&EPA
                          United States
                          Environmental Protection
                          Agency
                         Air and Radiation
                         (6204J)
           December 1992
Acid  Rain  Program
Permits
                           In order to reduce acid rain in the United States and Canada, Title IV of
                           the Clean Air  Act Amendments of 1990 established I the Acid Rain
                           Program. The program will cut sulfur dioxide emissions in half and
                           substantially reduce  nitrogen oxides emissions  from: electric utility
                           plants.  This fact sheet discusses the key components! of the permit
                           provisions of the Acid Rain Program and is one of a series containing
                           information about the program.                      i
HPhe overall goal of the Acid Rain
 JL Program is to achieve signifi-
cant  environmental  benefits
through reductions in emissions of
sulfur dioxide (SO2) and nitrogen
oxides (NOX), the primary causes
of acid rain. To achieve this goal at
the lowest cost to society, the pro-
gram employs both traditional and
innovative, market-based ap-
proaches for  controlling  air pollu-
tion. In addition,  the  program
encourages energy efficiency and
promotes pollution prevention.
  Title IV of the Clean Air Act sets
as its primary goal the reduction of
annual SOz emissions by  10 million
tons below 1980 levels. To achieve
these SO2  reductions, the law re-
quires a two-phase tightening of
the restrictions  placed  on fossil
fuel-fired power plants.
  Phase I  begins in 1995 and af-
fects 110  mostly coal-burning
electric utility plants located in 21
eastern and midwestern states.
Phase II, which begins in the year
2000, tightens the annual emis-
sions limits imposed  on these
large, higher emitting plants and
also  sets restrictions on smaller,
cleaner plants fired by coal, oil,
and  gas. The program affects ex-
isting utility units with  an output
capacity of greater than 25 mega-
watts and all new utility units.
   The Act also calls for a 2 million-
ton reduction in NOX emissions by
the year 2000. A significant portion
      of this reduction will be achieved
      by coal-fired utility boilers that will
      be required to install low  NOX
      burner technologies and to  meet
      new emissions standards.
        The innovative, market-based
      SO2 allowance trading component
      of the Acid Rain Program allows
      utilities to adopt  the most  cost-
      effective strategy  to reduce SO2
      emissions at units in their systems.
      The Acid Rain Program operating
      permit outlines the specific pro-
      gram requirements and compli-
      ance  options chosen by  each
      source. Affected utilities also will
      be required to install systems that
      continuously monitor emissions of
      SO2, NOX, and other related pollut-
      ants in order to  track progress,
      ensure compliance, and provide
      credibility to the trading program.
      In any year that compliance is not
      achieved, excess emissions penal-
      ties will apply, and sources either
      will have allowances deducted im-
      mediately from their account or
      may  submit  a plan to EPA that
      specifies how the excess SOz emis-
      sions will be offset.
       Introduction
         The Acid Rain Program is imple-
       mented through operating permits.
       Each permit specifies the enforce-
       able requirements that apply to each
       affected unit at a plant (or source).
       The  permitting requirements
afford flexible planning opportuni-
ties to help minimize  the costs of
compliance. All affected sources
must submit operating permit ap-
plications to EPA in Phase I, and to
an EPA-approved state or local per-
mitting authority in Phase II.
  The permit specifies each unif s
basic allowance allocation and NOX
limitation, which may vary from
the statutory requirements if the
source elects one or more optional
methods of compliance. The permit
must contain a compliance plan,
which describes how the source
will meet the  program require-
ments, if  it elects one of these
optional methods.
  Other requirements pertain to
certifying Designated Repre-
sentatives for affected sources,
schedules for submitting materials,
permit processing procedures, du-
ration of  terms, revision proce-
dures, and the periodic compliance
certification reporting.


Which Sources Must
Obtain Permits?

   Most electric utility plants in the
country must obtain an Acid Rain
Permit.
   Phase I addresses the 110 largest
SO2-emitting plants,  as listed in
Table 1 of the  Allowance Rule.
Other facilities may be permitted
in Phase  I if they are  part of  a
                             )Printed on paper that contains at least 50% recycled fiber.

-------

-------
compliance plan for a unit listed in
Table 1.
  Phase n addresses an additional
800 SOz-emitting utility plants.
Other facilities that may be permit-
ted are certain new units that began
commercial operation  on or after
November 15, 1990, and existing
units that increase  electrical gen-
eration from less than 25 mega-
watts to 25 megawatts or more.

Who Represents Sources
in Permitting Matters?
  The  owners  and operators of
each source must select one person
to represent  them in matters per-
taining to the Acid Rain Program
and may select a second person to
act as  an alternate for the first.
These two persons are known as
the Designated Representative
and Alternate Designated Repre-
sentative. Both persons must be
identified and approved by agree-
ment of the owners and operators
of a source  in the Certificate of
Representation.
   The Designated  Representative
is responsible for submitting to EPA
and state permitting authorities all
Acid Rain Program submissions
for the source and all units at  that
source, including allowance trans-
fers, emission monitoring reports,
compliance  certifications, Excess
Emissions Offset Plans, permit ap-
plications, and permit  revisions.
The Designated Representative
must sign and certify the truth and
accuracy of  each submission.  Per-
mits are only issued to a source if its
Designated Representative  has
been chosen and certified. The Des-
ignated Representative may be
changed at any time by agreement
of the  source's owners  and
operators.

 What Information  Must Be
 Included in Permit
 Applications?
   The source must complete stand-
 ard forms when applying  for an
 Acid  Rain  Permit.  The  forms
 request  information about the
Designated Representative, gen-
eral plant information, and specific
unit information and a compliance
plan for  each  affected unit. The
standard forms  ensure national
consistency in applications and
help facilitate a national allowance
market.
How Do Compliance Plans
Work?

  Each source must develop a
compliance plan for each affected
unit that describes the actions taken
to ensure compliance with the Acid
Rain Program. The plan must indi-
cate that the unit will hold enough
allowances to cover its annual S&2
emissions and will be operated in
compliance with the applicable
NOX  emissions limitations. The
plan may comprise one or more of
the following options:

  % Phase I—Substitution  Plan: A
    Phase I unit may reassign all or
    some of its Phase I SOz emis-
    sions reduction requirements
    to one or more existing units
    (called substitution units) that
    would otherwise not be regu-
    lated until Phase II,  if these
    units meet the Phase I unit's
    requirements.  A substitution
    unit consequently becomes a
    Phase I unit and, as such, must
    meet the SO2 limitations of
    Phase I. All units involved in a
    Substitution Plan must have a
    common owner or operator
    (including  a common Desig-
    nated Representative).

   • Phase  I—Extension  Plan: A
    Phase I unit, and any unit that
    becomes affected in Phase I
    under another compliance
     option, may apply for a 2-year
     extension of' Phase I SO2 limi-
     tations. Extensions are granted
     to units that (1) use a qualify-
     ing technology that can be
     shown to remove at least 90
     percent of a unit's SO2 emis-
     sions, or (2) reassign emissions
     reduction  obligations  to  an-
     other unit that uses such a tech-
     nology during Phase I.
    A Phase I extension unit is
 given extra SO2 emissions al-
 lowances  to cover the SO2 it
 emits beyond its basic Phase I
 allocation during 1995 and
 1996. A limit of  3.5 million
 allowances is available to
 these units. Applications are
 processed in  the order that
 they are received. The order of
 receipt for applications re-
 ceived on the same day is de-
 termined by lottery.

• Phase  I—Reduced  Utilization
 Plan: A Phase I unit may meet
 its emissions reduction re-
 quirements by reducing elec-
 tricity generation. The unit can
 compensate  for  planned
 reduced output by (1) desig-
 nating one or more non-Phase I
 SO2-emitting unit or units
 (called compensating units) to
 increase generation, (2) adopt-
 ing verifiable energy conser-
 vation or  improved  unit
 efficiency measures, or (3) des-
 ignating sulfur-free generators
 to provide generation.  EPA
 grants allowances to compen-
 sating units  based on 1985
 SO2 emissions rates and base-
  lines (i.e., average annual fuel
 use from 1985 to 1987).
    Because both  the original
  and compensating units must
  hold enough allowances  to
  cover SO2 emissions,  allow-
  ances may be transferred from
  the original unit to the com-
  pensating units to cover emis-
  sions beyond their granted
  allowances.  The units in a
  Reduced Utilization Plan do
  not have to  have the same
  Designated Representative as
  the original unit. If reduced
  utilization is not accounted for
  by a  compensating  unit,
  conservation, improved unit
  efficiency, or sulfur-free genera-
  tion, the unit reducing utiliza-
  tion may have to surrender
  allowances.

 • Phase  II—Repowering Exten-
  sion: Phase II units may obtain
  a 4-year extension  of the

-------

-------
   Phase n emissions reduction
   deadline if they repower with
   a qualified repowering tech-
   nology. Repowering requires
   replacement of  an existing
   coal-fired boiler with (1) one of
   seven technologies listed in the
   Clean Air Act Amendments,
   (2) a derivative of one of those
   technologies, or (3) a technol-
   ogy determined  by EPA and
   the Department of Energy to
   control multiple combustion
   emissions and improve boiler
   or generation efficiency while
   significantly reducing waste as
   compared to technology com-
   monly used in 1990.
     Qualified technologies are
   atmospheric or pressurized
   fluidized bed combustion,
   integrated gasification com-
   bined cycles, magnetohydro-
   dynamics, direct and indirect
   coal-fired turbines, and inte-
   grated gasification fuel cells.
   To obtain a Repowering Exten-
   sion  a Designated  Repre-
   sentative must petition EPA for
   conditional approval of the
   technology. If a unit proceeds
   with repowering that  later
   proves infeasible, it will not be
   held liable for failing to repower
   as long as it acted in good faith.
  The  Designated  Represen-
tative  may seek conditional,
pre-approval of compliance op-
tions, except for Phase I extensions.
In this way, the unit can select
the  appropriate compliance
option at a later date.  The Des-
ignated Representative simply
informs EPA of its choice, and the
permit  is  administratively
amended to include the change.
  Multi-unit  compliance options
involving separate sources may
have different Designated Repre-
sentatives. Compliance plans
must be properly cross-referenced
in the permit for each source and
signed  by  each  Designated
Representative.

What Does the Permitting
Authority Do with the
Application?
   When the permitting authority
receives a source's permit applica-
tion, the permit writer determines
if the application is complete. If it
is incomplete, the permit writer
will request  additional informa-
tion. Delays  in submitting infor-
mation can result in a denial of the
permit.
   Once all of the necessary infor-
mation  has  been obtained,  the
permit writer prepares a proposed
permit and a statement describing
the  legal and factual basis of the
permit  requirements.  These
         National
       Consistency
The acid rain permitting process gives utilities flexibility to select from a number of
compliance options and devise the most cost-effective compliance plan possible.
The standard permit forms ensure consistency on a nationwide basis. Finally, the
appointment of a Designated Representative secures the accountability that is the
key to achieving true reductions.
materials are provided to the
source and are made available to
the public.
  A comment period is then held
during which time the public can
comment on the proposed permit
and request a public hearing. After
all comments are  received, and a
public hearing (if granted) is held,
the permit is issued or denied, in
whole or in part.  Each Acid Rain
Permit will be effective for 5 years.
This action is subject to  appeal by
the source or the public.
  In Phase I, EPA's Regional Of-
fices  are responsible for issuing
Acid  Rain Permits.  In Phase II,
EPA-approved state or local agen-
cies will implement permit pro-
grams under both Titles IV and V
of the Clean Air  Act. States will
process Phase H  permit applica-
tions and submit proposed permits
to EPA for review. Permits will be
issued by states, assuming that EPA
does  not have any substantive
objections.
   EPA will process Phase n permit
applications for sources located in
those states that  do  not have
EPA-approved permit  programs
by July 1,1996. In these cases, EPA
will follow its Phase I, permitting
procedures.


When Should  the Permit
Materials Be Submitted?

   During Phase  I, the following
deadlines apply:
   • Permit  applications and pro-
    posed compliance  plans—by
    February 15,1993.
   • Certificates of Representation
    for Designated Representative
    for Phase I sources—no later
    than the permit application.

   • Compliance option forms—
    with the permit application
    or  as proposed  permit
    revisions .
   • Phase I Extension Early Rank-
    ing applications—40 days af-
    ter the final rule.

-------
 V
i   i

-------
  During Phase II, the following
deadlines apply:
  • SOz permit applications and
    proposed compliance plans—
    by January 1,1996.
  • NOX permit applications and
    proposed compliance plans—
    by January 1,1998.
  • Certificates of Representation for
    Designated Representative—
    no  later than  the  permit
    application.
  • New Unit  Plans—by January
    1,1998, or 24 months before the
    unit commences operation,
    whichever is later.
  • Compliance option forms—
    with the permit application or
    as a permit revision.

How Can Permitting
Decisions Be Appealed?
  Any person  challenging a per-
mitting decision of EPA in Phase
I or Phase II must file a petition
for review with the Environ-
mental Appeals  Board. Provi-
sions of the Permit  Rule and
other acid rain rules may not be
appealed to the Board. The peti-
tion for review must  show that
EPA's factual  findings or legal
conclusions are clearly errone-
ous or that policy determina-
tions underlying the decision
are arbitrary and capricious or
otherwise  warrant review. The
Environmental Appeals Board
will determine whether to hold
an evidentiary hearing and will
issue a decision affirming, re-
versing, modifying, or remand-
ing EPA's decision. Final actions
may be appealed to the federal
courts.
  Appeals or decisions of state or
local permitting authorities in
Phase II will be governed by the
administrative and judicial re-
view procedures specified in the
approved permit  program. If the
state made the decision at issue,
the state will conduct the appeal
process  unless   the  appeal
challenges or involves decisions or
actions of EPA. Decisions or actions
by EPA include, but are not limited
to, allowance allocations, determi-
nations on alternative monitoring
systems, and determinations of
whether a proposed technology
constitutes a qualified repowering
technology. When the  state con-
ducts an appeal, the state permit-
ting authority must notify EPA of
the appeal and the decision that is
reached.
How Can the Permit Be
Revised?

  In many cases, permit revisions
may be necessary. Three types of
permit revision  procedures are
specified in the rule:  permit
modifications (including  fast-
track permit  modifications), ad-
ministrative permit amendments,
and automatic permit amendments.
  The permit modification proce-
dure applies to, among  other
things, relaxation of an approved
Emissions Offset Plan; determina-
tions concerning failed repower-
ing projects; and  determinations
by a state interpreting, modifying,
or voiding any Acid Rain Permit
provisions. Permit modifications
involve the same public notice
and comment procedures as those
involved in the issuance of a per-
mit. The fast-track modification is
used for, among other things, in-
corporation of a new compliance
option; changes in Substitution or
Reduced Utilization Plans that re-
sult in a Phase II unit becoming a
Phase I unit; and changes in a
Phase I Extension Plan or Repow-
ering Plan.  With the fast-track
modification, the permittee will
publicize the proposed permit
modification in a newspaper of
general circulation in the area
where the source is located  or in a
state publication, as well as give
notice to the interested parties.
The public will have 30 days to
comment to  EPA. The permittee
will submit  its proposed modifi-
cation to EPA, and the Agency will
have 30 days after the close of the
comment period to rule on the pro-
posed modification.
  The  administrative  permit
amendments procedure applies
to simple alterations to a  per-
mit, such as corrections of typo-
graphical errors, and name and
address changes. Other changes
(such as activating certain compli-
ance options that were condition-
ally approved, changing the
Designated  Representative if a
new Certificate of Representation
is submitted, and terminating
certain compliance options), are
also handled as administrative
permit amendments. Administra-
tive amendments are made by the
permitting  authority  without
prior public notice.

  An automatic permit  amend-
ment occurs whenever an emis-
sions allowance transaction  is
recorded by EPA on the  Allow-
ance Tracking System. A permit
will not be  rewritten to include
these automatic amendments.
Rather, the applicable SO2 emis-
sions limitation will be deter-
mined at the end of each calendar
year according to each unit's
Allowance Tracking System
account.
  The  incorporation of  an Ex-
cess Emissions Offset Plan ap-
proved by  the  Administrator
also will be an automatic permit
amendment.
For More Information

  Write to:

  U.S. EPA
  Acid Rain Division (6204J)

  401 M Street, SW.
  Washington, DC 20460

  If you would like to receive other
fact sheets on the Acid Rain
Program, call the Acid Rain Hotline
at 617-674-7377  or the EPA Public
Information Center  (PIC) at
202-260-2080.

-------
           ,,•.1,;
II   ,'H,

-------