EPA/540/AR-92/079
                                                June 1993
    Resources Conservation Company
B.E.S.T.® Solvent Extraction Technology

          Applications Analysis  Report
       Risk Reduction Engineering Laboratory
        Office of Research and Development
       U.S. Environmental Protection Agency
              Cincinnati, Ohio  45268
                                         Printed on Recycled Paper

-------
                                                Notice
The information in this document has been funded by the U.S. Environmental Protection Agency (EPA) under the
auspices of the Superfund Innovative Technology Evaluation (SITE) Program under Contract No. 68-CO-0048 to Science
Applications International Corporation (SAIC). It has been subjected to the Agency's peer and administrative review,
and it has been approved for publication as an EPA document.  Mention of trade names or commercial products does
not constitute an endorsement or recommendation for use.

-------
                                                Foreword
The Superfund Innovative Technology Evaluation (SITE) Program was authorized in the 1986 Superfund Amendments.
The SITE Program is a joint effort between the U.S. Environmental Protection Agency (EPA) Office of Research and
Development and  Office of Solid Waste and Emergency Response.  The purpose of the program is to enhance the
development of hazardous waste treatment technologies necessary for implementing new cleanup standards that require
greater reliance on permanent remedies.  This is accomplished by performing technology demonstrations designed to
provide engineering and economic data on selected technologies.

This project consists of an evaluation of the Resources Conservation Company (RCC) pilot-scale Basic Extractive Sludge
Treatment (B.E.S.T.®) solvent extraction system. As a part of this evaluation, a demonstration test was conducted as a
cooperative  effort between U.S. EPA Region V, the Great Lakes National Program Office (GLNPO), the U.S. Army
Corps of Engineers (COE), and the EPA SITE Program. The B.E.S.T.® Demonstration Test used Grand Calumet River
sediment and took place at a centralized location immediately adjacent to the river in Gary, Indiana.  The goals of the
study, summarized in this Applications Analysis Report, are: 1) to assess the ability of RCC's pilot-scale B.E.S.T.® system
to remove (extract) organic contaminants from the bottom sediments of the Grand Calumet River, using a patented
solvent extraction technology that utilizes triethylamine as the solvent; 2) to evaluate the technology's potential beneficial
effect on the metals found in the sediments, by changing the metallic  compounds to less toxic or less teachable forms;
3) to assess the quality of the treated solids, water, and oil residuals; 4) to develop capital and operating costs for the
technology; and 5) to provide an overall mass balance for organic contaminants (polynuclear aromatic hydrocarbons and
polychlorinated biphenyls) around the B.E.S.T.®  solvent extraction system.  These goals were established by the SITE
Program.

Additional copies of this report may be obtained at no charge from the EPA's Center for Environmental Research
Information, 26 West Martin Luther King Drive, Cincinnati, Ohio, 45268, using the EPA document number found on the
report's front cover. Once this supply is exhausted, copies can be purchased from the National Technical Information
Service, Ravensworth Building, Springfield, Virginia, 22161, (800) 553-6847.  Reference copies will be available in the
Hazardous Waste Collection at EPA libraries. Information regarding the availability of other reports can be obtained
by calling the  Office of Research and Development Publications at  (513) 569-7562.  To obtain  further information
regarding the SITE Program and other projects within SITE, telephone (513) 569-7696.
                                                     E. Timothy Oppelt, Director
                                                     Risk Reduction Engineering Laboratory
                                                     111

-------
                                                Abstract
This document is an evaluation of the performance of the Resources Conservation Company (RCC) Basic Extractive
Sludge Treatment (B.E.S.T.®) solvent extraction technology and its applicability as a treatment technique for soils,
sediments, and sludges contaminated with organics.  Both the technical and economic aspects of the technology are
examined.

A demonstration of the RCC B.E.S.T.® solvent extraction system was conducted from July 1,1992 to July 22,1992 using
RCC's pilot-scale unit to treat two composited sediments (Sediment A and Sediment B) collected from the Grand
Calumet River. Operational data and sampling and analysis information were carefully compiled to establish a database
against which other available data, as well as the vendor's claims for the technology, could be compared and evaluated.
Conclusions were reached concerning the technology's suitability for use in removing organic contaminants from sediment.

The following conclusions are based on the demonstration test results collected by the Superfund Innovative Technology
Evaluation (SITE) Program and supported by other available data, including demonstration test data collected by RCC:

•       Contaminant concentration reductions of 96 percent for total polynuclear aromatic hydrocarbons (PAHs) and
        greater than 99 percent of total polychlorinated biphenyls (PCBs) were achieved for Sediment A.  Contaminant
        concentration reductions of greater than 99 percent for total PAHs and greater than 99 percent for total PCBs
        were achieved for Sediment B.

•       Removal efficiencies  in excess of 98 percent were realized for both sediments for oil and grease.

•       Mass balances conducted for total materials (including triethylamine) in the B.E.S.T.® system achieved closures
        of 99.3 percent and 99.6 percent for Sediment A and Sediment B, respectively. Mass balances comparing feed
        and product streams  (excluding triethylamine) achieved closures of 108 percent and 114 percent for Sediment
        A and Sediment B, respectively.

•       The products generated using the B.E.S.T.® process compared favorably with RCC's claims with regard to
        residual  triethylamine concentrations.  Treated solids produced  during  the optimum treatment  runs for
        Sediment B  had an average triethylamine concentration of 103 mg/kg.  Water generated during these runs had
        a triethylamine concentration of 2.2 mg/L or less, while the oil product collected at the end of all Sediment B
        treatment runs had a triethylamine concentration of 733 mg/kg. Because very little oil product was generated
        during the treatment of Sediment A, the Sediment A oil product was not processed to reduce its triethylamine
        concentration. Solid product generated from the optimum treatment runs for Sediment A realized an average
        residual concentration of 45.1 mg/kg, while water products from the optimum treatment runs for Sediment A
        had triethylamine concentrations of 1.0 mg/L or less.

•       The treatment cost for the remediation of contaminated soil, sediment, or sludge using the proposed 186-ton-per-
        day, full-scale B.E.S.T.® system is estimated at $94 per ton if the system is on line 80 percent of the tune or $112
        per ton if the system is on line 60 percent of the time.
                                                      IV

-------
                                                 Contents
Section                                                                                                 Page

Notice	        ii
Foreword	       iii
Abstract	       iv
Contents	        v
Tables	       ix
Figures	        x
Abbreviations	       xi
Acknowledgments	      xiii

1. Executive Summary .	        1

   1.1 Introduction  	        i
   1.2 Conclusions	        1
   1.3 Results	.  .        2

2. Introduction  	        3

   2.1 The SITE Program 	        3
   2.2 SITE Program Reports	        3
   2.3 Key Contacts	        4

3. Technology Applications Analysis	        5

   3.1 Introduction  	        5
   3.2 Conclusions	        5
   3.3 Technology Evaluation	        6
   3.4 Ranges of Site Characteristics Suitable for the Technology	        8
       3.4.1 Site Selection	        8
       3.4.2 Surface, Subsurface, and Clearance Requirements	        8
       3.4.3 Topographical Characteristics	        9
       3.4.4 Site Area Requirements  	-       9
       3.4.5 Climate Characteristics	        9
       3.4.6 Geological Characteristics	        9
       3.4.7 Utility Requirements	        9
       3.4.8 Size of Operation	        9
   3.5 Applicable Media	        9
   3.6 Regulatory Requirements		        9
       3.6.1 Federal Regulations 	;	      10
       3.6.2 State and Local  Regulations	      13

-------
                                       Contents  (Continued)
Section
Pae
   3.7 Personnel Issues  	•	       13
      3.7.1 Training	       13
      3.7.2 Health and Safety	       13
      3.73 Emergency Response	       14
   3,8 References  	       14

4. Economic Analysis	       15

   4.1 Introduction  	       15
   4.2 Conclusions	       15
   43 Issues and Assumptions	       15
      43.1 Costs Excluded from Estimate  	       15
      43.2 Maximizing Treatment Rate	       16
      43.3 Utilities	       16
      43.4 Operating Times  	       16
      43.5 Labor Requirements	       16
      43.6 Capital Costs	       16
      43.7 Equipment and Fixed Costs  	       16
   4.4 Basis of Economic Analysis	       16
      4.4.1 Site Preparation Costs	       17
      4.4.2 Permitting and Regulatory Costs	       17
      4.43 Equipment Costs  	       17
      4.4.4 Startup and Fixed Costs 	."	       18
      4.4.5 Labor Costs	       18
      4.4.6 Supplies Costs	       19
      4.4.7 Consumables Costs	       19
      4.4.8 Effluent Treatment  and Disposal Costs	       19
      4.4.9 Residuals and Waste Shipping, Handling, and Transport Costs	       19
       4.4.10 Analytical Costs	       20
       4.4.11 Facility Modification, Repair, and Replacement Costs  	       20
       4.4.12 Site Demobilization Costs	       20
   4.5 Results of Economic Analysis 	       20
   4.6 References  	       22

Appendix A - Process Description	       23

   A.1     Introduction 	       23
   A.2     The B.E.S.T.® Pilot Unit	       23
                                                    VI

-------
                                       Contents (Continued)
Section

   A3   Unit Operations		      23
          A.3.1  Feed Preparation	      23
          A.3.2  Extraction	      23
          A.3.3  Decantation, Solvent Recovery, and Oil Processing 	      25
          A.3.4  Solids Drying	      25
          A.3.5  Water Stripping	      26
          A.3.6  Product Water Treatment	      26
   A.4   References  	      26

Appendix B - Vendor's Claims  	      27

   B.I    B.E.S.T.* Process Effectively Removes PCBs and PAHs from Sediment	      27
   B.2    B.E.S.T.® Process Solvent Is Environmentally Friendly	      28
          B.2.1  Triethylamine Is Biodegradable	      28
   B.3    B.E.S.T.® Process Has No Air Emissions	      28
   B.4   , SITE and RCC Analytical Results Closely Correlate	'.'.'.'.'.'.'.'.'.      33
          B.4.1  Overall Mass Balance Results	      33
          B.4.2  RCC QA/QC Requirements .	'.'.'.'.'.'.'.'.'.      33
   B.5    B.E.S.T.® Process Performance Accurately Predicted by
          Bench-Scale Treatability Test Protocol	  '    33
          B.5.1  Bench-Scale Test vs. Pilot-Scale Test Data for Grand Calumet River Testing	      33
          B.5.2 Bench-Scale Test vs. Full-Scale Remediation	      34
   B.6    Other Pilot-Scale Test Project Results Substantiate SITE Demonstration Project Results	      34
          B.6.1  PCBs in Soils and Sediments at an Aluminum Manufacturing Site	   .   34
          B.6.2  PAHs in Sludge from Wood Treatment Facilities	      34
          B.6.3  PCBs in Soil at a Manufacturing Site	      35
          B.6.4  PAHs in Refinery Sludge	      35
   B.7    References	      35

Appendix C - SITE Demonstration Results	      36

   C.1    Introduction  	      35
   C3.    Contaminant Removal Efficiencies	      36
   C.3    Residual Triethylamine 	      37
   C.4    Mass Balances  	      37
          C.4.1  Solids Balance	      38
          C.4.2  PCB  Balance	      33
          C.4.3  PAH Balance	      38
          C.4.4  O&G Balance	 . .      33
          C.4.5  Water Balance	      39
                                                   vu

-------
                                       Contents (Continued)
Section

          C.4.6  Solvent (Triethylamine) Balance	      39
          C.4.7  Total Materials Balance	      39
          CAS  Feed and Product Materials Balance	      39
   CJ>    Leaching Characteristics	• • •  •      39
   C.6    PAH and PCB Concentrations in the Product Water and Product Oil	      40
   C.7    Air Emissions	      40
   C.8    Triethylamine Biodegradation Testing on Treated Solids	      40
   C.9    Particle Size Distribution	      41

Appendix D - Case Studies	      42

   D.I    Massena, New York Pilot-Scale Testing	      42
   D.2    Pilot-Scale Testing of Wastes from Wood Treating Facilities	      42
   D3    Pilot-Scale Testing of Waste from Machining Operations  	      43
   D.4    Pilot-Scale Testing of Petroleum Refining Sludge	      43
   D.5    Full-Scale Treatment of Oily Sludges	      43
   D.6    Reference	      43
                                                    vui

-------
                                               Tables
Number

  1     Summary of Results from Optimum Runs (Three per Sediment)	       2
  2     Characterization of the Untreated Sediment (Averages from Three Optimum Runs)  . . . .	       6
  3     Excavation Costs	      17
  4     Treatment Costs for 186-tpd B.E.S.T.® System Treating
       Contaminated Soil, Sediment, or Sludge	      21
  5     Treatment Costs as Percentages of Total Costs for 186-tpd B.E.S.T.® System
       Treating Contaminated Soil, Sediment, or Sludge	      21
  6     Projected Annual Downtime .	      22


B-l    SITE vs. RCC Analytical Results	 .  .	      33
B-2    SITE vs. RCC Analytical Results .	      33
B-3    Total Mass Balance Comparison:		      33
B-4    Transect 6 Testing Comparison	      34
B-5    Transect 28 Testing Comparison	      34
B-6    General Refining Site PCB Concentrations in Raw Sludge and Product Fractions	      34
B-7    Aluminum Manufacturing Facility PCB Removal from Soils and Sediments  	      34
B-8    Wood Treatment Facilities PAH Removal from Sediments 	      35

C-l    Total PAH, Total  PCB, and O&G Removal Efficiencies	      37
C-2    Residual Triethylamine Concentrations	      37
C-3    Mass Balance Summaries	      38
C-4    Solids Mass Balances	      38
C-5    PCB Mass Balances	      38
C-6    PAH Mass Balances	      38
C-7    O&G Mass Balances	„	      39
C-8    Water Mass  Balances	      39
C-9    Triethylamine Mass Balances .	      39
C-10   Total Materials Mass Balances	      39
C-ll   Feed and Product Materials Mass Balances	      39
C-12   PAH and PCB Concentrations in the Product Water	      40
C-13   PAH and PCB Concentrations in the Sediment B Product Oil	      40
C-14   Triethylamine Biodegradability in Treated Solids	      41
C-15   Particle Size Analysis Results .	      41

D-l    Treatment of Aluminum Manufacturing Solids and Sludges	      42
                                                  IX

-------
                                             Figures
Number

  1     Sediment Collection Locations - East Branch of the Grand Calumet River

A-l    Generalized Diagram of the RCC B.E.S.T.® Solvent Extraction Process ..
B-l    Transect 28 PAH Summary
B-2    Transect 6 PAH Summary .
B-3    Transect 28 PCB Summary .
B-4    Transect 6 PCB Summary  .
Page

   7

  24

  29
  30
  31
  32

-------
                                           Abbreviations
AAR      Applications Analysis Report

ARAR     Applicable  or Relevant and Appropriate
           Requirement

BDAT     Best Demonstrated Available Technology

B.E.S.T.®   Basic Extractive Sludge Treatment

BOP       Basic Oxygen Process

CAA      Clean Air Act

CERCLA   Comprehensive  Environmental Response,
           Compensation, and Liability Act

COE      U.S. Army Corps of Engineers

CPR       cardiopulmonary resuscitation

CWA      Clean Water Act

EPA       Environmental Protection Agency

GLNPO    Great Lakes National Program Office

gpm       gallons per minute

gpd        gallons per day

HEPA     high-efficiency particulate

IDEM     Indiana Department of  Environmental
           Management

MCL      Maximum Contaminant Level

NFPA     National Fire Prevention Association

NPDES    National Pollutant Discharge Elimination
           System
O&G      oil and grease

ORD      Office of Research and Development

OSHA     Occupational Safety and Health
           Administration

OSWER   Office of Solid Waste and Emergency
           Response

PAH      polynuclear aromatic hydrocarbon

PCB       polychlorinated biphenyl

PID       photoionization detector

POTW     publicly-owned treatment works

PPE       personal protective equipment

ppm       parts per million

QA        quality assurance

QA/QC    quality assurance/quality control

RCC      Resources  Conservation Company

RCRA     Resource Conservation and Recovery Act

RREL     Risk Reduction Engineering Laboratory

SAIC      Science Applications International
           Corporation

SARA     Superfund Amendments and
           Reauthorization Act

SDWA     Safe Drinking Water Act
                                                  XI

-------
                                 Abbreviations  (Continued)
SITE       Superfund Innovative Technology
           Evaluation

TCLP      Toxicity Characteristic Leaching Procedure

TDS       Total Dissolved Solids

TER       Technology Evaluation Report

tpd        tons per day

tph        tons per hour

TSCA      Toxic Substances Control Act

TSD       Treatment, Storage, and Disposal

TSS        Total Suspended Solids
                                                 xu

-------
                                         Acknowledgments
This report was prepared under the direction and coordination of Mr. Mark C. Meckes, Environmental Protection Agency
(EPA) Superfund Innovative technology Evaluation  (SITE) Project Manager in  the Risk Reduction Engineering
Laboratory (RREL), Cincinnati, Ohio.  EPA-RREL contributors and reviewers for this report were Mr. Dennis
Timberlake and Ms. Michelle Simon.  Other contributors and reviewers were Mr. George Jones and Mr. Lanny Weimer
of Resources Conservation Company; Mr. Stephen Garbaciak, Jr. of the EPA Great Lakes National Program Office; and
Mr. Jay A. Semmler and Ms. Linda Diez of the U.S. Army Corps of Engineers.

This report was prepared for EPA's  SITE Program by the Technology Evaluation Division of Science Applications
International Corporation (SAIC) in Cincinnati, Ohio for the U.S. EPA under Contract No. 68-CO-0048. This report was
written by Ms. Sharon Krietemeyer, Ms. Deana Demichelis, and Ms. Evelyn Meagher-Hartzell. The Work Assignment
Manager for the project was Mr. Thomas Wagner.
Cover Photos:  clockwise from top left are 1) bench-scale testing apparatus, 2) B.E.S.T.® pilot-scale unit, 3) collection
of sediments from Grand Calumet River, 4) untreated sediments being homogenized, and 5) sediment feed being weighed
prior to pilot-scale testing.
                                                   xiu

-------

-------
                                               Section 1
                                         Executive Summary
1.1     Introduction

This report summarizes the findings of an evaluation of
the  Basic  Extractive  Sludge Treatment  (B.E.S.T.®)
solvent extraction technology developed by Resources
Conservation Company (RCC).  As a part of this
evaluation,  a demonstration test was conducted as a
cooperative  effort between  the U.S. Environmental
Protection Agency (EPA)  Region V, the Great Lakes
National Program Office (GLNPO), the .Army Corps of
Engineers (COE), and the EPA Superfund Innovative
Technology Evaluation (SITE) Program.  During this
demonstration test, the B.E.S.T.® system was used to
treat composited sediments from two areas of the Grand
Calumet River.  Sediment collected from Transect 28
was  screened and homogenized to form Sediment A,
while sediment collected from Transect 6 was screened
and  homogenized to form  Sediment  B.  The results of
the demonstration test and supporting data from other
testing performed by RCC constitute the basis for this
report.
1.2     Conclusions

A number of conclusions  may  be drawn from  the
evaluation of this  innovative technology.  The most
extensive data were obtained during the SITE demon-
stration test.   The analytical results  obtained by  the
SITE Program were substantiated by separate analytical
results obtained by RCC.   Data from  other testing
activities have also been evaluated in relation to SITE
Program objectives. The conclusions drawn are:

•   Contaminant concentration reductions of 96 percent
    for total polynuclear aromatic hydrocarbons (PAHs)
    and greater  than  99 percent for total polychlor-
inated  biphenyls  (PCBs)  were  achieved  for
Sediment A. Contaminant concentration reductions
of greater  than  99 percent  for total  PAHs and
greater  than 99 percent  for total PCBs were
achieved for Sediment B.

Removal efficiencies in excess of 98 percent were
realized for both  sediments for  oil and  grease
(O&G).

Mass balances  conducted  for   total materials
(including triethylamine) in the B.E.S.T.®  system
achieved closures of 99.3 percent and 99.6 percent
for Sediment A and Sediment B, respectively. Mass
balances comparing  feed and product streams
(excluding triethylamine) achieved closures of 108
percent  and 114 percent for Sediment  A and
Sediment B, respectively.

The products generated using the B.E.S.T.® process
compared favorably with RCC's claims with regard
to residual  triethylamine concentrations.  Treated
solids produced during the optimum treatment runs
for Sediment  B had  an average  triethylamine
concentration of 103  mg/kg.   Water generated
during these runs had a triethylamine concentration
of 2.2 mg/L or less, while the composite oil product
collected at the  end of all Sediment B treatment
runs  had  a triethylamine concentration  of 733
mg/kg.   Because very  little  oil  product  was
generated during the treatment of Sediment A, the
Sediment A oil product was not processed to reduce
its triethylamine concentration.   Solid product
generated from  the optimum treatment  runs for
Sediment A realized an average residual concentra-
tion of 45.1 mg/kg, while water products from the
optimum treatment runs  for Sediment  A  had
triethylamine concentrations of 1.0 mg/L or less.

-------
    The  treatment  cost   for   the   remediation  of
    contaminated soil, sediment, or  sludge using the
    proposed 186-ton-per-day (tpd), full-scale B.E.S.T.®
    system  is estimated at  $94 per ton if the system is
    on line 80 percent of the tune or $112 per ton if the
    system  is on line 60 percent of the time.
1.3    Results

The objectives of this Applications Analysis are to assess
the ability of the process to comply with Applicable or
Relevant and Appropriate Requirements (ARARs) and
to  estimate  the cost  of  using  this  technology to
remediate a  Superfund site.   This  analysis includes
determining if the B.E.S.T.® process can 1) remove
                                        organic contaminants from the bottom sediments of the
                                        Grand Calumet River; 2) exert a beneficial effect on the
                                        metals found in the sediments by changing the metallic
                                        compounds to less toxic or  less leachable forms; 3)
                                        concentrate the organic contaminants into an oil phase;
                                        4) produce a  water phase that is  relatively  free of
                                        organic contaminants; and  5)  provide an overall mass
                                        balance for organic contaminants (PAHs and PCBs)
                                        around the B.E.S.T.® solvent  extraction  system.

                                        The treated solids and the untreated  sediment both
                                        passed the Toxicity Characteristic Leaching Procedure
                                        (TCLP) test for metals, so  it  was not possible to draw
                                        any significant  conclusions regarding the effects of the
                                        B.E.S.T.® process  on metals  leachability.   The other
                                        results are summarized in Table 1.
 Parameter
Table 1. Summary of Results from Optimum Runs (Three per Sediment)

                                     Sediment A                           Sediment B

                            PCBs     PAHs   Triethylamine         PCBs    PAHs  Triethylamine
Average Concentration in Untreated Sediment, mg/kg
Average Concentration in Treated Solids, mg/kg
Average Removal from Sediment, percent
Average Concentration in Oil Product, mg/kg
Maximum Concentration in Water Product, mg/L
12.1
0.04
99.7
NAb
<0.003
550
22
96.0
NAb
<0.01
NA"
45.1
NA
NAb
1.0
425
1.8
99.6
2,030
< 0.001
70,900
510
99.3
390,000
<0.01
NA'
103
NA
733C
2.2
.Notes;

a   NA = not applicable. These samples were not analyzed for triethylamine.

b   The Sediment A oil product was sampled at the end of the last run conducted on Sediment A. When the oil was sampled, there was not
    sufficient oil present for oil processing to reduce the triethylamine concentration and as a result, excess triethylamine was left in the oil. The
    triethylamine concentration in the oil does not provide meaningful data regarding the typical characteristics of the oil product.
c   This oil product was sampled following normal oil processing, which reduces the triethylamine concentration.

-------
                                                Section 2
                                              Introduction
2.1     The SITE Program

In 1986, the EPA Office of Solid Waste and Emergency
Response  (OSWER)  and Office of  Research  and
Development (ORD) established the SITE Program to
promote  the  development  and  use  of  innovative
technologies to  clean  up  Superfund sites across the
country.   Now in its sixth year, SITE is helping to
provide  the  treatment   technologies   necessary  to
implement new  Federal and state cleanup standards
aimed at permanent remedies rather than quick fixes.
The SITE Program is composed of four major elements:
the Demonstration Program, the Emerging Technologies
Program, the Measurement and Monitoring Technol-
ogies Program, and the Technology Transfer Program.

The  major focus has been  on the  Demonstration
Program, which is designed to provide engineering and
cost  data  for selected technologies.   To date,  the
Demonstration Program projects have not  involved
funding for technology developers. EPA and developers
participating  in  the program share  the cost of the
demonstration.    Developers  are  responsible  for
demonstrating their innovative systems at chosen sites,
usually Superfund  sites.   EPA  is responsible  for
sampling, analyzing, and evaluating all test results. The
result is an assessment of the technology's performance,
reliability, and costs. This information  is used in con-
junction with other data to select the most appropriate
technologies for  the cleanup of Superfund sites.

Developers of innovative technologies apply to  the
Demonstration Program by responding to EPA's annual
solicitation. EPA also accepts proposals any time a
developer  has a Superfund  waste treatment project
scheduled.  To qualify for the program,  a new technol-
ogy must be available as a pilot- or full-scale system and
offer some advantage over existing technologies. Mobile
technologies are of particular  interest to EPA.
Once EPA  has accepted a proposal,  EPA and  the
developer work with the EPA regional offices and state
agencies to identify a site containing waste suitable for
testing the capabilities of the technology. EPA prepares
a  detailed  sampling and analysis plan  designed  to
evaluate the technology thoroughly and to ensure that
the resulting data are reliable.   The  duration of a
demonstration varies from a few days to several months,
depending on the length of time and  quantity of waste
needed to assess the technology.  After the completion
of a  technology  demonstration,  EPA prepares two
reports,  which  are  explained  in  more   detail  in
Subsection 2.2.  Ultimately, the Demonstration Program
leads to  an  analysis  of the  technology's  overall
applicability to Superfund problems.

The second  principal element of the SITE Program is
the Emerging Technologies Program, which fosters the
further investigation and development  of treatment
technologies  that are  still  at  the laboratory scale.
Successful validation  of these technologies can  lead to
the  development of  a  system  ready  for field
demonstration and participation in the Demonstration
Program.

The third component of the  SITE Program,  the Mea-
surement  and   Monitoring  Technologies   Program,
provides   assistance   in   the   development  and
demonstration of innovative technologies to characterize
Superfund sites better.

The  fourth  component of the SITE Program is  the
Technology  Transfer  Program, which  reports and
distributes the results of both Demonstration Program
studies and Emerging Technology studies through the
Technology  Evaluation  Reports  (TERs),   the
Applications Analysis Reports (AARs), and abbreviated
bulletins from both programs.

-------
2.2     SITE Program Reports
2.3     Key  Contacts
The analysis  of technologies  participating  in the
Demonstration Program is contained in two documents:
the TER and the AAR.  The TER  contains a com-
prehensive description of  the demonstration sponsored
by the SITE Program and its results.  It gives detailed
descriptions  of the technology, the waste used for the
demonstration, sampling  and analyses during the test,
the data generated, and  the Quality  Assurance (QA)
program.

The scope of the AAR is broader than that of the TER.
The AAR includes a description of projected Superfund
applications  and estimated costs  for the  technology.
This report compiles and  summarizes the results of the
SITE demonstration, the  vendor's  design and test data,
and other  laboratory  and field  applications  of the
technology.  It discusses the advantages, disadvantages,
and limitations of the technology.

Costs of the technology  for different applications are
estimated based on available data from pilot- and full-
scale applications. The AAR discusses the factors, such
as  site  and waste characteristics,  that have a  major
impact on costs and performance.

The amount of available  data for the evaluation of  an
innovative technology  varies widely.  Data may  be
limited  to laboratory tests on synthetic waste or may
include performance data on actual wastes treated at the
pilot- or full-scale level. In addition, there are limits to
conclusions regarding Superfund applications that can be
drawn from a single field demonstration.  A successful
field demonstration does not necessarily ensure that a
technology will be widely applicable or fully developed
to  the  commercial scale.   The AAR  attempts  to
synthesize whatever information is available and draw
reasonable conclusions. This document is very useful to
those considering a technology for Superfund cleanups
and represents a critical  step in the  development and
commercialization of the  treatment technology.
For more information on the demonstration of the RCC
B.E.S.T.® technology, please contact:

1.  EPA Project Manager for the SITE demonstration
    test:

    Mr. Mark C. Meckes
    U.S. Environmental Protection Agency
    Risk Reduction Engineering Laboratory
    26 West Martin Luther King Drive
    Cincinnati, Ohio  45268
    (513) 569-7348

2.  Process vendor:

    Mr. Lanny Weimer
    Resources Conservation Company
    3630 Cornus Lane
    Ellicott City, Maryland  21043
    (301) 596-6066

    Mr. George Jones
    Resources Conservation Company
    3006 Northup Way                            .
    Bellevue, Washington 98004-1407
    (206)828-2400

3.  GLNPO Remedial Programs staff:

    Mr. Stephen Garbaciak, Jr.
    U.S. Environmental Protection Agency
    Great Lakes National Program Office
    77 West Jackson Boulevard
    Chicago, Illinois   60604-3590

-------
                                               Section 3
                                Technology Applications Analysis
3.1     Introduction

This section addresses the applicability of the RCC
B.E.S.T.® technology to contaminated soils, sludges, or
sediments for which PCBs and PAHs are the pollutants
of primary interest. Recommendations are based on the
results obtained from the SITE demonstration as well as
additional  data from  RCC.   The  results   of  the
demonstration,  which  allow an  evaluation   of  the
effectiveness of the technology in treating contaminated
sediment from the Grand Calumet River, are presented
in the body of this report.  Additional information on
the B.E.S.T.®   technology,  including a brief  process
description, vendor's claims, a summary of the dem-
onstration results, and brief descriptions of previous case
studies,  is provided hi Appendices A through D.

This demonstration was a cooperative effort between the
EPA - Region V,  GLNPO, the COE, and the SITE
Program.  GLNPO is responsible for undertaking a 5-
year study and demonstration program for contaminated
sediments known as the Assessment and Remediation of
Contaminated Sediments Program. The Assessment and
Remediation of Contaminated Sediments Program is
operated through a Management Advisory Committee
made up  of the chairpersons of the technical work
groups,  and the technical work groups themselves. The
Assessment  and   Remediation   of  Contaminated
Sediments  Program is  also involved in  evaluating
remedial activities of other groups such as the Superfund
Program and the COE to evaluate the effectiveness of
those activities.
3.2    Conclusions

The RCC B.E.S.T.®  solvent  extraction  technology
physically separates  organic contaminants  from an
inorganic matrix, thereby reducing the volume of wastes
which require further treatment. The process consists
of  multiple  extraction cycles  followed  by solvent
recovery,  oil polishing (removing virtually all of the
triethylamine from  the  oil product by  evaporation),
solids drying, and water stripping.   This technology
utilizes the solvent properties and variable miscibility of
triethylamine in water to separate oil-contaminated soils,
sediments, or sludges into their oil, water, and solids
fractions.   A more detailed  process  description  is
provided in Appendix A.

The  majority of the organic  contaminants  initially
present in the sludge, sediment, or soil are concentrated
in the oil fraction. This fraction may require additional
treatment  (e.g.,  incineration) to destroy or immobilize
these contaminants.   Whether the  water and solids
fractions can be  disposed  of or  discharged  without
additional treatment depends on the treatment efficiency
of the B.E.S.T.® process and the presence of inorganic
contaminants. The demonstration test was performed to
demonstrate  the ability of the B.E.S.T.* system to
remove PAHs and PCBs from contaminated sediments
in the Grand Calumet River.  This test was conducted
at a Gary, Indiana location adjacent to the river.

During the demonstration test, samples were collected
and analyzed separately by the SITE Program and by
RCC.   The  two sets of analytical results were in,
excellent agreement. A review of the demonstration test
indicates the following results:

•   Contaminant  reductions of 96  percent for total
    PAHs and greater than 99 percent for total PCBs
    were  achieved  for  Sediment  A.   Contaminant
    reductions  of greater than 99  percent for total
    PAHs and greater than 99 percent for total PCBs
    were achieved for Sediment B.

•   Removal efficiencies in excess of 98 percent were
    realized by both sediments for O&G.

•   Mass  balances  conducted  for total materials
    (including triethylamine) in the B.E.S.T.® system
    achieved closures of 99.3 percent and 99.6 percent
    for Sediment A and Sediment B, respectively.  Mass

-------
    balances comparing feed  and  product streams
    (excluding triethylamine) achieved closures  of 108
    percent and  114  percent  for Sediment A and
    Sediment B, respectively.

•   The products generated using the B.E.S.T.® process
    compared favorablywith RCC's claims in regards to
    residual  triethylamine   concentrations.   Treated
    solids produced during the optimum treatment runs
    for Sediment B  had   an  average  triethylamine
    concentration  of 103 mg/kg.  Water  generated
    during these runs had a triethylamine concentration
    of 2.2 mg/L or less, while the oil product collected
    at the end of all Sediment B treatment runs had a
    triethylamine concentration of 733 mg/kg. Because
    very little oil product  was generated  during the
    treatment of  Sediment  A, the  Sediment A oil
    product  was  not  processed   to  reduce  its
    triethylamine  • concentration.      Solid  product
    generated from  the optimum treatment runs for
    Sediment  A  realized   an   average  residual
    concentration  of 45.1 mg/kg, while water products
    from the optimum treatment runs for Sediment A
    had triethylamine  concentrations  of 1.0  mg/L or
    less.

•   The treatment cost for the remediation of con-
    taminated  soil,  sediment,  or sludge  using  the
    proposed 186-tpd,  full-scale B.E.S.T.® system  is
    estimated at $94 per ton if  the system is on line 80
    percent of the tune or $112 per ton if the system is
    on line 60 percent of the time.

The vendor's claims  for the  B.E.S.T.®  process are
presented  in Appendix B  and detailed  results  are
presented in Appendix C.
 demonstration.  Sediment A was a screened, homog-
 enized composite of sediment samples collected from
 Transect 28, which is downstream from an oil-skimmed
 settling lagoon.  This lagoon received wastewater from
 primary bar plate  mills and  a basic  oxygen process
 (BOP)  shop.  This location was chosen to acquire  a
 sample having a decreased organic concentration and a
 relatively high metals concentration.

 The  high  metals  concentration  of  Sediment A was
 designed  to  provide  an evaluation  of the B.E.S.T.®
 system's ability  to  reduce  the teachability of metals.
 Despite its high metals concentration, the untreated
 sediment passed the TCLP test for metals, so it was not
 possible to draw any significant conclusions regarding
 the   effects  of  the  B.E.S.T.®  process  on  metals
 teachability.  The metals concentrations in the treated
. solids were similar to those in the sediment, indicating
 that no significant amount of metals was removed by the
 B.E.S.T.® system.

 Sediment B was a screened, homogenized composite of
 sediment samples collected from Transect 6. Transect 6
 is located downstream of a coke plant and upstream of
 Transect  28.   O&G  were visually observed in the
 sediment collected during recent bottom sediment core
 sampling in  the  vicinity of Transect 6.   Sediment  B
 contained high levels of petroleum-based contaminants
 (i.e., O&G  and  PAHs) but low  levels of  metals.
 Analytical data characterizing Sediment A and Sediment
 B, according to the main parameters of interest for this
 demonstration  test,   are   presented  in  Table   2.
 Concentrations in Table 2 are given on a dry weight
 basis for all parameters except moisture.

 Table 2.  Characterization of the Untreated Sediment
         (Averages from Three Optimum Runs)
3.3    Technology Evaluation

The  objective of  this SITE  demonstration was to
demonstrate the effectiveness of the B.E.S.T.® solvent
extraction technology on two sediment samples having
different contaminants and/or contrasting concentration
levels of the same contaminants. The contaminants in
the river sediments include metals, organic compounds
such  as PAHs and  PCBs,  and inorganics  including
cyanide.

The sediment collection points are shown in Figure 1.
Sediments were collected from two locations  (Transect
28 and Transect 6) along the  Grand Calumet River
using hollow  aluminum  tubes which  were , driven
approximately 5 feet into the soft river  bottom.   The
"cores" from the tubes were emptied into buckets and
transported  to the demonstration  location.  These
sediment samples were obtained by the COE for the
  Parameter
                     Sediment A
                                      Sediment B
Total PCBs, mg/kg
Total PAHs, mg/kg
O&G, mg/kg
Moisture, percent
12.1
550
6,900
41
425
70,900
127,000
64
 To characterize the materials used hi this demonstration
 further, particle  size analyses were  performed for the
 untreated sediment  (by wet  sieve testing)  and the
 treated solids (by  dry sieve  testing).   Particle  size
 distributions were prepared to demonstrate the ability of
 the B.E.S.T.® system to treat materials containing large
 fractions of fine particles.  Approximately  40 percent
 and 57 percent of the particles in Sediments A and B,
 respectively, had diameters of 75  to  425  Mm-   The
 particle size distributions also indicated that 28 percent

-------
             EXPLANATION
          Industrial effluent outfall
       0 Municipal effluent outfall
       *- Direction of flow
                                                                           Collection Location for
                                                                                Sediment B
                                                                                (Transect 6)
                                              Collection Locationfor
                                                   Sediment A
                                                  (Transect28)
  Gary Wastewater Treatment
         • Plant (GWTP)
                     JND EAST-WEST
Figure 1. Sediment Collection Locations - East Branch of the Grand Calumet River.
and 38 percent of the particles in Sediments A and B,
respectively, had diameters of less than 75 /zm.

The demonstration site was located hi Gary, Indiana
near the Grand Calumet River.  The  Grand Calumet
River drains approximately 77 square miles of Lake and
Porter counties and discharges to southwestern Lake
Michigan via the Indiana Harbor and Canal.  Major
industries along the waterway include primary steel and
petrochemical industries.  The river's headwaters are at
the Grand Calumet River Lagoon at Marquette Park in
northwest Gary.  This  "East Branch" of  the  Grand
Calumet  River  flows   westward  through  heavily
industrialized sections of Gary and East Chicago.  The
Grand Calumet River is fed primarily by municipal  and
industrial wastewater (up to 90 percent of its flow)  and
a fairly rapid current is produced by these discharges
along several outfalls  throughout  the  river's course.
Flow is diverted due north via the Indiana Harbor and
Canal, which discharges at East Chicago.

The Grand Calumet River/Indiana Harbor and Canal
area has a long history of water quality problems and
has been designated by EPA as an area of concern. The
area of concern also includes nearshore Lake Michigan
in Lake County, Indiana.  Previous studies have been
conducted by EPA Region V, the Indiana Department
of Environmental Management  (IDEM), and the COE.
From these  studies, the COE  has  estimated that the
entire area of concern contains 3.5 to 4.0 million cubic
yards of contaminated sediments and the East Branch of
the Grand Calumet River contains 1.4 million  cubic
yards of contaminated sediments.

-------
The majority  of the  RCC B.E.S.T.®  pilot plant  was
constructed on two portable skids. One skid contained
the B.E.S.T.®  process equipment including the premix
tank, extractor/dryer,  centrifuge, centrate filters,  oil
decanter, stripping units, solvent evaporator, pumps, and
valves  required  to process contaminated sludges or
solids.  Utility systems which supported the pilot plant
were contained  on  a second skid.   These systems
included a refrigeration unit and a cooling water system.
Steam, nitrogen, and  instrument air were provided in
separate units which were contained in a support trailer.

The process  units  utilized  three   levels   of spill
containment, the first being the pilot unit piping itself.
Secondary  containment  consisted of  a 25£-inch-deep
stainless steel  pan underlying the entire unit.  Tertiary
containment consisted of a flexible membrane liner with
raised  edges forming  a berm.  This liner was situated
under the entire trailer unit in which the pilot plant was
enclosed.

The B.E.S.T.® pilot-scale system is designed to process
soil, sediment, or  sludge feeds.  The  system  separates
organic contaminants from soils, sludges, and sediments,
thereby potentially reducing the volume of the hazardous
waste that must  be treated. The technology uses amine
solvents; triethylamine is most commonly chosen  and
was the solvent  used during the SITE demonstration.
Triethylamine is reported by RCC to be an excellent
solvent for treating hazardous wastes because it exhibits
several characteristics that  enhance its use in a solvent
extraction system. These characteristics include:

•   A high vapor pressure; therefore the solvent can be
    easily recovered from  the extract (oil, water,  and
    solvent) via  simple steam stripping.

•   Formation of a low-boiling azeotrope with water;
    therefore  the solvent can be recovered  from the
    extract to very low residual levels, typically less than
    100 parts  per  million (ppm).

•   Triethylamine is alkaline (pH = 10); therefore some
    heavy  metals  are converted to metal hydroxides,
    which can precipitate and exit the process with the
    treated solids.
RCC's B.E.S.T.® pilot unit requires a feed stream that
is screened to less than or equal to Vz inch, although the
SITE demonstration utilized feed screened to less than
or  equal to  Vi inch  to  minimize  abrasion  to  the
equipment.  The technology is capable of handling either
"soil" type material or "sludge"  type  material, which
determines the process path used in the pilot unit.  RCC
classifies material low in oil and water contents  as "soil"
and material having  high  oil and water  content as
"sludge."   The  sediment  treated during the  SITE
demonstration was considered a sludge by RCC.  The
vendor claims that the technology is suitable for treating
inorganics   contaminated   with   complex   organic
compounds  including  PAHs, PCBs,  pesticides, and
herbicides.

RCC has a full-scale unit  that  is capable of treating
sludge but cannot handle soils. The proposed full-scale
unit discussed in the following sections will be capable
of treating either soil or sludge.

Limited  testing  to  assess  the biodegradability  of
triethylamine in the treated solids was conducted by the
SITE evaluation  team as part of the demonstration.
Samples of the treated solids were mixed with clean soil
that was intended as a source of naturally-occurring soil
bacteria. This soil mixture was split into two cells and
the biological activity in the control cell was inhibited by
the addition of mercuric chloride. This biodegradation
study produced no evidence that triethylamine present
at 25 to 100 ppm is biodegraded in this soil within 2
months of application. This study should not, however,
be  considered  evidence  that  triethylamine  is  not
biodegradable in soil, since no  attempt  was made to
optimize treatment parameters  such as pH, nutrient
availability, etc. The lack of biodegradation is supported
by  a previous study which used acclimated, activated
sewage sludge [1].  In contrast, it has been reported that
triethylamine is degraded  in  an Aerobacter bacterial
culture  [2].    These  results indicate  that  residual
triethylamine concentrations will not quickly biodegrade
in this  soil without the  addition of nutrients and/or
acclimated microbial strains.

The following paragraphs present information available
on the B.E.S.T.®  system and  its  performance and
summarize observations and conclusions from the SITE
demonstration.
3.4    Ranges of Site Characteristics Suitable
        for the Technology

3.4.1    Site Selection

The  pilot-scale  system  used  during  the  SITE
demonstration is fully mobile and is contained on two
skids.   RCC  states that the full-scale system will be
transportable.  It will be transported in sections and
reassembled  on or  near  the  treatment site.   The
B.E.S.T.® system is applicable to sites containing soil,
sediment, or sludge contaminated with organics.  Any
site on which the full-scale system is to be assembled
should also meet the physical requirements described in
the following  subsections.

-------
3.4.2    Surface,   Subsurface,   and   Clearance
        Requirements

A level, graded area capable of supporting a pad holding
the equipment is needed.  The foundation must be able
to support the weight of the B.E.S.T.® system and all
other equipment requiring a pad.  The dimensions of
the pad or pads will depend on the configuration of the
system. The total weight of the system and all auxiliary
equipment is  expected  to be approximately 120 tons.
The operating weight of the system, which includes the
weight of the material being treated, is estimated to be
1,100 tons.

The site  must be cleared to  allow construction and
access to  the facility.  It is estimated that the full-scale
B.E.S.T.® system will be transported in 11 truckloads.
The access road must be  at least 8 feet wide to admit
the trucks.   The  road  should  also  be capable  of
supporting loads up to 40,000 pounds.
3.43    Topographical Characteristics

The topographical characteristics of the site should be
suitable for the assembly of the B.E.S.T.® system.  If no
indoor storage is available at the site, a building must be
constructed for spare parts storage.
3.4.4    Site Area Requirements

At least 1 acre should be available for the assembly of
the B.E.S.T.® system.  Once constructed, the system,
storage tanks,  and  auxiliary  equipment will  occupy
approximately 10,000 square feet (0.23 acres). For much
of this area, a  pad will be required to support the
system.  In addition,  the  National Fire  Prevention
Association (NFPA) requires that a perimeter be esta-
blished around the solvent extraction equipment.  This
will increase the area required by the system.  A separ-
ate area should also be  provided for staging wastes for
treatment and for storing treated solids.  The required
site dimensions will depend on the configuration of the
full-scale system, which  may be somewhat flexible.
3.4.5    Climate Characteristics

This treatment technology may be used in a broad range
of climates,  although  prolonged periods of freezing
temperatures may interfere with soil excavation and may
require system modifications. Hot or cold climates may
also impact energy costs for treatment, as specific liquid
temperatures are required for the extractions.
3.4.6   Geological Characteristics

Generally, any site that is sufficiently stable to handle
the weight of the system is suitable for this technology.
3.4.7   Utility Requirements

The only utilities required by the full-scale system are
electricity and water.  The site should have at least 430
kilowatts of 3-phase, 440-volt electrical power available.
Potable water requirements  are 1,020 gallons per day
(gpd) for treatment, decontamination, etc. Steam and
compressed air will be provided by a boiler and an air
compressor that will be transported with the system.
3.4.8    Size of Operation

The pilot-scale B.E.S.T.® system was primarily contained
on two skids and operated at an average treatment rate
of approximately 90 pounds of contaminated sediment
per day during the SITE demonstration. The proposed
full-scale system will be much larger and will operate at
a nominal processing rate of 186 tpd.
3.5    Applicable Media

The RCC B.E.S.T.® solvent extraction system is capable
of physically separating organic contaminants such as
PCBs, PAHs, and O&G from inorganic media.  Media
that can be treated by the pilot-scale system used during
the SITE demonstration include soils, sediments, and
sludges.    The  prototype full-scale  system  is  only
applicable to sludges, but the proposed full-scale system
will be applicable to soils and sediments as well.

This technology has been demonstrated to be effective
in removing organic contaminants from varied sources,
including   wastes   generated   by   primary  steel
manufacturing,   aluminum manufacturing, petroleum
refining, machining operations, and wood treating.  A
summary  of the pilot-scale testing projects appears in
Appendix D.

The effectiveness of treatment  is illustrated by  the
results of this demonstration project and by other case
studies. This demonstration showed that the B.E.S.T.®
process removed 96 percent of the PAHs,  greater than
99 percent of the PCBs, and greater than 98 percent of
the O&G  from the  contaminated sediments.  Other
process  evaluations   (discussed  in  Appendix  D)
documented PCB removals ranging from 98.8 percent to
99.88  percent, PAH removals ranging from 99 percent
to 99.21 percent, and an O&G removal of 99.65 percent.

-------
3.6    Regulatory Requirements

Operation of the B.E.S.T.* solvent extraction system for
treatment of contaminated  soil,  sediment, or sludge
requires compliance with certain Federal, state, and
local regulatory standards and guidelines.  Section 121
of  the  Comprehensive  Environmental  Response,
Compensation,  and Liability Act  (CERCLA) requires
that, subject to specified exceptions, remedial actions
must be undertaken in compliance with ARARs, Federal
laws,  and more stringent promulgated state laws  (in
response to releases or threats of releases of hazardous
substances, pollutants, or contaminants) as necessary to
protect human health and the environment.

The ARARs  which must  be  followed in treating
contaminated media onsite are outlined in the Interim
Guidance on Compliance with ARAR, Federal Register,
Vol. 52, pp. 32496 et seq.  These are:

•   Performance,  Design,   or   Action-Specific
    Requirements.  One example is the  Clean Water
    Act (CWA) pretreatment standards for discharge to
    publicly-owned treatment works (POTWs).  These
    requirements  are  triggered  by  the  particular
    remedial activity selected to clean a site.

•   Ambient/Chemical-Specific Requirements.  These
    set hcalth-risk-based concentration limits based on
    pollutants and contaminants, e.g., emission  limits
    and ambient air quality standards.  The system must
    comply with  the most  stringent ARAR for each
    parameter.

•   Locational Requirements.  These set restrictions on
    activities because of site locations and environs.

Deployment of the B.E.S.T.® system will be affected by
three main levels of regulation:

•   Federal EPA air and water pollution regulations

•   State air and water pollution  regulations

•   Local   regulations,  particularly   Air   Quality
    Management District requirements

These  regulations  govern  the  operation   of   all
technologies. Other Federal, state, and local regulations
arc discussed hi  detail in the following paragraphs as
they apply to the performance, emissions, and residues
evaluated   from   measurements  taken  during  the
demonstration test.
3.6.1    Federal Regulations

3.6J.I  Clean Air Act (CAA)

The CAA of 1990 regulates major sources of air toxics
from specific source categories. The CAA revisions of
1990 included  a statutory list of 189 substances which
require  regulation as air toxics.  A draft list of source
categories was also released in 1990. Triethylamine is
one of the 189 listed air toxics  and solvent extraction is
on  the  draft  list  of source  categories.   The  1990
amendments define a "major source" as one which emits
10 tons  per year of a single air  toxic or 25  tons per year
of any  combination of air toxics.   The  triethylamine
emission rate  from the proposed full-scale B.E.S.T.®
system  has not yet  been determined,  but the process
may be subject to regulation under  the 1990 CAA
revisions.

During  the demonstration test, vent gases were filtered
by  primary  and secondary activated carbon canisters.
The air  between the two carbon canisters was monitored
daily with colorimetric tubes having detection limits of
3.5 ppm triethylamine. Triethylamine was detected at
over 3.5 ppm hi two instances during the demonstration.
In  each instance, the primary carbon  canister  was
replaced  immediately    and   the   triethylamine
concentration   returned  to below 3.5  ppm.    The
concentration of triethylamine at the vent gas outlet was
not measured at over 0.2 ppm at any time during the
demonstration.
 3.6.1.2 Comprehensive   Environmental   Response,
        Compensation, and Liability Act

 CERCLA of 1980, as  amended by  the Superfund
 Amendments and Reauthorization Act (SARA) of 1986,
 provides for Federal funding to respond to releases of
 hazardous substances to  air, water, and land.  Section
 121 of SARA, Cleanup Standards, states a strong
 statutory preference for remedies that are highly reliable
 and  provide  long-term  protection.     It   strongly
 recommends that remedial action use onsite treatment
 that "permanently and significantly reduces the volume,
 toxicity,  or  mobility of  hazardous substances."   In
 addition,  general factors which must be addressed by
 CERCLA remedial actions include:

 •   Overall. protection  of  human health  and  the
     environment

 •   Compliance with ARARs
                                                      10

-------
•   Long-term effectiveness and permanence

•   Reduction of toxicity, mobility, or volume

•   Short-term effectiveness

•   Implementability

«   Cost

•   State acceptance

•   Community acceptance
The long-term effectiveness of the B.E.S.T.® system is
demonstrated by  its apparent  ability to  achieve  a
permanent and significant  reduction in the  volume of
hazardous waste associated with soils, sediments,  and
sludges contaminated with organics. During treatment,
the majority of the organic contaminants are extracted
from the soil,  sediment, or sludge  and concentrated
within the oily product.  By removing the contaminants
from the soil, sediment, or sludge and concentrating
them within the oily fraction, the  technology perman-
ently isolates these contaminants from the treated solids,
potentially enabling them to be backfilled onsite.  In
addition,  a significant  reduction  in  the  volume of
material  requiring additional treatment and/or disposal
is realized.   Thus,  a  "permanent  and  significant"
reduction in the threat posed by the waste is realized.

The  B.E.S.T.*  SITE  demonstration  was  originally
designed to evaluate reduction in metallic contaminant
mobility.  One of the goals of the demonstration was to
evaluate  the  technology's  potential  ability  to  change
metallic compounds to less toxic or  less leachable forms.
The treated  solids and the  untreated  sediment  both
passed the TCLP test for metals, so it was not possible
to draw any significant conclusions  regarding the effects
of the B.E.S.T.® process on  the  mobility of metallic
contaminants.

Short-term effectiveness and overall protection of human
health and the  environment can  be  evaluated by
examining the  emissions from the B.E.S.T.®  system.
Solvent is  recovered and recycled within the  system,
eliminating the need for waste solvent disposal.   The
water and oil products are  decanted and processed (by
solvent evaporation and water stripping) to minimize
their solvent  concentrations, to  allow  reuse  of the
triethylamine, and to reduce the likelihood that the
water product will be classified  as a hazardous waste.
Since the process operates in a closed loop with one
small vent for removal of non-condensible gases, air
emissions are minimal. Air monitoring results from the
SITE demonstration are discussed in Appendix C and
subsection 3.6.1.1.
The B.E.S.T.®  system  appears  to be  capable  of
compliance with the known ARARs listed in Subsection
3.6.  Locational requirements and local regulations are
site-specific, and they must be evaluated individually for
each site.

The B.E.S.T.® solvent  extraction process is potentially
capable of significantly reducing the toxicity of soils,
sediments, and sludges contaminated with organics such
as  PAHs  and  PCBs.   Depending on the  other
contaminants  present  and  the  treatment  efficiency
achieved, the treated solids may be suitable for onsite
disposal  without  further treatment.    During  the
demonstration test,  the  B.E.S.T.® solvent  extraction
technology removed greater than 96 percent and greater
than 99 percent, respectively, of the PAHs and PCBs
from the bottom sediment of the Grand Calumet River.
If metals  are present,  the treated solids may require
additional treatment such as fixation.  The  B.E.S.T.*
system may be capable of changing the chemical nature
of the metals into a less leachable form. However, since
the untreated sediment passed the TCLP test for metals,
this could not be assessed during the demonstration test.

The nature of the contaminants  present also determines
the disposal requirements for the water and oil products.
In general,  depending on the contaminants initially
present and the  effectiveness  of the stripping steps
employed, water products will often be  suitable for
discharge  to a local POTW. Although the oil product
may be suitable for use as a fuel, this product is more
likely to require treatment or disposal as  a hazardous
waste.  During the demonstration test, the elevated pH
of the water product and PCB contamination within the
oil fraction caused these materials to be designated as
Resource Conservation and Recovery Act (RCRA) and
Toxic  Substances   Control  Act  (TSCA)  wastes,
respectively. The elevated pH of the water product was
due to the addition of excessive caustic  during water
stripping.   The average  pHs  of  the water products
generated during the treatment of Sediments A and B
were 12.3  and 11.9, respectively.  RCC claims that the
water product generated by the B.E.S.T.® system should
not typically exhibit a pH greater than 11 after operators
have become more  familiar with  the caustic addition
requirements of a given feed stream.  Depending on the
B.E.S.T.®  system configuration used and on the specific
contaminants present in the feed material, an additional
water  treatment step  may  be   needed during future
applications of the technology  to qualify the product
water for discharge to a local POTW.

There  are a number of basic site requirements for the
B.E.S.T.®  solvent extraction system.  The  system must
not  be operated in close  proximity to  combustible
materials. Area requirements for staging of treated and
untreated  wastes will also make  it difficult to implement
this technology at sites with limited space. Furthermore,
                                                      11

-------
the B.E.S.T.® full-scale system is rather complex and is
not easily or quickly assembled or disassembled.  As a
result, the per  ton remediation cost (including site
preparation, system mobilization, startup, treatment, and
demobilization) will be higher for small sites than for
large sites. Unit costs for various treatment scenarios
are provided in Section 4.

State acceptance and community acceptance are the last
two factors that must  be  addressed  by CERCLA
remedial actions. It is not possible to predict whether
a specific state  or  community will readily accept the
B.E.S.T.* system, but potential  community concerns
include the flammability of the solvent, the obnoxious
odor of the solvent, and potential explosion hazards.
3,6.1.3 Resource Conservation and Recovery Act

RCRA is  the  primary Federal legislation  governing
hazardous waste activities. Although a RCRA permit is
not  required  for  hazardous  waste  treatment   on
Superfund sites, the treatment systems must meet all of
the substantive requirements of RCRA. Administrative
RCRA requirements such  as reporting  and record-
keeping, however, are not applicable for onsite activity.

Subtitle C of RCRA contains requirements for genera-
tion,  transport, treatment,  storage,  and disposal of
hazardous waste. Compliance with these requirements
is mandatory for CERCLA sites producing  hazardous
waste onsite.

The water product generated during the demonstration
test was a RCRA-regulated material due to its elevated
pH. RCC states that the high pH of the water product
was caused by  excessive  caustic added during water
stripping.    The  water  product  generated by  the
B.E.S.T.®  system  should not typically exhibit  a pH
greater than 11. The nature of the water product will
depend on the B.E.S.T.® system configuration used and
the contaminants present  in the waste.  At many sites,
however, the system should be capable of generating a
water  product amenable for  discharge  to  the  local
POTW.  In general,  the  production of  hazardous
residuals is  dependent on  the contaminants present
within the  untreated solids.  Since the majority of the
contamination collects within the oil product,  this matrix
is more likely than the water product to be regulated as
a hazardous waste.

Since steam stripping and solvent evaporation are used
to  recover  any residual triethylamine  present in  the
water  and oil separated from the extraction solution,
solvent concentrations in  system products are typically
quite low.  Average triethylamine concentrations of 103
mg/kg, <1 mg/L, and 730 mg/kg for solid,  water, and
oil products, respectively, were generated  during  the
treatment of Sediment B.  Solid and water products
generated from the treatment of Sediment A realized
residual triethylamine concentrations of 45.1 mg/kg and
1.1 mg/L, respectively. Because this sediment contained
very little oil, excess triethylamine could not be removed
from the oil, and the triethylamine concentration in the
Sediment A oil product is not considered representative
of a typical product.

In order to maintain compliance with RCRA, sites em-
ploying the B.E.S.T.® system to treat hazardous wastes
must obtain an EPA generator identification number
and observe storage requirements stipulated under 40
CFR 262.  Alternatively,  a Part B Treatment, Storage,
and Disposal  (TSD) permit of interim  status may be
obtained.  Invariably, a hazardous waste manifest must
accompany offsite shipment of waste, and transport must
comply with Federal Department of Transportation
hazardous  waste  transportation regulations.   Without
exception, the receiving TSD facility must be permitted
and in compliance with RCRA standards.

The technology or treatment standards applicable to the
media produced by the B.E.S.T.® system  (treated solids,
product oil, and product  water) will be  determined by
the characteristics of the waste treated and the material
generated.   The RCRA  land disposal restrictions (40
CFR  268)  preclude the land disposal of hazardous
wastes which fail to meet the stipulated treatment stan-
dards. Wastes which do not meet these standards must
receive additional treatment  to bring the wastes into
compliance with the standards prior to land disposal,
unless a variance is granted.  The following residuals
were produced during the SITE demonstration:  a water
product classified as a RCRA waste due  to elevated pH
levels, an oil product that was a TSCA waste because it
contained PCBs,  and a potentially non-regulated solid
product.
3.6.1.4 Clean Water Act

The CWA regulates direct discharges to surface water
through the National Pollutant Discharge Elimination
System (NPDES) regulations. These regulations require
point-source  discharges   of  wastewater  to  meet
established water quality standards.  The  discharge of
wastewater to a sanitary sewer requires  a discharge
permit or, at least,  concurrence from state and local
regulatory  authorities  that  the   wastewater  is  in
compliance with regulatory limits.

The nature of the product, wash, and rinse  water is site-
specific; these matrices may be deemed hazardous waste
at some sites.  Although the product water generated
during the SITE demonstration was not suitable for
release to the local  POTW due to elevated pH  levels,
this was  simply  due to addition of  excessive caustic
                                                      12

-------
during water stripping.  It is projected that the system
will  typically generate  a  water product  suitable  for
discharge to an industrial or municipal water treatment
facility. Equipment rinse water from  decontamination
operations  during the demonstration  was suitable for
discharge.  In the commercial-scale system, the water
product will be generated at a continuous flow rate of
approximately 19 gallons per minute (gpm).  Wash and
rinse water  production will  be  dependent  on  the
frequency of decontamination as well as the extent of
the contamination present.
3.6.1.5 Safe Drinking Water Act (SDWA)

The SDWA establishes primary and secondary national
drinking water standards.  CERCLA  refers to these
standards and Section 121(d)(2) explicitly mentions two
of these standards for surface water or groundwater—
Maximum  Contaminant  Levels  (MCLs) and Federal
Water Quality Criteria. Alternate Concentration Limits
may be used when conditions of Section 121 (d)(2)(B)
are met and cleanup to MCLs or other protective levels
is not practicable. Included in these sections is guidance
on how these requirements may be applied to Superfund
remedial actions.   The guidance, which is based on
Federal requirements and policies, may be  superseded
by  more stringent promulgated state requirements,
resulting in the application of even stricter standards
than those  specified in Federal regulations.
3.6.1.6 Toxic Substances Control Act

Materials containing PCBs at concentrations of 50 ppm
or greater are regulated by TSCA, which addresses
disposal requirements in relation to the concentration of
PCBs in the waste. The oil product generated during
the demonstration test was a TSCA-regulated waste.
Because   organic  contaminants  from  the feed  are
concentrated into the  oil product,  it is likely that the oil
product  will be  a TSCA-regulated waste whenever
significant quantities of PCBs are present in  the feed.
For example, consider Sediment A, which contained 12
ppm PCBs. The concentration of PCBs in the Sediment
A oil product was approximately 190 ppm and would
have been higher if more of the residual triethylamine
had been removed from the oil.  In cases such as this,
the untreated material is not a TSCA-regulated waste
but a TSCA-regulated oil product is generated during
treatment.
3.62    State and Local Regulations

Compliance with ARARs may  require meeting  state
standards that are more stringent than Federal standards
or that are the controlling standards in the case of non-
CERCLA treatment activities.  Several types of state
and local regulations which may affect operation of the
B.E.S.T.® system are cited below:

•   Permitting requirements for construction/operation
•   Limitations on emission levels
•   Nuisance rules
3.7    Personnel Issues

3.7.1    Training

Personal protective equipment (PPE) levels for this
demonstration  were  designated  according to  the
potential hazards associated  with  each work activity.
Equipment preparation, test  start-up, and  equipment
decontamination activities were performed in Level D
PPE. Level C PPE was required for sediment/chemical
mixing and sample collection at the demonstration unit.
All personnel are also required to be trained with 40
hours of Occupational Safety and Health Administration
(OSHA) training covering PPE application, safety and
health,  emergency  response  procedures, and quality
assurance/quality  control  (QA/QC).     Additional
training  addressing the  site  activities,  procedures,
monitoring,  and   equipment  associated   with  the
technology is also necessary. Training provided prior to
the  operation  of  the  system included information
regarding  emergency  evacuation  procedures;  safety
equipment locations; the boundaries of the exclusion
zone, contaminant reduction zone, and support  zone;
and PPE requirements. These training procedures were
observed throughout the demonstration.
3.72    Health and Safety

Personnel should be instructed about potential hazards,
such  as the flammability and  explosiveness of the
solvent, associated with the operation of the B.E.S.T.®
system.     Health  and  safety   training  covering
recommended safe work practices, standard emergency
plans and procedures, potential hazards and provisions
for exposure monitoring, and the use and care of PPE
should be required. Onsite personnel should participate
hi a medical monitoring program.  Health and safety
monitoring  and incident  reports should be  routinely
filed, and records of occupational illnesses and injuries
(OSHA  Forms  102  and 200) should  be  maintained.
Audits ensuring compliance with the health and safety
plan should be carried out.

Proper PPE should be available and properly utilized by
all onsite  personnel.   Different  levels of  personal
protection  will  be required  based on the  potential
hazard associated with the site and the  work activities.
                                                      13

-------
Site  monitoring should be conducted to identify the
extent of hazards and to document exposures at the site.
The  monitoring  results  should  be maintained  and
posted.  During the demonstration test, concerns were
raised pertaining to the possible exposure of workers via
inhalation and/or direct  contact with  contaminants
present  in the untreated  sediment (e.g., PAHs and
PCBs) and process chemicals used in  the B.E.S.T.®
solvent extraction technology (e.g., triethylamine and
sodium hydroxide).  In response to these concerns, air
purifying  respirators   equipped  with organic  vapor
cartridges and high-efficiency particulate (HEPA) filters
or dust  covers were required for workers  in the
immediate proximity  of  the  pilot unit and  during
chemical/feed mixing operations.

Although  the  inhalation  of  contaminated soil-dust
particles was a concern, dust exposure was not expected
to be a problem under normal weather conditions. As
a  result,  continuous  particulate  monitoring was not
performed during the demonstration test.

Air  monitoring  was  performed  to  determine the
potential  for  respiratory  or  dermal  hazards.   A
photoionization detector (PID) was used to assess the
presence of ionizable organic vapors in the ambient air.
Particular emphasis was placed on ambient monitoring
for volatile emissions attributed to the solvent employed
by RCC.   The  maximum limit  for  organic  vapor
concentration  in  the  ambient air was 10 ppm  above
background levels;  none of the measurements taken
during the demonstration test exceeded this limit.

The  health and safety practices described above were
observed throughout the demonstration.
3.73    Emergency Response

In the event of an accident, illness, explosion, hazardous
situation at the  site,  or intentional acts of harm,
assistance should be immediately sought from the local
emergency response teams and first aid or decontamin-
ation should be employed where appropriate.

To ensure  a  timely  response  in the  case of  an
emergency, workers should review the evacuation plan,
firefighting procedures, cardiopulmonary resuscitation
(CPR)  techniques, and  emergency  decontamination
procedures  before  operating  the  system.    Fire
extinguishers, spill cleanup kits, and evacuation vehicles
should be  onsite  at all  times.   Other onsite  safety
equipment will include an air horn that can be used to
alert personnel in the event of an emergency.
3.8    References

1.  Chudoba, J., et al.  Chem  Prum 19,  pp. 76-80.
    1969.      (As  referenced   in   Handbook   of
    Environmental Fate and Exposure Data, Volume 2-
    -Solvents.   P.  Howard,  Ed.  Louis Publishers,
    Chelsea, MI, 1991.)

2.  U.S. Environmental Protection Agency. Treatability
    Manual, Volume 1 (EPA 600/8-80-042).
                                                     14

-------
                                                 Section 4
                                           Economic Analysis
4.1     Introduction

The  primary purpose  of this economic  analysis  is to
estimate costs (not including profits)  for commercial
treatment utilizing the  B.E.S.T.® system.  This analysis
is based on the results of a SITE demonstration which
utilized a pilot-scale B.E.S.T.® solvent extraction system.
To  a  lesser extent,  this analysis  is  also  based  on
information from previous tests,  including a full-scale
test conducted at the General Refining site  in Garden
City, Georgia. These previous tests are described briefly
in Appendix D. The pilot-scale unit utilized during the
SITE demonstration operated at an average feed rate of
approximately 90 pounds of contaminated sediment per
day;  it is projected that the commercial unit will be
capable of treating up to 186 tons of contaminated soil,
sediment, or sludge per day.
4.2     Conclusions

The  commercial-scale B.E.S.T.® system proposed by
RCC is  designed  to remediate soils, sediments,  and
sludges contaminated with PCBs, PAHs, and other
organics. Treatment costs appear to be competitive with
other available technologies. The treatment cost for the
remediation of contaminated soil,  sediment, or sludge
using the 186-tpd B.E.S.T.® solvent extraction system is
estimated at  $112  per ton if the system, is on line 60
percent of the time or $94 per ton if the system is on
line 80 percent of the tune.
4.3    Issues and Assumptions

RCC states  that the  186-tpd B.E.S.T.®  system  is
applicable for sites having greater than 5,000 cubic yards
(approximately 5,050 tons) of soil, sediment, or sludge
containing organic contaminants. The unit should also
be considered for smaller sites when the other treatment
alternatives, such as incineration, are costly.
Important assumptions regarding operating conditions
and task responsibilities that could significantly affect the
cost estimate results  are  presented  in  the following
paragraphs.
43.1   Costs Excluded from Estimate

The cost estimates presented are representative of the
charges typically assessed to the client by the vendor but
do not include profit.

•All  costs  associated  with site preparation,  system
mobilization, startup,  and demobilization have been
excluded from the treatment cost. The costs for system
mobilization, startup, and demobilization are incurred
once at every  site and are approximately  the  same
regardless  of the quantity of contaminated material
present at the site.  These costs are therefore presented
individually as fixed costs.  Site preparation costs are
proportional to the amount of contaminated soil present
at the site.

Many other actual or potential costs have also been
excluded from this estimate.  These costs are omitted
because site-specific  engineering designs beyond the
scope of this SITE project would be required to deter-
mine those costs.  As a result,  certain functions are
assumed to be the obligation of the responsible party or
site  owner and are not included in this estimate.

The costs that are assumed to be the responsible party's
(or site owner's) obligation include the costs for items
such as preliminary site preparation, obtaining permits,
determining regulatory  requirements,   initiation  of
monitoring programs,  waste  disposal,  conducting
sampling and analyses, and post-treatment site cleanup
and restoration.  These costs tend to be site-specific and
it is left to the reader to perform calculations relevant to
each specific case.   Whenever possible,  applicable
information is provided  on these topics  so the reader
may perform calculations to obtain  relevant  economic
data.
                                                      15

-------
432    Maximizing Treatment Rate

Factors limiting the treatment rate include the feed rate
and the online percentage.  Increasing the feed rate
and/or the online percentage can reduce the unit treat-
ment  cost.   Online percentages of 60  percent,  70
percent, and 80 percent are compared in the following
analysis.   Increasing the feed  rate  beyond  186 tpd
requires   equipment modifications   which  are  not
considered in this analysis.
433    Utilities

To support the operation of the B.E.S.T.® system, a site
must have clean water available at a flow rate of at least
1,020 gpd.  The majority of this water (980 gpd) will be
added  to the extractor/dryer  as  direct steam.  The
remainder  of the water will be used hi other miscella-
neous onsite applications including cleaning and rinsing.

Electrical power is required for the operation of many
components of the B.E.S.T.® system. RCC projects that
the full-scale unit will require 40  to 70 kilowatt-hours
per ton of feed.  For the purposes  of this cost estimate,
it is assumed  that the average electricity consumption
rate will be 55 kilowatt-hours per ton of feed.

For these cost calculations, it is assumed that sufficient
water and electrical power are available at the site. The
cost of preparing a site to meet these requirements can
be high and is not included in this  analysis.  Costs
associated with connecting  the B.E.S.T.® system to the
onsite water and electrical  supplies are included in the
site preparation costs, which  are  not included in the
treatment cost.
43.4    Operating Times

It is assumed the treatment operations will be conducted
24  hours per  day,  7 days per  week.  It is further
assumed  site  preparation,   assembly,  shakedown
(preliminary operation  followed by adjustments  to
improve efficiency  or  functioning)  and testing,  and
disassembly operations will be conducted 10 hours per
day, 7  days  per  week.  Excavation  activities will be
concurrent with treatment.  Assembly, shakedown and
testing, and disassembly are assumed to require 27 days,
18 days, and 30 days, respectively.
43.5   Labor Requirements

Treatment operations are assumed to require 18 onsite
personnel:   12  system  operators  (4  per shift), 3
operations  supervisors  (1  per  shift),  and 3 safety
personnel (1 per shift).  RCC projects that six of the
onsite personnel will be employees from RCC's mam
office who will collect per diem and will require rental
cars.  Per diem  and rental car allowances will not be
required for the  other 12 onsite personnel, who will be
local hires.  It is assumed that onsite personnel will work
in three shifts  for  24-hour-per-day,  7-day-per-week
operation.  Three administrative and clerical personnel
will  also  be  required.   It   is  assumed  that  these
employees will work 40 hours per week and will not be
located onsite. Per diem and rental car allowances are
therefore not included  for  administrative  or clerical
personnel.
43.6    Capital Costs

It is assumed that the full-scale B.E.S.T.® system will be
owned and operated by RCC. It is further assumed that
capital costs incurred by RCC will be distributed across
the useful life of the system and passed on to the users.
Capital costs are  estimated for all  major equipment
included in the B.E.S.T.® system. Specific items include
11 process tanks, 3 extractor/dryers, 2 boilers, cooling
towers, an air  compressor/dryer,  a  centrifuge, an oil
decanter,  a solvent evaporator,  a solvent decanter,  a
water stripper,  a chiller, 4 heat  exchangers, 3 trailers,
and storage equipment.
43.7    Equipment and Fixed Costs

Annualized equipment cost, and costs that are estimated
as percentages of equipment costs on an annual basis,
have been prorated  for the duration of time  that the
equipment is onsite.  The costs for equipment, insur-
ance, and taxes accrue during assembly, shakedown and
testing, treatment,  and disassembly.   The  per  ton
treatment cost, however, includes only the portions of
these costs which accrue during treatment.  Contingency
costs and facility modification, repair, and replacement
costs accrue only during treatment and are included in
the per ton treatment cost.
4.4    Basis of Economic Analysis

The cost analysis was prepared by breaking down the
overall cost into 12 categories.  The categories, some of
which do not have costs associated with them for this
particular technology, are:
    Site preparation costs
    Permitting and regulatory costs
    Equipment costs
    Startup and fixed costs
    Labor costs
    Supplies costs
                                                      16

-------
•   Consumables costs
•   Effluent treatment and disposal costs
•   Residuals  and  waste  shipping,  handling,  and
    transport costs
•   Analytical costs
•   Facility modification, repair, and replacement costs
•   Site demobilization costs

The 12 cost factors  examined as they apply to the
B.E.S.T.® solvent extraction system,  along with the as-
sumptions  employed, are  described in  the following
subsections.
4.4.1    Site Preparation Costs

It is assumed that preliminary site preparation will be
performed by the responsible party (or site owner). The
amount of preliminary site preparation will depend on
the site.  Site preparation responsibilities include site
design  and  layout,  surveys and site  logistics,  legal
searches,  access rights  and  roads,  preparations  for
support and decontamination  facilities, and auxiliary
buildings.  Since these costs are site-specific, they are
not included as part of the site  preparation costs in this
cost estimate.

Collection of the contaminated material (by excavation
or dredging)  is  considered  RCC's  responsibility.
Dredging costs for sediment typically range from $7 to
$10 per cubic yard. Excavation  costs are estimated to be
approximately $36 per  ton of  soil  excavated.   The
estimated excavation costs are based on rental costs for
operated   heavy  equipment,   labor  charges,  and
equipment fuel costs.  It is assumed the minimum rental
equipment required to achieve  the design excavation
rate of 18.2 tph includes six excavators, two box dump
trucks,  and  two backhoes.   The  operation of this
equipment will consume approximately 28 gallons of
diesel fuel per hour.  This  cost  estimate assumes that
excavation activities will be conducted 40 hours  per
week. Excavation costs are itemized hi Table 3.  Costs
associated with excavation or dredging are not included
in the estimated per ton treatment cost.
Table 3. Excavation Costs
Item
Excavator
Box dump truck
Backhoe
Supervisor
Excavator operator
Dump truck operator
Backhoe operator
Diesel fuel
Cost
$l,260/week
$525/week
$585/week
$40/hour
$30/hour
$30/hour
SSO/hour
$0.90/gallon
Certain other site preparation activities will be required
at all sites.  RCC will assume responsibility for the
construction of foundations to support the B.E.S.T.®
process and all auxiliary equipment.  It is assumed that
the responsible party  or  site owner will ensure that
adequate  electrical  power  and water  supplies  are
available at the site.  RCC will be responsible for utility
lines and connections within the treatment area. RCC
estimates   a  site  preparation cost  of  $100,000 for
foundations, electrical  power, and water.  This cost  is
not included hi the per ton treatment cost.
4.42    Permitting and Regulatory Costs

Permitting  and  regulatory  costs  are  generally  the
obligation of the  responsible party (or site owner), not
of the vendor.  These costs may include actual permit
costs,  system monitoring  requirements, and/or  the
development of  monitoring and analytical protocols.
Permitting and regulatory costs can vary greatly because
they are site- and waste-specific.  No  permitting or
regulatory costs are included in this analysis. Depending
on the treatment site, however, this may be a significant
factor since permitting activities can be both expensive
and time-consuming.
4.43    Equipment Costs

Major pieces of equipment include the following:
   Eleven process tanks
   Three extractor/dryers
   Two boilers
   Cooling tower(s)
   Air compressor/dryer
   Centrifuge
   Oil decanter
   Solvent evaporator
   Solvent decanter
   Water  stripper
   Chiller
   Four heat exchangers
   Three trailers
   Storage equipment
                                                           Equipment costs also include freight, sales tax, shop
                                                           fabrication,  instrumentation,  and electrical  systems.
                                                           Cost estimates are based on vendor quotes obtained by
                                                           RCC, on independently obtained vendor quotes, and on
                                                           information  from  Plant  Design  and Economics  for
                                                           Chemical  Engineers  by  M.S.  Peters   and  K.D.
                                                           Timmerhaus, Third and  Fourth Editions  [1][2].  The
                                                           total equipment costs (including the purchase cost of the
                                                           equipment,   sales   tax,    freight,    installation,
                                                           instrumentation, and electrical systems) are estimated to
                                                       17

-------
be approximately $4,613,000 and the useful life of the
system is estimated to be 10 years. After 10 years, it is
assumed that the equipment will have a scrap value of
10 percent of its original purchase cost of approximately
$2,856,000.  This yields an annualized  equipment cost
(based on straight-line depreciation) of approximately
$433,000.

Depending  on  the  nature  of  the  feed  stream,
pretreatment   equipment  may  also   be  required.
Pretreatment equipment  is assumed to consist  of a
hammermill and a vibrating screen.  The purchase cost
for these items is estimated to be approximately $74,700.

It is assumed no  rental  equipment will be required for
operation.   Support equipment is included  in the
equipment costs  provided above.  Support equipment
refers to pieces of purchased equipment necessary for
operation but not integral to the system.

The projected  full-scale B.E.S.T.® solvent  extraction
system  will  be   capable of  treating  186  tpd  of
contaminated soil, sediment, or sludge. System effluents
will  include oversized residuals (if oversized materials
are  present in the  feed), the treated solids,  an  oil
product, and an aqueous product. It is projected that
the aqueous product will be suitable for discharge to a
municipal or industrial wastewater treatment facility.

The annualized equipment cost is prorated to the actual
time the system is commissioned to remediate  a
contaminated material (including assembly, shakedown
and  testing, treatment, and disassembly). The portion of
this  cost that  is accrued during  treatment  is  then
normalized  relative  to  tons  of  feed treated  and
incorporated into the per ton  treatment cost.  The
equipment costs  accrued  during assembly, shakedown
and  testing, and disassembly  are included  in the
estimated costs for those functions.
4.4.4    Startup and Fixed Costs

Mobilization includes both transportation and assembly.
The BJE.S.T.* system will be transportable, but it is
large  and  its relocation will therefore  require  a
significant amount of time  and  planning.  For the
purpose  of  this  estimate,  transportation costs  are
included with mobilization rather  than demobilization
activities. Transportation activities include moving the
system, the solvent, and the workers to the site.  As a
rough estimate, it is assumed that the commercial-scale
B.E.S.T.® system can be transported in 11 truckloads.
Assembly (field installation)  consists of unloading the
system from the trucks and trailers and reassembling it.
RCC estimates a total mobilization cost (transportation
and assembly) of $500,000, which is not included hi the
per ton treatment  cost.
This cost estimate assumes that 18 days of shakedown
and testing will be required after assembly and prior to
the commencement of treatment. During this time, the
system  components  are  tested  individually.   It  is
estimated that eight workers will be required  for 10
hours per day, 7 days per week during shakedown and
testing.  Labor costs consist of wages ($40 per hour for
the supervisor and $30 per hour for the other seven
operating personnel) and living expenses  (refer to
subsection 4.4.5).  Labor costs  during shakedown and
testing are estimated to be $55,980 and are not included
hi the per ton treatment costs.

Equipment costs, insurance costs,  and property taxes
accrued during assembly,  shakedown, and testing  are
estimated to be approximately $91,500. Because these
costs are incurred during mobilization and startup, they
are not included hi the per ton treatment cost.

Working capital is the money required for the operation
of the system [1]. For remediation projects, the working
capital is the money that  the vendor has spent in the
operation of the  system but has  not yet recovered from
the site  owner or responsible party.   For  this estimate,
working  capital  consists  of the money invested  in
supplies, energy, spare parts,  and  labor costs for  1
month.  For the calculation of working capital, 1 month
is defined as one-twelfth of a year, or approximately 30.4
working  days.  At the  end of a project, all working
capital should be recovered. As a result, the only charge
to the project is  the "time-value" of the working capital
over the period  of the project.  This cost is estimated
based on the current prune lending rate of 6 percent.

The annual cost  for insurance is estimated as 6 percent
of the purchased equipment cost, and the annual cost
for property tax is estimated as 3 percent of the total
equipment cost  [1].   Costs  for insurance  and taxes
accrue  during  assembly,  shakedown  and  testing,
treatment, and disassembly. The per ton treatment cost,
however, includes only the portions of these costs which
accrue during treatment.

The cost for the initiation of monitoring  programs has
not been included hi this estimate.  Depending on the
site, local authorities may impose specific guidelines for
monitoring programs. The stringency and frequency of
monitoring required may  have  a significant  impact on
the project costs.

An annual contingency cost  of  10 percent  of  the
annualized equipment capital costs is allowed to cover
additional costs caused by unforeseen or  unpredictable
events,  such  as  strikes,  storms,  floods, and price
variations [1]. The  annual contingency cost has been
prorated to the  treatment tune and is included in the
per ton treatment cost.
                                                      18

-------
4.4.5    Labor Costs

Labor costs consist of wages and living expenses. Onsite
personnel requirements per shift during treatment are
estimated at:   four operators at $30  per  hour,  one
operations supervisor at $40 per hour,  and  one safety
officer at $40 per hour. Labor costs also include three
administrative and clerical employees, each working 40
hours per week at $20 per hour.  Labor rates include
benefits and overhead costs. It  is assumed  that onsite
personnel will work in three shifts for 24-hour-per-day,
7-day-per-week operation.

Living expenses depend on several factors: the duration
of the project, the number of local workers hired, and
the geographical location of the project.  RCC projects
that they will send 6 people from then: main office and
the other 12 onsite personnel will be local hires.  Living
expenses for all onsite personnel who are not local hires
consist of per diem and rental cars, both charged at 7
days per week for the duration  of the treatment.  Per
diem  covers hotel, food, and incidental expenses.  For
this analysis, per diem is assumed to be $70  per person
per day. This value is based on  a rough average of the
government per diem rates [3], which vary by location.
Two  rental  cars  are  required for  24-hour-per-day
operation and are available for an estimated $25 per day
per car.  Depending on  the location and length of the
project, RCC may elect to hire and train more or fewer
local  personnel.   Labor  costs must  be  adjusted
accordingly.
4.4.6   Supplies Costs

For this estimate,  supplies  consist of chemicals and
spare  parts.  RCC estimates  that  1  to  2 pounds  of
triethylamine  will  be required  per  ton  of waste
processed. The more conservative estimate of 2 pounds
of triethylamine is used for this analysis. Triethylamine
can be purchased in 330-pound drums for approximately
$1.40 per pound.

During the SITE demonstration, approximately 3 gallons
of 50 percent sodium hydroxide were consumed per ton
of   waste   treated.    Although   sodium   hydroxide
requirements will be site-specific, the economic analysis
is based on the level of consumption measured during
the demonstration.  A sodium hydroxide  cost of $2.33
per gallon is used for the economic analysis [4].

Nitrogen gas is also used in the B.E.S.T.® system. RCC
states that nitrogen costs typically range from $1.00 to
$1.50 per ton of waste treated. For the purpose of this
cost estimate, the assumed nitrogen cost is $1.50 per ton
of  feed processed.
The annual cost for spare parts is estimated at 5 percent
of the total purchased equipment cost [1].
4.4.7    Consumables Costs

Compressed instrument air will be produced by an air
compressor/dryer system that will be transported to the
site with the B.E.S.T.® system. As a result, compressed
air costs  are indirectly included elsewhere (in the
electricity and equipment costs).

RCC estimates that the process  will  consume 40 to 70
kilowatts of electricity per ton of feed. For the purposes
of  this  economic  analysis,  an  average   electricity
consumption rate of 55 kilowatts per ton  of feed is
assumed.   The average price of electricity  sold to all
ultimate consumers in the United States in  April 1992
was $0.066 per kilowatt-hour [5].  This average price was
used in this economic analysis.

It is  estimated  that the  operation  of the  B.E.S.T.®
system will consume approximately 1,020  gpd of water
during treatment.  A water cost of $0.0011 per gallon is
used in this economic analysis.
4.4.8    Effluent Treatment and Disposal Costs

Effluent treatment and disposal costs vary depending
upon the  contaminants initially present in the  soil,
sediment, or sludge. As a result, effluent treatment and
disposal costs are site-specific and are assumed to be the
responsibility of the  responsible party or site owner.
The effluent streams from the B.E.S.T.® process include
the  treated solids, oversized feed  material,  an  oil
product, and an aqueous product. If the untreated soil,
sediment, or sludge contains only organic contaminants
that can be removed effectively, the treated material
should  be suitable for return to the  site or use as
backfill.  If, however, there  are  leachable inorganic
contaminants present or there are excessive quantities of
organics remaining in the solids, the treated solids may
require further treatment or  disposal as a hazardous
waste. The quantity and characteristics of the oversized
materials will vary from site to site.  At some sites, they
may require treatment or disposal as a hazardous waste.
The organic contaminants from the soil, sediment, or
sludge   are  concentrated  into   the  oil product.
Incineration is the most likely disposal option for the oil.
The cost of incineration varies depending on the specific
organic contaminants present and the heating value of
the  oil  product.    The  aqueous  effluent  from the
B.E.S.T.® system should be suitable for discharge to a
sanitary or industrial wastewater treatment facility.
                                                       19

-------
4.4.9    Residuals and Waste Shipping, Handling, and
        Transport Costs

The residuals from the B.E.S.T.® process are the treated
soil, sediment, or sludge; oversized feed materials; an oil
product; and an aqueous product. Potential treatment
and disposal options for these residuals are described in
subsection 4.4.8. Other potential costs for each of these
residuals  include  the costs associated  with  storage,
handling, and transportation. These costs are assumed
to be the obligation  of the responsible  party (or site
owner)  and could significantly add to the total cleanup
cost, especially for TSCA or RCRA regulated residuals.
Equipment costs, insurance costs, and property taxes
accrued  during  demobilization  are estimated to be
approximately $61,000.  Total demobilization costs are
estimated to be approximately $180,000 and are not
included in the per ton treatment cost.

Site cleanup and restoration are limited to the removal
of all equipment from the site; this is included in the
cost of disassembly and decontamination. Requirements
regarding the filling, grading, or recompaction of the soil
will vary depending on the future use of the site and are
assumed to be the obligation of the responsible party (or
site owner).
4.4.10   Analytical Costs

No analytical costs are included in this cost estimate.
Much  of  the  monitoring,  sampling, and  analyses
required for full-scale treatment will be site-specific and
will  depend on the  contaminants present  and the
cleanup standards.   The  client may  elect or may be
required by local  authorities to  conduct additional
sampling  and  analysis.   Analytical costs  typically
contribute   significantly  to  the  overall  cost  of  a
remediation project.
4.4.11   Facility Modification, Repair, and Replacement
        Costs

For estimating purposes, total annual maintenance costs
(labor and materials) are assumed to be 10 percent of
annualizcd equipment costs. Maintenance labor typically
accounts for two-thirds of the total maintenance costs
and  has previously been accounted for in subsection
4.4.5. Maintenance material costs are estimated at one-
third of the total  maintenance cost and are prorated
over the entire period of treatment.  Costs for design
adjustments, facility  modifications,  and   equipment
replacements are included in the maintenance costs.
4.4.12   Site Demobilization Costs

Demobilization costs are limited to costs associated with
the disassembly and decontamination of the B.E.S.T.®
system and auxiliary equipment; transportation costs are
accounted for under mobilization activities. Disassembly
consists  of taking the B.E.S.T.®  system apart  and
loading it and all auxiliary equipment onto 11 trailers for
transportation. It requires the use of an operated 50-ton
crane,  available  at  $6,360 per  week,  for  4  weeks.
Additionally, disassembly requires an eight-person crew
working 10 hours per day, 7 days per week, for 30 days.
Labor  costs consist of wages  ($40 per hour for the
supervisor  and  $30  per hour  for  each of the other
workers) and living expenses (refer to subsection 4.4.5).
4.5    Results of Economic Analysis

The costs associated with the operation of the B.E.S.T.®
system, as presented in this economic analysis,  are
defined by 12 cost categories that reflect typical cleanup
activities encountered on Superfund sites. Each of these
cleanup activities is defined and discussed, forming the
basis for the cost analysis presented in Table 4. The
percentage of the total cost contributed by each of the
12 cost categories is shown hi Table 5.

Online factors of 60 percent, 70 percent, and 80 percent
are used to estimate the  cost of treatment using the
B.E.S.T.® system. The online factor is used to adjust
the unit treatment cost to compensate for the fact that
the system is not online constantly because of main-
tenance requirements, breakdowns, and unforeseeable
delays.   Through the use of the  online  factor, costs
incurred while the system is not operating are incorpo-
rated into the unit cost.

Manufacturers provided RCC with projected  preventive
maintenance and repair requirements for the centrifuge
and the extractor/dryers. Downtime due to repairs and
preventive  maintenance  for other  equipment was
estimated by RCC  based on pilot-plant experience.
Projected maintenance  and  repair requirements  are
summarized  in  Table  6.    These requirements  are
expected to represent a significant portion of the total
system downtime. The totals shown in Table 6 assume
that preventive maintenance tasks for the various pieces
of  equipment  are  planned  and can therefore be
conducted concurrently.  Repairs, on the other hand, are
often  unplanned  and  therefore   not   conducted
concurrently.

On an annual basis, RCC projects a total of 1,108 hours
of downtime due to preventive maintenance and repairs.
This represents  approximately 13 percent of the total
operating time available in 1 year.  The system is likely
to experience additional downtime due to other unfore-
                                                      20

-------
Table 4.  Treatment Costs for 186-tpd B.E.S.T.® System Treating Contaminated Soil, Sediment, or Sludge
                                                                                          Cost fa/ton)
Item
Site Preparation
Permitting and Regulatory Costs
Equipment Cost Incurred During Treatment
Startup and Fixed Costs0
Labor-
Supplies
Consumables
Effluent Treatment and Disposal
Residuals Shipping, Handling, and Transport
Analytical Costs
Facility Modification, Repair, and Replacement
Site Demobilization
Total Treatment Costs
60% online
a
b
10.62
9.13
48.14
15.40
28.48
b
b
b
0.35
d
112.12
70% online
a
b
9.11
7.85
41.27
14.84
28.48
b
b
b
0.30
d
101.85
80% online
a
b
7.97
6.90
36.11
14.46
28.48
b
b
b
0.27
d
94.19
     Site preparation costs are not included in these per ton treatment costs.  Preliminary site preparation costs are considered site-specific costs
     which are the responsibility of the site owner or responsible party.  Other site preparation costs (excavation or dredging of contaminated
     materials, construction of a foundation for the B.E.S.T.* system, and electrical and water lines and connections within the treatment area) are
     considered RCC's responsibility and are presented individually.  The costs for the foundation and  for the electrical and water lines and
     connections are estimated to total approximately $100,000.  Excavation costs are estimated to be approximately $36 per ton of soil excavated
     and dredging costs are estimated to be approximately $7 to $10 per cubic yard of sediment collected.
     Considered a site-specific cost which is the responsibility of the site owner or responsible party and therefore not included in these per ton
     treatment costs.
     Startup costs are presented individually and therefore not included in these per ton treatment costs.
     Considered a fixed cost which is presented  individually and therefore not included in these  per ton treatment costs.   The cost for site
     demobilization is estimated to be approximately $180,000.
 Table 5.   Treatment Costs as Percentages of Total Costs for 186-tpd B.E.S.T.® System Treating Contaminated Soil, Sediment, or Sludge
                                                                                       Cost fas % of total cost)
 Item                                                                 60% online                70% online             80% online
Site Preparation
Permitting and Regulatory Costs
Equipment Cost Incurred During Treatment
Startup and Fixed Costsc
Labor
Supplies
Consumables
Effluent Treatment and Disposal
Residuals Shipping, Handling, and Transport
Analytical Costs
Facility Modification, Repair, and Replacement
Site Demobilization
a
b
9.5
8.1
42.9
13.7
25.4
b
b
•b
0.3
d
a
b
8.9
7.7
405
14.6
28.0
b
b
b
0.3
d
a
b
85
7.3
38.3
15.4
30.2
b
b
b
0.3
d
     Site preparation costs are not included in these per ton treatment costs.  Preliminary site preparation costs are considered site-specific costs
     which are the responsibility of the site owner or responsible party.  Other site preparation costs (excavation or dredging of contaminated
     materials, construction of a foundation for the B.E.S.T.* system, and electrical and water lines and connections within the treatment area) are
     considered RCCs responsibility and  are presented individually.  The costs for the foundation and for the electrical and water lines and
     connections are estimated to total approximately $100,000.  Excavation costs are estimated to be approximately $36 per ton of soil excavated
     and dredging costs are estimated to be approximately $7 to $10 per cubic yard of sediment collected.
     Considered a site-specific cost which is the responsibility of the site owner or responsible party and therefore not included in these per ton
     treatment costs.
     Startup costs are presented individually and therefore not included in these per  ton treatment costs.
     Considered a fixed cost which is presented individually  and therefore not included in these per ton treatment costs.
                                                                   21

-------
Table 6,  Projected Annual Downtime
Major Equipment
Item
Extractor/diycr
Centrifuge
Other Major
Preventative
Maintenance,
hours per year
24
30
200
Repairs,
hours per year
300
408
200
  Equipment

 All Equipment
  Combined
200
                 908
seeable delays.  As a result, online factors of less than
87 percent appear to be appropriate.

The projected results of commercial-scale operation are
based on the results of the pilot-scale demonstration.
Cost estimates for several pieces of equipment are based
on quotes  obtained  from  vendors  by RCC  or on
independently  obtained  vendor  quotes.   Other cost
estimates are based  on information provided in Plant
Design and Economics for Chemical Engineers [1][2].
When necessary, the "six-tenths" rule is used to estimate
equipment costs from available cost data for equipment
of a different capacity [1]. In other cases, the Chemical
Engineering Cost Index is used to estimate current costs
(August 1992) from earlier cost data [1].

It is assumed the commercial-scale unit will have a feed
rate of 186 tpd. For the remediation of contaminated
soil, sediment,  or sludge, the results of the economic
analysis show a unit cost ranging from $94 per ton to
$112 per ton for 80  and 60 percent online conditions,
respectively.  These costs  are  considered  "order-of-
magnkude"  estimates as  defined by the  American
Association  of Cost Engineers.  The actual  cost  is
expected to fall between 70 percent and 150  percent of
these estimates. Since these cost estimates are based on
a preliminary design, the range may actually be wider.

The cost estimates presented in Table 4 do not include
costs   associated   with   site   preparation,   system
mobilization, startup, or demobilization.   These costs
will impact the  total  remediation cost. This impact will
be more noticeable  for small  sites,  where the total
treatment costs will be low  and the other costs will
therefore represent a larger fraction of the total cost.
The impact of these  costs on the total remediation cost
is less significant for large sites.

The cost estimates presented in Table 4 also  exclude
 certain   site-specific  costs  assumed  to   be  the
responsibility of the site owner or responsible party.
These costs are described in subsections 4.3 and 4.4.
This analysis does not include values for 6 of the 12 cost
 categories, so the actual cleanup costs incurred by the
                                   site  owner  or responsible party may be significantly
                                   higher than the costs shown in this analysis. A summary
                                   of the items  which are and are not  included in the
                                   treatment cost is presented in Table 7.
                                                            Table 7. Costs Included in Treatment Cost

                                                              Item
                                                                            Included in
                                                                          Treatment Cost?
                                                                               no
                                                                               no
                                                                               yes
                                                                               no
Costs for Collection of Contaminated Material
(by Excavation or Dredging)

Site Preparation Costs
Permitting and Regulatory Costs
Equipment Costs Incurred During Treatment
Equipment Costs Incurred During Startup and
Demobilization
Startup Costs (Costs Associated with
Transportation, Assembly, Shakedown, and
Testing)
Fixed Costs Incurred During Treatment
Fixed Costs Incurred During Startup and
Demobilization
Labor Costs Incurred During Treatment

Labor Costs Incurred During Startup and
Demobilization
Cost for Supplies
Cost for Consumables
Effluent Treatment and Disposal Costs
Residuals Shipping, Handling, and Transport
Costs
Analytical Costs
Facility Modification, Repair, and
Replacement Costs
Site Demobilization Costs
                                                                               yes
                                                                               no


                                                                               yes

                                                                               no


                                                                               yes
                                                                               yes
                                                                               no
                                                                               no

                                                                               no
                                                                               yes


                                                                               no
                                    4.6    References

                                    1.  Peters, M.S. and Timmerhaus, K.D.  Plant Design
                                        and Economics  for Chemical Engineers;  Third
                                        Edition; McGraw-Hill, Inc: New York, 1980.

                                    2.  Peters, M.S. and Timmerhaus, K.D.  Plant Design
                                        and Economics for  Chemical  Engineers; Fourth
                                        Edition; McGraw-Hill, Inc: New York, 1991.

                                    3.  Federal Register, Rules and Regulations.  Volume
                                        57 Number 39.  February 27, 1992.

                                    4.  Chemical Marketing Reporter.  Schnell Publishing
                                        Company, New York. October 12, 1992.

                                    5.  Energy  Information Administration.    Monthly
                                        Energy Review.   DOE/EIA-0035  (92/07).   July
                                        1992.
                                                        22

-------
                                               Appendix A
                                          Process  Description
A.I    Introduction

Resources  Conservation  Company's  (RCC's)  Basic
Extractive  Sludge  Treatment   (B.E.S.T.®)  solvent
extraction system  uses  a unique  property  of certain
amine solvents such as triethylamine to separate oil-
contaminated sludges or soils into their oil, water, and
solids fractions.  Organic contaminants in the sludge or
soil concentrate in the oil fraction after separation. The
physical property of inverse miscibility of triethylamine
in water can be used to  overcome solvent extraction
difficulties typically encountered when handling samples
with high water content. At temperatures below 60°F,
triethylamine is miscible with water (triethylamine and
water  are  each soluble in the  other).  Above  this
temperature, triethylamine and water are only partially
miscible.  This physical property can be exploited by
using triethylamine chilled below 60°F to solvate oil and
water simultaneously [1].

During this Superfund Innovative Technology Evaluation
(SITE) demonstration,  the feedstock was mixed with
triethylamine solvent to  create a single phase extraction
fluid.   The  liquid  is  a  homogeneous  solution  of
triethylamine and water present in the feedstock.  This
solution  solvates  the oils that  were  present  in the
feedstock, because the amine  solvents can  achieve
intimate contact  with  solutes  at  nearly ambient
temperatures and pressures. This is the reason that the
B.E.S.T.® process  is  able to handle feed mixtures with
high water content with a high extraction efficiency [1].
A.2    B.E.S.T.® Pilot Unit

The B.E.S.T.® pilot plant is a solvent extraction system
designed for batch operation.  A process flow diagram
for the B.E.S.T.® system is shown in Figure A-l.  Some
of the unit process operations, such as water stripping
and centrifugation, are normally operated continuously.
The pilot plant has a nominal feed volume  of 1 cubic
foot (8 gallons)  of dry solids per batch run [1]. Four
operators per shift were employed for system operation,
process  control,  sample  coordination,  and  safety
considerations.
A. 3    Unit Operations

The pilot plant operations, which will be described in
this section, consist of the following [1]:
    Feed Preparation
    Extraction
    Decantation, Solvent Recovery, and Oil Processing
    Solids Drying
    Water Stripping
    Product Water Treatment
A3.1   Feed Preparation

Feed preparation consists of sample collection, transport
to the pretreatment area, and screening out of oversize
material. The developer projects that screening to 
-------
                                                            Solvent Separation I Solvent Recovery
                                                                                     Solvent
                                                                                     Evaporator
                                                                                     Water Product
Figure A-1.  Generalized  Diagram of the B.E.S.T.® Solvent Extraction Process.

-------
The sediments treated during this demonstration were
first processed  in  the premix tank  [1].   The  first
sediment extraction phase (a cold extraction) consisted
of adding feedstock and a predetermined quantity of
caustic to the premix tank, which was then filled with
chilled solvent.  The mixture was agitated for 5  to 30
minutes and allowed to settle. The minimum settling
tune was determined in the RCC laboratory prior to the
demonstration [2]. The triethylamine/water/oil mixture
was decanted through decant ports, located on one side
of the premix tank, and drained to the decant pump
which transported the mixture to the centrifuge.  The
fine solids were separated by centrifugation and directed
to the extractor/dryer. The centrate was routed to the
centrate tank and  immediately pumped through the
centrate filter   into  the solvent  evaporator.    Cold
extractions were repeated and solids were accumulated
as feed was added to the premix tank. Because the feed
used in the SITE demonstration had  a high moisture
content (more than 40 percent), it required more than
one cold extraction.

Once a sufficient  volume  of moisture-free solids  is
accumulated, the solids are transferred to a steam-
jacketed extractor/dryer.  Warm triethylamine is added
to the solids. The mixture  is heated,  agitated, settled,
and decanted.    This  process can  also be repeated.
These warm and hot extractions result in separation of
the  organics not  removed  during  the  initial  cold
extraction.   The number of hot and  cold extraction
cycles required  depends on feedstock  composition and
settling  characteristics  [1].    Feedstock  processing
requirements during  the  SITE  demonstration were
predetermined  on  a  preliminary basis by bench-scale
testing prior to  the demonstration.
 A33    Decahtation,   Solvent  Recovery,  and   Oil
         Processing

 According to Figure A-l, the centrate recovered from
 the first extraction stage flows to the oil decanter, where
 it is separated into its aqueous and organic components.
 The aqueous phase is transferred to the water receiver
 tank.  The organic phase, which contains a mixture of
 triethylamine, oil, and water, is  pumped from the oil
 decanter to the solvent evaporator and heated.  During
 the SITE demonstration, the oil decanter was not used
 because it was not functioning properly.  The centrate
 was therefore pumped directly to the solvent evaporator.
 In either case, further heating in the solvent evaporator
 evaporates the low-boiling azeotrope of solvent  and
 water (boiling point of approximately 170°F), leaving the
 oil behind. The evaporation process is continued until
 the water is depleted.  At that point, the temperature of
 the boiling liquid rises until it reaches the boiling point
 of pure triethylamine (193°F) and evaporation continues
 until nearly all the triethylamine  is removed [1].
The  triethylamine/water  vapor   from  the  solvent
evaporator is condensed in heat exchangers  that use
cooling water  with a  temperature of approximately
100°F.  This produces  condensed triethylamine/water
with a  temperature of approximately 110°F.   At this
temperature,  the triethylamine  and  water are  only
partially miscible and separation is accomplished in a
continuous flow solvent decanter. The recovered solvent
is recycled back to the solvent storage tank and the
water is drained by gravity to a water storage tank for
storage  until  stripping  operations   are  performed.
Ultimately,  the water is steam stripped in the water
stripper column to  remove residual triethylamine [1].

Oil  processing  is  also performed  in  the  solvent
evaporator. The contents of the solvent evaporator are
heated  at approximately 193°F until  virtually all the
triethylamine is removed.    The  remaining residual
solvent is released by the injection of a small amount of
water into the oil.  The water forms an azeotrope with
the residual solvent, thereby dislodging it from the oil.
The recovered oil fraction  can be  dechlorinated or
incinerated to destroy the organics  [1].

When the samples  from Transect 28 were treated, the
amount of oil produced was too small for oil processing,
so the oil was left in solution with a Umited amount of
solvent. This oil/solvent mixture was stored in a drum
, for disposal.  Oil processing was conducted on the oil
product from the treatment of the Transect 6 sediments.
 A.3.4    Solids Drying

 Solids drying is performed on the solids remaining in the
 extractor/dryer after the last extraction stage.  Before
 drying, a small amount of caustic is added to the solids
 for pH control. The extractor/dryer is equipped with a
 steam jacket and direct steam injection ports.  To dry
 the washed solids, steam is first  supplied only to the
 steam jacket to indirectly heat the extractor/dryer and
 its contents to about 170°F.   After the bulk of the
 solvent  is removed, direct steam  is injected into the
 extractor/dryer vessel.   The entire drying process is
 performed with  the  extractor/dryer mixing paddles
 rotating.  This mixing increases the heat transfer, thus
 reducing the drying tune. The  solvent and steam form
 an  azeotrope which  is then  directed  to  the dryer
 condenser. After all the triethylamine is removed, the
 temperature of the vapor rises to the boiling point of
 water. After the drying process is complete, the solids
 are removed through  the discharge port on the bottom
 of  the  extractor/dryer  [1].     During  the  SITE
 demonstration, a portion of the solids were retained for
 laboratory analysis and the remainder was collected for
 transfer to a polychlorinated biphenyl (PCB) disposal
 facility.
                                                       25

-------
Liquid from the condenser drains into the mixing tank.
The triethylamine/water mixture and any carryover dust
are directed to the centrifuge to remove solids. The
ccntrate is then pumped through the centrate filter and
into the solvent evaporator, where it is combined with
the triethylamine/oil/water already present [1].
A3.5 '  Water Stripping

Water stripping is accomplished by direct contact steam
stripping.  Before the triethylamine is stripped from the
decant water, a predetermined amount of caustic soda
is added to the water to raise the pH. Steam is injected
directly into the bottom of the stripping column to heat
the column to the desired temperature.  Preheated feed
water is introduced into the top of the column.  The
non-vaporized feedwater flows through the column and
is stripped of residual solvent by upflowing steam. The
bottoms are returned to the water receiver tank until a
steady state is obtained. The bottoms are then rerouted
to  be discharged as product  water.   The  solvent
azcotrope vapors generated are routed to  the water
stripper condenser and the recovered solvent is recycled
[1].
AJ.6   Product Water Treatment

The final process involves the discharged stripped water,
termed product water. During the SITE demonstration,
this water was collected separately  for  each batch
processed. These samples were analyzed for pH, Total
Suspended Solids (TSS), Total Dissolved Solids (TDS),
oil and grease (O&G), residual solvent (triethylamine),
conductivity, PCBs, polynuclear  aromatic hydrocarbons
(PAHs), and metals.  Analytical results indicated that
the product water was a RCRA waste because of its
high pH.   RCC claims that the high pH  was due to
operator error (addition of excessive caustic) and should
not typically be an issue.
A.4    References

1.  Resources Conservation Company. Draft B.E.S.T.®
    Pilot Unit Test Report, Grand  Calumet River,
    Gary, Indiana, October 1992.

2.  Science Applications  International Corporation.
    Superfund Innovative Technology Evaluation - Draft
    Demonstration Plan, June 1992.
                                                    26

-------
                                              Appendix B
                                            Vendor Claims
NOTE: This appendix to the Environmental Protection
Agency's (EPA's)  Applications Analysis Report  was
prepared by Resources Conservation Company (RCC).
Claims and interpretations of results in this Appendix
are those made by the vendor and are not  necessarily
substantiated by test or cost data.  Many of RCC's
claims regarding cost and performance can be compared
to the available data  in  Section  4,  Section 3,  and
Appendix C of this Applications Analysis Report.

RCC, the developer of the  Basic Extractive Sludge
Treatment (B.E.S.T.®) solvent extraction process, states
that the B.E.S.T.® process offers several advantages over
other  treatment  technology  alternatives.    These
advantages include:

•   The  B.E.S.T.® process  can  effectively  remove
    polychlorinated biphenyls  (PCBs),  polynuclear
    aromatic hydrocarbons (PAHs) and other hazardous
    organic  compounds  from  soils,  sludges   and
    sediments.

•   Triethylamine,  the solvent used  in the B.E.S.T.®
    process, is environmentally friendly. Triethylamine
    is  biodegradable,  does  not  accumulate  in  the
    environment, and occurs naturally in the food chain.

•   There are  no  air  emissions from the B.E.S.T.®
    process.    Therefore,  permitting  and  siting  a
    B.E.S.T.®  process  unit is simpler than for other
    technologies,  such  as  incineration  or  thermal
    desorption.

Discussion of these claims is  presented in Subsections
B.I, B.2, and B.3.

RCC conducted a B.E.S.T.® pilot-scale demonstration
test  on  contaminated  sediments  from the Grand
Calumet River in Gary, Indiana.  Testing occurred in
Gary, Indiana between June 23, 1992 and July 28, 1992.
The test was performed to demonstrate the ability of the
B.E.S.T.® process  to remove PAHs and PCBs from
contaminated sediments.
Sediment from two locations was tested. The locations
were  Grand  Calumet River Transect 28 and Grand
Calumet River Transect  6.   Five batches  of each
sediment type were processed.  The less contaminated
sediment, Transect 28, was processed first.

During the demonstration program, RCC collected and
analyzed numerous samples from the  pilot  unit when
treating sediments from both Transect 6 and Transect
28. [RCC conducted these analyses in accordance with
published  EPA Quality Assurance/Quality  Control
(QA/QC)  guidelines.]    Subsection B.4 provides  a
comparison of  the Superfund  Innovative Technology
Evaluation (SITE) analytical data and RCC analytical
data.  The SITE and  RCC analytical results closely
correlate,  further  substantiating the success of this
demonstration program.

Subsection B.5 provides a comparison of the bench-scale
treatability test  data and the pilot-scale demonstration
test  data  generated  as part  of  this  project.   The
comparison   clearly   shows   that  the  bench-scale
treatability test protocol closely predicts pilot-scale test
results.  Subsection B.5 also provides a comparison of
bench-scale   treatability  test  data   to   full-scale
performance data from a previous project.

A summary of other pilot-scale  demonstration tests
conducted by RCC  is  provided  in Subsection  B.6.
Results from these pilot-scale test projects demonstrate
that  the  B.E.S.T.®  solvent extraction process can
effectively remove PCBs, PAHs and other  hazardous
organics from soils, sludges and sediments.
B. 1    B. E. S. T. ® Process Effectively Removes
        PCBs and PAHs from Sediment

This demonstration  of the B.E.S.T.® solvent extraction
process clearly shows that the technology can remove
PCBs and PAHs from  sediments with a  high  water
content. The following objectives of the demonstration
                                                     27

-------
program were successfully achieved:

•   Demonstrate the B.E.S.T.® process unit operations
    at pilot scale.   The  unit operation  components
    demonstrated included the following equipment:

    •   Extractor/dryer vessel
    •   Fines centrifuge
    •   Decanter vessel
    •   Solvent evaporator
    •   Water stripper

•   The pilot test will process  enough contaminated
    sediment  to  evaluate the  process sensitivity  to
    changes in the feed composition between the two
    locations tested; Transect 6 and Transect 28.

•   Demonstrate that the B.E.S.T.* process can achieve
    greater than 96 percent removal of total PAHs and
    total PCBs from the contaminated sediments.

•   Produce recovered water, solids and oil with solvent
    residual concentrations of less than 80 parts per
    million (ppm), 150 ppm, and  1000 ppm, respectively.

•   Calculate mass balance of feed material into the
    pilot unit versus total products out (solids,  water
    and oil) within the range of  100 ± 15 percent.

Overall success of the demonstration test was excellent.
RCC's analytical results for the sediments treated during
the demonstration test are summarized in Figures B-l,
B-2, B-3, and  B-4.
B.2    B.JB.S.r.®   Process    Solvent    Is
        Environmentally Friendly

Triethylamine, the solvent used for the B.E.S.T.® solvent
extraction process,  has  several characteristics that
enhance its use for removing hazardous organics from
the environment. These characteristics include:

    •   Triethylamine  is biodegraded  aerobically  by
        commonly occurring soil bacteria.[l]

    •   Triethylamine photochemically degrades in the
        atmosphere, will not adsorb to sediments, and
        does not bioconcentrate hi the environment.[2]

    •   Triethylamine  appears in the food chain in
        boiled beef, caviar, cheeses, wheat bread, and
        milk fermentation products.[3]

    •   Triethylamine   is  produced  from   natural
        ingredients; ethyl alcohol and ammonia.[4]
    •   Triethylamine is a commonly used industrial
        solvent.     Over  17   million  pounds  of
        triethylamine were produced in 1982.[5]
BJt.l    Triethylamine Is Biodegradable

As  discussed  in  Appendix  C,  part  C.8,  Science
Applications    International   Corporation   (SAIC)
conducted limited testing to assess the biodegradability
of triethylamine in one treated solids sample.  Samples
of a single batch of treated solids were mixed hi a 1 to 1
ratio with common potting soil.  No bacteria cultures
were taken to  quantitate the  bacterial activity in the
potting  soil.   No  attempt was  made  to  produce an
environment   suitable   for   bacterial   growth   or
biodegradation.  Specifically, the elevated pH of the
solid product was not neutralized, moisture content of
the solid product and potting soil was not measured or
adjusted,  and no  attempt was  made to aerate the
samples in this testing.

SAIC testing showed no observed difference between
the triethylamine biodegradability in the control samples
and the mixed soil samples.  These  results are too
limited to be of any use  in determining if triethylamine
can be  expected  to biodegrade.    The only  valid
conclusion that may be  reached as  a  result  of SAIC
biodegradation testing is that if the treated solids were
mixed  1 to  1  with  potting  soil,  with no  other
environment  adjustments and  no product aeration, no
significant biodegradation of  triethylamine would be
expected.

RCC studies have shown that neutralized samples with
a moderate  moisture content exhibit  the  ability  to
markedly  reduce   the   triethylamine  level   by
biodegradation  when  mixed with  soils containing
common  soil bacteria [6].  Triethylamine levels were
reduced by as much as 99 percent.  Independent studies
have  also been conducted on the biodegradability  of
triethylamine.    It   has also  been  reported  that
triethylamine is degraded in  an Aerobacter  bacterial
culture [1].  Aerobacter  is a common soil bacteria.  It
has also been reported  that  triethylamine readily
biodegrades  in a  brine  acclimated  waste  treatment
system [7].
 B.3    B.E.S.T.®   Process   Has   No   Air
        Emissions

 During the demonstration program SITE monitored the
 ambient ah- for organic vapors on a daily basis 5 meters
                                                      28

-------
                                 Batch
                                                                                          T-28 Untreated Sediment
                                                                                    T-28 Treated Solids
Figure B-l. Transect 28 PAH Summary.

-------

(0



1

(0
4-1
o
                                    Batch
                                                                                             T-6 Untreated Sediment
                                                                                       T-6 Treated Solids
    Figure B-2.  Transect 6 PAH Summary.

-------
                                                                                      T-28 Untreated Sediment
                            Batch
                                                                               T-28 Treated Solids
Figure B-3. Transect 28 PCB Summary.

-------
                              Batch
                                                                                         T-6 Untreated Sediment
                                                                                  T-6 Treated Solids
Figure B-4.  Transect 6 PCB Summary.

-------
upwind and  downwind  of the treatment  unit.   No
organic vapors were detected during the demonstration
program.  SITE also monitored the vent gases from the
treatment unit on a continuous basis.   No solvent was
detected in the vent gases released to the  environment.
Results of  SITE'S  air  monitoring   operations  are
provided in Subsection C.7.
B.4    SITE  and  RCC  Analytical  Results
        Closely Correlate

SITE analytical results were in agreement with RCC
analytical results.   A comparison  between SITE and
RCC PAH  and  PCB  analytical  results  follows  in
Tables B-l and B-2:

Table B-l.    SITE vs. RCC Analytical Results
            (PAH Results, mg/kg dry basis)
                                SITE        RCC
 Sample                         Results      Results
 Transect 28

  Untreated Sediment
  Treated Sediment

  Removal Efficiency, percent


 Transect 6
  Untreated Sediment

  Treated Sediment

  Removal Efficiency, percent
 550
 22

 96.0
70,900

 510
 99.3
 783
 34

 95.6
87,500

 716
 99.2
Table B-2.    SITE vs. RCC Analytical Results
            (PCB Results, mg/kg dry basis)

                                SITE        RCC
 Sample                         Results      Results

 Transect 28

  Untreated Sediment
  Treated Sediment

  Removal Efficiency, percent


 Transect 6
  Untreated Sediment

  Treated Sediment,

  Removal Efficiency, percent
 12.1

 0.04

 99.7
 425

 1.8
 99.6
 5.5
 0.07

 98.7
 580

 1.1

 99.8
 B.4.1    Overall Mass Balance Results

 The  overall mass  balances calculated by  RCC  were
 based on RCC's analytical results.   The overall  mass
                           balances  calculated  by  SITE  and  RCC  represent
                           excellent  mass balance  closure.   Both total mass
                           balances indicate that even though individual balances
                           may  vary because  of the  considerable number  of
                           analyses involved, no significant amount of material is
                           lost for either Transect 28 or  Transect 6.  The total
                           mass balances for RCC and SITE are compared here in
                           Table B-3:

                           Table B-3.     Total Mass Balance Comparison
                                                  RCC Total        SITE Total
                            Sample               Mass Balance      Mass Balance
                            Transect 28, percent        103.5
                            Transect 6, percent         106.2
                                                         99.3
                                                         99.6
                            B.4.2    RCC QA/QC Requirements

                            RCC prepared a detailed Sampling Analysis Plan and
                            Quality Assurance Project Plan in strict compliance with
                            published  EPA  QA/QC guidelines.   The QA/QC
                            requirements for this demonstration project included:
    Data quality objectives
    Field sampling and measurement procedures
    Sample custody and transport
    Calibration procedures and frequency
    Sampling, analysis and monitoring
    Data validation
    Performance audits and system audits
3.5    B.E.S.T.®    Process   Performance
        Accurately Predicted  by  Bench-Scale
        Treatability Test Protocol

In order to evaluate each potential application for the
B.E.S.T.®  process, RCC has  developed  a low  cost
bench-scale treatability test protocol.  This bench-scale
test provides data that closely simulate both pilot-scale
and  full-scale system performance.  The  bench-scale
treatability  test  data   allow RCC  to evaluate the
feasibility of the process and to estimate treatment costs.
When a pilot-scale test is performed, the bench-scale
test  is  used  to  obtain  information  which  provides
operational guidelines.
                            B.5.1    Bench-Scale Test vs. Pilot-Scale Test Data for
                                    Grand Calumet River Testing

                            RCC  performed bench-scale treatability testing with
                            Grand  Calumet River  sediment, before  pilot-scale
                            testing began. Split samples of the exact material to be
                            tested at the pilot scale were tested at the bench scale in
                            June 1992. A summary of results from all testing shows
                                                       33

-------
the ability of bench-scale testing to predict pilot-scale
test results:
Table B-4. Transect 6 Testing Comparison
(PAH and PCB Concentrations, mg/kg, dry basis)
Sample PCBs Total PAHs
Bench-Scale Test
Untreated Sediment
Treated Solids
Removal Efficiency, percent
Pilot-Scale Test
Untreated Sediment
Treated Solids
Removal Efficiency, percent

700
< 1
> 99.8

580
1.1
99.8

76,900
346
99.6

87,500
716
99.2
                                               General Refining, Inc., Superfund site.  All data were
                                               collected  by  an  EPA  contractor.    These  data
                                               demonstrate a close correlation  between bench-scale
                                               treatability test data and full-scale operating data.

                                               Table B-6.    General Refining Site PCB Concentrations in Raw
                                                            Sludge and Product Fractions (ppm)

Raw Sludge,
mg/kg, dry basis
Product Solids,
mg/kg, dry basis
Product Water,
mg/L
Extraction Efficiency,
percent
Test A
14
0.02
<0.01
99.9
TestB
12
0.14
<0.01
98.8
Processing (1987)
13.5
<0.13
<0.005
>99
Table B-5.
 Sample
Transect 28 Testing Comparison
(PAH and PCB Concentrations, mg/kg, dry basis)
                  PCBs
Total PAHs
 Bench-Scale Test

   Untreated Sediment              6           890

   Treated Solids                  <1          28

   Removal Efficiency, percent        >83          97


 Pilot-Scale Test

   Untreated Sediment              5.5          783

   Treated Solids                  0.07          34

   Removal Efficiency, percent        98.7          95.6
E.S2   Bench-Scale Test vs. Full-Scale Remediation

The reliability of the bench-scale treatability tests to
predict full-scale performance has been verified by the
US EPA report Evaluation of the B.E.S.T.® Solvent
Extraction  Sludge Treatment  Technology-  Twenty-Four
Hour Test, by Enviresponse, Inc.,  under EPA Contract
68-03-3255.   Evaluating the B.E.S.T.® process,  this
report states:

    Resources Conservation  Company has  conducted
    many laboratory tests and developed correlations to
    which data from full-scale operations, such as the
    General Refining site, can be compared.

Table B-6 presents data from two separate bench-scale
treatability tests and from  full-scale operations at the
B.6    Other Pilot-Scale  Test Project  Results
        Substantiate   SITE    Demonstration
        Project Results

The Pilot Unit has been tested at four facilities prior to
the SITE demonstration test.  A brief summary of the
results of those tests follows.
                                                B.6.1    PCBs in Soils and Sediments at an Aluminum
                                                        Manufacturing Site

                                                PCBs were removed from soils and sediments at an
                                                aluminum manufacturing site.  The treatment objective
                                                of 2 mg/kg  was  easily  met.  The .following table
                                                summarizes the results:

                                                Table B-7.   Aluminum Manufacturing Facility PCB  Removal
                                                           From Soils and Sediments
PCB Concentration
(mg/kg. dry basis')
Sample Untreated Sample . Treated Solids
Lagoon #1 (sediment)
Lagoon #2 (soil)
Lagoon #3 (sediment)
Lagoon #4 (sediment)
Landfill #1 (soil)
Landfill #2 (soil)
530
800
480
137
13
5
0.7
1
1
0.6
0.3
0.2
                                                B.6.2    PAHs  in  Sludge  from  Wood  Treatment
                                                        Facilities

                                                PAHs were removed from two contaminated sediments
                                                taken from  different wood treatment faculties.  The
                                                       34

-------
treatment goal of removal of greater than 90 percent of
PAHs was easily met.  The following table summarizes
the results:

Table B-8.    Wood Treatment Facilities PAH Removal From
            Sediments

                          Total PAH Concentration
                            (me/kg, dry basis)

 Sample               Untreated Sample  Treated Solids
Bayou Bonfpuca Site, 9700
Slidell,
Jennison
Louisiana
i-Wright Site, 8800
23

79
   Granite City, Illinois
B.63   PCBs in Soil at a Manufacturing Site

PCBs  were  removed  from  a  soil  sample  at  a
manufacturing site in Greenville, Ohio. Approximately
1000 pounds  of soil sample was treated in 18 distinct
batches;  The PCB  contamination level in the sample
was reduced  from 130 mg/kg  (dry basis) to 2 mg/kg
(dry basis).  The treatment objective of 10 mg/kg was
easily met.
B.6.4   PAHs in Refinery Sludge

PAHs were removed from four contaminated sludges at
the  Exxon refinery, Baton  Rouge, Louisiana.   The
sludges were tested to help establish Best Demonstrated
Available Technology (BDAT) standards for removal of
PAHs from K048-K052 wastes  (refinery  sludges).
Current BDAT standards are partially based on results
from this pilot testing.

The oil and grease content of the refinery sludges was
reduced from 26 percent to 0.09 percent.  Total PAHs
were reduced to 11.6 mg/kg.
B.7    References

1.   EPA  Document  EPA  Data  ORD  USEPA
    Washington,  D.C.  20460,  Feb.  1983  Manual
    (reprint), Volume 1 600/2-82-OOla (1983)

2.   Howard, P.H. et al: Handbook of Environmental
    Fate and Exposure Data for Organic Chemicals pp
    493-498(1990)

3.   Golonmya, R.V. et al: Chem Senses Flavour  4:97-
    105 (1979)

4.   Kirk  & Othmer:  Encyclopedia  of  Chemical
    Technology (1980)

5.   USITC:  United  States   International   Trade
    Commission, USITC 1982 (1986)

6.   Erikson, T., Resources Conservation Company:
    Biodegradation  of Triethylamine, (September  9,
    1992)

7.   Portier, RJ., Hoover, D., Fugisaki, K.: Evaluation
    of Biotreatment Approaches for Triethylamines and
    Methyl  Isobutyl  Ketones Waste  Waters, Hi-Tek
    Polymers, Inc.  Preliminary Study, Institute For
    Environmental Studies,  Louisiana State University,
    Baton Rouge, LA,  (July 1, 1991)
                                                     35

-------
                                             Appendix C

                                  SITE Demonstration Results
C.I    Introduction

This appendix summarizes the results of the Superfund
Innovative Technology Evaluation (SITE) demonstration
test of the Resources Conservation Company (RCC)
Basic Extractive Sludge Treatment (B.E.S.T.®) system.
These results are also discussed in Sections 1 and 3 of
this  report.    A  more  detailed  account  of the
demonstration may  be  found  in the  Technology
Evaluation Report (TER).

Test sediments were  collected  from  two locations
(Transect 28 and Transect 6)  in the Grand Calumet
River approximately  10 days before the start of the
demonstration. Sediments were collected using hollow
aluminum tubes that  were driven approximately 5 feet
into the soft river bottom. The sediment samples were
emptied into 5-gallon buckets  and  transported to the
demonstration site.   Sediment from Transect 28 was
screened and homogenized to form Sediment A,  while
sediment  from   Transect   6  was   screened  and
homogenized to form Sediment B.

For  the  SITE demonstration,  Sediment  A and
Sediment B were treated using the B.E.S.T.® pilot-scale
system.  Three runs (Runs 1, 2, and 3) were conducted
for each sediment to optimize operating parameters.
For each sediment, the operating parameters from one
of the first three runs were selected as "optimum" and
two more runs were conducted at optimum conditions.
Optimum conditions for each sediment were determined
by RCC based on observations, sampling, and analyses
(by RCC's laboratory) from the three initial runs. For
Sediment A, Runs  3, 4, and 5 were conducted at
optimum conditions.  For Sediment B, Runs 2,4, and 6
were  conducted  at  optimum   conditions.    The
summarized results presented in Sections 1 and  3 are
averages from the   runs   conducted at  optimum
conditions.  During all runs, sampling was performed in
accordance  with  the procedures outlined  in the
Demonstration Flan.
The primary objective of a SITE demonstration is to
assess the ability of the technology to meet applicable or
relevant and appropriate requirements (ARARs). The
ability  of the  B.E.S.T.® system to remove organic
contaminants from inorganic matrices such as soils and
sludges was evaluated. Results from this demonstration
include  polynuclear  aromatic  hydrocarbon  (PAH)
concentrations  in the treated and untreated sediment;
polychlorinated biphenyl (PCB)  concentrations in the
treated   and   untreated   sediment;   triethylamine
concentrations  in the treated sediment, product oil, and
product water; and metals teachability by the Toxicity
Characteristic  Leaching Procedure (TCLP)  for the
treated  and untreated  sediment.   PAH  and  PCB
concentrations  in the product oil and product water are
summarized in subsection C.6.  Air emissions results for
both the  vent emissions  and the ambient air are
presented in subsection C.7. Finally, the results of the
triethylamine biodegradability  testing are presented in
subsection C.8.
C.2    Contaminant Removal Efficiencies

During the demonstration, 96 percent of the PAHs and
greater than 99 percent of the PCBs initially present in
Sediments A and B were removed.  These results are
consistent with  demonstration  test  objectives and
support RCC's claims that average removal efficiencies
of 96 percent to greater  than  99  percent  could be
obtained for both PAHs and PCBs using the B.E.S.T.®
system.  Table C-l lists the specific concentrations and
removal efficiencies obtained during  runs performed
using optimum conditions.  These results were obtained
by comparing contaminant concentrations present in the
sediments before and after treatment.  Table C-l also
contains the  oil and grease  (O&G) removal efficiencies
obtained during the demonstration test. Average O&G
removal efficiencies of greater than 98 percent were
experienced  for both sediments.  The  measurement of
O&G is not required for the  evaluation of RCC's
claims. However, because PCBs and PAHs are among
the compounds detected by the analysis for  O&G, these
                                                    36

-------
Table C-l.    Total PAH, Total PCS, and O&G Removal Efficiencies
                              Total PCBs
                                                                 Total PAHs
                                                                                                     O&G
Raw Treated
Sediment Solids
mg/kg, mg/kg, Percent
Parameter dry dry Removal
Sediment A
Run3 8.01 0.05 99.4
Run 4 11.8 0.04 99.7
Run 5 16.4 0.04 99.8
Average 12.1 0.04 99.7
Sediment B
Run 2 316 2.1 99.3
Run 4 462 1.8 99.6
Run5 497 1.4 99.7
Average 425 1.8 99.6
O&G results support the removals experienced for both
PAHs and PCBs.
C.3 Residual Triethylamine
Treated solids produced during the optimum treatment
runs for Sediment B had an average triethylamine
concentration of 103 mg/kg. Water generated during
these runs had a triethylamine concentration of 2.2
mg/L or less, while the oil product collected at the end
of all Sediment B treatment runs had a triethylamine
concentration of 733 mg/kg. Because very little oil
product was generated during the treatment of Sediment
A, the Sediment A oil product was not processed to
reduce its triethylamine concentration. Solid product
generated from the optimum treatment runs for
Sediment A realized an average residual concentration
of 45.1 mg/kg, while water products from the optimum
treatment runs for Sediment A had triethylamine
concentrations of 1.0 mg/L or less. These results
comply with RCC's claims and the demonstration test
objectives regarding the system's ability to produce
residual triethylamine concentrations of less than 80,
150, and 1,000 parts per million (ppm) for water, solids,
and oil products, respectively. Table C-2 lists the
specific concentrations obtained for the three products
generated during those runs performed under optimum
conditions.
C.4 Mass Balances
Mass balances for Sediment A and Sediment B were
performed for water, oil, solids, PCBs, and PAHs
entering and exiting the system during system operation.
Raw Treated Raw Treated
Sediment Solids Sediment Solids
mg/kg, mg/kg, Percent mg/kg, mg/kg, Percent
dry dry Removal dry dry Removal
457 21 95 7,400 203 97.3
568 28 95 6,600 66 99.0
620 17 97 6,700 65 99.0
548 22 96 6,900 111 98.4
64,100 447 99.3 116,000 1,330 98.9
63,500 402 99.4 167,000 1,230 99.3
85,200 682 99.2 99,100 1,810 98.2
70,900 510 99.3 127,000 1,460 98.9
Table C-2. Residual Triethylamine Concentrations
Solids Water Oil
Parameter mg/kg mg/L mg/kg
Sediment A
Run 3 27.8 <1 a
Run 4 28.0 <1 a
RunS 79.6 2.2 a
Sediment B
Run 2 88.7 1.0 a
Run 4 130 <1 a
RunS 89.3 <1 733b
a Not analyzed
b This number is an average value for five aliquots collected
incrementally, following oil processing, at the end of the
treatment of Sediment B.
These balances were obtained by comparing the weights
and volumes of raw sediment and process additives (i.e.,
solvent, sodium hydroxide, etc.) entering the system with
the various product fractions and samples recovered
during testing. Analytical data regarding contaminant
concentrations within the various fractions, as well as
percent solids, O&G, water, etc., were used in
conjunction with measurements recorded during the
demonstration. Since material holdup within the system
could distort the individual material balances obtained
for each run (batch), the mass balances calculated within
this report evaluate overall performance during the five
runs cumulatively. Cumulative balances comparing total
materials (including and excluding triethylamine)
entering and exiting the B.E.S.T.® system were also
performed. Table C-3 summarizes all mass balance
results.
                                                          37

-------
Table C-3.    Mass Balance Summaries, Percent*
 Sample
                       Solids
                                 PCBs
                                           PAHs
                                                     O&G
                                                             Water
                               Triethylamine
                                         Feed and
                                          Product
                         Total Materials    Materials8
Sediment A
Sediment B
89
108
95
112
115
126
222
119
125
116
87
82
99.3
99.6
108
114
a   The project objectives for all mass balances were closures between 80 and 130 percent.
b   The vendor claim for this mass balance was closure between 85 percent and 115 percent for feed and product materials.
C.4.1   Solids Balance

Solids   balances   were   performed   during   the
demonstration by  comparing the  amount of  solids
entering the system as part of the feed sediment to the
process solids recovered.   Solids balance results are
consistent  with  demonstration  test objectives that
closures of between  80 and 130  percent could  be
obtained for solids treated within the B.E.S.T.® system.
The mass balances for solids are presented in Table C-4.
Table C-4.    Solids Mass Balances

                         Sediment A
 Sediment B
Solids Input, Ibs
Solids Output, Ibs
Solids Recovery, percent
474
420
89
285
306
108
                    C.43   PAH Balance

                    Like  PCBs,  all  of the  PAHs  entered in the  feed
                    sediment, while the majority exited in the product oil.
                    Closures  of  115 and  126 percent were obtained for
                    PAHs during the treatment  of  Sediments A and B,
                    respectively.  The PAH balance  results are consistent
                    with  the  demonstration test objectives  of closures
                    between 80 and 130 percent.  Mass balances for PAHs
                    are presented in Table C-6.
                    Table C-6.    PAH Mass Balances
                                             Sediment A
                                        Sediment B
                                                             PAH Input, Ibs              0.245
                                                             PAH Output, Ibs             0.283
                                                             PAH Recovery, percent         115
                                                                25
                                                                31
                                                               126
C.4.2   PCB Balance

Closures of 95 and 112 percent were obtained for PCBs
during the treatment of Sediments A and B, respectively.
The amount of PCBs entering the system was calculated
by multiplying the analytically determined value for PCB
concentrations present within the feed by the weight of
the  feed  entering the system.  This value  was then
compared with  the  cumulative  amount   of  PCBs
deposited in the various system products, particularly the
oil  product.  The PCB  balance results are consistent
with the demonstration  test  objectives of closures
between 80 and 130 percent. Mass balances for PCBs
are presented in Table C-5.
Table C-5.    PCB Mass Balances

                        Sediment A
Sediment B
  PCB Input, Ibs             0.00469

  PCB Output, Ibs            0.00444

  PCB Recovery, percent        95
   0.146

   0.163

   112
C.4.4   O&G Balance

Closures of 222 and 119 percent were  obtained for
O&G during the treatment of Sediments  A and B, re-
spectively.  The amount of O&G entering the system
was calculated by multiplying the analytically determined
value for the concentration of O&G present within the
feed by the weight of  the feed entering the system.
Values for O&G exiting the  system were determined
using analytical data regarding O&G concentrations
within the oil product.  The O&G mass balance closure
achieved for Sediment B met the demonstration object-
ive of closure between 80 and 130 percent.  The elevated
recovery obtained for Sediment A can in  part be attri-
buted to inaccuracies in the analytical values achieved
for O&G  concentrations  associated with the low oil
content of the sediment entering the system. The deter-
mination of the mass of O&G in the Sediment A pro-
duct oil and solvent mixture was also difficult because of
the high solvent fraction of this mixture.  In addition,
O&G in feed sediments were analytically determined by
extraction with methylene chloride, while  the  pilot unit
uses triethylamine as its extraction solvent.  The mass
balances for O&G  are presented in Table C-7.
                                                       38

-------
Table C-7.    O&G Mass Balances

                         Sediment A
Sediment B
 O&G Input, Ibs               3.48

 O&G Output, Ibs             7.71

 O&G Recovery, percent        222
   67.3

   80.0

   119
C.4.5   Water Balance

Water balances were performed during the demonstra-
tion by comparing the amount of process water entering
the B.E.S.T.®  system to the mass of product  water
exiting the system. Although the majority of the process
water enters the system as  part of the feed, a portion
enters the  B.E.S.T.®  system in the  extractor/dryer
vessel.  Closures of 125 percent and 116  percent were
obtained for testing performed on Sediments A and B,
respectively.  The water balance results are consistent
with  the  demonstration test objectives  of  closures
between 80 and 130 percent.  The water balances are
shown in Table C-8.
Table C-8. Water Mass Balances
Sediment A
Water Input, Ibs 555
Water Output, Ibs 692
Water Recovery, percent 125

Sediment B
767
888
116
C.4.6   Solvent (Triethylamine)  Balance

Triethylamine is used as the extraction solvent in the
B.E.S.T.® system.  The used triethylamine is recovered
and  reused without exiting  the system, although small
amounts of triethylamine remain in the treated solids,
water product, and oil product.  Solvent mass balance
closures of 87 percent and ,82 percent were obtained for
Sediments A and B, respectively.  The solvent balance
results  are consistent with  the demonstration test
objectives  of  closures between  80  and 130 percent.
Mass balances for triethylamine are presented in Table
C-9.
Table C-9.    Triethylamine Mass Balances
Sediment A
Triethylamine Input, Ibs
Triethylamine Output, Ibs
Triethylamine Recovery, percent
751
652
87
Sediment B
891
727
82
C.4.7   Total Materials Balance

Mass balances for all materials entering and exiting the
process were also calculated.  Closures of 99.3 percent
and  99.6 percent  were obtained for Sediment A and
Sediment B, respectively.  These closures are very good
and show that even though individual balances may vary
because  of  the  considerable number  of analyses
involved, no significant amount of material  is lost for
either Sediment A or Sediment B.  The mass balances
for the total materials are presented in Table C-10.
                    Table C-10.   Total Materials Mass Balances

                    	Sediment A   Sediment B

                    Total Materials Input, Ibs            1,784        2,010

                    Total Materials Output, Ibs           1,771        2,002

                    Total Materials Recovery, percent      99.3         99.6
                    C.4.8    Feed and Product Materials Balance

                    Mass  balances  for  all  feed and product  materials
                    (sediment,  water, steam, and sodium hydroxide feed
                    streams;  solid,  water, and oil products) entering and
                    exiting the process were also calculated. Closures of 108
                    percent and 114 percent were obtained for Sediment A
                    and Sediment B, respectively.  These closures comply
                    with the developer's claim that the mass balance of feed
                    material into the pilot unit versus total products (solids
                    plus water plus oil) out will be in the range of 85 to 115
                    percent.  The  mass balances for  the feed and product
                    material are presented in Table C-ll.
                    Table C-ll.   Feed and Product Materials Mass Balances

                                               Sediment A     Sediment B

                    Feed Materials Input, Ibs          1033          1119

                    Product Materials Output, Ibs      1119          1274

                    Recovery, percent     •          108           114
                    C.5    Leaching Characteristics

                    The metals portion of the TCLP was performed on both
                    the untreated sediment and the treated soh'ds. As stated
                    in Section 1  of this  report, the treated  solids and
                    untreated sediment both passed the TCLP for metals, so
                    no significant conclusions can  be drawn  from data
                    regarding the effects of the  B.E.S.T.®  process  in  the
                    treatment of metals.
                                                       39

-------
C.6    PAH and PCS  Concentrations in the
        Product Water and Product Oil

Table C-12 summarizes the PAH and PCB concentra-
tions measured in the product water generated during
each of the three optimum runs for each test sediment.
Averages of the optimum runs for each sediment are
also presented.  Table C-13 summarizes the PAH and
PCB concentrations measured in the oil produced from
the treatment of Sediment B. A total of five aliquots
(field replicates) of product oil were collected following
triethylamine removal in  the solvent evaporator  at the
end of the  fifth and final run.   This "oil polishing"
distillation procedure was not conducted for Sediment A
because  of the  small  amount of  oil  present  in
Sediment A.
C.7    Air Emissions

During the  demonstration,  the  ambient  air was
monitored  for  ionizable organic  vapors using  an
photoionization detector (PID).  The ambient ah- was
monitored  on  a daily  basis 5. meters  upwind and
downwind from the treatment unit. Particular emphasis
was placed on ambient monitoring for volatile emissions
attributed to the solvent employed by  RCC.   The
maximum limit for organic vapor concentration  in the
ambient air was 10 ppm above background levels; none
of the measurements  taken during the demonstration
test exceeded this limit.
                    Vent gases were filtered by primary and  secondary
                    activated  carbon  canisters  and  the  triethylamine
                    concentration  in the  air  between the  two carbon
                    canisters was monitored daily with reaction tubes. The
                    maximum limit for the triethylamine concentration in
                    the air between the two carbon canisters was 3.5 ppm.
                    This limit was exceeded twice during the demonstration
                    test  (15 ppm  and 30 ppm).   In  each instance,  the
                    primary carbon canister was replaced immediately and
                    the triethylamine concentration returned to below 3.5
                    ppm.   Vent gas  triethylamine emissions  were  not
                    measured at over 0.2 ppm at any time  during  the
                    demonstration.
                    C.8    Triethylamine Biodegradation  Testing
                            on Treated Solids

                    Triethylamine biodegradation  testing  on the treated
                    solids was added to the Demonstration Plan because it
                    was indirectly related  to  the  B.E.S.T.®  process.
                    Biodegradation was not a critical parameter in the
                    B.E.S.T.® SITE demonstration.  RCC, the  developer,
                    has referenced a U.S. Environmental Protection Agency
                    (EPA) report (EPA-600/2-82-001a) that states that 200
                    ppm of triethylamine in water was completely degraded
                    in 11 hours by Aerobacter, a common soil bacteria. The
                    use of this reference implies  that triethylamine may
                    biodegrade in the treated solids. Biodegradation testing
                    was thus  intended  to indicate whether triethylamine
                    would degrade in the treated solids produced during the
                    SITE demonstration.
Table C-12.   PAH and PCB Concentrations in the Product Water
                                                       Run Numbers
 Parameter
                                                         Average of
                                                       Optimum Runs
 Sediment A
 Total PAHs, pg/L
 Total PCBs, pg/L

 Sediment B
 Total PAHs, pg/L
 Total PCBs, /ig/L
<3
<3
                      <3
                                  <3
                                  <3
                                                            <3
Table C-13.   PAH and PCB Concentrations in the Sediment B Product Oil


                                                    Aliquot Number*
Parameter
Total PAHs, mg/kg
Total PCBs, mg/kg
1
498,000
2,030
2
438,000
1,750
3
299,000
2,520
4
297,000
2,150
5
436,000
2,180
Average
394,000
2,130
    The aliquots 1 through 5 were collected incrementally as the product oil in the solvent evaporator tank was drained by a hose into a drum.
                                                    40

-------
A very limited biodegradation study was conducted by
mixing equal portions of viable potting soil and treated
product  solid  samples  collected from three  of the
demonstration test runs (two Sediment A samples and
one Sediment B  sample).   For  each of  the three
sediment samples, two sets of 12  test  vials  were
prepared; the first set contained unaltered mixtures and
the   second   "control"   set   contained   the  same
homogeneous mixture spiked with mercuric chloride.

The samples were  then  stored away from light at room
temperature as test sample/control sample pairs. Each
pair was analyzed at four separate time intervals.
                                                Table C-14 summarizes the biodegradation test data.
                                                The  results  of the  biodegradation  study are  quite
                                                variable but they do not appear to provide any evidence
                                                that  triethylamine  present at  25  to  100  ppm  is
                                                biodegraded in this soil within 2 months of application.
                                                 C.9    Particle Size Distribution

                                                 Table C-15  presents particle  size distribution data for
                                                 the untreated solids (by dry sieve testing). The particle
                                                 size analyses demonstrate the ability of the B.E.S.T.®
                                                 system to treat materials containing a large fraction of
                                                 fine particles.
Table C-14.
Triethylamine Biodegradabflity in Treated Solids
                                   Time Interval Concentrations, mg/kg dry weight*
Sample
Sediment A, Run 1
Test Cell
Control Cell
Sediment A, Run 4
Test Cell
Control Cell
Sediment B, Run 4
Test Cell
Control Cell
DayO

85.8
73.6

42.4"
30.4b
- '-'-'-•
147
146
a All concentrations are the average of three replicate runs,
b Duplicate analysis was not performed on any of the three
Day 14

85.5
92.3

53.1
50.4

140
155
one of which was analyzed
replicate run samples.
Day 28

55.0
68.9

65.0
70.9

148
146
in duplicate.
Day 56

66.9
57.0

64.7
71.4

152
158

 Table C-15.   Particle Size Analysis Results
                                                             Percent of Total
  Sample
                         > 4.75 mm*
                              4.75-2.00 mmb
                2.00-425
                425- 75 /imd
                                                                                                      <75
  Sediment A
     Feedf
     Treated Solids*
  Sediment B
                0.00
                0.31
4.60
3.86
27.55
14.60
40.16
49.87
27.69
31.36
Feedf
Treated Solids*
0.00
2.38
0.10
12.01
4.25
60.01
57.20
23.83
38.45
1.78
 a  Retained by No. 4 sieve
 b  Retained by No. 10 sieve
 c  Retained by No. 40 sieve
 d  Retained by No. 200 sieve
 e  Passes No. 200 sieve
 f  Wet sieve
 g  Dry sieve
                                                         41

-------
                                              Appendix D
                                             Case Studies
D.I    Massena, New York Pilot-Scale Testing

Pilot-scale  tests were  conducted in September and
October of 1991 in Massena, New York to determine
the  ability  of Resources  Conservation  Company's
(RCCs) Basic Extractive Sludge Treatment (B.E.S.T.®)
solvent  extraction system to treat six wastes from  an
aluminum manufacturing facility.  Three of the wastes
were sludges taken from three lagoons,  including a
soluble  oil lagoon and a sanitary lagoon.   The other
three wastes were soils, two  of which were taken from
a waste lubricating oil landfill and a oily waste landfill.

Polychlorinated  biphenyls  (PCBs)  were  the  target
contaminants in all sk wastes. Treatment results for the
six wastes are shown in Table D-l. The concentrations
of PCBs initially present in  the wastes ranged from 5
mg/kg to 800 mg/kg, while the treated solids contained
between 0.2 mg/kg and 1.0 mg/kg of PCBs.   The
objective of these tests was  to determine whether the
B.E.S.T.® process was capable of reducing the PCB
concentrations in the soils and sludges to less than 2.0
mg/kg.  This goal was achieved for ah* six wastes.
D.2    Pilot-Scale  Testing  of  Wastes  from
        Wood Treating Facilities

In June 1991, the pilot-scale B.E.S.T.® solvent extraction
unit was  used  to conduct  treatability studies  on
contaminated soil from two wood treating facilities. The
soils were transported from the two facilities to the test
location in Vicksburg, Mississippi.

The treatability tests conducted on the wood treating
wastes were sponsored by  the  U.S. Environmental
Protection Agency (EPA). The objective of these tests
was to determine the Best Demonstrated Available
Technology (BDAT) standard for contaminated soil and
debris. This standard was successfully established.

Polynuclear  aromatic hydrocarbons (PAHs) were  the
target contaminants in these treatability tests. The soil
from one of the wood treating facilities contained 10,900
mg/kg PAHs; the resulting treated solids contained 109
mg/kg.  This represents  a  99  percent reduction  in
PAHs.  The soil from the other  wood treating facility
contained 14,000 mg/kg of PAHs. Following B.E.S.T.®
Table D-l.    Treatment of Aluminum Manufacturing Soils and Sludges
Waste Origin
Soluble Oil Lagoon
Sanitary Lagoon
60 Acre Lagoon
Waste Lubricating Oil Landfill
Oily Waste Landfill
Dcnnison Crossroads
Initial PCB Concentration
530 mg/kg
137 rag/kg
480 mg/kg
800 mg/kg
13 mg/kg
5 mg/kg
Final PCB Concentration
0.7 mg/kg
0.6 mg/kg
1.0 mg/kg
1.0 mg/kg
0.3 mg/kg
0.2 mg/kg
Removal of PCBs,
percent
99.9
99.6
99.8
99.9
97.7
96.0
                                                     42

-------
     solvent extraction, the  treated  solids contained 8.2
     mg/kg PAHs. This represents a 99.9 percent reduction
     in PAHs.
     D.3   Pilot-Scale   Testing   of  Waste  from
            Machining Operations

     In December 1989,  the B.E.S.T.® pilot-scale unit was
     used to conduct a treatability study in Greenville, Ohio.
     The soil at this site became contaminated with PCBs as
     a result of the  disposal of  lubricants  from machining
     operations.  B.E.S.T.*  solvent extraction reduced the
     PCB concentration in the soil from 130 mg/kg to 2.5
     mg/kg hi the treated solids,  a reduction of 98.1 percent.
     This  treatability  test  easily  met  its  objectives of
     producing treated solids containing less than 10 mg/kg
     PCBs.
     D.4    Pilot-Scale    Testing
             Refining Sludge
of  Petroleum
     The B.E.S.T.® pilot-scale solvent extraction unit was
     employed in February 1989  for  a  treatability test
     conducted in Baton Rouge, Louisiana.  The objective of
     this treatability test was to establish BDAT standards for
     K048-K052 wastes. These standards are partially based
     on the performance of the B.E.S.T.* unit during this
     pilot-scale test.   The waste  treated was  a  sludge
     containing PAHs and oil and  grease  (O&G) from
     petroleum refining operations.

     The petroleum refining sludge was initially 26 percent
     O&G. The  treated solids generated by the B.E.S.T.®
     solvent extraction system  contained 0.09 percent O&G
     and 11.6 mg/kg PAHs.
     D.5    Full-Scale Treatment of Oily Sludges

     RCC's prototype full-scale B.E.S.T.® solvent extraction
     system was employed hi the treatment of oily sludge at
     the General Refining site hi Garden City, Georgia. This
     oily sludge was generated during waste oil reclamation
     and re-refining activities and was disposed of hi unlined
     lagoons.  RCC mobilized the full-scale B.E.S.T.® unit
     and installed it at the General Refining site hi mid-1986.
     The system was tested and  modified, then employed hi
     the treatment  of approximately 3,700 tons  of oily
     sludges. An extensive 24-hour sampling and monitoring
     program  was  conducted  during the  last week of
     treatment, which was concluded hi March 1987 [1].

     The  24-hour  test was  conducted by  RCC with  the
     assistance of the EPA Region X Environmental Services
Division  and  Region  IV Emergency  Response  and
Control Branch. The primary objective of this test was
to determine the B.E.S.T.® system's ability to separate
the feed components  and isolate them into  specific
product streams.   The feed contained PCBs, metals
(primarily  lead),  volatile organics,  and  semivolatile
organics [1].

Samples were  collected from the feed stream, product
oil, product solids, aqueous  product  (before and after
the water treatment system), blowdown sludge from the
water treatment  system,  process  air  emissions,  and
recycled solvent.  The organics (PCBs, volatiles, and
semivolatiles) from the feed were concentrated hi the oil
fraction, although minimal amounts  of organics were
present hi the  solid and aqueous products. The metals
from the feed  were primarily concentrated hi the solid
product, but the concentration of lead hi the oil product
was also significant.  The low concentrations of metals
hi the aqueous phase were further reduced hi the Water
treatment system  [1].

After metals removal, the aqueous product was suitable
for discharge  into an industrial wastewater treatment
facility.  TCLP results for lead hi the solids product
ranged from 4.0 to 12 mg/L, while the regulatory level
is 5 mg/L.   Because the  lead was only marginally
leachable  and  the other metals were present hi stable
forms that resisted leaching, the test report states that
the solids are potentially  eligible for land disposal  or
detisting [1]. The oil product was sold  as fuel to a fuel
blender.

The B.E.S.T.® solvent extraction system used during this
project is a prototype and  is the only full-scale unit
currently available. This prototype system is capable of
treating up to  100 tons of contaminated sludge per day
(it is not applicable to contaminated  soils). Forty tons
of sludge were treated during the 24-hour testing period.
The average solvent to feed ratio during this period was
4 to 1. Because the system recycles the solvent, only 16
pounds of solvent were  consumed per ton of sludge
treated. Furthermore, RCC estimates the system can be
modified such that it will only consume 2.5 pounds of
solvent per ton of sludge treated [1].
                        D.6   Reference

                        1. U.S. Environmental Protection Agency. Evaluation
                           of  the   B.E.S.T.®   Solvent  Extraction   Sludge
                           Treatment Technology  Twenty-Four  Hour Test.
                           EPA/600/2-88/051, August 1988.
*U.S. GOVERNMENT PRINTING OFFICE: 1993-753-009
                                                          43

-------

-------