EPA 540/G-87/006
                            OSWER DIRECTIVE 9355.3-03
                                      February 1988
GUIDANCE DOCUMENT FOR PROVIDING
     ALTERNATE WATER SUPPLIES
  Office of Emergency and Remedial Response

     U.S. Environmental Protection Agency

           Washington,  DC 20460

-------
                                             NOTICE
    The information in this document has been funded, wholly or in part, by the United  States Environmental
Protection Agency under Contract No. 68-01-6939 to COM Federal  Programs Corporation. It has been subject
to the Agency's peer and administrative review and has been approved for publication as an EPA document.

-------
                                               FOREWORD
Section 118(a) of the  Comprehensive Environmental
Response, Compensation, and  Liability Act (CERCLA) of
1980 was amended by the  Superfund Amendments and
Reauthorization Act of 1986 (SARA) to "give a  high
priority to  facilities  where  the  release of hazardous
substances or pollutants or  contaminants has resulted in
the closing of drinking water  wells or has contaminated a
principal drinking water supply." This guidance document
was prepared to  assist Superfund contractors and  on-
scene Federal, State, and local officials with the planning
and implementation  of  alternate  water  supplies  at
uncontrolled hazardous waste sites.  The term "alternate
water supplies" includes, but is  not  limited to,  drinking
water and household water supplies.

Provision of an alternate water supply may be appropriate
when existing supplies are contaminated or are threatened
by contamination in the near future. The implementation of
alternate  water supplies  can be performed under the
removal program or the remedial  program,  depending on
the specific conditions of the site  and whether it is on the
National Priorities  List (NPL).  The four  implementation
options available are as follows:

   1. Time-Critical Removal Actions - These actions
     are performed at sites  where numeric action  levels
     established by  removal authority are  exceeded or
     site-specific  factors indicate  the  presence  of  a
     serious health threat. These  actions are only taken in
     cases where it is determined that action is  required
     within 6 months.

   2. Non-Time-Critical Removal  Actions  -  These
     actions are performed  at sites which meet the same
     criteria as above (numeric levels exceeded or site-
     specific factors) but do not require action  within 6
     months. These actions can   be  performed  by
     removal personnel using  Emergency  Response
     Cleanup Services (ERCS)  contractors or a  site-
     specific  contractor. These  actions  may   also  be
     performed as Expedited  Response Actions (ERA).
     ERAs  are conducted   under removal  authority  by
     remedial contractors and  personnel.  ERAs  are
     limited to sites listed on the National Priorities List
     (NPL).

  3. Operable Unit Remedial Action - These  actions
     are performed at NPL  sites  where  short-term
     threats to the human population exist. These actions
     are performed under remedial  authority  using  an
     abbreviated  remedial  investigation  and feasibility
     study  (RI/FS) process  and  require  State cost-
     sharing. Operable units  should  be  consistent with
     the final remedy for the site.

  4. Final  Remedial Action  -  These actions  are
     performed at sites which may present  a  long-term
     health threat  but no  immediate  or  short-term
     threats. These  actions are performed under the
     remedial program as  part of a final remedy and are
     preceded by a full RI/FS.

This document provides guidance for those sites  that do
not  require a time-critical removal action  but do  require
provision of an alternate water supply as either  a non-
time-critical  removal action or a remedial action before
implementation of a final remedy can be achieved. Those
actions are described in items two and three above. Items
one and four are outside the scope  of this guidance. The
ability to implement alternate water supplies  as non-tirne
critical  removal  actions  is  subject  to site-specific
considerations and  available  resources,  particularly at
non-NPL sites.  Further discussion of the  appropriate
authority for proposed actions is presented in Section
3.1.5. It is important to emphasize that this guidance does
not provide direction for situations requiring an emergency
or time-critical  response. Such  activities  should  be
performed   in accordance with  Superfund  Removal
Procedures (EPA 1987) guidance.

The guidance presented in this document was developed
using information from the National  Oil  and Hazardous
Substances Contingency Plan (NCP), other EPA guidance
documents, and experience gained  in the  implementation
of. the Superfund program.
                                                      in

-------

-------
TABLE OF CONTENTS
Section                                                                              Page
1.0  INTRODUCTION	   1-1
2.0   APPROACH  	   2-1
3.0  ALTERNATE WATER SUPPLY SELECTION PROCESS  	   3-1
     3.1   Site Characterization and Determination of Authority	   3-1
          3.1.1  Obtain Available Data 	   3-1
          3.1.2  Review and Evaluate Available Data and Identify Data Gaps  	   3-1
          3.1.3  Conduct Additional Sampling  .		   3-3
          3.1.4  Determine Applicable or Relevant and Appropriate Requirements  	   3-4
          3.1.5  Determine Appropriate Authority  	:	   3-5
     3.2  Determination of Response Scope  	   3-7
          3.2.1  Evaluate Problem Extent  	   3-7
          3.2.2  Develop Demand Requirements 	   3-7
          3.2.3  Prepare Maps	   3-9
          3.2.4  Determine Appropriate Response   	   3-9
     3.3  Preparation of Community Relations Plan   	   3-11
     3.4  Identification, Screening and Analysis of Alternatives  	   3-11
          3.4.1  Identify Alternatives   	   3-11
          3.4.2  Preliminary Screening  	   3-16
          3.4.3  Analysis of Selected Alternatives 	   3-16
          3.4.4  Recommended Alternative	   3-19
     3.5  Prepare EE/CA or FS Report   	   3-19
     3.6  Public Participation  	   3-19
     3.7  Selection of Remedy  	   3-19
 4.0 ALTERNATE WATER  SUPPLY DESIGN AND IMPLEMENTATION  	   4-1
     4.1  Design and Implementation Procedures 	   4-1
          4.1.1  General Consideration  	   4-1
          4.1.2  Treatment Processes and Facilities   	   4-1
          4.1.3  Transmission and Distribution Facilities  	   4-2
          4.1.4  Storage Facilities	   4-2
      4.2  Treatability Studies  	   4-2
          4.2.1  Bench  Scale  	   4-2
          4.2.2   Pilot Scale  	   4-3
      4.3  Contract Documents  	   4-4
      4.4  Contracting Procedure	   4-5
          4.4.1   Lump Sum Contract  	   4-6
          4.4.2   Unit Price Contract	   4-6
      4.5  Contract Provisions  	   4-6
          4.5.1   Change Orders	   4-6
          4.5.2  Special Provision 	   4-7
 5.0  POST IMPLEMENTATION ACTIVITIES 	   5-1
 6.0  REFERENCES	- - -   6-1

-------
APPENDIX  	   PAGE
APPENDIX A      LOCATIONS WHERE ALTERNATE SUPPLIES HAVE BEEN INSTALLED   A - 1
APPENDIX B      AN ANALYTICAL APPROACH TO DETERMINING A CONTAMINANT
                 TRANSPORT REGIME	  B - 1
APPENDIX C      EPA AMBIENT STANDARDS AND CRITERIA  	  C - 1
APPENDIX D      INTERIM FINAL GUIDANCE ON REMOVAL ACTION
                 LEVELS AT CONTAMINATED DRINKING WATER SITES   	  D - 1
APPENDIX E      TREATABILITY CLASSIFICATION OF PRIORITY POLLUTANTS  	.. . .  E-1
APPENDIX F      GLOSSARY OF ACRONYMS	  F - 1

                                    LIST OF FIGURES
Figure                                                                          Page
 1-1       Process for Selecting Alternate Water Supplies  	  1-2
 2-1       Site Characterization and Determination of Authority 	  2-2
 2-2      Determination of Response Scope  	  2-3
 2-3      Screening and Analysis of Alternatives  	  2-4
 3-1       Information  Source Matrix  	  3-2
 3-2      Availability of Usable Drinking Water Versus Time  	  3-8
 3-3      Relation of Extreme Consumption on Maximum and Minimum Days
          to the Average Daily Consumption of Potable Water 	   3-10

                                    LIST OF TABLES
Table                                                                          Page
 3-1      Treatment Process Applicability Matrix	   3-14
 3-2      Example of Decision Matrix	   3-20
 4-1      Typical Table of Contents for Technical Specifications  	  4-4
                                            VI

-------
                                    ACKNOWLEDGMENTS
This document was prepared for the Office of Emergency and Remedial Response under EPA Contract 68-
01-6939 by the following individuals:
     Douglas Sarno, Office of Emergency and Remedial Response, HSCD
     Nancy Willis, Office of Emergency and Remedial Response, HSCD
     Randall Kaltreider, Office of Emergency and Remedial Response, HSCD
     Jean Schumann, Office of Emergency and Remedial Response, ERD
     Karen Clark, Office of General Counsel
     Dana C. Pedersen, Camp Dresser & McKee Inc.
     William Swanson, Camp Dresser & McKee Inc.
     Wendy L. Sydow, COM Federal Programs Corporation
     Sidney F. Paige, C.C. Johnson & Malhbtra, P.C.
     Steven D. Stinger, C.C. Johnson & Malhotra, P.C.
Thanks are also extended to  the other EPA and  COM staff who assisted in  development  of this guidance
document through providing technical reviews, editing, and production support.
                                                vii

-------

-------
                                     1.0 INTRODUCTION
Non-time-critical  removal  actions,  ERAs,  and
operable unit  remedial actions are used to provide
faster response than  can  be achieved  with normal
remedial actions. In  order to  streamline  the
implementation of an alternate water supply,  first
operable unit remedial actions rely on an abbreviated
form of the remedial  investigation/feasibility study
(RI/FS). For non-time-critical removal actions  and
ERAs,  the process used to evaluate alternatives is
referred to as the engineering evaluation/cost analysis
(EE/CA).  Figure  1-1  illustrates the  decision-making
process used in this  guidance  for determining
alternate  water  supply  needs,  screening  and
evaluating  alternatives,  and  designing  and
implementing  the remedy. This  process  uses
components of  the  EE/CA and  RI/FS  guidance
combined with knowledge of alternate water supplies
to provide the  user with a complete and streamlined
approach to developing these actions in the field. This
guidance does not replace  guidance on EE/CAs or
RI/FSs and  should  not be  used as an  absolute
reference.
This manual should be used in conjunction with other
EPA guidance documents,  technical  reports  and
references. Selected  applicable references  are listed
below.
     • Superfund Amendments and Reauthorization
       Act of 1986 (SARA).

     • Comprehensive Environmental  Response,
       Compensation  and Liability Act  of 1980
       (CERCLA), 42 U.S.C. 9601-9657.
    • Revised National  Oil  and  Hazardous
      Substances Pollution  Contingency  Plan
      (NCP),  40  CFR Part 300,  1985 (47  FR
      31180).

    • Guidance  Document  for   Remedial
      Investigations  under CERCLA.  U.S. EPA
      OERR,  OWPE, OSWER EPA/540/G-85/002,
      June 1985.

    • Superfund Remedial  Design  and Remedial
      Action  Guidance. U.S.  EPA OERR,  June
      1986. OSWER Directive  9355.0-4A

    • Compendium  of  Field Operations Methods.
      OERR,  Planned August  1987.  OSWER
      Directive 9355.0-14

    • Superfund Removal Procedures,  U.S.  EPA
      OERR, ERD. July 1987.

    • Engineering  Evaluation/Cost Analysis
      Guidance, U.S. EPA OERR, ERD. Draft, June
      1987.

    • Guidance  on  Feasibility  Studies  under
      CERCLA. U.S.  EPA OSWER  and ORD.
      EPA/540/6-85/003.  June 1985.

    • Community  Relations  in Superfund: A
      Handbook. U.S.  EPA,  OSWER Directive
      9230.0-3A. March  1986.

    • State Participation in the Superfund Remedial
      Program,   U.S. EPA, OERR, February 1984.

This manual serves as a planning and guidance tool
and should not be substituted  for the services of
competent professionals.
                                               1-1

-------
 CHARACTERIZE
SITE; DETERMINE
  RELEVANT
  CRITERIA
 DETERMINE
APPROPRIATE
 AUTHORITY
EVALUATE SCOPE OF PROBLEM
AND DEMANDS OF THE AFFECTED
   COMMUNITY; IDENTIFY
     ALTERNATIVES
  LIMITED
SCREENING OF
ALTERNATIVES
                          NO
                 DISCONTINUE EFFORT
                OR CONSIDER ALTERNATE
                   WATER SUPPLY
                    AS PART OF
                   FINAL REMEDY
                                            EVALUATE
                                          ALTERNATIVES

                                          • TECHNICAL
                                          • ENVIRONMENTAL
                                          • PUBLIC HEALTH
                                          • COST
                                          • REGULATORY/
                                           INSTITUTIONAL
                                        FIGURE  1-1
         PROCESS FOR SELECTING ALTERNATE WATER  SUPPLIES

-------
                                           2.0 APPROACH
     This  document provides guidance at two levels
of decision making. The first level is determining if an
alternate water supply is needed. If needed, then the
second  level is selecting alternate water supplies and
implementing  the selected  alternative.  The  term
"alternate  water  supply"  is used  throughout  this
document to refer to both provision of new  supplies
and  treatment or redistribution of existing supplies.
The  term  "existing  water  supply"  is  defined in this
document as any potable  source, including a private
well, public wellfield,  or  surface supply such  as a
lake, reservoir,  or river, and the distribution  system
which connects  it with users. A water supply can
provide  200-300  gallons per day (for a small system)
up to 10-20 million gallons per day for an  average
city or even more for a larger city.
     This  manual discusses techniques which have
been derived  from removal and  remedial  actions
implemented  under  the  Superfund  program  and
provides  a systematic  approach  to  selecting  and
implementing these  or other  actions  for sites  with
contaminated water supplies. Appendix  A presents a
list of sites where  alternate supplies  have been (or
will  be) installed and  identifies the type of system
selected.  Based on the experience gained  at  these
sites, the following types  of alternate  drinking  water
supplies have been identified  and are given primary
consideration in this document:
    •  Connection to existing public water supplies
       or private supplies and distribution systems

    •  Development of new water resources

    •  Treatment at well  head or at each point of
       consumption

    •  Oversized  community storage  facilities  to
    compensate for loss of existing system capacity
    in emergency  demand  situations (storage  will
    not increase the actual capacity of the system)

    •  Blending of  new and  existing water supplies
       to achieve acceptable  levels.

    Figures  2-1,  2-2,  and  2-3  illustrate  the
detailed  methodology developed  for  selecting
alternate  water supplies.  Figure  2-1  illustrates  the
decision  components   corresponding  to  site
characterization and  determination of  response
authority. Figure 2-2  illustrates  the  components
corresponding  to  the determination of  response
scope.  Finally,  Figure 2-3 provides the  components
of the identification,  screening,  and  analysis  of
alternatives.
    A detailed discussion on the  decision process is
presented  in  Section 3.0.   Once this  process is
completed and an alternate water supply  is selected,
the selected  alternative will  be  designed and
implemented.  This  design  and  implementation
process is discussed in Section 4.0.
                                                  2-1

-------
to
                                   DETERMINE
                                    NEED FOR
                                   ADOmONAL
                                      DATA
                                                                                                                                                       DISCONTINUE EFFORT
                                 TABULATE TYPES,
                                 CONCENTRATIONS
                                 FOUND IN OR NEAR
                                  WATER SUPPLY
                                                                                          REMEDIAL PROGRAMS
                                                                   DO
                                                                 ANY SITE
                                                             SPECIFIC FACTORS
                                                             PRESENT A SERIOUS
                                                                  HEALTH
                                                                 THREAT?1
    CURRENT
 CONTAMINATION
 EXCEED NUMERIC
ACTION LEVEL FO
   REMOVALS
      DO
  CURRENT OR
EXPECTED VALUES
 EXCEED MCL'S?
     DOES RISK
ASSESSEMENT INDICATE
 UNACCEPTABLE RISK
     POPULATIONS
                                                            USING SITE-SPECIFIC
                                                           FACTORS AS DISCUSSED
                                                                                                         PERFORM AS
                                                                                                       FIRST OPERABLE
                                                                                                        UNIT REMEDIAL
                                                                                                          ACTION
                                                                  DOES
                                                                  RISK
                                                         ASSESSMENT INDICATE THAT
                                                            A SERIOUS THREAT
                                                                 EXISTS?
                                     WILL
                                  ACTION MEET
                               REMOVAL COST/TIME
                                RESTRICTIONS OR
                                  QUALIFY FOR
                                    AIVER
                                                                                                         PROCEED™
                                                                                                      DETERMINATION OF
                                                                                                      RESPONSE SCOPE
                                      IS
                                    ACTION
                                   REQUIRED
                                   WITHIN 6
                                   MONTHS?
                                              AS NON TIME-CRITICAL
             DRINKING WATER ACTION LEVELS DESCRIBED IN APPENDIX D
             OUT OF THE SCOPE OF THIS DOCUMENT
                                                                                   Figure 2-1
                                                       Site Characterization  And Determination Of Authority

-------
            IDENTIFY THE
       EXTENT OF CURRENT AND
        FUTURE WATER SUPPLY
          CONTAMINATION
         IDENTIFY/ESTIMATE
         THE DEMAND OF THE
        AFFECTED COMMUNITY
         PREPARE SITE MAPS
          (AS APPROPRIATE)
NONNPL SITES
               IS THE
          UNCONTAMINATED
      SUPPLY SUFFICIENT TO MEET
         DEMAND UNTIL A FINAL
             REMEDY IS
              PLEMENTE
                 9
    ADJUST CURRENT
  USE CHARACTERISTICS
      TO ELIMINATE
 CONTAMINATED VOLUMES
FROM SUPPLY AND CONSIDER
 ALTERNATE WATER SUPPLY
       AS PART OF
      FINAL REMEDY
       PROCEED TO SCREENING AND
       ANALYSIS OF ALTERNATIVES
                ©
                                Figure 2-2
                   Determination  Of  Response Scope
                                    2-3

-------

DELETE
ALTERNATIVE
1


DELETE
ALTERNATIVE
i


CONSIDER
COMBINATION OF
ALTERNATIVES
i

CONSIDERACTION
IN FINAL EVALUATION

,
                                   ARETHERE
                                UNCONTAMINATED
                               WATER SUPPUES IN OR
                                 NEARTHE STUDY
                                    AREA?

DELETE
ALTERNATIVE
i

DELETE
ALTERNATIVE
' i


CONSIDER
COMBINATION OF
ALTERNATIVES

CONSID
IN FINAL
1 \

DELETE
ALTERNATIVE
1


DELETE
ALTERNATIVE
1


CONSID
IN FINAL
\
                                  COULD
                                USE OF
                                   ESCONTRIBUT
                                 TO PROVIDING
                                  NECESSARY
                                     LIES
    ISTHERE
  LAND AVAILABLE
 FOR BUILDING SUCH
    A STORAGE
    FACILITY?

DELETE
ALTERNATIVE
i

DELETE
ALTERNATIVE
' i


CONSID
IN RNAL
\
                                    IS
                                 THERE ANY
                               COMBINATION OF
                              E ABOVE ALTERNA
                                   NT TO MEET.
                                 DEMANDS?
   ARETH
   ANY OTHER
AVAILABLE SOURCES
OF UNCONTAMINATED
    WATER?
   ARE
  ANY BLENDING
  COMBINATIONS
SUFFICIENTTODILUT
      DES1R
    LEVELS
                                                                                                                CONDUCT ANALYSIS
                                                                                                             OF REMAINING ALTERNATIVES
                                                                                                          BASED ON THE FOLLOWING CRITERIA:
                                                                                                                -COST
                                                                                                                -TECHNICAL
                                                                                                                -PUBLIC HEALTH
                                                                                                                -ENVIRONMENTAL
                                                                                                          	-INSTITUTIONAL
_
                                                               FIGURE  2-3
                                  SCREENING  AND  ANALYSIS  OF  ALTERNATIVES
                                                                            2-4

-------
                                   3.0 ALTERNATE WATER SUPPLY
                                         SELECTION PROCESS
3.1  SITE CHARACTERIZATION AND
    DETERMINATION OF AUTHORITY
     The activities discussed in this  section include
     the collection and review of data to  determine
     the levels of contamination present and  the
     determination of which  response authority, if
     any, is appropriate. The information collected at
     this stage will be used  throughout the selection
     and design  processes to accurately define  and
     effectively remediate the problem.

     3.1.1  OBTAIN AVAILABLE DATA

        Available data are collected to define  water
        supply system conditions and provide a basis
        for  a preliminary  water supply system
        evaluation.  Once collected  and  compiled,
        these data will also serve as the foundation of
        the data  base  that will   eventually  be
        assembled  for  evaluation of  potential
        technologies and  alternatives, and  the design
        of any removal and/or remedial actions during
        the implementation  phase.  As part of  this
        activity,   a  brief site history should  be
        developed.
        Information which may be needed  is listed in
        Figure 3-1,  along  with  potential sources.
        Although  some information may need to be
        collected  in each  area to provide an accurate,
        broad perspective of site conditions,  those
        topics at the top of the list are more critical to
        alternate water supply selection activities and
        should be the focus at  this  stage. The  On-
        Scene Coordinator  (OSC) or  Remedial
        Project Manager  (RPM)  will determine which
        data are  relevant depending on  site-specific
        conditions and time constraints.  As another
        important means of  gathering information, the
        OSC  or RPM may  want to  set up personal
        interviews with state or  local authorities  with
        jurisdiction over the  site as well as any public
        or private water purveyors in the area. This is
        particularly important because of  institutional
        concerns relating to  water supplies.

        Specific  documents  which  may  be
        investigated are listed below:
        •   Specifications, maps  or other descriptions
            of the water  supply system in question (if
            available)
 •   Records  of  average,  daily, monthly  or
     annual consumption  and  relationship
     between demand and safe yield

 •   Technical reports related to existing water
     supply  system  characteristics  and
     contamination (including sample locations
     and analytical results, if possible)

 •   Results of previous surface and/or ground
     water sampling and monitoring programs

 •   Remedial Action Master Plan (RAMP) and
     other initial planning  documents  (if
     available, for NPL sites only)

 •   Site history, ownership,  operations,  and
     disposal practices (past and present) from
     past owners, operators, and generators

 •   RI/FS reports from  prior site work  (NPL
     sites only)

 •   Specifications or descriptions of other
     uncontaminated water supply systems  in
     the vicinity of the study area (if present)

 •  Listing of legal  or institutional  constraints
     which may affect  implementation  of
     alternative water supply options

  •  Federal and State geological surveys

  •  Base  map of  study  area  (could  be
     provided by local governmental agency)

  •  Records from  local  health department
     regarding complaints  and testing of water
     supply
  •  Soil surveys  or  other  published
     documents  such  as university agricultural
     extension soil data
  •  Aerial photographs (sequential/dated).

3.1.2  REVIEW AND  EVALUATE  AVAILABLE
      DATA AND IDENTIFY DATA GAPS

  In this step,  available data are summarized in
  formats that will facilitate their use to meet
  the objective of the project.  In the process of
  reviewing and  evaluating the  available data,
  an understanding of study area conditions will
  be developed and data gaps will be identified.
  At this early stage it is important to compile
  information which is relevant to the existing
                                                    3-1

-------
         FIGURE 3-1
INFORMATION SOURCE MATRIX

Water Supply System Descriptions
System capacity
Contamination problems
Evaluation of water supply resource
Ease of integration with other regional supply systems
Contaminant Source
Wastes present
Quantities of each waste
Toxicity and persistence
Current contaminant migration
Othsr Regional Water Supply Systems
Distance from contaminated system
Available excess capacity
Ease of connection to contaminated supply's distribution system
Groundwater
Potential for water supply development
Flow direction and gradient
Location of recharge areas
Surface Water
Water quality, use and classification of area surface waters
Drainage area and flow potential
Potential for water supply development
Regional and Local Geology
Geologic history
Stratigraphy
Structure and characteristics of formations
Physiography/Topography
Study area slope orientation/drainage patterns
Study area topography
Soils
Soil types
Extent and thickness
Hydraulic properties
Climatology and Meteorology
Net precipitation and evapotransportation
One year 24-hour rainfall
Local temperature regime
Direction and magnitude of prevailing winds
Infiltration potential
LandUie
Study area land usa
Study area population density
Study area development density
Water Rights
Institutional and legal limitations
Local restrictions, agreements, etc.
Ecology
Ecologically sensitive areas in study area
Significant habitats in study area
Community Involvement
Community relations plan status
Level and nature of community concerns
EPA Region


•



.
.
•
.



.


•
.

.




















.
.
.

.


•


.
•
in



.












.
•


.
.

.
.
•

.
.























National & Oceanic
Atmoipharlc Administration


































.
.
.
.
.













Federal Emergency
Management Anencv




















































i






























.
.
.


















i
State Environmental
Agency

•




.
.
.
.





.
.
.

*




















.
.
.

.


.
.

.
• 1
State Health Department

•

.





•

•
•
•

.
.
.


.
.

.
.
.

.
.















!





i

State Water Supply Agency

•

.





•

•
•
•





.




















.
.
.

.
.






State Geological Survey



.



-







.
.
.


.
.

.
.
.

.
.




















!


•5



















.




















.
.










Ucal Water Authority 1

.

.
.






.

.

.
.
.

.

.
























}





Other Regional Watar
Authorities




*






.
.
.

.
.
.

.

.


























!


••
1
























	 1







	 ;













1




•
Peat and Present Contaminant
-Source Owners ' 1






.
.

.






































j



Aerial Photos j







.










:
1 	 1







' .
	











0
.





i
;

i

a
u
J
]


.



.
•'.

.





—











".-












	 j.
.
9
1
!


. '
,



1 	
j
! §
5








.






-



i 	


"




.












	











1
! a
1































«




















                 3-2

-------
 water supply  system, contamination  problems
associated with the present system, and factors
affecting the  applicability  of alternate  water
supply systems. The status of information on the
following areas should be determined:

  •  Condition of currently used water supply
      source including  total  capacity, existing
      treatment facilities,  contamination
      problems, and potential for total or partial
      rehabilitation

  •  Condition  of  currently  used  water
      distribution   system   including
      contamination  problems and potential  for
      connection to an alternate water supply
      source
  •  Location  and  present  condition  of
      contamination  source,  if  possible (e.g.,
      are contaminants still leaving the source
      and entering the water supply?)

  •  Capabilities of other regional water supply
      systems  including  available excess
      capacity and ease  of  connection to  the
      distribution system  of the contaminated
      water supply system

   •   Hydrogeology  and  hydrology  of water
       resources currently  providing  water
       supply and those which could  potentially
       provide a water supply (ground water or
       surface water)
   •   Implications of continuing or discontinuing
       pumping of wells in  the site  area  on
       plume movement.
   •   Construction  details  of wells in the  site
       area  (is there a potential for hydraulic
       conductance between two aquifers due to
       an existing well?)
   •   Geology and soils in the study area, with
       particular emphasis on areas between the
       contaminant source and water supply
       source.
   An important part of reviewing and  evaluating
   the available data is an  assessment of its
   reliability  (the extent  to  which  the data
   represent  site  conditions)  and  quality
   (accuracy and precision). The dates of maps,
   drawings,  and plans  should be  checked;
   sampling locations  should be evaluated for
   representativeness. Analytical data should be
   checked,  if  possible,  against  internal
   laboratory QA/QC criteria  (blanks, duplicates,
  spike/recovery)  and the methods of sample
  collection,  preservation,  handling,  and
  sampler decontamination should be examined
  for conformance with quality control protocols.
  If more than one laboratory tested samples
  from the same location in the study area, the
  results should be  assessed for consistency
  and variations in the identified methodology.

  It  may also  be  beneficial  to   examine
  information relating to alternative  response
  actions  to  ensure  that  available   data  are
  sufficient for the evaluation  of  each.  Topics
  for which data of questionable accuracy  and
  precision have been obtained may constitute
  data gaps because of the lack of reliability of
  the available data.
  Summarizing data in  graphical, tabular, or
  matrix formats usually provides a convenient
  means  of  evaluation.  These  formats  are
  compact and allow for efficient presentation,
  comparison, and identification of gaps. Unless
  the amount of  available data is quite  small,
  some written documentation  in the form of an
  "executive  summary"  should   also  be
  prepared.  All summaries,  whether graphical,
  tabular, or written, should identify both what is
  known,  (e.g., conditions  at the site), and what
  is not known (i.e., evident data gaps).

  Following identification of data gaps, an effort
  should be made to evaluate the importance of
  the gaps and to find additional information if it
  is necessary for the decision making process.
  If additional information  is unavailable, study
  area investigations  may  have  to  be
  undertaken to  provide  the  necessary
  information, as  discussed  in the  following
  section.
3.1.3  CONDUCT ADDITIONAL SAMPLING

  Due to  time involved in conducting additional
  sampling  and analysis,  existing data should
  be  thoroughly reviewed  to determine  its
  sufficiency for use in evaluating the condition
  of the  water supply.  In  many cases,  the
  amount of  available  analytical  data is not
  sufficient for decision  making. In such cases,
  additional  sampling  will  be  necessary.
  Whenever  possible,  this  sampling  should
  include existing wells and taps in the affected
  area. Screening of  samples for contaminants
  in the field or laboratory is an effective way to
  achieve  results   rapidly.  Obtaining  full
  laboratory  results  generally requires  several
                                               3-3

-------
 weeks or more depending on  the  analyses
 performed. However,  7-day  turnaround  for
 analytical  results  is available through CLP
 Special Analytical  Services.  For sampling  of
 private wells  it is  recommended to request
 low detection levels so that values below the
 Contract Required  Detection  Limits  (CRDLs)
 are reported. Designing a strategy  for siting
 new  wells,  drilling  wells,  sampling and
 analysis  will  take  much longer.  Certain
 portions  of   identifying  and  evaluating
 alternatives could   be   conducted
 simultaneously with sampling. It is important
 that  the need for additional  sampling  be
 identified as early as possible in the  selection
 process so that the data can  be collected,
 analyzed,  validated and  interpreted with  a
 minimum delay.

 If sampling is necessary,  certain  documents
 must be  prepared before  initiating field
 activities. These documents are:

 •   Sampling  and  Analysis Plan (includes a
    field  sampling plan  and  a  quality
    assurance project plan)

 •   Health and Safety Plan.

 The  required  contents of these  documents
 may vary depending on  the  authority used.
 Guidance  on  the preparation of these plans
 has  been published by EPA.  The  following
 references provide further information:

 •   U.S.   EPA. Guidance  Document for
    Remedial  Investigations   under
   CERCLA. OERR, OWPE,  OSWER,
   EPA/540/G-85/002,  June  1985.

 •  U.S.  EPA. Data Quality  Objectives for
    Remedial Response   Activities,
    EPA/540/G-87/003  and  EPA/540/G-
   87/004, March  1987.

 •  Sisk,  S.W. NEIC  Manual  for  Ground
   Water/Subsurface Investigations  at
   Hazardous Waste Sites.  EPA-330/9-
   81-002. July 1981.

•  U.S.   EPA. Interim  Guidelines and
   Specifications  for Preparing  Quality
   Assurance Project  Plans. QAMS-005/80.
   Office  of  Research and Development.
   December 1980.

•  U.S. EPA. Guidance for Phase  I - Fluid
   Quality Measurements.  UIC  Quality
   Assurance  Program,  Ground  Water
      Protection Branch, Water Supply Branch.
      July 1984.

   •  U.S.  EPA. Handbook for Sampling  and
      Sample Preservation  of Water  and
      Wastewater.  EPA-600/4-82-029.
      September 1982.

   •  U.S.  EPA.   Compendium  of  Field
      Operation  Methods, OSWER Directive
      9355.0-14 Office  of  Emergency  and
      Remedial  Response  Planned August
      1987.

   •  U.S. EPA.  Safety Manual for  Hazardous
      Waste Site Investigations (Draft), Office of
      Occupational  Investigation Center,
      Denver, Colorado. 1979.

   •  U.S.  EPA.  Standard Operating  Safety
      Guides,  Office  of  Emergency   and
      Remedial Response, Washington,  DC.
      1984.

3.1.4  DETERMINE   APPLICABLE   OR
RELEVANT    AND    APPROPRIATE
REQUIREMENTS

   Applicable or relevant  and  appropriate
   requirements (ARARs) are  determined on a
   site-specific  basis.

   There are a number of Federal  and  State
   standards  which state specific hazard  levels
   for contaminants in drinking water. State  laws
   that are  more   stringent  than Federal
   requirements may  be ARARS.  Local
   requirements are  not potential ARARs  but
   may be taken into consideration. The numeric
   values  for the  criteria  discussed in  this
   section  are  presented  in  Appendix C.
   Potentially  applicable or  relevant  and
   appropriate Federal standards are described
   below.

   In general,  alternate  water  supplies  are
  subject to  the  requirements of the National
   Environmental   Policy  Act  (NEPA).
  Specifically, NEPA requires the production of
  an Environmental Impact Statement (EIS)  and
  opportunity for public comment. Only  time-
  critical removal actions qualify for a statutory
  exemption  from  NEPA  requirements.
  However,   providing alternate  water supplies
  as  non-time-critical removal or  remedial
  actions may be exempt from NEPA based on
  categorical exclusions. OSWER Directive  No.
  9318.0-05 on  "Environmental  Review
                                         3-4

-------
Requirements for Removal  Actions"  (EPA
1987) contains more detailed guidance on the
applicability of NEPA requirements to removal
actions.
The  EPA  Office of  Drinking Water has
developed a  series of  numeric Health
Advisory  (HA)  levels for contaminants  in
drinking water. Separate levels are identified
for  1-day,  10-day,  longer term, and lifetime
health advisories. The lifetime health advisory
is referred to as the drinking water equivalent
level (DWEL). Under the Safe Drinking  Water
Act  (SDWA)  (P.L. 93-523)  maximum
contaminant levels (MCLs) for public  water
systems  have been  set for five classes of
contaminants:  microbiological,  turbidity,
inorganics, organics  (including  trihalo-
methanes)  and  radiological.  MCLs  are
enforceable standards [See EPA's  Guidance
on  Feasibility Studies under  CERCLA  (EPA
1985)  for  MCL calculations].  In addition to
MCLs, EPA has  set  maximum contaminant
level  goals (MCLGs). MCLGs  are health-
based goals set at levels at which no adverse
health effects may arise,  with a margin of
safety.  EPA  has established water quality
criteria (WQC) for a  number of metals and
organics,  many of which are  associated with
uncontrolled  hazardous  waste sites.  In
contrast  to MCLs,  WQC  do not  establish
requirements,  but  instead provide guidance
on  the human health effects  of carcinogenic
and non-carcinogenic pollutants.  WQC can
be  used  where;MCLs  do not exist  where
appropriate under the circumstances.

 EPA  has also developed  toxicity values  for
 substances commonly found at Superfund
 sites based on  Health  Effects Assessments
 (HEAs). HEAs are not ARARs but are used to
 establish  site-specific  engineering design
 goals for remedial  actions  which involve
 hazardous substances most frequently  found
 at  CERCLA  sites for which applicable or
 relevant standards do not exist. Compounds
 without HEAs will generally have a reference
 dose which gives a maximum intake value.

 A list of available drinking water standards are
 presented in Appendix C. When MCLs, WQC,
 HAs  or  HEAs are not available, contact  the
 Policy and Analysis Staff (PAS) of the  Office
 of  Emergency and Remedial  Response
 (OERR) or the Toxics Integration Branch  of
 the Hazardous  Site  Evaluation Division  at
  OERR for guidance criteria or  available
  advisories.

3.1.5  DETERMINE APPROPRIATE
      AUTHORITY

  This section  describes  the process  to  be
  used to determine the appropriate authority to
  implement alternate  water  supplies. The
  removal and remedial authorities use different
  criteria for determining the need  for  action;
  the application of these criteria will  determine
  which authority is to be used.

Removal  Authority  - The  method  used to
determine  drinking  water action  levels  for
removals  is  presented in Appendix D. The
removal program model includes consideration
of both  numeric action levels and  site-specific
factors.  The  numeric  action level is  based  on
the Drinking  Water Equivalent  Level (DWEL)
and, for carcinogens,  the 10-4 Lifetime Excess
Cancer Risk Level. Removal action  can only be
taken if  the numeric level is exceeded or if site
specific  factors otherwise indicate that a serious
threat exists. In general,  removal  actions to
provide  alternate  water  supplies  can  be
performed on the basis of  a  future  threat, if  it
can be determined that the  numeric action level
will be exceeded within 6 months. It is important
to note that removal authority is invoked only in
cases where no other party  can respond in  a
timely manner.  The  appropriateness of using
removal  authority  to implement   non-time
critical alternate water supplies will  be  judged
on  a site-by-site basis,   depending  on  the
priorities for removal resources in the region.

   In general, removal actions are limited to $2
   million and 12  months.  Actions  which  will
   exceed these limits may  not be  performed
   under  removal  authority unless  certain
   findings are made by the EPA in accordance
   with CERCLA 104(c), as amended by SARA.
   Although performed by  remedial contractors,
   expedited response  actions  (ERAs)  are
   performed under removal  authority and  are
   subject to  the same requirements as  all other
   removal  actions. These  statutory  limits  may
   be an important factor in determining whether
   to use  removal  or  remedial   authority.
   Responses lasting longer than 12 months  and
   responses to widespread  areas of low-level
   contamination may be too extensive for  use
   of removal authority  and therefore,  may be
   more  appropriately addressed by remedial
                                           3-5

-------
 authority.  At  non-NPL  sites,  removal
 personnel  should refer such  sites  to  the
 remedial program for further evaluation.

 Remedial  Authority - The criteria for taking
 action under remedial authority  are more
 flexible than  for removals;  however,  in order
 to  qualify  for fund-financed action  under
 remedial authority, the site must be listed on
 the National Priorities List (NPL). This is not a
 constraint under removal authority. If an NPL
 site does not satisfy the criteria for initiating a
 removal action, it may still be possible to take
 action under remedial authority. Non-NPL
 sites,  however,  may  not be considered  for
 action under remedial authority.

 The remedial program primarily uses MCLs or
 more  stringent state  standards  where
 available to determine the need for action  and
 these  values  are generally lower than  the
 numeric  criteria  under  the  removal authority.
 In  cases  where these  standards are  not
 available, remedial authority will also consider
 reference  doses, cancer  potency  factors,
 MCLGs,  water quality  criteria,  health
 advisories,  and  state  advisories. In addition,
 remedial  action  may be taken based  on  the
 threat of  future contamination in cases where
 these criteria are not yet exceeded. If potable
 wells  are not currently contaminated, it must
 be  determined if they will be  threatened with
 contamination   before  a  final  remedy
 addressing  ground water  contamination can
 be  implemented. To make this determination,
 the  rate  of  plume  movement  can  be
 calculated  (if the aquifer system is  relatively
 simple)  using  a form  of  Darcy's  Law.
 Appendix B  describes the  application  of
 Darcy's Law  and an  approach which can be
 used  to  calculate ground water movement.
 Sufficient data on ground  water hydrology
 may not  be  available  to  perform  these
 calculations at all sites. An easier method of
 estimating future contamination and validating
 results of contaminated transport modeling is
to monitor  contamination levels in  nearby
upgradient wells. It may be beneficial to install
new wells if suitable  points do not exist.  By
considering the rate of contamination increase
over time  in these wells,  it is  possible  to
estimate expected impacts on the threatened
water  supply.  In  some  cases,  special
circumstances may exist where protection of
human  health  requires  more stringent
 standards  than  MCLs.  Where  multiple
 contaminants or  pathways of  exposure
 present  extraordinary  risks,  more  stringent
 standards  will  be  considered  based  on
 appropriate risk ranges for carcinogens, levels
 of quantification,  and  other   pertinent
 guidelines.

 In many cases, sufficient numeric criteria are
 not available and the need for remedial action
 will  be  determined by performing  a risk
 assessment. As a  rough estimate, the total
 maximum risk that  a person would incur  by
 drinking water contaminated with a number of
 chemicals for a lifetime can be estimated  by
 calculating  the  excess carcinogenic risks
 associated  with  each  chemical  and then
 adding  the  risks together.  This  calculation
 assumes that risks are  additive and that there
 are no synergistic or antagonistic effects. For
 example,  production wells  are  contaminated
 with the following:
Compounds
trichloroethylene
1,1-dichloroethylene
1 ,2-dichloroethane
Concentration
15 U9/I
5 ng/l
2ng/l
10 -6 HEAorWQC
1.84iig/l
.033 jig/l
.51 iig/l
To calculate the excess cancer risk:

Trichloroethylene

       	X10-6=8.1X10~6

1,1 -dichloroethylene

      	X10~6= 151.5 X10 ~6
      .033

1,2-dichloroethane
           X10~6=
                    3.9X10
                            -6
      0.51

TOTAL RISK =163.5X10-6  =  1.6  X  10"*

This example is  presented as a  possible
approach for a situation  where only two or
three carcinogens are involved. For situations
involving  multiple  carcinogens  and/or
noncarcinogens, consult the Superfund Public
Health  Evaluation Manual (EPA 1986)  and
                                           3-6

-------
      seek the  assistance of a  competent health
      professional.

      Direct ingestion is  not the  only pathway of
      concern in providing alternate water supplies.
      Other pathways such  as  inhaling volatile
      organic compounds during showers and direct
      dermal contact may also present risks. These
      pathways should be investigated. Consult the
      Superfund Public  Health  Evaluation Manual
      or  contact a health  professional  for more
      information in calculating risk due to multiple
      pathways of exposure.

      EPA uses  a  risk range  of  10"4 to  10'7
      when determining an acceptable risk level.

      For  more  detailed information  on  risk
      assessment  and criteria contact the Toxics
      Integration Branch, OERR.  For. enforcement
      sites, refer to the Office of Waste  Programs
       Enforcement's  Endangerment  Assessment
       Guidance (EPA 1985) as well as the SPHEM.

3.2  DETERMINATION OF RESPONSE SCOPE

     Previous activities established the presence of a
     health threat due to contamination of drinking
     water  supplies.  The  purpose of  activities
     described in this section is to determine the
     extent of contamination and identify the quantity
     of usable water available, if any. The volume of
     usable water is compared to the demands of the
     affected community  to determine the need for
     further action.  Under both  the removal  and
     remedial authority, the goal of cleanup will be to
     achieve MCLs  at the tap. In cases where MCLs
     are  not available, other criteria as described  in
     Section 3.1.5, will be used.

     EE/CA and  FS activities will be performed using
     the  available contractors under the removal and
     remedial  programs  according to  standard
     contract procedures. Work will commence with
     either an  EE/CA  approval  memorandum
     (removal) or an FS work plan (remedial).

     3.2.1  EVALUATE PROBLEM EXTENT

       The purpose of this task is to  determine, over
       time, how much  of the  water supply will be
       contaminated beyond use  and to what extent
       good quality water will be available for use.
       Determination of  this  information  will involve
       quantifying the present level of contamination
       in the water supply. If ground water wells are
       used,  determine how  many  wells are
       contaminated, how many wells  are free from
  contamination,  how  many  have low enough
  contamination  for limited  use, and what
  quantities  are  available  for  each  of  these
  categories.

  In  addition  to  the extent  of  current
  contamination,  the estimated levels of future
  contamination  need  to be considered. It is
  important to determine whether the amount of
  available  uncontaminated  water  will be
  continually decreasing. The rate at which the
  contamination will increase can be  estimated
  by  contaminant transport  modeling  or
  monitoring of  nearby  wells as  discussed in
  Section 3.1.5.

  As a result of this task, a graph or table could
  be developed to show the  presently available
  quantity of usable  drinking  water and the
  expected rate of change in water quality over
  time.  An  example is  shown in Figure 3-2.
  The  result is  a  simple  curve  showing the
  amount of usable water available over a given
  period of  time.  By  overlaying the  expected
  demand  (as will  be developed  in the next
  section),  it is  possible to estimate  when the
  usable supply of water will  be insufficient.
  This information  will be critical to determining
  the  extent  of  alternate  water  supplies
  necessary.

3.2.2  DEVELOP DEMAND REQUIREMENTS

  It is important to know the quantity of water
  which will have to be supplied to the affected
  area and  if the available usable water supply
  can serve community  needs. This information
  will provide the  basis for  subsequent design
  and cost criteria.

  Water requirements  can  be calculated or
  estimated based  on average  daily,  maximum
  daily,  and peak  hourly demand;  however,
  water supplies are  normally sized  based on
  maximum instantaneous  demand.  These
  demand  estimates  should  not include
  projection  for  future  growth  because
  Superfund does not provide for the  expansion
  of a community and will only correct problems
  within an existing  system.  Fire  protection
  provisions will comply with all Federal, State
  and local fire codes. These provisions should
  only  require a small incremental cost, which
  generally  would allow for  providing hydrants,
  valves, and the means for providing adequate
  pressure. The  National  Fire Protection
  Association  codes  and Insurance  Services
                                                  3-7

-------
      USABLE
      WATER
      SUPPLY
      (gallons)
                                                  DEMAND
                     I   I  I   I   ]  I   I
                          Expected Date Of
                          Insufficient Supply
I   I  I
I   I  I   I   I  T
                                      TIME (weeks)
Availability Of Usable  Drinking  Water Versus Time
                           FIGURE 3-2
                                         3-8

-------
Office  (ISO) rates and durations  should be
considered during design.  If  an  expanded
remedy is desired by the State or locality for
fund-financed remedial or removal  actions,
the State will  generally have to  pay the
incremental cost and must have a defensible
basis  for  dividing  costs; the  remedy  must
then be implemented as  a State-lead action.
This determination should be made as early
as possible, usually prior to commencing the
EE/CA or FS.  State  Participation in the
Superfund Remedial  Program (EPA 1984)
contains  detailed information on coordinating
activities  with  States. Guidance  for removal
sites are  discussed in Appendix W, Guidance
for State  Lead Removals (July 1987).

There are a number of methods which can be
used  to  estimate the water demand. These
include (in order of decreasing accuracy):

•  Obtain metered consumption data for the
    community (both  for residential and for
    commercial/industrial) based on historical
    usage

•  Extrapolate from data on per capita water
    use  rates observed  by  municipal supply
    facilities in the general area

•  Estimate demand from general per  capita
    rates.  For  residential use,  an  average
    daily  consumption of 80-100  gallons per
    day per capita can be used (these values
    are  inflated  to  account for  system
    leakage). For industrial/  commercial uses
    the  reader  is .encouraged to  interview
    businesses  in  the  area  to obtain
    consumption data. Commercial usage  is
    highly variable  depending  on  the type  of
    business.   If data  are  not  available,
    commercial/industrial  usage  can  be
    estimated   to   average   2500
    gallons/connection/day.

 •  Apply engineering judgment  to estimate
    demand  from published   water  use
    patterns and  information  on  the  size  of
    existing equipment (Figure 3-3 indicates
    maximum  and minimum consumption
    values which can be obtained  if average
    daily consumption is known).

  Metered  consumption data is  preferred
  because it  is  the most accurate   data.
  However,  in   a small community  using
  individual private wells, such information may
  not be available. In this situation, water use in
  areas  of  similar  development  (i.e., rural,
  suburban, urban) can be used to predict use
  in the affected community.

3.2.3 PREPARE MAPS

  In order to accurately characterize the site, it
  may be beneficial to represent site conditions
  using maps. In instances where little data are
  available or where time is a  constraint,  the
  development of maps may not be warranted.
  They  are  intended  only as  an  aid  to
  performing the  site evaluation and  remedy
  selection.

  Two types of maps may be useful in providing
  an  accurate depiction of site  conditions and
  the extent of contamination. Community base
  maps  are  used to show all of  the  relevant
  features of the study area that may  affect
  design and implementation of  alternate water
  supplies.  The  community  base  map should
  show  all major surface features and identify
  areas  of contamination. The map should show
  the affected  study  area,   including  the
  contaminant source and the horizontal extent
  of  the contaminated plume.  It  should  also
   show the relative location of potential sources
   of  uncontaminated  water (either  existing
   public or  private  water  systems  and/or
   uncontaminated aquifers).  The needs of the
   site should be considered  in determining the
   degree of detail that will be required and the
   number and types of maps which should be
   drafted.  Subsurface  cross-sections  provide
   an overview  of  soils  and  geology and a
   schematic  representation  of the  extent of
   subsurface water contamination. Subsurface
   maps can be  developed  from  existing  site
   maps, soil and geologic  publications,  any
   existing  soil  boring and  monitoring well
   installation reports,  and analytical results of
   soil sampling  and  ground water sampling.
 3.2.4  DETERMINE
       RESPONSE
APPROPRIATE
   At this point the response authority has been
   chosen and the health threat and amount of
   contamination  have  been  quantified.  If
   removal action criteria are met and removal
   authority is selected to implement action  at
   the site, there is not a "no action" alternative.
   Selection  of removal authority implies that
   timely response to the situation is required.
                                            3-9

-------
      O.I
!*....?....".?..  *.:?....? 7  a910     1S    2  2.5  3    4   5  6  7  8 9 10     15  2O  25  30   4O  5O 6O 7O8O 100'
z
o
w

o
o
>-
_l
<
Q
Ul

&
IT

U)
o
l-
<
                  PEAK ON MAXIMUM  DAY
     MAXIMUM  24  HR.
     AVERAGE DAILY  CONSUMPTION
                  MINIMUM  2* HR
                  EXTREME MINIMUM ON MINIMUM DAY
    O.I
                                                                                                                   K>

                                                                                                                   9

                                                                                                                   8

                                                                                                                   7
5



4




3


2.5
                                                                                                                   1.5
                                                                                                      I.O

                                                                                                      .9

                                                                                                      .8

                                                                                                       7


                                                                                                       6


                                                                                                      ,5



                                                                                                      .4





                                                                                                      .3


                                                                                                      .25
                                                                                                                   .15
                           '4   5  6 7 8 9I°    l5   22-53.4   5  6 7 8 9 10     15   20 25 30  4O  5O 60 TO 8O  IOO



                                  AVERAGE  DAILY  CONSUMPTION  OF  POTABLE WATER  (MGD)
                                                                                                                  O.I
   RELATION OF EXTREME CONSUMPTION ON MAXIMUM  AND  MINIMUM  DAYS


   TO THE AVERAGE  DAILY CONSUMPTION OF  POTABLE WATER
                                                                                              FIGURE 3-3
   SOURCE:  WPCF and ASCE, 1970

-------
       Under remedial  authority, however, no action
       may  be taken if it can  be  documented that
       exposures  to  pollutants,  as  a  result of
       consuming contaminated water,  does not
       present a threat to public  health. In cases
       where pollutants are only detected in  isolated
       wells, an alternate  water supply  may not be
       required. This  decision  will  be  contingent
       upon the ability of  the  remaining supplies to
       meet the community's  water  needs and the
       assurance that  these wells will not become
       contaminated beyond safe use before a final
       remedy can be implemented.

       Even  if no action  with  respect  to alternate
       water supplies  is  justified, other remedial
       investigation  and  feasibility  study activities
       may  be  needed  to  provide  long  term
       protection of public health. For example, other
       activities being taken at the  site such as
       source or plume migration  control may slow
       or alleviate contamination of drinking water.  If
       an alternate water supply is  necessary, the
       FS should focus  solely on the  provision of
       that  water  supply and not  the  complete
       mitigation of the contaminant source.

3.3 PREPARATION  OF COMMUNITY  RELATIONS
    PLAN

  The details for producing a Community Relations
  Plan (CRP) are described in  Community Relations
  in  Superfund:  A  Handbook,  (EPA  1986).
  Preparation  of the  CRP  will coincide with the
  EE/CA  or  FS and should be completed  prior to
  release of these documents.

  The CRP is the planning document  for managing
  the  interaction between the community and the
  technical aspects of  the response actions at  a site.
  Community relations activities are  an integral part
  of Superfund response actions and  must be closely
  coordinated with  all  technical activities  conducted
  at the site. All site related activities, all statements
  made  to  the public, and even statements not
   made,  have the  potential to  affect  the technical
  activities  at the  site  and the  community's
  willingness  to cooperate with these activities. To
   expedite  production of the   CRP  as  well  as to
   assure consistent and  clear  communication with
   the public  and  press, a  community relations
   coordinator  should be designated. A  good
   community relations  plan is particularly important to
   work related to correcting drinking water problems
   because  such problems  often  involve significant
   community interest and  concern.
  If a CRP has not been prepared for the entire site,
  it will be necessary to prepare one which pertains
  specifically  to provision  of an  alternate water
  supply. While this document is abbreviated, it must
  be  consistent with CERCLA community relations
  policy.

3.4 IDENTIFICATION, SCREENING  AND ANALYSIS
   OF ALTERNATIVES

  Previous  efforts focused  on gathering  data and
  assessing the existing contamination at the  site.
  This  section describes procedures for  assessing
  the applicability of available alternate water supply
  options to the specific set of site conditions. The
  assessment includes,  (1)  the  identification of the
  alternatives,  (2) preliminary screening of water
  supply alternatives and  (3) analysis  of  the
  alternatives which survive the screening.

     3.4.1  IDENTIFY ALTERNATIVES

        While  there  may be other  possibilities,  the
        following list  covers  the  major  categories of
        alternatives that have survived screening at
        other  Superfund sites and  that  will be
        considered in this guidance document:

        •  No action (under remedial program only)

        •  Connection with  an existing municipal or
           private supply

        •  Develop  new  uncontaminated  water
           resources
        •  Removal  of contaminants via treatment

        •  Oversized community storage facilities to
           compensate for  loss of  existing system
           capacity

        •  Blending  contaminated   portion  of  water
           supply with  uncontaminated  water
           supplies  to  reduce contaminants to safe
           levels.

        In the development  of each alternative, the
        efficiency of the current system or a potential
        existing  system  should  be   assessed.  This
        assessment may be available from the utility
        or  from  previous  work. In many  cases,
        additional capacity may be created by taking
        steps  to  control leakage from  the  existing
        system,  thus eliminating the high costs of
        implementing a new  system. By such actions,
        it may be possible to increase the volume of
        safe water available  from the current system
                                                  3-11

-------
 or allow a neighboring system to provide the
 capacity needed.
 Connection To Existing Municipal Or Private
 Supplies

 If there is a public water supply  with  an
 uncontaminated  water  supply in  close
 proximity,  connection to the existing supply
 may  be a viable alternative.  It  is  strongly
 encouraged that existing supplies be used in
 implementing  alternate  water supplies
 wherever possible. In fact,  some  states have
 coordinated  Public  Water Supply  Master
 Plans that  discourage the proliferation of small
 public water systems in areas  where existing
 systems  have expansion  capacity  and a
 willingness to service new developments.

 In general, public  water  supplies  can be
 classified  as  publicly  owned  (municipally
 owned) or privately owned  (investor  owned).
 Private water suppliers are  regulated  by rates
 and  franchise (service  area) in  each  State,
 the District of Columbia, and the territories by
 a Public  Utility  Commission (PUG). Public
 water suppliers are generally not regulated by
 State PUCs; in some States, if a public water
 supplier sells water outside  its  corporate
 boundaries, its rates and/or franchise  areas
 fall under the jurisdiction of PUCs.

 Under  the Safe  Drinking Water  Act, a
 community water supply is  defined as having
 15 or more service connections or serving 25
 or more people substantially all  year  long. In
 general, all others  are defined as  non-
 community water  supplies.  Community  water
 supplies are more strictly regulated under the
 Safe  Drinking Water  Act.  Non-community
 water suppliers are  required to  monitor for
 acute hazards  but  less  frequently  than
 community suppliers.  (For  a  complete
 discussion, the reader should refer to  40 CFR
 part 141.) Community water supplies  may be
 either publicly  or  privately owned,  therefore,
 the ownership of the  water supply is not
 relevant when  classifying community  or non-
 community water supplies.

 Depending on  the  type of water  supply
available,  a number of factors  must  be
considered  to help determine the feasibility of
using  existing sources as follows:
 Connections to a Private,  Community Water
 Supply

 •   The rates charged to the new homes will
     be regulated by a PUC

 •   The  more  complete  monitoring  and
     reporting  requirements for acute  and
     non-acute materials  under the Safe
     Drinking Water Act will be required

 •   The water company's franchise may have
     to be extended by the PUC.

 Connections  to a  Private,  Non-Community
 Water Supply

 •   The rates charged to the new houses will
     be regulated by a PUC

 •   The  less  stringent  monitoring
     requirements under the Safe  Drinking
     Water Act  will  apply (other  criteria  may
     still be relevant and appropriate, however)

 •   Too  many  new  connections may cause
    the non-community supplier to  become
    a community supplier

 •  The water company's franchise may have
    to be extended by the PUC.

 Connections to a  Public,  Community Water
 Supply

 •  If the new  connections  are  outside the
    community's corporate boundaries, rates
    may  be regulated by  the PUC.  If the
    community  becomes regulated because
    of the new connections,  there  may  be
    opposition from  the  community.  A
    wholesale  supply  arrangement   where
    water is supplied in  bulk at the townline,
    may  preclude this problem.  In addition,
    the community may not want to extend its
    system outside the corporate boundaries
    because such  a  provision could  foster
    growth outside  of  the  town,  drawing
    business away from the town.

•   If the community's rates to the new
    homes would be  unregulated, there is  no
    regulatory  agency protecting the new
    connections from unfair charges.

•   The  more  complete  monitoring and
    reporting  requirements  for  acute and
    non-acute   materials under the Safe
    Drinking Water Act will be required.
                                          3-12

-------
Connections  to  a Public, Non-Community
Water Supply

•   If  the  new connections are  outside the
    community's  corporate boundaries,  rates
    may be regulated  by the PUC.  If the
    community becomes  regulated because
    of the  new  connections,  there  may  be
    opposition  from  the community.  A
    wholesale supply  arrangement  may
    preclude  this problem. The  community
    may  not want to extend  its  system
    outside the corporate  boundaries to foster
    outside growth.

•   If the  community's  rates to  the new
    homes would be  unregulated, there is no
    regulatory agency protecting  the new
    connections from unfair charges.

•   The  less   stringent  monitoring
    requirements under  the  Safe  Drinking
    Water Act will apply (other  criteria may
    still  be  relevant  and  appropriate,
    however).

In addition to the factors presented above,
considerable  institutional  and  political
resistence may  result due  to  the loss  of
autonomy caused by connection to another
existing supply.

Development of New Sources

New  ground water  sources  which  may be
available  include shallow wells  that can be
drilled upgradient of the contamination  source
so that the  ground  water is unaffected by
pollutants from the source. Such  an approach
may  also serve  to retard movement  of  the
contaminant  plume  downgradient of  the
source  if there  is sufficient  pumping. If an
aquifer  is located below the contaminated
aquifer  and is not hydraulically connected to
 it,  new wells can be drilled  in this  deeper
 aquifer. It is difficult,  however, to demonstrate
 conclusively the  absence of hydraulic
 connections. Therefore,  this option  should
 only  be used in cases where no other water
 supply is available. Finally, new  wells  can be
 drilled away from the source so that, with
 controls to  prevent  additional  contaminant
 migration,  a safe  water  supply can  be
 guaranteed.

 New surface water sources that may  be
 available  include streams,  rivers,  ponds,
 lakes, and reservoirs located upgradient from
this site. If these surface supply sources have
adequate watershed  yield and  quality, then
they may be  located  downgradient of the
source,  provided that the surface  supply is
not  hydraulically  connected   to  the
contaminated aquifer or, if downgradient, is a
safe distance from the source.

In cases where the location of the  source is
unknown,  it may be  difficult to predict the
locations  of potential water  supplies  and
detailed  sampling  and  analysis   may  be
required.

Removal Of Contaminants Via Treatment

Depending on  the  contaminants present,  a
treatment process can be designed to remove
contaminants and  reduce levels to comply
with drinking water standards.  Treatment of
contaminated  water  supplies is   used to
provide drinkable water at the tap and not as
a source remediation. The SARA preference
for treatment in Section 121(b) is,  therefore,
not  a primary  consideration  in  providing
alternate water  supplies.  Treatment  should
generally  not  be selected in  cases where
existing sources are available  to  meet the
demands  of the affected community.  The
treatment necessary to remove a  variety  of
contaminants can be complex and can involve
treatment  trains  consisting  of  various
processes in series. Processes used  can be
physical, chemical, or a combination of these.
Treatment  alternatives  require   additional
considerations to determine  applicability to  a
site depending on suitable space and facilities
to  locate the  treatment  equipment.
Environmental and public health assessments
will  need  to be performed to assess any
potential dangers  of the treatment process
itself. Many processes involve the  release of
hazardous gases  or  vapors which must be
controlled  as  well  as  treatment  media
 requiring  disposal  as a  hazardous waste.
Table 3-1   presents a  matrix  of  potentially
 applicable  treatment processes for a variety
 of pollutant types.

 Physical Processes

 Physical processes are those which separate
 the contaminants  from the  water  stream  by
 either applying  physical forces or changing
 the physical form  of the contaminants.   In
 these processes,  the chemical structure of
 the contaminants remains the same, and the
                                           3-13

-------
                                                            TABLE  3-1
                                      TREATMENT PROCESS  APPLICABILITY  MATRIX


TREATMENT TECHNOLOGY

CHEMICAL TREATMENT
CHEMICAL OXIDATION
ALKALINE CHLORINATION
OXDATCN
CHEMICAL REDUCTION
NEUTRALIZATION
PRECIPITATION
ION EXCHANGE
WET AIR OXIDATION
PHYSICAL TREATMENT
CARBON ADSORPTION
DENSITY SEPARATION
SEDIMENTATION
FLOTATION
FILTRATION
REVERSE OSMOSIS
STRIPPING
EQUALIZATIONOETENTION



ALCOHOLS
E
E
N
G,E
N
-


X

V




V

-



ALIPHATICS
V
V
N
P
N
-


X

V




V

-



AMINES
V
V
N
N
N
-


X

V






-



AROMATICS
V
V
N
F,G
N
-
F

X

G,E




C
E
-



i
G
G
N

N
-


X

V






-


i
HALOCARBO
P
P
N
F,G
N
-


X

G,E





E
-



METALS
PiF
P.F
N

G
-
E
E


N,P

E
G
E
E
N
-
POLLUTANTTYPE


B
N
N
N

N
PHI




E








PESTICIDES
N,P
N,P
N
E
N
ONTRO


X

E




E



PHENOLS
G
G
N
E
N



X

E




V

PRETREATMENT -


PHTHALATES
G
G
N

N
-
G

X

E






-

5
POLYNUCLB
AROMATICS
N,P
N,P
N
G
N
-
R



G,E






-


CYANIDE
F,G
F.G
E
E
N
-
N

X

N





N
-



G,E
G,E
N

N
-
N
N


N





G
-
Q
j>
TOTAL DISSO
SOLIDS
N
N

N
N
.
N
E
N

N




E
N
-
s
o
TOTALSUSPE
SOLIDS



•

-






X

X


-

5
GREASE AND





_







X



-
KEY
E - Excellent Performance Likely
G - Good Performance Likely
F - Fair Performance Likely
P - Poor Performance Likely
                                                                                                SOURCE: Adapted from Shuokrow etal., 1980
R - Reported to be Removed
N-Not Applicable
V - Variable Performance Reported for Different
   Compounds in the Class
X - Treatment is Applicable but not
  Specified in the Source Reference
 - A Blank Indicates no Data Available

-------
advantages of these systems  are that  the
processes  are  usually  simple,  relatively
inexpensive, and can  be applied  to a wide
range of wastes. Below is  a summary of
these processes.

•   Air Stripping - a process which removes
    volatile  organic  contaminants  via  mass
    transfer  from the  water  phase  to  the
    gaseous (air) phase. This process is often
    used in  combination with  a vapor  phase
    carbon  system  to  remove   the
    contaminants from the air before it  is
    released.
•   Steam  Stripping  - a process similar  to
    air  stripping  used for   less  volatile
    compounds where  the gaseous phase is
    water vapor

•   Activated Carbon Adsorption - a process
    by which contaminated water is  passed
    through activated carbon  and soluble
    organic  contaminants are  removed from
    the water stream  by adsorption onto the
    carbon

•   Filtration -  the removal   of  suspended
    solids from  a fluid by passage  through
    porous media

•  Ion  exchange   -  the  process  of
    exchanging toxic  ions  in solution  for
    non-toxic  ions   using  a  solid   ion
    exchange resin

 •  Membrane  separation  -  the  use  of
    specifically  constructed  membranes to
    selectively  reject  contaminants as water
    passes through the membrane

 •   Phase Separation - physical separation
     of  components  with  a specific  gravity
     different from water, such as skimming oil
     and grease constituents  off  the  top or
     settled  solids sludge removal from the
     bottom of a clarifier

 Chemical Processes
 Chemical treatment  processes alter the
 chemical structure of the contaminants to
 facilitate removal of  the contaminants  from
 the  water  stream. Below is  a summary of
 some of these processes.
 •  Chemical   reduction-oxidation  (redox)
     treatment  - this  process makes use of
     oxidizing agents such as ozone, hydrogen
   peroxide, or  UV/ozone  to induce  the
   oxidation of the contaminants in the water
   stream  and to reduce  or  eliminate  the
   toxicity of many toxic organics and heavy
   metals

•  Neutralization  - the additional  of an acid
   or base to adjust the pH of  the water to 7
   (neutral)

•  precipitation/Flocculation - the process
   where coagulant chemicals such  as lime
   or ferrous sulfate are added to the water
   to precipitate  out dissolved solids and to
   agglomerate  suspended solids so  that
   they will settle out by gravity

Treatment  processes  are  usually used  in
combination  to  remove several  types of
contaminants.  For  example,  a  typical
treatment  process   could  involve
precipitation/flocculation with lime to  remove
suspended solids and metals in the water,  a
gravity filter  to remove solids and  colloidal
residual  material, an  air stripper to  remove
volatile  contaminants  such  as  trichloro-
ethylene or  tetrachloroethylene,  and  a  final
polishing step with activated carbon to adsorb
any  organic contaminants  which may  not
have been removed in the air stripper.

The decision on  which treatment processes
should be used and design criteria should be
based on the type of contaminants  present,
data  available  on  effective  treatment
processes,  and  (at times) on  bench or pilot
scale  studies.  For some  well  known and
understood processes such as  air  stripping
and carbon adsorption,  enough data  are
available that a  full  bench and pilot scale
study  may not  be necessary. However, for
 other  lesser known  processes,  a  properly
 designed study  should  be used to obtain
 removal efficiencies and design criteria.

 Oversized Community Storage Facilities

 If an  alternate  supply  (or  the  portion  of a
 community's  supply   which  is   not
 contaminated) does not have a sufficient yield
 to  meet  maximum  demand,  round-the-
 clock pumping  and an  oversized storage
 facility may  provide adequate  flows.  It should
 be  noted,  however,  that such  facilities are
 commonly used only  for demand fluctuations,
 fire flows, emergencies,  or other situations in
 which the  demand  exceeds normal  daily
                                            3-15

-------
 demand and  cannot  be  used  alone  to
 overcome  the  loss of  source  capacity.
 Excessive pumping of single or multiple wells
 cannot  be  maintained for  extended periods
 without loss of source capacity.

 Blending Uncontaminated  Water with Portion
 of Contaminated  Water Supply to Achieve
 Safe Levels

 At times, water obtained from uncontaminated
 or new  sources (described above) may be
 mixed with  existing supplies which result in a
 dilution  of  pollutants  to levels  within water
 quality  standards  or  criteria.  Such  an
 approach  requires  daily  monitoring  and
 specialized  control equipment to assure the
 quality  of the contaminated supply remains
 consistently within standards or criteria. This
 alternative  should only  be used  as a  last
 resort.

 3.4.2   PRELIMINARY SCREENING

    The  screening and analysis  process  was
    outlined in the flow chart shown in Figure
    2-3.  Preliminary  screening  indicates
    which of the identified alternatives may be
    suited for  implementation, considering the
    specific site conditions and surrounding
    resources.

    The  alternatives in  the flow  chart  are
    ordered from  most desirable to least
    desirable.  The flow  chart is devised  so
    that the  user can move  directly to detailed
    evaluation  as  soon   as  a  feasible
    alternative  is identified. In  cases where
    time  is very limited, a full scale evaluation
    of all potential  alternatives  may not be
    feasible.  Generally,   however,  it  is
    recommended that  the flow  chart be
    followed in its entirety.  This  is especially
    important because  alternatives other than
    those considered in this guidance are not
    given consideration until the end of  the
    process. The user should also note that
    the hierarchy of these alternatives will not
    be applicable to all  sites and situations
    and  al!  feasible  alternatives  should  be
    given equal analysis before a recom-
    mendation  is made.
3.4.3   ANALYSIS   OF
       ALTERNATIVES
SELECTED
   An analysis is performed for each of the
   alternate water supply alternatives which
      have survived the preliminary screening.
      The analysis is data intensive and should
      only  be performed for alternatives which
      are viable candidates.

  There are  five   major  elements of  the
alternative analysis:

  •   Engineering   analysis  -  timeliness,
      performance,           reliability,
      implementability/constructibility,  and
      safety

  •   Cost analysis

  •   Environmental protection analysis

  •   Public health analysis

  •   Regulatory/institutional analysis.

  Each  of  these  topics is discussed  briefly in
  the following paragraphs, however, the user is
  directed to the primary  guidance documents
  referenced  in Section 1.0 for supplementary
  information. The  format  presented in this
  guidance does not match either the EE/CA or
  FS  process exactly.  Rather, this  document
  focuses on the information needed to prepare
  an  EE/CA  or FS  specifically  for  alternate
  water  supplies.  In preparing an  EE/CA or FS
  report, always  use the  format  specified  in
  those  guidance documents.

  Engineering Analysis

  The user should characterize each response
  action alternative in terms of major equipment
  required (including  sizes and specifications),
  personnel  requirements,  chemical and  utility
  requirements, and  specific  waste  disposal
  strategies.  Using the  information developed,
  the  user  should next compare  alternatives
  using the  following technical criteria:

  •   Timeliness - the speed  with which the
     selected alternative can be implemented

  •   Performance   -  effectiveness  and
     efficiency  in  accomplishing   design
     objectives over  the  system's useful life
     including the ability to meet established
     drinking water criteria

  •   Reliability  -  operation  and maintenance
     requirements, demonstrated  performance
     of  equipment  over time,  and  level  of
     operator training required
                                          3-16

-------
•   Implementibility/constructibility  -  (site
    conditions  and conditions external to  the
    site) and availability of adequately trained
    operation and maintenance personnel

•   Safety -  on-site personnel,  nearby
    communities, surrounding environment.

A  significant  degree  of  variation  can exist
between  the  success of techniques  when
applied for different  wastes and  in  different
hydrogeological settings.  A tabular summary
should be developed  including a  mechanism
for presenting positive and negative  features
of each alternative according  to  engineering
evaluation criteria.

Additional guidance  is available  in  the
literature  on the   details  of  potential
technologies  for  inclusion in remedial  or
removal  action alternatives and  the use of
technical  comparison  criteria.  Specific
information  on particular technologies  and
procedures  can  be  obtained  from  vendors,
equipment  manufacturers,  and  cleanup
contractors.

Case studies concerning the actions  which
have been  taken by other  individuals who
have faced  the  problem  of contaminated
water supplies should also provide information
on  potential  technologies and  their track
records. Superfund sites with alternate water
supplies are noted in Appendix A.

 Cosf Analysis
 Costs consist of all  capital  outlays, general
 and administrative expenses, and other costs
 required for  implementation  of  the
 remedial/removal action including engineering,
 design, and installation, as appropriate. Some
 cost data  may be  developed  during the
 screening   and  analysis  of remedial
 technologies  and would be very useful and
 applicable for this more detailed analysis.

 The  cost   analysis  should   take  into
 consideration  the  demand  requirements
 determined  according  to the guidelines
 discussed in Section 3.2.2. If an alternative
 includes  a distribution  system,  the cost  of
 constructing the distribution system should be
 included.  The  cost  of connecting existing
 households to the alternate water supplies will
 also be included.  EPA  does  not provide
 specific consideration for future  development
 (e.g., while  EPA will not preclude the owner
of an  empty lot from extending  a service
connection to buildings once the property is
developed, EPA  will   not consider  the
possibility  of  such future  connections in
determining the  size  of the mains to  be
installed  or the water supply necessary to
provide an alternate water supply). Whenever
possible  EPA will  use  existing  distribution
systems  or work with  the  public utility to
provide new distribution  systems so that the
cost of constructing the distribution system is
not borne by EPA.

The following list presents several costs that
should  be  considered   and  quantified
(discounted to  present  worth) during a  cost
analysis:

•  Engineering expenses, such as technical
    services related to  drilling,  sampling,
    testing,  designing,  managing,   and
    reviewing the response action

•  Land-related  expenses  for  the rent or
    purchase of  right-of-ways  easements,
    as well  as  expenditure  for land/site
    preparation  (if no  other  options  are
    available  for providing the  distribution
    system)
 •  Construction costs including direct outlays
    for equipment, hardware, materials,  and
    labor
 •  Transportation  and other costs associated
    with the disposal of wastes  (including soil
    and  sediments generated  from drilling
    operations  if  drilling  occurs   into
    contaminated soils)  at  an  approved off-
     site  facility
 •   Start-up  costs  including  operator
     training,  temporary professional services,
     additional testing, monitoring, processing
     contracts,  and equipment  and materials
     transport.

 All known costs associated with construction
 should  be included because these costs will
 be  used for  budgeting  purposes. EPA does
 not  provide  the  funds for operation  and
  maintenance of the system; however,  these
 costs should  be included  in  preparing  a
  budget  to provide a total cost of the system.
                                            3-17

-------
 The discount value  for  purposes  of the
 present worth analysis should be 10 percent.

 Environmental Analysis

 Provision of an alternate water supply would
 generally   not  consider  mitigation  of
 environmental  risk;  however,  selected
 technologies  must  be analyzed for possible
 increased  risk to  the environment. The
 analysis should focus  on  the adverse and
 beneficial   impacts  of  each  response
 alternative.  Some  alternatives   involve
 elements requiring  significant construction
 activities which may result in various negative
 environmental  impacts;  however,   these
.impacts are typically  short-term in nature.
 Other alternatives,  such as  operation  of  a
 treatment facility, may  require the handling of
 hazardous  materials.  This  situation  may
 increase the risk of exposure or accident and
 these impacts are more long-term.

 Potential  adverse  environmental  impacts
 which  may  preclude the  use  of  each
 alternative should be identified. Major actions
 required to  implement each alternative must
 be identified and a determination made as to
 whether any of these actions  will  or  could
 result in adverse environmental impacts.

Alternatives  that  cause significant  adverse
impacts or  do not adequately  protect the
environment should  be  eliminated; the
reasons the  alternatives  were  eliminated
should be documented. Beneficial impacts  of
a  response action  alternative  should  be
balanced against  any  potential  adverse
impacts.  The following  issues  must  be
considered:

•   Discharges of contaminants  to  the air,
    land, ground water, or surface water

•   Disruption of normal community  activities
    due to construction-   related  impacts
    (e.g., subsurface construction)

•   Characteristics  of long-term  system
    operation which may create a disruption
    or nuisance to the surrounding  community

•   Failure of alternative system to effectively
    and reliably  remove contamination  and
    provide potable water of adequate quality
    and quantity to the service area

•   Processes which increase the area and/or
    level of contamination in the study area.
 Public Health Analysis

 Public health analyses must be addressed to
 ensure that the alternative mitigates the actual
 or potential threat to public health  presented
 by  the contaminated  supply.  Remedial
 alternatives  are  generally  designed for risk
 level  in the 10-4 to 10-7  range, consistent
 with 300.68(c) of the NCP revisions.

 Impacts of the  alternatives should also  be
 considered. For instance, in  very  small
 communities, economies of scale may make
 central  treatment a  high  cost response
 alternative.  In  such cases,  use  of  home
 treatment  devices (e.g.  granular  activated
 carbon)  may represent a lower cost option.
 This   option,  however,  would  need to  be
 considered  with a  centrally  coordinated
 maintenance and monitoring program  which
 complies with State and Federal policy,  as
 activated carbon  requires regular regeneration
 to  provide  adequate  treatment and prevent
 the  growth of microbes.   Improperly
 constructed new  wells can  provide  an
 effective conduit for wastes to move from a
 contaminated aquifer to an uncontaminated
 aquifer.  Safety considerations (worker health
 and safety  during construction  and general
 safety features associated with  the site,  e.g.,
 protection of personnel from moving parts of
 pumps)  will include those that must  be
 implemented   both  during  and after
 implementation   of  the   selected
 strategy/technology.

 Regulatory and Institutional Analysis

 An analysis of Federal and State applicable or
 relevant and  appropriate requirements
 (ARARs) is  necessary  to  understand the
 possible impacts  of  implementing  the
 response action  alternatives. These  statutes
 and  regulations  may  directly impact overall
 feasibility, technical feasibility,  engineering,
 design, costs, and schedules associated  with
 any or all of the alternatives.  Local regulations
 may also require  consideration.  For  example,
 a certain water district may be forbidden from
 selling water to an adjacent  town. Thus, this
 analysis  must be completed as early as  is
feasible so  that regulatory constraints can be
identified and incorporated  into  subsequent
analyses. Any alternatives  which would  be
precluded or prohibited because of regulatory
restrictions may  not  warrant   further
                                          3-18

-------
consideration.  It  should  be noted,  however,
that  Section  121  of SARA specifies six
situations  in which ARARs may be waived.
These waivers should be investigated prior to
ruling out  a desirable alternative. Appropriate
officials  at  the Federal, Regional, State, and
local levels should  be contacted to review
response   actions  being  considered for
providing the community with alternate water
supplies. ARARs must be  determined  on  a
site-specific basis.

As  described  in  Section 3.1.5,  State
standards  and criteria must be considered in
evaluating  possible remedies for  remedial
authority sites. Generally, the remedial  action
selected will  meet State standards  that are
applicable  or relevant and  appropriate when
more strict than MCLs. If State standards are
waived,  the action must fit one of the waivers
identified  in section  121  of SARA. These
waivers  will be discussed in more detail in the
proposed NCP. Removal actions will attain or
exceed  ARARs or other Federal and  State
environmental  and  public health  laws to the
maximum  extent practicable considering the
exigencies  of  the  situation.  Specific
information on ARARs is presented in the
CERCLA  Compliance  with  Other  Laws
Manual  (EPA 1987).

Information on the responsibilities, authorities,
and potential roles of Federal agencies during
the planning and implementation of a remedial
action is presented in Guidance Document for
Feasibility  Studies under  CERCLA  (EPA
1985).  The  document  also includes an
extensive   list of  regulatory requirements
which potentially apply to the implementation
of a remedial action alternative.

Comparison of Alternatives.

A method  for evaluating  options is presented
in Table  3-2. Alternatives  with  high  costs
and  few  public  health  or  environmental
benefits should be eliminated. Those options
with  unacceptable  adverse  environmental
impacts or public  health  risks would be
eliminated,  (n addition,  alternatives  with
design  limitations  or  which  are marginally
proven  would  be given a low priority due to
the  length  of time  generally  required to
implement such  remedies.  This evaluation
process  will result  in   selection  of  a
       recommended  alternative  or  range  of
       alternatives for presentation to EPA.

     3.4.4  RECOMMENDED ALTERNATIVE

       Based upon the  results  of the  detailed
       analysis,  a potential  remedial action/removal
       action alternative will be selected by EPA that
       can  be  implemented  in  a  cost-effective,
       technically feasible,  and  environmentally
       acceptable manner.

3.5 PREPARE EE/CA OR FS REPORT
     Actions  performed  under  removal  authority
     (including ERAs) will require an EE/CA  report;
     remedial  authority activities will require  an  FS
     report.  The purpose  of  the  EE/CA  and  FS
     reports is to present the results of the study and
     to provide the community with an opportunity to
     review  and  comment  on   the   Agency's
     alternatives  and recommended response.

     These reports should be  consistent with  the
     appropriate  guidance. The EE/CA and Feasibility
     Study Guidance Documents contain  information
     on the appropriate  report  format  and specific
     contents of  each report.

3.6  PUBLIC PARTICIPATION

     Following completion of the EE/CA or FS  report,
     a 21-day public comment  period is  conducted
     under both  authorities. This is  to provide  the
     public with an opportunity to comment  on
     proposed  actions  before the design  and
     construction process begins. This public input is
     then considered in selecting the final remedy. A
     public hearing  may also be conducted for local
     citizens to  voice their concerns and opinions.
     Under both authorities, all relevant  information
     pertaining to  decisions made  for the  site is
     placed into  an  administrative record and  a local
     information  repository is established. Revisions
     under consideration for the  NCP may extend the
     public comment period to 30 days.

3.7  SELECTION OF REMEDY

     Following the public comment period, a remedy
     will  be selected from among the alternatives for
     implementation at the  site. The alternate water
     supply  remedy should  be consistent  with  the
     final remedy for the site and in accordance with
     the  guidelines in  the  NCP for the  respective
     program.  The selected remedy should represent
     the  best balance across all of  the engineering,
                                          3-19

-------
                                                   Table 3-2 EXAMPLE OF DECISION MATRIX
Alternative
1. No action


2. Connection to
Minneapolis
water system

3. Drill deeper
wells to
underlying
formations


4. Aquifer treatment
A. Ozone











B. Granular
activated
carbon
(GAC)







Cost ($1,000)
Capital



250


1,870





374




459



709


633




633


633


Present
Worth
— -_


8,102


2,916





1,618




2,109



2,434


2,150




2,263


24,050


Public Health
Concerns
Unacceptable exposure to
PAH during sunnier or
during fires.
Reduces public health
threat to less than
10 (migration).

Reduces public health
threat to less than
i
-------
protectiveness, and cost factors examined in the
analysis as presented in Section 3.4.3.

Under  remedial authority, the selected  remedy
will be developed and presented  in the  Record
of Decision  (ROD). The  ROD will contain  an
accurate and complete summary of the site, the
threat it poses, the selected remedy, as well as
the relative strengths and weaknesses of each
alternative considered and  a clear justification
for the final decision that is  made.  Under
removal authority, the selected remedy will  be
developed  and  presented  in an  Action
Memorandum.  The  Action  Memorandum also
provides  a   site  description,   threat
characterization,  and justification for the final
removal action selected.
                                            3-21

-------

-------
                                   4.0  ALTERNATE WATER SUPPLY
                                     DESIGN AND IMPLEMENTATION
    This section  outlines  procedures  for designing
    and implementing an  alternate water  supply
    system. The procedures and  requirements for
    selection,  design, and  implementation will vary
    according to the lead  agency involved.  This
    document discusses  the  general procedures
    involved  in  Federal-lead cases.  For  more
    complete  guidance  on  developing   State
    Superfund  contracts,  cooperative agreements,
    contract documents and implementing remedial
    actions,  the  user  should  consult  EPA's
    Superfund Remedial  Design  and  Remedial
    Action  Guidance  (June  1986) and   other
    appropriate documents.  For  removal   sites,
    consult the Technical  Assistance  Team (TAT)
    Contract Users Manual (Draft, August 1987) and
    the  Emergency Response  Cleanup  Services
    (ERCS) Users' Manual (Draft, August 1987).
4.1   DESIGN   AND
     PROCEDURES
IMPLEMENTATION
     Source, treatment, and distribution facilities are
     the principal  components of an alternate water
     supply  system.  Previous  sections  have
     discussed the identification and investigation of
     potential new sources for an  alternate  water
     supply. This section  will  discuss design and
     implementation procedures.

     4.1.1  GENERAL CONSIDERATION

       Most states require the approval of plans and
       specifications  for public  water supply facilities
       before construction begins. System additions,
       major alternations and new installations come
       under this  provision. Over  the  years,  the
       review agencies have  established  minimum
       design requirements and  standards.  New
       facilities should be in compliance with these
       standards where possible.

       The design engineers are  advised  to meet
       with regulatory agencies in  the early stages,
       preferably during preparation of the predesign
       reports.  State or local  engineers are often
       able to contribute helpful information  to assist
       designers  because of  their experience and
       knowledge  of local conditions.  Consultation
       with agencies such as the  U.S. Geological
       Survey and U.S. Public Health Service is also
       recommended  to  obtain  as  much  basic
  information concerning the proposed  project
  as possible.

  A safety factor is  usually considered  on  the
  basis  of  system  capacity.  The rated  or
  nominal capacity of the water supply system
  should  exceed  the maximum  daily water
  demand. For systems  comprising more than
  one  system,  the combined capacities should
  exceed the maximum daily demand.

  Careful survey  work  is  recommended  to
  eliminate expensive changes and  revisions in
  the  design  stage, during construction,  and
  after  completion.  Investigation  of  soil
  conditions  is  necessary  to   determine
  protective  coating requirements,  excavation
  procedures, permissible foundation pressures,
  design of anchor or thrust blocks and level of
  water tables.

4.1.2  TREATMENT  PROCESSES  AND
      FACILITIES

  The quality of the source, its variations and
  possible  future changes, and the cleanup
  levels form the basis for selecting a treatment
  process. The proven and  simple processes
  are preferred, especially for actions with time
  constraints. Alternative  and   innovative
  technologies, though  preferred  by  SARA,
  generally require  longer  periods  of time for
  implementation  and  are  not as  reliable  as
  proven  technologies and thus may  not be
  appropriate for alternate  water supplies.  For
  highly contaminated  water,  a  more
  conservative allowance for standby units
  should be  applied  than might be required for
  a single contaminant,  as reliability becomes
  more difficult to attain.

  Site  selection  and  acquisition for new
  treatment and storage facilities are likely to be
  time consuming. An accurate estimate of area
  required is important. This can be determined
  by a preliminary layout  of  tanks, buildings,
  and pumping and storage structures. Physical
  characteristics of new treatment  facilities  site
  will  affect  construction. Flooding, foundation
  conditions, ground  water  level, and  site
  preparation,  including clearing, grading, and
  drainage, are factors which directly influence
  the cost of construction. Flood records should
                                                4-1

-------
  be carefully  examined  because protection
  against flooding is essential.

  The availability of electric power must be
  ascertained.  A site  for  treatment  facilities
  linked  to  more than one source of outside
  power is favored with respect to  continuity of
  operation.

4.1.3 TRANSMISSION  AND  DISTRIBUTION
      FACILITIES

  Surveying  and laying out  of pipelines  are
  affected by both the size of the line and its
  location. More details and care are necessary
  as the size increases and as a line passes
  from rural to urban areas.

  In general, a  plan and profile, together with
  certain other details, are  necessary  for any
  water pipeline. The AWWA Manual of Water
  Supply Practices  recommends including  the
  following:

  •   Horizontal and vertical distances,  either
      directly or by survey station and elevation

  •   Location  of  angles  or  bends,  both
      horizontal  and vertical  (point  of
      intersection preferred)

  •   Degree of bends,  degree or  radius  of
      curves, tangent distances for curves,  or
      external distances if clearance is required

  •   Points of intersection with pipe centerline
      for tees,  wyes,  crosses, or other
      branches, together  with  direction-right
      or left hand,  up  or  down--or angle  of
      flow, viewed from inlet end

  •   Location and covering length of all valves,
      pumps, meters or other fittings

  •   Location  of  adjacent  or  interfering
      installations or structures

  •   Tie-ins with  property  lines,  curb  lines,
      road  or  street centerlines, and  other
      pertinent  features necessary to  define
      right-of-way and  locate  pipe centerline
      clearly

  •   Details or descriptions  of  all  specials,
      together  with  other  data  required  to
      supplement AWWA standards

  •   Details,  dimensions,  and   class
      designation or other  description of all
      flanges and mechanical field joints
       •   Any  special requirements affecting  the
           manufacture of the pipe  or  installation
           procedures.

     4.1.4  STORAGE FACILITIES

       Present and future  storage requirements  are
       to be considered for the design of the storage
       facilities. The required  storage capacity must
       provide for the following:

       •   Hourly  fluctuations—total  volume
           required  to meet  hourly consumption
           fluctuations  on   days  of  maximum
           demands  (generally  taken  to be a
           percentage  of the  maximum  daily
           demand). Fluctuation volumes above  the
           maximum  daily  demand  rate  are
           estimated using the projected peak hour
           to  maximum  daily  demand  ratios. This
           consideration helps  to  dampen  hourly
           demand  fluctuations at pumping stations,
           thus reducing operation costs.

       •   Fire  Flow—based  on  the  rates  and
           durations established by  the ISO. This
           consideration  helps to  reduce  pumping
           station capacity  and construction cost.

       •   Emergencies—A volume  of water  for
           emergencies in  case of pipeline breaks,
           mechanical  equipment  malfunctions,  or
           power failure. Emergency  storage is  not
           required  if full standby  power and a
           back-up water supply  is  provided.
           However,  if  standby  power  is  not
           provided, and/or a  back-up water supply
           is  not provided, the volume  of active
           storage that is generally recommended is
           equivalent  to  the average daily demand
           volume.

4.2  TREATABILITY STUDIES

     Before designing  an alternate  water supply
     system, treatability studies and pilot testing may
     be required  if  water treatment is the selected
     alternative.  Performing treatability  studies  will
     delay  the implementation of  alternate water
     supplies  and  should only  be  performed if
     necessary.  Sites  with  standard types   of
     contaminants  and  using  proven  treatment
     technologies will not generally require studies to
     be performed.  The  following  sections  discuss
     the  purposes and  procedures of bench-scale
     and pilot-scale testing.
                                           4-2

-------
4.2.1 BENCH SCALE

   Treatability studies  may be  required  to
   evaluate the effectiveness  of  a  treatment
   scheme.  If  treatment  is  recommended,
   studies should be  conducted  as soon as
   practicable.  Treatment of both  toxic  organic
   and  inorganic  contaminants  may  be
   considered.  Appendix  E  (adapted  from
   Shuckrow  et al.  1980)  presents  the
   applicability of various treatment processes to
   the  hazardous substance  list.  For more
   details, review Concentration Technologies for
   Hazardous Aqueous  Waste   Treatment,
   (Touhill 1981). Depending on the number and
   type of pollutants found in the water supply,
   two  or three treatment technologies  are
   generally  selected for  possible use.  The
   process  which  will  remove  the  worst
   contaminants most effectively will be the first
   examined  during the bench-scale studies.

   To monitor the effectiveness of the bench-
   scale testing,  representative compounds are
   selected from each pollutant group and are
   traced  through  the  system.  The
   representative compound should generally be
   the most difficult to remove by the selected
   treatment  process.  For example,  if  carbon
   adsorption is the chosen treatment process,
   the compound with the  lowest adsorbability
   should be  analyzed.   The selection of
   representative indicator compounds should be
   made,  however,  on  a  site-by-site  basis;
   this  will promote  high  quality  response
   activities.

   Once the  carbon adsorption system reaches
   equilibrium, a complete priority pollutant scan
   (if appropriate) can be run to determine if the
   removal of contaminants was  successful.  If
   the  water  is  still  above  cleanup  levels,
   additional treatment may be required. Other
   processes may also have to be tested.

4.2.2  PILOT SCALE

   Before final design of  a treatment process  is
   completed,  pilot  testing may be  necessary.
   Because of budget and schedule constraints,
   proven  conventional technologies are often
   favored for  alternate  water  supplies.  There
   may be  sufficient  data available on  these
   technologies that pilot  testing would  not be
   required. The goal of such studies is to verify
   the  applicability of processes previously
tested on a bench scale, to refine the design
criteria, and  to  obtain an estimate of O&M
costs.  If bench scale  testing cannot be
conducted  (e.g.,  air  stripping of  volatile
compounds), pilot studies may be  required.
Data  are usually available for predicting size
requirements without pilot testing for common
processes  such as  air  stripping and GAC
treatment.  Such data  may  be obtained by
consulting  equipment manufacturers  or  EPA
personnel  responsible  for implementation  of
treatment alternatives at previous sites  (see
Appendix A).

Bench  scale testing  can provide  adequate
data for conventional treatment plant design
and  processes.  A  conventional treatment
process includes chemical addition, mixing,
flocculation, sedimentation and filtration.  Pilot
testing  is often  appropriate  for  non-
conventional treatment processes  or  for
conventional  plants  which  treat  waters
containing  multiple contami nants.  The  time
required to conduct pilot testing depends on
the selected process and the water quality.
The  following  requirements  should  be
considered for pilot studies.

Operating  Conditions  -  Once  a treatment
alternative  is chosen, the purpose  of a  pilot
study is to  collect operating data and to refine
the design  parameters for full scale design of
the treatment system. Due  to  limitations  in
time  and  money,  a pilot  test  typically
investigates  a   small  range  of operating
conditions.  These conditions are often chosen
based on previous bench scale test results,
on  other full-scale plant operating  data, or
on literature information. As a general rule, all
pilot  processes should  be tested  at  two
significant  loading  concentrations  of  the
influent  water,  at  normal  or "average"
conditions, and at  high  or "stressed"
conditions.

Design  parameters typically  refined  in  pilot
studies  include  chemical  dosages  for
precipitation/flocculation systems, air to water
ratios in air strippers,  and carbon usage rates
for activated carbon adsorption. To save time
and money in the laboratory  analyses, a few
compounds are selected as  the  indicator
compounds and  are  analyzed for during the
study, typically hose which are the most toxic
or the  most difficult to remove  by  the
treatment  process.   However, extensive
analyses should be  done  for all  known
                                           4-3

-------
contaminants on occasion to confirm that the
effluent meets the drinking water standards.

Duration  of Testing - The length  of  time
required to conduct a pilot study is dependent
on various factors. Certain processes require
time to stabilize before steady state  operating
data can  be collected. For example, an air
stripping  process will  stabilize  after  several
minutes (e.g., an  air  flotation  process will
stabilize within 30-60 minutes). Once the
process is stable, data should be collected for
at least a few weeks to assure  that the
process  is achieving the desired results.
Another factor affecting  the duration of the
test is the  number of parameters  studied. An
increase in the number of parameters which
are varied and analyzed will result in a longer
period of  process  stabilization and  require
more time in  which to collect  data.  A third
consideration is  the  variability of the
contaminants in the water source.  This can
be  accounted for  by  operating the  pilot
facility, either continuously or  intermittently,
as appropriate, for sufficient time to  cover the
variation   in  raw  water quality. State
requirements for duration and time of year for
pilot  testing  should   be   taken  into
consideration.

It is possible, in some  cases, such  as  in
carbon adsorption studies, to reduce the time
required to obtain test results by using small,
highly loaded units. This  type of bench-scale
study can  be done in a laboratory rather than
in the field.

Installation and  Configuration  -  Since the
goal  of a  pilot study is to  obtain  design
parameters  and  to  confirm   process
effectiveness,  the pilot plant should  simulate
as closely as possible  the full-scale process.
As a rule of thumb,  a pilot  plant  should
operate at a flow of 5 percent of the full scale
plant. However, the actual flow of the pilot
plant may be determined by economics,
equipment availability, and the extent to which
scale  up  difficulties  are present (i.e.,
processes which do not scale up  well should
have pilot  plant  flow  rates  as  high as
economically feasible).

It is  also possible to have  various units in  a
pilot  plant which do not treat the same flow.
In this case, the flows through  the  plant can
be split into various streams testing multiple
       processes   or  operating   conditions
       simultaneously.

       Mobile and Prepackaged  Pilot  Plants - For
       many applications,  it   may  be  more
       economical  and  feasible  to lease a mobile
       pilot plant. Various manufacturers offer mobile
       treatment systems which include air strippers,
       carbon adsorption, reverse osmosis, filtration,
       metals removal,  neutralization and biological
       processes. Also, if a specialized or proprietary
       process  is  being  considered,  it  may  be
       necessary to  use  a manufacturer's  pilot
       system  to  determine  the  technology's
       effectiveness.

       The  use of  these services  may  include
       sampling, analyses and report preparation,  or
       the  manufacturer  may  just  provide  the
       equipment  and the  contractor would design
       and operate the entire pilot study.

4.3  CONTRACT DOCUMENTS

     In general,  an alternate water supply design will
     contain  the General  Condition  section which
     contains contractual language similar  to  most
     construction projects.  The  next  section,  the
     Technical Specifications,  outlines how the work
     will  be  conducted. Table  4-1  represents  a
     typical table of  contents  in the  Technical
     Specifications  section.  Much of  the  material
     under   Division  1  presents   the  project
     requirements. Divisions 2 through  17 focus on
     the  special conditions and  detail  how these
     conditions  are handled.  The  drawings for  an
     alternate water supply system have the same
     purpose as drawings  for construction-related
     projects. These drawings include the following:

     •     Cover sheet  with project  name,  location
       map, agency, engineer, etc.

     •     Grading, landscaping, and drainage plan
       around any major structures

     •     Plan  and profile of all pipelines

     •     Structural,  architectural,  mechanical,
       plumbing, HVAC, and electrical drawings,
       detail sheets

     •     Typical installation  drawings  for individual
       home treatment devices.
                                          4-4

-------
 Table 4-1    TYPICAL  TABLE  OF  CONTENTS   FOR
            TECHNICAL SPECIFICATIONS
 Section No.                       Description

              DIVISION 1 - GENERAL REQUIREMENTS
 01010                      Summary of Work
 01030                      Special Project Procedures
 01060                      Regulatory Requirements
 01340                      Submittals
 01510                      Temporary Facilities
 01590                      Support Area Facilities
 01601                      Control of Materials
 01671                      Temporary Site Utilities
 01700                      Contract Closeout

              DIVISION 2 - SITE WORK
 02100                      Site Preparation
 02221                      Trenching, Backfilling, Compaction
                           and Grading
 02223                      Granular Fill and Clay Materials
 02444                      Chain Link Fence
 02585                      Learning and Hydroseeding
 02596                      Sheeting and Filter Fabric
 02611                      Concrete Pipe
 02612                      Reinforced Concrete Pipe
 02615                      Cast-Iron Pipe
 02616                      Ductile Iron Pipe and Fittings
 02617                      Steel Pipe
 02618                      Corrugated Metal Pipe
 02622                      High  Density Polyethylene  Pipe
                           and Fittings
 02625                      Concrete Cylinder Pipe Fittings
 02640                      Valves,  Cocks and Hydrants
 02660                      Water Wells
 02734                      Groundwater Monitoring Wells

             DIVISION 3 - CONCRETE
 03200                     Concrete Reinforcement
 03250                     Concrete Accessories
 03300                     Concrete

             DIVISION 5 - METALS
 05500                     Miscellaneous Metal

              DIVISION 6 - WOODS AND PLASTICS
 06100                     Carpentry Work

             DIVISION 11  -  EQUIPMENT
 11201                      Sluice Gates
 11202                     Slide Gates and Weir Gates
 11240                     Liquid Alum Feed System
 11241                      Liquid Alum Storage Tanks
 11242                     Polymer System
 11312                     Pumps
 11313                     Automatic Pump Assembly
 11372                     Compressed Air Supply Equipment
 11373                     Trench and Sump Ventilation and
                          Heating

              DIVISION 13 -  SPECIAL CONSTRUCTION
 13122                     Prefabricated Metal Building
 13124                     Treatment Trailer
 13411                      Steel Tanks
 13416                      Trailer Mounted Storage Tank
 13573                      Treatment Operation Protocol
13574                      Bulking and Consolidation Protocol
13575                      Waste Material
13576                      Transport of Hazardous Materials
13577                      Disposal of Chemical Wastes
13600                      Instrumentation
Table 4-1
Section No.

13700
15061
15062
15064
15101
15102
15103
15107
15108
15113
15100

16000
16110
16310
16460
16470
16480
(Continued)
             DIVISION 15
 DIVISON 16
        Description

 Materials  and  Equipment
 Decontamination

• MECHANICAL
 Steel Pipe and Fittings
 Cast Iron Pipe
 Plastic Pipe
 Gate Valves
 Butterfly Valves
 Ball Valves
 Pressure Regulating Valves
 Solenoid Valves
 Valve Operators
 Valves and Appurtenances
 ELECTRICAL
 Electrical - General Provisions
 Raceways and Fittings
 Unit Substations
 Tranformers
 Panel Boards
 Motor Control Center
4.4  CONTRACTING PROCEDURE

     Design and construction of  an alternate water
     supply  for a non-time critical removal action or
     an  operable  unit  remedial  action  is  usually
     performed by  contractors who can successfully
     compete  with  other firms  during  the selection
     process.  Removal  authority may  also  use
     Emergency Response  Cleanup Services  (ERGS)
     in cases  where there is not sufficient  time to
     perform site specific  contracting.  Site  specific
     contracts are encouraged whenever possible. A
     contractor  that  meets  the  technical  re
     quirements  of  the job  responsibly  and  cost-
     effectively is selected. Sepa  rate firms will be
     selected for design and construction. The design
     firm may provide construction  management
     services and  perform  the contracting functions
     required to obtain a construction contractor. It is
     essential  that  contract  documents  completely
     and accurately  define all the  work required and
     comply  with  the  Construction  Specification
     Institute  (CSI)  format   and   any   State
     requirements.

     The  bidding and contract  requirements define
     the conditions  under which the contractor must
     perform the work. A number of financial  options
     may apply to a particular contract, such as lump
     sums and unit prices.  The contract bid  may be
     based  upon one  or  a  combination of these
     options. The  purpose  of  these  contracting
     options  is to provide  a  mechanism  by which
     numerous bids  may be compared.
                                                     4-5

-------
A brief discussion of these contract bid options
is presented below.

• Lump Sum  Contract - A lump  sum contract
  requires the bidder to determine project costs
  and to undertake the services outlined in the
  project plans. This  method  requires  the
  contractor to  accurately interpret the  plans
  and specifications,  as  well  as  unusual
  conditions.  This  will  help estimate project
  cost;  one price covers all work  involved.  A
  complete design is also  required  which
  identifies project risks.

• Unit Price  - A unit  price contract requires
  bidders to estimate the materials required to
  prepare  the  site,  install  pipelines   and
  appurtenances.  The contractor  then
  determines  the  project costs on a per  unit
  basis;  this  number is  extrapolated  to  the
  estimated number of units. The sum of these
  costs is  the bid price. The contractor is  paid
  for the number of units completed during the
  work assignment. This allows for flexibility and
  insures that the contractor will be paid for all
  work actually accomplished. This contract
  balances the risk between the contractor and
  EPA.

A combination of  the  described  bid options
above can be  used.

4.4.1 LUMP SUM CONTRACT

  The lump sum contract, is most applicable for
  pricing the well-defined  elements  of  the
  work. These elements include:

  •  Mobilization  -  up front  costs such as
      insurance,  bonding   requirements,
      obtaining  project-specific  licenses  and
      permits, and  the  development  of  site-
      specific contingency and  health  and
      safety plans.

   •  Site  Preparation -  typical construction
      related  activities  such  as  roadways,
      clearing, and grading.

   •  Structures and Equipment  -  building and
      vault foundations,  superstructures  and
      equipment including pumps, generators,
      treatment units, electrical, and HVAC.

   •  Temporary  Facilities  -  support  facilities
      such as  trailers, laboratory and utility
      hook-ups.
       •  Demobilization  -  payment  for
          decommissioning  utilities, final grading
          and reporting requirements.

    4.4.2 UNIT PRICE CONTRACT

       Unit pricing provides a fixed unit price (e.g.,
       per linear foot, per cubic yard and/or tons), at
       the time of bid. This unit price is determined
       for an estimated quantity of units rather than
       a set quantity, because  specific  conditions,
       such as number of drums to be handled, may
       not be known. The unit price system provides
       contractors with a mechanism that will pay for
       all work  completed,  regardless of  original
       estimates.

       Unit pricing requires that the price quoted for
       each unit include the cost for  all required
       labor and  equipment.  Typical unit cost items
       include: excavations, piping (including trench
       excavation),   concrete,  paving,  hydrants,
       individual home treatment units, wells, drilling
       and  associated  piping,  house  connections,
       and water treatment units. These price quotes
       are generally considered  firm unless there is
       a significant change in conditions or if there is
       a major increase or decrease in the original
       estimate;  a 15  percent  margin around  the
       price quote is standard. Deviations above or
       below this margin lead to renegotiation. The
       unit price concept can accommodate changes
       and provides  a mechanism by which bids can
       be compared.

4.5  CONTRACT PROVISIONS

     The  contract must contain provisions  which
     address the  scope of the project. A "Change of
     Conditions"  refers to  those activities which  do
     not coincide with the  scope of project but are
     still billable. In   addition, the  contract  should
     comply with State and  local requirements.

     4.5.1  CHANGE ORDERS

       As discussed  previously, different types of
       contracts  are available that  divide the  risk
       between  EPA  and  the  contractor; this
       provision  modifies the terms of the contract
       and lowers   the  risk  to  the  owner and
       contractor in  order to obtain the best possible
       price. When  this occurs, the work is  more
       strictly  defined.  Therefore,  a change  of
       conditions  is defined  as   unspecified  or
       unanticipated  additional work which  is paid
       separately. This  method,  called  a change
       order, is defined below:
                                             4-6

-------
      Without invalidating  the  Agreement  and
      without  notice to any surety,  OWNER
      may, at any time from time to time, order
      additions,  deletions  or revisions in the
      Work;  these  will be authorized by  a
      Written Amendment, a Change Order, or
      a Work Directive  change. Upon receipt of
      any such document, CONTRACTOR shall
      promptly proceed with the  Work involved
      which  will be  performed  under  the
      applicable conditions of  the  Contract
      Document  (except as otherwise
      specifically provided).

  General Conditions are the  provisions
  contained in the contract that outline  change
  order  conditions   and  the  accounting
  procedures that apply.

4.5.2  SPECIAL PROVISION

  Some aspects of the project are unique to the
  site and are not necessarily unknown but fall
  under the term "considerations."  There  are
  "considerations" in  each project that  the
  owner  expects  the contractor to  consider
  when preparing the bid.  These could  include
  provisions for the following:

  •      Coordination  with  government
      agencies

  •      Storage and handling of equipment

  •      Coordination with utilities

  •      Control of erosion and runoff

  •      Services   of  manufacturers'
      representatives  for  start-up,  training,
      operation manuals, lubrication schedules
 •  Connections to existing systems

 •  Disposal of materials

 •  Providing  adequate plant (i.e.,  support
    equipment)

 •  Inclement weather.

 Experienced contractors will be familiar with
 these  and   other  standard  operating
 conditions. However,  it is in  the  Agency's
 best interest to include such items.

 In addition, there may be  conditions that are
 not known during a  particular stage of the
 work. These  conditions may be included  in
 the contract and priced on a unit basis in the
 event that they occur. Such provisions are
 referred to as  "Control of Work"  and  may
 include the following:

 •   Relocation of existing utilities

 •   Removal/replacement  of  unsuitable
    materials

 •   Removal/replacement  of rocks   and
    boulders

 •   Dewatering via well points

 •   Wood  or steel sheeting

 •   Test pits.

 If any of these  conditions were encountered,
the contractor  would be bound to  the  price
specified in the proposal.
                                          4-7

-------

-------
                                5.0  POST IMPLEMENTATION
                                           ACTIVITIES
Alternate water supplies  may be  installed  to
provide  an interim  remedy  until  the existing
water supply is cleaned up or as a final remedy
to permanently  replace  the existing  water
supply.  At  non-NPL sites  and at  most  NPL
sites, alternate water supplies will be considered
a final remedy with regard to the drinking and
household  water pathway.  Further remedial
action may be needed at the NPL site.

EPA's responsibility for the  alternate  water
supply  system  ends  upon  completion  of
construction,  when  responsibility  for  operation
and maintenance of the system is transferred to
the appropriate utility or State  agency. EPA will
seek transfer of control as soon as construction
is complete. In cases where EPA implements an
alternate water supply and  no utility exists, the
State  Superfund  contract   must  provide
assurances under Section 104 for provision of
operation  and  maintenance  services for  the
system. In cases where  EPA  or  another party
implements the alternate water supply  for
inclusion in an existing utility,  the  OSC or RPM
should work closely with OGC to develop means
for transfer of control.
                                           5-1

-------

-------
                                 6.0 REFERENCES
Comprehensive Environmental Response,
    Compensation, and Liability Act of 1980
    (CERCLA)  as amended by  Superfund
    Amendments  and Reauthorization  Act.
    1986, 42 U.S.C.  9601-9657.

Revised National Oil and Hazardous
    Substances Pollution Contingency Plan
    (NCP). 40 CFR Part 300. 1985. 47  FR
    31180.

Sisk, S.W. July 1981.  NEIC Manual for
    Ground  Water/Subsurface  Investigations
    at Hazardous  Waste Sites. EPA-330/9-
    81-002.

Touhill (Schuckrow and Assoc., Inc.). 1981.
    Concentration   Technologies  for
    Hazardous Aqueous  Waste Treatment.
    EPA-600/2-91-019.

U.S. Environmental Protection Agency. 1979.
    Safety Manual for Hazardous Waste Site
    Investigations  (draft).  Office  of
    Occupational  Investigation  Center.
    Denver.

                   December 1980.
    Interim Guidelines and Specifications  for
    Preparing  Quality Assurance  Project
    Plans.  Office  of  Research  and
    Development.  QAMS-005/80.

                 . September 1982.
   Handbook  for  Sampling and  Sample
   Preservation of Water and Wastewater.
   EPA-600/4-82-029.

  	  . October 1982. EPA
   Descriptive  Summary:  Survey  of
   Operating and Financial Characteristics of
   Community  Water Systems. Office of
   Drinking Water.

                  . 1984. Standard
   Operating  Safety  Guides.  Office  of
   Emergency  and Remedial  Response.
   Washington, D.C.

  	. February 1984. State
   Participation in the  Superfund  Remedial
   Program. Office  of Emergency  and
   Remedial Response. Washington, D.C.

          	. July 1984. Guidance
   for  Phase   T  -  Fluid   Quality
   Measurements.  UIC  Quality Assurance
 Program,  Ground  Water  Protection
 Branch, Water Supply Branch.

              . June 1985. Guidance
 Document for  Remedial Investigations
 Under CERCLA. Office of Emergency and
 Remedial  Response,  Office  of Waste
 Programs Enforcement, Office of  Solid
 Waste and  Emergency  Response.
 Washington, DC. EPA 540/G-85/002.

	- June 1985. Guidance
 Document  for Feasibility Studies  Under
 CERCLA.  Office  of  Emergency and
 Remedial Response,  Office  of Waste
 Programs Enforcement, Office of  Solid
 Waste and  Emergency  Response.
 Washington, DC. EPA 540/G-85/003.

               _. August 1985. The
 Endangerment  Assessment  Handbook.
 Office of Waste Programs Enforcement.
 Washington, D.C.  Prepared  by Life
 Systems, Inc.  under EPA Contract 68-
 01-7037.

        	. March  1986.
 Community  Relations  in  Superfund: A
 Handbook.  Office of Solid  Waste and
 Emergency Response.  Washington, D.C.
 OSWER  Directive 9230.0-3A.

               _. June 1986. Superfund
 Remedial  Design and  Remedial Action
 Guidance.  Office  of  Emergency and
 Remedial  Response. Washington,  D.C.
 OSWER  Directive 9355.0-4A.

               . October 1986.
 buperfund Public  Health  Evaluation
 Manual.  Office of  Emergency  and
 Remedial Response. Washington,  D.C.
 OSWER  Directive  9285.4-1.   EPA
 540/1-86/060.

               . March 1987. Data
Quality  Objectives  for  Remedial
Response Activities.  Volume  1   -
Development  Process.  Office  of
Emergency and Remedial Response and
Office of Waste Programs Enforcement.
Washington,  D.C. OSWER Directive
9355.0-7B. EPA  540/G-87/003.

 	       March 1987. Data
Quality  Objectives  for  Remedial
Response Activities.  Volume 2   -
                                     6-1

-------
Example Scenario. Office of  Emergency
and Remedial Response  and Office of
Waste  Programs  Enforcement.
Washington,  D.C.  OSWER  Directive
9355.0-7B.  EPA  540/G-87/004.

               .April 13, 1987.
Environmental Review Requirements  for
Removal Actions. Office of Emergency
and  Remedial  Response. Washington,
D.C. OSWER Directive 9318.0-05.

               . July 1987. Superfund
Removal  Procedures.  Office  of
Emergency and  Remedial  Response.
Washington, D.C.
 	. Draft August 1987.
Compendium of  Field  Operations
Methods. Office  of  Emergency  and
Remedial Response. Washington, D.C.
OSWER  Directive  9355.0-14.

               . Draft July September
 1987.  Engineering  Evaluation/Cost
 Analysis Guidance. Office of Emergency
 and  Remedial Response.  Washington,
 D.C.
                 Draft September 1987.
 CERCLA Compliance  with Other Laws
 Manual. Office  of  Emergency  and
 Remedial Response.  Washington,  D.C.
 OSWER Directive 9234.1-01.

	. State Participation in
 the  Superfund  Program, Appendix  W,
 Guidance for State-Lead Removals, July
 10,  1987 (OSWER  Directive  9375.1-4-
 W).
	        Technical Assistance
 Team  (TAT) Contract User's Manual,
 Draft,  August 1987.  (OSWER Directive
 9242.4-01A).  (Final   expected
 September, 1987).
	. Emergency Response
 Cleanup Services (ERGS) Users'  Manual,
 Draft,  July,  1987 (OSWER  Directive
 9242.2-1 A).  (Final expected September,
 1987).
                                    6-2

-------
                                           APPENDIX A
          LOCATIONS WHERE ALTERNATE SUPPLIES HAVE BEEN INSTALLED
Site
South Valley Site
New Brighton
Milltown
San Gabriel
Western Sand and Gravel
Charles George Landfill
TacomaWell 12A
Verona Weil Field
Charlevoix Municipal Well
Krysowaty Farm
Bridgeport
Price Landfill
Eau Claire
Caldwell Trucking
Location
Albuquerque, NM
New Brighton, MN
Milltown, MT
San Gabriel, CA
Burrillviile, Rl
Tyngsboro, MA
Tacoma, WA
Battle Creek, Ml
Charlevoix, Ml
Hillsborough, NJ
Bridgeport, NJ
Pleasantville, NJ
Eau Claire, Wl
Fairfield, NJ
Selected Remedy for Water Supply
New wells
Connection to existing system
New wells
Connection to existing system
Home treatment units, new wells
Connection to existing system
Extraction well, aeration towers
Barrier wells with air stripping, new
wells
New surface water supply
Connection to existing system
Connection to existing system
New well field
Packed tower air stripping
Ground water treatment, alternate
water supply
Combe Fill South Landfill
Chisman Creek
Heleva Landfill
Lehillier/Mankato Site

Main Street Well Field

Old Mill
Chester Township, NJ

York County, VA

North Whitehall Township, PA
Lehillier/Mankato, MN

Elkhart, IN

Rock Creek, OH
Ground water pump and treat,
alternate water supply
Ground water pump and treat, ground
water diversion, alternate water supply
Extension of existing water supply
Ground water extraction and
treatment, extension of municipal
water system
Ground water treatment with
discharge to municipal distribution
system
Ground water extraction and
treatment, alternate water supply
                                                A-1

-------

-------
                                            APPENDIX B
       AN ANALYTICAL APPROACH TO DETERMINING A CONTAMINANT TRANSPORT REGIME
    It is necessary to assess the contamination rate
at a  site  to determine  how  quickly alternate  water
supplies should  be  provided. Many factors must  be
considered during an evaluation including defining the
local  lithology and  aquifer parameters. Complicated
lithologies  which involve  multiple aquifers require
digital  modeling  to approximate contaminant
movement. In  less  complex  systems,  however,
Darcy's equation may be adapted  to  provide  an
estimate of contaminant transport.

    It is necessary to establish the radius of the water
supply well; groundwater velocity may increase  within
these areas. Therefore,  it is  important to know the
size of the water supply and the groundwater velocity
when pumping is not occurring.

    The  size of the well  may be  determined
graphically if there  are existing observation  wells
within the pumping  well. This may be accomplished
by plotting drawdown(s) vs log r, where r equals the
distance between the  pumping and observation well.
The zero drawdown  intercept represents the radius of
the pumping well during the discharge rate test. If  no
observation wells exist, the size of the well  may  be
estimated  from a series of equations  using known or
estimated  aquifer parameters.

    The average velocity of groundwater  movement
may be estimated using a form of Darcy's Law:
    where:
                         Kdhldl
                            9
           v =     average velocity (feet/day)
          K =     hydraulic conductivity (feet/day)
    dh/dl    =     hydraulic gradient (dimensionless)
          9 =     effective porosity, as a decimal
                  fraction
Parameter Determination

    Hydraulic Conductivity (K)  - Pump  test data for
the production  well may  be  available.  A hydraulic
conductivity may have been calculated for the aquifer
of concern.  This value may be substituted into  the
Darcy equation or a hydraulic conductivity may be
estimated based on  the soil  description.  Tables
comparing hydraulic conductivity and soil type can be
found  in  Freeze  and  Cherry's  (1979)   text,
Groundwater.  Aquifers  capable of  sustaining a
production well generally have K values ranging from
102 to 104 feet/day.
    Hydraulic  Gradient  (dh/dl)  -  The regional
 hydraulic gradient may be derived from potentiometric
 surface  maps developed  for the site. The hydraulic
 gradient must  be  established from  data available
 outside the area of influence of the pumping well. In
 gently sloping  areas the hydraulic gradient usually
 ranges from 1 to 10 feet per 1,000 feet.

    Porosity (9) - The porosity of an  aquifer may be
 determined from laboratory test or may be estimated
 based on the soil type. Most aquifer  materials have
 porosities of 30 to  35%. Tables comparing soil type
 and porosity can  also  be  found in  Freeze  and
 Cherry's (1979) Groundwater text.

 Example

    In  this  example, a landfill  is located approximately
 6,500 feet  upgradient from a  production well which is
 releasing contaminants. If the production well was  not
 releasing contaminants, the distance from the edge of
 the contaminant plume to the production  well would
 be used. An aquifer test was performed when the well
 was put into service. The  radius  of the well was
 approximately 1 ,500 feet. The aquifer is composed of
 sand  and  gravel  with a  hydraulic conductivity of
 feet/day and  a  porosity of 35%.  The hydraulic
 gradient  is 10  feet/1,000  feet.  Substituting  these
 values into the Darcy equation:

                         K dh/dl
                    v~~   9
                                                                          (350 (-0.01)
                   -= 10 feet/day
                   v
    Groundwater  is moving with a  velocity of  10
feet/day. To calculate the travel time  of contaminants
to intercept the radius of influence of the  production
well the  distance of travel  in feet is divided by the
velocity in feet/day. Therefore:
               5,000 (feet)

               \Qfeetlday
= 500 days
The  contaminant  may  be expected to intercept the
radius of influence of the production well in 500 days.
                                                B-1

-------
Limitations and Considerations
   This simplified model must be used with, caution.
It assumes that the aquifer  is  homogeneous  and
isotropic.  It  does not  consider  contaminant
retardation, effects of contaminant dispersion  or the
additional stresses placed on the  aquifer system. The
fraction of the  total discharge  derived  from the
direction of the contaminant plume would  effect the
water quality in the production well.    The source of
groundwater in the production well may be decreased
if surface water is close by. Complex aquifer systems
may require more sophisticated analytical or digital
modeling.  However, a simplified analytical approach
may provide the  necessary information required  to
assess  contaminant  transport in  groundwater.  The
user is strongly encouraged to seek the assistance of
a  competent  hydrogeologist  to determine  an
appropriate modeling approach.
                                                 B-2

-------
            APPENDIX C
EPA AMBIENT STANDARDS AND CRITERIA
Chemical
Acenaphthene

Acrolein
Acrylonitrile
Aldrin
Antimony
Arsenic
Asbestos

Barium
Benzene
Benzidine
Benzo(a)pyrene
Beryllium
Cadmium
Carbofuran
Carbon monoxide
Carbon tetrachloride

Chlordane
Chlorinated benzenes
Hexachlorobenzene
1,2,4,5-Tetra-
chlorobenzene
Pentachlorobenzene
Trichlorobenzene

Monochlorobenzene
Chlorinated ethanes
1 ,2-Di-chloro-
ethane
1,1,1 -Trichloroethane
1 ,1 ,2-Trichloroethane
1,1,2,2-Tetra-
chloroethane
Hexachloroethane
Monochloroethane

1,1-Dichloroethane

1,1,1,2-
Tetrachloroethane
1,1,1,2-
Tetrachloroethane
Clean Water
Safe Drinking Act, Water
Water Act, Quality
MCLs, (mg/L Criteria for
unless Human
otherwise Health
noted) Drinking
Water Only a)
20 yg/L (or-
ganoleptic)d>
540 ug/L
0 (63 ng/L)e)
0(1.2ng/L)
146 ug/L
0.05 0 (2.5 ng/L)
0 (30,000
fibers/L)
1
0 (0.67 ug/L)
0 (0.15 ng/L)

0 (3.9 ng/L)
0.01 10pg/L


0 (0.27
ug/L)f>
0 (22 ng/L)

0 (21 ng/L)
1 80 ng/L

570 ug/L
Insufficient
data
488 ug/L

0 (0.5 ug/L)f>

1 9 mg/L
0 (0.6 ug/L)
0 (0.17 ug/L)

0 (2.4 ug/L)
Insufficient
data
Insufficient
data
Insufficient
data
Insufficient
data
Health Effects Assessments b)
AlCc) Carcinogenic Potency
Intake Cone. Intake 10-6 risk
(mg/kg/day) (mg/L) (mg/kg-day)-i










2.9x1 0'4 0.01 0.045 0.77 ug/L

11.5 3.0 ng/L




0.13 0.27 ug/L

1.6 0.22 ug/L

1.7 0.21 ug/L







0.069 0.51 uQ/t-

0.54 19
0.057 0.61 U9/L
0.2 0.175 ug/L










               C-1

-------
                              APPENDIX C (Continued)
Chemical
Safe Drinking
 Water Act,
MCLs, (mg/L
   unless
  otherwise
   noted)
                                         Clean Water
                                          Act, Water
                                            Quality
                                          Criteria for
                                            Human
                                            Health
                                            Drinking
                                         Water Only a)
                                                                                     . .
                                                            Health Effects Assessments W
                         .
                     AICO
                 intake     Cone.
               (mg/kg/day)  (mg/L)
      _   .      .  „  .
      Carcmogemc Potency

    Intake            10-6 risk
(mg/kg-day)-1
     Pen tachloroe thane


Chlorinted naphthalenes


Chlorinated phenols

     3-Chlorophenol

     4-ChlorophenoI

     2,3-Dichlorophenol

     2,5-Dichtorophenol

     2,6-Dichlorophenol

     3,4-Dichlorophenol

     2,3,4.6-
     Tetrachlorophenol

     2,4,5-Trichlorophenol

     2,4,6-Trichlorophenol
     2-Methyl-4-
     chlorophenol
     3-Methyl-4-
     chlorophenol
     3-Methyl-6-
     chtorophenol
Chlorophenoxys
     2,4-Dichloro-
     phenoxyacetic acid
     2,4,5-Trichloro-
     phenoxy-propionic
     (Silvex)
Chtoroalkyl ethers
     bis-(Chloromethyl)
     ether
     bis-(2-Chloroethyl)
     ether
     bis-(2-
     Chloroisopropyl) ether

Chloroform

2-Chlorophenol


Chromium Cr+6

          Cr+3

          TOTAL
                   0.1

                   0.01
                   0.1 g)
                                Insufficient
                                data

                                Insufficient
                                data
0.1  ng/L
(organoleptic)
0.1  ng/L
(organoleptic)
o.04 ng/L
(organoleptic)
0.5 n9/L
(organoleptic)
0.2 ng/L
(organoleptic)
0.3 ng/L
(organoleptic)
1.0 ng/L
(organoleptic)
2600 ng/L
0(1.8 ng/L)
1800 na/L
(organoleptic)
3000 ng/L
(organoleptic)
20 ng/L
(organoleptic)
                                              0.05
                                                           1.8
                                                                         0.02
                                                                      1.75 ug/L
(0.0039 ng/L)

0 (30 ng/L)

34.7 ng/L


o (0.19 ng/L)

0.1 ng/L
(organoleptic)

50 ng/L
170 mg/L     1.6
                                                                         .07
                                                                      0.50 ng/L
                                                           56
                   0.05
                                            C-2

-------
APPENDIX C (Continued)
Chemical
Copper

Cyanide
DDT

Dichlorobenzenes (all
isomers)
Dichlorobenzidines
Dichloroethylenes
1 , 1 -Dichloroethylene
1 ,2-Dichloroethylene

Dichloromethane


2,4-Dichlorophenol

Dichloropropanes/
Dichloropropenes
Dichloropropanes

Dichloropropenes
1 ,2-Dichloro-
propane
Dieldrin
2,4-Dimethylphenol

2,4-Dinitrotoluene
p-Dioxane
1 ,2-Diphenylhydrazine
Endosulfan
Endrin
Ethylbenzene
Ethylene glycol
Formaldehyde
Fluoranthene
Fluoride
Haloethers

Halomethanes
Heptachlor
Hexachlorobutadiene
Hexachlorocyclohexanes
Lindane (99% gamma-
HCH)
alpha-HCH
beta-HCH
gamma-HCH
Clean Water
Safe Drinking Act, Water
Water Act, Quality
MCLs, (mg/L Criteria for
unless Human
otherwise Health
noted) Drinking
Water Only a)
1 mg/L
(organoleptic)
200 ng/L
0 (>1,2
ng/L)
470

0 (20.7 ng/L)

0 (33 ng/L)
Insufficient
data
See
Halomethane
s
0.3 n9/L
(organoleptic)


Insufficient
data
87 ng/L


0(1.1 ng/L)
400 n9/L
(organoleptic)
0(0.11 ng/L)

0 (46 ng/L)
138 ng/L
0.0002 13 ng/L
2.4 mg/L


1 88 na/L
1.4-2.4
Insufficient
data
0(0.1 9 ng/L)
0 (1 1 ng/L)
0 (0.45 n9/L)

0.004

0 (13 ng/L)
0 (23.2 ng/L)
0 (26.4 ng/L)
Health Effects Assessments b>
AICC> Carcinogenic Potency
Intake Cone. Intake 1 __6 . .
(mg/kg/day) (mg/L) (mg/kg-day)-i



8.4 4.17 ng/L




























0.097 3.4








0.078 0.45 ng/L

1.3 0.27 ng/L




        C-3

-------
APPENDIX C (Continued)


Chemical
detta-HCH

epsilon-HCH

Technical-HCH
Hexachlorocyclopentadiene
n-Hexane
Clean Water . .
Safe Drinking Act, Water Health Effects Assessments b)
Water Act, Quality
MCun%(s7/L ^uman" A.CO Carcinogenic Potency
otherwise Health intake Cone. Intake 1Q.6 rjgk
noted) Drinking (mg/kg/day) (mg/L) (mg/kgvday)-1
Water Only a)
Insufficient
data
Insufficient
data
0 (17.4 ng/L)
206 ng/L

Hydrocarbons (non-
methane)
Isophorone
Kerosene
Lead                       0.05
Mercury (inorganic)          0.002
Mercury (alkyl)
Methoxychlor               0.1
Methyl Ethyl Ketone
Naphthalene

Nickel
Nitrate (as N)               10
Nitrobenzene
Nitrogen dioxide
Nitre-phenols
    2,4-Dinitro-o-cresol
 5.3 mg/L
 50
 10 ug/L
 Insufficient
 data
 15.4 ng/L

 19.8 mg/L
0.0014      0.05
0.002       0.07
2.9x10-4     0.01
Dinitrophenol
Mononitrophenol

Trinitrophenol

Nitrosamines
n-Nitrosodimethylamine
n-Nitrosodiethylamine
n-Nitrosodi-n-butylamine
n-Nitrosodiphenylamine
n-Nitrosophyrrolidine
Ozone
Particulate Matter
Pentachlorophenol
Phenol
Phthalate esters
Dimethylphthalate
Diethylphthalate
DIbutylphthalate
Di-2-ethylhexyl-
phthalate
70 n9/L
Insufficient
data
Insufficient
data

0 (1.4 ng/L)
0 (0.8 ng/L)
0 (6.4 ng/L)
0 (7.0 ng/L)
0 (16 ng/L)


1.01 mg/L 0.03 1.05
3.5 mg/L 0.1 3.5

350 mg/L
434 mg/L
44 mg/L
21 mg/L

              C-4

-------
                                         APPENDIX C (Continued)
Clean Water
Safe Drinking Act, Water
Water Act, Quality
Health
Effects Assessments W
MCLs, (ma/L Criteria for

Chemical

unless
otherwise
noted)
Human
Health
Drinking
Water Only a)
AICO
Intake Cone.
(mg/kg/day) (mg/L)
Carcinogenic Potency
Intake
(mg/kg-day)-1
     (PCBs)

 Polynuclear aromatic
     hydrocarbons (PAHs)
 Radionuclides
     Radium-226 and 228
     Gross alpha activity
     Tritium
     Strontium-90
     Other man-made
 Selenium
 Silver
 Sulfur dioxide
 2,3,7,8-TCDD

 Tetrachloroethylene
 Thallium
 Toluene
 Toxaphene
 Trichloroethylene
 Trihalomethanes (total)')
 Vinyl chloride
 Xylenes
 Zinc
              0 (> 12.6
              ng/L)

              0 (3.1 ng/L)
                                          4.3
                                         11.5
                                                         8.14 ng/L
                                                                        3.0 ng/L
5 pCI/L
15 pCi/L
20,000 pCi/L
8 pCi/L
h
0.01
0.05
                            0.29
0.005

0.1
10 ug/L
50 ug/L

0 (0.00018
ng/L)
0(1.8ug/L)f)
17.8 ng/L
15 mg/L
0 (25.8 mg/L)
(2.8 ug/L)

(O.0l5ng/L)f)
                                          5 mg/L       0.21
                                          (organoleptic)
                                        10
                                                    1.6x10-5         2.2x1 O^ng/L

                                                       0.04            0.88
0.019
                 5.8 ng/L
                                        7.4
Footnotes:
a) These adjusted criteria, for drinking water ingestion only, were derived from published EPA Water Quality Criteria (45 FR
79318-79379, November 28, 1980) for combined fish and drinking water ingestion and for fish ingestion alone. These
adjusted  values are not official EPA Water Quality Criteria, but may be appropriate for Superfund sites with contaminated
ground water.  In the derivation of these values, intake was assumed to be 2 liters/day for drinking water and 6.5 grams/day
for fish; human  body weight was assumed to be 70 kilograms.
b) Health Effects Assessments (HEA's) - interim toxicity values developed by EPA's Environmental Criteria and
Assessment office  for substances commonly found at Superfund sites.
c) Acceptable Intake Chronic (AIC) - the highest long-term exposure level not expected to cause adverse effects.
d) Organoleptic criteria are based on taste and odor effects, not human health effects.
e) The criterion for all carcinogens is zero; the concentration given in parentheses corresponds to a carcinogenic risk of
10-6. Water Quality Criteria documents present concentrations resulting in risks from 10-5 to 10-7. To obtain
concentrations  corresponding to risks of 10-4 and 10-5, the 10-6 concentrations should be multiplied by 100 and 10,
respectively. To obtain  concentrations corresponding to risk of 10-7, 10-6 concentrations should be divided by 10.
f) These values are based on updated calculations performed  by EPA's Carcinogen Assessment Group.
g) Chloroform is one of four trihalomethanes whose sum concentration must be less than 0.1  mg/L.
h) Activity corresponding to total body or any internal organ dose of 4 mrem/year.
i) Total trihalomethanes refers to the sum concentration of chloroform, bromodichloromethane, dibromochloromethane and
bromoform.
                                                     C-5

-------

-------
                                            APPENDIX D
      INTERIM FINAL GUIDANCE ON REMOVAL ACTION LEVELS AT CONTAMINATED DRINKING
                                            WATER SITES
 REMOVAL ACTION LEVELS FOR CONTAMINATED
 DRINKING WATER SITES

 Introduction
 The purpose of this guidance is to establish  "action
 levels"  for providing  alternate water supplies under
 Superfund removal authority at contaminated drinking
 water sites. The action level is the primary criterion
 that must be met for a site to qualify for removal
 response. The action levels  established in this
 guidance  must generally be satisfied before removal
 authority can be used at either National Priorities List
 (NPL)  sites or non-NPL sites.

 Under the 1982 National Contingency Plan  (NCP),
 removal  actions  were  taken  in  response  to
 "immediate and significant"  threats to human health
 or the environment.  The removal program  used the
 10-Day Health Advisory as the principal  benchmark
 to  identify those  drinking water contamination
 incidents that posed the most acute threats to human
 health. The November 1985  NCP broadened removal
 authority by  authorizing response  in situations that
 present  a "threat"  to  human  health  or the
 environment.  Therefore, removal actions may now be
 taken in less  urgent situations than under the 1982
 NCP.

 In response to this expansion of removal authority,
 the Office of Emergency and  Remedial Response
 (OERR) is revising removal program action levels for
 contaminated  drinking water sites.  This  guidance
 expands the  previous  policy  in a  number  of ways.
 First,  the  numeric action levels  are now based on
 levels that are protective for a lifetime exposure rather
 than a 10-day exposure. Second, both carcinogenic
 and non-carcinogenic health effects are considered.
 Third,  a reduction factor  is  used  for volatiles to
 account  for  exposure  due to  inhalation.  Finally,
 additional  guidance  is  provided on  the use  of  site-
 specific factors to trigger removal actions.

 The action levels established in this guidance allow a
 site to qualify  for removal  response if either:  1) the
 numeric trigger is exceeded at the tap, or 2)  site-
 specific factors otherwise  indicate  that a significant
 health  threat exists.  The  guidance also  discusses
 information sources on health  threats from drinking
 water  contamination, factors  to consider in
determining the  extent of action,  action  levels vs.
cleanup standards,  prioritizing removal sites,  and
obtaining  exemptions  to  the statutory  limits for
alternate water supply sites.

Action Level Based on Numeric Trigger

The numeric trigger is calculated  using a model that
establishes four different action levels, depending on
whether the substance is also a  potential  human
 carcinogen and/or  volatile.  The  model is explained
 below and summarized  in Exhibit 1. Based on this
 model, Exhibit 2 lists the numeric  action  level for
 various substances that  may  be found  in  drinking
 water at  Superfund  sites.  A  site may  qualify for
 removal response  if the numeric  trigger  for the
 drinking water contaminant is exceeded at the tap of
 at least one residence ("residence" includes schools,
 businesses, etc.). (Note that the decision to initiate a
 removal action is based on other factors as well, such
 as the availability of  other response mechanisms  to
 initiate action in a timely manner.)

 The  first  step  in calculating the  numeric trigger  is
 determining whether the substance of concern is also
 a potential human  carcinogen  and/or  volatile. For
 purposes  of this  guidance,  a substance  is  a
 carcinogen if it falls  into categories A, B,  or  C  of
 EPA's carcinogen  classification  guidelines.  (A
 substance  should be  considered  a non-carcinogen if
 it is in categories D or E.) Volatile organic chemicals
 (VOCs) are generally of low molecular weight,  high
 vapor pressure, and  low  solubility. For purposes  of
 this  guidance, VOCs  include those chemicals
 identified as volatiles in the following documents: Test
 Methods for Evaluating Solid  Waste, Vol. 1A,  SW-
 846,  3rd ed., November  1986 (Chapter 2);  Contract
 Lab  Program Statement of  Work, October  1986
 (Exhibit C); Methods for the Determination  of Organic
 Compounds in Finished  Drinking Water  and  Raw
 Source Water,  September  1986  (available  from
 Regional water program  offices); and  40 CFR  Part
 264, Appendix IX (analytical methods 8010 and  8240
 designate volatiles).

 With the substance thus classified, the second step is
 to  determine  the   appropriate  action  level  in
 accordance with the categories below:

 1.   Non-volatile  non-carcinogens  --  Action
     level equals the Drinking Water Equivalent Level
     (DWEL).*

     Volatile  non-carcinogens  --  Action  level
     equals 50 percent of the DWEL.

     Non-volatile  carcinogens  - Action  level is
     determined  by   comparing the DWEL to the
     10-4  Lifetime Upperbound  Cancer Risk Level,
     and choosing the lower of the two.

     Volatile  carcinogens  --  Action  level  is
     determined  by comparing  50 percent  of  the
     DWEL to the 10-4 Lifetime  Upperbound Cancer
     Risk Level, and choosing the lower of the two.

The action  level for  methylene chloride,  for example,
is calculated as follows.  Methylene chloride  is  a
 "DWEL equals Reference Dose (RfD) times 70 kg * 2 liters/day
2.
3.
4.
                                                D-1

-------
volatile and a potential  human carcinogen- (classified
as a  "82" under  EPA guidelines).  The  DWEL for
methylene chloride  equals  1750 ppb  and the 10-4
Cancer Risk Level equals 48 ppb. The action level is
determined by comparing 50 percent of the DWEL, or
875 ppb, to the 10"4 Cancer Risk Level, or 48 ppb,
and choosing  the lower  of the two, which is 48 ppb. If
at least one residence  has  methylene chloride levels
that exceed 48 ppb at the tap, the site may qualify for
removal response.
This model will provide an action level for many of the
substances commonly encountered in  drinking water
at Superfund  sites,  including  many  solvents.
However,  OERR is still working on establishing an
appropriate action level for  certain substances in the
two situations described below. Until action levels are
developed,  most  decisions  regarding  these
substances will be  made in  OERR. The modifications
discussed below have been incorporated into Exhibits
1 and 2.
•    The calculated action  level for a substance is
     lower   than   or   equal  to  the   Maximum
     Contaminant Level (MCL) established under the
     Safe Drinking  Water Act (SDWA). For  example,
     for vinyl chloride, a  volatile  carcinogen, the
     calculated action  level under this model is 1.5
     ppb  (1.5 ppb is  the  10'4 Cancer Risk Level,
     which  is  lower  than 50%  of the  DWEL).
     However,  1.5  ppb is  lower than  the  MCL for
     vinyl chloride,  which is 2 ppb. Given the limited
     scope of the  removal program, it may  not be
     appropriate for the removal program to trigger
     removal action at  levels equal  to or below the
     MCL. Therefore,  OERR is currently examining
     whether it would  be appropriate to establish an
     alternate action level for these substances that
     is above  the  MCL.  Until  an  action  level  is
     established for these substances, removal action
     may be  initiated if contaminant levels exceed the
     10-Day Health Advisory.  However,  if
     contaminant levels are between  the calculated
     action  level  and  the  10-Day Health  Advisory,
     OERR will review individual site conditions  to
     determine if removal action should be taken.

 •   The calculated action level is based on  the
     DWEL,  but the 10-Day Health Advisory is lower
     than the DWEL.  For  most substances, the 10-
     Day Health Advisory is higher than the  DWEL. In
     some cases,  however, the 10-day  advisory is
     lower than.the DWEL. (This situation  occurs
     primarily where 10-day exposure data were not
     available, so the  10-Day Health  Advisories
     were based  on other  studies.) For example, the
      action  level  for  barium  (a non-volatile  non-
      carcinogen) is based on the DWEL of 1800 ppb,
      but  the  10-Day  Health  Advisory for  barium is
      1500 ppb. OERR is currently examining whether
      it would be appropriate to use  the lower 10-day
      advisories as the removal action  level.  Until
     OERR determines if an alternate action level  is
     appropriate for these substances, removal action
     may be initiated if contaminant levels exceed the
     DWEL.  However,  if contaminant  levels  are
     between the (lower) 10-Day Health  Advisory
     and the  DWEL, OERR will review individual site
     conditions to determine if removal action should
     be taken.

Action Level Based on Site-Specific Factors

A significant health threat may exist even though the
numeric  action  level  has  not  been  exceeded.  A
removal action may be  initiated if the health risk at a
site  has been analyzed  in  detail and the analysis
indicates that a serious health risk is  present due  to
site-specific  factors.   Examples  of  such  factors
include  evidence  that  a contaminated groundwater
plume is moving,  contaminant  levels  will likely
increase (e.g.,  increased  pumping from  an aquifer
anticipated during  summer  months),  people  have
been drinking contaminated water for a long period of
time, multiple contaminants are  likely to  result  in
synergistic effects, there  are sensitive members  in
the population at risk, etc.

With  regard  to  a  threat  based  on  future
contamination, as a general rule, removal action may
be  warranted where it can be  projected  that the
numeric action  level  will be  exceeded   within  6
months.  It is important to note  that this  6 month
period  is not  related  to  the  definition   of  time-
critical/non-time-critical  removal   actions.  For
example, where contaminant levels will likely exceed
the DWEL by a significant amount within 6  months, a
time-critical  removal  action would  be appropriate.
However, if contaminant levels  will only exceed the
DWEL by a minimal amount within 6  months, a non-
time-critical  removal  action  may  be  more
appropriate.  Future  threat  may  therefore warrant
either a  time-critical  or non-time-critical removal
action.
When conditions such  as  those described  above are
present, the  site may qualify for removal action even
though a numeric indicator has not been  exceeded.
Decisions will be made  on  a  case-by-case basis.
OERR concurrence  must be  obtained before
approving Action  Memoranda  for  contaminated
drinking water  sites  where  the  removal  action
decision is   based  solely  on site-specific factors,
even where site cost  or time  projections do  not
exceed  the statutory  limits on removal actions.
However, if an emergency exists  based on  site-
specific  factors, action  may be initiated immediately
and OERR should be contacted as soon as possible.

Information Sources

DWELS, as well  as RfDs and  other relevant
standards and advisories, are available to the Regions
through the Integrated  Risk  Information  System
 (IRIS).  IRIS can be  accessed  on-line through  E-
                                                 D-2

-------
 mail; type in "IRIS" at the prompt rather than "mail."
 The EPA Office  of  Drinking Water  has  also
 established a Safe Drinking Water Hotline, which can
 provide  information  about relevant standards  and
 criteria,  and treatment techniques  for contaminated
 drinking water.  The  Hotline  telephone  number  is
 800-426-4791 (in  the Washington  D.C.  area,  382-
 5533).

 Additional  advice   and  information  on  health
 assessments at drinking  water contamination  sites
 may be  obtained  from  the  Agency  for Toxic
 Substances and Disease Registry  (ATSDR) and the
 Superfund Public Health Evaluation  Manual Directive
 #9285.4-01). ATSDR may be  particularly helpful  in
 providing advice on  threats  posed  by site-specific
 factors.

 OERR should be contacted if a substance of concern
 does not have a DWEL, RfD, and/or cancer risk level.

 Determining the Extent of Action

 Once it  has been determined that a site qualifies for
 removal  response based  on  a numeric trigger  or
 site-specific factors, the Region must determine how
 many residences (including businesses, schools,  etc.)
 will receive alternate water supplies.  First,  the area of
 impact  should  be  estimated (both extent  and
 magnitude of the threat) by considering factors such
 as  the  hydrogeology  of the site, plume  movement,
 and the  likelihood  of  contaminant levels  increasing.
 For sites where removal action  is warranted because
 the  numeric  trigger has been  exceeded at certain
 residences, the  area  of impact may  be  defined  to
 include neighboring residences which are  at risk, but
 do not exceed the numeric trigger.

 After the area of impact fs  defined, the  number  of
 residences to  be provided  with  alternate  water
 supplies  must be determined by considering cost vs.
 benefits  received,  the statutory limits on  removal
 actions,  and  the  availability  of  other  response
 mechanisms. For example, response to widespread
 low-level contamination  may  be too  extensive  for
 removal  action,  and  therefore, may be  addressed
 more appropriately by the  remedial  program.  In
 another case, a contaminated aquifer may affect a
 public water  supply  system and private  wells, but
 Superfund resources may only be needed  to address
the private wells.

 Determining the appropriate extent of action therefore
involves  analysis of  both  the area of impact  and
programmatic factors.

Action Levels vs, Cleanup Standards

The numeric action levels established in this guidance
are not  intended to be  used  as cleanup  standards.
The MCL,  if available,  will  generally  be  the
appropriate cleanup standard. (For guidance on the
use of MCLs  and MCLGs as cleanup standards,  see
"Interim  Guidance on Compliance with Applicable or
 Relevant and  Appropriate  Requirements,"  July  9,
 1987, OSWER Directive 9234.0-05. Final  guidance
 will be  issued in the  CERCLA  Compliance  with
 ARARs  Manual.) This means that for any residence
 provided with an alternate water supply, the goal will
 generally be to meet MCLs. For example,  if  carbon
 filter units will  be provided to treat drinking water
 contaminated with trichloroethylene  (TCE), treated
 water should achieve 5 ppb TCE, the MCL.

 Prioritizing Removal Sites.

 Sites may qualify for removal action under either the
 numeric indicator  or site-specific factor approaches.
 For the  purpose of prioritizing those site that qualify
 for removal  action, response  should be  initiated as
 soon as possible if contaminant levels exceed the
 10-Day  Health Advisory  or  site-specific  factors
 ptherwise indicate that an emergency exists.

 Exemption to the Statutory Limits

 To obtain  an exemption to  the $2 million/12  month
 limits on removal actions  based  on  a continuing
 emergency, it will generally not be adequate to show
 that contaminant levels exceed the numeric  action
 level by  some minimal amount. An exemption may be
 justified  if  contaminant levels  exceed  the  10-Day
 Health Advisory, significantly  exceed  the  numeric
 action level,  or an emergency exists based on site-
 specific  factors. A finding  that contaminant  levels
 exceed the numeric action level by a minimal amount
 may be  appropriate, however, in  "non-emergency"
 situations where an exemption  is based on  the new
 consistency waiver.

 Summary of Policy

 A  contaminated drinking water site  may qualify for
 removal  response if:  1) the  numeric  action  level
 (based  on  the DWEL and/or  the  10-4 Lifetime
 Upperbound  Cancer  Risk  Level)  is  exceeded, or
 2)  site-specific  factors  otherwise indicate  the
 presence of  a serious  health  threat.  In prioritizing
those sites that qualify for response under this model,
 Regions should  give  priority to sites  where
contaminant levels exceed  the  10-Day Health
Advisory  or site-specific factors otherwise  indicate
that an emergency exists.
                                                D-3

-------
Exhibit 1: Summary of Action Level Decision Model

Do contaminant levels exceed the NUMERIC action level?

Is the substance a volatile and/or potential human carcinogen?

•  Non-volatile non-carcinogens - Action level  equals  the  DWEL.

•  Volatile non-carinogens - Action level equals 50% of the DWEL.

•  Non-volatile  carcinogens  -  Action level  is  determined   by
   comparing the DWEL  to the 10-4  Lifetime  Upperbound  Cancer
   Risk Level, and choosing  the lower of the two.

•  Volatile carcinogens  -  Action  level is  determined  by comparing
   50%  of the DWEL to  the  10"4 Lifetime Upperbound Cancer  Risk
   Level, and choosing the lower of the two.

Do either of the two  modifications to  the numeric  action level
apply?
Is the numeric action level lower than or equal  to the MCL, if available?
If yes:
•   If contaminant levels are between the numeric action level and the
    10-day Health Advisory, contact  OERR to  determine  appropriate
    action.
•   If contaminant levels exceed the 10-Day Health  Advisory, action be
    taken if the site otherwise qualifies for removal response.

If the action level is based on the DWEL, is the 10-day Health Advisory
lower than the DWEL? If yes:
•   If contaminant levels  are  between the (lower) 10-day  Health
    Advisory  and the DWEL, contact  OERR to determine appropriate
    action.
•  If contaminant levels exceed the DWEL, action  may be taken if the
    otherwise qualifies for removal response

If contaminant levels do not exceed the numeric trigger,  can the
site  quality  for removal response based  on  SITE-SPECIFIC
FACTORS?
A site can qualify for removal response if the health risk at a site has
been analyzed in detail and  the analysis indicates that a  serious health
 risk is present due to site-specific factors.
 •  ATSDR may be particularly helpful  in providing advice on health due
    to site-specific factors.
 •  OERR concurrence must be  obtained  before approving Action
    Memoranda based on site-specific factors, even where the site will
    not exceed the statutory limits on removal actions.
                                D-4

-------
Exhibit 2
Removal Numeric Action
Chemical
Alachlor
Barium
Benzene
Cadmium
Carbofuran
Carbon tetrachloride
Chlordane
Chlorobenzene
Chromium (total)
Cyanide
o-Dichlorobenzene
p-Dichlorobenzene
1 ,2-Dichloroethane
1,1-Dichloroethylene
Cis-1,2-
Dichloroethylene
Trans- 1,2-
Dichloroethylene
Dichloromethane/
Methylene chloride
Endrin
Ethylbenzene
Heptachlor

Lindane
Mercury (inorganic)
Methoxychlor
Methyl ethyl ketone
(MEK)
Nickel
Pentachlorophenol (PGP)
Styrene
Tetrachloroethylene
(PCE)
Toluene
Toxaphene
1 ,1 ,1 -Trichloroethane
Trichloroethylene
Vinyl chloride
Xylenes (total)
Levels for Contaminated Drinking Water Sites (pg/L)
EPA
Volatile Carcinogen 10-Day
(Y/N) Groupa MCL HA DWELb
N
N
Y
N
N
Y
N
Y
N
N
Y
Y
Y
Y
Y

Y
Y
N
Y
N

N
Ne
N
Y

N
Y
Y
Y

Y
N
Y
Y
Y
Y
B2
D
A
D
E
B2
B2
D
D
D
D
C
B2
C
D

D
B2
E
D

B2
C
D
D
D

D
D
C
B2/C

D
B2
D
B2
A
D
None
1000
5
10
None
5
None
None
50
None
None
75
5
7
None

None
None
0.2
None
None

4
2
100
None

None
None
None
None

None
5
200
5
2
None
100
1500C
235
43C
50C
160
63
4300C
1400
22QC
8930C
1070QC
74QC
1000C
1000C

1430C
1500
5
3200C
10

1200
1.6<=
2000
7500C

1000
300C
200QC
2000

3460C
40
35000C
None
2600
7800C
350
1800
NA
17
175
24
1.6
1505
168
770
3115
3500
None
350
350

350
1750
1.6
3395
17

10
5.5
1750
864

350
1050
7000
500

12100
None
1000
257
None
2157
10-4 Removal
Cancer Risk Action
Level Level
44
NA
120
NA
NA
27
2.7
NA
NA
NA
NA
175
38
None
NA

NA
480
NA
NA
7.6

None
NA
NA
NA

NA
NA
None
66

NA
3.1
NA
280
1.5
NA
44
1800d
120
17
175d
12
1.6
753
168
770d
1558
175
38
175
175

175
480
1.6
1698d
7.6

10
5.5f
1750
432

350
525d
3500d
66

6050d
409
500
128
1300h
1078
                                          (Continued)
D-5

-------
Exhibit 2 (Continued)
        Chemical
Volatile
 (Y/N)
   EPA
Carcinogen
  Groupa
                                                  MCL
                                                            10-Day
                                                               HA
DWEL&
   10-4
Cancer Risk
   Level
Removal
 Action
 Level
a  Carcinogen group designation is from EPA carcinogen classification guidelines for effects from ingestion.
b  DWEL equals RfD times 70kg divided by 21/day. (Note that the DWEL in health advisory documents produced by
   EPA's Office of Drinking Water may be slightly different due to rounding.)
c  Because no suitable studies of appropriate duration were available, these 10-day Health Advisories were based
   on Health Advisories of greater or lesser duration, e.g., 1 -Day, Longer-term, and lifetime Health Advisories.
d  Removal action level is an interim value. OERR is examining whether it would be appropriate to use the lower
   10-Day Health Advisory (50% for volatiles) as the action. Until that time, if contaminant levels exceed the action
   level shown in the table, removal action may be taken. If contaminant levels exceed the 10-day advisory (50%
   for volatiles), but not the DWEL (50% for volatiles), consult OERR.
e. Not soluble in water.
f.  Removal action may be initiated if mercury levels exceed the DWEL of 5.5 ug/L. If mercury levels exceed the
   10-day advisory of 1.6 ug/L, but not 5.5 ug/L, consult OERR.
Q  Removal action may be initiated immediately if toxaphene levels exceed the 10-Day Health Advisory of 40 ug/L-
   If toxaphene levels exceed the 10'4 Cancer Risk Level of 3.1  ug/L, but not 40 ug/L, consult OERR.
h  Removal action may be initiated immediately if vinyl chloride levels exceed  1300 ug/L, which is 50% of the 10-
   Day Health Advisory. If vinyl chloride levels exceed the 10-4 Cancer Risk Level of 1.5 ug/L, but not 1300 ug/L,
   consult OERR.
NA = Not appropriate.
                                                   D-6

-------
               APPENDIX E
TREATABILITY CLASSIFICATION OF PRIORITY
               POLLUTANTS
NAME
Acenaphthene
Acenaphthlyene
Acetone
Acrolein
Acrylonitrile
Aldrin
Aluminum
Aniline
Anthracene
Antimony
Arsenic
Asbestos
Barium
Beryllium
Benzene
Benzidine
Benzo(a)anthracene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Benzole Acid
Benzo(ghi)perylene
Benzo(e)pyrene
Benzyl Alcohol
BHC-Alpha
BHC-Beta
BHC-Gamma
BHC-Delta
Bis (2-chloroethoxy)methane
Bis(2-chloroethyl)ether
Bis(chloromethyl)ether
Acenaphthene
Acenaphthlyene
Acetone
Acrolein
Acrylonitrile
Aldrin
Aluminum
Aniline
Anthracene
Antimony
Arsenic
Asbestos
Barium
Beryllium
Benzene
Benzidine
Benzo(a)anthracene
Benzo(b)fluoranthene
TREATABILITY CLASS
Aromatics
Aromatics
Ketones
Miscellaneous
Miscellaneous
Pesticides
Metals
Aromatics
Aromatics
Metals
Metals
Miscellaneous
Metals
Metals
Aromatics
Substitute Aromatics
Aromatics
Aromatics
Aromatics
Aromatics
Aromatics
Aromatics
Aromatics
Pesticides
Pesticides
Pesticides
Pesticides
Halocarbon
Chlorinated Ethers
Chlorinated Ethers
Aromatics
Aromatics
Ketones
Miscellaneous
Miscellaneous
Pesticides
Metals
Aromatics
Aromatics
Metals
Metals
Miscellaneous
Metals
Metals
Aromatics
Substitute Aromatics
Aromatics
Aromatics
SYNONYMS
1 ,2-Dihydroacenaphthylene


2 Propenal
2 Propenenitrile




Stibium

Amianthus


Benzol










Lindane




1 ,2-Dihydroacenaphthylene


2 Propenal
2 Propenenitrile




Stibium

Amianthus


Benzol



                        SOURCE: adapted, from Shuckrow et al. 1980
                  E-1

-------
            NAME
                                APPENDIX E (Continued)

                                     TREATABILITY CLASS
                                          SYNONYMS
Benzo{k)fluoranthene
Benzoic Acid
Benzo(ghi)perylene
Benzo(e)pyrene
Benzyl Alcohol
BHC-Alpha
BHC-Beta
BHC-Gamma
BHC-Delta
Bis (2-chIoroethoxy)methane
Bis(2-chloroethyl)ether
Bis(chloromethyl)ether
Bis(2-chloroisopropyl)ether
Bis{2-ethylhexyl)phthalate
Bromoform
4-Bromophenyl Phenyl Ether
2-Butanone
Butyl Benzyl Phthalate
Cadmium
Calcium
Carbon disulfide
Carbon Tetrachloride
Chlordane
4-Chloroaniline
Chlorobenzene
Chlorodibromomethane
Chloroe thane
2-Chloroethyl Vinyl Ether
Chloroform1
2-Chlorophenol
4-Chlorophenyl Phenyl Ether
2-Chloronaphthalene
Chromium
Chrysene
Cobalt
Copper
Cyanide
4,4'-DDD
4,4'-DDE
4,4'-DDT
Dibenzo(a,h)anthracene
Dibenzofuran
1,3-dichlorobenzene
1,2-Dichlorobenzene
1,4-DichIorobenzene
3,3'-Dichlorobenzidine
Dichlorbromomethane,
Dichlorodifluromethane
Aromatics
Aromatics
Aromatics
Aromatics
Aromatics
Pesticides
Pesticides
Pesticides
Pesticides
Halocarbon
Chlorinated Ethers
Chlorinated Ethers
Chlorinated Ethers
Phthalate Esters
Halocarbon
Chlorinated Ethers
Ketones
Phthalate Esters
Metals
Metals
Miscellaneous
Halocarbon
Pesticides
Chlorated Aromatics
Chlorinated Aromatics
Chlorinated Alkanes
Chlorinated Alkanes
Chlorinated Ethers
Halocarbon1
Phenols
Chlorinated Ethers
Chlorinated Aromatics
Metals
Aromatics
Metals
Metals
Miscellaneous
Pesticides
Pesticides
Pesticides
Chlorinated Aromatics

Chlorinated Aromatics
Chlorinated Aromatics
Chlorinated Aromatics
Substitute Aromatics
Halocarbon
Halocarbon
Lindane
Tribromomethane

Methyl Ethyl Ketone




Tetrachloromethane


Monochlorobenzene
(2-Chloroethoxy)Ethane
Trichloromethane1
1,2-Benzphenanthrene
                                                       SOURCE: adapted, from Shuckrow et al. 1980
1Trihalomethanes can be found in a water supply either due to direct contamination, or formation during
treatment or distribution. The treatment approach for this latter situation strives for prevention of formation,
rather than removal via treatment.
                                              E-2

-------
                                 APPENDIX E (Continued)
             NAME
                                     TREATABILITY CLASS
                                           SYNONYMS
 1,1-Dichloroethane
 1,2-Dichloroethane
 1,1 -Dichloroethylene
 2,4-Dichloro Phenol
 1,2-Dichloropropane
 1,3-Dichloropropylene
 Dieldrin
 Diethylphthalate
 2,4-Dimethylphenol
 Dimethyl Phthalate
 Di-N-Butyl Phthalate
 4,6-Dinitro-O-Cresol
 4,6-Dinitro-2-methylphenol
 2,4-Dinitrophenol
 2,4-Dinitrotoluene
 2,6-Dinitrotoluene
 Di-N-Octyl Phthalate
 1,2-Diphenyl Hydrazine
 A-Endosulfan-Alpha
 B-Endosulfan-Beta
 Endosulfan Sulfate
 Endrin
 Endrin Ketone
 Endrin Aldehyde
 Ethylbenzene
 Fluoranthene
 Fluorene
 Heptachlor
 Heptachlor Epoxide
 Hexachlorobenzene
 Hexachlorobutadiene
 Hexachlorocyclopentadiene
 Hexachloroethane
 2-Hexanone
 Indeno (1,2,3-c,d)Pyrene
 Iron
 Isophorone
 Lead
 Magnesium
 Manganese
 Mercury
 Methoxychlor
Methyl Bromide

 Methyl Chloride
Methylene Chloride
2-Methylnaphthalene
2-Methylphenol
4-Methylphenol
4-Methyl-2-pentanone
Nickel
 Halocarbon
 Halocarbon
 Halocarbon
 Phenolts
 Halocarbon
 Halocarbon
 Pesticides
 Phthalate Esters
 Phenols
 Phthalate Esters
 Phthalate Esters
 Phenols
 Phenols
 Phenols
 Substituted Aromatics
 Substituted Aromatics
 Phthalate Esters
 Substitute Aromatics
 Pesticide
 Pesticide
 Pesticide
 Pesticide
 Pesiticide
 Pesticide
 Aromatics
 Aromatics
 Aromatics
 Pesticides
 Pesticides
 Chlorinated Aromatics
 Halocarbon
 Halocarbon
 Halocarbon
 Ketones
 Aromatics
 Metals
 Miscellaneous
 Metals
 Metals
 Metals
 Metals
 Pesticides
 Hafocarbon

 Halocarbon
 Halocarbon
Aromatics
Phenols
Phenols
Ketones
Metals
 1,2-Benzenedicarboxylic Acid

 2-Methyl-4, 6-Dinitrophenol

 Aldifen
Perchlorobenzene
Hydrargyrum
Bromomethane; Monobromo-
methane; Embafume
Chloromethane
Dichloromethane
(Methyl Isobutyl Ketone)
                                                      SOURCE: adapted, from Shuckrow et al. 1980
                                             E-3

-------
          NAME
                            APPENDIX E (Continued)

                                 TREATABILITY CLASS
                                     SYNONYMS
2-Nitroaniline
3-Nitroaniline
4-Nitroaniline
Nitrobenzene
2-Nitrophenol
4-Nitrophenol
N-Nitrosodimethylamine
N-Nitrosodiphenylamine
N-Nitrosodipropylamine
Para-Chloro-Meta-Cresol
PCB-1016
PCB-1221
PCB-1232
PCB-1242
PCB-1248
PCB-1254
PCB-1260
Pentachlorophenol

Phenan thane
Phenol
Potassium
Pyrene
Selenium
Silver
Sodium
Styrene
2,3,7,8-Tetrachlorodibenzo-p-
Dioxin
1,1 ,2,2-Tetrachloroethane
Tetrachloroethylene
Thallium
Tin
Toluene
Toxaphene
1 ,2-Trans-DichIoroethylene
1 ,2,4-Trichtofobenzene
1,1,1-Trichloroethane
1,1,2-Trichloroethane
Trichloroethylene

Trichlorofluoromethane
Aromatic
Aromatic
Aromatic
Substituted Aromatics
Phenols
Phenols
Miscellaneous
Miscellaneous
Miscellaneous
Phenols
Polychlorinated Biphenyls






Phenols

Aromatics
Phenols
Metals
Aromatics
Metals
Metals
Metals
Aromatic


Halocarbon
Halocarbon
Metals
Metals
Aromatics
Pesticides
Halocarbon
Chlorinated Aromatics
Halocarbon
Halocarbon
Halocarbon

Halocarbon



Nitrobenzol













Penta; PCP; Penchloro;
Santophen

Carbolic Acid; Phenic Acid

Benzo(def)Phenanthrene







Perchlorothylene; Ethylene
Tetrachloride


Methylbenzene




Vinyl Trichloride
Trichloroethene; Ethinyl
Trichloride
Fluorotrichloromethane
2,4,5-Trichlorophenol
2,4,6-Trichlorophenol
Vanadium
Vinyl Acetate
Vinyl Chloride
Xylenes
Zinc
Chlorinated Aromatics
Phenols
Metals

Halocarbons
Aromatics
Metals
Dowicide 25; Omal
Chloroethylene
                                                 SOURCE: adapted, from Shuckrow et al. 1980
                                         E-4

-------
 ACI

 ARAR
 CERCLA

 CLP
 CRDL
 CRP
 DWAL
 DWEL
 EE/CA
 EIS
 EPA
 ERGS
 ERA
 FS
 GAG
 HA
 HEA
 ISO
 MCL
 MCLG
 NCP
 NEPA
 NPL
 OERR
 OSC
 PAS
 RAMP
 Rl
 RPM
 ROD
 SARA
 SDWA
 USGS
 USPHS
WQC
                           APPENDIX F
                   GLOSSARY OF ACRONYMS
 Acceptable Chronic Intake, developed by EPA's Environmental  Criteria and Assessment
 office.
 Applicable or Relevant and Appropriate Requirements
 Comprehensive Environmental  Response, Compensation and Liability Act of 1980.Also
 known as Superfund.
 Contract Laboratory Program
 Contract Required Detection Limit
 Community Relations Plan
 Drinking Water Action Levels
 Drinking Water Equivalent Levels
 Engineering Evaluation and Cost Analysis
 Environmental Impact Statement
 Environmental Protection Agency
 Emergency Response Cleanup Services
 Expedited Response Action
 Feasibility Study
 Granular Activated Carbon
 Health Advisory
 Health Effects Assessment
 Insurance Services Office
 Maximum Contaminant Level, established under the Safe Drinking Water Act.
 Maximum Contaminant Level Goal
 National Oil and Hazardous Substance Contingency Plan
 National Environmental Policy Act
 National Priorities List
 Office of Emergency and Remedial Response, U.S. EPA
 On-Scene Coordinator
 Policy Analysis Staff
 Remedial Action Management Plan
 Remedial Investigation
 Remedial Project Manager
 Record of Decision
 Superfund Amendments Reauthorization Act
 Safe Drinking  Water Act
 U.S. Geological Survey
 U.S. Public Health Service
Water Quality  Criteria
                                                F-1
                                                               U. S. GOVERNMENT PRINTING OFFICE: 1988/548-158/87038

-------

-------