c/EPA
          United States
          Environmental Protection
          Agency
            Office of Research and
            Development
            Washington DC 20460
EPA/540/AR-93/522
September 1994
Eco Logic International
Gas-Phase Chemical
Reduction Process—
The Reactor System

Applications Analysis Report
                SUPERFUND INNOVATIVE
                TECHNOLOGY EVALUATION

-------
                                                     EPA/540/AR-93/522
                                                       September 1994
Eco Logic International Gas-Phase Chemical Reduction
              Process—The Reactor System

                Applications Analysis Report
                     Risk Reduction Engineering Laboratory
                      Office of Research and Development
                     U.S. Environmental Protection Agency
                          Cincinnati, Ohio 45268

-------
                                 Notice
    The information in this document has been funded by the U.S. Environmental
Protection Agency (EPA) under the auspices of the Superfund Innovative Technology
Evaluation (SITE) Program under Contract No. 68-C9-0033 to Foster Wheeler Enviresponse,
Inc. (FWEI). It has been subjected to the Agency's peer and administrative review, and it
has been approved for publication as  an EPA  document. Mention of trade names or
commercial products does not constitute endorsement or recommendation for use.

-------
                               Foreword
    The SITE Program was authorized in the 1986 Superfund Amendments and Reautho-
rization Act (SARA). The program is administered by EPA's Office of Research and
Development (ORD). The purpose of the program is to accelerate the development and use
of innovative cleanup technologies applicable to Superfund and other hazardous waste
sites. This is accomplished through technology demonstrations designed to provide perfor-
mance and cost data on selected technologies.

    The SITE  Program funded a field demonstration to evaluate the ECO LOGIC Gas-
Phase Chemical Reduction Process,  developed by ELI Eco Logic International, Inc.,
Ontario, Canada.  The ECO  LOGIC Demonstration  took  place  at the Middleground
Landfill in Bay City, Michigan, using landfill waste; it assessed the technology's ability to
treat hazardous wastes, based on performance and cost. Three reports contain the results of
the demonstration: a Technology Evaluation Report (TER), which describes the field
activities and laboratory  results; this Applications Analysis  Report (AAR), which inter-
prets the data and discusses the applicability of the technology to liquid feedstocks; and a
second, independent AAR, which interprets the data and discusses the applicability of the
Thermal Desorption Unit  (TDU) to soil feedstocks.

    A limited number of copies of this report will be available at no charge from EPA's
Center for Environmental Research Information, 26 West  Martin Luther King Drive,
Cincinnati,  OH 45268 (513-569-7562). Requests  should include the  EPA document
number found on the report's front cover. When this supply is exhausted, additional copies
can be purchased from the National Technical Information Service, Ravensworth Bldg.,
Springfield,  VA  22161,  (703-487-4600). Reference copies will  be  available  at EPA
libraries in their Hazardous Waste Collection.  To inquire about the availability of other
reports,  call the  EPA Clearinghouse  Hotline at 1-800-424-9346 or 202-382-3000  in
Washington, DC.
                                       E. Timothy Oppelt, Director
                                       Risk Reduction Engineering Laboratory

-------
                               Abstract
    This report evaluates the capability of the ECO LOGIC Gas-Phase Chemical Reduc-
tion Process to detoxify organics in a liquid matrix. The report presents data from the
recent EPA SITE Demonstration of the reactor system, provides case studies, and evaluates
the costs of operating the system.

    The ECO LOGIC Reactor System  thermally separates organics, then chemically
reduces them in a hydrogen atmosphere, converting them to a reformed gas that consists of
light hydrocarbons and water. A scrubber treats the reformed gas to  remove hydrogen
chloride and particulates. Of this gas,  a portion recycles back  into the reactor;  the
remainder is either compressed for storage or feeds a propane-fired boiler prior to release
to the atmosphere. The reactor system produced two principal residual  streams: reformed
gas and scrubber effluent.

    The SITE Program evaluated the ECO LOGIC Process at the Middleground Landfill
in Bay City, Michigan. The reactor system processed 2.9 tons of wastewater and 0.2 tons of
waste oil, both contaminated with polychlorinated biphenyls (PCBs). The reactor system
demonstration revealed  that the process can  successfully treat both Toxic Substance
Control Act (TSCA) and Resource Conservation and Recovery Act (RCRA) hazardous
compounds. Although the reactor is not classified as an incinerator, stack emissions met
the TSCA destruction and removal efficiency  for PCBs and the RCRA destruction and
removal efficiency for tracer compounds,  which are specified in the respective incinerator
regulations. The system produced liquid effluent streams that may require further treatment
prior to publicly owned treatment works (POTW) processing.

    The ECO LOGIC Process is best suited to sites that contain oily liquid  wastes. Costs
fell in the range of $7.68/gal (60% utilization) to $6.41/gal (80% utilization) for liquid
feed. The ECO LOGIC Thermal Desorption Unit (TDU)/Reactor System Demonstration, a
proof-of-concept test that processed contaminated soil, is the topic of a second, indepen-
dent AAR.
                                       IV

-------
                                      Contents
Foreword	iii
Abstract	iv
Figures	vii
Tables	viii
Abbreviations	ix
SI Conversion Factors	xii
Acknowledgements	xiii
1.  Executive Summary	 1
    Introduction	 1
    The SITE Demonstration	 1
    Conclusions	 1
    Waste Applicability	2
    Costs	2
2.  Introduction	4
    The SITE Program	4
    SITE Program Reports	4
    Key Contacts	5
3.  Technology Applications Analysis	6
    Process Description	6
    Test Conditions	7
    Conclusions	8
    Technology Evaluation	9
        Organics Destruction	 10
        Air Emissions	 10
        Intermediate and Residual Stream Characterization	 12
        Equipment and Operating Considerations	 15
    Technology Applicability	 16
        Site Characteristics	 16
        Applicable Media	 16
        Safety Considerations	 17
        Staffing Issues	 17
    Regulatory Considerations	 17
        Clean Air Act	 17
        Clean Water Act	 17
        Comprehensive Environmental Response, Compensation, and Liability Act	 18
        Occupational Safety and Health Act	 18
        Resource Conservation and Recovery Act	 18

-------
                            Contents (Continued)
       Toxic Substances Control Act	 18
       State and Local Regulations	 18
    References	 18
4.   Economic Analysis	 19
    Introduction	 19
    Conclusions	 19
    Issues and Assumptions	 19
       Site-Specific Factors	 19
       Costs Excluded from the Estimate	20
       Utilities	20
       Supplies	20
       Operating Conditions	20
       Labor	20
       Basis for Economic Analysis	20
       Site Preparation Costs	20
       Permitting and Regulatory Costs	21
       Capital Equipment	21
       Mobilization and Start-up	22
       Operations Labor	22
       Supplies	22
       Utilities	22
       Effluents	22
       Residuals	22
       Analytical	22
       Repairs and Maintenance	23
       Demobilization	23
    Results of Economic Analysis	23
    References	23
Appendices
    A. Demonstration Sampling and Analysis	25
    B. Vendor's Claims	29
    C. Case Studies	36
                                             VI

-------
                                      Figures
1.       Gas-phase chemical reduction reactions	
2.       Reactor system and TDU schematic diagram
3.       The ECO LOGIC reactor	
A-l.    Sampling and monitoring stations	25
B-l.    ECO LOGIC process reactions	30
B-2.    Commercial-scale process reactor	31
B-3.    Commercial-scale process unit schematic	32
C-l.    Bench-scale reactor system schematic diagram	37
                                             VII

-------
                                        Tables
1.       Summary Results of Reactor System Tests	3
2.       MDNR Air Permit Conditions	 11
3.       Mass Distribution of Selected Streams	 12
4.       Component Partitioning	 13
5.       Reformed Gas Comparison to Other Fuels	 14
6.       Summary of Reactor Operating Conditions	 16
7.       Consumables Required by the ECO LOGIC Reactor Process	20
8.       Operating Labor	21
9.       Labor Costs Based on Utilization	21
10.      Demonstration Site Preparation Costs	21
11.      Capital Equipment for Commercial Operation	22
12.      Mobilization/Start-up Costs	23
13.      Cost Allocations	23
14.      Economic Analysis for the ECO LOGIC Reactor System	24
15.      Cost Extrapolations	24

A-l.    EPA Sample Locations	26
A-2.    ECO LOGIC Process Control Monitoring Stations	26
A-3.    Flue Gas Sampling and Analytical Methods	27
A-4.    Solids Sampling and Analytical Methods	27
A-5.    Liquids Sampling and Analytical Methods	28
B-l.    Hamilton Harbor Performance TestResults	33
B-2.    U.S. EPA SITE Program Results	34
B-3.    Summary of Test Results from the Lab-Scale Thermal Desorption Mill	35
C-l.    Sediment Samples	38
C-2.    Residue Streams	38
C-3.    Performance Results	38
C-4.    Waste Input and Effluent Analysis Components	40
C-5.    Characterization Test Air Sampling Components	41
C-6.    Air Emission Sampling Components	42
C-7.    Characterization Test Results	43
C-8.    Performance Test Results	44
                                              VIM

-------
                         Abbreviations
AAQ           ambient air quality
AAR           Applications Analysis Report
AAS           atomic absorption spectroscopy
ALR           analytical linear range
ASTM         American Society for Testing and Materials
BOC           beginning of condition
BOR           beginning of run
Btu/lbm        British Thermal Unit per pound mass
ARARs        applicable or relevant and appropriate requirements
C              carbon
CAA           Clean Air Act
CB            chlorobenzene
CEM           continuous emission monitor
CEMS         continuous emissions monitoring system
CERCLA       Comprehensive Environmental Response, Compensation, and Liability Act
cfm            cubic feet per minute
CFR           Code of Federal Regulations
CIMS          Chemical lonization Mass Spectrometer
Cl             chloride
C12            chlorine
CO            carbon monoxide
CO2            carbon dioxide
CP            chlorophenols
CVAAS        cold vapor atomic absorption spectroscopy
CWA          Clean Water Act
dP             pressure differential
DE            destruction efficiency
DOT           U.S. Department of Transportation
DRE           destruction and removal efficiency
dscm           dry standard cubic meter
dscf            dry standard cubic foot
                                      IX

-------
                Abbreviations (Continued)
ECO LOGIC    ELI Eco Logic International, Inc.
EPA           U.S. Environmental Protection Agency
EER           Energy and Environmental Research Corporation
FID            flame ionization detection
FPD           flame photometric detector
ft              feet
FWEI          Foster Wheeler Enviresponse, Inc.
g              gram
gal             gallon
GC            gas chromatography
GF             graphite furnace
gr             grains
gpm           gallons per minute
HR            high resolution
hr             hour
H2             hydrogen
HCB           hexachlorobenzene
HC1            hydrogen chloride
ICAP          inductively coupled argon plasma spectroscopy
in.             inches
kg             kilogram
Kw            kilowatt
L              liter
Ib              pound
m              meter
MASA         Method of Air Sampling and Analysis
MDNR         Michigan Department of Natural Resources
mg             milligram
min            minute
mo             month
MS            mass spectroscopy
NAAQS        National Ambient Air Quality Standards
NDIR          non-dispersive infrared
NDUV         non-dispersive ultraviolet
ng             nanogram
NOx           nitrogen oxides
NPDES         National Pollutant Discharge Elimination System
O2             oxygen
ORD           Office of Research and Development

-------
                 Abbreviations (Continued)
OSHA         Occupational Safety and Health Act
OSWER        Office of Solid Waste and Emergency Response
PAHs          polycyclic aromatic hydrocarbons
PCBs          poly chlorinated biphenyls
PCDD         polychlorinated dibenzo(p)dioxin
PCDF          polychlorinated dibenzofuran
PCE           perchloroethylene (tetrachloroethene)
pH             a measure of acidity/alkalinity
PICs           products of incomplete combustion
PIR            product of incomplete reduction
POHC         principal organic hazardous constituent
POTW         publicly owned treatment works
PPE           personal protective equipment
ppb            parts per billion
ppm           parts per million
ppmv          parts per million by volume
psi             pounds per square inch
psig           pounds per square inch gauge
QA            quality assurance
QI             quality indicator
RCRA         Resource Conservation and Recovery Act
RREL          Risk Reduction Engineering Laboratory
SARA         Superfund Amendments and Reauthorization Act
S              sulfur
sec             second
scf             standard cubic feet
scfm           standard cubic feet per minute
SITE           Superfund Innovative Technology Evaluation Program
SO2            sulfur dioxide
SVOC         semivolatile organic compounds
TCLP          Toxicity Characteristic Leaching Procedure
TDU           thermal desorption unit
TER           Technology Evaluation Report
THC           total hydrocarbons
TSCA          Toxic Substances Control Act
TSD           treatment, storage, and disposal
[ig             microgram
VOC           volatile organic compounds
VOST         volatile organic sampling train
WTC          Wastewater Technology Center
                                      XI

-------
SI Conversion Factors
Multiply
Area:

Flow rate:


Length:

Mass:

Volume:



Temperature:
Concentration:


Pressure:

Heating value:

English (US)
Units by
1ft2
lin.2
1 gal/min
1 gal/min
1MGD
1ft
lin.
lib
lib
1ft3
1ft3
Igal
Igal
°F-32
1 gr/ft3
1 gr/gal
1 lb/ft3
1 lb/in.2
1 lb/in.2
Btu/lb
Btu/scf
Factor
0.0929
6.452
6.31xlO-5
0.0631
43.81
0.3048
2.54
453.59
0.45359
28.316
0.028317
3.785
0.003785
0.55556
2.2884
0.0171
16.03
0.07031
6894.8
2326
37260
Metric (SI)
to get Units
m2
cm2
m3/s
L/s
L/s
m
cm
g
kg
L
m3
L
m3
°C
g/m3
g/L
g/L
kg/cm2
Newton/m2
Joules/kg
Joules/scm
          XII

-------
                     Acknowledgments
    Under EPA Contract 68-C9-0033, FWEI prepared this report for EPA's SITE Pro-
gram with the supervision and guidance of Gordon M. Evans, EPA SITE Program
Manager in the Risk Reduction Engineering Laboratory (RREL), Cincinnati, Ohio. The
FWEI Project Manager was  Gerard W.  Sudell;  James P.  Stumbar, Ph.D., provided
technical support; Marilyn K. Avery edited the document.

    Energy  and Environmental Research Corporation (EER)  provided sampling and
analytical support to EPA. Contracted to perform data analysis, data reduction, and
analytical review, EER provided the scientific data that form the sound basis for this report.

    Kelvin Campbell and  Craig McEwen  of ELI Eco Logic International provided
continued assistance throughout the project, as did Edward Golson of the City of Bay City.
Sue Kaelber-Mattock supported the project for the Michigan Department of Natural
Resources.
                                    XIII

-------
                                               Section  1
                                     Executive Summary
Introduction

This report summarizes the findings of the SITE Demonstra-
tion of the Gas-Phase Chemical Reduction Process developed
by ELI Eco Logic International, Inc. (ECO LOGIC) of Ontario,
Canada.

Under the auspices of the SITE Program, and in cooperation
with the City of Bay City, Michigan; Environment Canada;
and the Ontario Ministry of the Environment and Energy;
EPA conducted the demonstration of the ECO LOGIC Pro-
cess at Bay  City's Middleground Landfill. The  landfill ac-
cepted municipal and industrial wastes for approximately 40
years. A 1991 remedial investigation indicated elevated levels
in groundwater of trichloroethene, PCBs, 1,2-dichloroethene,
methylene chloride, toluene, and ethylbenzene. The ground-
water contained lesser  concentrations of benzidine, benzene,
vinyl chloride, chlorobenzenes, polycyclic aromatic hydrocar-
bons (PAHs), lindane, dieldrin, chlordane, and DDT metabo-
lites.

The patented ECO LOGIC Gas-Phase  Chemical Reduction
Process treats organic  hazardous waste in a  hydrogen-rich
atmosphere at approximately 900°C (1,650°F) and ambient
pressure to produce  a  reformed  gas. The reaction products
include hydrogen chloride from the reduction  of chlorinated
organics, such as PCBs, and lighter hydrocarbons, such as
methane and ethylene, from the reduction of straight-chain
and aromatic hydrocarbons. The absence of free oxygen in the
reactor inhibits  dioxin  formation. Water acts as  a hydrogen
donor to enhance the reaction.

A scrubber treats the reformed gas to remove hydrogen chlo-
ride and particulates. Of this gas, 95% recycles back into the
reactor; 5% feeds a propane-fired boiler prior to release to the
atmosphere. The recycle stream may be used as a fuel in other
system support  equipment, such  as the boiler  that generates
steam. The final combustion step in the boiler met the  RCRA
requirements, making the reformed gas environmentally ac-
ceptable for combustion.

The SITE Demonstration

The two-part demonstration took place in October and De-
cember  1992, using  PCB-contaminated oil, water, and  soil
extracted directly from the landfill. ECO LOGIC first per-
formed a  series of shakedown tests to establish optimum
system performance.  Two liquid tests investigated reactor
performance (Conditions 1 and 3); a soil test (Condition 2)
studied a complementary TDU, the topic of a second, inde-
pendent AAR. Each reactor test condition consisted of three
runs. The reactor program treated approximately 2.9 tons of
wastewater and 0.2 tons of waste oil. This report presents only
the results of the reactor tests. The program also conducted a
72-hour test to evaluate the reactor system reliability.

EPA collected extensive samples at points around the major
system components and stored or logged important data on
system operation and utility usage. Laboratory analyses pro-
vided information on the principal process streams: reactor
grit, scrubber residuals, reformed gas, and boiler stack emis-
sions. EPA evaluated these data against established program
objectives to determine the capability of the process to  treat
the designated waste.

Conclusions

Based on the program objectives, the demonstration  con-
firmed the feasibility  of the  gas-phase  chemical reduction
process for treating PCBs and other chlorinated organic com-
pounds, producing a fuel gas  from contaminated liquids and
providing environmentally acceptable air emissions.

In general, ECO LOGIC'S Reactor System  effectively de-
stroyed PCBs, reducing them to lighter hydrocarbons. Theo-
retically, the  destruction process could depend on both the
reactor system's gas  phase reduction reactions,  which pro-
duced the reformed gas, and on the propane/reformed gas-
fired boiler, a combustion device.

Although the result was not listed as a primary or secondary
objective for the demonstration, destruction and removal effi-
ciencies (DREs) for PCBs in the scrubbed reformed gas were
essentially equal to the DREs achieved at the boiler stack.
This shows that combustion of the reformed gas in the boiler
is not required to complete PCB destruction.

Stack emissions generally met stringent regulatory  levels.
However, average benzene concentrations in the  stack gas—
corrected to 7% oxygen—(Condition 1-73 jj^g/dscm; Condi-
tion 3-113 |j,g/dscm) and scrubber liquor (Condition 1-18.5
|J.g/L; Condition 3 - 347 |J,g/L) required close monitoring. The
reformed gas composition resembled coal-gas fuel. The scrub-
ber liquor required  either disposal as  a RCRA waste or

-------
recycling through the system for additional treatment. Table 1  independent AAR presents the results of the TDU (Condition
correlates the program conclusions with program objectives.   2) tests.

Waste Applicability                                 Costs

The SITE Program concluded that the ECO LOGIC Process  The 12 categories established for the SITE Program formed
efficiently treated liquid wastes containing oily PCBs, other  the basis for the cost analysis.  Costs  relate to the reactor
organics, and water containing PCBs,  other organics,  and  system, processing an average of 2.2 kg/min, as operated at
metals. Stack emissions met stringent regulatory levels.  The  the Middleground Landfill. Based on the economic analysis,
principal residual stream—the scrubber effluent—concentrated  the estimated cost  (1994 U.S.  dollars) for treating liquid
metals and some organics (benzene, PCBs, and PAHs), indi-  wastes similar to those at the Bay City site range from $2,0007
eating that  additional treatment might be  required prior to  ton (60% utilization factor) to $l,670/ton (80% utilization
disposal.                                                 factor). The most important element affecting cost is labor
                                                         (52% of cost), followed by site preparation (15%), supplies
The reactor did not directly process soil. Instead, ECO LOGIC  (12%), and start-up/mobilization (12%).
provided a complementary front-end TDU to treat soils. An

-------
Table 1.
             Summary Results of Reactor System Tests
              Objective
                                                  Not
                                           Met    Met
  Results


      Range
                                                                                                   Conclusions
Demonstrate ORE for PCBs: 99.9999%          X

Demonstrate DE for PCE: 99.99%               X

Ensure no formation  PCDD/PCDF               X


Characterize PIC emissions                    X
Characterize HCI emissions
Document MDNR air permit compliance
Characterize criteria air pollutants               X


Document TSCA permit compliance             X

Validate key cost assumptions                  X

Characterize effluents and residuals             X
Determine suitability of reformed gases
    for reuse/resale
Demonstrate system reliability
99.9999% to 99.99999%

99.99%

PCDD DE 63.05% to 98.36%
PCDF DE 99.91% to 99.98%

Benzene: 73 to 113 |ig/dscm
0.659 to 0.807 mg/dscm;
109.1 to 197.8 mg/hr;
99.98% removal

Benzene: 61  to 109 |ig/dscm
Throughput reliability: 20 to 55%
 of design. System availability: 24%
Good destruction.

Good destruction.

No net  PCDD/PCDF
formation.

PICs characterized;
benzene emissions
exceeded regulatory
limit.

Acceptable emissions.
Air permit compliance
documented; benzene
emissions exceeded
MDNR conditions.

Easily met permit
conditions.

Met permit conditions.

Cost elements identified.

Organics destroyed;
metals partitioned to
scrubber effluents;
after further treatment,
scrubber liquor may
be suitable for POTW.

Closely matched
composition of other
commercial fuel gases.

Process reliability
requires improvement.
Develop mass balances



Characterize scale-up parameters

Validate CIMS



Document system operation
                                       Generally good closures,
                                       except for certain
                                       metals.

                                       Characterized.

                                       May reflect data trends
                                       useful  for process
                                       control.

                                       Data available for
                                       commercial scale-up.

-------
                                               Section  2
                                             Introduction
The SITE Program

In 1986 EPA's Office of Solid Waste and Emergency Re-
sponse (OSWER) and ORD established the SITE Program to
promote the development and use of innovative technologies
to clean up Superfund sites across  the country. Now in its
eighth year, SITE is helping to commercialize the treatment
technologies necessary to meet new federal and state cleanup
standards aimed at permanent  remedies, rather than short-
term corrections.  The SITE Program includes four major
elements: the Demonstration Program, the Emerging Tech-
nologies Program, the Measurement and Monitoring Tech-
nologies Program, and the Technology Transfer Program.

The  major  focus has been on the Demonstration Program,
designed to provide engineering  and cost data on selected
technologies. EPA and the technology developers that partici-
pate  in the program share the cost of the demonstration.
Developers are responsible for demonstrating their innovative
systems, usually at Superfund sites selected by EPA. EPA is
responsible for sampling, analyzing, and evaluating test re-
sults. The  outcome is an assessment of the  technology's
performance, reliability,  and cost. This information, used in
conjunction with other data, enables EPA and state decision
makers to select the most appropriate technologies for Super-
fund cleanups.

Innovative technology developers apply to participate in the
Demonstration Program by responding to EPA's annual so-
licitation. EPA will consider a  proposal at any time from a
developer who has scheduled a treatment project on Super-
fund waste. To qualify for the program, a new technology
must have a pilot- or full-scale unit and offer some advantage
over existing technologies. Mobile technologies are particu-
larly interesting.

Once a proposal has been accepted, EPA and the developer
work with  the EPA regional offices  and state agencies to
identify a site containing wastes suitable for testing the tech-
nology. EPA prepares a detailed sampling and analysis plan
designed to thoroughly evaluate the technology by providing
analysts with reliable data. A demonstration may last any-
where from a few days to several months, depending on the
process and the quantity  of waste needed to assess the tech-
nology. Ultimately,  the  Demonstration Program rates the
technology's overall applicability to Superfund problems.
The second major element of the SITE Program is the Emerg-
ing Technologies Program, which fosters the further investi-
gation and development of treatment technologies that are still
at laboratory scale. Successful validation of these technolo-
gies could lead to the development of systems viable for field
demonstration. A third component of the SITE Program, the
Measurement and Monitoring  Technologies Program, pro-
vides assistance in the development and  demonstration of
innovative technologies that will better characterize Super-
fund sites. The Technology Transfer component ensures ef-
fective dissemination  of the results of the  demonstration
projects.

SITE Program Reports

Two documents incorporate the  results of each SITE Demon-
stration: the TER and the AAR.  The TER contains a compre-
hensive description of the demonstration and its  results. This
report assists engineers who are performing a detailed evalua-
tion  of the technology for a specific  site and waste. The
technical evaluations provide a detailed understanding of the
technology performance during  the demonstration and assess
the advantages, risks, and costs for a given application.

The AAR estimates Superfund applications  and technology
costs, based on available data.  It compiles design and test
data,  summarizes them, explores other laboratory and field
applications, and discusses the advantages, disadvantages,
and limitations of the technology.  The AAR  attempts to
synthesize available information and draw reasonable conclu-
sions  for the technology's use.  The report discusses factors
such as site and waste characteristics that have a major effect
on costs and performance. Pilot- and full-scale operations data
provide the bases for estimating technology costs for different
applications.

The amount of available data needed to evaluate an innovative
technology varies widely. Data  may be limited to laboratory
tests on synthetic waste or may extend to performance data on
actual wastes treated in the field at the  pilot or full scale. In
addition, conclusions regarding Superfund applications drawn
from a single field demonstration have limitations. A success-
ful field  demonstration does not necessarily ensure  that a
technology will become widely applicable or attain full devel-
opment at the commercial scale.  The AAR can assist remedial
managers in planning  Superfund cleanups; it represents an

-------
important tool in the development and commercialization of          James Nash
the technology.                                                 ELI Eco Logic International, Inc.
                                                              143 Dennis St.
Key Contacts                                              Rockwood, Ontario NOB 2KO
                                                              Canada
The sources listed below can provide additional information          Phone: 519-856-9591
concerning the SITE Demonstration, the site, or the ECO          Fax: 519-856-9235
LOGIC Gas-Phase Chemical Reduction Process.

        Gordon M. Evans
        SITE Project Manager
        U.S. Environmental Protection Agency
        26 W Martin Luther King Drive (MS-215)
        Cincinnati, OH 45268
        Phone: 513-569-7684
        Fax: 513-569-7620

-------
                                              Section  3
                       Technology  Applications  Analysis
This AAR assesses the capability of the ECO LOGIC Process
to treat liquids contaminated with PCBs and other hazardous
substances. EPA has based the assessment on the results of the
SITE Demonstration and on data supplied by the technology
developer. The report contains a summary of relevant material
from the more detailed TER. Since the results of the demon-
stration that are provided in the TER are of known quality, the
report bases its conclusions on them.

Appendix  A describes the demonstration sampling and ana-
lytical locations/methods; Appendix B, ECO LOGIC'S claims
for  the  technology; and Appendix C,  case studies of the
technology's application.

Process Description

The patented ECO LOGIC Gas-Phase Chemical Reduction
Process treats organic hazardous  waste in a hydrogen-rich
atmosphere at approximately 900°C (1,650°F)  and ambient
pressure, producing a reformed gas. Water acts as a hydrogen
donor to enhance the reaction.  The reaction products include
HC1, from the reduction of chlorinated  organics,  such as
PCBs, and lighter hydrocarbons, such as methane and ethyl-
ene from the reduction of straight-chain and aromatic hydro-
carbons. A scrubber treats the reformed gas to remove hydro-
gen chloride and particulates. Of this gas, a portion recycles
back into the reactor; the remainder is either compressed for
storage or feeds a propane-fired boiler prior to release to the
atmosphere. The absence of free oxygen in the reactor inhibits
dioxin formation.

Figure 1 shows some of the reactions that lead to the major
intermediate and final products. Through hydrogenation, the
first five reactions remove chlorine from PCBs and reduce the
higher molecular weight hydrocarbons to simpler, more satu-
rated compounds. The final reaction regenerates hydrogen.

Figure 2 illustrates the process in a schematic diagram of the
field demonstration unit. The demonstration-scale reactor (Fig-
ure  3) was 2 m (6 ft) in diameter and 3 m (9 ft) tall, mounted
on a 15 m (45 ft) drop-deck trailer. The trailer carried  a
scrubber system,  a recirculation gas system, and an electrical
control center. A second trailer held a propane boiler, a waste
preheating vessel, and a waste storage tank.

ECO LOGIC designed the process to treat 4 tons/day of waste
oil,  10 tons/day of wastewater, and 25 tons/day of soil, de-
pending on the nature of the contaminants, their degree of
chlorination, and their water content. The ECO LOGIC TDU—
designed to remove most volatile, most semivolatile,  and
some metallic contaminants—treats the soil. The TDU is the
subject of an independent AAR.

For the demonstration, a heat exchanger evaporated contami-
nated aqueous feedstock to  form steam and  a concentrated
heated liquor. Atomizing nozzles sprayed the heated liquor,
with associated particulates, into the reactor. A separate pump
sent PCB-rich oils directly to the reactor through other atom-
izing nozzles.  Compressed  hydrogen-rich recirculation gas
passed through a gas-fired heat exchanger and entered the top
of the reactor tangentially. The tangential entry swirled the
fluids to provide effective mixing. As indicated in Figure 3,
the swirling mixture traveled downward in the annulus formed
by the reactor wall and the central ceramic-coated steel tube,
past electrically heated bars.  These bars heated the mixture to
900°C  (1,650°F).  At the bottom of the  reactor the mixture
entered the tube, reversed direction, and flowed upward to the
outlet of the reactor. The reduction reactions occurred as the
gases traveled from the reactor inlets to the scrubber inlet.

After quenching, the gases flowed through a scrubber where
contact with water removed hydrogen chloride and fine par-
ticulates. A large water-sealed vent, acting as an emergency
pressure relief duct, passed scrubber water to a tank below. A
pump recirculated the scrubber water in a loop through an
evaporative cooler to reduce its temperature to 35°C (95°F).
Caustic  and make-up  water, added to the scrubber liquor,
maintained  HC1 removal efficiency. The scrubber produced
two effluent streams: sludge and decant water.

The reformed gas  exiting the scrubber contained excess hy-
drogen, lighter hydrocarbon reduction products such as meth-
ane and ethylene, and a small amount of water vapor. A
portion  of this hydrogen-rich gas was  reheated to 500°C
(930°F) and recirculated back into the reactor; the remainder
of the gas served  as supplementary fuel for a propane-fired
boiler. The boiler produced steam used in the  heat exchanger
and burned the reformed gas, which was the only air emission
from the process.

When treating  wastes containing highly concentrated organ-
ics, the process generates excess  reformed gas.  The system
can compress the reformed gas and store it for later use as fuel
in other parts of the process.

-------
                                         5H2
                  PCB
                        Benzene
                                      +   4HC!
                  Hydrogen
                   Chloride
             Polycyclic Aromatic
               Hydrocarbons
                                         3H2
               (Phenanthrene)
                        Benzene
                                      +   C2H4
                    Ethylene
                                     +   9H2
                  Benzene
                      9CH4
                      Methane
                   C2H4
2H2
2CH4
                  cnH(2n+2)
                  Straight-Chain
                  Hydrocarbons
(n-1)H2
                      Methane
                     CH4
H2O
  CO
+   3H2
Figure 1.    Gas-phase chemical reduction reactions.
Test Conditions

In preparation for the SITE Demonstration, ECO LOGIC first
adjusted the  system to obtain peak performance, then per-
formed a tracer material pretest to adjust sampling equipment
and trains. Two test runs (Conditions 1 and 3) followed over
the next 17 days. Condition 1 treated 2.9 tons of wastewater
contaminated with 3,757 ppm PCBs and 3,209 ppm perchlo-
roethylene (PCE)  (tracer). Condition 3 treated 0.2 tons of
waste oil contaminated with 25.4% (254,000 ppm) PCBs and
6,203 ppm PCE.
              The ECO LOGIC SITE Demonstration objectives were as
              follows:

               •  Demonstrate at least 99.9999% ORE for PCBs.
               •  Demonstrate at least 99.99% destruction efficiency (DE)
                  for PCE in the liquid feedstock.
               •  Ensure that no dioxins or furans were formed.
               •  Characterize emissions from products of incomplete com-
                  bustion (PICs).
               •  Characterize HC1 emissions.

-------
                N2-
                H2-
                                                                             Recirculating Gas
Propane  Exhaust     900°^
                                                              Scrubt
                                                                    er
35°C
                                                                                       Gas
                                                                                       Booster
                                                                                               Hydrocarbon
                                                                                                   Gas
                                                                                                Propane
      Thermal
   Desorption
Figure 2.     Reactor system and TDU schematic diagram.
 •  Document compliance with Michigan Department of Natu-
    ral Resources (MDNR) air permit conditions.
 •  Characterize criteria air pollutant emissions.
 •  Document compliance with TSCA permit requirements.
 •  Validate key cost assumptions used in process economic
    analyses.
 •  Characterize effluents and residual streams relative to
    disposal requirements.
 •  Determine the suitability of the reformed gases for reuse/
    resale.
 •  Demonstrate system reliability.
 •  Develop a system mass balance, including metals.
 •  Characterize critical process scale-up parameters.
 •  Validate  the ECO LOGIC  Chemical lonization Mass
    Spectrometer (CIMS).
 •  Document system operation during test runs.

Conclusions

Based on the program objectives, EPA found that the demon-
stration confirmed the feasibility  of the  gas-phase chemical
reduction process for treating PCBs and other chlorinated
organic compounds, producing a low Btu fuel gas from con-
taminated liquids and providing environmentally acceptable
air emissions.
                                 In general,  ECO LOGIC'S Reactor System effectively de-
                                 stroyed PCBs, reducing them to lighter hydrocarbons. Theo-
                                 retically, the destruction process could depend on both the
                                 reactor system's gas phase reactions, which produced the
                                 reformed gas, and on the propane/reformed gas-fired boiler, a
                                 combustion device.

                                 Although the result was not listed as a primary or secondary
                                 objective for the demonstration, DREs for PCBs in the scrubbed
                                 reformed gas were essentially equal to the DREs achieved at
                                 the boiler stack.  This shows that combustion of the reformed
                                 gas in the boiler is not required to complete PCB destruction.

                                 Stack emissions generally met stringent regulatory levels.
                                 However, average benzene concentrations in the stack gas—
                                 corrected to 7%  oxygen—(Condition 1-73 u.g/dscm; Condi-
                                 tion 3-113  u.g/dscm) and scrubber liquor (Condition 1-18.5
                                 u.g/L; Condition 3 - 347 u.g/L) required close monitoring. The
                                 reformed gas composition resembled coal-gas fuel. The scrub-
                                 ber liquor required either disposal as a RCRA waste,  or
                                 recycling through the system for additional treatment. Table 1
                                 (Executive Summary) correlates the program conclusions with
                                 program objectives.

-------
                                                                       To Scrubber
                                                                 Waste Injection Ports

                                                                 Reactor Steel Wall

                                                                 Fibreboard Insulation

                                                                 Refactory Lining

                                                                 Electric Heating Elements

                                                                 Ceramic-coated Central
                                                                 Steel Tube
                                >'
                            To Grit Box
Figure 3.     The ECO LOGIC reactor.
Technology Evaluation

The demonstrated ECO LOGIC Gas-Phase Chemical Reduc-
tion Process is a pilot or small commercial-scale, trailer-
mounted system, capable of treating wastewater and waste oil.
The SITE Demonstration of the reactor system consisted of
initial shakedown runs, a blank run to determine train capaci-
ties, and six liquid runs (Conditions 1 and 3). An independent
AAR discusses the TDU (Condition 2) demonstration results.

A liquid pool of waste within the Middleground Landfill
provided feedstock for the tests. Test Condition 1 treated 1.73
kg/min (totalling 2.9 tons) of wastewater containing 3,757
ppm PCBs. Condition 3 treated 0.385  kg/min (totalling 0.2
tons) of waste oil containing 25.4% (254,000 ppm) PCBs.
PCB concentrations were sufficient to calculate the DREs.
PCE added to the feedstock at levels of 3,209 and 6,203 ppm
respectively, served as a tracer to determine DEs. Additional
feedstock contaminants included fluoranthene, naphthalene,
phenanthrene, other PAHs, chlorobenzene, chlorophenol, me-
thyl chloride, tetrachlorethene, toluene, and various metals.

Based on the SITE test data—covered in detail in the TER—
analysts assessed the applicability of the ECO LOGIC Process
to the test wastes, as summarized in Table 1  and as discussed
in the following paragraphs.

-------
Organics Destruction
Dioxins and Furans
To  determine the efficiency of organics destruction, EPA
evaluated DREs and DEs, benzene ring destruction, and for-
mation of dioxins, furans, and other PICs.

ORE

DRE  compares the mass flow  rate of selected feedstock
compounds—in this case PCBs—to their mass flow rate in the
boiler stack gas.

        DRE (%) = ( 1 - Massstack / Massmput) x 100

Whenever possible, the evaluation based DRE calculations on
actual detected values. When the value was below the detec-
tion limit for the method, input stream values were set at zero,
while output streams were set at the detection limit value—the
most conservative approach.

The ECO LOGIC Reactor Process achieved PCB destruction
at the boiler stack ranging from 99.9999% to 99.99999%. This
met established TSCA DRE requirements, potentially  quali-
fying the process for use as a PCB treatment device. (Other
TSCA requirements affecting residuals, stack emissions, and
paniculate emissions must also  be  considered.) The SITE
Program results, supported by ECO  LOGIC'S laboratory-
scale tests and results from their Hamilton Harbor Test (Ap-
pendix C) provide evidence of acceptable PCB  destruction at
the  stack.
DE
DE is a measure of the system's ability to achieve organics
destruction as  measured around the  system  and all output
streams.

        DE (%) = ( 1 - Mass^ / Massmput)  x 100

PCE added to  the feedstock acted as a tracer compound to
calculate DEs; the system achieved  the target objective—
99.99%—for this tracer.

Benzene concentrations in the  output streams were higher
than expected.  In scale-up, ECO LOGIC must address ben-
zene concentrations in residual and effluent streams, since
high benzene concentrations  can affect the  costs of waste
disposal.

The  DRE and DE results indicate that the ECO LOGIC
Reactor System—with boiler—can achieve RCRA hazardous
waste incinerator DEs (99.99% measured at the boiler stack)
for most organic compounds.  ECO LOGIC'S lab-scale tests,
their Hamilton Harbor test on sediment contaminated with
PAHs (Appendix C), and the SITE Demonstration test of the
ECO LOGIC TDU, discussed in an independent AAR, further
support this conclusion. Assuming that scale-up factors main-
tain the same DE, a commercial-scale system would meet
RCRA emissions criteria.
The ECO LOGIC Process reduces organics in a high-tempera-
ture  hydrogen environment, as opposed to combustion by
incineration in an oxygen environment. The absence of oxy-
gen inhibits formation of polychlorinated dibenzo(p)dioxin/
polychlorinated dibenzofuran (PCDD/PCDF). Although veri-
fying the reduction mechanisms inside the reactor was not an
objective of the demonstration, the test confirmed a net de-
struction at the stack of trace PCDD/PCDF in the  feedstock.
Stack emissions (corrected to 7% oxygen, dry basis) ranged
from 0.156 to 0.368 ng/dscm dioxin and 0.007 to 0.011 ng/
dscm furan—results well within incineration regulatory guide-
lines. The low PCDD/PCDF stack concentrations support the
conclusion that the  system can  effect  a net PCDD/PCDF
destruction, resulting in PCDD/PCDF stack emission concen-
trations significantly lower than current limits.

PICs

"PICs" is an incineration term not directly applicable to the
ECO LOGIC  Process. The term  describes a combustion
system's ability to degrade feedstock organics. In  a combus-
tion  system  the  final  gaseous products are ideally  water,
carbon dioxide, and hydrogen chloride; other organic com-
pounds are PICs. The ECO LOGIC Process products are more
appropriately termed products of incomplete reduction (PIRs).
The process generates  both PIRs during the gas-phase reac-
tions and PICs during the reformed gas combustion phase.
Both terms are used here to facilitate comparisons between
the emissions from combustion devices and those from the
ECO LOGIC Process.

Incineration processes often select total hydrocarbons (THC),
carbon monoxide (CO), total PAHs, and benzene as indicators
of PIC/PIR formation.  For the  ECO LOGIC Reactor System
tests, the three indicators—THC,  CO, and total PAHs—were
much lower than regulatory guidelines  and well  within the
MDNR permit conditions. THC averages ranged from 1.53 to
15.5  ppmv, CO from 2.3 to 23.3 ppmv, and total PAHs from
24.0  to 28.6 j^g/dscm (all corrected to 7% O2,  dry basis). The
remedial manager can expect that the ECO LOGIC system
will meet anticipated permit limits  for THC, CO, and PAH
emissions at other sites.

Benzene, ranging from 73 to 113 |^g/dscm, exceeded both the
MDNR permit guidelines and allowable air emission concen-
trations.  A benzene ring balance,  calculated at  the stack,
ranged from 80 to 96% DE. This DE did not reduce benzene
concentrations to acceptable levels in the stack gas  and scrub-
ber effluent. Because benzene is a major intermediate product
in the reduction of PAHs and PCBs, high benzene concentra-
tions probably formed as these high molecular weight com-
pounds  degraded. Benzene  is a by-product  of the normal
combustion process; this may have further increased stack
emission concentrations. The remedial manager should closely
monitor benzene levels.

Air Emissions

EPA evaluated emissions of criteria air pollutants and HC1, as
well  as compliance with the MDNR air permit.
                                                       10

-------
Criteria Air Pollutants

During the tests, continuous emission monitors (CEMs) mea-
sured the concentrations of the criteria air pollutants at the
stack: nitrogen oxides (NOx), sulfur dioxide (SO2), particu-
lates, THC, and CO. Each of these pollutant emission concen-
trations was  low,  well under the  level established in the
MDNR air permit. NOx averages ranged from 60.8 to 63.5
ppmv; SO2, from 1.4 to 2.2 ppmv; particulates, from 0.17 to
0.99 mg/dscm; THC, from 1.53 to 15.5 ppmv; and CO, from
2.3 to  23.3 ppmv  (all corrected to 7% O2,  dry basis). The
system can be  expected to achieve similar results at  other
sites.

The  demonstration-scale boiler operated between high and
low fire, depending on the  system's steam requirements. The
test  analyses showed out-of-range spike concentrations  of
THC and CO (indicators  of combustion efficiency) during
low-fire operation,  most notably in Condition 1, Run 1 when
the boiler was cycling between high and low fire. Future users
must be alert to the potential for decreased combustion effi-
ciency and increased emissions of criteria air pollutants dur-
ing low-fire operation. The boiler should be operated at firing
rates and air/fuel ratios that prevent these spikes. Since the
DREs were adequate in the scrubbed reformed gas, reduced
combustion efficiency in the boiler will not affect the ability
of the reactor process to destroy hazardous organics.

HCI

The ECO LOGIC Reactor System reduced stack HCI emis-
sions to below the MDNR-permitted levels. RCRA emission
limits set incinerator HCI emissions at 4 Ib/hr (or less), or 99%
removal. The reactor  system  easily  achieved this—average
stack concentrations ranged from 0.66 mg/dscm at 109 mg/hr
to 0.81 mg/dscm at 198 mg/hr. Removal efficiencies reached
99.98%. Most of the chlorine in the feedstock accumulated in
the scrubber effluent.

MDNR Permit Compliance

Table 2 compares the test results to the conditions imposed by
the MDNR air permit.  Of the 15  permit criteria, only benzene
stack  concentrations exceeded the permit criteria. However,
the total quantity of emitted materials is low,  probably lower
than levels that normally present health risks to exposed
populations.  For future commercial units, a taller stack might
resolve this  problem;  greater dispersion could allow  less
Table 2.
            MDNR Air Permit Conditions
    Parameter
                                       Unit
                                                               Permit limit
                                                                                           Program average
HCI (7% 02, dry basis)
THC as methane
(7% O2, dry basis)
CO (7% O2, dry basis)
PCBs (dry basis)
Benzene (dry basis)
Chlorobenzenes as
1 ,2,4-trichlorobenzene (dry basis)
Opacity
Scrubber inlet temperature
Scrubber solution
On-line mass spectrometer
Reactor temperature
Reactor pressure
System oxygen
Gas booster dP
Recirculation flow rate
mg/dscm
Ib/hr
ppmv
Ib/hr
ppmv
Ib/hr
mg/dscm
Ib/hr
|ig/dscm
Ib/hr
|ig/dscm
Ib/hr
%
°C
PH
Yes/No
°C
in. H2O
%
in. H20
cfm
5.2
0.027
200
0.19
100
0.15
0.09
0.00048
20
0.00009
1
0.000002
0
>35
>8
Yes
>850
<10
O.04
<16
100
<0.67
<0.00034
5.5
0.0016
11.0
0.0059
0.00060
3.3E-07
65
>0.000034
(ND) O.88
4.3E-07
0
520
8.9
Yes
907
1.97
0.045
9.57
110
ND   Not detected.
BQL  Detected below the quantitation limit.
<    Emission rate is less than the mass indicated. The mass indicated assumes that the substance is present at the detection
                                 limit.
                                                        11

-------
restrictive stack concentrations. However, benzene emissions
could potentially exceed permit levels at other sites. Scale-up
designs should address these problems.

Intermediate and Residual Stream
Characterization

Intermediate and residual stream evaluations provided pro-
cess mass balance data; major effluent, intermediate process,
and miscellaneous stream characterizations; and confirmation
of adherence to TSCA permit conditions. Table 3 presents the
mass distribution of the waste feed and effluent streams as
fractions of the total waste feed. The waste oil was the major
waste input stream, containing the greatest mass of PCBs. The
major effluent streams were the stack gas and scrubber decant.
Most of the material in these streams entered the process
through combustion air and process water. Boiler combustion
air contributed most of the mass to the stack gas stream;
scrubber water, to the scrubber decant stream.

Table 4 shows the concentration of the major contaminants in
the intermediate and effluent streams. These data indicate the
tendency  of contaminants to concentrate in the intermediate
and residual streams.

Process Mass Balance

The test objectives included a system mass balance for metals,
carbon, hydrogen, oxygen, sulfur, chlorine, and total mass.
These balances were needed to evaluate system performance
and to  determine the fate of metals and other compounds in
the feedstock.

The program established a value of 0 + 50% (deviation from
perfect closure) as the quality indicator (QI) of mass balance.
Total mass balance closures ranged from -4.3 to +20.1%,
indicating that data based on process mass balances (such as
DRE, DE, and stack emission rates) can be considered very
reliable. Carbon, chlorine, hydrogen, oxygen, and sulfur mass
Table 3.
            Mass Distribution of Selected Streams
Material quantity*
Stream
Input
Wastewater
Waste oil
Residual/output
Reactor grit
Scrubber sludge
Scrubber decant
Scrubber liquor
Compressed tank
condensate
Stack gas


SS1
SS2

SS11
SS12
SS13
SS22
SS15
SS16
Condition
1

0.984
0.016

0.001
0.032
1.097
0.122
N/A
0.738
Condition
3

0.781
0.219

0.001
0.172
3.659
0.005
0.002
0.980
*kg material per kg total feed.
balance closures ranged from -41 to +29.1%. Only the hydro-
gen in Condition 1 (-53.8%) and sulfur (+129%) and carbon
(+98%) in Condition 3 exceeded the QI criterion. Therefore,
the elemental mass balances further support DRE, DE, and
partitioning data reliability.  Closure of the metals balances,
typically  difficult to achieve in any system, ranged widely
(from -153 to +175%). However, metal balance closures are
of less concern than metals partitioning and their concentra-
tions in residual streams.

Reactor Streams

The reactor system demonstration evaluated an intermediate
stream—the  reformed gas exiting the scrubber, and  three
major residual streams: reactor grit; scrubber residuals con-
sisting of sludge, decant, and liquor; and stack gas emissions.
It  also analyzed miscellaneous streams, and compared the
TSCA permit conditions to  residual stream analyses. Stack
gas emissions have already been discussed in the section on
air emissions.

Intermediate Process Streams

Table 5 compares the reformed gas composition to  several
commercially available fuels. The scrubbed reformed gas was
similar to blue water gas; its quality could be adequate to burn
in suitable combustion equipment during commercial-scale
operations. Use of the reformed gas in cogeneration or other
equipment to support the remedial operation could improve
the economics of large-scale applications.  Although the re-
formed gas was of commercial quality,  it would be a specialty
fuel requiring burners tailored to its properties. Compressing
and storing the reformed gas for resale or future use would
probably  be  uneconomical. Unlike propane, the compressed
reformed gas needs cryogenic temperatures to liquify. There-
fore, storage as a gas would require excessively large tanks.

Residual  principal organic hazardous  constituents (POHCs)
and PIRs may affect the end use of the gas. As previously
discussed, PCB DEs measured for the scrubbed reformed gas
were essentially equal to the DEs measured at the boiler stack.
This was also true for the PCE DEs, with the exception of two
Condition 3 runs. The measured PCE DE in the reformed gas
was an order of magnitude lower than that measured at the
boiler stack. Run 1 and Run 3 achieved 99.988% and 99.97%
DEs of PCE in the reformed gas, slightly below the 99.99%
target level for this tracer compound. The DE levels demon-
strated for the chlorinated organic compounds indicate that a
commercial-scale system can  achieve consistent  DEs of
99.99%.

Benzene  was the most prevalent PIR in the reformed  gas.
Benzene concentrations ranged between 522 and 1,780 mg/
dscm. PAHs were not measured. However, as shown in Table
4,  the  combustion step in the  boiler  destroys most of the
residual benzene. PAH emissions from the boiler stack also
were low. The reformed gas is generated from a hazardous
waste, presenting a further difficulty in its utilization as a fuel
outside of the process. However, the results of the demonstra-
tion show that burning the reformed gas in combustion equip-
ment would adequately destroy any residual hazardous organ-
ics.
                                                       12

-------
Table 4.
            Component Partitioning
                                                                     Stream (ppb)*
Component
Total PCBs (mono-deca)
Total PAHs
Total PCDD/PCDF
Total chlorobenzenes
Total chlorophenols
Benzene
PCE
Condition
1
3
1
3
1
3
1
3
1
3
1
3
1
3
SS1
Waste-
water
22.8
25.2
ND
24.8
0.00054
1.57
ND
ND
ND
ND
3.71
8.7
21
4.3
SS2
Waste
Oil
2.38E+08
2.54E+08
320,400
366,000
327
393
253,500
235,000
ND
ND
31
ND
ND
ND
SS11
Reactor
Grit
2,160,000
3,310
655,000
846,000
0.179
162
ND
ND
ND
ND
430
17.0002
ND
ND
SS12
Scrubber
Sludge
15,490
17,665
12,800,000
40,700,000
4.03
1.92
ND
ND
ND
ND
ND
ND
ND
ND
SS13
Scrubber
Decant
203
40.6
6,640
15,200
0.00063
0.00013
ND
ND
ND
ND
7,160
7.7002
ND
41
Component
Total PCBs (mono-deca)
Total PAHs
Total PCDD/PCDF
Total chlorobenzenes
Total chlorophenols
Benzene
PCE
Condition
1
3
1
3
1
3
1
3
1
3
1
3
1
3
SS22
Scrubber
Liquor
31.5
48.9
2,697
20,300
0.0004
0.001
ND
ND
ND
ND
18.5
347
ND
7
SS14
Reformed
Gas3
2.84
32.6
N/A
N/A
0.00021
0.000162
ND
ND
ND
ND
521 ,6002
1,781,000
8.89
2,481
SS15
Tank
Condensate
N/A
16,800
N/A
6,420,000
N/A
ND
N/A
ND
N/A
ND
N/A
81 92
N/A
7.751
SS18
Heat
Exchanger
8.67
10.79
5.25
43.84
0.00021
0.00053
ND
ND
ND
ND
9.3
120
ND
ND
SS16
Stack3
0.21
1.23
28.74
24.044
0.0004
0.0002
ND
ND
ND
ND
73.1
113
3.85
4.51
1   Compound(s) detected at concentrations below the quantitative limit.
2   Compound detected at concentrations above the linear range for analysis.
3   Concentration given as |ig/dscm.
4   Essentially naphthalene.
ND Not detected.
*   Averages of three runs, including NDs.
Major Residual Streams

Reactor Grit—The first test ran revealed that the reactor grit
volume was small enough for exclusion as an effluent stream.
Any accumulation can be either recycled or stored for permit-
ted disposal after the treatment program.

Considering only PCB congeners that  have three or more
chlorine atoms (as  defined by TSCA),  PCB concentrations
detected in the grit ranged from 1.67 to 2,100 ppm. A conge-
ner consists of all PCB compounds having the  same number
of chlorine atoms but arranged in different positions for any
individual congener compound.  The grit from Condition 1
exceeded the 2 ppm (per congener) TSCA criterion. If mono-
chlorobiphenyls, dichlorobiphenyls, and nondetected conge-
ners (assumed to be present at the detection  level) are in-
cluded, the grit could contain maximum PCB concentrations
between 3.3 and 2,160 ppm. These concentrations could af-
fect the DE if the grit  is considered a process output  rather
than a recycled stream. However, at the commercial-scale,
ECO  LOGIC  plans to recirculate this  stream through the
reactor.
                                                         13

-------
Table 5. Reformed Gas Comparison to Other Fuels

Gaseous
Fuels H2
ECO LOGIC Condition 1 41.1
reformed gas Condition 3 55.7
Blast furnace gas 1 .0
Blue water gas 47.3
Carburated water gas 40.5
Coal gas 54.6
Coke-oven gas 46.5
Natural gas (15.8% C2H6) —
Producer gas 14.0
Gaseous
Fuels
ECO LOGIC Condition 1
reformed Gas Condition 3
Blast furnace gas
Blue water gas
Carburated water gas
Coal gas
Coke-oven gas
Natural gas (15.8% C2H6)
Producer gas
Composition, percent by volume
N2
33.7
13.7
60.0
8.3
2.9
4.4
8.1
0.8
50.9
MW
16.7
11.6
29.6
16.4
18.3
12.1
13.7
18.3
24.7
02 CH4
0.05 12.2
0.06 16.9
— —
0.7 1.3
0.5 10.2
0.2 24.2
0.8 32.1
— 83.4
0.6 3.0
HHV
Btu/lbm
6,250
12,610
1,170
6,550
1 1 ,350
16,500
17,100
24,100
2,470
CO C02
5.1 6.7
8.0 3.3
27.5 11.5
37.0 5.4
34.0 3.0
10.9 3.0
6.3 2.2
28.0 4.5
HHV
Btu/scf
269
376
89
277
535
514
603
1,136
157
C2H4 C6H6
0.4 —
0.7 —
— —
— —
6.1 2.8
1.5 1.3
3.5 0.5
— —
Sp. gr.
air = 1.0
0.58
0.54
1.02
0.57
0.63
0.42
0.47
0.63
0.85
MW  Molecular weight
HHV  Higher heating value
Sp. gr. specific gravity compared to air at 60°F
The  grit also  contained PAH  levels exceeding 846 ppm,
benzene levels up to  17  ppm, and PCDD/PCDF reaching
0.162 ppm. Chlorobenzenes, chlorophenols, and PCE were
not detected.

Scrubber Residuals—The scrubber is a critical component
in the gas-phase chemical reduction process. The scrubber
effectively removes a variety of organic and metallic com-
pounds, particulates, and  chlorides. It is a key element in
achieving DREs. Table 4 shows elevated levels of hazardous
organic  compounds in the scrubber sludge—mainly PAHs,
with lesser concentrations of PCBs and PCDD/PCDF. If this
sludge is not recycled through the process,  it must be treated
as a TSCA and RCRA hazardous waste.

Based on detected PCB congeners, the PCB concentrations in
the scrubber decant (40.6 to 203 ppb total) and scrubber liquor
streams (31.5 to 48.9 ppb total) met the TSCA criterion of less
than 3 ppb per PCB congener in liquid residuals. For the
demonstration, these streams were combined  in a  storage
tank.  Subsequent sampling by  TSCA  personnel confirmed
that the stored  liquids met the 3  ppb TSCA criterion.

If monochlorobiphenyls, dichlorobiphenyls, and nondetected
congeners (assumed to be present at the detection level) are
included, the scrubber decant could contain maximum PCB
concentrations  of 203 ppb; the scrubber liquor could contain
PCB concentrations up to  48.9. If  these  streams are  not
recycled through the process, they will require further treat-
ment as a RCRA waste.

The scrubber residuals did not contain detectable levels of
chlorobenzene and chlorophenols. In Condition 3, PCE was
detected at very low levels in the scrubber decant and scrubber
liquor, but not in the sludge.

The absence of chlorobenzene, chlorophenols, and the rela-
tive absence of PCE in the residual streams downstream of the
reactor provide further evidence that the ECO LOGIC Process
effectively removes chlorine from chlorinated organic com-
pounds. PAHs were the principal organic compounds detected
in the residue; benzene occurred in elevated concentrations in
the residual streams. The benzene and PAHs are most likely
PIRs resulting from the  dechlorination of the PCBs. Also,
residual PCB concentrations and PCDD/PCDF  concentra-
tions, although low, were present in all residue streams. The
remedial  manager should evaluate  concentrations of these
compounds at other  sites,  as  they  will likely be found at
detectable levels.

Miscellaneous Streams

The demonstration team collected water that came in contact
with the processing equipment—such as wash and rinse water
from equipment decontamination—and stored it apart from
other wastes, disposing of it as a hazardous waste. The treat-
ment/disposal of this wash/rinse water is site-specific.
                                                       14

-------
TSCA Permit Conditions

The  program required that ECO LOGIC  obtain a  TSCA
research and development permit. The permit conditions ad-
dressed PCB throughput and PCB concentrations in the efflu-
ent streams. TSCA established maximum PCB levels  of 2
ppm per congener in soil and 3 ppb per congener in water
streams. TSCA evaluated the combined scrubber liquid re-
sidual streams based on samples from the storage tanks. These
samples met the criterion that allowed disposal in a commer-
cial treatment system. However, the local  POTW  imposed
stricter PCB effluent concentrations than those permitted by
TSCA, requiring disposal of the liquid residuals through a
RCRA-permitted facility. Since POTWs set their acceptance
requirements based on their effluent requirements,  accep-
tance/rejection of the  scrubber liquid streams will be  site-
specific. In order for the ECO LOGIC system to process PCB
materials,  a TSCA permit will  be required. The remedial
manager should formulate a schedule that includes obtaining a
TSCA permit and addressing any process and operating  con-
straints that the permit may impose.

Equipment and Operating Considerations

The remedial manager considering the use of the ECO LOGIC
Reactor Process  should understand  the function of major
process equipment components and potential operating prob-
lems associated with them.

System  Components

The principal components of the ECO LOGIC Reactor  Sys-
tem are the reactor, the scrubber system, the recirculating fan,
the propane-fired boiler,  the liquid  feed systems, and the
process instrumentation. Each of these components presented
operating problems that future users should consider.

Reactor—The reactor is the principal component of the sys-
tem. Here the  combination of temperature,  residence time,
feed rate, and hydrogen concentration determines the DE. The
reliability  and performance  of  the subsystems controlling
these critical parameters affect the reformed gas quality and
the appropriate disposition of process residues and emissions.

During the demonstration, the steam flow control valve, used
to control reactor pressure, did  not operate stably. Control
improved  as the  operators gained experience, made system
modifications,  and formulated program logic adjustments.
During one run, reactor overpressurization resulted in a sys-
tem shutdown, underlining the importance of reactor pressure
control.

Scrubber system—The scrubber system is a key component
in achieving acceptable emissions. Gases exiting the reactor
first enter  the spray tower leg for quenching, then pass to the
packed tower. The scrubber removes residual organics, met-
als, particulates, and chlorides—cleaning the reformed gas.

Initially, as a result of incorrect installation of internal piping,
the scrubber produced foam, affecting its efficiency. After
ECO LOGIC modified the piping, the foaming stopped and
the scrubber operated efficiently.
During processing, the pH meter did not perform satisfacto-
rily because of radio frequency interference emanating from
the recirculating heater spark plug wires. As a result, the
addition of excess caustic contributed to the  scrubber foam-
ing. However, ECO LOGIC was able to manually measure
and adjust the scrubber pH, preventing any program delays.
This demonstrates the importance of relatively close scrubber
pH control.

Recirculating fan—The  5-hp  recirculating  fan moved the
scrubbed, recirculated, hydrogen-rich gas to the reactor inlet,
the reformed gas to compression and storage, and a reformed
gas slip stream to the boiler as supplementary fuel.

Scrubber foaming and water carryover caused  excessive mois-
ture in the fan casing. Eventually this condition required fan
shutdown, cleaning, and motor winding replacement.

Boiler—The boiler provided clean steam to heat aqueous
wastes in  the heat exchanger and burned a portion of the
reactor product—the reformed gas. Under normal operation,
the boiler cycles between high fire and low fire, depending on
process steam requirements. However, during Condition  1,
Run 1, the boiler, operating at low fire, emitted high spike
concentrations of  THC and CO. Operation  improved after
ECO LOGIC adjusted the linkage controlling the air/fuel ratio
to the boiler. However, during the remainder of the demon-
stration, ECO LOGIC vented steam to maintain boiler high-
fire. Future design considerations should address the appro-
priate sizing of the boiler and control of fuel/air ratio  to
prevent excessive criteria pollutant emissions.

In Condition 3, the PCB-rich  feedstock generated surplus
reformed gas, more than the boiler could process. The boiler
capacity, therefore, limited the system's throughput. To over-
come this, ECO LOGIC added a compressed gas storage tank
to the system. If, at the commercial scale, the process were
operated as a fuel producer, the boiler would not restrict
system throughput. In future operations, ECO LOGIC intends
to compress and store the surplus reformed gas for sale and
reuse. However, the remedial manager should  address this
report's earlier cautions concerning storage capacity and sal-
ability.

Liquid feed systems—The ECO LOGIC Reactor System had
separate feed systems for organic liquid feed and aqueous
liquid feed. The organic liquid feed system consisted of a feed
tank and a feed  pump. The aqueous liquid feed system con-
sisted of a feed tank, a feed pump, and a heat exchanger. The
aqueous liquid feed pump operated unstably, requiring fre-
quent adjustment. ECO LOGIC should undertake further de-
sign work  to improve the pump's reliability.

Process monitoring—The oxygen analyzer  did not operate
reliably. This is an important  consideration since elevated
levels of O2 in the system can create an explosive atmosphere.
Apparently, blockages in  the analyzer sampling line caused
the problem. Future  configurations of this  critical system
should address this deficiency.

A differential pressure transmitter and a magnehelic gauge
control the hydrogen content in the system,  ensuring suffi-
                                                       15

-------
cient hydrogen to reduce (destroy) the organics. Insufficient
hydrogen content can slow the reaction kinetics, causing
incomplete reduction.  During the demonstration, the lines to
the pressure sensors plugged, resulting in an insufficient hy-
drogen content and generating oily residue that coated equip-
ment  and instrumentation,  further affecting system opera-
tions.  ECO LOGIC should  consider a design change to im-
prove instrument reliability.

System Reliability

The program evaluated system reliability during processing
and during a 72-hour uninterrupted test. The reliability has
been expressed in terms of planned availability compared to
actual on-line availability. The number of days planned for the
entire demonstration was 10 (reactor and TDU/reactor tests);
the program actually took 42. This translates to a 24% equip-
ment availability.

In addition, the program evaluated actual waste throughput as
a percent of the planned input—a throughput reliability. The
wastewater test was designed to treat 8 tons of material, but
processed 2.9 tons. The waste oil  test nearly  achieved the
planned throughput of 0.8 tons. The resulting throughput
reliability percentages varied between 20% and 55% over the
six runs. However, during the 72-hour continuous  operation
using  liquid feedstock, the system operated without interrup-
tion.

Scale-up Parameters

One program objective sought to identify the critical scale-up
parameters. Knowing these parameters assists future users in
evaluating a proposed commercial-size operation. This report
has addressed scale-up considerations as they  pertain to the
immediate discussion.

CIMS Validation

The CIMS is the primary process  control unit of the  ECO
LOGIC Process. It records  and stores data. It measures se-
lected compounds and their decomposition products to maxi-
mize organic destruction.

Demonstration results show that the CIMS may reflect data
trends useful for process control, but it is not, at this stage of
its development, a reliable source of quantitative data. Further
testing will determine whether the CIMS can provide ad-
equate process control.

System Operating Conditions

Automatic computer data and manual logs documented pro-
cess  operating conditions and the  status of  the  operating
components.  These  data clarified process results and docu-
mented compliance  with permit conditions. Table 6 lists the
averages for several key system parameters; the TER contains
further details.
                                                          Table 6.
            Summary of Reactor Operating Conditions
Test condition
averages
Equipment
Reactor
Scrubber
Parameter
Temperature (°C)
Pressure (in. H2O)
Residence time (sec)
Inlet temperature (°C)
Outlet temperature (°C)
Water pH
1
892
1.8
8
546
33
8.78
3
933
1.8
6.1
527
32
9.32
Recirculating fan



Vaporizer

Differential pressure
(in. H20)
Flow rate (cfm)
Gas pressure (in. H2O)
Temperature (°C)
Pressure (psi)
11.6

110
6.5
148.3
51.8
7.8

110
0.66
149
51.4
Technology Applicability

This section describes the applicability of the technology to
the site, waste media, safety, and staffing.

Site Characteristics

The ECO LOGIC system requires a fairly level area, approxi-
mately  120  ft x 180 ft, for the  processing and auxiliary
equipment. Utility  tanks require level surfaces or supports.
Except for process gas tank support pads, no additional sur-
face support is needed. The reactor system sits on two mobile
trailers.

Cold-weather operations may inhibit efficient destruction be-
cause of the incremental amount of energy required to heat the
reactor. In addition, feedstock liquids would require melting
prior to treatment, and liquid residuals could freeze in the
unheated storage tanks. Winterization, including heat tracing,
is  necessary to  provide adequate feedstock and to ensure
uninterrupted processing.

Applicable Media

Initially, ECO LOGIC designed the reactor system to process
liquids, with soil processing limited  to about 30%  solids1.
ECO LOGIC added the TDU to gain greater feedstock pro-
cessing capabilities. As explained in an independent AAR, the
demonstration indicated that the TDU requires further devel-
opment.

The reactor system is best suited for  processing liquids and
TDU off-gases/water vapor. The waste's organic content lim-
its the demonstration-scale system's feed rate  because  of
reformed  gas generation. Currently, ECO LOGIC plans to
improve  throughput by  storing excess reformed  gas  after
compressing it. Future users should consider the implications,
logistics, and costs of this approach.
                                                        16

-------
Safety Considerations
Process Safety System
The principal safety considerations for the ECO LOGIC Pro-
cess  concern personnel,  chemical use, equipment integrity,
and process control.

Personnel Safety

The components of personnel safety requiring attention are
those associated with Construction Safety Standards [29 CFR
1926] addressing such topics as slips, trips, and falls; confined
space entry;  contingency planning; etc. The regulations in 29
CFR 1910.120 address PPE. High voltage electrical  equip-
ment standards are also a concern.

Chemical  Use

The chemical hazards of the ECO LOGIC Process accompany
the use of propane, liquified nitrogen/oxygen, hydrogen, in-
dustrial chemicals, and hazardous feed material. In addition,
the process generates methane. Standardized industrial proce-
dures provide guidance for storing, transporting, and handling
these materials.

There should be no undue concern associated with hydrogen
usage in the process. Well established and proven procedures
are available for safe hydrogen storage and use. Hydrogen is
no more nor less dangerous than gasoline or methane. As with
these substances, hydrogen must be handled with due  regard
for its unique properties.

The electrical, petroleum refining, chemical, petrochemical,
and synthetic fuel industries have safely used hydrogen  in
large quantities for decades. Through much of the last century
Europe successfully used hydrogen-enriched gases  (coal gas,
town gas, producer gas) to satisfy residential fuel needs.2 The
Northeast United States used coal gas until the late 1950s.

For the demonstration, ECO LOGIC developed a Hydrogen
Safety Procedure based on the Canadian National Research
Council's Safety Guide for Hydrogen.2 Ultimately,  remedial
managers must assure themselves that the flammable gases
used in the ECO LOGIC Process are handled, stored, and used
in accordance with industry standards and guidelines.

Equipment Integrity

Verification  of  system component integrity is  essential  to
process  safety.  The remedial contractor should undertake
pressure testing, hydrostatic testing, and metal embrittlement
evaluations. The results should be certified before processing
hazardous materials. Hydrogen is more difficult to contain
than  other gases because of its small molecular size.  There-
fore,  interfaces of equipment, instruments, and piping must be
leak-free. To provide an additional safeguard, ECO LOGIC
maintains the system under slight positive pressure, prevent-
ing infiltration of oxygen. As a safety backup ECO LOGIC
monitors internal oxygen levels and maintains gas feeds (pro-
pane and hydrogen) at low pressure to prevent pipeline breaks.
ECO LOGIC designed a safety system to immediately react,
should any system upset occur. The control system initiates
system shutdown in response to high oxygen content, high
pressure drop across the fan, scrubber pump failure, ground
faults, boiler failure, high hydrocarbon emissions, or power
failure. However, these shutdown systems were not needed
during the demonstration.

Whenever process conditions require a system shutdown, the
system program  stops the waste input streams and replaces
them with clean steam to prevent any negative pressure in the
reactor. The program also stops hydrogen flow and introduces
a nitrogen purge.  Reformed gas flow to the boiler stops. Either
an operator or an automatic  computerized process controller
initiates these events.

Staffing Issues

The CIMS facilitates monitoring and remote adjustment of
process parameters. This reduces labor requirements for moni-
toring and maintenance  personnel. The monitoring personnel
must be capable of evaluating system problems and directing
maintenance personnel  in problem resolution.  Since opera-
tions can be controlled remotely, only those personnel need-
ing to manually  adjust  or maintain the system components
require personal protective equipment. Since the system will
be processing hazardous substances, the medical monitoring,
training,  and personal protection requirements  of 29  CFR
1910.120 will remain in effect.

Regulatory Considerations

Several pieces of federal legislation and any state or local laws
present compliance  considerations in operating  the ECO
LOGIC Reactor System.

Clean Air Act

The Clean Air Act (CAA) establishes primary and secondary
ambient air quality standards to protect public health; it also
sets emission limits for hazardous  air pollutants. Each state
administers its own permitting requirements as part of the
State Implementation Plan, developed to bring the state into
compliance with National Ambient Air  Quality  Standards
(NAAQS). These standards apply to the ECO LOGIC Process
because of its potential emissions. The process will probably
require an air permit to operate at any site, whether or not the
state has  attained its NAAQS. Even if the area is in attain-
ment, prevention of significant deterioration regulations may
further curtail emissions. Regulatory requirements must be
determined on a site-by-site basis.

Clean  Water Act

The Clean Water Act (CWA) regulates direct discharges to
surface water through the National Pollutant Discharge Elimi-
nation System (NPDES). These regulations require that waste-
water point-source discharges meet established water quality
standards. The ECO  LOGIC Process generates noncontact
and contact water discharges. Noncontact water sources in-
                                                       17

-------
elude the heat exchanger, evaporative cooler, boiler water,
and blow-down. Contact water comes from the TDU quench,
scrubber liquor, tank cleaning, and equipment wash down; it
will likely require further treatment prior to discharge to a
POTW. In any case, wastewater discharge to a sanitary sewer
requires a discharge permit or, at least, concurrence from state
and local regulatory authorities that  the wastewater is in
compliance with regulatory limits.

Comprehensive Environmental Response,
Compensation, and Liability Act

The  Comprehensive Environmental Response,  Compensa-
tion, and Liability  Act (CERCLA) of 1980, amended  by
SARA of 1986, provides federal funding to respond to  re-
leases of hazardous substances to air, water, and land. Section
121 of SARA, entitled "Cleanup Standards," states a strong
statutory preference for remedies that are highly  reliable and
provide long-term protection. It recommends that remedial
action utilize  on-site treatment that "... permanently  and
significantly  reduces the volume,  toxicity,  or  mobility of
hazardous  substances."  In addition, remedial actions must
consider the technology's long-term and short-term effective-
ness, implementability, and cost.

The ECO LOGIC Reactor Process satisfies the SARA man-
date to reduce the toxicity, mobility, and volume of hazardous
substances by reducing organic contaminants in the feed-
stock—such  as PCBs—to  lighter, nontoxic hydrocarbons,
such as methane and ethylene. The demonstration showed that
the reactor system destroyed more than 99.99%  (DE) of the
contaminants, illustrating both long-term and short-term  ef-
fectiveness with respect to organic compounds.  It indicated
that metals were mainly concentrated in the scrubber effluent,
which required additional treatment prior to disposal. EPA
cost estimates are found in Section 4.

The  system appears implementable as  currently designed.
Relatively  mobile,  it requires  water  and electric utilities;
hydrogen, oxygen, nitrogen, and propane storage; and front-
end material handling equipment to deliver feedstock to the
feed storage tanks.

Occupational Safety and Health Act

Sections 1900 to 1926 of the Occupational Safety and Health
Act  (OSHA)  govern ECO LOGIC  remedial  operations:
1910.120 for hazardous waste operations, 1926 for construc-
tion site activities, and 1910.1200 for worker and community
right-to-know.

Resource  Conservation and Recovery Act

RCRA is the primary federal legislation governing hazardous
waste activities. RCRA Subtitle C  contains requirements for
generation, transport, treatment, storage, and disposal of haz-
ardous waste, most  of which  are  applicable to CERCLA
activities.

Depending on the specific waste feed and the effectiveness of
the treatment, the ECO LOGIC Reactor Process generates two
potentially hazardous waste streams: the scrubber liquor and
the treated soil. To generate these wastes, the remedial man-
ager must obtain an EPA generator identification number and
either comply with generator accumulation and storage re-
quirements under 40 CFR 262, or receive a Part B Treatment,
Storage, and Disposal (TSD) interim status permit. CERCLA
mandates compliance with RCRA TSD requirements. A haz-
ardous waste manifest must accompany off-site waste ship-
ment; transport  must comply with Federal Department of
Transportation (DOT) hazardous waste transportation regula-
tions. The receiving TSD facility must hold a permit  and
comply with RCRA standards.

Technology or treatment standards apply to many hazardous
wastes; those appropriate for the ECO LOGIC Process depend
on the waste generated. RCRA land disposal restrictions, 40
CFR 268, mandate hazardous waste treatment after removal
from a contaminated site and prior to land disposal, unless a
variance has been granted. The scrubber liquor and treated
soil will require additional treatment prior to land disposal if
they do not meet their pertinent treatment standards.

Toxic Substances Control Act

The ECO  LOGIC Process treats  wastes containing PCBs.
Therefore, the remedial manager must address TSCA stan-
dards for PCB spill cleanups  and  disposal. The EPA docu-
ment, CERCLA Compliance with Other Laws Manual,3 dis-
cusses TSCA as it pertains to Superfund actions.

If ECO LOGIC plans  to  treat PCB-contaminated material
containing no RCRA wastes, they must obtain a TSCA autho-
rization. The conditions of this authorization may contain
operational, throughput, or disposal constraints that could
affect treatment efficiency and costs. If ECO LOGIC chooses
to treat PCB-contaminated material containing RCRA wastes,
a RCRA permit for a TSD facility will also be  required.

State and Local Regulations

Compliance with applicable or relevant and appropriate re-
quirements may require meeting state standards that are more
stringent than federal standards; state  standards may control
non-CERCLA treatment activities.  Several types of state and
local regulations affect operation of the ECO LOGIC Process,
such as, permitting requirements for construction/operation,
prohibitions on emission levels, and nuisance rules.

References

 1. U.S. Office  of Technology Assessment, "Dioxin Treat-
    ment Technologies" (background paper), OTA-BP-0-93,
    U.S. Government Printing Office, Washington, D.C., No-
    vember 1991.
 2. Kalyanam, K. M., and Hay,  D.  R., Safety  Guide for
    Hydrogen, National Research  Council of Canada,  Ot-
    tawa, Ontario, 1987.
 3. U.S. EPA. CERCLA Compliance with Other Laws Manual
    Part II: Clean Air Act and Other Environmental Statutes
    and State Requirements, Interim Final, EPA/540/G-89/
    009, OSWER, Washington, D.C.,  August 1989.
                                                      18

-------
                                               Section  4
                                     Economic Analysis
Introduction

Estimating the cost of employing an innovative technology is
a major objective in each SITE demonstration project. This
economic analysis presents data on the costs (excluding profit)
for a commercial-scale remediation using the ECO LOGIC
Gas-Phase Chemical Reduction Process. With a realistic un-
derstanding of the test costs, it should be possible to forecast
the economics of operating similarly  sized systems or to
extrapolate these figures for larger systems at other sites.

The SITE Demonstration of the ECO LOGIC Reactor System
conducted at the Middleground Landfill treated both PCB-
contaminated wastewater and waste oil. This economic analy-
sis is an extrapolation of that experience based on the com-
mercial use of a  system similar to that  employed during the
demonstration program. For the purposes of this analysis it
was assumed that 100,000 gallons of wastewater and 30,000
gallons of waste oil were stockpiled for treatment. The waste
streams are assumed to be  identical in composition to those
treated  during the demonstration  program. The following
feedrates were utilized forthis analysis: 1.73 kg/min of waste-
water and  0.485 kg/min of waste oil, simultaneously injected
into the reactor.  Since the  process could experience some
downtime, a sensitivity analysis presents three different on-
line utilization factors: 60%,  70%, and  80%. Certain cost
elements were fixed; others were time-sensitive.

Decreased process efficiency (lower utilization factor) would
require  an extended time  to  process the same  amount of
material, reflecting higher  costs. Final figures  have been
expressed as cost (U.S. dollars per ton) of material processed.

Conclusions

The data showed the ECO LOGIC Reactor Process to be an
acceptable remedial alternative for liquids contaminated with
PCBs.  Since the  process was effective  in treating the PCB-
contaminated Middleground Landfill  liquids,  it should  be
applicable to the remediation of other similar sites.

The treatment costs (1994 U.S. dollars) ranged from a low of
$l,670/ton to a high of $2,000/ton, depending on the utiliza-
tion factor. Because of limited data, the cost estimates pre-
sented in this analysis may range in accuracy from +50% to -
30%, an order of magnitude guideline suggested by the Ameri-
can Association of Cost Engineers.

Issues and Assumptions

The costs associated with this technology were calculated on
the basis of demonstration parameters such as the following:

 •  A small to medium hazardous waste site
 •  Three tons of liquid feed
 •  A short treatment period during the SITE Demonstration

While the equipment used for the demonstration was a small
commercial size, it may not be applicable where time con-
straints require increased capacity. The targeted test through-
put rates were considerably higher then those actually realized
during  the  demonstration. Variations in throughput could
significantly affect costs.

Important  assumptions  regarding specific operating  condi-
tions and task responsibilities, described below, will impact
cost estimates.

Site-Specific Factors

The demonstration site presented certain site-specific charac-
teristics that affected the cost estimate. Variations to these
site-specific characteristics may improve or worsen the project
economics:

 •  Proximity to utilities, with capacity sufficient to service
    project
 •  Favorable ambient conditions
 •  Clear, level work area
 •  Small, specialized project with minimal requirements for
    storage, administration,  services, etc.

Fixed costs are not related to  time or volume; nor are they
affected by project magnitude. Such costs include the trans-
portation/setup/removal of trailers, sanitary facilities, decon-
tamination facilities, process equipment, foundations, roads,
and utilities. In employing the  results of this SITE economic
analysis to forecast a unit cost (dollars/ton), the potential user
should recognize  that these same fixed costs  spread over
larger volumes of contaminated material would lower the unit
cost. The reverse would be true of a smaller project.
                                                       19

-------
Coste Excluded from the Estimate
Labor
Although the SITE Program provides a 12-item list of costs
on which the economic analysis of a demonstration should be
calculated, not all 12 apply to every project. Certain cost items
were excluded from this analysis because they were either
site-specific,  project-specific, or the obligation of the site
owner/responsible party.

Utilities

Electrical power was required for the operation of the various
pumps, blowers, feeders/conveyors, and electric heating ele-
ments, in addition to instrumentation, lighting, and miscella-
neous power outlets. The total system demand at full effi-
ciency averaged 30 kW.

Scrubber make-up water requirements were minimal; actual
volume used was not available. For calculations, the addition
of 178 kg/hr of water (about 50 gal/hr) was assumed.

The  recirculating gas heat  exchanger and boiler needed a
natural gas source  along with required piping and appurte-
nances. During the demonstration, propane fuel was used. For
Condition 1, the propane consumption rate was 7.62 kg/hr; for
Condition 3, 12.9 kg/hr.

With the exception of propane, the analysis assumed that all
utilities, in appropriate capacities, were available at the site.

Supplies

Table 7 shows the types and quantities of consumable sup-
plies required by the ECO LOGIC Reactor Process.

Operating Conditions

This analysis assumed that the facility would operate 24 hours
a day, seven days a week. At the throughput rates discussed
earlier, the required operating times were calculated with the
three different utilization factors, as follows:

         250 days (60% utilization)
         214 days (70% utilization)
         188 days (80% utilization)

These periods excluded mobilization, shakedown,  start-up,
and demobilization times.
Table 7
            Consumables Required by the ECO LOGIC
            Reactor Process
Item
Caustic
Hydrogen
Propane
Nitrogen
Measure
kg/hr
kg/hr
kg/hr
m3
Condition 1
(Water)
24.7
0.138
7.62
15
Condition 3
(Oil)
116.7
0.072
12.9
15
Four crews, consisting of a shift supervisor and two techni-
cians, would provide coverage  for a  24-hour, seven-day,
three-shift reactor operation. The project engineer/manager
would work Monday to  Friday during the day shift; a part-
time clerk, the same  schedule.  The first and second shifts
would require two technicians. The third shift (midnight to
8:00 am) would require only one.

The Project Engineer/Manager would hire all non-union local
workers. Table 8 lists the labor classification, number of
workers, and unit labor  rates used in the forecasts. Table 9
shows the data totals based on utilization percentage.

The estimates excluded costs for OSHA training time, medi-
cal screening for all personnel on-site, and operations training.

Basis for Economic Analysis

To provide a basis of cost-effectiveness comparison among
technologies, the SITE Program links costs to  12  standard
categories, listed below:

 •  Site preparation
 •  Permitting and regulatory
 •  Capital equipment
 •  Mobilization and start-up
 •  Operations labor
 •  Supplies
 •  Utilities
 •  Effluents
 •  Residuals
 •  Analytical
 •  Repair and maintenance
 •  Demobilization

Some of the cost categories above do not apply to this analysis
because they are site-specific, project-specific, or the obliga-
tion of site owner/responsible party:

 •  Project  engineering and design, specifications, requisi-
    tions
 •  Permits, regulatory requirements, plans
 •  Wells, pipelines, excavation/stockpiling/handling of waste
    (except for feed to process equipment),
 •  Backfilling, landscaping, any major site restoration
 •  Sampling and  chemical analysis except as required for
    disposal of miscellaneous effluents and wastes
 •  Initiation of monitoring programs
 •  Post-treatment reports, regulatory compliance

Wherever possible, applicable information has been provided
on these excluded costs so that potential users may calculate
site-specific economic data for their particular projects.

Site Preparation Costs

The extent of preparation depends on the specific site charac-
teristics. Such activities  include  site design, layout,  surveys,
acquisition of access  rights, establishment of support and
decontamination facilities,  and utility connections.
                                                        20

-------
Table 8. Operating Labor*

Category Hire Number
Engineering Direct 1
Shift supervisor Local 1
Technicians Local 2**
Clerk (part-time) Local 1
Subtotal
Time/labor for engineer
Total per week
* 24 hours per day, 7 days per week operation.
** 4 shifts (shift 3 - only 1 technician).
Table 9. Labor Costs Based on Utilization
Utilization (%) Cost/week Weeks Labor cost
60 $16,600 34 $564,400
70 16,600 30 498,000

80 1 6,600 26 431 ,600



Despite the fact that most of these activities are site-specific,
they represent a typical percentage of the overall cost that can
be expected on any project. Therefore, they have been in-
cluded in the cost analysis.

The analysis excluded site engineering, work plan prepara-
tion, and pretreatment of hazardous waste feed. Table 10 lists
the cost elements associated with site preparation for the ECO
LOGIC SITE Demonstration.
Permitting and Regulatory Costs
Permitting and regulatory costs are generally the obligation of
the responsible party or site owner. These costs may cover
actual permit application, monitoring, and the development of


Shifts
1
4
4
1





Table
Item
1
2
3

4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Total


Hr/wk
40
160
280
20





10. Demonstration
Description
Site fencing (chain link)
Snow fencing (wood)
Access roads

Gravel and stone
Concrete pads
HOPE liner
Temporary piping
Temporary electric
Telephone
Sump pumps
Security
Signs, etc.

All-in
cost/hr
$40.00
34.00
30.00
20.00





Site Preparation Costs
Cost
$2,500
100
12,000

2,000
4,500
3,500
1,300
2,000
500
1,000
8,000
1,000

Total
per week
$1,600
5,440
8,400
400
1 5,840
760
$16,600
















Personal protective equipment 2,000
Engineering support
Administrative support
Site supervision
Travel and living
Miscellaneous

5,000
5,000
60,000
12,000
5,000
$127,400





tory costs vary greatly because they are specific to the site,
waste, and technology. Therefore, no permitting and regula-
tory costs have been included in this analysis. Depending on
the treatment site, however, they could be a significant factor,
since  such activities can be both expensive and time-consum-
ing.

Capital Equipment

This cost category includes  all equipment provided by the
technology developer; it generally encompasses equipment
integral to the process. For this analysis, holding tanks and
incidental equipment have been relegated to other categories.

Table 11 provides a breakdown of the reactor capital equip-
ment  costs. Comparable  costs associated with the TDU/reac-
tor combination are addressed in the complementary TDU
AAR.

Prices for the various pieces of equipment were obtained from
vendor catalogs, Richardson's cost estimating handbooks, and
historical data. General specifications were provided by the
developer. The figures excluded all research and development
costs. No license fees or royalties have been included.

In terms of size and throughput capacity, the actual equipment
used for the demonstration was also used for the analysis.

The operational duration of the project in the forecast is less
then 1 year. Therefore, the equipment costs have been annual-
ized based on the following formula:
                    A = C
                           i (1 + i)n
                A = annualized cost, $
                C = capitalized cost, $
                i = interest rate, 6%
                n = useful life, 10 years
                                                        21

-------
Table
Item
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Total
11. Capital Equipment for Commercial
Description
Reductive heater
Heat exchangers (2)
Reactor
Scrubber
Recirculating fan
Gas storage vessel
Boiler
Pumps
Sludge/oil tank
Wastewater tank
Lowboy trailers
Ductwork
Electrical system
Control system
Miscellaneous pipes and valves
Miscellaneous structures and supports
Instrumentation
Electrical bulks
Miscellaneous process items

Operation
Total
$20,000
60,000
74,000
36,000
10,000
10,000
113,000
19,000
10,000
10,000
55,000
5,000
21,000
40,000
32,000
5,000
32,000
1 1 ,000
22,000
$585,000
Mobilization and Start-up

Mobilization includes the setup of the work site  including
trailers, utilities, and miscellaneous materials, as well as the
transportation and assembly of the process equipment. Table
12 breaks down the significant cost items associated with this
category.

Transportation costs were calculated on the basis of 500 one-
way road miles at an average of $2.00 per mile.  One-way
miles were used because it was assumed that the equipment
travels from active site to active site.

The process equipment consisted of two pre-assembled flat-
bed trailers. A separate allowance covered final hook-up at the
site, while shakedown costs comprised part of the allowance
for start-up (Table 13).

Transportation costs for personnel have been included in the
Labor category.

Taxes and insurance were calculated as 5% of capital equip-
ment. An allowance for  working capital, equivalent to ap-
proximately one month's inventory  of supplies,  has been
included ($9,000).

Start-up costs included labor for a five-man crew during one
60-hour week, plus an allowance for consumables and miscel-
laneous.  The cost analysis did not provide for a separate
contingency; however, start-up costs included a 10% contin-
gency.
Operations Labor

Personnel requirements for operating the facility under vari-
ous conditions have already been discussed. They included
wages and travel expenses for on-site  operations personnel.
Fully burdened wage rates were shown by labor category in
Table 8. It was assumed that all personnel would be local hires
except the project engineer/manager. Per diem for the project
manager—lodging, food,  and rental car for a seven-day-
week—has been calculated at $110/day.

Supplies

This cost category, consisting of chemicals and fuels, was
based on consumption rates for the various operating condi-
tions. Northeastern area vendors provided verbal quotes with
no consideration for large bulk quantity or unusual transporta-
tion. (Chemicals and fuels could be purchased locally for
approximately the same price.)

Supplies also  encompassed  disposable personal protective
equipment (PPE) for Level D. The category also included a
$5,000 allowance for unspecified consumables and spares.

Utilities

Electrical usage, make-up water consumption, and telephone
charges comprised the utilities category. Electrical demand in
kilowatt hours was extrapolated from actual demonstration
experience at $0.08/kWh.  Make-up water was calculated at
approximately 50 gal/day and $0.05/gal. Telephone charges
were set at $300/month.

All utilities were assumed to be available at the site. However,
costs excluded installation, hook-up, etc., which were covered
under Mobilization.

Effluents

There were no costs associated with effluents in this analysis
since  no material would be introduced into normal effluent
streams.

Residuals

Residuals generated by this process would  include  grit and
fines that would be stored in drums and transported to  an
approved disposal site. This category also included the trans-
portation and disposal of PPE stored in drums. The process
generated approximately 0.071  kg/hr of grit, slightly more
then 500 Ibs for this application.

Analytical

No analytical costs have been included in this cost estimate.
The client could elect (or might be required by local authori-
ties) to  initiate  a sampling and analytical program to  meet
local regulatory criteria. These analytical requirements could
significantly affect costs.
                                                        22

-------
Table 12.     Mobilization/Start-Up Costs

Description Cost/Month ($)
Fixed costs
Delivery /blocking trailers
Trailer furnishings
Hooking up process equipment
Storage tanks and vessels
Drums and pails
Crane rentals, etc.
Monthly costs
Trailers (5) 500
Portable toilets (2) 150
Dumpsters 150
Job vehicles 1 ,000

60%

$1,550
2,000
15,000
1 1 ,000
2,600
1,400

$4,000
1,200
1,200
8,000
Utilization
70%

$1,550
2,000
15,000
1 1 ,000
2,600
1,400

$3,500
1,050
1,050
7,000

80%

$1,550
2,000
15,000
1 1 ,000
2,600
1,400

$3,000
900
900
6,000
Table 13.
            Cost Allocations

Description
Transportation
Working capital
Insurance
Start-up (4,000)

60%
$1 ,000
9,000
32,000
20,000
Utilization
70%
$1 ,000
9,000
28,000
20,000

80%
$1,000
9,000
24,000
20,000
Repairs and Maintenance

Maintenance labor and material costs vary with the nature of
the waste, the performance of the  equipment, and  the site
conditions. For estimating purposes,  roughly $500/mo has
been allowed. This represents approximately 10% of capital
equipment.

The key maintenance items associated with the ECO LOGIC
Process are the electrically  heated  bars in the reactor. The
anticipated life span, under the operating conditions described,
has not yet been defined.

Demobilization

Demobilization costs were limited to disassembly, site cleanup,
and limited restoration. Disassembly covered the following:
disconnection of equipment and utilities,  surface decontami-
nation (for transportation off-site) of all process equipment,
and loading. Transportation to the next destination was not
included.

Site restoration  included the removal of all utilities, trailers,
and rental equipment. Requirements regarding permanent fenc-
ing, grading, landscaping, etc., vary by site. Depending on the
future use of the site, they were assumed to be the  obligation
of the site owner or the responsible  party.  They were not
included in this  analysis.
Results of Economic Analysis

Table 14 presents the  total  treatment cost for the reactor
system.  The table was organized in accordance with the 12
EPA cost categories. In addition to total treatment costs, a unit
cost (dollars/ton) has been provided. In an effort to address
unforeseen job conditions, a range of costs for 60%, 70%, and
80% utilization factors has been calculated.

The largest single cost component of this treatment technol-
ogy was operational labor—accounting for 52% of the total
treatment cost at 80% utilization. Supplies accounted for 12%
of the total, while site preparation made up 15%, and mobili-
zation/start-up, 12%. The remaining  eight categories com-
prised only 9% of the total treatment cost, with three having
no cost associated with them for this SITE project analysis.

Considering the effect of the labor component on price and
the  relative constancy in scale-up of the other components, it
is  likely that  unit costs  would benefit significantly  from
commercial  scale-up. Increasing equipment capacity would
decrease process  time and labor cost.

Table 15 compares the costs per ton for the actual test through-
puts with the  costs estimated for targeted throughputs. If
targeted throughputs had been achieved, costs per ton would
have been substantially lower. A commercial-scale unit would
further decrease these figures.

References

 1.  Richardson Engineering Services. Cost Estimating Guide,
    Vol 1, 1993 edition.

 2.  R. S. Means.  "General Building Construction," Cost Esti-
    mating Services.

 3.  Evans, G.  M. "Estimating Innovative Technology Costs
    for  the SITE Program."  EPA/RREL for Journal of Air
    Waste Management Association. July, 1990. Volume 40,
    No. 7.
                                                       23

-------
Table 14. Economic Analysis for the ECO LOGIC Reactor System
Activity
Site preparation
Capital equipment
Start-up/mobilization
Labor
Supplies
Utilities
Residuals
Maintenance costs
Demobilization
Totals
Costs
Table 15. Cost Extrapolations

At actual
throughput
60% 2,000
70% 1 ,850
80% 1 ,670

60%
(250 days)
$127,400
50,400
109,950
564,000
110,000
10,500
2,500
4,000
20,000
$998,750
$2,000/ton

Cost, $/ton
At targeted
throughput
670
620
550
Utilization
70%
(21 4 days)
$127,400
44,700
104,150
498,000
106,000
10,500
2,500
3,500
20,000
$916,750
$1,850/ton





80%
(188 days)
$127,400
37,800
98,350
431 ,000
103,000
10,500
2,500
3,000
20,000
$833,550
$1,670/ton




24

-------
                                         Appendix A
                  Demonstration Sampling  and Analysis
Introduction

The ECO LOGIC Reactor System SITE Demonstration con-
sisted of two test conditions with three runs each. Condition 1
treated  PCB-contaminated wastewater; Condition 3, PCB-
contaminated waste oil. The TDU demonstration comprising
Condition 2 processed contaminated soil—the subject of an
independent AAR.

Sampling and analysis of the feedstock, intermediate streams,
and residuals followed the procedures outlined in the demon-
stration plan. EPA subjected the entire sampling and analysis
program to a rigorous Category II Quality Assurance (QA)
procedure designed to generate reliable test data. The demon-
stration plan also contains the QA procedure. The TER pre-
sents a detailed account of the demonstration results.
Figure A-l shows the sampling locations. An SS designation
represents EPA contractor sampling locations shown in Table
A-l; MS indicates an ECO LOGIC Process monitoring sta-
tion, listed in Table A-2.

Methodologies

The EPA program sampled three matrices: gases, liquids, and
solids. EPA sampled and analyzed all key input and output
streams; they selected intermediate streams for physical prop-
erties (flow rate, density, moisture), PCBs, PCDD/PCDF,
PAHs, PCE, chlorobenzenes, chlorophenols, volatile organic
compounds (VOCs),  13 trace metals, HC1, O2, CO2, CO, SO2,
NOx, THC, and other selected  compounds. Tables A-3, A-4,
and A-5 list the sampling and analysis methods used by EPA.
The demonstration plan and TER contain further details about
the Sampling and Analysis Program.
 Clean
  Soil
 Quench (SS24
 Water
                                                                                      SS15J
                                                                                     Tank Condensate
Figure A-1. Sampling and monitoring stations.
                                                   25

-------
                      Table A-1.    EPA Sample Locations
                      Stream
                      SS1
                      SS2
                      SS3
                      SS4
                      SS5
                      SS6
                      SS7
                      SS9
                      SS10
                      SS11
                      SS12
                      SS13
                      SS14
                      SS15
                      SS16
                      SS18
                      SS19
                      SS20
                      SS22
                      SS24
    Description
Waste water
Waste oil
Contaminated soil
Caustic soda
Scrubber make-up water
Propane
Hydrogen
Combustion air
Treated soil
Reactor grit
Scrubber sludge
Scrubber decant
Reformed gas
Tank condensate
Stack gas
Heat exchanger
TDU gas
TDU molten bath
Scrubber liquor
Quench water
       Location
Feed line before pump
Oil drum
Feed drum
Caustic soda reservoir tank
Feed line
Feed line
Feed line
Boiler inlet
Treated soil collection drum
Reactor grit catchpot
Scrubber effluent tank
Scrubber effluent tank
Duct after gas booster fan
Bottom of condenser
Boiler stack
Heat exchanger residue waste drum
TDU-to-reactor feed line
Bath vessel
Scrubber tank
Quench water tank
Table A-2.    ECO LOGIC Process Control Monitoring Stations
Parameter
Temperature


Pressure


Flow rate


Feed rate

PH
Gas constituents
Stations
2, 3, 4, 5, 6, 7, 9,
11, 12, 13, 15, 16,
17, 18
12, 13, 16,
1,4,7
7, 10
7, 10
13
8
13
14
5
7
Frequency
Continuous


Continuous
Continuous
1/2 hour
Continuous
Continuous
Hourly
Hourly
1/2 hour
Continuous
Continuous
Method
Thermocouple


Pressure transmitter
Differential pressure transmitter
Gauge
Differential pressure transmitter
Vortex flow meter
Orifice meter
Vortex flow meter
Tracer injection
pH meter
O2 analyzer; CIMS
                                                            26

-------
Table A-3. Flue Gas Sampling and Analytical Methods
Sampling
Analyte Principle Reference
PCBs
Dioxins/furans
PAHs
CB/CP
Volatile organics
Metals
HCI
Participates
N0x
S02
°2
C02
CO
THC
Fixed gases
Sulfur compounds
Heating value
XAD-2
XAD-2
XAD-2
XAD-2
Tenax
Impinger
Impinger
Filter
OEMS
OEMS
OEMS
OEMS
OEMS
OEMS
Tedlar bag
Tedlar bag
Tedlar bag
Method 001 0*
Method 0010
Method 0010
Method 0010*
Method 0030*
EPA Method 29 (draft)
EPA Method 26**
EPA Method 5**
EPA Method 7E**
EPA Method 6C**
EPA Method 3A**
EPA Method 3A**
EPA Method 10**
EPA Method 25A**
EPA Method 18**
EPA Method 18**
EPA Method 18**
Analytical
Principle
HR GC/HR MS
HR GC/HR MS
GC/MS
GC/MS
GC/MS
CVAAS, ICAP, GFAAS
1C
Gravimetric
Chemiluminescence
NDUV
Paramagnetic
NDIR
NDIR
FID
GC
GC/FPD
GC
Reference
EPA 680*
EPA 23**
EPA 8270*
EPA 8270*
EPA 5041*
EPA 29 (draft)
EPA 26**
EPA 5**
EPA 7E**
EPA 6C**
EPA 3A**
EPA 3A**
EPA 10**
EPA 25A**
MASA 1 33***
EPA 15**
ASTM 2620M
Test Methods for Evaluating Solid Wastes, SW-846, U.S. EPA (November 1986, reissued July 1992 and November 1992).
Code of Federal Regulations, 40 CFR 60.
Lodge, J.P., Methods of Air Sampling and Analysis, 3rd Edition, Lewis Publishers, Inc., Chelsea, Ml, 1989.
Table A-4. Solids Sampling and Analytical Methods*
Analytical
Analyte Principle Reference
PCBs
Dioxins/furans
CB/CP
PAHs
Volatile organics
Metals
Organic halogens
Inorganic halogens
Hexavalent chromium
Total sulfur
TCLP volatiles
TCLP metals
Ash
Heating value
Ultimate analysis
Total organic carbon
Density
GC/MS
HR GC/HR MS
GC/MS
GC/MS
GC/MS
CVAAS, AAS, ICAP
1C
1C
Colorimetric
Gravimetric
GC/MS
CVAAS, ICAP
Combustion/gravimetric
Bomb calorimeter
Combustion
GC
Hydrometer
EPA 680*
EPA 8290*
EPA 8270*
EPA 8270*
EPA 8260*
EPA 6010, 7471*
EPA 9020*
ASTM E776
EPA 71 96*
ASTM D31 77
EPA 8240*
EPA 60 10, 7470*
ASTM D482
ASTM D240
ASTM D31 76
EPA 9060*
ASTM D1298
                              * Using grab samples, performed in accordance with U.S. EPA Office of
                               Solid Waste document Test Methods for Evaluating Solid Wastes, SW-
                               846, 3rd Edition, Volume II, Chapter 9, November 1986.
                                                               27

-------
Table A-5.    Liquids Sampling and Analytical Methods
Analyte
PCBs
Dioxins/furans
CB/CP
PAHs
Volatile organics
Metals
Organic halogens
Inorganic halogens
Hexavalent chromium
Total sulfur
TCLP volatiles
TCLP metals
Ash
Heating value
Ultimate analysis
Total organic carbon
Density
PH
Analytical
Principle
GC/MS
HR GC/HR MS
GC/MS
GC/MS
GC/MS
CVAAS, ICAP
1C
1C
Colorimetric
ICAP
GC/MS
CVAAS, ICAP
Combustion/gravimetric
Bomb calorimeter
Combustion
GC
Hydrometer
pH meter
Reference
EPA 680*
EPA 8290*
EPA 8270*
EPA 8270*
EPA 8260*
EPA 6010, 7470*
EPA 9020*
EPA 325.2
EPA 71 96*
EPA 6010*
EPA 8240*
EPA 60 10, 7470*
EPA 160.4
ASTM D240
ASTM D31 76
EPA 9060*
ASTM D1298
EP A9040*
* Using grab samples, performed in accordance with U.S. EPA Office of
 Solid Waste document Test Methods for Evaluating Solid Wastes, SW-
 846, 3rd Edition, Volume II, Chapter 9, November 1986.
                               28

-------
                                            Appendix B
                                        Vendor's Claims
Introduction

Following the 1992 SITE Demonstration of the ECO LOGIC
Gas-Phase Chemical Reduction Process in Bay City, Michi-
gan, several advancements have been made. Further research
and development has focused on optimizing the process for
commercial operations, and improving the design of the soil/
sediment processing unit. These advances along with relevant
background information are described herein.

Since 1986, ECO LOGIC has been conducting research with
the aim of developing a new technology for destroying aque-
ous organic wastes, such as contaminated harbor sediments,
landfill soil and leachates, and lagoon sludges. The goal was a
commercially viable chemical process that could deal with
these  watery  wastes  and also  process stored wastes  (e.g.
contaminated soils, solvents, oils, industrial wastes, pesticides
and chemical warfare agents). Other companies and agencies
at that time were focusing their efforts  primarily on incinera-
tion and were investigating a variety of predestruction clean-
ing or dewatering processes to deal  with the  problem of
aqueous wastes. The process  described in this paper was
developed with a view to avoiding the  expense and technical
drawbacks of incinerators, while still providing high destruc-
tion efficiencies and waste volume capabilities.

Following bench-scale testing supported by the National Re-
search Council, a lab-scale process unit was constructed in
1988  and tested extensively. Based on the results of these
tests,  a mobile pilot-scale unit was constructed with funding
support from the Canadian Department of National Defense.
The pilot-scale plant was completed  and commissioned in
1991. It was taken through a preliminary round of tests at
Hamilton Harbor, Ontario, where the  waste  processed was
coal-tar-contaminated harbor sediment. That demonstration
received funding from both Environment Canada's Contami-
nated Sediment Treatment Technology Evaluation Program
and the Ontario Ministry of Environment's  Environmental
Technologies  Program. In 1992,  the  same unit was taken
through a second round  of tests  as  part of EPA's SITE
program in Bay City, Michigan.  This  demonstration was
partially funded by the Environment  Canada Development
and Demonstration of Site Remediation Technology Program,
the Ontario Ministry  of Energy and Environment Environ-
mental Technologies Program and the  Canadian Department
of National Defense Industrial Research Program. In this test
program, the  pilot-scale unit processed PCBs in aqueous,
organic and soil matrices. This paper describes the process,
the commercial-scale system under construction, and the re-
sults of demonstration testing in Canada  and the United
States.

Process Chemistry

The process involves the gas-phase reduction of organic com-
pounds by hydrogen at temperatures of 850°C  or higher.
Chlorinated hydrocarbons, such as PCBs and polychlorinated
dibenzo-p-dioxins (dioxins), are chemically reduced to meth-
ane and HC1, while  nonchlorinated organic  contaminants,
such as PAHs, are reduced substantially to methane and minor
amounts of other light hydrocarbons. The HC1 produced can
be recovered as acid or scrubbed out in  a  caustic  scrubber
downstream of the process reactor.

Figure B-l shows some of the reduction reactions, including
intermediate steps, for the destruction of a variety of contami-
nants using the ECO LOGIC Process. Unlike oxidation reac-
tions,  the efficiency of these reduction reactions is enhanced
by the presence of water, which acts as a reducing agent and a
source of hydrogen. The water shift reactions shown produce
hydrogen, carbon monoxide, and carbon dioxide from meth-
ane and water. These reactions can be used at higher efficien-
cies by subjecting scrubbed methane-rich product gas to cata-
lytic steam  reforming,  reducing the requirements  for pur-
chased hydrogen.

A benefit of using an actively reducing hydrogen atmosphere
for the destruction of chlorinated organic compounds, such as
PCBs, is that no formation of dioxins or furans occurs. Any
dioxins or furans in the waste  are also destroyed effectively.
The reducing hydrogen atmosphere  is maintained at more
than 50% hydrogen (dry basis) to prevent formation of PAHs.
This makes  the scrubbed recirculation gas suitable for con-
tinuous monitoring using an on-line CIMS. By  measuring the
concentrations of intermediate reduction products, the CIMS
produces a continuous indication of DE.

SE25 Commercial-Scale Process  Unit

Figure B-2 is a schematic of the reactor where the destruction
of the  waste takes place. The various input streams are in-
jected through several ports mounted tangentially near the top
of the reactor.  Special nozzles are used to atomize liquid
wastes to accelerate  liquid vaporization. The gas mixture
                                                       29

-------
 Cl
           Cl
                     5H2
 ci
             ci
                                      O
+ 4HCI
                        PCB molecule and hydrogen react to produce benzene
                        and hydrogen chloride
                    23 H2
                                              + 4HCI + 2H2O
                                   14CH4
            9H2
                           6  CH4
                                                                     Dioxin molecule and hydrogen react to produce ben-
                                                                     zene, hydrogen chloride, and water
                        PAH molecule and hydrogen react to produce methane
                        Benzene and hydrogen react to produce methane
                     H2
                                    n  CH4
                        Hydrocarbons and hydrogen react to produce methane
CH4 +  H2O
                               Water Shift Reactions

                           CO +  3H2
                        Methane and water react to produce carbon monoxide
                        and hydrogen
 CO  + H2O
                          CO2 + H2
                        Carbon monoxide and water react to produce carbon
                        dioxide and hydrogen
Figure B-1.
               ECO LOGIC process reactions.
swirls around a central stainless steel tube and is heated by 18
vertical radiant tube heaters with internal  electric heating
elements. By the time it reaches the bottom of the reactor, the
gas mixture has reached a temperature of at least 850°C. The
process reactions take place from the bottom of the central
tube onward and take less than one second to complete.

Figure B-3 is a process schematic of the entire system, includ-
ing the reactor. Most of the system components are mounted
on highway trailers for ease of mobility. The reactor trailer
houses the reactor, the electric heating control  system, the
scrubber system, the recirculation gas blower,  the recircula-
tion gas heater,  and the watery waste  preheater vessel. A
second trailer contains the main power distribution room, the
dual-fuel steam boiler, the  catalytic steam reformer, and an
auxiliary burner for excess product gas. Cooling water for the
scrubbing system is generated by skid-mounted  evaporative
coolers, and scrubber stripping operations are carried out on a
small skid situated near the  boiler. The product gas compres-
sion and storage system is also skid-mounted to allow flexibil-
ity in site layout. For processing soils and other solids, the
thermal desorption mill (TDM) is housed on a separate trailer,
and the sequencing batch vaporizer (SBV) is a skid-mounted
unit. The process control system, gas analyzer systems, and
command center are housed in a standard office trailer. Sev-
eral  feed systems are available for various types of wastes,
depending on whether watery waste, oil waste, or solid waste
is being processed. Watery  waste is preheated in a preheater
vessel  using steam from the boiler. The contaminated steam
                                                         from the preheater vessel is metered into the reactor at a rate
                                                         determined by the process control system. Hot contaminated
                                                         liquid exits the bottom of the preheater vessel at a controlled
                                                         flow rate and enters the reactor through an atomizing nozzle.
                                                         Oil waste can be metered directly from drums into atomizing
                                                         nozzles using a diaphragm pump.

                                                         Solid wastes such as soil or decanted sediment are decontami-
                                                         nated in the TDM with the desorbed contaminants being sent
                                                         to the reactor through a separate port. The internal workings
                                                         of the TDM  are designed to vaporize all water and organic
                                                         contaminants in the waste soil/sediment while mechanically
                                                         working the solids into a fine granular mixture for optimum
                                                         desorption. The water vapor and organic contaminants are
                                                         swept into the reactor by a sidestream of scrubbed recircula-
                                                         tion gas.

                                                         Solids such  as  contaminated electrical  equipment  can be
                                                         thoroughly desorbed using the SBVs.  These chambers take
                                                         advantage of the reheated recirculation gas stream to heat the
                                                         equipment and carry contaminants into the reactor. The hy-
                                                         drogen atmosphere is nonreactive with most metals, and there
                                                         are none of the problems with metal oxide formation associ-
                                                         ated with rotary kilns. The SBV can also be used for vaporiza-
                                                         tion of drummed solid chemical wastes, such as hexachloro-
                                                         benzene (HCB). Significant stockpiles of "hex wastes" exist
                                                         and are still  being generated as by-products of chlorinated
                                                         solvent production. Advantages of vaporizing hex wastes
                                                         directly from the drum include decreases in worker exposures
                                                         30

-------
                                                                 	To Scrubber System
                                                                        Waste Injection Ports
                                                                        Reactor Steel Wai!

                                                                        6" Thick 'Pyro-Bloc' "Y"
                                                                        Ceramic Fibre Insulation
                                                                        Stainless Steel Inner Lining

                                                                        Radiant Tubes

                                                                        Stainless Steel Central Tube
                                  To Grit Box
Figure B-2.   Commercial-scale process reactor.
                                                          31

-------
                                                                    Recirculation Gas
                              Reformer     I  Gas
                                      Fuel Heater
Contaminated     Fuel
     Soil       Exhaust
                                                 Electrical
                                                  Energy
                Thermal
               Desorption
                  Mill
                       Desorbed
                        Gases
Fuel for Boiler
Steam Reformer
TDM
                           Cleaned Soil

                  Desorbed Gases
                   Contaminated
                    I Equipment,
                    L
                                                    Hot Watery Waste
 SBV
 Gas
Heater
                 Cleaned Equipment
                                                                                                -S. *~*t40
                                                                                                r^ Storage
                                                                                                             Fuel
Figure B-3.   Commercial-scale process unit schematic.
and fugitive emissions from dram transfer operations, clean-
ing of the drams in place, and segregation of inorganic con-
taminants into the existing drams. The SBV has been tested at
lab-scale with hex waste samples  and PCB-contaminated
electrical equipment.

The product gas leaving the reactor is scrubbed to remove
HC1, water, heat, fine particulates, aromatic compounds and
carbon dioxide. The first stage of the scrubber can be operated
to recover medium-strength HC1, which avoids the cost of
neutralization with caustic. The cost saving can be consider-
able if the waste stream is heavily chlorinated, the acid can
usually be recycled, and generation of large volumes of salty
wastewater is avoided.  The second stage of scrubbing drops
the temperature of the gas to remove  water and completes the
removal of HC1 by caustic packed tower scrubbing. Particu-
late matter, which may  have entered the reactor as dissolved
or suspended solids in the watery waste, is removed in both
the first and second stages of the scrubber and is filtered out of
the scrubber tanks continuously. Heat is removed using plate
heat exchangers on the first two stages and cooling water from
the evaporative cooling system.
                                                  The third stage of scrubbing removes low levels of benzene
                                                  and naphthalene from the gas stream by neutral oil washing.
                                                  The oil is  stripped and regenerated with  the benzene and
                                                  naphthalene going to the inlet of the catalytic steam reformer.
                                                  The fourth scrubbing stage is removal of carbon dioxide using
                                                  monoethanolamine (MEA) absorption. The MEA is stripped
                                                  and regenerated with the carbon dioxide going to the boiler
                                                  stack.

                                                  The scrubber water from the stage-two scrubber leg returns to
                                                  the covered section of the scrubber tank through a drop-tube
                                                  that extends well below the water surface. This acts as a seal
                                                  against air infiltration  and as an emergency pressure relief
                                                  mechanism. There will be  no gas  release if  a short-term
                                                  pressure surge forces gas out of the bottom of this tube since a
                                                  check valve allows the gas to re-enter the system once the
                                                  pressure  returns to normal.  The system normally  operates
                                                  within 10 in. water gauge (0.36 psi) of atmospheric pressure.

                                                  As waste is processed through the system, acid and water are
                                                  produced as effluents.  Filtered acid is pumped to a storage
                                                  tank for further activated carbon treatment prior to recycling.
                                                  Excess water is also filtered and carbon-treated to remove any
                                                        32

-------
trace of organic contamination and is then stored for analysis
prior to discharge.  Carbon can be regenerated on-site in the
SBV, and the minor amount of scrubber sludge produced can
also be processed through the TDM or SBV.

The cooled and scrubbed product gas is a clean dry mixture of
hydrogen, methane, carbon monoxide, and other light hydro-
carbons.  Some of the gas is reheated and recirculated back
into the reactor to increase the methane concentration in the
reactor when processing low-strength wastes. Recirculation
gas is also directed to the TDM as sweep gas, to the SBV as
sweep  gas, to  the catalytic steam reformer  for hydrogen
generation, or to the compressor for storage.

Throughout waste processing  operations, the product gas is
sampled for analysis  by the CIMS and other gas analyzers.
The  CIMS is capable of accurately monitoring up to  10
organic compounds every few seconds at concentrations rang-
ing from percent levels down to ppb levels. It is used as part of
the ECO LOGIC Process to monitor the concentrations of
certain compounds indicative  of the process  DE. The com-
pounds selected for monitoring depend on the waste being
processed.   For  example,   during  PCB  processing,
monochlorobenzene is typically monitored as an indicator of
DE. Low levels of this volatile compound indicate that de-
struction  of the PCBs is proceeding to completion. The CIMS
readings are monitored by the process control system, and the
exceedance of alarm  limits sends a message to the operator
(low-level alarm) or automatically curtails waste input (high-
level alarm). The CIMS also provides a continuous record of
the quality of the product gas being compressed and stored.

Storage of the product gas under pressure permits the analysis
of large batches of gas prior to using it as fuel and allows the
operation of the system in a "stackless" mode. Should the
product gas not meet the quality criteria established, there will
have been no emissions to the environment, and the gas  can
simply be reprocessed. Potential  applications for the stored
product gas  include  heating the  TDM, the catalytic steam
reformer, and the steam boiler. If more gas is generated than
can be used for fuel, an auxiliary burner located at the bottom
of the common boiler/steam reformer stack is used.

Demonstration  Testing

The pilot-scale process plant was tested for the first time at
Hamilton Harbor,  Ontario, in 1991. The waste processed
during those  tests was harbor sediment contaminated with
coal-tar at concentrations of up to 300 g/kg (dry weight basis).
The harbor sediment was injected directly into the reactor as a
5-10% solids slurry, since at that time, the TDM had not been
developed. The system had no catalytic steam reforming or
gas compression and storage capabilities, and the product gas
was  sent directly to the  dual-fuel boiler burner.  DREs of
99.9999% were calculated (see Table B-l), based on the total
organic input  and the  PAHs analysed in the boiler stack
emissions.1 During one test, the liquid waste input was spiked
with PCBs to create a waste with a PCB concentration of 500
mg/kg. The concentration of PCBs in the air emissions, liquid
effluent, and processed solids were below the detection limits
for each, respectively. Based on the detection limits for the
stack sampling trains, a PCB ORE of at least 99.9999% was
achieved.

A second round of tests of the pilot-scale unit was conducted
in 1992 in Bay City, Michigan, as part of the  EPA SITE
program. The wastes processed included oily PCB-contami-
nated water, high-strength PCB oil, and PCB-contaminated
soil.  As part of the demonstration, ECO LOGIC constructed
and commissioned a prototype TDU, which was the forerun-
ner of the current TDM, and demonstrated the capability to
compress and store the product gas generated. The results for
the test program, confirmed by EPA,2 are shown in Table B-2.
The  SITE Program Project Bulletins and TER have been
published and will be followed by the AAR.

The waste oil was  obtained from beneath the Bay City landfill
and was analyzed by EPA to contain 25% PCBs and percent
levels of other chlorinated solvents. The contaminated soil
was  obtained from installation of the sump wells used to
collect the oil, and the contaminated water was groundwater
from the landfill.  The test matrix called for three water/oil
tests, three oil tests, and three soil tests.

The water/oil tests were to be nominally 4000 mg/kg PCBs,
based on injecting the water and oil in a 100:1 ratio through
the atomizing nozzle. Perchloroethene was added as a tracer
compound. The oil tests were designed to process  the high-
strength oil  at higher throughputs  while demonstrating the
ability to compress and store the product gas generated. Steam
was added through a separate port, but liquid water was not
co-injected with the PCB oil. Again, perchloroethene was
added as a tracer compound. After oil waste processing, the
stored gas was directed to the boiler for about 24 hours, and
stack testing by the EPA subcontractor was conducted. The
target ORE for the PCBs was 99.9999%, and this was achieved
Table B-1.
            Hamilton Harbor Performance Test Results
Run
P1
P2
P3
P3
Target
Analytes
PAHs
PAHs
PAHs
PCBs
Cone, in
Waste
(mg/kg)
21 ,000
30,000
30,000
500
Decant
Water Cone.
(M/kg)
483
680
423
ND
Grit
Cone.
(mg/kg)
1.67
7.76
0.37
ND
Sludge
Cone.
(mg/kg)
32.8
56.1
4.3
ND
Stack
Gas Cone.
(|ig/m3)
0.27
0.23
0.14
ND
ORE
(%)
99.9999
99.9999
99.9999
99.9999
ORE = (Total Input - Stack Emissions) / (Total Input)
ND = Non-Detect
                                                        33

-------
Table B-2.    U.S. EPA SITE Program Results

Water/Oil and High-Strength Oil Tests
Run
1
2
3
4
5
6
Soil
Run
1
2
Waste Type
Water/Oil
Tracer
Water/Oil
Tracer
Water/Oil
Tracer
Oil
Tracer
Oil
Tracer
Oil
Tracer
Tests
Waste Type
Soil
Tracer
Tracer
Soil
Tracer
Tracer
Contaminant
PCBs
Perchloroethene
PCBs
Perchloroethene
PCBs
Perchloroethene
PCBs
Perchloroethene
PCBs
Perchloroethene
PCBs
Perchloroethene

Contaminant
PCBs
HCB
OCDD
PCBs
HCB
OCDD
Concentration
(mg/kg)
4,800
4,670
2,450
2,360
5,950
6,100
254,000
33,000
254,000
26,000
254,000
34,000

Concentration
(mg/kg)
538
1 2,400
0.744
718
24,800
1.49
Target
DRE/DE
99.9999
99.99
99.9999
99.99
99.9999
99.99
99.9999
99.99
99.9999
99.99
99.9999
99.99




Achieved
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes

Desorption Efficiency
(%)
94
72
40
99
99.99
99.8
for all six tests. The target DE for the perchloroethene was
99.99% and this was also achieved for all six tests. The SITE
program analytical results for the input concentrations of the
water/oil mixture and the high-strength oil are shown in Table
B-2.

Soils with various contamination levels were mixed  to pro-
duce a relatively homogeneous quantity of soil with a nominal
1000 mg/kg PCB  concentration. The soil test runs were con-
ducted after construction and commissioning of the new TDU
was completed. During the first TDU test, contaminated soil
was processed with a desorption efficiency of 94%, resulting
in a processed soil PCB concentration of 30 mg/kg. This result
was encouraging for a first run, but the desorbed soil was still
above the TSCA disposal criteria of 2 mg/kg. The waste soil
residence time inside the TDU was increased for the  second
run, and a desorption removal efficiency of 99% was achieved
according to SITE program results. The tracer compound used
for the soil tests was HCB, which was spiked at significantly
higher concentrations  than the PCBs. The HCB  was also
contaminated with significant levels of octachlorodibenzo-p-
dioxin (OCDD). The desorption efficiencies achieved for the
HCB and OCDD for Test 2 were 99.99% and 99.8%,  respec-
tively. Due to TSCA permit restrictions, only two runs were
performed for the  third test condition. It should be noted that
the performance of the TDU is independent of the destruction
process. The reactor destruction efficiencies for the desorbed
contaminants were high for both TDU runs.

An additional component of the test program was a 72-hour
endurance test aimed at demonstrating the continuous opera-
tion capabilities of the ECO LOGIC Process. The equipment
operated perfectly and the 72-hour test was concluded suc-
cessfully.

Current Status

The ECO LOGIC Process has been demonstrated to be a high-
efficiency alternative  to incineration for the destruction of
PCB wastes. High water-content wastes and high-strength oils
can both be processed with destruction removal efficiencies of
at least 99.9999%.  The ability to  compress and  store the
product gases  generated during  processing means that no
uncontrolled air emissions occur.

The existing pilot-scale unit is presently available for further
research and development work including new applications
such as mixed wastes (low-level radioactive PCBs), chemical
warfare agents and explosives. Further research and develop-
ment over the last 18 months has focused on optimizing the
process for commercial operations, and improving the design
of the  soil/sediment processing unit. The TDM  design cur-
                                                        34

-------
rently under construction has now achieved excellent results
in lab-scale research and development supported by the Na-
tional Research Council Industrial Research Assistance Pro-
gram. Soils and sediments have been desorbed from ppm and
percent levels down to low ppb levels, which are orders of
magnitude below disposal criteria. Table B-3 shows the re-
sults of a number of lab-scale TDM runs processing a variety
of waste types. The SE25 commercial-scale system now un-
der construction has a design capacity of 100-300 tonnes/day
of contaminated soil or sediment and 20 tonnes/day of PCB
askarel fluid. The cost of processing these waste streams is
estimated at $400 and $2,000 per tonne, respectively. The first
SE25 system is being exported to Australia and will begin
operations with a contract from Australian government agen-
cies for 200 tonnes of obsolete pesticide destruction. Con-
struction of a second SE25 system is also commencing to
serve the North American market, and this unit should be
commissioned for commercial use by the end of 1994. ECO
LOGIC has made proposals to several major North American
corporations and a number of government agencies for the
cleanup of contaminated sites.
Treatability studies using ECO LOGIC'S lab-scale destruction
system are continuing. The lab-scale equipment includes a
TDM for processing soil or sediment, and an SB V suitable for
processing samples of chemical wastes or contaminated elec-
trical equipment. Clients find that treatability studies are a
cost-effective method for determining the applicability and
effectiveness of the ECO LOGIC Process to their waste
problems.

The ECO LOGIC Process is a proven technology for the
destruction of high-strength PCB oil wastes and is suitable for
the destruction of askarel fluids used in electrical equipment
and PCBs and other organic contaminants in soils and sedi-
ments. ECO LOGIC offers a cost-effective alternative to
incineration and can provide a complete on-site destruction
service for the owners of hazardous organic wastes.
Table B-3. Summary of Test Results from the
Thermal


Waste Type
Soil (tarry, oily)

Soil (dry, sandy,
PCB-spiked)

Soil (dry, sandy,
PCB-spiked)
Sediment (muddy, fine,
PCB-spiked)

Sediment (muddy, fine,
PCB-spiked)

Sediment (muddy, fine,
PCB-spiked)
Sediment (muddy, fine)
Sediment (muddy, fine)

Sediment (muddy, fine)

Sediment (muddy, fine)

Sediment (muddy, fine)

Sediment (muddy, fine)
Sediment (muddy, fine)

Sediment (muddy, fine)





Desorption Mill
Waste PCB
Concentration
(ppm)
39

440


520

710


790


750

7.3
8.3

8.3

420

420

2000
1200

8.3





Lab-Scale

Grit PCB
Concentration
(ppm)
0.011

0.0039


0.0016

0.028


0.0097


0.065

0.0029
0.0066

0.0013

0.0017

0.012

0.044
ND (0.011)

ND (0.005)





References

 1  WTC Newsletter, published by the Wastewater Technol-
    ogy Centre,  Environment Canada, No.  2, March 1992.
    Contact: Mr. Craig Wardlaw, Project Scientific Author-
    ity, 905-336-4691.

 2  Technology  Evaluation Report, SITE Program Demon-
    stration, Risk Reduction Engineering Laboratory, U.S.
    EPA, Cincinnati, OH 45268, July 15, 1994. Contact: Mr.
    Gordon Evans, SITE Project Manager, 513-569-7684.
                                                     35

-------
                                           Appendix C
                                          Case Studies
Introduction

Two case studies illustrate the use and performance of the
ECO LOGIC Gas-Phase Chemical Reduction Process.

Case Study C-1:
Bench-Scale Demonstration on
Contaminated Harbor Sediment

Introduction

Environment Canada asked for a series of laboratory tests on
harbor sediment wastes prior to funding a pilot-scale unit. The
Canadian Contaminated Sediment Treatment Technology Pro-
gram provided funding for the tests.

Description

ECO LOGIC designed the 3 kg/hr reactor system to mimic the
operation of the pilot-scale field demonstration unit, to pro-
vide DE data, and to develop the process control and continu-
ous monitoring systems for the pilot-scale work.

As shown in Figure C-1, the reactor (LS) was a single cylin-
drical chamber with a 12-in. diameter and 72-in. length elec-
trically heated by glo-bars passing through the central axis.
The insulated reactor contained a relatively cool area (G)
where solids collected after passing through the reaction zone.
Thermocouples—at three  locations  inside  and outside the
inner stainless steel liner (T1-T6)—measured temperatures.
Liquid waste (L) and hydrogen (H2) flowed into  the reactor at
known, metered rates.

As the gases and fine particulates left the reactor, the CIMS
drew a small sidestream; the remainder of the gas flowed to
the  first condensation flask.  This flask (S) simulated the
scrubber in the pilot system. After the first knockout flask,
most of the gas flow passed through a heat exchanger tube
(HX), condensing the rest of the water in the second knockout
flask (KO).  A valved pump (P) and rotameter (R) drew some
of the gas through an XAD2 resin trap cartridge (X). The
remaining gas was vented (V). Analyses of the scrubber flask
water, the knockout flask water, and the XAD2 resin deter-
mined the reactor's DE.

A second sidestream, drawn from the main stream immedi-
ately after the scrubber flask (S) passed through a quartz tube
furnace (Q), along with air for combustion. This stream simu-
lated the DE obtained by using the boiler and reactor combi-
nation. After drying in a water knockout flask, the gas stream
passed through an XAD2 resin tube to a valved pump and
rotameter.

Monitored process  parameters included the hydrogen flow
rate, reactor pressure, reactor temperatures, boiler tempera-
ture, scrubber flask temperature, knockout flask temperature,
and quartz oven temperature. The CIMS also monitored and
recorded concentrations of 10 organic compounds.

Testing Protocol

Each run processed about 5 liters of sediment over a period of
several hours. Environment Canada provided eight sediment
samples: four from Hamilton Harbor, two from  Sheboygan
Harbor, two from Thunder Bay Harbor, and two from Hamilton
Harbor that were subsequently spiked with trichlorobenzene
(Table C-1). ECO LOGIC performed analysis on the samples,
except for the metals analyses, which were done by XRAL
Environmental.

Half of the samples were split for duplicate analysis by the
Wastewater Technology Center Laboratory, whose personnel
also observed most of the test runs. For two test runs, the
laboratory analyzed samples for dioxins, furans, PCBs, PAHs,
organo-chlorines, base  neutrals, chlorobenzenes,  chlorophe-
nols, and metals; for the other runs, only target compounds.

To begin the test, the operator charged a measured amount of
well mixed sediment to the waste flask (boiler). After the test,
the  operator emptied the flask and recirculation pump and
then flushed them with a measured volume of water. The test
operator combined some of the exit sample extracts prior to
analysis. Table C-2  lists the final five output samples.

Data Summary

Table C-3 summarizes the results of the ten test runs requested
by Environment Canada. Runs 1 and  2 processed Hamilton
Harbor sediment diluted to  about 4% solids. Both tests ob-
tained a 99.99% DRE. Run 1 samples received full analysis;
there were no dioxins or furans in any of the samples, includ-
ing the waste. Runs 1 and 2 achieved a solids reduction of
about 80%; the remaining grit contained no PAHs. A metals
analysis of the grit from Run 1 revealed sodium, manganese,
                                                      36

-------
                                                                                   Air
                                                                                                     KO
Figure C-1.   Bench-scale reactor system schematic diagram.
                                                          37

-------
Table C-1.
Run
1
2
3
4
5
6
7
8
9
10






Table C-3.

Run
1
2
3 PAHs
CB
4 PAHs
CB
5
6
7
8
9
10
Sediment Samples
Input
Source Analysis
Hamilton Full
Hamilton Target
Ham/TCB Target
Ham/TCB Target
Hamilton Target
Sheboygan Target
Thunder Bay Target
Hamilton Full
Sheboygan Target
Thunder Bay Target
Table C-2.
Sample
Reactor grit
Scrubber catch

Scrubber exit
Scrubber exit
Incinerator exit
Performance Results

ORE*
99.9939
99.9960
99.9980
99.9990
99.9944
100.0000
99.991 1
99.9990
100.0000
99.9836
99.9941
99.9960

Output
Analysis
Full
Target
Target
Target
Target
Target
Target
Full
Target
Target
Residue Streams
Type
Solids
Solids
Liquid
Solids
Liquid
Gas
Liquid
Gas


DE
67.9
85.2
61.3
99.9954
81.6
99.9999
-150.2
99.4
100.0
-1.1
99.8
96.8

Target WTC Lab
Compound Duplic.
N/A No
PAHs Yes
PAHs/CBs Yes
PAHs/CBs No
PAHs No
PCBs No
CPs Yes
N/A Yes
PCBs Yes
CPs No

Component Source
Reactor
Scrubber flask, lines
Scrubber flask
Heat exchanger, KO flask, lines
Heat exchanger, KO flask, lines
XAD2 resin
Knockout flask
XAD2 resin

Recirc. Solid
Rate Content
98.4 4.2
98.4 3.6
98.4 3.1

98.4 3.2

98.4 3.0
98.4 3.0
98.4 17.6
98.4 3.0
98.4 3.5
98.4 8.0

Mass
Balance
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes







Solids
Reduction
87.4
76.7
49.3

70.9

9.7
2.7
32.6
7.0
25.8
43.4
*  DREs based on total organics fed and PAHs analyzed in the stack.
                                                                    38

-------
phosphorous, titanium, copper, and lead. ECO LOGIC sug-
gested that some of the metals could be artifacts from the
reactor's stainless steel inner liner because concentrations of
manganese, titanium, copper, and lead in the waste were low.
The primary metals in the  waste  included iron, calcium,
sulfur, aluminum, magnesium, sodium, and phosphorous.

Runs 3 and 4 processed Hamilton Harbor sediment that was
diluted to  about 3% solids and spiked with approximately
1,000 ppm trichlorobenzene. These runs obtained a 99.99%
ORE  for  the PAHs; for trichlorobenzene,  99.999% and
100.0000%, respectively. Solids reduction from destruction
of organic materials averaged 60%.

Runs 6 and 9 processed Sheboygan Harbor sediment con-
taminated  with PCBs.  The waste was diluted to about 3%
solids. The resultant PCB concentration in the feed ranged
from 5 to 7 ppm. The runs achieved DREs  of 99.999% and
99.99%; solids reduction averaged 15%.

Runs 7 and 10 processed Thunder Bay sediments contami-
nated with chlorophenols. ECO LOGIC reasoned that the
sample matrix of the  waste may  have  caused analytical
procedure  problems; the values obtained did not match ECO
LOGIC'S expectations. There were no problems in analyzing
the other samples; ECO LOGIC reported DREs of 100.0000%
[sic]  and 99.999% for the two runs. Solids reduction was
40%.

Runs 5 and 8 processed Hamilton Harbor sediment diluted to
about 3%  solids. A large amount of naphthalene formed
during these runs, resulting in net negative total DEs.  How-
ever, naphthalene combustion in the quartz tube furnace was
good. The  DRE for Run 5 was 99.99%. Glassware breakage
lost the Run 8 sample  for the furnace XAD; the WTC lab
audit analysis provided the DRE for Run 8.

A larger-scale test will likely provide better DREs because
ECO LOGIC encountered a number of problems involving
size restrictions. As these will be eliminated in pilot-scale
tests, ECO LOGIC expects even better results than at bench
scale.

Conclusions

The conclusions from this study were as follows:

 •  The bench-scale system demonstrated that the gas-phase
    chemical reduction reaction can decontaminate polluted
    harbor sediment.

 •  PAHs, especially large ones (coal), were more difficult
    to process than chlorinated wastes.

 •  Harbor sediments can contain amounts of organic  mate-
    rial sufficient to show a  substantial volume decrease
    after treatment. The treated solids were free of organic
    material.

 •  The test program demonstrated proof-of-concept on ac-
    tual wastes.
Based on the interim results of the bench-scale test program,
Environment Canada and Environment Ontario contracted
ECO LOGIC to undertake a demonstration test program at
Hamilton Harbor, funded by the Environment Canada Con-
taminated Sediments Treatment Program  and the  Ontario
Environmental Technologies Program.

Case Study C-2:
Pilot-Scale Demonstration of
Contaminated Harbor Sediment

Introduction

ECO LOGIC'S research and development on the treatment of
harbor sediment began with laboratory testing of surrogate
compounds, followed by the bench-scale tests described in
Case Study C-l. The Canadian National Research  Council
Industrial Research Assistance Program, the Defense Indus-
trial Research Program, the Environment Canada Contami-
nated Sediments Treatment Program, the Environment Ontario
Environmental Technologies Program,  and ECO  LOGIC
funded the work.

ECO LOGIC began construction of the mobile pilot-scale
field unit during laboratory testing and undertook a demon-
stration program—the topic of this case study—at Hamilton
Harbor, Ontario, Canada.  ECO LOGIC installed its equip-
ment on Hamilton Harbor Commission property, adjacent to a
highly contaminated section of the harbor. The test ran from
April to August, 1991.

Description

The pilot-scale research and development proceeded in four
phases. First, laboratory testing proved the gas-phase chemi-
cal reduction reactions and established parameters for  resi-
dence time,  temperature,  and  ratios  of hydrogen-to-waste.
ECO LOGIC conducted these tests using  laboratory glass-
ware and a quartz tube furnace as a  reactor. Next,  a larger
reactor (Case  C-l)  processed 5-10  liters  of actual waste
samples, primarily harbor and  lagoon sediment. This estab-
lished the capability of the process to treat actual wastes in
complex matrices. During the third phase, ECO LOGIC de-
veloped a computer model to simulate operation of the reactor
system. At the fourth phase, they built the pilot-scale reactor
system and undertook proof-of-concept testing. This phase
included materials, component, and system integrity tests to
ensure  leak-free system operation  at the test temperatures,
flow rates, and pressures.

ECO LOGIC designed the pilot-scale demonstration system
to process contaminated harbor sediment.  The system  con-
sisted of an electrically heated reactor that heated and mixed
the watery sediment and hydrogen; a scrubber that removed
particulates, heat, water, and hydrogen chloride from the gas
product; a recirculation system that reheated most of the clean
dry product gas for reinjection into the reactor; a boiler fueled
by propane and the gas product; and a heat exchanger that
steam-heated the watery sediment prior to injection into the
reactor. Two standard drop-deck highway trailers held the
entire system.
                                                     39

-------
 Testing Protocol

A cable arm bucket removed approximately 12 m3 of contami-
nated sediment from the Sherman Inlet of Hamilton Harbor
and  placed it in a 30  m3 lugger box. The bucket crane
transferred the lugger box of contaminated sediment to the
demonstration site spill pad and positioned it at the rear of the
boiler trailer.

ECO LOGIC took water quality samples and measurements
before the  removal, immediately afterward, 24  hours later,
and 72 hours later. The laboratory analyzed water and sedi-
ment samples for PCBs, PAHs, oil, grease, and heavy metals.
Bioassays were performed on daphnia and fat-head minnows.

Characterization Tests—After commissioning  and system
integrity tests, ECO LOGIC processed a surrogate waste of
clean water and diesel fuel under a variety of conditions. ECO
LOGIC designed the characterization tests to evaluate system
performance on actual harbor sediment while operating within
design parameters, using  various feed rates  and sediment
concentrations.  During these short (2- to 4-hour)  tests, Air
Testing Services of  Toronto  measured  organic compound
emission rates (PAH, PCB, chlorobenzene, chlorophenol, di-
oxin, and furan) from the boiler stack emissions using the
Canadian regulatory  methods.  The stack gas organic com-
pound concentrations were within the regulatory limits for
ambient air; the DEs were  satisfactory.

Effluents from the process consisted of reactor grit and slag,
scrubber decant water, and scrubber sludge. These streams
were analyzed for PAHs, PCBs, and metals. The grit and slag
were free of organic contamination and contained only the
inorganic and  metallic components of the harbor sediment.
The Wastewater Technology Center (WTC) collected the grit
and slag from the program to evaluate disposal options.

ECO LOGIC tested the decant water for organic compounds
and metals; in all cases it was organic-free. Most of the metals
                  in the sediment exited with the grit. The decant water repre-
                  sented the largest volume of effluent from the process, equiva-
                  lent to the amount of water processed with the sediment. In all
                  cases, the decant water was acceptable for disposal at munici-
                  pal sewage treatment plants.

                  The scrubber sludge represented a minor by-product of the
                  process and contained primarily lime, carbon, fine  particu-
                  lates, and water. The sludge resulted from recirculating the
                  scrubber water;  some organic contamination of the sludge
                  occurred. As ECO LOGIC gained experience with the scrub-
                  ber, they modified system operating parameters to minimize
                  the amount of sludge  production. Although the sludge could
                  be sent to a landfill, ECO LOGIC found it more economical to
                  recycle this small effluent stream into the water input stream.

                  Performance Tests—ECO LOGIC then undertook perfor-
                  mance testing to demonstrate the capability of the system to
                  operate for  longer periods (days),  and to measure  a wider
                  range of emissions during longer sampling periods. During
                  the third performance test, they spiked the sediment waste
                  with PCB-contaminated oil to a concentration of 110 ppm.

                  The performance test effluents paralleled those produced dur-
                  ing characterization tests—the  scrubber decant could be sent
                  to a POTW, and the scrubber sludge was suitable for landfill
                  disposal. Sludge production totalled about one percent of the
                  volume of sediment processed. Hence, it could be economi-
                  cally  recycled into the waste input stream.

                  Data Summary

                  The test program progressed in three stages: six initial charac-
                  terization tests (Cl - C6), followed by a short period for
                  system modification and repair; five additional characteriza-
                  tion tests (C7 - Cll),  a preperformance test (C12); and three
                  performance tests (PI - P3). Table C-4 lists the compounds
                  analyzed in the waste input and effluent streams. Table C-5
                  lists the  characterization test stack components;  Table  C-6,
                  the performance test compounds.
Table C-4.
Metals




Waste Input and Effluent Analysis Components
Aluminum
Antimony
Barium
Beryllium
Cadmium
Calcium

Chromium
Copper
Iron
Lead
Magnesium
Manganese

Nickel
Phosphorous
Potassium
Selenium
Silver
Sodium
Polychlorinated aromatic compounds
Polychlorinated
biphenyls
PAHs
                                        Naphthalene
                                        Acenaphthylene
                                        Acenaphthene
                                        Fluorene
                                        Phenanthrene
                                        Anthracene
                          Fluoranthene
                          Pyrene
                          Benzo(a)anthracene
                          Chrysene
                          Benzo(b)fluoranthene
                          Benzo(k)fluoranthene
Benzo(a)pyrene
lndeno(1,2,3-cd)pyrene
Dibenzo(a,h)anthracene
Benzo(g,h,i)perylene
                                                        40

-------
Table C-5.    Characterization Test Air Sampling Components
Polychlorinated aromatic compounds  Chlorobenzenes            Polychlorinated dibenzofurans    Polychlorinated dibenzo-p-dioxins

                                  Polychlorinated biphenyls    Chlorophenols
Polyaromatic hydrocarbons
Naphthalene

Acenaphthylene

Acenaphthene

Fluorene

Phenanthrene

Anthracene
Fluoranthene

Pyrene

Benzo(a)anthracene

Chrysene

Benzo(b)fluoranthene
Benzo(k)fluoranthene

Benzo(a)pyrene

ldeno(1,2,3-cd)pyrene

Dibenzo(a,h)anthracene

Benzo(g,h,i)perylene
Combustion gases
Oxygen
Water vapor
                                                                                      Carbon dioxide
Characterization Tests—Table C-7 summarizes the results
of the characterization tests. In all 12 tests, the PAH  stack
concentrations were low; they consisted primarily of naphtha-
lene. Benzo-a-pyrene was not detected in any of the tests. The
concentrations of total PAHs in the stack were below the
Ontario  Clean Air Program ambient air quality (AAQ) limits
proposed for both naphthalene (30 |J,g/m3) and coal tar pitch
volatiles (1 |^g/m3). The chlorobenzene emission concentra-
tions also were below the Clean Air Program AAQ guideline
(35 |J,g/m3 for 1,2,4-trichlorobenzene). None of the  sample
trains contained chlorophenols, PCBs, or dioxins.  Furans
were detected during Characterization Test 5; ECO LOGIC
attributes this to reactor pressure instability, resulting from a
malfunctioning steam flow meter. The malfunction allowed
the flow of waste  steam  to the reactor to increase substan-
tially, causing the residence time,  temperature, and DE to
drop, producing  furans  from  incomplete destruction of
trichlorobenzene.

The residuals from the destruction process included grit from
the bottom of the reactor, decant water from the scrubber, and
scrubber sludge. The first six samples of grit contained mainly
water, presented as water concentrations in units of |J,g/L
(ppb). The next six tests were reported as dewatered concen-
trations  of the solid material in units of ng/g (ppb). In general,
the grit  contained a total PAH concentration of several ppm.
No PCBs appeared in the grit during any tests. The iron, zinc,
and magnesium levels in the grit make it potentially  recy-
clable as an ore for the steel industry. WTC collected the grit
to test for various disposal or recycling options.

The laboratory analyzed the  decant water for PAHs, PCBs,
and metals. It did not contain detectable levels of PCBs for
any of the tests. The levels of PAHs and metals in the decant
water met the standards for sewer disposal.

Scrubber sludge consisted mainly of lime, carbon, fine par-
ticulates, and  water; the  sludge  water characteristics  were
similar to those of the decant water.  The sludge was contami-
nated with PAHs  to some extent. Sludge metal content was
low but increased as the  sludge concentrated. Although the
sludge was suitable for landfilling, it was more economical to
recycle it into the water input stream.
                       Performance Tests—Table C-8 summarizes the results  of
                       the performance tests. During these tests, the system operated
                       24 hr/day, with periodic stoppages for maintenance.

                       Performance test stack emission sampling was more extensive
                       than sampling for characterization tests. ECO LOGIC used
                       three stack sampling trains per test to measure semivolatile
                       trace organic compounds, VOCs, and metals.  The semivola-
                       tile (MM5) train sampled the stack gas for PAHs,  PCBs,
                       chlorobenzenes, chlorophenols, dioxins, and furans; the vola-
                       tile train (VOST) and metals train, for the compounds and
                       metals shown in Table C-6. Continuous analyzers sampled the
                       stack gas for oxygen, carbon dioxide, carbon monoxide, total
                       hydrocarbons, water vapor, sulfur dioxide, and nitrogen ox-
                       ides. The gaseous emissions were all within AAQ guidelines.
                       The PAH  and chlorobenzene concentrations  in  the boiler
                       stack were below the  Clean Air Program AAQ limits. There
                       were no detectable emissions of chlorophenols, PCBs, diox-
                       ins, or furans. The results of the VOST testing indicated that
                       all of the levels were lower than AAQ guidelines. The metals/
                       paniculate train measured metals and paniculate emissions,
                       which also met AAQ guidelines.

                       The feedstock grit, decant water, and scrubber sludge were
                       analyzed for PAHs, PCBs, and metals; the feedstock analysis
                       also included solids content and total organic content.  The
                       effluents from the performance tests were  similar  to the
                       characterization tests.  The grit was almost free of PAHs and
                       contained no detectable PCBs. It had a total PAH concentra-
                       tion ranging from less than 1 ppm for Test 3 to 8 ppm for Test
                       2. Most of the contamination consisted of naphthalene. PCBs
                       were not detected in the grit from any tests. The grit contained
                       iron, calcium, magnesium, aluminum, potassium, and zinc.

                       Analyses of the decant water for PAHs, PCBs, and  metals
                       indicated no detectable levels of PCBs for any tests. PAHs
                       and metals in the decant water were well  below acceptable
                       limits for sewer disposal.

                       PAHs  contaminated the scrubber sludge. This sludge, when
                       combined with the sludge produced during the characteriza-
                       tion tests, was suitable for landfill disposal but could also have
                       been reprocessed. The volume of sludge produced during the
                                                        41

-------
Table C-6. Air Emission Sampling Components
Participate Material
Metals












Combustion gases



Polychlorinated aromatic compounds


PAHs







VOCs













Components
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Oxygen
Carbon dioxide
Carbon monoxide
Water vapor
Chlorobenzenes
Polychlorinated biphenyls
Polychlorinated dibenzofurans
Naphthalene
Acenaphthylene
Acenaphthene
Fluorene
Phenanthrene
Anthracene
Fluoranthene
Pyrene
Acetone
Dichloromethane
Hexane
Benzene
2-Methylhexane
3-Methylhexane
Heptane
Methylcyclohexane
Toluene
Perchloroethylene
Decane
Undecane
Pentylcyclohexane
Dichlorodifluoromethane

Nickel
Phosphorous
Potassium
Selenium
Silver
Sodium
Sulfur
Tellurium
Thallium
Tin
Titanium
Zinc

Sulfur dioxide
Nitrogen oxides
Total hydrocarbons

Chlorophenols
Polychlorinated dibenzo-p-dioxins

Benzo(a)anthracene
Chrysene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Benzo(a)pyrene
lndeno(1 ,2,3-cd)pyrene
Dibenzo(a,h)anthracene
Benzo(g,h,i)perylene
Trichlorofluoromethane
Methylpentane
Methylcyclopentane
Octane
Dodecane
Tridecane
Naphthalene
Ethylbenzene
Meta/Paraxylene
1 ,4-Dichlorobenzene
Methylnaphthalene
C9-C12 Aliphatics
C5-C10 Heterocompounds
C4 Substituted Benzene
42

-------
Table C-7. Characterization Test Results
Test number 1 2
Waste input (kg)
% Solids
% Organics
Stack concentration
(ng/DSCM)
PAHs
Chlorobenzene
Chlorophenol
Emission rates (ng/s)
PAHs
Chlorobenzene
Chlorophenol
Reactor grit
PAHs (ng/L)*
PAHs (ng/g)*
Metals (ng/ml)**
Metals (ng/g)**
Scrubber decant H2O
PAHs (ng/L)*
Metals (|ig/ml)**
Scrubber sludge
PAHs (ng/L)*
Metals (ng/ml)**
Waste input (kg)
% Solids
% Organics
Stack concentration
(ng/DSCM)
PAHs
Chlorobenzene
Chlorophenol
Emission rates (ng/s)
PAH
Chlorobenzene
Chlorophenol
Reactor grit
PAHs (ng/L)*
PAHs (ng/g)*
Metals (ng/ml)**
Metals (ng/g)**
Scrubber decant H2O
PAHs (ng/L)*
Metals (ng/ml)**
Scrubber sludge
PAHs (ng/L)*
Metals (ng/ml)**
200
5
30

1000
70
0
66
4.5
0
2.3
1.5
ND-0.05
66.0
ND-0.39
240
9
28

190
11
0
17
0.98
0
252.1
ND-3.61
1.1
ND-0.17
4.5
ND-0.84
250
5
30

999
100
0
96
9.8
0
3.6
ND-0.26
0.8
ND
48.2
ND-0.03
240
8
28

620
28
0
37
1.6
0
617.1
ND-550
1.1
ND-0.07
34.0
ND-1.64
3
350
5
30

260
19
0
19
1.4
0
2.2
ND-0.06
1.6
ND-0.06
30.6
ND-0.02
240
8
28

160
11
0
11
0.77
0
192.4
ND-220
2.4
ND-0.2
89.3
ND-0.66
4
400
5
28

1000
510
0
82
40
0
43.5
ND-8.52
0.5
ND-0.65
30.4
ND-0.09
240
8
28

250
13
0
18
0.92
0
61.5
ND-260
2.5
ND-0.07
42.2
ND-0.85
5
250
6
32

140
34000
0
8.9
2100
0
4.1
ND-9.72
1.9
ND-0.12
25.3
ND-0.44
240
9
29

280
11
0
20
0.84
0
423.0
ND-250
5.4
ND-0.05
78.3
ND-5.18
6
350
6
32

460
27
0
33
1.9
0
10.2
ND-6.04
2.1
ND-0.12
41.5
ND-0.14
122.5
6
32

370
10
0
20
0.72
0
292.4
ND-240
7.8
ND
1124.2
ND-40.7
*  Average of 16 PAH compounds.
**  Reporting only 40 CFR 261 Appendix VIII metals.
ND Not detected.
                                                                  43

-------
Table C-8. Performance Test Results
performance tests was about one percent of the volume of
waste sediment feed.
Test number
Stream
Waste input (kg)
% Solids
% Organics

1
850
7
30

Stack concentrations (ng/DSCM)
PAHs 270
Chlorobenzene 8.1
Chlorophenol
VOCs*
Metals (ng/DSCM)
Particulates (ng/DSCM)

Stack emission rates (ng/s)
PAHs
Chlorobenzenes
Chlorphenol
VOCs*
Metals (ng/s)
Particulates (ng/s)

Reactor grit
PAHs (ng/g)**
Metals (ng/g)***
Scrubber decant H2O
PAHS (ng/L)
Metals (ng/ml)

Scrubber sludge
PAHS (ng/L)
Metals (ng/g)
0
1821.5
1650
620


18
0.71
0
159.8
120
45


104.1
ND-418

30.1
ND-0.22


2046.9
ND-120
2
900
10
30

230
8.0
0
906.2
1275
622


26
0.87
0
98.7
116
57


484.9
ND-360

42.5
ND-0.08


3507.2
ND-203
3
600
10
30

140
68
0
5151.9
2060
1990


12
6.0
0
452.1
142
137


22.8
ND-140

26.4
ND-0.003


265.8
ND-106
During Performance Test 3, ECO LOGIC spiked the harbor
sediment with PCB oil to a level of 110 ppm to demonstrate
that the process could destroy PCB -contaminated material.
The analytical results found no detectable concentrations of
PCBs in the stack gas, the reactor grit, the scrubber decant
water, or the scrubber sludge. Chlorinated compounds such as
dioxins, furans, and chlorophenols were not detected in the
stack emissions. Based on the detection limits, ECO LOGIC
demonstrated a 99.9999% ORE.

Conclusions

The level of organic emissions produced by Performance Test
3, in which PCB -spiked waste was processed, demonstrated
that the process is suitable for destruction of PCB -contami-
nated material, verifying the bench-scale and laboratory-scale
research. PCBs were not detected in the stack gas, the reactor
grit, the scrubber decant water, or the scrubber sludge. The
stack emissions did not contain dioxins, furans, or chlorophe-
nols. ECO LOGIC demonstrated a 99.9999% ORE.

The process operated successfully for extended periods. Al-
though grit blockages and heating element breakage caused
interruptions in processing, ECO LOGIC has since corrected
both problems.
Key Contacts

Craig Wardlaw
Wastewater Technology Center
867 Chemin Lakeshore Road
P.O. Box 5068
Burlington, Ontario L7R 4L7
Panarta
*    Average of reported values.
**    Average of 16 PAH compounds.
***   Reporting only 40 CFR 261 Appendix VIII metals.
ND   Not detected
Phone: 416-336-4691

James Nash
ELI Eco Logic International, Inc.
143 Dennis St.
Rockwood, Ontario NOB 2KO
Canada
Phone: 519-856-9591
Fax: 519-856-9235
                                                         44

-------