vvEPA
                           United States
                           Environmental Protection
                           Agency.
EPA/540/SR-93/506
February 1994
                            SUPERFUND INNOVATIVE
                            TECHNOLOGY  EVALUATION
                            Technology Demonstration
                            Summary

                            CWM  PO*WW*ER™
                            Evaporation-Catalytic
                            Oxidation  Technology
                              As part of the Super-fund Innovative
                            Technology Evaluation (SITE) program,
                            the U.S. Environmental Protection Agen-
                            cy (EPA) demonstrated the Chemical
                            Waste Management, Inc. (CWM),
                            PO*WW*ER™ technology. The  SITE
                            demonstration was conducted in Sep-
                            tember 1992 at CWM's Lake Charles
                            Treatment Center (LCTC) site in  Lake
                            Charles, LA. During the demonstration,
                            the PO*WW*ER™ system treated landfill
                            leachate contaminated with volatile or-
                            ganic compounds (VOC), semivolatile
                            organiccompounds(SVOC), metals, am-
                            monia, cyanide, and other inorganic
                            contaminants.
                              SITE demonstration results show that
                            during treatment in  the PO*WW*ER™
                            system, the volume of  the landfill
                             leachate was significantly reduced. A
                            total solids (TS) concentration ratio of
                             32 to 1 was achieved. The SITE demon-
                             stration results also show that the
                             PO*WW*ER™ system effectively re-
                             moved sources of  toxicity such as
                             VOCs, SVOCs, metals, ammonia, and
                             cyanide. Concentrations of VOCs and
                             SVOCs in product condensate exiting
                             the PO*WW*ER™ system were below
                             their respective detection limits of 5 to
                             10 micrograms per liter (ug/L) and 10 to
                             130 ug/L. Product condensate contained
                             trace levels of metals. Ammonia and
                             cyanide concentrations in the product
                             condensate samples were below their
 respective detection limits of 0.1 and
 0.01milligramsperliter(mg/L).Theprod-
 uct condensate was nontoxic but only
 after it was cooled and its pH, dissolved
 oxygen level, and hardness or salinity
 were increased to meet demonstration
 objectives and as allowed in EPA acute
 toxicity testing procedures. Nonconden-
 sible vent gas emissions met proposed
 permit requirements for the LCTC site.
   Data provided by CWM show that the
 PO*WW*ER™ technology can effective-
 ly treat the following wastes: (1) landfill
 leachate, (2) contaminated well water,
 (3) contaminated lagoon water, (4) fuels
 decant water, (5) oil emulsion wastewa-
 ter, and (6) nitrogen-containing organic
 compounds wastewater. The PO*W-
 W*ER™ technology also effectively
 treats the following contaminants:
 VOCs, SVOCs, pesticides, herbicides,
 solvents, heavy metals, ammonia, cya-
 nide, nitrate, chloride, and sulfide.
   This Summary was developed by
 EPA's Risk Reduction Engineering Lab-
 oratory (RREL) in Cincinnati, OH, to an-
 nounce key findings of the SITE pro-
 gram demonstration that is fully
 documented in two separate reports (see
 ordering information at back).

 Introduction
   The SITE program was established in
  1986 to accelerate the development, dem-
 onstration, and use of new and innovative

           T$S) Printed on Recycled Paper

-------
 technologies that offer permanent cleanup
 solutions for hazardous waste sites. The
 SITE program is administered by the EPA
 Office of Research and DevelopmentRREL
 One component of the SITE program is the
 demonstration program, which develops
 reliable performance and cost data on in-
 novative technologies so that potential us-
 ers can assessatechnology'ssuitabilityfor
 specific site cleanups.
  ThePO*WW*ER™technologySITEdem-
 onstration was conducted atthe CWM LCTC
 In Lake Charles, LA, in September 1992.
 ThePO*WW'ER™pilot-scaleplantatLCTC
 has been operative since 1988. The pilot
 plant is used primarily as a demonstration
 unit  for parties interested in testing the
 system's applicability for treating specific
 aqueous wastes.
  The technology demonstration had the
 following objectives:
      Evaluate the technology's  ability to
      concentrate and reduce the volume
      of an aqueous waste to brine for
      further treatment or disposal
      Evaluate the technology's  ability to
      remove organic and inorganic con-
      taminants from landfill leachate
      Evaluate the technology's  ability to
      produce a noncondensible gas
      stream that meets proposed permit
      requirements for the LCTC site
  *   Evaluate the technology's  ability to
      produce a oondensate stream non-
      toxic to aquatic organisms
      Document the PO*WW*ER™ sys-
      tem's operating conditions and iden-
      tify potential operational problems
      Developthetechnology'scapitaland
      operating costs for use in the Super-
      fund decision-making process

Technology Description
  The PO*WW*ER™ system  reduces the
 volume of an aqueous waste  and catalyti-
 cally oxidizes volatile contaminants. Figure
 1 showsaflowdiagramofthePO*WW*ER™
 pilot scale plant, which was used during the
 SITE demonstration. The  PO*WW*ER™
 system consists primarily of an evaporator
 to reduce the influent wastewater volume,
 a catalytic  oxidizer to oxidize the volatile
 contaminants in the vapor stream from the
 evaporator, a scrubber to remove acid gas-
 es produced during  oxidation, and a con-
 denser to condense the vapor stream leav-
 ing the scrubber.
  The evaporator consists of three main
 pieces of equipment: the heat exchanger,
 the vapor body, and the entrainment sepa-
 rator. As feed waste is pumped to the
 evaporator, it combines with  heated pro-
 cess liquor. The feed waste is then further
 heated  in a vertical shell-and-tube  heat
 exchanger, before entering the vapor body,
 where boiling occurs and vapor is released.
 A portion of the concentrated brine is re-
 moved from the vapor body when the brine
 temperature reaches a value correspond-
 ing to a specific brine boiling point. The
 remaining brine is recirculated. Vapor exits
 the vapor body to an entrainment separa-
 tor, which removes water droplets.
  Vapor from the evaporator is heated to
 oxidation temperature by a direct-fired pro-
 pane burner.  In the PO*WW*ER™  pilot
 plant, air is fed to the system by a compres-
 sor. The heated vapor then enters the cat-
 alytic oxidizer and passes through the cat-
 alyst bed where oxidation takes place.
  Afteroxidation, the vapor stream exits the
 catalytic oxidizer and passes through awet
 scrubber to neutralize the acid gases pro-
 duced in the oxidizer. The scrubber con-
 sists of a packed bed in which  the vapor
 passes countercurrently through caustic
 solution.
  Vapor exiting the scrubber is cooled and
 condensed in a shell-and-tube condenser.
 The product condensate is collected in a
 condensate holding tank where  it remains
 until it is transferred to a stainless steel
 product tank. This product condensate can
 either be reused as boiler or cooling tower
 makeup water, or discharged to surface
 water, if appropriate.

Technology Testing
  The demonstration was conducted under
 one set of operating parameters,  which
 were established by CWM based on previ-
 ous operating experience  with  the
Caustic


i
3d 	 ^
ste
r
Feed
Tank
Acid
• Rir
Antifoam Wa
Agent
\

ise
ter H
r \
Propane 	 >•
eat
Air
• 1

x\ ^ Evaporator


j

Burner
i

Oxidizer
•* 	

                                                                       -Air
                                                                                   Noncondensible
                                                                                        Gas
                                                                                               KEY
                                                                                          Sampling Locations
Figure 1. Schematic diagram showing sampling locations for the PO*WW*ER™ pilot plant.

-------
PO*WW*ER™ system. These operating
parameters were applied in two sets of test
runs: one set of three replicate test runs
using unspiked LCTC landfill leachate and
one set of three replicate test runs using
spiked LCTC landfill leachate. The landfill
leachate, an F039 hazardous waste, was
spiked with the following compounds: 100
mg/L each of methylene chloride, tetra-
chloroethene (PCE), and toluene; 10 mg/L
of phenol; 2 mg/L of cadmium; 0.2 mg/L of
mercury;  and 50  mg/L each of copper,
nickel, and iron. The purpose of spiking the
feed waste was to test the effect of contam-
inant loading on the PO*WW*ER™ sys-
tem's performance.
  Each demonstration test required about 9
hr of PO*WW*ER™ system  operation to
conduct sampling and monitoring  activi-
ties. During the tests, landfill leachate was
processed at an average rate of 0.18 gal-
lons per minute (gpm).
  Sampling began when the PO*WW*ER™
system operated under steady-state condi-
tions. During each test run, samples were
collected from the feed waste, product con-
densate, brine, and noncondensible gas
stream. Feed waste, product condensate,
and brine samples were analyzed for total
suspended solids (TSS), total dissolved
solids  (TDS), VOCs,  SVOCs, ammonia,
cyanide,  metals, chloride, sulfate, nitrate,
pH, oil and grease, total organic  halides
(TOX), and total  organic carbon  (TOG).
Samples of feed waste and  product con-
densate were also analyzed for acute tox-
icity. Brine samples were also analyzed for
toxicity characteristic  leaching procedure
(TCLP) metals, VOCs, and SVOCs. Con-
tinuous emissions monitoring (GEM) of the
noncondensible gas stream included mon-
itoring for carbon monoxide (CO), sulfur
dioxide (SO2), nitrogen oxides (NOX), and
total nonmethane hydrocarbons (TNMHC).
Noncondensible gas  samples were also
collected and analyzed for VOCs, SVOCs,
and hydrochloric acid (HCI).
  Critical analytes for the feed waste and
product condensate included TSS, TDS,
VOCs, SVOCs, ammonia, cyanide,  and
acute toxicity, which was a critical analyte
only for the product condensate. Critical
analytes for the brine were TSS and TDS.
Critical analytes for the noncondensible
gas stream were CO, SO2, and NOX.

Demonstration Results
  Demonstration results are  based on ex-
tensive laboratory analyses.  The following
sections discuss critical parameters, non-
critical parameters, PO*WW*ER™ system
reliability, and an economic analysis.
  During the SITE demonstration,  CWM
imposed testing and monitoring limitations
that restricted data collection for the evalu-
ation of the PO*WW*ER™ system's perfor-
mance. These limitations were imposed to
protect CWM's proprietary know-how of
the PO*WW*ER™ system.

Critical Parameters
  Critical parameters forthe demonstration
were volume  reduction, VOC removal,
SVOC removal, ammonia and cyanide re-
moval, acute toxicity, and noncondensible
gas emissions. These parameters are dis-
cussed below.  ,

Volume Reduction
  During  each 9-hr  test  run,  the
PO*WW*ER™ system  processed  about
98 gal of feed waste. Brine was wasted and
sampled  only once during each 9-hr test
period. The total amount of brine wasted
during each 9-hrtest run was about 4.8 gal,
or about 5% of the total feed waste volume.
  The PO*WW*ER™ system's effective-
ness for volume reduction was evaluated
based on the concentration ratio, which is
defined as the ratio of the TS concentration
in the brine overtheTS concentration in the
feed waste. The TS concentration is the
sum of the TSS and TDS concentrations.
The TS concentration ratio was estimated
to be about 31 to 1 during the unspiked
tests and 32 to 1 during the spiked tests.
Similar results were obtained for metal and
chloride concentration ratios. The average
TS,  metal, and chloride concentration ra-
tios were statistically the same. Therefore,
these concentration ratios are considered
to represent a reliable measure of feed
waste volume reduction achieved  by the
 PO*WW*ER™systemduringtheSITEdem-
onstration.

VOC Removal
  The PO*WW*ER™ system removes
 VOCs from the feed waste by evaporation.
 VOCs are subsequently oxidized  in the
 catalytic oxidizer. Acetone,  2-butanone,
 methylene chloride, PCE, toluene, and vi-
 nyl chloride were identified as critical VOCs
 for the SITE demonstration. Vinyl chloride
 is not discussed further because it was not
 detected during unspiked and spiked test
 runs in feed waste, product condensate, or
 brine.
  The results in Table 1  show that during
 the  unspiked  and  spiked test runs, the
 concentrations of all critical VOCs,  except
 for methylene chloride, in the product con-
densate were belowtheir respective detec-
tion limits (5 to 10 ng/L). Methylene chloride
was detected in the product condensate
only during the second unspiked test run at
a concentration of 6 p.g/L. In addition, the
results show that total contaminant load-
ing, which increased during the spiked test
runs,  had  no measurable  effect on the
quality of product condensate under the
conditions tested. However, total contami-
nant loading appeared to have some effect
on VOC evaporation efficiency. For exam-
ple, during the unspiked test runs, the ace-
tone and methylene chloride concentra-
tions in brine samples were less than their
respective detection limits of  100 and 50
(ig/L for most samples analyzed. However,
during the spiked test runs, these contam-
inants were not completely removed from
the brine. Acetone and methylene chloride
concentrations in brine samples ranged
from 180 to 220 ng/L and 110 to 200 (ig/L,
respectively.

SVOC Removal
  Benzoic acid and  phenol were identified
as critical SVOCs for the SITE demonstra-
tion/The results in Table2showthat during
the unspiked and spiked test runs, benzoic
acid and phenol concentrations in product
condensate were less than their detection
limits, which ranged from  25  to 130 ng/L
and from 10 to 50 p.g/L, respectively. The
results also indicate that benzoic acid re-
mained primarily in the brine, while phenol
was removed from the brine, at least par-
tially, and was presumably oxidized.
  Although benzoic acid  and phenol are
both  acidic compounds,  they have very
different physical-chemical properties. Giv-
en these properties, phenol is more  likely
than benzoic acid to be removed from the
brine. Phenol has a vapor pressure over 30
times greater than that of benzoic  acid.
Also, under the test conditions, phenol was
likely present in the brine primarily in union-
ized  form while benzoic acid was  likely
present in ionized form.
  Other factors that may have affected the
removal of phenol from the brine include
the brine's boiling point rise (BPR),  strip-
ping  action of steam, and  ionic strength.
While phenol has a boiling point of 358 °F,
significantly higher than the steam temper-
ature used for heating in the evaporator
heat exchanger, the evaporation of phenol
can take place in the evaporator because
of the increase in the brine's boiling point,
which is known  as the BPR, and the strip-
ping action of steam released during boil-
ing. Another condition that  could  have

-------
Tab/9 1. Average Critical VOC Concentrations Dudng Unspiked and Spiked Test Runs
Unspiked Test Runs
Run No. Feed Waste

1
2
3

1
2
3

1
2
3

•1
2
3

1
2
3

11,000 M"
8,700 M
9,100 M

2, 100
1,500
1,800

1,100
1,100
690

<390
<500

-------
Table 3. Average Ammonia and Cyanide Concentrations During Unspiked and Spiked Test Runs
                   Unspiked Test Runs
                Spiked Test Runs
Run No.

1
2
3

1
2
3
Product
Feed Waste Condensate Brine3 Feed Waste

150
150
160

29
33
30


<0.10
<0.10

<0.01
<0.01
<0.01
Ammonia (mg/L)
5.4
23 H
11
Cyanide (mg/L)
77
150
140

160 H=
150 H
140

33
32
24
Product
Condensate

<0. 10 H
<0.10H
<0.10

<0.01
<0.01
<0.01
Brine3

7.8 H
7.5 H
7.4

36
17
77
  Brine was wasted and sampled once per test run. Therefore, the reported results represent
  analysis of one sample. However, the results for feed waste and product condensate represent the
  average of three composite samples collected during each run.
  <=Analyte not detected at the quantitation limit shown.
  H indicates that analyte concentration is estimated because sample holdng time was exceeded.
  Two test conditions were evaluated. Un-
der test condition 1, feed waste and prod-
uct condensate samples were adjusted to
pH, temperature, and hardness or salinity
levels optimum for survival of the test or-
ganisms. Under test condition 2, all above-
mentioned conditions were adjusted ex-
cept hardness. Only product condensate
samples were tested under test condition
2, with Ceriodaphnia dubiaand Pimephales
promelas as test organisms. Tests under
test condition 2 were conducted to examine
the effect of  hardness on the toxicity  of
product condensate.
  The results indicate thatthe PO*WW*ER™
system removed sources of toxicity in feed
waste. Feed waste was highly toxic to all
test organisms, with LC50 values consis-
tently less than 10%. Product condensate,
however, was found to be nontoxic with all
LC50 values statistically greater than 100%,
but only after the product condensate was
cooled and its pH, hardness, and salinity
were adjusted to meet demonstration ob-
jectives and as allowed in EPA acute toxic-
ity testing procedures.
Noncondensible Gas
Emissions
  CEM of the noncondensible gas was con-
ducted for CO, SO2, NOX, and TNMHC.
Average and maximum concentrations and
emission rates are summarized in Table 4.
Noncondensible vent gas samples were
collected and analyzed for VOCs, SVOCs,
and HCI. The following VOCs were detect-
ed: chloromethane, bromomethane, meth-
ylene chloride,  acetone,  1,1,1-tri-
chloroethane,    carbon   disulfide,
2-butanone, benzene, PCE, toluene, chlo-
robenzene, and ethylbenzene. The critical
VOC present in the noncondensible gas at
the highest concentration was PCE.  All
other  VOCs were present at trace levels.
The highest PCE concentration occurred
during the first spiked test run,  which also
had the highest CO, SO2, NOX, and TNM-
HC concentrations. HCI and some SVOCs
were also  detected in the noncondensible
gas. The following SVOCs were present at
trace  levels in the noncondensible gas:
phenol, benzoic acid, bis-(2-ethylhexyl)
phthalate,  and di-n-octylphthalate.
  Noncondensible gas emissions results
indicate that increases in total contaminant
loading may result in small increases in
contaminant concentrations in thevent gas.
Table 4.  Noncondensible Gas Average and Maximum Contaminant Concentrations and Mass Emissions Rates
Contaminant
Average3 CO (ppmvf
Average CO (Ib/hrf
60-min RAd Maximum CO (ppmv)
60-min RA Maximum CO (Ib/hr)
Average SO2 (ppmv)
Average SO2 (Ib/hr)
60-rnin RA Maximum SO2 (ppmv)
60-min RA Maximum SOZ (Ib/hr)
Average NOX (ppmv)
Average NO (Ib/hr)
60-min RA Maximum NOX (ppmv)
60-min RA Maximum NOX (Ib/hr)
Average TNMHC (ppmv)
Average TNMHC (Ib/hr)
60-min RA Maximum TNMHC (ppmv)
60-min RA Maximum TNMHC (Ib/hr)
Un,
1
21.4
0.00217
22.5
0.00228
<2e
<0.00049
2.40
0.00056
242
0. 0404
253
0.0421
<2
<0.00033
<2
<0.00033
spiked Test Runs
2
9.58
0.00110
11.1
0.00127
<2
<0.00055
<2
<0.00055
260
0. 0491
275
0.0519
<2
<0.00037
<2
<0.00037
Spiked Test Runs
3
13.9
0.00151
15.4
0.00166
<2
<0.00052
<2
<0.00052
243
0. 0432
254
0.0452
<2
<0.00035
<2
<0.00035
1
37.3
0.00392
40.8
0.00428
<2
<0.00051
3. 49
0.00084
292
0.0503
309
0.0534
<2
<0.00037
3.95
0.00067
2
24.6
0.00244
26.5
0.00263
<2
<0.00048
2.87
0.00065
255
0.0417
280
0.0458
<2
<0.00032
3.54
0.00057
3
18.7
0.00169
1Q ft
i y.o
0.00179
^2
<0.00043

-------
Noncritical Parameters
  Noncritical parameters include metals;
chloride; sulfate; nitrate; pH; oil and grease,
TOX, and TOG; and TCLP metals, VOCs,
and SVOCs. These noncritical parameters
are discussed below.

Metals
  During unspiked and spiked test runs,
metals concentrated primarily in the brine.
Concentration ratios ranged from 31 to 1 to
35 to 1 during unspiked test runs and from
29 to 1  to 31  to 1  during spiked test runs.
However, during the test runs, trace levels
of the following metals were also present in
the product condensate: chromium, cop-
per, iron, manganese, nickel, and zinc.

Chloride
  During unspiked and spiked  test runs,
 chloride concentrated primarily in the brine.
 Concentration ratios ranged from 32 to 1 to
 35 to 1  during unspiked test runs and from
 28 to 1 to 33 to 1 during spiked test runs.
 Chloride was not detected in product con-
 densate samples. Because HCI was de-
 tected  in noncondensible gas  emissions
 but not in product condensate samples, the
 results suggest that HCI was formed in the
 oxidizerduringtheSITEdemonstrationand
 was only partially removed by the scrubber.

Sulfate
   The results show that sulfate concentrat-
 ed in the brine with an average concentra-
 tion ratio of 15.5 to 1, almost one half of the
 TS, chloride, and metals concentration ra-
 tios. The reason for the difference could be
 due to sulfate in the brine precipitating as
 metal sulfate salts. These salts could have
 deposited on the evaporator surfaces and
 in the brine transfer piping instead of being
 collected in the brine samples.

 Nitrate
   During unspiked and spiked test runs,
 nitrate concentrations in feed  waste and
 brine were less than their respective detec-
 tion limits of 0.05 and 5 mg/L for  most
 samples analyzed. However, nitrate was
 detected  in  product condensate. During
 unspiked test runs, nitrate concentrations
 in product condensate ranged from 0.23 to
 0.37 mg/L. During spiked test runs, nitrate
 concentrations  in  product condensate
 ranged from 0.44 to 0.68 mg/L Nitrate in
 product condensate could have resulted
 from the hydrolysis of NO2. Three sources
  of nitrogen that may have contributed to the
  formation of NO2 during oxidation in the
catalytic oxidizer are ammonia, air, and
cyanide.

pH
  During unspiked and spiked test runs, the
pH of feed waste was about 9 and the pH of
brine was about 10. The pH of feed waste
was not adjusted during the SITE demon-
stration. The pH of product  condensate
ranged from 3.8 to 4.3 during unspiked test
runs and from 4.0 to 4.2 during spiked test
runs. The acidic pH of product condensate
may have been because of the presence of
nitric acid formed by the hydrolysis of NO2.

Oil  and Grease, TOX, ahd TOG
  The  results  indicate that some  of the
 material contributing to oil and grease in
thefeed waste is removed during treatment
 in the PO*WW*ER™ system. During un-
 spiked and spiked test runs, oil and grease
 removal efficiencies were greaterthan 76%.
  During unspiked and spiked test runs,
 TOX primarily concentrated in the brine,
 with average concentration ratios of 32 to 1
 and 28 to 1, respectively. These ratios
 suggest that TOX is comprised of haloge-
 nated nonvolatile organic compounds.
  During unspiked and spiked test runs,
 TOC evaporation efficiencies were greater
 than 93%.

TCLP Metals
  TCLP test results for metals indicate that
 brine, which is an F039-derived hazardous
 waste, exhibits the D004 hazardous waste
 characteristic because it contains TCLP
 arsenic  at concentrations ranging from
 34,400 to 103,000 ng/L. These concentra-
 tions are greater than the regulatory level of
 5,000 ng/L. All other TCLP metals met the
 Resource Conservation and Recovery Act
 (RCRA) regulatory requirements.

 TCLP VOCs and SVOCs
   Both TCLP VOCs and SVOCs met the
 RCRA TCLP  standards. The results show
 that total  contaminant loading, which in-
 creased during the spiked test runs, result-
 ed in increased TCLP VOC concentrations.
 However, contaminant loading did not have
 a significant effect on TCLP SVOCs.

 PO*WW*ER™ System
 Reliability
   Generally,  the  PO*WW*ER™  system
 operated reliably during the SITE demon-
 stration. During startup, the PO*WW*ER™
 system required about 9 days to reach
 steady-state conditions because of the low
solids content  in the feed waste.  The
following operational  observations  were
made:
     A 1-hr area-wide electrical power
     outage caused  the temperature in
     the evaporator to drop, resulting in a
     5-hr delay until the system returned
     to steady-state operation.
     During the power outage, the evap-
     orator circulation pump shaft was
     manually rotated to prevent solids
     from settling in the piping.
     The brine sampling line became
     clogged  with solids, limiting  brine
     sampling until a new sampling loca-
     tion was made available.
  These are minor operational problems
that do not affect the system's reliability but
should be considered in the design of a
full-scale PO*WW*ER™ system.

Economic  Analysis
  Economic data indicate that the capital
cost for a 50-gpm PO*WW*ER™ system is
approximately $4 million on a turnkey ba-
sis, including treatability study costs; de-
sign costs; all necessary components of a
PO*WW*ER™ system; all interconnecting
piping, controls, and monitoring equipment;
and assembly and installation costs. Annu-
al operating and  maintenance, including
labor, consumables, utilities, analytical ser-
vices, and waste disposal, at a Superfund
site are estimated to be about $3.3 million.
Waste (brine) disposal costs account for
about 70% of the annual costs. At an annu-
al inflation rate of 5%, the total cost of a
 project lasting 15 yr was estimated to be
 about $100 per 1,000 gal of aqueous waste
 treated, and the total cost of a project
 lasting 30 yr was estimated to be about $73
 per 1,000 gal of aqueous waste treated.

Conclusions
  The following  conclusions  about the
 PO*WW*ER™ technology are based on
 the results of the SITE demonstration:
       The volume of brine wasted and sam-
       pled during each 9-hr  test  period
       consisted of about 5% of the feed
       waste volume  processed. The con-
       centration ratio, defined as the ratio
       of TS concentration in the brine over
       the TS concentration in the feed
       waste, was about 32 to 1.
       Feed waste average concentrations
       of critical VOCs ranged from 350 to
       110,000 ng/L; critical SVOCs ranged
       from 6,000 to 23,000 ng/L; ammo-
       nia ranged from 140 to 160 mg/L;

-------
and cyanide ranged from 24  to
33  mg/L. Generally, no VOCs,
SVOCs, ammonia, or cyanide were
detected in the product condensate.
Noncondensible gas emissions had
the following characteristics: (1) av-
erage  CO concentrations ranged
from 9.58 to 37.3 ppmv, resulting in
emission rates ranging from 1.1 x1 Cr3
to 3.92X10-3 Ib/hr; (2) average SO2
concentrations were less  than
2 ppmv, resulting in emission rates
of less than 5.5x1 O^lb/hr; and (3) the
average NOX concentrations ranged
from 233 to 292 ppmv, resulting in
emission   rates  ranging  from
3.46x10-2 to 5.03x10-2 Ib/hr.  Non-
condensiblegas emissions forthese
parameters met the proposed regu-
latory requirements for the LCTC
site.
Contaminant loading, which in-
creased during the spiked test runs,
had a  measurable effect  on  VOC
evaporation efficiency.  Also, in-
creased contaminant loadings result-
ed in small increases in contaminant
concentrations in the noncondensi-
ble vent gas.
The PO*WW*ER™ system removes
sources of feed  waste toxicity. The
feed waste was acutely toxic  with
LC50s consistently below 10%. The
product condensate was  nontoxic
with LC50s consistently greater than
100%, but only after the product con-
densate was cooled and its pH, dis-
solved oxygen level, and hardness
or salinity were increased  to meet
demonstration objectives and as al-
lowed in EPA acute toxicity testing
procedures.
Metals,  sulfate, chloride, and TOX
concentrated  in the brine. The aver-
age metals, chloride, and TOX con-
centration ratios are almost identical
to the TS concentration ratios. The
sulfate concentration ratio was sig-
nificantly lower, probably due to sul-
fate in the brine precipitating as met-
al sulfate salts. These salts  could
have deposited on the evaporator
surfaces and in the brine  transfer
piping instead of being collected in
the brine samples.
Nitrate, which was not present in the
feed waste and brine, was present in
product condensate. Nitrate proba-
bly formed in the product conden-
sate as a result of the hydrolysis of
NO2, which was formed during oxi-
dation in the catalytic oxidizer. The
acidic pH of the product condensate
supports this hypothesis.
TOC  evaporation  efficiency  was
greater  than  93%  during  the  un-
spiked and spiked test runs. Com-
pounds  that contribute to  oil and
grease were removed from the feed
waste and brine with removal effi-
ciencies of greater than 76%.
The F039-derived hazardous waste
brine exhibits the D004 hazardous
waste characteristic because it con-
tains TCLP  arsenic at concentra-
tions greater than the regulatory lev-
el of 5,000  ng/L. All  other TCLP
metals, VOCs, and SVOCs met the
RCRA regulatory requirements.
The PO*WW*ER™ system operat-
ed reliably during the demonstration.
However, some minor operational
problems  were observed during
shakedown and startup operations,
and during the SITE demonstration.
Operational  problems  included an
area-wide  electrical power outage
and brine sampling line clogging.
Economic data indicate that the capi-
tal cost for a 50-gpm PO*WW*ER™
system is approximately $4 million
on aturnkey basis. Annual operating
and maintenance costs at a Super-
fund site are estimated to  be about
$3.3 million.  At an annual inflation
rate of 5%, the total cost of a project
lasting 15 yr was estimated to be
about $100 per 1,000 gal of aqueous
waste treated, and the total cost of a
project lasting 30 yr was estimated to
be about $73 per 1,000 gal of aque-
ous waste treated.
                                                               Tfru.S. GOVERNMENT PRINTING OFHCE: 1994 - 550467/80242

-------
 The EPA Project Manager, Randy Parker, is with the Risk Reduction Engineering
     Laboratory, Cincinnati, OH 45268 (see below).
 The complete report, entitled "Technology Evaluation Report: CWM; PO*WW*ER™
     Evaporation-Catalytic Oxidation Technology" consists of two volumes:
 "Volume I" (Order No. PB94-156239AS; Cost $27.00, subject to change)
 "Volume II" (Order No. PB94-156247'AS; Cost $61.00, subject to change)
     both will be available only from:
         National Technical Information Service
         5285 Port Royal Road
         Springfield, VA 22161
         Telephone: 703-487-4650
 A related report, entitled:  "CWM; PO*WW*ER™  Evaporation-Catalytic Oxidation
     Technology; Applications Analysis Report" EPA/540/AR-93/506, is available.
 The EPA Project Manager can be contacted at:
         Risk Reduction Engineering Laboratory
         U.S. Environmental Protection Agency
         Cincinnati, OH 45268
  Inquiries about the PO*WW*ER™ technology should be directed to:
         Annamarie Connolly
         ARI Technologies Inc.
         1501 E. Woodfield Road
         Suite 200 West
         Schaumburg, IL 60173
         Telephone: 708-706-6900
         Fax: 708-706-6996
United States
Environmental Protection Agency
Center for Environmental Research Information
Cincinnati, OH  45268
     BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
Official Business
Penalty for Private Use $300
EPA/540/SR-93/506

-------