimize the impact on traffic,  other  utilities,  and
 surface improvements.  One  of the main shortcomings of the in-place
 techniques  is making a leak-free connection between the main and
 lateral without excavating.   Because  these connections are .often
 responsible for significant leakage, the effectiveness  of the seal
 at this joint may be  essential to RII reduction.        ,

 Many  of the techniques originally developed for sewer mains have
 been modified for lateral rehabilitation.  However, since laterals
 are typically  short (less than  75  feet) , may  have many-bends or
 offsets,   and   often  lack  useable   points   of  access,  their
 rehabilitation by in-place techniques  is generally less cost
                                 3-6

-------
                         Control Methods


effective  than  for mains.   Access to  laterals,  both for testing
and  rehabilitation,  is .also  an  institutional  problem,  primarily
because the  installation and maintenance of laterals are usually
the  legal  responsibilities of the property owner.

The following techniques are applicable for rehabilitation of sewer
pipelines:

Conventional Replacement.  Convemtional replacement can be used as
a method for rehabilitation of a complete manhole-to-manhole pipe
reach,  as  well  as  for  repair  of  individual  defects.    The
replacement of an entire reach using modern pipe materials provides
an essentially leak-free pipe. Excavation and  repair of isolated,
joint-to-joint pipe sections (point repairs) may often be required
in conjunction with other sewer rehabilitation techniques such as
grouting or  lining.   Lateral to  main connections•  also generally
require excavation for  restoration of a leak-free joint.

Trenchless  Replacement.   Tunneling  and moling  are methods  of
trenchless installation of new pipe.  Variations of some of these
techniques, such as that commonly referred to as "pipe bursting,"
can  be used  to  replace a  pipe along  its existing  alignment,
including  installation  of  a  larger diameter  pipe.    Flexible,
jointless pipe, such as'polyethylene, is an effective replacement
material for RII control.  Moling is  often attractive for laterals
to minimize surface  impacts and allow  the existing  lateral  to
remain in  service  until the  new  service is installed.   Also, new
construction  using these  techniques does  not  require  granular
backfill,  thereby  minimizing  the  potential  for  transfer  of
extraneous water into and along the sewer trench.

Grouting.  Grouting is used to seal joints, small holes, and radial
cracks in otherwise sound pipe.  Pipes in poor structural condition
or with numerous defective  lateral connections  generally cannot be
effectively repaired by grouting.   Grouting requires no excavation
where manhole entry is  available.  The long-term effectiveness of
grouting  depends  upon  the  type  of  grout used,  the  moisture
conditions  around the  pipe,  and proper  application  and quality
control.   Periodic  testing  after  the  initial  grouting may -be
required, not only to re-test the seal on the grouted joints, but
also  to correct  new leaks  in previously  ungrouted  joints  arid
cracks.

Slip-lining.  Slip-lining consists  of  inserting  a  new liner pipe
inside  an  existing  sewer  pipe  or  lateral.    The  liner  pipe,
typically high-density polyethylene,  can be fused into long, joint-
free  (and  therefore,   leak-free)  sections prior  to  insertion.
Grouting must be used to seal the annular space between the liner
and existing pipe at manholes, and may be used  to seal the annular
space for  the entire  length  of the pipe reach.  Some newer slip-
lining methods  utilize  short,  threaded  liner .pieces,  helically
                               3-7

-------
                           Control Methods

                ->''".          . '. \    '    -       '      ' .  ,  • '      *
  wound strips,  and expandable  liners to  facilitate  the insertion
 'process.  When a sewer main is slip-lined, each lateral connection
  must be excavated and  reconnected to the slip-lined pipe.  If the
  laterals are also slip-lined,  the lateral and main sewer liners can
  be fused together to make, a leak-free joint.

  Cured-ail-Place Lining.  Cured-in-place lining utilizes a thermal-
  setting,  resin-coated  flexible  fabric   liner.     The ;liner  is
  typically inserted in the pipe by inversion.   Once inserted inside
  the pipe,  the = liner  is  hardened by circulation of hot  water -or
  steam.  The  liner  conforms to the internal shape df the existing
  outer pipe and provides  a  smooth,  joint-free lining.  Although a
  remote  cutting device,is available to reconnect laterals to the
  lined pipe,  remote  cutting does; not provide any means of sealing
  these joints.  Therefore,  if the lateral connections are subject
  to leakage,  they must be excavated for repair as in slip-lining.
  Cured-in-place lining  requires less surface excavation than does
  conventional slip-lining, but is generally more  expensive.

  Manhole Rehabilitation

  Specific manhole rehabilitation techniques are designed to correct
  manhole frame/chimney defects as well as  to  eliminate RII entering
  through the  walls  and base.   The Milwaukee Metropolitan Sewerage
  District has pioneered the development and testing  of  several new.
  repair  techniques .as  part of its manhole  rehabilitation pilot
  program.  Rehabilitation methods for manholes include both interior
  and  exterior :techniques.   Interior  repairs are  generally less
  expensive  and time consuming> but are frequently less effective.

  Interior  Repair  Methods.    Interior repair methods,  although
  typically less effective for RIl control, remain attractive in many
  cases  due  t6 the  low  cost, and  ease  of  undertaking.   These
  techniques   make  possible  the  sealing  of  all  manhole "joints,
  including  the lower ones,  which are often subject  to  the  largest
  hydrostatic  forces.   Interior repair techniques  utilize:

       o    Elastomeric sealants.   .               /
,,  . ,.    o   ;Chemical grouts.     ,
       o    Internal boots.

  Exterior Repair Methods.  Exterior  repairs are often more  effective
  than  internal  repair methods, but require excavation.,  Since it is
  difficult  to gain access to1  all manhole joints, external  repairs
  generally  focus  on  the  joints  close  to  the  ground   surface,
  including  the manhole frame/chimney connection.  Exterior  repair
  methods          ;                             ,
  utilize: .               -                              • •
                                  3-8

-------
                          Control Methods


     o    Elastomeric sealants.
     o    Elastomeric sheeting,.
     o    Rubber sleeves.
     o    Two-piece frames.

 Foundation Drain Disconnection

 Methods   for  foundation  drain   disconnection  are  relatively
 straightforward  and depend  primarily on the configuration of the
 existing  connection.  The disconnection involves:

     o    Directing the  foundation  drainage  discharge to  a sump.

     o    Installation of  a  sump pump.

     o    Construction of  a discharge line  to  the outside of the
          building  or to a storm drain.

     o    Plugging the existing connection to the sanitary lateral.

 If the sump and/or  sump  pump already exists,  then the disconnection
 may  simply involve  redirecting the discharge  to  an appropriate
 point.  If the discharge is to  go to a storm sewer, connection to
 an  existing storm  lateral  or  construction  of a  separate storm
 lateral to connect  into the storm sewer may also be required.

 DESIGN STANDARDS AND CONSTRUCTION PRACTICES

 Effective design standards  and  construction practices can ensure
 minimization of the potential for RII in new  sewer mains, manholes,
 and  building laterals.    Such  standards  and practices  are  also
 important for existing  sewer system rehabilitation.  This section
 presents the key concepts for design and construction as they apply
 to RII  control.    More  detailed discussion  of these  issues are-
 presented in Appendix E.

Modifications  of  sewer  design standards  provide  a  means  of
 controlling  future  RII  in sewer systems by preventing potential
 development  of  defects and  minimizing  the  potential   for  the
migration  of extraneous  water  to  any sewer  defects which  may
 develop.  Such modifications include:

     o     Restricting the flow of water in granular backfill.

     o     Reduction  of utility trench backfill  interconnections.

     o     Control of migration  of  fine soil  or backfill material
          particles.

     o    Reduction  in the number of pipe joints.
                               3-9

-------
                           Control Methods


      o    Incorporation  of  pipe   system   flexibility  to  reduce
           settlement stresses.                                   .
                         .  ,'•.'-'•        '          .    .    5
.      o    Improved sealing of pipe  connections at manholes.

      o    Provision for tight,  but  flexible,  lateral  connections.

      o    Provisions for access for testing, inspection,  and  repair
           of laterals.        .

  Implementation  of effective sewer  construction practices ensures
  that design standards are properly addressed.  This is accomplished
  by  regular  construction  inspection  and  adequate performance
  testing,  both  for  public sewer mains and  manholes and private
  building  laterals.   Leakage tests (air pressure or water) must
  include stringent standards that assure an acceptable infiltration
  rate over the life  of  the sewer.  Tests that allow for  relatively
  large leaks from individual joints, even though the: over all leakage
  in  the pipe reach  does not appear  to be excessive, may not be
  acceptable,                      ,

  RII CONTROL PROGRAM APPROACHES

  Various  approaches have  been  taken to control  infiltration and
  inflow  into sanitary  sewer systems,  but few  have  specifically
  addressed RII alone.   Typical control programs have consisted of
  physical  rehabilitation of, portions of the existing sewer  system
  in  an  attempt to immediately  reduce  the, magnitude of  extraneous
  flows.   Rehabilitation projects may have  included  some private
  facilities  (building laterals or foundation drains),  but typically
  have only addressed the public portion of the system.  Long-term
  control programs  have  sometimes been initiated either  in lieu of
  or  in  conjunction with  immediate   large-scale rehabilitation
  efforts.                     .                  ;

  The most controversial aspect 6f control programs  is the  question
  of how to deal with problems on private property.   In  recent  years,
  many communities have realized that private property  sources often
  contribute  the  majority of extraneous flows to the sewer system.
  Therefore,  significant flow reductions  can  only  be achieved if
  sources  on  private  property are  also addressed  by the control
  program.    However,  rehabilitation  on private  property entails
  institutional,  financial, and construction problems that are often
  perceived to be prohibitive.                   ,-            .

/This section discusses various approaches to RII  control.  In. this
  context, approaches imply various options for developing  an overall
  control program,  as opposed to selecting specific rehabilitation
  techniques or design standards.  The latter  two  involve primarily
  engineering judgements.  Selection  of an appropriate  and effective
  overall  approach to  RII  control  involves  both  engineering and
                                3^10

-------
                          Control Methods


 institutional decisions.  Institutional and regulatory approaches
 discussed  later  in  this  chapter,  are   means  of  facilitating
 implementation of Rll control programs.

 Rehabilitation Program Approaches

 In  developing a  rehabilitation  program  that  will  effectively
 achieve reductions in RII peak flows,  it is essential to correctly
 identify the areas of the system and the types of entry points that
 must be corrected.   The  first step in any rehabilitation program
 should be  to eliminate  obvious  sources  of  direct inflow.   The
 reasons for this approach are:

     o    Direct inflow  sources can be detected easily  by smoke
          testing and are generally  cost effective to remove.

     o    Once inflow sources are removed, Rll can be  quantified
          from flow  monitoring (otherwise  it is  not possible  to
          separate the SWI and RII portions  of the rain induced I/I
          hydrograph),  and   those   areas   of the  system  which
          contribute   significant   RII  flows   can  be   readily
          identified.

 Once the areas  to be addressed  in the RII  control  program  are
 established,  a proper approach for identifying the particular sewer
 system   components  to   be   rehabilitated  must  be   developed.
 Approaches  to rehabilitation programs  may  differ  in the following
 basic ways:

     o    Addressing  entire areas of  the sewer system versus repair
        .  of individual defects only.

     o    Including both  the private and  public  portions of  the
          sewer system versus only the  public  portion.

Rehabilitation programs that have only  addressed individual  large
defects or  only problems  on public  property have often failed to
achieve projected  Rll reductions.   One of the reasons  is that
migration of RII  to unrepaired defects can occur when only  some RII
entry points are eliminated.  Furthermore, building lateral defects
and/or  foundation  drain  connections   on   private  property may
represent  a  significant  portion  of  the   RII  in  many  systems.
Therefore,  the  effectiveness  of  a  rehabilitation  program  in
reducing Rll  is dependent not only  on  the  repair techniques used
but also on the extent of the rehabilitation effort.
                               3-11

-------
                          Control Methods


Long-term RII  Control  Approaches

Although  a  rehabilitation program may be effective in immediately
reducing  RII levels in  a sewer system, it  will not necessarily
guarantee that those RII levels are maintained.   Long-term control
requires  that  RII be prevented  from increasing in unrehabilitated
areas  of .the  system,  as  well  as  from  entering from  newly
constructed sewers.   Long-term RII  control can  be implemented
through:           '..•'.       ,                            :

     o    Effective preventive maintenance  programs.            .

  ,_   o    Implementation   of  appropriate  design  standards   and
          construction  practices.;

An effective preventive maintenance program  should include:

     o    Periodic  flow!monitoring in the system  to identify areas
          with  increases  in RII  levels.

     o    A  routine program-of cleaning  and root  removal.

     o    A  cyclic  program of  testing and inspection  of the sewers
          throughout the  system  to  identify  the  heed for repairs
          replacement.                           ;

In systems  where defective building laterals or  foundation drains
represent a significant portion  of the RII,  the program should also
include private facilities.

COST EVALUATION                          ,          '

Costs  for  sewer  system  rehabilitation to  reduce  RII  must  be
compared  to. those  for transport and treatment  of  RII  flows  to
evaluate  the cost effectiveness  of  various RII reduction options.
The  "traditional"  approach to  performing  I/I cost-effectiveness
analyses,  as  described  in  the EPA Handbook  for  Sewer  System
Evaluation and  Rehabi1itation f  is based upon determining the flow
contribution and correction cost for each individual  I/I source in
the sewer system identified through field inspection and testing.
The I/I sources are then  ranked  in order of least cost per unit ;of
I/I flow removed.   The  cumulative flow reduction  and corresponding
correction  cost for successive  elimination of the individual I/I
sources in  order of least unit  cost ranking  are calculated.   The
cumulative correction  cost is then  plotted against cumulative I/I
removed,  along with  the  corresponding   (decreasing)  cost  for
transport and  treatment  (see  Figure 3-1).    The  low  point  of the
total  cost   curve   represents  the  cost-effective level  of  I/I
reduction for  the   system.   Those   individual sources which  rank
above this  level are considered  to  be cost effective to correct.
                               3-12

-------
CO
O
o
i
09
U)
                                    TOTAL COST
TRANSPORT &
TREATMENT COST
          MINIMUM TOTAL
                 COST
         REHABILITATION
                 COST
                                 COST EFFECTIVE I/I REMOVAL
                        I/I REMOVED
                       FIGURE 3-1

    TRADITIONAL COST-EFFECTIVENESS CURVE

-------
                         Control Methods


 As  noted previously,  in sewer  systems where  the  primary  entry
 points  of RII are defects  in  sewer  pipes and laterals and  where
 such defects  are  generally  widespread,  migration  of   RII  to
 unrepaired, defects  may occur when only some points of RII  entry
 have been eliminated.  Additional defects may become active as the
 water seeks new entry-points to the sewers.   This  migration factor
 has  resulted  in the  failure of the traditional  cost-effectiveness
 analysis  approach to accurately predict the amount  of  extraneous
 flow reduction achievable through implementation of many correction
 programs^originally  calculated to be cost effective.

 For  this  study,  a cost evaluation was conducted to analyze the
 relative cost effectiveness  of different rehabilitation approaches.
 Cost-effectivenss analyses  were conducted  for different  "model"
 sewer systems, which were defined in  terms of their age and general
 physical  condition, magnitude and distribution of  RII,  and density
 of building laterals.  The models were developed to  evaluate sewer
 systems where the primary entry points of RII are  defects  in sewer
 mains and laterals, as opposed to systems in which the  primary RII
 entry is through manhole framed/chimney defects,  foundation drains,
 or other  entry points not generally  classified  as pipe  defects.

 The  purpose of the model system cost evaluation was to identify how
 the  cost-effectiveness  of  RII  correction  was  affected  by the
 characteristics   of   the  sewer  system  and  by  the  type  of
 rehabilitation  approach selected.   The rehabilitation  approaches
,evaluated included:,                    .

     o    Isolated repair  (spot  repair of  individual  defects or
          specific pipe  reaches).
                         /                 .      "       •
     o.   Rehabilitation of  public  sewer mains only.

     o  -•  Rehabilitation of sewer mains, plus lower  laterals (the
          portion within the public  right-of-way). .

     o    Rehabilitation of  sewer   mains   plus  entire,  building
          laterals.

 The  cost  analysis was designed to overcome the;major limitation of
 the   traditional   cost-effectiveness   methodology,   that  of
 overestimating rehabilitation effectiveness  by ignoring the effects
 of flow migration.   Two  key'assumptions were made:

     o    Rehabilitation was  assumed to be conducted  throughout
          contiguous  areas within sewer subsystems, rather than only
          addressing  individual RII  entry points.   To address a
          significant  portion (at least 50  percent) of* the RII in
  ' .       a  subsystem, an area that included at least 30 percent or
          more of  the "worst" sewers in the subsystem would require
          rehabilitation.    .The  RII   distribution  within  any
                               3-13

-------
                          Control Methods


          particular  subsystem  could be assumed to fall  within  a
          generalized envelope, as shown in Figure 3-2.

     o    The assumed Rll reductions  (removable percentages of RID
          assigned to various rehabilitation approaches were based
          on   recognized  limitations   of  "incomplete"   system
          rehabilitation due to flow migration effects.  Thus, large
          reductions  (greater than  50  percent)  were  considered
          achievable  only  if the rehabilitation program  included
          both the mains and laterals.'

 A detailed description of the assumptions  and  procedures  used for
 the  model system cost evaluation is  presented  in Appendix F.

 The  general results of the model system cost evaluation indicated
 that RII  correction would probably not generally be cost effective
 in a "typical" old sewer system (sewers  in generally poor condition
 and  defects widespread)  because of  the high cost  and need  for
 extensive rehabilitation.   However,  under  certain  conditions  (for
 example,  a newer system with very high RII flows but  low  lateral
 density), RII could  be cost  effective if the  mains  and  entire
 laterals  were  rehabilitated.

 However,  since the cost, evaluation was applied  to fictitious sewer
 systems and involved a number of assumptions regarding sewer system
 conditions  and existing transport and treatment capacities, it was
 not  intended to develop costs for RII control that could be applied
 to all sewer systems or draw definitive conclusions  about the cost-
 effectiveness  of  RII  correction  in any specific  sewer  system.  As
 noted previously, the types of RII correction programs addressed
 in the cost analysis are  primarily aimed at correcting sewer system
 defects   (RII  entry points)  using  commonly applied  techniques.
 Therefore,  the cost evaluation did not  consider  the potential for
 RII  reduction  through improved design.and  construction standards,
 new  or  less  costly techniques,  or  through as  yet undiscovered
 methods that might be developed  to intercept or  divert water  away
 from the  pathways through which  it reaches' the sewers.

 The cost effectiveness of RII  correction is highly dependent on the
 capacity of existing downstream transport and treatment facilities
 and on the costs to provide any additionally required transport and
 treatment  facilities.    In  a system  where pipeline construction
might be  required  in congested areas  or  under adverse  soil or
groundwater conditions,  transport costs would be  higher  and RII
correction could  be more cost effective.   Similarly, if treatment
plant site constraints make overall plant expansion  or construction
of flow equalization facilities prohibitively expensive, the cost
                               3-14

-------
  100 r
LU
             20       40       60       80



            PERCENT OF  SEWERS IN SUBSYSTEM
100
                     FIGURE 3-2




     HYPOTHETICAL Rll DISTRIBUTION

-------
                         Control Methods


effectiveness of RII correction would also be higher.  In the EBMUD
system, for example, the high costs to transport,and treat the peak
RII  flows have made RII correction cost  effective  in about 50
percent of the system.  This is despite the fact that EBMUD is an
old system with a relatively high lateral density.

An  important point  needs  to  made  about  old sewer  systems  with
respect to  assessing  the  cost effectiveness  of  rehabilitation.
Many   old  systems   have   experienced  significant  structural
deterioration.       Good   infrastructure   management   dictates
rehabilitation,  if  only  for the  purpose  of  maintaining  the
structural integrity and proper functioning of the system.  If it
is recognized that  life-cycle  replacement  and rehabilitation are
integral  parts  of  sewer  system  management,   then  the  cost
effectiveness of system rehabilitation can  be assessed in terms of
the benefits of both structural maintenance and RII reduction.  In
these cases, sewer system rehabilitation may be cost effective for
reasons other than  for RII reduction alone.

INSTITUTIONAL AND REGULATORY APPROACHES

Institutional  and   regulatory  approaches  can  help  facilitate
implementation of rehabilitation programs and long-term RII control
programs.   These types of measures are particularly suited for RII
control on private property.

Rehabilitation Programs

Institutional  and   regulatory  measures  that  can  be  used  in
conjunction with rehabilitation programs include:

     o    Public agency ownership of  laterals and/or responsibility
          for lateral construction.

     o    Financing programs (for public and/or private facilities).

     o    Enforcement (for private property rehabilitation).

     o    Public information programs.

Rehabilitation of both the public and private portions of a sewer
system as part  of  a single, integrated construction project has
distinct advantages in terms of lower cost,  better quality control,
and minimizing disruption to the community.  One option available
to an  agency that  is contemplating rehabilitation of  sewers and
laterals  is taking over temporary ownership of the laterals during
construction  and  assuming  responsibility  for  maintenance  of
laterals  for   a   ori'e   or  two  year  warranty  period  after
rehabilitation.  These steps would allow the agency to perform any
needed testing and rehabilitation without repeated  contact with the
property' owner.     After   the  agreed upon  time  period,   the
                               3-15

-------
                      ,   Control Methods

                           1            •           '        '
responsibility  for  the- lateral would automatically revert, to.the
property  owner.   The  length of the  time  period selected should
allow for completion of all  necessary work and include a warranty
period to ensure that  the work has been properly undertaken.

Rehabilitation programs are expensive and may present considerable
strain on the financial resources of both the public agency and the
individual property owners.  Financing options  for public agencies
include pay-as-you-go  financing  from general sewer use revenues,
revenue  bonds  (repaid out  of user  fees),, assessment  district
financing/and combinations thereof.  Financing assistance may also
be  offered to  individual property  owners  in  the form  of low-
interest  loans;  local assessment district  financing;  or reduced
costs  through agency  assistance in  design of  private  property
improvements,  preparation  of  bid  documents,  and construction
inspection.

Strict enforcement of requirements for private property repairs is
another option.  Municipalities with  foundation drain connections
to  the sanitary  sewer system have,  in some  cases,  instituted
inspection programs  with mandatory removal  of connected drains.
Local ordinances have^been passed for not disconnecting the drains,
with  penalties   ranging  from  warnings  to   fines   to  forcejd
disconnection.    Similar  regulatory  methods  can  be  used  for
enforcing building lateral rehabilitation.  Such enforcement would
require an ordinance that requires a building owner to maintain a:
properly operating lateral that does not  contribute  excessive non-
wastewater flows to the sewer system, or require that the lateral
be capable qf. passing  a standard leakage test.

The success'of  an overall  RII control program may greatly depend
upon how well-informed the general public is regarding the need and
requirements  for the  program.   An  effective public  education
program can potentially elicit substantial voluntary participation
from individual  property  owners.   For example,  in  Ames,  Iowa,  a
public  information  program,  combined  with  limited  financial.
assistance, was  successful  in implementing  necessary  foundation
drain disconnections on a voluntary basis.

Long—term Programs            ,

Since new  sewer facilities are often constructed  by  the /private
sector rather than a public agency> regulations provide a means of
enforcing desired design  standards and construction practices to
minimize future RII.  Preventive maintenance programs, particularly
for private facilities, can be facilitated through regulations with
requirements for testing,  inspection, and  repair of sewer system
components found to be contributing RII.
                               3-16

-------
                           Control Methods


                                SiSi?^ P??"la.rity in *any Parts
                   ent an lal^i^^^ViSIC^.P"**^

                   ^^^^
cycle,  integrating 4e testing re^fremen/to^  refsonai*e time
minimizes both  the administrftivf^urden  on Iht S&le °f Pr°Perty
financial im                                       agenc  and
                          nsrvurden on   h
  financial impact on the property owner.            agency and  the
                                  ac
 may be needed to effectively cleaS    lLS?> and at the  st«cture
 Consequently, some communities re™'i~S£eCt'  7 test each lateral.
 In some localities wherTa curb ci^™ fleanouts at both locations.
 will not maintain the lower SSrtionS?^d°fS.nOt exist' the a9ency
 installs one.  . in ^ otheT muSicioa?!?! £** t****?1 unless  the «««
 inspection is  required   S5SSSX -t   •  t^  iateral testing or
 inspection procesHf they SSSSt b^ f7o,S StalTled as  part of ^
 country  where  cleanouts T outSde  of  Sf *  JPtF** areas of the
 practical because of weather  c««rfr lateral
 or inspection.                 ay be necessary to complete testing
 EXAMPLE RII CONTROL PROGRAM - EBMDD
                      mt^^iS1!?^ Pr°.gram' that °f tte


2 ^ystemTut^^^^^

c^                   S  the
                  y^
the field i-tffa^1^^

-------
                          Control Methods   ,


 the SSESs.  While the fundamental concept of cost effectiveness was
 consistent  with basic  EPA  requirements,  a  very  detailed  and
 rigorous  approach  was  developed to  quantify  and  identify  I/I
• components and analyze the costs for I/I correction.

 Field Investigations

 The EBMUD sewer system consists of about 1,500  miles  of sewer
 mains.  The initial field effort involved focussing the study on
 those areas with the most significant I/I flows and therefore the
 greatest  potential for  cost-effective  I/I  correction.   This  was
 accomplished through a "gross" monitoring program,  in which over
 300 flow monitors, each with a tributary area containing an average
 of about  20,000  feet of sewer mains,  were  used to record sewer"
 flows over a two-month period during the rainy  season.   For each
 monitor, storm flow data was  "decomposed" into base flow and rain-
 induced I/I components.  A  method was developed to quantify  the
 rain-induced I/I as a percentage of rainfall volume and describe
 the shape of the  hydrograph with mathematical  parameters.  These
 parameters were then used to develop a  "projected" hydrograph for
 each area of the sewer system for an established five-year design
 storm.  This procedure enabled comparison of the rain-induced I/I
 flows from all areas of the  sewer system on the basis  of a common
 rainfall event.

 Based on  the  results of the gross monitoring program,  specific
 areas (subbasins) of the sewer system with the  greatest potential
 for cost-effective  I/I reduction  were identified for further field
 work.  The field work included smoke testing, dye flooding, manhole
 inspection,  and  flow isolation.    Based on the  results  of  flow
 isolation,  specific  sewer   reaches  within  each  subbasin  were
 identified for TV inspection. As  described in Chapter 2, the smoke
 testing results indicated that there were very  few  direct inflow
 sources in the system, and  that  laterals were a major potential
 contributor of RII.  other special field studies on laterals  (TV
 inspection,   leakage  testing,   rainfall simulation,   and  flow
 measurement  during  rainfall)  were conducted  to  verify  this
 hypothesis.  TV inspection of sewer mains indicated that the sewers
 in the  system  were  in  generally very poor structural condition,
 with numerous cracks,  offset joints,  and other  defects that serve
 as entry points for Rli;

 Cost-Effectiveness  Analysis

 The data  obtained from  flow monitoring and  field testing  and
 inspection were used to conduct a detailed analysis of the qost-
 fffectxveness  of sewer  system  rehabilitation  to  reduce  I/I.
 Although  -the analysis  addressed  all components of I/I (SWI,  Rli,
 and GWI) ,  the primary emphasis was on reduction of peak flows by
 controlling Rli entry into the system.

-------
                          Control Methods


 Rehabilitation Program
                                                    *
 second  year of  iroiementi?f««    « Program  is  currently in its
                                                 °-
pa«        ,.








                 e<"**ril  f
maintenance reasons   ra?Lt £^e
-------
                           Control  Methods
Long-term RII control

                                                   the EBMUD SSES
            odeo                              -   e EBMDD SSES
SUMMARY
                 and «„        .

                                                   rehabilitation
                                                        .in-
        sPe=if lcally
   0
                  to apply to later     '     3re ™°re costly and

-------
                          Control Methods
                 can be effective iti T reducih

                   ae;irMstisdam?nsiBar2dec?sttruction
          rehabilitated sewers  by          ^"  in°  new  or
                                                  .   «»~«*
          through I/I oorreotionecauet faii t?"n «*i«»
          migration of RII to unrepaired LleoU.   a°°ount for *»»
                           nf
         transport and treatment f aoiime's  aS th»eS ,°l .existin9
         to construct additional capacity?'        "lative costs
                                                    be necessary
         enforcement, f inancina  a  ™HI "  ?rder to  Pr°vida  for
         property  rehaMuiation.  P      «*°rfflation for private
RECOMMENDATIONS
                                                        «=

Physical conditios
                                           ef ec^f

-------
                     Control Methods


 o    The following considerations should be incorporated into
  .....the development of sewer system  rehabilitation  programs
     and .  evaluation   of   the   .cost    effectiveness   of
     rehabilitation:

         Addressing entire areas of the sewer system  versus
         repair  of individual defects only.

     -   Including both the public and private portions Of the
         sewer system versus only the public portion.

 o    Long-term   RII   control  should   be   ensured  through
     implementation of  an  effective  preventive maintenance
     program that includes:

     -   Periodic  flow  monitoring in the system to  identify
         areas with increases in RII levels.

     -   A routine program of cleaning and root removal.

     -   A 'cyclic  program of testing and  inspection of  the
         sewers throughout the system to identify the  need for
         repairs and replacement.

o    Sewer design standards should be modified to include  the
     following considerations:

         Restricting the flow of water in granular backfill.

         Reduction    of    utility    trench    backfill
         interconnections.

         Control  of  migration   of . fine   soil  or.  backfill
         material particles.

     -    Reduction in the number of pipe joints.

     -    Incorporation of  pipe  system flexibility  to reduce
         settlement stresses.

     -    Improved sealing of pipe connections at manholes.

     -    Provision   for   tight,   but   flexible,   lateral
         connections.

     -    Provision for  access  for testing,  inspection, and
         repair of laterals.

D    Effective sewer construction practices  should be followed
     to ensure that design  standards are met by:
                         3-22

-------
                Cont ro 1 • Methods"
- "  Regular construction inspection.

-    Adequate performance testing for public sewer mains
     as well as private laterals.

The institutional and regulatory framework governing the
construction  and  maintenance  of  house  laterals  (the
connection between the house or building and the collector
sewer in the street or other public right-of-way)  should
be re-examined.  Possible options include:

     Shifting  responsibility  for   construction  and/or
     maintenance of house laterals from the home owners to
     the municipality.
                     \ ,                              • .
-    Municipal  programs  to  help  home owners  pay  for
     maintenance and repairs of house laterals.

-    State  or  municipal  ordinances,  with  appropriate
     enforcement provisions, governing inspection, testing
     and repair of house  laterals.

-    Public education programs to inform citizens  of the
     importance of  excluding  extraneous  flows  from the
     municipal sanitary sewerage systems.

The development of new,  improved, and potentially less
costly sewer rehabilitation techniques, particularly for
laterals, should be encouraged.

The collection and publication of data  documenting the
effectiveness  of different  rehabilitation methods  and
approaches to controlling RII should be encouraged.
                     3-23

-------
                                 APPENDIX A
                          LIST OF ABBREVIATIONS
ABS         Acrylonitrile butadiene styrene pipe
AC          Asbestos cement pipe
ADWF       Average dry weather flow

BWF        Base wastewater flow  -
BOD        Biochemical oxygen demand

C-E Ratio    Cost-effectiveness ratio
CMP        Corrugated metal pipe
CSO         Combined sewer overflow

EBMUD  .   East Bay Municipal Utility District
EPA         U.S. Environmental Protection Agency

gpcd         Gallons per capita per day
gpd          Gallons per day
gpm         Gallons per minute
GWI         Groundwater infiltration

I/I           Infiltration/inflow

mgd         Million gallons per day
rag/I         Milligrams per liter
MMSD       Milwaukee Metropolitan Sewerage District

NEORSD    Northeast Ohio Regional Sewer District
NPDES      National PoUutant Discharge Elimination System

O&M        Operation and Maintenance

PVC         Polyvinyl chloride pipe
PWWF       Peak wet weather flow
RDI/I
RII
RII/I
Rainfall dependent infiltration/inflow (same as RII/I)
Rainfall induced infiltration
Rainfall induced infiltration/inflow

-------
SSES        Sewer system evaluation survey
SWI         Storm water inflow

TSS         Total suspended solids

VCP         Vitrified clay pipe

WWTP      Wastewater treatment plant

-------
                                  APPENDIX B

                                 REFERENCES
CHAPTER 2

Lee, David M., arid Molzahn, Robert E., "Foundation Drain Inflow Characterization in a
Rehabilitated Sanitary Sewer System."
Undated,

United States Environmental Protection Agency. "Handbook for Sewer System Evaluation
and Rehabilitation." MCD-19. December 1975.

East Bay Municipal Utility District, California
    '           •   ',      '   "~v-    ' . ,   .              •         .          ...'"--
CDM/Jordan/Montgomery. "East Bay Infiltration/Mlow Study, Berkeley Sewer System
Evaluation Survey Report." November 1985.

CDM/Jordan/Montgomery, CH2M HnJL/WLA,  The Eastshore Consultants.  "East Bay
Infiltration/Inflow Study,  Manual for  Cost-Effectiveness Analysis."  July 1981, revised
December 1985.                                                            ,

CH2M-HTJLL. "East Bay Infiltration/Inflow Study, Oakland North Sewer System Evaluation
Survey." January 1986.                                     ;          •,-..'"

East Bay Infiltration/Inflow Correction Program. "Final Environmental Impact Report."
April 1986...       .

Geotechnical Consultants, Inc. "Ground Water Infiltration Into Sanitary Sewers, Cities of
Albany, Berkeley, Emeryville, and South Oakland,California."April 1982.

';	. "Supplemental Geotechnical Investigation, East Bay Infiltration/Inflow Study, Cities of
Albany, Berkeley, Emeryville, and Oakland, California." April 1984.

The Eastshore Consultants  (Black & Veatch,  Brown  «&  Caldwell, Waste  & Water
International). "Building Lateral Testing and Rehabilitation Pilot Project."  East Bay I/I
Study. October 1984.                       .

Springfield, Oregon

Black, Edward. "City of Springfield, Oregon, Infiltration/Inflow Analysis." July 1976.
                                       B-l

-------
                                   References
CH2M-HH1. "City of Springfield Sewer System Evaluation Survey, Phase I Report." July
1978.

	. "Springfield, Oregon, Sewer System Evaluation Survey Summary Report." December
1980.

Rehabco Pipe Services, Inc. " I/I Control Plan For The City of Springfield." July 1986.

Milwaukee Metropolitan Sewerage District, Wisconsin

Milwaukee  Pollution  Control  Abatement  Program,  Program  Management  Office
(CH2M-Hill/Donohue & Associates, Inc./Howard Needles
Tammen & Bergendoff/Graef, Anhalt, Schloemer & Associates, Inc./ Polytech Inc./J.C
Zimmerman Engineering Corp./Klug & Smith  Co.) "Milwaukee Metropolitan Sewerage
District, Sewer System Evaluation Survey, Executive Summary." August 1981.

	. "Milwaukee  Metropolitan  Sewerage  District,  Sewer System Evaluation Survey,
General Report, Volume I." August 1981.

	. "Milwaukee Metropolitan Sewerage District, Sewer System Evaluation Survey, General
Report, Volume H" August 1981.

	. "Milwaukee Metropolitan Sewerage District, Private Property Infiltration/Inflow Pilot
Project." August 1981.

	. "Milwaukee Metropolitan Sewerage District, Manhole Rehabilitation Pilot Project."
April 1982.

Milwaukee Metropolitan Sewerage District, Operations  Division. "System Monitoring
Report." August 1986.

	. "System Monitoring Annual Report, Appendix." August 1986.

Northeast Ohio Regional Sewer District, Ohio
                                                        t            j  '',•,•
CH2M-HELL.  "Easterly Separate Sewer Segment Wastewater Facilities Plan, Volume 2
Infiltration and Inflow Analysis." 1978.

Dalton, Dalton,  Newport. "Northeast  Ohio Regional Sewer District, Easterly Separate
Sewer Area, Sewer System Evaluation Survey Summary Report." October 1983.
                                      B-2

-------
                                   References
    . 'The Northeast Ohio Regional Sewer District Heights/Hilltop Interceptor Sewer
 System Update, Summary Report, SSES ERRATA," November 1986.

   .'. "The Northeast Ohio Regional Sewer District  Heights/Hilltop Interceptor Sewer
 System Update Summary Report." November 1986.

 Dalton, Dalton, Newport/Frank A. Thomas & Associates, Inc. "Northeast Ohio Regional
 Sewer District, Easterly  Separate Sewer Area,  Sewer System Evaluation Appendices,
 Volume 1." June 1983^
   _. "Northeast Ohio Regional Sewer District, Easterly Separate Sewer Area, Sewer System
 Evaluation Appendices, Volume 3." June 1983.

 Dalton, Dalton, Newport/Havens and  Emerson, Inc.  "Northeast Ohio  Regional Sewer;
 District, Easterly Separate Sewer Area Advanced Facilities Planning Report." September
' 1983.  '   '      •    ' .   '   '-;-•"   " •  •" •   .../';-'   •'-•.'•  -."'  ; ;' .  ..,' '.

 __. "Northeast Ohio Regional Sewer District, Easterly Separate Sewer Area, Supplemental
 Facilities Planning Report." September 1983.

 Dalton, Dalton, Newport/Snell Environmental Group. "Northeast Ohio  Regional Sewer
 District, Easterly  Separate Sewer  Area, City of Cleveland  Heights  Sewer System
 Evaluation." June 1983.

 	. "Northeast Ohio Regional Sewer District,  Easterly Separate Sewer Area, City of
 Shaker Heights Sewer System Evaluation." June  1983.

 	_.   "Northeast Ohio Regional Sewer District, Easterly Separate Sewer Area, City of
 University Heights Sewer System Evaluation."  June 1983.

 John David Jones & Associates, Inc. "Northeast Ohio Regional Sewer District, Southwest
 Interceptor Area Sewer System Evaluation Survey Summary Report." February 1984.

 John David Jones & Associates, Inc./Howard Needles Tarnmen & Bergendoff. "Northeast
 Ohio Regional Sewer District, Southwest Interceptor Area Sewer System Evaluation Survey
 Final  Report For Columbia Township, Olmsted Falls, Township, Strongsville." February
 1984.      ''.'••                                                   .
                                       B-3

-------
                                    References
_ . "Northeast Ohio Regional Sewer District, Southwest Interceptor Area Sewer System
Evaluation Survey Appendices, Volume I, II, and
    Strongsvffle." February 1984.
Baton Rouge, Louisiana

Albert Switzer & Associates, Inc; and Naylor Industries, Inc. "Sewer System Evaluation
Survey,  Parish  of East Baton  Rouge, Louisiana, Consolidated Sewer District,  North
System." July 1979.
                , A  '  ^^^              '                    '        ,          '
_ .  "Sewer System  Evaluation Survey, Parish of  East  Baton  Rouge,  Louisiana,
Consolidated Sewer District, South System, Volume I." July 1979.

Barnard & Thomas  Engineering, Inc. "Minor  Rehabilitation During  Sewer  System
Evaluation Survey, Central Treatment Service Area, East Baton Rouge Parish, Louisiana,
Final Report." September 1986.

Camp Dresser & McKee  Inc. "Population and Flow Projection, City  of Baton Rouge,
Parish of East Baton Rouge, Wastewater System Improvement Program." November 1987.

_ . "Inventory of Existing Facilities, City of Baton Rouge, Parish of East Baton Rouge,
Wastewater System Improvement Program."
December 1987.

Springfield, Missouri

Consoer, Townsend and Associates. "City of Springfield, Missouri, Southwest Wastewater
Collection and Treatment System  Infiltration/Inflow Analysis." June 1974.

City of Springfield, Missouri. "Sewer System Evaluation  Survey."  1980.

North and South Shenango Joint Municipal Authority, Pennsylvania

L. Robert Kimball & Associates. "Sewerage System Evaluation Report for North & South
Shenango  Joint Municipal Authority." 1984.
                                                                                i
   _. "North & South Shenango Joint  Municipal  Authority Flow Monitoring Report."
October 1987.

Ames, Iowa
                                       B-4

-------
                                   References
Rieke Carroll Muller Associates, Inc. "Report on Infiltration/Inflow Analysis, City of Ames,
Iowa." December 1975.

	. "Sewer Systeation Survey Report For City of Ames, Iowa," May 1979.
 __. "Appendix to Sewer System Evaluation Survey Report For City of Ames, Iowa." May
1979.                             >

Coos Bay, Oregon                                                        ,

Brown & Caldwell  "Citos Bay, Wastewater Collection  and Treatment Facilities Plan
Supplement." February 1987.

H.G.E., Inc. "Cops Bay Wastewater System Facilities Plan, Draft." 1985.

Tulsa, Oklahoma

Max Holloway Engineering Co.,  Brutpn Knowles &  Love,  Inc.,  Black <& Veatch.
"Wastewater      Facilities Plan For Southslope Drainage
Basin City of Tulsa,  Oklahoma, Volume III, Infiltration/Inflow Analysis." August 1987.

CH2M-Hill,s  Mausur-Daubert-Williams,  Kellog, Gutierrez-Smouse-Wilmut.  "Executive
Summary Northside  201 Facilities Plan, City of Tulsa, Oklahoma." July 1982.

  .'. "Northside 201  Facilities Plan, City of Tulsa, Oklahoma." July 1982.

Gutierrez-Smouse-Wilmut, Mansur-Daubert-Williams,  Kellog,  CH2M-HH1.  "Northside
Infiltration and Inflow Analysis, City of Tulsa, Oklahoma," July 1982.

Gutierrez-Smouse-Wilmut, CH2M-Hffl  Inc. "Sewer System Evaluation Survey For The
Northside Facilities Planning Area, Phase I, City of Tulsa, Oklahoma." October 1986.

	. "Sewer System  Evaluation Surside Facilities Planning Area, Phase II, City of Tulsa,
Oklahoma." October 1986.

CHAPTERS

American Public works Association. '^Control of Infiltration and Inflow into Sewer Systems."
December  1970.
                                      B-5

-------
                                    References
 American Society of Civil Engineers and Water Pollution Control Association. "Existing
 Sewer Evaluation & Rehabilitation." 1983.

 Anon. "Sealing of Sewers in Unstable Soils." American City & County, Vol. 96, No. 3.
 March 1981.

 Anon. "Polyethylene Pipe Tackles Difficult Sewer Repair Job." Water & Sewage Works,
 Vol. 123, No. 2. February 1976.

 Anon. "A Sewer System Analysis as Performed for the City of Bellaire, Texas." Texas
 Innovation Group, College Station. March 1979.

 Anon. "Ground Water Infiltration and Internal Sealing of Sanitary Sewers, Montgomery."
 Montgomery County Sanitary Dept, Dayton, Ohio. June 1972.

 Backman, Hans. "Infiltration/Inflow in Separate Sewer Systems." Chalmers University of
 Technology, Dept. of Sanitary Engineering,
 Goteborg, Sweden. 1985.

 Brown and Caldwell. "Utility Infrastructure, Rehabilitation." U.S. Department of Housing
 and Urban Development. November 1984.

 Carter, William C. "The  Development and Implementation of a Progressive Rehabilitation
 Program for the Removal of Private Sector Infiltration/Inflow."  Water Pollution Control
 Federation, 60th Annual Conference, Philadelphia, Pennsylvania October 8, 1987.

 Carter, William C; Nogaj, Richard J.; Hollenbeck, Alan J. "Cost Effectiveness and Sewer
 Rehabilitation."  Public Works, Vol. 117, No. 10. October 1986.

 CDM/Jordan/Montgomery, "East Bay Infiltration/Inflow Study, Policy Considerations for
 Lateral Testing and Rehabilitation for the City of Oakland."  July 1987.

 Cox, G.C. "Making Use of the Hole - New Techniques for Sewer Renovation." Restoration
 of Sewerage Systems,  Proceedings of  an International Conference  organized  by the
 Institution of Civil Engineers, held in London on 22-24 June 1981. Thomas Telford Ltd,
London. 1982.

Driver, F.T., and Olson, M.R. "Demonstration of Sewer Relining by the Insituform Process,
Northbrook, IL." August 1983.
                                       B-6

-------
                                   References
Emery,  J.A.  "New Techniques in Non-Many  Entry Sewer Renovation." International
Conference  on the   Planning,  Construction,  Maintenance &  Operation of Sewerage
Systems, Reading, England, 12-14; September, 1984. ,

Evans, Jack, and Spence, Marlene. "Evolution of Jointing Vitrified Clay Pipe." Proceedings
of the International  Conference on  Advances in Underground Pipeline Engineering,
Madison, WJ,,August 27-29, 1985.          .                      .

Fiddes,  D. "Sewerage Rehabilitation  Strategy for the United Kingdom." International
Conference  on the   Planning,  Construction,  Maintenance &  Operation of Sewerage
Systems, Reading, England, 12-14 September, 1984.           .

Foster, William. S., and Sullivan,  Richard H. "Sewer Infiltration  and Inflow Product and
Equipment Guide." American Public Works
Association, Chicago, HI.

Gill, S.M. "Developments in Grouting Technology for Sewer Renovation." International
Conference  on the   Planning,  Construction,  Maintenance &  Operation of Sewerage
Systems, Reading, England, 12-14 September, 1984.

Goodman, W.J.P., and Hope, P.S. "Inspection and Renovation of Sewers: State of the Art
in Sydney."  International Conference on the Planning, Construction, Maintenance  &
Operation of Sewerage Systems, Reading, England, 12-14 September, 1984.

Hollenbeck, Alan J.   "Designing for Removal of Sanitary Sewer  Cross Connections."
Water/Engineering and Management,  Vol. 131, No. 4. April 1984.

Holmes,  Kenneth T.; Black, Edward; and  Brown, Dan E. "Infiltration/Inflow Analysis:
Finding  the Source." American City & County, Vol. 97, No. 2 February 1982.

Jacques, W.B. "Stopping  Water with Chemical Grout" Civil Engineering, Vol. 51, No. 12.
December 1981.

Jones, M.A.  "Small  Diameter  Pipe  Maintenance  and Renovation." International
Conference  on the  Planning,  Construction, Maintenance &  Operation of Sewerage
Systems, Reading, England 12-14  September, 1984.

Jones, Maurice B. "Sewer Renovation." Tunnels and Tunnelling, Vol. 19, No. 10. October
1987.
                                      B-7

-------
                                    References


 Mayer, John K.; Macdonald, Frank W.; and Steimle, Stephen E.  "Sewer Bedding and
 Infiltration, Gulf Coast Area." Tulane University,
 New Orleans, La. May 1972.

 Morgan, Thomas R. "Private Source Inflow Removal." Journal of the New England Water
 Pollution Control Association, Vol. 19, No. 2.
 November 1985.

 Munro, L, and Holmes, M.J. "City's Experience of Thin-Shell Sewer Lining." Restoration
 of Sewerage Systems, Proceedings of an                    .
 International Conference organized by the Institution of Civil Engineers, held in London
 on 22-24 June 1981. Thomas Telford Ltd, London. 1982.

 Murray,  J.B. "Infiltration Rates for Separate Sewage  Collection  Systems."  Gutteridge
 Haskins  & Davey, Melbourne, Aust., Water Science and Technology, Vol. 19, No. 3-4,
 1987, Water Pollution Research and Control, Part 2, Proceedings of the Thirteenth Biennial
 Conference of the International Association of Water Pollution Research and Control, Rio
 de Janeiro, Brazil, August 17-22, 1986.

 Olson, M.R. "Insituform and Other Sewer Rehabilitation Techniques." November 1985.

 Paulson, Richard L; Wylie, F. Samuel; Anderson, David S.; and Miles, Frank. "Attacking
 Private Infiltrationflnflow Sources." Public Works, Vol. 115, No. 2. February 1984.

 Pefl, Kelly  M., and Diehl, Douglas  S. "Reducing Sewer  Infiltration/Inflow."  Civil
 Engineering,  Vol, 45, No. 12. December 1979.

 Penner, I.L. "Grouting Provides Economical and Effective Maintenance in Kansas." Water
 & Sewage Works, Vol. 125, No. 3.  March 1978.

 Peters, D.C.  "Social Costs for Sewer Rehabilitation.' International Conference on the
 Planning, Construction, Maintenance & Operation of Sewerage Systems, Reading, England,
 12-14 September, 1984.

	. "Development of a Policy for Sewer Rehabilitation." Restoration of Sewerage Systems,
 Proceedings of an International Conference organized by the Institution of Civil Engineers,
 held in London on 22-24 June 1981. Thomas Telford Ltd, London. 1982.

 Quellette, Herve, and Schrock,  B. Jay.  "Rehabilitation of Sanitary Sewer  Pipelines."
American Society  of Civil Engineers, Transportation Engineering Journal, Vol. 107, No.
4 July 1981.
                                       B-8

-------
                                   References
Read, G.F. "Sewer Dereliction and Renovation - An Industrial City's View;" Restoration
of Sewerage  Systems,  Proceedings of an International Conference  organized by the
Institution of Civil Engineers, held  in London on 22-24 June 1981. Thomas Telford Ltd,
London. 1982.                                                      .

Reed, K, and Rumsey, P.B. "Renovation Development Trails." International Conference
on the Planning,  Construction, Maintenance & Operation of Sewerage Systems, Reading,
England, 12-14 September,  1984.

Schrock, B. Jay. "Pipeline Rehabilitation  Techniques." International Conference on the
Planning, Construction, Maintenance & Operation of Sewerage Systems, Reading, England,
12-14 September, 1984.                                    -.

	. "Solutions in the Pipeline." Civil Engineering, Vol. 55, No, 9. September 1984.

St. Onge, H.  "Relming: The Feasibility of Inserting Pipe into Existing Sewers:" Canadian
Water Resources Journal, Vol. 9, No. 3. November 1984.

Steketee, C.H., and Heinecke, Thomas L. "Key to Effective HI Control." Public Works, Vol.
115, No. 6 June 1984.,

Sullivan, Richard H., and Thompson, William B. "Assessment of Sewer Sealants." American
Public Works Association, Chicago, II. May 1982.    ,

United  States Environmental Protection Agency.   "Construction  Costs  for Municipal
Wastewater Treatment Plants: 1973-1977." MCD-37. January 1978.

__. "Construction Costs for Municipal Wastewater Treatment Plants: 1973-1978." FDR-11.
April 1980.
       ''.'•'            '                  •    \ '  -      ''•''•:'            '
	, "Handbook for Sewer System Evaluation and Rehabilitation." MCD-19.  December
 1975.                     •  •   •  ,  ;
                     1 \ •                 ' <     i     -'                    ,
 Watson, T.J. "Trenchless  construction for underground services." Construction Industry
 Research and Information Association,
 Technical Note 127. Undated.
                                        B-9

-------
                            APPENDIX C

                           CASE STUDIES
This  appendix  contains  detailed  descriptions  of the  RII case
studies  summarized in Chapter 2.   The  case  studies are:

     o    East  Bay Municipal  Utility District, California

     o    City  of  Springfield,  Oregon

     o    Milwaukee Metropolitan Sewerage District, Wisconsin

     o    Northeast Ohio  Regional  Sewer District,  Ohio

     o    City  of  Baton Rouge,  Louisiana

     o    City  of  Springfield,  Missouri

     o    North and  South Shenango Joint  Municipal  Authority,
          Pennsylvania

     o    City  of  Ames, Iowa

     o    City  of  Coos Bay, Oregon

     o    City  of  Tulsa,  Oklahoma

EAST BAY MUNICIPAL UTILITY DISTRICT, CALIFORNIA

The EBMUD wastewater service area is located in northern California
on  the  eastern shore • of San  Francisco  Bay. It  includes seven
community  wastewater  collection  agencies.  EBMUD operates  the
interceptor  system and treatment  facilities  which transport and
treat the wastewater  generated from these seven communities. The
collection systems, which include about 1,500 miles of sewer main,
are owned and operated by the  individual communities. Although the
original  sewers  installed prior  to  1938  were  constructed  as
combined storm drainage and sanitary sewage facilities, the systems
are now entirely separate sanitary systems.

The community collection systems,  as well as the EBMUD interceptor
and treatment facilities,  do  not have adequate capacity to handle
the peak flows which occur  during  wet weather.   As  a result,
overflows onto city streets and bypasses to  local watercourses and
to  San   Francisco   Bay occur  at   numerous  locations  within  the
community  systems and  at   seven  locations  along   the  EBMUD
interceptor. Peak  wet  weather flow rates^ may exceed twenty times
the average dry weather flow  in the  system.
                               C-l

-------
                           Case Studies
In, 1980, the wet weather problems in the EBMUD service area led to
the initiation of the East Bay Infiltration/Inflow Study to address
the problems  within the community collection systems.  Concurrent
with  this  East  Bay  I/1  Study,  EBMUD conducted  a . wet  weather
facilities plan  for its interceptor and treatment facilities. The
;East  Bay I/I Study included extensive flow  monitoring  and SSES
field  work within  the  community collection  systems. One  of the
major  conclusions  of the  study was that the major portion of the
peak wet weather flows in the EBMUD system are due to infiltration
of  storm  water  into defective  pipes  and manholes.   This RII
appeared to exhibit similar flow characteristics as direct  storm
water  inflow, with very rapid, high peak flows occurring in direct
response to rain storms. A major  source of the RII is believed to
be defective building laterals.

System Description                               .
               \  -....            '     -]  :
The EBMUD wastewater service area is located  on the east shore of
San Francisco Bay, extending eastward to the steep hills that form
the  eastern and  northern boundaries  of the area.  Most  of the
developed  portion  of the service  area,is located on an alluvial
plain, at an average elevation  of 75 feet and a width of from one
to three miles, which rises gently from the Bay shoreline eastward
to  the  foot  of the hills.  Predominantly newer development is
located in the hill areas, which rise to an average crest of  1,200
feet*   '    •• '- ^    '••".'''..."'".'    ..•."!,.    •  •  :

Rainfall. The average annual rainfall, as measured at the Oakland
Airport located on the shoreline of the Bay, is about 18.7 inches,
with  90  percent of  the rain falling  during  the period November
through April. Winter storms move through  the area  from west to
east, generally depositing a greater amount of precipitation in the
higher elevations  of the study area.  (Hence, the actual average
rainfall  in the study  area is higher than  the  Oakland Airport
data.) During the winter season, storms may occur one after another
during extended  rainy periods,  or dry periods of up  to several
weeks  without any  rain may occur.                             •

Soils. The soils within the study area range from loose sediments,
such as bay muds in the marshy tida^l flats,  to sedimentary  rocks
in the hillsides.  The tidal flats, consisting of clays and  silty
clays, extend along the perimeter  of the Bay. At higher elevations,
soils  were formed along flood  plains,  river-mouth  fans,  and low
terraces,  and  include silty clays, clays; silty clay loams, clay
loams, and sandy clay loams. Much  of the soils in the EBMUD service
area haveva high shrink-swell potential and low percolation rates.
Under prolonged dry periods,  as occur during the summer months, the
soils  are  subject  to shrinking  and cracking.
                               C-2

-------
                           Case Studies
Hydrogeology. Numerous small streams discharging to the Bay drain
the  basins  formed by the Oakland-Berkeley  hills.  These streams,
together with the intervening ridges, form the topographic features
that describe tributary areas (basins) of the wastewater collection
systems. Groundwater levels in the study area range from less than
five  feet below  the ground  surface in  locations  near  the Bay
shoreline to  greater than 10 feet below  the surface in the hill
areas.  However,  some higher groundwater levels may  be  found in
localized portions of the higher topographic areas due to in-filled
stream channels or soil variations in the Hayward fault zone, which
forms a north-south band through the  foothills. Groundwater levels
in the  study area generally vary  on a seasonal basis,  with the
lowest  levels occurring in  early  fall  after the long dry season,
and  the highest  levels  in the spring at  the  end of  the rainy
season.

Sewer System. The first sewers in the EBMUD area were constructed
in  the 1880's.  The  original sewers  were  six- and eight-inch
diameter  clay pipes  which  served as  a. combined  storm/sanitary
system  and generally  discharged the  flow to the nearest drainage
channel. Most of the early trunk sewers were enlarged  and extended
during the 1920's and 1930's, with downstream discharges near the
Bay  shoreline.   In   1951,  the   EBMUD  interceptor  system  was
constructed along the Bay  shoreline to  intercept  the  east-west
community trunk  sewers and  convey the flow to  the  new treatment
plant.

The major portions of the existing EBMUD community sewer systems
were constructed  in  the first part of this century,  and consist
primarily  of vitrified  clay  pipe  (VCP)  with short,  two-  or
three-foot pipe sections and rigid, cement mortar joints.  Most of
the early sewers  were laid  with bedding and backfill composed of
the native soil materials.  Soil logs from groundwater monitoring
wells drilled adjacent to sewer pipes  for the  East Bay I/I Study
show that the boundary between the trench fill and the  native soils
beneath the  trench is  generally  indistinguishable.  Most  of the
sewer system  was constructed piecemeal  by  individual developers
with little,  if  any, construction inspection  or quality control
provided  by  the  cities.  In addition,  maintenance  of  the sewer
system  over the years has been minimal,  other  than that required
for  emergency situations such as  blockages or  street  collapse.
Because the sloping topography of the area facilitates  gravity flow
from east to west, and because most building laterals are shallow
(homes  generally  do  not have basements), most  of the sewers, are
relatively shallow (typically four to six feet deep), with deeper
pipes being necessary only for the larger downstream trunk sewers
nearer the interceptor. The sloping topography also means that
                               C-3

-------
                           Case Studies
travel times through the sewer system are short, and upstream peak
flows  cumulate rapidly  and  reach  the  downstream end  of sewer
drainage basins in  a relatively short period of time  (typically,
within one to two hours or less).

The study area is characterized primarily by urban, single-family
residential development on small lots.  Therefore, the density of
building  laterals  is relatively  high,  with  an  average of 22
laterals  per  1,000 feet  of sewer  main. Many  of  the original
laterals were not connected to the factory-installed wye fittings
in the sewer main,  but were inserted through holes  (taps) broken
or chipped into the pipe. In, these cases,  some  reaches  may  have as
many  inactive  and  unplugged  factory  wyes  as   active   lateral
connections.   The upper portions of building laterals on  private
property are generally very shallow (less than three feet deep),
with a change\in vertical alignment typically occurring at the  curb
line  where the pipe angles  down toward the  main  sewer  in the
-street-   '•    •           •''•'';'.    -   -.'..-'. :. ..        "..-•;'•"
              (                    . '   ' ' '     .           ,    '   -  •
RII Documentation.   The condition of the EBMUD sewer systems has
been documented by the field work conducted as part of the East Bay
I/I Study.  The field work  included  smoke testing, dye flooding,
physical inspection of manholes, internal television  inspection of
sewer mains, and lateral testing and  inspection.

Smoke testing was conducted in over 50 percent of the  EBMUD  system.
The majority of the smoke returns were  from  defective building
laterals.   Direct  storm water inflow  connections accounted for
relatively  few of the observed  defects.

Dye flooding was conducted to verify suspected storm drain/sanitary
sewer cross connections detected during smoke testing or potential
"indirect1.1  connections where storm drains crossed  over or  closely
paralleled  sanitary sewers. In most of the dye  flooding tests, the
sanitary  sewer was  concurrently TV inspected in order to  observe
the exact location and relative quantity of dye transfer. With only
a very few exceptions, most of the instances of flow  transfer from
;the storm to the sanitary sewers were found to be cases of indirect
transfer  via exfiltration  of water  out of the  storm drain and
infiltration into the sanitary sewer through cracks  and defective
joints.          ,                ,--'"••./

Manhole  inspection  was conducted  for about  20  percent  of the
structures  in  the  system.  In general,  the  inspections  indicated
that  most  manholes  were   in  good  structural   condition   with
relatively  little  evidence  of  infiltration.    Based  on  these
inspections, it was concluded that manholes were not  a  significant
source of RII  in the EBMUD system.
                                C-4

-------
                                 Case Studies
      TV inspection was conducted for about 10 percent of the total sewer
      main footage in the service area, based on  I/I  flow contribution
      as determined through  flow monitoring and flow isolation.  Numerous
      defects in  the  system were  identified through  TV  inspection,
      including   structural  problems,  cracks,   offset   joints,   root
      intrusion,  and defective  lateral connections. The  TV  inspection
      results were used to  document the condition of the pipes  in the
      system and determine appropriate rehabilitation  methods,  but were
      not used  to attempt to quantify  the  I/I contribution  from
      individual  sources.

      Lateral Testing and Inspection.  Lateral field work conducted  as
      part of the East  Bay I/I  Study included  air  and  exfiltration
      testing, rainfall simulation,  flow measurement during rainfall,  TV
      inspection,  and visual inspection of exposed  laterals. Most of this
      work was done as  part  of special pilot projects.

      The lateral  field studies generally included samples ranging from
      10 to 200 laterals. While  these samples represent a small  fraction
      of the  total 175,000 laterals  in the EBMUD service area, the areas
      were selected to be representative  of typical conditions in the
      area.  Lateral inspections revealed that offset  joints and  root
      intrusion occur in most laterals, and other defects such as  cracks
      (particularly near the bells  of the pipes)  and misalignment are
      common. A limited program in which eleven lower  laterals  (portion
      within  the  public right-of-way) were excavated and  exposed  using
      "archeological" methods showed that in 90 percent of the laterals,
      the original mortar  in the joints had  deteriorated.  Most  laterals
      failed  air  and  exfiltration tests, and the  ones that passed were
      generally newer pipes  or  atypical (e.g.  cast iron rather  than VCP
      construction).  A comparison of  smoke testing  records  with the
      results of other  lateral  testing and inspection methods indicated
      that only  about  one-third of defective laterals were detected  by
3      smoke testing.

      I/I Flow Characteristics. The East Bay I/I Study included extensive
      flow monitoring  within  the  community  sewer  systems.  Fifty-six
      "long-term"  flow  monitors were  installed for  a  period of two  to
      three years, and wet weather flow monitoring was  conducted in over
      300 locations in the  system for periods of approximately two  to
      three months during the rainy  season.

      The analysis of flow data for the study was based  on separating the
      total wet weather flow into its component parts of base wastewater
      flow (BWF), groundwater infiltration (GWI), and rainfall-dependent
      I/I (RDI/I).  The  RDI/I was assumed to represent a combination  of
      direct  stormwater inflow  (SWI)  and rainfall-dependent or  rainfall
      induced infiltration (RDI  or RII); however,  it was recognized that
      the SWI and  RII components could not necessarily be  distinguished
                                    c-5

-------
                           Case Studies
 by simple flow hydrograph ^decomposition.  The combination of  BWF
 plus GWI was determined  based on the flow during a  nohrrainfall
 period near the time of the storm event being analyzed. Subtraction
 of BWF + GWI from the total storm flow hydrograph yielded the  RDI/I
 for-the rainfall event, as shown in Figure C-i. The  RDI/I volume
.was then expressed in terms;of a percentage  of the total rainfall
 volume for the  storm. This  percentage,  the ratio  of the  RDI/I
 volume to the total rainfall volume, was termed the  "R value" or
 "total R" for the storm event. R values ranged from  near zero in
 some subbasins to  over 50 percent  in  others,  depending on soil
 saturation (antecedent rainfall)  and other factors;

 Plots of rainfall volume versus RDI/I volume for all  storm events
 were developed for each of the 56 long-term monitors.  It was  found
 that the plotted  points fit within an "envelope"  (see Figure  C-2),
 with the storms representing early season or dry soil conditions
 (low R values) falling near the lower boundary of the envelope,  and
 the storms representing saturated soil  conditions  (high R values)
 falling near  the  upper  boundary.  The dry  soil  R  values were
 generally in the  range of 2  to 6  percent.  The  saturated soil  R
 values typically ranged  from  10 to 35  percent for the long-term
 monitoring sites.The  interpretation  of the  RDI/I envelope  lower
 boundary  condition  is  that  it  represents predominantly  SWI
 contributions,  since  the percentage  of runoff  from  impervious
 surfaces that collect  surface drainage is more or less independent
 of antecendent rainfall conditions. The  remaining RDI/I volume,  and
 possibly also a  portion of the RDI/I  volume represented by  the
 lower envelope boundary,  is  suspected  of being contributed from
 infiltration  sources such as  defects in sewer mains and laterals,
 including indirect transfer from storm  drains to sanitary sewers.
                ,'  •,         '           j   '"'''.      "•    ;
 The  interpretation  of the  upper  envelope  boundary  is that  it
 represents  maximum  RDI/I  contribution  under  saturated  soil
 conditions. Under such Conditions, the capacity of the soil mantle
 to absorb and transmit water would be limited, and more water  would
 .be transmitted through soil channels and through the more permeable
 pipe trenches to sewer defects.  In some cases, the saturated soil
 condition appeared to  be better represented by a  curvilinear  upper
 boundary, indicating a reduction in R for larger storms because of
 the limitation in the amount of water that can reach the defects
 in the pipes once  the soil has become  saturated,  as  well as  the
 inlet hydraulic  capacity of the defects themselves. The average R
 value for the  study area under saturated soil conditions (for  the
 selected design rainfall event) was found to be approximately 18
 percent.   If the R value under dry soil conditions  (average of
 about 4 percent)  is assumed to be the maximum SWI,  then this  means
 that  three-quarters or  more of  the  total RDI/I  volume  under
 saturated soil conditions is due to infiltration of ^stormwater into
 the system,  or RII.
                                C-6

-------
12
                                        24
                                              12
                                                    24
                 EBMUD I/I STUDY
  TYPICAL DECOMPOSED HYDROGRAPH
                  FIGURE C-1

-------
lit
Q
X
                 10
                             20          30


                        PRECIPITATION VOLUME
50
         | - RAINFALL-DEPENDENT INFILTRATION  (R||)


       '	  ALTERNATE CURVILINEAR UPPER BOUNDARY
                         EBMUO I/I STUDY
              TYPICAL BASIN RDI/I ENVELOPE
                         FIGURE C-2

-------
                           Case Studies
To  more precisely define  the magnitude and  shape  of the design
storm hydrograph for use in modeling of the sewer system,  the RDI/I
hydrograph for each  subbasin was  separated  into  three component R
values   (Rl,  R2,  and  R3)  which  summed  to  the  total maximum
(saturated soil) R for the subbasin, as illustrated  in Figure C-3.
In  general,  the Rl component represented the  most rapid  response,
with  a  time to peak of from one  to two hours after the start of
rain. The Rl component could therefore be assumed to represent SWI
and a portion of RII, presumably from shallow infiltration sources.
Rl  was  the dominant  component in  determining  the magnitude of the
peak  storm flows.

To  estimate  the magnitude  of   SWI  independently  of   the  flow
monitoring data, smoke testing data were used to  identify specific
SWI  sources   and  develop  quantitative  estimates  of  the  SWI
contribution  from  those sources. The  SWI  contributions from all
sources in each subbasin  were then  summed and  compared  to the
design  storm Rl volume  for the subbasin. In almost all cases, the
calculated SWI volume as a  percentage of the Rl volume was less
than  10 percent, and in most cases  was less than 5 percent.

While the calculated SWI is probably an underestimate of the actual
SWI volume because not all SWI sources may have been  included, the
estimated numbers did indicate that SWI appears to be only a small
part  of the peak  (Rl) component  of RDI/I.  Therefore,  it  was
concluded  that the major  portion of the peak RDI/I flow in the
EBMUD system is due to infiltration  (RII), rather than inflow, into
the sewers. Based on  the high number of defective  laterals detected
during  smoke testing, as well as the results of the lateral testing
and inspection work, it was surmised that the  peak RII flow is
largely due to  the rapid infiltration of stormwater  into shallow,
defective  laterals.  The magnitude of this RII flow can in great
part  be explained  by the  overall poor condition, as well as the
high density of the  laterals in the system.

Several of the field studies  that  were  conducted on laterals as
part  of the East Bay I/I  Study appear to  confirm the rapid flow
response in  laterals to rainfall  events.   These  studies included
actual  flow measurement of laterals which discharged directly to
manholes. During relatively low intensity storms  (on the order of
0.1 inches per hour rainfall),  approximately two-thirds  of the
laterals sampled contributed an average peak flow of 750 to 800 gpd
per lateral. Some individual laterals contributed as  high as 5,000
gpd peak flows. (Smoke testing records were  used  to verify that no
direct SWI connections existed for these laterals.) When projected
to  a  higher  intensity  design   storm,  the   average  pe.ak  flow
contribution  from  laterals  could be  greater than  3,000 gpd per
lateral. In most laterals contributing RII,  the peak  RII  flow
                               C-7

-------
                           Case Studies
occurred within an  hour of the peak rainfall intensity.  Several
laterals overlain by relatively impermeable surfaces also exhibited
high peak flbw responses, possibly indicating that infiltration can
apparently move  in a  horizontal  direction, as  well  as downward
through the soil.

Rainfall simulation testing also confirmed the rapid flow response
of laterals to rainfall. In this program,  230 laterals were tested
by application of simulated rainfall  (at a measured rate)  in a
six-foot wide spray zone  over  the upper portion of  the lateral
(portion upstream of  the sidewalk) . The  resulting flow from the
lateral was then measured from .the sewer main using a weir/packer
assembly attached to a TV camera.  The flow hydrographs indicated
a rapid response  to the rainfall  simulation, with the  peak flow
generally occurring within one to two hours after the start of the
simulated  rainfall.  In  a few  laterals,  the simulated rainfall
application rate was increased after several hours of testing, and
the flow response was an almost immediate  increase in the measured
infiltration   rate.  This   response appears to  indicate  that
infiltration rates are related to rainfall rates, and for a given
lateral, an increase in rainfall intensity will cause an increase
in infiltration.

The factors which impact RII flows in the  EBMUD system include the
physical characteristics of the service area> including clay soils,
seasonal rainfall pattern, and sloping topography  (which influences
sewer  depths  and  flow travel  times),  as  well  as the physical
condition and  characteristics  of the sewer  system.  The age and
original poor construction, type of pipe material  (VCjP with short
pipe  lengths   and deteriorated  cement  mortar  joints), lack  of
maintenance, relatively shallow depth (particularly of laterals),
high density of sewers and laterals, occurence  of root intrusion
from landscaping, and  pipe damage and  joint separation caused by
earth  movement and seismic  activity are  all factors „ which have
resulted in a large number of defects in the system through which
infiltration can enter. The flow data collected as part of the East
Bay I/1 Study document ,the high peak RII flows which occur in the
system.
                           /  i        ,     ,    '          .
RII Control Program

The  analysis  conducted  for the  East  Bay  I/I  Study found that
rehabilitation was cost effective for approximately one-half of the
subbasins.   The recommended  I/I  correction program  consists  of
"comprehensive rehabilitation," i.e., including the sewer mains and
the entire portion  of the service laterals. Because  of the high
cost  and size of  the construction  effort, the rehabilitation
program will be implemented over a period of 20 years.
                               C-8

-------
                   SYNTHETIC HYOROGRAPH
                       - ACTUAL ROI/I HYOROGRAPH
               R, COMPONENT
                    COMPONENT
                           R3COMPONENT
12
24
                               12
. !
24
 i
24
               :ESMUO t/l STUDY
    TYPICAL SYNTHETIC HYDROGRAPH

                FIGURE C-3

-------
                           Case Studies
To date,  the cities have completed  design and construction of the
first two years of projects.  Most  of the rehabilitation work has
consisted of slip-lining and replacement,  with some grouting.  In
most of the cities, only the sewer mains  and the portion  of the
lower  laterals   within  the ,public   right-of-way  have   been
constructed,  and  two-way cleanouts have  been installed on  the
laterals  at the property line. Private lateral rehabilitation will
be addressed at a  later date. However, one of the seven  tributary
agencies,  the Stege Sanitary District,  elected to construct and
finance  the  rehabilitation  work  on  private property  in  one
subbasin.

In  addition  to   the  20-year  I/I  correction program,  it  was
recommended that the communities implement long-term I/I management
programs.  These   programs  would  provide   for routine   testing,
inspection,  and maintenance  of  the sewer  system and  a  cyclic
replacement  program for  sewers  that have  outlived their  useful
• lives.     •       ....   .    '''..-,.'     .-'•-.   ','•-.

CITY OF SPRINGFIELD, OREGON

The City of Springfield is located in central western Oregon at the
confluence of  the McKenzie  and Willamette Rivers.  The  City's
sanitary   sewer  system  is  tributary  to  a regional  wastewater
treatment plant serving the Cities  of Eugene and  Springfield. The
City of Springfield system serves a population of  about 40,000 and
includes  approximately 165 miles  of sanitary sewer mains.

In the late  1970's a  regional  wastewater  management study  was
conducted for the  Eugene/Springfield area to identify  appropriate
means  for  expanding  and  upgrading  the  existing  wastewater
facilities.  At  that time, Eugene and  Springfield were  served by
separate  wastewater  treatment plants.  Problems  in  Springfield
included   surcharging  and  overflows  in  the   sewer  system  and.
bypassing of partially  treated  wastewater  from  the  Springfield
treatment plant during wet weather periods (almost continuously
during December and  January).  The  recommended project  included
construction of a regional  treatment  plant   (completed  and  in
operation since 1984). As part of the facilities planning phase of
that  project,   Springfield   conducted   an   I/I  Analysis,   which
determined that I/I was  rtexcessive", and subsequently  completed a
SSES in  1980.  The SSES determined  that only  20 percent of  the
design peak storm induced flow could be attributed to direct inflow
sources and indirect transfer from storm drains to sanitary sewers.
Therefore it was  concluded  that 80 percent  of  the  peak  storm
induced flow was   due  to "storm induced  infiltration"  through
defective sewers,  service laterals,  and  manholes.
                                C-9

-------
                           Case Studies
System Description

Most  of the  service  area  is  relatively flat,  with a  typical
100-foot east to west variation in elevation.  As most of the City
is located in a river floodplain,  the soils are primarily alluvial
deposits, ranging from gravelly silt-loams to silty clay-loams. The
climate is typical  of the west coast of  the  U.S.,  with  about 80
percent of the  total  rainfall  falling during the period November
through April. Average annual rainfall is  approximately 45 inches.
The groundwater table  is typically 10 to 20 feet below the ground
surface  during  the  summer,   with  about a  seven  foot  annual
fluctuation. The  groundwater  is highest  during  the winter rainy
season, and very  near the surface in the western portion of the
City near the river confluence.

The sewer system was originally constructed in the central portion
of the  City between 1910 and 1940,  with  expansion  of the system
into the eastern and northern portions taking place since 1940. The
older   sewers   are   VCP  or  concrete  with   cement  mortar  or
asphalt-poured  joints. Many of  the  older service  laterals  were
constructed  of Orangeburg  pipe,  although  many of these  have
presumably since been  replaced. Newer construction since 1960 has
been primarily concrete pipe with rubber gasket joints. The depth
of sewer mains ranges  from 5 to 11 feet, with an average depth of
8 to  9 feet.  Groundwater monitoring  conducted during the  SSES
indicates  that a  large  portion of  the sewer  mains are  below
groundwater during  the  winter.  There  are  approximately 13,000
service connections in the system, for an average lateral density
of 15 per 1,000 feet of main.
       '•        '  '                /           ,
RII Documentation

During the SSES, dry and wet weather  flow  monitoring was conducted
at 54 sites throughout the sewer system.   For  each monitored area,
the average dry weather flow, peak non-rainfall infiltration rate
and peak storm induced I/I rate were determined from  the flow data.
For the measured  storms,  peak  to average flow ratios ranged from
about 1.5  to  15.  The  peak storm-induced  flow was projected  to a
five-year  design  storm condition based on the  ratio of measured
(two-hour) rainfall to design rainfall intensity.  For the total
system, the ratio of  design PWWF to  ADWF was approximately 11 to
1.

The field investigations  conducted as part of the SSES identified
numerous defects and I/I  sources  in the system. Smoke testing was
conducted for over 90 percent of the  sewers. A large proportion of
                               C-10

-------
                          Case Studies
the smoke  emissions were observed  along the ground  above sewer
mains and laterals and near manholes.  Other smoke emissions were
from manhole frames  and lids, cleanouts, and storm drainage sources
(catch basins, storm sewer manholes, area and roof drains).

To verify whether storm drainage  sources were direct or indirect
connections  and to  quantify the flow  contribution  from these
sources, dye  flooding was conducted  for all  smoke emissions from
catch basins, storm sewers, and area drains.   The results of the
dye flooding indicated that over 90 percent of these sources were
cases of indirect flow transfer between storm and sanitary sewer
facilities;  only five direct connections  were  found.  Physical
reconnaissance was conducted for all  other specific smoke emission
sites, such as  cleanouts, which appeared to  be potential sources
of direct  inflow.  In addition, all  manholes in  the  system were
inspected to  identify  potential  inflow  sources through  holes in
manhole covers.                          ..

Television  inspection  was used to  identify specific  defects in
sewers where  infiltration during  dye flooding was identified. TV
inspection  or  review  of  past  TV  inspection  records was  also
conducted  for those sewers  where smoke was observed along the
ground surface over the pipe.

For all direct inflow sources, estimates of maximum flow rate were
made  using  the rational  formula, based on the surface  area and
drainage characteristics  of each source  and  the  design rainfall
intensity. Flow estimates based on dye  transfer rate were made for
indirect connections between storm drains and sanitary sewers. "The
calculated total peak  flow from  these sources was 13  mgd, or 20
percent of  the  projected peak storm induced I/I  flow of 65 mgd.
Since a portion of the 13  mgd  is due to indirect  transfer from
storm to sanitary sewers,  it can be concluded that over 80 percent
of the peak storm induced I/I appears to be due to RII.

A site  visit was made to  Springfield  during the course of this
study, and  City staff  were interviewed regarding  RII problems in
the sewer  system.  With respect to  the  condition of  the sewers,
staff  identified  service  laterals as  potentially  significant
contributors  of extraneous  flows. Specific problem areas are the
connections between the private and  public portion of the lateral,
between  the  lateral  and  the main, and at  the manhole.  Other
potential causes of RII  include  inactive, unplugged lateral taps
and, root intrusion. Because many  of  the older mains are located in
backyard alleys, unauthorized and uninspected hookups and repairs
                               C-ll

-------
                             Case Studies
   are  frequently made.   High flows are  also experienced in newer
   areas   built  during  the  mid-1970's  development   "boom,"  when
   construction  inspection  may  have  been  inadequate  because  of
   insufficient City staffing.
*                                           ...
   Some the primary factors affecting RII in Springfield,  in addition
   to the  condition  of  the, sewers,  appear  to be the high  groundwater
   and amount and pattern of rainfall.  During storms,  groundwater in
   the trench line has been known to wash out portions  of  streets and
   create  small "geysers" up through the asphalt. The  flow response
   to rainfall is rapid, and  generally decreases rapidly after the end
   of rain. This rapid rise and recession appear to be  independent of
   the groundwater infiltration rate immediately prior to the storm.
   Larger  flows occur  during  prolonged rainfall  periods than from
   isolated rain events.

   RII Control  Program

   As a result of the SSES and further cost-effectiveness evaluations,
   the City received a construction grant for sewer rehabilitation in
   four basins,  representing approximately five  percent of  the total
   system.   (The  official  grantee is  the Metropolitan Wastewater
   Management  Commission, the regional wastewater  agency  for  the
   Cities of Eugene and Springfield.) The area is an older part of the
   City, with most  of the original  sewers  over 40 years in age and
   constructed  predominantly  of  concrete  pipe with  cement mortar
   joints. This rehabilitation project (called the "C74" project) was
   based on  a  design philosophy  of "complete basin" rehabilitation
   (all of the  sewers,  including  service laterals) and  was projected
   to result in a 65 percent I/I  flow  reduction.   The first phase,
   consisting of replacement or  grouting  of the  mains and  service
   laterals within  the public right-of-way,  was completed in 1987;
   preliminary  flow  monitoring results  indicate that an  approximate
   50 percent flow reduction has been attained.

   In addition to the grant project, several small pilot projects have
   been completed,  including two  in the C74 area and two in newer
   areas of the City.  The C74  pilot projects involved rehabilitation
   of private   service  laterals  where  the main  had  already  been
   replaced or,  grouted.  The other  two  projects were  done under  a
   turnkey-type  contract in which  the  contract  bid  was  based  on
   achieving 65 percent flow  reduction  with a  price  incentive  for
   greater reductions.  Analysis of  the  flow reductions achieved  in
   these pilot  areas are  not conclusive because of the lack of rain
                                 C-12

-------
                           Case Studies
during the 1987/88 season. However,  preliminary results of the two
projects in the newer areas indicate 90 percent and over 50 percent
flow reductions,  respectively,  based on total storm  flow volume
calculations.

The City is currently re-assessing its approach to addressing I/I
and developing a long-term I/1 control plan. In general, City staff
feel that sewer system rehabilitation, particularly in older areas,
is  not cost  effective.  The  City is  lopking at other  options,
including  off-  line storage  for peak  flows and  concentrating
rehabilitation  efforts in newer areas, where they believe it may
be possible to  reduce I/I  at a lower unit cost.

Impact of Peak  Flows on WWTP Operation

The Eugene-Springfield regional WWTP is relatively new,  and was
designed to incorporate considerable flexibility for handling flow
variations due to wet weather and future growth. Design ADWF is 49
mgd; maximum design  flow  is approximately 180 mgd. At flows above
175 to 185 mgd,  raw wastewater bypasses  at the  pump stations and
WWTP would be activated. Current ADWF to the WWTP is 22 mgd. During
a recent storm  period, a peak flow of 143 mgd (95 mgd daily flow)
was reached. The flow from Springfield alone, however,  cannot be
reliably isolated because  of the  location and type  of flow metering
devices that were installed in the interceptor system.

Effluent requirements for discharge to the  Willamette River are
30/30,mg/1 BOD and suspended solids in winter and  10/10 in summer.
The WWTP is an activated  sludge plant, which is run as a contact
stabilization process in winter  and modified plug flow in summer.
During peak flow periods,  effluent quality  is maintained, first by
putting on line additional primary and secondary clarifiers, and
then by  bypassing a  portion  of the primary  effluent  around the
secondary treatment  process.  Bypassing is  generally'required for
only a few hours  to one- half day.  The  flow  to  the  secondary
process can be controlled  by pre- selecting the flow  level at which
bypassing  will  start.     The  disinfected  combined primary  and
secondary effluent  generally does not exceed 20  mg/1 susupended
solids.

In addition to the capital cost for excess capacity, the major cost
associated with treating  peak wet weather flows is  the increased
labor required for clean-up of the additional clarifier units which
must be put into service  during the peak flow periods but are' no
longer  needed  after the  flows  recede.  Increased energy  costs
associated with peak flows are fairly minimal,, since the bypassing
,6f  the secondary process means that  significant increases  in
aeration are not required. Because there is a "trade-off" between
maintaining effluent quality and reducing clean-up requirements,
                               C-13

-------
                           Case Studies
 there is a certain amount of guess work involved in deciding when
 to put additional clarifiers on line during peak flow periods.

 Other wet weather impacts at the WWTP  include problems  caused  by
 large quantities of grit which are washed out of the sewer system
. during the  first large  storm of  the  season,  sometimes  causing
 damage to equipment and plugged lines (the grit chamber is located
 downstream of the  comminutor).  Also during wet weather periods,
 solids washout may  occur, resulting in decreased gas production  in
 the digesters. Foreign materials  washed out of the  sewer system
 (oils, grease,  etc.) also may  inhibit bacterial  action.

 MILWAUKEE METROPOLITAN SEWERAGE DISTRICT, WISCONSIN

 The Milwaukee  Metropolitan Sewerage  District  (MMSD)  serves  28
 communities in the southeastern portion of Wisconsin. The largest
 of the  communities is  the City  of Milwaukee.  MMSD operates  a
 294-mile  interceptor  system  and  two   treatment   plants;  the
 collection  systems are  owned  and operated  by  the  individual
 communities. The total MMSD service area includes over 2,800 miles
 of sewer  mains,  of which approximately  20 percent  are  combined
 storm/sanitary sewers, mostly located within the City of Milwaukee.

 In the late  1970»s MMSD initiated the Milwaukee Water  Pollution
 Abatement Program to address the problems  caused by inadequacies
 in the wastewater  collection,  transport, and treatment  systems.
 These  problems  included   overflows   and  bypassess   from the
 interceptor and collection systems, sewage back-ups  into building
 basements, and discharges of  inadequately treated wastewater  to
 Lake Michigan. The Water Pollution Abatement Program included major
 projects to upgrade the interceptor system  and treatment plants,
 projects to address problems in the combined sewer  service area,
 as well as  a comprehensive  SSES  for the separate sanitary sewer
 portion of the service area. The SSES was completed  in 1981.

 Although  the Milwaukee  SSES  identified  direct   inflow  as   a
 significant portion of  peak wet weather  flows,  and much  of the
 subsequent rehabilitation effort was concentrated on removing those
 types of sources, the study did include documentation and extensive
 field investigation of sources which the study termed  "indirect
 inflow."   These   sources   included   leakage   through   manhole
 frame/chimney defects, as  well sis  sources on private  property,
 primarily  foundation  drains.  The  estimates  of   source  flow
 contributions developed for the SSES indicate that more  than  50
 percent of the maximum hour  I/I flow is due to these types of RII
 sources.
                               c-14

-------
                          Case Studies
System Description

The MMSD  service area is relatively  flat.  In general,  the, area
drains west to east and north to south toward the Milwaukee River
and Lake Michigan.  Soils  are typically clay, with more sandy soils
in the western portion of the service area.  Many of the soils are
of glacial origin, resulting  in  seams  of more permeable material
throughout the  soil  mantle.   The groundwater level  is  typically
about six feet below the surface, and increases to about three feet
in the spring.

The   Milwaukee   area  receives  approximately   31  inches   of
precipitation  (water  equivalent)  annually.    Rainfall  occurs
throughout the year, although it is  lowest  in the coldest months
of January and February when most precipitation occurs as snowfall.
In early spring,  conditions of rain,  showmelt,  and high groundwater
occur simultaneously,  resulting in the highest I/I flows.  Freezing
temperatures in the winter result in frost heave damage to streets
and manholes.

The original  sewers  in the separate sanitary sewer  system were
constructed in the 1920's, with more recent  construction in the
outlying communities.  The average depth of sewer mains is 15 to 20
feet?  service  laterals   are  typically  6  to  10   feet  deep.  A
considerable  portion  of  the  system  is  therefore  below  the
groundwater table.   In the older portions  of the  service area,
individual  buildings  are served by  both   storm  and  sanitary
laterals, which have commonly  been constructed in the same trench.

RII Documentation

Flow monitoring was conducted at several hundred locations during
the SSES.  Infiltration was /identified as the early morning flow
rate, and "inflow" was calculated as the difference between total
storm flow and  non-rainfall  flow (base  flow plus infiltration).
Both infiltration and inflow were projected to a maximum condition
using adjustment factors based on historical  data from 34 permanent
monitoring sites in the system.  These factors were determined for
diff erent, areas of the system by relating the measured infiltration
and peak  hour inflow  during the monitoring  period at the various
permanent monitoring sites to the infiltration and peak hour inflow
for selected maximum historical infiltration and inflow events. For
the total system, the ratio of design PWWF to ADWF is approximately
7.5 to 1. Of the projected total peak hour flow of 1,155 mgd, 878
mgd or 76 percent  is "inflow," i.e., rainfall induced I/I.


Extensive field  investigations were conducted as part of the SSES
to  identify  specific  sources   of   I/I  and  quantify  the  flow
                               C-15

-------
                           Case Studies
 contribution from each source.  Physical inspections were conducted
 for all manholes in  the SSES  area,  and  included lamping of  the
 inlet and outlet sewers from the manhole.   The manhole inspections
 identified vented covers, misaligned and unsealed frames, manholes
 subject to  ponding,  and  manholes and  sewers  with  evidence  of
 infiltration (leaks,  deposits, roots). Building inspections were
 done to  identify  I/I  sources on  private  property,  including
 downspouts,  roof drains, area drains,  foundation drains, and sump
 pumps.  Inspections were attempted at all  residential  and small
 commercial  buildings;  approximately   60  percent of  the  165,000
 attempted inspections were completed.

 Smoke testing was conducted for all of the SSES area.  Dye flooding
 was  conducted in approximately 35 percent of the area.  All storm
 sewers  and  drainage  ditches  which  paralleled or  crossed over
 sanitary sewers or laterals were included. Dye flooding identified
 both direct and indirect storm/sewer connections. Street flooding
 was  conducted for  about 10 percent of the manholes in  the system
 in order to identify and quantify I/I which enters manholes through
 frame/chimney defects.  TV inspection  was conducted for about  13
 percent of the system on  those  sewers  identified as inflow  or
 infiltration sources through dye   flooding  (medium  to  heavy
 transfer) or sewer  lamping. In addition,  two pilot projects were
 developed for in-depth investigation  of I/I sources from manholes
 and  from private property  (laterals and foundation drains).

 The  private  property  I/I  study found that flows from  foundation
 drains and defective laterals were responsive to rainfall, with the
 maximum flows occurring during rain events when the groundwater was
 high.  Indirect flow  transfer  from  foundation  drains  and storm
 sewers  and ditches  was identified as  a significant source of I/I
 in defective laterals.  TV  inspection  of  the laterals  (primarily
 pre-1960 VCP with mortar joints) indicated that  two-thirds of the
 joints  were  defective.  The  direction of  surface drainage  and
 location  of  downspout discharges  were  other   factors  cited  as
 influencing lateral and foundation drain  flows.

 The major sources of I/I identified through the  SSES were manholes
 (97  percent  with vented covers and  59  percent with  misaligned
 frames) and foundation drains. Distinction was made between inflow
 and  infiltration sources,  and between direct and indirect inflow
 sources.   Indirect   inflow   (RII)    sources   include  manhole
 frame/chimney  leakage and manhole,  sewer,  and lateral defects
 detected  through  rainfall  simulation  (smoke  testing  and  dye
 flooding), including  indirect  flow  transfer from  storm sewers.
Manhole frame/chimney  leakage occurs when surface runoff seeps into
 cracks  and  joints  in  concrete streets and enters  manholes with
unsealed  or  misaligned frames.  This  phenomenon  is  caused  by
 freezing and thawing, which create  gaps between the  frame  and
                               C-16

-------
                           Case Studies
chimney and  in the street pavement. In  some manholes which have
been excavated for repair, large voids  or channels have been found
around the  manhole frame, created by water  infiltrating  to the
defects.    ;     .,„''•      '       .•;-.".   .    -•   ~      .'_...'     ' •  ' .

Estimates of flow contribution were "developed for each type of I/I
source. For  direct  inflow sources, the rational method was used.
For  indirect  inflow,  flow estimates  were  based  oh  flow rates
measured during dye flooding and street flooding. The total maximum
hour I/'I  calculated in this manner  is approximately  800 mgd, of
which  32  percent  is  attributable  to  direct inflow  sources,  40
percent to foundation drains, 12 percent to manhole frame/chimney
leakage,  and 15 percent to infiltration through laterals, sewer
mains, and  manholes,  a  portion of which  was identified through
rainfall  simulation and therefore can be considered to  be RII.
Approximately 60 percent of the peak I/I  flow appears  to be due to
            "'''       ''
A site visit was made to Milwaukee during the course of this study,
and District and  community staff were  interviewed regarding RII
problems  in ,the  sewer  system.    Staff  indicate  that  RII  from
laterals may have been underestimated  in the SSES. .Dye flooding
work during the SSES identified considerable flow transfer from
storm  drains crossing over  laterals.  In  particular,  the common
trench storm and  sanitary laterals  that are typical in the older
portions of , the service area are potential sources of indirect flow
transfer. Some of these types of sources were demonstrated as weak
smoke  emissions from roof leaders  that were presumably properly
connected to a  storm lateral,  which was then exf iltrating to the
sanitary lateral.

RII Control  Program

The I/I correction work resulting from the SSES consisted primarily
of eliminating  direct  inflow through manhole covers and indirect
inflow (RII) through manhole f tame/chimney interfaces. The program
also included the correction of illegal  clear water connections to
the sanitary sewer from private property (other than  foundation
drains) , some sewer  main grouting,  correction of connected catch
basin leads, and bulkhead repairs. The District conducted a manhole
rehabilitation  pilot project  to evaluate different  methods  of
correcting   manhole   frame/chimney   leakage.  (A  more ..detailed
discussion  of these  manhole frame/chimney rehabilitation methods
is presented in Appendix  D.)
                               C-17

-------
                            Case Studies
  5?h    £c J?*e serv^ce lateral rehabilitation that was recommended in
  the  SSES  was  done  due  to  legal  ramifications.  Two  of  the
  ™r$7tii^S  ^YV^ssfully addressed foundation  drain sources.
  The Villages of Brown Deer and Menomonee Falls have  enforced  the
  disconnection of  the  foundation drains  identified  in  the SSES  and
  have instituted ordinances requiring  inspection and disconnection
  £,,««?   sanitary  sewer connections  (foundation drains, sump
  vSSXo turasp°utsi: The Brown Deer ordinance requires conformancS
  before the property  can  be  sold. The  Menomonee  Falls ordinance
  empowers  the  plumbing   inspector  to  enter  a  property   Son
  identification, to ascertain the quantity, quality; and condition
  ?f S™?^*11* clear:wate? discharges-,  and provides the lu?horl?y
  to require disconnection within six months of Written  notification
  of violation  of the ordinance. Brown Deer has taken further steps
  T™  S*!??'  .Ille9al  connections  in  buildings  that  were  not
  inspected during the SSES.
 «™     comnuilitie3 ±n the District «ave prevailed upon property
 owners to correct illegally connected sump pumps and area and roof
 drains, at least  for those properties inspected  during the SSES.
 All communities have also  adopted  ordinances  that prohibit clear
 water connections to the sanitary sewer system.  However, only the
 two   communities   identified   above  have  gone   beyond   the
 SSES-recommended private property rehabilitation program to address
 illegal connections on properties not inspected during the SSES and
 foundation drain connections that existed prior to adoption of the
 ordinance.
   orr         iS4-in ^ Process of implementing a long-term control
SSS^ I  m??y?-JP.  levels throu9h01* the system and track the
impact of rehabilitation work. Permanent monitors  with telemetry
are  installed at approximately 50 locations, and further phases of
the  program will include 100 to 150 monitoring sites  for smaller
areas  within the  communities.    The  data  collected  from  the
long-term monitoring program  will  be used  to identify  specific
areas  which continue to have particularly high I/I  flows  so  that
correction work can  be planned.
Impact of Peak Flows  on WWTP Operation
 ~ao °S?raJ:es two major wastewater treatment plants: Jones
Island and South Shore.  Both plants discharge to Lake Michigan. The
Jones Island plant service area includes the combined sewer portion
of the system, as well  as portions of the  separate  sewer  system.
                               c-18

-------
                           Case Studies
The District's interceptor system includes 20 diversion structures
(with 15 more planned),. which are used to control the flow during
wet  weather  periods.  Nine  of  these  diversion  chambers  are
automatically controlled  based on the monitored hydraulic grade
line  at  key  points  in  the  system,   as  well  as  monitored
precipitation. Because of the size of the District, precipitation
and flow trends must be monitored closely and are used to trigger
the activation of flow diversions. The interceptor diversions are
used to  divert  flows from  Jones  Island to the  South Shore WWTP
during peak flow periods.                                     .

The Jones Island WWTP  is currently undergoing expansion to increase
maximum day capacity  from 200  mgd to 330 mgd.  The design maximum
hourly flow is 390  mgd, of which 330 mgd receives full treatment
and  60  mgd  is  in-line  flow  receiving only   disinfection  and
dechlorination. Current average  flows during  low rainfall months
are in the range of  115 to 135 mgd. Prior to the current expansion,
the plant was limited by  secondary clarifier  capacity.   Flow was
taken until secondary  clarifier blankets were in danger of spilling
into the effluent.  When  high  secondary clarifier  blankets were
observed, a  portion of the flow was bypassed to  prevent solids
carry-'over into the effluent. All bypassed flows received primary
treatment and were chlorinated  and dechlorinated before discharge.

The current operating strategy for high wet weather flows includes
diverting flow to the  South  Shore WWTP and controlling the influent
flow through two (low- and high-level) siphon gates at the entrance
to the plant. Throttling of these gates backs up  the flow into the
collection system.  The  objective  of system  operation during high
flows is to maintain the sludge blanket in the secondary clarifiers
and avoid spilling  solids into the effluent.  Standard procedures
and criteria for wet weather operation have been developed and are
followed during periods of  high wastewater flows. After the plant
expansion  is  completed,   return  sludge  capacity  rather  than
clarifier capacity  could  become the  limiting  factor  in handling
high flows during bulking sludge conditions.

The South Shore WWTP has an average flow of 80 to 90 mgd, but may
experience peak flows in excess of 450 mgd. A typical "good-sized"
storm will produce flows of 300 to 350 mgd. There is a significant
lag time in the sewer system,  with normal dry weather peak flows
reaching the plant eight hours  after the  time of peak system flow.

During wet  weather, the  flow  through the plant is  increased to
avoid  back-ups , in  the collection  system.   This  is  done  by
increasing  the  grit  channel velocity by  opening  1Uie  butterfly
valves. Primary clarif iers  that may have been out of service for
maintenance or repair are put back on line. Flow through the plant
is limited by secondary clarifier capacity,  which is normally 240
                               C-19

-------
                            Case  Studies


                     caPacity through the  secondary process by §6


 NORTHEAST OHIO REGIONAL SEWER DISTRICT; OHIO
 ™™         °!£0 Re9ional Sewer  District  (NEORSD)  includes 41
 SS3XS tS *?      .cl*veland,  Ohio, metropolitan area. NEoHo is
 divided into two ma} or subdistricts : The city of Cleveland  which
 has a combined sewer system; and the surrounding communities; which
 have primarily  separate  systems . NEORSD operates  an interceptor
 system and five treatment plants; the collection Systems arfow^ed
                     individual communities. Most of the separSSd
                   ™*S °?ntained W±thin two ma3°r Planningareas?
                Separate  Sewer  Area  (ESSA)   and  the  Southwest
                  (TA)'  f °f which  SS*S '•  ^ere  ccn-pl^to ills
               me,S? seParate  sewers in the  District are located
              rt?°gethe5'  «»  ESSA a^ SWIA contain approximately
              °f sanitary sewers serving  a  population of  about
 500,000
 Overflows and bypasses occur at over 200 locations in the senarate
 sewer system, most activated by rain events of 1m San 0.1 incheS
                                                       ar  ued to
                                    Basenent back~ups are  a
System Description
        g^aP L°f the area ra™?es from flat to fairly steep, the
        elevations  located  on  a   glaciated  plateau  in  the
        ^?"*100 °f *?» Di-^i<* in the ESSA. Numerous SreamS
River t£d iSL  p4rea^ ^th draina^ generally toward the Cuyahoga
S ^.SS   ^t   ^'  S°lls consist Primarily of moraine deposits
S™3£?-  it and gravel* The Predominant  soil  association S
characterized by very slow permeability (less than 0.2 iri/hrJ and
a seasonally high groundwater table from November through 5une  Se
groundwater level is typically six to ten feet below the surface?
                              C-20

-------
                           Case Studies
 however>   high  bedrock  exists  in   some   areas,   with  perched
 groundwater at 12 to 30 inches below the surface.  Rainfall occurs
 year round and averages  35  to 40 inches, depending on location.
 Both localized and area-wide storms can occur in the system.

 Construction of the original separate sanitary systems began around
 1915,  with a majority of the  sewers  constructed during the first
 part ?f tne century.   Most of the sewers are clay,  with mortar or
 bituminous joints in the older pipes  and compression-type joints
 used since  1965.  Most older manholes  are  brick,  with  concrete
 manholes  being constructed since  1970.

 Service  laterals  are  also  predominantly  clay  pipe,  and  are
 typically constructed in the same  trench as.storm laterals.  Almost
 all  buildings  in the service  area  have storm laterals to convey
 roof and  foundation drainage to  the  storm  sewer system.  Direct
 foundation drain connections to the sanitary system are not common,
 since   storm  laterals  are   generally  deep enough  to   collect
 foundation drainage without the need  for sump pumps.

 The  oldest.sanitary sewers, constructed prior to about 1930, were
 installed in common trenches with storm sewers;  Over 50 percent of
 the  separate system (80 percent  of  the ESSA) consists of  common
 trench  sewers.  There  are  two  basic  types  of  common  trench
 construction:  dual system (side-rby-side) and over-under. In  the
 dual system, the storm  sewer was  typically laid  next to and about
 one  foot  higher than the  sanitary sewer. This was generally done
 by digging a single wide trench  and  refilling  the bottom of  the
 trench on one side to form a bench for the storm sewer.  The entire
 trench was filled with granular backfill; porous slag material  was
 often  used as bedding  and fill  material between the storm  and
 sanitary sewers. The two sewers were generally accessed by  separate
 manholes;  where  common manholes  existed, they  were separated  by
 either partial  or full-height walls.  However,  the  sewers are  so
 close together that the storm pipe walls are usually visible in  the
 sanitary sewer manholes.

 In the  over-under  sewers,  the storm drain is laid  on top of  the
 sanitary sewer,, often with less than one foot  clearance between  the
top of the sanitary pipe and the bottom of the storm sewer.  In many
cases the  fill  material between  the two pipes  has eroded, which
causes  settlement  of  the  storm sewer and structural  damage
 (springline  cracks  and potential  crushing) to the  underlying
sanitary  pipe.  The  over-under  sewer  manholes were generally
constructed with a steel or cast  iron plate separating the access
                               C-2'l

-------
                            Case Studies
                                       plates have
 RII Documentation
 o    ?°?in0r*n£-WaS conducted at 85 long-term monitoring sites and
 SS V^Vh(^~term Sites'  Flow data were  analyzed tl determine
 base infiltration and peak  (rain-induced) I/I.  Rain  induced I/I

 fi£^JSre ^°JeCtf-,d t0 a design storm Condition based on rainfall
 SJSS^ ity* These  flow Projections resulted  in ratios  of  ADWF to
 IS?? °Lreon20 t0 V* the ESSA and Approximately 12 to l in thS
 SWIA. Over 90 percent of the PWWF is due to rain induced I/I.
       investigations  conducted during the SSES's  included smoke
           dye  floodin9'  and  TV  inspection.  Smoke  testing  was
           ln. approximately  30 percent of the system. In many cases,
 ftnfl     n  ^     ^f0If0n  trench  storm and sanitary  sewers  wer4
 found to  leak so  badly that  the smoke  could  not reach  inflow
 connections, such  as  drains on private  property.   Also   it  was
 often  difficult  to  distinguish  between direct  and ^indirect
 ?SS   Sn! °n private Property (e.g., roof downspouts) because of
 iS J?6 ^^.^ common trench  storm and  sanitary  sewer  laterals.
 Dye flooding indicated -that the flow transfer between the storm and
                  WSS rapid- In ov®r-under systems, the  peak  flow
                    sewer  was  reached  within  10  minutes;   in
                  sePafate trench sewers,  within  20  to  30 minutes.
        ™     insP.ec.tlon of the sewers indicated that most of the
 leaks were. from 3oints and  service connections.
          o°f i direct  inflow,  based on  smoke  testing  and dye
fi™            account for 5 to 15 percent of the peak wet weather
flow. It was concluded that the remaining rainfall induced flow was
fto™0^^ ^^tion,  primarily due to exf iltration fromTeS?
storm drains and storm laterals into sanitary sewers and laterals.
Ll^Sf^ Tf %?ade t0- ? ORSD during the course of *****       ,
and District staff were interviewed regarding Rll problems in the
sewer system,  staff identified potential Rll  sources in soviet
         n?^011^17^6 connection to the main,  including hammer
        S   S* S? *^e steePer grade and often vertical drop of the
                main  connection;  traffic loads;  and  the greater

                                 portion  of the laterals wLn the
                              C-22

-------
                           Case Studies
RII Control Program

The primary emphasis of the District's program is construction of
new  interceptor sewers.  Each community within  the  District  is
responsible  for. its  own  rehabilitation  program.    With  few
exceptions, the rehabilitation work is addressing only the public
portion of the sewer system.  Since cross leakage between storm and
sanitary sewers, particularly with common trench construction,  is
the major  source  of I/1, correction efforts  are  concentrated  on
rehabilitation and flow  regulation  in  the  storm  sewer system,  as
well as sanitary sewer rehabilitation.  Work includes separation of
common trench sewers by construction of new storm sewers, addition
of  storm  sewer  capacity, and rehabilitation of  common  trench
storm/sanitary  sewer  manholes (constructing  walls  in  manholes
between side-by-side sewers,  sealing plates in over-under sewers).
Vortex regulators are  being  used in many  communities to restrict
the flow into the storm drain system.  The impetus for these types
of solutions is to  eliminate basement  flooding.  Essentially, the
vortex regulators  restrict storm flows  from entering  the storm
sewers, causing temporary flooding on the streets. This reduces the
load  on  the storm  drain system and  thus reduces  overflows and
indirect flow transfer to the sanitary system.

The District is coordinating  several pilot rehabilitation projects
in various communities.  Each community is  responsible for the
rehabilitation  work,  and   pre-  and   post-rehabilitation  flow
monitoring is conducted by the District.  Each of the pilot areas
includes approximately 2,500 feet  of pipe and 100  laterals. The
evaluation of the results of the pilot projects! has not yet been
completed*

Impact of Peak Flows on WWTP Operation

The  District  operates three major  wastewater treatment plants,
called Easterly, Westerly, and Southerly, based on their respective
locations  within  the  District service area.   The  Westerly and
Easterly plants discharge to Lake  Erie.    The  Southerly plant
discharges to the Cuyahoga River. All  of  the plants receive some
amount of combined sewer discharges. The majority of the combined
sewer  flows go to  the  Westerly  plant,  which   includes  a CSO
treatment facility. The Easterly plant, which serves a portion of
the  combined sewer  area,  as  well as  the  ESSA  with..a large
proportion  of  common trench construction,   has  a  wet  weather
capacity of 330 mgd.  Flows in excess of that amount are bypassed
to Lake Erie.

The Southerly plant has undergone a  recent  expansion to provide up
to 400 mgd of two-stage secondary capacity  (plus filtration), with
an additional 335 mgd of primary only treatment capacity for peak
                               C-23

-------
                             Case Studies
  CITY OF BATON ROUGE,  LOUISIANA


  is6 ?^L°«  B5ton*ou*e' Parish of East Baton Rouge (Baton
                                    sssss:
                          plant that discharges to the Mississippi
                              has  144  local wa^ewater  tre^mSS
                                   streams that flow to either the
 In the late 1970 's an extensive SSES program was conducted in  the
 area served by the three main treatment plants / The result! of tha?

             1^   X/X 1S "e^ssive..Pin tL  collection Astern!
                      es<.occur  tharoughout  the  collection  systei

                     ! St0rm  eVents  that a^e common in the  area?
                     large number of direct connections between  the

 ogl SSES       i«nrS  at-^at .time'  Errors  found  ^  SJ
 1987^8 i»f«l/«?? ^   t0 Yerifl°ation  field  work performed in
 o! th2 -nJfJ?   Pilot areas in the collection system.   The results

 defS£sP in  ?hegr™^ndlCatt ^ the ~J«ity  of I/I  sources  are
 DotentLi ^^  *• sewers'. not direct  connections.  Only   sixteen
 potential  direct connections have been  found in the uilot ar-^*!
 during the additional, field work. The City^stSf believl that a
System Description
Most  of the service area  is relatively flat, averaging  45 feet

easTinlo tSZ^  ¥**  V 2* S-Urface ^alnagi-ln  thl alea fllws
east  into the Comit or Amite Rivers, where as most of the sewatre

Sver  Is mosT^^ treatme*t and discharge l^tlS'ittSlSSl



ciayf  with  a  low  permeability.  Bedrock is  several  thousand feet
                              C-24

-------
                           Case Studies
 below the ground  surface.  The groundwater  is usually below  the
 sewers  except  in  those  areas  immediately  adjacent   to   the
 Mississippi,  Amite,  and Comite Rivers.

 The climate  is typical of states around the Gulf of Mexico, with
 about 54 inches of rainfall per year occurring throughout the year.
 Average monthly rainfall is  3  to  5 inches, and storm events range
 from high intensity short duration thunderstorms to more protracted
 rainfall   from  hurricanes   and  other  tropical  storms.    Peak
 intensities of greater than one inch per hour are fairly common  for
 storms in  the area.

 The sewer system was originally constructed in 1890 with clay pipe.
 Sewers constructed up  to 1960  were constructed with clay pipe  and
 cement mortar or  asphalt poured joints.   Beginning  around 1960
 concrete pipes were installed for  a major portion of the collection
 system for all pipe sizes including service laterals. Approximately
 80  percent of  the new sewers constructed in recent years.have been
 installed  in  backyard  and  cross country  easements  and drainage
 corridors.

 Joint  construction , in  the  1960's shifted to  rubber  gaskets.  In
 recent years, PVC has been used extensively  in  smaller  sewers
 because  of its  ease  of installation. Creek  crossings and canal
 crossings are made with cast or ductile iron pipe.   Sewer mains  are
 typically placed on the opposite side of the street from the storm
 sewer  with pipe crossings at intersections and catch basins.  The
 depth  of the sewers ranges from 4  to 20 feet, at which point a pump
 station is normally  constructed.  Service laterals range in depth
 from the .ground surface to about three feet at the curb.  Service
 lateral are constructed with a six-inch pipe from the main to  the
 curb line  and a four-  or six-inch upper lateral from the  curb to
 the .building.  There are approximately 105,000 service connections
 in  the system, for an average lateral density of 13 per  1,000 feet
 of  main.

 RII Documentation

 During the earlier SSES work flow monitors were placed at key pump
 stations and bypasses throughout the  CSD area.  The flow monitoring
 and subsequent field work indicated what was believed to be inflow
 resulting from direct cross connections to storm sewers,- drainage
 crossings, and manhole leakage.   The PWWF  (hour) to  ADWF (day)
 ratio ranged from 4 to 8 depending on the District. The peak flows
were projected to a 6-inch, 24-hour duration storm.

 Follow-up  investigations  of  the early  SSES  work "'showed many
 inconsistencies between the data and  the results presented, so  new .
 field  work was performed in four pilot areas  in  the  CSD  service
                               c-25

-------
                             Case Studies
  area,  containing 93,000 feet of sewers.  The majority of the field
  work conducted in the pilot areas was smoke testing since it proved
  52*22. m°?   ®JfeCt:LVe  durin9 the earlier SSES  work for  finding
  22£?i in  I    5*wers-  The  results  of the  smoke  testing  in
  S2JSJ lar  showed.  * dramatic  increase  in  the number of  Snoke
  testing  returns  than had been detected  during  the earlier  SSES
  IS?'  +."2*  tPpr°Ximately 16  Potential  cross  connections.  The
  estimated potential peak day I/I flow from each pilot area  was 2 .3
  to 2.8 times the estimate of the  earlier  SSES work.
  o™*       6,°R,  *ef??*s  we.re  looted  during  the  pilot program
 compared to  157  in th. earlier  SSES  for the  same areas tested. The
 greater than two times increase  in  the I/I  flow estimates for the
 pilot  areas may  be  attributable  to  the  differences  in  field
 procedures  and  that  the  1988 field  work  was  conducted during
  *°^ht condlti°ns. Drought conditions provided the maximum dryness
 .  Se S?I:L' allowing more smoke to reach the surface from defects
 in the pipes.

 Each smoke return  was  classified by type and location of defect,
 and amount of smoke observed. Based on the three observations, th4
 defect was then assigned an estimated I/I flow value that was used
 to calculate the estimated peak flow for each pilot area. The data
 was summarized to  show the percent of leaks detected and percent
         for*ributed by  main line,  service line  (laterals) ,  and
 manhole leaks. For three of the four pilot areas, the estimated I/I
   °,WfL   m •the sewer mains and  laterals were 85 percent or greater
 and the fourth area had  63 percent from the mains and laterals. The
 estimated I/I from the laterals ranged from 9 percent to 58 percent
 with an average value of 32 percent. Based on the information from
 3?16*.?     areas, the main  lines contribute the majority of the I/I
 to the collection  systems,  with the laterals also contributing a
 SS?J?S?"^ Portion of the I/I. The majority of the defects found
 during the pilot program appear to be from Rll with only 16 defects
 suspected of being direct  connections.  The  earlier  SSES  work
 apparently  included  both direct connections  and indirect  flow
 transfers in the inflow estimates.

 Television and manhole inspection of the sewers during the earlier
 SSES   work  concluded  that  the  mains  were  generally  in  good
 structural condition except at the joints.  The pipe joints in many
 cases were offset or open,  and lateral  connections to the  mains
 were  often cracked, protruding,  or otherwise improperly' sealed.
 To  date  no  television  inspections have been performed on  the
 laterals  to  determine structural  condition.

A  site visit was  made  to  Baton  Rouge during  the  course of  this
study,  and City staff  and consultants were interviewed regarding
RII problems in the sewer system. With respect to the  condition of
                               C-26

-------
                           Case Studies
the sewers, those present  identified mains and laterals as being
the primary  sources of RII  in the collection  system.   Specific
problems  are  connections  between  the  lateral  and  the  main,
connections at  manholes,  and  location  of sewer  lines  either in
easements or alongside drainage ditches. Roots are a common problem
in the Baton Rouge area, particularly in easement  areas. The roots
expand the size of a defect once the root has made  an entrance into
the sewer. Based on the types  and locations of smoke returns, it
would appear  that  soil  channels to the sewer .defects  may be the
primary RII pathway. The French drain effect of the backfill in the
trench was felt to be of minor significance except in local areas
where the predominant soils are clay.

The smoke testing in the pilot  areas found many  cave-ins above and
next  to  sewer mains ranging in  size  from  6-inches  to  over
24-inches. Defects  of this size adjacent  to drainage  ditches or
along  curbs  and  gutters  allow  large  amounts of  RII into  the
collection system.  The City  currently has no routine maintenance
program other than responding to emergency problems.  The current
backlog of over 600 defects and cave-ins means that only the worst
defects can be addressed. City staff felt that a good maintenance
program would greatly aid the reduction of .RII in the system.

RII Control Program

As a  result  of the early SSES and subsequent cost effectiveness
analysis,  limited  rehabilitation  work  was  performed  but  no
reduction in  I/I flows were  noted.   The current pilot program is
currently in  the  design  phase to rehabilitate  all  the main line
defects identified during the field testing program.  At this time,
City  staff  projects that a  40 percent reduction in I/I  will be
achieved using this type of  rehabilitation approach.  The City is
also looking into expanding the current rehabilitation program to
include work on the service laterals.

Rehabilitation techniques  used in the past  in  the  CSD area have
consisted of most of the currently available techniques including,
slip-lining, inversion lining and pipe replacement. Rehabilitation
techniques being  considered  for the pilot program  include point
repairs,  pipe  replacement,  slip-lining,   and  manhole  sealing.
Results  from  the pilot program  are anticipated  to  be available
within a year.                                          .

The City has re-assessed its approach to I/I and feels that a long-
term solution is required to properly achieve long-lasting results.
The early SSES work  performed by  the city was copducted  in a
compressed time  frame and the results  could not be* verified or
repeated. As part of the City's overall plan, all wastewater from
the suburban areas will be treated and disposed of at either the
                               C-27

-------
                            Case Studies
  t« £f  a™?t  ^stewater treatment plants to eliminate discharges
  to the  Amite River  Basin. Also  one  of the  goals of  the I/I
                 am    ^ elimination of at least 40 knSwnbypasi
 Impact of Peak Flow on WWTP Operations
 ^^^y-,^erate-,S-, three main wastewater treatment plants and has
 another  144 smaller  wastewater treatment  facilities  within its
 jurisdiction.  The three main plants discharge to the Mississippi
       S"    S smaller plants discharge to stream and sloughs in the
       River Basin. The three main WWTP's are the North CSD, central
            S°Uth  CSD  Plants'  the  smaller wastewater  treatment
   ™       a/e referred to  as the "suburban plants". A  brief
 discussion of the operation  of  the three main plants follows.
 ?«rth^C?D*WWTP- The North CSD Plant was Decently rehabilitated and
 upgraded from primary to secondary treatment with a design process
 capacity of 8 mgd and a hydraulic capacity of 23 mgd. To date all
 wet weather flows that  reach the  plant can be trelted.  The plant
 nas been designed to allow bypassing of peak flows in excess of the
 23  mgd  peak  capacity.  Some bypasses  exist  upstream  in  the
 occodH-          -     t0 bypass plant flows  has
 occurred. The pro} ected design  (year 2010) peak hour wet weather
 flow to the plant is about 47 mgd.

 Thf ?inal effluent limits for the North CSD plant are 30 mg/1  BOD
 and 30 mg/1 TSS.  The plant has just come on line  recently  after
 being upgraded from  primary treatment  only.   The new process  at
 this plant uses trickling filters to achieve  secondary standards.

 A£WFC«? ?«VDTv, f °r ,the. P-lant is about 6 *9d- The Stal  PWWF  to
 ADWF ratio for this plant is projected  to be  7.

 The major cost associated with treating the wet weather  flows  is
 increased labor  required to operate the  plant under peak flow
 S?« ?• i°nSl P°Wer costs do  not increase significantly since the
 final discharge is a  gravity outfall.   Chlorination use  is also
 increased and  therefore is more expensive than during dry weather
 flow operations.

 Central CSD WWTP. The Central CSD plant was constructed in i960 and
 upgraded  to secondary treatment in 1978. The secondary portion  of
 the plant has a  process capacity  of  20  mgd,  and  the'  overall
 hydraulic capacity of the  primary section of the plant is  40 mgd.
 Current operation of the plant during  wet  weather  is to  process
SS^?«L 2° -"?* 23  **d through  the secondary  system  with the
remainder  of the  flow  receiving only  primary  treatment.   The
influent flow meter  to  the plant  peaks  at 40 mgd, but City staff
are certain that higher  flows have come through the system.  Peak
                               C-28

-------
                           Case Studies
 projected flows for the Central region are approximately 55 mgd,
 and bypasses do occur in the collection system. Current ADWF at  the
 plant is  15  mgd.  The  ratio of  PWWF to  ADWF for  the  plant  is
 approximately  2.7.

 Discharge parameters for the plant are the same as  those for  the
.North CSD plant. Even during wet weather the seven day averages  for
 both  BOD  and  TSS  have been met  without difficulty.  The !basic
 secondary process  flow  train is a high  purity oxygen  activated
 sludge system with  secondary clarification. Secondary effluent  BOD
 during  peak flow is sometimes  high due to  solids loss over  the
 weirs at the clarifiers.

 The costs associated with operating the treatment plant during  wet
 weather  consists of increased labor and power costs. Final effluent
 is  pumped to  the Mississippi River  for  discharge.  Higher flows
 increase chemical costs particularly  for oxygen and  chlorine.

 South CSD WWTP. The South CSD treatment plant was constructed in
 1962  as  a primary  plant  and is  currently  being upgraded to a
 secondary process.  The secondary process will consist of  trickling
 filters  to bring the final effluent into compliance with  discharge
 requirements.  Discharge requirements are the same as those for  the
 North CSD plant.  The ADWF  for  the plant  is currently about 14.5
 mgd;  the  PWWF  to  ADWF  ratio is approximately  3.5. The current
 capacity of the plant is 16 mgd, and the plant can handle up to 30
 mgd peak  flows.  The 30  mgd peak flow limit is caused  by  the
 limitations of the  effluent pumps.

 Three major bypasses exist upstream of the treatment plant, so true
 peak  flows in  the collection system never reach the plant. Other
 than  the effluent  pumps, the hydraulic capacity is estimated at
 greater  than  50 mgd. When  the  suburban area connects to the  CSD
 system the majority of the flow that went  to  the many small  plants
 will  go  to the South CSD plant. This connection is scheduled to
 take  place by  1994.

 The costs associated with operating the treatment plant during  wet
 weather  flows  are  labor and  power with some additional cost  for
 chlorine.  With the secondary treatment plant on  line, the costs
 should not increase significantly for wet  weather flows,  since  the
 plant, will have trickling filters  for the  secondary  process.
                               C-29

-------
                          Case Studies
  CITY OF SPRINGFIEIJD, MISSOURI
     S ?    Springfield is located in southwestern Missouri. The
 wastewater service area is divided into two main drainaae bas

 JfV6^ by a seParate WWTP-  The larger of  the twogSasiS
 the Southwest area, which includes approximately 80 percent of

     '              1
 ovmle
 plople.            sanitary sewers serving  approximately  160,000
 5i??lef? due to  I/Z  include  surcharging and overflows  in the
 collection  system and  basement  flooding.  Overflows  occur  a?
 approximately ten sites during  any good-siled stlrm and a? ?So '£

 SrL^^n%lUrin? large rai"f^l events. Durln^the period ?957
 SSrSS r/-?3-' ^f C±ty conducteI—SI
                                               *

                            C-30

-------
                           Case Studies
Although the perennial groundwater table is at least 25 feet deep,
about 30 percent  of the area is characterized by a perched water
table which rests atop the bedrock or impermeable fragipan. Sink
holes and crevices in the limestone create underground passageways
for water.  Average annual rainfall is approximately 41 inches, with
May and June being the peak rainfall months.   The area experiences
both localized thunderstorm-type events, as well as more general,
longer duration storms.

The original  sewer system was constructed during the period 1894
to 1911. Roughly half of the sewer  system is  constructed of older
type VCP with mortar joints and brick manholes. The remaining half
of the  system has  been  constructed over the past  30  years with
newer,  improved joint materials  and precast concrete manholes.
Service  laterals   are  generally of similar  construction  as  the
mains.  The sewer  mains are  typically six  to eight  feet deep;
therefore, a substantial portion of the sewer trenches extend into
the bedrock.  Only a small portion of the City is served by a storm
sewer system.  Surface drainage is  generally carried by overland
flow along street gutters,  ditches,  and natural drainage channels.
Roughly 20 percent of the buildings in the  City have basements and
foundation drains.
         /   •   •              _  . .        ,        '.'•-,•--,.

RII Documentation

I/I flows  within  the  sewer system were documented  through flow
monitoring during  the  SSES,  which  was completed  by City staff in
1980. Ten areas of the system were  selected for monitoring, based
on known I/I problems. For the measured storms, maximum daily wet
weather  to average  dry  Weather flow ratios for  the  individual
monitored subareas ranged from about 5 to 20.

The field investigations conducted  during the SSES included smoke
testing, dye  flooding,  and  manhole inspection.  The smoke testing
and dye flooding  identified relatively  few  sources,  primarily
because direct inflow connections (roof and yard drains)  had been
identified and corrected under  previous programs.   Some indirect
connections between storm and  sanitary sewers were  located  and
corrected,  and some smoke returns were observed from sewer mains.
It was generally felt that the soil  may  not have been sufficiently
dry to  detect r pipe defects in mains and laterals.  The manhole
inspection  work  primarily  identified sources  of  infiltration
through manhole walls and inverts. Television inspection conducted
since 1966  throughout the  system  with the  City's  own equipment
identified lateral  taps  and laterals with clear water discharges
(from lateral  defects or foundation drain connections.) as specific
sources of infiltration.                             •
                               C-31

-------
                             Case Studies
  Although specific  flow estimates based on  source  detection work
  were not  developed as part of  the SSES,  the I/I Salylis  did

  vSSX  ?°^;nt^Y the total flow Contributions from dTreSTnflow
  versus  infiltration sources.  Estimates  of direct  inflow  were

            5?Se? °n the observation  of  rain-induced I/I flo^s fo?
            thunderstorm-type  events  during  relatively  dry  soil

             ^Vh*St  12?MMI  °f  St0rms'  it: was  observed that  a
             *X£  PSak  fl°W  was  reached  in direct  response  to
  It  ws  »«SLS he peak  receded quickly after the rainfall stopped.
  It  was  assumed  that this  response  was due primarily to  direct

  ~fi°W11SOl";CeS'  and a relationship  between  inflow  volume  and
  SS??li rf.^.^s^yeloped.  This  relationship  was then used to
  quantify the  direct inflow  portion  of the-  flow for a  large,
  5aS ?n»«?Sf Ja:L.nsto,rm  filing under saturated soil conditions . It
  oS J! ^?   at direct mflow could account for approximately 40 mgd
  of the 84-mgd peak flow. However, the flow was sustained at nearly
  raLSf?ik i*ya'J* infiltration alone for several hours aftJr  the
  ™v ~   -,£ ad  stopped and direct  inflow subsided. This sustained
  peak could not be accounted for as storage in the system. Rather,
  it was  theorized that  during the initial  peak storm period   the
                                     its peak flow rate dniy after
                       also analyzed the flow trends in the system
  ^ing,.the  P^ious 13 years.   It was found that both  I/I  as a
 percentage  of total  flow and  as a  percentage of  rainfall had
 increased steadily over that period.  The increlsed severity of I/I

 *a J^ribU*ed,,t0 b0th dete*ioration of the existing sewer system,
 a»™?i  v,aS .inadre/(^ate quality of construction of new sewers. On aA
 a^?i,-bafXS' T/\ Was cal.culated to be about  15 percent of total
 precipitation and approximately  25 to  30  percent  of  effective
 precipitation (total precipitation minus evaporation) .

 Factor  affecting Rll in Springfield may  include inadequate storm
 drainage and the hydrogeologic characteristics of the area. Because
                                                         .
                             WhiGh exists in many Potions  of the
             •     Slnk?°ieS  and  crevic«s  characteristic  of  the
                      bedrock' storm water can  easily and rapidly
Ai-ho            -r and lateral trenches and foundation drains.
Although  most buildings do not have foundation drains,  a  single
RII Control Program
The City has conducted sewer grouting since 1972,  particularly in
older areas of the system,  with little success in reduSig peak wS
weather flows. As part of the SSES, a pilot rehabilitation pro jlct
                               C-32

-------
                            Case Studies
 was conducted in a newer area of the City  (sewers constructed after
 1968) which experienced very high  flows  during rainfall periods.
 During a three-day heavy storm period prior to rehabilitation, the
 total flow volume was nearly seven times the  normal  dry weather
 flow. Manholes  in the rehabilitation area were  inspected during
 this  storm   period,  and   those   that  exhibited   significant
 infiltration were subsequently sealed.  The sewer main joints were
 air tested and grouted if neqessary; however,  most of the joints
 were found to be tight. During TV inspection, it was noted that
 many laterals  were  discharging  clear water  flows;   however,  no
 lateral rehabilitation was conducted as part of the project.  The
 results  of  the  pilot  project   indicated  that  although  the
 infiltration through the rehabilitated manholes had been reduced
 or eliminated, the rehabilitation efforts  had had negligible effect
 on the  flows from the overall area.

 Since the SSES,  the city has allocated approximately 10 percent of
 its  annual  sewer  budget  for   rehabilitation work,  primarily
 slip-lining  of   isolated  problem  sewer  reaches.     Ongoing  TV
 inspection is used to prioritize areas for rehabilitation.  City
 staff believe that grouting  has  been ineffective  in reducing RII,
 primarily because of migration  of the RII to other sewer defects
 and  to   laterals.  In  general,  they  feel  that  sewer  system
 rehabilitation is not cost-  effective on  a large scale basis.

 Impact of Peak Flows  on WWTP Operation

 The existing Springfield Southwest WWTP is an  advanced secondary
 treatment facility with nitrification, effluent filtration,  and
 ozone disinfection  with discharge to Wilson  Creek.    Effluent
 discharge limits are 10/10  mg/1 BOD  and suspended solids and 2 mg/1
 ammonia.  The plant utilizes equalization  basins during peak flow
 periods.  Under high flow conditions, however, the plant sometimes
 experiences  problems  meeting the  suspended  solids  and  ammonia
 discharge limits.  Currently, the equalization basins have limited
 capacity  during  extreme flow events.  The  State of  Missouri  is
 considering  amending the City's  discharge requirements to  allow
 discharge from the equalization basins after some settling,  to be
 dependent on stream flow and stream water quality.

 NORTH AND SOUTH SHENANGO JOINT MUNICIPAL AUTHORITY,
 PENNSYLVANIA

 The North and South Shenango Joint Municipal Authority includes the
 Townships of North and South Shenango, located along the shoreline
 of  Pymatuning  Reservoir  in  northwestern  Pennsylvania.    The
Authority  operates a  collection  system  and  treatment- plant which
 serve a permanent population of about 1,200 and a summer population
                               C-33

-------
                            Case Studies
                            ^^

































System Description
                              C-34

-------
                           Case Studies
 Because of the high groundwater and the fact that North and South
 Shenango are largely resort  communities,  few of the houses have
 basements.  Therefore, many of the laterals are as shallow as three
 to four feet below the  surface.  Storm drainage in the communities
 is by ditch system.,Many of the sewer mains  are  located directly
 under ditches or gutters along  the  side of the roadways.

 RII Documentation
        ' • '"            ,"•-•-     .      ,-     '     4-    t   ''   '
 Field work in  the collection system was  included in a Sewerage
 System Evaluation conducted in connection with the litigation over
 the pipeline construction. The field work included flow monitoring,
 flow isolation, groundwater monitoring, and limited smoke testing.
 The major  focus of the  field work was to isolate  and quantify the
 infiltration in  the differeht  pipeline contract  areas,  and  to
 determine    the   relationships   between    groundwater   level,
 infiltration,  and precipitation.                                 ,

 Groundwater monitors were installed in  sewer trenches  at 144
 locations  in the collection system. These monitors were designed
 to measure the hydrostatic head over the pipe in the trench.  In
 addition, shallow wells were drilled at four locations adjacent  to
 sewer trenches  to document the differences  in water level between
 the trench  and  the undisturbed soil around  the  trench.

 The groundwater monitoring information was used to develop maps  of
 groundwater elevation contours at different points  in time  and  to
 identify areas  where the sewer system was submerged. In general,
 the groundwater levels were highest in early  spring and  decreased.
 during the  summer.  A considerable portion of  the sewer system was
 found  to  be  submerged  during the  spring  and  early summer,
particularly  in the western portion of the service area near the
 lake. Comparison of the  groundwater data in the eastern and western
portions of  the  system  indicated  that  the  east-to-west  sewer
 trenches appear  to drain the  groundwater from  the undisturbed
 natural soil  in the eastern portion of the area and transport  it
 in the trenches toward the western portion of the area via a  French
 drain effect.

At  several  of  the  groundwater  monitoring  sites,  continuous
 recorders were  used to  monitor  the  response of groundwater  level
to precipitation.  Data from the recorders showed that water level
 in the  sewer trench can increase rapidly in response to  rainfall.
Increases of three feet  (the limit of monitoring) within^ a few
hours of the  onset of rainfall  were recorded at sites throughout
the  system. Water  levels seemed to be  the most  responsive  to
rainfall during the winter and early spring,  and also'-responded  to
the daily thawing and snowmelt which occurred during parts  of the
winter- Sewage  flows, as measured by flow monitors  in the system,
                               C-35

-------
                             Case Studies

   d          Study' . measurements  were made  of infiltration  from
 SSSS2   •    f r plpe ?oints at six locations in  the system.  This
 procedure  involved isolating the joints with a packer assembly and
 quantifying  the  infiltration  rate under a  range of  piezomltric
 heads   (measured as  the  differential  between  the  piezometric
 pressure  in the trench and the  inside of  the  sewer PpfpeT   SS
 infiltration rate  clearly  increased as  the  head  differential
 increased, with  rates ranging from 10 to as high as 2,600 gpd.   The
 magnitude  of the infiltration response varied  from location to
 location*
      i i      ?iat y-**1** infiltration rates were observed in sewers
 installed in trenches underneath ditch lines. Many of these ditches
 have been  observed to  be  flowing with water  over  one foot deJp
 "IS S™  ^?S/^Whl*h,Can easily Percolate into the disturbed soil
 S2oPSSfSf t ba1Cliflll1  mat^ial  in the underlying trench.  It was
 S  rSSSi^?  laterals and lateral connections did not appear to
 be  contributing   significant   extraneous   flows,   based  on  TV
 inspection conducted in  conjunction with subsequent rehabilitation
 Vr O JTJC •           -                                         ' •

 Because the sewer system  was constructed  so recently,  it  is
 unlikely that any  significant  direct inflow sources  exist  in the
 system.  This was  confirmed by  limited smoke  testing that  was
 ?£?d™ =, f °r thS .f t?dll' in Wh±Ch  °nly One Potential surface water
 S?S ~J ource was detected. Therefore,  it can be concluded that the
 »iS «£  wf ather f lows in «ie sewer system are due to infiltration,
 and the flow increases  during  rainfall are  due primarily to  the
 increase in infiltration into  defective sewer  joints  as  a  result
 of the increased groundwater level in the sewer trenches.

 RII Control  Program

 As part  of the  work to evaluate methods to  solve the  infiltration
 problems in  the sewer system, some sewer grouting was conducted in
       8*1   The gr°Ut  aPPeared  to  seal  the  joints  internally,  but
                  noreduced-   » is  believed that the- .inherent
            H                                            - .
   SiSf ^   the ^oint compression rings made grouting ineffective
   preventing leakage  due to  external hydraulic pressure.

A Pilot slip-lining project was performed on 1,400 feet  of  sewer
         86"1'  Yith  flow  monitoring  before  and' after the
             11-  W°£   ^ ^esults  of the project indicated that
              in the slip-lined sewer was  completely eliminated
                               C-36

-------
                           Case Studies
through the rehabilitation work. As a result of the settlement of
the construction  litigation, the Authority is now slip-lining all
of the mains and slip-lining  or replacing the lower laterals in the
four problem  contract areas. Due to the  lack  of rain this year,
evaluation of the flow reduction resulting from the rehabilitation
work  has not  been completed,  although early  results indicated
substantial reductions in those areas rehabilitated in March 1988,
prior to the drought period.

Impact of Peak Flows on WWTP Operation

The North  and South Shenango WWTP is,.an  activated .sludge  plant,
which was  designed for an average flow of 1.2  mgd and a maximum
flow  rate  of 3.0  mgd.  The  plant  consists  of  three  separate
400,000-gpd contact stabilization units.  It was envisioned that
only  one  unit would  be  operated in  the  wintertime,  and  the
additional  units  would  be  put  into  operation  to  handle  the
increased  summertime  population.  Although the current wintertime
service  area  population  is  less than  15 percent of the   design
maximum  population, this  high  flows  in the  system to  date have
forced the operation  of  all  three process units, even during the
winter months.  Since  overflows and bypasses occur in the  system
during peak  flow conditions, the current testa!  peak wet weather
flows cannot be measured,  and  the entire  flow does not reach the.
WWTP.

During high flow periods, the influent is so dilute that it often
meets  the  discharge  limits for  the plant  effluent. The major
problem, aside from lack of  available capacity for future growth,
is  that  the  plant  cannot meet  the  NPDES  permit  treatment
performance requirements for 85 percent  removal  of  BOD, due  to the
extremely dilute  influent. The plant  has  also  been flooded out a
few times due to the high flows.

CITY OF AMES, IOWA

The City of Ames, Iowa,  is located in central Iowa along the Skunk
River. The collection  system  and treatment plant serve  a population
of  approximately  45,000,  including  the  Iowa   State University
campus, which comprises  almost half  of  the total population;  The
collection system contains approximately 135 miles of sewers.

The City conducted an I/1 Analysis and SSES during the late  1970's
in conjunction with a facilities  plan for expansion of the WWTP.
During wet weather .periods, the plant cannot handle the peak flows
in the, system, and  the  influent sluice  gate  must be,throttled to
limit the  flow  entering the plant, often for as long as several
days. Several  times each  year during extremely  wet conditions,
bypassing of raw wastewater occurs both at the plant and at several
                               C-37

-------
                            Case Studies

 System Description
           I situated Primarily on the uplands surrounding the flood
  ol      ^°HriVerS* The toP°^phy varies from level to s?igh??y







                        as
 The sewer system ranges from new to over 80 years old. Most of the

 X25? £0rti°n °f System is Concentrated in two of ten su?sy2tems
 About 40 percent of the collection system is over  30  vef?s  old*























shallow plastic line to the  street curb or  yard  However  it iS


                  wta  dlsoha ^
                    .                          -          S
                                         winter during  freezng
                              C-38

-------
                            Case Studies
 RII Documentation

 The I/I  Analysis and SSES  field work included  flow monitoring,
 smoke testing, dye flooding, manhole inspections, flow isolation
 and TV  inspection.  Smoke testing and  dye flooding were  used to
 identify  direct inflow  sources  and  sources  of  indirect  flow
 transfer from storm  drains to sanitary sewers. Manhole inspections
 12f" •   ea sources  of direct  inflow through manhole lids.   In
 addition,  a   foundation  drain  study  was conducted  to  provide
 documentation of the I/I  flow contribution from foundation drains
 directly connected to the sanitary sewer-system.

 The foundation drain study included a survey  to locate foundation
 drain connections,  and measurements  of  foundation  drain  flows
 durinig  rainfall and  rainfall simulation.  The  survey included over
 8,500  buildings  and  identified  over  1,800   foundation  drain
 connections to the sanitary sewer system. These included about 100
 •wet basements11 with no foundation drain,  but where water  flowing
 through cracks  in the basement walls  enters the sanitary  sewer
 .through the basement drain.  In addition,  another  1,600 foundation
 drain sump pumps with normal discharge to the ground  were found
 Many of these have valving  capability  to divert flow to  the  the
 sanitary  sewer  during   freezing  conditions.   Presumably,   if
 homeowners neglect to switch the discharge back to the yard at the
 end of  winter,  a portion of these  foundation  drains would  also
 contribute flow  to  -the sanitary  sewer system during peak  flow
 conditions in the spring.

 Running  time  clocks were  installed oh 12  foundation drain  sump
 pumps over a  one and one-half  year period.  The locations were
 selected  to provide a representative range of  soil and  groundwater
 conditions, and included  locations where the  sump pumps ran  only
 during; extreme wet weather periods, as well as locations where the
 foundation drain was active continuously except tinder  extreme  dry
 weather conditions. The data from the sump pump pumping study  was
 used to project average flow rates for different design  conditions.
 For  the  .one-hour  maximum  flow  condition,   the  average  flow
 contribution per foundation drain was estimated to be  5.6  gpm.

Rainfall  simulation   was  conducted  for  seven  foundation drain
 locations. The testing was designed to simulate a  1 in/hr. rainfall
 (estimated two-year  recurrence  frequency).  For two of the sites
in  which  the  lots sloped  away from  the house,  no response  was
detected and the testing was  discontinued  after 30 minutes.  (These
foundation drains were normally  active  during wet weather.)   For
                              C-39

-------
                            Case Studies
 approximately 50 percent of the applied flow rate.


 Based on the results  of the SSES field work and

                SoSST  *evel?>?d of  the  «~           on
                sources. Direct inflow was estimated to account for

    n           -4°  Percent   of the  maximum Sur  i/i  |?oSf f Sd
 foundation drains  were  estimated -to contribute  about  50
 The proDected PWWF is estimated to be about six times
 SnL^h?^ t f los? in the svstem typically occur during the  spring
 under high groundwater and saturated soil conditions resulting from
 successive rainfall events.  The response of foundation drains
Cstaf  hav «         ,            -      Under «oo
city staff have observed that soil shrinkage may pull the soil awav

  °a     ?ai1S'<> which.may ^ one facto? in the rapid rale
                into foundation drains.  The factors tha
                                          The factors that affect
                                           $£* ata£s
                         -     cons truotion-  iocati™ ~
 RII Control Program
            Pfrf-?d since the SSES' «» City has completed much of
    .ita?i01? W°rk that was determined to be Sost effective
Sd  «fJf   Analysis primarily correction of direct inflow slurceJ
and  some sewer  rehabilitation.   About  two years ago,  the  Cit?
initiated  a foundation drain disconnection  program!  targeted at

SJKS*1^!? ?68  found.ation drain  connections 9over  a  ttn-year
SS?2;   / fi:091?* includes  Provisions  to  reimburse a  l™
portion  of the  homeowners'  disconnection  costs.     TO  date

ai?SnSaSely   3°°  *oundation   drain  connect?^  havl   be^A
?i ^   ^" ^Vn entlrely voluntary basis.  About half of these are

in aSarwfthe1 ai?aS' rj1* Priority f0^ disconnection being pfaSI
Jh4  A     listing storm drain facilities. The City anticipates
that  the   program  will   continue   beyond  the  required   768

SfSSTSS?-* N°  f°110W-!P flow ^nitoring has  been^conducted?

and basLSfL053^^ a decrease in «» "-bir- of complaint
                              C-40

-------
                            Case Studies
 Impact of Peak Flows on WWTP Operation

 The existing WWTP, constructed in 1950,  iss a single-stage trickling
 filter plant  with van design  average flow  capacity of 2.2  mgd.
 Although flows in excess of design capacity have been effectively
 handled at  the plant, peak  flows exceeded about  8 mgd must  be
 bypassed.  Current average flows are approximately 5 to 6 mgd,  with
 peak hour wet weather flow rates estimated to be over 35 mgd. The
 current WWTP  expansion  will increase design  capacity to 12 mgd
 average,  20 mgd peak day, and 34 mgd peak hour  flow,  utilizing a
 two-stage trickling  filter/solids contact process and equalization
 basins to handle flows in excess of 20  mgd.

 Generally, the existing plant can achieve 80 percent removal of BOD
 and suspended  solids*  During high flows, plant efficiency drops  to
 55  to 60 percent. Other problems which have been experienced during
 high flows include  hydraulic  washouts,  carryover of  solids, and
 digester upsets due  to fluctuating solids  loadings.

 CITY OF COOS BAY,  OREGON

 The City of Coos Bay is  located  on the southwest coast of Oregon.
 The City is divided  into two main sewer service areas,  each served
 by  a separate WWTP.  The major  I/1 problems are concentrated in the
 collection system tributary to WWTP No. 1, which serves the eastern
 portion of the  City and the adjacent Bunker Hill  Sanitary District
 outside of the  city.   The  Coos Bay wastewater system serves a
 population of  about  15,000 and contains  approximately  78 miles  of
 sanitary  sewers  (not  including  tributary districts).  The sewer
 system  is primarily a separate system,  although a small portion  is
 believed to be partially  combined.

 Problems due to high peak wet weather flows include bypassing and
 overflows  in the collection system, as well as  raw sewage bypasses
 and discharge  requirement violations  at WWTP No. 1. In 1971, the
 City  completed a comprehensive  sewerage study,  which  identified
 I/I  as  a major problem in the collection  system.  From the early
 1970«s  through  1982,  the City  conducted  source  detection  and
 rehabilitation   work  to  reduce   I/I.  The   program  included
disconnection   of  known   direct  inflow connections,  including
downspouts and  cross connections with  the  storm drain system, as
well as sewer main rehabilitation. However, despite the
                               C-41

-------
                            Case Studies
  rehabilitation program, the system still experiences high peak wet
  weather flows. Since smoke testing has confirmed that almost all
  direct inflow connections have been eliminated from the system,  it
  is believed that the majority of the peak rainfall  induced  flows
  are  due  to  infiltration  into  sewer main  and  service  lateral
 System Description

 The  City is located on  a peninsula surrounded by  Coos Bay  the
 largest  estuary  in  Oregon.  The two  sections of  the  city are
 situated  on  the eastern  and western sides  of the  peninsula.
 corresponding  to the WWTP  No.  l and  WWTP No. 2  service areas
 respectively. The topography is characterized by rolling foothills
 with elevations  varying  from sea level to  500 feet.  The flatter
 SS*8!?**-1?0?^ near the edges of the estuary. Soils are marine
 and alluvial deposits, primarily sandy loams with greater amounts
 ™LS* ^jand clay in the  eastern  (WWTP  No.  l)  area,  including bay
 mud in the downtown area near the estuary.  A large portion of the
 older area of the City is located in a tidal basin and constructed
 on dredge spoils  (fill) .  Average annual rainfall is approximately
 62 inches, with  75 percent  of the rain falling during  the period
 November through March. Groundwater elevations near the estuary are
 very high and influenced by tidal fluctuations.  In other areas, the
 groundwater level is typically below the sewers for most of the
 year, but increases during the winter rainy season.

 T5eJtewef.fystem was originally constructed in the central portion
 ?L*   Jrlty  
-------
                            Case Studies
 RII Documentation
 JSrJK ^    P    monitoring at 34 locations and wet weather flow
 mapping  (early  morning flow measurements taken  at key manholes)
 ™rnd. as part of a Facilities Plan Supplement completed
              d  ference Between wet weather and dry weather flows
               *^®^"-11**11 dePei»dent flow,  and ranged from zero
      *           *  he  34 subbasins- The projected  peak rainfall
 dependent  flow  for  a  five year design  storm was  calculated,
 resulting in a projected PWWF  of  about 14  mgd and a PWWF to ADWF
 ratio of about 8 to 1 .     ,

 Extensive smoke  testing was conducted during the period 1972  to
 1975 as part of the sewer system rehabilitation program. Although
 the^ primary objective  of the smoke testing was to  locate direct
 inflow sources, many leaking service laterals also exhibited smoke.
 TV inspection identified problems in sewer mains due  to leaking
 Doints and  root intrusion.  In areas near  the estuary,  ground
 settlement has  caused considerable  pipe  movement,  resulting  in
 cracks, breaks,  and  offset joints in  the   sewers  and  service
 laterals .

 Based on the previous elimination  of all identified  direct inflow
 connections  and the known poor condition of the sewer  system,  it
 can be concluded that the peak wet weather flows in the Coos Bay
 system are primarily  due to RII.

 RII Control  Program

 In previous years, the City has completed rehabilitation  (primarily
 grouting and some replacement)  of  sewer mains  with major problems
 identified through  smoke testing  and  TV inspection.   No work  on
 service laterals  has been conducted.   Although the basic approach
 to addressing the wet weather flow problem  in  the system consists
 primarily  of expansion  of the WWTP,  the City  has  instituted a
 program of  routine  TV  inspection  of  the  sewers  to  identify
 particular areas  in need of repair or  replacement.

 Impact  of  Peak Flows on WWTP Operation

 The existing Coos Bay WWTP No. i is a conventional activated sludge
 treatment  facility  with a design  average flow of 2.66  mgd and a
maximum hydraulic capacity of 5.85  mgd.  in  addition to  raw sewage
bypasses, the biological  process is  frequently upset by  hydraulic
overloading, resulting in solids washouts. A split stream treatment
scheme  is  practiced,  which  -provides  primary  treatment  with
disinfection to all plant influent flows and secondary  treatment
up  to  process design  limits.  This practice has  been relatively
                               C-43

-------
                            Case Studies
             .atF1meeting Affluent  discharge limits  except  during
          high flow conditions. Salt  water shock loads that  upset
          ??era£10n .ha,Ye al.SO occurred at the plant,  believed to be
       r,»l    ^ infl°W  int-° Storm  sewers  through  malfunctioning
       g  ™  tnd  P"*"8*0"* infiltration  into  the sanitary  sewel
         • t tre?3"61*  Plant is currently  being expanded to handle
        •                                                         e
Jrr?, f rejected five-year  storm design peak  hour flow  of 14 mgd
utilizing  a  similar split-stream process scheme during peak  flow
P^ZTxOdS *

CITY OF TULSA, OKLAHOMA


A^a«CitY r,°f  TulSa is  located in  northeast Oklahoma  along the
Arkansas River.  The wastewater service area  is  divided into two
main drainage basins, referred to as the Northside and Southside
?£« «««*   The  total  service  area   population   is  approximately
              *** collection s
     «««                                                     aey
 sewer m4i     ***  collection system includes over  1,400 miles of


 The City has conducted SSES work in the sewer system since 1982 as
 part of overall facilities planning efforts and in order to reduce
 surcharging and overflows in the collection system during rainfall
 In subbasins determined to have excessive I/I,  SSES work has been
 followed by rehabilitation. In the Southside basin, SSES work was
 completed  in 36  of 41 subbasins,  and  rehabilitation has  been
 SSS?  S® -,fr  de^gned  for 17 subbasins.  In the Northside basin,
 SSwf^J- W°^   W3S  co?ducted   in  12  of  22   subbasins  and
 SS2S *5   i«2e.xn.8 f"1*351113-  Source flow estimates based on the
 Northside  SSES  indicate   that over  70  percent   of  the  peak
 rain-induced I/I  flow  is  contributed by infiltration  sources  in
 collection sewers, manholes,  and service  laterals.

 System Description

 The topography  of the .service  area  ranges from  flat to  gently
 sloping.  The area  is  generally characterized by shallow  bedrock
 ranging from 20  to 60 inches below the ground surface.  The bedrock
 consists mainly  of limestones, shales, and sandstones,  overlain by
 moderately to  well-drained  loamy soils  formed  from  materials
 weathered  from  the bedrock or  from  alluvial deposits.   In the
 eastern portion of the service area, the soils are typically tight,
 S£ansive  ?lay-fV Avera^ annual rainfall  is about 39  inches; th4
 highest rainfall occurs during the months of April through June and
 September and October. Groundwater levels are typically low.   Onlv
 scattered  areas  experience high groundwater, typically near the
rivers, and the maximum  seasonal groundwater levels are generally
not higher than  about six feet below the surface.
                               C-44

-------
                           Case Studies
 The oldest portions  of the  sewer system date to  the  early 1900's.
 About  one-half of the existing system was  constructed before I960,
 and the system has  continued to expand  through the 1980's. The
 sewers in  the system are predominantly VCP, with some concrete and
 plastic pipe. Cast iron or PVC laterals are most common,  with VCP,
 AC,  concrete,  arid  Orangeburg pipe in the older areas.   The,older
 pipes  in the system utilized tar,  jute, or cement mortar joints and
 were bedded and backfilled using native  soil  materials.   Newer-
 pipes  have been  installed with,sand bedding,  and since  1962 have
 utilized  molded plastic  or  rubber  gasket joints.  Manholes are
 predominantly brick and mortar construction, with precast concrete
 manholes being installed more recently in  some of the newer  areas
 of the system. In general, the manholes do not have vent holes. The
 sewers mains average about ten feet deep and are  generally located
 above  the  groundwater.  Service  laterals  are typically two and
 one-half  to six feet deep. About 90  percent of the sewers are
 located in backyard easements or  alleyways*

 RII  Documentation                       .         .

 Flow monitoring was  conducted at 24  sites in the Northside  basin
 and  46 sites in the Southside basin to determine  dry  weather  flows
 and  rainfall  induced   I/I.     In  both  systems,   dry  weather
 (non-rainfall) infiltration was  not  found to  be excessive,  which
 is consistent with the low groundwater levels in  the  service  area.
 Measured PWWF to ADWF ratios  typically ranged from 2 to  5, with a
 few  subbasins experiencing higher peaks. For the overall Northside
 and\Southside systems under projected design storm conditions, the
 PWWF to ADWF ratios  are  about 3.5 to l.  The rainfall induced I/I
 represents  about 70 percent of the peak wet weather  flow.

 The  field  investigations conducted as part of the SSES's  included
 extensive   smoke  testing,  as  well  as  dye  flooding,  manhole
 inspection, and TV inspection. Based on ttye data collected in the
 eleven SSES subbasins in the Northside basin, the predominant  types
 of I/I sources identified were leaks from service laterals,  sewer
mains,  cleanouts,  and  under manhole  frames.  Over  half  of the
 defects were detected as smoke  returns observed along the ground
 over service laterals and sewer mains. There were very few direct
 inflow  connections such as  roof  leaders,  area  drains,  or  storm
drain/ sanitary sewer cross connections.

Visual and TV inspections  were  conducted, to assess the overall
condition of the  system.  The TV inspection  data was used primarily
to  determine  appropriate  rehabilitation  methods,   and not to
specifically identify or quantify I/I sources.' Common deficiencies
observed during these inspections included offset joints, cracks,
and  root  intrusion.  Lateral taps  were   also  found   to   be  a
significant problem.
                              C-45

-------
                             Case Studies
            "                                                 "

RII Control Program

                              C-46

-------
                           Case Studies
 based on  the SSES  tests  were notified  and requested  to make
 repairs.  An overall 70 to  80 percent compliance was achieved  in
 many  areas.                                              j.cy«=u

 Flow  monitoring  was performed before and after  rehabilitation  in
 order to assess  the overall effectiveness  in reducing i/i -For
 eight Northsiide  subbasins in which rehabilitatibn was  performed,
 the  initial  reductions  in  peak wet  weather flows  ranged from
 approximately 30  to 90  percent,  with  an  average  of  about   50
 percent.                                          ^       ««wuu

 Impact of Peak Flows on WWTP Operation
The City  is served primarily by  two major WWTP's, Northside and
Southside.   Both are conventional  activated sludge plants, each
treating  an average  dry weather  flow of  about  30 mgd.  At the
Southside WWTP, the peak flow reaching the plant is limited to 50
to 60 mgd by pump station capacity.  Flows in excess of this amount
are bypassed to the Arkansas River.  The Northside WWTP has limited
equalization  storage capacity; however,  it is  insufficient for
handling peak wet weather flows.  All flows  which enter the plants
pass through all  treatment process units.  During very high flows
or prolonged high flow periods, washouts can occur in the secondary
treatment process.
                              C-47

-------
                                     APPENDIX D

                    SEWER SYSTEM REHABILITATION METHODS
  This appendix contains discussions on sewer system rehabilitation methods applicable for
  control of RII.  The appendk is divided into three sections:  Pipeline  Rehabilitation,
  Manhole Rehabilitation, and Foundation Drain Disconnection

  PIPELINE REHABILITATION
                                                               ;         '
  Rehabilitation methods for sewer pipelines are divided into two categories: (1) replacement
  by conventional and trenchless techniques, and (2) rehabilitation by grouting and by lining
  techniques, including slip-lining and cured-in-place lining. The methods described in this
  section are not all-inclusive; other techniques are currently being developed.

  The focus in pipeline rehabilitation today is on in-place techniques such as trenchless pipe
  replacement, slip-lining, and cured-in-place lining. These methods minimize the impact at
  the surface, for example, minimizing traffic disruption and conflicts with  other utilities
  One of the main shortcomings of all the in-place techniques is making a leak-free joint at
 the main and lateral connection without excavating.  Because these connections are often
 significant sources of leakage, the effectiveness of the seal at this joint may be essential to
 RII reduction.

 Many rehabilitation techniques orginally developed for sewer mains have been modified
 tor lateral rehabilitation.  However, the cost effectiveness of these methods generally
 becomes less as the length of the individual rehabilitated pipe decreases. Since laterals are
 typically short (less than 75 feet) and may have many bends or offsets, rehabilitatation of
  aterak by in-place techniques is generally less cost effective than for mains.  Access to
 laterals for both testing and rehabilitation also remains a technical and institutional
 problem.

 Replacement

 Replacement is an effective option for RII correction, as well as for repair of structural
 deficiencies. Replacement of an entire manhole-to-manhole reach initially provides a new
 essentially  leak-free  pipe.  Conventional replacement methods involve  excavation and
removal of the  existing pipe or excavation of a parallel  trench for the new  pipe with
abandonment of the existing                                        -.      F H
                                       D-l

-------
                         Sewer System Rehabilitation Methods
 pipe in place. Excavation and .replacement of isolated, joint-to- joint pipe sections (point
 repairs) may also be used as a means of RII source correction, or in conjunction with other
 sewer    • •      "           '.'-    .-'-.•    •"     • ' ..': ... •,     .   ••   '  -   • '   •
 rehabilitation techniques. Whereas in-place repair techniques
 leave the original pipe grade, offsets, and sags unchanged, excavation and replacement
 generally correct these types of problems, as well as more severe problems such as sewer
 collapses. . Excavation  for  point repairs are often  necessary with other rehabilitation
 techniques.   For example,  severe joint offsets must  be excavated and repaired prior to
 slip-lining.  Lateral to main sewer connections are also frequently excavated for repair.

 Some of pipe replacement techniques that do not require excavation are described in the
 following paragraphs.

 Tunneling. There are a wide variety of construction techniques that can be classified as
 tunneling.   These techniques include microtunneling and  auger boring  as well  as
 conventional  tunneling.  Tunneling  is a  means of  replacing  an  existing pipe without
 extensive excavation.                           ,

 Microtunneling refers to tunnels which are too small to allow man entry.  Microtunneling
 techniques are also varied, and many are steerable.  In general these techniques allow
 installation of pipe up to a maximum of 300 to 400 feet.   The minimum pipe size  for
 today's equipment is about 8 inches. Techniques are available for installation below
 groundwater.  The technique is generally applicable in silts, clays, sands, and gravels, but
 deals poorly with stones or cobbles larger than two inches. The accuracy of the installation
 depends in part on the length. Concrete, clay, and fiberglass reinforced plastic pipe have
 been installed using this technique.  Access requires excavation of a launch pit 12 to 20
 feet long. Microtunneling can also be used to replace an existing pipe along its alignment.
 The technique has been used extensively in Japan, Germany, France, and Singapore.

 Auger boring is  used to describe  a nonsteerable technique.   Accuracy and length of
 installation are less than for microtunneling.   Pipes as small  as six-inch  diameter with
 lengths up to  400 feet can be installed. Access requires pits at each end, 6 to 15 feet in
 length.  The pipe installed is generally steel and called a casing. The process or carrier
 pipe is slipped inside the larger steel casing. This technique, often referred to as boring
 and jacking,  has been  used,since the 1940's in the  United States.  Pipe  jacking is a
variation of the bore and jack technique where the casing is eliminated and the pipe itself
is jacked.                                                          -_
                                        D-2

-------
                          Sewer System Rehabilitation Methods
Moles.  Moling mvolves use of a percussive hammer to create a duct through the soil.
niere are  two major variations, impact moling and pipe  bursting (also referred  to as
SS^hTT        n^  Tto§e teClmiqUeS aI1°W  ** trencWegss mstaUatoof new
               K          non-steer
                          n^                             rencess mstaaof new
                  K ^     y non-steerable'  PiPe burstm§ depends on an existing pipe for


  Impact moling typically utilizes a percussive hammer driven by air, although hydraulic
  versions have been developed.  The mole  creates a duct through clay, siltsfsands  and
  gravels.   Isolated boulders or cobbles can  be broken but often ihrow the moToff te
  alignment.  Very soft soils do not provide enough support for the weight of the mole; the
  mole may drop making reasonable grade control impossible. Normal installations are 100
  ?™,   g bu< mstf at'ons u? to 20° f^t long have been made.  Steerable moles exist;
  however  most moles depend on the  initial orientation for their alignment.  Pipes between
  one- and six-inch have  been installed with this technique.  The size of the launch pit is
  generally determined by the length of the pipe sections installed; the mole itself requires
  a launch  pit of about six feet in length.  This technique  is widely used in the United
 .Kingdom to install individual services.

 Pipe bursting uses  an expander in conjunction with a conventional impact mole.   The
 expander larger than the  existing pipe diameter, breaks the pipe and allows a new pipe
 £h»n?? 6i  °r puushe(lmto the sPace behind the expander.   The pipe installed may
 SST   ™ger than ** e3dS?g Pipe'  Pipes up to  18-mch have been installed by this
 technique. The maximum  length of installation is about 450 feet. Pipe bursting is effective
 in  existing cast  iron, unreinforced  concrete,  clay, and asbestos cement pipes.   New
 po yethylene, polypropylene, and clay pipes have been installed by this technique.  Butt
 welded polyethylene is particularly attractive for rehabilitation for RH control, since it is
 C bf™   T? & ?*** ™ ** * length fc ^^d, although a longer launch  pit
 may be required  depending upon the type of pipe installed.

 Moles are frequently utilized for laterals, both for new construction and  rehabilitation.
 ^tiltT  f  U'Cd b0th ^ eXfSting Pipes for ^acement (rehabilitation) and for
 installation of a new pipe. Impact moling provides a number of advantages.  Parallel
 replacement of a lateral can allow the existing lateral to remain in service until the new
seiyice is installed.  Also, new construction using impact moling installation  does not
requu-e granular backfill, thereby minimizing the potential for inflation into the sewe
                                       D-3

-------
                         Sewer System Rehabilitation Methods
 Rehabilitation

 Rehabilitation (as opposed  to  complete  replacement)  of an  existing pipe  can be
 accomplished "in-place" by several methods, including grouting slip-lining, and cured-in-
 place lining.  These methods are discussed below.

 Grouting. The least disruptive technique for rehabilitation, grouting, focuses on the sealing
 of joints, small holes, and radial cracks in otherwise sound pipe.  This technique involves
 ho excavation where manhole entry is available.  Grouting is performed with a miniature
 television camera which locates the pipe joint and defects.  Air testing  may be used to
 determine which joints are leaking and therefore require grouting.  After positioning, a
 temporary, double-bladder seal isolates the joint and grout is pumped through the joint.
 After grouting, the joint is pressure tested to ensure the  adequacy of the seal.

 A variety of chemical grouts are available.  The chemical grouts include acrylamide gel,
 acrylate gel, urethane gel, and polyurethane foam.  The gels are all capable of penetrating
 the pipe joint and filling voids outside the pipe wall.  The foam simply forms a gasket in
 the pipe joint.

 The; longevity of grout sealing may vary. Some of the grout products are susceptible to
 shrinkage under  alternate  wet and dry cycles (such as when the groundwater level varies
 above and below the pipe), reducing their sealing effectiveness. Foam grouts are designed
 to be unaffected  by water conditions, but may be difficult to apply.  In all grouting, quality
 control  during application may  have a  significant  impact on  grouting effectiveness.
 Therefore, periodic testing after the initial grouting (e.g., every three to five years) may be
 required, not  only to re-test the seal on grouted joints but also to ensure that new leaks
 in previously ungrouted joints and defects are also addressed.

 Lateral Grouting. Specific grouting techniques have been devised for lateral rehabilitation.
 One technique involves pumping the lateral full of grout under pressure and then cleaning
 the excess grout'from the  pipe interior. This method of joint sealing has shown limited
 success.

A second method known as the "sewer sausage" for grouting laterals has been devised.  In
this method, an inflatable plastic sock is inserted into the lateral through the. main sewer
using a special device that is operated by remote control.  The device is located inside the
sewer at the lateral, and is controlled by the operator by viewing through a TV camera.
The inflatable plastic sock generally covers the first two to three joints. Grout is injected
under pressure into the annulus created by the sock. After the grout Is set, the plastic
sock is pulled out and moved to the next lateral in the sewer. Although the sewer sausage
                                        D-4

-------
                           Sewer System Rehabilitation Methods


  method has been used for entire laterals, it is most effectively used for sealing the first
  joint between the lateral and the main sewer.

  In addition to the above techniques,  direct joint grouting techniques, as  used in larger
  diameter sewers can also  be  utilized for laterals.

  Slip-lining. In slip-lining,  a liner pipe, slightly smaller in outside diameter than the inside
  diameter of the existing pipe, is inserted into the  existing sewer. Prior to installation, the
  existing pipe must be televised to identify potential obstructions such as severe offset joints
  and protruding laterals, and failed pipe sections. These must be corrected by point repair
  Televising also serves to identify the locations., of services .which must be connected to the
  completed slip-lining.  Proofing the pipe by pulling a short piece of liner through the pipe
  is recommended.                                                                  r

  The slip-line insertion process involves excavating a small length of existing pipe to provide
  an insertion pit The depth and size of the excavation depend on the depth, diameter, and
  the flexibility of the pipe liner.  The liner, most often high-density polyethylene, is flexible
  and can be butt fused into long joint-free sections on the ground surface. The slip-lining
 pipe is pulled  by  a steel cable and is oftentimes  assisted by pushing the lining into  the
 existing pipe.  A tapered, pulling head provides gradual size transition and prevents debris
 from entering at the leading  end.  The gradual size transition makes it  possible to pass
 minor  obstructions.

 The ends of the liner at the manholes typically  are  grouted  to seal the annular space
 between the liner and the outer pipe. Full grouting of the annular space may also be
 done.  This decision is generally based on cost, the condition of the existing sewer, depth
 of cover, the potential for point loads on the pipe, and the amount of groundwater present.
 The slip-lining is resistant to attack from acid, such as sulfuric acid commonly formed from
 hydrogen sulfide in sanitary sewers.  This characteristic makes slip-lining suitable for repair
 of sewers with high potential for corrosion.

 When  a sewer main is slip-lined, each  lateral  connection must  be  excavated and
 reconnected to the slip-lined pipe.  If the  lateral  is also slip-lined, the lateral and main
 sewer liners can be fused together to make a leak-free joint.

 Two variations of the conventional slip-lining method are now available, both of which can
 be installed from existing manholes and therefore eliminate the need for excavation for
 insertion pits. The first method utilizes short, threaded high density polyethylene (HDPE)
pieces.  The physical properties of this material are higher than polyvinyl chloride (PVC),
while its resistance to  chemicals and effect of temperature on  physics] properties are
similar to that  of PVC lining.  The assembled liner pipe can either be pushed or pulled
                                        D-5

-------
                          Sewer System Rehabilitation Methods


  with the existing pipe by using simple winching equipment.  Low density grout is used to
  fill the space between the pipe and the lining. The cost of sliplining with short pieces may
  be less than other systems because non-skilled labor can be used for installation.

  The second non-conventional slip-lining method uses a specially designed PVC strip that
  is spun directly into  the existing sewer to be rehabilitated.  The PVC strip is helically
  wound by a machine  placed in an existing manhole.  The space between the pipe and the
  lining is filled with low density grout to stop groundwater from leaking into the annular
  space. The PVC lining used in this process has excellent properties as a protective lining
  against corrosion and can be designed for any strength requirements.

  In another variation of this method, the lining is expanded after insertion into the existing
  sewer.  This is accomplished by pulling an inflated plug  through the liner in the sewer
 while/spiral joints slip before the cement is set. With this method, no grouting is required
 since the lining touches the pipe. However, a bonding resin is recommended to be used
 between the lining and the pipe.

 As with conventional slip-lining, there is no dependable remote control method for cutting
 the internal connections.  The connections must be excavated and exposed, the liner pipe
 cut, and a fabricated connector fitted and adhered to the lining with solvent cement. The
 entire fitting is then covered with cement mortar.

 Expandable plastic liners (polyethylene and PVC) are recent developments in lining of
 pipe. These liners come in flattened rolls. They are heated slightly as inserted to increase
 flexibility.  After installation, further heating  results in reversion to the original circular
 cross section.  Handling  of manhole and lateral connections  is  similar to  that for other
 slip-lining methods.  These products have been through limited actual usage.

 Cured-In-Place Lining

 Cured-in-place lining techniques utilize a thermal-setting, resin-coated, flexible fabric, which
 is prepared to  match  the diameter and the length  of the pipe section to be lined.  The
 material is saturated with resin and kept chilled prior to installation.  Once in place the
 liner is cured and hardened.  The liner conforms  to any  shape and discontinuities and
 provides a smooth, joint-free lining.  The liner thickness is a design choice;  thicker linings
 can be designed to support weakened pipe or support greater hydrostatic loads.

 Until recently, only one cured-in-place lining method was available in the U.S. However,
 several other methods have been developed and are in use in Europe and Japan. At least
one of these has recently entered the U.S. market  All cured-in-place lining methods use
the same basic materials (thermo-setting resins), but differ in the techniques used to insert
                                        D-6

-------
                          Sewer System Rehabilitation Methods


  the liner into the pipe and the method for curing the resin.  In most methods, the lining
  is inserted into the existing pipe by inversion, although in at least one  method the lining
  is dipped inside the pipe. Inversion is generally accomplished with water or compressed
  air. Different methods may be used for curing the liner; hot water or steam are the most
  common, but ultraviolet light is used in one process.

  Cured-in-place lining does not require  any excavation unless there are major pipe failures
  or-severe lateral protrusions into the existing line. The pipe material is resistant to acid
  and can be used to repair corroded concrete sewers.   Although a remote cutting device
  can sometimes be used to reconnect laterals to  the lined pipe, the  exact location of the
  lateral connections may sometimes be  difficult to find.  If the original lateral connections
  are subject to leakage, remote cutting  will not provide  any  means of sealing these joints
  In such cases, the lateral connections would have to be excavated and repaired.

  MANHOLE REHABILITATION

  The magnitude of RII through manhole defects appears to vary widely from system to
  system.  It is well known that inflow through manhole lids can contribute to peak wet
  weather  flows, particularly when manholes are  located in  areas  subject to ponding or
  flooding.  Less well  documented is the RH through manhole  defects  where pavement
  defects  allow  rain to  move quickly  into base  rock materials adjacent to  manholes.
 Milwaukee Metropolitan Sewerage District (MMSD) studies suggested significant RII flows
 can result from manhole defects, specifically, frame and chimney connections.  RII may
 also  enter manholes through the walls and base, particularly  in brick manholes with
 deteriorated mortar.

 Rehabilitation methods for manholes include both interior and exterior techniques.  Interior
 repair techniques are less expensive and less time  consuming than external repairs but are
 frequently less effective.  MMSD has conducted  a pilot testing  program on the various
 manhole rehabilitation techniques described below, as well as others  deemed ineffectual-
 they continue to evaluate the effectiveness of the  arious techniques.
Interior Repairs

Interior repairs are typically less effective for infiltration control but remain attractive in
many cases due to the low cost and ease of construction.  These techniques make possible
the sealing of all manhole joints including the lower ones, which are often subject to the
                                       D-7

-------
                         Sewer System Rehabilitation Methods


  largest hydrostatic forces.  Interior repair techniques utilize elastomeric sealant, chemical
  grout, or an internal boot.

  Sealants.  Internally applied sealants are intended to seal leaky joints in the manhole wall
  including  the  manhole frame and chimney joint.  The surface  must be free of loose
  material, gaps filled, and the surfaces must be cleaned to assure  a bond for the sealant.
  Various products are available to be either troweled or brushed. A potential disadvantage
  of elastomers is that hydrostatic pressure can destroy  the bond, requiring replacement in
  the future.

  Grouts. Grouts may be utilized to plug voids behind manhole walls much as they are used
  in pipeline rehabilitation. The chemical gels have not functioned well in applications where
  alternate wetting and drying occur.  A grout that is not subject to  this complication could
 provide a positive seal since hydrostatic forces would not destroy the sealing capabilities.

 Internal Boot An internal boot utilizes a continuous band of elastomeric material forced
 against the manhole walls with adjustable expansive metal bands  to seal manhole joints.
 The boot provides for vertical displacement at the joint but has limited offset capabilities.
 The concrete contact surface must be smooth and without ridges which might preclude a
 seal.
          '                              '       . .                             S s

 Exterior Repairs

 Exterior repairs are often more  effective than  internal repair  methods, but require
 excavation.  Therefore, external manhole repair methods  are more costly more than
 internal repairs. It is difficult to gain access to all the manhole joints, consequently repairs
 focus on the joints  close to the surface.  These  techniques utilize elastomeric sealant,
 elastomeric sheet, rubber sleeves, and two-piece frames.

 Elastomeric  Sealants.  These elastomeric compounds are poured around or troweled on
 the manhole joint. The poured versions are available in cold pour and hot pour mixtures
 both requiring a form to contain the pour. The cost of both techniques are similiar  since
 the excavation, backfill, and pavement repair costs are significant percentages of the total
 cost.  MMSD found the trowellable version to be most attractive.

 Elastomeric Sheeting. Elastomeric sheeting can be banded or applied with adhesive to the
 outside of the manhole structure.  Joints in the sheeting may be thermally welded when
 thermoplastic materials  are utilized.

Rubber Sleeves.  Rubber sleeves similiar to the internal boot are manufactured. These can
be slipped over the manhole chimney.  The sleeves are held in place by upper and lower
                                        D-8

-------
                          Sewer System Rehabilitation Methods


  stainless steel band clamps.   Some versions are  designed to  accommodate vertical
  movement in between the manhole frame and chimney.
  J""™?* STS*  Tw°-Piece frames Prov*de another means of achieving vertical
  flexibility. The lower section of the frame is securely anchored to the top of the manhole
  chimney  and will not be displaced by surface movement; therefore, the frame/chimney
  joint remains intact. An elastic, water-tight gasket provides flexibility for vertical movement
  and a seal against infiltration between the two pieces of the frame.   Since the upper
  portion of the manhole frame must be supported by the pavement, a two-piece frame is
  probably  only suitable for application in rigid concrete pavement.

  FOUNDATION DRAIN DISCONNECTION

  Foundation drains may be a significant RH source in some areas, as shown by the case
  studies presented for MMSD and Ames, Iowa. Many cities have ordinances that prohibit
  direct  connection  of foundation  drains  to  sanitary  sewers.   However,  many older
  installations still exist.  It is also not uncommon for foundation drains to be diverted to
  sanitary sewers because of accumulation of ice or water  outside the building or in the
  street when the discharge is not connected to a storm sewer.

 Foundation drains may be connected to sanitary sewer laterals in one of several ways:

       o     Direct gravity connection to the sanitary lateral.

       sanitarfDiamagb into a sump with a pumped discharge to the

      Kanitar|Diamagfe into a sump with a gravity discharge to the

      o      Discharge onto the  basement floor  and drainage to a  basement  drain
             connected to the sanitary lateral.

Methods for foundation drain disconnection are relatively straightforward. Depending upon
which of the above existing configurations apply, the foundation drain discharge is directed
to a  sump (if one does not already exist), and a sump pump and discharge line are
installed (or the existing sump pump discharge is redirected) to the ground surface outside
of the building or to a storm drain.  Discharge of the foundation drainage to the storm
drain system would also require connection to an existing storm lateral or construction of
a separate  storm lateral to connect into the storm sewer. The connection to  the sanitary
sewer lateral must also be plugged.  It is important to make sure that  sanitary sewage
cannot enter the storm sewer, and that basement floor drains are connected to the sanitarv
sewer.                                               ,                           J
                                       D-9

-------
                                  APPENDIX E

                   DESIGN AND CONSTRUCTION STANDARDS



This appendix contains a discussion on design and construction for minimising RH into new
sewer constmr.tinn
 sewer construction.

 DESIGN STANDARDS

 Modifications to sewer design standards provide a means to minimi^  future RII in new
 construction.  Such modifications include:  restricting the flow of water in granular backfill,
 reducing interconnections between backfills of various utilities, reducing the number of pipe
 joints, providing flexibility to reduce settlement stress and breakage, sealing pipe/manhole
 connections, and control over lateral installations.
                i               .      '        v "       :        •-"'-?         -  '

 Restricting Flow of Water in Granular Backfill

 Granular backfill in pipe trenches can dewater surrounding soils with resultant increased
 settlement potential for the pipe and the  ground surface.  This results in stress and the
 potential for creation of RII entry points in the buried pipeline. Furthermore, the granular
 backfill provides a permanent hydraulic conduit (French drain) along the  exterior of the
 pipeline.  This hydraulic conduit can provide the means for large quantities of water to
 travel to damaged joints and pipe defects.

 This phenomenon can be alleviated by the addition of impermeable trench cut-off walls,
 or trench plugs.  The trench plugs consist of concrete, grout with cement, or bentonite clay
 to create an impermeable dam.  The number of trench plugs needed depends upon the
 slope of the pipe (and the backfill); trench plugs at more frequent intervals  should be
 specified for higher slopes.  An interval of 50 feet is common for such  trench plugs.

 If possible, a connection should be provided between the backfill and a point  where the
 collected water can be discharged. Such connections could be to a storm drain or a creek.
 It is ideal to provide these connections at trench plugs at an elevation below the spring line
 of the sewer.

 In some areas, other methods to reduce the permeability of the granular backfill  have been
 tried. These include the introduction of impermeable grouts into the granular backfill after
placement, the inclusion of additives such as cement or bentonite clay to granular backfill,
or the specification of a well-graded backfill material. These measures sfcrve to  retard the
rate at which water can infiltrate into sewer trenches.
                                      E-l

-------
                           Design and Construction Standards
  Reduction of Utility Backfill Interconnections

  A related issue is the common practice of placing granular backfill in areas where utilities
  cross.  This is done because adequate compaction  is difficult to achieve when  utility
  trenches  are in close proximity, either vertically and horizontally.  Granular backfill (e.g.
  pea gravel) can be compacted to higher levels with less compactive effort. Unfortunately'
  this backfill material also provides a pathway for water collected in the shallower  utility
  trenches  to move  into the backfill surrounding the sanitary  sewer, almost  always  the
  deepest utility. Trench plugs can be installed at these locations to prevent this connection.

  Control of Migration of Fines/Piping

  Sewers constructed at steep slopes and in areas where groundwater is constantly fluctuating
  present the problem of migration of soil fines.  This migration can take place along  the
  pipe and  at cross section to the pipe.

 Two separate measures should  be considered in such situations.   Installation of trench
 plugs may prevent the fines from being carried away downstream.  Installation of a semi-
 permeable membrane below and around the backfffl may prevent soil migration in and out
 of the trench.  These measures will benefit in reducing pipe subsidence and the subsequent
 formation of cracks and openings in the pipes., Also, the migration of fine particles  away
 from the pipe trench will be discouraged, resulting in more resistance to RH movement
 within the trench  and into the  sewer pipes.

 Reduction in the Number of Pipe Joints

 The use of pipe with fewer pipe joints is advantageous since the joints are potential RH
 sources. Old vitrified clay pipe used in the past for sewer mains and service laterals had
joints as close as two feet apart  Early joints were mortared and were subject to cracking
 and deterioration.   New pipe  materials, such as polyethylene, PVC, or ABS  pipe can
 provide almost jointless construction. Fewer joints simplify the determination of the source
 of problems indicated by failed performance tests following construction.  Fewer joints are
 also likely  to reduce the number of problems with roots growing into pipe joints.

Flexibility  to Reduce Settlement  Stresses

Stress  points occur at the connections of the main and lateral,  the lateral to the house,
manholes,  cleanouts, and other structures. Stress points may also occur in trenches where
underlying  soil  conditions change. The ability to accommodate differential settlement is
important  since unless the  pipe transfers  a  part  of the overburden  soil load to the
                                        E-2

-------
                          Design and Construction Standards


 supporting soil, the pipe must carry the entire load. Flexible connections may be provided
 by two joints in close proximity as well as by flexible materials such as rubber couplings.
 Flexible  connections are  important  between  laterals  and  sewer mains,  since  these
 connections are often documented as major sources of leakage.

 Manhole Connections/Joint Sealing   ,'   •" '

 Sealing  pipe connections at  manholes  is equally as  important as providing flexibility.
 Manholes generally have greater hydrostatic pressures outside the manhole  than within.
 Most manholes have no seep ring or water stop around the pipe as it enters the manhole.
 Many of the pipes used today, such as PVC and polyethylene, do not bond well to concrete
 manholes.   Some  additional  means of sealing  the pipe connection to the manhole is
 required to prevent  infiltration into this joint.  Rubber seals have been  developed for
 small pipes. Tape seals, which are  composed of bentonite and butyl rubber mixtures with
 adhesive backing, wrap around the pipe to form an expansive seal.

 Laterals              ,

 Laterals are extremely important because they may represent about one-half or more of
 the total length of collection system piping. RE in laterals has been shown to be very high
 in many areas. This is due in part to lack of design and construction standards for. laterals,
 limited degree of construction inspection normally provided, and because laterals typically
 receive little or no routine maintenance.  Exterior cleanouts allow ready access, fpr testing;
 one two-way  connection at the street (property line) and one at the building is  ideal.  To
 minimize RII, each lateral  connection at the main should be closely inspected, and the
 connection should utilize a manufactured sanitary tee, wye, or a saddle.  Pipe penetrations
 (hammer taps) should be  replaced.   Flexibility can be provided as  described earner.
 Cut-off walls or trench plugs in the  lateral trench can be an element of construction,,
 particularly here grade change or lateral length is great and granular backfill  is utilized.

 CONSTRUCTION STANDARDS

 Construction standards imply conformance  to the design intent  This conformance is
 accomplished by inspection  and testing.

 Regular Inspection                           ,,-.'.

 Stringent  construction standards for sewer lines cannot be  realized without  adequate
 inspection.  Major sewer construction should be continually monitored.  Although this
would be ideal with laterals, it is impractical to provide more  than a periodic inspection
during construction. Many agencies require post-construction television  inspection of new
                                        E-3

-------
                           Design and Construction Standards
  lines and lateral  This is quite valuable, but is not a substitute for inspection during
  construction   For example, post  inspection viewing  does  not indicate  if adequate
  compaction has been performed, if trench plugs have been installed, or if flexible couplings
  have been provided.   Ordinances requiring strict compliance with standard  construction
  details may help.

  Performance Testing

  Stringent standards for leakage testing (air pressure or water) should be set and achieved
  Since the results at the time of testing are probably the best the pipe will ever achieve'
  stringent test standards are necessary to assure acceptable infiltration over the life of the
 Leakage testing rarely imposes limitations on the length of pipe to be tested at one time
 Anything shorter than  manhole to manhole testing is impractical.   However  since
 permittable leakage is a function of length, longer reaches allow greater losses.  Current
 standards permit some joints to leak and  this is practical to accommodate construction
 capabilities. However, one joint may be responsible for 90 percent of the leakage in a test

 L6™!?1; -i  ^teSt in?UdeS ^ j0intS'  ** °ne * the "* badly leaking J'oint> the test
 would fail  If the test includes 40 joints, and badly leaking joint is included, the test may
 pass. Although testing of individual joints would eliminate this problem, it could be costly
 and time consuming.                                                   • •         J

 With leakage tests, no pipe lengths greater than single manhole-to-manhole reaches should
 be tested at one time.  Testing of  individual joints is recommended in large diameter
 piping,  18-inch and larger, using joint testing  equipment.

 Criteria for exffltration and air testing for gravity sewers and laterals are presented below
 rest criteria should be modified according to the manufacturer's recommendations.

Exffltration Test Criteria. Maximum allowable leakage of 25 gallons in 24 hours per inch-
diameter-mile  of  sewer  is  recommended  by  some manufacturers.   The Standard
Specifications  of Public Works Construction prepared by the  County Sanitation Districts
or Los  Angeles County  recommend  the  following formula for maximum  allowable
exfiltration.

            E= 0.0001 LD (H)w

                 E =  Allowable leakage  (gpm)
            L = Length of test section (feet)
            D = Internal diameter of pipe (inches)
                                       E-4

-------
                         Design and Construction Standards



            H=  Differenpe m elevation between water surface and invert at lower end
                  of pipe (feet)


Air Test Criteria.  When testing a new pipe,  the common procedure is to maintain air
pressure at 3.5 psig while the temperature stabilizes.  The system passes the test if loss of
pressure is 0.5 psig or less in 30 minutes. Failure to hold air pressure is usually indicated
within 15 to 30 seconds.
                                        E-5

-------
                                    APPENDIX F

                                COST EVALUATION
  This appendix describes the methodology and results of the RII cost evaluation summarized
  in Chapter 3.

  ANALYSIS METHODOLOGY

  The approach utilized for the RII cost evaluation is primarily intended to address sewer
  systems, such as the EBMUD system, where the primary sources of RII are  defects in'
  sewer mains and laterals. It is not intended for systems in which the primary RH sources
  are manhole frame/chimney leakage, foundation drains, or other specific types of sources
 not generally classified as pipe defects.

 The approach also assumes that the primary component of the peak I/I flow  is RII. In
 particular, it is assumed that base groundwater infiltration (GWI) is not "excessive"  (as
 defined under current  EPA regulations)  and that direct storm  water inflow (SWI) is
 insignificant compared to RH peak flows.

 The cost analysis procedure is intended to be applied  to a sewer subsystem which is
 relatively homogeneous with respect to age, soils, geology, groundwater conditions, sewer
 depths, and the general physical condition  of the system. A typical application  would be
 for  a monitored  area of between 10,000  and 50,000 linear feet  of sewer mains.  It is
 assumed that the RE flows  for the subsystem have been previously determined by flow
 monitoring or that a reasonable estimate of the RH can be made. As discussed in Chapter
 2, the magnitude and pattern  of RE flows are  a function of many different interacting
 factors.  Therefore, the RH response cannot necessarily be predicted  for any particular
 area based solely on the physical characteristics of the area or the sewer system.

 The assumptions  used  in the cost  analysis  should  not be perceived as limiting  its
 applicability to more "realistic" situations, for example, where GWI is also a significant flow
 component The basic concepts and approach can be applied to more complex situations
with appropriate modifications.
                                                               /

The RE cost analysis procedure consists of ten basic steps which are described below:

1.   Determine Subsystem  Peak RO Flow.  In the cost  evaluation, RII flow  is
     expressed in  terms  of a peak flow rate, since the major impact 61 RII in the
     sewer system is on the capabilities of facilities to handle peak flows.  Typically,
                                       F-l

-------
              •'<.-,                 Cost Evaluation               .


     the RII flow will be based on the peak hour (or other suitable short-term) flow
     for a specified design storm. The choice of design storm conditions may depend
     on  regulatory requirements or simply reflect the degree of conservatism that is
     desired in sizing facilities.

2.   Estimate RII Distribution.  In a typical subsystem, the RH will not be evenly
     distributed among all  pipes  in  the area.   Certain  "worse" pipe  reaches, or
     "mmibasins," may have higher unit RII contributions than others, i.e., contribute
     a greater proportion of the RII flow.  In the field, the RII distribution can be
     determined  through flow mapping (flow isolation) or intensive flow monitoring
     during rainfall.

     Figure F-l  presents a generalized  RII distribution  envelope.  Although the
     envelope is  conceptual in nature, it agrees well with data from several sewer
     systems in which infiltration (RII or GWI) distributions have been developed
     based on flow isolation data.  Based on a general knowledge of the  key RII
     factors  in the  subsystem,  the envelope  can be  used  to estimate  the  RII
     distribution.  Typically, older systems with more widespread defects will exhibit
     a more diffuse distribution (lower envelope boundary), while hewer systems might
     be characterized by more concentrated distributions (upper envelope boundary).

3.   Target the Percentage of the Subsystem for Rehabilitation.  This target value
     generally represents the point on the  RII distribution curve where the curve starts
     to 'level off." Above this percentage, the benefits of rehabilitation,  in terms of
     incremental  RII  flow  removed,  begin to  decrease.   However,  the target
     percentage of the subsystem should at  least be  large enough to significantly
     impact the RII flow (e.g., the targeted portion of the subsystem should contribute
     at least about 50 percent of the RE). For the envelope shown in Figure F-l, the
     target rehabilitation percentage for  a newer  system (concentrated distribution)
     might be about 30 percent of the subsystem, and 50 percent for an older system
     (more diffuse distribution). In these cases, the amount of the total subsystem RII
     contributed by the target percentage  of the subsystem would be about 80 percent
     of the RH.

4.   Select the Method of Rehabilitation.  Pipe rehabilitation methods that can be
     used for RII control were  described in Appendk D.  Most commonjy  used
     methods are  grouting and slip-lining.  Although in very old, deteriorated  systems,
     it may be necessary to replace a considerable number of pipes or pipe  sections
     because of structural problems, the  rehabilitation method selected for the RH
     cost analysis  should'be based on rehabilitation for RII correction only. It can be
                                       F-2

-------
        20       *0       60       80



       PERCENT OF SEWERS IN SUBSYSTEM
100
                FIGURE F-1



HYPOTHETICAL Rll DISTRIBUTION ENVELOPE

-------
                              ,  .  Cost Evaluation


    assumed that structural repair or replacement would be required regardless of
    RII considerations.

    For this cost analysis, the rehabilitation method is assumed to be grouting or
    slip-lining. The selection of either method should be based on known conditions
    in the sewer system.  In general, grouting would be most appropriate in newer
    systems in good structural condition, with few root problems, and in which the
    groundwater level does  not  fluctuate  below and above the pipes.  Sh'p-lining
    would be  more  appropriate for older  systems, in areas with extensive  root
    intrusion, or in areas where grout shrinkage could be a problem due to changing
    soil or groundwater conditions.

5.  Select Rehabilitation Approach.  The rehabilitation approach refers to the extent
    of rehabilitation in the project area, specifically, whether the project includes bnty
    the publicly owned portion of the system, or  also addresses the private, service
    laterals. Four rehabilitation  approaches are evaluated in this cost analysis:

         o    Isolated repair.

         o    Mains only.
     • •                            • " ' "               *       '
         o    Mains plus the lower portion of service laterals (to property line).

         o    Mains plus entire service laterals (to building).

    In  this context, isolated repair could include spot repairs of specific defects or
    manhole-to-manhole rehabilitation of non-contiguous reaches.  The selection of
    rehabilitation approach may  be dictated  by financial or institutional constraints

6.  Estimate Rehabilitation Effectiveness.  The significance of the distinction between
    the four rehabilitation approaches described above is in  the  amount of RH
    reduction  that can  be  expected  from  rehabilitation.   In general, the  more
    comprehensive the program,  i.e., the more components of the sewer system that
    are included, the greater reduction that will be achieved. Thus, rehabilitation of
    the mains  plus  the  lower laterals  should achieve  a proportionately greater
    reduction in RE than rehabilitation of the mains only.

    However,  because RII will migrate  to unrepaired defects, the percentage
    reduction  in RII cannot be directly  related  to the amount of Rn originally
    contributed  by the portion of the system that  is rehabilitated.  The following
    estimated  ranges for thb  effectiveness of  each of the four  rehabilitation
                                        F-3

-------
                                    Cost Evaluation
      approaches are based largely on engineering judgement, but supported by the
      touted data available from sewer rehabilitation projects for which an assessment
      of rehabilitation effectiveness has been able to be made.

           o   Isolated Repair              0 to 10 %
           o   Mains Only                 0 to 20 %
           o   Mains plus Lower Laterals   30 to 40 %
           o   Mains plus Entire Laterals   65 to 80 %

      The ranges are intended to reflect different types of sewer systems. For example
      the lower end of each range might apply to old  sewer systems, and the higher
      end  of the range to newer systems  constructed with modern joint materials
      For any given system, different assumed reductions might be warranted if such
      data  is available from previous rehabilitation projects, or if known conditions in
      the system  would suggest other values. For example, in the sewer system in
      North and South Shenango, Pennsylvania, described in Appendix C, a greater
      rehabilitation effectiveness would be expected through rehabilitation of the mains
      and lower laterals alone because the mains and lower laterals are known to have
      defective joints, and the upper portion of the laterals, constructed of different
      pipe materials, are believed to be relatively watertight.

      The rehabilitation benefit percentages presented above are intended to represent
      reductions in the peak RH flow, rather than the total storm volume of RH.  Also
      the percentages represent average reductions over the period of the cost analysis
      (20 years),  reflecting the  creation  of new RH  sources due  to damage and
     deterioration of the system over time.  Initial reductions  would be expected to
     be higher. For example, a rehabilitation program projected to have an average
     70 percent reduction over 20 years might be expected  to achieve a  90 percent
  •   reduction immediately after construction.

7.   Calculate  RH Reduction.  The RE  reduction  is the  rehabilitation  benefit
     percentage (from Step 6)  applied to  the portion of  the total subsystem RII
     contributed by the rehabilitated portion of the subsystem  (from Step 3).

8.   Estimate Rehabilitation Costs. The cost of rehabilitation depends on the amount
     of the subsystem  included in the rehabilitation program (from Step 3)  the
     selected rehabilitation method  and approach (from'Steps 4  and 5), and'such
     physical parameters  as depth of the  sewers, lateral density,  and soil and
     groundwater conditions.
                                       F-4

-------
                                  Cost Evaluation
     In  the  cost-effectiveness analysis, the rehabilitation costs are calculated, on a
     present worth basis. Therefore, the useful life of the rehabilitation method must
     be considered.   For example, slip-lining is  a relatively "permanent"  type of
     rehabilitation method, and might be considered to have a useful life of about 50
     years.  Grouting, on the other hand, would typically not last as long because of
     grout deterioration and development of new RH sources in the previously
     grouted pipe reach. Therefore, grouting might be assigned a useful life of 5 to
     15 years.  The determination of useful life might depend on the type of grout to
     be used, the anticipated quality of the work, the relative age and condition of the
     sewers, and physical conditions such as groundwater level which may affect the
     long-term durability of the grout.

9.   Estimate  Cost  Savings in  Transport and  Treatment.  The cost savings in
     transport and treatment is the difference in cost between those facilities required
     to handle the entire peak flow without system rehabilitation and those required
     after RH reduction (from Step 7). Transport and treatment costs will be highly
     dependent on the capacity of existing facilities, as well as  the length of  trunk
     sewers and interceptors downstream of the subsystem. Transport and treatment
     costs must generally be estimated based on the overall plan for the  total sewer
     system, since the incremental cost reductions due to rehabilitation in one single
     subsystem may not be significant.  Therefore, reasonable assumptions must be
     made regarding potential RE reductions in the other subsystems in the  system.
                           \ •       ,'•'.'',..                   -  i      \
     Although  RII correction  will reduce the annual operation and  maintenance
     (O&M) costs of the system as well as the capital costs  for construction of
     additional system capacity, the magnitude of the O&M cost savings will generally
     be very small compared to the capital costs for construction.  This is because
     system  facilities must be constructed to carry the design storm peak REE flow,
     whereas peak  flows  of  this  magnitude wfll  occur  relatively  infrequently.
     Furthermore, the cost for treatment may not be significantly affected by the peak
     flows, since treatment schemes wfll typically be designed for flow equalization or
     split-stream processing so that costly secondary treatment,  for example, is hot
     provided to the entire peak  flow (i.e., the plant effluent consists  of combined
     primary and secondary effluent meeting overall plant discharge requirements).

     Whether or not O&M costs  are significant wfll depend both on the treatment
     plant process and the seasonal rainfall pattern of the area. Since RII is  not a
     sustained flow like GWI and since treatment plants wfll generally not be designed
     to process peak hourly flows, the cost to treat the annual volume  of RII will
     generally not be a significant component  of total O&M  costs.   -  -„
                                       F-5

-------
                                  Cost Evaluation


     As with rehabilitation costs,  transport and treatment cost savings should be
     expressed on a present worth basis.

 10.  Calculate Cost Effectiveness  of KH Control.   The cost effectiveness  of RII
     control is determined by comparing the present worth cost savings in transport
     and treatment resulting from RII reduction (from Step 9) to the present worth
     cost of rehabilitation (from Step 8). The ratio of transport and treatment cost
     savings to rehabilitation cost is termed the "C-E Ratio". A C-E ratio greater than
     or equal to 1.0 indicates that RH correction is cost effective.

 COST EVALUATION OF MODEL SYSTEMS

 The cost analysis approach described in the previous  section was  applied to different
 "model" sewer systems.   The purpose  of  this  exercise  was  to identify how the
 cost-effectiveness of RII correction is affected by the characteristics of the sewer system,
 the type of rehabilitation approach selected, and other variables in the cost calculation.

 Model System Descriptions

 To facilitate the cost evaluation of model systems using a computer spreadsheet, four basic
 model system descriptions were developed:

     o   Type A - Relatively old system generally below the groundwater level.

     o   Type B - Relatively old system generally above the groundwater level.

     o   Type C - Relatively new system generally below the groundwater level.

     o   Type D - Relatively new system generally above the groundwater level.

The  designations "old" and "new" are not necessarily intended in the literal sense, but are
used to characterize the general construction and condition of the subsystem.  Specifically,
each subsystem type is intended to describe a  particular RE distribution (see Figure F-
1), as indicated in Table F-l.

Each of these basic system types were evaluated with respect to several  variables, as
follows:

     o    Magnitude of RII flows (as expressed as the ratio of peak RII to average  base
         sanitary flow, ranging from 5 to 20).
                                       F-6

-------
                                  Cost Evaluation
     b   Density of service laterals (ranging from 10 to 40 per 1,000 feet of sewer main).

     o   Rehabilitation approach (isolated repair,  mains only, mains plus lower laterals,
         mains plus entire laterals).

     o   Rehabilitation method (grouting or slip-lining).

The cost evaluation was used to identify the relative sensitivity of the cost effectiveness of
RII correction to each of these model variables.

Model Assumptions

The following assumptions were used in the cost evaluation:

System Size. The analyzed subsystem was assumed to contain 30,000 feet of, sewer main.
The subsystem was assumed to be part of an overall sewer system containing 50 similar
size subsystems, 20 of which were assumed to have similar RII characteristics and therefore
included in the rehabilitation program.

Wastewater  Flows before Rehabilitation.  Average  base wastewater flow (BWF) was
assumed to be 70 gpcd. For the analyzed subsystem, average BWF was calculated based
on the assumed lateral density in the subsystem, assuming three persons per lateral.  For
the entire system, average BWF was calculated based on an average of 1,500 persons per
subbasin (average lateral density of 16.7 per 1,000  feet).  Peak BWF was assumed to be
1.5  times average BWF for the total system flow to  the  WWTP,  and 2.5 times average
BWF for a trunk sewer serving the analyzed subsystem and four other similar subsystems.
Peak non-rainfall flow was also assumed to include an allowance  for  "non-excessive"
groundwater infiltration (GWI) of 50 gpcd. The peak RII flow in the analyzed subsystem
and  in the 20 similar subsystems was calculated as the RD/BWF ratio times the average
BWF. Peak RII flow  in all other  subsystems in the system was assumed to be 3 times
average BWF. The total peak flow before rehabilitation was calculated as the sum of the
peak BWF plus GWI allowance plus peak RE.
                                        F-7

-------
                                    Cost Evaluation
  Wastewater Flows after Rehabilitation.  An assumed effectiveness of rehabilitation (the
  percentage reduction in the peak RII flow in the rehabilitated portion of the subsystem!
  Tti8??*^10 CaCh SyStem type based on the rehabffitation approach, as indicated in
  lable F-l.  The amount of the RII reduction was then calculated based on the percentage
  reduction applied to 80 percent of the total subsystem peak RII flow. The same reduction
  was assumed to occur in the 20 similar subsystems also being rehabilitated. The total peak
  flow after rehabilitation was calculated as the total peak flow before rehabilitation minus
  the RH reduction in  all rehabilitated subsystems.

  Capacity of Existing Facilities.  The peak flow capacity  of the existing WWTP was
  assumedI tobe 25 times average dry weather flow. The peak capacities of the interceptor
  to the WWTP (assumed to carry the entire  flow from the system) and the trunk sewer
  serving the analyzed subsystem  (assumed to carry the flow from five similar subsystems}
  were assumed to be 4 times average dry weather flow.

  Cost Basis.  The cost analysis  was done on a  present worth basis assuming a 20-year
  analysis period and 8-7/8 percent discount rate.

  Rehabffitation Costs.  Unit costs for grouting and slip-lining were developed as  shown in
  iawe t-i. The unit costs were applied to the pipe footage and number of laterals in the
 rehabilitated  portion  of the  subsystem.   The  present worth  rehabilitation  cost was
 calculated based on a  useful life of 50 years for slip-lining (with a salvage value at 20 years
 based on straight-line depreciation) and a useful life of 5 or  10 years for grouting (with
 equivalent re-grouting required at the indicated interval).

 Transport and Treatment Costs. Based on the capacity of existing facilities and  the total
 peak flows before and  after rehabilitation, the additional capacities (for  the  WWTP
 interceptor, and trunk sewer) required before and after rehabilitation were calculated.  The
 cost for additional WWTP  capacity was based on providing flow  equalization to handle
 peak wet weather flows in excess of peak dry weather capacity.  The costs for additional
 interceptor
 and mink sewer capacity were based on providing parallel gravity sewers.  Unit costs for
 additional capacity were based on standard cost curves. The length of the interceptor was
 assumed to be 30,000 feet (about five miles), and the trunk sewer was assumed to be 5 000
 feet (about one mile).                                                           '

 The costs of facilities to carry these additional capacities were calculated  for the before
 and after rehabilitation conditions, and the cost savings, or difference between before and
 after costs, were determined. The cost savings were expressed in terms of present worth
values, assuming a useful life of 20 years for WWTP facilities and 100  years for new
                                        F-8

-------
                                    Cost Evaluation
 pipelines.  The total  cost savings for the WWTP, interceptor, and  trunk sewer were
 distributed equally  among  all  the  rehabilitated  subsystems  (including the  analyzed
 subsystem) served by each facility.

 Cost Effectiveness. The cost effectiveness of RII correction (C-E Ratio) was calculated as
.the ratio of  the  total cost  savings  for  the  analyzed subsystem  to  the subsystem
 rehabilitation cost.                                        ,       .

 Model System Cost Analysis Results

 The results of the cost analysis are presented in Table F-2,.  Based on the assumptions
 described in the previous section, the general results of the analysis are:

     o   RII correction is not calculated to be cost effective in subsystem types generally
          classified as "old."

     o   RII correction is  calculated  to be cost effective under certain conditions in
          subsystem types generally classified as "new," specifically, if peak RH flows are
          high, lateral density is low, and the mains and entire laterals are rehabilitated.

 Under certain very liberal assumptions,  grouting was found to be cost effective for isolated
 repair or mains-only rehabilitation of new systems with relatively high peak RII flows.  This
 was the  case  only if  the rehabilitation effectiveness indicated in Table F-l could be
 achieved even if the lateral connections  to the main were not included in the rehabilitation
 program and the useful life of grouting  was assumed to be at least  10 years.  Since lateral
 connections are typically significant sources of RII, and since the  useful life of grouting
 depends on a variety of factors, including quality control during construction, these may hot
 be realistic assumptions. In general, assuming a five-year versus a  ten-year useful life for
 grouting reduces the cost effectiveness  of RE correction by 40 to 50 percent.
                                          F-9

-------

-------

v:
           £5
           Sr-
                ^  «»
                a ^5
                s-

                                  2 —

                                 | |
                                               » 2
                                                               V*.
                                                              vn
                                                              S •  i.

              "S £
               •5 2

               si

                 s
        •a


        1
        O

        i
                           •5'
w

x>
      ss   sa


     "S   ^
                                    -JJ
              •4*

              "35
                      «   ^^    <3i

                                                                          ~'
                                                                          >>
                     'O •  C
                  i    5

                 Z   2
g,&|-
                                                        S V)

                                                          -
                                                        ae
                                                                               >, c
                                                                                . >

-------
    en

«M   S
^   cn
a   va


S   2


    wa

    S
                11

          2- ac ^> op   so op op op  , -  , „    so so so so i
          = s c c   sess   so so so so   ssss:
         .S .S .2 .S   '.s is .S !§  -s '5 -s -5   "1 *S '* '* '

         .S-.S-.S-.^   .5-.£•.£•.£•   i 1  S i   ^^•"s-"^l
         55353555   35555535  QCwC   333j5535:
  CB




     ^»

     Cs2


      •




^1!                                          -  i
                                                   i

Sd
                               a M    w               **



                               o si ci ci         " '





     w
                                                                    a   •§ •=
         ••rs — S   2S <-»t 25 ?5   2S ?5 S ?«   — rs — ?5
                                                    i •  »^i
                                                    !r  H3

                                                                    5   ^ *^
                                                                    aJ  : I
                                                                    s s '2 I
                                                                    * <2  — ^ '.
                                                                    — ->•
         <<<<   s
                                             w U CJ CJ   a a fi £
    — __

* III
U C .3? VI
• j ta ^^ yi
^ c £ <

-------