w .
             1
PB99-964009
EPA541-R99-027
1999
     EPA Superfund
           Record of Decision:
           Ross Metals Inc OU 1
           Rossville, TN
           4/2/1999

-------

-------
     ROSS METALS
    SUPERFUND SITE
 RECORD OF DECISION
       April 2,1999
                 \
           PRO'

U.S. Environmental Protection Agency
         Region 4

-------

-------
                         RECORD OF DECISION
                         TABLE OF CONTENTS
1.0 DECLARATION	Declaration - 1

2.0 DECISION SUMMARY ....:                                       -1-
      2.1 SITE NAME, LOCATION, AND DESCRIPTION	  -1-
      2.2 SITE HISTORY AND ENFORCEMENT ACTIVITIES                  -1-
      2.3 HIGHLIGHTS OF COMMUNITY PARTICIPATION                   -9-
      2.4 SCOPE AND ROLE OF OPERABLE UNIT                           -11-
      2.5 SITE CHARACTERISTICS	             -13-
            2.5.1 Land Use	 -13-
            2.5.2 Climatology	 -.13-
            2.5.3 Physiography	 -13-
            2.5.4 Surface Water	 -14-
            2.5.5 Geology and Hydrogeology	 -17-
            2.5.6 Previous Investigations	 -28-
            2.5.7 Nature and Extent of Contamination 	 -30-
                  2.5.7.1  Soil and Sediment 	 -30-
                  2.5.7.2  Groundwater	 -35-
                  2.5.7.3  Surface Water  	 -36-
                  2.5.7.4 Contaminant Fate And Transport	 -38-
            2.5.8 Treatability Studies	 -43-
                  2.5.8.1  Dewatering Study, December 1997	 -43-
                  2.5.8.2  Stabilization Study, March 1998	 -45-
                  2.5.8.3  Biosolids Study, November 1998	 -46-
       2.6 SUMMARY OF SITE RISKS  	                        -46-
                                     -i-

-------
                     RECORD OF DECISION
                     TABLE OF CONTENTS
       2.6.1 Human Health Risk Assessment Summary		  .45-
             2.6.1.1 Data Evaluation	  .45.
             2.6.1.2 Exposure Pathways  	    _4g.
             2.6.1.3 Toxicity Values	       .53.
             2.6.1.4 Risk Characterization 	      .55.
       2.6.2 Ecological Risk Assessment Summary	  .59.
             2.6.2.1 Identification of Chemicals of Concern	  -69-
             2.6.2.2 Ecological Exposure Assessment	  .72.
             2.6.2.3 Ecological Effects Assessment	  _7g_
             2.6.2.4 Conclusions	      _90_
2.7 REMEDIATION OBJECTIVES	       _91_
      2.7.1 Remedial Goals 	           _9I_
      2.7.2 Remedial Action Objectives 	       .93.
      2.7.3 Extent of Source Material Contamination Above Remedial Goals .   -95-
2.8 DESCRIPTION OF SOURCE MATERIAL ALTERNATIVES  .......  -102-
      2.8.1 Alternative S-l - No Action	  _102-
            2.8.1.1 Description	         -102-
            2.8.1.2 Overall Protection of Human Health and the Environment
                   	  -102-
            2.8.1.3 Compliance with ARARs	  _105_
            2.8.1.4 Long-Term Effectiveness and Permanence	 -105-
            2.8.1.5 Reduction of M/T/V Through Treatment	 -105-
            2.8.1.6 Short-Term Effectiveness	 _105-
            2.8.1.7 Implementability 	                  _105_
            2.8.1.8 Cost	               -106-
                                -H-

-------
              RECORD OF DECISION
              TABLE OF CONTENTS
2.8.2 Alternative S-2 - Capping	  -106-
      2.8.2.1 Description	  -106-
      2.8.2.2 Overall Protection of Human Health and the Environment
             	r	  -107-
      2.8.2.3 Compliance with ARARs		  -109-
      2.8.2.4 Long-Term Effectiveness and Permanence	  -111-
      2.8.2.5 Reduction of M/T/V Through Treatment	  -112-
      2.8.2.6 Short-Term Effectiveness	  -113-
      2.8.2.7 Implementability 	  -113-
      2.8.2.8 Cost	  -114-
2.8.3 Alternative S-3 - Capping With Pavement in Place	  -114-
      2.8.3.1 Description	  -114-
      2.8.3.2 Overall Protection of Human Health and the Environment
             	  -115-
      2.8.3.3 Compliance with ARARs	  -117-
      2.8.3.4 Long-Term Effectiveness and Permanence	  -119-
      2.8.3.5 Reduction of M/T/V Through Treatment	  -120-
      2.8.3.6 Short-Term Effectiveness	  -121-
      2.8.3.7 Implementability	  -121-
      2.8.3.8 Cost	  -122-
2.8.4 Alternative S-4 — Capping With Construction of Above-Ground Disposal
      Cell	  -122-
      2.8.4.1 Description	  -122-
      2.8.4.2 Overall Protection of Human Health and the Environment
             	  -123-
                           -ni-

-------
              RECORD OF DECISION
               TABLE OF CONTENTS
      2.8.4.3 Compliance with ARARs	  -125-
      2.8.4.4 Long-Term Effectiveness and Permanence	  -127-
      2.8.4.5 Reduction of M/T/V Through Treatment	  -128-
      2.8.4.6 Short-Term Effectiveness	  -129-
      2.8.4.7 Implementability		  -129-
      2.8.4.8 Cost			  -130-
2.8.5A Alternative S-5 ~ Excavation And Onsite Treatment With
      Solidification/Stabilization
      Option A - Onsite Disposal of Treated Waste	  -130-
      2.8.5A.1 Description	  -130-
      2.8.5A.2 Overall Protection of Human Health and the Environment
             	  -132-
      2.8.5A.3 Compliance with ARARs 	  -134-
      2.8.5A.4 Long-Term Effectiveness and Permanence  	  -136-
      2.8.5A.5 Reduction of M/T/V Through Treatment  	  -137-
      2.8.5A.6 Short-Term Effectiveness 		  -138-
      2.8.5A.7 Implementability	  -138-
      2.8.5A.8 Cost  	  -139-
2.8.SB Alternative S-5 - Excavation And Onsite Treatment With
      Solidification/Stabilization
      Option B - Offsite Disposal of Treated Material	  -140-
      2.8.5B.1 Description	  -140-
      2.8.5B.2 Overall Protection of Human Health and the Environment
             	  -141-
      2.8.5B.3 CompKance with ARARs	  -142-
                          -IV-

-------
             RECORD OF DECISION
              TABLE OF CONTENTS
      2.8.5B.4 Long-Term Effectiveness and Permanence 	  -142-
      2.8.5B.5 Reduction of M/T/V Through Treatment	  -142-
      2.8.5B.6 Short-Term Effectiveness	  -143-
      2.8.5B.7 Implementability	  -144-
      2.8.5B.8 Cost 	•  -144-
2.8.6A Alternative S-6 ~ Capping w/ Excavation & Onsite Treatment of
      Principal Threat Waste
      Option A-Onsite Disposal of Treated Principal Threat Waste .  -145-
      2.8.6A.1 Description	  -145-
      2.8.6A.2 Overall Protection of Human Health and the Environment
             	  -147-
      2.8.6A.3 Compliance with ARARs  	  -149-
      2.8.6A.4 Long-Term Effectiveness and Permanence 	  -151-
      2.8.6A.5 Reduction of M/T/V Through Treatment 	  -152-
      2.8.6A.6 Short-Term Effectiveness  	  -152-
      2.8.6A.7 Implementability	  -153-
      2.8.6A.8 Cost	  -154-
2.8.6B Alternative S-6 - Capping w/ Excavation & Onsite Treatment of
      Principal Threat Waste
      Option B - Offsite Disposal of Treated Principal-Threat Waste . -154-
      2.8.6B.1 Description	 -154-
      2.8.6B.2 Overall Protection of Human Health and the Environment
              	 -157-
      2.8.6B.3 Compliance with ARARs	 -159-
      2.8.6B.4 Long-Term Effectiveness and Permanence  	 -161-
                           -V-

-------
                    RECORD OF DECISION
                    TABLE OF CONTENTS
            2.8.6B.5 Reduction of M/T/V Through Treatment	 -161-
            2.8.6B.6 Short-Terra Effectiveness	 -162-
            2.8.6B.7 Implementability	 -162-
            2.8.6B.8 Cost	 -163-
2.9  WETLAND SEDIMENT ALTERNATIVE ANALYSIS	 -163-
      2.9.1 Alternative W-l — No Action	 -164-
            2.9.1.1  Description	 -164-
            2.9.1.2  Overall Protection of Human Health and the Environment
                   	 -164-
            2.9.1.3  Compliance with ARARs	 -164-
            2.9.1.4  Long-Term Effectiveness and Permanence	 -166-
            2.9.1.5  Reduction of M/T/V Through Treatment	 -166-
            2.9.1.6  Short-Term Effectiveness	  	 -166-
            2.9.1.7  Implementability  	,	 -166-
            2.9.1.8 Cost	 -166-
      2.9.2 Alternative W-2 - Capping with Clean Fill and Off-Site Creation of
            Wetlands	 -167-
            2.9.2.1  Description	 -167-
            2.9.2.2  Overall Protection of Human Health and the Environment
                 	 -167-
            2.9.2.3  Compliance with ARARs		 -168-
            2.9.2.4  Long-Term Effectiveness and Permanence	 -170-
            2.9.2.5  Reduction of M/T/V Through Treatment	 -170-
            2.9.2.6  Short-Term Effectiveness	 -171-
            2.9.2.7  Implementability 	 -171.
                                -VI-

-------
                   RECORD OF DECISION
                   TABLE OF CONTENTS
           2.9.2.8 Cost	  -172-
     2.9.3 Alternative W-3 - Excavation & Revegetation/Restoration of Wetlands
           Option A - Regrading With Clean Fill	 	  -172-
           2.9.3A.1 Description	  -172-
           2.9.3A.2 Overall Protection of Human Health and the Environment
                  	;	  -173-
           2.9.3A.3 Compliance with ARARs  	  -174-
           2.9.3A.4 Long-Term Effectiveness and Permanence  	  -175-
           2.9.3A.5 Reduction of M/T/V Through Treatment 	  -175-
           2.9.3A.6 Short-Term Effectiveness	  -175-
           2.9.3A.7 Implementability	  -176-
           2.9.3A.8 Cost  	  -176-
     2.9.3B Alternative W-3 -Excavation & Revegetation/Restoration of Wetlands
           Option B ~ Regrading with Biosolid Compost Material	  -176-
           2.9.3B.1 Description	  -176-
           2.9.3B.2 Overall Protection of Human Health and the Environment
                  	  -178-
           2.9.3B.3 Compliance with ARARs	  -178-
           2.9.3B.4 Long-Term Effectiveness and Permanence  	  -179-
           2.9.3B.5  Reduction of M/T/V Through Treatment	  -179-
           2.9.3B.6  Short-Term Effectiveness	  -180-
           2.9.3B.7  Implementability	  -181-
           2.9.3B.8  Cost	 .  -181-
2.10  COMPARATIVE ANALYSIS OF ALTERNATIVES  	  -181-
2.11  SELECTED REMEDY	  -185-
                               -Vll-

-------
                        RECORD OF DECISION                          it
                        TABLE OF CONTENTS
       2.12 STATUTORY DETERMINATIONS	  _193_
            2.12.1 Overall Protection of Human Health and the Environment	  -193-
            2.12.2 Compliance with Applicable or Relevant and Appropriate Requirements
                 (ARARs)	  _194_
            2.12.3 Cost-Effectiveness	               -196-
           2.12.4 Utilization of Permanent Solutions and Alternative Treatment (or
                 Resource Recovery) Technologies to the Maximum Extent Practicable
                 	•	•	 -197-
           2.12.5 Preference for Treatment as a Principal Element	 -197.
           2.12.6 Five-Year Requirements	 _199_    ••

3.0 RESPONSIVENESS SUMMARY	 _199_
      3.1 RESPONSIVENESS SUMMARY OVERVIEW 	   -199.
      3.2 SUMMARY OF MAJOR QUESTIONS AND COMMENTS RECEIVED BY THE
           ROSSVBLLE COMMUNITY  	 _200-
      3.3 SUMMARY OF THE MAJOR QUESTIONS AND COMMENTS RECEIVED BY
           THE "GROUP"	 _200.

APPENDIX A   PROPOSED PLAN
                                                                             »

APPENDIX B   LETTERS OF CONCURRENCE
                                                                             »-
APPENDIX C   TRANSCRIPT OF NOVEMBER 30,1998 PUBLIC MEETING
                                 -VIM-

-------
                            RECORD OF DECISION
                            TABLE OF CONTENTS
Figure 2-1    Site Location Map 	  -2-
Figure 2-2    Site Layout	  -3-
Figure 2-3    100 Year Flood Plain Map	  -15-
Figure 2-4    Wetlands Delineation  	  -16-
Figure 2-5    Regional Cross-Section  .".	  -18-
Figure 2-6    Cross-Section Locations	  -21-
Figure 2-7    Cross Section A-A' and B-B'	  -22-
Figure 2-8    Cross Section Locations - 1997 Borings	  -23-
Figure 2-9    Cross Section A-A', 1997 Borings	  -24-
Figure 2-10   Cross Section B-B', 1997 Borings	  -25-
Figure 2-11   Potentiometric Surface Map - October 1, 1990	  -26-
Figure 2-12   Potentiometric Surface Map - November 1996	  -27-
Figure 2-13   Extent of Lead in Surface Soils	  -31-
Figure 2-14   Maximum Lead Results in Sediment (TAL Analysis - Ecological Investigation)
               	,	  -32-
Figure 2-15   Contaminant Contour in Wetlands - March 1998 	  -33-
Figure 2-16   Extent of Lead in Subsurface Soils	  -34-
Figure 2-17   Total Lead Concentrations - Water	  -37-
Figure 2-18   Lead Results in Surface Water (TAL Analysis - Ecological Investigation) ...  -39-
Figure 2-19   Fate and Transport	  -40-
Figure 2-20   Conceptual Site Model	  -49-
Figure 2-21   Site and Reference Area Location Map	  -83-
Figure 2-22   Cleanup Goals v. Excavation Required	  -98-
Figure 2-23   Contaminant Contour in Wetlands 	  -99-
Figure 2-24   Alternative S-2      Capping	  -108-
Figure 2-25   Alternative S-3      Capping with Pavement in Place	  -116-
                                         -ix-

-------
                           RECORD OF DECISION
                                                          f
TABLE OF CONTENTS
 Figure 2-26   Alternative S-4       Capping with Construction of Above-Ground Cell ..  -124-


 Figure 2-27   Alternative S-5A     Treatment and On-Site Disposal	  .133.


 Figure 2-28   Alternative S-6A     Treatment w/On-Site Disposal of Treated Principal Threat Waste


                                 	  -148-

 Figure 2-29   Alternative S-6B     Treatment w/Off-Site Disposal of Treated Principal Threat


                                Waste


                                 	  -158-

Figure 2-30   Excavation Contours  	            '     -189-
                                      -x-

-------
                           RECORD OF DECISION
                            TABLE OF CONTENTS
Table 2-1     Non-Hazardous Waste Removed Offsite	  -7-
Table 2-2     Hazardous Waste Removed Offsite	  -8-
Table 2-3     Summary of Chemicals of Concern	...	 -51-
Table 2-4     Cancer Slope Factor	 -54-
Table 2-5     Reference Dose  	 -55-
Table 2-6     Process Area: Future Risk Summary	 -59-
Table 2-7     Process Area: Future Use Risk Summary (w/o Groundwater Pathway)	 -60-
Table 2-8     Process Area: Exposure to Lead	 -62-
Table 2-9     Process Area: Exposure to Lead (w/o Groundwater Pathway) 	 -63-
Table 2-10    Landfill: Future Risk Summary	 -64-
Table 2-11    Landfill: Future Risk Summary (w/o Groundwater Pathway)  	 -65-
Table 2-12    Landfill: Exposure to Lead	 -67-
Table 2-13    Landfill: Exposure to Lead (w/o Groundwater Pathway)  	 -68-
Table 2-14    COCs Distribution and Hazard Quotient Calculations	 -71-
Table 2-15    Ecological Exposure Pathways of Concern	 -79-
Table 2-16    COC Concentrations Expected to Provide Adequate Protection of Ecological Receptors
               	 -92-
Table 2-17    Remedial Goals  	 -94-
Table 2-18    Summary of Soil Alternatives Evaluation  	  -103-
Table 2-19    Summary of Wetland Sediment Alternatives Evaluation	  -165-
Table 2-20    Comparative Analysis of Soil Alternatives	  -182-
Table 2-21    Comparative Analysis of Wetland Sediment Alternatives	  -183-
Table 2-22    Excavation Standards	  -188-
Table 2-23    Capital Costs for Selected Remedy	  -191-
Table 2-24    Operation and Maintenance Costs for Selected Remedy	  -192-
                                         -XI-

-------

-------
                                                                              Record of Decision
                                                                              Ross Metals OU#1
1.0  DECLARATION

SITE NAME AND LOCATION

Ross Metals, Operable Unit #1
100 North Railroad Street
Rossville, Fayette County, Tennessee

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for the Ross Metals Site, Operable Unit #1, in
Rossville, Fayette County, Tennessee. This action is. chosen in accordance with CERCLA, as amended by
SARA, and, to the extent practicable,  the National Contingency Plan.   This decision is based on  the
Administrative Record for this Site.

The State of Tennessee concurs with the Selected Remedy.

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from this Site, if not addressed by implementing the
response action selected in this ROD, may present an imminent and substantial endangerment to public health,
welfare, or the  environment.

DESCRIPTION OF THE REMEDY

This operable unit is the first action of at least two operable units that are planned for the Site.

This operable unit remedy addresses source materials (soil, sediment, waste, pavement, and debris) through
treatment and off-Site disposal of principal and low-level threat wastes.

The major components of the remedy include:

•      Decontamination, demolition, and off-Site disposal of pavement and buildings with recycling of metal
       debris;

•      Excavation of contaminated  soil, landfilled slag,  and contaminated  sediment with appropriate
       confirmation sampling;

•      Backfill of excavated subsurface-soil areas and landfill with clean soil;

•      Stabilization/solidification/fixation of contaminated soil, stockpiled slag, landfilled slag, and wetlands
       sediment;
                                         Declaration -1

-------
                                                                                Record of Decision
                                                                                Ross Metals OU#1
•       Off-Site disposal of soils, slag and sediment at a RCRA-nonhazardous waste disposal facility;

•       Application of a layer of biosolids over the Site. Grass seeding of the facility and landfill areas; and
        revegetation of the Site wetlands according to the wetlands revegetation plan developed by EPA, 1998.

•       Development of a maintenance and monitoring plan to assess the effectiveness of the cleanup action.

STATUTORY DETERMINATIONS

The Selected Remedy is protective of human health and the environment, complies with Federal and State
requirements that are legally applicable or relevant and appropriate to the remedial action, and is cost-effective.
This remedy utilizes permanent solutions and alternative treatment technologies, to the maximum extent
practicable for the Site. This Remedy satisfies the statutory preference for treatment as a principal element.

Because this Remedy will not result in hazardous substances remaining on-Site above health-based levels that
allow for unlimited use and unrestricted exposure, a five-year review will not be required for this remedial
action.

ROD DATA CERTIFICATION CHECKLIST

The following information is included in the Decision Summary section of this Record of Decision.  Additional
information can be found in the Administrative Record file for this Site.

        •       Chemicals of Concern (COCs) and their respective concentrations;
        •       Baseline risk represented by the COCs;
        •       Cleanup  levels established for COCs and the basis for the levels;
        •       Current  and future land and ground-water use assumptions  used in the baseline  risk
               assessment and ROD;
               Land use that will be available at the Site as a result of the Selected Remedy;
        •       Estimated capital, operation and maintenance O&M), and total present worth costs; discount
               rate; and the number of years over which the Remedy cost estimates are projected; and
        •       Decisive factors that led to selecting the Remedy (i.e., description of how the Selected Remedy
               provides  the best balance of tradeoffs with respect to the balancing and modifying criteria).
        Date                                Richard D. Green,  Director
                                            Waste Management Division
                                          Declaration - 2

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
2.0 DECISION SUMMARY
2.1 SITE NAME, LOCATION, AND DESCRIPTION
The RM facility is located at 100 North Railroad Street in Rossville, Fayette County, Tennessee, (see
Figure 2-1). The facility's geographic coordinates are 35°02' 57" North latitude and 89° 32' 55" West
longitude, as  shown on the U.S. Geological Survey (USGS) topographic map quadrangle for
Rossville, Tennessee (U.S. Geological Survey [USGS] 1965).  The Site includes contaminated
wetlands to the north and northeast of the process area and the landfill. It is bordered by residential
property to the east, the Southern Railroad tracks to the south, and a municipal wastewater treatment
plant to the west.  A Site layout is presented in Figure 2-2.

2.2 SITE HISTORY AND ENFORCEMENT ACTIVITIES

From 1978 until June 20,1992, RM operated a secondary lead smelter at the Site. Prior to 1978, the
property was undeveloped.  RM produced specification alloyed lead that was sold for use  in
manufacturing  vehicle batteries, lead shot  pellets, and  sheet  lead (radiation shields)  (Ogden
Environmental Energy Services Company [Ogden] 1994). The facility  received spent lead acid
batteries, spent lead plates, lead oxide, scrap metal, and other lead waste and material from various
businesses and industries, including battery crackers and battery manufacturers. The primary material
used for the recycling process was spent lead acid batteries, with automotive and industrial batteries
accounting for 80 percent of the raw material processed. The remaining 20 percent consisted of other
 lead-bearing  materials, such as recycled dross, dust slag, and factory scrap.  Facility operations
 included not  only the smelting of lead and other scrap metals but a variety of other products, such as
 crushed drums, limestone, steel, and cast iron.  These materials were added to the blast furnace as
 flux to create a reducing atmosphere. Wastes generated from the process included slag, plastic chips,
 waste acid, lead emission control dusts, and lead-contaminated stormwater (Black & Veach Waste
 Science, Inc. [B&V] 1996).
                                            -1-

-------
NMfinphis



  Not to Scale
           Chattanooga
                             Ross Metals  Site
                               Rossville, TN
       Federal Programs Corporation
4 tabtUtv otcunp Dmitri UcKmlx.
                                               Site Location
                                                                                 Figure No.:

                                                                                     2-1
                                                                                    10/98

-------
                      ill
                                                                    ill
                    BLAST SLAG MONOFILL
                      8" CONCRETE
                         SLAB
                                     NORTH STORM WATER
                                     COLLECTION SUMf»
SLAG
FIXATION
CONTAINER
                                2 BAG
                                HOUSE
                                   4 BAG
                                   HOUSE
                 CENTRALv
                 FACILITY t3
                                              WASTE WATER
                                              TREATMENT
                                              CENTER
                        FURNACE
                    RAW MATERIALS
                        REFINERY
                                EAST STORM WATER
                                COLLECTION SUMP
                                                                               LANDFILL AREA

                                                                               FEN CELINE

                                                                               WETLAND AREA
                                                                                          240'
                                                                       SCALE IN  FEET
       Ross  Metals  Site
     Rossville,  Tennessee
CDM Federal Programs  Corporation
A tutoUay el Canp f\tn* t I'rn Hie.
                                                      Site  Layout
                                                                                   Figure No.

                                                                                      2-2
                                                                                        7/98

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
Upon receipt, batteries were stored on pallets located east and southeast of the facility; each pallet
held about 50 batteries. The batteries were then conveyed to the wrecker building for the battery
breaking operation. Wastewater used for battery breaking operations conducted inside the wrecker
building was managed by an on-Site wastewater treatment system. Water was used to separate lead
from other battery components based on its density. After separation, lead was transported to the
blast furnace slag area, where lead materials were passed through a smelter.  According to facility
representatives, 99 to 99.5 percent of the lead content was recovered. The molten lead product was
then moved to the refinery area. The refinery area consisted of four kettles that received molten lead
and formed ingots. The ingots were then moved to the finished storage area until they were shipped
to customers (B&V 1996).

Acid and sludge obtained during the battery breaking operation contained residual amounts of lead
and lead acid; the acid and  sludge were transferred to the wastewater treatment unit to reclaim the
remaining lead. Lead was reclaimed by allowing it to settle further in aboveground collection tanks.
This lead sludge, collected prior  to neutralization, was transferred to the blast furnace area and
immediately fed into the furnace. The remaining acid was neutralized with liquid caustic soda. Upon
neutralization, the solution was held for  additional settling to precipitate dissolved metals.  Sludge
resulting from the neutralization process was  also collected in settling tanks and recycled into the
blast furnace with other lead scrap. The pH of the waste stream generated by the facility was further
adjusted, and sludge-free effluent was discharged to the Rossville Municipal Sewage Treatment
Facility (Tibbels 1983).

Several areas of the operating facility contained large volumes of lead-bearing materials.  With the
exception of the container storage area, the lead-bearing materials were not containerized; instead,
they were placed on the asphalt foundation of the facility or directly on facility soils.

From 1979 until December 1988, blast slag that had accumulated as a part of the smelting process

                                            -4-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
was disposed of in an on-Site landfill.  On November 3, 1986, RM  submitted a petition for
registration for an existing industrial landfill used to dispose of blast furnace slag; RM considered the
slag a nonhazardous industrial waste.  On November 8,  1988, RM submitted a RCRA Part B
application stating tbat slag had been deposited on Site. Diagrams included in the application show
slag piles both inside and outside of the area designated as the landfill. EPA's RCRA Compliance
Section conducted a sampling investigation on December 7,1988, to determine if the waste generated
at the facility should be regulated. On December 20,1988, the Tennessee Department of Health and
Environment (TDHE) suspended all further processing of the request until  results from the EPA
sampling event could be assessed  and the EPA could determine whether the blast 'slag was a
nonhazardous waste (B&V 1996).  Several references in the EPA files for the RM Site debate the
status of blast slag as a hazardous waste. File material also indicates that on April 20, 1990, RM
applied for a solid waste classification variance for the blast slag. RCRA also conducted a sampling
investigation on May 9, 1990, to determine if smelting and landfilling activities at the facility were
causing adverse environmental impacts.  The variance was denied on June 6, 1990, because EPA
determined that blast slag was a hazardous waste and subject to the full extent of RCRA regulations.

In September of 1990, RCRA issued a Complaint and Compliance Order against Ross Metals. After
several months  of extensive negotiations, the parties reached an agreement to settle the case.
However, the company never  signed the Consent Agreement, because of its precarious financial
condition. In 1992, Ross Metals,  Inc. received an Administrative Dissolution under Articles of
Incorporation. There is no known  successor entity. Because of this, all State and Federal RCRA
enforcement actions at the Site ceased.

Once negotiations failed with  Ross Metals and all operations ceased at the facility, the  Site was
referred to EPA's ERRB. In a letter dated October 25,1993, ERRB notified TDEC that the Site was
eligible for a removal action. Prior to any ERRB clean-up  activities, TDEC  was approached by an
interested third party, Greyhound Finance Services (GFS), regarding the possible clean-up of the Site.

                                          -5-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
EPA and TDEC decided a State Lead RCRA Closure performed by GFS would be beneficial to all
parties.  An agreement concerning the RCRA Closure was never reached, therefore the Site was
referred back to ERRB in June of 1994.

On June 15, 1994, ERRB conducted a Site visit. Based upon ERRB's file review and Site visit, the
Ross Metals Site met the criteria for a high priority removal action. The removal action began in
September 1994 and was completed in June 1995.  The removal consisted of segregating, staging,
or removing forty-six wastestreams. The wastestreams, descriptions, and approximate volumes of
each is listed in the Tables 2-1 and 2-2.

Approximately 6,000 cubic yards (CY) of lead bearing blast slag was staged in on-Site buildings. The
removal action was completed in August 1995. During the removal action, EPA was also conducting
a Site investigation for the NPL listing process. In October 1996, the North Site Management Branch
began remedial investigations. The Site was listed on the final National Priorities List March 31,
1997.

An Engineering Evaluation/Cost Analysis (EE/CA) was finalized  in February 1998. In considering
the information presented in the EE/CA and the statutory limits which apply to non-time critical
removal actions,  EPA determined that  a Remedial Investigation/Feasibility Study Report that
develops appropriate remedial action alternatives was needed for this Site.

On March 24th, 1998, EPA sent general notice letters to the Potentially Responsible Parties (PRPs).

The threat of human exposure and reports of trespassing caused EPA to perform a removal action
in June and September of 1998. About 10,000 CY of slag are landfilied in an unlined and unsecured
area located just north of the facility process area. About 6,000 CY of stockpiled lead slag material
are still stored at the facility inside deteriorating sheet metal buildings. The buildings are no longer

                                           -6-

-------
:'"'"1 "''%, "}'<<',*?,"'*': , '^^^/^^^^Oia^^9^^^^^€^^St "<
Quantity Removed

Not Applicable







230 cubic yards
2 each
371 gallons
Not Applicable



850 cubic yards


88 containers
20 cubic yards
17 cubic yards

Dates Removed

9/26-10/10/94







10/3 - 12/20/94
10/21/94
10/25/94
10/31/94



11/05-11/18/94


11/11/94
11/30/94
12/12/94

Type of Waste Removed
c
battery cracking
equipment; ingot casting
conveyor, baghouse
blower, 1 7 colling
crucibles, battery saw,
conveyor belt, tumbler
and associated
framework.
construction-type debris
baghouses
diesel fuel
baghouse equipment:
baghouse frame and
associated ductwork,
screen
conveyor, cross members,
catwalk and ladder, scrap
metal
laboratory chemicals
old tires
soda ash


Type of Disposal
Facility
Reclamation Facility







Landfill
Reclamation Facility
Reclamation Facility
Reclamation Facility



Recycling Facility


Facility Local
High School Local
Landfill Recycling
Facility
-7-

-------
- S# V*J ss&*ik S^JW?;^ ^ 5? r$ $|
Quantity Removed
250 cubic yards
34,430 Ibs
288 cubic yards
307,220 Ibs
330 gallons
330 gallons
90 gallons
110 gallons
3500 gallons

Dates Removed
11/14-11/15/94
12/02 - 12/12/94
12/08 - 12/19/94
12/12 - 12/21/94
12/16/94
12/16/94
12/16/94
12/16/94
12/16/94
d^»^dtCS6^te' ^''/* "?->.
Type of Waste Removed
battery chips/leaded
debris
leaded tank sludges
((D008.D006)
leaded debris; debris,
soil, floor dust, rags,
PPE, cinderblocks
(D008)
raw materials
(K069.D008)
base-neutral liquid
motor oil
hydrochloric acid
sodium hydroxide
sodium hydroxide

Type of Disposal
Facility
Regional TSDF
Local TSDF
Regional TSDF
Reclamation Facility
Local TSDF
Local TSDF
Local TSDF
Local TSDF
Local TSDF
-8-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
providing protection from weather conditions because of deterioration.  Data collected in the
investigation revealed lead-contaminated surface soils (outside the fenced facility - approximately 8.58
acres). This area is adjacent to residential property and is located within a designated wetland. The
removal action consisted of placing tarpaulins over the 6,000 CY of stockpiled lead slag and installing
security fencing around the contaminated surface soils and landfill.

The Remedial Investigation/Feasibility Study was finalized in November 1998

2.3 HIGHLIGHTS OF COMMUNITY PARTICIPATION

Local officials have said that area residents have been fairly quiet about the presence of an NPL Site
in the community. A Fayette County Health Department representative said they have received very
few questions regarding health concerns.

A Fact Sheet was issued January 1997, prior to a Public Availability Session, which was conducted
by EPA and the Tennessee Department of Environment and Conservation. The Availability Session
was conducted January 6,1997. No citizens attended.

A fact sheet was released immediately after the Site was placed on the NPL. The Site was placed on
the NPL on March 31, 1997.

The Agency for Toxic Substances and Disease Registry (ATSDR), after reviewing the available
environmental data suggested that people were possibly exposed to metals in on-Site and off-Site
 surface soils and water. Therefore, ATSDR decided to conduct an Exposure Investigation (El) to
 determine the lead level present in the soil of the adjacent residences and offered blood-lead level
 testing to the residents adjacent to the Site. The El also included soil and dust testing for lead in
 residential areas. The El conducted was to investigate a possible public health problem and develop
                                            -9-

-------
                                                                       Record of Decision
                                                                       Ross Metals OU#1
plans for its control.

Following the issuance of notices to Potentially Responsible Parties (PRPs), EPA held an
informational public meeting on April 14, 1998.  During that meeting, citizens were encouraged to
form a Community Advisory Group (CAG).

ATSDR held a community meeting with residents of Railroad Street to explain the purpose of the El
on April 21, 1998.  Prior to the community meeting, ATSDR distributed flyers throughout the
community and coordinated media outreach with local newspapers in the area. In conjunction with
the Tennessee Department of Environment and Conservation, ATSDR collected blood, soil and wipe
samples from identified residents on May 30, 1998.

The Rossville CAG, composed of approximately 10 citizens, met for the first time in May 1998. The
CAG meets the first Tuesday of each month, as needed. Their mission statement is "The Rossville
Community Advisory Group exists to insure that the cleanup of the Ross Metals Superfund Site
protects human health and the environment."

A Proposed Plan Fact Sheet was released to the public which described EPA's preferred remedial
alternative and invited public comments about the alternatives. The Administrative Record file was
made available November 18,1998.  The file can be found at the information repository maintained
at the EPA Docket Room in Region 4 and Rossville City Hall.  The Notice of Availability of these
two documents was published in the Commercial Appeal on November 18,1998. A public comment
period was held from November 18, 1998  to  December 18, 1998.  An extension to the public
comment period was requested.  As a result, it was extended to January 19, 1998. In addition, a
public meeting was held on November 30,1998 to present the Proposed Plan to a broader community
audiences than those that had already been involved  at the Site. At this meeting, the Tennessee
Department of Environment and Conservation answered questions about problems at the Site and the
                                          -10-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
remedial alternatives. EPA also used this meeting to solicit a wider cross-section of community input
on the reasonably anticipated future land use. Public comments were received during this period.
A transcript of the public meeting is included in the Responsiveness Summary, which is part of this
ROD.

This decision document presents the selected remedial action for the Ross Metals OU#1 in Fayette
County Tennessee. The  remedial action chosen,  is in accordance with CERCLA, as amended by
SARA, and, to the extent practicable, the National Contingency Plan. The decision for this  Site is
based on the Administrative Record.

2.4  SCOPE AND ROLE OF OPERABLE UNIT

As with many Superfirad sites, the problems at the Ross Metals OU #1 are complex. As a result,
EPA organized the work into two operable units  (OUs). These are:

•       OU #1:  Contamination in the source materials.
•       OU#2:  Contamination in the aquifer.

The scope of this response action is to cleanup contaminated soil, wetlands, buildings and  waste.
Incidental ingestion of soil and the physical hazards pose the major risks to human health. Sediment
poses an acute risk to ecological receptors.  The cleanup  of the source materials is proposed to
prevent exposure to contaminated source materials and prevent contamination of groundwater and
surface water. This response action is the first of two operable units that will be used to address the
 contamination of the entire Site.
                                          -11-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
Operable Unit #1 will address:

       •      Waste Slag (landfilled and stockpiled)
       •      Contaminated soil (in facility area and landfill area)
       •      Buildings
       •      Demolition debris (pavement)
       •      Contaminated sediment (in wetlands)

EPA generally expects  to use treatment to address principal threats posed by a site, wherever
practicable.  Principal threat wastes are those source materials considered highly toxic or mobile that
cannot be reliably contained or would present a significant risk to human health or the environment
should exposure occur.  For the Ross Metals Site, principal threat wastes conservatively include
approximately:

       •      600 cubic yards of soil
       •      8,200 cubic yards of sediment
       •      6,000 cubic yards of stockpiled slag
       •      10,000 cubic yards of landfilled slag

Operable Unit #2 will require additional Site characterization studies in order to determine the nature
and extent of potential groundwater contamination. A Feasibility Study may be required to identify
and evaluate possible groundwater remedial actions.
                                            -12-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
2.5 SITE CHARACTERISTICS

2.5.1  Land Use

The area surrounding the Site is primarily rural or residential. A municipal wastewater treatment
plant is located adjacent to the western Site boundary, and no other known industries would have
contributed contamination to the Site. The towns of Rossville, Rossville Junction, and New Bethel
are located within a 4-mile radius of the Site; the total population within the 4-mile radius is 1,947.
The nearest school is located 0.3 miles southeast of the Site.

Current and reasonably anticipated future land uses and current and potential beneficial ground-water
uses are discussed in Sections 2.6.1.2 and 2.6.1.5.

2.5.2 Climatology

The RM Site is located in southwest Tennessee, about 30 miles west of Memphis. This area has an
average annual daily temperature of about  62.3 ° F.  The normal daily minimum and  maximum
temperatures are 52.4 °F and 72.1 °F, respectively.  Annual precipitation is 52.10 inches.  (Source:
National Weather Service Historic Data for Memphis,  1961-1990).

2.5.3 Physiography

The RM Site is located in the Gulf Coast Plain Physiographic Province of western Tennessee, which
is characterized  by  unconsolidated near-surface sands, silts, and clays.   Elevations within the
surrounding area vary from 290 to 470  feet National Geodetic Vertical Datum (NGVD) (USGS
1965). Ground elevations within the Site boundaries range from about 315 NGVD near the main
office building to about 310 NGVD at the northeast corner of the fenced portion of the Site. The RM
                                          -13-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
Site is located about 0.5 miles south of the Wolf River.

The RM Site consists of an old fenced facility area enclosing about 5.5 acres and a blast slag landfill
covering about 2.5 acres north of the old fenced area, and contaminated wetlands located north and
east of the facility and landfill areas, approximately 8.58 acres.  The fenced area includes several
buildings, most of which are constructed of sheet metal. Most of the area inside the fenced facility
area is paved with either concrete or asphalt, and an asphalt curb is.located just inside the fence. The
curb was apparently constructed to divert storm water runoff to the storm water collection sump in
the northeast corner of the property. Several stockpiles of waste slag are located in various buildings,
including the wrecker building, the slag fixation container, the furnace raw materials refinery building,
and the shipment building. The buildings are generally in poor condition, and some are in danger of
collapsing.

The landfill area was constructed in a wetland area north of the fenced area.  Several soil-covered
mounds ranging up to 6 feet high are located in the landfill area. An 8-inch-thick concrete slab is
located just north of the gate in the landfill area; however, evidence suggests that some slag may be
buried beneath the concrete slab. An estimated 10,000 CY of slag is buried throughout the landfill
at thicknesses of up to about 4 feet. About 1 to 2 feet of fill material has been placed over the slag
throughout the landfill.

As indicated on Figure 2-3, the RM facility and the wetlands north and east of the facility are located
in a 100-year floodplain. Figure 2-4 illustrates the type of wetlands that are part of the RM Site.

2.5.4  Surface Water

Storm water runoff from the entire facility drains into a basin located at the northeastern corner of
the fenced facility. The basin discharged to a small wetland area  located north and northeast of the
                                            -14-

-------
 APPROXIMATE LOCATION
     ROSS METALS, INC.
   Legend:
            100 Year Flood
   NOTES:

   1.   Flooding effects from Wolf River

   2.   Flood information taken from Flood
        Insurance Rate Map for the town of
        Rossville, Fayette County, Tennessee.
                      O1
Scale
 250'
500'
       Ross Metals Site
         RossviUe,  TN
       Federal FVograms Corporation
A iutwM»y of Ctmp Dauar t UcKoa Inc.
100 Year Flood
   Plain Map
     Figure No

         2-3
                                    10/98

-------
                                           liond Community T>p«

                                    U,V)  Scrub/Shrub

                                      Zj  £>nergent

                                         3rood-L«ov4d Deeiduout Forest
                                    ED  -Jcea<-L«ovi(i Deciuuous
                                         -Bold Cvpr«3i Forest
                                 GRAPHIC  SCALE
                        «»      .-0     100    XO
     Ross Metals Site
   Rossville, Tennessee
                                       wetlands Delineation
CDM Federal Pro|rtm9 Corporktioa

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
facility area. During an inspection on October 14, 1993, the holding dike of the storm water basin
was observed to be overflowing, and storm water was apparently not being collected in on-Site
storage tanks for wastewater treatment. Runoff from the landfill also drained to the wetland located
north and northeast of the landfill; in addition, the landfill has no documented run-on, run-off, or
collection facilities. The landfill is documented to lie  adjacent to a wetland area; however, the
wetlands are not delineated on the National Wetland Inventory (NWI) map.

The wetlands and wooded area extend to the north and ultimately drain to the Wolf River, which is
the main drainage body for the region. The Wolf River flows west, through Memphis, and into the
Mississippi River.

The Rossville municipal wastewater treatment plant is located west of the RM Site. The outfall for
the treatment plant is located on the Wolf River at the Highway 194 bridge, about 1.5 miles upstream
of the facility. The outfall and the treatment plant are not expected to have any adverse effect on the
wetland located north and northeast of the Site.

2.5.5 Geology and Hydrogeology

The Site is located in the Gulf Coast Plain Physiographic Province of Western Tennessee, which is
characterized by unconsolidated near-surface sands, silts, and clays.  Included in this sequence of
unconsolidated sediments is the Memphis Sand, which  contains an important water-bearing zone
known as the Memphis aquifer.  The Memphis Sand consists of a thick body of sand that contains
clay and silt lenses or beds at various horizons. The sand ranges from very fine to very coarse (B&V
1996). A regional cross-section is provided as Figure 2-5.

Recharge of the Memphis aquifer generally occurs along the outcrop of the Memphis Sand.  Recharge
results from precipitation and from downward infiltration of water from the overlying fluvial deposits
                                           -17-

-------
             Sboby County    LHIaCvpww loowrratcWa Rfcer
             fcyetl* County     canal      canal
        Low* and fluvial dtpeiiU     /Wuvfum      ro:0-32
     Ross  Metals Site
    Rossvffle, Tennessee
COM Federal Programs Corporation
                                       Regional  Cross-Section
Figure No.

    2-5
                                                                                  9/98

-------
                                                                          Record of Decision
                      	^	    •	Ross Metals OU#1
and alluvium, where present. In the outcrop-recharge belt, the Memphis aquifer is under water-table
conditions (unconfined), and the configuration of the potentiometric surface is complex and generally
conforms to the topography.  West of the outcrop-recharge belt, the aquifer is confined by other
members of the Claiborne Group  containing clay, silt, sand, and lignite.   Groundwater  in the
unconfined portion of the Memphis aquifer typically flows to the west. Transmissivities  of the
Memphis aquifer in the Memphis area range from about 20,000 to 42,800 square feet per day.
However, USGS literature referenced only one test conducted in Fayette County (the location of the
RM facility); the test indicated a transmissivity of 2,700 square feet per day. (B&V 1996).

The RM facility was constructed in part of a wetland; RM reportedly spread and compacted several
feet of clay prior to constructing the facility. A1987 memorandum written by the State of Tennessee
indicates that clayey silt was present in the area of the industrial landfill before its construction; the
clayey silt was present from 0 to 3 feet, and a silty clay was present from about 3 to 7 feet.

In May 1988,  five monitoring wells  were  installed by RM's contractor.  The borings for the
monitoring wells indicated the presence of about 11 feet of silty clay and  clayey silt overlying sands
of the Memphis Sand aquifer. In May 1997, eight additional monitoring  wells were installed at the
Site.  A soil boring (T-4) was also drilled in the southwest comer of the Site, but it was not completed
as a monitoring well.  Monitoring well depths ranged from 23 to 28 feet below ground surface (bgs).

 Soil samples collected during soil boring activities revealed that Site stratigraphy conformed generally
 to the May 1988  data collected by the RM contractor.  The predominant  soil type observed in
 surficial to shallow soil intervals (within 10 feet bgs) consists of gray, mottled, dry to moist clay. The
 clay unit contains a high percentage of silt (except in the western portion of the Site, where it grades
 to sandy clay); exhibits low plasticity and variable organic content; and occasionally exhibits a brown
 to tan coloration.  The clay unit extends from ground surface to depths ranging from 7 to 20 feet bgs
 and is generally thickest in the western portion of the Site.
                                            -19-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
Sands encountered at the Site are fine-grained and grayish-white in color. Sands are generally well
sorted and exhibit a fine to medium texture with occasional clay lenses and very little silt.  Sand
textures generally coarsen with increasing depth, becoming mediumto coarse in texture below 20 feet
bgs. A trend toward a decrease in the degree of sorting and an increase in the coarse sand fraction
was also observed in samples collected from below 20 feet bgs.

Groundwater at the Site is encountered in the upper portion of the sand section.  The aquifer
possesses a degree of hydrologic confinement due to the pervasive upper clay section, and water
levels in Site monitoring wells rise above the base of the clay unit.

Information collected during the 1988 and 1997 investigations conducted by the RM contractor and
PRC, respectively, conflict somewhat with a Tennessee memorandum written in 1987 concerning the
actual depth of clay beneath the Site. However, it can be assumed that at least 7 feet of silty clay and
clayey silt are present directly under the Site; it remains undetermined how much, if any, of it is native
material. Some of the clay may be part of the base of the Cook Mountain Formation or a clay lens
within the upper part of the Memphis Sand. Occurrences of the overlying members of the Claiborae
Group in the area of the Site may be thin or absent above the Memphis Sand.  Figures 2-6 and 2-7
present cross-section information obtained from the EPA Site investigations.  Additional cross-
sections were prepared for this RI/FS report using boring logs from monitor wells constructed in
1997.  The  1997 boring cross-section locations are illustrated on Figure 2-8. The 1997 cross-
sections are presented on Figures 2-9 and 2-10.

Although regional groundwater flows to the west, measurements collected fromSite monitoring wells
in 1990 indicate that shallow groundwater movement is north towards the Wolf River. However,
measurements collected from the monitoring wells in 1996 suggest a more northwesterly movement
of groundwater. Figures 2-11 and 2-12 present groundwater flow based on measurements collected
in an October 1990 investigation, and November 1996 investigation, respectively.  Two municipal
                                          -20-

-------
                      BLAST SLAO MONOFI
                                    NORTH STORM WATER
                                    COLLECTION SUM?-,
SLAG
FIXATION
CONTAINER
                          OUST 12
                         FURNACE IHOU
                                               WA
                                           HOLDING
                                           TANKS

                                           WASTE WATER
                                        O *•! TREATMENT
                                           CENTER
                   FURNACE
                 RAW MATERIALS
                   REFINERY
                                EAST STORM
                                COLLECTION
                                                                    LEGEND
0            150'
                   300'
       SCALE  IN FEET
'A CROSS SECTION
   LOCATION

5  TEMPORARY WELLS

>  MONITOR WELL
   LOCATION

— LANDFILL AREA

—- FENCELINE

   WETLAND AREA
        Ross Metals Site
      Rossville,  Tennessee
CDM Federal Programs Corporation
A Kttifay cf Camp Dnmr * HcX* tic.
                                              Cross—Section Locations
                                                                            Figure No

                                                                                2-6
                                                                                        7/98

-------
*CAD FILE. ROSS\CS-M
< °


=10



*~ f—
LO ,„
         o
         o
 II
 r£
 »5>
  •B
   CO
   O

   I
   o
         M
           S3
        S w
        ^ ^
        S *
        CD
      O
      w
      CO


      W
      (6
      O
      r*
      »^-
      O
      P
      CO
     ra
      I
     03
      ro
                  ho
                  O
                         ELEVATION  IN FEET


                                  3
                          cn
                                I
                                           m

                                           m
                                           z
                                           o
                       5  =£
                       >  X

                       m  =|
m


>
z
o


o
                                       O
               ^ cn
                O
                                                                   ELEVATION^IN FEET

                                                                    U<	O	O)

-------
   LEGEND



  J),  TEMPORARY 'WELLS



  J»,  MONITOR WELLS



  	LANDFILL AREA


  —-  FENCEUNE


  •*•  WETLAND AREA



  K%/J REMOVAL AREA
                  200'
SCALE IN FEET
     Boas  Metals Site

   Rossville,  Tennessee
COM Federal Pruranu C»n>oi.Uo»
   »  iw       ^
                                               Cross  Section  Locations—1997 Borings
                      Figure No.


                         2-8



                        8/98

-------

g
0 £
p»"55ji« 	


	 10

	 20
	 25
A
T4






/
/
/
/
t
\
/
•rX
/
/
/
/
/
i
1
>0' 100'
-i i
HORIZONTAL SCALE
                                             WW16
BX°XoXOr
3^^^fe444^/^2J
£J-~S£f?Sf-^W^~*?:^fSjS£2
                                                     • ' >. V .:..'.''-Ml-;"'-;."'"-."\',-.
                                                     ."*"•."''''.»''. k..' ' .".'... "*•/ ''".'
                                                     •:,4-. *; -•'••:•.- ,•• . •-
                                                     ;••>.;-..;:V--"'V-:'^'•'"•' ''.^"-•

                                                     ';"••'-'/'"j-.--^'>.;'-»- [:\::^ ;: \. VC .:.-/:-J-" S ^" V
             Ross Metals  Site
           Rossville,  Tennessee
      COM Federal Proerams Corporation
      A MMfay «/ Carp Dnmr * HcXtt *t
                                           Cross  Section A-A',  1997 Borings
Figure No.
 2-9
                                                                                         8/98

-------
                          •ft,
hi

c
0     5Q'   100'
         =a
         HORIZONTAL SCALE
                                               Ross  Metals  Site

                                              Rossville,  Tennessee
CDM Federal Programs Corporation
4 K&tay ef Cmp Onatr t Ucftt tot
                                                                                                                CLAYEY SAND
                                                                                                                ORGANIC LAYER
                                    Cross  Section  B-B',  1997 Borings
                                                                                                                    Figure Ho.

                                                                                                                     2-10
                                                                                                                         8/98

-------
         SLAG
         FIXATION
         CONTAINER
      NORTH STORM WATER
      COUECTICN SUMR-
                                       3O&3
                                      2 BAG
                                      HOUSE
  2 BAG
  HOUSE
     4BAG
     HOUSE  ._ .
             TORU WA
     __,,-. .-.'HOLDING
     O O OO TANKS

           ..WASTE WATER
                         FURNACE
                       RAW MATERIALS
                         REFINERY
            I TREATMENT
            CENTER
                                                                      503
                                                                     308.5
                                                                   309
              150'
              ES
         SCALE  IN FEET
300'
       Ross Metals Site
     Ross-ville,  Tennessee
COM Federal Programs Corporation
* ***fay if Coop Cnatr * IttW he
GROUNDWATER CONTOUR  LINE

GROUNDWATER ELEVATION

MONITOR WELL LOCATION

LANDFILL AREA

FENCELINE

WETLAND AREA
           Potentiometric Surface  Map
                  October  1.  1990
                      Figure  No

                        2-11
                                                                               7/98

-------

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
supply wells and three industrial production wells are located within 0.75 mile of the Site and are
screened in the Memphis aquifer.

2.5.6 Previous Investigations

EPA has conducted numerous sampling investigations at the RM Site. A discussion of sample results
from these investigations is presented in Section 2.5.7.

In May and November 1990, EPA Region 4 conducted RCRA investigations that included the
collection of groundwater, surface water, surface soil, and slag samples.

From September 22 through December 29, 1994, the EPA Emergency Response and Removal
Branch (ERRB) conducted an emergency time-critical removal of hazardous substances at the RM
Site. Source materials, structures, and debris were removed and disposed of off Site. Approximately
4,400 gallons, 170 tons, and 1,700 CY of waste were removed. Groundwater and surface soil
samples were also collected during this event.

During the week of June 13,1995, EPA conducted a Site Investigation for Hazard Ranking System
purposes.  Groundwater, surface and subsurface soil, sediment, and surface water samples were
collected.

In November 1996, EPA conducted site characterization studies that included surface and subsurface
soil, groundwater, surface water, and wipe samples from the buildings.

During the weeks of May 19 and May 26,1997, EPA conducted additional field sampling at the Site.
EPA completed the installation and sampling of nine monitoring wells, including borehole soil
sampling.  Two additional groundwater samples were collected from on-Site temporary wells, and
                                          -28-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
one groundwater sample was collected from a well at the wastewater treatment plant on adjacent
property located west of the RM Site.  Soil samples from the landfill and a composite sample of slag
stockpiles were also collected for analysis.               ,

The presence of lead-based paint in homes near the Site has been documented. File material indicates
that children living near the Site have had elevated levels of lead in their blood.  The children were
moved by Housing and Urban Development.  Although the documentation is not strong enough to
establish an observed release,  the findings are significant because  of the proximity of adjacent
residences and the history of the RM Site.    Soil samples collected adjacent to nearby homes
indicated 1,170 parts per million (ppm) of lead. An EPA time-critical removal (1994) of soils was
performed at this residence.

In April 1997, EPA collected surface water, sediment, plant tissue, grasshopper, and frog tissue
samples as part of the completion of an ecological risk assessment for the Site. All the sediment
samples were analyzed for arsenic, cadmium, copper, and lead via field portable x-ray fluorescence
(XRF). In addition, several of the surface water and sediment samples collected for the ecological
risk assessment were analyzed for TAL metals by an offsite laboratory.  Samples from two of the
surface water and sediment locations analyzed for TAL metals also were analyzed for volatile organic
compounds (VOCs), base neutral acids (BNAs) and pesticide/PCBs. Surface water and sediment
results are discussed in Section 2.5.7.1 and 2.5.7.3.

In December 1997,  EPA/ERTC collected and performed on-Site analysis of soil samples for metals
contamination, to delineate contaminant levels in the wetlands. Additionally, the effort involved the
completion of treatability studies to  evaluate soil treatment, and the completion of a wetlands
excavation and revegetation plan to provide a design for wetlands restoration. Target elements were
arsenic, cadmium, lead, and zinc. A reference grid was established on the Site and surface samples
were collected at the grid nodes.  The grid included the wetlands located north and east of the Site.
                                           -29-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
The results of 29% of the samples were confirmed by Inductively Coupled Plasma (ICP) analysis.

In June and September 1998, EPA conducted a second time-critical removal.  The removal action
included  fencing the soils which contained lead above 400 ppm; covering the waste piles with
tarpaulins; and posting the Site as a Superfimd Site.

2.5.7  Nature and Extent of Contamination

2.5.7.1 Soil and Sediment

 Surface soil and sediment samples were collected at depths of up to 2 feet bgs. Lead-contaminated
surface soil is present across the  Site and in the wetlands north and east of the facility.  Lead
concentrations in most surface soil and sediment samples collected throughout the Site exceeded 400
ppm. In addition, aluminum, antimony, arsenic, barium, cadmium, copper, iron, manganese, selenium,
and vanadium were detected above risk-based remedial goal option (RGO) levels. Figure 2-13 and
2-14 illustrate the extent of surface soil lead contamination throughout the Site. Additional samples
collected as part of an ecological risk assessment and analyzed using both XRF analysis and ICP
procedures showed a widespread presence of lead and other COCs defined in the risk assessment
above  RGO  levels  in the  wetlands north and east of the Site.  Figure 2-15 illustrates lead
concentration contours in the wetlands based on XRF and TAL samples collected in December 1997.

The highest levels of subsurface soil contamination were found in two isolated locations at the Site;
east of the wrecker building, and southeast of the truck wash. Figure 2-16 illustrates the extent of
subsurface soil lead contamination at the Site. Elevated lead concentrations were collected at depths
ranging from 18 to 40 inches beneath the pavement near the wrecker building and the truck wash and
at depths of up to 5.5 feet in the landfill; however, as Figure 2-16 indicates, none of the soil samples
collected from beneath the buried slag exhibited lead concentrations in excess of the RGO level.
                                          -30-

-------
   LEGEND
            0-400  mg/kg
            >  4OO  mg/kg
            INTERPRETED  ISOCONTOUR LINE,
            400 mg/kg INTERVAL
            LEAD CONCENTRATION, mg/kg
            SOIL  SAMPLE  LOCATION
ERRB SOIL SAMPLE LOCATION
ESD SOIL SAMPLE.  PRE  '96
COMPOSITE SOIL SAMPLE. CONCENTRATION
INSIDE (ERRB SAMPLE)
COMPOSITE SOIL SAMPLE. CONCENTRATION
INSIDE (ESD SAMPLE)
PRE-REMEDIAL  SOIL SAMPLE
LANDFILL AREA
WETLAND AREA
110'
              220'
                                                                                                     SCALE  IN  FEET
      Ross Metals Site
    Rossville, Tennessee
CDM Federal Programs Corporation
- « MB**7 «/ C«v CtUBt * UlSl «c
                                                       Extent  of Lead  in Surface Soils
                                                          Figure No.
                                                             2-13
                                                                                                                    8/98

-------
                30
                                                                           N
                            .31
                                          .11
                                     .32
 U1I-S
                                                            .22
                                                           •
                                                               a 26
11*49
                    LEGEND
                    TAL ANALYSIS  SAMPLE  LOCATION
                    SAMPLE LOCATION
                    TEMPORARY WELL
                    MONITOR WELL
                    LANDFILL AREA            —
                    FENCELINE                -
                    WETLAND AREA
                    REMOVAL AREA
                      0          150'
                                 555
                            SCALE  IN  FEET
                                                                               TW-I
                                                                                «
                                                                               MW-1
                                                                               300'
      Ross Metals Site
     Rossville, Tennessee
CDM Federal Programs Corporation
-4 MMfey ef t*rf Cnatf t IkZtt he.
Maximum Lead Results in  Sediment
           (TAL Analysis  -
       Ecological Investigation)
Figure No
  2-14
                                                                            7/98

-------
                                                 LEGEND
                                               /\  Sample Location


                                                   Wetland Community Types

                                              (23  Scrub/Shrub

                                              [••Av]  Emergent

                                              l=-ll  Brood-Leaved Deciduous Forest
                                              l^^l  N«edle- Leaved Deciduous
                                                   (Bold Cypress) Forest

                                                    eod Concentration Contour (mg
                                            GRAPHIC  SCALE
                                                     100     200

                                                     J—t
                                                 Scale in Feel
     Ross  Metals  Site
   Rossville,  Tennessee
COM Federil Profrarai Corporation
J MM* * CM* 0™» A MA* at
Conlaminant Contour  in
         Wetlands
       March 1998
Figure No.

   2-15
                                                                           8/98

-------
.

	
LEGEND
EH
l-'F'M
^jjjfjffl
m
N
!
0-400 mg/kg ' • 	 INTERPRETED ISOCONTOUR LINE I
400 mg/kg INTERVAL I
40, -800 mg/kg „,. ^ CONCENTRAT|ON mg/|
-------
                                                                         Record of Decision
                                                                         Ross Metals OLF#1
In addition to soils, other solid media were sampled during previous investigations. Waste slag
samples contained total lead concentrations ranging from 18,500 to 94,800 milligrams per kilogram
(mg/kg). Total lead and TCLP lead concentrations in a floor wipe sample collected from the furnace
and raw materials refinery building were 14,700 mg/kg and 574 mg/L, respectively.
                                     .:•

2.5.7.2 Groundwater

Analytical results of groundwater samples revealed the presence of several inorganic compounds at
concentrations that either exceed the primary or secondary drinking water standards or the State of
Tennessee domestic water supply criteria. Aluminum, arsenic, barium, cadmium, chromium, iron,
lead, manganese, nickel and vanadium were detected above respective guidance concentrations and/or
RGO levels.  Lead concentrations in filtered groundwater samples ranged from nondetectable to 770
micrograms per liter (ug/1); the EPA action level for lead in groundwater is 15 wg/L.

 Using only the filtered data set from the May 1997 sampling event, it appears that groundwater lead
contamination is limited to an area just east and downgradient of the RM wrecker building. Under
this assumption, the horizontal extent of the contaminant plume is about 300  feet by 200 feet.  In
contrast, using groundwater quality data from all historic unfiltered samples, combined with unfiltered
and filtered data from the May 1997 sampling event, it could be interpreted that groundwater
contamination is Site-wide. In this case, the entire Site would be  considered a source.  Under this
assumption, the horizontal extent of the contaminant plume is at least  800 feet by 450 feet and
extends off Site.

Although EPA Region  4 policy is to use only unfiltered  sample results for  risk assessment and
determining extent of contamination, the difficulty in using the historic unfiltered sample data and
even the May 1997 unfiltered sample data is that the turbidity of these samples does not meet EPA
Region 4 Standard Operating Procedure goal of less than 10 NTU.  The results from the unfiltered
                                          -35-

-------
                                                                            Record of'Decision
                                                                            Ross Metals OU#1
  samples with high turbidity are not representative of lead concentrations in fully developed water
  supply wells because water supply wells in regular use do not produce water with high turbidity due
  to the development of a natural filter pack around the well screen (EPA 1998d). In addition, the
  results for MW5 presented on Figure 2-17 indicate that recent samples do not confirm earlier sample
  results. Reported lead concentrations declined from 500 ug/1 to 3 ug/1 in seven years. This decline
  is difficult to explain because lead is not degradable and the source has not been removed. The lower
  levels present in the more recent sampling events suggest that the earlier data may not be valid.

 The high turbidity associated with the unfiltered samples collected at the RM Site means that the
 horizontal extent of contamination remains undefined. It may be much less than the current data
 indicate. Field measurements collected during the 1997 sampling event suggest that measurements
 with acceptably low turbidity could be attained at this  Site with longer development periods.

 In addition, the vertical extent of groundwater contamination has not been determined since there are
 no deep wells or cluster wells at the Site which could be used to determine the vertical hydraulic
 gradient.  Without  this  information, vertical extent of contamination  cannot  be defined.  It is
 important to have an understanding of the vertical extent of contamination to effectively evaluate
 potential remedial alternatives to use in the remediaiton of the contamination.

 Based on the groundwater information, EPA has divided the Site into Operable Units with the source
 materials being the first Operable Unit and the groundwater being the second. Additional data will
 be necessary for defining the nature and extent of groundwater contamination.

 2.5.7.3  Surface Water

Analytical results of surface water samples revealed concentrations of several inorganic compounds
that exceeded background concentrations. Significant  inorganic contaminants included antimony,
                                           -36-

-------
                                        FURNACE
                                OKSVBRAW MATERIALS
                                        REFINERY
 LEGEND

 ffi TEMPORARY WELLS
rv-i
j» ^ONITOR WELLS

   GROJJND WATER DATA BOX, RESULTS u«/L

                     i no)
                                                   LANORLL AREA

                                                   FENCEUNE

                                                   WETLAND AREA
X - E» MOULTS
X - BO NKSU.T3
                AMY IMO)
                (MMMOI tH
   • SURFACE WATER. ESO,  ug/L Pb

  O PRE-REMED1AL SURFACE WATER SAMPLE

  ffl REMOVAL AREA
                                                                                                             100'      	200'
                                                                                                                       ••

                                                                                                       SCALE IN  FEET
NOTE;?

ESO   ENVIRONMENTAL SERVICES DMS10N
ERRB  EMERGENCY RESPONSE AND REMOVAL BRANCH
HRS   HAZARD RANKING SYSTEM
 U    UNFILTERED
 F    FILTERED
ugA   M1CROGRAMS PER LITER (UNITS FOR ALL
      WATER SAMPLES)

(*) NOTE -  TW-10 AND MW-10 SAME BORING,
SAMPLES TAKEN AT  DIFFERENT DEPTHS.
TW -  SHALLOW SAMPLE COLLECTED DURING  BORING.
MW -  WELL  SAMPLE COLLECTED AFTER COMPLETION
     Ross  Metals Site
   Rossville.  Tennessee
COM Federal PrOfrejxu Corporation
* i nij «c»»*•»•••*»*«      *^
                                                     Total Lead  Concentrations - Water
                                                                                                            Figure No.

                                                                                                              2-17


                                                                                                              7/08

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 arsenic, cadmium, iron, lead, and manganese.  Figure 2-17 and 2-18 illustrate lead concentrations

in surface water.


2.5.7.4 Contaminant Fate And Transport


Metals, notably lead, are the primary contaminants of concern (COC) associated with the Site; these

contaminants are found in soils, structures, groundwater, and surface water. These contaminants are

not typically highly mobile in the environment and move primarily by soil/sediment or wind transport.


Primary mechanisms available for contaminant transport away from the RM Site are rainwater runoff,

rainwater infiltration to groundwater, and windblown dust movement.  A conceptual site model is

presented in Figure 2-19. The following transport mechanisms have affected contaminants at the RM

Site:
              Rainwater Infiltration to Groundwater: Rain falling directly on Site or as runon
              to the Site moves through contaminated soils and structures. This water picks up
              soluble contaminants, such as metals, and during  periods of heavy rainfall, moves
              sediments containing contaminants. Most of the area is paved and a concrete curb,
              which was built some years after the facility began operation, extends around most of
              the old fenced area. However, much of the pavement is in poor condition, allowing
              water seepage at the pavement discontinuities and infiltration to  groundwater.  A
              storm water collection sump located in the northeast corner of the old fenced area,
              apparently overflows during rain events creating runoff flow at the northeast corner
              of the property. Runoff appears to continue to migrate east and northeast of the old
              fenced area, where it enters the groundwater by infiltration. Within the landfill area,
              water  flowing  through  contaminated  material  (buried  slag)  infiltrates  into
              groundwater.


              Windblown Dust Movement: The old fenced portion of the RM Site is essentially
              devoid of vegetative cover.   During dry periods,  high winds could transport
              contaminants away from the Site with windblown dust. When the facility was in
              operation, wind could have transported contaminants in air coming from the exhaust
              stack away from the Site.
                                          -38-

-------
                30
                                             11
                         KTW-10
                                       .32
                                                       \MW-7
   r
   i®
   IMW-S
                     12S
   ~i
      14
                BLAST SLAG MONOF1U.
                 •.20
                                                       19.
                                                         ..17
                                                                 i.26
                  LEGEND
                  TAL ANALYSIS SAMPLE LOCATION
                  SAMPLE LOCATION
                  TEMPORARY WELL
                  MONITOR WELL
                  LANDFILL AREA
                  FEN CELINE
                  WETLAND AREA
                  REMOVAL AREA
                   0          150'
                                                              SCALE IN FEET
                                                                                   »2e
                                                                                   .1
                                                                                 TW-1
                                                                                  «
                                                                                 MW-1
                                                                                300'
       Ross  Metals  Site
     Rossville.  Tennessee
CDM Federal Programs Corporation
A MMby ef Cam Cnttte * Uc& he.
Lead Results in Surface  Water
         (TAL Analysis  -
    Ecological Investigation)
Igure  No,
  2-18
                                                                              6/98

-------
SOUTH
 KEU.OGC'S   CITY Or
PRODUCTION ROSSWLLE
  WELL      WELLS
0«I25 gpm 0-42 9pm
















SILTY CLAY/CLAYEY SILT
Kv«=2.5 X 10 -'cm/see
n-0,42
SAND
KH-LS X 10-Jcm/aec (?) (P
Kv=2.5 X 10-* cm/see
n=0.39
1-0.0019
MEMPHIS SAND
>600' THICK
ior
LEGEND
gpm - GALLONS PER MINUTE
151' ppm - PARTS PER MILLION
cm/sec » CENTIMETER PER S
mg/L = MILLIGRAMS PER LITE
245'
•>-!*.'
09/L = MICROGRAMS PER LIT
R
       NOT TO SCALE
                                                                                                                                        NORTH
                                                                                                                               LEAD-18.500 ppm
                                                                                                                               iTCLP-TiOmgA
                                                                                    RAINFALL
                                                                                    52"/YEAR
                                                                 SURFACE DEPOSITION OF
                                                                LEAD CONTAMINATED OUST.
                                                               - SOILS. WASTE, AND SEDIMENT
                                                           PAVEMENT•


                                                         POSSIBLE	
                                                         LEACHING
                           \  [LEAD (0-6-) 63-j9iOM_pjjjj]

                          --*•. [LEAD (>6") 7j-~6oo ppm  1
                            i.\fc'"   •       •    .   .. -.-. -I
                                                                                                                                              BORING 8
                                                                                                                                   LEAD CONTAMINATED
                                                                                                                                    SOIL BELOW SLAG
                                                                                                                           GROUNDWATER FLOW
                                                                                                                          NORTH TO WOLF RIVER
                                                                     KH - HORIZONTAL HYDRAULIC CONDUCTIVITY

                                                                     Kv - VERTICAL HYDRAULIC CONDUCTIVITY

                                                                     n  - POROSITY

                                                                     I - HYDRAULIC GRADIENT
ND
                                                                          POTENTIOMETRIC SURFACE

                                                                          DEPTH AT WHICH WATER IS ENCOUNTERED

                                                                          NOT DETECTED
                                                    Ross  Metals  Site
                                                  Rossville,  Tennessee
COM Federal Programs Corporation
A xtlHay of Crnif DrKMr * Ucffi Ac.
                                                                                                 Fate  and  Transport
                                                                                                figure No.

                                                                                                 2-19
                                                                                                                                             8/98

-------
                                                                           Record of Decision
                                                      	Ross Metals OU#1

       •       Transport by Rainwater Runoff:   During rainfall, water  moves  through
              contaminated media on the Site.  Much of the storm-water runoff within the fenced
              portion of the Site is routed to the collection  sump in the northeast corner and
              discharges off Site at this location.  In addition, no stormwater collection  facilities
              exist for the landfill area, and stormwater either infiltrates to groundwater or is routed
              north and east of the landfill. Runoff to the west is prevented due to the presence of
              the City of Rossville wastewater treatment ponds.  These ponds are bermed, and
              runoff towards this area is routed north of the Site.  Runoff from the Site may carry
              contaminated soils, as well as dissolved contaminants, into the Wolf River located
              about 0.5 miles north of the Site, although no data have been collected to support this
              conclusion. The Wolf River flows west, through Memphis, and into the Mississippi
              River.

The RM facility likely released lead in spills of battery acid, metallic or oxidized lead from improper

storage or disposal of battery plates or casings, airborne fallout from the smelter, and the smelter slag.
The solubility of lead minerals and complexes increases aspH decreases (Lindsay 1979). No specific
pH data for Site soils are available; however, a sustained leak of battery acid would neutralize soil
alkalinity, lowering the soil pH and increasing lead mobility in the soil. At the RM Site, spills of
battery acid may have transported lead deep  into the soil profile and to the aquifer.


Lead was released to the environment as metallic lead or lead oxide.  Metallic lead oxidizes slowly
to lead oxide, and lead from airborne fallout  is probably released to the environment as lead oxide.
Lead oxides are relatively soluble when compared to lead sulfates, phosphates, and carbonates.  The
smelter slag contained very high concentrations of lead; however, the slag is relatively inert.


Metal mobility in soil-waste systems is determined by the type and quantity of soil surfaces present,
contaminant concentrations, concentrations of competing ions and ligands, pH, and redox status. For
this reason, the use of literature or laboratory data that do not mimic the specific Site soil and waste
system are not generally adequate to describe or predict the behavior of the contaminant.  In order
to help determine the fate of lead contamination at the RM Site, several Site fate and transport models
                                            -41-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 were completed as part of the EE/CA completed for the Site.

 A one-dimensional geochemical model was used to evaluate (1) the migration of lead in soil beneath
 the smelter slag (2) the migration of lead below the contaminated soil near the wrecker building, and
 (3) a subsurface soil removal action level. The model suggested that the slag material is a potential
 source of contamination to groundwater; because it predicted that lead will migrate to groundwater
 in six years and the concentration of lead in groundwater will exceed 15 ug/1 in 55 years. In addition
 the geochemical model suggested that soils near the wrecker building are acting as a continuing
 source of contamination to groundwater and that lead concentration in groundwater will continue to
 increase (reaching a maximum of 23,600  ug/1 in 57 years) unless the source is removed.

 AHydrologic Evaluation of Landfill Performance (HELP) quasi-two-dimensional hydrologic model
 of water movement across,  into, through, and out of landfills, coupled with the  results of the
 geochemical modeling suggest  that the construction of a geosynthetic cap will effectively eliminate
 the potential for future groundwater contamination.

 Finally, a Random-Walk model was completed to simulate the progress of remediation for the various
 remediation scenarios developed for the WHPA modeling. The Random-Walk modeling suggested
 that a 15  ug/1 groundwater action level for lead cannot be attained under a "no action" scenario.
 However, the results of the Random-Walk modeling must be considered cautiously.

 While the modeling efforts completed for the EE/CA and the RI/FS provide more Site-specific
 information regarding the  fate  and transport of lead contamination, the results should  be  used
 cautiously. The completed modeling applications are considered interpretive. Interpretive models
are useful as a framework for studying system dynamics and for analyzing flow and transport in
hypothetical or assumed hydrogeologic systems.
                                          -42-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
In addition to lead, other inorganics also were identified as human health or ecological COCs.
Aluminum's behavior in the environment depends on its chemistry and surrounding conditions. In
soils, a low pH generally results in an increase in aluminum mobility.  Plants vary in their ability to
remove aluminumfromsoils. Biomagnification of aluminumin terrestrial food chains does not appear
to occur (ASTDR 1990).

Antimony's adsorption to soil and sediment is primarily correlated  with'iron, manganese, and
aluminum content (ASTDR 1991). Antimony can be reduced and methylated by microorganisms in
anaerobic sediment, releasing volatile methylated antimony compounds into water (ASTDR 1991).

Arsenic has four valence states (-3, 0, +3, +5) but rarely occurs in its free state in nature.  Inorganic
arsenic is more mobile than organic arsenic and poses greater problems by leaching into surface
waters and groundwaters.

Lead does not magnify to a great extent in food chains.  Older organisms typically contain the highest
tissue lead levels (Eisler  1988). Plants can uptake lead through surface deposition in rain, dust, and
soil, or by uptake through roots. A plant's ability to uptake lead from soils is inversely related to soil
pH and organic matter content.

2.5.8 Treatability Studies

2.5.8.1  Dewatering Study, December 1997

A bench-scale dewatering treatability study on sediment was performed to evaluate different methods
of reducing the water content of the untreated sediments and identify a treament which would
improve the material handling qualities of the sediment such that free liquids are not released during
transport and disposal.
                                           -43-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 The results of the initial dewatering tests determined that it would be difficult to effectively dewater
 these sediments.   Silty materials have finer particle sizes resulting in less free drainage when
 dewatering.  The gravity drainage test clearly demonstrated the difficulty encountered when
 attempting to use gravity to dewater these sediments.  The  silt fines prohibited the drainage of
 significant quantities of water from the sediments.

 The most effective dewatering technique tested in terms of increasing the total solids in the sediment
 and removing the largest quantity of liquid, was filter press. The cake that resulted from the filter
 press test demonstrated why dewatering would not be the most effective treatment method for these
 sediments.  The bottom layer (closest to the filtration  device) was most effectively dewatered.
 Sediment above this layer had much higher water contents and would not have passed the liquid
 release test.  This was a demonstration that the high fines in the silty material prohibit effective
 dewatering.  In addition, the dewatering process took more than two hours using the filter press
 dewatering method.

 The Buchner funnel test demonstrated that moderate success could Likely be achieved using a belt
 filter press.  However, the percent solids in the sediment only increased to 56 percent  using this
technique (untreated sediment 46 percent solids).

If dewatering is to be  considered for sediment, additional testing using conditioning agent such as
diatomaceous earth which would enhance the dewatering process would need to be used. While
diatomaceous earth will not reduce leachability of the lead, it should enhance the release of free
liquids from the sediments.

Given the high silt contents of these sediments, consideration of stabilization of these sediments is
recommended.  The  stabilization process can be  designed  to improve  the material  handling
characteristics of the sediment and reduce teachability of the sediment. Additional testing would be
                                          -44-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
required to identify effective stabilization reagent(s).

2.5.8.2  Stabilization Study, March 1998

A stabilization study was performed to evaluate stabilization reagents that would 1) reduce the
teachability of lead in treated sediment and 2) improve the material handling qualities of the sediment
so that free liquids are not released during transport or disposal. The results of the treability study
have determined that sediment can be treated using biosolids reagent N-Viro or phosphoric acid to
reduce the teachability of lead. Treatment using N-Viro material absorbed free liquids after curing
for 5 days and resulted in a material that could be excavated and transported for disposal.

Treatment using phosphoric acid, while reducing the teachability of lead, resulted in a material with
free liquids and a noxious sulfide odor. Reduction in the addition rate of phosphoric acid did not
reduce the sulfide odor.

The teachability of lead was decreased when the lower addition rates of CKD, LKD, and Fly Ash/PC
were added to the sediment. Given the amphoteric nature of lead, it is possible that the solubility of
lead in the sediment  increased with  the higher reagent addition rates.  It  is  possible that the
teachability would be reduced further if a 5 percent or lower addition rate was used. With the high
water content in the sediment, an inert absorbent would be required along with the stabilization
reagent to improve the handling characteristics.

The results of the stabilization study have demonstrated that this treatment process will effectively
reduce the teachability of  lead and improve the handling characteristics of the  sediment.
Considerations should be given to the method which the reagent is added to the sediment (in-situ or
ex-situ) and the ultimate deposition of the treated sediment.
                                            -45-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 2.5.8.3 Biosolids Study, November 1998

 The bench-scale column treatability study was performed to evaluate different methods of reducing
 lead contamination by adding biosolids material. Results indicate the lead concentration in the liquid
 fraction decreased from 5,400 to 2,100 ppb with an increase of biosolids to sediment ratio. Greater
 than 61.1 percent of lead concentration was reduced from biosolids to sediment rations of 0:5 and
 1:4 which is less than the TCLP regulatory level [5.0 ppm ]. The lead concentration remained the
 same (2,100 ppb) for biosolids to sediment ratios of 1:4 and 2:3. For another sample, the results
 indicate the lead concentrations in the liquid fraction were 230, 530, and 440 ppb for biosolids to
 sediment ratios of 0:5, 1:4, and 2:3, respectively.  Based on this data and  the 800  ppm goal,
 application of biosolids on the sediments appears to be feasible to sorb lead that may leach from the
 contaminated wetlands. Additional studies and tests will be required for confirmation.

 2.6 SUMMARY OF SITE RISKS

 2.6.1 Human Health Risk Assessment Summary

 The primary purpose of this baseline  risk assessment (BRA)  is to provide  a quantitative and
 qualitative understanding of the actual and potential risks to human health posed by the Ross Metals
 (RM) Site if no further remediation or institutional controls are applied. The BRA consists of both
 a human health evaluation and an ecological risk assessment.

2.6.1.1  Data Evaluation

Data used in this risk assessment were obtained from the following  sources:  May and November
 1990, Environmental Services Division (BSD) Resource Conservation and Recovery Act (RCRA)
investigations; 1994 Emergency Response and Removal Branch (ERRB) investigation during a time-
                                         -46-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
critical removal action; 1995 Black & Veatch pre-remedial investigation; November 1996 ESD
investigation; May 1997 PRC investigation; and 1997 Emergency Response Team Center (ERTC)
investigation.  These data were evaluated by ESD personnel and determined to be of acceptable
quality for use in a Baseline Risk Assessment.

Because of the nature of the plant's operations, the majority of the samples were analyzed for Target
Analyte List (TAL) parameters (inorganics) only. Two samples collected by ERTC were analyzed
for the entire Target Compound List/Target Analyte List (TCL/TAL) parameters.

The laboratory results were validated by EPA Region 4 ESD personnel using standard data validation
procedures.  They concluded that with the exception of a small percentage of the data that were
rejected for a variety of technical reasons, the overall data package can be accepted with confidence.

The data were then summarized to show all inorganic and organic chemicals that were positively
identified in at least one sample. Included in this group were unqualified results and results that were
qualified with a "J" which means the  chemical was present but the concentration was estimated.
These values were listed as actual detected concentrations which may have the effect of under- or
over-estimating the actual concentration. Tentatively identified compounds (qualified with an "N")
were included if there was reason to believe that they were present. For example, if a compound was
positively identified in other locations, the tentative identification was considered sufficient.

These positively identified chemicals were then screened to exclude chemicals that, although present,
are not important in terms of potential  health effects. The screening criteria fall into three categories:

(1).    Inorganics whose maximum detected concentration did  not exceed two times the average
       background concentration were excluded;
                                           -47-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
(2).   Inorganics that are essential nutrients or are normal components of human diets were
       excluded. Calcium, magnesium, potassium, and sodium were excluded because they are
       essential nutrients, with no known toxic effects at any relevant dosage level; and

(3).   Inorganic and organic chemicals whose maximum concentration was lower than a risk-based
       concentration corresponding to an excess cancer risk level of 1 x 10"6 or a Hazard Quotient
       (HQ) level of 0.1, as determined by EPA Region 3 toxicologists using residential land use
       assumptions, were excluded (EPA 1998b).

Since the overall site risk is the sum of risks from all relevant exposure routes (inadvertent ingestion
of soil, dermal contact with soil, inhalation of dust, and ingestion of groundwater), eliminating one
or more routes has the effect of reducing the apparent risk. The groundwater data that were used in
this assessment contribute a significant degree of uncertainty to the overall assessment. Among the
factors that should be considered is the substantial difference between the  filtered and unfiltered
samples (taken at the same location and time). This difference adds to the uncertainty in the exposure
concentration and subsequent  risk estimates.  If this difference is due to turbidity, then the
concentration of lead and other COPCs would change as the turbidity changes. This would result in
an increase or decrease in the exposure concentration and resultant risk.

2.6.1.2  Exposure Pathways

The conceptual site model for this assessment is presented in Figure 2-20. As seen in this figure,
metals, notably lead, are the primary contaminants of concern (COC) associated with the Site; these
contaminants are found in soils, structures, groundwater, and surface water. These contaminants are
not typically highly mobile in the environment and move primarily by sediment or wind transport. No
specific pH data for Site soils are available; however, low pH will, in general, make metals more
soluble and, therefore, more easily transportable from the Site, and more bioavailable.
                                          -48-

-------
                                            Figure 2-20
                                       Conceptual Site Model
                                          Ross Metals Site
                                        Rossville, Tennessee
Primary
 Source
  Primary
  Release
Mechanisms
Secondary     Secondary
 Sources       Release
             Mechanisms
Migration
Pathways
Exposure       Receptors
 Routes

NA




Soil



Ingestion
Dermal
Contact


Visitor
Resident
Worker
Lead Smelter


Air Emissions,
Landfilling


Contaminated
Soil
Stormwater
Runoff or
Aquifer
Connection to
Wetland

	 ^

Surface
Water and
Sediments




Ingestion
Dermal
Contact

>


Visitor


Leaching


»

Groundwater



Ingestion
	 ^»

Resident
Worker

'Dust Generation

EI


Wind




Inhalation

'>•
Visitor
Resident
Worker

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
Based on this understanding of the fate and transport of contaminants, and the potential for human
contact, the following media/receptors were examined:

(1)    Surficial soil/sediment in the Landfill Area and Wetland/Woodland Area. Potential receptors
       are Site visitors. In the future, residents and/or workers are potential receptors in the Process
       Area and Landfill Area.
(2)    Surface water in the Wetland/Woodland Area.  Potential receptors Site visitors.
(3)    Groundwater beneath the Process Area and the Landfill Area. Potential receptors are future
       residents and/or workers.
                                                                 are:
 Potentially complete exposure pathways examined in the risk assessment

        inadvertent ingestion of soil,
        dermal contact with soil,
        inhalation of dust,
        inadvertent ingestion of surface water,
        dermal contact with surface water, and
        ingestion of groundwater.

Reasonable maximum exposure (RME) point concentrations for soil/sediment, and surface water
were calculated according to EPA Region 4 guidance using the lesser of the 95 percent upper
confidence limit (UCL)  on the arithmetic average for a lognormal distribution or the maximum
detected value (EPA 1992a and 1995a). Where a chemical of concern was not detected at a given
location, one-half the sample quantitation limit was used as a proxy concentration; however, if both
the proxy concentration and the upper confidence limit exceeded the maximum detected value, the
maximum detected value was used as  the RME concentration.   The RME concentrations for
chemicals of concern are presented in Table 2-3.
                                         -50-

-------
f
*
:5f f£S- -J£S;^S£*ii"::>;
% s Vi^'' $p$£^i$&. *f ~~ > "\
'<•> ^A'jy^VA^' r'ff
/ '''"'% -, :' ?•?'
>CH:Of :
^CteMoft ,1
^"8?l
',, Mix.';, '
s s
\
f;:^S'':^
"t ?if^: "
,% '.•£'•'
,',"' '"' ' ', '
•li
'•1§
Process Area
Soil






Antimony
Arsenic
Barium
Cadmium
Copper
Lead
Selenium
7
3
19
0.1
6
6
1
730
479
790
99
712
97,700
48
21/21
25/26
21/21
16/26
18/21
29/29
7/21
217
99
157
99
238
97,700
8
; !5:'v^<:- ." . : t'.-.-:. :v':!..-;^r !:ir ^lindMArea !..-'• " ": .. . ':.-":-
Soil





Soil










Antimony
Arsenic
Cadmium
Lead
Manganese

Aluminum
Antimony
Arsenic
Barium
Cadmium
Copper
Iron
Lead
Manganese
Selenium
Vanadium
75
8
1
35
380

3,390
1
4
53
1
8
4,790
67
25
2
10
75
76
22
42,400
1,100
and/Woodls
24,000
1,350
681
610
18
465
40,000
98,100
1,500
84
63
1/4
4/4
3/4
11/11
4/4

46/46
14/42
46/46
46/46
28/46
45/46
46/46
52/52
46/46
13/46
46/46
75
76
22
42,400
1,100

13,331
32
41
147
6
43
19,576
5,827
752
4
31
95% UCL
95% UCL
95% UCL
Max
95% UCL
Max
95% UCL

Max
Max
Max
Max
Max

95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
95% UCL
                                                                 -51-

-------
                                               Site
                                       (Cpncentratipiis m ppb)
  Surface Water
  Groundwater
 Aluminum
                  Antimony
                  Arsenic
                  Cadmium
                  Copper
                  Iron
                  Lead
                  Manganese
                  Mercury
                  Selenium
                  Thallium
                  Zinc
Aluminum
                  Arsenic
                  Barium
                  Cadmium
                  Chromium
                 Iron
                 Lead
                 Manganese
                 Nickel
                 Vanadium
 168
                   18
                  313
                   36
                  229
                  0.2
                   13
                  39
380
                  21
                   11
                  39
                 1,300
                  130
                  45
 1,300
                            150
          554
                            120
                            140
        42,700
         16,000
         5,520
          0.4
                            11
          13
          568
23,000
          40
         380
          39
        64,000
                           1,600
         5,600
         160
                           49
                                                           7/10
                       7/10
                                                           9/10
                                                           6/10
                       9/10
                                                          10/10
                                                          10/10
              10/10
               4/10
                                                          2/10
                                                          3/10
                                                          7/10
                                                          9/14
                                                          2/24
                                                          14/14
                                        3/14
                                                          1/14
                                                          10/14
                                                          18/24
              10/14
                                                          4/14
                                                          3/14
UCL: Upper Confidence Limit
Max: The highest detected concentration
Ave: Average concentration within the plume
                                                                                                      f
                                                         1,300
                                150
                                                          554
                                        120
                                140
                                                        42,700
                              16,000
                                                         5,520
                                                          0.4
                                                          13
                                                         568
                                                         2,608
                                                          20
                                                          90
                              12,126
                                       196
                                                         1,472
                                                          24
                                                                                         Max
                                                                       Max
                                                                                         Max
                                                                       Max
                                                                       Max
                                             Max
                                                                       Max
Max
                                                     Max
                                                                     95% UCL
                                                                                         Max
                                                                                        Max
                                                                                         Ave
                                                                                         Ave
                                                                                         Ave
                                                                                        Ave
                                                                                        Ave
Ave
                                                                                        Ave
                                             Ave
                                                                                        Ave
                                                                                        Ave
                                              -52-

-------
                                                                                 Record of Decision
                                                                                 Ross Metals OU#1
         2.6.1.3 Toxicity Values

*        The RfDs and CSFs used in this assessment were primarily obtained from EPA's IRIS database (EPA
         1998c).  Values that appear in IRIS have been extensively reviewed by EPA work groups and thus
         represent Agency consensus. If no values for a given compound and route of exposure were listed
         in IRIS, then EPA's HE AST (EPA 1995b) were consulted. Where no value was listed in either IRIS
         or HEAST, EPA's National Center for Environmental Assessment (formerly the Environmental
         Criteria and Assessment Office) was consulted. Tables 2-4 and 2-5 summarize the toxicity values
         for carcinogenic and non-carcinogenic COCs, respectively.

         Neither a CSF nor an RfD is available for lead. Instead, blood lead concentrations have been
         accepted as the best measure of exposure to lead. Because children are the most vulnerable to lead
         toxicity, EPA has  developed an integrated exposure uptake biokinetic model (IEUBK) to assess
         chronic, non-carcinogenic exposures of children to lead. When this model is used, and the detected
         concentrations are shown to be acceptable to the most vulnerable group in the population (children),
         it is not necessary to address adult exposure.

         To characterize risk associated with dermal exposure, the toxicity values presented in Tables 2-4 and
         2-5 were adjusted from administered to absorbed toxicity factors according to the method described
         in Appendix A to RAGS (EPA 1989a). The following oral absorption percentages were employed:
         80 percent for VOCs, 50 percent for semi-volatile organics, and 20 percent for inorganics (EPA
                                                   -53-

-------
                                                                               Record of Decision
                                                                               Ross Metals OU#1
  Aluminum
  Antimony
   NA
 20%
NA
                                          NA
                                                                        NA
                                                                     D
  Arsenic
1.5E+00 i
100%
                                              NA
                                          NA
                                        Skin
  Barium
   NA
 20%
                                             NA
                                          NA
                                                                        NA
                                                                     D
  Cadmium
  NA
 20%
                                             NA
           6.3E+00 i
                                                      Lung
                                                                                      Bl
  Chromium
  NA
20%
                                             NA
                                       4.2E+01 i
                                                                       Lung
  Copper
  NA
20%
NA
                                          NA
                                                                        NA
                                                                     D
  Iron
  NA
20%
                                             NA
                                          NA
                                                                        NA
                                                                     D
  Lead
  NA
20%
                                             NA
                                         NA
                                       Kidney
                                                                                      B2
  Manganese
  NA
20%
NA
                                         NA
                                                                        NA
                                                                     D
  Mercury
  NA
20%
NA
                                         NA
                                                                        NA
                                                                     D
  Selenium
  NA
20%
                                             NA
                                         NA
                                                                        NA
                                                                     D
  Thallium
  NA
20%
                                             NA
                                         NA
                                        NA
                                                                                      D
  Vanadium
  NA
20%
                                             NA
                                         NA
                                                                        NA
                                                                     D
 Zinc
  NA
20%
                                             NA
                                         NA
                                                                       NA
                                                                     D
Source:
 i-IRIS
CSFo - Cancer Slope Factor (oral), (mg/kg/day)-l
CSFd - Cancer Slope Factor (dermal), (mg/kg/day)-l
ABSeff- Absorption efficiency: 20% inorganics, 50%
  semivolatiles, 80% volatiles. Based on RTY policy.
CSFi - Cancer Slope Factor (inhalation), (mg/kg/day)-l
NA - Not Applicable
                                 EPA Cancer Classes

                                 A - Human carcinogen
                                 B - Probable human carcinogen
                                 C - Possible Human carcinogen
                                 D - Not classifiable as a human carcinogen
                                            -54-

-------
                                                                                        Record of Decision
                                                                                        Ross Metals OU#1
 Aluminum
 lE+OOn
20%
2E-01
   NA
     Not specified
 Antimony
 4E-04i
 20%
8E-05
   NA
Longevity, blood glucose
 Arsenic
 3E-04 i
100%
3E-04
                                                                        NA
                  Hyperpigmentation
 Barium
  7E-02i
20%
1E-02
   NA
  Incr. blood pressure
 Cadmium (water)
 5E-04i
20%
1E-04
   NA
      Proteinuria
 Cadmium (food)
  1E-03 i
20%
2E-04
   NA
      Proteinuria
 Chromium
 5E-03 i
20%
1E-03
4.2E+01 i
       NOAEL
 Copper
 4E-02 n
20%
8E-03
   NA
     Not'specified
 Iron
 3E-01 n
20%
6E-02
                                                                        NA
                       NOAEL
 Lead
   NA
20%
 NA
                                                                        NA
                   CNS effects, blood
 Manganese (soil)
 7E-02 TV
20%
1E-02
 1.43E-05
       NOAEL
 Manganese
 (water)
2.4E-02 IV
20%
                                                         NA
                                                  NA
                                  Neurotoxicity
 Mercury
  3E-04i
20%
6E-05
                                                                        NA
                    Neurortoxicity
 Selenium
  5E-03 i
20%
1E-03
   NA
   Clinical selenosis
 Thallium
  9E-05 i
20%
2E-05
   NA
 Incr. SCOT and LDH
 Vanadium
  7E-03 i
20%
1E-03
   NA
   Deer, hair cystine
 Zinc
  3E-01 i
20%
6E-02
   NA
     Deer. ESOD
Sources:
 i - IRIS
 n - NCEA (National Center for Environmental Assessment)
IV - The RfDo for manganese in IRIS is 1.4E-1 mg/kg/day based on the NOAEL of 10 mg/day. For soil exposure, Region IV policy is
to subtract the average daily dietary exposure (5 mg/d) from the NOAEL to determine a "soil" RfDo. When this is done, a "soil" RfDo
of 7E-2 mg/kg/day results.  For water exposure, a neonate is considered a sensitive receptor for the neurological effects of manganese.
Thus caution, (in the form of a modifying factor) is warranted until more data are available.  Using a modifying factor of 3 results in a
"water" RfDo of 2.4E-2 mg/kg/day.

RfDo - Reference Dose (oral), (mg/kg/day)
RfDd - Reference Dose (dermal), (mg/kg/day)
ABSeff - Absorption efficiency: 20% inorganics, 50%
  semivolatiles, 80% volatiles. Based on RTV policy.
RfDi -Reference Dose (inhalation), (mg/kg/day)
NA - Not Applicable
                                                       -55-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  1995a).  The only exception to this was for arsenic.  According to recently released EPA Region 4
  guidance, the gastrointestinal absorption rate of arsenic may be considered 100 percent (Koporec
  1998). Thus, when considering dermal exposure to arsenic, no adjustment is necessary.

  2.6.1.4  Risk Characterization

  The final step of the baseline risk assessment is the risk characterization.  Human intakes for each
  exposure  pathway  are  integrated  with  EPA reference toxicity  values  to  characterize risk.
  Carcinogenic, non-carcinogenic, and lead effects are estimated separately.

 To characterize the overallpotential for non-carcinogenic effects associated with exposure to multiple
 chemicals, EPA uses a Hazard Index (HI) approach.  This approach assumes that simultaneous
 subthreshold chronic exposures to multiple chemicals that affect the same target organ are additive
 and could result in an adverse health effect.  The HI is calculated as follows:

       Hazard Index = ADDl/EfDl + ADD2/RfD2 +...ADD/RfD,
 where: ADD; = Average Daily Dose (ADD) for the ith toxicant
              RfD; = Reference Dose for the ith toxicant

 The term ADDj/RfDj is referred to as the Hazard Quotient (HQ).

 Calculation of an ffl in excess of unity indicates the potential for adverse health effects.  Indices
 greater than one will be generated anytime intake for any of the Chemicals of Potential Concern
 (COPC). However, given a sufficient number of chemicals under consideration, it is also possible to
generate an HE greater than one even if none of the individual chemical intakes exceeds its respective
RfD.
                                          -56-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
 Carcinogenic risk is expressed as a probability of developing cancer as a result of lifetime exposure.
 For a given chemical and route of exposure, excess lifetime cancer risk is calculated as follows:

        Risk = Lifetime Average Daily Dose (LADD) x Carcinogenic Slope Factor (CSF)

 These risks are probabilities that are generally expressed in scientific notation (i.e., 1 x 10'6 or 1E-6).
 An incremental lifetime cancer risk of 1 x 10^ indicates that, as a plausible upper-bound, an individual
 has  a one-in-one-million chance of developing cancer as a result of Site-related exposure to a
 carcinogen over a 70-year lifetime under the specific exposure conditions at the Site. For .exposures
 to multiple carcinogens, EPA assumes that the risk associated with multiple exposures is equivalent
 to the sum of their individual risks.

 Process Area: Current Use Risk Summary

 The Process Area presents physical and chemical risks to human health. The Site contains numerous
 unstable structures that pose physical risks to trespassers. Incidents involving unstable structures are
 potentially fatal and represent significant risk associated with the Site. The condition of the structures
 will worsen over time, with a corresponding increase in associated hazards.

 Apart from the physical hazards noted above, exposure to contaminants in soil in the Process Area
 is curtailed by the asphalt pavement that covers the great majority of the Site and exposure to
 contaminated soils  is not possible.  Also, there  are no  groundwater wells in use that tap the
 contaminated zone of the aquifer.  Thus, for these reasons, current exposure routes are incomplete.

Process Area: Future Use Risk Summary

In the future, the Site may be  redeveloped for either residential or commercial/industrial use based
                                           -57-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  on dialogue with local land use planning officials and citizens. Such redevelopment would expose
  the contaminated soils that exist beneath the pavement.  Potential receptors would be Site visitors,
  Site workers, child residents, adult residents, and lifetime residents.  Exposure routes potentially
  complete in such a scenario are:

  •      inadvertent ingestion of soil;
        dermal contact with soil; and
  •      inhalation of dust
  •      ingestion of groundwater

 Table 2-6 summarizes the cancer and noncancer risks for these receptors. The total incremental
 lifetime cancer risk estimates range from 3 x 10E-9 for the Site visitor to 5 x 10E-4 for the lifetime
 resident.  In addition to the lifetime resident, risk estimates for the child resident and adult resident
 are above EPA's target range for Superfund sites. Arsenic in groundwater accounts for the excess
 cancernsk. Noncancer effects are possible for Site workers, child, adult, and lifetime residents based
 on His of 2,25,7, and 10 respectively. Exposure to antimony, arsenic, and iron, and manganese in
 groundwater account for the majority of the potential non-cancer effects. Table 2-7 summarizes the
 cancer and noncancer risks for these receptors when the ingestion of groundwater route is eliminated.

 Process Area: Exposure to Lead

 In the future, the Site may be redeveloped for either residential or commerical/industrial use. Such
 redevelopment would expose the contaminated soils  that exist beneath the pavement. Potential
 receptors would be Site visitors, Site worker, child residents, adult residents, and lifetime residents.
 In this future scenario, ingestion of groundwater from wells developed from within the contaminant
plume is considered as an additional exposure route for  Site workers, child residents, adult residents,
and lifetime resident. Exposure routes potentially complete in such a scenario are:
                                           -58-

-------
                                                                  Table 2-6
                                           Summary of Cancer and Noncancer Risks by Exposure Route
                                                              Future Use Scenario
                                                                 Process Area
                                                               Ross Metals Site
                                                              Rossville, Tennessee
Exposure
Route
Ingestion Groundwatcr
Inadvertent Ingestion Soil
Dermal Contact Soil
Inhalation Dust
TOTAL RISK

SiteN
Cancer
NA
NA
NA
3E-009
3E-009

'isitor
1 ™
NA
0.3
0.1
0.0001
0.4

Site VI
Cancer
1E-004
NA
NA
3E-008
1E-004

/orker
I in
2
0.5
0.2
0.0004
7

Child I
2E-004
NA
NA
3E-008
?P 0(14

esidcnt
12
13
1
0.001
*>c
25
Adult Resident
cancer
3E-004
NA
NA
4E-008
3E-U04
Ml
5
t
03
0.001
7
Lifetime
Cancer
5E-004
NIA
NA
7E-008
SE-004
Resident
HI
7
01
.j
0.001
10
Cancer: Excess cancer risk level
HI:  Hazard index (non-cancer risk)
NA:  not applicable
                                                                    -59-

-------
                                                                  Table 2-7
                                           Summary of Cancer and Noncancer Risks by Exposure Route
                                                Future Use Scenario (w/o Groundwator Pathway)
                                                                Process Area
                                                               Ross Metals Site
                                                             Rossvillc, Tennessee
Exposure
Route
Inadvertent Ingestion Soil
Dermal Contact Soil
Inhalation Dust
TOTAL RISK

Site Visitor
Cancer
NA
NA
3E-009
3E-009

HI
0.3
0.1
0.0001
0.4

CifA VUnrlrnr
Cancer
NA
NA
3E-008
3E-008

HI
0.5
0.2
0.0004
i

/-"KIM f> 	 »_i. A
Ciiila 1'
Cancer
NA
NA
3E-008
it? nno

tiisiuuni
HI
13
1
0.001
13

Adult F
Cancer
NA
NA
4E-008
4E-008
Icsidcnt
HI
I
0.3
0.001
2

Lifetime
Cancer
NA
NA
7E-008
7E-OQ8
Resident
HI
4
0.3
0.001
4
Cancer:  Excess cancer risk level
HI: Hazard index (non-cancer risk)
NA: not applicable
                                                                   -60-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
•      inadvertent ingestion of soil,
•      dermal contact with soil,
•      inhalation of dust, and
•      ingestion of groundwater.

Lead was detected in all Process Area soil samples at concentrations ranging from 6 to 97,700 ppm;
the average concentration was 8,788 ppm.  Lead was also detected in  Site groundwater at
concentrations of 3 to 1,600 ug/l; the average concentration was 196 ug/l. These values were input
into version 0.99d of the IEUBK model. The results are summarized in Table 2-8.  An additional
model run was conducted with a default value of 4 ug/l for groundwater as an input.  The results are
summarized in Table 2-9. EPA uses a level of 10 ug lead per deciliter (dl) blood as the benchmark
to evaluate lead exposure.  As can be seen, the projected blood lead levels exceeded this threshold
for all age groups, indicating that lead concentrations are above the acceptable range.

Landfill Area: Future Risk Summary

 In the future, the Landfill Area may be redeveloped for commercial/industrial use or  it may be
 converted to residential use. Ingestion of groundwater is an additional exposure route that may exist
 in a future use scenario. Table 2-10 summarizes the cancer and noncancer risks for the Site visitor,
 Site worker, child resident, adult resident, and lifetime resident.  The total incremental lifetime cancer
 risk estimates range from 8 x 10'10 for the Site visitor to 5 x 10"4  for the lifetime  resident. In
 addition to the lifetime resident, the risk estimate for the adult resident is above EPA's target range
 for Superfund sites. Arsenic in groundwater accounts for the excess cancer risk. Noncancer effects
 are possible for Site workers, and child, adult, and lifetime residents based on His of 2, 18, 6, and
 8, respectively. Exposure to arsenic, antimony, and cadmium in soil and arsenic, iron, and manganese
 in groundwater account for the majority of the potential non-cancer effects.  Table 2-11 summarizes
 the cancer and noncancer risks excluding the groundwater pathway.
                                            -61-

-------
                                          Table 2-8
                          Projected Blood Lead Levels by Age Group
                                         Process Area
                                       Ross Metals Site
                                     Rossvilic, Tennessee

Year
0.5-1
40.5
Blood Lead Levels (ug/dl)
Year
1-2
47.4
Year
2-3
45.7
Year
3-4
45.4
Year
4-5
41.4
Year
5-6
38
Year
6-7
35.4
Source: Integrated Exposure Uptake Biokinetic Model for Lead in Children, version 0.99d.

Assumptions:
 Air concentration: 0.200 ug Pb/m3 (default)
 Diet (default)
 Soil and dust: 8,788 ug/g (average lead concentration in soil); Multiple Source Analysis
 Drinking water: 196 ug/1 (average concentration in plume)
 Paint intake: 0.00 ug Pb/day (default)
 Maternal contribution: Infant model (default)
                                            -62-

-------
                                          Table 2-9
                         Projected Blood Lead Levels by Age Group
                          Process Area (w/o Ground water Pathway)
                                      Ross Metals Site
                                    Rossvillc, Tennessee
Blood Lead Levels (ug/dl)
Year
0.5-1
38.4
Year
1-2
43.9
Year
2-3
42.0
Year
3-4
41.7
Year
4-5
37.2
Year
5-6
33.3
Year
6-7
30.5
Source: Integrated Exposure Uptake Biokinetic Model for Lead in Children, version 0.99d.

Assumptions:
 Air concentration: 0.200 ug Pb/m3 (default)
 Diet (default)
 Soil and dust: 8,788 ugVg (average lead concentration in soil); Multiple Source Analysis
 Drinking water: 4 ug/1 (default)
 Paint intake: 0.00 ug Pb/day (default)
 Maternal contribution:  Infant model (default)
                                            -63-

-------
                                                                 Table 2-10
                                           Summary of Cancer and Noncancer Risks by Exposure Route
                                                             Future Use Scenario
                                                                Landfill Area
                                                               Ross Metals Site
                                                             Rossvillc, Tennessee
Exposure
Route
Ingcslion Groundwater
Inadvertent Ingeslion Soil
Dermal Contact Soil
Inhalation Dust
TOTAL RISK
Site Visitor
Cancer
NA
NA
NA
8E-010
8E-010
HI
NA
0.1
0.02
0.003
0.2
Site Worker
Cancer
Ui-004
NA
NA
7E-009
1E-004
HI
2
0.2
0.1
0.01
2
Child Resident
Cancer
2I--004
NA
NA
6H-009
2E-004
HI
12
6
0.2
0.04
18
Adult Resident
Cancer
3E-004
NA
NA
1E-008
3E-004
HI
5
1
0.1
0.02
6
Lifetime Resident
Cancer
5H-004
NA
NA
2E-008
5E-004
HI
7
2
0.1
0.02
8
Cancer:  Excess cancer risk level
HI  Hazard index (non-cancer risk)
NA:  not applicable
                                                                    -64-

-------
                                                                  Table 2-11
                                           Summary of Cancer and Noncanccr Risks by Exposure Route
                                                Future Use Scenario (w/o Groundwatcr Pathway)
                                                                Landfill Area
                                                               Ross Metals Site
                                                             Rossville, Tennessee
Exposure
Route
Inadvertent Ingestion Soil
Dermal Contact Soil
Inhalation Dust
TOTAL RISK
Site Visitor
Cancer
NA
NA
8E-010
8E-010
HI
0.1
0.02'
0.003
0.2
Site Worker
Cancer
NA
NA
7E-009
7E-009
HI
0.2
0.1
0.01
0
Child Resident
Cancer
NA
NA
6E-009
6E-009
HI
6
0.2
0.04
6
Adult Resident
Cancer
NA
NA
1E-008
1E-008
HI
1
0.1
0.02
1
Lifetime Resident
Cancer
• NA
NA
2E-008
2E-008
HI
2
0.1
0.02
2
Cancer:  Excess cancer risk level
HI:  Hazard index (non-cancer risk)
NA: not applicable
                                                                     -65-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
Landfill: Exposure to Lead

Lead was detected in all Landfill Area soil samples at concentration ranging from 35 - 42,400 ppm;
the average concentration was 5,964 ppm.  Lead was also detected in  Site groundwater at
concentrations of 3 to 1,600 |ig/l; the average concentration was 196 p.g/1. These values were input
into version 0.99d of the IEUBK model. The results are summarized in Table 2-12.  Also, a default
value of 4 ug/1 for groundwater was input into the model. The results are summarized in Table 2-13.
EPA uses a level of 10 u.g lead per deciliter (dl) blood as the benchmark to evaluate lead exposure.
As can be seen, the projected blood lead levels exceeded this threshold for all age groups, indicating
that lead concentrations are above the acceptable range.

Wetland/Woodland Area

Future development in the Wetland/Woodland Area is unlikely due to its location in  a 100-Year
Floodplain and  wetlands.  Therefore,  the only  receptors that may come into  contact  with
contaminants are Site visitors. Exposure routes potentially complete are:

•      inadvertent ingestion of soil,
•      dermal contact with soil,
•      inhalation of dust, and
•      inadvertent ingestion of surface water

Wetland/Woodland Area: Exposure to Lead

Due to the intermittent exposure to lead in the Wetland/Woodland Area, the  IEUBK model cannot
be directly used to estimate blood lead levels.  However, if a child were to visit this area as little as
once per week (the same exposure frequency assumed for the Site visitor), the child would establish

                                           -66-

-------
                                         Table 2-12
                          Projected Blood Lead Levels by Age Group
                                        Landfill Area
                                       Ross Metals Site
                                     Rossvillc, Tennessee

Year
0.5-1
33.4

Year
1-2
39.6
Blood Lead Levels (ug/dl)
Year
2-3
38.3
Year
3-4
38.1
Year
4-5
34.9
Year
5-6
32.1
Year
6-7
29.9
Source: Integrated Exposure Uptake Biokinetic Model for Lead in Children, version 0.99d.

Assumptioas:
 Air concentration: 0.200 ug Pb/m3 (default)
 Diet (default)
 Soil and dust: 5,964 ug/g (average lead concentration in soil); Multiple Source Analysis
 Drinking water: 196 ug/1 (average concentration in plume)
 Paint intake: 0.00 ug Pb/day (default)
 Maternal contribution:  Infant model (default)
                                           -67-

-------
                                         Table 2-13
                          Projected Blood Lead Levels by Age Group
                          Landfill Area (w/o Groundwatcr Pathway)
                                      Ross Metals Site
                                     Rossvillc, Tennessee

Year
0.5-1
30.9

Year
1-2
35.4
Blood Lead Levels (ug/dl)
Year
2-3
33.9
Year
3-4
33.6
Year
4-5
29.7
Year
5-6
26.4
Year
6-7
24.0
Source: Integrated Exposure Uptake Biokinctic Model for Lead in Children, version 0.99d.

Assumptions:
 Air concentration: 0.200 ug Pb/ni3 (default)
 Diet (default)
 Soil and dust: 8,788 ug/g (average lead concentration in soil); Multiple Source Analysis
 Drinking water: 4 ug/1 (default)
 Paint intake: 0.00 ug Pb/day (default)
 Maternal contribution: Infant model (default)
                                           -68-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 a steady state blood lead level, and the risk to this child would be over EPA's acceptable level. This
 is because the lead concentration in the Wetland/Woodland Area (average concentration 4,555
 mg/kg) is more than seven times the lEUBK-based residential remedial level for lead (400 rag/kg).

 2.6.2  Ecological Risk Assessment Summary

 An ecological risk assessment was conducted to determine the potential for ecological risk at the Site.
 This section summarizes the approach that was followed and the conclusions that were drawn.

 The risk assessment was designed to evaluate the potential threats to ecological function from
 exposure to Site contaminants and to establish Site-specific clean-up levels for the contaminants of
 concern (COCs).  The problem formulation process included the identification of COPCs, the
 identification of exposure pathways, a determination of the assessment endpoints for the Site, the
 formulation of testable hypotheses, the development of a conceptual model, and the determination
 of the measurement endpoints.

 2.6.2.1  Identification of Chemicals of Concern

 A screening-level risk assessment was conducted  in which the maximum concentrations  of
 contaminants detected in the surface water and sediment at the  Site were compared to various
 benchmark values in order to identify chemical of potential concern (COPCs).  Metals had previously
 been identified as contaminants at the Site, based on knowledge of the industrial history of the facility,
 as well as the results from a variety of United States Environmental Protection Agency (U.S. EPA)
 sampling investigations. The metals and organics data were screened using a risk characterization
process that relates exposure concentrations to concentrations that potentially cause adverse effects.
The exposure concentrations were the highest concentration detected for each contaminant in the
sediment and surface water samples collected on Site (not including the reference samples). The
                                          -69-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 benchmark concentrations used in the screening-level risk assessment were the U.S. EPA Region 4
 Waste Management Divison Screening Values for Hazardous Waste Sites. If a Region 4 screening
 value was not available for a particular contaminant, the U.S. EPA Region 3 Screening Level, if
 available, was used (U.S. EPA 1995).

 An elevated hazard quotient (greater than one) resulting from the screening-level risk assessment
 indicates that exposure to the contaminant may cause an adverse effect.  However, more assessment
 is needed to determine if the contaminants exceeding the benchmark values pose a risk to ecological
 receptors at the Site. The contaminants for which maximum concentrations of compounds exceeded
 benchmarks for water and/or sediment at the Ross Metals Superfund Site are summarized next and
 in Table 2-14.

 Many inorganic compounds exceeded the benchmark values for surface water and/or sediment. The
 maximum surface water concentrations recorded at the Site exceeded the benchmark values for the
 following compounds: aluminum, antimony, cadmium, copper, iron, lead, thallium and zinc.  The
 maximum sediment concentrations recorded at the Site exceeded the benchmark values for the
 following compounds: antimony, arsenic, cadmium, copper, lead, mercury, nickel, silver, and zinc.
 In addition, twelve inorganic compounds for which no sediment benchmark exists were detected in
 sediment.  These compounds are aluminum, barium, beryllium, calcium, cobalt, iron, magnesium,
potassium, selenium, sodium, thallium, and vanadium (Table 2-14).

The listing of COPC was further refined by conducting a Site-specific ecological risk assessment.
                                         -70-

-------
Table 2-14
COCs Distribution and Hazard Quotient Calculations
Contamina
nt
Maximum Concentrations in Sediment
Maximum
Sediment
Concentration
Detection
s/Samples
Screenin
g Value
Referen
ce
Source
HQ
Metals mg/kg (dry weight)
Aluminum
Antimony
Arsenic
Cadmium
Copper
Iron
Lead
Mercury
Nickel
Silver
Thallium
Zinc
17,800
1,350
681
99.1
712
32,300
98,100
1.1
127
2.1
5.5
629
21/21
18/21
21/21
14/21
21/21
21/21
21/21
4/21
21/21
2/21
1/21
21/21
NB
12
7.24
1
18.7
NB
30.2
0.13
15.9
0.733
NB
124
NB
d
d
d
d
NB
d
d
d
d
NB
d
NB
113
94
99
38
NB
3,2
48
8
8
3
NB
5
Maximum Concentrations in Water (Filtered)
Maximum
Water
Concentratio
n
Detectio
ns/Sampl
es
ug/1
506
31.1
165
5.9
226
17,600
924
U
34
U
18
783
5/5
5/5
4/5
2/5
5/5
5/5
5/5
0/5
4/5
0/5
2/5
5/5
Screen!
ng
Value
Reference
Source

87
160
190
0.66
6.54
1,000
1.32
0.012
87.81
0.012
4
58.91
d
d
d
d
d
d
d
d
d
d
d
d
HQ

6
0.19
0.9
9
35
18
700
0
0.4
0
45
13
-71-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1     _
 2.6.2.2 Ecological Exposure Assessment

 Setting

 The wetlands delineated on the Site were both naturally formed and human-made. Wetlands on the
 landfill and within the RM Site boundary are considered human-made.  The remaining wetlands
 identified and delineated are considered natural systems.

 Four wetland areas were identified and delineated at the RM Site. Two of the wetland areas were
 isolated emergent wetlands delineated on the landfill in the northern portion of the RM Site.  One
 isolated emergent wetland was identified in the southwest portion of the RM Site. The areas to the
 east and north of the RM Site are classified as wetland. This wetland complex included an emergent
 wetland located in the southeastern portion of the landfill.  Wetlands east of the Site consisted of
 emergent wetlands that were replaced in succession by broad-leaved deciduous scrub/shrub and
 broad-leaved deciduous forested wetlands as you proceeded north and east. Wetlands north of the
 Site consisted of broad-leaved deciduous forested wetlands. Needle-leaved deciduous (baldcypress)
forested wetlands replaced the broad-leaved deciduous forested wetlands as you proceeded north and
northeast from the study area. These wetlands are part of a large wetland complex associated with
the Wolf River floodplain.

       Vegetation

       Five vegetation  types/communities (was one upland community and four wetland) were
       identified in the investigation area. The classification of wetlands followed Cowardin et al.
       (1979).

       1) Upland field
      2) Palustrine emergent (PEM)
                                         -72-

-------
                                                                    Record of Decision
                                                                    Ross Metals OU#1
 3) Palustrine broad-leaved deciduous scrub/shrub (PSS1)
 4) Palustrine broad-leaved deciduous forested (PFO1)
 5) Palustrine needle-leaved deciduous (baldcypress) forested (PFO2)

 Note that  the  survey was conducted  after fall  dieback of vegetation.   Therefore, the
 identification of herbaceous species was limited.

 Upland field

 The southern/southeastern portion of the RM Site contained an area of open field.'  Common
 species included Poa spp., broomsedge  (Andropogon spp.) and foxtail (Setaria spp.).

 Palustrine emergent wetland

 Four  separate emergent wetland areas  were identified at the Site.  Three were isolated
 wetlands. Two of these are located on the landfill. The third isolated wetland is located
 within the southeastern portion of the RM Site. The fourth emergent wetland is located to
 the east of the RM facility area and is part of a large wetland complex associated with the
 Wolf River.

 Dominant plant species for these areas included soft rush (Juncus effusus), cattail (Typha
spp.), cutgrass (Leersya spp.) and a variety of sedges, grasses and herbaceous species, most
 of which could not be identified due to  the time of the Site visit (following fall dieback of
 vegetation).

 Palustrine broad-leaved deciduous scrub/shrub (PSS1)

This wetland type was found east and northeast of the RM Site, and was a transition between
                                   -73-

-------
                                                                    Record of Decision
                                                                    Ross Metals OU#1
  the PEM and forested wetlands within the study area.

  Common sapling species include green ash (Fraxinuspennsylvanicd), willow oak (Quercus
 phellos), sweet gum(Liquidambarstyraciflua), red maple (Acerrubrum) and box elder (Acer
  negundo).  Common shrub species included buttonbush (Cephalanthus occidentalis) and
  Rubus species (Rubus spp.). Understory species included most of those identified in the PEM
 wetlands. Other common species included Japanese honeysuckle (Lonicerajaponica), field
 garlic (Allium spp.) and unidentified grasses and asters.

 Palustrine broad-leaved deciduous forested fPFOI)
                                                                               c,

 This wetland type was identified to the north of the landfill and to the east and north of the
 PSS1  wetlands.  Common tree species included sweet gum, willow oak,  overcup oak
 (Quercus lyrata), American elm (Ulmus americana), river birch (Betula nigra), and fed
 maple. Common shrub species included common winterberry (Ilex verticillata), and a
 honeysuckle species (Lonicera spp.). The sparse groundcover included numerous seedlings,
 birdbill spikegrass (Chasmanthium ornithorhynchum), sensitive fern (Onocleasensibilis), and
 nettles. Greenbriars (Smilax spp.) were a common woody vine.

 Palustrine needle-leaved deciduous fbaldcypress) forested (PFO2)

 This wetland type was located north of the PFO1  wetlands.  Baldcypress (Taxodium
distichum) was the only tree species in this wetland type. Virginia willow (Itea virginica) was
the only shrub species found, and was restricted to elevated mounds scattered in the wetland
area. Herbaceous species were lacking.
                                   -74-

-------
                                                                     Record of Decision
                                                                     Ross Metals OU#1
Soils
 Soil color was generally a reliable indicator of wetland (hydric) and nonwetland areas at the
 Site and adjacent areas. Gleying, oxidized root channels, and accumulation of organic matter
 in the top 12 inches of the soil surface were all positive indicators of hydric soils in wetland
 areas.  The soil profiles suggested alluvial soils.  This is consistent with the Fayette County
 soil survey mapping for the area (Flowers 1964)

 Upland soils lacked mottles and hydric color, and were generally a brighter color than hydric
 soils in wetlands.

Hydrologic Conditions

Direct evidence of wetland hydrologic conditions in the form of standing water, and soil
saturation or free water within twelve inches of the soil surface in soil borings, was recorded
at the wetland sample stations during Site visits. Emergent wetlands contained standing water
and saturation to the soil surface. The scrub/shrub and deciduous forested wetlands generally
had saturation  and/or free water within 10  inches  of the soil surface.  The baldcypress
wetlands contained standing water.

Indirect indicators of wetland hydrologic conditions included a lack of accumulated litter in
forested wetland areas and water stained leaves.  This suggests that the area may be flooded
by the Wolf River.

Other Waters

Two drainage features were identified within the study area. One of these is a drainage swale
(slough) north of the Site that conveys surface water to the north into a baldcypress swamp.
                                    -75-

-------
                                                                            Record of Decision
                                                        	_____	Ross Metals OU#1
         It is associated with an area of emergent wetland. This drainage feature likely receives runoff
         from the RM Site that gathers in the northeast comer of the Site and from portions of the
         landfill that slope towards the east and northeast.

         The second drainage feature, a ditch located north of the Site, is the remnant of an historic
         stream that was originally located along the western edge of the Site, and may have been part
         of the Site.  There are no defined channels connecting this ditch with the RM Site.

        Another ditch is located east of the Site, just to the east of the boundary of the PFO1 wetland
        along the eastern edge of the study area.  The ditch bends towards the west as it proceeds
        north, eventually discharging into the baldcypress swamp north of the RM Site.  No defined
        channels from the RM Site discharge into this ditch.

        These three drainage features join in the baldcypress swamp north of the RM Site, and
        eventually discharge into the Wolf River, which is a tributary of the Mississippi River.

 Exposure Pathways

 Prior to the initiation of the ecological risk  assessment, it was known that elevated levels of
 contaminants were present in the sediment, water, and possibly the biota on and adjacent to the Site.
 The contamination  was  not  only  present within the facility  boundaries,  but also  extended
 approximately  300 feet  east and 200 feet north of  the facility  boundaries.   The degree  of
 contamination further away from the facility was not known prior to conducting this risk assessment.
 A drainage ditch flows from a stormwater collection sump in the northeast corner of the facility area
 into the wetland area approximately 380 feet due northeast. This ditch could act as a pathway for
 contamination to continue migration northeast of the facility, especially during heavy rain events. It
was also not know whether the contamination had migrated into the Wolf River, approximately '/2-
mile north of the facility. Therefore, the wetlands north and east of the facility, the Wolf River, and
                                          -76-
f

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#l
 the facility itself were identified as areas of concern prior to this risk assessment.

 Chemical analyses of sediment, water, and biota were used to determine the levels of contaminants
 in each area. The maximum concentration and the arithmetic mean of each contaminant concentration
 were calculated from the resulting analytical data and used in the risk assessment to.represent the
 conditions of Site-specific exposure.

 On-Site receptors are potentially exposed to contaminants in abiotic matrices through direct contact,
 intentional ingestion (e.g., consumption of water and food items), and incidental ingestion (e.g.,
 sediment adhered to food items). Transfer of the contaminants to receptors could also occur through
 processes of bioaccumulation through the food chain, whereby higher trophic level receptors are
 exposed to Site contaminants through the  ingestion of contaminated prey items.

 Summary of field studies and modeling: A field investigation was conducted to obtain Site-specific
 contaminant  concentrations  in  water, sediment,  and biological tissue that would provide data
 necessary for the completion of the Site risk assessment.  Surface water and sediment samples were
 collected along a suspected contamination gradient (based on XRF data) in the adjacent wetlands and
 submitted for Target Analyte List (TAL) metals analysis.  The sediment samples were also submitted
 for toxicity evaluations. Analytical data from the Wolf River, a water body connected to the wetland
 system, was collected to assess potential risk to that system. Three locations were identified along
the Wolf River, "upstream," "midstream," and "downstream," from which sediment samples were
collected and submitted for TAL metals analysis. Site-specific  tissue concentrations were also
obtained for use in food chain modeling.  Plant, grasshopper, and frog samples were collected and
submitted for tissue analysis of TAL metals.  These Site-specific tissue residue levels were used to
predict the amount of contaminant transfer through trophic levels and subsequently, to the ecological
functioning of the system.

 Solid-phase toxicity evaluations  were  conducted to determine the effects of direct contact with Site
                                          -77-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  contaminants to aquatic organisms. The underlying premise of these toxicity evaluations was that the
  organism response can be associated with the contaminant levels determined by the chemical analyses.
  The endpoints for these evaluations were survival and growth (measured as body length for H.
  azteca and body weight for C. tentans).  The methods used to conduct these studies are described
  in the final  toxicological evaluation  reports.  In addition, measured concentrations of each
  contaminant of concern in surface water were compared to literature-based values on the toxicity to
  early life stages of amphibians.  This provided a  qualitative assessment of the risk of the Site
  contamination to amphibians.

 Finally, the results of the analyses of water, sediment, and tissue (food items) were use'd in a food
 chain model to predict exposure dosages for each contaminant of concern to upper trophic levels.
 For the purposes of the model, it was assumed that the food of herbivorous species (meadow vole)
 comprised 100 percent soft rush, the food of insectivorous species (red-winged blackbird, short-tailed
 shrew) comprised 100 percent grasshoppers, and the food of carnivorous species (green heron, mink)
 comprised 100 percent green tree frogs, since these were the food items collected from the Site and
 analyzed. The resulting exposure dosages were divided by an effect concentration derived from the
 literature to provide a hazard quotient for each contaminant of concern and each receptor species.

 2.6.2.3 Ecological Effects Assessment

 A review of the wetland and surrounding habitats provided  information for  the selection of
 assessment endpoints. A variety of invertebrates, vertebrates, and plants inhabit the wetland.  In
 addition, many birds and mammals from adjacent habitats could prey on the wetland flora and fauna.
 Therefore, the assessment endpoints will focus on these biological groups.  The assessment endpoints
 relate specifically to viability of avian, mammalian, and wetland invertebrate, vertebrate and plant
populations as well as organism survivability were selected as assessment endpoints for this risk
assessment. Listed next and summarized in Table 2-15 are the specific assessment endpoints selected
followed by the supporting measurement endpoint:
                                          -78-

-------
Table 2-15
Ecological Exposure Pathways of Concern
Exposure Media
Sediment/Surface Water
Sedjmenl/Surface Water
Soil/Sediment/Surfacc
Waler
Sediment/Surface Water
Soil/Sediment/Surface
Water
Soil/Sediment/Surface
Water
Soil/Sediment/Surface
Water
Exposure Routes
Incidental sediment ingeslion
Direct contact with sediment
Accumulation in forage
Direct contact with surface water
Incidental sediment ingeslion
Direct contact with sediment
Accumulation in forage
Direct contact with surface water
Incidental soil/sediment ingestion
Direct contact with soil/sediment
Accumulation in forage
Ingestion of surface water
Incidental soil/sediment ingeslion
Direct contact with soil/sediment
Accumulation in forage
Ingestion of surface water
Incidental soil/sediment ingestion
Direct contact with soil/sediment
Accumulation in plant forage
Ingestion of surface water
Incidental soil/sediment ingeslion
Direct contact with soil/sediment
Accumulation in forage
Ingestion of surface water
Incidental soil/sediment ingestion
Direct contact with soil/sediment
Accumulation in forage
Ingeslion of surface water
Assessment Endpoinls
Protection of benthic
invertebrate community
structure and (unction.
Protection of amphibians from
adverse effects on growth,
survival, and/or reproductive
success.
Protection of insectivorous
birds from adverse cflixts on
growlh, survival, and/or
reproductive success,
Protection of carnivorous
birds from adverse effects on
growlh, survival, and/or
reproductive success.
Protection of herbivorous
mammals from adverse effects
on growth, survival, and/or
reproductive success.
Protection of insectivorous
mammals from adverse effects
on growlh, survival, and/or
reproductive success.
Protection of carnivorous
mammals from adverse effects
on growlh, survival, and/or
reproductive success
Measurement Endpoinls
Toxicity of sediments to
Chironomus teutons and
Hyalella azteca
Comparisons with literature-
based values on the toxicity of
surface water concentrations
to early life stages of
amphibians
Dietary exposure studies were
selected to evaluate risk to
insectivorous bird species that
use the site.
Dietary exposure studies were
selected to evaluate risk to
carnivorous bird species thai
use Ihe site.
Dietary exposure studies were
selected lo evaluate risk to
herbivorous mammals that
use (he site.
Dietary exposure studies were
selected to evaluate risk to
insectivorous mammals that
use the site.
Dietary exposure studies were
selected to evaluate risk to
carnivorous mammals that
use the site.
Receptor
Chironomus
lenlans and
Hyalella azteca
Green tree frog,
Hyla cinerea
Red-winged
blackbird,
Agclaius
phoeniceus
Green heron,
Butorides
striatus
Meadow vole,
Microtus
pcnnsylvanicus
Short-tailed
shrew, Blarina
brevicauda
Mink, Muslela
vison
Endangered or Threatened Species
No
No
No
No
No
No
No
-79-

-------
                                                               Record of Decision
                                                               Ross Metals OU#1
  Protection of benthic invertebrate community structure and function.

  Toxicity evaluations using sediment and benthic invertebrate species were conducted
  to determine if contaminant levels in the sediment have an adverse effect on survival
  and growth, measured as body weight and body length. The midge, Chironomus
  tentans, and the amphipod,  Hyalella  azteca, were selected to represent benthic
  invertebrates.

 Protection  of amphibians  from adverse  effects  on  growth, survival,  and/or
 reproductive success.

 Comparisons with  literature-based values  on  the  toxicity  of surface water
 concentrations to early life stages  of amphibians were used to evaluate risk to
 amphibian species that use the Site. The green tree frog, Hyla cinerea, was selected
 to represent an amphibian.

 Protection of insectivorous birds from adverse effects on growth, survival, and/or
 reproductive success.

 Dietary exposure studies were selected to evaluate risk to insectivorous bird species
 that use the Site.  The red-winged blackbird, Agelaius phoeniceus, was selected to
 represent an insectivorous bird.  Appropriate food items were identified and a
 contaminant  dose  calculated based  on  the ingestion of  contaminated  prey
 (grasshoppers) and water.

Protection of carnivorous  birds from adverse effects on growth, survival, and/or
reproductive success.
                             -80-

-------
                                                                    Record of Decision
                                                                    Ross Metals OU#1
       Dietary exposure studies were selected to evaluate risk to carnivorous bird species
       that use the Site. The green heron, Butorides striatus, was selected to represent a
       carnivorous bird. Appropriate food items were identified and a contaminant dose
       calculated based on the ingestion of contaminated prey (frogs), sediment, and water.

*     Protection of herbivorous mammals from adverse effects on growth, survival, and/or
       reproductive success.

       Dietary exposure studies were selected to evaluate risk to herbivorous mammal
       species that use the Site. The meadow vole, Microtus pennsylvanicus, was selected
       to represent a herbivorous mammal. Appropriate food items were identified and a
       contaminant dose calculated based on the ingestion of contaminated food (plants),
       sediment, and water.

4      Protection of insectivorous mammals from adverse effects on growth, survival, and/or
       reproductive success.

       Dietary exposure studies were selected to evaluate risk to insectivorous mammals that
       use the Site. The short-tailed shrew, Blarina brevicauda, was selected to represent
       an insectivorous mammal. Appropriate food items were identified and a contaminant
       dose calculated based on the ingestion of contaminated prey (grasshoppers), sediment,
       and water.

*      Protection of carnivorous mammals from adverse effects on growth, survival, and/or
       reproductive success.

       Dietary exposure studies were selected to evaluate risk to carnivorous mammals that
       use the Site.  The mink, Mustela vison, was selected to represent a carnivorous
                                    -81-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
               mammal. Appropriate food items were identified and a contaminant dose calculated
               based on the ingestion of contaminated prey (frogs), sediment, and water.

 Summary ofToxicity Tests: The results of the 10-day sediment toxicity test using the amphipod,
 Hyalella azteca, are summarized in the Ecological Risk Assessment. Survival was significantly
 reduced in only the treatment for Location 3 (see Figure 2-21) when compared to both the laboratory
 control and Reference 1. There were no significant reductions in growth for any location compared
 to either Reference 1 or the laboratory control. Therefore, sediment from Location 3 was acutely
 toxic to Hyalella, but no chronic toxicity was detected in any of the locations. The final report for
 this test can be found in the Ecological Risk Assessment.

 The results of the 10-day sediment toxicity test using the midge, Chironomus tentans, are summarized
 in the Ecological  Risk Assessment. When compared to the  reference, survival was  significantly
 reduced only in the treatments for Location 3.  When compared to the laboratory control, survival
 in the treatments for Locations 2, 3, and 12 were significantly reduced. Since this Risk Assessment
 is based on comparisons to the reference area, it can be concluded that only the sediment from
 Location 3 was acutely toxic to  Chironomus tentans.  The final reports for these tests can be found
 in the Ecological Risk Assessment.

Summary of Food Chain Model Results:  The hazard quotient method (Bamthouse et  al. 1986;
U.S. EPA 1989) was employed  to predict the effects of surface water and sediment contamination
at the Site with regard to assessment endpoints. The hazard quotient method compares exposure
concentrations to ecological endpoints  such as reproductive failure or reduced growth.  The
comparisons are expressed as ratios of potential intake values to population effect levels. In addition,
due to the magnitude of the concentrations of lead in sediment and water collected at the Ross Metals
Site, an acute hazard quotient was also calculated for lead using an acute toxicity value. The effect
level values are based on studies published in the literature. The exposure concentrations  were
                                          -82-

-------
                                  LEGEND
                                  • SAMPLE LOCATION
                                  • SAMPLE LOCATION
                                   (XRF ONLY)
                                       GRAPHIC  SCALE
                                               900   1000
                                          1 Inch
                                                  1003t
U.S. EPA ENVIRONIIENTAI RESPONSE TEAM CENTER
         c pence*!**; AMD JWALYTIEX. CDNTHUCT
           FIGURE  2-21
      SITE AND  REFERENCE
      AREA LOCATION MAP
 ROSS METALS  SUPERFUND SITE
ROSSVILLE, FAYETTE COUNTY. TN
         JANUARY 1998

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  estimated by employing a food chain model for each receptor species. In these food chain models,
  ingestion rates of each contaminant of concern for each receptor species are determined based on
  known or estimated water, sediment, and food ingestion rates and body weights of each receptor
  species, as well as the measured concentrations of each contaminant in water, sediment, and food
  items collected at the Site.   The exposure concentrations and toxicity values are entered into the
  hazard quotient equation, and a hazard quotient is calculated. If the hazard quotient for a particular
  contaminant is greater than one based on an acute value, this indicates that there is an acute risk from
  that contaminant to the ecological receptor in question.  If the hazard quotient is greater than one
  based on a No Observed Adverse Effects Level (NOAEL), this indicates that there is a potential
  chronic risk from that contaminant to the ecological receptor in question. If the hazard quotient is
 greater than one based on a Lowest Observed Adverse Effects Level (LOAEL) for a particular
 contaminant,  this indicates a more serious risk in that the Site levels of that contaminant have the
 potential to produce an actual adverse effect on survival, reproduction, or growth of the ecological
 receptor in question.  The hazard quotient should be interpreted based on the severity of the effect
 reported.

 In  addition to determining whether each contaminant poses a risk to the selected assessment
 endpoints, preliminary ecotoxicologically-based  remedial  goals were established  for those
 contaminants  which were determined to be risks. These remedial goals are for sediment, and  they
 are based on the premise that if the concentration of a  contaminant is decreased in  sediment, its
 concentration would subsequently decrease in surface water and biota.  The characteristics of the Site
 were such that the surface water above the sediment was only a few centimeters deep. This would
 presumably allow for rapid equilibrium of contaminants between the sediment and water at the Site.
 Using these assumptions, a watensediment contaminant ratio and a biota:sediment contaminant ratio
 were calculated for the Site based on mean concentrations of each contaminant at the Site. The sump
 area was excluded from the sediment denominator in the water:sediment and plant:sediment ratios,
 because no water or plant samples were collected from the sump area.  The ratios were applied to
the food chain model described previously, and the sediment concentration in the model was changed,
                                          -84-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
thus changing the water and biota concentrations according to the calculated ratios until the hazard
quotient was just less than one. This calculation was performed for both the NOAEL and LOAEL
values, thus providing a preliminary ecotoxicologically based remedial goal for each contaminant
presenting a risk and for each assessment endpoint.

Results and Conclusions of the Acute Risk Characterization for Lead

The food chain model and acute hazard quotient calculations for lead and the five assessment
endpoints evaluated using this model are presented in the Ecological Risk Assessment. Using the
mean and maximum lead concentrations in sediment, no acute risk from lead to insectivorous birds,
carnivorous birds, or carnivorous mammals was calculated. However, for insectivorous mammals,
both the mean and maximum lead concentrations in sediment calculated an acute risk from lead. In
addition, an acute risk to herbivorous mammals was calculated when the maximum lead concentration
in sediment was used, but not when the mean concentration was used.  These results indicate that an
acute risk is posed to herbivorous and insectivorous mammals from the lead contamination at the
Ross Metals Superfund Site.

When the sediment concentration of lead was adjusted so that the acute hazard quotient was just less
than one, as described previously, a lead concentration of 9310 mg/kg in sediment was calculated for
herbivorous mammals and 2160 mg/kg for insectivorous mammals. Therefore, a lead concentration
of less than 2160 mg/kg in sediment at the Ross Metals Superfund Site is expected to be protective
of an acute threat to the avian and mammalian receptors evaluated in this risk assessment.

Results and Conclusions of the Chronic Risk Characterization for Insectivorous Birds

The food chain model and chronic hazard quotient calculations for insectivorous birds are presented
in the Ecological Risk Assessment. Using the maximum concentrations for each contaminant of
concern and the NOAEL, it was determined that a potential risk is associated with lead at the Ross
                                           -85-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
 Metals Superfund Site.  Additionally, the mean contaminant concentrations and the NOAEL also
 calculated a potential risk from lead at the Site. When the maximum contaminant concentrations and
 the LOAEL were used in the model, a risk was still calculated from lead. However, when the mean
 contaminant concentrations and the LOAEL were used in the model, no risk was calculated from any
 contaminant.

 When the sediment concentration of lead was adjusted so that the hazard quotient was just less than
 one, as described previously, a NOAEL of 933 mg/kg and a LOAEL of 93 30 mg/kg were determined.
 Therefore, a preliminary ecotoxicologically-based'target remedial goal of 933 mg/kg - 9330 mg/kg
 for lead in sediment was determined for the protection of insectivorous birds.

 Results and Conclusions of the Chronic Risk Characterization for Carnivorous Birds

 The food chain model and chronic hazard quotient calculations for carnivorous birds are presented
 in the Ecological Risk Assessment.  Using the maximum concentrations for each contaminant of
 concern  and the NOAEL,  it was determined  that lead poses a  potential risk at the Ross Metals
 Superfund Site. The mean contaminant concentrations and the NOAEL also calculated a potential
 risk from lead at the Site. When both the maximum and the mean contaminant concentrations were
 used with the LOAEL in the model, a risk was still calculated from lead.

 When the sediment concentration of lead was adjusted so that the hazard quotient was just less than
 one, as described previously, a NOAEL of 133 mg/kg and a LOAEL of 1330 mg/kg were determined.
 Therefore, a preliminary ecotoxicologically-based remedial goal of 133 mg/kg - 1330 mg/kg for lead
 in sediment was determined for the protection  of carnivorous birds.

Results and Conclusions of the Chronic Risk Characterization for Herbivorous Mammals
The food  chain model and chronic hazard quotient calculations for herbivorous mammals are
                                         -86-

-------
                                                                       Record of Decision
                                                                       Ross Metals OU#1
presented  in the Ecological Risk Assessment.  Using the maximum concentrations  for each
contaminant of concern and the NOAEL, it was determined that aluminum, arsenic, cadmium, lead,
and nickel pose a potential risk at the Ross, Metals Superfund Site. When the mean contaminant
concentrations and the NOAEL were used in the model, no risk from nickel was calculated, but a
potential risk was still calculated from aluminum, arsenic, cadmium, and lead. When the maximum
contaminant concentrations and the LO AEL were used in the model, a risk was still calculated from
aluminum, arsenic, cadmium, and lead. When the mean contaminant concentrations and the LOAEL
were used in the model, no risk was calculated from arsenic or cadmium, but a risk was still evident
from aluminum and lead.

When the sediment concentration of aluminum was adjusted so that the hazard quotient was just less
than one, as described previously, a  NOAEL of 123 mg/kg and a LOAEL of 1230 mg/kg were
determined.  Therefore, a preliminary ecotoxicologically-based remedial goal of 123 mg/kg -1230
mg/kg for aluminum in sediment was determined for the protection of herbivorous mammals.

When the sediment  concentration of  arsenic was adjusted so that the hazard quotient was just less
than one, as described previously, a NOAEL of 0.16 mg/kg and a LOAEL of 1.6 mg/kg in sediment
were established. Therefore, a preliminary ecotoxicologically-based remedial goal of 0.16 mg/kg -
1.6 mg/kg for arsenic in sediment was determined for the protection of herbivorous mammals.

When the sediment concentration of cadmium was adjusted so that the hazard quotient was just less
than one, as described previously, a NO AEL of 0.25 mg/kg and a LOAEL of 2.5 mg/kg in sediment
were established. Therefore, a preliminary ecotoxicologically-based remedial goal of 0.25 mg/kg -
2.5 mg/kg for cadmium in sediment was determined for the protection of herbivorous mammals.

When the sediment concentration of lead was adjusted so that the hazard quotient was just less than
one, as described previously, aNOAEL of 556 mg/kg and a LOAEL of 5560 mg/kg were determined.
Therefore, a preliminary ecotoxicologically-based remedial goal of 556 mg/kg - 5560 mg/kg for lead
                                         -87-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
 in sediment was determined for the protection of herbivorous mammals.

 When the sediment concentration of nickel was adjusted so that the hazard quotient was just less than
 one, as described previously, a NOAEL of 1.5 mg/kg in sediment was established.  A LOAEL for
 nickel in sediment was not determined because when the mean and maximum nickel concentrations
 and a LOAEL were used in the original model, no risk was established. Therefore, the preliminary
 ecotoxicologically-based remedial goal is an unbounded NOAEL of 1.5 mg/kg of nickel in sediment
 for the protection of herbivorous mammals.

 Results and Conclusions of the Chronic Risk Characterization for Insectivorous Mammals

 The food chain model and chronic hazard quotient calculations for insectivorous mammals are
 presented in  the Ecological Risk Assessment.  Using the maximum concentrations for each
 contaminant of concern and the NOAEL, it was determined that aluminum, arsenic, cadmium, lead,
 and nickel pose a potential risk at the Ross Metals Superfund Site. When the mean contaminant
 concentrations and the NOAEL were used in the  model, no risk from cadmium or nickel was
 calculated, but a potential risk from aluminum, arsenic, and lead was still evident. When both the
 mean and maximum contaminant concentrations and the LOAEL were used in the model, a risk was
 still evident from aluminum, arsenic, and lead.

 When the sediment concentration of aluminum was adjusted so that the hazard quotient was just less
 than one, as described previously, a NOAEL of 53.3 mg/kg and a LOAEL of 533 mg/kg were
 determined. Therefore, a preliminary ecotoxicologically-based remedial goal of 53.3 mg/kg - 533
 mg/kg for aluminum in sediment was determined for the protection of insectivorous mammals.

When the sediment concentration of arsenic was adjusted so that the hazard quotient was just less
than one, as described previously, a NOAEL of 0.14 mg/kg and a LOAEL of 1.4 mg/kg were
determined. Therefore, a preliminary ecotoxicologically-based remedial goal of 0.14 mg/kg -  1.4
                                         -88-

-------
                                                                       Record of Decision
                                                                       Ross Metals OU#1
mg/kg for arsenic in sediment was determined for the protection of insectivorous mammals.

When the sediment concentration of cadmium was adjusted so that the hazard quotient was just less
than one, as described previously, aNOAEL of 0.46 mg/kg in sediment was established. A LOAEL
for cadmium in sediment was not determined because when both the mean and maximum cadmium
concentrations and a LOAEL were used in the original model, no risk was established. Therefore,
the preliminary ecotoxicologically-based remedial goal is an unbounded NOAEL of 0.46 mg/kg of
cadmium in sediment for the protection of insectivorous mammals.

When the sediment concentration of lead was adjusted so that the hazard quotient was just less than
one, as described previously, a NOAEL of 129 mg/kg and a LOAEL of 1290 mg/kg were determined.
Therefore, a preliminary ecotoxicologically-based remedial goal of 129 mg/kg -1290 mg/kg for lead
in sediment was determined for the protection of insectivorous mammals.

When the sediment concentration of nickel was adjusted so that the hazard quotient was just less than
one, as described previously, a NOAEL of 1.40 mg/kg in sediment was established.  A LOAEL for
nickel in sediment was not determined because when the mean and maximum nickel concentrations
and a LOAEL were used in the original model, no risk was established.  Therefore, the preliminary
ecotoxicologically-based remedial goal is an unbounded NOAEL of 1.40 mg/kg of nickel in sediment
for the protection of insectivorous mammals.

Results and Conclusions of the Chronic Risk Characterization for Carnivorous Mammals

The food chain model and  chronic hazard quotient calculations for carnivorous mammals are
.presented in  the Ecological Risk Assessment.   Using  the maximum concentrations for each
contaminant of concern and the NOAEL, it was determined that aluminum, arsenic, and lead pose
a potential risk at the Ross Metals Superfund Site. When the mean contaminant concentrations and
the NOAEL were used in the model, a potential risk was still calculated from aluminum, arsenic, and
                                         -89-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
 lead. When the maximum contaminant concentrations and the LOAEL were used in the model, a risk
 was still calculated from arsenic and lead.  When the mean and LOAEL were used, no risk to
 carnivorous mammals was  evident from any of the contaminants.

 When the sediment concentration of aluminum was adjusted so that the hazard quotient was just less
 than one, as described previously, a NOAEL of 321 mg/kg in sediment was established.  A LOAEL
 for aluminum in sediment was not determined because when the mean and maximum aluminum
 concentrations and a LOAEL were used in the original model, no risk was established.  Therefore,
 the preliminary ecotoxicologically-based remedial goal is an unbounded NOAEL of 321 mg/kg of
 aluminum in sediment for the protection of carnivorous mammals.

 When the sediment concentration of arsenic was adjusted so that the hazard quotient was just less
 than one, as described previously, a NOAEL of 0.31 mg/kg and a LOAEL of 3.1 mg/kg in  sediment
 were established.  Therefore, the preliminary ecotoxicologically-based remedial goal of 0.31-3.1
 mg/kg of arsenic in sediment was determined for the protection of carnivorous mammals.

 When the sediment concentration of lead was adjusted so that the hazard quotient was just less than
 one, as described previously, a NOAEL of 4490 mg/kg and a LOAEL of 44,900 mg/kg in sediment
 were established.   Therefore,  the preliminary ecotoxicologically-based remedial goal for lead in
 sediment is 4490 - 44,900 mg/kg for the protection of carnivorous mammals.

 2.6.2.4  Conclusions

The results of the analyses  of the samples collected at the Site indicated that it has been heavily
contaminated with metals.  Contamination extends both north and east of the Site and into the
adjacent wetlands. Of all the metals calculated to pose a potential risk, lead was determined to pose
the highest risk to ecological receptors. It was also determined that organic contaminants are present
at the Site; however, the magnitude and extent of this contamination remains uncertain because of
                                         -90-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
the small sample size. Site-related contaminants have not been detected in the Wolf River.

The following sections present the conclusions that were drawn regarding the viability of avian,
mammalian, and wetland invertebrate, vertebrate  and plant populations, as well as organism
survivability.  NOAEL and LOAEL ranges for each receptor group are presented in Table 2-16.

2.7 REMEDIATION OBJECTIVES

2.7.1 Remedial Goals

For the protection of human health and ecological receptors, those COCs that are related to past
operations at the facility have been considered in the development of a soil/sediment remedial
alternative. These COCs include aluminum, antimony, arsenic, barium, cadmium, copper, iron, lead,
manganese, selenium, and vanadium. For ecological receptors, COCs include aluminum, antimony,
arsenic, cadmium, copper, iron, lead, mercury, nickel and zinc.

Development of a remedial effort specifically for contaminated surface water is not recommended if
the contaminant source is remediated. That is, if contaminated sediments are removed, surface water
would be remediated. Surface water quality could be monitored to determine the effectiveness of the
contaminant source remediation.

The geochemical model mention previously in Section 2.5.7.4 indicated that removal of lead to  100
ppm left a residual soil lead concentration of 31.71 ppm, which is near background levels.  It predicts
that removal of lOOppm would be protective or groundwater for at least 90 years.  However, the
conservative nature of this number, along with the uncertainty surrounding the modeling effort, make
it inappropriate to use as a subsurface soil cleanup goal.

The 100 ppm goal is based on the assumption of a 5,000 ppm surface load factor.  However, the
                                          -91-

-------
Table 2-16
COC Concentrations Expected to Provide Adequate Protection of Ecological Receptors
HabiuiType
Wetland/Creek
Welland/Soils
Wetlands/Soils
Wetlands/Soils
Wcllands/Soils
Wellands/Soils
Wetland/Creek
Exposure Medium
Sediment
Soil/Sedimenl
Soil/Sediment
Soil/Sediment
Soil/Sediment
Soil/Sediment
Surface Water
COC
Antimony
Arsenic
Cadmium
Copper
Lead
Mercury
Lead '
Lead
Aluminum
Arsenic
Cadmium
Lead
Nickel
Aluminum
Arsenic
Cadmium
Lead
Nickel
Aluminum
Arsenic
Lead
Aluminum
Arsenic
Cadmium
Copper
Iron
Lead
Zinc
Protective Level
Rings
19-70
10-45
3.2-3.3
15-68
2.790-13.098
1.5
53.3-533
0.14-1.4
>0.46
129-1290
>l.4
>321
0.31-3.1
4490-44,900
50
40
JO
40
30.000
40
10
Units
mg/kg.
ww
mg/kg.
ww
mg/kg.
ww
mg/kg,
ww
mg/kg.
ww
mg/kg.
ww
UE/L
Bads
Site specific NOAEI, to LOAEL range
Site specific NOAEL lo LOAEL range
Site specific NOAEL lo LOAEL range
Site specific NOAEL to LOAEL range
Silo specific NOAKI. lo IjOARL range
Site specific NOAEL to LOAEL range
Literature based loxicity information

Assessment Endpoint
Protection of bailhic invertebrate
community timeline and function.
Proteciion of insectivorous birds from
adverse effects on growth, survival,
and/or reproductive success.
Protection of carnivorous birds from
adverse effects on growth, survival,
and/or reproductive success.
Protection of herbivorous mammals
from adverse effects on growth,
survival, and/or reproductive success.
Protection of insecu'vorous mammals
from adverse effects on growth,
survival, and/or reproductive success.
Protection of carnivorous mammals
from adverse effects on growth,
survival, and/or reproductive success
Protection of amphibians from
adverse effects on growth, survival,
and/or reproductive success.

-92-

-------
establishment  of a 400 ppm risk-based surface  soil clean-up goal would mean surface  soil
concentrations no greater than 400 ppm.  With  a surface soil concentration of 400 ppm  and
considering the nature of the contamination, clean up of surface soils to 400 ppm in the area of the
wrecker building and truck wash should allow for the protection of groundwater.

Table 2-17 presents the risk-based (human health  and ecological) remedial goals for surface soil,
subsurface soil, and sediment.

2.7.2 Remedial Action Objectives

The remedial action objectives (RAOs) for the Ross Metals Site are as follows:
Soil
       prevent ingestion, inhalation, or direct contact with surface soil that contain concentrations
       in excess of the Remedial Goals (RGs);

       prevent further migration and leaching of contaminants in surface and subsurface soil to
       groundwater that could result in groundwater contamination in excess of MCLs;

       prevent further migration of contaminants in surface soil/sediment to surface water that could
       result in groundwater contamination in excess of MCLs;

       prevent ingestion or inhalation of soil that contain concentrations in excess of the RGs;
                                           -93-

-------
Table 2-17
Remedial Goals
Contaminant of Concern
Surface Soil (mg/kg)
Aluminum
Antimony
Arsenic
Barium
Cadmium
Copper
Iron
Lead
Manganese
Selenium
Vanadium
Subsurface Soil (mg/kg)
Lead
Wetlands Sediment (mg/kg)
Aluminum
Antimony
Arsenic
Cadmium
Copper
Lead
Mercury
Nickel
Remedial Goals

11,620
3
5
505
7
293
16,100
400
559
37
51

400

8,860
28.4 - 104
5.58
0.37 - 3.73
22.4-101.5
192 - 1,925
ND - 0.21
9.10
Basis

Avg. Background Concentration
Hazard Quotient Level = 0.1
Avg. Background Concentration
Hazard Quotient Level = 0.1
Hazard Quotient Level = 0.1
Hazard Quotient Level = 0.1
Avg. Background Concentration
Protection of Human Health
Avg. Background Concentration
Hazard Quotient Level = 0.1
Hazard Quotient Level = 0.1

Protection of groundwater

Avg. Background Concentration
Protection of Ecological Receptors
Avg. Background Concentration
Protection of Ecological Receptors
Protection of Ecological Receptors
Protection of Ecological Receptors
Protection of Ecological Receptors
Avg. Background Concentration
Footnote: Values for protection of ecological receptors were obtained by using a mean percent moisture concentration (33%) to convert NOAJEL/LOAEL
ranges (wet weight basis) to a dry weight range.

ND- Not Detected
                                                            -94-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 Wetlands
•      reduce potential for exposure  of contaminated sediments/soils and surface waters to
       ecological receptors;

       prevent transport andmigration of Site contaminants to the adjacent uncontaminated wetlands
       and the Wolf River,

•      restore impacted wetland communities; and

•      prevent further degradation of the wetlands and the adjacent areas.

2.7.3 Extent of Source Material Contamination Above Remedial Goals

To facilitate the evaluation of potentially applicable removal action alternatives for the Site, solid
media  waste can be divided into four general categories  based on physical and chemical
characteristics:
       •      Waste slag (landfilled and stockpiled on Site)
       •      Contaminated soil (in old fenced area and landfill area)
       •      Building ruins
       •      Demolition debris (pavement)
       •      Contaminated sediment (in wetlands)

Results from previous investigations suggest that lead will be the "driver" in any remediation effort
conducted at the Site. The presence of lead is sufficiently widespread that gearing a remediation
effort to lead will also remediate  other COC contamination, meaning that the extent of lead
contamination serves as a good indicator of the extent of all the COC contamination at the RM Site.
In addition, the ecological risk assessment  concluded that of all the metals  calculated to pose a

                                           -95-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  potential risk, lead was determined to pose the highest risk to the ecological receptors at the Site.

  Contaminated Solid Media in Old Fenced Area and Landfill

  Based on excavations performed in the landfill at the north end of the Site in November 1996, an
  estimated 10,000 CY of buried landfill slag is present on Site. In addition, several stockpiles of waste
  slag are located in various on-Site buildings (see Figure 2-2). The building labeled "furnace and raw
  materials refinery" contains two waste slag stockpiles totaling about 700 CY.  The buildings labeled
  "wrecker," "slag fixation," and "shipment" contain waste slag stockpiles of about 2,600; 700; and
 2,000 CY, respectively. The total combined volume of the stockpiled waste slag is about 6,000 CY.

 Lead-contaminated surface and subsurface soil is present in the landfill at depths of up to 5.5 feet bgs.
 Lead-contaminated surface soil is present throughout the fenced portion of the Site at depths of up
 to 1.5 feet beneath the pavement.  Based on an area of 450 by 525 feet, the volume of waste soil is
 estimated as 13,125 CY.

 Lead-contaminated subsurface soil was noted along the eastern edge of the wrecker building at depths
 up to 40 inches bgs. Lead-contaminated subsurface soil was also noted near the southeastern corner
 of the truck wash.  Based on two 125-ft-square areas at depths from 1.5 to 3 feet, the volume of
 contaminated subsurface soil is estimated as 2,500 CY. Figures 7-1 and 7-2 indicate the extent of
 lead contamination in Site soils.
The deteriorating buildings are located within the fenced portion of the Site.  The largest of the
buildings is a sheet metal building labeled "furnace and raw materials refinery;" the building is roughly
25 to 30 feet high, 180 feet long, and 100 feet wide.  Alter demolition and compaction, the combined
volume of the building debris is not expected to exceed 27,000 cubic feet (CF) (1,000 CY).  The
buildings are in poor condition and constitute a safety hazard.
                                          -96-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 Additional demolition debris maybe generated at the Site depending on the remedial action selected.
 About 20,000 square yards (SY) of asphalt and concrete pavement are located within the fenced
 portion of the Site. An 8-inch-thick concrete pad located within the landfill area covers about 1,333
 SY.  Therefore, the total area of pavement at the Site is about 21,333 SY (including asphalt and
 concrete).  The volume of concrete and asphalt estimated for disposal is 3,700 CY.

 Based on the estimated volumes of the landfilled and stockpiled slag, the total volume  of slag is
 estimated to be about 16,000 CY.

 Contaminated Sediment in Wetlands

 In December 1997, EPA ERTC conducted  sediment sampling to determine the extent of lead
 contamination in the wetland area adjacent to the old fenced area and landfill.  Samples were collected
 from 0 to 6 inches in depth and analyzed at the Site by field portable X-ray fluorescence (XRF) to
 determine the extent of lead contamination above. Because RGOs based on protection of ecological
 receptors are presented as ranges, an acceptable goal within the range must be selected in order to
 calculate the volume of contaminated sediment in the wetlands. Because lead, as previously indicated,
 is so widespread and presents the highest risk to ecological receptors; a cleanup goal established for
 it that takes into account impact to wetlands, should also ensure cleanup of other COCs to acceptable
 levels.  To determine an acceptable goal, a chart plotting cleanup goals versus area of wetlands to
 be excavated to obtain the cleanup goal was created and is shown in Figure 2-22.  Figure 2-22
 suggests that  800 mg/kg would be the most effective cleanup goal causing the least disturbance to
the wetlands.  Based on the XRF results, there are approximately 5.7 acres of material contaminated
above 800 mg/kg lead.  Figure 2-23 illustrates the contaminated wetlands.
                                          -97-

-------
                                                     Figure 2-22
                                     Cleanup Goals v. Excavation Required
10
                                                                                                         9.02
                                                                                                    fl.53/
                                     5.7    5.7   5.7    5.7    5.7   5.7   5.7
        5.5   5.5    5.5   6.5   5.5
                                                                            6.19
                                                              Area requiring excavation In order to meet cleanup goal
                                      i	i	i
        1900  1800  1700   1600  1500  1400  1300  1200  1100   1000   900   800   700   600   500   400   300   200
                                                  Cleanup Goal (ppm)

-------
                                                  LEGEND



                                                /\  Sample Location
                                               K%%  Removal Area


                                                    Wetland Community Types

                                               I'."-I  Scrub/Shrub

                                               f-^1  Emergent

                                               U-lJ  Brood-leoved Deciduous Forest
                                               i^)  Needle-Leaved Deciduous
                                                    (Bold Cypress) forest

                                              ~N800--Leod Concentration Contour (mg/kg)
                                             GRAPHIC  SCALE
                                                       100     200


                                                  Scale in Feet
     Ross Metals Site
   Rossville, Tennessee
COM Federal Programs Corporation
t  I I
Cohtaminant Contour in
         Wetlands
       March 1998
Figure  No.

  2-23
                                                                            8/98

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  Summary of Contaminated Solid Media
  The total estimated volume of contaminated solid media includes the following components:

  •       Waste Slag
               Landfill:      10,000 CY
               Surface Slag:  6,000 CY
        Lead-contaminated Surface Soil (volume includes areas contaminated with other COCs)
               Wetlands (sediment):        9,300 CY (at 800 ppm level)
               Old Facility Fenced Area:    13,125 CY (at 400 ppm level)
               Landfill Area:               8,750 CY (at 400 ppm level)
        Lead-contaminated Subsurface Soil  2,500 CY (at 400 ppm level)
        Lead-contaminated Buildings       1,000 CY (at 10 ug/dl level)
 •      Demolition Debris                  3,700 CY

 The contaminated solid media at the RM Site can be considered source material because it includes
 or contains hazardous substances, pollutants or contaminants that act as a reservoir for migration of
 contamination to groundwater, to surface water, to air, or acts as a source for direct exposure.
 Because the contaminated solid media is considered source material, the concept of principal threat
 and low level threat wastes should be applied to the RM Site.

 Principal threat wastes are those source materials considered to be highly toxic or highly mobile that
 cannot be reliably contained or would present a significant risk to human health or the environment
 should exposure occur.  Although no "threshold level" of risk has been established to identify principal
threat waste, source materials with toxicity and mobility characteristics that pose a potential risk
several orders of magnitude greater than the acceptable risk level for current or future land use can
be considered principal threat wastes.  For the RM Site, this would conservatively encompass solid
                                          -100-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
media with lead concentrations ranging from 40,000 ppm, since the RGO for lead is 400 pprn in soil,
and wetland sediment with lead concentrations ranging from 1,900 mg/kg upward since acute risk
occurs at the LOAEL which is equal to 1,920 mg/kg.

Low level threat wastes are those source materials that generally can be reliably contained and that
would present only a low risk in the event of a release. They include source materials that exhibit low
toxicity, low mobility in the environment, or are near health-based levels.

The identification of principal threat and low level threat wastes is important because their presence
influences the development of appropriate remedial alternatives. Although exceptions apply,  EPA
generally expects to  use  treatment to address the principal threats posed by a Site, wherever
practicable. On the other hand, the use of institutional controls, such as containment, is expected for
wastes that pose a relatively low long-term threat  or where treatment is impracticable (EPA 1991).

A review of the sampling results suggests that some of the contaminated solid media present at the
RM Site can be considered principal threat waste  based on the lead concentrations present. Waste
sample SL-01  and Site surface soil samples T4-LF/B12,  008SLA,  and 013SLA  all  had lead
concentrations greater than 40,000 ppm.  In addition, the soil associated with sample 020SLA could
be considered principal threat waste based on an arsenic concentration of 40 ppm.

Assuming an excavation depth of 1.5 ft bgs with a 50 foot x 50 foot excavation grid centered on each
of the Site soil samples exceeding 40,000 ppm lead, and each of the wetland sediment samples
exceeding 1,900 ppm lead, results in a volume of approximately 600 CY of contaminated soil and
8,200 CY of wetland sediment. Adding the 6,000 CY of stockpiled slag to this volume (based on the
results of waste sample WS-01), and the 10,000  CY of landfilled slag (based on similarity to the
stockpiled skg) results in a total volume of approximately 24,800 CY of the 53,275  CY of total
contaminated solid media that could be considered principal threat waste.

                                         -101-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
 2.8  DESCRIPTION OF SOURCE MATERIAL ALTERNATIVES

 A summary of source material alternatives is provided in Table 2-18.

 2.8.1 Alternative S-l - No Action

 2.8.1.1  Description

 Under this alternative, no action would be taken to remedy the contaminated surface soil, slag,
 sediment, or other solid media at the Site.  The alternative would only involve the continued
 monitoring of structures, surface soil,  slag, sediment, and surface water quality at the Site.
 Approximately  five wipe samples (from buildings)  and ten  surface soil and  fifteen  surface
 water/sediment samples would be collected from the affected areas and analyzed for the PCOCs found
 in each medium every five years for 30 years. Public health evaluations would be conducted every
 five years and would allow EPA to assess the ongoing risks to human health and the environment
 posed by the RM Site. The evaluations would be based on the data collected from media monitoring.

2.8.1.2  Overall Protection  of Human Health and the Environment

The no action alternative does not eliminate any exposure pathways or reduce the level of risk of the
existing soil contamination.
                                                                                           jqu±
                                         -102-

-------
                  r
                                                                                                                                   Table 2-18

                                                                                                                     Summary of Soil AKcnuttva Evaluation
        Remedial Alternative
       1 - No Action
       2 -Capping
      3 -Capping With
      ""avement In Place
       -Capping With
      ?onstruction of Above-
      >«ind Disposal Cell
                                 Overall Protection of Boutin
                                 Health uid UK Environment
                                Does not eliminate exposure
                                pathways or reduce the level of
                                risk.  Does not lifnh migration of
                                or remove contaminants.
                               Eliminates exposure pathways
                               and reduces the level of risk.
                               Isolates contamination sod
                               minimizes further migration.
 Eliminates exposure pathways
 «nd reduces the level of risk.
 Isolates contamination ind
 minimizes further migration.
Eliminate exposure pslhwiys
snd reduces the level of risk.
Isolates contamination and
minimizes further migration.
                                   Compliance with
                                        ARARs
                                  Chemical-spccUic
                                  ARARs in tat met
                                  Location-and
                                  action-specific
                                  ARARs do DO(
                                  apply.
                                 All action-spcci£c
                                 ARARs are expected
                                 to be met. Location-
                                 specific ARARs are
                                 applicable and
                                 would need to be
                                 met.
 All action-specific
 ARARs are expected
 to be met Location-
 specific ARARs are
 applicable and
 would need to be
 Ml action-specific
 \RARs are expected
 o be met Locatioo-
tpecific ARARs are
  iplicable and
 mild need to be
                        Lonj-Term Effectiveness
                            and Permanence
                       Tne contaminated material is
                       a long-tarn impact The
                       remediation goals are not met
 Long-term public hearlh
 threats associated with surface
 soil and sediment are greatly
 reduced No residual risks
 tan the alternative. Long-
 term erTecUveaess requires cap
 maintenance

 -ong.term public heahh
 threats associated with surface
 soil and sediment are greatly
 reduced. No residual risks
 ran the alternative. Lonj-
 erm efiectiveness requires cap
maintenance

 x»g-term public heahh
threats associated with surface
 (oil and sediment are greatly
reduced. No residual risks
 rom the alternative. Long-
£nn efiectiveness requires cap
 'lintenance
                                 Reduction of M/T/V Through
                                          Treatment
                               No reduction of M/T/V is realized.
                                                   Reduction of mobility is realized but
                                                   ronUminant volume or taxicfty sre
                                                   DOtreduced. For the principal threat
                                                   waste at the Site, does not meet
                                                   EPA's expectation to treat principal
                                                   threat waste.
 (eduction of mobility is realized but
 contaminant volume or toxichy are
 not reduced. For the principal
 la-eat waste at the Site, does not
 meet EPA's expectation to treat
 principal threat waste.
 {eduction of mobility is realized but
contaminant volume or toxjchy are
not reduced. For the principal
threat waste at the Site, does not
meet EPA's expectation to treat
principal threat waste.
Note: Option I includes excavated wetland sediment; Option 2 does not
                                        Sfcort-Term Effectiveness
                                                                  Level D protective equipment is
                                                                  required during sampling.
                                                                                                                                                                                           Ttchnlcal/EnfUKcrinj
                                                                                                                                                                                               Considerations
                                                                                                                                                                                             Estimated Tim* for
                                                                                                                                                                                           Implementation (rears)
                                    Level C and D protective
                                    equipment required during Site
                                    activities.  Excavating and grading
                                    may result in potential release of
                                    dust Noise nuisance from use of
                                    heavy equipment
                                                                                                                                                     Level C and D protective
                                                                                                                                                    equipment required during She
                                                                                                                                                    activities. Excavating and grading
                                                                                                                                                    may result in potential release of
                                                                                                                                                    dust  Noise nuisance from use of
                                                                                                                                                    heavy equipment
Level C and D protective
equipment required during Site
 ctivhies. Excavating and grading
may result in potential release of
dust Noise nuisance from use of
leavy equipment
                                                                                                                                 -103-

-------

Remedial Alternative
5A- Excavation and
Onshe Treatment With
Solidification'
Stabilization and Onsite
Disposal
5B- Excavation and
3nshe Treatment With
Solidification/
Stabilization and Oflsite
Disposal
6A- Capping With
Excavation and Onsite
Treatment And Disposal
Of Principal-Threat
Waste
Excavation and Onsite
Treatment And Oflsite
Disposal Of Treated
Principal-Threat Waste
— — — ^— — ^— — _».
Vote: Option 1 includes excavi
— ^ 	 — _ _
Threshold Cri
Overall Protection ofHumw
Health and the Environment
Eliminates exposure pathways
and reduces the level of risk.
Immobilizes contamination and
eliminate further migration.
Eliminates exposure pathways
and greatly reduces the level of
risk. Removes contamination
and mitigates further migration.
Eliminates exposure pathways
and greatly reduces the level of
risk. Removes contamination
and mitigates further migration.
liminales exposure pathways
and greatly reduces the level of
nsk. Removes contamination
and mitigate further migration.

terla
Compliance with
ARARi
Chemical-specific
ARARsiremet
Location- and
action-specific
ARARsare
applicable and
would need to be
met
ARARsare met
through onsite
treatment and oflsHe
disposal.
Chemical-specific
ARARsaremet
.ocation-and
ction-specific
ARARsare
pplicable and
would need to be
met
Chemical-specific
ARARsare met
.ocaiion- and
ction-specific
ARARsare
applicable and
ould need to be
et
^— .^••j


Lonj-Terra Effectiveness
and Permanence
Long-term public health
threats associated with surface
soil and sediment are
eliminated No residual risks
from the alternative. Requires
effective cap maintenance.
— — ^— . 	 •
Long-term public hearth
threats associated with surface
soil and sediment are
eliminated. No residual risks
from the alternative.
-ong-term public health
threats associated with surface
oil and sediment arc
liminatcd. No residual risks
'om the alternative. Requires
ffective cap maintenance.
— • 	 — . 	 	
•ong-term public heahh
treats associated with surface
oil and sediment are
iminaled. No residual risks
om the alternative. Requires
ffective cap maintenance.

Reduction ofM/r/VThrotifh
Treatment
Mobility and toxichy are reduced.
however, treatment process will
increase volume. Meets EPA
expectation to treat principal threat
waste, but also treats (rather than
contains) low-level threat waste.
Mobility and toxichy are reduced,
however, treatment process will
increase volume. Meets EPA
expectation to treat principal threat
waste, but alto treats (rather than
contains) low-level threat wastes.
vlobilhy and toxichy are reduced,
lowever, treatment process will
increase volume. Meets EPA
expectation to treat principal-threat
waste and contain low-level threat
waste.
Mobility and toxichy are reduced,
lowever. treatment process will
increase volume. Meets EPA
xpectation to.treat principal-threat
•asle and contain low-level threat
aste.
Short-Tenn Effectiveness
Level C and D protective
equipment required during Site
activities. Excavating and grading
may result in potential release of
dust Noise nuisance from use of
heavy equipment
Level C and D protective
equipment required during Site
activities. Excavating and grading
may result in potential release of
dust Noise nuisance from use of
heavy equipment
Level C and D protective
equipment required during Site
activities. Excavating and grading
may result in potential release of
dust Noise nuisance from use of
heavy equipment
Level C and D protective
quipment required during Site
activities. Excavating and grading
may result in potential release of
ust Noise nuisance from use of
eavy equipment

IrapIementabaHy
Technical/Engineering
Capping in a floodplain.
None
Capping in a floodplain.
Capping in a floodplain
tfed wetland sediment; Option 2 does not
Estimated Time for
Implementation (yem)

-------
                                                                                  Record of Decision
                                                                                  Ross Metals OU#1
4        2.8.1.3 Compliance with ARARs
         This alternative does not achieve the RAOs or chemical-specific ARARs established for surface soil.
         Location- and action-specific ARARs do not apply to this alternative since further remedial actions
         will not be conducted.

         2.8.1.4  Long-Term Effectiveness and Permanence

         The remediation goals derived for protection 'of human health and the environment would not be met.
         Because contaminated soil remains under this alternative, a review/reassessment of the conditions at
         the Site would be performed at 5-year intervals to ensure that the remedy does not become a greater
         risk to human health and the environment.

         2.8.1.5  Reduction of M/T/V Through Treatment

         No reductions in contaminants M/T/V are realized under this alternative.

         2.8.1.6  Short-Term Effectiveness

         Since no further remedial action would be implemented at this Site, this alternative poses no short-
         term risks to onsite workers. It is assumed that Level D personnel protection would be used when
         sampling various media.

         2.8.1.7  Implementability

         This alternative could be implemented immediately since monitoring equipment is readily available
         and procedures are in place.
                                                  -105-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
2.8.1.8 Cost

Minimal costs are associated with this alternative compared to other remedial action alternatives. No
capital costs are associated with this alternative. The estimated O&M costs for media sampling
associated with monitoring are approximately $100,247.

2.8.2 Alternative S-2 - Capping

2.8.2.1  Description

Capping the contaminated solid media at the RM Site would serve to prevent rainfall infiltration and
future leaching into the groundwater. In addition, capping also would limit direct contact exposure
to contaminated media under the cap.  Varying degrees of capping can be implemented depending
on the severity of contaminants in the area.  Caps  can range from a simple natural soil cap to a
multilayer soil/synthetic cap. This alternative evaluates a geosynthetic cap for implementation.  This
type of cap would produce a low permeability barrier sufficient to reduce contaminant migration.

This alternative includes the demolition of most of the on-Site pavement  and buildings. The main
office building and the pavement immediately surrounding this building would remain on Site, and
landfilled slag would remain in place. Contaminated soil beneath the pavement would be excavated
up to a 3 ft maximum depth and consolidated with the stockpiled slag, pavement, and building debris.
This waste material would be disposed in an on-Site excavation that would extend from the existing
landfill to about 375 feet south of the landfill.  This disposal area would be about 400 feet wide and
8 feet deep, although could be enlarged somewhat if necessary.  A geosynthetic cap and underlying
1.5-ft soil cushion layer would be added above the waste and existing landfill to cover about 6.7
acres. A  1.2-ft soil cover and 6-inch topsoil layer  would be placed over the entire Site.  These
components are outlined as follows:
                                          -106-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
          Demolition of pavement and buildings;
          Excavation of onsite contaminated soil (15,625 C Y);
     •    Excavation of  an on-Site disposal area (375 ft long by 400 ft wide by 8 ft deep;
          approximately 36,200 CY subsurface soil);
          Compaction of 26,325 CY of waste material (15,625 CY of waste soil; 6,000 CY of
          stockpiled slag; 3,700 CY of pavement; and 1,000 CY of building debris ) into disposal
          area     (Compaction of 35,625 CY of waste material if excavated wetland sediment is
          consolidated with surface soil for final disposition);
          Installation of 1.5-ft-deep soil cushion over the waste and existing landfill (20,300 CY);
     •    Installation of geomembrane liner and geotextile over soil cushion (6.7 acres);
     •    Soil cover (1.2  ft deep), topsoil cover (6 inches deep), and grass seeding over the Site (8
          acres); and
     •    Land/deed use restrictions and fencing.

The topsoil layer of the cap  would be graded to a minimum slope of 3% and a maximum of 5% to
promote surface drainage away from the waste cell and reduce infiltration. Surface drainage controls
would be constructed around the perimeter of the cap to collect surface water runoff.

Alternative S-2  would eliminate direct  contact with contaminated media, eliminate on-Site physical
hazards, minimize contaminant migration to groundwater, and eliminate contaminant migration to
surface water from the Site. Figure  2-24 illustrates the components of the  cap included in this
alternative as they would be applied to the RM Site.

2.8.2.2  Overall Protection of Human Health and the Environment

Successful implementation of this alternative would reduce risks to human health and the environment
and meet the removal action objectives by (1) eliminating exposure of residents and trespassers to

                                         -107-

-------
SOUTH
             DEPTH AT WHICH
        GROUNDWATER ENCOUNTERED
                                                                  WRECKER
                                                                  BUILDING
                                                                                                                                              NORTH
                                                                                                                  SURFACE DEPOSITION OF
                                                                                                                 LEAD CONTAMINATED DUST.
                                                                                                                   SOILS, AND SEDIMENT
                                                             6" TOPSOIL COVER/GRASS SEEDING

                                                         ~_~-~_~_~_'1.5 SOIL CUSHION-
                                                                  6.5' WASTE MATERIAL
                                                               .*.-»."•'  '     '.'
                                                                    —     •_
            DEPTH AT WHICH
        GROUNDWATER ENCOUNTERED
                                                             MOT TO SCALE
                                                                                                CONTAMINATED
                                                                                            SOIL eaow SLAG
                                                                                                     APPROXIMATE DIMENSIONS OF EXCAVATION: TOTAL DEPTH - 8 FT
                                                                                                                                       LENGTH - 375 FT.
                                                                                                                                       WIDTH - 400 FT.
NOTE:  Conceptual design. Federal, state, and local
requirements regarding construction in o floodplain
must be considered and  may affect design
Representation of waste  material Includes excavated
wetland sediments.
         Ross  Metals  Site
      Rossville,  Tennessee
COM Federal Programs  Corporation
* x&Kfay at Camf Dmxr * JfcAW he.
                                                    Alternative  2  -  Capping
Figure No.
 2-24

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
waste material by direct contact and airborne migration, (2) eliminating exposure of trespassers to
direct contact with on-Site physical hazards, and (3) minimizing the migration of contaminants to
groundwater and eliminating the  migration of contaminants to  surface water.  Consolidation and
isolation of the waste material beneath a geomembrane cap would eliminate receptor routes of
exposure through ingestion and inhalation. Structures throughout the Site would be demolished and
disposed of in an excavated disposal area beneath the existing pavement.  As a result, physical hazards
associated with deteriorating structures would be eliminated. In addition, geomembrane capping
would eliminate infiltration of precipitation and surface water that contributes to the migration of
contaminants to groundwater. However, because the waste material will remain on Site, contaminant
migration to groundwater cannot  be discounted as an adverse effect. Nevertheless, the elimination
of surface water infiltration makes this scenario unlikely, and contaminant migration through surface
water runoff to the adjacent wetlands and the Wolf River would be eliminated.

The threat of direct human exposure to contaminated waste and physical hazards would be practically
eliminated by this alternative; however, the threat could return over the long term if cap integrity was
compromised. The potential for ingestion; dermal contact, and inhalation of soil containing metals
would be eliminated by successfully placing the geomembrane cap over the waste material.

2.8.2.3  Compliance with ARARs

The RCRA hazardous waste disposal facility requirements are potentially applicable. The RM Site
is located in a 100-year floodplain within a zone designated  as A3, indicating that base flood
elevations and flood hazard factors have been determined for this area. The ARAR (40 CFR 264)
requires that disposal facilities be designed to withstand a 100-year flood.  In addition, EPA's
regulations (40 CFR Part 6, Appendix A) for implementing Executive Order 11988 (Floodplains
Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
floodplains, and to preserve and enhance the natural values of floodplains.   Specifically, when it is
apparent that a proposed or potential Agency action is likely  to impact a floodplain or wetlands, the
                                          -109-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 public should be informed through appropriate public notice processes.  Furthermore, if a proposed
 action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be
 undertaken, and a statement of findings explaining why the proposed action must be located in or
 affect the floodplain or wetlands.

 Regarding construction activities  related to implementing the alternative, 40  CFR 6 Appendix A
 requires that EPA-controlled structures and facilities must be constructed in accordance with existing
 criteria and standards set forth under the National Flood Insurance Program (NFIP) and must include
 mitigation of adverse impacts wherever feasible, including the use of accepted floodproofing and/or
 other flood protection measures.  To achieve flood protection, EPA shall  wherever practicable,
 elevate structures above the base flood level rather than filling land.  In addition, the capped area may
 be classified as a Tennessee Solid Waste Processing and Disposal (SWPD) Class II disposal facility.
 If so, the substantive requirements of the SWPD rule regarding Class II disposal facilities (e.g., siting)
 would apply to the Site. The SWPD rule (Rule 1200-1-7) and the Criteria for Classification of Solid
 Waste Disposal Facilities and Practices (40 CFR 257) require that disposal facilities must not be
 located in a 100-year floodplain, unless both of the following can be demonstrated:

     •   Location in the floodplain will not restrict the flow of the 100-year flood nor reduce the
          temporary water storage capacity of the floodplain; and
     •    The facility is designed, constructed, operated, and maintained to prevent washout of any
          solid waste.

Wetlands are located to the north and northeast of the facility and landfill, although these locations
are not identified on National Wetland Inventory (NWI) maps. The Protection of Wetlands Order
                                                                                                  *
(40 CFR 6) requires that no adverse impacts to wetlands result from a remedial action.  With
appropriate stormwater runon and runoff controls,  the substantive  requirements of this ARAR are
expected to be met. The SWPD rule requires that new landfills and lateral expansions shall not be         *
located in a wetlands, unless the owner or operator can make the following demonstrations:

                                          -110-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
     •    the presumption of a practicable alternative that does not involve wetlands is clearly
         rebutted;

     •    the construction/operation of the landfill will not cause or contribute to violations of
         applicable State water quality standards, any applicable toxic  effluent  standard or
         prohibition under Section 307 of the Clean Water Act (CWA), and will not cause or
         contribute to the taking of any endangered or threatened species or result in the destruction
         or adverse modification of critical habitat of endangered or threatened species;

         the landfill will not cause or contribute to significant degradation of wetlands;

     •    to the extent required under Section 404 of the CWA or Tennessee Water Pollution
         Control Act (TWPCA), steps have been taken to attempt  to achieve no net loss of
         wetlands (as defined by acreage and function); and

     •    sufficient information is available to make a reasonable determination with respect to these
         demonstrations.

The substantive requirements for stormwater discharges during construction activities as outlined by

the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this

remedial action.


All action-specific ARARs are expected to be met. The Tennessee Air Pollution Control Regulations

(T APCR) dust suppression and control requirements (Rule 1200-3-8) apply to earth-moving activities

associated with this alternative. ARARs for the control of fugitive dust  emissions would be met by

applying water to roads receiving heavy vehicular traffic and to excavation areas, as necessary.


2.8.2.4 Long-Term Effectiveness and Permanence


Under this alternative, the cap would have to be maintained to ensure that it continues to perform as

 designed; consequently, long-term monitoring, inspection, and maintenance would be required. The

 cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover

 integrity by deep-rooting vegetation and burrowing animals. The cover would need to be periodically


                                           -111-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 inspected, and required maintenance would need to be implemented in order to maintain effectiveness.

 The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
 design and grading layout. In addition, access restrictions such as land use controls and fencing
 would be required to prevent land uses incompatible with the Site; specifically, land uses that would
 compromise the cap should be precluded.

 2.8.2.5  Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to reduce contaminant mobility by isolating contaminants
 from receptor contact; contaminant volume or toxicity would not be reduced. Contaminant mobility
 would be reduced by installing an impermeable cap liner. The liner would eliminate surface water or
 precipitation  infiltration and  would greatly reduce contaminant migration to groundwater in
 conjunction with the existing clay unit beneath the Site.  Consolidation and capping would isolate
 waste source areas and would reduce contaminant mobility resulting from surface water transport and
 wind erosion. Contaminant mobility is expected to be reduced to an extent that would result in
 overall risk reduction from all pathways and exposure routes.

 This alternative would not meet EPA's expectation to use treatment to address the principal threats
posed by a site, although in some situations, containment of principal threats is warranted (EPA
 1991). Based on sample results collected during previous Site investigations, 600 CY of surface soil
 and 16,000 CY of stockpiled and landfilled slag would be considered  "principal-threat" waste.

Containment of principal threats maybe warranted where treatment technologies are not technically
feasible or available within a reasonable time frame; or where the volume of materials or complexity
of the site makes implementation of treatment technologies infeasible; or where implementation of
a treatment-based remedy would result in greater overall risk to human health and the environment
or cause severe effects across environmental media. A review of currently available technologies and
                                          -112-
o

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 Site conditions does not suggest that these situations Would apply to the RM Site.

 2.8.2.6  Short-Term Effectiveness

 The construction phase of this alternative would likely be accomplished within one field season;
 therefore, impacts associated with construction would likely be short term and minimal.  Short-term
 impacts are associated with excavation and consolidation of waste soil and slag; however, these
 potential, short-term impacts would be mitigated during the construction phase.

 If the excavated material is diy, on-Site workers will be exposed to waste soil and slag dust during
 excavation and consolidation activities.  Additional exposure to lead dust may occur during the
 demolition of building structures and pavement. Ingestion of dust could involve some health effects
 because of the high level of metals in waste soil and slag.

 On-Site workers would be adequately protected from short-term risks by using appropriate personal
 protective equipment and by following proper operating and safety procedures. However, short-term
 air quality impacts to  the  surrounding environment may occur during waste consolidation and
 grading. Dust emissions would be monitored at the property boundaries.  Fugitive dust emissions
 would be controlled by applying water as needed to surfaces receiving heavy vehicular traffic or in
 excavation areas.  A measurable, short-term impact to the surrounding area would include increased
 vehicular traffic and associated safety hazards, potential dust generation, and noise.

 2.8.2.7  Implementability

 Construction of a geomembrane surface cap is a standard construction practice.  Other than the
capping of contaminated material in a floodplain, no significant construction issues are expected to
be encountered.
                                         -113-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
                                                                                                 k
 No state or federal permits are expected to be required; however, advance consultation should occur
 while planning the action to ensure that all involved agencies are allowed to provide input.

 All services and materials for this alternative are readily available.

 2.8.2.8 Cost

 The total present worth for  S-2 is approximately $1,735,804 for Option  1, which includes the
 excavated wetlands sediment, and  $1,712,412 for Option 2, which does not include the wetland
 sediment. For Option 1, the estimated capital cost is approximately $1,575,908, and the estimated
 O&M cost is  approximately $159,895. For Option 2, the estimated capital cost is approximately
 $1,552,516, and the estimated O&M cost is approximately $159,895.

 2.8.3 Alternative S-3 - Capping With Pavement in Place

 2.8.3.1  Description

 Alternative S-3 differs from Alternative S-2 in that the waste is not disposed of in an excavation, but
 rather spread over the existing pavement and capped in place with the existing landfill. Alternative
 S-3 includes the demolition of most  of the on-Site buildings.  The main office building would remain
 on Site, and the landfilled slag would remain in place. Contaminated soil from areas not covered by
pavement would be excavated and  consolidated with the stockpiled slag and building debris, and
 excavated wetland sediment. This waste material would be spread above the pavement that extends
from the existing landfill to about 375 feet south of the landfill.  A geosynthetic cap and underlying
 1.5-ft soil cushion layer would be added above the waste and existing landfill and would cover about
6.7 acres.  The totsl height of the  capped area would be and existing landfill and would cover
approximately 6.7 acres. The total height of the capped area would be approximately 5 feet. A 1-ft
soil cover and  6-inch topsoil layer would be placed over the entire Site.  The components of this
                                          -114-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 alternative are outlined as follows:

      •    Demolition of buildings;
           Excavation of contaminated soil in southeastern corner of the Site (2,800 CY);
           Compaction of 9,800 CY of waste material above pavement and landfill (2,800 CY of
           waste soil; 6,000 CY of stockpiled slag; and 1,000 CY of building debris)  (Compaction
           of 19,100  CY of waste material if excavated wetlands sediment is consolidated with
           surface soil for final disposition);
           Installation of 1.5-ft-deep soil cushion over waste and existing landfill (20,300 CY);
           Installation of geomembrane liner and geotextile over soil cushion (6.7 acres);
           Soil cover (1  ft deep), topsoil cover (6 inches deep), and grass seeding over Site
           (8 acres); and
      •    Land use/deed restrictions and fencing.

 The topsoil layer of the cap would be graded to  a minimum slope of 3% and a maximum of 5% to
 promote surface drainage away from the waste cell and reduce infiltration. Surface drainage controls
 would be constructed around the perimeter of the cap to collect surface water runoff.

 Alternative S-3 would eliminate direct contact with contaminated media, eliminate on-Site physical
 hazards, further minimize contaminant migration to groundwater, and eliminate contaminant
 migration to surface water from the Site. Figure  2-25 illustrates the components of the cap included
 under this alternative as applied to the RM Site.

2.8.3.2  Overall Protection of Human Health and the Environment

Successful implementation of this alternative would reduce risks to human health and the environment
and meet the removal action objectives by (1) eliminating exposure of residents and trespassers to

                                         -115-

-------
    SOUTH
                                                                    WRECKER
                                                                    BUILDING
                 DEPTH AT WHICH
             GROUNDWATER ENCOUNTERED
                                                                                                                                         NORTH
                                                                                                                   SURFACE DEPOSITION OF
                                                                                                                  LEAD CONTAMINATED DUST,
                                                                                                                 SOILS, WASTE, AND SEDIMENT
                                                                                                                                                         0'
                                                                        6" TOPSOL COVER/GRASS SEEDING
                              GEOSYNTHETIC
                                 UNER
tfl
o
CL
NOTE: Conceptual design. Federal, state, and local
requirements regarding construction In a floodplaln
must be considered and may affect design
Representation of waste material includes excavated
wetland sediments.
  Ross  Metals  Site
Rossville,  Tennessee
                                                  CDM Federal Programs Corporation
                                                  4 «*«**)' of Camp Chsoer i lfc*» he.
                                                                                                       APPROXIMATE DIMENSIONS OF EXCAVATION:  TOTAL DEPTH - 5 FT.
                                                                                                                                        LENGTH - 600 FT.
                                                                                                                                        WIDTH - 400 FT.
Alternative  3  -  Capping  With
       Pavement  in Place
Figure No.

 2-25
                                                                                                                                                    8/98
                    I*


-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
   waste material by direct contact and airborne migration, (2) eliminating exposure of trespassers to
   du-ect contact with on-Site physical hazards, and (3) further reduce the migration of contaminants to
   groundwater over Alternative S-2 and eliminate the migration of contaminants to surface water
   Consolidation and isolation of the waste material beneath a geomembrane cap would eliminate
   receptor routes of exposure through ingestion and inhalation. Structures throughout the Site would
  be demolished and disposed of in the disposal area above the existing pavement and landfill area The
  waste material would be spread and compacted throughout the Site. Physical hazards associated with
  deteriorating structures would be eliminated. In addition, geomembrane capping would eliminate
  infiltration of precipitation and surface water that contributes to the migration of contaminants  to
  groundwater. However, because the waste material will remain on Site, contaminant migration  to
  groundwater cannot be discounted as an adverse effect.  Nevertheless, the elimination of surface
  water infiltration  makes this scenario unlikely, and contaminant migration through  surface water
  runoff to the adjacent wetlands and the Wolf River would be eliminated.

 The threat ^direct hunian exposure to contaniinated waste and physical hazards would be practically
 eliminated by this alternative; however, the threat could return over the long tern if cap integrity was
 compromised. The potential for ingestion, dermal contact, and inhalation of soil containing metals
 would be eliminated by successfully placing the geomembrane cap over the  waste material.

 2.8.3.3 Compliance with ARARs

 The RCRA hazardous waste disposal facility requirements are potentially applicable. The RM Site
 is located in a 100-year floodplain within a zone  designated as  A3, indicating that base flood
 elevations and flood hazard factors have been determined for this area. The ARAR (40  CFR 264)
 requires that disposal facilities be designed to withstand a 100-year flood.    In addition, EPA's
 regulations (40 CFR Part 6, Appendix A)for implementing Executive Order  11988 (Floodplains
Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
floodplains, and to  preserve and enhance the natural values of floodplains. Specifically,  when it is
                                         -117-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 apparent that a proposed or potential Agency action is likely to impact a floodpiain or wetlands, the
 public should be informed through appropriate public notice processes.  Furthermore, if a proposed
 action is located in or affects a floodpiain or wetlands, a floodplain/wetlands assessment shall be
 undertaken, and a statement of findings explaining why the proposed action must be located in or
 affect the floodpiain or wetlands.

 Regarding construction activities related to implementing the alternative, 40 CFR 6 Appendix A
 requires that EPA-controlled structures and facilities must be constructed in accordance with existing
 criteria and standards set forth under the NFIP and must include mitigation of adverse impacts
 wherever feasible,  including the use of accepted floodproofing  and/or  other flood protection
 measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
 base flood level rather than filling land.  In addition, the capped area may be classified as a Tennessee
 SWPD Class II disposal facility.  If so, the substantive requirements of the SWPD rule regarding
 Class II disposal facilities (e.g., siting) would apply to the Site.  The SWPD rule (Rule 1200-1 -7) and
 the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR 257) require
 that disposal facilities must not be located in a 100-year floodpiain, unless both of the following can
 be demonstrated:
      •   Location in the floodpiain will not restrict the flow of the 100-year flood nor reduce the
          temporary water storage capacity of the floodpiain; and
      •   The facility is designed, constructed, operated, and maintained to prevent washout of any
          solid waste.
Wetlands are located to the north and northeast of the facility and landfill, although these locations
are not identified on NWI maps. The Protection of Wetlands Order (40 CFR 6) requires that no
adverse impacts to wetlands result from a remedial action. With appropriate stormwater runon and
runoff controls, the substantive requirements of this ARAR are expected to be met. The SWPD rule
requires that new landfills and lateral expansions shall not be located in a wetlands, unless the owner

                                          -118-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
or operator can make the following demonstrations:
         the presumption of a practicable alternative that does not involve wetlands is clearly
         rebutted;

         the construction/operation of the landfill will not cause or contribute to violations of
         applicable State  water quality standards, any  applicable  toxic effluent  standard  or
         prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
         of any endangered  or threatened  species or  result  in the  destruction or  adverse
         modification of critical habitat of endangered or threatened species;

         the landfill will not cause or contribute to significant degradation of wetlands;

         to the extent required under Section 404 of the CWA or  Tennessee Water Pollution
         Control Act, steps have been taken to attempt to achieve no  net loss of wetlands (as
         defined by acreage and function); and

         sufficient information is available to make a reasonable determination with respect to these
         demonstrations.
The substantive requirements for stormwater discharges during construction activities as outlined by
the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this

remedial action.


All action-specific ARARs are expected to be met.   The TAPCR dust suppression and control
requirements (Rule 1200-3-8) apply to earth-moving activities associated with this alternative.

ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
heavy vehicular traffic and to excavation areas, as necessary.


2.8.3.4  Long-Term Effectiveness and Permanence


Under this alternative, the cap would have to be maintained to ensure that it continues to perform as

designed; consequently, long-term monitoring, inspection, and maintenance would be required. The

                                          -119-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
o
  cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover
  integrity by deep-rooting vegetation and burrowing animals. The cover would to need be periodically
  inspected, and required maintenance would need to be implemented.

  The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
  design and grading layout.  In addition, access restrictions such as land use controls and fencing
  would be required to prevent land uses that,are incompatible with the Site; specifically, land uses that
 would compromise the cap  should be precluded.

 2.8.3.5  Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to reduce contaminant mobility by isolating contaminants
 from receptor contact; contaminant volume or toxicity would not be reduced. Contaminant mobility
 would be reduced by installing an impermeable cap liner. The liner would eliminate surface water or
 precipitation infiltration and would greatly reduce contaminant  migration  to  groundwater in
 conjunction with the existing clay unit beneath the Site. Consolidation and capping would isolate
 waste  source areas and reduce contaminant mobility resulting from surface water transport and wind
 erosion.  Contaminant mobility is expected to be reduced to an extent that would result in overall risk
 reduction from all pathways  and exposure routes.

 This alternative would not meet EPA's expectation to use treatment to address the principal threats
 posed  by a site,  although in  some situations, containment of principal threats is warranted  (EPA
 1991). Based on sample results collected during previous Site investigations,  600 CY of surface soil
 and the 16,000 CY of stockpiled and landfilled slag would be considered "principal-threat" waste.           *

Containment of principal threats may be warranted where treatment technologies are not technically
feasible or available within a reasonable time frame; or where the volume of materials or complexity
of the site makes implementation of treatment technologies infeasible; or where implementation of     Ml
                                          -120-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 a treatment-based remedy would result in greater overall risk to human health and the environment
 or cause severe effects across environmental media. A review of currently available technologies and
 Site conditions does not suggest that these situations would apply to the RM Site.

 2.8,3.6 Short-Term Effectiveness

 The construction phase of this alternative would likely be  accomplished within one  field season;
 therefore, impacts associated with construction would likely be short-term and minimal. Short-term
 impacts are associated with excavation and consolidation of waste soil and slag;  however, these
 potential, short-term impacts would be mitigated during the construction phase.

 If the excavated material is dry, on-Site workers will be exposed to waste soil and slag dust during
 excavation and consolidation activities. Additional exposure to lead dust may occur during building
 structure and pavement demolition.  Ingestion of dust could involve some health effects because of
 the high level of metals in waste soil and slag.

 On-Site workers would be adequately protected by using appropriate personal protective equipment
 and by following proper operating and safety procedures.  However, short-term air quality impacts
 to the surrounding environment may occur during waste consolidation and grading.  Dust emissions
 would be monitored at the property boundaries. Fugitive dust emissions would be controlled by
 applying water to  surfaces receiving heavy vehicular traffic or  in excavation areas, as needed.  A
 measurable, short-term impact to the surrounding area would include increased vehicular traffic and
 associated safety hazards, potential dust generation, and noise.

 2.8.3.7  Implementability

 Construction of a geomembrane surface cap is a standard construction practice.  Other than capping
contaminated material in  a floodplain, no  significant construction  issues are expected  to  be
                                          -121-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 encountered.

 No state or federal permits are expected to be required; however, advance consultation should occur      *
 while planning the action to ensure that all involved agencies are allowed to provide input.

 All services and materials for this alternative are readily available.

 2.8.3.8  Cost

 The total present worth for Alternative S-3 is approximately $ 1,453,803 for Option 1, which includes
 the excavated wetlands sediment, and $1,430,411 for Option 2, which does not include the wetland
 sediment. For Option 1, the estimated capital cost is approximately $1,293,907, and the estimated
 O&M cost is approximately $159,895. For Option 2, the estimated capital cost is  approximately
 $1,270,515, and the estimated O&M cost is approximately $159,895.                               «P

 2.8.4 Alternative S-4 ~ Capping With Construction of Above-Ground Disposal Cell

 2.8.4.1  Description

 Alternative S-4 differs from Alternatives S-2 and S-3  in that waste is not disposed of in the area of
 the existing pavement; instead, it is consolidated over the surface of the existing landfill and capped
 in place. This method would  result  in a disposal cell approximately 15 feet high throughout the
 landfill area. This alternative includes the demolition of most of the on-Site pavement and buildings.
 The main office building and the pavement immediately surrounding this building would remain on         *
 Site, and landfilled slag would remain in place. Contaminated soil beneath the pavement would be
 excavated up to a 3 ft maximum depth and consolidated with the stockpiled slag, pavement, and
building debris.  This alternative includes the following components:
                                          -122-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
      •   Demolition of pavement and buildings;
          Excavation of onsite contaminated soil (15,625 CY);
          Compaction of  26,325 CY of waste material (15,625 CY of waste soil; 6,000 CY of
          stockpiled slag;  3,700  CY  of pavement; and 1,000 CY of building debris) in existing
          landfill area with a cell height of about 12 to 13 feet (Compaction of 35,625 CY of waste
          material, with a cell height of 15 feet if excavated wetlands sediment are consolidated with
          surface soils for  final disposition;
      •   Installation of 1.5-ft-deep soil cushion over the waste and existing landfill (7,600 CY);
          Installation of geomembrane liner and geotextile over soil cushion (2.5 acres);
          Soil cover (1 ft deep),  topsoil cover (6 inches deep), and grass seeding over the Site (8
          acres); and
      •    Land use restrictions and security fencing.

Surface drainage controls would be constructed around the perimeter of the cap to collect surface
water runoff.

Alternative S-4 would eliminate direct contact with contaminated media, eliminate on-Site physical
hazards, minimize contaminant migration to groundwater, and eliminate contaminant migration to
surface water  from the Site. Figure 2-26 illustrates the components of the cap included under this
alternative as applied to the RM Site.

2.8.4.2 Overall Protection of Human Health and the Environment

Successful implementation of this alternative would reduce risks to human health and the environment
and meet the removal action objectives by (1) eliminating exposure of residents and trespassers to
waste material by direct contact and airborne migration, (2) eliminating exposure of trespassers to
direct contact with on-Site physical hazards, and (3) further reduce the migration of contaminants to

                                          -123-

-------
SOUTH
                                                                                                                                       NORTH
                                                              KRECKER
                                                              BUILDING
                                                                                                            SURFACE DEPOSITION OF
                                                                                                           LEAD CONTAMIHATEO DUST.
                                                                                                          SOILS, WASTE. AND SEDIMENT
            DEPTH AT WHICH
                                                                                                                     15' HIGH DISPOSAL CELL
                                                                                               CEOSYNTHETIC-
                                                                                                  UNER
                                                                      6  TOPSOIL COVER/GRASS SEEDING
                                                                                                            :-p^>    121 WASTE. MATERIAL'   V T^X-?
                 DEPTH AT WHICH
            GROUNDWATER  ENCOUNTERED
NOTE: Conceptual design. Federal, state, and local
requirements regarding construction In a floodplaln
must be considered and may affect design
Representation of waste  material Includes excavated
wetland sediments.
                                                    APPROXIMATE DIMENSIONS OF EXCAVATION:  TOTAL DEPTH - 15 FT.
                                                                                     LENGTH - 200 FT.
                                                                                     WIDTH - 400 FT.
        Ross  Metals  Site
      Rossville,  Tennessee
COM Federal Programs Corporation
A MtsUay a Cmt Oww « Htftt he.
 Alternative  4  -  Capping With
Construction of  Above  Ground
            Disposal Cell
figure No.
 2-26
                                                                                                                                             8/98

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
groundwater over Alternative S-2 and eliminate the migration of contaminants to surface water.
Consolidation and isolation of the waste material beneath a geomembrane cap would eliminate
receptor routes of exposure through ingestion and inhalation. Structures throughout the Site would
be demolished and disposed of in the disposal area above the existing pavement and landfill area. The
waste material would be spread and compacted over the landfill area. Physical hazards associated
with  deteriorating structures would be eliminated.  In  addition, geomembrane capping would
eliminate  infiltration of  precipitation  and surface water  that contributes to  the migration of
contaminants to groundwater. However, because the waste material will remain on Site, contaminant
migration to groundwater cannot be discounted as an adverse effect. Nevertheless, the elimination
of surface water infiltration makes this scenario unlikely, and contaminant migration through surface
water runoff to the adjacent wetlands and the Wolf River  would be eliminated.

The threat of direct human exposure to contaminated waste and physical hazards would be practically
eliminated by this alternative; however, the threat could return over the long term if cap integrity was
compromised. The potential for ingestion, dermal contact, and inhalation of soil containing metals
would be eliminated by successfully placing the geomembrane cap  over the waste material.

2.8.4.3  Compliance with ARARs

The RCRA hazardous waste disposal facility requirements are potentially applicable.  The RM Site
is located in a 100-year  floodplain within a zone designated as  A3, indicating that base flood
elevations and flood hazard factors have been determined  for this area. The ARAR (40 CFR 264)
requires that disposal facilities be designed to withstand a 100-year flood.  In addition, EPA's
regulations (40 CFR Part 6, Appendix A) for implementing Executive Order 11988 (Floodplains
Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
floodplains, and to preserve and enhance the natural values  of floodplains. Specifically, when it is
apparent that a proposed or potential Agency action is likely to impact a floodplain or wetlands, the
public should be informed through appropriate public notice processes. Furthermore, if a proposed
                                         -125-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be
undertaken, and a statement of findings explaining why the proposed action must be located in or
affect the floodplain or wetlands.                                                        .

Regarding construction activities related to implementing the alternative, 40 CFR 6 Appendix A
requires that EPA-controlled structures and facilities must be constructed in accordance with existing
criteria and standards set forth under the NFIP and must include mitigation of adverse impacts
wherever feasible, including the use of accepted floodproofing and/or other flood protection
measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
base flood level rather than filling land. In addition, the capped area may be classified as a Tennessee
SWPD Class II disposal facility.  If so, the substantive requirements of the SWPD rule regarding
Class II disposal facilities (e.g., siting) would apply to the Site.  The SWPD rule (Rule 1200-1 -7) and
the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR 257) require
that disposal facilities must not be located in a 100-year floodplain, unless both of the following can
be demonstrated:
         Location in the floodplain will not restrict the flow of the 100-year flood nor reduce the
         temporary water storage capacity of the floodplain; and
         The facility is designed, constructed, operated, and maintained to prevent washout of any
         solid waste.
Wetlands are located to the north and northeast of the facility and landfill, although these locations
are not identified on NWI maps. The Protection of Wetlands Order (40 CFR 6) requires that no
adverse impacts to wetlands result from a remedial action. With appropriate stormwater runon and
runoff controls, the substantive requirements of this ARAR are expected to be met. The SWPD rule
requires that new landfills and lateral expansions shall not be located in a wetlands, unless the owner
or operator can make the following demonstrations:
                                          -126-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
       •    the presumption of a practicable alternative that does not involve wetlands is clearlv
            rebutted;                                                                      J

       •    the construction/operation of the landfill will not cause or contribute to violations of
            applicable  State water  quality standards, any applicable toxic effluent standard  or
            prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
            of any endangered  or  threatened  species or result in the  destruction or  adverse
            modification of critical habitat of endangered or threatened species;

       •    the landfill will not cause or contribute to significant degradation of wetlands;

       •    to the extent required under Section 404 of the CWA or Tennessee Water Pollution
           Control Act, steps have been taken to attempt to achieve no net loss of wetlands (as
           defined by acreage and function); and                                    •

       •    sufficient information is available to make a reasonable determination with respect to these
           demonstrations.                                                     H


 The substantive requirements for stormwater discharges during construction activities as outlined by
 the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this
 remedial action.


 All  action-specific ARARs  are expected to be met.  The TAPCR dust suppression and control
 requirements (Rule  1200-3-8) apply to earth-moving activities associated with this alternative.
 ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
 heavy vehicular traffic and to excavation areas, as necessary.


 2.8.4.4 Long-Term Effectiveness and Permanence


 Under this alternative, the cap would have to be maintained to ensure that it continues to perform as

 designed; consequently, long-termmonitoring, inspection, and maintenance would be required. The
cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover

integrity by deep-rooting vegetation and burrowing animals. The cover would need to be periodically

                                          -127-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 inspected, and required maintenance would need to be implemented.

 The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
 design and grading layout. In addition, access restrictions such as land use controls and fencing
 would be required to prevent land uses that are incompatible with the Site; specifically, land uses that
 would compromise the cap should be precluded.

 2.8.4.5 Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to reduce contaminant mobility by isolating contaminants
 from receptor contact; contaminant volume or toxicity would not be reduced. Contaminant mobility
 would be reduced by installing an impermeable cap liner. The liner would eliminate surface water or
 precipitation  infiltration and  would  greatly reduce contaminant  migration to groundwater  in
 conjunction with the existing clay unit beneath the Site. Consolidation and capping would isolate
 waste source areas and reduce contaminant mobility resulting from surface water transport and wind
 erosion. Contaminant mobility is expected to be reduced to an extent that would result in overall risk
 reduction from all pathways and exposure routes.

 Based on sample results collected during previous Site investigations, 600 CY of surface soil and the
 16,000 CY of stockpiled and landfilled slag would be considered "principal-threat" waste.  This
 alternative would not meet EPA's expectation to use treatment to address the principal threats posed
 by a site, although in some situations,  containment of principal threats is warranted (EPA 1991).

 Containment of principal threats may be warranted where treatment technologies are not technically
feasible or available within a reasonable time frame; or where the volume of materials or complexity
 of the site makes implementation of treatment technologies infeasible; or where implementation of
a treatment-based remedy would result in greater overall risk to human health and the environment
or cause severe effects across environmental media. A review of currently available technologies and
                                          -128-
o

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
program prior to excavation activities.

On-Site excavation shall be backfilled and restored to a condition consistent with the intended iuture
use of the property.  The backfill source must be prequalified to document its quality. Treatability
testing may be required to confirm the value of using a biosolid as a backfill.

The wetlands will be revegetated according to the Wetlands Revegetation Plan (ERRT 1998). The
facility area and landfill area (approximately 8 acres) will be grass seeded.  Maintenance plans to
eliminate the intrusion of less desirable species and to promote success shall be developed and Site
monitoring will be required.

Excavated material may be stockpiled on-Site prior to off-Site transportation. All excavated material
shall be transported off-Site for disposal in an approved RCRA-permitted landfill. All transportation
and off-Site disposal activities shall be conducted in full accordance with all ARARs, including but
not limited to, RCRA regulations. Per the requirements of Phase IV Land Disposal Restrictions
(LDRs)  - waste, soil, and debris classified as hazardous must be treated to Universal Treatment
Standards  (UTS)  prior  to  land  disposal.     Treatment  of these  materials  shall   use
solidification/stabilization/fixation to achieve UTS.

Summary of Estimated Remedy Costs

Table 2-23 provides a cost estimate for implementing the selected remedy.

Expected Outcomes of the Selected Remedy

The purpose of this response action is to eliminate and reduce risks posed by ingestion, inhalation,
or  direct  contact  with soil/sediment/slag/buildings; minimize  migration  of contaminants  to       *
                                          -190-

-------

  Ross Metals Site
RpasviHe. Tennessee
                                                  LEGEND



                                                A  Somple Locoticn


                                                    Wetland Community .Types

                                               IVJ  Scrub/Shrub

                                               ESI  Emergent

                                               C3  Brood-Leoved Deciduous Forest
                                               03  Needle-Leoved Deciduous
                                                    (Bold Cypress) Forest
                                               IS3  Excovotion lo BOOmgAg

                                               U  E«covation to lOOmjA?
                                                       Concentration Contour (nig/kg)
                                            GRAPHIC  SCALE
                                               0      100     200

                                                    ifc=fc
                                                Scale in Feet
                                     Excavation Contours
Figure Ho.
  2-30

-------
Table 2-22
Excavation Standards
Contaminant of Concern
Surface Soil (mg/kg)
Aluminum
Antimony
Arsenic
Barium
Cadmium
Copper
Iron
Lead
Manganese
Selenium
Vanadium
Subsurface Soil (mg/kg)
Lead
Wetlands Sediment (mg/kg)
Aluminum
Antimony
Arsenic
Cadmium
Copper
Lead
Mercury
Nickel
Slag





Excavation Standard

11,620
3
5
505
7
293
16,100
•400
559
-37
51

400'

8,860
28.4 - 104
5.58
0.37-3.73
22.4-101.5
800
ND - 0.21
9.10
Since the blast slag waste has unique
characteristics that make it easily
identifiable, removal of the landfill area slag
and stockpiled slag will be verified by visual
inspection and approved by EPA or its
representative.
ND - Not Detected
* - Modeling conducted during Remedial Design may indicate a less conservative clean-up goal is sufficient for protection of
  groundwater.
                                               -188-

-------
                                                                            Record of Decision
          •	—	—	Ross Metals OU#1
  recycling facility. The equipment will be sold or donated to interested parties. All other debris will
  be taken off Site to a nonhazardous disposal facility.

  Soil/sediment with constituent concentrations greater than the excavation levels listed in Table 2-22
  shall be excavated and disposed in an off-Site RCRA-permitted non-hazardous waste landfill. Figure
  2-30 provides a map delineating the approximated areas where soil/sediment will be excavated based
  upon data  obtained during  the  RI field investigations.  An estimated 33,674 cubic yards  of
  soil/sediment exceed the excavation standards. An estimated 16,000 cubic yards of slag exceed the
  excavation  standards.  Approximately 1,000 cubic yards of lead-contaminated buildings constitute
 a safety hazard. An estimated 3,700 cubic yards of demolition debris will be generated as a result of
 the remediation activities, of which approximately  1,500 tons of metal debris/equipment will be
 available for metal recycling.

 Prior to excavation activities, a statistically-based sampling program shall be implemented within the
 areas slated for removal to farther define those soils which  exceed the applicable  excavation
 standards.   EPA shall have a reasonable opportunity to review and comment on  the proposed
 statistical sampling program prior to implementation. Results of this sampling program shall be
 reviewed and approved by EPA prior to excavation activities.

 All excavation activities shall be conducted in a manner which provides adequate short-term
 protection of on-Site workers, and minimizes disruptions to local businesses and adjacent residents.
 Air monitoring during active excavation shall be implemented for the protection of on-Site workers
 and to assess potential off-Site impacts. As warranted, dust and odor control measures shall be
 instituted to mitigate adverse impacts in the active excavation areas, haul roads and adjacent off-Site
 areas.  An excavation confirmation sampling  program shall be developed  to verify that all soil,
sediment,  and slag have been removed to  the specified excavation standards. EPA shall have
reasonable opportunity to review the statistical methods employed by this confirmational sampling
                                          -187-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
•    On-Site excavation areas shall be backfilled and restored to the existing grade or better.  The       *
     backfill source, biosolids, may require treatability testing to confirm the value of using biosolid
     as a backfill;                                                                               ^

•    Stabilization/solidification/fixation of contaminated soil, stockpiled slag, landfilled slag, and
     wetlands sediment;

•    Off-Site disposal of soils, slag, and sediment to a RCRA-disposal facility;

•    Application of a layer of biosolids to the entire Ross Metals Site. Grass seeding of the facility
     and landfill areas; and revegetation of the Site wetlands according to the Wetlands Revegetation
     Plan developed by EPA, 1998.

•    Development of maintenance and monitoring plan to assess the effectiveness of the cleanup
     action.

The total estimated construction costs  associated with both alternatives  are $ 7,390,687.  The
estimated Operations and Maintenance costs are $30,045. The estimated total present worth costs
are $ 7,420,732.  ,               '  .

Performance Standards

Demolition of most of the on-Site pavement and buildings.   The main office building  and the
pavement immediately surrounding this building will remain on Site. Appropriate testing and any
necessary decontamination of the main office building shall be performed.   EPA  shall have a
reasonable opportunity to  review  and comment  on the proposed sampling and decontamination
program prior to  implementation.   The  building debris, pavement, and equipment  will  be
decontaminated by steam cleaning. The decontaminated metal debris will be taken offSite to a metal
                                          -186-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 agreement with the selected  alternatives S-5B and W-3B.  Please refer to the Responsiveness
 Summary which contains a letter of concurrence from TDEC.

 EPA received several letters from residents in the Town of Rossville which supported the selected
 remedy proposed by EPA. During the public meeting on November 30, 1998, town residents and
 local government officials expressed interest and support for the selected remedy presented by EPA.
 Please see the Responsiveness Summary which contains these letters and a transcript of the public
 meeting.

 2.11  SELECTED REMEDY

 The EPA Selected Remedy is Source Materials Alternative S-5B and Wetlands Alternative W-3B.
 Based upon current information, this  remedy appears to provide the best balance among the nine
 criteria that EPA uses to evaluate alternatives.  EPA has determined that the Selected Remedy would
 be protective of human health and the environment; would attain the Site goals; comply with ARARs;
 and would be cost effective.
   /

The Selected Remedy shall include the following:

     Demolition of most of the on-Site pavement and buildings.  The main office building and the
     pavement immediately surrounding this  building will remain on Site.   The building debris,
     pavement, and equipment will be decontaminated by steam cleaning. The decontaminated metal
     debris will be taken off Site to a metal recycling facility. The equipment will be sold or donated
     to interested parties. All other debris will be taken off Site to a permitted disposal facility;

     Excavation of contaminated soil, landfilled slag,  and  contaminated wetlands sediment that
     exceed their corresponding cleanup standard;
                                        -185-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 for each evaluation criterion.  Each alternative's performance against the criteria (except for present
 worth) was ranked on a scale of 0 to 5, with 0 indicating that none of the criterion's requirements
 were met and 5 indicating all of the requirements were met. The ranking scores are not intended to
 be quantitative or additive, rather they are only summary indicators of each alternative's performance
 against the CERCLA evaluation criteria.  The ranking scores combined with the present worth costs
 provide the basis for comparison among alternatives.

 For soil, Alternatives S-2 through S-7 all rank higher than Alternative S-l in overall protection of
 human health and the environment, compliance  with ARARs,  long-term  effectiveness  and
 permanence, and reduction of M/T/V. The three capping alternatives, Alternatives S-2, S-3, and S-4,
 are ranked similarly with the exception that Alternative S-2 ranks lowest in long-term effectiveness
 and permanence. The  two treatment alternatives receive similar ranking  in all criteria with the
 exception Option  B of  Alternative  S-5 ranks highest in compliance with ARARs long-term
 effectiveness and permanence, and implementability. A comparison of the capping alternatives to the
 treatment alternatives indicates that the treatment alternatives (Alternatives S-5 and S-6) rank slightly
 higher than the capping alternatives (Alternatives S-2, S-3, and S-4) in overall protection of human
 health and the environment and reduction of M/T/V, but are more costly.

 For wetland sediment, both Alternatives W-2 and W-3 rank higher than Alternative W-l in overall
 protection of human health and the environment, compliance with ARARs, long-term effectiveness
 and permanence, and reduction of M/T/V. Both options under Alternative W-3 (Excavation,
 Regrading and Wetlands Revegetation) rank higher than Alternative W-2 (Capping and Off-Site
 Creation of Wetlands) in overall protection of human health and the environment, compliance with
 ARARs, long-term effectiveness and permanence, and reduction of M/T/V.

EPA and the Tennessee Department of Environment and Conservation (TDEC) have cooperated
throughout the RI/FS process.  The State has participated in the development of the RI/FS  and
Proposed Plan by providing comments on planning and decision documents. EPA and TDEC are in
                                         -184-

-------
                                                                   Table 2-21

                                               Comparative Analysis of Wetland Sediment Alternatives
                                                                 Ross Mciais Site
                                                               Rossvillc, Tennessee
Remedial
Alternative

W-l- No Action
W-2- Capping with
Off-site Creation of
Wetlands
W-3 A — Excavation,
Regrading with
Clean Fill and
Wetlands
Revcgetation/
Restoration
W-3 B - Excavation,
Regrading with
Biosolid Compost
Material and
Wetlands
Rcvegctation/
Restoration

Overall Protection of
Human Health and
the Environment
0
3


5





5






Compliance
with ARARs

0
2


5





5





Criteria Rating '
Long-Term
Effectiveness and
Permanence
0
2


5





5





Reduction of
M/T/V Through
Treatment
0
3


4





5





Short-Term
Effectiveness

5
3


4





4





Implementability

5
4


4





3





Approximate
Present Worth
($)

5100,247
$611,762


$780,071





$699,548





'A ranking of "0" indicates noncompliance, while a ranking of "5" indicates complete compliance.
                                                                    -183-

-------
              Table 2-20
Comparative Analysis of Soil Alternatives
            Ross Metals Site
          Rossvitlc, Tennessee
Remedial Alternative
S-I -No Action
S-2 - Capping
SO - Capping With
Pavement In Place
S-4 - Capping With
Construction of Above-
Ground Disposal Coll
S-5A — Excavation and
Onsite Treatment With
S/ S and onsite Disposal
S-5B - Kxcavation and
Onsile 'I'rcalmonl With
SIS and oHsite Disposal
S-6A - Capping With
Uxcavation & Onsite
Treatment of Princ. Thrt
Waste & onsite disposal
S-6B -- Capping With
Excavation & Onsite
Treatment and Oflsite
Disposal of Principal
Threat Waste
Criteria Rating '
Overall Protection of
Human Health and the
Environment
0
4
4
4
5
5
5
5
Compliance
wlthARARs
0
4
4
4
4
5
4
4
Long-Terra
Effectiveness and
Permanence
0
2
3
3
4
5
4
4
Reduction of M/T/V
Through Treatment
0
3
3
3
5
5
5
5
Short-Terni
Effectiveness
5
4
4
4
4
4
4
4
Implementablllty
5
3
3
3
3
4
3
3
Approximate
Present Worth
($)
$100,247
Opt. 1-$ 1,73 5,804
Opt.2-$l,712,412
Opt. l-$ 1,453,803
Opt.2-$ 1,430,4 11
Opt. 1-$ 1,506,847
Opt.2-$ 1.48 1,865
Opl.l -$4,907,274
Opl.2-$4,244,992
Opl.l -$7,477, 199
Opt.2-$6,lKI,lf>0
Opt.l-$3,175,137
Opl.2-$2,729,543
Opt. 1 -$4,936,044
Opt.2-$4,OI3,508
'A ranking of "0" indicates noncompliance, while a ranking of "5" indicates complete compliance. Opt. 1 includes excavated wetland sediment; Opt. 2 docs not.
               -182-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 2.9.3B.7 Implementability

 The use of biosolid compost material to address metals contamination is an emerging technology with
 limited Ml scale application. However, all services and materials for this alternative should be readily
 available.

 2.9.3B.8 Cost

 The total present worth cost for Alternative W-3, Option B is approximately $699,548.  The
 estimated capital cost is $620,379.  The estimated annual O&M cost is approximately $79,170.

 2.10 COMPARATIVE ANALYSIS OF ALTERNATIVES

 This section presents a comparative analysis of the surface soil/sediment and groundwater alternatives
 based on the threshold and balancing evaluation criteria. The objective of this section is to compare
 and contrast the alternatives.

 The alternatives are presented here to give decision makers a range of potential actions that could be
 taken to remediate this Site.  These actions include:

     Soil                    No Action (Alternative S- 1 )
                             Capping (Alternatives S-2, S-3, S-4, and S-6 )
                             Solidification/Stabilization (Alternatives S-5 and S-6)
     Wetland Sediment        No Action (Alternative W-l)
                             Capping and Off-site Creation of Wetlands (Alternative W-2)
                             Excavation,  Regrading and  Wetlands Revegetation/Restoration
                             (Alternative W-3)

Tables 2-20 through 2-2 1 present a summary of each remedial alternative along with ranking scores


-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 treatment.

 2.9.3B.6  Short-Term Effectiveness

 The construction phase of this alternative would likely be accomplished within one field season;
 therefore, impacts associated with construction would likely be short-term and minimal. Short-term
 impacts are associated with excavation;  however, these potential, short-term impacts would be
 mitigated during the wetlands  restoration phase.  The revegetation plan uses plant species which
 should restore the system within one growing season, thereby limiting the impacts. Controls can be
 implemented to reduce impacts on adjacent wetlands.

 On-Site workers would be adequately protected by using appropriate personal protective equipment
 and by following proper operating and safety procedures.  However, short-term air quality impacts
 to the surrounding environment may occur during waste consolidation and grading. Dust emissions
 would be monitored at the property boundaries.  Fugitive dust emissions would be controlled by
 applying water to surfaces receiving heavy vehicular traffic or in excavation areas,  as needed.  A
 measurable, short-term impact to the surrounding area would include increased vehicular traffic and
 associated safety hazards, potential dust generation, and noise.

 Short-term impact on biological communities in the wetlands caused by excavation will be notable
 because of excavation of wetlands sediment. However, the goal of the wetland mitigation program
is to replace lost  wetland  vegetation so that wetland function and values either will be present
immediately following the completion of mitigation or will develop over time.  In addition, a
consideration of breeding seasons, and control of erosion and sedimentation in terms of scheduling
activities should ease short-term impact.
                                          -180-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 if a proposed action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment
 shall be undertaken, and a statement of findings explaining why the proposed action must be located
 in or affect the floodplain or wetlands.

 The Protection of Wetlands Order (40 CFR 6) requires that no adverse impacts to wetlands result
 from a remedial action. The wetlands revegetation component of this alternative includes a 2-to-l
 creation-to-loss ratio to compensate for the loss of forested and scrub/shrub wetlands which is
 expected to meet  the wetlands mitigation requirements of CWA Section 404.

 The substantive requirements for stormwater discharges during construction activities as outlined by
 the CWA are relevant and appropriate.  However, a specific NPDES permit is not required for this
 remedial action.

 All action-specific ARARs are expected to be met.  The TAPCR dust suppression  and  control
 requirements (Rule 1200-3-8) apply to earth-moving activities associated with this alternative.
 ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
 heavy vehicular traffic and to excavation areas, as necessary.

 2.9.3B.4 Long-Term Effectiveness and Permanence

 This alternative provides source control and removal of contaminated sediments in the wetlands. This
 action would permanently remove contaminated sediments and thereby reduce risk to ecological
 receptors and improve water quality.  The revegetation  plan will restore the wetlands to a high
 functioning value which should support diverse ecological communities.

2.9.3B.5 Reduction of M/T/V Through Treatment

Mobility, toxicity, and  volume of contaminants will be  reduced through  removal, not through
                                         -179-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 acres where lead occurs above 800 mg/mg in sediment and which includes approximately 1.5 acres
 of forested and scrub/shrub wetlands.  To compensate for the loss of forested and scrub/shrub
 wetlands; these areas will be replaced at a 2-to-l creation-to-loss ratio. The revegetation of the
 wetlands is based on planting 3 acres of forested wetland and 9 acres of emergent wetlands.  Forested
 mitigation areas would be seeded (3 Ibs/acre) with a mixture of herbaceous plant species that do not
 form a turf and minimize competition with planted trees and shrubs.  Trees and shrubs would each
 be planted at a density of 436 plants/acre. Emergent wetland areas would be seeded at a rate of 5
 Ibs/acre and planted with plugs or bare root plantings at a density of 4,840 plants/acre.

 Land use restrictions and security fencing may be placed on the Site while the remedial action  takes
 place. Monitoring would be required to assess the effectiveness of the remedial action.

 2.9.3B.2  Overall Protection of Human Health and the Environment

 Source control of surface runoifand sediment transport will effectively eliminate a source of loading
 of contaminants to the adjacent wetlands. The removal of the contamination from the Site wetlands
 will effectively protect the environment.  Removal will also reduce risk to ecological receptors.

 The RAOs for reduction of risk to ecological receptors will be met and the alternative will restore the
 degraded wetlands1 structure and function.

 2.9.3B.3  Compliance with ARARs

 EPA's regulations (40  CFR Part  6,  Appendix A) for implementing Executive Order 11988
 (Floodplains Management) requires federal agencies to avoid or minimize adverse impacts of Federal
 actions upon floodplains, and to preserve and enhance the natural values of floodplains. Specifically,
when it is apparent that  a proposed or potential Agency action is likely to impact a floodplain or
wetlands, the public should be informed through appropriate public notice processes. Furthermore,
                                         -178-

-------
                                                                          Record of Decision
.	_	Ross Metals OU#1
2.9.3B  Alternative W-3 -Excavation & Revegetation/Restoration of Wetlands
          Option B — Regrading with Biosolid Compost Material

2.9.3B.1 Description

Option B is similar to Option A except that excavated areas would be backfilled with a biosolid
compost material rather than clean fill. The compost would serve as the fill material, a metal-binding
material and as a source of fertilizer to encourage revegetation/restoration.  The compost material
may also serve to bind contaminated groundwater should it percolate through the wetland. As with
previous alternatives, a Site monitoring program would be implemented.

As is the case for Option A, excavated sediments would be stockpiled with contaminated surface
soils and  final disposition  of the contaminated wetlands sediment would follow the remedial
alternative selected for surface soils. In excavating the approximately 5.7 acres of sediment with lead
concentrations greater than 800 mg/kg to a  depth  of  -one  foot; approximately 9,300 CY of
contaminated sediment will be generated. Approximately 8,200 CY of the excavated sediment would
be considered principal-threat waste and 1,100 CY would  be considered low-level threat waste.

Treatability testing may be required to determine if pre-treatment (e.g. dewatering or stabilization)
of the wetlands sediment would be required to decrease teachability of lead and improve handling
characteristics of sediment prior to transport and disposal  in order to implement this alternative as
well as to confirm the value of using a biosolid backfill. If pre-treatment is required, the development
or selection of the process must consider the impact of the process on the wetlands community.

Excavated areas will be backfilled to the existing grade and revegetated according to the Wetlands
Revegetation Plan developed'for the RM Site wetlands (ERRT 1998).  Maintenance plans to
eliminate the intrusion of less desirable species and to promote success will be developed and Site
monitoring would also be required. The revegetation of the wetlands is based on excavation of 5.7
                                         -177-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 would be monitored at the property boundaries. Fugitive dust emissions would be controlled by
 applying water to surfaces receiving heavy vehicular traffic or in excavation areas, as needed. A
 measurable, short-term impact to the surrounding area would include increased vehicular traffic and
 associated safety hazards, potential dust generation, and noise.

 Short-term impact on biological communities in the wetlands caused by excavation will be notable
 because of excavation of wetlands sediment. However, the goal of the wetland mitigation program
 is to replace lost wetland vegetation so that wetland function and values  either will be present
 immediately following the completion of mitigation or will develop over time.  In  addition, a
 consideration of breeding seasons, and control of erosion and sedimentation in terms ofscheduling
 activities should ease short-term impact.

 2.9.3A.7  Implementability

 All services and materials for this alternative are readily available. Moderate difficulty is posed by
 conducting operations in unstable sediment substrate.  To avoid problems, excavation can be limited
 to dry periods.  Revegetation will be performed in the spring and will require one  month  for
 completion.

2.9.3A.8 Cost

The total  present worth cost for Alternative W-3, Option A is approximately $780,071.  The
estimated capital cost is $700,901. The estimated annual O&M cost is approximately $79,170.
                                         -176-

-------
o
Record of Decision
Ross Metals OU#1
           ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
           heavy vehicular traffic and to excavation areas, as necessary.
          2.9.3A.4 Long-Term Effectiveness and Permanence

          This alternative provides source control and removal of contaminated sediments in the wetlands. This
          action would permanently remove contaminated sediments and thereby reduce risk to ecological
          receptors and improve water quality. The revegetation plan will restore the wetlands to a high
          functioning value which should support diverse ecological communities.

          2.9.3A.5 Reduction of M/T/V Through Treatment

          Mobility, toxicity, and volume of contaminants will be  reduced through removal, not through
          treatment.

          2.9.3A.6 Snort-Term Effectiveness

          The construction phase  of this alternative would likely be accomplished within one field season;
          therefore, impacts associated with construction would likely be short-term and minimal. Short-term
          impacts  are associated with excavation;  however,  these potential, short-term impacts would be
          mitigated during the wetlands restoration phase. The revegetation plan uses plant species which
          should restore the system within one growing season, thereby limiting the impacts. Controls can be
          implemented to reduce impacts on adjacent wetlands.

          On-Site workers would be adequately protected by using appropriate personal protective equipment
          and by following proper operating and safety procedures. However, short-term air quality impacts
          to the surrounding environment may occur during waste consolidation and grading. Dust emissions

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
The RAOs for reduction of risk to ecological receptors will be met and the alternative will restore the      *
degraded wetlands' structure and function.
                                                                                              m
2.9.3A.3 Compliance with ARARs

EPA's regulations (40  CFR  Part 6, Appendix A) for implementing Executive  Order  11988
(Floodplains Management) requires federal agencies to avoid or minimize adverse impacts of Federal
actions upon floodplains, and to preserve and enhance the natural values of floodplains.  In addition,
EPA's regulations (40  CFR  Part 6, Appendix A) for implementing Executive'  Order  11988
(Floodplains Management) requires federal agencies to avoid or minimize adverse impacts of Federal
actions upon floodplains, and to preserve and enhance the natural values of floodplains. Specifically,
when it is apparent that a proposed  or potential Agency action is likely to impact a floodplain or
wetlands, the public should be informed through appropriate public notice processes. Furthermore,
if a proposed action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment
shall be undertaken, and a statement of findings explaining why the proposed action must be located
in or affect the floodplain or wetlands.

The Protection of Wetlands Order (40 CFR 6) requires that no adverse impacts to wetlands result
from a remedial action.  The wetlands revegetation component of this alternative includes a 2-to-l
creation-to-loss ratio to compensate for the loss of forested and scrub/shrub wetlands which is
expected to meet the wetlands mitigation requirements of CWA Section 404.

The substantive requirements for stormwater discharges during construction activities as outlined by
the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this
remedial action.

All action-specific ARARs are expected to be met.  The TAPCR dust suppression  and control
requirements (Rule 1200-3-8) apply to  earth-moving activities associated with this alternative.

                                         -174-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 sediment would be considered principal-threat waste and 1,100 CY would be considered low-level
 threat waste.

 Treatability testing may be required to determine if pre-treatment (e.g. dewatering or stabilization)
 of the wetlands sediment would be required to decrease leachability of lead and improve handling
 characteristics of sediment prior to transport and disposal in order to implement this alternative.  If
 pre-treatment is required, the development or selection of the process must  consider the impact of
 the process on the wetlands community.

 The revegetation of the wetlands is based on excavation of 5.7 acres where lead occurs above 800
 mg/mg in sediment and which includes approximately 1.5 acres of forested and scrub/shrub wetlands.
 To compensate for the loss of forested and scrub/shrub wetlands; these areas will be replaced at a 2-
 to-1 creation-to-loss ratio. The revegetation of the wetlands is based on planting 3 acres of forested
 wetland and 9 acres of emergent wetlands. Forested mitigation areas would be seeded (3 Ibs/acre)
 with a mixture of herbaceous plant species that do not form a turf and minimize competition with
 planted trees and shrubs.  Trees and shrubs would each be planted at a density of 436 plants/acre.
 Emergent wetland areas would be seeded at a rate of 5 Ibs/acre and planted with plugs or bare root
 plantings at a density of 4,840 plants/acre.

 Deed restrictions may be placed on the Site while the remedial action takes place. Monitoring would
 be required to assess the effectiveness of the remedial action.

 2.9.3A.2 Overall Protection of Human Health and the Environment

 Source control of surface runoff and sediment transport will effectively eliminate a source of loading
 of contaminants to the adjacent wetlands. The removal of the contamination from the Site wetlands
will effectively protect the environment. Removal will also reduce risk to ecological receptors.
                                          -173-

-------
                                           -ZLl-
 pajBABOxa aqijo ^3 QOZ'8 ApjBunxojddy 'pajBjanaS aq IJIA\ jaaunpas pajBtnureiuoD jo ^3 QOE'6
 AiajBunxojddB Uooj auo jo qtfap B oj 3>j/gui Q08 a^RJ Jaisajg snoiiBJiuaouoo pBaj qjiM. inaunpas
 jo sajoB //£ A"iajBunxo.iddB sqj guijBABoxa iq  -ApjBjredss jo pssodsip PUB psqoinui ao
 P9JBABOX9 qjiA^ pgjBpjiosnoo aq ppoM IBUSJBUI joBid paiBABoxa 'spAaj psiBuiurejuoD no
 •sijos aoBpns JQJ papsps aAi}BUjaj{B iBipauiaj aqj Avonqj pinoM jnaunpas spireiia
 aqjjo uoijisodsip iBug pns sfios aoBjans paiBorurejnoo qjiM pajid^oojs aq pjnoAV sjuaunpas pajBABoxg
 •pajinbaj aq OSJB pjnoA\ Souojiaoui ajig pnB padojaAap aq n?M ssaoons ajoraoad oj puB sapads
 ajqBJisap ssa] jo uoisruim aqj ajBaiunia oj snBjd aotreaaiurejAi  -(8661  1¥H3) spoB^aM ajig pra
 aqi JDJ padojaAap OBIJ aoijBiagaAa-y- spuBpa^ aqj oj SmpaoooB pajsjaSaAaj PUB apBj§ Smjsixa aqj
 °* PZWPPvq. aq TIF^ SB3JB pajBABOxg -s\ios uBap qjiM jBuajBiujBqi SmoBidaj 'y ooiido Japan
 'jooj aao jo qjdap B 01 sjuaunpas puBpaM pajBurarejuoo jo noiiBABDxa aqi saAjOAin £-
                                                                                l'V£'6'Z

                                       IRA UBao VIM §uipB4§3^[ -
              'I9l'0£$ A>JBiuixojddB si isoo jAi^o psiBunjsa aqj puB 't09'Ii7S$ XpiBunxojddB si
jsoo |BjidBo paiBunjsa aqx 'Z9C 1 19$ ApJBunxoaddB Si i-j^ aAijBoiajiv JOj qyoA\ jnasajd JBIOI
                                   iBAB XjipBaj ajB aAijBtuai|B siqi aoj sjBuajBui PUB saoiAjas
  •jndm aptAOjd oj paA\onB ajB sapnagB paAjoAm JJB }Bqj ajnsna oj UOIJOB aqj SmnnBid ajiqM .
pinoqs uoijBJinsaoo aouBApy 'paiinbaj aq 01 pajoadxa ajB sjrauad (3QDV) sjaauiSagjo sdiO3 Xuuy

                                          •pajajnnooaa aq 01 pajoadxa ajB sanssi noiiDaiisuoo
l#no
UOIS;03Q JO

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 This alternative would not meet EPA's expectation to use treatment to address the principal threats
 posed by a site, although in some situations, containment of principal threats is warranted (EPA
 1 99 1 ). Based on sample results collected during previous Site investigations, 8,700 CY of sediment
 would be considered "principal-threat" waste.

 Containment of principal threats may be warranted where treatment technologies are not technically
 feasible or available within a reasonable time frame; or where the volume of materials or complexity
 of the site makes implementation of treatment technologies infeasible; or where implementation of
 a treatment-based remedy would result in greater overall risk to human health and the environment
 or cause severe effects across environmental media. A review of currently available technologies and
 Site conditions does not suggest that these situations would apply to the RM Site.

2.9.2.6  Short-Term Effectiveness

The construction phase of this alternative would likely be accomplished within one field season;
therefore, impacts associated with construction would likely be short term and minimal.

On-Site workers would be adequately protected from short-term risks by using appropriate personal
protective equipment and by following proper operating and safety procedures.
The wetland system would be destroyed since application of the cap will alter grade and hydrology.
A measurable, short-term impact to, the surrounding area would include increased vehicular traffic
and associated safety hazards, potential dust generation, and noise.

2.9.2.7  Implementability

Construction of a soil cap is a standard construction practice and materials are readily available.
Other than the capping of contaminated  material in  a floodplain  and wetland, no significant
                                          -171-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 All action-specific ARARs are expected to be met.  The TAPCR dust suppression and control
 requirements (Rule 1200-3-8) apply to earth-moving activities associated with this alternative.
 ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
 heavy vehicular traffic and to excavation areas, as necessary.

 2.9.2.4  Long-Term Effectiveness and Permanence

 Under this alternative, the cap would have to be maintained to ensure that it continues to perform as
 designed; consequently, long-term monitoring, inspection, and maintenance would be required. The
 cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover
 integrity by deep-rooting vegetation and bun-owing animals. The cover would need to be periodically
 inspected, and required maintenance would need to be implemented in order to maintain effectiveness.

 The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
 design and grading layout.  In addition, access restrictions such as land use controls and fencing
 would be required to prevent land uses incompatible with the Site; specifically, land uses that would
 compromise the cap should be precluded.

 The remedial action objectives of reduction of exposure and prevention of transport and migration
 of Site contaminants, and prevention of degradation of adjacent wetlands will be achieved. However,
the restoration of wetland communities and elimination of further degradation of the Site wetlands
will not be achieved.

2.9.2.5 Reduction of M/T/V Through Treatment

This alternative will not remove or dispose of the contamination. Contaminated sediment will be left
intact but the pathway of exposure will be reduced for multiple receptors. Toxicity may be  reduced
by limiting bioavailability. The volume of material  at the  Site will not be altered.
                                          -170-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
          temporary water storage capacity of the floodplain; and
          The facility is designed, constructed, operated, and maintained to prevent washout of any
          solid waste.
 The Protection of Wetlands Order (40 CFR 6) requires that no adverse impacts to wetlands result
 from a remedial action.  With appropriate stormwater runon and runoff controls, the substantive
 requirements of this ARAR are expected to be met.  In addition, the  off-Site creation of wetlands
 component of this alternative to compensate for the loss of forested and scrub/shrub wetlands  is
 expected to meet the wetlands mitigation requirements of CWA Section 404. The SWPD rule
 requires that new landfills and lateral expansions shall not be located in a wetlands, unless the owner
 or operator can make the following demonstrations:

     »    the presumption of a practicable alternative that does not involve wetlands is clearly
          rebutted;
     »    the construction/operation of the landfill will not cause or contribute to violations of
          applicable State water quality standards,  any applicable  toxic effluent standard or
          prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
          of  any endangered or threatened species or result in the destruction or adverse
          modification of critical habitat of endangered or threatened species;
     «    the landfill will not cause or contribute to significant degradation of wetlands;
     «    to the extent required under Section 404 of the CWA or Tennessee Water Pollution
          Control Act, steps  have been taken to attempt to achieve no net loss  of wetlands (as
          defined by acreage and function); and
     »    sufficient information is available to make a reasonable determination with respect to these
          demonstrations.

The substantive requirements for stormwater discharges during construction activities as outlined by
the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this
remedial action.
                                          -169-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
2.9.2.3 Compliance with ARARs

The RCRA hazardous waste disposal facility requirements are potentially apph'cable. The RM Site
is located in a 100-year floodplain within a zone designated  as A3, indicating that base flood
elevations and flood hazard factors have been determined for this area. The ARAR (40 CFR 264)
requires that disposal facilities be designed to withstand a 100-year flood.  In addition, EPA's
regulations (40 CFR Part 6, Appendix A) for implementing Executive Order 11988 (Floodplains
Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
floodplains, and to preserve and enhance' the natural values of floodplains. Specifically, when it is
apparent that a proposed or potential Agency action is likely to impact a floodplain or Wetlands, the
public should be informed through appropriate public notice processes.  Furthermore, if a proposed
action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be
undertaken, and a statement of findings explaining why the proposed action must be located in or
affect the floodplain or wetlands.

Regarding construction activities related to implementing the alternative, 40  CFR 6 Appendix A
requires that EPA-controlled structures and facilities must be constructed in accordance with existing
criteria and standards set forth under the NFIP  and must include mitigation of adverse impacts
wherever feasible, including the use  of accepted  floodproofing and/or other  flood protection
measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
base flood level rather than filling land.  In addition, the capped area may be classified as a Tennessee
SWPD Class II disposal facility. If so, the substantive requirements of the SWPD rule regarding
Class II disposal facilities (e.g., siting) would apply to the Site. The SWPD rule (Rule 1200-1 -7) and
the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR 257) require
that disposal facilities must not be located in a 100-year floodplain, unless both of the following can
be demonstrated:

     •   Location in the floodplain will not restrict the flow of the 100-year flood nor reduce the
                                         -168-

-------
o
Record of Decision
Ross Metals OU#1
         2.9.2 Alternative W-2 - Capping with Clean Fill and Off-Site Creation of Wetlands

         2.9.2.1  Description

         Capping the contaminated sediment in the wetlands at the RM Site would serve to prevent rainfall
         infiltration and future leaching into the groundwater. In addition, capping also would limit direct
         contact  exposure to contaminated media under the cap.  Varying degrees of capping can be
         implemented depending on the severity of contaminants in the area.  Caps can range from a simple
         natural soil cap to a multilayer soil/synthetic cap.  For the wetlands, a foot of topsoil would be placed
         on the surface of the contaminated wetland sediment and graded evenly.  Capping with a minimum
         of one foot of clean fill would be required to eliminate multiple exposure pathways as identified in
         the ecological risk assessment.  The cap would be applied to the approximately 5.7 acres of wetlands
         containing sediment with lead concentrations greater than 800 mg/kg. Because this action results in
         a destruction of the wetlands by altering the grade and hydrology of the system, off-Site creation of
         wetlands is required to compensate for the loss.

         Alternative W-2 would eliminate direct contact  with contaminated media, minimize  contaminant
         migration to groundwater, and eliminate contaminant migration.  Land use restrictions and security
        fencing may be placed on the  Site while the remedial action  takes place.  Monitoring would be
        required to assess the effectiveness of the remedial action.

        2.9.2.2 Overall Protection of Human Health and the Environment

        This alternative will not remove or contain the contaminated sediments but potentially limits multiple
        exposure pathways to ecological receptors. Organisms utilizing portions of the wetlands below the
        surface may potentially continue to be exposed. The volume and concentration in the wetland will
        not be altered. Lead and other metals in the wetland sediment may continue to result in adverse
        impacts.
                                                 -167-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 2.9.1.4 Long-Term Effectiveness and Permanence

 The remediation goals derived for protection of ecological receptors would not be met.  Because
 contaminated wetland sediment remains under this alternative, a  review/reassessment of the
 conditions at the Site would be performed at 5-year intervals to ensure that the remedy does not
 become a greater risk to human health and the environment.

 2.9.1.5 Reduction of M/T/V Through Treatment

 No reductions in contaminants M/T/V are realized under this alternative.

 2.9.1.6 Short-Term Effectiveness

 Since no further remedial action would be implemented at this Site, this alternative poses no short-
term risks to  onsite workers. It is assumed that Level D personnel protection would be used when
sampling various media.

2.9.1.7 Implementability

This alternative could be implemented immediately since monitoring equipment is readily available
and procedures are in place.

2.9.1.8 Cost

Minimal costs are associated with this alternative relative to other remedial action alternatives. No
capital costs  are associated with this alternative.  The estimated O&M cost  is approximately
$100,247.
                                         -166-

-------
                  Table 2-19






Summary of Wetland Sediment Alternatives Evaluation
I Remedial Alternative
1 -No Action
2 —Capping w/Clean
Fill and Off-Site
Creation of Wetlands
3 A- Excavation «nd
RevegetauW
Restoration of Wetlands
andRegradingwhh
Clean Fill
SB-Excavation and
Revegeution'
Rcjteralico of Wetlands
ahdRegradtngwith
Biowlid Compost
Threshold Criteria
OveraQ Protection of Human
Health and the Environment
Doe not eliminate exposure
pathways or reduce the level of
risk. Does not limit migration of
or remove contaminant*.
Potentially eliminates multiple
exposure pathways to ecological
receptors. Organisms utilizing
portions of the wetlands below
the surface may potentially
continue to be exposed
Eliminates exposure pathways
and reduces the level of risk.
Remove] contamination and
restores functional value of
contaminated u-etlindt.
Eliminate! exposure pathways
and reduces the level of risk.
Removes contamination and
restores functional value of
ceMamiiuled wetlands.
Compliance Kith
ARARs
Chemical-specific
ARARs are not met
Location- and
action-specific
ARARs do not
apply.
Does not meet
ARARS for
protection of
wetlands.
All action-specific
ARARs are expected
o be met Location-
pecific ARARs are
applicable and
would need to be
met.
All action-specific
ARARs are expected
be met. Location-
specific ARARt are
applicable and
DuMnecdlobe
nut

Lont-Term Eflectivenen
and f ennanence
The contaminated material is
a long-term impact The
remediation goals are not met
Will reduce or eliminate
viable exposure pathway! and
prevent degradation of
adjacent wetlands No residual
risk* from the alternative.
Long -term effectiveness
requires cap maintenance
Long-term ecological threats
associated with sediment are
{really reduced. No residual
risks from the alternative.
Long -term effectiveness
require] cap maintenance
Long-term ecological threats
associated with jedimenl are
ptaUy reduced. No residual
rislct from the ahemuive.
Long -term effectiveness
requira cap maintenance
Balancing Criteria
Reduction of MOW Through
Treatment
No reduction of MOW 'a realized.
Reduction of mobility is realized but
contaminant volume or toxraty are
not reduced. For the principal threat
waste at the She, does not meet
EPA's expectation to treat principal
threat waste.
deduction of mobility, toricity, and
volume is achieved through
removal, not treatment
eduction ofmobility, Io.ticity,«nd
volume it achieved through
emoval. not treatment
Additionally, use ofbiosolid
conipoa reducej lankily by liaiiimg
oiviaability of conlininanU.

Short-Term EfTectiv«Ku
Level D protective equipment is
required during sampling.
Level C and D protective
equipment required during She
activities. Grading may result in
potential release of dust Noise
nuisance from use of heavy
equipment
Level C and O protective
equipment required during SHe
activities. Excavating and grading
may result in potential release of
dust Short-term impacts to the
wetlands from excavating activities
will occur.
.evel C and D protective
equipment required during Site
activities. Excavating and grading
oay result in potential release of
uL S)iorMcmi impacts to the
tmlands from excavating activities
wiBoccw.

ImpIementablUty
Technical/Engineering
ConsMerafloni
None
Capping in a floodplaia and
wetlands.
s'one
•one.

Estimated Time for
<1
<1
<1


y 	
Cost
Approi. Total Proent
Worth
	 _
S100.247
— 	 _J
$611,752
$780.071 *"
-^— ^•^"— ^^-^_^_
K»^«
	 1
                -165-

-------
                                                                      Record of Decision
                                                                         Ross Metals OU#1
creation of wetlands, composting/fixation of wetlands sediment with off-Site creation of wetlands,
capping  with off-Site creation of wetlands, and excavation and grading with either clean fill or
composting and revegetation. Table 2-19 is a summary of the wetland alternatives considered.

2.9.1 Alternative W-l ~ No Action

2.9.1.1 Description

Under this alternative, no remedial action would be taken with respect to the wetlands. A monitoring
program would be implemented to address wetland sediments, surface water and associated uptake
by biota utilizing the affected area. The monitoring program would be developed in order to allow
for regulators to assess the migration of the contaminants from the wetlands and determine if remedial
actions might be necessary in the future. The monitoring program would take place on a yearly basis
with a risk evaluation conducted within 5 years to determine the effectiveness of this approach.

2.9.1.2 Overall Protection of Human Health and the Environment

The no action alternative does not eliminate any exposure pathways or reduce the level of risk of the
existing wetland sediment contamination.

2.9.1.3 Compliance with ARARs

This alternative does not  achieve the RAOs or chemical-specific ARARs established for wetland
sediment. Location- and action-specific ARARs do not apply to this alternative since further remedial
actions will not be conducted.
                                         -164-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 low level-threat material in a floodplain,  no significant construction issues are expected to be
 encountered.

 Treatment of contaminated soil and slag is offered by numerous vendors. On-Site treatment utilizes
 standard construction practices and material handling equipment. No significant construction issues
 are expected to be encountered.

 Treatment of the  contaminated waste will likely increase the volume of the waste soil and slag
 material; however, slight volume reductions may occur when some chemical reagents are used to treat
 the material.  Typical volume increases range from about 5 percent to as high as 100 percent,
 depending upon the treatment method used. An increase in the volume of the treated waste material
 will have an impact on the disposal volume  required. Calculations used in the development of this
 alternative utilized  a volume increase estimate of 5 percent.

 All services and materials for this alternative are readily available.

 2.8.6B.8 Cost

The total present worth for Alternative S-6B is approximately $4,936,044 for Option  1, which
includes the excavated wetlands sediment, and $4,013,508 for Option 2, which does not include the
wetland sediment.  For Option 1, the estimated capital cost is approximately $4,776,149, and the
estimated O&M cost is approximately $159,895. For Option 2,  the estimated capital cost is
approximately  $3,853,613 and the estimated O&M cost is approximately $159,895.

2.9 WETLAND SEDIMENT ALTERNATIVE ANALYSIS

The alternatives that were selected for surface soil at the RM Site include no action, institutional
controls and off-Site creation of wetlands, surface water and sediment control/diversion with off-Site
                                         -163-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 This alternative would meet EPA's expectation to use treatment to address the principal threats posed
 by a Site, as well as EPA's expectation to use containment to address low-level threats posed by a
 site. Based on sample results collected during previous Site investigations,  600 CY of surface soil
 and the 16,000 CY of stockpiled and landfilled slag would be considered "principal-threat" waste.

 2.8.6B.6  Short-Term Effectiveness

 The construction phase of this alternative would likely be accomplished within one field season;
 therefore, impacts associated with construction would likely be short-term and minimal.  Short-term
 impacts are associated with excavation and consolidation of waste soil and slag; however, these
 potential, short-term impacts would be mitigated during the construction phase.

 If the excavated material is dry, on-Site workers will be exposed to waste soil and slag  dust during
 excavation and consolidation activities. Additional exposure to lead dust may occur during building
 structure and pavement demolition. Ingestion of dust could involve some health effects because of
 the high level of metals in waste soil and slag.

 On-Site workers would be adequately protected by using appropriate personal protective equipment
 and by following proper operating and safety procedures.  However, short-term air quality impacts
 to the surrounding environment may occur during waste consolidation and grading.  Dust emissions
 would be monitored at the property boundaries. Fugitive dust  emissions would be controlled by
 applying water to surfaces receiving heavy vehicular traffic or in excavation areas, as  needed.  A
 measurable, short-term impact to the surrounding area would include increased vehicular traffic and
 associated safety hazards, potential dust generation,  and noise.

 2.8.6B.7 Implementability

Construction of a geomembrane surface cap is a standard construction practice. Other than capping
                                          -162-

-------
fft
                                                                          Record of Decision
 	„,	.    	      Ross Metals OU#1
 All action-specific ARARs are expected to be met.  The TAPCR dust suppression and control
 requirements (Rule 1200-3-8) apply to earth-moving activities associated with this alternative.
 ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving
 heavy vehicular traffic and to excavation areas, as necessary.

 2.8.6B.4  Long-Term Effectiveness and Permanence

 Under this alternative, the cap would have to be maintained to ensure that it continues to perform as
 designed; consequently, long-term monitoring, inspection, and maintenance would be required. The
 cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover
 integrity  by deep-rooting  vegetation  and burrowing animals.   However, the cover  would be
 periodically inspected, and required maintenance could be implemented.

 The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
 design and grading layout.  In addition, access restrictions such as land use controls and fencing
 would be required to prevent land uses that are incompatible with the Site; specifically, land uses that
 would compromise the cap  should be precluded.

 2.8.6B.5 Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to reduce contaminant mobility by isolating contaminants
 from receptor contact; contaminant volume or toxicity would not be reduced.  Contaminant mobility
 would be reduced by installing an impermeable cap liner. The liner would eliminate surface water or
 precipitation infiltration and  would greatly  reduce contaminant migration to groundwater in
 conjunction with the existing clay unit beneath the Site.  Consolidation and capping would isolate
waste source areas and reduce contaminant mobility resulting from surface water transport and wind
erosion. Contaminant mobility is expected to be reduced to an extent that would result in overall risk
reduction from all pathways and exposure routes.
                                         -161-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
          temporary water storage capacity of the floodplain; and

      •   The facility is designed, constructed, operated, and maintained to prevent washout of any
          solid waste.
 Wetlands are located to the north and northeast of the facility and landfill, although these locations
 are not identified on NWI maps. The Protection of Wetlands Order (40 CFR 6) requires that no
 adverse impacts to wetlands result from a remedial action.  With appropriate stormwater runon and
 runoffcontrols, the substantive requirements of this ARAR are expected to be met.  The SWPD rule

 requires that new landfills and lateral expansions shall not be located in a wetlands, unless the owner
 or operator can make the following demonstrations:


      •    the presumption of a practicable alternative that does not involve wetlands is clearly
          rebutted;

      •    the construction/operation of the landfill will not cause or contribute to violations of
          applicable State water quality standards,  any applicable  toxic effluent  standard or
          prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
          of any endangered or threatened species  or result in the  destruction or adverse
          modification of critical habitat of endangered or threatened species;

      •    the landfill will not cause or contribute to significant degradation of wetlands;

      •    to the extent required under Section 404 of the CWA or Tennessee Water Pollution
          Control Act, steps have been  taken to attempt to achieve no net loss of wetlands (as
          defined by acreage and function); and

      •    sufficient information is available to make a reasonable determination with respect to these
          demonstrations.
The substantive requirements for stormwater discharges during construction activities as outlined by
the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this
remedial action.
                                          -160-

-------
o
                                                                          Record of Decision
                                                                  	Ross Metals OU#1
2.8.6B.3 Compliance with ARARs
          The RCRA hazardous waste disposal facility requirements are potentially applicable. The RM Site
          is located in a 100-year floodplain within  a zone designated as A3, indicating that base flood
          elevations and flood hazard factors have been determined for this area. The ARAR (40 CFR 264)
          requires that disposal facilities be designed to withstand a 100-year flood.  In  addition,  EPA's
          regulations (40 CFR Part 6, Appendix A) for implementing Executive Order 11988 (Flo'odplains
          Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
          floodplains, and to preserve and enhance the natural values of floodplains.  Specifically, when it is
          apparent that a proposed or potential Agency action is likely to impact a floodplain or wetlands, the
          public should be informed through appropriate public notice processes. Furthermore, if a proposed
          action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be
          undertaken, and a statement of findings explaining why the proposed action must be located in or
Mi      affect the floodplain or wetlands.

         Regarding construction activities related to implementing the alternative, 40 CFR 6 Appendix A
         requires that EPA-controlled structures and facilities must be constructed in accordance with existing
         criteria and standards set forth under the NFIP and must include mitigation of adverse impacts
         wherever feasible,  including the use of accepted floodproofing  and/or other flood  protection
         measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
         base flood level rather than filling land. In addition, the capped area may be classified as a Tennessee
         SWPD Class II disposal facility. If so, the substantive requirements of the SWPD rule regarding
         Class II disposal facilities (e.g., siting) would apply to the Site. The SWPD rule (Rule 1200-1-7) and
         the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR 257) require
         that disposal facilities must not be located in a 100-year floodplain, unless both of the following can
         be demonstrated:
•i

             •   Location in the floodplain will not restrict the flow of the 100-year flood  nor reduce the
                                                  -159-

-------
SOUTH
                                                                                        NORTH
                                                              WRECKER
                                                              BUILDING
                                                                                                           SURFACE DEPOSITION OF
                                                                                                          LEAD CONTAMINATED  OUST.
                                                                                                            SOILS, AND SEDIMENT
                                                                                                                            LANDFILL
             DEPTH AT WHICH
        GROUNDWATER ENCOUNTERED
                                                                         6" TOPSfflL
              GEOTEXTILE
                LINER
                    DEPTH AT WHICH
               GROUNDWATER ENCOUNTERED
                                                           NOT TO SCALE
                                                                                                APPROXIMATE DIMENSIONS OF EXCAVATION:  TOTAL DEPTH - 5 FT.
                                                                                                                                LENGTH - 250 FT.
                                                                                                                                WIDTH - 450 FT.
 NOTE: Conceptual d««lgn.  Federal, state, and local
 r«qulr«m«nta regarding construction In a floodploln
 must ba considered and mgy affect design
 Representation of wavte material Includen excavated
 wetland sediments.
                                                     Ross Metals  Site
                                                   Rossville,  Tennessee
CDM Federal Programs Corporation
X xMbfa? a/ tear Dnsxr i HcJ&f IK.
          Alternative  6B
Treatment  W/Offsite  Disposal
 of  Treated Principal Threat
                Waste
                                                                                              Figure No.
                                                                                               2-29
                                                                                                                                            8/98

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 Site physical hazards, minimize contaminant migration to groundwater, and eliminate contaminant
 migration to surface water from the Site. Figure 2-29 illustrates the components of the cap included
 under Alternative S-6B as applied to the RM Site.

 2.8.6B.2 Overall Protection of Human Health and the Environment

 Successful implementation of this alternative would reduce risks to human health and the environment
 and meet the removal action objectives by (1) eliminating exposure of residents and trespassers to
 waste material by direct contact and airborne migration,  (2) eliminating exposure of trespassers to
 direct contact with on-Site physical hazards, and (3) further reduce the migration of contaminants to
 groundwater over Alternative S-2 and eliminate the migration of contaminants to  surface water.
 Consolidation and isolation of low level-threat waste material beneath a geomembrane cap would
 eliminate receptor routes of exposure through ingestion and inhalation. Structures throughout the
 Site would be demolished and disposed of in the disposal area above  the existing  pavement and
 landfill area.  The waste material would be spread and compacted throughout the  Site.  Physical
 hazards associated with deteriorating structures would be eliminated.  In addition,  geomembrane
 capping  would eliminate infiltration of precipitation  and surface water that  contributes to  the
 migration of contaminants to groundwater. However, because the waste material will remain on Site,
 contaminant migration to groundwater cannot be discounted as an adverse effect. Nevertheless, the
 elimination of surface water infiltration makes this  scenario unlikely, and contaminant migration
 through surface water runoff to the adjacent wetlands and the Wolf River would be eliminated.

 The threat of direct human exposure to contaminated waste and physical hazards would be practically
 eliminated by this alternative; however, the threat could return over the long term if cap integrity was
 compromised. The potential for ingestion, dermal contact, and inhalation of soil containing metals
would be eliminated by successfully placing the geomembrane cap over the waste material.
                                          -157-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
       •   Offsite disposal of 34,335 tons of treated principal-threat waste (assuming 5% increase in
           volume due to treatment) in  RCRA Subtitle D landfill (47,250 tons if contaminated
           wetlands sediment are excavated and consolidated with surface soil for final disposition);
       •   Installation of 1.5-ft-deep soil cushion over waste and treated material and low-level threat
           material capped in place (20,300 CY);
           Installation of geomembrane liner and geotextile over soil cushion (6.7 acres);
       •    Soil cover (1 ft deep), topsoil cover (6 inches deep), and grass seeding over Site
           (8 acres); and

       •    Land use restrictions and security fencing.

 The final treatment system would depend upon the outcome of treatability testing and would be
 determined during the remedial design phase. The fixed material would be subjected to TCLP testing
 to determine if treatment has been effective, prior to placement in the excavated disposal area. Note
 that the components of this alternative are  considered a conceptual design, but other designs may be
 possible.  The final design would be based on requirements regarding construction in a floodplain.

 Treatability testing may be required to demonstrate contaminant immobilization for this treatment
 process and to help determine the volume increase caused by the solidification/stabilization process.

 Land use restrictions and security fencing may be placed on the Site while the remedial action takes
 place.  Monitoring would be required to assess the effectiveness of the remedial action.

 The topsoil layer of the cap would be graded to a minimum slope of 3% and a maximum of 5% to
promote surface drainage away fromthe waste cell and reduce infiltration. Surface drainage controls
would  be constructed around the perimeter of the cap to collect surface water runoff.
Option B of Alternative S-6 would eliminate direct contact with contaminated media, eliminate

                                         -156-
on-

-------
                                                                           Record of Decision
	_____	Ross Metals OU#1

by steam/pressure cleaning. Onsite contaminated soil considered principal threat, and buried slag in

the landfill would be excavated and consolidated with the stockpiled slag.  In addition, contaminated

soil from areas not covered by pavement, and non-principal-threat landfill soil would be excavated

for placement in the excavated onsite landfill. This low level-threat waste material would be disposed

in the excavated landfill area (450 x 250 ft x 5 ft deep).  A geosynthetic cap and underlying 1.5-ft soil

cushion layer would be added above the waste and existing landfill and would cover about 2.5  acres.
A 1-ft soil cover and 6-inch topsoil layer would be placed over the entire Site.


For treatment, contaminants within soil and slag would be physically bound or enclosed within a

stabilized mass (solidification), or chemical reactions would be induced between a stabilizing  agent

and the contaminant to reduce its mobility (stabilization).  The decontaminated building debris would
be taken offsite to a metal recycling facility. The components of this alternative are outlined  as
below:


          Decontamination and demolition of buildings;

     •    Recycling of metal building debris;

          Excavation of principal-threat contaminated soil (500 CY), landfilled slag (10,000  CY),
          and non-principal threat landfill soil (6,500  CY) to allow access to landfilled  slag.
          (Excavation of an additional 8,200 CY of principal-threat contaminated wetland sediment
          and 1,100 CY of non-principal threat contaminated wetland sediment if  contaminated
         wetland sediments are excavated and consolidated with surface  soil for final disposition);

     •    Stabilization  or solidification of principal-threat contaminated soil and wetland sediment,
         stockpiled slag, and landfilled slag (about 32,700; 45,000 tons if contaminated wetland
         sediments are excavated and consolidated with surface soils for final disposition);

     •   Excavation of on-site disposal area (450 ft long by 250 ft wide by 5 ft deep) in landfill area;

         Compaction of 6,500 CY of low-level (non-principal threat) waste material (7,600 CY if
         contaminated wetland sediments are excavated and consolidated with surface  soil for final
         disposition;
                                          -155-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 depending upon the treatment method used.  An increase in the volume of the treated waste material
 will have an impact on the disposal volume required. Calculations used in the development of this
 alternative utilized a volume increase estimate of 5 percent.

 The on-Site disposal area for the treated waste may be classified as a Class II disposal facility. If so,
 the substantive requirements of the SWPD rule regarding Class II disposal facilities would apply to
 the Site.

 All services and materials for this alternative are readily available.

 2.8.6A.8  Cost

 The total present worth for Alternative S-6A is approximately $3,175,137 for Option 1, which
 includes the excavated wetlands sediment, and $2,729,543 for Option 2, which does not include the
 wetland sediment. For Option 1, the estimated capital cost is approximately $3,015,241, and the
 estimated O&M cost is approximately $159,895. For Option  2,  the estimated capital cost is
 approximately $2,569,647, and the estimated O&M cost is approximately $159,895.

 2.8.6B  Alternative S-6 - Capping w/ Excavation & Onsite Treatment of
                    Principal Threat Waste
                    Option B - Offsite Disposal of Treated Principal-Threat Waste

 2.8.6B.1 Description

 Option B is similar to Option A except that treated principal-threat waste is disposed offsite in a
RCRA subtitle D landfill rather than being capped onsite with the low-level threat waste. Like Option
A, Option B for Alternative S-6 includes the demolition of most of the on-Site buildings.  The main
office building would remain on Site. The building debris and pavement would be decontaminated
                                         -154-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
potential, short-term impacts would be mitigated during the construction phase.
If the excavated material is dry, on-Site workers will be exposed to waste soil and slag dust during
excavation and consolidation activities. Additional exposure to lead dust may occur during building
structure and pavement demolition. Ingestion of dust could involve some health effects because of
the high level of metals in waste soil and slag.

On-Site workers would be adequately protected by using appropriate personal protective equipment
and by following proper operating and safety procedures. However, short-term air quality impacts
to the surrounding environment may occur during waste consolidation and grading. Dust emissions
would be monitored at the property boundaries. Fugitive dust emissions would be controlled by
applying water to surfaces receiving heavy vehicular traffic or in excavation areas, as needed.  A
measurable, short-term impact to the surrounding area would include increased vehicular traffic and
associated safety hazards, potential dust generation, and noise.

2.8.6A.7 Implementability

Construction of a geomembrane surface cap is a standard construction practice. Other than capping
treated and low level-threat material in a floodplain, no significant construction issues are expected
to be encountered.

Treatment of contaminated soil and slag is offered by numerous vendors. On-Site treatment utilizes
standard construction practices and material handling equipment. No significant construction issues
are expected to be encountered.

Treatment of the contaminated waste will likely increase the volume of the waste soil and slag
material; however, slight volume reductions may occur when some chemical reagents are used to treat
the material.   Typical  volume increases range  from about 5 percent to as high as  100 percent,
                                          -153-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  periodically inspected and maintained.

  The long-term effectiveness of capping the waste would be enhanced by selecting the proper cover
  design and grading layout.  In addition, access restrictions such as land use controls and fencing
  would be required to prevent land uses that are incompatible with the Site; specifically, land uses that
  would compromise the cap should be precluded.

  2.8.6A.5 Reduction of M/T/V Through Treatment

  The primary objective of this alternative is to reduce contaminant mobility by isolating contaminants
  from receptor contact; contaminant volume or toxicity would not be reduced. Contaminant mobility
 would be reduced by installing an impermeable cap liner. The liner would eliminate surface water or
 precipitation infiltration and would  greatly reduce contaminant migration to groundwater  in
 conjunction with the existing clay unit beneath the Site. Consolidation and capping would isolate
 waste source areas and reduce contaminant mobility resulting from surface water transport and wind
 erosion. Contaminant mobility is expected to be reduced to an extent that would result in overall risk
 reduction from all pathways and exposure routes.

 This alternative would meet EPA's expectation to use treatment to address the principal threats posed
 by a site, as well as EPA's expectation to use containment to address low-level threats posed by a site.
 Based on sample results collected during previous Site investigations, 600 CY of surface soil  and
 the 16,000 CY of stockpiled and landfiUed slag would be considered "principal-threat" waste.

 2.8.6A.6  Short-Term Effectiveness

The construction phase of this alternative  would likely be accomplished within one field season;
therefore, impacts associated with construction would likely be short-term and minimal. Short-term
impacts are associated with excavation and consolidation of waste soil and slag; however, these
                                          -152-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
          the presumption of a practicable alternative that does not involve wetlands is clearly
          rebutted;

          the construction/operation of the landfill will not cause or contribute to violations of
          applicable State water quality standards,  any applicable toxic effluent  standard or
          prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
          of any  endangered or threatened species or result in the destruction  or adverse
          modification of critical habitat of endangered or threatened species;

          the landfill will not cause or contribute to significant degradation of wetlands;

          to the extent required under Section 404 of the CWA or Tennessee Water Pollution
          Control Act, steps have been taken to attempt to achieve no net loss of wetlands (as
          defined by acreage and function); and

          sufficient information is available to make a reasonable determination with respect to these
          demonstrations.
The substantive requirements for stormwater discharges during construction activities as outlined by

the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this

remedial action.


All action-specific ARARs are expected to be met.   The TAPCR dust suppression and control

requirements (Rule 1200-3-8) apply to earth-moving activities associated with this  alternative.

ARARs for the control of fugitive dust emissions would be met by applying water to roads receiving

heavy vehicular traffic and to excavation areas, as necessary.


2.8.6A.4 Long-Term Effectiveness and Permanence


Under this alternative, the cap would have to be maintained to ensure that it continues to perform as

designed; consequently, long-term monitoring, inspection, and maintenance would be required. The

cap would be susceptible to settlement, ponding of surface water, erosion, and disruption of cover

integrity by deep-rooting vegetation and burrowing animals.  However, the cover would be

                                          -151-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment shall be
  undertaken, and a statement of findings explaining why the proposed action must be located in or
  affect the floodplain or wetlands.

  Regarding construction activities related to implementing the alternative, 40 CFR 6 Appendix A
  requires that EPA-controIled structures and facilities must be constructed in accordance with existing
  criteria and standards set forth under the NFIP and must include mitigation of adverse impacts
 wherever feasible, including the use of accepted floodproofing and/or other flood protection
 measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
 base flood level rather than filling land. In addition, the capped area may be classified as a Tennessee
 SWPD Class II disposal facility. If so, the substantive requirements of the SWPD rule regarding
 Class II disposal facilities (e.g., siting) would apply to the Site. The SWPD rule (Rule 1200-1 -7) and
 the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR 257) require
 that disposal facilities must not be located in a 100-year floodplain, unless both of the following can
 be demonstrated:

     •   Location in the floodplain will not restrict the flow of the 100-year flood nor reduce the
          temporary water storage capacity of the floodplain; and
     •   The facility is designed, constructed, operated, and maintained to prevent washout of any
          solid waste.

Wetlands are located to the north and northeast of the facility and landfill, although these locations
are not  identified on NWI maps. The  Protection of Wetlands Order (40 CFR 6) requires that no
adverse impacts to wetlands result from a remedial action.  With appropriate stormwater runon and
runoff controls, the substantive requirements of this ARAR are expected to be met. The SWPD rule
requires that new landfills and lateral expansions shall not be located in a wetlands, unless the owner
or operator can make the following demonstrations:
                                         -150-

-------
                                                                         Record of Decision
   .	Ross Metals OU#1
groundwater over Alternative S-2 and eliminate the migration of contaminants to surface water.
Consolidation  and isolation of the waste material beneath a geomembrane cap would eliminate
receptor routes of exposure through ingestion and inhalation. Structures throughout the Site would
be demolished and disposed of in the disposal area above the existing pavement and landfill area. The
waste material would be spread and compacted throughout the Site.  Physical hazards associated with
deteriorating structures would be eliminated. In addition, geomembrane capping would eliminate
infiltration of precipitation and surface water that contributes to the migration of contaminants to
groundwater. However, because the waste material will remain on Site, contaminant migration to
groundwater cannot be discounted as an adverse effect.  Nevertheless, the elimination of surface
water infiltration makes this scenario unlikely, and contaminant migration through surface water
runoff to the adjacent wetlands and the Wolf River would be eliminated.

The threat of direct human exposure to contaminated waste and physical hazards would be practically
eliminated by this alternative; however, the threat could return over the long term if cap integrity was
compromised.  The potential for ingestion, dermal contact, and inhalation of soil containing metals
would be eliminated by successfully placing the geomembrane cap  over the waste material.

2.8.6A,3 Compliance with ARARs

The RCRA hazardous waste disposal facility requirements are potentially applicable. The RM Site
is  located in a 100-year  floodplain  within a zone designated as A3, indicating  that base flood
elevations and flood hazard factors have been determined for this area. The ARAR (40 CFR 264)
requires that disposal facilities be designed to withstand a 100-year flood.  In addition, EPA's
regulations (40 CFR Part 6, Appendix A) for implementing Executive Order 11988  (Floodplains
Management) requires federal agencies to avoid or minimize adverse impacts of Federal actions upon
floodplains, and to preserve and enhance the natural values of floodplains. Specifically, when it is
apparent that a proposed or potential Agency action is likely to impact a floodplain or wetlands, the
public should be informed through appropriate public notice processes. Furthermore, if a proposed
                                          -149-

-------
    SOUTH
                                                                                          NORTH
I
                                                                                                                SURFACE DEPOSITION OF
                                                                                                                LEAD CONTAMINATED DUST,
                                                                                                                  SOILS, AND SEDIMENT

                                                                                                                                 LANDFILL
                                                                                                                                           CONTAMINATE!
                                                                                                                                            BELOW SLAG
                DEPTH AT WHICH
            GROUNDWATER ENCOUNTERED
                                                                                                                              >' TREATED AND  '^'  . V-"
                                                                                                                          '.. . LOW-L|VE'L THREAT  .
                                                                                                                            MATERIAL (WETLANDS) •'    » J
                                                                                                                                    •"
                                                                                    PAVEMENT-

                                                                                   THREA W
                     DEPTH AT WHICH
                 GROUNDWATER ENCOUNTERED
               NOT TO SCALE
                                    APPROXIMATE DIMENSIONS OF EXCAVATION:  TOTAL DEPTH (BELOW GROUND SURFACE) - 5 FT.
                                                                    TOTAL HEIGHT (BELOW GROUND SURFACE) -  6 FT.
                                                                    LENGTH - 250 FT.
                                                                    YrtDTH - 450 FT.
     NOTE:  Conceptual design.  Federal, state, and local
     requirement* regarding construction in a floodplaln
     must be considered and may affect design
     Representation of waste material Includes excavated
     wetland sediments.
                                                         Ross  Metals  Site
                                                       Rossville,  Tennessee
CDM Federal Programs Corporation
K auteJfcry rf Camp Drnxr * MrAW fee
              Alternative  6A
    Treatment  W/Onsite  Disposal
of  Treated  Principal  Threat  Waste
                                                                                               Figure No.

                                                                                                2-28
                                                                                                                                                 8/98
                                                                                                                                              9.-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 The final treatment system would depend upon the outcome of treatability testing and would be
 determined during the remedial design phase. The fixed material would be subjected to TCLP testing
 to determine if treatment has been effective, prior to placement in the excavated disposal area. Note
 that the components of this alternative are considered a conceptual design, but other designs may be
 possible.  The final design would be based on requirements regarding construction in a floodplain.

 Treatability testing may be required to demonstrate contaminant immobih'zation for this treatment
 process and to help determine the volume increase caused by the solidification/stabilization process.

 Land use restrictions and security fencing may be placed on the Site while the remedial action takes
 place. Monitoring would be required to assess the effectiveness  of the remedial action.

 The topsoil layer of the cap would be graded to a minimum slope of 3% and a maximum of 5% to
 promote surface drainage away from the waste cell and reduce infiltration. Surface drainage controls
 would be constructed around the perimeter of the cap to collect surface water runoff.

 Option A of Alternative S-6 would eliminate direct contact with contaminated media, eliminate on-
 Site physical hazards, minimize contaminant migration to groundwater, and eliminate contaminant
 migration to surface water from the Site. Figure 2-28 illustrates the components of the cap included
 under Alternative S-6A as  applied to the RM Site.

 2.8.6A.2 Overall Protection of Human Health and the Environment

 Successful implementation of this alternative would reduce risks to human health and the environment
 and meet the removal action objectives by (1) eliminating exposure of residents and trespassers to
waste material by direct contact  and airborne migration, (2) eliminating exposure of trespassers to
 direct contact with on-Site physical hazards, and (3) further reduce the migration of contaminants to
                                          -147-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
For treatment, contaminants within soil and slag would be physically bound or enclosed within a

stabilized mass (solidification), or chemical reactions would be induced between a stabilizing agent

and the contaminant to reduce its mobility (stabilization). The decontaminated building debris would
be taken offsite to a metal recycling facility.  The components of this alternative are outlined as
below:


     »   Decontamination and demolition of buildings;

         Recycling of metal building debris;

         Excavation of principal-threat contaminated soil (500 CY), landfilled slag (10;000 CY),
         and non-principal  threat landfill soil  (6,500 CY)  to allow access  to  landfilled slag'
         (Excavation of an  additional 8,200 CY of principal-threat contaminated sediment and
         1,100 CY  of non-principal  threat contaminated sediment if contaminated  wetlands
         sediments are excavated and consolidated with surface soils for final disposition);

         Stabilization or solidification of principal-threat contaminated soil, stockpiled slag, and
         landfilled slag (about 32,700 tons; 45,000 tons if principal-threat wetlands sediments are
         included);

         Excavation of on-Site disposal area (450 ft long by 250  ft wide by 5  ft deep) in landfill
         area;.
         Compaction of 23,825 CY of waste material; assuming a 5% increase in volume of
         principal-threat material due to stabilization/solidification, and no increase in volume of
         non-principal threat material (33,535 CY of waste material if contaminated wetlands
         sediments are excavated and consolidated with surface soils for final disposition);

         Installation of 1.5-ft-deep soil cushion over waste and treated material and low-level threat
         material capped in place (20,300 CY);

         Installation of geomembrane liner and geotextile over soil cushion (6.7 acres);

         Soil cover (1 ft deep), topsoil cover (6 inches deep), and grass seeding over Site
         (8 acres); and

        Land use restrictions and security fencing.
                                         -146-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  wetland sediment. For Option 1, the estimated capital cost is approximately $7,313,400, and the
  estimated O&M cost  is approximately $163,799. For Option 2, the estimated capital cost is
  approximately $6,017,361, and the estimated O&M cost is approximately $163,799.

  2.8.6A Alternative S-6  - Capping w/ Excavation & Onsite Treatment of
                      Principal Threat Waste
                      Option A - Onsite Disposal of Treated Principal Threat Waste

 2.8.6A.1 Description

 Alternative S-6 is similar to Alternative S-5 in that it also includes the excavation and treatment of
 contaminated material  via solidification/stabilization.   However,  Alternative  S-6  differs  from
 Alternative S-5 in that treatment is limited to that material that is considered  principal-threat. As
 indicated in section 8.3, principal threat waste at the RM Site includes the landfiUed and stockpiled
 slag, and approximately 500 CY of soil.

 Option A for Alternative S-6 includes the demolition of most of the on-Site buildings.  The main
 office building would remain on Site.  The building debris and pavement would be decontaminated
 by steam/pressure cleaning. Onsite contaminated soil considered principal threat, and buried slag in
 the landfill would be excavated and consolidated with the stockpiled slag.  In addition, above the
 RGO, contaminated soil from areas not covered by pavement, and non-principal-threat landfill soil
 would be excavated for placement in the excavated onsite landfill along with the treated principal-
 threat waste.  This waste (and treated) material would be disposed in the excavated landfill area (450
 x 250 ft x 5 ft deep). A geosynthetic cap and underlying 1.5-ft soil cushion layer would be added
 above the waste and existing landfill and would cover about 2.5 acres. A 1-ft soil cover and 6-inch
topsoil layer  would be  placed  over  the entire Site.    The capped disposal  area would  rise
approximately 6 ft above ground surface.
                                         -145-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  2.8.5B.7 Implementability                            >.

  Treatment of contaminated soil and slag is offered by numerous vendors. On-Site treatment utilizes
  standard construction practices and material handling equipment. No significant construction issues
  are expected to be encountered.

  Treatment of the contaminated waste will likely increase the volume of waste soil and slag material;
 however, a slight volume reduction may occur if a chemical reagent is used to treat the material.
 Typical volume increases range from about 5 percent to as high as 100 percent, depending upon the
 treatment methodology used. An increase in the volume of the treated waste material will have an
 impact on the transportation costs to a disposal facility. Calculations used in the development of this
 alternative assume a volume increase of 20 percent.

 Wastewater may be generated during implementation of this alternative through water runoff
 generated as a result of dust emission control.  Wastewater may also be generated as a result of
 decontamination activities required for both equipment and on-Site workers.   Containment and
 treatment or disposal of these wastewaters may be required.  Depending upon  the treatment
 methodology selected, the wastewater may be able to be utilized in the soils treatment process.

 No state or federal permits are expected to be required; however, advance consultation should occur
 in planning the action to ensure that all involved agencies are allowed to provide input.

 All services and materials for this alternative are readily available.

2.8.5B.8 Cost

The total present worth for Alternative S-5B is approximately $7,477,199 for Option 1, which
includes the excavated wetlands sediment, and $6,181,160 for Option 2, which does not include the
                                          -144-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1

   1 6,000 CY of stockpiled and landfffled slag would be considered "principal-threat" waste. This
  alternative meets EPA's expectation to use treatment to address the principal threats posed by a site
  by treating all the contaminated soil, sediment, and slag.  However, treatment of what would be
  considered low-level threat waste does not meet EPA's expectation to use containment to address
  such waste, although in some situations, treatment rather than containment of low-level threats is
  warranted (EPA 1991).

  2.8.5B.6 Short-Term Effectiveness

  The construction phase of this alternative would likely be accomplished within one field season;
  therefore, impacts associated with construction would likely be short term and minimal. Short-term
  impacts are associated with excavation, consolidation and treatment of waste soil and slag; however,
 these potential, short-term impacts would be mitigated during the construction phase

 If the excavated material is dry, on-Site workers will be exposed to waste soil and slag dust during
 excavation and consolidation activities. Additional exposure to lead dust may occur during the
 decontamination and demolition of building structures and pavement. Ingestion of dust could involve
 some health effects because of the high level of metals in waste soil and slag.

 On-Site workers would be adequately protected from short-term risks by using appropriate personal
 ProtectiveequipmentandbyfollowingProperoperatingandsafetyProcedures.However,short.term
 air quality impacts to the surrounding environment may occur during waste consolidation and
 grading. Monitoring ofdust emissions would be monitored at theproperty boundaries. Fugitive dust
 emissions would be controlled by applying water as needed to surfaces receiving heavy vehicular
trafficorinexcavationareas.Ameasurable,shoil-tenninpacttothesurroundingareawouldinclude
increased vehicular traffic and associated safety hazards, potential dust generation, and noise.
                                         -143-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 2.8.5B.3 Compliance with ARARs

 All action-specific ARARs are expected to be met. The TAPCR dust suppression and control
 requirements (Rule 1200-3-8) apply to earth-moving activities associated with this alternative.  If
 remedial equipment is used on Site, such as a pugmill mixer or crusher, dust and vapors generated
 from the use of this equipment  will be contained and treated  before being discharged to the
 atmosphere, if required.  ARARs for the control of fugitive dust emissions would be met by applying
 water to roads receiving heavy vehicular traffic and to excavation  areas, as necessary.

 2.8.5B.4 Long-Term Effectiveness and Permanence

 Treatment and  removal of the  waste  material would not require  monitoring, inspection,  or
 maintenance for the Site. Treatment reagents are typically tested by MEP SW-846 Method 1320 to
 measure long-term stability. The test is intended to approximate teachability under acidic conditions
 over a 1,000-year time frame.  Based on successful completion of bench-scale testing that would
 include MEP analysis, this alternative is expected to provide adequate long-term effectiveness and
 permanence.  Access restrictions such as  land use controls and fencing would likely not be required.

 2.8.5B.S Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to  reduce contaminant toxicity and mobility  through
 treatment; contaminant volume would not be physically reduced.  Contaminant toxicity would be
 reduced by altering the physical or chemical structure of the contaminant into a nonhazardous
 material. Contaminant mobility would be reduced by binding or  bonding the contaminant into  a
 nonleachable form.  Subsequent removal would mitigate contaminant migration from the Site.
 Contaminant volume would not be physically reduced under this alternative.

Based on sample results collected during previous Site investigations, 600 CY of surface soil and the
                                         -142-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
           (about 60,150 tons; or 78,750 tons if excavated wetlands sediment are consolidated with
           surface soil for final disposition);
           Off-Site disposal at nonhazardous disposal facility (63,158 tons assuming a 5 percent
           increase in volume during  treatment;  82,688 tons if excavated wetland sediment is
           included); and
      •    Bacfill excavation, soil cover (1 ft deep), topsoil cover (6 inches deep), and grass seeding
           over Site (8 acres).

 Alternative S-5B would eliminate direct contact with contaminated media, eliminate on-Site physical
 hazards, and eliminate contaminant migration to groundwater and surface water from the Site.

 Deed restrictions may be placed on the Site while the remedial action takes place. Monitoring would
 be required to assess effectiveness of the remedial action.

 2.8.5B.2  Overall Protection of Human Health and the Environment

 Successful implementation of this alternative would  eliminate  risks  to human health and the
 environment and  meet the removal action objectives by (1)  eliminating exposure of residents and
 trespassers to waste material by direct contact and airborne migration, (2) eliminating exposure of
 trespassers to direct contact with on-Site physical hazards, and (3) eliminating the migration of
 contaminants  to  groundwater and surface  water.   The threat  of direct human exposure  to
 contaminated waste and physical hazards would be eliminated by this alternative. Treatment and
 removal of the waste material would eliminate contaminant exposure through the receptor routes of
 ingestion  and inhalation.  Contaminated soil and slag  would be treated and convened  to  a
 nonhazardous material and transported to an off-Site disposal facility. Structures throughout the Site
would be demolished and either disposed of in an excavated disposal area beneath the existing
pavement or recycled. As a result, physical hazards associated with deteriorating structures would
be eliminated.  Removal of waste would mitigate contaminant migration from the Site.

                                          -141-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  estimated O&M cost is approximately $163,799. For Option 2, the estimated  capital  cost  is
  approximately $4,081,193, and the estimated O&M cost is approximately $163,799.

  2.8.5B Alternative S-5 - Excavation And Onsite Treatment With Solidification/Stabilization
               Option B - Offsite Disposal of Treated Material

 2.8.5B.1  Description

 Option B for Alternative S-5 is similar to Option A in that it also consists of the decontamination and
 demolition of most of the on-Site pavement and buildings and on-Site treatment. The main office
 building and the pavement immediately surrounding this building would remain on Site. The building
 debris and pavement would be decontaminated by steam cleaning.  The decontaminated building
 debris would be taken off Site to a metal recycling facility. Contaminated soil throughout the Site,
 and buried slag in the landfill would be excavated and consolidated with the  stockpiled slag.
 Contaminants in soil and slag would be physically bound or enclosed within a stabilized mass
 (solidification), or  chemical reactions  would  be induced between  a  stabilizing agent and the
 contaminants to reduce mobility (stabilization). Solidification/stabilization treatment technologies
 include the addition of cement,  lime, pozzolan, or silicate-based additives or chemical reagents that
 physically or chemically react with the contaminant. Option B differs from Option A in that after
treatment and confirmation that the soil is nonhazardous, the treated soil and slag would be hauled
off Site to a disposal facility. A  1.0-ft soil cover and a 6-inch topsoil layer would be placed over the
entire Site. These components ase outlined as follows:

     •   Decontamination and demolition of pavement and buildings;                                    *
     •   Recycling of metal building  debris;
     •   Excavation of contaminated soil (21,875 CY), and landfilled slag (10,000 CY);                  *
     •   Stabilization or solidification of contaminate^ soil, stockpiled slag,  and landfilled slag        4fe
                                         -140-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
the material.  Typical volume increases range from about 5 percent to as high as 100 percent,
depending upon the treatment method used. An increase in the volume of the treated waste material
will have an impact on the disposal volume required.  Calculations used in the development of this
alternative utilized a volume increase estimate of 20 percent.

The dimensions of the Site property are about 450 by 800 feet, including the existing landfill. The
waste storage capacity required for  this alternative is 49,150 CY assuming a 20 percent volume
increase of the treated material. To meet the SWDP buffer zone siting standards, the excavation area
would be 700 by 250 feet, and with an 8-ft average depth, depending on the thickness of the clay unit.
The disposal area would be located beneath the existing pavement.

Wastewater may be generated during  implementation of this alternative  through water runoff
generated as a result of dust emission control.  Wastewater may also be generated as a result of
decontamination activities required for equipment and on-Site workers. Containment and treatment
or disposal of these wastewaters may be required.  Depending upon the treatment methodology
selected, the wastewater may be able to be utilized in the soils treatment process.

The on-Site disposal area for the treated waste may he classified as a Class II  disposal facility. If so,
the substantive requirements of the SWPD rule regarding Class II disposal facilities would apply to
the Site.
                    »
All services and materials for this alternative are readily available.    •

2.8.5A.8 Cost

The total present worth for Alternative S-5A is approximately $4,907,274 for Option 1, which
includes the excavated wetlands sediment, and $4,244,992 for Option 2, which does not include the
wetland sediment. For Option 1, the estimated capital cost is approximately $4,743,474, and the
                                          -139-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  2.8.5A.6 Short-Term Effectiveness
  The construction phase of this alternative would, likely be accomplished within one field season;
  therefore, impacts associated with construction would likely be short term and minimal.  Short-term
  impacts are associated with excavation, consolidation, and treatment of waste soil and slag; however,
  these potential, short-term impacts would be mitigated during the construction phase.

  If the excavated material is dry, on-Site workers will be exposed to waste soil and slag dust during
  excavation and consolidation activities.  Additional exposure  to lead dust may occur during the
  decontamination and demolition of building structures and pavement. Ingestion of dust could involve
  some health effects because of the high level of metals in waste soil and slag.

  On-Site workers would be adequately protected from short-term risks by using appropriate personal
 protective equipment and by following proper operating and safety procedures. However, short-term
 air quality impacts to the  surrounding  environment may occur during waste  consolidation and
 grading.  Dust emissions would be monitored at the property boundaries. Fugitive dust emissions
 would be controlled by applying water as needed to surfaces receiving heavy vehicular traffic  or in
 excavation areas. A measurable, short-term impact to the surrounding area would include increased
 vehicular traffic and associated safety hazards, potential dust generation, and noise.

 2.8.5A.7 Implementability

 Treatment of contaminated soil and slag is offered by numerous vendors. On-Site treatment utilizes
 standard construction practices and material handling equipment. No significant construction issues
 are expected to be encountered.

Treatment of the contaminated waste will likely  increase the volume of the waste soil and  slag
nrnterial;however,shghtvoliimereductionsW^
                                          -138-

-------
€>
                                                                          Record of Decision
 	,	__	  Ross Metals OU#1
 animals.  However, the cover would be periodically inspected, and required maintenance could be
 implemented.

 If the RM Site is not classified as a Class II disposal facility; monitoring, inspection, and maintenance
 may not be required.  Treatment reagents are typically tested by the Multiple Extraction Procedure
 (MEP, SW-846 Method 1320) to measure long-term stability. The test is intended to approximate
 teachability under acidic conditions over a 1,000-year time frame.  Based on successful completion
 of bench-scale testing that would include MEP analysis, this alternative is expected to provide
 adequate long-term effectiveness and permanence. Access restrictions such as land use controls and
 fencing may be required to prevent land uses incompatible with the Site.

 2.8.5A.5 Reduction of M/T/V Through Treatment

 The primary objective of this alternative is to reduce contaminant toxicity and mobility through
 treatment; contaminant volume would not be reduced. Contaminant toxicity would be reduced by
 altering  the  physical  or chemical  structure of the contaminant  into a nonhazardous material.
 Contaminant mobility would be reduced by binding or bonding the contaminant into a nonleachable
 form that would eliminate contaminant migration from the Site.  Contaminant mobility is expected
 to be reduced to an extent that would result in overall risk reduction from all pathways and exposure
 routes.

 Based on sample results collected during previous Site investigations, 600 CY of surface soil and the
 16,000 CY of stockpiled and landfilled slag would be considered "principal-threat" waste.  This
 alternative meets EPA's expectation to use treatment to address the principal threats posed by a site
 by treating all the contaminated soil, sediment, and slag. However, treatment of what would be
 considered low-level threat waste does not meet EPA's expectation to use containment to address
 such waste, although in some situations, treatment rather than containment of  low-level threats is
warranted (EPA 1991).
                                         -137-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
           defined by acreage and function); and
       •   sufficient information is available to make a reasonable determination with respect to these '
           demonstrations.

  The Protection of Wetlands Order (40 CFR 6) also requires that no adverse impacts to wetlands
  result from a remedial action. Historical evidence suggests that the existing landfill was created in
  a wetland. However, this area was not observed to contain standing water during sampling events
  conducted in 1996 and 1997. It  is not known whether the area of the existing landfill would be
  classified as a wetland area.

  The substantive requirements for stormwater discharges during construction activities as outlined by
 the CWA are relevant and appropriate. However, a specific NPDES permit is not required for this
 removal action.

 All action-specific ARARs  are expected to be met. The Tennessee Air Pollution Air Control
 Regulations (TAPCR) dust suppression and control requirements (Rule 1200-3-8) apply to earth-
 moving activities associated with  this alternative. If remedial equipment is used on Site such as a
 pugmill mixer or crusher, dust and vapors generated fromthe use of this equipment will be contained
 and treated before being discharged to the atmosphere, if required. ARARs for the control of fugitive
 dust emissions would be met by applying water to  roads receiving heavy vehicular traffic and to
 excavation areas, as necessary.

 2.8.5A.4 Long-Term Effectiveness and Permanence

 If the disposal area is classified as a Class II disposal facility, the area may have to be maintained to
 ensure that it  continues to perform as designed; consequently, monitoring,  inspection, and
maintenance would be required. The soil cover area would be susceptible to settlement, ponding of
surface water, erosion, and disruption of cover integrity by deep-rooting vegetation and burrowing
                                          -136-

-------
                                                                                   Record of Decision
                                                                                   Ross Metals OU#1
o
         actions upon floodplains, and to preserve and enhance the natural values of floodplains. Specifically,
         when it: is apparent that a proposed or potential Agency action is likely to impact a floodplain or
         wetlands, the public should be informed through appropriate public notice processes. Furthermore,
         if a proposed action is located in or affects a floodplain or wetlands, a floodplain/wetlands assessment
         shall be undertaken, and a statement of findings explaining why the proposed action must be located
         in or affect the floodplain or wetlands.

         Regarding construction activities related to implementing the alternative, 40 CFR  6 Appendix A
         requires that EPA-controlled structures and facilities must be constructed in accordance with existing
                                                                                         t
         criteria and standards  set forth under the NFIP and must include mitigation of adverse impacts
         wherever feasible,  including the use of accepted floodproofing and/or other flood protection
         measures. To achieve flood protection, EPA shall wherever practicable, elevate structures above the
         base flood level rather than filling land.

         Wetlands are located to the north and northeast of the facility and landfill, although these locations
         are not identified on NWI maps. The SWPD rule requires that new landfills and lateral expansions
         shall  not  be located  in a wetlands, unless the owner  or operator can  make  the  following
         demonstrations:
the presumption of a practicable alternative that does not involve wetlands is clearly
rebutted;
the construction/operation of the landfill will not cause or contribute to violations of
applicable  State  water quality standards, any  applicable toxic  effluent  standard or
prohibition under Section 307 of the CWA, and will not cause or contribute to the taking
of any endangered  or threatened  species or  result  in the  destruction or  adverse
modification of critical habitat of endangered or threatened species;
the landfill will not cause or contribute to significant degradation of wetlands;
to the extent required under Section 404 of the CWA or Tennessee Water Pollution
Control Act, steps have been taken to attempt to achieve no net loss of wetlands (as
                                 -135-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
  decontamination would eliminate contaminant migration from the Site.

  2.8.5A.3  Compliance with ARARs

  The State of Tennessee SWPD rules are potentially applicable. The State may classify the on-Site
  disposal area for treated waste as a Class II (industrial waste) landfill facility.  Class II facilities must
  meet the same requirements as Class I (solid waste) disposal facilities unless a waiver of one or more
  of the standards is obtained as set forth in SWPD Rule 1200-l-7-.01(5).  Class I standards include
  requirements for landfill liners, geologic buffers, leachate collection systems, and other requirements -
 that may not be necessary for the RM Site to be protective of human health and the environment.
 The SWPD rule also includes buffer zone standards for Class II facilities. These standards require
 that new facilities be located so that fill areas are, at a minimum,  100 feet from all property lines and
 500 feet from all residences unless the owner agrees in writing to a  shorter distance. A disposal area
 that is constructed to be about 700 feet by 250 feet would likely meet both the buffer zone and
 capacity requirements for the RM Site.

 The RM Site is located in a  100-year floodplain within a zone designated as A3, indicating that base
 flood elevations and flood hazard factors have been determined for this area.  The SWPD rule (Rule
 1200-1 -7) and the Criteria for Classification of Solid Waste Disposal Facilities and Practices (40 CFR
 257) require that disposal facilities must not be located in a 100-year floodplain, unless both of the
 following can be demonstrated:

      •   Location in the floodplain will not restrict the flow of the 100-year flood nor reduce the
         temporary water storage  capacity of the floodplain; and
      •   The facility is designed, constructed, operated, and maintained to prevent washout of any
         solid waste.
In addition, EPA's regulations (40 CFR Part 6, Appendix A)for implementing Executive Order 11988
(Floodplains Management) requires federal agencies to avoid or minimize adverse impacts of Federal
                                          -134-

-------
    SOUTH
               DEPTH AT WHICH
           GROUNDWATER ENCOUNTERED
                                                             WRECKER
                                                             BUILDING
                                                                                                                               NORTH
                                                                                                       SURFACE DEPOSITION OF
                                                                                                      LEAD CONTAMINATED DUST,
                                                                                                        SOILS, AND SEDIMENT
                                                                                                1' ABOVE GROUND LEVEL
   F-
   T

   R
                            4      .. .  •   -•*.'*•  V  9' TREATED MATERIAL *  .   .  &   • .      ."  -    ' .  •> '  '

                            '':••''•• v«v'%:'.•  :•••'•  ••-';•'-."-••.>    ^V'-v:^
                            '"I"" I " I  I  I  I  I I  I  I i i  i  i Ti * i  i f ii  i ---j	1	M-             	;	   <.   .  >-
L.
a
             DEPTH AT WHICH —-^
         GROUNDWATER ENCOUNTERED
NOTE: Concepluol dastgn. Fodwd, slots, end loeol
r«juiremenU regarding conalrucllon lit a floodplota
must bo considered and may offset design
Repr«j*nlollon of woilo moltrlol Includes excavated
wellond sediments.
                                                         NOT TO SCALE
                                                                                                                                   •11*

                                                                      APPROXIMATE DIMENSIONS OF EXCAVATION:  TOTAL DEPTH (BELOW GROUND SURFACE) - 8 FT.
                                                                                                    TOTAL HEIGHT (ABOVE GROUND SURFACE) -  4.5 FT.
                                                                                                    LENGTH - 700 FT.
                                                                                                    WIDTH - 250 FT.
                                                    Ross  Metals  Site
                                                  Rossville, Tennessee
CDM Federal Programs Corporation
A xMfiqr 
-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 Figure 2-27 illustrates the component of the on-Site disposal area included under Alternative S-5 A.

 Treatability testing may be required to demonstrate contaminant immobilization for this treatment
 process and to help determine the volume increase caused by the solidification/stabilization process.
 One treatability study to evaluate stabilization reagents that would 1) reduce the teachability of lead
 in treated woodland sediment and 2) improve the material handling qualities of the sediment so that
 free liquids are not released during transport or disposal was completed in March 1998 (EPA 1998).
 The results of that study demonstrated that a biosolid product produced by N-Viro effectively
 reduced  the leachibility of lead, absorbed free liquids and resulted in a material that could be
 excavated and transported for disposal.

 Deed restrictions may be placed on the Site while the remedial action takes place.  Monitoring would
 be required to assess the effectiveness of the remedial action.

 2.8.5A.2 Overall Protection of Human Health and the Environment

 Successful  implementation of this alternative would eliminate risks  to  human health and the
 environment and meet the removal action objectives by (1) eliminating exposure of residents and
trespassers to waste material by direct contact and airborne migration, (2)  eliminating exposure of
trespassers to direct  contact with on-Site physical hazards, and (3) eliminating the migration of
contaminants to  groundwater and surface water.  The  threat of direct human  exposure  to
 contaminated waste and physical hazards would be eliminated by this alternative. Treatment of the
waste material would eliminate contaminant exposure through the receptor routes  of ingestion and
inhalation. Contaminated soil and slag would be treated and converted to a nonhazardous material.
Structures throughout the Site would be demolished and either disposed of in an excavated disposal
area beneath the  existing pavement or recycled.   As a result, physical hazards  associated with
deteriorating structures would be eliminated. Waste immobilized by treatment or removed by
                                          -132-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
Once treated and confirmed to be nonhazardous, the soil and slag would be consolidated with the
pavement debris and disposed of in an on-Site, unlined excavation.  The decontaminated building
debris would be taken off Site to a metal recycling facility.  The onsite disposal area would extend
from the northern boundary of the existing landfill to about 100 feet north of the Site entrance and
would be about 700 feet long, 250 feet wide and 8 feet deep.  A 3.0-ft soil cover consisting of
uncontaminated soil excavated from the disposal area and a 6-inch topsoil layer would be placed over
the entire Site.   The total height of the capped area would be approximately 4.5  feet.   The
components of this alternative are outlined as follows:

     •    Decontamination and demolition of pavement and buildings;
     •    Recycling of metal building debris;
          Excavation of contaminated soil (21,875 CY) and landfilled slag (10,000 CY);
     •    Stabilization or solidification of contaminated soil,  stockpiled  slag, and landfilled slag
          (about 60,150 tons  or 78,750 tons if excavated wetlands sediment are consolidated with
          surface soil for final disposition);
     •    Excavation of on-Site disposal area (700 ft long by 250 ft wide by 8 ft deep);
          Compaction of 40,817 CY of waste material (52,771 CY of waste material if wetland
          sediment is included); assuming a 5% increase in volume due to stabilization/solidification;
          Soil cover (3.0 ft deep), topsoil cover (6 inches deep), and grass seeding over Site (8
          acres);
     •    Land use restrictions and security fencing.

Alternative S-5 would eliminate direct contact with contaminated media, eliminate on-Site physical
hazards, and eliminate contaminant migration to groundwater and surface water from the Site.  The
final treatment system would depend upon the  outcome of treatability testing and would be
determined during the remedial design phase.  The fixed material would be subjected to TCLP testing
to determine if treatment has been effective, prior to placement in the excavated disposal area.

                                          -131-

-------
                                                                            Record of Decision
                                                                            Ross Metals OU#1
 No state or federal permits are expected to be required; however, advance consultation should occur
 while planning the action to ensure that all involved agencies are allowed to provide input.

 All services and materials for this alternative are readily available.

 2.8.4.8  Cost

 The total present worth for Alternative S-4 is approximately $ 1,506,847 for Option 1, which includes
 the excavated wetlands sediment, and $1,481,865 for Option 2, which does not include the wetland
 sediment.  For Option 1, the estimated capital cost is approximately $1,346,951, and the estimated
 O&M cost is approximately $159,895. For Option 2, the estimated capital cost is approximately
 $1,321,970, and the estimated O&M cost is approximately $159,895.

 2.8.5A Alternative S-5 - Excavation And Onsite Treatment With Solidification/Stabilization
                     Option A - Onsite Disposal of Treated Waste

 2.8.5A.1 Description

 Option A for Alternative S-5 includes the decontamination and demolition of most of the on-Site
 pavement and buildings.  The main office building and the pavement immediately surrounding this
 building would remain on Site.  The building debris and pavement would be decontaminated by
 steam/pressure cleaning. Contaminated soil throughout the Site, and buried slag in the landfill would
 be excavated and consolidated with the stockpiled  slag.  Contaminants within soil and slag would be
physically bound or enclosed within a stabilized mass (solidification), or chemical reactions would be
induced between a stabilizing  agent and the  contaminant to reduce its mobility (stabilization).
Solidification/stabilization treatment technologies include the addition of cement, lime, pozzolan, or
silicate-based additives or chemical reagents that physically or chemically react with the contaminant.
                                          -130-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#l
 Site conditions does not suggest that these situations would apply to the RM Site.

 2.8.4.6 Short-Term Effectiveness

 The construction phase of this alternative would likely be accomplished within one field season;
 therefore, impacts associated with construction would likely be short-term and minimal. Short-term
 impacts are associated with excavation and consolidation of waste soil and slag; however, these
 potential, short-term impacts would be mitigated during the construction phase.

 If the excavated material is dry, on-Site workers will be exposed to waste soil and slag dust during
 excavation and consolidation activities. Additional exposure to lead dust may occur during building
 structure and pavement demolition. Ingestion of dust could involve some health effects because of
 the high level of metals in waste soil and slag.

 On-Site workers would be adequately protected by using appropriate personal protective equipment
 and by following proper operating and safety procedures.  However, short-term air quality impacts
 to the surrounding environment may occur during waste consolidation and grading. Dust emissions
 would be monitored at the property boundaries.  Fugitive dust emissions would be controlled by
 applying water to surfaces receiving heavy vehicular traffic or in excavation areas, as needed.  A
 measurable, short-term impact to the surrounding area would include increased vehicular traffic and
 associated safety hazards, potential dust generation, and noise.

 2.8.4.7  Implementability

 Construction of a geomembrane surface cap is a standard construction practice.  Other than capping
contaminated material in a  floodplain,  no significant construction issues are expected to be
encountered.
                                          -129-

-------
f
Table 2-23
Capital Coses for Selected Remedy

-j ITEM DESCRIPTION


SITE DECONTAMINATION/DEMOLITION
Building Demolition
Concrete/Asphalt Demolition
Building Demolition
Pavement Demolition
Recycling Metal Debris
loading and transportation
payment from recycling
Equipment
EXCAVATION
Soil and Sediment Excavation
(9.300+ 1 3. 125+8.750+2.500)
Dust Control & Placement in Staging Areas
(2 water trucks- each @S3 .500/rnomh)
Etcavau'on of Landfilled Slag
Excavation Monitoring
ON-SITE TREATMENT
Treatabilily Study
Treatment
~- {33.675 CYxl.5 + 16.000CYx2)
Treatment System Monitoring
Off-Site Disposal of Non-hazardous Material
(Assume 5% increase)
Backfill Landfill and sub-surface areas w/Clean Fill
(10,000+8.750+2.500)
Installation ot'Biosolids Throughout Site
Installation of Vegetative Cover on Facility Area
Plant Emergent Forested Area
Plant Forested Wetland Area
EQUIPMENT &. MATERIALS
Erosion Control
Health and Safely Equipment (30 people ©
$60/person/day) «•*••=>

UNITS

each

cf
<*
sf
sf
Ion
lump sum

cy
month
V
sample

lump sum
ton
sample
Ion
cy
acres
acre
acre
acre

*
day
QUANTITY

1

27.000
21.333
126.000
192.000
1.500
1.500
1

33.675
3
10.000
45

1
82.513
50
86,639
22,250
14
8
3
3

500
90
UNIT PRICE
DOLLARS
$30,000

$0.23
SIOJ7
$0.75
SO.S5
S20
$50
$25.000

S5
$7,000
S2
$500

$50.000
30
$500
$30.000
$10
$12.000
£2,000
$3,500
$5,500

$2.14
$1.800
Subtotal - Capital Cost
TOTAL COSTS
DOLLARS
$80,000

$6,210
$221,223
$94,500
$163,200
-$45,000
$25.000

$168,375
S2 1.000
S20.000
S22.500

$50,000
32.475,375
$25,000
$2.599.160
$222.500
$168.000
$16,000
$10,500
$16,500

$1,070
$162.000
56,523,113
Engineering* Administrative (3% of Capita! Cost) „._, „,
Subtotal
$6.718,806
Contingency ( 1O% of Subtotal)
tal CoBstructioa Cost
S7J90.6S7
[i .esent Worth O&M Cost

Tool Present Worth
	 . 	 ___ __ 	 	 	 57,420,732
                                                         -191-

-------

ITEM DESCRIPTION
Wetlands and Lawn
Inspection
Wetlands and Lawn
Maintenance
Mowing: 8 Ac x 43.560 SF;
Fertilizing: 14 Acx 43.560
SF
Table 2-24
Operation and Maintenance Costs for Selected Remedy
UNITS
inspection
l.OOOSF
1,000 SF
QUANTITY
2/yr
5/yr
2/yr
UNIT PRICE
DOLLARS
$500
SI. 78
$2.10
TOTAL
ANNUAL COST.
DOLLARS
$1.000
3.101
2.561
OPERATION
TIME,
YEARS
5
5
5
PRESENT
WORTH
$4,100
12.714
10,500
Subtotal S5.662 $27,314
Contingency (10% of S566 S">731
Subtotal)
Total S6.228 $30,045
-192-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
 groundwater; restore impacted wetland communities and prevent further degradation of the adjacent
 wetlands.  The remedy shall address all soils contaminated with contaminants of concern in excess
 of their corresponding risk-based cleanup level.  Since no Federal or State ARARs exist for
 soil/sediment, the action levels were determined through a Site-specific risk analysis. Remediation
 activities shall be monitored to ensure that clean-up levels are achieved. The Site is expected to be
 available for industrial/residential/recreational land use as a result of the remedy.

 2.12 STATUTORY DETERMINATIONS

 Under CERCLA Section 121, EPA must select remedies that are protective of human health and the
 environment, comply with applicable or relevant and appropriate requirements (unless a statutory
 waiver is justified), are cost-effective, and utilize permanent solutions and alternative  treatment
 technologies or resource recovery technologies to the maximum extent practicable.  In addition,
 CERCLA includes a preference for remedies that employ treatment that permanently and significantly
 reduces the volume, toxicity, or mobility of hazardous wastes as a principal element. The following
 sections discuss how the selected remedy meets these statutory requirements.

 2.12.1  Overall Protection of Human Health and the Environment

 EPA's Selected Remedy protects human health and the environment through the  excavation and
 immobilization of lead-contaminated media followed by off-Site disposal.

 Cancer risks, non-cancer risks and lead exposure to human receptors for future use at the Site will
 be eliminated.  The exposure levels will be reduced to within EPA's acceptable risk range of 10-4 to
 10-6 for carcinogens; below the HI of 1 for noncarcinogens; and below EPA's acceptable blood lead
 level of 10  ug per deciliter for lead.  Protection of human health will be achieved by excavating,
treating, and shipping off-Site the soils, sediments, and wastes which pose future risks to  a lifetime
resident, child resident,  adult resident, and site worker.
                                         -193-

-------
                                                                         Record of Decision
	Ross Metals OU#1
Acute and chronic risks to ecological receptors are mitigated. The exposure levels will reduced
below the HI of 1 for noncarcinogens.
                                                                                             f
2.12.2 Compliance with Applicable or Relevant and Appropriate Requirements (ARARs)

The selected remedy shall be in compliance with all Federal ARARs and any more stringent State
ARARs. It is important to note that the Selected Remedy is the only practicable alternative outside
the floodplain.. Executive Order 11988 - Floodplain Management emphasizes the importance of
evaluating alternatives to avoid effects and incompatible development in the floodplains; and those
alternatives located in the floodplain may not be selected unless a determination is made that no
practicable alternatives exist outside the floodplain. The Selected Remedy is considered a practicable
alternative outside the floodplain. The selection of any other alternative would require a floodplains
assessment and following methods to minimize potential harm to the floodplain.

The following ARARs will be attained by the selected remedy:

Action-Specific:

•     RCRA requirements for identification, management and transportation of hazardous waste (40
     CFR 261, 262 and 263).

•     RCRA requirements pertaining to the land disposal of particular hazardous wastes (40 CFR
     268).

     Clean Water Act exceptional quality sludge criteria (40 CFR 5 03) for regulating sludge and sets
     criteria for the safe use of sludge-derived products.
                                         -194-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 Location-Specific:

 •     Protection of Wetlands and Floodplains are EPA regulations for implementing Executive Orders
      11988 and 11990 (40 CFR Part 6, Appendix A).
                                                L

      RCRA requirements for hazardous waste facility locations (40 CFR 264).

      Regulations Governing Solid Waste Processing and Disposal in Tennessee, Chapter 1200-1-7
      establishes specific requirements for the  operation and maintenance of solid waste landfill
      disposal sites,

      Tennessee Air Pollution Control Act, Chapter 1200-3-6 and 1200-3-8 sets nonprocess emission
      standards and regulates fugitive dust emissions.

Other Criteria. Advisories, or Guidance To Be Considered (TBCs):

     Floodplain  Management Executive Order  11988  for avoiding adverse effects, minimize
     potential harm, and restore and preserve natural and beneficial values of the floodplain.

     Wetlands Management Executive Order 11990 for minimizing the destruction, loss or
     degradation of wetlands.

     Test Methods for Evaluating Solid Waste  Physical/Chemical Methods, SW-846, 3rd Edition,
     latest update, Chapter 9.

     Methods for Evaluating the Attainment of Cleanup Standards Volume 1: Soils and Solid Media,
     U.S. EPA.
                                        -195-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
      Guidance for Hazardous Waste Site Investigation, EPA QA/G-4HW.

 2.12.3  Cost-Effectiveness

 EPA's Selected Remedy is cost-effective and represents a reasonable value for the money to be spent.
 In making this determination, the following definition was used: "A remedy shall be cost-effective if
 its costs are proportional to its overall effectiveness."  (40 CFR 300.430(f)(l)(ii)(D).  This was
 accomplished by evaluating the "overall effectiveness" of those alternatives that satisfied the threshold
 criteria (i.e., were both protective of human health and the environment and  ARAR compliant).
 Overall effectiveness was evaluated by assessing three of the five balancing criteria in combination
 (long-term effectiveness and permanence; reduction in toxicity, mobility, and volume through
 treatment; and short-term effectiveness). Overall effectiveness was then compared to costs to
 determine cost effectiveness. The relationship of the overall effectiveness of this remedial alternative
 was determined to be proportional to its costs and hence represent a reasonable value for the money
 to be spent.

 For this Site, Alternative S-l is not cost-effective because it would not result in any reduction of the
 toxicity, mobility, or volume of wastes nor would it be effective in the long-term at reducing site risks
 in a permanent manner.  Alternatives S-2, S-3, and S-4 were not considered to be cost-effective as
 they would not result in treatment of principal threat waste and reduction of toxicity and volume is
 not realized. Alternatives S-5A/B and S-6A/B were determined  to be cost-effective.  In evaluating
 the incremental cost-effectiveness of these alternatives, the decisive factors considered were the time
 frame required to construct the remedy, the time frame in which the remedial goals will be achieved,
 long-term effectiveness and compliance  with  ARARs.  EPA believes that  the additional money
required to implement Alternatives S-5B merits the overall effectiveness of the remedy and represents
the best value for the money to be spent.
                                          -196-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
  2.12.4 Utilization of Permanent Solutions and Alternative Treatment (or Resource Recovery)
  Technologies to the Maximum Extent Practicable

  EPA has determined that the Selected Remedy represents the maximum extent to which permanent
  solutions and treatment technologies can be utilized in a cost-effective manner for this Site. Of those
  alternatives that are protective of human health and the environment and comply with ARARs, EPA
 has determined that the Selected Remedy provides the best balance of tradeoffs in terms of the five
 balancing criteria, while also considering the statutory preference for treatment as a principal element
 and considering State and community preference.

 The Selected Remedy treats the principal threats posed by the Site, achieving significant reductions
 in toxiciry and mobility.  Off-Site disposal will not require extensive monitoring, inspection, or
 maintenance for the  Site as compared to the other on-Site disposal alternatives.  The other
 alternatives considered would all require long-term monitoring, inspection and maintenance. The
 capping alternatives would be susceptible to settlement, ponding of surface water, erosion and
 disruption of cover integrity.  The Selected Remedy satisfies the criteria for long-term effectiveness
 by removing the source materials and stabilizing lead in contaminated media.

 The Selected Remedy reduces toxicity, mobility, but not volume through treatment.  There are no
 short-term threats associated with the Selected Remedy that cannot be readily controlled. There are
 no  special implementability  issues that sets  the Selected Remedy apart from any of the  other
 alternatives evaluated. In fact, the administrative and technical issues associated with siting a landfill
 in a floodplain will make the other alternatives considered more difficult to implement than the
 Selected Remedy.

2.12.5 Preference for Treatment as a Principal Element

By treating the contaminated soils, sediment and slag through immobilization, the Selected Remedy
                                          -197-

-------
                                                                          Record of Decision
                                                                          Ross Metals OU#1
addresses the principal threats posed by the Site. By utilizing treatment as a significant portion of the       *"
Remedy, the statutory preference for remedies that employ treatment as principal element is satisfied.

2.12.6 Five-Year Requirements

Because this remedy will not result in hazardous substances remaining on-Site above health-based
levels, a five-year review will not be required for this remedial action.
                                         -198-

-------
                                                                      Record of Decision
                                                                      Ross Metals OU#1
3.0  RESPONSIVENESS SUMMARY

The U.S. Environmental Protection Agency (EPA) held a public comment period fromNovember 18,
1998 to December 18,1998. An extension to the public comment period was requested. Asaresult,
it was extended to January 19,1998. The public comment period was held for interested parties to
comment on the Remedial Investigation/Feasibility Study (RI/FS) results and the Proposed Plan for
the Ross Metals Super-fund Site in Rossville, Tennessee.

The Proposed Plan included in Attachment A of this document, provides a summary of the Site's
background information leading up to the public comment period.

EPA held a public meeting at 6:30 pm on November 30, 1998 at the Rossville Christian Academy,
Rossville, Tennessee to outline the RI/FS and describe EPA's proposed remedial alternative for the
Ross Metals Site.  All comment received during the public comment period have been considered in
the final selection of the remedial alternative.

3.1  RESPONSIVENESS SUMMARY OVERVIEW

During the public comment period, the Rossville community and local government officials expressed
their support of the EPA Selected Remedy. Four letters by the community were received during the
public comment period which supported the Selected Remedy.  As evidenced in the November public
meeting transcript, the community and  local government officials expressed their support of the
Selected Remedy during the meeting. Some of the major concerns expressed included the length of
time it is taking to clean up the Ross Metals Site and the length of time it may take to negotiate with
the PRPs to clean up the Site.
                                                                 j

The PRPs submitted three different comment letters during the public comment period.  In each of

                                       -199-

-------
                                                                   Record of Decision
                                                                   Ross Metals OU#1
4»
these submittals, the PRPs disagreed with EPA's Selected Remedy. The main objection to EPA's
Selected Remedy is off-Site disposal.
                                                                                      f
3.2  SUMMARY OF MAJOR QUESTIONS AND COMMENTS RECEIVED BY THE
     ROSSVILLE COMMUNITY

The public comments appear in bold text and the EPA response follows.

•    EPA's Preferred Alternative, nor any of the other options, address the removal of lead-
     contaminated sludge from Rossville Lagoon — Cell #1.

Comment acknowledged. EPA reviewed the waste-water treatment plant records and found sampling
results from Cell #1. It was determined by the State that the sludge in Cell #1  is non-hazardous.
Lead results ranged from 10 - 245 ppm. EPA's soil cleanup numbers for the Ross Metals Site are    UK
400 ppm and 800 ppm. Lead results from the sludge are below EPA cleanup numbers.

EPA is considering the use of sludge from Cell #1 for use as backfill at the Ross Metals Site.  EPA
will perform comprehensive sampling of Cell #1 to confirm the earlier lead results. Should the sludge
pass appropriate lead and other criteria, EPA with the City of Rossville's permission, will use this
material in the Superfund cleanup at Ross Metals.  The City of Rossville would then be able to use
Cell #1 in their waste-water treatment system as they deem necessary.

3.3  SUMMARY OF MAJOR QUESTIONS AND COMMENTS RECEIVED BY THE
     "GROUP"                                                                         *
The Group's comments appear in bold text and the EPA response follows.
                                      -200-
                                                                                    4ft

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
     An RI consistent with EPA protocols (EPA/540/-G-89/004) was not conducted.

•    EE/CA investigation did not generate data sufficient to support an adequate FS or the
     development of an RD.

•    A pre-design investigation will be necessary as part of the RD stage to fill the data gaps.

•    Existing data are not sufficient to estimate volumes of waste accurately.

EPA disagrees with  these comments.  The EE/CA investigation focused on  soils, slag and
groundwater contamination. The EE/CAprovided adequate data to support a decision for soils, slag,
buildings and equipment. In addition to the EE/CA, a human health risk assessment, an ecological
risk assessment which included additional soils/sediment characterization, a stabilization treatability
study, a dewatering treatability study, and a biosolids treatability study were performed. The totality
of this information has provided sufficient data and is consistent with the RI/FS process. As indicated
in the RI/FS, additional information is needed to characterize groundwater. Volumes of waste have
been accurately estimated.  Graphics depicting the  results of trenching operations  during the
November 1996 field work were inadvertently left out of the RI/FS. The graphics will be included
in the next Administrative Record update.  Pre-Design investigations are a routine part of the
Remedial Design process.

•    The selected remedy is inconsistent with EPA policy, as  defined in  Land  Use in
     Superfund Remedy Selection. Future development of the Site for residential purposes
     is prohibited because it is zoned light industrial. EPA should consider current zoning in
     the selection of remedial action levels.

EPA does not agree with this comment. EPA has followed the Land Use Directive by considering
                                         -201-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
the information presented below.                                                                *

The Site is currently zoned as general industrial.  The zoning specifically states that "this district is     ^
not intended to allow uses which may be considered hazardous because of the use of, or production
of, toxic or highly flammable materials." It is important to note that Ross Metals, a secondary lead
smelter, produced a hazardous waste and was located in this district.

The zoning does not prohibit residential development.  The Site is currently located immediately
adjacent to residences with children. The Site has used been for agriculture and a community park
in the past.

The Town of Rossville has not been able to attract new industry in recent years and does  not
anticipate new growth patterns. The Site is also physically bound by it's surroundings and location -
it  is located  in the 100-year  floodplain, adjacent to wetlands,  a waste-water treatment plant,   fltt
residences, and a railroad.

EPA has had discussions with local land use authorities and community members regarding future
land use for the Ross Metals Site.  They have strongly expressed their desire for the Site to be used
in the future for the community, e.g., a park. The Town of Rossville and Fayette County officials are
interested in the Town of Rossville obtaining the Site property deed.

•    EPA's selection of a 400 ppm lead-in soil performance criterion for subsurface soil is not
     based on site-specific data and should instead be based upon additional studies, to be
     performed  during the remedial design,  that would determine whether 400 ppm lead       ,,
     leaches dissolved lead to groundwater above the action level for lead in groundwater.

EPA acknowledges this comment and agrees that modeling conducted during the pre-design effort
may indicate that a less conservative clean-up goal will be sufficient for protection of groundwater.   jg^
                                         -202-

-------
                                                                         Record of Decision
	Ross Metals OU#1
As indicated in the FS, a one-dimensional geochemical model was used to evaluate the migration of
lead in soil beneath the smelter slag and the migration of lead below the contaminated soil near the
wrecker building. The model suggested that the slag material is a potential source of contamination
to groundwater. The model predicted that lead will migrate to groundwater in six years and the
concentration of lead will exceed 15 ppb in 55 years. In addition, the geochemical model suggested
that soils near the wrecker building are acting as a continuing source of contamination to groundwater
and the lead concentration in groundwater will continue to increase unless the source is removed.
Model output indicated that removal of lead to 100 ppm left a residual concentration of 3.71 ppm,
which is near background levels, and predicts that a removal action level of 100 ppm would be
protective of groundwater for at least  90 years. However, the conservative nature of this number,
along with the uncertainty surrounding the modeling effort, make it inappropriate to use as  a
subsurface cleanup goal.  The 100 ppm goal is based on the assumption of a 5,000 ppm surface load
factor. However, the establishment of a 400 ppm risk-based surface soil clean-up goal would mean
surface soil concentrations no greater than 400 ppm With a surface soil concentration of 400 ppm
and considering the nature of contamination, clean up of subsurface soils to 400 ppm in the area of
the wrecker building and truck wash should allow for the protection of groundwater.

      Have not determined conclusively whether there has been an impact to groundwater
      quality in the shallow aquifer resulting from the residual lead in soil or from the presence
      of residual slag.

 EPA agrees. Please see above comment regarding the slag  and soils near the wrecker building. In
 addition, lead results in  groundwater  samples collected to date suggest that the Site has impacted
 groundwater quality.  However, as the RI/FS indicates, recent results from MW5 do not confirm
 earlier (higher) sample results, and the high turbidity associated with unfiltered samples collected as
 the Site means the horizontal extent of contamination may be much less than the current data indicate.
 Further definition impact to groundwater will be completed as part of the Operable Unit No. 2 RI/FS.
                                          -203-

-------
                                                                        Record of Decision
                                                                        Ross Metals OU#1
•    No investigation to determine whether lead in wetlands is attributable to mobilization of
     dissolved lead in shallow groundwater and discharge into the wetland areas.

EPA disagrees with this comment. As indicated in the RI/FS, primary mechanisms available for
contaminant transport away from the Site are (1) transport by rainwater runoff, (2) rainwater
infiltration to groundwater, and (3) windblown dust movement. Existing data in the wetlands clearly
indicates the wetlands have been impacted by the Site contaminants. The Operable Unit No. 2 will
provide data regarding to what extent,  if any, groundwater contamination is migrating to  the
wetlands.

•    Remedial action objectives for surface soil containing lead and other metals should be
     based on exposure scenarios provided in the Risk Assessment Guidance for Superfund
     (EPA/540/1-89/002), and should be consistent with agency-approved cleanup goals at
     other secondary smelting Superfund sites in EPA Region 4, where a soil remedial action    MB
     objective of 1,000 ppm has been selected (e.g., DLCO Superfund Site).

The Risk Assessment  was completed in accordance with the framework provided in the Risk
Assessment Guidance for Superfund. The guidance does not provide specific site exposure scenarios
to use in the completion of a site risk assessment.  Cleanup goals at the Ross Metals Site are primarily
a function of managing risk in consideration of site-specific characteristics, not other secondary lead
smelting sites. Also note, that of the 22 sample results (within the fenced facility) illustrated on
Figure 7-1 that are above 400 ppm, 18 are also above 1,000 ppm. Excavation areas and resulting
volumes proposed for the various alternatives would not change because of the need to either create
a sufficient excavation for on-Site disposal or adequate regrading/revegetation of the Site for off-Site       »
disposal.

                                                                                            .jt
•    Selected remedy was not based on the regulatory provision that a remedial action can
                                        -204-

-------
                                                                       Record of Decision
                                                                        Ross Metals OU#1
     consist of any combination of treatment, remedial action, engineering and institutional
     controls.

EPA disagrees with this comment.  In developing the alternatives, EPA considered a variety of
technologies and process options. Please see RI/FS Section 9.0 and 10.0 which screens and evaluates
technologies and process options; and develops the range of alternatives selected for the Ross Metals
Site. Also, it is important to ndte.that the Selected Remedy allows for stabilization, solidification,
fixation, or composting processes. These processes may be used in any combination for the Site soils
and waste to meet the land disposal regulations.

•    A floodplain assessment per OSWER Directive 9280.0-02 that requires EPA to assess the
     effects of proposed  alternatives  on floodplains and  floodplain protection  was not
     conducted as part of the EPA site investigations, nor was it considered in the FS.

EPA acknowledges this comment. EPA believes the commenters have misunderstood the Floodplain
Management Executive Order 1198. EPA's Selected Remedy will not be located in a floodplain and
will therefore, not adversely effect the floodplain. An Assessment would have been necessary had
the Agency chosen a remedy located in the floodplain.

•    Long-Term Effectiveness and Permanence - On-Site disposal  alternative could be
     considered more effective because  the  Group will  maintain  specific control and
     management of the treated materials, whereas there would be no control for specific
     wastes at off-Site facilities.

EPA disagrees with this comment. The Group proposes to maintain specific control of the treated
materials by establishing a trust fund for the City to conduct O&M at the Site; yet the current status
of the City's WWTP berm - as reported by the Group - has eroding banks.  The Group's comment
                                        -205-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 that they will maintain specific control and then the comment that they will create a trust fund for
 others to implement the long-term operation and maintenance  activities is a contradiction.  In
 addition, if the Group's assertion that the preferred alternative merely transfers risks from one Site
 to another, then the Group's alternate remedy leaves that risk on Site, and limits rather than increases
 the number of options the community has in redeveloping the Site. Finally, the off-Site disposal of
 wastes would occur at facilities where appropriate controls are in place.

 •     Short-Term Effectiveness - The short-term risk of injury or fatality to workers and
      community members is significant for off-Site disposal alternatives.  In addition, there
      is an increased exposure to residents to particulates, ozone, and carcinogenic compounds
      known to occur in diesel fuel exhaust.

 EPA disagrees with this comment.  A Site-specific Health and Safety Plan will be required before
 implementation of the Remedial Action. There are no short-term threats associated with the Selected
 Remedy that cannot  be readily controlled. EPA has considered  the costs for implementing dust
 control measures, erosion control, personal protection and off-Site disposal. Please see the cost
 estimates provided in RI/FS Appendix O.

     In addition to transportation risks associated with the off-Site disposal of materials from
     the Site, concern exists about the future, potential long-term liabilities that would be
     incurred  by those parties that agree to implement an  off-Site disposal remedy that
     involves disposal of material at a facility operated and managed  by an independent
     company.

EPA acknowledges this comment. Pursuant to Section 107  of CERCLA, 42 U.S.C. § 9607, "any
person who by contract, agreement or otherwise arranged for disposal or treatment..." is liable as
a potentially responsible party.  However, mitigating factors are contemplated in Section 107 which
                                         -206-

-------
                                                                           Record of Decision
                                                                           Ross Metals OU#1
 provides certain defenses including:
       1. Act of God,
      2. Act of War, and
      3. An act or omission of a third party whose act or omission occurs in connection with a
      contractual relationship.

 It appears that the Group is concerned about acts or omissions of a third party (landfill operator) who
 takes over custody of the waste once it is shipped off Site.  In order to establish the third defense,
 a pany must establish  that (a)  he exercised due care with respect to  the hazardous "substances
 concerned, and (b) he took precautions against foreseeable acts or omissions of any such third party.
 The risks posed by the hazardous waste in question is substantially reduced because prior to disposal
 the waste will be treated on Site and thereafter will be in a non-hazardous state. The act of reducing
 the toxicity of the contaminants is indicative of the exercise of due care.   Further, if the Group
 carefully selects an authorized RCRA landfill that has been in operation  for a respectable period of
 time, this should help to establish that they took precautions against foreseeable acts or omissions of
 the landfill operator. Regardless, some long term potential liability exists  whether the waste is
 transported off Site or remains on Site. Given the extra precautions that will be taken and the public
perception factor, disposal of the waste off Site does not necessarily pose more risk.

     Cost - EPA's costs in the FS for off-Site disposal might be substantially underestimated.
     The costs for off-Site disposal will increase proportionally to the volume of  material
     requiring transportation and disposal The on-Site containment alternative costs do not
     increase directly with volume.

     Several on-Site disposal remedies for source materials, each of which is equally or more
     protective that EPA's proposed remedy, could be implemented at a lower cost than
     EPA's proposed remedy.
                                         -207-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
EPA acknowledges this comment. On-Site containment alternatives are equally affected by increase
in volume of material requiring disposal.  The size of required excavation, amount of materials
handling, and height of the required cap are all affected by volume of material requiring disposal, and
therefore all affect costs. In addition, the Group's alternate remedy would include pre-design costs
related to implementing a cap in a floodplain, as well as costs associated with additional engineering
considerations associated with capping in a floodplain; hydrogeologic investigations to site a landfill;
and long-term operations and maintenance costs into infinity.

The  RI/FS report indicates that while certain onsite disposal remedies may be as effective as the
preferred alternative in overall protection of human  health and the  environment,  and could be
completed at lower cost, they are not as effective as the preferred alternative in achieving compliance
with long-term effectiveness, reduction in toxicity, mobility, and volume through treatment, and
short-term effectiveness. Cost effectiveness is not determined merely by cost.  Cost effectiveness is
the costs proportionality to its overall effectiveness.  Although the Selected Remedy will cost more
to implement, the decisive factors considered were the time frame to implement the remedy, the time
frame in which the remedial goals will be achieved, long-term effectiveness and compliance with
ARARs. The additional money required to implement the Selected Remedy merits the  overall
effectiveness of the remedy and represents the best value for the money to be spent.

•    State  Acceptance -  The State would accept the alternate remedy (on Site with
     provisions).

•    TDEC was prepared to approve Ross Metals request to construct an on-Site landfill
     while the facility was in operation.

EPA disagrees with this comment. The commenters apparently missed portions of State and EPA
                                         -208-

-------
                                                                                  Record of Decision
          	  ,.	,,.,	Ross Metals OU#1
          records. Ross Metals was issued a Notice of Violation for the existing disposal site on June 16,1986.
          The Notice of Violation required Ross Metals to either register the Site or to close it. The facility's
          landfill predated RCRA Subtitle D and was therefore not subjected to its current requirements. Ross
          Metals chose to apply for a permit and submitted an application.  As was the practice at that time,
          TDEC's  Division Geologist conducted a preliminary  Hydrogeologic Review  of the Site  and
          determined that the Site may have been suitable for a landfill. On December 20,1988, Paul Patterson
          of the Memphis DS WM Office notified Ross Metals that the review of their landfill application would
          be suspended until the status of the slag could be determined.  They filed a RCRA Part B Permit
          Application November 8, 1988.  The Permit was never approved.

          EPA disagrees with the Commenter's assertion that the State would accept the alternative remedy
          with provisions. As evidenced by the State's letter of concurrence, the State concurred with EPA's
          selected remedy. The letter is included in Appendix B.

          •    The scoring approach described in the FS was used to compare the Alternative Remedial
               Action (ARA) and EPA's preferred remedial alternative selected in the Proposed Plan.
               Based on the scoring, consistent with the NCP evaluation criteria, the ARA scores higher
               than or equal to EPA's preferred remedial alternative for each threshold and primary
               balancing criterion. As a result and consistent with the NCP, on-Site placement of the
               treated material is the preferred remedy, which is also consistent with EPA's EE/CA,
               conducted in December 1997.

          EPA disagrees with this comment.  Soil Alternative 6A, as presented in the FS, is the most similar
y         to the Group's alternative remedy, with the exception of the end use of the Site.  S-6A was ranked
          lower than the Preferred Alternative in the areas of compliance with ARARs, long-term effectiveness
          and permanence, and implementability. There is greater difficulty for S-6A because of capping in a
 4?
          floodplain. Additional ARAR requirements would need to be implemented if construction occurred
                                                   -209-

-------
                                                                         Record of Decision
                                                                         Ross Metals OU#1
 in a floodplain and siting a landfill occurred.  Also, there is additional risk of leaving untreated
 material (low-level threat waste) on Site.

 The EE/CA did not include a developed analysis of the ARAR requirements as compared to the FS.
 The EE/CA did not include the ecological data, treatabih'ty studies, a baseline human health risk
 assessment, or an ecological risk assessment. The EE/CA did not include the nine-criteria .analysis
 as required by the NCP. The EE/CA combined with the additional studies, ARAR analysis, and nine-
 criteria analysis were used in the RI/FS report. The fact that the EE/CA selected remedy differs from
 the RI/FS selected remedy is a function of the  more complete assessment that the RI/FS process
 requires as compared to the EE/CA process. It was during the EE/CA report preparation that the
 potential for selecting off-Site  disposal as part  of the RI/FS  process became apparent.   EPA
 recognized that the additional assessment would be necessary so that unnecessary money would not
 be spent performing an on-Site disposal removal, and then at a later date as a result of the remedial
 process, potentially performing an off-Site disposal remedy.

     The Group's proposed alternative on-Site disposal remedy will create a public park with
     other environmentally beneficial features.

EPA acknowledges this comment. EPA will support the creation of a park in addition to the Selected
Remedy. EPA, DOI, and the City of Rossville are in favor of a park as future land use and will
coordinate with the Group in implementing such a community benefit.
                                        -210-

-------

-------
•#•

-------
This fact sheet will provide:

•     An overall review of the
      Site -
•     The results of the Remedial
      Investigation
•     Possible health risk posed
      by the Site
•     A summary of treatment
      technologies
•     A summary of the
      Feasibility Study
•     A presentation of EPA's
      preferred Alternative
•     Announcement of Public
      Comment Period
•     Places to get information
 PUBLIC MEETING
DATE: November 30, 1998
TIME: 6:30 p.m.
LOCATION:
Rossville Christian Academy
280 High Street
Rossville, Tennessee
                                United States             Region IV
                                Environmental Protection    61 Forsyth Street
                                Agency                  Atlanta, GA 30303
                                           Alabama, Florida, Georgia,
                                           Kentucky, Mississippi,
                                           North Carolina, South
                                           Carolina, Tennessee
                                         SUPERFUND  FACT SHEET

                                         PROPOSED PLAN  FOR  REMEDIAL
                                         ACTION  AT THE ROSS  METALS
                                         SUPERFUND  SITE
                                         Rossville, Tennessee
                                                November  1998
     Ross Metals
       'Site
INTRODUCTION

This Proposed Plan Fact Sheet is issued
to describe the alternatives that the U.S.
Environmental Protection Agency (EPA)
has considered for the cleanup at the
Ross Metals National Priorities List
(NPL)   Site  located  in  Rossville,
Tennessee.   'This plan  presents  an
evaluation of the cleanup alternatives,
including the alternative  preferred  by
EPA.    The cleanup alternatives for
contaminated soils,  wetlands, landfill
waste, and buildings are summarized in
this Fact Sheet and are  described in
greater  detail   in  the  Remedial
Investigation (RI) and Feasibility Study
(FS) reports. The RI and FS reports are
more complete sources of information
and are  part of the Administrative
Record.  The Administrative Record
consists  of technical  reports and
reference documents used by EPA to
develop the Proposed Plan.  These
documents may be  found  in   the
information repository located at the
Rossville  City  Hall in Rossville,
Tennessee.

Based on Site information, EPA has
divided the Site into Operable Units or
cleanup phases, with the source being
the first Operable Unit and the ground-
  Note: Words that appear in the glossary
  on page 10. are in italics the first time
  they appear in the body of this fact sheet

-------
water being the second. This has been done to begin cleanup
of the contaminated source material, while continuing to
evaluate potential groundwater contamination.  Operable
  nit No.  1  will address the contaminated soils, landfill
waste, wetlands and buildings.  Operable Unit No. 2 will
address the potential cleanup of groundwater contamination.

The Ross Metals RI/FS was prepared by CDM Federal
Programs Corporation, under contract with EPA.   The
alternative EPA prefers for OU #1 represents a preliminary
decision, subject to public comment.

Section  117(a)  of the  Comprehensive  Environmental
Response, Compensation and Liability Act (CERCLAJ of
1980, as amended by the Superfund Amendments and
ReauthorizationAct (SARA) of 1986, requires public notice
and a brief analysis of the EPA preferred alternative for Site
remediation.

EPA encourages the public to submit written comments on
all alternatives presented in this plan. Please see page 9 for
more information on where to  submit written comments.
EPA will consider public comments as part of the final
decision-makingprocess for selecting the cleanup remedy for
the Site.

SITE BACKGROUND

The Ross Metals Site (herein after referred to as "the RM
site" or "the site") operated as a secondary lead smelter from
 1978 to 1992, during which the facility processed spent lead-
acid batteries, lead dross, lead scrap, and other lead bearing
material into reusable lead alloy.  The 13.7 acre site is
located in a rural and residential area of Rossville, Fayette
County, Tennessee. An unlined landfill containing about
 10,000 cubic yards (CY) of blast slag is located  in the
northern portion of the site. In addition, about 6,000 CY of
stockpiled slag is stored on site in several  deteriorating
buildings.   Lead-contaminated  surface  soil is located
throughout the site, and lead-contaminated subsurface soil is
present in isolated portions of the site.

The purpose of the Ross Metals RI/FS is to document the
nature and extent of contamination to develop and evaluate
remedial alternatives, as appropriate.

Results of sampling investigations were used to develop this
RI/FS  and show that  lead-contaminated surface soil is
present across the site and in the wetlands north and east of
the  site.  Lead  concentrations in  most surface soil and
sediment samples collected throughout the site exceeded 400
ppm.  In addition, aluminum, antimony, arsenic, barium,
cadmium, copper, iron, manganese, selenium, and vanadium
were detected above their cleanup levels.

In addition, lead concentrations ranging from 1,000 ppm to
52,000 ppm were detected in subsurface soils in two isolated
locations at the site; east of the wrecker building,  and
southeast of the truck wash.  Blast slag samples contained
total lead concentrations ranging  from 18,500 to 94,800
ppm. Total lead and lead leachate concentrations in a floor
wipe sample collected from the furnace and raw materials
refinery  building  were 14,700  ppm  and  574 ppm,
respectively.

Sampling results of surface water samples and sediments
revealed concentrations of several inorganic compounds that
exceeded background concentrations. Significant inorganic
contaminants included antimony, arsenic, cadmium, iron,
lead, and manganese. Lead concentrations in surface water"
were found as high as  1,600 ppb. Lead concentrations in
sediment were found as high as 98,100 ppm.

SUMMARY OF SITE RISKS

As part of the RI/FS, an analysis was conducted to estimate
the  human health or environmental problems that could
result if contamination at the Site is not cleaned up. This
analysis, known as a Baseline Risk Assessment, focused on
the  current and future  human health and environmental
effects from long-term direct exposure to the contaminants
found at the Site.

EPA has concluded that the major risks to human health at
the site would be incidental ingestion of contaminated soil.
The contaminant of greatest concern in these media is lead
which causes well known health effects, especially in young
children.  At the present time, nc^ unacceptable exposure is
occurring because no  one is drinking water from  the
contaminated aquifer and no one is in regular contact with
contaminated soil.

Additional pathways were evaluated or considered, but the
current  and future impacts  were  found to be within
acceptable risk levels. For example, direct contact exposure
to contaminants in soil, sediment, and surface water was
examined, but the risks associated with these pathways were
found to  be negligible.  Similarly, possible  exposure to
surface water via  inadvertent ingestion  while wading and
exposure to soil via inhalation to dust were examined and
found to be unimportant in terms of potential health effects.

-------
 SCOPE AND ROLE OF RESPONSE ACTION

 As previously stated, this response action addresses only the
 cleanup of the contaminated soils, buildings, and wetlands.
 Tie cleanup of the source materials is proposed to prevent
  xposure to the contaminated source materials and prevent
'further contamination of groundwater and surface water.

 The preferred alternative will address:

        Waste Slag (landfilled and stockpiled)
   •    Contaminated soil (in facility area and landfill area)
   •    Buildings
   •    Demolition debris (pavement)
   •    Contaminated sediment (in wetlands)

 EPA generally expects to use treatment to address principal
 threats posed by  a site, wherever practicable.   Principal
 threat wastes  are those source materials considered highly
 toxic or mobile that cannot be reliably contained or would
 present a significant risk to human health or the environment
 should exposure occur. For the Ross Metals Site, principal
 threat wastes  would conservatively include:

   •    600 cubic yards of soil
   •    8,200 cubic yards of sediment
   •    6,000 cubic yards of stockpiled slag
         10,000 cubic yards of landfilled slag

 Based on new information or public comments, EPA in
 consultation with the State of Tennessee, may modify the
 preferred alternative  or  select another response action
 presented in the Proposed Plan and the FS Report.   The
 public is encouraged to review  and comment on all
 alternatives identified.

 SUMMARY OF SOURCE MATERIAL
 ALTERNATIVES

 This section summarizes the 6 source material alternatives
 that EPA evaluated.

 Institutional controls (e.g., future land use restrictions, local
 zoning ordinances, or permitting requirements) and security
 fencing are common components to all the alternatives that
 include capping (S-2, S-3, S-4, S-5A, S-6A and S-6B).

 The alternatives that leave contamination on Site (S-l, S-2,
 S-3, S-4, S-5A, S-6A, and S-6B) would involve continued
 monitoring of the Site. EPA would assess the risks to human
 health and the environment every five years.
Alternative S-l
  No Action            .

Under this alternative, no action would be taken to remedy
the contaminated surface soil, slag, sediment, or other solid
media.

Alternative S-2
  Capping

This alternative includes the demolition of most of the on-
Site pavement and buildings.  The main office building and
the pavement surrounding this building  would remain on
Site,  and  landfilled  waste  would  remain   in  place.
Contaminated soil beneath the pavement would be excavated
and consolidated with the stockpiled slag, pavement,  and
building debris. This waste material would be  disposed in
an on-Site excavation that would extend from the existing
landfill to about 375 feet south of the landfill.  This disposal
area would be about 400 feet wide and 8 feet deep, although
it could be enlarged somewhat if necessary. A soil cushion
layer, a geosynthetic liner; a soil cover, and topsoil with
grass seeding would be placed over the buried contaminated
material. The new landfill would cover about 6.7 acres.

Alternative S-3
  Capping with Pavement in Place

Alternative 3 differs from Alternative 2 in that the waste is
not disposed of in an excavation, but rather spread over the
existing pavement and capped in place with the existing
landfill. Alternative 3 includes the demolition of most of the
on-Site buildings. The main office building would remain on
Site, and the landfilled  slag would remain in place.
Contaminated soil from areas  not  covered  by pavement
would be excavated and consolidated with the stockpiled
slag and building debris, and excavated wetland sediment.
This material would be spread above the pavement  that
extends from the existing landfill to about 375 feet south of
the landfill. A soil cushion layer, a geosynthetic liner, soil
cover, and topsoil  with grass seeding would be  placed over
the contaminated material. The new landfill would be about
6.7 acres.

Alternative S-4
  Capping with Construction of/Above-Ground
  Disposal Cell

Alternative 4 differs from Alternatives 2 and 3 in that waste
is not disposed of in the area of the existing pavement;
instead, it is consolidated .over the surface of  the existing
landfill and capped in place.  This method would result in a
disposal cell approximately 17 to 18 feet high throughout the

-------
 landfill area. This alternative includes the demolition of on-
 Site pavement and buildings. The main office building and
 the pavement immediately surrounding this building would
 remain on Site, and landfilled slag would remain in place.
 Contaminated soil beneath the pavement would be excavated
  .id consolidated with the stockpiled slag, pavement,  and
 building debris.' A soil cushion layer, a geosynthetic liner, a
 soil cover, and topsoil with grass seeding would be placed
 over the contaminated material.  The new landfill would be
 about 2.5 acres.

 Alternative S-5
   Excavation and On-Site Treatment with
   Solidification/Stabilization

   Option A - On-Site Disposal of Treated Waste

 Option A for Alternative 5 includes the decontamination and
 demolition of most of the on-Site pavement and buildings.
 The main office building and the pavement surrounding this
 building would remain on Site.  The building debris  and
• pavement  would be decontaminated  by steam/pressure
 cleaning. Contaminated soil throughout the Site, and buried
 slag in the landfill would be excavated and consolidated with
 the stockpiled slag. Contaminants within soil and slag would
 be physically bound or enclosed within a stabilized mass
 (solidification), or chemical reactions would be  induced
 between a stabilizing agent and the contaminant to reduce its
 mobility (stabilization).  Solidification/stabilization treatment
 technologies include the addition of cement, lime, pozzolan,
 or silicate-based additives  or chemical reagents  that
 physically or chemically react with the contaminant. Once
 treated and confirmed to be nonhazardous, the soil and slag
 would be  consolidated  with the  pavement debris  and
 disposed of in an on-Site excavation. The decontaminated
 building debris would be taken off Site to a metal recycling
 facility. The on-Site disposal area would extend from the
 northern boundary of the existing landfill to about 700 feet
 south of the landfill (100 feet north of the Site entrance) and
 would be about 250 feet wide and 8 feet deep. A soil cover
 and topsoil with grass  seeding  would be placed  over the
 entire Site. The new landfill would be about four acres in
 size.

   Option B - Off-Site Disposal of Treated Material

 Option B for Alternative 5 is similar to Option A in that it
 also consists of the decontamination of most of the on-Site
 pavement and  buildings and on-Site treatment.  The main
 office building and the pavement immediately surrounding
 this building would remain on Site. The building debris and
 pavement would be decontaminated by steam cleaning. The
 decontaminated building debris would be taken off Site to a
metal recycling facility.  Contaminated soil throughout the
Site, and buried slag in the landfill would be excavated and
consolidated with the stockpiled slag. Contaminants in soil
and slag would be treated by solidification or stabilization.
Option B differs from^ Option A in that after treatment and
confirmation that the soil is nonhazardous, the treated soil
and slag would be hauled off Site to a disposal facility. A
soil cover and topsoil with grass  seeding would be placed
over the entire site.

Alternative S-6

  Option A - Capping with Excavation and OnSite  .
  Treatment of Principal Threat Waste

Alternative 6  is similar to Alternative  5  in that it also
includes the excavation  and treatment  of contaminated
material  via   solidification/stabilization.     However,
Alternative 6 differs from Alternative 5 in that treatment is
limited to only that material that is considered a principal
threat. As previously stated, principal threat waste includes
the landfilled and  stockpiled slag, anS approximately 500
cubic yards of soil.

Option A for Alternative 6 includes the demolition of most
of the on-Site buildings.  The main office building  would
remain on Site. The building debris and pavement would be
decontaminated by steam/pressure cleaning. Principal threat
wastes would be excavated and consolidated with the stock-
piled slag. Contaminants in the principal threat waste would
be treated by solidification or stabilization.

Contaminated soil from areas not covered by pavement, and
non-principal threat landfill soil would be excavated for and
placed in an on-Site landfill along with the treated principal
threat waste.  This waste (and treated) material would be
disposed in the excavated landfill area (450 x 250 x 5 ft.
deep).  A soil cushion layer, a geosynthetic liner,  a soil
cover, and topsoil with grass seeding would be placed over
the entire site. The new landfill would be about 6.7 acres in
size.

  Option B - Off-Site Disposal of Treated Principal
  Threat Waste

Option B is similar to Option A except that treated principal
threat waste is disposed in an off-Site landfill rather than
being capped on Site with the low-level threat waste. Like
Option A, Option B for Alternative 6 includes the demolition
of most of the on-Site buildings.  The main office building
would remain on Site.  The building debris and pavement
would be decontaminated by steam/pressure cleaning. On
Site contaminated soil considered principal threat waste, and

-------
buried slag  in  the landfill  would  be excavated  and
consolidated with the stockpiled slag. Contaminants in soil
and slag would be treated by solidification or stabilization.
Contaminated soil from areas not covered by pavement, and
 in-principal threat landfill soil would be excavated for
   .cement in an on-Site landfill. This low-level threat waste
material would be disposed in the excavated landfill  area
(450 x 250 x 5 ft deep). A soil cushion, ageosynthetic liner,
a soil cover, and topsoil with grass seeding would be place
over the entire Site.  The new landfill would be about 6.7
acres in size.

SUMMARY OF WETLAND ALTERNATIVES

This section summarizes the three wetland alternatives that
EPA evaluated.

Institutional controls (e.g., future land use restrictions,
local zoning ordinances, or permitting requirements) are
included as components for alternatives W-l and W-2.

Each of the alternatives include a site monitoring program.

Alternative W-l
  No Action

Under this alternative,  no remedial action would be taken
with respect to the wetlands. A monitoring program would
 '6 implemented to address wetland sediments, surface water
 .id associated uptake  by biota utilizing the affected area.
The  monitoring program would be developed in order to
allow for  regulators  to  assess  the migration of the
contaminants from the wetlands and determine if additional
action is necessary.  The monitoring program would take
place on a yearly basis and an EPA evaluation conducted
every five years.

Alternative W-2
  Institutional Controls and Creation ofOfT-Site
  Wetlands

Under this alternative, a cap consisting of at least one foot
of natural soil would be placed over the 5.7 acres of
contaminated wetland sediment and graded evenly  The
final component of this alternative is the creation of an off-
Site wetlands to mitigate the loss (due to contamination) of
the Site wetlands. The purpose of the off-Site creation of
wetlands is to match the functional value of the Ross
Metals Site wetlands where sediment is contaminated
greater than 800 ppm - approximately 5.7 acres. The
creation of an off-Site wetlands under this alternative
would involve the determination of the functional value of
 he Site wetlands; acquisition of an appropriate type and
area of land to create the off-Site wetlands; and vegetation
of the off-Site land to match or better the functional value
of the Site wetlands.

Alternative W-3
  Excavation and Revegetation/Restoration of
  Wetlands

Option A - Regrading with Clean Fill

Alternative 6 involves  the  excavation  of contaminated
wetland sediments to a depth of one foot, and under Option
A, replacing that material with clean soils. Excavated areas
will be backfilled to the existing grade and  revegetated
according to the Wetlands Revegetation Plan developed for
the  Site wetlands.  Maintenance plans  to  eliminate the
intrusion of less desirable species and to promote success
would be developed and Site monitoring would also be
required.  Excavated sediments would be stockpiled with
contaminated surface  soils and  final disposition of the
contaminated wetlands sediments would follow the Source
Material Alternative selected for surface'soils. In excavating
the  approximately  5.7  acres  of  sediment with lead
concentrations greater than 800 ppm to a depth of one foot;
approximately 9,300 cubic yards of contaminated sediment
would be generated. Approximately 8,200 cubic yards of
the excavated sediment would be considered principal threat
waste and 1,100 cubic yards would be considered low-level
threat waste.

Monitoring would be required to assess the effectiveness of
the cleanup action.

Option B - Regrading with Biosolid Compost Material  •

Option B is similar to Option A except that excavated areas
would be backfilled with a .biosolid compost material rather
than clean fill. The compost would serve as the fill material,
a metal-binding material and as  a source of fertilizer to
encourage revegetation/restoration.

As is the case for Option A, excavated sediments would be
stockpiled  with contaminated  surface  soils  and  final
disposition of the contaminated wetlands sediment would
follow the Source Material Alternative selected for surface
soils.  In excavating the approximately 5.7 acres of sediment
with lead concentrations greater than 800 ppm to a depth of
one foot; approximately 9,300 cubic yards of contaminated
sediment will be generated.   Approximately 8,200 cubic
yards of  the excavated sediment would be considered
principal threat waste and 1,100 cubic yards would be
considered low-level threat waste.

-------
  EVALUATION OF
  ALTERNATIVES

  The EPA preferred alternatives for
  'ic  Ross Metals Superrund Site,
   perable  Unit  #1  is  Source
  Materials  Alternative  S-5B  and
  Wetlands Alternative W-3B. Based
  on  current  information,  these
  alternatives provide the best balance
  of the nine criteria that EPA uses to
  evaluate alternatives. These criteria
  are described on the next page.  The
Evaluation of Cleanup Alternatives
Tables on pages  7-8 provide  an
analysis  and comparison  of the
alternatives  considered.    The
following information is  regarding
two  of these   criteria,  State  of
Tennessee   and   community
acceptance,  that  is  not  fully
addressed on the evaluation table.

State of Tennessee Acceptance

The State of Tennessee has assisted
EPA in the review of reports and
Site  evaluation.  The  State has
tentatively agreed with the proposed
remedy  and  is  awaiting  public
comment before final concurrence.

Community Acceptance

Commuity acceptance of the various
alternatives will be evaluated during
the 30-day public comment period
and will be described in the Record
of Decision (ROD) for the Site.
                            CRITERIA FOR EVALUATING REMEDIAL ALTERNATIVES

 EPA always uses the following nine criteria to evaluate alternatives identified in the Feasibility Study.  The remedial
 alternative selected for a Superfund site must achieve the two threshold criteria as well as attain the best balance among
 the five evaluation criteria. The nine criteria are as follows:

                                            THRESHOLD CRITERIA

 Overall Protection of Human Health and trie Environment: Degree to which each alternative eliminates, reduces, or controls
 threats to public health and the environment through treatment, engineering methods or institutional controls.
                                           "       f          x
 Compliance with Applicable or Relevant and Appropriate Requirements (ARARs): Alternatives are evaluated for compliance
 'with all state and federal  environmental laws and regulations and^are determined  to  be applicable or relevant ;and
  ppropriate to the she conditions.                                                                      •.?;.-'.'. ••••V1'

                                           EVALUATING CRITERIA                                       ;   ;

 Cost: The benefits of a particular remedial alternative are weighed against the cost.

 Implementability: Technical feasibility (e.g.,  hp.w difficult the alternative is to construct and operate) and administrative
 ease (e.g., the amount of coordination with ;o,th0r government agencies that is needed)  of a remedy, including the
 availability of necessary materials and services.

 Short-Term Effectiveness: The length of time needed ,to implement each alternative andjthe "risks that may be posed  to
 workers and nearby residents during construction and implementation.
             .'•'••              '„',""'            ''         .  " ,          *       '       '    ><
 Long-Term Effectiveness: The ability to maintain reliable protection of public health and the environment over time once
 the cleanup goals have been met.

 ; Reduction of Toxlcrty. Mobility, and Volume: Degree  to which an alternative reduces (1) the harmful nature of the
 contaminants, (2) their ability to move through the environment, and (3) the volume or amount of contamination at the
- site/  :/   • '.;" ':< "i'y i;           ,    ' -   -%  f,     ,„     ^             r   "

                   '•'•                       MODIFYING CRITERIA

 State Acceptance: EPA requests state comments on the Remedial Investigation and Feasibility Study reports, as well  as
 the Proposed Plan, and must take into consideration  whether the state concurs with, opposes, or has no comment  on
 EPA's  preferred alternative.                  :

 Community Acceptance: To ensure that the public has an adequate opportunity to provide input, EPA holds  a public
  .omment period and considers and responds to all comments received from the community prior to the final selection of
 a remedial action.
                                                      6          .     '

-------
EVALUATION OF SOURCE .AL CLEANUP ALTERNATIVES
Alternative
S-1- No Action
% v
S-2- Capping
S-3~ Capping with
Pavement In Place
S-4- Capping with
Construclion of Above-
Ground Disposal Cell
S-5A - Excavation and
On-Slte Treatment with
SoHdification/Stablfizatlon
and On-Slte Disposal •
-• • ...:...
S-5B - Excavation arid"
On-Slte Treatment with
Solidification/Stabilization
and Off-Site Disposal
S-6A -Capping with :
Excavation and On-Sile
Treatment and On-Slte
Disposal... .; . .
S-6B - Capping with
Excavation and On-Slte
Treatment and Off-Site :
Disposal of Treated
Principal Threat Waste
OvBral Protection of
Human Healtti and
Environment
NO
YES
YES
YES
YES
YES
: YES
YES
Compilancewih .
- ARARs'
NO
YES
YES
YES
YES
YES
YES
YES
ReduclkxiofToxfcity.Mobitityand
. / Volume (TWy) ;::;;:-
Does not affect TMV.
Toxlctty and volume unchanged.
Mobility significantly reduced.
Does not meet expectation for
treatment.
Toxic'rty and volume unchanged.
Mobility significantly reduced.
Does not meet EPA expectation
for treatment.
Toxtclty and volume unchanged.
Mobility significantly reduced.
Does not meet EPA expectation
for treatment.
Toxlclty and mobility virtually
eliminated. Volume may increase
Meets EPA expectation for
treatment.
Toxloity and mobility virtually
eliminated. Volume may Increase
Meets EPA expectation for
treatment
Toxlclty and mobility virtually
eliminated. Volume may increase
Meets EPA expectation for
treatment.
Toxictty and mobility virtually
eliminated. Volume may increase
Meets EPA expectation for
treatment.
'. ' Short-Term Effectiveness, .
Does not achieve goals2
0 years
Goals achieved. Protective
equipment required. Noise
nuisance.
6 months
Goals achieved. Protective
equipment required. Noise
nuisance.
6 months
Goals achieved. Protective
equipment required. Noise
nuisance.
6 months
Goals achieved. Protective
equipment required. Noise
nuisance.
6 months
Goals achieved. Protective
i equipment required. Noise
nuisance.
6 months
Goals achieved. Protective
equipment required . Noise
nuisance.
6 months
Goats achieved. Protective
equipment required. Noise.
nuisance.
6 months

. .. -..-• Imptementabllity '•• ,-. •:
Routine monitoring. Readily
Implemented.
Technology readily available and
constructed. Capping In a floodplaln
and wetlands.
Technology readily available and
constructed. Capping In a floodplaln
and wetlands.
Technology readily available and
constructed. Capping In a floodplain
and wetlands.
Technology readily available.
Moderately complex to Implement.
Capping In a floodplaln.
Technology readily available.
Moderately complex to Implement.
Technology readily available.
Moderately complex to Implement..
Capping in a floodplaln.
Technology readily available.
Moderately complex to Implement.
Capping in a floodplain.
Present Net
Worth
(•w/wetlands)
$100,247
$1.712.412
$1,735,804*
$1.430.411
$1,453.803'
$1.481.865
$1.505,847'
$4,244,992
$4,907.274'
$6,181,160
$7.477,199'
$2,729.543
$3,175,137'
$4.013,508
$4,936,044'
Ranked
Preferable
Alternative
S
7
5
6
4
1
2
3
Notes:    ' ARARs - Applicable or Relevant and Appropriate Requirement; * Goals (prevent human contact and further degradation of groundwater).

-------

Alternative


W-2 - Capping w/Clean Fill
and Off-Sile Creation of
Wetlands . ..•
W-3A- Excavation and
Revegetalfon/Restoratlon of
Wellands and Regrading
w/CleariFIII ' . : -"••

W-3B-'Excvallonand .
RevegetattorVRestoratfon of •
Wetlands and Regrading with
Biosplid Compost . . •.';."".

Overall '
Protection of
Human Health
and .
Environment

NO
Potentially

YES


YES


Compttencevrfth
ARAR31

NO
NO

YES


YES

EVALUATION OF WETLAND
ReducfcnofToxtcJty.Mobityond
VotumefJMV)

No reduction of TMV
No reduction in toxlcity or volume.
Reduction of mobility. Does not
meet EPA expectation of treat-
ment
TMV virtually eliminated.


TMV virtually eliminated.

S CLEANUP ALTERNATIVES
Short-jerm Eff
-------
     EPA's PREFERRED ALTERNATIVE

"Tie EPA preferred alternatives are Source Materials
  temative S-5B and Wetlands Alternative W-3B.
.cased upon  current information, these alternatives
appear to provide the best balance "among the nine
criteria that EPA uses to evaluate alternatives., EP. A
has determined that the preferred alternatives wouldte
protective of human health  and the environment;
would attain the Site goals; comply with ARARs; and
would be cost effective. ;.

The preferred alternative consists of the following-

•       Decontamination/ demolition of pavement and
        buildings with recycling of metal debris;^

•       Excavation of contaminated  soil, landfill ed
        slag, and contaminated wetlands sediment and
        appropriate confirmation soil sampling;

        Backfill of excavated soil areas and landfill
        with clean soil;

V-      Stabilization or solidification of contaminated
 ;       soil,:  stockpiled slag,  landfilled slag, and
 •'"• ,     wetlands sediment;

 •       Off-Site disposal of soils, slag, and sediment
  '..     at nonhazardous disposal facility,

r  :     Application of a layer of biosolid compost to
! '';     the entires Ross ;MetaIs Site. Grass seeding of
 :';>     thefacnlii^and landfill areas;andrevegetation
        of the Site wetlands according to the wetlands
',•••-     revegetation plan developed by EPA, 1998.

 • •      Development of maintenance and monitoring
        plan to assess the effectiveness of the cleanup
        action.

The total estimated construction costs associated
 with both alternatives are $ 7,736,897. The
•estimated Operations and Maintenance costs are
 $242,969. The estimated total  present worth costs
 are $ 7,979,866.
THE NEXT STEP:  THE COMMUNITY'S ROLE IN
           THE SELECTION PROCESS

EPA solicits input from the community on the cleanup
alternatives proposed for each Superfund site.  EPA has set
a public comment  period from  November  18, 1998
through  December  18,  1998,  to  encourage  public
participation in the selection process. The comment period
includes a public meeting at which EPA will present the
RI/FS Report and Proposed Plan,  answer questions, and
receive both oral and written comments.

The public meeting is scheduled for 6:30 PM, November
30,1998, and will be held at Rossville Christian Academy
inRossville.

EPA is required to  extend the comment period, for a
minimum of 30 days, upon receipt of a timely request to do
so.  At the end of the public comment period, a summary of
all the questions and comments received from the public and
EPA's responses will be provided in the  Responsiveness
Summary.  The  Responsiveness Summary is included in
EPA's Record of Decision (ROD), which is the document
that presents EPA's final selection for Site cleanup.

The public can send written comments to or obtain further
information from:

                    Beth Brown
              Remedial Project Manager
                 U.S. EPA Region IV
                61 Forsyth Street, S.W.
             Atlanta, Georgia 30303-3104
                  1-800-435-9233 or
	•    404-562-8814     	

The Proposed Plan and the RI/FS Reports have been placed
in the information repository and Administrative Record for
the Site. These documents are available for  public review
and copying at the following location:
                  Rossville City Hall
                  360 Morrison Road
               Rossville, Tennessee 38066

-------
                                                   GLOSSARY
  Administrative Order on Consent: A legal and enforceable
      ment signed between EPA and Potentially Responsible
       ; (PRPs) whereby PRPs agree to perform or pay the cost
      3 investigation.
  Biosolids: Organic matter (e.g., wood ash, compost, or waste-
  water treatment plant sludge) that can be used with topsoil for
  stablizing slopes, reducing erosion, and providing a nutrient-rich
  invironmcnt for vegetation.                     .       '..-

  Blast Slag: A by-product or waste that is generated during the
  lead smelting process.

  Comprehensive, Environmental Response, 'Compensation,
  and Liability Act (CERCLA): A federal law passed in 1980
  and amended in 1986 by the Superfund Amendments 'land ,.'•
  Reauthorization Act.  This law created; a special tax that goes •"
  into a trust fund, commonly known as Sluperr^d,;to'investigat^ •
 and clean up abandoned or uncontrolled hazardbus^asls sit«. •! ' ;
 Under the Superfund .program," EPA can  either., pay for 'site ";
 cleanup when the responsible parties cannot be located pr'^are '  :
 unwilling or unable to perform the work, or take legal action^ ; :
 force responsible parties to clean up the site or reimburse EPA "
 for the cost of cleanup.

 Feasibility Study (FS): A Feasibility Study evaluates different .
 remedial alternatives for site  cleanup and  recommends .the  "•
 alternative that provides the best balance or profectiveness
 f  -Uveness, implementabilhy, and cost.     '  ;  ;      ;V.:-':

 i    synthetic Liner:   A man-made textile that significantly
 reduces rainwater from  passing throgh  its 'tightly woven
 structure of plastics and clay.

 Groundwater:  Water beneath the earth> surface that .fills
 spaces among soil, sand, rock, and gravel.  Precipitation, such
 as rain, reaches the ground and then slowly moves tfarpugh soil  :
 sand, gravel, and rock into small cracks and creyices'telowjthe ':
 ground surface. During a 'process that can take'inaiiy :ye4rs : ":-'!:
groundwater has the potential of becoming" a /drinking water
SOUrce.:          _-=       ...-,•• •• .H^^^rryiT-'l^sv-;. '.

Institutional Controls: Legal mechanisms to prevent human' ^
exposure to contamination remaining on hazardous ; waste : sites.  :
                                           .when .\yater:
                                           !and collects
Lcachate:   A contaminated liquid jresultingX
percolates or trickles through waste materials"1
components of those wastes.

Monitoring: The continued collection of information atout the
enwonmcntthat helps gauge the effectiveness of a:cleanup:i-
   National Priorities List (NPL):  EPA's list of the most serious
   uncontrolled or abandoned hazardous waste sites identified for
   possible long-term remedial action under Superfund.

   Parts Per Billion (ppb or /zg/L): A unit of measurement used
   to describe levels of contamination.  For example, one gallon of
   a liquid in one billion gallons of water is equal to one part per
   bilhon.                                                  .

   Parts Per Million (ppm or mg/L): A unit of measurement
   used  to describe levels of contamination.  For example  one
   gallon of a liquid in one million gallons of water is equal to one
.'part per .million.

   Preferred Alternative: EPA's selected best alternative based
   on mformatiori collected to date, to address contamination at a
  site.'.";!.:.;.:;;;'.         •'-..-.:

;• Prop/osed Plan:  A fact sheet summarizing EPA's preferred
•; cleanup  strategy for a Superfund siteV the rationale  for the
  preference,; and a review of the alternatives developed in the
 ;RI/FSprocess,  '           '       '    :"            ;  '":-.:.

  Resource Conservation and Recovery  Act (RCRA): A law
  that  established a regulatory system  to  track  hazardous
  substances from the time of generation to disposal.  Provides
  closure and post-closure minimum requirements for landfills^

  Record of Decision (ROD):  A public document that explains
  which Cleanup alternative will be used at an NPL site and the
  reasons  for choosing that cleanup  alternative over other
  possibilities.

  Remedial Alternatives:   A list of the  most technologically
  feasible alternatives for a cleanup strategy.              •

  Rem^diaJ, Design:  An engineering phase  that  follows the
••  •999S?.*? Decision when technical drawings and specifications
 ?r? ye$5lppe'd for the cleanup action at a Superfund  Site" ••

:;^?.??5^'-lllvestiga*i.o;n';' (HI)1   A  Remedial Investigation
,exarnuies the. nature and extent of .contamination problems at a


 Responsiveness  Summary:   A summary of written or oral
:; comments;:received by EPA during a public comment period.

: Superfund:  A term commonly used to  describe'-the Federal
 program established by CERCLA.

 Superfund Amendments and Reauthorization Act (SARA)-
 Amendments to CERCLA enacted on October 17, 1986.

Treatability Study: A study to evaluate the effectiveness of a
technology in remediating contamination.
                                                       10

-------

-------

-------
                             STATE OF TENNESSEE
                DEPARTMENT OF ENVIRONMENT AND CONSERVATION
                      MEMPHIS ENVIRONMENTAL FIELD OFFICE
                            SUITE E-645, PERIMETER PARK
                               2510 MT. MORI AH
                           MEMPHIS, TENNESSEE 38115-1520
 February 3,  1999

 Ms.  Beth Brown
 Remedial Project Manager
 U.S.  Environmental  Protection  Agency
 Region 4 ,
 61 Forsyth  Street,  SW                 •
 Atlanta,  GA  30303-3104

 RE:   Ross Metals Superfund  Site  (TND  09-607-0396)
      Rossville,  Fayette  County, Tennessee                   • •
      ELM, Inc.  and  Leed  Environmental,  Inc. Comments on proposed ROD
      Dated  January  18, 1999

 Dear  Ms.  Brown:

 I  have  reviewed the copy of the comments you forwarded to this office
 and  have some responses  concerning these comments.   Specifically, I
 will  address the  areas  covered  by the  Regulations  Governing Solid
 Waste Processing and  Disposal  in  Tennessee,  Rule Chapter 1200-1-7.

 The  commenters  state  that  the facility  is not in  the  100  year flood
 plain.    Additionally,  they  state that  the  Rossville  POTW  is  not
 included  on  the FEMA flood  maps.   The  July 5,   1983  Flood Insurance
 Rate  Maps for Rossville  and  surrounding Fayette  County show that this
 facility  is  in  the  100  year  flood  plain  and  clearly  show  the
 Rossville POTW.  -Portions of the  facility may have been raised above
 the 100 year flood, but the  existing disposal  area is in the 100 year
 flood plain.    While  the Tennessee Regulations  do not preclude  the
 placement  of  a  landfill  unit  in the  100  year  flood  plain,  the
 standard  practice has been  to totally remove  the facility  from  the
 flood plain by  constructing a  levee.    In  no case  would  any facility
 be located in the flood way.  Additionally, Rule  1200-1-7-.04(3)(a)4.
 requires  a  200  foot  buffer  between  a  fill  area  and  the  normal
boundaries of springs, streams, and lakes.  The commenters  claim that
the proposed  off-site landfills   are  also located in  the 100  year
 flood plain, without a list of the proposed facilities  I  can not make
a  global  assertion,   however no currently  operational   Class   I
 (Sanitary) landfill in  Tennessee  within 100 miles of this  facility
are located in a 100 year flood plain.

The existing on site landfill predates the RCRA.Subtitle  WD"

-------
 Ms. Beth  Brown
 February  3,  1999
 Page 2


 compliant Tennessee Regulations and is therefore -not subject to them.
 Any new waste disposal activity would have to  fully  comply with the
 Regulations.    This  would  include  the requirements  for a  geologic
 investigation  and a  design that  included  a synthetic  liner.   The
 proposed  alternate plan does not appear to include these in it's cost
 estimate.

 Of  particular  concern to  the  Tennessee Division  of  Solid  Waste
 Management is  this  facility's  location in the recharge  zone  for the
 "Memphis  Aquifer".    Numerous  private and public  wells are  located
 down  gradient  from  this   facility.    While  a  geologic  buffer  is
 indicated  on the bore logs for  the  on-site monitoring wells/  the
 permeability of the underlying soils has not  been established.

 The commenters  apparently missed  some portions  of the record.   Ross
 Metals  was  issued a  Notice of Violation for the existing  disposal
 site on June 16, 1986.  The Notice of Violation  required Ross  Metals
 to either  register  the site or to  close  it.   Ross  Metals chose  to
 apply for a permit and submitted an application.  As was  the practice
 at  that  time/  the   Division  Geologist  conducted  a  preliminary
 Hydrogeologic Review  of  the site  and determined that  the  site, may
 have been suitable  for  a  landfill.    On December  20,  1988,  Paul
 Patterson  of  the Memphis  DSWM Office  notified  Ross  Metals that the
 review  of  their landfill application would  be   suspended  until the
 status  of  the slag could be  determined.

 Considering the sites  susceptibility  to inundation,  the presence  of
 wetlands,  and the facility's  location in the recharge  zone for the
 Memphis  Aquifer, on-site  disposal  of the slag,  as proposed, presents
 the  potential  for harm to  the public  health and  the   environment.
 Specifically,  the  plan does  not  describe  any  liner  and  leachate
 collection system.

 Should  you have  any  questions  about  this letter or  the Regulations .
 Governing  Solid Waste  Processing  and Disposal  in  Tennessee,  please
 feel free  to  contact me at  (901) 368-7948.
Sine
     Boatrightj, P.E.
 ^vision of Solid Waste Management

JWB\79019034\ag

c:    DSWM MEAC File
     DSWM NCO File
     Jordan English, TDSF/MEAC

-------
                 United States Department of the Interior
                                FISH AND WILDLIFE SERVICE
                                        446 Neal Street
                                     Cookeville, TN 38501
                                     January 22,1999
  Ms. Beth Brown
  U.S. Environmental Protection Agency
  Atlanta Federal Center
  61 Forsyth Street
  Atlanta, Georgia 30303-8960

  Dear Ms. Brown:

  U.S.  Fish  and  Wildlife  Service  (Service)  personnel  have  reviewed  the  Remedial
  Investigation/Feasibility Study (RJ/FS) for the Ross Metals Superfund Site in Rossville  Fayette
  County, Tennessee.  We have been actively involved with wetland and ecological risk issues
 regarding this  site  and  commend the Environmental Protection Agency (EPA)  for its close
 coordination with this office and Service representatives in Edison, New Jersey.

 The Service supports the preferred Source Materials (S-5B) and Wetlands (W-3B) alternatives for
 remediation of contamination at the site.  Based on the comments presented by the representatives
 of the primary  responsible parties (PRPs) at the January 19th meeting in Atlanta,  we could if
 necessary, a^o consider other alternatives for the final disposition of lead contaminated soil and
          l^r6^"8 S?dleS SUggeSt that °n-site disP°sa! of «cavnted soil and sediment is
       , potential additional wetland impacts should be fully evaluated and mitigated  Since onlv
       *1? *? reSt°rati0n Plan ^ °ffered by ** PRP'S *P^ntatives, we Lommend that a
     h 7  T dT!?lon;res!ora!lon'^^
    s be developed. This plan should consider and incorporate the technical information previously
provided by Roy F.  Weston, Inc. (U.S. EPA Work Assignment No.:  2-284) and the US  EPA
Environmental Response  Team Center, as well as any field data subsequently generated during
hydrogeological studies of the Ross Metals site.  A final plan should then be included ^
appropriate decision document and provided to this office for further review.

-------
We appreciate the opportunity to comment. Upon receipt of a ROD, the Service will evaluate the
effectiveness of the proposed remedy and whether a covenant not to sue for damages to Service trust
resources is appropriate.  Should you have any questions or need technical assistance regarding
wetland issues at the site, please contact Steve Alexander of my staff at 931/528-6481, ext. 210.

                                        Sincerely,
                                        Lee A. Barclay, Ph.D.
                                        Field Supervisor
xc:    James H. Lee, DOI, Atlanta
       Nancy Firdey, FWS, Edison, New Jersey
       Allen Robison, FWS-ES, Atlanta
       Patricia Cortelyou-Hamilton, DOI, Atlanta


-------
                                STATE OF TENNESSEE
              DEPARTMENT OP ENVIRONMENT AND CONSERVATION
                       MEMPHIS ENVIRONMENTAL FIELD OFFICE
                              SUITE E-645. PERIMETER PARK
                                   2510 MT. HORIAH
                             MEMPHIS, TENNESSEE 36115-1520
March 31, 1999

Ms. Beth Brown
Environmental Project Manager
United States Environmental Protection Agency
Region IV, Waste Management Division
61 ForsythSt.
Atlanta, GA 30303
Re:    Concurrence for the Record of Decision for the Ross Metals siie, Rossville, Fayette
       County, Tennessee, April 1999, TDSF $24-501.

Dear Ms. Brown:

The Tennessee Division of Supeifund (TDSF) has reviewed the draft Record of Decision for the
Ross Metals site. Kossville, hsyette County, Tennessee, received in this office on March 16,
1999.

The Tennessee Department of Environment and Conservation (TDF.r.) is in concurrence with
this ROD. The level of cooperation that has occurred among all agencies with regard to this site
has been extremely good.  TDEC is hopeful that this cooperation will serve 05 a model for future
relationships between die State Of Tennessee and EPA.

Sincerely,
James W. Ha>nes. Director
Tennessee Division of Superfund

C:     TDSF, NCO file
       TOSH, EAC-M file

-------

-------

-------

-------
February 9, 1999
Cindy Gibson
Community Involvement  Coordinator
North Site Management  Branch
United States Environmental  Protection Agency
Region 4
Atlanta Federal Center
61 Forsyth Street
Atlanta, Georgia 30303-8960

Dear Cindy:

          Enclosed please  find the transcript of the  U.S.
Environmental Protection Agency's public  meeting on November
30, 1998, at the Rossville Christian Academy in  Rossville,
Tennessee.

          I have made  the  few corrections that you requested
that I make and am returning this copy to you.  Since the
time of this hearing,  I have received and updated my
computer software.   This new update changed the  format of my
programming, and therefore changed the page layout of this
transcript.  Because of this I have gone  ahead and reprinted
the entire transcript  rather than just the few pages  that
needed corrections.  I draw  your attention to this simply
because you are still  in possession of the original
transcript, and the  pages  will no longer  match.

          I hope this  transcript now meets with  your
approval and will serve the  purposes for  which you had it
recorded.  If I can  be of  any further assistance to you,
please feel free to  contact  me.
 Sirfcerely,
      -x
'Debra A.  Dibble
Alpha Reporting  Corporation

-------

-------
 1




 2




 3




 4




 5




 6



 7




 8




 9




10




11




12




13



14




15



16



17




18




19



20



21



22



23




24
           EPA SUPERFIND SITE
       ROSS METALS, INCORPORATED
          ROSSVILLE, TENNESSEE
   at the Rossville Christian Academy
           November 30, 1998
      ALPHA REPORTING CORPORATION




    Debra A. Dibble, C.S.R., R.P.R.




Suite 210-A  -  100 North Main Building




           Memphis, TN 38103




             (901) 523-8974
            ALPHA REPORTING CORPORATION  -  (901)  523-8974

-------
   1




   2



   3



   4



   5



   6



   7



   8



   9



 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



24



25
                     PROCEEDINGS




            MS. BARRETT:  EPA is going to present  a brief



 history about the site, findings from the remedial



 investigation,  and the various options for cleaning  up the



 soil and the wetland area-here at the site.




            My name is Diane  Barrett.   I'm a community



 involvement  coordinator with  EPA.




            Cindy Gibson is the community involvement



 coordinater  for this site,  and usually — she is  on  an




 extended holiday with her family,  so she'll be back  to the '



 office soon.




      I would  like to,  first of  all,  introduce you to EPA



 participants.




           Beth  Brown.   If  you'll stand, please.   She is the



 site project manager.




           Harold Taylor, he is the chief of the



 Kentucky/Tennessee section in Atlanta.




           Marlene Tucker.   She is the attorney for the site.



           And Andy Hey, who's a paralegal specialist  also



 working  on the site.




           So  we  thank you both — all of you.



           Are there any officials with us tonight?



           I guess there is.  Thank you for being here.



          Are  there any other  officials?   Quite a  few  I



don't know.  City and county officials.
 18:32:33





 18:32:33





 18:32:36





 18:32:41





 18:32:43





 18:32:46





 18:32:49





 18:32:51





 18:32:56





 18:32:57





 18:32:55





 18:33:03





 18:33:03





 18:33:08





 18:33:10





 18:33:11





 18:33:16





 18:33:18





 18:33:23





 18:33:25





 18:33:26





 18:33:27





18:33:31





18:33:36

-------
  1               AUDIENCE:   Curry Morris.



  2               MS.  BROWN:   Let's point out one  thing.   We do have



  3     a court reporter,  so  she's recording everything  that's said



  4     at the meeting,  so that if at any point you'd  like to review



  5     what's been  said at the meeting, you can.



  6               So we  just  ask that if you do speak, that you bear



  7     in mind we're  trying  to record it.



  8               MS.  BARRETT:   I was going to say that,  but further



  9     on down.  You  beat me to it.   But I should have  said it



 10     earlier.



 11               Other  officials?



 12               AUDIENCE:   I'm Ken Spencer,  Alderman.



 13               AUDIENCE:   Ben Farley, Alderman.



 14      .         MS.  BARRETT:   Also,  we have  Sally Spencer here in



 15     the community.



 16           .    Representing  from the state?   State people?



 17               AUDIENCE:   Phil Davis.


 18               MS.  BARRETT:   Anybody else?    That's got  all  of



 19     these people,  and  then  all interested  citizens that  are



 20     here.   We welcome  you and thank you for  coming.  Thank  you



 21     very much for  coming.    This is  an important meeting.



 22               In order to help me  relay to you, and I'm  not  —



 23               Is this  anyone's first time  to attend a meeting?



24     All  right,  let's just cut to the chase.



25               AS you entered  the room tonight,  I hope you all
 18:33:42




 18:33:44




 18:33:48




 18:33:51




 18:33:52




 1B:33:56




 18:34:00




 18:34:02




 18:34:05




 18:34:06




 18:34:09









 18:34:21




 16:34:27




 18:34:47









 18:34:56




 16:35:00
   *.



 18:35:02




 18:35:06




 18:35:08




 18:35:15




18:35:21




18:35:22

-------
  1    got your information,  got a fact sheet.   It's what we're




  2    going to be discussing.



  3              Also, this packet is what Beth  is  going to be




  4    reviewing with everyone,  so this will help you follow along.



  5    It makes good night-time  reading.



  6              And then we  have information on capping and




  7    immobilization.  These are two of the alternatives that are



  8    being considered.



  9              And then lastly,  is  what is a superfund process.



 10    And so that's kind of  what I'm going to go through real



 11    quickly with you.



 12         Also,  as Beth did say earlier,  this is  an official



 13    meeting,  and it is being  recorded by our court reporter,  so



 14    as we speak,  if you would,  when it comes to  the question and



 15    answer period, if you'd just give your name  so that  she can



 16    make sure she gets it  accurately.



 17               A transcript will be made  of this meeting  and



 18     placed in the repository.  And usually we'll get  that  back



 19     about 14  working days  —  10, 14  working days,  and it will  be



 20     placed in the repository  for you to  look at.



 21               Right now,  we are —  you can't see this  real  good,



22     but  we are  right here in the public  comment period area.



23     And  after the public — after  this meeting tonight,  the




24     proposed  planning meeting, we will take  all of the comments



25     from this public comment period, which is  from November the
 18:35:24





 18:35:30





 18:35:30





 18:35:30





 18:35:36





 18:35:38





 18:35:41





 18:35:44





 18:35:45





 18:35:50





 18:35:52





 18:35:53





 18:35:59





 18:36:02





 18:36:04





 18:36:07





 18:36:09





 18:36:12





 18:36:16





 18:36:19





 18:36:23





 18:36:26





 18:36:31





 18:36:37





18:36:40

-------
  1    18th through December the  18th.  All  comments received

  2    tonight,  and in writing, a responsiveness  summary will be

  3    prepared  which will address all of the  comments we received.

  4    And this  responsivness summary will also be  placed in the

  5    official  document which is called the record of decision.

  6               And once that has been completed,  then we will, at


  7    that time,  start renegotiations with  the potential

  8    responsible parties, and see who will,  EPA or they,  will pay

  9    for and conduct the rest of the process, which is the design

 10    and the actual physical construction  of whatever treatment


 11    process we anticipate having.

 12         During this time, during the process  of selecting a

 13    remedy, we always have to make sure it  is, first of all,

,14    protective,  efficient, implementable, and  cost effective for

 15    handling  all of the contamination at  the site.

 16         These,  the steps that we have remaining,  will take

 17    about maybe twelve plus months, so it will be maybe the year

 18    2000, a little after the first of the year 2000 that actual

 19    cleanup activities might occur at this  site.   And so Beth

 20    will go into that more as a projection, but  at this time,

 21    that's kind of an estimate.

 22         And  that about concludes what I've got  to say as far as

 23    community relations.

 24               As this chart indicates,  community relations
                                *
 25    activities  happen throughout the event.  This is a process.
18:36:44


18:36:48


18:36:51


18:36:55


16:36:59-


18:37:04


18:37:07


18:37:12


18:37:18


16:37:22


18:37:26


18:37:29


18:37:36


18:37:36


18:37:44


18:37:48


18:37:51


18:37:56


18:38:01


18:38:03


18:38:09


18:38:12


18:38:17


18:38:17


18:38:20

-------
       The information repository is  housed there in the  city hall



       so  all of the documents should be  in there as they are



       developed.



                  We're holding public meetings,  presenting  fact



       sheets.



                 Another thing that will  occur is that once the



       process has been collected,  the record of decision has  been



       signed, then  we will have a notice  in  the newspaper



       announcing that collection,  and it  will be based on all of



 10    the data  that  we have,  all of the comments,  you know.   That



 11    will be how we will  select the technology.



 12         I guess that's  it.



 13              Are  there  any comments or questions  at this point?



 14         Okay.  I  thank  you for  your attention.   I will 'turn it



 15    over to Beth now.  And  as  she said, when  you do get ready to



 16    voice your comments, please  speak up so our court  reporter



 17    can hear.   Thank you.



 18         MS. BROWN:  Well,  thanks for coming  tonight.   I know



 19    it's probably tough to  get back in  the swing of  things  after



 20    Thanksgiving.



 21          It's  been a long time getting  to this point in the



 22     process, and  I'm pleased to say that we're at the decision



 23     point.   And we'd like you to  comment on it if you have  any



24     comments at all.  Like Diane  said,  there's information  over



25     at city hall.
 18:38:26





 18:38:30





 18:36:32




 18:38:33




 18:38:37





 18:38:37




 16:38:40




 18:38:44




 18:38:46




 18:38:49




 18:38:54




 18:39:00




 18:39:01




 18:39:05




 18:39:08





 18:35:14




 18:39:17





 18:39:20




 18:39:22
   '.



 18:39:24




18:39:27




18:39:30




18:39:33





18:39:37




 8:39:40

-------
  1              There's  probably, I don't know, five  or  six



  2    volumes like  this  worth of information, and  I'm going to try



  3    and condense  it  down at about the next ten minutes.   I don't



  4    want to overwhelm  you tonight.  I gave you a lot of



  5    information at the last meeting, that has some  of  the data



  6    results.  Tonight  is just going to be a real brief overview



  7    of how we got here.



  8              Tonight  I'd like to focus more on what the  cleanup



  9    alternatives are.   So this is basically what I'll  be



 10    covering.   The site  history,  what EPA has done  to  date,



 11    brief summary of the sampling results,  what kind of cleanup



 12    alternatives we've come up with, and probably what you  guys



 13    want to know most, when we're going to  actually move  some



 14    dirt.



 15         You folks probably know  the operational history  as  well



 16    or better  than I do.   It started operating in 1978 through



 17    1992.   It's my understanding  that  they  formed a — or



 18    administrative dissolution?



 19              MS.  TUCKER:   The company was  actually



 20     administratively dissolved.  And basically when a  company



 21     violates a corporate  law of the  state,  the state



 22     administratively dissolves  the corporation,  so  it's — it



 23     was  involuntarily dissolved, not voluntarily  dissolved.



24               MS.  BROWN:  And  I don't mind  questions in between



25     if you  do  have them, so  just let me  know.
 18:39:42




 18:39:46





 18:35:51




 18:39:55





 18:39:58




 18:40:00




 18:40:04




 18:40:05




 18:40:09




 18:40:13




 18:40:17




 18:40:22




 18:40:25




 18:40:27





 18:40:30




 18:40:34




 18:40:42




 18:40:45




 18:40:47
   *



 18:40:47 .




 18:40:54




 18:40:59




 18:41:02




18:41:07





18:41:09

-------
  1         Ross Metals actually was producing an alloy  that they




  2    later sold, and in doing so they  accepted wastes  from other



  3    industries as well as automotive  batteries.



  4         So far EPA has performed two removal actions,  the first



  5    one was in 1994-1995, where a pretty large volume of



  6    hazardous wastes were removed from the site, and  some




  7    temporary security measures were  taken.



  8              At the last meeting in  the spring, some of the



  9    citizens voiced concerns, and appropriately so, that they



 10    wanted — we had temporarily stored all  of the waste,  the



 11    slag,  blast slag in the buildings.   And  since then  the




 12    buildings were falling down, they were deteriorating,  and



 13    they also wanted some additional  security measures.



 14              It was pointed out that  people were actually




 15    breaking in the property, for what  reason we don't  know.



 16              So in the summer we actually put up additional



 17    fencing and we covered the wastes with tarps,  another



 18    temporary measure until we take our  final action.



 19        We've actually conducted at  least three or four



 20    investigations in the last three years.   We've collected



 21     soil samples,  sediment samples,  ground water,  surface  water.



 22     We've  done a lot of laboratory evaluations to find out



 23     whether  or not the  contaminants  out there would pose a risk



24     to the bugs and critters out there.



25               We also have to do human health risk assessments
 18:41:13





 18:41:19





 18:41:20





 18:41:29





 18:41:37





 18:41:42





 18:41:45





 18:41:47





 18:41:48





 18:41:54





 18:41:56





 18:41:59





 18:42:03





 18:42:09





 16:42:11





 18:42:13





 18:42:18





 18:42:21





 18:42:31





 18:42:35





 18:42:38





18:42:44





 18:42:47





18:42:50





18:42:53

-------
 1     to  determine whether  or  not there would be an impact to



 2     human beings should they come in contact with the waste, or




 3     the soils.



 A          That's about it.



 5          Wipe samples.  We actually took samples from the




 6     building by just taking  a cloth and wiping the buildings and




 7     then analyzing that.



 8               So that's about it.



 9          So as  a result of our investigation, EPA's determined




10     that we've  got a lot  of  contaminated media out there.  The




11     slag,  about 16,000 cubic yards,  surface soil about 32,000



12     cubic yards.  Very small amount of subsurface soil.  The



13     buildings are obviously  contaminated, and we've got a lot of



14     construction debris out  there that we need to take care of.



15          Ground water, the data has been misleading.  We're not




16     sure that we even have a ground water problem.



17              Unfortunately,  we're going to split that out.



18     We're going to go ahead  and take an immediate action, or an



19     action on the solid medias,  all  of these, slag,  soils,



20     buildings,  and demolition debris.   In the meantime,  we'll go



21     ahead and collect additional ground water data.



22          We decided to look  at the site in two ways.  The source



23     materials,  which are what's out  on the actual asphalt and



24     concrete pad where the buildings are,  and the wetland



25     sediments is another issue.  And so we determined that  the
18:42:55





18:42:58





18:43:01





18:43:06





18:43:07





18:43:10





18:43:13





18:43:15





18:43:23





18:43:30





18:43:33





18:43:36





18:43:41





18:43:45





16:43:48





18:43:51





18:43:55





18:43:59





18:44:01





18:44:06





18:44:09





18:44:23





18:44:28





18:44:31





18:44:36

-------
                                                                    10
   1



   2



   3



   4



   5



   6



   7



   8



   9



 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



24



25
 most  appropriate alternatives to consider are capping;



 excavation;  immobilization, which is basically just



 solidifying  it  with a type of cement; and disposal, which is



 either on  site  or off ^site.



       We're actually required to look at a no  action



 alternative,  just to give us a comparison of  whether the



 site  poses a  risk if we don't do anything verses  if we do,



 you know,  one or  some of these type of technology.



      Wetland sediments.   We considered certain types of



 surface water diversion,  sediment control to  keep the water''



 from going into the  wetlands and letting them dry up.   We



 looked at capping it,  excavating it,  treating it with some



 type of solidification,  or  mitigation is a term that's  used



 for when you contaminate a  wetlands.   EPA requires  that you



 either restore that wetlands  on  site,  or you have to  go



 somewhere else and create a brand new wetlands.



           And it's some ratio depending  on how important



 that wetlands is.   If it's a really important  wetland you



 might,  have  to,  say,  if you have  five  acres of  contaminated



 wetland,  you  may have to buy 15  acres somewhere else and



 revegitate  it  with all of these wetland type of plants.  So



 it gets into  a more expensive option when  you  get  into



 off-site mitigation.



     In your handout  there's actually some pictures  of what



some of these alternatives look like.   And actually,  there
 18:44:35





 18:44:44





 18:44:48





 18:44:53





 18:44:56





 18:44:58





 18:45:02





 18:45:07





 18:45:11





 18:45:15





 16:45:21





 18:45:24





 18:45:27





 18:45:33





 18:45:40





 18:45:42





 18:45:46





 18:45:51





 18:45:53





 18:45:55





 18:46:04





 18:46:04





 18:46:07





18:46:17





18:46:22

-------
                                                                   11
  1     are pictures of all  of  them except for 5-B.



  2               I'm trying to find my handout.  Here  it  is.



  3               The first  one is,  you know, the no action,  which,




  4     again, EPA requires  us  to evaluate,  for really  a comparison




  5     purpose.



  6          The second one  is  capping.   And if you'll  look  at  your



  7     handout.  And mine,  of  course,  are not in order.



  8               AUDIENCE:   10-10.



  9               MS. BROWN:  Yeah.   The first capping, the  S-2.



 10     The capping alternative really  looks at leaving everything



 11     in place as it is now,  and just  capping over it with  a  type



 12     of soil and clay, and then revegetating it so it would



 13     prevent, you know, contact with  what's there,  but  the waste




•14     remains there in place.



 15          The next alternative is capping with pavement in place,



 16     and on this alternative,  as  you  can  see,  we would  go  in and



 17     excavate some of the surface soils and then compile it all



 18     back on the landfill —  and  where  the pavement exists now,



 19     and build a cap over that.   So you end up with a cap that's



 20     about five feet above ground, and  it's about 600 feet long,



 21     verses the first alternative, which  was about  eight feet



 22     tall and about 375 feet  long.



 23          The next alternative  looks  at excavating  all of the



 24     surface soil,  and then piling it up  on the back part of the



 25     property,  which is the landfill  area,  so  you actually end up
 18:46:2''





 18:46:30





 18:46:32





 16:46:35





 18:46:40





 18:46:41





 18:46:45











 18:47:02





 18:47:07





 18:47:11





 18:47:16





 18:47:21





 18:47:26





 18:47:27





 18:47:34





 18:47:37





 18:47:42





 18:47:47





 18:47:52





 18:47:58





 18:48:02





 18:48:12





18:48:15





18:48:20

-------
12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
IS
16
17
18
19
20
21
22
23
24
25
with a pretty tall disposal cell, about 15 feet. But the
advantage of that is you end up with only a disposal cell
that's about 200 feet long, 400 feet wide.
Alternative 5a and 5b involve treatment with
solidification or stablization. And again, solidification
and stabilization is basically adding some kind of additive
that will chemically or physically bind the contamination so
that it's no longer mobile. It looks like a big concrete
mass.
And we evaluated it for disposing of that. Everything
on site, the soils, the sediments and waste, we would treat
it and leave it on site, or treat it and ship it off site.
And the last alternative 6, a and b, involves treating
the waste that poses the most risk, and shipping it off
site, which is option b, or leaving the treated principal
waste and leaving it on site.
So all of these alternatives either involve capping it
and not treating it, or treating it and capping it, or
treating and shipping it off.
AUDIENCE: Do we have a picture of 5b?
MS. BROWN: No. Because everything is gone.
Everything is treated and shipped off. The buildings, the
demolition debris, the pavement, it's all shipped off.
AUDIENCE: It's not hazardous to ship it?
MS. BROWN: We hope to achieve that so that the
18:48:23
18:48:30
18:48:34
18:48:49
18:46:55
18:49:00
18:49:03
18:49:09
18:49:14
18:49:18
18:49:27
18:49:30
18:49:39
18:49:44
18:49:50
18:50:02
18:50:05
18:50:07
18:50:12
18:50:29
18:50:32
18:50:36
18:50:39
18:50:42
18:50:45

-------
                                                                   13
 1    cost  will go down, because if you don't treat it you still



 2    have  a hazardous waste.   Number one,  it's expensive, and



 3    it's  difficult to ship  it off.   We have requirements when



 4    you treat it to reach certain levels.



 5               Unfortunately,  I didn't make an overhead of the



 6    comparative analysis.   Does everybody have a copy of this?



 7          This is action where we look at  the criteria that EPA




 8    is required to in order to evaluate the different




 9    alternatives.



10          Is everybody there?



11          As Diane pointed out,  in order for EPA to select an



12    alternative, first it has to be protective of human health



13    and the environment, and secondly,  it  needs to comply with



14    all of the laws and regulations,  because if it doesn't, we



15    have  to do a waiver, and we prefer not to do that.  We



16    prefer to comply with all of the laws  and regs.



17          Then we look at whether or not it reduces the toxicity



18    and mobility or volume  of the waste, which is EPA's



19    preference.   And some of these don't effect the  toxicity,



20    volume,  or the mobility.   Some do parts of it, some do all



21    of it.



22          And then we have to look at short-term effectiveness.



23    You know,  how does it affect the workers?  Can we control it



24    from  negatively affecting the workers?  How quickly can we



25    reach our clean up goals?  We look at  the implementability.
18:50:47





18:50:52





18:50:54





18:50:57





18:51:05





18:51:09





18:51:14





18:51:19





18:51:23





18:51:29





18:51:33





18:51:37





18:51:42





18:51:42





18:51:46





18:51:50





18:51:53





18:51:55





18:51:59





18:52:03





18:52:09





18:52:11





18:52:14





18:52:18





18:52:23

-------
14
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Is this a difficult technology to implement, or is it fairly
easily, you know, fairly easy to obtain. And we also look
at the cost.
And for some reason, I don't know if I ran out of
room on this table, we also look at the long-term
effectiveness, which is, you know, in the long term, you
know, how much is it going to cost us to keep looking at
this remedy. Or if we shipped everything off, we don't have
any costs.
And then the ranking is based on criteria. These
criteria and how the contractors are viewed, the
alternatives with respect to each of these criteria. You
can come up with your own method of ranking the criteria,
okay? This is somewhat subjective.
We've chosen alternative 5b for the source materials.
We feel like it provides the best balance of the nine
criteria.
It's a technology that's fairly common. It removes the
problem,. There is no monitoring requirements. And the cost
of it to physically go out there and remove everything is
about 7.4 million.
Okay.
AUDIENCE: The next closest to that is about two
million less?
MS. BROWN: Which one are you looking at?
18:52:31
18:52:34
18:52:38
18:52:39
18:52:43
18:52:45
18:52:46
18:52:52
18:52:55
18:52:57
18:53:04
18:53:09
18:53:12
18:53:16
18:53:22
18:53:27
18:53:32
18:53:32
18:53:37
18:53:43
18:53:48
18:53:54
18:53:55
18:53:58
18:54:00
      
-------
                                                                    15
  I               AUDIENCE:   5a,  6a,  and 6b.




  2               MS. BROWN:   Right.                                    16:54:07




  3               AUDIENCE:   So  all  four of them achieve  the goals?   18:54:07




  4               MS. BROWN:   Correct.                                  18:54:08




  5               AUDIENCE:   The  two  and a half million more to haul  18:54:08




  6    it  Off  Site?                                                    18:54:11




  7               MS. BROWN:   Correct.   So it gets into how            18:54:12




  8    important  is it to remove everything,  verses contain it on   _18:54:14




  9    Site.                                                            18:54:19




 10               AUDIENCE:  How much would the monitoring cost,    •'  18:54:21




 11    say, over  20 years?                                             18:54:24




 12               MS.  BROWN:  I think we  came  up with about  200,000.  18:54:24




 13               AUDIENCE:  So 20 years  of monitoring for 200,000?   18:54:27




 14                MS.  BROWN:  Right.                                   18:54:31




 15                AUDIENCE:  Two and a half million to haul  it  off?   18:54:31




 16                MS.  BROWN:   .Correct.                                 18:54:33




 I"7                You  have  some other problems,  and that's the  flood  18:54:33




 18     plain issue  and the wetland issue.   I didn't  mention this,    18:54:35




 19     but that whole site is in a 100-year flood  plain,  and most    ie:S.4:4i




 20     of these alternatives  are going to  involve  construction in a  18:54:43



 21     flood plain, which  the Corps  of Engineers and FEMA are not    18:54:47




 22     advocating any more at all.                                     18:54:55




 23               And actually, we had a lot of discussions  with      18:54:55




24     them about what we  would  have  to do on this site to meet the  18:54:57



25     requirements.                                                   18:55:04

-------
                                                                    16
  1               Anything we do out there is  going to have to  be



  2    flood  proof.   It's going to have to be built a foot above



  3    the base  flood elevation.




  4               We  also have the problem of  it  being a wetlands.



  5    We've  already contaminated a wetlands,  and  if we leave  it



  6    there  contaminated,  we're  going to have to  go off site  and



  7    create a  new  wetlands.



  8               And EPA has a preference for one,  not building in



  9    a flood plain.   It's actually a policy, on  building in  a



 10    wetland.




 11               MR.  TAYLOR:   I just want to add something to that.



 12               States  learned from other sites that  the soils in



 13    the area,  most of  west  Tennessee,  erodes very easily.   And



 14     caps,  anything above  grade,  which  is  basically  anything



 15     above ground surface  down there at  Ross Metals  is  going to



 16     erode.   There is a lot  of costs associated with that.



 17               And you can look at the  long-term cost to  the site



 18     and just say,  Well, look at  20  years or look at 30 years.



 19     If you  put that remedy  in place, it's  forever.  It's going



 20     to be there forever.  And any costs associated with



 21     maintaining that site, or monitoring that  site will be  there



 22     for eternity.   If you look at costs in  that  perspective, I



 23     think you  can  stand the extra cost on the  early phase.



24         We had a  similar site at Gallaway  that  was continually



25     eroded.  It was a stabilized site.   All  the  waste was
 18:55:04





 18:55:06





 18:55:12





 18:55:12





 18:55:14





 18:55:18





 18:55:21





 18:55:24





 18:55:27





 18:55:31





 18:55:35





 16:55:35





 18:55:43





 18:55:48





 18:55:51





 18:55:54





 18:55:56





 18:55:59





 18:56:04





 16:56:08





 18:56:10





18:56:11





18:56:16





18:56:19





18:56:23

-------
                                                                    17
  1    solidified,  stabilized, but  we  kept  having erosion problems.



  2    Just  couldn't deal with it.   It was  costing us 20 to $30,000



  3    a year  just  to keep the site accessible  and presentable



  4    where it  would keep the waste in the cap.   It just didn't —



  5    I didn't  feel like it was worth the  headache.   Potential



  6    failure.



  7               MS.  BROWN:  Okay.  ' And there's  a more in-depth



  8    analysis  in  the RI/FS.



  9         The  wetland alternatives,  again, we had to look at no



 10    action, for  comparison purposes.




 11         We also looked at capping.   Leaving the contaminated



 12    sediment  in  place,  capping over  it with clean  fill and



 13    creating  an  off-site wetlands.  And it's a  hard cost to come



 14     up with,  because  we'd have to work with the  Department  of



 15     Interior  to  come  up with what value they place  with  —  for



 16     that wetlands.  So  we did the best we could with costing it,



 17     but  you actually  don't know until you go into purchasing the



 18     property.



 19          And  lastly,  we looked at excavating all of the



 20     sediments, and  revegetating it,  and restoring it based  upon



 21     a  plan that  Fish  and Wildlife came up with.  And we looked



 22     at two options, both  of  which are good.   One is regrading



 23     with clean fill and then revegetating on  top of it, or



 24     regrading  it  with compost.



25         Are most of you  familiar with compost?
 18:56:26





 18:56:31





 18:56:34





 18:56:37





 18:56:40





 18:56:44





 18:56:48





 18:56:50





 18:57:07





 18:57:10





 18:57:13





 18:57:17





 1B:57:21





 18:57:26





 18:57:29





 18:57:33





 18:57:39





 18:57:41





 18:57:43





 18:57:47





 18:57:51





 18:57:56





 18:57:59





18:58:03





18:58:06

-------
                                                                     18
   1




   2




   3




   4




   5




   6



   7




   8




   9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
            AUDIENCE:  I know  what compost is,  and it was on



  the back sheet of terminology,  but there was  no  explanation



  for clean fill.  So my question is —



            MS. BROWN:  Clean  fill is just dirt.



            AUDIENCE:  Just dirt.   So compost seems  the most



  desirable of the two then?



            MS. BROWN:  Right.



            AUDIENCE:   Correct?



            MS. BROWN:  Mm-hmm.



            AUDIENCE:   All  right.




            MS.  BROWN:  There's different  kinds of compost,



 which you  may be  interested in as a citizen,  because



 different  kinds of  compost  may have more  smells than others.



           We  haven't specified at this point  what type of



 compost we want,  whether  we  want it to be wood ash, whether



 we want it to be  sludge from the treatment ponds  next door,



 that are very organic rich and provide a very  healthy



 habitat for growing  the grasses and different  types of



 vegetation.




           AUDIENCE:   This definition on the glossary thing



back here on the back of this  sheet that  came out said wood



ash   compost or waste water treatment  plant sludge.



           Is that — so we're, at  this point,  optional  on



which type  —




          MS.  BROWN:   Right.
  18:58:09.





  18:58:11





  18:58:17





  18:58:21





  16:58:22





  18:58:27





  18:58:29





 18:58:29





 18:58:31





 18:58:31





 18:58:33





 18:58:35





 18:58:38





 18:58:43





 18:58:46





 18:58:49





 18:58:54





 18:58:58





 18:59:01





 18:59:02





 18:59:06





 18:59:11





 18:59:14





18:59:17





18:59:18

-------
                                                                    19
  1               AUDIENCE:  — of compost,  but it would be compost?



  2               MS.  BROWN:  Right.   If that's something you would



  3    like to comment on,  there is some  information available on



  4    the internet.




  5               AUDIENCE:   I have no comment 'other than that I'm



 '. 6    pleased that biosolids was better  than clean fill.



  7               MS.  BROWN:  Right.  Yeah.  And it would be very



  8    nice if we could just use the sludge from next door.   It



  9    would be much  cheaper.




 10              AUDIENCE:   The only problem  (inaudible)  —



 11              MS.  BROWN:  You're right.  You're absolutely



 12    right.



 13              AUDIENCE:   What was the statement?



 14              MS.  BROWN:  He said the odor  would  be a  problem.



 15              MS.  TUCKER:   Obnoxious.



 16              MS.  BROWN:   And again,  I did  not  make an overhead



 17     of the  evaluation of the wetland cleanup alternatives.



 18          The only  one, obviously,  that doesn't meet protection



 19     of the  environment is  the no action alternative.   In  both W,



 20     alternative two and  three, they both reduce —  I'm sorry,



 21     they both  reduce the mobility,  but  alternative  two does not



 22     reduce  the toxicity, or  volume,  because we're leaving it on



 23     site.




 24          So we're looking  at,  alternative  two and three,  at



25     costs of both about  half  a million,  and we choose
 18:59:16





 18:59:20





 18:59:24





 18:59:27





 18:55:30





 18:59:32





 18:55:37





 18:59:39





 18:59:43





 18:55:46





 18:55:49





 18:59:51











 18:59:53











 19:00:01





 19:00:05





 19:00:13





 19:00:17





 19:00:24





 19:00:29





 19:00:37





 19:00:37





19:00:41





19:00:42

-------
20
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
alternative 3b.
So we're looking at a grand total cost of about 7.7
million, and monitoring costs of about 240.
AUDIENCE: Is that over the cost to date?
MS. BROWN: Are you talking about present worth
cost?
AUDIENCE: No, the costs that have been incurred
to date?
MS. BROWN: No. No.
Oh, yes, you're right, this is in addition to what
we've already spent.
AUDIENCE: And it doesn't cover the groundwater?
MS. BROWN: Correct.
AUDIENCE: And it's not the grand total? The
ground water is still out of picture?
MS. BROWN: Right. I think, if we actually have
to do ground water cleanup, the highest cost we've seen
would be about half a million. We think that if we have to
clean up ground water there may be some more innovative type
technology that we should take a look at rather than the
traditional pump-and-treat . Ground water pump and treat.
AUDIENCE: Do you have a ballpark of what the
costs have been incurred to date?
MS. BROWN: No.
AUDIENCE: Ballpark?
19:00:46
19:00:53
19:00:58
19:01:04
19:01:08
19:01:09
19:01:11
19:01:11
19:01:13
19:01:14
19:01:16
19:01:18
19:01:20
19:01:20
19:01:23
19:01:25
19:01:25
19:01:29
19:01:33
19:01:36
19:01:39
19:01:43
19:01:46
19:01:47
19:01:49

-------
                                                                     21
   1
   2
   3
   4
   5
   6
   7
   8
   9
 10
 11
 12
 13
 14
 15
 16
 17
 18
 19
 20
 21
 22
 23
24
25
            MS.  BROWN:  I'm sorry, no.  Do you  guys  have any
  idea?
            MS.  TUCKER:   Total costs incurred?
            AUDIENCE:   Costs incurred to date?
            MS.  TUCKER:   At the site?
            MS.  BROWN:   For the —
       See,  we've done the  removal and the investigation of  —
            MS. TUCKER:   I  think in the region of 1.4, I
 think.
            AUDIENCE:  What was  that  figure  on the estimates
 of ground  water,  if indeed you  think  it  might need some
 treatment?
            MS.  BROWN:   Pump and  treat we  looked at  numbers of
 about half a  million.
      All of the information on  the ground water that we  have
 to date is still in the RIFS.  We've just chosen at  this
 point to break  it off,  and we're going to collect more data.
 So the numbers  are  all  in  the RIFS.
           That brings up another point I  wanted to make.
 We've actually, as  of this week, been able  to put the RI  —
 well,  the RIFS, on  the  internet.  So I have a web address,
most  everything in  volume  one  is available.   We're working
on volume two.  It  also has the  proposed  plan on there.
          Why  don't I go ahead and give you  guys that
internet  address.
  19:01:5C

  19:01:52

  19:01:53

  19:01:54

  19:01:57

  19:01:57

  19:01:57

  19:01:55

  19:02:01

  19:02:05

  19:02:08

 19:02:13

 19:02:14

 19:02:14

 19:02:16

 19:02:18

 19:02:23

 19:02:28

 19:02:30

 19:02:31

 19:02:37

 19:02:41

 19:02:44

 19:02:51

19:02:53

-------
                                                                    22
  1          And I did not come up with this  address.



  2               We're still working on volume one.  There may be



  3     some figures or tables that still aren't available.



  4               Okay,  this is still one and this is — I'm not



  5    misspelling this,  it is under Ross M-E-T-L.



  6               MR.  TAYLOR:   Beth,  you might  want  to make those



  7    dots  a  little  bigger so people won't  ...



  8               MS.  BROWN:   Okay.   Diane went  over this so, just



  9    to reemphasize the importance of your role,  here in the  next



 10    30 days  you have an opportunity either —  actually in this



 11    meeting  as  well, I will respond to your  verbal comments  in



 12    this document  called the responsiveness  summary.   I'll also



 13    respond  to  any written comments.   We haven't talked about



 14     this, but you  can  request  an  extension as  long as it's done



 15     in a timely manner, and that  would give  you  an additional 30



 16     days.




 17          AUDIENCE:  That's  30  days  from the end  of —



 18               MS. BROWN:   December  1 through January  18th.



 19          Okay.  After  the comment period  is over,  I write  a



 20     formal document that's  called a record of decision.   It's



 21     actually about 40 pages or so long.   It will also include



 22     the  responsiveness summary, which I hope won't be bigger



23     than  the record of decision.



24          Then the next  step is we will notice —  PRPs is an



25     acronym  for potentially responsible parties.
 15:03:03





 19:03:15





 19:03:16





 19:03:30





 19:03:45





 19:03:55





 19:03:56





 .19:04:16





 19:04:15





 15:04:24





 15:04:25





 19:04:33





 19:04:36





 19:04:40





 19:04:46





 19:04:48





 19:04:52





 19:04:56





 19:05:01
   '.




 19:05:10





 19:05:13





 19:05:16





 19:05:20





19:05:22





19:05:27

-------
23
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Although Ross Metals owned the property, they did
business with a lot of folks, and we noticed them back in
the spring to let them know that we have their names, that
they may be potentially responsible for the contamination at
the Ross Metals site. So they are aware that we are about
to write a record of decision.
Once that's written up we'll send an official
notice letter to them and begin an official investigation.
Those typically run from three to six months, at
which point they will either decide not do the cleanup, or '
they will do the cleanup, with EPA's oversight, and we'll
sign a document, an official document, and EPA will be very
involved with the project even though the PRPs will actually
be spending their money to do the cleanup.
So — yeah?
AUDIENCE: I may not be remembering this
correctly, but it was my understanding this was being done
last time we met, six months ago.
MS. BROWN: Right. You're absolutely right. We
had noticed them back in the spring, which is actually when
we met .
Actually, the day we met with you was the day we
met with the responsible parties. They have actually been
waiting on EPA to write this record of decision. And once
we've done that, which will be in December, that is our
19:05:30
19:05:32
19:05:35
19:05:40
19:05:43
19:05:47
19:05:50
19:05:52
19:05:58
19:06:01
19:06:07
19:06:11
19:06:16 •
19:06:18
19:06:21
19:06:22
19:06:26
19:06:29
19:06:34
19:06:37
19:06:37
19:06:39
19:06:41
19:06:45
19:06:47

-------
                                                                     24
   1



   2



   3




   4



   5



   6



   7 j



   8



   9




 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



 24



25
  legal — that's a — legally  we can now notice  them to do



  the cleanup.




            MS. TUCKER:  This is  all  done through  the regs and



  statute.   We can't notice them  without having done  the



  remedy,  selecting a remedy to clean up the site.




            AUDIENCE:   It was my  understanding that was  what



  we  were doing last time.   And it was my understanding  — as



  a matter  of  fact  I recall well,  on  the subject,  which  would



  be  60 days from now  we're going to  do  this and we'll do



  that.




           MS.  BROWN:  Right.




           AUDIENCE:  Obviously that hasn't happened.  This



 is still going on.  How do we  know if it really  goes on?



 How can we check on —




           MS. BROWN:  You're absolutely right.   When I  met



 with you in the spring I said  in July we will have a record



 of  decision.   And  at that point  I had a remedial



 investigation feasibility study, and it went through a  peer



 review.  And  one of the  ground water hydrologists found



 problems with our  ground water .data.  And so for the  next



 couple of  months we were trying to figure out whether or  not



we could go ahead  and declare a pump and treat,  or a cleanup



technology for ground  water  or  not.   So  we  actually spent



several months  on  that issue.




          AUDIENCE:  Well, if we  run into something similar
  19:06:54





  19:07:00





  19:07:01





  19:07:04





  19:07:09





  19:07:12





  19:07:15





  19:07:17





  19:07:20





  19:07:22





  19:07:22





 19:07:22





 19:07:24





 19:07:27





 19:07:29





 19:07:31





 19:07:34





 19:07:38





 19:07:42





 19:07:48





 19:07:51





 19:07:52





 19:07:57





19:08:00





19:08:03

-------
   1




   2




   3




   4




   5




   6




  7




  8




  9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
                                                                    25
 to  that again, is there  any way we,  as the city and citizens



 in  general,  will be notified of that,  or is there anything



 we  can  do to help it along?




            MS.  BROWN:  I've  been negligent.   I should have



 sent you  guys  fact sheets when  I'm not meeting my schedule



 with you.




            AUDIENCE:   I didn't mean to  jump  on Beth.   I'm



 trying  to  find out how we can —




            MS.  BROWN:   I take responsibility.



            AUDIENCE:   — to make it work.




            MS.  BROWN:   Fortunately, at  this point  I can say



 with confidence,  the  record of decision will  be written by



 mid January.  And I would like it to be written in December.



 If no one  requests an  extension to the public  comment



 period,  I can write it  by December.   And then  really we'll



 notice  the PRPs in January.   But if  I have to wait until mid



 January, we're not going  to  notice the PRP's until mid



 January.




           AUDIENCE:  What  value  would it be  to us if we had



 an extension?   Is that just simply to  allow more people to



 comment?




           MS.  BROWN:   Right.   If you  don't feel like  you've



had adequate  time to review  the  documents, then you  should



request  an  extension.




          Now,  how it  will actually happen is,  when you
  19:08:05





  19:08:08





  19:08:11





  19:08:13





  19:08:15





  19:08:19





  19:08:19





  19:08:21





 19:08:23





 19:08:25





 19:08:26





 19:08:27





 19:08:32





 19:08:35





 19:08:38





 19:08:44





 19:06:49





 19:08:53





 19:08:54





 19:08:57





 19:09:00





 19:09:00





19:09:03





19:09:08





19:09:11

-------
                                                                    26
       write your comments,  if you have  technical comments  that



       impact the decision that we've made.   Say someone, you know,



       writes some incredible,  you know,  dissertation on why we



       should have chosen capping verses  excavation and off-site



       treatment,  and they have a solid technological reason for



       it, we have to consider it.



                  AUDIENCE:   So assuming — you're going to  have to



  8    talk  layman to me.



  9               MS.  BROWN:   Sure.



 10              AUDIENCE:   My  understanding  is  that the PRPs  were



 11    notified that  they were  responsible.   What they are  now,  and



 12    waiting for, is the amount of money that  they are



 13    responsible for.   Is  that  correct?



 14              MS.  BROWN:   Partially.



 15              AUDIENCE:   Because  you  didn't tell  them — you



 16    simply told  them you're  responsible?



 17              MS.  BROWN:   Right.



 18              AUDIENCE:   But you  didn't tell them how much money



 19    they were going to have to  come up with?



 20              MS. BROWN:  We didn't tell them what  they  were



 21    going to have to do.  We just  said you're potentially



 22    responsible, and we'll notice  you  at a later  date  that



 23     here's what we want you to do.



24               So this  record of decision will say,  EPA has



25     selected,  you know, treatment  and  off-site disposal.   PRP's,
 19:09:12





 15:09:16





 19:09:21





 19:09:25





 19:09:30





 19:09:35





 19:09:39





 19:09:45





 19:09:46





 19:09:46





 19:09:<3





 19:09:51





 19:09:55





 19:10:00





 19:10:00





 19:10:00





 19:10:03





 19:10:03





 19:10:05





 19:10:05





 19:10:07





19:10:11





19:10:15





19:10:17





19:10:22

-------
                                                                     27
   1

   2

   3

   4

   5

   6

   7

   9

   9

 10

 11

 12

 13

 14

 15

 16

 17

 18

 19

 20

 21

 22

23

24

25
  you perform it.


            AUDIENCE:   All right.  Now, my question is — all

  right.  If  you —  if the public comment  period  is over by

  December the 18th, and you have a month  there until  the

  middle of January  to get this long, drawn-out,  epistle

  written,  then you  would notify these people in  mid January,

  and they now have  three to six months?  The three to six

  months bothers me because,  you know, I'm struggling here

  with a Tag group that  was  fussing  over why didn't we get
                                                          .•
  cancelled  in July,  and  August,  and  September,  and October,

  and  November,  and you  say  three  to  six months,  and I  don't

  understand why  three  to six months.

            MS. TUCKER:  That is statutorily required as  well.

 I mean, it says so  in the statute, you have 120  days  to

 negotiate.


           AUDIENCE:   If the negotiations period  would be,

 let's say I'm a PRP,  I negotiate with you how much of that

 millions of dollars I am willing or can spend?   Is that

 what we're negotiating?


           MS. TUCKER:    No.   I  think typically we're offering

 you  the opportunity to  do the  work,  and that's  the ultimate

 statement.   You  do the  work or we'll  do the work.

          MS.  BROWN:  But you're  actually  partially correct,

because  they'll  also be on the hook  for everything EPA has

spent to date, so  we have to negotiate that.
  19:10:27


  19:10:29


  19:10:31


  19:10:35


  19:10:37


  19:10:43


  19:10:48


  19:10:53


  19:10:57


  19:11:02


  19:11:05


 19:11:10


 19:11:14


 19:11:17
  9:11:22


  9:11:25


 19:11:29


 19:11:34


 19:11:37


 19:11:38


 19:11:44


 19:11:50


19:11:53


19:11:54

-------
                                                                    28
  1               Plus there's, in total,  I  think about  600  of  them,



  2    of which,  you know,  they all have  to coordinate, and we have



  3    to coordinate meetings with them.



  4               So a lot of — unfortunately,  a lot of it  becomes



  5    logistics  between a  large group of people.   And you  can



  6    imagine with,  you know, say 100 different people, they  have



  7    different  interests.



  8               AUDIENCE:   Can they ask  for an extension period  of



  9    more than  six months?



 10               MS.  BROWN:   That — yes, they  can.



 11               MS.  TUCKER:   They can, but it's gotten really



 12    difficult  to  grant extensions.   We try to stick to the



 13    schedule of  120 days.   And we have to have  a  good reason.



 14              MR.  TAYLOR:   They ask for it,  but we  don't have  to



 15    say yes.




 16              AUDIENCE:   But  in my  public comment sheet  that I



 17    have  here,  then one of  my public comments could be that no



 18     extension be given to these PRPs.   Is that  correct?



 19               MS. BROWN:  Sure.



 20               AUDIENCE:   I  mean,  I  assume I can say,anything I



 21     want  to,  but ...




22               MS. TUCKER:   You're entitled to.



23              AUDIENCE:   And  I won't  have a problem with that.



24              However, you  know, if we  give  them an  extension



25     of, in  addition to six months more  then  we are  looking  at
 19:11:58





 19:11:59





 19:12:03





 19:12:06





 19:12:09





 19:12:13





 19:12:16





 19:12:17





 19:12:20





 19:12:23





 19:12:25





 19:12:27





 19:12:31





 19:12:37





 19:12:40





 19:12:41





 19:12:43





 19:12:45





 19:12:50





 19:12:51





 19:12:54





 19:12:56





19:12:57





19:13:00





19:13:02

-------
                                                                     29
   1
   2
   3
   4
   5
   6
   7
   8
   9
 10
 11
 12
 13
 14
 15
 16
 17
 18
 19
 20
 21
 22
 23
24
25
  beyond the year  2000,  and personally I've waited  15 years,
  and I'm not willing  to wait another bunch.
            MS. TUCKER:   Well,  we'll take that into
  consideration then.  This has been taking long, and we
  really wouldn't want an extension to further delay  the
  project.
            AUDIENCE:  Because  at this point,  now, I  see here
  it  says actual field work,  September 1999,  but what Beth
  said was  2000.
            MS.  BROWN:   Oh,  Diane did.
            MS.  BARRETT:   I was anticipating  —
            MS.  BROWN:   This is optomistic.  And  I came up
 with four  months  of negotiations,  and then a period of about
 four months for designing  the actual cleanup.
           AUDIENCE:   I  thought the cleanup was  designed.
           MS. BROWN:  No,  the basic — let me explain that
 part.
      From the remedial  investigation feasibility study,
 that's  all the information we've collected to date.
     And now,  say we had chosen to cap.   Well,  you can't
 just go out there and build  a  cap.   We don't  have plans for
 exactly how they should  build  it.   You know,  how much, how
high.   These are conceptual diagrams  that  I've  put in there,
but  they're not engineering specifications.
          AUDIENCE:   I guess my question is, why in the
  19:13:05

  19:13:09

  19:13:13

  19:13:14

  19:13:17

  19:13:21

  19:13:23

  19:13:24

  19:13:29

  19:13:32

 19:13:35

 19:13:37

 19:13:41

 19:13:44

 19:13:50

 19:13:52

 19:13:54

 19:13:55

 19:13:58
    *.
 19:14:01

 19:14:05

 19:14:12

 19:14:15

19:14:17

19:14:22

-------
30
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
world are we not just going ahead with figuring out what the
design will be, in December, January, and April? Why must
we wait for August if, in fact, you do go with these W-3b
and S-5b?
What's the reason for waiting until all of this
period of time has progressed before we go ahead with the
19:14:25
19:14:28
19:14:34
15:14:40
19:14:41
19:14:45
j
design process? ' 19:14:49
It seems to me you could go ahead with that at
this point if, in fact, these are the two options that are
selected, and at least move the thing along by a few months.
MS. BROWN: That is an excellent question.
Unfortunately, I don't think you're going to like the
answer.
AUDIENCE: Oh, well all right, give it to me and
let me grump about that in my comments.
MS. BROWN: EPA has a preference for not spending
the superfund money, the EPA money. We have a preference
for the PRPs to spend their money.
*
So we have to — I don't know if it's statutorily
required.
MS. TUCKER: We have to do. We have to offer them
the opportunity to do the work.
MS. BROWN: I believe it's a policy, though, isn't
it?
So once you identified these group of people,
19:14:49
19:14:53
'19:14:56
19:15:01
19:15:03
19:15:06
19:15:07
19:15:09
19:15:12
19:15:16
19:15:20
19:15:22
19:15:24
19:15:26
19:15:28
19:15:31
19:15:31
19:15:33

-------
  1




  2




  3




  4




  5




  6



  7




  8




  9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
                                                                    31
 which  we  now have, by  law we are required to give them  the    1S:15:37




 opportunity.  So you can't  —                                19:15:39




            AUDIENCE:  So what you're saying is —




            MS.  BROWN:   Until  we let them  —                   19:15:42




            AUDIENCE:  That  these PRPs could essentially  do     19:15:44




 the work,  or have the  work done on this site themselves, and  19:15:50




 the EPA would  merely monitor what  they do?                    19:15:52




            MS.  BROWN:    Right.                                   19:15:56




            AUDIENCE:  As opposed to the EPAs selecting people  19=15:58




 tO do the  Work?                                                -19:16:00




            MS.  BROWN:   Right.   But  everything that  PRP does    19:16:01




 is subject to  EPA approval.   If  they  select  a contractor,  I   19:16:03




 have to approve  it.   If they  submit a  plan,  I have  to         19:16:08




 approve it.                                                     19:16:11




           If they're  out  here doing field  work, there's  an    19:16:11




 EPA representative  on  site most of the time.                   19:16:16




           AUDIENCE:  All  right.  So is that the real  big      19:16:17




 advantage  of having a TAG  coordinator there?   Is that the    19:16:21



 big advantage?                                                  19:16:2"?




           MS. BROWN:  Can  you ask me one more time?   I'm not   19:16:28



 sure  I  understood.                                              19:16:31




           AUDIENCE:  If the PRPs do the work?                  19:16:31




           MS. BROWN:  Mm-hmm.                                  19:16:33




           AUDIENCE:  Let's  assume that.  And the CAG group    19:16:39



gets a TAG grant?                                              19:16:39

-------
                                                                      32
   1
   2
   3
   4
   5
   6
   7
   8
   9
  10
  11
  12
  13
  14
 15
 16
 17
 18
 19
 20
 21
 22
 23
24
25
             MS.  BROWN:   Okay.
             AUDIENCE:   Then is that essentially the biggest
  advantage  of having the  TAG  grant, and having that TAG
  person on  site to see  that it's monitored?
            MS. BROWN:   It's certainly additional oversight.
            AUDIENCE:  But  you  have EPA do all  of that?
            MS.  BROWN:  Right.
            AUDIENCE:   And  you  may want to explain what the
  TAG grant is.   Some of the people may not know.
            MS.  BROWN:   I'm going  to let Diane answer  that
  one.
            MS.  BARNETT:  A TAG grant is  one  that  is offered
 to a community, a work community, and  each  superfund  site.
 The site  is on the national priorities  list,  so it does
 apply.  It  is applicable  for  a group to request to receive a
 TAG grant.
           A TAG grant is,  $50,000,  and that's like -- it's
 put into an account for the group,  and then they would
 select a consultant that would work with the group to go
 over all of the documents, explain the documents  to it,  and
 submit  comments to EPA.
           And as the  work  is done,  then monies will be drawn
down from  the account to pay the accountant  — or  the
consultant,  excuse me.
           Also, in a TAG grant, the group  would put in like,
  19:16:41

  19:16:42

  19:16:45

  19:16:47

  19:16:53

  19:17:00

  19:17:03

  19:17:03

  19:17:04

  19:17:07

  19:17:11

  19:17:11

 19:17:14

 19:17:17

 19:17:21

 19:17:26

 19:17:26

 19:17:31

 19:17:34

 19:17:40

 19:17:43

 19:17:45

 19:17:48

19:17:53

19:17:54

-------
33
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
I think it's been reduced down to about 10 to 15 percent
in-kind services, whereas like if you had an accountant that
would want to take care of the records, voluntarily, then
that would be in-kind service. So what the process, if you
are interested in that, you can submit a letter of intent to
the EPA.
AUDIENCE: I've already done that.
MS. BARNETT: Well, if Cindy has it, then she's
got that in process.
MS. BROWN: Any other questions?
Please feel free, because this is an important
meeting for you guys.
AUDIENCE: If you say that you're going to give
the PRPs the opportunity to clean this up. What's the
recourse if they don't do it?
MS. BROWN: Well, I'll let Marlene address that
one .
MS. TUCKER: If they refuse to do the work, EPA
Superfund's money will be used to do the work. Then, after
spending our funds, we will sue them for reimbursement of
all of the cost.
MS. BROWN: Three times? Not three times?
MS. TUCKER: Another option that we have — thanks
for reminding me.
We can issue a UAL, which is a Unilateral
19:18:01
19:18:03
19:18:07
19:18:10
19:18:16
19:18:18
19:18:20
19:18:23
19:18:26
19:18:28
19:18:29
19:18:31
19:18:32
19:18:34
19:18:38
19:18:40
19:18:42
19:18:42
19:18:50
19:18:57
19:19:01
19:19:02
19:19:06
19:19:09
19:19:09

-------
   1



   2



   3



   4



   5



   6



   7



   8



   9



 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



 24



25
  Administrative Order to order  them to do the work.   That's



  another option.




            MS. BROWN:  We can ask them to do it.   They may



  agree,  if we sign a certain kind of document.  And  if they



  don't agree to it we can actually order them to do  it.   And



  then  if they still don't comply  with this order,  we  can



  actually sue them for three times  the cost of our cleanup.



  So  in this  case it would be,  you  know,  $22 million.




           MS.  TUCKER:   We actually  have two other options.



 We  can  do .the  work ourselves,  then  sue  them later, or we can



 issue an order to  force  them  to do  it.




           AUDIENCE:  Up  to  this point it  seems  like we're



 spending a mighty  lot of  time  giving them the opportunity to



 clean it up.   I don't understand why they might  want to



 consider it.




           MS. BROWN:  In fairness to this group of



 potentially responsible parties,  most of them, the first



 time they even heard about the  site was in the spring of



 this year.




           AUDIENCE:  I doubt that.




           AUDIENCE:  Has the delay  until now been a result



of PRPs  activities?




          MS. BROWN:   I  still  don't  understand.




          AUDIENCE:   Has  the delay from  June until now been



the responsibility  of the  PRPs?
  19:19:17





  19:19:17





  19:19:22





  19:19:24





  19:19:26





  19:19:30





  19:19:33





  19:19:41





  19:19:43





  19:19:46





  19:19:46





 19:19:53





 19:19:56





 19:19:56





 19:19:58





 19:19:59





 19:20:02





 19:20:05





 19:20:07





 19:20:09





 19:20:11





 19:20:15





 19:20:18





19:20:18

-------
                                                                    35
  1




  2




  3




  4




  5




  6




  7




  8




  9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
            MS.  BROWN:  No.  It's been  EPA's  responsibility.



 The PRPs  actually have been waiting for  this  date and to be



 notified  to  do the cleanup.




            MR.  TAYLOR:   In fact, to the PRPs credit,  they



 have been  doing what we've asked them to do so  far.   That




 is, organizing themselves in a group, and getting ready for



 this next  notice letter which they know they're going to be



 getting.




            You  know,  if we had — if each of you were  a  PRP,



 it would take  a  while  for all of you to come together to



 agree on how to  do  something.   We noticed 128 of  them.   So




 it naturally takes  them a while to organize the group.



           They have  done that,  and I think they're pretty



 much ready for this  letter to come.   That is called the



 special notice letter.   It starts  the  negotiations for the



 actual  cleanup.




           MS. BROWN:  And some  of  these  folks  are  folks that



 sent  their batteries to  Ross Metals.   They  were  battery



 recyclers.   Some of it was waste from  their  plants that they



 sent to Ross  Metals to recover  the lead.




     AUDIENCE:   All these possibilities that they  had at—



 I don't know  a  better word other than  stalling.




           In  other words, they  could refuse  to do  the.work,



they could  be cited and all of  those different things.



Those are very  time-consuming things,  as  I understand it.
 19:20:22





 19:20:24





 19:20:28





 19:20:31





 19:20:33





 19:20:37





 19:20:39





 19:20:44





 19:20:44





 19:20:47





 19:20:52





 19:20:56





 19:21:01





 19:21:01





 19:21:06





 19:21:10





 19:21:11





 19:21:13





 19:21:18





 19:21:21





 19:21:26





 19:21:30





 19:21:33





19:21:39





19:21:39

-------
                                                                      36
    1
    2
    3
    4
    5
    6
    7
    8
    9
   10
   11
   12
   13
   14
   15
   16
   17
  18
  19
  20
  21
  22
  23
  24
5 25
            MS. BROWN:  You're  absolutely correct.
            THE WITNESS:  I'm still  back on the 2000  problem.
            MS. TUCKER:  I just wanted to add, if we  issue a
  unilateral administrative order, it's effective in  30  days.
            AUDIENCE:  So if you tell  them they must  clean
  up  —
            MS. TUCKER:  That alternative won't create any
  delay.   In fact,  it would expedite it.
            MS. BROWN:   Realistically,  I  mean,  you're right.
  If they  enter in  negotiationss with us,  but  they don't have
 any intentions of doing  a  cleanup,  but  they're  just, you
 know, requesting  an extension.   You know, we  have  to
 evaluate their requests  —
           MS. TUCKER:  — in good faith?
           MS. BROWN:  — requesting this extension in good
 faith?  Are they really interested  in doing the work?
           At some point during this three to four  months
 we're going to have to decide,  and  if we don't think they're
 acting in good faith,  or we don't think maybe they are
 acting in good faith but they can't come together,  we'll
 issue  an  order and then that really starts  the clock
 ticking,  because  if they don't  comply  with  it within 30
 days,  EPA can  hire a contractor to begin the  design.
          AUDIENCE:  Whatever happened to the  actual owners
that made the  mess?
  19:21:43

  19:21:45

  19:21:47

  19:21:52

  19:21:54

  19:21:56

  19:21:56

  19:21:58

  19:22:03

  19:22:03

 19:22:08

 19:22:10

 19:22:14

 19:22:16

 19:22:18

 19:22:19

 19:22:21

 19:22:25

 19:22:29

 19:22:31

 19:22:35

 19:22:39

 19:22:41

 19:22:46

19:22:48

-------
                                                                     37
   1




   2




   3




   4




   5




   6



   7




   8




   9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




23




24




25
            MS. BROWN:   There's rumors, but  I  don't  know



 anything for sure.




            MR. TAYLOR:  Well,  Malcolm Ross  is  —  the  owner,



 is dead.   His son —




            MS. TUCKER:  His  son I have spoken  to, and I  can




 contact  him.   I don't have  an address for him, but he has




 called the 1-800 number and has  spoken to me  about




 background of the ownership.




            There is David Johnson,  who appears to be  a major




 player as  far as past owners.  He  has not been forthright in




 his involvement,  so he is someone  what we'll end up  deposing




 so we can  get on record the truth  and have a document that



 we can use  in a  court situation.




           AUDIENCE:   (Inaudible) —  don't have any assets?




           MS.  TUCKER:   As far as I know.   You know,  that's




 something that,  you  know,  I think we  will eventually find



 out more  about.




           AUDIENCE:   Is David Johnson the son  that  you're



 referring to?




           MS.  BROWN:  No,  Steve Ross.  Steve Ross is  the



 son,




           David Johnson,  I  think was the  president of the




company for a  while.  When Malcolm Ross stepped out of the




picture,  David Johnson and Steve  ran the  company.




          AUDIENCE:  I heard at one time,  I thought maybe
  19:22:49





  19:22:51





  19:22:55





  19:22:58





  19:22:59





  19:23:04





 19:23:07





 19:23:12





 19:23:14





 19:23:19





 19:23:27





 19:23:34





 19:23:38





 19:23:43





 19:23:46





 19:23:49





 19:23:52





 19:23:57





 19:23:57





 19:23:59





 19:24:00





 19:24:01





 19:24:05





 19:24:14





19:24:17

-------
                                                                     38
   1




   2




   3




   4




   5




   6



   7




   8




   9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
  somebody in the family had gone  to Mexico and maybe set up



  an operation.




            MS. BROWN:  Yeah, we've  heard they set  up an



  operation.   Actually they were operating in Mexico;   And do



  you have any information?




           AUDIENCE:   They ran a  joint  project with  another



  company in  Mexico.




           MS.  BROWN:   And they cracked open the batteries  in



 Mexico.  Again,  this  is  — I've only heard this.  They



 cracked open  the batteries in Mexico,  and  sent  them to



 Galviston where  they  then reclaim the  lead.




           AUDIENCE:   In answering your question  about



 whether  they have money,  we're still looking?




           MS. TUCKER:  Right.   It's hard to tell at  this



 point, but it's going to  take  deposing these parties and



 swearing them under oath.




           AUDIENCE:   There's nothing to hook them  on.   If



 there's anything to hook them  on, we will,  but if  there's



 nothing to hook,  what can we do?




           MS.  TUCKER:   In the meantime,  we  have  128 major



 parties that we can  get and try to get  them to do the work.



          And they also,  these parties,  once they sign on to



agree  to do  the work,  they have a cause of  action against



the owners if they have assets.  So we'll just  have to see



how it plays out.
  19:24:21





  19:24:25





  19:24:26





  19:24:28





  19:24:31





  19:24:32





  19:24:36





  19:24:39





  19:24:42





 '19:24:44





 19:24:48





 19:24:52





 19:24:55





 19:25:00





 19:25:00





 19:25:03





 19:25:04





 19:25:09





 19:25:12





 19:25:15





 19:25:18





 19:25:20





 19:25:26





 19:25:29





19:25:35

-------
39
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
But for now we are more interested in getting to
the parties that we have, and know that they're doing things
and getting them to do the work. And we'll see who else
falls into that.
MS. BROWN: And it's a way of keeping you
informed. We can issue a fact sheet, you know, after the
negotiations are through to let you know who's signed on to
do the work, whether it's fallen to the early or whether
we —
Yes, sir?
AUDIENCE: As a matter of public comment, it seems
to me, the importance of the red tape is more important than
the need in our community. There's something wrong with our
system on this.
The people that have left the lead have all of the
opportunities to get out of it, and we have all - of the
opportunities to consume more lead.
The town is not big enough to do anything about it.
We've asked the federal government to help, and I can't tell
if the bigger pollutant is lead or red tape.
MS. BROWN: You know, I think most of us have been
working in the Superfund for a while, and I don't think
you'll hear any disagreements on our part.
AUDIENCE: I don't understand it. There's no
realistic question, in anybody's mind here, whether or not
19:25:35
15:25:38
19:25:42
19:25:44
19:25:45
19:25:47
19:25:50
19:25:54
19:25:57

19:25:58
19:26:02
19:26:07
19:26:11
19:26:14
19:26:17
19:26:19
19:26:26
19:26:26
19:26:29
19:26:32
19:26:35
19:26:37
19:26:42
19:26:46

-------
                                                               40
   you're going to be able to collect any money from these
   people.   It won't happen.   But still we go through this
   dance, while we live here  with the lead,  and pay taxes  to
   support  the Superfund.
             MS.  BROWN:  Yeah.   You're right.
             I guess  the only good news I  have  for you is  that
  there are  no current risks to human health at the site.
             There are, however,  acute risks to the bio,  the
  bugs and the bunnies.  We're  taking action based on  the
  future risks, if someone should come  into contact with the
  waste or the soils, and the acute risks and chronic risks to
  the  bugs  and bunnies.
            AUDIENCE:  Because  we're looking at another  year

            MS. BROWN:   Yes,  ma'am.
            AUDIENCE:   —before anything  happens, and it
 makes me angry that there is all this time consumed in
 giving these  people an opportunity  to delay it,  and  you know
 darn good and well if you were  one  of  these PRPs,  you  would
 delay as long as possible,  whether or  not — you know,  it's
 a question of who we can get a hold  of.   And if  Mr. Ross  is
 not get-a-holdable,  then you'll go after the next fella down
 the line.
          And personally,  it's  going to  come  out  of my
pocket one  way or another, any  way you look at it.  YOU are
  19:26:50

  19:26:52

  19:26:55

  19:27:00

  19:27:03

  19:27:03

  19:27:06

  19:27:10

  19:27:14

  19:27:18

  15:27:21

  19:27:27

  19:27:28
 19:27:32

 19:27:32

 19:27:32

 19:27:39

 19:27:42

 19:27:46

 19:27:49

 19:27:54

 19:28:00

19:28:01

19:28:03

-------
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
not controlling the Superfund, you are controlling my pocket
book, and I'm ready to spend it.
MS. BROWN: Right.
AUDIENCE: And I resent the fact that these people
seem to have more rights than I do. And I — you know, this
is silly. I'm not joking.
Fifeen years is long enough, and you're telling me
now, that it ' s going to be another year and a couple of
months before the first possibility that you could actually
get your shovel in the dirt —
MS. BROWN: Right.
AUDIENCE: T-- is about to happen, and that's just
flat out unacceptable.
I mean, it is. It really is.
And I understand they have 30 days, they have 60
days, they have 120 days. They have been having 30, 60, and
120 days since last June.
MS. BROWN: I understand your point. I mean, I
guess that, again, EPA did take care of what we considered
the immediate risks.
AUDIENCE: And I appreciate that. In the last
meeting when we voiced all of the comments about the
dilapidated buildings and all of that, that you did come
right behind it and take care of that, and I do appreciate
that. Because I'm close enough to the site to be able to
19:28:07
19:28:11
19:28:13
19:28:15
19:28:17
19:28:20
19:28:23
19:28:25
19:28:29
19:23:34
19:28:37
19:28:37
19:28:39
19:28:42
19:28:42
19:28:44
19:28:50
19:28:52
19:28:55
19:28:58
19:29:00
19:29:02
19:29:06
19:29:07
19:29:13

-------
                                                                     42
   1




   2




   3




   4




   5




   6




   7




   8




   9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19




 20




 21




 22




 23




24




25
  look at it out my back  yard.




       However, I know darn  good and well that this little



  town is expanding.  We  have 100 and some odd houses  going up



  here.   We have a school here,  and  it's impossible for us,  as



  a  community,  to get more and more  people here if they know



  about  it.




            MS. BROWN:  Well, if is  an eye sore,  there is  no



  doubt.




            AUDIENCE:   The eye sore  is not the concern.  In



  other words,  not  all of these 100  and  so houses  know that  we



 have a  superfund  site less than four blocks  away from their



 houses.  If they  did,  they might not be  so anxious  to plop



 down $114,000 for a  house.




           MS.  BROWN:  We can help you out with that.   That's



 a matter of education.   Because you guys are all  aware of



 the carrier plant in Collierville?    That's a Superfund



 site,  and it  certainly hasn't impacted  Collierville1s



 growth.




           And every time that there is  a business that wants



 to  locate next to that site, they write a letter to EPA,  or



 make a phone call,  and I write a letter to them.   And it



 hasn't impacted their growth.




          So  it is possible to live next  to a Superfund



 site, and as long  as  we keep everyone informed and educated,



you know, you  can  survive the  economic,  you know,  growth or,
  19:29:15





  19:29:17





  19:29:22





  19:29:26





  19:29:26





  19:29:33





  19:29:35





  19:29:38





  19:29:38





  19:29:42





  19:29:43





 19:29:47





 19:29:51





 19:29:55





 19:29:58





 19:30:00





 19:30:04





 19:30:07





 19:30:07





 19:30:09





 19:30:13





 19:30:17





 19:30:17





19:30:21





19:30:25

-------
  1    you  know,  you can encourage  the growth.




  2               AUDIENCE:  You  say that  you have got it  contained




  3    in the  fact it's piled on the concrete slabs?




  4               MS.  BROWN:  Right.




  5        •       AUDIENCE:  And  it's covered with tarp?




  6               MS.  BROWN:  Temporarily,  yes.




  7               AUDIENCE:  What about all of that that's buried




  8    out under  the  ground under the  back?  There is no cap or no




  9    anything.   These many years  leads have been leaking out.




 10               MS.  BROWN:,  We took samples  above the slag, took




 11    samples of the slag, and took samples  below the slag.  It's




 12    not migrating  very fast.   We  anticipate that  it would take




 13    about 70 years for the lead in  that  slag to impact ground




 14    water.




 15              AUDIENCE:   Well, we've got 15 working on it.




 16              MS.  BROWN:   I  know.  Unfortunately,  folks,  I don't




 17     know  that  I —  I'm not going to have any answer for you




 18     tonight that's  going to make you more  comfortable  with the




 19     schedule at all.




 20               I mean,  I  understand.




 21               AUDIENCE:   How  come your late  is  September  '99




 22     date  for the actual  field work?  -Is that pretty firm?




 23               MS.  BROWN:   No.  That's optimistic.




 24               AUDIENCE:   Wow.




25               MS.  BROWN:   I think if you talk to a  lot  of
 19:30:25





 19:30:32





 19:30:35





 19:30:38





 19:30:40





 19:30:43





 19:30:44





 19:30:45





 19:30:48





 19:30:52





 19:30:56





 19:31:00





 19:31:07





 19:31:09





 19:31:12





 19:31:12





 19:31:16





 19:31:19





 19:3?.:21





 19:31:26





 19:31:34





19:31:34





19:31:34





19:31:40





19:31:45

-------
   1



   2



   3



   4



   5



   6



   7



   8



   9



 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



24



25
  communities that have lived near a  Superfund site,  probably



  the  biggest complaint we hear is about  how long it  takes us.



            It is the most common one  I hear.



            AUDIENCE:  The good point  is  that  things  are  in .



 motion.   Something is going to happen.   There is a  set



 schedule,  maximum is three,  four,  five  years down the road.



 It's going to  be cleaned up.



            MS.  BROWN:   Yes,  it is.




            AUDIENCE:   Beth,  is it all going to be off site?



            MS.  BROWN:   That's  EPA's preference.



            AUDIENCE:   Who makes the decision?



            MS.  BROWN:   I  do, with my management's approval.



            I'm  sure  I'm going  to  have to respond to comments,



 you know,  for  those that aren't  in  favor of  treating it on



 site and shipping it  off, but  we chose this  on  very firm



 ground.   We can back  it up.




           AUDIENCE:   You're going to dig it  out  of  the



 ground and haul it off?




           MS. BROWN:  As far as  I know.   I can't think  of



 any argument that anyone would have  that would make  EPA



 change their mind.  And if,  you know,  the long shot, that



 were  to happen  or information were to be,  you know,  to come



 available to EPA,  we'd have  to come to you again.




           AUDIENCE:   When you get through  with it we'll  be



able to use it  for anything  we want to?    Like a park or
 19:31:47




 19:31:50



 19:31:54



 i9:3i:5S



 19:32:04



 i5-.32-.os



 19:32:11



 19:32:12



 19:32:15



 19:32:18



 19:32:22



 19:32:22



 19:32:25



 19:32:2?



 19:32:31



 19:32:35



 19:32:40



 19:32:41



 19:32:44



 19:32:46



 19:32:51



 19:32:55



 19:32:59



 19:33:03



19:33:05

-------
       anything?




                  MS.  BROWN:  That's really going to depend  on



       whether  EPA does the clean  up,  or whether the PRPs do the



       clean up,  and who actually  will have control of the



       property.




                  My understanding  is there isn't a whole lot of



       interest  in that property ever  being industrial.  I  mean,



       it's in a  wetlands,  it's in a flood plain.




                  AUDIENCE:   The history of the property is  —. it



 10     used to be in  a park.




 11                MS.  BROWN:  Right.



 12                AUDIENCE:   The city is interested in taking up a



 13     study to see if it can be made  into a  park again.



 14           '   -  MS.  BROWN:  EPA would love that,  and we're, if we



 15     do it,  I think,  you  know, it  will  happen.   If the  PRPs do



 16     it,  we'll  work with  the community  and  encourage the PRPs to



 17     do that with the property.




 18               AUDIENCE:   Do you mean if  the  PRPs  do it  then  they



 19     will not necessarily have to do  it to  your  specifications?



 20     You  mean  —



 21               MS.  BROWN:  As far as what the future  use  of the



 22     property is?




 23               MR.  TAYLOR:   He's  talking about clean  up levels.



24               AUDIENCT:  From the answer that you gave me, that



25     if you do the job it would be done right.  If the PRPs do
 19:33:08





 19:33:11





 19:33:12





 19:33:15





 19:33:18





 19:33:18





 19:33:21





 19:33:25





 19:33:28





 19:33:32





 19:33:33





 19:33:33





 19:33:36





 19:33:38





 19:33:41





 19:33:45





 19:33:50





 19:33:51





 19:33:55





 19:33:58





 19:34:03





 19:34:03





19:34:03





19:34:09





19:34:09

-------
   1



   2



   3



   4



   5



   6



   7



   8



   9



 10



 11



 12



 13



 14



 15



 16



 17



 18



 19



 20



 21



 22



 23



 24



25
                                                                     46
 the  job,  it might be done right or  it may not be  done right.  19:34:05




            MS.  BROWN:  No, it will be  done right,  but  the      19:34:17




 difference is  who owns the property after the clean up.        19:34:17




 That  was  your  question, right?                                  19:34:17




            AUDIENCE:   Well, no.  I wanted to know  about  the    19:34:22




 Clean up.                                                        13:34:22




            MS.  BROWN:  Clean up is going  to be done right      19:34:22




 whether we do  it  or  the PRPs do it.                             19:34:26




            AUDIENCE:   I want to know,  according to you, other  19:34:26




 than  I would like to see it done correctly,  and whomever    "  19:34:29




 owns  it, the property could do with it whatever they want      19:34:31



 tO.                                                               19:34:34




           MS.  BROWN:   After it's cleaned up  —                 19:34:36




           AUDIENCE:   After it's cleaned up.                     19:34:38




           MS; BROWN:   Go  ahead.                                  19:34:38




           AUDIENCE:   First  of  all,  since I've  been so  ugly    19:34:40




 to you,  I  want  to tell you that  these  two options  are  the     19:34:42




 ones  I chose.   I read this eleventy-seven times.   Let's see   19:34:45



 her type that.                                                   19:34:50




           MS. BROWN:   How many typos did you find?            19:34:52




           AUDIENCE:  Well, being an  English teacher, I did    19:34:54




pretty well and didn't look for that.                           19:34:59




           But these options were the two  that I chose  before  19:35:00




I read the  back page  to see which ones you had chosen.   So    19:35:04




these  were,  without question, the two  better options.          19:35:09

-------
*



*
                                                                           47
 1          My surprise,  when we talked  before the meeting began,


 2    was  that if the PRPs clean this property up,  then


 3    essentially it does provide them  with ownership.


 4               MS.  BROWN:  Well, actually — not ownership.


 5    They're going to have to take  control of the property


 6    temporarily to do the cleanup.  But  then it's a matter of


 7    who  owes the back taxes, and all  of  that.   And I think that


 8    the  county is going to have to put it up for sale.


 9               AUDIENCE:  Okay, the city  and the CAG group, the


10    CAG  group has already gone on  record,  but  I want to make


11    sure that I make a statement tonight,  that the CAG group


12    choice  was that the property be turned over,  purchased by,


13    or whatever legal requirements were  necessary, by the City


14    of Rossville,  to be used as community property, the entire   |


15    tract of 7.5 acres.  And that  it  be  used — isn't that       j

                                                                     t
16    correct,  7.5?


17               MS.  BROWN:  You're talking about just the facility


18    record  and the backfill?


19               AUDIENCE:  Well, that plus the wetlands.


20               MS.  BROWN:  The landfill and the facility is about


21    eight,  and then the wetlands is about another eight.


22               MS.  BROWN:  Right.   Of  about a 242-acre parcel.


23               AUDIENCE:  Correct.  That  the entire tract of land


24    be turned over to the City of  Rossville to do with for


25    community property; parks, recreational areas, community
 19:35:12



 19:35:16



 19:35:20



 19:35:25



 19:35:28



 19:35:31



•19:35:35



 19:35:41



 19:35:44



 19:35:47



 19:35:49



 19:35:53



 19:35:57



 19:36:01



 19:36:05



 19:36:11



 19:36:14



 19:36:16



 19:36:17



 15:36:17



 19:36:23



 19:36:23



 19:36:26



 19:36:29



 19:36:32

-------
     1
     2
     3
     4
     5
     6
     7
     8
    9
   10
   11
   12
 ,  13
   14
   15
   16
   17
   18
   19
  20
  21
  22
  23
  24
1  25
  area.
            And that, you know,  that was our request  in the
  very back — or the very beginning of this.
            MS. BROWN:  And I think  that's a great  idea.   And
  maybe it's a matter of getting the county mayor —  is it
  still Jim Voss? — involved, because  I'm not sure how your
  local laws work with the —
            AUDIENCE:   When I talked to him he assured  me  if
  the property was available,  and the cost  of it was back
  taxes, that  the  city of Rossville  would have no difficulty
  in acquiring the property.
           MS. BROWN:   Would  they have to  bid against
 other —
           AUDIENCE:  According  to Mr.  Voss,  at  that  time,
 no.
           MS. BROWN:  We need to  look  into that.
           AUDIENCE:  Because of the back taxes, and  some
 legal  ramifications that were involved,  that the city  could
 basically assume it.
           MS. BROWN:   Hmm.   Let's get  it  cleaned up  first.
           AUDIENCE:  I do care who  owns it,  very much.
           MS.  BROWN:   For those of  you that  arrived late,
we're  not  trying  to heat — make you guys  hot,  but we  turned
the heat off  so we could actually hear each  other.
          AUDIENCE:   Who owns that property  now?
  19:36:38

  19:36:39

  19:36:41

  19:36:46

  19:36:49

  19:36:50

  19:36:54

  19:36:58

  19:37:00

  19:37:03

  19:37:06

  19:37:10

  19:37:12

  19:37:12

I  19:37:14

  19:37:16

 19:37:17

 19:37:20

 19:37:25
 19:37:27

 19:37:32

 19:37:36

 19:37:39

 19:37:41

 19:37:44
  I
0

-------
   i




   2




   3




   4




   5




   6




   7




   8




   9




 10




 11




 12




 13




 14




 15




 16




 17




 18




 19 I




 20




 21




 22




23




24




25
            MS.  BROWN:  It's — nobody.




            AUDIENCE:   Well, somebody.




            MS.  BROWN:  Back taxes are owed.




            AUDIENCE:   The company did?




            MS.  TUCKER:   The company still owns  it  as far as



  we know.




            AUDIENCE:   I  thought you said it was



  administratively dissolved.




            MS. TUCKER:   The corporation.  It doesn't mean



 that  they don't own  the  property.




            MS. BROWN:  I  mean,  I've  been told,  you know,  off




 the record,  that it's actually Greyhound that  owns it.




            AUDIENCE:  You mean  the bus?




            MS.  BROWN:   They're  a  financial  service that was



 interested in taking over the property.




            MS.  TUCKER:  I think they loaned  —




            MS.  BROWN:   In redeveloping it.




            MS.  TUCKER:  They loaned the money to David




 Johnson to purchase it from Malcolm, so somehow they have a




 financial  investment  in  the property.




           MS. BROWN:   All I know is the county  called  me




 about  two years ago wanting to  foreclose on it  for back




 taxes,  and decided not to because it was a Superfund site,




 and they  didn't know  that  this  — if they bought the




property  today they might  get a letter saying you have to
  19:37:46





  19:37:47





  19:37:49





  19:37:50





  19:37:52





  19:37:54





  19:37:56





  19:37:58





  19:38:00





 '19:38:02





 19:38:06





 19:38:09





 19:38:12





 19:38:14





 19:38:16





 19:38:21





 19:38:23





 19:38:25





 19:35:27





 19:38:31





 19:38:33





 19:38:36





 19:38:40





19:38:45





19:38:50

-------
                                                                    50
  1    clean it up.



  2               AUDIENCE:  So Greyhound  actually, on the  record



  3    book,  owns it at this point?



  4               MS.  BROWN:  I can't say  for sure.



  5               MR.  TAYLOR:  I think, on  the record book,  if  you



  6    went  up  to the courthouse,  I think  you would see Ross



  7    Metals,  Incorporated is the official  owner.



  8               But,  again, that  company  has been administratively



  9    dissolved,  and the taxes have not been paid,  and I think



 10    that's what you're referring to.



 11               AUDIENCE:   Is it  possible that  Greyhound have



 12    mortgage interests in the property?



 13               MS.  TUCKER:  I believe that  may be  the case, yeah.



 14                MS.  BROWN:   Greyhound actually  looked into



 15     cleaning it up  themselves a number of  years ago when we were



 16     doing the  removal,  and the  deal fell through.   EPA



 17     negotiated with them.




 18          Well, I tell  you what,  we'll  hang around here  if



 19     anybody, else would have  any questions they  have  for  us.



 20               So,  you  know,  as  far  as  the official meeting,



 21     thank you very much for  coming.'



 22               MS.  BARNETT:   One  quick  question.



23               MS.  BROWN:  Sure.



24               MS.  BARNETT:   Did everybody sign in?



25               And  the reason I ask this  is that if you did not
 19:38:5C





 19:38:52





 19:38:55





 19:38:57





 19:38:59





 19:39:00





 19:39:03











 19:39:12





 19:39:13





 19:39:16





 19:39:19





 19:39:22





 19:39:26





 19:39:29





 19:39:32





 19:39:36





 19:39:42





 19:39:45





 19:39:48





 19:39:50





 19:39:53











19:39:56





19:39:58

-------
 10

 11

 12

 13

 14

 15

 16

 17

 18

 19

 20

 21

 22

 23

 24

25
                                                                    51
       get mail,  and if you want to  receive information about the

       site  in  the future, be sure to  sign this so I can make sure

       you're on  the mail list to receive  it.

                  So I just want to make  sure you sign this.

                  That's all.

                  MS.  BROWN:   Thanks  again.

                                      (Whereupon,  the public meeting
                                       was  concluded at 7:40 p.m.)
19:39:59


19:40:03


19:40:06


19:40:09


19:40:12


15:40:13

-------
It*

-------
                   Reproduced by NTIS
          0)
«- ^ o  o
o c o  o
^r if- &.  o
E
    o>

    0 0)
   =  :«f-
3    u-I
• ••  ^T 1 J ^H
 EES°
 0  o o^
      .
  c * e
  3T5 C
  •&.««
  «- E'
«
                   National Technical Information Service
                   Springfield, VA 22161
                           This report was printed specifically for your order
                         from nearly 3 million titles available in our collection.
For economy and efficiency, NTIS does not maintain stock of its vast
collection of technical reports. Rather, most documents are printed for
each order. Documents that are not in electronic format are reproduced
from master archival copies and are the best possible reproductions
available.  If you have any questions concerning this document or any
order you have placed with NTIS, please call our Customer Service
Department at (703) 605-6050.

About NTIS
NTIS collects scientific, technical, engineering, and business related
information — then organizes, maintains, and disseminates that
information in a variety of formats — from microfiche to online services.
The NTIS collection of nearly 3 million titles includes reports describing
research conducted or sponsored by federal agencies and their
contractors; statistical and business information; U.S. military
publications; multimedia/training products; computer software and
electronic databases developed by federal agencies; training tools; and
technical reports prepared by research organizations worldwide.
Approximately 100,000 new titles are added and indexed into the NTIS
collection annually.
                      For more information about NTIS products and services, call NTIS
                      at 1-800-553-NTIS (6847) or (703) 605-6000 and request the free
                       NTIS Products Catalog, PR-827LPG, or visit the NTIS Web site
                                         http://www.ntis.gov.
                                               NTIS
                        Your indispensable resource for government-sponsored
                                   information—U.S. and worldwide

-------

-------