PB99-964505
                               EPA541-R99-045
                               1999
EPA Superfund
      Record of Decision:
      George Air Force Base OU3
      Victorville, CA
      10/5/1998

-------

-------
                                  SFUNO RECORDS CTR
                                    3058-00099


                                  SFUND RECORDS Ct
                                -< DM S# 48592
George Air Force Base,

California


Installation Restoration Program

Prepared for
Air Force Center for Environmental Excellence
Brooks Air Force Base, Texas

Contract F41624-92-D-8038

Final
Operable Unit 3 Record of Decision
November 1998
                       MONTGOMERY WATSON

-------

-------
   INSTALLATION RESTORATION PROGRAM
                   FINAL

           RECORD OF DECISION
             OPERABLE UNIT 3
   GEORGE AIR FORCE BASE, CALIFORNIA
                Prepared For:

U. S. Air Force Center for Environmental Excellence
            Brooks Air Force Base
        Contract No. F41624-92-D-8038
             Delivery Order 004
Montgomery Watson Project No. 1212009.04090074
                Prepared By:

            Montgomery Watson
        1340 Treat Boulevard, Suite 300
        Walnut Creek, California 94596

-------

-------
                             TABLE OF CONTENTS

Section                                                                    Page
1.0 DECLARATION     	1-1
    1.1    SITE NAME AND LOCATION	1-1
    1.2    STATEMENT OF BASIS AND PURPOSE	1-1
    1.3    ASSESSMENT OFTHE SITE	1-2
    1.4    DESCRIPTION OF THE SELECTED REMEDIES	1-2
    1.5    STATUTORY DETERMINATIONS	1-2
    1.6    APPROVED   	...	1-4

2.0 DECISION SUMMARY	2-1
    2.1    SITE NAME, LOCATION, AND DESCRIPTION	2-1
          2.1.1   Description of Operable Units	2-1
          2.1.2   Physical Characteristics of OU 3	2-3
    2.2    SITE HISTORY AND ENFORCEMENT ACnVITIES	2-12
          2.2.1   Base History	2-12
          2.2.2   OU 3 Site Investigations	2-13
    2.3    HIGHLIGHTS OF COMMUNITY PARTICIPATION	2-16
    2.4    SCOPE AND ROLE OF OPERABLE UNIT WITHIN THE SITE
          STRATEGY   	2-17
    2.5    LANDFILL SITE SUMMARY	2-18
          2.5.1   Summary of Landfill Site Characteristics and Risk Assessments	2-19
          2.5.2   Description of Landfill Site Alternatives	2-28
          2.5.3   Summary of Comparative Analysis of Alternatives for the
                Landfill Sites	2-33
          2.5.4   The Selected Remedies for the Landfill Sites	2-43
          2.5.5   Statutory Determinations for the Landfill Sites	2-50
    2.6    TPH/VOC SITE SUMMARY	2-51
          2.6.1   Summary of TPH/VOC Site Characteristics and Risk Assessments	2-52
          2.6.2   Description of TPH/VOC Site Alternatives	2-62
          2.6.3   Summary of Comparative Analysis of Alternatives for the
                TPH/VOC Sites	2-69
          2.6.4   The Selected Remedies for the TPH/VOC Sites	2-77
          2.6.5   Statutory Determinations for the TPH/VOC Sites	2-86
    2.7    SITE OT-69 SUMMARY	2-87
          2.7.1   Summary of Site OT-69 Characteristics and Risk Assessment	2-88
          2.7.2   Description of Site OT-69 Alternatives	2-91
          2.7.3   Summary of Comparative Analysis of Alternatives for Site OT-69	2-93
          2.7.4   The Selected Remedy for Site OT-69	2-100
          2.7.5   Statutory Determinations for Site OT-69	2-101
    2.8    DOCUMENTATION OF SIGNIFICANT CHANGES	2-103
    2.9    CURRENT SITE STATUS	2-103
          2.9.1   Landfill Sites	2-104
          2.9.2   TPH/VOC Sites	2-107

-------
                          TABLE OF CONTENTS
                                (Continued)

3.0 RESPONSIVENESS SUMMARY	3-1
    3.1   OVERVIEW	3-1
    3.2   BACKGROUND ON COMMUNITY INVOLVEMENT	3-1
    3.3   SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC
         COMMENT PERIOD	3-2

REFERENCES

FIGURES

TABLES

APPENDICES

A - Action Items to Meet ROD Requirements
B - Criteria for Active Site Remediation - Site OT-69
C - Administrative Record
D - Responses to Agency Comments to April 1997 Draft ROD
E - Responses to Agency Comments to November 1997 Draft Final ROD
F - Responses to Agency Comments to February 1998 Draft Final ROD
                                  11

-------
                                 LIST OF FIGURES
                       (Figures are located at the end of the text)
Figure
  No.
 1     Vicinity Map

 2     Operable Unit Site Locations

 3     Regional Physiography

 4     Major Hydrogeologic Features in the Mojave River Basin

 5     Approximate Locations of Known Municipal and Domestic Water-Supply Wells,
       GAFB Vicinity

 6     Operable Unit 3 Feasibility Study Site Locations

 7    Conceptual Diagram of Surface Controls/Rehabilitated Soil Cover, OU 3 Landfill
      Sites

 8     Conceptual Diagram of Capping Alternatives, OU 3 Landfill Sites

 9     Remediation Goals for Soils at the OU 3 TPH/VOC Sites

 10   Remediation Goals for TCE in Soils at Site FT-19c

 11    Schematic of SVE System Design

 12    Schematic Diagram of Soil Vapor Sampling From Monitoring Point

 13    Schematic of Bioventing System Design

 14    Site OT-69 Location Map
                                       in

-------
                                 LIST OF TABLES
                       (Tables are located at the end of the text,)
Table
  1    Recommended Remedial Alternatives for OU 3 Sites

 2    Summary of OU 3 Landfill Site Characterizations

 3    Summary of Detailed Analysis of Remedial Alternatives for OU 3 Landfill Sites

 4    ARARs for GAFB OU 3 Landfill Sites DP-03, DP-04, LF-12. LF-14, and the SEDA

 5    Summary of Preliminary Remedial Alternative Costs for OU 3 Landfill Sites

 6    Preliminary Cost Estimate for Site DP-03 Preferred Alternative

 7    Preliminary Cost Estimate for Site DP-04 Preferred Alternative

 8    Preliminary Cost Estimate for Site LF-12 Preferred Alternative

 9   Preliminary Cost Estimate for Site LF-14 Preferred Alternative

 10  Preliminary Cost Estimate for Site LF-44 Preferred Alternative

 11   Preliminary Cost Estimate for the SEDA Preferred Alternative

 12  Summary of Operable Unit 3 TPH/VOC Site Characterizations

 13   Numerical Cleanup Standards for TPH/VOC Ground water Sites

 14   Summary of Detailed Analysis of Remedial Alternatives for OU 3 TPH/VOC Sites

 15   ARARs for GAFB OU 3 TPH/VOC Sites WP-17, FT-19a, FT-19b, FT-19c. OT-51, and
     OT-69

 16   Summary of Remedial Alternative Costs for OU 3 TPH/VOC Sites

 17   Preliminary Cost Estimate for Site WP-17 Preferred Alternative

 18   Preliminary Cost Estimate for Site FT-19a Preferred Alternative

 19   Preliminary Cost Estimate for Site FT- I9c Preferred Alternative

20   Preliminary Cost Estimate for Site OT-51 Soils Preferred Alternative

21   Preliminary Cost Estimate for Site OT-51 Groundwater Preferred Alternative
                                       IV

-------
                                LIST OF TABLES
                                   (Continued)
Table
 No.
 22   Summary of Detailed Analysis of Remedial Alternatives for Site OT-69

 23   Summary of Remedial Alternative Costs for Site OT-69 Groundwater

 24   Preliminary Cost Estimate for Site OT-69 Preferred Alternative (G-2)

 25   Summary of Current Remedial Alternative Costs for OU 3 Sites with Accelerated Actions
      Performed

-------
                        ACRONYMS AND ABBREVIATIONS

AFBCA      Air Force Base Conversion Agency
AFCEE      Air Force Center for Environmental Excellence
ARAR       applicable or relevant and appropriate requirement
bgs          below ground surface
BTEX       benzene, toluene, ethylbenzene, and xylene
CDWR       California Department of Water Resources
CFR         Code of Federal Regulations
CERCLA     Comprehensive Environmental Response,"Compensation, and Liability Act
cfm          cubic feet per minute
cfs          cubic feet per second
COPC       compound of potential concern
COPEC      compound of potential ecological concern
CRP         Community Relations Plan
DCA         dichloroethane
DCE         dichloroethene
DHS         Department of Health Services
DTSC       Department of Toxic Substances Control
EM          electromagnetic terrain conductivity
ET          evapotranspiration
FFA         Federal Facilities Agreement
FML         flexible membrane liner
FS          Feasibility Study
FSRA       Full Service Remedial Action
ft/day        feet per day
ftVday       square feet per day
ft/ft          feet per foot
GAC         granular activated carbon
GAFB       George Air Force Base
gpd          gallons per day
gpm         gallons per minute
GPR         ground penetrating radar
HVOC       halogenated volatile organic compound
IRP          Installation Restoration Program
IT           International Technologies Corporation
JMM         James M. Montgomery Consulting Engineers, Inc.
LRA         Local Reuse Agency
LSA         LSA Associates, Inc.
LUFT       Leaking Underground Fuel Tank
M&E        Metcalf & Eddy, Inc.
MAG        magnetometry
MAP         Management Action Plan
MCL         Maximum Contaminant Level
pg/kg        microgram per kilogram
pg/L         micrograms per liter
mg/kg       milligram per kilogram
mg/L         milligrams per liter
                                         VI

-------
                       ACRONYMS AND ABBREVIATIONS
                                    (Continued)

mph         miles per hour
ms!          mean sea level
MWA       Mojave Water Agency
NCP         National Oil and Hazardous Substances Pollution Contingency Plan
NEDA       Northeast Disposal Area
NFA         No Further Action
NPL         National Priorities List
O&M        operations and maintenance
ORC         Oxygen Release Compound
OU          Operable Unit
OVA         organic vapor analyzer
PAH         polynuclear aromatic hydrocarbon
PCB         polychlorinated biphenyl
PCE         tetrachloroethene
POL         petroleum, oil, and lubricant
ppm         parts per million
PRG         Preliminary Remediation Goal
RAB         Restoration Advisory Board
RAO         remedial action  objective
RCRA       Resource Conservation and Recovery Act
RfD         reference dose
RI           Remedial Investigation
ROD         Record of Decision
RPM         Remedial Project Manager
RSA         Regional Statistical Area
RWQCB     Regional Water Quality Control Board
SAIC         Science Applications Internationa] Corporation
SARA       Superfund Amendments and Reauthorization Act of 1986
SCIA         Southern California International Airport
SEDA       Southeast Disposal Area
STP         sewage treatment plant
SVE         soil vapor extraction
SVOC       semivolatile organic compound
TBC         to-be-considered
TCA         trichloroethane
TCE         trichloroethene
TE          toxicity equivalent
TMV         toxicity, mobility, and volume
TPH         total petroleum hydrocarbons
TRC         Technical Review Committee
USAF       U.S. Air Force
USEPA      U.S. Environmental Protection Agency
USFWS      U.S. Fish and Wildlife Service
USGS       U.S. Geological Survey
UST         underground storage tank
                                       vn

-------
                      ACRONYMS AND ABBREVIATIONS
                                  (Continued)

UV         ultraviolet
VOC        volatile organic compound
VVEDA     Victor Valley Economic Development Agency
VVWRA    Victor Valley Wastewater Reclamation Authority
WPA        Work Plan Addendum
WQPS       Water Quality Protection Standards
                                    vin

-------
                                                       CO
           Section 1
MONTGOMERY WATSON

-------

-------
                                1.0 DECLARATION

 1.1          SITE NAME AND LOCATION

 George Air Force Base
 Operable Unit 3
 San Bernardino County, California

 1.2          STATEMENT OF BASIS AND PURPOSE

This decision document, a  Record of Decision  (ROD), presents the selected remedies for
Operable Unit (OU) 3 sites at George Air Force Base (GAFB), which were chosen in accordance
with the  Comprehensive Environmental Response, Compensation, and Liability Act of  1980
(CERCLA), as amended by the Superfund  Amendments and Reauthorization Act  of  1986
(SARA), and, to  the extent practicable, the National Oil and Hazardous Substances Pollution
Contingency Plan (NCP). This decision is based on the administrative record for these sites and
complies with 40 Code of Federal  Regulations (CFR),  Part 300.  The format of this ROD is
consistent with the  guidance  provided in  the U.S.  Environmental  Protection  Agency's
(USEPA's) "A Guide to Developing Superfund Records of Decision" (USEPA, 1990).

OU 3 consists of 60 Installation Restoration Program (IRP) sites.  Each of the OU 3 sites and any
proposed remedies are listed on Table 1. These sites are distributed throughout the base and
range in size from a few hundred square feet to over 90 acres. The purpose of this ROD is to set
forth the remedial actions to be conducted to remediate OU 3 IRP sites that were presented in the
OU 3 Feasibility Study (FS) Report (Montgomery Watson, 1997a) and to document the selection
of no further action (NFA) as final closure for the remaining OU 3 IRP sites.

The sites addressed in the OU  3 FS are presented in this ROD in two groups: 1) landfill sites
(DP-03, DP-04, LF-12, LF-14, LF-35, LF-44, and the Southeast  Disposal Area [SEDA][the
SEDA remediation boundary includes nine separate sites]) (referred to as "landfill sites" in this
ROD);  and 2)  sites  affected by total  petroleum hydrocarbons  (TPH) and/or volatile organic

                                         1-1

-------
  compounds (VOCs) (WP-17, FT-19a, FT-19b, FT-19c, FT-20 [soil], OT-51, SS-59, and OT-69)
  (referred to as 'TPH/VOC sites" in this ROD).  The TCE detected in groundwater in monitoring
  wells in the vicinity of Site FT-20 (groundwater) is currently associated with the groundwater
  contamination at  OU  2.  Therefore, final decisions regarding potential actions at Site FT-20
  (groundwater) will  be determined in the OU  2 ROD.   The  remaining OU 3  sites  are
  recommended for NFA (see Table 1).

  The U.S. Air Force (USAF), USEPA Region IX, and the State of California concur with the
  selected remedies.

  13    ^     ASSESSMENT OF THE SITE

 Actual  or threatened  releases of pollutants and  contaminants  from the landfill  sites  and
 TPH/VOC sites, if not  addressed by implementing the  remedial actions presented in this ROD,
 may present a risk to  public health, welfare, or the  environment.  The  remaining sites are
 recommended for NFA  (see Table 1).

 1.4           DESCRIPTION OF THE SELECTED REMEDIES

 Based on remedial investigations and alternatives evaluated in the  OU 3 FS  (Montgomery
 Watson,  1997a), the USAF determined the final action  for the 60 OU 3 IRP sites addressed in
 this ROD as summarized in Table 1. The determination of these final actions was achieved with
 the concurrence of the USEPA and the State of California. Section 2.0 provides further details
 describing the remedies for  sites requiring action.  Risk assessment and remedy  selection
considered reuse.  As a result, selected remedies are compatible with intended property reuse.
The selected remedy for the affected specific parcel will be reviewed with the local reuse agency,
prior to a transfer, to ensure that it remains compatible with reuse.
                                         1-2

-------
 1.5           STATUTORY DETERMINATIONS

 The selected remedies (Table 1) are protective of human health and the environment, comply
 with federal and state requirements that are legally applicable or relevant and appropriate to the
 remedial actions,  and  are cost-effective.   The  remedies utilize  permanent  solutions  and
 alternative treatment technology to the maximum extent practicable for these sites. The remedies
 for the TPH/VOC sites satisfy the statutory preference for remedies  that employ treatment that
 reduces toxicity, mobility, and volume (TMV) as  a principal  element.   However, because
 treatment of the principal threats of the landfill  sites was not found to be practicable, the
 remedies for the landfills do not satisfy the statutory preference for treatment  as a principal
element.^ A review of this ROD will be conducted every 5 years to ensure that the remedies
continue to provide adequate protection of human health and the environment.
                                        1-3

-------
  1.6
APPROVED
 ALBERT F.
 Director
 Air Force Base Conversion A^gency
                                Date
                                 Concurrence
 Chief, Federal Facilities Cleanup ;Branch
 Environmental Protection Agency
 Region:
JOHN E. SCAlgpURA
 -hief, Southern California Operations
Office of Military Facilities
Department of Toxic Substances Control

               f
HAROLD SINGER    J
                                              Date
                                Date
Executive Officer
California Regional Water Quality Control Board
Lahontan Region
                                              Date

-------
                                                     §
          Section 2
MONTGOMERY WATSON

-------

-------
                               2.0 DECISION SUMMARY

  This  decision summary  provides a  description of OU 3 including the regional  setting,
  physiography, meteorology, demography and land use, hydrology, hydrogeology, and water use.
  This section also summarizes the problems posed by the conditions at OU 3, the remedial
  alternatives, and the rationale for  the selection and how the selected remedy satisfies statutory
  requirements.

  2.1           SITE NAME, LOCATION, AND DESCRIPTION

  GAFB encompasses an area of approximately 5,347 acres and is  located in San Bernardino
  County in the western Mojave Desert near  the cities of Victorville and Adelanto, California.
  Victorville  is located on Interstate 15, approximately 70  miles northeast of the City  of Los
  Angeles, 35 miles north of San Bernardino, and 31 miles south of Barstow (Figure  1).  In
 evaluating environmental conditions at GAFB, all identified sites have been combined into three
 OUs based on the type of waste present and the geographical location (Figure 2).

 2.1.1         Description of Operable Units

 OU 1 consists of three sites: (1) Site SD-25 (S-20), an Industrial/Storm Drain which in the past
 received industrial  waste; (2) Site WP-26 (S-21), the former sewage treatment plant (STP)
 percolation ponds; and (3)  the dissolved TCE plume detected in the groundwater beneath the
 northeast portion of the base and adjacent off-base areas.  A ROD has been finalized for OU 1
 (Montgomery Watson, 1994).

 OU 2 consists of six sites: (1) Site SS-30, a free-phase JP-4 jet fuel plume identified beneath the
 Operational Apron; (2) Site ST-54, a pipeline leak near Building 708; (3) Site ST-57, Fuel Pit
No. 1; (4) Site SS-58, the underground storage tank (UST) complex at Building 690; and (5) Site
ST-67, the entire Liquid Fuel Distribution System, including five aboveground tanks, two major
pipelines (8-inch and 10-inch), and all hydrants (Fuel Pits  1  through 7) and associated piping.
                                         2-1

-------
 and (6) FT-20 (groundwater), TCE detected in the groundwater in the vicinity of the old sewage
 treatment plant percolation ponds.

 OU 3 consists of the 60 remaining IRP sites located throughout GAFB. The OU 3 sites consist
 of a variety of potential contaminant source areas including landfills, other waste disposal and
 storage sites, fire training areas, spill sites, and leachfields.  Table 1 presents a summary of all
 OU 3 IRP sites.  These sites are distributed throughout the base and range in size from a few
 hundred square feet to over 90 acres.  These sites have been designated as disposal pit (DP), fire
 training  area (FT), landfill (LF), radiological  waste (RW), spill site (SS), waste pit (WP), or
 "other" (OT).  The remedial investigations and site characterizations for the  OU  3 sites are
 detailed  in the OU 3 Remedial Investigation (RI) Report (Montgomery Watson, 1996a).  This
 ROD presents the final decision for closure of all OU 3 IRP sites.

 The pesticide dieldrin has been detected in monitoring wells in the eastern portion of the base in
 the vicinity of the former residential housing area (i.e., monitoring wells NZ-63, NZ-64, and NZ-
 66) (Montgomery Watson, 1996a and 1997d). These detections are not currently associated with
 OU 3 and will be addressed as part of another OU; therefore, the are not addressed as part of this
 OU 3 ROD. The manner in  which these detections are addressed is  to be determined based on
 discussions between the Remedial Project Managers  (RPMs)  for the USEPA, the California
 Department of Toxic Substances Control (DTSC) (formerly the California Department of Health
 Services  [DHS]), the Lahontan Regional Water  Quality  Control Board (RWQCB), and the
 USAF.

Based on the OU 3 remedial investigations,  the "landfill sites"  and the 'TPH/VOC sites" were
assessed for remedial actions as detailed in the OU 3 FS Report (Montgomery Watson, 1997a);
the remaining sites were recommended for NFA. Table 1 lists all OU 3 sites and documents the
sites for which NFA is recommended. The discussions that follow regarding OU 3 sites refer to
the sites that require some form of remedial action (i.e., the landfill sites and TPH/VOC sites).
                                         2-2

-------
  2.1.2         Physical Characteristics of OU 3

  The 60 OU 3 IRP sites arc located throughout GAFB.  The area immediately surrounding the
  base  is the  Victor  VaJley portion of  the  Upper  Mojave River  Basin.    The  regional
  geomorphology,  surface water  hydrology,  geology,  hydrogeology, regional  planning, and
  ecology  of GAFB and  the surrounding area are discussed in detail in the OU 3  RI Report
  (Montgomery Watson, 1996a) and are summarized below.

  2.1.2.1        Regional Physiography.  GAFB is located in the Mojave Desert physiographic
  province of California.  Locally, the base lies  within a wedge-shaped tectonic block in the
  south-central  portion of the Mojave Desert,  flanked by  the Sierra Nevada Mountains to the
  northwest, the Radman and  Cady Mountains to the northeast, the San Gabriel Mountains to the
 southwest, and the San Bernardino Mountains to the southeast (Figure 3).  The local region is
 comprised  predominantly  of  northward  sloping  alluvial  fan deposits   derived  from the
 surrounding mountains,  and recent deposits  associated  with the Mojave  River.   Regional
 elevations reach as high as  8.500 feet (near Crestline), where  annual precipitation typically  is
 more than 40 inches.  In contrast, the terminus of the Mojave River at Soda Dry Lake (elevation
 923 feet) south of Baker receives 3 inches of precipitation annually. Elevations in the vicinity of
 GAFB range from 2,650 feet at  the northeast corner of the study area, to 2,920 feet at the
 southwest comer of the  base, south of Air Base Road.  The average elevation at  GAFB  is
 approximately 2,750 feet, with average slopes of approximately 2 to 4 percent to the  northeast.
 The base is relatively flat  except at the  eastern edge, where the surface elevation drops
 approximately 200 feet to the Mojave River. The average elevation of the Mojave River flood
 plain immediately east of the base is approximately 2,580 feet (Montgomery Watson, 1996a).

The Mojave River flows along the east side of GAFB in a northwesterly direction.  Communities
within the Victor Valley area include the city of Adelanto, directly west and adjacent to GAFB,
the city of Victorville directly .southeast, and Oro Grande, Silver Lakes, Apple Valley, and
Hesperia.  The Victor Valley Wastewater Reclamation Authority (WWRA) treatment plant is
located approximately one-half mile north of the northern border of GAFB.
                                          2-3

-------
 2.1 JU2       Meteorology.  The climate in the GAFB area is typical of the high desert region
 of California and Nevada. The summers are hot and dry, with maximum daily temperatures
 often exceeding 100°F in July and August. Winters are cool and dry and nighttime temperatures
 often fall below  freezing in  December and January (SAIC,  1987).   The annual average
 temperature is 62°F.

 Based on Air Force records from 1942 to 1992, annual precipitation at GAFB ranges from 0.77
 inch to 11.22 inches, with an average annual precipitation of 5.72 inches (Montgomery Watson,
 1996a).  Monthly precipitation typically ranges from 0.25 inch to 4.47 inches, with the period
 from January through March being the wettest.  During storm events, daily precipitation may
 reach as much as 2.93 inches.  Snowfall is infrequent, but may total a few inches per year and
 was recorded to be as high as 17 inches in 1974. The average annual potential evapotranspiration
 (ET) rate is about 83 inches (SAIC, 1987), far exceeding average annual precipitation.

 Prevailing winds in the area of GAFB are from the south; however, the strongest gusts are
 typically from the west.  Westerly gusts of 50 miles per hour (mph) or more usually occur in the
 spring.  In the summer, strong southerlies blow over the San Bernardino Mountains (Cajon Pass)
 in the evenings.  Northerly winds occur more frequently in the fall and winter months (SAIC,
 1987).

 2.1.2-3  ,      Demography and Land Use. GAFB is located within Census Tract 91.02, and
 Regional Statistical Area (RSA) 32B of San Bernardino County (US Census Bureau).  RSA 32B
 also includes the cities  of Adelanto, Hesperia,  and Victorville and  the unincorporated
 communities of Phelan, Apple Valley, and Lucerne Valley.  According to the closure documents
 for GAFB, the estimated combined GAFB military and civilian work force on base in mid-1992
was 3,725. However, because the base closure in December 1992, there no longer arc permanent
residents on base. The following are 1994 estimated populations of the surrounding cities and
communities, according to their respective city offices or San Bernardino County (Montgomery
Watson, 1996a):

                   Adelanto                   13,000
                   Apple Valley              53,450
                                        2-4

-------
                     Hesperia                   58,050
                     Lucerne Valley             10,000
                     Oro Grande                    430
                     Phelan                     15,000
                     Silver Lakes                 3,000
                     Victorville                  57.830
                     TOTAL                   210,760

 The Victor Valley area has experienced significant population growth in the past two decades.
 Between  1970 and  1980, the number of residents in RSA 32B increased approximately  70
 percent (SAIC, 1987). Population growth in the area is projected to be approximately 5 percent
 annually until 2010 (USAF, 1992). The projected annual growth figures may be greater than 5
 percent depending on the ultimate reuse of GAFB.

 The major land  use activities of the Victor Valley area  include residential  development,
 government  and  commercial  services,   cement  manufacturing,   railroad  and  highway
 transportation, localized agricultural activities along the Mojave River, and industrial mining in
 the outlying areas. The California Aqueduct carries water across the high desert approximately 5
 miles south of the base and may impact long-term land use planning. A major fuels distribution
 pipeline parallels Air Base Road for half the length of the base, and a high-voltage transmission
 utility corridor crosses the southeast comer of the base.

 GAFB was established during World War n and provided the foundation for a steady economic
 base for the Victorville, Adelanto, and Apple Valley areas.  Until 1992, GAFB was the largest
employer  in the Victorville area.  Residential and commercial development  and growth  of
community services was, in large part, due  to the presence of the base. Despite the recent base
closure, the climate and recreational attractions within the region continue to contribute to the
development  of vacation  and/or second  homes as  well  as the  expansion of retirement
communities.  Growth in the Victor Valley also has been impacted as increasing numbers  of
people move  to the area seeking to avoid the congestion and high cost of living in the Los
Angeles Basin.
                                         2-5

-------
  The  proposed action for reuse of GAFB  is development of an international  airport  and a
  commercial, industrial, and business park development. The Local Reuse Agency (LRA) and the
  Victor Valley Economic Development Agency (VVEDA)  has  designated the airport as the
  Southern California International Airport (SCIA).   There are currently light  industry  and
  commercial  companies  using the facilities.   There are  no  current plans for residential
  development on former base property (CRSS Constructors, Inc., 1996). The  above reuse was
  considered during the development of risk assessments and remedy selection.   As a result, the
  selected remedies are compatible with reuse.  The selected remedy for the affected specific parcel
  will be reviewed  with the local reuse agency,  prior to a transfer, to ensure that it  remains
  compatible with reuse.

  2.1.2.4 ^     Hydrogeology. GAFB is located in the George Groundwater Sub-Basin which is
  a sub-basin of the Upper Mojave River Basin.  The George Sub-Basin reportedly is a structural
  trough containing up to 3,000 feet of alluvial sediments in the deepest parts of the basin.  The
 depth to bedrock is estimated to be approximately 1,350 feet below ground surface (bgs). Water
 level and lithology data have been used to identify two distinct water-bearing zones  in the GAFB
 area:  a shallow "Upper Aquifer" and a deeper "Lower Aquifer," separated by the "Aquitard."

 The Upper Aquifer is  a zone of saturated, highly to moderately permeable, interbedded silty
 sands, poorly sorted sands, silts, and clays.  Pumping test data indicate that the Upper Aquifer
 has transmissivities ranging from 7 square feet per day (ftVday) to 2,400 ftVday and hydraulic
 conductivities ranging  from less than 0.01 feet per day (ft/day) to 35 ft/day.  Groundwater
 elevations within the area range from approximately 2,680 feet above mean sea level (msl) in the
 northeastern  portion  of the base  to 2,760 feet  above msl in the southwest.  The  general
 groundwater flow direction typically varies from the north to northeast with a hydraulic gradient
 of approximately 0.003  feet/foot (ft/ft).  North of the base, the groundwater gradient increases to
 0.01 towards the northeast. The Upper Aquifer exists beneath GAFB; however, it terminates to
 the north and eastern portion of the base.  The saturated zone is up to approximately 80 feet thick
 and thins to a thickness of zero where the aquifer terminates.

The Aquitard, consisting of interbedded very low to low permeability clays and  silts, is  present
from approximately 2,650 feet above msl to 2,740 feet above msl and is approximately 20 to 40
feet thick.   The Aquitard  is believed  to  have been  deposited in a lake-filled basin  which
historically occupied the vicinity of GAFB.  The Aquitard hydrauiically separates the Upper and
Lower aquifers  but is not continuous north of the base and east of the area along the Mojave
                                          2-6

-------
  River bluffs.  However, the Aquitard is continuous to the west and southwest as determined by
  investigation activities performed for OU 1 (Montgomery Watson, I995b), OU 2 (IT, 1992), and
  OU 3 (Montgomery Watson, 1996a). The lack of hydraulic communication between the aquifers
  through the Aquitard is supported by a zone of  unsaturated moderately permeable materials
  encountered below the Aquitard and above the Lower Aquifer and dry clays within the Aquitard
  encountered in well borings during investigations  for OU 1, OU 2, and OU 3.  Geotechnical
  testing has indicated hydraulic conductivities of Aquitard silts and clays ranging from 3.1E-4
  ft/day to 1.7E-3 ft/day (Montgomery Watson, 1995b).  Where the Upper Aquifer terminates to
  the north and east of the area, the lateral edge of the Aquitard has been inferred.

 The Lower Aquifer is present beneath the entire base and generally consists of interbedded sands,
 gravelly sands, and silts with minor caliche beds. Groundwater elevations in the Lower Aquifer
 within the area range from 2,590 to 2,584 feet above msl.  The gradient in the central portion of
 the base is 0.0002 ft/ft and increases to 0.001 ft/ft  toward the east. Pumping test data indicate
 that  the Lower Aquifer has transmissivities ranging from  170 ftVday to  6,000 ftVday and
 hydraulic conductivities that may exceed 80 ft/day based on an assumed aquifer thickness of 100
 feet.  The Lower Aquifer is geographically extensive and is hydraulically associated with the
 Mojave River Aquifer. The Mojave River Aquifer  occupies the river channel  sediments east of
 the base.  The Mojave River deposits overlie and are interbedded with older Lower Aquifer soils.
 This unit is  relatively transmissive and  provides  good quality water to regional  wells.
 Potentiometric  contours of the Lower Aquifer are perpendicular to the directions of flow in the
 Mojave River.  Therefore,  groundwater flow in the Mojave River  and  Lower aquifers are
 parallel.

 2.1.2.5      Surface Water Hydrology.  The Mojave River is the major surface drainage in
 the Victor Valley. The Mojave extends for approximately 125 miles from its headwaters at the
 Mojave Forks in the San Bernardino Mountains to its terminus at Soda Dry Lake south of Baker
 (Figure 4). The river drains an area over 3,000 square miles (USAF, 1992). East of GAFB, the
 river flows northward, coming as close as approximately 1,500 feet from the northeast corner of
 the base.  Surface flow in the Mojave River through most of the Victor Valley typically occurs
only during heavy rainstorms. In the Upper Mojave River Basin, however, perennial flow occurs
                                          2-7

-------
 for approximately 1 mile below the Mojave Forks because of the perennial flow of Deep Creek
 (which merges with the Mojave at its headwaters), and again near Victorville through the Upper
 Narrows and the Lower Narrows.  The Narrows are formed by a bedrock ridge that creates a
 subsurface flow barrier, causing river underflow to rise to the ground surface.  U.S. Geological
 Survey (USGS) topographic maps and aerial photographs indicate that, historically, surface flow
 continued downstream as far as Bryman, 8 miles north of GAFB. Today, surface flow persists
 only approximately 1  mile below the Lower Narrows, except during and shortly  after heavy
 rainfall.  Regional  withdrawal of groundwater  apparently has lowered  the Mojave River
 underflow in the vicinity of GAFB.

 Daily mean discharge values of the Mojave River through the Lower Narrows during 1993
 ranged from 3 to 13,800 cubic feet per second (cfs), with an  average daily discharge of 394 cfs.
 Daily discharge in  1993, a very wet year, averaged nearly 28  times greater than 1990 values
 (Montgomery Watson, 1996a).  Discharge records maintained  since 1899 indicate an average
 discharge of 75.2 cfs, with a maximum discharge of 70,600 cfs recorded March 2, 1938 (USGS,
 1992).

 East of GAFB, the Mojave River has cut a channel approximately 1 mile wide and 200 feet deep.
 No perennial streams are located within the boundaries of GAFB. Rainfall generally percolates
 into the topsoil,  collects in low  areas  and  evaporates, or  discharges through  small  natural
 channels. Surface water from GAFB drains predominantly  to the northeast and east.  Runoff
 from the flight line and the industrial and office areas is directed through roadways, storm drains,
 culverts, and ditches to the Outfall Ditch on the northeast side of the base.   Flow from this
 drainage ditch reaches the Mojave River only during heavy storms.  Runoff from  the eastern
 residential areas discharges through small natural gullies located to the north and  east. This
 runoff travels  north and east toward the Mojave River wash. Much of the southern part of the
base drains northward into the industrial and flight line runoff system. Intermittent surface flow
 on the western half of the base discharges north-northwestward into tributaries that discharge  to
 the Mojave River near Helendale.
                                          2-8

-------
   A large, north-trending arroyo dissects the northeast section of the base.  The arroyo channel is
   approximately 15 feet wide near the northern base fence line and 100 feet wide where the arroyo
   discharges into the Mojave River wash. It was formerly fed by the Outfall Ditch from the base,
   numerous gullies, and a smaller drainage ditch that originates from the Fire Training Area.  The
   arroyo  intermittently receives treated effluent from  the  OU 1 groundwater  extraction and
   treatment system. This water percolates into the subsurface just north of the base boundary and
   before the arroyo discharges to the Mojave River wash.

   Discharge sources into the Mojave River upstream of GAFB are limited to agricultural  and
   recreational  uses and several fish hatcheries.  East of GAFB,  the Riverside  Cement Plant
  discharges cooling water into the Mojave River Channel.  The VVWRA sewage treatment
  facility northeast of GAFB discharges treated water directly into the Mojave River wash east of
  the plant.  Although annual discharge volumes vary, they have been steadily increasing.  Data
  supplied by the VVWRA indicate that during 1993, the treatment plant discharged an average of
  approximately 5 million gallons per day (gpd) into the Mojave River, and another 1  million gpd
  through its percolation ponds (Montgomery Watson, 1996a).

  2.1.2.6       Water Use. Water usage includes domestic, industrial, and agricultural. The per
  capita rate of water demand has been estimated to be 200 to 285 gpd (SAIC, 1987).  Because of
 arid conditions and lack of surface water bodies in the Upper Mojave River Valley Groundwater
 Basin, groundwater has been the principal source  of water used in the Victor  Valley desert
 communities.  The Mojave Water Agency (MWA) oversees the adjudication of groundwater
 within the Mojave River Groundwater Basin. Consumptive groundwater usage  in the Upper
 Mojave River Groundwater  Basin (the MWA's "Alto" portion of  the basin)  in  1990  was
 estimated to be 89,400 acre-feet. The projected annual consumption for the year 1995  was
 94,500 acre-feet.

 Population increases in  the study area caused domestic water demand to almost double during the
 period between  1973 and  1983 (SAIC,  1987), and double again between 1983  and 1994
 (Montgomery Watson,  1996a). The increase in demand  has  led to overdraft conditions (water
removed from the basin  but  not replenished) within the  Mojave River Groundwater Basin.
                                         2-9

-------
  Groundwater overdraft in the Upper Mojave  River Basin for  the years 1990 and  1995 is
  estimated to be  19,900  and 25,000 acre-feet, respectively (Montgomery  Watson,  1996a).
  Groundwater consumption in the George Groundwater  Sub-basin has  not  been specifically
  tracked by the MWA; however,  tracking by smaller use areas is being pursued as groundwater
  overdraft in the region continues  to be a concern.

  As of 1990, the MWA has been entitled to 50,800 acre-feet per year of water from the California
  Water Project.  However, due to recent statewide drought conditions, the MWA has not yet been
  allotted their full entitlement.  Once allotted, the MWA plans  to begin utilizing their water
  entitlement to directly recharge groundwater in the Mojave River Basin (Montgomery Watson,
  1996a).

 Limited information is available concerning  supply  wells on and  in the vicinity of GAFB.
 Available data indicate the existence of off-base wells beyond the northeast corner of the base,
 below the southeast corner of the base,  and along the Mojave River beyond  the eastern base
 boundary (Figure 5).

 Two supply wells owned by the VVWRA are located northeast of the base. These two wells are
 reported to be screened at depths of 65 to 75 feet bgs with pumping capacities of 500 gallons per
 minute (gpm) each.  Based on the location and approximate elevations of the wellheads, these
 wells are believed to be screened in  the Mojave River Aquifer.  The groundwater table was
 measured at 36 feet bgs. Groundwater from these WWRA wells  is used only for non-potable
 and industrial applications, while bottled drinking water is supplied for workers at the plant
 (Montgomery Watson, 1996a).

 According to the records maintained by the California Department of Water Resources (CDWR),
 four production wells exist southeast of the base (Figure 5). The production capacities of these
 wells range from 100 to 1,200  gpm. The wells are screened to depths ranging from 500 to 610
 feet bgs, and may  be screened in  a  deeper and possibly different aquifer system than the
monitoring wells installed at GAFB in the Lower Aquifer.
                                         2-10

-------
  Currently, seven production wells supply water to both GAFB and the adjacent city of Adelanto.
  An eighth well was closed when production rates declined.  Water elevations indicate that these
  wells are screened below or in the deeper portions  of the Lower Aquifer (Boyle. 1987). All of
  the production wells are located near the Mojave River beyond the eastern base boundary, on the
  west side of the Mojave River in Section 30 T6N, R4W, just north of the Lower Narrows (Figure
  5).  Five of the seven water supply wells near GAFB  operated while the base was active;
  however, production rates since base closure are not known.  These wells will likely be used to
  service the future uses of the base property.

  Three additional wells are located northeast of GAFB production wells along the eastern bank of
  the Mojave River (Figure 5), and supply water to the town of Oro Grande.

  It is suspected that privately owned wells and smaller capacity domestic and irrigation wells in
  the vicinity draw from the Upper Aquifer.

 2.1.2.7       Vegetation. The most predominant type of vegetation is the creosote bush scrub
 community, which includes creosote bush, cheesebush, burroweed, ricegrass, and Mormon tea.
 This type of vegetation is typically found in the undeveloped areas of the base. Russian Thistle,
 or tumbleweed, is often found in the disturbed areas.  Riparian (associated with water) vegetation
 communities including cottonwoods,  willows, cattail  rushes, and sedges are found along the
 Mojave River channel, near the base golf course and the former GAFB STP percolation ponds
 (Montgomery Watson, 1996a).

 A biological assessment was conducted in  1989 in the northern portion of the  base and in an
 off-base section just north of the northern base boundary.  This assessment was  done as part of
 the initial FS  for the Northeast Disposal Area (NEDA) (JMM,  1988). The dominant plant
 species found were creosote bush, sweetbush, cheesebush, paperbag bush, and indigo bush, all
 Mojave Desert creosote bush scrub. Golden cholla cactus, beavertail cactus, and pencil cholla
were also found scattered throughout the site.  Herbaceous plants  included introduced grasses
such as abu-mashi and red brome, as well as native grasses and herbs such as Indian ricegrass.
                                         2-11

-------
 spurge, chia, and fiddlencck.  Joshua trees occur along the base of the steep slopes in the area
 (LSA, 1989).

 Several sensitive plant species may occur in the area of GAFB. Good habitat exists for several of
 the plant species; however, only Joshua trees were actually observed  during the survey of the
 area  (LSA, 1989).  Additionally, the U.S. Fish and Wildlife Service (USFWS) lists three
 Category-2 species that may be present on GAFB.  These are the alkali mariposa lily, Bars tow
 woody sunflower, and the  desert cymoperus.  Category-2 species are  those for which  existing
 information is insufficient to warrant listing as endangered or threatened species (USAF,  1989).

 2.1.2.8       Animal Life.  Animal life in the vicinity of GAFB includes both desert and
 riparian species such as black-tail jackrabbit, cottontail rabbit, and antelope ground  squirrel
 (Montgomery  Watson,  1996a).  Seventy-five bird species  have been identified  in the area,
 including ravens, hawks, owls, quail, flycatchers,  larks,  warblers,  sparrows, and blackbirds.
 Other wildlife includes lizards, snakes, pocket mice, raccoons, and coyotes. Generally, animal
 activity is highest in the northern and southern portions of the base where native plants are least
 disturbed.  Animal activity typically has been lowest in the high traffic areas of the base, such as
 the housing and industrial complex, the recreation  areas,  and the  runways (USAF,  1989);
 however, it is likely that some activity and reinhabitation has occurred since base closure.

 The desert tortoise is the only animal species found on  the base that is listed by the USFWS as a
 threatened or endangered species. Two Category-2 animal species that may be present on GAFB
 are the ferruginous hawk, and Mojave ground squirrel (USAF, 1989).

2.2          SITE HISTORY AND ENFORCEMENT ACTIVITIES

2J2.1         Base History

GAFB is a 5,347-acre facility constructed between 1941 and 1943. GAFB was commissioned as
a flight training school. With flight training as primary activity at GAFB throughout its history,
bombardier and glider, single- and twin-engine,  and jet  flight training schools  were  all
 *
                                         2-12

-------
 accommodated on the base at various times. Over the years, a wide variety of aircraft has been
 stationed at GAFB.

 To effectively carry out the primary mission of pilot training,  GAFB engaged in a variety of
 support  operations such  as aircraft maintenance and fire fighting training, that required the
 handling, use, and disposal of hazardous and non-hazardous materials.

 Since 1980, the USAF has had an active  environmental cleanup  program which is currently
 known as the IRP.  The purpose of the IRP at GAFB is to protect human health and the
 environment by identifying and cleaning up environmental contamination resulting from past
 disposal practices.   The cleanup at GAFB  is  being conducted  under the  requirements  of
 CERCLA. Section 120 of CERCLA states that the facilities must investigate and remediate, if
 necessary, past releases of hazardous waste.

 In December 1988, GAFB was informed that it would be decommissioned as an Air Force base
 in December 1992.  In February 1990, the USEPA added GAFB to the Superfund National
 Priorities List (NPL).

 In October 1990, GAFB signed a Federal Facilities Agreement (FFA) with USEPA Region DC,
 the DTSC, and the Lahontan RWQCB. The  three OUs were created with the signing of the FFA.
 The base was formally closed on December 15, 1992.

 2J2.2         OU 3 Site Investigations

 RI/FS activities at GAFB began in 1981 when the USAF performed a records search to identify
 possible contaminated sites and potential problems that may result from contaminant migration
 from these sites (CH2M Hill, 1982).  Since  1981, the USAF has performed investigations in an
effort to confirm the presence of potential contamination at sites identified during the records
search and to define the extent of contamination at these sites.
                                        2-13

-------
  The first preliminary study conducted under the ERP at GAFB was completed in January 1982.
  This study was a Phase  I records search and was based on  a review of available records
  pertaining to chemical handling and disposal practices, interviews with site personnel, and a site
  survey of activities at many  sites  within GAFB.  The 1982 report  indicated that potentially
  hazardous waste from past activities was stored and disposed at GAFB  (CH2M Hill,  1982).

  In 1992, a work plan was prepared for OU 3 (JMM, 1992).  This work plan summarized the
  historical information for all known OU 3 sites including the results of any prior investigations.
  The  OU 3 Work Plan Addendum (WPA) assessed historical information, the Phase 1 records
  search (CH2M Hill, 1982), and subsequent site inspections. Based on this assessment, the WPA
 recommended NFA for 20 sites determined not to pose a threat  to human health or the
 environment and presented the recommended remedial investigation activities for the remaining
 OU 3 sites.

 The OU 3 remedial investigation activities began in 1992. Of the 60 OU 3 IRP sites that make
 up OU 3, no further investigation was required at the 20 sites designated as NFA in the OU 3
 WPA (JMM, 1992), land use restrictions were recommended for Site LF-35 in the WPA, and the
 remaining  sites were investigated.  Of the sites investigated, Montgomery Watson investigated
 27 IRP sites; Metcalf & Eddy  (M&E) investigated eight sites;  Montgomery Watson and M&E
 investigated two sites, and  International Technologies Corporation (IT) investigated two sites.
 Table 1 summarizes this information. The 20 sites recommended as NFA in the WPA included
 one site located in the SEDA (LF-11) and three sites (DP-02, LF-43, and LF-45) associated with
 OU 3 sites that were  investigated by  Montgomery Watson.  The OU 3 RI  Report presented
 results from the OU 3  remedial investigations including cumulative basewide human health and
 ecological risk assessments.

The primary objective of the  OU 3 RI  was  to obtain sufficient information to support an
informed decision regarding the most appropriate future action at each site. Specific objectives
of the RI report included  identification of the extent of contamination, analysis of the fate and
transport of contaminants, and development of a baseline risk assessment.
                                         2-14

-------
 Specific field investigation activities included aerial ground penetrating radar (GPR) surveys,
 surface GPR surveys, boundary confirmation borings, soil-gas surveys, surface and subsurface
 soil sampling,  test pit  excavations, soil  borings, monitoring  well installation,  downhole
 geophysics, aquifer testing, monitoring  well  sampling, geotechnical sampling, HydroPunch®
 sampling, record searches, biological testing, dioxin testing, surface mapping, and a radiological
 survey.

 To help identify compounds of potential concern  (COPCs), background  concentrations were
 established for inorganics in soil and groundwater.  Detected organic compounds  were  not
 considered to be naturally occurring and, therefore, were considered to be above background.

 Vadose zone contaminant migration modeling (SESOIL) was performed under hypothetical
 worst case conditions to estimate potential  impacts to groundwater.  For  most sites  modeled,
 results suggested that the most mobile constituents detected in soils would  migrate less than 20
 feet below the bottom of the site within 100 years. Therefore, utilizing the known  data in  a
 conservative  fashion,  impacts to groundwater from the landfills are unlikely.   However,
 modeling suggested that groundwater will be impacted by vadose zone contamination at Sites
 FT-19candOT-51.

 Human health and ecological risk assessments were performed for the COPCs at each site as
 appropriate. The risk assessment addressed public health impacts from ingestion, inhalation,  and
 dermal exposure to the COPCs in the  soil.  Specific receptors and exposure scenarios were
 identified for each site. The exposure scenarios used to evaluate the potential risk for a particular
 site were dependent on the proposed reuse of land parcel in which a site was located, the COPCs
 identified at the site, and the potential completed exposure pathways.  At the time of the remedial
 investigation  and performance of the risk assessment, the proposed reuse of land parcels at
GAFB were identified in the base Management Action Plan (MAP) (USAF, 1993).  Exposure
 scenarios that were used for each site-specific risk assessment included: industrial/commercial,
trespasser/visitor, construction worker (potential surface  soil  exposure), construction worker
 (potential subsurface soil exposure), and  future resident.  Additional details describing the risk
 assessment methodology are presented in the OU 3 RI Report (Montgomery Watson, 1996a).

                                         2-15

-------
  Based on the results of the RI activities and results of the risk assessment, sites that posed a
  potential threat to human health and the environment were analyzed in detail in the OU 3 FS.
  The sites assessed in the OU 3 FS Report were grouped in "landfill sites" and "TPH/VOC sites"
  because of the similarity between the sites in each group with respect  to contaminant  type,
  distribution, site characteristics, and potential cleanup activities.  The "landfill sites" included:
  Sites DP-03, DP-04. LF-12, LF-14, LF-44, and the SEDA (remediation boundary includes nine
  sites; see Table 1).  The "TPH/VOC sites" included: WP-17, FT-19a, FT-19b, FT-19c, FT-20
  (soil), OT-51, SS-59, and OT-69. A separate detailed FS analysis of Site OT-69 was presented in
 the RI/FS for the TCE/tetrachloroethene (PCE) Study Area (IT, 1995a).

 Table 1 summarizes the 60 OU 3 IRP sites and the proposed remedy (i.e., NFA or the remedial
 alternative selected through the FS process).   The findings and conclusions of this ROD are
 based on the analysis of OU 3 presented in the final FS Report (Montgomery Watson,  1997a)
 and the accompanying Proposed Plan (Montgomery Watson, 1997b). The technical information
 supporting each alternative is included in these reports and the  OU 3 RI Report (Montgomery
 Watson, 1996a).

 23          HIGHLIGHTS OF COMMUNITY PARTICIPATION

 The Community Relations Plan (CRP)  was completed in 1991  for GAFB  by IT following
 USEPA guidance (IT,  1991).  Consistent with the  CRP, the USAF established a Technical
 Review Committee (TRQ which was composed of the USEPA, DTSC, Lahontan RWQCB, and
 representatives from  adjacent communities. The TRC met  on a quarterly  basis to provide
 community representatives with up-to-date information on recent milestone events.  In January
 1994, GAFB established the Restoration Advisory Board (RAB)  which replaced the TRC. The
 RAB  met on a  quarterly basis until  1997 when it voted to move to an annual meeting.  The
 meetings are open to the public. The RAB is designed to act as a focal point for environmental
exchange between GAFB and the public.
                                        2-16

-------
  The OU 3 RI Report (Montgomery Watson, 1996a), OU 3 FS Report (Montgomery Watson,
  1997a), and OU 3 Proposed Plan (Montgomery Watson, 1997b) were released to the public and
  were made available in both the Administrative  Record File and in  information repositories
  maintained at the following locations:

         •      The Air Force Base Conversion Agency (AFBCA) Office at GAFB
               The Victorville Branch of the San Bernardino County Library
         •      The Adelanto Branch of the San Bernardino County Library

  The  availability of these  documents and  announcement of the public  meeting  and public
  comment period  were  published in the  Daily  Press in Victorville, the Desert  Dispatch  in
  Barstow, and the Sun in San Bernardino in September 1997.  A press release was sent to five
  other local newspaper  and radio organizations announcing  the  public  meeting  and public
  comment period.

 The Proposed Plan was mailed in September 1997 to all parties identified in the CRP, including
 government officials, media, private organizations, and interested members of the community.

 A public comment period was held from September 22, 1997 to October 22, 1997.  A public
 meeting was  held on  October 8,  1997 at the  Green  Tree Inn, Victorville,  California.
 Representatives from  the USAF, USEPA, DTSC, and Lahontan RWQCB  were  present at the
 meeting.  The Responsiveness  Summary (Section 3.0 of this  ROD) contains responses to
 questions from the meeting and comments submitted by mail.

 2A           SCOPE  AND  ROLE  OF  OPERABLE UNIT  WITHIN  THE SITE
              STRATEGY

 As  summarized in Section  2.1,  the  suspected hazardous  waste sites present at GAFB were
 grouped into three OUs based on  the type of waste present and the geographical location (Figure
 2).  This ROD deals specifically with OU 3.  Chemicals found at 60 OU 3 ERP sites potentially
 relate to  activities associated with equipment maintenance; fire training; fuel  use and storage;
pest control; laboratory, shop, and hospital operations; and landfill and solid waste disposal.

                                        2-17

-------
 As summarized in Table 1,40 OU 3 sites were recommended for NFA based on the results of the
 WPA (JMM, 1992) and the  OU 3 RI investigation (Montgomery Watson, 1996a).  Land use
 restrictions were recommended for Site LF-35 in the OU 3 WPA (JMM, 1992). Final decisions
 regarding the groundwater in the vicinity of Site FT-20 will be determined in the OU 2 ROD
 because it is currently associated with the groundwater contamination at OU 2 (this affected
 groundwater is now referred to as FT-20 [groundwater]). The remaining role for OU 3 is to set
 forth the remedial action to be conducted to remediate the remaining sites that were presented in
 the OU 3 FS Report (Montgomery Watson, 1997a).   These remaining  sites (Figure 6) are
 presented in two groups: the landfill sites (DP-03, DP-04, LF-12, LF-14, LF-44, and the SEDA
 [remediation boundary includes nine sites]); and the TPH/VOC sites (WP-17, FT-19a, FT-19b,
 FT-19c, FT-20 [soil], OT-51,  SS-59, and OT-69) and are discussed in detail below.

 2JB          LANDFILL SITE SUMMARY

 This section summarizes the site characteristics, risk  assessment results,  descriptions of the
 alternatives evaluated, alternatives comparison, and the selection of the final remedies for the OU
 3 landfill sites requiring action (Sites DP-03, DP-04, LF-12, LF-14, LF-35, LF-44, and the
 SEDA).

 Site  characterization activities were not performed  for  Site LF-35 as part  of the OU  3
 investigations. Site LF-35 is a reported landfill for asbestos and fiberglass located in Parcel A.
These constituents are not expected to be mobile in soils. Unless mobilized via excavation
activities, any asbestos or fiber glass present should not pose  a threat to human  health or the
environment. Therefore, land use restrictions are recommended in the OU 3 WPA (JMM, 1992).
By placing land use and  deed restrictions on the site forbidding disturbance of buried materials,
the potential exposure pathways for asbestos or fiberglass .will not be completed and protection
of human health would be assured.

The site characterization activities for the remaining landfill sites arc discussed below.
                                        2-18

-------
 2.5.1         Summary of Landfill Site Characteristics and Risk Assessments

 The OU 3 landfill sites presented in this ROD were investigated and evaluated using the same
 rationale  and investigative techniques, including geophysics, soil gas, test pits, and soil  and
 groundwater sampling. Table 2 presents a summary of the OU 3 landfill site characterizations on
 a site-specific basis.  The  results of the each of the landfill  site investigations were similar;
 various inorganics were detected  as  were  hydrocarbons, semi volatile organic compounds
 (SVOCs), and dioxins. The results of the baseline risk assessments indicated that although there
 were some sites with a maximum excess iifetime cancer risk above the California benchmark of
 1E-06, all were within or below the USEPA guidelines of  1E-04 to 1E-06.  The site-specific
 ecological risk assessments indicated that a potential risk to ecological receptors was present at
 Sites  DP-03, DP-04,  LF-12,  LF-14,  and  the  SEDA.   Ecological risks were  considered
 insignificant at Site LF-44.

 The site characterizations and risk assessments for the landfill sites requiring remedial action are
 summarized below. Additional details regarding the site characterizations and risk assessments
 are presented in the OU 3 RI/FS reports (Montgomery Watson, 1996a and 1997a).

 2.5.1.1      Site  DP-03.   Site DP-03  is a suspected  acid  and  oil  burial site  located
 approximately 400 feet north of the northeast end of the Crosswind/Secondary Runway.  The
 following subsections summarize the site characterization and risk assessment for Site DP-03.

 Site Characterization.  To characterize Site DP-03, aerial  GPR  and surface geophysics
including GPR, electromagnetic terrain conductivity (EM), and magnetometry (MAG) were
performed. Additionally, an extensive soil-gas program was conducted, surface and subsurface
(test pit) samples were collected and analyzed, and physical site conditions were evaluated. Data
gathered were used to perform fate and  transport modeling and were also incorporated into the
baseline risk assessment.

Geophysical anomalies suggested the presence of buried material concentrated near the center of
the site. VOCs in shallow soil-gas were detected sporadically throughout the site. Three test pits

                                         2-19

-------
 were excavated to depths up to 10 feet to investigate geophysical and soil-gas anomalies.  In
 general, geophysical anomalies corresponded to construction debris such as rebar, concrete, and
 asphalt, and fill materials were encountered to depths greater than 9 feet bgs.  No evidence of
 buried drums were found, and no soil staining or visual indications of contamination was noted
 in the test pits.  Lead, 10 SVOCs, and hydrocarbons were detected sporadically in surface and
 subsurface samples above background.  Although benzene, toluene, ethylbenzene, and xylene
 (BTEX) was detected in the  soil gas,  no VOC contamination was found in the  surface or
 subsurface soil  samples.  Vadose zone modeling results showed that even  under the  most
 conservative conditions, the most mobile constituent detected at any OU 3 landfill site will not
 migrate deeper than 20 feet below the bottom of the disturbed areas within 100 years.  Therefore,
 the less mobile contaminants detected at this site  would not be expected to migrate deeper than
 20 feet below the bottom of the disturbed areas. Because the depth to groundwater beneath Site
 DP-03  is  greater than 100 feet, modeling  results indicate  that there  is no potential for
 contaminant leaching to groundwater.

 Risk Assessment. As described in Section 2.2.2, a baseline risk assessment was performed for
 Site DP-03 for which risk assessment scenarios were evaluated based on the proposed reuse of
 the land parcel in which the site is located (USAF, 1993).  Using the likely future land use of an
 airfield and related facilities, the baseline human health risk  assessment evaluated risk for the
 following scenarios:  industrial/commercial, trespasser/visitor, construction worker (potential
 surface soil exposure), and construction worker (potential subsurface  soil exposure).   This
 baseline risk assessment estimated the highest excess lifetime cancer risk of 1.9E-05, primarily
 because of polynuclear aromatic hydrocarbons (PAHs) under an industrial/commercial scenario.

The qualitative  ecological benchmark screening indicated that there  are potential  risks  to
ecological  receptors  because of the localized presence of PAHs.  However, the  results  of
subsequent quantitative food  chain modeling specifically for bioaccumulative compounds
indicated that bioaccumulative compounds of potential ecological concern (COPECs)  pose no
significant  risks  to vegetation  and wildlife at the site.  Human activities associated with the
proposed land use for this parcel are expected to limit the selection of Site DP-03 as a primary
habitat for many ecological receptors.

                                         2-20

-------
  2.5.1.2       Site DP-04. Site DP-04 is a reported pesticide and oil drum burial site located
  between Sites DP-03 and LF-14. The following subsections summarize the site characterization
  and risk assessment for Site DP-04.

  Site Characterization.   To characterize Site DP-04, aerial  GPR and  surface geophysics
  including GPR, EM, and MAG were performed. Additionally, an extensive soil-gas program
  was conducted, surface and subsurface  (test  pit) samples were collected and analyzed, and
  physical site conditions were evaluated. Data gathered were used to perform fate and transport
  modeling and were also incorporated into the baseline risk assessment.

 Geophysical anomalies suggested the presence of buried material concentrated near the center of
 the site. VOCs in shallow soil-gas were detected sporadically throughout the site.  Six test pits
 were excavated to depths up to  15 feet to investigate geophysical and soil-gas anomalies.  In
 genera], geophysical anomalies corresponded to construction debris such  as concrete, metal,
 wood, and plastic, and fill materials we.re encountered to depths greater than  15 feet bgs.  No
 evidence of buried drums were found, and no soil staining or visual indications of contamination
 were noted in  the test pits. Lead,  nickel, mercury, zinc, two pesticides, one polychlorinated
 biphenyl (PCB) and hydrocarbons were detected sporadically in surface and  subsurface samples
 above background.  Although benzene and total BTEX were detected in the soil gas, no VOC
 contamination was  found in the surface or subsurface soil samples. Vadose zone modeling
 results showed that even under the most conservative conditions, the most  mobile constituent
 detected at any OU 3 landfill site will not migrate deeper than 20 feet below the bottom of the
 disturbed areas within 100 years. Therefore, the less mobile contaminants detected at this site
 would not be expected to migrate deeper than 20 feet below the bottom of the disturbed areas.
 Because the depth to groundwater beneath Site DP-04 is greater than 100 feet, modeling results
 indicate that there is no potential for contaminant leaching to groundwater.

 Risk Assessment.  As described in  Section 2.2.2, a baseline risk assessment  was performed for
Site DP-04 for which risk assessment scenarios were evaluated based on the proposed reuse of
the land parcel in which the site is located (USAF, 1993). The scenarios evaluated for this site
                                         2-21

-------
  included:  industrial/commercial, trespasser/visitor,  construction worker (potential surface soil
  exposure), and construction worker (potential subsurface soil exposure). This baseline human
  health risk assessment estimated the highest excess lifetime cancer risk of 6.7E-05, primarily
  because of Aroclor 1260 (a PCB) under the industrial/commercial scenario.

  The results of the ecological risk assessment indicated a potential risk to burrowing mammals
  and their predators (e.g., barn owl), primarily because of the highly localized presence of Aroclor
  1260.  However, human activities associated with the proposed land use for this parcel along
  with the disturbed nature of the site are expected to limit the selection of Site DP-04 as a primary
  habitat for many ecological receptors.
      3       Site LF-12.   Site LF-12 is an abandoned landfill site  located in an unpaved,
 relatively undeveloped area north of the base residential area and east of Phantom Street. The
 following subsections summarize the site characterization and risk assessment for Site LF-12.

 Site Characterization.   To characterize Site  LF-12, aerial  GPR and  surface  geophysics
 including GPR, EM, and MAG were performed. Additionally, an extensive soil-gas program
 was conducted,  surface and subsurface (test pit)  samples were collected and analyzed, up- and
 downgradient monitoring wells were installed and sampled, and physical site conditions were
 evaluated.   Data gathered were used to perform fate  and transport modeling and  were also
 incorporated into the baseline risk assessment.
       *
 Geophysical anomalies suggested the presence of buried material concentrated near the center of
 the site.  VOCs in shallow soil gas were detected  sporadically throughout the site.  Five test pits
 were excavated to depths up to  15 feet to investigate geophysical and soil-gas anomalies. In
 general,  geophysical anomalies  corresponded  to construction debris such as metal,  plastic,
 concrete, glass and plaster board, and fill materials were encountered to depths greater than 10
 feet bgs. No evidence of buried drums were found, and no soil staining or visual indications of
contamination was noted in  the test pits.  Barium, lead,  mercury, zinc,  three  dioxins,  and
hydrocarbons were detected sporadically in surface and  subsurface samples above background.
Although benzene, total BTEX, and TCE were detected in the soil gas, no VOC contamination
  •
                                         2-22

-------
 was found in the surface or subsurface  soil samples.  One monitoring well was  installed
 upgradient of the site,  and three monitoring wells were  installed downgradient of  the site.
 Analysis of the soil samples collected from the borings and the groundwater samples collected
 from the wells indicate that no leaching of contaminants has occurred at the site. Vadose zone
 modeling results  showed that even  under the most conservative conditions, the most mobile
 constituent detected at any OU 3 landfill site will  not migrate deeper than 20 feet  below the
 bottom of the disturbed areas within 100 years. Therefore, the less mobile contaminants  detected
 at this site would not be  expected  to migrate deeper than 20 feet  below the bottom of the
 disturbed areas. Because the depth to groundwater beneath Site LF-12 is greater than 100 feet,
 modeling results indicate that there is no potential for contaminant leaching to groundwater.

 Risk Assessment  As described in Section 2.2.2, a  baseline risk assessment was performed for
 Site LF-12 for which risk assessment scenarios were evaluated based on the proposed reuse of
 the land parcel in which the site is located (USAF, 1993).  The scenarios evaluated for  this site
 included:  industrial/commercial, trespasser/visitor,  construction worker (potential surface soil
 exposure), construction worker (potential subsurface soil exposure), and future resident. This
 baseline human health risk assessment estimated the  highest excess lifetime  cancer risk of 7.7E-
 07, primarily because of dioxins under the future resident scenario. This is below the benchmark
 values for risk assessment.

 The results of the  ecological risk assessment indicated a potential risk to burrowing  mammals
 and their predators (e.g., barn owl), primarily because of the highly localized presence of dioxins,
 lead, zinc, and barium.  However, human activities associated with the proposed land use for this
 parcel are expected to limit the selection of Site LF-12 as a primary habitat for many ecological
 receptors.

Although the calculated risk to human health was below the benchmark, because  the site was an
abandoned landfill and there is a potential risk to ecological receptors, closure actions were
considered in the OU 3 FS.
                                         2-23

-------
 25.1.4        Site LF-14.  Site LF-14 is an abandoned landfill site located in an unpaved,
 relatively undeveloped area east of the Alert Hangar.  The following subsections summarize the
 site characterization and risk assessment for Site LF-14.

 Site Characterization.   To characterize  Site LF-14,  aerial GPR, and surface geophysics
 including GPR, EM, and MAG were performed.  Additionally, an extensive soil-gas program
 was conducted, surface and subsurface (test pit) samples were collected and analyzed, up- and
 downgradient monitoring wells were installed and sampled, and physical site conditions were
 evaluated.  Data gathered were used to perform fate and transport modeling  and were also
 incorporated into the baseline risk assessment.

 Geophysical anomalies suggested the presence of buried materials at the site.  VOCs in shallow
 soil-gas were detected sporadically throughout the site.  Seven test pits were excavated to depths
 up to 15 feet to investigate geophysical and soil-gas  anomalies.   In general, geophysical
 anomalies corresponding to construction debris such as metal, wood, glass, plastic,  asphalt,
 concrete,  gravel, trash, and fill materials were encountered to depths greater than 15 feet bgs.
 Two of the test pits were located near crushed drums on the surface of the site.  Empty and
 crushed drums were also located in these test pits, but no evidence of soil staining was noted on
 the surface of the site or in the test pits. Lead, cadmium, copper, mercury, manganese, zinc, four
 SVOCs, three pesticides, toluene, and hydrocarbons were detected sporadically in surface and
 subsurface samples above background.  Although benzene, toluene, PCE, TCE, trichloroethane
 (TCA), freon-11 (F-ll), and total  BTEX were detected in the soil gas, no  widespread  VOC
 contamination was found in the surface or subsurface soil samples.  Toluene was the only VOC
 detected at the site, and it was detected in two of the subsurface samples. Two monitoring wells
 were installed downgradient of the site to assess the water quality. Analysis of the soil samples
collected from one boring and the groundwater samples collected from the wells indicate that no
leaching of contaminants has occurred at the site.  Vadose zone modeling results showed that
even under the most conservative conditions, the most mobile constituent detected at any OU 3
landfill site will not migrate deeper than 20 feet below the bottom of the disturbed areas within
 100 years. Therefore, the less mobile contaminants detected at this site would not be expected to
migrate deeper than 20 feet below the bottom of the disturbed areas.  Because the depth to

                                         2-24

-------
  groundwater beneath Site LF-14 is greater than 100 feet, modeling results indicate that there is
  no potential for contaminant leaching to groundwater.

  Risk Assessment As described in Section 2.2.2, a baseline risk assessment was performed for
  Site LF-14 for which risk assessment scenarios were evaluated based on the proposed reuse of
  the land parcel in which the site is located (USAF, 1993). The scenarios evaluated for this site
 included:  industrial/commercial, trespasser/visitor, construction  worker (potential surface soil
 exposure), and construction worker (potential subsurface soil exposure).  This baseline human
 health risk assessment estimated the highest excess  lifetime cancer risk of l.OE-05 primarily
 because of cadmium under an industrial/commercial  scenario.   Although this  is above the
 benchmark values for risk assessment, the cadmium at the site is considered naturally occurring
 and within background ranges.

 The results of the ecological risk assessment indicate a potential risk to burrowing mammals and
 their predators (e.g., bam  owl), because  of the  localized  presence  of cadmium,  lead,  and
 pesticides. However, human activities associated with the proposed land use for this parcel are
 expected to limit the selection of Site LF-14 as a primary habitat for many ecological receptors.

 Although the calculated risk to  human  health was due to  constituents that are considered
 naturally occurring, because the site was an abandoned landfill and there was a potential risk to
 ecological receptors, closure actions were considered in the OU 3 FS.

 2^.1.5       Site LF-44.  Site LF-44 is an abandoned landfill  site located about  1.000 feet
 south of Site LF-14.  The following subsections summarize the  site characterization and risk
 assessment for Site LF-44.

 Site Characterization. To characterize Site LF-44 aerial GPR and surface geophysics including
GPR, EM, and MAG were performed. Surface and subsurface (test pit) samples were collected
and analyzed, and physical site conditions were evaluated. Data gathered were  used to perform
the fate and transport modeling and were also incorporated into the baseline risk assessment.
                                         2-25

-------
  Geophysical anomalies suggested the presence of buried material concentrated near the center of
  the site. VOCs in shallow soil gas were detected sporadically throughout the site.  Four test pits
  were excavated  to depths up to  15 feet to investigate geophysical and soil-gas anomalies.  In
  general, geophysical anomalies corresponded to construction debris such as concrete and trash,
  and fill materials were encountered to depths greater than 8 feet bgs.  No evidence of buried
  drums were found, and no soil staining or visual indications of contamination was noted in the
  test pits. Antimony, lead, and hydrocarbons were detected sporadically in surface and subsurface
  samples above background. No VOC contamination was found in the surface or subsurface soil
  samples.   Vadose zone modeling results  showed  that even  under the most  conservative
  conditions, the most mobile constituent detected at any OU 3 landfill site will not migrate deeper
 than 20 feet below the bottom of the disturbed areas within 100 years. Therefore, the less mobile
 contaminants detected at this site would not be expected to migrate deeper than 20 feet below the
 bottom of the disturbed areas.  Because the depth to groundwater beneath Site LF-44 is greater
 than 100 feet, modeling results indicate that  there is no potential for contaminant leaching to
 groundwater.

 Risk Assessment  As part of the screening for the baseline human health risk assessment, no
 COPCs were identified, therefore, no human health risk assessment was completed.

 The results  of the ecological risk  assessment suggest some potential ecological impacts at Site
 LF-44 from physical disturbances.  Some stress on vegetation exists at the site as a result of
 physical disturbance related to former site activities.  However, significant  chemical  risks to
 vegetation or wildlife were not indicated by the site characterization data. Nevertheless, because
 this site was an abandoned landfill with exposed debris, in order to restore the natural surface at
 the site, closure actions were considered in the OU 3 FS.

2*5.1.6        Site SEDA.  The geographic  area known as the SEDA historically  included 10
OU 3 sites:  five landfill sites (Sites LF-07, LF-08, RW-09, DP-10, and LF-11), one burial site
(WP-40), one spill site (SS-52), and three munitions disposal areas (DP-15, DP-33, and DP-34).
The location of the SEDA relative to  GAFB is presented in Figure 2.   Site  LF-11 is located
generally to  the east of the other sites and was recommended for NFA in the OU 3 WPA (JMM,
                                                                                  *
                                         2-26

-------
   1992).  Because of the geographical proximity of the remaining nine sites and the generally
   indeterminable  boundaries between them, the entire area has  been handled as a unit.  The
   following subsections summarize the SEDA site characterization and risk assessment.

  Site Characterization. To characterize the SEDA, aerial GPR and surface geophysics including
  GPR, EM, and MAG  were performed.  Additionally, an extensive soil-gas program  was
  conducted,  surface and subsurface (test pit  and soil borings) samples were  collected  and
  analyzed, up- and downgradient monitoring wells were installed and  sampled, and physical site
  conditions were evaluated. Data  gathered were used to perform fate and transport modeling
  using SESOIL and were also incorporated into the baseline risk assessment.

  Geophysical anomalies suggested the presence of buried materials at the site. VOCs in shallow
  soil-gas were detected sporadically throughout the site. Twenty-two test pits were excavated to
  depths up to 15 feet to investigate geophysical and soil-gas anomalies.  In general, geophysical
  anomalies corresponded to construction debris such as concrete, asphalt, metal, paper,  glass,
 wood, rubber, and plaster board. This construction debris, burned debris, and fill material was
 encountered to depths greater than 13.5 feet bgs. A few crushed and empty drums were noted as
 surface debris at the site; however,  no evidence of buried drums was found and no soil staining
 or visual indications of contamination was noted in the test pits. Although total benzene, BTEX,
 PCE, TCE, dichloroethene (DCE), TCA, Freon-11 (F-l 1), and carbon tetrachloride were detected
 in the soil gas, no widespread VOC contamination was found in the surface or subsurface soil
 samples.  Toluene was the only VOC detected at the site, and it was detected in two subsurface
 samples. Two monitoring wells were installed upgradient of the site, and seven monitoring wells
 were installed downgradient of the site.  Analysis of the soil samples collected from the borings
 and the groundwater samples collected from the wells indicates that no leaching of contaminants
 has occurred at the site. Vadose zone modeling results (SESOIL) showed that even under the
 most conservative conditions, the most mobile constituent detected at any OU 3 landfill site will
 not migrate deeper  than 20 feet below the bottom of the disturbed  areas within 100 years.
Therefore, the less mobile contaminants detected at this site would not be  expected to migrate
deeper than 20 feet below the bottom of the disturbed areas. Because the depth to groundwater
                                        2-27

-------
 beneath the SEDA is greater than 100 feet, modeling results indicate that there is no potential for
 contaminant leaching to groundwater.

 Risk Assessment.  As described in Section 2.2.2, a baseline risk assessment was performed for
 the SEDA for which risk assessment scenarios were evaluated based on the proposed reuse of the
 land parcel in which the site  is located (USAF,  1993).  The scenarios evaluated for this site
 included:  industrial/commercial, trespasser/visitor, construction worker  (potential surface soil
 exposure), construction worker (potential subsurface soil exposure), and future resident.  This
 baseline human health risk assessment estimated the highest excess lifetime cancer risk of 8.4E-
 05 primarily because of arsenic and chromium under the future resident scenario. Although this
 is above the benchmark values for risk assessment, the arsenic and chromium values detected at
 the SEDA are considered within background and naturally occurring.

 The results of the ecological risk assessment indicated a potential risk to burrowing mammals
 and their  predators (e.g., barn  owl), because of the  localized  presence of several metals and
 dioxin/furan congeners.

 Although  the  calculated risk  to  human  health was due  to constituents  that are considered
 naturally occurring, because the site was an abandoned landfill and there is a potential  risk to
 ecological receptors, closure actions were considered in the OU 3 FS.

 2.5.2          Description of Landfill Site Alternatives

Based  on the  results of remedial investigations,  it was determined that remedial action was
potentially necessary at the OU 3 landfill sites (DP-03, DP-04, LF-12, LF-14, LF-44, and the
SEDA).  An FS analysis was performed in which (1) remedial action objectives (RAOs) were
identified; (2) potentially  applicable technologies were . identified  and  screened  based on
effectiveness, implementability, and cost; (3) the technologies retained after  the initial screening
were combined  into potential  alternatives  for each  site;  and  (4) the alternatives were  then
subjected  to a detailed analysis with respect to the  nine criteria  defined  by  the USEPA for
CERCLA sites (USEPA. 1988).

                                          2-28

-------
 Alternatives were developed and evaluated  for the landfill  sites as a group because of the

 similarity between the sites with respect to contaminant type, distribution, site characteristics,

 and potential actions. The RAOs established for the OU 3 landfill sites are summarized below:


       •      prevent direct contact with landfill contents;

       •      minimize  infiltration  that  may result   in  waste  constituents  leaching  to
              groundwater;

       •      control surface water runoff and run-on, and erosion; and

       •      monitor groundwater quality  to determine  if landfill  contaminants are leaching to
              the groundwater.


Five remedial alternatives  were developed for the OU 3  landfill sites from an analysis  of

remedial technologies as part of the OU 3  FS (Montgomery Watson,  1997a).  The  five
alternatives, with their components, are as follows:


       Alternative 1 (No Action with Monitoring)
              1)  Groundwater Monitoring
             2)  5-Year Site Review

       Alternative 2  (Institutional Controls)
             1)  Surface Restoration
             2)  Access Restrictions
             3)  Land Use Restrictions
             4)  Groundwater Monitoring
             5)  5-Year Site Review

       Alternative 3  (Surface Controls/Existing Cover Rehabilitation)
             1)  Surface Controls
             2)  Surface Restoration
             3)  Access  Restrictions
             4)  Land Use Restrictions
             5)  Groundwater Monitoring
             6)  5-Year Site Review

      Alternative 4 (Soil Cover)
             1) Native Soil Cover
             2) Surface Controls
             3) Surface Restoration

                                         2-29

-------
              4)  Access Restrictions
              5)  Land Use Restrictions
              6)  Groundwater Monitoring
              7)  5-Year Site Review

        Alternative 5 (Synthetic Cap)
              1)  Synthetic Cap
              2)  Native Soil Cover
              3)  Surface Controls
              4)  Surface Restoration
              5)  Access Restrictions
              6)  Land Use Restrictions
              7)  Groundwater Monitoring
              8)  5-Year Site Review


These alternatives are presented  in detail in the OU 3 FS and are summarized in the sections
below.
2.5.2.1        Alternative 1:  No Action with Monitoring. As required by the NCP, the no

action alternative serves as a baseline against which other landfill site alternatives are compared.

Its components include groundwater monitoring and the 5-year site review.


Groundwater monitoring at the OU 3 landfill sites would be part of the an approved basewide

long-term monitoring plan for GAFB. Selected monitoring wells at each site would be sampled

annually, semi-annually, or quarterly, to determine if landfill contaminants are leaching to the
groundwater.


The no  action alternative would leave the landfill contents in place with no closure activities

undertaken.  Because contaminants would remain on site, a site review would be conducted

every 5  years as required by CERCLA.  This would include a review of annual environmental

monitoring results to determine if landfill contaminants have migrated to the environment (i.e.,

moved beyond the known boundaries of the landfill sites). The purpose of the 5-year site review

and long-term monitoring would be to assess the effectiveness of an alternative.


2.5.2.2       Alternative 2:  Institutional Controls. Alternative 2 includes access and land

use restrictions, surface restoration, groundwater monitoring, and the 5-year site review.

                                         2-30

-------
  Access restrictions would involve the installation of 8-foot-high chain-link fences with barbed
  wire and/or posting of warning signs posted along the perimeter of the site. The locations of the
  fences at each landfill would be determined as part of the design and would minimize access to
  people, vehicular traffic, and terrestrial animals.

  The  implementation  of land use restrictions  at the OU 3  landfill sites would assure the
  protectiveness of the remedy and human health.  Deed restrictions would be recorded to restrict
  use of the sites for the following purposes:  1) a residence, including any mobile home or factory-
  built housing, constructed or  installed for use as permanently occupied residential  human
  habitation, 2)  a long-term care hospital for humans, 3) a traditional  public or private school for
  persons under 21 years of age, and 4) a day care center.  In addition, the deed would prohibit the
  disturbance of the landfill cover, subsurface soils, and fencing without prior approval from the
  USAF and appropriate state and local agencies.

 Surface restoration would involve the removal of municipal wastes and debris, such as plastics,
 tires, paper products, rubble, etc., from the landfill surface.  Use of backhoes and dump trucks to
 remove wastes would be combined with manual collection, following the proper health and
 safety procedures.  Collected wastes would be disposed of at an off-site Class m landfill facility,
 or may be consolidated with other wastes under an OU 3 landfill cap.

 The definitions of the other components of this alternative (e.g., groundwater monitoring and the
 5-year site review) are the same as for Alternative 1.

 £5.2.3     Alternative 3: Surface Controls/Existing Cover Rehabilitation.  Alternative 3
 has the same components as Alternative 2 with the addition of surface controls.  In addition, the
 existing cover  conditions would be evaluated and rehabilitated  to  functional parameters as
 discussed below.

Surface controls include general site grading, drainage, and  revegetation.  General site grading
would be accomplished by using cut-and-fill techniques which involve excavation of clean soils

                                          2-31

-------
  from outside the landfill boundary and from elevated mounds of clean soils within the landfill
  and consolidation of these soils in the "potholes" within the landfill.   In order to minimize
  intrusive activities at the OU 3 landfill sites, the remedial design for this alternative would ensure
  that the fill volume is greater than the cut volume and the difference would be imported from and
  off-site borrow source. This design would effectively produce a soil cover on the landfill with an
  estimated thickness of 12 to 18 inches.  The final grade for each site would have a minimum
  slope of 1.5 percent, with the actual slope designed to fit the natural topography of the site. Site
  drainage would be implemented by constructing drainage channels around the landfill boundary
  to divert surface water away from the landfill site.  A conceptual diagram of the implementation
  of surface controls/existing cover rehabilitation is shown on Figure 7.

 The land use restrictions for sites where surface controls would be implemented would include
 the prohibition  of subsurface development  (e.g.,  excavation,  pile-driving)  and  excessive
 vehicular traffic (e.g., off-road vehicles, dirt bikes), in addition to the more general types of land
 use restrictions which may be applied.

 2.5.2.4       Alternative  4:   Soil Cover.   Alternative  4 has  the  same  components as
 Alternative 3 with the addition of a 24-inch-thick native soil cover installed over the graded
 landfill surface.  The soil cover would be compacted only  for structural purposes because the
 native soil  at GAFB is expected to be  difficult to compact to low permeability levels.  The
 primary purpose of the native soil cover is to provide a separation layer that would prevent direct
 contact with landfill contents. A conceptual diagram of a native soil cover is shown on Figure 8.
              Alternative 5:  Synthetic Cap.  Alternative  5 has the same  components  as
Alternative 4 with the addition of a synthetic flexible membrane  liner (FML), 30-mil thick,
installed over the graded landfill surface.  A native soil cover would then be installed over the
synthetic liner, as described for Alternative 4.  In addition to preventing direct contact with
landfill contents, the synthetic cap also prevents surface water infiltration that could lead to the
leaching of landfill contaminants to the groundwater and/or storm water. A conceptual diagram
of a synthetic cap is shown on Figure 8.
                                          2-32

-------
 2.53        Summary of Comparative Analysis of Alternatives for the Landfill Sites

 The remedial alternatives developed were analyzed in detail using the nine evaluation criteria
 required  by the  NCP.  These  criteria are classified as threshold criteria, primary balancing
 criteria, and modifying criteria.  Threshold criteria are:

        1)    Overall protection of human health and the environment
        2)    Compliance with applicable or relevant and appropriate requirements (ARARs)
 Primary balancing criteria are:
        3)    Long-term effectiveness and permanence
        4)     Reduction of TMV through treatment
        5)     Short-term effectiveness
        6)     Implementability
        7)     Cost
 Modifying criteria are:
        8)     State/support agency acceptance
       9)     Community acceptance

 The resulting strengths and weaknesses of the alternatives were then weighed to identify  the
 alternative providing  the  best balance among the  nine  criteria.  Table 3 summarizes this
 comparison.

 &5.3.1       Overall Protection  of Human Health and the Environment. This criterion is
 an overall assessment of whether each alternative provides adequate protection of human health
 and  the environment.   The evaluation focuses on a determination of the degree to which a
 specific alternative achieves adequate protection and describes the manner in which site risks are
 eliminated, reduced, or controlled through treatment, engineering, or institutional measures. The
 potential for cross-media impacts is also assessed.

 Alternative  1:  Does  not provide  any  direct protection of human health and the environment
 because no landfill closure activities are undertaken.  This alternative would not change the risks
currently associated with a site.

                                        2-33

-------
 Alternative 2:  Provides the minimum requirements necessary to protect human health  by
 reducing the potential for direct contact with landfill contents through access and land use
 restrictions and the removal of municipal wastes from the surface. However, Alternative 2 does
 not satisfy the RAOs for minimizing infiltration and controlling runoff and soil erosion and
 current risks associated with the site are only slightly reduced.

 Alternative 3:  Provides better protection of human health and the environment than Alternative
 2 by providing a final cover with the proper grade and protected slopes.  The potential for direct
 contact with landfill contents is substantially reduced and  the potential for contaminant leaching
 is reduced. By eliminating potential exposure pathways to landfill contaminants, the  initially
 low risks associated with the site are additionally minimized.

 Alternative 4: Provides better protection of human health and the environment than Alternative
 3  by providing a thicker soil cover.  The potential  for direct contact with landfill contents is
 practically eliminated and the potential for contaminant leaching is further reduced.  Alternative
 4 provides additional confidence that the risks associated with the site are minimized.

 Alternative 5:   Provides the same protection of human health and better protection of the
 environment than Alternative 4 by providing a final cover that is  more effective in reducing
 infiltration. The potential for contaminant leaching is practically eliminated.

 2.53.2        Compliance with ARARs. Pursuant to Section  121  (d) CERCLA, as amended,
the remedial actions must attain a degree of cleanup which assures protection of human health
and the environment.   In addition CERCLA  requires  that remedial actions  meet standards,
requirements, limitations, or criteria that are ARARs.  ARARs are  of three  types:  chemical-,
action-, and location-specific.  The three types of ARARs are defined as follows:

       •     Chemical-Specific  ARARs.    Chemical-specific   ARARs  include   those
             environmental laws and regulations that regulate the release to the environment of
             materials  possessing certain chemical or physical  characteristics  or containing
             specified chemical compounds.  These requirements generally set health- or risk-

                                         2-34

-------
               based concentration limits or discharge limits for specific hazardous substances
               (USEPA, 1989).

               Location-Specific ARARs.  As defined in the USEPA draft guidance (USEPA,
               1988):  "Location-specific ARARs are restrictions placed on the concentration of
               hazardous substances or the conduct of activities solely because  they  are in
               specific  locations.  Some examples of special  locations  include  floodplains,
               wetlands, historic places, and sensitive ecosystems or habitats."

              Action-Specific  ARARs.  Action-specific ARARs are restrictions that  define
              acceptable treatment and disposal procedures  for hazardous substances.  These
              ARARs  generally set performance, design,  or other similar  action-specific
              controls or restrictions on particular kinds of activities related to management of
              hazardous substances or pollutants, such as Resource Conservation and Recovery
              Act of  1976 (RCRA) regulations for waste  treatment, storage, and disposal.
              These requirements are triggered by the particular remedial activities  that are
              selected to accomplish a remedy.  The type and nature of these requirements is
              dependent upon  the  particular  remedial  or removal  action  taken  at  a site.
              Therefore, different actions or technologies are often subject to different action-
              specific ARARs.


Identification and consideration of potential ARARs associated with a site and its remedial action

is an ongoing process throughout site characterization and remediation.


An ARAR may be either "applicable" or "relevant and appropriate," but not  both. The NCP

(contained in Title 40 of the CFR Part 300) defines "applicable"  and "relevant and appropriate
requirements" as follows:


       "Applicable requirements means those cleanup standards, standards of control, and other

       substantive requirements, criteria, or limitations promulgated under federal environmental

       or  state environmental or facility  siting law  that specifically address a hazardous

       substance, pollutant, contaminant, remedial action, location, or other circumstance at a

       CERCLA site. Only those state standards that are identified by a state in a timely manner

       and that are more stringent than federal requirements may be applicable."


       "Relevant and appropriate requirements means those  cleanup standards, standards of

      control, and other substantive  requirements,  criteria, or limitations promulgated under

      federal environmental  or state environmental or  facility siting laws  that,  while not

                                         2-35

-------
       'applicable' to a hazardous substance, pollutant, contaminant, remedial action, location,
       or other circumstance at a CERCLA site, address problems or situations sufficiently
       similar to those encountered at the CERCLA site that their use is well suited to the
       particular site. Only those state standards that are identified by a state in a timely manner
       and that are more stringent than federal requirements may be applicable."

In other words, a requirement is "applicable" when the remedial action or the circumstances at
the  site  satisfy all  of the jurisdictional prerequisites of that requirement.  Relevant  and
appropriate requirements must be complied with to the  same degree as if they were applicable,
but there is more discretion in this determination and it is possible for only part of a requirement
to be considered relevant and appropriate in a given case.
                                                                                      •
Where no promulgated standards  exist  for  a given chemical  or situation,  nonpromulgated
advisories and guidance  ("to-be-considered" [TBC]  materials) issued by  federal or  state
government may be used in determining the necessary level of cleanup for protection of human
health or the environment.  TBCs do not have the status of potential ARARs; however, in many
circumstances they will be considered along with ARARs as part of the site risk assessment and
may be used in determining the necessary level of cleanup.

Identification of ARARs and TBCs must be done on a site-specific basis.  Neither CERCLA nor
the NCP provides across-the-board standards for determining whether a particular remedy will
effect an adequate cleanup at a particular site. Rather, the process recognizes that each site will
have unique characteristics that must be evaluated and compared to those'requirements that apply
under the given circumstances.

Final ARARs for  the OU  3  landfill sites were established through discussions  between the
Lahontan RWQCB, DTSC, USEPA, and USAF.  A listing of agreed upon federal and state laws
and regulations that are ARARs for the OU 3  landfill sites is provided in Table  4.  Based on the
ARARs identified:   Alternative 1 will not comply  with all ARARs  for the landfill  sites;
Alternative 2 may not comply with all federal and state ARARs on landfill closure at all sites;
                                         2-36

-------
  and Alternatives 3. 4, and 5 are expected to comply with the pertinent federal and state ARARs
  on landfill closure such as grading, drainage, slope protection through revegetation, etc.

  2.5.3.3        Long-Term Effectiveness and Permanence. The purpose of this criterion is to
  assess the residual risk and the adequacy and reliability of controls associated with a particular
  alternative.  The magnitude of risk resulting from the presence of untreated waste or treatment
  residuals is assessed with respect to the volume or concentration of residual contaminants.

 The second component,  adequacy and reliability of controls, assesses the containment systems
 and institutional controls in place to determine if they are sufficient to ensure that both human
 and environmental exposure is within protective levels. The long-term reliability of management
 controls to provide continued protection from residuals is also addressed with regard to (1) the
 potential need to replace technical components of the alternative,  and (2) the potential exposure
 pathway and resulting risks should the remedial action need replacement.

 Alternative 1:  This alternative does not satisfy the RAOs for preventing direct  contact with
 landfill contents, minimizing infiltration, and controlling runoff and soil erosion.  Therefore, the
 risks from direct contact and the potential for contaminant leaching remains unchanged.

 Alternative 2: This alternative partially satisfies the RAO for preventing direct contact with
 landfill contents (through surface restoration and access and land use restriction), thereby slightly
 reducing  the  risks.   However, the  long-term reliability  of access restrictions  and surface
 restoration would not be as reliable as the soil cover rehabilitation and/or installation described
 for Alternatives 3 through 5. In addition, land use restrictions may be difficult to enforce in the
 long term. Alternative 2  does not satisfy the RAOs for minimizing infiltration and controlling
 runoff and soil erosion. Therefore, the potential for contaminant leaching remains unchanged.

 Alternative 3:  This alternative satisfies the RAO  for  preventing direct contact with landfill
contents (through surface controls and cover rehabilitation), thereby  effectively  minimizing
potential risks.  The  alternative  effectively meets the RAOs for  reducing  infiltration  and
controlling runoff and soil  erosion, thereby reducing the potential for contaminant leaching.

                                           2-37

-------
 However,  surface  controls require comprehensive long-term maintenance to prolong  their
 effectiveness.

 Alternative 4: This alternative effectively satisfies the RAOs for preventing direct contact with
 landfill contents, minimizing infiltration, and  controlling  runoff and soil erosion,  thereby
 eliminating the risks and the potential for contaminant leaching. However, a soil cover requires
 comprehensive long-term maintenance to prolong its effectiveness.

 Alternative 5: This alternative effectively satisfies the RAOs for preventing direct contact with
 landfill contents, minimizing infiltration,  and controlling  runoff and soil erosion,  thereby
 eliminating the risks and the  potential for contaminant leaching.  However, a soil cover and a
 synthetic cap both require comprehensive long-term maintenance to prolong their effectiveness.

 2.5.3.4        Reduction  of Toxicity,  Mobility,   and   Volume  through  Treatment.
 Alternatives are assessed to determine the extent to which they permanently reduce TMV of the
 contaminants posing the principal threats at a site.  The specific factors considered in this
 assessment include:
       •      treatment or recycling process(cs) of associated target contaminants  and the
              amount of contaminants to be destroyed or treated;
       •      degree of expected reduction in the TMV and the degree to which treatment or
              recycling will be irreversible;
       »      type and quantity of treatment residuals expected to remain following treatment;
              and
       •      whether or not the alternative satisfies the statutory preference for treatment as a
              principal element.

Alternative 1: This alternative does not provide any reduction of TMV of contaminants in the
landfill sites.
Alternative 2: The removal of municipal wastes from the surface reduces the amount of wastes
at the landfill sites.
                                          2-38

-------
    Alternative 3: The removal of municipal wastes from the surface reduces the amount of wastes
    at the landfill sites. This alternative does not provide any reduction of toxicity or volume of
    contaminants in the landfill sites.  However, the surface controls/existing cover rehabilitation
    nummizes surface water infiltration and runoff, thereby reducing the mobility of contaminants
   through leaching.

   Alternative 4: The removal of municipal wastes from the surface reduces the amount of wastes
   at the landfill sites. This alternative does not provide any reduction of toxicity or volume of
   contaminants in the landfill sites.  However, the surface controls, existing cover rehabilitation
   and soil cover, minimize surface water infiltration and runoff, thereby reducing the mobility of
  contaminants through leaching.

  Alternative 5:  The removal of municipal wastes from the surface reduces the amount of wastes
  at the landfill sites.  This alternative does not provide any reduction of toxicity or volume of
  contaminants in the landfill sites.  However, the surface controls, existing cover rehabilitation
  so,l cover, and synthetic cap all minimize surface water infiltration and runoff, thereby reducing
  the mobility of contaminants through leaching.
               Short-Term Effectiveness.   Alternatives are  evaluated with  respect to their
 effects on human health and the environment during implementation of the remedial action. This
 evaluation addresses protection of site workers and  the community during remedial actions.
 potential environmental impacts, and the time until remedial action objectives are achieved.

 Alternative 1:  This alternative results in no risks to construction workers because no closure
 activities are undertaken.
Alternative 2: This alternative results in minimal risks to construction workers during surface
restoration activities.
                                         2-39

-------
Alternative 3:  This alternative results in minimal risks to construction workers during surface
restoration, surface controls, and existing cover rehabilitation activities.

Alternative 4:  This alternative results in minimal risks to construction workers during surface
restoration, surface controls, existing cover rehabilitation, and soil cover installation activities.

Alternative 5:  This alternative results in minimal risks to construction workers during surface
restoration, surface controls, existing cover rehabilitation, and soil cover and  synthetic  cap
installation activities.

2.5.3.6        Implementability. This criterion has three components: (1) technical feasibility,
(2) administrative feasibility,  and (3) availability of services and materials.  Each alternative is
assessed on the basis of factors within these three categories.

The assessment of the administrative feasibility of a particular remedial alternative is based on
the number and complexity of activities needed to coordinate  with other offices and regulatory
agencies during preparation and implementation of the alternative. Factors that are considered in
the assessment of technical feasibility include:

       •      potential  for  problems  associated  with  construction  and  operation  of an
              alternative;
       •      reliability of an alternative and its components;
       •      ease of undertaking additional remedial action, if needed; and
       •      ability to monitor the effectiveness of the remedy  and evaluate the risks of
              exposure should monitoring be insufficient to detect a failure.

The availability of services and materials is to be considered. This includes such items as off-site
treatment, storage or disposal capacity, equipment, and specialists.

The implementability of each remedy becomes progressively more difficult from Alternative  1 to
Alternative 5 because of the consecutive addition of components as described below.

-------
  Alternative 1:   This alternative is  easily implemented because  no closure  activities are
  undertaken. Groundwater monitoring is easy to implement and the materials required are readily
  available. There arc no administrative difficulties associated with this alternative.

  Alternative 2:  Although more difficult to implement than Alternative  1, surface restoration is
  easy to implement, using standard equipment and technologies and readily available services and
  materials.  Some administrative  difficulties may be encountered for land use  restrictions
  depending on property disposal and reuse plans.

  Alternative 3:  This  alternative  is more difficult to implement than  Alternative  2 with the
  addition of surface  controls and  existing cover  rehabilitation.   Additional components are
  feasible, using standard equipment and technologies and readily available services and materials.
 Some difficulties in site grading may occur because of uneven topography in some areas.  Some
 administrative difficulties may be encountered for land use restrictions depending on property
 disposal and reuse plans.

 Alternative 4:   This alternative is more difficult to implement than Alternative 3 with the
 addition of the soil  cover component.  Additional components arc  feasible, using standard
 equipment and technologies and readily available services and materials.  Some administrative
 difficulties may be encountered for land use restrictions depending on  property disposal  and
 reuse plans.

 Alternative 5:  This  is the most difficult to implement with the addition of the synthetic cap
 component.  Implementation of the synthetic cap  is  feasible, using standard equipment and
 technologies and readily available services and materials. Installation of the synthetic cap can be
difficult and care must be  taken so that punctures or tears to not develop during placement.
Some administrative difficulties may be encountered  for  land use restrictions depending on
property disposal and reuse plans.
                                         2-41

-------
 2,53.7        Cost. Both capital costs and operation and maintenance costs are considered for
 each alternative, with a target accuracy of -30 to +50 percent. Capital costs include both direct
 (e.g., equipment) and indirect (e.g., contingency allowances) costs.  Costs are presented on a
 present-worth basis over a period of 30 years, with a discount rate of 7 percent. Table 5 presents
 a summary of the remedial alternative costs for the landfill sites for each of the five alternatives.
 Detailed cost analysis is presented in the OU 3 FS Report (Montgomery Watson, 1997a).

 2.5.3.8       State Acceptance.  This assessment considers the  technical and administrative
 issues and concerns the state or support agency may have regarding each of the alternatives.
 Final application of this criterion will occur in the approval of this ROD.

 Alternative 1: It is likely the state would not accept this alternative because it does not include
 components to achieve the RAOs, in particular, it does not actively prevent contact with landfill
 contents or minimize infiltration.

 Alternative 2:   It is unlikely  the  state would  accept  this  alternative for sites with  COPCs
 resulting in calculated human health or COPECs resulting in calculated ecological risk because it
 does not actively minimize infiltration.  However, this site is likely to be satisfactory for sites
 with exposed debris but not having COPCs or COPECs (i.e., Site LF-44).

 Alternative 3: This alternative would be considered more acceptable  than Alternatives  1 and 2
 because it eliminates  the  potential for direct contact  with  landfill contents and reduces the
potential for contaminant leaching through the rehabilitated existing landfill cover with the use of
surface controls.

Alternative 4: This alternative may be perceived as preferable to  Alternative 3 because of the
additional protection from contact with landfill contents and reduction of infiltration provided by
the native soil cover.

Alternative 5: This alternative may be perceived as preferable to  Alternative 4 because of the
additional protection from infiltration provided by the synthetic liner.
                                           2-42

-------
  2.5.3.9       Community Acceptance.  Community acceptance indicates the public support
  for a given alternative.  Section 3.0 of this ROD documents the community acceptance of the
  selected remedies, as presented in the Proposed Plan (Montgomery Watson, 1997b).  Section 3.0
  includes a responsiveness summary that addresses the comments  received during the public
  comment period.  The community did not express any significant objections to the selected
  remedies during the public meeting or public comment period.

  2.5.4         The Selected Remedies for the Landfill Sites

  This section provides a description of the preferred alternatives  for remediation of the OU 3
  landfill sites based on the detailed evaluation of alternatives presented in the OU 3 FS Report
  (Montgomery  Watson, 1997a).  This section includes the basis for selection of a preferred
 alternative, a description of the preferred alternative, and cost analyses.

 2^.4.1        Selection of the Preferred Alternatives.  The RAOs established for the landfill
 sites in the OU 3 FS are summarized in Section 2.5.2. An evaluation of the five alternatives with
 respect to the nine  CERCLA criteria resulted in the  selection of the  following  preferred
 alternatives to meet the RAOs for the OU 3 landfill sites.

 Site  DP-03.   Under the industrial/commercial scenario,  the  baseline  human health  risk
 assessment estimated the highest cancer risk of 1.9E-05 for this landfill site, primarily because of
 the presence of PAHs. This risk value is above the California and USEPA acceptable benchmark
 value of l.OE-06.

 The ecological  risk assessment indicated that there were potential  risks to ecological receptors
 because of the localized presence of PAHs. However, the results of subsequent quantitative food
chain modeling specifically  for bioaccumulative compounds indicated that bioaccumulative
constituents pose no significant risks to vegetation and wildlife at the site. Human activities
associated with the proposed land use for this parcel are expected to  limit the selection of Site
DP-03 as a primary habitat for many ecological receptors.
                                         2-43

-------
 Because the benchmark for human health risk is exceeded and to expedite reuse, the RAO for
 preventing direct contact with landfill  contents  must be satisfied by recommending either
 Alternative 4 or Alternative 5 for Site DP-03 in the OU 3 FS. Both of these alternatives also
 satisfy the RAOs for minimizing infiltration and controlling runoff and soil erosion. Alternative
 4  is less expensive but equally effective in satisfying the RAOs  as  Alternative 5.   The
 implementation of surface  controls  and  the  installation of a  soil cover at Site  DP-03 would
 constitute landfill closure and therefore make the site a potential candidate for delisting in the
 future.

 Therefore, Alternative  4 was the selected  remedy for  Site DP-03.   This alternative  was
 implemented as described in Section 2.9.  Actions at the OU 3 landfill sites were completed in
 April 1997.

 Site DP-04.   Under the  industrial/commercial  scenario, the baseline  human health  risk
 assessment estimated the highest cancer risk of 6.7E-05 for this landfill site, primarily because of
 the presence of Aroclor-1260. This  risk  value is above the California and USEPA acceptable
 benchmark value of l.OE-06.

 The results of the ecological risk assessment  indicated  a potential risk to burrowing mammals
 and their predators (e.g., bam owl), primarily because of the highly localized presence of Aroclor
 1260.  However, human activities associated  with the proposed land use for this parcel along
 with the disturbed nature of the site are expected to limit the selection of Site DP-04 as a primary
 habitat for many ecological receptors.

Because the benchmark for human health risk  was exceeded and to expedite reuse, the RAO for
preventing direct contact with landfill contents  must  be  satisfied  by recommending either
Alternative 4 or Alternative 5 for Site DP-04  in the OU 3 FS.  Both of these alternatives also
satisfy the RAOs for minimizing infiltration and controlling runoff and soil erosion. Alternative
4 is less expensive but equally effective in satisfying the RAOs as Alternative 5.  Therefore,
Alternative 4 was the recommended selected remedy for  Site DP-04  in the OU 3 FS.   The
implementation of surface controls and the installation of a soil cover at Site DP-04 would
                                         2-44

-------
  constitute landfill closure and therefore make the site a potential candidate for delisting in the
  future.

  Therefore, Alternative  4 was  the  selected remedy for Site DP-04.   This alternative was
  implemented as described in Section 2.9. Actions at the OU 3 landfill sites were completed in
  April 1997.

  Site LF-12.   Under the future resident scenario, the baseline human  health risk  assessment
  estimated the  highest cancer risk of 7.7E-07  for this landfill site, primarily because of the
  presence of dioxins found in some burn pits. This risk value is below the California and USEPA
  benchmark value of acceptable risk (i.e., risks calculated below this value would not require
  attention).

 The results of the ecological risk assessment indicated a potential risk to burrowing mammals
 and their predators (e.g., barn owl), primarily because of the highly localized presence of dioxins,
 lead, zinc, and  barium. However, human activities associated with the proposed land use for this
 parcel are expected to limit the selection of Site LF-12 as a primary habitat for many ecological
 receptors.

 In order to satisfy the RAOs for minimizing infiltration and controlling runoff and soil erosion.
 Alternative 3 was the recommended remedy for Site LF-12 in the OU 3 FS. Alternatives 1 and 2
 are not capable of satisfying these RAOs.  In addition, the implementation  of surface controN
 and cover rehabilitation at Site LF-12 would constitute landfill closure and  therefore make the
 site a potential candidate for delisting in the future.

 Therefore, Alternative 3  was the selected remedy for Site LF-12.   This alternative was
 implemented as described in Section  2.9. Actions at  the OU 3 landfill sites were completed in
 April 1997.

Site LF-14.    Under the  industrial/commercial  scenario, the baseline human health risk
assessment estimated the highest cancer risk of l.OE-05 for this landfill site, primarily because of

                                          2-45

-------
  the presence of cadmium values that are considered naturally occurring. Therefore, the probable
  health risks at Site LF-14 are expected to be lower, thereby reducing the importance of the RAO
  for preventing direct contact with landfill contents.

  The results of the ecological risk assessment indicated a potential risk to burrowing mammals
  and their predators (e.g., bam owl), because of the  localized presence of cadmium, lead, and
  pesticides. However, human activities associated with the proposed land  use for this parcel are
  expected to limit the selection of Site LF-14 as a primary habitat for many ecological receptors.

  In order to satisfy the RAOs for minimizing infiltration and controlling runoff and soil erosion.
  Alternative 3 was the recommended remedy for Site LF-14 in the OU 3 FS. Alternatives 1 and 2
 are not  capable of satisfying these RAOs.  In addition, the implementation of surface controls
 and cover rehabilitation at Site LF-14 would constitute landfill closure and therefore make the
 site a potential candidate for delisting in the future.

 Therefore,  Alternative 3 was the selected remedy  for  Site LF-14.   This  alternative  was
 implemented as described in Section  2.9.  Actions at  the OU 3 landfill sites were completed in
 April 1997.

 Site LF-44. The screening risk assessment identified no COPGs for this landfill  site. Therefore.
 there are no human health risks for direct contact with landfill contents and there is no potential
 for contaminant leaching. This practically eliminates the need to satisfy  any of the RAOs for
 Site LF-44.

The results of the ecological risk assessment suggested some potential ecological impacts at Site
LF-44 from physical disturbances. Some  stress on vegetation exists at the site as a result of
physical  disturbance related to former site activities.   However,  significant chemical risks to
vegetation or wildlife were not indicated by the site characterization data.

However, in order to restore the natural surface of the site, Alternadve 2 was recommended for
Site LF-44 in the OU 3 FS. The implementation of surface restoration and  institutional controls

                                          2-46

-------
  at Site LF-44 would constitute landfill closure and therefore make the site a potential candidate
  for delisting in the future.

  Therefore,  Alternative  2  was  the  selected remedy  for  Site LF-44.   This alternative was
  implemented as described in Section 2.9. Actions at the OU 3 landfill sites were completed in
  April 1997.

  SEDA. Under the future resident scenario, the baseline human health risk assessment estimated
  the highest cancer risk of 8.4E-05 for this  landfill site, primarily because of arsenic and
  chromium values that are considered naturally occurring. Therefore, the probable health risks at
  the SEDA arc expected to be lower, thereby reducing the importance of the RAO  for preventing
 direct contact with landfill contents.

 The results of the ecological risk assessment indicated a potential risk to burrowing mammals
 and their predators  (e.g., bam owl), because of the localized presence of several metals and
 dioxin/furan congeners.

 In order to satisfy the RAOs for  minimizing infiltration and controlling runoff and soil erosion,
 Alternative 3 was selected for the SEDA in the OU 3 FS. Alternatives 1 and 2 are not capable of
 satisfying these  RAOs.   In  addition,  the implementation of  surface controls and  cover
 rehabilitation at the SEDA would effectively produce a soil cover on the landfill with an average
 thickness of 1.6 feet based on  preliminary grading  plans.  Therefore,  Alternative 3  would
 constitute landfill closure and make the site a potential candidate for delisting in the future.

 Therefore, Alternative 3 was the selected remedy  for  the SEDA.   This alternative was
 implemented as described in Section 2.9.  Actions at the OU 3 landfill sites were  completed in
 April 1997.

 2.5.4.2       Detailed Description of the Landfill Site Preferred Alternatives.  The selected
 alternatives from the OU 3 FS  for the landfill sites (identified in Section 2.5.4.1) are described in
detail below.

                                         2-47

-------
 Sites DP-03 and DP-04.  Installation of Alternative 4 for Sites DP-03 and DP-04 includes the

 following specific activities:
        •       grading the existing soil cover to promote surface runoff and decrease infiltration
               of surface water into landfill wastes;

        •       restoration of existing soil cover;

        *       installation of drainage ditches  to prevent surface  water from running onto the
               sites;

        *       installation of a 2-foot-thick native soil cover to reduce the potential of exposure
               to contaminants;

        •       re-establishment of native plant species on the graded surface;

        0       implementation  of long-term groundwater monitoring  in  accordance with  an
               approved basewide long-term groundwater monitoring plan;

        0       installation  and maintenance  of site perimeter  fencing  to  control site  access
               including signage warning against unauthorized vehicular traffic;

        0       implementation of land use restrictions such as preventing construction  activities
              that would impair the integrity of the existing cover and preventing installation of
              monitoring  or injection wells  in the  site area  (except  where  required  for
              environmental purposes); and

       •      5-year site review to assess the effectiveness of the remedy.


Sites LF-12, LF-14, and the SEDA.  Installation of Alternative 3 for Sites LF-12 and LF-14

includes the following specific activities:
       •      removal of surface debris;                  '

       •      grading or  cutting of  the  surface to promote surface runoff  and decrease
              infiltration of surface water into landfill wastes;

       •      restoration of existing soil cover,

       •      installation of drainage ditches to prevent surface water from running onto the
              sites;


                                          2-48

-------
               re-establishment of native plant species on the graded surface;
        •      implementation  of long-term  groundwater monitoring  in accordance  with an
               approved basewide long-term groundwater monitoring plan;
        •      installation and  maintenance of site  perimeter  fencing to control site access
               including signage warning against unauthorized vehicular traffic;
        •      implementation of land use restrictions such as preventing construction activities
               that would impair the integrity of the existing cover and preventing installation of
               monitoring or injection wells in the  site  area (except where required for
               environmental purposes); and
        •       5-year site review to assess the effectiveness of the remedy.

 Site LF-44.  Contaminants  of potential concern were  not detected in  soil samples at LF-44.
 Installation of Alternative 2 for Site LF-44 includes the following specific activities:

        •      removal of surface debris and disposal at an off-site disposal facility;
        •      implementation of  long-term groundwater monitoring in  accordance with an
              approved basewide long-term groundwater monitoring plan;
        •      implementation of land use notifications identifying the area as an NFA site; and
        •      5-year site review to assess the effectiveness of the remedy.

Additional detail regarding the preferred action for the  landfill sites has been presented in the
Closure and Post-Closure Technical Plans for the landfill sites (Montgomery Watson, 1996b). A
contingency plan would be implemented should it be determined that the remedy is no longer
protective of  human health  and the  environment.   Contingency plans will  be described as
necessary as part of the operations and maintenance (O&M) documentation.

2.5,43        Cost  Analysis.   A  preliminary cost estimate was prepared for the selected
alternatives for each landfill site as part of the OU 3 FS process. Tables 6 through 11 summarize
the cost analysis for the preferred alternative for each site.

2.5.4.4        System  Implementation.   In an effort to  accelerate  the remedial  process, to
minimize present and future environmental risks, reduce potential impacts to groundwater,  and
                                          2-49

-------
  facilitate timely transfer of property to the community, cleanup activities have been initiated
  under the direction of the USAF, at some of the sites presented in this ROD. These accelerated
  actions were performed in  agreement with the RPMs including the USEPA, DTSC, Lahontan
  RWQCB, and USAF.  The accelerated  actions were performed at landfill Sites DP-03, DP-04,
  LF-12, LF-14, LF-44,  and  the SEDA as detailed in the Technical Plans for the landfill sites
  (Montgomery Watson, 1996b) and the Site Closeout Report for the landfill sites (Montgomery
  Watson, 1997c). The actions at the landfill sites began in June 1996 and were completed in April
  1997.  These actions arc summarized in Section 2.9  (Current Site Status).  The effectiveness of
  these remedies will be assessed as part of the ongoing O&M and long-term monitoring and will
  be the focus of the 5-year site review.
              Statutory Determinations for the Landfill Sites
 The selected remedies satisfy the statutory requirements of Section 121 of CERCLA, as amended
 by SARA, in that the following four mandates are attained:
        "      The selected remedies are protective of human health and the environment, will
              decrease  site  risks,  and will not create  short-term risk nor have  cross-media
              consequences.
        •      The selected  remedies comply with federal and  state requirements  that are
              applicable or  relevant and appropriate to  the remedial action such as chernical-
              specific ARARs, chemical-specific clean-up  standards,  and  action-specific
              ARARs.
       •      The selected remedies are cost-effective in its fulfillment of the  nine CERCLA
              evaluation criteria through remediation of the landfill sites in a reasonable period
              of time.
       •      The selected  remedies utilize  permanent solutions and  alternative treatment
              technologies  or  resource  recovery technologies,  to the  maximum extent
              practicable.

              Protection of Human Health  and the Environment  Protection of human
health and the environment at the OU 3 landfill sites is achieved by the selected remedy  for each
site by  reducing or eliminating the  potential  for direct contact with landfill contents and
minimizing infiltration.
 *
                                         2-50

-------
  2.5.5.2       Compliance with ARARs.  All pertinent ARARs identified for the OU 3 landfill
  sites (Table 4) will be met by the selected remedies.
               Cost Effectiveness. The USEPA, the USAF, and the State of California believe
  that the selected remedies fulfill the nine criteria of the NCP and provide overall effectiveness
  with respect to their costs.

  2.5.5.4        Utilization of Permanent Solution and Alternative Treatment (or Resource
  Recovery) Technologies to the Maximum Extent Possible.  The selected remedy represents, to
  the maximum extent to which permanent solutions and treatment technologies can be used, a
 cost-effective manner for remediating the OU 3 landfill sites.  The remedies selected provide the
 best balance of long-term effectiveness and permanence; reduction of TMV through treatment;
 short-term effectiveness; implementability and cost effectiveness.

 2.5.5.5       Preference for Treatment as a Principle Element The selected remedies will
 leave contaminants in place at the OU 3 landfill sites.  The size of the landfill sites and the
 heterogeneous nature of the wastes present, preclude a remedy in which contaminants could be
 excavated and treated effectively. Therefore, the selected remedies do not satisfy the preference
 for treatment as a principle element. However, the selected  remedies provide a cost-effective
 method to reduce the mobility of contaminants.

 2.6           TPH/VOC SITE SUMMARY

This  section  summarizes  the site  characteristics, risk assessment results, descriptions of the
alternatives evaluated, alternatives comparison, and the selection of the final remedies for the OU
3 TPH/VOC  sites  potentially requiring action (Sites WP-17,  FT-19a, FT-19b, FT-19c, FT-20
{soil], OT-51, and SS-59).  Because  potential  remedial  alternatives for Site QT-69 were
evaluated separately (IT, 1995a), this site is discussed separately in Section 2.7.
                                         2-51

-------
 2.6.1
Summary of TPH/VOC Site Characteristics and Risk Assessments
 The OU 3 TPH/VOC sites presented in this ROD were investigated and evaluated using the same
 rationale and investigative techniques, which included a  combination  of  soil-gas and soil
 sampling (soil borings, HydroPunch®, and monitoring wells).  Table 12 presents a summary of
 the OU 3 TPH/VOC site characterizations on a site-specific basis.

 Because of the similarities between these sites, they were initially investigated separately from
 the other OU 3 sites. The data was presented in the Remedial Investigation Summary Report for
 Soil Removal at Miscellaneous OU 3 Sites (M&E, 1994).   Detected  concentrations  were
 compared to "initial evaluation  criteria" to determine whether FS analysis to assess potential
 remedial  action was required.   The initial  evaluation  criteria were based on the Leaking
 Underground Fuel Tank (LUFT) Manual (LUFT Task Force, 1989) and were presented in the
 M&E RI Report as follows for soils less than 30 feet bgs (M&E, 1994):
              TPH
              benzene
              toluene
              ethylbenzene
              total xylenes
                    1,000       milligram per kilogram (mg/kg)
                    1,000       micrograms per kilogram (ug/kg)
                   50,000       ug/kg
                   50,000       ug/kg
                   50,000       ug/kg
The results of the M&E investigation of the TPH/VOC sites were summarized in the subsequent
OU 3 RI Report (Montgomery Watson,  1996a) in which a risk assessment was performed for
each site.

Six of these sites (WP-17, FT-19a,  FT-19b, FT-19c, OT-51, and SS-59) had TPH and BTEX
constituents detected in soil at concentrations exceeding the initial evaluation criteria for these
constituents.
         *

The risk assessments performed for the TPH/VOC sites indicated that Sites FT-19a, FT-19b, FT-
19c, and FT-20 [soil] had risks exceeding the California benchmark value of 1E-06; however, the
                                        2-52

-------
   risks were primarily  a result of the presence of inorganics which were considered naturally
   occurring.

   Two sites had groundwater affected by COPCs (Sites OT-51  and OT-69).  Site OT-51 had
   detectable concentrations of TPH (extractable as JP-4) and BTEX in the area of contaminated
   soil. A detailed risk assessment was not performed for groundwater at Site OT-51 because there
   is no completed exposure pathway  to receptors (i.e., groundwater is at approximately 120 feet
  bgs and is not used as a source for potable water, irrigation, etc., in  the vicinity of Site OT-51).
  Site OT-69 is defined  as the TCE and PCE detected in groundwater in monitoring wells in the
  flightline and operations support facilities area.  Site OT-69 has been addressed separately in
  Section 2.7.  The groundwater beneath Sites FT-19a, b, and c is affected by TCE; however, this
  contamination is addressed in the final ROD for OU 1 (Montgomery Watson, 1994).

  The site characterizations and risk assessments for the TPH/VOC sites requiring remedial action
  are summarized below.  Additional details  regarding  the  site characterizations  and risk
  assessments are presented in the OU 3 RI/FS reports (Montgomery Watson, 1996a and 1997a).

 2.6.1.1       Site WP-17.  Site WP-17 is located near Buildings 551 and 552 in the  central
 portion of the base. The site consists of a petroleum, oil, and lubricant (POL) leachfield used for
 disposal of waste  POLs from vehicle  maintenance and  a  fuels laboratory.  The following
 subsections summarize the site characterization and risk assessment for Site WP-17.

 Site Characterization.  To characterize Site WP-17, M&E  performed investigation activities
 including a  historical records  review, a soil-gas survey, and soil boring installation. Subsurface
 samples from the soil  borings were collected  and analyzed.   Data gathered were  used  by
 Montgomery Watson to perform the fate and transport modeling and were also incorporated into
 the baseline risk assessment.

Elevated organic vapor analyzer (OVA) readings observed during the soil-gas survey were used
to locate the four initial soil  borings.  Soil-gas survey  results indicated pronounced  0,-CO,
inversions at Site WP-17. The pronounced 0,-CO, inversions could indicate that  aerobic

                                         2-53

-------
  degradation has occurred and may be occurring.  Localized elevated (>200 parts per million
  [ppm]) methane  levels in locations with strong  Oj-CO,  inversion suggested  that anaerobic
  degradation of constituents may be occurring in some areas (M&E, 1994).

  Eleven soil borings were advanced to further investigate the soil-gas results and to assess the
  presence of POL and fuel constituents at the site. TPH and VOCs were detected in surface and
  subsurface samples collected  from borings  throughout  the  site.   Based on the soil boring
  analytical results, it was concluded that detected concentrations exceeded the initial evaluation
 criteria (see Section 2.6.1) for TPH and BTEX in the boring adjacent to the oil-water separator at
 WP-17 (SBS-06). Concentrations exceeding these criteria were not detected deeper than 25 feet
 bgs at this boring. Several of the other borings in  the vicinity of the former leachfield showed
 detectable concentrations of hydrocarbons and  VOCs; however, these were lower than the
 evaluation criteria. Based on an assumed depth to groundwater of  120 feet bgs, vadose zone
 modeling results indicated that  under the base case  scenario (best estimate of site conditions for
 calibrated model), benzene in the soil water (i.e., the water distributed between the soil particles
 in the vadose zone) will not reach the water table and the soil water concentrations will reduce to
 less than  1.0 micrograms per liter (ng/L) in  100 years. The TPH constituents detected at Site
 WP-17 arc less mobile than benzene; therefore, petroleum hydrocarbons constituents detected at
 Site WP-17 are not expected to adversely impact groundwater.

 Risk Assessment. As described in Section 2.2.2, a baseline risk assessment was performed for
 Site WP-17 for which risk assessment scenarios were evaluated based on the proposed reuse of
 the land parcel in which the site is located (USAF,  1993).  The scenario evaluated for this site
 was the construction worker (potential subsurface soil exposure).  This baseline human health
 risk assessment estimated the highest excess lifetime cancer risk of 9.7E-07, primarily because of
 total chromium. Although this  is below the benchmark values for risk assessment, because the
 initial evaluation criteria (based on the LUFT Manual; see Section 2.6.1) for TPH and BTEX
 were exceeded in soils at the site, the site was assessed in the OU 3 FS.

The results of the ecological risk assessment indicated that Site WP-17 was not an area of
potential ecological concern because of the lack of suitable habitat for environmental receptors.

                                         2-54

-------
 2.6.1.2       Sites FT-19a and FT-19c.  Sites FT-19a and FT-19c  are fire  training areas
 located north of the Crosswind/Secondary Runway (Figure 2). Site FT-19a is an older training
 area located underneath a formerly  concrete-lined training area.  In addition to the main area,
 smaller areas, also used for fire training, are located south and east of the main training area. The
 smaller  areas  make  up Site FT-19c.    The  following subsections  summarize  the  site
 characterization and risk assessment for Sites FT-19a and FT-19c.  Groundwater beneath Site
 FT-19 is considered part of OU 1.

 Site Characterization. To characterize Sites FT-19a and FT-19c, M&E performed investigation
 activities including a soil-gas survey, soil boring installation, composite sample dioxin testing
 (with a risk assessment), biological testing, and removal activities (with associated confirmation
 sampling).   Samples  from  the  soil borings and confirmation samples  were collected and
 analyzed.  Data gathered were used by Montgomery Watson to perform the fate and transport
 modeling and were also incorporated into the baseline risk assessment.

 Concentrations of VOCs in shallow  (7 feet bgs) soil-gas points were identified throughout the
 site.  Thirty-eight soil borings were advanced to investigate the fire training rings and to further
 investigate the soil-gas results.  Four composite samples from surface soil samples throughout
 the site showed detectable concentrations of some dioxin constituents. Based on the application
 of total equivalence factors to the dioxin results, M&E reported that the  toxicity equivalents
 (TEs) were below action levels (M&E, 1994). TPH, VOCs, and SVOCs were detected in surface
 and subsurface samples in borings throughout the site.   Based on the  soil boring analytical
 results, it was concluded that petroleum concentrations exceeded the initial evaluation criteria for
TPH and BTEX (based on the LUFT Manual; see Section 2.6.1) in several locations at the sites.
Biological testing suggests that, although some aerobic biological activity may be occurring at
the site, very little  anaerobic biological activity  was occurring (M&E,  1994).  Vadose zone
modeling results indicated that under the base case scenario (best estimate of site conditions for
calibrated model), benzene in the soils at  Sites FT-19a and FT-19c will not adversely affect
groundwater quality. However, under die base case scenario, model results predicted that TCE
present in the vadose zone at Site FT-19c would reach the water table  within 75 years with

                                         2-55

-------
  concentrations increasing to  greater than  400 milligrams  per liter (mg/L) within 100  years.
  Because FT-19 overlies the OU  1  TCE plume and is considered a potential source for this
  contamination, the modeling of the groundwater beneath this area has been considered separately
  as part of OU  1. The proposed OU 1 treatment system design, including modeling scenarios and
  results, is presented in detail in the OU 1 Pre-Design Study (Montgomery Watson, 1995b).

 Risk Assessment As described in Section 2.2.2, a baseline risk assessment was performed for
 Sites FT-19a and FT-19c for which risk  assessment scenarios were  evaluated based on the
 proposed reuse of the land parcel in which the site is located (USAF, 1993).  The scenarios
 evaluated for these sites included:  industrial/commercial, trespasser/visitor, construction worker
 (potential surface soil exposure), and construction worker (potential subsurface  soil exposure)
 This baseline human health risk assessment  estimated the highest lifetime cancer risk of 4.0E-06
 for Site  FT-19a, primarily because of arsenic under a construction worker (subsurface soils)
 scenario. Although this is above the benchmark values for risk assessment, the arsenic at the site
 is considered naturally occurring. However, because the initial evaluation criteria (based on the
 LUFT Manual; see Section 2.6.1) for TPH and BTEX were exceeded in soils at the site, the site
 was assessed in the OU 3 FS.

 The baseline human health risk assessment estimated the highest lifetime cancer risk of 3.UE-06
 for Site  FT-19c,  primarily because of chromium  under  an industrial/commercial scenario.
 Although this is above the benchmark values for risk assessment, the chromium at the site is
 considered naturally occurring  and within  background  ranges.  However,  because  the initial
 evaluation criteria (based on the LUFT Manual; see Section 2.6.1) for TPH and BTEX were
 exceeded in soils at this site and vadose zone modeling indicated TCE in soils may adversely
 affect groundwater quality, the site was assessed in the OU 3 FS.

The results of the ecological risk assessment indicated that Sites FT-19a and FT-19c are not areas
of potential ecological concern because of the lack of suitable habitat  for environmental
receptors.
                                         2-56

-------
  2.6.1.3       Site FT-19b.  Site FT-195 is the Medical Waste Disposal Area adjacent to Site
  FT-19c (Figure 2).  The site is located approximately 800 feet south of the main fire training area
  (Site FT-19a). Medical waste was discovered at the site during soil-gas investigations conducted
  in the Site FT-19 area in 1987 (Montgomery Watson, 1996a).  Because of the unique nature of
  Site FT-19b, it  was investigated separately from Sites FT-19a and FT-19c.  The following
  subsections summarize the site characterization and risk assessment for Site FT-19b.

  Site Characterization. To characterize Site FT-19b, M&E performed investigation activities
  including a soil-gas survey, soil boring installation, composite sample dioxin testing (with a risk
  assessment), biological testing, and disposal area assessment  with shallow test pits.  Samples
  from the soil borings and confirmation samples were collected and analyzed. Biological testing
  and composite dioxin sampling was performed over the Site FT-19 area as a whole (sites a,  b,
  and c).  Data gathered were used by Montgomery Watson to perform the fate and  transport
 modeling and were also incorporated into the baseline risk assessment.  It was found that the soil
 beneath the medical  wastes was affected by hydrocarbons and VOCs similar to Sites FT-19a and
 FT-19c as detailed below.

 Concentrations of VOCs in shallow (7 feet bgs) soil-gas points were identified throughout the
 site. Eleven soil borings were advanced to further investigate the soil-gas results and assess the
 presence of fuel and VOC constituents at the site.  TPH, VOC, and SVOCs were detected in
 surface and subsurface samples in borings throughout  the site.  Based on the soil boring
 analytical results, is was concluded that petroleum concentrations exceeded the initial evaluation
 criteria (based on the LUFT Manual; see Section 2.6.1) for TPH and BTEX in two borings  at the
 site. TPH was detected to a maximum depth of 25 feet bgs.   Vadose zone modeling results
 indicated that under the base case scenario (best estimate of site conditions for calibrated model),
 the most mobile constituents in the soils at Site FT-19b will not adversely affect groundwater
 quality. The disposal area assessment and test pits revealed that medical wastes were present
 primarily in the surface soil.

It is believed that the TPH and VOC constituents detected at the site are related to activities at
Sites FT-19a and FT-19c. However, the summary of the site  characterization at Site  FT-19b

                                         2-57

-------
  have been presented separately from Sites FT-19a and FT-19c to be consistent with the original
  data presentation in the M&E RI  Report (M&E,  1994) and  because  of the  unique site
  characteristic of the medical waste being present. The approximate area where medical wastes
  were observed was mapped by M&E (M&E. 1994) and is presented in the OU 3 RI Report
  (Montgomery Watson, 1996a). The medical wastes at this site have been removed and disposed
  of at an off-site disposal facility under the Full Service Remedial Action (FSRA) activities.

  Risk Assessment As described in Section 2.2.2, a baseline risk assessment was performed for
  Site FT-19b for which risk assessment scenarios were evaluated based on the proposed reuse of
  the land parcel in which the site is located (USAF,  1993). The scenarios evaluated for this site
  included:  industrial/commercial, trespasser/visitor, construction worker (potential  surface soil
  exposure), and construction worker (potential subsurface soil exposure).  This baseline human
  health risk  assessment estimated the highest excess.lifetime cancer risk of 5.2E-06,  primarily
 because of incidental ingestion of beryllium and nickel in soils under the industrial/commercial
 worker scenario. Although this is above the benchmark value for risk assessment, the beryllium
 and nickel detected at the site were considered naturally occurring and within background ranges.
 However, because the initial evaluation criteria (based on the LUFT Manual; see Section 2.6.1)
 for TPH and BTEX were exceeded in soils at the site, remedial actions were considered in the
 OU 3 FS for the TPH and VOCs detected at Site FT-19b.

 The results  of the ecological risk assessment indicated that Site FT-19b was not  an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.
2.6.1.4
Site FT-20 (Soil)
Site FT-20 (soil) is the reported location of an abandoned fire training area (Figure 2).  The site is
located in an unpaved area south of the STP percolation ponds (Site WP-26). Site FT-20 (soil) is
the designation for the soil in this area. The affected groundwater in this vicinity is designated as
FT-20 (groundwater) which is currently an OU 2 site; therefore, it is not addressed further in this
ROD.  The following subsections summarize the site characterization and risk  assessment for
Site FT-20 (soil).
                                         2-58

-------
 Site Characterization.  To characterize Site FT-20 (soil), an  active soil-gas program was
 conducted, five borings were installed, and surface and subsurface (soil boring) samples were
 collected and analyzed. Compiled data were used to perform fate and transport modeling and
 were also incorporated into a baseline risk assessment.

 TCE in shallow soil-gas was detected sporadically throughout the site.  Five soil borings were
 installed to depths of 15 feet to investigate soil-gas anomalies and  reported bum areas.  Arsenic,
 barium, lead,  mercury, zinc,  and hydrocarbons  were detected  sporadically in surface and
 subsurface samples above background. Although TCE was detected in the soil-gas, no  VOC
 contamination was found in the surface or subsurface soil samples. Hydrocarbons were detected
 in two surface soil samples at concentrations of 4,200 mg/kg and 8,900 mg/kg.  Vadose zone
 modeling results showed that even under the most conservative  conditions, the most mobile
 constituent will not migrate deeper than 20 feet below the bottom of the disturbed areas within
 100 years.  Therefore, the less mobile contaminants detected at  this site  are  not expected to
 migrate significantly below the bottom of the disturbed areas and would pose no threat to the
 groundwater.

 Risk Assessment. As described in Section 2.2.2, a baseline risk assessment was performed for
 Site FT-20 for which risk assessment scenarios were evaluated based on the proposed reuse of
 the land parcel  in which the site is located (USAF, 1993).  The scenarios evaluated for this siie
 included: industrial/commercial,  trespasser/visitor, construction worker  (potential surface soil
 exposure), and construction worker (potential subsurface soil exposure).  This  baseline human
 health risk assessment estimated  a highest excess lifetime cancer risk  of 4.0E-05, primarily
 because of  arsenic under an industrial/commercial scenario.  Although  this is  above the
 benchmark value for risk assessment, the arsenic at the site is considered naturally occurring and
 within  the  background  range.    However,  because  elevated concentrations of petroleum
 hydrocarbons were detected in surface samples, the site was assessed in the OU 3 FS.

The results of the ecological risk  assessment  indicated that Site FT-20 (soil) is not an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.

                                         2-59

-------
  2.6.1.5       Site OT-51/SS-59.  The location of Site OT-51 is shown on Figure 2.  The site
  consists of five engine test cells.  The section of the site designated as OT-51  is located near
  engine test cell Facilities 799 and 807. Periodic jet fuel spills have reportedly occurred at the site
  during testing. The section of the site designated as SS-59 is located near Facility 819.  Site SS-
  59 is the reported location of an 8,000-gallon jet fuel spill.  The two remaining test cells are
  located in revetments  south of Site  SS-59.   Because  the sites are closely related, they were
  combined  for investigation  activities.   The   following  subsections  summarize  the  site
  characterization and risk assessment for Site OT-51/SS-59.

 Site Characterization. To characterize Site OT-51/SS-59, M&E performed investigation and
 removal activities including soil boring and monitoring well installation, and UST and septic
 system removal.  Surface and subsurface samples from the soil borings were collected and
 analyzed.   Based on preliminary  analytical  data collected  by M&E,  Montgomery  Watson
 performed subsequent investigations at a "hot spot" identified at Site OT-51.  The additional
 investigation activities at Site  OT-51  included: subsurface soil sampling during installation of
 HydroPunch® borings, soil borings, and monitoring wells; downhole geophysics; aquifer testing;
 and  groundwater sampling.   Data  gathered  from the  M&E and  Montgomery Watson
 investigations were used by Montgomery Watson  to perform the fate and transport modeling and
 were also incorporated into the baseline risk assessment.

 The results of the M&E investigations at  Site OT-51/SS-59 are presented in detail in the M&E
 RI Report (M&E, 1994) and arc summarized  in the OU 3 RI Report (Montgomery Watson,
 1996a). Based on the initial evaluation criteria presented in the M&E RI Report (based on the
 LUFT Manual; see Section 2.6.1), it was concluded that no further action was warranted at the
 soil ocrm at Facility 807 or the two  revetment engine test cells  south of SS-59.  However,
consideration of potential remedial  action warranted at Facility 819 (Site SS-59) and  further
investigation was required at the soil berm at Facility 799 (Site OT-51) to define the extent of
constituent concentrations exceeding the initial evaluation criteria for TPH and BTEX.
                                         2-60

-------
 Subsequent investigations at Site OT-51, performed by Montgomery Watson to fill general data
 needs, included collection of subsurface soil samples and groundwater sampling. Results of this
 investigation showed  that detectable concentrations  of  TPH  and BTEX are  present in the
 groundwater in the area of the hot spot identified during  the M&E investigations.  Monitoring
 wells  installed  upgradient  (WZ-05)  and  downgradient  (MW-1) showed  no  detectable
 concentrations of TPH (extractable as JP-4) or BTEX during the September  1994 sampling
 event.  However, TPH (extractable as JP-4) and BTEX were detected in monitoring wells WZ-04
 and WZ-06 (installed in the area of the hot spot), and in crossgradient HydroPunch® borings
 SBS-25 and SBS-27.   Soil  sampling confirmed  the elevated hydrocarbon  constituent
 concentrations reported by M&E with the highest concentrations of TPH (extractable as JP-4)
 and BTEX occurring in samples collected from WZ-04.  Soil sampling  from  the M&E and
 Montgomery Watson investigations confirmed that the elevated TPH and VOC concentrations in
 the soil are primarily limited  to the area of the hot spot.   Occasional hits of TPH  and BTEX
 compounds are present in some surrounding borings, with the highest detected  concentrations
 occurring at depths of approximately 100 feet bgs. Vadose zone modeling results indicated that
 under the base'case scenario (best estimate of site conditions for calibrated model),  benzene  in
 the soil will continue to reach the water table over the 100 years modeled.  Based on the fact that
 groundwater is affected by TPH and VOCs beneath Site OT-51,  and vadose zone modeling
 results, the affected groundwater was also modeled  for the site using benzene as an indicator
 compound.  Results of this modeling indicated that over 50 years, the migration of benzene
 leaching from the vadose zone will be limited. The base case scenario indicated that the leading
 edge of a 0.5  ug/L benzene plume  boundary would migrate  approximately 400 feet from the
 source area.

 After the completion of the remedial investigations at the site in September 1994, subsequent
 sampling rounds were performed  as  part  of the  basewide long-term  monitoring  plan  in
 September  1995, January  1996, May 1996, October 1996, February  1997, and July 1997
 (Montgomery Watson, 1996c,d,e,f; Montgomery Watson, 1997d,e,f). All four monitoring wells
had detectable concentrations of TPH and  BTEX  in the September 1995 sampling event.
Concentrations of most of these compounds increased in subsequent sampling rounds, with peak
values  in January  and  May 1996,  after which concentrations generally  decreased.   BTEX

                                        2-61

-------
 compounds were near or below detection limits during the last sampling event (July 1997), and
 TPH values ranged from <50 mg/L (non-detect) to 120 mg/L.

 Risk  Assessment  Preliminary Remediation Goal  (PRO) screening in accordance with the
 methodology presented in the OU 3 RI indicated that further human health risk analysis was not
 required because confirmed contamination was at depths that would  not affect receptors in the
 risk assessment scenarios.  However, because the initial evaluation criteria (based on the LUFT
 Manual as presented in the M&E RI Report [M&E, 1994]) for TPH and BTEX were exceeded in
 soils at the site and because groundwater quality is affected, the site  was assessed in the OU 3
 FS.

 The results of the ecological risk assessment indicated that Site OT-51/SS-59 is not an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.

 2.6.2       • Description of TPH/VOC Site Alternatives

 Based  on the results of remedial  investigations, it was determined  that remedial  action  was
 potentially necessary at OU 3 TPH/VOC Sites WP-17, FT-19a, FT-19b, FT-19c, OT-51. and SS-
 59 to protect groundwater quality. An FS analysis was performed for these sites as described for
 the landfill sites in Section 2.5.2.  Alternatives were developed and evaluated for the TPH/VOC
 sites as a group because of the similarity between the sites with respect to contaminant type,
 distribution, site characteristics,  and potential actions.  The RAOs established for the OU 3
TPH/VOC sites are summarized below:

Soil Site?. The RAOs developed for the soils  at the TPH/VOC sites are summarized below.

Protection of Human Health
             Prevent human exposure to soil having 1E-04 to 1E-06 excess cancer risk from all
             carcinogens.
             Prevent human exposure to soil having noncarcinogens in excess of reference
             doses (RfDs).
                                        2-62

-------
  Protection of the Environment

        •     Reduce the TMV of the contamination in unsaturated soil to reduce the potential
              migration of contaminants to groundwater.
              Remove, to the extent practical, the COPCs detected in unsaturated soils to meet
              or exceed the remediation goals discussed below.

 To protect  groundwater quality,  remediation goals  for the BTEX and TPH  in soils  were
 determined in the FS based on the LUFT Field Manual (LUFT Task Force, 1989) by completing
 the scoring system presented in the LUFT manual for a general site at GAFB.  Figure 9 presents
 the remediation  goals for TPH and BTEX in the form of depth-specific levels relative to the
 groundwater table. The depth to groundwater for the TPH/VOC sites is approximately 120 feet
 bgs.

 The LUFT manual does not provide a method for determining remediation goals for TCE (the
 primary constituent of concern for Site FT-19c); therefore, remediation goals were  determined
 using SESOIL modeling as detailed in the OU 3 FS Report (Montgomery Watson,  1997a).  A
 graphical presentation of the levels of TCE that must be obtained are presented on Figure 10.

 Based on these remediation goals, a remedy would be  implemented and operated until the mass
 of contaminants  remaining was such that no impact to groundwater was anticipated.  Prior  to
 closure of a TPH/VOC site for which a remedy has been implemented, confirmation samples
 (soil and vapor) would be collected as necessary to demonstrate that soil cleanup levels presented
 on Figures 9 and 10 are achieved.  If contamination remaining in soil can be demonstrated  to
 have  no impact  to groundwater  quality,  concentrations remaining in soil may exceed the
 numerical values  presented in Figures 9 and 10, and the site may be considered for closure.

 Groundwater Sites.  There are currently no complete  exposure pathways for the contaminated
groundwater at Site OT-51.  Groundwater in the site area is not  used as a source of domestic,
industrial, or agricultural  supply.  Therefore, there is currently no danger of adverse exposure to
either base personnel or residents.  In  addition, the groundwater does not reach the ground
                                        2-63

-------
 surface within the base boundaries; therefore, there is no known current exposure pathway to
 ecological receptors.


 However, in accordance with ARARs which  call for  protection of groundwater resources,

 groundwater at Site OT-51 should be protected.   Therefore, the RAO  for groundwater is as
 follows:


        •      Reduce the dissolved concentrations for identified COPCs in the groundwater
              beneath Site OT-51 so that the most stringent concentrations identified in the
              ARARs are not exceeded (maximum contaminant levels  [MCLs], secondary
              MCLs, or quantifiable taste or odor criteria).


 The groundwater numerical cleanup standards for Site OT-51 are presented on Table 13.


 Remedial alternatives were developed for the TPH/VOC sites  from an analysis of remedial

 technologies  as part of the OU 3 FS (Montgomery Watson, 1997a).  The alternatives, with their

 components,  are presented in the following sections as applicable for soil and groundwater.


 Soil Alternatives. Four remedial alternatives were  developed for the TPH/VOC-affected soils

 from an analysis of remedial technologies as part of the OU 3 FS (Montgomery Watson, 1997a).
The four alternatives, with their components, are as follows:

      Alternative 6  (No Action for Soil)
             1) Groundwater Monitoring
             2) 5-Year Site Review

      Alternative? (Removal/Disposal)
             1) Removal of Contaminated Soils
             2) Transport of Soils to Off-Site Treatment/Disposal Facility
             3) .Surface Restoration

      Alternatives (Soil Vapor Extraction [SVE])
             1) Installation of SVE System to Remediate Soils
             2) Groundwater Monitoring
             3) Access Restrictions
             4) Land Use Restrictions
             5) 5-Year Site Review
                                        2-64

-------
        Alternative 9 (Bioventing)
               I) Installation of Bioventing System to Remediate Soils
               2) Groundwater Monitoring
               3) Access Restrictions
               4) Land Use Restrictions
               5) 5-Year Site Review


 Groundwater Alternatives. Two remedial alternatives were developed for TPH/VOC-affected

 groundwater at Site OT-51 from an analysis of remedial technologies as part of the OU 3 FS

 (Montgomery Watson,  1997a).  The alternatives, with their components, are as follows:


       Alternative 10 (No Action for Groundwater)
              1) Groundwater Monitoring
              2) 5-Year Site Review

       Alternative 11 (Oxygen Enhanced Bioremediation)
              1) Land Use Restrictions
              2) Use  of an oxygen-releasing chemical (i.e.,  Oxygen  Release  Compound
                 [ORCJ®  or  hydrogen  peroxide [rLOJ)  in existing wells  if  COPCs  in
                 downgradient monitoring wells do not meet groundwater numerical  cleanup
                 standards (Table 13) within a sufficient time frame
              3) Groundwater Monitoring
              4) 5-Year Site Review


 2.6.2.1        Alternative 6:   No Action for SoiL   As required by the NCP, the no action

 alternative serves as a baseline against which other TPH/VOC soil alternatives are compared.  Its
 components include groundwater monitoring and the 5-year site review.


 Groundwater monitoring at the  OU 3 TPH/VOC sites would be part of an approved basewide

 long-term monitoring plan for GAFB. Selected monitoring wells at each site would be sampled

 annually, semi-annually, or quarterly, to determine if TPH/VOC contaminants are leaching to the

 groundwater.  Additional monitoring wells may be required to satisfy this monitoring component
 (i.e., at Site OT-51).


The no-action alternative would leave TPH/VOC-affected soils in place with no closure activities

undertaken; however, natural degradation of the TPH and VOCs would  occur.   Because

contaminants would remain on site, a site review would be conducted every 5 years as required


                                        2-65

-------
  by CERCLA.  The purpose of the 5-year site review and long-term monitoring would be to
  assess the effectiveness of the alternative.

  2.6.2.2       Alternative   7:    Removal/Disposal.    Alternative  7  includes  removal  of
  contaminated soils, transport to an off-site treatment/disposal facility, and surface restoration.

  For this alternative, backhoes and dump trucks would be used to remove affected soils. Surface
  restoration  would  involve importing clean fill  and restoring  the excavated area to a level,
 compacted surface.  Affected soils would be transported to the off-site treatment/disposal facility
 and clean fill would be imported with dump trucks.  Some demolition and/or cutting of existing
 concrete pads would be required (i.e., at Site SS-59).

 It is assumed that, after the contaminated soils are removed from the site, there would be closure
 on the site and continued groundwater monitoring would not be conducted and the 5-year site
 review would not be required.

 2.6.23      Alternative 8:   Soil Vapor Extraction.  Alternative 8 consists of using SVE  to
 remediate soil  with  confirmation sampling, groundwater  monitoring, land use and  access
 restrictions, and 5-year site review.

 SVE is a soil remediation technology that  uses vacuum blowers to pull large volumes of air
 through contaminated soil. The air flow sweeps out the soil gas, causing desorption of volatile
 contaminants from the soil into the vapor phase.  A schematic of a typical SVE system design  is
 presented in Figure 11.

 SVE for soil would be achieved using a series of extraction vents. Monitoring points would be
installed for soil vapor sampling to facilitate  a pilot test  study at the site  and  for subsequent
system evaluation. A schematic for a typical monitoring point and vapor sampling apparatus is
presented on Figure 12.
                                         2-66

-------
  To evaluate system performance for this alternative, confirmation samples would be collected
  and  groundwater monitoring would be performed.   Confirmation sampling  to  determine
  completion of the remediation could include soil and vapor.

  In addition,  land  use and access restrictions would  be employed until the remediation is
  confirmed to be complete. Land use restrictions would prohibit disturbance of affected soils and
  restrict installation  of wells for use  other than  groundwater monitoring.  Access restrictions
  would protect the remedy while in place and would be achieved through fencing and/or standard
  security procedures minimizing access from unauthorized personnel.  When the remediation is
  complete, the restrictions described above would be reassessed by the appropriate regulatory
  agencies as part of the 5-year site review. The purpose of the 5-year site review and monitoring
  would be to assess the effectiveness  of the alternative.

 2.6.2.4       Alternative 9:  Bioventing.  Alternative 9 consists of using in situ bioventing to
 remediate  soil with confirmation  sampling, groundwater  monitoring, land use  and access
 restrictions, and 5-year site review.

 Bioventing uses  forced aeration to stimulate soil-indigenous  microorganisms to aerobically
 metabolize organic compounds in unsaturated soils.  Depending on air flow rates, VOCs may be
 simultaneously removed through volatilization. A schematic of a typical bioventing system is
 presented in Figure 13.

 To evaluate system performance for this alternative, confirmation samples would be collected
 and groundwater monitoring  would  be  performed.  Confirmation sampling to determine
completion of the remediation could include soil samples and vapor samples.

In addition, land use and access restrictions (as described in Section 2.6.2.3), and 5-year site
review would be employed until remediation is confirmed complete as described for Alternative
8.
                                         2-67

-------
 2.6.15       Alternative 10:  No Action for Groundwater. As required by the NCP, the no
 action alternative serves as a baseline against which other TPH/VOC groundwater alternatives
 are compared. Its components include groundwater monitoring and the 5-year site review.

 Selected monitoring wells would be sampled annually, semi-annually, or quarterly, to monitor
 constituents present in the groundwater. Additional monitoring wells may be required to satisfy
 groundwater monitoring requirements.

 The no-action alternative would leave TPH/VOC-affected groundwater in place with no closure
 activities undertaken.  Because contaminants would remain  on site, a site review would be
 conducted every 5 years as  required by CERCLA. The groundwater monitoring and 5-year site
 review would be used to assess the effectiveness of the alternative.

 2.6.2.6       Alternative 11: Oxygen Enhanced Bioremediation. Alternative 11 consists of
 land  use restrictions, use of oxygen-releasing chemicals (i.e., ORC® or H,O,) in  existing
 monitoring wells if  COPCs  in downgradient monitoring wells do not  meet groundwater
 numerical cleanup standards (Table  13) within a sufficient time frame, groundwater monitoring,
 and 5-year site review.

 With this alternative, the implementation of land use restrictions at the site would restrict access
 to  the affected groundwater and  prohibit disturbance of  existing monitoring  wells and
 appurtenances.  Administrative measures would be taken to ensure that groundwater is not used
 for domestic uses (i.e., drinking or irrigation).

The top portion of the groundwater would be oxygenated through the use of oxygen-releasing
chemicals (i.e., ORC® or H,O,)  in the existing monitoring wells  to  accelerate  natural
biodegradation. ORC® is a fine, insoluble magnesium peroxide compound that slowly releases
oxygen when it is activated by moisture.  The oxygenation would enhance the degradation of
fuels and VOCs by naturally occurring aerobic microorganisms. ORC® is a passive process
which does not disturb the hydraulics of the plume.  Installation would consist of installing an
appropriate number of inert  filter socks containing the ORC®  compound into the groundwater

                                        2-68

-------
 via the existing monitoring wells. The ORC® socks would require replacement every 6 to 12
 months, depending on the concentrations of constituents in the groundwater.

 Similarly, H2O2 can be used to oxygenate the groundwater by injecting a dilute solution into the
 contaminated groundwater zone.  For  comparison  purposes, the discussion  that  follows,
 including the cost analysis, assumes the use of ORC®.

 The groundwater monitoring and 5-year site review would be used to assess the effectiveness of
 the alternative.

 Subsequent to the  remedial investigations  at  Site OT-51, groundwater at the site has been
 routinely monitored  as  part  of the  Basewide Long-Term  Groundwater  Monitoring Plan
 (Montgomery Watson, 1995c and  1996c).  The groundwater data collected since September 1995
 at Site OT-51 as part of the long-term groundwater monitoring effort (Montgomery Watson,
 1996d,e,f; 1997d,e,f) have indicated that the COPCs in groundwater increased slightly and then
 began decreasing.  It is expected that the plume will be below detectable levels of benzene in 5
 years. Under this alternative, if subsequent rounds of long-term monitoring do not continue to
 show the trend of decreasing levels of COPCs, the contingent task of installation of the oxygen-
 releasing chemicals described above would be implemented.

 2.63        Summary of Comparative Analysis of Alternatives for the TPH/VOC Sites

The remedial alternatives developed were analyzed in detail using  the nine evaluation  criteria
required by the NCP as detailed in Section 2.5.3 for the landfill sites.

The resulting strengths and weaknesses of the  alternatives were then weighed to identify the
alternative providing the best  balance  among  the nine criteria.   Table  14  summarizes this
comparison.
                                         2-69

-------
 '2.6 J.I       Overall Protection of Human Health and the Environment This criterion was
 defined in Section 2.5.3.1 for the landfill sites. The comparative analysis for this criterion for the
 TPH/VOC sites is presented below.

 Soil:
 Alternative 6: This alternative does not provide any direct protection of human health arid the
 environment at any of the TPH/VOC soil sites because no cleanup activities are undertaken.

 Alternative 7:  The overall protection of human health and the environment is high at  the
 applicable sites (FT-20 [soil] and SS-59).   This alternative removes  the  potential for direct
 contact with TPH/VOC-affected soils through removal, treatment, and disposal, and reduces  the
 potential for further leaching to the groundwater.

 Alternative 8: The overall protection of human health and the  environment is  high at  the
 applicable site (FT-19c).  This alternative would reduce the levels of TPH/VOC constituents in
 soils to below remediation goals.

 Alternative 9:  The overall protection of human health and the  environment is  high at the
 applicable sites (WP-17, FT-l9a, FT-19b, and OT-51).  This alternative would reduce the levels
 of TPH constituents in soils to below remediation goals.

 Groundwater (Site OT-51):
 Alternative 10:  This alternative does not provide any additional  direct  protection of human
 health and the environment because no enhanced remedial activities are undertaken and access to
 the affected  groundwater is not restricted. The process of natural attenuation would occur.

Alternative  11:   This  alternative  provides overall  protection  of human  health  and the
environment through land use and deed restrictions prohibiting installation of domestic supply
wells until remediation can be demonstrated.  This alternative enhances natural degradation  of
contaminants.
                                          2-70

-------
 2.6.3.2       Compliance with ARARs,  The definition of ARARs and this criterion  was
 presented in Section 2.5.3.2 for the landfill sites.  Final ARARs for the OU 3 landfill sites were
 established through discussions between the Lahontan RWQCB, DTSC, USEPA, and USAF. A
 listing of agreed upon federal and state laws and regulations that are ARARs for the  OU 3
 TPH/VOC sites is provided in Table 15.

 Soil:
 Alternative 6:  May not comply with all ARARs at all TPH/VOC sites because the existing
 contamination remains in place with no active remediation to achieve cleanup goals.

 Alternative 7: The active removal of contaminated soils and subsequent appropriate disposal is
 expected to comply with the ARARs for TPH/VOC sites.

 Alternative 8: The active remediation of contaminated soils through S VE is expected to comply
 with the ARARs  for TPH/VOC sites.

 Alternative 9: The active remediation of contaminated soils through bioventing is expected to
 comply with the ARARs for TPH/VOC sites.

 Groundwater (Site OT-51):
 Alternative 10:   May not comply with all ARARs for groundwater because no enhanced
 remediation of the groundwater plume is undertaken. Although natural attenuation processed
 would occur, the state considers movement of the plume as a discharge which violates  State
 Water Resources Control Board Resolution 68-16; an ARAR for this site.

 Alternative 11: This alternative is expected to comply with ARARs. Specifically, the proposed
 action is expected to enhance biodegradation and address threatened impacts to waters of the
 state.

2.63.3       Long-Term Effectiveness and  Permanence.  This criterion  was defined  in
Section 2.5.3.3 for the  landfill sites.   The comparative  analysis for this criterion for the
                                        2-71

-------
  TPH/VOC sites is presented below.  All of the TPH/VOC alternatives satisfy the RAO on
  groundwater monitoring to assess potential migration of constituents to groundwater.

  Soil:
  Alternative 6:  This alternative does not provide an active method to satisfy the  RAOs for
  preventing human exposure to soils having excess risk, to reduce concentrations of contaminants
  to meet remediation goals, and to  reduce the TMV of contaminants.   However, the natural
  degradation of fuel constituents would occur. Therefore, the risks from direct contact with the
  TPH/VOC-affected soils remains unchanged.

 Alternative 7: This alternative satisfies all of the RAOs at the applicable sites (FT-20 [soil] and
 SS-59); therefore, long-term effectiveness of this alternative is expected to be high.

 Alternative 8:  This alternative satisfies  all  of the RAOs  at the applicable  site  (FT-19c);
 therefore, long-term effectiveness of this alternative is expected to be high.  SVE has  proven to
 be effective in remediating soil contaminated with VOCs to below target remediation  goals. In
 addition, the aeration of the soil via vapor extraction may encourage biological degradation of
 TPH constituents.
 Alternative 9: This alternative satisfies all of the RAOs at the applicable sites (WP-17, FT-19a,
 FT-19b, and OT-51); therefore, long-term effectiveness of this alternative is expected to be high.
 Bioventing has proven to be effective in  remediating soil contaminated with hydrocarbons to
 below target remediation goals.

 Groundwater (Site OT-51):
 Alternative 10: This alternative does not satisfy the RAOs for preventing human exposure to
 contaminated groundwater having excess risk.  Therefore, the risks from direct contact with the
 affected groundwater remain unchanged.

Alternative 11:  For this alternative, restriction of access to the affected groundwater provides a
permanent solution. Biodegradation would ultimately reduce the contaminant concentrations.
                                          2-72

-------
   2.63.4       Reduction of Toxicity, Mobility,  and  Volume through  Treatment.   This
   criterion was defined in Section 2.5.3.4 for the landfill sites.  The comparative analysis for this
   criterion for the TPH/VOC sites is presented below.

  Soil:
  Alternative 6:  This alternative provides no active reduction of TMV of TPH/VOC-affected
  soils at any of the sites.

  Alternative 7:  This alternative would reduce the TMV of soil contaminants at the applicable
  sites (FT-20 [soil] and SS-59) by physically removing, treating, and ultimately disposing of the
  affected soils.

  Alternative 8t SVE would reduce the TMV of soil contaminants at the applicable site (FT-19c).

 Alternative 9: Bioventing would reduce the TMV of soil contaminants at the applicable sites
 (WP-17, FT-19a, FT-19b, and OT-51).

 Groundwater  (Site OT-51):
 Alternative 10: This alternative provides no enhanced reduction of TMV of TPH/VOC-affected
 groundwater at Site OT-51. The total mass of contaminants is reduced by degradation and the
 concentrations  are reduced by natural  attenuation to below groundwater numerical cleanup
 standards.  The volume of affected groundwater is not reduced; however, the volume of water
 that contains constituents above numerical cleanup standards would be reduced.  Mobility is not
 actively reduced; however, results of groundwater modeling for the site indicated that over 50
 years, the benzene leaching from the vadose zone would  not migrate far from the source areas.
 The base case  model scenario indicated that the leading edge of a 0.5 ug/L benzene plume
 boundary would migrate approximately 400 feet from the source area.

Alternative 11:  This alternative provides enhancement of the naturally occurring reduction of
TMV  of TPH/VOC-affected groundwater at Site OT-51.  The total mass of contaminants  is
                                        2-73

-------
  reduced by degradation  and the concentrations are reduced to below groundwater numerical
  cleanup standards. The volume of affected groundwater is not reduced; however, the volume of
  water that contains constituents above numerical cleanup standards would be reduced.  Mobility
  is not actively reduced; however, results of groundwater modeling for the site indicated that over
  50 years, the benzene leaching from the vadose zone would not migrate far from the source areas.
  The base case model scenario indicated that,  left untreated, the leading edge of a 0.5 ug/L
  benzene plume boundary  would  migrate approximately  400 feet from  the source area.
  Additional groundwater monitoring beyond Alternative 10 would provide data to allow efficient
  evaluation of  the natural degradation and potential migration of contaminants at the site.
 Oxygenation of top  portion  of  the groundwater  with  oxygen-releasing chemicals  would
 accelerate natural degradation of constituents.

 2.6.3.5       Short-Term Effectiveness. This criterion was defined in Section 2.5.3.5 for the
 landfill sites. The comparative analysis  for this criterion for the TPH/VOC sites is presented
 below.

 Soil:
 Alternative 6:  This alternative entails no risks to construction workers because no cleanup
 activities arc undertaken at any site.  In addition, no short-term public health and environmental
 impacts would be expected from this alternative.

 Alternative 7:   Short-term  public health and environmental  impacts  associated with this
 alternative  at the applicable sites (FT-20  [soil]  and SS-59) are expected to be minimal.  Site
 remediation workers would need to take appropriate precautions during removal and transport of
 affected soils.

Alternative 8:    Short-term  public health and environmental impacts  associated  with this
alternative at the applicable site (FT-19c) are expected to be minimal.  Site remediation workers
would need to take appropriate precautions during installation and operation of the SVE system.
                                         2-74

-------
  Alternative 9:  Short-term public health  and environmental impacts  associated with this
  alternative at the applicable sites (WP-17, FT-19a,  FT-19b, and OT-51) are  expected to  be
  minimal.   Site  remediation  workers would need  to take appropriate  precautions  during
  installation and operation of the bioventing systems.

  Groundwater (Site OT-51):
  Alternative 10:  This alternative entails no risks to  construction workers because no cleanup
  activities are undertaken at the site.  In addition, no short-term public health and environmental
  impacts would be expected from this alternative.

 Alternative 11:  Short-term public health and environmental impacts associated  with this
 alternative are expected to be minimal. Site remediation workers would need to take appropriate
 precautions during installation of the selected soil remediation  system and use  of oxygen-
 releasing chemicals in the existing monitoring wells.

 2.63.6       Implementability.  This criterion was defined in Section 2.5.3.6  for the landfill
 sites. The comparative analysis for this criterion for the TPH/VOC sites is presented below.

 Soil:
 Alternative 6:  This  alternative is easily implemented because no closure activities are  under
 taken.  Groundwater  monitoring  is easy to implement and the materials required  are readily
 available. There are no administrative difficulties associated with this alternative.

Alternative 7: Removal and disposal of soils is a feasible technology and is easily implemented
for shallow contamination (i.e., Sites FT-20 [soil]  and  SS-59).  Materials and services required
are readily available.

Alternative 8: SVE is a demonstrated technology that is readily implemented.  Materials and
services required are readily available.  There are no administrative difficulties associated with
this alternative.
                                         2-75

-------
 Alternative 9: Similar to Alternative 8, bioventing is a demonstrated technology that is readily
 implemented. Materials and services required are readily available. There are no administrative
 difficulties associated with this alternative.

 Groundwater (Site OT-51):
 Alternative 10: This alternative is easily implemented because no closure activities are under
 taken.   Groundwater monitoring is easy to implement and the materials required are  readily
 available. There are no administrative difficulties associated with this alternative.

 Alternative 11: Use of oxygen-releasing chemicals (i.e., ORC®) in the existing monitoring
 wells is relatively easy. All services and materials required are readily available.

 2.63.7        Cost. This criterion was defined in Section 2.5.3.7 for the landfill sites. Table 16
 presents a summary of the remedial alternative costs for the TPH/VOC sites. Costs are presented
 on a present-worth basis over a period of 30 years, with a discount rate of 7 percent.  Detailed
 cost analysis is presented in the FS (Montgomery Watson, 1997a).

 2.63.8       State Acceptance. This criterion was defined in Section 2.5.3.8 for the landfill
 sites. Final application of this criterion will occur in the approval of this ROD. The comparative
 analysis for this criterion for the TPH/VOC sites is presented below.

 Soil:
 Alternative 6: It is likely the state would not  accept this alternative for most TPH/VOC sites
 because no active steps are taken  to achieve the RAOs.  However, this alternative may be
 acceptable for shallow contamination at levels near or below the  remediation goals (i.e., FT-19b,
FT-20 tsoil], and SS-59).

 Alternative 7:   It is  likely the state would accept this  alternative for shallow TPH/VOC
contamination because the affected soils are completely removed.
                                          2-76

-------
  Alternative 8:  It is likely the state would accept this alternative for the applicable site (Site FT-
  19c) because the contaminants are actively removed from the site.

  Alternative 9:  It is likely the state would accept this alternative for the applicable sites (Site
  WP-17 and FT-19a) because the contaminants are actively degraded during the bioventing
  process.

  Groundwater (Site OT-S1):
  Alternative 10; The state may not accept this alternative because no steps are taken to enhance
  the natural processes that would ultimately achieve the RAOs.

 Alternative 11: The state is likely to accept this alternative because the remedy would reduce
 the contaminants in the state's waters with enhanced biodegradation.

 2.6.3,9       Community Acceptance.  As defined in Section 2.5.3.9 for the landfill sites,
 Community  acceptance indicates the public support for a given alternative. Section 3.0 of this
 ROD documents  the community acceptance  of the selected remedies,  as presented in  the
 Proposed Plan (Montgomery Watson, 1997b).  Section 3.0 includes a responsiveness summary
 that addresses the comments received during the public comment period.  The community did
 not express  any significant objections to the selected remedies  during the public  meeting  or
 public comment period.

 2,6.4         The Selected Remedies for the TPH/VOC Sites

 This  section  provides a description of the preferred alternatives  for remediation of the OU 3
 TPH/VOC sites based on the detailed evaluation  of alternatives presented in  the OU 3 FS
 (Montgomery Watson, 1997a).   This section includes the  basis for selection of a preferred
 alternative, a  description of the preferred alternative, and cost analyses.

2.6.4.1        Selection of  the Preferred  Alternatives.   The  RAOs  established for  the
TPH/VOC  sites  in  the OU 3 FS are summarized in  Section 2.6.2.  An evaluation of the
                                         2-77

-------
 alternatives with respect to the nine CERCLA criteria resulted in the selection of the following
 preferred alternatives to meet the RAOs for the TPH/VOC sites.

 Site WP-17.  Under the construction worker scenario (subsurface soils), the baseline human
 health risk assessment estimated the highest cancer risk of 9.7E-07 for this TPH/VOC-affected
 soil site, primarily because of the presence of total chromium found in subsurface soils. This risk
 value is below the California and USEPA acceptable benchmark value of l.OE-06. However, the
 initial evaluation criteria (based on the LUFT Manual;  see Section 2.6.1) for TPH and BTEX
 were exceeded in the soils at the site.

 The results  of the ecological risk assessment indicated that Site WP-17 was  not an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.

 In order to satisfy the RAOs for preventing human exposure to contaminated soils, to reduce
 concentrations of contaminants  to meet remediation  goals,  and  to  reduce  the TMV of
 contaminants, Alternative 9 (Bioventing) was recommended for Site WP-17 in the  OU 3 FS.
 Alternative 6  (No  Action)  is  not  capable  of  satisfying  these RAOs.  The technologies
 incorporated in Alternative 7  (Removal/Disposal) were screened out as not applicable for Site
 WP-17 because of the prohibitive costs associated  with the volumes of soil  that would be
 required to be removed. The  technologies incorporated for Alternative 8 (SVE) were screened
 out as not applicable for Site WP-17 because, although SVE encourages biodegradation of TPH
 constituents, it is less effective and more costly than bioventing.

Therefore, Alternative 9 (Bioventing) was the selected remedy for Site WP-17.  The bioventing
system has  been installed as discussed  in Section 2.9.   The system became  operational in
February 1996 and it is anticipated that remedy  completion will be achieved within 5 years.

Site FT-19a.  Under the  construction worker (subsurface soils) scenario, the baseline human
health  risk assessment estimated the highest lifetime cancer risk  of 2.8E-06 for Site FT-19a,
primarily because of the presence of arsenic. Although this is above the benchmark values for
risk assessment, the arsenic at the site is considered naturally occurring.  However, the initial

                                          2-78

-------
 evaluation criteria (based on the LUFT Manual; see Section 2.6.1) for TPH and BTEX were
 exceeded in soils at the site.

 The results of the  ecological risk assessment indicated that  Site FT-19a  was not an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.

 In order to satisfy the RAOs for preventing human exposure to contaminated soils potentially
 posing excess risk,  to reduce concentrations of contaminants to meet remediation goals, and to
 reduce the TMV of contaminants. Alternative 9 (Bioventing) was recommended for Site FT-19a
 in the OU 3 FS.  Alternative 6 (No Action)  is not capable of satisfying these RAOs.  The
 technologies  incorporated  in Alternative  7  (Removal/Disposal) were screened out as  not
 applicable for Site FT-19a  because of the prohibitive costs associated with the volumes of soil
 that would be required to be  removed. The technologies incorporated for Alternative 8 (SVE)
 were  screened out as not applicable for Site  FT-19a because,  although  SVE encourages
 biodegradation of TPH constituents, it less effective and more costly than bioventing.

 Therefore, Alternative 9 (Bioventing) was the selected remedy for Site FT-19a.  The bioventing
 system has been installed as discussed in Section 2.9. The system became operational in April
 1996 and it is anticipated that remedy completion will be achieved within 5 years.

 Site FT-19b.  The initial evaluation criteria (based on the LUFT Manual; see  Section 2.6.1) for
 TPH and BTEX were exceeded in soils at the site; therefore, the site was evaluated in the  OU 3
 FS.   However, the contamination  at the  site  appears to be  limited in  distribution with
 concentrations of TPH not  detected below 25 feet bgs (M&E, 1994).  Vadose zone modeling
 results indicated that under  the base case scenario (best estimate of site conditions for calibrated
 model), the most mobile constituents in  the soils  at Site FT-19b will not adversely  affect
 groundwater   quality.     A  subsequent  risk   assessment   indicated   that  under   the
 industrial/commercial worker scenario, the baseline human health  risk assessment estimated the
highest lifetime risk of 5.2E-06 for the site, primarily because of the presence of beryllium and
nickel. Although this is above the benchmark value for risk assessment, the beryllium and nickel
detected at the site is considered naturally occurring and within background range. The results of

                                          2-79

-------
 the ecological risk assessment indicated that Site FT-19b is not an area of potential ecological
 concern because of the lack of suitable habitat for environmental receptors.  The medical wastes
 at this site have been removed and disposed  at  an off-site disposal facility under the FSRA
 activities ongoing at the base.

 Based on the detailed analysis of alternatives, Alternative 6 (No Action) was recommended for
 Site FT-19b in the OU 3 FS. The technologies incorporated in Alternative 7 (Removal/Disposal)
 were screened out as not applicable for Site FT-19b because of the prohibitive costs associated
 with the volumes of soil that would be required to be removed.  The technologies incorporated
 for Alternative 8 (SVE) were  screened out as not applicable for Site FT-19b because, although
 SVE encourages biodegradation of TPH constituents,  this technology  is  used primarily to
 encourage volatilization of VOC contamination.  Alternative 9 (Bioventing), is less costly than
 SVE and more effective for treating TPH contamination. However, given the limited distribution
 of detected TPH and VOCs, vadose zone model results indicating that groundwater quality will
 not  be adversely affected, and risk assessment  results indicating excess  risk are the result of
 metals considered naturally occurring, remedial action at the associated costs are not believed to
 be warranted.  Therefore,  the no  action alternative is the  selected  remedy  at this site.
 Groundwater monitoring will  be performed for this  area as part of the remedial actions to be
 performed for Sites FT-19a and FT-19c; therefore, there would be no costs associated with the no
 action alternative for this site.

Site FT-19c.  Under the construction worker (subsurface soils) scenario, the baseline human
health risk assessment estimated the highest lifetime cancer risk of 3.1E-06 for Site  FT-19c,
primarily  because  of chromium under a  construction worker (subsurface soils) scenario.
Although this is above the benchmark  values for  risk  assessment, the chromium at the site is
considered naturally occurring and within background ranges.  However, the initial evaluation
criteria (based on the  LUFT Manual; see Section 2.6.1) for TPH and BTEX were exceeded in
soils at the site. In addition, vadose zone modeling results indicate that TCE present in soils will
adversely affect groundwater beneath the site.
                                         2-80

-------
 The results of the ecological risk assessment indicated that Site FT-19c was not an area of
 potential ecological concern because of the lack of suitable habitat for environmental receptors.

 In order to satisfy the RAOs for preventing human exposure to contaminated soils, to reduce
 concentrations  of contaminants  to  meet  remediation  goals,   and to reduce  the  TMV  of
 contaminants. Alternative  8  (SVE)  was recommended  for Site FT-19c  in the OU 3 FS.
 Alternative  6 (No  Action) is not  capable  of  satisfying these  RAOs.   The technologies
 incorporated in Alternative 7  (Removal/Disposal) were screened out as not applicable  for Site
 FT-19c because of the prohibitive costs associated with the volumes of soil that would be
 required to be  removed.   The technologies incorporated in Alternative 9 (Bioventing)  were
 screened out as not applicable  for Site FT-19c because  bioventing would not be effective at
 removing the TCE detected in the subsurface soils at the site.

 Therefore, Alternative 8 (SVE) was the selected remedy for Site FT-19c.  The SVE system has
 been installed as discussed in Section 2.9.  The system became operational in March 1996 and it
 is anticipated that remedy completion will be achieved within 5 years.

 Site FT-20 (Soil). The baseline human  health risk assessment estimates the  highest excess
 lifetime cancer  risk  of 4.0E-06,  primarily because of  arsenic under an  industrial  worker,
 construction worker, and trespasser scenario.  Although this is above the benchmark values for
 risk assessment, the  arsenic  at the  site is considered  naturally occurring and  within the
 background ranges. The results of the ecological risk assessment indicated that Site FT-20 (soil)
 is  not an  area  of potential ecological concern because  of the lack  of suitable  habitat for
 environmental receptors. However, petroleum hydrocarbons were  detected in surface samples at
 this site.

 Site FT-20 (soil) was recommended for NFA in the OU 3 FS. The technologies incorporated in
 Alternatives 8 (SVE) and 9 (Bioventing) were screened out as not applicable at Site FT-20 (soil)
 because they are not  considered effective for shallow soils.  Based on an evaluation  of the
concentrations of petroleum hydrocarbons and metals detected  at  the site, the RPMs have
determined that the constituents would not pose a threat to groundwater. The detected levels of

                                          2-81

-------
 hydrocarbons are less than the remediation goals for TPH/VOC sites (Figure 9).  Therefore, the
 implementation  of  Alternative  6  (No  Action   with  Monitoring)  or  Alternative  7
 (Removal/Disposal) are not  considered cost-effective for Site FT-20 (soil), and NFA was  the
 selected remedy.

 Site OT-51.  PRO screening in accordance with the methodology presented in the OU 3 RI
 indicated that detailed human health risk analysis was  not required. The results of the ecological
 risk assessment indicated that Site OT-51/SS-59 is not an area of potential ecological concern
 because of the lack of suitable habitat for environmental receptors.   However,  the  initial
 evaluation  criteria (based on the LUFT Manual; see Section 2.6.1) for TPH and BTEX were
 exceeded in soils at the site.  Because this site is unique among the TPH/VOC sites in that TPH
and VOC constituents were detected in both soil and  groundwater, potential remediation  in the
soil and groundwater are addressed separately as discussed in the sections below.

      SoiL  Site SS-59 was  recommended for NFA in the OU 3 FS.   The  technologies
      incorporated in Alternatives  8  (SVE)  and 9 (Bioventing) were screened out as not
      applicable  at Site  SS-59 because they are not considered effective for shallow  soils.
      Based on an evaluation of the limited distribution of detected petroleum hydrocarbons at
      the site, the RPMs have determined that the  constituents would not pose a threat to
      groundwater.   Therefore, the  implementation of  Alternative 6  (No  Action   with
      Monitoring) or Alternative 7  (Removal/Disposal) are not  considered cost-effective for
      Site  SS-59, and NFA was recommended.

      In order to satisfy  the RAOs  for preventing human exposure  to contaminated soils, to
      reduce concentrations of contaminants to meet remediation goals, and  to reduce the TMV
      of contaminants, Alternative 9 (Bioventing) is recommended for Site OT-51. Alternative
      6 (No Action) is not capable of satisfying the RAOs. The  technologies incorporated in
      Alternative 7 (Removal/Disposal) were screened out as  not  applicable  for  this site
      because of the prohibitive costs associated with the volumes of deep soil that  would be
      required  to be removed.  The technologies incorporated for Alternative 8 (SVE)  were
                                        2-82

-------
        screened out as not applicable  for Site OT-51 because, although SVE  encourages
        biodegradation of TPH constituents, it is less effective and more costly than bioventing.

        Therefore, Alternative 9 (Bioventing) was the selected remedy for Site OT-51.  The
        bioventing system has been installed as discussed in Section 2.9.  The system became
        operational in April  1996 and it is anticipated that remedy completion will be  achieved
        within 5 years.

        Groundwater.  In order to satisfy the RAOs for reducing dissolved contaminants in
        groundwater  to below  MCLs, natural attenuation is  the selected remedy  for the
        groundwater at Site OT-51. Although Alternative 10 (No Action) will ultimately satisfy
        the RAOs, it does not ensure that groundwater will not be used for domestic purposes in
        the future. As part of natural attenuation institutional controls, continued groundwater
       monitoring would be performed to assess potential future migration and degradation of
       COPCs in the groundwater. Land use  restrictions would prohibit  domestic  use of the
       groundwater and ensure protection  of human health and the environment. If the levels of
       COPCs observed in the downgradient monitoring wells do not decrease to meet
       groundwater numerical cleanup standards  (Table 13) within a sufficient time frame,
       oxygenation of the top portion  of the groundwater  using  oxygen-releasing  chemicals
       (Alternative 11) would be implemented to accelerate natural degradation.

2.6.4.2       Detailed Description  of the  TPH/VOC Site  Preferred Alternatives.   The
selected alternatives from the OU 3  FS for the TPH/VOC sites (identified in Section 2.6.4.1) are
described in detail below.

Site ET-Wc.  Alternative 8 has been selected for this site and soil will be treated with SVE. This
includes the following specific activities:

      •      installation of an SVE system including extraction vents, monitoring points, air
             blower, abovcground piping, equipment pad, and associated appurtenances;
      •      implementation of a soil vapor off-gas monitoring program to assess  system
             performance;
                                        2-83

-------
         •      implementation of access restrictions to prevent unauthorized access to installed
               equipment;

         •      implementation of land use restrictions which will restrict construction activities
               that would impair the integrity of the existing system (i.e., SVE and monitoring
               wells) while it is in place and prevent installation of monitoring or injection wells
               in the site area (except where required for environmental purposes); these would
               be enforced until the soil  remedy is completed (groundwater restrictions are
               covered under the OU 1 ROD [Montgomery Watson, 1994]);

        •      collection of confirmation samples (soil and vapor) to assess remedy completion;
               and

        •      5-year site review to assess the effectiveness of the remedy.


 Sites WP-17, FT-19a, and OT-51 (soil). Alternative 9 has been selected for these sites and soils

 will be treated with bioventing. This includes the following specific activities:


        •     installation of bioventing systems including injection vents, monitoring points, air
              blower, aboveground piping, equipment pad, and associated appurtenances;

        •      implementation of a soil vapor monitoring program to assess system performance;

        •      implementation of  long-term groundwater monitoring  in  accordance  with an
              approved basewide long-term groundwater monitoring plan;

       •      implementation of access restrictions to prevent  unauthorized access to  installed
              equipment;

       •      implementation of land use restrictions which will restrict construction activities
              that would impair the integrity of the existing system (i.e., bioventing, SVE, anJ
              monitoring wells) while it is in place and prevent installation of monitoring or
              injection  wells in  the. site area (except where  required  for  environmental
              purposes); these would be enforced until the soil remedy is completed;

       •      collection of confirmation samples (soil and vapor) to assess remedy completion;
              and

       •      5-year site review to assess the effectiveness of the remedy.


Site OT-51 (groundwater). Natural attenuation  has been selected as the remedy for this site.

As a contingency, Alternative 11 would be implemented such that groundwater would be treated


                                         2-84

-------
  with oxygenation of the groundwater using oxygen-releasing chemicals if COPCs observed in
  downgradient  monitoring  wells do  not  decrease to meet groundwater  numerical cleanup
  standards (Table 13) within a sufficient time frame.  This remedy includes the following specific
  activities:

              decommissioning the abandoned well casing downgradient of Site OT-51;
              implementation of long-term groundwater monitoring in accordance  with  an
              approved basewide long-term groundwater monitoring plan;
              implementation of use restrictions which  would prohibit domestic use of the
              groundwater,
              installation of one or two downgradient monitoring wells to satisfy long-term
              monitoring requirement (the OU 3 FS cost estimate included well installation for
              the soils alternative presented on Table 20);
             implementation of oxygen-releasing chemicals (Alternative 11) as a contingency
             if COPCs in groundwater do not decrease to groundwater numerical  cleanup
             standards within a sufficient time frame (see Section 2.6.2.5); and
             5-year site review to assess the effectiveness of the remedy.

 2.6.43       Cost Analysis.  A preliminary cost estimate was prepared for the selected
 alternatives for each TPH/VOC site as part of the OU 3 FS process.  Tables  17 through 21
 summarize the cost analysis for the selected alternative for sites WP-17, FT-19a, FT-19c, OT-51
 (soil and groundwater [assuming  the use of ORC®]). With the selection of NFA for Sites FT-
 19b, FT-20 (soil), and SS-59, there would be no additional costs incurred for these sites.

 2.6.4.4       System Implementation.  In an effort to accelerate the remedial process, early
 remedial actions have been initiated, under the direction of the USAF, at the TPH/VOC  sites
 presented in this ROD. These accelerated actions were conducted to minimize present and future
environmental risks and were performed in agreement  with the RPMs including the USEPA.
DTSC, Lahontan RWQCB, and USAF.  The accelerated actions were performed at TPH/VOC
Sites WP-17, FT-19a, FT-19c, and OT-51 as summarized in Section 2.6.4.3 and detailed in the
Work Plan for Remedial Activities at the TPH/VOC sites (Montgomery Watson, 1995a).
                                       2-85

-------
  Bioventing systems were installed at WP-17, FT-19a, and OT-51 from December 1995 through

  April 1996. These systems are currently in operation. An SVE system was installed at Site FT-

  19c from December 1995 through March 1996 and is currently in operation. These actions are
  summarized in Section 2.9 (Current Site Status).
  2.6.5
Statutory Determinations for the TPH/VOC Sites
 The selected remedies satisfy the statutory requirements of Section 121 of CERCLA, as amended
 by SARA, in that the following five mandates are attained:


        •      The selected remedies are protective of human health and the environment, will
              decrease  site risks, and  will not create short-term risk nor have  cross-media
              consequences.

        *      The selected remedies  comply  with  federal  and state requirements  that are
              applicable or relevant and appropriate  to the remedial action such as chemical-
              specific  ARARs, chemical-specific  clean-up  standards,  and  action-specific
              ARARs.

       •      The selected remedies are cost-effective in their fulfillment of the nine CERCLA
              evaluation criteria through remediation of the TPH/VOC sites in a reasonable
              period of time.

       •      The selected  remedies utilize permanent solutions and  alternative treatment
              technologies or resource recovery technologies, to the maximum extent practical.

       •      The selected remedies satisfy the preference for treatment as a principle element.


2.6.5.1        Protection of Human Health and the  Environment  Protection of  human

health and the environment at the OU 3 TPH/VOC sites is achieved by the selected remedies for

each site by removal of the contamination through treatment (i.e., biodegradation and SVE).


2.6.5.2       Compliance with ARARs.  All pertinent ARARs identified for the TPH/VOC

sites (Table 15) will be met by the selected remedies.
                                        2-86

-------
  2.6.5.3       Cost Effectiveness. The USEPA, the USAF, and the State of California believe
  that the selected remedies fulfill the nine criteria of the NCP and provide overall effectiveness in
  relation to their costs.

  2.6.5.4       Utilization of Permanent Solution and Alternative Treatment (or Resource
  Recovery) Technologies to the Maximum Extent Possible. The selected remedy represents, to
  the maximum extent to which permanent solutions and treatment technologies can be used, a
  cost-effective manner for remediating the OU 3 TPH/VOC sites.  The remedies selected provide
  the best balance of long-term effectiveness  and permanence; reduction of TMV  through
  treatment; short-term effectiveness; implementability and cost-effectiveness.

  2.6.5.5       Preference for Treatment as a Principle Element. The preference for treatment
  as the principle elements is satisfied  to the  extent practicable  by the selected remedies.
  Alternative 9  (Bioventing)  at Sites WP-17,   FT-19b.  and OT-51 will remove and  treat
 contaminants in soils to below acceptable levels through biodegradation.  Alternative 8 (SVE) at
 FT- 19c will remove the primary COPC (TCE) from soils by physical transfer from soil to air and
 discharging the TCE. The expected concentrations of TCE discharged to the air (less than 1
 pound/day) do not require treatment. By selection of natural attenuation for groundwater at Site
 OT-51, the COPCs will be treated through natural attenuation with contingent implementation of
 oxygen-releasing  chemicals  (Alternative  11)   if the levels  of COPCs  observed   in  the
 downgradient  monitoring wells do not decrease to meet groundwater numerical cleanup
 standards (Table 13) within a sufficient time frame.

 2.7          SITE OT-69 SUMMARY

This section summarizes the  site characteristics, risk  assessment results, descriptions  of the
alternatives evaluated, alternatives comparison, and the selection of the final remedy for Site OT-
69.
                                        2-87

-------
 2.7.1         Summary of Site OT-69 Characteristics and Risk Assessment

 Site OT-69 consists of the TCE and PCE groiindwater contamination that was detected in the
 flightline and operations support facilities area.  The site was investigated independently by IT
 and results of the investigations are discussed in detail in the RI/FS  for the OU 3 TCE/PCE
 Study Area (IT, 1995a). Additional modeling for the groundwater in the northeast portion of the
 flightline area was performed by Montgomery Watson (Montgomery Watson, 1996a). Figure 14
 presents select affected wells that identify the five plumes that make up Site OT-69. The results
 of the investigations are summarized below.

 The TCE/PCE contamination in this area was first  identified during the 1992 investigation of
 aviation jet fuel (JP-4) contamination  within OU  2.  In  1993, the extent of the TCEi/PCE
 groundwater contamination in the vicinity of the flight line and operational support facilities was
 investigated by  IT.  The 1993 investigations determined that the Aquitard under the Upper
 Aquifer would prevent contaminants from  migrating to greater depths, and wells completed to
 the base of the Upper Aquifer, or to the top of the Aquitard, contained no contaminants.  The soil
 and groundwater TCE/PCE contamination at well MW-49 was further delineated by IT in 1995.
 The additional investigations performed to further characterize the extent of TCE and  PCE
 contamination in the vicinity of MW-49 included soil-gas, soil and groundwater sampling and
 analysis, and installation of cluster monitoring wells (IT, 1995a).

The 1993 Site OT-69  RI performed by IT resulted in the following principal findings  and
conclusions (IT,  1995a):
             The highest concentration of TCE in groundwater (37.0 ug/L) was detected in
             well MW-49 on the southern edge of the study area. TCE was detected above the
             MCL of 5 ug/L in seven samples.
             The TCE groundwater contamination in OU 3 occurs in several, small, isolated
             plumes.  The new wells  placed limits on the  extent of contamination detected
             during the OU 2 investigation.
             TCE and PCE were not detected in any of the  613 soil samples analyzed during
             the JP-4 OU 2 RI, or the 115 soil samples analyzed during the 1993 TCE/PCE RI

                                         2-88

-------
              investigation. TCE was detected in only 4 of the 29 soil samples collected during
              the MW-49 TCE investigation.

        •      Contaminant fate and transport indicated that the highest levels of TCE in OU 3
              will attenuate to 5 ug/L in approximately 40 to 45 years by physical mechanisms.

        •      PCE groundwater contamination (highest concentration was 7.8 pg/L) occurs in
              one area near the southwest end of the flight line.

        •      Analysis  of groundwater samples  from  cluster wells indicated that the TCE
              groundwater contamination was limited to the upper 30 feet of the aquifer.  In the
              middle and bottom portions of the aquifer, no TCE was detected.

       •      The total volume of TCE  and PCE  dissolved within  the groundwater  was
              calculated in the OU 3 TCE/PCE draft RI/FS to be approximately 0.8 gallons of
              TCE and 0.006 gallons of PCE.


Subsequent to the 1992 OU 2 RI and 1993 RI (for Site OT-69), it was determined that additional

data was required to evaluate the extent of TCE/PCE at Site OT-69. The primary objective was

to further characterize the extent of TCE/PCE in the vicinity of well MW-49. The 1995  RI/FS

for the  TCE/PCE study area (Site OT-69) resulted in the following principal findings  and
conclusions (IT, 1995a):


             The highest concentrations of TCE contamination (78 ug/L) occur in the top 6 feet
             of the water table. The TCE concentrations drop to 4 ug/L, 6 feet below the water
             table, and are non-detect 30 feet and deeper below the water table.

      •     TCE contamination  in the vadose  zone  soils  is lower than  the level in  the
             groundwater. The concentration of TCE in soil-gas  is below the equilibrium
             concentration for the associated groundwater contaminant level. Therefore, the
             vadose zone contamination does not  pose  a source for  further groundwater
             contamination.

      •      The TCE concentrations have declined in well MW-49 and increased in MW-60,
             suggesting the plume has moved downgradient during the previous 2 years.

      •      Soil-gas and soil sample analysis indicated that MW-49/MW-72 are closer to the
             source than the wash rack (see IT,  1995a).

      •      Fate and transport modeling indicates that the TCE contaminant plume in MW-49
             area will reduce to 5 ug/L within 46 years and  move  approximately 1,000 feet
             north from the original location.  The other plumes will attenuate to the MCL in
             much less time.

                                        2-89

-------
               Contaminant dispersion modeling suggest that the TCE plume will degrade to the
               detection level and before being intercepted by the OU 1  groundwater treatment
               system.

  Groundwater sampling of wells NZ-51, NZ-52, NZ-54, and NZ-68 near the STP percolation
  ponds has indicated the presence of TCE in the groundwater in the northeast flightline area. This
  area is now considered part of Site OT-69; however, it was not  specifically addressed in the
  RI/FS for the TCE/PCE Study Area (IT, 1995a).  Therefore, Montgomery Watson performed
  additional  solute-transport modeling of this  area to  assess the natural attenuation of the
  "northeast" OT-69 plume.

 The results of the additional modeling  for the northeast OT-69 plume showed the  current
 northeastward migration of TCE at the northeast OT-69 plume will be changed significantly by
 percolation resulting from the OU 1 treatment system. Modeling suggests the plume will move
 south and east after commencement of effluent percolation from this system, and concentrations
 are predicted to drop below the current MCL for TCE (5 ug/L) in less than two years.

 There are currently no complete exposure pathways for the contaminated groundwater at: Site
 OT-69.   Groundwater in  the  site  areas is not used  as a source  of domestic,  industrial, or
 agricultural  supply.  Therefore, there is currently no danger of adverse exposure to either base
 personnel or residents.  In addition, the groundwater does not reach the ground surface within the
 base  boundaries; therefore,  there  is no  known exposure pathway to  ecological receptors.
 However, a risk assessment was performed that considered the possibility that the groundwater
 within the study area would migrate beyond the boundaries of the base or that the base would be
 used for residential development in the future (FT, 1995a). The risk assessment found there were
 no  likely exposure pathways and consequently no risks to the on-base workers  and off-base
 residents from  TGE/PCE  contamination.  The total  carcinogenic risk  from dichloroetlhane
 (DCA), TCE, and PCE based on three groundwater exposure pathways (drinking water; dermal
contact, and inhalation) is 2E-05 for a basewide residential development case  and 3E-08 for a
limited residential development case.
                                        2-90

-------
  2.7.2         Description of Site OT-69 Alternatives

  Based on  the results  of remedial investigations, it  was determined that remedial action
  alternatives be assessed at Site OT-69.  An FS analysis was performed for this site as described
  for the landfill sites in Section 2.5.2. Part of the FS process included development of RAOs as
 described below.

 There are currently no complete exposure pathways for the contaminated groundwater at Site
 OT-69.   Groundwater in the site areas  is not used as a source of domestic, industrial, or
 agricultural supply.  Therefore, there is currently no danger of adverse exposure to either base
 personnel or residents.  In addition, the groundwater does not reach the ground surface within the
 base  boundaries; therefore, there is no known exposure pathway to ecological receptors.
 However, in  accordance with  ARARs  that call  for protection  of  groundwater resources.
 groundwater at Site  OT-51 should be protected.  Therefore, the RAO for  groundwater is as
 follows:

       •       Reduce the dissolved concentrations for identified COPCs in the groundwater at
              Site OT-69 so that the most stringent concentrations identified  in the ARARs are
              not exceeded (MCLs, secondary MCLs, or quantifiable taste or odor criteria).

The groundwater numerical cleanup standards for Site OT-69 are presented on Table 13.

Six alternatives were developed for Site OT-69 as detailed in the RI/FS for the TCE/PCE Study
Area (IT, I995a). The alternatives, with their components, are as follows:

      Alternative G-l
             1) No Action
      Alternative G-2
             1) Land Use Restrictions
            2) Deed Restrictions
            3) Natural  Attenuation with Groundwater Monitoring
      Alternative G-3
             1)  In Situ Air Sparging
            2)  SVE Recovery/Abatement
                                        2-91

-------
                3) Groundwater Monitoring
                4) Institutional Controls
         Alternative G-4
                1) Groundwater Extraction
                2) Surface Groundwater Treatment with Ultraviolet (UV) Oxidation
                3) Reinjection of Treated Groundwater
                4) Institutional Controls
         Alternative G-5
                1)  Groundwater Extraction
                2)  Surface Groundwater Treatment with granular activated carbon (GAC)
                3)  Reinjection of Treated Groundwater
               4)  Institutional Controls
        Alternative G-6
                1)  Groundwater Extraction
               2)  Surface Groundwater Treatment with Thermally Abated Air Stripping
               3)  Reinjection of Treated Groundwater
               4)  Institutional Controls

 2,7.2.1        Alternative G-l: No Action.  Alternative G-l serves as a baseline against which
 other soil alternatives are compared.  No institutional controls  or remedial action would be
 undertaken.  Natural attenuation of groundwater contamination would be allowed to continue.
 All monitoring would be discontinued.

 2.7.23       Alternative G-2: Natural Attenuation/Institutional Controls. Alternative G-2
 consists of natural attenuation with institutional controls which  include land use  restrictions
 prohibiting installation of wells for domestic  purposes in  the affected  aquifer  and deed
 restrictions prohibiting use of contaminated water.  In addition,  continued monitoring of the
 natural attenuation of the plume would be achieved through annual groundwater monitoring of
 approximately 10 wells.

2.7.23      Alternative G-3: In Situ Air Sparging, SVE Recovery/Abatement in Vadose
Zone, Groundwater  Monitoring.  Alternative G-3 includes installation of approximate  58
sparge wells at isolated detection points.  Air injection at each well would occur at 25 cubic feet
per minute (cfm) into the bottom 10 feet of the Upper Aquifer. Approximately 183 SVE vents
would be used to capture VOCs transferred from the liquid to vapor phase (assuming a radius of
                                         2-92

-------
  influence of 50 feet).  Vapor abatement from SVB system would be accomplished using a
  catalytic thermal oxidation system or an internal combustion engine (to be determined based on
  the results of pilot tests).

  2.7.2.4       Alternative G-4: Groundwater Extraction, Surface Groundwater Treatment
  with UV-Oxidation, Reinjection  of  Treated Groundwater.   Alternative  G-4 includes
  installation of approximately 21 extraction wells at isolated detection points. Extraction wells
  would be pumped at an average rate of 25 gpm (totaling 525 gpm).  Extracted groundwater
  would be pumped to a central surface treatment plant where contaminants would be removed
  using aqueous enhanced UV-oxidation.  Approximately 225 gpm of treated groundwater would
  be reinjected directly to  the Upper Aquifer using nine  injection wells located around  the
 perimeter of isolated detection points. Because of hydraulic limitations, the remaining 300 gpm
 of treated groundwater would be discharged to the surface.

 2.7JL5       Alternative G-5: Groundwater Extraction, Surface Groundwater Treatment
 with GAC, Reinjection of Treated Groundwater. Alternative G-5 is the same as G-4 with the
 exception that contaminants  would be removed from  the groundwater with  GAC (rather than
 UV-oxidation).

 2.7.2.6       Alternative G-6:  Groundwater Extraction, Surface Groundwater Treatment
 with Thermally Abated Air Stripping, Reinjection of Treated Groundwater. Alternative G-
 6 is die same as Alternatives G-4 and G-5 with the exception that contaminants would  be
 removed from the groundwater with  an air stripper with  a thennal fuel-assisted combustor for
 vapor abatement (rather than UV-oxidation or GAC).

2.7.3         Summary of Comparative Analysis of Alternatives for Site OT-69

The remedial alternatives developed for  Site OT-69 were analyzed  in detail using the nine
evaluation criteria required by the NCP as detailed in Section 2.5.3 for the landfill sites.
                                        2-93

-------
  The resulting strengths and weaknesses of the alternatives were then weighed to identify the
  alternative  providing the best balance among the nine criteria.  Table 22  summarizes this
  comparison.

  2.7.3.1       Overall Protection of Human Health and the Environment This criterion was
  defined in Section 2.5.3.1 for the landfill sites. The comparative analysis for  this criterion for
  Site OT-69 is presented below.

  Alternative G-l: Would reduce concentrations of contamination to levels affording acceptable
  risk levels in approximately 46 years.  There are currently no exposure pathways that would
  result in a threat to human health. Given future land use plans, completed exposure pathways are
  not anticipated in this time frame.

 Alternative G-2:  Would reduce concentrations of contamination to levels affording acceptable
 risk levels in approximately 46 years.  There  arc currently no exposure pathways that would
 result in a threat to human health. Given future land use plans, completed exposure pathways are
 not anticipated in this time frame. In addition,  land use and deed restrictions provide protection
 of human health.

 Alternative  G-3:   Would  reduce  concentrations of contamination  to  acceptable levels  in
 approximately 1 year. Potential additional risk  introduced through the transfer of COPCs to the
 air would  be reduced to acceptable levels  through  treatment via catalytic thermal oxidation
 system. A potential residual risk remains associated  with off-site disposal of SVE condensate;
 therefore, proper disposal is required.

 Alternative  G-4:   Would reduce  contaminated   groundwatcr to  acceptable  levels  in
 approximately 10 years.

Alternative G-5:    Would reduce  contaminated  groundwater to  acceptable  levels  in
approximately 10 years. Potential residual risk remains associated with off-site disposal of spent
GAC; therefore, proper disposal is required.
 *
                                         2-94
r

-------
  Alternative G-6:   Would  reduce  contaminated  groundwater  to  acceptable  levels  in
  approximately  10 years.  Potential additional risk introduced through the transfer of COPCs to
  the air would  be reduced to acceptable  levels through treatment via a thermal fuel-assisted
  combustor. Potential residual risk remains associated with off-site disposal of spent  acid from
  stripping tower wash down; therefore, proper disposal is required.

  2.7.3.2      Compliance with ARARs.  The definition of ARARs and  this criterion was
  presented in Section  2.5.3.2 for the landfill sites.  A listing of federal and state  laws  and
  regulations that are ARARs for the OU 3 TPH/VOC sites is provided in Table  15. These are also
  the ARARs for Site OT-69.  ARARs are  expected to  be met  with all alternatives.  Chemical-
  specific ARARs will  be met by ultimately achieving the  cleanup standards.  Action-specific
 ARARs will be met by appropriate design and implementation of remedial alternatives.

 2.7.3.3       Long-Term Effectiveness  and Permanence.  This  criterion was  defined  in
 Section 2.5.3.3 for the landfill sites. The comparative analysis for this criterion for Site  OT-69 is
 presented below.

 Alternative G-l:  Natural attenuation is expected to reduce risk to acceptable levels.  Controls
 for on-site residuals are not required.

 Alternative G-2:  Natural attenuation is expected to reduce risk to acceptable levels. Controls
 for on-site residuals are not required.

 Alternative G-3:  Remediation through air sparging and SVE is expected to reduce risk to
 acceptable levelsr Potential residual risk  remains  associated  with off-site disposal  of SVE
 condensate; therefore, proper disposal is required. Controls for on-site residuals are not required.

Alternative  G-4:  Remediation groundwater extraction and surface treatment is expected  to
reduce risk to acceptable levels. Controls for on-site residuals are not required.
                                         2-95

-------
  Alternative G-5:  Remediation groundwater extraction and surface treatment is expected to
  reduce risk to acceptable levels.  Potential residual risk remains associated with off-site disposal
  of spent GAC; therefore, proper disposal is required.  Controls for on-site  residuals are not
  required.

  Alternative G-6:   Remediation groundwater extraction and surface treatment is expected to
  reduce risk to acceptable levels. Potential residual risk remains associated with off-site disposal
  of spent acid from stripping tower wash down; therefore, proper disposal is required.  Controls
  for on-site residuals are not required.

 2.7.3.4       Reduction  of Toxicity, Mobility, and Volume  through  Treatment.   This
 criterion was defined in Section 2.5.3.4 for the landfill sites. The comparative analysis for this
 criterion for Site OT-69 is presented below.

 Alternative G-l:   Toxicity and mobility is not  reduced.   However, concentrations of
 contaminants are reduced to levels detennined to be protective of human health. In addition, the
 volume of  affected groundwater is  not reduced; however, the volume of groundwater  with
 concentrations of contaminants resulting in excess risk is ultimately reduced to zero.

 Alternative G-2: Same as Alternative G-l.

 Alternative G-3:   A high degree of TMV reduction is achieved because contaminants are
 destroyed on site through  SVE  abatement (catalytic thermal oxidation system or an internal
 combustion engine).

 Alternative G-4:   A high degree of  TMV reduction is achieved because contaminants are
 destroyed on site through UV-oxidation.

 Alternative G-5:  A high degree of TMV reduction is achieved locally because contaminants are
removed from groundwater with GAC. Some chemical toxicity  is transferred to an off-site
location with spent GAC.
                                          2-96

-------
   Alternative G-«: A high degree of TMV reduction is achieved locally because contaminants are
   destroyed on site through thermal abatement. Some chemical toxicity is transferred to an off-site
   location with spent acid wash.

   2.7J.5       Short-Term Effectiveness. This criterion was defined in Section 2.5.3.5 for the
   landfill sites. The comparative analysis for this criterion for Site OT-69 is presented below.

   Alternative G-l:  Under current or expected base land use, there are no completed exposure
   pathways. However, in the event land use changes such that exposure pathways are completed,
   this alternative would  not eliminate exposure  pathway reduction of concentrations  to below
  MCLs for 46 years.  Because there is no remedial action taken, there is not potential exposure to
  remedial workers.

  Alternative G-2: Under current or expected base land use, there are no completed  exposure
  pathways.  In addition, this alternative prevents the completion of exposure pathways in the
  future  by implementing institutional controls. There is possible exposure to remedial workers
  during groundwater sampling which can be mitigated by following appropriate health and safety
  procedures.

 Alternative G-3: This alternative prevents the completion of exposure pathways in the future by
 implementing institutional controls.  A small potential risk to the community is generated by
 transfer of contaminants to the vapor phase which is partially mitigated through SVE  vapor
 abatement/recovery. A relatively small short-term risk exists with the transport and disposal of
 SVE condensate.  There is possible exposure to remedial workers during monitoring activities
 which can be mitigated by following appropriate health and safety procedures.

Alternative G-4:  In addition, this alternative prevents the completion of exposure pathways in
the future by implementing institutional controls.  There is  possible exposure  to remedial
workers during monitoring activities which can be mitigated by following appropriate health and
safety procedures.
                                         2-97

-------
  Alternative G-5: In addition, this alternative prevents the completion of exposure pathways in
  the future by implementing institutional controls.  A relatively small short-term risk exists with
  the transport and disposal of spent GAC.  There is possible exposure to remedial workers during
  monitoring activities  which can be mitigated  by following appropriate health and safety
  procedures.

  Alternative G-6:  In addition, this alternative prevents the completion of exposure pathways in
  the  future by implementing institutional controls.  A small potential risk the community is
  generated by transfer of contaminants to the vapor phase which is partially mitigated through
  vapor abatement.  A relatively small short-term risk exists with the transport and disposal of
  spent acid wash water.  There is possible exposure to remedial  workers during monitoring
  activities which can be mitigated by following appropriate health and safety procedures.

 2.7.3.6        Implementability.  This criterion was defined in Section 2.5.3.6 for the landfill
 sites. The comparative analysis for this criterion for Site OT-69 is presented below.

 Alternative G-l:  No remedial action is undertaken for this alternative; therefore, there arc no
 technical or administrative limitations and no services or materials are required.

 Alternative G-2:   There  are no  technical  or  administrative limitations for  this alternative.
 Services and materials required for groundwater monitoring arc readily available.

 Alternative G-3: The technologies that make up this alternative arc technically implememtable,
 proven, and available.  Permitting may be required for off-site disposal of SVE condcnsate.
 Services and   materials  required  are readily  available; however, significant  amounts  of
 supplemental fuel would be required for SVE abatement system.

Alternative G-4: The technologies that make up this alternative are  technically implementable,
proven, and available.  Services and materials required are readily available.
                                         2-98

-------
  Alternative G-S: The technologies that make up this alternative are technically implementable,
  proven, and available. Permitting may be required for off-site disposal of spent GAC. Services
  and materials required are readily available.

  Alternative G-6: The technologies that make up this alternative are technically implementable,
  proven, and available. Permitting may be required for off-site disposal of spent acid wash water.
  Services  and  materials required  are  readily  available; however,  significant amounts  of
  supplemental fuel would be required for vapor abatement system.

 2.7.3.7        Cost  This criterion was defined in Section 2.5.3.7 for the landfill sites.  The
 comparative  analysis  for this criterion for Site OT-69 is summarized in Table 23.   Costs are
 presented on a present-worth basis over a period of 30 years, with a discount rate of 7 percent. A
 detailed cost analysis is presented in the RI/FS for the TCE/PCE Study Area (IT, 1995a).

 2.7.3.8       State Acceptance. This criterion was defined in Section  2.5.3.8 for the landfill
 sites. The comparative analysis for this criterion for Site OT-69 is presented below.

 Alternative G-l:  It is not likely the state would accept this alternative because it does not assure
 prevention of exposure in the event future land use plans change.

 Alternative G-2:  It is likely the state would accept this alternative because it assures protection
 of human health through periodic monitoring and deed restrictions.  The Lahontan  RWQCB has
 accepted this alternative provided the assessment of other more active remedies is considered as
 a contingency if the natural attenuation remedy is not restoring water quality in a timely manner.

Alternative G-3:  It is likely that this alternative would be perceived favorably because of the
short duration of the remedial action (approximately 1 year).  There may be objections to the
perception that there would be air emissions caused by this alternative; however, these would be
mitigated by proper abatement.  There may also be objection to the production of residual waste
(SVE condensate).
                                          2-99

-------
   Alternative G-4:  It is likely the state would accept this alternative because it assures protection
   of human health  through  periodic monitoring, deed restrictions, and  ultimate reduction of
   contaminants to acceptable levels (in approximately 10 years).

   Alternative G-5: It is likely the state would accept this alternative because it assures protection
   of human  health through periodic monitoring, deed restrictions, and ultimate reduction of
   contaminants to acceptable  levels (in approximately 10 years). There may be objection to the
   production of residual waste (spent GAC).

  Alternative G-6:  It is likely the state would look favorably at this alternative because it assures
  protection of human health through periodic monitoring, deed restrictions, and ultimate reduction
.  of contaminants to acceptable levels (in approximately 10 years). There may be objections to the
  perception that there would be air emissions caused by this alternative; however, these would be
  mitigated by proper abatement.  There may also be objection to the production of residual waste
  (spent acid wash).

  2.7.3.9      Community Acceptance.  As defined in Section 2.5.3.9 for the  landfill sites.
  Community acceptance indicates the public support for a given alternative. Section 3.0 of this
  ROD documents the community acceptance of the selected remedies,  as  presented in the
  Proposed Plan (Montgomery Watson, 1997b). Section 3.0 includes a responsiveness summary
 that addresses the comments received during the public comment period.  The community did
 not express any significant objections to the selected remedies during the public meeting or
 public comment period.

 2.7.4         The Selected Remedy for Site OT-69

 This section provides  a description  of the  preferred  alternative for Site OT-69 based on the
 detailed evaluation of alternatives presented in the RI/FS for the TCE/PCE  Study Area (IT,
 I995a).  This section includes the basis for selection of a preferred alternative, a description of
 the preferred alternative, and cost analyses.
                                         2-100

-------
  2.7.4.1       Selection of the Preferred Alternative.  The RAOs established for Site OT-69
  are presented in Section 2.7.2. The preferred alternative that best meets these objectives for Site
  OT-69 based on the comparative analysis of the alternatives with respect to the nine CERCLA
  criteria is Alternative G-2 (Institutional Controls/Natural Attenuation). This alternative assures
  protection of human health and the environment  through institutional controls, is effective at
  ultimately reducing contaminant concentrations to acceptable levels though natural attenuation,
  is very easy to implement, and is cost effective.

 2,7.4.2        Detailed Description of the Site OT-69 Preferred Alternative. Alternative G-2
 consists of natural attenuation with institutional controls which include land use restrictions
 prohibiting installation  of wells for domestic purposes in  the  affected  aquifer  and deed
 restrictions prohibiting  use  of contaminated  water.   Continued  monitoring  of the natural
 attenuation of  the  plume will  be achieved  through  an approved  long  term  groundwater
 monitoring plan.  More active remedies would be considered as a contingency if- the natural
 attenuation remedy is not restoring  water quality in a timely manner.  The criteria under which
 active remediation would be initiated at Site OT-69 were detailed in a memorandum prepared by
 IT which is included as Appendix  B to this ROD (IT, 1995b).  Details regarding the criteria
 established in this memorandum are  summarized  in Section  2.9.2.5.  If it is determined that
 natural attenuation is not restoring water quality, more active remedies would be assessed as part
 of the 5-year review process and may include alternatives assessed  as part of this ROD or
 additional new technologies that may become available.

 2.7.43       Cost Analysis.   A  preliminary  cost estimate  was  prepared for  the  selected
 alternative for Site OT-69 as part of the OU 3 FS process. Table 24 summarizes the cost analysis
 for Site OT-69.

 2.7.5        Statutory Determinations for Site OT-69

The selected remedy satisfies the statutory requirements of Section 121 of CERCLA, as amended
by SARA, in that the following mandates are attained:
                                         2-101

-------
        •      The selected remedy is protective of human health and the environment, will
               decrease site risks, and will not create short-term risk nor have cross-media
               consequences;
        •      The selected remedy complies  with federal  and state  requirements that  are
               applicable or relevant and appropriate to the remedial action such as chemical-
               specific  ARARs,  chemical-specific  clean-up  standards,  and action-specific
               ARARs;
        •      The selected remedy is cost-effective in  its fulfillment of the nine CERCLA
               evaluation criteria through remediation of Site OT-69 in a reasonable period of
               time;
        •      The selected remedy utilizes  permanent  solutions  and alternative treatment
              technologies or resource recovery technologies, to the maximum extent practical;

 The distribution of contaminants at Site OT-69 and prohibitive costs associated with treatment
 alternatives, preclude a remedy in which contaminants could be treated effectively.  Therefore,
 the selected remedy does not satisfy the preference for treatment as a principle element.

 2.7.5.1        Protection of Human Health and the Environment.  There  are currently no
 complete exposure pathways for the contaminated groundwater at Site OT-69.  Groundwater in
 the site areas is not used as a source of domestic, industrial, or agricultural supply.  Therefore,
 there is currently  no danger of  adverse exposure to either base personnel or residents.  In
 addition, the groundwater  does  not reach the ground surface  within  the base  boundaries;
 therefore, there is  no known exposure pathway to ecological  receptors.  Protection of human
 health and the environment at Site OT-69 is achieved through the selected remedy by ultimately
 achieving acceptable concentrations through natural attenuation.

 2.7.5.2       Compliance  with ARARs.  All pertinent ARARs identified  for Site OT-69
 (Table IS) will be met by the selected remedy.

2.7.5.3       Cost Effectiveness. The USEPA, the USAF, and the State of California believe
that the  selected remedy for Site OT-69 fulfills the nine criteria of the NCP and provides overall
effectiveness in relation to their costs.
                                        2-102

-------
  2.7.5.4       Utilization of Permanent Solution and Alternative Treatment (or Resource
  Recovery) Technologies to the Maximum Extent Possible.  The selected remedy represents, to
  the maximum extent to which permanent solutions and treatment technologies can be used, a
  cost-effective manner for addressing  Site  OT-69.  The alternative selected provides the best
  balance of long-term effectiveness  and  permanence; reduction  of  TMV through natural
  attenuation; short-term effectiveness; implementability; and cost-effectiveness.

  2.7.5.5       Preference for Treatment as a Principle Element

 The preferred alternative does  not incorporate active treatment.  However, concentrations of
 contaminants are reduced to levels determined to be protective of human health. The volume of
 affected groundwater is not reduced; however, the volume of groundwater with concentrations of
 contaminants resulting in excess risk is ultimately reduced to zero.

 2.8           DOCUMENTATION OF SIGNIFICANT CHANGES

 There are no significant changes in this ROD from the OU 3 Proposed Plan.

 2.9           CURRENT SITE STATUS

 The  preferred  alternatives described in this ROD are based on meeting the RAOs identified
 during the OU 3 FS process (Montgomery Watson, 1997a and IT, 1995a). The findings of the
 final OU 3 FS Report and the accompanying OU 3 Proposed Plan (Montgomery Watson, 1997b)
 were used  to  develop this ROD.  The technical information supporting each alternative is
 included in these reports and the OU 3 RI Report (Montgomery Watson, 1996a).

 In an effort to accelerate the remedial  process, to minimize present and future environmental
 risks, to reduce potential impacts to groundwater, and to facilitate timely transfer of property to
 the community, cleanup activities have  been initiated under the direction of the USAF, at some
of the sites presented in this ROD. These accelerated actions were performed in agreement with
the RPMs including the USEPA, DTSC, Lahontan RWQCB, and USAF. This work has been
                                      2-103

-------
 performed under the FSRA contract with the Air Force Center for Environmental Excellence
 (AFCEE).  Accelerated actions performed  to date have  implemented the proposed cleanup
 activities.

 The detailed alternatives evaluation for these sites presented in the OU 3 FS was performed prior
 to the initiation of the accelerated action; therefore, the FS alternatives comparison and  cost
 analysis are presented in the  previous sections of this ROD in its original form.  Table 25
 presents the current  estimates of present worth  costs  for the selected remedial alternatives
 incorporating the actual construction costs incurred to date for sites where accelerated actions
 were performed.

 The accelerated  actions performed  to  date are summarized in the sections below.   The
 effectiveness of these remedies will  be  assessed as part of the ongoing O&M and long-term
 groundwater monitoring and will be the focus of the 5-year site review.  As part of the 5-year
 review, the status of compliance  with ARARs will be  evaluated and reported.  The specific
 action items to meet the requirements of this ROD are presented in Appendix A.

 2.9.1        Landfill Sites

 Accelerated actions were performed at landfill sites DP-03, DP-04, LF-12. LF-14, LF-44, and the
 SEDA (nine sites).  The actions at the landfill sites began in June 1996 and were completed in
 April 1997. The preferred alternatives implemented for the landfills minimizes or mitigates the
 human health and ecological risks presented on Table  2  by providing  a  physical barrier to
potential contamination. A description of the barrier and the accelerated activities performed at
the landfill sites are discussed below.

Z9.1.1       Sites DP-03 and DP-04.  Grading the existing soil cover to promote surface
runoff and decrease infiltration of surface water into the refuse; installation of a 2-foot-thick
native soil cover to  reduce the potential of exposure to contaminants; installation of  site
perimeter fencing to control site access; installation of drainage  ditches  above the landfill to
prevent surface water from running onto the landfill sites; and re-establishment  of native plant
 •
                                        2-104

-------
  species on the graded surface.  Prior to construction of the soil cover at Site DP-04, hot spot
  removal was performed by removing approximately 10 cubic yards of soil to reduce potential
  risk to burrowing animals. This soil was disposed off site.

  2.9.1.2       Sites LF-12, LF-14, and the SEDA (Nine Sites).  Removal of surface debris;
  rehabilitation of the existing soil cover to produce a cover with an estimated thickness of 12 to 18
  inches; grading or cutting of the surface to promote surface runoff and decrease  infiltration of
  surface water into the refuse; installation of drainage ditches above the landfill to prevent surface
  water from running onto  the landfill sites; installation of site perimeter fencing to control site
  access; and re-establishment of native plant species on the graded surface.

 2.9.1.3       Site LF-44. Contaminants of potential concern were not detected in soil samples.
 Activities performed at this site included the removal of surface debris in September and October
  1995. This debris was disposed of off site.

 2.9.1.4       Groundwater Monitoring For  the  Landfill  Areas.   Regulations  require
 groundwater monitoring for each landfill site.  Groundwater monitoring at the landfill sites  is
 being performed as presented  in the Basewide Long-Term Groundwater Monitoring  Plan for
 GAFB  and the Site Closeout Report  for DP-03,  DP-04, LF-12,  LF-14, and the Southeast
 Disposal Area (Montgomery Watson, 1996c, 1997c).  Several rounds of groundwater monitoring
 have been completed under this plan (Montgomery Watson, 1996d,e;  1997d).

 As part of the monitoring  program, monitoring wells associated with the landfills are sampled
 and analyzed for halogenated volatile organic  compounds  (HVOCs) (EPA method 8260
 suggested), and landfill indicator parameters (pH, total dissolved solids, chloride, sulfate, and
 nitrate).  The sampling frequency and analyte selection  may  be  modified as the program
 progresses.

 Monitoring is used to assess whether contaminants have migrated into the environment.  Water
 Quality  Protection Standards (WQPS) will be developed to assess  whether there has been a
release from the landfills.  The WQPS will be developed within 6 months of the signing of this

                                        2-105

-------
  ROD and will be based on the available groundwater data to establish baseline values for which
  future sampling results will be compared.

  2.9.1.5        Ecological Monitoring  For the Landfill Areas.   The  landfill remediation
  consisted of activities that would minimize exposure of landfill wastes to ecological receptors.
  For example, landfill remediation consisted of the installation of a 12- to 24-inch native soil
  cover as described above. During construction of the remedy, the native soil was compacted by
  grading. Site access is controlled by fencing. The fence was installed to a depth of 1 foot bgs.
 The sites were revegetated with native plants.

 Although the soil was compacted during construction, the sites provide potential habitat for
 burrowing animals that can burrow under or move  through  small  openings in the fence.
 Burrowing animals could potentially compromise the effectiveness of the cap as a barrier
 between the waste and the surrounding  ecosystem.  Burrowing animals that could potentially
 enter the area include special-status species such as the Mojave ground squirrel, Mojave vole,
 desert tortoise, San Diego homed lizard, and burrowing owl. Other species that may impact the
 soil cover include the coyote, badger, and kangaroo rat.

 The soil covers at each site will be maintained by surveying for animal burrows. The Air Force
 will consult with the  State Department of Fish and Game to develop a burrows management
 protocol for the O&M document.  A contingency plan for recurring burrow problems and the
 specific  details of the ecological monitoring plan  will be presented in the subsequent O&M
 document.

 The maintenance activity schedule is presented in the Site  Closeout Report for DP-03, DP-04,
 LF-12, LF-14, and the Southeast Disposal Area (Montgomery Watson, 1997c). The schedule to
 implement any recommended repairs noted during the routine maintenance inspections will vary
 depending on  the type of repair.  Minor repairs may be  implemented in  30 days, but more
 difficult  or more costly repairs  may require more time  to implement.   Implementation of
revegetative repairs will be limited by seasonal conditions relating to the plant's life cycle.  An
effort will be made to make revegetative repairs as soon as it is practical based on seasonal

                                        2-106

-------
   timing.  The subsequent routine maintenance inspection will note if the recommended repairs
   were made.

   2.9.2         TPH/VOC Sites

   Accelerated actions at petroleum TPH/VOC sites were conducted to minimize present and future
   environmental risks, reduce potential impacts to groundwater, and facilitate reuse as described
   below. Access and land use will be restricted at all sites.  These restrictions on site use will be
   subject to re-evaluation as remediation efforts progress.  It is anticipated that this land will be
   used only for industrial purposes.

  2.9.2.1       Sites WP-17, FT-19a, and OT-51 (Soil).  Soil at these sites is currently being
  treated with bioventing.  The bioventing systems were installed from December 1995 through
  April 1996 and are currently in operation.

  2.9^2        Site FT-19b.  Petroleum contamination at this site was evaluated in the OU 3  FS
  Report and the site is recommended for NFA (Montgomery Watson, 1997a). Medical waste
  found on the surface was removed and disposed off site. Downgradient monitoring will continue
 to assess groundwater quality.

 2.9.2.3       Site FT-19c.  Soil at this site is currently being treated with SVE.  The SVE
 system was installed from December 1995 through March 1996 and is currently in operation.

 2.9.2.4       Site OT-51 (Groundwater).  The groundwater data collected since September
 1995 at Site  OT-51 as part  of the long-term  groundwater monitoring effort (Montgomery
 Watson, 1996d,e,f; 1997d,e,f) have indicated that the COPCs in groundwater increased slightly
 and  then began decreasing.  It is expected that  the plume  will be below detectable levels of
 benzene in  5 years.  If subsequent rounds of long-term monitoring do not continue to show the
 trend of decreasing levels of COPCs. the contingent remedy of installation of oxygen-releasing
chemicals described for Alternative 11 (Section 2.6.2.6) will be implemented.
                                        2-107

-------
 2.9.ZS       Site O1V69.  The Lahontan RWQCB has accepted Alternative G-2 (Institutional
 Controls/Natural Attenuation)  provided the assessment of  other more active remedies  is
 considered as a contingency if the natural attenuation remedy is not restoring water quality in a
 timely manner.  The criteria under which active remediation would be initiated at Site OT-69
 were detailed in a memorandum prepared by IT which is included as Appendix B to this ROD
 (FT. 1995b).  The contents of this memorandum are summarized below.

 The monitoring and response plan proposed by the USAF was developed based on computer
 modeling simulations that estimate specific future concentrations  in particular wells projecting
 that water quality  objectives will be restored  in  approximately  50  years.  If the  expected
 reductions do not occur in the projected time frame, plus or minus  15% of  the projected
 concentration, then the data will be evaluated. If the data are less than two standard deviations of
 the projected concentrations, then monitoring may continue.  If the data are greater than  two
 standard deviations, then the wells will be resampled and the data reevaluated. If the data are
 still greater than two standard deviations of the original projected concentrations, then an active
 remedy consisting of air sparging with soil vapor extraction will be implemented or the agencies
 will reach consensus regarding  a technical decision for implementing some other  appropriate
 active remedy. The ROD will be amended at that time to specify the ARARs for the contingent
 remedy.

 As part of the remedy for Site OT-69,  groundwater will be  monitored and the data will be
evaluated.  If measured TCE concentrations exceed the predicted ranges presented in Appendix
B, the following steps will be taken:

       1)    Determine the variability of the analytical method employed at the time of the
             analysis.
       2)    Consider the analytical standard deviation and calculate the possible contaminant
             concentration range.
       3)    Determine if the  calculated range in  concentration is two standard deviations
             above the predicted concentration range.
                                        2-108

-------
        4)     If the concentration is two standard deviations above the predicted concentration
               range, initiate verification measures.
        S)     If the concentration is  less than two standard deviations above the predicted
               concentration range, maintain routine sampling schedule.

 If it is determined that natural attenuation is  not restoring water quality, more active remedies
 would be assessed as part of the 5-year review process. If a more ac.tive remedy is determined to
 be warranted, the USAF will make a timely request for funds by identifying to the Department of
 the Air Force the funding needed to complete the activities in accordance with Executive Order
 12088 and OMB circular A-106 (which is updated bi-monthly and for which funding requests are
 made  at least two years in advance when possible), or any pertinent amendments to these
 requirements.

 In the event that Congress fails to appropriate necessary funding for OU 3  ROD activities at
 GAFB, the following will occur:

              the USAF will so advise all FFA signatories within 90 days of such failure; and
              the USAF will provide to all FFA signatories documentation of all measures it
              will undertake to ensure that ROD activities are completed. These measures may
              include, but are not limited to,  continuing to seek funding for implementing the
              contingent remedy.

2.9.2.6       System Monitoring of the TPH/VOC Sites.  A vapor monitoring  program for
the bioventing and SVE systems was developed based on field observations and on the results of
pilot testing before  system startup. Field monitoring at the bioventing and SVE sites includes
routine system maintenance  and monitoring of soil vapor to document reductions in  petroleum
TPH/VOC concentrations and to determine the effectiveness of cleanup.  At the bioventing sites,
soil gases (oxygen  and carbon dioxide) are monitored because they can indicate changes in
biological activity.   Increased biological activity  is an indicator of  biodegradation of  the
hydrocarbon compounds.  Soil vapor monitoring  is conducted by collecting soil  vapor from
monitoring points installed at  various locations at  the sites.   Confirmation  samples (soil and
                                         2-109

-------
 vapor) will be collected as necessary from the TPWVOC sites to confirm completion of the
 remedy prior to closure of the sites.

 2.9.2.7       Groundwater  Monitoring For the TPH/VOC Sites.  Groundwater monitoring
 at applicable sites will be performed as presented in  an approved long-term groundwater
 monitoring plan for GAFB.  Several rounds of groundwater monitoring have been completed
 under this plan (Montgomery Watson, 1996d,e,f and 1997d,e,f).  The sampling frequency and
 analyte selection  may be modified as the program progresses.  The rationale for system shut
down will be provided in subsequent RD/RA documents.
                                     2-110

-------
                                                     §
                                                     w
           Section 3
MONTGOMERY WATSON

-------

-------
                         3.0 RESPONSIVENESS SUMMARY

 3.1          OVERVIEW

 The public comment period for the proposed plan began on September 22, 1997 and ended on
 October 22, 1997.  A public notice summarizing the OU 3 Proposed Plan, and announcing the
 public comment period and public meeting was printed in the Daily  Press in Victorville, the
 Desert Dispatch in Barstow, and the Sun in San Bernardino at the start of the public comment
 period.  A press release was sent to five other local newspaper and  radio organizations also
 summarizing the OU 3 Proposed Plan and announcing the public comment period and the public
 meeting.

 The public meeting was held on October 8, 1997 at the Green Tree Inn, Victorville, California.
 Representatives  from USAF,  DTSC,  USEPA, and Lahontan  RWQCB  were present at the
 meeting.  No members of the community attended. During the public comment period, written
 comments were received from the SCIA and the City of Victorville in  a letter dated October 3,
 1997.

Judging from the  comments received, the community accepts the USAF's preferred remedial
 alternatives for the 60 OU 3IRP sites.

3.2          BACKGROUND ON COMMUNITY INVOLVEMENT

The USAF values public input and has endeavored to maintain public involvement since the
beginning  of the environmental investigation and cleanup activities at GAFB.  A chronological
history of the community involvement with environmental issues at the GAFB is summarized
below.

In November 1987, GAFB provided information about environmental  concerns at the base as
part of the "GAFB Community Days" activities. In 1988, a repository of information for public
review was established at the GAFB library.  In early 1990, similar repositories were established

                                        3-1

-------
  at the Adelanto and  Victorville public libraries.  Administrative files  for the project are
  maintained at the GAFB AFBCA located in Building 321.  In October 1992, GAFB held an
  informational open house to discuss the environmental cleanup program and visit the potentially
  contaminated sites.

  In July 1991, GAFB established a TRC that consisted of members of the community  and local
  agencies  and governments.  The TRC met on a quarterly basis.  In January 1994,  GAFB
  established the RAB which  replaced the TRC. The RAB is designed to act as a focal point for
 environmental information exchange between GAFB and the public. The  RAB met  quarterly
 until 1997 when it voted to meet annually. The meetings are open to the public.  An RAB and
 community update meeting was held June 4, 1997, in Victorville, California.

 33          SUMMARY  OF  COMMENTS  RECEIVED  DURING THE  PUBLIC
             COMMENT PERIOD

 Comments received during the GAFB OU 3 public comment period on the final FS and Proposed
 Plan are summarized below.  The comment period was held from September 22, 1997 to October
 22, 1997.  The comments are presented in the order in which they were received and copies of
 comments arc included as part of the administrative record (Appendix C).

 PubUc Meeting:  No comments were received during the public meeting.

Written Comments:

 1.    The SCIA and the City  of Victorville issued a letter dated October 3, 1997 containing
      comments as summarized below:

      a)     Concerned was expressed that the implementation of Alternative 4 (Soil Cover) to
             Sites DP-03 and DP-04 would restrict future reuse of the land in  this  area.
             Additionally, the question was asked as to what would be the cost associated with
            remediating the sites such that future reuse would not be limited.

                                       3-2

-------
 b)     The SC1A inquired as to whether the preferred alternative constituted cleanup for
        Sites DP-03 and DP-04.

 c)     A request for clarification was made as to what is meant by  the "preferred
        alternative,"   what alternatives were  evaluated  other than  the  "preferred
        alternative,"  and whether the preferred alternative is permanent.

 Air Force Response: The response to these comments is as follows:

 a)     As part  of the  FS process (Montgomery Watson, 1997a),  technologies were
        evaluated and screened as to whether they would be appropriate for the landfill
        sites.  The only technology that would allow unrestricted reuse of Sites DP-03 and
        DP-04 would be removal of all  wastes  and disposal  at an  off-site facility.
        Removal and disposal of was "screened out" as  a potential technology largely
        because of the impracticality of the technology  given  the  heterogeneity and
        volume of the  wastes.   The  general  CERCLA  experience  has led to  the
       establishment of containment as the appropriate response  for landfill sites.  This
        issue is discussed in additional detail in Sections 4.2 and 5.4 of the OU  3  FS
       Report (Montgomery  Watson,  1997a).   Because  removal and  disposal was
       screened out as a technology, it was not considered in the alternatives evaluation
       phase of the FS process. Therefore, a detailed cost analysis was not performed  for
       this option. However, it is anticipated that removal and disposal of all wastes at
       these sites would be cost prohibitive.

b)     The preferred alternative  would constitute cleanup of the sites and its selection
       would be documented with the signing of this OU 3 ROD.

c)     The term "preferred alternative" refers to the remedial option that is determined to
       best meets the nine CERCLA criteria of 1) overall protection of human health and
       the environment, 2) compliance with ARARs, 3) long-term  effectiveness and

                                   3-3

-------
 permanence, 4) reduction of TMV through treatment, 5) short-term effectiveness,
 6)  implementability, 7)  cost,  8) state/support agency  acceptance,  and  9)
 community acceptance.

 The preferred alternative selected for Sites DP-03 and DP-04 is Alternative 4 (Soil
 Cover). However, five separate alternatives were evaluated for these sites.  The
 alternatives evaluated for these sites were as follows:
        Alternative 1  (No Action with Monitoring)
        Alternative 2  (Institutional Controls)
        Alternative 3  (Surface Controls/Existing Cover Rehabilitation)
        Alternative 4  (Soil Cover)
        Alternative 5  (Synthetic Cap)

The selection of the Alternative 4 for Sites DP-03 and DP-04 is considered to be
the most effective to minimize present and future environmental risks, reduce
potential impacts to groundwater,  and facilitate timely transfer of the surrounding
property to the community.  The implementation of the preferred  alternative
would be the permanent  solution  pending 5-year review of monitoring activities
as required by CERCLA.
                             3-4

-------
                                    REFERENCES

 Boyle Engineering Corporation (Boyle), 1987.  "Alter Base Water Supply/George Air Force
       Base, Victorville, California.  Well Field Analysis." San Bernardino, California.

 CH2M Hill,  1982.  "Installation Restoration Program Phase I Records Search for George Air
       Force Base, California."  Gainesville, Florida

 CRSS Constructors,  Inc., 1996.  "Activation Plan for the Southern California International
       Airport." Irvine, California. July 1996.

 Hinchee, R.E., S.K.  Ong, R.N. Miller, D.C.  Downey, and R.  Frandt,  1992.  Test Plan and
       Technical Protocol for a Field Treatability Test for Bioventing, Revision 2. Prepared for
       the U.S. Air Force Center for Environmental Excellence,  Brooks Air Force Base, Texas.
       May 1992.

 International  Technologies Corporation (IT),  1991.   "Community Relations  Plan for the
       Installation Restoration Program at George Air Force Base, California." San Bernardino,
       California, April 1991.

 IT, 1992.  "Remedial Investigation, Operable  Unit 2, JP-4 Spill, George Air Force Base,
       California." San Bernardino, California, April  1991.

 IT, 1995a.  "Remedial Investigation Feasibility Study, OU 3 TCE/PCE Study Area, George Air
       Force Base, California." San Bernardino, California.  July 1995.

 IT, 1995b.  "Criteria for Active Site Remediation - OT-69," from Kandi Brown of IT to Denise
       Caron of the AFBCA. November 6,1995.

James M. Montgomery, Consulting Engineers,  Inc.  (JMM), 1988.   "Installation Restoration
       Program, Phase FV-A Feasibility Study.  Northeast Disposal  Area, Upper Aquifer
       Remediation.  George Air Force Base, California."  Pasadena, California, April 1988.

JMM, 1992.  "Work Plan Addendum, Operable Unit 3,  George Air Force  Base, California."
       Walnut Creek, California. August 1992.

Leaking Underground  Fuel Tank (LUFT)  Task Force, State of California, 1989.   Leaking
       Underground Fuel Tank  Field Manual:  Guidelines for Site Assessment, Cleanup, and
       Underground Storage Tank Closure.  October 1989.

LSA  Associates. Inc. (LSA), 1989.  "Biological Assessment of the Montgomery Engineers
       Groundwater Contamination Remediation System." July 1989.

Metcalf & Eddy (M&E), 1994.  "Remedial  Investigation Summary Report for Soil Removal at
       Miscellaneous  OU 3 Sites.  George Air Force Base,  California."  Redwood City,
       California. June 1994.                                   *


                                         R-l

-------
                                     REFERENCES
                                       (Continued)


   Montgomery Watson, 1994.  "Record of Decision, Operable Unit 1, George Air Force Base
         California." Walnut Creek, California. March 1994.

   Montgomery Watson, 1995a.  "Work Plan for Remedial Activities at Sites WP-17  FT-19a FT-
         19b, FT-19c, OT-51 and the Oil/Water Separators, George Air Force Base, California "
         Walnut Creek, California. August 1995.

  Montgomery Watson 1995b.  "Pre-Design Study, Operable Unit 1, George  Air  Force Base,
         California." Walnut Creek, California.  October 1995.

  Montgomery Watson, 1995c.  "Basewide Long-term Groundwater Monitoring Work Plan/Field
        Sampling Plan, George Air Force Base. California." Walnut Creek, California.  October


  Montgomery  Watson, 1996a.  "Remedial Investigation Report, Operable Unit 3,  George Air
        Force Base, California." Walnut Creek, California.  April 1996.

  Montgomery Watson, 1996b.  "Closure and Post-Closure Maintenance Plan for DP-03 DP-04
        LF-12, LF-14, and the Southeast Disposal Area, Technical Plan, and Quality Program'
        Plan, George Air Force Base, California." Walnut Creek, California. April 1996.

 Montgomery Watson, 1996c.  "Basewide Groundwater Monitoring Sampling and Analysis Plan,
        George Air Force Base, California." Walnut Creek, California. September 1996.

 Montgomery  Watson. 1996d.    "Basewide  Long-Term  Groundwater Monitoring  Report
        September  1995 Sampling Event, George Air Force Base, California."  Walnut Creek
        California.  March 1996.

 Montgomery Watson, 1996e.  "Basewide Long-Tenn Groundwater Monitoring Report, January
        1996 Sampling Event, George Air  Force Base, California." Walnut Creek.  California
       August 1996.

 Montgomery Watson, 1996f.   "Basewide  Long-Term Groundwater Monitoring Report.  May
       1996 Sampling Event, George Air Force Base, California."  Walnut Creek,  California
       October 1996.

Montgomery Watson, 1997a.  "Feasibility Study Report, Operable Unit 3, George  Air Force
       Base, California." Walnut Creek, California. February 1997.

Montgomery Watson, 1997b.  "Proposed Plan for Operable Unit  3, George Air Force Base
       California."  Walnut Creek, California.  September 1997.
                                        R-2

-------
                                     REFERENCES
                                      (Continued)

  Montgomery Watson, 1997c.  "Site Closeout Report for DP-03, DP-04, LF-12, LF-14, and the
        Southeast Disposal Area, George Air Force Base, California."  Walnut Creek, California
        June 1997.

  Montgomery Watson, 1997d.  "Basewide Long-Term Groundwater Monitoring Report, October
        1996 Sampling Event,  George Air Force Base, California."  Walnut Creek, California
        February 1997.

  Montgomery Watson, 1997e. "Basewide Long-Term Groundwater Monitoring Report, February
        1997 Sampling Event, George Air Force Base, California."  Walnut Creek, California
        June 1997.

 Montgomery Watson, 1997f. "Basewide Long-Term Groundwater Monitoring Report, July 1997
        Sampling Event, George Air Force Base, California." Walnut Creek, California.  October


 Norris, R. M., and R. W. Webb, 1990. Geology of California. Second Editinn  John Wiley &
       Sons, Inc., New York, New York.

 Regional  Water Quality Control Board  (RWQCB), 1995.  "A Compilation of Water Quality
       Goals." RWQCB, Central Valley Region, Sacramento. California. July 1995.

 Science Applications International Corporation (SAIC). 1987. "Installation Restoration Program
       - Phase II - Stage 2 Confirmation/Quantification (Final  Report), George Air Force Base.
       California." Bellevue, Washington.  January 8,  1987,

 Thomas Bros. Maps, 1992. California Road Atlas and Driver's Guide. Irvine, California.

 U.S. Air Force (USAF), 1989.  "Closure of George Air Force Base,  San  Bernardino County.
       California, Draft Environmental Impact Statement." December 1989.

 USAF, 1992. "Environmental Impact Statement, Disposal and Reuse of George Air Force Base
       California." March 1992.

 USAF, 1993. "Management Action Plan (MAP), George Air Force Base, California." October
       19, 1993.

U.S. Environmental Protection Agency (USEPA), 1988.  Guidance for Conducting  Remedial
      Investigations  and Feasibility Studies Under CERCLA.  Interim  Final.   Office  of
      Emergency and Remedial Response,  Washington, D.C., EPA/540/G-89/004, October
       1988.
                                        R-3

-------
                                  REFERENCES
                                    (Continued)

USEPA,  1989.  Risk Assessment Guidance for Superfand.  Vol. 1: Human Health Rvaluatinn
       Manual, Part A, Region EX Recommendations, Office of Solid Waste and Emergency
       Response, December 1989.

USEPA, 1990. A Guide to Developing Superfund Records of Decision.  Office of Emergency
       Response, Hazardous Site Control Division, Directive: 9335.3-02FS-1. May 1990.

U.S. Geological Survey (USGS),  1992.  "Streamflow Reports for the  Mojave River,  1905
       through 1992." Published and unpublished records.
                                      R-4

-------
                                                         I
            Figures
MONTGOMERY WATSON

-------

-------
                                                   •  $ SILVER
                                                     =  MTN  S
                                           B*M   \  ~  SPARKHULE
                                            I         '      MTN
                                                                                             Lucun* Valtay^.
                                                                              SAN
                                                                          BERNARDINO
                                                                          MOUNTAINS
               """OrllE!.       x.  J

,,„•,,  /      MOUNTAINS        \\

     '*.                          '^
                                                                          GEORGE AIR FORCE BASE
                                                                               VICINITY MAP
       SCALE IN MILES

 Source: ModHod from Thoow Btot. Maps (1W2)

-------
                              vs( shewn.
          WV, DT-4S OT-61. OT-6Z. WP-63. OT-64. OT-ffi. asd OT-6S;
2l SEDA S4ift «K4XJ9 LF-tt?. IP-PS, RW-OS,OfMO. W. (5.


-------
      5    •Jox*>
        XV,  \
"•..  \       "•-%„  Ji
                        /    p  \ cr  "	'X v-«-   A v-  ->. v
                            /    \ ™>ntlll    \     VS.  -.    %\
                            /A***.***^ $     "',   X.      \JohnmX    V\

                        ^£!ssi^       	'•""'*"	^"-,  ^
•%,„
     "mi,,,
                                                GEORGE AIR FORCE BASE

                                               REGIONAL PHYSIOGRAPHY
 Sowc*: MMMM tan Thexno Bnw. Map* (1932) ant Nonfc «l «l. (1880)

-------
               He*p«ria

            MOJAVE
               BASIN —
                •    X
GulnBoundoy
                                                                      SCALE IN MILES


                                                                       0    5   10
LEGEND
     Psrann!*! Bowing Stream
	InMonlMnt Flowing Stream

— AppKcdmatiLocallonofQ«orgaGreun«atin
     {SUMUifKB Surveys, 1990)
 SOOfCfc 3MC.IM7
     MUNIhUMUl WHTSON



MAJOR HYDROGEOLOGIC FEATURES

    IN THE MOJAVE RIVER BASIN


             FIGURE 4

-------
                                                                           0   ^^P      \

                                                                        APPROXIMATE SCALE IN MILES
LEGEND
 O Municipal W*W Supply MM

 O Domestic Wat«r Supply Wrt

 £  Surface Spring
/
Approximate Dirtction erf
Groundwatw Row in Upper
AquKtr
Approximata Oiraction of
Qroundwatar Bow in Lower
AquHw
w««« •!• «ppTOjdmimy locawd bisod on C«lltoini« O«p«mr>«ni wuer Rnourew rncord*
      MONTMMBIY MMTSON


  APPROXIMATE LOCATIONS OF
     KNOWN MUNICIPAL AND
DOMESTIC WATER-SUPPLY WELLS,
          QAFB VICINITY


             FIGURE 5

-------
                                                                               N
                              •-_.  —Ti   <       .   -^  , ^ •	,/
                                 1 -  !L	i.-j	.*. f  '—•'•.  '-
LEGEND
Q OU3STTE

    OT-69 TCE PLUMES (OU 3)
                  SCALE W FEET
    GEORGE AIR FORCE BASE
OPERABLE UNIT 3 FEASIBILITY STUDY
         SITE LOCATIONS
                                                                               Figure
                                                                                 6

-------
          Existing Condition
                                                         Wastes)
         Implementation of Surface Controls
Add Native Soil .
 From •QH'Sit© 5
       Areas
                                                      Remove Wastes From the S;
                                                       k Grade to * 5% Jvfcnimun
        Result
                                                 , Rehabilitated Sod Cover
                                                                  ,. Revegstc

                                                         ±^L    *
                                                        K
                                                              W

-------
        Alternative 4: Native Sofi Cover
                                           24-«ich Thick Soil Cowef
                                                   X"
                                                                            Revegetati
                        *          V  ~  *
Drainage Channel
                                                                      Graded Surface
                                                                     {Min. l.S% Slope)
       Attcrnative 5: Synthetic Cap
                                                  24-inch Thick Soi! Cover
   /
Drainage Channel
                                                                           -Surface
                                                                    (M?n. 1.5% Slope)

-------
                                                                                     id Surfs
                                         10,000
                          TPH(«»g«oljnt)    1,000
                          Benzene             t
                          Toluene             50
                          Elhytfaanzena         so
                          Total Xytenw         so
                        8
TPH (as dies*)
TPH(ugaaolrM)
Bwuen*
Toktww
EOtyltenzww
Total Xytonw
1.000
100
0.3
0.3
1
t
                                         TPH(MOlM«0       100
                                         TPH (at gasoline)      10
                                         BarcniM         0.005
                                         ToltMn*          o.OOS
                                                        0.005
                                                        0.015
                                                                               Water Tabl*
         Nods:
         Not to •ate
         Unttt •/• mg*g (pprn)
Soure»: (LUFTTuk Face*. 1988)
    GEORGE AIR FORCE BASE
REMEDIATION GOALS FOR SOILS
  AT THE OU 3 TPH/VOC SITES

            RGURE9

-------


g"
A
















	
i




S"


















k




p













TCE


1

k


.

s










7,50


TOE




k




?






//%M^
f&*


900


TCE 37S


TCE 100

I
TCE 30 j

1 k
| TCE 12.5
§
' b — — — — — •
t TCE 0.6 I
?> I... .. I
	 [ 	 v_ _„ __y**??$*___. _
        Nou*:
        Not to teal*
        Unte v* M»*0 (ppb)
Souic*, SESCML MixMIng «t nr-ISedMtad k> ttw OU 3 FS.
    MONTCOMBIYWftTSON
   GEORGE AIR FORCE BASE
REMEDIATION GOALS FOR TCE
   IN SOILS AT SITE FT-19C

          FIGURE 10

-------
            Discharge to
            Atmosphere
                                                             Flow
                                                            control
                                                            valva
                                                Air-water
                                                separator
Temperature
   gauge
                                    Blower
                                                                  Air velocity
                                                                  rotameter
Vacuum
 gauge
                        1
                             AIR
                             EXTRACTION
                             WELL
Not*: Not to Scale
                       SCHEMATIC OF SVE
                         SYSTEM DESIGN

                            FIGURE 11

-------
     Male
     quick
    connect
   \.
                       Moisture
FemaJa
 quick
connect
      A
                                  Sampling
                                   pump
                   ^-^&-
                                                                            Analyzer
               'Soil vapor monitoring point
                                        Not to Scale
Modilitd from Hnctwt. H. (1.1992.
                                                       MONTGOMDmHKTSON

                                                       SCHEMATIC DIAGRAM OF
                                                     SOIL VAPOR SAMPUNG FROM
                                                          MONITORING POINT

                                                               FIGURE 12

-------
      Air from
    Atmosphere
Vacuum gauge
 Flow
control
 valve
Temperature
   gauge
Pressure
  relief
  valve
Pressure
 gauge
                      Air filter
               Blower
                                                          Air velocity
                                                          rotameter
                                                                          AIR
                                                                      INJECTION
                                                                         WELL
Note: Not to Scale
                                                                 MONTGOHEKVWKrSON

                                                               SCHEMATIC OF BIOVENTING
                                                                    SYSTEM DESIGN


                                                                       FIGURE 13

-------
            KEY HAT
                                          OT-69TCEPIumn
                                          (OuUlo* is 5 H9/L Contour)
                                                                       APPROXIMATE SCALE IN FEET
So«c»,
     MONTGOMDIV MWCT50N
GEORGE AIR FORCE BASE
 SITE OT-69 LOCATION MAP
Figure
  14

-------
                                                            s-
                                                            8
            Tables
MONTGOMERY WATSON

-------

-------
                   TA6lfil




RECOMMENDED REMEDIAL ALTERNATIVES FOR OU 3 SITES
Site
DP-OI
DP-02
DP-03
DP-04
LF-07"
LF-08*
RW-09*
DP-IO*
*
LF-ll
LF-12
LF-13
LF-14
DP-15*
WP-16
WP-17
SD-18
FT-19a
FT-19b
FT-I9C
FT-20(soil)
SS-21
OT-22
SS-23
SS-24
SD-27
SD-28
WP-29
WP-32
DP-33"
Description
Paint drum burial
Pesticide and paint burial
Acid and oil burial
Pesticide and oil burial
Base landfill
Tctraethyl Lead (TEL) disposal
Radioactive disposal
Landfill (cartridges)
Landfill (paper)
Landfill street sweeping: disposal site
Original base landfill
Base landfill
Munitions/oil
POL leach field
POL leach field
Fuel and oil disposal
Fire training area
Waste burn pit
Fire training area
Abandoned fire training area
Tip tank drainage area
Golf course/waste water treatment plant imgatioi
Salvage yard/hazardous waste storage yard
Building 580 unserviced transformer storage
Abandoned drain pit/dry well
Abandoned drain pit/dry well
Sludge drying beds
Leach field
Munitions
Presenting
Selected
Remedy
WPA
WPA
OU3FS
OU3FS
OU3FS
OU3FS
OU3FS
OU3FS
WPA
OU3FS
OU3R1
OU3FS
OU3FS
OU3RI
OU3FS
WPA
OU3FS
NA
OU3FS
OU3FS
OU3RI
WPA
OU3RI
WPA
OU3RI
OU3RI
WPA
OU3RI
OU3FS
Activities
Conducted
By:


MW
MW
MW
MW
IT
MW
-
MW
MW
MW
MW
M&E
M&E
-
M&E
M&E
M&E
MW
M&E
.
M&E
.
M&E
MW
.
MW
MW
Reuse
Parcel
(USAF.1993)
D
A,D
A
A
K
K
K
K
K
D
C
A.D
K
D
D
A, B
A
A
A
C
C
F.J
D
C
D
C
C
C
K
	 Selected Remedy 	
NFA
NFA
Alternative 4 (Soil Cover)
Alternative 4 (Soil Cover)
Alternative 3 (Surface Controls/Existing Cover Rehabilitation) *
Alternative 3 (Surface Controls/Existing Cover Rehabilitation)*
Alternative 3 (Surface Controls/Existing Cover Rehabilitation) *
Alternative 3 (Surface Controls/Existing Cover Rehabilitation) *
NFA
Alternative 3 (Surface Controls/Existing Cover Rehabilitation)
NFA
Alternative 3 (Surface Controls/Existing Cover Rehabilitation)
Alternative 3 (Surface Controls/Existing Cover Rehabilitation)'
NFA
Alternative 9 (Biovenling)
NFA
Alternative 9 (Bioventing)
Alternative 6 (No Action With Monitoring)
.. Alternative 8 (Soil Vapor Extraction)
NFA
NFA
NFA
NFA
NFA
NFA
NFA
NFA
NFA
Alternative 3 (Surface Controls/Existing Cover Rehabilitation) '

-------
                                              RECOMMENDED REMEDIAL ALTERNATIVES FOR OU3 SITES
                                                                      (P*«e2or3)
                                            Sttecled
 DP-34*
  LF-35
  LF-36
  LF-37
  LF-38
  LF-39
WP-401
 SDMI
 SD42
 LF-43
 LF-44
 LF-45
 DP-46
 DP-47
 OT-48
 OT-49
 OT-50
 OT-51
SS-52*
 SS-53
 SS-55
 ST-56
 SS-59
DP-60
OT-61  ,
OT-62
WP-63
OT-64
OT-65
  Munilioru/bombs
  Landfill (wood/debrit di$pos«J)
  Conslniclion debris/botrow pit
  Landfill (road nuttritls buriil)
  Trash disposal
  Conilruction debris/trmh
  Chemical toilet iludje
  Riprap for industrial drain dischtrje
  Ripnsp for off-base water supply
  Rubble disposal
  Misc. trash/rubble disposal
 Conslniclion demolition
 F-l 11 Aircraft burial
 Aircraft parts burial
 Salvage yard
 Aircraft crash residues
 Earth embankment
 Test cells 799
 Creosote spill area
 Jet fuel spill
 Fuel spill collection point
 Spill near Building 549
 Building 819 fuel spill
 Sewerage sludge disposal
 Shop waste disposal area
 Rinse  water disposal pit
 Sewage sludge disposal areas
Transformer sites
Outlying revetments
OU3FS
WPA
WPA
OU3RI
OU3RI
OU3RI
OU3FS
WPA
WPA
WPA
OU3FS
WPA
OU3R1
OU3RJ
WPA
WPA
OU3RI
OU3FS
OU3FS
WPA
OU3RI
OU3RI
OU3FS
OU3R1
WPA
WPA
WPA
WPA
OU3RI
MW
.
,
MW
MW
MW
MW
.
.
.
MW
_
MW
MW
.
_
M&E
M4E.MW
MW
.
MW
MW
M&E
MW
.
_
,
_
MW
                                                                 Activities
                                                                 CtoKbcted       P»«d
                                                                    By:      JUSAF. 19931
   K
 A.D
   A
   B
   B
 D.J
   K
  A
 NA
  A
  D
  A
  D
  C
  D
 NA
  B
 B
 K
 D
 C
 C
 B
 A
NA
NA
NA
NA
NA
 Allemttive 3 (Surface Controls/Existing Cover Rehabilitation)'
       Lind Use Restrictions/Posting of Warning Signs
                         NFA
                         NFA
                         NFA
                         NFA
 Alternative 3 (Surface Controls/Existing Cover Rehabilitation)1
                         NFA
                         NFA
                         NFA
            Alternative 2 (Institutional Controls)
                         NFA
                         NFA
                         NFA
                         NFA
                         NFA
                         NFA
     Alternatives 9 (Bioventing) and Natural Attenuation
Alternative 3 (Surface Controls/Existing Cover Rehabilitation)'
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA
                        NFA

-------
                                                                     T.
    Site
Notes:
                         Description
                                   RECOMMENDED REMEDIAL ALTERNATIVES FOR OU 3 SITES
                                                           (p«tt3of3)

                                                 it   InvatJg»ti(m"
                                         Presenting    Activities       Reuse
                                          Selected     Conducted       Parcel
                                          Remedy
OT-66 Nonpoinl-source residential housing WPA
WP-68 Paint disposal pit
OT-69 fCEfKE Plume

OU3RI MW
ITRI/FS IT
IRP Site Total 60 b
JUMF, mj)
NA
£

— - — - — — — — ___^_^^__ _
                                                                                                              Selected Remedy
                                                                                                                   NFA
                                                                                                                   NFA
  located outside of the FS remediation boundary
b Sites FT- I9a and FT- I9c mj counted as one site.
                                                                                             Alternative G-2 (Natural Attenuation/Institutional Omimlci
                                                                                  '      '  M°' ™d SS'52' Slle LIM ' is P"1 of *" SEDA: «">*ev«r, it is
Acronyms:  FS = OU 3 Feasibility Study Report (Montgomery Watson. I997a)
          IT RI/FS = IT KUFS for OU 3 PCOTCE Study Area (IT. I995a)
          M&E = Melcalf&Eddy
          MW = Montgomery Watson
          NA = Not Applicable
          NFA = No Further Action
          OU = OperaMeUnit
          PCE = letrachloroelhene
          RI = OU 3 Remedial Investigation Report (Montgomery Watson, I996a)
          TCE = irichloroethene
          WPA B Wotk Plan Addendum (JMM, 1992)

-------
                                                                   TABLE2

                                        SUMMARY OF OU 3 LANDFILL SITE CHARACTERIZATIONS
      Site
     Nam*
                                   Sampling RatfaMalt/lnTcttijraUon Results
                                                                                            Human
                                                                                          Health Rhk b
    DP-03
              • CPR indicated buried debris covering approximately 2 acres.
              •Trace soil-gas detected.
              • Nine SVOCs delected in one of the three surface sampla.
              • Fill maierialJ including concrete, asphalt, metal, and travel encountered at depths up to 7
              feet in two of the three test pits.
             • to the three subsurface samples, one VOC. 10 SVOCs. hydrocarbons, and lead detected
             above background levels.
             ' Vadose zone modeling indicated no risk to groundwater.
                                                                                    • Cumulative Cancer
                                                                                    Riskd.9E-5
                                                                                    (industrial/commercial
                                                                                    worker scenario)

                                                                                    • Hazard Index  < 1.0

                                                                                    •BloodLead < 10
   A limited potential
   for ecotopcal risk
   due to a limited
   distribution of PAHs.
             • GPR indicated buried debris covering approximately 5.5 acres.
             • Trace soil-gas detected.
             • Three inorganics (lead, nickel and zinc) were detected above background in one of the
             three surface samples. Three pesticides and hydrocarbons were also detected.
             • Fill materials including concrete, asphalt, metal, plastic, wood, and gravel encountered at
             depths below J5 feet in five of the six lest pits.
             • Hydrocarbons, and two inorganics (lead and mercury) detected above background levels
             in the subsurface samples.
             • Vadose zone modeling indicated no risk to groundwater.
                                                                                    • Cumulative Cancer
                                                                                    Risk-6.7E-5
                                                                                    (industrial/commercial
                                                                                    worker scenario)

                                                                                    •Hazard Index < 1.0

                                                                                    • Blood Lead < 10
   A potential ecological
   risk 10 burrowing
   mammals and their
   predators due mainly
   to the highly
   localized presence of
   Aroclor 1260.
 • GPR indicated buried debris covering approximately 4 acres.                            . Qunui.^ CtDea

 • Three dioxins. hydrocarbons and four inorganics (barium, lead, mercury and zinc) detected  2^, rl^nt^a^
 above background in surface soil samples.                                                   rcswem scenano)
 • Fill materials including concrete, metal, plastic, glass and plaster board encountered to       . Hazard Inda < I 0
 depths of 10 feet in ten pits.                                                            ™«iiin»«« i.u
 • Hydrocarbons, and barium detected above background levels in the subsurface sample*.     . Blood Lead < 10
 • Inorganic constituents below or near background were detected in groundwater.
• Vadose zone modeling indicaled no risk to groundwater.
                                                                                                                     A potential ecological
                                                                                                                     risk to burrowing
                                                                                                                     mammals iind their
                                                                                                                     predators due mainly
                                                                                                                     to the highly
                                                                                                                     localized presence of
                                                                                                                     dioxins, kid. zinc.
                                                                                                                     and barium.
           • GPR indicated buried debris covering approximately 9 acres.
           • Trace soil-gas detected.
           • Four SVOCi. two pesticides, hydrocarbons and five inorganics (cadmium, copper, lead.
           mercury and zinc) detected above background in surface soil samples.
           • Rll materials including concrete, asphah. metal, plastic, wood, glass and gravel
           encountered at depths below 15 feet in lest pits.
           • Two VOCs. one SVOC. hydrocarbons, and two inorganics (lead and manganese) detected
           above background levels in the subsurface samples.
           • loorganic constituents below or near background were detected in groundwater.
           • Vadote zone modeling indicated no risk to grouodwater.
                                                                                   • Cumulative Cancer
                                                                                   RUk»I.OE-5
                                                                                   (industrial/commercial
                                                                                   worker scenario)

                                                                                  •HazardIndex < 1.0

                                                                                  •BloodLead < 10
  A potential ecological
  risk to burrowing
  mammals and their
  predators due to the
  localized presence of
  cadmium, lead, zinc.
  pesticides, ind PAHs.
          • GPR indicated buried debris covering approximately 0.41
          • Trace toil-gas detected.
          • Hydrocarbons and lead delected above background in surface soil samples.
          • Fill materials including concrete, metal, wood, trash and burned debris encountered to
          depths up 10 9 feet in test pits.
          • Hydrocarbons and two inorganics (antimony and lead) detected above background levels
          in the subsurface samples.
          * Vadose zone modeling indicated no risk to groundwater.
                                                                                  • PRO screening
                                                                                  indicated site
                                                                                  chemicals are within
                                                                                  acceptable levels;
                                                                                  therefore a risk
                                                                                  calculation was not
                                                                                  perfuciiKd.
                                                                                  •Blood Lead < 10
 Ecological impacts
 not significant.
        •  • GPR indicated buried debris covering approximately 50 acres.
          • Trace soil-fa* detected.
          • Eight djoxint. one pesticide, hydrocarbons and 10 inorganics detected above background
          in surface soil samples.
          • Fill materials including concrete, asphalt, metal, rubber, wood, glass, plaster board, and
          burned debru encountered al depths below 13.5 feet in test pits.
          • Toluene, hydrocarbons, and 14 inorganics detected above background levels in the
          subsurface samples.
          • Inorganic constituents below or near background were detected in groundwater.
          • Vadoae zone modeling indicated no risk to groundwater.
                                                                                  • Cumulative Cancer
                                                                                  Risk  -S.4E-5 (future
                                                                                  adult resident scenario).

                                                                                  • Hazard Index -1.36

                                                                                  • Blood Lead < 10
A potential ecological
risk to burrowing
mammals and their
predators due; to the
localized pretence of
several metals and
dioxin/furan
congeners.
Notes:
a The SEDA remediation boundary includes 9 sites (LF-07, LF-08. RW-09, DP-IO. DP-IS. DP-33. DP-34. WP-40. and SS-J2).
b Highest cancer risk from all scenarios evaluated the scenario under which the highest cancer risk was calculated is presented.

-------
                                                                    TABLE 3

                       SUMMARY OF DETAILED ANALYSIS OF REMEDIAL ALTERNATIVES FOR OU 3 LANDFILL SITES
       Alternative
Protection of
Human Health
and the          Compliance with
Environment     ARARs
Effectiveness    Reduction of TMV
ImplementabilitY     Total Cost
I. No Action with
   monitoring
Does not reduce   Does not comply.
potential for
future exposure.
Not effective.    No reduction of TMV.
No technical
limitations.
See Table 5.
2. Institutional Controls
Reduces potential  Complies with        Moderate
for future         ARARs.             effectiveness.
exposure
                Reduces volume through    Easily implemented.   See Table 5.
                surface restoration.
3. Surface Controls/
   Existing Cover
   Rehabilitation
Significantly      Complies with
reduces potential  ARARs.
for future
exposure.
Effective.        Reduces the mobility of    General site grading   See Table 5.
                the landfill contaminants    may be difficult in
    <            by reducing surface water   areas of uneven
                infiltration and controlling  topography.
                run-on/runoff.
4.  Soil Cover
 Significantly      Complies with
 reduces potential  ARARs.
 for future
 exposure.
Effective.         Same as Alternative 3, but  Same as Alternative   See Table 5.
                 provides greater reduction  3.
                 in infiltration through the
                 addition of a soil cover.
 5.  Synthetic Cap
 Significantly      Complies with
 reduces potential  ARARs.
 for future
 exposure.
Effective.        Same as Alternative 4, but   Same as Alternative    See Table S.
                 provides a greater          3.
                 reduction in infiltration
                 through the addition of a
                 synthetic liner.
ARAR - applicable or relevant and appropriate
TMV - toxicity, mobility, or volume

-------
                                                                                  TABLE4
                                            ARAR. FOR GAFB OU 3 LANDHLL SITES DP43. DP-W, LF-12, LF-I4, AND THESEDA
                                                                                 (P«C« t of »)
Sonrco
Standard Requirements,
Critorton, or Limitation*
ARARStataf'
Description
                                                                                                                                                        Coiucftt
 California Integnted Watte
 Management Act of 1989
 PRC 40502 & 43020
 California Integrated Waste
 Management Act of 1989
 PRC 40502 & 43020
 California Integrated Watte
 Management Act of 1989
 PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 ft 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
 14 CCR 17766
 Chapter 3. Article 7.8
 Disposal Site Closure and
 Poitclocure Maintenance
 14CCRI7767c,d,e.f.&g
 Chapter 3. Article 7.8
 Disposal Site Closure and
 Poitclosure Maintenance
 14CCR1777la(2)
 Chapter 3. Article 7.8
 Disposal Site Closure and
 Postclosure Maintenance
14 CCR 17772
Chapter 3. Article 7.8
Disposal Site Closure and
Postclosure Maintenance
14CCRI7773a&c-e
Chapter 3. Article 7.8
Disposal Site Closure and
Postclosuie Maintenance
 Relevant and Appropriate
 Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate
14 CCR 17774 a-e{D & H      Relevant and Appropriate
 Emergency Response Plan: potential emergency conditions
 that may exceed the design of the site and could endanger the
 public health or environment must be anticipated. Response
 procedures for these conditions must be addressed in the
 RD/RA plans.

 Security at Closed Sites: all points of access to the site must
 be restricted, except permitted entry points. All monitoring.
 control, and recovery systems shall be protected from
 unauthorized access.  Notification signs must be posted at the
 site,

 Structure Removal: dismantle and remove structures are
 required by the closure plan.
                            Chapter 3, Article 7.8
                            Disposal Site Closure and
                            Poitcloiure Maintenance
 Decommissioning of Environmental Control Systems:
 components of the environmental control systems, which
 have come into contact with leacbate or landfill gas need to
 be dismantled and disposed of in a manner that will not pose
 a potential health threat.

 Final Cover: the design and construction of the final cover
 must meet specific performance standards regarding
 infiltration. landfill gas emissions, and reuse of the site. This
 section incorporates the prescriptive standards of 23 CCR
 2581(a); however, an engineered alternative that meets the
 performance standards is being proposed and must meet the
 engineered alternative criteria including 23 CCR
 25IO(b)&(c)and2580(e).

Construction Quality Assurance (CQA):  a CQA program
must be designed and irnpkineRisd. it must include specific
parameters (and for some components specific testing
methods) for the final cover.
 Closure or Postclosure
 Maintenance Standard of Title 14,
 CCR, Chapter 3, Article 7.8.
 Scope and Applicability pursuant
 to 14 CCR 17760.

 Closure of Poslclosure
 Maintenance Standard of Title 14,
 CCR, Chapter 3. Article 7 J.
 Scope and Applicability pursuant
 to 14 CCR 17760.

 Closure or Postclosure
 Maintenance Standard of Title 14.
 CCR, Chapter 3, Article 7.8.
 Scope and Applicability pursuant
 to 14 CCR 17760.

 Closure or Postclosure
 Maintenance Standard of Title 14,
 CCR, Chapter 3, Article 7.8.
 Scope and Applicability pursuant
 to 14 CCR 17760.

 Closure  or Postclosure
 Maintenance Standard of Title 14.
CCR, Chapter 3. Article 7.8.
Scope and Applicability pursuant
to 14 CCR 17760.
                                                                                                               Closure or Postclosure
                                                                                                               Maintenance Standard of Title 14,
                                                                                                               CCR. Chapter 3. Article 7.8.
                                                                                                               Scope and Applicability pursuant
                                                                                                               to 14 CCR 17760.

-------
                                                                                 TABLE4

                                          ARARi FOR GAFB OU 3 LANDFILL SITES DP-03, DP-M, LF-12, LF-14, AND THE SEDA
                                                                                (P«gt2of9)
         Source
 Standard Requirements,
 Criterion, or LlmlUttoii'
      ARAR Status*
                                                                                                         Description
                                                                                                                                                       Comment
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 ft 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
14 CCR 17776
Chapter 3. Article 7.8
Disposal Site Closure and
Postclosure Maintenance
Relevant and Appropriate
14 CCR 17777m
Chapter 3, Article 7.8
Disposal Site Closure and
Postctofure Maintenance
14 CCR 17778
Chapter 3, Article 7.8
Disposal Site Closure and
Postclosure Maintenance
14 CCR 17779
Chapter 3. Article 7.8
Disposal Site Closure and
Postclosure Maintenance
14 CCR 17781 a&b
Chapter 3, Article 7.8
Disposal Site Closure and
Postclosure Maintenance
Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate
 Final Grades: the Anal grades for the covered landfill must
 meet grading standards provided in 23 CCR 2581 (b). and be
 based on local topography, climate condition!, and
 postclosure land use; they must be appropriate to control
 runoff and erosion.  Survey monuments must be installed to
 monitor settlement as required by 23 CCR 2580(d).  Upon
 completion of closure activities and in the postclosure
 maintenance period, contour maps are required to calculate
 settlement using 2 foot contour intervals and the scale
 specified in 23 CCR 2S97(b).

 Hnal Site Face:  the design of the final site face must provide
 for the integrity of the final cover both under static and
 dynamic conditions.
Final Drainage:  the design of the final cover and any
associated collection and holding facilities must control
runon and runoff produced by a 100-year 24-hour storm
event as required by 23 CCR 2S46(a),(c) & (D) and
2S9S(d)(2) and must be prepared according to CQA
requirements.

Slope Protection and Erosion Control: the design and
construction of the slopes must protect the integrity of (be
final cover and minimize soil erosion.
Leachate Control During Closure and Postclosure: if
leachate is being produced at the site, it must be monitored,
collected, treated, and discarded pursuant to 23 CCR 2SS9,
2543. and 2546(b), respectively.
                                                                                    Closure or Poslclosure
                                                                                    Maintenance Standard of Title 14,
                                                                                    CCR, Chapter 3, Article 7.8.
                                                                                    Scope and Applicability pursuant
                                                                                    to 14 CCR 17760.
Closure or Postclosure
Maintenance Standard of Title 14,
CCR. Chapter 3, Article 7.8.
Scope and Applicability pursuant
to 14 CCR 17760.

Closure or Postclosure
Maintenance Standard of Title 14,
CCR, Chapter 3. Article 7.8.
Scope and Applicability pursuant
to 14 CCR 17760.
Closure and Postclosure
Maintenance Standard of Title 14,
CCR. Chapter 3, Article 7.8.
Scope and Applicability pursuant
to 14 CCR 17760.

The state does not intend that
subsurface leachate monitoring
and collecting systems need to be
added to existing landfills unless
leacbate production and/or
accumulation is evident.

-------
                                                                                 f
                                                                                 TABLE4

                                           ARARf FOR GAFB OU 3 UNDFILL SITES DP43, DP.04, LF-12, LF-14, AND THE SEDA
                                                                                (Fate 3 of 9)
          Source
  Standard Requirement*,
  Criterion, or Lfanltatleo'
 California Integrated Wute
 Management Act of 1989
 PRC 40502 & 43020
California Integrated Watte
Management Act of 1989 -
PRC 40502 ft 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43020
California Integrated Waste
Management Act of 1989
PRC 40502 & 43509

California Integrated Waite
Management Act of 1989
PRC 40502 & 43509
California Integrated Wute
Management Act of 1989
PRC 40502 & 43509
 14 CCR 17783
 (attempting m exemption)
 Chapter 3. Article 7.8
 DiipoMl Site Clowns and
 Poitdonire Maintenance

 14 CCR 17788
 Chapter 3. Article 7.8
 Disposal Site Cloiure and
 Postckuure Maintenance
 14 CCR 17796
Chapter 3. Article 7.8
Disposal Site Closure and
Poitclosure Maintenance
 14 CCR 18262 Ja(l-5B)i
(8) Chapter 5. Article 3.4
Closure Plans

I4CCR18265.3a(l-7)and
(9 & 10) Chapter 5, Article
3.4, Poitclosure
Maintenance Plans

14 CCR 18275 Chapter 5,
Article 3.4, Postckuure
Maintenance Plans
                                                              ARAR Statue*
 Relevant and Appropriate
Relevant and Appropriate
Applicable
Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate
                                                                                                         Description
 Gas Monitoring and Control During Closure and Port
 Closure: landfill gases must be collected and analyzed; (he
 concentration of combustible gas at the landfill boundary
 must be 5 percent or leu, (race gases must not be at levels
 that cause adverse health or environmental impacts.

 Postclosure Maintenance: the landfill must be maintained
 and monitored for no less than 30 yean following closure
 and in accordance with 23 CCR 2581 (c).
Postctosure Land Use: Site Closure Design shall show one
or more proposed uses of the closed site or show
development that is compatible with open space. The owner
of the site must notify the agencies of any proposed change*
in postclosure land. Changes in the land use must be
implemented in accordance with the standards in this section
to ensure that public health and the environment are
adequately protected.

Provides the content requirements for closure plans for solid
waste disposal sites.
Provides the content requirements for poatctosure
maintenance plans for solid waste disposal sites.
Provides the content requirements to obtain certification that
the solid waste disposal sites has closed pursuant to state
standards.
                                                                                                                                                       Comment
                                                                                    An exemption may be granted
                                                                                    pursuant (o 14 CCR 17783.17 once
                                                                                    the proposed monitoring data it
                                                                                    received,
 Maintenance and monitoring is to
 continue for 30 years following
 closure until it can be
 demonstrated that the landfill does
 not pose a threat to public health
 and safety or a threat to the
 environment.

 Closure or Postclosure
 Maintenance Standard of Title 14.
 CCR. Chapter 3. Article 7.8.
 Scope and Applicability pursuant
 to 14 CCR 17760.
Applies to solid waste disposal
site* that received waste after
January 1,1988.

Applies to solid waste disposal
sites that received waste after
January 1,1988.
                                                                                    Applies to solid waste disposal
                                                                                    sites that received waste after
                                                                                    January 1,1988.

-------
                                                                                 TABLE4

                                           ARARi FOR GAFB OU 3 LANDFILL SITES DP-03, DP-04, LF-12, LF-14, AND THE SEDA
                                                                                (P»«c 4 of 9)
         Source
Standard Requirements,
CriUrioa. or Umrtalton*
ARAR Status'
                                                                                                          Description
                                                                                                                                                        Conuacnt
Water Quality Control Plan    Table 2-1, Beneficial Uses     Applicable
for the Lahontan Region       of Ground Waters in Upper
(Basin Plan)                 Mojave Hydro-logic Unit
                            (628.20)
                            Objectives for Ground
                            Water
                            California Water Code J
                            13176

                            California Water Code 5
                            13370 etteq.
                           Applicable



                           Applicable


                           Applicable
                            California Water Code §
                            13750
                          Applicable
                            California Water Code }       Applicable
                            13750.5

                            California Water Code }       Applicable
                            13752
                                                       Defines beneficial uses for groundwaters beneath GAFB as:
                                                       municipal, agricultural, industrial service, and freshwater
                                                       replenishment.
                      Defines the groundwater quality objectives for:
                      nondegradation, taste and odor, bacteria, chemical
                      constituents, radioactivity, and minerals.

                      Requires the analysis of material to be performed in a State
                      certified laboratory.

                      Requires compliance with Federal Clean Water Act
                      requirements for surface water discharges.  Includes National
                      Pollutant Discharge Elimination System Requirements for
                      storm water runoff from certain construction or industrial
                      activities. The Air Force must comply with the substantive
                      requirements for a) eliminating most non-storm water
                      discharges, b) developing and implementing a storm water
                      pollution prevention plan, and c) performing monitoring of
                      storm water discharges. For landfills that are inactive, prior
                      to final closure, these regulations are contained in the
                      SWRCB General Industrial Storm Water Permit (Order No. .
                      91-13-DWQ. as amended by Order No. 92-12-
                      DWQXNPDES No. CAS000001). For Landfills that are
                      going through final closure, these regulations are contained
                      in the SWRCB General Construction Activity Storm Water
                      Permit (Order No. 92-08-DWQ)(NPDES No. CAS000002).

                      Requires an intent to drill notice to be filed with the State
                      Department of Water Resources for water wells, monitoring
                      wells, and cathodic protection wells.

                      Requires well drillers to possess a C-57 license.
                                                      Allows other governmental agencies to obtain and submit
                                                      well reports, provided (he public is allowed to see them only
                                                      after obtaining written permission from the owner.
The identification of the
groundwaters beneath landfill sites
as potential drinking water sources
forms a basis for selection of
concentration limits, cleanup
levels, and treatment levels.

Concentration limits, cleanup
levels, and treatment levels must
conform to the objectives.

For all investigation and remedial
actions.
                                                                                                               For any well.
                                                                                                               For any well.
                                                                              For any well.

-------
                                                    TABLE*
                        ARAR, FOR GAFB OU3LANDFILLSnESDP^,DP^LF.12,LF.M,AND™ESEDA
                                                   (Pa je 5 of 9)
Source
Standard Requirements,

Criterion, or Limitation1

Discharges of Water to 5 25 1 0(g)
Land. Chapter 15, Title 23.
CCR. Article 2 - Waste
Classification and
Management
52520
* M£ Ml
$2523
Discharges of Waste to } 2546
Land. Chapter 15, Title 23.
CCR. Article 4-
Construction Slandards
52550.1
Porter-Cologne Act { 2550 4
Chapter 15




}2550.7(bXIXA)
|2550.7(bXIXB>
§ 2550.7(b)(2)
• .- .
— fttvin awuy
	 DMCriPtion 	 Comment
Relevant «! Appropriate C.o^ inactive, or abandoned waste management units as
of 1 1/27/84 may be required to implement a monitoring
program. If water quality impairment is discovered
corrective action may be required.
Relevant and Appropriate

Relevant and Appropriate
Relevant and Appropriate

Relevant and Appropriate
Relevant and Appropriate




Relevant and Appropriate
Relevant and Appropriate
Relevant and Appropriate

^SSSS^^"*** ^ — withintheselandfiUs
solid waste.
Non-Hazardous Solid Waste - putrescible and non-
putrescible waste that may be discharged to a Class III unit.
Precipitation and Drainage Controls - criteria for diversion
and drainage of storm water.

Defines the type of monitoring programs that apply.
Different monitoring programs may apply at the same unit at
the same lime. TTie requirements (ROD) must specify the
type of program applicable to the unit.
Concentration Limits (CL) - Must be established for
groundwater. surface water, and the unsaturated zone. Must
be based on background, equal to background, or for
corrective actions, may be greater than background
(CLGTB), not to exceed the lower of the MCL or the
concentration technologically or economically achievable. ,
Have a "sufficient number" of background MPts.
For detection monitoring, have a sufficient number of MPts
at the POC. additional locations as necessary, unsaturaied
zone, perched aquifers, and zones of highest conductivity.
Background monitoring does not necessarily have to be
upgradient of unit, ii may be representative of uparadient
conditions.
* < • '

-------
                                                                      TABLE4

                                 ARARs FOR GAFBOU 3 LANDFILL SITES DP-03, DP-04, LF-12, LF-M, ANDTHESEDA
                                                                     (Page C of 9)
Source
Standard Requirements,
Criterion, or Limitation'
ARAR Status1
                                                                                               Description
                                                                                                                                            Comment
                   |2550.7(bM4)


                   |2550.7(bX5)



                   |2550.7(bX6)


                   12550.7(bX7)

                   J2550.7(eX2)



                   }2550.7(eX3)


                   S 2550.7(eX4)



                   J2550.7(e)(5)
                   { 2550.7(eX6)
                   § 2550.7(e)(7)
                          Relevant and Appropriate


                          Relevant and Appropriate



                          Relevant and Appropriate


                          Relevant and Appropriate

                          Relevant and Appropriate




                          Relevant and Appropriate


                          Relevant and Appropriate




                          Relevant and Appropriate
                          Relevant and Appropriate
                          Relevant and Appropriate
                      Monitoring wells are to be constructed and cased in a manner
                      to prevent being a conduit for contaminant transport.

                      Sampling interval shall be appropriately screened and
                      equipped with a filter pack to enable representative
                      groundwater sample collection.

                      The annular space (hall be appropriately sealed to prevent
                      cross-contamination.

                      Monitoring wells are to be adequately developed.

                      Cuttings to be logged during drilling under supervision of a
                      registered geologist, lithology logs submitted to Regional
                      Boards:  Soils - USGS, Rocks - as appropriate. Unsaturated
                      Zone • record depth and thickness.

                      Separate groundwater monitoring systems are not necessary
                      for contiguous units.

                      Consistent sampling and analytical procedures are required
                      incorporating: sample collection, sample preservation and
                      shipment, analytical procedure!, and chain-of-custody
                      control.

                      Monitoring program to include appropriate methods for each
                      COC and monitoring parameter (MPa).
                     For each unit collect all data necessary to select an
                     appropriate statistical method for establishing background.
                     As a minimum, quarterly sampling for one year, considering
                     highest and lowest groundwater elevations.

                     Propose a statistical method for evaluation of each COC and
                     MPa. Mutt be specified in requirements (ROD). Selection
                     criteria are given.
Far all wells.


For all wells.



For all wells.


For all wells.

For all wells.
                                                                                                                                 The monitoring parameters are the
                                                                                                                                 metal surrogates chloride, sulfate,
                                                                                                                                 nitrate as nitrogen, total dissolved
                                                                                                                                 tolids, and volatile organic
                                                                                                                                 constituents as defined by
                                                                                                                                 Appendix I of 40 CFR 258.  The
                                                                                                                                 constituents of concern are those
                                                                                                                                 constituents listed in Appendix II
                                                                                                                                 of 40 CFR 258.

-------
                                                                     TABLE4

                                ARARi FOR GAFB OU 3 LANDFILL SITES DP-03, DP-W, LF-12, LF-14, AND THE SEDA
                                                                    (P*C«7of>)
Source
                   Standard Requirement*,
                  §2550.7(eX8)
                  12550.7(eX9)

                  S 25S0.7(eX10)
                  52550.7(e)(ll)

                  } 2550.7(eX12)
                 52550.7(eXl3)


                 52S50.7(e)(14)
                 § 2550.7(eXI5)
                                                   ARAR Statin*
 Relevant and Appropriate
 Relevant and Appropriate

 Relevant and Appropriate
 Relevant and Appropriate

 Relevant and Appropriate
Relevant and Appropriate


Relevant and Appropriate
                                                                                            Description
 Acceptable Statistical Methods:
 -  ANOVA using mean values
 -  ANOVA using median values
 -  Tolerance or Prediction Interval
 -  Control Charts
 -  Alternate Proposal, verification criteria are included.
 Performance Standards are given for each statistical method.

 Based upon the data collected and statistical method chosen
 to analyze the data, propose and justify a procedure to
 determine background for each COC and MPa, may use:
 - background
 - method to update background with new data.

 The requirements (ROD) shall specify the method chosen
 above.

 for each COC and MPa the requirements (ROD) shall
 specify the sampling methods to establish background and
 for monitoring, consistent with:
 - the appropriate number and kind of samples for the
  statistical lest chosen
 • (he sampling method, including frequency and interval.
  ensuring independent samples.

Must collect groundwater surface elevation and field
parameters each time a well is sampled.

All data must be graphed at least manually, criteria are given
graphs.
                                                                                                                                        Comment
Relevant and Appropriate     The groundwater flow rate and direction must be determined.
 For each well.


 Except where there is no new data,
 the guidelines of the PAT
 documents entitled Lone Term
 Manife^Md Reporting
 Hvdf oeeologic Date arr
 appropriate.

RPMs should adjust this
requirement as necessary. Semi-
annual determination should be
adequate.

-------
                                                                                   TABLE4
                                            ARARi FOR GAFB OU 3 LANDFILLSITES DP-03, DP-04, LF-12, LF-I4, AND THE SEDA
                                                                                  (Pace 8 of 9)
           Source
   Standard Requirement!,
   Criterion, or Limitation'
 California Well Standards
 for water wells, monitoring
 wells, and camodic
 protection wells

 Hazardous Waste Control
 Laws
California Health and Safety
Code, Div. 26, Chapter 13
                              i 2550.7(eXI6)


                              } 2550.8

                              12550.8(d)

                              12S50.8(e)
 J 2550.8(1)

 J 2550.8(g)


 } 2S50.8(b)


 { 2550.g(i)



 }2580(c)

 BuUetin 74-90 and 74-81,
 adopted pursuant to
 California Water Code §
 13800

 Title 22, California Code of
 Regulations (CCR). Division
 4.5 Environmental Health
 Standards for Management
of Hazardous Waste,
Chapters 11.12. 14, and 18

Mojave Desert Air Quality
Management District
(MDAQMD), Rule 401
                                    ARAR Status'


                              Relevant and Appropriate


                              Relevant and Appropriate

                              Relevant and Appropriate

                              Relevant and Appropriate
 Relevant and Appropriate

 Relevant and Appropriate


 Relevant and Appropriate


 Relevant and Appropriate



 Relevant and Appropriate

 To Be Considered




 Applicable
                                                                                                                                                          Comment
Applicable
 All data collected shall be maintained. The requirements
 (ROD) shall specify when data are to be reported.

 Detection Monitoring.

 The requirements (ROD) shall specify the WQPS.

 MPas shall be proposed and specified in requirements
 (ROD) to include physical parameters, hazardous
 constituents, and reaction products to provide a reliable
 Indication of a release. A list of items to consider is given.

 Monitoring parameters and frequencies shall be as specified.

 COCs to be monitored if there is statistic evidence of a
 release.

 All data must be maintained so that statistical evidence of a
 release may be determined.

 Lists criteria for determining statistical evidence of a release,
 includes physical determination (i.e., rapid pond declines or
 spills).

 Prevents excessive irrigation on the final cover.

 Provides minimum construction and destruction criteria for
 water wells, monitoring wells, and cathodic protection wells.
 Also includes criteria for borehole abandonment


 Regulations governing  hazardous waste control;
 identification and listing of hazardous waste, standards
applicable to generators of hazardous waste waste transfer;
treatment, storage, and  disposal facilities; and land disposal
restrictions.
This rule prohibits the discharge of air contaminants which
obscure visibility by more than 20 percent for a period of
more than 3 minutes in any I hour.
                                                                                                                                              MPas may be known as the Short
                                                                                                                                              List at opposed to the Long List of
                                                                                                                                              COCs.
                                                         For all wells.
                                                                                     Only applicable if the wastes from
                                                                                     the sites are classified as
                                                                                     hazardous waste.
                                                                                     This regulation is applicable to any
                                                                                     remedial action activity, which
                                                                                     may cause a visible emission.

-------
                                                                                TABLE4

                                           ARAR. FOR GAFB OU 3 LANDFILL SITES DP4>3, DP-04, LF-12, LF-14, AND THE SEDA
           Source
                              Siaadard Requirements,
                              Criterion, or LtmlUtkn*
                                                             ARAR Status*
                                                                                                       Dqcriptlon
                                                                                                                                                   Couufit
  California Health uid Safety   MDAQMD, Rule 402         Applicable
  Code, Div. 26. Chtpler 13
  California Health and Safety    MDAQMD. Rule 403         Applicable
  Code, Div. 26, Chapter 13
  California Health and
  Safety Code, Div. 26,
  Chapter 13
                             MDAQMD, Rule 1303        Applicable
This rule prohibits the discharge of air contaminants in
quantities which may cause injury, detriment, nuisance, or
annoyance to any considerable number of persons or which
endangers the comfort, response, health, or safety of any
such person or which causes or has natural tendency to cause
injury or damage to business or property.

This rule requires a person to lake reasonable precaution not
to cause or allow emissions of fugitive dusts from being
airborne beyond the property line from which the emission
originated.

This rule requires (he installation of best available
technology (BACT) to a new emission unit or modification
of existing emissions unit.
                                                                                                                                        This regulation ii applicable to any
                                                                                                                                        remedial action activity, which
                                                                                                                                        may discharge air contaminants as
                                                                                                                                        denned by the rule.
This regulation is applicable to any
remedial action activity, which
may cause the release of fugitive
dust

This regulation is applicable to any
remedial action activity that may
cause the emissions of 25 pound
per day or more of any
Nonanainment Air Pollutant
1 Sections of Title 14 CCR and Title 23 CCR have been recodified into Title 27 CCR.

' The State does not agree on the characterization of certain ARARs in this table to be
  the ROD at ARARs, the State will ool dispute this ROD.

14 CCR - California Code of Regulations. Title 14
23 CCR - California Code of Regulation*. Tide 23
ANOVA - Analysis of Variance
ARAR - applicable or relevant and appropriate requirement
BACT - best available technology
CFR - Code of Federal Regulations
CL - concentration limits
CLGTB - Concentration Limit Greater than Background
COC - Constituent of Concern
CQA - Construction Quality Assurance
MCL - Maximum Contaminant Level
MDAQMD - Mojave Desert Air Quality Management District
Mrs - monitoring parameter
MPu - Monitoring Points
POC - Point of Compliance
RD/RA - remedial design/remedial action
ROD - Record of Decision
RPM - remedial project manager
WOPS - Water Quality Protection Standards
                                                                        See Title 27 CCR for the new equivalent section numbers that apply.

                                                                        "Relevanl and Appropriate" instead of "Applicable." However, because these requirements will be included in
WOPS-

-------
                                              TABLES
         SUMMARY OF PRELIMINARY REMEDIAL ALTERNATIVE COSTS FOR OU 3 LANDFILL SITES
    Site     Cost Criteria
Alternative 1   Alternative 2   Alternatives   Alternative 4   Alternatives
DP-03
DP-04
LF-12
LF-14
LF-44
SEDA
^ VBHWVII^
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present- Worth Cost
Construction Cost
Direct Capital Cost
Total Capita! Requirement
30- Year Present-Worth Cost
	 — 	 — 	
$5,000
$6,500
$8,000
$460,000
$5,000
$6,500
$8,000
$420,000
$0
$0
$0
$450,000
$0
$0
$0
$530,000
$0
$0
$0
$370,000
$0
$0
$0
$970,000
- 	 ••-- 	
$69,000
$90,000
$170,000
$680,000
$70,000
$91,000
$170,000
$640,000
$130,000
$170,000
$270,000
$830,000
$330,000
$420,000
$600,000
$1,400,000
$34,000
$44,000
$110,000
$510,000
$610,000
$780,000
$1,100,000
$2,600,000
$230,000
$290,000
$440,000
$1,100,000
$200,000
$260,000
$400,000
$980,000
$430,000
$540,000
$780,000
$1,600,000
$1,300,000
$1,600,000
$2,200,000
$3,800,000
$130,000
$160,000
$270,000
$740,000
$2,700,000
$3,400,000
$4,600,000
$7,800,000
$280,000
$360,000
$540,000
$1,200,000
$250,000
$320,000
$480,000
$1,100,000
$560,000
$710,000
$1,000,000
$1,900,000
$1,800,000
$2,300,000
$3,200,000
$5,300,000
$150,000
$190,000
$310,000
$800,000
$3,800,000
$4,800,000
$6,500,000
$11,000,000
$370,000
$470,000
$680,000
$1,400,000
$340,000
$440,000
$640,000
$1,300,000
$860,000
$1,100,000
$1,500,000
$2,700,000
$2,700,000
$3,400,000
$4,600,000
$7,400,000
$190,000
$240,000
$370,000
$900,000
$5,800,000
$7,300,000
$10,000,000
$16,000,000
" Costs are as presented in the OU 3 FS Report (Montgomery Watson, 1997a).

-------
                                   TABLE 6

      PRELIMINARY COST ESTIMATE FOR SITE DP-03 PREFERRED ALTERNATIVE
                                  (Page 1 of 2).
Item/Description
Quantity   Unit
                                                          Unit Cost ($)  Total Cost ($)
DIRECT CAPITAL COST (DCC)
Construction Cost (CC):
GENERAL
Construction Trailer (Rental)
Temporary Utilities (Telephone/Power)
Decon Trailers
Health & Safety Equipment
Vehicle Decon Station
Vehicle Decon Equipment
Dust Control
Mobilization
Demobilization
SITE WORK
Clear and Grub (w/ Class in Disposal)
Soil Testing (compaction and density)
Excavate Native Soil (within 1 mile)
Haul and Dump Native Soil
Fill, Spread, and Compact Soil
General Site Grading (min. 3% slope)
Construct Drainage Channels (riprap)
Erosion Control and Revegetation
Maintain and Repair Haulage Roads
Chain-Link Fencing (8 ft high. Barbed)
Downgradient Monitoring Well (Installed)

Supervision. Health & Safety
Bid Contingency
Scope Contingency

INDIRECT CAPITAL COST
Land Use Restrictions
Prc-Design Studies
Engineering Design Services
Construction Management
Administrative Cost (GAFB/AFCEE)



1 month $500
1 month $1, 500
month $2,400
month $3,000
each $5,000
month 5700
month $11.000
lump sum $20.000
lump sum $15.000

180.000 SF $0.07
20 each $100
26.000 CY $1
26.000 CY $2
26.000 CY $0.50
180.000 SF $0.05
1.500 LF $20
180,000 SF $0.05
16,000 SF $0.90
2400 LF $20
1 lump sum $5,000
Subtotal Construction Cost (CC)|
10% of CC
IO%ofCC
8%ofCC
Subtotal Direct Capital Cost (DCC)|

1 lump sum $50,000
5% of DCC
5% of DCC
10% of DCC
15% of DCC
TOTAL CAPITAL REQUIREMENT 1
PERIODIC OPERATING AND MAINTENANCE COST
Annual Maintenance for Soil Cover
Annual Groundwatcr Monitoring (4 wells) —

5% of DCC
4 sample $3,000



$500
$1.500
$2,400
$3,000
$5,000
$700
$11.000
$20.000
$15,000

$12,600
$2,000
$26,000
$52,000
$13,000
$9,000
$30,000
$9.000
$14,400
$50,000
$5.000
$280,000 |
$28.000
$28,000
$22,400
$360.000 ]

$50.000
$18.000
$18.000
$36,000
$54,000
$540.000 |

$18,000
$12,000

-------
                           TABLE 6

PRELIMINARY COST ESTIMATE FOR SITE DP-03 PREFERRED ALTERNATIVE
                         (Page 2 of 2)
Item/Description
Semi-Annual Groundwater Monitoring (2 wells)
Quarterly Groundwater Monitoring (1 well)
Semi-Annual Storm Water Monitoring (2 locations)
5- Year Site Review
PRESENT WORTH
Quantity
2
2
4
1
Unit
sample
sample
sample
lump sum
Discount Rate
Years
Unit Cost ($)
$3.000
$3.000
$2.000
$10,000
7%
30
Total Cost ($)
$6.000
$6.000
$8,000
$10.000

                              30-YEAR PRESENT WORTH COST |   $ 1.200.0001

-------
                                      TABLE 7

         PRELIMINARY COST ESTIMATE FOR SITE DP-04 PREFERRED ALTERNATIVE
                                     (Page 1 of 2)
Item/Description
DIRECT CAPITAL COST (DCC)
Construction Cost (CC):
GENERAL
Construction Trailer (Rental)
Temporary Utilities (Telephone/Power)
Decon Trailers
Health & Safety Equipment
Vehicle Decon Station
Vehicle Decon Equipment
Dust Control
Mobilization
Demobilization
SITE WORK
Clear and Grub (w/ Class in Disposal)
Soil Testing (compaction and density)
Excavate Native Soil (within 1 mile)
Haul and Dump Native Soil
Fill, Spread, and Compact Soil
General Site Grading (min. 3% slope)
Construct Drainage Channels (riprap)
Erosion Control and Revegetation
Maintain and Repair Haulage Roads
Chain-Link Fencing (8 ft high. Barbed)
Downgradient Monitoring Well (Installed)
Quantity Unit



month
month
month
month
.each
month
month
lump sum
lump sum

190.000 SF
20 each
21.000 CY
21.000 CY
21,000 CY
190,000 SF
1,300 LF
190,000 SF
12.000 SF
2,000 LF
1 lump sum
Unit Coat ($)



$500
suoo
$2,400
$3,000
$5,000
$700
$11,000
$20.000
$15.000

$0.07
$100
$1
$2
$0.50
$0.05
$20
$0.05
$0.90
$20
$5,000
Subtotal Construction Cost (CC)|
Supervision. Health & Safety
Bid Contingency
Scope Contingency
10%ofCC
JO%ofCC
8%ofCC



Subtotal Direct Capital Cost (DCC)|
INDIRECT CAPITAL COST
Land Use Restrictions
Pre-Design Studies
Engineering Design Services
Construction Management
Administrative Cost (GAFB/AFCEE)

1 lump sum
5% of DCC
5% of DCC
10% of DCC
15% of DCC

$50.000




TOTAL CAPITAL REQUIREMENT |



Total Cost ($)



$500
$1.500
$2.400
$3.000
$5.000
$700
$11,000
$20.000
$15.000

$13,300
$2.000
$21.000
$42,000
$10^500
$9.500
$26,000
19.500
*W*v^\AJ
$10.800
$40,000
$5.000
$250.000 |
$25,000
$25,000
$20.000
$320,000 1

$50.000
$16,000
$16,000
$32,000
$48,000
$480,0001

Annual Maintenance for Soil Cover
                                                5% of DCC
                                                                           $16,000

-------
                                  TABLE?

      PRELIMINARY COST ESTIMATE FOR SITE DP-04 PREFERRED ALTERNATIVE
                                 (Page2of2)
Item/Description
Quantity    Unit
Unit Cost ($)  Total Cost ($)
Annual Groundwater Monitoring (3 wells)
Semi-Annual Groundwater Monitoring (2 wells)
Quarterly Groundwater Monitoring (1 well)
Semi-Annual Storm Water Monitoring (2 locations)
5- Year Site Review
PRESENT WORTH


3
2
2
4
1



sample
sample
sample
sample
lump sum

Discount Rate
Years
$3,000
$3,000
$3,000
$2,000
$10,000

7%
30
$9,000
$6.000
$6,000
$8,000
$10,000



                                      30-YEAR PRESENT WORTH COST |   $1.100.0001

-------
                                                  TABLE 8
         Item/Description
                     |           _
     DIRECT CAPITAL COST (DCC)
        Construction Cost (CC):
        GENERAL
           Contraction Trailer (Rental)
           Temporary Utilities (Telephone/Power)
           Decon Trailers
           Health & Safety Equipment
           Vehicle Decon Station
           Vehicle Decon Equipment
          Dust Control
          Mobilization
          Demobilization
      SITE WORK
          Clear and Grub (w/ Class in Disposal)
          Soil Testing (compaction and density)
         Excavate Native Soil (within 1 mile)
         Haul and Dump Native Soil
         Fill. Spread, and Compact Soil
         General Site Grading (min. 3% slope)
         Construct Drainage Channels (riprap)
         Erosion Control and Revegetation
         Maintain and Repair Haulage Roads
         Chain-Link Fencing (8 ft high. Barbed)
     Supervision, Health & Safety
     Bid Contingency
     Scope Contingency
 INDIRECT CAPITAL COST
    Land Use Restrictions
    Pre-Design Studies
    Engineering Design Services
    Construction Management
    Administrative Cost (GAFB/AFCEE)
PERIODIC OPERATING AND IVUINTENANCE COST
   Annual Maintenance for Surface Controls
   Annual Groundwatcr Monitoring (4 wells)
                                                       Qwntity     Unit       Unit Cost ($)  Total Cost ($)
2 month 5500
2 month $1.500
2 month 52.400
2 month $3(0oo
' each 55,000
2 month $700
2 month $11,000
1 lump sum $20.000
1 lump sum 515,000
600.000 SF $0.07
20.000 CY '??
20.000 CY $2
20.000 CY $050
600.000 SF $oo5
1.800 LF $20
600.000 SF $005
4.000 LF W$S
Subtotal Construction Cost (CC)|
8%ofCC
10% of CC
8% of CC
ff.ft. t it:
auoiotaj Direct Capital Cost (DCC)|
1 lump sum 550,000
5% of DCC
5% of DCC
10% of DCC
15% of DCC

^^^A^- v- A fJiAL REQUIREMENT |
j 	 	 - 	
5% of DCC
4 ^Pfe 53.000
$1.000
$3,000
$4.800
$6,000
55,000
51,400
522,000
520,000
515,000
542,000
56,000
520,000
540,000
$10,000
$30,000
S36.000
530,000
554,000
580.000
5430.000]
534,400
543.000
534,400

5540,000^
550.000
527,000
527,000
554.000
581,000

5780.000]
•
527,000
512,000

-------
                                  TABLE 8

      PRELIMINARY COST ESTIMATE FOR SITE LF-12 PREFERRED ALTERNATIVE
                                 (Page 2 of 2)
Item/Description
Quantity    Unit
Unit Cost ($)  Total Cost ($)
Semi-Annual Groundwaier Monitoring (2 wells)
Quarterly Groundwater Monitoring ( I well)
Semi-Annual Storm Water Monitoring (2 locations)
5- Year Site Review
PRESENT WORTH


2
2
4
]



sample
sample
sample
lump sum

Discount Rate
Years
$3,000
$3,000
$2.000
$10.000

7%
30
$6.000
$6.000
$8,000
$10.000



                                      30-YEAR PRESENT WORTH COST |    $1.600.000]

-------
                                   TABLE 9
       PRELIMINARY COST ESTIMATE FOR SITE LF-14 PREFERRED ALTERNATIVE
                                  (Page 1 of 2)
Item/Description
                                       Quantity    Unit
Unit Cost ($)  Total Cost ($)
DIRECT CAPITAL COST (DCC)
Construction Cost (CC):
GENERAL
Construction Trailer (Rental)
Temporary Utilities (Telephone/Power)
Decon Trailers
Health & Safety Equipment
Vehicle Decon Station
Vehicle Decon Equipment
Dust Control
Mobilization
Demobilization
SITE WORK
Clear and Grub (w/ Class in Disposal)
Soil Testing (compaction and density)
Excavate Native Soil (within 1 mile)
Haul and Dump Native Soil
Fill. Spread, and Compact Soil
General Site Grading (min. 3% slope)
Construct Drainage Channels (riprap)
Erosion Control and Revegetation
Maintain and Repair Haulage Roads
Chain-Link Fencing (8 ft high. Barbed)

Supervision. Health & Safety
Bid Contingency
Scope Contingency

INDIRECT CAPITAL COST
Land Use Restrictions
Pre-Design Studies
Engineering Design Services
Construction Management
Administrative Cost (GAFB/AFCEE)



4 month $500
4 month $1,500
4. _
month $2,400
4 month $3,000
2 each $5.000
4 month $700
4 month $] 1,000
I lump sum $20,000
1 lump sum $15,000

1.900.000 SF $0.07
190 each $100
150.000 CY $|
150.000 CY $2
150,000 CY $0.50
1,900.000 SF $0.05
3.500 LF $20
1,900.000 SF $0.05
40,000 SF $0.90
9.000 LF $20
Subtotal Construction Coot (CC)|
8%ofCC
10%ofCC
8%ofCC
Subtotal Direct Capital Cost (DCC)|

I lump sum $50,000
5% of DCC
5% of DCC
10% of DCC
15% of DCC
TOTAL CAPITAL REQUIREMENT J

PERIODIC OPERATING AND MAINTENANCE COST
Annual Maintenance for Surface Controls
Annual Groundwater Monitoring (5 wells)


5% of DCC
5 sample $3.000



$2,000
$6.000
$9,600
$12,000
$10.000
$2,800
$44,000
$20.000
$15.000

$1133.000
$19.000
$150,000
$300,000
$75,000
$95,000
$70.000
$95.000
$36.000
$180,000
$1.3100.000 |
$104,000
$130.000
$104.000
$1. 600.0001

$50.000
$80,000
$80,000
$160.000
$240,000
$2.200.000 I


$80,000
$15.000

-------
                                    TABLE 9

       PRELIMINARY COST ESTIMATE FOR SITE LF-14 PREFERRED ALTERNATIVE
                                   (Page 2 of 2)
Item/Description
Quantity    Unit
Unit Cost ($)  Total Cost ($)
Semi-AnnuaJ Groundwater Monitoring (3 wells)
Quarterly Groundwater Monitoring (1 well)
Semi-Annual Storm Water Monitoring (2 locations)
5- Year Site Review
PRESENT WORTH


3
2
4
1



sample
sample
sample
lump sum -

Discount Rate
Years
$3,000
53,000
52,000
$10,000

7%
30
$9,000
$6,000
$8,000
$10,000



                                        30-YEAR PRESENT WORTH COST |    $3.800.000|

-------
                         TABLE 10




PRELIMINARY COST ESTIMATE FOR SITE LF-44 PREFERRED ALTERNATIVE
Item/Description
DIRECT CAPITAL COST (DCC)
Construction Cost (CC):
Surface Restoration (w/ Class HI Disposal)
Chain-Link Fencing (8 feet high. Baited)
Supervision, Health & Safety
Bid Contingency
Scope Contingency
INDIRECT CAPITAL COST
Land Use Restrictions
Engineering Design Services
Construction Management
Administrative Cost (GAFB/AFCEE)
Quantity Unit
70,000 SF
1.400 LF
Subtotal Construe
8%ofCC
10% of CC
10% of CC
Subtotal Direct Capil
1 lump sum
5% of DCC
10% of DCC
15% of DCC
TOTAL CAPITAL REQ
PERIODIC OPERATING AND MAINTENANCE COST
Annual Maintenance for Institutional Controls 5% of DCC
Annual Groundwater Monitoring (2 wells) 2 sample
Semi-Annual Groundwater Monitoring (2 wells) 2 sample
Quarterly Groundwater Monitoring (1 well) 2 sample
Semi-Annual Storm Water Monitoring (2 locations) 4 sample
5-Year Sile'Review 1 lump sum
PRESENT WORTH
Discount Rate
Years
30-YEAR PRESENT WO
Unit Cost ($)
$0.08
S20
lion Cost (CC)j^

al Cost (DCC)£
$50.000
UIREMENT £j

$3,000
$3.000
$3.000
$2,000
$10.000
7%
30
RTHCOST |

ToUl Cost ($)
$5,600
$28,000
$34.000 |
$2.720
$3,400
$3,400
$44,0001
$50,000
$2,200
2(4,400
$6,600
$110.0001

$2.200
$6.000
$6.000
$6.000
$8.000
$10.000

$510,000 I


-------
                                 TABLE 11
      PRELIMINARY COST ESTIMATE FOR THE SEDA PREFERRED ALTERNATIVE
                                 (Page 1 of 2)
Item/Description
Quantity    Unit
Unit Cost ($)  Total Cost {$)
DIRECT CAPITAL COST (DCC)
Construction Cost (CC):
GENERAL
Construction Trailer (Rental)
Temporary Utilities (Telephone/Power)
Decon Trailers
Health & Safety Equipment
Vehicle Decon Station
Vehicle Decon Equipment
Dust Control
Mobilization
Demobilization
SITE WORK
Clear and Grub (w/ Class III Disposal)
Soil Testing (compaction and density)
Excavate Native Soil (within 1 mile)
Haul and Dump Native Soil
Fill, Spread, and Compact Soil
General Site Grading (min. 3% slope)
Construct Drainage Channels (riprap)
Erosion Control and Revegetation
Maintain and Repair Haulage Roads
Chain-Link Fencing (8 ft high. Barbed)



6 month
6 month
6 month
6 month
2 each
6 month
6 month
1 lump sum
1 lump sum

4.000,000 SF
400 each
375,000 CY
375,000 CY
375.000 CY
4.000,000 SF
8,500 LF
4.000.000 SF
80.000 SF
14,500 LF



$500
$1,500
$2.400
$3.000
$5,000
$700
$1 1,000
$20,000
$15,000

$0.07
$100
$1
$2
$0.50
$0.05
$20
$0.05
$0.90
$20
Subtotal Construction Cost (CC)|
Supervision. Health & Safety
Bid Contingency
Scope Contingency

INDIRECT CAPITAL COST
Land Use Restrictions
Pre-Design Studies
Engineering Design Services
Construction Management
Administrative Cost (GAFB/AFCEE)
8%ofCC
10% of CC
8* of CC
Subtotal Direct Capita]

1 lump sum
5% of DCC
5% of DCC
10% of DCC
15% of DCC



Cost (DCC)|

$50,000




TOTAL CAPITAL REQUIREMENT |






$3,000
$9,000
$14,400
$18,000
$10,000
$4,200
$66.000
$20.000
$15.000

$280,000
$40.000
$375,000
$750,000
$187,500
$200,000
$170.000
$200.000
$72.000
$290,000
$2,700,000 |
$216.000
$270,000
$216.000
$3,400.000 |

$50.000
$170,000
$170,000
$340,000
$510.000
$4,600,000 [

PERIODIC OPERATING AND MAINTENANCE COST
Annual Maintenance for Surface Controls
Annual Groundwater Monitoring (9 wells)
5% of DCC
9 sample
A
$3.000
$170,000
$27,000

-------
                                 TABLE 11

      PRELIMINARY COST ESTIMATE FOR THE SEDA PREFERRED ALTERNATIVE
                                 (Page 2 of 2)                               t-
Item/Description
Quantity    Unit
Unit Cost ($)  Total Cost ($)
Semi-Annual Groundwaler Monitoring (6 wells)
Quarterly Groundwater Monitoring (3 wells)
Semi-Annual Storm Water Monitoring (2 locations)
5-Year Site Review
PRESENT WORTH


6
6
4
1



sample
sample
sample
lump sum •

Discount Rate
Years
$3,000
$3,000
$2,000
$10,000

7%
30
$18,000
$18,000
$8.000
$10.000



                                     30-YEAR PRESENT WORTH COST \   $7.8000001

-------
                                                                  TABLE 12

                                 SUMMARY OF OPERABLE UNIT 3 TPH/VOC StTE CHARACTERIZATIONS
Site
WP-17
FT-l9a
SazDpUnc RctfefuJe/Imreititaflon Results
• Some aerobic activity: indications of anaerobic activity.
• TPH, VOCi (BTEX). and chromium were detected above background.
• Vadoie zone modeling indicaied that benzene in toib will not adversely impact the
groundwater quality.
• TCE, PCE. Chloroform. I.I.I-TCA. and 1,1 -DCE detected in soil-gas.
• TPH. VOCi (BTEX), SVOCs. and 5 metals were detected above background.
• Some aerobic activity occurring; very linle anaerobic activity occuninf at the site.
• Vadoie zone modeling indicated Uul benzene in toils will not adversely impact the
froundwater quality.
Human
Health Risk *
• Cumulative Cancer Risk <
1 .06-6 (construction worker
scenario)
•Hazard Index <1.0
•Stood Lad <10
• Cumulative Cancer Risk =«
4.06-6 (construction worker
scenario)
• Hazard Index 1.0
• Blood Lead < 10
Ecological Risk
There ij no h»bitu
available for ecological
receptors; therefore, there
is no potential ecological
risk.
There is no habitat
available for ecological
receptors: therefore, there
is no potential ecological
risk.
 FT-19b      . Various constituents delected in soil-gas.
             • TPH, VOCs. SVOCs. and 6 metals were delected above background.
             • Test pit excavations revealed that medical wastes were primarily in the surf*
; soils.
• Cumulative Cancer Risk »  There is no habitat
5.2E-6 (industrial/          available for ecological
commercial worker scenario) receptors: therefore, there
• Hazard Index < 1.0        » no P<«»««' ecological
                                                                                           •Blood Lead < 10
                                                                                                                      risk.
 FT-19C      •TCE.PCEChloroform.and l.l.I-TCAdetectedmtoil-g«.
             • TPH. VOCs (BTEX and TCE}. SVOCs. and 11 metals detected above background.
             • Some aerobic activity occurring: very little anaerobic activity occurring at the site.
             • Vadoie zone modeling indicated thai TCE in soils may migrate to the groundwater in
             75 yean if untreated.
          • Cumulative Coxa Risk »
          3.1E-6 (industrial/
          commercial worker scenario)
          •Hazard Index < 1.0
          • Blood Lead < 10
                          There is no habiut
                          available for ecological
                          receptors: therefore, there
                          is no potential ecological
                          risk.
FIXZOfsoil) « TCE detected in soil-gas.
            • TPH. TRPHs. and seven metals detected above background in soil samples. No TCE
            detected.
            • inorganics below or near background were detected iBdowngradiem groundwater,
            • Vadose zone modeling indicated thai contaminants detected at the site do not pose a
            threat to groundwater.
          • Cumulative Cancer Risk <
          4.0E-S (industrial/
          commercial worker)
          •Hazard Index< 1.0
          • Blood Lead < 10
                          There is no habitat
                          available for ecological
                          IfiCtpliil 4i tnCTCiOCCt tACfV
                          is no potential ecological
                          risk.
OT-Sl










SS-59
• No COPCs were detected in samples collected from the soil berm at Facility 807.
• TPH and BTEX detected in samples collected from the soil berm at Facility 799 from
10 to 1 20 feel bgs. Concentration! exceeded the screening criteria.
• TPH detected in samples collected from the engine less cells.
• TPH and BTEX were detected in crougradient groundwaier samples, but were noi
drtrrted in downgradient samples.
• Groundwater Modeling indicaied that benzene may migrate approximately 400 feet
from the source area in SO yean.
• TPH delected in groundwaier samples from two wells installed in the hot spot.


• TPH constituents detected in soil samples at concentralions exccedinc the screenini
• Preliminary screening
indicated thai the site does
not pose a risk because the
confirmed contamination is
at depths that would not
affect receptors in the risk
assessment scenarioc.
Therefore, a risk assessment
calculation was not
performed.
•Blood Lead < 10
See Site OT-Sl.
There is no habiut
available for 'ecological
receptors; therefore, there
is no potential ecological
risk.






There is no habitat
                                                                                                                     available for ecological
                                                                                                                     receptors: therefore, there
                                                                                                                     is no potential ecological
                                                                                                                     risk.
OT-69       -TCEand PCE detected above MCLsin groundwater.
             • PCE not detected in soil samples: TCE detected in small percentage of soil samples.
             • Highest levels of TCE will attenuate to 5 ug/L ia 4O to 45 years.
             • TCE limited to the upper 30 feet of the aquifer.
             • Total volumes of TCE = 0.8 gallons and PCE * 0.006 gallons.
          • Total carcinogenic risk =
          2E-05. No likely exposure
          pathways to on-base workers
          and off-base residents.
          •Hazard Index < 1.0
          • Blood Lead - not
          applicable
                          Because the site is
                          comprised of
                          groundwaier, there is no
                          completed exposure
                          pathway for ecological
                          receptors.
Notes:
a Highest cancer risk from all scenarios evaluated and the scenario under which the highest risk was calculated is presented.

-------
                                          TABLE 13


            NUMERICAL CLEANUP STANDARDS FOR TPH/VOC GROUNDWATER SITES
                           Federal
                                                             Suggested
                                                          Concentration to
                                                          Meet Secondary
Constituent
*
Benzene
Ethylbcnzene
Toluene
Trichloroethene (TCE)
Tetrachloroethene (PCE)
Xylenes
••"•"
MCL
— •— ^— *•-
5
700
1,000
5
5
10,000
	
SMCL
—••*•—— ^•••—-B
NA
30
40
NA
NA
20
ii»
MCL
1
700
150
5
5
1,750
1 '" .
w» a»«w
SMCL
-
NA
NA
NA
NA
NA
NA
aM\*Li ui J
Odor Units
•^ — — •^— — _
NA
29
42
NA
NA
17
Cleanup
Standard
1
29
40
5
5
17
MCL = maximum contaminant level
NA = not applicable
SMCL =s secondary maximum contaminant level


Note: All concentrations are presented in pg/L.


Source: "A Compilation of Water Quality Goals," California RWQCB, Central Valley Region (RWQCB, 1995).

-------
                                                                                                                          tit
                                                                        TABLE 14

                              SUMMARY OF DETAILED ANALYSIS OF REMEDIAL ALTERNATIVES FOR OU 3 TPH/VOC SITES


Alternative


Applicable
Sites
Protection of
Human Health
and the
Environment


Compliance with
ARARs Effectiveness Reduction of TMV Implementability


Total Cost
 6.  No Action for Soil
 7.  Removal/Disposal
 9.  Bioventing
 10. No Action for
    Groundwatcr
 I!. Oxygen Enhanced
    Bioremediation
WP-17.FT-     Does not reduce    Does not comply.    Not effective.
19a, FT-19b,    potential for future
FT-l9c.FT-20   exposure.
(soil),OT-5l.
SS-59
FT-20(soil),
SS-59
 8.  Soil Vapor Extraction     FT-l9c
WP-17.FT-
!9b.OT-5l
OT-51
OT-51
Reduces potential   Complies with      Effective.
for future exposure  ARARs.
Significantly       Complies with      Effective.
reduces potential   ARARs.
for future
exposure.

Significantly       Complies with      Effective.
reduces potential   ARARs.
for future
exposure.

Does not reduce    Does not comply.   Not effective.
potential for future
exposure.
Significantly       Complies with
reduces potential   ARARs.
for future
exposure.	
Effective.
                                                                                            No reduction of TMV.   No technical            See Table 16.
                                                                                                                 limitations.
                Significant reduction of  Easily implemented.     See Table 16.
                TMV through removal.
                treatment, and disposal
                of contaminated soils.

                Significant reduction of  Easily implemented.     See Table 16
                TMV.
                Significant reduction of  Easily implemented.     See Table 16
                TMV.
                                                                 No reduction of TMV.   No technical            See Table 16.
                                                                                      limitations.
                                                                 Significant reduction of  Easily implemented.      See Table 16
                                                                 TMV.
ARARs - applicable or relevant and appropriate requirements
TMV - toxicily, mobility, or volume

-------
                                                                            I
          Source
 Porter-Cologne Water
 Quality Control Act
 (California Water Code)

 Porter-Cologne Water
 Quality Control Act
 (California Water Code)

 Porter-Cologne Water
 Quality Control Act.
 California Water Code
 Sections 13000,13140.
 13240
Porter-Cologne Water
Quality Control Act,
California Water Code
Sections  13140,13240,
13304. 13307
                                                                        TABLE 15

                                                            ARARs FOR GAFB OU 3 TPH/VOC
                                                  SITES WP-17, FM9a, FM9b, FT-lfc, OT-51, AND OT-69
                                                                       (Pace 1 of 9)
 Standard, Requirement,
 Criterion, or Limitation'   ARAR Status*
                                                                                                          Description
 California Water Code
 9 13176


 California Water Code
 5 13750.5


 Slate Water Resources
 Control Board Resolution
 68-16 Statement of Policy
 with Respect to
 Maintaining High Qua|j|y
 of Waters of the Slate
 (Resolution 68-16)
 55 land 2
State Water Resources
Control Board Resolution
92-49 (as amended)
Policies and Procedures
for Investigation and
Cleanup and Abatement of
Discharges Under WflKr
Code Section I33Q4
(Resolution 92-49)
§ HI G.
   Applicable     Requires data analysis to be performed in a State certified laboratory.
                 Potentially applicable to cleanup alternatives involving sampling.


   Applicable     Requires well drillers to possess a C-57 license.
                 Potentially applicable to cleanup alternatives involving installation of wells.


See Description   The resolution establishes requirements for activities involving discharges of contamination
                 directly into surface waters or groundwater (e.g., quality of pump and treat effluent into
                 surface waters or groundwater).

                 The Air Force and the State of California have not agreed whether State Water Resources
                 Control Board Resolution No. 68-16 is an ARAR for the remedial action at any of the OU 3
                 sites.  Therefore, this FS does not identify the requirement as an ARAR for the remedial
                 action. The State asserts that the requirement is an ARAR. and that it requires soil
                 remediation where a discharge impacts or threatens to impact the beneficial uses of waters of
                 the State. The State has decided not to invoke dispute resolution because the proposed action
                 will address threatened impacts to waters of the State.

See Description   The USAF and USEPA agree that Resolution No. 92-49, Section I1I.G. is an ARAR for
                purposes of the OU 3 RI/FS with respect to groundwater remediation at all groundwater sites
                and the soil remediation at OT-51 and FT-19. The USAF contends, for purposes of this
                RI/FS, that Section 1H.G. is a "relevant and appropriate" requirement. The Slate contends
                Section III.G is an "applicable" requirement. The cleanup standards set forth in  Table 13
                satisfy (he requirements of SWRCB Resolution 92-49.

-------
          Source
                                                                       TABLE IS

                                                           ARARs FOR GAFB OU 3 TPH/VOC
                                                 SITES WP-17, FT-19a, FT-19b, FT-19c, OT-51, AND OT-69
                                                                      (Page 2 of 9)
 Standard, Requirement,
 Criterion, or Limitation'   ARAR Status'
                                                                                                        Description
 Porter-Cologne Water
 Quality Control Act,
 California Water Code
 Sections  13240,13241,
 13242.13243,13382
Porter-Cologne Water
Quality Control Act,
California Water Code
Sections  13240,13241,
13242. 13243, 13382

Federal Safe Drinking Water
Act, 40 CFR Part 141,
Subpari G or California
Hazardous Waste Control
Law.22CCR
 Water Quality Control
 Plan for the Lahontan
 Region (Basin Plan)
 effective March 31,1995
 Table 2-2. Beneficial Uses
 for Groundwater of the
 Lahontan Region,
 Department of Water
 Resources Basin No. 6-42,
 Upper Mojavc River
 Valley, page 2-46

 Basin Plan
 Water Quality Objectives
 for Groundwatcrs, page 3-
 2,3-12. and 3-13
40 CFR 141.61 or
Table 64444-A-
Maximum Contaminant
Levels - Organic
Chemicals
 Applicable
 Applicable
Relevant and
Appropriate
 The beneficial uses of ground waters beneath GAFB are defined as:
 a) Municipal;
 b) Agricultural;
 c) Industrial;
 d) Fresh Water Replenishment; and  '
 e) Aquaculture,
 Potentially applicable to alternatives addressing groundwater contamination at Sites OT-51
 and OT-69.
The water quality objectives that apply to affected ground waters are for: Coliform Bacteria.
Chemical Constituents, Radioactivity, and Taste and Odor. Compliance will consider other
potential ARAR standards such as State and Federal MCLs. Potentially applicable to
alternatives addressing groundwater contamination at Sites OT-51 and OT-69  The cleanup
standards for this ROD are set forth in Table 13.

Primary MCLs for organic constituents which are contaminants of concern at the Site.  State
MCLs which are more stringent than the Federal MCLs, or not addressed by Federal MCLj,
and therefore potentially ARARs are:  benzene, toluene, and xylene. Potentially relevant and
appropriate to remedial alternatives addressing groundwater at Sites OT-51 and OT-69 The
cleanup standards for this ROD are set forth in Table 13.

-------
                                                                         I
                                                                      TABLE 15
         Source
                                                          ARARi FOR GAFB OU 3 TPH/VOC
                                                SITES WP-17, FT-19., FW», FT.19c, OT-S1, AND OT-69
                                                                     (Page 3 of 9)
Standard, Requirement,
Criterion, or U mttation'   ARARSutusk
CSDWA
                           Table 64449-A-
                           Secondary Maximum
                           Contaminant Levels,
                           Consumer Acceptance
                           Limits
                           Table 64449-B-
                           Secondary Maximum
                           Contaminant Levels -
                           Ranges
                          Relevant and   Defines secondary maximum contaminant levels (SMCLs)
                          Appropriate    Potentially rckvam ^d appropriate to remedial alternatives addressing groundwater at Sites



                                                 '"?•' *f ^ L° d'SagrcC"language has bcen estob«*«l between the Air Force and
                                        "The State asserts that the narrative taste and odor water quality objective specified in the
                                        Water Quality Control Plan for Lahontan Regional Water Quality Control Board which
                                        incorporates state primary and secondary drinking water standards, is an ARAR that applies to
                                        the esubhshment of cleanup levels at this OU. The Air Force agrees that the narrative taste
                                        and odor water quality objective is an ARAR. but does not agree that the secondary odor
                                        standard of three odor units is an ARAR because the measurement is subjective based upon
                                        the sensory determination of a panel.  The Air Force agrees to implement the taste and odor
                                        objectwe for toluene, ethylbenzene. and xylenes by using the numeric taste and odor standards
                                        proposed by USEPA, but not promulgated, as to be considered standards that will be
                                        identified as performance standards in this ROD. The numeric values in Table 13 reflect this
                                        agreement The Air Force also agrees to evaluate compliance with the three odor unit
                                        objective, based on appropriate standard protocols, e.g., EPA Method 140 or Standard
                                        Methods for the Examination of Water and Wastewater, in determining whether the remedial
                                        action is complete. The State reserves its right to dispute, according to the terms of the
                                        Federal Facility Agreement, whether the Air Force has achieved compliance with the taste
                                        and odor objective in the Water Quality Control Plan »

-------
            (»*•
                                                                       TABLE 15

                                                           ARARs FOR GAFB OU 3 TPH/VOC
                                                 SITES WP-17, FT-lJi, FT-19b, FT-19c, OT-51, AND OT-«9
                                                                      (Page 4 of 9)
           Source
  Standard, Requirement,
  Criterion, or Limitation'   ARAR Status*
                                                                                                        Description
 Basin Plan
 Water Quality Objectives for
 Groundwaters, page 3-2 and
 3-12
 Porter-Cologne Water
 Quality Control Act (Porter
 Cologne Act),  California
 Water Code Sections 13140
 -13147.13172.13260,
 13263,13267.13304
 Discharges of Waste to
 Land. Title 23. Chapter 15,
 California Code of
 Regulations (Chapter IS)

 Porter-Cologne Act
 Chapter IS
Porter-Cologne Act
Chapter IS
Porter-Cologne Act
Chapter IS
Memorandum titled
"Beneficial Use-Protective
Water Quality Limits For
Components of Petroleum-
Based Fuels", dated 17
May 1995 (replaces
memoranda dated 3/26/90,
1/14/91,7/6/92,5/13/93,
and 1/18/95)
Central Valley Regional
Water Quality Control
Board- Jon Marshack

§25ll(d)
J2550.l(a)(4)
§ 2SS0.4
J 2550.10
                              To Be
                            Considered
                            Applicable
Relevant and
Appropriate


Relevant and
Appropriate
                          Relevant and
                          Appropriate
                Provides beneficial use protective water quality limits for components of petroleum based
                fuels.
                                                                                                                    ments
               Exempts actions taken by or at the d,rection of public agencies from Chapter IS requirements
               providedI wastes removed are discharged in accordance with Chapter 15. Article 2 and walS
               contained implement Chapter IS requirements to the extent feasible
                                        Requires monitoring performance of selected remedial alternative.
                                        Potentially relevant and appropriate to remedial alternatives addressing groundwater
                                        contamination (Sites OT-51 and OT-69).

                                        Concentration Limits (CL) - Must be established for groundwater. surface water, and the
                                        unsaturated zone. Must be based on background, equal to background, or for corrective
                                        actions, may be greater than background (CLGTB), not to exceed the lower of the MCL or
                                        the concentration technologically or economically achievable (Sites OT-51 and OT-69).

                                        Specifies requirements for ground water remedial action to ensure that the water quality
                                        pr«ect,on standard ,s achieved throughout the zone affected by the release including  but not
                                        hunted to, source control measures and monitoring                     'nc.uamg. but not

-------
                                                           ARARi FOR GAFB OU 3 TPH/VOC
                                                SITES WP-17, FT-19», FT-19b, FT-19c, OT-51, AND OT-
-------
                                                                         i,E 15
                                                         ARARs FOR GAFB Ol) 3 TPH/VOC
                                              SITES WP-17, FT-19a, FT-19b, FT-19c, OT-51, AND OT-69
                                                                    (Page 6 of 9)
         Source
Standard, Requirement,
Criterion, or Limitation*   ARAR Status*
                                                                                                     Description
                           Drilling, Coring,              To Be
                           Sampling and Logging at     Considered
                           Hazardous Substances
                           Release Sites

                           Monitoring Well Design        To Be
                           and construction for          Considered
                           Hydrogeological
                           Characterization

                           Representative Sampling       To Be
                           of Ground Water for         Considered
                           Hazardous Substances

                           Ground Water Modeling        To Be
                           for Hydrogeological          Considered
                           Characterization
                                        Provides minimum construction and destruction criteria for water wells, monitoring wells,
                                        and cathodic protection wells.  Also includes criteria for borehole abandonment
Federal Safe Drinking
Water Act
Federal Clean Water Act 40
CFR122
40CFR144-
Underground Injection
Control Program
USBPA Administered
Permit Programs:
National Discharge
Elimination System 40
CFR122-26
Applicable     Establishes substantive requirements for actions that involve injection of fluids into
              subsurface through wells. The injection cannot cause a violation of primary MCLs, must be
              maintained, must be monitored, and injection cannot take place until the well construction is
              complete.
              Applies to cleanup of OT-51.

Applicable     Requirements ensure stormwater discharges from remedial action activities do not violate
              surface water quality standards. To comply with this requirement, the US AF must comply
              with the requirements contained in the State General Industrial Storm Water Permit (Order
              No. 91-13-DWQ, as amended by Order No. 92-12-DWQ, NPDES CAS000001).

-------
                                                         ARARs FOR GAFB OU 3 TPHAVOC
                                               SUES WP-17, FT.19*, FT.lSfc, FM9c, OT-5I, AND OT-69
          Sourc*
 Federal Clean Water Acl
 40CFRPart264.SubpartB
 (General Facility
 Standards), as delegated to
 the State and implemented
 through Hazardous Waste
 Control Law (HWCL) TiUe
 22 Social Security, (22
 CCR) Division 4.5.
 (Environmental Health   .
 Standards for the
 Management of Hazardous
 Wastes), Chapter 11,
 Articles 1-5, Chapter 12
 (Standards Applicable to
 Generators of Hazardous
 Waste) and Chapter 14
 (Standards for Owners and
 Operators of Hazardous
 Waste Transfer, Treatment,
Storage, and Disposal
Facilities), Articles 2
 Stiadanl, Requirement,
 Criterion, or Limitation*   ARAR Status*
 40CFR 5122.41(d),
 122.41 (e), and 122.44(d)
40 CFR 5264.13
22 CCR $66262.11
22 CCR 566262.13

40 CFR 5264.14
22 CCR 566262.14

40 CFR 5264.15
22 CCR 566262.15
                                                                             f
                                                                   likelihood of causmg adverse impacts on surface water quality
                                                                   *«•***»» «-« beproperiy operated and
Applicable
                                                   0rt0min^
             Potentially applicable to cleanup alternatives at facilities which involve on-site treatment.
             storage, or d,sposal of hazardous waste (i.c, investigation derived waste [1DWJX

-------
                                                                             15
                                                         ARARs FOR GAFB OU 3 TPH/VOC
                                               SITES WP-17, FT-19a, FT-19b, FM9c, OT-51, AND OT-69
                                                                    (Page 8 of 9)
         Source
Standard, Requirement,
Criterion, or Limitation*
                                                    ARAR Status'
                                                 Description
40 CFR Part 264, Subpart C
(Preparedness and
Prevention) as delegated to
the State and implemented
through HWCL 22
CCR, Division 4.5, Chapter
14, Ankle 3 (Preparedness
and Prevention)

40 CFR Part 264, Subpart D
(Contingency Plan and
Emergency Procedures) as
delegated to the State and
implemented through
HWCL 22
CCR, Division 4.5, Chapter
14, Article 4 (Contingency
Plan and Emergency
Procedures)

40 CFR Part 264, Subpart 1
(Use and Management of
Containers) as delegated to
the State and implemented
through HWCL 22 CCR,
Division 4.5, Article 9 (Use
and Management of
Containers
40 CFR 55 264.31-34
22 CCR 55 66264.31-34
40 CFR 55 264.51-
264.53.(a) and 264.55
22 CCR 5566264.51-
53(a) and 66264.55
 40 CFR 55 264.171-
 264.178
 22 CCR 55 66264.171
 66264.178
Applicable or   Requires that hazardous waste TSD facilities be designed, constructed, operated and
Relevant and   maintained to minimize the possibility of fire, explosion, or release of hazardous waste (40
 Appropriate    CFR 5 264.31 and 22 CCR 566264.31).
               Potentially applicable or relevant and appropriate to cleanup alternatives at facilities which
               involve on-site treatment, storage, or disposal of hazardous waste (i.e., IDW).
Applicable or   Requires development and, if appropriate, implementation of a contingency plan to minimize
Relevant and   hazards to human health or the environment from fire, explosion, or release of hazardous
 Appropriate    substances (40 CFR 1264.51 and 22 CCR §66264.51).
               Plan must contain certain items (40 CFR 5264.52 and 22 CCR 566264.52).
               Plan and emergency coordinator must be on-site (40 CFR 55 264.53.(a) and 264.55; 22 CCR
               §566264.53(3) and 66264.55).
               Potentially applicable or relevant and appropriate to cleanup alternatives at facilities which
               involve on-site treatment, storage, or disposal of hazardous waste (i.e., IDW).
Applicable or   Requires that containers used for storage be in good condition (40 CFR § 264.171 and 22
Relevant and   CCR 566264.171).
 Appropriate    Requires that containers used for storage be compatible with the hazardous substance (40
               CFR 5 264.172 and 22 CCR 566264.172).
               Requires proper management of containers during storage and handling (40 CFR 5 264.173).
               Requires inspections of containers used to store hazardous substances (40 CFR 5 264.174
               and 22 CCR 566264.174).
               Requires adequate secondary containment for stored hazardous waste, as specified (40 CFR
               5 264.175 and 22 CCR 566264.175).
               Requires isolating stored, ignitable waste (40 CFR 5 264.177 and 22 CCR 566264.177).
               Requires removal of stored hazardous waste at closure of the TSD hazardous waste facility
               (40 CFR 5 264.178 and 22 CCR 566264.178).

               Potentially applicable or relevant and appropriate to cleanup alternatives at treatment,
               storage, or disposal facilities which store hazardous waste on-site (e.g., IDW).

-------
                                                        ARARs FOR GAFB OU 3 TPH/VOC
                                              SITES WP.17, FT-19., FM9b( FT-19C, OT-51, AND OT-
-------
                                                        ; 16
                           SUMMARY OF REMEDIAL ALTERNATIVE COSTS FOR OU 3 TPWVOC SITES
Site
WP-I7



FT-19.



FT-19b



FT-JJc



FT-20(sotl)



OT-51
(soil)


OT-51
(groundwater)


SS-59



Cost Criteria Alternative 6 Alternative? Alternatives Alternative 9 Alternative 10 Alternative 11
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present- Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30-Year Present- Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30-Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30-Year Present- Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present-Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30- Year Present- Worth Cost
Construction Cost
Direct Capital Cost
Total Capital Requirement
30-Year Present-Worth Cost
$8.800
$12.900
$14,800
$110.000
$0
$0
$0
$170,000
$0
$0
$0
$170,000
$0
$0
$0
$170,000
$0
$0
$0
$170.000
$16,600
$24.200
$27,000
$280,000
NA
NA
NA
NA
$8.800
$12.900
$14.800
$110.000
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
$27,600
$40,300
$52.800
$52,800
NA
NA
NA
NA
NA
NA
NA
NA
$28,200
$41.200
$54,000
$54,000
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
$199,500
$326.900
$444.000
$680,000
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
$46.400
$73.100
$107.000
$270.000
$228,480
$369,900
$501.000
$780.000
$40.600
$64,600
$95.000
$250.000
NA
NA
NA
NA
NA
NA
NA
NA
$182.900
$280.700
$383.000
$660.000
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
$0
$0
$0
$250.000
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
$3.500
$6,500
$62,000
$280,000
NA
NA
NA
NA
NA - not applicable

-------
                          TABLE 17

PRELIMINARY COST ESTIMATE FOR SITE WP-17 PREFERRED ALTERNATIVE
                         (Page 1 of 2)
Item/Description
DIRECT CAPITAL COSTS (DCC) '
Equipment Costs (EC)
Aboveground collection Piping (2-inch PVC)
Bioventing Blower (IS horsepower)
Valve/gauge

Construction Costs (CC)
Surface Repair/Preparation
Extend Power from Bldg. 551 or 552
Fence
Visquecn
Pea Gravel
Vents and Monitoring Point Borings
Equipment Pad
Analytical
Mechanical
Instrumentation
Electrical

Supervision, Health & Safety
Bid Contingency
Scope Contingency
Contractors Overhead and Profit

INDIRECT CAPITAL COSTS
Treatability Study
Engineering Design Services
Construction Management
Administration Costs {GAFB/AFCEE)
Final O&M Manuals
Quantity Unit

30 linear foot
1 each
3 each


1 lump sum
1 lump sum
40 feet
4,800 square feet
20 cubic yards
1 lump sum
1 lump sum
! lump sum
40% of EC
10% of EC
20% of EC

8% of CC
10%ofCC
8%ofCC
20% of CC
Subtotal Direct Capital

lump sum
6% of DCC
10% of DCC
15% of DCC
2% of DCC
Unit Cost ($)

$30
$4.000
$150
Subtotal EC

$3,000
$2.500
$20
$2
$90
$15,864
$2,500




Subtotal CC




Cost* (DCC)





TOTAL CAPITAL REQUIREMENT)



Total Cost ($)

$900
$4.000
$450
$5.350

$3.000
$2,500
$800
$9,600
$1,800
$15,864
$2.500
$1.243
$2,140
$535
$1.070
$46,402
$3,7112
$4 MO
«^*T(»^rw
$3.712
$9,280
$73,096

$9.455
$4,386
$7,310
$10,964
$1,462
$107,000 1

PERIODIC OPERATING AND MAINTENANCE COSTS 	 	 ' 	
Bioventing (Years 1-3)
Energy
Labor
Maintenance Materials

10,000 kW-hr
250 hours
5% of EC

$0.10
$60


$1,000
$15.000
$268

-------
                                           TABLE 17

          PRELIMINARY COST ESTIMATE FOR SITE WP-17 PREFERRED ALTERNATIVE
                                          (Page 2 of 2).
Item/Description
Quarterly Ground water sampling (1 well)
Demobilization (Year 3)
System Demolition
Vent/Well Abandonment
Site Closure Analyses
Confirmation Sampling (Year 5)
Boring Installation ( 1 boring)
Analytical
5- Year Site Review
PRESENT WORTH
Quantity
4
1
7
1
1
1
1
Unit
sample
lump sum
each
lump sum
lump sum
lump sum
lump sum
Discount Rate
Years
TOTAL PREI
Unit Cost ($)
$3,000
Subtotal
$20.000
$3.000
$45.000
Subtotal
$4.892
$1.388
Subtotal
$5.000
7%
5
SENTWORTH[

Total Cost ($)
$12.000
$28.268
$20.000
$21.000
$45.000
$86,000
$4.892
$1.388
$6,280
$5.000

$270.000 |

Assumptions:
 1 After 3 year estimated cleanup time, there will be closure on the site and no continued monitoring.
 2 One injection vent and 6 monitoring points will be installed as part of bioventing system.
 3 One confirmation boring will be installed to a depth of 80 feet at the hot spot at the end of year 3. Five samples will
   be collected from the boring.

-------
                                     TABLE 18

         PRELIMINARY COST ESTIMATE FOR SITE FT-19. PREFERRED ALTERNATIVE
                                    (Page 1 of 2)
  Item/Description

DIRECT CAPITAL COSTS (DCC)

  Equipment Coots (EC)
Quantity   Unit     Unit Cost ($)   Total Coat ($)
»u~>i.giuuiiu coiiccuon ripmg (2-incn PVC
Biovcnting Blower (5 horsepower)
Valve/gauge

Construction Costs (CC)
Surface Repair/Preparation
Extend power from OU I Treatment System
Fence
Vjsqueen
Pea Gravel
Vents and Monitoring Point Borings
Equipment Pad
Analytical
Mechanical
Instrumentation
Electrical


Supervision, Health 
-------
                                           TABLE 18

          PRELIMINARY COST ESTIMATE FOR SITE FT-19* PREFERRED ALTERNATIVE
                                           (Page 2 of 2)
   Item/Description
Quantity    Unit
Unit Cost ($)    Total Cost ($)
     Maintenance Materials
     Quarterly Groundwater Sampling (2 wells)
          5% of EC
           sample
      $3,000 _
     Subtotal
 $1,818
$24,000
                                                                                     $44,148
Demobilization (Year 5)
System Demolition
Vent/Well Abandonment
Site Closure Analyses
Confirmation Sampling (Year S)
Boring Installation (4 borings)
Analytical
5- Year Site Review
PRESENT WORTH
1 lump sum
14 each
1 lump sum
1 lump sum
1 lump sum
lump sum
Discount Rate
Years
$20,000
$3,000
$45.000
Subtotal
$12.858
$4.484
Subtotal
$5.000
7%
5
$20,000
$42,000
$45,000
$107,000
$12,858
$4,484
$17341
$5.000

                                                       TOTAL PRESENT WORTH!    $780,000   \
Assumptions:
 1 After S year estimated cleanup time, there will be closure on the site and no continued monitoring.
 2 Six injection vents and 9 monitoring points will be installed as part of bioventing system.
 3 Three confirmation borings (one at each hot spot) will be installed each to a depth of 115 feet at the end of year 5.
  Five samples will be collected from each boring.

-------
                                  TABLE 19
      PRELIMINARY COST ESTIMATE FOR SITE FT-19c PREFERRED ALTERNATIVE
                                 (Page 1 of 2)
Item/Description
                                     Quantity    Unit     Unit Cost ($)  Total Cost ($)
uiKfcl 1 CAPITAL COSTS (DCC) 	
Equipment Costs (EC)
Aboveground Collection Piping (2-inch PVC)
SVE Blower ( 10 horsepower)
Valve/gauge
Construction Costs (CC)
Surface Repair/Preparation
Extend power from FT-19a treatment unit
Fence
Visqueen
Pea gravel
Vents and Monitoring Point Borings
Equipment Pad
Analytical
Mechanical
Instrumentation
Electrical
Supervision. Health & Safety
Bid Contingency
Scope Contingency
Contractors Overhead and Profit
INDIRECT CAPITAL COSTS
Treatability Study
Engineering Design Services
Construction Management
Administration Costs (GAFB/AFCEE)
Final O&M Manuals
400 linear foot $30 $12,000
1 each $20,000 $20.000
24 «!ach $150 $3.600
Subtotal EC $35,600
1 lump sum $3,000 $3.000
1 lump sum $10,000 $10.000
40 feet $20 $800
20,000 square feet $2 $40,000
380 cubic yards $90 $34.200
1 lump sum $45.945 $45,945
1 lump sum $2.500 $2,500
1 lump sum $2,524
4°* °f EC $,4,240
10% of EC $3,560
20% of EC $7,120
Subtotal CC $199.489
8% of CC $15,959
IO%ofCC $19,949
8%ofCC $15,959
20%ofCC $39.898
Subtotal Direct Capital Costs (DCC) $326,854
lump sum $9,455
6% of DCC $i9,6n
10% of DCC $32.685
15% of DCC $49,028
2% of DCC $6437
loi ALLAPiiAL REQUIREMENT) $444.000 |
PERIODIC OPERATING AND MAINTENANCE COSTS 	 	
SVE (Years 1-5)
S£f 67.000 kW-hr $0.10 $6.700
., . 250 hours $60 Sisnnn
Mamtcnance Materials 5%ofEC *" »*«»

-------
                                          TABLE 19

         PRELIMINARY COST ESTIMATE FOR SITE FT-19c PREFERRED ALTERNATIVE
                                         (Page 2 of 2)
   Item/Description
Quantity     Unit      Unit Cost ($)   Total Cost {$)
     Quarterly Groundwater Sampling (2 wells)
           sample
 $3,000 _
Subtotal'
$3,000
                                                                                 $26,480
Demobilization (Year 5)
System Demolition
Vent/Well Abandonment
Site Closure Analyses
Confinnation Sampling (Year 5)
Boring Installation (4 borings)
Analytical
5- Year Site Review
PRESENT WORTH
1 lump sum
19 each
1 lump sum
1 lump sum
I lump sum
1 lump sum
Discount Rate
Years
$20,000
3,000
$45,000
Subtotal
$16.142
$9.368
Subtotal
7%
5
$20,000
$57.000
$45,000
$122.000
$16,142
$9,368
$25,510
$5.000

                                                    TOTAL PRESENT WORTHJ   $680.000    I
Assumptions:
 1 After 5 year estimated cleanup time, there will be closure on the site and no continued monitoring.
 2 Seven injection vents and 12 monitoring points will be installed as part of SVE system.
 3 Four confirmation borings (one at each hot spot) will be installed each to a depth of 115 feel at the end of year 5.
   Five samples will be collected from each boring.

-------
                                  TABLE 20
  PRELIMINARY COST ESTIMATE FOR SITE OT-SI SOILS PREFERRED ALTERNATIVE
                                 (Page 1 of 2)
Item/Description
                                     Quantity    Unit    Unit Cost ($)   Total Cost ($>
DIRECT CAPITAL COSTS (DCC)
Equipment Costs (EC)
Aboveground collection Piping (2-inch PVC)
Bioveniing Blower (5 horsepower)
Valve/gauge

Construction Costs (CC)
Downgradiem Monitoring Well Installation
Surface Repair/Preparation
Extend power from OU 1 Treatment System
PWru*A
j^ncc
Visqucen
Pea Gravel
Vcnis and Monitoring Point Borings
Equipment Pad
Analytical
Mechanical
Instrumentation
Electrical

Supervision, Health & Safety
Bid Contingency
Scope Contingency
Contractors Overhead and Profit
INDIRECT CAPITAL COSTS
Treatability Study
Engineering Design Services
Construction Management
Administration Costs (GAFB/AFCEE)
Final O&M Manuals


30 linear foot
1 each
12 each


2 lump sum
1 lump sum
1 lump sum
40 feet
4.800 square feet
20 cubic yards
1 lump sum
1 lump sum
1 lump sum
40% of EC
10* of EC
20% of EC

8%ofCC
10%ofCC
8% of CC
20%ofCC


$30 $900
$11.000 $11.000
$150 $1,800
Subtotal EC $13,700

$16,605 $16,605
$3.000 $3,000
$75.000 $75.000
$20 $800
$2 $9,600
$90 $1,800
$45.113 $45.113
$2,500 $2,500
$5.151
$5.480
$1,370
$2.740
Subtotal CC $182.859
$14,629
$18.286
$14,629
$36.572
Subtotal Direct Capital Costs (DCC) $280,674
lump sum
6% of DCC
10% of DCC
15% of DCC
2% of DCC
$9,455
$16,840
$28,067
$42 1O1
«*•**» * VI
$5.613
TOTAL CAPITAL REQUIREMENT! $383.000 1



PERIODIC OPERATING AND MAINTENANCE COSTS 	 : 	 ' 	
Bioventing (Years 1-5)
Energy
¥ 1.
Labor
Maintenance Materials

16.700 IcW-hr
250 hours
5% of EC

$0.10 $1,670
$60 $15000
***"* «*• I •*« VvV
$685

-------
                                           TABLE 20

      PRELIMINARY COST ESTIMATE FOR SITE OT-51 SOILS PREFERRED ALTERNATIVE
     	                    (Page 2 of 2)
    Item/Description
Quantity    Unit     Unit Cost ($)    Total Cost ($)
      Quarterly Groundwater Sampling (2 wells)
   Demobilization (Year 5)
      System Demolition
      Vent/Well Abandonment
      Site Closure Analyses
   Confirmation Sampling (Year 5)
           sample
   1      lump sum
   10       each
   1      lump sum
 $3.000
Subtotal"
$20,000
 $3,000
$45,000 _
Subtotal
$24.000
                                                                                     $41,355
$20,000
$30,000
$45.000
                                                                                     $95,000
Boring Installation (4 borings)
Analytical
5- Year Site Review
PRESENT WORTH
1 lump sum
i lump sum
lump sum
Discount Rate
Years
$16.652
$5.305
Subtotal
7%
5
$16.652
$5,305
$21,957
$5,000

                                                       TOTAL PRESENT WORTHl    $660.000
Assumptions:
 1  After 5 year estimated cleanup time, there will be closure on the site and no continued monitoring.
 2 Four injection vents and 6 monitoring points will be installed as pan of bioventing system.
 3 Four confirmation borings will be installed each to a depth of 120 feet at the end of year 5. Five
   samples will be collected from each boring.
 4 Installation of two 135-foot downgradient monitoring wells would be required to satisfy
   long-term monitoring requirements.

-------
                                   TABLE 21
PRELIMINARY COST ESTIMATE FOR SITE OT-51 GROUNDWATER PREFERRED ALTERNATIVE
                                  (Page 1 of 2)
  Item/Description
                                       Quantity    Unit   Unit Cost ($)  Total Cost ($)
Initial Equipment Costs (ffiC)
ORC Filler Sock Canister
Periodic Equipment Costs (PEC)
ORC filter socks (3 wells. 10 feet each)
Shipping for ORC filter socks
Construction Costs (CC)
Installation of ORC
Mobilization
Demobilization
Supervision. Health & Safety
Bid Contingency
Scope Contingency
Contractors Overhead and Profit
•
INDIRECT CAPITAL COSTS
Land Use Restrictions
Administration Costs (GAFB/AFCEE)
Engineering Design Services
Final O&M Manuals
PERIODIC OPERATING AND MAINTENANCE
Annual Groundwater Monitoring {4 wells)
Semi-Annual Groundwater Monitoring (4 wells)
Quarterly Groundwater Monitoring (2 wells)
Semi-Annual ORC sock replacement (years 1-3)
5- Year Site Review
PRESENT WORTH 	
30 feet
30 feet
138 Ibs
1 lump sum
1 lump sum
1 lump sum
8% of CC
10%ofCC
8% of CC
20%ofCC
Subtotal Direct Capita
1 lump sum
I lump sum
6%ofDCC
2% of DCC
TOTAL CAPITAL REQ
COSTS 	
4 sample
4 sample
4 sample
2 each
1 lump sum
Discount Rate
Years
$11 $330
subtotal IEC $330
$32.50 $975
$0.27 $37
subtotal PEC $1.012
$2400 $2.500
$500 $500
$500 $500
Subtotal CC $3.500
$280
$350
$280
$700
1 Costs (DCC) $6,452
$50.000 $50.000
$5.000 $5.000
$387
$129
fUlREMENTf $62.000 J

$3,000 $12.000
$3.000 $12,000
$3,000 $12.000
$6.122 $12.245
$5,000 $5.000
,— —
7%
5
                                         TOTAL PRESENT WORTH["1280000""]

-------
                                           TABLE 21

 PRELIMINARY COST ESTIMATE FOR SITE OT-51 GROUNDWATER PREFERRED ALTERNATIVE
                                           (Page 2 of 2)

Assumptions:
  1  Oxygenation of upper portion of aquifer would be accomplished with system to be installed to remediate soils
    and the use of oxygen release compound (ORC) in the top 10' of groundwater in the 3 existing monitoring wells.
  2  Installation of ORC will require a 2 person crew for 2 days.
  3  Source removal will be achieved through the use of a bioventing system.
  4  ORC socks will be replaced every 6 months for 3 years starting at the end of the first 6 months.
  5  Filter sock canister is reusable.  They prevent socks from getting stuck in wells once spent.
  6  Spent ORC socks can be disposed of in a sanitary landfill.
  7  Groundwaier cleanup will be achieved in 3 years. Groundwater monitoring will continue through year 5.

-------
                                                                       TABLE22

                                 SUMMARY OF DETAILED ANALYSIS OF REMEDIAL ALTERNATIVES FOR SITE OT-69
             Alternative
  G-l No Action.
 Protection of
 Human Health and
 the Environment     Compliance
	  wfthARAto    Effectiveness

 Does not reduce       Complies with   Effective.
 existing potential for   ARARs.
 future exposure.
 G-2 Natural Attenuation/Institutional   Reduces potential for Complies with  Effective.
      Controls                       future exposure      ARARs.


 G-3 In Situ Air Sparging, SVE        Significantly reduces  Complies with  Effective
      Recovery/Abatement in Vadose   potential for future    ARARs.
      Zone, Groundwater Monitoring,   exposure.

 G-4 Groundwater Extraction, Surface   Significantly reduces  Complies with  Effective
      Groundwater Treatment with      potential for future    ARARs.
      UV-Oxidalion, Reinjection of     exposure.
      Treated Groundwater.

 G-5 Groundwater Extraction, Surface   Significantly reduces  Complies with   Effective
      Groundwater Treatment with      potential for future    ARARs.
      GAC, Reinjeciion of Treated      exposure.
      Groundwater.

 G-6 Groundwater Extraction. Surface   Significantly reduces  Complies with   Effective
      Groundwater Treatment with      potential for future    ARARs.
      Thermally Abated Air Stripping,   exposure.
      Reinjection of Treated
	Groundwater.
* Present worth with 7% discount rate.

ARAR - applicable or relevant and appropriate
TMV - toxicity, mobility, or volume
Reduction of TMV      ImplemqiUbUity      Total Cost'

                                                 SO
                                                                                       Reduces concentrations to  Very easy.
                                                                                       acceptable levels through
                                                                                       natural attenuation.

                                                                                       Reduces concentrations to  Very easy.
                                                                                       acceptable levels through
                                                                                       natural attenuation.

                                                                                       Significantly reduces      Technically
                                                                                                               implementable.
                                                                                       Significantly reduces      Technically
                                                                                                              implemenlable.
                                                                                       Significantly reduces
                                                                                       TMV.
                                                                                       Significantly reduces
                                                                                       TMV.
                                                                           Technically
                                                                           implementable.
                                                                           Technically
                                                                           implementable.
                                                                                                  $668,000
                                                                                                 $14.876,000
                                                                                                 $23,917,000
                                            $11,005,000
                                            $10,757.000

-------
                                                          TABLE 23
                      SUMMARY OF REMEDIAL ALTERNATIVE COSTS FOR SITE OT-69 GROUNDWATER
   Site      Cost Criteria
Alternative G-l  Alternative G-2  Alternative G-3  AlternativeG-4  Alternative G-5 Alternative G-6
  OT-69    Capital Cost
            O&M Cost
            30-Year Present Worth Cost
            SO         $122.000
            $0          $40.000
            $0         $668.000
$13.090,000
 $1,911.000
$14,876.000
$12,693.000
 $1.598.000
$23.917.000
 $5.211,000
  $825,000
$11.005.000
 $3,705,000
 $1.004.000
$10,757.000
Source: (IT, I995a)

-------
                                        TABLE 24

         PRELIMINARY COST ESTIMATE FOR SITE OT-69 PREFERRED ALTERNATIVE
(G-2)
Item/Description
Quantity Unit
DIRECT CAPITAL COST (DCC)
Natural Attenuation Work Plan , iumpsum
Install 10 Dedicated Sampling Pumps i |umpsum
Allowance for Unidentified Equipment i lump sum
Allowance for Offloading and Setting Equipment 1 Jump sum
Freight Allowance
Subtotal Construe!
Contingency 20%ofCC
Subtotal Direct Capita
TOTAL CAPITAL REQj
PERIODIC OPERATING AND MAINTENANCE COST
Annual Groundwater Monitoring (10 wells, 4 quarters)
Annual Maintenance Cost
40 wells
1 lump sum
PRESENT WORTH
Discount Rate
Years
30-YEAR PRESENT WO1
Unit Coat ($)
$56,000
$31,000
$9,000
$2,000
$4,000
Son Cost (CC)Q

•1 Cost (DCC)Q

UIREMENT f"~
$1.000
7%
46
RTHCOST |
Total Cost ($)
$56,000
$31.000
$9.000
$2,000
$4,000
$102,000 1
$20,000
$122,000 |

$122.000 I
$39,000
$1.000

$668.000 1
Assumptions:
  Estimated duration of remediation is 46 years.

Source: IT, 1995a

-------
                                             TABLE 25

             SUMMARY OF CURRENT REMEDIAL ALTERNATIVE COSTS FOR OU 3 SITES
                           WITH ACCELERATED ACTIONS PERFORMED
   Site
            FS Estimated      Actual
 Selected       Present      Construction
Alternative   Worth Cost *b   Cost to Date*
Current Estimated
  Annual O&M
     Cost*
Current Estimated
  Present Worth
     Cost**
Landfill Sites
DP-03
DP-04
LF-12
LF-14
LF-44
SEDA
TPH/VOC Sites
WP-17
FT-l9a
FT-19c
OT-51 (Soil)

4
4
3
3
2
3

9
9
8
9

$1,200,000
$1,100,000
$1,600,000
$3,800,000
$510,000
$7,800,000

$270,000
$780,000
$680,000
$660,000

$340,000
$340,000
$1,093,000
$1.639,000
$51,000
$3,795,000

$72,000
$191,000
$224,000
$96,000

$4,000
$4,000
$16,000
$24,000
$500
$53.000

$4,000
$6,000
$11,000
$6,000

$1,100,000
$900,000
$2,200,000
$3,100,000
$390,000
$6,600,000

$210,000
$450,000
$520,000
$380,000
a)  Includes long-term groundwater monitoring for an assumed period of time.

b)  FS present worth costs are initial estimates as presented in the OU 3 FS Report (Montgomery Watson, 1997a)
   developed prior to implementation of accelerated actions.

c)  Based on actual construction costs for accelerated actions performed to date.
d) Current estimated present worth is modified from FS present worth by including actual construction costs
   and current estimated O&M costs.

-------

-------
                                                    Q.
                                                    5*
                                                    >
          Appendix A
MONTGOMERY WATSON

-------

-------
             APPENDIX A
ACTION ITEMS TO MEET ROD REQUIREMENTS

-------

-------
                                    APPENDIX A

                 ACTION ITEMS TO MEET ROD REQUIREMENTS


Table 1 of this document lists the Operable Unit (OU) 3 Installation Restoration Program (IRP)

sites and presents the selected remedy for each site.  As described in Section 2.9, accelerated

actions have been initiated at some of the OU 3 Sites presented in this OU 3 Record of Decision

(ROD).  The following is a summary  of the action  items identified in this document to be

performed to satisfy the requirements of this ROD for the OU 3 IRP sites:


     •      Develop OU 3 Landfill Post-Closure Maintenance and Monitoring Plan.

     •      Develop Water Quality Protection Standards (WQPS) for OU 3 Landfill sites. The
           WQPS will be developed within 6 months of the signing of this ROD and will be
           based on the available  groundwater data to establish  baseline  values for which
           future sampling results will be compared.

     •      Develop detailed language describing access and land use descriptions.

     •      Prepare  periodic Site WP-17  Bioventing operations  and maintenance (O&M)
           Reports.

     •      Prepare  Site WP-17 Closeout Report.

     •      Prepare  periodic Site FT-19a Bioventing O&M Reports.

     •      Prepare  Site FT-19a Closeout Report.

     •      Prepare periodic Site FT-19c SVE O&M Reports.

     •      Prepare Site FT-19c Closeout Report.

     •      Complete closure of large diameter casing well near Site OT-51.

     •      Prepare periodic Site OT-51 Bioventing O&M Reports.

     •      Prepare Site OT-51 Closeout Report.

     •      Prepare Site OT-69 Closeout Report.
                                        A-l

-------

-------
                                                    TJ

                                                    Q.
                                                    5°
          Appendix B
MONTGOMERY WATSON

-------

-------
                  APPENDIX B
CRITERIA FOR ACTIVE SITE REMEDIATION - SITE OT-69

-------

-------
                                                Memorandum
lto:    D. Caron, GAFB                                    Dote:        November 6, 1995

From:
      K. Brown, IT  /Ct*                                         IT Project No. 409887

SubjectCRTTERIA FOR ACTIVE SITE REMEDIATION - SITE OT-€9

      The following text addresses concerns stated by the California Regional Water Quality Control
      Board (RWQCB) in their October 16, 1995 correspondence.

      Model Projections
      Specific trichloroethene (TCE) concentration projections, over time, for monitoring wells located
      in the MW-49 and Operable Unit 2 (OU2) areas have been developed.  Figure 3-1 of the
      TCE/PCE Remedial Investigation/Feasibility Study is attached and presents the impacted area
      locations.  Tables 1 and 2 illustrate the decreasing concentration of TCE which is expected
      during natural attenuation.  Predicted concentrations are stated as a range, showing 15 percent
      variation about the mean. This 15 percent range is used to account for non-analytical variances
      which may occur during sampling.  Analytical method variances will also be considered  (see
      Criteria for Evaluating Data).

      Non-analytical variances are attributable to normal variations recognized with changes in
      sampling  personnel, procedures, and equipment  These variances should be accounted  for,
      especially during the sampling of a volatile.

      A two-dimensional numerical model, Solute, was used to model the fate and transport of TCE.
      For a detailed discussion refer to Section 4.0 of the TCE/PCE RI/FS. Conservative estimates
      of modeling parameters such as hydraulic conductivity, dispersitivity, density, and porosity were
      used during modeling.  As a result, no variability was built into the model that would account
      for analytical and non-analytical variances. All model data was generated using 1995 sampling
      results.

      Ground Water Monitoring
      Five monitoring wells located in the MW-49 area will be monitored three times per year from
      September 1995 through July 1996. These monitoring wells include MW-43, MW-41, MW-15,
      MW-49 and MW-60, and were selected  for monitoring by the George Air Force Base (GAFB)
      remedial project managers (RPM). All wells will be sampled using a combination of slow purge
      and bailing techniques and analyzed for TCE via U.S. Environmental Protection Agency (EPA)
      Method 8010.  The first round of groundwater sampling was completed on September 29, 1995.
      Additional rounds have been contracted and are scheduled for February and July 1996.
                                                                                   44.6-as

-------
 081011                                 **«e 2                      November 7, 1995

 Fbllowing July 1996, these wells will be monitored  yearly by Method 8010.  During the
 evaluation of groundwater data the appropriateness of well selection will be evaluated.

 TCE/PCB-impacted wells within OU2 include MW-28, MW-30, MW-46, MW-23, and MW-14.
 MW-23 and MW-14 were identified as no further action sites due to low concentrations; the
 remaining OU2 well locations will be monitored for TCE/PCE quarterly during the JP4 Natural
 Attenuation Treatability Study.

 MW-23, included in  1995 sampling rounds, provides an illustration of the natural attenuation
 of chlorinated solvents in the presence of aromatic cometabolites (i.e., toluene).  Specifically,
 the MW-23 7 micrograms per liter Gig/L) 1992 TCE concentration has been reduced to 2.8 j*g/L
 (1995) with corresponding detection of biological byproducts (dichloroethane [DCA]).

 The remaining OU2 wells (MW-28, MW-30, and MW-46) were not sampled directly in 1995,
 however, wells downgradient of these primary wells were sampled and analyzed by EPA Method
 8010. In association with MW-28, downgradient wells MW-47, MW-33, and MW-31  were
 sampled twice in 1995 and will be monitored quarterly during 1996. TCE concentrations in
 MW-47, MW-33, and MW-31 were 1.1,0.98, and 2.7 ftg/L, respectively. Each well also had
 DCA, a degradation byproduct.

 MW-36 and MW-64, downgradient of MW-30 and MW-46, were sampled in 1995 and contained
 approximately 3.1  and 1.4 pg/L TCE, respectively.  DCA was detected in MW-64.

 Overall, there is evidence supporting the cometabolic removal of TCE during OU2 plume natural
 attenuation.  Sampling and analysis of selected OU2 wells will occur quarterly during 19% and
 yearly thereafter.

 Criteria for Evaluating Data
 All data will be evaluated following the completion of each sampling event.  Once data has been
 accepted as valid through review of the data quality objectives, results will be compared with
 the previous sampling results and predicted concentrations to screen for significant deviations.
 If there is a significant deviation in contaminant concentration, the well(s) will be resampled in
 a timely  manner.

 As noted in Model Predictions, predicted concentrations are stated as concentration ranges (15
percent around the predicted concentration).  If the sampling data indicates that  the TCE
concentration is above the predicted range, the analytical variability of the sampling method must
be determined.   If the measured concentration is 2 analytical  standard deviations above the
predicted concentration range, verification measures will be initiated. Two standard deviations
are necessary to assure that the contaminant concentrations are truly above the anticipated range
given the extremely low contaminant concentrations that are being considered.

-------
 Cuoa                                   ***« 3                       November 7,  1995

 For example, if TCE concentrations at MW-41 are predicted to range ftom 1.50 to 2.02 pg/L
 during the second year of groondwater sampling, however, the actual concentration is measured
 at 2.5 pg/L, the following steps win be taken.

 1.    Determine*the variability of the analytical method employed at the time of analysis.
 2.    Consider the analytical standard deviation and calculate the possible  contaminant
       concentration range.
 3.    Determine if the calculated range in concentration is 2 standard deviations above the
       predicted concentration range.
 4.    If the concentration is 2 standard deviations above the predicted concentration range,
       initiate verification measures.
 5.    If the concentration is less than 2 standard deviations above the predicted concentration
       range, maintain routine sampling schedule.

 If at the end of this process it is determined that the analytical standard deviation is 0.3 pg/L
 for the above example, men the possible contaminant range is calculated to range up to 2.62
 Mg/L.  The measured concentration at MW-41 fall* within this concentration range, therefore,
 the results indicate that the routine sampling schedule should be maintained.

 Throughout data evaluation, the Air Force wffl maintain open  lines of communication with all
 FFA signatories, including the Water Board.

 Verification Measures
 If it is decided through evaluation with the Water Board that significant concentration increases
 are documented per the criteria presented above in any of the wells sampled during a single
 event, the well  will be resampled in a timely manner.  Additionally, the predictive model will
 be rerun (baseline will not be changed - the model only calibrated) and selected monitoring wells
 reevaiuated to determine their appropriateness in light of potential plume movement.  All data
 and modeling results will be submitted to the GAFB RPM members for discussion prior to
 revising any sampling protocol.

 Once the verification measurements are completed, the Air Force and regulatory agencies will
 meet again to review all data generated and decide on the requirement for an active remediation
 or further monitoring and recalibration of the predictive model. If no treatment or increased
 monitoring is required then aquifer monitoring will revert back to yearly.

Triggers for Active Remediation
During  increased  monitoring,  if any  of the wells tested  indicate increased  contaminant
concentrations (per the method developed in Criteria for Evaluating Data), the Air Force will:

 1. Implementation of the active remedy, or

-------
 Caron
Pftge 4
                                                                    November 7, 1995
 2. Acceptance of a proposal to continue monitoring at an increased frequency, rerun the model
 and/or re-evaluate the monitoring wells used.
 In the event that an active remediation system is required,  in  situ air stripping/soil vapor
 extraction (SVE) recovery will be implemented. The selection of this alternative is valid for at
 least 10 years based on the information available during the development of the RI/FS   No
 additional feasibility studies are anticipated prior to implementation. Revised cost estimates
 should be prepared for the year in which the contingent remedy would be implemented.

 The implementation of in situ air stripping with SVE recovery at the MW-49 area would not
 negatively impact any vadose zone remediation since none is required.  (No contaminant source
 areas were identified in the vadose zone.) It should also be noted that this contingent remedy
 applies only to the MW-49 area and may not be recommended for remediation of the OU2 area.

 As future advances in engineering practice may occur, a reevaluation of remedial alternatives
 is recommended prior to implementation or selection of an active remedial system beyond the
 next decade. The requirement for additional feasibility studies should be determined during the
 reevaluation process.

 Active remediation of OU2 will not adversely  impact the natural attenuation of the MW-49
 plume.  The OU2 plume is downgradiem of MW-49 and will encompass this TCE plume.

 It should also be noted that the Air Force wfll maintain deed restriction/institutional controls on
 tbeproperty.  In addition, the Air Force will pursue through the County of San Bernardino the
 identification of all Base wells within impacted areas as well exclusion zones as a secondary
 backup to deed restrictions. In the event that deed restrictions fail and a well is drilled into the
 plume, the Air Force will initiate well head treatment to remove any contaminant prior to water
 usage.

 The Air Force also suggests that the protocol presented in this document be reviewed every  five
 years along with the ROD by all regulatory parties of the FFA to provide an additional layer of
 surveillance to the process.

 Financial Assurances
The U.S. Air Force will make a timely request for funds by identifying to the Department of
the Air Force the funding needed to complete the ROD activities described in the most recently
approved final ROD in accordance with Executive Order 12088 and OMB circular A-106 which
is updated bi-monthly and for which funding requests are made at least two years in advance
(when possible)  and which are incorporated herein by reference, or any pertinent amendments
to those requirements.
t
   '

-------
Caron                                  Page 5                      November 7, 1995

In the event that Congress fails to appropriate necessary funding for ROD activities at George
Air Force Base, the following will occur

a.    The Air Force will so advise all FFA signatories within 90 days of such failure: and

b.    The Air Force will provide to all FFA signatories documentation of all measures it will
      undertake to ensure that ROD activities are completed in accordance with the most
      recently approved ROD. These measures may include, but are not limited to, continuing
      to seek funding for implementing the contingent remedy.

cc:   J. Cass, Water Board

-------
i
r
I
r
a
         8
       sis
             t*
       ?
           S
               te O
                    is
                    8

                    Ok

                    a

                       8
8
l




ot
                     s
                              is
                              8



                              S
                             Bs;
                           S3
                                 s ±
                                    Si
                               88
                                            f
                                      li
                                      ss
                                       ?1
                                            §
                                               3
                       mt

                       i
                                                    3  H
                                                   a
                                                   •z
                                                     tf

                                                   i!

-------
(V
                                                Table 2
                             Predicted TCE Concent rations Selected OU2 Sites
                                    George Air Force Base, California

                                         IT Project No. 409887
Yetr
U«
I
2
3
4
S
10
15
20
25
30
35
40
45
50
MW-29
7.10
(I»S)
1.21









-



MW-29
Rufe
6.04-1.17
1.03 - 1.39













MW-M
10.00
(1993)
4.54













MW-34
luge
1.50-11.5
3.16-5.22













MW-2J
14.00
(1993)
1.74
7.54
7.27
7.03
6.14
4.64








MW-2S
lute
11.90-16.10
7.43 - 10.05
6.41 - 1.67
6.11-1.36
5.91 -l.0t
5.22-7.06
3.94- 5 J4








MW-4*
16.00
(1993)
5.77
5.10
5.56 .
5J3 •
J.34
4.66

•






M1M6
RwfC •
13.60-11.40
4.90-6.64
4.93 - 6.67
4.73-6.39
4.53-6.13
4.54-6.14
3.96- 5 36








       Hate:

-------
!_Jls

-------
                                                  I
                                                  I
          Appendix C
MONTGOMERY WATSON

-------

-------
                APPENDIX C
         ADMINISTRATIVE RECORD

(On file at the GAFB Environmental Programs Office
    Contact: Air Force Base Conversion Agency
          Department of the Air Force
           AFBCA/DD, Building 321
            13436 Sabre Boulevard
          Victorville, California 92394)

-------

-------
          Appendix D
                                                   I

                                                   §
                                                   Q.
                                                   5"
                                                   o
MONTGOMERY WATSON

-------

-------
                    APPENDIX D
RESPONSES TO AGENCY COMMENTS TO APRIL 1997 DRAFT ROD

-------

-------
        RESPONSES TO USEPA COMMENTS DATED JULY 3,1997 ON THE
          DRAFT RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                    GEORGE AIR FORCE BASE, CALIFORNIA
GENERAL COMMENTS
Comment No. 1:
Response:
Comment No. 2:



Response:


Comment No. 3:


Response:

Comment No. 4:



Response:
As previously agreed at RPM meetings and confirmed in the OU 3
FS, GAFB would not justify selected remedies based on exceeding
human health risk. Accordingly, delete or modify any reference to
the same within the document.

As discussed at the August  14, 1997 RPM meeting, the justification
for the selection of remedies is based on the nine CERCLA criteria,
which includes protection of human health and the environment.
Historically, the RPMs have requested that risk management decisions
be considered for sites where the risk exceeded l.OE-6.  Text has been
added to Section 2.9 (Current Site Status) to state that "in an effort to
accelerate the remedial process, to minimize  present and future
environmental risks, reduce potential impacts to groundwater, and
facilitate  timely transfer of property  to  the community,  cleanup
activities have been initiated under the direction of the USAF, at some
of the sites presented in this ROD" to clarify that site  risk is not the
only reason the RPMs agreed to implement remedial actions.

An  additional summary statement  for Section 2 should cite that
ecological risk concerns will be managed through  a monitoring
plan.

A discussion of the ecological monitoring  plan has been added to
Section 2.9.

For clarity and consistency, Figure 6 should also show the location
of LF-35 it was categorized as a site requiring some action.

Site LF-3S has been added to Figure 6.

A brief summary should be made, for the results of GAFB's follow
through  with U.S. Fish and Wildlife (Doug Laye), for desert
tortoise concerns related to the skeet ranges.

The subject of this ROD is the OU 3  IRP sites.  The skeet ranges are
not IRP sites.
                                      D.l-1

-------
           RESPONSES TO USEPA JULY 3,1997 COMMENTS (Continued)
Comment No. 5:
Response:
Comment No. 6:
Response:
Comment No. 7:
Response:
OT-69 should be cited that it has been transferred to OU 2.  A
very brief explanation should outline why it was transferred.

Site OT-69 is currently an OU 3 site. A sentence has been added to
Section 1.0 clarifying that the TCE in the vicinity of FT-20 is now part
ofOU2.

Landfill  sites (left in  place) should show the  planned deed
restrictions and/or land use.

The text has been modified where  appropriate to provide additional
detail regarding deed and land use restrictions.  See responses to the
DTSC's (Ron  Okuda's) comments.  Actual restrictions  will not  be
written until how the land transfer will occur is known.

The  pesticide dieldrin  agreements  for continuous  monitoring
requirement,  additional investigation (if needed), and related
contingent remedy discussed at the June 30, 1997 meeting should
be cited in the ROD.

As agreed during the  RPM  Meeting  on September 17, 1997, the
dieldrin that has been detected in wells in the eastern portion of the
base (in the vicinity of LF-39) are not currently considered part of OU
3; therefore, it  is not presented in this ROD. Text has been added to
Section 2.1.1 (Description of Operable Units) to state that the dieldrin
detected in wells in the eastern portion of the base will be addressed as
part of another OU.
                                       D.l-2

-------
 RESPONSES TO DEPARTMENT OF TOXIC SUBSTANCES CONTROL COMMENTS
                          DATED JUNE 27,1997 ON THE
          DRAFT RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                    GEORGE AIR FORCE BASE, CALIFORNIA
RON QKUDA'S COMMENTS

Comment No. 1:       Section 2.5.2.2, Alternative 2:  Institutional Controls Pages 2-24
                      and 2-25. This section in part states:

                      "Alternative 2 includes access and land use restrictions, surface
                      restoration, groundwater monitoring, and the 5-year site review.

                      Access  restrictions  will involve the  installation of 8-foot-high
                      chain-link fences with barbed wire and/or posting of warning signs
                      posted along the perimeter of the site. The locations of the fences
                      at each landfill would be determined as part of the design.

                      The implementation of land use restrictions at the OU 3 landfill
                      sites will depend highly on the disposal and reuse plans for the
                      GAFB property. There should be agreement between the USAF.
                      future owners of the property, and the concerned  regulatory
                      acencles regarding the types of land use that may be restricted on
                      site-bv-site. parcel-bv-parcel basis.

                      Surface restoration will involve..."

                      The land use restrictions  are a  part of the remedy and  are
                      necessary to assure the protectiveness of the remedy. The future
                      owners of the property should not have the ability to  negotiate the
                      restrictions. The human health risk assessment was conducted to
                      determine the risks associated with a future commercial/industrial
                      use scenario.   To protect  human health, land  use restrictions
                      should be recorded prohibiting residential uses.

                      I recommend that the above underlined sentences be revised as
                      follows:

                      "The implementation of land use restrictions at the OU 3 landfill
                     sites will assure the protectiveness of the remedy and human health.
                     Deed restrictions  will be recorded to restrict use of the sites for the
                     following purposes: (a) A residence, including any mobile home or
                     factory built housing, constructed or installed for use as permanently


                                     D.2-1

-------
              RESPONSES TO DTSC JUNE 27, 1997 COMMENTS (Continued)


                         occupied residential human habitation, (b)A long-term care hospital
                        for humans, (c) A traditional public or private school for persons
                         under 21 years of age, (d) A day care center. In addition, the deed

                        andfe^g."   diStUrbanCe °f the *""&« fOV"> ^surface soils


                        If the landfill is located over the contamination plume, the ROD
                                                        againsl Pu™Pin^nJection of
                        If the BCT is aware of other restrictions that would be necessary
                        to assure the protectiveness to human health and the environment,
                        those restrictions should also be discussed/disclosed in ROD.

                        There is a possibility that the remedy is not compatible with the
                        future reuse plan.  If this is so, and the BCT does not (or cannot)
                        change the remedy  to accommodate the reuse plan,  the ROD
                        should provide a clear description of the constraints  (land  use
                        restrictions) that the  Local Redevelopment Authority will have to
                        comply with in the future.
                       A^'^**1"!11*8" that *' Air Foree- *« Local Redevelopment
                       Authority and the regulatory agencies can negotiate would be a
                       protocol the future landowner or the Air Force will follow to seek
                       ™ "^   m ** restrictions> or h«ve the restrictions removed.
                       The deed can have a section specifying that the future landowner
                       can petition the UA EPA or other regulatory agencies based on
                       revised/new data (he., data has demonstrated that bioremediation
                       has reduced the concentration of the COPCs to a level that would
                       allow residential development).

Response:              The text has been  modified as requested with minor revision  for
                      consistency and clarity.

Comment No. 2:       Section 2.6.2, Description of TPH/VOC Site Alternatives, Pag,* 2-
                      ^^ onn 9_C^4
53 and
                      The  description of the land use restrictions in this section is
                      inadequate.   The discussion  of Alternatives  8 (Soil  Vapor
                      Extraction) and Alternative 9 (Bioventing) state that "land use and
                      access restrictions will be employed until remediation is confirmed
                      to be complete"; however, the specifics of the restrictions are not
                      discussed.  Will  the areas be fenced in a manner similar to the
                                     D.2-2

-------
 Response:
RESPONSES TO DTSC JUNE 27,1997 COMMENTS (Continued)


            landfills?  Will restrictions be imposed to prevent disturbance of
            the remedy and groundwater monitoring wells?  Will the future
            landowner be prohibited from  disturbing the soil?  This section
            needs further discussion of the restrictions.

            Alternative 11 (Oxygen Enhancement with ORC)  does mention
            land use restrictions to prohibit use  for domestic purposes.  In
            addition, I  would  recommend  that the ROD include something
            about the restrictions to prohibit disturbance of the remedy and
            monitoring wells.

            Sections 2.6.2 and  appropriate subsections have been  modified to
            address these issues as follows:
              •   A separate  paragraph has been added to Section 2.6.2.3 to
                  specify  the  nature  of  land use and access  restrictions  for
                  Alternative 8.
              •   A statement has been added to  Section 2.6.2.4 that the land
                  use and access restrictions for Alternative 9 would be the same
                  as Alternative 8.
              •   The change  requested for Alternative 11 (Section 2.6.2.6)  has
                  been made.
Comment No. 3:
Response:
           There are numerous sites in the Draft OU 3 ROD that  are
           proposed  for NFA where the health risks were evaluated for a
           commercial/industrial, exposure scenario.   If  the  sites are not
           protective enough for unrestricted uses (i.e., residential), land use
           restrictions should  be imposed at those sites.  This would mean
           that those sites are no longer eligible for a NFA decision.

           The OU 3 RI Report details the approved methodology used for the
           risk assessments performed for OU 3 sites. Table ES-4 of the final OU
           3 RI Report (Montgomery Watson,  1996a)  presents  the complete
           summary of the results of the human health risk assessment analysis.

           Potential    risk    assessment    exposure   scenarios    included:
           industrial/commercial,   trespasser/visitor,    construction    worker
           (potential  surface  soil exposure), construction  worker  (potential
           subsurface soil exposure), and future resident. The exposure scenarios
           evaluated  for a  particular site were  dependent  on  the expected
           exposure pathway and the proposed  land use as presented in the
           Management Action Plan  (MAP)  (USAF, 1993).  In most  cases,
           multiple  scenarios were evaluated for a particular site  including the
           future resident scenario if the site was in a parcel with the potential for
           residential use.
                                        D.2-3

-------
RESPONSES TO DTSC JUNE 27,1997 COMMENTS (Continued)


           To clarify this issue in the OU 3 ROD, the text that summarizes the
           risk assessment for each site requiring action has been revised to
           clearly present all risk assessment scenarios that were evaluated for
           that site and  reference  the MAP and OU  3  RI  Report  where
           aDDronriafe
appropriate
                        D.2-4

-------
   RESPONSES TO DEPARTMENT OF TOXIC SUBSTANCES CONTROL COMMENTS
                            DATED JULY 9,1997 ON THE
            DRAFT RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA
  GENERAL COMMENTS
  Comment No. 1:
 Response:
Comment No. 2:
Response:
 During the Remedial  Project Managers  (RPM) meeting in
 Walnut Creek where the remaining risk assessment issues were
 discussed, it was agreed that the Air Force would include in the
 Record of Decision, the  basis for expediting the accelerated
 actions was NOT  risk  based,  rather  it  was  for  reuse
 considerations.  The ROD must be absolutely clear on this issue
 and it need only state the agreements developed hi this process.

 The meeting referred to above was held to discuss human health risk
 assessment on October 1, 1996. This issue was discussed; however,
 in that context, it was also stated by the Air Force that the decisions
 to support the final remedy were based on the nine CERCLA criteria
 which  includes  overall  protection  of  human  health and  the
 environment (i.e.f risks). The outcome of that meeting was presented
 in minutes submitted to the RPMs October 7, 1996.  Subsequent to
 the October 1, 1996 meeting, the RI was approved as final and the
 FS was revised (via inserts) and approved as  final. The presentation
 of the  decisions  in  the  OU 3 ROD are consistent with  the
 presentation in the final OU 3 FS.

 In addition to the October 1, 1996 meeting, a ecological risk meeting
 was held on September 19,  1996. Please note that ecological risks
 are also considered in the determination  of the most appropriate
 remedy.

 This issue was again discussed during the August 14, 1997 RPM
 meeting regarding the preparation of the OU 3 Proposed Plan.  At
 that  time,  it was agreed  that  risk management  factors  were
 considered in  the decision whether to carry  a site through the FS
 process or to propose no further action.

 The deed restrictions, land use limitations and access restrictions
 must be further delineated.  Mr. Ronald Okuda, Environmental
Assessment and Reuse Specialist  has  provided comments to
bring the document up to par. Said comments are attached.

See responses to Ronald Okuda's comments.
                                      D.3-1

-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
  Comment No. 3:
 Response:
 Comment No. 4:
 Response:

 Comment No. 5:


 Response:
  This ROD must provide contingencies for the ongoing  field
  efforts in the event that the proposed remedies fail to perform as
  expected.   For example, if it is  found,  through verification
  sampling that the  Bioventing  activities  simply pushed the
  contaminants away  from their original locations,  it  will be
  necessary to chase the contaminants, define their extent and
  implement an  agreed  to remedy.   We  hope this will not be
  necessary but it is necessary to consider the possibilities.

  Text has been added to appropriate places in the document to clarify
  that the effectiveness of the remedies are being assessed as part of
  the ongoing O&M and long-term monitoring. Assessment of system
  effectiveness will be the focus of the 5-year site review.

  This ROD mentions OT-69 will be addressed as part of OU 2.
  The situation has changed and as  of May 6, 1997 during the
  RPM meeting it was decided to include OT-69 groundwater
 plumes with OU 3. Please revise the text, figures and tables as
 necessary.

 OT-69 has been added to the text as an OU 3 site.

 The ecological risk management agreements which were agreed
 to are missing and should be included in the ROD.

 The primary agreement  for ecological risk management was the
 presentation  of an ecological monitoring plan.  This plan  is now
 summarized  in Section 2.9. hi addition, this section documents the
 actions that have occurred to date, including the hot spot removal
 that was performed prior to construction of the soil cover at Site DP-
 04 to reduce potential risk to burrowing animals.
SPECIFIC COMMENTS
Comment No. 1:
Response:

Comment No. 2:
Pg. 1-1, Para. 3. Site OT-69 groundwater is described as having
been  relegated to  OU 2 to  be addressed.  This is no longer
accurate.  It will stay with OU 3 and must be addressed in the
ROD See General Comment No, 4.

See response to General Comment 4.

Pg. 1-2, Para. 3. The last part of the first sentence, "and are cost
effective." should be deleted. The Air Force could have saved
                                   D.3-2

-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
 Response:
 Comment No. 3:
Response:

Comment No. 4:
Response:


Comment No. 5:


Response:
 considerable amounts of  time and  money had  they pursed
 additional Remedial Investigations as requested by regulators.
 By expediting the accelerated actions in lieu of sampling, the Air
 Force may have committed themselves to post closure activities
 such  as long term monitoring at the landfill sites.  Which are
 rather costly. This part of the sentence must be deleted.

 All accelerated actions  were performed  with  the  consent and
 participation of the regulatory agencies through the RPM meetings,
 document reviews, remedial action work plans, etc. In addition, all
 sampling met or exceeded that presented in the final OU 3 Work
 Plan Addendum (JMM, 1992). The sites that were carried into the
 FS process were agreed upon  in the final OU 3 FS Report.  In the FS,
 cost analysis was performed  to  satisfy that  aspect of the nine
 CERCLA  criteria and  was  considered in alternative  selection.
 Therefore, in that context, the most cost effective option for the site
 that required action was selected.

 Pg. 1-3, Para. 3. Please replace the name and title of the DTSC
 person who will sign this document. The proper name and title
 is:

 John E. Scandura, Chief
 Southern California Operations
 Office of Military Facilities
 Department of Toxic Substances Control

 The text has been modified accordingly.

 Pg. 2-1, Para 2. The last sentence implies that Figure  6 has all
 the sites associated with all three Operable Units. This must be
 revised.  In addition, it seems that the sites included on Figure 6
 are only those  sites which  are action recommended.   Please
 include sites LF-35 and OT-69 (groundwater) as well as any sites
 which  have actions recommended.

 The text now refers to Figure 2 which presents all three Operable
 Units.  Sites LF-35 and OT-69 have been added to Figure 6.

 Pg. 2-2, Para  1.   See previous comments  on site OT-69
groundwater. Revise the last sentence accordingly.
The text has been modified accordingly.
the text as an OU 3 site.
OT-69 has been added to
                                    D.3-3

-------
              RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
  Comment No. 6:
  Response:


  Comment No. 7:



 Response:


 Comment No. 8:
 Response:
Comment No. 9:
Response:
  Pg. 2-7, Para 2.   The last sentence  which discusses  OU 1
  discharge of effluent into  the  arroyo  is  no longer accurate.
  Please re-iterate the existing conditions for OU 1 discharge as of
  the June 4, 1997  RPM meeting and the July 1,  1997 RPM
  meeting. The final OU 1 discharge will be in agreement with the
  ROD  or the Team will have to go thru a ROD modification
  procedure.

  The text has been revised to state  that the  arroyo intermittently
  receives discharge from the OU 1 extraction and treatment system.

  Pg. 2-9, Para 2. The DTSC recommends  that the last sentence in
  paragraph 2 and paragraph 3 be deleted.  The statements are
  speculative and can either be investigated or left out of the ROD.

  The first sentence in question has been deleted. The second sentence
  has been revised.

  Pg. 2-11, Para 3.  Please  modify the last sentence  as follows:
  replace "these investigations  to" with "those investigations in an
 effort to-.*'  Basically the  Air Force refused to do additional
 characterization. The regulators did not force the issue since the
 work which was performed satisfied the minimum requirements.
 Never the less, the proposed revisions is  more appropriate and
 must be included hi this ROD.

 The sentence is introductory and refers to basewide activities. To
 clarify,  the text has been revised to state "the USAF has performed
 investigations in an effort to..." All OU 3 sampling met or exceeded
 that in the final OU 3 Work Plan Addendum  (JMM, 1992).

 Pg. 2-13,  Para. 6.  The tense for this paragraph is incorrect, it
 will take  place but has not taken place.  In addition the dates
 have subsequently changed and must be updated. Currently the
 public meeting is scheduled for August 14,1997 and the 30 day
 public comment period should start around July/August  time
 frame. This section must be updated.

 This version of the ROD is being submitted after the public meeting
 and public comment period have occurred. The text has been revised
to state that the public meeting was held on October 8, 1997 and the
public comment period ended on October 22, 1997.  Past tense is
now appropriate.
                                   D.3-4

-------
            RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
Comment No. 10:



Response:

Comment No. 11:
Response:


Comment No. 12:
Response:
Comment No. 13:
Pg. 2-14, Para. 3.  See prior comments regarding site OT-69.
This site will not be addressed in the OU 2 ROD as stated in the
document This must be updated.

See responses to prior comments regarding site OT-69.

Pg. 2-14, Para. 5.  The use of land use restrictions for LF-35 in
and of  itself  is  insufficient.    Deed  restrictions,  land  use
restrictions and access restrictions must be specified for all sites
which  have potential hazardous wastes and substances left in
place.  See Ronald Okuda's comments.
The text has  been modified to be more clear.
Ronald Okuda's comments.
See responses to
Pg. 2-16, Para. 1.   The last sentence, in  its present form is
misleading.   Actually, die modeling, shows that there is no
potential for contaminant leaching in to the groundwater. The
model has certain assumptions which may or may not correlate
to the actual amount of contamination present   In practical
terms, the post closure  landfill requirements  for monitoring
apply at these landfills due to the high uncertainties associated
with the data. This is due to the low quantity of analytical data
available. In addition the remedy is to leave  wastes in place
which requires deed restrictions, access limitations and land use
restrictions in perpetuity.  This sentence and  all such sentences
may be deleted or replaced with language which incorporates the
above comments.

The  sentence  referenced  (and  other similar  sentences  in  the
document) have  been modified  to  state that  "modeling results
indicate that  there is no potential  for  contaminant  leaching  to
groundwater."

Pg. 2-16, Para. 3. The first and second sentences contradict each
other.   Is there an  ecological risk issue or  not  The DTSC
position  is that there is since the desert  tortoise can  easily
burrow below the 12 to 18 inches of cover placed on the landfills.
The Air Force agreed to implement risk management measures
to limit the access and future use of all the landfills.  See the Risk
Assessment meeting  in Walnut Creek in December 1996. This
agreement  was  reached  in   lieu  of  additional  Remedial
                                    D.3-5

-------
              RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)


                           Investigations which may have been performed. The agreements
                           from the meeting must be included in the ROD.

   Response:                The text has been revised to clarify the distinction between  the
                           qualitative  ecological  benchmark  screening and  the  subsequent
                           quantitative bioaccumulative food chain modeling.

                           At a meeting at the USEPA offices in San Francisco, California on
                           December 11,  1995, it  was agreed that food chain modeling  for
                           bioaccumulative compounds would be  performed  to address any
                          perceived insufficiency  of  data.   The  text now  reads  that the
                          localized presence of PAHs (not included in the bioaccumulative
                          food chain modeling) may be a potential risk to ecological receptors.
                          However, the food chain modeling performed for bioaccumulative
                          compounds at DP-03 did not suggest a risk to vegetation or wildlife.
                          This information is discussed in detail in the final OU 3 RI Report
                          (see Table ES-5 for a summary).   In addition, these results  were
                          presented at the ecological risk assessment meeting in Walnut Creek
                          on September 19, 1996. It is assumed that this is the meeting which
                          is referenced above.

                          A discussion  of the ecological monitoring plan is now presented in
                          Section 2.9 of the OU 3 ROD.
 Comment No. 14:
 Response:
Comment No. 15:
Response:
 Pg. 2-17, Para. 1.  The last sentence needs a little clarification,
 add "within 100 years." or delete the phrase "... no potential"
 Once again due to the low confidence in the data sets used or
 high uncertainties, ALL these comments must  be revised or
 deleted.

 To clarify, this statement, and other similar statements for other sites.
 have been revised to read "within 100 years."  All prior comments to
 the OU 3 RWS related to perceived concerns regarding the agency's
 low confidence in data sets and uncertainties  were addressed in the
 final  OU  3 RI/FS Reports.   The text referenced  is primarily a
 summary of discussions presented in the OU 3 RI  and/or FS (for
 example, the specific text referenced is presented on page 3-7 of the
 final OU 3 FS [Montgomery Watson, 1997aJ).

Pg. 2-18, Para. 1. Comment 2-17,1 applies at the end of the first
paragraph.

See response to Specific Comment 14. See also page 3-3 of the final
OU 3 FS (Montgomery Watson, 1997a).
                                    D.3-6

-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
 Comment No. 16:
 Response:
Comment No. 17:
Response:
Comment No. 18:

Response:


Comment No. 19:
 Pg. 2-18, Para. 2.  Why was the highest estimated excess cancer
 risk estimated for the future risk scenario at this  landfill?
 Landfills which are not clean closed should  be evaluated for
 industrial/commercial scenarios like the other landfills.

 To clarify this issue, the text that summarizes the risk assessment for
 each site requiring action has been revised to clearly present all risk
 assessment scenarios that were evaluated for that site.

 For example, this site (LF-12) was evaluated for five scenarios (i.e.,
 industrial/commercial,  trespasser/visitor,  etc.).    The  exposure
 scenarios  evaluated for a particular  site were dependent on the
 expected exposure pathway and the proposed land use as presented
 in the Management Action Plan  (MAP) (USAF, 1993).  The  text
 referenced above is presenting the highest risk observed because it is
 the risk that would drive risk management decisions. The final OU 3
 RI (Montgomery  Watson, 1996a) presents the complete results of
 this analysis and discusses the approved methodology.

 Pg. 2-18, Para. 4. The paragraph implies that the remedies were
 selected based on risk. This is not the  case and the paragraph
 must be re-written or deleted. See general comment No. 1. This
 section must be revised accordingly.

 See response to General Comment 1.  Risk was part of, but not the
 only, determining factor for carrying a site through the FS process
 (as stated in the text) for many sites. Through the FS process, risk
 management decisions were a consideration for the most appropriate
 remedy as part of the nine CERCLA criteria.

 Pg. 2-19, Para. 2. Comment 2-17,1 also applies here.

 See response to Specific Comment 14.  See also page 3-4 of the final
 OU 3 FS (Montgomery Watson, 1997a).

 Pg. 2-19, Para. 3.  Why does the Air Force evaluate risk  for
 industrial/commercial  in LF-14 and for the future  resident
scenario in LF-12?   Landfills are landfills  and should  be
evaluated to  one standard, commercial/industrial, based  on
current EPA guidance which addresses evaluation for future use
under the  current  use scenario.  The  risk numbers must be
comparable, i.e.,  address the landfills In  this ROD  under the
industrial/commercial scenario for human health.
                                    D.3-7

-------
              RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
   Response:

   Comment No. 20:
  Response:
  Comment No. 21:
 Response:



 Comment No. 22:


 Response:


 Comment No. 23:
Response:
   See response to Specific Comment 16.

   Pg. 2-20, Para. 2. This paragraph is in need of being re-written.
   The Base Closure Team (BCT) agreed not to stop work on the
   accelerated actions  with the condition that the work would not
   be justified under CERCLA by risk assessment methodologies.
   The Air Force  agreed.  This paragraph, and other similar
   paragraphs,   can    quantify   the    human   risk    for
   commercial/industrial scenarios with its associated confidence
   levels. However,  the basis for proceeding with the work was the
  Air Force's prerogative to expedite reuse.  The DTSC wouJd like
  to see these points stipulated clearly in the ROD.

  See responses to  General Comment 1 and  Specific Comment  17
      *0 P3gC 3"5 °f ** final  °U  3 FS  
-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
  Comment No. 24:
 Response:
 Comment No. 25:



 Response:

 Comment No. 26:
Response:

Comment No. 27:
Response:
  Pg. 2-24, Para. 7. As regards to access restriction, see previous
  comments and Ronald Okuda's comments.  The last sentence
  has an inappropriate tense, the location of the fences do not have
  to be determined, they are in place. Do not be afraid to state the
  facts, whatever they are.

  See responses to Ronald Okuda's comments.

  The tense is appropriate as written. This section (2.5.2) presents the
  alternatives that were evaluated for all landfill sites, not necessarily
  the actions that have occurred (i.e., it is pah of the summary of the
  FS  process and discusses what  would be  done  if a particular
  alternative were selected for a particular site). Section 2.9 has  been
  added to the ROD that details the actions that have occurred to date.

 Pg. 2-24, Para. 8. See Ronald Okuda's comments. Specify  who
 the concerned regulatory agencies are which will determine the
 types of land use that may be restricted on the next page.

 See responses to Ronald Okuda's comments.

 Pg. 2-27, Para. 5,6.   The DTSC would prefer  to see the term
 "reduced"  in  place  of "practically eliminate" for these  two
 paragraphs. Rodents will burrow into the cover, as well as the
 desert tortoise if the fences are not maintained.  There needs to
 be details included  in the ROD which addresses the need for
 ecological monitoring, post closure land fill cover requirements
 and access control in the future.

 The text has been modified accordingly.

 Pg. 2-30,  Para. 6. Risks have been effectively reduced to zero?
 This is stretching risk assessment too far.  Risk reduction  has
 been accomplished to some degree  and this amount of  risk
 reduction can be quantified.   The quantified  level of  risk
 reduction can replace "zero."

 The  statement regarding reduction of risks to zero has been  revised
 to clarify  that  potential risk is minimized.  At a  risk assessment
 meeting between the RPMs on September  19, 1996 the issue of
recalculation of risk was a point of some discussion (see meeting
minutes). Subsequent to that time, all agency comments to the OU 3
RI and FS report were  addressed and  it was accepted that  a post-
                                    D.3-9

-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
 Comment No. 28:
Response:
  Comment No. 29:


  Response:
 Comment No. 30:


 Response:

 Comment No. 31:

 Response:

 Comment No. 32:

Response:

Comment No. 33:
                                 T           rfsk assessmen' wou'd not be prepared for
                         the sites. Therefore, quantitative risk numbers arc not available.
                                               lt k P°SSible that "* state
                                                     Air  ForCC  done
                                                     quantlfy  *«  **»•    There is a
                                     that the Air Force wouid have done the accelerated
                           actions  in spite of the low levels of risk for reuse
                           However the DTSC must consider and where appropria
                           accept the no action alternative.  Alternatives 1  a£d  2
                           therefore be revised accordingly.


                           As discussed  at the August 14, RPM meeting, the agencies did not
                           histoncally accept no action (Alternatives 1) for the

                           rwSen £hTtiVCn2 W "** ^^ f°r Site
                           as written is histoncally accurate.
                       Pg. 2-36, Para. 4.  Please delete line 3.  Alternative 4 is less
                       expensive but NOT equally effective in satisfying the RAO's.


                       Alternative 5 differs from Alternative 4 in that is has the addition of
                       a synthetic Imer. The purpose of the liner is to further protect a^nsf

                       sC r±T  I^UOn'  .AIthOUgh at first «lance AltoLlve /may
                       ST TnTlSririfr A/terna!ive 4' the dat^ does not support
                       Sal  35 ^ T? eV^Uati°n PCrf°nned aBd Prcsented ^
                       5Sfi^.i   •!       ^  that  ^  synthetic  ]iner W°"W not
                       significantly aid in meeting this RAO.


                       Pg. 2-37, Para. 2. Why is the resident scenario used for LF-12?
                      See previous comments on this issue.

                      See response to Specific Comment 16.


                      Pg. 2-38, Para. 5. Same comment as 2-37, 2 for the SEDA.

                      See response to Specific Comment 16.

                      Pg. 2-41, 3rd bullet Delete this bullet


                      See response to Specific Comment 2.
                                                                    levek    n
                     and the evaluation criteria to which it was compared.  The term
                     "Mgnificantly lower than the evaluation" is nebulous
                                D.3-10

-------
             RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
  Response:
 Comment No. 34:
 Response:



 Comment No. 35:



 Response:

 Comment No. 36:


 Response:
Comment No. 37:
  The text has been revised to summarize the evaluation criteria in
  Section 2.6.1. The term "significantly" has been removed from the
  sentence in question. The text in this paragraph has been revised to
  clarify the point that the evaluation criteria were exceeded in one of
  11 borings.

  Pg. 2-48, Para. 3.  The DTSC does not consider the Air Force
  contractors, M&E, the correct entity to conclude that no further
  action was warranted.  Normally, the potentially responsible
  party proposes recommendations, such as no further action and
  the base closure team can concur unless we disagree amongst the
  BCT.  In such cases the US E.P.A. concludes on the CERCLA
  issues  and the Regional Board or DTSC concludes on  state
  issues.

 The text in this  sentence, and any similar sentences, have been
 revised to give the more appropriate explanation that the conclusions
 were drawn, reported, and agreed to by the RPMs.

 Pg. 2-50, Para. 4.  Figure 10 has a typographical  error which
 shows the cleanup goal for soils 20 feet above the groundwater at
 125ug/kg. This must be corrected.

 The figure has been modified accordingly.

 Pg. 2-52, Para.  6.   Which additional monitoring  wells  are
 necessary to satisfy which specific monitoring components?

 The monitoring wells referred to are hypothetical and  therefore do
 not have names. The text is summarizing the FS process (alternative
 development)  and  is stating  that  additional  monitoring  well
 installation might be required.  For example, if an alternative with a
 groundwater monitoring  component was selected  for  a site were
 sufficient downgradient monitoring wells were not available.

 Pg. 2-53, Para. 7.  Bioventing is an acceptable cleanup method.
 However, it has been proven by confirmation sampling events
that this process simply moves certain contaminants from area X
to areas around X.  We hope this is not the case  here  but a
contingency should be included where the Air Force commits to
remedying such a possibility.
                                   D.3-11

-------
              RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)
  Response:
  Comment No. 38:
 Response:
 Comment No. 39:



 Response:

 Comment No. 40:



 Response:


 Comment No. 41:



Response:

Comment No. 42:
Response:
  Text has been added to appropriate places in the document to clarify
  that the effectiveness of the remedies are being assessed as part of
  the ongoing O&M and long-term monitoring.  Assessment of system
  effectiveness  will  be the  focus  of  the  5-year  site  review.
  Confirmation sampling (soil or vapor) will be collected to confirm
  the remedies have been completed prior to site closure.

  Pg. 2-(55-61).  The use of alternative  6,7,8 and 9 for soil and
  alternatives 10 and  11 for groundwater makes it difficult to
  compare,  why not, rather, use the name of the process?  This
  will make it much clearer and easier to read.

  Each alternative is defined at  first use.   In addition, a table is
  presented cross referencing the number and name of each alternative
  with the CERCLA  criteria as follows:  Table 3 for landfill  sites,
 Table 14 for TPH/VOC sites, and Table 22 for Site OT-69.

 Pg. 2-(62-67).  The DTSCs general  comment No. 1 applies
 throughout this section.   The risk  must be de-emphasized
 throughout the ROD as agreed to by the BCT.

 See response to General Comment 1.

 Pg. 2-69, Para.  2.  There are very few technologies which can
 completely remove and treat contaminated soils.  Lets replace
 completely with adequately.

 The text has been modified to state that the remedies "will remove
 and treat contaminants in soils to below acceptable levels."

 Pg. 2-69, Para. 5.  In line 4 lets replace the  term remedial  with
 accelerated actions since  the work did not take place via an
 approved ROD.

 The text has been modified accordingly.

 Pg. 3-1, Para. 2.  The date has slipped form July 15, 1997  to a
 proposed date of August 14, 1997 for the public meeting.  Lets
 keep the tense correct on  these documents as they are being
revised.

See response to Specific Comment 9.
                                   D.3-12

-------
            RESPONSES TO DTSC JULY 9,1997 COMMENTS (Continued)


TableS                  T"6 Air F°rce should use the actual dollar amounts spent for the
                        actions taken thus far where the information is available.  The
                        tables must be updated.

Response:                Table 25 presents a summary of current present work cost estimates
                        as well as actual remedial action costs for the accelerated actions
                        performed for OU 3 sites.  The text has been modified to clarify this
                        point.
                                 D.3-13

-------

-------
    RESPONSES TO LAHONTAN REGIONAL WATER QUALITY CONTROL BOARD
                     COMMENTS DATED JULY 11,1997 ON THE
            DRAFT RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA

  GENERAL
  Comment No. 1:
  Response:

  Comment No. 2:
 Response:


 Comment No. 3:
Response:


Comment No. 4:
  Board staff comments on the draft Proposed Plan are dated May
  5,1997. Enclosed with Board staff comments was Regional Board
  Resolution 6-97-62 authorizing the Executive Officer to sign the
  OU 3 ROD provided there are not significant changes and that the
  following comments are satisfactorily addressed.

  Comment noted.

  The ROD must indicate that the Regional Board has agreed to the
  natural attenuation alternative for the Site OT-69 chlorinated
  solvent plumes provided an active contingent remedy is specified
  in the ROD and will be implemented.  This contingency will be
  implemented if  the  Regional Board  deems that  the  natural
  attenuation remedy is not restoring water quality objectives in a
  timely manner.

  Text presenting this information has been added to Sections 2738
  and 2.9.2.

  The cover letter to the draft ROD indicates that Site OT-69 has
 not been included in the  document because the remedial project
 managers (RPMs) were still discussing whether to include the site
 or not in the OU 3 ROD. The RPMs met on Tuesday, May 6  1997
 and decided that the Site OT-69 plumes investigated by IT Corp
 will be part of the OU 3 ROD.

 The five plumes investigated by  IT as Site OT-69 have been included
 in the OU 3 ROD.

 The RPMs also decided to consider the trichloroethylene 
-------
           RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)
 Response:
 Comment No. 5:
Response:
Comment No. 6:



Response:

Comment No. 7:
  Board staff  request  (May S, 1997) for a  time schedule for
  conducting additional investigations at this site.

  The text has been revised to clarify that Site FT-20 (soil) is an OU 3
  site for which No Further  Action is recommended, and that "final
  decisions regarding potential actions at  the Site FT-20 (groundwater)
  will be determined in the OU 2 ROD."

  Closure activities at the landfill sites is now complete as indicated
  in the draft ROD and  long-term post closure maintenance shall
  continue.  Active soil remediation is  in progress  at Sites OT-51,
  WP-17 and FT-19 as indicated  in the draft ROD.  The ROD
 should reflect actual site closure and remediation costs as provided
 by Montgomery Watson by letter dated April 22, 1997. During
 the May  6, 1997 RPM meeting, Montgomery Watson  indicated
 that the table attached to the April 22,1997 letter did not include
 monitoring costs. The long term costs should include collection of
 groundwater monitoring data for an assumed period of time.  The
 cost estimate tables should include all costs (to date and projected)
 and state assumptions.

 The table referred to was included in the Draft OU 3 ROD as Table 22.
 During the May 6, 1997 RPM meeting. Montgomery Watson stated
 that the table column entitled "Current Estimated Annual O&M Cost"
 did  not include monitoring.  However,  it was  also  stated  that
 monitoring costs are included in the present worth cost (i.e., the total
 costs include monitoring  as written). This table (now Table 25) has
 been revised to clarify that is presents the current estimates for sites
 where  accelerated  actions  have occurred to  date  using  actual
 construction costs.  In addition, assumptions have been modified for
 clarification.

 Table  13 shows Quality Goals for TPH/VOC  Groundwater Site
 (OT-51). Changes should be made to this table. Comments 7-10,
 below, pertain to this table.

 See response to comments 7 through 10.

 The numerical standard for odor (adopted secondary MCL) is 3
odor units and must be added to the table. Please see Table 64449-
A, Title 22, Cal. Code of Regulations.  References should  be made
to agreements  made at the June 30, 1997 Applicable or Relevant
and  Appropriate  Requirements  negotiations,  meeting  with
attorneys present, regarding the applicability of this criteria.  In
                                      D.4-2

-------
  Response:
 Comment No. 8:
 Response:


 Comment No. 9:
Response:
Comment No. 10:
            RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)
  other words, the State and Air Force would disagree regarding the
  applicability  of the 3 odor  unit secondary  drinking water
  standard, however the Air Force will clean up to that standard.

  The header of the column titled 'Taste and Odor Threshold" in the
  Draft ROD has  been revised to "Suggested Concentration to Meet
  Secondary MCL of 3 Odor Units."

  The "agree to disagree" language established for OU 2 during the June
  30, 1997 specifically regarding the 3 odor units has been added where
  appropriate to Table 15 (ARARs for TPH/VOC sites).

  A footnote should  be  added  to the  table  clarifying that  the
  proposed federal secondary  maximum contaminant  levels  are
  constituent specific and may be  used to represent the 3 odor units
  for petroleum hydrocarbons, however when  used independently,
  they may not accurately reflect odor of a complex mixture. The
  proposed federal secondary standards  are not  promulgated,
  however the 3 odor unit secondary standard is promulgated.

 See response to Comment  13. The requested language has been added
 to Table 15.

 Napthalene must be added to  the table.  A  value  of  20 ug/I is
 recommended as 'To-Be-Considered" and is the numerical water
 quality objective unless an alternate  standard acceptable  to the
 Regional Board is proposed.  This is the USEPA recommended
 health advisory for toxicity other than cancer.

 Napthalene is not a COPC for OU  3.  Note that IT Corp. has sampled
 for napthalene in and around the OU 2 plume and the results have been
 nondetect (see "OU 2, Routine Plume Monitoring Informal Report,
 September 1997," page 9).  The  use of napthalene as a surrogate
 COPC is not an appropriate precedent to set in this ROD.  Note that
 text has been added to the ROD to indicate sampling frequency and
 analyte  selection for  the  long term monitoring program may  be
 modified as the program progresses (see response to Comment 23).

 Dieldrin must be added to the table.  A value of 0.0022 ug/I is
 recommended as "To-Be-Considered" and is the  numerical water
 quality objective unless an alternate standard acceptable to the
 Regional Board is proposed. This is the Cal-EPA cancer potency
factor as a water quality criteria.
                                      D.4-3

-------
           RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)
 Response:
 Comment No. 11:
Response:
Comment No. 12:
Response:
Comment No. 13:
 As agreed during the RPM  Meeting on September  17,  1997,  the
 dieldrin that has been detected in wells in the eastern portion of the
 base are not currently considered part of OU 3; therefore, dieldrin has
 not been added to the table.  Text has been added to Section 2.1.1
 (Description of Operable Units) to state that the dieldrin detected in
 wells in the eastern portion of the base is not considered part of OU 3
 and will be addressed as part of another OU.

 The ROD must indicate that collection of confirmation samples at
 Sites WP-17, OT-51, and FT-19 is  required to verify that the soil
 cleanup levels indicated in Figures 9 and 10 are attained. Please
 correct the 20 foot above ground  water cleanup level shown on
 figure 10 from 125 ug/kg to the correct numerical value.

 Text has been added to Section 2.6.2 to state that "prior to closure of a
 TPH/VOC  site   for  which  a  remedy  has  been  implemented,
 confirmation   samples   (soil   and/or  vapor  to  estimate   soil
 concentrations) would be collected as necessary to demonstrate that
 soil cleanup levels presented on Figure 9 are achieved." Note that this
 section precedes the description of alternatives for the TPH/VOC sites.
 The description of alternatives also indicates that confirmation samples
 (soil and/or vapor) will be collected to confirm that remediation goals
 have been achieved.

 Figure 10 has been revised to state the correct value of 12.5 ug/kg.

 The ROD must indicate that the active remediation systems (soil
 vapor extraction and  bioventing) will  operate so long as the
 systems continue contaminant mass reduction in a manner that is
 technically and economically feasible.

 Text has been  added to Section 2.6.2 to state that based on the
 remediation goals, a remedy would be implemented and operated until
 the mass of contaminants remaining was such that no impact to
 groundwater was anticipated.

 Recently Board staff sent the Air  Force a letter dated June 27,
 1997  requesting a Preliminary   Assessment/Site Investigation
 (PA/SI) for the occurrence of the pesticide dieldrin in wells located
 adjacent to Landfill Site LF-39.  Dieldrin is present at levels of
 approximately 0.12 ug/l. The draft ROD indicates that No Further
Action is appropriate based on the  Air Force contention that Site
LF-39 was  never a  landfill.  This  request for additional site
information is not made at the "llth hour** as indicated by the Air
Force  during the June 30,  1997  meeting.   Board  staff have
                                        D.4-4

-------
 Response:
RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)


            previously indicated  that  the  western portion of the  landfill
            beneath  base  housing was not properly investigated, that No
            Further Action was not appropriate, and  that dieldrin  was of
            concern (May 2,1995 Board staff comments on the OU 3 Remedial
            Investigation/Feasibility   Study).    The ROD  must  provide
            supporting rationale for the recommendations made. As agreed to
            during the June 30,1997 meeting, the ROD may include a remedy
            for Site LF-39 that indicates long term monitoring for pesticides
            will be conducted in the affected wells. The  ROD should indicate
            that a contingent remedy will be evaluated if: 1) water production
            causes plume movement or 2) if the PA/SI results indicate a need.
            The PA/SI may be conducted outside of OU  3, allowing the OU 3
            ROD  to be completed and decisions related  to the dieldrin in
            groundwater to be made outside of OU 3.

            LF-39  is proposed for no further action (NFA)  based on site-specific
            data. Because dieldrin is located in wells upgradient of LF-39, this site
            is not considered a source. Therefore it is appropriate that LF-39 be an
            NFA site because dieldrin was not found in site soils.

           The ROD does not make a statement  regarding LF-39 never being a
           landfill. All comments to the  OU 3 RI/FS Reports were addressed in
           writing and are presented in appropriate appendices to those reports.
           These comments were provided to the RPMs with the final submittal.

           As  agreed during the RPM Meeting on September 17, 1997, the
           dieldrin that has been detected in wells in the eastern portion  of the
           base (in the vicinity of LF-39) are not currently considered part of OU
           3; therefore, it is not presented in this ROD. However, text has been
           added to Section 2.1.1  (Description of Operable Units) to clarify this
           point
 Comment No. 14:
Response:
Comment No. 15:
           The  ROD  must indicate that  the  abandoned  well  casing
           downgradient  of Site OT-51  will  be  properly  sealed  and
           decommissioned. Please refer to Board staff memorandum dated
           February 2, 1995 with information provided to the  Air Force
           regarding appropriate decommissioning methods.

           Section 2.6.4.2 has been revised to state that the preferred alternative
           for OT-51  includes the decommissioning  of the abandoned well
           downgradient of the site.

          The ROD must clarify a number of issues for the Site OT-51 JP-4
          plume comments, 16 to 19 pertain to this issue.
                                      D.4-5

-------
            RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)
  Response:

  Comment No. 16:
  Response:


  Comment No. 17:
 Response:
 Comment No. 18:
Response:
Comment No. 19:
  See response to Comments 16 through 19.

  ORC is proposed as a contingent remedy for the Site OT-S1 JP-4
  ground water plume.   Based on information in the Basewide
  Groundwater Monitoring Report for the February 1997 Sampling
  Event,  dated June 1997, prepared by Montgomery Watson, long
  term monitoring of the JP-4 plume is appropriate.

  Section 2.6.4.2 states that the preferred alternative for OT-51 includes
  long term monitoring.

  The criteria that will be used to determine when the contingent
  remedy will be implemented must be stated.  Board staff have
  previously indicated  that  natural  attenuation is  acceptable  if
  plume stability is demonstrated and  concentration  reductions
  occur as expected (May  5, 1997 Board staff memorandum with
  comments on  the draft OU 3 Proposed Plan  and Staff Report
  dated April 1997).

  As agreed  during the conference call between the RWQCB, USAF.
  DISC, and Montgomery Watson on October 14,  1997, the text  has
 been modified where appropriate to state that the implementation of
 the oxygen releasing chemicals would be contingent on the continued
 reductions of COPCs in groundwater in a reasonable time frame. Data
 collected as part of the basewide long-term monitoring program have
 shown that the  plume is characterized and concentrations are  being
 reduced.

 The  expected  duration  to attain  cleanup to water quality
 objectives must be stated.  This duration calculation must include
 all assumptions used.
                                                             s
 Based on  best  engineering  judgment, it is  anticipated  that the
 groundwater will be remediated to within acceptable levels within 5
 years.  The is primarily based on the fact that the source is being
 removed  by installation of  a  bioventing  system and  the recent
 basewide groundwater  monitoring data indicating that  levels  of
 COPCs are decreasing (Montgomery Watson, 1996 d, e, f and 1997 d,
 e, f)-   The text  of the ROD has been revised to cite this recent
 groundwater monitoring data.

 Currently there are insufficient groundwater monitoring points
downgradient   of  the  plume.     Additional  downgradient
                                      D.4-6

-------
           RESPONSES TO RWQCB JULY 1.1,1997 COMMENTS (Continued)


                       groundwater  monitoring  points  are necessary  to  verify  site
                       conditions during monitoring prior to closure.

 Response:             The draft ROD discussed the need for additional monitoring points
                       downgradicnt of Site  OT-51 in Sections  2.6.2.1  and 2.6.2.5.   In
                       addition. Table 20 included 2 wells as part of the FS cost estimate. An
                       additional statement has been added to Section 2.6.4.2 that one or two
                       wells will be installed to satisfy the long-term monitoring requirement
                       for Site OT-51.
 Comment No. 20:
Response:
Comment No. 21:
Response:
Comment No. 22:
Response:
 Because the closure activities at the landfill sites are complete, the
 ROD should include references  to Table 4 (Landfill ARARs)
 describing the compliance status of each ARAR. This will allow a
 determination of which  ARARs  apply  during the post-closure
 maintenance and monitoring phase.

 Text has been added to Section 2.9 (Site Status) that "as part of the 5-
 year review, the status of compliance with ARARs will be evaluated
 and reported."

 The ROD must clarify when the landfill post-closure maintenance
 and monitoring plan will be  submitted  to meet the substantive
 requirements of the following section of the California Code of
 Regulations, Title 23, Chapter  15: §2580(a), §2581(c), and §2597.

 The draft "Site Closeout Report  for DP-03, DP-04, LF-12, LF-14, and
 the Southeast Disposal Area"  was  submitted in  June  1997.   The
 proposed maintenance activity schedule is presented in this report and
 is summarized on Table 12-3 of the Closeout Report. This document
 is referenced where appropriate in the text of the ROD.

 The ROD  must include  information to determine if a landfill
 release has occurred. Board staff have previously indicated that
 the Water Quality Protection Standard (WQPS) must be specified
 in the ROD.

 As  agreed during the conference call between the  RWQCB, USAF,
 DTSC, and Montgomery Watson on  October  14, 1997, text has been
 added in Section 2.9 as follows; "Water Quality Protection Standards
 (WQPS) will be developed to assess  whether there has been a release
 from the landfills. The WQPS will be developed within 6 months of
 the  signing  of this  ROD and will be  based on  the available
 groundwater data  to  establish   baseline  values  for  which  future
sampling results will be compared."
                                       D.4-7

-------
           RESPONSES TO RWQCB JULY 11,1997 COMMENTS (Continued)
  Comment No. 23:
 Response:
 Comment No. 24:
Response:
 The Site Close-out Reports for DP-03, DP4M, LF-12, LF-14 and
 the  Southeast  Disposal  Area, dated June 1997, provided  by
 Montgomery  Watson,  Section  12,  Table 12-2, gives useful
 information regarding analyte selection.   The elements of long
 term monitoring should be  incorporated  in the ROD, giving
 flexibility for future changes.

 Text has been added to Section 2.9 to state that "as part of the
 monitoring program, monitoring wells associated with the landfills are
 sampled and analyzed for halogenated volatile organic compounds
 (HVOCs) (EPA  method 8260  suggested),  and landfill  indicator
 parameters (pH, total dissolved solids, chloride, sulfate, and nitrate).
 The sampling frequency and analyte selection may be modified as the
 program progresses."

 As discussed during July 1,1997 meeting, for long term detection
 monitoring at landfills, it is not necessary  to sample for metals
 unless sufficient data has not yet been collected for determining
 the  WQPS.   It  is  necessary  to  monitor  for volatile organic
 compounds in all landfill detection monitoring wells by USEPA
method 8260.

See response to Comment 23.
                                     D.4-8

-------
          Appendix E
MONTGOMERY WATSON
                                                 m

-------

-------
                         APPENDIX E
RESPONSES TO AGENCY COMMENTS TO NOVEMBER 1997 DRAFT FINAL ROD

-------

-------
                        RESPONSES TO USEPA COMMENTS
                DATED DECEMBER 5,1997 ON THE NOVEMBER 1997
        DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA

 GENERAL COMMENTS
 Comment No. 1:
 Response:

 Comment No. 2:
Response:
  Page 1-3, Revise EPA's approval signature to the following:
     Daniel D. Opalinski
     Chief, Federal Facilities Cleanup Branch
     Environmental Protection Agency
     Region IX

  Agree. The text has been modified accordingly.

  Pages 2-17/18, y*/4* respective paragraphs.   EPA's comment
  number one on the draft ROD concerning human health risk was
  not adequately addressed.  There are still instances where the
  ROD cites the remedy selection  was based mainly on human
  health risk, specifically with DP-03/04. Again, human health risk
  was only one of several, but not the main deciding factor used for
  remedy selection.   This must  be made clear  throughout the
 document as stated in our previous comments in the FS and the
 Draft ROD comments.

 The sentences in question have been removed from the document as
 agreed during the December 23, 1997 RPM meeting.

 Text in Section 2.9 (Current Site Status) of the November 1997 Draft
 Final ROD states that "in an effort to accelerate the remedial process,
 to minimize present and future environmental  risks, reduce potential
 impacts to groundwater, and facilitate timely transfer of property to the
 community, cleanup activities have been initiated under the direction
 of the USAF, at some of the sites presented in this ROD" to clarify that
 site risk is not the only reason the RPMs agreed to implement remedial
 actions.

 The section referenced is 2.5.1, which summarizes the RI/FS activities
 and presents  the  risk  assessments  performed.   The  sites were
 considered in the OU 3 FS because of the exceedence of risk (human
 and ecological).   Remedy selection is based on the nine CERCLA
criteria as detailed in die subsequent Section 2.5.3.
                                     El-1

-------
        RESPONSES TO USEPA DECEMBER 5,1997 COMMENTS (Continued)
 Comment No. 3:
Response:
Comment No. 4:
Response:
Section 15.4.2, first bullet, "grading existing soil cover to a slope
of 1.5 to 25 percent to promote surface runoff...wastes." Delete the
underlined as shown, and any reference to same throughout the
document, because our official landfill discussions only involved 1
to 3 percent grade.  Although you responded to our concerns
about LF-14 that only "field changes" occurred, we disagree with
your response resulting that no changes were  made withouit our
knowledge.   Because  of the  steep slope  on the landfill  caps
modified  during  its  construction, a  contingency  plan should
address  potential  erosion  problems  in   the  Operations  and
Maintenance document.

Agree. The text has been modified to remove the statement specifying
1.5 to 25 percent slope.

Additionally, Section 2.5.4.2 been modified to state that a contingency
plan will be implemented should the remedy no longer be protective of
human health  and the  environment.  Contingency  plans  will be
described as necessary as part of the O&M documentation.

EPA's draft ROD comment number  six  concerning land use
applies.  The known land use restrictions, for the OU 3 sites,
should be described in more detail in the final ROD. If this is not
possible, the ROD should state that the language and form of the
land use restrictions will be provided to EPA for approval prior to
implementation. The sites for which land use restrictions are part
of the remedy are:
          Sites DP-03 and DP-04           (page 2-40)
          Sites LF-13, LF-14, and SEDA    (page 2-41)
          Site LF-44                      (page 2-41)
          Site FT-19c          ,          (page 2-69)
          Sites WP-17, FT-19a, OT-51 (soil) (page 2-70)
In addition, the description of Site OT-51 (groundwater) on page
2-69 mentions land use  restrictions,  but  there  is no parallel
reference in the detailed description on  page 2-70.  Assuming that
land use restrictions are intended to be  part of the remedy alt Site
OT-51 (groundwater), appropriate language should be added to
page 2-70.

The text has been modified to contain the language agreed upon at the
December 23,  1997 RPM meeting.   The sections describing the
selected remedy for each of the sites listed above (i.e., Sections 2.5.4.2
and 2.6.4.2)  have been revised to include the agreed upon language
                                       E.l-2

-------
         RESPONSES TO USEPA DECEMBER 5, 1997 COMMENTS (Continued)

                       specific to the alternatives selected (i.e., landfill covers, bioventing,
                                            opportunity to rcview ** language for
                      fAfcte typographical error in the comment: LF-13 should be LF-12.)

 CommentNo.5:        M--y Watson (MW> requested
                      m     «*        In *!y *• operation systems for various
                      TPH/VOC sites being remediated. Since mid 1995, the recurring
                      message by MW/GAFB was that these sites would be c£n™n
                      two years."  GAFB should provide the rationale in the RD/RA
                      doT1^ ?   !" ^ Why "* System «• ta -^"^ * ^ut
                      dZ'^118 ^f November RPM meetin8' ^ want«« ^ *«
                      down the moventing system at WP-17. EPA cannot concur with
                      R^D £J« rt"
-------
                RESPONSES TO URSG CONSULTANTS COMMENTS
               DATED DECEMBER 5,1997 ON THE NOVEMBER 1997
       DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                    GEORGE AIR FORCE BASE, CALIFORNIA

 GENERAL COMMENTS
 Comment No. 1:
Response:
Response:
Response:
 Section  2.6.4.2, Detailed  Description of  the  TPH/VOC  Site
 Preferred Alternative, page 2-69.

 a.) Site FT-19c, last bullet: "collection of confirmation samples
    (soil  or vapor [to  estimate soil  concentrations])  to  assess
    remedy completion."

    Confirmation sampling should reveal concentrations of COPCs
    in both soil vapor and soils. It is recommended that the phrase
    "soil or vapor" be replaced by "soil and vapor."

 Agree. The text has been revised to state "soil and vapor" samples will
 be collected to assess remedy completion.

 b.) Sites WP-17, FT-19a, OT-51 (soil), page 2-70.

    The above comment applies to these sites.

 See response to Comment la.

    Third bullet:   "implementation  of long-term groundwater
    monitoring  in  accordance  with  the   basewide  long-term
    groundwater monitoring plan (Montgomery Watson, 1996c).

    The 1996 basewide  long-term groundwater monitoring plan
    was never  received  and approved.  This bullet should be
    revised  and state that a basewide long-term groundwater
    monitoring plan will be developed for approval to address
    groundwater quality concerns at these sites.  This comment
    also applies the second bullet under site OT-51 (groundwater),
    page 2-70.

Please note that the base  has been  operating under an approved plan
(Montgomery Watson,  1995c and I996c). However, for clarity this
reference has been removed from the page in question. The 1996 plan
is now referenced in the document  only when  discussing specific
sampling events that have  already occurred.
                                     E.2-1

-------
         RESPONSES TO URSG DECEMBER 5, 1997 COMMENTS (Continued)
                       When referring to future long-term monitoring in general, the text
                       throughout the document has been modified to refer to "an approved
                       long-term groundwater monitoring plan for GAFB."

                       Sections 2.9.1.4 and 2.9.2.7 discuss long-term monitoring and state
                       that "sampling frequency and analyte selection may be modified as the
                       program progresses."

                       d)  Sites OT-51

                          The Remedial  Investigation  Report/OU 3 indicates that  a
                          Hydropunch  sample  (groundwater  at  SBS-25)  contains
                          benzene of 1,000 ug/L.   GAFB should cite that additional
                          contingency plans may be required in case implementation of
                          oxygen release chemicals show little  effect   A potential
                          anaerobic state at the site would make ORC ineffective.

Response:              (Note: no comment "c" was received. The numbering system has been
                       left unchanged to be consistent with the original comments submitted
                       bytheUSEPA.)

                       At the request of the RWQCB, the Draft Final ROD  is written such
                       that the use of oxygen-releasing  chemicals  (Alternative  11)  is  a
                      contingency and natural attenuation is the final remedy (see Section
                      2.6.4.2). The text has been modified where appropriate to clarify this
                      decision.   Additionally, note that  an  anaerobic state is a condition
                      under which  the  use of  oxygen releasing  chemicals would be
                      considered.

                      Regarding  HydroPunch® sampling, Section 2.6.1.5 documents in the
                      Draft Final ROD that HydroPunch® samples were collected in borings
                      SBS-25 and SBS-27. This information is further detailed in the OU 3
                      RI,  finalized   in  April  1996.    This   document  explains  that
                      HydroPunch® data is Level HI (nondefinitive) and therefore is suitable
                      for  screening purposes only.  The HydroPunch® samples were the
                      basis for monitoring well placement.
Comment No. 2:
                      Section 2.7.1, Summary of Site OT-69 Characteristics and Risk
                      Assessment, page 2-73.

                      First paragraph, line 1: "Site OT-69 consists of the TCE and PCE
                      groundwater contamination that was detected in the flight line and
                      operations support, facilities area."
                                      E.2-2

-------
         RESPONSES TO URSG DECEMBER 5,1997 COMMENTS (Continued)
 Response:
 Comment No. 3:
Response:
 Locations of TCE/PCE contaminated areas were not clear to the
 reader even though Figure 14 is referenced later in this paragraph.
 The ROD is a primary document and is meant to be stand-alone.
 GAFB  should  indicate   the   location  of  each  TCE/PCE
 contaminated area in the text and provide a name for each area so
 that the reader may distinguish one from the other.

 Formal "names" for the plumes have not currently been identified. As
 agreed during the December 23, 1997 RPM Meeting, Figure 14 has
 been revised  to show select  affected  wells  to  aid in  plume
 identification.

 Section 2.7.4.2, Detailed Description of the Site OT-69 Preferred
 Alternative, page 2-84.

 a)  Line 3: "In addition, continued monitoring of the natural
    attenuation  plume  will   be  achieved   through   annual
    groundwater monitoring of approximately 10 wells'*

    The frequency of monitoring and number of wells should be
    deleted from ROD and be stated in a site-specific groundwater
    monitoring plan.. GAFB  should state that the site-specific
    groundwater monitoring plan will be developed to  address
    monitoring details for OT-69.

Agree.  The text has been modified  to remove  "approximately 10
wells."

When referring to future long-term monitoring in general,  the  text
throughout the document has been modified to refer to "an approved
long-term groundwater monitoring plan for GAFB."

Sections 2.9.1.4 and 2.9.2.7 discuss long-term monitoring and state
that "sampling frequency and analyte selection may be modified as the
program progresses."

b) The ROD should cite a contingency plan if TCE levels remain
   high at OT-69 (e.g., well MW-72). The contingency plan can
   be developed in the RD/RA document that should include the
   following: (1) which contaminated areas will be involved, (2)
   cite the predicted concentrations at each well, and (3) rationale
   for any active remedial actions. It is recommended that active
   remedial actions be taken when measured TCE concentrations
                                      E.2-3

-------
        RESPONSES TO URSG DECEMBER 5,1997 COMMENTS (Continued)

                          is 50 percent higher than the predicted concentration (mean
                          value).

Response:              Agree   The text has been modified to state, "More active remedies
                      wouJd be considered as a contingency if the natural attenuation remedy
                      «s not restoring water quality in a timely manner.  The criteria under
                      which active  remediation would be initiated at Site  OT-69  were
                      detailed  in  a memorandum  prepared  by IT which is included as
                      Appendix B to this ROD (IT, 1995b)... If it is determined that natural
                      attenuation is not restoring water quality, more active remedies would
                      be assessed as part of the 5-year review process and may include
                      alternatives  assessed  as  part  of this  ROD  or  additional  new
                      technologies that may become available."
                                    E.2-4

-------
•Tr

-------
  RESPONSES TO DEPARTMENT OF TOXIC SUBSTANCES CONTROL COMMENTS
               DATED DECEMBER 2,1997 ON THE NOVEMBER 1997
        DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA


 GENERAL COMMENTS

 Comment No. 1:         The DTSC concurs with the Regional Water Quality Control
                        Board, Lahontan Region, comments.

 Response:,              Comment noted.

 Comment No. 2:         High quality analytical  samples will be required in order  to
                        demonstrate that the remedial action objectives  have been
                        satisfied for all remedies.

 Response:               Agree. The ROD identifies where analytical samples are proposed
                        (i.e., long-term groundwater monitoring, confirmation samples for
                        TPH/VOC sites).

 SPECIFIC COMMENTS;

 Comment No. 1:         Page 2-40, para. 3.  The ROD must clearly specify in general
                       terms  that Operations  and  Maintenance  (O&M)  will  be
                       implemented as outlined in a regulatory agency approved plan.

 Response:               As agreed during the December 23,  1997 RPM meeting. Section
                       2.5.4.2 has been modified to state that contingency plans will be
                       described  as necessary as part of the O&M documentation.  Section
                       2.9.1.5 has been  modified  to state  that "if instances of burrowing
                       animal problems continue to persist, an appropriate contingency plan
                       will be developed and presented in a subsequent O&M document."

                       In addition, Section 2.5.4.4 references ongoing O&M activities  and
                       Appendix  C states that a Post-Closure Monitoring and Maintenance
                       Plan will be developed for the OU 3 landfill sites.

Comment No. 2:         Page 2-52, para.  5.   This section addressees groundwater
                       protection levels as outlined in Figures 9 and 10. Two revisions
                       must he made to this section:
                                     E.3-1

-------
            RESPONSES TO DTSC DECEMBER 2,1997 COMMENTS (Continued)

                           (a)   First, it must be made clear that these levels are purely for
                                groundwater quality protection. This must be so indicated
                                in the text and hi the figures.
  Response:



  Comment No. 3:


  Response:

  Comment No. 4:
 Response:
Comment No. 5:
                           (b)
        Second, these levels appear to be unacceptable for human
        and ecological health. The risk, especially at the surface
        must be evaluated with a human and ecological health risk
        assessment based on high quality data points which are to
        be obtained when the remedies have run their course.
        This risk assessment must take into account all pathways
        and chemicals of potential concern.
                                                 *

        Ultimately any remedy  which  is  not deemed  by  a
        regulatory agency to be protective is inadequate and must
        be further remedied.
  (a)   Agree. The text has been modified accordingly.

  (b)   Agree. The remedy must be protective.

  Page 2-53, para. 2.  The same comment  as Page 2-52 above
  applies to this paragraph.                                   '

  See response to Comment 2.

  Page 2-67, para. l.  FT-19 groundwater does in fact  have
  groundwater  contaminated  with  TCE   above  regulatory
  thresholds. The agreement is to monitor nearby wells and take
 any necessary actions. The ROD should include language state
 that the groundwater monitoring plan which is implemented for
 FT-19 must meet all the remedial action objectives either per
 Operable Unit or on a basewide basis.

 As discussed in Section 2.6.1.2, the TCE in the groundwater beneath
   ~1S P8It of OU L  For this reason, it is not addressed in the OU
Response:
Page 2-69, para. 4, fifth bullet.  The current bullet 5 spells out
that soil or vapor samples will be obtained for confirmation
purposes. Replace the word "or" with the word "and." Both are
needed for site closure.

Agree. The text has been modified accordingly.
                                   E.3-2

-------
         RESPONSES TO DTSC DECEMBER 2,1997 COMMENTS (Continued)
 Comment No. 6:
 Response:
Comment No. 7:
Response:
  Page 2-70, para. 1. The same comment as for page 2-69 above
  applies for sites WP-17.  FT-19c and OT-51.  In addition, the
  OT-51 groundwater site may require a contingency plan if the
  preferred alternative proves inadequate.

  See Response to Specific Comment 5.

  The  text describing the selected remedy for OT-51  groundwater
  states that the remedy includes "implementation of oxygen releasing
  chemicals as a contingency if  COPCs in groundwater do  not
  decrease  to water quality goals  within a sufficient time frame."
  Section 2.9.2.4 goes into further detail by stating "If  subsequent
  rounds of long-term monitoring do not continue to show the trend of
 decreasing levels of COPCs, the contingent remedy of installation of
 oxygen-releasing chemicals described for Alternative 11 (Section
 2.6.2.6) will be implemented."

 Page 2-84, para. 3.  The number of wells and the frequency of
 sampling should be established in  an appropriate long term
 monitoring plan which addresses the remedial action objectives
 for each  ROD or basewide.  Please delete "approximately 10
 wells."

 In addition, a contingency plan should be included for OT-69
 should groundwater levels remain above action levels.

 Agree.  The text has been modified to remove "approximately 10
 wells."

 Regarding the contingency plan for Site OT-69, as agreed during the
 December 23, 1997 RPM meeting, this comment has been addressed
 as follows:

 1) The text in Section 2.9.2.5 and has been modified to state "the
   criteria under which active remediation would be initiated at Site
   OT-69 were detailed in a memorandum prepared by  IT which is
   included  as Appendix B  to this ROD."   This  memorandum
   includes the plume maps and concentration predictions made in
   October 1995.

2) The text in  quotations from the RWQCB's Specific Comment 3
   has been included in Section 2.9.2.5.
                                   E.3-3

-------
         RESPONSES TO DTSC DECEMBER 2,1997 COMMENTS (Continued)

                         3) The  "Criteria for evaluating data" and "Financial  assurances"
                            sections of  IT's  November  1995  memorandum  have  been
                            summarized in Section 2.9.2.5.

 Comment No. 8:         page 2-89, para. 7.  The discussion of the agreed upon remedy
                         for OT-69 is incomplete.  The section is missing a summary of
                         the Internationa] Technology Memorandum dated November 6,
                         1995 which spells out the detailed  methodology from passive
                         monitoring to active remedy.  The ROD must include  this
                         information.

                         In  addition,  the  ROD  must  include  the specific land  use
                         prohibitions regarding the placement of water production wells
                         In the upper aquifer in the vicinity of the flightline.  These land
                         use prohibitions must  be agreed to and approved  by  the
                         governing  regulatory  agencies.     The  release  from such
                        prohibitions must be agreed to, in writing by the Department of
                        Toxic Substances  Control  or the Lahontan  Regional Water
                        Quality Control Board.

Response:               See response to Specific Comment 7.

                        Regarding  land   use  restrictions.   Section  2.7.4.2  (Detailed
                        Description of the Site OT-69 Preferred Alternative) states that the
                        remedy will "include land use restrictions prohibiting installation of
                        wells for domestic purposes  in the affected aquifer  and deed
                        restrictions prohibiting use of contaminated water."   In addition,
                        Section 2.7.4.2 refers the reader to Section 2.9.2.5 for further detail.
                                  E.3-4

-------
    RESPONSES TO LAHONTAN REGIONAL WATER QUALITY CONTROL BOARD
          COMMENTS DATED DECEMBER 3,1997 ON THE NOVEMBER 1997
         DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA

  SPECIFIC COMMENTS
  Comment No. 1:
 Response:
 Comment No. 2:
Response:
Comment No. 3:
  Page 1-2, Section 1.4, Description of Selected Remedies.  Please
  delete the phrase "the USAF,  the USEPA, and  the  Sate  of
  California have determined."  Section 1.2 of the ROD states that
  the State of California concurs with the remedy.  The role of the
  State is to concur with, not approve, the selected remedy.  The
  statement that the  State  "determined" a  final remedy would
  suggest that the State is making a discretionary decision subject to
  the California Environmental Quality Act.

  Agree.  The text  has been modified  to  state that the USAF has
  determined the final action  with the concurrence of the regulatory
  agencies.

 Page  2-53,  Section  2.6.2,  Description   of TPH/VOC  Site
 Alternatives. Please change the last sentence of the paragraph on
 this page as follows.  "Prior to closure of a TPH/VOC site for
 which a remedy has been implemented, confirmation samples (soil
 or vapor [to estimate soil concentrations]) would be  collected as
 necessary to demonstrate that no farther impact to groundwater
 remains using the soil levels presented" in Figure 9 and 10 as a goal
 sail cleanup levels prtjtnt an Flguit 9 arc athitttd." As indicated
 in the prior sentence, site closure is dependent on threat to water
 quality and the numerical levels shown in the figures are a goal to
 meet the cleanup objective.

 As agreed during the December 23, 1997 RPM meeting,  the text has
 been modified as follows: "Prior to  closure of a TPH/VOC site for
 which a remedy has been implemented, confirmation samples (soil and
 vapor)  would  be collected as necessary  to demonstrate that soil
 cleanup levels presented on  Figures 9 and 10 are achieved.  If
 contamination  remaining in soil can be demonstrated to have no
 impact  to groundwater quality, concentrations remaining in soil may
 exceed the numerical values presented in Figures 9 and 10, and the site
may be considered for closure."

Page 2-89,  Section  2.9.2.5, Site  OT-69.   The discussion of the
remedy agreed to by the Regional Board  is incomplete and does
                                     E.4-1

-------
RESPONSES TO RWQCB DECEMBER 3,1997 COMMENTS (Continued)

               not reference  the active  contingent remedy spelled out  in the
               November 6,1995 Memorandum prepared by IT Corp, on behalf
               of the Air Force. The ROD must clearly indicate the scope of the
               Site OT-69 remedy agreed to the  Regional Board.  The ROD
               should include the following language:

               "The monitoring and response plan proposed by the Air Force
               was developed  based upon computer modeling simulations that
               estimate  specific  future  concentrations  in  particular  wells
               projecting that water quality objectives will be restored in about
               50 years.  If the expected reductions do not occur in the projected
               time frame, plus or  minus 15%  of the projected concentration,
               then the data will be evaluated.  If the data are less than 2
              standard  deviations  of  the projected  concentrations  then
              monitoring may continue.   If the  data  are greater  than two
              standard deviations, then the wells will be resampled and the data
              re-evaluated.   If the data are still  greater than two standard
              deviations of the original projected concentrations, then an active
              remedy consisting of Air Sparging with Soil Vapor Extraction will
              be implemented or the agencies will reach consensus regarding a
              technical decision for implementing some other appropriate active
              remedy. The ROD will be amended at that time to specify the
              ARARs for the contingent remedy."

              In addition, the ROD must include a map of the plumes and tables
              with predicted TCE concentrations in selected wells.  The tables
              must  clearly indicate that  projected  future concentrations are
              based upon data collected in the  summer of 1995 and the time
             projections were made in October 1995 as a reference date.  The
             monitoring frequency  and specific wells niay vary as determined
             by remedial project managers.

             The ROD must specifically indicate that the Air Force will provide
             for  land use prohibitions  regarding the placement of water
             production  wells  in the  upper aquifer  in  the vicinity of the
             flightline.  Such  land  use restrictions must be included in any
             parcel, lease or deed and recorded  with the County. The specific
             language contained in the site parcel lease or deed restriction must
             be reviewed and approved by the regulatory agencies.  The ROD
            must indicate that a Well Exclusion Zone, administered by San
            Bernardino  County will be  considered  and  implemented, if
            feasible.  The State Department  of Toxic Substances Control or
            Regional Water Quality Control Board, Lahontan Region must
                            E.4-2

-------
         RESPONSES TO RWQCB DECEMBER 3,1997 COMMENTS (Continued)

                         approve removal of the deed restriction.  Further, the ROD must
                         include the  Federal Certification of  ensuring that  financial
                         resources  will be obtained  to  implement the active contingent
                         remedy.  Refer  to 22250, Title 27, Cal. Code of Regs for  the
                         requirements of Federal Certification.
  Response:
 Comment No. 4:
Response:
  As agreed during the December 23, 1997 RPM meeting, this comment
  has been addressed as follows:

  1) The text in Section 2.9.2.5 has been modified to state "the criteria
     under which active remediation would be initiated at Site OT-69
     were detailed in a memorandum prepared by IT which is included
     as Appendix B  to this ROD."  This memorandum includes the
     requested  plume maps  and concentration predictions  made  in
     October 1995.

 2)  The text in quotations (with revision for consistency  and clarity)
     has been included in Section 2.9.2.5.

 3) The "Criteria for evaluating  data" and "Financial assurances"
    sections  of  ITs  November  1995  memorandum  have  been
    summarized in Section 2.9.2.5.

 4) Regarding  land  use  restrictions, Section  2.7.4.2  (Detailed
    Description of the Site OT-69 Preferred Alternative) states that the
    remedy will "include  land use restrictions prohibiting  installation
    of wells for domestic purposes in  the affected aquifer and deed
    restrictions  prohibiting use of contaminated water."  In addition,
    Sections 2.7.4.2  refers the reader to Section  2.9.2.5  for further
    detail.

 Table 4, ARARs for GAFB OU 3 Landfill Sites, DP-03, DP-04, LF-
 12, LF-14 and  the SEDA.  Board staff previously indicated to the
 Air Force that  Title 27, Cal. Code of Regs was recently adopted to
 replace portions of Titles 14 and 23, Cal. Code of Regs.   The
 appropriate new section numbers should  be cited in this table.
 Otherwise, the following footnote should be placed at the end of
 the table and flagged. "These sections of Title 14 Cal. Code of
 Regs and Title 23 Cal. Code of Regs have been recodffied into Title
 27 Cal. Code of Regs. See Title 27 Cal. Code of Regs for the new
equivalent section numbers that apply."

The above footnote has been added to Table 4 (on page 10 of 10) with
minor revision for consistency and clarity.
                                       E.4-3

-------
       RESPONSES TO RWQCB DECEMBER 3,1997 COMMENTS (Continued)
 Comment No. 5:
Response:

Comment No. 6:
Response:
 Table IS, page 1 of 9, fourth item [SWRCB Resolution 92-49J.
 Please delete the last sentence in the description which states "In a
 separate forum, the Department of Defense (DoD), USEPA Region
 IX, and the State are attempting to globally resolve the ARAR
 status of SWRCB Resolution 92-49, including Section III.G, for all
 DoD sites within the State." Board staff understand that there are
 no current efforts in progress, or planned, to resolve the ARAR
 status of SWRCB Resolution 92-49.

 The table has been modified accordingly.

 Table 15, page 6 of 9, second item [NPDES Stormwater Program].
 Please Include the following sentence after the existing sentence in
 the description column.  'To comply with this requirement, the
 Air Force must comply with the requirements contained in the
 State  General Industrial Storm Water Permit (Order No. 91-13-
 DWQ, as amended  by Order No. 92-12-DWQ,  NPDES  No.
 CAS000001)."    The State administers  the federal   NPDES
stormwater program.

The table has been modified accordingly.
                                     E.4-4

-------
                        RESPONSES TO USEPA COMMENTS
                DATED FEBRUARY 2,1998 ON THE NOVEMBER 1997
       DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA
 Comment No. 1:
 Response:
Comment No. 2:
 Pages  2-37  and  2-65, Selected  Remedies.   The DF ROD is
 presented more like a FS rather than a decision document The
 reader cannot easily identify the selected remedy for each site, the
 main purpose of a ROD.  Accordingly, the ROD should clearly
 document the selected remedy  along with the estimated cleanup
 time for sites in active remediation. Sites that have already been
 remediated should show the dates of their completion.

 The presentation of the OU 3 ROD is consistent with the USEPA's "A
 Guide to Developing Superfiind  Records of Decision" (dated May
 1990, Directive:  9335.3-02FS-1). In accordance with this guidance
 document, the elements of the FS are summarized (i.e. summary of site
 characteristics and risks,  descriptions of alternatives, comparative
 analysis of alternatives using  the nine CERCLA criteria, and the
 selected remedy). This guidance document is now cited in Section 1.2.

 Statements have  been added to  Sections 2.5.4 and 2.6.4 explicitly
 stating the "selected remedy" for each site and the estimated duration
 of cleanup or date of remediation completion.

 The selected remedies for OU 3 sites are also identified in other places
 in the document as follows:  1)  Table 1 summarizes all 60 OU 3 sites
 and identifies  the selected remedy, and 2) Section 2.9 summarizes the
 current site status and presents the action that has occurred, dates that
 remedial action was  performed,  and dates  of completion  (where
 applicable).

 Pages 2-40/41/69/70,  various OU 3 sites.  The revised tend use
 comment developed  during  the  December  22,  1997  meeting,
 "implementation of  access and land use restrictions such as
 preventing construction activities that would impair the integrity
 of the existing cover," is a good start, but still falls short of meeting
 CERCLA  and DoD  requirements.  The Under  Secretary of
 Defense's memorandum of July 25, 1997 (re:  land use),  which
 outlined CERCLA requirements, requires the following specific
 land use language in the ROD:

-  Identify future land use assumptions or objectives.
                                      E.5-1

-------
          RESPONSES TO USEPA FEBRUARY 2,1998 COMMENTS (Continued)

                         -  Specify  land  use restrictions and how they will be enforced
                            (e.g.,  deed   restrictions,  easements,   inspection/monitoring,
                            zoning,  etc.).  Potential  deed restrictions should also  be
                            documented (e.g., no residential use, no groundwater use for
                            drinking, etc.).   Refer to  our December 5* letter for more
                            guidance.

  Response              The purpose of the meeting held on December 23,  1997 during which
                        the OU 3 ROD was discussed was to agree to the  final language that
                        would  be acceptable to all  agency RPMs. During that meeting, the
                        comments from the USEPA's letter dated December 5,  1997 were read
                        and specific language to address each comment was developed.

                        In addition to the language agreed upon during the December 23, 1997
                        meeting, the text in the above referenced sections has been modified to
                        include language suggested by the  USEPA in subsequent telephone
                        conversations with the USAR  This includes notations that signage
                        will be posted  on  the  fences  at the  landfills  warning  against
                        unauthorized vehicular traffic, restricting access to equipment at the
                        TPH/VOC sites, and preventing installation of monitoring or injection
                        wells accept for environmental purposes at the landfill and TPH/VOC
                        sites.
 Comment No. 3:
Response:
 Page 2-88, Ecological Monitoring Plan.
 -  Because of desert tortoise habitat identified in a 1990 survey,
    GAFB should coordinate Section 7 consultation with the UJS.
    Fish and Wildlife Service, and the  State Fish and Game, to
    develop a sound ecological monitoring plan.

 •  Section 2.9.1.5, 3" paragraph, last sentence:  "If the burrows
    are constructed by species common to the area,...conditJon."
    This seems to imply that burrows made by species not common
    to the area would not be repaired.  Accordingly, the section,
    "constructed  by  species  common"  should  be  deleted and
    replaced  with "If  burrows  are found in  the area,  the
    burrows^.condition."

-   A three month lapse time is not responsive in  maintaining
    landfill cap integrity for burrowing problems. Burrows in the
    cap  should be  repaired  as soon as possible  to  minimize
   ecological risk problems.

-  The ecological monitoring plan will be included as part of separate
   remedial action documentation.  Appendix C of the Draft Final
                                       E.5-2

-------
RESPONSES TO USEPA FEBRUARY 2,1998 COMMENTS (Continued)

                 ROD identifies the action items to meet ROD requirements, which
                 included developing an OU 3 Landfill Post-Closure Maintenance
                 and Monitoring Plan.

              -  Details regarding the ecological monitoring plan will be presented
                 in the OU 3 Landfill Post-Closure Maintenance and Monitoring
                 Plan discussed above.

              -  The  text  as  written  indicates  that minor  repairs  may  be
                 implemented in 30  days.    Additional  details  regarding the
                 ecological monitoring plan will be presented in  the OU 3 Landfill
                 Post-Closure Maintenance and Monitoring Plan discussed above.
                            E.5-3

-------

-------
                                                    I
                                                    a
                                                    X
           Appendix F
MONTGOMERY WATSON

-------

-------
                                    APPENDIX F
           RESPONSES TO AGENCY COMMENTS TO FEBRUARY 1998 DRAFT FINAL ROD
3

-------

-------
   RESPONSES TO LAHONTAN REGIONAL WATER QUALITY CONTROL BOARD
           COMMENTS DATED MARCH 24, 1998 ON THE FEBRUARY 1998
        DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                     GEORGE AIR FORCE BASE, CALIFORNIA
 SPECIFIC COMMENTS
 Comment No. 1:
 Response:


 Comment No. 2:
Response:
Comment No. 3:
 Table 15, Title 27 Cal. Code of Regs (CCR) - Board staff indicated
 that the note added to Table 4, also applies to Table 15. That note
 states:  "Sections of Title 14 CCR and Title 23 CCR have been
 recodified into Title  27 CCR.  See  Title 27 CCR for the  new
 equivalent numbers that apply." Please include this statement at
 the end of Table  15 or indicate the correct Title 27 section
 numbers in Table 15.

 The statement previously included on Table 4 has been added to Table
 15.

 Tables 4 and 15, Footnote versus Note - The above referenced
 statement was added to Table 4 as a "Note". Board staff strongly
 believe that this statement should be included to Table 4 (and 15)
 as a referenced footnote, to provide the proper emphasis. This is
 because the current state standards are not as indicated in  the
 table.  Title 23 currently only applies  to hazardous waste. Board
 staff provided  the option of including the footnote rather than
 revising the table (as preferred) to minimize the time spent in
 finalizing this document  Please include the above statement as a
 footnote rather than a note.

 The  language previously included  as a "Note"  has been referenced
 with a superscript "a"  in the "Standard, Requirement, Criterion, or
 Limitation" column of Tables 4 and  15 to reference the  footnote
 identified with a superscript "a" on the last page of the table.

 Table 15, Inclusion of State Ground Water Standards for Cleanup
 (Concentration  Limits) - When the Applicable or Relevant and
 Appropriate Requirements (ARAR) were negotiated between the
 legal staff  of  the respective  parties to  the Federal Facilities
 Agreement (FFA), Operable Unit Three did not contain Site OT-
 69 (Small  solvent plumes  selected  for  natural attenuation).
 Subsequent to the development of the ARAR tables, Site OT-69
 was  included   with   OU-3.     Therefore,   Section  2550.4
 (Concentration Limits) must be added to Table 15. The correct
citation should be Title 27, § 20400.  Please include reference to
                F.l-1

-------
        RESPONSES TO RWQCB MARCH 24,1998 COMMENTS (Continued)

                      this section in Table 15.                                             <*

Response:              The primary meeting to negotiate ARARs was held on August 20,
                      1996 at the USEPA offices in San Francisco, California.  At that        •/;
                      meeting, Section 2550.4 was deleted from the ARARs list for the
                      TPH/VOC sites and agreed to by all parties.  Site OT-69 was part of
                      the discussion regarding the TPH/VOC sites.
                                    F.I-2

-------
    RESPONSES TO UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
           COMMENTS DATED MARCH 19,1998 ON THE FEBRUARY 1998
       DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                    GEORGE AIR FORCE BASE, CALIFORNIA
 SPECIFIC COMMENTS
 Comment No. 1:
Response:

Comment No. 2:
Response:

Comment No. 3:
Response:
 In Section 2.9.1.5., Ecological Monitoring For the Landfill Areas.
 3rd paragraph, the next-to-last sentence states:  "If the burrows
 are  constructed by species common to the area, the burrows will
 be filled with native soil materials to restore the soil cover to its
 original condition." This appears to mean that burrows will not
 be repaired if the burrowing species are not common to the area.
 When EPA questioned this  language during the RPM meeting,
 apparently  inconsistent  explanations  were   provided    by
 representatives of Montgomery Watson,  to the effect that  all
 burrows would be filled, and/or that burrows used by special-
 status species (such as burrowing owls or desert  tortoises) would
 not be filled. The section should be rewritten to make clear what
 is intended. EPA's position is that all burrows should be filled.

 The text has been modified accordingly.

 In Section 2.9.1.5, 3rd paragraph, the  last sentence should  be
 revised to specify  that George AFB will coordinate with the State
 Department of Fish and Game and the U.S. Fish and Wildlife
 Service to develop the ecological monitoring plan as part of the
 Operations and Maintenance document.

 The text has been modified accordingly.

 In Section 2.9.1.5,4th paragraph, EPA believes that a three-month
 lapse tune is not responsive in maintaining landfill cap integrity
 for burrowing problems. Burrows in the cap should be repaired
 as soon as possible, when discovered during the scheduled landfill
 inspections, to minimize ecological risks to burrowing mammals.

The text has been modified accordingly.
                                     F.2-1

-------
I

-------
   RESPONSES TO UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
         COMMENTS DATED MARCH 26,1998 ON THE FEBRUARY 1998
      DRAFT FINAL RECORD OF DECISION FOR OPERABLE UNIT 3 SITES
                   GEORGE AIR FORCE BASE, CALIFORNIA
SPECIFIC COMMENTS
Comment No. 1:
Response:

Comment No. 2:
Response:
2.9.1.5., 3rd paragraph, page 2-106:  delete the following in its
entirety;   "If burrows are observed, the animals  . . .  O&M
document"

Replacement language:  "The Air Force will consult with the State
Department of Fish and Game to develop a burrows management
protocol for the O&M document.   A  contingency  plan  for
recurring  burrow problems and the specific  details  of  the
ecological monitoring plan will be presented in the subsequent
O&M document."

The text has been modified accordingly.

2.9.1.5, 4th paragraph, page 2-107:  delete  the following in its
entirety; "An effort will be made to make repairs within 3 months
of the maintenance inspection, when possible."

Replacement language:   "An  effort will  be made  to  make
revegetative repairs as soon as it is practical based  on seasonal
timing."

The text has been modified accordingly.
                                    F.3-1

-------
•
 'I

-------

-------

-------
   I

r"
-,-•-'5T

           0  = 00)
           .   (8 d*.
              Q.

          £ a)    c
           0) O OS
           ajS>c
          4-> CLGIn
           0£ = o
             = •0 =
Reproduced by NTIS

National Technical Information Service
Springfield, VA 22161
        This report was printed specifically for your order
      from nearly 3 million titles available in our collection.
For economy and efficiency, NTIS does not maintain stock of its vast
collection of technical reports.  Rather, most documents are printed for
each order. Documents that are not in electronic format are reproduced
from master archival copies and are the best possible reproductions
available.  If you have any questions concerning this document or any
order you have placed with NTIS, please call our Customer Service
Department at (703) 605-6050.

About NTIS
NTIS collects scientific, technical, engineering, and business related
information — then organizes, maintains, and disseminates that
information in a variety of formats — from microfiche to online services.
The NTIS collection of nearly 3 million titles includes reports describing
research conducted or sponsored by federal agencies and their
contractors; statistical and business information; U.S. military
publications; multimedia/training products; computer software and
electronic databases developed by federal agencies; training tools; and
technical reports prepared by research organizations worldwide.
Approximately 100,000 new titles are added and indexed into the NTIS
collection annually.
                                For more information about NTIS products and services, call NTIS
                                at 1-800-553-NTIS (6847) or (703) 605-6000 and request the free
                                 NTIS Products Catalog, PR-827LPG, or visit the NTIS Web site
                                                   http://www.ntis.gov.
                                                         NTIS
                                   Your indispensable resource for government-sponsored
                                             information—U.S. and worldwide

-------
A

-------