United States
                       Environmental Protection
                       Agency
                        Office of
                        Research and Development
                        Cincinnati OH 45268
EPA/54Q/R-96/507a
April 1998
        r/EPA
Site  Technology Capsule
 Rochem  Separation
 Systems,  Inc.,  Disc Tube™
 Module  Technology
Abstract
  The Rochem Separation Systems, Inc. (Rochem) Disc
Tube™ Module (DIM) technology is an innovative mem-
brane separation process. It is designed to treat liquid
waste that is higher in dissolved solids content, turbidity,
and contaminant levels than waste treated by conven-
tional membrane separation processes. According to the
technology developer, Rochem, the innovative DTM de-
sign reduces the  potential  for membrane fouling and
scaling, which allows it to be the primary treatment for
liquid wastes such as landfill leachate.
  The DTM technology was evaluated by Science Appli-
cations  International Corporation (SAIC) under the
Superfund Innovative Technology Evaluation (SITE) Pro-
gram at the Central Landfill  Superfund Site in Johnston,
Rhode Island.  The DTM technology treated leachate
contaminated with chlorobenzene  and 1,2-dichloroben-
zene at average concentrations of 21 and 16 milligrams
per liter (mg/L), respectively,  and lower levels of 1,4-
dichlorobenzene at 0.7 mg/L; toluene at 1.8 mg/L; xy-
lenes at 1.3 mg/L; and ethylbenzene 0.79 mg/L. Total
organic carbon (TOG) was present in the leachate at an
average concentration of 460 mg/L, and  total dissolved
solids (TDS) were present at an average concentration
of 4,900  mg/L.  Metals were also  present at average
concentrations such as 1.4  mg/L for barium, 130 mg/L
for calcium, 48 mg/L for iron, and 21 mg/L for manga-
nese. The purpose of this SITE Demonstration was to
assess the DTM technology's effectiveness in removing
organic  and inorganic  contaminants from the landfill
leachate and in resisting scaling and fouling of the mem-
branes.
                        Overall,  the DTM  technology was very effective in
                      removing contaminants from the landfill leachate. Mean
                      contaminant rejections were greater than 96.7% for TOG
                      and 99.4% for TDS, both exceeding the developer's
                      claims of 92% for TOG and 99% for TDS. The overall
                      mean rejection for total metals was greater than 99.2%,
                      exceeding the developer's claim of 99%. The overall
                      mean rejection for target VOCs was greater than 92.3%
                      which exceeded the developer's claim of 90% for VOCs.
                      In addition, the DTM process achieved a  treated water
                      recovery rate  of approximately  75%. The developer's
                      claim was 75%. DTM operational parameters, such as
                      permeate (treated water) flow rate and module pressure
                      drop, and  system  permeate quality,  indicate that there
                      was a decrease in  technology performance over the
                      course of the Demonstration.
                        The  Rochem DTM technology was evaluated based
                      on seven criteria used  for  decision-making in  the
                      Superfund Feasibility Study (FS) process. Results of the
                      evaluation are summarized in Table 1.

                      Introduction
                        This report provides information on the Rochem DTM
                      technology, an innovative membrane separation process
                      for removal of contaminants from liquid hazardous waste
                      streams. The Rochem DTM technology was evaluated
                      under the U.S. Environmental Protection Agency's (EPA)
                      SITE Program during August and September 1994 at the
                      Central Landfill Superfund Site in Johnston, Rhode Is-
                      land. Contamination  in an area of the Central Landfill
                      designated as the "hot spot" resulted  from the disposal
                      of chemical wastes in the mid-1970s. Leachate from this
                                           INNOVATIVE
                                TECHNOLOGY EVALUATION

-------
Table 1.
                  Criteria Evaluation for the Rochem Disc Tube™ Module Technology
Overall
Protection of
Human Health &
the Environment
Provides both
short- and long-
term protection
by reducing
exposure to
organic and
inorganic
contaminants in
landfill leachate
(or liquid waste).

Prevents harmful
effects of liquid
waste migration
to public water
supplies.

Reduces the
volume of
contaminated
material.
Concentrated
contaminants can
be incinerated or
treated by other
methods.
Technology is
able to treat a
variety of
contaminants.


























Compliance with
Federal ARARs
Requires compliance
with RCRA treatment,
storage, and land
disposal regulations
(for a hazardous
waste).

On-site treatment may
require compliance
with location-specific
ARARs.

Permeate discharge to
POTW or surface
bodies requires
compliance with the
Clean Water Act
regulations. Without
additional treatment,
the final permeate
produced during the
Demonstration met
discharge permit
requirements for
heavy metals. The
discharge requirement
for total toxic organics
(TTO) was met after
activated carbon
polishing. Limits for
biochemical oxygen
demand, chemical
oxygen demand, and
total suspended solids
were not applicable to
Central Landfill' s
Industrial Waste
Discharge Permit.

If volatile compounds
are present in the
liquid waste, emission
controls may be
needed to ensure
compliance with air
quality standards,
depending on local
ARARs.

Requires compliance
with OSHA regulations
to protect the health
and safety of workers
at hazardous waste
sites.




Long-Term
Effectiveness
Permanently
reduces the
volume of
contaminated
leachate or other
liquid waste.

Involves a
demonstrated
technique for
removal of
organic and
inorganic
contaminants.

Permeate may
require treatment
prior to disposal,
depending on
site-specific
discharge
limitations.

Removed
(concentrated)
contaminants
may require
treatment by
other methods
such as
incineration or
solidification/
stabilization prior
to disposal.
Recirculation by
surface
application to the
landfill may be
appropriate for
municipal landfill
leachate.

Membrane
cleaning is
required to
maintain system
performance and
to extend
membrane life.
Membranes are
cleaned at the
discretion of the
operator, typically
based on a
change in
module pressure,
flow rate, or
temperature
readings.
Short-Term
Effectiveness
Depending on
the application,
additional
modules may be
added to the
DTM™ system to
reduce
remediation time.

Treatment may
cause noise and
minor air
emissions,
posing short-term
risks to workers
and possibly to
the nearby
community.
Process noise
levels are not
high. Air
emissions can be
mitigated.

Some personal
protective
equipment (PPE)
may be required
for workers
during system
operation.


























Reduction of
Toxicity, Mobility,
or Volume
through
Treatment
Significantly
reduces toxicity
of treated water
and volume of
contaminated
water through
treatment.

Permeate water
quality is
dependent on
waste
characteristics.
During the
Demonstration,
contaminant
levels were
reduced 90% or
greater on
average (99.4%
for TDS, 99.2%
for target metals,
96.7% for TOC,
and 92.3% for
VOCs).

Waste volume
reduction is
dependent on
waste
characteristics
and the required
system water
recovery rate.
Waste volume
reduction for the
Demonstration
was
approximately
75%.


















Implementability
Utility requirements
are minimal and
include water and
electricity.

Equipment is skid-
mounted or
containerized and
easily transportable
by a tractor trailer.
Support equipment
includes a heavy
duty forklift or crane
for loading/
unloading and
arranging the units,
and tanks for
process stream
storage.
Treatability testing
with the selected
waste is
recommended prior
to field installation.

If the necessary
facilities and
utilities are
available, the
system can be set
up and operational
in three to five
days. Initial testing
(shakedown) of the
equipment prior to
going on-line
normally takes two
to five days. After
treatment, the
entire system can
be demobilized
within two to three
days.
The concentrations
and types of
scaling ions can
limit the treated
water recovery rate
or cause
membrane fouling
and scaling,
thereby limiting the
use of the DTM
technology.



Cost
The estimated costs
for treating leachate
at 3 and 21 gpm at
a fixed facility and
with a treated water
recovery rate of
75% are $0.1 61
permeate-gal and
$0.06/permeate-gal,
respectively. These
costs do not include
a waste disposal
fee for the
concentrate since
this cost is site- and
concentrate-
specific. Costs are
based on data
gathered from the
Demonstration and
on treating a
leachate with
characteristics
similar to the
Central Landfill
leachate. Estimated
costs are highly
leachate-specific.
Treatment costs are
higher for liquid
wastes that have a
high potential for
membrane scaling
and thus require
increased use of
chemical cleaners
and pH adjustment
chemicals.

Operating the
technology at a
higher on-line factor
and treated water
recovery rate (both
dependent on
system design and
leachate
characteristics) will
result in a lower
overall cost.









-------
hot spot was pumped from an existing well for treatment
by a Rochem Model 9122 DIM system  operating at a
feed  flow rate  of about 4  gallons  per minute. Approxi-
mately 33,000  gallons of leachate were  treated during
the Demonstration  at the  Central Landfill. The leachate
contained VOCs, metals, and high dissolved solids.
  Information in  this Capsule  details  the  specific site
characteristics and  results of the SITE technology Dem-
onstration at the  Central Landfill. This Capsule presents
the following information:
     Technology Description
     Technology Applicability
     Technology Limitations
     Process Residuals
     Site Requirements
     Performance  Data
     Economic Analysis
     Technology Status
     SITE  Program Description
     Sources of Further Information

Technology Description
  The DTM technology can utilize reverse osmosis (RO),
ultrafiltration (UF), or microfiltration (MF) membrane ma-
terials, depending  on the  application.  The  membranes
are generally more  permeable to water than to contami-
nants or impurities. RO  membranes are most commonly
used with this technology. They can reject dissolved and
suspended  solids,  dissolved salts  and ions, and  many
low and most high  molecular weight organic compounds
(1). In  RO,  water in the feed is forced through  a  mem-
brane by applied pressure which exceeds  the  osmotic
pressure of the feed. This water, called permeate,  has a
lower concentration of contaminants. The impurities are
selectively  rejected by  the membranes  and are thus
concentrated in the concentrate left behind. The percent-
age of water that passes through  the  membranes is a
function of operating pressure, membrane type, and con-
centration and  chemical characteristics of the contami-
nants.  The  DTM technology  utilized thin-film composite
(TFC) RO membranes during the Demonstration  at the
Central Landfill.
  The patented membrane module features larger feed
flow channels and  a higher feed flow velocity than con-
ventional membrane separation systems. According to
the technology developer, these characteristics allow the
DTM greater tolerance for dissolved solids and turbidity,
and a greater resistance to membrane fouling and scal-
ing. Suspended  particulat.es are readily flushed  away
from the membrane during  operation. The high flow
velocity, short feed water path across each membrane,
and the circuitous  flow  path create turbulent mixing to
reduce boundary layer effects and minimize membrane
fouling and  scaling. In addition, the developer claims that
the design of the DTM allows easy cleaning  and mainte-
nance  of the membranes—the open channels facilitate
rinsing and cleansing of  particulate  matter, and  mem-
branes can  be  removed  as needed from  modules for
replacement.
  Figure 1 details a cutaway diagram of the  Disc Tube™
Module. Membrane material for the DTM is formed into a
cushion surrounding a porous spacer material. The  mem-
  Feed water
                          Permeate  Concentrate
                          (product)   (reject)
                                      Pressure vessel
 End flange     Tension rod
                              Membrane    Hydraulic
                       /      cushion      djsc
Figure 1.    Cutaway diagram of the Disc Tube™ module.

brane cushions are alternately  stacked  with  hydraulic
discs on a tension rod. The hydraulic discs support the
membranes and provide the  flow channels for the feed
liquid to pass over the membranes. After passing through
the membrane material, permeate flows through collec-
tion channels out  of the module to a product recovery
tank. A stack of  cushions and discs is housed  in a
pressure vessel. Flanges seal the ends of the module in
the pressure vessel and provide the feed water input and
the product (permeate) and  reject (concentrate) output
connections. The  number of discs per module, number
of modules, and the  membrane materials can  be cus-
tom-designed to suit the application.
  Modules are  typically combined in a treatment unit.
The DTM system design includes built-in multimedia and
cartridge  filters  to remove  suspended particulates from
the input feed  and to  protect pumps and membranes
from physical damage. The multimedia filters are cleaned
by backwashing; cartridge  filters are manually replaced
as needed. To monitor the operation of the modules, the
system is equipped with pressure and flow meters.
  A three-stage DTM  process was used  to treat the
leachate at the  Central Landfill site.  Each stage was a
separate  DTM unit interconnected with piping and tank-
age. Two  DTM  stages were  used in series to  produce
the final  permeate. The third DTM stage was a high-
pressure  unit (HPU) which further treated  the  concen-
trate from  the  first-stage to increase  system  water
recovery. A schematic of the multistage DTM  process
utilized during the Demonstration is presented in Figure
2. The system operated up to eight hours a day for 19
days at a  feed  flow rate of 3 to 4.5 gallons per minute
(gpm).

-------
                                     Acid
                                     feed
                                                         First stage
                                                         DIM unit
         Leachate
         tank
                     Feed tank
                              Media
                              filter
Hi-pres.  Booster
pump   pump

    A	6^
                                     ft
                                   Second
                                   stage
                                   DIM unit
                                                                                    '-fi*
                                      Cartridge
                                      filter
                                           Acid
                                           feed
  tfl
                        First
                        stage
                        permeate
                        tank
First
stage
cone.
tank
                    Feed stream
                    Concentrate stream
                    Permeate stream
                                                  Hi-pres.
                                                  DIM unit
                      	I
                                                                                         Second
                                                                                         stage
                                                                                         (final)
                                                                                         permeate
                                                                                         tank
                                            To municipal
                                            sewer
Figure 2.    Schematic of the DIM process.
  Two 5,000-gallon tanks stored  leachate  that  was
pumped continuously from well MW91ML7. This leachate
was then pumped to a 100-gallon feed tank for the  first-
stage unit. After  filtration,  contaminated  leachate  was
pumped into the first-stage unit at pressures which ranged
from 600 to 1,000 pounds per square inch gauge (psig).
The first-stage unit  had eight  modules  which utilized
standard TFC membranes. The permeate  produced  from
this unit was directed to a  holding tank designated for
first-stage permeate, and was then fed at 700 to 1,000
psig to the second-stage unit for further treatment.
  The  second-stage unit,  which  had  2  modules  that
utilized standard TFC membranes, was not brought on-
line until enough first-stage  permeate accumulated in its
feed holding tank. The second-stage permeate was the
system's final permeate,  while the second-stage concen-
trate was recycled into the first-stage feed line. Rochem
had originally planned to use a different DTM system for
the Demonstration in which the first-stage unit and the
second-stage unit were  combined in a single prefabri-
cated container and the HPU housed  in  a separate
container. With this type of system, the second-stage
unit is not operated in a semi-batch mode, but is continu-
ously fed permeate from the first-stage unit.
  The concentrate from the  first-stage unit was routed to
a 300-gallon holding tank. This concentrate was fed into
the HPU at 1 to 3.5 gpm and 900 to  1,800 psig. Use of
the HPU was initiated later than the first two stages  after
           accumulation of first-stage concentrate; the  HPU oper-
           ated in a batch mode. The HPU had two stainless steel
           modules which utilized TFC membranes specially modi-
           fied for high pressure.  The purpose of the HPU  was to
           reduce the volume of the first-stage concentrate, thereby
           reducing the final waste volume and increasing the sys-
           tem water recovery rate. High pressure was needed to
           overcome the osmotic pressure of the first-stage  con-
           centrate. HPU permeate was recycled into the first-stage
           permeate  tank (feed  for the second-stage). The HPU
           produced  the system's final concentrate.  Initially,  the
           HPU was  operated in a recycle mode to  allow the HPU
           concentrate to  reach an optimal concentration and  fur-
           ther  increase the system's water recovery rate.  This
           mode of operation  was discontinued after the first  two
           days of the test. It was determined by  Rochem that the
           desired system water recovery rate could be achieved
           without the concentrate recycle mode; recycling the con-
           centrate increased the chance of HPU membrane fouling
           and scaling.
             Permeate  was used  to  rinse and clean  the  DTMs.
           Rinsing was  performed on the HPU and second-stage
           unit  in  between  batch  treatment  cycles each  day to
           displace any leachate from membrane surfaces. In addi-
           tion, all stages were rinsed at the end of the day to flush
           the system prior to shutdown overnight. Cleaning was
           accomplished by adding cleaning agents—either alkaline
           for fouling, acidic for membrane scale, or detergent for

-------
both—to the rinse tank for each unit. The cleaning solu-
tion was then cycled through the unit. Membranes were
cleaned at the discretion of the  Rochem system operator
based  on  an increase in module pressure readings or
changes in operating temperature or flow rate.
  Hydrochloric (HCI) acid was added to the first-stage
feed and the HPU feed at dosing rates of 1.6 to 2.8 liters
per hour (L/hr)  and 0.53 to  1.6  L/hr, respectively. The
addition of HCI,  which facilitated pH adjustment, was not
started until the third day of leachate treatment. Rochem's
target system feed pH for the Demonstration was  be-
tween 5 to 6.
  As a precautionary measure, the final permeate was
run through activated carbon  canisters to ensure compli-
ance with discharge requirements.  After treatment  by
activated  carbon, it was stored and batch  discharged to
the sanitary sewer.

Technology Applicability
  Rochem  claims that the  DTM technology  can treat
liquid waste streams containing volatile and semivolatile
organics, metals and other inorganic ions or compounds,
and radioactive  wastes. The  DTM technology  has been
used to treat landfill leachate, water soluble oil coolants,
oil/water mixtures,  and solvent/water mixtures (2). The
DTM technology was used in the United States to treat
lagoon water contaminated  by  petrochemical wastes
(volatile organics, phenols, heavy metals, and polychlori-
nated biphenyls).  In addition, the technology is treating
municipal landfill leachate in the U.S. and municipal and
hazardous landfill leachate in Europe. (See "Technology
Status" for further details).
  The DTM technology is capable of treating liquid waste
with wider ranges and higher  levels of contaminants than
conventional  membrane separation  technologies using
RO membranes. A  high-pressure unit can be used to
increase the treated water recovery rate for liquid wastes
that have a higher level of TDS or scaling ions. Results
from the Demonstration show that the DTM technology
achieved  excellent removals  of metals, TDS, and TOG.
VOC removals were also very good (approximately 90%
or greater). The VOC removals are notable because
membrane  separation  technologies typically do  not  ef-
fectively separate lower molecular weight organic com-
pounds, particularly VOCs; these  compounds tend to
pass through the membranes (3).
  The suitability of the DTM process is dependent on the
characteristics of the feed liquid. Rochem claims that for
many liquid wastes, the DTM system's hydraulic design
allows  it  to operate with minimal  or no  pretreatment.
However,  chemical  or physical  pretreatment may  be
needed to reduce the potential for membrane scaling or
fouling for liquid  wastes such as  the Demonstration
leachate. This may add to the cost of using the technol-
ogy. Pretreatment may include equalization, aeration to
remove carbon dioxide generated from acid addition  (for
pH adjustment), and other processes (4). The user of the
technology will be responsible for arranging for treatment
and disposal of  the final concentrate and disposal of the
final permeate.
  The Rochem DTM technology is transportable on trac-
tor trailers  and  can be installed  by Rochem personnel
within three to five days, if power and auxiliary tankage
and piping are available. Multiple DTM systems can be
used to increase treatment capacity.

Technology Limitations
  The composition of the feed waste may limit the appli-
cability of the DTM technology. In RO, inorganic  salt
percent rejections are usually high (ninety to ninety-nine
percent).  Some constituents (barium, calcium,  fluoride,
iron, silica, strontium, sulfate, etc.) may cause scaling on
membranes, depending on the water recovery rate. Higher
water recovery  rates increase the  potential for scaling
and fouling because of potential for precipitation of spar-
ingly soluble  salts such as  calcium carbonate  (CaCO3)
and calcium sulfate (CaSO4). Deposits of metal oxides
(formed from metals such as iron  or manganese),  col-
loids,  organic compounds,  or oil and grease can also
contribute to scaling and fouling as will biological activity.
This,  in turn, may  limit membrane life  and treatment
effectiveness (5).
  The  maximum treated water recovery  rate is depen-
dent on the TDS concentration  in the liquid waste.  For
treatment of landfill leachate with high scaling potential,
the use of acid  dosing for pH  control is necessary to
achieve a high water recovery rate. A water recovery
rate of 75 to 80% is achievable for leachate similar in
composition  to the  Central Landfill leachate while  still
maintaining acceptable membrane life and permeate  wa-
ter quality.  Higher recovery  rates may be  possible  but
may require the  use of additional  equipment and sup-
plies.  Any increased operating costs  may  be offset by
cost savings  for  treatment and  disposal of a smaller
volume of concentrate.

Process Residuals
  The DTM process separates contaminants from liquid
waste generating two process streams: permeate (treated
water)  and concentrate (waste). If appropriate discharge
limitations are met and the proper permits are obtained,
the permeate can be discharged to  the  local publicly
owned treatment works (POTW), into surface waters, or
reinjected  through underground  injection wells.  When
discharge requirements are  not met, polishing treatment
is  required. Depending on its composition and classifica-
tion, the  concentrate may be  a hazardous waste  and
may require further treatment and disposal.
  The approximate volume ratio of permeate to concen-
trate (including  used cleaning solutions and  unused
samples) produced  during the Demonstration was  3:1.
Permeate  generated was  discharged to  a municipal
sewer. Although not classified as  a RCRA waste,  the
concentrate required off-site treatment prior to land  dis-
posal  due to  its  elevated levels of hazardous constitu-
ents.  Concentrating the liquid waste volume  reduced
transportation and treatment costs. Options  for concen-
trate treatment or disposal  include  solidification/ stabili-
zation, evaporation, and  recirculation into the landfill by
surface application in  the  case of  municipal landfill
leachate (4).
  During treatment of waste containing VOCs, there may
be minor releases of volatile contaminants to the atmo-
sphere from  intermediate process  holding  tanks. Such

-------
losses were measured during the technology  Demon-
stration at  the  Central Landfill. These losses did not
significantly influence  system performance  results, but
may require mitigation to  reduce air emissions  in some
cases. Emissions from auxiliary storage tanks may also
need to be  controlled.

Site Requirements
  Each DIM unit or stage is comprised of a control unit
and  membrane  modules. The control  unit  consists of
electronic controls, pumps, filters, pressure gauges, and
valves. During the Demonstration  the  control units and
corresponding  modules were separate and mounted on
skids with a maximum weight of one ton each. The skid-
mounted units were transported by tractor trailer  and
could be moved with a heavy-duty forklift. In most cases,
the units are built into  cargo containers for easier trans-
portation and installation and to prevent leaks and spills
during operation.  For loading  and  unloading, container-
ized units require a crane capable of lifting 15,000 pounds.
The containerized units may be placed on wheels  for
indoor mobility. Additional equipment necessary for sys-
tem operation includes auxiliary tanks for process stream
storage and interconnecting piping.
  Utilities requirements are  limited to electricity  and wa-
ter. The DTM system used for the Demonstration (Model
9122) required a three-phase, 440/480-volt, 60-hertz elec-
trical circuit to power the pumps and control equipment.
The 9122 DTM system requires a maximum power sup-
ply of 21  kilowatts (kW).  A direct on-site  hookup is
preferred, but if this is  not available, a generator may be
used (4). The use of a generator is not cost effective for
long-term applications. DTM systems larger than the one
utilized  for the Demonstration  have  higher power  re-
quirements than  Model 9122.  For example, Model 9142
requires a maximum power supply of 50 kW. Additional
power is needed for on-site office trailers (if present),
any ancillary pumps, and outdoor lighting. Water is  re-
quired to perform system leak-testing, and to shakedown
and calibrate the equipment.  Water is  also  needed  for
cleanup and decontamination.
  Support facilities include shelter to protect equipment
and personnel from weather extremes and level equip-
ment staging areas. At locations with colder climates, an
indoor installation with heating would be preferred. Dur-
ing the Demonstration, the treatment units were arranged
under a tent. A more permanent shelter including office
space  is desirable for  long-term treatment projects. The
technology  requires a flat site in order to control liquid
levels and provide optimum operation. A 500-square-foot
equipment staging area with additional storage space for
auxiliary system tanks was adequate for the  three-stage
Demonstration system.
  Storage of raw feed and final concentrate  is required,
and storage of final permeate may be required. Storage
tank sizing and  design are dependent on site-specific
applications. The user of the technology may be respon-
sible for providing storage  tanks.  In  addition,  an area
constructed to contain potential spills is required to hold
containers  for  process stream storage, chemicals,  and
process wastes.
Performance Data
  The DTM  technology was evaluated  on its effective-
ness in  removing organic and  inorganic contaminants
from leachate and the extent, if any, of membrane foul-
ing and  scaling observed when treating landfill leachate
containing hazardous constituents.
  Prior to the  SITE Demonstration, bench-scale treat-
ability tests were conducted on hazardous leachate from
a landfill in the western U.S. This leachate was contami-
nated with many of the same constituents as the Central
Landfill  leachate, including VOCs, heavy metals,  and
high dissolved  solids. The purpose  of the  treatability
tests was to determine  how effectively the technology
could treat hazardous leachate. Data were also obtained
so Rochem  could establish the type of DTM system to
be  used,  the  order of system units,  and the type of
membranes  to be used for a demonstration at that site.
The treatability tests aided Rochem in developing claims
for the quality and quantity of water that the DTM system
could produce when treating hazardous  landfill leachate.
  Treatability testing was not conducted by Rochem on
the Central Landfill leachate. Shakedown testing with the
Central Landfill leachate was performed by Rochem for
about one day prior to the Demonstration.
  Based  on  prior treatability testing and other Rochem
applications, the following critical objectives were devel-
oped for the Demonstration:
     determine  if  the  technology could  meet  the
     developer's claims for contaminant  rejections of
     greater than 90% for VOCs, greater than 92% for
     TOG, and greater than 99% for TDS and metals;
     determine  if the technology could  achieve  and
      maintain a system treated  water recovery  rate of
     75% or greater; and
     evaluate the DTM technology's resistance to mem-
      brane  fouling and scaling.
  Other noncritical objectives for this Demonstration were
to
     develop  capital and operating costs  for the DTM
     system;
     determine  whether the  DTM system could meet
     applicable  or  relevant regulatory criteria for  dis-
     charge of the permeate;
     evaluate the ease of use,  reliability, and mainte-
      nance requirements of the DTM system;
     calculate  a material balance for the overall pro-
     cess for water and target contaminants; and
     estimate the potential fugitive emissions from the
     system during use.
  During the Demonstration, samples were collected from
sample taps on 11 process streams throughout the sys-
tem. The process streams considered critical in evaluat-
ing the technology were the raw feed, the final permeate,
and the  final concentrate. Samples for off-site laboratory
analysis were collected at a frequency of once per day
(three times  per day on two selected days). Samples for
field analyses  were collected  once or twice per day,
depending on the analysis. Off-site laboratory analyses
included TDS,  total solids (TS), TOG, VOCs, total met-
als, ammonia,  and anions. Field parameters that were

-------
measured included turbidity, pH, temperature, conductiv-
ity,  silica, alkalinity,  chemical  oxygen demand  (COD),
calcium,  and hardness. Table 2 presents the average
concentrations of contaminants measured in the system
feed, permeate, and concentrate process streams during
the Demonstration.
  Percent rejections of contaminants were calculated
from daily raw feed and final permeate  concentrations.
Table 3 summarizes the calculated mean percent rejec-
tions achieved for the target contaminants considered
critical  for this Demonstration.  Mean contaminant rejec-
tions were greater than 96.7% for TOG and 99.4% for
TDS,  both exceeding the developer's claim.  All target
metals except potassium showed mean rejections greater
than the developer's claim of 99%. The overall mean
rejection for total metals was greater than  99.2%.  The
mean rejection for potassium  was greater than  98.7%
and the 95% confidence interval around this mean  was
98.0 to 99.4%. The calculated mean percent  rejections
of 1,2-dichlorobenzene; ethylbenzene; toluene; and xy-
lenes were greater than the developer's claim of 90% for
VOCs. The  overall  mean  rejection for total VOCs  was
greater than 92.3%.  However, the calculated  mean re-
jection  for chlorobenzene was  86.8% with a confidence

Table 2. Average Concentration for the System Feed, Permeate and
        Concentrate Streams
                       Average Concentration (Mg/L)
Table 3. Target Contaminants Average Percent Rejection
System
Contaminant Feed
Target VOCs
1,2-Dichlorobenzene 16
1,4-Dichlorobenzene 0.70
Chlorobenzene 21
Ethylbenzene 0.79
Toluene 1.8
Xylenes 1 .3
Target Metals
Barium 1.4
Calcium 130
Iron 48
Magnesium 250
Manganese 21
Potassium 150
Sodium 710
Strontium 0.89
Anions
Chloride 2,500
Fluoride <2.7
Nitrate <12
Sulfate 81
Other Parameters
Total Alkalinity (as CaCO3)1 ,600
Ammonia 650
Silica 15
Total Dissolved Solids 4,900
Total Solids 5,800
Total Organic Carbon 460
* = Permeate concentration is based
Final
Permeate
.76
<0.081
2.7
<0.031
0.083
<0.039
<0.014
<1.1
<0.38
<1.6
<0.14
<1.8
<5.7
<0.0068

<13.
<0.10
<0.40
<1.8

<1.0*
5.3
<0.63*
<32
<100
<15
on 6 sampling days.
Final
Concentrate
23
<0.80
36
1.1
3.4
<1.7
4.3
410
140
850
70
550
2,500
2.9

1 1 ,000
11
<26.
300

4,100
2,300
86
17,000
21 ,000
1,600

Developer's
Claims
Percent
Rejection
Contaminant (%)
Target VOCs
1 ,2-Dichlorobenzene
1,4-Dichlorobenzene
Chlorobenzene
Ethylbenzene
Toluene
Xylenes
Target Metals
Barium
Calcium
Iron
Magnesium
Manganese
Potassium
Sodium
Strontium
Total Dissolved Solids
Total Organic Carbon
>90
>90
>90
>90
>90
>90
>99
>99
>99
>99
>99
>99
>99
>99
>99
>92
Average
Percent
Rejection
Achieved*
(%)
94.9
>87.6
86.8
>95.6
93.8
>95.0
>99.0
>99.2
>99.2
>99.3
>99.4
>98.7
>99.2
>99.2
>99.4
>96.7
95%
Confidence
Interval
(%)
92.7-97.1
83.5-91 .7
83.1-90.5
94.1-97.1
90.5-97.1
92.3-97.7
98.3-99.7
98.5-99.9
98.6-99.8
98.6-99.9
98.7-100.0
98.0-99.4
98.5-99.9
98.5-99.9
98.9-99.9
95.6-97.8
  Greater than symbol indicates that at least one measured value was
  below the method detection limit.
                                                       interval of 83.1 to 90.5%; the calculated  mean rejection
                                                       for 1,4-dichlorobenzene was  87.6% with a 95% confi-
                                                       dence interval of 83.5 to 91.7%. These rejections were
                                                       less  than  the specified criteria of 90%, but the 90%
                                                       rejection criteria fell within the 95% confidence intervals
                                                       for both compounds. These results indicate that the DTM
                                                       system was very effective  in removing all  classes of
                                                       contaminants in the Central  Landfill leachate.
                                                         Vent emissions were measured during the Demonstra-
                                                       tion from an intermediate concentrate holding tank in the
                                                       system. VOC losses were calculated from  these mea-
                                                       surements. Comparing these results on a mass basis to
                                                       the system VOC mass shows the vent losses to be no
                                                       more than  0.5% of the total mass of any  given com-
                                                       pound. Therefore, these losses did not significantly af-
                                                       fect  the  calculated  percent rejections  of  VOC
                                                       contaminants.
                                                         Flow rates, totalized  flows, pressures, and electricity
                                                       usage were recorded on field log sheets at hourly inter-
                                                       vals  during system operation. Totalized flows were used
                                                       in the calculation  of system  water recovery rates. Sys-
                                                       tem  water  recovery is defined  as the  volume  of final
                                                       permeate divided  by the volume of feed, times  100%.
                                                       Figure 3 illustrates the daily percent system water recov-
                                                       eries. Breaks in the  data represent periods when the
                                                       system was off-line due to  weather,  maintenance, or
                                                       temporary  mechanical  problems. The average  system
                                                       water recovery  rate for the  Demonstration  was  73.3%
                                                       with  a 95% confidence interval of 70.7% to  75.9%. The
                                                       developer's claim of 75% water  recovery falls within this
                                                       confidence interval. The calculated daily  water recovery
                                                       rates ranged from 66.4 to 84.4%. The system recovery

-------
yu
an _

S '°
o
o
£ fin -
Ji
13
3 c,,-
„ bu
c
s
*
'c5
"a on -
OJ 30
CD
2
> 9n-
£ 20
1 n, -
n -









• I



























•B Average daily percent recovery
— Average system % recovery = 73.3


I _












































































ma



















•































              8/11 8/12 8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/21 8/22 8/23 8/24 8/25 8/26 8/27 8/28 8/29 8/30 8/31 9/1  9/2

                                                    Date (1994)


Figure 3.    Rochem DIM system daily percent water recovery.
rate was equal to or greater than the claim of 75% on
eight days of treatment. These daily recovery rates were
reduced by the use  of first-stage and final permeate for
rinsing of the second-stage and  the HPU modules be-
tween batch treatment  cycles each day to displace re-
sidual  leachate from  the  membrane  surfaces. An
allowance was not  made for  permeate  lost  to these
rinses because they were part of normal operation for
the system  used  for the Demonstration.  According to
Rochem, for other DIM system designs that are better
integrated and typically  require  less module rinsing  than
the system demonstrated at the Central Landfill, achiev-
able  recovery  rates  may be higher (75 to 80%) when
treating a similar liquid waste.
  System operating data was evaluated to determine the
performance of membranes which received  the bulk of
waste loading during the Demonstration. Figures 4 and 5
depict pressure and  flow rate trends for the first-stage
and the  high-pressure  units. The flow rate data were
standardized for pressure, temperature, and  waste  con-
centration using  ASTM Standard D4516-85,  Standard
Practice for Standardizing RO  Performance Data.  The
standardized  data are  also  presented on the graphs.
Breaks in the data represent periods when the system
was off-line due to weather, maintenance, or temporary
mechanical problems. Standardized flow rates were  simi-
lar to the actual flow rates.
  In general, the data presented in these figures show
an increase in operating pressures  and  a decrease in
flow  rates  over time,  indicating a  slight decrease in
performance for the units receiving the  bulk  of waste
loading during treatment. A  sharp decrease in perfor-
mance is seen during  the first two days of treatment
(pressure increasing and flow rate decreasing). After this
point, the system was shut down for thorough membrane
cleaning. This performance  decrease was  probably a
result of the lack of pH adjustment to control precipitation
and membrane scaling. HCI acid addition for pH adjust-
ment was initiated after this time  and seemed to help
maintain  membrane  performance; membrane cleaning
was not required for the next ten days of treatment. The
feed  pressure in the first-stage unit began  increasing on
about August 22, 1994. The system recovery rate setting
was increased on August 24 by Rochem, and this was
followed by additional pressure  increases as well as a
decrease in flow rate until the end of the  leachate test.
During  this period,  routine membrane cleaning was con-
ducted  for short periods of  time  almost  every  day  of
operation. Apparently, the first-stage  membranes were
beginning to foul or scale, and  increasing the recovery
rate compounded this problem.  As a result,  the system
experienced  a reduction  in flow rate and reduction  in
permeate quality for some contaminants. Figure 6 illus-
trates a trend in the reduction of permeate quality (most
notable near the  end of the Demonstration) for TDS,
TOG, and total VOCs. Membrane cleanings were helpful
in maintaining system performance, but the leachate did
appear to have an impact on  membrane performance
over the course of the Demonstration. However, due to
the  short  duration of system  shakedown and  of the
Demonstration, it was not possible for Rochem to fully
optimize  the  membrane  cleaning procedures  for this
leachate. The developer felt that better performance may
have been achieved if a more thorough process shake-
down had been performed and  more sophisticated pre-
treatment for pH control had been used. Baseline testing
also  indicated a decrease in  membrane performance
over the course of the Demonstration. Baseline testing

-------
           1000


            900 -
                4


            800 -



            700 -
            600 j
         §  500 -

         8
         o>
        ol  400 -
            300 -
            200 -
            100 -
                          System
                          off-line
                                     -»- Average feed pressure
                                     -O- Average permeate flow rate
                                     -4- Average standardized permeate flow rate
                 4.5



              -   4



              -   3.5



              -   3



              - -  2.5  |
                     S
                     o>

              +  2   |
                     o
                                                                                                             O	<
System
off-line
                              -\	h
                                           -\	1	1	1	1	1	1	h
                                                                              -1	1	1	1	1	1-
                                                                                                        -1	1-
                                                                                                                  -- 1.5
                                                                                                                  -- 1
                                                                                                                  -- 0.5
               8/11 8/12  8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/218/22 8/23 8/24 8/25 8/26 8/27 8/28 8/29 8/30 8/31 9/1  9/2

                                                             Date (1994)



Figure 4.    First-stage unit: feed  pressure and permeate flow rate vs. time.
           1800
           1 600 - -
           1400 --
           1200 --
                          System
                          off-line
                                     -»- Average feed pressure
                                     -O- Average permeate flow rate
                                     -^- Average standardized permeate flow rate
                         -1	h
                                               -1	1-
 System
 off-line
                                                                                                                  -1.2
                                                                                                                  -- 1
                                                                                                                  -0.4
                                                                                                                    0.2
               8/11
                    8/12 8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/218/22 8/23 8/24 8/25 8/26 8/27 8/28 8/29 8/30 8/31 9/1  9/2

                                                             Date (1994)
Figure 5.    High pressure unit: feed pressure and permeate flow rate vs. time.

-------
          160
            0
            8/11 8/12 8/13 8/14 8/15 8/16 8/178/18 8/19 8/20 8/218/22 8/23 8/24 8/25 8/26 8/278/28 8/298/30 8/31 9/1

                                                Date (1994)
Figure 6.    Final permeate stream: IDS, TOC, and total VOCs vs. time.
involves determining  the  change in  flux (flow rate per
unit membrane area) as a result of liquid waste (leachate)
treatment. Baseline testing results can be found in the
Innovative Technology Evaluation Report (ITER).
  System  mass balance calculations gave good results
for metals, TOC, TDS, and TS. Totalized flow measure-
ments were used for daily  mass balance calculations.
Adjustments were made to these measurements to ac-
count for  rinse cycles  that  used permeate  to  perform
rinses. This permeate was lost as concentrate. The over-
all mass balance for metals was within 15 percent  of
closure, which is considered good for this type of pro-
cess. The closures for TOC, TDS, and TS were within
plus or minus  5  percent. These  results indicate that
analytical data and system flow measurements  were  of
good quality and that these contaminants were accounted
for.  Mass balances for VOCs showed a typical loss of 40
to 60%  of these compounds  through  the system, and
final concentrate levels for VOCs were lower than ex-
pected based on feed levels and the system water re-
covery rate. These differences are probably due to VOC
losses during system sampling and possibly due to VOCs
adhering to  membrane surfaces. The feed and espe-
cially the final concentrate process streams were foam-
ing   during sampling  due  to acid addition and
pressurization, making  sampling for  VOCs difficult and
probably resulting in VOC  losses to  the atmosphere.
Organic fouling  of the membranes was occurring during
leachate treatment, as evidenced by the amount of mem-
brane cleaning required using an alkaline cleaner. VOCs
may have  been responsible  for some of the  organic
fouling, possibly in combination with iron or silica, how-
ever, these foulants would have probably been removed
from the  membranes during cleaning cycles and would
therefore not be accounted for in the mass balances.
  During  the  Demonstration,  final  permeate was col-
lected in  holding tanks and then  discharged to the sani-
tary sewer under a modification to the Central Landfill's
Wastewater Discharge Permit. The  measured quality of
the permeate from the DTM technology complied with
discharge permit requirements for heavy metals without
further treatment. Polishing treatment with activated car-
bon was utilized to ensure compliance with the total toxic
organics  (TTO) discharge limit of 2.13 mg/L. The TTO
level of the final  permeate from the DTM  technology
ranged from about  1 mg/L, less than the discharge limit,
to 10 mg/L, with an average of  about 3.4 mg/L for the
Demonstration. The calculated TTO for the final perme-
ate is based  on VOC analytical results; other organic
compounds were not detected in the full TTO analysis
performed on  the  final discharge samples.  Measured
COD, BOD, and TSS values were  generally very low
mg/L or non-detectable. There were no discharge permit
limits for these parameters.
  The primary maintenance activity for this technology is
membrane cleaning. The  technology  is  designed  to fa-
cilitate membrane cleaning to maintain performance and
extend membrane  life. During the  Demonstration, for
each unit, short cleaning cycles (approximately 30 to 60
minutes in duration) were used  to maintain  daily treat-
ment effectiveness. More thorough  cleaning was  occa-
sionally required  to  remove  accumulated  membrane
                                                   10

-------
deposits. This extensive cleaning was partially effective
in restoring membrane flow rates (flux). During the Dem-
onstration, membrane cleaning was performed more fre-
quently than typical due to inadequate pH control.
  The reliability of the technology during the Demonstra-
tion was good. After some initial adjustments, the system
ran steadily with short  breaks  for routing  membrane
cleaning. The feed pump  for the first-stage unit was
defective and had to be replaced towards the end of the
Demonstration. As a replacement pump was  not on site,
the system was  down for one day while a  pump was
delivered. Typically, spare pumps and components would
be on-site, and replacement could be completed in a few
hours (4).

Economic Analysis
  Estimates on  capital and  operating costs  have been
determined for treating leachate similar to the  SITE Dem-
onstration leachate  (hazardous  landfill leachate). Two
cost estimate cases are presented  for  DTM systems
operating 24 hours per day  (hpd) at fixed facilities. The
first case is for a 9122 DTM system treating three gal-
lons of leachate per minute. This is slightly smaller than
the 9122 Demonstration system. The second case is for
a 9142 DTM system treating 21  gallons of leachate per
minute. For both  cases the DTM system includes a high
pressure unit (HPU).
  The estimated costs for treating leachate similar to the
Demonstration leachate are $0.16/permeate-gallon  ($0.047
permeate-liter)  for the  9122 system  case  and  $0.067
permeate-gallon ($0.01/permeate-liter) for the 9142 sys-
tem  case.  These  costs are for operating  at  a fixed
facility. They include all factors except for  permitting and
waste disposal costs for the  concentrate  stream. Costs
are highly site- and leachate-specific.  If only  annualized
equipment costs and consumables costs were consid-
ered, then the cost would decrease to $0.07/permeate-
gallon and $0.03/permeate-gallon for the 9122 and 9142
systems, respectively.
  The cost for treatment using the Rochem DTM system
is based  on, but not limited to, the following information:
     Treating  leachate  similar to the leachate  at the
     Demonstration. Leachate  characteristics  directly
     influence the treatment cost. Different leachates
     may require a  different: cleaning  frequency, on-
     line efficiency factor, pH adjustment requirement,
     membrane life, and cartridge filter life.
     An on-line  efficiency  factor of  90%.  This factor
     accounts for downtime due to scheduled and un-
     scheduled cleanings and maintenance. It is based
     on  observations recorded during the SITE Demon-
     stration and other data from Rochem. The approxi-
     mate  on-line  efficiency factor  during  the SITE
     Demonstration was 84%.
     A permeate recovery factor of 75%. This is based
     on  data collected during the SITE Demonstration.
     Cleaning frequencies  and cleaning solutions  re-
     quirements  based  on observations made  during
     the  SITE  Demonstration  and  other  data from
     Rochem.
     The same  pH adjustment  requirements that were
     observed during the SITE Demonstration.
     The following  membrane lifetimes: five years for
     the second stage permeate-membrane, three years
     for the first stage leachate-membrane,  and two
     years  for the  concentrate-membrane. These life-
     times are based on information from other Rochem
     applications.
     System  operating  times  of 24  hpd,  7  days per
     week,  and  50 weeks  per year.
     Labor requirements of one operator on-site for four
     hpd. Because these  cost estimates are based on
     the Demonstration leachate characteristics, they
     are higher than costs estimated for treating a non-
     hazardous landfill  leachate. This  is because the
     Demonstration  leachate  required more  frequent
     cleanings and a larger volume of pH adjustment
     chemicals  than  other types  of leachates would
     require. A detailed explanation of these cost esti-
     mates can be found in the ITER.

Technology Status
  Rochem Separations Systems, Inc. based in Torrance,
California is licensed to  supply the DTM technology  in
the United States. They are a subsidiary of the  Swiss-
based  Rochem Group which  developed and  patented
the DTM technology. The  DTM units and systems are
designed and  fabricated in Germany. They have been
manufactured since 1988.  The high-pressure unit such
as used during the  Demonstration at the Central Landfill
is  a new design  implemented to increase treated water
recovery rates where high  recovery rates are desirable
or for applications with high TDS.
  Rochem has over 800 installations of the DTM tech-
nology worldwide, mostly in Europe. During the last six
years,  the technology has been  used  to treat  landfill
leachate at more than 50 landfills in Europe,  according
to  Rochem. Rochem has also had projects in the United
States. At the French Limited Superfund site near Crosby,
Texas, the technology treated lagoon  water  contami-
nated by petrochemical wastes (volatile organics, phe-
nols,  heavy metals, and  PCBs).  Two  units with  30
modules and one with  10  modules were used to treat
three million gallons of lagoon  water per month  at this
site. According to Rochem, nearly 40 million gallons  of
water were  processed at a 30 to 50 percent  recovery
rate. TOG levels from 1,700 to 1,800 mg/L in the  lagoon
water were  reduced to  20 to  25 mg/L  in the treated
water, less than the EPA discharge  requirements (6). At
the Superior Landfill in Savannah, Georgia, the technol-
ogy is treating  municipal landfill leachate at a flow rate of
6,000 to 7,000 gallons per day. According to Rochem,
over 200,000 gallons of leachate have been treated  to
date at a 73 to 74% recovery rate (4).
  Rochem has four systems available for waste treat-
ment: Model 9122 rated for 3,000 to 9,000 gallons per
day (gpd) [11,000 to 34,000 liters per day (Ipd)]; Model
9142 rated for 10,000 to 32,000 gpd (38,000 to 120,000
Ipd); Model 9152 rated for 33,000 to 79,000 gpd (125,000
to  300,000  Ipd); and  Model 9532 rated  for 9,000  to
133,000 gpd (34,000 to 500,000 Ipd). All are one-stage
systems containing a leachate DTM  unit and a permeate
DTM unit. A high-pressure unit can be combined with
any system.  The modular design and construction of the
                                                   11

-------
DIM units allows them to be combined in series (two-
stage) to increase  product quality, or in parallel to in-
crease treatment capacity. The cost per permeate-gallon
for treatment with  the  DIM  technology decreases with
increasing treatment capacity.
  Based  on  the results of  this Demonstration, waste
treatability testing is strongly recommended prior to pro-
cess design and application.  On-site pilot-scale treatabil-
ity testing should be performed to determine operational
and maintenance procedures such as chemical addition
and membrane  cleaning requirements.  In addition, pre-
treatment requirements can be formalized. Rochem nor-
mally performs an on-site pilot-scale treatability test lasting
two to six weeks prior  to process installation (4). Treat-
ment effectiveness  is very waste specific, although any
significant treatment concerns can probably be  identified
from preliminary waste characterization data. If needed,
bench-scale treatability  testing is used to determine mem-
brane compatibility with the waste and expected perme-
ate  quality. This can be performed off-site by shipping
samples of liquid waste to Rochem's laboratory facility or
on-site by Rochem using a  bench-scale system. Once
installed,  a few days to a week, depending on the appli-
cation, are required to  properly shakedown the system.
Once on-line, the DTM  technology can operate 24 hours
per day with occasional breaks for cleaning and mainte-
nance. This is the most cost-effective mode of operation.
Operator attention  requirements for system monitoring
and maintenance can be as little as  one to two hours per
day. For more  difficult or hazardous  wastes,  greater
operator attention is required.
SITE Program Description
  In  1980, the  U.S. Congress  passed the Comprehen-
sive  Environmental Response,  Compensation, and Li-
ability Act (CERCLA), also known as Superfund.  CERCLA
was amended by the Superfund Amendments and Re-
authorization Act (SARA). The  primary purpose of the
SITE Program is to maximize the use of alternatives in
cleaning up hazardous waste sites by encouraging the
development and demonstration of new, innovative treat-
ment  and monitoring  technologies. It consists  of four
major elements:  the Demonstration Program, the Emerg-
ing  Technology  Program, the Monitoring and Measure-
ment Technologies Program, and the Technology Transfer
Program. The Rochem DTM technology was evaluated
under the Demonstration Program. This  Capsule was
published as part of the Technology Transfer Program.
Sources of Further Information

  EPA Contact:

  U.S. EPA Project Manager:

  Douglas Grosse
  U.S. Environmental Protection Agency
  National Risk Management Research Laboratory
  26 West Martin Luther King Drive
  Cincinnati, OH 45268
  Telephone No.: (513) 569-7844
  Fax No.: (513) 569-7676

  Technology Developer Contact:

  David LaMonica
  President
  Rochem Separation Systems, Inc.
  3904 Del Amo Boulevard, Suite 801
  Torrance, CA 90503
  Telephone No.: (310) 370-3160
  Fax No.: (310)370-4988

References

  1.   Porter, M.C.,  Nucleopore Corp., Pleasanton, Cali-
      fornia,  "Selecting the Right Membrane," Chemical
      Engineering Progress (Vol. 71, No. 12) December
      1975; pp. 55-61.
  2.   Rochem Separation Systems,  Inc. "The Use  of
      Membrane Systems to Treat Leachate." SITE Pro-
      posal.
  3.   American Water Works Association.  "Removal  of
      Low Molecular Weight Organic Contaminants from
      Drinking Water Using  Reverse Osmosis  Mem-
      branes," 1987 Annual  Conference Proceedings:
      Part 2 Sessions 23-28. Kansas City, MO. June 14-
      18, 1987.
  4.   Telecommunications between Rochem and  SAIC.
      1994-1995.
  5.   Dupont Company,  Plastic Products  and Resins
      Dept, Permasep Products, Wilmington, DE. "Pre-
      treatment Considerations for Reverse  Osmosis."
      Technical Bulletin No. 401. September, 1977.
  6.   Collins, Mark and Ken Miller. "Reverse Osmosis
      Reverses Conventional Wisdom with Superfund
      Cleanup Success." Environmental Solutions, Sep-
      tember 1994.  pp 64-66.
                                                  12

-------
   Q

   <
   CL

   00
   LU
   LLJ
      CD

     .  d
CD
LLJ    J=
rn    2
      ce
      UJ
oo    CL
O
CL





(/>
_CD
CO
to

T3
-2
'E
CD
CD
<
c
o
t>
CD
2
CL
To
*~f
c
CD
E
C
2
->
c


CO
-^J
c
CD
ironm
>
c
LU

e

CD
~t^
C
CD

CM
|S"«.
1^*-
6
c
_g
"S
E
L_
£
c
—
JZ
p
J_
CO
CD
w
CD



OO
CD
CM
ID
<*
X
O
-
^
CO
c
c
'o
c
LU  o  a:  o
                          13
                       ^E CL
                        U>  !_
                        =5  O
                       m «-
                       _  >^
                        CO ±i
                       'o  <5 o
                       Li=  C O
                       ^  
-------