&EPA
           United States
           Environmental Protection
           Agency
           Office of Research and
           Development
           Washington DC 20460
EPA/540/AR-93/503
January 1995
BESCORP Soil Washing
System for Lead Battery
Site Treatment
           Applications Analysis Report
                SUPERFUND INNOVATIVE
                TECHNOLOGY EVALUATION

-------


-------
                                          EPA/540/AR-93/503
                                              January 1995
BESCORP Soil Washing System for
     Lead Battery Site Treatment

     Applications Analysis  Report
          Risk Reduction Engineering Laboratory
           Office of Research and Development
          U.S. Environmental Protection Agency
               Cincinnati, OH 45268

-------
                                           Notice

The information in this document has been funded by the U.S. Environmental Protection Agency (EPA)
under the auspices of the Superfund Innovative Technology Evaluation (SITE) Program under Contract No.
68-C9-0033 to Foster  Wheeler Enviresponse, Inc.  It has been  subjected to the Agency's  peer  and
administrative review, and it has been approved for publication as an EPA document.  Mention of trade
names or commercial products does not constitute an endorsement or recommendation for use.

-------
                                          Foreword
The Superfund Innovative Technology Evaluation (SITE) Program was authorized in the 1986 Superfund
Amendments. The Program is a joint effort between EPA's Office of Research and Development and Office
of Solid Waste and Emergency  Response.  The purpose of the program is to enhance the development of
hazardous waste treatment technologies necessary for implementing new cleanup standards that require
greater reliance  on permanent remedies.   This is accomplished  by  performing  the technology
demonstrations designed to provide engineering and economic data on selected technologies.

This project consists of an evaluation of the BESCORP Soil Washing System (BSWS). The Demonstration
Test took place at the Alaskan Battery Enterprises (ABE) Site in Fairbanks, Alaska.  The primary technical
objective of this project  was to determine the ability of the process to produce washed soil that would
comply with EPA's lead cleanup goals for redeposit at the site (less than 1,000 mcj/kg total  lead a*nd less
than 5 mg/L TCLP  lead).  The goals of the study were (1)  to evaluate the technical effectiveness and
economics of this technology relative to its ability to treat soils contaminated with lead, lead compounds,
and battery casing chips from broken lead batteries; and (2) to establish the potential applicability of the
process to other wastes and Superfund sites.  The results are summarized in this Applications Analysis
Report.

Additional copies of this report may be obtained at no charge from EPA's Center for Environmental Research
Information, 26 West Martin Luther King Drive, Cincinnati, Ohio, 45268, using the EiPA document number
found on the report's front cover.  Once  this supply is exhausted, copies can be purchased from the
National Technical Information Service, Ravensworth Building, Springfield, Virginia, 22161, (703) 487-4600.
Reference copies  will be available at EPA libraries in their Hazardous Waste Collection.
                                                          E. Timothy Oppelt, Director
                                                          Risk Reduction Engineering Laboratory

-------
                                           Abstract
This report evaluates the Brice Environmental Services Corporation (BESCORP)  Soil Washing  System
(BSWS) and  Its applicability  in remediating lead-contaminated  soil at lead battery  sites.  It presents
performance and economic data,  developed from the U.S. Environmental Protection  Agency Superfund
Innovative Technology Evaluation  (SITE) Demonstration (three test runs) and additional data provided by
the developer. The Demonstration took place at the Alaskan Battery Enterprises (ABE) Site in Fairbanks,
Alaska.

The original BSWS, built to  process 20 tons per hour (tph) of  soli when  removing  silt and clay from
uncontamlnated  sandy soil, was a water-based, volume-reduction unit that employed agitation,  attrition
scrubbing, high pressure washing,  and particle size separation.  This system was modified to remove lead,
lead compounds, and battery casing chips through the addition of a density separator and a casing chip
separator. The modified system capacity is about 5 tph, primarily due to restricted flow in the casing chip
separator.

Products from the process included washed gravel and sand, a metallic-lead fraction, battery casing chips,
a water effluent  suitable for  discharge to a POTW, and a lead-contaminated sludge effluent for RCRA
disposal or posttreatment. The metallic lead and casing chips were potentially recyclable to lead smelters.
However, this is not a current industry practice.

The system, operating from 2 to 4 tph, generated a washed gravel product, free of fine material, that passed
EPA's redeposit cleanup goals for total lead (less than 1,000 mg/kg) and TCLP lead (less than 5 mg/L).
The washed sand did not achieve the cleanup goals due to the presence of contaminated  fines that the
system did not separate from the sand fraction.  BESCORP did not anticipate  this result during the
Demonstration because the feed soil  differed significantly from the soil  samples tested in the pre-
Demonstratton treatability study.

Economic data for a commercial 20-tph unit processing wastes similar to those treated in the SITE
Demonstration, Including disposal  of waste effluents, project operating costs to be about $165/ton of soil
(dry basis) containing 6.6 wt percent moisture. This figure does not reflect any revenue from recycling of
metallic lead or casing chips.
                                               IV

-------
                                          Contents
Notice  	       ii
Foreword  	       iii
Abstract	       iv
Tables	      viii
Figures  	       x
Abbreviations	       xi
Acknowledgements	      xiii


1,   Executive Summary	       1
     1.1  Background  	       1
     1.2  Overview of the SITE Demonstration	       1
     1.3  Results and Conclusions	       2
2.   Introduction	       5
     2.1  The SITE Program	       5
     2.2  SITE Program Reports	       5
     2.3  Key Contacts   	       6
3.   Technology Applications Analysis	       7
     3.1  Introduction	       7
     3.2  Conclusions	       7
     3.3  Technology Evaluation	       9
          3.3.1    Lead Battery Sites  	       9
          3.3.2    Soil Washing Process  	      10
          3.3.3    Feed Soil Characterization  	,	      10
          3.3.4    Mass Balances and Process Stream Characterization  	:..      12
          3.3.5    Process Performance	      12
          3.3.6    Scale of Operation and Reliability	      12
     3.4  Ranges of Site  Characteristics Suitable for the Technology	      17
          3.4.1    Site Selection   	,	      17
          3.4.2    Topographical Characteristics   	      17
          3.4.3    Site Area  Requirements   	      17
          3.4.4    Climate and Geological Characteristics	      17
          3.4.5    Utility Requirements	      17
          3.4.6    Size of  Operation	      17
     3.5  Applicable  Media  	      17
     3.6  Environmental Regulation Requirements	      18
     3.7  Personnel Issues	      18
          3.7.1    Training	      18
          3.7.2    Health and Safety   	      18
     3.8  References  	      19

-------
                                   Contents (Continued)
                                                                                        Page

4.  Economic Analysis	      20
     4.1   Introduction  	      20
     4.2   Conclusions	      20
     4.3   Issues and Assumptions	      20
          4.3.1   Costs Excluded from Estimate  	      21
          4.3.2   Utilities	      21
          4.3.3   Operating and Maintenance Schedules	      21
          4.3.4   Labor Requirements	      21
          4.3.5   Capital Equipment and Fixed Costs  	      21
          4.3.6   System Design and Performance Factors  	      21
          4.3.7   System Operating Requirements	      21
     4.4   Basis of Economic Analysis  	      21
          4.4.1   Site Preparation Costs 	      24
          4.4.2   Permitting and Regulatory Costs	      24
          4.4.3   Equipment Costs	      24
          4.4.4   Startup Costs  	      24
          4.4.5   Labor Costs	      27
          4.4.6   Supplies and Consumables	      27
          4.4.7   Utilities	      27
          4.4.8   Effluent Treatment and Disposal Costs  	      27
          4.4.9   Residuals and Waste Shipping, Handling, and Disposal Costs  	      27
          4.4.10 Analytical Costs   	      27
          4.4.11  Facility Modification, Repair, and Replacement Costs 	      28
          4.4.12 Site Demobilization and Decontamination Costs	      28
     4.5   Results of Economic Analysis  	      29
     4.6   References	      29

Appendices

     A    Process Description  	      30
          A.1   Introduction	      30
          A.2   Process Description	      30

     B    Vendor Claims for the BESCORP Soil Washing System   	      33
          B.1   Introduction	      33
          B.2   Technology Description  	'	      33
          B.3   Claims	      33
          B.4   Description of Demonstration Conditions   	      35
          B.5   BSWS Modified Commercial Unit for ABE-Type Lead Removal  .,	      35
                                              VI

-------
                              Contents (Continued)
                                                                                    Page
C    SITE Demonstration Results  	      37
     C.1   Introduction   	      37
     C.2   Soil Washer Performance	      39
           C.2.1   Overview  	      39
           C.2.2   Process Monitoring and Control  	      39
           C.2.3   Performance Summary  	      52
           C.2.4   Input and Output  Flow Rate Stability  	      53
     C.3   References  	      54

D    Case Studies  	      55
     Case D.1   Treatability Study and Site Remediation: Army Ammunition Plant	      55
     Case D.2   Removal of Minus 100 Micron (150 Mesh) Material:
                Hanford Simulated Soil 	      57
     Case D.3   Discrete Partial Recovery  Plant:  Tramway Bar Mine, Alaska	      58
     Case D.4   On-Site Field Test: Radium-Contaminated Soil at Oklahoma Mr Force
                Base 	      59
     Case D.5   Copper Wire Incineration and Recovery Site Treatability Study:
                Lead-Contaminated Soil	      59
     Case D.6   Lead-Contaminated Metal Recycling Facility	      60
     Case D.7   Lead-Contaminated Target Range Sites	      61
     Case D.8   Treatability Study: Hydrocarbon-Contaminated Soils 	      62
     Case D.9   Uranium-Contaminated Soils	      62
     Case D.10  ABE Treatability Study 	      62
                                         VII

-------
                                    Tables





Number                                                                     Page.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
B-1
C-1
C-2
C-3
C-4
C-5
C-6
BESCORP SITE Demonstration Test Results 	
SITE Lab Data for Washed -1/4C1 to +10 Mesh Sand 	 	 	
BESCORP Lab Data for Washed -V? to +80 Mesh Sand 	
Vendor's Projected Commercial Performance 	
Summary of Key Process Stream Characterization Data 	
Lead Distribution 	 	 	
Mass Balances for the Three SITE Demonstration Test Runs 	
Mass Balance for Commercial Unit 	
Lead Removal (Process) Efficiencies 	 	
Lead Removal (Total) Efficiencies 	
Process Efficiency 	
Casing Chip Removal 	 	 	
BSWS Average System Mass Balance for Commercial Unit 	 	 	
Utilities and Consumables 	
Treatment Costs for the BSWS Modified Commercial Unit 	 	 	 	
BSWS Capital Equipment Cost Breakdown 	 	 	
Excavation Labor Requirements 	 	 	
BSWS Assembly Labor Requirements 	 	 '. 	
Operations Labor Requirements 	
BESCORP Attrition Washing and Screening Vendor Bench-Scale Data 	
Key Process Stream Characterization Data 	
Statistical Summary of Lead In Feed Soil, Gravel, and Sand Fractions 	 	
Detailed Mass Balances for the Three SITE Demonstration Runs 	
Lead Partitioning 	
Performance Summary 	
Downtime Summary for the Three Runs 	
2
3
3
4
8
9
13
15
16
16
16
17
23
23
25
26
28
28
28
36
41
42
43
52
53
54
                                       viii

-------
                                        Tables (Continued)

Number                                              .                                      Page
   D-1    Particle Size and Lead Distribution at an Army Ammunition Site  	      56
   D-2    Cleanup Levels for TCAAP 	      57
   D-3    Size Separation  Efficiency  	      58
   D-4    Material Balance for a 150-tph Plant  	      58
   D-5    Particle Size and Metals Distribution at a Copper Wire Site	      59
   D-6    Particle Size and Lead Distribution at a Lead Recycling Facility  	      60
   D-7    Particle Size and Lead Distribution before and after Treatment	      60
   D-8    Particle Size and Lead Distribution at Target Ranges	      61
   D-9    Particle Size and Lead Distribution in Rl Raw Sample  	      63
   D-10    Lead Distribution in Rl Sample After Processing  	      63
   D-11    Lead Distribution in Second Fraction of Rl Sample after Processing  	      63
   D-12    Particle Size and Lead Distribution in Rl Sample after Simulated Processing	      64
                                                IX

-------
                                         Figures

Number                               •                                               Page
   1      The BESCORP Soil Washing System 	      11
   2      Simplified BSWS flow diagram for the SITE Demonstration 	      14
   3      BSWS modified commercial-scale flow diagram 	      22

   A-1      BESCORP Soil Washing System (isometric drawing) 	      31
   B-1      BESCORP block flow diagram  	      34
   C-1      ABE site map  	      38
   C-2      Detailed BSWS flow diagram for SITE Demonstration  	      40
   C-3      Plant layout  	      44
   C-4      Run 1 - total lead concentration in feed soil and washed gravel and sand  	      45
   C-5      Run 2 - total lead concentration in feed soil and washed gravel and sand  	      46
   C-6      Run 3 - total lead concentration in feed soil and washed gravel and sand  	      47
   C-7      Lead TCLP in washed gravel and  sand   	      48
   C-8      Run 1 - solid stream flows 	      49
   C-9      Run 2 - solid stream flows 	      50
   C-10     Run 3 - solid stream flows  	      51

-------
                                     Abbreviations
AAR
ABE
ARAB
avg.
BESCORP
BSWS
CEC
CERCLA
yd3
EPA
FWEI
gpm
H2SO4
HSWA
kwh
Ib/ft3
meq/L
mg/kg
mg/L
NPL
OERR
ORD
OSHA
OSWER
POTW
ppb
ppm
QAPP
Applications Analysis Report
Alaskan Battery Enterprises (Superfund NPL Site)
Applicable or Relevant and Appropriate Requirements
average
Brice Environmental Services Corporation
BESCORP Soil Washing System
cation exchange capacity, meq/L
Comprehensive Environmental Response, Compensation, and Liability Act
cubic yards
U.S. Environmental Protection Agency
Foster Wheeler Enviresponse, Inc.
gallons per minute
sulfuric acid
Hazardous and Solid Waste Amendments to RCRA -1984
kilowatt-hour
pounds per cubic foot
milliequivalents per liter
milligrams per kilogram (ppm)
milligrams per liter (ppm)
National Priorities List
Office of Emergency and Remedial Response
EPA Office of Research and Development
Occupational Safety and Health Act
EPA Office of Solid Waste and Emergency Response
publicly owned treatment works
parts per  billion
parts per  million
Quality Assurance Project Plan
                                            XI

-------
                               Abbreviations (Continued)

QA/QC        quality assurance/quality control
RCRA         Resource Conservation and Recovery Act of 1976
RFP          Request for Proposal
Rl            Remedial Investigation
RREL         Risk Reduction Engineering Laboratory
SARA         Superfund Amendments and Reauthorization Act of 1986
sp gr         specific gravity, gr/cc
SITE          Superfund Innovative Technology Evaluation
TCI.P         toxicity characteristic leaching procedure, mg/L
TER          Technology Evaluation Report
TM           trademark
TOC          total organic content
TPH          total petroleum hydrocarbons
tph           (short) tons per hour
                                            XII

-------
                                   Acknowledgements
This project was directed and coordinated by Hugh Masters, EPA SITE Project Manager in the Releases
Control Branch of the Risk Reduction Engineering Laboratory, Edison, New Jersey.

This report was prepared for EPA's Superfund Innovative Technology Evaluation (SITE) Program by Roger
J.  Gaire, P.E., of Foster Wheeler Enviresponse, Inc. (FWEI) under Contract No. 68-C9-0033.  FWEI,
supervised  by  Michael Merdinger,  performed  field  activities, including sampling.  Laucks Testing
Laboratories, Inc. performed the chemical analyses for this SITE Demonstration.  Dr. James Stumbar of
FWEI conducted a technical review. The cooperation and participation of BESCORP throughout the course
of the project and in the review of this report are gratefully acknowledged.

Keith Rose, Remedial Project Manager of EPA Region 10, provided assistance and guidance in initiating the
project and in interpreting and responding to regulatory requirements.
                                             xiii

-------
Intentionally

-------
                                            Section 1
                                     Executive Summary
7.7    BACKGROUND

In 1986,  the  U.S.  Environmental Protection Agenqy
(EPA) established the Superfund Innovative Technology
Evaluation (SITE) Program to promote the development
and  use  of  innovative technologies  to remediate
Superfund sites. Technologies in the SITE Program are
analyzed  in two documents, the Technology Evaluation
Report and the Applications Analysis  Report.  This
Applications Analysis Report evaluates the applicability
of the  Brice  Environmental Services  Corporation
(BESCORP)  Soil   Washing  System   (BSWS),  and
estimates the costs of operating it based on available
data.  Data not generated from the SITE Demonstration
were provided by BESCORP, the technology developer.

The BSWS was evaluated under EPA's SITE Program,
based on a Demonstration Plan agreed to by EPA and
BESCORP. The Demonstration was conducted at the
Alaskan Battery Enterprises (ABE)  Site  in Fairbanks,
Alaska on the basis  of a  remedial investigation (Rl)
report and the site's inclusion on the National Priorities
List (NPL). The primary objectives  of the BSWS SITE
Demonstration  consisted of the following:
•   Assess the ability of the  process to comply with
    EPA's lead cleanup  goals for redeposit of washed
    soil at the site (less than 1,000 mg/kg total lead and
    less than 5 mg/L TCLP lead),

•   Determine if the BSWS can achieve greater than 75
    percent process efficiency by cleaning sufficient
    percentages of contaminated gravel and sand to the
    levels suitable for redeposit, and

•   Develop economic data for the BSWS.
Secondary objectives were as follows:

•    Determine if the washed battery casing chips meet
     the cleanup goals,

•    Evaluate the BSWS reliability, and

•    Document the operating conditions of the BSWS
     for application to other hazardous waste sites.

This  report  provides information  based on the results
from the SITE Demonstration and related case studies.
This information is necessary if the BSWS technology is
to be considered for use on Superfund and Resource
Conservation  and  Recovery Act (RCRA)  hazardous
waste sites.  Section 2 of this  report presents  an
overview of the SITE Program, explains how the SITE
Program results are documented, and lists key contacts.
Section 3 discusses the SITE Demonstration objectives,
describes the  Demonstration, and relates its findings to
the technology's application.  This includes potentially
applicable state and federal environmental regulations,
the effects  of waste  characteristics  and  operating
parameters  on  technology  performance,  applicable
media, and personnel issues.  Section 4 summarizes the
costs of implementing the1 technology. The Appendices
provide A) a description  of the BSWS technology, B)
BESCORP's claims  regarding this technology,  C) a
summary of the SITE Demonstration results,  and  D)
information  from case studies prepared by BESCORP.

12  OVERVIEW OF THE SITE
     DEMONSTRATION

The BSWS was demonstrated at the ABE Site in August
1992. About 46 tons of soil contaminated with broken
lead batteries were treated during the program. The soil

-------
was  excavated, passed  through  a 2W screen,  and
stockpiled as feed for the unit.  The Demonstration
Included a series  of shakedown tests and three test
runs.  As shown  in Table 1, the feed soil  analyses
differed, to a minor degree, for each of the three runs.
They  necessitated  certain  proprietary   process
adjustments, but no major modifications.

Extensive  data were  collected  to  assess  process
performance.  Liquid and solid samples were  analyzed
to determine lead partitioning and  leaching potential of
the process streams.  Operating data were monitored
and  recorded,  Including the raw  waste  feed rate,
washed gravel and sand  rates, electrical consumption,
water make-up, pH, and temperature.
1.3  RESULTS AND CONCLUSIONS

In summary, the BESCORP Demonstration was a partial
success in terms  of removing large battery casings,
casing chips, and discrete, metallic-lead particles from
the washed gravel and sand fractions. The process
effectively washed the gravel fraction (Table 1) to  meet
the cleanup goals after process adjustments during the
first run.

Although significant lead reduction was achieved in the
sand  fraction,  the cleanup  goals were not attained.
However, Table 2 SITE laboratory analytical data for the
minus 14" to plus 10 mesh sand fractions, which were
extracted from Table 5, Indicate that this coarser portion
               TABLE 1.  BESCORP SITE DEMONSTRATION TEST RESULTS

Run
1
2
3
Feed soil
Total Pb
mg/kg
Avg.
4,210
10,400
2,280
Range
2,290 - 8,870
2,910-45,500
951 -4,710
Standard
deviation*
2,600
12,700
1,130
Pb TCLP
mg/L
Avg,
72
132
50
Range
42-170
61-440
26-90
Standard
deviation
42
117
21
Washed gravel
1
2
3
2,540
903
15
32 - 9,630
17 - 6,640
5-32
3,200
2,070
8
1.0
0.8
0.2
0.4-1.6
0.5 - 1.1
0.1 - 0.6
0.4
0.2
0.2
Washed sand
-%" to 150 mesh
1
2
3
1,810
1,670
1,510
1,450-2,000
963 - 2,480
830 - 1,900
260
530
310
42
40
26
37-48
30-47
21 -29
3
5
3
        *Tho presence of metallic lead particles caused wide variations in the standard deviation. This is discussed in Appendix C.

-------
            TABLE 2.  SITE LAB  DATA FOR WASHED -W TO +10 MESH SAND
                                    (Extracted from Table 5)

SITE Run 1
SITE Run 2
SITE Run 3
Total
Pb
Avg.
191
162
69
Pb
TCLP
Av9-
4.8
5.7
1.7
Washed sand dry basis
wt. %
Avg.
44.3
43.7
38.3
        TABLE 3.  BESCORP LAB DATA FOR WASHED -1/4" TO +80 MESH SAND*

SITE Run 1
SITE Run 2
SITE Run 3
Total Pb
mg/kg
Avg.
184
185
225
Pb TCLP
mg/L
Avg.
2.6
4.4
2.5
                   *The data above were not generated during the SITE Demonstration, but developed in
                   vendor laboratory tests that did not employ U.S. EPA QA/QC procedures.
of the washed sand (about 40%) is substantially within
the cleanup goals.

The data in Table 3 suggest process performance could
be improved; however, no SITE data were developed to
verify this conclusion.   In  Appendix  B,  BESCORP
discusses post-Demonstration tests on the washed sand
fraction. Based on these tests, BESCORP claims that
the addition of an attrition scrubber, plus size separation
(at plus 80 mesh) in a third separation chamber, would
improve the performance of the BSWS.

The data provide a basis for the following conclusions:

•  Lead  removal  (process) efficiencies in  the three
   Demonstration  test  runs,   measured  as  the
   percentage of lead  removed from the gravel  and
   sand fractions of the feed, were 28, 91, and  77,
   respectively. The higher removal efficiencies during
   Runs 2 and 3 are traceable to process adjustments
   made during the first run.  Total  lead removal,
   based on the lead content of all the  feed fractions,
reached 61, 93,  and 85  percents.respectively.
Calculations are presented in Section C.2.3.

The process efficiency, which is represented by the
washed gravel  and sand (minus 2W to plus 150
mesh) that meet EPA cleanup goals, expressed as
a percentage of the Feed that was greater than 150
mesh, improved significantly from 11 to 32 to 49
percent during  the three runs.  However,  process
efficiency did not approach the 75 percent SITE
objective.  The  failure  of the sand fraction to meet
the cleanup goals contributed  significantly to the
loss in process efficiency.

The three runs produced  the following  battery
casing chip removal efficiencies (measured as the
percentage of chips removed from the gravel and
sand fraction):  97,  100, and 70, respectively.  As
expected,   none  of  the  Demonstration runs
produced a washed casing chip fraction that met
the EPA cleanup goals for redeposit.

-------
   The cost to remediate 30,000 yd3 or 56,362 tons
   (dry) of contaminated soil, using a 20-tph modified
   commercial  BSWS,  is  estimated  at  $165/ton,
   assuming the system is on-line 80 percent of the
   time.   This  cost excludes  solid-waste effluent-
   shipping costs to a RCRA landfill. The modified unit
   adds an attrition scrubber and a third separation
   chamber to yield a smaller  washed  gravel/sand
   fraction  (minus 2V£" to  plus  80 mesh),  which
   BESCORP claims will meet the  cleanup goals as
   shown in Table 4.

   On  this  basis,  BESCORP  projects a process
   efficiency of about 71 percent for the ABE-Site-type
   soil.  In addition, BESCORP projects both lead and
   casing chip removal efficiencies in the 20-tph unit to
   be greater than 90  percent,  due  to  improved
   process control and elimination of bottlenecks in the
   Demonstration  unit.  No SITE Demonstration data
   are available to verify these projections.

   The BSWS is adaptable to soils containing battery
   casings, casing chips, or  metallic lead.   Much of
   the lead removal is achieved by separation of the
battery casings and metallic lead from the feed
soil.

The unit operated at feed rates from 2.4 to 4.2 tph
with a process on-line reliability of 87 percent.
Scale-up risk  to a 20-tph  commercial unit  is
minimal, even with the addition of equipment for
sand washing and a clarifier  sludge vacuum filter
for  minimizing water loss.

The effectiveness  of  the  BSWS as a volume
reduction unit is dependent on (1) the insolubility
of the lead compounds in the washing medium, (2)
the lead separation from  the gravel and  sand
fractions by  density  separation  that  removes
discrete, metallic-lead particles and by sieving that
removes the contaminated  fines, and (3) the feed
soil particle size distribution.

Treatability studies on  representative feed soil are
required to determine the cut point of washed
gravel/sand fraction that meets the EPA cleanup
goals and to predict the effectiveness of the BSWS
on other feedstocks.
           TABLE 4.  VENDOR'S PROJECTED COMMERCIAL PERFORMANCE
Feed soil
Total Pb
mg/kg
Avg.
5,600
Pb TCLP
mg/L
Avg.
85
Washed gravel
Total Pb
mg/kg
Avg.
150*
Pb TCLP
mg/L
Avg.
0.5*
Washed sand
-1A" to +80 mesh
Total Pb
mg/kg
Avg.
200*
Pb TCLP
mg/L
Avg.
3*
"The data above were not generated during the SITE Demonstration, but developed in vendor laboratory tests that did not employ
 U.S. EPA QA/QC procedures.

-------
                                            Section 2
                                           Introduction
2.1    THE SITE PROGRAM

The  EPA Office of  Solid  Waste  and  Emergency
Response (OSWER) and the Office  of Research and
Development  (ORD)   established  the   Superfund
Innovative Technology Evaluation (SITE)  Program in
1986  to   promote   the   development   and
commercialization  of   innovative .  technologies  to
remediate Superfund sites across the country. Now. in
its eighth year, the SITE Program is helping to provide
the treatment  technologies necessary to  meet new
federal and state cleanup standards aimed at permanent
remedies, rather than short-term corrections. The SITE
Program   includes  four  major  elements:'    the
Demonstration Program,  the Emerging Technologies
Program,   the   Measurement  and   Monitoring
Technologies Program,  and Technology  Information
Services.

The  major  focus  has been on  the  Demonstration
Program, designed to provide engineering and cost data
on selected technologies.  EPA and the technology
developers  participating in the program share the. cost
of the demonstration.  Developers are  responsible  for
demonstrating their  innovative systems,  usually  at
Superfund sites agreed upon by EPA and the developer.
EPA is responsible for sampling and  analysis activities
and  test  result  evaluation.   The  outcome  is  an
assessment of the technology's performance, reliability,
and  cost. This information, used in conjunction with
other data,  enables EPA and state decision-makers to
select the most appropriate technologies to remediate
Superfund sites.

Innovative   technology   developers  apply  to  the
Demonstration Program by responding to  the annual
EPA solicitation.   To  qualify  for  the program,  a
technology developer must have a pilot- or full-scale unit
and  offer some advantage over existing technologies.
Mobile technologies are of particular interest to the EPA.
Once EPA has accepted a proposal, the SITE Program,
the developer, the EPA  Regional offices,  and state
agencies work together to identify a site  containing
wastes  suitable  for  testing the  capabilities  of  the
technology. The EPA SITE Program prepares a detailed
sampling and analysis  plan designed to thoroughly
evaluate  the technology  and  to ensure  that  the
demonstration test data are reliable.  A demonstration
may require  from a  few days  to  several  months,
depending on the type of process and the quantity of
waste needed to assess the technology.

In regard  to  the  BSWS,  where steady  state can be
achieved within an hour from startup, a minimum of
three demonstration runs, each requiring 5 to 6 hours of
steady state operation, \vere necessary to evaluate this
process. Ultimately, the Demonstration Program leads
to an analysis of the technology's overall applicability to
Superfund sites.

The  Emerging  Technologies  Program  focuses on
conceptually proven,  but untried technologies. These
technologies  are  in an  eaily stage of development
involving  laboratory  or  pilot testing.    Successful
technologies  are encouraged  to advance  to  the
Demonstration Program.

The   Measurement   and  Monitoring  Technologies
Program  identifies  existing technologies  that  can
improve field  monitoring and site characterizations. It
supports the  development and demonstration of new
technologies that provide 'faster, more cost-effective real-
time data on contamination and cleanup levels. Finally,
it formulates the protocols  and  standard operating
procedures for demonstrated methods and equipment.

As part of the SITE Program's Technology Information
Services,  an Applications   Analysis  Report  and
Technology  Evaluation Fleport are published at the
conclusion of each demonstration. Research reports on

-------
emerging  technology projects  are also produced.
Results and status updates are distributed to the user
community—EPA Regions, state agencies, remediation
contractors, and  responsible parties-through  many
media and activities.

2.2    SfTE PROGRAM REPORTS

The evaluation of technologies demonstrated in the SITE
Program Is  presented  in  two  documents:   the
Technology  Evaluation  Report   (TER)   and  the
Applications Analysis Report (AAR): The TER contains
a comprehensive  description and complete results  of
the demonstration sponsored by the SITE Program.  It
details the technology process, the waste used for the
demonstration, sampling and analysis activities during
the demonstration, the data generated, and the quality
assurance program.

The scope of the AAR Is broader than the TER.  It
encompasses discussions of Superfund applications and
estimation of technology costs. The AAR compiles and
summarizes the results of the SITE Demonstration, the
vendor's design and test data, and information gathered
from other laboratory and  field applications of the
technology. In addition to discussing the technology's
advantages, disadvantages, and limitations, it estimates
the costs of the  technology for different situations,
based  on  data  available  from pilot-  and  full-scale
applications.  The AAR discusses factors that have a
major Impact on costs and performance,  such as site
and waste characteristics.

The amount of data available for the evaluation  of an
innovative technology varies widely.   Data may be
limited to laboratory tests on synthetic waste or may
Include performance data on actual wastes treated  at
the pilot-  or full-scale level.   Regarding Superfund
applications, there are limits to conclusions that can be
drawn from a single field demonstration. A successful
field demonstration does not necessarily ensure that a
technology will be widely applicable or fully developed
to the commercial scale. The AAR attempts to integrate
whatever information is available and draw reasonable
conclusions.  The AAR Is useful when considering the
selection  of  a  Superfund  cleanup technology;  it
represents  a  critical   step   in   the  technology's
development and commercialization.

2.3    KEY CONTACTS
EPA SITE Demonstration Project Manager

Mr. Hugh Masters
U.S. EPA - ORD
Releases Control Branch (MS-104)
2890 Woodbridge Avenue
Edison, New Jersey  08837-3679
Telephone: (908)321-6678

Process Vendor

Mr. Craig Jones,  Project Manager
BESCORP
3200 Shell Street
P.O. Box 73520
Fairbanks, Alaska 99707
Telephone: (907) 456-1955
For more information on the development of BSWS for
contaminated  soil,  please  contact  the following
Individuals:

-------
                                             Section 3
                             Technology Applications Analysis
3.1    INTRODUCTION

This analysis addresses the potential applicability of the
BSWS to Superfund sites and other locations where
contamination from lead batteries is of primary interest.
The EPA tracks the development of control technologies
[1,4,5] for remediation  of lead battery recycling sites
because these sites  represent a major  source of
hazardous material.  BESCORP is currently developing
applications of their process to treat radioactive wastes
and organic contaminants. However, these activities are
outside the scope of this MR.

The  SITE Demonstration at ABE  provides a limited
database for conclusions  on the effectiveness and the
applicability of the technology to other cleanups. To
understand the potential applicability of the  BSWS, the
database needs to be expanded with information from
recent  particle-size  separation  tests,   conducted
subsequent to the SITE Demonstration.  These data
have resulted in system modifications incorporated into
the commercial-scale plant in order to improve the
BSWS performance.

The observations and conclusions,  summarized below,
are drawn from  the  SITE  study  and the  above-
mentioned supplemental information. Discussions cover
site and soil characteristics, impact of state and federal
environmental regulations,  applicable  media,   and
personnel factors.  Additional information  about the
BESCORP  process  (a process description,  vendor
claims, a summary  of the Demonstration test  results,
and case studies of treatability tests),  is provided in the
Appendices.

3.2    CONCLUSIONS

The BESCORP Demonstration was partially successful
in removing large battery casings, battery casing chips,
and discrete, metallic-lead particles from the washed
gravel  and sand  fractions.  The  process effectively
washed the gravel fraction to meet the cleanup goals
(Table 5) after process adjustments during the first run.
Although significant lead reduction was achieved in the
sand fraction,  the cleanup goals  were not attained.
However, SITE analytical data for the minus 14" plus 10
mesh sand fraction (Table 6) indicate that  the coarser
portion of the washed sand (about 40%) is substantially
below the cleanup limits.  These data suggest process
performance could be improved; however, no SITE data
were developed to veriify this conclusion.  In Appendix
B, BESCORP discusses post-Demonstration tests on the
washed sand fraction.  EJased on these tests, BESCORP
claims  that the addition of an  attrition scrubber, plus
size separation (at plus 80 mesh) in a third separation
chamber, would improve the performance of the BSWS.

The specific conclusions are as follows:

•    Lead  removal (process) efficiencies in the three
     Demonstration   test   runs,  measured  as  the
     percentage of lead removed from the gravel and
     sand  fractions of the feed, were 28, 91, and 77,
     respectively.   The  higher removal  efficiencies
     during Runs  2 and  3 are traceable  to  process
     adjustments made during the first run.  Total lead
     removal  measurements,  based  upon  the  lead
     content of all feed fractions, were 61, 93, and  85
     percents, respectively. Calculations are presented
     in Section C.2.3.

•    The process efficiency, which is represented by the
     washed gravel and sand  (minus 2V£" to plus 150
     mesh) that meets EPA cleanup goals, expressed
     as a percentage of the Feed that was greater than
     150 mesh, improved  siginificantly from 11 to 32 to
     49 percent  during  the  threeruns.   However,
     process efficiency did not approach the 75 percent

-------
                                                                  TABLES
                                         SUMMARY OF KEY PROCESS STREAM CHARACTERIZATION DATA
Stream 1A**
feed soil
average
SSI analysis
Run1*
Run 2*
Run3*
Casing
chips
wt%
dry
6.0
5.0
1.7
Total
moist
wt%
7.3
7,1
5.S
pH
6.6
6.7
7.1
Soil fraction
2.5 to 1/4" mesh
Pb
ma/ka
1,080
11,600
497
Wt%
dry
57.2
48.1
45.1
1/4" to 10 mesh
Pb
mfl/ka
3.650
8,900
824
Wt%
dry
7.8
9.5
9.7
10 to 150 mesh
Pb
ma/ka
5,670
6,840
3.340
Wt%
dry
23.9
31.3
35.7
< 150 mesh
Pb
ma/ka
17,700
16,000
8.210
Wt%
dry
11.0
11.3
9.5
Composite
Pb
mo/ka
4,210
10,400
2,280
Std.
dev."*
2,600
12,700
1,130
TCLP
Pb
mart.
72
132
50
Std.
dev.»**
42
117
21

Stream 2**
gravel
average
SS2 analysis
Run1*
Run 2*
Run 3*
Casino
chips
wt%
dry
0.4
0.0
1.2
Total
moist,
wt%
1.7
1.3
3.9
pH
7.2
7.0
6.7
2.4 to 1/4"
mesh
wt%
dry
98.3
96.9
96.3
1/4" to 150
mesh
wt%
dry
1.7
1.1
1.6
<150
mesh
wt%
dry
0.02
0.04
0.04
Composite
Pb
ma/kei
2,540
903
15
Std.
dev.***
3,230
2,070
8
TCLP
Pb
mg/L
1.0
0.8
0.2
Std.
dev.***
0.4
0.2
0.2

Stream 3**
sand
average
SS3 analysis
Run1*
Run 2*
Runs*
Casinc
chips
wl%
dry
0.0
0.0
0.0
Total
moist.
wt%
11.7
11.4
12.7
PH
6.3
6.4
6.6
Soil faction
1/4' to 10 mesh
Pb
mg/kg
191
162
69
Pb, TCLP
mg/L
4.8
5.7
1.7
Wt%
dry
44.3
43.7
38.3
< 10 mesh
Pb
mg/kg
3,110
2,820
2,400
Wt%
dry
55.7
56.3
61.7
< 1 50 mesh Composite
Wt%
dry
0.5
1.0
1,3
Pb
mg/kg
1,810
1,670
1,510
Std.
dev.***
256
526
306
TCLP
Pb
mg/L
42
40
26
Std.
dev.***
3
5
3
CEC TOO TPH
Wt%
tnea/L dry ma/kq
2,7 2.0 240
2,7 1.5 228
7.1 1.2 117

00
       * Run 1 - average of 7 data points
        Run 2 - average of 9 data points
        Run 3 - average of 8 data points
       ** See Figure 2 for stream identification.
       *** The presence of metallic lead particles caused wide variations in the standard deviation. This is discussed in Appendix C.

-------
                             TABLE 6.  LEAD DISTRIBUTION
Run
1
2
3

1
2
3
-W to +10 mesh fraction
Feed soil - SS1*
Total Pb
mg/kg
3,650
8,899
824
Standard
deviation
3,207
9,012
872
Sand fraction - SS3*
Total Pb
mg/kg
191
162
69
Standard
deviation
24
36
31
Pb TCLP
mg/L
4.8
5.7
1.7
Standard
deviation
1.0
1.0
1.1
-10 mesh to +150 mesh fraction
5,671
6,844
3,338
1,446
2,118
1,900
3,114
2,822
2,400
549
865
485






    *See Rgure 2 for sample location.
SITE objective. The failure of the sand fraction to
meet the cleanup goals contributed significantly to
the loss In process efficiency.

The three  runs produced the following  battery
casing chip removal efficiencies (measured as the
percentage of chips removed from the gravel and
sand fraction):  97,  100, and  70, respectively. As
expected, none of the Demonstration runs produced
a washed casing chip fraction  that met the EPA
cleanup goals for redeposit.

The BSWS is adaptable to soils containing battery
casings, casing chips, or metallic lead.  Much of the
lead removal  is  achieved  by  separation of the
battery casings and metallic lead from the feed soil.

The unit operated at feed rates from 2.4 to 4.2 tph
with a process  on-line reliability of 87  percent.
Scale-up risk to a 20-tph commercial unit is minimal,
even  with  the addition  of equipment  for  sand
washing  and a  clarifier sludge-vacuum  filter for
minimizing water loss.

The effectiveness of the  BSWS  as  a volume
reduction unit depends on (1) the insolubility of the
lead compounds in the washing medium, (2) the
lead separation from the gravel and sand fractions
by  density   separation  that  removes  discrete,
metallic-lead particles and by sieving that removes
the contaminated fines, and (3) the feed soil particle
size distribution. Treatability studies on representative
feed soil are required to determine the cut point of
washed gravel/sand that meets the EPA cleanup goals
and to predict the effectiveness of the BSWS on other
feedstocks.

3.3 TECHNOLOGY EVALUATION

3.3.1    Lead Battery Sites

A total of 44 CERCLA lead battery sites are located
throughout the  United States,  including 22 on  the
Superfund National Priority List (NPL).  The ABE Site is
on the NPL.  Batteries account for over 80 percent of
the lead used in the United States; about 50 percent of
it is recycled  lead from  battery-breaking operations.
There are 29 forms of commercially recyclable lead [2]
including  five  from  batteries  and  two  found  in
Superfund-type soils and cleanup materials/wastes.
Battery casings and chips are also sources of potentially
recyclable material, primarily as a  fuel supplement in
secondary  (and  possibly   primary)  lead   smelters.
However, no such commercial operations exist.

Lead  is the  primary  contaminant  found  in  soils,
sediments, and sludges at these sites.  Concentrations
ranging up to seven  percent have  been encountered.
(The highest  at ABE  was 4.5 percent.)  Metallic lead
(Pb), lead sulfate (PbSO4), lead oxide (PbO),  and lead
dioxide (PbO2)'are the predominant lead species found
at lead battery sites; these species were found at ABE

-------
by  electron  microscope  analyses in the  Remedial
Investigation  (R!) [3].

Sites with carbonate soils  generally  contain  lead
carbonate (PbCCy, hydrocerussite (Pb3(COa)2(OH)a), or
lead hiilite (Pb
-------
                RECYCLE WATER
-2 1/2 " TO +0
CONTAMINATED
SOIL
1 r >
FEEDER
-1
1
WAS
CASING
i
MAKE-UP
WATER
1
fc TROMMEL/WASH „ SEPARATION _
* UNIT * CHAfo

/4" TO +10 MESH
>
^ CASINC
* SEPAF
HED l
CHIPS -21/2" 1
WASHE
QR/
FRAC

CHIPS .1/4" JO
	 +150 MESH ,

3 CHIP DEN
^ATOR SEpAf


rn 1 1 /4" '
:p SOIL DEWATERINQ
^EL SPIRAL
'TION CLASSIFIER
1BERS A " <-"J1"
1
COAGULANT

IFIER 	 >•
FILT

i •
flV^a -150 MESH SLUDGE SOLIDS
™TOR TO DRUMS


> r

                                                            CLARIFIER
                                                         FILTER RESIDUES
            f
   METALLIC
LEAD FRACTION
   -1/4" TO +150 MESH
              C/"MI
     SAND FRACTION
Figure 1. The BESCORP Soil Washing System.

-------
    effectively clean (to EPA goals) the soil down to 150
    mesh.  However, lead analyses of the washed sand
    fraction (minus %" to plus 150 mesh) from the three
    test runs  Indicated  lead contamination above the
    EPA  limits  (Table 5),  which  was  traced  by
    BESCORP, after the Demonstration, to high lead
    levels in the minus 80 to plus 150 mesh portion of
    the washed sand (Table 3).

    The Rl sample was determined to have possessed
    different   characteristics   from   the  actual  soil
    excavated for the Demonstration.  BESCORP claims
    that  the   washed  sand  fraction  from ABE  soil
    excavated for the SITE tests, sized at minus V4" to
    plus  80 mesh, will meet  EPA cleanup goals. An
    attrition scrubber and  a third separation chamber
    have been added to the commercial 20-tph BSWS
    unit to produce this sand fraction.

*   Adaptability to handle heterogeneous feedstocks,
    as demonstrated at ABE, showed the  flexibility of
    the BSWS in handling feed soil containing any size
    or quantity of battery casings,  casing chips,  or
    discrete, metallic-lead particles (battery posts, grid
    plates,  etc.).     intermittently   throughout  the
    Demonstration, operators observed large quantities
    of these materials in the feed.

*   Particle size distribution of feed affects  process
    performance.  At ABE, the BSWS is projected to
    clean soil down to 80 mesh (cut point).  In a typical
    soil washing system, 20 to 35  percent fines are
    normally acceptable, assuming negligible attrition in
    the process.  This would set 20 to 35 percent of
    minus 80 mesh soil as the fines target content in the
    feed.  The ABE  soil was subjected to significant
    attrition; the minus 80  mesh fines  increased  from
    about  12  percent  of  the feed  material  before
    processing to about 30  percent of the feed material
    after processing.  This factor is  significant and
    should be part of future soil washing treatabiiity
    studies.

3.3.4   Mass   Balances  and  Process   Stream
       Characterization

For the three SITE runs, Table 5 presents the stream
characterization  data  and   Table   7  shows   the
corresponding mass balances for the streams illustrated
by Figure 2. Table 8  presents the mass balance for the
commercial unit.   Mass  balances for the three runs,
expressed as the percentage of total out based on total
in, were 107, 99, and 98 percents (dry solids basis),
respectively.  These high levels of accuracy were the
result of the strict EPA SITE QA/QC standards.

3.3.5   Process Performance

Lead Removal Efficiency

Table  9  summarizes  the  lead   removal   (process)
efficiencies; Table 10, the total lead removal, including
lead in fines.  Both are based on the mass balance data
in Table 7.

The  higher removal efficiencies in Runs  2  and 3 are
traceable to process adjustments, made during Run 1,
to the casing chip separator.  More detailed  discussion
on lead removal is presented  in C.2.3,

Process Efficiency

Table 11 summarizes the process efficiency for the three
test  runs,  based on the  mass balance data in Table 7
and  detailed characterization data.

Failure to meet cleanup goals  for the sand fraction con-
tributed significantly to the loss in process efficiency.
Section C.2.3. discusses process efficiency in detail.

Battery Casing Chips Removal Efficiency

Table 12 summarizes the casing chip removal efficiency
for the three test runs, based on the mass  balance data
in Table 7.  The washed casing chip fraction  (Stream 7)
did not achieve the  EPA cleanup goals in any of the
three test runs.  This was expected, based on the high
porosity of the plastic casing material.

3.3.6   Scale of Operation and Reliability

The  three SITE  test runs processed throughputs from
2.4 to  4.2 tph.   A  substantial amount of the BSWS
equipment has  run at 20 tph, including  the trommel
washer,   dewatering  spiral    classifier,    separation
chambers, vibrating screen, and conveyors. Scale-up to
the commercial 20-tph unit should entail  minimal risk.
Throughout the test runs, the BSWS demonstrated a
high degree of process reliability at 87 percent average
on-line time.
                                                   12

-------
                                             TABLET
                     MASS BALANCES FOR THE THREE SITE DEMONSTRATION RUNS
Stream
Description
Wet
total
Ibs/hr
Dry
total
Ibs/hr
Lead
-2 1/2" to
+150 mesh
Ibs/hr
Composite
Ibs/hr **
Casing chips
-2 1/2" to
+150 mesh
Ibs/hr
Composite
Ibs/hr **


1A
5


2
3
4
7
8
g






Feed soil
Make— up water
Total in

Gravel
Sand
Clarifier sludge*
Washed casing chips
Heavy metal (lead) fraction
Clarifier filter residue
Total out


Total in


4,660
1,580
6,240

2,140
1,080
3,340
382
46
12
7,000



Run1
Streams in
4,320
4,320
Streams out
2,100
954
1,150
357
44
6
4,611





9.7
—

;
—





18.2
18.2

5.3
1.7
12.1
39.0
1.7
0.02
59.8





259
-

8.4
0.0
N/A
N/A
N/A
N/A
_





259
259

8.4
0.0
~~



1A
5
2
3
4
7
8
9
Run 2
Streams in
Feed soil
Make-up water
Total in
4,950
2,540
7,490
4,590
4,590
39
-
47.7
47.7
230
-
Streams out
Gravel
Sand
Clarifier sludge*
Washed casing chips
Heavy metal (lead) fraction
Clarifier filter residue
Total out
Total outx 100 = % balance
Total in
1,810
1,210
3,930
333
60
25
7,368
98%
1,790
1,070
1,290
321
55
8
4,534
99%
-
—
—
1.6
1.8
10.9
32.8
2.1
0.02
49.2
103%
0.0
0.0
N/A
N/A
N/A
N/A
—
—
230
230

0.0
0.0
—



1A
5


2
3
4
7
8
9


Run 3
Streams in
Feed soil
Make— up water
Total in
8,260
3,410
1 1 ,670
7,830
-
7,830
11.7
—
-
17.8
-
17.8
133
-
-
133
-
133
Streams out
Gravel
Sand
Clarifier sludge*
Washed casing chips
Heavy metal (lead) fraction
Clarifier filter residue
Total out
Total out x 100 = % balance
Total in
3,540
1,960
5,510
375
162
64
11,611
3,440
1,710
1,950
364
145
24
7,633
99% I 97%
i
-
-
-
-
-
-
—
*~
0.1
2.6
11. J>
0.5
5.7
0.02
20.4
115%
41.3
0.0
N/A
N/A
N/A
N/A
—
™
41.3
0.0
-
-
-
-
—
~
* Unsettled Clarifier sludge. This sludge settled/dewatered to about 40 wt% moisture in 48 hours.
** Composite of all feed fractions.
N/A — not analyzed
                                                13

-------
MAKE-UP
 WATER
     CLARIFIER
   FILTER RESIDUE
                Figure 2.  Simplified BSWS flow diagram for SITE demonstration.

-------
                                                                  TABLE 8
                                                       MASS BALANCE FOR COMMERCIAL UNfT





Average system
balance
Solids (tph-dry)
Water-gpm

Feed soil

Dry total
Ib/rr

40,000
(20)

Water
Ib/hr

3,020



Make-up
Water

Ib/hr

2,960

6

Washed grave!/
sand
Dry total
Ib/hr

25,400
(12.7)

Water
Ib/hr

1,470


Cterifier
dewatered sludge
cake/residue
Dry total
Ib/hr

1 1 ,400
(5.7)

Water
Ib/hr

2,850



Casing chips

Dry total
Ib/tr

2,670
(1.3)

Water
Ib/hr

131



Metallic
lead fraction
Dry total
Ib/hr

545
(0.3)

Water
Ib/hr

50



Treated
waste
Water
Ib/hr

1,480

3
Ol

-------
   TABLE 9. LEAD REMOVAL (PROCESS) EFFICIENCIES

Run
1
2
3
Le
-2%" to +150
mesh
feed fraction
9.7
39.0
11.7
ad, Ib/hr
-2V2" to +150 mesh
washed gravel and sand
7.0
3.4
2.7

Process removal
efficiency
%
28
91
77
    TABLE 10.  LEAD REMOVAL (TOTAL) EFFICIENCIES
Run
1
2
3
-2M "total feed
18.2
47.7
17.8
-2^"to+150 mesh
washed gravel and sand
7.0
3.4
2.7
Total removal
efficiency*
61
93
85
*For composite feed, all fractions.
           TABLE 11. PROCESS EFFICIENCY
Run
1
2
3
Washed gravel fraction
% Meeting
cleanup goals
20
71
100
Ibs/hr
dry
2,100
1,790
3,440
Feed soil
-2y2" +150 mesh
Ibs/hr (dry)
3,870
4,040
7,070
Process
efficiency (%)
11
32
49
                         16

-------
                             TABLE 12.  CASING CHIP REMOVAL
Run
1
2
3
Casing chips, ib/hr
-21/2Bto +150 mesh
Feed fraction
259
230
133
-21/2"to +150 mesh
Washed gravel and sand
8.4
0
41.3
Removal efficiency
%
97
100
70
3.4    RANGES OF SITE CHARACTERISTICS
       SUITABLE FOR THE TECHNOLOGY

3.4.1   Site Selection

The BSWS commercial-scale unit is trailer-mounted; ft
can be moved from site to site.  The following discus-
sion  of suitable site  characteristics  applies to  this
commercial-scale unit.  Although the geological features
of a site determine what equipment may be used within
the contaminated area, the BSWS is usually assembled
within  the confines of  the  contaminated  area  or
positioned so that the contaminated soil can be easily
transported to the unit.  Ultimately, the characteristics of
the site must allow assembly of the system.

3.4.2   Topographical Characteristics

A level, graded area capable of  supporting the trailer-
mounted  equipment is  needed. The site must be clear
to allow  access to the  facility.  The  topographical
characteristics of the site should  be suitable for the
assembly  of the unit and the feed system, including
stockpiles.

3.4.3   Site Area Requirements

A minimum area of 1,000 square  feet is required for the
BSWS. Additionally, separate areas should be provided
for storage of wastes generated during treatment and
for feed preparation activities.  Since the unit can be
configured into many positions, the shape of the site is
inconsequential,  except where it limits access to the
equipment.

3.4.4   Climate and Geological Characteristics

This  treatment technology  is  limited  to operating at
temperatures above freezing. Generally, any site that is
sufficiently stable to handle the weight of the trailers is
suitable for this technology.

3.4.5  Utility Requirements

The  BSWS requires access to  electrical  power and
water.  A 3-phase electrical source capable of providing
440  volts  at 200  amps  is required to  install and to
operate the  unit.   A  minimum water flow  rate  of  10
gallons per  minute (gpm) is  also required.  Finally,
based  on the  BSWS   Demonstration,  wastewater
disposal to a POTW,  at  Ihe rate of about 10 gpm, is
required.  BESCORP claims that a commercial unit will
not require a wastewater  discharge.  (See Appendix B.)

3.4.6  Size of Operation

The  contaminated  soil  feed  rate  for   the  SITE
Demonstration was approximately 2.4 to 4.2 tph. The
projected soil feed rate for the commercial-scale  unit is
20 tph. The layout of Ihe commercial-scale system may
be adjusted somewhat to  conform to an optimum facility
design plan.  The area needed for on-site assembly of
the system will vary with  i.he configuration,  requiring at
least 1,000 square feet. The area for the feed stockpile
should be sufficient to store 700  yd3 of soil.

3.5  APPLICABLE MEDIA

The BSWS can treat soils contaminated with lead from
broken lead  batteries found at lead  battery recycling
sites. The Demonstration test  indicated that the  unit is
capable of separating battery casings, casing chips, and
lead/lead compoundsfrom gravelly/sandy soil fractions.
BESCORP projects that a commercial unit, treating ABE-
type soil,  could process material from 2V£" to about 80
mesh  (cut point)  and meet the EPA  cleanup  goals
proposed for ABE.  Treatability tests on  representative
soil samples can determine site-specific performance
                                                 17

-------
and the corresponding cut point to meet the cleanup
goals at other sites.

The  process Is not effective  in treating sludges or
sediments because they contain a high percentage of
fines. BESCORP claims to have applied their process,
either In bench-scale or pilot-scale operation, to other
contaminated   feeds  including  radioactive  wastes
(Appendices B and D).

3.6    ENVIRONMENTAL REGULATION
       REQUIREMENTS

Under the Comprehensive Environmental  Response,
Compensation,  and Liability Act of 1980 (CERCLA) and
the Superfund Amendments and Reauthorization Act of
1986  (SARA), EPA Is  responsible for determining the
methods and criteria for removal of waste and residual
contamination  from  a site.   The  utility and cost
effectiveness  of the BSWS  depends on  the extent of
decontamination necessary for site restoration and on
the treatment  appropriate  to achieve  the  required
cleanup levels for the particular site. If a waste exhibits
a characteristic hazard (e.g., lead toxicity), treatment will
be required. For the ABE site, EPA goals for redeposit
of soil were established (i.e., total lead less than  1,000
mg/kg and TCLP lead less than 5 mg/L).

Since the  use of remedial action that "... permanently
and significantly reduces the volume, toxicity, or mobility
of hazardous substances"  is strongly recommended
(Section 121 of SARA), the  BSWS would  appear to be
an  attractive   candidate  for  remediation of  sites
contaminated by lead batteries.

SARA also added a criterion for assessing cleanups that
includes consideration of potential contamination of the
ambient air.  This  supplements the general criteria
requiring that remedies be protective of human health
and the environment.  Other  than normal concerns
about  volumes of contaminated soils  handled  by
workers  and   the  dust   generated  during  those
operations, there  appears  to be  minimal  risk of
contaminant exposure for workers or neighbors. Since
the soH washing is a  wet process, air emissions are
minimal. BSWS-treated wastewater effluent (containing
less than  1 mg/L Pb) during the SITE Project was
suitable for discharge to the Fairbanks POTW.

White the  SITE  Project is exempt from formal permit
requirements  under the Resource  Conservation and
Recovery Act of 1976 (RCRA), the Hazardous and Solid
Waste Amendments  (HSWA)  of 1984  and equivalent
state  regulations may require a RCRA permit for the
entire commercial or large-scale system to operate as a
hazardous waste treatment facility.  In addition, a state-
issued air permit and a water permit may be required to
cover discharges from the system.  Local requirements
for these permits vary from state to state. Therefore, it
is important to review specific  state regulations early in
the planning stage.

3.7 PERSONNEL  ISSUES

3.7.1    Training

Since  personnel  involved  with   sampling  or other
activities close to the unit are required to wear Level D
protection, 40-hour OSHA training that covers Personal
Protective Equipment Applications, Safety and Health,
Emergency   Response   Procedures,   and   Quality
Assurance/Quality  Control  is required.   Additional
training  to  address   site  activities,  procedures,
monitoring,  and   equipment  associated   with  the
technology is recommended. Personnel should also be
briefed  when   new  operations are  planned,  work
practices change, or site conditions change.

3.7.2    Health and Safety

Personnel should be instructed on the potential hazards
associated   with   the  operation  of the  BSWS,
recommended  safety work practices, and  standard
emergency plans and procedures.  Health and safety
training should cover the potential hazards of exposure,
monitoring, provisions for response to exposure, and
the use and  care  of personal protective equipment.
When appropriate, workers should have routine medical
exams to monitor for exposure to lead.   Health and
safety monitoring and incident reports must be routinely
filed;  records  of occupational illnesses  and  injuries
(OSHA Forms 101 and 200) must be maintained. Audits
ensuring compliance with the health and safety plan
should be performed.

Proper  personal  protective  equipment  should  be
available for proper use by on-site personnel.  Different
levels of personal protection will be required,  based on
the potential hazards associated with the site and the
work activities.

Site monitoring should be  conducted  to  identify the
extent of hazards and to document  exposures at the
site.  The monitoring results should be  maintained and
posted.
                                                  18

-------
3.8    REFERENCES

1.  USEPA Engineering Bulletin. "Selection of Control
   Technologies  for  Remediation  of Lead  Battery
   Recycling Sites."  EPA/540/S-92/011. September
   1992.

2.  Lead  Recycling:    1992  Directory,  The  Lead
   Industries Association, Inc.  New York, NY. [Lead
   Media Hotline 1-800-922-LEAD]

3.  Remedial Investigation Report for ABE, Volume I.
   Prepared by Ecology and Environment, Inc. March
   1992 for EPA Region 10.

4.  Raghavan, R., D.H. Dietz, E. Coles. Excavated Soil
   Using Extraction Agents: A State-of-the-Art Review.
   Foster Wheeler Enviresponse, Inc. for EPA/RREL
   Cincinnati, OH.   EPA/600/2-89-034.  December
   1988.

5.  Gaire, R., A. Selvakumar, and T. Basu. Selection of
   Control  Technologies  for  Remediation  of Lead
   Battery  Recycling  Sites.     Foster  Wheeler
   Enviresponse, Inc. for EPA/RREL, Cincinnati, OH.
   EPA/540/2-91 /014. July 1991.

6.  Dragun, J.    The  Soil  Chemistry of Hazardous
   Materials.  Hazardous Materials Control Research
   Institute.  1988.
                                                 19

-------
                                            Section 4
                                      Economic Analysis
4.1    INTRODUCTION
The primary purpose of this economic analysis is to
estimate costs (excluding profit) for BSWS commercial-
scale remediation.  With realistic knowledge of test
costs, ft should be possible to estimate the economics
of operating similar-sized systems at other sites. The
feed rate of the BSWS for the SITE Demonstration was
2.4 to 4.2 tph. The commercial unit  is projected to
operate at 20 tph.

This economic analysis is based on assumptions and
cost figures provided by BESCORP, results of the SITE
Demonstration, and  best engineering judgement. The
conclusions are presented In such a manner that the
reader can vary the assumptions, as needed, and thus
draw other conclusions.

This analysis assumes that the commercial-scale system
Is  essentially the  same  soil  washing .equipment
evaluated in the Demonstration, with certain additions
detailed  In Appendix  B.   It also assumes that the
performance   of   the  modified  commercial-scale
equipment will improve over the SITE Demonstration
performance (Appendix C), so that the gravel and sand
fractions meet the cleanup  goals  that  allow  their
redeposit on site.

Order-of-magnitude  cost  estimates provided  in this
section  are generally  +50 to  -30 percent;  they are
representative of charges typically billed to the client by
the vendor, exclusive of profit.

4.2   CONCLUSIONS

The commercial-scale BSWS appears to be applicable
to remediation of soils contaminated with lead from lead
batteries. The treatment cost to remediate 30,000 yd3 or
56,362 tons (dry) of contaminated soil, using a 20-tph
modified commercial BSWS unit, is estimated at a total
of $9.3 million, or $165/ton, when the system is on-line
80 percent of the time. This amount includes the solid-
waste  effluent cost  for RCRA landfill  disposal  but
excludes the expenses for manifesting and shipping to
the RCRA landfill.  It also does, not cover total cleanup
cost because 4 out of the  12 categories for complete
cleanup were not included.

The modified BSWS unit adds an attrition scrubber and
third separation chamber to yield a smaller washed
gravel/sand fraction (minus 2Vz" to plus 80 mesh) that
BESCORP claims (See  Appendix B.) will meet  the
cleanup goals. [The washed sand fraction, minus !4" to
+ 150 mesh in the SITE test runs, did not meet cleanup
goals.]  On this basis, BESCORP projects  a process
efficiency of about 71 percent for the ABE-type soil.  In
addition, BESCORP projects both lead and casing chip
removal efficiencies, in the 20-tph unit, to be greater
than 90 percent, due to improved process control and
elimination of bottlenecks in the unit. Recycling markets
for  casing chips and the metallic-lead fraction would
further reduce treatment costs.  However, at this time,
recycling  markets for BESCORP casing  chips and
metallic lead have not materialized.  Therefore,  these
materials have been included in the solid-waste effluent
cost.

4.3 ISSUES AND ASSUMPTIONS

This section   summarizes  the  major  issues  and
assumptions used to develop the costs of the BSWS
[1].  In general, assumptions are based on information
provided by BESCORP.  Certain assumptions account
for variable site and waste parameters; they will need to
be  refined to reflect site-specific  conditions.   For
purposes  of this  economic analysis, a  hypothetical
commercial-scale cleanup of the ABE site was assumed.
The volume of contaminated  soil  to  be  treated  is
approximately 30,000 yd3 with 6.6 wt% moisture and a
bulk density of 149 ib/ft3.  The soil weight on a dry basis
is then 56,362 short tons.  About 46 tons were treated
in the SITE Demonstration program.
                                                 20

-------
4.3.1   Costs Excluded from Estimate
4.3.5   Capital Equipment and Fixed Costs
The cost estimates represent the charges typically billed
to the client by the vendor but do not include profit.
Many other actual or potential costs were not included
in this  estimate because  site-specific  engineering
designs, beyond the scope  of this SITE  project, are
required to determine those added costs. Certain costs
that are considered to be the responsible party's (or site
owner's) obligation, such as preliminary site preparation,
permits, regulatory requirements, initiation of monitoring
programs, waste disposal,  sampling and analyses, and
posttreatment  site cleanup  and restoration,  are not
included.  These expenses  tend to  be site-specific.
Calculations must be performed for each specific case.
Wherever possible, applicable information is provided on
these topics to facilitate site-specific calculations.

4.3.2   Utilities

To support the operation of the BSWS, a site must have
clean water available at a flow rate of at least 40 gpm.
Electric power at 440 volts is also  required for the
operation. A POTW trunk line is assumed to be located
at the site boundary for discharge of treated wastewater.

4.3.3   Operating and Maintenance  Schedules

Operating and maintenance schedules are based on the
BSWS  operations, conducted at 20 tph, 24 hours per
day, 7  days per week. Excavation is scheduled at 84
tph,  8 hours per day, 5 days per week; assembly, 12
hours per day, 7 days per  week. Excavation activities
for feed preparation  are  concurrent  with assembly,
shakedown,  and   treatment  operations.     Time
requirements for assembly, shakedown, startup, testing,
and  disassembly/decontamination  are forecast at 1
week, 3 weeks, and 1 week, respectively,  or about 35
days.

To treat 30,000 yd3 of feed soil at 20 tons/hr (dry) will
take about 118 days. To  account for both scheduled
maintenance and unscheduled shutdowns, a 20 percent
downtime is included, for an actual treatment time
forecast of 148 days.  Scheduled maintenance would be
performed by a mechanic during the day shift.  Total
time on-site is estimated to be 183 days.

4.3.4   Labor Requirements

Labor requirements for excavation, equipment assembly,
startup, treatment operations,  decontamination, and
demobilization are detailed in Section  4.4.5.
Annualized equipment and associated costs are pro-
rated for the period that the equipment is on-site.

4.3.6   System Design and Performance Factors

Figure 3 shows a process flow diagram of a 20-tph
mobile BESCORP  commercial plant. This plant requires
about 6 gpm (18 gal/Ion dry soil) of make-up water and
discharges about  3 gpm (9 gal/ton dry soil) of treated
wastewater  to a POTW  where  the  expected lead
content, based on the SITE Demonstration, is less than
1  mg/L Pb.  The  washed  gravel/sand fraction  Is
assumed to be clean  enough for redeposit on-site.  The
metallic-lead fraction, plus the casing chips and battery
casings, may be candidates for recycling to a secondary
lead smelter. However, this  issue was not part of the
SITE Program, nor has it been investigated to date.
Site-specific studies  are  required to determine the
feasibility  of  recycling  these materials.  This study
assumes that these  materials will be disposed at a
RCRA landfill. The darifier- dewatered sludge cake will
be  contaminated  and,  therefore, will  also require
disposal at a RCRA landfill.

4.3.7   System Operating Requirements

Table C-3 (Appendix C) summarizes the mass balances
for  the three BSWS SITE Demonstration runs.   An
average system mass, balance (Table 13) for the 20-tph
BSWS commercial plant is developed from projected
feed/product streams from Table C-3 with adjustments
made for system  modifications.  Table 14 summarizes
operating utilities and consumables.

4.4  BASIS OF ECONOMIC ANALYSIS

For economic analysis EEPA breaks down the overall
cost into 12 categories:
     Site preparation
     Permitting and regulatory
     Equipment (amortized over 10 years)
     Startup
     Labor
     Supplies and consumables
     Utilities
     Effluent treatment and disposal
     Residuals/waste shipping, handling, disposal
     Analytical activities
     Facility modification, repair, and replacement
     Demobilization and decontamination
                                                  21

-------
(18 QAUTON)
6 QPM
MAKE-UP WATER
* SUHQE/W
TANt
> r
CLEAN
WATER -^
TANK 	 £•
WATER
PUMP
oc
oc
3
to
til
COAGULANT <
DRUM 5
>
OJ 	 ^ COAQ
MIX CH
l^w PIIMP - - ..
*> CLARIFIER -—Ji-
gs FILTER nxn ^
o
' i N
TREATED WASTE
WATER TO POTW 1
^^ 20 TPH (DRY)
/SPS f?*0*0"-*, A s>lto-riPHRis
EXCAVATED r^~^\ - X 	 // CAS»NQ SOflEEN
SOIL /K=K====rfs T // 1
ATER J^"1";"::'";
; BATTEHY CASINGS
(UNSPECIFIED QUANTITY)
DIRTY WATER RECIRCULATION
A
T CLtAN RINSE WATbH
"\ F
J HC
V V > '
SLURRY *___nDRUM ^ 	 TROMMEL/WASH
v , , TANK * | SCREEN * UNIT *— fT 	
"\ f 1 ' '
* Oz QZ* rA ' 	 1
i^cc 1 gd- ^~- ' ^ f < i ^ PA^INO;
<« L ^*r 5S SLURRY ' „ r Y f "K CHIP
SS J- -S§n f^ PUMP ^Q V J \ VX SEPARATOR
tor g •* col FC CONVEYOR ~| \
i- yS ATTRITION _^  ' , k DEWATERINQ
WASHED SEPARATOR WASHED RilsfilPIFR
^_^_^ rnNTAMINATfin FINFS ^ '

h
SCREENED
FEED
21/2' TO +0
> f
"EED
)PPER
^ '
/ 'X
^
1
> ' ^?>
— ' "r xO. >.
JLANT < 	 * , O CONVEYOR ( l/fy*k, WASHbO
» i? n r-ri ... «... . i TOU in 	 fel V-.JL... «____»«,.. ^ -"^ O' /v o A i/e?i »tf.Ak,^
AMBER 	 	 	 ^1 "*"'"" """""
»... . -«^
MESH CASINGS * 1'3 TPH (DRY5 CASINQ CHIPS
A »
1 v 0-3 TPH (DRY) METALLIC LEAD FRACTION
CLARIFIER
\ / S.F. RECYCLE WATER
^f SLUDGE
FILTER (S,R) rt 57 TPH (DRY) ^
C.F. RESIDUE 80 MESH SLUDGE ^ f
3 6PM
(9 GAl/TON)
ARIFIER DEWATERED
UDGE CAKE/RESIDUE

Figure 3.  BSWS modified commercial-scale flow diagram.

-------
                                      TABLE 13.  BSWS AVERAGE SYSTEM MASS BALANCE
                                                   FOR COMMERCIAL UNIT


Average system
balance
Solids (tph-dry)
Water - gpm

Feed soil
Dry total
Ib/hr
40,000
(20)

Water
Ib/hr
3,019



Make-
up
water
Ib/hr
2,958

6

Washed gravel/
sand
Dry total
Ib/hr
25,364
(12.7)

Water
Ib/hr
1,470


Clarifier
dewatered sludge
cake/residue
Dry total
Ib/hr
11,383
(5.7)

Water
Ib/hr
2,846



Casing chips
Dry total
Ib/hr
2,688
(1.3)

Water
Ib/hr
131



Metallic
lead, fraction
Dry
total
Ib/hr
545
(0.3)

Water
Ib/hr
50



Treate
d
waste
Water
Ib/hr
1,478

3
W
                                           TABLE 14.  UTILITIES AND CONSUMABLES
Process operating utilities
and consumables
Make-up water
Treated wastewater
Electric power (440V)
Coagulant
Diesel fuel
Units
18 gal /ton dry feed
9 gal/ton*
4 kwh/ton
0.026 gal/ton
$0.25/ton
                            "This estimate is based on 1he BSWS Demonstration. BESCORP claims that a commercial unit will not
                            require a wastewater discharge.

-------
Some of these categories  do not affect the costs of
operating the BSWS. The 12 cost factors examined, as
they apply to the BSWS, along with the assumptions
used, are summarized in Table 15.

4.4.1    Site Preparation  Costs

The analysis assumes that  preliminary site preparation
has been performed by the responsible party  (or site
owner).  The amount  of preliminary site preparation
depends on the site.  Site preparation  includes site
design  and layout, surveys  and site logistics,  legal
searches, obtaining access  rights and/or adding roads,
preparing  support  and  decontamination  facilities,
installing  utility  connections,  and  erecting auxiliary
buildings.  These costs are site-specific; they  are not
Included in the site preparation costs.

Site  preparation   activities,  such   as  excavating
hazardous-waste feed from the contaminated site, will
be required at all sites. Therefore, they are included in
this estimate.  Estimates for site preparation are based
on rental costs for heavy equipment, labor charges, and
equipment fuel costs.   Assuming a rate of 84 tph,
excavation activities should be conducted for 8 hours
per day, 5  days per week,  over a period of 17  weeks.
Rental equipment required  to achieve the 84 tph rate
Includes an excavator at $1,260/week and a dump truck
at $700/week. This equipment consumes approximately
5 gal/hr of diesel fuel.

4.4.2    Permitting and Regulatory Costs

    Permitting and regulatory costs are generally the
obligation of  the responsible party  (or site owner).
These costs may  include  expenses for applications,
actual permit,  system monitoring requirements,  and/or
the development of monitoring and analytical protocols.
Permitting  and  regulatory  costs  can vary  greatly
because they are  site-  and  waste-specific.   No
permitting  or  regulatory costs are  included  in this
analysis.  Depending on the treatment site,  however,
such costs may be both expensive and time-consuming
factors.

4.4.3     Equipment Costs

Soil Washing

Soil washing is not an "off-the-shelf process; it must be
modified for site-specific conditions on a case-by-case
basis.   Factors such as  contaminant type and level,
cleanup criteria, soil mineralogy, and soil particle-size
distribution  must be considered when designing a
treatment system.  The  soil  is first characterized to
determine the nature and location of the contaminants.
A strategy is then developed  to effect the separations
necessary to achieve the volume reduction required to
meet regulatory  goals.   This is  accomplished by
concentrating the contaminants in a small volume of
material while producing a washed soil product that
meets appropriate cleanup criteria.  The number, size,
and type of  unit operations required to accomplish the
necessary separations will have an impact on the capital
costs.

BESCORP  estimates  the  construction  cost  of a
commercial, 20-tph mobile soil washing system to be
$770,000.   This was  independently verified,  using
outside sources, purchasing  experience,  and  good
engineering  judgement.  Table 16 summarizes this
estimate.   The equipment list and quantities were
compiled from Figure 3.
4.4.4
Startup Costs
Startup costs include assembly of the BESCORP unit,
shakedown, operator training, startup, performance
tests, and initiation of health and safety monitoring.

Assembly

The BESCORP unit will be delivered to the site on two
mobile trailers. Site-specific cost of transportation to the
site is excluded.   Estimates assume that a level and
bermed location has been prepared at the site for the
two BESCORP trailers.

Three mechanics, a boom truck operator, and a front-
end loader operator will be required for 1 week (7 days,
12 hours per day in two 6-hour shifts) to assemble the
unit and connect  utilities—water, wastewater (POTW)
lines, and power (440 volts).  A boom truck at $5,000
per week and a front-end loader at $3,000/week will be
rented.   Diesel  fuel  consumption is  estimated at 4
gal/hr.  The labor is itemized in Section 4.4.5.

Shakedown,  Operator  Training,   Startup,   and
Performance Tests

BESCORP's experience from the SITE Program showed
that 3 weeks will be sufficient time to shake down the
unit, start it up, train operations personnel, and perform
several  capacity tests to ensure that the unit  meets
performance criteria.  Labor encompasses one project
                                                  24

-------
            TABLE 15.  TREATMENT COSTS FOR THE BSWS MODIFIED COMMERCIAL UNIT*
Cost component
1. Site preparation (feed excavation only)
2. Permitting & regulatory
3. Equipment (amortized over 10 years)
4. Startup
5. Labor
6. Consumables and supplies
Health & safety gear
Flocculant/coagulant
Fuel and lubricants
7. Utilities
Process make-up water
Electric power
8. Effluent treatment & disposal
Treated wastewater
Solid wastes
9. Residuals/Waste shipping, handling,
and disposal
10. Analytical
1 1 , Facility modification, repair/
maintenance, and replacement
12. Decontamination and demobilization
TOTAL
Cost
33,300($)
—
31,200
32,000
1,131,000
50,000
74,100
19,400
1,000
18,200
1,700
7,900,000
-
—
5,700
8,000
9,305,600
Cost distribution
%
0.36
—
0.34
0.34
12.14
0.54
0.80
0.21
0.01
0.20
0.02
84.89
--
—
0.06
0.09
100.00
         *Based on treatment of 30,000 yd3 of contaminated soil by the 20-tph unit, operating with an 80% on-line factor.
manager (day shift) who also performs health and safety
functions, one lead operator, one equipment operator
(payloader), three operators per 8-hour shift, and one
mechanic for one 8-hour shift per day.

These personnel are included  in the total labor cost
component (Section  4.4.5), which  also covers living
expenses for managers and supervisors. Maintenance
staff, the boom/pay-loader operator, and operations
personnel are locally hired.  Personnel must be OSHA-
trained in hazardous-waste operations.

Health and Safety

The cost of health and safety equipment is assumed to
be  similar  to that used  at ABE during  the  SITE
Demonstration,   where  the  only  pollution  issues
concerned noise and lead-contaminated soil.
                                                  25

-------
                      TABLE 16. BSWS CAPITAL EQUIPMENT COST BREAKDOWN
Equipment
Feed hopper/conveyor
Trommel washer unit
Attrition scrubber
Separation chambers
Clarifier
Sludge filter
Pumps
Casing chip separator
Conveyor
Density separator
Dewatering spiral classifier (sand screw)
Clarifier filter
2!£M vibrating screen
Miscellaneous equipment
Quantity
1
1
1
3
1
1
4
1
5
1
1
1
1
..
Total equipment cost
Installation labor/material**
Total installed
Contingency
Installed grand total equipment cost
1993
Cost, $*
20,000
50,000
30,000
30,000
24,000
90,000
12,000
27,000
30,000
6,000
16,000
10,000
92,000
19,000
456,000
220,000
676,000
94,000
770,000
         •Costs developed from January 1993 vendor quotes.
         "Use 50% installation factor reference [2].
The project manager doubles as the health and safety
officer on day shifts and a  lead operator doubles at
night.  Personnel on-site must wear Level D protection
as noted below. The cost is presented in Section 4.4.6.
Depending on the site, however, local authorities may
Impose more stringent health  and safety regulations,
which may have significant impact on the project cost.
 Health and Safety Equipment
Tyvek suits     Safety glasses
Double gloves  Decibel meter
Safety boots
Hard hats
Ear plugs
Air RAM monitor
Eyewash station
Decontamination supplies
                                                  26

-------
4.4.5    Labor Costs
4.4.7
Utilities
    Labor costs are divided  into salaries and  living
expenses.     Salaries   include   benefits   and
administrative/overhead costs but exclude profit. Living
expenses  ($130 per day  per person)  for all on-site
personnel  (project manager,  lead  operators,  and
supervisors)  include  sharing  a rental  car.   Other
employees are locally hired.

Excavation Labor Requirements and Rates

From Section 4.4.1, the labor requirements are shown in
Table 17.

BSWS Equipment Assembly Labor and Rates

From  Section  4.4.4,  the  labor  requirements  are
summarized in Table 18.

BSWS Operations Labor and Rates (Shakedown and
Production)

Referring to Section 4.4.4, operations staff will consist of
1 lead operator, 3 operators, and 1 equipment operator
(payioader).  The BSWS will operate 24 hours per day
(three 8-hr shifts per day), 7 days per week. Four crews
will be assigned to a standard shift rotation, with each
person working 40  hours  per week and 8 scheduled
overtime hours during  each 4-week rotation. A project
manager  (who  also   performs health  and  safety
functions) and a maintenance mechanic are scheduled
for 5 days per week on the day shift.  The BESCORP
operations labor requirements and rates are detailed in
Table 19.  These requirements are the same for both
shakedown and full production operations.  Note that
each operator works an average of 42 hours per week
(one overtime shift every 4 weeks).

4.4.6    Supplies and Consumables

•   Health  and  safety   equipment  (Level  D),  a
    consumable item, costs about $40,000 for the 183-
    day project.

•   Fuel and lubricants should total about $19,400.

•   Coagulant consumption is about 0.026 gal/ton (dry
    feed).
•  Make-up water costs about $0.02/ton of dry feed
   based on 18 gal/ton at $1.00/1,000 gai.

•  Electric power costs $0.32/ton based on 4 kwh/ton
   at $0.08 kwh.
4.4.8
Effluent Treatment and Disposal Costs
The treated wastewater, containing less than 1 mg/L
total lead, should be suitable for discharge to a POTW.
The responsible party or site owner must obtain a
discharge permit from the local municipality.  Typical
cost (Fairbanks) is $3.35/1,000 gal.  Cost per ton (dry
feed) is then $0.03 at 9 gal/ton consumption—assuming
a POTW trunk line is available at the site.

Contaminated solid effluent wastes including casing
chips,   metallic-lead   fractions,   and   clarifier
residue/dewatered sludge cake will be sent for disposal
to a RCRA-permitted facility.  In Table 13, these wastes
total about 0.44 wet Ions/ton of dry feed. This estimate
includes the  landfill cost of $138.60/ton of dry feed,
based on a tipping fee al a RCRA landfill of $315/ton of
lead-contaminated waste.

However, shipping, handling, manifesting,  and waste
profile analyses are assumed to be the obligation of the
responsible party and, therefore, are not included in this
estimate.

4.4.9       Residuals and Waste Shipping, Handling,
           and Disposal Costs

Disposal costs for contaminated health and safety gear,
protective plastic sheeting,  and other residuals  are
assumed to be  the obligation of the responsible party
(or site owner).  They are not included in this estimate.

4.4.10     Analytical Costs

Analytical costs are  not  included  in this estimate.
Standard operating procedures for the BSWS do not
require  sampling and analytical activities.  The client
may elect, or  may be required by local regulatory
agencies, to initiate and fund a sampling and analytical
program.  If specific sampling and monitoring criteria
are imposed by local regulatory agencies, the analytical
                                                  27

-------
                    TABLE 17.  EXCAVATION LABOR REQUIREMENTS
Position
Excavator operator
Dump truck operator
Number
1
1
Hours
per week
40
40
Rate
$/hour
30
30
                  TABLE 18.  BSWS ASSEMBLY LABOR REQUIREMENTS
Position
Boom & front-end loader operators
SupervIsor/H&S officers
Mechanics
Number
2
2
6
Hours
per week
42
42
42
Rate
$/hour
30
50
30
                 Note: Each person works 6 hrs/day for 7 days.
                    TABLE 19.  OPERATIONS LABOR REQUIREMENTS
Position
Project Manager/H&S officer
Process Lead Operators
Process Operators
Equipment Operators
Mechanic
Number
1
4
12
4
1
Hours
per week
40
42
42
42
40
Rate
($/hour)
60
50
40
30
30
requirements could significantly increase the cost of the
project.

4.4.11   Facility   Modification,   Repair,  and
        Replacement Costs

Maintenance labor and material costs vary with'the
nature  of  the  waste and the  performance  of the
equipment.  For estimating purposes, total annual costs
of maintenance (labor and materials) are assumed to be
10 percent of  annualized equipment costs.  Main-
tenance labor typically accounts for two-thirds the total
maintenance costs, as previously discussed in Section
4.4.5.  Maintenance material costs are estimated at one-
third the total maintenance cost and are prorated to the
entire treatment period.  Costs for design adjustments,
facility modifications, and equipment replacements are
included in the maintenance costs.

4.4.12     Site Demobilization and Decontamination
          Costs

Based on the SITE Program experience, decontamina-
tion of mobile equipment and demobilization requires
                                              28

-------
seven days.  A boom truck at $5,000/week and a front-
end loader at $3,000/week will be rented for one week.
Fuel consumption is estimated at four gal/hr.  These
costs are limited to equipment decontamination and
demobilization; transportation is excluded.

Site cleanup and restoration are limited to equipment
removal from the site.  Requirements regarding  the
filling, grading, or recompaction of the soil will vary
depending  on the future use of  the site;  they  are
assumed to be the obligation of the responsible party
(or site owner).

4.5     RESULTS OF ECONOMIC ANALYSIS

Table 15 presents the total BSWS treatment cost, at 80
percent on-line, to be $9.3 million, itemized by cost
category. It should be noted that the dollar total does
not add up to the total cleanup cost because some cost
categories (i.e., complete site preparation, permitting,
sampling, analyses, and  residuals/waste shipping and
disposal) were not included. The disposal cost for the
solid waste effluent streams (clarifler residue/dewatered
sludge,  casing  chips   and  metallic  lead  fraction)
represents about 85 percent of the treatment costs. The
next largest cost components are labor (12 percent) and
consumables and supplies (1.5 percent).

Based on 56,362 tons (dry basis) of contaminated  soil
treated, the total unit cost is $165 per ton.  BESCORP
believes it is feasible to develop recycling markets for
casing chips and the metallic-lead fraction, which would
further reduce treatment  costs. However, at this time,
the recycling markets have not materialized.
4.6
REFERENCES
1. Evans, G.E.   "Estimating Innovative Technology
   Costs for the SITE Program." EPA/RRELforJourna/
   of Air Waste Management Association. July 1990.
   Volume 40, No. 7.

2. Peters, M.S. and K.D. Timmerhaus.  Plant Design
   and Economics for Chemical Engineers.  Third
   Edition. McGraw-Hill, Inc., New York.  1980.
                                                 29

-------
                                            Appendix A
                                      Process  Description
A.1    INTRODUCTION
A.2 PROCESS DESCRIPTION
Genera!

Previous treatability tests  indicate  that the BSWS, a
continuous flow process, can remove metals such as
lead,  lead compounds, and certain radioactive waste
from  coarse/sandy  soil  through  a combination  of
trommel agitation,  high-pressure   washing,  density
separation, and particle-size segregation. Typically, the
heavy metals concentrate in the fines fraction (less than
1SO mesh),  a  small portion of  the original soil, thus
reducing the volume of material requiring disposal or
further treatment.   The BSWS  effectively  separates
washed coarse/sandy soil  particles from  the fines.
Contaminant solubility in the process water can be a
significant factor both in contaminant distribution and
wastewater treatment.  The arrangement and operation
of the  process will  depend on site contaminant(s)
characteristics.

ABE Site

The contamination at the ABE Site was primarily metallic
lead and lead compounds from broken batteries found
In a gravelly/sandy soil. The soil was a heterogeneous
feedstock that contained large pieces of battery casings,
various size pieces of metallic-lead battery posts, battery
casing chips, together with fine particles of lead and
lead compounds.

For the SITE Demonstration, the soil was prescreened
from material that would not pass a 21/6" x 2V£" square
grating,  eliminating some rocks and the large battery
casings.  Previous tests by BESCORP indicated water
(no additives) was sufficient as the washing medium.  A
mobile 20-tph   unit was used to  perform  this  SITE
Demonstration, though flow rates for the test runs were
significantly below 20 tph, at 2.4 to 4.2 tph, due to flow
limitations (bottleneck) in the casing chip separator.
Figure A-1  presents an isometric flow diagram of the
BSWS SITE  Demonstration.   A more detailed flow
diagram  with sampling  points  and  mass  balance
streams is  presented  in Appendix  C,  Figure C-2.   A
modified commercial-scale flow diagram is presented in
Section 4.

Contaminated soil, screened from battery casings and
consisting of particles less than 2V6" in diameter, falls
from a hopper to a conveyor that feeds the revolving
trommel wash unit.  The washer  breaks the soil apart
through deagglomeratlon and attrition washing.

Soil ranging from minus 214" to plus 14" diameter (gravel
fraction) passes  from  a drum screen  to a conveyor,
which ends at a casing chip separator that removes
battery casing chips from the gravel.  This unit also
takes out any heavy metallic-lead particles, which then
fall into a drum for recycling. The washed gravel  is
stockpiled.

Material smaller  than  1/4"  passes through the  drum
screen into a slurry  tank from  which the slurry  is
pumped into the first counter-flow separation chamber.
The small casing chips (less than 1/4"),  separated from
the soil by a 10-mesh screen, travel to the chip pile.
The fine slurry flows through the  10-mesh screen and
passes to the second counter-flow separator for further
particle size separation.

The minus  %" to plus  150  mesh soil  particles (sand
fraction) recovered from the two separators pass over a
density  separator.  This  device  removes discrete,
metallic-lead particles,  which are stored in drums with
the larger  particles of metallic  lead  from the chip
separator. The remaining soil enters a dewatering spiral
classifier where the washed sand exits on a conveyor to
a washed sand stockpile.
                                                  30

-------
No.      Description                   No. Description

1        Excavated soil
2        Debris screen -2V4"
3        Battery casings and debris
4        Screened feed pile (-ZW to +0)
5        Feed hopper
6        Feed conveyor
7        Trommel wash unit
8        Drum screen
9        Slurry tank
10       Slurry pump
11       Separation chamber No. 1
                                       No.  Description
12   Screen -10 mesh
13   Density separator
14   Heavy metal fraction (Pb) drum
15   Dewatering spiral classifier
16   Product conveyor
17   Washed sand pile (-W to + ISO mesh)
18   Separation chamber No. 2
19   Product conveyor
20   Casing chip separator
21
                                   22
                                   23
                                   24
                                   25
                                   26
                                   27
                                   28
                                   29
                                   30
Washed casing chips (-2W to 10 mesh) 31
Washed gravel stockpile (-2W to + W1)
Coagulation mix chamber
Clarlfler
Liquid discharge to POTW
Sludge drum
Coagulation drum and pump system
Make-up water
Filter and surge/water storage tank
Clean water tank
Water circulation pump
                      Figure A-1. BESCORP Soil Washing System (isometric drawing).
                                                       31

-------
The finest particles, small enough to pass through a
150-mesh screen,  mix with a  coagulant and  enter a
clarifier.  There they form a dense sludge, which is
discharged to waste storage drums for proper disposal
at an EPA-approved landfill. The liquid recycles in the
system from the clarifier through a filter and surge/water
storage tank. Clean make-up water enters through the
surge/water storage tank.
                                                  32

-------
                                          Appendix B
             Vendor's Claims for the  BESCORP Soil Washing System
B.1    INTRODUCTION

The  concept   of  reducing  the  volume  of  soil
contaminated with chemicals is based on the tendency
of many organic and inorganic contaminants to bind
chemically or physically to clay and silt particles.  These
particles may attach to larger soil particles (sand and
gravel) through chemical  precipitation  that  coats
particles,  or through physical  processes such  as
adsorption, absorption,  or compaction  of soil mass
(agglomeration),

B.2    TECHNOLOGY DESCRIPTION

The BESCORP Soil Washing System (BSWS) is a water-
based process for mechanically scrubbing excavated
soils. The process uses a variety of treatment methods,
depending on the contaminant type(s), as follows:

•   Particle size separation:
    -  Concentration of contaminants with the fine soil
   fraction
•  Gravity separation:
         Liberation  and removal of  dense or light
    paniculate contaminants
•  Attrition scrubbing:
   - Liberation of chemical coatings (such as PbSO4)
   from soil particles
•   Contaminant dissolution in the wash solution:
    -  Partitioning contaminants to the wash solution,
   and removing them  in the wastewater treatment
    system

Figure B-1 depicts a simplified block flow diagram of the
BSWS, which can vary based on the characteristics of
both the soil and the contaminants).  In addition, the
approach can vary depending on whether a physical
volume-reduction process (resulting in a smaller volume
of more contaminated material)  is requested, or if total
remediation of the site material is specified.

B.3 CLAIMS

BESCORP can  separate soils and  contaminants  by
virtue of the size and density character of each, based
on  physical  principles  and  treatability  tests  that
BESCORP has performed.

1.   The BSWS can segregate fine material from the
     coarse material, alter the "size" cut within minutes,
     and produce a coarse fraction that  is free from
     undersize.  This is a very important capability
     because the fines very often are the contaminants,
     or are very contaminated.  The ability to produce
     the  oversize iree from fines  is   not  easily
     achievable with other sizing devices such  as
     hydrocyclones or sand screws.

2.   The BSWS can recover material from the soils
     based on the density of the contaminant as well
     as the particle size so it can recover the dense
     metals as well as light material that might  be
     contaminated (such as  the battery casings that
     are permeated with lead).

3.   The  BSWS can  remove contaminated  surface
     coatings from soil, sand, and gravel particles, thus
     moving the contamination from the oversize to the
     fine fraction.

The above  processes are able to provide a washed
sand and gravel fraction (2V& in x 150 mesh) that is
suitable for placement back on-site in many instances.
In other cases,  ft will be necessary to provide  post-
treatment to complete remediation. The BSWS process
provides a more amenable material for post-treatment.
Soil fractions can be processed through a series of
steps optimized for each individual feed requirement.
                                                 33

-------
         Contaminated
           Soil Feed
         Initial Screening
 +2 1/2" Oversize Material
Battery Casings and Debris
     Solids Deagglomeration/
         Wash Process
                                              Casing Chips
       Coarse Particle Size
    Separation/High-Pressure
             Rinse
                             -2 1/2" to +1/4"
                                Material
                  1
            Gravity Separator
        Fine Particle Size
           Separation
                           -1/4" to +150
                            Mesh Soil
        Gravity Separator
                                           Discrete Metallic Lead

                               •150 Mesh Contaminated
                           Fines to Disposal or Post Treatment
Water Recycle
                Figure B-1.  BESCORP block flow diagram.
    -2 1/2' to +1/4"
   Washed Gravel
       Fraction
-> Metallic-Lead
      Fraction

->  -1/4" to+150
    Mesh Washed
        Sand
                                     34

-------
B.4   DESCRIPTION OF  DEMONSTRATION
       CONDITIONS

Soil washing is a flexible  processing  approach for
contaminated soil volume reduction. This flexibility can
only be utilized when the material has been properly
evaluated through effective sample collection and site
assessment.  The proper configuration of the plant is
dependent on the lab evaluation of the material at the
site, as represented by the remedial  investigation and
treatability  samples  provided  to the  soil washing
contractor.  This must be determined before the  plant
can be built or modified for that particular application.
If the sampling program that generates the samples
and/or data that are used to design the plant Is in error,
then the plant performance will be compromised.

The   BESCORP  participation   in   the EPA   SITE
Demonstration  Program provided an opportunity  to
operate the BSWS with very concentrated oversight on
the application of the plant to a contaminated material
that was perfect for a size-separation-only process. This
was the concept until the site was excavated  for the
material to be processed.

The excavated material was observed to be dramatically
different from the  ABE Treatability Study samples
(Appendix D Case  D.10).  There were nearly whole
battery casings  and every size  smaller; there  were
metallic lead pieces as large as 5-pound battery buses.
BESCORP immediately realized that the plant would not
be able to provide a passing product.  As  mentioned
elsewhere, the  plant was modified to remove dense
metallic lead in every imaginable size and configuration,
and to remove  every size casing particle from half
casings down,  in  both ebonite and polyethylene.
BESCORP  made best  estimate projections from the
evaluation of this material as to the split required at 150
mesh to provide a  clean sand fraction.  After the
shakedown period, BESCORP felt that they were within
the design envelope for this material to process through
the BSWS plant and meet the  redeposit goals; however,
subsequent SITE test data revealed that the sand cut
should have been set at 80 mesh.

After the first run through the plant, no  further alterations
were allowed under the SITE Program oversight, as the
three  runs needed to be consistent  to measure  plant
performance.   The  weather allowed only marginal
operating   temperatures  for  the   plant;   freezing
temperatures prevented  processing of all the material
stockpiled on-site. BESCORP was able to complete the
test runs and began decontamination of the plant with
6 inches of snow on the ground and many components
frozen. No attempt to rerun the tests was possible at
that point.

B.5  BSWS MODIFIED COMMERCIAL UNIT
     FOR ABE-TYPE LEAD REMOVAL

As discussed in Appendix C, the SITE analytical data in
Tables C-1 and C-3 indicate that the BSWS is effective
in removing lead from the minus %" to plus 10 mesh
fraction of the feed soil to produce a corresponding
fraction of washed sand that meets the cleanup goals.
The minus 10 mesh to plus 150 mesh sand fraction will
not meet the established EPA goals due to the presence
of excessive contaminated fines. Therefore, the washed
sand fraction (that  will  meet EPA  goals)  must be cut
somewhere between 10 and 150  mesh to maximize the
quantity of material that meets these goals.

Based  on  recent  bench-scale  tests  in Table  B-1,
BESCORP  claims  that the addition of an attrition
scrubber  plus size  separation  (at  plus 80 mesh) in a
third separation chamber  will  produce a  minus 1/4" to
plus 80 mesh sand fraction that will meet these goals
(these equipment items are discussed below).  From
these data, BESCORP  projects the following process
efficiencies for the three Demonstration runs:  76, 67,
and 69 percent, respectively.  This has not yet been
demonstrated by the BSWS unit.

To upgrade the BESCORP unit to a full commercial size,
and to achieve the performance objectives, the following
equipment items are included in Figure 3:

•    Performance  Objective:   Remove large battery
     casings from  soil.

     A 2W vibrating screen unit is included.  This item
     was used at ABE but was not within the scope of
     the BSWS SITE Demonstration unit.

»    Performance Objective: Clean sand to meet EPA
     cleanup goals.

     Downstream  of the  density separator, add an
     attrition scrubber that contains slurry agitation
     cells in series, each with a large variable speed
     agitator.

     Downstream of the attrition scrubber, add a third
     separation chamber that  produces a minus 1/4" to
     plus 80 mesh sand fraction.
                                                 35

-------
                    TABLE B-1.  BESCORP ATTRITION WASHING AND SCREENING
                                     Vendor Bench-Scale Data*
Run
1
1
Average
2
2
Average
3
Average
Bench
test
1-5
1-C

2-7
2-C

3-1

-1/4" to +80 mesh sand fraction
Dry wt.% of
total sand fraction
83.3
88.4
85.9
. 91.8
87.9
89.9
84.2
84.2
Total Pb
mg/kg
98
270
184
390
185
288
225
225
Pb, TCLP
mg/L
1.2
3.9
2.6
4.1
4.6
4.4
2.5
2.5
       *Da!a not validated under SITE Program.
»  Performance  Objective:   Reduce water loss  in
   clariffer sludge.

   Add a rotary vacuum sludge filter to reduce the
   water loss. Filter vendor claims ABE sludge could
   achieve 80 to 85 percent dry solids content.
                                                36

-------
                                           Appendix C
                                SITE Demonstration Results
C.1   INTRODUCTION

The goal of this SITE Demonstration was to determine
the effectiveness of the BSWS in  remediating lead-
contaminated soil at a lead battery site.  ABE was
selected  as  a representative site on the basis of a
Remedial Investigation (Rl) and the site's inclusion on
the NPL (Figure C-1) in 1989,   SITE Demonstrations
emphasize  meeting  the EPA cleanup  levels (and/or
ARARs) for the hazardous contaminants) present.

The established EPA cleanup levels for redeposit of the
ABE Site soil were less than 1,000 mg/kg total lead and
less than 5 mg/L TCLP lead. Soil excavations at three
different locations resulted in three marginally different
feed soil analyses.

The primary objectives of the BSWS SITE Demonstra-
tion consisted of the following:

•   Assess the ability of the process to comply with
    EPA's lead cleanup goals for redeposit  of washed
    soil at the site;

•   Determine if the BSWS can achieve greater than 75
    percent  process  efficiency by washing sufficient
    percentages of contaminated gravel and sand to the
    levels suitable for redeposit;

•   Develop economic data for the BSWS.

Secondary objectives were as follows:

•   Determine if the washed battery casing chips meet
    the cleanup goals;

•   Evaluate the BSWS  reliability;

•   Document the operating conditions of the BSWS for
    application to other hazardous waste sites.
The  Rl  analytical  data  plus Initial  treatability tests
(Appendix D) performed by BESCORP in 1991 on ABE
soil samples (used for 1 he Rl analyses) indicated that the
site was ideal for the BSWS because lead contamination
consisted primarily of fine particles (minus 150 mesh) in
a gravelly/sandy soil. However, feed soil excavated for
the Demonstration  differed significantly from the  Rl
samples due to sizable quantities of whole  battery
casings, casing chips, and  metallic lead  discovered in
the soil, plus contamination of a portion of the sand
fraction above 150  mesh,   BESCORP modified their
system to  remove these  materials by adding a casing
chip separator and  a density separator. Whole battery
casings were eliminated with a 2!£" screen prior to the
Demonstration runs.

A portable BSWS unit with a design capacity of 20  tph
was  used  to evaluate the process effectiveness.  The
original BSWS, built to process 20 tph of soil when
removing silt and clay From  uncontaminated sandy soil,
was  a water-based, volume-reduction unit that used
agitation, attrition scrubbing, high pressure washing, and
particle size separation.  This system was  modified to
remove lead, lead compounds, and battery casing chips
through the addition of a density separator and a casing
chip separator. The modified system capacity is about
5 tph, primarily due to restricted flow in the casing chip
separator.

The BSWS was demonstrated at the ABE Site in August
1992. About 46 tons of soil contaminated with broken
lead batteries were treated during the program.  The
Demonstration included a series of shakedown tests and
three test runs.  Prior to initial system startup, the EPA
and  the SITE contractor  (FWEI)  reviewed the final
Demonstration Test Plan (including the approved Quality
Assurance Project Plan) with BESCORP personnel  [1].
Pilot plant shakedown and blank runs started the first
week in August and continued for three weeks.  During
this time, a field audit was  made by S-Cubed,  Inc. for
the EPA.
                                                 37

-------
                               X
X
X
                                                                                               -X
CO
CO
                                              30TH   AVENUE
                           DOWNED POWER POLES
                           ELECTRICAL
                           SUB-STATION
                   LEGEND
                   —x	     EXISTING FENCE LINE
                                BESCORP UNIT
                                                                             FWEl

                                                                            OFFICE
               ALASKAN

               BATTERY
              ENTERPRISES

               CONCRETE PORCH

                 i
                                           OLD  RICHARDSON  HIGHWAY
                                                                                                 SCALE.r-SQ'-e-
                                       FOSTER WHEELER ENVIRESPONSE, INC,


                                       ALASKAN BATTERY ENTERPRISES

                                           EPA SITE PROGRAM

                                           FAIRBANKS, ALASKA	

                                              SITE MAP
                                                                                         RiV. B 7/0/S2 a AuW
                                                                                         RiV. I  3/23/M  J. DaHno
                                                                                                            tag, A?y-BAT
                                                        Figure C-1. ABE site map.

-------
The three SITE test runs were conducted during the last
two weeks in August.

C.2   SOIL WASHER PERFORMANCE

C.2.1  Overview

Figure C-2 presents a detailed  flow diagram  of the
BSWS SITE  Demonstration Unit with identification and
location of sample points and  mass balance streams.
Process   stream  characterization  and  associated
statistical  data are presented in Tables  C-1  and C-2.
The detailed mass balances for the three test runs are
shown in Table C-3. Appendix A contains a description
of the process. Figure C-3 presents the plant layout.

Total Lead

Figures C-4,  C-5,  and  C-6  plot  the  total  lead
concentration  in the feed soil  (SS1), washed gravel
(SS2),  and sand fractions (SS3) as a function of total
lapsed time for the three Demonstration runs.  In Run 1,
three gravel samples contained discrete  pieces  of
metallic lead due to improper operation  of the casing
chip separator. Minor equipment adjustments, made to
this  separator  after  Run  1,  improved  metallic  lead
removal. By Run 3, no metallic lead was  present in the
washed gravel.    With  the improved  metallic  lead
removal, the washed gravel easily met the EPA goals for
both total  lead and TCLP (Figures C-6 and C-7).

Effect of Metallic Lead on Heterogeneity

The presence of metallic lead particles was the largest
contributing  factor in producing heterogeneous lead
removal data.  Table C-2 summarizes the total lead and
TCLP measurements for both  the untreated feed soil
and the treated gravel and sand fractions. Samples that
contained visible metallic lead particles had much higher
lead content and much greater variability (heterogeneity)
than the samples where  no visible  metallic  lead was
detected.  This effect  was most obvious in the gravel
fraction, where both the average total lead content and
the standard deviation are two  orders  of magnitude
greater for samples with visible metallic  lead.   The
bimodal population containing visible metallic lead and
no  visible metallic lead indicates the importance  of
efficiently  removing the metallic  lead from the gravel
fraction. The sand fraction contained no visible metallic
lead.
Total Lead and TCLP Profiles

The total lead and TCLP concentration profiles of the
washed sand fractions did not meet EPA goals in any of
the three runs (Figures C-4, C-5, C-6, and C-7) because
the sand  fraction  was  improperly sized due to  the
presence  of excessively contaminated fines.   This
conclusion is substantiated by the data presented in
Tables C-1  and  C-4  (Lead  Partitioning).  Table  C-1
indicates  that the washed composite sand  fraction
(SS3), consisting of minus 1/4" to plus 150 mesh material,
failed both TCLP lead (42, 40, and 26 mg/L) and total
lead (1,808, 1,670, and  1,509  mg/kg) cleanup goals.
However,  if the washed  material  is split into a coarse
(minus W to plus 10 mesh) and a fine (minus 10 to plus
150 mesh) fraction, the coarse sand fraction meets the
EPA  goals,   with  Ihe  exception  of  one   TCLP
measurement that slightly exceeded the TCLP goal. The
sand fines fraction (minus 10 mesh to plus 150 mesh)
failed to meet the  EPA goals.  Appendix B discussed
modifications to the BSWS unit in washing the sand to
improve operation for  a commercial unit.

C.2.2   Process Monitoring and Control

Mass Balances

Washed gravel (Stream 2, Figure C-2) and sand (Stream
3) were weighed  on a truck scale  at about 10-minute fill
times (45- to 60-minute  intervals) to develop flow rate
data.  The feed soil (Stream 1) was also weighed by
truck scale and dumped into the feed hopper by a front-
end loader on a fairly  consistent,  although intermittent,
batch basis—as presented in Figures C-8, C-9, and C-10.
These figures show the total lapsed  time for each run
including shutdowns.

The feed flow rate  to the trommel washer (Stream 1A)
was controlled by the  combination of variable speed of
the conveyor and  adjustable discharge port opening.
Feed  rate was calibrated before each  test run.  The
mass balance flow rates in Table C-3 represent  the
average rates calculated  over the actual operating time
of the unit   (excluding  downtime).    Clarifier sludge
(Stream 4) was collected in drums, at a fairly uniform
rate.   When  filled, 1hese  drums were  immediately
sampled with a Coliwasa tube to obtain a representative
sample (SS4). The drums were weighed and analyzed
at the end of a run. The total sludge weight was then
divided by the operating hours  to develop the average
                                                  39

-------
MAKE-UP
 WATER
                                                                                                         SCREENED
                                                                                                           FEED
                                                                                                         STOCKPILE
                                                                                                        -21/2' TO +0


                                                                                                        CONTAMINATED
                                                                                                          FEED SOIL
                                                                                                       VARIABLE
                                                                                                        FLOW
                                                                                                      CONVEYOR
                                                                                                            -2V2" TO +1/4"
                                                                                                            WASHED SOIL
                                                                                                           GRAVEL FRACTION
                                                                                                              STOCKPILE
  CLARIFIER
FILTER RESIDUE
                                                     SLUDGE DRUMS
                                                     FOR DISPOSAL
                                                                           WASHED
                                                                           CASING
                                                                            CHIPS
                                                                          •2V2' TO +0
                                                                            DRUM
                                                                                               1/4" TO +150 MESH
                                                                                                WASHED SOIL
                                                                                                SAND FRACTION
                                                                                                 STOCKPILE
                                                                                        LEGEND
                                                                                             SAMPLE POINT

                                                                                             MATERIAL BALANCE STREAM
               Figure C-2.  Detailed  BSWS flow diagram for SITE  demonstration.

-------
                                                TABLE C-1
                                 KEY PROCESS STREAM CHARACTERIZATION DATA
Stream 1A
feed soil
average
SS1 analysis
Run1*
Run a*
Runs*
Casing
chips
wt%
drv
6.0
5.0
1.7
Total
moist
wt%
7.3
7.1
5.3
pH
6.6
6.7
7.1
Soil fraction - modified lead digestion without grinding
2.5 to 1/4 'mesh
Pb
ma/kq
1,080
11,600
497
Wt%
drv
57.2
48.1
45.1
1/4" to 10 mesh
Pb
mq/kq
3,650
8,900
824
Wt%
drv
7.8
9.5
9,7
10 to 150 mesh
Pb
ma/ka
5,670
6,840
3,340
Wt%
drv
239
31 3
357
< 150 mesh
Pb
mq/ka
17,700
16,000
8,210
Wt%
drv
11.0
11.3
9.5
Composite
Pb
ma/kq
4,210
10,400
2,280
Pb
TCLP
mq/L
72
132
50
Stream 2
gravel
average
SS2 analysis
Run1*
Run 2*
Run 3*
Casing
chips
wt%
drv
0.4
0.0
1.2
Total
moist.
wt%
1.7
1.3
3.9
pH
7.2
7.0
6.7
2.4 to 1/4"
mesh
wt%
drv
98.3
96.9
96.3
1/4"to150
mesh
wt%
drv
1.7
1.1
1.6
<150
mesh
wt%
drv
0.02
0.04
0.04
Composite
Pb
ma/ka
2,540
903
15
Pb
TCLP
mg/L
1.0
0.8
0.2
Streams
sand
average
SS3 analysis
Run1* '
Run 2*
Runs*
Casing
chips
wt%
dry
0.0
0.0
0.0
Total
moist
wt%
11.7
11.4
12.7
pH
6.3
6.4
6.6
Soil fraction - modified lead digestion without grinding
1/4 to 10 mesh
Pb
mg/kg
191
162
69
Pb. TCLP
mg/L
4.8
5.7
1.7
Wt%
dry
44.3
43.7
38.3
<10mesh
Pb
mg/kg
3,110
2,820
2,400
Wt%
dry
55.7
56.3
61.7
< 150 mesh
Wt%
dry
0.5
1.0
1.3

Composite
Pb
mg/kg
1,810
1,670
1.510
Pb
TCLP
mg/L
42
40
26
* Run 1 — average of 7 data points
 Run 2 — average of 9 data points
 Run 3 — average of 8 data points
                                                 41

-------
               TABLE C-2.  STATISTICAL SUMMARY OF LEAD IN FEED SOIL,
                           GRAVEL, AND SAND FRACTIONS
Run
Food Soil
1

2

3

Gravel Fraction
1

2

3

Sand fraction*
1
2
3
Metallic
lead

No
Yes
Total
No
Yes
Total
No
Yes
Total

No
Yes
Total.
No
Yes
Total
No
Yes
Total

Total
Total
Total
Data
points

5
2
7
4
5
g
7
1
8

3
3
6
7
2
9
8
0
8

7
9
8
Total lead
mg/kg
Avg.

2,649
8,318
4,211
4,516
14,322
10,374
2,116
3,223
2,276

33
4,423
2,541
26
3,972
903
15
NA
15

1,808
1,670
1,509
Range

2,293-3,362
7,765-8,870
2,293-8,870
3,686-6,590
2,911-45,450
2,911-45,450
951-4,709
3,223
951-4,709

32-35
1,078-9,631
32-9,631
17-35
1,302-6,641
17-6,641
5-32
NA
5-32

1,449-2,172
963-2,477
833-1,903
Standard
deviation

400
553
2,600
1,201
14,322
12,686
1,145
NA
1,132

1.4
3,167
3,283
6.2
2,670
2,067
8.2
NA
8.2

256
526
308
Pb TCLP
mg/L
Avg.

75
63.5
72
156
113
132
46
72
50

0.6
1.3
1.0
0.8
0.9
0.8
0.2
NA
0.2

42
40
26
Range

42-170
45^2
42-170
50-440
48-190
48-440
26-90
72
26-90

0.4-0.7
1.2-1.6
0.4-1.6
0.5-1.1
0.8-1,0
0.5-1.1
0.1-0,6
NA
0.1-0.6

37-48
30-47
21-29
Standard
deviation

47.8
18.5
42.0
164
48.2
117
20.3
NA
20.8

0.14
0.19
0.40
0.20
0.10
0.20
0.15
NA
0.15

3.4
5.0
3.0
*No metallic lead found in sand fraction.

-------
                                                    TABLE C-3

                      DETAILED MASS BALANCES FOR THE THREE SITE DEMONSTRATION RUNS
Stream
Description
Wet
total
Ibs/hr
Dry
total
Ibs/hr
Water
Ibs/hr
Lead
mfl/kfl
TCLP
ma/L
Ibs/hr
Casing chips
Wt%
dry
Ibs/hr

1A
5
2
3
4
7
8
9
Run 1
Streams in
Feed soil
Make— up water
Total in
4,660
1,580
6,240
4,320
4,320
340
1,580
1,620^
Streams ou
Gravel
Sand
Clarrfiof sludge*
Washed casing chips**
Heavy metal (lead) fraction***
ClarMer filter residue
Total out
TolaTout x 1 00 = •* Balance
Total in
2,140
1,080
3,340
382
46
12
7,000
2,100
954
1,150
357
44
6
4,611
36
126
2,190
25
2
7
2,386
4,210
~
72
~
t
2,540
1,810
10,500
102,000
39,000
2,600
~.
112% T T07% I 124% 1 -
1.0
42.0
85
613
380
N/A
~

18.2
18.2

5.3
1.7
12.1
39.0
1.7
0.02
59.8
329%
6.0
~

0.4
0.0
N/A
N/A
N/A
N/A
"~"
—
259
	 259"

8.4
0.0
— .
"I

1A
5
Z
3
4
7
8
9
i
Ruri""2 	 	 ' '
Streams in
Feed soil
Make -up water
Total in

Gravel
Sand
Clarrfier sludge*
Washed casing chips**
Heavy metal (lead) fraction***
Clarffier filter residue
Total out
I otai out x i do = % balance
Total in
4,050
2,540
7,490

1,810
1,210
3,930
333
60
25
7,368
aS%
4,590
4,590

1,790
1,070
1,290
321
55
8
4,534
»9%
351
2,540
2,891
Streams ou
24
130
2,640
12
5
17
2,828
88%
10,400
~
t
903
1,670
8,500
102,000
39,000
2,100
—

132
~

0.8
40.0
52
613
380
WA
*~

47.7
47.7

t.6
1.8
10.9
32.8
2.1
0.02
48.2
103%
5.0
~

0.0
0,0
N/A
N/A
N/A
N/A
—

230
230

0.0
0.0
—


1A
5
2
3
4
7
8
9
Huns
Streams in
Feed soil
Make-up water
Total in
8,250
3,410
11,670
7,830
7,830
438
3,410
3,848
2,280

50
~
17.8
17.8
1.7
"~
Streams out
Gravel
Sand
Clarrfier sludge*
Washed casing chips**
Heavy metal (lead) fraction***
Ctarifier filter residue
Total out
1 otal out x 1 00 = % balance
Total in
3,540
1,960
5,510
375
162
64
11,611
»9%
3,440
1,710
1,950
364
145
24
7,633
87%
82
249
3,560
11
17
40
3,959
103%
15
1,510
5,900
1,500
39,000
850
~

0.2
26.0
60
36
380
N/A
~
~
0.1
£.6
11.5
0.5
5.7
0.02
1.2
0.0
N/A
N/A
N/A
N/A
20.4
115%
mm.
133
133

41.3
0.0
™
""**
* Unsettled clarifier sludge. This sludge settled/dewatered to about 40 wt% moisture in 48 hours.
** TCLP and total lead analyses were averaged for the first 2 runs (same feed stockpile).
*** TCLP and total lead analyses were averaged over the three runs
N/A — not analyzed
                                                      43

-------
  CLARIFIER/
  THICKENER
                       CLEAN WATER
                          TANK
CHEMICAL INJECTION PUMP/^   WATER
                           PUMPS
WATER
 TANK
COAGULANT
   TANK
            CHEMICAL
             MIXING
            CHAMBER
                        SEPARATION
                        CHAMBERS
       l

TROMMEL/WASH
    PLANT
                                             SLURRY TANK
                                                                              HOPPER
FEEDER
                                            Q=,
                                                     SLURRY
                                                     PUMP
SPIRAL
CLASSIFIER
DENSITY
SEPARATOR
                                        r
                         CONVEYOR BELTS l FOR CLEAN
                                MATERIAL l DISCHARGE
                                        l
                                        l
                                        l
                                   CASING CHIP
                                   SEPARATOR
                                                         TRAILER DIMENSIONS 8' x 40'
                              Figure C-3. Plant layout.

-------
                         Figure C-4
             Run 1 - Total Lead Concentration in
           Feed Soil and Washed Gravel and Sand
 10
38
o
o
0»
£

6
c
o
o 4
T3
0)
   0
    0
       1
 234
Total Elapsed Time (Mrs)
    Legend

    ~A-  Feed Soil

    ~H~  Washed Sand
                             Washed Gravel
                        	 EPA Cleanup Goal
                            (1,000 mg/kg Total Pb)
* Sample contained metallic lead
                            45

-------
                    Figure C-5
        Run 2 - Total  Lead Concentration in
       Feed Soil and Washed Gravel and Sand
        1
 2        3       4
Total Elapsed Time (Hrs)
Legend

-^-  Feed Soil

     Washed Sand
 * Sample contained metallic lead
               Washed Gravel

               EPA Cleanup Goal
               (1,000 mg/kg Total Pb)
                        46

-------
                         Figure C-6
             Run 3 - Total Lead Concentration in
           Feed Soil and Washed Gravel and Sand
  10
o
o
o

X

o
*L
o
c
o
o  4
CJ
   0
       -0-
                   2345

                    Total Elapsed Time (Mrs)
    Legend
     -^^ Feed Soil              -©-

     ~H~ Washed Sand          	


     *  Sample contained metallic lead
 Washed Caravel

 EPA Cleanup Goal
(1,000 mg/kg Total Pb)
                             47

-------
                          Figure C-7

            Lead TCLP in  Washed  Gravel and Sand
  50
  40
-a 30
a.
a>
E
•*•«••

a.
_j
O
i-
20
  10
   0
     0
                         -A.
          1
      Legend

          WG Run 1-


          WS Run 2
2345

 Total Elapsed Time (Hrs)



e-  WG Run 2-B- WG Run 3~
                                              WS Run 1
                    WS Run 3-
      WG - Washed Gravel
      WS - Washed Sand
                EPA Cleanup Goal
                (5 mg/L Pb)
                             48

-------
                           Figure C-8
                   Run 1 - Solid Stream Flows
  2.5

-------
                          Figure C-9
                  Run 2 - Solid Stream Flows
  2.5
  1.5
cd
o:
  0.5
      o
      e
      o

      a
ts
c
o
a>
C
o
o
c
o
09
c
o
a
c
o
SB
C
O
05
C
o
09
C
O
                                       J	J
                                      I   I
                       I
   0
     0
          234
        Total Elapsed Time (Hrs)
        • Feed Soil
        Stream 1A
           " Washed Gravel
           Stream 2
                        • Washed Sand
                        Stream 3
                              50

-------
                        Figure C-10
                Run 3 - Solid Stream Flows
                   c: O
                        CDC
                        1!
                                          — -a— Sen
                                          £ — oo—
                                  CO
                                  — •a
     w
     c
     o
           II
c
o
c
o
CO
cr
  0
                                          CM <»
                                             0 -<

-------
                               TABLE C-4.  LEAD PARTITIONING

Run
1
2
3
-1/4" to +10 mesh fraction
Feed soil
SS1
Pb
mg/kg
3,650
8,899
824
Sand fraction
SS3
Pb
mg/kg
191
162
69
Pb
TCLP
4,8
5.7
1.7
-10 mesh to +150 mesh
Feed soil
SS1
Pb
mgAg
5,671
6,844
3,338
Sand fraction
SS3
Pb
mg/kg
3,114
2,822
2,400
hourly flow rate. Similarly, the casing chips (Stream 7)
and  metallic-lead  fraction  (Stream 8)  were  each
collected in drums and weighed at  the end of a run.
The average hourly flow rate was calculated.

The high QA/QC standards of the EPA SITE Program
resulted in accurate mass balances  for the three runs
(107,  99,  and 98  percent) as measured by  percent
balance (output/input) in Table C-2 for total dry solids.
The balances for lead were acceptable for Runs 2 and
3:  104 and 115 percent  respectively.   But the Run 1
balance at 330 percent demonstrated the difficulty in
analyzing  heterogenous  soil  mixtures  that  contain
metallic lead.  The dilemma is caused by the  need to
determine low lead concentrations in mg/kg (parts  per
million)  due to the high toxicity of lead.  Thus, small
amounts of metallic lead can greatly influence the lead
analyses.  This problem  was particularly apparent in
several washed gravel samples from Runs 1 and 2 in
Figures C-4 and C-5.  These high lead concentrations
underscore  the  importance  of efficient metallic-lead
removal, not only in the chip separator for the  washed
gravel, but also in the density separator for the  washed
sand.

Sampling

Streams 1A, 2, and 3 were sampled every 45  minutes
during process operations (Samples SS1,  SS2, and
SS3). A siudge sample (SS4) was collected from every
drum (51 drums in Run 3) and composited for each run.
A composite sample was collected at the end  of each
run for casing chips (SS7) and the metallic-lead  fraction
(SS8).

pH Monitoring

Every 2 hours, a field pH reading was taken of  the
aqueous streams; dirty water recirculation (SS9),  clean
water recycle (SS10), and chip separator recycle water
(SS12). The overall system pH remained in the 6.3 to
7.1 range.

C.2.3   Performance Summary

Three  key performance  criteria for this project were:
lead  removal  efficiency (both  process  and  total),
process efficiency, and  battery casing chips removal
efficiency.  A  summary of the  performance data is
presented in Table C-5.

•    Lead removal (process) efficiency is measured as
     the amount of lead  In the feed soil (expressed as
     Pb1A) contained In the minus 2W to plus 150 mesh
     fraction, less the lead in the washed gravel (Pb2)
     and sand (Pb3) fractions, divided by the lead in this
     feed fraction (Pb1A).
% lead removal (process) =
pb1A-pb2-PD3
       Pb1A
X 100
     This is a true measure of the BSWS lead removal
     capability because it discounts the lead in the feed
     soil fines fraction (minus 150 mesh) that could be
     removed  by   simple  screening  (i.e.,  without
     washing). Table C-3  shows the lead distribution
     among the various process streams.

     Lead removal (total) efficiency Total lead removal
     efficiency, including the fines, is reported in Table
     C-5. This is measured as the total amount of lead
     in the feed soil (PbT1A) less the lead  in the washed
     gravel (Pb2) and sand (Pb3) fractions, divided by
     the total amount of lead in the feed  soil.
% lead removal (total) =
                        PbT1A-Pb2-Pb3
X100
                              PbT
                                                                                      1A
                                                  52

-------
                           TABLE C-5.  PERFORMANCE SUMMAFIY
Form of measurement
Lead removal efficiency (process +150 mesh)
Lead removal efficiency (total, including fines)
Process efficiency
Battery casing chips removal efficiency
Performance achieved
%
Run 1
28
61
11
97
Run 2
91
93
32
100
Run 3
77
85
49
70
•  Process efficiency represents the amount of the
   washed  gravel fraction  plus  the  sand fraction,
   expressed as the  percent of feed greater than 150
   mesh (dry weight basis) that meets the EPA cleanup
   goals on an hourly-flow basis (totalled for each run
   cycle).   The  total lead  and TCLP  values  are
   averaged for each time interval (for each washed
   fraction—gravel and sand) to determine the amount
   of soil that  meets  these goals.

   In Run 1, only 20 percent of the washed gravel met
   the cleanup goals. This is equivalent to 11 percent
   process efficiency.  In  Run 2, 71 percent of the
   washed gravel met the goals  (32 percent process
   efficiency).   In Run 3, 100 percent of the washed
   gravel  passed  (49 percent  process  efficiency).
   None of the washed sand from  any of the three
   runs met the cleanup goals (Table C-3).  Although
   the process did  not meet the 75  percent target
   efficiency, performance improved significantly as the
   Demonstration progressed.

   This approach to process efficiency is very rigorous
   because it  rejects any hourly average analysis of
   either total  lead or TCLP lead that exceeds the
   cleanup goals.   Note that for Run 2, the  overall
   composited average total lead and TCLP analyses
   for the  gravel from Table C-3 are 903  mg/kg  and
   0.8 mg/L, which meet the cleanup goals. However,
   Figure C-5 shows excessive total lead concentration
   in one  sample.   This causes a  reduction in
   performance for the gravel fraction from 100 percent
   to 71  percent.  On the  other  hand, this approach
   eliminates the possibility of the whole run being a
   failure,  if,  for example, the  overall  composited
   average had been 1,003 mg/kg total lead.
     Battery  casing  chips  removal  efficiency is
     calculated as the weight percent of chips in the
     feed soil (C1A) contained in the minus 21/£" to plus
     150 mesh fraction, less chips in the washed gravel
     (C2) and sand (C3) fractions, divided by the weight
     of chips in this feed fraction (C1A), expressed as
% casing chips removal ==
                          C1A-C2-C3
X100
                                 •"1A
     Table  C-3 shows the casing chips distribution
     among  the  feed,  washed  gravel, and  sand
     fractions.  No attempt was made to develop an
     overall casing chip mass balance.  Note that the
     amount of chips in the whole feed was equal to the
     amount in the minus 2M>" to plus 150 mesh fraction
     because the lab only reported the chips that could
     be manually  removed from a sample aliquot (i.e.,
     down to about 10 mesh). As expected, none of
     the washed  casing chips from any of  the three
     runs met the cleanup  goals (Table C-3).

C.2.4   Input and Output  Flow Rate Stability

Figures C-8, C-9, and C-10  present the stream flows for
the three Demonstration  runs for  feed  soil, washed
gravel, and sand.  These data show that, at 2,4 to 4.2
tph, the BESCORP unit operated satisfactorily most of
the time. From the data in Table C-6, process downtime
was about 13 percent and nonprocess downtime was 8
percent for a total of 21 percent. Therefore, process on-
line time was 87 percent.  In Section 4, the economics
for a commercial 20-tph BSWS unit are developed on
the basis of 80 percent on-line time.
                                                 53

-------
                    TABLE C-6. DOWNTIME SUMMARY FOR THE THREE RUNS
Cumulative
total (3 runs)
Shutdowns Process Oriented
Conveyor jam
4 pluggings in chip separator
Process total
Shutdowns Nonprocess Oriented
Low make-up water flow
City power failure
Nonprocess total
OVERALL DOWNTIME
Time*
(min.)
91
46
137
62
29
91
228
Downtime

13

8
21
      "Total run time 18 hours.
C.3   REFERENCES

1.  Guide to Conducting Treatability Studies Under
   CERCLA:   Soil  Washing  Interim  Guidance.
   EPA/540/2-91/020A. September 1992.
                                            54

-------
                                          Appendix D
        Case Studies: Full-scale Demonstrations  and Treatabiiity Studies
                                    [Provided  by Vendor]
Using  various  process   approaches,   BESCORP
performed full-scale  demonstrations  and treatability
studies to determine contaminant removal efficiencies.
The studies focused on contaminant removal from soils
of varying characteristics. The most important aspect
regarding soil washing  is an in-depth analysis of the
contaminated soil through treatability studies and pilot-
scale feasibility demonstrations.  No soil-contaminant
combination will establish a generic treatment process;
a specific soil characteristic warrants a site-specific
process approach. As illustrated at ABE, representative
sampling is mandatory;  a sampling plan that does not
characterize  the site adequately  may  prescribe  a
treatment process for site conditions that do not exist.

•   Lead Site Remediations

    BESCORP tested material from five different lead-
    contaminated sites.  Analytical results established a
    need for different process approaches for each site.
    BESCORP analyzed soils contaminated with lead in
    various forms:  discrete metallics,  battery casings,
    vegetation matrix, iron hydroxide  precipitate, and
    mixed metals at an ammunition destruction site.

•   Radium-Contaminated Soils

    BESCORP  conducted   an  on-site  treatability
    demonstration involving Radium-226 contaminated
    soil, in which 50 percent of the material was minus
    400 mesh. The field data demonstrated a qualitative
    ability to partition radium to 20 percent of the soil.

•   Depleted Uranium-Contaminated Soils

    BESCORP conducted  treatability testing for the
    removal of uranium  metal and oxides from soil at a
    munitions  testing site.   The  treatability testing
    targeted a combination  of density separation and
    chemical leaching.
*    Hydrocarbon-Contaminated Soils

     BESCORP demonstrated cleaning hydrocarbon-
     contaminated soils with and without surfactants.
     Results demonsl rated the use of high pressure and
     warm water as a stand-alone volume reduction
     process, or as a pretreatment for separating and
     feeding the contaminated  fines to a  bloslurry
     reactor.

CASE  D.1    TREATABILITY  STUDY  AND  SITE
REMEDIATION: ARMY AMMUNITION PLANT
Location:
Plant Size:
Quantity:

Process:
Overview
New Brighton, Minnesota
20-tph mobile plant
1,900 tons (to be continued in summer
1994)
Water-based,   physical   separation
system, using a coagulant only
Soil at a munitions manufacturing and testing site was
expected  to contain  only  process  residue,  with
contamination by lead  stypphnate and other forms
associated with  initiators.  A  company, contracted to
provide a leach process, (discovered metallic lead in the
soil, which would extend the leach time for processing
the material  to a prohibitive  length.  BESCORP  was
contracted to confirm the presence  of metallic lead and
establish a process for removal.

Bench-Scale Study

The material was sized and treated to obtain a dense
material fraction and a clean fraction. Size distribution
of the material is presented in Table D-1.

The soil was contaminated with discrete, metallic-lead
particles from plus 8 mesh to  minus 200 mesh.
                                                 55

-------
                   TABLE D-1.  PARTICLE SIZE AND LEAD DISTRIBUTION
                                AT AN ARMY AMMUNITION SITE
Size
+14 inch
-Winch to +8 mesh
-8 to +30 mesh
-30 to +50 mesh
-50 to +100 mesh
-100 to +140 mesh
-140 to +200 mesh
-200 mesh
TOTAL
%
11.3
4.7
12.1
25.4
20.9
4.6
1.4
19.6
100.0
Pb, ppm
0
0
1,436
1,025
901
948
940
679

Duplicate process runs resulted In removal efficiencies
from 43 to 91 percent, with final lead concentrations
ranging from 138 to 739 ppm Pb.  The minus 200 mesh
fraction was the  most  contaminated.    This  high
concentration of lead Is quite amenable to leaching.
Subsequent  leaching  tests were  conducted  on
composite material of all mesh sizes, where removal of
80  to  90  percent  of  the  remaining  lead  was
accomplished. This easily met the anticipated 300 ppm
Pb discharge limit.

Full-Scale Application

At the Twin CWes Army Ammunition Plant (TCAAP),
located In  New Brighton,  Minnesota,  BESCORP Is
providing excavation and soil-washing services for soils
contaminated with eight metals.  BESCORP's process,
coupled with the COGNiS TerraMet leaching system, is
performing complete soil remediation.  Lead extracted
from the processed soil is being recovered and shipped
to a smelter for reuse.  All processed soil is being
returned to the site.

Site "F," located within the four-square-mile TCAAP site,
was originally a munitions burning and burial area. The
site  Is part of the  Army's $370 million  Installation
Restoration Program. Remediation is being conducted
under  a  Resource  Conservation and Recovery  Act
permit.  Remedial Investigations determined that lead
levels In trenches and shallow soils over the three-acre
area exceeded 4,000  ppm. While lead was identified as
the primary metal of concern, seven other sites were
discovered at high levels throughout Site F.   Ash,
residues, metallic lead, and copper spread over the site.
In addition, 0.30 and 0.50 caliber casings and  cyanide
pots were buried in trenches throughout the plant.

Remedial alternatives, such as solidification/stabilization
and land filling, were evaluated and dismissed because
these techniques leave the  metals in the soil and
continue the risk for long-term liability.  The involved
parties determined to evaluate soil-washing as the long-
term solution.

Soil-Washing Activities

In the  spring  of 1993,  COGNIS and  BESCORP
conducted joint treatability and bench-scale studies in
order to determine the applicability of their processes to
complete soil remediation. The studies determined the
following:

•    BESCORP's Soil Washing System could be linked
     with the COGNIS TerraMet™ process to treat the
     separated fines as a continuous and complete soil
     treatment process.

•    Site "F" soils could  be successfully treated to meet
     the required cleanup levels specified below In
     Table D-2.

BESCORP commenced  construction  of a  high-
throughput  plant  designed   around   the   process
demonstrated at the ABE Superfund Site under the EPA
                                                 56

-------
                         TABLE D-2.  CLEANUP LEVELS FOR TCAAP
1 Metal:
Performance goal
(mg/kg):
Sb
4
Cd
4
Cr
100
Cu
80
Pb
300
Hg
0.3
Ni
45
Ag
5
SITE Program in 1992.  The new plant was completed
in July 1993.  In the fall of 1993, 2,000 yds of material
were processed and the material stockpiled on-site until
the remainder of the material could be processed and
the cleaned soils graded back onto the site.  The time
(shipping  the  unit,  on-site set-up, and shakedown)
totalled 17 days.

The five-trailer, full  soil treatment process (BSWS and
COGNIS)  was situated at Site "D," a 185 ft x  100 ft
cement pad equipped with sumps and bins for holding
processing soil.  The  pad, originally built for a PCB-
treatment process, was an ideal location for processing
as it was located only 1,500 ft from the excavation area.
                                      Process Performance

                                      The  full-scale,  soil  washing  and  leaching  system
                                      acceptance period started on September 17, 1993 with
                                      340 tons of excavated and stockpiled material.  The
                                      cleanup goals were met, and material processed until
                                      temperatures dropped to freezing and activity had to be
                                      interrupted until the spring of 1994.

                                      It is believed that Site *F" contains approximately 7,500
                                      tons (5,000 yds) of metal-contaminated soil.  To date,
                                      approximately  1,900 tons  have  been  successfully
                                      remediated; clean, processed soil has been transported
                                      from the  soil-washing  area  back  to  Site  "F"  for
                                      redepositing and seeding with native vegetation.
CASE D.2  REMOVAL OF MINUS 100 MICRON (150 MESH) MATERIAL: HANFORD SIMULATED SOIL
Location:
Plant Size:
Quantity:
Process:
Overview
Prosser, Washington
20-tph mobile plant
500 yards (900 tons) processed
Water-based,   physical   separation
system, using a coagulant only
Analysis,  by Westinghouse  Hanford Company,  of
Hanford soils contaminated with heavy metals (including
Uranium 238, 235, cobalt, and cesium) determined that
contaminants can  be partitioned to the minus 100
micron (-150 mesh) soil fraction.  In 1991, BESCORP
conducted  laboratory  tests  for  determining  the
applicability of using a water-based physical process for
removing minus 100 micron soil particles from Hanford-
type (gravely-sandy)  soils.   Based on those  results,
BESCORP constructed  a  20-tph  plant  in Prosser,
Washington, for testing and demonstration purposes.

Using the 20-tph plant, BESCORP achieved verification
of the  particle size  cut  by washing  900 tons  of
noncontaminated Hanford simulated soil.
Documented  Evidence  (Process  Approach  and
Efficiency)

Informal demonstrations were conducted for Ebasco
Environmental, Westinghouse, and Battelle personnel
with the 20-tph plant in Prosser, Washington. Based on
those demonstrations and an evaluation of the system's
efficiency using water in conjunction with a coagulant,
the BESCORP System was included in a presentation by
R.L. Treat at Environmental Restoration (ER) '91.

Efficiency data (below) were included in the presentation
at ER '91 regarding the ability of the system to produce
an excellent separation of coarse and fine soil.  While
the  plant  was   processing  material   at  20  tph,
Intermountain Materials Testing, Inc. collected samples
and performed the analysis in accordance with ASTM
C136, D422, and  D1140, respectively.

The results highlight the ability of the BSWS to separate
the fine soil fraction, using a water-based process.
Essentially no fines in the coarse fraction were leaving
the plant, and no coarse material was associated with
the separated fines (Table D-3).
                                                  57

-------
                       TABLE D-3.  SIZE SEPARATION EFFICIENCY
Sieve size
(mesh)
4 in.
10
20 -
40 (0.42 mm)
80 (0.177 mm)
200 (0.074 mm)
270 (0.053 mm)
400 (0.037 mm)
635 (<0.037 mm)
Stream 1
(coarse discharge)
% passing
100
95
84
33
1
0.3
0
0
0
Stream 2
(fine discharge)
% passing
100
100
100
100
100
99
97
84
62
CASE D.3 DISCRETE PARTIAL RECOVERY PLANT: TRAMWAY BAR MINE, ALASKA
Location:      Tramway Bar, Alaska
Plant Size:     150 tph
Quantity:      71,400 tons processed
Process:       Water-based,   physical   separation
              system, using a coagulant only
Overview

A 150-tph plant was built in 1989, processing 42,000
yards (71,400 tons) of material. Designed originally for
separating gold fines, the process was adapted for use
In the soil remediation  arena.  The  system operated
successfully, classifying  material, and appealed to both
miners and the regulatory agencies, because of its low
water requirements and high classification efficiency.
The 150-tph plant generated the results shown in Table
D-4,  where recovered clean material totalled 97.5 wt
percent.
                TABLE D-4.  MATERIAL BALANCE FOR A 150-TPH PLANT
Material
Clean material
Soil fines (to waste container)
Secondary waste
TPH
146.3
3.75
0.56
                                            150 - 3.75 - 0.56
                    wt. percent recovered  =  	 x 100 = 97.5%
                                                  150
                                               58

-------
CASE D.4 ON-SITE FIELD TEST:  RADIUM-CONTAMINATED SOIL AT OKLAHOMA AIR FORCE BASE
Overview

In  conjunction  with  a teaming  partner,  BESCORP
conducted   on-site   demonstrations   at   a   site
contaminated with radium as a result of manufacturing
activities.  The area was partially excavated, samples
were collected, and the remaining material stored.

Demonstration Results

Soil samples were collected from storage drums and
screened for activity wilh  a Nal scintillation  gamma
detector. Two of the samples were sized and monitored
for  radiation.   Relative Geiger counter  rates were
recorded as an indication of residual radium  in each
fraction.  The test  showed that  activity was primarily
confined to 20 percent of the soil.

The  soil consists  almost  entirely of clay; however,
radium was found  to consist of medium-sized, dense
particles.  High attrition breakdown of the clay, along
with  a highly efficient gravity separation process, was
determined to be an effective remedial approach.
CASE  D.5   COPPER  WIRE INCINERATION  AND  RECOVERY SITE  TREATABILITY STUDY:
CONTAMINATED SOIL
                                           LEAD-
Overview

A wire burning site was the location of a previous
copper  recycling effort.    BESCORP's  testing  was
performed as a joint treatability study with a teaming
partner that has metal leaching and recovery processes.
BESCORP  provided an' up-front  physical process,
removing 50 to 75  percent of the total lead and 50
percent of the  initial copper.   The  initial material
contained 12,000 ppm Pb (1.2 percent) and 100,000
ppm copper (10 percent).

Bench-Scale Study

The initial screening tests consisted of material sizing to
obtain a soil histogram and to determine the extent of
lead contamination.  The material contained obvious
pieces of copper wire, and occasionally a chunk of
melted and solidified so!der.  Treatability test results
determined that  remediation could be accomplished
with a combination of soil sizing and gravity separation,
with a chemical leach of the soil fines.  Typical results
on replicate samples for size distribution and resulting
lead and copper concentrations are presented in Table
D-5.

Removal efficiency v/ith a mineral jig  (based on  the
percentage in the concentrate) was 86.8 percent for
lead, and 77.7 percent for copper.  Typical amounts of
soil incorporated into the gravity concentrate were from
4.3 percent  to  8.9  percent of the  feed.   This  was
achieved with a single pass.  It is expected that the feed
percentage in the concentrate will decrease with a full-
scale process,  which  will  incorporate a  secondary
concentration process.
                 TABLE D-5.  PARTICLE SIZE AND METALS DISTRIBUTION
                                    AT A COPPER WIRE SITE
Particle mesh
size
+40
-40 to +140
-140
Jig concentrate
TOTAL
Feed soil
wt %
15.8
6.2
48.9
NA
70.9
Pb
(ppm)
2,500
2,500
3,330
80,000

Copper
(ppm)
31,600
60,000
2,3,000
324,000

                                                 59

-------
CASE D.6 LEAD-CONTAMINATED METAL RECYCLING FACILITY
Overview

The site was previously used for automobile metal
recovery and recycling, with deposition debris on-site.
The contaminant of prime concern is lead.

Bench-Scale Study

The soil consists of debris that one might imagine to be
present at a site where complete cars were hydraulically
smashed for compaction prior to shipment for repro-
cessing:  plastic bits and pieces, metal, bits of debris
(wood chips, paper, and cardboard), and a tremendous
amount of iron hydroxide precipitate.
Lead contamination, as a function of particle size, is
depicted in Table D-6.

Soil washing of the material with magnetic separation
did not improve lead segregation. An attrition scrubber
removed iron hydroxide from the surface of the material,
and segregated  the lead  to the finer fractions.  The
treatment results are presented in Table D-7.

Preliminary  results indicate  decreased levels of lead
contamination in the material. Further improvement of
the attrition process to remove lead from the coarse
fractions should improve the subsequent leach process
and potentially reduce the fraction that must be leached.
Current treatability tests indicate lead concentration after
leaching to be in the range of 50 ppm.
                  TABLE D-6.  PARTICLE SIZE AND LEAD DISTRIBUTION
                              AT A LEAD RECYCLING FACILITY
Particle mesh size
+4
-4 to +8
-8 to +40
-40 to +140
-140
TOTAL
%
35.5
14.3
18.4
14.0
17.8
100.0
Pb (ppm)
4,000
3,050
3,450
5,450
NA

                  TABLE D-7.  PARTICLE SIZE AND LEAD DISTRIBUTION
                             BEFORE AND AFTER TREATMENT
Particle
size
+4 mesh
-4 to +8 mesh
-8 to +20 mesh
-20 to +40 mesh
-40 to +140 mesh
Pb
ppm
(prior to attrition)
4,000
3,050
3,100
3,450
5,450
Pb
ppm
(after attrition)
ND
1,065
500
1,980
5,400
          *ND - Nondetectable
                                               60

-------
CASE D.7  LEAD-CONTAMINATED TARGET RANGE SITES
Overview

The site (conisting of three areas) was used for skeet
and small arms shooting; lead shot was distributed over
a large field,

Bench-Scale Treatability

The soil was sized to obtain an initial split of the material
for delineating lead distribution. Large quantities of lead
shot were  found at the site, and extremely  large
amounts of lead bullets were found in a small portion of
the site.  Shot was also found in samples from  areas
that were supposedly not used for skeet activity.
Table D-8 shows that analysis of organic material (grass,
etc.) revealed lead concentrations exceeding 4 percent,
which was surprising since this level of bioaccumulated
lead had not been encountered at any other site.  Work
has yet to be performed to determine how the lead is
bound  in the vegetation.

With exception  of the Site 3 material, the BESCORP
process is expected to achieve 65 to 75 percent volume
reduction, the remainder of the soil consisting of dense
metallic material suitable for  recycling.  BESCORP is
investigating the possibility of the vegetation being used
for  lead recovery by thermal  destruction in a lead
smelter.  This would eliminate  the  need for off-site
disposal.
                  TABLE D-8.  PARTICLE SIZE AND LEAD DISTRIBUTION
                                      AT TARGET RANGES
                                               Site 1
                                               Site 2
                                               Site 3
Particle mesh size
+4
-4 to +40
-40 to +140
-140
TOTAL
%
4.8
16.0
67.6
11.6
100.0
Pb, ppm
—
(335
545
3,1570

Particle mesh size
+4
-4 to +40
-40 to +140
-140
TOTAL
%
6.3
1.0
79.1
13.6
100.0
Pb, ppm
1,500
1,000,000
25
1,452

Particle mesh size
+4
-4 to +40
-40 to +140
-140
TOTAL
%
14.7
7.7
67.0
10.6
100.0
Pb, ppm
1,000,000
1,000,000
7,387
24,000

                                                 61

-------
CASE D.8 TREATABIL1TY STUDY: HYDROCARBON-CONTAMINATED SOILS
                                                     by a bio-slurry reactor to destroy the hydrocarbons
Overview                                            removed from the oversize.  The entire process is
                                                     accomplished either with a surfactant-augmented water
                                                     wash or a steam wash.
Treatability studies on hydrocarbon-contaminated soils
were performed at military facilities in Alaska. The work
focused on successfully cleaning the soil oversize and
processing the hydrocarbon-contaminated fines with a
bio-slurry reactor.

Bench-Scale Study

The bench-scale study of hydrocarbon removal from
soils has consisted of determining  the ability  of the
system  to  clean the  plus  40 mesh material  to  a
hydrocarbon  contamination  level that will  allow for
redeposit  on-site  (<100  mg/kg  total  petroleum
hydrocarbon). The minus 40 mesh soil will be treated
                                                     Volatilization of the organic  material  and associated
                                                     health hazards are potential problems with the steam
                                                     wash. However, the contaminated samples consisted of
                                                     residual diesel and jet fuel.   BESCORP  achieved a
                                                     cleaner fraction with steam (96 and 108 ppm) than with
                                                     a surfactant wash (270 ppm).

                                                     The studies to date have investigated the ability to treat
                                                     residual hydrocarbons, which  are the largest volume of
                                                     contamination in our locale. BESCORP plans to expand
                                                     the BSWS treatment capabilities to handle diesel-range
                                                     and, eventually, gasoline-range hydrocarbons.
CASE D.9 URANIUM-CONTAMINATED SOILS

Overview

The site was used by an armament manufacturer for
testing depleted uranium munitions. The contamination
Is limited to a catch box and surrounding area where
vibration has spread the contamination.  The uranium
exists as discrete metallic pieces and uranium oxides,
which are quite friable and can be segregated to the fine
soil fractions.

Treatability Study

The treatability study  Is a joint effort using physical
processing for the removal of discrete uranium in con-
                                                    junction with chemical leaching of soil fines for removal
                                                    of metallic and oxide uranium.

                                                    The  sample   was   initially  sized  and   uranium
                                                    concentrations in  each fraction were measured by
                                                    gamma spectroscopy.  The material did not show any
                                                    significant distribution of uranium versus size. Gravity
                                                    separation of the material  within  each  size range
                                                    produced a uranium concentrate of a consistent and
                                                    appreciable fraction.   Analysis  revealed  uranium
                                                    concentrations as high as three percent in the sample.
                                                    The results are proprietary. However, a combination of
                                                    physical and chemical processes  will remediate the soil
                                                    to acceptable  release criteria.
CASE D.10  ABE TREATABILITY STUDY

Overview

The ABE NPL site was chosen for the BESCORP SITE
Demonstration based on the Remedial Investigation (Rl)
that was performed in 1988. The Rl stated that the lead
was in the fine soil material on the site (i.e., no discrete
metallic-lead, no battery casings, and no casing chips),
which would have been a perfect match for the BSWS.

However,  the  material   excavated   for  the  SITE
Demonstration  was considerably different from  this
                                                    material.  The stockpile of material excavated  was
                                                    approximately 10 to 15 percent battery casings  with
                                                    visible metallic portions of lead acid batteries.

                                                    Treatability Tests on Rl Sample

                                                    Initial BESCORP work was performed on a sample from
                                                    the Ri (Sample B-7), which was sized to determined the
                                                    distribution of the material and the lead content of each
                                                    fraction. The data for the minus V4- inch raw sample are
                                                    shown in Table D-9.
                                                  62

-------
      TABLE D-9.  PARTICLE SIZE AND LEAD DISTRIBUTION IN Rl RAW SAMPLE
Particle mesh size
+8
-8 to +30
-30 to +50
-50 to +100
-10010 +140
-140 to +200
-200
TOTAL
Soil wt. %
7.58
2.80
7.79
12.44
9.30
10.89
40.83
100.00
Pb, ppm
190
19,300
1,190
548
772
1,090
1,820

        TABLE D-10.  LEAD DISTRIBUTION IN Rl SAMPLE AFTER PROCESSING
Material
(s.g. 0.9-1 .3) float (casing chips)
(s.g. 1.3-2.5) light
(s.g. 2.5-5.0) mid
(s.g. 5.0-10.0) heavy (lead)
TOTAL
%
1.9
82.0
14.6
1.5
100.0
Pb (ppm)
6,850
252
862
9,117

            TABLE D-11.  LEAD DISTRIBUTION IN SECOND FRACTION OF Rl
                              SAMPLE AFTER PROCESSING
Material
(s.g. 0.9-1.3) float (casing chips)
(s.g. 1.3-2.5) light
(s.g. 2.5-5.0) mid
(s.g. 5.0-10.0) heavy (lead)
TOTAL
%
2.1
87.6
10.1
0.2
100.0
Pb (ppm)
3,975
354 .
t,040
51,282

When a portion of this  material was  processed by
gravity and density separation, products contained the
lead distribution indicated in Table D-10. The specific
gravity ranges are approximations, as the size of the
particle and the density determine where the material
will collect.  Good results are expected for the gravity
process at this site. A second size fraction, minus 50 to
plus 100 mesh, was distributed as shown in Table D-11.
A second portion of the B-7 sample was processed on
a mineral jig, and the concentrate measured 164,000
ppm Pb.  The tails analysis was found to contain 848
ppm Pb. After the tails, were washed to remove the -200
mesh material, the analysis was 261 ppm lead.  The
fines themselves were analyzed to 2,200 ppm Pb.  This
data further  supports the gravity separation as a
reasonable approach to process this material. The size
                                              63

-------
separation Is also shown to be important. With a total
lead content of 261 ppm, the maximum TCLP lead value
would  be 13 ppm  if 100 percent of the lead was
dissolved.

BESCORP was  proceeding with this evaluation when
they were advised that they would need to remove the
battery casings from the on-site material, as well as
needing a circuit to  remove the discrete, metallic-lead
particles that were present in the excavated material.

With a short time frame to develop and implement both
a dense and a light fraction circuit capable of operating
over a size range of minus 21/6 inch to plus 150 mesh,
attention was focused on the processing rather than the
further analysis.

Further sample work was performed on the excavated
material  to  verify the  process  approach  and  the
effectiveness on the  "real" ABE Site soil.
Treatability   Tests  on   Feed   Pile   for   SITE
Demonstration

The samples treated in the BESCORP plant simulation
were taken randomly from the surface and subsurface
of the excavated stockpile.  Typical results from the
simulated process are listed in Table D-12.

In retrospect, these data show how important the cut
point for the size classification is, but BESCORP did not
anticipate prior to the SITE Demonstration that the small
portion of minus 100 to plus 140 mesh material (two
percent of the sand screw discharge) would have such
a  high  lead  content  and  that  it would exert the
subsequent adverse effect on the product (sand) stream
analysis.   This lead content exceeded the redeposit
limits for the washed sand fraction.  Post-SlTE Program
treatabilfty tests,  presented  in Appendix B, show the
preferred cut point for the sand fraction to be about plus
80 mesh.
                        TABLE D-12.  PARTICLE SIZE AND LEAD DISTRIBUTION
                           IN Rl SAMPLE AFTER SIMULATED PROCESSING
Particle mesh size
-8 + 100 mesh
-100 + 140 mesh
-140 + 200 mesh
-200 mesh
Pb (ppm)
256
2,540
1,600
8,420
                                                 64

-------
Intentionally

-------


-------
Page Intentionally Blank

-------
United
        enfa! Prefecton A§t}ncy
      for ErWkftnmaptaf ftes
-------