DOE
                               United States
                               Environmental Protection
                               Agency
                     Office of
                     Research and Development
                     Cincinnati, OH 45268
EPA/540/R-97/509a
December 1998
S/TE Technology  Capsule
In  Situ   Electrokinetic
Extraction  System
Abstract

AspartoftheSuperfund Innovative Technology Evaluation
(SITE) program,  the U.S. Environmental  Protection
Agency (EPA) demonstrated the In Situ Electrokinetic
Extraction(ISEE) system at the U.S. Department of Energy
(DOE) Sandia  National  Laboratories  (SNL) Chemical
Waste Landfill site in Albuquerque, New Mexico.  This
demonstration was funded by DOE's Office of Science and
Technology through the Subsurface Contamination Focus
Area. The ISEE system treated chromate-contaminated
soil at the Unlined Chromic Acid Pit (UCAP) of the SNL
Chemical Waste Landfill site.

The SITE demonstration results show that the ISEE
system removed hexavalent chromium in the  form of
chromate from soil under unsaturated conditions. At SNL's
preferred operating  conditions, (1)  approximately  200
grams (g) of hexavalent chromium were removed during
about 700 hours  of system operation, (2) the overall
removal  efficiency for the system was approximately
0.14 g of hexavalent chromium per kilowatt hour (kWh),
and (3) the average removal rate for the entire system was
approximately 0.29 g/ hour.

Potential sites for appropriate application of this technology
include Superfund and other hazardous waste sites where
soils are  contaminated with hexavalent chromium under
unsaturated conditions. Economic data indicate that soil
remediation costs are very high, perhaps because the
system  demonstrated at  UCAP  requires  significant
improvements.
               Introduction

               The SITE program was established in 1986 to accelerate
               the development, demonstration, and use of innovative
               new technologies that offer permanent cleanup alterna-
               tives for hazardous wastes. One component of the SITE
               program  is the demonstration  program,  under which
               engineering, performance, and costdata are developed for
               innovative treatment technologies. Data developed under
               the SITE demonstration program enables potential users to
               evaluate each technology's applicability to specific waste
               sites.

               The SITE demonstration of the SNL ISEE system was
               conducted at the UCAP within the Chemical Waste Landfill
               site at Technical Area III.  The system was evaluated from
               May  15  to  November 24, 1996,  to  determine  its
               effectiveness for treating unsaturated soil contaminated
               with hexavalent chromium.

               This technology capsule was developed by EPA's Office of
               Research  and  Development  in  Cincinnati,  Ohio, to
               announce key findings of the ISEE SITE demonstration,
               which is fully documented in two separate reports: the
               innovative technology evaluation report (ITER) and the
               technology evaluation report.   These  reports can be
               obtained by contacting Mr. Randy Parker (see "Source of
               Further Information" below).
                             SUPERFUND INNOVATIVE
                             TECHNOLOGY EVALUATION
                                                                       Printed on Recycled Paper

-------
This capsule summarizes the following information:

    Technology description
    Technology applicability
    Technology limitations
    SITE demonstration overview
    Treatment residual
    Site preparation requirements
    Demonstration results
    Operating problems
    Comparison to Superfund feasibility evaluation criteria
    Estimated treatment costs
    Technology status
    Source of further information

Technology Description

The ISEE  system was  developed  by  SNL to  remove
hexavalent chromium from  unsaturated soil.  The ISEE
system  used for the demonstration was housed in two
buildings: a control trailer and a temporary structure. The
control trailer  contained the control  panels, the power
supply,  and the data logging  system.   The  temporary
structure protected  the electrokinetic technology equip-
ment  and  personnel  and  maintained  the  operational
exclusion zone required during  ISEE system operation.

The technology involves the in situ application of direct
current to soil, which results in dissolved chromate ions
migrating through  water in soil pores to the anode,  a
           phenomenon  known as electromigration.  In addition to
           electromigration cathode, a bulk flow of pore water occurs
           toward the cathode, a phenomenon known as electroos-
           mosis. Chromate ions are extracted in the anode effluent.

           The SNL  ISEE  system consists of the following: an
           electrode system,  a  vacuum control system,  a water
           control system, a power supply, a monitoring system, and
           ancillary equipment. Figure 1 shows the ISEE system's
           main components.  Figure 2 shows the electrode layout of
           the ISEE system used during the SITE demonstration. The
           system consisted of an anode row oriented east to west
           and four rows of cathodes parallel to the anode row, two
           rows north and two rows south of the anode row. Two types
           of cathodes were used during the SITE  demonstration:
           cathodes similar to the anodes, which will be referred to as
           "cathodes," and simple design  cathodes, which will be
           referred to as "cold  finger cathodes"  (identified as "CF" if
           they are  standalone  or  "CFG"  if they are adjacent to
           cathode casings). The treatment zone was determined by
           the active portion of these electrodes and extended from 8
           to 14 feet bgs.

           The innovative feature of the ISEE system is that lysimeter
           technology is  used  in the construction of the anodes and
           cathodes  to  hydraulically  and  electrically  create a
           continuum between  the electrolyte and the pore water. The
           electrode fluid is held inside the electrode by an applied
           vacuum, keeping the fluid from saturating soil. This feature
           allowed the removal of chromate from unsaturated  soil
                                       Power Supply System
                                        Compressed Air
                                      Vacuum Control System
                                Ground Surface





<
**"r
— *
— »
— »


'
^



, ,


1 !
fTemperature
I Probe to
i Monitoring
! System
A Anolyte
Y Sampling Port
Fi
<^><_><^.>
i
cfc



! i
I
\
\
I
I
I


n^
'^?&




Chiller 	 r/f. 	 ,
	 i ! i
Conductivity and pH Probe!
to Monitoring System •
Recycle Flow Loop c« g j |
^ Chromate j I
| Check Valve I |


Potahl- i Sodium ; Three-Way
wltr i Hydroxide; Va ve
;._ Water J : solution ;
„ ,w^ ;^


? ]
fi ?
11
«3 S
CO
CD
£
i
i
D
)
r
                  0.75-inch-Diameter
                     PVC Pipe
                  1-inch-Diameter
                   Copper Pipe
                  Cold Finger
                   Cathode
                                  - 3 feet -
 3-inch-Diameter__
  PVC Casing

3.5-inch-Diameter
 Ceramic Casing

  I rid i urn-Coated
  Titanium Pipe -
   (Anode)
  Anode Casing —

  Bladder Pump -
                                    Electrode System
Figure 1.  ISEE system schematic diagram.

-------
Cl CFC3 CFC4 CF
-} r\ r\ r
j
T3
/, •' ,-NT4,-
/ ,-'' ••' *''
V
12 <
CF3

„/ V
NT3n»T4andT6
T5« CF4
'T8 .-•',-•'.-•',
/ \_
T7

                                                                                        II
           AIQ/   v-;-y:0—'--—O   -*vv:  O
          0A5
• NT6

F6 (

'<


s
T10

LcFce J

••',-•' £T,8
N'I8«
w
Til anclT13

K CFCV
•NT-7'..-'',-
T9 ••'//'/
.-•',-•' ..CF9
T12
»T15
S CFCV

T.14 ',-•'..-


S CFC1V
_/ vv v^ v_/ v,
C7 C8 C9
KT9 "NT10
m T16



J C 1 0
                                                                            LEGEND
                                                                            C6  - Cathode 6
                                                                            Al  - Anode 1
                                                                            CF1 - Cold finger cathode 1
                                                                            CFC1 - Cold finger at cathode 1
                                                                            Tl  - Temperature probe 1
                                                                            NT1 - Neutron hydroprobe access station I
                                                                            | / | - Test 13 zone of influence


                                                                            NOTE
                                                                            The area displayed measures 12 by 12 feel.
                                                                            Each square measures 3 by 3 feet.
Figure 2.  Test area electrode layout.
during the demonstration without significantly altering the
soil  moisture  content.  The  vacuum  control  system
maintains the  vacuum in the anode electrode, which
creates the pressure gradient between the anode's porous
ceramic casing and the surrounding soil necessary  to
hydraulically control water movement between the anode
casing and the soil.  Hydrogen gas, which is produced by
electrolysis  reactions  resulting  from  direct  current
application,  was  purged from the  cathode casing  to
eliminate the danger of explosion.

The water control system consists of water circulation and
pH control systems. The anode water circulation system
mixes the anolyte  in the electrode, removes and samples
anolyte, monitors the chemical condition of the anolyte, and
maintains the anolyte temperature  at about  12 °C.
Circulation is maintained in a recycle flow loop by a bladder
pump.  Because  the bladder pump is  contained in the
electrode  casing,  under subatmospheric conditions, an
additional vacuum source is necessary  for its operation.
The cold finger cathode water control system consists of a
chillerthat cools water pumped to the cathodes and has no
recirculation system. The pH control system maintains the
pH of the anolyte  at about 9 using a  10 percent sodium
hydroxide solution.
The  power supply  energizes the  electrodes.    The
demonstration system consisted of four 10-kilowatt (kW)
powersupply units. Each unit was ope rated independently
under constant voltage conditions.  The current applied to
each electrode was monitored and limited to 15 amperes
(A).

The  monitoring  system records water  control  system
information such as anode casing water level, recycle flow
rate, influent and effluent rates, recycle flow temperature,
conductivity, and pH.  The monitoring system also records
air purge rates, the vacuum in  the anodes, and ancillary
equipment  information such  as soil  temperature  and
voltage profiles of subsurface soil. The monitoring system
can shut down  the  entire  ISEE  system if operational
parameters are not within established ranges.

Technology Applicability

The ISEE technology developed by SNL  is applicable for
treating  unsaturated  soil contaminated with hexavalent
chromium.   According  to SNL, this technology  can be
modified  to treat  saturated contaminated  soil  and  to
remove contaminants dissolved in the pore water besides
chromate. Because other anions will compete with the

-------
targeted contaminant ions to be removed, it is necessary to
determine the electrical conductivity of the soil pore water
and  the target  ion  concentration  to determine the
applicability of the technology.

Technology Limitations

Prior to  implementing  electrokinetic  remediation at a
specific site, field and laboratory screening tests should be
conducted to determine if the site is amenable  to this
technology.

Field conductivity surveys are necessary to determine the
soil's electrical conductivity.  Also, buried metallic objects
and utility lines could short-circuit the current path, thereby
influencing  the  voltage  gradient  and  affecting  the
contaminant extraction  rate.  Electromagnetic surveys
should  be conducted to determine the presence of buried
metallic objects.

In  addition,  if volatile organic compounds (VOC) are
present in  soil  at the  site undergoing  electrokinetic
treatment, the VOCs will likely be stripped from the soil to
significantly increase the soil vapor VOC concentrations
that could result  in significant VOC  migration from the
treatment area, if soil temperature exceeds 50°C. Special
measures therefore need to be taken to contain and  control
VOC emissions.

SITE Demonstration Overview

The ISEE technology SITE demonstration was initiated on
May 15,1996, and was terminated on November24,1996.
During this period, the system operated for a total of about
2,800 hours.  The test areas ranged from 36 to 72 square
feet, and contaminated soil at 8 to 14 feet bgs was treated.
Predemonstration soil samples collected within the test
areas contained hexavalent  chromium at concentrations
ranging from below the detection limit  of 0.4 milligram per
kilogram  (mg/kg) to 6,890 mg/kg  and total chromium at
concentrations ranging from 7.7 to 26,800 mg/kg.

Evaluation of hexavalent chromium removal from  soil by
the ISEE system  was  the primary project  objective
because the ISEE system is primarily designed to remove
hexavalent chromium. To accomplish this objective, SNL
collected and analyzed  anolyte samples for hexavalent
chromium  at the  field  laboratory  throughout  the
demonstration period.  An  independent check  of field
analytical data was  provided  by EPA through split sample
analysis at an off-site laboratory. Field analytical data were
therefore deemed adequate to estimate the amount of
hexavalent  chromium removed from  soil  by  the ISEE
system.
Predemonstration and postdemonstration  soil samples
collected by EPA were analyzed for hexavalent chromium
to verify the hexavalent chromium removal estimate based
on anolyte sample analysis.

The secondary objectives of the technology demonstration
were to determine whether treated soil meets the toxicity
characteristic leaching  procedure (TCLP)  regulatory
criterion for chromium and to evaluate the ISEE system's
ability to remove trivalent chromium from site soil.

To conduct the demonstration, SNL was required to meet
the  conditions   of  the   New  Mexico Environmental
Department's Resource Conservation and Recovery Act
(RCRA) Research,  Development,  and Demonstration
permit for the ISEE system.   Predemonstration testing
results indicated that some of the soil in the demonstration
area  is hazardous  (EPA waste code D007) because
chromium concentrations exceeded the TCLP criterion for
chromium.   Therefore,  the  permit required that  SNL
perform postdemonstration TCLP testing to determine the
impact of the   ISEE system on  soil known  to be
contaminated. SNL therefore  collected a large number of
treated soil samples for total chromium analysis  after
extraction using TCLP.

Because incidental removal of trivalent chromium will likely
be accomplished by the ISEE system, evaluation  of
trivalent chromium  removal  was  a secondary project
objective of this project. To accomplish this objective, the
Predemonstration and postdemonstration  soil samples
collected for  hexavalent chromium analysis  were  also
analyzed for total chromium so that the trivalent chromium
concentrations could be calculated as the  difference
between the total and hexavalent chromium concentra-
tions.

During the SITE demonstration, 13  tests were performed
during six phases.  The test areas  ranged from 36 to 72
square feet, and  contaminated soil  from 8 to 14 feet bgs
was treated. The first 12 tests were conducted so that SNL
could determine the preferred operating conditions fortest
13 and to facilitate the migration of  hexavalent chromium
toward the central portion of the  test area.  Test 13
consisted  of  system performance  testing  under  SNL's
preferred operating conditions forthe SITE demonstration.
Table 1 summarizes key conditions  of the 13 tests.

Treatment

The ISEE system treatment residual consists of anolyte.
This effluent contains hexavalent chromium extracted  from
the soil in the form of chromate solution. The ISEE system
does  not have the capability to treat this waste stream;
therefore, this treatment residual should be characterized
and disposed  of as hazardous waste.

-------
Table 1.  Test Conditions for SNL ISEE System SITE Demonstration
Test Area
1 South Side
(A1-A5toC6-
C10)









2 North Side
(A1-A5toCFC1-
CFC5)



3 Southern Half
of North Side
(A1-A5toCF1-
CF5)
4 South Side
(A1-A5toCFC6-
CFC10)
5 Northern Half of
South Side
(A1-A5toCF6-
CF10)
6 Central Portion
(CF1-CF5to
CF6-CF10)
Test
No. Phase
1 A1.A2, A3,
A4, and A5
2 A1.A3, A4,
and A5
3 A1.A3, A4,
and A5
4 A1.A3, A4,
and A5
5 A1.A3, A4,
and A5
6 A1.A3, A4,
and A5
7 A1.A3, A4,
and A5
8 A1,A3, A4,
and A5
9 A1 , A3, A4,
and A5
10 A1,A3, A4,
and A5


11 A1 , A3, A4,
and A5

12 A1.A3, A4,
and A5


13 A1.A3, A4,
and A5

Cathodes Used
C6, C7, C8, C9, anddO

C6, C7, C8, C9, andCIO

C6, C8, C9, andCIO

C6, C8, C9, andCIO

C6,C8,C9, andCIO

C6,C8,C9, andCIO

CFC1.CFC3, CFC4, and
CFC5
CFC1, CFC3, CFC4, and
CFC5
CFC1, CFC3, CFC4. and
CFC5
CF1.CF3, CF4, andCFS



CFC6, C8, CFC9, and
CFC10

CF6, CF8, CF9, and CF10



CF1, CF3 through CF6, and
CF8 through CF10

Average Average
Current Power
(A) (kW)
19.45 1.3

21.09 1.68

20.08 1.77

34.25 4.65

42.15 5.76

41.07 4.56

29.27 4.14

20.94 1.9

20.79 1.87

30.31 2.7



33.49 2.38


39.31 2.86



35.92 2.1


Analyte
Extraction
Rate
(L/hour)
0.44

0.87

0.879

2.026

3.54

3.957

3.404 "

0.376

0.723

0.51



0.5


0.848



0.662


Test
Duration
(hour)
106

368

283

244

34

181

75

89

333

176



20


111



707


Site Preparation Requirements

This section describes site preparation requirements for
the ISEE technology. Some of these requirements may
apply to situations in which the ISEE system is used to
remediate contaminated soil. During the demonstration, in
addition to the test area, an additional 8,800 square feet
were necessary to accommodate the control trailer, water
tanks, and supply storage. Based on the design of the
ISEE system, which can transmit system information off
site, no  personnel are  required to be present on site for
system operation.  The system is equipped with a CR7
data-logger that monitors system parameters and can shut
down  the system (such as by cutting off power to  the
electrodes and terminating the water supply). The data-
logger consequently sends a signal to the system operator
identifying the problem.  Technical  service personnel
should be available on an as-need basis to remediate any
problems.  According to the developer, maintenance and
routine sampling and analysis requirements for a full-scale
system should require the on-site presence of a technician
for 8 hours a week.

The ISEE system demonstrated at UCAP was powered by
four 10-kW power supply units. The units were capable of
operating independently or in parallel. When connected in
parallel, the maximum output was 64 A at 600 volts of direct
current.  According to the developer, a three-phase, 230-
volt,  150-kW power supply is necessary to operate a full-
scale system.

-------
Potable and decontamination water are also necessary to
operate the  system.  The monitoring system  requires
connection to a telephone line or cellular telephone to
download data to an off-site computer and to transmit a
signal  indicating that the system  has  shut down  to
maintenance personnel.

A temporary structure may be required to protect the ISEE
system and personnel from the weather and also to provide
an exclusion zone during system operation.  The data-
logger, control panels, and other analytical equipment can
be housed in a trailer. If the ISEE system is used outdoors
in a cold climate, provisions should be made for insulating
the exposed portions of the water control system to prevent
freezing.

Demonstration  Results

The  following sections summarize results of the ISEE
system SITE demonstration according to the primary and
two secondary project objectives.

Removal ofHexavalent Chromium

The primary objective of the ISEE system  demonstration
was  to  estimate the  amount  of hexavalent chromium
removed from soil  by the ISEE  system.  The  mass of
hexavalent chromium removed was to be determined from
the amount  of hexavalent chromium extracted  in the
anolyte during the demonstration.
As mentioned  before, 13 tests were  performed  in six
phases during the demonstration.  The first 12 tests,
performed between May 15 and October 18, 1996, were
used by SNL to determine preferred operating conditions of
the system. Test 13 was performed between October 21
and  November 24, 1996, to determine system perfor-
mance and the operating costs. Test 13 was conducted in
the central portion of the demonstration  area,  which
measured 12 by 6 feet. The system was operated for 707
hours in this configuration.  Table 2 summarizes ISEE
system performance results during the 13 tests performed.

The total  mass of hexavalent chromium extracted by the
ISEE system should have been verified by calculating the
difference between hexavalent chromium mass in treated
soil before and after the demonstration. However, soil
results for hexavalent chromium exhibited a  high spatial
variability resulting from (1) the nonhomogeneous distribu-
tion  of  chromate  concentrations in   soil  before  the
demonstration and (2) the fact that the demonstration was
terminated before chromate removal was completed.  In
addition, limited data appearto indicate that contaminants
had  likely migrated from  areas outside of and near the
treatment  area.  Thus, a  determination of the  mass of
hexavalent chromium removed based on soil sampling
results was not possible.

Hexavalent chromium soil sampling results are as follows:
(1)51 predemonstration soil samples contained hexavalent
chromium-concentrations from below the detection limit of
Table 2. ISEE System Hexavalent Chromium Removal Results
Test
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Test Duration
(hour)
106
368
283
244
34
181
75
89
333
176
20
111
707
Hexavalent Chromium
Mass Removed (g)
7.84
35.7
22.5
56.0
11.5
38.2
11.1
9.01
59.0
36.0
4.71
25.4
204
Hexavalent Chromium
Removal Rate (g/hour)
0.074
0.097
0.079
0.230
0.338
0.211
0.149
0.101
0.176
0.204
0.236
0.229
0.288
Hexavalent Chromium
Removal Efficiency (g/kWh)
0.057
0.058
0.046
0.049
0.058
0.047
0.036
0.053
0.094
0.075
0.094
0.081
0.136

-------
0.4 mg/kg to 6,890 mg/kg; and (2) 84 postdemonstration
soil samples contained hexavalent chromium concentra-
tions from below the detection limit of 0.4 mg/kg to 4,730
mg/kg. Of the 48 locations sampled both before and after
the   demonstration,    21    locations   contained
postdemonstration hexavalent chromium in  concentra-
tions that exceeded predemonstration concentrations. As
stated earlier, soil analytical results could not be used to
verify the  estimated  mass  of hexavalent chromium
removed based on anolyte results.
Compliance with  TCLP Regulatory Criterion for
Chromium

Table 3 presents TCLP results for  chromium for soil
samples collected before and afterthe demonstration from
the treatment zone from approximately 8 to 14 feet bgs. Of
the 43 predemonstration soil samples  analyzed by TCLP,
18 exceeded the TCLP limit of 5 milligrams per liter (mg/L)
of total chromium at concentrations ranging from 5.6 to 103
mg/L,  with  a  median  concentration  of  15.4 mg/L.
Table 3. ISEE System TCLP Chromium Results
Sampling
Location
No.
A1
A2
A3
A5
C1a
C2a
C3a
C4a
C5a
C6
C7
C8
C9
C10
CF1
CF4
CF5
CF6
CF7a
CF9
CF10
NTS
NT7
NTS
8 to 10
Predemonstration
(mg/L)
0.64
<0.5
<3.3
2.5
<1
< 1
< 1
-
<0.5
0.37
—
0.49
—
3.1
—
13
—
—
—
—
—
9.2
19.7
5
feet bas
Postdemonstration
(mg/L)
-
-
--
-
-
--
-
0.078
~
-
1
-
0.24
~
0.92
1.1
21
0.99
0.072
3.8
29.9
--
-
--
Sampling Depth
10 to 12 feet bas
Predemonstration
(mg/L)
20.8
3
17.8
103
<0.5
-
<0.5
-
<0.5
0.007
-
5.6
27.4
-
-
49.3
-
-
-
-
-
5.6
35.5
1.7
Postdemonstration
(mg/L)
19.7
--
9.4
-
-
-
-
0.017
--
-
0.6
-
0.35
--
6
12
4.9
15.2
6.6
57.2
62.4
-
40.6
1.2
12 to 14
Predemonstration
(mg/L)
0.52
1.8
20.8
19.5
<0.5
—
<0.5
-
<0.5
<0.5
~
6.1
1
-
-
8.6
—
-
-
-
--
7.1
7.9
6
feet bas
Postdemonstration
(mg/L)
-
14
..
„
-
—
—
8.9
—
-
3.6
--
0.011
-
32.8
1.9
0.052
13.8
43.9
67
22.2
-
—
-
  Notes:
  Numbers presented in bold font exceed the TCLP limit of 5 mg/L.
  a These locations are not shown in Figure 2 because electrodes at these locations were not used during the
  demonstration.
  - No sample analyzed from this depth.

-------
Postdemonstration results indicate that 18 out of 35 soil
samples  exceeded  the  TCLP regulatory criterion  for
chromium at concentrations ranging from 6 to 67 mg/L, with
a median concentration of 20.4 mg/L.

Removal of Trivalent Chromium

Trivalent chromium concentrations were to be determined
by calculating the difference between total and hexavalent
chromium concentrations.  In general, the ratio of trivalent
chromium  to  total   chromium  ranged  from  7.6  to
94.9 percent in the predemonstration samples and from
27.6 to 99.6 percent in the postdemonstration samples.
This large variability precluded the calculation of trivalent
chromium concentrations as originally intended because it
would have further increased the data variability.

Total chromium concentrations in the 51 predemonstration
samples analyzed ranged from 7.7 to 26,800 mg/kg; and
total chromium concentrations in the 84 postdemonstration
samples  ranged  from 8.2 to  16,200 mg/kg.  Of the 48
locations sampled both before and afterthe demonstration,
31   locations  contained   postdemonstration  trivalent
chromium concentrations that exceeded predemonstration
concentrations.

This increase may be the result of chromium migration in
the treatment area in addition to inherent variability at the
test areas. Therefore, no conclusion was drawn regarding
the ISEE system's ability to remove trivalent chromium.

Operating Problems

The ISEE system's  operation was observed during  the
demonstration, and  the problems and their  resolutions
were recorded by SNL personnel.  The demonstration
lasted over approximately 4,230 hours.  The system was
not operable for 36 percent of the time. Table 4 presents
the reasons for the shut downs and the percentages of
shutdown times  relative to the  entire duration of  the
demonstration. In addition, the system was not energized
for 3 percent of  the time (approximately 140 hours) to
perform anolyte sampling and soil moisture measurements
using the neutron probe.

Comparison to Superfund Feasibility Evalua-
tion Criteria

Table 5  summarizes the ISEE system's performance
compared to the  Superfund feasibility evaluation criteria.
This table is provided to assist Superfund decision-makers
in  considering the  ISEE system  for  remediation of
contaminated soil at hazardous waste sites.

Estimated Treatment Costs

Based on information provided by SNL and the results and
experiences gained  from the SITE demonstration, an
economic analysis was performed to examine 12 separate
cost categories for using the ISEE technology to remediate
hexavalent  chromium-contaminated, unsaturated  soils.
According to SNL, a full-scale commercial system design
would significantly differ from the system operated during
the demonstration.   In  addition, the developer has not
completed  a  full-scale design of a commercial  ISEE
system.  Therefore,  it is not possible to prepare a cost
estimate fora full-scale ISEE system. Because SNL states
that  the  full-scale  treatment  system   design  will  be
significantly modified based on the performance of the
system used during the demonstration, the treatment cost
of a full-scale system will also differ from the treatment cost
of the system operated during the demonstration. When
the technology is ready  for commercialization, further
economic analysis should be performed.

This cost estimate is based on the system's performance at
SNL's preferred operating conditions during test 13  of the
SITE  demonstration  and  the  following  parameters:
(1) configuration  of four anodes  and eight  cold  finger
cathodes, (2) a treatment area of 16 cubic yards, (3) a
Table 4. System Shutdown Information
                         Reason for System Shutdown
                     Shut Down Time
                         (percent)
         Intentional shutdown to perform maintenance and modifications to
         the system
         Problems related to electrode water (such as bladder pumps, float
         switches, and chiller leakage)
         Power supply failures and problems
         pH control system problems
         Data-logger problems
         Total
                            21
                            4
                            2
                            2
                            36

-------
Table 5. Superfund Feasibility Evaluation Criteria for the ISEE Technology
    Criterion
Discussion
    Overall Protection of Human
    Health and the Environment
    The ISEE technology is expected to protect human health by lowering the concentration of
    hexavalent chromium in soil under unsaturated conditions. According to the developer, the
    technology can also treat soil contaminated with other heavy metals under both saturated and
    unsaturated conditions, but this capability was not evaluated during the SITE demonstration.

    Overall reduction of human health risk should be evaluated on a site-specific basis because
    VOCs could be stripped from soil during treatment and released to ambient air. Also, the system
    effluent (anolyte) contains hexavalent chromium and therefore needs to be characterized and
    handled and disposed of as hazardous waste.

    The technology protects the environment by curtailing migration of hexavalent chromium in soil.

    Protection of the environment at and beyond the point of anolyte extraction depends on how the
    anolyte is handled and disposed of.  Protection of the environment also depends on the extent of
    VOC emissions.
    Compliance with Applicable
    or Relevant and Appropriate
    Requirements (ARAR)
    According to the developer, the technology has the potential to comply with existing federal,
    state, and local ARARs (for example, TCLP limits) for several inorganic contaminants (for
    example, chromium).  However, about 51 percent of the postdemonstration samples did not meet
    the chromium TCLP limit of 5 mg/L.
    Long-Term
    Effectiveness and
    Permanence
    Human health risk can be reduced to acceptable levels by treating soil to a 1 x 10~6 excess
    lifetime cancer risk level. The time needed to achieve cleanup goals depends primarily on
    contaminated soil characteristics.

    The treatment achieved is permanent because contaminants are contained in the anolyte, which
    is extracted from the soil for disposal.

    Periodic review of treatment system performance is needed because application of the
    technology to contaminated soil at hazardous waste sites is new.
    Reduction of Toxicity,
    Mobility, or Volume Through
    Treatment
    The technology reduces the volume and mobility of contaminants in soil because contaminants
    are contained in the anolyte, which is extracted from the soil for disposal.

    The technology can effectively control soil contaminant migration because contaminants are
    contained in the anolyte, which is extracted from the soil for disposal.
    Short-Term Effectiveness
    About 51 percent of postdemonstration samples did not meet the chromium TCLP limit of 5 mg/L.
    This failure may be because the developer did not have the state permit required to carry out the
    demonstration for a longer period of time.
    Implementability
    The technology is still in the development stage.  No commercial system is currently available
    from SNL.

    State and local permits must be obtained to operate the ISEE system.
    Cost
    Treatment costs vary significantly depending on the size of the treatment system used,
    contaminant characteristics and concentrations, cleanup goals, the volume of contaminated soil
    to be treated, and the length of treatment.  Economic data indicate that soil remediation costs are
    very high, perhaps because the system demonstrated at UCAP was not of commercial scale and
    requires significant improvements.
    State Acceptance
    This criterion is generally addressed in the record of decision. State acceptance of the
    technology will likely depend on (1) expected residual contaminant in soil, (2) how the anolyte is
    handled and disposed of, and (3) the steps taken to reduce the potential for VOC emissions.
    Community Acceptance
    This criterion is generally addressed in the record of decision after community responses have
    been received during the public comment period. Because communities are not expected to be
    exposed to harmful levels of fugitive emissions, the level of community acceptance of the
    technology is expected to be moderate.

-------
hexavalent chromium removal rate of 0.29 g/hour, (4) a
hexavalent chromium removal efficiency of 0.14 g/kWh,
and (5) an on-line time of 85 percent.  The total treatment
costs for the ISEE system to treat 16 cubic yards of soil are
estimated to be $1,400 per cubic yard for removing 200 g of
hexavalent chromium. The estimate will vary depending on
cleanup goals, soil type, treatment volume, and system
design changes.  The  estimate is  order-of-magnitude
estimate,  as defined by the American Association of Cost
Engineers, with an expected accuracy of+50 percentto -30
percent. A detailed explanation of these costs,  including
the 12 cost categories examined, is presented in the ITER.

Technology

The SNL  ISEE system is not commercially available for
treatment of contaminated soils.  The system evaluated
during the SITE demonstration is a prototype and not the
system that will be used foractual remediation. To conduct
actual soil remediation,  SNL's research  team plans  to
design and build a system that is low-maintenance and that
can be operated  unsupervised for a long time. SNL states
that the cost of remediation will be significantly reduced as
a result of these  improvements.

         of Further Information

EPA Project Manager:

Mr. Randy Parker
U.S. Environmental Protection Agency
National Risk Management Research Laboratory
26 West Martin Luther King Drive
Cincinnati, OH 45268
Telephone No.:  513-569-7271
Fax No.: 513-569-7571
e-Mail Address: Parker.Randy@epamail.epa.gov
                                                  10

-------
11

-------
m

?
Si
-|x
O

7
CD
~N|

O1
O
CD
CO
<& ~o  o


O 03  Q.
    ?*  CD
      .
     U
        03
        (/>
        (/>
    CD
    C
    w
    03
0
zs"
o
zs
zs
CO
o
X

*.
tn
ro
CO
m







J}
CD
(/)
CD
03
3
s
03
ET
O
i
,-*.
O
•3
"Q
i
°°*>j
(O




Z
Q3_
5"
zs
CO
ZI
(/)'
7T
g
03
ZS
03
CQ
CD
3
CD
ZS
f*




m
zs
^
— s
O
zs
3
CD
ZS
(-*•
CO

~a
B
t~*
CD
a
o
Z!
>
CQ
CD
ZS
O
C
zs
CD'
Q.
CO
S
CD"











C
~o
"O
0
CTJ
^np

Q)
ZI
Q.
8
3
0)
__,















Q.
a
B)
O
zr
o
—t
o
o
13
••<
ET
M"
o
o
<
0)
-
0)
ZJ
Q.
<3_
C
3
f~t-
o
E?

s

s
•^
o
3,
0)
O
I
m
O
A
I
m
70
m
P

O
•— !
O
o
~o
•<

ZJ
Q.
3
ET
ZJ
o"

Ef

zr
0)
ZJ
Q.
O
O
™(
ZJ
(D
™(
T3

o

CO
o
ZJ
Ef

o
5T
cr
0
Q.
Q
B3"
o
zr
                                    TJ
                                    m
                                    73
                                    S
                                    H
                                    Z
                                    o

                                    Q
                                                       TJ
                                                       O
                                                       W

                                                       >  03
                                                       O  C
                                                       m
                                                       TJ
                                                       D

-------