United States
          Environmental Protection
          Agency
             Solid Waste and
             Emergency Response
EPA 540-R-97-028
OSWER 9240.1-33
PB97-963503
xvEPA
          Superfund
SUPERFUND METHOD FOR THE
DETERMINATION OF* RELEASABLE
ASBESTOS IN SOILS AND
BULK MATERIALS

-------

-------
 SUPERFUND METHOD FOR THE
DETERMINATION OF RELEASABLE
     ASBESTOS IN SOILS
     AND BULK MATERIALS
          INTERIM VERSION

-------

-------
                                    DISCLAIMER

Although this work was completed under contract to the U.S. Environmental Protection Agency,
such support does not signify that the work or the conclusions drawn from the work necessarily
reflect the views and policies of the Agency, nor does the mention of trade or commercial
products constitute endorsement or recommendation for use.

A series of conceptual design figures are included in this method to assist users with their own
design and construction of an appropriate dust generator for supporting this method.  However,
these figures are not to be construed as formal construction drawings and IGF Technology will
accept no liability for their reference or use.

-------

-------
                            TABLE OF CONTENTS
1.0  INTRODUCTION  . . . .		:	.......	 . ... . 1-1
          r '.•-•,'•'                      .
2.0  BACKGROUND		.		.2-1
       2.1   REQUIREMENTS FOR A METHOD DESIGNED TO SUPPORT RISK
            ASSESSMENT ...........	 . .	 2-1
            2.1.1     Sensitivity	. . 2-2
            2.1.2    Precision ..:..../.	 2-2
            2.1.3    Asbestos Characteristics			 2-3
            2.1.4    Reporting Requirements	.'...•	 2-4
       2-2   ASBESTOS CONTAINING MATERIALS TYPICALLY ENCOUNTERED
            AT SUPERFUND SITES	.. ..	', . 2-5
       2.3   REQUIREMENTS FOR FACILITATING REPRODUCIBILITY BETWEEN
            LABORATORIES..	......... ..~	. . 2-6-
       2.4   COST CONSIDERATIONS  . ..........	. . . .	 2-7

3.0  OVERVIEW OF METHOD  ..'.,.'. . . . ., .	..:.....	 3-1

4.0  DEFINITIONS . .; .	 .	 .	. . . , . . . 4-1

5.0  SYMBOLS AND ABBREVIATIONS . .	 .	 5-1
       5.1   SYMBOLS		 .	. 5-1
       5.2   ABBREVIATIONS............	 5-4

6.0  FACILITIES AND EQUIPMENT			.6-1
       6.1   SAMPLE COLLECTION EQUIPMENT AND CONSUMABLE SUPPLIES .... 6-1
       6.2   LABORATORY FACILITIES	.........:...,... 6-2
       6.3   THE DUST GENERATOR AND APPURTENANT EQUIPMENT .......... 6-2
       6.4   SPECIMEN PREPARATION EQUIPMENT . .	 . . :	 6-3
       6.5   OTHER LABORATORY EQUIPMENT			. . 6-3
       6.6   CONSUMABLE/REUSABLE LABORATORY SUPPLIES	 6-3

7.6  REAGENTS .............	......		 7-1-

8.0  SOIL OR BULK SAMPLE COLLECTION ............;..	 8-1
       8.1s   SAMPLE COLLECTION	 . . :		 8-1
            8.1:1     Sampling to Derive Estimates of Asbestos Concentrations in
                    a Road Surface	; .	 ...	 8-2
            8.1.2    Sampling a Mine Tailings Pile to Derive Estimates of
                    Asbestos Concentrations Within the Pile .	 8-2
       8.2   FIELD PREPARATION . . . . .		...:...	.	 8-3
            8.2.1    Weighing	;	 .	:. 8-3
            8.2.2    Size Reduction	 .^ .. 8-5
            8.2.3    Sample Homogenization and Splitting .............	  8-5
 ,    ,8.3   COMPOSITING SAMPLES (OPTIONAL) .	: . . .	  8-15
       8.4   SAMPLE HANDLING AND SHIPMENT ......		  8-16
                                     in

-------
                           TABLE OF CONTENTS (cont)
 9.0 SAMPLE PREPARATION BY DUST GENERATION .	                    9-1
        9.1    SAMPLE RECEIVING AND STORAGE	     9-1
        9.2    SAMPLE HOMOGENIZATION AND SPLITTING IN THE LABORATORY      9-2
        9.3    DUST GENERATOR SETUP	:..'.'.'.  9-2
              9.3.1    Conditioning a Stock of Filters	  9-2
              9.3.2    Initiating Humidity Control	''....'.•	. ...  9-3
              9.3.3    Priming the Scrubber	  9.3
              9.3.4    Adjusting Initial Air Flow	                     9-3
        9.4    DUST GENERATOR OPERATION	....'.'.'.'.'.'.'.'.'.'.  9-6
              9.4.1    Loading the Tumbler	  9-6
              9.4.2    Conditioning the Sample.	„	  9.7
              9.4.3    Initiating a Run	'.  9.7
              9.4.4    Monitoring the Rate of Respirable Dust Generation	  9-8
              9.4.5    Generating Appropriately Loaded Filters for Asbestos
                     Analysis  .	  9.9
              9.4.6    Obtaining Asbestos Samples from the Scrubber  .......       9-11
        9.5    CLEANING THE DUST GENERATOR		  9-12

 10.0 PREPARATION OF SPECIMEN GRIDS FOR TEM ANALYSIS		     10-1
        10.1    PREPARATION OF SPECIMEN GRIDS FROM FILTERED ALIQUOTS
              OF THE SCRUBBER SUSPENSION	     10-1
        10.2    SPECIMEN GRID PREPARATION FROM FILTERS COLLECTED OVER
             THE 1ST OPENING OF THE ELUTRIATOR .			  10-1
              10.2.1    Specimen Grid Preparation Using a Direct Transfer
                     Technique	 .	  10-2
        10.3   Specjmen Grid Preparation Using an Indirect Transfer Technique	  10-2

11.0 PROCEDURES FOR.ASBESTOS AND DUST ANALYSIS	               11-1
        11.1   PROCEDURES FOR ASBESTOS ANALYSIS	'.','.  H-1
             11.1.1    Analysis of Specimen Grids Prepared from Filters Collected
                     Over the 1ST Opening of the Elutriator	  11-1
             11.1.2 .   Analysis of Specimen Grids Prepared from Filtered Scrubber
                     Suspension	  ,          11.3
       11.2   EVALUATING THE RATE OF RELEASE OF RESPIRABLE DUST	"  11-5
       11.3   DETERMINING THE CONTENT OF RESPIRABLE DUST ....            11-8
       11.4   DETERMINING THE CONTENT OF ASBESTOS		 11 -10
             11.4.1    Based on Directly Prepared Filters Collected Over the 1ST
                     Opening of the Elutriator	11-10
             11.4.2    Based on Specimens Prepared from Scrubber Water	11-12
             11.4.3    Procedure for Adjusting Asbestos Concentrations to
                     Account for the Presence of Coarse Material in the Sampled
                     Matrix  .	11-13

12.0 PERFORMANCE CHARACTERISTICS AND QUALITY CONTROL/QUALITY
       ASSURANCE REQUIREMENTS		              12-1
       12.1   METHOD PERFORMANCE	....'.     •••"••••••
                                      IV

-------
                          TABLE OF CONTENTS (cont)
       12.2
12.1.1    Analytical Sensitivity	:	  12-1
12.1.2   Precision	  12-1
12,1.3   Accuracy	  12-2
12.1.4   Asbestos Characteristics	 . ...... 12-3
12.1.5   Reporting Requirements	....	  12-3
QUALITY CONTROL REQUIREMENTS			 .  12-3
12.2.1    Blanks ..'..-.		....;.....;....	  12-3
12.2.2   Duplicates/Replicates	,	.................  12-5
13.0  REPORTING REQUIREMENTS .	, . .  13-1
       13.1   FIELD AND LABORATORY NOTEBOOKS	  13-1
             13.1.1   Field Notebooks		..13-1
             13.1.2   Laboratory Notebooks . ;	  13-2
       13.2   FIELD ACTIVITIES REPORT	 .		  13-3
       13.3   SAMPLE ANALYSIS REPORT-		: . .	  13-4
       13.4   SAMPLE BATCH REPORTS		.....................	  13-6

14.0  REFERENCES			.  .	  14-1

-------
                                   LIST OF FIGURES
•  Figure 3-1   Sample Collection and Field Preparation  ..	  3-2
  Figure 3-2   Laboratory Preparation and Analysis ..-..'	  3-3

  Figure 8-1   Weighing a Soil Sample on a Field Scale	  8-4
  Figure 8-2   Weighing a Sample Split on a- Field Scale	  8-6
  Figure 8-3   Sieving a Soil Sample	  8-7
  Figure 8-4   A Riffle Splitter	  3-8
  Figure 8-5   Using a Riffle Splitter to .Homogenize/Split Samples	  8-9
  Figure 8-6   Loading a Sample Split into a Sample Bottle	  8-11
  Figure 8-7   Transferring Sample from a Mixer to a Plate for Coning and Quartering ...  8-13
  Figure 8-8   Coning and Quartering	'..'..	  8-14

  Figure 11-1  Typical Cumulative Mass Release Versus Time Curve for a 30 RPM Run  . .  11-6
  Figure 11-2  Typical Cumulative Mass Release Versus Time Curve for a 60 RPM Run  . .  11-7
  Figure 11 -3  Illustration of the Optimization of the Estimate of Initial Mass "M0"  .......  11-9

  Figure 13-1  Format for the Field Activities Report	  13-5
  Figure 13-2  Sample Analysis Report Format	  13-7
  Figure 13-3  Sample Batch Report Format	 13-10

 Figure A-1   Schematic of Dust Generator	 .	A-2
 Figure A-2   The Dust Generator	  A-3
 Figure A-3   Tumbler in Constant Humidity Chamber	  A-4
 Figure A-4   Tumbler Assembly	 .  A-5
 Figure A-5   Main Body of Vertical Elutriator	'.-...  A-8
 Figure A-6   Bottom Assembly of Vertical Elutriator . ...	  A-9
 Figure A-7  . Top Assembly of Vertical Elutriator  . . .	  A-10
 Figure A-8   Dust Collection System			  A-12
 Figure A-9   Filter Mounts	  A-13
 Figure A-10  Tubing Connections for the Scrubber of the Dust Generator  .	  A-15
 Figure A-11  Tubing Connections for Filter Cassettes Mounted on the Elutriator of the
             Dust Generator  ......	  A-16
 Figure A-12  Detail of Tubing Connections at the Top of the Vertical Elutriator	.....  A-17
 Figure A-13  Overall Prototype Dust Generator Assembly	  A-23
 Figure A-14  Prototype Tumbler Assembly Detail	  A-24
 Figure A-15  Prototype Vertical Elutriator Detail	,	...  A-26
 Figure A-16  Section of Elutriator Top with Extension Tube	  A-27
 Figure A-17  Longitudinal and Transverse Sections of Isokinetic Sampling Tube  	  A-28
 Figure A-18  Prototype Slide Mechanism Detail	  A-29
 Figure A-19  Detail of Prototype Filter Cassette Mount?	 .	  A-30
                                          VI

-------
                                   1.0  INTRODUCTION
 This is a sampling and analysis method for the determination of releasable asbestos in soils
 and bulk materials.  Samples are collected  in a manner suitable for providing representative
 measurements of the releasable fraction of asbestos in the matrix sampled, prepared using a
 dust generator, and  analyzed by transmission electron microscopy (TEM).   Guidelines for
 constructing the required dust generator are. also included.

 During  dust generation, the respirable fraction of the dust generated from  the sample is
 collected on filters.  The filters are then weighed and the cumulative mass of dust collected is
 plotted  against time to determine the rate  of release of  dust.  Results are  extrapolated to
 provide an estimate of the total mass of respirable dust in the original sample. The asbestos
 released during dust  generation fs either collected  on a filter or in  the suspension of a
 scrubber  (or  both),  depending  on the configuration  under  which the  dust generator is
 operated.  Filters may be prepared for TEM analysis by either a direct  or an  indirect transfer
 technique.  Preparation of  the'scrubber  suspension for TEM analysis is equivalent to an
 indirect transfer procedure.   Depending  on the  intended  use of the data,  the results of
 asbestos  analyses from  this method may be reported  either in  terms  of  the  number of
 structures  per unit mass of respirable. dust generated from the sample or the  number of
 structures per unit mass of the original sample.

 The method allows  for the  determination of the mineralogical type(s) of asbestos that is
 present  in the  sample  and  for  distinguishing asbestos  structures from non-asbestos
 structures.  In this method, asbestos structures are characterized  as fibers, bundles, clusters,
 or matrices and the length and width of each asbestos structure are measured. Although the
 method is  designed  specifically to provide results suitable for supporting-risk  assessments at
 Superfund sites, it may be applicable to a wider range of studies.

 As reported in this  document,  the  method focuses  on requirements  for the collection,
 preparation, and analysis of samples obtained  from  individual  locations.   During a  site
 investigation, samples will typically be collected from multiple locations that are arranged in
 an array  designed  to provide measurements suitable  for deriving  a representative  (i.e.
 unbiased)  estimate of the .concentration of releasable asbestos over the sampled matrix as a
 whole.   Thus,. proper  design of a comprehensive sampling  strategy, which includes  the
 detailed design of the array of sampling  locations, is also  critical to the  success of an
 investigation.   However, design of a sampling strategy is necessarily  site specific and site-
 specific considerations are  beyond the scope of this  document.  For further guidance on
 developing appropriate sampling strategies, see Bermah and Chesson (undated).

 This method has not yet been validated.  Validation requires completion of  a field study in
 which airborne exposure  concentrations of asbestos caused by the release and transport, of
 asbestos  from soils  or bulk materials (under specific conditions)  are related  to  the  bulk
 measurements of asbestos  derived from this method.  However,, while such a study is in
 progress, this  method  has  already been successfully tested  in the laboratory.   Such tests
. have demonstrated that the  method is .capable of achieving adequate sensitivity and precision.
•, to support risk assessment.  The method also provides asbestos measurements that preserve
 the information on the sizes and shapes  of asbestos structures that are  required to assess
 risks.  Thus,'the principle features of the method are well enough established  to allow it to be
                                            1-1

-------
employed in current field investigations.  At the same time, until the formal validation study is
completed, this should.be considered an interim method.


      NOTE                            ,

      This document is intended to serve several audiences including site project managers,
      field sampling teams, data reviewers,  and laboratory analysts.  The document may be
      separated into segments so that individuals may focus on the sections of most interest
      to their particular roles on a project.
                                        1-2

-------
                                  2.0 BACKGROUND
• This  method  was  developed specifically to satisfy the needs  of the  Superfund program
 including:                 ,                                                      .

       •    the need to provide results suitable for supporting risk assessment;

       •    the need  to  be applicable to  the types  of asbestos-containing  materials
            commonly encountered at Superfund sites; and

       •    the need to facilitate  reproducibility  within  and between laboratories  that may
            offer the method  commercially.                            •   •'

 An additional  consideration addressed  during the development of this method is the need to
 control sampling and analysis costs.

 The first item  listed above  is what distinguishes sampling and analysis methods adapted for
 use in the Superfund program from methods used  in other programs.  This is because the
 statutory requirements of the Superfund program mandate that risk management decisions be
 based oh  risk assessment.  Risk assessment requires that analytical data be relatable to
 health effects.  Although the  remaining requirements listed above are also important, the first
 item is a central feature of the Superfund program.

 Because this method is designed for supporting risk assessment, the results of analyses from
 this method are intended to be used  as  inputs to  release and transport models to  predict
 airborne asbestos  exposure  concentrations (see Section  2.2).   This is  a  very different
 objective from existing bulk  asbestos  methods, which are designed as qualitative tools for
 determining whether asbestos is present in a  particular matrix in excess of a defined,
 regulatory limit.  For such methods, the regulatory limits are defined operationally as functions
 of the methods themselves and, therefore, do not necessarily relate in any direct fashion to
 the potential for asbestos to be released and contribute to risk.

 2.1    REQUIREMENTS FOR A METHOD DESIGNED TO SUPPORT RISK ASSESSMENT

 A feasibility study  (Berman  1990) was completed  both to identify the requirements of  a
 method for the determination of asbestos in soils and bulk  materials that could be used to
 support risk assessment  and to  evaluate existing  sampling and analysis technologies to
 determine  whether  such a method might be  readily  developed.    Results of the  feasibility
 study indicate that, to support risk  assessment under Superfund, the method must:

       •    achieve sufficient analytical sensitivity to adequately measure asbestos over the
            entire1 range of concentrations that might potentially pose an unacceptable risk;

       •    provide adequate precision over the range of asbestos concentrations of interest;

       •    provide  measurements  of the  complete range of the  sizes and shapes  of
            asbestos structures that are believed to contribute to health effects;
                                          2-1

-------
        •     provide measurements that are representative of the fraction of asbestos that is
             readily releasable1 from the matrix of interest; and

        •     provide results reported in units that are amenable for use as inputs to fate and
             transport models  that  can be  used  to relate (bulk) source concentrations  of
             asbestos to (airborne)  exposure point concentrations of asbestos.

        2.1.1     Sensitivity               ,

 Based on calculations presented in the feasibility study completed for this method (Berman
 1990), asbestos concentrations in soil or a bulk environmental matrix .that are on the order of
 3x10  long asbestos s/gso|jd (i.e. 30 million asbestos structures longer than 5 jim per gram of
 solid) or 5x108 total  asbestos s/gsoljd (i.e. 0.5 billion total  asbestos  structures per gram  of
 solid) may potentially pose a risk exceeding 1  x 10"6. This is based on evaluation  of a series
 of scenarios in which asbestos is released from the solid matrix due to any of several types of
 disturbance (i.e.  vehicular traffic on the surface,  agricultural  tilling,  or  natural weathering).
 Once released, asbestos is dispersed into the air, where exposure may occur.  Note that, for
 a typical chrysotile matrix, the concentrations reported above for the two different size ranges
 of  structures are expected to  be approximately equivalent  (i.e. concentrations observed for
 each of the two size ranges in a sample containing common chrysotile  are expected to be
 approximately proportional to the two values given so that a sample observed to exceed one
 will also likely exceed the other). Therefore, either concentration might serve as an adequate
 target  sensitivity  for  chrysotile.   However,  such  may  not be  the  case for  all  asbestos-
 containing matrices, particularly those containing amphibole asbestos.

 To  assure that negative results from a soil-bulk method do  not mask  potential  problems,
 ideally, the  analytical  sensitivity  for  the method   should  be  set  at   one   tenth  of the
concentrations potentially capable of producing risks that exceed 1 x 10"
target analytical sensitivities for this method have been set at:
Therefore,  the
       •    3x10  long asbestos s/gso|id (i.e. 3 million asbestos structures longer than 5 urn
            per gram of solid); or

       •    5x107 total asbestos s/gsoljd (i.e. 50 million total asbestos structures per gram of
            solid).

The analytical sensitivity is reported for the two different size ranges of asbestos structures to
allow flexibility in the application  of the method,

       2.1.2    Precision

The only precision data currently available for this method is from the recently described pilot
study (Berman et al. 1994a).  To establish a reasonable goal for the precision of this method,
a study of the precision achievable by commercial laboratories performing the method would
be required.  Because data;from commercial laboratories are not available, the data from the
       As used here, 'readily releasable" means particles that have already been separated into respirable size and that are
       available in a poo! of loose material that can  be released directly during some type of disturbance.  This is
       distinguished from particles that may be aggregated with others and that may be separated from the aggregate for
       future release.                    -
                                           2-2

-------
pilot study (Berman et al.  1994a) were evaluated to provide a rough estimate of the level of
precision potentially achievable  once the method  is commercialized (see Section .12.1.2).
Results suggest  that a  relative  percent  difference of 50%; should  be easily  achievable for
sample splits performed  by. a single laboratory.

The USEPA has set informal precision guidelines for each of the analytical methods employed
in the  contract laboratory program (CLP), under which the majority  of sample analyses have
been conducted  for the  Superfund program. These goals tend to be defined as achievable
relative percent differences for sample splits "performed within a  laboratory and they  range
between 10% and 35% for the analysis of inorganic chemicals in soils and up to 50% for the
analysis of organic chemicals in  soils. Therefore, given the above, a guideline of 50% for the
relative percent difference between sample  splits performed within a laboratory is proposed
for this method.

       2.1.3     Asbestos Characteristics  '

Based on what is known about the biological activity of asbestos (for a critical review  of the
extensive literature on this subject, see Berman and Crump 1989), if asbestos measurements
are to  be related to risk, it is  necessary to characterize the  sizes,  shapes, and mineralogy of
the asbestos  structures  in each sample.  This involves enumeration of individual  structures
within  certain  size categories with particular  emphasis on the longest and thinnest structures.
Although the  range of dimensions over which  asbestos structures contribute to biological
activity has yet  to be  precisely defined, this  method is  designed to  provide a  detailed
characterization of structures encompassing  the entire range of potential importance.

Results  of the feasibility; study  for this  method (Berman  1990)  indicate that transmission
electron microscopy (TEM)  is the  only  analytical tool  capable  of  characterizing  asbestos
structures  over the entire range  of  sizes  and  shapes that  potentially contribute to risk.
Consequently, the asbestos derived from soil or bulk samples is analyzed using TEM  in this
method.                    ,

When  evaluating  detailed asbestos size characterizations,  it is  important  to consider the
effects of sample preparation.   The dust  generator incorporated into this method was
developed.because its use eliminates the need to employ other preparation techniques (such
as crushing or grinding) that  potentially alter the distribution of respirable asbestos structure
sizes and shapes found in the sample.  The dust generation employed  in this method is a
gentle process; it is expected to  preserve  the  distribution of asbestos  structure  sizes and
shapes that may be released to  the air-when asbestos-containing media  are disturbed in the
environment.       ,             ..'•                   ,

The size distribution of  asbestos structures  found in the dusts generated using this method
may also vary depending on whether  TEM specimen grids are  prepared  from  the dust;
samples, using a direct or an indirect transfer  technique.   Existing risk factors are  based
largely on studies incorporating the equivalent  of  direct transfer techniques,2 while indirect
transfer techniques are  expected to provide increased precision  (see, for example, Berman
       Most of the epidemiology studies (from which estimates of asbestos potency are derived) .employed either phase
       contrast microscopy (PCM) for the analysis of asbestos concentrations in work place air or converted other types of
       measurements to PCM equivalents (Berman and Crump 1989).  PCM analyses are performed directly on sample filters
       after the filter material has been rendered transparent by a suitable solvent. Since the fibers are observed as originally
       deposited, this corresponds closely to a direct transfer technique for TEM analysis.


         •         '     •           •         2-3.            '   •-  •   ."...-      '•      .

-------
  and Chatfield 1990).  Hence, this method incorporates a procedure,by which the majority of
  samples, are prepared by an indirect technique with a subset prepared in tandem by a direct
  technique.  This facilitates  evaluation of the  relationship between  structure counts derived
  from samples prepared, respectively, by each technique.

        2.1.4    Reporting Requirements

  It is anticipated that soil or bulk samples to be analyzed using this method will typically be
  collected to determine the asbestos content of a potential source from which asbestos  may
  be released (via a particular mechanism) and transported to the air (where exposure  may
  occur).  It is also expected that asbestos release and transport will be modeled  and that one
  of the critical  inputs to such models will be the concentration of releasable asbestos in the
  source matrix.                                                         .

  Results  of the feasibility  study for this method  (Berman 1990)  indicate that  most  of the
  available models that predict releases to the air from soil  or some other bulk  matrix (in
  association  with  specific  release mechanisms) were designed to  predict the  release  and
  transport of respirable dust.  Only a very limited number of such  models have actually been
  developed specifically for asbestos.   The  dust models may be used  to  predict asbestos
  release and transport with minimal modification, however, provided that the appropriate types
  of  asbestos  measurements  are  available.   Such  adaptations  rely  on  the  following
•  assumptions:

        •     the rate,of settling of respirable asbestos particles  is  no more rapid than the
             average settling rate for respirable dust; and

        •     the release of asbestos and the release  of respirable dust from a source matrix
             are highly correlated (i.e. are proportional), at least over the long term.

 The former assumption is expected to be true because fibers tend to settle more  slowly in the
 air than spheres of comparable mass.  The latter assumption appears reasonable because, if
 it were false, one would expect the source matrix to become either enriched or depleted in
 asbestos over time.  However, such effects are  not generally observed.

 Many of  the release models developed for respirable dust require the mass fraction of silt in
 the  source  matrix  as  an  input  parameter.    For such models, substituting  the fiber
 concentration of asbestos  (per unit mass of source matrix) for  the mass fraction of silt should
 allow the model to  be used to predict asbestos  release  (with no additional modifications).
 Under  such  circumstances,  a dimensional  analysis  of the model should indicate  that  the
 outputs would now be expressed in terms of the number of asbestos structures released from
 a defined area (or mass) of the source matrix per unit time (rather than the mass  of respirable
 dust released from a defined area or mass of the source matrix per unit time).  Such outputs
 are then  typically combined  with air dispersion models  to  predict  airborne concentrations at
 locations  (i.e. points of exposure) of interest.

 As an  alternative, it may, be useful to  multiply the  respirable dust release rates, (that  are
 predicted by a model) by a factor representing the number of asbestos structures (of a size
 range of  interest) per unit mass  of respirable  dust  released  from the sample.   For certain
 models, this  approach for"converting a dust model to an asbestos release model may prove
 easier than the approach discussed above.
                                          2-4

-------
This method is designed to provide results that can be reported as the number of asbestos
structures (of a size range of interest) per unit mass of source matrix with an option allowing
the reporting of the number of asbestos structures per unit  mass of the respirable dust
released from the sample.  The appropriate reporting option should be selected based on the
specific models with which the -measurements from this method are anticipated to be used for
a specific project.  ,             -                          •
      NOTE

      This method may also be used to provide an independent (qualitative) check of the
      predictions of specific release models in some cases. In one of the intermediate steps
      of this method, the rate of release of respirable dust from the sample is  determined.
      This can  be compared to the rate of release predicted by  a release model. The
      relative magnitude of the release rate observed using this method and the  release rate
      predicted  by a model should be consistent with that expected based on the relative
      aggressiveness of the type of disturbance applied to the sample' during measurement
      using this method and the type of disturbance associated with the field  activity (i.e.
      vehicular traffic, excavation, wind entrainment, etc.) represented by the model.

2.2   ASBESTOS CONTAINING MATERIALS TYPICALLY ENCOUNTERED AT
      SUPERFUND SITES

Asbestos containing materials commonly encountered at Superfund Sites include:

      •    natural rocks that contain asbestos;

      •    soils containing natural asbestos generated from weathered rock;

      «    soils containing asbestos introduced by transport from other locations;

      •    mine or mill tailings (i.e. fractured or depleted rock);   .

      •    discarded asbestos wastes, including,(for example):
  ,         -    asbestos/cement pipe;     ,
                roofing materials;                        ,
                insulation materials;, and

    •  •    soils containing discarded asbestos wastes.                            -.   .
                                         2-5

-------
 This method is  designed specifically to  handle the above materials  (with the exception of
 unfractured  rock )  and  may be  applied generally to samples of any unconsolidated or
 friable4 matrix.

 2.3   REQUIREMENTS FOR FACILITATING REPRODUCIBILITY BETWEEN
       LABORATORIES

 Results of the feasibility study for this method (Berman 1990) indicate that, for a method for
 the  determination  of  asbestos   in  soils  and  bulk  materials  to  adequately  facilitate
 reproducibility between laboratories that  might offer trie method commercially, the following
 requirements must be satisfied:

       •    preparation steps  in  the  procedure  have  to be kept  simple and  must be
            standardized  and  documented  sufficiently to  allow  technicians  in  different
            laboratories to perform them invariably (i.e.  objectively); and

       •    the representativeness of a sample (i.e. the degree with which the sample retains
            the characteristics  of  the matrix from which it is derived)  has to be preserved
            throughout all  stages  of handling,  preparation, and  sub-sampling  that  are
            incorporated into the method.

 To address each of the above requirements, the ability to homogenize the sample has to be
 maintained throughout all stages  of sample preparation and  handling, and  dust generation
 satisfies these requirements.  In addition,  dust  generation is incorporated into this method as
 the means of extracting the respirable fraction  of releasable asbestos from bulk samples in a
 manner that can be performed invariably; it is a mechanical  process that can be controlled
 objectively by specifying the design and the operation  of the equipment to be used for dust
 generation.                                                                               '

 Use of a dust generator eliminates most of the  sample manipulation steps typically performed
 manually (and subjectively) for other bulk asbestos methods.  More importantly, it eliminates
the need for sub-sampling of amounts smaller than approximately 100 g, which is a mass that
 is  large enough to be sub-sampled reproducibly (by following specified procedures). A 100 g
sample is also sufficiently large to  retain representative  characteristics of all components  of a
sampled matrix in which the particles are smaller than approximately 1 cm in diameter.

Results of the feasibility study (Berman  1990) indicate that  the ability to homogenize an
unconsolidated bulk  sample (in preparation for sub-sampling) is a  direct  function of  the
largest particle in the distribution of component particles; to allow representative sub-sampling
of such a matrix, the largest particle must represent no more than a few percent of the total
mass of the sample.  Therefore, because the final sub-sample  to be extracted in this method
is  on the order of 100 g, the largest particles that can  remain in-the sample prior to  sub
       It is assumed that any asbestos imbedded in unfractured rock can be considered to be non-releasable.  If there is a
       desire to evaluate the release of asbestos from the surface of such rock (or the potentialfor release of asbestos from the.
       rock as it becomes fractured in the future due to aging or disturbance), conceivably, a sample of the rock might be
       crushed to particles no larger than 1 cm in diameter (see text) and a sample of the crushed rock might then be
       analyzed using this method. However, no formal protocol has been developed for this procedure at this time.

       As used here, the term friable is intended to mean any material that can be crushed or deformed with the hand with the
       attendant release of fibers.
                                           2-6

-------
sampling must be no larger than 2 or 3 g.  Assuming a typical density for silica type materials
(i.e. 2.6 g/cc), the largest particle,that can be retained while allowing 100 g samples to remain .
representative  of the  sampled matrix is 'approximately  1  cm  (3/8th  inch)  in diameter
(4/3nr3*density = 1.4 g).  Consequently, this method  incorporates a step in which samples
are sieved to remove particles larger than 1 cm in diameter5.

It must be emphasized that the particles larger than 1 cm in diameter that are removed from
the sample by sieving in this method are not discarded.  Rather, both the fraction  passed by
the sieve and the fraction retained by the sieve are weighed and the weights recorded so that
the asbestos content measured can ultimately be reported as a function of the total mass of
the initial sample (i.e. the asbestos concentration measured in the method is multiplied by the
ratio of the  total mass of the original sample collected and the mass of the fraction of the
sample analyzed).  The larger particles do  not need to  be carried through the entire analysis,
however, because it is, unlikely that significant amounts  of the. releasable asbestos  in a
sample reside in the coarse fraction.        '

2.4    COST CONSIDERATIONS

To,be. useful,, it was determined that the cost of an  individual analysis using  this method
would  have to be competitive with other methods that might be used to derive comparable
information.6  In fact, once a laboratory invests in  the construction of a  dust generator to
support  the method  and procures the required  ancillary equipment,  it is  expected that the
cost of analysis  using this  method will be very competitive with other soil or bulk methods
(that might  be designed to provide  similar information).  This is  because use of the  dust
generator effectively concentrates asbestos from the sample (by removing the non-respirable
component). ^Sueh concentration allows highjpr Joadings on specimen grids so that smaller
areas need to be scanned with the TEM to  complete an analysis.

It is expected that sample preparation using the dust generator will cost approximately $400
(twice  what  it costs to  complete the preparation of an air sample using an indirect transfer
technique).    This  cost,  however,  is  expected  to be more than  compensated  by  the
corresponding reduction in cost for TEEM scanning time, which is reduced due to the ability to
scan more highly concentrated  samples (see above).  It is therefore expected  that the total
cost of an analysis using this method  may run between $900 and  $1,500, which  should be
competitive  with any other soil or bulk method that is designed to provide comparable
information.  This cost is approximately 10 to 15% higher than that for the analysis of an air
sample in which comparable structure size  information is recorded.

Incorporated into this method (as an option) is a compositing procedure that can be used to
reduce significantly the  number of bulk analyses that might  otherwise be  required to
adequately characterize a source matrix from which asbestos may be released  (Section 8.3).
Recognizing that airborne exposure due to emissions  from a, source matrix tend to  be the
result  of average  emissions, over .relatively  large areas, compositing  of samples  is  a
       The dust generator designed for this method best handles samples up to a maximum of approximately 80 g. However,
       the practical difference between 80 and 100 g samples, in terms of the maximum size of the particles that can be
       retained (while assuring.the ability to homogenize the sample), is not significant.


       This assumes analysis using TEM in which comparable size and mineralogy information is recorded; methods in which
       analysis is performed by polarized light microscopy (PLM) are not capable of providing information over the complete
       range of structure sizes and shapes that are believed to relate to risk.       -


                   . '   ' '                   2-7      =  '   -                  "'...•

-------
particularly powerful tool that can be. used in  tandem with this method.   By reducing the
number oJ sample analyses required to adequately characterize a particular source, the cost
of a particular investigation  can be reduced correspondingly.

An additional  cost saving measureJncorporated into this method is completion of the early
stages of sample preparation in the field.  This simplifies  the  handling  and preparation
performed by the laboratory and limits the size  (mass) of each sample that has to be stored
or disposed by the laboratory.             .

Handling and  preparation of bulk samples in the laboratory are dusty operations that require
protective enclosures.  The  larger  the  sizes  of the samples,  the  larger  the  protective
enclosures required.  Additionally, asbestos containing samples handled by a laboratory must
be disposed as asbestos wastes.  Clearly, the larger the  mass of such samples handled by
the laboratory, the greater the cost of disposal.
                                         2-8

-------
                              3.0  OVERVIEW OF METHOD
 Samples are collected in the field according to a pre-defined sampling  plan identifying the
 number of samples to be collected and the locations from which samples are to be collected.
 Procedures for  designing  such a  plan  are beyond the scope  of  this document but are
 reported elsewhere (see, for example, Berman and Chesspn, undated).

 Any of a variety of commercially available sampling equipment (i.e. trowels, shovels, augers,
 corers, etc.) may be used to collect samples for this method.  However, they must have been
 specified in the pre-defined sampling plan based on the nature of the material being sampled
 and the  depths over which  samples are to be  collected.  Whatever sampling technique  is
 employed, the minimum size sample to be collected at each location shall be 1 kg.

 Once collected,  each  sample is brought to a central  location for field preparation.   Field
 preparation steps are listed  in Figure 3-1  arid discussed in  detail in Chapter 8.  Each sample
 is first weighed (Section 8.2.1).  Then the sample is sieved .using  a screen with 3/8th in.
 (1 cm) openings  to separate a coarse and fine fraction.  The material placed  on the sieve is
 worked with  gloved hands  to assure that all friable  components pass through the screen
 (Section 8^2.2).

 The coarse fraction, composed of material that is retained  by the  screen, is transferred to a
 bucket and weighed prior  to discarding on site.  The fine fraction, is  also Weighed.  As
 indicated  in Figure  3-1, the fine fraction is then homogenized.  The procedure recommended
 in this method for hornogenization  is repetitive splitting • using a  riffle splitter with the split
 halves of the sample being re-combined at the end of each  split (Section 8.2.3). Studies
 indicate  that  five  to   seven .iterations  are  typically sufficient  to  achieve  adequate
 hornogenization.                   .

 Once homogenized, the  fine fraction is then sub-sampled using the riffle splitter (Figure 3-1).
 During sub-sampling, the one-half of the sample from one of the two receiving trays  is
 discarded  after each split (Section 8.2.3) and the second half of the sample,  is then re.-split.
 The process is repeated until sub-samples weighing between 50 and 80 g are produced  in
 each of the two receiving trays.  The material in each tray is then transferred quantitatively to
 a sample  bottle, packaged and shipped to the laboratory.

 Sample handling, preparation, and analysis in the laboratory is depicted in Figure 3-2 and
 described  in detail in  Chapter 9.   Once sub-samples weighing between 50 and 80  g are
 obtained, they can be separately prepared and analyzed (Section 9.2).

,To prepare samples, as indicated in 'Figure 3-2, first load  the sample into the tumbler of a
 dust generator.  The design, construction, and operation of a dust generator suitable for use
 with this  method is provided in  appendix A. .The  sample is  then  conditioned  by flowing
 humidity-contrplled  air through the tumbler and  over the sample for several  hours (Section
 9.4.2).        '             '.-•'.                   '          .'..'..

 Once the sample is conditioned, the tumbler of the  dust generator is started and a sample
 run  is initiated  (Section 9.4.3).  During each run, a series of filters is collected continuously
 from the top  of one of the openings of the dust generator and these are weighed to plot the
 cumulative dust loss from the samplex(Section 9.4.4 and the right side pathway of Figure 3-2).
                                          3-1

-------
                               FIGURE 3-1
              SAMPLE COLLECTION AND FIELD PREPARATION
                                SURVEY SITE:
                         IDENTIFY SAMPLING LOCATIONS
                              COLLECT SAMPLES
                                        FOR EACH SAMPLE
                               WEIGH SAMPLE
       FINE FRACTION
       {< 1 CM. DIA.)
SIEVE SAMPLE
COARSE FRACTION
  (> 1 CM. DIA.)
              WEIGH FRACTION
                                            WEIGH FRACTION
                HOMOGENIZE
                                            DISCARD ON SITE
              WEIGH FRACTION
                   SPLIT
DISCARD SPLIT
                              WEIGH SPLIT
                                 SPLIT
              DISCARD SPLIT
                           SUB-SAMPLING
                           REPEAT AS REQUIRED
                           UNTIL FINAL SPLITS
                           WEIGH BETWEEN
                           50 AND 80 G.
                                             WEIGH SPLIT
                           BOTTLE AND LABEL
                            FOR TRANSPORT
                                TO LAB
                          BOTTLE AND LABEL
                           FOR TRANSPORT
                              TO LAB

-------
                          • .    FIGURE 3-2
               LABORATORY PREPARATION AND ANALYSIS
                            RECEIVE SAMPLE FROM
                                .THE FIELD
                         Yes
    HOMOGENIZE
   DOES
  SAMPLE
WEIGH MORE
   THAN
   80G?
    SPLIT SAMPLE
                           LOAD DUST GENERATOR
                             CONDITION SAMPLE
              SCRUBBER
             SUSPENSION
   I
                            RUN DUST GENERATOR
 FILTER SUSPENSION
FILTERS COLLECTED
FOR DUST ANALYSIS
      FILTERS
      COLLECTED
      FOR DIRECT
      ASBESTOS
      ANALYSIS
             PERFORM
            GRAVIMETRY
    PREPARE TEM
   SPECIMEN GRIDS
     PERFORM
    TEM ANALYSIS
                       PLOT CUMULATIVE DUST
                         LOSS FROM SAMPLE
                             ESTIMATE MASS OF
                              DUST ON FILTERS
                                 USED FOR
                             ASBESTOS ANALYSIS
     DETERMINE
 CONCENTRATIONS OF
    SIZE-SPECIFIC
ASBESTOS STRUCTURES
 IN RESPIRABLE DUST
                                                            DETERMINE
                                                        CONCENTRATION OF
                                                        RESPIRABLE DUST IN
                                                             SAMPLE
     DETERMINE
 CONCENTRATIONS OF
,   VSIZE-SPECIFIC
ASBESTOS STRUCTURES
 IN ORIGINAL SAMPLE

-------
 While the dust  generator is  operating, a second set of filters is also collected over the
 opening.of the  dust generator that articulates with  an isokinetic sampling tube (the center
 pathway of Figure 3-2).  These are collected  such that loading  is appropriate for specimen
 grid preparation  using a direct transfer technique (Section 9.4.5).

 Asbestos structures are also trapped in the suspension of a scrubber during each run of the
 dust generator  (the left  side pathway of  Figure 3-2).   The suspension is then  diluted
 appropriately and filtered to create an additional set of filters from which specimen grids will
 be prepared  for asbestos analysis (Section 9.4.6).  However, because asbestos structures
 derived  from this  process will have been suspended in the aqueous environment of the
 scrubber suspension, preparation of grid  specimens from filtered  scrubber suspension are
 considered to have  been prepared  in a  manner that is equivalent to an  indirect transfer
 technique.

 Next, as indicated in  Figure 3-2, TEM specimen grids are prepared using a  direct transfer
 technique  from  the filters collected  either from  atop the isokinetic sampling tube of the
 elutriator or from filtering scrubber suspension  (Sections 10.1  and 10.2).  Specimen grids are
 then  analyzed using  the counting  and  identification  rules  of the International Standards
 Organization  (ISO) Method for the determination of asbestos in air using an indirect transfer
 technique (Chatfield 1993) with the stopping rules modified as indicated in Section  11,1.

 Calculations are  performed from plots of the cumulative dust loss (Section  11.2) to estimate
 both the mass of dust co-collected with asbestos on the filters  prepared for asbestos analysis
 and the total mass  of respirable  dust in the original sample.   Dust  estimates  are  then
 combined  with asbestos counts  to allow  reporting  of both  the concentration of asbestos
 structures per unit mass of respirable dust in the sample and the concentration of asbestos
structures  per  unit  mass  of the  original  sample  (Figure  3-2)7.    Typically,  asbestos
 concentrations will be reported from this method for a specific size  range of asbestos
structures of interest.
      When asbestos concentrations are to be reported as a function of the mass of the original sample, the concentration
      calculated in the laboratory, which represents the concentration of asbestos in the fine fraction of the original >ample,
      must ultimately be adjusted to account for the mass of the coarse fraction of the sample as well (Section 11.4.3).


                                           3-4

-------
                                   4.0 DEFINITIONS
Amphibole:   a group of rock-forming ferromagnesium silicate minerals,  closely related  in
crystal form and composition, and having the nominal formula:
        A0-1B2C5T8022(OH.F'CI)2
where:            -        t                        .   ,

            A = K, Na;   :  .,        "                            '

            B = Fe2+, Mn, Mg, Ca, Na;                                  .     .  .''   '   '   ,
                                   •  .              ,                   j
            C = Al, Cr, Ti,,Fe3+, Mg, Fe2+;

     -       T = Si, Al, Cr, Fe3+, Ti.         !
                                  - ''  .     l              '
In some varieties of  amphibole, these  elements  can be partially substituted by Li, Pb, or Zn.
Amphibole is characterized  by a cross-linked  double chain of Si-O tetrahedra with a silicon:
oxygen  ratio  of  4:11, by columnar  or  fibrous  prismatic crystals and by  good prismatic
cleavage in two directions parallel to the  crystal faces and intersecting at angles of about 56°
and 124° (see Chatfield 1993).  ,

.Amphibole Asbestos: amphibole in an asbestiform habit.

Analytical  Sensitivity:  the  calculated asbestos concentration in soil or a bulk matrix,  in
asbestos structures/g, equivalent to counting of one asbestos structure in the analysis.

Asbestiform:  a specific type of mineral  fibrosity in which the fibers and fibrils possess high
tensile strength and flexibility.              .'  .   -.
                                                        •                  ''"'/-.
Asbestos:  a term applied  to a  group of fibrous silicate minerals that readily separate into'
thin, strong fibers that are flexible, heat resistant and chemically inert.           '       ,

Asbestos Component: a term applied to any individually identifiable asbestos sub-structure
that is part of a larger asbestos structure.                                   ,         .

Asbestos Structure: a term applied to  any contigupus grouping of asbestos fibers, with  or
without equant particles.                                       ,   .   ,               ,

Aspect Ratio:  the ratio of the length to width of a particle. _

Blank:  a fiber count made  on TEEM specimen grids prepared from an unused filter (or a filter
through which' asbestos-free  water  has  been, passed), to  determine  the  background
measurement.  Blanks consist of filter  blanks,  field blanks and laboratory blanks.  Laboratory
blanks for this method .may include  scrubber blanks.

Bundle:  a fiber-composed of parallel, smaller diameter fibers attached  along  their lengths
(see Chatifield 1993).                "            .'                     .
                                          4-1

-------
 Chrysotiie:  the asbestiform  habit of a mineral of the serpentine group that has the nominal
 composition:

                                     Mg3Si205(OH)4

 In some varieties of chrysotiie, the silicon may be partially substituted by Al or less commonly
 by Fe.  The magnesium may be partially substituted by Fe, Ni, Mn or Co.  Some varieties
 contain Na,  Cl or  both.  Chrysotiie is a  highly fibrous and  silky variety and constitutes the
 most prevalent type of asbestos (see Chatfield 1993).

 Cluster:  an assembly of randomly oriented fibers (see Chatfield 1993).

 Component  Count:  for any sample,  a  tally  that includes the individually  identified
 components of  complex asbestos  structures and  each  single asbestos  structure with  no
 identifiable components.

 Elutriator:   a device in which differential flow through  a fluid (gas or liquid) against  an
 opposing force (i.e. gravity) is employed to separate  particles by size.

 Equant Particle: as used in this document, a non-asbestos particle bound to, or overlapping
 with, asbestos structures observed on a TEM specimen grid.

 Fiber:  an elongated  particle that has parallel or stepped sides.  In this method,  a fiber is
 defined to have an  aspect ratio equal to or greater than 5:1  (see Chatfield 1993).

 Fibril:  a single fiber of  asbestos  that cannot be further separated longitudinally  into smaller
 components without losing its fibrous properties or appearance.

 Fibrous Structure: a contiguous grouping of fibers,  with or without equant particles.

 Field Blank:  a filter cassette that has been taken  to the sampling  site,  opened, and then
 closed.  Such a filter is  analyzed  to determine the background asbestos structure count for
 measurement and  to  document the treatment  of the filter from sample  collection through
 analysis.

 Filter  Blank:   an  unused  filter  that is  analyzed to  determine the background asbestos
 structure count on the filter matrix.              .     .   "    ,

 Friable: as used in this  document, capable of being crushed or deformed with the hand with
the attendant release of fibers.

 Habit:  the  characteristic crystal form  or combination  of  forms  of a  mineral, including
characteristic irregularities.                      ,

Identify:  during  asbestos analysis,  the use of a sequential set of procedures to determine
and confirm the mineralogy of  a structure.                                  ...

Isokinetic Sampling:   sampling air in such a manner so as not to  disturb the  direction or
velocity of air flow at the point  sampled.
                                          4-2

-------
Isokinetic Sampling Tube:  a tube placed in the air flow of the vertical elutriator portion of the
dust .generator used in this  method, which samples the air  at  the  top of the  elutriator
isokinetically,                           '.';-

Laboratory Blank:  an unused filter that is analyzed along with sample filters to determine the
background asbestos structure count in the laboratory.
                                                        N
Matrix:8 A connected  assembly of asbestos fibers with particles  of another species (non-
asbestos) (see Chatfield 1993).

PCM. Equivalent  Structure:  A structure of aspect ratio greater than or equal to 3:1, longer
than 5 jim, and which has a mean diameter between 0.2 jim and 3.0 \im for a part of its
length greater than 5 jim.   In this method, PCME structures "also must contain at least one
asbestos component (see Ghatfield 1993).               ,

Riffle Splitter: a device  composed of a hopper and multiple,  uniform, parallel chutes that
alternately feed from the hopper to opposing receiving trays.                               ^

Scrubber:   a device for  removing particles from an  air stream by passing the air  stream
through  a  super-saturated vapor in which  the particles serve as nucleation  centers for
condensation and are thus captured. The resulting droplets (containing the trapped particles)
then fall back into a central reservoir of boiling liquid.

Serpentine: a group of common rock-forming minerals having the nominal formula:

                      .     .  •-  '   Mg3Si205(OH)4                     .       .

Serpentine, deposits often contain chrysotile asbestos  (which is serpentine in an asbestiforrrV
habit).                   ''-.'";•'.

Structure Count:  for any sample, a  tally of each individually  identified  asbestos  structure
regardless of whether the structure contains identifiable components. This is equivalent to> a
count of the total  number of separate asbestos entities  encountered on the  sample.

Vertical Elutriator:  see Elutriator.                                               .
Tumbler: a-device that is rotated to provide continuous agitation to a bulk material placed
inside.   In the  dust  generator  employed Jn this method, air  is blown through a tumbler
containing sample to carry away the dust generated during agitation by the tumbler.
       When used to describe an asbestos structure.  The term is also used in this document to ^describe .a heterogeneous
       bulk solid.                             .           ' ,   .

          '  '•  •          -'.''.    *     4-3    .•     ' '     '        '     .:          ' ,

-------

-------
                         5.0 SYMBOLS AND ABBREVIATIONS
5.1    SYMBOLS

        dust
        smpl


      CF


      cm

      cm2

      cm3

      cm3/min

      d

      DF


      °C

      °K \

      AMf


      AIVL
          o


      At


      T

      eV  '
 the area of a filter from which a specimen grid is prepared (mm ).

 the average area of a specimen grid opening (mm2).

 the concentration of asbestos structures (of a defined size and type) in
 the respirabie dust from a sample (s/gdust).

 the concentration of asbestos structures (of a defined size and type) in
 the original field matrix that was sampled for analysis using this method.

 the concentration of asbestos structures (of a defined size and type) jn a
 soil or bulk sample (s/g).               '

 the coarseness adjustment factor representing the ratio of the mass of
 the fine fraction to the total mass of a matrix that is sampled in the field.

 centimeter (10~2 rneter).

 square centimeter.   ',„'.'.'.      ;

 cubic centimeter.

 cubic centimeter per minute.

 the density of a particle (g/cm3).

 the  dilution factor representing the ratio  of the scrubber suspension
 volume to the aliquot that is filtered to prepare specimen grids.

 degrees centigrade.

 degrees Kelvin.

.the mass of respirabie dust collected on a single filter.during the interval
 At(g).      •                       ,i

 the mass of respirabie dust released from the sample during the interval
 At(g).

 a short time interval (no more than 10 minutes).            •

 the dynamic viscosity of air  (g/cm*s).
                         f             "             -
 electron volt.
                                          5-1

-------
ft
g
    i
g

g/L
g/cm3
hp
k
kg
kV
in
L
L/min
M,
  coarse
M.
  'f
Mf30

Mfine
M
 the .rate of airflow (i.e. the volumetric flow rate) through the top exit (ME)
 opening  of  the elutriator  that  does  not pass  through the  isokinetic
 sampling tube (cm3/s).
 the rate of airflow (i.e. the volumetric flow rate) through the top exit (1ST)
 opening  of the  elutriator that  passes through  the isokinetic  sampling
 tube (cm3/s).
 the rate  of airflow (i.e.  the volumetric flow rate) through the  scrubber
 (cm3/s).
 foot.
 gram.                                     -
 the acceleration  due to gravity (cm/s2), when used as a variable in an
 equation.
 gram per liter.                   ~                   s
 gram per cubic centimeter.
 horsepower.
 the first order rate constant (s~1).
 kilogram (103 gram).
 kilovolt.
 inch.
 liter.,
 liters per minute.
the mass  of the coarse fraction of a matrix sampled in the field.
the 'cumulative  mass of respirable dust collected on filters from the start
of a run to time, t (g).
the cumulative mass of  respirable  dust  collected  on filters during an
entire 30 rpm run (g).
the mass  of the fine fraction of a matrix sampled in the field.
the mass  of respirable dust in a sample at the start of a run (g).
the cumulative  mass of respirable dust released from a sample  from  the
start of a run to time, t (g).
                                    5-2

-------
Ms

Mscrbr
  sample
Mtot
ml
mm
mm2
N
  go
N
 'gon
nm
 t
%RD
r2
 ch
the mass of respirable dust remaining in a sample during a run but after
time, t (g).  ,
the mass of respirable dust collected in the scrubber during a run (g).
the mass of a 'Sample introduced into the dust generator (g).  ,'.
           '           '         -     '     "  /
the total mass of respirable dust estimated to reside in a sample (g).
millimeter (10~3 meters).       .   .   ,   '            ,  .
square millimeter.
microgram (10~6 grams).
micrometer (10"6 meters).
the number of grid openings counted during a scan (#).
the number of grid openings counted during a high magnification scan
(#).
the number of grid openings counted during, a low magnification scan
                 '                            "
nanometer (10~9 meter).
the pressure measured at a flowmeter (torr).
                                        \
the pressure estimated at an elutriator opening (torr).
the mass percent of respirable dust in a sample (%)
the radius of a particle (cm).             ,  '
the  coefficient  of  determination  (also  defined  as  the  correlation
coefficient squared).
the flow reading from a flowmeter (cm/s). ,
the number of asbestos structures  (of a defined size and type) counted
during a high magnification scan (#).       .
the number of asbestos structures  (of a defined size and type) counted
during a low magnification scan (#).
the number of asbestos structures  that must be detected during a TEM
scan for asbestos to be defined as detected (#).
                                   5-3

-------
        smpl
       s

      •S/g
       S/L

       S/mm2

       t

       Tf

       T.
       V.
        a1
      v
      w
 the required analytical sensitivity for this method (defined separately for
 total and long asbestos structures) (s/g).

 second.

 structures per gram.

 structures per gram of dust.

 structures per liter.

 structures per square millimeter.

 time (s).                                          ,
                                                             •-\
 the temperature at a flowmeter (°K).

 the temperature at an exit opening of the elutriator (°K).

 the volume of the first aliquot collected from the scrubber suspension to
 be used for further dilution (ml).

 the volume of the final aliquot collected from Vd, which  is filtered for the
 preparation of specimen grids for TEM analysis (ml).

 the volume into which the first aliquot from the scrubber suspension is
 diluted (ml).

 linear air flow rate (cm/s).

the volume of scrubber suspension generated from a run (ml).

the volumetric air flow rate (cm3/s).

watt.
5.2   ABBREVIATIONS

      ED      -    Electron diffraction

      EDXA   -    Energy dispersive X-ray analysis

      FWHM   -    Full width at half maximum

      HEPA   -    High efficiency particle absolute

      1ST      -    refers to the opening at the top of the elutriator that is associated with
                   the isokinetic sampling tube

      MCE    -    Mixed cellulose ester
                                          5-4

-------
 ME     -    refers to the main exit opening at the top of the elutriator, which is not

             associated with the isokinetic sampling tube



.PCM    -    Phase contrast optical microscopy



 PCME   -    Phase contrast microscopy equivalent



 PLM    -    Polarized light microscopy


 RPM    -    Revolutions per minute     .



 SAED   -    Selected area electron diffraction                          .



 TEM    -    Transmission electron microscopy


 TSP     -    Total suspended particulate
                               "•* r                                 '

 LJ1CC    -    Union Internationale Contre le Cancer
                                    5-5

-------

-------
                           6.0 FACILITIES AND EQUIPMENT


6.1   SAMPLE COLLECTION EQUIPMENT AND CONSUMABLE SUPPLIES

To complete field sampling per this method, the following field equipment is mandatory:

      •    survey equipment appropriate to the manner in which sample locations are to be
           defined per the sampling plan;

      •    appropriate trowels, shovels, augers, or corers for  sample collection  per the
           sampling plan;

      •    (when sampling surface materials) a 12 in square aluminum template with an 8 in
        :   square hole in the center; ;.."••                    L

      •    a minimum of three 3-gal plastic buckets;

      •    a brass or steel sieve with 3/8 in. (1 cm) openings;                        '

      •    a field balance (with a capacity of 40 kg and capable of achieving a precision of
           ± 10 g);

      •    a field  balance (with a capacity of 2 kg and capable of achieving a precision of
           + 0.2g)9                                ,.' .                      ^

      •    a  riffle splitter with  a minimum of 24, 3/4 in. (minimum size) chutes and three
           sample trays;

      •    one L plastic sample containers;                        ;

      •    sufficient plastic coolers to store and ship samples at ice temperature;

      •    equipment for cleaning sampling tools, including:
           -   large buckets and tubs;
   ;        -  , a container of asbestos-free water;                                     >
           -   garden sprayers;                      ,           ,                     ,
           -   bio-degradable detergent;     .                                ,
           -   assorted asbestos-free rags, sponges, etc.;
               an air compressor with HEPA filter (optional, for drying,equipment);      L

      •    field logbook and appropriate custody forms and sample labels;

      •    assorted garbage bags, paper towels, and tape;

      •    Tyvek suits and protective gloves; and                                    x
      If appropriate equipment is available, it is advantageous to use a single field balance to achieve both sets of capacity
      and precision requirements for field weighing.              , ,


         ,   -.      .         .              6-1             ' •    '•  .

-------
       •    appropriate equipment for respiratory protection.

 6.2    LABORATORY FACILITIES

 Laboratories wishing to adopt this method must develop and maintain the following facilities:

       •    a properly ventilated room for bulk sample handling that is entirely isolated from
            other  room(s)  in which  air samples are handled  and asbestos samples are
            analyzed.   All  such  facilities  must be sufficiently  well  ventilated  to  allow
            preparation  of  blanks that yield  background determinations  satisfying the
            requirements of Section 10.6 of the Superfund air method (Chatfield and Berman
            1990);

       •    a glove  box or equivalent isolation chamber of sufficient size to house a riffle
            splitter (or other equipment) required for the homogenization and sub-sampling of
            samples for this  method.  The glove box or  isolation chamber must provide
            ample room for handling  kg  size  soil or bulk  samples  while  maintaining
            background  concentrations  in  the  outside  room  air  at  levels  considered
            acceptable as defined in Section 10.6 of Chatfield and Berman (1990);

       •    a dust generator constructed per the specifications provided in Appendix A;

       •    a TEM operating at an accelerating  potential of 80-120 kV,  with  a resolution
            better  than 1.0 nm  and a magnification range of approximately 300  to 100,000.
            The ability to obtain a direct screen magnification of about 100,000 is necessary
            for inspection  of fiber morphology;  this magnification  may  be  obtained by
            supplementary optical enlargement of the  screen image by use of a binocular if it
            cannot be obtained directly.  The TEM shall also be equipped with an  energy
            dispersive X-ray analyzer  capable of achieving  a  resolution better than  175 eV
            (FWHM)  on the MnKa  peak.  For requirements concerning screen calibration and
            SAED and ED performance, see  Chatfield and Berman (1990); and

       •     a computer  system  for recording  analytical  results.  As indicated in  the section
            addressing reporting requirements (see Chapter 13), analytical results are to be
            provided on computer disk (either 3.5 inch or 5.25  inch in double sided or  high
            density format)  in a file format that is compatible with LOTUS™. ASCII files are
            acceptable.

6.3    THE DUST GENERATOR AND APPURTENANT EQUIPMENT

The dust generator is to be constructed per the design drawings and specifications provided
in Appendix A.  Appurtenant equipment required to support the dust generator includes:

            a 129 hp DC motor (rated for 0 to 139 rpm) to drive the tumbler;

       •    two vacuum pumps  capable of drawing 20 L/min at minimum load (will be run at
            1 to 2 L/min);                                                '
                                         6-2

-------
       •    two variable area flowmeters capable of reading volumetric airflow velocities up to
   	1500 ml/min and one variable  area flowmeter capable of  reading airflow up to
   ,         250 ml/min;        : .         u          "'  '   '      '

       •    a heating  mantle and variable voltage transformer suitable for maintaining water
            at a boil in, a 1  L round bottom flask; and

       •    an immersion  pump and cooler (or equivalent system) of sufficient capacity to
            provide 0° C water at a rate of 1 -to 2 L/min.

6.4    SPECIMEN PREPARATION EQUIPMENT

As  defined  in the ISO Method for  the  determination  pf  asbestos in  air using an indirect
transfer technique (Chatfield 1993).  .                          ,             .

6.5    OTHER LABORATORY EQUIPMENT

As  defined  in the ISO Method for  the  determination  of  asbestos in  air using an indirect
transfer technique (Chatfield 1993).

6.6    CONSUMABLE/REUSABLE LABORATORY SUPPLIES

For each run of a sample using the dust generator:

       •    a lot of fifty MCE filters (0.45 urn  pore size, 25 mm) that  exhibit no more than
            10 s/mm2 asbestos as background  ; and

       •    forty plastic petri dishes for storing  25 mm filters.       ,

Also, other items as defined in the ISO Method for the determination of asbestos in air using
an indirect transfer'technique (Chatfield 1993)11.
  .10  -This 'value is selected to assure that detection of a single structure in 4 grid, openings is more likely than not to
      constitute asbestos from a samp.le.     ,    • ,   .                      ,     .
  ,11
      This includes a supply of MCE filters (0.22 /im pore size) for filtering scrubber suspension.

-------

-------
                                      7.0  REAGENTS
To support use of the dust generator, the following reagents are required:

       •    asbestos-free water (a regular supply of freshly distilled, filtered water must be
            available);

       •    potassium carbonate dihydrate (analytical grade)12; and

       •    sodium hexametaphosphate (analytical grade).

Also, reagents required  to support asbestos  analysis are defined in the ISO Method for the
determination of asbestos in air using an indirect transfer technique (Chatfield 1993).

WARNING - USE ALL REAGENTS IN ACCORDANCE WITH THE APPROPRIATE HEALTH
AND SAFETY REGULATIONS.
       This salt is required for loading, into the constant humidity chamber and the desiccators to be used for conditioning
       filters under the recommended default conditions for running the dust generator. A supply of alternate salt (analytical
       grade) may be employed for studies in which dust generation is to be performed at a relative humidity other than the
       default recommendation (see Section 9.3.2).                '       •


         '    '.-  '       "'            •   •      7-1

-------

-------
                        8.0 SOIL OR BULK SAMPLE COLLECTION
Sample collection procedures adopted for this method are flexible to allow adequate sampling
of a broad variety of matrices. The method also incorporates several,field preparation steps.
that are designed to preserve sample  representativeness while reducing  the mass of the
samples sent to a laboratory for analysis.  Controlling  the mass  of the samples sent to a
laboratory from the field is a cost saving  measure (see Section 8.2).

       WARNING:

       MOST OF THE SAMPLE COLLECTION  PROCEDURES AND FIELD PREPARATION
       PROCEDURES  DISCUSSED  IN  THIS   DOCUMENT ARE  INHERENTLY  DUSTY
       OPERATIONS.   THEREFORE, WHEN HANDLING  SOILS OR  BULK MATERIALS
       THAT ARE  KNOWN TO CONTAIN OR POTENTIALLY CONTAIN ASBESTOS, IT IS
       IMPERATIVE  THAT  PROPER  RESPIRATORY  PROTECTION  BE  WORN  WHILE
       CONDUCTING THESE PROCEDURES.

8.1    SAMPLE COLLECTION

Any variety of commercially available field sampling equipment  (trowels,  shovels,  augers,
corers, etc.)  may toe  used  to  collect samples for this  method.   The  equipment and
procedure(s) selected should be based  on the nature of the material being  sampled  and the
depths over which samples are to  be collected.   Two common examples are  presented
belpw.,   Whatever  equipment  and  procedures  are chosen,  however,  shall  be  applied
consistently and invariably at each sampling location13.

Whatever technique  is  chosen, the  minimum size sample  that shall  be collected at each
sampling  location shall  be 1 kg.  Larger samples may be  required, however,   if particularly
large (i.e. larger  than a 4 or 5 cm in diameter) rocks or debris are. present in the  material
being  sampled.   To assure representativeness, the largest component  sampled  should
occupy no more than a few percent  of  the volume of the  sample  collected (Section  2.3).  If
samples are to be composited (Section  8.2), they shall be of similar mass (i.e. differences in
mass between composited samples shall be no  larger than 10% of the mass of the smallest
sample).  (                                                  '
       Locations from which soil or bulk samples are to be collected shall be selected formally as part of a comprehensive
       strategythat is designed to provide a representative (unbiased) set of measurements for characterizing the releases of
       asbestos from the entire source matrix of interest. Procedures for designing such a strategy are beyond the scope of
       this document but are available elsewhere (see, for example, Berman and Chesson undated).

       It is particularly critical, when collecting samples for soil or bulk asbestos analysis, to minimize field decisions that might
       alter the locations for sample collection that have been selected as part of a formal strategy. Such .locations should be
      • representative of the variation of all characteristics of the  sampled matrix that might affect asbestos release.  It is
       inappropriate, for example, to adjust the location of a sample just because a large rock happens to be located within
       the footprint over which the sample is supposed to be collected; the presence of-that rock as part of that sample helps
       to represent the fraction of the surface of the sampled matrix from which asbestos release cannot occur.

       When used,to represent the central characteristics of a large matrix, random or systematic sampling schemes depend
       on faithfully preserving the consequences associated with the choice of each, sampling location. In general, therefore, it
       is not appropriate to alter the selected locations even if collection of a sample at a specific location is impossible.,
       Rather than altering, such a location, any difficulties or  interference that may  hinder sample collection at a defined
       location shall be noted in detail in the field log book.


                                            8-1

-------
All sampling  equipment  shall be washed thoroughly  with  water and  detergent between
collection of each sample.  Sampling equipment shalj then be rinsed thoroughly with filtered,
distilled water and allowed to air dry.  Forced air may be used to expedite drying. If forced air
is to be  used to facilitate drying, however, such air must be  passed through a HEPA filter to
prevent delivery of any potential contamination.

Record the identification number, the date, time, and method of collection for each sample in
a field notebook.  Record the. locations from which each sample is  collected in the field
notebook.  Note in the logbook any changes between the sampling locations proposed in the
sampling strategy and the actual  locations sampled. As indicated previously, such changes
are to be  avoided  to  the extent possible.  If changes  are absolutely necessary,  clearly
document the rationale behind each change.

Supplement written  documentation with  photographs  of  each sampling  location.  This is
particularly  important if the sampling locations are  not laid  out on a formal, documented
sampling grid that is tied to a permanent field marker.

       8.1.1     Sampling to  Derive  Estimates of  Asbestos Concentrations in a  Road
                Surface
To illustrate the important features of sampling for this method, assume that sampling is to be
performed to determine  the concentration of releasable asbestos  in the  material of a
serpentine-covered road.  In this case, it is assumed that measured asbestos concentrations
are to be related to current emissions so that it is only the actual surface layer of the road
that is of interest.

Sampling a road  surface shall be conducted using a metal template to define the bounds of
each  sample and a trowel (or other digging device) to  remove material within the template to
a  uniform  depth  of 0.5 in.  (approximately 1.5 cm).  To assure that the  samples  collected
exceed 1  kg in mass  (assuming a density for unconsolidated serpentine  of 2.2 g/cm3), the
sample volume should be a minimum of 450 cm3 (28 in3). Assuming, as indicated above, that
each  sample will  be excavated to a uniform depth of 0.5 in., an 8 in. square hole in a 12 in.
aluminum template works  well.

At each selected  sampling location, center the template on the  defined location and press it
firmly against the .ground surface.  Carefully excavate  the material within  the  template to a
uniform depth of  0.5 in. and place the material in  a clean, pre-weighed  bucket (see Section
8.2.1 )14.  Transport the sample to  a central  location on the  site where field preparation
(Section 8.2) will be performed.                         ,
       8.1.2     Sampling   a  Mine  Tailings  Pile  to  Derive  Estimates
                Concentrations Within the Pile
of  Asbestos
As a second illustration of sampling to support this method, assume that sampling is to be
performed to determine the concentration of releasable asbestos in the material of a mine
       Depending on conditions encountered, it may be necessary to remove surface debris (such as leaves or foreign dust)
       from an area prior to sampling.  The determination as to whether or to what extent surface debris needs to be removed
       prior to sampling should be based on careful  inspection of the sampling location and review of the motivation for"
       sampling. Surface debris should generally nof  be removed unless such material is clearly distinguished visually from
       the matrix material to be sampled.


                                          8-2

-------
 tailings pile.  Assume further that the  goal  is to predict long-term emissions from the pile
 based on  the asbestos concentrations measured.   In this case,  it  is the concentration  of
 asbestos within the volume of the entire pile that is of interest.

 For the assumed tailings pile, conduct sampling  using a hand auger (if the pile, is no thicker
 than -a few feet) or a power auger or other drilling equipment (if the pile is significantly thicker
 than a,few feet).  A coring cylinder that is 12 in. long and 2 in. in  diameter (assuming an
 average  density for 'the, pile material of 2.2 g/cm3) yields a sample of approximately 1.4 kg.
 Such a cylinder shall  be collected from  each location (defined in 3-dimensions: longitude,
 latitude, and depth) that is selected for sampling within the pile.

 Cores  shall be driven  until their mid-point overlies the proposed sampling location.  Collect
 the core carefully from each selected location, being sure that the entire core is extracted
 from the pile.   Transport the sample to a central location on the site where field preparation
 (Section  8.2) will be performed.

 8.2    FIELD PREPARATION

 Although the following activities might conceivably be conducted in the laboratory (following
 collection and shipment of kg  size samples), to minimize the mass  of samples sent to the
 laboratory and thereby reduce costs, the following field preparation  activities are incorporated
 into this method. For special cases, assuming that the laboratory of choice has access to the
 required  equipment in  the required protective enclosures, these activities  may be  conducted
 in the laboratory rather than in the field.

 Per the instructions in the following sections,  samples that are collected as defined in Section
 8.1 are to be:        ,    ._-'.'-.    ...  .       '-  .

        •     weighed;                           '

        •     sieved to separate a coarse and fine fraction;

        •     the coarse and fine fractions are to be weighed;

        •     the fine fraction is to be homogenized and split; and

        •     each of the  two  final  sub-sample splits of the .fine  fraction are to  be weighed,
             packaged, and shipped to the laboratory (as paired duplicates).

        8.2.1    Weighing                                             .

 As indicated in Section 8.1,, samples shall be'transported in clean, pre-weighed buckets'from
•the locations at which they were collected to  a central location for field preparation. The first
 step of the  process shall  be to weigh each'sample.

 Kg size samples are to, be  weighed using  a field  scale  capable of reading mass with  a
 minimum precision of ± 10 g.  If necessary, wipe the outside surface of each sample bucket
 with a clean, dry (asbestos free) cloth before  placing it on the  scale (Figure 8-1).  Record the
 mass measured for each sample (along  with its identification number)  in a field notebook and
 subtract the tare weight of the bucket to derive the net weight of the  sample.           .
                                           8-3

-------
                                FIGURE 8-1

                 WEIGHING A SOIL SAMPLE ON A FIELD SCALE
 Bucket for
Fine Fraction

-------
Following size reduction (Section 8.2.2), both the coarse  and fine fractions of each sample
are to be. weighed agajn. If necessary, wipe the outside surfaces of the buckets containing
each size fraction with a clean,  dry (asbestos free) cloth  before placing  it on the scale..
Record the  measured  weight for each fraction in the field notebook  under the  appropriate
sample identification number.  Subtract the tare weight of each bucket holding, respectively,
the coarse and fine fractions from the sample and record the net weights of each in the field
notebook.

'Following homogenization and splitting (Section 8.2.3), sub-samples that are to be sent to the
laboratory are to be weighed yet again. In this case, sample weights  are expected to range
between approximately 50 and 80 g (see Section  9.1) and  will need  to be measured on a
scale that  can achieve a precision of ±  0.2 g..   Depending on the types of equipment
available to' the sampling team, this may or may  not be the same scale that  is used  for
weighing the initial (heavier) samples.  When sending 50 to 80 g splits to the laboratory, both
halves of the final sample split shall be sent to the laboratory as a duplicate pair.             ,
                         '                     r " •• '
Wipe the outside surface of each sample container  with  a  clean,.dry (asbestos free) cloth
before placing  it  on the scale.  Record the  weight,  identification  number, and  pedigree of
each sample split of each duplicate pair sent to the  laboratory in the field notebook (Figure
8:2).  Subtract the tare  weight of each sample container from each sample and record the net
weight  of each sample in  the field notebook next to the appropriate  sample identifier.
Package and send each sample to the laboratory as described in Section 8.4.

       8.2.2    Size Reduction

After collection and the initial weighing {described above), pass each sample through a clean,
wire-mesh sieve with 1 cm (3/8th  in) openings. Reduce all clods and soft aggregates  by
hand and force all reducible material through the sieve  into a clean, pre-weighed bucket
(Figure 8-3),  Stones and debris retained  by the  sieve that cannot be hand crushed shall  be
placed in a separate pre-weighed bucket.  Once separated, the coarse and fine fractions from
each sample are to be weighed  separately (Section,8.2.1).

Clean the sieve with detergent  and rinse with filtered, distilled water between samples.  Dry
the sieve with an asbestos free  cloth or with appropriately filtered, forced air before each use.

       8.2,3    Sample Homogenization and Splitting

The fine fraction  of samples collected for this method may be homogenized and split  by
either of two procedures.:                              '  ..            ,
                                          8-5

-------
                  FIGURE 8-2
   WEIGHING A SAMPLE SPLIT ON A FIELD SCALE
Scale  ,
Sample Container

-------
'\;'^li^                                        *  '•'1''<';'^:^°'"".»{*<*9J^                            -,-  ',/S*:*"," "r J   ° \<   (-xV  -'""
> T %'"/^ V /'' ?' ^ * *»+ ^^ ^  "?** ^ i'Hj>0" "*• ^   <'    ^ •* "-   ^ * J ^ ^ «* > ^  < ^ \ ^Cs *v s t'^  '_, * " '  ^ < °^/   T ».„ "   *^s *f * y*  j. •SI>''   ^}  ^/J? , f   *"" >     f  ** '           < '
x^ *<^>j*^ J*^ ^f (> *4j^lv A ' W*}*  ^    "  ?*« ^"'* '^^  * ^^ <. V \>* ^s* ^^ss cj.^.^^  , tj ^  ^ '•> %" ^ .A"  ^    -,^y N >J >  V0< o '^'o'* '     " "^^  -~    «  *  /  ^ v/t    '<


-------
        Option  1:  use of a  riffle splitter15.   Set a clean, dry riffle splitter with  3/4 to  1.in.
 chutes (Figure 8-4) on its stand on flat ground and place two receiving trays under the splitter
 so that they will each catch material that falls through one of the two sets of chutes  (Figure
 8-5).  Place the sample to be homogenized in a third splitter tray (which  must be clean and
 dry).  Shake the splitter tray  gently,  until the sample is evenly distributed within the entire tray.

 Place the long lip of the tray containing the sample against the  inside of the long lip of the
 splitter hopper and slowly rotate the tray along an access defined by its lip so that the sample
 slowly empties into the splitter and slides down  the  near wall of the  hopper to the  chutes
 (Figure 8-5).   Continue to rotate the  tray  until it lies entirely inverted over the top of the
 hopper of the splitter.                •

 Tap the tray vigorously several times to free any remaining material  and remove the emptied
 tray from  the  splitter.  Tap  the splitter vigorously several times to facilitate the flow of  all
 material through  the chutes into the  receiving trays.   If necessary, any sample remaining
 along any of the soldered corners and  nooks of the splitter may be freed with a clean, coarse
 nylon brush. When brushing is completed, tap the brush vigorously against the splitter wall
 to  free  any material clinging to  the brush .  . Remove the  two  receiving  trays (each
 containing-half of the sample) from the  splitter.

 What is to be done next depends on whether the goal is to homogenize the sample or to split
 the sample. If the sample is in the process of being homogenized, combine the half of the
 sample from each receiving tray back into the third tray from the splitter.  Be sure to tap each
 tray vigorously to assure quantitative transfer of the sample material.  Replace the two empty
 receiving trays under the splitter and repeat the process of splitting the sample (in the manner
 described  above).  The  sample should be subjected  to a minimum of five cycles to assure
 adequate homogenization.

 If the  goal  is to split (rather than homogenize) the sample, pour the material in one of the
 receiving  trays  from the'splitter into a spare bucket  and tap the tray vigorously to assure
 quantitative transfer.  The remaining tray that still contains sample material now becomes the
 new sample tray  and the original  sample  tray  (now  empty), along with the  just  emptied
 receiving tray, should be placed under the splitter as the new receiving trays.

 Repeat the process of dispersing the remaining sample material (containing  half the  mass  of
the original sample) by shaking the sample tray so that it is uniformly distributed.  Repeat the
procedure described above for splitting the sample,  discarding the material in one of the two
receiving trays each time, until the mass.of the material in each receiving tray at the end  of
one cycle falls  in the range of 50 to 80 g.  At that point,  carefully transfer the material from
   15
  16
Results obtained as part of the pilot study for this method (Berman and Kolk 1994) suggest that some respirable dust
may be lost each time a sample is passed through a riffle splitter. If the process is conducted carefully, however, such
loss may be kept sufficiently small so that the multiple passes required to homogenize and split a sample properly will
not significantly alter the estimated concentration of dust and asbestos derived using this method; losses should be" less
than an absolute maximum of 10 to 15% of the total respirable dust in the sample after as many as 10 passes.  Because
the estimate of the magnitude of loss was necessarily based on measurements of samples that had to be suspended in
water, however, actual losses for most cases are expected to be much smaller.

One important consideration: avoid using the splitter in the field  on windy days (i.e. when wind velocities exceed
approximately 5 mph) unless an effective wind screen can be devised.


The brush will have to be washed, rinsed, and dried thoroughly before use on another sample.


                                    .  8-8

-------

-------
                            FIGURE 8-5

    USING A RIFFLE SPLITTER TO HOMOGENIZE/SPLIT SAMPLES
  ,,   t    '  - x  •-  >
JJ* ,*s' i **»""   *•   •••*.•



^«,«»,„-'*', cf*t^>Hf fe.«
; *'. Aj-.^-lifTs ' a?.. V WC^^^M^^ *%^>i
              SaropteTray'   Receiving Trays     Splitter Hopper    'Splitter Stand

-------
each tray into a clean, pre-weighed sample bottle (Figure 8-6) to be^weighed (Section 8.2.1)
and packaged for shipment to  the  laboratory  (Section 8.4).   Be sure that  samples are
transferred quantitatively from each tray.    h             "
       NOTE

       NEVER MAKE A PARTIAL TRANSFER OF MATERIAL FROM A SPLITTER TRAY TO
       A  RECEIVING  CONTAINER.    THIS  WOULD, J3EFEAT  THE  PURPOSE  FOR
       HOMOGENIZATION AND SPLITTING BECAUSE IT IS IMPOSSIBLE TO  ASSURE
       THAT ALL OF THE SIZE COMPONENTS OF THE SAMPLE ARE TRANSFERRED
       PROPORTIONALLY UNDER SUCH CIRCUMSTANCES.
Clean the body of the spijtter, all trays, and any appurtenant equipment (such as a nylon
brush) between samples (but not between splits of the same sample) with a detergent wash
followed by thorough rinsing with distilled, filtered water.  Be sure that the splitter, trays,  and
appurtenant equipment are completely dry before use.  These may ,be  dried with forced air
that is properly filtered to be free of asbestos.          ,

      Option 2: Use  of  a mixer with coning and  quartering.   Samples may  also be
homogenized  for this  method using any of various sealed, rotating  mixers (tumblers).   The
mixers should contain internal.baffles to promote mixing.  Such mixers must be sufficiently
large  to accommodate the  largest sample to be homogenized17 with adequate room to
spare so that tumbling is facilitated. The mixers must be sealable to prevent the loss of fines
during mixing.           v
Place the fine fraction of the sample to be homogenized in a clean, dry mixer.  Seal the mixer.
Tumble  the mixer  at  the manufacturers  recommended speed for  an  amount  of time
recommended by the manufacturer to assure adequate homogenization.  Stop the mjxer and
allow ample time (approximately 15  minutes) for the fines to settle.  Disconnect the mixing
container from the rest of the mixer.  Open the mixer.

Under this option, a procedure termed coning and quartering is used to split a homogenized
sample.  Lay out a clean, aluminum  plate on  a flat surface.  Hold the mixer immediately over
the center of the plat? and rotate the mixer around an axis represented by the lip on one side
.of its  mouth  so that the sample material slowly  pours onto the metal plate  forming  a
symmetrical cone (Figure 8-7).  Keep the point at which the poured material impacts the cone
at the same spot and slowly'raise the mixer  as the pouring  continues to keep the distance
between the mixer lip and the top of the cone, approximately constant.  When the mixer  is
fully inverted, tap it vigorously to complete the quantitative transfer.    .        • -,

To halve the cone,  hold a second  (clean, dry) aluminum plate directly over the apex (top
center) of the cone at an angle that is perpendicular to the aluminum plate on  which the cone.
lies.  Slowly lower the second plate  so  .that it splits the cone precisely  in half (Figure 8-8a).
While holding  the two plates steady, push  one half  of trie cone off of the original plate and
away from the rest of the  sample (Figure 8-8b).  Brush the area from which  this  material  is
       If samples are to be composited as described in Section 8.3, the mixer may have to be capable of handling samples
       that range up 40 kg in size.                                       •

       •'•'"•      • -        /      '    8-11

-------
                  FIGURE 8-6

LOADING A SAMPLE SPLIT INTO A SAMPLE BOTTLE
Scale
                            Bottle  >    -Receiving Trays    '- Rittte Splitter1 x-
                                ,T ~*  » Frorp>Splitter - "           <* "

-------
                           FIGURE 8-7

          TRANSFERING SAMPLE FROM A MIXER TO A PLATE
                  FOR CONING AND QUARTERING
                      Mixer
  Slowly
Increase
    Tilt
Keep This Distance Small
and Constant

-------
                            FIGURE 8-8

                     CONING AND QUARTERING
       Slow  1
       Steady 1
       Motion
                                                            Aluminum" Plates
A. POSITION OF ALUMINUM PLATES IN PREPRATION FOR HALVING SAMPLE
                                                     Remove All Material
                                                     From This Side of
                                                     Vertical Plate
     B. POSITION OF ALUMINUM PLATES AFTER HALVING SAMPLE

-------
removed  to complete a  quantitative transfer, leaving only clean metal.  Once half of the
sample material has been removed, withdraw the vertical aluminum plate slowly by pulling it
upward vertically.

To complete'quartering of the cone, rotate the vertical aluminum plate above the cone 90° on
a vertical  axis.  Lower the plate slowly once again so that it splits the remaining portion of the
sample cone-evenly into two  new halves.  Once again, quantitatively remove half of the
sample material (i.e. remove all of the material from one side of the vertical  plate).   This
process may be repeated by quantitatively transferring the remaining  sample material into a
clean bucket and pouring the sample onto the clean aluminum plate to form a new cone.

Repeat the coning and quartering process  until the remaining quarters  (or halves) of the
sample at the end  of one  cycle falls in the range of 50 to 80 g.  At that point, carefully transfer
the materialfrom each quarter (or half) into a clean, pre-weighed sample bottle to be weighed
(Section 8.2.1) and packaged for, shipment to the laboratory (Section 8.4).

      NOTE

      NEVER  MAKE A  PARTIAL TRANSFER OF  MATERIAL FROM  ANY PORTION OF
      THE CONE THAT  DOES NOT INCLUDE A WEDGED-SHAPE SLICE THROUGH  THE
      CENTER OF THE  CONE OVER ITS ENTIRE THICKNESS (DEPTH).  THIS WOULD
      DEFEAT THE PURPOSE FOR FORMAL CONING AND QUARTERING BECAUSE IT
      IS  IMPOSSIBLE TO ASSURE  THAT ALL OF  THE  SIZE COMPONENTS,  WHICH
      WILL WOT BE HOMOGENEOUSLY DISTRIBUTED VERTICALLY THROUGHOUT  THE
      CONE OF THE SAMPLE, ARE TRANSFERRED PROPORTIONALLY.
8.3   COMPOSITING SAMPLES (OPTIONAL)

In  many  cases,  there may be  interest in limiting the  number of analyses required to
characterize a matrix that serves as a potential source without sacrificing representativeness.
One procedure that may be employed for this purpose is to composite  samples in the field.
Note however, while compositing can reduce the cost of analysis by reducing the number of
samples requiring analysis, also  lost is information concerning the  spatial variability of the
sampled  matrix.   Therefore,.' if  such  information is desired  for  any  particular reason,
compositing is not recommended.                                               -

Only minor adjustments to the field preparation  procedures described above are required to
incorporate compositing into this method.  First, during planning, group the samples to be
collected in the field into sets that are to be  composited. For example, there may be a desire
to  combine all samples from the eastern  part of a road into a composite representing trie east
end of the road.  Similarly, samples from the west end might be combined into a west end
composite.  Alternately, all samples from the road may be combined  into a.single composite,
representing the road as a whole.  As another alternative,  the composite road  sample might
also be split into duplicate pairs to allow determination the variability contributed by sample
preparation and analysis:  Such decisions shall all be determined during planning.
                                       8-15

-------
       NOTE

       It is expected  that the same  set of locations will  be selected for sample collection
       whether or not compositing is employed; compositing only changes the number of
       analyses required.  This is because, the same number of samples collected from a set
       of locations selected using the same formal procedures are still required to adequately
       characterize the sampled matrix, whether  or  not  samples are  composited  prior to
       analysis.


When  brought to the central location where field preparation is conducted, after the initial
weighing, the  samples collected from a set that is to be composited can be combined in a
common bucket.  Modify the procedures described in Sections 8.2.1 and 8.2.2 as follows:

       •    transport each sample (of a set to be composited) from the point of collection to
           a central location in a clean bucket;


       •    weigh  the sample  and  record the  weight  along  with  the  appropriate  sample
           identifier.  Subtract the tare weight of the bucket and record the net weight of the
           sample;

       •    sieve the sample and collect the  fine fraction from each sample in the set to be
           composited in a  common bucket.   Weigh  the  bucket containing the fines
           following the  addition  of the  contributions of  each  sample and  subtract  the
           previous weight  of the  bucket  to determine the net weight contributed by each
           sample. Record the weight with the proper identifier in the field notebook; and

       •    transfer the coarse fraction from  each sample in the set to be composited to a
           common bucket.  Weigh the bucket containing the  coarse fraction  following the
           addition of the contributions from each sample and  subtract the previous weight
           of the  bucket to determine the net weight contributed by each sample.  Record
           the weight of  the coarse fraction with the proper sample  identifier in the field
           notebook.

Once all the samples  of  the set to  be composited  have been collected and added, the
combined fine fraction from all of the samples (which  resides in a common bucket) shall be
given a separate identifier  representing the  intended composite.  Record  the new identifier in
the field notebook.  This material can now be treated as a single,  composite sample for all
remaining steps of field preparation and sample handling, packaging, and shipment to the
laboratory.   Thus, homogenize and  split  the sample as  described in Section 8.2.3  and
package  and ship the sample to the laboratory as  described  in Section 8.4.   Record the
appropriate weights of the samples to  be shipped as described in Section 8.2.1.

8.4   SAMPLE HANDLING AND SHIPMENT

Once their weights and identifiers are recorded, the samples to be shipped to the laboratory
must be  sealed and labeled.  Fill out and apply appropriate labels to  each sample bottle.
Record the date and  time that each sample was created on .both the label and the field
notebook and be sure that the identification  numbers on the label and field notebook match.
                                        8-16

-------
Fill out the appropriate chain of custody forms and seal each-sample cap with a breakaway
label,   .As indicated in  Section 12.2, be sure to complete the field activities report and to
include this report in the package with samples sent to the laboratory.

Wipe each sample to be shipped to the"laboratory with a clean,  asbestos-free cloth and place
it in  a cooler.  'Ship samples to the laboratory  in a cooler with ice to limit biological growth
during  shipment.  Sufficient ice must be provided to assure that samples remain cold until
received and processed by the  laboratory. .                    '
      NOTE

      When matrices that are sampled contain a significant fraction  of.coarse material (i.e.
      more than 10% by mass), the final determination of the concentration of asbestos in
      that matrix must be adjusted to account for the fraction  of coarse material./  This
      requires determining the ratio of the mass of fine material in the sampled matrix to the
      total  mass of material in the sampled  matrix to generate a "coarseness  adjustment
      factor". The  concentration of asbestos  determined for samples sent to the laboratory
      must .then be  multiplied  by this  coarseness  adjustment factor  to determine the
      concentration of. asbestos in the sampled matrix.
                         "             .         '-         *•(•'      •          '
      Equations for deriving and using the coarseness  adjustment  factor, are provided  in
      Section; 11.4.3.  The weights  of the  coarse and fine fractions of each sample are to be
      included (along with the  appropriate sample identifiers) as part of the field  activities
      report that is to be shipped, with the sample to the laboratory (Section 12.2).  This
      assures that individuals  responsible for estimating the concentration of asbestos for
      the project have access to the required field information.
                                         8-17

-------

-------
                   9.0  SAMPLE PREPARATION BY DUST GENERATION
 The  primary  purpose for sample  preparation by  dust  generation that is  described  in this
 section  is to generate dust-laden filters that can be suitably  prepared for analysis  by an
 appropriate method for the determination  of asbestos  in air8.  The  rate of generation  of
.total respirable dust  is  also monitored and is used- both to  estimate the total  mass  of
 respirable dust in the original sample and to tie asbestos structure concentrations determined
 from filters-to the mass of the original sample. Such information might also be used in some
 studies  to characterize  the releasibility of asbestos (or total dust) from particular sample
 types.                                     '

 A detailed description of the apparatus  employed for dust  generation  and its theory  of
 operation is  provided in  Appendix A.  Specifications•., and  construction drawings  are  also
 provided.

 9.1    SAMPLE RECEIVING AND STORAGE
          I     ,                        '                 '.•-•"<        '          "
 All samples received from the field are to be wiped Clean with a damp  cloth prior to storage
 or other handling.  Samples shall be stored at ice temperature (to minimize biological growth)
 until sample preparation is initiated. To minimize complications from biological'agents, once
 initiated,  sample  preparation  shall  be  completed  expeditiously.   In any case, sample
 preparation shall  be completed within 48 hours.

 Samples to be prepared using the dust generator are to be inspected for the presence  of free
 water. If a sample  contains free water or if the sample appears visibly moist, it shall  be dried
 at low temperature.  If time permits, place the sample in an open, shallow container and store
 it for several days in a desiccator containing moist  potassium carbonate dihydrate or another
 salt that  corresponds to the salt selected for humidity control (see Section 9.3.2). The type of
 salt placed in  the desiccator is chosen deliberately; rather than to dry the sample completely,
 the goal is to bring the moisture content of the  sample into equilibrium with conditions that
 Will prevail in the dust generator.

 If sufficient time is not available to dry the sample  in a desiccator, the  sample may  be oven
 dried. Dry the  sample  in an  open, shallow container  in an  oven that is maintained at a
 temperature .below  60° C until the sample  comes to constant weight.  Note that  oven-dried
 samples  may  require additional time for conditioning (Section  9.4.2) because the  moisture"
 content  of the sample will need to be increased to bring it into equilibrium with  conditions
 prevailing in the dust generator.

 Once dry, samples smaller than 80 g can be loaded directly into the tumbler of the dust
 generator (Section  9.4.1).  Larger samples  must be homogenized and  split, as described  in
 Section 9.2, prior to being placed in the tumbler of the dust generator.
   18
       The ISO method for the determination of asbestos in air (using either an .indirect or a. direct filter preparation technique -
       - Chatfield 1993) is the default method recommended for use in tandem with this method.


               '".''-     .  -  '        9-1                                  -

-------
 9.2   SAMPLE HOMOGENIZATION AND SPLITTING IN THE LABORATORY

 Samples received from the field that are larger than approximately 80 g must be dried, as
 described above, and then homogenized and split as described in this section.

      WARNING:

      BECAUSE  ASBESTOS  CONTAINING  DUSTS MAY BE GENERATED FROM THE
      HANDLING AND PREPARATION  OF BULK SAMPLES, ALL OF THE FOLLOWING
      PREPARATION  STEPS  SHALL BE PERFORMED IN A PROTECTIVE ENCLOSURE
      (I.E. A HEPA FILTERED GLOVE  BOX OR AN APPROVED FUME HOOD THAT IS
      DESIGNED TO  MINIMIZE EXPOSURE TO LABORATORY PERSONNEL19).  IT IS
      ALSO NECESSARY THAT ALL HANDLING OF BULK SAMPLES BE CONDUCTED IN
      A SEPARATE ROOM THAT IS  PHYSICALLY ISOLATED FROM THE ROOM(S) IN
      WHICH  AIR  SAMPLES  ARE  HANDLED  AND   ASBESTOS  ANALYSIS  IS
      PERFORMED.

As with field  homogenization and splitting (Section 8.2.3), either of two options may be
selected  for  homogenization and  splitting  in the  laboratory.   When performed  in the
laboratory, however, such equipment must fit within an  appropriately designed,  protective
enclosure, which is why field preparation may.be cost-effective.

Homogenize large samples in  precisely  the same manner as described in Section 8.2.3.
Once samples are homogenized, split samples in precisely the same manner as described in
Section 8.2.3.  Continue splitting until a paired set of samples are produced that each contain
between  50 and 80 g  of material.  Record in a laboratory notebook'the final weights and
identifipation numbers of the samples homogenized and split.

9.3   DUST GENERATOR SETUP

Prior to using the dust generator, a supply of at least 35 MCE filters  must be conditioned and
stored .for use, the constant humidity chamber must be loaded with the appropriate solution,
the scrubber must be primed, and air flow within the dust generator must be calibrated and
adjusted.

     . 9.3.1     Conditioning a Stock of Filters

A stock of at least 35 filters (0.45 jim pore size, 25 mm diameter), all from the same filter'lot,
must be conditioned in a desiccator overnight to bring them into equilibrium with the relative
humidity at which they will be used during  a run.  Place the 35 MCE filters in a desiccator
containing moist salt of the same variety as  that selected to fill the pans in the humidity
control chamber of the dust generator (Section 9.3.2).  For most applications, this will be
potassium carbonate dihydrate (see Appendix A).
      The work should be performed in a Class II biohazard hood as per the specifications of Standard #49 of the National
      Sanitation Foundation.                                                   ,


                                       9-2

-------
After storing the filters  overnight in the desiccator, pre-wejgh  each  filter to  a minimum
precision of ±0.0002 g20.  Each  filter shall then be placed in  a separate, covered Petri dish
with  its weight  marked  on  the top of  the  container.   The  lids shall also be numbered
sequentially and the filters shall all be used during the run in the order numbered.

       9.3.2     Initiating Humidity Control

Use  asbestos-free  (filtered, distilled) water to  make a  2 L solution of saturated salt.  As
indicated previously, for  most applications, use potassium carbonate dihydrate (to achieve a
relative humidity of  43%), but other salts may be used for specific applications (see Appendix
A)21.                                        ,             -

Prepare the solutions by placing  1000 g of the anhydrous salt into a  one L container and
adding distilled water to fill the container. The container should be capped and additional
water and salt added as necessary the next day.  No water or salt should be added within a
day of  using the mixture since some time is needed to saturate the  salt solution and form a
hydrate when  adding anhydrous  potassium  carbonate.   However, sufficient salt shall have_
been added previously to assure that  sufficient undissolved potassium carbonate dihydrate""
has precipitated in the container to form a closely  spaced layer of the material on the bottom
of the shallow pans that will be covered with a thin layer of the solution (next paragraph).

.Open the top of the humidity control chamber and remove the two pans.  Fill each pan with
the saturated salt solution being sure that a small quantity of excess (undissolved) salt is also
transferred  to  each pan.  Replace the pans and seal the top of the plastic enclosure;  air
should  enter the enclosure primarily from the front opening.

       9.3.3     Priming the Scrubber

Fill the round  bottom flask of the scrubber to about one third  full with asbestos-free (i.e.
filtered,  distilled) water.   Initiate the  flow  of ice water through  the entrance and exit
condensers.  Adjust the variable voltage transformer on the heating mantle so that water in
the round bottom flask boils and the  rate at which condensate drops back into the flask from
the condensers is approximately equal to one drop per second.

       9.3.4     Adjusting Initial Air Flow

The air flow within  the various components of the dust generator must be adjusted so that""
flow  within the vertical elutriator  will properly  separate and  pass only respirable particles.
Based on the discussion presented  in Appendix A (Section A.2.3), tire proper linear flow rate
in the  elutriator shall be set at 0.31 cm/s,  which is 5% greater than the Stokes'  velocity.
estimated for the largest  spherical, respirable particles (i.e. those with  a radius of 5
   20
   21
Fitters to be used to collect samples over the isokinetic sampling tube of the elutriator (see Section 9.4.5) must be
weighed to a minimum precision of ± 0.00002 g.'


Note that potassium carbonate dihydrate is not the usual form of potassium carbonate sold commercially. The usual
commercial forms are the anhydrous and the sesquihydrate. The dihydrate can be made by allowing either of the com-
mercial varieties of the salt to stand in their saturated solution for some extended period of time with some temperature
cycling (Berman and Kolk 1994). A week appears to be sufficient but the process can be accelerated by augmenting
the temperature cycling.                          .       '  :                     •>


  ..-..'..••''.        .-9-3    '-..'-               ••''•'

-------
Next, calculate the required volumetric air flow, Vv, within the elutriator using Equation 9-1:
                       = 81.1*V
(9-1)
                where:
                    V,  is  the estimated  linear flow rate  required  to  separate respirable
                        particles (i.e. 0.31 cm/s); and

                    Vv  is  the  corresponding  volumetric  flow rate (cm3/s)  through the
                        elutriator.
The coefficient, 81.1, in Equation 9-1 corresponds to the cross-sectional area of the elutriator
(in cm2).

To adjust the initial flow valve settings on the pumps, first connect one of the flowmeters such
that air flows directly from the exit opening at the top of the elutriator that is not articulated
with the isokinetic sampling tube22.  This is the exit that opens directly into the top, tapering
portion of the elutriator (see Appendix A) and is  labeled the "ME" opening in Figure A-1.  A
filter cassette containing a filter from the batch of filters to be used for the run shall be placed
between the flowmeter and the pump when adjusting the flow valve on 'this pump.
       NOTE

       The easiest way to directly connect a flow line to one of the top openings of the
       elutriator (the ME or the 1ST opening) is to align the appropriate slide mechanism so
       that a filter mount is directly over the opening, mount a cassette without a filter into the
       mount, and connect  the  air flow line to the exit side of the filterless cassette  (see
       Section A.I,6 of Appendix A).   During  calibration,  such  a  line would  then  feed
       sequentially into a flowmeter, a filter-containing cassette, and a pump.
Connect a second flowmeter  directly to the exit line of the scrubber (the entrance  line of
which should already be attached to the two side exit openings on the elutriator) and place a
filter cassette containing a filter from the batch of filters  to be used for the run between this
flowmeter and the pump for the scrubber.                                              -

Adjust the flow control valves on both the scrubber pump and the pump to be connected to
the ME opening of the elutriator so that flow in both lines are equal and that each flow is set
at0.48*Vv.


Connect a third flowmeter to the exit openi'ng  on the top of the elutriator that articulates with
the isokinetic sampling tube. This is labeled the "1ST1 opening in Figure A-1.
   22
       To access this opening, it will be necessary to dismount any filter cassettes from the appropriate slide mechanism and
       to align one of the two openings in the appropriate slide mechanism over the desired opening in the elutriator (see
       Appendix A).  •                    •


                                           9-4                              '

-------
 The flowmeter attached to the 1ST opening shall also be backed by a filter cassette containing
 a filter from the batch  to be used during the run and adjust the  flow in this line so that it is
 equaj to 0.047*VV23.  Due to the low flow required on this Jine, an auxiliary low flow valve is
 also  attached to this pump and must be adjusted  to achieve the desired flow.  To optimize
 conditions, it may be necessary to adjust the flow control valves on the three air lines that exit
 the elutriator iteratively.

 To prepare for a  run  using'the dust generator, disconnect the flowmeters from the slide
 mechanisms over the top bpenings of the elutriator  (I.e. the ME and 1ST openings) and mount
 filters in each of the four cassette  holders on the two slide  mechanisms that cover the two
 elutriator openings. Connect one of the air flow lines coming  off of the 'T1 from each pump to
 each  of the two  filters on the same slide mechanism for the appropriate opening of the
 elutriator (i.e. the  opening for which the  pump had  been calibrated).  Then  adjust each slide
 so that one filter  cassette is  aligned  directly over each elutriator opening.  Be sure that the
 valves on  each   'T1 are configured so  that flow is directed from the  filter cassette  that is
 aligned directly over the elutriator opening (see Section A.1.6 of Appendix A).


       NOTE

       The  connections between the exit side of the filter cassettes mounted on the slide
       mechanisms and the flow control valves on the pumps should  now be direct; there
       should be no^second filter cassette in the line.


The flowmeter attached to the exit line of the scrubber may remain attached during a run  to
monitor air flow through the scrubber.  If there is a desire also to monitor airflow through one
or both of the filter cassettes mounted over the top openings of the elutriator during a run,
flowmeters may now be attached to the downstream side of the filter cassettes (i.e. between
the filter cassettes and  the pumps). Due  to the pressure drop across the filters, however, the
readings from these flowmeters must be adjusted  using the following equation to provide
estimates of the true flow through  each elutriator opening:
            Ft =
(9-2)
       where:
            Ft   is the true flow rate through the elutriator opening (cm/s);

            Rf   is the flow reading from the flowmeter (cm/s);

            Pf   is the pressure at the flowmeter (torr);

            Tf   is the absolute temperature at the flowmeter (°K);
  23
      The coefficient, 0.047, used to estimate the volumetric flow rate for air passing through the isokinetic sampler represents
      the fraction of the cross-sectional area of the elutriator that is subtended' by the isokinetic sampling tube and therefore
      represents the fraction of the total flow that should pass through the tube, assuming that flow in the elutriator has been
      properly set.            ,                                             .

                                   •        9-5               .         -     "••'•'•:

-------
            Pt  is the pressure at the elutriator opening (torr); and

            Tt  is the absolute temperature at the elutriator opening (°K).   .


To use this equation, Pf and Pt will have to have been measured during flow calibration, prior
to  a run,  using mercury manometers  or other appropriate  pressure measuring devices.
Generally,  Tt and Tf can  be considered equal and will drop out of the equation.  However,
Equation 9-2 can also be used to adjust .flow readings between calibrations and runs that are
conducted on different days, such that temperatures may vary between the time during which
the calibration was conducted and the time that the run is performed.24

9.4    DUST GENERATOR OPERATION

To prepare asbestos samples using the dust generator, load the tumbler, condition the bulk
sample, begin the run, monitor the rate of dust generation, and collect appropriately  loaded
filters for asbestos analysis.  Asbestos is also collected in the scrubber.  Prior to use, be sure
that the dust generator is  clean (see Section 9.5).                            •     .     •,

       9.4.1   '  Loading the Tumbler

Detach the tumbler  from its drive motor and the vertical elutriator and  remove  it from the
plastic enclosure at the bottom of the dust generator (see Appendix A). Place the tumbler on
a flat surface and open the top for loading.  Be sure that the tumbler is clean  prior to loading.

Introduce a sample25 by holding the sample  container against the inner lip of the tumbler
and tilting  the container  so that the sample  pours smoothly  into the tumbler.  ' Move the
sample container back and forth  along  the length of the tumbler  to  facilitate uniform
deposition  of the sample in the tumbler.  When pouring is complete, tap the sample container
vigorously  so that the quantitative transfer is complete.  The masses  of samples introduced
into the tumbler shall range between 50 and 80 g. Larger samples shall be homogenized and
split prior to loading  as described in Section 9.2.

Shake the tumbler gently to assure uniform deposition  of the sample within the tumbler, which
should be no more than about one third full. Be sure that the rubber gasket  on the tumbler is
in good repair and properly  seated.  Replace the gasket if it is worn.  Secure the top of the
tumbler with 10  screws and  replace the tumbler within the plastic enclosure  at the bottom  of
the dust generator.  Reattach the elutriator entrance tube and D.C. motor to  the tumbler (see
Appendix A).         ,
   24   Because the viscosity of air is somewhat temperature dependent, when runs are to be conducted at temperatures that
       differ by more than a few degrees from room temperature (nominally 20° C), Equation A.10 (in Appendix A) may have
       to be adjusted to account for the varying viscosity (see Equation A.9) so that the correct flow regime can be established
       at the new temperature to assure that the elutriator of the dust generator passes only respirable particles. .


   25   Samples to be introduced into the tumbler shall have been dried per Section 9.1.


                                           9-6

-------
       9.4.2    Conditioning the Sample            >

 Before conditioning the sample,  be sure that the dust generator has been  properly set up.
 This means, check that:    ,                             .

       •     the pans in  the constant humidity chamber  have  been filled with saturated
            solution;

       •     filters have been mounted on each of the four cassette mounts  on the slide
            mechanisms atop the elutriator;

       •     water is boiling in the scrubber;         >

       •     the air flow valves have been properly set; and

       •     all air lines between  the dust  generator,  flow  valves, and pumps  are properly
            configured (see Section A.1.6 of Appendix A).

To condition  the  sample, turn on all  pumps  and begin the flow of air through the  dust
generator. DO NOT TURN ON THE TUMBLER MOTOR.  Allow the flow of air to continue for
a  minimum  of two  hours  before beginning  a run. If the sample was  oven dried rather than
equilibrated with,an  appropriate salt in a  desiccator (Section 9.1), the  sample  should be
conditioned for a minimum of four hours prior to initiating a run.

       9.4.3     Initiating a Run

Once the sample has been conditioned, set the tumbler drive motor to 30 rpm and turn it on.
Simultaneously, move the two slide mechanisms at the top of the elutriator so that new, clean
filters are now aligned over both the ME  and ,'l'ST  openings  of the  elutriator.   Be  sure to
change the valve orientations on. the lines leading to the filters so that  air flow  is directed
through the filter cassettes that are newly aligned with the elutriator openings.

Replace  the filters originally aligned over the elutriator openings (but no longer  aligned) with
clean, filters and  weigh and  store  the old  filters in  labelled Petri dishes.  These filters  are
equipment blanks.   After five minutes,26 move the sliding  mechanism again to  bring new,
clean filters over the ME and 1ST openings of the .elutriator. Immediately after the filters are
brought  out of alignment,  dismount the cassette and turn the potentially, dust-laden side of-
the filter  face  up before  halting the flow of air through the filter (by turning the appropriate
valves).  Once flow from the dismounted cassettes has been halted (correspondingly, flow will
have been re-directed to the  cassettes that are  currently aligned over the elutriator openings),
replace the  dismounted filters with clean filters  and weigh and store the dismounted filters in
labelled Petri dishes.  These filters are run blanks.

As the run proceeds, record the times that air flow was started and stopped for each filter, the
initial and final weights of each filter, and the identifier of each filter in a log book.     ,
  26
      This-interva! is selected because, in the absence of channeling, five minutes is just less than the time over which the
      fastest particles are expected to reach the fitter.

           '            '-.-'':        9-7          •             '-         '.

-------
       9.4.4     Monitoring the Rate of Respirable Dust Generation

 The rate of respirable dust generation is monitored during a run by recording the weights of a
 set of filters that are sequentially changed out of the filter mounts over the ME opening of the
 elutriator at defined, regular intervals.                                           -

 Initially, change the filter that is aligned over the ME opening of the elutriator at intervals  of
 five to eight minutes.  The change is accomplished by moving the slide mechanism to switch
 a new filter into alignment at the same time that the old filter is switched out of alignment.
 Immediately after the filter is brought out of alignment,  dismount the cassette and turn the
 dust-laden side of the filter face  up before halting the flow of air through this filter (i.e. by
 turning the appropriate valves to  re-direct air flow to  the filter that is newly aligned over the
 ME opening).  Exchange the old filter for a new filter.


       NOTE

       Because the time during which  air flow is  directed through  a  dismounted cassette
       (rather than the filter that is aligned over the elutriator opening) results in a disturbance
       in the otherwise smooth flow of air through the elutriator, the  changing of filters shall
       be performed  expeditiously.  As long as this interval is not more than a few seconds,
       however, studies indicate that this effect is not significant (Berrnan and Kplk 1994).


Along with the proper identifier,  record the times during which air flow is started and halted for
each  filter.  Weigh each filter after dismounting.  Record the initial and final weights of the filter
and the net weight of dust deposited on the filter (i.e. the difference between the initial and
final weight).                   ,

After exchange of the first two or three filters, the interval over which dust is collected on each
filter may be optimized.  The ideal weight of dust to  be deposited on each filter is between
0.01  and 0.03 g (Berman and Kolk  1994).  Based on the rate of dust deposition on the first
two or three filters, estimate the interval  of time required to deposit approximately 0.02 g and
exchange  later filters at  this  rate  (see  Section  A.2.2  of Appendix  A,   Equation A-8)27.
However, it is important that time  be adjusted so that no more than 0.03 g be deposited on
each  filter because the possibility that a portion of the deposit accidently drops from the filter
increases as the weight of the deposit on the filter increases.                               -


       NOTE

       Until there is a need for generating filters for asbestos analysis (see Section 9.4.5), the
      filters that get aligned over the 1ST opening of  the elutriator need to be changed only
       one fifth to one tenth as often as the filters over the ME opening of the  elutriator.
      These filters shall  be changed at this lower rate, however, to prevent the potential for a
      heavy deposit to drop off of the filter and fall back into the elutriator.
      At the beginning of a run the rate of dust deposition on the filters has been observed to be nearly constant with time.

                                           9-8

-------
Continue the run at 30 rpm (with continuing exchange of filters) for approximately two .hours;
this time interval has generally  been observed as sufficient to define the rate of respirable
particle rejease at this rotation rate (Berman et al 1994a). Generally, the plot of the release of
respirable dust versus time at 30 rpm shows almost no curvature (see Section 11.2).

After completing the run at 30 rpm, select a new,  higher  rotation rate to continue the run.
Generally, the new rotation rate selected shall be 60 rpm, unless the rate of release at 30 rpm
was noticeably  low in comparison with  prior runs  on other samples,  in .which case 90 or
120 rpm shall be used.    •"  '•               ..'.:'••


       NOTE

       Use  of the  highest rotation  rates should  generally  be  avoided,  unless there is
       compelling evidence for their efficacy, because they tend to facilitate the transport of
       non-respirable particles from the tumbler into the Bottom of the elutriator and,  if such
       transport is heavy, this may affect results (see Section A.1.3 of Appendix A).        .


Continue the  run at the higher  rate of rotation by  collecting a minimum of eight additional
dust-laden filters.  The same procedures outlined above should be continued  for collecting
data during the  run at this  higher rotation rate except that the interval between the exchange
of filters must be adjusted  downward to assure  that  deposits on these  latter  filters' do not
exceed 0.03  g  (see  Section  A.2.2 of Appendix A,  Equation A-8, but  note  that the rate
constant, k, is dependent on the rotation rate for  the tumbler so that Equation A-8 cannot be
extrapolated across runs).
                -,        '   •   •  '             •          '          '"             '
When the run is complete, turn off the tumbler motor but allow the  air flow to continue for ten
or fifteen  additional minutes to  empty the elutriator.   Be sure to  continue the exchange of
filters, if necessary to prevent overloading.  The air flow pumps may now be shut off.

       9.4.5     Generating Appropriately Loaded  Filters for Asbestos Analysis

The, primary purpose for collecting dust on filters mounted over the  exit of  the isokinetic
sampling tube of the elutriator (the opening labeled "1ST1 in Figure A-1) is to obtain samples
suitable for asbestos  analysis using a direct transfer technique, although use  of an  indirect
transfer technique is riot precluded.  This  is an option built into the design of the dust
generator as an alternative to preparation of a specimen for asbestos analysis using the liquid"
from the scrubber, which necessarily mimics an  indirect transfer technique because (in the
scrubber) the asbestos is captured and suspended in water.

Collect filters for asbestos analysis near the end of each of the two runs (i.e. one run at each
of two  rotational speeds for the tumbler) that is described in the previous section of this
chapter.  Filters to be used for asbestos analysis shall be collected at the end of the runs
both because this will be the period when the rate of asbestos emission is the lowest  and
because sufficient time will have elapsed over each run to  allow a steady-state  distribution of
particle sizes  to have developed in the dust traversing the elutriator.  At the beginning of a
run,  only the  smallest  (fastest) respirable particles  reach the filters and it. takes time for the
larger  (slower) respirable particles in the  air  stream to begin reaching the filters in numbers
that  are proportional to, their rate of  emission from the tumbler.  It takes several  tens of
minutes for transport of a steady state distribution to develop.
                                           9-9

-------
Collect multiple filters during  each run that bracket the estimated time during which an
optimal loading for analysis of a directly prepared specimen is expected to  be achieved.
Mount, exchange, dismount, weigh, record, and store filters precisely in the manner described
in Section.9.4.4.

Estimate the  time required for achieving an optimum loading  as follows.  The optimal mass
loading on a filter to  be prepared by a direct transfer technique lies between 1  and 10 jig
(see, for example, Berman and Chatfield 1990). Assume a target of 5 \ig.  However, this may
have to be adjusted based on experience with the dust generator. Equation A-7 (Appendix A)
can then be re-arranged to estimate the time required to collect 5 fig (or some other defined
mass)  of dust:
                At = AM/0.047*k*Ms
(9-3)
           where:
                Ms is the  mass of respirable dust remaining in the sample at time "t" after
                   the beginning  of the run, but, it is  assumed constant over the short
                   interval of time  "At" (g);

                AMfis the  mass of  respirable dust collected on a filter over the  1ST opening
                   during the short time interval "At" (as indicated above, assume a target of
                   5 jig orSxIO^g);

                At  is -a short time  interval (no more than several minutes) during which the
                   release of dust  is being estimated (s);  and

                k   is the  first-order  rate constant for the release that  is derived from the
                   dust measurements collected during the run (s"1).
The mass of respirable dust remaining in the sample during the time interval of interest (Kg) is
estimated using a rearrangement to Equation A-2 (Appendix A):
                Ms = M  *exp(-kt)
(9-4)
           where:
              .  Ms is the mass of respirable dust remaining in the sample at time T (g);

                M0 is the mass of respirable dust in the sample at the start of the run (i.e. at
                   time t = 0) (g).

                t   is the time from the start of the run to  the beginning of the time interval
                   "At" (s); and                                               .

                k   is the first-order rate constant for the release (s"1).
                                         9-10

-------
 Based on the recently completed pilot study for this method (Berman et al. 1994a), a typical
 rate constant for dust emission from the tumbler is 0.004 min  (6.7 x 10"5 s~1). Results from
 this study also suggest that the range in respirable  dust content likely to be encountered for
 samples .typically run using the dust generator may vary between 0.5% and 2%.  Therefore,
 given  a typical  sample mass of  70 g, M0 for the 30  rpm  run  likely  ranges  between
 approximately 0.17 and 0:68 g.   Given that  a typical  3D rpm  run lasts  for approximately
 3 hours  (1.1  x 104 s) and  substituting these  values for  M0, k, and t into Equation 9-4, and
 then substituting the subsequent estimate of Ms  into Equation  9-3,  it appears that between
 2.3 and 9 seconds would be required at the end of the 30 rpm run to collect 5 jig of material
 o'n a filter loaded over the isokinetic sampler.

 Similarly, assuming that the initial mass of respirable dust in a sample at the beginning of a
 60 rpm run, MO^Q, is equal to the remaining mass at the end of the 30 rpm run (i.e. the "Ms"
calculated above), remembering that a 60 rpm run typically lasts 2 hours (7.2 x-103 s), and
once again noting the typical value for k indicated above, Equation 9-4 is used to estimate an
appropriate Ms for the end of a 60 rpm run.  Substituting this new value into Equation 9-3,  it
appears that between 4 and 15 seconds may be required to collect 5^g of material on a filter
that is loaded over the isokinetic sampler at the end of a 60 rpm run.

Given the above, to  properly bracket the optimal  loading for a filter to be employed' for
asbestos  analysis using a (direct transfer technique), collect filters over the 1ST opening of the
elutriator  that are exposed  for periods of  3,  10, and 20 seconds (at both the  end of the
30 rpm run and the end of the 60 rpm run).    •

       9.4.6    Obtaining Asbestos Samples from the Scrubber

At the end of all runs for a particular sample (after all pumps have been shut off), turn off the
heating mantle to the scrubber and let it cool for 10 to 15 minutes before discontinuing the
flow of ice water to the condensers.  Disconnect the outlet  lines from  the  elutriator to the
scrubber  at the elutriator.  Samples shall  be extracted from the scrubber expeditiously to
minimize losses to the walls  of the glassware and to facilitate cleaning.

To  minimize  loss, before disconnecting the transfer lines and condensers from the round-
bottom flask of the scrubber, pour approximately 100 ml of asbestos-free (filtered, distilled)
water down the exit condenser and another 100 ml down the transfer lines and entrance
condenser.  Such rinsing should be performed in multiple stages, approximately 20 ml at  a
time. Swirl each condenser (and the transfer lines) as the water drains into the flask.  Tap-
each condenser  (and  the transfer lines)  several times after rinsing to assure a reasonably
quantitative transfer. .

Detach and remove the round-bottom flask from the condensers and its stand and pour the
contents of the flask into a  clean,  pre-weighed, wide-mouthed 1  L plastic  container. Rinse
the  found bottom flask several  times  with additional asbestos-free  water to assure  a
quantitative transfer of any residual solids.  Reweigh the container and record the net weight
as the  total  weight of suspension.  If necessary,  the sample may then be stored at ice
temperature until it can be  prepared.  However, preparation  shall not be delayed for more
than 48 hours.

Immediately prior to filter preparation, add  1.5 g/L of sodium  hexametaphosphate to the
suspension in  the plastic  container.    Shake the  suspension vigorously , and  divide  it
                                         9-11,

-------
 approximately evenly into two (or, if necessary, three)  500 ml Erlenrneyer flasks.  Place the
 flasks on a  laboratory shake table for approximately three hours.   Quickly re-combine the
 contents of the two (or three) flasks into a clean, plastic container (with minimal flushing) and
 place the container in a sonicator.   Sonicate the suspension for approximately  1 minute (with
 the power of the sonicator set at no more than 0.1 W/ml).  Withdraw one ml with a disposable
 pipette from  the center of the volume of the suspension in the plastic container  and dilute this
 with asbestos-free water to 100 ml in a clean, volumetric flask.

 The mass of respirable dust collected in the  scrubber should be equal to the  sum of the
 cumulative mass of dust measured on the filters collected above  the ME opening of the
 elutriator over the entire run(s) during which the scrubber suspension was collected. Use this
 estimated mass  (and account for the  100-fold dilution performed as  described  in the last
 paragraph)  to estimate the  size  of aliquots required to  produce  filterable suspensions
 containing: 0.5, 2,  and 5 fig of  respirable material.  Dilute each aliquot to a  minimum  total
 volume of 20 ml and filter each aliquot in the manner described in Sections 10.34 and 10.35
 of the ISO Method for the determination of asbestos in air using an indirect transfer technique
 (Chatfield 1993)28.

 The filtered aliquots shall all be prepared  as described in Section 10.1  and scanned briefly at
 low magnification in the TEM to select the optimally loaded specimen for  detailed analysis
 (see Section  11.1.2).

 9.5    CLEANING THE DUST GENERATOR

 The dust  generator is designed  for quick and easy assembly and  disassembly to facilitate
 cleaning.  Most  of the joints are  simple friction couplings  or ring clamp couplings.  To clean
 the dust generator, disconnect and disassemble  the tumbler, remove the  bottom cup and
 dust  collector system from  the  elutriator, decouple the  two  halves  of the elutriator tube,
 disassemble  the  slide mechanisms of the dust collector and disconnect the transfer lines to
the scrubber.    The  metal  pieces of  the  dust  generator  may  then  be  washed  with
 biodegradable detergent, rinsed with asbestos-free water, sonicated briefly, and rinsed again.
The pieces may then be left to dry in room air or may be dried with a forced, HEPA-filtered air
stream.

The  glassware of  the  scrubber shall  also  be washed with biodegradable  detergent and
asbestos-free water, rinsed liberally, and dried in room air or dried with a forced, HEPA-filtered
air stream.  It is  recommend that new transfer lines between the elutriator and the scrubber-
 (constructed  of 1.00 in. i.d. Tygon tubing)  be cut and installed after each cleaning.
  23
      As indicated in Chatfield (1993), filters to be employed for filtering scrubber suspensions are of a different type than
      those employed in dust generator mounts. Filters used to filter scrubber suspension are to be the 0.22 urn pore size
      variety                                                                     •     -


                                          9-12       .                .   . •

-------
             10.0  PREPARATION OF SPECIMEN GRIDS FOR TEM ANALYSIS
 For Superfund applications of this method, asbestos analysis of all samples prepared using
 the dust generator are to  be performed on specimen grids prepared from aliquots of the
 scrubber suspension.  In addition, for a minimum of a subset of 5% (preferably 10%) or 10
 samples (whichever is greater), asbestos analysis is also to be performed on specimen grids
 prepared  by a direct transfer technique from  filters collected over  the  1ST .opening of the
 elutriator (i.e. the opening over the isokinetjc sampling tube). These analyses are then paired
 with the analyses of asbestos from scrubber suspension collected during the same runs to
 provide a link between samples prepared by each technique.

 The primary reason for preparing  100%  of samples from the scrubber suspension is to
 facilitate identification  of distinctions in sample characteristics; samples  prepared  in this
 manner are expected to exhibit the best precision among the options for this method.  At the
 same  time, when comparing results to  published  slope  factors,  the  apparent need for
 normalizing asbestos analyses to counts derived from directly prepared specimens (see, for
 example, Berman and Crump 1989)  is satisfied by providing  a subset of samples prepared"
 both ways to allow a regression to be performed linking results from the scrubber suspension
 samples to specimens prepared by a direct technique.   As indicated  previously (Section
 2.1.3), the  recomrnended procedure  is based on a  compromise allowing optimum precision
 for distinguishing among relative measurements  (and relative risks)  while excepting a small
 reduction in the precision of estimates of absolute risk.29

 10.1   PREPARATION  OF  SPECIMEN GRIDS FROM  FILTERED ALIQUOTS  OF THE
       SCRUBBER SUSPENSION

 Filters generated from aliquots of the scrubber suspension (as described in Section 9.4.6)
 shall be prepared using the direct transfer technique that is described in Sections  10.5 of the
 ISO  Method (Chatfield 1993).   As  indicated  previously, multiple aliquots representing a
 sequence of dilutions are to be prepared to allow selection of the optimally loaded filters (and '
 corresponding set of specimen grids) for final, detailed analysis.

 From  each filter, prepare a minimum of three specimen grids: one from near  the center of the
filter, one from a location that is half the distance between the center and the outer edge, and
 one from near the outer edge of the filter.
10.2  SPECIMEN GRID PREPARATION FROM FILTERS  COLLECTED OVER THE 1ST
      OPENING OF THE ELUTRIATOR

Although this method specifies that.filters collected over the 1ST opening of the elutriator shall
be prepared using a direct preparation technique, an indirect preparation technique is also
described, as an option for non-Superfund applications.
      For other applications of this method, options might include preparation of 100% of samples from filters collected over
      the 1ST opening of the elutriator and/or preparation of filters collected over this opening using an-indirect transfer
      technique. The method is designed to be flexible.
                                         10-1

-------
       10.2.1    Specimen Grid Preparation Using a Direct Transfer Technique

Filters collected over, the 1ST opening of the elutriator (as described in Section 9.4.5) shall be
prepared  using the direct transfer technique that is described in Sectiqn 10.5 of the ISO
Method (Chatfield 1993).  As indicated previously, sections of multiple filters representing a
range of  loadings are to be prepared  to allow selection of the optimally loaded specimen
grids for final, detailed.analysis.
From each filter that has been collected over the 1ST opening,  prepare four specimen grids
from  locations on  the  filter that  are  each separated by 90°  radially.  Select two  of the
locations (from opposing sides of the filter) at points that are about two thirds of the distance
from the center to  the edge of the filter.  The remaining two locations shall be selected at
points that are about one third of the distance from the center to the edge of the filter.  Such
an arrangement will eliminate any effects potentially associated  with a linear gradient across
the filter that may develop due to the brief time over which the filters are exposed to air flow
from the elutriator and, consequently, the potentially significant time  during which the filter is
being slid in and out of alignment.                              .

10.3   Specimen Grid Preparation Using an Indirect Transfer Technique  .

As  an  option  to the procedure described  in  Section  10.2.1 above (for non-Superfund
applications only),  filters collected over the 1ST opening of the  elutriator (as  described  in
Section 9.4.5) may  also be prepared using the indirect transfer technique that is described in
Sections 10.3 to 10.5 of the  ISO Method (Chatfield 1993).  For this  option, multiple sections of
the most  highly  loaded  .filter obtained from the dust generator shall  be  prepared using a
range of dilutions to allow selection of the optimally loaded specimen grids for final, detailed
analysis.
                                          10-2

-------
               11.0 PROCEDURES FOR ASBESTOS AND DUST ANALYSIS


 11.1   PROCEDURES FOR ASBESTOS ANALYSIS                                .

 Specimen grids prepared as described in Chapter 10 are to be analyzed using transmission
 electron microscopy (TEM).  Follow the procedures for analysis described in the ISO Method
 (Chatfield 1993) including procedures for:

       •    examining specimen grids to determine acceptability for analysis;

       r    structure counting  by TEM (except determination of the stopping point);

       •    structure morphological classification;                   .  ~     .''•."

       •    structure mineralogical identification; and

       •    blank and quality control determinations.                          ' •    -      ~

The stopping points for the,analyses conducted in support of this method are  a function of
the required sensitivity for the method and are defined in Sections 11.1.1 and 11 ^1.2 below.

Begin by examining  one of each set  of specimen grids derived for a defined loading from a
particular run of the dust generator and select the optimally loaded set for analysis.  Use the
criteria for determining the acceptability of specimen grids (from the ISO  Method) to define
optimal loading.           ! ."                              '

When performing detailed analysis, be  sure to distribute asbestos  counts evenly  over the
entire set of specimen grids prepared from a particular filter at a  defined (optimal) loading.
Record  the  morphology and mineral type of asbestos structures as described in the ISO
Method (Chatfield 1993). Also as described in the ISO Method, .complete separate scans for
counts of total structures and, at  lower magnification, for counts of structures longer than
5  -
      11.1.1   Analysis of Specimen Grids Prepared from Filters Collected Over the 1ST
               Opening of the Elutriator           ,
Prior to initiating a detailed analysis of specimen .grids, the stopping rules for the analysis
must be defined. Assuming these specimen grids have been prepared using a direct transfer
technique (as discussed in Section  10.2), define the stopping rules for the detailed analysis
as follows.
             .  ;   -       '              , •              -                    ,        !  -
First, calculate the maximum number of grid openings that will have to be scanned during the
analysis from the relationship:
      Ngo =
(11-1)
                                         11-1

-------
    where:
        N™
                        is the maximum number of grid openings to be" scanned;
                Sd  is the number  of structures  required to  define  detection  using the
                    analysis (defined here as 1);                     ;    .  '

                Af . is the total  area  of the  filter from which the specimen  grids  were
                    prepared (mm2);

                %RD    is the mass percent of respirable dust in the sample and is defined
                        using Equation 11-9;

                Ssmp,   is the required analytical sensitivity for the method (s/g)';

                Ago is the area of a single grid opening (mm2); and

                AMfis the  mass  of respirable dust collected  on the filter from  which the
                 .   specimen grids were  prepared.  It is defined using Equation  A-7 of
                    Section A.2.2 of Appendix A (g).


The following are typical values for the above parameters:
smpi
       °/
       AM
          f
                  5x10' (for total structures) or
                  3 x TO6 [for structures longer than 5 fim)30;
                  382 mrrn   ,    ,
                = 8.1
          between 0.5% and 2%31; and
               32.
Given  the above  values,  it  is estimated  using Equation 11-1 that between 1 and 4  grid
openings will.typically need to be scanned to derive a count of total structures. However, a
minimum of 4 grid openings shall be  scanned during any  analysis.   Based  on the above,
similarly, between  15  and 62 grid openings will typically need to be scanned to derive a count
of structures longer than 5 jim.

The number of grid  openings to be scanned for specific analyses shall be  determined by
substituting case-specific values for the above listed parameters into Equation 11-1.

Stop the counting, characterization, identification, and recording of asbestos structures on a
particular analysis when one  of the following obtains:
   30   See Section 2.1.1.


   31   This is the range of values observed for a diverse variety of samples tested during the pilot study for this method
       (Berman et al. 1994a).                         ,
       See Sections 9.4.5 and A.2.2 of Appendjx A.
                                          11-2

-------
        •    the scan is completed for the grid opening on which the 50th asbestos structure
             is counted; or                                                  '...'..-
                                                             i   •-,.-•
        •    either 4 grid openings or the maximum number of grid  openings (estimated as
             defined.above), whichever is greater, are scanned completely.             ,
                       1                              •             . *
 These rules are to be applied separately to the scan for total structures and the scan for long
 structures (i.e. longer than 5 jim) that are described in the ISO Method.

     .   11.1.2  Analysis of Specimen Grids Prepared from Filtered Scrubber Suspension

 Prior to initiating  a detailed analysis of specimen grids, the stopping rufes  for the analysis
 must also be defined in this case.  Given that these specimen grids  have  been prepared as
 described in Section 10.1, define the stopping rules for the detailed analysis as follows.

, First, calculate the maximum number of grid openings that will have to be scanned during the
 analysis from the  relationship:
        Ngo = Sd*Af*%RD*DF/(Ssmp|*Ago*100*Mscrbr)
                                                                      (11-2)
where:
    NL,
                        is the maximum number of grid openings to be scanned;
                Sd     is the number of structures required to  define detection using the
                     •   analysis (defined here as 1);

                Af      is the total area of the filter from which the specimen grids were
                        prepared (mm2);

                %RD   is the mass percent of respirable dust in the sample and is defined
                        using Equation 11-9;

                Ssmp|   is the required analytical sensitivity for the method (s/g);
                                                             ,2s.
                  90
                 DF
            is the area of a single grid opening (mm );

            is the dilution factor by which the scrubber suspension -had to  be
            diluted to  prepare' specimen grids that  are suitably  loaded for
            analysis; and
                 Mgcrbr  is the mass of respirable dust collected in the scrubber suspension
                        during the run.
 The dilution factor, DF, is simply the  product of the individual dilution factors  for the two
 sequential  dilutions performed  to  derive the final volume that  is ultimately  filtered (per the
 procedure defined in .Section 9.4.6):
                                           11-3

-------
            DF =
(11-3).
            where:
                Vs  is the volume of the initial scrubber suspension (which is estimated from
                    the recorded weight of the supernatant assuming a density of 1 g/cm3)
                    (ml);                                                  '        ,

                Va1 is the volume of the first aliquot collected from the scrubber suspension
                    for further preparation (the default defined in Section 9.4.6 is 1 ml);

                Vd  is the volume into which the first aliquot from  the suspension is diluted
                    (the default defined in Section 9.4.6 is 100 ml); and

                V^ is the  volume of the  final aliquot collected from Vd that is ultimately
                    filtered for preparation of the optimally loaded specimen grids (ml).

The mass of respirable dust collected in the scrubber suspension, Mscrbr, is derived from the
cumulative mass of dust collected during the run  on filters that are mounted  over the  ME
opening of the elutriator (defined below as Mf).  These differ by the ratio of the  air flow into
the filters and the air flow into the scrubber:
            Mscrbr = Mf*
(11-4)
            where:
                Mscrbr  is tne mass of respirable dust collected in the scrubber during the
                        run(g);                                 .

                Mf  is the cumulative mass of dust collected on the filters (mounted over the
                    ME opening of the  elutriator)  during the same  run  (calculated  from
                    Equation A-4 of Section A.2.1 . of Appendix A);

                Fs  is the volumetric air flow rate into the scrubber (cm3/s); and

                Fc  is the volumetric air flow rate into the  filters over the ME opening of the
                    elutriator (cm3/s).

Assuming air flow in the elutriator is setup as described in  Section 9.3.4, Fs and Ff are equal
so that Mscrbr simply equals Mf.
Given  the typical  values for the corresponding  parameters provided  in  Section  11.1.1,
assuming a typical value for DF ^ of between 2 x 10* and 4 x 104, and selecting a range of
typical values for Mf (i.e. between 0.1 and 0.2 g) from among the range observed during the
pilot study (Berman et al. 1994a),  it  is  estimated  using Equation 11-2 that between 1 and 8
grid openings will  need to be scanned to derive counts of total structures.  Similarly, it is
estimated that between 8 and 133  grid  openings will need to be scanned to  derive counts of
long structures (i.e. longer than 5
      This assumes typical values for M, (between 0.1 and 0.2 g) from among the range of values observed among diverse
      samples during the pilot study. (Berman and Kolk 1994) and further assumes that the dilution factor is selected so as to
      produce a loading of 5 fig on the fitter.       '.
                                                                      '^

                                           11-4                         -

-------
 Determine the actual number of grid openings required for a specific analysis by substituting
 case-specific values for the above parameters into Equations 11 -2, 11 -3, and 11 -4,

 Stop .the counting, characterization, identification, and  recording of asbestos structures on a
 particular analysis when one of the following obtains:

       >    the  scan is completed for the grid opening on which the 50th asbestos structure
            is counted; or

       •    either 4 grid  openings  or the maximum number of grid openings (estimated as
            defined above), whichever is greater, are scanned completely.

 These rules,are  to be applied separately to the scan for total structures and the scan for long
 structures (i.e. longer than 5 jim) that are described  in the ISO Method (Chatfield 1993).
                  '            '               • »                 -                ,
 11.2  EVALUATING THE RATE OF RELEASE OF RESPIRABLE DUST

 The rate of release of respirable dust from a sample  prepared  using the dust generator is
 estimated from  measurements  of the mass of dust collected  over time on the set of filters
 mounted over the ME opening of the elutriator.  The measurements used specifically are from
 those  filters  that are collected while the tumbler  is operating at the highest rotation rate
 employed for the sample (see Section A.2.1 of Appendix A).                    '

 Begin  by plotting the cumulative mass collected on the  filters as a function of time.  To derive
 the cumulative mass for a particular time interval, add the mass of dust measured on the filter
 collected  from that time interval  to the  sum of the masses measured on the set of filters"
 collected  earlier in  the  run.  Typical curves are depicted in Figures 11-1  and 11-2.   Next,
 calculate the cumulative mass released from the sample over time  from the cumulative mass
 collected on filters over time using the relationship developed in Section A.2.1 of Appendix A:
             r = 2.1*Mf
(11-5)
      where:          •
            Mr  is the cumulative mass of dust released from a sample between the start of a
                run and time T (g); and             '

            Mf  is the cumulative mass collected on filters34 between the start of a run ,and
                time "t" (g).
Equation 11-5 is appropriate to use to relate the mass of dust collected on filters to the mass
released from the sample when air flow in the dust generator is setup as indicated in Section
9.3.4.   If different air .flow  conditions  are established  for  a particular experiment,  the
relationship between Mr and Mf will have to be derived using Equation A-4 from Appendix A.
      These are the fitters that are mounted over the ME opening of the elutriator.


                                         11-5

-------
                                FIGURE 11-1


                     TYPICAL CUMULATIVE MASS RELEASE

                     VERSUS TIME CURVE FOR 30 RPM RUN3
CO
DC

2.

a

t
CO
o
a.
UJ
a

CO
CO

a
U
                      100
200
300
400
                              TIME (MINUTES)



         KEY:


         DUST SAMPLE MEASUREMENT


         BEST FIT LINE
        3FROM THE 30-RPM RUN ON SAMPLE 1-100, WHICH WAS COMPLETED

         ON 8/27/93 DURING THE PILOT STUDY (BERMAN ET. AL. 1994a).

-------
                                 FIGURE 11-2


                      TYPICAL CUMULATIVE MASS RELEASE

                      VERSUS TIME CURVE FOR 60 RPM RUN8
^    0.14
CO
a
ia

to
o
a
ui
a

CO
CO
Q

UI



1

ID



O
     0.00
                                    200
400
                               TIME (MINUTES)
          KEY:


          DUST SAMPLE MEASUREMENT


          BEST FIT LINE
         8FROM THE 60-RPM RUN ON SAMPLE 1-100, WHICH WAS COMPLETED

          ON 8/27/93 DURING THE PILOT STUDY (BERMAN ET. AL. 1994a).

-------
 The total mass of dust in the sample at the beginning of the run must next be estimated using
 the relationship developed in Appendix A. Based on the relationship (see Section A.2.1):


            ln(M0 - Mr) = ln(M0) - kt    •           -                                 (11-6)

       where:
            M0 is the mass of dust in the sample at the start of the run (g);

            k   is the first-order rate constant for the release of dust from the sample (s~1);
                and. ,                                                   •

            t    is the time since the start of the run (s);
                                                  /
 a plot of ln(M0 - Mr) versus t should be a straight line with a slope equal to the rate constant
 for the release of dust from the sample and an intercept equal to the natural logarithm, of the
 mass  of dust in the sample  at the start of the run.   Derive estimates of  "M0"  and "k" by
 programming Equation 11-6 into a spreadsheet and running a regression35.

 Input a range of guesses for the value of M0 into the spreadsheet and run a regression to fit
 a value for k and to calculate a  Value for the regression coefficient, "r^" for each value of  M0.
 Plot the regression coefficient,  "r2" as  a function of  M0.  An example of  such a  plot is
 presented in Figure 11 -3.  The  value of M0 that provides the fit with the largest regression
 coefficient (i.e. with ^closest to  1) shall be reported as the correct value for the mass of dust
 in the  sample at the start of the  run and shall be reported with the corresponding k value as
the estimated rate constant for dust release from  the sample during the run.

 11.3   DETERMINING THE CONTENT OF RESPIRABLE DUST

To determine the mass percent  of  respirable dust in the original sample, first determine  the
total mass of respirable dust in the sample at the start of a run for the last run completed on
the sample,  which is  derived as  described in the last section.

 Because the dust generator run analyzed as described in Section 11.2 will generally have
been preceded by a run with the tumbler speed set at 30 rpm (see Section 9.4.4), to estimate
the total mass of dust present in the sample, it is necessary to include the mass released
during this first run.

Sum the masses of dust measured  on each of the filters collected during the 30 rpm run and
designate this sum, "M^", which is the cumulative mass of dust collected .during the 30 rpm
run.  Using  the following equation, estimate the total mass of dust released from  the sample
during the  30 rpm run, "M^,"  based on the mass of, dust collected during that run (see
Section A.2.1 of Appendix A):
                = 2.08'M^
(11-7)
  35  Any of several commercial spreadsheet programs (including, for example, LOTUS™) contain the necessary capabilities
      and may be employed to derive optimum values for 'M ' and "k."       '
                                          11-8

-------
                                      FIGURE 11-3

                            ILLUSTRATION OF THE OPTIMIZATION

                           OF THE ESTIMATE OF INITIAL MASS "Mn
A. TYPICAL PLOT OF CORRELATION COEFFICIENT VERSUS INTITIAL MASS FOR A DUST GENERATOR RUN3

         .'    -   •   . 1-
         CM

         DC
          UJ

          O

          u.
          U.
          1U
          O
          O
         HI
         DC
         DC

         8
                0.9995
                0.9965
                        0.16  0.18  0.2  0.22  0.24  0.26  0.28   0.3


                                     TIME (MINUTES)
  B. TYPICAL PLOT OF THE OPTIMIZED FIRST ORDER RATE EQUATION FOR A DUST GENERATOR RUN3



                   -1.5
              CM
              CM

              O
                                    y = 1.51-0.00379 *x

                                    R2 = 1.000
                                          100


                                    TIME (MINUTES)
100
                 aFROM THE 60-RPM RUN ON SAMPLE 1-100, WHICH WAS COMPLETED

                  ON 8/27/93 DURING THE PILOT STUDY (BERMAN ET. AL. 1994a).

-------
 Calculate the total mass of dust originally present in the sample, Mtot, by summing the mass
 released during the 30 rpm run with the mass of dust estimated to have resided in the sample
 at the beginning of the higher rpm run, M0 (this is equal to the mass of dust remaining in the
 sample at the  end of the 30 rpm run).  M0 will  have been derived as described in Section
 11.2:    ,                                             ,
            Mtoi = Mrso + Mc
(11-8).
 Estimate the mass percent of respirable dust in a sample as follows:


            %RD = 100*Mtot/Msamp|e                                               (11-9)

       where:                                      .        •   '    "                   —
            %RD   is the mass percent of respirable dust in the sample (%); and

            ^sample 's *ne mass °ftne original sample placed in the tumbler (g).

11.4   DETERMINING THE CONTENT OF ASBESTOS

The concentration of  asbestos in a sample  is determined differently depending on whether
asbestos  is  determined  from sampling grids prepared from filters collected  over the  1ST
opening of the elutriator or from scrubber suspension.


       NOTE

       For samples originally containing a significant fraction of coarse material (see Section
      .8.4), the concentration of asbestos reported as a function of the mass of the sample
       (specified in'this section) must be adjusted for the quantity of coarse material originally
       measured in the matrix sampled in the field before it can be considered representative
       of that matrix.  A procedure for adjusting asbestos concentrations to account for the
       coarse fraction  of an environmental matrix is presented in Section 11.4.3.

       11.4.1   Based on Directly Prepared Filters Collected Over the 1ST Opening of the
               Elutriator

Procedures for determining the concentrations of  asbestos structures in a  sample differ
sligTitly depending on  whether the structures of interest are longer or shorter than 5 urn.

Structures that are shorter than 5 jim in length are derived only from the high magnification
scan of an analysis.   Calculate and report the concentration of short asbestos in the original
sample based on  the counts of asbestos structures that are derived as defined  in  Section
11.1.1  using the following relationship:
                                        11-10

-------
       Csmpl = Sch*V%RD/(Ngoh*Ago*100*AMf)
                                                                         (11-10)
            where:
                Csmp|   is the concentration of asbestos structures (of a defined size range
                        or type) in the original sample (s/g);          ,   ,     .

                Sch     is the number of structures (of the defined size  range or type of
                        interest) counted during the high magnification scan of the analysis;

                        is the total area of .the  filter  from which the specimen  grids were
                        prepared  (rnm2);
         V

         %RD
                        is the mass percent of respirable' dust in the sample and is defined
                        using Equation 11-9 (%);                   x   '

                Ngoh    is  the  number  of grid  openings  scanned  during the   high
                        magnification scan of the analysis;

                        is the area of a single grid opening (mm2); and

                   if     is the mass of respirable dust collected on the filter from which the
                        specimen grids were prepared.  It is defined  using Equation A-7 (see
                        Section A.2.2 of Appendix A) (g).
        "go

        AM
Structures that are longer than 5 jim in length are derived from combined counts collected
during both the high and low magnification scans of an analysis.   Calculate and report the
concentration of long asbestos in the original sample  based on the counts of asbestos
structures that are derived as defined in Section 11.1.1 using the following relationship:
           where:
                C
'smpl = (Sch + Sc,)*V%RD/|;(Ngoh + Ngol)*Ago*100*AMf]                    (11-11)


         .smp!   is the concentration of asbestos structures (of a defined size range
                or type) in the original sample (s/g);

         3ci     is the number of structures (of the  defined size range or type of
                interest) counted during the low magnification  scan of the analysis;
                and                .

         Ig0i    is  the  number of  grid   openings  scanned  during   the  low
                magnification scan of the analysis.
                N
Thus, for long structures, it is the total counts of structures observed over both the high and
low magnification scans and the total area scanned (over both the low and high magnification
scans) that are used to determine concentration.
                                         11-11

-------
As an option, asbestos concentrations may also be reported as a function of the mass of
respirable dust in a sample using the following relationships.  For short structures, use:
       Cdust = Sch*Af/(Ngoh*Ago*AMf)  -
                                                               (11-12)
            where:
                C
•dust    is the concentration of asbestos structures  (of any  defined  size
       range or type) in the respirable dust of the sample (s/gdust); and all
       other parameters are defined as described above.
Similarly, for long structures, use:
          st = (Sch + Sc|)*Vt(Ngoh + Ngo|)*Ago*AMf]

       1 1 .4.2   Based on Specimens Prepared from Scrubber Water
                                                               (11-13)
As described in Section 11.4.1, procedures for determining the concentrations of asbestos
structures in a sample differ  slightly depending  on whether the structures  of interest are
longer or shorter than 5
Structures that are shorter than 5 jim in length are derived only from the high magnification
scan of an analysis.  Calculate and report the concentration of short asbestos in the original
sample based on the counts of short asbestos structures that are derived from the scrubber
suspension as defined in Section 11.1.2 using the following relationship:
      Csmp! = Sch*V%RD*DF/(Ngoh*Ago*100*Mscrbr)
                                                               (11-14)
           where:
               Csmp,   is the concentration of asbestos structures (of a defined size range
                       or type) in the original sample (s/g);

               Sch     is the  number of structures (of the defined  size range or type of
                       interest) counted during the high magnification scan of the analysis,;—-

               Af      is the  total  area of the filter from which  the specimen grids were
                       prepared (mm2);

               %RD   is the mass. percent of respirable dust in the  sample and is defined
                       using Equation 11-9 (%);
               N
                 goh
      is  the  number  of  grid  openings  scanned  during  the   high
      magnification scan of the. analysis;

      is the area of a single grid opening (mm2);
                                         11-12

-------
                DF     is the dilution factor by which the scrubber suspension had to be
                       diluted to prepare specimen grids for analysis (derived as defined in
                       Equation 11-3); and                                  -

                Mscrbr  is the mass of respirable dust cpllected in the scrubber suspension,
                       during the run (derived as defined in Equation 11-4).

Structures that are longer than 5 jim in length are derived from combined counts collected
during both the high and low magnification scans of an analysis. Calculate and report the
concentration of long asbestos in the original sample based on the counts of long asbestos
structures that are derived from scrubber  suspension as defined in Section 11.1.2 using the
following relationship:
        smpl
            where:
                C
                                              Ngo,)*Ago*1 00*Mscrbr]
                                                                                (11-15)
                 s  |   is the concentration of asbestos structures (of a defined size range
                       or type) in the original sample (s/g);

                 c|     is the  number of structures (of the defined size  range or type of
                       interest) counted during the low magnification scan of the analysis;
                       and
                N
                 'goi
                       is  the  number  of  grid  openings  scanned  during  the  low
                       magnification scan of the analysis.
      f
As an option for analysis  of the scrubber suspension, asbestos concentrations may also be
reported as  a function of the  mass  of respirable dust in a  sample  using the  following
relationships.  For short structures, use:            .              ,         :
      Cdust = Sch*Af*DF/(Ngoh*Ago*Mscrbr)
                                                                                 (11-16)
           where:     -.   .   -
               Cdust   is the concentration of asbestos structures  (of any defined .size
                       range or type) in the respirable dust of the sample  (s/g^gt); and all
                       other parameters are defined as described above.
Similarly, for long structures, use:
       Cdust =
                     Sc))*Af*DF/[(Ngoh + Ngo,)*Ago*Mscrbr]
(11-17)
                                         11-13

-------
       11.4.3   Procedure  for  Adjusting Asbestos Concentrations to Account for the
                Presence of Coarse Material in the Sampled Matrix

As indicated in Section 8.4,  due to the need to incorporate field data into this calculation, a
formal protocol designating  who is to perform this calculation and  how that individual is to
obtain the needed field information must be defined at the start of a study using this method.

To provide  a representative measure of the  concentration of asbestos jn an  environmental
matrix in which significant coarse material is found (i.e. more than 10% by weight), first derive
an appropriate coarseness adjustment factor:
CF = Mfrne/(Mfi
                             ne   Mcoarse)
(11-18)
            where:
                CF
        is  the  coarseness  adjustment  factor for  a  particular  sample
        (dimensionless);
               Mfjne   is the mass of fine material measured immediately after sieving the
                       sample in the field (g); and

               Mcoarse is tne mass °f coarse material measured immediately after sieving
                       the .sample in the field (g).
Then, to  determine  the concentration  of  asbestos in the environmental matrix  that was
sampled, perform the following adjustment:
                   Cmtrx = CF*Csmpl
                                                                (11-19)
           where:                                                 .
               CF     is the coarseness adjustment factor for a particular sample (derived
                       as defined above);

               Cmtrx   is the concentration of asbestos structures (of a defined size range
                       or type) in the field matrix sampled '(s/g); and          :

               Csmp,   is the concentration of asbestos structures (of a defined size range
                       or type)  in  the  sample  sent to the  laboratory  (s/g).   This  is
                       determined as described in Sections 11.4.1 and 11.4.2 above.
                                         11-14

-------
      12.0  PERFORMANCE CHARACTERISTICS AND QUALITY CONTROL/QUALITY
                             ASSURANCE REQUIREMENTS
12.1   METHOD PERFORMANCE

The method defined in this document achieves the target performance requirements defined
in Section 2.1  at a cost that should be  competitive with  other procedures that might be
designed to produce comparable information (Section 2.4).

       12.1.1   Analytical Sensitivity

As  indicated in Section 11.1,  depending on sample characteristics,  between 1 and'8 grid
openings will likely  have to be scanned  at high magnification  (20,000x) to achieve the target
analytical sensitivity for total asbestos structures of 5x107 s/gso|id.  Similarly, between 15 and
133 grid  openings will likely have to be scanned at low magnification (10,000x) to achieve the
target analytical sensitivity for long asbestos structures (longer than 5 |im) of 3x106

The defined sensitivities for total  and long structures were, easily
study for the method (Berman et al 1994a).

       12.1.2  .Precision
                                                                              the pilot
Results of the pilot study for this method  (Berman etval,1994a) indicate that, when  50
structures are counted, the average relative percent difference observed among eight sets of
duplicate samples (four sets  of duplicate  samples analyzed by each of two laboratories) is
20%.                             ,

The precision of an  asbestos measurement (in this case, expressed as the relative percent
difference)  should be inversely proportional to the square root of the number of structures
counted. Given that 1 0 structures are likely to be counted at the target concentrations for this
method (see Section 2.1.1) and, based on the precision observed in the pilot study when  50
structures are counted, it is expected that the average relative percent difference achievable
for  this method should be 43% at the target concentrations listed in Section 2.1.1.  Thus,
given the  analytical sensitivities defined in Section  2.1.1 and the stopping rules defined in
Section 11.1, this method is capable of achieving a level of precision that is comparable with
the guidelines recommended  in the CLP for the analysis of other, analytes in soils and defined-
f or this method in Section 2.1.2.                                              -     -

The precision observed during the pilot study for this method  is based on specimen grids
prepared from the suspension collected in the scrubber of the  elutriator (Appendix A). It is
expected that the precision  achieved  for analyses derived  from scans of  specimen grids
derived by direct preparation  of filters collected over the isokinetic sampling tube of the dust
generator  (see Appendix A) will be significantly worse.  Procedures are therefore incorporated
into this method in which the majority of samples will be analyzed based on preparation of
specimen  grids from filtered scrubber suspension with a subset of 5 to  10% simultaneously
analyzed using specimen grids prepared by a direct transfer technique from filters collected
over the isokinetic sampling tube  of the elutriator (see Chapter 10).  The latter is required to
develop a regression relating  these two types of preparations so that measurements  can  be
evaluated  using existing  dose-response  factors for asbestos (see Section 2.1.3);  existing
                                         12-1

-------
 dose-response factors  tend  to  be based on the analysis of samples whose  preparation
 corresponds most closely to a direct preparation.
       NOTE

       It is  anticipated that a direct, linear relationship will be observed between  asbestos
       concentrations  derived,  respectively,  from  scrubber suspension and from  filters
       collected over the  1ST opening  of the elutriator for samples collected from the same
       environmental matrix.  However, there is little reason to expect that such a relationship
       will hold across samples collected from different environmental  matrices. Therefore,
       samples to be employed to determine the relationship between asbestos  measured
       from scrubber suspension  and from  filters  mounted over the  1ST opening of the
       elutriator should be selected and  evaluated separately for  each  environmental matrix
       sampled during a study for analysis using this method.

 It must be recognized that compromises are required when developing a method of this type.
 The proposed  reporting of samples prepared primarily by an indirect technique with a small
 subset of directly prepared samples (the latter used primarily to  provide a link between the
 reported measurements and existing dose-response factors) represents such a compromise.

 The proposed procedure allows for the determination of relative concentrations with maximum
 precision so that arbitrarily small differences in concentrations can be easily  distinguished.
 Among other things, this will facilitate distinguishing upwind and downwind concentrations by
 a  source.   At  the same time, somewhat lower precision  is  considered  acceptable  for
 estimating the absolute risk associated with any particular measurement.


       NOTE

       The uncertainty of the proposed regression to link results from directly and indirectly
       prepared samples  is  expected to be attributable almost  exclusively to.the limited
       precision of the directly prepared samples.  Therefore, use of the proposed regression
       for estimating  risks may not  significantly increase the uncertainty  of such a  risk
       analysis beyond what would  be associated  with  assigning an  estimated risk to an
       asbestos concentration derived from a directly prepared sample in any case.

       It  is also assumed that a sufficient number of samples (i.e. a minimum of approximately
       10) will be co-prepared and analyzed to allow reasonable confidence in the  results of
       the regression.                                               '

       12.1.3    Accuracy

 Based on the results of the pilot study (Berman et al. 1994a), there appears to be a problem
with laboratory bias during the counting  of asbestos structures in support of this  method.
The bias is  introduced specifically during the analysis of specimen grids because  duplicate
samples  prepared by the same laboratory  using  identical  procedures nonetheless  yield
significantly  different counts by analysts from each of two laboratories.
                                         12-2

-------
 Given that  analysts within a single laboratory appear to be capable  of achieving  good
 agreement  on counting (also  demonstrated in the pilot study), the  problem of between-
 laboratory bias will  need  to be addressed  by the implementation  of an aggressive  inter-
 laboratory quality control  (QC)  program  in which samples are regularly shared  among
 laboratories and a procedure for verified  counting  is instituted... It may also be useful  to
 promote  meetings with discussion  sessions in  which analysts  from different  laboratories
 discuss  the  interpretation of  structures  viewed  simultaneously  (either directly from  a
 microscope or from a video).     \              ,                                 ,

       12.1.4    Asbestos  Characteristics,
   v              .                        '            '                      '
 As was observed during the pilot study (Berman et al. 1994a), this method is easily capable
 of preserving  information concerning the distribution of the sizes and shapes of asbestos
 structures that are likely to be released from environmental matrices that are disturbed by
 natural or anthropogenic forces.  As indicated in Section 2.1.3, such'information is critical  to
 evaluating the potential health  effects  of the asbestos dusts  generated by  releases from
 asbestos-containing matrices (see, for example,  Berman and Crump 1989).

 Interferences  and limitations concerning  the ability to identify and characterize asbestos
 structures using the counting and identification rules of the ISO Method,  as adopted for this
 method (Section 11.1), are  described in the ISO Method (Chatfield 1993).
        '   -                • (                  ,        ' '  -*„         •        •          .
       12.1.5    Reporting Requirements

As indicated in Section 11.4, the concentrations of asbestos structures (of any defined size  or
type) that are  measured using this method can be easily reported either as a function of the
mass of the sampled material or as a function of the mass of respirable dust in the sampled
material.   This should allow sufficient flexibility to facilitate use of results from this method  in
concert with any of the fate, and transport models that may be employed to predict exposure
(Section 2.1.4).                             .

12.2   QUALITY CONTROL REQUIREMENTS

The  quality assurance/quality  control  (QA/QC) requirements indicated in the ISO Method
(Chatfield 1993) shall be considered relevant and appropriate when using this method.  In
addition,   the  following  blank -and  duplicate/replicate schedule  shall be employed  when
running samples using this  method.                         "                        .-..-_

       12.2.1   Blanks
                                 ' •        .    '•        *•> '        '         .    • .
The following blanks shall be collected routinely in concert with use of this method: ,

            lot blanks or filter blanks. Two filters from each lot of 50  filters obtained from the
            manufacturer shall be prepared using a direct transfer procedure and analyzed  to
            assu're that background  contamination  on the  filters does not- exceed 10s/mm2
            (Section 6.6).  Only filters from lots whose blanks pass the defined criterion shall
            be used in support of this method;

            laboratory blanks.    A sufficient number of  laboratory blanks shall be collected,
            prepared using a direct transfer technique and analyzed to show that the room in
                                         12-3

-------
            which bulk samples are handled and prepared satisfy the requirements defined in
            Section 10.6 of Chatfield  and Berman '(1990).  When laboratory blanks indicate
            that room air is out of compliance with the stated criterion, use of this method is
            to cease until appropriate  corrective actions are completed;

            field  blanks.    Field  blanks  shall  be collected  during  any sample collection
            activities performed in association with use of this method.  The number of such
            blanks to be collected and the schedule for their analysis shall  be  determined
            based on  the complexity of the anticipated sampling  scheme and shall be
            defined as part of the sampling plan for the site.  QC criteria for field  blanks will
            also be set as part of the planning for the study;

            equipment blanks.  Equipment blanks are collected at the beginning of each run
            of the dust  generator, as  described  in Section 9.4.3.  Equipment blanks do not
            generally need to be analyzed on a regular basis but shall be stored in case their
            use is required to help  determine  the  source  of contamination that  may be
            discovered by some other means;

            run blanks.  Run blanks are also collected  at the beginning of each  run  of the
            dust generator, as described in Section 9.4.3. One run blank shall be analyzed
            routinely for the first run completed on any particular sample.  The remaining run
            blanks generated in association with a particular sample shall be stored in case
            their use is  required to help determine the source of contamination that may be
            discovered by some other means.

            Should asbestos structure counts on  run blanks exceed the target  criterion of
            10s/mm2,  use of this'method shall cease until  appropriate corrective actions
            have been  completed  and new run blanks are shown to achieve  the  stated
            criterion; and                                             „

            scrubber blanks.  Scrubber blanks shall be derived by collecting a 1 ml aliquot of
            scrubber liquid (after the scrubber is loaded and assembled for a run  but before
            heating of the scrubber is initiated), diluting  the aliquot to 10 ml, and completing
            the preparation of the diluted  aliquot as described in Section  9.4.6.   Scrubber
            blanks do not need to be analyzed routinely  but shall be stored in

            case their use is required to help determine the source of contamination that may,
            be discovered by some other means.

In addition to the above listed blanks that must be collected routinely in association with use
of this method, the following may prove helpful for identifying the source of any contamination
that might be detected in association with use of the dust generator:

            modified run and  scrubber blanks.   Modified run and scrubber blanks may be
            generated by setting  up and operating a clean dust generator without sample.
            Filters may  be collected  from either the ME or the  1ST opening of the dust
            generator at. any point of such a run.  Similarly, aliquots of scrubber liquid may
            be withdrawn from the scrubber at any point. Such blanks may prove useful for
            determining  whether  contamination  is being  introduced  by any   of  the
            components of an operating dust generator (including, for example, the constant
                                         12-4

-------
            humidity solution, the  rotating tumbler,  the elutriator tube, the air transfer lines,
            and/or the glassware or liquid of the boiling scrubber); and

            post-run scrubber blanks.  , A  post-run  scrubber blank may be  generated  by
            repeating  the  rinse  of the transfer lines,  condensers, and  scrubber  flask
            immediately after the quantitative  rinse conducted for a particular sample (see
            Section 9.4.6).   The resulting liquid must then be weighed, diluted quantitatively,
            and prepared in the same manner as  described for the scrubber suspension of a
            sample (Section 9.4.6).   The normalized concentration of asbestos structures
            found in such a blank shall represent no more than 10% of the concentration of
            asbestos structures observed   in the  sample  prepared  immediately  prior to
            collecting the post-run blank.   Higher blank concentrations shall be considered
            unacceptable.  If blank concentrations are observed, procedures for quantitative
            rinsing shall be  reviewed, modified, and tested  until losses can be shown to be
            acceptable.                                                •
           NOTE                                                                     -
                                          '-      -* '
           Asbestos observed  in post-run blanks constitute asbestos that is lost from a
           sample during preparation.                     '  .
       12.2.2   Duplicates/Replicates

A fixed fraction (5 to 20%) of the samples collected in the field in support of this method shall
be collected as spatial duplicates ('two samples collected at immediately adjacent locations).
These shall be labeled and sent to the laboratory in such a manner so as to  assure that
laboratory  personnel  cannot identify them as  duplicates.   The frequency  of collection of
spatial duplicates shall be defined as part of the sampling  plan for the site.   Comparison of
the results of the analysis of such samples provides a measure of all of the  components of
total precision except population variability.


As indicated previously (Section 8.2.1), 100% of the samples shipped from the field are to be
shipped  as duplicate  pairs.  The  laboratory shall randomly select 10% of the duplicate
samples  shipped from the field and shall analyze both samples  of  the pairs so selected.—
Comparison of the results of the analysis of such samples, which are homogenized splits of
the same sample, provides an Indication of the precision achieved by  sample preparation and
analysis.                   ,

Should analysis of duplicate pairs indicate an unacceptable  degree  of variability (i.e. a relative
percent difference greater than 50%),  replicate counts shall  be  performed  on designated
samples  by multiple analysts in the laboratory  (or by the same analyst on  different days).
Laboratory management shall  assign such  counts so as  to  assure that analysts cannot
determine  which  counts are replicates.  Results of such  replicate counts shall  serve to
distinguish,whether the major source of variability observed among duplicate pairs is due to
analysis or to sample preparation. Appropriate corrective actions may then be devised.
                                         12-5

-------

-------
                          13.0 REPORTING REQUIREMENTS
13.1   FIELD AND LABORATORY NOTEBOOKS

Over the course of the project, information critical to the proper reporting and interpretation of
each  sample analysis will be developed both in the field  and in the laboratory.  .Formal
procedures are required to preserve such information and to allow for the documentation of
attendant information  that, while  not  employed  directly in  the calculation  of  results, may
provide insight into the interpretation of such results.

       13.1.1   Field Notebooks

During  sample collection, detailed  notes will be  kept in  a  stan'dard field or  laboratory
notebook that is bound and  pre-paginatedi  All entries to the notebook are to be  dated and
initialed.   Information  to  be  recorded during sample  collection should include (but  is not
limited to):                .                                          ,

       (a)  reference to this method;                            '

       (b)  the project title,  identification of the site, and  the  names and titles of field
           personnel participating in the sampling effort;          •,

       (c)  identification of each sample or fraction of each sample handled in the field;

      '(d)  the date and time that each sample was collected and the time interval during
           which each sample was prepared in the field;

      (e)  the location  from which each  sample was collected  and the manner in  which
           sample locations were selected (including  reference to the sampling plan  under
           which sampling was conducted);                           .

      (f)  - a general description of the physical appearance of the materials sampled;

      (g)  the types of equipment and the procedures employed to collect each sample;

      (h)  a summary of the procedure employed for field  preparation of each sample"	
           (including, for example, the number of passes through a riffle splitter employed
           for homogenization, and the number  of splits required to reduce the  sample to
           the size required);

      (i)   the relevant identities and weights of each fraction of sample handled during field
           preparation (including  specifically the weights of the coarse  and fine fractions
           separated from each sample during sieving);                  ,     ^

      (j)   other  relevant field observations (including,  for example, the meteorological. ,
           conditions under  which sampling was conducted); and

      (k)   the identification, weight, and  intended destination of each sample shipped from
           the field.
                                        13-1

-------
      13.1.2   Laboratory Notebooks                   .-.'.-

During sample handling, preparation, and analysis, detailed notes will be kept in a laboratory
notebook that is bound and pre-paginated. All entries to the notebook are to be dated and
initialed.  Information to be recorded during sample  preparation and analysis should include
(but is not limited to):

      (a)  reference to this method;    .  •'     '     .

      (b)  identification of each sample 'or fraction of each sample received from the field
           and the date and time that each sample was received;

      (c)  identification of all laboratory personnel who participate  in the preparation and
           analysis of samples and the specific operations performed by each;

      (d)  identification  of reagents,  equipment,  and  supplies  employed  during sample
           handling, preparation, and analysis;

      (e)  relevant material weights and/or volumes;

      (f)   the  lot number  and   manufacturer of the filters  employed during  sample
           preparation;

      (g)  a summary of the procedure employed for laboratory preparation of each sample
           (including, for  example, the number of passes through a riffle splitter employed
           for homogenization and the number of splits required to reduce the sample to the
           size required);

      (h)  the relevant identities  and weights of each fraction of sample handled during
           laboratory preparation;

      (i)   the setup conditions employed for the dust generator (including, for example, the
           identity of the salt employed for  humidity control,  air flow conditions, and the
           setting on the variable voltage transformer employed for the scrubber);

      (j)   the date and starting time, description (including, primarily, the tumbler rotational
           speed), and sample identification for any run conducted on the dust generator;

      (k)  the weight and identity of the sub-sample placed in the dust generator;

      (I)   the identities, time intervals of collection, the starting and ending weights, and the
           net weights of filters collected during a run on the  dust generator that are to be
           used to determine the rate of dust generation;

      (m)  the figures and calculations employed to determine the rate of dust generation
           and the quantity of dust in the sample;

      (n)  the identity, time interval of collection, starting and  ending weights, and the net
           weights of filters collected during a run on the dust generator that are to be used
           to generate specimen grids for asbestos analysis;
                                         13-2

-------
       (o)  the identity, time interval of collection, the weight/volume, dilution factor,  aliquot
            identification, and filter identification for the collection, handling, and filtering of
            scrubber suspension;

       (p)  the identity of all filter sections used for preparation of specimen grids and the
            identity of the  specimen  grids (include  a description of the sector and radial
            distance from the center of the filter represented by each section);

     .  (q)  energy levels and settings for.instruments employed for analysis;

       (r)   flow rates, pressures, temperatures, and other relevant physical parameters that
            potentially impact prpcedures;

       (s)   room  conditions  (i.e.  temperature, relative  .humidity,  and ventilation   rates)
            prevailing during sample preparation;

       (t)   other relevant observations (including, for example, any difficulties encountered
            during preparation and analysis and any procedural  changes  incorporated into"
            the method that are necessitated by such difficulties);

       (u)   documentation  of all  calculations  performed in support  of  preparation and
            analysis;

       (v)   all relevant QA/QC measurements (including  the results of the analysis of all
            blanks, duplicates, and replicates-see Chapter 12); and

:       (w)  a detailed time log of events including the time that particular procedures are
            initiated and completed for each sample.

13.2   FIELD ACTIVITIES REPORT

To assure that the field information required to complete estimation of dust and asbestos
concentrations and release  rates are provided to the data  users, a field activities report must
be completed and must  be  submitted to the laboratory  along  with  the corresponding
samplesi  Laboratory  personnel are then to attach this report directly to their batch  report,
which shall cover the corresponding batch of samples.

The field activities report shall include the following for each sample batch, at a minimum:

       (a)   the project title and the identification of the site;                 •

       (b)   reference to this method;                   ,

       (c)   reference to the sampling and analysis plan under which samples were collected;
                              '                                      •*'                   i
       (d)   a brief description of the objectives for sampling;

       (e)   a brief description of the  procedures employed for selecting sampling locations
            and the motivation for employing such procedures;
                                          13-3

-------
       (f)   for'each sample in the batch accompanying the report:

                the identifier for each sample fraction submitted to the laboratory;

                the identifier  for the  original sample from which each  submitted sample
                fraction was derived;      _

                the type of equipment and reference  to  (or a brief description of)  the
                procedures employed for collection of the original sample;

                the coordinates at which each original sample was collected36;

                the total mass of the  original sample from  which each sample fraction
                originated and the masses of the coarse and fine fractions separated during
              ^sieving of the sample in the field;

                a brief description of the procedures employed for  sample homogenization
                and for sample splitting;

          •  -    the date and time that each sample was collected and the date and time that
                each sample fraction was prepared in the field; and

                a brief discussion of any deviation from the sampling and analysis plan not
                covered in e.

An example of the format to be employed for a field  activities report is provided  in Figure
13-1.                                                .

13.3   SAMPLE ANALYSIS REPORT

The sample analysis report for each sample shall include the following at a minimum:

       (a)   reference to this method;

       (b)   reference to the sample identification and batch number for the sample;

       (c)   the date and site from which the sample was collected;

       (d)   the weights and identities of the coarse and fine fractions of the sample and the
            sub-sample of the fine fraction sent for analysis;

       (e)   the weights and identities of any splits or other fractions of the sample generated
            during laboratory preparation;

       (f)    the weight and identity of the sub-sample placed in the dust generator;
      H the submitted sample fraction is a sub-sample of a composite, what should be described here is the specific area of
      concern (or portion thereof) that is intended to be represented by the composite),


                                      .   13-4                             '

-------
                                                                     FIGURE 13-1
                                                          FORMAT FOR THE FIELD ACTIVITIES REPORT
Name of field activities contractor
Address of contractor
     Contact Name
    . Telephone Number

PROJECT/SITE:
     Name
     Address
METHODS AND PROCEDURES:
      Field Investigation Design: (Reference the sampling plan)
      Sample Collection and Handling: (Reference this method)
SAMPLING OBJECTIVES:   >
      (Complete a brief description here)
SAMPLING LOCATION SELECTION PROCEDURE:
      (Complete a brief description here)
Report Title:
Report Number:
Date
SAMPLE DATA
Field
Sample
Number

Location
Identifiers

.
•'
Mass of
Sample
•.
• .
• .
'
Mass
Fine
Fraction
. .
Mass
Coarse
' Fraction

Mass
Sample
Split
" • .;•'
. *
.
. - Mass
Duplicate
Split
.
-
Sample
Split
ID
.-
,'
Duplicate
Split
ID
,
'
V
Date
.Sampled

.' :
                                                                                                                 Time | Comments:
                                                                                                             Sampled |
                                                                                                                     | (Include Identification
                                                                                                                     j of all field sampling
                                                                                                                     \andfieldpr0paratlon
                                                                                                                     j procedures employed)

-------
 An example of the format to be employed for a sample analysis report is presented in Figure
 13-2.

 13.4  SAMPLE BATCH REPORTS                                     •

 In addition to the sample analysis report for each sample, provide a summary page for each
 batch of samples representing an entire project. The summary sheet shall include: .

       (a)  the project title;

       (b)  reference to this method;

       (c)  the  date that samples were collected,  the date they were  received  by the
           laboratory, and the date they were analyzed;

       (d)  a summary listing of sample results including:

               the sample number;

               the estimated concentration of respirable dust in the sample;

               the analytical sensitivity achieved for each size/type category of interest;

               the total number of structures of each size/type category of interest counted;

               the  concentration of asbestos  structures  of each  size/type  category of
               interest in the sample  and in the respirable dust of the sample (both reported
               along with corresponding 95% confidence limits); and

               the  concentration of asbestos  structures  of each  size/type  category of
               interest estimated for  the environmental  matrix that was sampled in the field
               (reported along with corresponding 95%  confidence limits).

An  example of the format to be employed  for sample batch  reports  is presented 'in Figure
13-3.
                                         13-7

-------
                                             !      FIGURE 13-2
                                        SAMPLE ANALYSIS REPORT FORMAT
Laboratory Name
Laboratory Address •
      Laboratory Contact
      Telephone Number
Date Analysis Started (M/D/Yr) '
Date Analysis Completed (M/D/Yr)
Analyst(s) Initials

Laboratory Sample No.
Field Sub—Sample Identification No.
Field Preparation Technique (Attach a Copy of the Relevant Field Activities Report)
Additional Laboratory Preparation Procedures (describe any employed)          '
      Sample Drying
      Sample Splitting
      Other

TEM Analysis:                                ,
      Effective Area of Analytical Filter (sq mm)  ,
      (Indicate whether from Scrubber or from 1ST Opening)
      Magnification                              ,                          ,
      Grid Opening  Area (sq mm)
      Number of G.O. Scanned
      Asbestos Structure Size and Type Categories of Interest (see Chatfield 1993)
      Minimum Acceptable Structure Identification Category (see Chatfield 1993)

Dust Generator
      Mass of Sample Tumbled (g)       i  •  !  '•.     -
      Air Flow Rate Through ME Opening of Dust Generator (ml/min)
      Air Flow Rate Through 1ST Opening of Dust Generator (ml/min)
      Air Flow Rate Through Scrubber (ml/min)          . •
      Estimated Totat Air Flow Rate Through Elutriator (ml/min)

      Total Mass of  Dust Collected on Dust Filters (g)
      Time of Dust Collection (24 hour clock) at 30 rpm
            Start:           •       ..'•.'•-
            Stop:                            ,       .
     'Time of Dust Collection (24 hour clock) at 60 rpm
            Start:            •
            Stop:   ,             ,
      Estimated first—order rate constants-for dust generation (min"1)
            At 30 rpm:        •                  ,   -
            At 60 rpm:
      Estimated Starting Mass of Respirable Dust in Sample (g)
            (Attach time plots and calculations)

Samples from the Scrubber Suspension
      Total Volume of Scrubber Suspension (ml)                                  '
     - Estimated Mass of Dust Collected in Scrubber Suspension (g)
      Volume of Aliquot Withdrawn from Scrubber Suspension (ml)
      Volume into which Scrubber Aliquot Diluted (ml)      -
      Dilution Factor (dimensionless)          .   ,
      Volume of Aliquot Filtered (from Diluted .Suspension) (ml)

Samples from the Isokinetic Sampling Tube (1ST) Opening of the Dust Generator .
      (indicate whether 30 or 60 rpm run)                 '
      Time of Collection (24 hour clock)
  .  •        Start:
          :  Stop:        •'•,'•                            -      '     '
      Estimated Mass of Dust Collected on Filter             -                 •    '
Report Date
Project Name (Optional)
METHODS:'
                                                                                              (reference this method)
                                                   Page 1 of 2

-------
                                                  FIGURE 13-2
                                    SAMPLE ANALYSIS REPORT FORMAT (Cont.)
 Laboratory Name

 Laboratory Sample No.
                               Report Date
Chrysotile Asbestos Analysis Results:
      No. of Total Chrysotile Asbestos Structures
      No. of Long (> 5 um) Chysotile Asbestos Structures'
      No. of Total Chrysotile Asbestos Fibers/Bundles
      No. of Long (> 5 um) Chysotile Asbestos Fibers/Bundles
                                                            Low
                                                        Magnification
            High
         Magnification
XXX
XXX
                                                            Low
                                                        Magnification
            High
         Magnification
Amphibole Asbestos Analysis Results:
      No. of Total Amphibole Asbestos Structures                XXX
      No. of Long (> 5 um) Amphibole Asbestos Structures
      No. of Total Amphibole Asbestos Fibers/Bundles            XXX
      No. of Long (> 5 um) Amphibole Asbestos Fibers/Bundles

      (Indicate Amphibole Mineral Type)

ESTIMATED CONCENTRATIONS OF RELEASABLE ASBESTOS IN SAMPLE
                                                         .  Cone.      95%UCL
      Total Chrysotile Structures per g Sample:                    '
      Total Amphibole Structures per g Sample:-
      Total Asbestos Structures per g Sample:  •       .
      Long Chrysotile Structures per g Sample:
      Long Amphibole Structures per g Sample:
      Long Asbestos Structures per g Sample:

      Estimated Analytical Sensitivity: (structures/g sample)

ESTIMATED CONCENTRATIONS OF RELEASABLE ASBESTOS IN RESPIRABLE DUST OF SAMPLE
                                                           Cone.      95%UCL
      Total Chrysotile Structures per g Dust:
      Total Amphibole Structures per g Dust:
      Total Asbestos Structures per g Dust:
      Long Chrysotile Structures per g Dust:
      Long Amphibole Structures per g Dust:
      Long Asbestos Structures per g Dust:

      Estimated Analytical Sensitivity: (structures/g dust)
(Attach a Copy of the TEM Raw Data Sheets)
                                                 Page 2 of 2

-------
                                                           FIGURE 13-3
                                                  SAMPLE BATCH REPORT FORMAT
 Laboratory Name
'Laboratory Address
      Laboratory Contact
      Telephone Number
 RELEASABLE ASBESTOS.IN-RESPIRABLE DUST
Report Date'
Project Name (Optional)

METHODS:
 (reference this method)
Laboratory :
Sample I. D. \Respirable
Dust
Cone
(g/gsmpl)

Total
Asbestos
•'.. Analytical
Sensitivity
(s/g dust)
"•" • '
RELEASABLE ASBESTOS IN LABORATORY SA
Laboratory
Samplel.D. -
RELEASABLE /
Laboratory •
Sample!. p,

Respirable
Dust
Cone
. (g/g smpl)
'.
ASBESTOS IN Fl
Field
Samplel.D.

Total
Asbestos
Analytical
Sensitivity
(s/g smpl)
Long
Total , Total Asbestos
Asbestos Asbestos Analytical
. ,Conc 95% UCL Sensitivity
(s/g dust) (s/g dust) (s/g dust)
-': ' '.V '•'• •' . ' ' '
. - .
:. -" • ' ' .-. •'.
MPLES - -
Total
Asbestos
Cone
(s/g smpl)
ELD SAMPLE MATRICES
~
Mass
Fine
Fraction
(g)

.
Mass
Coarse
Fraction"
-(g)

Long
Total Asbestos
Asbestos Analytical
95% UCL _ Sensitivity
(s/g smpl) (s/g smpl)
Dust Dust | Comments;
-Long 'Long Generation Generation |
Asbestos Asbestos Rate Rate |
Cone 95%UCL .'(atSOrpm) (at60rpm)|
... (s/g dust) . (s/g dust) "(min'1) (min-1) j
• 1
"•-" ' • '•:•• - \ ";
•'-..••• i
- • • -, - - i .-
- \ "
Long'
Asbestos
Cone
(s/g smpl)
.';' . I...
Adjusted Adjusted Adjusted
Respirable Total Total
Dust Asbestos Asbestos
: Cone Cone 95% UCL
(g/gmtrx): (s/gmtrx) (s/grritrx)
:.
._ Long
Asbestos
95% UCL
(s/g smpl)

Adjusted
Long
Asbestos
Cone
(s/g mtrx)

Comments: ' " ' . -.
•'• ''.[..'.• • ; • •'•

Adjusted | Comments:
Long.
Asbestos
95% UCL . . . .
(s/gmtrx)
-

-------

-------
                                  14.0  REFERENCES
 Berman, D.W. and Kolk, A.J.  "Performance  of a  Dust Generator Designed to Support the
 Determination of Asbestos in Soils and Bulk Materials." 1994. In Preparation.

 Berman, D.W.; Crurrip, K.S.; Chatfield, E.J.; Davis, J.M.G.; and Jones, A.  The Sizes, Shapes,
 and Mineralogy of Asbestos Structures that Induce Lung Tumors or Mesothelioma in AF/HAN
 Rats Following Inhalation."  1995. Risk Analysis 15/2/181 -195.

 Berman, D.W. and Chesson, J.  "A  Superfund  Guide:  Development of Effective Sampling
 Strategies for the  Investigation of Asbestos-Related Hazards."  USEPA publication, undated.
 Under EPA review.            .

 Berman, D.W.; Kolk, A.J.; Krewer, J.A.; and Corbin, K. "Comparing Two Alternate Methods for
 Determining Asbestos in Soils and Bulk Materials." Session-Chair. Session presented at the
 Eleventh Annual Conference  and Exposition  of the Environmental Information Association.
 San Diego, March, 1994a.

 Berman, D.W.; Kolk,  .A.J.; Krewer,  J.A.;  and Corbin, K. "Pilot Study  Results."   (1994b)
 Unpublished.

 Berman, D.W.  'The Search for  a  Method Suitable  for Supporting Risk Assessment:  The
 Determination of Asbestos in Soils and Bulk Materials, A Feasibility Study." USEPA publica-
tion, 1990.  Under EPA review.                                     .

 Berman, D.W. and Chatfield,  E.J.   "Interim  Superfund Method for the Determination of
Asbestos in Ambient  Air, Part 2:   Technical  Background Document."   USEPA publication •
540/2-90/005b, May 1990.                                               :

Chatfield, E.J. "Ambient Air: Determination of Asbestos Fibres, Indirect-Transfer Transmission
Electron Microscopy Procedure."  Submitted to: ISO/TC 146/SC 3. 1993.

Chatfield,  E.J. and Berman,  D.W.    "Interim  Superfund Method for the Determination  of
Asbestos in Ambient Air, Part 1:  Method." USEPA publication: 540/2-90/005a,  May 1990.
                                        14-1

-------

-------
    '             APPENDIX A:




CONSTRUCTION AND OPERATION OF A DUST GENERATOR

-------

-------
                                     APPENDIX A:
              CONSTRUCTION AND OPERATION OF A DUST GENERATOR
              FOR ISOLATING THE RESPIRABLE FRACTION OF MATERIAL
                       FROM SOILS OR OTHER BULK SAMPLES
 The dust generator incorporated into this method for the determination of asbestos in soils
 and bulk materials is designed to  isolate the respirable fraction of material (including the,
 releasable fraction  of respirable asbestos)  that  is present within the  matrix of the parent
 sample.  A description of the apparatus is provided below along with a brief discussion of the
 theory of its operation.  Figures depicting design of the prototype are also provided in the last
 section of this appendix to facilitate design and construction of similar equipment.

 A.1    DUSt GENERATOR DESCRIPTION

 The dust generator is, composed of a tumbler, a vertical elutriator, a dust collection system,
 and a scrubber.  A schematic diagram of the apparatus is presented in Figure A-1 and a
 photograph of the apparatus is shown in Figure;A-2.  The appurtenant equipment required to
 operate the dust generator is also shown in Figure A-2. This includes: .'

       •     . a DC motor to drive the tumbler;    >

       •      a constant humidity chamber to control the humidity of the air that flows into
            .the dust  generator, This is the clear plastic box enclosing the tumbler in the
             photograph;

       •      the pumps required to create an air flow through the dust generator and the
             flow controllers required to monitor and apportion air flow through the various
             filters and the scrubber; and                                 •   •  •  ,   ,

       •      the heating mantle, variable voltage transformer,  and  cooling towers required
             for the scrubber.                                  .

       A.1.1  The Tumbler

The  tumbler is  located in the clear plastic  enclosure  at the bottom of the  dust generator
 (Figures A-2 and A-3).  It is a long shallow tube of square cross section  that is approximately
 1 and 1/8 inches in height and width and has an overall length of 10 inches (Figure A-4).

The  tumbler is driven by a variable speed DC motor,  which  rotates the  tumbler around its
long axis. The tumbler's rotation rate can be varied over the range of 10 to  150  revolutions
per minute (rpm).,  The DC  motor  is attached to,the  tumbler  using a slip-on type flexible
coupling  so that they can be  readily detached simply by pulling the motor  away from the
tumbler.  The tumbler can also  be readily detached from the connection tube to the elutriator;
they are  connected with a slip fit over the  outer race of the ball bearing assembly that is
welded-to the end of the tumbler (Figure A-4).                    '
                                        A-1

-------
                                FIGURE A-1

                     SCHEMATIC OF DUST GENERATOR
                                To Pumps
            Slide Mechanisms
ME Opening From Elutriator

                   To Scrubber
To DC
Motor
                                         Dust Filter Cassettes
                                         and Mounts
               Tumbler
                                     \
                                          \   - 1ST Opening From Elutriator

                                          To Scrubber
                                           *• Isokinetic
                                           Sampling
                                           Tube
                                           ^Elutriator
                                         Auxilliary Air Inlet

-------
  ^ Ffov/  -  -.1

Contfol Valves -
 p.C. Motor-.'/

  Controller s
  Qonstant  '~'
  Humidity ;';.
  .Chamber / -,}
                    .--<
                   D,C;Motor<^ Tumble  '   :".

-------
                                                  FIGURE A-3

                                 TUMBLER IN CONSTANT HUMIDITY CHAMBER
Front Opening
 to Humidity
  Chamber
 Salt Solution
    Trays
           D.C, Motor
 Friction
Coupling
Air Inlet to
 Tumbler
Tumblef
 Body
Ball Pearing
 Assembly
' Entrance fo
the Eiutrtator  ,

-------

-------
       NOTE

       The seal between the tumbler and elutriator need not be air tight. In fact, a small leak
       at this fitting will reduce the chance that  particles discharged  from the tumbler will
       settle in the entrance tube to the elutriator. However,  such a leak must not be more
       than 10% of the total airflow through the tumbler.  '  -
Once the tumbler has been detached from the motor and elutriator, it can simply be lifted out
of the constant humidity chamber.

The top cover of the tumbler is secured with 10 screws and can be removed so that the
tumbler can be loaded or cleaned (Figure A-4).  A rubber gasket is  employed to assure an
airtight seal between the tumbler cover and body.

       A.1.2  The Constant Humidity Chamber

The plastic enclosure that houses the tumbler and isolates it from  outside air, except for an
opening at the top front  of the  enclosure,  is  designed  as a constant humidity chamber
(Figures A-2 and A-3).  Air drawn  into the front of the  enclosure flows successively over two
trays (located on shelves at -the top  of the enclosure) before being drawn  into the tumbler.
The trays are designed to hold a saturated salt solution that is  selected to exhibit a vapor
pressure equal  to the relative  humidity  desired  for running the  dust generator.  The path
length over the two trays is designed  to assure that air drawn through the device will come to
equilibrium at  a relative humidity within a few percent of the desired value (assuming that the
outside air exhibits a starting humidity within the range common to  Pasadena, California1);
the path length must be  sufficient to allow adequate exchange of vapor between the salt
solution and the moving air.

For most studies, a relative humidity of approximately 50% should be  employed because this
is the humidity at which emission of asbestos is expected to be maximum (Zimon, A.D. 1982).
At higher humidities, air moisture tends to wet surfaces  so that aggregation decreases particle
release.   At  lower  humidities,  electrostatic effects tend  also to  cause aggregation and,
therefore, also to decrease emissions. A saturated solution of potassium carbonate dihydrate
is recommended for most applications because such a solution maintains equilibrium with air
at  43%  relative humidity at room temperature (20° C) with less than  1% change in humidity
over a range of temperatures varying  by  several degrees on either side of room temperature.

For special applications of this method, where dust generation  is to be run at  a  different
relative  humidity than that produced over a saturated solution  of potassium  carbonate
dihydrate, the  conditioning pans in the dust generator may be filled with  a saturated solution
of  another, salt.  Such salts may be selected to yield  any of a broad range of conditions.  For
example, the  International Critical Tables  provides a  list  of  saturated salt  solutions that
maintain equilibrium with a broad range of relative humidities in air.
       The prototype device was constructed and tested in Pasadena.  The design of the constant humidity chamber may
       have to be modified slightly (e.g. by increasing the number of trays) for operation in other locale's.

                                          A-6                               .

-------
       A.1,3  The Vertical Elutriator

 The vertical elutriator is  the  tail metal cylinder visible  in Figure A-2.  Its dimensions were
 selected to assure that the path length traversed by particles  in the elutriator. is at least 10
 times'the  diameter  of the elutriator (in the direction perpendicular to the air flow).  Thus,
 channeling is expected to be minimized (Dennis, R 1976).

 The elutriator separates respirable from non-respirable  particles and respirable particles are
 passed on to dust collection filters and the scrubber.  Air flow within the elutriator is adjusted
 to a velocity such that only those particles in the respirable size range will  be lifted to the top.
 The velocity of air selected for the elutriator determines the  rate of air flow through all of the
 other parts of the dust generator.                .                              ,    .

 The main body of the elutriator is composed of two, 20 in. sections of 4-in. i.d. stainless steel
 tubing with a tapered,  o-ring  flange welded to each end  of each tube (Figure A-5a and b).
 These flanges allow the two halves of the main body to be connected to each  other and to
 the top and bottom  assemblies of the elutriator using quick-release,  pressure clamps (Figure
 A-5a).                                                  "•                ..  ' ..

 The entrance tube to the  elutriator (from the tumbler) is pointed downward at its exit point in
 the bottom of the elutriator (Figures A-1 and A-5b).  This geometry  was selected to prevent
 introduction of a large concentration of particles into the bottom center of  the elutriator. This
 geometry should also promote a flatter velocity profile-in the air traveling up the elutriator.  It
 is expected that  respirable particles will make the  upward turn because the  taper  at the
 bottom of the elutriator promotes a higher velocity profile at this location than in  the main
 body of the elutriator (where the air velocity is just sufficient to lift particles in the respirable
 size range but no larger).

 The bottom assembly of the elutriator has also been designed to allow the removal of coarse
 particles while assuring that respirable particles"remain in the elutriator air stream (Figure A-6a
 and b).,  This is to minimize buildup of a zone at the bottom  of  the elutriator of  a high
 concentration of coarse  particles  through which respirable particles would have to  pass
 before moving up the  elutriator to  the dust  collection  system.   Thus,  it is expected that
 collisions   between  respirable  particles  and. coarse  particles  (with  subsequent  loss  of
 respirable particles due to aggregation) are minimized.

 An  opening at the bottom of the elutriator allows coarse particles to pass into a. removable,
 glass cup (Figures  A-1 and A-6a  and b). .  The glass cup has a small side; arm .that is
 connected to a two  ft. piece of one quarter in. i.d. Tygon tubing. The far end of the Tygon
tube is open  to the air-  It has been found that, as long  the Tygon tube ,is not crimped or
 otherwise blocked, air drawn through this tube is just sufficient to prevent  respirable particles
from passing through the bottom  opening of the dust generator into the glass cup while
 allowing larger particles to do so.                                ,

There are four openings where  air may exit from the top assembly of the elutriator (Figures
A-1  and A-7a and b).  The two side openings lead into the scrubber  (described below). The
two top openings lead into the  air filter cassettes of the dust collection system  through two
 different paths; one draws air isokinetically from the uniform portion of the elutriator through a
 long, thin-walled  tube and the  other draws air  from the top, tapered  part of the  elutriator
 (Figures A-1 and A-7a and b).  For ease of reference, the opening'in  the elutriator that draws
                                          A-7

-------
                                FIGURE A-5

                   MAIN BODY OF VERTRICAL ELUTRIATOR
     a. Top Section
                                           b. Bottom Section
Body Tube
Quick Release
Pressure Clamp
Entrance Tube1  >   BqdyTube
 toEfutriator  •  ~  ,    ~  /<

-------

-------
                                               FIGURE A-7

                               TOP ASSEMBLY OF VERTICAL ELUTRIATOR
             a. Underside View
  b. Top View
                                         Side Exits
                                      ;  (To Scrubber)>
                                                        1ST Opening to
                                                        \ Elutr&tor,
ME Opening to
  Elutfiator v.
,,'  ^  "•?
 ,<•  ,   f >
 ' ' Slide M&
ME Opening         Isokinetic      1ST Opening
                Sampling Tube'   -

-------
 air through the isokinetic sampling tube is labeled the "1ST1 opening in this document.   The
 opening that draws air from the top of the main  body of the  elutriator  is labeled the "ME"
 opening.  The dust collection system mounted over both of the  top  openings of the elutriator
 is described below.                                ,

       A. 1.4  The Dust Collection System

 The dust collection system consists  of two mounts for filter cassettes welded to each of two
 sliding mechanisms, Which  in turn  are mounted directly over the exit openings  of  the top
 assembly of the vertical elutriator (Figure A-8a and b).  An underside view of the tapered top
 piece of the elutriator was also shown in Figure A-7a in which the isokinetic sampling tube,is
 visible.     s               -        ,    ;     •             .   .

 The sliding mechanisms permit the filter cassettes aligned over the ME and the 1ST openings
 of the elutriator, respectively, to be changed with minimal disturbance of the air flow; at either
 of the two extreme positions in the travel of each  slide mechanism, one  of the two cassette
 mounts-are aligned over the corresponding  exit opening of the  elutriator and the other is
 effectively isolated from the  air flow.   Details of the sliding mechanisms and filter mounts are
 shown in Figures A-7b and A-8a and b.
       NOTE

       The slides  are sealed against the elutriator with b-rings.
       periodically for wear and replaced if worn.
These must be inspected
The design  of the filter mounts in the dust collection system proved to be important to the
performance of the dust generator; it is critical that these mounts be leak tight.  The design
that was ultimately adopted is depicted in Figure A-9a and b. The filter mounts each consist
of a tapered aluminum base that is glued to the  bottom half of a commercially available filter
cassette.        •    ,            •    .                                        ,

The aluminum  base  of a filter  mount  is sealed  in  each of the  openings of  the slide
mechanisms with the o-rings that are visible, in Figure A-7b, The bottom  half of the plastic,
25 mm filter cassette is glued into the inside taper of the aluminum base. Filters are mounted
in the traditional  manner between the  top and  bottom halves  of the plastic filter cassette,
which are then pressure sealed.  To further assure a good seal, pressure tape is also applied
to the outside of each filter cassette at the seam where the filters are mounted.

      A.1.5 The Scrubber

The scrubber, which can be seen sitting  on the table to the right of the main body of the dust
generator in Figure A-2, is constructed  from ordinary laboratory glassware. In the scrubber,
water is boiled in the bottom of a 1' liter, round bottom flask (shown seated within a heating
mantle).  A straight-jacketed, cold-water condenser is incorporated along the entrance  line to
the scrubber and a spiral condenser is incorporated along the exit line from the scrubber. An
immersion  pump circulates  water between a cooler  containing  a water-ice mix  and .the
condensers.  Water - flowing  into the condensers is  maintained  at approximately  0° C. to-
prevent  moisture from feaving the.scrubber.         .        .   ....                    ,
                                         A-11

-------
                                         FIGURE A-8

                                 DUST COLLECTION SYSTEM
           a. Side View
b. Top View
Side Exit Opening
  of Elutriator
 (To Scrubber) >

-------

If.'V  •"  -*  ^         i                 ""           f               (     „ ""       * ClJ J*            *•       * ^*   ft            *                   «    **      ^      *                     "'?,,St~'"jrX4''Cl'%I'\f^V'*'           *  *     }:         "    A. '   ^XV *>    V      S '        ^)^            '^rtXS'V!'            S
S*      ;              J                         "                   *                  •* ^f                   f        !'x              ^>    Vn *>£  j.  •#        ?       »   ""      <^     •*     •?          -?1   ^   ft   t      ^^                -S              «         y      4 ^ *^ .-^       -0-™*-  ^   jj      ?         ^^\        S>      NN      *   ^ \?"   >     ?       *

-------
 Particles in the air stream entering the scrubber serve as nucleation centers around which the
 steam in .the scrubber condenses. The resulting water droplets eventually fall back into the
 water reservoir,at the bottom of the scrubber so that the trapped particles are collected in this
 reservoir.

 A flowmeter and a filter cassette are also placed in the air flow line that exits-the scrubber
 (between the  scrubber and the vacuum pump).  The primary reason for including the filter
 cassette is to make the pressure drop through this path approximately equal to the pressure
 drop through  the other filter cassettes  mounted on top of the elutriator (the dust collection
 system). The pressure drop through the elutriator and scrubber is small enough not to affect
 the flowmeter  operation.

       A.1.6  The Configuration of Air Transfer Lines

 A schematic indicating the configuration of air transfer lines leading to and from the scrubber
 is presented in Figure A-10.  As indicated  in the figure, the two side exits from the elutriator
 are each attached to one ft sections of 1.00 in. i.d. Tygon tubing, which then join at a glass
 "Y" connector. The stem end of the "Y" connector is attached (with a one ft section of 1.00 in.
 i.d. Tygon tubing) to  a diameter reducing  piece of  glass  that  feeds  into  the  entrance
 condenser to  the scrubber through a rubber stopper.  The large tubing is held in place at
 connections by ring clamps (Figure A-2).

 Also as indicated in Figures A-10 and A-2, the exit condenser of the scrubber is connected to
 a flow control valve with 0.25  in. i.d. Tygon tubing.  The exit side of the flow control valve is
 connected first to  a 25 mm  filter  cassette and  then to a vacuum pump.   Both  of these
 connections also use 0.25 in. i.d. Tygon tubing.

 A schematic indicating  the configuration of air transfer lines leading from the  filter cassette
 mounts of the dust collection system is depicted in Figure A-11. A photograph of the transfer
 line connections  is also presented in  Figure A-12. As indicated in the figures,  a 0.25 in. i.d.
 Tygon line leads from  the exit side  of each filter cassette to a  plastic,  stop cock  valve.
 Another Tygon line then leads from each valve to one of two plastic "T1 connectors so that
 the pair  of filter  cassettes mounted on the slide mechanism  over the 1ST opening of the
 elutriator are joined (beyond the stop cock valves) and the pair of filter cassettes mounted on
 the slide mechanism over the ME  opening are a[so  joined (beyond the stop  cock valves).
 The  common  line  from  the  exit side of each "T" connector  is then connected first to a
 flowcontrol valve  and then to a vacuum pump. All such connections use 0.025 in. i.d. Tygon
 tubing.
       NOTE

       This is the configuration of air transfer lines that is appropriate during the operation of
       the dust generator.   The configuration that is appropriate during calibration of air flow
       is discussed in Section 9.3.4 of the main text.                       .

As indicated  previously, the side arm on the bottom cup  of the elutriator is connected to a
two ft section of 0.25 in. i.d. Tygon tubing that is simply allowed to hang free (Figure A-6a).
                                         A-14

-------
                                          FIGURE A-10

                            TUBING CONNECTIONS FOR THE SCRUBBER
                                    OF THE DUST GENERATOR
                       I	To Pumps
              For Detail
         , See Fig. A-11
To DC
Motor
             Tumbler
Flow Rate Meter
(-1200 ml/min)
Valves Closed
For Initial
Calibration
                                                                To Precision
                                                               Control Valve
                                                           and Vacuum Pump
                                  _ Auxiliary Air Inlet
                                    (Always Open)
     25mm Filter
       Cassette
    With Stopper
   and 1/4" Metal
           Tube
                                                                               Stop Cock Valves

-------
                           FIGURE A-11
           TUBING CONNECTIONS FOR FILTER CASSETTES
      MOUNTED ON THE ELUTRIATOR OF THE DUST GENERATOR
                                   ME Opening From Eluatriator
                                                   Slide Mechanisms on the
                                                   Top of the Elutriator
                                                     Top of the Elutriator
                                                1ST Opening From Elutriator
                               Isokinetic Sampling Tube
             To Precision Control Valve
             and Vacuum Pump
Stop Cock Valves

-------
V  .* ' ^  *«2i     %    ^^^^^^^^^^^j^^**^^*^^^



-------
 A.2   THEORY OF OPERATION

       A.2.1  The Dynamics of Dust Generation

 The dynamics of the release  of  dust from a sample during a run using the dust generator
 have been evaluated so that the rate  of release and mass of dust in the sample  can be
 derived from  measurements of the  mass of dust deposited over time on the set of filters
 collected over the ME opening  of  the elutriator.  Analysis  of  data obtained  from  several
 different types  of samples during the  pilot study  for this  method  (Berman  et  al., 1994)
 indicate that the rate of release of mass from a sample in the dust generator is well described
 by a first-order rate equation:                                          -                .
where:



      t

      k
                                   = k*M
                                                                    (A-1)
                           is the mass of respirabie dust remaining in the sample at time "t"
                           (g);

                           is the time since the start of the run (s); and

                           is the first-order rate constant for the release (s"1).
The minus sign in this equation indicates that mass is lost-with time.

Equation A-1 can be integrated to yield:
                    ln(Ms) = ln(M0) - kt
                                                                    (A-2)
              where:
                    M0    is the mass of respirabie dust in the sample at the start of the
                           run (i.e. at time t = 0) (g).


Given that "Ms" can also be expressed as the difference between "M0" and "Mr" the cumulative
mass released up to time "t," Equation A-2 can also be expressed as:
                    ln(M0 - Mr) = ln(M0) -kt
                                                                    (A-3)
             where:
                    Mr     is the cumulative mass released between the start of a run and
                      . '    time T (g).
The relationship presented in Equation A-3 indicates that a plot of the natural logarithm of the
quantity (M0 -Mr) versus time should be a straight line with a slope equal to the rate constant
for dust release, k, and an intercept equal to the initial mass of dust in the sample at the start
                                         A-18

-------
 of the run, M0. The cumulative mass of dust released from the sample over time, Mr, can be
,.derived from measurements of dust collected on filters during the run! However, because M0
 also  appears  as part  of one  of the parameters  that  must  be  plotted  to  evaluate the
 relationship expressed in  Equation A-3, the value of  M0 must be optimized using regression,
 as described in Section 11.2 of the main text of this method.

 The cumulative  mass released from  a sample at  time "t" during a  run, "Mr" is directly
 proportional to the cumulative  mass measured on filters collected during the run:
                    M, = Mf*(Fs + Fd + FC)/FC

              where:
                                                       (A-4)
                     s
is the cumulative mass measured on filters collected from filters
mounted over the top of the elutriator up to time "t" (g);

is the rate of airflow through the scrubber (cm3/s);

is the rate of airflow through the  1ST  opening of the  elutriator
(cm3/s); and   .                                   "
                     rc     is the rate of airflow through the ME opening of the elutriator
                           (cm3/s).
 Because Fs and Fc will typically have been set to 0.48*VV and Fd will typically have been set
 to 0.047*VV  during  the  initial setup of the dust generator (see Section 9.3.4), for  most
 applications,  Equation A-4 reduces to:                   /        .              ,
                           Mr = 2.1 *Mf
                                                       (A-5)
As indicated above, values for MQ must be derived by performing a regression analysis of the
relationship described by  Equation A-3.  This can be accomplished by using any of several
commercially'  available  spreadsheet  programs  (such  as, for example,  LOTUS™).   The
procedure to be followed to derive estimates of M0 and k are described in Section 11.2.

       A.2.2   The Time Dependence of Dust Collection

As indicated in Section A.2.1 above, the generation of dust from the tumbler is well described
by the first  order rate equation:                  ;
                           -dMs/dt = k
                                                       (A-1)
However,  experience gained during the-pilot study for  this method (Berman et  al.  1994)
further indicates that the rate of change of Ms is sufficiently slow in most cases such that, for
periods of no  more than 5 to  10 minutes,  Ms can be considered  constant.   Thus, for
                                         A-19

-------
 estimating such things as the time required to load individual filters in the dust generator, a
 simpler form of Equation A-1 can be used (in which Ms  is considered constant):
              where:
                            A Ms = k*Ms*At
(A-6)
                     Ms     is still the mass of respirable  dust remaining in the sample at
                            time "t" but it is assumed constant over the short interval of time
                            "At"(g);

                     A Ms   is the mass of  respirable dust released from the sample over the
                            short time interval "At" (g);
                     At    is a relatively  short time  interval (no more than ten  minutes)
                           during which the release of dust is being estimated (s);  and
                           is still the first-order rate constant for the release (s"1).
Based  on Equation  A-6,  the  mass of respirable dust  deposited on  a filter in the  dust
generator, call this AMf, is  simply the product of the dust released from the sample, AMS, and
the fraction of the  flow through the dust  generator that is also directed  through that filter.
Thus, for filters collected over the isokinetic sampling tube (the 1ST opening of the elutriator):
                    AMf = 0.047* k*Ms*At


or for filters collected over the ME opening of the elutriator:
(A-7)'
                    AM, = 0.48* k*Ms*At
(A-8)
The correct value for Ms to be used with Equations A-7 and A-8 is the value estimated by the
relationship provided in  Equation A-2 of Section A.2.1  where  the "t" In Equation A-2 is the
time that has elapsed from the beginning of the run to the start of the interval of interest, "At".
       NOTE

       In  deriving Equations  A-7 and A-8,  it was  assumed that air  flow within the dust
       generator was setup as described in Section 9.3.4.
                                          A-20

-------
        A.2.3  Size Separation Using the Vertical Elutriator

 Separation of the respirable fraction of a paniculate matrix can be accomplished by exploiting
 differences in the settling velocities of particles of different sizes when  such particles  are
 suspended in either a liquid or gaseous medium.  However, air was selected as the medium
 into  which  samples  would be suspended  in  this  method  to avoid changes  in  the
 characteristics of asbestos that typically occur when asbestos samples are placed in water2.
 The force on  a particle  suspended in  a moving fluid is given by  Stake's Law (Fuchs, N.A.
 1964).  When such  a particle is suspended  in a fluid that is moving upward  such that  the
 force of the fluid and the force of gravity on the particle just balance and the particle remains
 motionless, Stake's Law  indicates that the following relationship holds:
                     4/3**:*r3*d*g = -6*jt*n
  (A-9)
              where:
                     r      is the radius of the particle (cm);

                     d      is the density of the particle (g/cm3);         '

                     g      is .the acceleration due to gravity (cm/s2);

                     T)      is the dynamic viscosity of the fluid (g/cm*s); and

                     V|     is the linear velocity of the fluid (cm/s).
The velocity estimated in Equation A-9 is termed the Stake's velocity, Vs.

By substituting the viscosity of air at room temperature  (i.e.  20° C) and the acceleration  due
to gravity into Equation  A-9, the value of the Stake's velocity of a particle is  estimated as
follows:                              '                 '                     •'.-,'
                            Vs =
(A-10)
where Vis -the radius of the particle and "d" is the density of the particle.  Because respirable
particles are generally defined as those exhibiting an "aerodynamic  equivalent diameter" of
10 urn, where an aerodynamic equivalent diameter is the diameter of a particle of unit density
that settles at the same rate as the particle of interest, Equation A-10 can  be used to find the
Stake's velocity of the largest  respirable particles in the elutriator (i.e. by substituting a radius
of 5 |im and assuming a density of 1):
                            V. = 0.295 cm/s
       It is well documented that the size distribution of' asbestos structures in a sample change when such a sample is
       placed in water. For an overview of such documentation, see Berman and Chatfield (1990).  Typically, the number of
       small fibers and bundles increases and the number and complexity of clusters and matrices decrease when asbestos
       samples are placed in water.   .                                         '


                          • •       .   •      A-21                              •••.•''.-•'

-------
The Stake's velocity for a particle is also equal to the veiocity of the fluid stream that will just
hold  a particle motionless against gravity.   Because the  goal  of the dust  generator  is  to
capture all  particles that are potentially respirable, the velocity of air within  the  elutriator
should be set so that it is just slightly larger (i.e. by 5%) than the Stake's velocity estimated
above (for the largest respirabie particles) so that all respirable particles.entering the elutriator
will be imparted with an upward velocity and will be carried along with the air stream so that
they  are,  ultimately, either deposited on a  filter or passed into the  scrubber.   therefore,
airflow within the dust generator should be set so that the velocity of air within the vertical
elutriator is 5% greater than 0.295:
                           V( = 0.31 cm/s.
A.3    DUST GENERATOR PROTOTYPE DESIGN FIGURES AND CONSTRUCTION
       GUIDELINES

The figures of the prototype dust generator that are included in this package are intended to
be suggestive and not meant to be followed in exact detail.  However, the dimensions of the
various cross-sectional areas of different parts of the dust generator, which affect the relative
air flows in various  places, need to be followed closely for the  dust generator to perform as
intended. Other design features, such as couplings, clamps, and seals are intended more to
be illustrative; alternate designs can be equally effective.

In spite of  the  low  pressure differentials  developed during  operation  in  the  prototype,
performance  was found to be very sensitive to leaks,  especially  leaks occurring  in  the
isokinetic sampler filter mounts. Design features  associated with the dust collection system
should therefore  be selected so as to minimize the potential for leaks in  this  area.  The air
flow  path in the elutriator of any dust generator that is constructed for use with this method
should be tested for leaks when construction is completed and periodically  thereafter.

So  that dust  generator  equipment  constructed  for  use with this  method will perform
adequately, the following requirements must be incorporated into its design:

       •     the tumbler must be designed to hold a minimum of approximately  100 g of
             sample (with ample  space left over to allow adequate tumbling) so that field
             homogenization  requirements  are   not  compromised.   It should  also  be
             designed  to assure a  reasonably  long pathlength  over  which  air passes
             through the sample  and baffles  (or  square  corners) should be incorporated to
             assure adequate tumbling action and thorough mixing of sample and air;

       •     the pathlength of the elutriator should be  a  minimum of 10 times its diameter to
             minimize the  possibility of channeling and the diameter should be large enough
             to assure a cross-sectional area that is at least 10 times that of the tumbler.
             This latter requirement is to assure  adequate air flow in the tumbler that  will
             effect efficient transfer of sample while flow throughout the device is limited to
             allow flow in the elutriator to be set at 1.05 times the settling  velocity of  the
             largest respirable particle of interest;         .         '
                                         A-22

-------
       •      the entrance tube  and bottom of the  elutriator should  be shaped so that
        .      sufficient air velocities are maintained in this part of the device to assure a
              smooth, transition (with  efficient sample  transfer), between flow in the tumbler
              and flow in the elutriator.  It is also recommended that the entrance tube to the
              elutriator be pointed  downward as  a further, hindrance to  channeling  in the
     •    ^     elutriator; and

       •      filter  mounts in  the dust  collection  system need to allow for ready,  facile
              exchange  of filters while minimizing the  potential for  air leaks in this area.  A
              modification  incorporated  into  the prototype  device  to  achieve  both
              requirements was to design aluminum mounts that are tapered such that the
              shaved bottom half of commercially available filter cassettes fit snugly and can
             -be glued in place (to prevent  air leaks at this joint).  These  can then be fitted
              with filters  and joined to  the matching  top halves of commercially available
              cassettes.   This feature takes good advantage of the fit between the two plastic
              halves of a commercial  filter cassette, which are  designed to join with minimal
              leakage while allowing  for rapid exchange of filters.   The bottom half  of the
              aluminum filter mounts are sealed" into the slide mechanisms on the prototype
              apparatus  with o-rihgs.

The following figures are  included in this  package:        ,                  ,   ,

       »      Figure A-13 indicates the overall assembly of the prototype dust generator;

       •      Figure A-14 indicates the details of the prototype tumbler assembly;

    ,   •      Figure A-15 indicates the details of the prototype vertical elutriator;

       • ,     Figure  A-16 is  a vertical  cross-section  of the  top of the  prototype vertical
              elutriator indicating  the  relationship  between  the  elutriator  openings, the
              isokinetic  sampling tube,  and the  slide mechanisms of  the dust collection
              system;

       •      Figure A-17 indicates the, details of the isokinetic sampling tube;

              Figure A-18 indicates the details of the prototype slide mechanism of the dust
              collection assembly; and                                       ,-.,.'.

  .     •      Figure A-19 indicates the details of the prototype filter cassette mounts. '
                                          A-23

-------

-------
                                              FIGURE A-13  OVERALL PROTOTYPE DUST GENERATOR ASSEMBLY
                                                                                                                             10
                                                                                                                                                          12
           o
1
\
\
\
;N




•






i

- *


a




\
1










~C"~


\

i
i







&

»





si

i
/

i
















•>

»






















u


X










e




—


0













o




"-]


VA


                               53
000
                                   42.000
                                       12.
        750-

           6.000
      MAX FLOff RATE PER MIN

              '   I   ' "  '
         •     ••  I      	
 »&» III    373 lit       375 Ml   3712 Ifl.
_L_    I           I        I  :
                                                                                           •
                                                               p
    ——12.000:	-I

     FRONT END  VIET
                L
K WT 5Ct£ OMNSi
                                                                          r-J    r— L
                                                                                  \   wr
                                                                                     wrut
                                                                                              s
                                                                                             1
                                                                                                                   56.
                                                                                    000
                                                                  - PIPE FITS-
                                                                  OVER  BEARING
                                                                                                                                                              I
                                                                                                                                           /-SECURED.BY
                                                                                                                                            SPRING HOLDERS    ,
                                      -36.000-
                                                                      SIDE WEf
                                                                           LIST:
                                                  A. 1'  SO, SIBEL TUBE
                                                  B. 1*  X .25' STEEL STRAP
                                                  C. .0625 ALUMINUM SHROUD
                                                  D. SPEED CONTROLLER (0-150rpm)
                                                  E. DC-MOTOR•(O.-JSOrpm)
                                                  F. MOTOR MOUNTS :
                                                  G. MOTOR PWTE
                                                                                          REAR' END VIET
                                                              fl. PIPE ASSEMBLY  •
                                                              I. FLOW METERS
                                                              J. HUMIDITY CONTROLLED PLASTIC ENCLOSURE
                                                              K.: ALUMINUM SHAFT IT/COUPLINGS
                                                              L SAMPLE CHAMBER                  '
                                                              M. SEALED BEARING
                                                              N.-SPRING HOLDERS

-------
                                           FIGURE A-14 PROTOTYPE TUMBLER ASSEMBLY DETAIL
                                                                                                    10
                                                                                                                          12
    .375 DIA. HOLE
    FOR AIR FLOW
                               TOP  VIEff




1
5QO


•










--

	 • 1 J.Ut>£) 	
Uornn 	 ._ 	

to or.nn 1 - o oenn | .0 'Kn.n.- «.*--— 9 ?^nfi..-«-<
l./OUU - — ' i.ijUU ' •' — i.^jUU " -• i.^OUU "
O — p O O O O
1.7500 ' )
1 V '''
O — L^ O O O JO
                                                                                       NOTE: Use  10-32 SHCS
         L.2SO OIA. HOLE FOR AIR FLOW
     CUT AWAY FOR CLARITY
•.0625  S.S. FLANGED PLATE
                 SEALED BEAKING
                  ALUMINUM  END PLUG  #1
                 1.250.X .0625 S.S.  SQ. TUBE
                 ALUMINUM END PLUG J2 ^
                 SPIDER COUPLING
                                                                                                    00.8750
                                                                      RUBBER  GASKET
                                                                      S.S.  COVER  PLATE
                                                                                                          0 2.1250
                                 SIDE  VIEff
                                          END VIEF
AOSC (MUSS OJHOtttSf SlfVfXZ
  00 HOT SOU MUttZ

-------
                                                          FIGURE A-15  PRU1UI
HOC Mas omma smm
   ca tor sou w**t
                                                    .TOP SLIDE ASSEMBLY
                                                     CASKET
                                                      SECTION 1
                                                    SEE  DETAIL A

                                                   - 0-R.ING
                              20.5625
                                                     SECTION 2
4.00  DIA. X .0625  ffAE
   S.S.  RD.  TUBING
                                                      0-RINC
                              20.^625.
                                    13.000
                                                	SECTION 3
                                                 4.00 DIA. X  .0625
                                                     S.S. RD.  TUBING
                                               -1.50 DIA. X  .0625 ffAU
                                                     S.S. RD. TUBING
                                                      0-RING

                                                      SECTION-4


                                                      1.50 DIA.  X .0625 1TALL
                                                         S.S. RD. TUBING
                                                      GLASS CONTAINER
                                                      fflTH RUBBER  SEA,',
                                                                                                                                        10
                                                               NOTE: S.ections joined together  -
                                                                     by pivot  damps.

                                                                     AH screws are 10-32  SHCS
                                                                              p  ;  •'»•»«»« -jol
                                                                           I   /   L 1.060 x .03 si »: -  /    \ !  .
                                                                           U     ."".•/     U'
                                                                          nwtvnr

                                                                        -—tins—
                                                        MATERIAL: STAINLESS STEEL
DETAIL A
                                                                                                                                                                       12
                                                                                                                                          10
                                                                                                                                                                        12-
                                                                                                                                                                                   A''

-------
          FIGURE A-16

  SECTION OF ELUTRIATOR TOP
     WITH EXTENSION TUBE
    i
'///I  '//*    I — — - Ob
W////////////////////////I
                I

        CL
                     GL

-------
              FIGURE A-17

LONGITUDINAL & TRANSVERSE SECTIONS OF
       ISOKJNETIC SAMPLING TUBE

8.
>
t
t
6.3
5"
\
/
1.-
r >
'•'"'' ^
• ' * ^
s
\
x
' *
X
\
X
X
\
S
S
X
s
X
X
X
X
s
N
X
N
X
. . s
X
X
X
X,
0
• ' - • \
X
X
X
75" ' \
X
X
X
\
s,
X,
X
N
X
X
\
X
X
X
\
N
X
• N
\
\
. • \
\
N
: \
A
\
\
X
N
o
\
X
. • \
^
v\
X
/ ' -I
X
\ ' 1
A
.. A
75" .
r ,




V
V
0
0
V
V
\
^
V
\
\ "
0
0
Xs
0
v;
x
V
S
C
C
\ -
0
0
\
X
X
s
X '
0
c
\
^
V
X
c
X . .
X
c
c
X
s
v
s
x
X
X
V •"
\
s
\
\.
\
\ .
\
r •
\
\
s • •
V
\
c .
\
\
V
\
\ -
V
\
\ • •
\ -
\
\
\
\
V
\
\
c
c
\ .
V
!;
\
c
x
x
\
\
0 .
c
X. __i 	
\
\
c
c
\
c
\
1
)
(
/ 78.3°
1' ' A1
^ v .
X
X
X
X
X
X
/ -
/ 87.3°
SCALE 1"=,1" ^L
                                   \\
I/
                                      «E	—' 0:87"-
                                            -0.905"-
                                             1.06"-
                                              AA1


                                           SCALE x2

-------
                                          FIGURE A-18  PHOTOTYPE SUDE MECHANISM DETAIL
                                                                                                             10
                                                                                                                                       12
r.

            0,0
           O   '   0
          TOP VOT
                                   SLIDER BLOCK jl
                                   SLIDER SI
                                   GUIDE RAIL jl

                                   BASE PLATE

                                   CENTER GUIDE RAIL
                                   SLIDER #2
                                   SLIDER BLOCK #2
                                   GUIDE RAIL #2
         Zin-	CENTER GUIDE RAIL

1         I
                  •GUIDE RAIL #2

                                                                                                                              r
                                                                                    W
                                                                                    i
                                                                                                  urn
                                                                            r-U4
                                                                         <*	p       «^

                                                                    SLIDER #2     GUIDE RAIL #2
                                                                                    ||_[  SLIDER BLOCK #2
                                                     BASE PLATE
                                                                                                        CENTER GUIDE RAIL
                                                GUIDE RAIL #1   	-C?I  '!
                                SLIDER BLOCK #2                      !  I   \
                                GASKET           SLIDER BLOCK #1
                                                GASKET	:	!•
         —lOOOO-—
          SIDE WEff
• SLIDER #2

- 0-RINGS

• BASE  PLATE
                                                SLIDER #1

                                                0-RINCS
                                                                                     CENTER GUIDE JttIL
                                                                        GUIDE RAIL #2

                                                                        SLIDER BLOCK #2
                                                                        GASKET

                                                                        SLIDER #2
                                                                        0-RINGS

                                                                        BASE PLATE
                                                         END WE₯
                                               TOP  SLIDE-ASSEMBLY
                                                                                                                     MATERIAL: ALUMINUM

-------
                            FIGURE A-19

            DETAIL OF PROTOTYPE FILTER CASSETTE MOUNTS
                           Radius Corner
 23.6mm
".930 in.
                                       23 mm
                                       .905 in.
/. •
2 Degree
Included Angle
\^___
. .

1
i




i

 ALUMINUM CASSETTE HOLDER, TOP MODIFIED WITH INTERNAL TAPER AS SHOWN
                                       Radius Corner

I
1

















>

rf 20mm k
.787 in.
* \
t ^
23mm f Degree
905 in Included Angle
r j



25MM MILLIPORE CASSETTE, BOTTOM MODIFIED WITH EXTERNAL TAPER AS SHOWN
    CASSETTE AND HOLDER SHOWN JOINED TO CREATE A TAPER LOCK SEAL

-------

-------
                                    REFERENCES
 Berman, D.W.; Kolk, A.J.; Krewer, J.A.; and Corbin, K. "Comparing Two Alternate Methods for
. Determining Asbestos in Soils and  Bulk Materials." Session Chair.  Session presented at the
 Eleventh Annual Conference and  Exposition  of the Environmental Information Association.
 San Diego, March, 1994.                      '

 Berman, D.W. and Chatfield, E.J.  "Interim  Superfund  Method  for the Determination  of
 Asbestos in  Ambient  Air,  Part 2:  Technical  Background Document."   USEPA publication:
 540/2-90/005b, May 1990.
  s           \,                      .'          •_           .         ."'"''-.,
 Dennis, R.  (ed.) Handbook on Aerosols.  Reprinted by the Technical Information Center.  U.S.
 Department of Energy. NTIS No. TID-26608. 1976.

 Fuchs, N.A. The Mechanisms of Aerodols. Oxford: Pergamon Press, N.Y. 1964. Translation
 of: Mekhanika Aerozolei.                                    '

 Zimon, A.D.   Adhesion of  Dust  and  Powder  (2nd  Ed.)  Constants  Bureau, N.Y.  1982.
 Translated from Russian by R.K. Johnston.
                                         A-31

-------

-------