PB99-963909
                             EPA541-R99-013
                             1999
EPA Superfund
      Record of Decision:
      Aberdeen Proving Ground
      (Edgewood Area)
      Aberdeen Proving Ground, MD
      6/11/1999

-------

-------
CLUSTER 3, SITE 3, OLD BUSH RIVER ROAD DUMP
BUSH RIVER STUDY AREA, EDGEWOOD AREA
ABERDEEN PROVING GROUND, MARYLAND
RECORD OF DECISION
FINAL
                           DISTRIBUTION RESTRICTION STATEMENT
                           APPROVED FOR PUBLIC RELEASE:
                           DISTRIBUTION IS UNLIMITED 2753-A-3

-------

-------
     CLUSTER 3, SITE 3
OLD BUSH RIVER ROAD DUMP
  BUSH RIVER STUDY AREA
     EDGEWOOD AREA
ABERDEEN PROVING GROUND

   RECORD OF DECISION
         FINAL

-------

-------
                               CONTENTS

 1.0    DECLARATION	                     L
       l.l   SITE NAME AND LOCATION	"""!!!.'":!!!".'.'	 	 1
       1.2   STATEMENT OF BASIS AND PURPOSE	 . 	 1
       1.3   ASSESSMENT OF SITE		 !
       1.4   DESCRIPTION OF THE SELECTED REMEDY 	   	 1
       1.5   STATUTORY DETERMINATIONS	 2

 2.0    DECISION SUMMARY	         3
       2.1   SITE NAME, LOCATION, AND DESCRIPTION	3
       2.2   SITE HISTORY AND ENFORCEMENT ACTIVITIES 	        	 6
            2.2.1   SITEHISTORY 	   	'5
            2.2.2   ENFORCEMENT 	.!/".'....	   6
       2.3   HIGHLIGHTS OF COMMUNITY PARTICIPATION	7
       2.4   SCOPE AND ROLE OF THE OLD BUSH RIVER ROAD DUMP ...       	7
       2.5   SITE CHARACTERISTICS 	      g
            2.5.1   SUMMARY OF SITE SURFACE WATER CHARACTERISTICS .........."... 8
            2.5.2   SUMMARY OF SITE SEDIMENT CHARACTERISTICS  	  8
            2.5.3   SUMMARY OF SITE SOIL CHARACTERISTICS	9
            2.5.4   SUMMARY OF GROUNDWATER CHARACTERISTICS ..             9
       2.6   SUMMARY OF SITE RISKS	              9
            2.6.1   HUMAN HEALTH RISK 	     	9
            2.6.2   ECOLOGICAL RISK	'.!'.l!""!"!'.!"""lO
       2.7   REMEDIATION OBJECTIVES AND DESCRIPTION OF ALTERNATIVES  '""".10
       2.8   SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES            12
            2.8.1   THRESHOLD CRITERIA 	"".'.." 12
            2.8.2   PRIMARY BALANCING CRITERIA	          14
            2.8.3   MODIFYING CRITERIA 	    	 15
       2.9   THE SELECTED REMEDY: SOIL CAP	15
            2.9.1   DOCUMENTATION OF  SIGNIFICANT CHANGES	16
            2.9.2   PERFORMANCE STANDARDS	                 16
            2.9.3   COMPLIANCE WITH ARARs	 17

3.0    RESPONSIVENESS SUMMARY	                                 21
      3.1    OVERVIEW 	...""".."."""^"^"Z.  21
      3.2    BACKGROUND ON COMMUNITY INVOLVEMENT 	'.....'...'............. 	21
      3.3    SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC
            COMMENT PERIOD AND APG'S RESPONSES  	        22
      3.4    SAMPLE NEWSPAPER NOTICE ANNOUNCING THE PUBLIC
            COMMENT PERIOD AND THE PUB LIC MEETING 	41

MARYLAND DEPARTMENT OF THE ENVIRONMENT APPROVAL	  42

-------
                                FIGURES

FIGURE 1.0  IRP EDGEWOOD AREA LOCATION MAP	  4
FIGURE 2.0  BUSH RIVER STUDY AREA - CLUSTER 3  	..5


                                TABLES

TABLE 1.    COMPARISON OF REMEDIAL ACTION ALTERNATIVES	 13
TABLE 2    DESCRIPTION OF ARARs FOR SELECTED REMEDY	 18,19,20
                                111

-------
                                    ACRONYMS
 APG          Aberdeen Proving Ground
 ARARs        Applicable or Relevant and Appropriate Requirements
 BRSA         Bush River Study Area
 STAG         Biological Technical Assessment Group
 COPCs        contaminants of potential concern
 CERCLA      Comprehensive Environmental Response, Compensation, and Liability Act
 DDTr         total of pesticides DDT, ODD, and DDE
 DSERT        Defense Sites Environmental Restoration Tracking System
 FAWQC       Federal Acute Water Quality Criteria
 FFA           Federal Facility Agreement
 FS            Feasibility Study
 HEAST        Health Effects Assessment Summary Tables
 HI            hazard index
 HQ            hazard quotient
 IRIS           Integrated Risk Information System
 IRP          installation Restoration Program
 LUCAP        Land Use Control Assurance Plan
 MCLs         Maximum Contaminant Levels
 MDE          State of Maryland Department of the Environment
 NCP           National Oil and Hazardous Substances Pollution Contingency Plan
 NPL           National Priorities List
 OU            operable unit
 PAHs          polynuclear aromatic hydrocarbons
 RAB           Restoration Advisory Board
 RBAs          risk-based activities
 RBCs          risk-based concentrations
 RCRA         Resource Conservation and Recovery Act
 RFA           RCRA Facility Agreement
 RFI            RCRA Facility Investigation
 RfD            reference dose
 RI             remedial investigation
 RME           reasonable maximum exposure
 ROD           record of decision
TRY           Toxicity Reference Value
 UCL           upper confidence limit
 USEPA         United States Environmental Protection Agency
                                          IV

-------

-------
                                   1. THE DECLARATION


 1.1 SITE NAME AND LOCATION

 Cluster 3, Site 3
 Old Bush River Road Dump
 Bush River Study Area
 Aberdeen Proving Ground
 Harford County, Maryland

 1.2 STATEMENT OF BASIS AND PURPOSE

 This Record of Decision (ROD) document presents the remedial action selected to reduce the risks posed
 by the Old Bush River Road Dump located at the Bush River Study Area at Aberdeen Proving Ground
 (APG). The remedial action is intended to comply with the National Environmental Policy Act of 1969.
 The selection of the remedial action was conducted in accordance with the Comprehensive Environmental
 Response, Compensation, and Liability Act  (CERCLA)  of 1980  as  amended  by  the  Superfund
 Amendments and Reauthorization  Action  (SARA) of 1986. and the National  Oil and  Hazardous
 Substances Pollution Contingency Plan (NCP).  This decision is based on the Administrative Record for
 the site.

 The Maryland Department of the Environment (MDE) concurs with the selected remedy at this site.

 1.3 ASSESSMENT OF SITE

 Actual or threatened  releases of hazardous substances from this site, if not addressed by implementing
 the remedial action selected in this ROD, may present an imminent and substantial endangerment to
 public health, welfare, or the environment.

 1.4 DESCRIPTION OF THE SELECTED REMEDY

 The Cluster 3 cleanup is part of a comprehensive environmental investigation and cleanup currently being
 performed at  APG under the CERCLA program. APG is divided into 13 study areas that encompass
 potential sources of  contamination.  The Old Bush River  Road Dump of Cluster 3  is part of the Bush
 River Study Area. The remaining clusters of the Bush River Study Area and other study areas are being
 addressed as separate actions.

This action addresses the principal threats at the Old Bush River Road Dump by constructing a soil cap.
The soil cap reduces migration of contaminants by reducing infiltration and stabilizing the Old Bush
 River Road Dump (OBRRD) to prevent erosion of surface soil, and attenuates the detonation of a 4.2-in.
chemical mortar.   The selected  remedy  for  the  OBRRD will  include  long-term  monitoring and
institutional controls  which will include:

 •   The cap will be inspected for erosion, subsidence, vegetation density, and any other problems that
    may impede performance of the soil cap. Sediments downgradient to the OBRRD will be sampled.
Final January 1999

-------
     Because the remedy does not allow for unrestricted future use ot" the site, a review will be conducted
     within 5 years after commencement of remedial actions to ensure adequate long-term protection of
     human health and the environment is maintained.

     Institutional controls will be implemented in the area. A 6-foot fence with warning signs will be
     maintained around the OBBRD to restrict access.  In addition, the restrictions will be included in
     APG's Geographical Information System (GIS), which is used in documenting APG's Real ProDertv
     Master Plan.
  1.5 STATUTORY DETERMINATIONS

 The selected remedy is protective of human health and the environment, complies with federal and state
 requirements that are legally applicable or relevant and appropriate to the remedial action, and are cost-
 effective.  The remedy uses permanent solutions and alternative treatment technologies to the maximum
 extent practicable.  The capping of the OBRRD reduces the mobility of contaminants by placing them in
 controlled, monitored locations. However, it does not meet the statutory preference for treatment that
 reduces the volume or toxicity of contaminants. With respect to landfill wastes, the potential presence of
 unexploded ordnance (UXO) supports containment rather than a removal remedy.  Because the remedy
 does not allow for unrestricted future use of the site, a  review will  be  conducted within 5  years after
 commencement of remedial actions to ensure adequate  long-term protection of human health and  the
 environment is maintained.
 EDWARD L. ANDREWS                                   Date
 Major General, U.S. Army
 Commander, U.S. Army Aberdeen Proving Ground
Abraham Ferdas                                    0ate
Director
Hazardous Site Control Division
U.S. Environmental Protection Agency, Region III
Final January 1999

-------
                                   2. DECISION SUMMARY
  2.1 SITE NAME, LOCATION, AND DESCRIPTION
                                                                                  southMstmi
  Joppa, Magnoha, Ferryman, and Aberdeen.  The Bush River divides APG into twTma n ar?J The
  Edgewood Area of APG lies to the west of the river and the Aberdeen Area lies lo the east

  response
                                                                 NPL is EPA'S list
                                       Considered Prioritie* for long-term  remedial evaluation and
                                      DefenSC Sites  Environmental  Restoration  Tracking  System
                                   is djvidedk 1MO lhree areas: Nonhera Bush River-           us

                                                                                    in   lhe
t de.  The
are
                                along ,he ditches and into Laudorick Creek
                                                 which drain into an
^"n"Cd fqUlfef(™J??7^' AThe s"rflclf ^"'fer thins and appears intermittently in this area and does
                          A confining layer composed of silts and clays separates the Canal Creek
                          units above it. The confining layer is continuous beneath the OBRRD.

-------

                                                          *
                                                         Mlchaelsvflle
                                                        Landfill NPL Site
                                                    Other Aberdeen
                                                       Areas
                                                               Chesapeake
                                                                 Bay
                                                                  Chesapeake
                                                                    Bay
                                                                   N
Installation Restoration Program Edgewood Area Location Map
                                 Figure 1
                                    4

-------
           CLUSTERS


SITE 23: TRANSFORMER
STORAGE YARD

-------
 2.2 SITE HISTORY AND ENFORCEMENT ACTIVITIES

 2.2.1 Site History

 The Bush River Study Area (BRSA) covers approximately 500 acres on a peninsula located in  the
 northeast portion of the Edgewood Area and is bounded on the north by Lauderick Creek, on the east and
 south by Bush River, and on the southwest by  Kings Creek. As early as 1918, portions of the BRSA were
 used for training, test activities, chemical storage, and waste disposal.  The southern part of the peninsula
 was designated as "A-Field"  and  was used  for artillery firing, training, testing, and for  smoke and
 incendiary munitions testing.  It is not known if there was a munition  impact area in the BRSA. During
 World Wars I and n, the area was a main storage and transshipment depot for chemical-filled munitions.
 The large dock on the southeastern boundary  received foreign chemical munitions that were captured in
 Europe and shipped to the  Edgewood Area for testing and disposal.  Dredging materials from the dock
 channel were deposited onto a southern parcel of the peninsula (US AEHA 1989).

 The OBRRD predates World  War II and may have existed before 1917,  when the Edgewood Area
 became government property.  A U.S. Geological Survey topography  map from 1915 indicates a former
 home site was located near the present location. There is no historic documentation on what was disposed
 of at the site. Aerial photographs  indicate the OBRRD was active in 1929 and continued to be active
 through the  early  1940s (USAEHA  1989).   Inspections reveal that wastes were  pushed  out toward
 Lauderick Creek over time, not all wastes were covered, and burning occurred at the site.  The site is
 currently inactive; according to aerial photographic evaluations, disposal  activities last occurred during
 the mid 1940s.

 2.2.2    Enforcement

 From 1984 to 1985, APG was evaluated as a potential National Priorities List (NPL) site under CERCLA
 (USEPA 1985).  In 1985, the Edgewood Area of APG was proposed for inclusion on the NPL; it  was
 listed on the NPL in 1990. In 1986, between the time of the proposed  listing and the final listing, a
 Resource Conservation and Recovery Act (RCRA) corrective action permit (MD3-21-002-1355)  was
 issued by the USEPA Region HI to address solid waste management units (SWMUs) in the Edgewood
 and Aberdeen Area of APG.  As part of the RCRA permit. U.S.  Army Environmental Hygiene Agency
 (USAEHA) performed a RCRA Facility Assessment (RFA) study for  the Edgewood Area. In addition to
 the RFA, the RCRA permit required that a RCRA Facility Investigation (RFI) be performed. However,
because of the final listing of the  Edgewood Area on the  NPL  in 1990, the RFI was not  completed.
Further investigations were to be performed under CERCLA.

After the Edgewood Area was  placed on the NPL, a Remedial Investigation (RI) was initiated at Cluster
 3.  The Remedial Investigation recommended a Feasibility Study be conducted to evaluate  potential
 remedial alternatives for the Old Bush River Road Dump (Site 3).

The following documents provide details of the site investigations and  cleanup actions at Cluster 3:

 •   USAEHA, 1989. RCRA Facility Assessment  Report,  Edgewood Area. Aberdeen Proving Ground.
    Maryland, Report No. 39-26-0490-90.

-------
  •   APG,  1996.  Bush River Study Area Wetlands Delineation  Report, Aberdeen Proving  Ground
      Maryland, September 1996.
  •   APG,  1998. Remedial Investigation Report. Bush River Study Area, Cluster 3, Aberdeen Proving
      Ground, Maryland, July 1998.
  •   APG,  1997. Focused  Feasibility Study  Data Report. Cluster 3. Site 3. Bush River Study Area
      Aberdeen Proving Ground, Maryland, April 1997.
  •   APG, 1997. Focused Feasibility Study Data Report Addendum for Cluster 3, Site 3, Bush River Study
      Area, Aberdeen Proving Ground, Maryland, October  1997.
  •   APG,  1998. Feasibility Study,  Cluster 3,  Old Bush River Road Dump, Bush River Study Area
     Aberdeen Proving Ground, Maryland, July 1998.
  •   APG, 1998. Proposed Plan for Cluster 3, Site 3, Old Bush River Road Dump, Bush River Study Area
     Aberdeen Proving Ground, Maryland, July 1998.


  2.3  HIGHLIGHTS OF COMMUNITY PARTICIPATION

  APG currently has a  Restoration Advisory Board (RAB) that consists of representatives from local
  government agencies,  businesses, and the community groups playing an active role in the Installation
  Restoration Program (IRP) process.  One active group represented on the RAB is the Aberdeen Proving
  Ground Superfund  Citizens Coalition. The RAB meets monthly to discuss and concur on a variety of
  topics regarding the environmental  program at APG.  The  RAB has  the opportunity  to  review and
 comment on all documents addressing the IRP sites.  APG offered opportunities for  public input and
 community participation during the RI, Feasibility Study (FS) and Proposed Plan for Cluster 3  Site 3
 Old  Bush River Road Dump.  The Proposed Plan was  made available  in the Administrative Record'
 which was housed in public facilities off the APG installation. The notice of availability of the Proposed
 Plan was published in The Aegis (Harford County local paper), the Kent County News (Kent County local
 papers), The Avenue and The Essex Times (Baltimore County local paper), and the Cecil  Whig (Cecil
 County local paper) on July 29, 1998, and in the APG News (installation newspaper) on July 30  1998  A
 public comment period was  held from July 31 through September 14,  1998. APG held a public meeting
 on August 18, 1998, at 6:30 p.m. at  the Edgewood Senior Center. Edgewood, Maryland, to discuss the
 i"SF J™**"?*8 that °CCUrTed at  the °ld Bush  River Road  DumP-  Representatives from  the
 UMiPA, MDE, and APG were  present to answer questions about APG, OBRRD, and the recommended
 alternative.

 A summary of questions and  responses  from the  public meeting is included in the Responsiveness

                                                    activlties  fulfin  the requirements  of Section
2.4 SCOPE AND ROLE OF THE OLD BUSH RIVER ROAD DUMP OPERABLE UNIT
                               remedy f°r SUrface soiL surface water- Md sediment, at the OBRRD
             represents  one component of a comprehensive environmental investigation and cleanup
being performed under the IRP at APG. Protectiveness of this action will be evaluated during the five-
year review process. Long-term monitoring data will be available for those reviews.

-------
 The purpose of the remedial action is to prevent future environmental impacts as a result of the migration
 of contaminants to areas where humans and environmental receptors may be exposed.

 A study of groundwater in the BRSA  is ongoing.  Groundwater contamination is not addressed in this
 ROD.   Subsequent  actions  will  evaluate the  risks  and  need  for  action based on  groundwater
 contamination.
 2.5 SITE CHARACTERISTICS

 The Cluster 3 RI report investigated 2 sites: the OBRRD (Site 3) and the Transformer Storage Area (Site
 23).  The RI concluded that there would be no further action for the surficial aquifer, since it meets the
 requirements of Type in aquifer under the Code of Maryland Regulations, and cannot be considered a
 potential potable water supply.  Also, there would be no further action at the Transformer Storage Area, a
 removal action was completed in 1991. However, it did recommend a Feasibility Study for the Old Bush
 River Road Dump.

 The OBRRD is approximately 1.56 acres.  The site contains many areas where surface debris  is either
 uncovered or partially covered.  There is no documentation on the types of wastes placed into the Old
 Bush River Road Dump.  However, there is potential for hazardous materials. Lead contaminated soil;
 discarded laboratory supplies and glassware; recovered UXO; chemical plant process equipment; burned
 remnants of gas mask canisters; concrete pieces and bricks; metal objects, rods, wire, and pipes; as well as
 other demolition and household waste have been found at the site. The types of UXO which were used
 during this era and may have been disposed of in the dump  include 75 mm shells, Livens projectors, and
 4.2 inch mortar rounds.

 The Army completed a removal action involving the placement of a fence around the OBRRD in May of
 1996.

 2.5.1 Summary of Site Surface Water Characteristics

 Fourteen surface water samples (seven locations in two rounds) were collected during the field
 investigations.  Only two samples had exceedences above the Fresh Acute Water Quality Criteria
 (FAWQC). The FAWQC was used to evaluate the groundwater's potential impact on surface water.  The
 two samples had exceedences of lead (94.3 and 115 ug/L) just above the FAWQC of 82 ug/L.

 2.5.2  Summary of Site Sediment Characteristics

 Sediment samples were compared to USEPA Biological Technical Assessment Group (BTAG) screening
 criteria for sediment, which are based on ecological risk values. Sediment samples showed elevated levels
 of lead (484 mg/kg), nickel (125 mg/kg), and zinc (669 mg/kg) relative to BTAG criteria. Six sample had
 concentrations of beryllium (up to 5.8 mg/kg) which  where above the human health  screening criteria
 (0.150 mg/kg) [EPA Region HI Risk Based Concentrations residential (RBCs)].  The elevated levels of
 metal in the sediment  are the same metals  that are present on top of the landfill and the northeastern
pushout area.   Therefore, it  appears the sediment contamination  has come from past  or  continuing
slumping and erosion of the surface of the OBRRD.

-------
  2.53 Summary of Site Soil Characteristics

  Two out of seven soil  samples had concentrations (4,700 and 3.120 mg/kg) above the EPA ecological
  screening level for lead (400 mg/kg). These samples were taken from the bum areas on the landfill.  The
  surface soils on the OBRRD contain elevated levels of metals compared to samples adjacent to the Dump.
  Metals such as copper (13,600 mg/kg), nickel (42mg/kg). zinc (669 mg/kg), mercury, and arsenic (49.2
  mg/kg) have been found at elevated levels on the landfill. However, these levels of contamination are
  below industrial risk based screening criteria.

  The  burn areas are sparsely vegetated, and the soil in these areas is discolored.   Elevated levels of  lead
  (484 mg/kg) were found in a soil sample near a burn area.  Lead was also found in soil samples taken
  from the burn areas (4,700 and 3,120 mg/kg).  It also appears that erosion and soil slumping in this  area
  have transported contaminated soil and sediment from the landfill into the streams and wetlands.

 2.5.4  SUMMARY OF GROUNDWATER CHARACTERISTICS

 Five  deep geotechnical borings drilled in BRSA indicate there are three distinguishable aquifers separated
 by confining units. The three  aquifers are the surficial aquifer, the Canal Creek Aquifer, and the lower
 confined aquifer (APG 1997).  Wells and borings drilled in Cluster 3 show that a water-bearing fill zone
 exists within the northeast portion of the OBRRD and  along the two perennial streams bordering the
 Dump.  The surficial aquifer thins and appears intermittently in this area. The Canal Creek Aquifer is
 under confined conditions.  In the vicinity of the Dump, the aquifer dips to the east. It is encountered at
 elevations  around  -2 to -13 ft mean sea level (MSL).  It varies in thickness from 5 to 20 ft  The Canal
 Creek Aquifer outcrops and is recharged west of the Dump.  Groundwater flow in the Canal Creek
 Aquifer is to the northeast. A confining layer composed of silts  and clays separates the Canal Creek
 Aquifer and the water-bearing  units above.  The confining layer is continuous beneath the Dump.  The
 confining layer varies in thickness from 2 to 30 ft.  Any contamination migrating downward is contained
 in the fill zone and cannot enter the underlying aquifers.  Groundwater contamination in the Bush River
 Area  is  being addressed in a separate Operable Unit and is not addressed in this ROD.

 2.6 SUMMARY OF SITE RISKS

 APG  conducted a human  health and  ecological  risk assessment as part  of  the RI to  estimate the
 probability and magnitude  of  potential adverse  human health effect and  environmental effects from
 contaminants at the site.

 2.6.1  Human Health Risk

 The human health risk assessment evaluated each contaminant detected in the groundwater, surface water,
 soil, and sediment samples collected during the RI and  the Feasibility Study (FS).  The contaminant
 concentrations were compared  to the EPA RBCs and background  concentrations.  Contaminants above
 screening criteria were evaluated in the risk assessment.

The human health risk assessment evaluated eight contaminants of concern The contaminant of concern
identified in groundwater samples was cadmium. The contaminants of concern identified in soil samples

-------
 were benzo(a)pyrene (a semivolatile organic  compound). 4.4'-DDT, arsenic, copper, iron, beryllium,
 antimony, lead, p-chlorophenylmethyl sulfone. and 2-hexone.RBC. Beryllium, iron, 4,4'-DDT, arsenic,
 copper, iron, benzo(a)pyrene, beryllium, chlordane, 2-methylnaphthiene,  phenanthrene, lead, magnesium,
 and  antimony were identified as contaminants of concern in the sediment.  Arsenic was identified in
 surface water. See the FS for more information on contaminants of concern (Section 1.3.3.2, page 1-16).

 Health risk  levels, determined using EPA guidance  to ensure that conservative  estimates of potential
 health effects are determined, differ depending on the assumed land use  because human exposures differ
 with land use. A conservative estimate of risk was developed incorporating the  potential exposure
 pathways and includes ingestion and dermal absorption of the affected media.

 The  human health risk assessment concluded the conservative estimate of potential carcinogenic  risk of
 each chemical detected at Cluster 3 was below I x 10"6 . which falls within EPA's acceptable risk range.
 In addition,  the hazard indices for  each exposure pathway at  the OBRRD were  less than one.  The
 OBRRD property is  in an  industrial area, however  there is  military residential housing north  of the
 OBRRD. A review of historical information and recent UXO surveys indicates that detonation of a 4.2-in.
 chemical mortar located at the existing ground surface is the worst case scenario for risk to human  health.
 The  risk assessment considered the proximity of the residential  property to  the landfill.  The selected
 remedial actions will be protective of the residents.


 2.6.2 Ecological Risk

 An ecological risk assessment was  performed to assess potential adverse effects  from Cluster  3 to
 ecological .receptors.   Absolute  conclusions cannot be made regarding the potential for chemicals at
 Cluster 3 to adversely affect ecological  resources because of the many uncertainties surrounding the
 estimates of toxicity  and exposure.   However, several general conclusions  were made regarding the
 potential for adverse effects to ecological resources.

 The results of the sediment analysis indicate  the greatest potential for adverse  effects to the benthic
 organisms are likely posed by the creek sediments in the freshwater marsh.  The results of the surface
 water analysis indicate a limited potential for adverse effects to aquatic life from the surface water of the
 creek in the freshwater marsh.

 The analytes  noted to  exceed ecological criteria include ODD, lead, and nickel, which were characterized
 as having the  greatest potential for adverse effects  to benthic  organisms in the RI Ecological  Risk
 Assessment.

2.7 REMEDIATION OBJECTIVES AND DESCRIPTION OF ALTERNATIVES

Remedial action objectives (RAOs) developed for the OBRRD are to:

«   prevent direct contact with the Dump's soil and waste,
•   reduce infiltration into the Dump and possible migration of contamination,
•   prevent erosion of surface soil from the Dump to surface water and sediment,
"   contain any potential risk of detonation of unexploded ordnance by providing a physical barrier to the
    release of either chemicals or fragmentation, and
                                                10

-------
  •   reduce/ eliminate risk to ecological receptors.

  The EPA's Presumptive  Remedy  for CERCLA  Municipal/Military Landfills was used in developing
  remedial action alternatives.  The presumptive remedy process involves streamlining the FS to analyze
  only containment options  and no-action alternative.  Several remedial action alternatives were developed
  from the general response  action of containment.  The following remedial action alternatives  were
  developed:

  ALTERNATIVE 1:  No Action

  Annual O&M Cost   $17,162
  Present Worth       $328,323

 CERCLA, as amended, and the National Contingency Plan require that the  "no action" alternative be
 evaluated at every site to establish a baseline for comparison.  Remedial action is not included as part of
 the "no action" scenario; however, long-term monitoring will be included to  determine if contaminants
 migrate from the landfill.

 ALTERNATIVE 2:  Composite Cap

 Capital Cost        $1,257,628
 Annual O&M Cost   $23,222
 Present Worth       $1,701,884

 The purpose of the composite cap is to prevent  infiltration by  layering  geosynthetic material to  drain
 water off the OBRRJD, prevent infiltration through  the composite layers, vent gases produced from the
 OBRRD, and contain  any potential risk of detonation of a buried 4.2 inch chemical mortar.  This type of
 cap is commonly used for municipal and hazardous waste landfills. A combination of a low-permeability
 geosynthetic clay layer and a flexible geomembrane would be installed as a  highly effective means of
 reducing the potential for infiltration of water into the  OBRRD, thereby reducing the possibility of
 contaminant migration.

 ALTERNATIVE 3: Soil Cap

 Capital Cost        $881,856
 Annual O&M Cost   $21,782
 Present Worth       $1,298,564

 The purpose of the soil cap is to reduce infiltration, stabilize the OBRRD to  prevent erosion of surface
 soil, and contain any potential risk of detonation of a buried 4.2 inch chemical mortar.  A vegetative cover
 is established to minimize erosion, enhance  evapotranspiration, and minimize infiltration.  Establishing
 and maintaining a good vegetative cover is important in the performance of this alternative.

ALTERNATIVE 4:  Vegetative Barrier Cap

Capital Cost        $819,236
Annual O&M Cost  $ 19,652 to $54,963 (varies by year)
                                               11

-------
 Present Worth       $1,308,699

 The vegetative barrier cap, in conjunction with a soil cap, is an innovative technology used for landfill
 closure.  This technology uses selected trees or grasses to further reduce infiltration into the OBRRD
 through transpiration. Although trees and certain grasses can increase the surface roughness of a landfill
 and thus increase infiltration, the  transpiration  rates should compensate for the added amount of
 infiltration entering the surface of the OBRRD.  This technology uses alternative vegetation such as
 poplar trees and grasses to prevent precipitation from percolating beyond the root zone. This alternative
 will also contain any potential risk of detonation of a 4.2 inch, chemical mortar round.

 2.8  SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

 The remedial alternatives presented in  Section 2.7 were  evaluated in accordance with  the regulatory
 requirements of CERCLA using the nine criteria specified  by USEPA as set forth in the NCP. The nine
 criteria are categorized into three groups: threshold criteria, primary balancing criteria, and modifying
 criteria.  The alternative that is ultimately implemented must satisfy the threshold criteria, which are the
 most important. Primary balancing criteria weight the major trade-offs among alternatives.  Modifying
criteria are considered after conclusion of the public comment period.  This section summarizes the
relative importance of each remedial alternative with respect to these criteria.   Table I presents  a
comparison of remedial action alternatives for the OBRRD.

2.8.1  Threshold Criteria

•   Overall Protection of Human Health  and the Environment.  All of the alternatives except
    Alternative  1 (No Action) provide long-term protection of human health and the  environment.
    Alternative  4, Vegetative Barrier Cap,  is  an innovative technology used specifically to prevent
    infiltration of precipitation into  the  Dump's material  using vegetation, specifically poplar trees.
    Although this is not a proven technology, the vegetative barrier is a variation  of Alternative 3, Soil
    Cap.  Existing information on poplar trees suggests that this technology would be effective long term
    and provide protection to human health and the environment.  The vegetative barrier cap has the
    fewest short-term impacts during construction. The composite cap and soil cap require consolidation
    of waste in the northeast portion of the landfill,  whereas the vegetative barrier cap does not. The
    possibility of UXO presents  problems in conducting  intrusive work in and around the Dump and
    creates short-term risks to workers.  The composite cap  also requires grubbing of trees and woody
    vegetation to prepare the surface of the landfill.  This also creates more short-term risks to workers.
    The soil cap and vegetative cap do not require grubbing. Existing wetlands will be destroyed with all
    three alternatives.  However, wetlands will be reestablished to offset long-term  impacts.  All the
    alternatives  except Alternative 1 (No Action) meet all ARARs.  Alternatives 2, 3,  and 4 meet RAOs
    for the Dump. These three alternatives (1) prevent exposure to the Dump, (2) reduce infiltration and
    subsequent contaminant migration, (3) prevent erosion of surface soil and risk to ecological receptors,
    and (4) contain any potential risk of detonation of a UXO and prevent chemical or fragmentation
    release.  Alternative 1, No Action, does not meet any of  the RAOs  and  does not meet chemical-
    specific ARARs.
                                               12

-------

Remedial
alternatives
Alternative 1, No
Action
Alternative 2,
Composite Cap
Alternative 3,
Soil Cap
Alternative -4,
Vegetative-
Barrier C.'ap
	 _ 	 .„»«. *. WU...U.UIMJII 01 remedial action alternatives for the Old Rush, RjYPr RnaH Hiimn
Evaluation criteria
Overall protectiun of
human health and the
environment
Does not provide adequate
protection; AKAKs are not
met; RAOs are not met
High level of protection;
possibility of more ihort-
(erm impacts than other
alternatives;
meeis AKAKs and RAOs
Protective of human health
and the environment,
short-term impacts fioiii
excuvulion; meets ARARs
and KAOs
Innovative technology;
pci loi mancc data aic not
available, use ol vegetation
to decieuse inlilli.ilioii:
lewcbt shoii-leim impacts;
il cllcclivc. will inccl
ARARs and RAOs

Compliance with
ARARs
Will not meet
Will meet
Will meet
Will iikvi

Long-term effectiveness
and permanence
Risks are not reduced
High degree of reliable
long-term protection to
human health and
environment; commitment
to O&M is required
Reliable long-term
protection to human health
and environment;
commitment to O&M is
required
l'imide» long-term
piotcclioii ID human hcalih
and environment; high
degiec ol O&M is required.
••— 	
Reduction of loxicity,
mobility, and volume
No reduction of loxicity,
mobility, or volume
Reduces contaminant
mobility but not foxicily
or volume
Reduces contaminant
mobility but not lox icily
or volume
Reduce^ contaminant
mobility but nut loxicity
or volume
Short-term effectiveness
No impacts to workers or
community; no reduction of
risk in short-term
Greatest shon-lenn impacts
because it requires the most
excavation; effective as soon
as constructed
Some slmit-lerm impacts
from excavation; effective as
soon as grassy vegetation is
established
Fewest shun term impact-,
iHxatise least amount ol
excavation, lake.*, luiigci to
establish vegetation and
effectiveness
Implementability
Easily implemented,
installation of
monitoring wells
Most difficult to
implement because of
the use of geosynthetics;
however il is a well-
developed technique;
materials and equipment
readily available
Least difficult to
implement; materials
and equipment readily
available
t:a.->> ID implement,
however, more dilliculi
to maintain, luiwevci.
materials may not Ik;
leadily available, high
degieeol O&M.
Cost
Long-term Monitoring
0&M:JJ328,323
NPW:^328,323
Capital: $1,257,628
O&M: $444,256
NPW:$ 1,701, 884
Capital: $881,856
O&M: $4 16,707
NPW:$ 1,298,564
Capital. MIY.-'.id
O.VM 14XV.-K.1
NPW..$l.1l)8.MW
13

-------
 •   Compliance with Applicable or Relevant and Appropriate Requirements .  Alternatives 2, 3, and
     4 comply with all identified ARARs. Alternative 1  does not comply with all ARARs. Alternative  1
     does not comply with chemical-specific ARARs or RCRA Hazardous Waste Landfill requirements,
     which set forth criteria for cover systems for solid waste landfills.

 2.8.2  Primary Balancing Criteria

 "   Long-term Effectiveness  and Permanence. Alternatives  2  and 3  provide  reliable,  long-term
     protection  of human health and the environment.  None of the  alternatives  provides  permanence
     because the waste at the Dump is not treated.  As discussed earlier. Alternative 4, Vegetative Barrier
     Cap, is an innovative technology used to prevent infiltration into the Dump's material using poplar
     trees and grassy vegetation. Information on poplar trees suggests they would be effective long term.

    Alternative 1, No Action, is not effective long term and is not permanent.  Commitment to O&M is
    essential in the long-term effectiveness of these alternatives.  Alternative 4, Vegetative Barrier Cap
    will require the most maintenance of all three alternatives.

"   Reduction of Toxicity, Mobility, and Volume.    Alternatives 2, 3,  and 4 reduce contaminant
    mobility by reducing surface water infiltration and limiting the transport of contaminants via surface
    water runoff. According to the HELP Model, the composite cap prevents infiltration better than the
    soil cap.  However, both are comparable in preventing erosion of surface soils.  No reduction in
    toxicity or volume of landfill contaminants is achieved with any of the alternatives because the waste
    at the Dump is left in place.  Again, the vegetative  barrier cap  is an innovative  technology, and
    performance data are not available on reduction of infiltration rates. However, the technology using
    poplar trees suggests that infiltration will be greatly decreased and mobility would then be reduced
    during the growing season. Alternative I, No Action, does not reduce toxicity, mobility, or volume.

"    Short-term Effectiveness.   The vegetative barrier  cap  has the fewest short-term impacts  during
    construction.   The planning stages  of all three alternatives include minimizing  excavation.  The
    possibility of UXO presents problems in conducting  intrusive work in  and around the Dump and
    creates  short-term risks to workers. The composite cap, soil cap, and vegetative  barrier cap require
    consolidation of waste, which will require excavation in  the northeast portion of the  landfill.   All
    three alternatives require  rerouting of  the streams,  which involves  minimal  excavation.   The
    composite cap also requires grubbing of trees and woody vegetation to prepare  the surface of the
    landfill.  This also creates more short-term risks to workers.  The soil cap and vegetative cap  do not
    require  grubbing.  The vegetative  barrier cap  may take longer to  become effective than the other
    alternatives.  As the poplar trees grow, they absorb more water; therefore, this alternative may not be
    as effective as the composite cap and soil cap within the first  year.  The composite  cap and soil cap
    are very similar with respect to short-term effectiveness. Alternative 1 is not effective short term and
    has no short-term impacts to site workers.

1   Implementability.  Alternative 1, No Action, is the easiest to implement. Of the other alternatives,
   Alternative 3, Soil Cap, is easier to implement.  Conventional construction equipment and techniques
   are used, and materials are  readily available.  The vegetative cap  is easy to construct.   However,
   because this technology  is patent pending, materials may  be  available from  only one  service
   contractor.  However, most of the work will require conventional construction equipment.  The
   Vegetative Barrier Cap will also require the greatest amount of maintenance. The composite cap is
                                               14

-------
      more difficult to implement than the other alternatives because of the use of geosynthetic materials.
      However, composite caps using geosynthetics have been used at many hazardous waste sites and the
      technique  is well developed.  Extreme  weather conditions can  delay  implementation of  all the
      alternatives, particularly Alternative 2, Composite Cap.

  •   Cost.  Following are the costs of the alternatives from least expensive to most expensive:

     Alternative 1,No Action               $328,223
     Alternative 3, Soil Cap              $ [ ,298,564
     Alternative 4,Vegetative Barrier Cap  $1,308.699
     Alternative 2, Composite Cap         $ 1,701,884

  2.83  Modifying Criteria

  •   State/Agency Acceptance. Maryland Department of the Environment does not accept Alternative I.
     Alternative 3 is acceptable because this alternative prevents direct contact with the OBRRD soil and
     waste, reduces infiltration into the OBRRD and possible migration of contamination, prevents erosion
     of surface soil, contains the detonation of buried UXO. and reduces risk to ecological receptors.

 -   Community Acceptance. The community has accepted Alternative 3 during the public comment
     period.

 2.9 THE SELECTED REMEDY: SOIL CAP

 The soil  cap, is the selected remedy for remediation  of the Old Bush River Road Dump.  The soil cap
 reduces migration of contaminants by reducing infiltration, stabilizing the OBRRD to prevent erosion of
 surface soil, and contain the risk of detonation of a 4.2-in.  chemical mortar. A review of historical
 information and recent UXO surveys indicates that detonation of a 4.2-in. chemical mortar located at the
 existing ground surface is the worst case scenario for risk to human health.  The Conventional Weapons
 Effects Model shows that a burial depth  of 3 ft is sufficient to contain the blast produced by  a  42-in
 chemical  mortar. The soil cap will consist of two  layers.  The first layer will  be a minimum  3  ft
 foundation layer.  The second layer will be a minimum  6  inch layer of topsoil to support vegetation
 Therefore, the soil cap will be a minimum of 3 feet 6 inches. The HELP model, which is used by EPA to
 understand infiltration through landfill caps, shows that a soil cap with good vegetative cover will reduce
 infiltration of precipitation into the landfill by 76%.

 Institutional controls will be  implemented in the area.  A 6-foot fence with  warning signs will be
 maintained around the OBBRD to restrict access.   In addition,  land use, access,  and excavation
 restrictions will be included in APG's GIS, and in APG's Real Property Master Plan. All use restrictions
 will be incorporated in  any real  property and/ or  real  estate documents  necessary  for transferring
ownership from the Army, in the unlikely event that the Army transfers the property.  The real  property
and/ or real estate documents would also include a discussion of the NPL status of the site, as well  as a
description of the contaminants at the site. Quarterly inspections will be performed and the Army  will
certify to EPA on an annual basis that the institutional controls are functioning.  A site-wide LUCAP is
being developed for APG, and will  incorporate Cluster 3.
                                                15

-------
 This alternative meets the Remedial Action Objectives of (1) preventing direct contact with the OBRRD
 soil and waste, (2) reducing infiltration  into  the OBRRD and  possible migration of contamination, (3)
 preventing erosion of surface soil, (4) contain the risk of detonation of buried UXO, and (5) reducing risk
 to ecological receptors.  A comprehensive monitoring plan for the site will be developed through a
 cooperative effort between the U. S. Army APG. USEPA. and MDE, after this ROD is finalized. The
 plan will approved by the USEPA and be available in the administrative record, as required by CERCLA.

 2.9.1 DOCUMENTATION OF SIGNIFICANT CHANGES

 There have been no significant changes since the Proposed Plan  was presented.

 2.9.2    PERFORMANCE STANDARDS

 "   The soil cap will consist of two layers. The first layer above the OBRRD surface will be a minimum
    3-ft foundation  soil layer designed to contain a blast of buried UXO and prevent an acute release of
    chemical gases. As with the composite  cap, a  review of historical information and recent  UXO
    surveys indicates that a detonation of a single 4.2-in. chemical mortar located at the existing ground
    surface  is  the  worst case scenario  for  risk to human health, since  chemical munitions do not
    sympathetically detonate. The Conventional Weapons Effects Model shows that a burial depth of 3 ft
    is sufficient to  contain the blast produced by a 4.2-in. chemical mortar. The soil cap, which will
    consist of two layers, will be a minimum of 3 feet 6 inches.

 •   The second (top) layer will be a minimum '/2-ft-thick layer of topsoil. The cap will be thicker in some
    areas to bring the surface of the cap to a level grade with a 4% slope to facilitate drainage.  A
    vegetative cover will be established to minimize erosion, enhance evapotranspiration, and minimize
    infiltration.  Surface and subsurface wastes outside the limits of the OBRRD cap will be consolidated
    and placed under the cap limits

 »   Both adjacent streams  will be filled because of their proximity to the OBRRD.  The streams will be
    relocated around the slope of the OBRRD; the northern stream will be  moved to the north and the
    eastern stream to the east. Both  streams support emergent wetland vegetation that will be destroyed
    during construction.  State regulations and policy on  destruction of nontidal wetlands dictate that
    emergent wetlands must be reestablished on a minimum 1:1 basis. The area  of the wetlands that will
    be disturbed and reestablished onsite is approximately 0.35 acres.

•   Long-term  monitoring  will be  performed  for  a minimum of  30  years to  ensure the  long-term
    performance of  the soil cap.  The cap will be inspected for erosion, subsidence, vegetation density,
    and any other problems that may impede performance of the soil cap. Sediments downgradient to the
    OBRRD will be sampled quarterly for the first year, and annually thereafter.

•   Because the remedy does not allow for unrestricted future use of the site, a review will be conducted
    within 5 years after commencement of remedial actions to ensure adequate long-term protection  of
    human health and the environment is maintained. At that time the need for additional 5 year reviews
    will be evaluated.

•   Institutional  controls will be implemented in the area. A  6-foot fence  with warning signs will  be
    maintained  around the OBBRD to  restrict access.   In  addition,  land  use, access,  excavation
                                                16

-------
    restrictions will be included in APG's GIS. and in APG's Real Property Master Plan.  In addition, the
    Director of APG's Directorate of Safety, Health,  and the Environment will certify to EPA on  an
    annual basis that  there have been no violations of the prohibitions.  If a violation has occurred, a
    description of the violation and corrective actions to be taken will be provided.

2.9.3 COMPLIANCE WITH APPLICABLE OR RELEVANT APPROPRIATE
     REQUIREMENTS

The selected remedy meets or exceeds all ARARs. The specific ARARs are listed in Table 2: Description
of ARARs for Selected Remedy.
                                             17

-------
                              Table 2 Description of ARARs for Selected Remedy
    Media
 Require
   ment
    Synopsis of
    Requirement
                                                      Action to be Taken to Attain Requirement
                                                              Status
 Ground
 Water
 Chemical
 And
 Action
 Federal Clean
 Water Act
 40 CFR Part 131
 Water Quality
 Standards
The objectives of the Clean Water Act is to restore and
maintain the chemical, physical, and biological integrity
Of the nation's waters. This objective is achieved through
The control of discharges of pollutants to navigable waters.
This control is implemented through the application of federal,
state, and local discharge standards. CERCLA § 121 states
that hazardous substances, pollutants, or contaminants left on-
site at the conclusion of the remedial action shall attain federal
water quality criteria. Water quality criteria are based on the
potential use of the stream. Therefore, FAWC are applicable
for cleanup standards for the streams near the Dump.
Applicable
 Ground
 Water
 Chemical
 Maryland Water
 Quality
 COMAR
 26.08.02.01-08
Maryland water quality regulations designate uses of the
waters of the state and establish water quality standards to
protect the designated uses. This regulation is applicable and
will be met by constructing a soil cap on the Dump minimizing
the potential for leachate to degrade surface water.
 Hazardous
 Waste
Location
Maryland Natural
Resources Code
annotated
Sections 8.1801 to
8.1816
Because Site 3 is within the I.OOO-ft buffer of the Chesapeake
Bay known as the Critical Area, activities are subject to natural
resource protection standards and restrictions, which require
the implementation of storm water runoff control devices and
other impact reviews and controls.  Storm water and sediment
controls will be implemented to meet the requirements of this
regulation.
                                                                                           Applicable
-J
 Applicable
Ground
Water
Action
Changes in Stream
Channels or
Floodplains
COMAR 26.04.07
                                Permits are not required for CERCLA actions. However, the
                                substantive requirements of the regulation must be followed;
                                therefore, this regulation is applicable.
                                                           Applicable
Ground
Water
Action
Maryland
Standards for
Groundwater
Monitoring and
Protection
 DMAR
26.13.05.06
                                Applies to owners and operators of permitted hazardous waste
                                facilities, including  landfills, for groundwater monitoring and
                                protection. This regulation addresses general groundwater
                                monitoring requirements, concentration limits, and compliance
                                points.  The Dump is not a permitted facility; however, the
                                monitoring requirements are relevant and appropriate to the
                                situation at the site.  A groundwater monitoring system will be
                                implemented to determine if migration is occurring from the
                                landfill.
                                                           Relevant
                                                           And
                                                           Appropriate
                                                        18

-------

Media
Ground
Water and
Soil
Ground
Water and
Soil
Ground
Water and
Soil
Hazardous
Waste
Soil
Air
Ground
Water and
Soil

Require
ment
Action
Action
Action
Action
Action
Action
Action
Table 2 Description of ARARs for Selected Remedy cont.
Synopsis of
Requirement
U.S. Army Corps of
Engineers(33OSC
1341 Certification]
33 CFR Part 323
Nontidal Wetlands
COMAR 26.23.01-
.05
Clean Water Act
Section 404
National Wide
Permits
Munitions Rule 40
CFR 264.300
Maryland Erosion
and Sediment
Control COMAR
26.09.01
Maryland Air
Quality Regulations
COMAR 26. 11.01-
26.11.02.21
Maryland
Regulations for
Well Drillers
COMAR 26.05
Action to be Taken to Attain Requirement
Although a permit is not required because this is a CERCLA
site, the substantive requirement must be followed. Capping
procedures must follow requirements for wetland protection
or implement engineering controls to minimize or prevent
adverse impacts.
Although a permit is not required because this is a CERCLA
site, the substantive requirement must be followed. State
policy on the destruction of wetlands requires that emergent
wetlands must be mitigated on a 1:1 basis.
Permits are not required for CERCLA actions. However, the
substantive requirements of the regulation must be followed.
After a munition is determined to be a solid waste, the
regulations establish if it is also a hazardous waste. White
phosphorous was found in a munition in the Dump. White
phosphorous is considered a RCRA hazardous waste because
it is highly reactive.
Requires a erosion and sediment control plan to be in place
for any federal project unless the project involves less than
100 cubic yards of grading of 5.000 square feet of grading.
An erosion and sediment and control plan will be
implemented.
Dust Suppression techniques will be used to minimize the
airborne transport of contaminated dust in compliance with
this regulation.
Applicable to the abandonment of monitoring wells within
the limits of the cap.
Status
Applicable
Applicable
Applicable
Applicable
Applicable
Applicable
Applicable
19

-------
                          Table 2 Description of ARARs for Selected Remedy cont.
   Media
 Require
   ment
     Synopsis of
    Requirement
       Action to be Taken to Attain Requirement
   Status
 Ground
 Water
Action
Groundwater Quality
Regulations COMAR
26.08.02.09
The Dump is not a permitted disposal unit; potential
discharges are being mitigated, and approval from the state
will not be needed or required. However, the purpose of the
regulation is to protect groundwater and surface waters of
the state: therefore, putting a soil cap on the Dump prevents
migration of contaminants to surface water and complies
with the substantive requirements of the regulation.
Relevant and
Appropriate
Hazardous
Waste
Action
AR 200-2
Environmental
Effects of Army
Actions
Provides guidance on incorporating into the CERCLA
process (FSs).  It implements the Council on Environmental
Quality's NEPA regulations. As a matter of policy, the
organization preparing the FS ensures the document
complies with 40 CFR 1500-1508.
Applicable
Hazardous
Waste
Action
CEQNEPA
Regulations
40 CFR 1500-1508
This regulation will be complied with by implementing AR
200-2.
Relevant and
Appropriate  J


—•
Applicable
Hazardous
Waste
Location
Fish and Wildlife
Coordination Act (50
CFR Part 402
Interagency
Cooperation-
Endangered Species
Act of 1973, as
amended)
No Bald Eagle nests are currently within 500 meters of
Cluster 3; applicable if there are possible impacts to
threatened or endangered species.
Hazardous
Waste
Location
Federal Conservation
of Wildlife Resources
50 CFR Part 402
(Endangered Species
Act)
No endangered species are believed to be within 500 meters
of Cluster 3. Applicable if there are possible impacts to
threatened or endangered species.
 Applicable
Hazardous
Waste
Location
Maryland Threatened
and Endangered
Species Regulations
COMAR 08.03.08
The Bald Eagle is believed to forage in and around the study
area.  However, no nest sites are currently within 500 meters
of Cluster 3. Construction activities are not anticipated to
impact the bald eagle: applicable if there are possible
impacts to threatened or endangered species.
 Applicable
                                                       20

-------
                              3.0   RESPONSIVENESS SUMMARY
  The final component of the Record of Decision is the Responsiveness Summary.  The purpose of the
                *
  During the public comment period, written comments were received by APG.

  APG held a public meeting on August 18, 1998, to formally present the Proposed Plan and to answer

  STSS Alr/ndVpAT1115- The;ranfript °f ^ meetmg * part °f the ^ministnuive record S The
  s te. The Army and EPA have conSldered all comments and concerns summarized below in selectine the
  cleanup method for the Old Bush River Road Dump Site.                                selecting the

     This responsiveness summary is divided into the following sections:

     3.1 Overview.
     3.2 Background on community involvement.
     3.3 Summary of comments received during the public comment period and APG's responses
     3.4 Sample newspaper notice announcing the public comment period and the public meeting!

 3.1  OVERVIEW
              ™                        ,                   preferred altemative for ** ™ Bush
 River Road Dump Site. APG proposed a soil cap and long-term monitoring. EPA concurred that the soil
 cap would provide adequate protection for this site.  EPA also indicated they would need to work wUh the
                                            generally SUpP°rted the *™S* P^-S aZative £
                                                 C°mmentS- MDE has con'urred w«h the selected
      dA                                          C°ncems have been exPressed «*«« the type of
3.2 BACKGROUND ON COMMUNITY INVOLVEMENT


                      Focused Feasibili^ Smdy being scaned for ,he OU Bush
                                             21

-------
            The Board further discussed the site at the December 1996 and August 1997 meetings.  In
            August 1998, APG repeated the Proposed Plan briefing given at the public meeting on August
            18 at the Board meeting.

        •   APG released the Proposed Plan for the Old Bush River Road Dump Site for public comment
            on July 31, 1998. Copies were available to the public at APG's information repositories at the
            Aberdeen and  Edgewood  Branches of  Harford  County Library, and Miller  Library at
            Washington College.  A copy of the Proposed Plan also was  posted on  the  Installation
            Restoration Program's Web Site, and the public was invited to comment through the Web Site.

        •   APG prepared a release for the APG News announcing the availability of the Proposed Plan,
            the dates of the public comment period, and the date and time of the public meeting.

        •   A 45-day public comment period on the Proposed Plan ran from July 31 to September 14, 1998.

        •   APG placed newspaper  advertisements announcing the  public comment period  and public
            meeting in The Aegis, the Cecil Whig, The Avenue, the Essex Times, and the Kent County
            News.

        •   APG prepared and published a fact sheet on the Proposed Plan.  APG mailed copies of this fact
            sheet to over 2,650 citizens and elected officials on its Installation Restoration Program mailing
            list. The fact sheet included a form which citizens could use to send APG their comments.

        •   On August 18, 1998, APG held a public meeting at the Edgewood Senior Center,  Edgewood,
            Maryland. Representatives of the Army, EPA. and the MDE presented information on the site
            and their respective positions on the proposed cleanup alternatives.


33 SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
AND AGENCY  RESPONSES

Comments raised during the Old Bush River Road Dump Site public comment period on the Feasibility
Study and the Proposed Plan are summarized below. The comments are categorized by source.

COMMENTS FROM QUESTIONNAIRE INCLUDED WITH FACT SHEET

As part of its fact sheet on the Proposed Plan, APG included a questionnaire that residents could return with
their comments. APG received 10 completed returns.  The alternatives preferred by individuals returning
comment forms were:

        0   Alternative No. 1 - Take No Action.
        1   Alternative No. 2 - Composite Cap.
        6   Alternative No. 3 - Soil Cap (see comments I and 2 below).
        I   Alternative No. 4 - Vegetative Barrier Cap (see comment 3 below).
        2   Have no preference.
                                               22

-------
     Written comments included on the form are summarized below.

 Comment No. 1:  "An excellent, thorough report."

 Response No. 1: APG acknowledges and appreciates the feedback.

 Comment No. 2: "If No. 3 does not comply with landfill regulations, then take alternative No. I."

 Response No. 2: The selected alternative complies with all State ARARs. See comments from Maryland
 Department of the Environment at the end of this Responsiveness Summary.

 Comment No. 3:  "If I understood correctly. No. 3 would require removal of trees and woody vegetation,
 same as No. 2. I therefore chose #4."

 Response No. 3: All of the alternatives would require the removal of some vegetation. Alternative 4, the
 vegetative barrier cap, would be used in conjunction with a soil barrier cap and thus vegetation would need
 to be removed. The purpose of the vegetative barrier cap would be to further reduce infiltration into the site
 through transpiration.  However, this is  a new technology and  may take longer to become effective as
 compared to the other technologies. Therefore, APG and EPA selected Alternative No. 3.

 COMMENTS FROM RESTORATION ADVISORY BOARD MEMBERS

 As part of its efforts to involve the public in decisions as early as possible, APG provided Restoration
 Advisory  Board members  with a draft of the Proposed  Plan and a final version of the  Proposed Plan.
 Preferred alternatives and comments from Board members are summarized below.

        0   Alternative No. 1 - Take No. Action.
        1   Alternative No. 2 - Composite Cap.
        4   Alternative No. 3 - Soil Cap.
        0   Alternative No. 4 - Vegetative Barrier Cap.
        1   Alternative No. 3/Altemative No. 4 (see comment no. 5 below)

 Comment No. 4:  "My only concern is that when work begins on the cap, dust and any  other sources of
 potential transmission of existing surface  contaminants be kept to a level which is safe. Safe because the
 work will occur in close proximity to family housing."

Response No. 4: APG agrees with this comment and will take appropriate dust control and sediment and
erosion control measures during the construction.

Comment  No. 5: "Report does not state why Alternative 3 (soil cap) was chosen. According to the report,
the vegetative cap has many advantages with the only disadvantage being limit of contractor and amount of
maintenance. You might want to explain APG and MDE's reason  for choice."

Response  No.  5: The vegetative cap is also lacking in performance data for both short-term and long-term
implementation.  For this reason, APG and EPA selected the soil  cap. The soil cap is easier to implement
and maintain, will be protective of human health and the envi ronment. and is cost effective.
                                               23

-------
  Comment No. 6: "This alternative [alternative no. 3] seems to be the most cost-effective option."

  Response No. 6:  APG agrees that Alternative 3 is  a cost-effective option.  While protection of human
  health and the environment is the most important criteria, the effective use of taxpayers'  resources is a
  criteria APG is required to consider.

  Comment No. 7:  "Since the true components of the landfill  cannot be determined, there  is at least one
  exceedence, and the groundwater (water-bearing zone is  hydraulically connected to  the  headwaters of
  Lauderick Creek, I recommend the composite cap to ensure future leaching into the groundwater does not
  occur. The added cost of $400,000 for the low-permeable cap  is money well spent if it keeps metals from
  entering the Bay.  As the report admits, dealing with unknowns of the landfill,  the plan should take a more
  conservative approach."

  Response No. 7: APG agrees protection of the Bay and  other surface water bodies  is important.  Our
  environmental sampling downgradient of the site found little evidence of contamination, except from the
  erosion of the existing landfill surface soil. The proposed soil cap will prevent  further erosion and mitigate
  the possibility of movement of metals in the Bay. In addition. APG will implement a long-term monitoring
 program that includes sampling and bioassays to ensure the soil  cover is functioning properly and continues
 to be protective.

 COMMENTS AT THE AUGUST 18.1998 PUBLIC MEETING

 A full transcript of the public  meeting  is at APG's information repositories.   Following is  a summary of
 verbal comments made at the meeting. (Several comments made by a consultant to APGSCC at the public
 meeting are addressed in the section which includes all  of APGSCC's comments.)

 Comment No. 8:  A representative from Harford County Division of Environmental Affairs asked why a
 single membrane cap or similar design  was not considered.  He also asked about the potential for lateral
 movement of substances from buried munitions along the  interface between the soil cap  and the underlying
 clay layer.

 Response No. 8:  In response to the first comment, the State of Maryland regulations require  a double-layer
 cap for hazardous waste landfills.  The State of Maryland has determined that the requirement for a double
 layer cap  does not apply to the  Dump.  Several capping configurations were evaluated in the FS. The
 selected alternative meets or exceeds the requirements identified  by the State.

 In response to the second comment, APG did evaluate the potential for munitions to be in  the landfill and to
detonate. APG believes it is possible for munitions to be present but very unlikely that they would detonate.
APG believes Alternative 3 will provide adequate protection of human health and the environment even in
the unlikely event a munition would detonate.

OTHER WRITTEN PUBLIC COMMENTS

The following written comments were submitted from a resident:

Comment No. 9 :  "It appears that Alternative 3 is the most cost-effect, proactive remedial measure. I am
not clear, however, as to the material to  be used for the 3-foot foundation.  Would this be an impermeable
                                                24

-------
  material? Would this material be calcium based or enriched due to the migration of metals observed at the
  site leaching into ground water?

  Response No. 9 :  The exact specifications of the cover will be contained in the remedial design which is
  the next step in the  process.  Once the design is complete. APG will send the community a fact sheet
  showing the exact specifications of the cover. It is anticipated the three-foot foundation will be a common
  borrow soil, and would not be impermeable.  It is not expected that the material would be calcium enriched.
  A second layer of topsoil, with a minimum of !/2  foot thickness, will be placed on top  of the foundation
  layer. This layer will include a vegetative cover which will  reduce infiltration of precipitation into the
  landfill by  76%.

  Comment No. 10: The commenter noted Alternative 1 was not acceptable. He stated Alternatives 2 and 3
 are the most reliable remedial approaches, with Alternative 2 being the most conservative and costing over
 $400,000 more to implement.  He asked:  "How  many monitoring events  would be required with each
 alternative to determine effectiveness and  obtain closure?  Will  the State  issue a waiver to COMAR
 26.13.14  to avoid a possible NOV? Should the State stand firm with COMAR, it would be worth spending
 the extra $400,000. Although I believe that if the cost estimations are accurate and the general effectiveness
 of Alternative 3 is sufficient that the State will essentially be forcing the installation to  waste federal tax
 dollars based on formalities and technicalities."

 Response No.  10:  See comments from the  Maryland Department of the Environment  at the end  of this
 Responsiveness Summary.

 Comment No. 11: "I do not understand why the Risk Assessment was overly conservative  and included
 ingestion  as an exposure pathway. If this aquifer  of concern was determined not to be viable, then why
 would any other scenario outside of the "construction worker scenario" be applicable?  Was ingestion
 included due to the proximity of the Bush River? Is there evidence that the aquifer provides base flow to the
 river (a good assumption).  At that point, would you be considering the source of ingestion to be through
 fish and game that would use the  river as a drinking water source? Or are there municipal water intakes
 located downstream? Thank you for this opportunity to comment."

 Response No.  11:  APG  follows EPA guidance  in preparing Risk Assessments; this  guidance is very
conservative to be  protective of the public and the ecology. Under the guidance, APG looked at potential
exposure pathways including ingestion by humans.  The ecological risk assessment examined the potential
for impact to fish and other aquatic life. The ecological risk assessment found only a limited potential for
any adverse effects. APG's surface water sampling also showed only one minimally elevated detection of
dissolved lead above the Federal Ambient Water Quality Criteria.

COMMENTS FROM APG SUPERFUND CITIZENS COALITION f APGSCO

 APGSCC is the recipient of Technical Assistance Grants from the U.S. Environmental Protection Agency.
 These grants allow APGSCC to hire consultants to help them review and comment on technical documents.
 Following are comments prepared by APGSCC and their consultant, the University of Maryland.
                                                25

-------
  Comment No. 12:  "Presenting only no action and capping alternatives for this 1.56-acre site reduces the
  community's ability to evaluate a reasonable spectrum of possible solutions and to concur or disagree
  with the selected approach. As raised by APGSCC's technical consultant  at the Restoration Advisory
  Board meeting, an appropriate diversity of alternatives should be included in the proposed plan. While
  the selection of these alternatives was based on EPA's presumptive remedy for municipal and military
  landfills, it should be noted that the Citizen's Guide to Understanding Presumptive Remedies supports the
  community's right to request the evaluation of other alternatives."


  Response No. 12:  EPA's objective for presumptive remedies is to use past experience at similar sites to
  streamline investigations and speed up selection of cleanup actions. The use of presumptive remedies can
  ensure consistency in remedy selection and reduce the cost and time required to clean up similar types of
  sites.  EPA expects presumptive remedies to be used at all appropriate sites except where site-specific
  circumstances suggest  that either the  presumptive remedy would not be appropriate,  or that another
  remedial alternative would be clearly superior when evaluated using CERCLA remedy evaluation criteria.
  As discussed in the feasibility study, EPA established source containment as the presumptive remedy for
  CERCLA municipal landfill sites in  1993,  and in 1996 issued guidance on  the  application  of this
  presumptive remedy to military  landfills.   The guidance presents a decision framework to  use in
 determining if use of the presumptive remedy is appropriate.  This decision  framework is presented and
 employed in the feasibility study, and clearly indicates that the presumptive  remedy, containment, is the
 most appropriate remedial response.

 Published  policy  and procedures by EPA on presumptive remedies states: "The  identification  of a
 presumptive remedy does not relieve the EPA or the Army of the obligation to respond to comments
 suggesting that  other alternatives  should have  been considered." The guidance further states:  "... the
 submission of comments advocating other approaches does not necessarily require broadening of the FS
 or EE/CA,  or conducting  additional analysis after the plan  has been proposed.   Whether additional
 documentation is  required  will depend upon how substantial  or persuasive the comments  are  (e.g.,
 whether a comment identifies unusual site circumstances that seriously call into question the applicability
 of the presumptive remedy)."  APGSCC has not identified any such site circumstances that would make
 the presumptive remedy inappropriate, and other alternatives do not warrant more detailed study.

 Comment No. 13: "The ERP's determination that excavation is not feasible due to costs and  explosive
 risks, as delineated at the RAB, are not conclusions that should be drawn before public comment and full
 discussion of the pros and cons via the RAB and the proposed plan. The presence of munition wastes has
 been  raised as reasoning for why excavation is  not a possibility.  However,  as APG has vigorously
 pointed out at other sites, no chemical warfare materiel (CWM) has actually been found at Cluster 3, and
 one should not automatically assume that it is  present just because an empty CWM round was retrieved.
 Additionally, contamination has migrated from the site, as elevated contaminants have been found in
 Lauderick Creek.  The information does not appear to definitively indicate that capping the site will
 improve the quality of Lauderick Creek.  This site contains a push out area resulting from the clearance of
 past burning and dumping activities, by  which wastes are pushed out into the marsh to allow additional
 disposal activity. At a minimum, monitoring  will need to take place in the marsh and creek to evaluate
 the effectiveness of the proposed alternative.   Ecological impacts in Lauderick Creek from current
 contamination levels should also be  adequately evaluated.  Without comprehensive exploration  of
unknown site characteristics, APG runs the risk of exposing unsuspecting individuals to unnecessary
risks,  and although this is  not  always avoidable, the seriousness of inadequate source evaluation and
environmental fate must be given considerable weight in selecting a course of action."
                                                26

-------
   Response No. 13:  EPA guidance requires issues related to m.litary-speciflc wastes be considered in the
   feasibility study, and that an evaluation be performed to determine if excavation of the waste is practical
   This analysis is a fundamental element in determining the applicability of the presumptive remedy at the
   OBRRD and was accomplished during  the feasibility study.  During the public  comment period the
   public is encouraged to review the feasibility study. Also, members of  the public may form their own
   opinions, suggest  other alternatives, and provide feedback to the Army and EPA   The use of the
   presumptive remedy approach was  presented at  the August  1997 RAB meeting  thus informing RAB
   members early in the process of the planned approach.

  For the OBRRD, both an empty Livens projectile (the empty CWM round) and an explosively configured
  white phosphorus  munition {4.2 inch) have been found at the  site.  While no rounds containing lethal
  chemical warfare materiel (i.e., mustard, phosgene, Lewisite, etc.) have been found,  given the time period
  of sue usage, the existence  of such items at the site is possible. Munitions filled with CWM have been
  recovered in the Bush River Area.   It also should be noted that the presence of ordnance containing
  explosives and white phosphorus are also a significant hazard,  would make site excavation a hazardous
  operation.

  Surface soil within the OBRRD contains lead and other constituents of concern. Without remedial action
  erosion processes would result in continued release of these constituents to Lauderick Creek  The soil
  cover will prevent transport of constituents of concern to Lauderick Creek and also  will achieve all other
  remedml action objectives.   The effectiveness of this remedy in protecting human health and the
  environment is clearly stated in both the feasibility  study and the proposed  plan.

  Monitoring of nearby Lauderick  Creek sediments is planned.  The  work will include chemistry and
  thereafter     quartedy samPlin8 evfints from before and after construction, with annual monitoring


 Comment No. 14:   "The TAG Group strongly suggests that all future proposed plans be expanded to
 present more diverse alternatives to be considered.  Excavation and partial excavation scenarios should be
 fully evaluated within the feasibility study and outlined within the proposed plan. Simply stated the
 community cannot participate if only  limited options are  included in the document  that is  most likely to
 be read by the public."                                                                        J

 Response No. 14: Consistent with EPA guidance and policy, APG will continue to consider presumptive
 remedies where appropriate.  The consideration of presumptive remedies can both accelerate remedial
 programs as well as reduce costs, thus benefiting the public. Use of presumptive remedies does not limit
 community participation, and expansion of the feasibility study  process to perform detailed analysis of
 remedial alternates that are  not practical does not expand public participation and is not an effective use
 or taxpayer resources.

 APG  intends to consider the  use of presumptive remedies for the 22nd and 30th Street landfills in the
 Southern Bush River Study Area, as well as other similar sites.  The decision to limit feasibility study
 work  to consideration of only no action and the presumptive remedy, or to have an  expanded feasibility
study  with consideration  of  a wider  range  of alternatives, will be made during  the feasibility study
woT* hr°Ce,SS ™* P«fcil»Mon by APG, EPA Region III, MDE and the public.  The feasibility study
work at these landfill sites has been initiated and scoping will occur during calendar year 1999
                                                27

-------
 Comment No. 15:  "APGSCC has long supported the characterization of contamination from a holistic
 perspective." "As for the risk assessment, the contamination and resulting risks at a particular site should
 be evaluated in  conjunction with  other risks from nearby contamination.   Assessing  the Cluster 3
 contamination as it relates to adjacent sites should be done."

 Response No. 15:  APG agrees that that it is important to consider data from nearby study areas  when
 evaluating contaminant transport and when assessing risk.  Both a regional and local perspective  must be
 maintained  when developing an understanding of groundwater  movement.   A substantial amount of
 investigation has been  accomplished in the Cluster 13 area, and data collection to support the Cluster 13
 feasibility study work is ongoing. The groundwater plume from Cluster 13 does extend southward across
 the local  branch of Lauderick Creek, but is still roughly 2000 feet from and has no potential  to impact
 groundwater quality in the Cluster  3 and the OBRRD area.  There is no use of groundwater from the
 Cluster 3, Cluster 13, or onpost housing areas, and because there is no exposure pathway, there is no risk
 to current APG workers or  residents  from Cluster 13 groundwater.  Alternatives for remediation of
 groundwater in the Cluster 13 area are  being analyzed as part of ongoing feasibility study work for that
 operable unit, and that work  has no relationship  to  the OBRRD  remedial decision process.  Data from
 both  efforts  is being considered when developing an understanding of groundwater occurrence and
 movement in the general  vicinity of Lauderick Creek.

 APG agrees, when assessing risk to ecological receptors within a drainage  basin, it is  appropriate to
 consider all of the contaminated areas within the basin, and that there are potentially additive impacts of
 separate sources  and contaminated  areas.   APG  has been conducting ecological risk assessment work
 addressing large  geographical areas, with  the studies  of the Gunpowder and Bush Rivers and their
 tributary creeks being examples.  As monitoring and assessment  work in Lauderick Creek proceeds, all
 data will be evaluated when assessing risk.

 Data from adjacent contaminated sites has no bearing on the conclusions of the RI/FS that soil within the
 OBRRD contains constituents at levels  that create risk to potential ecological receptors, that constituents
 have  migrated to nearby Lauderick Creek sediments via  erosion  and sediment transport,  and that
 remediation of the OBRRD as a source is necessary. Data from studies in adjacent sites is not necessary
 for remedial  alternative selection for the OBRRD.

 Comment No. 16:   "The Transformer  Storage Area within Cluster 3  is the other area of concern within
 Cluster 3  that was evaluated within  the remedial investigation.  The authors of the report  concluded that
no further action was necessary at this site. Yet, within  the proposed plan, it is stated that this  site is
recommended for further evaluation.  Chapter 6 of the remedial  investigation mentions determined
concentrations of metals  and  DDT (and degradation products) present within the cluster, and evaluated
potential  impacts to terrestrial  plants, soil-dwelling  invertebrates,  small carnivorous  mammals and
carnivorous birds. The risk assessment supported the possibility of impacts as a result of the metals and
pesticides measured, including arsenic, cadmium, mercury, nickel,  lead and selenium.  APG should
clarify whether additional evaluation  will  be considered.   Based on  the risk assessment,  additional
investigation, including bioassays, seem appropriate. Sampling areas of clear concern  include soil sample
locations SS-04 and SS-05, where some of the highest metal  concentrations were detected. SS-04 exists
within the heart of Transformer Storage Area (Site 23) and SS-05 appears to be outside the landfill area to
be capped. Please clarify if these areas of soil contamination were addressed during  any  removal  action
to date. If they are not, what efforts will be made to ensure that continued run-off and wind  dispersion
                                                28

-------
   does not add to the already elevated concentrations of some of these metals in the sediments of Lauderick
   Creek.  Considering that this area may remain a source area, will there be any assessment of the soil
   between these two sampling locations to determine the extent of these particularly high areas? APGSCC
   requests that the community be updated  on the further evaluation that is to take place according to the
   proposed plan  as the  TAG Group cannot support no  further action as recommended in the  if media!
  investigation
  Response No. 16: Supplemental surface soil sampling is planned for the Site 23 area, within which the
  former transformer storage area was located.  The objective of the supplemental surface soil sampling and
  analysis is to determine the extent of lead in surface soil at locations SS-04 and SS-05 in support of a
  planned removal action to address soil containing lead at greater than 200 mg/kg. Samples at SS-04 and
  SS-05 w,ll also be analyzed for PCBs.  Data from this supplemental soil sampling and Analysis, together
  with data from the planned sediment monitoring and bioassay and that data already available will provide
  Site ?f and ^SSS^n0^11 C0"taminat!on  and contaminated sediment  transport in the vicinity  of
  under evaluation                     additional work to address other  constituents in soil is currently
         T"     ^"u118  T   e" accomPlished at Site 23-' The exact extent of the soil cover for the
           anet
       andi,     HH                    ' bUt k JS antic'Pated that le*d ™ surface soil at both
       and SS-04 will be addressed by a removal action to be accomplished after the planned sampling
                     ne the lXtent °f lead"  APGSCC the Resto^,on Advisory Board, and the public
                                            f°r the °BRRD s°" c-er -d ^ - -*•£-

 Comment No. 17:  "With regard to Site 23, it should be mentioned that a removal action was  conducted
 lkl7rn°rreTVf * C°nCrete ^ ^ * "* 8ite °f f°fmer Buildin* E1372> « underground storage
 ank and contents of a sump assoc.ated with this building. From the remedial investigation it appears that
 conCCp°fT    f In  S3mpl£g C°nfirmed that contaminated Aerials  had been removed SSwTto a
 concentrauon of 50 ppm.  The remedial investigation indicates that the 50 ppm  clean up  level is a
 regulatory / guideline for determining sites with contamination that would require management  as TCB
 waste and/or hazardous waste.  However, this the clean up conducted through this removal action does
 not appear necessanly to be protective of human  health or the environment  The industrial  ristbued
                                               ^ «* — - -"a is 100 pp,
Response No. 17:  The objective of the removal action was to remove contaminated structural materials
and  terns requmng management as PCB and/or hazardous waste (concentrations exceeding 50 ppm)
        s o1thCeTmWaS» n? implemented to remove a11  -'  ^at might have been contaminated^ The
        s ot the removal action were accomplished.
 rasess                ?*!'** ^ ™K "* ^ '" ^uantitative risk assessment calculations
«mnr  T  g *f J      ,      Cr remediatlon at the ^moval action site.  The supplemental soil
sampling discussed above will include analysis of selected samples for PCBs.
                                              29

-------
  Comment No.  18:   "Significant issues  remain  to  be  addressed regarding the RAD risk  assessment
  conducted at Cluster 3.  While RESRAD was used as a screening method, the support documents contain
  almost no information regarding the parameters used in the modeling. One section of the RI indicates that
  this model may  have only been used to assess soil contamination. Attachment B to the risk assessment
  portion of the RI Report notes that the ingestion of drinking water was not considered in the RESRAD
  model, which brings  into question the validity of the future scenario risk assessment. Were inhalation and
  ingestion considered  in the RESRAD modeling?"

  Response No. 18:   During the  last  several years, the  approach  to human  health  risk assessment  for
  radionuclides has evolved.  The  current approach at APG is consistent with the approach employed at
  most other facilities, including Department of Energy  facilities.

 The approach involves calculating risk using two methodologies.  The first methodology is to  simply
 calculate carcinogenic risk using cancer  slope factors  in a manner  identical to that  for carcinogenic
 chemicals, with  the risk result then being compared to  the EPA target range of 10"6 to 10"4 for excess
 lifetime cancer risk.  The second methodology involves the calculation of radiation dose which  is then
 compared  to  a health-based criteria, with 1-5 millrem/yr (mrem) currently proposed by EPA.  The  15
 mrem/yr effective dose equivalent is approximately equal to a cancer risk of 3 x 10"4. The identification
 of radiological constituents  of potential concern for inclusion in the quantitative  risk assessment is
 accomplished by screening against risk-based activities (RBAs) in a manner identical to screening of
 chemicals  against risk-based  concentrations (RBCs).   The  RBAs are  calculated  using exposure
 assumptions and procedures identical to those used  for calculating RBCs  (with modifications that are
 appropriate for radiation/radionuclides).

 The  approach to risk assessment for radionuclides is conceptually identical to that for chemical risk
 assessment. There are necessarily some differences in details. For example, radiological risk assessments
 must consider the effects of external gamma radiation, as well as exposure routes such as ingestion and
 inhalation.

 The risk assessment for Cluster 3 was originally accomplished  approximately two years ago, using  an
 approach that, at that time, was considered  by regulatory authorities to be acceptable for APG sites.
 When the Cluster 3 RI report was finalized in August of 1998. the original radiological risk assessment
 was  used, but at  the same  time a  reassessment  was accomplished  using  the  currently accepted
 methodology discussed in the above paragraph. RESRAD is simply a computer program that can be used
 as a  tool to  calculate dose estimates  given  radionuclide concentrations in environmental  media and
 exposure assumptions.

The RESRAD model calculations for the reassessment included estimates of risk from ingestion  of
soil/sediment, ingestion of groundwater and external radiation. Soil was the only source term used in the
RESRAD calculations, and groundwater exposure  was based on  RESRAD estimates of transfer between
media rather than actual groundwater data. Inhalation was not included as an exposure route because it is
not significant for the Cluster 3 site.   For Cluster 3, nearly all of the estimated risk  is from external
radiation because Cs-137 and K-40 are strong gamma emitters.  Default input parameters for RESRAD
were  used in the  Cluster 3 risk assessment, and assume a subsistence farming land use scenario. This
scenario  is conservative because it allows for a relatively high  level of exposure to soil and the crops
grown in it.
                                                30

-------
  In discussing radiological risk assessment,  it is also  important to understand that the data used in the
  radiological nsk assessment is from gamma spectrometry analysis.  Gamma spectrometry is a very useful
  screening toot for .dentifying radionuclides that may be  present and the approximate  level of activity
  within a media sample.  However, it must  be recognized that not all gamma spectrometry data are of
  sufficient precision and accuracy for use in a quantitative  risk assessment, and are appropriate only for
  initial screening level site assessment and estimates of risk. Gamma spectrometry data often have a high
  relative level of uncertainty at low concentrations near the detection limits, which is often the situation
  when analyzing environmental samples, and is the case for the Cluster 3 samples.  The  interpretation of
  gamma spectrometry data must include evaluation of the estimated concentration relative to the detection
  Iimit^ the total  propagated uncertainty relative  to  the  estimated concentration, and the potential  for
  interference.                                                                        ^

  The precision and accuracy of gamma spectroscopy data are dependent on a number of factors  including
  the radionuchde of interest. Gamma spectrometry is generally a relatively good method for identifying
  and quantifying  the  concentrations  of strong gamma emitters  in a sample. For example,  gamma
  spectroscopy provides relatively good data for Cs-137.  The detection efficiency for other radionuclides
  relative to Cs-137 can  vary  substantially,  with  a factor of 20 not being unusual.  This variation in
  detection efficiencies is greater than for gross alpha and gross beta analyses, where relative detection
  efficiency factors are more typically in the 3 to 4 range.

  The results of gamma spectrometry analysis are  subject to interference because different radionuclides
  can have emissions at the  same energies. For example, both radium-226 and uranium-235 are naturally
  occurring and have an emission energy of 186 Kev as part  of their characteristic emission spectrum  U-
 235 also has emissions at higher energy levels and in interpretation of the data a computer estimates the
 relative amounts of Ra-226 and U-235, but not always with a high degree of accuracy. The combination
 of this interference and uncertainty in analysis are the reasons  why it is not uncommon for gamma
 spectrometry  to show Ra-226 levels  that are inconsistent  with and much higher  than  the gross alpha
 measurement.  In such an instance the gross alpha should be  used to assess the maximum levels of Ra-226
 that could be present m  the sample. When there  is inconsistency between gross alpha data and Ra-226
 data from gamma  spectrometry analysis, radium  analysis should be accomplished using more suitable
 methodology.
         method °f a"alySiS dePends on both the radionuclide of interest and also the media of concern
 For Ra-226 in water, radon emanation is the methodology that is appropriate for drinking water sample
 analysis, and for generation of data for use in quantitative risk  assessment  where radionuclides are of
 concern.  The measurement of activity by alpha emitters in water is most commonly accomplished by
 alpha spectrometry. Because of the nature of alpha and beta radiation, gamma spectrometry is the most
 commonly employed method for soil analysis.  In recent years the approach to radiochemistry analysis for
 some  study areas  has been to perform gross alpha, gross nonvolatile  beta and gamma spectrometry
 analyses on  all  samples.   The routine use  of gamma spectrometry for all samples  at APG is being
discontinued and gross alpha and gross nonvolatile beta will be  used  as screening tools.   For water
samples, further analyses  will follow the approach used for drinking water sample analysis.  For  soil
samples, further analysis will be accomplished when there is evidence of  radionuclide contamination  at a
site. This is the commonly used approach at CERCLA sites, including at DOE facilities
                                                31

-------
 The Cluster 3 remedial investigation and risk assessment were accomplished using the best available data,
 which for radionuclides is entirely from gamma spectrometry analysis.  The radiological portion of the
 human health risk assessment has been revised using the latest accepted procedures.  This revised risk
 assessment determined that Cluster 3 risks associated with radionuclides are not  substantially different
 from risks associated with local background concentrations.

 When  considering radionuclides in the environment, it must also be remembered that many are naturally
 occurring, and that certain others are man-made and found in environmental media as a result of historical
 nuclear weapons  testing.  For example, potassium-40 (K-40), Ra-226 and thorium-228 (Th-228) are
 naturally  occurring,  and  cesium-137  is  a  man-made  radionuclide that  is  commonly  found  in
 environmental media as a result of fallout from weapons testing during the 1940s and 1950s.

 K-40  is  of relatively  high  abundance (0.0117%) and  long half-life (1.28  billion years).   Because
 potassium is a very abundant element in nature, it is common for a substantial portion of nonvolatile gross
 beta activity in samples to be due to naturally occurring K-40.  K-40 is also a gamma emitter, and the
 greater abundance of potassium in clay minerals than in silica sands is the reason why natural gamma logs
 of boreholes can readily identify zones of high clay that will act as low permeability confining units and
 distinguish them from sandy aquifer zones.  K-40 is also commonly found in solution  in surface water
 and groundwater,  and is often the principal source of nonvolatile gross beta in groundwater samples.
 Unfiltered groundwater samples will often have very high levels of nonvolatile gross beta activity when
 they contain suspended silt and clay particles, because those particles contain potassium.

 Comment  No. 19:  "The proposed plan states that there is  no historical documentation of what was
 disposed  of at the site.  However, the community  was recently informed that  Chemical, Biological
 Defense Command (CBDCOM) has a 4-story vault containing historical records of their activities. These
 records need to be evaluated as soon as possible.   While DSHE  may not be able to  investigate this
 information source prior to the Record of Decision for this cluster, every effort should be made to do  so
 before the remedial work at this site begins."

 Response No. 19:  The 4-story vault referred to is a part of the CBDCOM Technical Library system.  The
 classified card catalog for this library was thoroughly reviewed as an element of the  RCRA Facility
 Assessment for the Edgewood Area of APG. Thousands of documents in this library were reviewed for
 information related to waste management.   Environmental  studies and reports were not prepared during
 the period prior to World War n, and the logbooks and technical reports of the library only make
 occasional reference to methods of waste disposal, and most often do not mention the exact location  of
 disposal activities.  None of the library documents reviewed describe the OBRRD or the nature of wastes
 disposed at that site.  While it cannot be stated  with certainty that there are no  documents within the
 library containing such information, the review work already accomplished suggests that a 100% review
 of library documents would provide little if any information related to the  OBRRD. It is unlikely that
 information from historical documents would  change the conclusions of the remedial investigation and
 feasibility study, and would not change the  conclusion that the presumptive remedy, containment, is the
most reasonable remedial approach.
                                                32

-------
  Comment No. 20: 'The groundwater flow and contamination migration issues appear complicated in the
  Cluster 3 area, and our TAG review of the available information has raised multiple concerns  Included
  m these observations  is  the  potential  that  the  identity  of  the  different  aquifers may have been
  misinterpreted. Furthermore, the presence and migration of certain classes of contaminants need to be
  meticulously  reviewed,  as APG's ability to  assess present and.  more  importantly, future exposure
  pathways depends on the  comprehensive evaluation of known contamination, environmental fate and
  potential sources.  This request to review such issues is supported by  the determination that the non-
  cancer health nsks to a future worker, via groundwater.  exceeds the hazard quotient of  1  which is not
  discussed in the PP. APGSCC  requests that APG and the EPA evaluate these concerns described below
  to ensure that these important  issues  are  being assessed adequately.  A  written assessment  would be
  appreciated, although a follow-up meeting may be necessary if the response does not clearly outline the
  logic and supporting data for the conclusions drawn  in these CERCLA documents."

  Response No. 20:  The issues related to  groundwater occurrence and interpretation of aquifer zones is
  complex at Cluster 3, and  because of this complexity, a substantial  effort was made to coordinate the
  interpretation  and remedial investigation description with geologists from  both EPA Region m and the
  MDEpnor to publication of the remedial investigation report.  It is hoped that the following  responses
  (21 through 27) to specific comments will be  informative  and  helpful.  APG also is willing  to hold a
  follow-up meeting to help clarify issues.

  Comment No. 21:  'The proposed plan indicates that because the groundwater has been classified as a
  type m aquifer, water quality  criteria were  used  in the  evaluation  process instead of maximum
 contaminant levels (MCLs). However, the MCLs were used as the comparison  criteria in chapter 4 of the
 Remedial Investigation  Report.  It has been  an ongoing practice at APG  in recent  years  to  select
 chemicals of concern based on the EPA's risk-based concentrations (RBCs) from Region ffl,  which were
 used in the  baseline risk assessment discussion  in  Chapter 6 of the remedial investigation Report   What
 was the reasoning for the alternating comparisons?"

 Response No.  21:  Different comparisons were made because in  each of the circumstances the objectives
 of  interpretation and discussion were different.  While the groundwater has been classified as a Type m
 aquifer,  it is still useful  and necessary to  discuss nature and extent of contamination in groundwater
 Chapter 4 of the remedial investigation contains comparisons to Maximum Contaminant Levels (MCLs)
 and to RBCs for tap water for constituents without MCLs. because these comparisons are useful tools in
 discussion of nature and extent of contamination.  In Chapter 6 of the remedial investigation the risk
 assessment,  constituents  of potential concern  are identified by screening against appropriate RBCs (or
 KBAs tor radionuchdes).  MCLs are not used  in this screening to identify COPCs because MCLs  while
 based at least partly on health considerations, are  not set ut a concentration that correlates to a specific
 level of risk. Therefore, the RBCs for tap water  are a more conservative and consistent screening tool for
 risk assessment  In the feasibility study  and  proposed plan, the objective was to illustrate that  the
 discharge of shallow groundwater to surface  water  was very unlikely to have any adverse impact on
 surface water, therefore the Federal Ambient Water Quality Criteria (FAWQC) were used as  appropriate
comparison criteria. Please see the responses to following comments for related  discussion
                                               33

-------
  Comment No. 22:  'There  appears to be significant disconnect  between the nature and extent of
  contamination discussed in Chapter 4 of the remedial investigation Report, the baseline risk assessment
  discussed in Chapter 6, and the groundwater contamination referenced in the proposed plan.  With regard
  to organics. Chapter  4  discusses 1,1,2,2-tetrachloroethane and  a variety of pesticides.  However, the
  baseline risk assessment included compounds such as benzene. benzo(a)pyrene, carbon tetrachloride and
  chloroform as  chemicals of  potential  concern  (COPC),  while many of the pesticides and  1,1,2,2-
  tetrachloroethane were not assessed in  the risk assessment.   Also, certain inorganics  were selected as
  COPCs but not discussed in Chapter 4, including cobalt and vanadium. Complicating anyone's effort to
  participate in this process even further is the fact that the proposed plan  mentions cadmium as the only
  chemical of concern identified by the risk assessment process, but this metal is not discussed in Chapter 4
  or Chapter 6."

  Response No. 22:  The differences in discussion between Chapters 4 and 6 of the  RI report are due to the
  differences in the  objectives of the discussion.   Chapter  4  is  a presentation of nature and extent of
  contamination.  Chapter 6 is an assessment of risk to human and ecological receptors.

 The differences in constituent discussion is in part a  function of the data screening  process  for the two
 chapters, which has already been discussed  in the  response to comment no. 21.  An example of how the
 two data screening processes can result in  focus  on different sets of constituents can be illustrated by
 considering benzene in groundwater. Benzene was  detected in 1 of 11 surficial aquifer groundwater
 samples at a concentration of 1.4 ug/L.  This concentration is less than the MCL of 5 ug/L, and was not
 the focus of discussion  in  Chapter 4 of the  remedial investigation.   However, the single detected
 concentration does  exceed the RBC for tap water, and was designated as a COPC in Chapter 6.

 APG recognizes that this difference  in data  screening and presentation approaches can be confusing and
 misleading. More recent remedial investigation reports now in preparation are using a slightly different
 approach in Chapter 4 of the RI report. Tables for each environmental media at each waste unit/site/area
 of interest will list all detected constituents, the frequency of detection, other summary statistics including
 range  of detected concentrations   and mean  concentration,   and  comparisons  to  (1) background
 concentrations. (2) ARARS (MCLs for groundwater, etc.). and (3) risk-based screening levels for human
 health and ecological receptors, as appropriate.  This approach will present a wide range of information,
 and better illustrate to readers the range of constituents that  may be related to site  historical activities,
 those for which  there may be some associated risk (human  or ecological), and finally, those  that exceed
 ARARs. This approach will also be more consistent with and a better lead-in to fate and transport analysis
 in Chapter 5 and the risk assessment in Chapter 6.

 Comment No. 23:  "With regard to groundwater, the geological  cross sections (figures 3-5 through 3-7)
 within the RI appear  to  have an area of discrepancy.  Figure 3-6  presents a wide surficial aquifer
 northwest of the landfill, stretching from  10 - 25 feet above mean sea level (MSL).  In this cross section,
 the surficial aquifer is shown to reduce in thickness and more downward to 0 MSL at WBR-06 and WBR-
04. These two data points are in close proximity to WBR-05.  Figure 3-5, depicting the geology at WBR-
05, shows the canal creek  aquifer to be present at 0 MSL. Please explain this observation in the data."

Response No. 23: The information in the report is correct and demonstrates the discontinuous nature of
the surficial aquifer within Cluster 3.  What is  portrayed in the  cross sections is the best interpretation
based on  lithology at the  boring/well locations.  This APG interpretation was reviewed and considered
reasonable by geologists of the Army Corps of Engineers, MDE and EPA Region DDL
                                                34

-------
 Comment No. £4:  We need to assess what ramifications are possible from the hydraulic connect.on

 shou>edenb   lie?** -""IT1  -^ek aqUifefS WUh regUrd t0  long-tem ""tarnation migration   It
 should  be noted that in the feasibihty study, the aquifer identified as  the surficial aquifer is in close
 proxirnuy to what is identified as the Canal Creek aqu.fer.  It is not clear that this shallower  aquifer is
 separated from the lower water-bearing unit by a continuous confining layer.  In fact the cross-lections
 provided in the FS suggest that as one moves from the area  which  thetwo* streams converge a ^ the head
 waters of Laudenck Creek back  toward  the marsh area to the west of the proposed cap area the  two
 aquifers come closer together. Why has APG contractors not developed a three-dimensional model of the
 subsurface? If these aquifers are connected, the notion from APG reports that contamination in  the Canal
 Creek Aquifer originated from the west in the Canal Creek Study Area would be questionable."

 Response No. 24:  In the area immediately west of Cluster 3  the Canal Creek Aquifer is also the surf.cial

y   ,'* K V°"e mOV6S  eaf-tWard im° the CIuster3 area' the Canal Creek A^fer  dips, becoming
 eparated by Cretaceous confining clays from a surficial aquifer that is discontinuous in nature and very

     '
                                                                                n naure an  very
  file's? sThrnu'hTVTS' ?" ^™ ^ and ^ thr°Ugh 3'7 of remedial inv^tigation report and
  r™?r   I    Se          feasibility study report). The possible connection between the surficial and
  Canal Creek aquifer zones  m this area has been given  much consideration, and the most definitive
  evidence is from water level measurements that show a large difference in groundwater elevation between
  he two aquifer zones throughout the Cluster 3 area.  This large difference  in groundwater  elevadon
  approximately 12 ft) indicates that there is no hydraulic connection between the Ca?al cJ^dfeS
  the surficial aquifer (where it exists) in the Cluster 3 area.

  The cross sections are a three-dimensional model depicting the interpretation of lithology within the area
  No numencal  groundwater  flow model  has been developed  because groundwater is not a  trans^rt

  n^ ^JTT?       6m K?1 ^ °BRRD (°ther tha" Seepage of Perched water within the fill
  matenal created by the lower permeability of the fill material relative to surrounding native soils  which is
 discussed in the feasibility study report).

 Comment No 25: "While it is not discussed in the proposed plan/nickel is present in the Canal Creek
 Aquifer at well  WBR-03  located at the southern perimeter of the OBRRD. £ fact, nickel is present!*
  his aquifer at concentrations  above 2,000 ppb, which is more than 20 times the McL for this metal   As
  Hndf^  1SHahWare' M    COmp°Unds  including U^-tetrachloroethane, alpha-BHC, gamma-BHC
 oS± l^    P       ^oxide were found in the Canal Creek Aquifer at this Nation.  Data for various
 S  ? r in°LganiC C°mpOUnds sugSest  that contamination in the vicinity of this well migrate toward
 Laudenck  Creek,  as  various  contaminants were found at  WBR-08  at the next highest concentrations

 knn    Trl      Bd t*" ^"^ " ^^ °f 8°° PPb>'  In U«ht °f thls' II  WOUld ««™ importamto
 s^Ll ab^BTAr5 ^rr fCharf S £° LaUdenCk Creek' Where nickel has ^ ^ ££
 he S S A^v-, J . T ^    S, b,ee" Sh°Wn 3t °ther  IOCati°ns induding KinSs Creek' acco^i"g '0
 the U.S. Army s Ruk and Bwlogtcal Impact Assessment, where contaminants from the Canal Creek
 Aquifer have been shown to be discharging to surface water bodies."
           tafdaricTr ^ th%CanalfGrheek A^uifer diPs toward the southeast, it is likely that it does not
ok   aufer the n r  r  !            I ? WM d'SCharge °f contaminated groundwater from the Canal
quaTitv of ^ ?dimenrP  H ial,jmpaCtS W°uld not be "Assessed or ignored.  Past efforts have assessed the
quality of sediment and surface water within Lauderick Creek, and as RI/FS  efforts continue at sites
within the Lauderick Creek drainage basin, such assessments will continue.
                                               35

-------
  It is also suggested that caution be exercised in the use of contaminant concentrations to determine the
  direction of groundwater flow. It cannot always be assumed that groundwater movement is from a well
  location with high concentration toward one with lower concentration of a particular constituent.  Site
  hydrogeology will determine groundwater flow pathways, and dissolved constituents will move along
  these pathways.   Constituent concentrations can  provide  very valuable insight  into groundwater
  movement, but is secondary to hydrogeologic data in importance in assessing flow pathways.

  Comment No. 26:  "While there are multiple  lines of evidence to suggest that contamination is flowing
  from WBR-03 toward WBR-08, one must entertain the possibility that WBR-03 may be situated on a
  divide and that groundwater also flows from this point toward the west (WBR-05) and the Canal Creek
  Study Area.  In fact, I believe IRP  personnel at previous RAB  meetings  have presented information
  regarding the migration of contamination from the Northern  Bush River Study Area toward the Canal
  Creek Study Area.  The detection of the same pesticides and various metals in  well WBR-05, as those
  found at WBR-03, support such a possibility. This observation plus the fact that nickel turned up in other
 wells believed to be in a different aquifer reinforces the need to resolve the observation discussed above -
 namely  that the IRP must be sure that the surficial and Canal Creek aquifers have not been misidentified
 from one location to another.  These concerns regarding aquifer identification and contaminant migration
 direction is also supported by the radial flow contours depicted in figures 3-9 and 3-10 of the RI report."

 Response No. 26:   "Water level data over a period of time  shows that groundwater movement in the
 Canal Creek Aquifer is  consistently in  roughly an eastward  direction  across  the Cluster 3 area.
 Constituent concentration  data cannot be used alone without hydrogeologic data in assessing groundwater
 movement. Figures 3-9 and 3-10 of the remedial  investigation report are for the surficial aquifer zone,
 and not the Canal Creek Aquifer.

 The presence of nickel in surficial aquifer groundwater at the locations of wells WBR-04, -06 and -07,
 and in Canal Creek Aquifer wells WBR-05 and -03, suggests that there was  a historical source of nickel
 in Site 23, as stated in the remedial investigation report.  A review of the data for the Canal Creek study
 area indicates that nickel  is one of the most common inorganic constituents to  exceed the former MCL
 level  of  100 ug/L, with samples from at least a dozen wells in five widely separated  areas having such
 levels of nickel (Canal Creek Study Area,  Remedial Investigation  Progress Report,  Edgewood Area,
 Aberdeen Proving Ground, Maryland. Jacobs Engineering Group.  September 1995).  The available data
 are not adequate to determine if the nickel detected in the Cluster 3 area is from upgradient sources within
 the Canal Creek study area.

 The risk  assessment did not identify nickel as a final constituent of concern for groundwater. There is no
 longer an MCL for nickel, and the groundwater at Cluster 3 is a Type III aquifer to which MCLs do not
 apply,

 Comment No. 27: "Gross beta readings were found to be elevated compared to background at WBR-03,
 WBR-04 and WBR-10, at concentrations  of  31,  24 and 97 pCi/L, respectively.  In  addition to our
concerns regarding the migration of contaminants at WBR-03. as discussed previously, APGSCC is also
concerned about the presence of elevated radiological data in groundwater  so close to on-post housing
(less than 200 feet).  It should be noted that gross alpha was also detected at this well at 25 pCi/L+/-10,
which would place it at the MCL for alpha radioactivity of 15  pCi/L.  Gross beta was found consistently
at this location between 90 and 110 pCi/L for three consecutive rounds. The RAD  risk discussion  in
                                                36

-------
                n            concems generated by these data.  In fact, section 6.3 the MCL for Radium
            and Ra-228 combined is 5 pCi/L while Ra-226 was detected in the groundwater at Cluster 3 at
   7.7 pCi/L. A proposed rule was mentioned for Ra-226 of 20 pCi/L in the text, but the significance of this
   proposed rule versus the current standard is not discussed."

   Response No. 27:  The elevated gross beta levels are due to naturally occurring potassium-40
   Of the three mentioned wells, only for WBR-10 did groundwater samples consistently show high gross
   beta.  The groundwater samples from this well were  also quite high in total potassium, with detected
   concentrates ranging up to 94.5 rng/L.  For this total potassium level, the nonvolatile beta activity due
   to naturally occurring K-40 : would be approximately 80 pCi/L.  In the sampling of a monitoring well, it is
  common for there to be substantial variation in amounts of suspended solids between sample containers

  S- ^ r1? ^L I'6',   Th0 SamP'ing Pla" f°r  C1UStCr 3 Spedfied  that  the  samP'e 'ontainer  fT
  radionuchdes be the last contamer filled. As the last container filled, it would have normally contained
  the greatest amount of suspended solids, and with analysis of unfiltered samples, would have caused gross
  beta measurements to be elevated due to K-40.  The elevated levels of total  potassium in samples  from
  this well are due to  grout contamination  within the screened  interval created during well installation
  fromlhis teH          ""^ characteristic of Srout contamination, is also observed in water samples


  As noted in the response to other comments, the gamma spectrometry -methodology for water commonly
  provides erroneous results for Ra-226.                                            ,       ^'»«»ui"y


  Ir^TH^ thC ladi°cl|emistry  data for Cluster 3 does not show  any evidence of contamination  by
  radionuchdes, with  results being consistent with naturally occurring levels  and variability typical for
  gamma spectrometry analysis.

  Comment No. 28:  'This same section mentions that  RESRAD was used to back-calculate acceptable
  sotl concentrations,  but does not discuss how the groundwater  issue was evaluated   APGSCC requests
  that the  presence of this radiological contamination  be  evaluated under  the  best risk  assessment
 procedures available and that APG evaluate possible sources for such contamination, including naS
 cotTf tTRgF?LPn S  Hf8- TTake thlS PrOC6SS transParent to *« Public, the TAG Group needs a
 copy of the RESRAD model to evaluate its design.  Furthermore, APG, the EPA and APGSCC need to
 meet to assess the input parameters used in the model for APG.  Lastly, the risk evaluation process must
 be clearly delineated within  the text of the CERCLA  documentation for this and other APG siteTof
 frnr^-  ' remamS imperative that APG develop a comprehensive, clear approach for  assessing risk
 IZnrtn hT  /°T """"L10"'  3nd the "^ t0 ade1uately eva'"*e radiological risk at Cluster  3 is
 supported by the data from other media discussed below."

 Response No. 28: Please see Response No.  18 for a discussion  on handling of groundwater. A clear and
 m^SmrenTiSSme  ^    aSS6SSment for radio™clides has been adopted by APG, and  will be seen
Comment No. 29:  "Lead was found in a few surface water samples collected, with at least one sample
exceeding its water quality criterion. While the proposed plan does not identify it as such, the comparison
criterion used in this assessment appears to be the acute concentration,  which is much higher than  the
chronic criterion.  Given that the landfill is a constant source in the area and continuously releasing
contamination, it is not clear why the acute criterion has been accepted in this assessment. Furthermore, a
                                               37

-------
  majority of the samples analyzed were collected in two rounds during a fairly small time window between
  October 24 and November 13, 1996. It is questionable whether this sampling approach would give a
  reasonable picture of contamination, considering the various environmental factors from one season to the
  next that would influence run-off, contaminant solubility,  etc.   In support of this  concern, it  is  worth
  noting the samples that revealed surface  water contamination in excess of the water quality criteria were
  collected in early September and late March, both months  of which represent environmental conditions
  considerably different than the last October/early November time period. Gross beta readings were found
  in both surface water samples at fairly consistent  concentrations. 58 and 73 pCi/L, respectively. This is
  worth noting since a considerable distance separates the two sampling points. While the RI Report notes
  that the concentrations were  much  lower in the second round, this  is not surprising  since consistent
  detections in surface water is not common for sites where ground water discharge or surface runoff are the
  most likely  avenues for this contamination to reach the surface water body.  APGSCC  requests that
  additional surface water sampling be conducted to  evaluate the persistence of the lead and radiologicals."

  Response No. 29:  APG recognizes that a thorough understanding of contaminant transport from the
  OBRRD via surface water and sediment  is important. While the proposed remedy for the OBRRD will
 eliminate releases from the source area, it is important that  monitoring measure the effectiveness of this
 remedy, and  also develop data that can be used to assess the long-term ecological risk associated with
 constituents already in sediments of Lauderick Creek. APG is planning to conduct sampling and analysis
 of sediment  because constituents have  migrated to nearby  Lauderick Creek sediments via  sediment
 erosion  and transport.  The monitoring  will include multiple sampling events from before until  after
 construction,  and will include  sediment  chemistry as well  as sediment bioassay.  This monitoring will
 assess seasonal effects and trends,  and  will include assessment using appropriate toxicity  reference
 values. APG is also considering the use of sediment bioassay as a long-term monitoring tool.

 The types of  constituents that are of concern at the OBRRD have a relatively low  water solubility and
 high soil/water partition coefficient,  and  as a result  are  primarily  associated and  transported  with
 sediments  (as opposed to solute transport).  Because of these characteristics, future monitoring will focus
 on sediments  rather than surface water. Transport of constituents will be associated  with storms or other
 events that disturb source areas or sediments, and will typically be short in duration.

 Comment No. 30:  'These same issues exist for the  few sediment samples collected.  Specifically, lead
 was found in  both remedial investigation samples above the maximum reference concentration; for one
 location  the lead was present at a concentration  10 times greater than the BTAG criterion of 46.7 ppm.
 Radiological contamination was also found in both remedial investigation sediment samples at 28 and 32
 pCi/L. Interestingly, the man-made isotope cesium was present at both sites  as well, although cesium-137
 and  potassium-40 were reported to  be detected below  background levels collected  by the Maryland
 Department of Natural Resources. Radium-226 was present in sediment at levels greater than background
 (1.80 vs. 1.98 pCi/g).  Lastly, we are concerned that the isotopes reported only account for 1/4 - 1/3 of the
 gross beta measured  in the sediments.  While  the  lead contamination was mentioned in the PP, the
 radiological contamination was not included. As acknowledged in the  PP, sediment samples exceed the
 BTAG criteria for  metals.   Upon review  of the FS (fig.  1-10). these contaminants  include arsenic,
 beryllium,  lead, mercury and nickel.  From the data reviewed,  it does not appear  that there are many
samples from  the marsh and Lauderick Creek outside the selected area for cap construction.  With the
limited number of samples in Lauderick Creek, it is not clear that an adequate assessment of contaminant
migration and  ecological impacts has taken place.  APGSCC requests clarification as to the role the EPA
Biological  Technical  Assistance Group (BTAG)  played in evaluating the ecological  issues regarding
                                                38

-------
  Cluster 3 and the adjacent water body.  Additionally, please explain why bioassays were not conducted
  with regard to the contamination in the marsh surrounding the landfill and in Lauderick Creek?

  Response No. 30: Please see responses to other comments concerning plans to assess metals in sediment
  by  sampling, chemical analysis, and laboratory  bioassay testing.   Please  also  see other comments
  concerning the presence of naturally occurring and man-made radionuclides in environmental media as
  well as the limitations of the gamma spectrometry method of analysis.  There are no indications of
  radionuclide contamination at Clusters  or the OBRRD.  Please see response to  comment  no  18 for
  further discussion.

  Please see responses to other comments concerning plans to assess metals in sediment by  monitoring and
  bioassay. Please also note that the-proposed remedy will prevent any further release of constituents from
  source  areas  in the OBRRD, and that the remedy can be accomplished without further data assessing
  impacts on Lauderick Creek. Bioassays have been performed with sediment samples collected within the
  mam portion of Laudenck Creek and have not identified toxicity problems. That work did not address the
  tributary portion of Laudenck Creek immediately downstream of the OBRRD, which will be the  focus of
  the planned, monitoring and assessment.

  Comment No. 31: "Furthermore, the proposed plan asserts that the contamination in the sediments has
  come from past or continuing slumping and erosion of the surface of the OBRRD  Yet as acknowledged
  in the previous sentence within the proposed plan (page 6), it is also possible that such contamination is
 coming from the anomaly areas detected in the marsh (the push out areas). Given the 1) lack of sampling
 conducted outside the area to be capped, 2) the data gaps regarding the source(s) of contaminants detected
 m the segment  samples that were collected in Lauderick Creek, and 3) the funds saved  by cappine the
 site instead or  removing the  source, APGSCC requests that  additional sediment and surface water
 sampling be  implemented as part of the ROD and long-term monitoring efforts to further evaluate the
                       '" thC marSh and thC effectiveness of the caP in educing further deterioration of
 Response No. 31: The push out areas mentioned are a part of the OBRRD and will be addressed by the
 proposed remedy Then jis no further need to conduct sampling and analysis to support the remedial
 decision process for  the OBRRD.  Sampling and analysis of sediment, as well as sediment bioassay is
 planned to evaluate the implementation and effectiveness of the remedy, and to provide data necessary to
 s                                           risk associated  with
APG believes that there is sufficient justification to proceed with remediation of the OBRRD as a source
area to ensure that there is no further release of constituents of concern to Lauderick Creek. The planned
monitoring will be separate from the decision process and ROD. allowing remediation to proceed.
          n°* ^ "GT ^tawere elevated in a» soil samples collected from Cluster 3. Cesium was
present m all samples and other isotopes including radium-226 and thorium-228 were detected. Although
it is not discussed m the PP, the baseline risk assessment chapter in the RI notes that Ra-226 was detectfd
in sod and sediment at concentrations three and two times higher than concentrations corresponding to the
                                        Yet' no other discussion  takes  iace i
                                               39

-------
 Response No. 33:  Please see other responses related to radiochemistry and the natural and anthropogenic
 occurrence of radionuclides.  A review of the radiochemistry data for Cluster 3 does  not show any
 evidence of contamination by radionuclides, with results being consistent with naturally occurring levels
 and variability typical for gamma spectrometry analysis.

 COMMENTS FROM MARYLAND DEPARTMENT OF THE ENVIRONMENT

    The Environmental Restoration  and Redevelopment Program  (EERP) of the Waste Management
Administration provided the following comment.

Comment No. 34:  MDE noted there was an incorrect Code of Maryland Regulations (COMAR) citation
in the Proposed Plan and stated it should be deleted.

Response No. 34: APG has deleted the reference.
                                              40

-------
  U.S. ARMY WVHcS PUBLiC CMMENT
                                 •
        ON pn
                                     ron
.^berdee* ProTtaf Qiwaw***^'
                                   mbUetocmtttMii*
   0*ttor**^,W*^"^V^*/*G'*
            Mil
                        •Ro*ddu*pcUej
   The public nay «obmUwniieyra>i»-;
menu on the Proposed Phm deitaf thW-
Idty comment period which ren> N*H«ff
3 Mo September 14.1998. CSmmeWr^sl
be postmtrked by September .I4:ihd av be
sentto:             ..'.'-.
Mr.KeKSttdilw      .  •"','-"
U.S. Arar Omison. ATTN: STEAMrM*
5n9H
-------
                MARYLAND DEPARTMENT OF THE ENVIRONMENT
                2500 Broemng Highway • Baltimore Maryland  21224
                (410)631-3000 • 1-800-633-6101 •  http://www.mde. state, rnd. us
Parris N.  Glendening                                                                  j^g -p
Governor                                                                                 '„
                                                                                         Secretary


                                             October 15, 1998
      Mr. Ken Stachiw
      Directorate of Safety, Health and Environment
      U.S. Army Aberdeen Proving Ground Support Activity
      Aberdeen Proving Ground MD 21005-5001

      RE:    Bush River Study Area. Edeewood Area. APG. Proposed Plan. Cluster 3. Site 3. Old
             Bush River Road Dump July 1998                                              ,

      Dear Mr. Stachiw:

             The Maryland Department of the Environment, Waste Management Administration
      (MDE/WAS) has reviewed the above-referenced document.  This review indicated that a Code
      of Maryland Regulations (COMAR) citation was incorrectly referenced in the subject document
      as an Applicable or Relevant and Appropriate Requirement (ARAR). Unfortunately during the
      development of the Feasibility Study for this site, the Federal Facilities Section of the
      Environmental Restoration and Redevelopment Program (ERRP) erroneously identified the
      citation from COMAR 26.13.14 as a potential ARAR for the subject action.  The error was then
      transferred to your document.

             Once this error was identified, the correct citation was reviewed in some detail
      Following the revaluation of COMAR 26.13.05.14, which is in the State's Hazardous Waste
      regulations, ERRP does not believe that the cited COMAR is more stringent than the equivalent
      Federal regulation. Therefore, COMAR 26.13.05.14 should not be considered State ARAR for
      this action. Please revise the subject document by deleting the reference to COMAR 26.13.14.

             The subject document adequately presents the Army's proposal to construct a soil cover
      on the Old Bush River Road Dump.  The action is expected to reduce further erosion and
      mitigate exposure to unexploded ordnance. This action will address the concerns identified
      during the remedial investigation of this site, principally, further erosion of material at the site
      and direct exposure to unexploded ordnance buried at the site. The Army's commitment to long-
      term monitoring will further ensure that the action sufficiently addresses site concerns. The
      ERRP considers the actions proposed by the Army to be appropriate to the circumstances at this
      site.

-------
Mr. Ken Stachiw
Page 2
       If you have any questions, please contact me at (410) 631-3440.

                                        Sincerely,
cc:     Mr. Steve Hirsh
       Mr. Richard Collins
       Ms. Hilary Miller
       Ms. Shari Wilson
                                        John Fairbank, Chief
                                        Federal/NPL Superfund Division

-------

-------
                  Reproduced by NTIS
      00
 wr ^^

 BM
*3 0 0) 0
 .. c u _^
s o o ?
 0) C

>i Q
 0£.£o
•n C 0) c
"3-D C
w^
                  National Technical Information Service
                  Springfield, VA 22161
                          This report was printed specifically for your order
                        from nearly 3 million titles available in our collection.
                  For economy and efficiency, NTIS does not maintain stock of its vast
                  collection of technical reports. Rather, most documents are printed for
                  each order. Documents that are not in electronic format are reproduced
                  from master archival copies and are the best possible reproductions
                  available. If you have any questions concerning this document or any
                  order you have placed with NTIS, please call our Customer Service
                  Department at (703) 605-6050.

                  About NTIS
                  NTIS collects scientific, technical, engineering, and business related
                  information — then organizes, maintains, and disseminates that
                  information in a variety of formats — from microfiche to online services.
                  The NTIS collection of nearly 3 million titles includes reports describing
                  research conducted or sponsored by federal agencies and their
                  contractors; statistical and business information; U.S. military
                  publications; multimedia/training products;  computer software and
                  electronic databases developed by federal agencies; training tools; and
                  technical reports prepared by research organizations worldwide.
                  Approximately 100,000 new titles are added and indexed into the NTIS
                  collection annually.
                      For more information about NTIS products and services, call NTIS
                      at 1-800-553-NTIS (6847) or (703) 605-6000 and request the free
                       NTIS Products Catalog, PR-827LPG, or visit the NTIS Web site
                                        http://www.ntis.gov.
                                              NTIS
                        Your indispensable resource for government-sponsored
                                  information—U.S. and worldwide

-------

-------