United States
Environmental Protection
Agency
                            Solid Waste and
                            Emergency Response
                            (5306W)
EPA-530-F-OO-OOIc
June 2000
www.epa.gov/osw
Four Times  Square
New York, New York
58%  Reduction of Demolition and
Construction Materials
As of its fifth quarter of construction, the Four Times Square office tower
project has demonstrated that materials recovery makes good sense and
can save money. ByMarch 1999, project participants had diverted an
average 58% of total demolition and construction discards (59% by weight
of demolition debris and, so far, 58% by weight of construction discards) from disposal.
Contractors saved over $780,000 in disposal fees and earned over $105,000 in revenue from
materials sales by diverting 17,800 tons of materials from disposal.
Project Description

   Four Times Square is a 48-story office tower
   located at the intersection of Broadway and
42nd Street. It is the first office tower to be built
in Manhattan since 1988.  It is also, due to the
commitment of its owners, one of the first office
towers of its size designed to address
environmental building issues, such as energy
efficiency and indoor air quality. The
 implementation of responsible construction
 techniques led to the recovery of 58% of
  overall demolition and construction  debris.
      The project involved both a demolition
   phase and a construction phase. Before
   construction could begin, crews had to
   remove six buildings. Extensive salvage
   combined with recycling resulted in  the
   recovery of over 15,000 tons of materials. Prior
         to demolition, private groups removed
          all salvageable materials such as
          doors, copper facial corners, and 112
         tons of wood beams. As the  structures
          were removed, the waste hauler
          carted away over 15,800 tons of
         metal and rubble for recycling, and
        the demolition contractor disposed of
        almost 11,100 tons of materials
        including unsalvageable bricks and
        commingled wood, insulation, and
         gypsum board.
               To assure that materials were
         recovered during the construction
                                                              Times Square building.
                                             phase, project coordinators worked closely with
                                             the demolition contractor and required it to
                                             report tonnage data on materials recycled or
                                             reused. Prior to construction, the owners,
                                             principal architects, and construction manager
                                             held a pre-construction meeting with the
                                             construction contractors to discuss the
                                             importance of materials efficiency and recovery.
                                             The environmental consultant adjusted the
                                             contract to include language that maximized
                                             recovery. She also created forms that contractors
                                             could use to anticipate packaging waste


                                                   Materials Collected
                                                   Recycled
                                                      (Demolition) steel, scrap metal, brick,
                                                      concrete, dirt, (Construction)
                                                      aluminum, miscellaneous metal,
                                                      cardboard, wood, dirt, and rock
                                                   Salvaged for Reuse
                                                      ornate stone work, office doors, copper
                                                      facial corners, and wood timbers.

-------
generated during the construction process.
The construction management firm
threatened to withhold payments unless
the contractors adhered to the contract and
completed the forms. Although some
contractors were reluctant to complete the
forms, no payments were withheld. By the
fifth quarter of construction (March 1999),
the contractor had recovered 1,900 tons of
the construction debris generated.
    There was little room to sort and
collect recyclables, no space to place drop-
off containers, and no room for multiple
trucks to pick up materials for recovery or
disposal at the construction site.  Hoist and
        Project Summary
Date Started                August 1996
Projected Date of Completion    July 1999
Project Square Footage
    Demolition
    Construction
Total Waste Generated (Tons)
    Demolition
    Construction
Disposed (Tons)
    Demolition
    Construction
Total Materials Diverted (Tons)
    Recycled
        Demolition
        Construction
    Salvaged
        Demolition
        Construction
Total Materials Diverted
    Demolition
    Construction
Disposal Costs ($/ton)
    Landfill
 462,500
1,600,000
  30,314
  27,027
   3,287
  12,480
  11,097
   1,383
  17,833
  15,805
   1,904
     125
       0
  58.4%
   58.9%
   57.9%

     $44
Revenue/Savings from Demolition Materials
Diversion
     Planning and Labor Costs          NA
     Tip Fees for Recyclables            NA
     Revenue from Materials Sales   $92,3 75
     Value of Materials Salvaged     $12,500
     Savings from Avoided Disposal $700,920
Revenue / Savings from Construction
Materials Diversion
     Planning and Labor Costs          NA
     Tip Fees for Recyclables            NA
     Savings from Avoided Disposal  $83,755
Total (Savings) from Diversion         NA
Key: NA = not available.
Notes: Data reflects figures as of March 1999, before
construction was complete. Contractors received all
revenue from materials sales. Hauling costs for
materials landfilled were not available. Materials
diversion through source reduction is not reflected
in the percentage of materials diverted.
              elevator operators, busy performing
              construction tasks, had little time to make
              multiple trips to move recyclables. Instead
              the contractor practiced "post-collection
              recycling" by having all debris hauled to a
              central site and then sorted.
                  In addition to recovering materials for
              reuse and recycling, contractors practiced
              source reduction during the project.
              Contractors reduced waste by requiring
              suppliers to reduce packaging or use
              durable packaging and by returning some
              packaging, such as pallets, to suppliers.
              Costs/Benefits
   The project contractor realized all
   savings resulting from materials
recovery. The building owners chose to
use the possibility of savings as an
incentive to encourage recovery and lower
contract costs rather than collect the
savings themselves. Although cost data
attributed to materials recovery are
unavailable, the environmental consultant
reported that the materials recovery was
cost-effective.  Disposal tip fees
of $44 per ton saved the
demolition contractor over
$700,000 in avoided
disposal costs and the
construction contractor
over $83,000 from avoided
disposal as of March 1999. When
combined with the revenue received
from the sale of steel and scrap metal
($92,375), wood beams ($7,500), and
other salvaged materials ($5,000), the
demolition contractor believes these
savings far outweighed waste reduction
costs for planning, additional labor, and
tip fees for recycled materials. The
planning and development costs
included the fees of the environmental
consultant for writing additions to
contracts, creating materials tracking
forms, organizing team meetings, and
overseeing all materials recovery efforts.
    Project facilitators considered post-
collection recycling the most cost-
effective materials recovery technique,
because on-site labor was very
expensive.
  Tips for Replication

  •   Obtain instructions from the top and
  communicate them to all project
  participants.
  •   Educate contractors about materials
  recovery techniques and the importance of
  resource conservation. Ask for their help.
  •   Ask contractors to avoid generating
  waste by using reusable containers and
  requesting materials with reduced
  packaging.
  •   Require contractors to estimate waste
  generated on site, including packaging, so
  you can anticipate the nature and amount
  of the recyclable materials that will be
  generated on site.
  •   Encourage
  communication among
  the client, project
  facilitators, and
  contractors.
Environmental Consultant
Durst Organization
1155 Avenue of the Americas
New York, New York 10036
Contact: Pamela Lippe
Phone: 212-922-0048 Fax: 212-922-1936
E-mail: plippe@aol.com
Web site: http://www.durstny.org
Architect
Fox and Fowle Architects
22 West 19th Street
New York, New York 10011
Contact:  Daniel Kaplan (Project Architect
        and Principal)
Phone: 212-627-1700 Fax: 212-463-8716
Construction Manager
Tishman Construction
666 5th Avenue
New York, New York 10103
Contact:  Mel Ruffini (Project Director)
Phone: 212-399-3600

-------