EPA542-R-98-016
                                   September 1998
Remediation Case Studies:
On-Site Incineration

Volume 12
                  Federal
                 Remediation
                 Technologies
                 Roundtable
                
                 Prepared by the

            Member Agencies of the
    Federal Remediation Technologies Roundtable

-------

-------
Remediation Case Studies:
On-Site Incineration
    Volume 12
    Prepared by Member Agencies of the
    Federal Remediation Technologies Roundtable
        Environmental Protection Agency
        Department of Defense
            U S Air Force
            U S. Army
            U.S Navy
        Department of Energy
        Department of Interior
        National Aeronautics and Space Administration
        Tennessee Valley Authority
        Coast Guard
                   September 1998

-------
                                            NOTICE
This report and the individual case studies and abstracts were prepared by agencies of the U S
Government  Neither the U S Government nor any agency thereof, nor any of their employees, makes any
warranty, express or implied, or assumes any legal liability or responsibility for the accuracy,
completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that
its use would not infringe privately-owned rights   Reference herein to any specific commercial product,
process, or service by trade name, trademark, manufacturer, or otherwise does not imply its endorsement,
recommendation, or favoring by the U S  Government or any agency thereof  The views and opinions of
authors expressed herein do not necessarily state or reflect those of the U S Government or any agency
thereof

Compilation of this material has been funded wholly or in part by the U S Environmental Protection
Agency under EPA Contract No  68-W5-0055
                                                11

-------
                                         FOREWORD

This report is a collection of sixteen case studies of on-site incineration projects prepared by federal
agencies  The case studies, collected under the auspices of the Federal Remediation Technologies
Roundtable, were undertaken to document the results and lessons learned from technology applications
They will help establish benchmark data on cost and performance which should lead to greater confidence
in the selection and use of cleanup technologies

The Roundtable was created to exchange information on site remediation technologies, and to consider
cooperative efforts that could lead to a greater application of innovative technologies  Roundtable member
agencies, including the U S Environmental Protection Agency, U S  Department of Defense, and U S
Department of Energy, expect to complete many site remediation projects in the near future These
agencies recognize the importance of documenting the results of these efforts, and the benefits to be realized
from greater coordination

The case study reports and abstracts are organized by technology in a multi-volume set listed below
Remediation Case Studies, Volumes 1-6, and Abstracts, Volumes 1 and 2, were published previously, and
contain 54 case studies  Remediation Case Studies, Volumes 7-13, and Abstracts,  Volume 3, were
published in September  1998 Volumes 7-13 cover a wide variety of technologies,  including on-site
incineration technologies (Volume 12) The 16 on-site incineration case studies in this report include
completed full-scale remediations and large-scale field demonstrations   In the future, the set will grow as
agencies prepare additional case studies

                                          1995 Series

       Volume 1      Bioremediation, EPA-542-R-95-002,  March 1995, PB95-182911

       Volume 2      Groundwater Treatment, EPA-542-R-95-003, March 1995, PB95-182929

       Volume 3      Soil Vapor Extraction, EPA-542-R-95-004, March 1995, PB95-182937

       Volume 4      Thermal Desorption, Soil Washing, and In Situ Vitrification, EPA-542-R-95-005,
                      March 1995, PB95-182945

                                          1997 Series

       Volume 5      Bioremediation and Vitrification, EPA-542-R-97-008, July 1997,  PB97-177554

       Volume 6      Soil Vapor Extraction and Other In Situ Technologies, EPA-542-R-97-009,
                      July 1997, PB97-177562

                                          1998 Series

       Volume 7      Ex Situ Soil Treatment Technologies  (Bioremediation, Solvent Extraction,
                      Thermal Desorption), EPA-542-R-98-011, September 1998

       Volume 8      Soil Vapor Extraction, EPA-542-R-98-012, September 1998
                                               111

-------
                                     1998 Series (continued)

        Volume 9      Groundwater Pump-and-Treat (Chlorinated Solvents), EPA-542-R-98-013,
                      September 1998

        Volume 10     Groundwater Pump-and-Treat (Nonchlorinated Contaminants), EPA-542-R-98-014,
                      September 1998

        Volume 11     Innovative Groundwater Treatment Technologies, EPA-542-R-98-015,
                      September 1998

        Volume 12     On-Site Incineration, EPA-542-R-98-016, September 1998

        Volume 13     Debris and Surface Cleaning Technologies, and Other Miscellaneous
                      Technologies, EPA-542-R-98-017, September 1998
                                           Abstracts

       Volume 1      EPA-542-R-95-001, March 1995, PB95-201711

       Volume 2      EPA-542-R-97-010, July 1997, PB97-177570

       Volume 3      EPA-542-R-98-010, September 1998
Accessing Case Studies

The case studies and case study abstracts are available on the Internet through the Federal Remediation
Technologies Roundtable web site at  http //www frtr gov The Roundtable web site provides links to
individual agency web sites, and includes a search function  The search function allows users to complete
a key word (pick list) search of all the case studies on the web site, and includes pick lists for media treated,
contaminant types, and primary and supplemental technology types The search function provides users
with basic information about the case studies, and allows them to view or download abstracts and case
studies that meet their requirements

Users are encouraged to download abstracts and case studies from the Roundtable web site  Some of the
case studies are also available on individual agency web sites, such as for the Department of Energy

In addition, a limited number of hard copies are available free of charge by mail from NCEPI (allow 4-6
weeks for delivery), at the following address

       U S EPA/National Center for Environmental Publications and Information (NCEPI)
       PO Box 42419
       Cincinnati, OH 45242
       Phone  (513) 489-8190 or
               (800) 490-9198
       Fax    (513) 489-8695
                                              IV

-------
                                  TABLE OF CONTENTS

Section                                                                               Page

INTRODUCTION                                                                          1

ON-SITE INCINERATION CASE STUDIES                                                   9

       Baird and McGuire Superfund Site, Holbrook, Massachusetts                              10

       Bayou Bonfouca Superfund Site, Shdell, Louisiana                                       25

       Bridgeport Refinery and Oil Services Superfund Site,
       Logan Township, New Jersey                                                         39

       Celanese Corporation Shelby Fiber Operations Superfund Site,
       Shelby, North Carolina                                                              53

       Coal Creek Superfund Site, Chehahs, Washington                                        65

       FMC Corporation - Yakuna Pit Superfund Site, Yakuna, Washington                       79

       Former Nebraska Ordnance Plant Site, Mead, Nebraska                                   95

       MOTCO Superfund Site, Texas City, Texas                                           127

       Old Midland Products Superfund Site, Ola, Arkansas                                    141

       Petro Processors Superfund Site, Baton Rouge, Louisiana                                155

       Rocky Mountain Arsenal Superfund Site, Commerce City, Colorado                       171

       Rose Disposal Pit Superfund Site,  Lanesborough, Massachusetts                          185

       Rose Township Dump Superfund Site, Holly, Michigan                                  199

       Sikes Disposal Pits Superfund Site, Crosby, Texas                                      215

       Times Beach Superfund Site, Times Beach, Missouri                                    231

       Vertac Chemical Corporation Superfund Site, Jacksonville, Arkansas                      247


                                         TABLES

Table                                                                                 Page

1      General Information on the Selected Sites                                                3

2      Summary of Cost Data for Each Site                                                   6

-------
This Page Intentionally Left Blank
               VI

-------
                                       INTRODUCTION

Increasing the cost effectiveness of site remediation is a national priority  The selection and use of more
cost-effective remedies requires better access to data on the performance and cost of technologies used in
the field  To make data more widely available, member agencies of the Federal Remediation Technologies
Roundtable (Roundtable) are working jointly to publish case studies of full-scale remediation and
demonstration projects Previously, the Roundtable published a six-volume series of case study reports
At this time, the Roundtable is publishing seven additional volumes of case study  reports, primarily focused
on soil and groundwater cleanup

The case studies were developed by the U S Environmental Protection Agency (EPA), the U S
Department of Defense (DoD), and the U S Department of Energy (DOE) The case studies were
prepared based  on recommended terminology and procedures agreed to by the agencies  These procedures
are summarized in the Guide to Documenting and Managing Cost and Performance Information for
Remediation Protects (EPA 542-B-98-007, September 1998) (The September 1998 guide supersedes the
original Guide to Documenting Cost and Performance for Remediation Projects, published in March 1995 )

The case studies present available cost and performance information for full-scale remediation efforts and
several large-scale demonstration projects  They are meant to serve as primary reference sources, and
contain information on site background and setting, contaminants and media treated, technology, cost and
performance, and points of contact for the  technology application The studies contain varying levels of
detail, reflecting the differences in the availability of data and information  Because full-scale cleanup
efforts are not conducted primarily for the  purpose of technology evaluation, data on technology cost and
performance may be limited

The case studies in this volume describe a  wide variety of incinerators, including rotary kiln (13),
horizontal liquid injection (1), submerged quench (1), and infrared (1) Air pollution controls include
secondary combustion chambers (SCC), quench towers, baghouses, cyclone separators, wet scrubbing
systems,  gas conditioners, mist eliminators, and cooling towers  Contaminants treated by the incinerators
included  dioxins, volatile organic compounds (VOCs), polycychc aromatic hydrocarbons (PAHs),
pesticides, and explosives and propellants  Relatively small and large incineration projects are included,
with the quantity of material treated ranging from 4,660 to 496,000 tons of solid material (soil, sludge, and
debris) and from 213,000 to 350,000,000 gallons of liquids

-------
Table 1 provides a summary including information on technology used, contaminants and media treated,
and project duration for the 16 on-site incineration projects in this volume  This table also provides
highlights about each application Table 2 summarizes cost data, including information on quantity of
media treated In addition, Table 2 shows a calculated unit cost for some projects, and identifies key
factors potentially affecting project cost  (The column showing the calculated unit costs for treatment
provides a dollar value per unit of soil or liquid treated )  Cost data are shown as reported in the case
studies and have not been adjusted for inflation to a common year basis The costs should  be assumed to
be dollars for the time period that the project was in progress (shown on Table 1 as project duration)

While a summary of project costs is useful, it may be difficult to compare costs for different projects
because of unique site-specific factors  However, by including a recommended reporting format, the
Roundtable is working to standardize the reporting of costs to make data comparable across projects  In
addition, the Roundtable is working to capture information in case study reports that identify and
describe the primary factors that affect cost and performance of a given technology  Key factors that
potentially affect project costs for incineration projects include  economies of scale, concentration levels
in contaminated media, required cleanup levels, completion schedules, matrix characteristics such as soil
classification, clay content and/or particle size distribution, moisture content, total organic  carbon, Btu
value, halogen content, and metal content, and other site conditions

-------
Table 1. Summary of Remediation Case Studies: On-Site Incmeration
?^%f gvI^^W^ S^tj^^:
V f'f^'^1'^ "• *% "^K"'^! •» ''
Baird & McGmre, MA
Bayou Bonfouca, LA
Bridgeport Refinery and Oil
Services, NJ
Celanese Corporation Shelby
Fiber Operations, NC
Coal Creek, WA
FMC Corporation - Yatama,
WA
^^-"^"C'^l^-'giiF^<'"«S |p".
Rotary kiln, SCC,
quench tower, baghouse,
wet scrubbing system
Rotary kiln, SCC,
quench system, gas
conditioner, scrubber,
mist eliminator
Rotary kiln, SCC,
cyclone separator,
ventun quench, packed
tower scrubber, mist
eliminator
Rotary tain, SCC,
quench duct, baghouse,
packed bed scrubber
system
Rotary tain, SCC,
baghouse, scrubber
Rotary tain, SCC,
quench tank, ventun
scrubber, cooling tower,
packed bed adsorber,
ionizing wet scrubber

Dioxm
VOCs
Polynuclear aromatic
hydrocarbons (PAHs)
Pesticides
PAHs
PCBs
VOCs
Ethylene glycol
VOCs
PAHs
Phenol
PCBs
Pesticides
*4f?'"f.-; v $\ \ , / ?
SS^fe^6:
Soil (210,000 tons)
Sediment (1,500 cubic
yards)
Sediment (250,000 tons)
Lagoon sediment and sludge
(138,350 tons)
Debris (13,000 tons)
Levee material (12,550
tons)
Lagoon oil (3,850 tons)
Soil (4,250 tons)
Soil and sludge (4,660 tons)
Soil (9,715 tons)
Soil (5,600 cubic yards or
7,840 tons)
''">»%:,
, ">^wraiw%//<
3/95 - 3/97
11/93-7/95
12/91 - 1/96
4/91 - 12/91
1/94 - 5/94
1/93-5/93
l^-HSisfeVcV?
Successfully treated a wide variety
of contaminants in soil and
sediment, including dioxins, VOCs,
PAHs, and pesticides
Project completed 18 months ahead
of schedule for this relatively large
quantity of waste
Inadequate design caused numerous
mechanical problems during the
treatment of a variety of matrices,
including sludge, sediment, debris,
oil, and soil, contaminated with
VOCs and PCBs However, all
performance standards and
emissions requirements were met
during the 50 months of operation
The project was completed within
nine months
Incineration operated under a
TSCA permit, therefore,
compliance with DRE requirements
was allowed to be demonstrated
without spiking
Frigid ambient air temperatures
caused delays in setting up the
incinerator, as shakedown activities
occurred during the winter months
(shakedown and testing originally
had been scheduled for spring and
summer)

-------
Table 1. Summary of Remediation Case Studies: On-Site Incineration

Former Nebraska Ordnance
Plant -OU1, ME
MOTCO.TX
Old Midland Products, AR
Petro Processors, LA
Rocky Mountain Arsenal, CO
Rose Disposal Pit, MA
1 J Incineration System
: r , * Design
Rotary kiln, SCC,
baghouse, quench tank,
scrubber
Rotary kiln, SCC,
second incinerator with
single liquid injection
combustion chamber,
both had quench system,
gas conditioner, wet
scrubber, mist eliminator
Rotary kiln, SCC,
quench tower, ventun
scrubber, baghouse, wet
scrubber
Honzontal liquid
injection incinerator,
quench tank, wet
scrubber, paniculate
scrubber, entrainment
separator
Submerged quench
incinerator, quench
chamber, spray dryer,
ventun scrubber, packed
tower scrubber
Rotary bin, SCC,
cyclone separator,
baghouse, quench
towers, wet scrubbing
system
Principal
Explosives and
propellants
Styrene tars
VOCs
Pentachlorophenol
PAHs
Chlonnated
hydrocarbons
PAHs
Oils
Organochlonc and
organophosphoric
pesticides
PCBs
VOCs
-9 i-*
Media (Quantity)
Soil and debns (16,449
tons)
Soil (4,699 tons)
Sludge (283 tons)
Organic liquids (7,568 tons)
Aqueous waste (10,471
tons)
Soils, sludges, and
sediments (102,000 tons)
Organic liquids and fumes
(213,376 gallons, as of June
1997)
Liquids (10 9 million
gallons)
Soil (51,000 tons)
Project
Duration
9/97 - 12/97
5/90 - 12/91
6/92-5/93
(Ongoing
report covers
11/94
through 5/97)
7/93-7/95
2/94-7/94
•Hv ^s^ l-f «
Project completed within three
months
Mechanical problems, caused in
part by the lack of accurate waste
charactenzahon, were encountered
On-site incineration was stopped m
December 1991 because of a
dispute between the contractor and
the responsible party (RP), the
remedy was changed to off-site
incineration, in part because of the
dispute and mechanical problems
According to project managers, this
incineration project encountered
few problems because of good
waste charactenzation
Incineration was used to treat free
product and emissions from a
groundwater pump and treat
system
Submerged quench incinerator used
to treat liquid pesticide wastes
Innovative design was used to
capture metal particulates
Incinerator used to treat more than
50,000 tons of soil contaminated
with high levels of PCBs (400,000
mg/kg)

-------
Table 1. Summary of Remediation Case Studies: On-Site Incineration
N " fr^\',, "' NVt/,'ha|V,
H^'«-S|te;ffame,Stote> *" •
Rose Township Dump, MI
Sikes Disposal Pits, TX
Times Beach, MO
Vertac Chemical Corporation,
AR
c stiitiijerati i
Infrared incinerator,
SCC, quench, ventun
scrubber, packed-column
scrubber
Rotary kiln, SCC,
quench section, ventun,
two-stage scrubber
Rotary kiln, SCC,
quench section, ventun,
two-stage scrubber
Rotary kiln, SCC,
cyclone separators, wet
scrubbers
^ V £wwajw$f\*i, ^
' . fiCoiitanupatjIs >sss"
PCBs
VOCs
Semivolatile organic
compounds (SVOCs)
Organic and phenolic
compounds
Dioxm
Dioxm
VOCs
Pesticides
'•vSt. U,«^^JSI
Soils and debns (34,000
tons)
Soil and debns (496,000
tons)
Contaminated water (350
million gallons)
Soil and debns (265,000
tons)
Still bottom waste and soil
in drums (9,804 tons)
•f ;, "T''!Cr*"'"'r'
*>..t
rjpBmflMW-.,'-
9/92-10/93
2/92 - 6/94
3/96 - 6/97
1/92 - 9/94
^'•'%1J&, "^^:^.l^:.Jfy91^^^S'ff^
^''\^^K'-^lf"Li'^J »,s, \.\J, ",' -•<,•,! * ,
t'K "''*•-; ^X-Z'/^Ji&
•'^•Mm:, m^^^"?M^
Infrared incinerator used to treat
contaminated soil and debns
Weather-related operational
problems led to delays in the
project schedule
Two SCCs in parallel were
required to maximize throughput of
incinerator Steam generated by
quenching of slag caused
overpressunzation in the kiln
The incinerator was used as a
central treatment facility for 27
sites in the state of Missoun that
were contaminated with dioxin
Two temporary restraining orders
were filed to stop the incineration
project in light of public concern
about the incineration of dioxin-
listed waste, on-site incineration
proceeded with non-dioxm wastes

-------
Table 2. Remediation Case Studies: Summary of Cost Data
: -rr
: SiteNaiffiet r
State i -
Bairdfe
McGuire, MA
Bayou Bonfouca,
LA
Bndgeport
Refinery and Oil
Services, NJ
Celanese
Corporation, NC
Coal Creek, WA
FMC
Corporation-
Yakima, WA
Former Nebraska
Ordnance Plant -
OU1.NE
MOTCO, TX
:--=•—-* Project Cost
Treatment
NA
$72,000,000
NA
$1,900,000
NA
NA
$6,479,245
$31,000,000
Total
$133,000,000
$110,000,000
NA
$5,300,000
$8,100,000
$6,000,000
$10,700,000
$76,000,000
Quantity and
Media
Incinerated
213,000 tons of
soil and
sediment
250,000 tons of
sediment
172,000 tons of
sediment, sludge,
debris, oil, and soil
4,660 tons of soil
and sludge
9,715 tons of soil
7,840 tons of soil*
(5,600 cubic yards)
16,449 tons of soil
and debris
23,021 tons of soil,
sludge, organic
liquid, and
aqueous waste
Calculated Unit
Cost for
Treatment**
NA
$288/ton
NA
$410/ton
NA
NA
$394/ton
$l,346/ton
Total
Unit Cost
$620/ton
$440/ton
NA
$l,000/ton
$830/ton
$770/ton
$650/ton
$3,300/ton
~ ~ -— - - -- _ - 5--
Key Factors Potentially Affecting Project -
Cost
No comments
EPA paid for the incineration on the basis of dry
weight of the ash instead of the weight of the
feed material It therefore was more desirable to
the contractor to optimize the process train and
guard against the unnecessary incineration of
moisture
SCC supports required rebuilding to repair loss
of structural integrity Slag falling into ash
quench caused damage to ash and feed augers
requiring numerous repairs
The site operator believes on-site incineration
was uneconomical, compared with off-site
incineration because a relatively small amount of
waste was treated
No comments
Statistical methodology used to minimize the
amount of soil excavated
Project costs were higher than expected due to
the increased volume of contaminated soil than
was encountered during excavation Additional
costs were also incurred due to shutdown of the
system during a period of inclement winter
weather
Inaccurate initial characterization of the waste
stream resulted in many mechanical problems
during incineration operation

-------
Table 2. Remediation Case Studies: Summary of Cost Data
S%, ' **S. 1 ,, ""*, 'i.r
^4'-f V\i'£%V';I
-ji-«-, . «• -• B|a|% , • ^H!|
Old Midland, AR
Petro Processors,
LA
Rocky Mountain
Arsenal, CO
Rose Disposal
Pit, MA
Rose Township
Dump, MI
Sikes Disposal
Pits, TX
Times Beach,
MO

fl? . *%5 ,,""%, S _ .?!
$22,500,000
(excavate,
incinerate,
backfill)
$4,800,000
through 5/97
$58,000,000
NA
NA
$81,000,000
Confidential
'•<-. • • ."V fff'f, '1
^;:%tei-%^
$27,100,000
$59,220,000
through 5/97
$93,000,000
NA
$12,000,000
$115,000,000
(total includes
$11, 000,000 in
miscellaneous
O&M costs)
$110,000,000
•WL^&^p'^
>j^,|^iaBtrtyi^ttd[ >
•4%> . wl?>,t-fe
,.,'- 'J^citter^ed^,
102,000 tons of
soil, sludge, and
sediment
213,376 gallons of
organic liquid and
fumes (as of June
1997)
10 9 million
gallons of liquid
5 1,000 tons of soil
34,000 tons of soil
and debris
496,000 tons of
soil and debris
265,000 tons of
soil and debris
f'CMcljateA TJnJitj
^^Shw-^l""
$3&&£&9&£
$220/ton
(excavate,
incinerate,
backfill)
$21/gal
$5/gal
NA
NA
$160/ton
Confidential
• ,&$£>•>} ~'*i!%
$264/ton
$280/gal
$9/gal
NA
$350/ton
$230/ton
$800/ton
'.; '-1^^i-%^>;
\^\; r^t "'^^^^J^''S' •^tf«\:.*> "•**
The cntenon for dioxm and furans in ash was
raised from 0 1 to 1 0 ppb, reducing residence
time and increasing throughput Amount of
contaminated soil underestimated
No comments
Heavy rainfall increased volume of liquid
requiring treatment The construction of a
special holding pond was required, increasing
"before treatment" capital costs Before
treatment costs were $14,800,000, after
treatment costs were $18,900,000
Operating in the winter caused weather-related
difficulties, resulting m suspension of the
operation until spring
An estimated 600 tons of incinerator ash required
remcineratton because it did not meet criteria for
on-site disposal
Completed 18 months ahead of schedule because
the contractor supplied a larger incinerator
Before treatment costs were $20,000,000, after
treatment costs were $3,000,000
An estimated 1,900 tons of incinerator ash
required remcineration because it did not meet
catena for backfilling

-------
                                       Table 2. Remediation Case Studies:  Summary of Cost Data
Site Name,
State
Vertac Chemical
Corporation, AR
Project Cost
Treatment
NA
Total
$31,700,000
Quantity and
Media
Incinerated
9,804 tons waste
and soil
Calculated Unit
Cost for
Treatment**
NA
Total
Unit Cost
$3,200/ton
Key Factors Potentially Affecting Project
Cost
The mixed solid and liquid waste stream had a
variable Btu content, creating difficulties in
maintaining optimal temperature in the kiln
Because of low pH of waste stream issues related
to worker health and safety arose Residual ash
was disposed of in a facility permitted under
RCRA Subtitle C, thereby increasing disposal
costs
Quantity reported as cubic yards Tons were calculated by multiplying cubic yards by an average density value of 1 4
Calculated unit cost for treatment provided for applications where a cost for on-site incineration was available separately from costs for other activities at a site such as
Rl/FS or remedial design

-------
On-Site Incineration




    Case Studies

-------
This Page Intentionally Left Blank
               10

-------
    On-Site Incineration at the
Baird and McGuire Superfund Site
    Holbrook, Massachusetts
               11

-------
          Incineration at the Baird and McGuire Superfund Site
                           Holbrook, Massachusetts
Site Name:
Baird and McGuire Superfund
Site
Location:
Holbrook, Massachusetts
Contaminants:
Dioxms, volatile organic
compounds (VOCs),
polynuclear aromatic
hydrocarbons (PAHs),
pesticides, and heavy metals,
including lead and arsenic
Period of Operation
March 1995 to March 1997
Cleanup Type*
Remedial action
Site General Contractor
OHM Remediation Services
Corporation
16406 US Route 224 East
Fmdlay, OH 45839
(419)423-3526
SIC Code:
2879 (Pesticides)
2841 (Soaps)
2842 (Floor Wax)
2869 (Solvents)
Technology
• Removal of moisture from
  soil using rotary dryer
• Combustion of contaminants
  in dry soil using rotary kiln
• System designed to treat 25
  tons of contaminated soil per
  hour
• Ash and flue gases
  discharged from kiln
• Residuals generated from
  incinerator returned to
  excavated areas on site
Cleanup Authority.
CERCLA
• ROD signed in September
  1986 (soil)
• ROD signed in September
  1989 (sediment)
• US Corps of Engineers
  Lead
Point of Contact
Chet Janowski
U S  EPA Region 1
John F Kennedy Building
One Congress Street
Boston, MA 02203
Waste Source:
Land disposal of process
wastes
Type/Quantity of Media Treated
Soil (210,000 tons) and sediment (1,500 cubic yards)
Purpose/Significance of
Application:
Treats wide range of
contaminants in soil and
sediment, including dioxm,
VOCs, PAHs, and Pesticides
Regulatory Requirements/Cleanup Goals
Destruction and Removal Efficiency (ORE) of 99 99% for principal organic hazardous constituents
(POHCs) as required by Resource Conservation and Recovery Act (RCRA) incinerator regulations in
40 CFR part 264, subpart O	

Results:
Trial burn data indicate that all ORE emission standards were met	
                                         12

-------
          Incineration at the Baird and McGuire Superfund Site
                           Holbrook, Massachusetts
                                     (Continued)


Description
Between 1912 and 1983, the site was operated as a chemical mixing and batching company During
a remedial investigation at the site, dioxm concentrations in the soil were measured as high as
27 8 yug/kg  A Record of Decision (ROD) signed in 1986 specified on-site incineration as the selected
remedy for the contaminated soils at the site  A second ROD signed in 1989 specified on-site
incineration as the selected remedy for the contaminated sediments of the nearby Cochato River

The incineration system included a rotary dryer for removal of moisture from the soil  The dried soil
was fed to the rotary kiln where the contaminants in the soil were volatilized and destroyed  From
March 1995 through March 1997, the incinerator processed approximately 210,000 tons of
contaminated soil and 1,500 cubic yards of contaminated sediment  All of the residuals generated
from the incineration and subsequent ancillary operations, including ash and wastewater treatment
sludge, were landfilled on site  Treatment performance and emissions data collected during this
application indicated that all required performance standards and emissions requirements were
achieved

The total cost for remediation using the incineration system was approximately $133,000,000
                                          13

-------
                                                                Baird and McGuire Superfund Site
                                    EXECUTIVE SUMMARY
    This report presents cost and performance data
    for the application of on-site incineration of
    contaminated soil at the Baird and McGuire
    Superfund site (Baird and McGuire) in Holbrook,
    Massachusetts  A rotary kiln incinerator was
    operated from March 1 995 through March 1 997
    as part of a remedial action  Contaminants of
    concern in the soil were dioxins, volatile organic
    compounds (VOCs), polynuclear aromatic
    hydrocarbons (PAHs), pesticides, and heavy
    metals, including lead and arsenic

    The Baird and McGuire site was operated as a
    chemical mixing and batching company from
    1912 to 1983 Some of the raw materials used
    on site were stored in a tank farm and piped to
    on-site laboratory and mixing buildings  Other
    raw materials were stored in drums  During the
    remedial investigation, dioxm concentrations in
    the soil were measured as high as 27 8
A
   A Record of Decision (ROD) signed in 1986
   specified on-site incineration as the selected
   remedy for the contaminated soils at the site
   second ROD signed in 1989 specified on-site
   incineration as the selected remedy for the
   contaminated sediments of the nearby Cochato
   River  Both RODs set standards requiring a
   destruction and removal efficiency (ORE) of
   99 9999% for principal organic hazardous
   constituents (POHCs)
   The remediation activities performed at Baird
   and McGuire also included the construction and
   operation of a groundwater treatment system
   Only issues relating to on-site incineration are
   discussed in this report
All of the material that was incinerated was
mechanically screened to remove debris
before incineration  The incineration system
included a rotary dryer for removal of
moisture from the soil  The dried soil was
fed to the rotary kiln where the
contaminants in the soil were volatilized and
destroyed Off-gases from the rotary kiln
were then routed to a secondary combustion
chamber (SCC)

The exhaust gas from the rotary kiln was
directed to an air pollution control system
(ARCS) consisting of a baghouse for
particulate removal, a quench tower, a wet
scrubber for fine particulate removal
Wastewater from the ARCS was treated in
an on-site wastewater treatment system

All of the residuals generated from the
incineration and subsequent ancillary
operations, including ash and wastewater
treatment sludge, were landfilled on site

During two years of operation, the
incinerator processed approximately
210,000 tons of contaminated soil, and
1,500 cubic yards of contaminated
sediment  Treatment performance and
emissions data collected during this
application indicated that all performance
standards and emissions requirements were
achieved

The total cost for remediation using the
incineration system was approximately
$133,000,000
US ENVIRONMENTAL PROTECTION AGENCY
Office of Sohd Waste and Emergency Response
Technology Innovation Office
                                               14

-------
                                                               Baird and McGuire Superfund Site
                                     SITE INFORMATION
   Identifying Information

   Baird and McGuire Superfund Site
   Holbrook, Massachusetts

   CERCLIS # MAD001041987
   ROD Date  September 30,1986 (soil)
               September 14, 1989 (sediment)
Treatment Application

Type of action   Remedial (on-site rotary
kiln incineration)

Period of operation  March 1995 - March
1997

Quantity of material treated  210,000 tons
of contaminated soil and 1,500 cubic yards
of contaminated sediment
   Background

   Historical Activity that Generated
   Contamination at the Site  Mixing, packaging
   and distribution of pesticides, disinfectants,
   soaps, floor waxes and solvents

   Corresponding SIC Codes: 2879 - Pesticides,
   2841 - Soaps, 2842 - Floor Wax, and 2869 -
   Solvents

   Waste Management Practice That
   Contributed to Contamination   Land disposal
   of process wastes

   Site History

   •   The site operated from 1912 until its closure
       in 1983  During this period, activities at the
       site included mixing, packaging, storing and
       distribution of various products, including
       pesticides, disinfectants, soaps, floor waxes,
       and solvents
    The Baird and McGuire site is located
    near the western bank of the Cochato
    River in northwest Holbrook, Norfolk
    County, Massachusetts  The site
    consists primarily of coniferous
    woodlands and wooded wetlands
    Approximately two-thirds of the site is
    within the 100-year floodplam of the
    Cochato River

    Contamination at the site has been
    attributed to the direct discharge of
    process wastes to soils, a nearby brook
    and wetlands, and a former gravel pit,
    all of which are within the current site
    borders

    Soil and sediment at Baird  and McGuire
    was contaminated with dioxm, VOCs,
    PAHs, other organic compounds,
    pesticides, and heavy metals such as
    lead and arsenic

    A site inspection was conducted in
    January 1984 and a Remedial
    Investigation (Rl) and a Feasibility
    Study (FS) were conducted in 1985 and
    1986 respectively
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                               15

-------
                                                               Baird and McGuire Superfund Site
                                 SITE INFORMATION (CONT.)
    Background (Cont
       The highest concentrations of contaminants
       were under and around former process
       buildings  In this area, soil sampling and
       subsequent analysis did not show any
       discernable decrease in contamination with
       depth  Contamination was assumed to exist
       to bedrock at a depth of approximately 15
       feet [3]

       Elevated concentrations of contaminants
       were also found in the area used as an on-
       site disposal area for a removal action in
       1983-1984  This area was fenced and
       capped after EPA removed approximately
       1,000 cubic yards of contaminated soil [3]

       Based on the results of an Rl and FS, a
       ROD was signed on September 30,1986
       specifying excavation and on-site
       incineration of contaminated soils at the
       site. Another ROD was signed on
       September 14,1989 specifying excavation
       and on-site incineration of contaminated
       sediment at the site

       It was estimated that 191,000  cubic yards of
       soil would be excavated for incineration
       This quantity included only the "Hot Areas"
       which were established such that the
       contaminant concentrations in the remaining
       soils would be one to two orders of
       magnitude less than those to be excavated
       [1]

       Between 1995 and 1997, an on-site rotary
       kiln incinerator was employed to remediate
       the excavated soil and sediment
    During two years of operation, the
    incinerator processed approximately
    210,000 tons of contaminated soil and
    1,500 cubic yards of contaminated
    sediment

Regulatory Context

•   A ROD signed in September 1986 (soil)
    and a ROD signed in 1989 (sediment)
    specified on-site incineration as the
    selected remedy for both contaminated
    soil and contaminated sediment

•   Compliance standards for the
    incineration were set based on the
    Resource Conservation and Recovery
    Act (RCRA)  regulations for incinerators
    in 40 CFR part 264 subpart O

•   Site activities were conducted under the
    authority of the Comprehensive
    Environmental Response
    Compensation, and Liability Act of 1980
    (CERCLA), as amended by the
    Superfund Amendments and
    Reauthorization Act of 1986 (SARA)
    and the National Contingency Plan (40
    CFR part 300)

Remedy Selection  On-site incineration
was selected as the remedy for
contaminated soil and sediment at the Baird
and McGuire Superfund site because it was
a cost-effective alternative that was
protective of human health and the
environment [1,2]
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                               16

-------
                                                           Baird and McGuire Superfund Site
                              SITE INFORMATION (CONT.)
                                  Table 1  Timeline [1,2,10]
* 'JflP^iffiiZ* *$**&• :
«-> Mff^.i.jK *!(Patj».# «, ^* , *W>-
1912-1983
May 1981
March 1983
July 1985
May 1985 - August 1986
September 1986
September 1989
January 1995
March. 1995 - March 1997
jS/fc
Chemical mixing and batching occurs at Bard and McGuire site
Site Investigation
EPA-imttated immediate removal action Removal of approximately 1 ,000 cubic yards of
contaminated soil and construction of a clay cap
Site sampling and analysis revealed the presence of dioxin
Remedial Investigation/Feasibility Study
Records of Decision signed
Trial burn
Rotarv kiln incinerator operational
   Site Logistics/Contacts

   Site Management. United States Army Corps
   of Engineers-lead

   Oversight.  United States Environmental
   Protection Agency

   Remedial Project Manager
   Chet Janowski
   U S  EPA Region 1
   John F Kennedy Building
   One Congress Street
   Boston, MA 02203
Treatment System Vendor
OHM Remediation Services Corporation
16406 US Route 224 East
Fmdlay, OH 45839
(419)423-3526
   Matrix Identification
                                 MATRIX DESCRIPTION
   Type of Matrix Processed Through the
   Treatment System: Soil and sediment
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            17

-------
                                                              Baird and McGuire Superfund Site
                               MATRIX DESCRIPTION (CQNT.)
    Contaminant Characterization

    Primary Contaminant Groups:  Dioxin, VOCs
    PAHs, other organic compounds, pesticides,
    and heavy metals such as lead and arsenic
    Matrix Characteristics
     The contaminant of greatest concern
     was dioxm  The maximum
     concentration detected was 28 7 ug/kg
     in the soil beneath the process
     buildings [3]
    The matrix characteristics that most significantly affect cost or performance at this site and their
    measured values are presented in Table 2 The results of these measurements were obtained based
    on the analysis of contaminated soil incinerated during the trial burn

                             Table 2  Matrix Characteristics of Soil [10]
Parameter " "*w
Moisture Content
Heat Content
Ash Content
Chloride Total
Total Chrornatographica! Orgamcs (TCO)
*P 1,4, ^tipwgsi&i- . •* isx ,, -
*'#Ha»*.3,.*, TOn* ,y ^ C •**<.
9%
430 BTU/lb
97%
0 06 %
5,600 mg/kg
                            TREATMENT SYSTEM DESCRIPTION
    Primary Treatment Technology

    Rotary Kiln Incinerator, including
    •    Rotary dryer
    •    Rotary kiln incinerator
        Secondary combustion chamber
Supplemental Treatment Technology

Pre-treatment (soil): Screened and dried

Post-treatment (air). Air Pollution Control
System, including
•   High temperature baghouse
•   High energy wet scrubbing system
•   Quench tower

Post-treatment (water)- On-site
wastewater treatment for treatment of
wastewater from wet scrubbing and
quenching
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              18

-------
                                                               Baird and McGuire Superfuncf Site
                               MATRIX DESCRIPTION (CONT.)
   System Description and Operation

   •   The excavated soil was mechanically
       screened to remove debris prior to
       incineration  The excavated sediment was
       placed into specially designed containers and
       trucked to the incinerator Feed soils and
       sediments were dried in a rotary dryer before
       being processed in the incinerator

   •   A flow diagram of the incinerator system is
       presented as Figure 1

   •   The dried material was fed to the rotary kiln
       via a drag-chain conveyor  The organic
       contaminants were volatilized and partially
       destroyed in the kiln chamber

   •   The kiln was manufactured by OHM
       Remediation Services Corporation and had a
       length of 40 feet and an inside diameter of 8
       feet  The kiln was lined with high-density
       castable refractory brick and was designed
       such that the optimal throughput of
       contaminated soil was approximately 25 tons
       per hour

   •   The kiln was rated at 32 million BTU/hr  The
       kiln drive system employed a 40 hp motor
       and rotated at a maximum rate of 120
       revolutions per hour

   •   Kiln ash was quenched in a water bath and
       discharged to a storage area  Settled solids
       were continually removed from the ash
       quench bath by a drag-chain conveyor

   •   The exhaust gas from the rotary kiln was
       routed through the rotary dryer to provide
       heat for soil drying  After passing through
       the dryer, the exhaust gas entered the
       baghouse through an internal, 180-degree
       bend knockout chamber  The exhaust gas
       then passed through 456 bag modules

   •   The baghouse was rated for a gram loading
       of treated exhaust gas less than or equal to
       0 02 grains per dry standard cubic foot (dscf)
       The air to cloth ratio was 4 40 to 1  The
       design operating conditions for exhaust gas
       flow rate and exit temperature were 24,000
actual cubic feet per minute (acfm) and
350 °F

Dust removed by the baghouse was
treated in an indirect-fired rotary
chamber  Exhaust gas from this unit
was fed back to the rotary dryer

Exhaust gas leaving the baghouse
entered the downf low quench tower
then passed through 3 levels of quench
sprays  The gas was directed by a
contactor tube to  impact sump water at
the base of the quench tower  [10]

The gas then passed into a 23 5-foot-
long mobile mounted, two-stage Hydro-
Sonic Scrubber where chemical
(caustic) and particulate scrubbing
occurred [10]

Exhaust gas from the scrubber was
routed to the SCC for further
combustion of volatilized
contaminants  The SCC operated at
approximately 1,950°F  The exhaust
gas residence time in the SCC was a
minimum of 2 seconds

Combustion gas was drawn through
the incinerator by an induced draft fan
(resulting in a constant negative
pressure throughout the system) and
was exhausted through a 100-foot
stack  Stack gas flow rate was 44,435
acfm and the stack exit temperature
was approximately 175°F

All of the residuals generated from
incineration and subsequent operations
were returned to the excavated areas
on site' This included the quenched
ash from the rotary kiln, ash from the
incineration of baghouse dust, and
wastewater treatment sludge
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                               19

-------
                                                             Baird and McGuire Superfund Site
                              MATRIX DESCRIPTION (CONT.)
      Figure 1 Incineration Flow Diagram, Baird & McGuire Superfund Site, Holbrook, Massachusetts
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                             20

-------
                                                              Baird and McGuire Superfund Site
                              MATRIX DESCRIPTION (CONT.)
                            Table 3  Summary of Operating Parameters
if jf^*S *$*m&dl&B$*Vf^~*r ^'"' ^"<
Residence Time
System Throughput
Kiln Discharge Temperature
r^ V . ', ,/
Not Available
25tph
1,233°F
                           TREATMENT SYSTEM PERFORMANCE
   Cleanup Goals/Standards
   •   The cleanup goals and standards were
       specified in the RODs Compliance
       standards for the incineration were
       established based on the RCRA incinerator
       regulations in 40 CFR part 264 subpart O
       [1,2]

   •   The RODs required a ORE of 99 9999% for
       principal organic hazardous constituents
       (POHCs)

   •   No quantitative soil cleanup standard was
       set  The limits of excavation were
       established such that contaminant
       concentrations in remaining soils were one
       to two orders of magnitude lower than the
       concentrations in the excavated soils
       According to the findings of a risk
       assessment performed for the site, the
       remaining areas of contamination  after
       excavation presented an excess lifetime
       cancer risk between 1x 104 and 1x 107

   Treatment Performance and Compliance
Incineration performance requirements
included
    99% removal of HCI,
-    99 99% ORE of all POHCs,
    particulate emissions less than 180
    mg/dscm (corrected)
-    99 9999% ORE of dioxm surrogate
    [10]

Site-specific criteria for arsenic and lead
were developed by USAGE based on the
results of site-specific air modeling  The
requirements specify a maximum stack
emission rate for arsenic and lead of
0 00793 g/s and 0 00231 g/s, respectively
[10]
       A trial burn was conducted from January 24,
       1995 through January 26, 1995 The trial
       burn was conducted at conditions that would
       reflect worst-case destruction and removal
       of all constituents of concern Naphthalene
       and monochlorobenzene were selected as
       the POHCs 1,2,4,5-tetrachlorobenzene
       (TeCB) was selected as a surrogate for
       dioxm  Naphthalene and TeCB were spiked
       into the waste feed soil as solids and
       monochlorobenzene was spiked as a liquid
       The spiking occurred as the waste feed
       entered the dryer The data for the DREs is
       included in Table 4
The incinerator operated within the
operating limits established during the trial
burn, signifying that all cleanup
requirements were met  The AWFCOs
limits that were used during the operation
of the incinerator are shown in Table 5
Information regarding the frequency of
AWFCOs was not available  Trial burn
operating parameters are shown in Table
6  (Information regarding actual  values
for operating parameters was not
available)

The residual ash was tested for each of
the POHCs These data are presented in
Table 7
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              21

-------
                                                          Baud and McGwre Superfund Site
                     TREATMENT SYSTEM PERFORMANCE (CONT.)
              Table 4 Average Destruction and Removal Efficiencies from Trial Bum [10]
Contaminant
Naphthalene
Monochlorobenzene
1 ,2,4,5-Tetraohlorobenzene
Average Contaminant Feed
Rate in Soil (Ib/hrr-' -
20521
163
2037
Average Contaminant Stack QaS
^I^EmlsstbialBat^db^hr} - ~'.
10x10 5
34x105
18x105
-DREW
99 999951
99 99979
99 999991
                           Table 5  Automatic Waste Feed Cutoffs [10]
I I I I I III
Parameter
Maximum Average Feed Rate (one hour rolling average)
Maximum Instantaneous Feed Rate (one minute average)
Minimum Kiln Discharge Temperature
Minimum Kiln Exit Pressure
Minimum SCO Gas Temperature
Draft Average SCO Exit Pressure
Minimum Exhaust Gas Oxygen
Maximum Exhaust Gas Carbon Monoxide Concentration
Minimum Scrubber Nozzle No 1 Recycle Flow Rate
Minimum Scrubber Nozzle No 2 Recycle Flow Rate
Minimum Scrubber Pressure Drop
Minimum Scrubber pH
Maximum Stack Gas Row Rate
i:- fjpf- - x- '>', >4
.-* ,l"CutIfttirnit -,. /,/
52,840 Ibs/hr
59,080 Ibs/hr
1170°F
<-0 1 inch w c
1880 °F
<-0 1 inch w c
>3%
199ppm
40gpm
32gpm
35 inch w c
60
50,000 acfm
   we- Water column
                              Table 6  Operating Parameters [10]
| „ -"f fy ^
Parameter *$t
Waste Feed Rate
Kiln Discharge Temperature
Secondary Temperature
Secondary Oxygen
Kiln Draft
Baghouse Pressure Drop
Scrubber Pressure Drop
Scrubber pH
"**^ "*~- *""' -;•"?•":>
TriaPOTh?ValUfe., ~\. •':.-,: ~:': '?•>$
5,1 94 Ibs/hr
1233 °F
1951 °F
7 24 %
-1 42 inches w c
3 71 inches w c
46 8 inches w c
669
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           22

-------
                                                           Baird and McGufre Superfund Site
                     TREATMENT SYSTEM PERFORMANCE (CONT.)
                              Table 6  Operating Parameters [10]
¥H vj&&& Q
Stack Temperature
Stack Flow Rate
Secondary Draft
Dryer Discharge Temperature
Baghouse Quench
Secondary Combustion Chamber Retention Time - calculated
J^^'W^Mtei^^^*:i^j'£
174 8 °F
44435 act m
-0 71 inches w c
309 1 °F
1514gpm
2 51 seconds
   we -Watercolumn
Table 7 Contaminant Concen
.!* f3/£j* i£« ;., , ; '7s, Js'fafeiS'OHCs *!l'-'"'*t, ;,;,,,,_ -'*'J:
Naphthalene
Monochlorobenzene
1 .2.4.5-Tetrachlorobenzene
ration in Residual HOI
*• ^S2ifeAi{1^4':; % !S
<0316
<0810
<0422
   Performance Data Quality

       According to the site personnel, the QA/QC
       program used throughout the remedial
       action met all  EPA requirements  All
       monitoring and sampling analysis was
       performed using EPA-approved methods,
       and the vendor did not note any exceptions
       to the QA/QC protocols
                              TREATMENT SYSTEM COST
   Procurement Process
       USAGE contracted with OHM Remediation
       Services to acquire and operate the
       incinerator at the site  OHM Remediation
       Services used several subcontractors to
       implement specific aspects of the operation
       [10]
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            23

-------
                                                             Baird and McGuire Superfund Site
                           TREATMENT SYSTEM COST (CONT.)
    Cost Data

    •   The estimated cost for operating the
       incinerator at the site was $133,000,000
       [11]  A total of 213,000 tons of soil and
       sediment were incinerated  This
       corresponds to a total unit cost for
       incineration of $620 per ton  A detailed
       breakdown of these costs was not available
                        OBSERVATIONS AND LESSONS LEARNED
    Observations and Lessons Learned

    •   Under certain unusual weather conditions,
       the steam plume from the incinerator stack
       touched down on nearby residences  In
       response to the public concern that was
       generated, USAGE added 50 feet to the
       height of the incinerator stack According to
       EPA officials, there were no public health
       reasons for this action  [8]
                                       REFERENCES
    1   Superfund Record of Decision. Baird and
       McGuire Site, Holbrook, Massachusetts,
       September 29,1986

    2   Superfund Record of Decision. Baird and
       McGuire Site, Holbrook, Massachusetts,
       September 14,1989

    3   Remedial Investigation Report. Baird and
       McGuire Site, Holbrook, MA, May 22,1985

    4   Feasibility Study Report. Baird and McGuire
       Site, Holbrook, MA, July 18,1986

    5   Final Addendum Report  Remedial
       Investigation Phase II. Baird and McGuire
       Site, Holbrook, MA, June 27,1986
6  EPA Supplement to the Baird and
   McGuire Feasibility Study Report of
   July. 1986

7  EPA Environmental News. October 2,
   1985

8  EPA Environmental News. March 16,
   1995

9  Superfund  Progress at National
   Priority List Sites. 1997 Update.
   Massachusetts Baird and McGuire Site.
   January, 1997

10 Trial Burn Report for the Baird and
   McGuire Superfund Site. Holbrook. MA.
   March 10, 1995

11 Engineering News-Record. McGraw-Hill
   Companies, July 14,1997
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                             24

-------
   On-Site Incineration at the
Bayou Bonfouca Superfund Site
       Slidell, Louisiana
              25

-------
          Incineration at the Bayou Bonfouca Super!und Site
                              Slidell, Louisiana
Site Name-
Bayou Bonfouca Superfund
Site
Location:
Slidell, Louisiana
Contaminants-
Polynuclear aromatic
hydrocarbons
benzo(a)anthracene,
benzo(a)pyrene,
benzo(b)fluoranthene,
benzo(k)fluoranthene,
ideno(1,2,3-cd)-pyrene,
chrysene, and creosote
Period of Operation:
November 1993 - July
1995
Cleanup Type:
Remedial action
Vendor:
IT Corporation
312 Directors Drive
Knoxville, TN 37923
(423)690-3211
SIC Code:
2491 (Wood Preserving)
Technology
• Sediment transported
  through a feed system that
  included dewatenng and
  mixing
• Incineration system
  consisting of rotary kiln and
  secondary combustion
  chamber (SCC)
• SCC operated between
  1,600°Fand1,800°F
• Exhaust gases from SCC
  directed through gas
  cleaning system
• Residual ash was landfilled,
  and an engineered cap was
  placed over residual ash and
  surface soil
Cleanup Authority:
CERCLA and State
Louisiana
• Phase I ROD signed
  August 1985
• Phase II ROD signed
  March 1987
• Fund-lead
• ESD Signed February
  1990
Point of Contact:
Mark Hansen
U S EPA Region 6
1445 Ross Avenue, Suite
1200
Dallas, TX 75202
(214) 665-7548
Waste Source:
Bayou sediments - creosote
waste
Type/Quantity of Media Treated.
Sediment (169,000 cubic yards)
Contaminated material from waste piles (10,000 cubic yards)
Purpose/Significance of
Application:
Underestimated volume of
contaminated soil by a factor of
three, prompting EPA to
reevaluate remedial plans
Completed 18 months ahead of
schedule
Regulatory Requirements/Cleanup Goals
Destruction and Removal Efficiency (ORE) of 99 99% for all constituents of concern as required
by Resource Conservation and Recovery Act (RCRA) incinerator regulations at 40 CFR part 264,
subpart O	

Results:
Monitoring and trial burn data indicate that all ORE and emission standards have been met	
                                        26

-------
          Incineration at the Bayou Bonfouca Superfund Site
                               Slidell, Louisiana
                                    (Continued)
Description
Between 1892 and 1970, the Bayou Bonfouca site operated as a former creosote works facility
During this period, numerous creosote releases occurred In 1970, a fire at the plant released
large amounts of creosote into the environment Sediments in Bayou Bonfouca, an adjacent
navigable waterway, were heavily contaminated with creosote (PAHs)

In August 1985, a Phase 1 Record of Decision (ROD) was signed, specifying excavation and off-
site landfilling of creosote waste piles  In March 1987, a Phase II ROD was signed The remedial
actions for the Phase II ROD included the excavation and on-site incineration of sediment and the
contents of surface waste piles with placement of an engineered cap over residual ash and
surface soils During 1988, a detailed design investigation showed that the volume of
contaminated sediment was underestimated by a factor of three The volume increase resulted
in a cost increase and prompted EPA to issue an Explanation of Significant Difference (ESD) in
February 1990

The selected incineration system consisted of a feed system, a rotary kiln, a secondary
combustion chamber (SCC) and a gas cleaning system  Sediment was dewatered and then
mixed before being fed to the incinerator  During its operation, the incinerator processed
approximately 250,000 tons (169,000 cubic yards) of contaminated sediments and waste pile
material  Treatment performance and emissions data collected during this application indicated
that all performance standards and emissions requirements  were met

The actual cost for remediation using the incineration system was approximately $110,000,000
                                         27

-------
                                                                 Bayou Bonfouca Superfund Site
                                    EXECUTIVE SUMMARY;
   This report presents cost and performance data
   for the application of on-site incineration at the
   Bayou Bonfouca Superfund site in Slidell,
   Louisiana  A rotary kiln incinerator was
   operated from November 1993 through July
   1995 as part of a remedial action
   Contaminants of concern at the site included
   specific polynuclear aromatic hydrocarbons
   (PAHs)

   The Bayou Bonfouca site was a former creosote
   works facility that operated from 1892 until its
   closure in 1970  During this period, numerous
   creosote releases occurred  In 1970, a fire at
   the plant released large amounts of creosote
   into the environment Sediment at the Bayou
   Bonfouca site was contaminated with PAHs

   In August 1985, a Phase I Record of Decision
   (ROD) was signed, specifying excavation and
   off-site landfilling of creosote waste piles  In
   March 1987, a Phase II ROD was signed  The
   remedial actions for the Phase II  ROD included
   the excavation and on-site incineration  of
   sediment and the contents of surface waste
   piles with placement of an engineered cap over
   residual ash and surface soils

   The matenal  specified for excavation and
   incineration included approximately 165,000
   cubic yards of bayou sediments contaminated
   with PAHs in excess of 1,300 mg/kg and 10,000
   cubic yards of contaminated material from
   waste piles  The ROD also specified incinerator
   requirements that included a destruction and
   removal efficiency (ORE) of 99 99% for each
   contaminant of concern

   During 1988, a detailed design investigation
   showed that the volume of contaminated
   sediment was underestimated by a factor of
   three  The volume increase resulted in a cost
   increase and prompted EPA to issue an
   Explanation of Significant Difference (ESD)  in
   February 1990
The ESD divided the Phase II ROD
remedial action into two operable units  a
groundwater and a source control operable
unit  On-site incineration was a component
of the response for the source control
operable unit

The selected incineration system consisted
of a feed system, a rotary kiln, a secondary
combustion chamber (SCC) and a gas
cleaning system  Sediment was dewatered
and then mixed before being fed to the
incinerator

A countercurrent kiln lined with castable
refractory brick was used at the Bayou
Bonfouca site The resulting ash was
discharged from the kiln and quenched
outside of the kiln, while exhaust gases
were channeled to the SCC  The SCC
provided additional combustion of  organics
in the exhaust gas which was subsequently
quenched with water

The gas cleaning system consisted of a
quench system, a combustion gas
conditioner, a Hydro Sonic® scrubber, and a
vane separator  Particulate matter and acid
gasses were removed throughout the gas
cleaning system

During its operation, the incinerator
processed approximately 250,000  tons
(over 170,000 cubic yards) of contaminated
sediments  Treatment performance and
emissions data collected during this
application indicated that all performance
standards and emissions requirements were
met

The actual cost for remediation using the
incineration system was approximately
$110,000,000
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                               28

-------
                                                                Bayou Bonfouca Superfund Site
                                       SITE INFORMATION
   Identifying Information

   Bayou Bonfouca Superfund Site
   Slidell, Louisiana

   CERCLIS # LAD980745632

   Phase II ROD Date March 31,1987
Treatment Application

Type of action: Remedial (on-site
incineration)

Period of operation* November 1993 -
July 1995

Quantity of material treated.
approximately 250,000 tons of
contaminated sediments
   Background

   Historical Activity that Generated
   Contamination at the Site: Creosote plant that
   treated pilings for use in railway construction

   Corresponding SIC Code-  2491 (Wood
   Preserving)

   Waste Management Practice That
   Contributed to Contamination  Improper
   waste storage and disposal practices

   Site History

   •   The Bayou Bonfouca Superfund site is
       characterized by standing water and
       saturated surface soil

   •   The northern section of the site is heavily
       wooded  and the remainder of the site is
       bordered by a drainage ditch, a creek, and
       the Bayou Bonfouca

   •   The site operated as a creosote works
       facility from 1892 until it was closed as the
       result of a fire in 1970  During this period,
       numerous creosote releases occurred,
       contaminating the area with PAHs [4]  The
       fire in 1970 released large amounts of
       creosote into the environment

   •   In 1976, the Coast Guard investigated the
       Bayou Bonfouca waterway  The creosote in
       the bayou sediments was so concentrated
       that Coast Guard divers received  second-
       degree chemical burns and found that the
       bayou was biologically sterile The initial
       investigation was supplemented in 1978 by
       a study conducted by EPA, the Coast
    Guard, and the National Oceanic and
    Atmospheric Administration The
    Remedial Investigation (Rl) and
    Feasibility Studies (FS) were completed
    in 1987

    In 1988, design investigations showed
    that the volume of waste was
    approximately three times the amount
    previously estimated   This resulted in a
    dramatic increase in cost These two
    factors led EPA to divide the remedial
    action into two operable units, allowing
    remediation of the groundwater
    operable unit to continue while further
    investigating the source control
    operable unit  At the same time, EPA
    conducted a Value-Engineering (V-E)
    study to ensure that the remedy
    selected was still the most appropriate

    Incineration operations began in
    November 1993 when a trial burn was
    conducted Incineration was completed
    July 1995,18 months ahead of
    schedule

    Approximately 250,000 tons of
    contaminated sediment were
    incinerated between November 1993
    and July 1995

    Remedial actions were funded by EPA
    through the Superfund program and by
    the state of Louisiana
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              29

-------
                                                                Bayou Bonfouca Superfund Site
                                SITE INFORMATION (CONT.)
    Background (Cont.)

    Regulatory Context:

    •   In September 1983, the Bayou Bonfouca
       site was placed on the National Priorities
       List (NPL)

    •   A ROD for Phase I was signed in August
       1985, specifying excavation and off-site
       landfilhng of creosote waste piles and
       contaminated on-site soil, and the disposal
       of contaminated water by deep-well
       injection at an approved Resource
       Conservation and Recovery Act (RCRA)
       facility

    •   A ROD for Phase II was signed in March
       1987, specifying excavation and on-site
       incineration of sediment from the Bayou
       Bonfouca

    •   EPA issued an ESD in February 1990, as a
       result of the discovery of more waste than
       estimated by the RI/FS and the subsequent
       increase in cost  The ESD upheld the
       decision to use on-site incineration, but
       divided the Phase II remedial action into two
       operable  units  groundwater and source
       control
   Timeline
•  The DREs were set in accordance with
   RCRA incinerator regulations in 40 CFR
   part 264, subpart O, §264 343

•  Site activities were conducted under the
   provisions of the Comprehensive
   Environmental Response,
   Compensation, and Liability Act of 1980
   (CERCLA), as amended by the
   Superfund Amendments and
   Reauthonzation Act (SARA) of 1986,
   and the National Contingency Plan, 40
   CFR 300 [1]

Remedy Selection:  On-site  rotary kiln
incineration was selected as the remedy for
contaminated sediment at the Bayou
Bonfouca Superfund site based on the site
investigation, feasibility study, Health
Assessment, Technical Assistance
Memoranda for Development of Record of
Decision, and Reports on Public Hearings
                                      Table 1  Timeline [2J
Date
1892-1970
1976
September 1983
August 1985
1987
March 31, 1987
1988
February 1990
November 1993
November 1993-JuIy 1995
Activity r^ 'm& W *& & i
The facility on the Bayou Bonfouca site produced creosote
Coast Guard investigated Bayou Bonfouca waterway
Site was placed on the NPL
Record of Decision for Phase I signed
Remedial Investigation/Feasibility Study completed
Record of Decision for Phase II signed
Design investigations revealed volume of waste material was three times
previous estimates
ESD divided the remedial action into two operable units
Trial burn performed
Rotary kiln incinerator operated
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              30

-------
                                                               Bayou Bonfouca Superfuntf Site
                               SITE INFORMATION (CoNT.)
   Site Logistics/Contacts

   Site Management: EPA-Lead

   Oversight  Louisiana Department of
   Environmental Quality (LDEQ)

   Remedial Project Manager:
   Mark Hansen
   U S EPA Region 6
   1445 Ross Avenue, Suite 1200
   Dallas, TX 75202
   (214) 665-7548
State Contact:
Duane Wilson
Louisiana Department of Environmental
Quality
Inactive and Abandoned Sites Division
7290 Bluebonnet Drive
Baton Rouge, LA 70810
(504) 765-0463

Treatment System Vendor
IT Corporation
312 Directors Drive
Knoxville, TN 37923
(423) 690-3211
                                   MATRIX DESCRIPTION
   Matrix Identification

   Type of Matrix Processed
   Through the Treatment System:  The
   primary feed for the incinerator was
   dewatered bayou sediment  Small  amounts
   of creosote generated from groundwater
   treatment at the site and contaminated soil
   also were incinerated

   Contaminant Characterization

   Primary Contaminant Group Polynuclear
   aromatic hydrocarbons (PAHs)

   •   The contaminants of greatest concern were
       benzo(a)pyrene, benzo(a)anthracene,
    benzo(b)fluoranthene, benzo(k)-
    fluoranthene, mdeno(1,2,3-cd)-pyrene,
    and chrysene

    The maximum concentration of PAHs
    detected at the site was 13,450 mg/kg
   Matrix Characteristics Affecting Treatment Cost or Performance

   Table 2 presents the matrix characteristics
   that most significantly affected cost or
   performance at the site and their measured
   values
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                             31

-------
                                                                Bayou Bonfouca Superfund Site
                              MATRIX DESCRIPTION (CONT.)
                                  Table 2  Matrix Characteristics
Parameter
Moisture (%)
Ash (%)
Total Chloride (%)
Sulfur (%)
Carbon (%)
Oxygen (%)
Hydrogen (%)
Nitrogen (%)
Bayou Sediments
Maximum
Value
77
810
029
1 24
605
252
814
161
Minimum
Value 1'
17
36
002
004
03
03
001
002
Average >
r*VValue,.^
52
40
007
025
92
68
24
042
-ISSreWoteVfoste^ltelL **fe, **»
Maximum^
ValiftS*
NA
NA
1 42
079
963
1978
456
143

NA
NA
002
004
317
055
064
010

NA
NA
017
024
45
76
24
064
    Note NA - Not Available
                            TREATMENT SYSTEM DESCRIPTION
    Primary Treatment Technology

    Rotary kiln incineration, including

    •   Rotary kiln, and
    •   Secondary combustion chamber
   System Description and Operation

   •   The rotary kiln incineration system used at
       the Bayou Bonfouca site consisted of two
       chambers (the kiln itself and a secondary
       combustion chamber) and a gas cleaning
       system consisting of a quench system, a
       combustion gas conditioner, a Hydro Sonic®
       scrubber, and a vane separator

   •   Turbidity curtains, silt curtains, and
       absorbent booms were placed along the
       bayou prior to dredging  The curtains were
       manufactured from synthetic materials
       which allowed the passage of water but
       prevented the flow of soil particles

   •   Sediments were pumped through an 18-inch
       pipeline from the bayou into a water
       retention basin  Sediment was then moved
       to a feed preparation building where it was
Supplemental Treatment Technology

Pre-Treatment (solids)  Dewatermg and
mixing

Post-Treatment (air)

•  Quench system,
•  Combustion Gas Conditioner,
   Hydro Sonic® Scrubber, and
•  Vane Separator

Post-Treatment (water)  Oil water separator
and carbon adsorption
   dewatered in a filter press The filter
   cakes were mixed to create a
   homogeneous matrix Prepared solid
   waste was transferred to mass flow
   feeders by front-end loaders  The waste
   was then moved by a transfer conveyor
   to a slmger belt conveyor, which fed the
   waste into the kiln The transfer
   conveyor and slmger belt conveyor
   were completely enclosed and under
   negative pressure

   The countercurrent rotary kiln had a
   length of 75 feet, with an inside
   diameter of 12 feet and a volume of
   8,475 cubic feet  The kiln was a carbon
   steel chamber lined with 9 inches of
   super-duty castable refractory and was
   operated in an oxidative mode
US ENVIRONMENTAL PROTECTION AGENCY
Office of Sohd Waste and Emergency Response
Technology Innovation Office
                                              32

-------
                                                                Bayou Bonfouca Superfund Site
                       TREATMENT SYSTEM DESCRIPTION (CONT.)
       Hot ash from the kiln was discharged to an
       ash pan conveyor and then transferred to
       the ash cooler where the ash was quenched

       A slag removal system was installed in case
       slagging occurred  The system consisted of
       a slag quench chamber, a slag roller
       crusher, and a dewatermg slag removal
       screw  According to site personnel,
       slagging was not a problem

       Flue gases from the kiln were routed to the
       SCC for additional combustion of volatilized
       contaminants The SCC operated between
       1,600°F and 1,800°F, with an average
       oxygen content of 4 to 8 percent The
       inside diameter of the SCC was 10 feet, 6
       inches, and the minimum off-gas retention
       time was 2 seconds

       The exhaust gases from the SCC were
       directed through a gas cleaning system
       First, the gases were channeled through the
       quench system to cool the off-gases and
       remove particulates and acid gas  Flue gas
       from the quench system then flowed into the
       gas conditioner, where additional paniculate
       and acid gas were removed

       Gas leaving the gas conditioner entered a
       Hydro-Sonic® scrubber where caustic
       solution was sprayed into the gas stream

       The gas stream entered the vane separator,
       where the spray solution from the scrubber
       was removed
The incinerator system was equipped
with an emergency relief vent system to
treat off-gases from the kiln during
emergency shutdowns The
Environmentally Safe Temporary
Emergency Relief System® (ESTER®)
received electricity from a battery-
powered unmterruptable power source,
so the off-gases were treated even
during power outages The ESTER
system consisted of a natural gas ring
burner, two continuous gas pilots, and
two natural draft air dampers  The
system was designed to be a complete
stand-alone combustion system in
emergency shutdown situations [5]

Combustion gases were drawn through
the kiln system and  gas cleaning system
by an induced draft fan, resulting in a
constant negative pressure throughout
the system Gases were exhausted
through a 100-foot stack

Residual ash was required to meet a
goal of 10 mg/kg  PAH or less before
land disposal  Residual ash was
landfilled on-site, and an engineered
cap was placed over residual ash and
surface soils

Water from the sediment was treated by
sand-bed filters, with oil/water
separation and carbon adsorption  The
treated water was discharged into the
bayou
                            Table 3 Summary of Operating Parameters
>/V \i -* *-<*' ^ Parameter '«,,"-' ",.
Residence Time (Solids)
System Throughput
Kiln Temperature
_„ " : ~ -•*•' '"-" -Value "-r ' \ 'r „,,<
30 - 40 minutes
25 tons/hr
1,200°F
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              33

-------
                                                                Bayou Bonfouca Superfund Site
                            TREATMENT SYSTEM PERFORMANCE
    Cleanup Goals/Standards

    The cleanup goals and standards were
    specified in the Phase II ROD

    •   The sediment cleanup level was 1,300
       mg/kg of PAHs

    •   Residual on-site soils containing greater
       than 100 mg/kg PAHs and less than 1,000
       mg/kg were collected and landfilled on-
       site  Soils less than 100 mg/kg were left
       in place and those greater than 1,000
       mg/kg were incinerated  All ash  had to be
       less than 10 mg/kg PAHs before on-site
       landfillmg
The required ORE was 99 99% for each
contaminant of concern

The ESD re-evaluated the cleanup levels
presented in the ROD The levels
represented a lifetime increased cancer
risk of less than 1x104 which conformed
to the acceptable health risk criteria
contained in the National Contingency
Plan
    Treatment Performance and Compliance

    •   The trial burn conducted at the Bayou
       Bonfouca site was designed to operate the
       incineration system at conditions that
       reflected worst-case destruction and
       removal of all constituents of concern

    •   Anthracene, naphthalene, and toluene were
       selected as the POHCs for the Bayou
       Bonfouca site  The reported ORE for each
       POHC are included in Table 4
The incinerator operated within the
operating limits established during the trial
burn, signifying that all performance
requirements were met  Table 5 presents
the AWFCO limits during the operation of
the incinerator  Information regarding the
frequency of AWFCOs was not available
AWFCOs occurred occasionally
throughout the project primarily due to
electrical power interruptions from the
regional electric power provider, CLECO
Table 6 presents values for operating
parameters measured during the trial burn
and subsequent operations
            Table 4 Average Destruction and Removal Efficiencies from Compliance Testing
Contaminant
Toluene
Naphthalene
<\nthracene
Average Contaminant
Peed Rate In Soil (Ib/hr)
2336
8309
7987
Average Contaminant Rile
Stack Gas Emissions (Ib/hr)
87E-5
2 18E-3
1 99E-3

00004
00068
<0 0804
BfiE ("4 ,
>99 9996
>99 997
>99 998
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              34

-------
                                                             Bayou Sonfouca Superfuncf Site
                     TREATMENT SYSTEM PERFORMANCE (CONT.)
                           Table 5  Automatic Waste Feed Cutoffs [2]
,^^-rTt
Maximum kiln feed rate, 15-mmute rolling average
Maximum instantaneous kiln pressure
Minimum kiln off-gas temperature, 1-hour rolling average
Minimum kiln off-gas temperature, instantaneous
Minimum SCC off-gas temperature, 10-minute rolling average
Minimum SCC off-gas temperature, instantaneous
ESTER® pilot out
Maximum quench outlet gas temperature
Minimum GCS differential pressure, 10-minute rolling average
Maximum stack gas flow, 10-minute rolling average
Maximum stack CO, 1-hour rolling average corrected to 7% O2
Maximum stack gas CO, instantaneous corrected to 7% O2
Maximum stack gas THC, 1-hour rolling average as propane, corrected to 7% O2
Minimum stack gas O, , 1 -minute rolling average
': '' ^ 1| *& HutoJijLhnif *r -^
29 05 tph
-0 02 in w c
1,088°F
1,088°F
1,689°F
1,689°F
400°F
220° F
21 2 in W c
45,580 acfm
100ppm
500 ppm
20ppm
3 % dry volume
Table 6 Operating Parameters [2]
1 'ii *^ *ff -*""" •*"*« >.^ ?*•'••* f .£,«,„_ , ,-;,.-»• N
'• r* -.-i. ' Parameter^*-- ^',,k.^C
Minimum kiln off-gas temperature, instantaneous
Kiln Pressure, 15-mmute rolling average
Minimum SCC off-gas temperature, instantaneous
Maximum stack gas flow, 10-minute rolling average
Maximum kiln feed rate, 15-mmute rolling average
Minimum scrubber change in pressure, 10-minute rolling average
Minimum Hydro-1 Recycle flow rate
Maximum stack gas CO, 60-mmute rolling average, corrected to 7% oxygen
Maximum stack gas THC, 60-mmute rolling average, corrected to 7%
oxygen
Stack gas CO2
Stack gas O2 , 1 -minute rolling average
HCI Emissions
Particulate Matter Concentration
- 9
1,094°F
NA
1,689°F
45,580 acfm
29 05 tph
212
396
100
20
NA
NA
NA
NA
** ifti «ar -* JSu y§
SiTrial BftrnwlBelt
1053°F
-1 49 in w c
1626°F
45,050 acfm
30 79 tph
24 15 in we
396 gpm
2 ppm
15 ppm
9 78% dry volume
10 31% dry volume
0 036 Ib/hr
0 0059 gr/dscf
   'Anticipated values from the trial burn report
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            35

-------
                                                              Bayou Bonfouca Superfund Site
                      TREATMENT SYSTEM PERFORMANCE (CONT.)
    Performance Data Completeness

    •   Data are available for concentrations of
       contaminants in the incinerator residue
       These data were collected at the end of four
       separate runs during the trial burn
Performance Data Quality

•  The Quality Assurance/Quality Control
   (QA/QC) program used throughout the
   remedial action met the EPA and the state
   of Louisiana requirements
   Procurement Process
                               TREATMENT SYSTEM COST
       The prime contractor was a joint venture, IT
       Corporation (68%) and O H Materials,
       Incorporated (32%)
       The estimated total cost for operating the
       incinerator at the site was $110,000,000,
       with a cost of $72,000,000 for thermal
       treatment A total of 179,000 tons of
       sediment and waste pile material were
       incinerated  This corresponds to a total unit
       cost of $440 per ton, and a unit cost for
       thermal treatment of $288 per ton
                                        Table 7  Costs
WBS Number
331
331
331
331
331
331
331
331
01
01
01
02
02
02
02
03
01
02
03
03
05
06
09
03




Description J&fl^
Mobilization of construction equipment and facilities
Mobilization of personnel
Submittals/implementation plans
Air monitoring and sampling
Sampling surface and groundwater
Sampling soil and sediment
Laboratory chemical analysis
Earthwork (i e , excavating, stockpiling)
Miscellaneous
Total Capital Costs
Annual Operating and Maintenance Cost
Total Operation and Maintenance Costs
i
$21 million
$0 5 million
$2 0 million
$4 million
$0 8 million
$0 5 million
$2 5 million
$20 million
$3 million
$54 million
$18million/yr
$30 million
   Cost Data Quality

   •   Cost data was provided by IT Corporation
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                             36

-------
                                                                 Bayou Bonfouca Superfund Site
                         OBSERVATIONS AND LESSONS LEARNED
    Cost Observations and Lessons Learned

    •   EPA chose an innovative approach to pay
       for the incineration by paying on the dry-
       weight basis of the ash instead of on the
       weight of the feed material  This helped to
       prevent the incineration of unnecessary
       moisture by placing the responsibility on the
       contractor to optimize the process tram
After incineration of the waste at Bayou
Bonfouca was completed, the incineration
system was used to incinerate waste from
Southern Shipbuilding, a site less than
two miles away  According to site
personnel, reusing the system at Bayou
Bonfouca instead of building a new one at
Southern Shipbuilding saved at least $20
million
   Other Observations and Lessons Learned

       Approximately 96% of the AWFCOs were
       due to momentary power glitches partially
       attributable an old system of power lines
       These were not true power outages, but
       the sensitive equipment would register the
       glitch as a break in power, resulting in an
       AWFCO
    Public Involvement
The Bayou Bonfouca site had some
problems with power outages that
occurred during storms  To prevent this
from being a problem, wastes were not
fed to the unit during storms

A stack/ID fan silencing system allowed
24-hour operation without disturbing local
residents
       A Community Involvement Plan was
       developed April 1984 and revised in
       August 1985  Twenty open houses and
       workshops were held for the public
       between 1985 and 1996 Several fact
       sheets were mailed to the 318 citizens on
       the mailing list
A high level of interest existed in the
community according to site personnel
Nearby residents were generally
supportive of EPA's efforts because they
wanted the source of contamination to be
addressed
                                          REFERENCES
    1   Superfund Record of Decision Operable
       Unit 1. Bayou Bonfouca, Slidell,
       Louisiana, August 1985

    2   Superfund Record of Decision Operable
       Unit 2. Bayou Bonfouca, Slidell,
       Louisiana, March 1987

    3   Explanation of Significant Differences.
       Bayou Bonfouca, Slidell, Louisiana,
       February 1990

    4   Public Health Assessment Addendum.
       Bayou Bonfouca, Slidell, Louisiana,
       December 1993
Bayou Bonfouca Trial Burn Report. IT
Corporation, January 1994

EPA Region VI Superfund Homepage,
lnternet,(http //www epa gov /earth 1 r6/6sf/
b-bonfou pdf) March 24, 1997

Personal communication with Kevin
Smith, IT Corporation, April 3,1997

Personal communication with Mark
Hansen, USEPA, Region 6, June 1997
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                              37

-------
This Page Intentionally Left Blank
               38

-------
           On-Site Incineration at the
Bridgeport Refinery and Oil Services Superfund Site
          Logan Township, New Jersey
                      39

-------
              Incineration at the Bridgeport Refinery and
                       Oil Services Superfund Site
                      Logan Township, New Jersey
Site Name:
Bridgeport Refinery and Oil
Services Superfund Site
Location:
Logan Township, New Jersey
Contaminants
Polychlormated biphenyls
(PCBs), volatile organic
compounds (VOCs), and metals
    benzene
    cadmium
    methylene chloride
    chromium
    toluene
    barium
    acetone
    zinc
    lead
Period of Operation
December 1991 to January
1996
Cleanup Type
Remedial action
Vendor:
ENSCO, Inc
SIC Code:
NA
Technology
On-site Incineration
•  Incineration using direct-
   fired rotary kiln
•  Screening and mixing of
   contaminated sediments
   prior to incineration
•  Quenching of kiln ash in
   water bath
•  Treatment of wastewater
   from system on-site and
   discharge to nearby creek
•  Combustion of remaining
   VOCs and PCBs in
   secondary combustion
   chamber (SCC)
Cleanup Authority
CERCLA
•   ROD signed 1984
•   EPA-lead, managed
    by U S Army Corps of
    Engineers
Point of Contact
Don Lynch
U S EPA Region 2
290 Broadway
New York, NY 10007-1866
212-637-4419
Waste Source:
Lagoon Sediments-waste oil
storage and reprocessing
operations waste
Type/Quantity of Media Treated

Lagoon sediments and sludges, debris, levee material, lagoon
oil, and soil (172,000 tons)
Purpose/Significance of
Application:
Inadequate design caused
numerous mechanical
problems, incineration
operation suspended twice
because of mechanical
problems, problems with
demulsifymg complicated
dewatermg of sediment
                                       40

-------
              Incineration at the Bridgeport Refinery and
                        Oil Services Superfund Site
                       Logan Township, New Jersey
                                   (Continued)
Regulatory Requirements/Cleanup Goals
• Destruction and Removal Efficiency (ORE) of 99 99% for VOCs as required by Resource
  Conservation and Recovery Act (RCRA) incinerator regulations in 40 CFR Part 264, Subpart O,
  The ORE of 99 9999% for RGBs and ash residual as required by Toxic Substances Control Act
  (TSCA) regulations in 40 CFR Part 761


Results:
• Emissions and trial burn data indicate that all ORE and emission standards have been met


Description:
Between the 1960s and continuing through 1981, an on-site lagoon was used for disposal of
wastes from waste oil reprocessing operations conducted on site  Lagoon sediment was
contammatecTwith PCBs at concentrations greater than 500 mg/kg, as well as VOCs and metals

In 1984, EPA signed a Record of Decision (ROD) specifying on-site incineration as the selected
remedy for the sludge, sediment, soil, debris, and lagoon oil at the site  Remedial  actions were
managed by the U S Army Corps of Engineers (COE) under the oversight of EPA Region II

The material to be incinerated was excavated from the lagoon, and screened and mixed before
incineration  The material was then conveyed into a rotary kiln by a screw auger  The
incineration system also included a secondary combustion chamber (SCC) to provide further
destruction of any VOCs and PCBs  Kiln ash was quenched in a water bath  Wastewater from
the incinerator was treated in an on-site wastewater treatment system and discharged to a nearby
creek Exhaust gas from the kiln was directed to an air pollution control system (APCS) The
APCS consisted of a cyclone separator for removal of larger particulates, a secondary
combustion chamber (SCC) for destruction of any remaining VOCs and PCBs

During its 50 months of operation, the incinerator processed over 172,000 tons of sediment,
sludge, debris, oil, and soils Treatment performance and emissions data collected during this
remedial action indicated that all performance standards and emissions requirements were
achieved

The actual cost for remediation using the incineration system was approximately $187,000,000
(includes costs associated with treatment of lagoon water and removal of tank farm)
                                        41

-------
                                             Bridgeport Refinery and Oil Service Superfund Site
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site incineration at the
Bndgeport Rental and Oil Services Superfund
Site (Bridgeport site) in Logan Township, New
Jersey  A rotary kiln incinerator operated at the
Bridgeport site from December 1991 through
January 1996 as part of a remedial action

Beginning in the 1960s and continuing through
1981, an on-site lagoon was used for disposal of
wastes from waste oil reprocessing operations
conducted on site  Lagoon sediment was
contaminated with RGBs at concentrations
greater than 500 mg/kg, as well as VOCs and
metals

Because responsible parties could not be
identified quickly enough to adequately address
threats to human health and the environment
posed by the site, EPA initiated remedial actions
at the site In 1984, EPA signed a Record of
Decision (ROD) specifying on-site incineration
as the selected remedy for the sludge,
sediment, soil, debris, and lagoon oil at the
Bridgeport site  Performance standards for the
incineration included a destruction and removal
efficiency (ORE) of 99 9999% for PCBs and
99 99% for VOCs [2]

Remedial actions were managed by the U S
Army Corps of Engineers (COE) under the
oversight of EPA Region II  The material to be
incinerated was excavated from the lagoon, and
screened and mixed before incineration The
matenal was then conveyed into a rotary kiln by
a screw auger

The incineration system also included a
secondary combustion chamber (SCC) to
provide further destruction of any VOCs and
PCBs  Kiln ash was quenched in a water bath
Wastewater from the incinerator was treated in
an on-site wastewater treatment system and
discharged to a nearby creek
Exhaust gas from the kiln was directed to an
air pollution control system (APCS) The
APCS consisted of a cyclone separator for
removal of larger particulates, a waste heat
recovery boiler to reduce the temperature of
the SCC exit gas, a ventun quench to
further cool the gas stream, start the gas
absorption process, and remove some of
the entrained solids, a packed tower for
additional scrubbing, and an educator
scrubber for removal of acid fumes Dust
removed by the cyclone separator was
discharged to the kiln ash quench

During its 50 months of operation,  the
incinerator processed over 172,000 tons of
sediment, sludge, debris, oil, and soils
Treatment performance and emissions data
collected during this remedial action
indicated that all performance standards
and emissions requirements were achieved

Detailed cost information was  not available
for on-site incineration at the Bridgeport site
The actual cost for remediation at the  site
was approximately $187 million  This figure
includes costs associated with treatment of
lagoon water and removal of the tank farm
U.S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           42

-------
                                             Bridgeport Refinery and Oil Service Superfuntf Site
identifying Information

Bridgeport Rental and Oil Superfund Site
Logan Township, New Jersey

CERCLISt  NJD053292652

ROD Date  December 31,1984
                                  SITE INFORMATION
Background

Historical Activity that Generated
Contamination at the Site.  Waste oil storage
and reprocessing

Corresponding SIC Code:  NA

Waste Management Practice That
Contributed to Contamination- Waste
disposal in an on-site lagoon

Site History

•   The Bridgeport site occupies a 30-acre
    parcel of land which includes a 13-acre
    waste oil and wastewater lagoon, and a tank
    farm consisting of 90 tanks and process
    vessels

    The lagoon was used for the disposal of
    wastes from on-site waste oil reprocessing
    and storage performed on site from the
    1960s through 1981 The tank farm was
    used for waste oil storage and recovery

•   The lagoon depth reached 21 feet in some
    areas, with the bottom 13 feet in contact
    with groundwater  The volume of
    contaminants disposed of in the lagoon is
    not known,
Treatment Application

Type of action  Remedial (on-site rotary
kiln incineration)
Period of operation
1991-January 1996
December
                                                 Quantity of material treated during
                                                 application  172,000 tons, including
                                                 138,350 tons of lagoon sediment and
                                                 sludge, 13,000 tons of debris, 12,550 tons of
                                                 levee material, 3,850 tons of lagoon oil, and
                                                 4,250 tons of soil
    In the early 1970s, the eastern dike of
    the lagoon was breached, contaminating
    3 acres of land with waste oils The
    remedial action that is the subject of this
    report did not include soil from this
    3-acre area

    In the spring of 1981 the liquid level
    began to rise in the lagoon and
    threatened to overflow the dike for the
    lagoon  The U S Coast Guard
    increased the height of the dike by 5
    feet

    In the spring of 1982 and again in the
    spring of 1983 the liquid level in the
    lagoon rose and liquids threatened to
    overflow the lagoon's dike  During
    those two periods, EPA initiated
    emergency response actions at the site
    These actions consisted of reducing the
    level of liquids in the  lagoon by pumping
    the aqueous phase through a mobile
    activated carbon system and
    discharging the treated water to a
    nearby stream under a National
    Pollutant Discharge Elimination System
    (NPDES) Permit The lagoon level was
    reduced by approximately 2 feet  in  each
    instance
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           43

-------
                                             Bridgeport Refinery and Oil Service Superfund Site
                             SITE INFORMATION (CoNhr.)
Background (Cont)

•   In late 1983 and early 1984, under an initial
    removal action at the site, EPA reduced the
    level of liquids in the lagoon by 8 feet by
    pumping the aqueous phase through a
    treatment system consisting of oil/water
    separation, flocculation/sedimentation, sand
    filtration, and granular activated carbon
    adsorption

•   A Phase I Remedial Investigation/Feasibility
    Study (RI/FS) was completed by EPA in 1984
    to determine the nature and extent of soil
    contamination caused by operations related
    to the lagoon and tank farm and to evaluate
    remedial alternatives for these two areas of
    contamination  A Phase II  RI/FS was initiated
    in September 1988 to determine the extent of
    groundwater contamination and to evaluate
    remedial alternatives for the groundwater and
    any remaining hazards posed by the site
    Work to date has been performed by EPA,
    however, due to negotiations between EPA
    and the Potentially Responsible Parties
    (PRPs), work on the Phase II RI/FS has been
    suspended

•   Based on the results of the Phase I  RI/FS, a
    ROD was signed on December 31,1984
    specifying remediation through excavation
    and on-site incineration of contaminated
    sludge, sediment, soil, debris, and oil from
    the lagoon and tank farm   The ROD
    specified that contaminated areas would be
    excavated until the material removed was no
    longer visibly contaminated with oil, followed
    by additional  sampling to determine the need
    for additional excavation to meet cleanup
    goals

•   A trial burn was conducted in March and April
    of 1991, which demonstrated that the on-site
    incinerator could meet the performance
    requirements specified in the ROD
•  The incineration took place from
   December 1991 through January 1996
   Contaminated material treated by
   incineration at the Bridgeport site
   included sludge and sediments from the
   lagoon, the oil on the surface of the
   lagoon, lagoon levee material, drums
   and debris excavated from the lagoon,
   and soil surrounding the lagoon

Regulatory Context.

•  In 1983 the Bridgeport site was placed
   on the National Priorities List (NPL)

•  Because responsible parties could not
   be identified before a response was
   necessary to protect human health and
   the environment, no cooperative
   agreements for remedial actions at the
   Bridgeport site were reached for the
   early actions

•  The ROD signed in 1984 mandated that
   the lagoon sediments and  sludge be
   removed until there was no evidence of
   oil staining in soils below the sludge
   layer

   The selected remedy is consistent with
   the Comprehensive Environmental
   Response, Compensation, and Liability
   Act of 1980 (CERCLA), the Superfund
   Amendments and Reauthonzation Act
   of 1986 (SARA) and the National
   Contingency Plan (NCP) in 40 CFR part
   300

Remedy Selection  EPA determined that
on-site incineration was technically feasible,
reliable, and provided adequate protection
on human health and the environment
EPA also determined that on-site
incineration was the lowest cost alternative
that provided a solution to the  problems and
potential problems posed by the Bridgeport
site [4]
U.S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           44

-------
                                          Bridgeport Refinery and Oil Service Superfund Site
                          SITE INFORMATION (CONT.)
                                  Table 1  Timeline
'" , VH '.^ X. *"?< "' lfc\~** *• "^< ' " ^-'^ »K
v «y>' wi -j->> iJuate;st is-w;,^
1960-1981
1981
1982
1983
1983
1983-1984
1983-1984
December 31, 1984
March-April 1991
November 1991
January 1 996
September 1996
*f ,^^i- &fevi&^ ^^ If *.«:££ J«
Lagoon used for waste disposal at the Bridgeport site
U S Coast Guard emergency response increases height of lagoon dike 5 feet
EPA emergency response reduces lagoon liquid level 2 feet
Site placed on NPL
EPA emergency response reduces lagoon liquid level 2 feet
EPA initial remedial action reduces lagoon liquid level 8 feet
EPA performs Phase I RI/FS
Record of Decision signed
Trial Burn
Excavation and incineration operations begin
Incineration operations completed
Site restoration and demobilization activities completed
Site Logistics/Contacts

Site Management:  EPA-lead

Mark Wheeler
U S Army Corps of Engineers
609-241-1673

Oversight  EPA Region 2
Remedial Project Manager.
Don Lynch
US EPA Region 2
290 Broadway
New York, NY 10007-1866
212-637-4419

Treatment System Vendor:
ENSCO, Inc
Address NA
NA
                             MATRIX DESCRIPTION
Matrix Identification
Type of Matrix Processed Through the
Treatment System: Lagoon sediments and
sludges, debris, levee material, lagoon oil, and
soil
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                        45

-------
                                            Bridgeport Refinery and Oil Service Superfund Site
                           MATRIX DESCRIPTION (Cokr.)
Contaminant Characterization

Primary Contaminant Groups:  Material
incinerated at the Bridgeport Site was
contaminated with PCBs, VOCs, and metals

•   The contaminants of greatest concern were
    PCBs, benzene, methylene chloride,
    toluene, acetone, lead, cadmium,
    chromium, barium, and zinc
    Lagoon sediment contained PCBs at
    concentrations over 500 mg/kg, VOCs
    including benzene, methylene chloride,
    and toluene at concentrations up to 1
    mg/kg, and acetone at levels up to 70
    mg/kg In addition, metals, including
    lead, cadmium, chromium, barium, and
    zinc were found at the site
Matrix Characteristics Affecting Treatment Costs or Performance

Information on matrix characteristics such as
soil density, particle size, and soil moisture
content was not available
                        TREATMENT SYSTEM DESCRIPTION
Primary Treatment Technology

ENSCO Modular Waste Processor (MWP)-2001
Rotary kiln Incineration System, including

•  Waste feed handling system
•  Rotary kiin incinerator
•  Secondary combustion chamber
Supplemental Treatment Technology

Pretreatment (solids)

•  Screening
•  Mixing

Post Treatment (air)

   Cyclone separator
   Ventun quench
   Packed tower scrubber
   Educator scrubber
   Demister
   Stack

Post Treatment (water)

•  pH adjustment and clarification
   (scrubber wastewater)
•  Oil/water separation, flocculation,
   sedimentation, sand filtration, and
   activated carbon adsorption (quench
   wastewater)
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          46

-------
                                             Bridgeport Refinery and Oil Service Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
System Description and Operation
    Soils and lagoon material lying above the
    groundwater table at the Bridgeport Site
    were excavated using backhoes and
    bulldozers  Lagoon sludge that was not
    mixed with debris was excavated using a
    barge- mounted hydraulic dredge  Sludge
    that contained too much debris to be
    effectively excavated by the dredge was
    removed by large land-based cranes and an
    amphibious excavator

    Debris was separated from excavated
    material using a vibrating bar screen
    Larger pieces of debris and unshreddable
    debris were removed and disposed of off-
    site The remaining debris were shredded
    and incinerated

    To provide a homogenous feed, matenal
    was mixed prior to incineration in ponds
    constructed on-site for this purpose

    Material to be incinerated entered the rotary
    kiln at the flame end via screw auger,
    sludge lance, or ram feeder, then traveled
    through the kiln concurrent with the
    combustion gas  In the direct-fired rotary
    kiln, the PCBs and VOCs were volatilized
    and destroyed Ash and exhaust gas were
    discharged from the kiln

    Kiln ash was quenched  in a water bath and
    then sent through a filter press  Ash was
    analyzed for heavy metals, a select list of
    organic compounds, and total PCBs Ash
    that exhibited a characteristic of a
    hazardous waste for organic compounds or
    that contained greater than 2 mg/kg PCBs
    was incinerated a second time  Ash that
    exhibited a characteristic of a hazardous
    waste for metals was stabilized to remove
    the characteristic  Approximately 64,000
    tons of ash were stabilized All ash that met
    the treatment criteria, including ash that was
    retreated or stabilized, was then backfilled
    into the excavated lagoon
The rotary kiln had an inside diameter
of 8 5 feet, an outside diameter of 10
feet, and a combustion chamber volume
of 4,103 cubic feet  The kiln was limited
to a throughput rate of 24 tons of
contaminated material per hour

The kiln was designed to heat feed
material to 1,200 to 1,400°F and
combustion gas to 1,400 to 1,600°F
The kiln was heated by two 30 million
BTU/hr Lmde "A" burners fired with pure
oxygen and fuel, and was designed to
rotate at a rate of 1 to 2 rpm  The
design residence time for solids in the
kiln was 40 to 80 minutes

The off-gas from the kiln then was
routed to the SCC, which provided
further destruction of remaining
contaminants The SCC was 103 feet
long and had an internal diameter of 6 5
feet  The SCC was equipped with a 30
million BTU/hr Lmde "A" burner fired by
an oxygen/fuel mixture  The SCC was
designed to operate at a minimum
temperature of 2,012° F and provide a
minimum residence time of 2 seconds

Off-gas from the SCC passed through a
duct equipped with a water spray header
and a fire-tube boiler to reduce the
exhaust gas temperature to
approximately 500-700°F

Off-gas from the SCC was directed to a
cyclone separator for removal of larger
particulates  Particulate matter
extracted from the exhaust gas fell to
the bottom of the cyclone and was
transported to the kiln ash quench bath

The off-gas was then passed to a
venturi quench where water was
sprayed into the gas stream to reduce
the temperature to less than 190°F
The off-gas continued to the packed
tower
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           47

-------
                                            Bridgeport Refinery and Oil Service Superfund Site
                   TREATMENT SYSTEM DESCRIPTION (CONT.)
         escription and Oeration  Cont
   The packed tower removed any remaining
   particulate matter The packed tower was
   72 inches in diameter with space for as
   much as 1 0 feet of packing  The packing
   was continuously wetted by a water spray

   Off-gas exited the packed tower to the inlet
   of an induced draft fan  The induced draft
   fan provided a negative pressure throughout
   the system to prevent fugitive emissions
   From there the off-gas passed through a
   Hydrosonic® educator scrubber, a demister,
   and a stack  The educator was designed to
   remove additional acid fumes while the
   demister was designed to remove water
   vapor from the gas  Off-gas exited the
   stack with a temperature of 180 to 200° F
   and at a flow rate of 20,000 to 37,000 acfm
Scrubber water streams were
recirculated through a sump which
provided pH adjustment and
clarification During the remedial action
at the Bridgeport Site, sump bottoms
and quench solids were filter pressed
and used as lagoon backfill on site
Quench water from the incinerator was
treated in an on-site wastewater
treatment system and discharged to a
nearby creek
                       TREATMENT SYSTEM PERFORMANCE
.Cleanup Goals/Standards

•  The cleanup goals and standards were
   specified in three documents the ROD, the
   contract plans and specifications, and an
   incinerator "Permit Equivalency" document

•  The ORE and ash residual management
   standards for VOCs and metals were based
   on RCRA  regulations (40 CFR § 264 343 for
   the DREs and 40 CFR § 261 24 for ash
   residuals) The DRE standards for PCBs
   were based on regulations issued under the
   Toxic Substances Control Act (TSCA) (40
   CFR part 761)

•  The ROD  required that the lagoon
   sediments and sludge be removed until no
   oily soils were observed beneath the sludge
   layer The ROD did not specify numerical
   limits for remedial action at the  site, but
   required that sampling and analysis would
   be conducted once visibly contaminated
   material was removed The sampling
   results were to be reviewed by EPA to
   determine whether removal of additional
   material was required
The DRE requirements for the
incinerator were set at 99 9999% for
PCBs and 99 99% for VOCs

For VOCs and metals, ash was subject
to the Toxicity Characteristic Leaching
Procedure (TCLP) test  The maximum
permissible concentration of PCBs in
the residual ash was set at 2 mg/kg
The maximum permissible
concentrations of metals were the
applicable regulatory threshold
concentrations in 40 CFR § 261  24
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          48

-------
                                             Bridgeport Refinery and Oil Service Super-fund Site
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
Treatment Performance and Compliance

•   The trial burn at the Bridgeport site,
    conducted from March 12 through April 7,
    1991, was designed to operate the
    incineration system at conditions that would
    reflect worst-case destruction and removal
    of all constituents of concern

•   The POHCs selected for the trial burn were
    carbon tetrachlonde and
    monochlorobenzene,  which acted as
    surrogates for the VOCs found at the site

•   Soil excavated in the  tank farm area and
    clean fill material from off-site were used as
    incinerator feed in the trial burn Known
    quantities of PCBs (in tnchlorobenzene),
    POHCs (carbon tetrachlonde  and
    monochlorobenzene), and a metals slurry
    (arsenic trioxide, calcium oxide, and a
    potassium dichromate) were spiked into the
    incinerator feed  During the trial burn,
    concentrations of spiked contaminants in
    the waste feed and stack gas  were
    measured These data were used in
    conjunction with flow  rate data to calculate a
    ORE for each of the spiked contaminants
    The reported DRE for each of the spiked
    contaminants are included in Table 2  The
    DREs for the constituents of concern are
    assumed to be greater than those of the
    spiked contaminants
During the trial burn DREs exceeded
99 9999% for PCBs and 99 99% for
monochlorobenzene and carbon
tetrachlonde  Metals removal
percentages were in excess of 99% [3]

AWFCO limits used during operation of
the incinerator are shown in Table 4,
information on the frequency of
AWFCOs was not available  Trial burn
and typical operating parameters are
shown in Table 5

The incinerator at Bridgeport operated
within the operating limits established
during the trial burn, signifying that all
cleanup requirements established in the
ROD were met

The residual ash was tested by TCLP to
see if it was in compliance with the on-
site land disposal requirements  Data
from the TCLP analyses were not
available  Approximately 8,800 tons of
ash were incinerated a second time
because it failed to meet the PCB
concentration requirement of less than 2
mg/L Approximately 64,000 tons of
ash were stabilized because they failed
the TCLP test for heavy metals
      Table 2  Average Destruction and Removal Efficiencies and Removal Percentages from
                              Trial Burn Compliance Testing [1]
: y •£ ¥' ~7 *
"\ ,,* v- £- ^x •;

^~ Contaminant «*
Concentrations In *
Asfcfcte/LK *
<0 0001
<10
NA
<0012
<0005
0041
*"' ' ' <"•* ."" - , ,:'
<* " i*» '*"" rir v""
£ ^ 3jf . S$r -, v»
'", DRE(%)S /
>99 99997
>99 99989
>99 99998
>9992
9968
9999
aThis represents a removal percentage only and not a true DRE
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           49

-------
                                        Bridgeport Refinery and Oil Service Superfund Site
                 TREATMENT SYSTEM PERFORMANCE (CONT.)
                       Table 3 Automatic Waste Feed Cutoffs [2]
J'jii' 	 ,:'„ ","•; 	 ,;'! 	 I;; ' Parameter , | , , „ ' ,„<
SCO Temperature
Kltn Exit Temperature - No Flame
Kiln Exit Temperature - With Flame
Kiln Exit Draft
CO in Stack - 1 hour average
CO In Stack - 10 minute average
Oxygen in Stack
Steam Drum Level
Loss of Power
Loss of Induced Draft Fan
Loss of Water Flow To Quench Nozzle
" jf;x * v* "'casruwK £r -^ & ~?~.
<2,066deg F
Not applicable
<1,200,>1,580deg F
>-0 1 in w c
>100ppmv
>500 ppmv
<3 5%
<25%
Not applicable
Not applicable
Not applicable
N/A- Not Available
                          Table 4 Operating Parameters [2]
I 	 Paramefer
Contaminated Soil Feed Rate
Secondary Combustion Chamber Temperature
Secondary Combustion Chamber Residence Time
Kiln Exit Temperature
Arsenic in Feed
Cadmium In Feed
Chromium in Feed
Lead in Feed
Mercury in Feed
Nickel In Feed
Beryllium In Feed
^cumgrue f£fc.
<21, 800,000 grams/hr
>2066deg F
>2 seconds
>1580deg F
10mg/kg
10mg/kg
130 mg/kg
1 0,000 mg/kg
1 mg/kg
40 mg/kg
1 mg/kg
Maximum Allowable Emission Rate
P articulate
Sulfur Dioxide
Nitrogen Oxide
CO
Hydrocarbon
Arsenic
Beryllium
Chromium
Lead
Mercury
Nickel
PCBs
HCI
2,600 grams/hr
4,900 grams/hr
11, 400 grams/hr
4,500 grams/hr
1,400 grams/hr
3 3 grams/hr
1 6 grams/hr
2 6 grams/hr
522 grams/hr
10 9 grams/hr
3 9 grams/hr
0 0045 grams/hr
1 ,800 grams/hr
.*?' ' Trial Burft'V J|e ""I
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA

332 grams/hr
227 grams/hr
NA
NA
NA
<0 14 grams/hr
<0 3 grams/hr
0 2 grams/hr
1 6 grams/hr
015 grams/hr
0 31 grams/hr
<0 0082 grams/hr
35 grams/hr
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                      50

-------
                                            Bridgeport Refinery and Oil Service Superfund Site
                OBSERVATIONS AND LESSONS LEARNED (CONT.)
                            Table 4 Operating Parameters [2]
?Jfli;-;- IS
Dioxins and Furans
Benzene
Carbon Tetrachlonde
Chloroform
Ethylene Dichlonde
1 ,1 ,2,2-Chloroethane
Tetrachloroethylene
1 ,1 ,2-Trichloroethane
Trichloroethylene
Dioxane
Ethylene Amine
Ethylene Dibromide
•jCt-fr ^..,\ »^*.v r- ^pjip^Slj; _ '8£|£si5 '; = s
*& ^v^^^m^^ v»
0 000045 grams/hr
109grams/hr
4 5 grams/hr
1 4 grams/hr
0 14 grams/hr
0 0045 grams/hr
3 6 grams/hr
0 045 grams/hr
0 91 grams/hr
0 045 grams/hr
0 045 grams/hr
0 045 grams/hr
•$
NA
NA
0049
NA
NA
NA
NA
NA
NA
NA
NA
NA
                            TREATMENT SYSTEM COST
No information was available on the costs of on-site incineration at the Bridgeport site
                     OBSERVATIONS AND LESSONS LEARNED
Observations and Lessons Learned

   Significant difficulty was encountered
   excavating material from below the water
   table because of debris and structural
   instability of soils at the lagoon bottom
   Large cranes with excavating buckets and
   an amphibious excavator were employed in
   addition to the barge-mounted, hydraulic
   dredge originally planned

•  Passage of heavy equipment over the site
   resulted in an oily material rising from
   underground up to the surface  Where this
   oily material surfaced, approximately 230
   cubic yards of soil were excavated and
   incinerated The resulting holes were
   backfilled with clean material from an
   off-site source
The sediment excavated from the
lagoon could not be dewatered as
originally anticipated  The sediment
was an emulsified mixture of soil, water,
and oil, and was difficult to demulsify
Sedimentation in ponds, flocculation
with polymers, screening, and
centrifugation were all attempted but did
not show satisfactory separation of
water In addition, the properties of the
sludge varied significantly  Ponds
initially constructed for dewatermg of
sludge were used to mix the sludge to
achieve some homogenization prior to
incineration
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          51

-------
                                            Bridgeport Refinery and Oil Service Superfund Site
                OBSERVATIONS AND LESSONS LEARNED (CONT.)
    Debns in the sediment caused problems
    and delays and made excavation of material
    more difficult than anticipated  Intact
    drums, large and unshreddable pieces of
    debris, and a large amount of municipal
    solid waste discovered during excavation of
    the lagoon were disposed off site In
    addition, special handling was required of
    some intact drums that were found to
    contain sulfunc acid

    The incinerator experienced a number of
    mechanical difficulties, including jams in the
    feed auger, jams in the incinerator ash
    auger, failure of the ash removal system at
    the ash quench, overpressunzation of the
    kiln, induced draft fan failures, loss of boiler
water, slag build-up in the kiln and
secondary combustion chamber, and
excursions outside permitted operating
parameters These problems resulted
in reduced performance and down time

On one occasion, a release of ash to
the atmosphere occurred when a slide
gate became disengaged from the
cyclone

Incineration was suspended in order to
conduct repairs from February to April
1995 and again from July to August
1995
                                    REFERENCES
1.   ENSCO MWP-2001. Trial Burn Report.
     March 12 through April 7.1991  ENSCO,
     Inc. July 18,1991

2    Operable Unit Remedial Action Report.
     Laaoon and Protect Site Cleanup.
     Bridgeport Rental and Oil Services Site
     U S EPA Region II Undated

3.   Remedial Action Update. Bridgeport Rental
     and Oil Services  U S EPA Region  II
     Februarys, 1996
 Superfund Record of Decision.
 Bridgeport Rental and Oil Services
 Site, Logan Township, New Jersey,
 December 31, 1984

 USEPA National Priorities List.
 Bridgeport Rental and Oil Services
 Fact Sheet  US EPA, August 1996
U.S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          52

-------
                     On-Site Incineration at the
  Celanese Corporation Shelby Fiber Operations Superfund Site
                      Shelby, North Carolina
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                 53

-------
                Incineration at the Celanese Superf und Site
                             Shelby, North Carolina
  Site Name:
  Celanese Superfund Site
  Location:
  Shelby, North Carolina
Contaminants
Ethylene glycol, volatile organic
compounds, metals,
polynuclear aromatic
hydrocarbons, and phenol
• Trichloroethylene, benzene,
  phenols, lead, chromium, and
  antimony
• Maximum concentrations of
  ethylene glycol (12,000
  mg/kg) antimony (3,000
  mg/kg), lead (2,041 mg/kg)
  and chromium (40 mg/kg)
Period of Operation
April 1991 to December
1991
Cleanup Type
Remedial action
  Vendor:
  Terry Elmaggar
  GDC Engmeenng, Inc
  822 Neosho Avenue
  Baton Rouge, LA 70802
  (504) 383-8556
  SIC Code:
  2824 (Manufacturing manmade
  organic fibers)
Technology:
On-Site Incineration
• Solids pretreated with
  screening and mixing with
  sawdust
• Incineration system consisting
  of rotary kiln and secondary
  combustion chamber (SCC)
• Soil residence time of 45
  minutes, kiln temperature of
  1,500°F,  SCC temperature of
  1,900°F
• Treated soil and sludge
  (incineration ash) discharged
  into a wet ash collection
  system	
Cleanup Authority
CERCLA and State North
Carolina
• ROD Date  3/28/89
• PRP-Lead
Point of Contact
McKenzie Mallary
U S EPA Region 4
Atlanta Federal Center
100 Alabama Street
Atlanta, GA 30303-3104
(404) 562-8802
  Waste Source:
  Disposal of waste sludges
  Purpose/Significance of
  Application:
  Lowest volume incinerated for
  all of the case studies
Type/Quantity of Media Treated
Sludge and Soil
• 4,660 tons of sludge and soil
• Moisture content sludge - 25%
  Regulatory Requirements/Cleanup Goals
  • Destruction and Removal Efficiency (ORE) of 99 99% for each constituent of concern as
   required by Resource Conservation and Recovery Act (RCRA) incinerator regulations in 40
   CFR part 264, subpart O	
  Results:
  • Emissions and trial burn data indicate that all ORE and emission standards were met
  » Analytical data of residuals indicate that cleanup goals were met	
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          54

-------
                Incineration at the Celanese Superfund Site
                             Shelby, North Carolina
                                     (Continued)
  Description
  The site began operation in April 1960 and is still operating Between 1960 and the early 1980s,
  plant wastes from the production of polyester raw-material were disposed of in burn pits and
  sludge was buried in trenches  Between 1970 and 1978, drums of waste chemicals and solvents
  were stored on site  A site investigation was conducted in 1981  A Record of Decision (ROD),
  signed in March 1989, specified on-site incineration as the remediation technology for the
  excavated sludge and soil  Site cleanup goals and ORE standards of 99 99% for constituents of
  concern were specified in the ROD

  On-site incineration began in April  1991  During its period of operation, the incinerator processed
  4,660 tons of sludge and soil  The treatment system consisted of a rotary kiln and an SCC An
  enclosed conveyor moved the soil  and debris to the kiln for treatment Treated ash from the
  incinerator was discharged to a wet ash collection system  The system used an air pollution
  control system that consisted of a baghouse and a packed-bed scrubber Incineration achieved
  the soil cleanup goals specified in the ROD

  The total cost of the  remedial action was approximately $5,800,000, including $3,925,000 in
  capital costs and $1,875,000 m operation and maintenance costs
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          55

-------
                                                          Celanese Corporation Superfund Site
                                 EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site incineration at the
Celanese Corporation Shelby Fiber Operations
(Celanese) Superfund site in Shelby, North
Carolina  A rotary kiln incinerator was operated
from April  1991 through December 1991 as part
of a remedial action Contaminants of concern
at the site were trichloroethyiene (TCE),
benzene, phenols, polynuclear aromatic
hydrocarbons (PAHs), lead, chromium, ethylene
giycol, and antimony

The Celanese site is a polyester raw-material
production facility that began operation in April
1960 Between 1960 and the early 1980s,
various wastes were stored and disposed of on-
site in unlmed pits and trenches  In March
1988, a Record of Decision (ROD) for Operable
Unit 1 (OU-1) was signed that required
treatment of contaminated groundwater

In March 1989, a ROD for OU-2 was signed
The remedial actions for OU-2 included the
excavation and incineration of Giycoi  Recovery
Unit (GRU) sludges and associated soil; and the
excavation, solidification, and disposal of plastic
chips, burn pit residuals,  and stream sediments
The remainder of this report will address the
incineration specified in OU-2, unless otherwise
stated

The ROD specified the excavation and
incineration of approximately 1,500 cubic yards
of GRU sludge plus an additional foot of soil
below the sludge/soil interface  The ROD also
specified incinerator requirements that included
a destruction and removal efficiency (ORE) of
99 99% for each constituent of concern

The selected incineration system consisted of a
feed system, a rotary kiln, a secondary
combustion chamber (SCC) and an air pollution
control system (APCS) [2]
Before entering the feed system, waste
sludge and soil were mixed with sawdust to
facilitate materials handling  The mixture
passed through a separator to remove any
pieces of metal, then was conveyed to a
weigh hopper, and finally to the kiln

The kiln used at the Celanese site was lined
with refractory brick  The rotary kiln
volatilized and  partially destroyed organic
compounds from the contaminated  material
Ash generated  in the incinerator was
collected in a wet ash collection system and
conveyed out of the system for solidification
and disposal, while exhaust gases were
drawn into the SCC  The SCC provided
further combustion of organics in the off-
gases which were then quenched with
water

The APCS consisted of a baghouse and a
packed-bed scrubber Particulate removal
occurred in the baghouse, and gas polishing
and acid neutralization occurred in the
scrubber

During the nine months of operation, the
incinerator processed 4,660 tons of GRU
sludge and associated soil [2]  During
excavation, several drums containing a tar-
like substance were found  The drum
contents also were incinerated  Treatment
performance and emissions data collected
during this application indicated that all
performance standards and emissions
requirements were met

The actual cost for remediation using the
incineration system was approximately
$5,800,000,  consisting of $3,925,000 in
capital costs and $1,875,000 in operation
and maintenance costs
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            56

-------
                                                        Ce/anese Corporation Superfunof Site
                                 SITE INFORMATION
Identifying Information
Celanese Corporation Shelby Fiber Operations
Superfund Site, Shelby, North Carolina

CERCLIS # NCD003446721

OU-2 ROD Date- March 28, 1989
Background

Historical Activity that Generated
Contamination at the Site: Manufacturing of
polyester polymer resin and filament yarn

Corresponding SIC Code: 2824 (Organic
Fibers)

Waste Management Practice That
Contributed to Contamination Storage and
land disposal of wastes generated from the
manufacturing process

Site History

    The Celanese Corporation Superfund site is
    located on the 469-acre property of an
    operating polyester raw-material production
    facility in south central Cleveland County
    The site began operation in April 1960

•   Between 1960 and the early 1980s, plant
    wastes were disposed of in burn pits and
    GRU sludge was buried in trenches
    Between 1970 and 1978, drums of waste
    chemicals and solvents were stored on site

•   The primary contaminants of concern in the
    soil and sludges were ethylene glycol,
    volatile organic compounds (VOCs)
    including TCE and benzene, phenols, PAHs,
    and metals including lead, chromium, and
    antimony
Treatment Application

Type of action- Remedial (on-site
incineration)

Period of incinerator operation  April
1991 - December 1991

Quantity of material treated during
application  4,660 tons of GRU sludge and
associated soil incinerated
   A site investigation was conducted in
   1981 and a Remedial Investigation (Rl)
   was completed in June 1986  A
   Feasibility Study (FS) for OU-1 was
   completed in February 1988, and the
   FS for OU-2 was completed in April
   1989

   Remedial action related to the GRU
   sludge and associated soil (waste)
   began in January 1991 when the
   responsible party (RP) began
   excavating the waste Beginning in
   April 1991, a rotary kiln incinerator was
   used to  remediate the excavated waste

   A period of optimization was followed by
   a mini-burn and then a trial burn  The
   mini-burn was conducted in April 1991
   to provide enough data for tentative
   approval from EPA  The trial burn was
   conducted in June 1991

   Approximately 4,660 tons of waste were
   processed between April  1991 and
   December 1991  By August of 1992, all
   remediation activities for OU-2 were
   complete
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           57

-------
                                                       Celanese Corporation Superfund Site
                            SITE INFORMATION (CONT[)
Background (Cont)

Regulatory Context:

•   In June 1986, the Celanese Corporation
    site was placed on the National Priorities
    List (NPL)

•   A ROD was signed in March 1989,
    specifying a remedial action that included
    excavation and on-site incineration to
    reduce the concentration of chemical
    contaminants at the site  Ground water
    remediation was addressed by OU-1, and
    source remediation was addressed by
    OU-2

•   The selected remedy was conducted
    under the provisions of the
    Comprehensive Environmental Response,
    Compensation,
   and Liability Act of 1980 (CERCLA), as
   amended by the Superfund Amendments
   and Reauthonzation Act (SARA) of 1986
   and the National Oil and Hazardous
   Substances Contingency Plan in 40 CFR
   part 300 [1]

•  The DREs were set in accordance with
   Resource Conservation and Recovery Act
   (RCRA) incinerator regulations in 40 CFR
   part 264, subpart O

Remedy Selection: On-site rotary kiln
incineration was selected as the remedy for
contaminated soil and sludge at the Celanese
Superfund site based on the results of the
RI/FS and long-term economic considerations
Timeline
                                  Table 1  Timeline [21
\* 	 , 	 Date,
Apnl 1960 - Ongoing
1981
June 1986
June 1986 - Apnl 1989
March 28, 1989
April 1991
June 1991
January 1991 - March 1992
April 1991 - December
1991
March 1992 - August 1992
^ ,._^£^ ,^ ,"' '&**•
The facility on the Celanese site is in operation
Initial site investigation
Site placed on the NPL
Remedial Investigation/Feasibility Study
Record of Decision for OU-2 signed
Mini Burn
Trial Burn
GRU sludge and soil are excavated for incineration and/or solidification
Rotary kiln incinerator operational
Decontamination and demobilization of the incinerator
Site Logistics/Contacts

Site Management:  RP-Lead

Oversight: EPA

Remedial Project Manager
McKenzie Mallary
US EPA Region 4
Atlanta Federal Center
100 Alabama Street, S W
Atlanta, GA 30303-3104
(404) 562-8802
  Treatment System Vendor
  Terry Elmaggar
  GDC Engineering, Inc
  822 Neosho Avenue
  Baton Rouge, LA 70802
  (504) 383-8556
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          58

-------
                                                       Celanese Corporation Superfund Site
                               MATRIX DESCRIPTION
Matrix Identification

Type of Matrix Processed
Through the Treatment System

•   GRU sludges and associated soil were
    excavated  Metal was removed, solidified
    and disposed on site The sludge and soil
    were mixed with sawdust prior to
    incineration

Contaminant Characterization

Primary Contaminant Groups: Ethylene
glycol, VOCs, metals, PAHs, and phenol

•   The contaminants of greatest concern were
    VOCs (including TCE and benzene),
    phenols, PAHs, lead, chromium, and
    antimony

•   Waste feed samples were collected and the
    concentrations of ethylene glycol and total
    antimony were measured The average
   concentration of ethylene glycol was
   1,740 mg/kg with a range of 43 to
   12,000 mg/kg  The average
   concentration of antimony was 694
   mg/kg with a range of 190 to 3,000
   mg/kg [2]  The maximum GRU sludge
   concentrations for lead and chromium
   were 53 mg/kg  and 40 mg/kg,
   respectively The maximum
   concentration of lead in the soil was
   2,041 mg/kg
Matrix Characteristics Affecting Treatment Cost or Performance

The major matrix characteristics that most significantly affected cost or performance at the site and
their measured values are presented in Table 2

                              Table 2  Matrix Characteristics
'.^ '**Ctf:' -v? f?aramet«e ^ ';: - T±
Sludge Classification
Sludge Moisture Content
Average Upper Heating Value of Sludge
^ ^-- T^j £< -$hie ^ ^ ff ';; "£.;•*{',
Mixture of semi-viscous sludge and dry, hard material
25%
5,400 BTU/lb
                        TREATMENT SYSTEM DESCRIPTION
Primary Treatment Technology

Rotary kiln incineration including

•   Rotary kiln,
•   Secondary combustion chamber, and
•   Quench duct
Supplemental Treatment Technology

Pretreatment (solids) Mixed with sawdust
and screened

Air pollution control system including

•   Baghouse, and
    Packed bed scrubber system

Post-Treatment (water)  Neutralization
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          59

-------
                                                         Celanese Corporation Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
System Description and Operation

•  The rotary kiln incineration system
   employed at the Celanese site consisted of
   two chambers (the kiln itself and a
   secondary combustion chamber) and an air
   pollution control system consisting of a
   baghouse and a packed-bed scrubber
   system

•  Overburden material at the site (those
   matenals not collected for incineration
   and/or solidification) were removed and
   stockpiled  The GRU sludges and soil were
   mixed with sawdust in a pugmill to facilitate
   material handling  The waste feed was
   screened before being fed to the rotary kiln
   by a feed screw

•  The kiln had a length of 45 feet and an inner
   diameter of 6Vz feet  The kiln was lined with
   refractory bnck rotating on a slight incline (2
   degrees)

-  The kiln was rated at 20 MBTU/hr The kiln
   rotated at a maximum  rate of 0 98
   revolutions per minute

•  Residual ash from the  kiln was collected in
   a wet ash collection system and was
   solidified with 15 to 20 percent Portland
   cement and then used for backfill
  Flue gases from the kiln were routed to
  the SCC for additional combustion of
  volatilized contaminants The SCC
  operated at approximately 1,900°F and
  an average percent oxygen between 4
  and 8 percent

  The exhaust gas from the SCC was
  channeled through the quench duct and
  then to the system's baghouse  The
  design operating condition exit
  temperature for the baghouse was
  approximately 350° F

  Combustion gases were drawn through
  the kiln system and baghouse by an
  induced draft fan (resulting in a constant
  negative pressure throughout the
  system) and were exhausted through a
  69-foot reinforced concrete stack
  Typical stack gas velocity was between
  1,143 and 1,750 feet per second and
  the typical stack exit temperature was
  below 180°F

  Scrubber water effluent was treated by
  an on-site neutralization system
                         Table 3  Summary of Operating Parameters
II"1'1 	 " 	 » 	 i 	 "" 	 " 	 >» •> 	 Parameter 	 ' J*^
Residence Time
System Throughput
Kiln Temperature
~~ '%&".*&*' J?**"
45 minutes
2 3 tons/hour
1,500°F
Cleanup Goals/Standards
    The required ORE was 99 99% for each
    constituent of concern

    The OU-2 ROD originally established a
    remedial action that included excavation
    and incineration of approximately 1,500
    cubic yards of GRU sludge plus an
    additional foot of soil below the sludge/soil
    interface  Other wastes and sediments
    excavated on site were to be solidified
    and disposed of on site
Waste was excavated to the visual
sludge/soil interface and an attempt was
made to excavate to an additional one
foot below the sludge/soil interface [2]
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           60

-------
                                                         Ce/anese Corporation Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
•   Due to the hardness of the clay and
    bedrock beneath the GRU sludge, the
    removal of an additional one foot of soil
    was not always possible

•   Sampling was not performed in the
    excavated pits because the intent of the
    remediation was not to provide
    cleanclosure  The groundwater treatment
    system was expected to treat any
    remaining contaminants [2]

Treatment Performance and Compliance
                             Residual ash was solidified and disposed
                             of on site  The maximum allowable
                             ethylene glycol concentration for all
                             material
   A trial burn conducted at the Celanese
   Corporation site was designed to operate
   the incineration system at conditions that
   would reflect worst-case destruction and
   removal of all constituents of concern

   Tetrachloroethene was selected as the
   POHC for the Celanese Corporation site
   Naphthalene was initially chosen as the
   POHC, but problems occurred with cross
   contamination The calculated ORE for
   tetrachloroethene is shown in Table 4
                             The incinerator operated within the
                             operating limits established during the trial
                             burn, signifying that all cleanup
                             requirements were met  The limits
                             established for the AWFCOs are shown in
                             Table 5  Information on the frequency of
                             AWFCOs was not available  Trial burn
                             and typical operating parameters are
                             shown in Table 6

                             The residual ash was sampled and
                             analyzed for ethylene glycol and toxicity
                             characteristic leaching procedure  metals

                             Workers were required to maintain level D
                             protection through the remedial action
         Table 4  Average Destruction and Removal Efficiencies from Compliance Testing
           ant
                 Average Cor^arriin
              Werage Contaminant
               in $taek Gas Emissions
                   ""         '
 Tetrachloroethene
8,163
00415
NA
99 9995
                          Table 5  Automatic Waste Feed Cutoffs {21
It- -J """ ,.;i-;-.,x
Minimum Secondary Combustion Chamber Oxygen
Maximum CO (rolling average)
Minimum Primary Combustion Chamber Temperature
Minimum Secondary Combustion Chamber Temperature
Minimum Scrubber pH
Maximum System Draft
Minimum Baghouse Differential Pressure *
Minimum Stack Velocity
sit f8*^ O $5»8fti«S &. * ^:n r? '•'"
3 0% O2
SOppm
1430°F
1840°F
65
-0 1 inch in w c
4 0 inch H2O
1750 feet/mm
we = Water column
* Note  Limit for baghouse differential pressure not activated until 6 hours after incinerator start-up
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           61

-------
                                                        Celanese Corporation Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
                             Table 6  Operating Parameters 121
| ' < Parameter
Contaminated Soil Feed Rate
Primary Combustion Chamber Temperature
Secondary Combustion Chamber Temperature
Averags percent oxygen in secondary chamber
Kiln draft average
Baghouse pressure drop average
CO emissions
Percent oxygen In stack
Percent carbon dioxide average
Scrubber pH

2 5 tons/hr
1,487°F
1,880°F
5 07%
-0 17 in we
4 76 in w c
NA
NA
NA
92
	 ?%&%,, ... %%? i^i^ii^g^
BorwJtfaius^liil
immT ^» lliP?
2 5 tons/hr
1,500°F
1,850°F
4 3% to 7 8%
-0 19to-02l in we
275to724inwc
0 5 ppm to 3 4 ppm
11 7% to 130%
4 8% to 6 8%
3 7 to 101
we = Water column
•Proposed operating parameters based on the results of the trial bum

Performance Data Available

•  Verification sampling was not performed on
   excavated pits because clean closure was
   not the intent of the remediation for OU-2
   [2]

•  Initial contaminant concentrations are
   included in the RI/FS and the Treatabihty
   Study Investigation
For each day the incinerator was
operating, one incinerator ash sample
was analyzed for total ethylene glycol
Excluding mini-burn and trial burn
samples, 137 samples were taken  Of
the 137 samples taken, only three
samples had ethylene glycol
concentrations above the detection limit
of 10 mg/kg  The concentrations of
those samples were 31, 47, and 10
mg/kg [2]
Performance Data Quality

•   The Quality Assurance/Quality Control
    (QA/QC) program used throughout the
    remedial action met the EPA and the State
    of North Carolina requirements  All QA
    auditing and monitoring were performed by
    SEC Donohue and RP personnel [2]
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          62

-------
                                                       Celanese Corporation Superfund Site
                            TREATMENT SYSTEM COST
Procurement Process

•  The RP contracted with SEC Donohue to
   develop the remedial design and oversee
   the remedial work The RP also retained
   GDC Engineering, Inc to conduct the
   remedial work
Cost Data
   The cost of incineration at the Celanese
   Corporation site was reported as
   $5,300,000 The capital costs for the
   incineration system were $3,425,000 and
   operations and maintenance (thermal
   treatment) costs totaled $1,875,000 A
   total of 4,660 tons of soil and sludge were
   incinerated This corresponds to a total
   unit cost of $1,000 per ton, and a unit cost
   for thermal treatment of $410 per ton
                                Table 7  Capital Costs [6]

331
331
331
331
331
331
331
331
331

01
01
01
02
02
02
02
03
03

01
02
03
03
05
06
09
03
05

,?•".. /r^" .V ^-~ -f
Mobilization of construction equipment and facilities
Mobilization of personnel
Submittals/implementation plans
Air monitonng and sampling
Sampling surface and groundwater
Sampling soil and sediment
Laboratory chemical analysis
Earthwork (i e , excavating, stock piling)
Fencing
Incineration equipment
Trial bum
Set up/construct temporary facilities
Total Capital Costs
;'* ;'f %Cos*£'4<> -''
$100,000
$50,000
$250,000
$300,000
$500,000
$25,000
$2,000,000
$100,000
$100,000
$3,425,000
                       Table 8 Operation and Maintenance Costs [6]
•^'/-
342
14
T* J- ™^&,t&MeS& *" .?, •' ";; •
i •*?»§&• •* , , , «•?«.•"• ^-as«' ^ s f#*>£> •— * f
Thermal treatment
• Labor
• Direct operating cost
• Permitting
• Overhead
Total Operation and Maintenance Costs
-- ,-- ^ Cost, >*_ , ^
$750,000
$750,000
$25,000
$350,000
$1,875,000
Cost Data Quality

•   Cost data was provided by Hoechst Celanese
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          63

-------
                                                        Celanese Corporation Superfund Site
                      OBSERVATIONS AND LESSONS;|_EARNED
Cost Observations and Lessons Learned

•   In relation to off-site incineration, on-site
    incineration is most economical with large
    volumes of waste  Because the amount
    incinerated at Celanese was comparatively
    not very large, off-site incineration would
    have been more economical

Other Observations and Lessons Learned
•   The initial estimate of 1,500 cubic yards of
    GRU sludge and 500 cubic yards of soil was
    exceeded  The treatment performance data
    indicate that the incinerator processed 4,549
    tons of sludge, 111 tons of soil, and 1,200
    tons of sawdust [2]

    Initially, clay in the waste feed was collecting
    on the walls of the kiln resulting in a reduction
    in throughput  This was remedied by mixing
    the waste with sawdust and optimizing the
    waste feed rate

•   Initially, problems occurred with naphthalene,
    the first POHC, cross contaminating the
    blanks In response, naphthalene was
    replaced with tetrachloroethene

Public Involvement	
    Weekly field reports identified difficulty
    with the feed screw as the cause of
    many AWFCOs  Other AWFCOs were
    caused by loss of burner flame in the
    kiln and SCC caused by a faulty relay,
    weigh cells around the line hopper
    failing to operate properly, and quench
    nozzles breaking  The actual number
    of AWFCOs was not included in these
    reports
    Citizens of the Earl/Shelby area expressed
    interest in the remediation of the Celanese
    Corporation site The group, The United
    Neighbors for cleanup at Earl, was formed
    because of concerns about the quality of
    water in their area
    At public meetings conducted by EPA,
    the community favored remedial action,
    but few citizens expressed a preference
    for a particular process [1]
                                    REFERENCES
1   Superfund Record of Decision Operable Unit
    2, Celanese Corporation Shelby Fiber
    Operations, Shelby, North Carolina, March
    1989

2.  Remedial Action Report Operable Unit 2
    Remedial Action. Celanese Shelby Fiber
    Operations Superfund Site. SEC Donohue,
    June 1993

3   Personal communication with Susan
    Schrader, Tetra Tech EM, Inc , Denver,
    August?, 1997
4   Personal communication with Terry
    Elmaggar, GDC engineering, July 16,
    1997

5   Trial Burn Report Operable Unit 2
    Hoechst Celanese. Westmghouse
    Environmental and Geotechnical
    Services, Inc , August 30,1991

6   Personal communication with Jeff
    Randolph  Hoechst Celanese, June
    1997
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           64

-------
On-Site Incineration at the
Coal Creek Superfund Site
  Chehalis, Washington
           65

-------
             Incineration at the Coal Creek Superf und Site
                           Chehalis, Washington
Site Name:
Coal Creek Superfund Site
Location:
Chehahs, Washington
Contaminants:
Polychlormated biphenyls and
lead Also other metals,
including
    lead
    copper
    barium
    mercury
    cadmium
    zinc
Period of Operation
January 1994 to May 1994
Cleanup Type
Remedial action
Vendor:
Matthew Beatty
Roy F Weston, Inc
1 Weston Way
West Chester, PA 19380-1499
610-692-3030
SIC Code:
4953 (Refuse Systems)
Technology
On-Site Incineration
•  Soil screened prior to being
   fed to incinerator
•  Incineration system
   consisting of a rotary kiln
   and a secondary
   combustion chamber (SCC)
•  SCC system temperature of
   2,100 °F, gas from SCC
   cooled by water sprays
   before being sent through
   air pollution control system
•  Process water was treated
   by carbon filtration system
   then discharged on-site
Cleanup Authority:
CERCLA
•  ROD signed October
   1990
•  Consent Decree entered
   1992
•  RP-lead with EPA
   oversight
Point of Contact
Bob Kievit
US EPA Region 10
1200 Sixth Avenue
Seattle, WA 98101
360-753-9014
Waste Source:
Disposal areas - oil containing
PCBs
Type/Quantity of Media Treated
Soil (9,715 tons)
Purpose/Significance of
Application:
Because of previous
performance, and because it
had a TSCA permit, the
incinerator was allowed to
demonstrate ORE compliance
without spiking
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (ORE) of 99 9999% for PCBs as required by Toxic
  Substances Control Act (TSCA) regulations in 40 CFR part 761
                                       66

-------
             Incineration at the Coal Creek Superfund Site
                            Chehalis, Washington
                                   (Continued)


Results:
• Emissions and performance data indicated that all ORE and emission standards were met


Description:
Between 1949 and 1983, the Coal Creek site was used for scrapping, salvaging, and repairing
electrical equipment  During this time, oil containing PCBs was drained on to the ground

In October 1990, a Record of Decision (ROD) was signed, specifying excavation and on-site
incineration of soil with greater than 50 mg/kg PCBs  In 1992, the responsible parties (RP)
entered into a Consent Decree with EPA, agreeing to implement the remedial action described by
the ROD

Remedial Action began in January 1994 The incineration system consisted of a feed system, a
rotary kiln, a secondary combustion chamber (SCC), and an air pollution control system  (APCS)
The soil was screened before being fed to the incinerator Over a 5-month period, the incinerator
processed approximately 9,700 tons of soil Treatment performance and emissions data
collected during this application indicated that all performance standards and emissions
requirements were met

The actual cost for remediation using the incineration system was approximately $8,100,000
                                        67

-------
                                                                  Coal Creek Superfund Site
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site incineration at the
Coal Creek Superfund Site in Chehalis,
Washington  A rotary kiln incinerator was
operated from January 1994 to May 1994 as
part of a remedial action Contaminants of
concern at the site included polychlormated
biphenyls (PCB) and lead

The Coal Creek site was used for scrapping,
salvaging, and repairing electrical equipment
from 1949 to 1983  During this time, oil
containing PCBs was drained on to the ground
Concentrations of PCBs were measured as high
as 21,000 mg/kg at the site

In October 1990,  a Record of Decision (ROD)
was signed, specifying excavation and on-site
incineration of soil with greater than 50 mg/kg
PCBs  The ROD also required a destruction
and removal efficiency (ORE) of 99 9999% for
the  incineration  In 1992, the responsible
parties (RP) entered into a Consent Decree with
EPA, agreeing to implement the remedial action
descnbed by the ROD

The incineration system consisted of a feed
system, a rotary kiln, a secondary combustion
chamber (SCC), and an air pollution control
system (APCS) The soil was screened before
being  fed to the incinerator
      In the rotary kiln, organic compounds from
      the contaminated soil were volatilized and
      destroyed  The resulting ash was
      discharged from the kiln and quenched
      outside of the kiln, while exhaust gases
      were routed to the SCC  The SCC provided
      further combustion of PCBs in the off-gas,
      which was then quenched with water

      The APCS consisted of a baghouse and a
      scrubber, which removed particulate and
      acid gas, respectively

      Over a 5-month period, the incinerator
      processed approximately 9,700 tons of soil
      Treatment performance and emissions data
      collected during this application indicated
      that all performance standards and
      emissions requirements were met

      The actual cost for remediation using the
      incineration system was approximately
      $8,100,000
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
68

-------
                                                                   Coal Creek Superfund Site
                                  SITE INFORMATION
Identifying Information

Coal Creek Superfund Site
Chehalis, Washington

CERCLIS # WAD980726061

ROD Date- October 17,1990
Background

Historical Activity that Generated
Contamination at the Site  Scrapping,
salvaging, and repairing electrical equipment

Corresponding SIC Code:  4953 (Refuse
Systems)

Waste Management Practice That
Contributed to Contamination- Improper
storage and disposal of waste

Site History

•   The site is approximately one mile north of
    Chehalis and covers approximately 8 acres
    in the Coal Creek Valley  The site is bound
    by Coal Creek to the south and west
    Wetlands are present on the western portion
    of the site

•   The first documented use of the site was in
    1935 when it was occupied by a coal-fired
    electrical generating plant   From 1949 to
    1983, the site was used for scrapping,
    salvaging, and repairing electrical
    equipment, including electrical transformers

»   One prominent feature in the northeast
    corner of the site was a mound of fill
    material, which covered one-fourth of the
    site The mound was comprised of two to
    eight feet of fill material including soil, ash,
    coal, and mixed debris from transformer
    scrapping operations  A one-to-two-foot-
    thick sand and gravel cover was placed
    over the fill as a working surface for vehicle
    access during facility operation
      Treatment Application

      Type of action  Remedial (on-site rotary
      kiln incineration)

      Period of operation: January 1994 - May
      1994

      Quantity of material treated during
      application: 9,715 tons of soil
          A drainage ditch extended from the fill
          mound through the wetland area and
          discharged to Coal Creek

          Oil containing polychlormated biphenyls
          (PCB) from electrical transformers was
          drained on site during the salvage
          operation

          The ROD estimated that 8,300 cubic
          yards of soil contains PCBs at
          concentrations greater than 50 mg/kg

          Beginning in 1979, EPA and the
          Washington State Department of
          Ecology conducted various inspections
          and sampling and analysis of soil and
          groundwater at the site  In 1983 and
          1984, at the request of the state,
          potentially responsible parties (PRP)
          stabilized the site by covering portions
          of the fill mound with plastic, damming
          the drainage ditch, installing ground
          water monitoring wells, and securing the
          site

          A remedial investigation and feasibility
          study (RI/FS) was performed in 1988

          Remedial action took place in two
          phases  Phase I, which began in
          February 1993, included the demolition
          of a two-story concrete building and
          foundation, asbestos abatement,
          demolition of the site drainage system,
          disposal of resulting debris, and
          removal and decontamination of
          underground storage tanks

          Phase II began in August 1993  It
          included excavation and incineration of
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
69

-------
                                                                 Coal Creek Superfund Site
                             SITE INFORMATION (CONT.)
contaminated soil, construction of a containment
cell, disposal of debris, and wetland restoration

•   The erection of the incinerator and
    excavation of soil for incineration were
    completed  in December 1993  The
    performance test burn and incineration
    under interim standards began in January
    1994
          The incineration system processed
          approximately 9,700 tons of soil and
          debris in the four months that it
          operated  Incineration was completed
          in May 1994
Background

•   Various RPs entered into a consent decree
    with EPA in February 1988 EPA and the
    settling defendants entered into a Major
    Consent Decree effective February 1992
    under which the settling defendants agreed
    to design and implement the remedial
    action described in the ROD

•   The ROD was signed in October 1990,
    specifying excavation of soil with greater
    than 1 mg/kg PCBs, incineration of the soil
    with greater than 50 mg/kg, and on-site
    containment of the ash with the soil
    containing 1 to 50 mg/kg PCBs

Regulatory Context:

Remedy Selection The remedial actions
selected were the only response actions planned
for the site  They were intended to address the
principal threats posed by PCBs and other
contaminants
          The site activities were conducted under
          provisions of the Comprehensive
          Environmental Response,
          Compensation, and Liability Act of 1980
          (CERCLA), as amended by the
          Superfund Amendments and
          Reauthonzation Act of 1986 (SARA),
          and the National Contingency Plan
          (NCP) in 40 CFR part 300

          The DREs were set in accordance with
          the Toxic Substance Control Act
          (TSCA) regulations in 40  CFR part 761
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
70

-------
                                                              Coal Creek Superfuncf Site
                           SITE INFORMATION (CONT.)
                                  Table 1  Timeline

Early 1900s -1983
1979
February 1988
1989
October 1990
August 1993 - December 1993
January 1994
January 1994 -May 1994
October 1994
November 1994
Ol" -> -•r,-,, ,V ifJ-A--' Activity/ l'~ '**?"'' £7*TJ^ " i~ -;
Operations performed at the Coal Creek Site
Initial site investigation
Various RPs enter into a Consent Decree to cleanup the site
Remedial Investigation/Feasibility Study
ROD is signed
Contaminated soil is excavated
Performance test bum conducted
Rotary kiln incinerator operational
Containment cell cap seeding and wetland seeding
Final site inspection
Site Logistics/Contacts

Site Management  RP-lead

Oversight- EPA

Remedial Project Manager
Bob Kievit
US EPA Region X
1200 Sixth Avenue
Seattle, WA 98101
(360) 753-9014
      Treatment System Vendor:
      Matthew Beatty
      Roy F Weston, Inc
      1 Weston Way
      West Chester, PA 19380-1499
      (610) 692-3030
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
71

-------
                                                                Coal Creek Superfund Site
                               MATRIX DESCRIPTION
Matrix Identification
Type of Matrix Processed Through the
Treatment System- Contaminated soil from
the mound area

Contaminant Characterization

Primary Contaminant Groups:  PCBs and
metals

•  The contaminants of greatest concern were
   PCBs and lead  Other metals such as
   copper, barium, mercury, cadmium, and
   zinc were also present in soil at the site
         The maximum concentration of PCBs in
         the soil was 21,000 mg/kg  Elevated
         concentrations of copper (31,000
         mg/kg), lead (3,800 mg/kg), barium
         (1,200 mg/kg), mercury (20 mg/kg),
         cadmium (9 mg/kg), and zinc (5,300
         mg/kg) also were detected in the soil
Matrix Characteristics Affecting Treatment Costs or Performance

•   Information on matrix characteristics such
    as soil classification,  moisture content, and
    soil density was not available
                        TREATMENT SYSTEM DESCRIPTION
Primary Treatment Technology

Incineration system including

•   Rotary kiln, and
•   Secondary combustion chamber (SCC)
      Supplemental Treatment Technology

      Pretreatment (solids)  Screened and mixed

      Post-Treatment (air)
      •  Baghouse, and
      •  Scrubber

      Post-Treatment (water)  Carbon adsorption
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
72

-------
                                                                  Coal Creek Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
System Description and Operation

•   Approximately 28,000 tons of granular fill
    was placed at the site to provide a working
    surface around the incineration equipment,
    and also to meet the requirement that the
    incinerator be located outside of the 100-
    year floodplam

•   The site was excavated using a CAT 235
    and a CAT 966 loader  Excavated soil was
    divided into two stockpiles soil with PCB
    concentrations between 1  and 50 mg/kg,
    and soil with PCB Concentrations greater
    than 50 mg/kg  A track loader and three
    wide-track bulldozers were also used when
    soil at the site was wet

    Debris was screened from the soil  At times
    the soil was too wet and cohesive to allow
    debris to be removed by conventional
    screening operations Large debris was
    hand-picked out, corn cob pellets were
    mixed with soil to absorb moisture, and then
    the soil was screened When corn cob
    pellets were not available, wood chips were
    used

•   After feed preparation, the waste was
    loaded into a feed hopper  Screw
    conveyors fed the material to the rotary kiln

•   The incineration system consisted of two
    chambers (the kiln itself and the SCC) and
    an air pollution control system, consisting of
    a baghouse and a scrubber

•   The rotary kiln was 25 feet long and 7 5 feet
    in diameter  The maximum rotational speed
    was 1 2 rpm with a minimum soil residence
    time of 30 minutes  The burner was rated at
    33 million BTU per hour

•   Ash was discharged from  the kiln and
    immersed in water for quenching The ash
    and excavated soil containing 1 to 50 mg/kg
    PCBs were disposed of in waste cells on
    site
          Exhaust gas from the kiln was
          discharged to the SCC and heated to a
          minimum temperature of 2,100°F for at
          least 2 seconds  The SCC was
          vertically oriented to avoid slag buildup
          Gas from the SCC was cooled to 450° F
          using water sprays before being sent
          through the air pollution control system
          (APCS)  Both the kiln and the SCC
          were supplemented with oxygen

          Exhaust gas from the SCC was
          channeled to the baghouse for
          particulate  removal

          The baghouse was rated for a gram
          loading of treated exhaust gases of less
          than or equal to 0 02 grains per dry
          standard cubic foot (dscf) To prevent
          acid condensation in the baghouse, the
          unit was insulated and heat traced
          Special high-temperature, acid-resistant
          coatings also were applied to all interior
          metal surfaces to prevent corrosion

          The gas was then routed to the scrubber
          system where caustic solutions were
          used for neutralization  The gas was
          first quenched to its adiabatic saturation
          temperature before entering the
          fiberglass reinforced polyester scrubber
          The quenched flue gases passed
          through the horizontal-flow packed
          tower, and  finally, through a mist
          eliminator prior to discharge to the
          stack

          Process water was treated by a carbon
          adsorption  system then discharged on
          site

          Combustion gases were drawn through
          the kiln system and baghouse by an
          induced draft fan (resulting in a constant
          negative pressure throughout the
          system) and were exhausted through a
          50-foot stack  Typical flue gas velocity
          was 58 feet per second, and the typical
          stack exit temperature was 187°F
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
73

-------
                                                                Coal Creek Superfund Site
                   TREATMENT SYSTEM DESCRIPTION (CONT.)
Operating Parameters Affecting Treatment Cost or Performance

                         Table 2 Summary of Operating Parameters
pi |n IH 1 1 1 1 1 II l ' -- ^sSi ^"-
j, _ Pnwieter w*.
Retention Tima
System Throughput
Kiln Temperature
^ ,^%,^iivl&*' ~''A <• -,
30 minutes
20,000 Ibs/hr
1, 700° F to 2,000° F
                       TREATMENT SYSTEM PERFORMANCE
Cleanup Goals/Standards

Cleanup goals and standards were specified in
the ROD

•  Soil with a concentration of PCBs greater
   than 50 mg/kg was incinerated

•  Residual ash with a concentration of PCBs
   greater than 50 mg/kg was re-incinerated
   until incineration operations were
   discontinued, then ash with those
   concentrations of PCBs was disposed of off-
   site at a TSCA-approved landfill  Ash with
   concentrations less than 50 mg/kg PCB and
   less than 500 mg/kg lead were backfilled
   into an on-site waste containment cell with
   no additional treatment  Ash with greater
   than 500 mg/kg of lead was stabilized with
   Portland cement prior to backfilling

•  The ROD required treatment standards that
   corresponded with a 1 x 10s excess lifetime
   cancer risk level
         The ROD specified a 99 9999% ORE
         The incineration system at Coal Creek
         had a history of acceptable performance
         and had demonstrated a ORE of greater
         than 99 9999% in nine previous
         performance tests In addition, the
         concentration of PCBs was so low a trial
         burn would have required spiking in
         order to demonstrate compliance  For
         these reasons, EPA did not require a
         trial burn  In lieu of a trial burn, ORE
         calculations for PCBs were performed
         during operation of the system  EPA
         agreed to take into account the
         limitations on data evaluation (analytical
         and statistical confidence  levels) posed
         by the low concentrations of PCBs in
         the feed soil   A performance burn was
         conducted to demonstrate that the
         incinerator could meet the minimum
         requirements
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
74

-------
                                                                  Coal Creek Superfund Site
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
Treatment Performance and Compliance

«   An extensive sampling program was
    implemented during the performance burn
    which included collecting and analyzing
    samples from feed soil, treated soil, spray
    tower fly ash, fabric filter fly ash, scrubber
    blowdown, and stack gases EPA
    determined that the unit was capable of
    meeting the incineration requirements and
    approved full-scale operation  Operating
    conditions were based on the operating
    limits developed during the performance
    burn

•   The AWFCOs could be triggered by
    incinerator monitors or the  CEMs The
    AWFCOs limits are shown  in Table 4
    Information about the frequency of
    AWFCOs was not available Values for trial
    burn operating parameters are shown in
    Table 5, information about  actual values for
    these parameters was not available  The
    incinerator at Coal Creek operated within
    the operating limits established during the
    performance burn, signifying that all
    cleanup requirements established in the
    ROD were met

•   The residual ash was analyzed for PCBs,
    2,3,7,8-tetrachlorodibenzo-p-dioxm(TCDD),
    and for metals using the Toxicity
    Characteristic Leaching Procedure (TCLP)
    Samples for TCDD equivalents were
    analyzed during the performance test The
    results of this analysis demonstrated that
    the performance criteria would be met by
    the incinerator, and TCDD  testing was not
    required after the performance test

•   Final disposal was determined based on
    analysis of PCBs and metals  Ash with
    greater than 50 mg/kg PCBs was
    reprocessed through the treatment system
    Ash that was below 50 mg/kg PCBs and 500
    mg/kg lead was placed in on-site waste
    containment cell without additional
    treatment  Ash that contained more than
    500 mg/kg lead was stabilized by mixing
    with Portland cement prior  to being
    backfilled in the waste cell
          An ambient air monitoring program was
          implemented at the site to document
          ambient air quality before, during, and
          after remedial activities  The
          monitoring program was designed to
          identify the most likely airborne
          migration directions and to collect data
          usmgreal-time particulate monitors and
          time-integrated ambient air sampling
          methods  Nine air monitoring stations
          were set up around the perimeter of the
          site The stations collected samples to
          determine airborne concentrations of
          PCBs, mhalable particulate matter of 10
          microns diameter or less (PM10), and
          PM10 lead

          Action levels were developed for
          airborne concentrations of PCBs (0 95
          ug/m3), PM10 (75 ug/m3), and PM10-lead
          (0 75 ug/m3)  Exceedance of the action
          levels required implementation of dust
          suppression techniques  Weekly air
          monitoring reports were prepared by
          Weston during major excavation,
          incineration, and backfilling operations

          The airborne concentrations of PCBs
          and PM10 lead were below site-specific
          action levels  during the Phase II
          remedial action activities  The action
          level for PM10 was exceeded on one
          occasion  The cause of this
          exceedance was thought to be
          backfilling operations  Additional dust
          control  measures (e g , use of  sprayers,
          ceasing backfilling operations on windy
          days) were instituted after the elevated
          level was recorded  The action level
          was not exceeded for the remainder of
          the remedial  action
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
75

-------
                                                                Coal Creek Superfund Site
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
         Table 3  Average Destruction and Removal Efficiencies from Compliance Testing
	"rii"1,,' '»	
   Contaminant
                  Average Contaminant
                 Feed Rate In Soli (Ib/hr)
         Average Contaminant Rate In
         Stack Gas Emissions (Ib/hr)
 PCS
453
                                         2 66x10"6
NA
99 99994
                          Table 4 Automatic Waste Feed Cutoffs
|,i Parameter
Maximum waste feed rate
Maximum kiln temperature
Minimum kiln temperature
Maximum SCO temperature
Maximum baghouse inlet temperature
SCO retention time
Burner in kiln or SCO
Maximum Baghouse pressure drop
Minimum combustion efficiency
Maximum carbon monoxide
Maximum shield pressure
Emergency damper
Minimum scrubber pH
Minimum scrubber pack pressure drop
Minimum scrubber Inlet flow
Minimum SCO excess oxygen
Maximum stack flow rate
^ '" . ' ''r*>
5 1 tons/hr
2,000°F
1,700°F
2,100°F
450°F
2 seconds
flameout
18 inches water gauge
99 9%
100ppm
-000
open
66
2 inches water gauge
158 gallons/minute
3%
1 6,500 acfm
                              Table 5  Operating Parameters
j'ii '»i'''; ' " ' ' 	 i «"' Parameter .. '"*"'
Kiln temperature
Waste feed rate
Baghouse Inlet temperature
Baghouse differential pressure
Scrubber blowdown turbidity
Scrubber pH
Stack flow rate
Scrubber Inlet flow
HCI stack emissions
Partlculate stack emissions
CO (hourly rolling average)
*- ^ ssi^> ' Trial Bdf^KfX^Sl^' ga.' f-'
1,718°F
5 1 tons/hr
411°F
2 73 inches w c
NA
667
15,074 acfm
160gpm
<0 0227 Ibs/hr
<0 00061 Ogr/dscf
nondetect
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office                   76

-------
                                                               Coal Creek SuperfuncT Site
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
Performance Data Available
   Data are available for concentrations of
   contaminants in the sediment before
   treatment
Performance Data Quality

•  An independent quality assurance team,
   CH2M Hill, was tasked to ensure that the
   remediation complied with the
   performance standards  The Quality
   Assurance/Quality Control program used
   throughout the remedial action was
   deemed to have met the EPA and the
   state of Washington requirements
         Data are also available for
         concentrations of contaminants in the
         incinerator residue These data were
         collected periodically throughout
         operation of the incinerator before on-
         site disposal
                            TREATMENT SYSTEM COST
Procurement Process

•  Roy F  Weston, Inc , was the remedial
   contractor for Phase II, which included the
   incineration

Cost Data

•  The total cost was approximately
   $8,100,000  A total of 9,715 tons of soil
   were incinerated  This corresponds to a
   total unit cost of $830 per ton  A detailed
   breakdown of those costs was not
   available
        The total cost provided here is an
        estimate reported in the Remedial Action
        Report
                     OBSERVATIONS AND LESSONS LEARNED
Observations and Lessons Learned

•   Before excavation began, structures on
    site were torn down and removed  During
    this process, PCB contaminated soil was
    disturbed and contamination was spread
    Public Involvement

    •   No written comments were received
        during the 60 day public comment period
        on the proposed plan, but support for a
        permanent and immediate solution was
        voiced during public meetings The
        community response to the incineration
        was generally supportive
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
77

-------
                                                              Coal Creek Superfund Site
                                   REFERENCES
1  Superfund Record of Decision. Coal
   Creek, Chehahs, Washington, October
   1990

2.  Mini-Burn #1 Test Result, Coal Creek,
   January 1994

3.  Memorandum from Catherine Massimmo,
   Senior RCRA/Superfund, to Loren
   McPhiilips, Coal Creek RPM, February
   1994
       Addendum 4 - Risk Assessment
       Addendum, Coal Creek, February 1994

       Coal Creek Remedial Action Report.
       CH2M Hill and Roy F  Weston, Inc ,
       December 1994
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
78

-------
        On-Site Incineration at the
FMC Corporation - Yakima Pit Superfund Site
           Yakima, Washington
                   79

-------
    Incineration at the FMC Corporation - Yakima Pit Superfund
                         Site Yakima, Washington
Site Name:
FMC Corporation - Yakima Pit
Superfund Site
Location:
Yakima, Washington
Contaminants
• ODD, DDE, DDT, dieldrin,
  endosulfan, ethion,
  malathion, parathion,
  cadmium, chromium, and
  zinc
• ODD concentrations of 76
  mg/kg, DDE concentration of
  210mg/kg, and DDT
  concentrations of 210 mg/kg
• The maximum concentrations
  of contaminants (mg/kg)
  detected in soil were ODD
  (76), DDE (28), DDT (210),
  dieldrin (40), endosulfan
  (7,000), ethion (180),
  malathion (170,000),
  parathion (3,300), cadmium
  (6), chromium (320), and zinc
  (1,020)	
Period of Operation.
January 1993 - May 1993
Cleanup Type:
Remedial action
Vendor:
VESTA Technology Ltd
1670 West McNab Road
Ft Lauderdale, FL 33309
SIC Code:
2879 (Pesticides and
Agricultural Chemicals)
Technology
On Site Incineration
• Solids crushed and mixed
  with soil
• Incineration system
  consisting of co-concurrent
  rotary kiln and secondary
  combustion chamber (SCC)
• Enclosed twin screw
  conveyor transported soil and
  debris to the unit
• Soil had a through part rate
  of 60 kg/mm with kiln
  temperature of 650 °C, the
  SCC temperature of 1,107
  °C
• Ash discharged onto
  conveyers, sampled and
  analyzed, and then landfilled
Cleanup Authority.
CERCLA
• ROD Date 9/14/90
• EPA-lead
Point of Contact
Lee Marshall
US EPA Region 10
1200 Sixth Avenue
Seattle, Washington 98101
(206) 553-2723
                                       80

-------
    Incineration at the FMC Corporation - Yakima Pit Superfund
                          Site Yakima, Washington
                                    (Continued)
Waste Source
Pesticide production wastes
disposed of in an unhned pit
Purpose/Significance of
Application:
Initially, was estimated in the
ROD that between 900 and
4,000 cubic yards of material
were contaminated However,
contamination extended  deeper
than previously anticipated
and, as a result, over 5,600
cubic yards of material was
excavated for incineration
Type/Quantity of Media Treated-
Soil and Debris
• 5,600 cubic yards
Regulatory Requirements/Cleanup Goals.
• Destruction and Removal Efficiency (ORE) of 99 99 for all constituents of concern as required
  by Resource Conservation and Recovery Act (RCRA), 40 CFR Part 264 Subpart O	
Results.
• Monitoring and trial burn data indicate that all DRE and emission standards have been met
« Analytical data of residuals indicate that cleanup goals have been met	
Cost Factors-
• The actual cost for remediation using the incineration system was approximately $6,000,000
Description-
Between 1952 and 1969, wastes contaminated with pesticides were disposed of on the site in an
unlmed waste disposal pit  It was estimated that 2,000 pounds of material was disposed of on the
site in the pit contaminating soil with 1,1-dichloro-2,2-bis(p-chlorophenyl)ethane (ODD), 1,1-
dichloro-2,2-bis(p-chlorophenyl)ethylene (DDE), 1,1,1-tnchloro-2,2-bis(p-chlorophenyl)ethane
(DDT), and dieldnn

A Record of Decision (ROD) signed in September 1990 specified on-site incineration as the
remedial technology  Site cleanup goals and destruction and removal efficiency (DRE) standards
were established for constituents of concern

On-site incineration began in January 1993 and was completed in May 1993  The treatment
system consisted of a rotary kiln and an SCC  Enclosed twin screws moved the soil to the kiln for
treatment  Ash was collected and flue gas was completely incinerated Incineration has
achieved the soil cleanup goals specified in the ROD

The actual cost for remediation using the incineration system was approximately $6,000,000
                                         81

-------
                                                  • FMC Corporation - Yakima Pit Superfund Site
                                EXECUTIVE SUMMARY!
This report presents cost and performance data
for the application of on-site incineration at the
FMC Corporation - Yakima Pit (Yakima)
Superfund site in Yakima, Washington A rotary
kiln incinerator was operated from January 1993
through May 1993 as part of a remedial action
Contaminants of concern at the site included
pesticides and metals

The Yakima site was the location of a former
pesticide manufacturing plant which operated
from 1951 until its closure in 1986 Between
1952 and 1969, wastes contaminated with
pesticides were disposed of on the site in an
unlined waste disposal pit  It was estimated that
2,000 pounds of material was disposed of on the
site in the pit  Soil at Yakima was contaminated
with 1,1-dichloro-2,2-bis(p-chlorophenyl)ethane
(ODD), 1,1-dichloro-2,2-bis(p-
chlorophenyl)ethyiene (DDE), 1,1,1-tnchloro-
2,2-bis(p-chlorophenyl)ethane (DDT), dieldrm,
endosuifan, ethion, malathion, parathion,
cadmium, chromium, and zinc During the
remedial investigation, the maximum
concentrations of these contaminants in mg/kg
detected in the soil were ODD (76), DDE  (28),
DDT (210), dieldnn (40), endosuifan  (7,000),
ethion (180), malathion (170,000), parathion
(3,300), cadmium (6), chromium (320), and zinc
(1,020)

A Record of Decision (ROD) signed in
September 1990 established a Destruction and
Removal Efficiency (ORE) of 99 99% for
constituents of concern  In 1991, a Consent
Decree was entered in the Eastern District of
Washington in which the Responsible Party
(RP) for the site agreed to implement the
remedial action proposed in the ROD

The RP conducted remedial activities including
the operation of a rotary kiln incinerator to
dispose of the contaminated soil  The
incineration system at Yakima was comprised of
a solid waste feed system, a co-current rotary
kiln, a secondary combustion chamber (SCC),
and an air pollution control system (APCS)
The incineration equipment was located on
six flat bed trailers and several skids
Contaminated material was fed to the
incinerator by a jacketed, twin-screw
conveyor

The incinerator volatilized and partially
destroyed organic compounds from the
contaminated material  Resulting ash from
the incinerator was removed by a
submerged drag conveyor while the off-gas
was drawn into the SCC  The SCC was a
down-fired steel shell that provided further
combustion of contaminants in the gas

Off-gas from the SCC was then drawn into
the APCS, which was divided into three
stages The first stage, which consisted of a
quench tank and two Venturis, trapped and
collected particulate matter  The second
stage, which consisted of a packed bed
adsorbei and cooling tower, removed acid
gases The third stage, which consisted of
an ionized wet scrubber, provided further
removal of particulate matter  Ash collected
from the incinerator and APCS was sampled
and analyzed to determine if it was in
compliance with site-specific land disposal
requirements, at which time it was either re-
mcmerated or landfilled on the site

During the five months of operation, the
incinerator processed approximately 5,600
cubic yards of contaminated material
Treatment performance and emissions data
collected during this application indicated
that all performance standards and
emissions requirements were achieved

The actual cost for remediation using the
incineration system was approximately
$6,000,000
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            82

-------
                                                  • FMC Corporation - Yakima Pit Superfund Site
                                  SITE INFORMATION
Identifying Information
FMC Corporation - Yakima Pit Superfund Site
Yakima, Washington

CERCLIS#  WAD000643577

ROD Date  September 14,1990
Background

Historical Activity that Generated
Contamination at the Site  Manufacture of
pesticides
Corresponding SIC Code
and Agricultural Chemicals
2879 (Pesticides
Waste Management Practice That
Contributed to Contamination  Waste
disposal in an unhned pit

Site History

•   The site operated from 1951 until its closure
    in 1986  The site has remained vacant
    since its closure

    From 1952 until 1969 wastes containing
    pesticides were disposed of in an on-site,
    unlmed waste pit and covered with soil  The
    waste material included raw material
    containers, soil contaminated by leaks or
    spills from process equipment, broken bags,
    and off-specification materials [1]

•   In the 1970s, liquid products were
    formulated on-site using solvents,
    emulsifiers, and stabilizers  Spills and leaks
    of these materials were believed to have
    been a source of concrete and soil
    contamination [1]
                        Treatment Application

                        Type of Action Remedial (on-site rotary
                        kiln incineration)

                        Period of operation  January 1993 - May
                        1993

                        Quantity of material treated during
                        application  5,600 cubic yards of soil and
                        debris
Contamination at the site was found
within a 58,000-square-foot area on the
northeastern portion of the 10-acre site

Soil at Yakima was contaminated with
pesticides and metals including DDD,
DDE, DDT, dieldrm, endosulfan, ethion,
malathion, parathion, cadmium,
chromium, and zinc  A remedial
investigation conducted in  1988 showed
elevated concentrations of DDT and
other pesticide constituents in the
former disposal pit

Removal actions in 1988 and 1989
included excavation, removal, and
disposal of 850 tons of contaminated
soil from the waste pit [1]

A ROD signed in 1990 addressed the
contamination that remained in and
around the waste pit  The  ROD called
for on-site incineration of contaminated
soil and debris
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           83

-------
                                                 1FMC Corporation - Yakima Pit Superfund Site
                             SITE INFORMATION (CONT.)
Background (Cont.)

•   In April 1992, site mobilization began  By
    December 1992, incinerator shakedown had
    begun using contaminated soil  The trial
    burn scheduled for December 1992 was
    canceled due to delays in completing
    incinerator instrumentation installation and
    checkout  The trial burn was re-scheduled
    for January 1993

•   In January 1993, the re-scheduled trial burn
    was canceled due to mechanical difficulties
    with the incinerator  After extensive
    incinerator modifications, the shakedown
    period was extended  Later in the month an
    EPA-mandated 72-hour demonstration test
    of the incinerator using clean soil was
    completed  Incineration of contaminated
    soil resumed under operational guidelines
    and limits established in an extended
    shakedown plan

    In March 1993, the extended shakedown
    activities were completed The trial burn
    was conducted and successfully completed
    later in the month

•   Between January 1993 and May 1993,
    approximately 5,600 cubic yards of
    contaminated material were incinerated
    This amount included the material which
    was incinerated during the shakedown
    period
•   Incinerator ash was disposed of on the
    site  Backfilling of the ash was
    completed in June 1993  Site
    demobilization activities were
    completed in July 1993

Regulatory Context

•   In 1983 the Yakima site was placed on
    the National Priorities List (NPL)

•   The selected remedy was implemented
    under the provisions of the
    Comprehensive Environmental
    Response, Compensation, and Liability
    Act of 1980 (CERCLA), as amended by
    the Superfund Amendments and
    Reauthonzation Act of 1986 (SARA),
    and the National Contingency Plan
    (NCP) in 40 CFR part 300 [6]

•   The DREs were set in accordance with
    Resource Conservation and Recovery
    Act (RCRA) incinerator regulations in 40
    CFR part 264, subpart O

Remedy Selection  On-site incineration
was selected as the remedy for
contaminated soil and debris at the Yakima
Pit Superfund site based on treatability
study results, its ability to be protective of
human health and the environment, and its
ability to comply with Applicable or Relevant
and Appropriate Requirements (ARARs)
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           84

-------
                                              1FMC Corporation • Yakima Pit Superfunof Site
                           SITE INFORMATION (CONT.)
Timeline
                                Table 1  Timeline [1, 2]
If pi
1951 - 1986
1952-1969
1983
1988
1988
1989
September 1990
April 1992
January 1993
March 1993
May 1993
June 1993
July 1993
August 1993
.: /- :v>» ..^^&wr.^mi^^ - : „ - _, *~ **•*•:*. .•<*
Pesticides were manufactured at the Yakima site
Wastes from pesticide manufacturing were disposed of in an on-site unlined pit
Yakima site placed on NPL
Remedial Investigation
First Removal Action
Second Removal Action
ROD signed specifying on-site incineration
Site mobilization begins
72-hour demonstration test completed
Incineration Performance Test completed
Incineration completed
On-site backfilling of ash completed
Site was demobilized
Remedial Completion Inspection of the site
Site Logistics/Contacts

Site Management  RP-lead

Oversight EPA

Remedial Project Manager:
Lee Marshall
US EPA Region 10
1200 Sixth Avenue
Seattle, WA 98101
(206) 553-2723
Treatment System Vendor:
VESTA Technology Ltd
1670 West McNab Road
Ft Lauderdale, FL 33309
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         85

-------
                                                1FMC Corporation - Yakima Pit Superfund Site
                               MATRIX DESCRIPTION
Matrix Identification
Type of Matrix Processed Through the
Treatment System

•   Soil and debris from an unlined waste
    disposal pit

•   Contaminated concrete from the
    manufacturing plant

Contaminant Characterization

Primary Contaminant Groups  Pesticides and
Metals

•   The contaminants of greatest concern were
    ODD, DDE, DDT, dieldnn, endosulfan,
    ethion, malathion, parathion, cadmium,
    chromium, and zinc
   The maximum concentrations of
   contaminants (mg/kg) detected in soil
   were ODD (76), DDE (28), DDT (210),
   dieldnn (40), endosulfan (7,000), ethion
   (180), malathion (170,000), parathion
   (3,300), cadmium (6), chromium (320),
   and zinc (1,020)
Matrix Characteristics Affectina Treatment Costs or Performance

Information on matrix characteristics, such as
soil classification, moisture content, and
density, was not available
                        TREATMENT SYSTEM DESCRIPTION
primary Treatment Technology

VESTA Technology, Ltd Model 200
Transportable Hazardous Waste Incinerator
(incineration system) including

•   Solid waste feed system
•   Co-current, rotary kiln
•   Secondary combustion chamber
Supplemental Treatment Technology

Pretreatment (solids)

•  Crushing
•  Mixing

Post-Treatment (air)

•  Quench tank
•  Venturi scrubber
•  Cooling tower
•  Packed bed absorber
•  Ionized wet scrubber

Post-Treatment (water)

•  Surge tank
•  Particulate filters
•  Carbon filter
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          86

-------
                                                  • FMC Corporation - Yakima Pit Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
System Description and Operation

•   In addition to the soil, approximately 10
    cubic yards of concrete and a limited
    amount of decontamination fluid was
    incinerated  The concrete was crushed to 1
    inch pieces and mixed with the soil for
    incineration   Decontamination fluid,
    generated from cleaning concrete and
    personal protective equipment was collected
    and also mixed with soil for incineration

•   The mam components of the incineration
    system included the rotary kiln, the SCC,
    and the ARCS  The equipment was located
    on flat bed trailers and skids  The final
    system consisted of six trailers in a 100-foot
    by 120-foot work area [3]

•   The waste feed system consisted of a
    variable speed J C Steele Feeder, a weigh
    belt conveyor, an inclined drag conveyor
    and a twin 6-inch screw feeder  The J C
    Steele Model 88C Even Clay Feeder was a
    multi-shafted conveyor which included a
    hopper and hopper extension to hold soil
    fed to it by a mechanical loader  The rate of
    discharge from the feeder was controlled by
    adjusting the rate at which the screws turned
    [3]

•   Solids from the Steele feeder fell onto a
    Model MD-24T Thayer weigh belt conveyor
    The belt passed over an  isolated frame
    connected to a load cell, which measured
    the deflection caused by the weight of the
    soil   It then transmitted a signal to a
    controller which governed the rate at which
    the Steele feeder discharge soil to the feed
    system [3]

•   Solids fell from the weigh belt to a bottom
    carry drag conveyor manufactured by
    Taunton Engineering  The drag conveyor
    was 25 feet long and had a 12 foot high
    discharge flange  The conveyor was driven
    by a 2 horsepower (hp) motor [3]

•   Soils fell from the drag conveyor onto a
    water-jacketed twin screw conveyor, which
    fed the soils into the kiln The conveyor
was driven by a 6 7-hp drive motor
Water was circulated in the jacket to
protect the conveyor components from
the high temperatures generated by the
kiln

The co-current kiln was 25 feet in
length, had an inside diameter of 5 9
feet, and was lined with high-
temperature refractory The kiln was
designed to operate with excess air or
oxygen and to handle a maximum
throughput rate of 10,000 pounds per
hour

The average throughput of waste feed
was 60 6 kg/mm  The kiln was rated at
105 million BTU/hr and operated at
650° C

Residual ash from the kiln fell from the
discharge end of the conveyor into the
ash drag conveyor  The bottom end of
the conveyor was completely
submerged in water to cool the hot ash
The conveyor discharged the ash into a
hopper  The ash was then sampled and
analyzed to determine if it met
requirements for on-site land disposal
The TCLP analyses of the ash
confirmed that it was not a RCRA
characteristic waste, and therefore
could be landfilled on site

Flue gas from the kiln was routed to the
SCC to ensure complete combustion of
volatilized contaminants  The SCC
operated at approximately 1,107°C and
was equipped with an excess air burner
Air flow in the SCC was co-current to
the flue gas flow  The burner was rated
at 12 5 million BTU/hr  The SCC was
30 feet long and had an inside diameter
of 6 5 feet
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           87

-------
                                                 • FMC Corporation - Yakima Pit Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
    The exhaust gas from the SCC was then
    routed to the system's ARCS  The ARCS
    contained three distinct units  The first
    stage consisted of a quench tank and a
    ventun scrubber to reduce flue gas
    temperature and remove particulates Acid
    gas was neutralized by a pH-controlled
    spray in the ventun  Solids were removed
    from the process water by a clarifler  The
    clanfier used a filter press to remove solids,
    and the treated water was recycled to the
    ventun

    The second stage of the ARCS consisted of
    a packed bed absorber and a cooling tower
    to subcool the off-gas The process water
    for the absorber was pH controlled to ensure
    sufficient removal efficiency of acid gas
    The subcoolmg of the off-gas was in a
    closed loop through a heat exchanger to
    reduce heavy metal emissions Slowdown
    from the second stage was treated and then
    used as makeup water for the first stage [3]

    The third step consisted of a two-stage
    ionized wet scrubber to remove particulates
    The scrubber used high voltage lonization to
    electrostatically charge particulates in the
    gas stream before they entered the scrubber
    section Particles greater than 3  microns
    were collected by mertial impaction
    Smaller particles were attracted to the
    neutral surfaces of the scrubber due to the
    electrostatic charge which had been
    imparted on them  Slowdown from the
    scrubber was treated and then used as
    makeup water for the first stage [3]
Operating Parameters Affectina Treatment Cost or Performance

                         Table 2 Summary of Operating Parameters
The blowdown from the second and
third stages was treated in a system
which consisted of a 1,000 gallon surge
tank, a three-stage particulate filter, an
activated carbon filter, and a particulate
post filter  The surge tank acted as a
primary settling tank for particulate
removal and provided capacity to
handle excess flow conditions The
three-stage particulate filter was
designed to remove particulates larger
than 1 micron  The carbon filter was
designed to remove organic compounds
that were present  The post filter
removed any particulate larger than 0 5
microns  The solids collected by the
filters were collected and sampled prior
to disposal [3]

Combustion gases were  drawn through
the kiln system and ARCS by an
induced draft fan and were exhausted
through a 30-foot fiberglass reinforced
plastic stack Typical flue gas velocity
was 85 m3/mm
	 Parameter
Residence Time
System Throughput
Kiln Temperature
•v^jsT', S ';P 9 'ff t
NA
60 6 kg/mm
650°C
U S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office

-------
                                                  1FMC Corporation - Yakima PA Superfund Sits
                        TREATMENT SYSTEM PERFORMANCE
Cleanup Goals/Standards

•  The cleanup goals and standards were
   specified in the ROD The ORE standards
   were set based on RCRA incinerator
   regulations in 40 CFR part 264, subpart O

•  A ORE of 99 99% was required for each
   constituent of concern

•  Ash residuals were tested using the Toxicity
   Characteristic Leaching Procedure (TCLP)
   prior to on-site disposal

•  Cleanup standards in mg/kg were set for the
   following constituents in soil  ODD (5 1),
   DDE (3 6), DDT (3 6), Dieldnn (0 076),
   cadmium (8 0), hexavalent chromium (1 0),
   endosulfan (4 2), ethion (42 4), malathion
   (1,695), parathion (11 0), zinc (500)
                                                     Cleanup standards in mg/100 cm2 were
                                                     set for the following constituents in
                                                     concrete and other surfaces ODD
                                                     (0 0065), DDE (0 0046), DDT (0 0046),
                                                     dieldrm (0 0001), endosulfan (0 010),
                                                     ethion (0 270), malathion (8 2), and
                                                     parathion (2 4)

                                                     The soil cleanup criteria were
                                                     established according to a risk
                                                     assessment which allowed a 5 x 106
                                                     excess lifetime cancer occurrence

                                                     A cumulative hazard index was set at
                                                     less than or equal to 1 for all
                                                     noncarcmogenic substances
Treatment Performance and Compliance

•   A trial burn conducted at Yakima was
    designed to operate the incineration system
    at conditions that would reflect worst-case
    destruction and removal of all constituents
    of concern  Hexachlorobenzene was
    selected as the POHC  The reported ORE
    for this POHC is included in Table 3

•   The incinerator at Yakima operated within
    the operating limits established during the
    trial burn, signifying that all cleanup
    requirements established in the ROD were
    met  The AWFCOs limits used during the
    operation of the
                                                     incinerator are shown in Table 4
                                                     Information about the frequency of
                                                     AWFCOs was not available  Available
                                                     trial burn and typical operating
                                                     parameters are shown in Table 5

                                                     The residual ash was sampled and
                                                     analyzed using the Toxicity
                                                     Characteristic Leaching Procedure
                                                     (TCLP) to determine if it was in
                                                     compliance with on-site disposal
                                                     requirements These data are
                                                     presented in Table 6
            Table 3 Average Destruction and Removal Efficiencies from Trial Bum [4]
   Contaminant
                , Average Contaminant
                                     *r ** 'Vff  t *      *  ,^,
                                   Average Contaminant Rate in
                                    Stack Gas emissions (Itj/nr)
 Hexachlorobenzene
                        30
                                           246x107
                                                                   0130
99 999992
                           Table 4 Automatic Waste Feed Cutoffs
#'-??'&&'jp:£&&#ii*i* d*w" :.,,.>;••"
Maximum contaminated soil feed rate1
Maximum kiln temperature
Minimum kiln temperature
Minimum SCO outlet temperature
':- *•" ^-^' T C&ofrtLtaii,?'7 / -IV ' -' ••"'
67 kg/mm
1,000°C
600°C
1,093°C
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                            89

-------
                                             • FMC Corporation - Yakima Pit Superfund Site
                 TREATMENT SYSTEM PERFORMANCE (CONT.)
                        Table 4  Automatic Waste Feed Cutoffs
I""1'1 ' , Parameter **" /
Maximum quench outlet temperature
Minimum recycle to venturl
Minimum venturi differential pressure
Minimum absorber recycle flow
Minimum absorber flow water pH
Maximum cooling tower Inlet temperature
Minimum Ionized wet scrubber #1 recycle water flow
Minimum Ionized wet scrubber #2 recycle water flow
Minimum Ionized wet scrubber #1 voltage
Minimum Ionized wet scrubber #2 voltage
Maximum exhaust stack CO concentration
Maximum exhaust stack average CO concentration1
Maximum exhaust stack O2
Maximum exhaust stack flow
Minimum kiln Oz level
Minimum SCC outlet O2 level
Maximum kiln pressure
Bypass stack not closed
'i '\%S-tS»;i«c«io®«!it £•- :'," "~ "-
100°C
150 Lpm
750 mm w c
1,000 Lpm
6
80°C
1 ,000 Lpm
1 ,000 Lpm
12 kV
12 kV
500 ppm
100ppm
4%
175 rrrYmm
6%
3%
-1 3 mm w c
Open
'One hour rolling average
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                       90

-------
                                                 1FMC Corporation • Yakima Pit Superfuncf Site
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
                            Table5  Operating Parameters [4, 7]
• ;: • " - - ~"~ 'i
Contaminated Soil Feed Rate
Fuel Fired Feed Rate
Emission Rate
Particulate
HCI
CI2
S02
NOX(@7%O2)
Operating Conditions
CO concentration in gas
Exhaust stack O2 concentration
Kiln temperature
SCC outlet temperature
Stack gas flow rate
Quench outlet temperature
r^'^'J; ^^^*J' ,".< -* C^', y^
1,,. J^AelttalValue1 i,V
60 6 kg/min
10 5 million BTU/hr
NA
NA
NA
NA
NA
10ppm
10%
650°C
1,107°C
85 m3/mm
85°C
,-w. ,->** oi_ ^ ^ .» ^A -j
;,,, TftalBOtttValae - A
81 8 kg/min
10 5 million BTU/hr
00014gr/dscf
0 004 kg/hr
<0 001 kg/hr
6 18 ppm
1,123 83 ppm
18 44 ppm
1297%
NA
NA
NA
NA
'Anticipated values as reported in the Incineration Work Plan
                           Table 6  TCLP Comparison for Residual
<.J -^ Jf?J ,*. -'- - * ;^ / M>VJ, ? ,
..? '-,» ^ <*=* ^-Cooltituent , _, C^r*
Metals
Arsenic
Barium
Cadmium
Chromium
Lead
Mercury
Selenium
Silver
Organochlorine Pesticides
Chlordane
Endnn
Heptachlor (and epoxide)
Lmdane
Methoxychlor
Toxaphene
" ' ' JiMlrii^^y Threshold ' " "
-• x<5s>ndhlrattwting/iir)* *r^

5
100
1
5
5
02
1
5
003
002
0008
04
10
05
" ^rerageTCLP-CorKsentratlon -
" =•!* ~***tfRS$3> M *•- «v ^

0016
019
00028
0011
0020
000012
00099
00046
0 00037
0 000082
000018
0 000037
000011
00012
Note Only pollutants that were detected are included in this table
aExcerpted from 40 CFR § 261 24 Table 1
bGeometnc mean value of reported ash samples
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           91

-------
                                                1FMC Corporation - Yakima Pit Superfund Site
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
Performance Data Completeness

•   Data are available for concentrations of
    contaminants in the soil before treatment
Performance Data Quality

•   According to site personnel, the QA/QC
    program used throughout the remedial
    action met the EPA and the State of
    Washington requirements  All monitoring
    was performed using EPA-approved
    methods, and the vendor did not note any
    exceptions to the QA/QC protocols
     Data are also available for
     concentrations of contaminants in the
     incinerator residue These data were
     periodically collected prior to on-site
     land disposal
                            TREATMENT SYSTEM COST
Procurement Process
   The RP contracted with VESTA Technology
   Ltd to provide and operate the incinerator
   at the site
Cost Data

•  The estimated treatment cost of
   $6,000,000 was reported by Bechtel
   Environmental, Inc  A total of 7,840 tons
   of soil were incinerated  This corresponds
   to a total unit cost of $770 per ton A
   detailed breakdown of these costs was not
   available
Cost Data Quality

•   Actual capital and operations and
    maintenance cost data are available from
    the treatment vendor for this application
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          92

-------
                                                 1FMC Corporation • Yakima Pit Superfuncf Site
                     OBSERVATIONS AND LESSONS LEARNED
Observations and Lessons Learned

•   It was estimated in the ROD that between
    900 and 4,000 cubic yards of material were
    contaminated  However, contamination
    extended deeper than previously anticipated
    and, as a result, over 5,600 cubic yards of
    material was excavated for incineration

•   Samples from  7 feet below ground surface
    taken during excavation contained
    contaminant concentrations above the
    cleanup goals  EPA determined that
    excavation below 7 feet was technically
    impracticable,  and that the material did not
    pose an exposure risk because soil at this
    depth was constantly submerged below
    water  Additionally, EPA felt that the
    groundwater was not at risk due to the
    excavation of material which had already
    taken place Groundwater monitoring was
    scheduled to take place for five years
    following the completion of the incineration
    project [5]
Many problems occurred while trying to
get the incinerator operational
Shakedown activities were scheduled
for the winter months with average
temperatures around 25° F  The cold
weather caused many delays in setting
up the incinerator  Additionally, the
incinerator contractor did not anticipate
the amount of monitoring that would
occur on-site, which caused further
delays [6]

Excavation of contaminated soil at the
site was complicated by environmental
factors The water table at the site is at
its seasonal low of 7 feet below ground
surface during the winter months
Excavation of soil with the water table  at
this level is preferred but harsh winter
conditions in Washington introduced
other problems  During the warmer
summer months, the water table at the
site is at its seasonal high of 6 inches to
1 foot below ground surface  While the
warmer temperatures make outdoor
operations easier, the high water table
hampers soil excavation
                                    REFERENCES
1   Superfund Record of Decision. FMC
    Corporation Yakima Pit, Yakima,
    Washington, September 14,1990

2   Remedial Action Completion Report.
    Bechtel Environmental, Inc , May 16,1994

3   Performance Demonstration Test Plan
    Section 2. VESTA Model 200 Incinerator
    Engineering and Design Specifications.
    VESTA Technology, November 1992

4   Final Results of the Trial Burn
    Demonstration Test of the VESTA
    technology. Ltd Model 200 Incinerator at
    the Former FMC Pesticide Formulating
    Facility in Yakima. Washington.
    Environmental and Risk Management, Inc ,
    April 1993
Explanation of Significant Differences -
FMC Corporation Yakima. Washington.
U S EPA Region X, April 1993

Personal Communication, Mr  Kevin
Rocklm, May 19,1997

Incineration Work Plan - Revision 3.
Addendum 2. VESTA Technology, Ltd ,
January 1993

Cleanup Summary for Incinerator Ash
and Waste. Beehtel Environmental,
Inc, June 1993
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           93

-------
This Page Intentionally Left Blank
               94

-------
Incineration at the Former Nebraska
       Ordnance Plant Site
         Mead, Nebraska
               95

-------
         Incineration at the Former Nebraska Ordnance Plant Site
                                  Mead, Nebraska
Site Name:
Former Nebraska Ordnance
Plant - Operable Unit 1
Location:
Mead, Nebraska
Contaminants
Explosives and Propeliants
•   TNT, RDX, TNB, DNT,
    DNB, HMX, Tetryl, o-NT
    and m-NT
•   Maximum concentrations
    in mg/kg - TNT
    (133,000), RDX (23,270),
    TNB (430) and DNT
    (1193)     	
Period of Operation:
•   Mini and Trial Burn
    Operation - September
    1997
•   Full-Scale Operation -
    October to December  1997
Project Management
U S Army Corps of
Engineers Formerly Used
Defense Sites Program
Edwin Louis
Kansas City District
700 Federal Building
Kansas City, Missouri 68144-
3869
(816) 983-3563
Technology:
On-Site Incineration
•   Soil stream was fed
    through a grizzly screen
    to remove large debris
•   Incineration system
    consisting of a co-current,
    rotary kiln and one
    secondary combustion
    chamber (SCC)
•   Kiln operated at an exit
    gas temperature of 1150
    to 1800 °F, SCC operated
    1800°F
•   Hot flue gases exiting the
    kiln were quenched using
    water spay nozzles
•   Solids exiting the kiln
    were stockpiled for
    compliance sampling
Cleanup Type:
Remedial Action
Cleanup Authority
CERCLA and State
ROD date - August 29, 1995
                                                       SIC Code:
                                                       9711B (Ordnance Production
                                                       and Storage) and 9711C
                                                       (Ordnance Testing and
                                                       Maintenance)
Waste Sources:
Discharge of contaminated
rinse water and burning of
explosives
Purpose/Significance of
Application:
Project completed in
extremely short time period,
including all permitting
requirements
Type/Quantity of Media
Treated:
Soil and Debris
•   16,449 tons (13,009 cubic
    yards) of soil and debris
•   Average Moisture
    Content 1682%
•   Average BTU value per
    pound 1220
•   Average Soil Density -
    93 7 pounds per cubic
    foot
Regulatory Points of
Contact
Craig Bernstein
USEPA Region VII
726 Minnesota Avenue
Kansas City, Kansas 66101
(913)551-7688

Troy Bendenkamp
NDEQ
Suite 400, The Atrium
1200N Lincoln Street
Lincoln, Nebraska 68509-8922
(402)471-2214	
                                        96

-------
      Incineration at the Former Nebraska Ordnance Plant Site

                                Mead, Nebraska



                                    (Continued)


Regulatory Requirements/Cleanup Goals.
Destruction and Removal Efficiency (ORE) of 99 99% for POHC
The following limits were set for treated soil after incineration in mg/kg
-  TNT-17 2
-  RDX-58
-  TNB - 1 7
-  DNT-09
-  TNB - 1 7
-  HMX-1,7152
-  Tetryl - 343
-  NT-343

Results:
•  Emission and trial burn data indicated that all ORE and emissions standards were met
•  Treated soil sampling indicated that all soil cleanup goals were met

Costs
The total cost for this project was $10,700,001 The technology cost was $6,479,245 ($394 per
ton of contaminated material)


Description:
During  several intervals between 1942 and 1959, the Nebraska Ordnance Plant (NOP) site was
used for loading, assembly and testing of bombs, boosters and shells  During site cleaning
activities, explosives-containing wash water was discharged into surface water drainage ditches
at the site  In addition,  contamination was observed in soil at the Burning/Proving Grounds at
the site A Record of Decision (ROD) was signed in August 1995, specifying on-site
incineration as the remedial technology for addressing shallow contaminated soil at the site
Shallow contaminated soil at the former NOP (soil between 0 and 4 feet below the ground
surface) was identified as Operable Unit (OU) 1  Site soil cleanup goals were specified in the
ROD

Because the former NOP site was designated as part of the Formerly Used Defense Site
(FUDS) program, the USAGE was responsible for managing remedial actions at this site

Site work for construction of the incinerator was commenced in February 1997  Incinerator
start up and shake down were performed in August and September 1997 Mini burn and trial
burn tests were conducted in September 1997  After receiving approval from EPA and NDEQ
of the proposed operating limits, the incinerator was put into full production in October 1997
Treatment was completed in December 1997 The incineration system consisted of a co-
current, rotary kiln followed by a secondary combustion chamber (SCC)  After confirming that
treated soil met the cleanup criteria, the soil was returned to an excavation at the site
Demobilization of the incinerator from the site was completed in May 1998
                                         97

-------
                                                                      Former NOP OU-1
                                 SITE INFORMATION
IDENTIFYING INFORMATION Ml
Site Name:
Location:
Operable Unit:
CERCLIS #:
ROD Date:
Technology:
Type of Action:
Former Nebraska Ordnance Plant (NOP)
Mead, Nebraska
OU1
NE6211890011
August 1995 (Signed by EPA on August 29, 1995)
On-Site Rotary Kiln Incineration
Remedial
Figure 1 shows the location of the former NOP in Nebraska

TECHNOLOGY APPLICATION (2)

Period of Operation:
Mini and trial burn operation - September 1997
Full-scale operation - October through December 1997

Quantity of Material Treated During Application:
16,449 tons of explosives-contaminated soil

BACKGROUND

Site Background (1,3):

•      The former NOP facility is located on 17,000 acres of land approximately 2 miles south of
       the town of Mead in eastern Nebraska The site was used to load, assemble and pack
       bombs, boosters and shells in the 1940s during World War II and in the 1950s during the
       Korean conflict The NOP included the following facilities

             Four bomb Load Lines,
             A Bomb Booster Assembly plant,
             An ammonium nitrate plant,
             Two explosives burning areas,
             A proving range,
             A landfill,
             A wastewater treatment plant,
             Analytical laboratories, and,
             Administration facilities
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          98

-------
                                 Figure 1  Location of the Former NOP Facility m Nebraska
                                                                                                         Former NOP OU-1
               NOP1 DWG DC-RTG 4/9/98
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                                           99

-------
                                                                          Former NOP OU-1
•      In 1959 the facility was declared excess to Army needs, and was transferred to the General
       Services Administration for disposition

•      Since 1959, various portions of the 17,000 acres have been transferred to government
       agencies (Army, Air Force and The Department of Commerce), local public officials (The
       University of Nebraska) and various private individuals and corporations  Since its closure,
       the majority of the former NOP facility has been used for agricultural production  However,
       several private businesses have been operated at the facility since 1959

Figure 2 shows the layout of the former NOP facility

SIC Code:
9711B (Ordnance Production and Storage) and 9711C (Ordnance Testing and Maintenance)

Waste Management Practices that Contributed to Contamination (1)

Explosives production  equipment and buildings were regularly cleaned and decontaminated with
water Wash water containing explosives flowed into drainage ditches and sumps outside the
buildings  Explosives were regularly tested in the Burning/Proving Grounds at the site

Site Operation History (1):

•      The Nebraska Defense Corporation operated the NOP facility from 1942 to 1945, producing
       boosters in the booster assembly area and bombs at the four load lines The facility was
       placed on inactive status in 1945  Routine operations at the NOP included discharge of
       explosives-containing wash water into site sumps and open ditches

•      The facility was decontaminated in 1945 Decontamination procedures included the
       following

              Building floors were cleaned by sweeping and flushing,
              Explosives-production surfaces were scraped and brushed by  hand,
              Internal roofs and trusses were steam-cleaned,
              External roofs were cleaned by flushing with water, and,
              Cleaning residues, contaminated soil and sludges and selected wooden structures
              and tile drainage pipe were all taken to the Burning/Proving Grounds for disposal by
              burning

       In 1950, the facility was reactivated to produce weapons for the Korean Conflict  The NOP
       was placed on standby in 1956, and declared excess to Army needs in 1959

•      Decontamination records following 1950 could not be located for the NOP  It is assumed
       that portions of the facility were decontaminated with hot water and steam  It is likely that
       several areas of the facility were not decontaminated
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           100

-------
                          Figure 2.  Layout of the Former NOP Facility
                                                                                   Former NOP OU-1
            NOP3 DWG DC-RTG 4/9/98
                                                         E CROP I
                                                         enoN  j
                                                                                PROPERTY OF
                                                                                 FEDERAL
                                                                                GOVERNMENT
                                                                                    n
                    FORMER RAILROAD
                    ROAD
                    NOP BOUNDARY
                    LAND USE BOUNDARY
                                                                                  2000   4000

                                                                             APPROXIMATE SCALE IN FEET
U S  ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                                 101

-------
                                                                        Former NOP OU-1
•      In 1959, the facility was transferred to the General Services Administration  Over the next
       several years, parcels of the property (totaling approximately 3,000 acres) were retained by
       the Army, Air Force and the Department of Commerce

•      In 1962 and 1964,10,200 acres were transferred to the University of Nebraska for
       agricultural research  The remaining land was sold to various private individuals and
       corporations

•      A fireworks company operated in the Bomb Booster Assembly Area from 1969 to 1989

•      Since closure of the NOP, the property has been used primarily for agricultural production
       and research

Site Investigations (1):

•      An archives search was performed in 1983 by the U S Army Toxic and Hazardous Materials
       Agency (USATHAMA)  The documents located during this search  indicated that the most
       likely areas of explosives contamination at the NOP facility were the four Load Lines, the
       Booster Assembly Area and the Burning/Proving Grounds

•      PCB investigations were performed by the following groups in the years listed

              University of Nebraska -1984 and 1985
              USEPA-1988
              USAGE-1993

•      In 1989, the USAGE investigated soil, sediment surface water and  groundwater at the site

•      In 1990, a shallow soil gas survey was performed at the site

•      In 1991, the USAGE conducted soil and unexploded ordnance (UXO) investigations

•      In 1991, a preliminary health assessment for the site was conducted by the Agency of Toxic
       Substances and Disease.Registry (ATSDR)

•      In 1991 and 1992, a Remedial Investigation was performed for operable unit (OU) 1 by the
       USAGE  Results of this investigation indicated that explosives contamination was present in
       the shallow soil in several areas at the former NOP facility

•      In 1991, the USAGE performed a Supplemental Soil Remedial Investigation for OU 1

•      In 1995, a Record of Decision (ROD) was signed for OU 1

•      In 1996, a soil investigation for polychlormated biphenyls (PCBs) was performed at the NOP
       facility

The investigation and remediation at the former NOP facility has been divided into three OUs by the
USAGE in consultation with the USEPA and the Nebraska Department of Environmental Quality
(NDEQ)  The OUs are described as follows

•      OU 1 includes remediation of shallow (less than 4 feet below ground surface (bgs))
       explosives- contaminated soil

•      OU 2 includes remediation of contaminated groundwater, volatile organic compound (VOC)-
       contammated soil and explosives-contaminated soil deeper than 4 feet bgs

•      OU 3 includes remediation of the on-site landfill and other disposal areas not identified in the
       Inter-Agency agreement (IAG) among the USAGE, USEPA and NDEQ

In addition, it was determined by the USAGE, in consultation with USEPA and NDEQ, that PCB-
contaminated soil would be addressed separately from OU 1 soils
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          102

-------
                                                                      Former NOP OU-1
SITE LOGISTICS/CONTACTS

William J Crawford, P E
USAGE
HTRW Center of Expertise
12565 West Center Road
Omaha, Nebraska 68144-3869
(402) 697-2579

Edwin Louis, PM
USACE
Kansas City District
700 Federal Building
Kansas City, Missouri 64106-2896
(816)983-3563

Kevin Birkett
USACE
CENWO-CD-QA-KBIRKETT
215 North 17th Street
Omaha, Nebraska 68102
(402)221-4271

Jennifer Young
USACE
Ft Crook Area Off ice
PO Box13287
Offutt AFB, Nebraska 68113
(402) 293-2566

Troy Bendenkamp
NDEQ
Suite 400, The Atrium
1200 N Lincoln Street
Lincoln, Nebraska 68509-8922
(402)471-2214

Craig Bernstein
USEPA Region VII
726 Minnesota Avenue
Kansas City, Kansas 66101
(913)551-7688

Gregory McCartney
OHM Remedial Services Corporation
16406 US 224 E
Fmdlay, Ohio
(419)425-6003
                    MATRIX AND CONTAMINANT DESCRIPTION
MATRIX IDENTIFICATION

Soil (ex situ)

SITE GEOLOGY/STRATIGRAPHY

The NOP subsurface consists of four discreet Pleistocene-age unconsolidated layers consisting of
alluvial and eolian (wind-deposited) material overlying sedimentary bedrock  The surficial deposits
consist of a gray to brown sand and gravel alluvium that is up to four feet thick Beneath the surficial
alluvium is the clayey silt, silt, and silty clay Peoria Loess unit that ranges in thickness from 2 to 27
feet  Beneath the loess deposits is the Todd Valley Sand Unit, which is a 35 to 90 feet thick unit

U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office

-------
                                                                          Former NOP OU-1
consisting of gray to yellow-brown, very fine to coarse sand  The deepest unconsolidated layer
consists of the Grand Island-Crete Sand and Gravel Unit, which is a predominantly gray to yellow-
brown, fine to coarse sandy gravel unit, that is 0 to 55 feet thick

Sedimentary bedrock that underlies the unconsolidated material consists of Cretaceous-age shales
and sandstones of the Omadi Formation  Depth to bedrock beneath the NOP site ranges from 48 to
150 feet below grade The shallower shale is brown-yellow to green-gray, non-calcareous,
micaceous, and moderately hard  The shale overlies a yellow to orange, poorly to moderately
cemented, fine to medium grained, quartzitic sandstone  The Cretaceous-age bedrock overlies older
Pennsylvanian-age shale and limestone bedrock

Groundwater beneath the NOP site is first encountered in the unconsolidated Pleistocene sands and
gravels Groundwater is also present in the deeper sandstone bedrock  Where present, the shale
bedrock will act as an aquitard that separates the sand and gravel aquifer from the deeper sandstone
aquifer. Average transmissivities for the sand and gravel and sandstone aquifers are 69,000 gallons
per day per foot (gpd/ft) and 196,000 gpd/ft, respectively  Groundwater beneath the NOP site flows
in a south-southeasterly direction under a hydraulic gradient of approximately 115 feet per mile

CONTAMINANT CHARACTERIZATION m

Primary Contaminant Group.  Explosives/Propellants

Key Specific Contaminants:

2,4,6-Tnnitrotoluene (TNT)
Hexahydro-1,3,5-tnnitro-1,3,5-tnazme,  or cyclonite, or research department explosive (RDX)
1,3,5-trmitrobenzene (TNB)
2,4 and 2,6-dmitrotoluene  (DNT)
1,3-dmitrobenzene  (DNB)
Octahydro-1,3,5,7-tetranitro-1,3,5,7-tetrazme (high melt explosive or HMX)
2,4,6-tetranitro-n-methylanilme (tetryl)
o-nitrotoluene (o-NT)
m-nitrotoluene (m-NT)

CONTAMINANT PROPERTIES (5. 6. 7.10.131

Table 1 lists selected properties for several of the contaminants present at the NOP site

                             Table 1.  Contaminant Properties
Property
Chemical
Formula
Molecular Weight
Specific Gravity
Vapor Pressure
Octanol-Water
Partition
Coefficient
Soil-Water
Partition
Coefficient (K,)
Units
-
g/mole
-
mm Hg
logK™
L/kg
TNT
C7H5N306
22713
1 654
(20°C)
1x10^
(20°C)
1 65-2 83
38
(soil)
RDX«*
C3H6N606
22226
1 82
(20°C)
1x10^
(25 °C)
081-1 41
616
(bentonite)
«
C6H3(N02)3
21311
1 76
(20°C)
22x10"
(25°C)
1 18
NA
? W OUT*
C6H3CH3(N02)2
18213
1 521
(15°C)
217x10"
(25°C)
1 88-2 77
2512
NA - Not available
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           104

-------
NATURE AND EXTENT OF THE CONTAMINANTS (10. I'M
                                                                         Former NOP OU-1
The results of the Rl indicated that explosives-contaminated soil was present in the following areas

•      All four Load Line Areas,
•      The Burning/Proving Grounds,
•      The Bomb Booster Assembly Area, and,
•      The Administration Area

Contamination was predominantly located in areas in and around sumps and drainage ditches at
each area Because the contaminated areas at OU 1 were numerous and spread across large areas
of the NOP facility, it is not practical to show the areal extent of contamination in this report  Based
on data collected for the Rl, it was estimated that approximately 9,200 cubic yards of soil was
contaminated in OU 1

During remediation activities, it was determined that contaminated soil volumes were  greater than
originally estimated  In addition, some of the soil excavated was contaminated with PCBs, and was
therefore sent off site for disposal  Actual contaminated soil volumes from each area at the facility
are listed below It should be noted that all volumes listed are based on surveys of the excavations
and do not account for expansion of the soil during excavation

   	Table 2. Actual Contaminated Soil Volumes Excavated at the NOP Facility	
      sir    &
                                     ,
                             (cubifc yar

  Load Line 1
39237
1223
38014
  Load Line 2
42876
 82
42794
  Load Line 3
15703
1799
 13904
  Load Line 4
 191 3
374
 1539
  Burning/Proving Grounds
3431 2
 250
3181 2
  Administration Area
 1924
                       1924
  Bomb Booster Assembly
  Area
 106
                       106
  TOTALS
136071
5978
130093
The total volume of soil processed through the incinerator was 13009 3 cubic yards  This volume,
when converted to mass was equal to 16,449 tons  Based on this conversion, the average soil
density was equal to 93 7 pounds per cubic foot

CHARACTERISTICS OF UNTREATED SOIL M. 3^

Soil samples were collected from vanous depths and at several locations during the 1991 Rl and the
1992 Supplemental RI/FS Selected results from these samples are shown in Table 3
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           105

-------
                                                                      Former NOP OU-1
                      Table 3. Characteristics of Untreated Soil (1)
IP I- I ""
I 1 ' , 1 ' II , -
1 , 	
i T ,
1 Sample Location
Load Line 1
Load Line 2
Load Line 3
Load Line 4
Booster Assembly Area
Burning/Proving Grounds
Administration Area
Pnmary Area
T"' MWfti
: "iif|
.«*$
(mg/
num '
f'l'"']' ;
UM
&
133,000
176,000
29,700
131
70
313
0314
045
y W^J7m f ~
t J. Tf> V <*P|!f ^ t
396
23,270
404
227
ND
1,700
ND
ND
, 't^ffiufex «.
<^%*$M 's
Cortoempaiion^
ffcund ,-..,*.
l^tW9^s)^^.
338
430
953
60
36
353
ND
ND
Maximum DNT
Jtohceirtration
Pound (mg/kg)
289
1193
148
176
ND
125
ND
ND
ND - not detected

MATRIX CHARACTERISTICS AFFECTING TREATMENT COST OR PERFORMANCE (Si

Table 4 lists selected characteristics of untreated soil from the former NOP facility

                            Table 4  Matrix Characteristics
Soil Classification
Clay Content and/or Particle Site Distribution
Soil Plasticity
Moisture Content (%)
Porosity
Total Organic Carbon
BTU value (BTU/lb)
Halogen Content
Metal Content or the Presence of Metals
Presence of Alkali Metal Salts
USCS Soil Type CLandCH
88 to 100 percent silty and clay
0 to 12 percent sand
Information not available
1682*
Information not available
Information not available
1220*
Information not available
Information not available
Information not available
*Average value from the tnal bum test
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         106

-------
                                                                      Former HOP OU-1
                        TREATMENT SYSTEM DESCRIPTION
PRIMARY TREATMENT TECHNOLOGY (4)

Incineration

A mobile rotary kiln incineration system was used for this project, including the following

•      Solid waste screening to remove debns larger than 2 inches,
•      Solid waste feed system (dual-screw feeder), and
•      A refractory bnck-lined, propane-fired (oxygen-ennched), co-current rotary kiln

SUPPLEMENTARY TREATMENT TECHNOLOGIES (41

Post-Treatment (hot flue gas) - Incineration (secondary combustion chamber)
Post-Treatment (hot flue gas) - Baghouse
Post-Treatment (hot flue gas) - Quench (scrubber)

TIMELINE 12. 3)
                            Community Relations Plan prepared and issued
                            Proposed Plan for the site released by USAGE and USEPA
         June 1995
Gn-site incineration accepted as the recommended alternative by
NDEQ
        August 1995
ROD signature by USEPA Region VII Administrator Project
Plans, Tn?l Bum Plan and Site Design accepted by USAGE,
USEPA and NDEQ
        January 1997
Notice to Proceed issued to OHM for OU 1 Delivery Order
       February 1997
Begin site work atOU1
         March 1997
Preconstruction Meeting
         May 1997
Begin incinerator set up
         July 1997
Incinerator set up completed
   August - September 1997
Incinerator start up and shake down
       September 1997
Incinerator Mini Bum and Trial Bum tests performed
      October 14.1997
Begin full-scale operation of the Incinerator
     December 21,1997
Remediation completed, incinerator shut down
   January 5 -May 22.1998
Demobilization of the Incinerator and site restoration
TREATMENT SYSTEM SCHEMATIC AND TECHNOLOGY DESCRIPTION AND OPERATION

Figure 3 shows a process flow diagram for the mobile incineration system used to treat ex-situ soil at
the former NOP facility

Mobilization (2)

The contractor began mobilizing to the site on February 24, 1997 A proconstruction meeting was
held on March 29, 1997

Construction (2)
Incinerator construction was started on May 27, 1997 and completed on August 29, 1997
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         107

-------
_______._-____—-——————.^—^—————  Former NOPOU-1

Operation (2.3.9)

The treatment system was operated using the following steps

•      Contaminated so. was excavated from previously designated areas, transported to the feed
       preparation area and screened to remove oversized particles  Excavation sampling was
       performed to confirm that dean up criteria were met for soil remaining in-place
       Contaminated soil was blended pnor to treatment to equalize contaminant levels in the feed
       stream

•      Contaminated soil was fed through a grizzly screen onto a variable speed feed belt, weigh
       belt conveyor, and into the kiln feed hopper The waste stream was delivered from the
       hopper to the kiln via dual water-cooled feed screws

•      The pnmary kiln was 45 feet long and had an inside diameter of 6 5 feet The kiln was
       operated co-currently with the waste feed located at the same end as the oxygen-propane
       burner  Contaminated soil traveled through the kiln via gravity The kiln was designed to
       operate at exit gas temperatures of 1150 to 1800°F

•      Solids exiting the kiln were conveyed to a wet ash storage area for stockpiling and
       compliance sampling Hot flue gases were quenched using water nozzles in the kiln breech
       and in the duct cooler after exiting the kiln

•      Kiln gases then passed through a baghouse for removal of paniculate matter and submicron
       heavy metals The baghouse was designed to operate at a maximum temperature of 500°F

•      Exhaust gases from the baghouse were fed to a secondary combustion chamber (SCC)
       The SCC was designed to be operated at 1800°F with a gas retention time of 2 seconds

•      Exhaust gases from the SCC were cooled from 1800°F to 180°F with water in a quench
       tank. The tank was level controlled  The pH was maintained between 6 5 and 8 0 by addition
       of hydrochloric acid to the spray water circulation line  The quench tank was followed by a
       mist eliminator

•      An induced draft (ID) fan drew gases througi. the entire system and discharged to the stack
       at the end of the treatment system  The fan produced negative pressure throughout the
       treatment unit, including within the kiln

A mini bum test (three runs) was conducted  on September 17 and 18,1997 A trial bum test (four
runs) was conducted from September 22 to September 29,1997  A total of 1376 tons of
contaminated soil was treated during the mini bum and trial bum tests

In addition to the incineration system, a wastewater treatment system was installed and operated at
the site  The following sources of wastewater were encountered during this project-

•      Wash water from equipment and personnel decontamination activities,
       Rain water collected from the soil excavation cavities,
•      Quench tank blowdown, and,
•      Rain water collected in the incineration processing area
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waete and Emergency Reeponee
Technology Innovation Office

-------
                                             Figured. Process Flow Diagram
                                                                                                          FomwNOPOU-1
         NOP2.MC DC-KIE »/'/»•
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                                           109

-------
——^———_———^_—  Former NOP OtM

The wastewater treatment system consisted of the following units and treatment steps-

       wastewater storage tanks;
       chemical precipitation,
       flocculation,
       sand filtration,
       carbon absorption,
       bag filtration.
       pH adjustment, and,
       a sludge filter press

Post-Operation (3)

When soil treatment operations were completed, the treatment system was shut down and
dismantled for demobilization from the site Areas where contaminated soil had been excavated
were filled with dean soil taken from other areas at the NOP facility  Treated soil was returned to a
large on-site excavation.  The reason for placing all of the treated soil into one excavation was to
provide a source of sterile soil for planned agricultural experiments to be performed by the University
of Nebraska As part of demobilization, OHM graded disturbed areas, repaired damage to facility
roads, and placed topsoil where necessary to support planting of grass in the future Based on an
agreement between the USAGE and the current owner of the site, The University of Nebraska, the
disturbed areas will be seeded by The University of Nebraska. The costs for seeding will be paid by
the USAGE

Treatment system demobilization and site restoration activities (other than University of Nebraska
seeding) are scheduled to be completed on May 22,1988

OPERATING PARAMETERS AFFECTING TREATMENT COST OR PERFORMANCE (31

The following table lists operating limits for the Incineration system that were approved by the
USEPA and NDEQ prior to full-scale operation of the system
  Waste
 6 6 hourly raffing average
19 6 Instantaneous	
  Nln Draft, Maximum, inches we
-0 50 audible alarm
•01 (10 sec delay)
00 Instantaneous
  KHn Temperature. Minimum. *F
1416. Instantaneous
  SCO Temperature. Minimum. «F
1825. Instantaneous
  Stack Gas Velocity. Maximum, ft/sec
2133
      Home Pressure Drop. Mta. Inches we
1 0
      Quench Water Fkw, Minimum, gpm
397 4 alarm
350 Instantaneous
                                            65-80
             i, Maximum, ppmv
100 ppmv (10 sec delay)
200 ppmv Instantaneous
(may resume feed after i5 minutes operating s100
ppmv)
  KHn Rotation. Maximum, rpm
                                                        I average
we-water column
gpm - gallons per minute
CO • carbon monoxide
ppmv - parts per million (by volume)
rpm - revolutions per minute

The following table lists values for parameters associated with operation of the incinerator at the
former NOP site The parameters were selected for this report based on USAGE guidance
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          110
                                                                        ForrmrNOPOU-1

-------
                                                                       Former NOPOU-1
  Oxygen Flow Rate
                               2.5 tph
Gas Residence Time in Rotary
Film
System Throughput (tph)
Kiln Minimum Temperature (°F)
SCO Combustion Temperature
(°R
5 3 seconds
(at 18 tph and
1200°F)
18
1150-1800
1800
NA
166 (average)
196
(instantaneous)
1416
1825
8 5 seconds*
(average)
13.44 (average)
1416-1616
1825-1950
NA-Not Applicable
tph-tons per hour
* Calculated based on 13 44 tph and 1516°C in the kiln
                       TREATMENT SYSTEM PERFORMANCE
PERFORMANCE OBJECTIVES
The following table lists the treatment compliance objectives for the MOP Incinerator  These
objectives were established during the mini and trial bum tests and were approved by USEPA and
the USAGE
                       Table?.  Treatment
  POHC Destruction and Removal Efficiency (DRE)
  Hydrochloric Add Stack Emissions
£40 Ib/hr or 2 99 % removal
  Carbon Monoxide Stack Emissions
The following table lists the concentration objectives for soil treated in the incinerator operated at the
NOP facility  These objectives were established In the ROD for OU1
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         111

-------
                                                                        Former HOP OU-1
                             Table a Treated Soil
HMX
RDX
TNB
DNB
TNT
DNT
NT
Tatryl
1,7152
5.8
1.7
34
172
09
3430
343.0
In addition to treatment objectives for explosive compounds, Created soil (ash) also had to be below
the following TCLP (or corresponding total) concentrations before it could be returned to the site as
fill material. These requirements are outlined in the ROD for OU1.
           Barium
1000
2,000
         Cadmium
 10
 20
         Chromium
 50
 100
            Lead
 5.0
 100
          Mercury
 0.2
  4
           Silver
 5.0
 100
          Selenium
JLSL
 20
* Total concentrations are based on 20 times TCLP values

TREATMENT PLAN f31

Following construction of the incinerator in August 1997, a mini bum test was performed This test
consisted of three runs conducted on September 17 and 18 Contaminated site soils spiked with
naphthalene were used for the test  The three runs confirmed that the incinerator could meet several
significant performance criteria, Including destruction and removal efficiency (DRE), paniculate
emissions, HCI emissions and backfill requirements (allowable ash concentrations). The following
table summarizes the results of the mini bum test
gr/dscf - grains per dry standard cubic foot
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                           112

-------
 . .-'   •	      i • i   .ii.ii                    	        Former HOP OU-1

Based on the results of the mini bum test, a tnal bum test of the incinerator was performed The test
consisted of four runs (run three was repeated) conducted from September 23 to 29  Table 11 lists
the operating parameters dunng the various tnal bum runs
            Table 11. Trial Bum Process
Waste Feed Rate
Win Discharge
Temp
SCO Temperature
Secondary
Oxygen
Kiln Draft
Baghouse
Pressure Drop
Stack Carbon
Monoxide
SCC Quench
Recycle
Kiln Oxygen
Scrubber pH
Stack
Temperature
Stack Row Rate
SCC Draft
Kiln Rotation
Stack Oxygen
tons/hr
°F
°F
%
inches we
inches we
ppmv
gpm
%
PH
°F
fps
inches we
rpm
%
1734
1,417
1,813
601
-1 72
161
00
399
693
706
184
2136
-2.20
207
998
1551
1,412
1,823
592
-1.98
151
00
398
636
736
185
2067
-242
198
978
1688
1,427
1,806
592
-191
154
00
398
645
745
185
2136
-239
197
978
1688
1,408
1,849
565
-1.93
191
01
397
740
756
185
2178
-252
222
903
Test 4 was a re-run of Test 3
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          113

-------
                               	                               Forn*r HOP OU-1

Table 12 lists analytical results for the contaminated soil fed to the incinerator (pnor to treatment)
during the trial bum test.
                  Table 12. Trial Bum Contaminated Soil Feed
Moisture. %
Heat Value,
BTU/lb
TNB, jug/kg
DNB.^q/kg
TNT.wg/kg
DNT.jua/kg
HMX.tfO/kg
NT, MO/kfl
RDX^o/ka
Tetryl, jwg/kg
Arsenic, mg/kg
Banum. mg/kg
Cadmium, mg/kg
Chromium,
Lead, mg/kg
Mercury, mg/kg
Selenium, mg/kg
f:j i TO J i iCT ITTaaa'
1 Naphthalene,
1 «o/ka
25
1,200
4.500
<510S
240.000
<510
<510
<510
<510
<510
<13
160
0.7
6
15
003
<13
6
190
158
2,100
5.800
<540
310.000
<540
<540
<540
<540
<540
5
160
0.8
6
14
003
<12
2
110
15.8
1,300
1,200
<490
150.000
<490
<490
<490
<490
13,000
5
170
1
8
15
0.04
<12
2
470
15.5
1,600
2,700
<510
160,000
<510
<510
<510
<510
1,500
5
150
08
7
14
003
<11
2
82
15.6
330
7,800
<440
76.000
<440
<440
<440
<440
3.000
NA
NA
NA
NA
NA
NA
NA
NA
<390
16.82
1,220
4.213
<491
165.000
<491
<491
<491
<491
4,506
7.6
160
085
7
145
0033
<11.8
27
273
•Metals and PHCs reported on a dry basis
"Represents duplicate sample.
'Estimated concentration below the reporting limit

Tables 13,14, and 15 list additional results from the Trial Bum including,
treatment soil concentrations, and baghouse ash concentrations

TREATMENT PERFORMANCE DATA
Treated soil (ash) was analyzed prior to disposal for parameters listed previously in this section
Explosives concentrations were compared to maximum allowable concentrations.  Total metals
concentrations were compared to 20 times the allowable TCLP concentrations  All results met the
explosives and metals treatment objectives with the exception of three samples, which did not meet
the total lead concentration requirement One of these samples was reanalyzed for total lead and
passed. The remaining two samples were reanalyzed for TCLP lead and also passed Starting on
December 12, all samples were analyzed for TCLP metals concentrations without first analyzing for
total metals concentrations Bypassing the total metals analysis step increased the analytical cost,
but allowed for more rapid determination of compliance with treatment criteria
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of SJId Watte and Emergency RttponM
Technology Innovation Office
                                          114

-------
                                                                                 FormorNOPOU-1
                            Table 13. Trial Bum Stack Gas
  2.4.6-Trl
                                        <37E-6
           <34E-6
             NA
          <35E-6
           <3.5E-6
           108E-2
  RDX.
 <3.7E-6
 <34E-6
 NA
 <35E-6
<3.5E-6
                                                      106E-1
  1,3.5-Trinttrobenzane. gfa
 <3.7E-6
 <34E-6
 NA
                                <175E-S
            8.2E-6
           282E-3
  LS-Dhiltrobenzene. gte
 <37E-6
 <34E-6
 NA
 <35E-6
                                           <3.5E-6
           811E-3
  a4-DWtrotoluena. (
                                        <37E-6
           <34E-6
             NA
          <3.5E-6
           <3.5E-€
           4.39E-1
 <37E-6
 <34E-6
 NA
 <35E-6
<3.5E-6
318E-1
  2,6-OWJrotoluene.afe
 <37E-6
 <3.4E-6
 NA
 <3.5E-6
                                           05E-6
           1.35E-1
  NHrotohiane. pto
                                        <37E-6
           <3.4E-6
             NA
                                                                        <3.5E-6
                     <3.5E-6
                      2.5E+0
  Nitrobenzene, gfls
 1.2E-5
 <55E-6
 NA
 <55E-6
<77E-6
6.38E-2
                                        <59E-6
           <5.5E-6
             NA
          <5.5E-6
           <5.5E-6
           180E-2
                                        <59E-6
           <55E-6
             NA
          <5.5E-6
           enzo(k)f»uoranthene. ate
 <81E-6
 <7.5E-6
 NA
 <76E-6
<77E-6
567E-2
  Chrysane, gfc
  PfcenzofarQanthracene. i
 <37E-6
 <34E-6
 NA
 <35E-6
<3.5E-6
1.90E+0
 <74E-6
 <69E-6
 NA
 <69E-6
<71E-6
                                        <44E-6
           <41E-6
             NA
                     <4.2E-6
                                                   10E-4
                                                             9.8E-5
                                  NA
                                                                                   1 1E-4
                                        34E-5
            35E-5
            41E-5
            NA
                                 37E-5
  Barium, gfs
 19E-4
 19E-4
18E-4
  NA
 19E-4
790E-5
                      2.08E-3
                                                      371E-2
1J27E+0
  BenBum.gts
                                        <86E-7
           <83E-7
           <8.3E-7
            NA
           <84E-7
                                                     410E+0
  Cadtntum, g^8
 29E-6
 58E-6
44E-6
  NA
                                            44E-6
                                           194E-1
  Chromium, g/s
 24E-4
 56E-5
            NA
                                            11E-4
                      1.55E-2
                                        17E-5
           <16E-5
           <17E-5
            NA
         i<17E-S
  Meroufy, gi's
 27E-4
 2.6E-4
21E-4
  NA
                                            24E-4
                                           422E-4
                                        21E-4
            44E-4
            10E-4
            NA
            2.5E-4
                                                                                             1.90E+0
                                                  <49E-5
                      5.9E-5
                        NA
                     <53E-5
                      190E-2
  Silver,
                                       <86E-6
                      1.5E-5
                        NA
                       1E-5
                      137E-2
  Thaaum. ate
           <49E-5
           <50E-5
            NA
                                           <50E-5
        i corrected to 7% Oxygen
 <063
  2.3
 4.5
  NA
 <2.5
                                 100
            tTEQ
 <0011
<00087
 NA
<00090
<00096
  NA
  PCDD/PCDFsTEQ
<77E-11
<54E-11
 NA
<56E-11
                               779E-9
NA-Results not available
g/s - grams per second
ng/dscm - nanograms per dry standard cubic meter
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                               115

-------
                                                                                       Former NOP OU-1
               Table 14.  Contaminant C
              Hone In Treated Soil Du
                                     4500
               3000
               2700
               2400
               NA
  1.3.5-Ttlnltobenzane. ua/kg
1500
               <490
               
-------
                                                                                        Former NOPOU-1
            Table 15.  Contaminant Concentrations
                                        During the Trial Bum
  1,3-Onltrobenene.^gAg
<490
<450
                <440
                <470
                                                               3400
  2,4.6-Trinltrotoleune. Mg/Kg
<490
<450
<440
                                                <470
                                               17200
  2.4-Dlnltroto>uene.ti8/kg
<490
<450
<440
<470
                                                                900
  2,6-DWtrottuene,ug/kg
<490
<450
<440
<470
                                                                900
  HMX.«g/fcB
<490
<450
                                                                <440
                <470
              1.715.200
              343.000
  m-Nttrotoluene, ^g/kg
<490
<450
<440
<470
  o*Nftotolu9ne, nfitoQ
<490
<450
<440
                                                <470
                                              343.000
  p-Nitrotaluene, usfno
<490
<450
                                                                <440
                                                <470
                                                              343,000
                                <490
                <450
                                <440
                                <490
                <450
                <440
                                 54
                 64
                 65
                                                 03
                                04
                                                
-------
                                                                        FormwNOPOU-f
Table 16 summanzes selected results from explosives analyses performed on treated soil piles
None of the treatment objectives for explosives compounds were exceeded in any of the treated soil
samples
                                          Results from Treated
HMX
RDX
TNB
DNB
TNT
2.4-DNT
2,6-DNT
60
60
60
60
60
60
60
0
2
0
0
25
0
0
MA
026-0.44
NA
MA
023-60
NA
NA
1,7152
58
17
34
17.2
09
0.9
NA-Not Applicable

Wastewater sample results were also compared to allowable concentrations for selected parameters
as specified in the NPDES permit application  Most of the samples met all of the requirements,
however, three samples exceeded the maximum daily allowable concentration for iron  The overall
average iron concentration for the project duration was below the allowable average concentration

In addition, the wastewater treatment system had difficulty meeting the proposed aluminum
concentration requirement throughout the project  On December 4,1997, OHM requested that the
discharge limit for aluminum be waived based on the fact that aluminum is a common background
element in the site soil, and because it was estimated that treated water did not leave the former
NOP facility before infiltrating in the ground Because this project was conducted under CERCLA
regulations, it was not necessary to obtain this permit, or a waiver for aluminum

PERFORMANCE DATA QUALITY

A sampling and analysis plan (SAP), included as part of the construction quality control (CQC) plan,
was used for excavation sampling and for treated soil sampling performed on this project  A total of
549 soil samples were collected from excavation bottoms and sidewalls.  Results from the soil
samples were used to determine if additional excavation was necessary in each area. Each of the
60 treated soil piles was sampled individually  Treated soil samples were collected as composites to
accurately represent each pile  Results from the treated soil samples were used to determine if
treated soil could be returned to the site as fill material.
                             TREATMENT SYSTEM COST
PROCUREMENT PROCESS f!2l

OHM Remediation Services Corp. was selected to design, construct, test and operate the
incineration treatment system for this site.  The contract bid quantity for this project was 9600 tons of
contaminated soil The bid price for this quantity was $6,748,302. This price translates to $703 per
ton of contaminated soil.

Because OHM had performed the initial design that was approved by the regulators, they were
•elected to perform construction and operation of the thermal treatment unit  OHM subcontracted
with the following companies to perform the listed project tasks
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Offlct
                                          118

-------
———————————————^———_  Former MOP O(M

Subcontractor
Judds Brothers Construction       Grading, forming and placement of concrete foundations for the
                                thermal treatment unit, the feed preparation building, the oxygen
                                vaporizer, the propane tank saddles and the ash storage pad
                                Construction of the feed storage building

Davis Crane and Rigging              Crane services for set up and teardowi

Miller Electric                    Electrical wiring for the treatment plant

Butler County Landfill             Disposal of non-TSCA regulated PCB-contaminated soil

Kobus Construction               Transportation of non-TSCA regulated PCB-contaminated soil to
                                the Butler County Landf i!'


TREATMENT SYSTEM COST tS\

The total project cost for remediation of OU 1 soils at the former NOP facility was $10,700,001. The
total mass of soil treated was 16,449 tons Therefore, the cost for treatment was $650 per ton of
contaminated soil Table 17 summarizes the costs for construction and operation of the incineration
system

COST SENSITIVITIES

According to the Feasibility Study, changes in the volume of soil to be treated would cause the
project cost to change significantly This was the only parameter that was identified in the Feasibility
Study as a significant source of cost sensitivity
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office

-------
                                                                                                      Former MOP CXM
m 	 i aote i i. summary OT i reanmm vonm m HUK. warogonzeo Accorqing ro nw WBS IBJ
BBHH
33101
33101 01
33101.01 01
33101 01.02
33101 01 03
33101 01 04
33101 01 04.24
33101 01 06
33101.02
33101 02 09
331010211
33101.03
33101.0302
331010304
33101.0306
3310105
33101 05.07
3310106
331010801
33101 14
33101 1401
33101 14.01 05
33101 140106
33101.14.01 07
33101 14 01.09
33101 14 50
tm&ems&s&mam^fori^^Mud* • jjaam
H I'RW Remedial Action (Construction)
tori zation and Preparatory Work
toW rat on o Construction Equipment and Facilities
Mobilization o Personnel
Submitted/Implementation Plans
Setup/Construct Temporary Facilities
Security Fencing
Construct Temporary Fencing
Temporary RefocattonaVRoads/Structures/Utilities


Laboratory Chemical Analysis
Geotechnksal Testing
Includes testing for the concrete slab
Siteworfc
Clearing and Grubbing
Roads/Parking/Curbs/Walks
Electrical Distribution
Indudes transformer and connection fees
Surface Water Collection and Control
Sediment Barriers
Solids Collection and Containment
Contaminated Soil Collection
Digging, dean pit, includes hauling, includes dean cover
Thermal Treatment
Indneration
Mobilization/Setup of Portable Treatment Plan
Mob of all equipment to set up the temporary incinerator
Startup
Trial Bum
Demobilization of Portable Treatment Plant
40 trucks were used in demoting the equipment from the
incinerator
O&M of Permanent Treatment Plant During Construction
Plant was not constructed to operate in winter conditions, yet
the plant was winterized since the operations were extended
due to finding more contaminated soil
Construction of Permanent Plant Facility
Construction of a Metal building that will be left on site for the
owner to OCCUDV Size of metal buildina 8ffx\2ff
BB^

100
100
100

2,40000
100

100
100

700
1,00000
1,10000

20000

13,60700


100
100
100
400
100


EA
EA
EA

LF
EA

EA
EA

ACR
SY
LF

LF

CY


EA
EA
EA

EA
?•:$ '^l-i^i •» • i&'T.''' •'.;

113,59400
68,110.00
571.219.00

740
1.37900

173.51200
18,11700

4,59500
620
4183

1530

5548


2,133,01500
708,12000
601,23000
759,22000
730,80000
772.06200
113.59400
68.11000
571.21900
17.760.00
17,76000
1.37900
191.62900
173.51200
18,11700
84.37800
32.16500
6.20000
46,01300
3.06000
3.06000
754,916 38
754,916 38
7.210.045.00
6.479.245 00
2,133,015 00
708,120 00
601,23000
3,036,880 00
730,800 00
US ENVIRONMENTAL PROTECTION AGENCY
Office of SoW Waste and Emergency Response
Technology Innovation Office
                                                         120

-------
••••
33101.19
33101 1921
33101.1922
3310120
331012001
3310120.03
33101200301
3310120.04
3310121
3310121 01
3310121.01 24
3310121 04
3310121.05

HBHHHBHB99HBEQH
Disposal (Commercial)
Transportation to Storage/Disposal Facility
Di
Si
Isposal Fees and Taxes
te Restoration
Earthwork
hauling and backfill
Permanent Features
Roads
Repair of existing roads on site
Revegetation and Planting
University of Nebraska is doing all the revegetation
Demobilization
Removal of Temporary Facilities
Security Fencing
Removal of temporary fencing
Demobilization of Construction Equipment and Facilities
Demobilization of Personnel

E3B9I
125000
1.25000

13,60700

15,00000
1100


2,40000
100
100


TON
TON

CY

SY
ACR


LF
EA
EA


1470
7980

8320

1000
15300


250
207.000.00
69,000.00
onnwnur uu-7
PBBI
118,12500
18.375.00
99.75000
1.283.78538
1,132,10238
150.00000
150,00000
1,68300
282.00000
6.00000
6,00000
207.00000
69.000.00
•IK r, P. i»ra m p [<^/:
-------
__^__-_—^_-—-——^—-—-——————————————— Form* HOP OU-1

It is possible that overall project costs could have bean reduced by using a unit price payment
schedule instead of alime and materials schedule  If unit pricing (payment per mass of soil treated)
had been used, the USAGE would not have incurred labor and equipment costs during down time
associated with equipment failure or material handling problems The element of nsk assumed by
the contractor on this project created an inherent difficulty in negotiating the cost of remediation
under a unit price payment schedule  Because this contract was negotiated under a pre-placed
remedial action contract, and with a short procurement schedule, it was difficult to determine a
"reasonable cost" for the risks assumed by the contractor It is recommended that project managers
use competitive procurements for future unit price incineration projects.
                       REGULATORY/INSTITUTIONAL ISSUES
Because this project was performed under CERCLA regulations, it was not necessary to obtain
permits from local regulatory authorities for on-site activities  It was necessary, however, to meet the
substantive requirements of potentially applicable regulations  The following permitting and public
relations issues were addressed on this project

•      A NPDES permit application was submitted for wastewater discharges associated with the
       thermal treatment system  For reasons discussed above, a permit was never issued  Dunng
       treatment operations, a problem arose with treatment of aluminum It was subsequently
       speculated that the elevated aluminum concentrations in the wastewater were a result of
       high aluminum background concentrations in the site soil

•      A public meeting was held on October 13,1997 to discuss the operating limits of the
       incineration system  The operating limits that were approved at this meeting are presented
       at the beginning of this section  Treatment of contaminated soil began the next day (October
       14)

•      A permit for disposal of soil and debns from the NOP site at the Butler County Landfill was
       issued on October 21,1997 This permit was necessary to handle any material that was too
       large to be processed through the kiln
                     OBSERVATIONS AND LESSONS LEARNED
COST OBSERVATIONS AND LESSONS LEARMED

Project costs were higher than expected due to the increased volume of contaminated soil that was
encountered during excavation  These additional costs could have been accounted for during the
procurement process if site investigations had more accurately delineated the extent of
contamination

Additional costs were also incurred due to shut down of the system during a penod of inclement
winter weather These costs could have been avoided if the system had been operated during a
warmer portion of the year.  Because the project was performed under a tight time table, it is unlikely
that these additional costs could have been avoided
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          122

-------
——^——.^—_—.^_____ Former HOP OU-1

It is recommended that better planning and scheduling be performed during the procurement phase
on future similar projects  Because the project schedule was so tight, the USAGE lost some
leverage dunng contracting negotiations

PERFORMANCE OBSERVATIONS AMD LESSONS LEARNED

Dunng operation, the most sensitive aspect of the treatment system was the soil feed system  On
several occasions the incinerator had to be shut down to address issues with the feed system.  It is
recommended that future projects of this nature place increased emphasis on selecting and
designing the most appropriate feed system

Unexpected problems associated with handling of high and low moisture-content soil were observed
on several occasions dunng treatment These problems were chiefly observed in the feed system. In
addition, a recurring problem  was observed relating to separation of extremely fine soil particles
dunng treatment  This fine material became suspended at the top of the wet ash conveyor, and
when the suspension became thick enough it would inhibit discharge of solids from the bottom of the
tank  This problem was ultimately solved by periodically pumping the suspended soil to the ash
handling area where it was gravity dewatered and filtered through hay bales  It is recommended that
future projects of this nature include preliminary study of the handling charactenstics of the soil to be
treated  In addition, it may be beneficial to include pilot-scale testing as part of the system design.
This would allow the design team to identify problems similar to those described above pnor to full-
scale operation

OTHER OBSERVATIONS AND LESSONS LEARNED f14l

It is recommended that future projects Include a preliminary meeting with field office personnel and
CX personnel  The purpose of this meeting would be to provide insight regarding past projects of a
similar nature

The primary remedial action objective was to eliminate the potential for dermal exposure to
contaminants in the soil at the site  To achieve this objective, the top four feet of soil was excavated
and incinerated in areas identified as being contaminated. Additional areas were excavated to
remove potential sources of groundwater contamination  Contaminated areas were identified in the
vicinity of the former load lines based on historical records that descnbed discharge of contaminated
wash water dunng facility cleaning activities

Site conceptual model assumptions from the remedial investigation did not correlate in all cases to
observations made in the field dunng soil excavation activities  For example, a substantial volume
of additional contaminated material was found at the Burning/Proving Grounds The contaminants
were placed in this area by burning and burial of explosive materials, not by discharge of
contaminated surface water  Therefore, the site conceptual model did not predict the presence of
large pieces of unbumed explosives in the subsurface at this site Unbumed explosives were
observed at depths between 4 and 12 feet bgs dunng excavation at the Burning/Proving Grounds

Discrete soil sampling may not have been appropriate for characterizing this explosives-
contaminated site  Explosives are solid at ambient temperature, dissolve slowly and sparingly in
aqueous solution and have low vapor pressures  These properties can restrict the transport rates of
these contaminants in soil, especially when compared to rates for other contaminants, such as fuels
or solvents  Typically, areas of high explosives contamination will remain at or near the ground
surface at the point of deposition, unless the soil containing the contamination Is physically moved.
Too often, local spatial heterogeneity Is ignored In favor of sampling, based on the theory that
heterogeneity will be accounted for if the number of samples is sufficiently large.  At this site,
heterogeneity of contamination was not properly accounted for by characterization soil sampling
Although it Is possible to over-characterize a site, project planners may increase the efficiency  of
remedial actions by performing a combination of composite sampling, field homogenlzation of
samples and on-slte colorimetric analyses.  This type of characterization will produce data that  are

U 8 ENVIRONMENTAL PROTECTION AGENCY                                   '     ——
Office of Solid Waste and Emergency Response
Technology Innovation Office

-------
                                                                        Former NOP OU-1
accurate and precise, but that also may be more representative of site conditions  It is also
recommended that the type of characterization sampling be selected based on the nature of
contaminant deposition  This may necessitate varying sampling methods in different areas at a
single facility

To ensure proper blending of contaminated soil prior to incineration, it is recommended that any
identified "hot spots" be remediated prior to incineration. This will help ensure that the feed material
to the incinerator remains uniform during treatment operations

A problem with freezing of a water line was encountered on one occasion dunng operation of the
treatment unit  it was subsequently determined that the buned water line had frozen due to its
proximity to a liquid oxygen line During a period of low air temperature, the sheath of ice that
typically surrounds a liquid oxygen line expanded and encompassed the water line  It is
recommended that future projects take into account this possibility when locating utilities

It is recommended that future projects include regular project team meetings or conference calls
The NOP project included a weekly conference call attended by representatives from the USAGE,
USEPA, NDEQ, and OHM Allowing a weekly forum for project communication helped facilitate
timely, efficient completion of the project

This project used an innovative procedure for obtaining timely approval of allowable airborne
contaminant emission rates from the treatment unit  Prior to performance of the mini brm or trial
bum tests, a list was developed of emission rates that met typical air permitting requirements  These
hypothetical rates were submitted to NDEQ and USEPA, and were  ultimately approved after review
and comments by the regulatory agencies When the mini bum and tnal bum tests were completed
and it was determined that the system could keep emission rates below the hypothetical rates, rapid
approval was obtained for full-scale operation of the system Full-scale production began
approximately two weeks followinr completion of the tnal bum test It is recommended that other
projects of this nature use this procedure if rapid approval of emission rates is desired
        REFERENCES
1)     Final Record of Decision. Operable Unit 1, Former Nebraska Ordnance Plant, Mead
       Nebraska, USEPA Region VII and USAGE Kansas City District, August 1995

2)     Draft Remedial Action Report. Former Nebraska Ordnance Plant, OU-1, Mead Nebraska,
       OHM Remediation Services Corporation, January 1998

3)     Incineration of Explosives Contaminated Soil at the Former Nebraska Ordnance Plant.
       William J  Crawford, P E (USAGE) and Kevin W Birkett (USAGE), January 8,1998

4)     Operation and Maintenance Manual. Mead Thermal Treatment Unit, Asset No  61027, OHM
       Remediation Services Corporation, August 1997

5)     The Merck Index. Eleventh Edition, Merck and Co, 1989

6)     Hawlev's Condensed Chemical Dictionary. Eleventh Edition. N  Irving Sax and Richard J
       Lewis,  Sr, 1987

7)     Handbook of Environmental Data on Organic Chemicals. Second Edition, Karel
       Verschueren, 1983

8)     Former NE Ordnance Plant Operation Unit #1. Single Project WBS Report - With Notes, no
       date provided.
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Reeponee
Technology Innovation Office
                                           ImrT

-------
                                                                     Former HOP OU-1
9)



10)



11)


12)



13)



14)
Memorandum - From John OToole, to File, dated September 23,1997, Re NPDES
PERMIT, Discharge Standards

Remedial Alternative Feasibility Study. Operable Unit 1. Former Nebraska Ordnance Plant.
RUST Environmental, September 22,1993
Supplemental RI/FS. Former Nebraska Avenue Plant. Operable Unit 1. Mead. Nebraska.
SEC Donohue, September 23,1992
Draft Remedial Action Report for the Fonner Nebraska Ordnance Plant. OU-1 ,?. Mead.
Nebraska. OHM Remediation Services Corporation, March 13,1998
Encyclopedia of Explosives and Related Items. PATR 2700, Volume 9, US Army Armament
Research and Development Command, 1980

Sampling Error Associated with Collection and Analysis of Soil Samples at TNT-
Contaminated Sites. T F Jenkins, et al, published in Field Analytical Chemistry and
Technology 1 (3) 151-163,1997
                               ACKNOWLEDGMENTS
This report was prepared for the U S Army Corps of Engineers under USACE Contract No
DACA45-96-D-0016, Delivery Order No 12
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                        125

-------
This Page Intentionally Left Blank
               126

-------
On-Site Incineration at the
 MOTCO Superfund Site
    Texas City, Texas
          127

-------
               Incineration at the MOTCO Superfund Site
                              Texas City, Texas
Site Name:
MOTCO Superfund Site
Location:
Texas City, Texas
Contaminants:
Styrene tars, VOCs, PCBs, and
metals
benzene, vinyl chloride, 1,1,2-
trichloroethane, lead, cadmium,
mercury, and chromium
Period of Operation:
May 1990 to December
-991
«  '^•^^•^••••••^^^•i^^HMMMMMMB
Cleanup Type:
Remedial action
Vendor:
IT Corporation
312 Directors Drive
Knoxville, TN 37923
(423)690-3211
SIC Code:
2865 (Industrial organic
chemicals)
Technology:
• Two incineration systems
  the Hybrid Thermal Treatment
  System* HTTS-2 and
  HTTS-3, HTTS-2 designed to
  process solids, sludges, tars,
  aqueous wastes, and organic
  liquids, and HTTS-3
  designed to process aqueous
  wastes and organic liquids

• Solids transferred to feed
  preparation building where
  materials were mixed and
  screened

• The HTTS-2 consisted of two
  chambers (the kiln and SCC)
  and a gas cleaning system
  consisting of a quench
  system, gas conditioner, wet
  scrubber system, and a vane
  separator; the HTTS-3
  consisted of a combustion
  chamber and a gas cleaning
  system

• Solids, sludges, and aqueous
  wastes fed to the HTTS-2 kiln
  by a screw conveyor; organic
  liquid wastes used as primary
  fuels in the kiln

• Residual ash from kiln
  collected, landfilled, and
  capped on site
Cleanup Authority:
CERCLA and State
Texas
• ROD signed 3/15/85
• RP-lead, EPA oversight
Point of Contact:
Ashby McMullan
Texas Natural Resources
Conservation Commission
(512) 239-1000
Wast* Source:
On site pits - styrene tars and
chemical wastes - wood
preserving wastes
Type/Quantity of Media Treated:
Soil, sludge, organic liquids, and aqueous wastes
• 10,471 tons aqueous wastes
• 7,568 tons organic liquids
• 283 tons sludges and tars
• 4,699 tons soH
                                        128

-------
                Incineration at the MOTCO Superf und Site
                               Texas City, Texas
                                    (Continued)
Purpose/Significance of Application:
Mechanical problems were encountered, caused in part by lack of accurate waste
characterization, onslte incineration halted in December 1991 because of dispute between the
contractor and RP; remedy changed to off-site incineration in part because of dispute and
mechanical problems
Regulatory Requirements/Cleanup Goals:
Destruction and Removal Efficiency (ORE) of 99 99% for each principal organic hazardous
constituent as required by Resource Conservation and Recovery Act (RCRA) incinerator
regulations In 40 CFR part 264, subpart 0,99.9999% ORE for PCBs as required by Toxic
Substances Control Act (TSCA) regulations in 40 CFR part 761
Results:
Emissions and performance data indicate that all ORE and emissions standards have been met
Description:
The MOTCO site was established in 1959 for the recycling of styrene tars From 1961 to 1968,
on-sfte pits that held styrene tars were used for the disposal of chemical wastes from local
industries In March 1985, a Record of Decision (ROD) that required source control was signed,
and in September 1989, a ROD that addressed off-site migration of contaminants was signed

The remedy selected for the first Operable Unit (OU-1) was off-site treatment and disposal of
contaminated material, however, the ROD specified that on-site incineration was a viable
alternative to be evaluated dui ing the design phase  A later Consent Decree required on-ate
incineration and established incinerator requirements

The site operated two incineration systems  The first system was called the Hybnd Thermal
Treatment System* 2 (HTTS*-2), and the second system was referred to as HTTS-3. The HTTS-
2 consisted of a rotary kiln, a secondary combustion chamber (SCC), and a gas cleaning system.
This incineration system processed solids, sludges, tars, aqueous wastes, and organic liquids
The HTTS-3 consisted of a combustion chamber and gas cleaning system identical to the SCC
and gas cleaning system of the HTTS-2  The HTTS-3 processed only aqueous wastes and
organic liquids

In December 1991, the HTTS-3 had passed the tnal bum and was performing under intenm
operating conditions, and the HTTS-2 was in the process of conducting a tnal bum when the
contractors stopped incineration and filed a lawsuit against the responsible party (RP) for breach
of contract. Due to the dispute and several technical problems (Including slagging), on-site
incineration did not resume

In January 1993, an Explanation of Significant Differences (ESD) specified off-site incineration of
the remaining sludges, tars and organic liquid  The remaining soil was to be capped on site

The cost incurred during the on-site incineration was approximately $76 million consisting of $20
million in capital costs and $56 million in operating costs.
                                        129

-------
                                                                    MOTCO Superfund Site
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-srte incineration at the
MOTCO Super! und site in Texas City, Texas
Incineration began in May 1990 but was halted
in December 1991 by a contractor dispute
Contaminants of concern at the site were  PCBs,
styrene tars, volatile organic compounds
(VOCs), and metals

The MOTCO site was established in 1959 for
the recycling of styrene tars.  The recycling was
discontinued in 1961 due to damage by
Hurricane Carta  From 1961 to 1968, on-site
pits that held styrene tars were used for the
disposal of chemical wastes from local
industries In March 1985, a Record of Decision
(ROD) that required source control was signed,
and in September 1989, a ROD that addressed
off-site migration of contaminants was signed
This report addresses the incineration specified
in the first ROD, unless otherwise stated

The remedy selected for the first Operable Unit
(OU-1) was off-site treatment and disposal of
contaminated material; however, the ROD
specified that on-srte incineration was a viable
alternative to be evaluated during the design
phase A later Consent Decree required on-site
incineration and set incinerator requirements
including a destruction and removal efficiency
(DRE) of 99 99% for each principal organic
hazardous constituent (POHC) and 99 9999%
for polychlorinated Wphenyls (PCBs)

The site operated two incineration systems  The
first system was called the Hybrid Thermal
Treatment System* 2 (HTTS*-2), and the
second system was referred to as HTTS-3  The
HTTS-2 consisted of a rotary kiln, a secondary
combustion chamber (SCC), and a gas cleaning
system.  This incineration system processed
solids, sludges, tars, aqueous wastes, and
organic liquids.  The HTTS-3 consisted of a
combustion chamber and gas cleaning system
identical  to the SCC and gas cleaning system of
the HTTS-2. The HTTS-3 processed only
aqueous wastes and organic liquids
In the rotary kiln, organic compounds from
the contaminated matenal were volatilized
and destroyed  The exhaust gases were
channeled to the SCC  The SCC provided
further combustion of organics in the off-
gases, which were then water quenched
Waste oils were used as fuel in the kiln and
SCC of the HTTS-2 and in the combustion
chamber of the HTTS-3

The gas cleaning systems for both
incineration systems consisted of a quench
system, a gas conditioner, a wet scrubber,
and a vane separator  The quench system
and gas conditioner removed paniculate
and acid gas  Caustic solution was sprayed
into the gas stream in the wet scrubber for
particulate matter and acid gas removal,
and the solution was then removed from the
gas stream by the vane separator

In December 1991, the HTTS-3 had passed
the trial bum and was performing under
interim operating conditions, and the HTTS-
2 was in the process of conducting a trial
bum when the contractors stopped
incineration and filed a lawsuit against the
responsible party (RP) for breach of
contract  Due to the dispute and several
technical problems (including slagging), on-
site incineration did not resume

In January 1993, an Explanation of
Significant Differences (ESD) specified off-
site incineration of the remaining sludges,
tars and organic liquid  The remaining soil
was to be capped on site

The cost incurred during the on-slte
incineration was approximately $76 million
consisting of $20 million in capital costs and
$56 million in operating costs
 U.S ENVIRONMENTAL PROTECTION AGENCY
 Office of Solid Waste and Emergency Response
 Technology Innovation Office
                                           130

-------
                                                                    MOTCO Superfund Site
                                  SITE INFORMATION
Identifying Information
MOTCO Superfund Site
Texas City, Texas

CERCLIS # TXD980629851

ROD Date: March 15,1985 (OU-1)
Rnclcaraund
Traatmant Annllcailon
Type of action: Remedial (on-site
incineration)

Period of incinerator operation:  May
1990-December 1991

Quantity of material treated during
application: 10,471 tons of aqueous
wastes, 7,568 tons of organic liquids, 283
tons of sludges and tars, and 4,699 tons of
soil
Historical Activity that Generated
Contamination at the Site:  Recycling styrene
tars and disposal of petrochemical wastes

Corresponding SIC Code: 2865 Industrial
organic chemicals

Waste Management Practice That
Contributed to Contamination: Disposal of
wastes is unlined surface impoundments

Site History:

•  The MOTCO site is located on the Gulf
   Coastal Plain at the edge of a coastal marsh
   system

•  The site is within 1/4 mile of the habitats of
   four endangered species in Texas (the
   Brown Pelican, the Arctic Peregrine Falcon,
   the Attwater's Frame Chicken, and the
   American Alligator) as listed in Endangered
   Species of Texas and Oklahoma  1980  [2]

•  The site recycled styrene tars from 1959
   until 1961 when flood waters from Hurricane
   Carla inundated pits containing the styrene
   tars  The pits on the site were then used
   until 1968 for disposal of chemical wastes
   from local petrochemical industries [12]

•  During this period, various solvent wastes
   were disposed of in seven unlined waste
   disposal pits. An estimated 500,000 gallons
   of material  was disposal of; some of this
Baekctmund /Cont.l
    matenal was removed dunng attempts
    at waste recycling in the 1970s [13]

•   The pit contained four layers of source
    matenal surface pit water (aqueous
    waste), organic liquids, sludges and
    tars, and soil The aqueous waste was
    acidic and contained metals and
    organics The organic liquid was
    igmtable and the primary contaminants
    werePCBs  The sludge/tar layer and
    the soil contained styrene tars, VOCs,
    and metals [1]

•   In 1980, the  US  Coast Guard removed
    drums, extended a dike around the
    perimeter of the pits, and erected a
    fence around the pits cPA conducted
    three emergency response actions
    (September  1981, March 1983, and
    September 1983) to treat and discharge
    excess aqueous liquid caused by heavy
    rainfall [3]

•   Two site investigations were conducted
    in 1981-82 and a Feasibility Study (FS)
    was completed in September 1984

•   The contaminated materials to be
    Incinerated were located in seven
    unlined pits covering a surface area of
    approximately 4 6 acres The OU-1
    ROD estimated that 62,200 tons of
    aqueous wastes,  13,920 tons of
    sludges/tars, and 31,950 tons of soil
    would require Incineration.
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          131

-------
                                                                    MOTCO Suparfund Sit*
                             SITE INFORMATION (CONT.)
•   Incineration began in May 1990, but ended
    in December 1991 when the remedial
    contractors filed suit against the RP for
    breach of contract. The dispute involved
    several operational problems discussed
    later in this report under Lessons Learned

•   In the time that the on-site incinerators
    operated, 10,471 tons of aqueous wastes,
    7,568 tons of oil, 283 tons of sludges/tars,
    and 4,699 tons of soil were incinerated
    When on-site incineration ceased, it *as
    estimated that approximately 8,100 tons of
    organic liquid, 10,100 tons of sludges/tars,
    and 61,600 tons of soil remained at the site
    [12]  All PCB-contaminated organics had
    been incinerated by this time

Regulatory Context:

•   In Jury 1982, the MOTCO site was placed
    on the National Priorities List (NPL)

•   An OU-1 ROD was signed in March 1985,
    specifying source control by incineration of
    organic liquids on site or off site, biological
    treatment of pit surface water and/or on-site
    incineration, and off-site landfillmg of
    sludges, tars, and soils or on-site
    incineration [3]

•   In 1987, EPA and the RP entered into a
    Consent Decree  At that time, the
    alternative of on-site incineration was
    selected

•   The OU-2 ROD was signed  in September
    1989, specifying management of migration
    by incineration of dense, nonaqueous phase
    liquids (DNAPLs), treatment of
    contaminated ground water, and
    consolidation and capping of slightly
    contaminated surface soils [41
•   During the design phase for the OU-2
    remedy, EPA determined that long-term
    management of the site was necessary
    The complete removal of all
    contaminated matenal associated with
    OU-1 was deemed no longer essential,
    therefore contaminated soils were left
    on site to be incinerated by the OU-2
    remedy [12]

•   EPA prepared an Explanation of
    Significant Differences (ESD) in
    January 1993, specifying off-site
    incineration of liquids and sludges/tars
    and capping of contaminated soils [12]

 •  The remedial standards applied at
    MOTCO were based on the following
    laws, regulations, and policies  the
    Toxic Substances Control Act (TSCA)
    and associated regulations in 40 CFR
    part 761, Executive Order 11990
    (Protection of Wetlands), Executive
    Order 11988, (Floodplam Management),
    and the Resource Conservation and
    Recovery Act (RCRA) and associated
    regulations in 40 CFR part 264, subpart
    0[3]

•   Site activities were conducted under
    provisions of the Comprehensive
    Environmental Response,
    Compensation, and Liability Act of 1980
    (CERCLA), as amended by the
    Superfund Amendments and
    Reauthorization Act (SARA) of  1986,
    and the National Contingency Plan
    (NCP) 40 CFR part 300 [12]

Remedy Selection: On-site rotary kiln
incineration was selected as the remedy for
the contamination at the MOTCO site based
on the results of the RI/FS, two site
investigations, a responsiveness summary,
and long-term economic considerations [3]
 U.8. ENVIRONMENTAL PROTECTION AGENCY
 Office of Solid Wsjte and Emergency Retpome
 Technology Innovation Office
                                           132

-------
Timeline
                                                                  MOTCO Superfund Site
	 Table 1 Timeline f 21 	
yp^j^K^^^i^
1959-1968
1981
1962
July 1982
September 1984
March 1985
October 1987
October 1990
May 1990- December 1991
December 1991
January 1993
Operations ware performed at the MOTCO site
Initial site Investigation performed
Second site rnvasUgaUan conducted
Site placed on the NPL
Feastoffity Study completed
Record of Decision f or OU-1 signed
EPA entered into a Consent Decree with a number of Potentially Responsible Parties
Trial Bum for second incineration system (HTTS-3)

Incineration occurred on site

Contractor stopped Incineration and fled suit against RP
ESD specified off-site incineration as new remetfal action for liquids and sludges/tars with
capping 01 coniarTiin&ou SON..

SJteLontetlM/Contacte
Site Management: HP-Lead

Oversight: EPA

Remedial Project Manager:
Cartrs Sanchez
U.S EPA Region 6
1445 Ross Avenue, Suite 1200
Dallas, TX 75202
(214) 665-8507
                                   State Contact:
                                   Ashby McMullan
                                   Texas Natural Resources Conservation
                                   Commission
                                   (512) 239-1000

                                   Treatment System Vendor:
                                   IT Corporation
                                   312 Directors Onve
                                   Knoxville, TN 37923
                                   (423) 690-3211
                               MATRIX DESCRIPTION
Matrix Identification
Type of Matrix Processed
Through the Treatment System: Soils,
sludges, tars, organic liquids, and aqueous
wastes were removed from unlined pits
Contaminant
Characterization
Primary Contaminant Groups:  Styrene tars,
VOCs, PCBs and metals

•  The contaminants of greatest concern were
   styrene tars, benzene, vinyl chloride, 1,1,2-
   trichloroethane, lead, cadmium, mercury,
   and chromium
                                   •   The maximum concentrations of
                                       selected organic constituents and
                                       metals in the pit wastes were 22,000
                                       mg/kg of styrene, 61,000 mg/kg of
                                       1,1,2-trichloroethane, 41,500 mg/kg of
                                       1,2-dlchloroethane, 7,600 mg/kg of vinyl
                                       chloride, 5,440 mg/kg of benzene,
                                       12,000 mg/kg of aluminum, 920 mg/kg
                                       of cadmium, 550 mg/kg of chromium,
                                       and 46,000 mg/kg of lead.
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                         133

-------
                                                                  MOTCOSMMTftmrfSfte
                           MATRIX DESCRIPTION (CONT.)
The major matrix characteristics that most significantly affected cost or performance at the site and
their measured values are presented in Table 2
                  Table 2  Matrix Characteristics of
Density
Ash Content
OfgmfcCMorine
1003 gAnl
0.59%
0048%
The matrices most affecting cost were the
viscosity and heat content of the oils and
sludcds. For example, the heat content of the
as-encountered waste exceeded the as-
characterized waste by 40 percent, and the
as-encountered waste viscosity substantially
exceeded the as-characterized viscosity  This
required the majority o* the waste feed to be
treated in the smaller HTTS-2 kiln instead of
in the two SCO chambers as onginally
planned The net result was that the
equipment on site had excess capacity for
treating pumpable sludges and insufficient
capacity to treat solid sludges and soils
Hence, the project was not as economical as
had onginally been planned
                        TREATMENT SYSTEM DESCRIPTION
HTTS-2-

•   Rotary kiln; and
•   Secondary combustion chamber (SCO).

HTTS-3

•   Combustion chamber
  SiiDDtemantal Traatmant Technology

  Pretreatment (solids)  Shredded and Mixed
  Post-Treatment (air) for both HTTS-2 and
  HTTS-3, including-

  •   Quench system,
  •   Gas conditioner;
  •   Wet scrubber hydro-sonic tandem
     nozzle scrubber system; and
  •   Vane separator.

  Post-Treatment (water)  Filtration in a
  closed-loop system
            rtotk
    Two incineration systems were designed for
    useattheMOTCOsHe: HTTS-2 and
    HTTS-3. The HTTS-2 was designed to
    process solids, sludges, tars, aqueous
    wastes, and organic liquids. The HTTS-3
    was designed to process only aqueous
    wastes and organic liquids
     Organic liquids, aqueous waste, and
     pumpable sludge were transferred to
     dedicated tanks before being fed to the
     incineration systems  Any solids were
     prepared in the feed preparation
     building where materials were mixed to
     provide a homogeneous matrix, then
     screened.  Oversized material was
     shredded and remixed.
U 3. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* and Emwgancy Response
Technology Innovation Offlca
                                         134

-------
                                                                    MOTCO Supfrfund SHe
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
Sv«fam Pagcriptlon and Operation fConU

•   The HTTS-2 employed at the MOTCO site
    consisted of two chambers (the kiln Itself
    and the SCC) and a gas cleaning system
    consisting of a quench system, gas
    conditioner, wet scrubber system, and a
    vane separator  The HTTS-3 consisted of a
    combustion chamber and a gas cleaning
    system that were identical to the SCC and
    gas cleaning system of the HTTS-2

•   Solids, sludges, and aqueous wastes were
    fed to the HTTS-2 kiln by a screw conveyor
    designed to minimize air infiltration, and the
    sludges and aqueous waste were pumped
    from separate tanks through separate
    lances into the kiln Organic liquid wastes
    were used as primary fuels in the kiln

•   The HTTS-2 kiln was a carbon steel
    chamber that measured 45 feet long, with
    an outer diameter of 7 feet, 7 inches, an
    inner diameter of 6 feet, 6 inches, and a
    volume of 1,540 cubic feet The kiln was
    lined with a 6-inch-thick layer of super-duty
    refractory brick.  The kiln was rated at 40
    million BTU/hr  The kiln was of
    countercurrent design and was capable of
    operating in either an oxidative mode or a
    combined oxidative and reductive mode,
    depending on the waste feed

•   The aqueous wastes and organic liquid
    wastes were injected into the HTTS-3
    combustion chamber burners through air-
    atomized burner guns Organic liquid
    wastes were also used as primary fuels for
    the SCC and the HTTS-3 incineration
    chamber main burners

•   The SCC for the HTTS-2 and the
    combustion chamber for the HTTS-3 were
    down-fired steel chambers  The chambers
    were lined with 7 to 9 inches of refractory
    insulating material and were approximately
    52 feet tall with an outer diameter of  12 feet.
    The units operated at a minimum of 3
    percent excess oxygen with a 2-second off-
    gas retention time.

•   Residual ash from the kiln was collected
    and was to be Sandffiled and capped on site,
    but disposal of the ash did not occur before
    the contractors stopped Incineration and
filed the lawsuit Disposal of ash was
addressed by the subsequent BSD.

The exhaust gases from the HTTS-2
SCC and the HTTS-3 combustion
chamber were directed through
separate but identical gas cleaning
systems  First, the gases were routed
to the quench system for cooling and
removal of particulate matter and acid
gas Flue gas from the quench system
then flowed into the gas conditioner,
where additional particulate matter and
acid gas were removed.

Gas leaving the gas conditioner ente'e4
the first of two Hydro-Sonic* subsonic
nozzles where caustic solution was
sprayed into the gas stream  The gas
stream then passed through a mixing
tube to the second Hydro-Sonic*
subsonic nozzle for additional
treatment.

The gas stream passed through a
second mixing tube before entering the
vane separator, where the spray
solution from the scrubber was
removed

Combustion gases were drawn through
the incineration system by an induced
draft fan (resulting in a constant
negative pressure throughout the
system) and were exhausted through an
80-foot fiberglass reinforced plastic
Both systems had an emergency relief
vent system to treat off-gases from the
kiln during emergency shutdowns. The
Environmentally Safe Temporary
Emergency Relief System* (ESTER*)
received electricity from a battery-
powered unlnterruptable power source,
so the off-gases were treated even
during power outages. The ESTER
system consisted of a natural gas ring
burner, two continuous gas pilots, and
two natural draft air dampers. The
system was designed to be a complete
stand-alone combustion system In
emergency shutdown situations [5]
U.S. ENVIRONMENTAL PROTECTION AQENCV
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                          135

-------
                                                                  UOTCOSuperfundSOe
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
                        Tabled  Summary of
            Residence Time (Solids)
15 to 90 minutes
            System Throughput
NA
            Kiln Exit Temperature
800°-1800°F
                       TREATMENT SYSTEM PERFORMANCE
   The cleanup goals and standards were
   specified by the Consent Decree The ORE
   and ash residual standards were set based
   on regulations under TSCA in 40 CFR part
   761,subpartD

   The pits were to be excavated to the sludge/
   soil interface and to a depth of one foot
   below the sludge/soil interface.  The
   sludge/soil interface was identified visually
   by the personnel performing the excavation
   [3]

   Cleanup levels had to conform to a level
   that presented a lifetime increased cancer
   nsk of 1x10* or less
        Applicable or relevant and appropriate
        requirements (ARARs) required a ORE
        of 99 99 percent for POHCs and
        99 9999 percent for PCBs

        The management of residual ash from
        on-site incineration was addressed by
        the second consent decree that
        specified off-site incineration
   The trial bums conducted at the MOTCO
   site were designed to operate the
   incineration system at conditions that would
   reflect worst-case destruction and removal
   of all constituents of concern
   Naphthalene, 1,1,2-tnchloroethane, and
   carbon tetrachlonde were selected as the
   POHCs for the MOTCO site

   The MOTCO site was required to
   demonstrate a 99 9999 percent ORE for
   PCBs  However, the concentration of PCBs
   was not sufficient to demonstrate this ORE.
   Therefore, the DREs for 1,1,2-
   trichloroethane and carbon tetrachloride
   were demonstrated to be greater than
        99 9999 percent rather than the 99 99
        percent specified [5]

        Before the trial bum for HTTS-3, the
        wastes were analyzed and a 10 percent
        spike of 1,1,2-trichloroethane and a 10
        percent spike of carbon tetrachloride
        were added to the organic liquids.
        Concentrations of naphthalene were
        measured and were deemed high
        enough so that spiking was not
        necessary
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                         136

-------
                                                                    MOTCOSuptrfundSite
                          •MENT SYSTEM PERFORMANCE
 •   The AWFCO limits for the incinerator are
    shewn in Table 4  Information about the
    frequency of AWFCOs was not available

 •   The HTTS-3 had completed a trial bum and
    was running under interim standards and the
    HTTS-2 was in the process of conducting a
    trial bum when on-srte incineration ceased
    as the result of a dispute between the RP
    and the contractor The chemical makeup,
    quantities, and mixture of the waste were
    found to be different than initially estimated
    As a result, the incineration systems were
not properly designed for the actual waste
A number of technical difficulties were
expenenced with the systems, including
slagging, paniculate carryover, dust
blocking the flame detector in the kiln, and
low utility fuel gas pressure

•  Several problems that caused the
   dispute are presented in the Lessons
   Learned section of this report
            Table 4  Proposed Automatic Waste Feed Cutoffs for HTTS-2 and HTTS-3
MMmum rotary Mb) temperature
-a I. •! t. fe * A.
Minimum secondary combustion chamber temperature
Maximum Mn soMfeludge/aqueous flow (HTT5-2only)
Maximum Win organic liquid flow (HTTS - 2 only)
Maximum SCC organic liquid flow
Maximum SCC aqueous waste flow
Maxknum Mn pressure (15 second delay) (HTTS • 2 only)
Maximum quench chamber temperature



Maximum sncK gas caroon monoxKie cuncenvanon ( i-nour

Minimum stack gas oxygen concentration
Maximum stack gas ftow(1 hour roWng average)
SOOT
2,020
20tons/hr
2,500 to/hr
7,300 IbAir
9,700 tolhr
0 Inches we
220 F
35 Inches we
lOOppm
3vol%dry
55,000 acfm
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                          137

-------
                                                                   MOTCO Superfund Site
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
    A list of contaminants detected in the
    various matrices at the site is available in
    the Initial Investigation [1]
    According to site personnel, the Quality
    Assurance/Quality Control (QA/QC)
    program, used throughout the remedial
    action met the EPA and the State of Texas
    requirements
                             TREATMENT SYSTEM COST
•   The RP contracted with IT Corporation to
    conduct the remedial work

Cost Data               	
    The total capital cost exceeded $20 million
    In the time that the incineration systems
    were operated, the contractor spent
    approximately $56 million in operating and
    maintenance costs  The initial bid for on-
    slte incineration was $30 million, and at the
    time
     Data Oiialltw
the contractors stopped incineration and
filed the lawsuit, the RP had paid the
contractor $20 million The total cost to
complete the on-site incineration was
estimated to be $110 million  A total of
23,021 tons of material - including soil
sludge, organic liquid, and aqueous
waste ~ were incinerated This
corresponds to a total unit cost for
incineration of $3,300 per ton
    Cost data was acquired through personal
    communications between IT and EPA and
    between the RP and EPA
                      OBSERVATIONS AND LESSONS LEARNED
    The Initial profile of the contamination on
    site was inaccurate. Therefore, the
    incineration systems that were designed
    were not optimal for the wastes. This
    resulted in a large Increase in clean-up time
    and cost. The contractor Interpreted the
    waste characterization data to show
    principally pumpable organic waste suitable
for direct firing in an SCC, and
subsequently mobilized two SCCs with
one small kiln. In actuality, most of the
waste was solid In nature and needed to
be fed to the kiln Hence, the two
incinerators did not provide feed
systems suitable to the actual on-site
waste.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          138

-------
                 OBSERVATIONS AND LESSONS
                                                                     MOTCO SupvfundSH*
•   The MOTCO site had several technical
    problems with the incineration systems, one
    of which was slag buildup and plugging in
    the bottom of the HTTS-2 SCO  According
    to site personnel, a possible solution would
    have been to discharge the ash while it was
    still hot and quench and cool the ash and
    slag outside of the SCC A Key cause of the
    slag build-up was the high gas velocity in
    the HTTS-2 kiln due to increased feed rates
    for soils and sludges The resulting high
    gas velocities carried particulates into the
    HTTS-2 SCC

•   Another problem was excessive participate
    carryover from the air pollution control
    system  Fine paniculate was produced in
    the quench due to the high chlorine content
    of the waste and the use of a saturated
    bnne crystallizer system to remove salt from
    recirculatmg quench wastes  A water/steam
    "supersub" was placed in the first hydro
    scrubber to address this problem

•   Slide valves in the incineration systems
    were used to isolate certain areas during
    incineration A workman at the  MOTCO site
    was killed when removing timbers that had
    been used to block open a slide valve
    dunng internal maintenance. Any designs
    utilizing slide valves should incorporate
    devices that will safely keep valves open

Public Involvement	

•   A community Involvement plan was
    developed in 1987 and revised in 1989
    Two open houses and workshops were held
    in November 1990 and October 1993  EPA
    held public meetings for the source control
    ROD and the management of migration
    ROD in January 1986 and July 1989,
    respectively.  Starting In 1987, several fact
    sheets were sent to 270 citizens on the site
    mailing list
Almost a third of the shutdowns at the
MOTCO site were, due to incinerator
dust blocking the flame detector  The
detector would signal that the kiln
burners were extinguished and then
shut down the system

Another problem was caused by an
electrical switchgear in the Induced draft
fan overheating by operating at peak
capacity in the Texas heat. Site
personnel stated that sensitive electncal
equipment should be protected from
such weather by air-conditioned and
heated buildings or other means [14]

Low utility fuel gas pressure caused
several problems  Site personnel felt
that an oversized gas line would have
improve the utility fuel gas pressure
A high level of organized interest
existed in the community regarding the
cleanup of the site. Many concerns
voiced were regarding air emissions
during the trial bums and the litigation
between the RP and their contractor
U.S ENVIRONMENTAL PROTECTION AGENCY
Off let of Solid Waste and Emergency Response
Ttohnology Innovation Office
                                          139

-------
                                   REFERENCE
                                                                MOTCO Supwfund Sfl»
1   Initial Investigation of MOTCO Hazardous
    Waste Disposal Site. Final Report. Black &
    Veatch Consulting Engineers, December 23,
    1981.

2   Source-Control Feasibility Study MOTCO
    Site. LaMaroue. Texas. CH2M Hill,
    September, 1984

3   Suoerfund Record of Decision Operable
    Unit 1. MOTCO, Texas City, Texas, March
    15,1985

4   Superfund Record of Decision Operable
    Unit 2. MOTCO, Texas City, Texas,
    September 27,1989

5.   MOTCO Site Remediation and Incineration
    Proiect Trial Bum Report for HTTS-3. IT
    Corporation, February, 1991

6.   Personal Communication between E F
    Steelier of the MOTCO Trust Group and
    U.S. EPA Region 6, Novembers, 1991

7.   Complaint. IT Corporation v MOTCO Site
    Trust Fund and Monsanto Company. The
    United States District Court for the Southern
    District of Texas, Houston Division,
    Decembers, 1991
8  IT Corporation News Release. Houston,
   December4,1991

9  Personal Communication between
   Frances E Phillips of Gardere & Wynne
   and U S EPA Region 6, December 17,
   1991

10 Personal Communication between R E
   Guilliams of the MOTCO Trust Group
   and U S EPA Region 6, December 5,
   1991

11 Personal Communication between R E
   Guilliams of the MOTCO Trust Group
   and U S. EPA Region 6, December 19,
   1991

12 Explanation of Significant Differences.
   MOTCO Superfund Site, LaMarque,
   Galveston County, Texas, January 13,
   1993

13 EPA Region 6 Superfund Homepage,
   lntemet,(http.//www epa gov/earth1r6/6s
   f/motco pdf) March 28,1997

14 Personal communication with Carl
   Edlund, U S EPA Region 6, May 15,
   1997.
U.8 ENVIRONMENTAL PROTECTION AGENCY
Offiet of Solid Watte and Emergency Rttpoma
Technology Innovation Office
                                        140

-------
     On-Site Incineration at the
Old Midland Products Superfund Site
           Ola, Arkansas
                141

-------
      Incineration at the Old Midland Products Superfund Site
        	   	Ola, Arkansas	
Site Name:
Old Midland Products
Superfund Site
Location:
Ola, Arkansas
Contaminants:
Pentachlorophenol and
polynuclear aromatic
hydrocarbons, end VOCs
• Benzo(a)anthracene,
  benzo(a)pyrene,
  benzo(k)fluoranthene,
  chrysene, fluoranthene, 2-
  methyl naphthalene,
  phenanthrene, benzene,
  toluene, tnchloroethylene,
  xylene, and chloroform
• POP concentrations up to
  5.900 mg/kg and PAH
  concentrations up to 38,000
  mg/kg
Period of Operation:
June 1992-May 1993
Cleanup Type:
Remedial action
Vendor
Chemical Waste Management,
Inc
ENRAC South Division
P O. Box 579
Ola, AR 72853-0579
SIC Code:
2491 (Wood Preserving)
Technology:
On-Sfte Incineration
• Solids pretreated with
  shredding, screening, and
  mixing with cement kiln dust
• Incineration system
  consisting of rotary kiln and
  secondary combustion
  chamber (SCC)
• Enclosed conveyor
  transported contaminated soil
  and debris to the unit
• Kiln temperature of 1,425°F,
  SCC temperature of 2,091 °F
• Treated soil and debns
  (incinerator ash) discharged
  onto conveyors and taken to
  an ash storage area
Cleanup Authority:
CERCLA and State.
Arkansas
• ROD Date* 3/24/88
Points of Contact:
Carlos Sanchez
US EPA Region 6
1445 Ross Avenue
Suite 1200
Dallas, TX 75202
(214) 665-8507

Clark McWilliams
State of Arkansas
Department of Pollution
Control and Ecology
PO Box 8913
Little Rock, AR 72219
(5011682-0850
                                       142

-------
       Incineration at the Old Midland Products Superfund Site
                                 Ola, Arkansas
                                    (Continued)
Waste Source:
Disposal lagoons - wood
preserving waste	
Purpose/Significance of
Application:
Initially, dioxms and furans
were believed to be present in
the soil  Later, concentrations
of dioxins and furans were
determined to be very low and
none were in the form of
2.3.7.8-TCDD.   	
Type/Quantity of Media Treated:
Sludge and Soil
• 102,000 tons of sludge and soil
• Moisture content- sludge - 43.6%
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (DRE) of 99 9999% for all constituents of concern as
  required by Resource Conservation and Recovery Act (RCRA) incinerator regulations in 40
  CFR part 264. subpart O	
Results:
• Monitoring and tnal bum data indicate that all DRE and emission standards have been met
• Analytical data of residuals indicate that cleanup goals have been met	
Description:
Between 1969 and 1979, the site operated as a wood preserving plant Effluents from the
treatment process containing PCP and PAHs were discharged to seven on-site lagoons  A series
of inspections at the site were performed by the Arkansas Department of Pollution Control and
Ecology and the U S EPA between 1981 and 1986 A Record of Decision (ROD) was signed
March 1988, specified on-site incineration as the remedial technology for the sludge, soil, and
sediments  Site cleanup goals and DRE standards were specified for constituents of concern

On-site incineration began in June 1992 and was completed in May 1993. The treatment system
consisted of a rotary kiln and an SCC An enclosed conveyor moved the soil and debris to the kiln
for treatment  Treated ash from the incinerator was discharged to a conveyor and conveyed to a
collection area  During its period of operation, the incinerator processed 102,000 tons of sludge
and soil. Incineration achieved the soil cleanup goals specified in the ROD

The total cost of the remedial action was approximately $27,000,000
                                        143

-------
                                                        Old Midland Products Superfund Site
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-srte incineration at the
Old Midland Products Superfund site in Ola,
Arkansas  A rotary kiln incinerator was operated
from June 1992 through May 1993 as part of a
remedial action Contaminants of concern at
the site included pentachlorophenol (PCP) and
polynuclear aromatic hydrocarbons (PAHs)

The Old Midland Products site was a former
creosote and pentachlorophenol wood
preserving plant and sawmill that operated from
1969 to 1979  During this time, effluent from
wood preserving processes was discharged to
on-site lagoons. Soil and sediment in the area
of the lagoons were found to be contaminated
with PCP and PAHs in concentrations as high as
5,900 mg/kg and 38,000 mg/kg, respectively

In March 1988, a Record of Decision (ROD) was
signed for the site, specifying incineration of
surface soils, lagoon sludge, and sediments
The remedial action was conducted by the state
of Arkansas, but was financed under the
Comprehensive Environmental Response,
Compensation, and Lability Act (CERCLA)
The material specified for excavation and
incineration included approximately 2,770 cubic
yards of sludges, 850 cubic yards of sediment,
and up to 21,000 cubic yards of soil  The ROD
specified incinerator requirements that included
a destruction and removal efficiencies (ORE) of
99 99% or 99 9999%, depending on the
constituent The ROD also specified that
approximately 450,000 gallons of contaminated
groundwater were to be pumped and treated on
site  The remainder of this report will address
only the incineration as required by the ROD,
unless otherwise stated
The selected Incineration system consisted
of a feed system, a rotary kiln; a secondary
combustion chamber (SCC), and an air
pollution control system (APCS).
Excavated matenal was taken to a feed
preparation building where it was screened
and mixed with cement kiln dust prior to
being fed to the kiln

The resulting ash was discharged from the
kiln and conveyed to an ash storage area
while exhaust gases were channeled to the
SCC  The SCC provided for further
combustion of organics in the off-gases,
which were then quenched with water

The APCS consisted of a baghouse, a
ventun quencher, and a scrubber
Particulate removal occurred in the
baghouse  The ventun quencher cooled the
gas, then the scrubber removed acid gases

Dunng the 9 months of operation, the
incinerator processed approximately
102,000 tons of soil,  sludge, and sediment
Treatment performance and air monitoring
data collected during this application
indicated that all performance standards
and monitoring requirements were met

The total cost for remediation  using the
incineration system was approximately
$27,000,000
 U 8. ENVIRONMENTAL PROTECTION AGENCY
 Offlc* of Solid Waste and Emergency Response
 Technology Innovation Office
                                          144

-------
                                                         Old Midland Product* Supwfund Site
                                  SITE  INFORMATION
Old Midland Products Superfund Site
Ola, Arkansas

CERCLJS * ARD980745665

ROD Data  March 24,1988
Rackaround
                                                 Treatment Application
Type of action  Remedial (on-site rotary
kiln incineration)

Period of operation  June 1992-May
1993

Quantity of material treated during
application 102,000 tons of creosote-
contaminated sludges, soils, and
dramageway sediments.
Historical Activity that Generated
Contamination at the Site  Creosote and
pentachlorophenol wood preserving plant and
sawmill

Corresponding SIC Code 2491 (Wood
Preserving)

Waste Management Practice That
Contributed to Contamination  Storage and
disposal of wastes in lagoons

Site History:

•   The Old Midland Products site is flat with a
    total area of approximately 37 acres It is
    located in an agncultural area  A wildlife
    management area is located one mile north
    of the site

•   Between 1969 and 1979, the site operated
    as a wood preserving plant Effluents from
    the wood treatment process containing POP
    and PAHs were discharged to seven on-site
    lagoons

•   A senes of  inspections and investigations at
    the site v/sre performed by the Arkansas
    Department of Pollution Control and
    Ecology (ADPC&E) and the U.S EPA
    between 1981 and 1986.

•   The remedial investigation and feasibility
    study (RI/FS) were completed in October
    1987.  An estimated 9,000 to 21,000 cubic
    yards of contaminated soil, 850 cubic yards
    of contaminated dralnageway sediments,
    and 2,770 cubic yards of lagoon sludges
    were identified (a total of approximately
    45,000 tons)

•   The pnncipal pollutants of concern were
    POP and PAHs  DunngtheRI,
    chlorinated dibenzodioxins and
    dibenzof urans were believed to be
    present, but later studies found only
    very low concentrations of these
    pollutants, no 2,3,7,8-TCDD was found

•   A tnai bum was conducted in Apnl 1992
    Incineration began In June 1992 and
    was completed in May 1993 In that
    time, 102,000 tons of soil, sediment,
    and sludge were  incinerated

Regulatory Context:

•   In June 1986, the Old Midland  Products
    site was placed on the National
    Priorities List (NPL)

•   The ROD was signed March 24,1988,
    specifying source control by incineration
    of surface soils, lagoon sludge, and
    dralnageway sediments

•   The Old Midland  Products site  was a
    state-lead site that was financed under
    CERCLA
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wart* and Emergency Response
Technology Innovation Office
                                          145

-------
                                                       Old Midland Products Superfund Site
                            SITE INFORMATION (CONT.)
Background (ConLV
   The selected remedy was conducted under
   the provisions of CERCLA, the Superf und
   Amendments and Reauthonzation Act of
   1986 (SARA), and the National Contingency
   Ran MCP) 40 CFR Part 300

   Tha DREs were set in accordance with
   RCRA incinerator regulations in 40 CFR
   part 264, subpart O, §264.343.
Remedy Selection  On-site incineration
was selected as the remedy for
contaminated soil at the Old Midland
Products Superf und site  This remedial
action was deemed to be protective and
cost-effective, and attained applicable or
relevant and appropriate federal and state
standards  It utilized permanent solutions
and treatment technologies that reduced
contaminant mobility, toxicity, and volume
to the maximum extent practicable
Tlme!ine
1969-1979
1981
June 1986
October 1967
March 1988
1991 - 1992
Aptl 1992
June 1992 -May 1993
October -November 1993
Dates of site operations
taWal site Investigation
Site placed on the NPL
Remedial IrwesfJgaBon/Feaslbfflty Study completed
Record of Decision signed
Contaminated sol Is excavated
Trial bum conducted
Rotary KHn Incinerator operational
Site cleanup Inducing seeding
Stta Loolftticft/Contact*
Sit* Management  State-lead

Oversight  State

Remedial Project Manager:
Carlos Sanchez
US EPA Region 6
1445 Ross Avenue,  Suite 1200
Dallas, TX 75202
(214) 665-8507
State Contact:
Clark McWilhams
State of Arkansas Department of Pollution
Control and Ecology
P O. Box 8913
Little Rock, AR 72219
(501) 682-0850

Treatment System Vendor:
Chemical Waste Management, Inc
OHM Remediation
John Patin
225 West Alrtex Boulevard
Houston, TX 77090
(281) 775-7071
U.S. ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Watte and Emergency RaaponM
Technology Innovation Office
                                         146

-------
                                                       Old Midland Products Supviund Site
                                MATRIX DESCRIPTION
 Uatrf
Typeofl
       d Through the
Treatment System:  Surface soils, lagoon
sludges, and drainageway sediments
       liumt fihi
aracterlzaflon
Primary Contaminant Groups-
Pentachlorophenol, polynuclear aromatic
hydrocarbons, and VOCs

•   Specific contaminants of concern included
    benzo(a)anthracene, benzo(a)pyrene,
    benzo(k)fluoranthene, chrysene,
    fluoranthene, 2-methyl naphthalene,
    phenanthrene, benzene, toluene,
    trichloroethylene, xylene, and chloroform.
                                    The maximum detected concentrations
                                    of POP was 790 mg/kg In the surface
                                    soil and 5,900 mg/kg in the lagoon
                                    sediments.' The maximum detected
                                    concentrations of PAHs were 14,000
                                    mg/kg in the surface soil and 38,000
                                    mg/kg in the lagoon sediments.
The major matrix characteristics that most significantly affected cost or performance at the site and
their measured values are presented in Table 2
                      Table 2  Matrix Characteristics of
            SoHCtessfficaBon
Moisture Content
Chloride
Organtes
Heat Content
436%
113%
1339%
6.165 Btu/fc
NA
NA
NA
NA
                            ATMENT SYSTEM DESCRIPTION
Primary Treatment Tt

Incineration system including
•  Rotary kiln, and
•  Secondary combustion chamber (SCC)

                                Pretreatment (solids) Screened and mixed
                                with cement kiln dust

                                Post-Treatment (air):
                                •   Quench tower
                                •   Baghouse
                                •   Venturi quencher
                                •   Scrubber

                                Post-Treatment (scrubber water)  Off-Site
                                deep weli injection
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                         147

-------
                                                         Old Midland Products SuporfundSte
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
Svatom Description and QparaUon
•   Excavated matenal was stockpiled and
    during the wet winter months, mixed with
    cement kiln dust to control its moisture
    content. The stockpiles were then moved
    into a feed preparation building where they
    were screened before being fed to the
    incinerator. An enclosed belt conveyor
    system fed bulk solids to the kiln feed
    hopper located above the screw feed
    system  From the kiln hopper, waste was
    conveyed into the kiln with a dual-rotor
    screw feeder

•   The kiln was constructed of 0.5-inch-thick
    steel plate and was lined with 5 5-inch-thick,
    high-fired, super-duty firebrick backed with a
    C 5-inch-thick insulating board  The tain had
    an inside diameter of 6  5 feet and a length
    of 45 feet

•   The oxygen-fuel burner was designed to
    bum natural gas or propane  The burner
    was rated at 30 million BTU per hour

•   The incineration system had a series of
    conveyors designed to combine incinerator
    ash collected at various points in the
    incinerator into a single ash stream for
    conveyance to the ash storage area  Ail
    conveyors used in the incineration system
    were totally enclosed and vented to the
    incinerator SCO or ARCS to control fugitive
    emissions  Ash that was generated was
    sampled and analyzed to determine whether
    ft met disposal requirements

•   Hot flue gases from the (din were
    discharged through a hot gas cyclone into
    the SCC  The hot gas cyclone was a
    refractory-lined vessel that removed a
    portion of the paniculate cany-over from the
    flue gases before their introduction Into the
    SCC.  The SCC was a vertical cylindrical
    chamber lined with six inches of high-
    temperature refractory with a burner located
    at the base of the unit   The SCC was
    operated at a minimum temperature of
    2,050°F.
•  The SCC gases entered the quench
   tower where the temperature was
   reduced to approximately 400°F with
   air-atomized water spray nozzles The
   quenched combustion gases passed
   into two parallel baghouse assemblies
   Each baghouse was designed with a
   four-to-one air-to-cloth ratio

•  From there, the internal draft fan drew
   combustion gases through the wet
   scrubbing system out to the stack. The
   fan was of centrifugal design, sized to
   develop a vacuum of approximately 25
   inches water column (we)  The fan was
   powered by a 350-horsepower vanable-
   speed motor  The fan maintained a
   negative pressure in the kiln

•  The wet scrubbing system consisted of
   a ventun quencher, a pre-packing spray,
   a packed bed absorber, and a Chevron
   mist eliminator

•  The ventun quencher used water sprays
   that cooled the off-gases from
   approximately 350°F to 185°F  A
   mildly caustic scrubber-water solution
   neutralized dissolved acid gases in the
   system.  From the venturi quencher, the
   cooled flue gases entered the packed
   bed absorber section of the scrubber
   where they came in contact with the
   scrubber solution The packed bed was
   designed to provide  sufficient contact
   between the off-gases and the scrubber
   solution to permit efficient absorption
   and removal of the acid gas
   contaminants  Before the gas exited
   the stack, it passed through a Chevron
   mist eliminator for removal of entrained
   water droplets
U S. ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watt* and Emergency Response
Technology Innovation Office
                                           148

-------
                                                        Old Midland Products Superfund Site
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
Sv«tem Description and Operation fCont.1
    The stack was made of fiberglass-reinforced
    plastic and was approximately 73 feet high
    with a design flue gas exit velocity of 20 to
    35 feet per second.
Water used for ash quenching system
was recirculated  Scrubber blowdown
water was taken off site and disposed of
by deep well injection
 SoDd Residence Time
            NA
  System Throughput
          18tons/hr
 Kin Extt Gas Temperature
                       TREATMENT SYSTEM PERFORMANCE
The cleanup goals and standards were specified
by the ROD  The ORE was set based on RCRA
standards

•  Soils, sludges, and sediments with
   concentrations of greater than 1 mg/kg of
   POP were excavated and incinerated

•  The incinerator operating conditions set by
   the State specified that the incinerator must
   achieve a ORE of 99 99% for each organic
   hazardous constituent with the exception of
   POP, polychlorodibenzo-p-dioxins (PCDD),
   and polychlorodibenzofurans (PCDF) which
   were required to achieve a DRE of
   99.9999%.  Once excavation began, the
   concentrations of dioxins and furans were
   determined to be very low; no 2,3,7,8-TCDD
   was found  However, the RP decided to
   meet the DRE of 99.9999% for these
   contaminants although it was not necessary
Ash was placed on site and covered
with a vegetated soil layer The ash
disposal criteria were 1 ppm for PCP,
10 ppm for total PAHs, and 1 ppb for
total dioxm and furans as TCDD

The maximum allowable concentration
for total dioxins and furans was
eventually raised from 0.1 ppb to 1 0
ppb TCDD equivalents after review and
consideration of the thermal treatability
study, the capabilities of the incinerator,
and the long term risks to human health
and the environment [6]

The cleanup levels were deemed to be
sufficient to clean the site to a 1x10*
excess lifetime cancer nsk level
U 3. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          149

-------
                                                         Old Midland Products Superfund SHe
                   TREA
                              IT SYSTEM PERFonr
   A trial bum conducted at the Old Midland
   site was designed to operate the
   Incineration system at conditions that would
   reflect worst-case destruction and removal
   of all constituents of concern

   Naphthalene and 1,2,4-trichlorobenzene
   were selected as the POHCs to demonstrate
   the DREs lor PAHs and POP, respectively
   The DREs for dioxins and f urans also were
   demonstrated with 1,2,4-trichlorobenzene

   The incinerator at Old Midland operated
   within the operating limits established during
   the trial bum, indicating that all
   requirements established in the ROD were
   met  The AWFCOs and their frequency of
                                                    occurrence dunng the operation of the
                                                    incinerator are shown in Table 5
                                                    Values for operating parameters dunng
                                                    the trial bum are shown in Table 6;
                                                    actual values for these parameters
                                                    dunng operation were not available

                                                    Ash generated from the incinerator was
                                                    sampled and analyzed to determine if it
                                                    was in compliance with disposal
                                                    requirements The complete list of
                                                    maximum allowable concentrations for
                                                    hazardous constituents in the ash is
                                                    presented in Table 7
         Table 4. A\
                       t Destruction and Removal Efficiencies from
                           Table 5. Automatic Waste Feed Cutoffs
 fttadmum
 MMtimu Un pressure, Instsntsnsous
                                                     •oilnchwe
                                                        20
 MWmum Mn temperature, 1 hour roMng mirage
                                                       1396*F
                                                       1200*F
 MMniUHi misty Mflvspufyt flow, InslsnUnsous
                                                       SOchn
                                                                             33
 MlnlnuM) ratify vriw PUTQA prMiure, InsbmlMwous
                                                     OSinchwe
 MMTOOT 8CC Ismpsreture, Instantaneous
                                                       2,068°F
                                                        82
 MWmum SCC oxyge
                    ntration, dry gas volume percent
                                   3%
                       176
 MHmum bugh
              dHftrentW p
     re, instantaneous
1 1nch we
10


                                                        451 gpm
                                                                              10
 MMmum scfublMr pH, If tMlow ft)r 60 mkuit*§ or mort
                                                        65
fctodmum stack gas CO <
           !)	
rrtraOon, uneorrectad 1 hour roUng
                                                       lOOppmv
MeMmurn stack gas THC (
icing average (dry g»)
ntratton, uncorrected 1 hour
                                                        20ppmv
 MttdnHiin stack QM vsloclty, lostsntansous
                                                      20.7 Wssc
                                                        66
US ENVIRONMENTAL PROTECTION AGENCY
Offlo* of Solid Wattt md Emtrgmwy Response
Technology Innovation Offlc*
                                           150

-------
                                                    Old Midland Product* Supertund SH»
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
Waste feed rate
Kin pressure
Kin temperature
Rotary valve purge flow
SCC temperature

SCC oxygsn concentration
Baghouse oKterenttal pressure
Scrubber waste flow rate
Scrubber pH

Stack gas CO concentration

stack gas THC concentration
Stack gas vatocfty
Chlorine feed rate
Ash feed rate
Dissohwd soNds m the scrubber water
Differential pressure across scrubber packing
Quench exit temperature
18tph
-01 Inches we
1,4250F
379ctm
2.091 °F
3%
1 inch we
451 gpm
65
100 ppm
20 ppm
20.2 ft/sec
171tomr
29,900 ttVhr
lOBg/mL
1 1nch we
426-F
       Table 7.  Maximum Allowable Concentrations for Hazardous Constituents in the Ash

Pentachlorophenol, PCP
Dknvns and Furans as TCDD
Naphthatane
Phenanthrene
Acanaohthene
Acenaphthytene
Fhjorene
Chryaane
Pyrane
Benzene
Ethytoenzene
Toluene
Xvtane (total)
Total BNA
Total PNA
10
10ppb
10
0.3
03
03
0.3
03
03
01
01
01
01
100
10.0
* Reported m ppm In IMS otherwise stated.
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Witt* and Emtrgency Rasponte
Tachndogy Innovation Office
                                       151

-------
                                                         Old Midland Pr
                                                                 jt»Sup»rfundSitm
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
Performance Data Complatanaaa
•   Data are available for concentrations of
    contaminants in the soil and sediment
    before treatment.
                                           Data are also available for concentrations
                                           of contaminants in the incinerator residue
                                           These data were collected periodically
                                           throughout operation of the incinerator
                                           prior to landf tiling
   The Quality Assurance/Quality Control
   program used throughout the remedial
   action was deemed to have met EPA and
   State of Arkansas requirements
                             TREATMENT SYSTEM COST
•   Chemical Waste Management, Inc,
    ENRAC South Division was the remedial
    contractor for the incineration

Cost Data

•   The cost data were provided by the
    Arkansas Department of Pollution Control &
                                          Ecology The estimated cost for operating
                                          the incinerator at the site was about
                                          $17,100,000. Additional contaminated soil
                                          was encountered during the remedial action
                                          A total of 102,000 tons of soil, sludge, and
                                          sediment were incinerated.  Total project
                                          cost was approximately $27,000,000  This
                                          corresponds to a total unit cost of $264 per
                                          ton  Table 8 shows information on costs for
                                          the remedial action at the site
 331
01
01
Mobilization of Construction Equipment and Facilities
  $984,500
 331
01
03
Submittals/lmplementation Plans
 $1,031,304
 331
01
04
Setup/Construct Temporary Facilities
  $303,600
 331
02
06
Sampling Soil and Sediment
 $1,307,900
 331
02
09
Laboratory Chemical Analysis
 331
03
02
Clearing and Grubbing
  $210,490
 331
03
03
Earthwork (I e , excavating, backfill, grading, stockpiling)
$12,699,115
 331
14
01
Incineration (Including feed preparation)
 331
03
05
Fencing
   $26,056
                       Miscellaneous
                                                                    3551,000
                       Additional contaminated soil
                                                                   $9,886,035
                       Total
                                                                 $27,000,0001
1   This number Is an approximation, as a result, the total of the number's In the table do not exactly match
    this number.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Witt* and Emergency Response
Technology Innovation Office
                                           152

-------
                                                         OM Midland Products Superfund Sit*
                      OBSERVATIONS AND LESSONS LEARNED
    The cost was higher than initially estimated
    because the amount of material to be
    incinerated was underestimated According
    to site personnel, the very demanding
    cleanup goals required additional
    excavation not originally planned based on
    the results of the RI/FS.  In addition, the
    geology of the area was folded and faulted,
    as a result, analysis of soil borings did not
    yield representative results of subsurface
    contamination
•   Site personnel reported few problems during
    incineration  Reasons cited for success
    include thorough characterization of the
    waste before it was fed to the incinerator
    and the development of detailed plans at
    the beginning of the project

Public Involvement
    According to site personnel, local politicians
    and residents did not raise significant
    opposition to the selected remedial action
                               A community involvement plan was
                               developed in August 1985 and revised
                               in December 1988.  An open house was
                               held May 1986, and periodically, fact
                               sheets were sent to the 10 citizens on
                               the site mailing list.
    Suoerfund Record of Decision. Old Midland,
    Ola, Arkansas, March 1988
2   Old Midland I
i Suoerfund Site
    Incinerator Facility Trial Bum Plan 2. Radian
    Corporation, Match 1992

3   Old Midland Products Superfund Site
    Incinerator Operating Conditions. State of
    Arkansas, June 1992

4   EPA Region VI Superfund Homepage,
    Internet, (rrttp //www epa gov/earth1r6/6sf/
    midland pdf) March 26,1997

5.   Personal communication with Carlos
    Sanchez, U.S. EPA Region VI, June 9,
    1997.
Remedial Action Report Construction
Phase Old Midland Products Site. IT
Corporation, May 1996

Contractor's Site Specific Worker
Health and Safety Plan. Old Midland
Products Site, Chemical Waste
Management, May 1991.

Old Midland Products Superfund Site
Incineration Facility Trial Bum Test
Report. Radian Corporation, May 1992
                           9   Inolner
                               Chemical'
                               January 1992.

                           10  Remedial li
Remedial Investigation Draf
Midland, IT/MTR, July 1987
                 ^Description Report.
                            Inc.
Draft. Old
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Offkj*
                                           153

-------
This Pags IntMitkMMHy Loft Btank
             154

-------
   On-Site Incineration at the
Petro Processors Superfund Site
    Baton Rouge, Louisiana
              155

-------
         Incineration at the Petro Processors Superfund Site
                          Baton Rouge, Louisiana
Site Name:
Petro Processors Superfund
Site
Location:
Baton Rouge, Louisiana
Contaminants:
Chlorinated Hydrocarbons,
Polynudear Aromatic
Hydrocarbons (PAHs), Heavy
Metals, and Oils
• Hexachlorobutadiene and
  hexachlorobenzene
Period of Operation:
(Report ongoing covers
11/94-5/97)
Cleanup Type:
Remedial action
Site General Contractor:
NPC Services, Inc.
500 Brooklawn Drive
Baton Rouge, Louisiana 70816
(504)778-6200
SIC Code:
4953 (Refuse Systems)
Technology:
On-Site Incineration
• Combustion of fumes and
  liquids from groundwater
  treatment system
• Incineration system consisting
  of a horizontal, direct-fired
  kiln
• Air fan delivers fumes and
  centrifugal pump delivers
  liquids to the unit
• Kiln temperature of 2,000° F
  to2,400°F
• Slowdown from the system is
  pH adjusted with lime and
  discharged	
Cleanup Authority:
CERCLA and State
Louisiana
• ROD Date No ROD,
  Consent Decree took the
  place of the ROD
• RP-lead
Point of Contact:
Cynthia Kalen
Remedial Project Manager
US EPA Region 6
1445 Ross Avenue
Dallas, Texas 75202-2733
(214) 665-6772
Waste Source:
Disposal of petrochemical
wastes in on-site lagoons
Type/Quantity of Media Treated:
Liquids and Fumes
• 213,376 gallons of DNAPLs to date
Purpose/Significance of
Application:
Incinerator treats liquid
organics and air shipper fumes
from a groundwater treatment
system	
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (ORE) of 99.99% for organic constituents of concern as
  required by Resource Conservation and Recovery Act (RCRA) incinerator regulations in 40
  CFR part 264. subpart O	

Result*:
• Emissions and tnal bum data indicate that all DRE and emission standards have been met to
Cost Factors:
• Total cost of the Incinerator is approximately $32,827,799 to date
• Approximate Total Capital Costs- $18,159,087 (Including equipment, site preparation,
  construction/engineering, startup), Projected Future Capital Costs: $500,000
• Approximate Total Operating Costs- $14,668,912 (Including maintenance, project
  management, sampling and analysis, supplies), Projected Future Monthly Operating Costs
  $300.000 oer month	
                                        156

-------
          Incineration at the Petro Processors Superfund Site
                           Baton Rouge, Louisiana
                                    (Continued)
Description:
Between 1961 and 1980, the Petro Processors Superfund Site operated as a petrochemical waste
disposal area A remedial investigation determined that soil and groundwater at the site were
contaminated A Consent Decree entered into Federal Court on February 16,1984 specified that
a plan of action be developed for the site  The plan included a groundwater treatment system
which utilized an incinerator to treat liquid organics and air shipper fumes  Site cleanup goals
and ORE standards were specified for the organic constituents of concern.

The treatment system began operation in November 1994 and is ongoing at the time of this
report. The Incineration system consists of a horizontal, direct-fired incinerator A centrifugal
pump and an combustion air fan deliver the liquid and fume waste, respectively, to the
incinerator. The incinerator is equipped with an air pollution control  system consisting of a
quench tank; an HCI absorber/caustic scrubber tower; a paniculate scrubber, and a entrapment
separator

The total cost of the remedial action is approximately $32,827,799 to date. Capital costs
accounted for approximately $18,159,087 with a projected future cost of $500,000  Operation
and maintenance costs accounted for approximately $14,668,912 with a projected future monthly
cost of $300,000
                                        157

-------
                                                            PftroPnc9»9onSup9rfundSit»
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site Incineration at the
Petro Processors (Petro) Superfund site in
Baton Rouge, Louisiana. Since November
1994, an incinerator designed to dispose of
fumes and liquids from the groundwater
treatment system has been operating as part of
a remedial action  Contaminants of concern at
the site include chlorinated hydrocarbons,
polynudear aromatic hydrocarbons (PAHs),
heavy metals, and oils

The Petro  site operated as a petrochemical
waste disposal site from 1961 to 1980  During
this period, various chemical wastes were
disposed of in lagoons.  It was estimated based
on the results of an investigation conducted at
the site that 330,000 m3 of soil was
contaminated.  Groundwater and soil at Petro is
contaminated with hexachlorobutadiene and
hexachlorobenzene

In 1984, a Consent Decree was signed by
Federal and State government agencies and the
Responsible Parties (RPs) for the Petro site  A
Destruction and Removal Efficiency (ORE) of at
least 99 99% for organic constituents of concern
was called for by the approved operating
specifications.

Remedial activities at the site include the
design, construction and operation of a
groundwater treatment system which uses the
incinerator for the destruction of the residuals
generated  This report focuses on the cost and
performance of the incinerator and does not
present any detailed information on the
groundwater treatment system

Groundwater is currently being extracted with a
system of  165 recovery wells Recovered
groundwater is treated by phase separators to
remove non-aqueous phase liquids (NAPLs)
from the water; the separated water is treated
with air strippers to remove additional
contaminants.
The NAPLs removed by the groundwater
treatment system are stored in a waste feed
tank prior to being fed to the incinerator
through a liquid waste feed nozzle  The
vent gas from the air stoppers also is fed to
the incinerator as part of the combustion air

The incineration system consists of a vent
gas feed system; a liquid waste feed
system, a horizontal, direct-fired incinerator;
a quench tank, a HCI absorber/caustic
scrubber; a particulate scrubber; and an
entrapment separator

The incinerator volatilizes and destroys
organic compounds from the liquid and
fumes Treated gas is then drawn into the
quench tower for cooling  The HCI
absorber/caustic scrubber then removes
HCI, CI2, SO2, and some particulate matter
The particulate scrubber and errtrainment
separator remove additional particulate
matter before off-gas is released through
the stack

Dunng the 30 months of operation, the
incinerator has processed approximately
213,376 gallons of dense non-aqueous
phase liquids (DNAPLs) Treatment
performance and emissions data collected
during this application indicate that  all
performance standards and monitoring
requirements are being achieved.

The cost for treatment of the residuals using
the incineration system is approximately
$32,827,799 to date This amount consists
of $18,159,087 in capital costs and
$14,668,900 in operating costs.
U.S. ENVIRONMENTAL PROTECTION AQENCY
Offlct of Solid WMte and Emergency Response
Technology Innovation Office
                                           158

-------
                                                             ffefro Processors Suporfund Site
                                    ITE INFORMATION
idanttfvlno information
 Petro Processors Superf und Site
 Baton Rouge, Louisiana

 CERCUSt: LAD057482713

 ROD Data: Not Applicable  A Consent Decree
 was issued in lieu of a ROD
        und
Type of action: Remedial (groundwater
treatment with on-srte incineration of
residuals)

Period of operation: 1994-present

Quantity of material treated during
application:  213,376 gallons of LNAPLs to
date
Historical Activity that Generated
Contamination at the Site: Waste collection
and disposal

Corresponding SIC Code: 4953 (Refuse
Systems)

Wast* Management Practice That
Contributed to Contamination: Disposal of
waste in on-stte lagoons

Site History:

•   The Petro site operated from 1961 until its
    closure in 1980  The site is comprised of
    two former petrochemical waste disposal
    areas, the Scenic Highway and Brooklawn
    areas, which are located approximately 1 5
    miles apart

•   The Scenic Highway area operated from
    1961 until 1974 and covers approximately
    17 acres  The area was filled and closed in
    1974, but there was still concern over the
    potential for leachate migration and erosion

•   The Brooklawn site operated from 1969 until
    1980 and covers approximately 60 acres
    No known actions were taken to mitigate
    potential risks to human health and the
    environment at the time operations ceased

•   During the site's penod of operation, various
    petrochemical wastes were disposed of in
    unlined lagoons. It was estimated based on
    investigation at the site that 330,000 m* of
    soil was contaminated
    Soil and groundwater at Petro were
    contaminated with chlorinated
    hydrocarbons, PAHs, heavy metals, and
    oils

    A spill from the waste lagoons in 1969
    contaminated a local ranch, killing 30
    cattle  Additionally, on several
    occasions, waste in the lagoons
    spontaneously ignited

    The Petro site is located over a drinking
    water aquifer for the area referred to as
    the 400-foot sands

    In July 1980, the U S Department of
    Justice, the State of Louisiana, the City
    of Baton Rouge, and the Parish of East
    Baton Rouge filed suit against the site
    owner and several waste generators
    who had transported material to the site
    for disposal [1 j.

    A Consent Decree was entered into the
    Federal Court's record on February 16,
    1984. Under the terms of the decree
    the site was closed and the RPs were
    required to investigate and develop a
    detailed plan of action for the Petro Site
    [1].

    The proposed remedy included the
    excavation and incineration of visibly
    contaminated soil; the solidification,
    incineration,  or off-site disposal of all
    non-aqueous phase wastes in the
    lagoons, and the Installation of recovery
   wells to recover NAPLs [1].
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watte and Emergency Response
Technology Innovation Office
                                           159

-------
                                                            PWroPr
                          Supertax/S/te
                                          1AT10N (CONT.)
            fCnrtt.l
   In 1987, during the early phases of the
   excavation at Brooklawn, on-ate air
   monrtonng equipment detected volatile
   organic compounds  Operations at the site
   ceased in order to protect the safety of on-
   site workers and the safety of workers at
   industrial plants adjacent to the site

   In December 1988, the RPs reported in a
   Supplemental Remedial Action Plan
   (SRAP) that the remediation could not
   continue under the proposed plan without
   future unacceptable releases of volatile
   organic compounds. As required by the
   Consent Decree, the RPs also proposed
   methods for remediation in the SRAP EPA
   Region VI, however, found the RPs' findings
   insufficient and began an internal 18-month
   review of potential remedial solutions

   In 1989, the SRAP was approved amending
   tha Consent Decree and the remedy
   changed to capping the lagoons and
   hydraulic containment of the groundwater
   plume  Based on the findings of the
   amended Consent Decree, the RPs began
   design and construction activities

   The majority of the Brooklawn area was
   covered by a soil cap, seeded, and
   contoured to control erosion This action
   was completed July 1990, at which time the
   RPs also submitted a workplan for the
   earthwork which was needed at the Scenic
   Highway site  One lagoon in the area was
   and currently is left open in order to deposit
   drill cuttings from the wells installed on site
   A groundwater treatment system was
   installed in 1994, which currently includes
   98 sumps and 190 operating recovery wells
   of a planned number of 213.

   As in the Brooklawn area, the Scenic
   Highway area was covered with a soil cap,
   seeded, and contoured to control erosion
   This action was completed September
   1992. In October 1996, eleven
   recovery wells were installed to recover
   NAPLs from the area and thirty-four
   monitoring wells were installed to gauge
   the natural attenuation of the plume
   The contingent remedy had not been
   implemented at the time this report was
   prepared

•  The treatment system that was
   constructed at the Brooklawn area
   included an incinerator which was
   capable of disposing of both organic
   liquids and fumes A trial bum was
   conducted the week of November 7,
   1994, after which the incinerator began
   operating under intenm conditions  The
   final operating specifications were
   approved by EPA on December 28,
   1995

•  Bayou Baton Rouge was re-routed
   during remedial activities so that it did
   no flow through the site. Portions of the
   site are located within the Bayou Baton
   Rouge flood plain

•  A section of the Brooklawn area is in the
   Mississippi River flood plain
   Additionally, the Mississippi flood plain
   located to the south of the Brooklawn
   area, known as Devil's Swamp, is
   classified as a wetland A state health
   advisory currently covers parts of
   Devil's Swamp

Regulatory Context:

•  In 1984, the Petro Site was placed on
   the National Priorities List (NPL)
U 8 ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Wttte and Emergency Response
Technology Innovation Office
                                          160

-------
                                                              Potro Pmc»*9or» Superfund Site
                              SITE INFORMATION (Cor\rr.)
 Bflcknround fCont.)
    in 1984, a Consent Decree was filed into
    Federal Court, which required remedial
    activities at the site in Baton Rouge,
    Louisiana

    Treated groundwater is discharged under a
    National Pollutant Discharge Elimination
    System (NPDES) permit

    The DREs were set in accordance with
    Resource Conservation and Recovery Act
    (RCRA) incinerator regulations in 40 CFR,
    part 264 subpart O
                      Remedy S0K>ctlon: Hydraulic containment
                      and recovery followed by on-site
                      incineration of free-product and nonaqueous
                      organic residuals from the groundwater
                      treatment system was selected as the
                      remedy for the Petro Processors Superf und
                      site  On-site incineration was selected
                      based on the cost associated with using an
                      incinerator and the reduction in long-term
                      threats to human health and the
                      environment which occurred as a result of
                      destroying the contaminants
Timeline
          1961 - 1980
                                      Table 1. Timeline
The Petro Site was used for Disposal of petrochemical waste
         February 1984
Consent Decree established for site cleanup
            1984
Petro Stte was placed on the NPL
            1987
Remedial construction begins
            1989
Consent Decree amended
      November 7 -11, 1994
                             Trial Bum
  November 1994 - December 1995
Incinerator operated under Interim standards
       December 28. 1995
Final ooeraBno standards approved for Incinerator
Site Loalatlca/Contacte
Site Management:  RP-lead

Oversight. EPA

Remedial Project M anager:
Cynthia Kalen
US EPA Region 6
1445 Ross Avenue
Dallas, Texas 75202-2733
(214) 665-6772
                      State Contact:
                      Glenn Miller
                      Louisiana Department of Environmental
                      Quality
                      Inactive and Abandoned Sites Division
                      PO  Box 82282
                      Baton Rouge, Louisiana 70884-2282

                      Site General Contractor:
                      Bill Dawson
                      NPC Services, Inc
                      3867 Plaza Tower Drive
                      Baton Rouge, Louisiana 70816
                      (504) 778-6206
U S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watta and Emergency Response
Technology Innovation Office
                                           161

-------
                                                                  Pfoctitoft Suptffund Sft»
Type of Matrix Processed
Through the Treatment System: Organic
liquid and gas residuals generated during the
treatment of groundwater contaminated by
infiltration from unlined waste lagoons used for
waste disposal
Primary Contaminant Groups: Chlonnated
hydrocarbons, PAHs, heavy metals, and oils
     The contaminants of greatest concern
     were hexachlorobutadiene and
     hexachlorobenzene
Information on matrix characteristics was not available
Incineration system including.

•   Fume waste feed system
•   Organic liquid waste feed system
•   Horizontal, direct-fired incinerator
Pretreatment (liquids)

•  Agitation

Post-Treatment (air)-

•  Quench tank
•  HCI absorber/caustic scrubber tower
•  Particulate scrubber
•  Entrainment separator

Post-Treatment (water)

•  pH adjustment
•  Carbon adsorption
    Groundwater is recovered from the
    BrooMawn site using an existing system of
    165 extraction wells. The groundwater Is
    pumped through phase separators to
    remove NAPLs and air strippers to remove
    dissolved organtes. The treatment system
    Is designed to treat groundwater with 1,000
    to 2,000 mg/L of chlorinated organics
     The MAPI liquid waste is stored in a
     waste feed tank, which contains an
     agitator to maintain a homogenous
     mixture, prior to being fed into the
     Incinerator. The tank is a pressure
     vessel rated at 15 pslg with a storage
     capacity of 4,760 gallons, which
     provides storage capacity of
     approximately one day. [2].
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Oific*
                                           162

-------
                    TREATMENT SV<
DESCRIPTION (CONT.)
    The tank is padded with nitrogen to
    maintain an inert, non-flammable mixture
    above the liquid and it is kept at an
    operating pressure between 2 and 10
    psig  To maintain the correct pressure,
    the tank is vented as needed to the
    incinerator through a flame arrester  The
    waste tank is equipped with an electric
    heating panel to control the viscosity of
    the waste at a temperature between 70°F
    and95°F

    The liquid waste is pumped by a
    centrifugal pump through a strainer to
    remove any solids and into the incinerator
    liquid waste feed nozzle. The liquid waste
    feed is monitored by a Conolis meter and
    controlled by a flow control valve and a
    safety shutoff valve If an  automatic
    waste feed cutoff  (AWFCO) is initiated,
    the pump is shut down, and the feed
    control valve and  safety shutoff valve are
    closed. The liquid waste feed nozzle is
    atomized with air supplied  by an on-site
    air compressor; the atomization air
    pressure is maintained above the liquid
    waste feed pressure at the nozzle [2]

    The vent gas stream produced by the air
    strippers is fed to the incinerator through a
    combustion air fan and is discharged into
    the incinerator as  part of the total
    combustion air  The flow of the
    combustion air fan is controlled such that
    the minimum air flow to the incinerator
    exceeds the vent gas flow; this is
    designed to provide the incinerator with
    sufficient air for proper combustion A
    gravity damper allows fresh air to be
    pulled into the blower with the vent gas
    stream if the burner demands more air
    than that supplied by the vent gas stream
    12]
       The design maximum vent gas flow rate
       is 2,800 standard cubic feet per minute
       (scfm); the combustion air fan has a
       design capacity of 3,260 scfm The
       combustion air flow is monitored by a flow
       meter and controlled by a flow control
       valve on the suction line [2].

       The incinerator is 30 feet in length, has an
       outar diameter of 8.5 feet, and is lined
       with 8 inches of firebrick and castable
       lining. The incinerator has a firing
       capacity of 14 million BTU/hr A negative
       pressure is maintained within the
       incinerator in order to prevent fugitive
       emissions

       The incinerator is designed to dispose of
       vent gases and liquids simultaneously, but
       can process either wastestream
       separately should an AWFCO occur.

       The incinerator operates in both a fume
       and liquid-injection mode  While
       operating in the fume mode natural gas is
       used as a fuel. The liquid-injection mode
       includes operation while using liquid
       organics recovered from the site to
       supplement or replace the natural gas [2]

       The incinerator is equipped with two
       burners  A low-No, main burner is used
       for firing liquids The waste and
       atomization air are discharged from the
       nozzle through small orifices in the nozzle
       tip directly into the main bum flame [2]
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emcrgtncy ReiponM
Technology Innovation Offlcn
                                           163

-------
                                                            P»tro PracMKN* Supwftmd Site
       n**erintton MM! Ouaratlon /Cont.1
   Natural gas is used as auxiliary fuel for the
   incineration system and is fed to the
   incinerator through a burner located at the
   inlet end of the incinerator chamber, which
   is fired tangentially into the mam burner
   flame [2].  The design liquid waste feed rate
   is 1,600 Ib/hr and the design temperature for
   liquid-injection operation is 2,000°F to
   2,400°F

   The exhaust gas from the incinerator is
   channeled to the quench tower, where it is
   cooled with water to approximately 175°F
   The quench tank is a vertical, wet-walled,
   rubber-lined steel vessel. An emergency
   water tank is installed above the quench
   tank in the event of a toss of process water
   The RP estimate is estimated that 50% of
   the HCI in the exhaust gas is absorbed in
   the quench tank

   Following the quench tank, the exhaust gas
   enters the HCI absorber/caustic scrubber
   tower  The tower is a vertical fiberglass
   vessel containing packed sections  Water
   recirculated through the HCI absorber
   removes approximately 40% of the HCI in
   the gas.

   The caustic scrubber is designed to remove
   approximately 99 9% of the remaining HCI,
   97% of the CI2,90% of the SO2, and some
   participate matter A btowdown stream from
   the caustic scrubber is fed to the HCI
   absorber to remove salt and ash from the
   caustic scrubber system [2J
•  Residuals collected in the blowdown
   from the APCS Is treated by a carbon
   adsorption unit which is part of the
   groundwater treatment system

•  The off-gas leaves the scrubber system
   and enters a high-energy paniculate
   scrubber, where it is split into two
   streams The two streams are then
   recombined and are contacted with a
   recirculating water stream where water
   droplets entrap participate matter The
   particles are then removed from the
   water in the entrainment separator

•  Blowdown from the APCS is pumped
   into a neutralization system. The
   blowdown is treated with lime to bnng
   the pH into the 6 - 9 range before
   discharge under the terms of a NPDES
   permit to the Mississippi River

•  Combustion gases were drawn through
   the incineration system by a variable
   speed, induced draft fan and were
   exhausted through an 100-foot stack
   The fan has a 75 tip motor and is
   designed to handle 4,400 scfm  Design
   condition flue gas velocity is 3,800 -
   4,000 actual cubic feet per minute
   (acfm) at a temperature of 147°F

•  The groundwater which was isolated
   from the NAPLs in the phase separator
   is treated with carbon adsorption before
   being discharged under a NPDES
   permit
                         Table 2.
    Parameters
                                                              2Mconds
System Throughput
KHn Temperature
980 to/hr (liquid)
1,600' (fume mode)
2,000'F - 2,300'F (liquid mode)
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* and Emergency RttporiM
Technology Innovation Offlct
                                          164

-------
                                                                 ProcMMW SifMf/uncf SAW
                        TREATMENT SYSTEM PERFORMANCE
    The ORE requirements were set based on
    RCRA incinerator regulations 40 CFR part
    264, subpart O

    A ORE of 99.99% was required for each
    constituent of concern.

    A 60-mmute rolling average stack gas CO
    concentration less than or equal to 100 parts
    per million by volume (ppmv), dry basis,
    corrected to 7% O2 is required for the
    incinerator
                              Stack gas parbculate concentrations of
                              less than or equal to 0 04 grains per dry
                              standard cubic foot (gr/dscf), dry basis,
                              corrected to 7% O2 are required for the
                              incinerator.

                              HCI emissions of less than or equal to 4
                              Ib/hr are required for the incinerator.
    Two trial bums, one for liquid mode
    incineration and one for fume mode
    incineration, were conducted at Petro
    These trial bums were designed to operate
    the incineration system at conditions that
    would reflect worst-case destruction and
    removal of all constituents of concern

    Tetrachloroethene and monochlorobenzene
    were selected as the principal organic
    hazardous constituents (POHCs) * or the
    liquid mode tnal bum, 1,1,2 -
    tnchloroethane and tnchloroethei  were
    selected as the  POHCs for the fume mode
    tnal bum  The reported DREs for each
    POHC are included in Table 3-A and 3-B
                              To date, the incinerator at Petro has
                              operated within the operating limits
                              established during the tnal bum,
                              signifying that all cleanup requirements
                              that have been established are being
                              met  The AWFCOs and their frequency
                              of occurrence dunng the operation of
                              the incinerator are shown in Table 4-A
                              and4-B Trial bum and typical
                              operating parameters are shown in
                              Tables 5-A and 5-B
     Table 3-A Av
i Destruction and Removal Efficiencies from
Mode Trial Bum [3]
     Tabte 3-B. Average Destruction and Removal Efficiencies from Fume Mode Trial Bum [4,
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                          165

-------
                                                                            i Sup»rhmd SHo
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
            Table 4-A. Automatic Waste Feed Cutoffs for
 Msalmumorgsnlc squid fssd rate1
                                       1.470«Vhr
Monthly
 MMmumcombustkOTChsmbsfg^tsnysrature'
                                        2.000"F
Monthly
 Msxfcnun combustion crambsra^tsmpsrahire*
                                       2.300'F
Monthly
 MMmumcaurtte scrubber pH1
                                         7.5
Monthly
 MMmum HCI sbsoffasr yscyde flow rate
                                       130 axn
Monthly
  MstsnuHi caustic iciubbif recycle flow rate
                                       300 gpm
Monthly
 Msidmum stack gas flow rate1
                                      15,200 Mir
Monthly
 Mtaln^parfculste scrubber dOTsrsnM pressure1
                                     35 Inches we
Monthly
 Ma*num<
chamber pi
Monthly
                                                        IQOppmv
                                                             Monthly
 MHmum stack(
                     mtraflon1
                                   2% volume oYybaate
Monthly
 Mtrtmumqmnch chamber •xttgai temperature'
w.c -Watercolumn
'Bated on 60-mlnute nMng wwage
Instantamous vriue
                                        200-F
Mom>:
            Table 4-B. Automatic Waste Feed Cutoffs for Fume Mode Incineration [4,(
••••••iHHHaBBBBIMHiHHBIl^B^^^^^^^^^^BBHI^BMl
Mndmum eJr tlilppei wtter flow rate1

Mnknum combunon cnimoer OBB umpennurar
MkUmum caustic acrubber pH1
MMmum HCI etworberrecyde flow rate*
MMmum caustic enubber recycle flow rate1
Mrtmum stack QM flow rate1
Mndmum combustion ulMmbw pnMsunr

MMmum •IKK BM co conowinnon (oomciM to n» ug)
MMmum stack get O. concentraflon1
^^^•^^IH^^^I^MBH^H
200 gpm
1.600'F
7^
130 gpm
300 gpm
16,200 Mir
-Ollncrw6HtO
lOOppmv
2% volume dry basts
Monthly
Monthly
Monthlv
Monthly
Monthly
Monthly
Monthly
Monthly
Monthly
 Mssd on eXHrnraite i
Instsntsneous vshie
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offlo* of Solid Wattt «nd Emwgtnoy RttponM
Technology Innovation OffkM
                                            166

-------
                                                              Putro AOOMMM* Suptrfund Site
                    TREATMENT SYSTEM PERFORMANCE (CONT.-)
                                                      14 million BTU/hr
                                                                     14mmonBTU/hr
  Emission Rate
      Partlculate matter
      HO
      a,
  	HydKXiflroons
                                                     MA
                                                     NA
                                                     NA
                                                     NA
                      00264 gr/dscf
                       OIQOto/hr
                       0003 b/hr
                       07ppnw
  Operating Conditions
      ktadmumCOcani
              ntratton In gas (corrected to 7% Oj)
Mnknum combustion chamber gas temperature
MWmum caustic scrubber pH
MWmum HCI absorber recycle flow rate
MMmum caustic scrubber recycle flow rate
MMmum partteutate scrubber deferential pressure
Marfmum combustion chamber pressure
Quench chamber exft gas temperature	
   16ppmv
   2.042-F
   8.2 s u
   178 gpm
   369 gpm
 37 Inches we
-2 34 Inches we
   169-F
                                                                             17ppmv
                                                                             2,000°?
                                                                             131 gpm
                                                                             305 gpm
                                                                           35 inches we
                                                                          -1.26 Inches we
                                                                              178°F
we E Water column
	 Table 5-B Operating Parameters tor Fume Mode Incineration
£^3«i.r^^^^ii^ •*
Air Stripper Fkw Rate
Fuel-Fired Feed Rate
Emission Rate
Paniculate matter
HCI
q,
Hydrocarbons
Operating CondWons
Maximum CO concentration In gas (corrected to 7% OJ
Mnknum comDusoon cnarnoer gas tsmperature
Meodmurn combustion chamber pressure
Quench chamber exit gas temperature
93 gpm
14 mHon BTU/hr
NA
NA
NA
NA
1.2 ppmv
1,680»F
-2 443 inches we
156°F
fj§ ^ J
•(•WdHW
^^•{•^^^•^^•HaM
"" 	 ™^» 	
200 gpm
14 mWon BTU/hr
00018gr/dscf
OOltVhr
007IVhr
NotAvaUMe
38 ppmv
1,6008F
-450lncheewc
158°F
we «Watercolumn
    Data are available for concentrations of
    contaminants In the groundwater before
    treatment
                                            •   Data are also available for
                                                concentration of contaminants in the
                                                liquid and gaseous waste that were fed
                                                to the Incinerator the two trial bums
Parfa
       i Data Oualltw
    The QA/QC program used throughout the
    remedial action met EPA and the State of
    Louisiana requirements  All monitoring was
                                                performed using EPA-approved
                                                methods, and the vendor did not note
                                                any exceptions to the QA/QC protocols.
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                           167

-------
                                                                PftroPr
                                                                        rfundSto
                               TREATMENT SYSTEM Cos
    The RPs have installed and are operating the
    treatment system, including the incinerator,
    at the site
    The estimated treatment cost of $59,221,500
    and the projected costs were reported by the
    RPs in terms of capital costs and operation
    and maintenance costs  To date, the
    estimated capital costs for the incinerator are
    $44,552,586 and the estimated operation and
    maintenance costs are $14,668,908  The
    projected cost for the remaining capital
    expenditures is $6,971,000  The projected
    monthly operation and maintenance costs for
    the incinerator are $300,000. The estimated
    costs for thermal treatment were about
    $4,800,000. To date, a total of 213,000
    gallons of organic liquids and fumes have
    been incinerated This corresponds to a total
    unit cost of $280 per gallon and a unit cost
    for thermal treatment of $21  per gallon
    Tables 6 and 7 show capital costs and
    operation and maintenance costs for the
    remedy
                    Mobilization and preparatory work
   331
       Monitoring, sampling testing, and analysis
                                                                $4,310.840
                                                                      $520.000
   331
03

                                            $6,405,230
                                                                                  $150,000
   331
05
Surfa
oHBcDon and control
$2,418,588
                                                                                  $100.000
   331
08
Qroui
     i and control
$9,285,089
                                                                                 $3,100.000
   331
22
General requirements
                                 $3,973,752
                                                                                 $3.101,000
                    Tote/Capfttf Costs
                                                   $44,552,586
                                                             S6.971.000
                         Table 7  Operation and Maintenance Costs 171
   342
02
Monitoring, sampling, tasting, and analysis
                                                   $1.696,888
                                                                                   $35,000
   342
03
SHswork
                                                                  $232.520
                                                                       $6000
   342
14
Thermal trsatnwrt
                                 $4.749.582
                                                                                  $115000
   342
18
                                              $92.429
                                                                                    $2.500
   342
             22
                                                                $7.987.489
                                                                                   141 50
                    TottlOptntton and Mibttrmnc* Coed
                                                   $14,668,908
                                                                                  $300000
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wait* and Emergency Response
Technology Innovation Office
                                             168

-------
                                                          Petro Procrasof* Superfund Sfte
                     TREATMENT SYSTEM COST (CONTINUED)
    Actual and projected capital and operations
    and maintenance cost data are available
    from the RP for this application
                     OBSERVATIONS AND LESSONS LEARNED
    Site personnel feel that there have been
    relatively few problems with the incinerator
    thus far  They have attributed this to the
    fact that they used all of their allowable pre-
    operation, or shakedown, hours to properly
    adjust the system in order to successfully
    complete the tnal bum [5]
                                   REFERENCES
1   Suoerf und Site Status Summaries. US
    EPA, "Petro Processors of Louisiana, Inc",
    http //www.epa.gov/earth1r6/6sf/petropro,
    May 9,1997

2   Remedial Design and Construction Plan.
    Petro-Processors. Inc. "Design &
    Construction Specifications. Operating
    Specification for the Liquid Mode Operation
    of the LTAD Incineration System,
    Addendum A, Volume III, Part 5, Book 10 of
    17, NPC Services Inc, November 15,1995

3   Remedial Design and Construction Plan.
    Petro-Processors. Inc. "Design &
    Construction Specifications Operating
    Specification for the Liquid Mode Operation
    of the LTAD Incineration System,
    Addendum A, Volume III, Part 5, Book 1 of
    17, NPC Services Inc, November 15,1995
4   Remedial Design and Construction
    Plan. Petro-Processors. Inc. "Design &
    Construction Specifications  Operating
    Specification for the Fume Mode
    Operation of the LTAD Incineration
    System, Addendum A, Volume III, Part
    4, Book 1 of 11, NPC Services Inc,
    November 15,1995

5   Personal Communication, Ms Cynthia
    Kaleri, April 2,1997

6   Personal Communication, Mr. Bryan
    McReynolds, July 24,1997

7   Personal Communication, Mr Marty
    Munley, July 28,1997
U.3 ENVIRONMENTAL PROTECTION AGENCY
Offlet of Solid WMM and Emergency RMponi*
Technology Innovation Office
                                         169

-------
This Page Intentionally Left Blank
              170

-------
On-Site Incineration of Basin F Liquids at the
  Rocky Mountain Arsenal Superfund Site
        Commerce City, Colorado
                   171

-------
     Incineration at the Rocky Mountain Arsenal Superfund Site
                         Commerce City, Colorado
Site Name:
Rocky Mountain Arsenal
Superfund Site
Location:
Commerce City, Colorado
                             Contaminants:
                             Organochloric and
                             organophosphoric pesticides
                             and metals
                              ardnn
                              dieldnn
                              vapona
                              copper
                              zinc
                              arsenic
                                                        Period of Operation:
                                                        July 1993-July 1995
                                                        Cleanup Type:
                                                        Intenm response
Vendor:
T-Thermal Sub-X® Liqui-
Datur® Incinerator
manufactured by T-Thermal
Incorporated and cross-
licensed by Nittetu Chemical
Engineering, Limited
SIC Code:
NA
                             Technology:
                             On-Site SQI Incineration
                             • High-temperature oxidation in
                              a down-fired, SQI
                             • High-energy ventun scrubber
                              for paniculate emission
                              control
                             • Packed tower caustic
                              scrubber for neutralization of
                              GXn&USt QdSGS
                             • Residuals transported to off-
                              site handling facility
                                                        Cleanup Authority:
                                                        CERCLA and State.
                                                        Colorado
                                                        • U.S. Army, PRP, and
                                                          EPA enter into Federal
                                                          Facilities Agreement 2/89
                                                          - includes 13 intenm
                                                          response actions
                                                        -ROD signed 12/9/96
                                                        • DoDLead
                                                        Point of Contact:
                                                        Colonel Eugene H Bishop
                                                        Program Manager
                                                        Rocky Mountain Arsenal
                                                        Commerce City, CO
                                                        80022-2180
                                                        (303) 289-0467-Public
                                                        Affairs Off ice
                                                        (303) 286-8032-SQI
                                                        Information Hotline
Waste Source:
Evaporation basin used to store
manufacturing wastewaters
                             Type/Quantity of Media Treated:
                             Uquids
                             • 10 9 million gallons
Purpose/Significance of
Application:
Innovative design used to
capture metal particulates;
250,000 pounds of copper
recovered and recycled
Regulatory Requlf
                     ite/Ctoanup Qoala:
•gulatory Reqi              	
Destruction and Removal Efficiency (ORE) of 99.99% for all constituents of concern as required
by Resource Conservation and Recovery Act (RCRA) Incinerator regulations in 40 CFR part
264. tuboartQ	
                                       172

-------
     Incineration at the Rocky Mountain Arsenal Superfund Site
                         Commerce City, Colorado
                                    (Continued)
Results:
Monitoring and tnal bum data Indicate that all ORE and emission standards have been met
Description:
RMA was established in 1942 and historically has been used for manufacturing and
demilltarizating chemical incendiary weapons Portions of RMA were leased for the private
production of agricultural chemicals including pesticides from 1947 to 1982. Between 1957 and
1982 an evaporation pond (Basin F) was used for disposal of various wastewaters from the site's
manufacturing process and wastes from demilitarization activities

The Army and the on-site chemical manufacturer were designated as responsible parties in a
Federal Facilities Agreement (FFA) entered into in 1989  The FFA specified 13 interim response
actions (IRAs), including the remediation of Basin F A Record of Decision (ROD) for all operable
unite at the site was signed June 11,1996

The Army selected SQI to dispose of Basin F liquids  The SQI system included an atomizing
liquid injection system, an incinerator chamber; a quench chamber; a spray dryer; a venturi
scrubber for paniculate matter control, a packed-tower scrubber for neutralization of off-gases;
and a residuals handing facility

Full-scale operation of the SQI began in July 1993, and incineration of approximately 10 9 million
gallons of Basin F liquid was completed by July 1995  The SQI was decommissioned,
dismantled, and sold for parts, per the FFA, upon completion of the project. All applicable and
relevant or appropriate requirements were met throughout the project.

The actual cost for remediation of Basin F was approximately $93,000,000. including
$14,800,000 in capital costs and $78,500,000 in operation and maintenance costs.
                                        173

-------
                                                      ftocfcy Mountain ArawMf Supwfund SH*
This report presents cost and performance data
for the application of on-sfte incineration at the
Rocky Mountain Arsenal (RMA) Superfund Site
near Commerce City, Colorado Anon-site
submerged quench incinerator (SQI) was used
from July 1993 through July 1995 to treat liquid
wastes generated at RMA

The primary contaminants of concern in the
liquid waste included organochloric pesticides
(including aldrin and dieldrin), organophosphoric
pesticides (including vapona), and metals
(including copper, lead, arsenic, and zinc)

RMA was established in 1942 and historically
has been used for manufacturing and
demilitanzating chemical incendiary weapons.
Portions of RMA were leased for the private
production of agricultural chemicals including
pesticides from 1947 to  1982  Between 1957
and 1982 an evaporation pond (Basin F) was
used for disposal of various wastewaters from
the site's manufacturing process and wastes
from demilitarizations

The Army and the on-site chemical
manufacturer were  designated as responsible
parties in a Federal Facilities Agreement (FFA)
entered into in 1989. The FFA specified 13
interim response actions (IRAs), including the
remediation of Basin F  Standards for Basin F
were established in a 1990 Final Decision
Document (DD)  These standards included
treatment resulting  in a 99 99% destruction and
removal efficiency (ORE) of organic
constituents A Record of Decision (ROD) for
all operable units at the  site was signed
June 11,1996
                                                 Remediation of Basin F was conducted in
                                                 two parts  The first part consisted of
                                                 removal and temporary storage of liquid,
                                                 and ^removal and stockpiling of solids and
                                                 sludges. Tte second part consisted of
                                                 disposal of the stored liquid  The remainder
                                                 of this document addresses the disposal of
                                                 Basin F liquids, unless otherwise stated

                                                 The Army selected SQI to dispose of Basin
                                                 F liquids  The SQi system included an
                                                 atomizing liquid injection system; an
                                                 incinerator enamben a quench chamber; a
                                                 spray dryer; a venturi scrubber for
                                                 paniculate matter control, a packed-tower
                                                 scrubber for add neutralization of the
                                                 exhaust gases; and a residuals handing
                                                 facility

                                                 Full-scale operation of the SQI began in
                                                 July 1993, and incineration of approximately
                                                 10.9 million gallons of Basin F liquid was
                                                 completed In July 1995  The SQI was
                                                 decommissioned, dismantled, and sold for
                                                 parts, per the FFA, upon completion of the
                                                 project Ail applicable and relevant or
                                                 appropriate requirements (ARARs) were
                                                 met throughout the project

                                                 The actual cost for remediation of Basin F
                                                 was approximately $93,000,000. This
                                                 consisted of approximately $14,800,000 in
                                                 capital costs and $78,500,000 in operating
                                                 and maintenance costs.
U.S. ENVIRONMENTAL PROTECTION AQENCY
OfflM of Solid Watt* And Emergency Ratpontt
Technology Innovation Office
                                          174

-------
                                                      Rodty MounttAi Aram*/ Supvfund Sft»
Rocky Mountain Arsenal Superfund Site
Commerce City, Colorado

CERCLISf  MA

ROD and DD Date: A Decision Document for
the Basin F IRA was issued May 1890  A single
ROD for all on-site OUs, including Basin F. was
signed June 11,1996
Type of action: Interim response (on-site
SQI incineration)

Period of tail-scale Incinerator operation:
July 1993 through July 1995

Quantity of material treated during
application: 10.9 million gallons of liquid
hazardous waste
Historical Activity that Generated
Contamination at the Site. Manufacture and
demilitarization of chemical munitions and
manufacture of pesticides

Waste Management Practice that
Contributed to Contamination-  Disposal of
manufacturing wastewater into an evaporation
basin

Site History:

•   RMA was established in 1942 for the
    manufacture of chemical and incendiary
    munitions as well as demilitarization of
    chemical munitions  Pesticides were
    manufactured at the site from 1947 through
    1982

•   The RMA site is located on approximately
    17,000 acres  10 miles northeast of
    metropolitan Denver, Colorado and directly
    east of Commerce City

•   From 1943 through 1950, stocks of
    Levinstein mustard gas were distilled,
    several million rounds of mustard-filled
    shells were demilitarized, and mortar rounds
    filled with smoke and high explosives were
    test-fired
    In 1947, portions of RMA were leased
    for production of chlorobenzene, DDT,
    naphthalene, chlonne, and fuzed
    caustic

    In 1951, another manufacturer assumed
    the lease and produced pesticides until
    1982

    Through 1956, waste streams from the
    above manufacturing operations were
    discharged to unlined evaporation
    basins (Basins A through E)

    In 1956, Basin F was designed and
    constructed as an evaporation basin to
    receive various manufactunng wastes.
    The basin had a surface area of 93
    acres and a capacity of approximately
    243 million gallons. The basin was
    constructed using an asphalt liner
    covered by a 1-foot layer of sand
    Between August 1957 and December
    1981, Basin F was the only evaporative
    wastewater disposal location in service
    at RMA.

    Basin F was located in the northeast
    section of RMA and was used to
    dispose of wastes containing
    organochloric and organophosphoric
    pesticides and various metals
U.S. ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Watt* and Emergency ResportM
Technology Innovation Offlc*
                                          175

-------
                                                      Rocky Mountain Amnal SupMfunrf Site
            fCant.1
    In 1986, the Department of Interior, the
    Department of Health and Human Services,
    the Department of Justice, and the U.S.
    EPA (EPA et a/,), and the potentially
    responsible parties (PRP) at the site agreed
    (via the Basin F Memorandum of
    Understanding) to undertake a removal
    action to address threats to human health
    and the environment posed by liquids and
    contaminated soils and sludges in Basin F
    Part One of the removal action (completed
    in December 1968) included the removal of
    liquids from  Basin F to storage tanks and a
    surface impoundment, and the removal of
    soil and sludge to a double-lined waste pile.
    Part Two included incineration of the Basin
    F liquid that was stored in the holding tanks
    and surface impoundment

    In February 1989, EPA et al.,  and the PRPs
    entered into a FFA for all of RMA, including
    remediation of Basin F.

    In May 1990. the Army issued a Final
    Decision Document for Basin F Liquids
    which specified remediation via SQI with a
    venturi/packed-tower scrubber.
•  Between July 1993 and July 1995, the
   SQI processed 10.9 million gallons of
   Basin F liquids, meeting the standards
   established in the FFA.

Regulatory Context:  In February 1989,
EPA et al., the Army and the second PRP
entered into a FFA that stated RMA Is
subject to the cleanup standards in Section
121 of the Comprehensive Environments
Response, Compensation, and Uabilrt / Act
(CERCLA) and provisions of the National
Contingency Plan for Oil and Hazardous
Substances (NCR).

Remedy Selection. On-stte submerged
quench incineration (SQI) was selected as
the remedy for Basin F liquids at RMA
based on the results of feasibility studies, a
preliminary risk assessment, and treatability
studies (laboratory and pilot-scale testing),
economic considerations; and input from the
public
TtttMlhM
                                    Table 1. Timeline
1942
1M3-19SO
1947
1961-1962
1957-1982
1986
JUV1987
May 1988 -Daoamtoar
1986
8aplambaM9SB
February 1969
Dacambar1989
RMA aatottahad tor manufacture and damMMzaton of chamtealaridlmMmtaymunNtona.
ChamlcalimailfcnamanulaclufadanddamB*^^
Portion* of RMA teased; manufacture oC cMorabanzana, DDT, naphAalana. chtorina, and fuzad
PRP ataumaalaaiiind manufacture paattcMee
BarinFtouaadaaanwaporaltonpondtorMn^RIM
U S, Aimy. another PRP, and EPA al al . agraa to Bartn F Mamorandum of Undaratandbig,
outttfng
BaatoFIRA
RMAptoadcnttjaNPL

ran una 01 oaam r IHA eonaucno (ramoMi am Mmporavy aniapa OF MMMM;
PartTtoof Bailn F IRA InlMad (oharaeMriaatoor
^B^M«k^Jk^ ^^••kaj* drf ta^^HbMMBit t^rfi hr> nJ-mm j ft a^biM f& 4*^^rfaM^ant n*ix»»»»t
•NrTpfipvt. wwKi oi oMnNvn wcnnowyy, o won or vMnrnvn PTOOMII
U.8. Army, andhar PRP, and EPA at al , antar Into a FFA that Ineludat 13 IRAa at RMA (Including
atwo*artlRAforrarmK*atlonforBaiinF
Final Tcaafenam Aaaasamant Raport daaorttng Vw prafarradallarnallvafortraalmantofBatlnF
Intffk
US ENVIRONMENTAL PROTECTION AGENCY
Offkw of Solid Waat* and Emergency Racpona*
Technology Innovation Offlc*
                                          176

-------
                                                      Rocky Mountain Annul Suf*rfund Slto
                                    Table 1. Timeline
MsylMO
Ssctsmbsr 1902
Msy 20-25. 1903
Jim 10-12. 1903
July 1993 -July 1995
DKntfNM993
Msy 1996
FhisJ Dwtoton DocunMnl tor Bask) F taiidlnKiiMntlsauML
Trial Bum Ptan submitted

TWO MN DUIIB COnOUCMQ HO SSISDISn KlMlm MINIS)
TrW Bum conducted
Futacato opsnflon of SOI conducted
TiW Bum SumnMiy Rsport compMsd.
SQI dscofnmte»lon«d,oTsnwiisdtrt sold for parts
Site Management DOO-Lead

Oversight: EPA with input from Colorado
Department of Health, U.S Fish and Wildlife
Service, and Tri-County Health Department

Remedial Project Manager:
Laura Williams
U.S. EPA Region 8
99918th Street, Suite 500
Denver, Colorado 80202
(303)312-6660
Type of Matrix Proceseed Through the
Treatment System- Liquid waste from
pesticide manufacturing processes
U.S. Army Contact:
Colonel Eugene H Bisnop
Program Manager
Rocky Mountain Arsenal
Commerce City, CO 80022-2180
(303) 289-0467 - Public Affairs Office
(303) 286-8032 - SQI information Hotline

Treatment System Vendor and Operator:
T-Thermal Sub-X® Uqui-Datur® Incinerator
manufactured by T-Thermal Incorporated
and cross-licensed by Nittetu Chemical
Engineering, Limited

SQI system operated by Western Inc.
        Contaminants: Organochloric and
organophosphoric pesticides and metals in
solution

•   The contaminants of greatest concern
    include pestiddss (aldrin, dtoldrin, and
    vapona) and metals (copper, zinc, and
    arsenic)

•   Several organochlorte pestiddes were
    detected, including vapona at a maximum
    concentration of 2.40 mg/L
   Several organophosphoric pesticides
   were found at concentrations ranging
   from 011 to 0.89 mg/L

   Several metals were detected, including
   copper, zinc, and arsenic at maximum
   concentrations of 210 mg/L 0.95 mg/L
   and 3.0 mg/L respectively.
US ENVIRONMENTAL PROTECTION AGENCY
OfHoe of Solid Waste and Emergency Response
Technology Innovation Offlcs
                                         177

-------
                                                       /tacfcy Mountain 4fumf Supwfluntf Site
    The Basin F liquid was sampled and
    analyzed and determined to be corrosive,
    according to RCRA regulations in 40 CFR
    261.22.  The higher heating value of Basin
    F liquid was measured to be 37 BTU/Ib
   Specific gravity and pH of the liquid
   were measured to be 1.2 and 6.02,
   respectively.
                                       SYSTLFJ DFSC
Submerged quench incineration system
including:

•   Atomizing liquid injection system
•   Submerged quench incinerator
•   Quench chamber
•   Spray dryer
Post treatment (air):

•   High-energy venturi scrubber for
    partlculate matter control
•   Packed tower caustic scrubber for add
    neutralization of the exhaust gases
    The incineration system at RMA consisted
    of high-temperature oxidation in a down-
    fired. SQI followed by a high-energy venturi
    scrubber for paniculate emission control and
    a packed tower caustic scrubber for acid
    neutralization of the exhaust gases  A
    schematic of the incineration system is
    presented in Figure 1

    During operations, liquid waste was fed to
    the flame zone of the down-fired incinerator
    through an atomizing spray nozzle. Molten
    salts (residuals from combustion) flowed
    down the sides of the Incineration vessel
    and fell into a quench tank with water
    circulation. Combustion gases were
    bubbled through the quench tank and routed
    to the ARCS. The quench tank liquid
    (brine), which contained dissolved salts and
    residual heavy metals, was transported first
    to the residuals storage facility and
    ultimately off-site where the metals were
    removed and recycled to a smelter.

    The ARCS included of a mechanical venturi
    scrubber for removal of paniculate* In the
    off-gases from the quench tank.  TheAPCS
    also Included a caustic (packed) tower
    scrubber used as secondary treatment
    for the quench tank gases and primary
    treatment for the discharge air from the
    residuals handling facility The packed-
    tower scrubber system consisted of an
    absorber section, a mist eliminator, and
    an exhaust stack

    Combustion gases were drawn through
    the SQI and ARCS by an induced-draft
    fan and were exhausted through a 30-
    meter reinforced, concrete stack.
    Typical exit gas velocity was 14.7
    meters per second.

    The SQI was developed by T-Thermal,
    Inc  The SQI design operating
    parameters are presented in Table 2
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergsncy ReiponM
Technology Innovation Offlo*
                                           178

-------
                                                  Rocky Mountain Anuial Suporfund SHo
                   TREATMENT SYSTEM DESCRIPTION (CONT.)
  Cm tmountun after quench
        Figure 1  Conceptual Schematic of the Submerged Quench Incineration System
                       (prepared by Woodward-Clyde Consultants)
                       TRF. ATMFNT  Svsn.r.i PERFOHMANCF
   The cleanup goals and standards specified
   in the FFA were consistent with the
   requirements In Section 121 of CERCLA
   and the provisions of the NCP.

   The maximum acceptable concentrations of
   contaminants corresponded to a 1x10*
   excess lifetime cancer risk and a hazard
   Index of 1 00.
The required DRE for POHCs was
9999%
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offlo* of Solid Waste and Emergency RMponM
Technology Innovation Office
                                      179

-------
                                                      Rocky Mountain Aram/ Suf*rfund Sit*
    Two mini-burns were conducted at RMA
    May 20 through May 25,1993, and a full
    trial bum was conducted from June 10
    through June 12,1993  The bums ware
    designed to operate the incineration system
    at condWons that would reflect worst- case
    destruction and removal of all constituents
    of concern Monochtorobenzene and
    carbon tetrachloride were selected as
    POHCs for the trial bum at RMA. The
    POHC feed rate, stack gas emissions rate,
    and calculated DREs are shown in Table 3
    Interim operating limits were then
    established based on results of the mini-
    bums These interim limits were used until
    approval of final limits.
                       The SQI operated within the operating
                       limits established during the mini bums
                       and trial bum, signifying that all
                       emissions requirements were met or
                       surpassed  Tnal bum and interim
                       operating parameters are shown in
                       Table 4
             Table 3. A
Destruction and Removal Efficiencies from Trial Bum
•Ndttwr POHC %MS detected In toe waste feed.

                             Table 4 Operating Parameters [4]
WsBtaFMdRste
Emission Ratr
Parfcutoto -O7%Ot
• O12K CO,
HO
CO(HRA)
THC
NO,
S0t
HO
Openflng CondWons
MMmum SQI Chsmbsr Tsmpsmtur*
MNWVNIff) ^NkMnOA TNVI9
minimum Beets Oxygsn
Minimum Quench pH
Minimum Scrubber pH
Mtadmum Vwturt Rsoyoto Flow Rita
178feAi*i

OQ214grakisftkcf
00320gra*w/*cf
0^291 toUr
51^ppm
8.2Sppm
131 ppm
55 6 ppm
zsoppm

183B*F
272 see
8.50%
012
5.78
l267qaVmki
<166bAnln

<006gralnsAiscf
<010g«*isAJ8cf
<4h/hr
< 100 ppm
MA
NA
NA
NA

1825'F
2.7 S«C
9%
4
6.25
lOOgsVmln
U.8. ENVIRONMENTAL PROTECTION AGENCY
Of/let) of 8oHd Wsjstc and Emergency RMporwc
Ttchnology Innovation OffkM
                                          180

-------
                                                        Rocky Mountain A/MM/ Sqpevfund Site
MBdmum Venturi DffleranM Praseum
Ma*num UquU/Ga* Raflo
Mttdmum Scrubber ftocycto Rate
Natural Gas Row Rate
Total Combustion Air
SOI Chamber Prasaura
90 fetches W.C.
mgaMccf
2857gaHi*i
438scfm
7,107 scfm
3.87 prig
80 Inches W.G.
9.3gaMccf
ZTOgaMnln
MA
MA
NA
• A 	 «•»•«•••*!••* *«»l»a» ***- 	 	 	 •• — ' 	 • -»•-»—-•—• 	 MM nuia ^ J 	 	 - ' 	
*ont half th* daMcflon Imtt for kKMckMlnon-delactraMlte ww
   lm In* »rtbfchrt during hw-mlnH)unw"cono^               TtimvriuaewmusadatllmrlsumilapprovaJof
   th* ImHs pnposad during thv trial burn
dtcf - Dry standard cubic tot
HRA-HounyroingavBraoe
tef-Thousand cubic feet
paig • Pounds per square Inch, gauge
scfm - Standard cubic feet per minute
NA-NotaMtabto
w.c -Watercolumn
    Complete results of Basin F liquid testing
    can be found in the Summary Report for
    Incineration of Basin F Wastes [1] and the
    Trial Bum Summary Report [4].
     Complete risk assessment results can
     be found in the Final Human Health
     Risk Assessment [S\.
    According to site personnel, Quality
    Assurance and Quality Control (QA/QC) for
    all testing and associated analyses,
    evaluation of all data, and the complete
    decision making process was followed in
    accordance with the FFA.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offlo* of Solid Wast* end Emergency Reeponae
Technology Innovation Office
                                           181

-------
                                                      Rocky Mountain Antnal Suptrfund Sfa
                             TREATr:
IT SYS'
•   IT and Weston, Inc were contracted to
    commission, test, and operate the SQI at
    the site.

Coat Data

•   The total project cost of $93,337,779 was
    reported by Rocky Mountain Arsenal in
    terms of capital costs and operation and
    maintenance costs The capital costs for
    the incineration system were $14,829,318
    and operation and maintenance totaled
    $78,508,461  The total costs for thermal
    treatment were reported as $58,145,681 A
    total of 10.9 million gallons of liquid waste
    were incinerated. This corresponds to a
    total unit cost of $9 per gallon, and a unit
    cost for thermal treatment of $5 per gallon
    Tables 5 and 6 show the operation and
    maintenance costs for incineration
331
331
331

01
02
03

MobMzaKon and preparatory wok
Monitoring. samping, tasting, and analysis
SMewoifc
Total Cartta! Costs
$6,923,728
$3.505.590
$2.400,000
$14.829.318
                                          and Maintenance Costs
342
342
342

14
18
22


1 iWTTtW 1 IMUIMII (inCtflMaWOilJ WTHCfl nCMOM
• EqulpnMnt
• Labor
• Dlrsct operating costs
• Overhead
DteoossJ
QsnarsJ Rsoulremsnta
TotfJOottqpon v$ MalntoWKi Costa
$58,145,681
$18.936.616
$1.428.164
S78.S06.4ei
   Actual capital and operations and
   maintenance coat data are available from
   Rocky Mountain Arsenal.
U.S. ENVIRONMENTAL PROTECTION AOENCY
Offlos of Solid Watt* and Emwgtnoy RsjponM
Technology Innovation Offlc*
                                          182

-------
                       OBSERVATIONS AND LESSONS LEARNED
 •   Unexpected weather conditions caused
    delays in the start-up of the incinerator  A
    heavy rainfall classified as a 25-year/24-hour
    event significantly increased the volume of
    liquid in the open holding pond just before
    the start of the project  This necessitated
    construction of a special double-lined holding
    pond for additional storage capacity
    Additionally, a tornado touched down near
    the tanks and holding pond, requiring
    inspection and subsequent repair of
    equipment.

 Public Involvement

 •   An extensive Community Relations program
    was developed in 1988 at RMA that
    addresses public concern relating to the
    entire site This program included the
    establishment of an on-site information
    center, providing speakers for local clubs and
    organizations, attending conventions, public
    meetings, and open houses.

    A 24-hour telephone hotline was established
    and a monthly publication (the Rocky
    Mountain Arsenal SQI Update) was
    developed

    In addition, a Restoration Advisory Board,
    including members of local governments and
    the public, was established to obtain input on
    the remedial approach from various parties

    According to site personnel, these actions
    helped to alleviate public concern related to
    the on-slte remediation action
                                   The draining of liquid from Basin F and
                                   the subsequent drying of soils,
                                   sediments, and the Basin F liner was
                                   identified as a significant odor concern
                                   by nearby residents. Air purifiers were
                                   distributed to affected homes to help
                                   alleviate the odors. lexicologists from
                                   various agencies identified the
                                   compounds causing the odors and
                                   determined that they did not present
                                   acute health effects.
                                     REFERENCES
    Summary Report for Incineration of Basin F
    Wastes at Rockv Mountain Arsenal. Volume
    1; September 1988

    Final Decision Document for the Interim
    Response Action, Basin F Liquid Treatment,
    Rocky Mountain Arsenal, Volume I - Text,
    May 1990.
3   Interim I
> Action. Basin F Liquid
    Incineration Project, Implementation
    Document, Volume I; January 1992.
                                  Trial Bum Summary Report for the Interim
                                  Response Action, Basin F Submerged
                                  Quench Incineration Project, Volume I,
                                  December 1993

                                  Interim Response Action, Basin F Liquid
                                  Incineration Project, Final Human
                                  Health Risk Assessment, Volume I;
                                  March 1994
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wute and Emergency Response
Technology Innovation Office
                                           183

-------
This Page Intentionally Left Blank
               184

-------
   On-Site incineration at the
Rose Disposal Pit Superfund Site
 Lanesborough, Massachusetts
              185

-------
         Incineration at the Rose Disposal Pit Superfund Site
                      Lanesborough, Massachusetts
Site Name:
Rose Disposal Pit Superfund
Site
Location:
Lanesborough, Massachusetts
Contaminant*:
Primary Contaminant
Groups: PCBs, volatile
organic compounds (VOCs)
including TCE, benzene, and
vinyl chloride
•  PCBs at were detected at
   concentrations up to
   440,000 mg/kg The
   average PCB concentration
   was 500 mg/kg
Period of Operation:
February 1994-July 1994
Cleanup Type:
Remedial action
Vendor:
Mark Phillips
Maximillian Technology
Pittsf ield, MA
(413) 494-3027
SIC Code:
NA
Technology:
On-sfte incineration
•  Soil was pretreated with
   crushing and shredding to
   achieve a homogenized
   incinerator feed
•  Incineration system
   consisting of rotary kiln and
   secondary combustion
   chamber (SCC)
•  SCC temperatures
   averaged 2000 T
•  Ash was discharged, and
   returned to the excavated
   areas on site
Cleanup Authority:
CERCLA
•  ROD Date. 9/30/96,
   11/21/89
•  EPA-lead
Point of Contact:
Pam Shields
U S  EPA Region 1
Waste Source:
Disposal of manufacturing
wastes in an open trench
Type/Quantity of Media Treated:
Soil (51,000 tons)
Purpose/Significance of
Application:
Incineration of PCB-
contaminated soil
Regulatory Requirements/Cleanup Goals:
Destruction and Removal Efficiency (ORE) of 99 9999% for DCBs as required by Toxic
Substances Control Act regulations in 40 CFR part 761 subpart D
Results:
Treatment performance and air monitoring data collected during this application indicated that all
required performance and standards emissions were achieved
                                      186

-------
         Incineration at the Rose Disposal Pit Superfund Site
                     Lanesborough, Massachusetts
                                  (Continued)
Description:
Between 1951 and 1959, the 14-acre residential tot received wastes from a nearby manufacturer
Soil at the site was contaminated with PCBs as well as volatile organic compounds (VOCs)  A
Record of Decision signed September 23,1988 and November 21,1989 specif iedon-site
incineration as the remedial technology for the soil and sediments Site cleanup goals and DRE
standards were specified for constituents of concern

On-sfte incineration began in February 1994 and was completed in July 1994  The treatment
system consisted of a rotary kiln and an SCC  Kiln ash was treated and stored and treated gas
was exhausted to a stack. Incineration has achieved the soil cleanup goals specified in the ROD

No information was available on costs for the remedial action.
                                      187

-------
                                                             Alow Disposal Pit Superfund Site
                                EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site incineration at the
Rose Disposal Pit Superfund Site (Rose Site) in
Lanesborough, Massachusetts. A rotary kiln
incinerator was operated from February 1994 to
July 1994 as part of a remedial action

The Rose site is a 1 5-acre section of a 14-acre
residential lot located in Lanesborough,
Massachusetts. From 1951 through 1959 and
possibly later, wastes from a nearby
manufacturer were disposed of in an open
trench at the site. Soil at the Rose Site is
contaminated with PCBs, as well as volatile
organic compounds (VOCs) including
trichloroethylene, benzene, and vinyl chloride
Measured concentrations of PCBs at the site
VHP re as high as 440,000 mg/kg

In 1988, EPA signed a Record of Decision
(ROD) specifying on-site incineration as the
selected remedy for the contaminated soil at the
Rose Site In 1989, EPA released an
Explanation of Significant  Differences (ESD)
which outlined EPA's agreement with the
responsible party to conduct complete source
remediation. To achieve complete source
remediation, the responsible party excavated
and incinerated a greater volume of
contaminated soil than that specified in the
ROD  The ROD set a Destruction and Removal
Efficiency (ORE) standard for PCBs of
The remediation activities performed at the
Rose Site also included the construction and
operation of a groundwater treatment system,
However, unless otherwise indicated, only
Issues relating to on-site incineration are
discussed in this report
The excavated soil at the Rose Site was
crushed and blended before incineration
The blended soil entered the rotary kiln at
through the kiln co-current with the exhaust
gas. Kiln ash was quenched in a water
bath, while the exhaust gases were directed
to a secondary combustion chamber (SCC)
for further destruction of contaminants in the
waste feed

The air pollution control train consisted of a
cyclone separator for removal of larger
paniculate matter, a quench tower, a
baghouse for removal of finer paniculate
matter, a second quench tower, and a wet
scrubbing system designed to remove
residual contaminants. Dust removed by
the cyclone separate^ and the baghouse
was discharged to the ash quench bath
Wastewater from the quench towers and the
scrubbing system was also discharged to
the ash quench bath  All of the solid waste
generated by the system was removed with
the incinerator ash and landfilted on site

Dunng its five months of operation, the
incinerator processed approximately 51,000
tons o* contaminated soil  Treatment
performance and air monitoring data
collected during this application indicated
that all required performance and standards
emissions were achieved
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           188

-------
                                                            Ro»* Dfepom/ Pit Sup»ffund SH»
                                  SITE INFORMATION
Identifying Informatlcfl

Rose Disposal Pit Superfund Site
Lanesborough, Massachusetts

CERCLIS f MAD980524169

ROD Date:  September 23,1988 (ROD)
            November 21,1989 (ESD)
Treatment Application

Type of action: Remedial (on-site rotary
kiln incineration)

Period of operation: February 1994 - July
1994

Quantity of material treated: 51,000 tons
of contaminated soil
Historical Activity that Generated
Contamination at the Site:  The site was used
for disposal of waste generated from many
different manufacturing processes

Corresponding SIC Codes: NA

Waste Management Practice That
Contributed to Contamination: Disposal of
manufacturing waste in an open trench

Site History:

•   The Rose Site is located on Balance Rock
    Road in Lanesborough, Massachusetts
    approximately 4 miles north of Pittsfield
    The site is bounded on the north and
    northeast by the deciduous forest of
    Balance Rock State Park, on the east and
    southeast by cropland and pasture, on the
    west by mixed forest, and on the southwest
    by a residential area

•   The Rose Site is the location of a trench
    used for disposal of manufacturing wastes
    generated by the responsible party between
    1951 and 1959 The wastes contained
    PCBsandVOCs

•   Between 1980 and 1982, EPA conducted
    the preliminary assessment, site inspection,
    and field investigation All subsequent
    activities at the site have been performed
    by the responsible party

•   A remedial investigation (Rl) was conducted
    in 1983 and supplemented in 1986, and the
    feasibility study (FS; was conducted In
    1988.
•   Based on the results of the Rl and the
    FS, a ROD was signed on September
    23,1986 specifying excavation and on-
    srte incineration of contaminated soils.
    The ROD specified excavation of the
    contaminated soil to the top of the
    saturated zone

•   In 1989, EPA released an ESD which
    outlined EPA's agreement with the
    responsible party to conduct complete
    source removal  Under this agreement,
    the responsible party excavated
    additional soil below the saturated zone
    Complete source removal allowed the
    responsible party to avoid installing a
    cover and establishing other long-term
    institutional controls

•   Approximately 51,000 tons of soil were
    processed between February 1994 -
    July 1994  By July 1994 all of the
    cleanup goals had been met for the
    contaminated soil, and incineration had
Regulatory Context:

•   In 1984, the Rose Site was added to the
    National Priorities List (NPL)

•   A ROD was signed in 1988 requiring the
    responsible party to conduct remedial
    activities at the Rose Site
U S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          189

-------
                                                          AM* Otpotul Mr Supfrfund SU»
   In 1989, EPA released an ESD which
   outlined EPA's agreement with the
   responsible party to conduct complete
   removal; this action was more aggressive
   then that associated with the goals set
   forth in the ROD

   The ORE and ash residual standards were
   established the provisions of the Toxic
   Substance(s) Control Act (TSCA) and
   associated regulations in 40 CFR part 761
   subpartD.

   The selected remedy is consistent wfth
   the Comprehensive Emergency
   Response, Compensation and Liability
Act of 1980 (CERCLA). as amendeo by the
Guperf und Amendments and Reauthorization
Act of 1986 (SARA), and to the extent
practicable, the National Contingency Plan
(NCR) in 40 CFR part 300.

Remedy Selection: EPA determined that on-
site incineration was the only available
alternative that satisfied all of the criteria
established in the ROD. particularly
permanence, and that on-site incineration was
more cost effective than off-site incineration
for the Rose Site [1].
1851-1959
1960-1982
1983
1984
May 1984
1966
1988
September 23. 1988
Nwwnber21,1989
Octobar1993
February 1994
April 1994 -July 1994
Wattes am dhpoead of by ttw HP at ffw Ron Disposal Pit site.
M_kl 	 L^. — „ 	 « _l>^ * 	 MS 	 	 • «_•_•• 	 ••_.» 	 tm ii it i
U by EPA.
Araro»dMlnviatlg
-------
                                                            ROM Otcpoe*/ Ptt Supfftund SK»
                                MATRIX  DESCRIPTIOT
Type of Matrix Proces»ed Through the
Treatment System: Contaminated soil
excavated from the disposal pit both above
and below the saturated zone
Primary Contaminant Groups:  PCBs, volatile
organic compounds (VOCs) including TCE,
benzene, and vinyl chloride
     PCBs at were detected at
     concentrations up to 440,000 mg/kg
     The average PCB concentration was
     500 mg/kg.
The matrix characteristics that most significantly affected cost or performance at this site and their
measured values are presented in Table 2
Sol Density
Heat content
Ash
Chlorine Content by Wright
IBgfcc
290Btu/t>
86%
038%


TREATMENT SYSTEM DESCRIPTION •
Rotary kiln incineration system, including
•   Waste feed handling system
•   Rotary kiln incinerator
•   Secondary combustion chamber
Air Pollution Control System, including
•    Cyclone separator
•    Baghouse
•    Quench towers
•    Wet scrubbing system
   The soil at the Rose Site was excavated
   and transported to the crusher/shredder.
   The crusher/shredder was used to reduce
   the particle size of the soil feed to less than
   075 Inches. The crushed soil was
   transported to the soil blending building
   where it was blended before Incineration to
   achieve a homogenized incinerator feed
   The soil blending building was equipped
   with a vapor-phase carbon filtration system
   designed to reduce possible PCB or VOC
   emissions.
•   The soil feed entered the kiln at the
    flame end and traveled through the kiln
    co-current with the combustion gases
    Ash and exhaust gases were discharged
    from the kiln.

•   Kiln ash was quenched in a water bath
    and discharged to a storage area. The
    solids in the ash quench bath were
    allowed to settle and were continuously
    removed
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* and Emergency Response
Technology Innovation Office
                                          191

-------
                    TREATT
       (CONT
   The co-current rotary kiln was 110 feet long
   with an internal diameter of approximately 8
   feet. The kiln consisted of three refractory-
   lined cylindrical sections bolted together at
   flanged connections to function as one unit
   The kiln was designed for an optimal
   throughput of approximately 50 tons of
   contaminated soil per hour

   The kiln was fired with oxygen, fuel oil, and
   excess air  The kiln-drive system employed
   a 200-hp moto'.

   The kiln exhaust gases were directed to a
   cyclone separator for j.noval of larger
   particulates   Exhaust gases entered the
   cyclone sep- T"  rtangentially allowing
   larger parho.es to fall out  Particles
   separated from the exhaust gas fell to the
   bottom of the cyclone and were transported
   to the ash quench bath.

   The exhaust gas then entered the SCO
   which provided further destruction of
   remaining contaminants. The SCO was 52
   feet long and had an internal diameter of 11
   feet It was  lined with refractory brick and is
   fired with oxygen, fuel oil, and excess air

   Exhaust gas from the SCO was cooled in a
   quench tower from approximately 2,000 °F
   to approximately 425 °F  Quench nozzles
   in the tower  spray atomized recycled water
   into the gas  stream
The quenched exhaust gas was then
drawn into a baghouse  The baghouse
consisted of 1,020 woven fiberglass
bags. Each bag had a 6-inch diameter
and length of 10 feet for a surface area
of 16 square feet per bag. The total
filter area of the baghouse was
approximately 16,300 square feet  The
dust removed in the baghouse was
discharged to the ash quench bath
were then quenched in a second quench
tower similar to the one previously
described

The filtered and quenched exhaust
gases were drawn through a packed-
tower-design wet scrubber  Scrubbing
was achieved by spraying caustic
solution over the packed bed as the
exhaust gas flowed up through the bed
Scrubber wastewater was continuously
recycled, with a bleed stream
discharged to the ash quench bath

Gases were forced out of the scrubber
and into the exhaust stack which was
mounted on top of the scrubber The
stack released gas to the atmosphere at
approximately 200 °F  The internal
diameter of the stack was 4.5 feet and
the height above the ground was 66
feet

The solids in the quench bath included
all of the residuals from the air pollution
control units as well as the ash from the
incinerated soil These solids were
sampled and analyzed using the TCLP
and eventually returned to the
excavated areas on site
U S. ENVIRONMENTAL PROTECTION AGENCY
Offlcn of Solid Watt* and Emargancy Rwponw
Technology Innovation Offlc*
                                           192

-------
                        TREATMENT SYSTEM PERFORMANCE
        i Goate/Standardi
    The cleanup goals and standards were
    specif led in the ROD  The ORE was set
    based on TSCA regulations 40 CFR part
    761 subpart D [1]

    The soil cleanup level was 13 mg/kg for
    PCBs. This corresponds to a 1 x 10 *
    excess lifetime cancer risk level for the
    average case
The required ORE was 99.9999% for
PCBs

The maximum concentration of PCBs in
the residual ash was set at 2 mg/kg
    A tnal bum conducted at the Rose site was
    designed to operate the incineration system
    at conditions that would reflect worst-case
    destruction and removal of all constituents
    of concern

    PCBs were determined to be present in the
    soil at sufficient concentrations such that
    spiking with PCBs or principle organic
    hazardous constituents (POHCs) was not
    necessary
The AWFCOs limits dunng the
operation of the incinerator are shown in
Table 4 Information about the
frequency of AWFCOs was not
available The values of various
operating parameters as measured
during the tnal bum are shown in Table
5, information on actual values of these
parameters dunng operation was not
available

The average concentration of PCBs in
the residual ash was 0.0618 mg/kg.
                                                                            9999987
 Maxknum pressure Win at entry
 Mbiimum afterburner gas am temperature, Instantaneous
          1,915'F
Minimum afterburner residence time, Instantaneous
Minimum pH at scrubber sump
Minimum flow scrubber redrculation flne
Maximum CO (7% O,)
Minimum O, (dry volume)
Minimum combustion efficiency
Maximum temperature quench f 1 gas ndt
Maximum temperature scrubber entry
2 seconds
5
450 gpm
lOOppmv
3%
999%
500'F
300-F
•Recommended limits from Trial Bum Report
U S ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          193

-------
                            Tables
SCO Exit OM Temperature
Sol FMd Rate
PCS Feed Rate
Nkt Fuel O* Feed Rate
Ken Pressure
Quench ffl E* Temperature
SCC Residence Tbno
Scrubber Entry Temperature
Scrubber RedrcufaHon Flow
ScrabberpH
Slack Gas Carbon MonoxfcJe (60-Mnuto RoHng
Average)
Sleek Gw Oxygen (Diy Baste)
Secondary Draft
Combustion Efficiency
2,100 «F
51.8 tow/hour
740 Mir
1,734 fc/hr
-OSIncheewc
394 »F
4J seconds
206»F
575.8 gpm
7.5 8 U
9.9ppmv
90vd%
•OTIkicheewc
99.991
we -Watercolumn
«.u > Standard pH units
                          Tables  TCLP Comparison for Residual
1,4-Dichlorabarasm
24Mhylphenol (o-cnwoO
nvcrasol^i-cnaol



NHrooenzene
• j^^jAlfimfA*. rt^relar*^
HWKnniDOUtBnMIW
2,4.6-Trtchtoropnenol
2,4,5-Titehlorophenol
2,4-DWtrotoluene
hlnmtun
i lawcnUHwenune

enUKnioropnanoi
Pyridrw
7JS
2000
2000
30
20
0.5
20
4000
013
013
1000
60
0010
0010
0021
0010
0010
0010
0010
0010
0.010
0010
0.021
0010
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offlc* of Solid Wtet» and Emwgwtoy RNponaa
Technology Innovation Offlct
                                         194

-------
                                                             AM0 JXqtmM/ Pit Superfund SH»
                    TREATMENT SYSTEM PERFORMANCE (CONT.)
 Cadmium
                           Table 6 TCLP Comparison for Residual
                                                                      <00066
 Chromium
                                          SO
00137
                                           50
                                                                        0124
 Mereuiy
                                                                      <00070
 Selenium
                                          10
<00219
 Slyer
                                           50
                                                                       <00133
 Vinyl Chloride
                                          0.2
<0011
 1.1-Dfchtoroelnane
                                          07
                                                                      <0011
 Chloroform
                                          60
<0011
 1,2'Dichloroethan0
                                          05
                                                                      <0011
 2-Butamne (MEK)
                                         2000
                                                                      <0011
 CarfxmTeCracMoride
                                          05
                                                                      <0011
TricNoroethene
                                           OS
                                                                       <0011
 Benzene
                                          05
<0011
 Tabachtoroemene
                                          07
<0011
 Chtorabanzene
                                         1000
<0011
 gamma-BHC (Undana)
                                           04
 Endrfn
                                           002
                                                                      <0005
                                           100
 Toxaphene
                                          05
 Heptachtor
                                         0008
<0003
 1 Jnr»*f>nhlr>r
 riopfBcmor
                                         0008
<0003
 Chtordane
                                           003
                                                                      <001
U 3. ENVIRONMENTAL PROTECTION AGENCY
Offlca of Solid Waste and Emargency Response
Technology Innovation Office
                                           195

-------
                                                         AM* fftpoM/ PH Supvfund SH»
                  TREATMENT SYSTE
   According to site personnel the QA/QC
   program used throughout the remedial
   action met all EPA requirements  All
   monitoring was performed using EPA-
   approved methods, and the vendor did not
   note any exceptions to the QA/QC
   protocols [3]
                            TREATMENT SYSTEM Co<
   According to site personnel the
   responsible party contracted with Clean
   Berkshire, Inc (CBI) To provide
   design/remedial services at the site CBI
   used several subcontractors to implement
   specific aspects of the operation. [3]
•  Information on the costs of on-site
   incineration was not available
                      OBSERVATIONS AND LESSONS LEARNED
   The incinerator was constructed during the
   winter of 1992  Heavy snowfalls and low
   temperatures hampered the progress of
   workers
Cold weather also affected incinerator
startup, which occurred in January
1994  The extreme temperatures
caused various problems with water
used for cooling  In addition, valves
cracked, solenoids remained closed or
open, and air lines froze
US ENVIRONMENTAL PROTECTION AGENCY
Offtet of Solid Wwte and Emergency Rtcponse
Technology Innovation Office
                                         196

-------
                                                           Rote Disport Wf Suptrfumt Sft»
                  OBSERVATIONS AND LESSONS LEARNED (CoNT.)
Public Involvement

•   Citizens expressed concern that the
    incineration and excavation process would
    create excessive noise  EPA worked with
    local officials to minimize the adverse
    impacts of the site remediation activities [1]

•   Many public meetings were held, and EPA
    and state personnel met individually with
    local officials and residents to discuss
    specif ic concerns Neighborhood residents
    formed a group that worked with EPA to
    address public concerns
    The RP setup a neighborhood network
    that used volunteer neighbors to
    periodically distribute fact sheets
    regarding the site incineration project
                                     REFERENCES
1. Superfund Record of Decision. Rose
   Disposal Pit Site, Lanesborough,
   Massachusetts, September 23,1988

2  Memorandum - Explanation of Significant
   Differences. Rose Disposal Pit Site,
   Lanesborough, Massachusetts, November
   21,1989.
3  Trial Bum Report for the Clean
   Berkshires. Inc. High Temperature
   Incinerator (HTI) System. Rose Disposal
   Pit Superf und Site, Lanesborough,
   Massachusetts, December, 1993

4  Remedial Action Completion Report
   F T. Rose Suoerfund Site, September
   1994
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* and Emergency Response
Technology Innovation Office
                                         197

-------
I

-------
     On-Site Incineration at the
Rose Township Dump Superfund Site
          Holly, Michigan
               199

-------
      Incineration at the Rose Township Dump Superfund Site
                               Holly, Michigan
Site Name:
Rose Township Dump
Superfund Site
Location:
Holly. Michigan
Contaminants:
PCBs, metals, and volatile end
semivolatfle organic
compounds

• Most common contaminants
  (and maximum
  concentrations) were toluene
  (4,700 mg/kg), ethylbenzene
  (430 mg/kg), chlorobenzene
  (570 mg/kg), xylene (1,400
  mg/kg), naphthalene (31
  mg/kg), pentachlorophenol
  (32 mg/kg), acetone (76
  mg/kg), and total phthalates
  (91 mg/kg)
Period off Operation:
September 1992 - October
1993
Cleanup Type:
Remedial Action
Vendor:
OHM Remediation Services
Corp.
16406 U.S Route 224 East
Findlay, OH 45840
SIC Code:
N/A
Technology:
On-Srte Infrared Incineration
• Excavated material screened
  and blended with fuel oil pnor
  to incineration
• PCBs and VOCs volatilized
  and partially destroyed in
  primary combustion chamber
• Kiln ash quenched by water-
  cooled screw
• Exhaust gas from kiln
  directed to air pollution
  control system, consisting of
  secondary combustion
  chamber (SCC)
• Wastewater treated on-site
  and discharged under
  NPDES permit
Cleanup Authority:
CERCLA and State:
Michigan
• ROD signed 9/30787
• EPA-lead
Point off Contact:
Kevin Adler
US EPA Region V
77 West Jackson
Boulevard
Chicago, IL
Phone  312-886-7078

State Contact:
Brady Boyce
Michigan Department of
Environmental Quality
301 S Capitol Street
Lansing, Ml 48933
Phone  517-373-4824
                                       200

-------
       Incineration at the Rose Township Dump Superfund Site
                                Holly, Michigan
                                    (Continued)
Waste Source:
Waste disposal areas in
landfills and surface
impoundments — wastes
included spent solvents, paint
sludges, lead battery sludges,
waste oils
Purpose/Significance of Application:
Operating in writer led to weather-related difficulties resulting
in suspension of the operation until spring
Type/Quantity of Media
Treated:
Soil
• 34,000 tons of surface and
  subsurface soil	
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (DRE) of 99 9999% for principal organic hazardous
  materials as required by Resource Conservation and Recovery Act (RCRA) regulations in 40
  CFR part 264, subpart O, DRE of 99 9999% for PCBs as required by Toxic Substances Control
  Act (TSCA) regulations in 40 CFR part 761              	
Results:
• EPA determined that demonstration of a 99.9999% DRE for PCBs was not necessary during the
  tnal bum because (1) substantial hazards were associated with transporting and stonng
  concentrated PCB oils, and (2) the unit had demonstrated the ability to adequately destroy
  PCBs in order to obtain its TSCA permit	
Description:
From 1966 to 1968 approximately 5,000 drums containing spent solvents, paint sludges, lead
battery sludges, and waste oils were buned in a 12-acre area at the Rose Township Dump site
Bulk wastes were also discharged to the surface or into shallow lagoons or pits in the area. On
September 30,1987, EPA signed a Record of Decision (ROD) specifying on-site incineration as
the selected remedy for contaminated soil at the site A consent decree was signed by 12
potentially responsible parties (PRPs) and EPA in 1988 to remediate the site

The incinerator used to process soils at the site was the OHM Mobile Infrared Thermal
Destruction Unit (TDU)  The PCBs and VOCs were volatilized and partially destroyed in the
primary combustion chamber Off-gases from the preliminary combustion chamber were routed
to a secondary combustion chamber (SCC) for further destruction of any remaining VOCs and
PCBs Kiln ash was quenched by a water-cooled screw  During the on-srte incineration remedial
action, 34,000 tons of contaminated soil were incinerated Treatment performance and emissions
data collected during this application indicated that all performance standards and emissions
requirements were achieved

The total cost for remediation using the incineration system was approximately $12 million.
                                        201

-------
                                                        Ro*» Township Dump Supvfund Stt»
This report presents cost and performance data
for the application of on-srte incineration at the
Rose Township Dump Superf und Site (Rose
Township Site) in Holly, Michigan  An infrared
incinerator was operated from September 1992
through October 1993 as part of a remedial
action. The contaminants of concern at the
Rose Township site were PCBs. metals, and
volatile and semivolatile organic compounds

From 1966 to 1968 approximately 5,000 drums
containing spent solvents, paint sludges, lead
battery sludges, and waste oils were buried in a
12-acre area at the Rose Township Dump site
Bulk wastes were also discharged to the surface
or into shallow lagoons or pits in the area

Dunngthe Remedial Investigation (Rl),  PCBs
were detected in the soil at concentrations up to
980 mg/kg  The majority of PCB contamination
was contained in an area approximately 200
feet by 750 feet Excavation of material to
depths of 22 feet was required to meet the
cleanup goals  Lead was detected at
concentrations up to 3,200 mg/kg  A variety of
volatile and semivolatile organic compounds
also  were detected in soils during the Rl The
most common contaminants (and maximum
concentrations) were toluene (4,700 mg/kg),
ethyibenzene (430 mg/kg), chlorobenzene (570
mg/kg), xyiene (1,400 mg/kg), naphthalene (31
mg/kg), pentachlorophenol (32 mg/kg), acetone
(76 mg/kg), and total phthalates (91 mg/kg)

On September 30,1987, EPA signed a Record
of Decision (ROD) specifying on-srte
incineration as the selected remedy for
contaminated soil at the Rose Township Site
Performance standards for the incineration
process included a destruction and removal
efficiency (ORE) of 99 9999% for PCBs A
consent decree was signed by 12 potentially
responsible parties (PRPs) and EPA in 1988 to
remediate the site

Remedial actions were managed by Perini
Environmental, a remedial contractor hired by
the PRPs, and were performed under the
oversight of EPA Region 5.
Contaminated soil was excavated using
backhoes and longarms. Prior to
incineration, excavated material was
screened to less than one inch in diameter,
and blended with fuel oil to achieve the
desired BTU value. Wet soil was dried in a
drying building by heaters and blowers prior
to screening  Oversize rocks, tree stumps,
and personal protective equipment were
shredded and incinerated Intact drums
unearthed dunng the excavation of soil were
disposed of off the site.

The incinerator used to process soils at the
Rose Township site was the OHM Mobile
Infrared Thermal Destruction Unit (TDU)
Off-gases *rom the preliminary combustion
chamber were routed to a secondary
combustion chamber (SCC) for further
destruction of any remaining VOCs and
PCBs.  Kiln ash was quenched by a
water-cooled screw

Exhaust gas from the kiln was directed to an
air pollution control system (APCS) The
APCS consisted of a water spray to reduce
the temperature of the SCC exit gas, a low-
energy verrtun scrubber and a packed bed
adsorber to control particulates and acid
gas, and a high-energy ventun scrubber and
mist eliminator to control mete's emissions
and remove additional particulates  All of
the wastewater generated by the system
was treated on site and discharged under a
fvpDES permit

During the on-site incineration remedial
action, 34,000 tons of contaminated soil
were incinerated.  Treatment performance
and emissions data collected during this
application indicated that all performance
standards and emissions requirements were
achieved

The total cost for remediation using the
incineration system was approximately $12
million.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offfe* of Solid Wait* and Emwgmcy Rwponie
Technology Innovation Offte*
                                          202

-------
                                                             Townthlp Dump Supfrtuntl Site
                                  SITE INFORMATION
 Identifying Information

 Rose Township Dump Superfund Site
 Holly, Michigan

 CERCLISf: MID980499842

 ROD Date: September 30,1987
Background

Historical Activity that Generated
Contamination at the Site:  Dumping of spent
solvents, paint sludges, lead battery sludges,
and waste oils. No manufacturing or other
industrial activity was conducted at this site

Corresponding SIC Code: Not applicable

Waste Management Practice That
Contributed to Contamination: Waste
disposal in landfills and surface impoundments

Site History:

•  The Rose Township site occupies a 110-
   acre parcel of land A portion of the site
   was used for farming from the 1950s to the
   1960s  From 1966 to 1968 approximately
   5,000 drums containing spent solvents,
   paint sludges, lead battery sludges, and
   waste oils were buried in a 12-acre portion
   of the site  An undetermined amount of
   bulk wastes were also discharged to the
   surface or into shallow lagoons or pits in the
   area

•  The results of investigations at the site
   indicate that surface and subsurface soils
   and groundwater at the site were
   contaminated with PCBs, metals, and
   volatile and semivolatile organic
   compounds

•  In April 1979, the Michigan Department of
   Natural Resources (MDNR) surveyed the
   site and identified approximately 1,500
   drums of unknown contaminants
Treatment Application

Type of action: Remedial (on-site infrared
incineration)

Period of operation: September 1992 -
October 1993

Quantity of material treated during
application: 34,000 tons of contaminated
soil
•   A search warrant obtained in June of
    1979 allowed the drums to be sampled
    by the MDNR to identify their contents

•   Based on the results of 1979 drum
    sampling, a toxic substances
    emergency was declared by the
    Michigan Toxic Substances Control
    Commission  A removal action,
    completed in July 1980 resulted in the
    removal of over 5,000 drums from the
    site for off-site disposal

•   A Remedial Investigation [Rl] and a
    Feasibility Study [FS] were initiated at
    the Rose Township Site in February of
    1984 and were completed in June of
    1987

•   On September 30,1987, EPA signed a
    Record of Decision (ROD) specifying
    on-site incineration as the selected
    remedy for the contaminated soil at the
    Rose Township Site  An amendment to
    the ROD was issued in 1989

•   From September 1992 until October
    1993, an infrared incinerator operated at
    the Rose Township Site as part of a
    remedial action During the remedial
    action, 34,000 tons of contaminated soil
    were incinerated
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          203

-------
                                                      flow Township Dump Supfrfund SA»
                            SITE INFORMATION (CONT.)
Regulatory Context:
   The Rose Township Site was placed on
   the National Priorities List (NPL) in 1982

   On September 30,1987, EPA signed a
   Record of Decision (ROD) specifying the
   site cleanup requirements

   A consent decree was signed by 12
   Potentially responsible parties (PRPs) and
   EPA in 1988 to remediate the site.

   The DREs were set in accordance with
   Resource Conservation and Recovery Act
   (RCRA) incinerator regulations in 40 CFR
   part 264, subpart O and Toxic Substances
   Control Act (TSCA) regulations in 40 CFR
   part 761
•    The selected remedy was conducted
     under the provisions of the
     Comprehensive Environmental
     Response, Compensation, and Liability
     Act of 1980 (CERCLA), the Superfund
     Amendments and Reauthorization Act
     of 1986 (SARA) and the National
     Contingency Plan (NCP) in   40 CFR
     part 300

Remedy Selection: EPA determined that
on-srte incineration would be protective of
human health and the environment, and cost
effective. EPA further determined that on-site
incineration satisfied the CERCLA
requirement that the remedy reduce toxicity,
mobility, or volume of the waste
                                   Table 1. Timeline
••^•••^•••••^••••••^•iBaamH^^BB^
1966-1968
Apnl 1979
June 1979
July 1980
1982
February 1984-September 1987
CnntamKAr 1 QfiT
oepieniDer isw/
September 1992
September 1992
October 1993
Wastes are disposed of at Rose Township site
Michinan Danartmant of Natural RaftntiiKas fMDNRl
surveys site
Drums sampled by MDNR
5,000 drums removed from site by MDNR
Site placed on NPL
MDNR perfonns Remedial Investigation and Feasibility
Study
Record of Decision signed
Trial bum conducted
Excavation and Incineration operations begin
Incineration operations completed
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         204

-------
                                                       /to** Township Dump Superfund SA»
Site information

•   The Rose Township site occupies 110-acres
    on Demode Road in rural Rose Township,
    Michigan Located approximately 1 mile
    west of the town of Rose Center, the site
    comprises an upland area almost
    completely surrounded by wetlands with an
    abundance of wildlife on the site The
    southern portion of the site is heavily
    wooded with hardwoods  The middle
    portion, a rolling meadow, is bordered by a
    marsh to the west and northeast and
    Demode road to the north
    There are two groundwater contaminant
    plumes on-srte  In the northern part of
    the site is a plume containing vinyl
    chloride, and in the southwest is a
    plume containing vinyl chloride, xylene,
    toluene, and benzene. The northern
    plume threatens to contaminate nearby
    domestic drinking-water wells, one of
    which is located within 1,600 feet of the
    site
Site Lodistics/Contacts
Site Management: EPA Region 5-lead

Oversight: Michigan Department of Natural
Resources
Remedial Project Manager:
Kevin Adler
US EPA Region 5
77 West Jackson Boulevard
Chicago, IL
Phone 312-886-7078
State Contact:
Brady Boyce
Michigan Department of Environmental
Quality
301 S Capitol Street
Lansing, Ml 48933
Phone 517-373-4824

Treatment System Vendor
Greg McCartney
OHM Remediation Services Corp
16406U.S Route 224 East
Findlay, OH 45840
                               MATRIX DESCRIPTION
Matrix notification
Type of Matrix Processed Through the
Treatment System: Soil, rocks, and tree
stumps

Contaminant Characterization
Primary Contaminant Groups: RGBs, metals,
and volatile and semivolatile organic
compounds.

•   Dunng the Rl, contaminants detected in the
    soil included PCBs at concentrations up to
    980mg/kg. Lead was detected at
    concentrations up to 3,200 mg/kg. A variety
    of other volatile and semivolatile organic
    compounds also were detected In soils
   during the Rl  The most common
   contaminants and their respective
   maximum concentrations were toluene
   (4,700 mg/kg), ethylbenzene (430
   mg/kg), chlorobenzene (570 mg/kg),
   xylene (1,400 mg/kg), naphthalene (31
   mg/kg), pentachlorophenol (32 mg/kg),
   acetone (76 mg/kg), and total phthalates
   (91 mg/kg)
U 8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         205

-------
                                                         Ro*»Town»hlpDumpSiip»rfundSH»
                            MATRIX'DESCRIPTION (CONT.)
The major matrix characteristics that most significantly affected cost or performance for this
technology and their measured values are presented in Table 2
                              Table 2  Matrix Characteristics
1    Th» value given Is the range of values found m sols incinerated during the trial bum Information on matrix characteristics for
    the fuR-scde hdnowton is not currently available

1    SMEW W-Standard Methods for the Examination of Water and Waste, ITtfi EelBon. 1989

3    ASTM-Amertcan Society for Testing and Materials, 1985 edHton
                         TREATMENT SYSTEM DESCRIPTION
Prinvv Tntntrnent Tectinotociv

Incineration system including OHM Mobile
Infrared Thermal Destruction Unit, including

•   Waste feed handling system
•   Infrared incinerator
•   Secondary combustion chamber
Pretreatment (solids).
•   Screening
•   Drying
•   Blending
•   Crushing/shredding (rocks/debns)

Post Treatment (air)
•   Quench
•   Low-energy venturi scrubber
•   Packed-column chemical scrubber
•   High-energy ventun scrubber
                                                  Post Treatment (water).
                                                     Clarification
                                                     Sand filtration
                                                     Bag filtration
                                                     Activated carbon adsorption
                                                     Ion exchange
U.C ENVIRONMENTAL PROTECTION AGENCY
Offlc* of Solid WMte and Emergency RMDOHM
Technology Innovation Office
                                           206

-------
                                                       J?OM Township Dump Suptrfund SHe
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
Sv«ti
i DMcrlotion and
    Soil was excavated from the Rose Township
    Site using backhoes and longarms.
    Excavated materials were screened to
    remove debris greater than 1 inch in
    diameter using a portable three-tiered
    screen  Wet soils were dned before
    screening in a drying building to prevent
    clogging of the screen

    Drying was conducted on the site in a
    building equipped with heaters and blowers
    Excavated material that required drying was
    placed in the building  and periodically mixed
    with a f rontend loader or tractor equipped
    with a rototiller  Soil was also screened in
    the building following  drying

    Screened soils were blended with fuel oil or
    diesel fuel to raise its  heat content to
    approximately 500 BTU/lb

    Debns such as rocks and tree stumps
    screened out of the soil were stored
    separately for further processing  Rocks
    were crushed using a  mobile crusher and
    tree stumps were shredded in a tub gnnder
    Both the rocks and tree stumps were
    reduced to less than one inch diameter and
    incinerated along with shredded personal
    protective equipment

    Intact drums unearthed dunng the
    excavation were sampled and analyzed to
    determine their contents and disposed of off
    the site at approved facilities

    Material to be incinerated was loaded into a
    feed hopper, from which it was discharged
    onto a weigh belt feeder The material then
    dropped from the weigh belt feeder to an
    enclosed conveyor belt, where it was
    leveled as it passed under a screw The
    material then dropped from the conveyor
    belt to a high temperature metal alloy belt
    that conveyed it through the primary
    combustion chamber

    in the primary combustion chamber material
    was heated with Infrared radiant heat
    generated by silicon carbide heating
    elements  Ash and off-gases were then
                                             discharged from the primary combustion
                                             chamber

                                             Ash from the primary chamber dropped
                                             on to an enclosed, water-cooled screw
                                             conveyor. Ash discharged from the
                                             screw was sprayed with water to
                                             suppress dust and for additional cooling
                                             Ash that contained greater than 1 mg/kg
                                             RGBs was incinerated again,
                                             aporoximately 600 tons of material was
                                             incinerated again  Ash that exceeded
                                             the extraction procedure (EP) toxicity
                                             test threshold of 5 mg/L for lead or
                                             arsenic was stabilized. All ash that met
                                             the treatment criteria, including ash that
                                             was incinerated or stabilized, was
                                             disposed of on site

                                             The primary combustion chamber
                                             residence time was required to be
                                             greater than 15 minutes for incineration
                                             at the Rose Township Site  The
                                             incinerator feed rate was limited to less
                                             than 13,800 Ib/hr

                                             The maximum heat input to the primary
                                             combustion chamber from the
                                             silicon-carbide heating elements was
                                             3,412,000 BTU/hr. The primary
                                             combustion chamber was capable of
                                             operating at temperatures up to
                                             1,800°F, and was required to be
                                             operated at the site at temperatures
                                             greater than  1,400° F  Within the
                                             primary combustion chamber the
                                             material was stirred by cake-breakers
                                             powered by 1/2 horsepower (hp) motors

                                             Pnmary combustion chamber gas
                                             flowed counter-current to the material
                                             being incinerated  Combustion air was
                                             provided by an forced draft blower
                                             manufactured by Buffalo Forge
                                             Company, Model No. 270, type BL
U.8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                         207

-------
                                                        ROM Township Dump Suptrfund Sit*
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
   Off-gas from the primary combustion
   chamber entered the SCO for further
   destruction. The SCO was 88 feet, 10
   inches long and had an internal height of 8
   feet, internal width of 7 feet, and internal
   volume of 3,770 cubic feet. The SCO was
   fired by 4 Multifile® natural gas burners,
   Model No  31534. manufactured by Maxon
   Corporation, Munde, Indiana. Integral to
   the burner system was a 20 hp forced air
   blower capable of providing 32 inches of
   water column pressure. The burner system
   had a maximum firing capacity of
   12,020,000 BTU.

   The SCO was designed to operate at
   temperatures up to 2,400°F, and was
   required to operate at greater than 1,950°F
   at the Rose Township Site

   Excess combustion air was provided in the
   SCO by a blower manufactured by the
   Chicago Blower Corporation, Model 24-1/2
   SQAD, with a maximum capacity of 14,000
   acfm.

   Gas exiting the SCC was quenched with a
   water spray that reduced its temperature to
   less than 250°F

   The off-gas from the quench was then
   routed to a low-energy venturi scrubber to
   remove particulates Water was injected
   into the ventun scrubber at a rate of 140
   gallons per minute (gpm), and the pH In the
   venturi scrubber was controlled by the
   addition of a 10% caustic solution  The off-
   gas was then sent to a packed column
   chemical scrubber

   The packed column chemical scrubber
   removed acid gas by passing the gas
   through 260 cubic feet of 3.5-inch Jeager
   Tripack polyethylene packing. Water at a
   flow rate of greater than 150 gpm was
   passed through an overhead distribution
   plate onto the packing to scrub the gas.
   The pH of the packed column was
controlled by the addition of a 10%
caustic solution

The off-gas then was sent to a
high-energy venturi scrubber to remove
particulates and heavy metals.  Water
was injected into the scrubber at a rate
of 140 gpm, a pressure drop of 55 to 65
inches of water column was maintained
across the scrubber

After passing through the high-energy
venturi scrubber, the gas was passed
through 4 banks of high efficiency
Munter Chevron mist eliminators, and
then to an exhaust stack with an inside
diameter of 32 inches and a height of 37
feet. Two induced draft fans maintained
a negative pressure in the system One
fan was a Robinson Industries Model
No. 70x3.5 RBD-SWSI, which could
draw 30,000 acfm at 190°F, induced a
pressure of 45 inches water column,
rotated at a speed of 1,780 rpm, and
was powered by a 200 hp motor.  The
second fan was a Robinson Industries
Model No 57x3.5 RBD-SWSI, which
could draw 30,000 acfm at 190°F,
induced a pressure of 35 inches water
column, rotated at a speed of 1,780
rpm, and was powered by a 200 hp
motor

Wastewater generated by the scrubbers
and mist eliminators was treated on the
site with a system consisting of
clarification, sand filtration, bag
filtration, activated carbon adsorption,
and ion exchange After treatment the
water was discharged under a NPDES
permit

The health and safety plan developed
for the Rose Township Site required
level C personal protective equipment
in the soil crying building

Figure 1 shows a simple block diagram
of the incineration system.
U.8. ENVfRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Retporme
Technology Innovation Office
                                          208

-------
                                                      Rou»Ta*mmhipDumpSuj»rfuntlSlt»
                   TREATMENT SYSTEM DESCRIPTION (CONT.)
                                 SECONDARY
                                 COMBUSTION
                                 CHAMBER
 PRIMAHY
 COMBUSTION
 AIR BLOWER
 oA«h Storage*
                                                                Water
                                                                                   I
 Figure 1. Block Diagram of Incineration System used at the Rose Township Dump Superfund Site
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wctta and Emergency Response
Technology Innovation Office
                                        209

-------
                                                       AOM TowraNp Dump Suptrfund Sft»
                       TREATMENT SYSTEM PERFORMANCE
    The cleanup goals and standards were
    specif led in the ROD  The ORE and ash
    management standards for metals were
    based on the regulations under Resource
    Conservation and Recovery Act (RCRA) (40
    CFR 264.343 for the OREs and 40 CFR
    261 24 for ash residuals)  The ORE
    standards for PCBs were based on the
    Toxic Substances Control Act (TSCA)(40
    CFR part 761)

    The ROD established target cleanup levels
    of 10,70,14. and 0.08 mg/kg for PCBs,
    lead, arsenic, and total VOCs, respectively
    The ROD specified on-site incineration of all
    soil contaminated with either organics or
    PCBs However, a consent decree signed
    in 1988 by 12 PRPs required incineration of
    PCB-contaminated soil and an alternate
    remediation for soil contaminated with
    organics only. Therefore, a soil target
    cleanup level was not established for
    semivolatile organic compounds in
    incinerated soil
The DRE requirements for the
incinerator were set at 99 9999% for
PCBs. The metals emissions
requirements were based on EPA
guidance and Michigan Act 348

The incinerator ash was required to
contain less than 1 mg/kg PCBs prior to
disposal on-site
   A trial bum, conducted on September 11
   and 12,1992, was designed to operate the
   incineration system at conditions that would
   reflect worst-case destruction and removal
   of all constituents of concern.  Samples of
   all influent and effluent streams during
   operation at these conditions were collected
   during the trial bum  These samples were
   then analyzed to determine whether all of
   the incinerator operating standards were
   met Operating limits were then set based
   on the worst-case values that were
   established during the trial bum

   Because of the detection limit used for
   PCBs, and the low concentrations of PCBs
   in soils at the Pose Township Site, it was
   not possible to demonstrate a 99 9999%
   DRE However, the Incineration unit
   employed at the Rose Township site had
   been issued a TSCA permit for the
   incineration of contaminated soils, based on
   a trial bum conducted In June of 1988 at
another site. EPA determined that
demonstration of a 99 9999% DRE for
PCBs was not necessary during the tnal
bum because (1) substantial hazards
were associated with transporting and
storing concentrated PCB oils, and (2)
the unit had demonstrated the ability to
adequately destroy PCBs in order to
obtain its TSCA permit
                                    f
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid W«itt and Emergency Response
Technology Innovation Office
                                         210

-------
                                                             Township Dump Suporfund SK»
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
 •   Dunng the tnal bum, the incinerator
    demonstrated its ability to meet the
    emission standards specified in its TSCA
    permit for the incineration of
    PCB-contaminated soils, and the Michigan
    Act 348 metals and PCB emissions
    standards

 •   Soil excavated from areas on site that was
    known to be contaminated with RGBs, lead,
    and arsenic was incinerated dunng the tnal
    bum  Before incineration the soil was
    blended with fuel oil or diesel fuel to
    achieve a minimum heat content of 500
    BTU/lb

 •   Dunng the tnal bum conducted in June 1988
    as part of the procurement of a TSCA PCB
    incineration permit for the incinerator, a
    99 9999 % ORE was demonstrated on
    waste feed containing 5,600 mg/kg of PCBs
    This information was deemed sufficient by
    EPA to demonstrate compliance at the site.
    The ORE for PCBs was calculated by the
    PRP, and this information is shown in Table
    3

•   The incineration system included continuous
    emissions monitors (CEMs) for carbon
    monoxide, carbon dioxide, oxygen, and total
    hydrocarbons  The stack operating data for
    the CEMs dunng the tnal bum were used to
    set ranges for normal operating conditions
    The CEMs were employed during the
    normal operations of the incinerator to
    ensure that operating conditions remained
    within the bounds established dunng the tnal
    bum.

•   The incineration system also included an
    automatic waste feed cutoff (AWFCO)
    system to suspend operations if the
    operating conditions were not within the
    proper ranges set by the tnal bum  The
    AWFCO limits used dunng the remedial
    action are shown in Table 4
    Information about the frequency of
    AWFCOs was not available

•   Tnal bum and typical operating
    parameters are shown in Table 5.

•   The incinerator operated at the Rose
    Township Site operated predominantly
    within the operating limits established
    dunng the trial bum

•   The residual ash was sampled and
    analyzed using the EP toxicity test for
    lead and arsenic to determine whether
    these parameters met the requirements
    specified in the ROD for on-srte disposal
    as backfill  The ROD required ash that
    failed to meet the requirements for
    teachable metals to be stabilized before
    land disposal No ash required
    stabilization before land disposal

•   Initially some of the incinerated soil at
    the site did not meet the cleanup goal of
    less than 1  mg/kg PCBs This was
    attributed to the fact that the size of the
    material being fed to the incinerator
    was too large. As a result,
    approximately 600 tons of material
    required reincmeration  All subsequent
    feed to the incinerator was screened to
    less than 2 inches In diameter No
    material r< ,uired reincineratton after the
    institution of such screening. The DRE
    was met for PCBs and metals
                  Tables  Average Destruction and Removal Efficiencies from
                             Trial Bum Compliance Testing I
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          211

-------
                  TREATMENT SYSTEF.
3MANCE (CONT.)
                       Tabfe* Automatic Waste Feed Cutoffs
Secondary Chamber Temperature
Secondary Chamber Excess Oxygen Level

Stack Cannn MowxHe Concentration
PifenaiyBenFalure
Primaiy Chamber Pressure
Ash Cooing Conveyor Failure
Induced Draft Blower Fahire
Stack Temperahire
Scrubber Quench Temperature


Primary Chamber Zone A2 Temperature
Primary Chamber Zone B2 Temperature
High-Energy Venturi Pressure Drop
Scrubber pH
<1950°F,>2,500eF
<3%
> 90 ppmwHh 2 rnlnute delay, >1 50 ppm Instantaneous
NA
<0 00 Inches we
Not Applicable
NotAppHeable
>250°F
>2SO"F
NotAppHeable
<1.400eF
<1,530'F
<20 Inches we
<4su
    NotAvaiabte
su.» Standard units
w.c = Water column
Primary Combusflon Chamber Zone A2
Temperature
Primary Combustion Chamber Zone 82
Temperature
Primary Combustion Chamber Pressure
Secondary Combustion Chamber
Temperature
Secondary Combustion Chamber Excess
Oxygen
Stack Carbon Monoxide
Stack Gas Flow Rate
Scrubber pH
Low-Energy Venturi Pressure Drop


Wast* Feed Rate
Primary Combustion Chamber Retention
?"• 	 	 - .
>1.400°F
>1.530"F
<00 inches we
>1,950'F
>3%
<90ppm
<6,l80dscm
>60
>6tncheewc
>45 Inches we
<13,800trVhr
>15 minutes
1,523-1.543°F
1.624- 1,651 »F
NA
2,025 -2,048°F
6125-651%
279-334 ppm
4,958- 5.411 dsom
641-687
11 42 -11 96 Inches we
52.98 -56 4 Inches we
13,092- 13.937 RVhr
NA
	
we •wanreolumn
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid WMta and Em«rgancy Response
Technology Innovation Office
                                        212

-------
                                                        ROM Township Dump Superfund Sftf
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
    Data are available for concentrations of
    contaminants in the soil before incineration
    Confirmatory soil samples were collected by
    the vendor after the remediation was
    completed
  Data are also available for
  concentrations of contaminants in the
  incinerator residue These data were
  collected penodically prior to landfillmg.
  In addition, emissions data are available
  from the incinerator compliance test
                             TREATMENT SYSTEM COST
Procurement Process

•   The PRP contracted with Penni
    Environmental to acquire and operate the
    incinerator at the Site  Perini
    Environmental used several
    subcontractors to implement specific
    aspects of the operation
The total cost for operation of the
incineration system was approximately
$12,000,000  A total of 34,000 tons of
soil, rocks, and tree stumps were
incinerated This corresponds to a total
unit cost for incineration of $350 per ton
A detailed breakdown of these costs was
not available.
                     OBSERVATIONS AND LESSONS LEARNED
   Substantially more soil required incineration
   than anticipated, which resulted in increased
   costs  Based on the results of the RI/FS,
   9,000 to 13,000 cubic yards of soil were
   estimated to require incineration  However,
   verification sampling
  during excavation indicated additional
  soil required incineration in order to
  meet cleanup goals, and 18,000 cubic
  yards of soil were ultimately incinerated
  at the Rose Township Site
   Soil screening was hindered in wet weather
   because soil formed clumps that would not
   pass through the screening equipment  A
   drying building equipped with heaters and
   blowers was constructed to dry the soil
   before screening

   The incinerator was shut down periodically
   to replace broken or damaged heating
   elements and for repairs to the conveyor
   belt Replacement of the main conveyor
   belt required a 3-day shut down at one point
   during the project  No cause of these
   failures was Identified by site personnel
  Several times during the project the
  incinerator had to be shut down to
  remove fry ash that had slagged in the
  duct between the primary and
  secondary combustion chambers and in
  the secondary combustion chamber

  Other operational problems included
  ash discharge system malfunction, loss
  of flame in the secondary combustion
  chamber, temporary loss of power, and
  weigh belt feeder malfunction
U S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                         213

-------
                OBSERVATIONS AND LESSONS
                                                       Row Township Dump Supttfund SH»
Public involvement

•  The public comment period for the RI/FS
   commenced on June 29.1987 and ended
   on August 12,1987 A public meeting
   was held on July 1,1987 to discuss the
   RI/FS and to present the proposed
   remediation plan.  During the public
   meeting, no significant opposition was
   raised against the proposed plan  The
   public was generally supportive of the
   proposed plan as they wished the source
   of the contamination to be removed
1   Emissions Verification Test Plan. OHM
    Remediation Services Corp., Findlay, Ohio,
    June 12,1992

2   EPA National Pnonties List. Rose Township
    Dump Fact Sheet. USEPA Region V,
    February. 1996
    Final Closure Report. Excavation and
               Rose Township Site. Oakland
6.
7.
    Dountv.
                Perini Environmental
   Services, Inc, Framingham,
   Massachusetts, March, 1996

4. Final Design Report. Thermal Treatment of
   PCB Laden Soils.  Pertand Environmental
   Technologies, Inc  April 1,1992.

5. Final Soil Investigation Report. Rose
   Township Site in Oakland County. Michigan
   Pertand Environmental Technologies, Inc,
   Burlington, Massachusetts, August 28,
   1992
Incineration of PCB Contaminated Soils at
the Rose Township Suoerf und!
    Superfund XV Conference and I
    Proceedings. Ungs, R.T, et al., PRC
    Environmental Management Inc, Denver
    Colorado, 1994.
      on Volatile Oroanlcs in Soils. Rose
        Site. Oakjand County. Michigan.
Perini Environmental Services, Inc.,
Framingham, Massachusetts, March, 1996
                                            8.
   Suoerfund Record of Decision. Rose
   Township Dump Demode Road
   Suoerfund Site. U.S. Environmental
   Protection Agency, September 30,
   1987.
                                            9.  Trial Bum Report. Mobile Destruction
                                                   Unit. Rose Townsh p Superfund Site.
   Hotlv. Michigan  OHM Remediation
   Services Corp., Findlay, Ohio,
   November 6,1992
                                            10  U S. EPA Fact Sheet. Update on
                                                Remedial Actior
                                                Demode Road Superfund Site. Rose
                                            11
   Township. Michigan  USEPA Region V.
   October 1989.

   Personal communication between Peter
   Shields, Eastern Research Group and
   Kevin Addler, U.S. EPA Region V. April
   22,1997
12. Shirco Infrared Incineration System
   Applications Analysis Report. US
   Environmental Protection Agency, June,
   1989

13. Personal communication between
   James Styers, Tetra Tech EM Inc. and
   Ed Hammond, Massachusetts Port
   Authority (formerly of Perini
   Environmental)  December 1,1997
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                         214

-------
    On-Site Incineration at the
Sikes Disposal Pits Superfund Site
         Crosby, Texas
               215

-------
        Incineration at the Sikes Disposal Pits Superfund Site
                                Crosby, Texas
SHeName:
Sikes Disposal Pits Superfund
Site
Location:
Crosby, Texas
Contaminants:
Organic and Phenolic
Compounds
• Naphthalene, chlorobenzene,
  creosote, toluene, xylene,
  dichloroethane, and vinyl
  chloride
• Maximum concentrations in
  mg/kg - naphthalene (58),
  chlorobenzene (2 3), toluene
  (5), dichloroethane (20), and
  vinyl chloride (1)	
Period of Operation:
February 1992 to June
1994
Cleanup Type:
Remedial action
Vendor:
Mike Gust
International Technology
Corporation
2790 Mosside Boulevard
Monroeville, PA 15146-2792
(800) 444-9586
SIC Code:
Not Applicable
Technology:
On-Site Incineration
• Soil and debris pretreated
  with shredding and mixing
  with lime
• Incineration system consisting
  of rotary kiln and two
  secondary combustion
  chambers (SCCs)
• Enclosed conveyor
  transported contaminated soil
  and debns to the unit
• Soil residence time of 45
  minutes, kiln temperature of
  1,300°F, SCC temperature of
  1,800°F
• Treated soil and debns
  (incinerator ash) discharged
  into rotary mixer, where it is
  sprayed with water  	
Cleanup Authority:
CERCLA and State Texas
• ROD Date 9/18/86
• State-lead
Point of Contact:
Earf Hendnck
Remedial Project Manager
US EPA Region 6
1445 Ross Avenue
Dallas, Texas 75202-2733
(214) 665-8519
Waste Source:
Disposal Pits - drummed and
bulk wastes     	
Purpose/Significance of
Application:
Third largest Remedial Action
Contract ever awarded to
incinerate nearly 1/2 million
tons of contaminated soil and
debris
Type/Quantity of Media Treated:
Soil and Debns
• 496,000 tons of soil and debns
• Moisture Content soil -10 -12%
• Soil Density (in situ) 1 58 -1 72 g/cm3
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (DRE) of 99 99% for principal organic constituents of
  concern as required by Resource Conservation and Recovery Act (RCRA) incinerator
  regulations. 40 CFR part 264. subpart O   	
Results:
• Emissions and trial bum data indicated that all DRE and emissions standards were met
• Analytical data of residuals Indicated that cleanup goals were met
                                        216

-------
        Incineration at the Sikes Disposal Pits Superfund Site
                                 Crosby, Texas
                                    (Continued)
Description:
Between 1961 and 1967, the Sikes Disposal Pits Superfund Site was the location of the
unpermrtted disposal of drummed and bulk wastes into unhned sand pits A remedial investigation
determined that soil at the site was contaminated with VOCs and PAHs  A Record of Decision
(ROD), signed in September 1986, specified on-site incineration as the remedial technology for
the soil and debris Site cleanup goals and DRE standards were specified for the organic
constituents of concern

Remedial Activities began in October 1990 when IT/Davy began clearing the site On-site
incineration using the IT Corporation Hybrid Thermal Treatment System* began in February 1992
and concluded in June 1994  Following demobilization and site cleanup, remedial activities
ceased in December 1994  The treatment system consisted of a rotary lain and two SCCs  An
enclosed conveyor moved the soil and debns to the kiln for treatment Ash from the incinerator
was discharged to a rotary mixer where it was quenched with water Incineration achieved the soil
cleanup goals specified in the ROD

The total cost of the Remedial Action was approximately $115,000,000 Capital costs accounted
for approximately $20,000,000 Operation and maintenance costs accounted for approximately
$95,000,000
                                       217

-------
                               ^EXECUTIVE SUMMARY
This report presents cost and performance data
for the application of on-site incineration at the
Sikes Disposal Pits Superfund site in Crosby,
Texas. A rotary kiln incinerator was operated
from February 1992 through June 1994 as part
of a remedial action Contaminants of concern
at the site were organic and phenolic
compounds including naphthalene,
chiorobenzene, creosote, toluene, xylene,
hahdes, dichloroethane, and vinyl chloride

The Sikes Disposal Pits site was used for the
disposal of drums and bulk wastes from 1961
through 1967  Dunng this period, an estimated
1,500 fifty-five gallon drums and an
undetermined amount of bulk waste was
disposed of at the site  Dunng the remedial
investigation, soil concentrations  were
measured as high as 58 mg/kg for naphthalene,
2 3 mg/kg for chlonnsnzene, 5 mg/kg for
toluene, 20 mg/kg fc. dichloroethane, and 1
mg/kg for vinyl chlonde

In June 1982, EPA signed a cooperative
agreement with the Texas Water Commission
(TWC), currently the Texas Natural Resource
Conservation Commission (TNRCC), to oversee
response actions at the site A Record of
Decision (ROD) signed in 1986 established a
destruction and removal efficiency (DRE) of
99 99% for organic contaminants

EPA and TWC conducted remedial activities
including the operation of a rotary kiln
incinerator to dispose of the contaminated soil.
The incineration system used at Sikes Disposal
Pits was comprised of a solid waste feed
system, a countercurrent, controlled-air, rotary
kiln, two secondary combustion chambers
(SCCs), two wet gas cleaning systems (GCSs);
and a treated materials handling system

In order to prepare the feedstock, soil excavated
at the site was mixed with lime if  its moisture
content was above a prescribed level, and
drums were shredded to reduce their size to  an
acceptable size for the incinerator  Prepared
material was fed to the incinerator by an
enclosed conveyor
Resulting ash from the incinerator was
removed and quenched with water while off-
gas was drawn into one of the two parallel
SCCs  The SCCs were down-fired steel
shells that provided further combustion of
contaminants in the off-gases The
incinerator and both SCC's were fueled by
natural gas

Treated gas was then drawn into the GCS,
which consisted of a quench section for
cooling, and a venturl scrubber and a two-
stage Hydro-Sonic® scrubber for removal of
parhculate matter The GCS cooled the gas
from the SCC and controlled particulate and
acid gas emissions Ash and dust collected
from the incinerator and GCS were sampled
and analyzed to determine whether they
were in compliance with on-site land
disposal requirements, at which time they
were landfilled on site

During the 28 months of operation, the
incinerator processed approximately
496,000 tons of contaminated soil and
debris and the on-site water treatment
system treated 350 million gallons of
contaminated groundwater and stormwater
Treatment performance and emissions data
collected during incinerator operation
indicated that all performance standards
and emissions requirements were achieved.

The actual total cost for remediation using
the incineration system was approximately
$115,000,000 This amount consisted of
approximately $20,000,000 in capital costs
and $95,000,000 in operating costs
U.3. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wattt and Emergency Response
Technology Innovation Office
                                           218

-------
                                                           Sttus DttpOM/ Pitt Supnrtund Site
                                  SITE ^FORMATION
Sikes Disposal Pits Superfund Site
Crosby, Texas

CERCLISf TXD980513956

ROD Date: September 18,1986
Type of action: Remedial (on-site rotary
kiln incineration)

Period of operation: February 1992 - June
1994
                                                 Quantity of
                    reated during
                                                 application: 496,000 tons of soil and
                                                 debns
Historical Activity that Generated
Contamination at the Site: Waste disposal

Corresponding SIC Code:  Not applicable

Waste Management Practice That
Contributed to Contamination:  Disposal of
drummed and bulk waste in unlmed sand pits

Site History:

•   The site was used in the 1950s as a source
    of sand for local construction projects  The
    site subsequently was used for disposal of
    drums and bulk wastes from 1961 until
    1967

•   The Slkes Disposal Pits is an 185-acre site
    bordered on the west by the San Jacinto
    River and on the north by the Jackson
    Bayou  The majority of the site is within the
    10-year flood plain and the entire site is
    within the 100-year flood plain

•   During this penod, an estimated 1,500 fifty-
    five-gallon drums were disposed of  in
    unlined sand pits  An undetermined amount
    of bulk waste was dumped or pumped into
    low-lying areas and sand pits
   The contents of the drums were not
   analyzed  By the time remedial
   activities began, the contents of the
   drums had solidified into a substance
   with a consistency similar to tar. The
   contents had been exposed to the air for
   many years, allowing the volatile
   compounds to evaporate, leaving a very
   low concentration of volatile organic
   compounds within the drums

   Soil at the site was contaminated with
   organic and phenolic compounds,
   including naphthalene, chlorobenzene,
   creosote, toluene, xylene, halfdes,
   dichloroethane, and vinyl chloride

   A site investigation was conducted by
   Region VI of EPA and TWC in 1981  in
   June 1982, EPA and TWC signed a
   cooperative agreement to oversee
   response actions at the site A
   Remedial Investigation and Feasibility
   Study (RI/FS) was conducted from May
   1983 until June 1986

   Based on the RI/FS, a ROD was signed
   in September 1986, specifying a
   remedy which included on-site
   incineration to reduce the concentration
   of contaminants in soil and debris at the
   site
U 8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                          219

-------
                             SITE  INFORMATION (CONT.)
   Construction management and oversight
   services for the remedial action activities
   began in September 1989.  In April 1990
   TWO awarded the remedial action contract
   to the joint venture of International
   Technology Corporation and Davy McKee
   Corporation (IT/Davy).

   Remedial activities began in October 1990
   when IT/Davy began clearing the site.
   Rood protection at the site was required due
   to Hs location m the flood plain  IT/Davy
   constructed an earthen embankment
   structure to elevate the incineration facility
   above the 100-year flood plain  and
   constructed a dike around the Main Waste
   Pit area As required in the Remedial
   Action Contract, the structures were a
   minimum of two feet above the 100-year
   floodplam

   A shallow aquifer is located two to ten feet
   below the pre-excavatlon ground surface.
   Sampling and subsequent analysis showed
   that the aquifer was contaminated by
   leaching of contaminants from organic
   sludge in waste pits.

   A second aquifer located 65 feet below the
   shallow aquifer and separated from the
   shallow aquifer by plastic day showed
   concentrations of contaminants just above
   detection limits.

   A third aquifer, the Chicot aquifer, Is located
   140 feet below the second aquifer and
   serves as a primary drinking water source
   for the city of Houston  The second aquifer
   and the Chicot aquifer are separated by
   clay. As a result, it was assumed that the
   Chicot aquifer was not affected by the
   contamination at the site [2]

   Pre-trial bums were conducted at the site in
   February and March 1992, followed by a
   trial bum in April 1992  While awaiting
   approval of trial bum results the incinerator
   operated under interim conditions (at
   reduced throughput) from April through
   August 1992. Upon approval of the trial
   bum conditions in August 1992, the
   Incinerator began operating at full
   production rate.
•  IT/Davy processed approximately 496,000
   tons of soil and debris between
   February 1992 and June 1994
   Following the completion of the
   incineration of contaminated soil and
   debris, IT/Davy began demobilization
   and the last stage of the cleanup, the
   planting of native grasses  By
   December 1994, all of the soil cleanup
   goals specified in the ROD had been
   met and all soil-related remedial
   activities ceased  In April 1995 the final
   inspection of the worksite took place

Regulatory Context:

•  In 1982, EPA and TWC entered into a
   cooperative agreement, which included
   remediation activities at the site in
   Crosby, Texas

•  In 1983, the Sikes Disposal Pits site was
   placed on the National Priorities List
   (NPL)

•  As a result of the cooperative
   agreement, EPA and TWC identified
   site cleanup requirements described in
   a ROD signed on September 18,1986
   [1]

•  The selected remedy was consistent
   with the Comprehensive Environmental
   Response, Compensation, and Liability
   Act of 1980 (CERCLA), the Superfund
   Amendments and Reauthorizatfon Act
   of 1986 (SARA), and the National
   Contingency Plan (NCP) 40 CFR part
   300 [1]

•  The DREs were set according to
   Resource Conservation and Recovery
   Act (RCRA) Incinerator regulations In 40
   CFR part 264, subpart O

Remedy Selection: On-site incineration
was selected as the remedy for
contaminated soil and debris at the Sikes
Disposal Pits Superfund site based on
treatabllity study results and long-term
economic, public health and welfare, and
environmental considerations.
U.S ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watt* and Emcrgtncy RetponM
Technology Innovation Offlc*
                                          220

-------
                                                        SItos Disposal Pits Supsrfund Site
Timeline
                            SITE INFORMATION (CONT.)
1981
1982
1983
May 1983 -June 1986
September 1986
September 1987 - December 1988
October 1990
February -March 1992
April 1992
April -August 1992
August 1992 -June 1994
June 1994
December 1994
April 1995
EPA and TWO conducted site Investigations
EPA and TWO signed cooperative agreement to oversee Sites Disposal Pits
remeojanon
Sfcee Disposal Pits site placed on NPL
RemedW InvesttgaHon/FeasbMty Study
Record of Decision signed specifying on-slte incineration
niii»iiiiBol #|A«|JWI
nemooKH design
IT/Davy began clearing site
Pre-trial Bums conducted
Trial Bum conducted
Interim operation of Incinerator
Full opwftUon of incinerator
Ash backM completed
Completion of eol-related remeolal activities
Final bispection of worksite
SHe Management: State-lead

Oversight:  EPA

Remedial Project Manager:
Earl Hendnck
U.S EPA Region 6
Allied Bank Tower at Fountain Place
1445 Ross Avenue
Dallas, TX 75202-2733
(214) 665-8519
State Contact:
Jim Sher
Texas Natural Resources Conservation
Commission
MC144
12100 Park 35 Circle
Austin, TX 78753
(512) 239-2444

Treatment System Vendor:
Mike Gust
IT Corporation
2790 Mosside Boulevard
Monroeville, PA 15146-2796
(800) 444-9586
U.8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                        221

-------
                                                          SflkM mpontf PH» Sujwrftjntf Site
                                MATRIX  DESCRIPTION
Type of Matrix Processed Through the
Treatment System:

•   Soil from the unlined sand pits

Contaminant Characterization

Primary Contaminant Groups: Organic and
phenolic compounds

•   The contaminants of greatest concern were
    naphthalene, chlorobenzene, creosote,
    toluene, xylene, dichloroethane, and vinyl
    chloride.
    Drums which were disposed of on site
   The maximum concentrations detected
   in mg/kg were naphthalene (58),
   chlorobenzene (2.3), toluene (5),
   dichloroethane (20), and vinyl chloride
The matrix charactenstics that most significantly affected cost or performance at the site and their
measured values are presented in Table 2.
                             Table 2.  Matrix Character
                        TREATMENT SYSTEM DES
IT Corporation's Hybrid Thermal Treatment
System* (Incineration system) including

•  Solid waste feed system
•  Countercurrent, controlled air rotary kiln
   manufactured by Kennedy Van Saun
•  Two parallel secondary combustion
   chambers.
Sv«tem DMcrlotlon and
    The contaminated soil and drums were
    excavated using track excavators and
    loaded onto 25-ton haul trucks for transport
    Drums were taken to the solid waste feed
Supplemental Treatment Technoioov

Pretreatment (solids)-

•  Lime addition
•  Shredder.

Post-Treatment (air)

•  Gas cleaning system manufactured by
   the John Zirik Company including.
   —  Water quench tower
   —  Two-stage scrubber
   —  Vane separator
•  Environmentally Safe Temporary
   Emergency Relief System* (ESTER*)

Post-Treatment (water)'

•  On-srte wastewater treatment system
   system in the Feed Preparation Building
   and soil was taken to a staging pad for
   blending with other materials.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watts and Emergency Reaporwe
Technology Innovation Offlc*
                                         222

-------
                                                           Sftw Disposal Ptot Supfrfund SH»
                    TREATMENT SYSTEM DESCRI
    Blending at the staging pad was
    accomplished through the use of bulldozers
    and discs [2]. The Feed Preparation
    pressure to control volatile organic
    compound (VOC) emissions  This building
    housed a shredder to prepare material for
    treatment, and had the capacity to store up
    to a five-day supply of matenal for the
    incinerator.  The prepared matenal was fed
    to the incinerator by an enclosed conveyer

    Some of the excavated soil had a  high clay
    content, resulting in difficulties
    homogenizing the incinerator feed stock
    To better prepare the feed stock, lime was
    added to the soil if it was wet. Drums were
    prepared by placing them in the shredder to
    reduce their size to acceptable standards for
    the incinerator

    The kiln was 75 feet in length, had an
    outside diameter of 14 feet, and was lined
    with high-temperature refractory. The
   approximately 29 tons per hour (tph) with a
   corresponding solids residence time of 45
   minutes. The kiln was rated at 120 million
   BTU/hr and operated at approximately
   1,300°F A negative pressure was
   maintained within the tain in order to prevent
   fugitive emissions

   Residual ash from the kiln was transferred
   to the treated matenal quench facility where
   it was water cooled in a rotary mixer to a
   temperature of 180°F.  The ash was then
   placed in storage bins to await testing to
   ens- -e that it met Toxicity Characteristic
   Leaching Procedure (TCLP) criteria
   Following sampling, analysis,  and necessary
approval, the quenched ash was
landf illed on site. All of the ash met
site-specific land disposal requirements.

Flue gases from *he kiln were routed to
one of to..* two vertically downfired
SCCs for further combustion of
volatilized contaminants. The
incineration system was configured with
an SCO and its respective GCS in
parallel with another SCO and GCS
The SCCs operated at approximately
1,800°F  The flue gas residence time in
the SCCs was a minimum of 2 seconds.

The exhaust gas from the SCCs was
channeled to the GCS, where it was first
cooled to a temperature of 220°F in the
GCS's water quench section Aventuri
scrubber and a two-stage Hydro-Sonic®
scrubber were then used to control
paniculate and acid gas emissions

Water used in the GCS was collected in
sumps below the unit  This water, along
with water from the ash quench, was
treated in an on-site waste water
treatment system

Two systems that treated the water from
the GCSs and the ash quench
contained hydroclones and clanflers to
remove suspended solids from the
process water and a belt filter press to
dry the solid materials for handling [2].
The treatment processes were closed
systems with the water being discharged
into on-site holding ponds  A third water
treatment system was used to treat
contaminated groundwater and
stormwater collected from the site.
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* end Emergency Response
Technology Innovation Office
                                          223

-------
                   TREATMENT SYSTEM DESCRIPTION (CoNT.)
           arfption and Operation fConLl
   Combustion gases were drawn through the
   kiln system and GCS by induced draft fans
   and were exhausted through two 85-foot
   fiberglass stacks  Typical flue gas velocity
   was 26,500 actual cubic feet per minute and
   the typical stack exit temperature was
   220°F.
The incinerator also was equipped with
an emergency backup system  The
Environmentally Safe Temporary
Emergency Relief System* (ESTER")
provided for combustion of
contaminants in the kiln in the event of
a forced shutdown of the incinerator
Dunng such an event, the rotary kiln
gases were diverted to the ESTER9,
which was equipped with a 60 million
BTU Burner to thermally treat the gases
before release to the atmosphere
                        Tables. Summary of Opera
 Win Exit Gas Temperature
                       TREATMENT SYSTEM PERFORMANCE
   The cleanup goals and standards were
   specified in the ROD.  The ORE was set
   based on RCRA Incinerator regulations in
   40 CFR part 264, subpart O

   A ORE of 99.99% was required for each
   contaminant of concern
Cleanup standards required the
excavation and treatment of soil and
debris with volatile organic aromatic
concentration greater than 10 mg/kg

Ash residuals had to pass the Toxicity
Characteristic Leaching Procedure
(TCLP) before on-site disposal
   A trial bum conducted at Sikes Disposal Pits
   was designed to operate the incineration
   system at conditions that would reflect worst
   case destruction and removal of all
   constituents of concern

   Naphthalene was selected as a principal
   organic hazardous constituent (POHC)
   because It was a semivolatite c-ganic
   compound present at hgh concentrations at
   the site and because it ?*as a high Thermal
Destructibility Ranking Chlorobenzene
also was selected because it is a
volatile organic compound, was present
in abundance at the site, has a high
Thermal Destructibility Ranking, and is
a source of chlorine residuals [2]
U S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Retponse
Technology Innovation Office
                                         224

-------
                                                            SOa* Disposal Pit* SupulundStto
                   TREATMENT SYSTEM PERFORMANCE (CON~
    The incinerator at Sikes Disposal Pits
    operated wrthm the operating limits
    established during the trial bum The
    AWFCOs limits used during the
    incineration action and their frequency of
    occurrence are shown in Table 4 Trial
    bum and actual operating parameters are
    shown in Table 5
                    The residual ash was sampled and
                    analyzed to see if it was in compliance
                    with the Remedial Action Contract's on-
                    site land disposal requirements The
                    residuals were tested had to pass the
                    TCLP before land disposal.  These data
                    are presented in Table 6
                          Table 4  Automatic Waste Feed Cutoffs
                                                       4576tph
Maximum k8n pressure^
Mnbnum Un ndt gas temperature9
Maximum total SCO water gun flow rale*
MWmum SCC extt gas temperature*
Maximum quench outlet gas temperature3
Mtalmun oaa condHkvw redrculattan flow rate*

Mkiimum GCS-1 TedrcutaHon flow rate4
Mbitmum GCS-2 redrcutetton flew rate4
Minimum 6CS-2 sump pH4
Minimum pressure deferential across QCS-1 and 2s

MTMniuin oloCK ySS Uj COncenVBUOn
Maximum CO concentration In stack gas (O 7% oxygen)'
Maximum stack gas corrected THC concentration (O 7%
own)8
Maximum stack gas flow rate*
00 Inches wo
1.058-F
17.5 gpm
1,688-F
191 °F
28 gpm
251 6 gpm
183 gpm
69
32.2 inches we
3%
500 ppm
20ppm
47.550 acfm
975
36 |
0
40
120
8
12
9
148
114
148
1
5
5
'15-mlnute rolling average
230-second delay
Instantaneous
4Smlnutedetey
Bl-hour rolling average
tph = tons per hour
gpm = gallons per minute
ppm * parts per mlfflon
acfm • actual cubic feet per minute
we = water column
U.8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           225

-------
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
                             Tables.
Contaminated Soi Feed Rate
Fuel Fired Feed Rate
. .._.*
Emission Rater
PartfcuMe
HO
S04«
Lead'
NO,
Operating CondWons
Kan pressure
co concemranon in gas
Mh eodt pjes temperature
SCC exit temperature
SUck gas flow rate
MHmum OCS pressure drop
Quench exit gas temperature
astph
120mMonBTU/hr
llMfl/m8
NotAvalable
OBugAn*
OCBugAnP
15ugAn*
-OTSfncheewc
144ug/m*
1^00"F
1,800°F
42,000 acfm
34 Inches we
180"F
45 78 ton
120m»onBTU/hr
16.704 Mg/rn3
<0 027 to/fir
2688ug/m*
NA
MA
NA
10
1.058eF
i,688«F
47 550 acfm
32^ Inches we
NA
we = Water column
•ActualvoJue. average parameters for daily operations as reported in the Remedtel Action Report.
•Corrected to 7% Oj
'Annual value
^Quarterly value.
Arsenic
Barium
Cadmium
Chromium
Lead
Mercury
Selenium
Silver
50
1000
10
50
50
OS
10
50
<0.5
<100
<01
<05
<05
<002
<01
<0.5
Note: Only contaminants that were analyzed for are Included m thtstabte
*c~~~~t~l «.m in r*co aa< ni T«MA «
•   Data are available for concentrations of
    contaminants in the soil before treatment
Data are also available for TCLP
analysis for contaminants In the
incinerator residue. These data were
collected periodically throughout
operation of the incinerator prior to
landfilling.
US ENVIRONMENTAL PROTECTION AQENCY
Offict of Solid Wast* and Emergency Rctporw*
Ttohnology Innovation Offlc*
                                           226

-------
                                                           Stttes Disposal Pita SuporfundSHe
                                           PERFORMANCE (CONT.)
    According to site personnel, the QA/QC
    program used throughout the remedial
    action met EPA and TWO requirements
    established in the ROD All monitoring was
    performed using EPA-approved methods
                             TREATMENT SYSTEM COST
Procurement Pro
    TWO contracted with Lockwood, Andrews, &
    Newnam, Inc (LAN) to manage the Sikes
    Disposal Pits site IT/Davy was contracted
    to provide and operate the incinerator at the
    site
   331
                                     •  The estimated treatment cost of
                                        $115,000,000 was reported by LAN and
                                        IT/Davy in terms of capital costs and
                                        operation and maintenance costs. The
                                        estimated capital costs for the
                                        incineration system were $20,051,000
                                        and estimated operation and
                                        maintenance costs totaled $95,027,000
                                        [5]  The estimated total cost for thermal
                                        treatment was $81,000,000  A total of
                                        496,000 tons of soil and debns were
                                        incinerated  This corresponds to a total
                                        unit cost for incineration of $230 per
                                        ton, and a unit cost of $160 per ton for
                                        thermal treatment.
                    Mobilization and preparatory work
02
Monitoring, sampling, testing, and analysis
  $139.000
   331
03
Sitework
 $3.986.000
   331
05
Surface water collection and control
 $4.020.000
   331
22
General requirements
   $95.000
                    Total Capital Costs
                                                                $20,051.000
                    Monitoring, sampling, testing, and analysis
   342
14
Thermal Treatment (Incineration) which includes
•   Equipment
•   Labor
•   Direct operating costs
•   Overhead
$81,000,000
   342
18
Disposal
 $3,044,000
   342
22
General requirements
 $6,754,000
                    Total Operation and Maintenance Costs
                                                                $96,027,000
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          227

-------
                                                           Sites Disposal Pits Superfund SHo
                              TMENT SYSTEM COST (CONT.)
Co«t Data Quality
   Actual capital and operations and
   maintenance cost data are available from
   the treatment vendor and EPA Region 6 for
   this application.
                      OBSERVATIONS AND LESSONS LEARNED
   Actual costs for the project were
   approximately 26% more than the projected
   costs because the volume of contaminated
   soil that required treatment was 45% greater
   than anticipated

   Change orders amounted to 25% of the
   original contract cost
The added cost of building and installing
an additional SCO train was offset by
the fact that the extra train increased
the throughput rate of incinerator, which
decreased the amount of time that the
unit would have had to operate
IT/Davy anticipated that it would cost
less money to build an extra train and
operate for a shorter amount of time
than to operate with only one train [6]
    Operation at the site was completed
    approximately 18 months before the
    deadline specified in the remedial action
    contract even though 496,000 tons of
    material was incinerated instead of the
    342,000 tons originally estimated [4]
    Because the incinerator used by IT/DAVY
    was over three times larger than required
    and the average throughput rate of 29 tons
    per hour was almost two and a half times
    greater than the minimum throughput rate of
    12 tons per hour required in the contract,
    the remediation was completed ahead of
    schedule

    The incinerator provided by IT/Davy was
    larger than required because it was
    anticipated that the incinerator would be
    used at two other sites following Sikes
    Disposal Pits  Building the incinerator
    larger, therefore, cut down on overhead
    costs when compared to building three
    separate incinerators. The Incinerator used
    at Sikes Disposal Pits, along with one SCO
    train, was transported to the Times Beach
Superfund Site upon the completion of
the project [6]

The limiting factor for the throughput
rate of the incinerator was the size of
the SCC tram and its capacity to
channel kiln off-gas  The SCC train
size was constrained by the fact that it
had to be transported to the site  One
SCC train would not have allowed the
incinerator to operate at its intended
capacity  Therefore, the decision was
made by IT/Davy to install a second
SCC train Fn parallel with the first, giving
a 30% increase in throughput rate  The
two trains were designed to operate
simultaneously, however, one train
could be shutdown for routine
maintenance while the incinerator still
functioned with one operating train [6]

Drum handling was an important issue
on site. Separate protocols were
developed for handling both intact and
ruptured drums. When excavation was
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wast* and Emergency Response
Technology Innovation Office
                                           228

-------
                                                           Sikes Disposal Pits SuporfundStte
                 OBSERVATIONS AND LESSONS LEARNED (CONT.)
    completed, however, it was discovered that
    only one intact drum existed  Few volatile
    organic compounds remained in the
    ruptured drums because they had previously
    leaked into the soil or into the air  Site
    management felt that resources had been
    spent developing a protocol for conditions at
    the site which did not exist, and a more
    thorough investigation might have avoided
    this situation.

    Dunng operations, 86 ESTER* events
    occurred at the site  Each event was
    typically 2 to 3 minutes in length, beginning
    with a shutdown of the induced draft fans
    and the opening of the vent from the
    incinerator to the ESTER* stack A dark
    paniculate plume was visible around the
    ESTER* stack during the event, but no
    significant changes were measured by
    monitors in ambient air quality [2]
Public involvement
    Following the events there was
    approximately a 45 minute delay which
    occurred to get the system back on-line
    The cause of the events was usually a
    problem with instrumentation and not a
    problem with incinerator operation [3]

    Overpressunzation of the kiln caused
    frequent AWFCOs  The primary cause
    of the overpressure in the kiln was
    related to slag build-up in the SCCs. As
    the slag built up, it would eventually fall
    to the bottom of the SCC chamber,
    which contained a water well The slag
    falling into the water generated steam,
    which would then back-up into the kiln
    creating overpressure A similar
    situation also developed, although to a
    much lesser extent, from the ash
    cooling system, where steam generated
    from the water used to cool the ash also
    backed up into the kiln [3]
    The largest concern of the public was that
    the incineration system would become a
    permanent facility and treat waste from
    other sites The public was not convinced
    that such a large amount of money would
    be spent on a facility which was only
    temporary  EPA held a series of public
    meetings with local citizens in an
    attempt to alleviate their concerns
                                     REFERENCES
1.  Suoerfund Record of Decision. Sikes
    Disposal Pits, Crosby, Texas, September
    18,1986

2   Sikes Disposal Pits Suoerfund Proiect
    Remedial Action Report. Lockwood.
    Andrews & Newnam, Inc., December 28,
    1995
3   Personal Communication, Mr Earl
    Hendnck, USEPA Region VI, April 10,1997
4   Successful Completion of tha Sikes
    Incineration Protect. James R. Donnelly
    and Michael Gust, Superfund XV
    Conference and Exhibition

5   Correspondence with Mr Kevin Smith,
    IT Corporation, Apnl 4,1997

6   Personal Communication, Mr Mike
    Gust, IT Corporation, May 6,1997
U 8 ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Wute and Emergency Response
Technology Innovation Office
                                          229

-------
This Page Intentionally Left Blank
              230

-------
 On-Site Incineration at the
Times Beach Superfund Site
   Times Beach, Missouri
           231

-------
            Incineration at the Times Beach Superfund Site
                           Times Beach, Missouri
Sif@N&
-------
            Incineration at the Times Beach Superfund Site
                           Times Beach, Missouri
                                    (Continued)
Description:
Between 1970 and 1972, a pharmaceutical and chemical company produced wastes that
contained TCOD from the production of hexachlorophene A waste oil company mixed this waste
with waste oil and used the mixture to spray roads in Times Beach and the surrounding areas to
control dust. A remedial investigation determined that soil was contaminated at 27 sites in the
State of Missouri; Times Beach served as a central treatment facility for these sites. A Record of
Decision (ROD), signed in September 1988, specified on-site incineration as the remediation
technology for the excavated soil and debris Site cleanup goals and ORE standards were
specified for TCDD
On-srte incineration using the IT Corporation Hybrid Thermal Tiaatment System* began in
1996 and was completed in June 1997 The treatment system consisted of a rotary tain and an
SCO An enclosed conveyor moved the soil and debris to the kiln for treatment  Treated ash
from the incinerator was discharged to a cooler where it was quenched with water  Dunng its
operation, the incinerator at Time Beach processed 265,000 tons of soil and debns. Incineration
achieved the soil cleanup goals specified in the ROD, including 1,900 tons of incinerator ash that
met soil cleanup goals only after re-incineration

The total cost of the Remedial Action was approximately $1 10,000,000.
                                       233

-------
                                                                Time* 0Mcn Supfrfund Sto
                                EXECUTIVE Sur.
This report presents cost and performance data
for the application of on-slte incineration at the
Times Beach Superfund site in Times Beach,
Missouri. A rotary kiln incinerator was operated
from March 1996 through June 1997 as part of a
remedial action. The contaminant of concern at
the site was 2,3,7,8-tetrachlorodibenzo-p-dioxin
(TCDD)

The Times Beach site served as a central
incineration facility for 27 TCDD-contaminated
sites across the state of Missouri   Soil and
debris at these sites were contaminated with
TCOD in the 1970s by waste generated in the
production of hexacnloropnene by a
pharmaceutical and chemical company This
waste was mixed with waste oil and sprayed on
roads as a dust suppressant by a private firm.

The contaminated debns from the 27 sites
included home insulation, furniture, flooring,
carpet, and mattresses; scrap metal, and tree
stumps and brush  Contaminated soil contained
rocks, asphatt, gravel, and sawdust [4]. The
geometric mean of TCDD concentrations
measured during the remedial investigation was
79ug/kg

In 1990, EPA and the State of Missouri entered
into an agreement with the Responsible Party
(RP)  A Record of Decision (ROD) signed in
September 1988 established a destruction and
removal efficiency (ORE) of 99 9999% for
TCDD.

The RP conducted remedial activities including
the operation of the rotary kiln incinerator.  The
incineration system used at Times Beach was
comprised of a solid waste feed system, a
countercurrent, controlled-air, rotary kiln with an
oxygen-enhanced burner; a secondary
combustion chamber (SCC); a wet gas cleaning
system (GCS); and a treated material handling
system [4].
Soil and debris were collected in bags,
drums, and boxes, and transported to the
Times Beach incinerator  To prepare the
feedstock, soil was mixed with lime to
reduce moisture content and debns was
shredded to an acceptable size for the
incinerator. Prepared matenal was fed to
the incinerator by an enclosed conveyor

Resulting ash from the incinerator was
removed and cooled with water, while off-
gas was drawn into the SCC.  The SCC was
a down-fired steel shell that provided further
combustion of contaminants in the off-
gases Both the incinerator and SCC were
fueled by natural gas.

Treated gas was then drawn into the GCS,
which consisted of a quench contactor, a
gas conditioner, two Hydro-Sonic*
scrubbers, and a vane separator. The GCS
cooled the gas from the SCC and was
designed to remove particulate matter,
metals, and add gases before discharge to
the atmosphere. Ash collected from the
incinerator and GCS was sampled and
analyzed, if it met the treatment critena it
was landfilled on site  Ash that failed to
meet criteria was re-incinerated.

During its 16 months of operation, the
incinerator processed approximately
265,000 tons of contaminated material.
Treatment performance and emissions
collected during this application indicate that
all performance standards and emissions
were achieved

The actual cost for remediation using the
incineration system was approximately
$110,000,000
US ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watt* and Emergency Response
Technology Innovation Offlc*
                                           234

-------
ktontttwina
Information
nfltmen
Times Beach Superfund Site
Times Beach, Missouri

CERCUSf  MOD980685226

ROD Date- September 29,1988
packoreund

Historical Activity that Generated
Contamination at the Site Production of
hexachlorophene

Corresponding SIC Code: 2834
(Pharmaceutical Preparations)

Waste Management Practice That
Contributed to Contamination: Oil used for
roadside dust suppression

Site History-

•   The Times Beach site occupies a 0.8 square
    mile area on the Meramec River The site
    served as the central collection and
    treatment center for the 27 TCDD-
    contaminated sites in the state of Missouri

•   From Apnl 1970 until January 1972, a
    pharmaceutical and chemical company
    generated TCDD-contaminated waste
    during the production of hexachlorophene

•   From February 1971 until October 1971, a
    waste oil company removed TCDD-
    contaminated still bottoms from the
    chemical plant and mixed It with waste oil
    The town of Times Beach contracted the oil
    company to spray unpaved roads with waste
    oil to control dust from the summer of 1972
    through the summer of  1976 [ f CJ

•   In July of 1971, drums of waste containing
    TCDD were buried at the Denney Farm site
    An additional 225,000 gallons of waste were
ilteatk
                                     Type of action  Remedial (on-site rotary
                                     kiln incineration)

                                     Period of operation: March 1996 - June
                                     1997

                                     Quantity of material treated during
                                     application- 265,000 tons of soil and
                                     debris
                                         taken to the wastewater treatment
                                         school at Neosho. In October 1979, an
                                         anonymous caller tipped EPA that the
                                         waste was applied at various locations
                                         in Missoun including Minker, Stout, and
                                         Romaine Creek  Subsequent
                                         investigations found TCDD
                                         contamination at the Denney Farm site
                                         and other farms, the wastewater at
                                         Neosho, and in fish and sediment in the
                                         Spring River [7C§.

                                         A site investigation was conducted in
                                         the town of Times Beach in 1982  In
                                         February 1983, under the advice of the
                                         Center for Disease Control (CDC), EPA
                                         transferred funds to the Federal
                                         Emergency Management Agency
                                         (FEMA) to permanently relocate Times
                                         Beach residents and businesses [21

                                         A Remedial Investigation and Feasibility
                                         Study (RI/FS) was conducted in 1984
                                         for the Times Beach and Minker, Stout,
                                         and Romaine Creek sites Based on the
                                         RI/FS, a ROD was signed in September
                                         1988, specifying on-site incineration to
                                         reduce the concentration of TCDD in
                                         soil and debris.

                                         EPA determined that Times Beach was
                                         the best location for a temporary
                                         treatment facility for the TCDD-
                                         contaminated soil and debris from the
                                         various sites in the state of Missouri
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Rwponw
Technology Innovation Office
                                         235

-------
                             SITE INFORMATION (CONT.)
•   The RP began excavating the contaminated
    soil at all of the sites in 1992 Between
    1992 and March 1996, the contaminated
    soil and debris were stored in temporary
    containment facilities. In March 1996, a
    mobile, rotary kiln incinerator began
    operation to remediate the excavated soil
    and debris

•   The RP incinerated approximately 240,000
    tons of soil and debris between March 1996
    and June 1997 [72J.

Regulatory Context:

•   The Missouri Department of Natural
    Resources (MONR) and EPA identified site
    cleanup requirements described in a ROD
    signed on September 29,1988 [2] The
    ROD called for placing a dean soil cover at
    least 1 foot in depth over soil in the state
    that contained TCDD concentrations ranging
    from 1 to 20 ug/kg  Excavation and
    incineration was required for soil with
    concentrations exceeding 20 ug/kg

•   In 1990, the state of Missouri and EPA
    entered into an agreement with the PRP,
    which included remediation activities at the
    site in Times Beach, Missouri
•  The selected remedy was consistent
   with the Comprehensive Environmental
   Response, Compensation, and Liability
   Act of 1980 (CERCLA), the Superfund
   Amendments and Reauthorization Act
   of 1986 (SARA) and the National
   Contingency Plan (NCP) in 40 CFR part
   300 [1].

•  Hazardous Waste Management Facility/
   RCRA Permit No  MO0000335919,
   issued by EPA and MDNR, signed on
   April 14,1995, required a trial bum and
   a dioxm stack test and set requirements
   for air emissions from on-site
   incineration of contaminated soil and
   debris

•  Resource Conservation and Recovery
   Act (RCRA) regulations require a DRE
   of 99 9999% for TCDD. Stack gas
   monitoring was conducted for oxygen
   and carbon monoxide in accordance
   with 40 CFR part 264, subpart O.

Remedy Selection- On-site incineration
was selected as the remedy for
contaminated soil at the Times Beach
Superfund site, wastes from 26 other sites
in the State of Missouri also were
incinerated at the site based on treatability
study results, long-term economic concerns,
and human health considerations.
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emwgwcy Rttponte
Technology Innovation Office
                                         236

-------
                                                                  Tftn
                                                             torn* Site
                              SITE INFORMATION (CONT.)
Timeline
                                    Table 1  Timeline [1
       July 1971
Waste buried at Penney Farm site
   Summer 1972-Summer
         1976
An <* company applied waste oH to unpavad streets of Times Beach
      October 1979
225.000 gallons of waste token to Neoshi
atmentschi
      October 1982
Initial site kn
      February 1983
EPA formers furris to FEMA to permanaTtryreta^
      February 1966
Remedial IriVBstigatoVFeasfcityStuclyccjrnpleted
     September 1988
Record of Decision signed
   November 11,13.14,
         1995
                      Trial Bum
         1992
Contarnlnated soil excavation started at Times Beach and 26 other sites
  March 1996 - Juw 1997

Site Information

•   Soil samples were collected at more than
    1,000 different locations at the Times Beach
    site, at varying depths to characterize the
    extent of the contamination
                                Soil samples were also collected and
                                analyzed at 26 other sites across the
                                state to characterize the extent of
                                contamination at these sites
Site Management  RP-lead

Oversight EPA

Remedial Project Manager:
Robert W. Feild
U.S EPA Region 7
726 Minnesota Avenue
Kansas City, KS 66101
(913) 551-7697
                            State Contact:
                            James O. Silver, OSC
                            Missouri Department of Natural Resources
                            Times Beach Project Oversight Office
                            97 North Outer Road, Suite 4
                            Eureka, MO 63025
                            (314) 938-9150

                            Treatment System Vendor:
                            Con Murphy
                            International Technology Corporation
                            97 North Outer Road, Suite 8
                            Eureka, MO 63025
                            (314)938-9711
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                           237

-------
                                                              TftiMS BMcft SupHfUnd Site
                               MATRIX DESCRIPTION
Itotriy Identification

Type of Matrix Processed Through the
Treatment System- Soil and debns

•   Excavated soil contained rock, asphalt,
    gravel, and sawdust
   Debns included insulation, furniture,
   flooring, clothing, drapes, carpet,
   mattresses, plastic liners, rubble, trash.
   vinyl flooring, charcoal, water, metal
   scrap, brush, tree stumps, vacuum truck
   hoses, personal protective clothing,
   samples, and containers [4]
Primary Contaminant Group  Dioxins

•  The contaminant of greatest concern is
   TCDD.
   The minimum and maximum
   concentrations detected in the state
   were 1 ug/kg and 1,800 ug/kg
   respectively, with a geometric mean
   value of 79 ug/kg
   The soil treated at Times Beach had a
   moisture content that ranged from 0 53 to
   32%, with a geometric mean value of 7.8%
   \A
   Soil and debris from each of the sites
   was collected in bags, drums, and
   boxes. Each of these containers also
   was incinerated
                          TREATMENT SYSTEM DESCRIPTION
IT Corporation's Hybrid Thermal Treatment
System* (Incineration system) including-

•   Solid waste feed system
•   Countercurrent, controlled air rotary kiln with
    oxygen-enhanced burner manufactured by
    Kennedy Van Saun
•   Secondary combustion chamber
Pretreatment (solids).

•  Lime addition
•  Screening and shredding

Post-Treatment (air)-

•  Gas Clean System manufactured by the
   John Zink Company including:
   —  Water quench tower
   —  Two-stage scrubber
   —  Vane separator
•  Environmentally Safe Temporary
   Emergency Relief System* (ESTER*)

Post-Treatment (water)

•  On-site wastewater treatment system
U.S. ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Wait* and Emergency Revporwe
Technology Innovation Office
                                         238

-------
                                                                      SMC/I SkfMfftmcr Sffl»
 System Description and Operation

 •   The contaminated soil had a relatively high
    moisture content. To prevent the buildup of
    excessive pressure in the kiln, the soil was
    pre-treated to remove moisture  Lime was
    added to the soil or, if time permitted, the
    soil was sun-dned

 •   Other feed material was prepared for
    incineration using several pieces of
    equipment  Matenal preparation took place
    in the Feedstock Handling Building, which
    was maintained at a slight negative
    pressure to prevent fugitive emissions  An
    initial screening device allowed six inch or
    smaller matenals to fall into a crushing
    circuit  Material greater than six inches was
    broken up with mobile equipment  The
    matenal was then stacked radially within the
    building and a magnetic separator removed
    metal items which could damage processing
    and conveying equipment  The matenal
    was then fed into a shredder, which crushed
    the matenal to a two inch or smaller size
    The matenal was then blended to achieve
    the desired feed consistency [4]  Once the
    matenal was prepared, it was fed to the kiln
    by an enclosed conveyor

•   The kiln had a length of 75 feet, an outside
    diameter of 13 feet, 7 5 inches, and an
    installed slope of 0 25 inches per foot  The
    tain was lined with 9 inches of high-
    temperature, add resistant, insulating
    refractory and was designed such that the
    optimal throughput of contaminated soil was
    approximately 38 tons per hour  The kiln
    rotated at a maximum rate of 60 revolutions
    per hour with a corresponding solids
    residence time of  1 hour

•   The kiln employed an oxygen-enhanced
    burner which had a firing capacity of 40
    million BTU/hr and operated at
    approximately 1,250*F The oxygen-
    enhanced burner increased incinerator
    productivity by increasing heat transfer and
    throughput rate
 Residual ash from the kiln was
 transferred to a treated matenals cooler
 and was water quenched until it reached
 200°F. The ash was then sampled and
 analyzed to ensure that it met treatment
 criteria If the ash met the critena, it
 was landfilled on site, if not, it was re-
 incinerated.

 Flue gases from the kiln were routed to
 the SCO to ensure complete
 combustion of volatilized contaminants
 The SCO was downfired, with an
 outside diameter of 12 feet, and a
 height of 38 feet. The SCC operated at
 approximately 1,750°F  The flue gas
 residence tome in the SCC was
 approximately 2 seconds for a gas flow
 rate of 87,000 actual cubic feet per
 minute (acfm)

 The exhaust gas from the SCC was
 then routed to the system's GCS.  Off-
 gas entenng the GCS first passed
 through a quench contactor where gas
 was cooled by the evaporation of water
 From the quench contactor the off-gas
 was channeled to the gas conditioner
 The gas conditioner contained wetted
 packing matenal, to provide a surface
 area for the collection of paraculate
 matter  Following the gas conditioner,
 the off-gas passed through two Hydro-
 sonic* scrubbers where high-energy
 water sprays created small droplets to
 capture particulate matter  The  last
 stage of the GCS was a vane separator,
 which contained multiple flat surfaces
 onto which collected particulate  matter
 that was entrained in water droplets [4]

 Water used in the GCS was recycled in
 a sump below the unit  Theblowdown
 from this sump was either reused to
 quench the ash from the incinerator or
 treated in an on-site waste water
treatment facility Particulate matter
 removed in the treatment process was
dried, and subsequently sampled and
analyzed to determine whether it could
be disposed of on the site.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                          239

-------
                                                               Times Seocn Suptrfund $&•
                    TREATMENT SYSTEM DESCRIPTION (CONT.)
    The GCS was rated for a design paniculate
    loading of 0.01 grains per dry standard
    cubic foot, corresponding to a paniculate
    emission rate of 1 pound per hour [5|  The
    design operating conditions for GCS flow
    rate and exit temperature were 12,000 dry
    cubic feet per minute (dcfm) and 200°F,
    respectively.

    Combustion gases were drawn through the
    kiln system and GCS by an induced-draft
    fan and were exhausted through a 100-foot
    stack. Typical stack gas flow was 37,000
    acfm
The incinerator was also equipped with
an emergency backup system The
Environmentally Safe Tempo'ary
Emergency Relief System* (ESTER*),
provided for combustion of
contaminants in the kiln in the event of
a forced shutdown of the incinerator.
Dunng such an event, the rotary kiln
gases were diverted to the ESTER*,
which contained a propane-fired
oxidation system to thermally treat the
off-gases before release to the
atmosphere  The ESTER* stack was
designed to reach a temperature of
1800°F
   The ROD site performance requirements
   and the MDNR established a ORE of
   99.9999% for TCDD.
Cleanup standards required incineration
of soil with a TCDD concentration
exceeding 20 pg/kg  A clean soil cover
of at feast 1 foot was required for soil
with TCOD concentrations from 1-20
Mg/kg
•   The ROD rated that soils with TCDD
    concentration exceeding 1 ug/kg at the
    surface or exceeding 10 \igfog at a depth of
    1 foot are of concern for the protection of
    human health in residential settings
    However, the ROD also stated higher TCDD
    concentrations would be acceptable in
    commercial and industrial settings and
    concluded that a 20 pg/kg TCDD
    concentration cleanup level would provide
    adequate protection of public health when
    considering the future expected land use at
    the site [2]
A nsk assessment concerning the
operation of the incinerator estimated
that the excess lifetime cancer risk level
was below 1x10* for all residents in the
immediate vicinity of the site.
US ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                          240

-------
                                                                 Ttmea Beach Sqpwfund Site
                    TREATMENT SYSTEM PERFORMANCE (CONT.)
    A trial bum conducted at Times Beach was
    designed to operate the incineration system
    at conditions that would reflect worst case
    destruction and removal of all constituents
    of concern  Hexachloroethane and 1,2,4-
    tnchlorobenzene were selected as the
    principal organic hazardous constituents
    (POHC) The reported DREs for each
    POHC are inducted in Table 2

    AWFCO limits and the frequency of
    occurrence of AWFCOs dunng the
    operation of the incinerator are shown in
    Tabled

    The incinerator at Times Beach operated
    within the operating hmrts established dunng
    the trial bum signifying that all cleanup
    requirements esteul«&ned in the ROD were
    met  Values for trial bum and actual
    operating parameters are shown in Table 4
                         The residual ash was sampled and
                         analyzed in accordance with standards
                         set in the CERCLA Exclusion for Times
                         Beach Thermal Treatment Residues
                         which required that the ash meet
                         Toxicity Characteristic Leaching
                         Procedure (TCLP) landfill standards for
                         metals. The results of this analysis are
                         presented in Table 5.

                         MDNR provided oversight at Times
                         Beach to ensure proper facility
                         operation Additionally, St Louis county
                         officials inspected operations and
                         tracked air-monitoring to ensure that the
                         emissions were in compliance with the
                         county's air pollution permit
            Table 2 A
Destruction and Removal Efficiencies from Trial Bum i
                          Table 3. Automatic Waste Feed Cutoffs
 Maximum contaminated sol feed rate*
              417tph
                                                                        Rarely
Maximum CO <
(0
miration In stack gas
                                         lOOppmv
                                            Never
 Mnknum Mki odt gas temperature''
              1,117-F
                                                                      Rarely
 Minimum SCC exit gas temperature
              1,714°F
                                                                      Rarer/
 Maximum stack gas flow rate1
            38,260 aetim
                                                                      Once
 Minimum GCS differential pressure*
           24.2 Inches H,O
                                                                      Never
 Maximum quench exit yn temperature
              250°F
                                           Rarely
 Mndmum Win pressure
           -006 inches H.O
                                                                      DaAV*
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                          241

-------
                                                                     TiRM
                                      vperfundStte
                     TREATMENT SYSTEM PERFORMANCE (C
                            Tables Automatic
  Maximum ojuench radrcutaflon rate
 400 gpm
                                                                            Rarely
  MHmum quanch redrctdatton pump
  power
                                              OkW
                                 Rarely
  MMnun Hydro-1 recfecuMion rate
 307 gpm
                                                                            Rarely
MMmum Hydrc-2 reeirculatlon rate
                                             215 gpm
                                 Rarely
  Minimum scrubbing liquid pH in Hydro-2
  sump
                                 Rarely
  Maximum ID for vibration
04SkVBec
                                                                            Rarely
  Maximum ID for cur-ant
  720 A
                                                                            Rarely
  MMmum WESP secondary voltage
 174KV
                                                                            Rarely
MNmumgasO.(
nitration
                                           3 5% by volume
                                 Never
'AWFC tags were not maintained  These descriptions
represent operator estimates
'l-hourroHng average
"lO-mlnute raing average
'High moisture content In the soN has caused overpressuriza-
tkxiofthekfti This caused 2 to 12 automatic waste feed
cutoffs per day and was the primary cause of AWFCO
         su s standard PH units
         tph = tons per hour
         acfm = actual cubic feet per minute
         gpm = galons per minute
         A=amps
         kV = Wlovolts
Table 4. Operating Parameters [7,8]
ig-'imm- •-%:•«-'-•>• •:-T:^-.-' ' •' •.•^&t •••'-;• ^'*zr^9m
Contaminated Sol Feed Rate
Fuel Fired Feed Rate

emission rune
Paniculate
HO
0,
CO,
0,
Lead
No.
Operating Conditions
co concentration n stack Gas
KNn ExK Qas Temperature
SCC ExH Temperature
Stack Qas Flow Rate
GCS Differential Pressure
Quench Extt Gas Temperature
31 tph
40 mWon BTLMir
MA
Not Monitored
Not Monitored
9% by dry volume
7-8% by volume
Not Monitored
Not Monitored
Trace
1,250'F
1.750-F
37,000 acfm
25 Inches H..O
200'F
41 7 tph
40 miton BTU/hr
0.94ltVhr
OOUtVhr
00023 to/hr
11 7% by dry volume
6 7% by volume
00082 Whr
157BVhr
Trace
1,117-F
1,714-F
38,300 acfm
242 Inches HtO
250°F
"Actual Value anticipated parameters for daily operations as projected In the Trial Bum Report
toh-tons per hour
acfm - actual cubic feet per minute
U.S. ENVIRONMENTAL PROTECTION AGENCY
Ohio* of Solid Wutt and Emergency Response
Tschnoteoy Innovation Office
                                              242

-------
                                                               Times Bmach Superfund Sto
                   TREATMENT SYSTEM PERFORMANCE (CONT.)
                         Tables  TCLP Comparison for Residual Ash
  Barium
1000
                                                                       0278
 Cadmium
                                                10
                                                                       0072
  Chromium
  50
0008
  Lead
  50
0.233
  Mercury
  02
                        < 00008
 Selenium
  10
                                                                       0041
 Silver
  50
                                                                       <0004
Mole. Only contaminants lhatwwe analyzed for are Included In this table
•Excerpted from 40 CFR §261.24 Table 1


Performance Data Comnleteness
    Data are available for concentrations of
    TCDD in the soil before treatment
Performance Data Quality

•   The QA/QC program used dunng the
    remedial action met EPA and MDNR
    requirements.  All monitonng and sampling
    and analysis was performed using EPA-
    approved methods
     Data are also available for
     concentration of TCDD in incinerator
     residuals These data were collected
     before residuals were disposed of on
     the site
                              TREATMENT SYSTEM COST
Procurement Process
•   The RP contracted with Foster Wheeler
    Environmental Corporation to manage the
    Times Beach site  IT Corporation was
    contacted by Foster Wheeler to operate the
    incinerator at the site

Coat Data

•   The cost for operation of the incinerator at
    Times Beach was $110,000,000 A total of
    265,000 tons of soil and debris were
    incinerated  This corresponds to a total unit
    cost for incineration of $800 per ton A
    detailed breakdown of these costs was not
    available.
U S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Response
Technology Innovation Office
                                         243

-------
                                                                Times Beach Superfund Site
                      OBSERVATIONS AND LESSONS LEARMED
    Site personnel expenenced problems with
    the power supply to the incinerator One
    incident involved an unexpected storm
    which interrupted power supply  Strong
    wind gusts from the storm blew out the pilot
    bgn*s on the ESTER* system  Therefore,
    w&he i the power was interrupted and the kiln
    shut down, kiln gases routed to trie ESTER*
    were released directly to the ambient
    atmosphere  Emission levels used in this
    analysis could only be estimated because
    the aii-monitonng equipment was on the
    sanr-9 electrical circuit as the incinerator and
    did not operate  To prevent future weather-
    related occurrences, the operator decided to
    work closely with the local weather service
    to receive accurate weather forecast
    updates. Subsequently, the waste feed was
    ceased during severe weather
Public
Involvement
                                              High moisture content in the waste feed
                                              caused overpressunzation in the kiln
                                              resulting in 2 to 12 automatic waste
                                              feed cutoffs per day  Site personnel
                                              noted that excavating the soil when  it
                                              was dry would have been the best way
                                              to avoid this problem. However, at the
                                              time of remediation, soil was either
                                              being (1) excavated immediately pnor
                                              to incineration due to time constraints,
                                              which did not always allow the soil to be
                                              excavated when it was dry or (2) was
                                              stored in large bags from other sites In
                                              response to this problem, personnel at
                                              the Times Beach site added lime to  the
                                              soil, or, if time permitted, let it sun dry to
                                              reduce moisture content before feeding
                                              the soil to the incineration [11].

                                              An estimated 1,900 tons of incinerator
                                              ash required re-incineration because it
                                              did not meet requirements   Following
                                              re-incineration,  it met the requirements
                                              and was able to be backfilled on site
   The concern most frequently expressed by
   local residents was the possibility that the
   Times Beach incinerator would eventually
   be used to incinerate dioxin-contaminated
   material from other states  EPAandMDNR
   assured the public that the Times Beach
   incinerator would cease operation once the
   cleanup from the 27 sites in Missoun was
   completed [11]
                                               Before remediation began at the site,
                                               local residents expressed concern about
                                               the potential for excessive noise from
                                               the incinerator  This never became a
                                               problem because the operations took
                                               place within enclosed buildings.  This
                                               also served to prevent fugitive
                                               emissions dunng matenals Handling
US ENVIRONMENTAL PROTECTION AGENCY
Offlc* of Sottd Waste and Em«rgercy R«epon«e
Technology Innovation Office
                                           244

-------
                                                               Times Beach Superfund Site
                                     REFERENCE;
1   Superfund Record of Decision. Times
    Beach, St  Louis, Missouri, January 13,
    1984

2.  Superfund Record of Decision. Times
    Beach, Times Beach, Missouri,
    September 9,1988

3   Letter to Mr GaryJ  Pendergrass, P E ,
    Project Coordinator for the Settling
    Defendants, from Mr David A  Shorr,
    Director of the Missouri Department of
    Natural Resources, Information on Modified
    Hazardous Waste Management Facility
    Permit for Times Beach, March 15,1996

4   Engineering Description and Trial Bum
    Plan. Times Beach Thermal Treatment Unit.
    IT Pollution Control Engineenng, April 1994

5   Final Times Beach Site Multimedia Risk
    Assessment Vol  I. U S  Environmental
    Protection Agency, March 28,1995

6.  Letter to  Mr  David Shorr, Director of the
    Missouri  Department of Natural Resources,
    from Mr.  Fred Striley. Dioxin Incineration
    Response Group, Information on permit
    application for the Times Beach incinerator,
    June 18,1995
Trial Bum Report for the Times Beach
Remediation Project. IT Corporation,
January 1996

Dioxin Stack Test Report for the Times
Beach Remediation Project. IT
Corporation, January 1996
8
9.  WeeMv Progress '^pfo*0,. Eastern
    Missouri Dioxin Cleanup Proiect.
    Missouri Department of Natural
    Resources, March 17,1997.

10. A Chronology. Important dates in the
    Times Beach Superfund site history, St
    Louis Post-Dispatch

11  Personal Communication, Mr  James
    Silver, March 27,1997.

12. Engineenng News-Record. McGraw-Hill
    Companies, July 14,1997
U.S. ENVIRONMENTAL PROTECTION AGENCY
OfflM of Solid Waste and Emergency Response
Technology Innovation Office
                                         245

-------
This Page Intentionally Left Blank
              246

-------
        On-Site incineration at the
Vertac Chemical Corporation Superfund Site
          Jacksonville, Arkansas
                   247

-------
  Incineration at the Vertac Chemical Corporation Superf und Site
                          Jacksonville, Arkansas
Site Name:
Vertac Chemical Corporation
Superf und Site
Location:
Jacksonville, Arkansas
Contaminants:
Dioxins and Volatile Organic
Compounds

• TCDD, chlorinated benzene,
  chlorinated phenols, 2,4-D,
  and 2,4,5-T.
• TCDD concentrations up to
  50mg/L
Period of Operation:
January 1992 - September
1994
Cleanup Type:
Remedial action
Vendor:
MRK Industries
SIC Code:
2879 (Pesticides and
Agricultural Chemicals)
Technology:

On-Site Incineration
• Solids preheated by triple
  nnsing, shredding, and
  drying
• Incineration system
  consisting of rotary kiln and
  secondary combustion
  chamber (SCC)
• Enclosed conveyor
  transported contaminated
  matenal to the unit
• Residence time was
  approximately 40 minutes,
  kiln temperature of 2,000 °F
  and SCC temperature of
  2,200 °F
• Treated materials
  (incineration ash and
  residual) were collected and
  disposed of off site in a
  Subtitle C hazardous waste
  disposal facility.	
Cleanup Authority:
CERCLA, SARA, RCRA,
and State: Arkansas
• ROD Date MA
• State-lead
Point of Contact:
MlkeArjmandi
Arkansas Department of
Pollution Control & Ecology
P.O. Box 8913
8001 National Drive
Little Rock, AR
 72219-8913
(501) 682-0852
                                      248

-------
  Incineration at the Vertac Chemical Corporation Superfund Site
                           Jacksonville, Arkansas
                                   (Continued)
Waste Source:
Drummed still bottom waste -
herbicide manufacturing waste
Purpose/Significance of
Application:
Two temporary restraining
orders were filed to stop the
incineration project over public
concern about the incinerator
Type/Quantity of Media Treated:
Storage Drums, Drummed Waste, and Soil
• 9,804 tons of waste
• 1,027 tons of soil
Regulatory Requirements/Cleanup Goals:
• Destruction and Removal Efficiency (DRE) of 99 9999% for all constituents of concern as
  required by Resource Conservation and Recovery Act (RCRA) incinerator regulations, 40 CFR
  part 264, subpart O
Results:
• Emissions and trial bum data indicated that all DRE and emissions standards were met
Cost Factors:
The incineration system at the site consisted of a rotary kiln and a secondary combustion
chamber, followed by an air pollution control system  	
Description:
Between 1948 and 1987, the Vertac site operated as a herbicide manufacturer within the city
limits of Jacksonville, Arkansas  The by-product TCDD was placed in drums and stored on-site
Investigations at the site conducted by the U S. EPA and the Arkansas Department of Pollution
Control and Ecology (ADPC&E) as part of Vertac's participation in the 1978 National Dioxin
Survey revealed TCDD concentrations as high as 40 mg/L in production wastes and eventually
resulted in the site being placed on the National  Priorities List (NPL) in 1983.

A Consent Decree was entered into by EPA, ADPC&E, and two RPs in January 1982, which
required an independent consultant to assess the management of wastes being stored on the site
and to develop a proposed disposal method The proposed remedy was implemented In the
summer of 1984 by court order over the objection of EPA who deemed the proposal
unsatisfactory

On-site incineration began in January of 1992 and was completed in September 1994
                                       249

-------
                                                   V*rt»c Chemical Corporation SupwfundSlto
This report presents cost and performance data
for the application of on-site incineration at the
Vertac Chemical Corporation (Vertac)
Superfund site in Jacksonville, Arkansas A
rotary kiln Incinerator was operated from
January 1992 through September 1994 as part
of a remedial action. Contaminants of concern
at the site included 2,3,7,8-tetrachlorodibenzo-p-
dioxin (TCDD);  2,4-dichlorophenoxyacetic acid
(2,4-D); 2,4,5-trichlorophenoxacetlc acid (2,4,5-
T); chlorinated benzene; and chlorinated
phenols

The Vertac site was a former pesticide
manufacturing plant which operated from 1948
until  it was abandoned in 1987. During this
period, approximately 29,000 drums of still-
bottom waste from the production process were
generated and stored on site.  The drummed
waste at Vertac contained solvents and TCDD
During the remedial investigation, TCDD
concentrations were measured as high as 50
mg/L in the still bottom wastes and 2,800 ug/kg
in the soil

In 1987, the Arkansas Department of Pollution
Control and Ecology (ADPC&E) determined that
it would contract for the incineration of the
drummed wastes, and would finance the action
using a trust fund and letter of credit provided
by one Potentially Responsible Party (PRP) at
the site. Applicable  regulations under the
Resource Conservation and Recovery Act
(RCRA) required a 99.9999% destruction and
removal efficiency (ORE) for cHoxin listed
ADPC&E conducted remedial activities
including the operation of a rotary kiln
incinerator to disposed of the drummed wastes
until June 1993, when EPA assumed
management responsibilities at the site  The
incineration system used at Vertac was
comprised of a direct-fired rotary kiln, two
cyclone separators, a secondary combustion
chamber (SCC), a baghouse, a wet scrubbing
system, and ash removal facilities
The waste drums were opened, emptied,
and raised in an enclosed building
maintained at a negative pressure Waste
from the drums was fed to the incinerator
Wastewater generated was treated and
recycled in a closed system  Ash from the
while off-gas from the kiln was routed to the
cyclone separators

The cyclone separators removed
parttculates, which were routed to the waste
feed system and re-incinerated, and
discharged the gas to the SCC. The SCC
provided further oxidation of the remaining
organic contaminants in the gas.

Treated gas was drawn through an air
pollution control system (ARCS), which
consisted of a spray drier, to lower the
temperature of the gas, and a baghouse
assembly, venturi scrubber, and baffle
absorption scrubber to remove additional
particulates. The gas was then discharged
to the atmosphere. Ash collected from the
incinerator and scrubbers was disposed of
at a Subtitle C hazardous waste disposal
facility

Dunng the 32  months of operation, the
incinerator processed 9,804 tons of waste.
Additionally, approximately 1,200 tons of
2,4,5-T waste was incinerated at an off-site
facility Treatment performance and
emissions data collected during this
application indicated that all performance
standards and emissions requirements were
achieved

The actual cost for remediation using the
incineration system was approximately
$31,700,000  This amount consisted of
approximately $21,000,000 in capital costs
and approximately $10,700,000 in operating
U.8. ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watt* and Emergency Response
Technology Innovation Office
                                          250

-------
                                                  Vwtte Gnomic*/ Corporation Superfund Sft»
UBDttfti
Vertac Chemical Corporation Superf und Site
Jacksonville, Arkansas

CERCUSt ARD000023440

ROD Date: Not applicable
Type of action: Removal (on-ate rotary
kiln incineration)

Period of operation: January 1992-
September 1994

Quantity off material treated during
application: 9.804 tons of still bottom
waste, soil, and debns
Historical Activity that Generated
Contamination at the Site:  Manufacture of
herbicides

Corresponding SIC Code: 2879 (Pesticides
and Agricultural Chemicals)

Waste Management Practice That
Contributed to Contamination: Improper
waste storage and disposal practices

Site History:

•   The site operated from 1948 until it was
    abandoned in 1987. The Vertac site is
    located within the city limits of Jacksonville,
    Arkansas, which has 28,000 residents
    Approximately 1,000 people live within one
    mile of the site, which is bounded by
    residential areas to the east and south, Little
    Rock Air Force base to the north, and an
    industrial area to the west

•   During this period, herbicides, primarily
    2,4-D and 2,4,5-T, were manufactured at
    the site  TCDD was a by-product of the
    manufacturing process  The drummed still
    bottom wastes generated in the
    manufacturing process were stored on site

•   The Vertac site participated in the 1978
    National Dioxin Survey  TCDD
    concentrations as high as 40 mg/L were
    found In the 2,4-D and 2,4,5-T production
    wastes EPA and ADPC&E began
    Investigations at the site, resulting in the site
    eventually being placed on the  National
    Priorities List (NPL) in 1983. ADPC&E
    issued an order in 1979 which required
    the operators of the site to improve
    hazardous waste handling practices [1].

    During site investigations, TCDD
    concentrations in the 2,4,5-T drummed
    waste were measured as high as 50
    mg/L TCDD concentrations in the 2,4-
    D waste were generally less than 1
    ug/L All of the waste on site, however,
    was classified acutely hazardous waste
    (see the dioxm listing rule of January
    14,1985 (50 FR 1978))

    A Consent Decree was entered into by
    EPA. ADPC&E, and two PRPs In
    January 1982, which required an
    independent consultant to assess the
    management of wastes being stored on
    the site and to develop a proposed
    disposal method  The proposed remedy
    was implemented in the summer of
    1984 by court order over the objection
    of EPA who deemed the proposal
    unsatisfactory [1]

    The remedy specified by the Consent
    Decree required that the site's cooling
    water pond and equalization basin  be
    closed and the sediments from these
    areas be placed in an unlined
    excavated area where waste had
    previously been buried. The remedy
    specified that a French drain, leachate
    collection system, and monitoring wells
    be Installed around the area and
    required the area to be capped.
U.S. ENVIRONMENTAL PROTECTION AGENCY
Offle* of Solid Watt* and Emergency Response
Technology Innovation Office
                                          251

-------
                                                 VfrttcChunWCorponOonSupnfunaSite
                            SITE INFORMATION (CONT.)
   A series of treatabllity studies using Vertac
   wastes were performed In 1985 at the EPA
   Combustion Research Facility in Jefferson,
   Arkansas to determine if a 99 9999% ORE
   was achievable  The tests showed that
   incineration was viable based on this
   criterion, and in 1985 the RP operating the
   site contracted with Environmental Services
   Company (ENSCO) to incinerate the
   wastes

   Later in 1985, EPA and ADPC&E entered
   into an agreement with the RP operating the
   site, under the terms of which the RP
   established a trust fund and a letter of credit
   for environmental remediation

   In 1986, after several unsuccessful trial
   bums, ENSCO left the site  In January
   1987, the RP declared bankruptcy and
   abandoned the site. The trust fund that had
   been established continued to fund remedial
   action through 1993.

   When the site was abandoned, nearly
   29,000 55-gallon drums of still bottom
   production wastes remained on site.
   Approximately 25,600 of these drums
   contained waste from 2,4-D production and
   about 3,200 others contained waste from
   2,4,5-T production. The drums contained
   high concentrations of solvents (for
   example, toluenes and phenols), had an
   average chlorine content of  25%, and had a
   pH In the 2 - 3 range  In addition, 650 tons
   of contaminated sludges, liquids, and solids
   were abandoned In approximately 100 of
   the 190 production tanks that had been used
   in the manufacturing process

   EPA and ADPC&E also discovered that
   many of the drums and production tanks
   were leaking presumably as a result of the
   corrosivlty of the waste and ultraviolet
   degradation.  EPA issued a work order to
   the site which Instructed them to fix the
   leaking tanks and dean up the spills
The contaminated soil at the site was
addressed in a separate operable unit
It was excavated and landfilled in a
Subtitle C facility.

In February 1987, EPA and ADPC&E
initiated an immediate removal action to
mitigate the hazards posed by the
deterioration of the drums  The drums
were placed in 85-, 110-, and 130-gallon
overpack drums, and placed in a
covered storage area.

In 1987, ADPC&E awarded a contract to
MRK Industries using funds from the
trust for the incineration of the waste at
the Vertac site  A trial bum was
conducted from August 30,1990 until
December 10,1990  A second trial
bum was required due to several
problems with the first tnal bum
ADPC&E cited problems with surrogate
spike recoveries for semi-volatile
compounds, data gaps for recorded
parameters, and laboratory QA/QC
procedures as the reasons for a second
tnal bum  [1]

In September 1990, Records of
Decision (RODs) were signed for the
Jacksonville Municipal Landfill and the
Rogers Road Municipal Landfill, which
called for the excavation and
incineration at the Vertac site of
contaminated soils. Both landfills were
located in Jacksonville, approximately
five miles from the site and had been
contaminated by waste from the Vertac
site  A total of 1,027 tons of landfill soil
and debris was transported to Vertac
and Incinerated.
U.8. ENVIRONMENTAL PROTECTION AGENCY
Offlct of Solid Watt* and Emergency Raspont*
Technology Innovation Offtct
                                          252

-------
                                                   V»rtK C/wmfc*/ Corporation Supwfuntf Site
   On May 29,1991 a motion was filed by
   several organizations for a preliminary
   injunction to halt the incineration of the
   drummed hazardous wastes at the site  The
   organizations claimed that the incineration
   would cause irreparable damage to the
   community of Jacksonville. After court
   testimony, the injunction was dissolved and
   incineration was allowed to continue

   The second tnal bum was conducted
   October 9 through 11,1991 and the results
   were approved by ADPC&E  Incineration of
   the 2,4-D waste began in January 1992

   On October 28,1992, the Government
   Accountability Project (GAP) filed a petition
   in Federal District Court requesting a
   temporary restraining order and temporary
   injunction against burning the 2,4,5-T waste
   at the Vertac site.  On October 29,1992, the
   court  granted the restraining order,  but
   allowed ADPC&E five days in which they
   could bum 2,4,5-T waste to gather
   emissions data.

   On October 29 through 31,1992, ADPC&E
   incinerated approximately 80 drums of
   2,4,5-T waste  Data gathered from the
   three  day test showed dioxm and furan
   emissions to be approximately the same as
   emissions from the earlier 2,4-D
   incineration

   On November 16 and 17,1992, ADPC&E
   conducted three stack tests using Method
   23 in 40 CFR part 60 to quantify emissions
   of dioxins and furans emitted during 2,4,5-T
   incineration. Results showed that mass
   emissions of dioxins and furans as TCDD
   equivalents were less than detected during
   the second trial bum  ADPC&E resumed
   the incineration of the 2,4-D waste following
   the completion of the stack tests.

   ADPC&E managed the 2,4-D Incineration
   until June 1993 when the remedial contract
   was terminated because the funds from the
   trust had been exhausted. EPA took over
   responsibility for the site and resumed the
   incineration
•   Although the results of the incineration
    test with the 2,4,5-T waste
    demonstrated that the emissions were
    similar to those from the incineration of
    the 2,4-D waste. EPA decided in 1994
    to transport the 2,4,5-T waste off site for
    incineration. The decision to incinerate
    the 2,4,5-T waste off site was based on
    (1) the fact that on-srte incineration
    would have been more expensive and
    (2) ADPC&E's desire to finish the
    remediation of the site more quickly.

•   On-srte incineration of the 2,4-D waste
    at Vertac concluded in September 1994
    Subsequently, approximately 3,200
    drums of 2,4,5-T waste were
    transported to the Aptus incinerator in
    Coffeyville, Kansas until March 1996.
    The incineration of this waste was
    completed in Apnl 1996.

 •   MRK processed 9,804 tons of waste
    between January 1992 and September
    1994

•   Off-site disposal of 33,972 drums of
    incinerator salt and ash residuals was
    completed in December 1996  The
    residual was disposed of at the Highway
    36 Land Development Company,
    Subtitle C facility, in Deer Trail,
    Colorado [2]

Regulatory Context:

•   In 1983, the Vertac site was placed on
    theNPL.

•   Remedial activities at the site were
    conducted under the provisions of two
    Remedial Actions.

•   The selected remedy was consistent
    with the Comprehensive Environmental
    Response, Compensation, and Liability
    Act of 1980 (CERCLA), the Superfund
    Amendments and Reauthorization Act
    of 1986 (SARA), and the National
    Contingency Plan (NCP) 40 CFR Part
    300 [3].
U.8. ENVIRONMENTAL PROTECTION AQENCY
Offlo* of Solid Wwte and Emergency RMpons*
Technology Innovation Offlo*
                                          253

-------
                                                 Vwttc Cftwnfear Corporation StfMfftntf SH»
   The DREs were set in accordance with
   RCRA standards, at 40 CFR part 264,
   subpartO
Remedy Selection: On-stte incineration
was selected as the remedy for drummed
waste at the Vertae Superfund site based on
treatabihty study results and long-term
economic considerations
                                  Table 1.  Timeline [I
1948- January 19B7
1878
1963
1984- July 1986
1985
February 1987
August 1990 - Oeeambar 1990
October 9-11, 1991
leWUta»U -1OQ3
MMJmy I We
kanei 1QQA

*lar^imhaf "IflfM

March 1996
December 1996
Vwtac site manufactured hertDfcides
National Dtorin Survey
Site placed on the NPL
Proposed Interim remedy knplemerrted
Indneraeon plot studes warn conducted
Emergency drum ovwpecklng
First Trial Bum
Second TiW Bum






Transport to off-rtte tnuliMfllor WBB comptotod
Off-site dteposal of residual salt and ash vwscompteted
Site Management: EPA-lead

Oversight:  ADPC&E

Remedial Project Manager
Philip Allen
U.8. EPA Region 6
1445 Ross Avenue
Dallas, Texas 75202-2733
(214) 665-8516
State Contact:
Mike Arjmandi
Arkansas Department of Pollution Control &
Ecology
P O. Box 8913
8001 National Drive
Little Rock, Arkansas 72219-8913
(501) 682-0852

Treatment System Vendor:
MRK Industries
Address NA
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waits and Emergency Reeporwe
Technology Innovation Office
                                         254

-------
                                                  Vwttc Gftemfcaf Corporation Supertax* SA»
                                MATRIX DESCRIPTION
Type of Matrix Processed Through the
Treatment System: Still-bottom waste from
the production of 2,4-D and 2,4,5-T, soil and
debris
    The composition of the drummed waste
    varied, but most of the drums contained
    a mixture of solids, liquids, and sludges
    11]

    Soil and debris from off-site landfills
Primary Contaminant Groups: Oioxinsand
Volatile Organic Compounds

•   The contaminants of greatest concern were*
    TCDD; chlorinated benzene, chlorinated
    phenols; 2,4-D, and 2,4,5-T
    The maximum concentrations detected
    in the still bottom waste in mg/L were
    TCDD (50); chlorinated benzene (MA),
    2,4-D (NA), and 2,4,5-T (NA)
The matnx charactenstics of the drummed still bottom waste that most significantly affect cost or
performance at the site and their measured values are presented in Table 2
                             Table 2  Matrix Characteristics
PH
Average chlorine contort
Average heat content (solids)
Maximum hart content (organic Iqukte)
2-3
25%
7,500 BTU*
10.500 BTU/to
Incineration system including

•  Waste feed system
•  Rotary kiln
•  Secondary combustion chamber
Pretreatment (solids)*

•   Suction lance
•   Two-stage shredder
•   Mixing with corncobs

Post-Treatment (air)

•   Cyclone separator
•   Wet scrubbers

Post-Treatment (water),

•   Carbon adsorption
•   Evaporation
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watte and Emergency Response
Technology Innovation Office
                                         255

-------
                                                  Vurtac Chemical Corporation Supmfund SK»
                   TREATMENT SYSTEM DESCRIPTION (CONT.)
            rintion and ODMfttlon
   Drums were delivered to the feed
   preparation building on a flatbed truck,
   which could carry approximately 12 drums
   The drums were removed from the truck
   and placed on a rolling conveyor, where the
   drums were weighted and subsequently
   transported into the feed preparation
   building. The building was maintained at a
   negative pressure to prevent fugitive
   emissions, air from the building was
   channeled to the SCC to destroy
   contaminants released during waste
   handling

   In the building, two operators, in Level A
   personal protective equipment, opened the
   overpacks and the drums  Theoverpacks
   were triple-rinsed in accordance with 40
   CFR § 261.7, they were later used for the
   storage of salt generated by the incineration
   system.  The overpack rinsate was treated
   by carbon adsorption before discharge to
   the scrubber water evaporation unit The
   operators used a suction lance to remove
   liquid organtcs from the drums which were
   then pumped to a storage tank Once the
   liquids were removed, the drums were
   placed on an elevator, which took them to
   the top of a two-stage shredder

   As the drums entered the shredder,
   pulvenzed corncobs were added  The
   corncobs served as a drying agent, which
   absorbed any liquids liberated from the
   drums during shredding. The first stage of
   the shredder broke the drums into large
   pieces. The pieces then dropped to the
   second stage of the shredder and were
   further broken into 1-Inch pieces.  A
   collection pan below the shredder was
   designed to capture liquids which leaked
   from the process.

   The shredded material was transported by
   an enclosed drag chain conveyor to a
   weight hopper. The conveyor was covered
   with a nitrogen blanket to purge oxygen
   from the area  The conveyor assembly was
   also perforated to allow for the drainage
   of excess liquids. From the weight
   hopper, the material was transported to
   the incinerator by a screw auger
   conveyer The liquid organics in the
   storage tank were fed to the incinerator
   through a liquids nozzle

•  The incineration facilities were placed
   on a 90-by 160-foot temporary
   foundation that was sloped to the center
   to collect releases of wastes and
   stormwater. The kiln was 38 feet in
   length, had an outer diameter of 7 feet,
   and was lined with high-temperature
   refractory brick. The optimal throughput
   of contaminated feed was
   approximately 5,000 pounds per hour
   with a corresponding waste residence
   time of 1  hour

•  The kiln was rated at 50,000 BTU/hr,
   and was fueled by natural gas The
   average kiln operating temperature was
   2,000°F, and it rotated at a rate of 30
   revolutions per hour. The waste
   residence time was approximately 40
   minutes

•  Residual ash from the kiln was collected
   in an ash bin and later stored In drums.
   Off-gas from the incinerator was routed
   to two parallel 8-foot-diameter cyclone
   separators to partially remove
   particulates. Removed particulates
   were recycled to the waste feed and re-
   incinerated

•  Gases from the cyclone separator were
   routed to the SCC for further
   combustion of volatilized contaminants
   The operating temperature of the SCo
   was approximately 2,200°F. The SCC
   had a length of 38 feet, a diameter of 7
   feet, and was lined with high
   temperature refractory brick. The SCC
   was fueled by natural gas
U.S. ENVIRONMENTAL PROTECTION AQENCY
Office of Solid Waste and Emergency Response
Technology Innovation Offict
                                          256

-------
                                                    Vertac Chamlcal Corporation Suparfund SH*
TEATME
                                             DESCRIPTION (CONT.)
Sv«tem Description and Oo6ratlon fCont.)

•   The exhaust gas from the SCO was then
    channeled to the system's spray drier to be
    cooled After passing through the spray
    drier, the exhaust gas was drawn through a
    baghouse assembly; the baghouse
    assembly contained four individual
    baghouses in a two-by-two parallel
    configuration  The system allowed two
    baghouses in series to be in operation while
    the parallel system was cleaned  Following
    the baghouses, a ventun scrubber and a
    fiberglass reinforced vinylester baffle
    absorption scrubber removed additional
    particulates and acid gases from the gas
    The spray drier, baghouse assembly,
    ventun scrubber, and absorption scrubber
    were designed to achieve a 95% parbculate
    removal efficiency and a 99% add gas
    removal efficiency for hydrogen chlonde
    prior to atmospheric discharge [5]

•   The quench and ventun scrubber sections
    required a water flow rate of approximately
    300 gallons per minute (gpm) and the
    absorption scrubber required 600 gpm. The
    scrubbing system was fed with re-circulated
    water which was previously  fed through a
    pH controller. The pH controller analyzed
    the pH of the water in order to control the
    feed rate of the sodium hydroxide used to
    neutralize the acid gases
                              •   The wastewater blowdown from the
                                 system contained sodium chloride salts
                                 and ash residue  The blowdown stream
                                 was controlled automatically by a liquid
                                 level control in the recirculation tank,
                                 which maintained the stream at
                                 approximately 40 gpm  Make-up water
                                 was provided to the system at a rate of
                                 120 gpm to replace water lost through
                                 quenching and evaporation

                              •   The wastewater blowdown was
                                 discharged to a carbon adsorption
                                 system to remove organics The
                                 discharge from the carbon system was
                                 passed to :-n evaporation system where
                                 the water was evaporated, leaving
                                 sodium chloride salts The salts were
                                 collected in drums  The water used in
                                 the air pollution control system (ARCS)
                                 was recycled within a closed system

                              •   Combustion gases were drawn through
                                 the incinerator and ARCS by an induced
                                 draft fan and were exhausted through a
                                 40-foot fiberglass reinforced vinylester
                                 stack.

                              •   Incinerator residual and ash were
                                 disposed of off site in a Subtitle C
                                 hazardous waste disposal facility A
                                 Subtitle C facility was required because
                                 the wastes fed to the incinerator were
                                 listed hazardous wastes, and therefore
                                 all residuals from the incineration
                                 process were also classified as
                                 hazardous wastes.
                         Table 3  Summary of
Residence Time
System Throughput
rain Temperature
40 minutes
NA
2,000°F
U.S. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Waste and Emergency Response
Technology Innovation Office
                                           257

-------
                                                  Vrnlac Chemlcfl Corporation Supfrfund Stte
                       TREATMENT SYSTEM PERFORMANCE
   All of the material on site was considered
   acutely hazardous waste and was treated as
   listed hazardous waste under the "derived
   from* provision of the dioxm listing rale of
   January 14,1985,50 Federal Register, pp.
   1978-2006 [3].

   Although the contents of all of the drums
   were incinerated on or off site, an action
   limit was established which corresponded to
   a 4.2 x 10* excess lifetime cancer nsk over
   a 3 - year exposure, and a 9 9 x 10*9 excess
   lifetime cancer risk over a 70-year lifetime
   exposure
                             A ORE of 99.9999% was required for
                             the POHCs in each dioxin listed waste
                             that was fed to the incinerator

                             The delisting critena for incinerator ash
                             was set at 0 004 parts per tnllion for
                             dioxins
•  The two trial bums conducted at Vertac
   were designed to operate the incineration
   system at conditions that would reflect worst
   case destruction and removal of all
   constituents of concern
   Hexachlorobenzene was selected as the
   POHC for both trial bums  The reported
   ORE for hexachorobenzene is included in
   Table 4.

•  The incinerator at Vertac operated within the
   operating limits established during the tnal
   bum, signifying that all cleanup
   requirements established were met
                             The AWFCOs and each parameter's
                             respective percentage of the total
                             number of cutoffs during the operation
                             of the incinerator are shown in Table 5
                             Values for operating parameters during
                             the trial bum are shown in Table 6
                             Information on the values of these
                             parameters during post-tnal bum
                             operation was not available
       Table 4. A
Destruction and Removal
from the Second Trial Bum 16
U 8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Watt* and Emergency Rttponse
Technology Innovation Offlct
                                          258

-------
                                                Vortac Chemical Corporation Superfund Site
                  TREATMENT SYSTEM PERFORMANCE (CONT.)
                       Table 5. Automatic Waste Feed Cutoffs [7,11]
Minimum stack gas O, concentration
Maximum stack gas CO concentration (O 7% oxygen)
MMmum kttn exit temperature
Minimum SCO extt temperature
MWmum Win draft
MHmum SCO draft
Minimum scrubber Iqrfd pH
Maximum stack gas flow rate
MWmum Venturi scrubber pressure differential
Minimum brine flow to spray dryer
87%
SOppm
1,604'F
2^04'F
0 015 Inches w.c
0015 Inches we
26
29,750 acfm
210 inches we
no flow
75
4
3
B
7
4
1
<1

-------
                                                   Vertoe Chemical Corpontion Sup. /unc/Sfte
                             TREATMENT SYSTEM COST
   ADPC&E contracted with MRK Industries to
   acquire and operate the Incinerator at the
   site  When EPA took responsibility for the
   site in 1993, they contracted with URS
   Consultants, Inc. (now URS Greiner) to
   provide oversight at the Vertac site
   ADPC&E initially managed the Vertac
   site using the $10.7 million which was
   provided by the established trust fund
   and letter of credit  When this money
   was exhausted, EPA took over
   management of the site [3].
   The actual cost of on-ate incineration of
   $31,700,000 was reported in terms of
   capital costs and operation and
   maintenance costs.  The actual capital costs
   for the incineration system were
   approximately $21,000,000 and actual
   operation and maintenance costs totaled
   approximately $10,700,000 for 32 months of
   operation. A total of 9,804 tons of still-
   bottom waste and soil were incinerated
   This corresponds to a total unit cost for
   incineration of $3,200 per ton.
Coat Pate Quality

•  Actual capital and operations and
   maintenance cost data are available
   from the treatment vendor and EPA for
   this application
                      OBSERVATIONS AND LESSONS LEARNED
   The high cost per ton of waste incinerated
   was attributed to waste feed limitations
   due to the nature of the waste,
   specifically, high chlorine content and low
   PH[8]

   The contract cost of incinerating the 2,4,5-
   T waste off-site was $2/lb of dioxm waste
   The total cost amounted to approximately
   $4,000,000 for 1,200 tons Of 2,4,5-T
   waste [11]
•   The variable nature of the waste feed
    slowed the incineration project  The
    inconsistency of the waste and the
    difference in heat content between the
    solid and liquid phases of waste,
    necessitated constant adjustment of the
    feed rate

•   Electrical surges caused unexplained
    shutdowns of the Incinerator. Surge
Publle Invoh/MMnt
  suppressors were installed to the
  input/output racks of the incinerator
  control system Following installation, the
  number of shutdowns were reduced [12]

  Originally, calcium hydroxide solution was
  used as the neutralizing agent in the
  APCS  However, the subsequent calcium
  chloride residual in the brine solution
  which was recirculated through the APCS,
  clogged the spray drier  Therefore the
  neutralizing agent was changed to sodium
  hydroxide, which did not cause clogging
  problems

  A video camera was installed in the
  shredder to allow operators to detect
  potential problems before the shredder
  jammed [5].
  A second CEM system was installed to
  allow daily calibration of the CEMs to
  occur without an incinerator shutdown
  The second system allowed incineration
  to continue uninterrupted during
  calibration [5]
U.8. ENVIRONMENTAL PROTECTION AGENCY
Office of Solid Weete and Emergency Reeponte
Technology Innovation Office
                                           260

-------
                                                   Vertac Ctomkxl Corporation Superfund Site
    The public expressed a great deal of
    concern pertaining to the Vertac site Two
    temporary restraining orders were filed to
    stop the incineration project  Theanti-
    incineration campaign was led by
    Greenpeace and the Government
    Accountability Project  These groups felt
    that the citizens of Jacksonville would be
    put at risk from the emissions of the
    incinerator  The first restraining order was
    dissolved after court testimony
    substantiating the low-risk involved with
    operating the incinerator The second
    restraining order temporary prevented
    the incineration of the 2,4,5-T waste,
    which was later incinerated off site [9].
  Pro-incineration groups expressed
  concern over the amount of time it was
  taking to start the project. These groups
  wanted the EPA to start and finish the
  project as quickly as possible [9].
1.  Vertac Incineration Project - Background
    and Site History. Provided by U.S EPA,
    Region VI.

2   Suoerfund Site Status Summaries.
    U.S EPA, "Vertac, Inc.,"
    http.//www epa gov/earth1 r6/6sf/vertac,
    April 30,1997.

3   Superf und Record of Decision. Vertac,
    Incorporated, Jacksonville, Arkansas, June
    1993

4.  Action Memorandum. Request for Approval
    of Non-Time Critical Removal Action Ceiling
    Increase for the Vertac Chemical Core Site.
    Jacksonville. PulasM County. Arkansas.
    April 7,1992

5.  Petition for a Regulatory Amendment and
    Exclusion for Four Waste Byproducts at the
    Vertac Site in Jacksonville. Arkansas.
    Arkansas Department of Pollution Control &
    Ecology.

6.  Report on Trial Bum Testing. Clean Air
    Engineering, Decembers, 1991

7.  Impact of Reducing the Vertac Site
    Contractors fVSC} Incinerator Stack Oxygen
    Interlock Level at the Vartac CERCLA
    Incinerator Located in Jacksonville.
    Arkansas. Draft. URS Consultants,
    October 15,1994.

8   Personal Communication, Mr Rick
    Ehrhart, March 18,1997.

9.  Personal Communication, Mr Rick
    Ehrhart, Apnl 1,1997

10. Risk assessment for Vertac Off Site
    Residents as Impacted bv Burning
    Hazardous Waste on Vertac Site.
    Texas/Oklahoma Remedial Section,
    Suoerfund Branch, Hazardous Waste
    Division, U.S EPA, June 24,1993.

11  Personal Communication, Mr Rick
    Ehrhart, June 30,1997

12  Vertac Project Operations Closure
    Report. URS Consultants, Inc, June
    1997.
U.S ENVIRONMENTAL PROTECTION AGENCY
Office of SoHd Wait* and Emergency Response
Technology Innovation Office
                                          261

-------