United States
                     Environmental Protection
                     Agency
  Office of
  Research and Development
  Cincinnati, OH 45268
I £PA/540/R-99/503a
 March 1999
                     SITE Technology Capsule
                     MultB/endor  pbremediation
                     Demonstration Project:
                     Environmental  Laboratories/
                     SBP  Technologies'  UVB
                     Vacuum Vaporization Well
                     Process
Abstract

The UVB process was developed by IEG Technologie
GmbH of Germany and licensed in the eastern U.S. by
Environmental  Laboratories,  Inc.  (ELI)  and  SBP
Technologies, Inc. (SBP). A modified microbial system
employing an in-well biofilter was demonstrated under the
SITE Program at the Sweden-3 Chapman landfill in
Sweden, New York, along with the ENSR/Larsen Biovault
technology and the R. E. Wright Environmental, Inc. In
Situ Bioventing System, as part of a Multi-Vendor
Bioremediation Demonstration.

A single wide bore UVB-400 well (Vacuum Vaporization
Well) equipped  with  a biofilter  was  used  in the
demonstration. Groundwater was circulated through the
well and is returned,  presumably with  an increased
microbial population, to the saturated zone for further in
situ biodegradation of volatile organic compounds (VOCs).
An aboveground blower assists circulation of air, provides
oxygen for biodegradation, and strips volatiles from the
vadose zone. Extracted volatiles were treated by an ex
situ vapor phase biofilter followed by activated carbon.
The developers estimated that the single well would
influence a soil volume of approximately 1000 yd3.
A primary objective of the demonstration waste determine
the effectiveness of the UVB Process in reducing the
concentrations of six target VOCs in the vadose zone soil
to below New York State Department of Environmental
Conservation (NYSDEC) Soil Cleanup Criteria (acetone:
0.2 ppm, methyl ethyl ketone: 0.6 ppm, 4-methyl-2-
pentanone: 2 ppm, cis-1,2-dichloroethene: 0.6 ppm,
trichloroethene: 1.5 ppm, and tetrachloroethene: 2.5 ppm).
ELI/SBP expected that 90% of the soil samples collected
from the vadose zone of the 50 ft x 50 ft test area would
meet the NYSDEC Criteria for the six target contaminants
after six months (one  season) of treatment. A second
primary objective was to evaluate the developers' claim
that biodegradation would be the dominant mechanism of
contaminant removal, but all participants agreed that this
claim could only be evaluated qualitatively because of
limitations in the sampling  procedures. Assessing the
effectiveness of the process in reducing groundwater
contamination by VOCs was a secondary objective of the
study.

Because of the time required to establish the convection
loop coupled with operational and site problems, the
investigation was extended from 5.5 months to 14 months.
After 5.5 months, only 65% of approximately 50 soil


                    «§5 Printed on Recycled Paper
                             SUPERFUND INNOVATIVE
                             TECHNOLOGY EVALUATION

-------
|™^ 	 J'IH 	 ,'!!,ji'!i 'fiji'i '" '""!:' BE :i "IT1- 	 ";,'ll|1'1'1 	 ' """"' 	 l|!]"'|!" ' II"1 11"'!1" "' 	 • '"'" 	 i"1' '!":,,:' ""' " "" , ...,-,; ,i.. , , y „, ; , ,„ 	 ;<|F| < • ,, -. 	 ,,|,r!i, 	 |.,.| 	 mX'9i V; . .n'hviijciw.iii1
rt 	 Jjj 	 = 	 ; 	 : 	 ! 	 ! 	 	 • 	 i 	 ' 	 ; 	 !l=i 	 :iii 	 * 	 : 	 : 	 : 	 : 	 ' 	 ' 	 	 :: 	 ; 	 • 	 ! 	 ; 	 ^ 	 ; 	 ; 	 :=: 	 :;!
1 ,|'!!'',l' ':' ' 'jjl! " ' ' 1" !' ' ' ';'j :' ' ' ', " ' . ''j" ' i ' ' • '::'. ,„. n ^ ' I'1!
i;!;;;,:;,!!,,;,!:.!!:!!;!;;.!:!!;;;;!;,:!;:::; 	 ; 	 i;,;;!!;;!:,!:;;,.; 	 ; 	 ;; 	 ;,; 	 ^, 	 1:1; 	 i:;;,;;;; 	

i.;\, ;,', ... ,'i. . .. . ," ... ' I,:!; ; ,;;,,
i'iii|i| |ii" :;|ii 	 !' " '"'in

ii'iiif

iN"

	 ;
         les from both vadose arid saturated zones met the
          .J Criteria, and "only 70% met the Criteria after 14
          ,. Nevertheless, significant removal of the ketones
          •id td"lake place over the 14-month study.
              	a	i	i	i	
!i..:..j"!	!	q|o3egra3aT!on	and	slnpplng were important mechanisms
                                           Groundwater
    „«„,,>,. fieextentof removal nor the removal mechanism
    - ~w... i^.—^.—
    'for'treating'""Hazardous""wastes.1 The sites on the National
    Pj|prittes  Qsi  total  over  1,200 and  comprise a broad
    di
-------
ambient
air Inlet
NNT r-i
2
7 A*
18
2.8'
1
.6'
t
r<
4 	
*
2.V

trloolno
lactor c
c
s
act carbon

biofilter
packer 	

c
e
o
f tump





/

T

q
n
!i —
EB










i u i

m

vacuum port
to blower .





i
1 ! ki B

JT -
^
"^L
4
t—
4
C[
sump
1(


)

Tp--

n
i"







•^ ' 	
land tfc.
UK .
T 4
V
t
T
5.
i
II
I
r *•«'
0'
12.T (8/12/94)
3' italic wator tovel

5*
r
r
NOT TO SCALE
Figure 1.  Schematic of UVB System
                                                                                     Drawing ravlied 8/16/84
                                                                                     basod on 8/13/94 sit* visit

-------
E 	 m 	 a
1 	 : 	 f: 	 -
" '(". ' .i
	 if" 	
".:'"'
	 fji'j:! 	 1 	 	 "

• ! ', - :' r ;' „ , Pj'!1!' ,',,'• , . ' , i |, ' , ' • ! • i : •,„,!,•' ,...„, ' I,'; ;.. ' , ,' ' • •••
, . !i."" , , !!i, ,'.'••„,• " ' ' ' . .' , ',' •'•",. i '„]' i'i"!;,, • • . " .
"i!1!"! 	 !"! 	 Si 	 : 	 ":' 	 j 	 : 	 i'l!! 	 !* 	 Ml*]1;
'•'•.:" , . .\ •.: ' "•• ;i;:.;;:
iiijijli: 	 I,:!: 	 : 	 ;,;,,
,*; l";i: -"'
•ill 	 S'i 	 : 	 i 	 i-;
'jp^te—tbcafed pipe as well as from lie surrounding vadose zone
     raising the level of water already present in the well.
            ajr Infiltrating the surrounding soil formation
captures ybCs  that may volatilize.   Infiltration also
Increases the o3^erTconceh^i{ron of the grouhdwater/soil
matrix and stimulates indigenous microbes to enhance the
biodegradation of contaminants.  The ambient air also
bubbles  through the raised  groundwater, sparging  or
stripping VOCs in the process.  The VOC-laden air is then
exhausted through a combination of ex situ, vapor-phase
btoraactors and activated carbon filters on the positive
pressure side of the blower to minimize VOC emissions to
the atmosphere.

After  treatment  in  the stripper  reactor, the elevated
groundwater is discharged into the upper soil stratum and
 )©rco!ates  back to its  natural level, again picking  up
circulation  loop is established.   This circulation  cell
C^nistahtly transports contaminants, nutrients, oxygen and
indigenous  bacteria through  the affected  soil.    The
ecAffibution pf the physical "stripping" effect as compared
J  tie, biological effect varies  according to site specific
  	!"!:::	"""	"	"•	'	!	'"""'""	:i"-":ri'r	-""	arid	water	
                     ^

      perrfieabilily, indigenous microbe characteristics, etc.).
 1	1	!::	'	!;•
  ||:
According  to ELI/SBP^ dewatering is  not  essential for
efficient operation of thisi system. Treatment of the phreatic
            '-'i
      system can be operated  in either a standard mode as
      depjjribed above and used for the demonstration, or in a
      re^se-flow circulation mode by the addition of a pump;
                   in	be	readily converted in the field.
       Finally, in|ectlon  of heated  air can enhance both VOC
       tjesorption and the rate of biodegradation  of organic
  '	':;""'  ;!"; 'i:i'"!il!	'  '	"*  This would be particularly useful in regions
                   	.	_
       nocrfiay subject to cold winter climates. These concepts
       Ifere not evaluated during this demonstration.
       :                    ' i       '                        i
       technology Applicability
       The UVB  Mlcrobial Treatment Process was evaluated
       Bas'ed on the nine criteria used for decision making as part
       Mthe Super-fund Feasibility Study (FS) process.  Results
       of the evaluation are summarized in Table 1.
source areas. The technology employs readily available
equipment and materials, and the material  handling
requirements and site support requirements are minimal,
according to the developers.

Technology Limitations

According to ELI/SBP, the UVB system is most appropriate
for treatment of sites with good hydraulic conductivity in the
saturated zone and  high air  permeability in the vadose
zone.  Good  hydraulic conductivity in the saturated zone
accelerates the establishment of a circulation cell for faster
                                                              and more effective cleanup.  High air permeability in the
                                                              vadose zone increases the volatilization of contaminants,
                                                              improves the supply of oxygen to indigenous microbes for
                                                              enhanced  biological degradation, and increases the air
                                                              supply to the in situ stripper reactor for better performance
                                                              while reducing the size of the blower required and lowering
                                                              overall remediation costs.

                                                              The effectiveness of the technology may be limited for soils
                                                              contaminated with high concentrations of heavy metals that
                                                              could  be toxic or could inhibit  biological performance.
      Jhg ieyeippers suggest! several  means of enhancing the
      biocfpflradation. The fixed film indigenous microflora used
      by the bioreactor can be augmented with other types  of
      contaminant-degrading  microbes,  depending  on  site
      cof^ittons and contaminants. Degradation also can be
                I by the addition  of either liquid  or  gaseous
                nutrients and/or alternative electron acceptors.
       s  • 'i            '                            .
       The ELI/SBP UVB system is designed to treat vadose and
       saturated zone soils and groundwater contaminated with
       "'"~"^   an! semjvojatfles.   ^e chemical  and 'physical
                                                      water
       rnafe this jjechnofogy suited for remediation of contaminant
 Types and concentrations of metals present as well as any
 other compounds that may be toxic to the indigenous soil
 mjcrobes need to be assessed at each site  under
 consideration.

 In areas with very shallow groundwater (less than 5 ft), it
 may be difficult to establish contact between the gas and
 aqueous phases long  enough to remove contaminants.
 The technology has further limitations in thin aquifers (less
 than	10	ft);	the	saturated	zone	must	be	of	sufficient	
 thickness	to alow	propir	iriiteTIallon	offfieweTI	sysTerru	in	
 addition, the thickness of the saturated zone affects the
 radius  of the  circulation cell;  the smaller the aquifer
 thickness, the smaller the radius of the circulation cell and
 consequently the larger the number of wells required.

 The majority of the water being drawn from the aquifer into
 the lower screened section is treated water reinfiltrating
 from the upper section. As the UVB system continues to
 operate, the circulation cell expands until a steady state is
 reached. As the circulation cell grows, the amount of
 recircuiated water  increases,   causing a  significant
 decrease in contaminant concentrations in the water being
 treated  by  the  syslem.  This  can potentially  have ah
 adverse effect on the performance of both the bioreactor
 ',§DS! strigper, since their performance  is concentration
	depiridenT	

 Conversely, high concentrations of volatile compounds
 may require multiple passes through the system to achieve
 reffiediation gpals. This may be a problem since a portion
 of the treated water is not captured by the system and
 continues to leave the  circulation cell in the downgradient
 direction.   However,  once the UVB circulation  cell  is
 established, the influent concentrations should be diluted
 to below levels requiring more  than  one pass, thereby

-------
                                                                                                                    1
         Table 1. FS Criteria Evaluation for UVB In Situ Bioremediation Treatment Process
           Criteria
UVB Performance
           Overall Protection of
           Human Health and the
           Environment
           Compliance with Federal
           ARARs
           Long-term Effectiveness
           and Performance

           Reduction of Toxicity,
           Mobility, or Volume
           through Treatment

           Short-term Effectiveness
           Implementability
           Cost
           Community Acceptance
           State Acceptance
Provides both short- and long-term protection by eliminating organic
contaminants in soil. Prevents further groundwater contamination and
minimizes off-site migration. Minimal emissions and discharges during
installation and operation.

Requires compliance with RCRA treatment, storage, and land disposal
regulations (of a hazardous waste) particularly during installation. Installation
and operation require compliance with location-specific ARARs.  Emission
controls may be needed to ensure compliance with air quality standards if
VOCs are present.

Has the potential to effectively remove contamination source. May involve
some residuals treatment and disposal (e.g., extracted air, well cuttings).

Significantly reduces toxicity and mass of soil contaminants by treatment. May
distribute organic contaminants through zone of influence.
Presents minor short-term risks to workers from air releases during installation
of UVB well.

Involves few administrative difficulties, other than those associated with well
installation. Wells and aboveground system can be constructed in less than 2
weeks. Requires heavy equipment, such as crane, to install and position UVB
system.

$149/yd3 based on successful removal of VOCs from 12,800 yd3 over 14
months. Actual costs of remedial technology are site-specific and dependent
on factors such as the cleanup level, contaminant concentrations, soil
characteristics, and volume of soil treated.

Presents minimal short term risk to community. Public familiar with and
comfortable with biotreatment as in wastewater treatment. Some minor,
controllable noise from blowers.

State permits may be required if remediation is part of RCRA corrective action.
limiting the potential migration of contaminants from the
system.

The relative  sizes  of the  circulation  cell  and  the
contaminant source area will determine the number of wells
needed for remediation of a particular site.

As with other biological processes, the ELI/SBP technology
could be impacted by low temperatures, which are known
to slow biodegradation  processes.   Extended periods of
below  freezing  temperatures   could  seriously  affect
treatment performance. As such, the technology may be
better suited to areas with moderate winters, may require
a heated enclosure for protection against extreme cold
weather  conditions, may require the ambient air to be
heated, or may be operated on a seasonal  basis.

Process Residuals
                     The materials handling requirements for the UVB system
                     include managing spent activated carbon or residues from
                     other offgas treatment, drilling wastes, purge water, and
                     decontamination  wastes  generated during  installation,
                     operation, and monitoring of the system.   Spent carbon
                     generated by offgas treatment can either be disposed of or
                     regenerated  by  the  carbon  vendor.   Drilling wastes
                     produced  during installation  of the system  well  and
                     monitoring wells can be managed either in 55-gallon drums
                     or in roll-off debris bins, depending on quantity  and
                     characteristics. Disposal options for this waste depend on
                     state and local  requirements and  on the  presence or
                     absence of contaminants. The options may range from on-
                     site disposal to disposal in a hazardous waste landfill.

                     Purge water generated during development and sampling
                     of groundwater monitoring wells usually can be stored in

-------
i,|i ! 1 ii "i i ii'ji' ' ,i ii
'!
Ii
I I lll'l 1 I
	 i 	 i; 	
''!!' 1',
 55-gallon drums. Disposal options again depend on state
 and local restrictions and on the presence or absence of
 contaminants. Options include surface discharge through
 a  National  Pollutant  Discharge   Elimination  System
 (NPDES) outfall,  disposal ffirough  a Publicly Owned
 Treatment Works (POTW), and treatment and disposal at
 a peifnitted hazardous waste facility, all with or without on-
,	g|e	grejreajment.	|	"	|	|	

 pecontaminatiqn wastes generated during  installation,
 decommissioning,  and  sampling  activities  include
 decontamination water. A decontarninatign pad may be
 I^Ulred for ihe drill rig. Solid decontamination wastes can
 be managed In roll-off type debris	boxes and liquid wastes
i can be managed in 55-gail6n-l3HJmsI	Dlipoial	ppliorii	are	
 slmfer to those for drilling wastes and purge water.
                                                       contamination in the soil sufficiently to meet NYSDEC Soil
                                                       Cleanup Criteria.  As^a remediation goal to evaluate this
                                                       objective, the developers expected that 90% of the soil
                                                       samples collected from the anticipated vadose zone in the
                                                       plot after 5.5 months (nominally one warm season) of
                                                       operation would be below NYSDEC Cleanup Criteria for six
                                                       target VOCs (acetone: 0.2 ppm, MEK: 0.6 ppm, MlBK: 2.0
                                                       pjjjm, cis-DCE: 0.6  gpm, TCE: ' 1 .5 ppm, and PCE: 2.5 "
                                                      ..... '    ........................................ ...................        .....................   ..................          ....................       ....................
Site Requirements

A UyB  microbial  treatment system  consists of several
major components: a dual-screened well, stripping reactor,
bfefjjter,  well  packer,   submersible1	pump]	blower!	
aboveground vapor phase  bioreactors,  and  carbon
Adsorption units. A drill rig is required to install and remove
frie well casing and to installtfieeo]ulprnelirwltrt?ntfiewefl
ItSelf,                ;",'   ':., '          '.
                     ',' I'1,1  ,; '!"!''i      ' '   ',',,'
The site support requirements needed for the UVB system
are potable water, electricity, and space to set up the ex-
situ bloreaqlors and off-fas treatment system. The blower
requires standard 440 VQlts (200 amperes). An electrical
pole, a 4OT-yolt  3-ghase ranverter for  the operating
systerri'i	incf	elec^Eal	RojoRup	Bitwein	fh'e	supply	Rneii	
pole, and Ifie  UVB  treatment system are necessary to
supply power.   The  space  requirements  for  the
aboyeground components of ffie UVB system, including the
"" ^ system well, off-gas treatment units, blower,  and
     j  used  during  the  SITE  demonstration,  were
apprSxtrnately  250 square feet.  Other requirements for
instajlatlon „ and routine  monitoring	of	the	system	may	
Include access roads for equipment transport, security
fencSlig, and decontamination water and/or steam for
drilling and sampling.
Thesiteshopd"	be~FeiatiYeiy	level	and	clesir^FoBsfrucHoni	
to facilitate well and equipment  placement.   As noted
earlier, vadose'and saturated zones should be well defined
and  shou!q*  be reasonably consistent from  season to
season,   '	       "  ''"	'

Performance Data
          ^    .     •{'  ••'
pilot-scale testing of the UVB-400 in situ process was
conducted in a 50 ft x 50 ft plot at the Sweden-3 Chapman
landfill in Sweden, New Vork'as part of the Multi-Vendor
Demonstration,
          (' I          I |
A primary objective of the demonstration was to determine
the effectiveness of the technology in  reducing VOC
           i           i    i
                                          In ................... addition! ..................... the .................. developers .................... claimed .................... that .........
                                 biodegradation would be the dominant mechanism  of
                                 contaminant removal from the formation. The developers
                                 also expected that groundwater would exhibit significant
                                 reductions  in VOC  concentrations as  a result of the
                                 recircuiation cell through the in situ biofilter. Finally, as an
                                ........ acjjuTict ......... to ........... the ............ prpjecli ............. Ifie ............ developers ............. also ............ iougHt ........... to .........
                                 evaluate the effectiveness of ex situ biofilters in removing
                                 VOCs from the air extracted from the formation.

                                              the primary and  secondary objectives,
                                 samples from the  soil, groundwater, and extracted air
                                 streams were collected at intervals starting  in July 1994
                                 and continuing  to  the termination  of  the  project  in
                                 September 1995. To assure that a maximum number of
                                 the soil samples would contain detectable concentrations
                                 of the critical VOCs, the plot was first divided into a 3 x 3
                                 grid. Soil borings (2-inch  split spoon) from the expected
                                 vadose zone '(-9 to 15 ft below ground surface, bgs) were
                                 first scanned by a field photoionization detector (PID). On
                                 the basis  of this screening,  sixteen additional boring
                                 locations were  selected  to maximize  the  detection  of
                                 contamination. It quickly became clear that the vadose and
                                 saturated zones were  not clearly  defined and  that the
                                 vadose zone was  usually  much narrower than the
                                 anticipated  9 - 15 ft bgs.   To overcome some  of these
                                 unanticipated problems,  samples  were designated as
                                 "vadose" or "saturated" and were analyzed separately. In
                                 addition, again to assure maximum  contamination, the
                                 sample from each 2-foot split spoon section was  selected
                                 based on a "hot spot" reading by the PID. Consequently,
                                 the resulting -50 samples from the 25 borings obtained
                                 during  each sampling event cannot be considered to be
                                 representative of the site,  and  may not even be
                                 representative of an  individual  core.   Samples were
                                 analyzed for VOCs, other contaminants, microbiological
                               ..................... activity^ ............... and .................. nulnints ................. to .................. assess ................... performance  and
                                 effectiveness of the system.

                                 When preliminary results indicated that little decrease in
                                 soil VOC concentrations  was occurring during  the first
                                 growing season,  due to  bad weather  and operational
                                 difficulties or the unique characteristics of the UVB system,
                                 the EPA and the  NYSDEC agreed  to continue the
                                 evaluation through a second warm  season.  Operation of
                                 the in situ system was  continued through the winter and
                                 was assumed, for evaluation purposes, to be continuous
                                 for the 14-month test period. Modifications to the system
                                 also were made in the Spring of 1995 to accommodate
                                 large, unanticipated  variations in the water table and to
                                 assure that the exhausted air passed through the ex situ
          ill	
I	In   tllli
                                                                          iii
                                                                                                         HI ill

-------
 vapor phase bibfiffers.

 The primary objective (achievement of the NYSDEC Soil
 Cleanup Criteria) was evaluated by measuring the residual
 concentrations of the selected VOCs in grab samples from
 cores obtained from twenty five locations within the test
 plot at the completion of the first season (-5.5 months) and
 at the end  of the 14-month  test period.  Although the
 original intent was to  evaluate the effectiveness  of the
 technology for the vadose zone only, a high and variable
 water table left only a very shallow vadose zone and made
 it prudent to evaluate changes in both the vadose and the
 saturated zone.

 The  second objective, estimating the contribution of
 biodegradation to overall  removal,  was  assessed  by
 several biological and  chemical measurements over the
 course  of the demonstration.  In addition to VOC mass
 removal, other measurements used to assess the extent of
 biodegradation included: changes in CO2,02, cis-DCE and
 vinyl  chloride  concentrations,  and  changes  in  total
 heterotroph and TCE-degrading microbial growth in the soil
 and groundwater.   The mass removal  of VOCs  in the
 groundwater could not readily be estimated because of
 factors such as flushing and migration.

 Based on the analytical results (Table 2), the developers
 were not successful in meeting the 90% cleanup objective,
 even after 14 months.  Only 65%  of  the usable soil
 samples collected in the plot after 5.5 months and 70% of
 the samples collected after 14 months met the NYSDEC
 Cleanup Criteria. (At the outset of the demonstration the
 calculated compliance was 67%).

 As  indicated in  Table  2,  some  of the  analytical  data,
 primarily for acetone and  MEK,  could  not  be utilized
 because detection limits were higher than  the NYSDEC
 criterion for that contaminant and it could, consequently,
 not be determined whether these samples met the Criteria.
 Higher-than-anticipated concentrations of aromatic VOCs
 (compared  to predemonstration  data)  were a  major
 contributing factor in the high detection limits for the critical
 analytes.

 Table 3 compares  initial and final (14 month)  calculated
 masses for the six critical VOCs and toluene, using the
 Practical Quantitation Limits (PQLs) for "ND" value, and
 also indicates the relative contribution to VOC removal in
 the exhausted air.  Ketone removals from the soil appear
 to be more extensive than removal  of chlorinated
 hydrocarbons; cis-DCE  results may be ambiguous due to
 production of this compound by degradation of TCE and/or
 PCE.

 Because of apparent elevated masses of VOCs after 5.5
 months,  the contribution of biodegradation (if any)  to
 removal could not be estimated.  Using calculated values
for the masses of each VOC at the 14-month event and the
masses of each contaminant removed in the extracted air
      Table 2. UVB Compliance with NYSDEC Cteanup Criteria
VOC

Criterion
(ppb)
Usable
Data
Points
f#)
Data Points
Meeting
Criterion
Oft (%)
                RESULTS AFTER 5.5 MONTHS
       Acetone

       MEK

       MIBK

       DCE

       TCE

       PCE

       Total
 200

 600

2000

 600

1500

2500
 11

 12

 23

 32

 31

 31

140
 0

 0

21

14

27

29

91
 0

 0

91

44

87

94

65
                RESULTS AFTER 14 MONTHS
Acetone
MEK
MIBK
DCE
TCE
PCE
Total
200
600
2000
600
1500
2500

19
25
46
46
46
46
229
0
4
45
22
45
44
160
0
16
98
48
98
96
70
     Note: (*) Data reported as non-detectable were not utilized
     in  the evaluation if the detection limit was above the
     NYSDEC Criterion.

     Developers  "credited"  with  any samples  that were
     uncontaminated initially.
stream and in  the  knockout  water  (very small), rough
estimates  of  removal  (61-70%)  and  the   potential
contribution  of biodegradation   (94-98%)  could  be
calculated  for the ketones, but not for the chlorinated
VOCs.   The effects  of extraction, biodegradation, or
flushing by groundwater on any of the contaminants are not
included. Degradation of TCE and/or PCE to cis-DCE is
another factor that may be affecting the observed values
for cis-DCE.

Other data expected to support numerical data do not
clarify the interpretation of the results of this demonstration.
Oxygen and carbon dioxide concentrations in the extracted
air remained essentially unchanged, as expected, because
of the intake of ambient air.  TCE-degrading microbial
populations in the soil and the groundwater were small and
decreased over the course of the demonstration, providing
little support for biodegradation of the chlorinated VOCs.
On the other hand, average total heterotroph populations
for the soil samples,  with approximately a 7-fold increase
over the course of the demonstration, were more indicative
of biodegradation; however, total heterotroph populations
in groundwater samples decreased over the course of the

-------
  Tabla 3. VOC Removals by UVB System after 14 Months

     ill in nil
         vbd
                              Mass in Soil (gm)
   Mass      Overall Percent
Removed in      Removal
Air & Water
Percent Potentially
  B|odegraded
Acetone
MEK
WIBK
cfS-DCE
TCE
PCE
Toluene


3700
6300
2200
1900
1500
380
58000


960
2100
440
1200
3200
350
7400


	 lymj
120
58
69
2200
510
120
1900


74
67
80
37
8
	 : 	 : 	 : 	
87

71
66
77

-
84


demonstration. These observations,  the  high  removal
efficiency for the ketones, and the apparent production of
cSs-fja-dlchioroethene  would   suggest  that  some
b!odegrada|6n Is underway, althoughIhe evktenceTs not
strong. The detection of significant concentrations of vinyl
chloride (VC) in the exhausted air and in groundwater (but
not  in soil  samples) suggests that  biodegradation is
occurring, but that anaerobic mechanisms rather than the
expected aerobic mechanisms may be operative.

Analyses of groundwater samples, particularly those from
Weils upgradient of the UVB well, indicate significant but
Variable reductions	in	VOC	conjamjnation	over the	course	
     g	deirw^ffixi^gJTJjiSjfiy^	in	'wells	closer	to"	trie	
     	well!	"^roun3wa!eiTvii^	dili	initially	and	for each
sampling event also indicated that concentrations of all
• contaminants^increasedJdpWngradjent^from the UVB well.
The data also	Indicate	IfiaT	Ivt'EK	cis-DCE, toluene and
vinyl chloride were the most prominent VOCs, and that the
ketones  tended to be  concentrated  in  the   shallow
groundwater  while  th|  chlorinated  ethenes were
concentrated	in	the	deeg	Monitoring wells, as might be
anticipated!	Vinyl	cHon3e	remained"	if	significant	
concentrations in all wells throughout the 14-month study,
     jesting that anaerobic biodegradation was occurring.

Analyses of influent to and effluent from the in situ biofilter
Indicated that VOC removal was taking place in the biofilter
over the course of the demonstration as well as during the
short residence time in Ihe BTofilter.  It is not possible to
attribute this to biodegradation or adsorption without more
extensive testing.

Due to excessive head'"loss* the original single, spiral-
Wound vapor phase biofifter was replaced in April 1995 with
two biofilters, each containing  seven carbon cartridges.
Operating in parallel, the new design produced much lower
hea,d loss.  Flow and VOC data confirmed that the changes
were successful In assuring uniform passage of air through
 the two  trains.  Sampling and analysis of the air stream
 before and after the two redesigned indicate target VOC
                                                           removals  of about  60%  to  75%,
                                                           mechanisms cannot be defined.
                                         but the  removal
                                                           In general; various aromatic compounds were much more
                                                           prevalent than the target VOCs in all soil samples. Toluene
                                                           is included in the data compilations as an example. High
                                                           concentrations of these aromatic VOCs adversely affected
                                                           the ability to detect or quantify low concentrations of the
                                                           target  VOCs,  but  they  also  may have served  as
                                                           cometabplites for biodegradation - if the concentrations
                                                           were not high enough to cause toxicity to the biological
                                                           system.

                                                           	For	the"	T'£monfh~	deTnoTistration j	the estimated cost was'
                                                           $347/yd3 to treat about 628 yd3 in the test plot. The cost to
                                                           remediate approximately 13,000 cubic yards of similarly
                                                           contaminated vadose zone soil over a 14 month period at
                                                           the  Sweden-3  Chapman site using 22 UVB wells  is
                                                           estimated at $149/yd3. Increasing the treatment time to 3
                                                           years  or  5  years,  as  suggested by  the developers,
                                                           increases the cost to $259/yd3 and  $375/yd3, respectively.
                                                           Because of the nature of the technology, saturated zone
                                                           soils and groundwater within the radius of influence would
                                                           also be treated simultaneously. However, no credit was
                                                           taken for groundwater treatment in this economic analysis,
                                                           i'i" which focused on vadose zone soil treatment As the full-
                                                           scale"	T^monTn"	cos!	analysis	wis	confTgurecT	the	largest	
                                                           cost categories are site preparation and equipment costs,
                                                           accounting for 40% and 22% of the costs. Labor accounts
                                                           for 17% of the costs.  As the  duration of the remediation
                                                           increases, the contribution   of site preparation  costs
                                                           decreases and the labor cost increases.  This technology
                                                           is typical  of  other bipremediation  processes in that the
                                                           majority of the costs are in the initial site preparation and
                                                           startup phases. For this estimate no costs were assigned
                                                           for  permitting  and   regulatory  requirements  or  facility
                                                           modification, repair or replacement.
                                                                                    i

                                                                              1 inn in i n in i ii i ii iiiii in in ii mi mi
"'I                               I
III Jill                         III  11


  II   I   11 III ill    lllllllllll I  III  I I    II I llllllllll I Illllllllllli I Illllll  111 III II I I III	Ill	
                                                                                                        :	ii!	

-------
Technology Status
investigation.
The DVB microbial technology has been  utilized  at a
number of  sites throughout  the  world,  primarily for
treatment of BTEX-contaminated groundwater.

Disclaimer

The data, observations and conclusions presented in this
Capsule  have  been   reviewed  by  EPA's   Quality
Assurance/Quality Control Office.

Sources of Further Information

An  Innovative Technology Evaluation Report  will be
available for the DVB technology and  for the other two
technologies that were evaluated as part  of the same
EPA Contact:

U.S. EPA Project Manager
Michelle Simon
U.S. EPA NRMRL
26 W. Martin Luther King Jr. Dr.
Cincinnati, OH 45268
(513) 569-7469
Fax (513) 569-7676
email: simon.michelle@epamail.epa.gov
New York State Contact:
NYSDEC Project Manager
 James Harrington, P.E.
New York State Dept. of Environmental
Conservation, Room 222
50 Wolf Road
Albany, NY 12233
(518)485-8792
Fax (518) 457-1088
NY State Center for Hazardous Waste Mgmt.
Professor Scott Weber
Jarvis Hall
SUNY at Buffalo
Buffalo, NY 14260
(716)645-2114
Fax (716) 645-3667
Technology Developers:

Richard Desrosiers
MACTEC, Inc.
1819 Denver West Drive, Suite 400
Golden, CO 80401
3032783100
303 278 5000 fax
76435.2527@compuserve.com

Jim Mueller
Dames and Moore
1701 Golf Road
One Contental Towers, Suite 1000
Rolling Meadows, IL 60008
847 228 0707
847 228 1328 fax
chijgm@dames.com
                                                           GOVERNMENT PRINTING OFFICE: 1999 - 750-101/00059

-------
                                                                                                                                                                                                                ii          !
        i
    	'	|l	i	
lllllll
,  ,	III',!,
Illlllll!

	I	
                                                                                                                                                                                            1	1,1	lii,,1
                                                                                                                                                                                                            i.	ill

-------

-------
1
1?:;
|:

i; "


"*-



-B-r,!

s


i

-i" -




— «-
~-r :
4

m
SK


Ii

^ ",
3F--











;;_ --


=« ^^^ s .-. - --• — — ir
United States ......_ please make all necessary changes on the below label, detach II
Environmental Protection Agency or copy, and return to the address in the upper left-hand corner. jl
Center for Environmental Res
Cincinnati, OH 45268


Official Business


'enalty for Private Us
$300

EP,/
"


n i
n i


i i


I






i
i











I!
f flp:





'- --
=U^:















V5;|

"
I [












f



:I =

...
-^
=
-
0/R-


p
1

)3a

1
K ! s,
m t-












f






^~:
S
j

H

i I
i
l

"||



~*i



4
1
:.sr
_^t


>e


:" - "•- -•: -'^




| :
I

earch Information )f you do no{ wjsh {o recejve these reports CHECK HERE[-,; j • j |
detach, or copy this cover, and return to the address in the i ^

upper left-hand corner.
.; i __ ! J I
II - • • •
I 1 1

ii = • «
- , i



1
I - • • !
a • i
= mm
~ = s
!l

I I I S ' -
a •
• =
lie
-: _
I



1 1 ! •
1 l !! !
i I Ii 1 • •
4 -1 11
- Ill : I
= • = = = = ^
! ! I
= « i
! i i

«
i sl
i i ii









=:-







:---~





1 1
! I
I I
l
I =1


t


:-"- -i»: :-
, -



_ ; :'-}«

-.
---^---w













= •
=
1
1 1
- !
i i i

I_=
=
• i
i
i l
i
= = =
! 1
~ •
•
j -:-.-.-:
i _ . - _
r--=r-— -= -- -= -s - -= - — 	 = ^^— - =
i iii
1 ! !•
! JI
i

i : i I
, . ^
i 11
•- I •
. =
l i •
1 1 i
i il
1 a m
i il
1 !!
1 Ii
i ii
= San
T
|I
1
! 1
1 _ 4
i i
± |
i
• - - - —~° - -'

l|
"i


i










-i^-







w
Fif -B


i
M
-II
I

i i
n
. i

*• ~



i
i i
il
;

















PRESORTED STANDARD
POSTAGE & FEES PAID
EPA
PERMIT No. G-35


1
i
!
| •
! H
I]
-M
1|
j|
:=
l m
~m
1
H
•
1

- '|
-:|
1
1
f
	
--~a
1
1
; H-
1
1
-

HI





i
• .11
M
I || .-



j












"








=
'- f
=a
n.
il
M! i ;
II I
1 II
; i











.-- - -



"--, ."•_


JZf









-
-i
-

i

i .





•-








-

•••-.:
-



ii




"i

'
-






- =f~ -

.___-*-


--,_.


1^;

























;;




-r-~




! :

i






-- -

III

f •*
f :J

II f
|I [
I ^
Hi . t





--*

.4

I! 1






-
i i






—
-^


j


--T


-4









W >L
-•---
r


.-->








-^
ii >




in -i
ISi t





'=?
-j^l

j
\~4


irt

-------