EPA-542-X-95-002
                                             May 1995
FEASIBILITY STUDY ANALYSIS, VOLUME II:

                SITE SUMMARIES
                    April
                H 21,
   1995
                     Prepared for:
                         and
       Technology
Office of Solid Waste
    U.S. Environmental
            410 M S
         Washington
Innovation Office
    Emergency Response
  Protection Agency
 :reet, S.W.
  D.C.  20460
            Environmental Management Support, Inc.
                 8601 Georgia Ave., Suite 500
                Silver Spring, Maryland 20910

-------

-------
 7.      How did the cost(s) compare to standard technologies?             [
               '                      ii                '       -'••,!•••
                  Cost Estimates for IRAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)    i
8.
10.
   Oo
   O'
Alternative
RAA-1
RAA-2
'!
!•
I
Standard Technology
No action/monitoring
Sheet piling vertical barrier/
dewatering/water treatment/soil
excavation/dff-site incineration/
monitoring '
Estimated Costs
3 Criteria
$755,000
$187,351,000
I
f
9 Criteria
$755,000
$242,931,000
       If a standard technology was chosen, why?

       A standard technology was not chosen.
                                      :hosen, why?
9.      If an innovative technology was

       Alternative RAA-6 was selected.; It includes lowering the water table! by three feet and using
       in situ soil venting tosremediate Unsaturated soils. Saturated soils and groundwater would be
       remediated by injecting groundwater fortified with nutrients and an oxygen source into the
       contaminated zone to stimulate biological degradation of contaminants.  It was selected
       because it permanently removes a high percentage of contaminants.  It achieves remedial goais
       in a fairly short period of time Mlfoile minimizing impacts to the community.  This results from
       employing in situ techniques with little disturbance of the site. It satisfies the preference for
       treatment.  The feasibility of the 'biotreatment component is based on bench-scale tests.  The
       applicability of this technology will be investigated by performing more extensive pilot tests.

       RAA-1 was eliminated because ;ijt would not provide protection to human health and the
       environment. RAA-2 would meet state MCLs and permanently remove contaminants from the
       site, but would  have disadvantages, such as high cost and a long perk>d of remediation. RAA-
       3 was eliminated because significant quantities of contaminants woukj be left at the site,
       remediation relies  on natural flushing of the aquifer, and exposure pathways exist that would
       provide inadequate protection to | human health and the environment. Moreover, RAA-3 would
       have a relatively high cost for the level of protection provided. RAA4 would be cost-
       effective, but cleanup goals would not be reached  for many years. RAA-5 would provide
       similar levels of protection as Rj
-------
Disposal:
Excavation, RCRA landfill (on-site and off-site)
Was an innovative technology considered in the FS?  If so, which technology?

Innovative technologies considered during the identification and screening of technically
feasible technologies were:                                 -,     •      ••

Biological treatment:   Landfarming, contained solid-phase aerobic degradation, anaerobic
                      degradation, in situ biodegradation
Chemical treatment:    In situ hydrolysis, in situ oxidation, in situ reduction, in situ soil
                      venting (vapor extraction)
Thermal treatment:     On-site thermal desorption, pyrolysis
What was the cost estimate for the innovative technology?

During the initial screening process, in which technically feasible technologies are identified ;
(prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
estimated  costs then are recalculated during evaluation by the nine criteria established by the
NCP: long-term effectiveness and permanence; short-term  effectiveness; compliance with
ARARs; protectiveness of human health and the environment; reduction in contaminant
mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
community acceptance.                                                               ,
                         v                   '             ,        '-.'.•
          Cost Estimates for RAAs That Include Innovative Technologies
                     (selected remedial alternative is in bold)                          '
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
Innovative Technology
Partial soil excavation/on-site thermal
desorption/monitoring
In situ venting (vapor extraction)/
monitoring
Sheet piling vertical barrier/dewatering/
water treatment/in sini soil venting
(vapor extraction)/monitoring
In situ soil venting (vapor extraction)/
ground water extraction/air stripping/
in situ biodegradation/monitoring
Estimated Costs
3 Criteria
$10,044,000
$2,312,000
$12,166,000
$4,507,000
9 Criteria
$10,321,000
$1,977,000
$11,399,000
$4,507,000
                                       -2-
                                                                                          063

-------
                                                                       ;
                             Applied Environmental Services
                                  (aka  Shore Realty Site)
                                            OU-1
                         Glenwood landing, Nassau County, New York
                                   i i       Region 2

 GENERAL SITE INFORMATION
                       . - --	   i
                    - -. -       "      ML

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?
        Maximum concentrations of principal
        contaminants were:
        Soil (mg/kg)

        Methylene Chloride    20
        Benzene              0.005
2.      What volume of material is to Ire
        remediated?    *•
       The volume of material to be remediated
       included:                    !;
               105,000 cubic yards of soil
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
10/84
10/86
4/17/91.
6/24/91
             Background

PRP-lead        !
PRPs:  Shore Reality, over 100 third-party
       defendants;
FS prepared by:  Roux Associates, Inc.
3.     What type of site is this?
               •  '        '          1i         ' '-  "         .  •       '.>•   :          .   •'.
       Chemicals and Allied Products,,: A former petroleum, gasoline, and solvent chemical facility,
       which more recently has been used as a hazardous waste storage facility and chemical waste'
       blending facility.                                               '
TECHNOLOGY SELECTION
                 . '     '           .!!   . .     •-  '      '-   •'     '   I:-    !"'"-'.-   "•   '  •
4.      What standard technologies were considered for selection in this FS*
                                   i!         '    •    '   •       '      t ...-.•   •.
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:             ;                                 f
                                   I i   '   • •              -           ''t*      • •

       Containment:         Capping  (synthetic, asphalt, or layered), vertical barriers (sheet piling,
                            slurry w^lls)                              |
       Chemical treatment:    Solidificjation/stabilization (cement  based, silicate based, thermoplastic)
       Thermal treatment:     Incineration (rotary kiln,  circulating fluidized -bed, multiple hearth,
                            mobile)                                  I
  062
                                            -1-

-------
               Single vs. multistep treatment
               Preference for treatment and alternative treatment technologies (vs. containment)
16.    How are alternatives compared?

       Alternatives were compared by: comparing their costs with excavation and .treatment/disposal;
       the time to remediate the site; complexity of the remediation technology; site space controls;
       and spread of contamination from excavation and stockpiling.  Remediation time for soil
       flushing, determined through partition/pore volume flush models, was considered questionable
       because soil and contaminant parameters are difficult to quantify. Soil flushing was also
       compared to the other technologies as unpredictable based on hydrogeological complexities.
17.    What technical considerations had to be considered in the selection of a remedy? Were
       technical considerations primary in the selection of the remedy?

       Technical considerations primary in the selection of an alternative were the sandy nature of the
       site soil and the proximity of the underlying water table. The chosen technology has been
       proven highly successful in removing volatile organics, particularly from sandy soil matrices
       such as those found at the site.  Further, it is expected that the technique will volatilize and
       enhance biodegradation of semi-volatiles thus reducing their concentration below action levels.
       The proximity of the water table to the contaminated soil, and the potential for water table ,
       fluctuations, dictated that a solution reduce the toxicity and volume of contaminants rather than
       merely containing them.  Thus alternative RAA-SC-2, which proposed capping, was
       considered insufficient.
                                                                                                061
                                               -D-                 ,                       "

-------
12,
13.
                                   ||                     _             V ' ,
        SC-6 (thermal desorption) because excavation and stockpiling would cause fugitive dust and
        run-off problems.  Implement^bility was also a factor in eliminating RAA-SC-3 and RAA-SC-
        5 that included soil flushing because of the impact on ground water flow and the difficulty in
        implementation compared to SVE. RAA-SC-6 was affected because of the lack of space for
        stockpiles.
 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was thai
ARAR?  What risk level was selected to establish cleanup goals?   j
                            [\                   '.  •.          4' •           *
No chemical-specific ARARs for soils were identified.  The action flevels, which were based
on New Jersey Soil Action Levels set by the New Jersey Department of Environmental
Protection (NJDEP), were considered cleanup goals.               j
Contaminant j
Total volatile organics
Total semi-volatile
organics
i
Cleanup Level
1 ppm
10 ppm
ARAR or Other Basis
i NJDEP
NJDEP
       For carcinogens an excess upper bound individual lifetime cancer rijsk of between 10"4 to 10"6
       was acceptable.  For non-carcinogens a Hazard Index less than or e^qual to 1.0 was acceptable.
Was the innovative technology'eliminated because of the cleanup goals? Could the standard
technology meet the cleanup gi?als?                             i

Although failure to meet cleanup goals eliminated innovative technologies during the initial
screening, no innovative technologies were eliminated during the three-criteria or 9-criteria
screening because of the cleanup goals. Many of the innovative technologies were considered
to have the potential  for leaving soil contaminants in the soil at concentrations above NJDEP
action levels. Only thermal desorption was expected to remove the (contaminants of concern to
near detection limits.  Standard technologies considered would  not itoeet cleanup standards
either.                                                        !
14.
Were treatability studies conducted on the innovative technology or'standard technology?
            '           -  '  - [i              •          .'-'I'
No, but an additional study on soil vapor extraction will be performied during the remedial
design phase.                l                                  '
75.     What measures/criteria were used to compare alternatives?
                                   11       .  ,     '    -       ' •
       The following measures were used to compare the alternatives:

       -      Total cost            i:
              Time to design/constract/operate
              Proven reliability     j
              Capital costs vs. operational costs
 GGO
                                            •• -5-

-------
        •      Radio frequency heating was eliminated because it was considered experimental and
               too costly.                                                           .
        •      In situ vitrification was eliminated because it was considered experimental and tpo
               costly
        •      Critical fluid extraction was eliminated because it was considered experimental and too
               costly                  •
        •      Solvent extraction was eliminated because it was considered as being primarily used to
               treat PCS contaminated soils and sludges.
        •      Dechlorinqtion was eliminated because it was considered as being primarily used to
               treat PCB contaminated soils and sludges.

        Innovative technologies included in the RAAs but eliminated during the three-criteria .screening
        process include:

        •      Biodegradation was eliminated  because of the following reasons:  1) the complex soil
               contamination at the site that would limit the effectiveness, 2) significant reductions in
               toxicity could be achieved only if a diverse microbial population capable of degrading
               the compounds of interest can be maintained, 3) bench and pilot scale tests would be
               required, 4) bioremediation would also require long-term operations  to develop and
               maintain microbial population and, 5) bioremediation was considered too complex and
               experimental.
        •      Land treatment was eliminated because:  1) it is not proven to be effective for the
               degradation of highly  chlorinated aromatic compounds and other organics that are
               resistant to biological  attack, 2) it is not reliable in achieving cleanup standards in soil,
               3) it, requires  spreading and mixing of contaminated soil into areas that are currently
               non-contaminated, 4) it creates a situation where contamination could be spread by
               dust, run-off,  and infiltration, 5) it might not be implementable because of
               environmental regulations, due to the potential to contaminate clean  areas.

        Innovative technologies that were eliminated during the nine-criteria screening and selection of
        a remedy include:

        •      Soil flushing was eliminated due to:  1) it does not reduce toxicity or volume of the
               soil contaminants but only increases the mobility of contaminants to allow collection
               and treatment using groundwater extraction and treatment, and 2) large numbers of
               variables influence soil flushing and there is  uncertainty  in achieving remediation
               objectives quickly.
        •      Thermal desorption was eliminated because:   1) it does not destroy contaminants or
               reduce their toxicity and will therefore require further destruction or disposal, 2) it
               requires excavation and stockpiling that could interfere with plant operations and
               require relocation of roads, as well as require stockpile areas off site, 3) a Part B
               equivalent would be required.
11.    Which of the nine criteria were weighted most highly in selecting the technology?  Did one of
       the nine criteria eliminate the innovative technology from being chosen?  If so, which one?
       Which of the criteria supported the use of a standard technology?

       Reduction of toxicity, mobility, and volume and short term effectiveness appeared to rank the
       highest in selection of the technology.  SVE was estimated to take only one year.  Under
       short-term effectiveness, the short-term impact was considered and helped to eliminate RAA-


                                               -4-.      ••.•••         .  ,          '  .
059

-------
Alternative
RAA SC-6
/
1; .
' ' •-- '- I''-- -" :-., ' ' •' " -
Innovative Technology
Excavation and low temperature thermal
desorption
'Estimated Costs
3 Criteria
!|J/A
!
F
9 Criteria
$4,518,000
7.     How did the cost(s) compare \\o standard technologies?           i
••                                '  . ''               •                '!••••
                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)   '
Alternative
RAA SC-1
RAASC-2
sit
'i
uidard Technology
No action
Capping ;
Estimated Costs
3 Criteria
k/A
N/A
9 Criteria
$319,000
$135,000
8.     If a standard technology was chosen, why?
                                   !!.-"•       '
       A standard technology was not chosen.
10.
                                    !    _               •                  '      -      -
       If an innovative technology wti$ chosen, why?                  •  ['
                                   , I            -           •          . f. .'.•-.
                                    ,          •                        j                    ' ^
       In situ soil vapor extraction (SVE) with activated carbon off gas treatment with disposal of
       residual off-site was selected, for the following reasons: 1) it direcfly reduces the volume arid
       mobility of soil volatile and semi-volatile organic contaminants and may indirectly reduce the
       toxicity of phenolic soil contaminants through enhanced biodegradation, 2) removal of
       contaminants reduces future grpundwater contamination, 3) no shont term risks are produced,
       4) past experience on similar projects has shown SVE techniques tci be successful in removing
       VOCs in sandy soil, 5) it is technically feasible to construct in the i-emediation (lagoon) area,
       6) it is an in situ process and involves no costly excavation and treatment/disposal, 7) expected
       cleanup in one year is said to |se typical, 8) major O&M costs are riot expected.
       If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                ,                         I
                                   ij          •           '•,'•'••  !''•   '•   • '-       •'-
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementabilityj and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include:
  058
               In situ bioremediationwas, eliminated because it was considered applicable only for
               soils below the water liable.            ,
                                              -3-

-------
       What type of site is this?

       Chemicals and Allied Products. A former resin manufacturer.
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                               ,  ,
       Access restriction:
       Containment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Site fencing, deed restrictions
RCRA cap, multimedia cap, asphalt cap
Stabilization/solidification
Incineration
Excavation, on-site landfill, off-site landfill
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
        Biological treatment:
        Phys/Chem treatment:
        Thermal treatment:
In situ biodegradation, land farming
In situ soil flushing, in situ soil vapor extraction
Low temperature thermal desorption
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified •
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been.
        formulated, costs are estimated as part of the three criteria (effectiveness, implemehtability,
        cost) screening process to identify alternatives of sufficient merit to undergo detailed
        evaluation. The estimated costs are recalculated during an evaluation by the nine criteria
        established by the NCP.,                                                         *"''   _ .

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)       r
Alternative
RAA SC-3
RAA SC-4
RAA SC-5
Innovative Technology
Soil flushing
Soil vapor extraction
Soil vapor extraction and soil flushing
Estimated Costs
3 Criteria
N/A •
N/A
N/A
9 Criteria
$499,000
$810,000
$1,016,000
                                               -2-
                                                                                                 057

-------
                                       A.O. Polymer

                                     Trenton, New Jersey
                                           Region 2
 GENERAL SITE INFORMATION
 1.      What were the principal contaminants,
        contaminant levels, and media being
        addressed in this feasibility stiidy?

        Maximum concentrations of principal
        contaminants were:
2.
        Soil (mg/kg)

        Tetrachloroethene
        1,1,1 -Trichloroethane
        Trichloroethene
        Trans-1,2-dichloroethene
        Toluene
        Xylenes(total)
        Ethylbenzene
        Chlorobenzene
        Phenanthrene
        2-Methylnaphthalene
        Chrysene
        Fluorene
        Pyrene
        Naphthalene
        Acenaphthene
        Fluoranthene
        Benzo(k)fluoranthene
        Benzo(b)fluoranthene
        Benzo(a)anthracene
        Benzo(a)pyrene
        Benzo(g,h,i)perylene
        Indeno(l,2,3-CD)pyrene
        Bis(2-ethylhexyl)phthalate
        Di-N-butylphthalate
        Butylbenzylphthalate     >
        Dibenzofuran
        N-nitrosodiphenylamine(l)
                             2.6
                            :32
                             27
                            1.34''
                            iis
                            ;i.5

                            ;9.6
                            10.56
                            :4.2
                            10.74

                            :2.6
                            !0.96
                            JO.88

                            10.59
                            ;0.52
                            ;0.29
                             0.26
                             4-1
                            '0.26
                             0.29
                            !4.6
                             0.12
What volume of material is to he remediated?

The volume of material to be remediated included:
           '               •-  i
                            i-
•      7,500 cubic yards of soil
   056
                                                           Site History
                                              NPL Proposed:
                                              NPL Final:
                                              FS:
                                              ROD:
                     N/A
                     9/1/83
                     4/91
                     6/28/91
             Baickground

EPA Fund-lead ]
PRPs:  A.O. Polymer Corporation
FS prepared by: IICF Technology
       Incorporated
                                             -i-

-------
15.    What measures/criteria were used to compare alternatives?                        .

       The following measures were used to compare the alternatives:

               Time to design/construct/operate
               Preference for treatment (vs. containment)


16.    How are measures compared?

       The chosen alternative was preferred because it employs an innovative source treatment
       technology (low temperature thermal aeration) and thus provides long-term effectiveness and
       permanence. Implementation time also was a factor in the selection process.  For example,
       low temperature thermal aeration would take approximately 1 to 2 years, while another
       technology, in situ soil aeration, was eliminated because it twould take approximately 15 years
       to complete.


17.    What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?

       The site soil's low permeability would preclude the implementation of soil flushing as a
       remedial technology.  In the initial screening, low soil permeability was a primary technical
       consideration in the decision to eliminate this technology.
                                                                                                  055

-------
aquifers
protectic
The "Decision Tree 1
in of future ground wa
' - ".' • ' - • 1 " - • -
' , ' ' { • ' • •
' • ~ [.'"I''
*rocess" was 'used to set soil cleanup levels that ensure
er quality. ARARs were used as input into this model
.....'•-/ . - - ...••••.
Contaminant
Cleanup Level (ppiri)
ARAB or Other Basis
Carcinogens
1 , 1 -Dichloroethene
Trichloroethene
Tetrachloroethene ;
Noncarcinogens
0.1
0.1
0.1
MCLGVMCL"
MCL
pMCLc
'• - . • • 1'. ' '. . •
i • - ' ' I '...;.
1,1 -Dichloroethene ;
Tetrachloroethene ;•
Total xylenes i
0.1
0.1
100
MCLG-MCL
pMCL
pMCLGd-pMCL
• . . ' . ' . ' ' ' • h' - ' •'
              aMaximum Contaminant Level Goal.
              bMaximum Contaminant Level.                          j
              Troposed Maximum Contaminant Level.                 |
              Proposed Maximum Contaminant Level Goal.            ;1
                                   !             '            •     •   i  '-•.-'•    '   -
       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"* to  10"6
       was acceptable.  For noncarcinbgens, a Hazard Index less than or eqjual to 1.0 was acceptable.

                                   -'I I   '       '            ' "    '      *' "      '           '
13.     Was the innovative technology Eliminated because of the cleanup  golals?  Could the standard
       technology meet the cleanup goals?                             j
  .  '           '  '   .           •  '  ii    ' •   .        •   .    -"    ,•'!.-.•'
       Innovative technologies eliminated because of cleanup goals include:              —
          • "      .            •      ii-             "           >•      - i •     •.  . •   '
                                   :\\  ; ' '            '.      |   '       'Jr-  .
       •      In situ soil aeration/vacuum extraction                   ['.'..
                                   !!'                   '            t'  '     :  ,     ' '   ' '
       Standard technologies eliminated because of cleanup goals include: j             '   . " •  ^

       •      None
14.     Were treatability studies conducted on the innovative technology or 'standard technology?
                       '• . '         -<\  "        '•'•..•          ' ,      I •
       No treatability studies  were conducted.                  '         i
054
                                             -5-

-------
       Innovative technologies eliminated during the initial screening include the following:

       •      In situ soil flushing was eliminated because artificial mounding of ground water in the
               area around injection systems can create unusually high natural ground water gradients
               that can move ground water chemical concentrations outward; it is suitable only for
               soils of relatively high permeability, while site soils have low permeability; treatment
               of water prior to reinjection can cause the formation of precipitates that can clog wells
               and the aquifer; and maintenance costs are high.
       •      In situ radio frequency heating was eliminated because it would require a pilot study
               and the cost of the process is very high.
       «      Biodegradation was eliminated because it would  not beeffective for treating site
               chemicals.
       "      In situ vitrification was eliminated because it would not be effective for treating site
               chemicals.                   .                                            ,
       •      Composting was eliminated because it would only be effective for surface treatment
               and therefore would not be appropriate for the depths of contamination at the site.
       •      Steam flushing/thermal stripping was eliminated because it would not be effective for
               treating site chemicals.            ,
       "      Solvent extraction was eliminated because its effectiveness in removing the many
               VOCs present is untested for full-scale operation, 2) the liquid solvent waste stream
               will require treatment resulting in high  operational costs.
       •   .   Freeze-crystallization was eliminated because it must be combined with a separation
               technology to remove contaminants.              •                   •'   •   .   .

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed  analysis include the following:

       •      In situ soil aeration/vacuum extraction was eliminated because it would not achieve
               the low clean-up levels; the time frame for clean-up using soil vapor extraction is
               uncertain; difficult to verify attainment of clean-up levels throughout the soil.
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion? Which of the criteria supported the use of a standard technology?

       The most heavily weighted criteria in selecting.a remedial technology were protectiveness of
       human health and the environment, long term effectiveness, implementability, and reduction of
       toxicity, mobility or volume.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

       Cleanup levels for soil were set to eliminate human health risks associated with the ingestion
       of contaminated ground water and to prevent further leaching of soil contaminants into
                                               -4-,
053

-------
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-SC-1
(SC-1)
RAA-SC-2
(SC-2)
RAA-SC-3
(SC-3)
RAA-SC-4A
RAA-SC-4B
RAA-SC-7
(SC-7)
Standard Technology
No action/ground water monitoring
Deed restrictions/ground water
monitoring/fence maintenance
Demolition! of existing structures/deed
restrictions/multimedia cap
Demolition! of existing structures/
excavation of unsaturated soils/disposal off
site at RCRA facility
Demolition iof existing structures/
excavation of unsaturated and saturated
soils/disposal off site at RCRA facility
Demolition tof existing structures/
excavation of unsaturated soils/on-site
rotary kiln incinerator/on-site disposal of
treated soils
Estimated Costs
3 Criteria
low
low
moderate
\ery high
very high
high to
very high
9 Criteria
$78,000
$101,000
$956,000
eliminated
eliminated
i
$7,531,000 ,
to
$11,076,000
8.
If a standard technology was cfiosen, why?

Off-site disposal was chosen fot some wastes.
9.      If an innovative technology was'chosen, why?

       Thermal desorption was selected because: 1) it will permanently eliminate
       the soil contaminants on the site, 2) reduce continuing migration of s
       ground water, 3) would reach the low clean-up standards set at the
       for remediation.
                                                              soil
                                                              site
    through treatment,
 contaminants into
, 4) short time required
                                    i i
10.     If an innovative technology^ was not chosen, why not? At what stage
       technology eliminated?        ;
                                                               was the innovative
       Innovative technologies could tie eliminated from the remedial technology
       three stages:  during the initial screening; during the screening of the
       effectiveness, implementability,!;and cost; or during the detailed evah ation
                                                                    selection process at
                                                               three criteria of
052
                                              -3-

-------
Disposal:
Excavation, RCRA landfill
Was an innovative technology considered in the FS?  If so, which technology?

Innovative technologies considered during the identification and screening of technically
feasible technologies were:

Biological treatment:   Biodegradation, composting                    .
Phys/Chem treatment:  Vapor vacuum extraction, solvent extraction, in situ soil flushing
Thermal treatment:     In situ vitrification, steam flushing, thermal stripping, radio frequency
                      heating, ex situ low temperature thermal aeration, pyrolysis
What was the cost estimate for the innovative technology?                              •

During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
formulated, costs are typically estimated as part of a three-criteria screening process
(effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
evaluation. In this case, no specific costs were generated; cost categories (e.g., high* low)
were used instead. The estimated costs were calculated during an evaluation based on the nine
criteria established by the NCP. RAAs presented parenthetically represent alternative
designations in the ROD.

         Cost Estimates for RAAs That Include Innovative Technologies
                     (selected remedial alternative is in bold)
Alternative
RAA-SC-5A
RAA-SC-5B
(SC-5)
RAA-SC-6
(SC-6)
Innovative Technology
Demolition of existing structures/
excavation of unsaturated soils/low
temperature thermal aeration/on-site
disposal of treated soil
Demolition of existing structures/
excavation of saturated and unsat-
urated soils/low temperature thermal
aeration/on-site disposal of treated soil
In situ soil aeration/vacuum extraction
system/monitor/fence
Estimated Costs
3 Criteria
moderate to
high
moderate to
high
high to very
high
9 Criteria
eliminated
P
$3,553,000
$3,946,000
                                       -2-
                                                                                    051

-------
                                   tfnion Chemical Co., Inc.
                                        South Hope, Maine
                                             Region 1
  GENERAL SITE INFORMATION
  1.      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?        ;;

         Maximum concentrations of principal
         contaminants were:       ~.  [i
         Soil (mg/kg)

         1,1-Dichloroethene    4
         Trichloroethene       46
         Tetrachoroethene      600
         Xylene               3,600
  2.      What volume of material is to be
         remediated?
                                                                   Site History
                                                      NPL Proposed:
                                                      NPL Final:
                                                      FS:
                                                      ROD:
                                                                   Hi ckground
                                                      PRP-Jead
                                                      PRPs:  Union Chemical
                                                             many others
                                                      FS prepared by:
        The volume of material to be Remediated included:

        »      1,500 cubic yards of soil
                                   L I , ,

3..     What type of site is this?     >;

        Chemicals and Allied Products!  A former paint stripping and solvent


TECHNOLOGY SELECTION

4,      What standard technologies were considered for selection in this FS?

       Standard technologies considered during th? identification and screening of technically feasible
       technologies were:
        Access restriction:
        Containment:
050
                             Site security, fencing, deed restrictions
                             Capping (clay, synthetic, multimedia, asphallt/concrete,
                             single/multilayer), grout injection, grading, rcvegetation
       Chemical treatment:    Neutralization, oxidation, reduction, chemica fixation, polymerization,
                             solidification,  stabilization                             .           '
       Physical treatment:     Ambient temperature aeration, on-site storage, off-site storage
       Thermal treatment:     Incineration (rotary  kiln, multiple, hearth, high-pressure boilers,
                             infrared, fluidized bed, fume, catalytic, circulating bed combus'tor)

                                .  ,ii              .   .   '     '.     -[-....-...••
                               .    j ..'••'•  -1-   .-        '         i-    .
      4/85
      10/89
      12/17/90
      12/27/91
       Company and
   not listed
Canonic Environmental
                                                                        manufacturing company.

-------
Were treata
                  bility studies conducted on the innovative technology or standard technology?

       No treatability studies were carried out.  It was suggested that treatability studies would be
       necessary if any of the innovative technologies were chosen.


15.    What measures/criteria were used to compare alternatives?             ,

       The following measures were used to compare the alternatives:


               Total cost
               Proven reliability
               Long-term O&M
               Number of vendors
               Time to mobilize treatment equipment


 16.     How are alternatives compared?

        The most expensive alternative is incineration, followed by solvent extraction  and     ^






         there are fewer vendors than for the other technologies. All of the treatment technologies
         (incineration,  solvent extraction, S/S) would require mobilization  demobilization,™^_
         Implementation of sediment/soil treatment units, which may require a greater lead time for

         remediation.                    ,'                        ;


  17     What technical considerations had to be considered in the selection of a remedy?  Were
         technical considerations primary in the selection of the remedy'
   Se  EPA decided that disruption of the wetlands would be necessary and all of the action
   ^^SeJwedai^diauptioo-.tod restoration.  Technical considerations were not
   primary in the selection of a remedy at this site.
                                                                                            049
                                           -6-

-------
                           •'"'!''      "              '
        Innovative technologies eliminated daring the detailed analysis include:

        "      On-site solvent extraction (RAA-5) was eliminated because there would be short-term
               risks to workers during remediation, wetlands must be restored following excavation,
               treatability studies would be required, and the natural organics in the wetland soils
               would have to be replaced for suitable wetland fill.  In addition, it is more costly than
               the selected alternative, it is  and less implementable than the selected alternative
               because obtaining competitive bids on the solvent extraction unit may be difficult
               because there are fewer vendors, and mobilization may require a greater lead time than
               the selected remedy.  • i,  •             .                   1
11:
Which of the nine criteria were weighted highest in selection of the technology? Did one of
the nine criteria eliminate the innovative technology from being chosen? If so, which one?
Which of the criteria supported the use of a standard technology? i

For those alternatives that were protective and attained ARARs, the!most heavily weighted
criteria in selection of a remedy were cost and implementability.  Except RAA-1 (No Action),
all RAAs were protective of human health and the environment and met all ARARs.
Implementability and cost were the most important criteria in eliminating solvent extraction
and supporting on-site disposal.          _                       ;
12.
What clean-up goals were selected. If the clean-up goal was based on an ARAR, what was
that ARAR? What risk level was selected to establish clean-up goals?

Clean-up goals were based on ecological risk assessments that were!established to be
protective of Middle Marsh species.                           •   f   .
For care
was accc
acceptab
Contaminant
Non-Carcinogens:
PCBs Wetlands
PCBs Terrestrial
PCBs Aquatic
.



Clean-up Level

15 mg/kg
15 mg/kg
19.5 ug/gm
\ ARAR or Other Basis
,!
i
j Mean Interim Sediment
I Quality Criterion
'Mean Interim Sediment
1 Quality Criterion
i Sediment Quality
; Criteria
inogens an excess upper bound individual lifetime cancer risk of between ICT4 to W6
jptable. For non-carcinogens a Hazard Index (HI) less than lor equal to 1.0 was
le. •' •• ; . ... , , •' i: , • .; ,, : .
- •• , r '
-: • • • .' ' , '['•'• -
13.     Was the innovative technology eliminated because of the clean-up goals?  If a standard
       technology \yas chosen, could it meet the clean-up goals?          ]
048
       Innovative technologies eliminated because of clean-up goals include in situ bioremediation.
       The selected standard technologies could reach clean-up goals.      !
                                              -5-

-------
       The selected remedy, RAA-2B (on-site disposal at Sullivan's landfill), was chosen because it
       would significantly reduce mobility of the contaminants by placing excavated sediment/soils
       under the RCRA cap to be constructed in OU-1, would not require use of specialized treatment
       equipment with limited availability, would be more easily implemented than some of the
       alternatives, and is the least costly of the action alternatives.  The selected RAA provided no
       treatment and was therefore somewhat less permanent than other alternatives. However,
       permanence was deemed less important because the PCB levels in soil/sediment at Middle
       Marsh were low enough to be effectively contained in the Sullivan's Ledge Landfill.
9.      If an innovative technology was chosen, why?                                      •

       The selected remedial alternative did not include any innovative technologies.  However,
       solvent extraction was selected as a contingency remedy for OU-2 in case the timing of OU-1
       implementation (capping Sullivan's landfill) prevents further use of the landfill. From pilot
       studies, it is expected that solvent extraction could reach PCB cleanup levels and permanently
       treat sediment.                      ,      .
10.    If an innovative technology was not chosen, why? At what stage was the innovative
       technology eliminated?                                 '

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:, during the initial screening; during the screening for the three criteria of
       effectiveness, implementability, and cost; or during, the detailed evaluation;

       Innovative technologies eliminated during the initial screening include:             ;

       •      None    '           '                                    •      •        '

       Innovative technologies eliminated during the screening of the three criteria include:

       •      In situ bioremediation (RAA-3) was eliminated because the technique has not been
               proven or well established for PCBs.  Its was uncertain whether its,effectiveness would
               be maintained in the dense organic silt present at Middle Marsh.  Also, since aerobic
               biodegradation is necessary, it was questionable whether microbes could reduce soil
               PCB concentrations to the remediation'cleanup goal of 15 mg/kg.  It would be
               technically difficult to provide the necessary oxygen to maintain aerobic decomposition
               in such dense sediment, and implementation of the aerobic phase may cause additional
               wetlands impacts.  Further, it is possible that the bacteria might prefer the highly
               organic sediment in Middle Marsh to  PCBs. Finally, there are not many vendors
               available to implement this technology.
       »      On-site bioremediation (RAA-4) was  eliminated because the wetlands would be
               impacted during excavation and would have to be restored, there would be short-term
               risks to workers during remediation, it is not well demonstrated for treating PCBs, few
               contractors are available, and dewatering of treated sediments would require treating
               the  wastewater prior to disposal.
                                                                                                047

-------
 7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
vseiecieu iciuciuai alternative is in DOldJ
•! • • ' ' / . ••-'• - •" ' ; -.
Alternative
RAA-1
RAA-2A
RAA-2B
RAA-6A
RAA-6B
RAA-6C
RAA-7A
RAA-7B
RAA-7C
RAA-8
Standard Technology
No action/limited environmental
monitoring
In situ containment/multi-layer cap
Excavatiori/dewatering/water treatment/
disposal to Sullivan's Landfill OU-1/
wetlands restoration/long-term
monitoring/institutional controls
Excavation/on-site stabilization and
solidification of sediment and soil/disposal
at OU- I/wetlands restoration/long-term
monitoring/institutional controls
Same as 6A except disposal of solidified
material at RCRA landfill to be
constructed at Middle Marsh
Same as 6A except disposal of solidified
material off site at RCRA landfill
Excavation/on-site incineration of soil and
sediment/disposal of ash at Sullivan's
Landfill/wetlands restoration/long-term
monitoring
Same as 7 A except disposal of ash at
RCRA landfill constructed on golf course
Same as 7A except disposal of ash at off-
site RCRA landfill
Off-site incineration of excavated" sediment
and soil
Estimated Costs
'2 Criteria
$50,000
$1,800,000
$2,000,000
j
$3,200,000
$5,000,000
$6;400,000
$6,600,000
\ -
,|
$8,000,000
$7,100,000
$14,000,000
f .
9 Criteria
$50,000
eliminated
$2,801,100
$5,052,700
$6,074,300
eliminated
$9,824,200
eliminated
$9,962,300
eliminated
8.      If a standard technology was ctibsen, why?                       I
                                    !!       '          -                I      •      '
       For this OU, EPA determined that there are no significant risks to human health posed by
       contaminants in the marsh. The, PCS contamination, however, does present an imminent and
       substantial endangerment to biota present in the environment of the marsh. EPA further
       determined that disturbance of wetlands and floodplains is the only practicable alternative that
       would be protective of the biota! while minimizing adverse impact on [the terrestrial and aquatic
       ecosystem.  Therefore, a comprehensive wetlands restoration would be implemented for all
       wetland alternatives except no action.                             I
04G
                                             -3-

-------
       Containment:
       Thermal treatment:

       Physical treatment:
       Disposal:
Capping                              .
Incineration, including fluidized bed incinerators, rotary kilns, infrared
thermal units
Stabilization/solidification
Sullivan's Landfill, which is to be capped in the future, disposal at a
RCRA facility
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                                        ,

        Biological treatment:   In situ or ex situ biodegradation
        Chemical treatment:    Solvent extraction
        Thermal treatment:     Pyrolysis
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of the three criteria (effectiveness, implementability,
        cost) screening process to identify alternatives of sufficient merit to undergo further detailed
        evaluation.  The estimated costs are recalculated during evaluation by the nine criteria
        established by the NCR                           '-..'.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
Contain area/in situ biodegradation
On-site biological treatment of excavated
sediment/soil
Site preparation/excavation/on-site solvent
extraction treatment/off-site disposal of
PCB-cdntaining solvent/disposal of treated
soil and sediment into Middle Marsh/
wetlands restoration/long-term monitoring
Estimated Costs
3 Criteria
$1,500,000
$3,100,000
$4,600,000
9 Criteria
eliminated
eliminated
$7,616,777
                                               -2-
                                                                                                 045

-------
                               Sullivan's Ledge/Middle Marsh
                                   New Bedford, Massachusetts
                                    il       Region 1
   GENERAL SITE INFORMATION
   i.
  2.
What were the principal contaminants,
contaminant levels, and media being
addressed in this'feasibility study?
                           11
Maximum concentrations of principal
contaminants were:
                           'v\
                           [ 1
Surface Sediments/Soil (rag/kg):
                      , _    :\	

PCBs                34     !

Subsurface Sediments/Soil (nig/kg):

PCBs                97     ,
What volume of material is to be
remediated?                \\ '
                                                                   Sile History
                                                      NPL Proposed:
                                                      NPL Final:
                                                      FS:
                                                      ROD:
                                                      EPA Fund-lead
                                                      PRPs:  14 ownerfoperatoi
                                                             transporters
                                                      FS prepared by:
         The volume of material to be remediated included:
      1982
      9/84
      5/91
      9/27/91
                                                                   Background
       >rs, generators,
  ;, and disposers  ,
Metcalf & Eddy, Inc.
         n
       Total remediation area of 1.92 acres   ,                 |
       Total contaminated soil/sediment volume of 5,220 cubic yariis
  3.      What type of site is this?     !i' '.               '               i         '" •  '.
                                    I                         , '-        f
                                    ; ;      '     '          '           - ,f '
         Industrial Landfill,  the second, Operational Unit (OU-2) at Sullivan's Ledge consists of
         Middle Marsh, a 13-acre freshwater wooded swamp/marsh wetland. | Sediments in Middle
         Marsh were contaminated by migrating pollutants from the quarry or disposal area at
         Sullivan's Ledge OU-1.       i                   .             1
  TECHNOLOGY SELECTION       "                 ,               ]
                                    ":'•.'--'•.• i    "  '           '

  4.      What standard technologies were considered for selection in this FS?
      • ,                        •     i i                                 '          -       '
                                    it.                      .

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:           '                               '  | .   .
         Removal:
                           ' >                •                 ,f                     ' •
                     Dragline dredge, backhoe, air conveyance dredging system, bulldozer,
                     hand shovel, light-weight excavators       i
044
                                              -i-

-------
       the treatments incorporated into the selected alternative, would serve only to immobilize
       contaminants and therefore did not offer the greatest degree of long-term protection and
       permanence. Alternatives that proposed incineration, a treatment that would provide a
       permanent reduction in site contaminants, were eliminated because of expense or short-term
       risks from excavation.  Impact on nearby populations was another important factor in choosing
       a remedy.  Alternatives that would require excavation were eliminated because of VOC
       releases.  The chosen alternative remediates VOCs prior to excavation.  Several alternatives
       were eliminated because they would not be cost-effective.  Finally, alternatives that proposed
       off-site disposal or incineration of site soil were eliminated because it would be difficult and
       expensive to find a landfill that would accept dioxin- and PCB-contaminated soil.
                                         '""".'                             ./

17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       Because the site is in a residential area, a major factor in selecting a remedy was short-term
       risk to the community. Excavation of site soil containing VOCs could pose a short-term risk
       due to their volatilization.   Other technical  site characteristics that were considered in the
       selection process were, the low soil permeability and the diversity of contaminants at the site.
       These factors restricted the number of viable alternatives and, with the exception of
       incineration (which was not chosen), no alternative would reduce all site contaminants:
                                                                                                       043

-------
Contaminant
PAHs (total) !
PCBs i
Cleanup Level (ppb)
29,000
1,000
ARAR or Other Basis
Background
1 TSCA" .
Noncarcinogens ' f
Styrene
Lead
14,000
500,000 ,
'•-. | Risk
OSWER Directivec
               The cleanup level for dioxin is based on the Agency for Toxic Substances and
               Diseases Registry (ATSDR) recommendation for residential Land use.
               The cleanup level for PCBs is based on the Federal Toxic Substances Control Act
               (TSCA) for Superfund Sites for residential land use.       I
               The cleanup level for kad is based on OSWER Directive 9365.4-02,,"Interim
               Guidance on Establishing Soil Lead Cleanup Levels at Superfund Sites."  ,
13.    Was the innovative technology Eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                              1
                                 • ' '!   -   •-•-.••,.     -   •        ')••-••.
       Innovative technologies eliminated because of cleanup goals include:!
                     -              i1                .':•!•
                                   11         '               •        , i
       •      Thermal desorption   l|                                 i      •   • • -
       *      Solvent extraction    J                                 ;
        •       '          '       .:!'••'.'•                ;t                '
       Standard technologies eliminated because of cleanup goals include:  ';   .

     •  •  '    None    '          '!!•'..     ••      ..-....-.      :[..
                                    i        -            ~             i   ,       •
14.    Were treatabllity studies conducte'd on the innovative technology or standard technology? •
                                    ',\:  '        -'.. -    .. .  •   ,        "\,   .    '    •••...
       Treatability studies were carried > out for stabilization/solidification and vacuum vapor extraction
       techniques.                   ;                                 '
75.    What measures/criteria were used to compare alternatives?
                                    1L
       The following measures were used to compare the alternatives:

              Total cost             !|
              Preference for treatment (vs. containment)
              Impact on nearby populations
16.     How are measures compared?  \\
       The chosen alternative was selected because it employed two treatment technologies that
       addressed site contaminants:  Treatment was preferred over containment.  Stabilization, one of
 042
                                             -8-

-------
Contaminant
Trans-1,2-
dichloroethene
1,1,1 -Trichloroethane
1 ,2-Dichlorobenzene
1,2,4-
Trichlorobenzene
Ethylbenzene
Styrene
Toluene
Xylenes
Cleanup Level (ppb)
67
300
8,900
720
6,800
170
2,700
22,000
Basis for Leaching Model
MCLG
PQL
- MCLG
pMCLG6
MCLG
MCLGC
MCLG
MCLG
       "Maximum Contaminant Level.
       ''Proposed Maximum Contaminant Level.
       'Maximum Contaminant Level, Goal.
       Practical Quantitation Limit.
       Proposed Maximum Contaminant Level Goal.

Surficial Soils

Cleanup levels for surficial soils were developed to reduce risks associated with direct contact
and ingestion exposure to site soils.  Since no ARARs were available for the indicator
contaminants in soils, health-based levels were derived. Health-based cleanup levels were
developed for soil contaminants that were found to pose a risk in excess of           •
10'6 or a Hazard Index greater than 1.0, when evaluated under the worst-case scenario.
Occasionally policy-based,cleanup criteria or background  levels were utilized.
Contaminant
Cleanup Level (ppb)
ARAR or Other Basis
Carcinogens
Benzene
1 , 1 -Dichloroethene
1 ,2-Dichloroethane
Methylene chloride
1,1,2,2-
Tetrachloroethane
Trichloroethene
Arsenic
Dioxin
15,000
720
4,800
58,000
2,200
40,000
21,000
1
Risk
Risk
Risk
Risk
Risk
Risk
Background
ATSDR"
                                       -7-
                                                                                        041

-------
  11.
  12.
040
Which of the nine criteria were weighted most heavily- in selecting the technology?  Did failure
to meet i,   of the nine criteria result in the elimination of the innovative technology?  If so
which cn^rion? Which of the criteria supported the use of a standard technology?
                           ' J !                                 L           '
When choosing between alternatives that were protective of human health and the
environment, the deciding factor was implementability.
         A t, A D ,   „,. ' 8°al,S I?*™ selected? Vthe cleanuP Soal was based on an ARAR, what was that
         AKAR/   What risk level was selected to establish cleanup goals?   ;

         Unsaturated Soils

         The cleanup levels for unsaturated soils  were based on the potential Lgestion of ground water
         contaminated by leaching fromjunsaturated-zone soils. Cleanup goals for the leaching scenario
         were evaluated using three analytical models: the equilibrium model:, the organic leaching
         model, and the MacKay partitioning model.                       i
Contaminant ,
Carcinogens
Benzene •
Carbon tetrachloride
Chloroform .
1 , 1 -Dichloroethene !
1,2-Dichloroethane •
Methylene chloride ;
1,1,2,2- :
Tetrachloroethane •
1,1,2-Trichloroethane !
Trichloroethene '
Bis(2- ;
ethylhexyl)phthalate ;
1,2-Dichloropropane ;
Dioxin
Hexachlorobenzene !
PAHs ;
PCBs ;
Noncarcinogens , . |
Chlorobenzene
• i
^
Cleanup Level (ppb)
-
4
5
40
" • 5 , , •
1
. •'"! •'
6
„ 3
6
300
3
1
34
10,000
2,300

300
-6-
Basis for Leaching Model
' ' . i -. ';
MCLa
MCL
MCL
MCL
MCL
pMCLb
PQLd
pMCL
MCL
pMCL
MCL
pMCL
pMCL
pMCL
MCL

MCLG


-------
Innovative technologies eliminated during the initial screening include the following:

•      Biodegradation was eliminated because of the variety of contaminants present in site
       soils; microorganisms that degrade one type of contaminant have different
       environmental requirements than organisms that degrade another type of contaminant;
       contaminants degraded by one set of organisms may be toxic to organisms that
       degrade other contaminants: design and implementation of a biosystem is questionable;
       degradation products for all contaminants is unknown;  sequential batch reactors would
       be difficult to operate; cold weather would decrease performance; degradation of
       chlorinated aliphatics, PCBs and dioxins  has not been demonstrated at the field  scale.
•      Soil flushing was eliminated because soils at the site have low permeability; uniform
       distribution and collection of flushing solution would be difficult to implement because
       of the stratified and heterogenous nature  of site soils.
•      Soil washing was eliminated because no  data is available for PCBs and. dioxin removal
       effectiveness; disadvantages with the large volume of surfactant required; the spent
       surfactant/contaminant solution to be disposed; and the residual surfactant and
       contaminants remaining in the soil.
•      Critical and supercritical extraction were eliminated because of the inability to
       successfully treat soils that are heterogenous with low  permeability and the lack of cost
       effectiveness.                          ,          *                           .
•     In situ steam stripping was eliminated because it has not been field demonstrated; its
        effectiveness for volatile  organic compounds is questionable; no significant removal or
        treatment of less volatile substances such as PCBs, dioxins and metals is expected;
        reduced effectiveness during winter months.
•      Ex. situ steam stripping was eliminated because the soil would need to be excavated,
        which would create VOC emissions. Furthermore, the technique  would not affect the
        site's semivolatiles.
 •      Radio frequency heating  was eliminated because there are no vendors and full-scale
        equipment; the technology has not been  evaluated for  removal of PCBs and dioxins;
        and it is  not expected to  remove or immobilize metals; and its reliability can't be
        assured because it has not been demonstrated at field scale.
 •      In situ vitrification was eliminated because  it would be infeasible to implement in an
        urban setting. Careful control would be necessary to avoid vitrifying nearby facilities
        existing utilities and foundations.  Associated settling  could also damage roads, utilities
        and foundations outside the vitrified area. Also, no significant removal of PCBs,
        dioxins,  and metals is expected.

 Innovative technologies eliminated during the detailed analysis include the following:

 •      Thermal desorption was not chosen because it would  require excavation of volatile
        organic contaminated soiis; only limited treatability testing done to assess potential for
        treatment of PCBs and dioxins and no testing at all for treatment of contaminants in
        wet, fine grained soil at  site; technical experts expressed doubt about the practical
        efficiency of achieving the range of clean-up goals for dioxins and PCBs anticipated
        for the site; process might make some metals more teachable by  oxidizing them; and
        soil treated would be subject to TCLP; high cost compared to other remedies.
 •      Solvent extraction was eliminated because it may not  meet PCB and dioxin clean-up
        levels; bench or pilot studies would be required to test effectiveness on dioxins, since
        it is not a proven  technology for treatment of dioxins.
                                                                                          039
                                         -5-              '-'.'•'

-------
  7.
 How did the cost(s) compare to standard technologies?

           Cost Estimates for RAAs That Include Standard
                                                                    Technologies
(.selected remedial alternative is in bold)
.'••'! ' r ••'.--..'..,. ' ' -
Alternative
RAA-SC-1
RAA-SC-2
RAA-SC-10
RAA-SC-12
1 1
Standard Technology
No action/restricted access
Access restrictions/RCRA cap
construction
,
Incineratioii/stabilization/ solidification/
on-site disposal/ construction of RCRA
landfill and cap
Off-site incineration/stabilization/
solidification
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A ,
9 Criteria
$1,050,000
$5,370,000
$53,879,000
eliminated
 8.      !f a standard technology was chosen, why?
                                      \ i

        Solidification/stabilization and a;RCRA cap was selected ^conjunction with soil vapor
        extraction to treat any residual contamination left after vapor extraction. In this Feasibility
        Study and Record of Decision soil vapor extraction was proposed with a number of alternative
        technologies for residual treatment or containment.  Solidification/stabilization was selected
        because 1) inorganic and non- volatile organic contaminants would remain in soils  after
        treatment with soil vapor extraction,  2) limits mobility and migration to ground water, 3)
        reduces risks from direct contact, inhalation and ingestion, 4) cost, 5)'readily available services
      ,  and materials.                  h                                   i         .
 9.      If cm innovative technology was'chosen, why?                      \
                                            '                            ,E

        Soil vapor extraction was selected in conjunction with solidification/stabilization and capping
        because:  1) a treatability study showed that VOC clean-up levels can be attained for most
        target compounds, 2) removes VOCs which are the bulk of the contarnination at the site, 3)
        readily available services and materials, and 4) cost.                !
10.
                            .11       ...        ,              L
If an innovative technology was not chosen,  why not? At what stage was the innovative
technology eliminated?                                            [
                    •    ',     i!'  "   -.      '.  •    '-          .     |,'  -*"*  .     -     -;
Innovative technologies could be eliminated  from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or  during the detailed evaluation.
038
                                               -4-

-------
Cost Estimates for RAAs That Include Innovative Technologies
          (selected remedial alternative is in bold)
Alternative
RAA-SC-3
RAA-SC-4
RAA-SC-5
RAA-SC-6
RAA-SC-7
RAA-SC-8
RAA-SC-9
RAA-SC-I1
RAA-SC-13
RAA-SC-14
RAA-SC-15

Innovative Technology
Vacuum vapor extraction/RCRA cap
construction
Vacuum vapor extraction/excavate
remaining contaminated soil/
stabilization/solidification/on-site
disposal/construction of RCRA cap
Vacuum vapor extraction/stabilization/
solidification/off-site disposal at RCRA
landfill
Thermal desorption/stabilization/
solidification/on-site disposal/
construction of RCRA landfill and cap
Thermal desorption/stabilization/
solidification/off-site disposal at RCRA
landfill
Vacuum vapor extraction/thermal
desorption/stabilization/ solidification/
on-site disposal/construction of RCRA
landfill and cap ,
Vacuum vapor extraction/thermal
desorption/stabilization/solidification/
off-site disposal at RCRA landfill
Vacuum vapor extraction/stabilization/
solidification/incineration/on-site
disposal/construction of RCRA landfill
and cap
Vacuum vapor extraction/ stabilization/
solidification/off-site incineration
Vacuum vapor extraction/solvent
extraction/stabilization/ solidification/
on-site disposal/construction of RCRA
landfill and cap
Vacuum vapor extraction/solvent
extraction/stabilization/solidification/
off-site disposal/construction of RCRA
landfill and cap
Estimated Costs
3 Criteria3
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$9,020,000
$10,620,000
eliminated
$51,250,000
eliminated
eliminated
eliminated
$17,220;000
eliminated
$10,850,000
$18,620,000
                                                                          037

-------
3.      What type of site is this?  'i

        Recycling.  A former chemical waste reclamation facility.
TECHNOLOGY SELECTION        j[                                  j
                                     •i!                 •'                i         -.
4.      What standard technologies weire considered for selection in this FS?
               "   '              •    -•!    •       '   '      '              p  ••..'.   •
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:    ~      "j!                                  i
                                     'I I  '      •       • "               -   !      --.-•.-•''
         '.                      • -   ,.  • *\         ,    -'      '      '        i'   ''-,..
        Access restriction:     Fencing, deed restriction                    i
        Containment:          Capping                                  j
        Physical treatment:     Stabilization/solidification, dewatering       |
        Thermal treatment:     Rotary kiln incineration, circulating bed incineration, infrared
                              incineration
     .." Disposal:              Excavation, on-site landfill, off-site  landfill
        Was an innovative technology considered in the FS?  If so, which technology?
                                     \\ '     '              ' '          ,  •  i  ••       '    ,
        Innovative technologies considered during the identification arid screening of technically
        feasible technologies were:     !i                                  i      ,
                          -            i                   '               [•         •
        Biological treatment:   Biodegradation                             I
        Phys/Chem treatment:  Solvent extraction, soil flushing (solvent), washing (solvent), vacuum
                              vapor extraction                          "  i  ,
        Thermal treatment:     Critical and supercritical fluid extraction, thermal desorption, steam
                              stripping!, radio frequency heating, in  situ vitrification
6.     ,  What was the cost, estimate for the innovative technology?           \
                                     r       .    .        •:     "      .  !•   '    '   '  '•  ,  .  •
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAA's), the FS does not quantify costs, After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening prixess (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of humah health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency  acceptance; and
        community acceptance. Present value cost estimates were not calcula ed during the three-
        criteria screening,             i
 036
                                              -2-

-------
                            Silresim Chemical Corporation

                                   Lowell, Massachusetts
                                         Region 1
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?   '

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Carbon tetrachloride          450
       Chlorobehzene        .       260
       Chloroform                  50
       1,1-Dichloroethene            146
       1,2-Dichloroethane            490
       1,2-Dichloropropane          70
       Methylene chloride           480
       1,1,2,2-Tetrachloroethane      830
       1,1,1-Trichloroethane          1,900
       1,1,2-Trichloroethane          33
       Trichloroethene              1,900
       Benzene                     115
       Ethylbenzene                630
       Styrene                     3,800
       Toluene                     1,200
       Xylenes                     400
       Bis(2-ethylhexyl)phthalate     470
       1,2-Dichlorbbenzene          752
       Dioxins(2,3,7,8-equiv.)        0.01
       Hexachlorobenzene           44
       PCBs                       1500
       PAHs                       2255
       1,2,4-Trichlorobenzene        240
       Trans-1,2-Dichloroethene      13
       Arsenic                     640
       Lead                        7,850
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1982
1983
6/19/91
9/19/91
             Background

PRP-lead
PRPs:  Not listed
FS prepared by: GZA
       GeoEnvironmental, Inc.
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      137,000 cubic yards of soil
                                            -1-
                                                                                           035

-------
 16.    How are alternatives compared?

                                -     | ! '           •              '        "I
        Of the RAAs that underwent detailed evaluation, total cost was the primary measure used to
        eliminate in situ vitrification (RAA-SC-5), incineration (RAA-SC-10), and off-site disposal
        (RAA-SC-11).  Also, in situ vitrification was considered an innovative technology and its
        reliability was questioned.  Capping was not considered as permanent or as protective as the
        selected remedy because it does not treat contaminants and there is ithe potential for future
        failure of components of the remedy that would require repair.     ;

        The Summers Leaching Model '(EPA/540/2-89/057) was used to estimate residual soil and
        sediment levels not expected to impair future groundwater quality.  !
 17.
                             ;.               '"'           "      -I
 What technical considerations had to be considered in the selection of a remedy?  Were
 technical considerations primary in the selection of the remedy?    \   •  •

 The PSC site is about 1.5 acres?; located within the 100 .year fioodplain of the Quaboag River
 and is bounded by wetlands to the south and east.  Site soils were observed to be stained black
 from, spills of waste oil/sludges to a depth of up to six feet and the depth to groundwater
 ranges from one to eight feet, which accounts for groundwater contamination from the site.
 Space limitations created implementation difficulties for incineration and on-site
 biodegradation.  The need for both a biodegradation facility and a landfill for the latter
 alternative would result in a reduction of the flood storage capacity currently present in this
 area.  The adjacent wetlands would suffer greatest damage from the incineration and off-site
disposal alternatives due to the more intrusive excavation  necessary. However, the majority  of
technologies were eliminated because of the wide variety  of organic and  inorganic
contaminants at the site.  Technical considerations could not be cons dered primary in the
selection of a technology at this site.  ..-'"'•''
034
                                                                                                           >-v
                                                                                                            )
                                                                                                          -.-^
                                             -10-

-------

                      Contaminant
                Arsenic
                Non-Carcinogens:
                Total PAHs
                Lead
Clean-up Level (ppm)
                                                     12
                                                     10
                                                     375
                                                                    ARAR or Other Basis
                                HHRA
                                 ERAC
                                 ERAd
              "Human Health Risk Assessment.
              bUptake/biokinetic model.
              Theological risk assessment.                            .
              ''Clean-up levels for lead and zinc were established with an ERA to ensure the
              protection of birds.
                                                                                   /         -
       For carcinogens an excess upper bound individual lifetime cancer risk of between 10"4 to 10'6
       was acceptable.  For non-carcinogens a Hazard Index (HI) less than or equal to 1.0 was
       acceptable.           ,             ,             '    .


13.     Was the innovative technology eliminated because of the clean-up goals?  If a standard
       technology was chosen,  could it meet the clean-up goals?                      ,

       Most innovative technologies were eliminated during the technology screening process because
       they were not considered effective for the organic and inorganic contaminants at the site.
       Innovative technologies included in RAAs that were eliminated because of clean-up goals were
       on-site bioreclamation and soil  flushing. The selected standard technology (in situ
       stabilization) could meet clean-up goals.


14.     Were treatability studies conducted on the innovative .technology or standard technology?

        Yes, several treatability studies were carried out.  A limited bench-scale biodegradation study
        was'done on PSC Resources soil to evaluate the feasibility of applying bioremediation
        techniques to reduce or remove contaminants in the soils at the PSC site, verify the existence
        of a microbial population in  the contaminated soils,,and evaluate the biodegradation of
        contaminants by on-site microbes.  Another soil column flushing study evaluated the transport
        of VOCs from the soil  to groundwater and the effectiveness of using surfactants for flushing
        vadose zone soils.  A third study explored the effectiveness of a soil stabilization mixture on
        site soils.
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

                Total cost
                Proven reliability                       '
        -       Preference for treatment
                Permanence
                                               -9-
                                                                                                    033

-------
ft II?
YS ^^ ***
' ' ' . J ., ,
•f-'.'~
I ' I '
1 1 ' ' ' • '•','•
. , , , 1 , , .. . ,
. [, - . _ • ' ' • , .
Contaminant ;
Benzene* • !
i
Non-Carcinogens: ',
Lead
Total ncPAHs*
1,1-Dichloroethane* ,
Cis-l,2-Dichloroethylene*
Trans-1,2- f
Dichloroethylene*
1 , 1 , 1 -Trichloroethane*.
Clean-up Level (ppm)
1

500
151
243
5
7 ' ' '
135
ARAR or Other Basis
MCL

UBKMb
i risk
risk
\ MCL
MCL
!
MCLG
i , . r •
Lagoon Sediment Clean-up Levels:
Contaminant '
Carcinogens:
Bis(2-ethylhexyl) phthalate*
Trichloroethylene*
Tetrachloroethylene*
Methylene chloride* 1 1
Benzene* \
Total cPAHs j
Non-Carcinogens: I
1,1,1 -Trichloroethane*
Total ncPAHs* :
1,1-Dichloroethane*
Lead '
Acetone* :
Clean-up Level(ppm)

368
4
12
1
3
100

200
1,206
1
500
10
ARAR or Other Basis

MCL
MCL
1 MCL
MCL
MCL
HHRA
!
; MCLG
risk
risk
UBKM
risk
1 ' ' . , , . !
Wetland Sediment Cleam-up Levels:
i . • , " • . -
Contaminant ;
Carcinogens: '
Total PCBs :
Clean-up Level (ppm)

1
AFAR or Other Basis
i • -
HHRA
.:! - ••.-.-' {.._ • •; ; • ;

-------
11.
       on the site.  Further, it was expected that this technique would require an intense pilot
       study to determine its long-term effectiveness prior to full-scale implementation. The
       need for both a biodegradation facility and a landfill for this alternative would result in
       a reduction of the flood storage capacity currently present in this area.
•      Soil flushing (RAA-SC-9) was eliminated because it would be very difficult to:
       implement due to the diversity of contaminants present since no individual flushing
       solution could address all contaminants. Only a selective reduction in contaminants
       would be  achieved.  Further, there would be potential for exposure in the short term.

Innovative technologies eliminated during the detailed analysis include:

•      In situ vitrification (RAA-SC-5) was eliminated because it has not been used in any
       commercial applications, raising questions about its implementability, and it requires
       very high amounts of electricity not available at the site.


Which of the nine criteria were weighted highest in selection of the technology?  Did one of
the nine criteria eliminate the innovative  technology from being chosen?  If so, which one?
Which of the criteria supported the use of a standard technology?

The most heavily weighted screening factors appeared to be cost  and long-term
effectiveness/permanence. RAA-SC-6 and RAA-SC-4 were the least expensive and easiest to
implement RAAs. RAA-SC-6 was superior to RAA-SC-4 with regards to longrterm
effectiveness and permanence and  its provision for treatment.  RAA-SC-5 (in situ vitrification),
RAA-SC-10 (incineration), and RAA-SC-11 (off-site disposal) would provide greater reduction
in toxicity, mobility, or volume, but were eliminated because they were more costly and more
difficult to implement.
 12.     What clean-up goals were selected. If the clean-up goal was based on an ARAR, what was
        that ARAR?  What risk level was selected to establish clean-up goals?

        Area soils and sediments  were considered a source of VOCs to groundwater.  It was believed
        that the future contamination of groundwater by soil and sediment leachate would result in an
        unacceptable risk to those who drank the contaminated groundwater.  For these contaminants,
        clean-up levels for soils and sediments were established to protect the aquifer from potential
        soil leachate. The Summers Leaching Model (EPA/540/2-89/057) was used to estimate
        residual soil and sediment levels not expected to impair future groundwater quality.  Interim
        clean-up levels for groundwater were used as input into the leaching  model.  Contaminants
        whose clean-up goals were  estimated with this model are noted with  an asterisk (*).

               Soil Clean-up Levels:
Contaminant
Carcinogens:
Total PCBs
Trichloroethylene*
Tetrachloroethylene*
Clean-up Level (ppm)

1
1
2
ARAR or Other Basis
•
HHRAa
MCL
MCL
                                               -7-
                                                                                            031

-------
    °.      If an innovative technology was chosen, why?

            An innovative technology was; not chosen.
                                     "             •          «                        ve technobgy
           Innovative technologies could be eliminated from the remedial technology selection process at
           three stages:  during the initial Screening; during the screening of the thSl criteria of
           effectiveness, implementability, and cost; or during the detailed evaluation
                               .  '      H      '.-..•            '          [       •             • •
                                       »!••••            .            •>
           innovative technologies eliminated during the initial screening include:

           •      Low temperature thermal stripping was eliminated because L temperature necessary
                  to remove PGBs will be in excess of the flashpoint of other constituents
           •      Vacuum extraction was,eliminated because it does not address inorganic constituents
                  Molten salt destruction was eliminated because it was not considered implementable
                  due to uncertainties associated with waste destruction performance
           •      Solvent extraction was eliminated because the soil is organically rich (attributed to
                  waste oils) making liquid extraction less favorable and its effectiveness is limited by
                  the solubility of contaminants and the ability of the solvent to permeate through the
                  soil to influence entrapped contaminants.                   \
                  Dechlorination was elnninated because of its effectiveness with chlorinated organics
                  S^rfSl?1 ^,M COStS! apd difficulties wi*h implementation.
                                                 it does not address inorganic compounds and has
                         glass method was eliminated because it is an innovative technology that is
                  difficult to implement at this stage of development and has high capital and O&M
                  costs.                 '                                   f     '
                                       f p               •'                  ^            '
                  In situ bioreclamation vi^as eliminated because  it  has a limited effectiveness
                  remediating chlorinated [organic compounds and inorganics, has high initial capital
                  costs, and has high O&M costs in the future                I '
                  Land treatment was not included in the RAAs, although no explicit reason was given
                  On-site bioremediation was included in the RAA as the representative biological    '
                  process option. The FS noted that land treatment has limited ; effectiveness on
                  chlonnated organics and inorganics.                        !
                  Wet air oxidation was not included in the RAAs, although noUplicit reason was
                  given.  Incineration and in situ vitrification were included in the RAA as the
                 representative thermal process option. The FS  noted that wetjair oxidation has limited
                 effectiveness on chlorimited organics and inorganics.         !            nas limited
                 Supercritical water oxidation was not included  in the RAAs, although no explicit
                 reason was given.  Incineration in situ vitrification were included in the RAA as the
                 hTn^Vyhral P^esl °Ption-  ** FS noted that supercritical water oxdation
                 has limited effectiveness on chlorinated organics and inorganics.

         Innovative technologies eliminated during the screening of the three catena include:
                                      (]^AA-SC-8) was eliminated because both short-term and long-
                term effectiveness are low. Potential for exposure during implementation is great  fo
                the long-run, the technique would not address inorganic and PCB contamination found
030                                 ;L
                                       II        -6-

-------
        Alternative
         Standard Technology
                                                                     Estimated Costs
                                                                 3 Criteria
9 Criteria
        RAA-SC-6
Long-term monitoring/access restric-
tions/lagoon dewatering and treatment/
consolidate sediment and soils/in situ
stabilization of consolidated source
materials/permeable cap over stabilized
mass/wetlands restoration	
                                                                 $3,070,000
$3,067,045
         RAA-SC-7
Long-term monitoring/access restrictions/
lagoon dewatering and treatment/construct
stabilization plant/construct residual source
materials storage facility/dewater beneath
AOC with ground water treatment and
discharge/obtain treatability variance/
excavate sediment and soils/on-site RCRA
disposal/stabilize residual source
materials/wetlands restoration	
                                                                 $5,500,000
 eliminated
         RAA-SC-10
 Long-term monitoring/access restrictions/
 lagoon dewatering and treatment/construct
 on-site incinerator/construct temporary
 source material storage facility/dewater
 beneath AOC and treat ground water/
 excavate sediment arid soil for storage/on-
 site RCRA disposal/incinerate source
 materials/place incinerator residuals into
 disposal facility/cap/wetlands restoration
                                                                 $15,010,000
$15,009,715
         RAA-SC-11
 Long-term monitoring/access restrictions/
 lagoon dewatering and treatment/dewater
 beneath AOC, with groundwater treatment
 /excavate and containerize soils and
 sediments/off-site RCRA disposal/backfill
 excavation/wetlands restoration
                                                                  $34,626,000
 $36,261,417
8.      If a'standard technology was chosen, why?           '                 ;.

       In situ stabilization (RAA-SC-6) was chosen because it permanently reduces risks posed to
       human health and the envkonment; meets all ARARs; uses readily implementable techniques
       that have been successfully used at other NPL sites; emphasizes treatment; has minimal short-
       term risks- and is cost-effective.  In situ vitrification (RAA-SC-5), incineration (RAA-SC-10),
       and off-site disposal  (RAA-SC-11), are all more expensive and less implementable than in situ
       stabilization. Capping  (RAA-SC-4) was considered as cost-effective as the selected remedy,
       but does not comply with the statutory preference for treatment and was considered less
       protective because none of the contaminants would be eliminated, reduced, or stabilized.
                                              -5-
                                                                                              029

-------
  7.
Alternative
RAA-SC-8
RAA-SC-9
'!.-._
Innovative Technology
Long-term monitoring/access restrictions/
lagoon dewatering and treatment/construct
biodegradatkm facility/obtain treatability
variance/excavate sediments and soils/
construct ori-site RCRA disposal facility/
bioremediate residual source materials/cap
disposal facility/wetlands restoration
Long-term monitoring/access restrictions/
lagoon dewatering and treatment/excavate
wetlands and lagoon sediment for disposal
at off-site RCRA facility/in situ soil
flushing of property soils/leachate
collection and treatment/permeable cap
over property ^oils/wetlands restoration
' Estimated Costs
3 Criteria
,$4,255,000
1
$5,020,000
i
•I
(
f
\
9 Criteria
eliminated
eliminated
ii • . • ... ^ - . .
' - ; • • ; ' ' J ".'-• . ,:. • '
How did the cost(s) compare to standard technologies?
1 , -•'•' ' - '
                Cost Estimates for RAAs That Include Established Technologies
                           (selected remedial alternative is in bold)   j
028
Alternative
RAA-SC-1
RAA-SC-2
' RAA-SC-3
RAA-SC-4
Si
tandard Technology
No action: long-term monitoring
Limited action: long-term monitoring/
access restriction
Long-term monitoring/access restriction/
lagoon dewzitering and treatment/
permanent cap over lagoon, property,
wetland soils, and sediments/wetlands
restoration
Long-term monitoring/access restrictions/
lagoon dewatering and treatment/consolida-
tion of sediment and soil/impermeable cap
over consolidated source materials/earthen
levee/subsurface drain and vertical barrier/
ground water collection in barrier for
treatment anjfl discharge/wetlands
restoration ;
' Estimated Costs ,
3 Criteria
$(550,000
$760,000
Ji
,l
$863,000
* ?'
(
$2,680,000
i
i
!'
9 Criteria
$648,800
eliminated
eliminated
$2,677,815
J - ''''''.' - ••
1 • ' • . ' ' •
1 - } '..'''
' ' . '1 ' -.4- '' "-'-••- ..-•:•• ;''•'-'

-------
5.       Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies eliminated during the identification and screening of technically
        feasible technologies were:

        Soil

        Biological treatment:   On-site bioremediation, in situ bioreclamatioh, land treatment
        Phys/Chem treatment:  Vacuum extraction, solvent extraction, soil flushing, dechlorination
        Thermal treatment:     Low temperature thermal stripping, vitrification, molten salt  . ]
                              destruction, pyrolysis, molten glass method

        Lagoon Sediment

        Biological treatment:   In situ bioreclamation, on-site bioreclamation, land treatment, activated
                              sludge
        Phys/Chem treatment:  Solvent extraction, soil flushing, dechlorination
        Thermal treatment:     Wet air oxidation,  supercritical water oxidation, vitrification, pyrolysis,
                              molten glass method

        Wetlands Sediment

        Biological treatment:   On-site bioremediation, in situ bioreclamation, land treatment
        Phys/Chem treatment:  Solvent extraction, soil flushing, dechlorination
        Thermal treatment:    Low temperature thermal stripping, pyrolysis, molten glass method
         What was the cost estimate for the innovative technology?
                                                          .                       i
         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are estimated as part of the three criteria (effectiveness, implementabihty,
         cost) screening process to identify alternatives of sufficient merit to undergo detailed
         evaluation.  The estimated costs are recalculated during evaluation by the nine criteria
         established by the NCP.

                  Cost Estimates  for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-SC-5
Innovative Technology
Long-term ground and surface water
monitoring/access restrictions/lagoon
dewatering and treatment/consolidation of
sediments/in situ vitrification of
consolidated source -materials/permeable
cap over vitrified mass/wetlands restoration
Estimated Costs
3 Criteria
$10,380,000
s.
9 Criteria
$10,383,403
                                                 -3-'
027

-------
  2.      What volume of material is to be remediated?
                                     [•!''    .."       -•••'•    /
                                     " '
          The volume of material to be remediated included:
 *                                  .if-,.-.         s

          B      11,000 cubic yards ofj contaminated property soil
          «      450 cubic yards of wetland sediment
         .•      1,245 cubic yards of lagoon sediment
                                     1!                          -
                                     '''

  3.      What type of site  is this?     i
                                     f '•         "           '         r
         Waste Oil. A former waste oil reclamation facility.

                                     i i     •                  " :  '

  TECHNOLOGY SELECTION       "
                                     , f '  :

  4.      What standard technologies were considered for selection in this Fi
         Standard technologies considered during the identification and
         technologies were:           ;              :
         Soil

         Access restrictions:
         Containment:
         Physical treatment:
         Thermal treatment:

         Chemical treatment:
         Disposal:

         Lagoon Sediments

         Access restrictions:
         Containment:
         Chemical treatment:
         Thermal treatment:
         Physical treatment:

         Disposal:

        Wetlands Sediment

        Access restrictions:
        Containment:
        Chemical treatment:
        Physical treatment:
        Thermal treatment:
        Disposal:
 Deed restrictions, fencing
 Capping, surface controls (grading)
 Dewatering, lime-based pozzolan, sorption
 Rotary kiln incinerator, infrared treatment,
 thermoplastic microencapsulation
 Precipitation, vacuum extraction with carbon
 On-sitelRCRA landfill, off-site RCRA landfill
 Deed restrictions, fencing
 Slurry wall, sheet piling, bottom liner
 Precipitation
 Rotary kiln incinerator, infrared treatment, „ ,
 Evaporation, dewatering, lime based pozzolaa
 pozzolaii, asphalt based microencapsulation,
 Off-site RCRA landfill
                                     screening of technically feasible
 stabilization
 c: rculating bed combustor,
   adsorption
circulating bed combustor
   , portland cement
  sorption stabilization
Deed restrictions, fencing                   i
Capping, coffer dams, revegetation          j
Precipitation                               j
Dewatering, evaporation, sorption stabilizatiop
Rotary kiln incineration, infrared treatment, circulating bed combustor
On-site,: off-site RCRA landfill         ..[.-,
026
                                              -2-

-------
                                 PSC Resources Site
                                         OU-1

                                  Palmer, Massachusetts
                                        Region 1
GENERAL SJTR INFORMATION

L      What were the principal contaminants,
       contaminant levels, and media being  t
       addressed in this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg):

       Total PCBs                 65
       Trichloroethylene            390
       Tetrachloroethylene          63
       Benzene                   16
       Total ncPAHs               953
       1,1-Dichloroethane           7
       1,2-Dichloroethylenes       '190
       1,1,1-Trichloroethane        200 ,
       Lead                       39,200

       Lagoon Sediments (mg/kg):

       Total cPAHs              '  7,250
       Bis(2-ethylhexyl)phthalate     580
       Trichloroethylene             33
       Tetrachloroethylene          21
       Methylene chloride   .        20
       Benzene .                   340
        1,1,1-Trichloroethane         1,700
       Total ncPAHs               97,350
        1,1-Dichloroethane           10
        Acetone                    43
        Lead                        12,600

        Wetland Sediments (mg/kg):

        Total PCBs                 32
        Arsenic                     22
        Total PAHs             ,     129
        Lead                        50,100
            Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1982
9/83
1/10/91
9/15/92
             Background

EPA Fund-lead
PRPs:  PSC Resources, Inc., Newtown
       Refining Co., Refinemet Inter-
       national, Ag-Met Refining Co.,
       over one hundred other PRPs
FS prepared by: HMM Associates, Inc.
                                             -1-
                                       025

-------
 17.
        For carcinogens, an excess upper bound individual lifetime cancer ri
        was acceptable.  For noncarcinogens, a Hazard Index less than or e
 14.     Were treatability studies

        No treatability studies were conducted
                                                                      risk of between 1Q"4 to W6
                                                                           to 1.0 was acceptable.
                                                                      qual


13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       .Innovative technologies eliminated because of cleanup goals include

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None
                               conducted on the innovative technology or (tandard technology?
                                        to compare alternatives?

                                         to compare the alternatives:
15.     What measures/criteria were used

        The following measures were used

               Total cost
        -   , •   reliability


16.     How are measures compared?
                                     !             •               '      t        ''
        Seven of the ten original alternatives proposed source treatment technologies.  Treatment was
        preferred because it would ensure the greatest degree of long-term effectiveness and
        permanence. The chosen alternative utilized an  innovative treatment itechnology that was
        considered superior because it minimizes short-term risk and is cost-eiffective.  Several
        eliminated alternatives (RAA-4, RAA-5, RAA-6, and RAA-7) would ipose short-term risks to
        site workers and off-site populations during excavation. The remedy. |was considered reliable
        since it  had been applied often for contaminants and site conditions.  •;
       What technical considerations were factors in selecting a remedy?  W^ere technical
       considerations primary in the selection of the remedy?              \
                             •       !'  '    -   -,                 ''f-     •"•..-•'•
       Site-specific wetland ARARs were primary in the elimination of RAA-SC-10 since it would
       disturb arid destruct wetlands.  ',\     '     '                        I
024
                                              -7-

-------
       Innovative technologies eliminated during the three-criteria screening include the following:

       •      Soil flushing was eliminated because 1) it is less effective than Soil Vapor Extraction,
              and 2) less reliable than Soil Vapor Extraction.
       •      In situ heating (unspecified) was eliminated based on cost.                          ,

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Ex situ vapor extraction was eliminated because it would result in short-term risk
              during excavation and it would not be as cost-effective as the chosen alternative.
       •      On-site low temperature thermal stripping was eliminated because it would result in
              short-term risk during excavation arid it would not be as cost-effective as the chosen
              alternative.
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?  ,

       An innovative technology was chosen over several other innovative and standard technologies
       because it offered the greatest protectiveness at the least cost, provided short term effectiveness
       and was implementable.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        Soil cleanup levels were established to protect the aquifer from potential soil leachate. The
        Summers model was used to estimate residual soil levels that are not expected to impair future
        water quality.  Interim cleanup levels for ground water were used as input into leaching model.
Contaminant
Cleanup Level (mg/kg)
Basis for Model Input
Carcinogens
Trichloroethene
Vinyl chloride
1 , 1 -Dichloroethane
O.Q7
0.005
0.36
MCLa
MCL"
SHAb
Noncarcinogens
Toluene
Ethylbenzene
1 ,2-Dichloroethene
1,1,1 -Trichloroethane
14
17.4
0.46
2.1
MCLGC
MCLGC
MCLGC
MCLGC
               "Maximum Contaminant Level.    /
               bState Health Advisory.
               cMaximum Contaminant Level Goal.

                                               -6-
023

-------
                            1 !                    -               f
™      Hydrolysis was eliminated because 1) it is most applicable to ester compounds, 2)
       aromatic VOCs are resistant to hydrolysis, and 3) hydrolysis rates of chlorinated VOCs
       are on orders of years,                                   I
•      Dehalogenation was eliminated because 1) it is inappropriate for in situ application
       since mixing can't be controlled and contact with contaminants can't be ensured, 2)
       testing with chlorinated VOCs suggest removal was the result of volatilization.
M      Soil cooling was  eliminated because it is practical only as a short-term measure
       because of energy costs.                                 j   '
n      Ground freezing was eliminated because it is practical only; as a short-term measure
       because of energy costs.                                 I-
B      In situ vitrification wzis eliminated because 1) it is most suitable for radioactive and
       highly toxic wastes because of cost, and 2) may result in air emissions.

Ex situ Technologies                                            |                  . ' -
B      Solvent extraction was eliminated because 1) applicable primarily to heavily impacted
       spill sites, and 2) it is difficult to quantitatively recover solvent from  soil.
n      Supercritical extraction was eliminated because 1) the process has been lab tested for
       PCBs and DDT only, and 2) applicability to  VOGs in soil is unknown.
«      Addition of agricultural products was eliminated because the technology is in the
       research stages, mostly with pesticides, herbicides and sewage sludge.
n      Anaerobic digestion bioreactor was eliminated because 1) available reactor designs are
       not suitable for soils, 2) chlorinated VOCs degrade relatively slowly and may require
       additional carbon sources to support organism growth, and 2) degradation of
       chlorinated VOCs may produce toxic metabolites.    ,     I
n      Composting was eliminated because 1) most  experience is Mth wastewater treatment
       sludge, 2) utility for soil is limited because of insufficient djegradable organic  matter to
       sustain composting process.                              [
B      Land/arming was eliminated because 1) application to hazardous  waste sites is in the
       early research stage, 2) requires secondary containment, 3) expected not to apply to
       contaminated  soils but to concentrated wastes, 4) halogenated solvents ; require
       pretreatment to enhance degradation.                      !
n      Catalytic oxidation was eliminated because it is applicable lio aqueous waste streams
       only.         •       ;;        '          >           .    .|    ..  . .        ,
n      Ex situ dehalogenatioii was eliminated because 1) testing for chlorinated VOCs
       indicated removal by Volatilization, not dechlorination, 2) applicable only to PCB oils
      - and other concentrated haloaromatic compounds,  3) no research on haloaliphatic
       compounds in soil.   ;                      .             i
B      Molten salt was eliminated because 1) it is applicable to liquids, free-flowing powders,
       sludges and shredded solid wastes, 2) not suitable for soils, land 3) mobile units are not
       available.            :                                   I
B      Pyrolysis was eliminated because 1) it is applicable primarily to sludges, liquids and
       solid wastes that undergo partial or complete phase changes during thermal processing
       and 2) use on soil would encounter operational problems and high costs.
n      Wet air oxidation was eliminated because it is applicable only for aqueous  waste
       streams with less than 5 % organic compounds.           f
B      Supercritical water oxidation was eliminated  because 1) it is  primarily applicable to
       liquids, sludges and slurries and solids soluble in water, 2)  requires minimum  of 1 - 2
       % organic content to. avoid supplemental fuel requirement,  3)  operational costs for
       soils may be high because of supplemental fuel requirements.
                                                                                                            \
                                                                                                             *
022

-------
Alternative
RAA-SC-9
Standard Technology
Off-site disposal
Estimated Costs
3 Criteria
$2,100,000
to
$2,900,000
9 Criteria
eliminated
8.     If a standard technology was chosen, why?

     •"' See below regarding the use of a cap with soil vapor extraction.
9.     If an innovative technology was chosen, why?

       In situ vapor extraction with installation of an upgradient interceptor trench and cap to dewater
       the soil was selected.  The remedy was selected because: 1) in situ treatment would eliminate
       disturbance of VOC-impacted soils, 2) treatment using vapor extraction and installation of a
       cap would reduce human exposure, 3) prevent further deterioration of ground water, 4)
       permanently reduce mobility, toxicity and volume, 5) cost less, 6) easy to implement, 7)
       construction methods for the remedy are well-established and the equipment and materials are
       readily available, 8) qualified contractors exist.                                    :
10.     If an innovative technology was not chosen, why not?  At what stage was the innovative
        technology eliminated?                                              ,               .

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation:

        Innovative technologies eliminated during the initial screening include the following;

        In Situ Technologies
        •      Aerobic biodegradation was eliminated because: 1) it is inappropriate for chlorinated
               solvents because of extended time required for aerobic degradation, 2) operational
               limitations imposed by low hydraulic conductivities on nutrient/oxygen injection and
               recovery of metabolites, and 3) treatment of recovered water may be necessary.
        "      Enzymatic degradation was eliminated because, 1) it is in the research stage, 2) its
               applicability to VOCs is unknown, and 3) most research has been for extractable
               organic compounds 'and pesticides.
        »      Vegetational uptake was eliminated because it is, 1)  applicable primarily to metals, 2)
               depends upon uptake by root systems of harvestable vegetation, so it is suitable only
               for surface and near surface soils.                                     s
        •      Oxidation was eliminated because 1) it may increase mobility of metals in soils, and 2)
               chlorinated solvents incompatible with common oxidizing agents may form more
               mobile or different chlorinated products.
        •      Reduction was eliminated because: 1) it is not applicable to VOCs and 2) it may for
               toxic or more mobile VOC products.     ,                       ,       ,
                                               -4-
                                                                                                  021

-------
7.
                 Cost Estimates for RAAs That Include Innovative Techno! ogi
                            (selected remedial alternative is in bold)
                                                                    es
Alternative
RAA-SC-3
RAA-SC-4
RAA-SC-6
RAA-SC- 10b
r '
Innovative Technology
In situ vapor extraction/capping
i;
On-site vapor extraction
On-site low temperature thermal
stripping ;;
In situ vapor extraction/ground water
treatment system
Estimated Costs
t
3 Criteria
$600,01)0 to
$700,000"
$700,000 to
$900,000
$i,ooo;!ooo
to!
$i,4oo,;ooo
N/A .
9 Criteria
$690,000
$1,000,000
$2,400,000
$2,100,000
       *A range of costs was presented due to uncertainties in exact soil volumes
        RAA-SC-10 was developed at the detailed analyses phase and therefore has no three-criteria
       cost estimate. Furthermore, this: report renumbered the alternatives for the detailed analyses
       phase and, because two options |were eliminated, RAA-SC-10 is  referred to as RAA-SC-8
       IHC  JTo.                      | •                                '•
                                                                                in
How did the cost(s) compare to standard technologies?            j

          Cost Estimates for RAAs That Include Standard Technologies
                    (selected remedial alternative is in bold)    I
Alternative
RAA-SC- 1
RAA-SC-2
RAA-SC-5
RAA-SC-7
RAA-SC-8
Standard Technology
No action r ' •
-' I" '
Multilayer cap
Chemical fixation
On-site thermal destruction via rotary
kiln incineration
Off-site thermal destruction at a
RCRA-permitted rotary kiln
incineration unit
Estimated Costs
3 Criteria
$150,000 to
$200,000
$400,000 to
$450,000 1
$1,100,000
to!
$1,300,000
$6,000,000
to I
$8,000,;000
$6,800,!boO
to !
$9,000,000
9 Criteria
$300,000
$790,000
$1,900,000
eliminated
$9,700,000
020
                                           -3-

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
        Phys/Chem treatment:
        Thermal treatment:
        Disposal:
Site security, monitoring
Single-layer cap, multilayer cap, bottom grouting
Neutralization, carbon absorption, thermoset fixative, cement/silicate
fixative, thermoplastic fixation, surface microencapsulation, addition of
proton donors, mechanical aeration, dewatering, physical separation
(screens and sieves), filtration, vacuum filtration
Evaporation, rotary kiln incineration, multiple hearth incineration, high
temperature fluid wall incineration, infrared incineration, fluidized bed
incineration, advanced electrical reactor, plasma arc, circulating bed
combustor
Excavation, dredging, RCRA landfill, resource recovery facility,
asphalt batch plant
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Biodegradation, vegetative uptake, in situ enzymatic degradation,
                               landfarming, addition of agricultural products and by-products, ex situ
                               anaerobic digestion, composting
        Chemical treatment:    Dehalogenation, soil flushing (solvent), vapor vacuum extraction,
                               hydrolysis, catalytic oxidation, solvent extraction, supercritical water
                               oxidation, oxidation, reduction
        Thermal treatment:     In situ vitrification, soil cooling, artificial ground freezing, low
                               temperature thermal stripping, supercritical extraction, molten salt,
                               molten glass, pyrolysis, wet air oxidation
         What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
         implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
         estimated costs then are .recalculated during an evaluation based on nine criteria established by
         the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
         ARARs; protectiveness of human health and the environment;  reduction in contaminant
         mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
         community acceptance.                                  .
                                                 -2-
                                                                                                   019

-------
                                     Mottolo Pig Farm
                                   '' -         '         ~
                                  Raymond, New Hampshire
                                           Region 1
  GENERAL SITE INFORMATION
 1.
What were the principal contaminants,
contaminant levels, and media being
addressed in this feasibility study?

Maximum concentrations of principal
contaminants were:           ;
                           11
                           11 •
Soil/Sediment (rag/kg)       • i|-
        Trichloroethene       f
        Ethylbenzene         140
        Toluene              47
        1,1,1-TrichIoroethane  0.064
        1,1-Dichloroethane    0.36
        Methylene Chloride
        Tetrachloroethene
        Xylenes
        Acetone
        Vinyl Chloride
        1,2-Dichloroethene
                    .t
                    t
                    270
                    t
                    *
                                                                     History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     4/10/85
                     7/22/87
                     2/1/91
                     3/29/91
             Background
                j                ••  • '
Fund-lead       . I
PRPs:  Richard AJ Mottolo; KJ. Quinn
       Company, incorporated; Service
       Pumping aiild Drain Company,
       Inc.      i
FS prepared by:  Balsam
       Environmental Consultants
       "These'compounds were not detected in the soils but were detected at significant
       concentrations in ground water. jjSoil cleanup levels were developed for both of these
       TMaximum concentrations of these contaminants were not found
       What volume of material is to be

       The volume of material to be

       •      3,400 to 4,000 cubic  yards
                             remediated?

                         remediated included:

                              of soil and sediment
3.      What, type of site is this?

       Uncontrolled Waste Site.  A
      . 1975 and 1979.
                        former piggery that was used as a hazardous waste site between
  018
                                           -i-

-------
       Contaminant concentrations in sediment were all below health-based risk levels  The
       estimated blood lead level from exposure to lead in sediments was below levels believed to
       cause adverse health effects.      ,

       Cleanup levels were set for ground water but not for sediment.


13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:        -

       •     None                                                   .                 ,'•'

       Standard technologies eliminated because of cleanup goals include:

        •      None       .."                     .                     '


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:
                                  '                         • '    ^           •."•.'
               Waste left in place/institutional controls


 16.     How are measures compared?

         The chosen remedy is the most comprehensive and protective option.  The remedy uses  • ^
         containment and migration management to address site contamination. One alternative, RAA-
         5A, proposed a more protective cap,  but was eliminated because the cap design would cause
         the permanent loss of wetlands.

         RAAs also were compared based on  the Hydrologic Evaluation of Landfill Performance
         (HELP) computer model, which estimated how much leachate would be generated and where
         it would  migrate.                                                                   -


  17.    What technical considerations were factors in selecting a remedy? Were technical
         considerations primary, in the selection^/ the remedy?

         The primary .consideration was the location of the landfill, which is surrounded by wetlands
         and surface water bodies.  As was previously discussed (#15), two proposed RAAs were
         eliminated for not meeting site-specific wetland and floodplain ARARs.
                                                                                                   017

-------
 10.
11.
12.
 If an innovative technology was not chosen, why not?  At what stage was the technology
 eliminated?                   i                                  (                '•.-.,'.

 Innovative technologies could be eliminated from the remedial technology process at three
 stages: during the initial screening; during the screening of the three criteria of effectiveness,
 implementability, and cost; or during the detailed evaluation        j

 Innovative technologies eliminated from consideration during the initial screening include the
 following:                »   :

 •      In situ soil flushing wa!s eliminated because of the possibility that contaminants flushed
        into the aquifer could not be captured and might intensify the problem; the
        heterogeneous and variable nature of landfill materials and difficulty in extracting the
        contaminated ground water.                              [
 •      Vacuum extraction was; eliminated because the process option is not an effective or
        implementable treatment method for the  contamination in the landfill.
 •      In situ biodegradation was eliminated because the monitoring and control of all
        elements necessary for effective degradation would be difficult; because of the
        fluctuating water table,  the location of source material both above and below the water
        table; degradation products are more toxic than'the parent compound.
 •      Low temperature thermal aeration was eliminated because it would require excavation
        and would not be implementable because of the volume and nature of the landfill
        material.                                                !
 •      On-site biodegradation  was eliminated because it would require excavation and"would
        not be implementable, because of the volume and nature of the landfill material.
                              eliminated during the screening for three crileria include the following
Innovative technologies elii

•     .None

Innovative technologies elirninajted during the detailed analyses include the following:

•     None
Which of the nine criteria were
to meet one of the nine criteria
which criterion?  Which of the
       Protection of human health and[
       Final decision was based on
                                     weighted most heavily in selecting the
                                     result in the elimination of the innovative
                                    criteria supported the use of a standard
                              the environment, implementability,
                           community input into the design of the
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
       For carcinogens, an excess upper bound individual lifetime cancer risk
       was acceptable.  For noncarcinpgens, a Hazard Index less than or eqi al
 016
   technology? Did failure
      technology ? If so,
    technology?
community acceptance.
 cap.
                                                                  of between KT4 to 10"6
                                                                 1 to 1.0 was acceptable.
                                              -4-

-------
        Alternative
        RAA-4
        RAA-4A
        RAA-5
        RAA-5A
         Standard Technology
Modify the top of the existing cap/long-
term maintenance/monitoring of gas
collection/monitor ground and surface
water quality/perimeter fence/surface
drainage improvements/leachate
collection/off-site treatment and disposal
Same as RAA-4, also includes ground
water extraction system/on-site leachate
and ground water treatment
Upgrade entire cap/perimeter fence/monitor
gas collection/monitor ground and surface
water quality       	   •      	
 Same as RAA-5, also includes ground
 water extraction system/on-site ground
 water treatment        :
        Selected        Reconstruction of the existing landfill
        Remedy        cap over the entire 60 acres/cap
                        maintenance/surface drainage system/
                        gas collection and monitoring/leachate
                        collection, treatment and disposal/
                        perimeter fence/long-term monitoring of
                        surface and ground water
                                        '

       The selected remedy was developed during the ROD.
                                                                     Estimated Costs
                                                                 3 Criteria
                                                                   ;N/A
                                                                    N/A
                                                                    N/A
                                                                    N/A
                                              N/A
9 Criteria
$5,637,179
$13,567,296
$13,700,349
$24,301,892
$12,553,524a
8.      If a standard technology was chosen, why?               .

       A standard remedy was selected that includes: reconstruction of the landfill cap, surface
       drainage control and leachate collection.  This remedy was selected because: 1) it prevents
       direct contact and ingestion of site contaminants, 2) it reduces the volume of leachate, 3) will
       minimize erosion of the landfill into surrounding wetlands, 4) involves little construction
       which avoids adverse affects on the wetlands.
        If an innovative technology was chosen, why?

        No innovative technologies were chosen.
                                              -3-
                                                                                              015

-------
        Dir.^osal:
        Ph    al treatment:
        Thermal treatment:
Excavation and off-site disposal
In situ solidification
Incineration
        Was an innovative technology considered in the FS? If so, which technology?
        Innovative technologies considered during the identification and
        feasible technologies were:     ;:
                                      scree ning of technically
       Biological treatment:   In situ biodegradation, on-site biodegradation
       Chemical treatment:    In situ soil flushing
       Thermal treatment:     Vacuum'extraction (solvents), in situ thermal
                                           aeration
6.       What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible
        (prior to the formulation of RAAs), the FS does not quantify costs.
        formulated, costs typically are estimated as part of a three-criteria sen
        (effectiveness, implementability,and cost) to identify alternatives that
        evaluation.  In this case, costs were calculated during an evaluation
        established by the NCR        :
                                       tecl nologies are identified
                                         After the RAAs have been
                                           «ning process
                                           merit a more detailed
                                         biased on the nine criteria
       No innovative technologies were incorporated into remedial alternatives.
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Established Technologies
                            (selected remedial alternative is in bold)

Alternative
RAA-1
RAA-2
RAA-3
RAA-3A
i i
Standard Technology
No action •'• • '
Complete existing cap/long-term
maintenance/perimeter fence/monitoring of
gas collection/monitor ground and surface
water quality j:
Complete existing cap/perimeter fence/
long-term maintenance/monitoring of gas
collection/monitor ground and surface
water quality/leachate cpllection/off-site
treatment andidisposal of leachate/surface
drainage improvement
Same as RAA-3, also includes ground
water extraction system/leachate and
ground water treatment on site
Estimated Costs
3 Criteria
N/A
N/A
i
N/A
N/A
• °14 •'. '• ik'" -2- • •-• ' ;: '
9 Criteria
$0
$2,231,611 .
$5,190,155
$13,151,862
-

-------
                          Iron Horse Park (Shaffer Landfill)
                                          OU-2

                                  Billerica, Massachusetts
                                         Region 1
GENERAL SITE INFORMATION

7.      What were the principal contaminants,
       contaminant levels, and met
       this feasibility study?

       Sediment (mg/kg)

       1,1 -Dichloroethene
       Trans-1,2-dichloroethene
       1,2-Dichloroethene
       Toluene
       Acetone
       Methyl ethyl ketone
       Acenaphthene
       Anthracene
       Fluoranthene
       Benzo(a)pyrene
       Indeno(l,2,3-cd)pyrene  x
       Benzo(g,h,i)perylene
tinants,
addressed in
<


0.1
0.57
0.17
0.039
0.63
0.22
3.3
4.2
2.2
11
4.5

Site History
NPL Proposed: N/A-
NPL Final: 9/94
FS: 1/10/91
ROD: 6/27/91
'
Background

EPA Fund-lead
PRPs: Not listed
FS prepared by: Camp Dresser &
McKee Inc.


, ,
•5.3 • "..••" ;
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      5,000,000 cubic yards of waste material
3.     What type of site is this?

       Municipal Landfill.. Operational Unit 2 (OU-2) is a former landfill and one of three units at
       the site.
TECHNOLOGY SELECTION

4.      What established technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                             ^          " •
       Access restriction:
       Containment:
Fencing, deed restrictions
Capping


                -1-
                                                                                            013

-------
16.    How are alternatives compared?                        •   •     j

       Only alternatives that provided protection to human health and the environment, attained
       ARARs, and had proven to be reliable were considered appropriate i^s site remedies. Cost
       effectiveness was measured by comparing the level of protectivenesii provided with the cost of
       an alternative.  Impacts on nearby populations were considered when comparing methods for
       reducing exposures to contaminated landfill materials and sediment^  The amount of technical
       and support equipment resources required was considered when comparing installation of a
       slurry wall versus an interceptor trench/barrier wall.               j,
17.
What technical considerations had to be considered in the selection of a remedy?  Were
technical considerations primary in the selection of the remedy?    !
                           • n                                . 'i
A portion of the site lies within a 100 year floodplain of the Cocheco River, 500 feet to the
east.  The Bellamy reservoir, a Calderwood well, and four wetland systems are within the
vicinity of the site.  The site overlies both an upper and a lower aquifer that are separated by
impermeable clay.  RAA-SC-5 and RAA-SG-5A included a slurry wall that was believed to be
potentially detrimental to the clay layer. Technical considerations (beyond the volume of
landfill material) could not be considered primary in the selection ofia remedy at this site.
   012
                                            -7-

-------
12.
technologies were considered in the nine criteria evaluation.  Only standard technologies were
considered at this point.


What clean-up goals were selected? If the clean-up goal was based on an ARAR, what was
that ARAR?  What risk level was selected to establish clean-up goals?
Contaminant
Non-Carcinogens:
Arsenic
Clean-up Level (ppm)
:
50
ARAR or Other Basis

ERLa
               The environmental risk level (ERL) is a level deemed protective for environmental
               receptors and uses National Oceanic and Atmospheric Administration standards.

       For carcinogens an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable. For non-carcinogens a Hazard Index less than  or equal to 1.0 was acceptable.
13.     Was the innovative technology eliminated because of the clean-up goals?  Could the standard
        technology meet the clean-up goals?

        Innovative technologies were eliminated primarily because they were not applicable to the
        range and volume of contaminants present at the site.  No innovative technologies were
        eliminated because of cleanup goals.  The technology selected for remediation of contaminated
        perimeter drainage sediments was excavation and deposition in the landfill prior to capping.
        This standard remedy could meet cleanup goals.                             .
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        A treatability study was conducted by HMM to provide data to evaluate treatment options for
        the site and to reduce cost and performance uncertainties for treatment options. The study
        consisted of an additional round of sediment, surface water, and groundwater sampling. The
        study was aimed at evaluating the implementability and feasibility of groundwater remedial
        technologies.
 75.    What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

                Cost effectiveness
                Impact on nearby populations
                Proven reliability
                Technical and support equipment resources
                                                                                                Oil
                                               -6-

-------
 10.     Ifan innovative technology-was,not chosen, why?        :    ....-

         Innovative technologies could be eliminated from the remedial technology selection process at           - <
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, :and cost; or during the detailed evaluation.
              .      .                  'i !•'  •        '            '            !»     "      '             ' -

         Innovative technologies eliminated during the initial screening include:

         Solid Waste:                                                    [

                      '               ••;!            '  •         ;    ••'•    ''I  :       :'     •'.    ••  .   '"  '  ••-..  ,
         •      Wet air oxidation is typically used for treating pumpable aqueous and sludge wastes
                It was eliminated because it is not feasible for treating mixtures of waste types present
                in  solid waste matrices.:                                  i    .
         •      Bioremediation was eliminated because it has only limited effectiveness for chlorinated
                solvents (low biodegradation rate) and metals.              '
         •      Dechlorination was eliniiinated because it specifically addresses chlorinated
                polyaromatic constituents that do not comprise the majority of contaminants found at
                the Dover site.  It also has relatively high capital and O&M costs.
         •      Solvent extraction on a large scale has shown limited success^ it has relatively high
                implementation costs, and residual solvent adhering to treated soils presents a process
                problem.               i                                  !
         •      Thermal desorption was eliminated because its effectiveness is limited by the vapor
                pressure of the contaminants of concern and temperatures necessary to vaporize
                contaminants must not exceed the flashpoint of any constituent.
         •      Soil flushing has limited success  at high cost. The composition of the landfill is                   .
                undetermined and soil flushing may not work because it is dependent on solubility and             )
                surfactant contact that is adversely affected by channeling in the soil matrix
        •      Vacuum  extraction was eliminated because it applies selectively to volatile compounds
                and will not address metal contaminants.  Further, it can only ^be operated at limited
                depths, which precludes its use at greater depths within the laiiidfill.
        •       In situ vitrification was eliminated because it has never been implemented on a large
                scale.  Further, it requires significant electrical power and is therefore prohibitively
                expensive.               ;                                  I"                    ,
                                             ;                     .'"•!•'
        Sediment:                                                                       -
                                      'ii  '        '         •      '' '       •'        •         • •
        •      In situ vitrification cannot be used because of the saturated state of contaminated
               sediments.             ,ii           .         -              i
        •      Oxidation/reduction was eliminated because it shows only limited promise for metal
               contaminants and does not address organic constituents.      I

        No innovative technologies were incorporated into RAAs.

                       '               ii    •   •  '•
                                      i !•                    .                -         .•.
11.     Which of the nine criteria were weighted'highest in selection of the technology? Did'one of
        the nine  criteria eliminate the innovative technology from being chosen? If so,' which one?
        Which of the criteria supported the use of a standard technology?    t
                                                                         :,  ..           •

                                                                                                             \
       <~~^,  uic ciucim ui cosi, impiementability, and long-term effectiveness were most heavily              )
       weighted (pnmanly because there was little difference in other criteria!  No innovative
   010
                                              -5-

-------
=====
Alternative
RAA-SC-T
•
or
RAA-SC-7A
RAA-SC-8
RAA-SC-8A
RAATSC-9
=======
	 , 	 	 — 	 	 ~ —
Standard Technology
Long-term monitoring/recontouring
of landfill/multi-layer cap/perimeter
barrier/sediment consolidation/
methane gas collection and ventila-
tion/interceptor trench/groundwater
treatment/discharge to Cocheco River
Same as SC-7 except discharge to
POTW
Long-term monitoring/excavation of
hazardous materials and sediment/off-
site treatment and disposal at RCRA
facility/on-site RCRA landfill for
noncombustible materials
Same as SC-8 with discharge to POTW
Excavation/off-site RCRA TSD
facility/off-site RCRA disposal
. 	
Estimated Costs
3 Criteria
$22,270,600
$22,171,900
$301,350,700
$302,795,000
$1,038,390,000
===============
9 Criteria
$22,270,600
$22,171,900
eliminated
eliminated
eliminated
========
       The decision to discharge to the Cocheco River or to the POTW will be made during pre-
       design studies.

8.      If a standard technology was chosen, why?                       „          .

       RAA-SC-7 or RAA-SC-7A was selected;^ difference between these alternatives is the
       ultimate discharge location of treated water, which will be determined during design.  The
       selected remedy combines the most cost-effective remedial alternatives that are both protective
       of human health and the environment and attain ARARs.  Alternatives RAA-SC-5 and RAA-
       SC-5A would provide similar protection to human health and the environment and ARAR
       attainment, however, they would be much more costly and more difficult to implement.
       Obtaining clay  of sufficient volumes for the low permeability layer of the cap  may be difficult
       under RAA-SC-5 and RAA-SC-5A.  The interceptor trench/barrier wall of RAA-SC-7 and
       RAA-SC-7 would require less technical and support equipment resources to install than the
       slurry wall of RAA-SC-5 and RAA-SC-5A.  The limited excavation provided for in RAA-SC-
       7 and RAA-SC-7 would be much easier and quicker to implement.

       Other alternative remedial strategies  that were proposed, RAA-SC-1 and RAA-SC-2,  were less
       expensive.  However, RAA-SC-1 did not meet any ARARs and provided no protection of
       human or environmental health, and RAA-SC-2 met only a few ARARs and provided limited
       protection of human health and no protection of the environment.
        If an innovative technology was chosen, why?

        No innovative technologies were selected or included in the RAAs.
                                                                                              009
                                             -4-

-------
7.
1 • . . " ' • 1
i • , r . • " ••
How did the cost(s) compare to standard technologies? ' \
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Alternative
RAA-SC-1
RAA-SC-2
RAA-SC-3
RAA-SC-3A
RAA-SC-4
RAA-SC-4A
RAA-SC-5
RAA-SC-5A
RAA-SC-6
RAA-SC-6A
Standard Technology
No action with long-term monitoring ,
Limited action with long-term
monitoring 
-------
       Thermal treatment:

       Disposal:

       Sediment

       Access restrictions:
       Containment:
       Sediment control:
       Chemical treatment:

       Disposal:
Rotary kiln incineration, fluidized incineration, multiple hearth
incineration, infrared treatment
On-site RCRA landfill, off-site disposal at an existing RCRA landfill
Fencing, deed restrictions
Soil cover cap, single-barrier cover cap
Dikes, berms                                              '
Thermoplastic/thermosets solidification, surface microencapsulation,
cement and silicate fixatives, oxidation reduction
On-site or off-site at.a RCRA disposal facility
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Solid Waste

        Biological treatment:   On-site bioremediation
        Chemical treatment:    Wet air oxidation, dechlorination, solvent extraction
        Physical treatment:     Soil flushing, vacuum vapor extraction
        Thermal treatment:     Thermal desorption, in situ vitrification
                                    \
        Sediment

        Thermal treatment:     In situ vitrification
        Chemical treatment:    Oxidation/reduction
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of the three criteria (effectiveness, implementability,
        cost) screening process to identify alternatives of sufficient merit to undergo further detailed
        evaluation. The estimated costs are recalculated during evaluation by the nine criteria
        established by the NCP.                                      .                    .

        No innovative technologies were included in the RAAs^ therefore, no cost esttmates were made
        for innovative technologies.
                                               -2-
                                                                                              007

-------
 GENERAL SITE INFORMATION
                                 Dover Municipal Landfill
                                    Dover, New Hampshire
                                        v  Region 1
 1.
    What were the principal contaminants,
    contaminant levels, and media being
    addressed in this feasibility study?

    No contamination was found in off-site
    surface soils.  Landfill contents were not
    sampled.  Maximum concentrations of
    principal contaminants were:  ;
                               i i-
                               ., ;  *
    Sediments (mg/kg):

    Arsenic               210   '!'
    Cadmium    >         3.31   !i
    Methyl ethyl ketone    1.7  •;;
    Trichloromethane      0.4    i!
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                                                                  Site History
                                               12/30/82
                                               9/8/83
                                               2/28/91
                                               9/10/91
                                                                 Background
                                                    PRP-lead       |     :
                                                    PRPs: Dover Landfill PRP Group
                                                    FS prepared by:  JHMM Associates, Inc.
2.
   What volume of material is to be remediated?

   The volume of material to be remediated included:
                      ''         ' '                     .

   •      1,300 cubic yards of perimeter drainage sediment
   •      3.5 million cubic yards | soil, sludge, and debris in the landfill
3.     What type of site is this?       ;            '  :   -

       Municipal Landfill.  Inactive municipal landfill  (accepted some it
                                                           industrial waste).
TECHNOLOGY SELECTION         ;

4,      What standard technologies weitf considered for selection in this FSt
       Standard technologies considered during the identification and
       technologies were:            '•;
   Solid Waste

   Access restrictions:
   Containment:
   Chemical treatment:
   Physical  treatment:

006
Fencing, deed restrictions
Clay and soil capping, single-layer synthetic
.Cement land silicate fixatives, thermoplastic
Mechanical aeration
                                            -i-
                                                                                                        )
                                                          screenmg of technically feasible
                                                                    < ap, multi-layer cap
                                                                   s( lidification

-------
       Standard technologies eliminated because of cleanup goals include:             ..

       •      None


14.     Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.


75.     What, measures/criteria we're used to compare alternatives?

       The following measures were used to compare the alternatives:

               Total cost  .
               Time to design/construct/operate


16.    How are measures compared?

       The chosen alternative was preferred because it would achieve remediation goals in the
        shortest amount of time (1  to 3 years compared to 18 to 73 years). The selected remedy was
        also the least expensive of the alternatives offering containment and ground water treatment.
        While the capital costs for the selected remedy were higher due to the construction of a slurry
        wall, the operating and management costs were lower due to the reduced treatment time.
                      ' *                   ,                   '       -
        A ground water flow model, MODFLOW, was used to compare the effectiveness of remedial
        alternatives RAA-3, RAA-4, RAA^5, and RAA-6.


 17.    What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Although not primary, a shallow  water table required components of the remedy to lower the
        water table for reduction of leachate mto the groundwater and seeps.
                                                                                              005
                                               -5--         '  '        •    •'  '  '  '    - .     '•

-------
6.
7,
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                                        '                              'l .              '
       >                 - " '             -                                I
        Access restriction:     Institutional controls (site security, deed restrictions)
        Containment:          Multilayer cap, slurry wall
        Disposal:              Excavation
        Physical treatment:  s  , Natural flushing


 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
        No innovative technologies were considered for remedial action alternatives.
 What was the cost estimate for the innovative technology?

 During the initial screening process, in which technically feasible technologies are identified
 (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
 formulated, costs are typically estimated as part of a three-criteria screening process
 (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
 evaluation. For this site, the three criteria process was eliminated arid the FS went directly
 from initial screening to a detailed evaluation.  Costs then were estimated during an evaluation
 based on the nine criteria established by the NCP.                           -

 No innovative technologies were considered for remedial action alteatives.
How did the cost(s) compare to standard technologies?

          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)
          Alternative
         RAA-1,3-A
                           Standard Technology
                  No action
                         Minimal action/institutional controls/
                         deed restrictions/environmental
                         monitoring
                                                                       Esltimated Costs
                                                                   3 Criteria
                                                                      N/A
                                                               N/A
9 Criteria
                                                                               $0
$1,147,000
    002
                                             -2-

-------
                           Brunswick Naval Air Station
                                        OU-1

                                   Brunswick, Maine
                                       Region 1
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediment (rag/kg)

       Mercury              4.7
       PAHs                24

       Other contaminants at site without
       specified concentrations:

       Arsenic
       Cadmium
       Chromium
       Cyanide
       Lead
       Manganese
       Mercury
       Nickel
       Vanadium
       Zinc
       DDT
       PCBs
        1,1,2,2 Tetrachloroetharie
                                                              Site History
                                                 NPL Proposed:
                                                 NPL Final:
                                                 FS:
                                                 ROD:
N/A
1987
10/91
6/16/92
                                                              Background

                                                 Federal Facility
                                                 PRPs:  U.S. Navy
                                                 FS prepared by:  B.C. Jordan Co.
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      300,000 cubic yards of waste
3.     What type of site is this?

       Military.  A landfill at an active Naval Air Station.



                                            -1-
                 001

-------

-------
Region/Site                                   Primary Technologies Selected


signet^   -                           .       |°!| ^ ^^  •••;;;;:::::; :•:'1213


vSwaters & Ro^'  °'                   foil vapor extraction	
Westinghouse Electric Corp. (Sunnyvale Plant)    Incineration...	, •••



Region 10

Bangor Ordnance Disposal, OU-1 "               Soil washing ........:.......	1241
                   •                           Disposal
Bunker Hill Mining & Metallurgical, OU-1        Capping	••••••		••    _
Bunker Hill Mining & Metallurgical, OU-2        Capping .	• • •
Joseph Forest Products                •         Unspecified treatment	,;. - *  1260
Umatilla Army Depot  (Lagoons), OU-1           Solid-phase biodegradation  .	   266
Union Pacific Railroad Co.                      Soil flushing	, -  - - - • • •  V"
                                              Disposal     -                             g
Wyckoff Co./Eagle Harbor, OU-3                Capping . . . . . ... . -	
   '   •          •                            Solidification/stabilization

 Yakima Plating Co.                            DisPosal •••••••••••	' 129°

                                              Vlll

-------
 Region/Site

 Mid-America Tanning Co.
 People's Natural Gas Co., OU-1
 Pester Refinery Co.
 Shaw Avenue Dump, OU-1
 Region 8

 Anaconda Co. Smelter, OU-11
 Broderick Wood Products, OU-2

 Central City-Clear Creek
 Chemical Sales  Co., OU-1
 Denver Radium Site, OU-8
 Denver Radium Site, OU-9
 Hill Air Force Base, OU-3
 Idaho Pole Co,

 Ogden Defense  Depot, OU-1
 Ogden Defense  Depot, OU-3

 Ogden Defense  Depot, OU-4
 Portland Cement (Kiln Dust 2 & 3), OU-2
 Rocky Flats Plant (USDOE), OU-2
.Silver Bow Creek/Butte Area, OU-12
 Wasatch Chemical Co. (Lot 6)
Region 9

Advanced'Micro Devices, Inc.
Atlas Asbestos Mine, Mine Area OU
FMC (Fresno Plan!:)
Hassayampa Landfill
Indian  Bend Wash Area, OUs-1, 4, 5, 6
Iron Mountain Mine, Boulder Creek OU
Jasco Chemical Corp.
Lawrence Livermore Nat. Lab. (USDOE)
Monolithic Memories, OU-1
National Semiconductor Corp., OU-1
Purity Oil Sales, Inc., OU-2
Rhone-Poulenc Inc.(Zoecon) Sandoz, OU-1

Sacramento Army Depot, OU-3
Sacramento Army Depot, OU-4
 Primary Technologies Selected         ,  page
                    i          .   '  •' '     '  '
 In situ solidification/stabilization ........  1003
 Solidification/stabilization
 Disposal                                   '
 In situ biodegradation I	1Q08
 Soil flushing ....... I	  1014
 In situ biodegradation 1
 Disposal                        ,   '  . '
 In situ solidification/stabilization	  1019
                    :!            .     '.    "  '
                    'i              ,
                    i
                    \           • "°
                    !            '•'•'•'
 Solidification/stabilization .	'.'.  1024
 Biodegradation  .....I ............... 1033
 Solidification/stabilization
 Capping .. .	. .j.  . . ..... . . . . .... .  1044
 Soil vapor extraction  i ............... 1050
 Solidification/stabilization	 1056
 Capping . .	(.-:...		1064
 Capping			 1069
 Soil flushing	1	^ ....... 1073
 Land treatment
 Disposal	, .... .". ... .... . . ..... 1080.
 Disposal	... .	 1086
 Incineration
 Disposal ...	......:.........  1092
 Solidification/stabilization . .....  	  1099
 Soil vapor extraction  .j	  HQ5
 Solidification/stabilization	  1110
 In situ vitrification  .. j	  1117
 Land treatment       j   -.        ,




 Incineration	 i	  1125
 Capping . ...	  H30
 Soil washing  ...... .L	  1135
 Soil vapor extraction .].	  1142
 Soil vapor extraction .[	  1149
 Capping	i. .	 ....  1155
 Solid phase biodegradation ............  1160
 Soil vapor extraction .1 ..............  1166
 Soil vapor extraction	,  1171
 Soil vapor extraction	  1179
 Soil vapor extraction .!.....	  1187
Capping		L ...............  1193
Solidification/stabilization
Soil vapor extraction ................  1199
Soil washing	 L	  1206
                                           Vll

-------
Region/Site                                   Primary Technologies Selected            Page

Peerless Plating Co.                            Soil vapor extraction	 824
                                             Solidification/stabilization
Rasmussen's Dump, OU-1                      Capping ,	,		.....:... 831
Savanna Army Depot Activity, OU-1             Incineration		... 836
South Andover Site, OU-2                      Disposal	 843
                                             Biodegradation
Spickler Landfill, OU-1                        Solidification/stabilization	.......... 848
Stoughton City Landfill                        Capping	 854
Sturgis Municipal Wells                        Soil vapor extraction	 . . . . 859
                                             Disposal                               ^
Tar Lake, OU-1                               Disposal .;.......		• • 865
Thermo-Chem, Inc., OU-1                      Incineration		 . . . .:. . . 871
                                              Soil vapor extraction
Torch Lake, OU-1 & OU-3                      Capping	, .,	............... 877
                                              Disposal                             ,
Tri-County Landfill Co.AVaste Mgmt. IL          Capping	  882
Twin Cities AF Reserve Base (SARL)            Institutional controls	  890
Verona Well Field, OU-2                    >   Soil vapor extraction	  895
Zanesville Well Field                  • --       Soil vapor extraction . . .		  902
                                              Soil washing


Region 6

Cimarron Mining Corp.,  OU-2                   Solidification/stabilization...	. .  908
Double Eagle Refinery Co., OU-1                Solidification/stabilization	 . .	913
Fourth Street Abandoned Refinery, OU-1         Solidification/stabilization	  919
 Gulf Coast Vacuum Services, OU-1              Incineration		.	925
                                              In, situ solidification/stabilization
 Gulf Coast Vacuum Services, OU-2              Capping	 933
 Mosley Road Sanitary Landfill                  Capping	,	;	 938
 Oklahoma Refining Co.                         In situ solidification/stabilization  . . .	943
                                    i          In situ biodegradation
 Petro-Chemical Systems, Inc. (TB), OU-2         Soil vapor extraction		951
                                              Capping
 Prewitt Abandoned Refinery                    Disposal	 957
                                              Land treatment
                                              Soil vapor extraction


 Region 7

 29th & Mead GW Contamination, OU-2          Soil vapor extraction   ............ .. . .. 966
 E.I. Dupont DeNernours & Co. (Road X23)        Solidification/stabilization .  .	,. .	. 972
                                               Disposal
 Ellisville Site                                  Incineration ...:....	•. . .'	;..;.. 978
 Hastings GW Contamination, OU-10 & OU-2      Capping  .............	983
 John Deere (Ottumwa Works Landfill)            Institutional controls	 988
 Lee Chemical                                 Soil flushing		993
 Lehigh Portland Cement Co.                     Capping	 998
                                              VI

-------
 Region/Site

 Oak Ridge Reservation (USDOE), OU-2
 Robins AFB (LF #4/Sludge Lagoon), OU-1

 Sangamo Weston, Inc./12 Mile Creek, OU-1
 Standard Auto Bumper Corp., OU-1
 Wrigley Charcoal Plant
 Primary Technologies Selected
 Capping	
 In situ solidification/stabilization .  .
 Soil vapor extraction
,Low temperature thermal desorption
 Disposal	 . '.	
 Disposal	
 Incineration
                                                        j
 Region 5

 Acme Solvent Reclaiming (Mor. Plant), OU-2

 Allied Chemical & Ironton Coke, OU-2


 American Chemical.Service, Inc.
 Berlin & Farro
-Buckeye Reclamation, OU-1
 Butterworth #2 Landfill
 Canrielton  Industries, Inc.           ;
 Carter Industrials, Inc.
 Central Illinois Public Service Co.
 Chem Central
 City Disposal Corp. Landfill
 Clare Water Supply, OU-2          ;
 Dakhue  Sanitary Landfill, OU-1
 Electrovoice, OU-1

 Fadrowski Drum  Disposal           ,

 Folkertsma Refuse
 Fultz Landfill, OU-1
 G&H Landfill,.OU-1

 H. Brown  Co., Inc.
 Kentwood  Landfill
 Kohler Co. Landfill, OU-1
 LaGrande Sanitary Landfill
 Lemberger Landfill, Inc., OU-1
 Main Street Well Field, OU-2
                     1
 Michigan Disposal Service (Cork St. LF)
 Motor Wheel, Inc.
 Muskego Sanitary Landfill

 Pagel's Pit, OU-1
Low temperature thermal desorption
Soil vapor extraction
In situ biodegradation
Incineration
Land treatment
Soil vapor extraction
Low temperature thermal desorption
Solidification/stabilization
Disposal
Solidification/stabilizat on
Capping . . . .-'. . . .
Capping .....'....
Disposal • •	
Low temperature them: al desorption
Disposal . .	
Soil vapor extraction
Soil vapor extraction
Soil vapor extraction
Capping	
Soil vapor extraction
Solidification/stabilization
Unspecified  treatment
Capping ,
Capping	
Capping	
Capping .........
Incineration
Solidification/stabilization
Capping . .	I. .
Capping	I; .
Solidification/stabilization
Capping	
Soil1 vapor extraction
Disposal
Capping	;
Capping	
Capping .........
Soil vapor extraction  |
Capping	 . .",|..........;.....  819
649

659


667
676
683
689
695
702
710
715
720
725.
731
735-

744

749
755
761

767
775
780
785
789
795

802
808
813

-------
                                                                                                        -ft
Region/Site

Raymark, OU-1
Resin Disposal, OU-1
Rhinehart Tire Fire Dump, OU-2
Saunders Supply Co.

Strasburg Landfill, OU-3
'Tonolli Corp.
 Whitmoyer Laboratories, OU-2

 Whitmoyer Laboratories, OU-3



 Region 4

 Agrico Chemical Co., OU-1
 Alabama Army Ammunition Plant, OU-1

 Arlington Blending & Packaging

 Benfield Industries, Inc.
 Carolina Transformer Co.           ..  ,
 Carrier Air Conditioning Co.
 Charles Macon Lagoon & Drum Storage
 Ciba-Geigy Corp. (Mclntosh Plant), OU-2
 Ciba-Geigy Corp. (Mclntosh Plant), OU-4
 Florida Steel Corp., OU-1
 Geigy Chemical Corp. (Aberdeen Plant)
 Golden Strip Septic Tank Service
 Interstate Lead Co. (ILCO), OU-1

 JFD Electronics/Channel Master

 Marine Corps Logistics Base, OU-3

 Maxey Flats Nuclear Disposal
 Medley Farm Drum Dump, OU-1
Primary Technologies Selected
Soil vapor extraction	 420
Capping	 427
Disposal	...:.... 436
Low temperature thermal desorption  	440
Dechlorination
Capping	 447
Solidification/stabilization . .  .	452
Capping
Disposal
Incineration	 462
Solidification/stabilization
Biodegradation  ..................... 471
Solidification/stabilization




Solidification/stabilization	 481
Incineration		 487
Disposal
Low temperature thermal desorption  ...... 492
Solidification/stabilization
Soil washing	• • 501
Solvent extraction  	.."	507
Solidification/stabilization
Disposal
Soil vapor extraction  . .	...;.... 513
Land treatment	 519
Soil vapor extraction
Disposal
Incineration	 527
 Solidification/stabilization
 Soil flushing
 Soil vapor extraction
 In situ biodegradation
 Incineration	.-  555
 In situ solidification/stabilization
 Low temperature thermal desorption1
 Soil flushing      /
 Solidification/stabilization	  564
 Disposal	..:........  570
 Solidification/stabilization	577
 Solidification/stabilization	 584
.Capping   ,       '   '    -
 Chemical treatment (ex situ)  ...... . . . .-, - 589
 Solidification/stabilization
 Capping  . .	594
 Disposal
 Capping	• • • • 602
 Soil vapor extraction	 609
                                               IV

-------
Region/Site
                                              Primary Technologies Selected
                                                                                     Page
 Juncos Landfill, OU-1                          Capping  ...... ... ........ ......... 192
 Kin-Buc Landfill, OU-2                         Disposal  .......... .....' ...... ..... 197
 Mattiace Petrochemical Co., Inc., OU-1           Soil vapor extraction  L . . : ............. 202
 Nascolite Corp.                                Disposal  ......... 1 ............ ..... 208
                                              Solidification/stabilization
 Naval Air Engineering Center, OU-1              Soil flushing . . . ...... ........ ...... 213
 Naval Air Engineering Center, OU-2              Soil flushing ..... .[.......... ...... 218
 ML Industries, OU-2                            Solidification/stabilization ...... ..... ... 223
 Pasley Solvents & Chemical, Inc.                 Soil vapor extraction  .......... . ....... 229
 Plattsburgh Air Force Base, OU-1                 Capping  ........ . i . . ..... . . ..... . . 234
 Plattsburgh Air Force Base, OU-3                Capping  ..... ....[.... . .  ........ . . 238
 Preferred Plating Corp., OU-2                   Solidification/stabilization ....... ....... 242
 Ramapo Landfill                               Capping  ........;[.... .......... ... 248
 Roebling Steel Co., OU-2                   ,    Disposal  ........ !'.... ............ . 253
                                              Solidification/stabilization
 Rowe Industries GW  Contamination   •           Disposal  ......... , ........ ........ 259
 Sinclair Refinery, OU-2           .              Capping  :• ........ [ ......  .' ........ . . 265
 South Jersey Clothing Co.                       Soil vapor extraction  ........... ,".• .... 272
 Swope Oil & Chemical Co., OU-2          -      Soil vapor extraction  ..... ............ 277
 Warwick Landfill, OU-1                         Capping  ...... . . . i ......  ..... ..... 283


 Region 3

.Aberdeen Proving Ground (Michaelsville)         Capping  ......... '.'...:• ........... 288
 Abex Corp., OU-1                             Solidification/stabilization....  ...... ....293
 Arrowhead Associates/Scoville Corp.              Soil vapor extraction  I ........... ..... 299
 Brodhead Creek, OU-1                          In situ steam extraction  ......... ...... 304
 Brown's Battery Breaking,  OU-2                 Unspecified innovative! technology ........ 310
 C &' D Recycling                              Disposal  ......... j ................ 315
                                         '     Solidification/stabilization
 CryoChem, Inc., OU-3                  .        Soil vapor extraction  .... ' •. ... ....... ...321
 Defense  General Supply Center, OU-1         "   Institutional controls  j .............. . 326
 Defense  General Supply Center, OU-5             Soil vapor extraction  j ..... .  .......... 333
 Dixie Caverns County Landfill, OU-1             Pyrometallurgical reprocessing   ....... ... 339
 Eastern Diversified Metals, OU-1 & OU-2         Incineration -,...'.. ...... '."... ..... .... 344
 Eastern Diversified Metals, OU-3                 Recycling/recovery  .,!....... ...... ....351
 First Piedmont Corp. Rock Quarry (Route 719)     Capping  . . . . ...... I ......  ....' ....... . 357
                             ,                Unspecified treatment j
 Halby Chemical Co., OU-1                      Solidification/stabilization ..... . .....  ...  362
 Hellertown Manufacturing Co.                   Capping  .........  j ........ ......  ...  368
 Industrial Lane, OU-2                          Capping  . . . . .  ..... ! . .' ......... ... ; .  374
 Letterkenny Army Depot (SE Area), OU-1         Low temperature thermal desorption  ......  379
 Lindane Dump                                 Capping  ...... . . .  ....  . ... .... ...'.. . . .  385
 Mid- Atlantic Wood Preservers, Inc.               Solidification/stabilization .  ..... ........  392
                                      ,        Capping
 Modem Sanitation Landfill                      Capping  . . ...... .  j ..... ...........  397
 Old City of York Landfill   ,                    Capping  . . . ... ...-.!'. .......... '.....' 402
                                              Disposal             |                '       '
 Paoli  Rail Yard              '    . ,             Solidification/stabilizatiion ..... . . . . .' .  ____ 410
                                                                                                   -,
                                                                                                   .J

-------
Region/Site

Region 1
Table of Contents

           Primary Technologies Selected
Brunswick Naval Air Station, OU-1               Capping		....... 1
Dover Municipal Landfill                        Capping	 .	••••-.. 6
Iron Horse Park, OU-2                        :  Capping  ...	. . . .	13
Mottolo Pig Farm                              Soil vapor extraction		18
PSC Resources                                 1° sit" solidification/stabilization  . . .  ....... 25
Silresim Chemical Corp.   ;                    Soil vapor extraction	 .35
Sullivan's Ledge, OU-2                         Capping	. .,.'. . . .	'.....	. - • • 44
Union Chemical Co., Inc.                        Low temperature thermal desorption   ....... 50
                                             . Disposal                             , _  - •


Region 2                                  ,

A.O. Polymer                                 Soil  vapor extraction	• -  56 .
Applied Environmental Services                  Soil  vapor extraction  . . . . .	  62
                                              In situ biodegradation
Asbestos Dump, OU-2                          In situ solidification/stabilization	-.-.•••  68
C & J Disposal Leasing Co. Dump               Disposal	 . : .	  73
Circuitron Corp.                     -          Soil vapor extraction	79
                                              Incineration
Colesville Municipal Landfill                    Capping  ...'...	.......:	85
Conklin Dumps                               Capping		.	91
Cosden Chemical Coatings Corp.                In situ solidification/stabilization	96
                                      .        Disposal    .            .      ,
Curcio Scrap Metal, OU-1                      Incineration .....'	 .,	: ... 104
Ellis Property     ,                            Incineration ....:...	 109
                                              Disposal
Endicott Village Well Field, OU-2               Capping	 .		116
Facet Enterprises, Inc.                      '    Disposal		,121
                                              Solidification/stabilization
Fibers Public Supply Wells                     Disposal		. - :	•  • 127
                                              Capping
 Fort Dix (Landfill Site)                      •  Capping		 132
 Frontera Creek                                Disposal . .	 138,
 Garden State Cleaners  Co.                      Soil vapor extraction	.............. 143
 General Motors (Cen. Foundry Div.), OU-1       Biodegradation		> •.. -148
 General Motors (Cen. Foundry Div.), OU-2        Biodegradation  .........:..-..-.	154
                                               Capping .  .                              .   ..
 Genzale Plating Co.                            Soil vapor extraction  .	- 163
 Global Sanitary Landfill, OU-1                   Capping				169
                                               Solidification/stabilization
                                               Disposal       '
 Hertel Landfill                                 Capping	.-.,.:	.-. ..	174
 Industrial Latex Corp., OU-1                     Low'temperature thermal desorption  .......  180
 Islip Municipal Sanitary Landfill     ;           Capping  .	.187

-------

-------
                                        Introduction

This analysis was conducted by the Technology Innovation Office of the Office of Solid Waste and
Emergency Response. The Office of Solid Waste and Emergency Response established the
Technology Innovation Office (TIO) to foster the development and use of innovative technologies for
remediating contaminated sites. Part of TIO's mission is to collect information on the use of
innovative technologies, examine why  innovative technologies are not used more frequently, and
remove barriers to their use. Much of the information needed to address these questions may be
contained in RODs and FSs.
                                                                             i
Abstracts of FSs have been prepared for the following 205 Superfund sites to summarize pertinent
information on why technologies are being selected for site cleanups, why innovative technologies are
eliminated  from consideration as remedial technologies,  and what conditions at Superfund sites may
affect the selection of innovative technologies for site remediation. The FS abstracts were compiled
from information in source control RODs signed during FY91 and FY92 and their associated FSs.

Source control RODs address the remediation of contaminant sources at Superfund sites, such as soils,
sediments  sludges, solid wastes, and other solid (non-aqueous)  media.  Many of the RODs included in
this analysis also address contaminated groundwater and surface water; however water treatment
technologies have not been examined. This analysis does not include sites where only groundwater
was addressed, where "no action" was selected as the site remedy, and  where an interim source control
remedy addressed only the removal of drums  or surface debris.   Contaminant sources found entirely in
the saturated zone, such as pools of DNAPLs, were not included in the analysis because they generally
are addressed using groundwater treatment methods.  In addition, technologies for decontaminating
buildings were not included.                       ,                      '             ;

-------
Innovative technologies eliminated during the initial screening include the following:

•      Landfarming was eliminated because three is insufficient level land at the site and
       New York state regulations require that the'bottom of the treatment zone must be
       greater than three feet above the seasonal high water table, which is not possible at the
       site. Also, the potential of chemicals in the soils to migrate to surface waters is high.
•      • Ex situ contained solid-phase aerobic degradation was determined to be technically
       infeasible based on land use requirements for treated soil piles.
•      Ex situ anaerobic treatment was eliminated because primary contaminants of concern
       are most readily biodegradable by aerobic treatment.  Anaerobic treatment may only
       partially degrade contaminants.
•      In situ oxidation was eliminated because complete oxidation of constituents of concern
       has not been demonstrated in an in situ process.                      .   ,
•      In situ reduction was eliminated because its successful use has been limited to aqueous
       solutions and small-scale field plots.  Its use on organic constituents has not been well
       demonstrated.                                             i
•      In situ hydrolysis was eliminated because it is not an  effective treatment for the
       contaminants of concern at this site.
•      Pyrolysis was not appropriate for soils at the site.

Innovative technologies eliminated during the screening of the three Cjriteria include the
following:                                         . .   .

•      None

Innovative technologies eliminated during the detailed analysis include the following:

•      On-site thermal desorption (RAA-3) was eliminated because it involves significant soil
    	 excavation that would expose heavily contaminated soils and 'excavation followed by
       thermal treatment is relatively costly. The RAA in which thermal desorption was
       included did not provide for treatment of ground-water and saturated soils, relying
       instead on natural attenuation of contaminants in these media.} This disadvantage to
       the remedial alternative was not related to the effectiveness of the technology but  .
       contributed to its elimination.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Which of the criteria supported the use of a standard technology?
••'•'•        •                                       i
Compliance with ARARs, short-term effectiveness, and cost were the criteria weighted most
heavily in selecting the technology.  RAA-1, RAA-3, and RAA-4 would not comply with
ARARs because they would not address contaminants in saturated soiils and groundwater.  The
short-term effectiveness of RAA-2 and RAA-3 is low because they involve significant soils
excavation that would expose heavily contaminated soils. 'The cost o:
the selected remedial alternative.             .
RAA-5 is twice that of
                                        -4-
                                                                                          065

-------
 12.     Wha( cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?                     >
Contaminant'
Cleanup Level (ppb)
ARAR or Other Basis
Carcinogens
Benzene
Methylene Chloride
665
222
Risk
Risk
        For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to W6
        was acceptable.
13.
        Was the innovative technology eliminated because of the cleanup goals?  If a standard
        technology was selected, could the it meet the cleanup goals?

        Innovative technologies that were eliminated during the initial screening process because they
        could not meet cleanup goals included ex situ anaerobic treatment, in situ oxidation, in situ
        reduction, and in situ hydrolysis.  The selected innovative remedies, in situ bioremediation of
        groundwater and saturated soils and soil venting of unsaturated soils were expected -to  meet
        cleanup goals.
                                                                                    .  . •      / .
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        An in situ soil vapor extraction pilot test and a bench-scale biotreatability test were conducted
        for this site.  The soil vapor extraction pilot test showed that levels of volatile organic
        compounds in the soil within the test area were reduced dramatically in the first 5 weeks of
        operation. The biotreatability study showed that indigenous bacteria caused the loss of target
        compounds and that the potential for bioremediation on the site appeared excellent for
        saturated soils.  However, the bacteria were not as effective for unsaturated soils.
                                                                                                           )
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Waste left in place
               Time to remediate
               Cost
               Permanence
               Community impacts
16.     How are alternatives compared?

        RAA-1, RAA-3, and RAA-4 would leave significant quantities of groundwater contaminants in
        place and would rely on natural attenuation processes that would take many years to be
        effective. RAA-3 also involves significant soil excavations that would expose heavily ,
        contaminated soils.  Although RAA-2 would achieve the highest degree of protection,
066
                                               -5-

-------
       disadvantages include its extremely high cost, soil excavations that would expose heavily
       contaminated soils, and implementation difficulties caused by the needs to install a large water
       treatment system, maintain a constant water drawdown over a long period of time, overcome
       offVsite incinerator capacity limitations, minimize fugitive emissions, and regulate a high
       volume of truck traffic.  RAA-5 and RAA-6 would minimize impacts ^p the community and
       likely achieve similar levels of remediation but differ significantly in cost due to the more
       aggressive dewatering approach of RAA-5.
17.    What technical considerations were factors in selecting a remedy?  Wf re technical
       considerations primary in the selection of the remedy?

       The site is part of a small peninsula on the east shore of Hempstead Harbor, with mudflats
       (designated as tidal wetlands) around the site and a shallow water table.  The upward
       groundwater flow at the site prevents surface contaminants from migrating to deeper portions
       of the aquifer.  Infiltration of rainfall and tidal fluctuations allow for the continued
       mobilization of organic chemicals from the soil to the groundwater arijd surrounding surface
       water.  The shallow water table would make dewatering costly and difficult to maintain, which
       contributed to the elimination of RAA-5 (drawdown and soil venting);!  The contaminated
       mudflat sediments made indirect remediation (eliminating source of contaminants in soils)
       preferable due to potential for habitat disruption during active remediation.  Technical
       considerations could not be considered primary in the selection  of the remedy at this site.
                                               -6-
                                                                                                  067

-------
                                        Asbestos Dump
                                             OU-2

                                   Morris County, New Jersey
                                            Region 2
  GENERAL SITE INFORMATION

  1.      What were the principal contaminants,
          contaminant levels, and media being
          addressed in this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Surface Soil (mg/kg)

         Asbestos             300,000
  2.
 What volume of material is to be
 remediated?

 The volume of material to be remediated
, included:
                                                           Site History
                                              NPL Proposed:
                                              NPL Final:
                                              FS:
                                              ROD:
                     N/A
                     9/1/83
                     6/7/91
                     9/27/91
             Background

EPA Fund-lead
PRPs:  National Gypsum Company
FS prepared by: Alliance Technologies
       Corporation
         «      37,000 cubic yards of asbestos-containing soil


 3.      Wtiat type of site is this?

        Industrial Landfill.  An asbestos dump.                                          :


 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                     '                         °       .     J.   •31L'1C


        Containment:                 Clay cap, soil/vegetation cap,  asphalt cap, concrete cap >
                                    multimedia cap                                    -
        Physical/Chemical treatment:   In situ and ex situ cement-based solidification, pozzolanic
        _     ,                      solidification, thermoplastic solidification             '
        Thermal  treatment:            Incineration                                ;       ;
        DisP°sal:                    Off-site landfill, on-site landfill             ;
OG8
                                             -1-

-------
       Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                      |      ,
       Biological treatment:
       Thermal treatment:
           In situ biodegradation, ex situ biodegradation
           In situ vitrification, ex situ vitrification, pyrolysis
       What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are estimated as part of the three criteria (effectiveriess, implementability,
       cost)  screening process to identify alternatives of sufficient merit to undergo detailed
       evaluation. The estimated costs are recalculated during evaluation by the nine criteria
       established by the NCP.  Costs were not developed at this site during the three-criteria
       screening  because the current guidance allowed for the minimization jor elimination of the
       screening  effort if a limited number of alternatives have been develojied.
                                                                      i
                                       '•••'•      ;        •    ,'
                 Cost Estimates for RAAs That Include Innovative Technologies   '
                            (selected remedial alternative is in bold)
           Alternative
         RAA-3
         Standard Technology
Exeavation/off-site vitrification
                                                                       Estimated Costs
3 Criteria
   N/A
                                                                                 9 Criteria
$24,700,000
7.      How did the cost(s) compare to standard technologies?
                                    -'  •      • -      • ^
       Costs were not developed at this site during the three-criteria screening because the current
       guidance allowed for the minimization or elimination of the screening effort if a limited
       number of alternatives have been developed.                      !   '.

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
                                              -2-
Alternative
RAA-1
RAA-2
RAA-4
RAA-5
Standard Technology
No action
Soil/vegetative cap
In situ cement-based stabilization/
solidification ,
Excavation/off-site landfill disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$0
$1,700,000
$5,700,000
$16,000,000
                                                                                                 069

-------
8.      If a standard technology was chosen, why?                                                    ___

        The selected remedy, RAA-4, includes treatment of all materials containing greater than 0.5%          "  ^
        asbestos by^an in situ cement-based stabilization/solidification process.  It was selected because
        it would provide a high degree of protection and attain cleanup levels without excavation of
        waste materials, with some limited short-term risks due to fugitive dust emissions caused by
        disturbance of surface and subsurface contaminated materials. Excavation is particularly a
        problem at this site because of the risk of creating airborne asbestos concentrations.  Although
        capping would create less risk of airborne asbestos, in situ stabilization/solidification provides
        a much higher degree of long-term effectiveness.                                         '


9.      If an innovative technology was chosen, why?
                                                                                       f
                                                               .
        An innovative technology was not chosen.                                             -  -
                                                 '                          •'•;••'•:.•    •     .
                                                                    •  .                 ; '  '
10.     If an innovative technology was not chosen, why not? At what stage was the innpvative
        technology eliminated?                                       ,                      -

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial  screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include:              ,
                                          .'      .-" ,'    -        '•'•-.'    • •   ' .     ' '
        •      In situ vitrification was eliminated because it would not be effective for treating
               shallow depths of waste due to heat loss at  surface.
        »      Ex situ biodegradation was eliminated because it was considered not applicable to
               asbestos-containing material. No other explanation was given.          :    i
        •      In situ biodegradation was eliminated because it was considered not applicable to
               asbestos-containing material. No other explanation was given.

        No innovative technologies were eliminated during the three-criteria screening process

        Innovative technologies eliminated during the detailed analysis include:

        •      Ex situ vitrification (RAA-3) was eliminated because of the high short-term risk
               created by the excavation of asbestos and the high cost of vitrification in comparison
               to the selected alternative.                                                '


11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did one of
        the nine criteria eliminate the innovative technology from being chosen? If so, which one?
        Which of the criteria supported the use of a standard technology?

        In comparing alternatives that were protective of health and me environment and met all
        ARARs, long-term effectiveness and permanence, short-term  effectiveness, and cost became
        the decision-making criteria.  The  chosen RAA offered reasonable long-term effectiveness  and     dj^   "^ r
        permanence while minimizing short-term risk and cost.                 "                         ^^r   *



   070                                     :3.

-------
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that.
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level
ARAR<
Carcinogens
Asbestos
0.5 percent

Transmission Electron Microscopy (TEM) detection limit. T
sensitive method available for measuring asbestos.
>r Other Basis

IBM",

IB TEM is the most
       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable.  For noncarcinogens, a Hazard Index (HI) less than ojr equal to 1.0 was
       acceptable.       ,                                               j
13.     Was the innovative technology eliminated because of the cleanup goals?  If a standard
        technology was chosen, could it meet the cleanup goals?            \
                                                                   .  •  i                '     '
        No innovative technologies were eliminated because of cleanup goals.  The selected standard
        technology could meet cleanup goals.                              I
14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


75.     What measures/criteria  were used to compare alternatives?

        The following measures were used to compare'the alternatives:

               Cost effectiveness
        •-"      Permanence
               Preference for treatment
        - '      Creation of short-term risk (airborne asbestos)
               Need for continuing maintenance
               Implementability
               Time to complete remediation
 16.     How are alternatives compared?

        Disadvantages of RAA-3 and RAA-5 compared to the selected
        cost of implementation, high short-term risk of creating airborne
        difficulty of implementing in a wetland environment.  A further
        that it would not treat contaminants. The selected alternative was
       ^effective than RAA-2 because it provides a much higher degree of
        and permanence due to difficulties of constructing and maintaining a
        environment. Time to complete remediation ranged from six months
                                              -4-
alternative included their high
 asbestos concentrations, and
 disadvantage of RAA-5 was
   considered more cost-
   long-term protectiveness
     cap in a wetland
      for capping (RAA-2) to
                               071

-------
       ten months for stabilization/solidification (RAA-4) and did not appear to affect remedy
       selection.                                                                                       "  ' '"
                                                                                        i:                 '•—** •

17.    What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?                            !

       The site is located in a swamp and in a 100-year flood plain. Site location played a role in the
       remedy selection process since erosion and soil movement in a wetlands environment would
       continually contribute to degradation of the cap. Further, the shallow water table would
       increase the difficulty of excavation required for vitrification and off-site disposal. The nature
       of the contaminant (asbestos) and its location in the surface soil caused great concern about the
       production of fugitive dust during the implementation of several alternatives (particularly
       RAA-3  and RAA-5).  Technical considerations could be considered primary in the selection of
       the remedy.                                         -'.-.'
  072
                                             -5-

-------
                                C&J Disposal Leasing Co. Dump
                                                OU-1
                                          r
                                           Eaton, New York
                                               Region 2
*
                                                         NPL Proposed:
                                                         NPL Final:
                                                         FS:
                                                         ROD:
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media being
       addressed in this feasibility study?

       Maximum concentrations of principal
       contaminants were:              ,

       Soil (mg/kg)

       Bis(2-ethylhexyl)phthalate     29,000
     r  Di7n-octyl phthalate     ,      220
       Di-n-butyl phthalate           110
       Butyl benzyl phthalate        19
       4-Methylphenol          .   - 17
       2,4-Dimethylphenol           0.210
       Benzene                    6
       Ethylbenzene                190
       Toluene                     650
       Xylenes                     560
       4-Methyl-2-pentanone         1,100
       2-Butanone                  250
       1,2-Dichloroethane            8
       Trichloroethene              3
       Lead                       637
       2.      What volume of material is to be remediated?

              The volume of material to be remediated included:

              •      1,250 cubic yards of contaminated soil and debris


       3.      What type of site is this?

              Industrial Landfill. Former industrial waste disposal area.
                                                                      Site IHistory
                     1986
                     3/89
                     1/91
                     3/29/91
                                                                      Background
EPA Fund-lead
PRPs:  Occidental Petroleum, C&J
       Leasing, Biirge Company, Charles
       Picariello, James Picariello
FS prepared by:  Elsasco Services
       Incorporated
                                                                                                     073
                                                   -i-

-------
 TECHNOLOGY SELECTION
 4.       What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:                                                       •  -
        Containment:

        Physical treatment:
        Thermal treatment:

        Disposal:
                              Synthetic membrane cap, single-layer cap, multi-media cap, slurry
                              wall, sheet piles, grout curtains, bottom sealing, vitrified wall barrier
                              On-site or in situ stabilization/solidification               :
                              Rotary kiln incinerator, on-site fluidized.bed1 incinerator, on-site
                              infrared treatment, off-site thermal treatment (incineration)
                              Excavation, on-site landfill, on-site RCRA vault, off-site TSD facility
5.
        Was an innovative technology considered in the FS?  If so, which technology?     ,          '

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   In situ bioremediation, on-site slurry bioreactor, on-site leach bed, on-
                              site composting
        Phys/Chem treatment:  In situ soil washing (soil flushing), on-site soil washing, > situ
                              oxidation, in situ vacuum extraction
        Thermal treatment:     In situ steam extraction, on-site low temperature thermal  stripping, on-
                              site high temperature thermal stripping, in situ vitrification, on-site
                              vitrification
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are estimated as part of the three criteria (effectiveness, implementability
       cost) screening process to identify alternatives of sufficient merit to undergo detailed1     '
       evaluation. The estimated costs are recalculated during evaluation by the nine criteria
       established by the NCP.                          -

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)                   ;
          Alternative
                                Innovative Technology
                                                                       Estimated Costs
                                                                   3 Criteria
9 Criteria
        RAA-6
                        Ground water monitoring/dewatering/in
                        situ vitrification/backfill
                                                                   $1,551,800
$1,551,800
  074
                                             -2-

-------
7.      How did the cost(s)s compare to standard technologies?          .   ;

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is IE bold)     t
Alternative
RAA-1
RAA-2 s
RAA-3
RAA-4
RAA-5
Standard Technology
No action; ground water monitoring
Land use restrictions/deed restrictions/
ground water monitoring
Ground water monitoring/dewatering
wells/multimedia cap
Ground water moiutoring/dewatering/
excavation and backfill/off-site treatment
and disposal
Ground water monitoring/dewatering/
excavation and backfill/off-site thermal
treatment and disposal .
Estimated Costs
3 Criteria
$528,5100
$558,000
$712,500
$672,400
$1,219,500
9 Criteria
$528,500
$558,500
$712,500
$672,400
$1,219,500
 8.      If a standard technology was chosen, why?                        [

        The selected alternative,'RAA-4, includes off-site treatment and disposal.  It will eliminate
        potential for cross-media impacts, provide permanent remediation of jhe site, be easy to
        implement, require groundwater monitoring at the site for only one year, and be less costly
        than off-site thermal treatment and in situ vitrification.  No action (RAA-1) and land use
        restrictions (RAA-2) would not prevent contaminant migration from  the site.  Capping (RAA-
        3) would require installation of a permanent dewatering system that may adversely impact
        nearby agriculture and wetlands,  In situ  vitrification (RAA-6) would require 30 years of  i
        monitoring at the site and would not be as effective in reducing contaminant toxicity, mobility,
        and volume.                                                    [
 9.     If an innovative technology was chosen, why?

        An innovative technology was mot chosen.
  10.     If an innovative technology was not' chosen, why not? At what stage was the innovative
         technology eliminated?                                          I

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages: during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.
                                               .-3-
075

-------
          Innovative technologies eliminated during the initial screening include:

                 Vitrified wall barriers were eliminated because there was no underlying confining,

          •      In situ soil washing (soil flushing) would be ineffective because the principal
          ^      contaminants, phthlates, are bound in a "solid plastic matrix" and are not leachable.
                 i»o^^ f,   *u   Vj  i   •              "" "•*-f""'<"«»ics present are not iiiKely to be
                 leached from the solid plastic waste material and the VOCs are incorporated in die
                 waste matrix and not the soil.                                         '
                 site ^ VaCUUm} extractlon was eKminated because the majority of contaminants at the

         •       In situ steam extraction was eliminated because the majority of the waste matrix is
                 solid plastic residue containing phthlates, which will not be removed by this method
                 On-stte low temperature thermal stripping was eliminated because the majority of the
                 waste matrix is solid plastic residue containing phthlates, which will not be removed
                 oy tnis method.                                             .            .
         •       On-site high temperature thermal stripping was eliminated because process
                temperatures are not high enough to destroy the plastic residue in which thd  VOCs are
                incorporated.                               - '                 :
         "      ?n'f6 c°™PostinZ was eliminated because the plastic waste matrix will not be readily
                Biodegradable.           -                                    •'•;••'
         •      In situ bioremediation was eliminated because the majority of contaminants: are
                incorporated in a plastic waste matrix that is not expected to be fully biodegradable
                On-stte slurry bioreactors were eliminated  because the contaminants are incorporated
                in a plastic waste matrix that is not expected to be readily available for biodegradation
                On-site leach  beds  were eliminated because the majority of contaminants are
                incorporated in a plastic waste matrix that is not expected to be fully biodegradable
                On-site vitrification was eliminated  because insufficient quantities of waste exist to '
               justify transporting  and erecting an on-site plant.
        "      Inr.?" ?xidation was eliminated because it  would not be effective in destroying the
               solid plastic waste matrix where VOCs and SVOCs are bound.

        No innovative technologies  were eliminated during  the three-criteria screening process.

        Innovative technologies eliminated during the detailed analysis include:

        •      In situ vitrification (RAA-6) was eliminated because it. would require 30 years of
               monitoring at the site, would only reduce contaminant mobility and  volume, and would
               be more difficult to  implement and much more expensive than the selected remedy:


11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did one of
        ml n™e™tena ell™™te the innovative technology from being chosen? If so, which one?
        Whicfi of the criteria supported the use of a standard technology?

       Implementability and cost-effectiveness were weighted most heavily is selecting a remedy.
       The se ected remedy would be easier to implement than all of the alternatives but RAA-5
        ine selected remedy would be more cost-effective than RAA-5.                   '    '
 076
                                              -4-
                                                                                                           „, I

-------
12.     What cleanup goals were selected?  If the cleanup goal was based on Ian ARAR, what was that
      'ARAR?  What risk level was selected to establish cleanup goals?    j

       There are no chemical-specific ARARs provided for soil.  Cleanup criteria were based on
       background levels found in off-site and native soil samples.  No specific levels were provided
       intheFS or ROD.                                               j

       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable.  For non-carcinogens a Hazard Index (HI) less than oj-equal to 1.0 was
       acceptable.                                                   '  - i   "

       The cumulative upper bound risk at the site was estimated to be 2 x Ip"4. The risks for •
       carcinogens at the site are at the high end of the acceptable EPA risk range. The estimated HI
       for non-carcinogenic effects from dermal contact is 4 and, therefore, greater than the level
       accepted by EPA.           v


13      Was  the innovative technology eliminated because of the cleanup goals?  If a standard
       technology was chose, could it meet the cleanup goals?                 -'

       A number of innovative technologies were eliminated because they were not considered
       suitable for treating the plastic waste matrices found at the site.  No innovative technologies
       that were considered suitable for the waste type present were eliminated because of cleanup
       goals.  The selected standard technology, off-site treatment and disposal, could meet the site
       cleanup goals.
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Cost effectiveness
        -      Waste left in place
               Impact on nearby populations
               Need for long-term monitoring
               Trench dewatering model
 16.     How are alternatives compared?
                                                                     lace
The RAAs were compared primarily on the basis of waste left in pi;
Because wastes were under the shallow water table and wetlands were
wastes left in place without treatment (capping, institutional controls)
human health and the environment.  A trench dewatering model was
amount of drawdown required to keep the wastes out of the groundwiati
wastes would be left in place (in situ vitrification), long periods of monitoring
                                               -5-
  aiid cost effectiveness.
  adjacent to the site,
 would pose a threat to
used to determine the
 :er. Where treated
         would be
                                                                                                077

-------
        required.  For those alternatives that removed waste from the site, cost effectiveness^
        d-nermined which alternative was selected.                    ,
                                     ..-•'•       :   „ .           '            •     ,  •       .

17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
        ^^                                      '            ,                          i
        The site lies about 100 feet from a regulated freshwater wetland, which feeds into a pond used
        as a backup source of potable water for a nearby village.  The water table is very shallow and
        wastes found at the site lie within the groundwater.  There is no underlying confining layer so
        that neither a slurry wall nor a vitrified wall barrier were possible. Since the water table is
        above the waste, bottom sealing was not feasible.  Because of the high water table and the
        adjacent wetlands, permanent dewatering required for installation of a cap  was not considered
        desirable.  In addition, the presence of the high water table required that wastes either be
        removed from the site or that monitoring be conducted for a period of 30 years.  Technical
        considerations can be considered primary in the selection of the remedy at this site.
3
073
                                             -6-

-------
                                Circuitron Corporation
                                          OU-1

                                East Farmingdale, New York
                                         Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media being
       addressed in this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Surface Sediments/Soil (mg/kg):

       1,1-Dichloroethene          '0.005
       Trichloroethene              0.009
       1,1,1-Trichloroethane         100
       Tetrachloroethene            0.1
    ;   Bis(2-ethylhexyl)phthalate .20
       Copper            ;         485

       Subsurface Sediments/Soil (mg/kg):
       1,1 -Dichloroethane
       1,1,1 -Trichloroethane
       Benzene
       Tetrachloroethene
       Cadmiunr
       Copper
       Mercury
0.065
1.5
0.008
0.021
2.8
23.900
6.6
Site
                                 History
                NPL Proposed:  6/88
                NPL Final:  3/89  |
                FS:  1/91         ;
                ROD:  3/91       |
                             Background
                EPA Fund-lead ;
                PRPs:  Circuitron Corporation, 82 Milbar
                       Corporation, ADI Electronics
                FS prepared by:  Ebasco Services, Inc.
       What volume of material is to be remediated?
                   \    --             -    -            .
       The volume of material to be remediated included:

       •     48 cubic yards of sediment
       •     370 cubic yards of soil
        What type of site is this?       ,

        Electrical Equipment.  Electronic circuit board manufacturing facility
                                             -1-
                                                                                                079

-------
 TECHNOLOGY SELECTION                                                       !

 4.       What standard technologies were considered for selection in this FS?            '

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:      •                                    '                  •,

         Containment:          Capping, subsurface barriers
        Physical treatment:     Stabilization, thermoplastic solidification                          '
        Thermal treatment:     Rotary kiln incineration, infrared treatment, fluidized bed incineration
        Disposal:             On-site disposal, off-site disposal at RCRA facility        j
5.      Was an innovative technology considered in the FS?  If so, which technology?     \

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Chemical treatment:   Supercritical fluid extraction, in situ hydrolysis, soil washing with
                             water/solvent                                           I
        Biological treatment:  In situ biodegradation                                    '
        Thermal treatment:    In situ vitrification, enhanced volatilization             '   ':'
        Physical treatment:    In situ soil flushing with water, vacuum extraction         ;


6.       What was the cost estimate for the innovative technology?                        '

        During the initial screening process, in which technically feasible technologies are identified
        (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are. typically estimated as part of the three criteria (effectiveness, implement-
        ability, cost) screening process to identify alternatives of sufficient merit to undergo detailed
        evaluation. However, the three-criteria screening was not conducted in the FS because only
       five RAAs were developed.  The estimated costs were calculated during evaluation bv the nine
       criteria established by the NCP.                                                  JC

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)                  ;
Alternative
RAA-4
RAA-5
========
	 	 	 =================
Innovative Technology
In situ vacuum extraction/excavation of
sediments/on-site stabilization and
disposal/site containment
In situ vacuum extraction/excavation of
contaminated sediments/off-site
incineration and disposal/site
containment
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$$73,945
$685,675
i ]
080
                                             -2-

-------
7.      How did the cost(s) compare to standard technologies?              \
                                ;'•*''       •    •     ' '    '            'I
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
 8.
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
Long-term monitoring/public education
Long-term monitoring/public education/
access restrictions
Long-term monitoring/repaving the site/
decontaminating the building/diversion of
storm precipitation runoff

Estimated Costs
3 Criteria
N/A


If a standard technology was chosen, why?
N/A
N/A
9 Criteria
$380,160
$412,150
$656,695
•
        Off-site incineration was included in the remedy.
 9.     If an innovative technology was chosen, why?                      j    ..  .

        RAA-5 was chosen-because it provides source control measures that ivould prevent further
        migration of contaminants into groundwater, reduces toxicity and mobility of contaminants,
        satisfies the preference for treatment, provides a permanent solution, and is cost-effective
        RAA-1 and RAA-2 (natural attenuation) would not provide for a long-term solution.  RAA-3
        (capping) would require long-term monitoring and maintenance to ensure its  effectiveness, also
        fluctuations in the water table may cause additional leaching of contaminants into groundwater.
         Although RAA-4 (stabilization of sediments) is slightly less costly than the selected remedy, it
         is slightly less short- and long-term effective, permanent, and implernientable.

                             1         ,          .           •              i  '  '•           • . •
  10.     If an innovative technology was not chosen, why? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated  from the remedial technology selection process at
         three stages: during the initial screening; during the screening of the; three criteria of
         effectiveness, implementability, and cost; or  during the detailed evaluation.  The preferred
         alternative in the Proposed Plan was RAA-5, which also was selected by the ROD.

         Innovative technologies eliminated during the initial screening include:

          •      Soil washing was eliminated because the mixtures of contaminants at the site (volatile
                 organics, semi-volatile organics, and metals) make the development of a washing
                 solution very difficult. The technology was considered infezisible because an excessive
                 amount of washing fluid would be necessary due to the variisd partition coefficients of
                 the contaminants at the site and large amounts of wastewater would be produced.
                                                                                                  081
                                                 -3-

-------
         •      Supercritical fluid extraction was eliminated because of uncertainties in its
                performance in treating volatile organics and metals.
         •      In situ soil flushing was eliminated because of the need for vertical groundwater
                barriers that must be supported by a clay layer.  Since no clay layer exists to support a
                slurry wall, implementation of this technology could enhance the spread of i    '
                contamination into the aquifer.
         •      In situ biodegradation was eliminated because the chlorinated compounds at 'this site
                would require anaerobic treatment, and this technology was considered uncertain.  It
                was noted that metal concentrations might inhibit anaerobic degradation. Moreover,
                the infiltration of microbes into the aquifer was of concern.             ,   !
         •      In situ hydrolysis was considered an unproven  technology for Superfund sites.  It also
                was considered infeasible because the site has no confining bottom layer and1 because
                it cannot remediate VOCs and semi-volatiles.  '
         «      In situ vitrification was eliminated because it requires an exorbitant amount of
                electricity, which makes it very costly. This technique also requires auxiliary
                equipment and space that is not available at the site.  Finally, the presence of buried
                objects, such as the buried barrels and tanks at the site, would make implementation of
                this technology very difficult.
        •       Enhanced volatilization was eliminated because treated sediments would require
                additional treatment to control metals.

        The three-criteria screening was not performed because only five RAAs were developed.

        No innovative technologies were eliminated during detailed analysis.  Although RAA-4
        included SVE and this alternative was, eliminated, SVE is also included in the selected
        alternative.                                       .
        Which of the nine criteria were weighted highest in selection of the technology? Did one of
        the nine criteria eliminate the innovative technology from being chosen? If so, which one?
        Which of the criteria supported the use of a standard technology?

        The highest weighted criteria, were protection of human health and the environment and long-
        term effectiveness and permanence, and public acceptance.  Only two RAAs provided adequate
        protection to human health and the environment and permanence.  Of these two, the selected
        alternative  was preferred by the public.                                           '
12.    What clean-up goals were selected?  If the clean-up goal was based on an ARAR, what
       that ARAR?  What risk level was selected to establish clean-up goals?

       Soil and sediment performance goals were based on leachability modeling.
was
 082
Contaminant
Carcinogens:
1 , 1 -Dichloroethane
Tetrachloroethene
Trichloroethene
Clean-up Level (ppb)

5
5
5
ARAR or Other Basis

MCL :
MCL . ;
MCL • •
                                              -4-

-------
                    Contaminant
               Benzene
               Non-Carcinogens:
                1,1-Dichloroethene
                1,1,1 -Trichlofoethane
                Copper
                Cadmium
                Mercury
                Bis(2-ethylhexyl)
                phthalate
Clean-up Level (ppb)
        1,300
         10
         4.2
                                                               ARAR or Other Basis
                                                                       MCL
                                                                       MCL
                                                                       MCL
                                                                       MCL'
                                                                       MCL
                                                                        MCL
                                                                        MCL
       For carcinogens an excess upper bound individual lifetime cancer risk of between W4 to 10'6
       was acceptable. For non-carcinogens a Hazard Index less than or equal to 1.0 was acceptable.
13.     Was the innovative technology eliminated because of the clean-up go:als? If a standard
       technology was chosen, could it meet the clean-up goals?          |            .    .

       Innovative technologies that were eliminated because of clean-up goals include in situ
       biodegradatioh. The components of the selected remedy that are standard technologies
       (excavation and off-site treatment and disposal) could meet clean-up goals.


14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                  '    •         •      7       '.'•.•.
       No treatability studies were performed.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Permanence
               Preference for treatment
               Waste left in place
 16.     How are alternatives compared?

        RAAs that would not provide a permanent solution and leave untreated waste in place were
        eliminated.  The deciding factor in selection of RAA-5 over RAA-41J which both met the above
        criteria, was acceptance by the public of RAA^5.
                                                                                               083
                                              -5-

-------
17.     What technical considerations had to be considered in the selection of a remedy?  Y/ere
        technical considerations primary in the selection of the remedy?                                 ^^    V
                                                                                    • '                    -—>r
                                                                                     .             .       ,i-
        The site is one acre of flat land  in an industrial/commercial land-use area located about 90 feet
        above sea level.  The site lacks-  .1 clay layer between the  bedrock and the aquifer, which                   !.
        resulted in the elimination of all remedial technologies that required the use of a vertical
        barrier.  Sandy soils underlying  the site are suited ideally for the use of SVE. Although these
        technical considerations affected the selection of a remedial technology, alternatives'•• were     ••   .         !
        available and technical considerations could not be judged as primary in the selection of a                 !'
        remedy.                                                                      !                       |
    084
                                              -6-

-------
                              Colesville Municipal Landfill
                                           OUrl

                                    Colesville, New York
                                          Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil

       Using magneto-meter survey technology,
       trbnches of industrial waste were located.
       No "hot spots" of contamination were
       identified, however, and no sampling and
       analysis of potentially contaminated media
       were conducted.
             Site; History
NPL Proposed:
NPL Final:
FS:
ROD:
10/84
6/86
12/90
3/29/91
             Background
                 i    .       '     • -
PRP-lead         j   .
PRPs:  Broome County Department of
       Public Works, GAF Corporation
FS prepared by:  \^ehran-New York,
       Inc.
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated included:

        •      468,000 cubic yards of waste


 3.      What type of site'is this?

        Municipal Landfill.  A former municipal and industrial landfill.


 TECHNOLOGY SELECTION                  '

 4.      What standard technologies were considered for selection in this FS?      •

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                    ...       -                 •'      '_           j            .:•
        Containment:          Synthetic membrane'cap, single-layer capr multimedia cap, slurry wall,
                              sheet piles, grout curtains, bottom sealing, vitrified wall barrier
        Physical treatment:     Stabilization/solidification                ;
        Thermal treatment:     On-site incineration (rotary kilri, fluidized bed, infrared), off-site
                              commercial incineration
                                                                                               085

-------
         Disposal:
On-site RGRA vault, off-site disposal to TSDF
 5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                           /

         Phys/Chem treatment:  In situ soil washing (solvent), on-site soil washing (solvent), in situ
                              chemical oxidation,  in situ vacuum extraction
         Thermal treatment:     In situ steam extraction, on-site low temperature thermal stripping, on-
                              site high temperature thermal stripping, in situ vitrification, on-site
                              vitrification
        Biological treatment:   In situ bioremediation, on-site slurry reactor, on-site leach bed, on-site
                              composting                                              j'


 6.      What was the cost estimate for the innovative technology?

        During the  initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability,  and cost) to identify alternatives that  merit a more detailed evaluation! 'The
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        bytheNCP.                                   ;                                !

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)                   i
                                  Innovative Technology
Landfill excavation/on-site vitrification
                                                                       Estimated Costs
                                     3 Criteria
                                                                  $101,790,000
                                                        9 Criteria
                                                   eliminated
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action/monitoring program
No further action/existing residential
well monitoring/water supply program
Estimated Costs:
3 Criteria
$128,000
$236,000
9 Criteria
$128,000
eliminated
 036
                                             -2-

-------
Alternative
RAA-3A
RAA-3B
RAA-4A1
RAA-4A2
RAA-4B1
RAA-4B2
RAA-4C1
RAA-4C2
RAA-4D1
RAA-4D2
RAA-4E1
• . . , ;
Standard Technology
Existing residential well monitoring/
upgraded water supply system/deed
restrictions/purchase of affected
residences
New water supply to affected
residences/well monitoring
Landfill cap/natural recovery of glacial
outwash aquifer/upgrade water supply
Landfill cap/natural recovery of glacial
outwash aquifer/new water supply
Downgradient pumping/landfill cap/
ground water treatment/surface water
discharge/upgraded water supply
Downgradient pumping/landfill cap/
ground water treatment/surface water
discharge/new water supply
Pumping at landfill and down gradient/
landfill cap/ground water treatment/
surface water discharge/upgraded water
supply
Pumping at landfill and down
gradient/landfill cap/ground water
treatment/surface water discharge/
new water supply
Downgradient cutoff/landfill cap/ground
water collection/ground water treatment/
surface water discharge/ natural
recovery of glacial outwash outside of
cutoff/new water supply
Downgradient cutoff/landfill cap/
ground water collection/ground water
treatment/surface water discharge/
additional pumping outside of cutoff/
upgrade water supply
Complete ground water cutoff/landfill
cap/ground water collection/ground
water treatment/surface water discharge/
natural recovery outside complete
cutoff/new water supply
Estimated Costs
3 Criteria
$679,000
(plus
residential
purchases)
$650,000
$5,550,090
$5,530,000
$5,593,000
$5,647,000
$5,043,000
$5,136,000
$10,9179,000
$11,227,000
$18,«>42,000
9 Criteria
$672,000
(plus
residential
purchases)
$648,000
eliminated
eliminated
$5,595,000
$5,646,000
$5,044,000
$5,135,000
$10,977,000
$11,230,000
eliminated
.' ' •'- ' :' .^ ' •"'.'-• '' .< '. (
j 1 i ' '
037

-------
Alternative
RAA-4E2
RAA-5A
RAA-5C
RAA-5D
Standard Technology
Complete ground water jputoff/landfill
cap/ground water collection/ground
water treatment/surface water discharge/
additional pumping outside complete
cutoff/upgrade water supply
Landfill excavation/on-site stabilization
and solidification
Landfill excavation/off-site treatment
and disposal
Landfill excavation/on-site incineration
Estimated Costs
3 Criteria
$18,766,000
$70,200,000
$297,180,000
$474,084,000
9 Criteria
eliminated
eliminated
eliminated
• • i
eliminated
8.      If a standard technology was chosen, why?

        The selected alternative includes a landfill cap; pumping at the landfill and downgradient.
        This remedy was selected because:   1) the size of^the landfill and the fact that there are not
        identified on-site "hot spots" that represent the major sources of contamination, preclude any
        remedial response actions in which  the landfilled material could be excavated and treated, 2)
        cap and leachate collection system will eliminate direct contact, and 3) least expensive of all
        the alternatives.                                                                '
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                            •              ;

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of;
       effectiveness, implementability, and cost; or during the detailed evaluation.          |

       Innovative technologies eliminated during the initial screening include the following: \

       •      In situ soil washing was eliminated because the entire mass of waste would need to be
              treated to extract a relatively small mass of VOCs.
       •      On-site soil flushing was eliminated for the same reasons as in situ soil washing.
       •      In situ vacuum extraction was eliminated because the entire mass of waste would have
              to be treated to extract a relatively small mass of VOCs.                   "•
       •      In situ steam extraction was eliminated for the same reason as vacuum extraction.
       •      On-site low temperature thermal stripping was eliminated for the same reason as
              vacuum extraction.
   038

                                              -4-

-------
               On-site high temperature thermal stripping was eliminated for the same reason as
               vacuum extraction.
               In situ bioremediation was eliminated because it would require a
lot of oxygen to
               create aerobic conditions in the anaerobic landfill, and the entire mass would need to
               be treated to extract a relatively small mass of VOCs.
        •      On-site slurry reactors were eliminated for the same reasons as in site bioremediation.
        •      On-site leach beds were eliminated for the same reasons as in situ bioremediation.
        •      In situ vitrification was eliminated because it would be effective Only to a depth of 35
               feet, and the site's contaminants were deeper.
        •      On site composting was eliminated because VOCs would be released from the
               mechanical aeration and a large amount of waste would need to be excavated in order
               to eliminate a relatively small amount of VOCs.                       ,

        Innovative technologies eliminated during the screening of the three criteria1 include the
        following:                                                          i

        •      On -site vitrification was eliminated because its effectiveness was (uncertain.
               Furthermore, implementation would be problematic, requiring the: excavation of
               municipal waste containing bulky  materials that might need to be; decontaminated.

        Innovative technologies eliminated during the detailed analysis include the following:

        •    ''  None   .        '                           ' •                i     . .       '

•          ;.   •    '.    .    "        ••..-       .   '  ••'   '.      "      •   |v  •:••      .   •'.:  '.
 1.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to me$t one of the nine criteria result in the elimination of the innovative^ technology?  If so,
        which criterion ? Which of the criteria supported the use of a standard technology?

        Three alternatives were deemed equal in protectiveness of human health zind  the environment
        and in compliance with ARARs, but superior to all other alternatives with respect to their
        long-term effectiveness. The, deciding factor  among these three were cost-effectiveness and the
        time required to attain ARARs.  The alternative that attained ARARs fastest and was the most
        cost-effective was chosen.                                            i
                                         - -        ,            ,            •(•            ,
                                                                           i        . '     ',
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?       \

        No chemical-specific ARARs for soil were available.  Clean-up goals were established only for
        groundwater clean-up.  The remedial action objective is to eliminate direct contact with the
        waste, the site's leachate seeps and any associated leachate discharges into streams to prevent
        further sediment contamination.  Because the  increased health risk associated with direct
       contact of existing sediments is within the acceptable range, remediation of existing sediments
       is not necessary.                              '                       r         :

       For carcinogens, an excess upper bound individual lifetime cancer risk Of between  KX4 to 10'6
       was acceptable.  For noncarcinogens, a Hazard Index less than or equal  tcj 1.0 was acceptable.

       Since the landfill contains RCRA-listed hazardous waste, regulations specified in NYCRR Part
       360 (New York Code of Rules and Regulations) apply to the installation of a multimedia cap.


                                              -5                                             039

-------
        Based on the landfill's size and the fact that no "hot spots" could be identified, remedial
        response actions to excavate and treat landfill material are precluded.
 13.     Was the innovative technology eliminated because of the cleanup goals? Could the
        established technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •      None                                                       '
14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted. It was noted that stabilization/solidification and on-site
        vitrification would require treatability studies to determine their effectiveness.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Risk level achieved
               Total cost
               Cost-effectiveness
               Time to design/construct/operate
16.    How are measures compared?                                               •}.'-.

       The chosen alternative attains an acceptable risk level (2 x 10's) within the shortest time period
       (3 years).  One other alternative (RAA-4B2) would attain comparable risk levels in a timely
       manner, but would be less cost-effective.  Several alternatives (RAA-4D1, RAA-4D2, RAA-
       4E1, and RAA-4E2) were eliminated because they would cost too much. The chosen
       alternative  also had the shortest ,time for operation,  Implementation of the selected technology
       would remediate the site to ARAR levels approximately two to five times faster than other
       proposed alternatives.  A ground water flow and contaminant transport model was us|ed to
       estimate contaminant transport and to compare the estimated time to reach ARARs and the
       decline in risk achieved between alternatives.                                     ;
                                                                                    i
17.     What technical considerations were factors in selecting a remedy?  Were technical  i
       considerations primary in the selection of the remedy?                           '

       The nature,of the landfill waste was a primary factor in the choice of a remedial.alternative.
       The contaminants of concern were VOCs and the landfill contained an undetermined j amount
       of bulky and  oversized waste.  There was an emphasis towards the elimination of remedies
       that required the excavation of waste since VOCs would be released and segregation :of the
       waste would be extremely difficult.                     .
 030
-6-

-------
                                     Conklin Dumps
                                           OU-1

                                     Conklin, New York
                                          Region 2
GENERAL SITE INFORMATION
       What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Ground water, not soils, was tested for
       contaminant levels.  Chloroethane, observed
       in groundwater at 68 ppb, was the
       contaminant of concern at the site.
       What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:
                                     Site History
                       NPL Proposed:
                       NPL Final:
                       FS:
                       ROD:
                                                                 Background
                        PRP-lead
                        PRPs: Town of Co;nklin
                        FS prepared by: O'
Brien and Gere
              71,900 cubic yards of upper landfill                      ,
              over an :area of 5.5 acres
              32,500 cubic yards of lower landfill over an area of 2.5 acres
3..     What type of site is this?

       Municipal Landfill.  Inactive municipal landfill.


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:
       Containment:
       Disposal:
Deed restriction, fencing
Asphalt cap, concrete cap, clay cap, multimedia cap
Consolidation into one landfill, excavation, off-site landfilling
5.      Was an innovative technology considered in the FS?  If so, which tecf nology't

        No innovative technologies were considered in the FS.
                                             -1-
   6/86
   3/30/89
   1/91
   3/29/91
                                                                                                091

-------

6.      What was the cost estimate for the innovative technology?                        '
                            ;                  •              ;   •• •                    i   •
       No innovative technologies were included in remedial action alternatives, and therefore, no
       costs were estimated.                                                          ;
7.      How did the cost(s) compare to standard technologies?                           i

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs' have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
       estimated costs then are recalculated during an evaluation based on the nine criteria established
       by the NCR                                      .                            :
                                                                            -        ! "
                Cost Estimates for RAAs That Include Established Technologies      \
                           (selected remedial alternative is in bold)                  i
Alternative
RAA-1
RAA-2A
RAA-2B
RAA-2C
RAA-2D
RAA-3
RAA-4
Established Technology
No action/long-term monitoring
Long-term ground water monitoring/
fencing/deed restriction/multimedia cap at
both landfills/enhanced leachate collection
with extraction wells/on-site treatment with
air stripping and discharge to surface water
Same as RAA-2A except off-site leachate
treatment and disposal at POTW
Same as RAA-2A except enhanced leachate
collection with interceptor trench
Same as RAA-2C except off-site leachate
treatment and disposal at POTW
Long-term ground water monitoring/
fencing/deed restrictions/multimedia cap at
both landfills/ground water collection with
extraction wells/perimeter leachate
collection/on-site treatment with air
stripping/discharge to surface water
Long-term ground water monitoring/
fencing/deed restrictions/multimedia cap at
both landfills/ground water collection with
extraction wells/perimeter leachate
collection/on-site treatment with chemical
oxidation/discharge to surface water
Estimated Costs
3 Criteria
$111,000
$4,559,000
$4,352,000
$4,644,000
$4,423,000
$4,859,000
to
$4,935,000
$5,114,000
to
$5,344,000
9 Criteria
$111,446
$4,558,947
|
$4,352,078
$4,^44,183
$4,423,255
i
$4,934,726
; !
$5,113,678
' 1
• i
i
i • •
  092
-2-

-------
Alternative
RAA-5
RAA-6
Established Technology
Long-term ground water monitoring/
fencing/deed restrictions/multimedia cap at
both landfills/ground water collection with
extraction wells/perimeter leachate
collection/off-site leachate treatment and
discharge at POTW
Consolidation of the upper and lower
landfills at the upper landfill/fencing/deed
restrictions/multimedia cap/perimeter
leachate collection/on-site leachate treatment
with air stripping/discharge to surface water
Estimated Costs
3 Criteria
$7,924,000
!to
$10,893,000
j
'|
$5,218,000*
1
i
I
9 Criteria
$10,893,217
$5,218,316
       "Alternative RAA-6 assumes no hazardous material in the lower landfill.  If. hazardous material
       is found during excavation, the cost would increase significantly.     i
8.     If a standard'technology was chosen, why?      ,                  i
                                      1               .,.-,-   i    '.•
       The selected remedy was RAA-2B, which includes long-term groundwater monitoring, fencing,
       deed restriction, multimedia caps at both landfills, enhanced leachate (collection with extraction
       wells, and off-site leachate treatment and  disposal at a POTW.  It would rely on natural
       attenuation of groundwater contaminants,  which would take 7 to 9 yeiirs to reach site goals, is
       the least costly of the action alternatives,  and provides short- and long-term effectiveness. Of
       the four RAA-2 alternatives (A, B, C, D), RAA-2B was selected because it would be the
       simplest to implement.                                           j

       RAA-1  (no action) would  not protect human health.  RAA-3, RAA-4, and RAA-5 include
       extraction and treatment of groundwater, which would remediate groundwater within 14 to 24
       years, a longer period of time than natural attenuation alone.  Extraction would interfere with
       natural biological activity by diluting contaminant levels. RAA-5  also would be much more
       expensive.  RAA-6 included consolidating the upper and lower landfills, which would create a
       short-term threat of exposures not warranted by the low groundwater contamination in the
       lower landfill.                                                   ;
9.      If an innovative technology was chosen, why?

       No innovative technology was chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                          ;

       Innovative technologies were not considered even during the initial screening of technologies.
       The size of the landfill and the aibsence of on-site hot spots of contaminants precluded
       excavation and treatment of landfill materials as a means of source control.
                                             -3-
                                                                                                093

-------
11,    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure     ^&
       to meet one of the nine criteria result in the elimination of the innovative technology?. If so,              \
       which criterion?  Which of the criteria supported the use of a standard technology?  j                —

       Short-term effectiveness and cost effectiveness Were weighted most heavily in selectiop of a
       remedy at this site.  Natural attenuation was estimated to be able to remediate the groundwater
       in a shorter time than pump-and-treat alternatives. Consolidation of the upper and lovter
       landfills was expected to create unwarranted short-term exposure risks. The selected remedy
       was the least costly of the action alternatives.                                      j
                                                                                       !   •

 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR,  what was that
       ARAR?   What risk level was  selected to establish cleanup goals?                   |

        Chemical-specific ARARs for groundwater were based on New York State Class Ground
        Water Quality Standards (the  chloroethane cleanup level may not exceed 5 ppb). No jspecific
        ARARs were developed for soil or sediment.  Alternatives developed for this site were aimed
        at blocking infiltration of precipitation into the landfill with a multimedia cap. This technique
        would be supplemented by leachate collection and treatment. Therefore, treatment ofjlandfill
        soil/sediment was not an integral part of any alternative proposed.                   ;     .


 13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                              ;
                                                                 •    -                  ;    •      ,
        No innovative technologies were eliminated because of cleanup goals.  The standard  i
        technology selected could meet cleanup goals.                                    !
                                                                          - •            i       '
                                                                                       i
 14.    Were treatability studies conducted on the innovative technology or standard technology?
                                                                             .          i
        No treatability studies were conducted.                                           ]
                           •                       ,     .'             /     •-•'[./'••
 15.     What measures/criteria were used to compare, alternatives?                        !

        The following measures were used to compare alternatives:           ^             :

                Time to design/construct/operate                                         i
                Total cost                                                              I
                Proven reliability                                                       j

                                                           •  •              ...         |^

  16.     How are alternatives compared?                                           .     ; .
                                                                 •'             .         I "   i
         The time required for natural attenuation to reduce chloroethane concentrations to grpundwater
         standards was estimated using a first-order decay equation to be 7 to 9 years. The time
         required for groundwater pump-and-treat systems to reduce chloroethane  concentrations to
         groundwater standards was estimated using a groundwater flow rate equation to be 14 to 24
         years, assuming no biological degradation processes.  Proven reliability was noted for many of
         the treatment technologies as an advantage to its use. Where alternatives would take similar
    094
-4-

-------
       times for remediation and their reliability was similar, cost was used to select the most
       appropriate remedy.                                          ;    •
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?             \

       The site consists of two landfills. The lower landfill is bordered by v/etktnds and a 100- year-.
       old floodplain.  Sbale/siltstone underlies the entire site. Groundwater occurs between one to  ,
       14 feet below the lower landfill and at 24 feet below the upper landfill.  1While these technical
       considerations were factors in the remedy selection, technical considerations were not primary
       in the selection of a remedy.                                      ;
                                                                                                 095

-------
                       Cosden Chemical Coatings Corporation

                                City of Beverly, New Jersey
                                         Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       Toluene              1,600
       Ethylbenzene          1,600
       Xylene     .          7,900
       Trichloroethene       1.6
       Lead                6,580
       Cadmium            2.6
       Chromium (total)     36,000
       Beryllium            0.6
       PCBs                120
                   Site History
      NPL Proposed:
      NPL Final:
      FS:
      ROD:
N/A
7/87
7/92
9/30/92
                   Background         i-

       EPA Fund-lead                   j
       PRPs:  Cosden Chemical Coatings Corp.
       FS prepared by:  Ebasco Services Inc.
2.     What volume of material is to be remediated?                                    \

       The volume of material to be remediated included:                                j
                                                                                 -, i
       •     8,000 cubic yards of soil                                               i


3.     What type of site is this?                                            .          ;

       Chemicals and Allied Products. The site housed a paint formulation and manufacturing
       facility that produced coatings for industrial applications. The surrounding area is suburban
       with some light industry.                                                      ,
                                                                                   •!•
                                                                                   i  '
TECHNOLOGY SELECTION                                     , '                  I

4,     What standard technologies were considered for selection in this FS?                |

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                        '   h"

       Access restriction:     Land use restriction, public information,programs            \
       Containment:          Cap (clay, asphalt, synthetic membrane, chemical sealant, multimedia)
   09G
-1-  ,

-------
       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Stabilization (solidification), in situ stabilization (solidification)
Mechanical aeration                       , <
Incineration (multiple hearth, rotary kiln, infnired,, fluidized bed)
Excavation, on-site RCRA landfill, off-site RCRA landfill, 6n-?site
nonhazardous disposal, off-site nonhazardous disposal
5.     Was an innovative technology considered in the FS? If so, which technology?
                                           1'   '                        !
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                       ;

       Biological treatment:   Biodegradation
       Phys/Chem treatment:  Alkali metal dechlorination (APEG), soil washing and extraction,
                             supercritical fluid extraction, in situ soil flushing      .
       Thermal treatment:    High-ternperature thermal desorption, in situ yitrification, in situ
                             vacuum extraction                       .  '•;    '
        What was the cost estimate for the innovative technology?          ;
               '             .   '     •    •                '             •  \     '''..'
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs,  y^fteir the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and  cost) to identify alternatives that! merit a more detailed
        evaluation.  The estimated costs then are recalculated during an evaluation based on nine
        criteria established by the NCP.           .                        I
                                                                       !        .1
        A risk assessment prepared concurrently with the FS showed that.VOC contamination does not
        pose an unacceptable risk to human health. Accordingly, the RAAs brought forward from the
        FS to the Proposed Plan were changed to exclude specific treatment of VOCs in site soils.
        Separate tables are presented for RAAs in the FS and RAAs in the Proposed Plan and ROD.

                 Cost Estimates for RAAs Tfaat Include Innovative Technologies
                            (selected  remedial alternative is in bold)

        FS         '  •          '.      •      '     -    ''.-•••••'

Alternative
RAA-6
RAA-7 •


Innovative Technology
Excavation/on-site high-temperature
thermal desorption/on-site stabilization
(solidification)/on-site disposal/soil
cover/land use restrictions/ground water
monitoring
In situ vacuum extraction/in situ
stabilization (solidification)/soil
cover/land use restrictions/ground water
monitoring
. • .•'• -2-
Estimate<
3 Criteria
$4,948,300
$3,957,400

1 Costs
9 Criteria
$4,948,300
$3,957,400

                                                                                                 097

-------
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                         (selected remedial alternative is in bold)

       FS                                        *
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology '
No action/soil monitoring
Post warning signs/public education
program/land use restrictions/soil
monitoring
Asphalt cap/land use restrictions/
ground water testing
EXcavation/off-site incineration/off-site
stabilization (solidification)/off-site
disposal/backfill with clean off-site soil
Excavation/on-site incineration/on-site
stabilization (solidification)/on-site
disposal/soil cover/land use restrictions/
ground water monitoring
i
Estimated Costs
3 Criteria
$894,900
$968,8,00
$2,515,100
$15,231,900
$5,788,800
9 Criteria
$894,900
$968,800.
$2,515,100
i
[
$15,231,900
eliminated
       Proposed Plan and ROD
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action/soil monitoring
Post warning signs/public education
program/land use restrictions/soil
monitoring
Asphalt cap/land use restrictions/
ground water testing
Excavation/off-site stabilization
(solidification)/off-site disposal/backfill
with clean off-site soil
Excavation/on-site stabilization
(solidification)/on-site backfill/soil
cover/land use restrictions/ground water
monitoring
Estimated Costs
PP
$55,600
$88,000
$2,515,100
$7,187,850
$3,793,250
-
ROD
$55,600
$5$,600
i
$2,515,100
$7,187,850,
• i
i
$3,793,250
. i .
i
i
 098
                                          -3-

-------
Alternative
RAA-6
Standard Technology
Excavation/in situ stabilization
(solidification)/soil cover/off-site
disposal/land use restrictions/ground
water monitoring
Estimated Costs
!PP
$3,268,000
i
1 - "
i
ROD
$3,268,000
8.      If a standard technology was chosen, why?                        ,

       Compared to other alternatives, the selected remedy achieves ARARii more quickly, or as
       quickly, and at less cost.  The selected remedy is protective of humain health and the
       environment, dealing effectively with the threats posed by the contaminants which were
       identified. The principal threat posed by the site is the contaminated soils.  Stabilizing the
       contaminated on-site soils will protect against future direct contact, iagestion, and inhalation
       hazards.  Additionally, stabilization prevents the infiltration of soil contaminants into the
       ground water.  The selected remedy complies with chemical- specific; ARARs in that the
       contaminants of concern in the soil will be treated to reduce the direct contact, ingestion, and
       inhalation exposure  risks to 1 x 10'6 for carcinogens, and to  an ffl of less than 1.0 for
       noncarcinogens.  The selected remedy complies with action- specific! ARARs in that the
       stabilized soil will meet RCRA standards for teachability and toxiciry.  Of the alternatives that
       most effectively address the threats posed by site contamination, the;selected remedy provides
       for overall protectiveness in proportion to its cost. The treatment of soils contaminated with
       PCBs over 50 ppm  at an approved off-site facility significantly reduipes the toxicity, volume,
        and mobility of the  contaminants. The stabilization of soil contaminated with metals and
        PCBs less than 50 ppm will reduce the mobility of these contaminants and, therefore,
        represents a permanent solution to the risks posed by the contaminated soil.  The toxicity and
        volume of the contaminated soil, however, will not be reduced.  Considering the relatively
        large volume of metals and PCB-contaminated soil (8,000 cubic yards), EPA believes.that the
        selected  remedy represents the maximum extent to which the toxicity, mobility, and volume
        can be reduced in accost-effective manner. The statutory preference for remedies that employ
        treatment as a principal element also will be satisfied for the contaniinated on-site soil.  The
        metal- and PCB-contaminated soil will be stabilized in situ, thereby!reducing risk to human
        health.                                                         I
 9.      If an innovative technology was chosen, why?

         An innovative technology was not chosen.
  10.     If an innovative technology was not chosen, why not? At what stag* was the innovative
         technology eliminated?                                         j

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.
                                                -4-
                                                                                                099

-------
      Innovative technologies eliminated during the initial screening include the following: ',

      «      Biodegradation was eliminated because of significant uncertainties regarding treatment
             reliability for both organic and inorganic contaminated soil.  Biodegradation is a
             developmental technology for hazardous waste cleanup which requires extensive
             bench- and pilot-scale testing to verify its effectiveness. While aerobic biodegradation
             has been demonstrated to be effective on some organics such as benzene, toluene, and
             xylene, uncertainty exists regarding its effectiveness in remediating PCBs, which are
             among chemicals of concern at the site.  Anaerobic biodegradation might be effective
             on chlorinated organics under controlled conditions.  The presence of elevated levels
             of metals in the soil might adversely affect microorganisms.  In addition, volatile
             organics  would volatize while mixing and aerating the contaminated soil and vj/ould
             need to be captured and treated.                                           ,''-.-
      •      Alkali metal dechlorination (APEG) was eliminated because the APEG processes are
             used for the treatment of chlorinated compounds, primarily PCBs. In addition!to
             PCBs, the site also needs PAHs and VOCs removal.  The alkali metal dechlorination
             technology has not been shown to be effective in treating other organics such as the
             VOCs and PAHs present in contaminated soil at the site.                    !
      •      Soil washing and extraction was eliminated because the most promising soil washing
             and extraction application is its use in the extraction of heavy metals. The use' of soil
             washing and extraction for organics with a volatile component  would require a closed
             loop washer with a vapor emissions control system. Large volumes of contaminated
             wash water and/or spent extraction solution would be generated which would require
             recovery, further treatment, and/or disposal. In addition, multiple contaminants would
             require multiple washing steps. Other treatment technologies are available that would      Jlfc-' .
             be easier to implement and equally effective, without generating large voluniesl of          ^pr J
             secondary waste.                                                          |                  -^
      •      Supercritical fluid extraction was eliminated for the following reasons. Supercritical
             fluid extraction is currently available from only one vendor; therefore, the availability
             of equipment would be limited. This technology would require further treatment for
             metals. Since this  technology also requires a pumpable waste such as sludge, a soil
             slurry would have to be prepared. Supercritical fluid  extraction would require & higher
             capital cost, and involve processes and equipment that are more complex than other
             technologies.                                                              :
     »      In situ soil flushing was eliminated for the following reasons. The contaminated soil
             at the site is  mainly sandy soil and gravel with high hydraulic conductivity (l.li x  10"2
             to 1.96 x  10'3 cm/sec).  The ground water table is approximately 20 feet below j grade.
             There are no horizontal or vertical confining barriers to isolate the contaminated areas;
             therefore, the flushing solution would migrate into the ground water and would) not  be
             effectively captured. The site also contains a discontinuous lens of silt and clay  in
             some locations at a depth of approximately 10 feet, which would create dead spots and
             make in situ  flushing ineffective.  In addition, this technology would require treatment
             of large volumes of flushing solution.  The technology would be difficult to implement
             and process efficiency would be uncertain.                                  I
     •      In situ vitrification  was eliminated because, although the technology is commercialized
            for low-level radioactive waste stabilization, heavy metal fixation, and hydrocarbon
            destruction, the technology is not very effective for volatile organics because volatile
            organics migrate laterally during the vitrification process and might escape untreated.               .
100                                      -5-

-------
      innovative technologies eliminated during the screening of the three criteria include the
      following:                                                      I
                    '             ,     .       )•-..'.      ,      .'!'.•          :
      •      None              ;                             . .. -•.!"•••
                                                                      I          :
      Innovative technologies eliminated during the detailed analysis include the following:

      •      High-temperature thermal desorption was eliminated because a risk assessment
              prepared concurrently with the FS showed that VOC contamination does not pose an
              unacceptable risk to human health.  Accordingly, the RAAs brought forward from the
              FS to the Proposed Plan were changed and no longer include!specific treatment of
              VOCs in the site soils.  One of these treatments was high- temperature thermal
              desorption.
       •      In situ vacuum extraction was eliminated because a risk, assessment prepared
              concurrently with the FS showed that VOC contamination does not pose an
              unacceptable risk to human health. Accordingly, the RAAs brought forward from the
              FS to the Proposed Plan were changed and no longer include; specific treatment of
              VOCs in the site soils.   One of these treatments was in situ vjacuum extraction.
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria .result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                                      i   .      •'        •••
       Short-term effectiveness and cost were weighted most heavily in selecting the in situ
       stabilization. Compared to other alternatives, the selected remedy costs less and achieves
       ARARs more quickly, or as  quickly, than the other options. Failure |to meet one of the nine
       criteria did not result in the elimination of an innovative technology.!
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that  ,
        ARAR?  What risk level was selected to establish cleanup goals?   j
Contaminant
Carcinogens
PCBs
Beryllium
Chromium (VI)
Lead
Noncarcinogens
Chromium (HI)
Cleanup Level (rag/kg)

1
1
390
500

78,000
ARAR or Other Basis
i . i
OS'WER directive
#9344.4-02
Quantification limit3
;Risk-basedb
OSWER directive
•• #9355.4-02
' .
Risk-based
                "Calculated from IxlO"6 risk* then deferred to practical quantification limit
                                               -6-
                                                                                               101

-------
13.
               "Tor carcinogens, an excess upper bound individual lifetime cancer risk of between 10
               to 10"6 was acceptable.  For noncarcinogens, a Hazard Index less than or equial to 1.0
               was acceptable.                                                       !
        Was the innovative technology eliminated because of the cleanup goals?  Could the Standard
        technology meet the cleanup goals?                                            !
                                                               ,                     i
        Innovative technologies eliminated because of cleanup goals include:             . i
                                                                                    i
        •      None                                                                i
                                                      -  '   .         ,               r i *
        Standard technologies eliminated because of cleanup goals include:               . i  '    ,  '

        •      None                        .                                        i
14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                                          i
15.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Risk level achieved
             Total cost
             Time to design/construct/operate
             Proven reliability
             Impact on nearby populations
16.     How are measures compared?                                                 ;
                                                                                    i
       RAA-1 and RAA-2 would not reduce the human health hazards associated with direct contact
       and ingestion of contaminated soils.  RAA-3 would effectively control the dermal contact and
       ingestion pathways, and therefore provide adequate protection of human health. RAAi-1,
       RAA-2, and RAA-3 would not meet risk-based guidance for cleaning up lead or PCB's. RAA-
       4, by removing contaminated soil for off-site disposal, would offer the greatest level of overall
       protection.  RAA-5 and RAA-6 would offer adequate protection by immobilizing    '
       contaminants.  RAA-6 costs less and achieves ARARs more quickly  than, or as quickly as the
       other options.  The amount of time until protectiveness is achieved is approximately the same
       for all of the soil treatment alternatives.  Estimated present worth costs for stabilization range
       from $3,268,000 for RAA-6 to $7,187,850 for RAA-4.  Solidification of metals and P^B
       contaminated soil is common to RAA-5 and RAA-6, and is an easily implemented and proven
       technology.  All of the  alternatives would require the implementation of a health and Safety
       plan to minimize any short term risks to on-site workers and nearby residents.       '•
                                                                         "   .        E   "  I
 102
                                             -7-

-------
17.     What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?              :

       Technical considerations were not primary in selecting a remedy. However, in situ soil
       flushing was eliminated for the following reasons. The  contaminated soil at the site is mainly
       sandy soil and gravel with high hydraulic conductivity (1.71 x 10'2 to 1.96 x 10'3 cm/sec).
       The ground water table is approximately 20 feet below grade.  There are no horizontal or
       vertical confining barriers to isolate the contaminated areas; therefore] the flushing solution
       would migrate into the ground water and would not be effectively captured. The  site also
       contains a discontinuous lens of silt'and clay in some locations at a depth of approximately 10
       feet, which  would create dead spots and make in situ flushing  ineffective.
                                                                                                   103

-------
                            Curcio Scrap Metal Incorporated
                                           OU-1

                                  Saddle Brook, New Jersey
                                          Region 2
 GENERAL SITE INFORMATION
 L
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil (mg/kg)

       PCBs
       Lead
                     4,500
                     39,300
2.     What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       •      1,800 cubic yards of soil
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                     N/A
                     7/87
                     6/90
                     6/28/91
             Background
                               I
PRP-lead                       j
PRPs:  Consolidated Edison Company of
       New York, Incorporated; Curcio
       Scrap Metal, Incorporated; SECO
       Corporation              |
FS prepared by: Blasland, Bouck and
       Lee                     ;
3.     What type of site is this?

       Recycling.  An active scrap metal recycling business.
TECHNOLOGY SELECTION                                   '                    !

4.      What standard technologies were considered for selection in this FS?               ;

       Typically standard technologies are identified during the initial screening process, In this case,
       no initial screening process was conducted.  Technologies presented below were extracted from
       the proposed RAAs.                                                          ;

       Access restriction:     Fencing, deed restrictions                 '      '         i
       Containment:          Asphalt surface pavement                                :
       Chemical treatment:    Stabilization/solidification (cement, pozzolan, thermoplastic, pqlymer)
       Thermal treatment:     Off-site incinerator                                      i
       Disposal:             Excavation, off-site disposal at RCRA/TSCA landfill       , - :  "
   104
                                            -i-

-------
5.       Was an- innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                         ,      ... -      j

        Thermal treatment:    In situ vitrification                         ;
        What was the cost estimate for the innovative technology?           i

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs typically are estimated as part of a three-criteria screlening process
        (effectiveness, implementability, and cost). In this case, the three criteria screening was
        eliminated and technologies are introduced for the first time in the detailed analysis.
        Estimated costs were calculated during an evaluation based on the nine criteria established by
        the NCP. Costs were recalculated for the description of alternatives presented in the ROD.
                         -                   '     '                       '
                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)     !           •-    •
Alternative
RAA-6
Innovative Technology
In situ vitrification
Estimated Costs
9 Criteria
$1, 670,000
ROD
eliminated
        How did>the cost(s) compare to standard technologies?              ;

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)     i
Alternative
RAA-1
RAA-2
RAA-3
JfcAA-4
RAA-5
Standard Technology
No action/fencing/deed' restrictions
Asphalt surface pavement
Excavation/off-site disposal at RCRA/
TSCA disposal facility
Excavation/off-site incineration at
RCRA/TSCA permitted incinerator
On-site stabilization/solidification
Estimated Costs
9 Criteria
!EO
$171,000
$1,650,000
$11,400,000
$930,000
ROD
$0 '•'
$242,000
eliminated
$7,500,000"
eliminated
        While the decrease in estimated cost between the FS and ROD is noit explained, it appears to
        be due to miscellaneous costs (20 percent) and contingency costs (25tpercent) that are included
        only in the FS calculation.                                        !          ,
                                                                                                105
                                               -2-

-------

 5.      If a standard technology was chosen, why?

        Excavation with off-site incineration was selected as the remedy at the site, due to the high
        concentration of contaminants in the soil and the corresponding high risk associated with the
        contamination.  EPA is addressing the soil remediation on an expedited basis.  The remedy
        was selected because of the following reasons: 1) need to expedite clean-up, 2) compliance
        with regulations, specifically TSCA (soils contaminated with PCBs at concentrations [greater or
        equal to 50 ppm can be  incinerated, treated by an equivalent method or disposed in a TSCA
        landfill), RCRA Land Disposal Restrictions (LDRs) and NJDEP Soil Action Levels, j 3) other
        standard technologies and innovative technologies were not considered equivalent treatment to
        incineration by TSCA and would not comply with LDRs or the NJDEP Soil Action Levels, 4)
        permanence, 4)  need to not interfere with the on-going scrap metal reclamation operations, 5)
      •  the small size of the site.                                        . •   ';   .       '


9.      If an innovative technology was chosen, why?                        .            j                      ;
                                                                                   "  ' i. •            '         ',
        An innovative technology was not chosen.                                        !
                                                                                     • i                   *   -;1-'-
                                                             -             • .           |                      '''-'

10.     V on innovative  technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                                          !

        Innovative technologies could be eliminated from the remedial technology selection process at     ^fc  ~-\
        three stages:  during the initial screening; during the screening of the three criteria of i             ^P  J
        effectiveness, implementability, and cost; or during the detailed evaluation.     '  '   i               ^     ,|

        Innovative technologies eliminated during the initial screening include the following: I                      |

        •      Biodegradation was eliminated  because it is not effective on the types of contaminants              i
              at the site.                                                              i           •           >
        •      Vacuum/steam extraction was eliminated because is not effective on  the types! of                    I
              contaminants at the site.        .                    ,                      i                  ,
        •      Soil flushing was eliminated because it would significantly deteriorate the quality  of
              groundwater and may have limited effectiveness for the treatment of metals iri soils.

       Innovative technologies eliminated during the screening of the three criteria include the                     J
       following:   ,                                                               ,    j                      £
                                                                •                      i ~                     T
       »      None, not performed.                                                     I                      :L

       Innovative technologies eliminated during the detailed analysis include the following: |                   •   t

       •      In situ vitrification was eliminated because1) its  effectiveness is unproven ami
              extensive pilot testing would be required, 2) the time to conduct the pilot test was a               '  j
              concern due to the magnitude of human health risks presented by the site, 3) no                     '
              Superfund site had been treated  at the time of the ROD with ISV, 4) migration
              potential  of contaminants, 5) requires specialized equipment and highly trained             ^^  V
              personnel, 6) small size of site would not accommodate ISV equipment.                   ••  ) j
                                             "                                        i            " ^«^    _f

 106                                                                               \
                                             -3-       •     •.                     , -   '      '           .     '

-------
11.
13.
                                                               :                 •
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?
       Important factors in selecting the remedy were: compliance with
       effectiveness; reduction of toxicity, mobility or volume; and impleme
                                                                   ; short term
                                                               ntability.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Carcinogens
PCBs
Lead
Cleanup Level (mg/kg)

1
250 -.1,000
ARAR or Other Basis
i
EPA"
NJDEP"
               "EPA "Guidance on Remedial Action for Superfund Sites
               OSWER Directive No. 9355.4-01, August 1990.
               ""New Jersey Department of Environmental Protection Soil
                                                             wih
    PCB Contamination,"

Action Levels.
 Was the innovative technology eliminated because of the cleanup goals? Could the standard
 technology meet the cleanup goals?     .

 Innovative technologies eliminated because of cleanup goals include

 •      None                    .-
                                                ,'*
 Standard technologies, eliminated because of cleanup goals include:

 •      Surface pavement             /
 »      Stabilization/solidification
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Time to design/construct/operate
               Proven reliability
               Preference for treatment (vs. containment)
        -      Impact on nearby populations
                                               -4-
                                                                                                 107

-------
16.    How are measures compared?      •   •.   •       •                               I
                                                                                      !
       Due to the magnitude of risk posed by the site to on-site workers, visitors, and nearby
       residents, choosing a readily implementable alternative was critical. Proven reliability was,
       therefore, an important factor  since treatability studies for unproven technologies would require
       too much time.  Two technologies, in situ vitrification and stabilization/solidification,! were
       eliminated because their effectiveness in remediating site contaminants was unknown and they
       would require,treatability  studies prior to implementation. The selected alternative's treatment
       technology was preferred  over containment technologies proposed in other alternatives.
17,     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Site size was a primary factor in determining a remedy.
  108
                                              -•"I.

-------
                                    Ellis Property

                            Evesham Township, New Jersey
                                       Region 2
      AT STTF INFORMATION
1. What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:
Soil(mg/kg)
Arsenic 31.8
Lead 3,790
PCBs 23
Bis(2-ethylhexyl)phthalate 2.3
1 Chromium 123
Sediment (mg/kg)

Site
NPL Proposed:
NPL Final:
•pc-
ro. .
ROD:
Bac
EPAFund-lead
PRPs: Irving and
FS prepared by: I
T
. Inc.


History
N/A
9/1/83
4/92
9/30/92
kground
Rebecca Ellis
>.oy F. Weston,


       Lead
       Trichloroethene
                                   103
5.4
2.      '"What volume of material is to be remediated?

       The volume of material to be remediated included:

       • ;    690 cubic yards of soil contaminated with metals
       •     60 cubic yards of soil contaminated with PCBs
       B     10 cubic yards of soil contaminated with BNA compounds
       •     320 cubic yards of sediment
 3.  •  '  What type of site is this?

        Recycling.  A former drum storage and reconditioning facility
                     local ed in an agricultural area.
 TECHNOLOGY SELECTION

 4,     What standard technologies were considered for selection in this
                        FS?
        Standard technologies considered during the identification and
        technologies were:
                      screening of technically feasible
                                                                                               109
                                              -i-

-------
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
                      . Fencing, warning sighs
                       Capping (clay, concrete, asphalt, synthetic membrane), slurry wall
                       grout curtains, sheet piling, grout injection, block displacement, run
                       on/run off controls, coffer dams                          ,
                       Stabilization (in situ, ex situ)          .              '  •  :
                       Incineration                                          -   !
                       Excavation, landfill (on-site, off-site)                    '  j
6.
                                                                               i
 Was an innovative technology considered in the FS?  If so, which technology?      j

 Innovative technologies considered during the identification and screening of technicallv
 feasible technologies were:                                                      |


 Biological treatment:  In situ biodegradation, composting/farming, bioreactor       |
 Phys/Chem treatment: In situ soil flushing, dechlorination, soil washing, in situ volatilization
 Thermal treatment:    In situ supercritical extraction, electromagnetic heating with to situ
                      volatilization, in situ vitrification, low-temperature thermal treatment
                                                                       -        i

 What was the cost estimate for the innovative technology?                         \   •
                                                                               \

During the initial screening process, in which technically feasible technologies are identified
& t ^  f0rmulatlon of RAAs>'the FS does not quantify costs. After the RAAs have been
formulated, costs are typically estimated as part of a three-criteria  screening process  !
(effectiveness, implementability,  and co'st) to identify alternatives that merit a more detailed
evaluation. In tins case, the estimated costs were calculated during an evaluation based on
nine criteria established by the NCP.                    '         '. '              .   ""


         Cost Estimates  for RAAs That Include Innovative Technologies        j
                     (selected remedial alternative is in bold)                   '
       Soil
          Alternative
        RAA-SS-3A
        RAA-SS-3B
                          Innovative Technology
                  Excavation/soil washing/on-site disposal
                  Excavation/dechlorination/on-site
                  disposal
                                                                       Estimated Costs
                                                                   3 Criteria
N/A

N/A
            9 Criteria
eliminated

eliminated
                                Innovative Technology
                         Excavation/soil washing/on-site disposal
  110
                                             -2-

-------
       7.      How did the cost(s) compare to standard technologies?
*
                        Cost Estimates for RAAs That Include Standard Technologies
                                   (selected remedial alternative is in bold)
              Soil
Alternative
RAA-SS-1
RAA-SS-2
RAA-SS-4
RAA-SS-5
Standard Technology
No action
Institutional controls
Excavation/off-site incineration of
PCB-contaminated soil/off-site
disposal and possible stabilization of
soil contaminated with metals
Capping/surface controls
Estimated Costs
3 Criteria
N/A •
N/A
N/A -
• i •
N/A
9 Criteria
$646,000
$732,000
$716,000 to
$1,922,000'
$3,033,000
to
$5,616,000
              "Cost range corresponds to different cleanup levels.

              Sediment                     ...'-.
Alternative
RAA-SED-1
RAA-SED-2
RAA-SED-4
Standard Technology
No action
Institutional controls
Excavation/off-site disposal
Estimated Costs
3 Criteria
N/A
1^/A
N/A
9 Criteria
$400,000
$495,000
$376,000
              If a standard technology was chosen, why?             _     "     •:                     .,

              RAA-SS-4 was chosen because it deals effectively with the threats posed by the site's
              contaminants, thereby protecting human .health and the environment. jThe principal threat to
              the site is contaminated soil and the exposure pathways that include infiltration of soil
              contaminants into ground water,, and further migration of contarriinanits into the aquifer.
              Excavating site soil will  ensure that the source of the risk will be reduced.  Removing'soil
              contaminants also will prevent further degradation of wetlands caused by surface soil erosion.
              The treatment of soil contaminated with PCBs/organic compounds at|an approved off-site
              facility will significantly reduce their toxicity, volume, and mobility 
-------
        comprehensive health and safety plan.  This alternative complies with ARARs and it reduces
        risk posed by the site's soil to the acceptable range of W4 to 10"6 for carcinogens and an           ^^  *\
        Hazard Index less than 1 for noncarcinogens.  This alternative is cost effective, since ;of the    -        —"'"'
        alten stives that most effectively address threats by site contaminants, it provides overall
        protection proportionate to its cost.                                            '   '•

        RAAs for sediment were developed in the FS but not carried forward to the Proposed Plan or
        the ROD. A remedial action to address the wetlands sediment was deemed unnecessary since
        the New Jersey Department of Environmental Protection and Energy (NJDEPE) and EPA
        determined that the contaminants in the surface water and sediments of the wetlands do not
        pose an unacceptable risk to human health and the environment.                    '•
                                                                                       i


9.      If an innovative technology was chosen, why?                                    •'*•'.
                                                                                       |

        An innovative  technology was  not selected.                                      . i


10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                                          i

        Innovative technologies could be eliminated from the remedial technology selection pijocess at
        three stages: during the initial  screening;  during the screening of the three criteria of j
        effectiveness, implementability, and cost; or during the detailed evaluation.     '     i
                                  •          .        -  •'         .      .   .              |        -.      •~"
        Innovative technologies eliminated during the initial screening include the  following: ;      ,        ^^  )

        •      In situ  biodegradation was eliminated because it would be very difficult to control or
               verify the success of the treatment, toxic byproducts could be formed, and the!
               technology would not be effective on metals.                               i
        •      In situ  supercritical extraction was eliminated because it would not remove metals and
               would be applicable only to volatile and semivolatile contaminants, which are ja
               concern only in the wetland sediment.  Furthermore, the  low permeable site solils
               would retard the flow of contaminants through the soil^ this  technology would!be more
               applicable to deep contamination in contrast to the shallow contamination at this site,
               and the shallow ground water table would create further problems.           |        -
        •      In situ  volatilization was eliminated because it would not be applicable to the site since
               VOC contamination is in saturated soil. This process would not be effective in
               saturated  soil  since porous soil is required to allow sufficient air flow.        \    -    .
        •      Electromagnetic heating with in situ volatilization was eliminated because it wbuld not
               be effective on metals and would be inhibited by shallow ground water and tight, low
               permeability soil.
        •      In situ vitrification was eliminated because it would be technically  unfeasible to vitrify
               sediment  located in the wetland  without permanently destroying the wetland,  i       .
        •      In situ soil flushing was eliminated because of uncertainties associated with introducing
               solvents into an uncontrolled environment, the enhanced migration  of hazardous     .
               materials  requiring capture and treatment, and the ineffectiveness of this technique in
               wetlands since they are periodically saturated.                              j
       •     Low-temperature thermal treatment was eliminated because the relatively low !
              concentrations of VOC-containing  sediment would not justify the permitting arid
112
                                              -4-

-------
11.
12.
              expense associated with construction of an on-site treatment system. Further, the
              process would not address metals.                                :
       •    ,  Composting/landfarming was eliminated because the degree of treatment and products
              of degradation are uncertain.  Furthermore, it would not be effective for treating metal-
              containing soil and therefore the treated soil  would require subsequent
              treatment/disposal.                                        !
       •      Bioreactor was eliminated because treatment would take a long time; it would not be
              effective for metals removal or treatment, and therefore metal-containing soil would .,
              require further treatment/disposal; and extensive treatability studies would be required
              to identify suitable microorganisms and to determine if treatment goals could be met.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:  >                                                     ;...'••        ;
                                                                       i
       •      Soil washing was eliminated because of its uncertain effectiveness in meeting treatment
              action levels for site soil, the high unit cost for construction £|nd operation of the
              treatment system, and the requirement for disposal or treatment of the spent wash
              solution.  ,                                          .:....'
       •      Dechlorination for soil treatment was eliminated because of its uncertain effectiveness
              in meeting treatment action levels for site soil, the high unit cost for construction and
              operation of the treatment system,  and the requirement for disposal or treatment of the
              spent reagent solution and wastewater.

       Innovative technqlogies  eliminated during the detailed analysis include the following:

       »      None
Which of the nine criteria were weighted most heavily in selecting
to meet one of the nine criteria result in the elimination of the
which criterion? Which of the criteria supported the use of a
    the technology?  Did failure
 innovative technology?  If so,
standard technology?
       Long-term effectiveness and permanence and compliance with ARARs
       weighted most heavily in selecting a remedial alternative.  These
       the chosen alternative.
                                                                  were the criteria
                                                            criteria were best provided by
       Some innovative technologies (soil washing and dechlorination) were
       cost.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
        NJDEPE requested that soil be remediated to the levels specified in i
        Standards for Contaminated Sites (February 1992). While these
        recognized as ARARs under CERCLA because they are not yet
        that they do not conflict or are not inconsistent with the remedy.
        fund the incremental costs associated with this additional cleanup.
                                                             The
                                               -5-
                                                                 eliminated due to high
                                                               its
        Proposed Cleanup
   proposed standards are not
  promulgated, EPA determined
        NJDEPE has agreed to
                                                                                             113

-------
 13.
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Bis(2-ethylhexyl)
phthalate
Lead
PCBs
20/20
46/49
500/100
1/0.45
Risk"/NJDEPEb
Risk/NJDEPE |
Risk/NJDEPE !
Risk/NJDEPE j
Noncarcinogens
Chromium
945/NA
Risk/NJDEPE ;
        *EPA's risk-based cleanup levels.                                          j
        "WDEPE's proposed residential soil cleanup, levels for contaminated sites.    :

 These cleanup levels will reduce exposure risk posed by soil to an acceptable range of; lO^to
 10'  for carcinogens and to a Hazard Index less than 1 for noncarcinogens.           '
                                                                             1   !

 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?                                               i

 Innovative technologies eliminated because of cleanup goals include:                 '
                                                                                l
 •      Soil washing                                                             j
 •      Dechlorination                                                           ;
                                                                    '      '      i  .
 Standard technologies eliminated because of cleanup goals include:                  ;
                                                                '         • "      i '-
 •     None                                 •                                   I
 14.
Were treatability studies conducted on the innovative technology or standard technology?

Treatability studies were not conducted.                                            '
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Single vs. two treatments
             Preference for treatment (vs. containment)
             Waste left in place/institutional control
114
                                              -6-

-------
16.     How are measures compared?                           '••.!'
                                                                        ,f          '
       Because of the different types of contaminants present in the soil, treatment of the soil with a
       single technology was not practicable.  As described in the FS, no single technology would be
       effective for treating organic compounds, PCBs, and heavy metals in soil.  Furthermore, the
       cost of constructing an on-site treatment system would not be justified by the small volume of
       metal-contaminated soil.  The selected alternative addressed this problem by providing two
       individual remedies for PCB-contaminated and metal-contaminated soil.

       RAA-5 was eliminated because treatment was preferred over cpntainmbnt since it would offer
       greater long-term effectiveness and permanence and meet all ARARs. iRAA-2 was eliminated
       because institutional controls were deemed to be unprotective because they would  not control
       off-site migration or infiltration of contaminants.          "          i  .
17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?              |
                                            '                    •        i       -               ' i --
                                                                        t.
        The saturation, low permeability, and high water table were technical considerations in
        selecting a remedial alternative; however, no technical considerations were primary. One
        reason capping was not chosen is that future fluctuations in the water .liable could bring it into
        contact with contaminated soil  causing an increase in contaminant volume.  Many technologies
        were eliminated because they could not be implemented in low-permeability soil.  These
        include in situ supercritical extraction, in situ volatilization, and electromagnetic heating with
        in situ volatilization.                     ,
                                               -7-
                                                                                                 115

-------
                                Endicott Vfflage Well Field
                                            OU-2

                                 Village of, Endicott, New York
                                           Region 2
              Site History
 NPL Proposed:
 NPL Final:
 FS:
 ROD:
10/15/84
6/10/86
7/92
9/92
 GENERAL SITE INFORMATION

 L      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

        Landfill Waste (rag/kg)

        BTEX compounds     20
        Trichloroethene       110
        1,2-Dichloroethene     15
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:

        •      No specific waste volume was .
               provided; the average depth of waste
               is 15 to 20 feet over 60 acres.
3.     What type of site is this?         .                                             ;
                                                                                 ~ i   •
       Municipal Landfill.  An active landfill located in a rural area.  '  '  -'               !

                                                                                   i
TECHNOLOGY SELECTION                                                        '

4.     What standard technologies were considered for selection in this FS?               \

       Standard technologies considered during the identification and screening of technically ifeasible
       technologies were:                                                            ,
                                                                                   i
       Access restriction:     Deed restrictions, fencing                                 :
       Containment:          Capping (native soil, single barrier, double barrier)           !
       Physical treatment:     Gas venting                                        ••.!..
             Background       \

PRP-lead
PRPs:  Endicott Johnson Corporation,
       George Industries, Inc.,    :
       International Business Machines
       Corporation, Midstate Lithd,
       Village of Endicott, Town of
       Union               •  " _ j
FS prepared by: Ground Water    j
       Associates               '
 116
                                            -i-

-------
5.      Was an innovative technology considered in the FS?  If so, which technology

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were::

       Physical treatment:    Vacuum extraction
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible
        (prior to the formulation of RAAs), the FS does not quantify costs.
      '  formulated, costs are typically estimated as part of a three-criteria
        (effectiveness, implementability, and cost) to identify alternatives that
        evaluation.  In this case the estimated costs were calculated during an
        criteria established by the NCP.  No  innovative technologies were  i
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
tec! nologies are identified
  After the RAAs have been
screening process
    merit a more detailed
    evaluation based on nine
 incorporated into RAAs.
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-3C
RAA-3D
RAA-4A
RAA-4B
RAA-4C
Standard Technology
No action
Institutional controls
Native soil cover
Native soil cover/leachate treatment
with air stripping
Native soil coverAeachate transported
to POTW for disposal
Native soil cover/piping leachate to
POTW for treatment and disposal
Low permeability barrier cap
consistent with 6NYCRR Part 360
Low permeability barrier cap
consistent with 6NYCRR Part 360/
leachate treatment with air stripping
Low permeability barrier cap consis-
tent with 6NYCRR Part 360/leachate
transported to POTW for disposal
Estimated Costs
3 Criteria
N/A
N/A
JST)A
\. N/A
N/A
('
NfA
i
N/A
N/A
1
[
N/A
'i.
1 i
9 Criteria
$132,500
$390,000
- $3,267,000
$4,830,000
. $4,811,600'
$4,634,800
$43,508,700
$45,071,700
$45,053,300
                                               -2-
                                                                                                 117

-------
            Alternative
           RAA-4D
           (RAA-5A/B)'
          ,(RAA-5A/C)a
          (RAA-5A/D)8
                           Standard Technology
                    Low permeability barrier cap consis-
                    tent with 6NYCRR Part 360/piping
                    leachate to POTW for treatment and
                    disposal
                    Low permeability barrier cap with
                    6NYCRR Part 360 variance/leachate
                    treatment with air stripping
                   Low permeability barrier cap with
                   6NYCRR Part 360 variance/leachate
                   transported to POTW for disposal
                   Low permeability barrier cap with
                   6NYCRR Part 360 variance/piping
                   leachate to POTW for treatment and
                   disposal
                                                                       Estimated Costs
                                                                  3 Criteria
                                                                     N/A
N/A
N/A
N/A
             9 Criteria
            $44,8:76,500
                                                                                $12,710,000
                                                                                $12,747,200
        *RAA-5 was developed in the Proposed Plan and ROD.


 8.      If a standard technology was chosen, why?

        RAA-5A/B was preferred because it protects human health and the environment by containing
        waste with a landfill cap, by controlling landfill gas through monitoring and venting and by
        controlling and treating the leachate seep.  By reducing leachate production the remedy limits
        further contamination of ground water and thereby builds upon other site actions at OU-1 and
        OU-3,  It complies with all federal and state ARARs.  The selected remedy affords overall
        effectiveness proportional to its cost because, among other things, it uses a terraced or !
       .washboard design to attain a 4-percent slope to promote runoff, thereby reducing infiltration
        and leachate generation. The landfill waste will not be treated because it is not practical
        Since no "hot spots" were identified, effective excavation and  treatment of contaminant's is
        precluded.                                                               .   -   | .
9.
If an innovative technology was chosen, why?

An innovative technology was not selected.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative1
technology eliminated?                                           ,              |  .

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of  j
effectiveness, implementability, and cost; or during the detailed evaluation.           i
118
                                             -3-

-------
11.
12.
13.
       Innovative technologies eliminated during the initial screening include the following:

       •      None

       Innovative technologies eliminated during the screening of the three .< riteria of technologies
       include the following:

              Vacuum extraction was eliminated because of the high capita  and operating costs for
              an active gas system, versus a passive gas collection system.
              offers only a negligible increase in effectiveness and no regulatoiy basis for selection.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      None
       Which of the nine criteria were weighted most heavily in selecting the
       to meet one of the nine criteria result in the elimination of the innovative
       which criterion?  Which of the criteria supported the use of a standard
       Long-term effectiveness, reduction of contaminant mobility, and cost
       weighted most heavily in selecting a remedial alternative.  Of the two
       reduce landfill infiltration and resultant leachate generation, the least
                                                                 were the criteria
                                                                  RAAs that would best
                                                                expensive was chosen.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
       No cleanup goals were developed for the landfill.  Treatment of the
       its size and the fact that no "hot spots" were identified that represent
       contamination that could be excavated and treated effectively.
Was the innovative technology eliminated because of the cleanup got Is?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None
            •'           '     •      .              I   .  .
Standard technologies eliminated because of cleanup goals include:

•      None
14.     Were treatability studies conducted on the innovative technology or j

        Treatability studies were not conducted.
                                               -4.
                                                                 An active gas system
                                                                  technology ? Did failure,
                                                                     technology? If so,
                                                                   technology?
                                                                landfill was precluded by
                                                                 major sources of
                                                                 tandard technology?
                                                                                               119

-------
 75.     What measures/criteria were used to compare alternatives?                    ..-  '•

        The following measures were used to compare the alternatives:                    *

              Percentage risk reduction                                        ''•'••
              Cost-effectiveness                                                       |
              Waste left in place/institutional control                              "      >

                                                                                     i       •
 16.     How are measures compared?                                                  !

        RAA-5 was preferred over RAA-1 and RAA-2 because they would not be protective jof human
        health and the environment. No action or institutional controls would minimize landfill
        infiltration and leachate generation. RAA-5A/B was preferred over RAA-3 because it provides
        a thicker cap and a runoff system, which will better reduce the leachate generation arid provide
        a greater reduction in contaminant mobility and volume.  Further, RAA-5 will be more
        effective in the short term because it limits leachate production, allowing more effective
        cleanup of ground water.  RAA-4A-D were comparable to RAA-5A/B  in most respects
        RAA-4A-D would have been slightly more effective in the long term because it meet& the
        most stnngent standards for a low permeability cap. RAA-5 is much less costly and is cost
        effective.
17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

No technical considerations were primary in selecting a remedial alternative.
120
                                            -5-

-------
                       Facet Enterprises, Incorporated
                               '.          .          -      " *
                       Village of Elmira Heights, New Yprk
                                     Region 2
7. What were the principal
contaminant levels, and
this feasibility study?
contaminants,
media addressed in

Maximum concentrations of principal
contaminants were:
Surface Soil (mg/kg)
Benzo(a)anthracene
Benzq(b)fluoranthene
Benzo(k)fluoranthene
Benzo(a)pyrene
Indeno(l,2,3-cd)pyrene
PCBs
Arsenic
'-....

' 43
69
69,
7
16
11
Site
NPL Proposed:
NPL Final:
FS:
ROD:
Bac
PRP-lead
PRPs: Facet Entt
'FS prepared by: 1


247 ' — 	 	
History
10/1/81
9/1/83
3/45/92
. 9/29/92
kground
rprises, Inc.
iRM-Northeast, Inc.



     Subsurface Soil (mg/kg)

     Benzo(a)anthracerie
     Benzo(b)fluoranthene
    ' Benzo(k)fluoranthene
     Benzo(a)pyrene
     PCBs

     Surface Sediments (mg/kg)

     Benzo(a)anthracene
      Benzo(b)fluoranthene
      Benzo(k)fluoranthene
      Benzo(a)pyrene
      Indeno(l,2,3-cd)pyrene
      PCBs
      Arsenic
      Chromium
                          160
                          330
                          330
                          130
                          28
                          8,000
                          30,000
                          30,000
                          22 .
                          6
                           14
                           320
                           3,920
2.
What volume of material w to be remediated?

The volume of material to be remediated included:

•      1,840 cubic yards of surface soil
•      3*,630 cubic yards of subsurface soil
                                            -1-
                                                                                         121

-------
        "      2,704 cubic yards of sediment


 3-      What type of site is this?                   . '

        Industrial Landfill.  A manufacturing facility and


TECHNOLOGY SELFCTrnM

4.
                                                      associated disposal areas
6.
         Access restriction:
         Containment:
         Chemical treatment:
         Physical treatment:
         Thermal treatment-
         Disposal:
                           Fencing, security, deed restrictions
                           Cap (soil, vegetative, RCRA)
                           Stabilization
                           Dewatering
                           Incineration
                           Excavation, disposal at off-site RCRA landfill
        Biological treatment:   Biodegradation
        Chenuca  treatment:    Soil washing (solvent)
        Thermal treatment:     Low-temperature thermal aeration
                                                  •
                        estimate for the innovate technology?
                                                 ^ntification .d screening of tecnnicall
                                                                technologies are identified
               d, costs are usually estimated « p^TtC^T8'  ^ ^ RAAs ^ been
       (effectweness, implementability, and cost) 10^^  u       screei»ng process
       SSBS             -» -
122
                              Innovative Technology
                                                                            9 Criteria

                                                                            $2,342,064
                    Low-temperature thermal treatment/
                    KCRA cover

-------
         7.      How did the cost(s) compare to standard technologies?
                          Cost Estimates for RAAs That Include Standard Technologies
                                    (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-6
RAA-7
RAA-8
Standard Technology
No action
Deed restrictions/fencing/security
RCRA cover
Stabilization and RCRA cover
Off-site disposal
On-site RCRA-cell disposal
Off-site treatment (stabilization) and
disposal at RCRA landfill
Estimated Costs
3 Criteria
N/A
tf/A
N/A
N/A
N/A
. N/A
N/A,
9 Criteria
$0
$9,730
$1,047,943
$1,582,718
. $2,811,931
$1,187,101
$2,462,334
. ^HL;
8.      If a standard technology was chosen, why?

       A standard technology was selected.  The remedy includes stabilization and off-site disposal.
       This remedy was selected because it: 1) would comply with lland Disposal Restrictions by
       using a stabilization method that would meet TCLP standards, 2) other alternatives would have
       to meet New York state requirements, 3) risks from exposure to contaminated soil and
       sediment would be removed, 4) future use of property will be unrestricted, 5) reduces the
       mobility of inorganic contaminants, 6) involves little construction and implementation, 7)
      , equipment and personnel are readily available.
        9.      If an innovative technology was chosen, why?

               An innovative technology was not chosen.
        10.     If an innovative technology was not chosen, why not? At what stage was the innovative
               technology eliminated?                                           ;
                                                                               !   '
               Innovative technologies could be eliminated from the remedial technology selection process at
               three stages:  during the initial screening; during the screening of the three criteria of
               effectiveness, implementability, and cost; or during the detailed evaluation.

               Initial screening was not completed. Innovative technologies eliminated during the initial
               screening  include  the following:

               •      None                        ,
                                                      -3-
                                                                                                     123

-------
                                                                                    '  !
       Innovative technologies eliminated during the screening of the three criteria include the
       following:   •              .                                                   j
                                                                                      I
                                                                                      !
       •      Soil washing was eliminated because it has not been used extensively, so that! it's
               effectiveness is not well documented; soil at the site with a high percentage of silt and
               clay will adsorb contaminants and be difficult to remove with soil washing; soil could
               be transformed into sludge, which would require dewatering and additional treatment;
               a literature survey does not show soil washing use on metal hydroxides; the buffering
               capacity of metal hydroxide in the waste would hinder soil  washing; no cost j
               information is available; no full-scale remediations using soil washing have occurred;
               some vendors require a minimum volume to be treated which exceeds the volume o be
               remediated at the site; Geraghty and Miller soil washer is not effective for soils
               containing greater than 20 to 30 % fines or with particle size less than 63 microns; and
               several U.S. remediation contractors, which offered this technology in the past have
               ceased performing this work or have ceased operations.                     I
       •      Biodegradation was eliminated because: the chemicals of concern at the facility  may
               not be amenable to this technology, specifically the PCBs and semi-volatiles may not
               biodegrade; metals in the  soil may prove toxic to  microorganisms; contaminant
               concentrations may not be high enough to promote biodegradation; extensive bench
               and pilot scale treatability studies would  be required; remediation would be lengthy
               and a time consuming process.                                           !
                                  -•.'".'•"'                         !
       Innovative technologies eliminated during the detailed analysis include the following:;  .

       •      Low  temperature thermal  treatment was eliminated because: it would require i
               treatability testing to ensure effectiveness, and it would have to meet New York State
               air regulations prior to full-scale operation.                                |
.^f,
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology? \
                                                                                      i

       The criteria that were weighted most heavily in selecting a remedial alternative were protection
       of human health and the environment and long-term effectiveness, reduction in toxicity,
       mobility and permanence, and implementability. No innovative technologies were eliminated
       due to these nine criteria.                                                        [         ,
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

               Surface Soil
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
i
Carcinogens
Benzo(a)anthracene
Benzo(b) fluoranthene
20
20
Risk3
Risk 1
      124
                                              -4-

-------
Contaminant
Benzo(k) fluoranthene
Benzo(a)pyrene
Indeno(l,2,3-
cd)pyrene
PCBs
Arsenic
Cleanup Level (mg/kg)
43
3 -
12
10
19
ARAM or Other Basis
! - "
\ Risk
Risk
; Risk
EPA"
Risk
"For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
to 10"6 was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0
was acceptable.
bU.S. EPA "Guidance on Remedial Actions for Superfund Sites with PCB
Contamination," OSWER Directive No. 9355.4-01.

Surface Sediment
Contaminant
Carcinogens
Benzo(a)anthracene
Benzo(b) fluoranthene
Benzo(k) fluoranthene
Benzo(a)pyrene
Indeno( 1,2,3-
cd)pyrene
PCBs
Arsenic
Chromiumb
Cleanup Level8 (mg/kg)

3
3
7
1
•" 2
1.
7
1,110
ARAiR or Other Basis

• Risk
Risk
Risk
Risk
Risk
; EPA
:Risk
Risk
"Cleanup levels are lower for the drainage way and Creek
there is a greater potential for exposure.
""Remediation goals assume that all chromium is present as

Subsurface Soil
      Contaminant
Cleanup Level (mg/kg)
ARAR
  Carcinogens
  Benzo(a)anthracene
         54
                              -5-
                           surface sediments because

                            hexavalent chromium.
or Other Basis
        Risk
                                                     125

-------
i
Contaminant
Benzo(b) fluoranthene
Benzo(k) fluoranthene
Benzo(a)pyrene
PCBs
Cleanup Level (mg/kg)
55
118
8
25
ARAR or Other
i
Basis
Risk ;
Risk
i
i
i
Risk '\
EPA
i
'13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard,
        technology meet the cleanup goals?                                            i

        Innovative technologies eliminated because of cleanup goals include:-              '"  .
                                                                                     i
        •      None                                                                 I

        Standard technologies eliminated because of cleanup goals include:                |

        »      Capping                                                              i
                                                -                                  •   i

 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                                          i

                                                                                     i      ' •
                                                                                     I   .
 75.     What measures/criteria were used to compare alternatives?                       |

        The following measures were used to compare the alternatives:                    '
                                                                                     i
               Proven reliability         .                                            . |    '  .
               Preference for treatment (vs. containment)                               i
               Time to design/construct/operate                                        i
                                                                                     i

 16.     How are measures compared?                 •    .<.                            \

        Some technologies were eliminated because their reliability was unproveri and they would
        require treatability studies, which would increase cost and implementation time.     j
 17.     What technical considerations were factors in selecting a remedy?  Were, technical
        considerations primary in the selection of the remedy?                           '

        The percentage of fines in the soil were too high for soil washing.                 ''~
   126
                                               -6-

-------
                              Fibers Public Supply Wells
                                          OU-2

                                   Guayama, Puerto Rico
                                         Region 2
GENERAL SITE INFORMATION
1. What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (mg/kg):

Chromium 2,110
Asbestos 40
PCB 1.88
Tetrachloroethene 65
Trichloroethene ,67
, " . -

2. What volume of material is to be
remediated?
~~ - . . '

Site History

NPL Proposed: N/A
NPL Final: . 9/1/84
FS: , 4/91
ROD: 9/30/91

Background

PRP-lead
PRPs: ' Phillips Petroleum
Chevron Chemical Company,
Home Products











Company,
American

FS prepared by: ILeggette, Brashears and
Graham, Incorporated

~ ' ,



       The volume of material to be remediated
       included:

       •      9,010 cubic yards of soil
3.      What type of site is this?

       Rubber and Plastic Products. A soil disposal area formerly used by a nylon and polypropylene
       fiber manufacturing plant.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in, this FS1'

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Deed restrictions, fencing
       Containment:         Capping, slurry wall
       Physical treatment:     In situ stabilization/solidification
       Thermal treatment:     Incineration
                                                                                         127

-------
        Disposal:
Excavation, off-site disposal
5.      Was an innovative technology considered in the FS?  If so, which technology?       \

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                                       |
                        •                  •                                             i •
                                                                                       i -
        Biological treatment:   In situ biodegradation, ex situ biodegradation                i
        Chemical treatment:  '  In situ soil flushing (water or surfactants)                   !
        Physical treatment:     In situ vacuum extraction                                  j
        Thermal treatment:     Steam stripping, in situ vitrification, radio frequency decontamination
6.      What was the cost estimate for the innovative technology?                          i -

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during a detailed evaluation based on the nine criteria
        established by the NCP. No innovative technologies were included in the remedial action
        alternatives, therefore, no cost estimates were made.
7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action/air monitoring
Deed restrictions/fencing/warning
signs
Capping/deed restrictions/
fencing/long-term maintenance
Excavation/off-site disposal
Estimated Costs
l
3 Criteria
$169,000
$232,000
$450,000
$1,315,000
9 Criteria
$1691000
$232,1000
.' '!
$450JOOO
i
$1,231,000
8.      If a standard technology was chosen, why?                                        1

       RAA-4 was chosen because it would eliminate risks of long-term exposure; offers a permanent
       solution; reduces contaminant toxicity, mobility, and volume; and provides overall     !
       effectiveness in proportion to its cost. RAA-4 was selected even though it will pose s
-------
         environment.  RAA-2 was not chosen because it would reduce only c-ontaminant mobility and
         its long-term effectiveness was questionable, as it depended on deed restrictions, which are
         difficult to enforce.  RAA-3 was eliminated because asbestos would remain on site, require
         long-term maintenance, and be less effective in the long term. Also, RAA-2 and RAA-3 may
         be less implementable than RAA-4 due to potential  difficulties in gaining deed restrictions for
         an area that has not been permitted for solid waste disposal.
 9.     If an innovative technology was chosen, why?

        An innovative technology was not chosen.
 10.
11.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?                                           i
                               ' ,                               'i.'1'.';           ''  ' C'
 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages:  during the initial screening; during the screening of the three criteria of
 effectiveness, implementability, and cost; or during the detailed evaluation.

 Innovative technologies eliminated during the initial screening include the following:

 •      In situ biodegradation was eliminated because it would be effective only for organic
     ,   wastes and not for asbestos removal.                       !
 •      Ex .situ biodegradation was eliminated because it would be effective only for organic
        wastes and not for asbestos removal.                       •
 •      In situ soil flushing was eliminated because asbestos is insoluble aind would not be
        removed from the soil.
 •      In situ vacuum extraction was eliminated because it would be effective only for
        volatile  organic compounds and not for asbestos removal.    '
 •      Steam stripping was eliminated because it would be effective only for organic
        compounds and not for asbestos removal.                   :
 •      Radio frequency decontamination was eliminated because it wouM not be effective for
        chemicals  with boiling points lower than 400 degrees centigrade, such as asbestos.
 •      In situ vitrification was eliminated because it would be very expensive to transport
        specialized equipment to Puerto Rico from United States' mainland.

No innovative technologies were include in the RAAs, therefore no innovative technologies
were eliminated during the three-criteria screening process or during detailed analysis.

                                                                . i                '  '
Which of the nine  criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the  nine criteria result in the elimination of the innovative technology?  If so
which criterion? Which of the criteria supported the use of a standard technology?
                        ',                             '•-!,'<••
For those RAAs that provided adequate protection of human health and the environment and
attained ARARs, long-term effectiveness and implementability were weighted most heavily in
selecting a remedy.
                                              -3-
                                                                                         129

-------
12.    What cleanup goals -were selected?  If the cleanup goal was based on an ARAR, whait was that
       ARAR?  What risk level was selected to establish cleanup goals?                   i
                 Contaminant
Cleanup Level (%)
ARAR or Other Basis'
                 Carcinogens
                 Asbestos
                               NESHAF
               "National Emission Standards for Hazardous Air Pollutants.                 \

        For carcinogens, an excess upper bound individual lifetime cancer risk of between 1014 to 10"6
        was acceptable. For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                              |

        Innovative technologies were eliminated primarily because they were not suitable for jthe type
        of waste to be treated. No innovative technologies were eliminated because of cleanup goals.
        The standard technologies selected could meet cleanup goals.                      |
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                                           '
                                                                   )
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Risk level achieved
               Waste left in place/institutional control
               Permanence                              *
 16.     How are alternatives compared?                                                !
                                                         1                             i
        Although three alternatives would provide overall protection of human health and the:
        environment, the alternative selected would eliminate the risk of long-term exposures!by
        removing contaminants from the site, thereby providing a permanent solution. The reliability
        of institutional controls in preventing future exposures was questionable.           , J
 17.     What technical considerations were factors in selecting a remedy? Were technical  |
        considerations primary in the selection of the remedy?                      '      '

        Soil contamination resulted from disposal of sludge and debris in a soil disposal areal(SDA),
        which is not in contact with groundwater. (Groundwater contamination resulted from disposal
        of contaminants in separate wastewater lagoons.) No surface or subsurface migration of
    130
                                               -4-

-------
asbestos from the SDA was noted. Beyond the fact that few technolog
treating asbestos, technical considerations were not primary in selecting
at this  site.
                                       -5-
;ies are available for
  a remedial technology
                                                                                       131

-------
                                   Fort Dix (Landfill Site)

                               Pemberton Township, New Jersey
                                           Region 2
  GENERAL SITE INFORMATION
  7.
 What were the principal contaminants,
 contaminant levels, and media addressed in
 this feasibility study?

 Maximum concentrations of principal
 contaminants were:

 Waste

 Subsurface waste samples in the landfill
 were not collected  because of the unknown
 nature of wastes disposed of at the site.
 Waste types are expected to vary greatly in
 relation to spatial distribution and time of
 disposal. Based on the sampling and
 modeling of ground water, the landfill is
 believed to be the source of contamination
 to the aquifer.
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:  i
                                                     ROD:
9/14/84   i
7/87      i
7/87      i
2/24/91    !
                                                                 Background

                                                    Federal Facility
                                                    PRPs:  U.S. Army
                                                    FS prepared by:  Camp Dresser &
                                                           McKee Inc.
                                                                                   i
 2.
Wliat volume of material is to be remediated?                              '    •  i

The volume of material to be remediated included:                                i
                                         '                             •'      ;
•      The volume of material to be remediated was not given. The site .covers  126 acres.
3.     What type of site is this?                                             .-;.'•

       Military. A former landfill located on the U.S. Army's Fort Dix Military Reservation, j


TECHNOLOGY SELECTION                                                        '
                                                        -                           [

4.     What standard technologies were considered for selection in this FS?         ,      !
                                                                                   I

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                            i

       Access restrictions:     Fencing, deed restrictions                                 I
       Containment:          Capping, slurry wall, grouting, sheet piling                 - '
       Chemical treatment:    Solidification/stabilization, immobilization       ,            i
 132
                                                                                                iol
                                           rl-

-------
5.       Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:           ,-                           ;
                            '.-,'-                ,            '
        Biological treatment:    In situ bioreclamation                     |
        Chemical treatment:    In situ soil flushing, in situ chemical treatment
        Thermal treatment:     In situ vitrification
        What was the cost estimate for the innovative technology?          !
                  -       ,         •'.'•'••     "             ,     •'•   ,1 .••'''';••
        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the.FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during  an evaluation based on
        nine criteria established by the NCP. No innovative technologies were incorporated into
        remedial alternatives.                                             ,
        How did the cost(s) compare to standard technologies?    •    .    i  '

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)   :
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-3C
RAA-3Da
RAA-4A
RAA-4B
Standard Technology
No action
Low permeability cap/expanded
monitoring program
Ground water pumping/on-site treatment
Ground water pumping/off-site
treatment
Plume pumping/off-site treatment and
disposal/downgradient slurry wall/
landfill closure
Partial ground water pumping/on-site
treatment
Ground water interception/6n-site
treatment
Ground water interception/off-site
treatment
Estimated Costs
3 Criteria
|N/A
^N/A
!
i
'i
IN/A " •
IN/A
eliminated
\
•{'N/A;
i
IN/A'
I N/A
i
9 Criteria
$8,400,000
$15,100,000
$28,100,000
$32,900,000
eliminated
N/A
$31,900,000
$36,800,000
' '
a This alternative was developed in the ROD and no present worth cost was estimated.
•' - i \
1
: ' -2- ;'. '. J. ' . ..'•'•..'
                                                                                                 133

-------
                                                                                       I
 5.      If a standard technology was chosen, why?                                       j

        The chosen alternative, a low permeability cap, was preferred because it reduces siteirisks by
        eliminating direct contact with waste materials in the landfill. Additionally, fencing arid deed
        restrictions limit opportunities for contact with on-site soil and grading inhibits erosion and the
        transport of contaminants in runoff. The cap also will reduce leaehate formation by limiting
        the infiltration of rain water through the landfill. Subsequently this will reduce the rate of
        contaminant discharge to ground water and surface water.  The chosen alternative, thus,
        reduces the mobility of contaminants, minimizes short-term risk, and is the most simple to
        implement of all of the proposed alternatives. The chosen alternative meets remediation goals
        as quickly as the other alternatives, will not produce residuals that require further treatment or
        disposal,  and is cost-effective.                                                    [
                                                                                  .     i  ."

9.      If an innovative technology was chosen, why?                                     j

        An innovative technology was not chosen.                                         i
10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?                                                 -         |.
                                                                              •!•'.-•

 Innovative technologies could be eliminated from the remedial technology selection pjocess at
 three stages:  during the initial screening; during the screening of the three criteria of:
 effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                                [
                                                                             . t ' I
 Innovative technologies eliminated during the initial screening include the following: !
                                 -                          -                     i
 •      In situ bioreclamation was eliminated because microorganisms that effectively:
        synthesize volatile organics to harmless byproducts have not been identified.  Aerobic
        organism that breakdown halogenated organics have not been identified. Anaerobes
        are suspected of converting DCE to vinyl chloride a more toxic compound.  Ambient
        soils are not homogenous enough to ensure the distribution of "reactants."  Numerous
        organic food sources would compete with contaminants for biodegradation
        Bioreclamation systems would be "frustrated" by the inability to maintain and Imonitor
        the distribution of reactants throughout the waste.  No full-scale field systems have
        been demonstrated in similar hydrogeological systems.                      •
 •      In situ vitrification was eliminated because it has not been reliably demonstrated, and
        there is uncertainty regarding energy consumption, long-term degradation, andlle'aching
        potential.                                  .               '  .                    6
 •      In situ soil flushing was eliminated because the hydrogeological and geochemical
        nature of the site would preclude the effective delivery of reagents to  the contaminants
        The progress and effectiveness of the chemical process could not be forecasted or
        monitored with confidence, Introduction, control, and formation of potentially!
        hazardous substances into the subsurface system could exacerbate the  current  i
        conditions.  Performance of full-scale systems has not been adequately demonstrated.
        The process would produce a high volume of liquid waste that would  require treatment
        before disposal.                                                 -  '       •   •    .
"      In situ chemical treatment was eliminated for the same reasons (except the generation
        of liquid waste) as in'situ soil flushing. .                                   !
  134
                                             -3-

-------
       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •     None  '.                   .   .'   - -  .  ..-•'                  ;' "" .

       Innovative technologies eliminated during the detailed analysis include the  following:

       •     None                                    '                •
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The most heavily weighted criterion in the selection of a'remedial alternative was protection of
       human health and the environment. The  chosen alternative will provide as much protection as
       the other alternatives that propose containment and ground water treatment. Ground water
       treatment would not provide additional health benefit over landfill capping and closure because
       existing site conditions do not pose a  significant risk to human health and the environment.
       Under present conditions, the total risk to human health in the worst lease scenario is 1 X 10"7.
       The estimated cancer risk for future ground water use is, however, greater than the  acceptable
       range. Capping is believed to be sufficient, since it acts to reduce the infiltration of water
       through the landfill and the consequent leachate production. This technique is expected to be
       adequate to protect  ground water since under existing  site conditions the amount of ground
       water discharging to surface water is very small and the contamination appears to, be
       dissipating through  natural processes.                              .;
12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that;
       ARAR?  What risk level was selected to establish cleanup goals?    ;
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens 1
Arsenic
Cadmium
Chromium *
Lead
Nickel
PCBs
Total VOCs
.20
3
100
100
100
1-5
1
i NJDEP
! NJfDEP
; NJfDEP
NJDEP :_ ,
1 NJDEP ' '
: NJFDEP
! NJDEP
l
Noncarcinogens , \
Barium
Copper
400
170
\ NJDEP
' ] NJDEP
                                                                                                135
                                               -4-

-------
   13.
Contaminant
Mercury
Silver
Selenium
Zinc
Total cyanides
Cleanup Level (mg/kg)
1
5
4
350
12
ARAR or Other Basis
NJDEP i
NJDEP
NJDEP
NJDEP
NJDEP i
        •Based on standards established by the New Jersey Department of Environmental
        Protection's Bureau of Industrial Site Evaluation for the evaluation of cleanup plans at
        industrial sites under the New Jersey Environmental Cleanup Responsibilities Act.
                                                                              I

 Was the innovative technology eliminated because of the cleanup goals?  Could the 'standard
 technology meet the cleanup goals?                                             i

 Innovative technologies eliminated because of cleanup goals include:

 •      None                                              ^

 Standard technologies eliminated because of cleanup goals include:

 •     -None                                       . _
   14.
Were treatability studies conducted on the innovative technology or standard technology?

No treatability studies were conducted.                                           !
  15.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

               Risk level achieved
  16.    How are measures compared?                                                  j

         The chosen alternative was preferred because it meets remediation goals without the use of
         treatment.  Other alternatives that proposed ground water treatment were deemed unnecessary
         and not worth the additional effort and cost.                                      !     .
136
                                      -5-

-------
17.     What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
                                                                      This
Excavation of the waste and landfill would not be practical or safe.
consideration precluded the use of many ex situ proposed source treatments
hydrogeologic and geochemical nature precluded the effective delivery
contaminants,.in situ chemical treatment and soil flushing were eliminated
considerations were not, however, primary in selecting a remedy.
                                               -6-
  technical
      Since the site's
of reagents to the
     These technical
                                                                                                 137

-------
                                       Frontera Creek

                                     Humacao, Puerto Rico
                                           Region 2
 GENERAL SITE INFORMATION
 1.      What were the principal contaminants,
        contaminant levels, and media being
        addressed in this feasibility study?

 Maximum concentrations of principal contaminants
 were:

        Soil/Sediments (mg/kg)

        Mercury              535
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:

        •      180 cubic yards of soil
        •      370 cubic yards of sediment
                                      Site History
                         NPL Proposed:
                         NPL Final:
                         FS:
                         ROD:
N/A      ;
8/83      j
4/91      I
9/30/91    ;
                                      Background        I

                         PRP-lead                        |  .
                         PRP:  Revlon Inc.                !
                         FS prepared by:  Dynamac Corporation
                                                   <      i '
3.      What type of site is this?                                 •      .             ~ '  '••

       Electrical Equipment.  Industrial disposal of manufacturing wastewaters containing mercury
       into surface waters.                                                            <
TECHNOLOGY SELECTION
                  •        «_                                    ^                     |
                                                                                     I -.
4.     What standard technologies were considered for selection in this FS?                \

       Standard technologies  considered during the identification and screening of technically i feasible
       technologies were:                                                              j
       Access restriction:
       Containment:
       Chemical treatment:

       Physical treatment:
       Thermal treatment:

       Disposal:
Deed restriction, site security                               i
Single-layer cap, multilayer cap, slurry wall, sheet pilings, barrier walls
Fixation/solidification (cement based, silicate based, sbrbent materials
techniques, thermoplastic techniques, organic polymer processes)
Dewatering, separation-drying beds                          !
Rotary kiln incineration/multiple hearth incineration, liquid injection,
infrared advanced electrical reactor                          j
Excavation/dredging, off-site RCRA landfill, on-site RCRA landfill
 138
                                            -1-

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?
                         '              *''..•              I
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                       1  '    '
             -                                      ' • '      "    :       !            .
       Biological treatment:   Biodegradation, landfarming                ;
       Chemical treatment:   Soil washing (water or solvent), hydrometallurgical extraction,
                             oxidation-reduction, soil flushing (water or solvent)
       Physical treatment:    Soil vapor extraction                       ;
       Thermal treatment:    Ex situ  low-temperature thermal desorption, in  situ vitrification,
                             pyrolysis                             "     '    •   •
        What was the cost estimate for the innovative technology?          1

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs typically are estimated as part of the three-criteria (effectiveness,
        implementability, cost) screening process to identify alternatives of sufficient merit to undergo
        detailed evaluation.  The estimated costs are recalculated during evaluation by the nine criteria
        established by the NCP.  At this site, the three-criteria screening was conducted prior to
        formulation of RAAs; therefore, no cost estimates are included for the RAAs below in the "3
        Criteria" column.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Excavation/on-site thermal desorption/
1 backfill treated soil
Estimated Costs
3 Criteria
N/A '
9 Criteria
$959,000
        How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard
Technology
No action
Deed restrictions/access restrictions/
monitoring
Excavation/dewatering/off-site disposal
at RCRA facility on mainland USA
Estimated Costs
3 Criteria
N/A -'
N/A
N/A
9 Criteria
$0
$209,000
$562,000-
$730,000
-2-, . ' . • . , ' . ,
                                                                                                 139

-------
Alternative
RAA-4
RAA-5
RAA-7
Standard Technology
Excavation/chemical fixation/off-site
disposal at RCRA facility on mainland
USA
Excavation/on-site solidification/fixation
Remove existing water/cap/single layer
clay liner/revegetation
Estimated Cbsts
3 Criteria
N/A
N/A
N/A
9 Criteria
$661,000-
$871,000
$461,000
$442,000
 8.      If a standard technology was chosen, why?                                       ;

        RAA-3 was chosen because it offers protection to human health and the environment/meets
        all ARARs, reduces the mobility of site contaminants, provides permanence and long-term
        effectiveness, and is cost-effective.  RAA-1 and RAA-2 were eliminated because they, did not
        ensure protection to human health and the environment and they were not in compliance with
        ARARs.  Alternative RAA-4 was very similar to the chosen alternative except for the'addition
        of off-site treatment, which increased the expense and reduced cost-effectiveness  withbut
        increasing protectiveness.  RAA-5 also offered a reduction in toxicity through treatment;
        however, its long-term effectiveness was considered uncertain because future intrusive activity
        at the disposal site could result in a contaminant release.  RAA-6 offered a reduction jn
        toxicity and mobility through an innovative treatment; however, it was eliminated because it
        would require an extensive treatability study that would increase the design time of the remedy
        and it was more costly. The containment cap proposed in alternative RAA-7 was eliminated
        because it was not a permanent solution and would require long-term maintenance,   i       \
                                                                                                    )
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                                          \
                                                                               i

Innovative technologies could be eliminated from the remedial technology selection at three
stages in the process:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.          !

Innovative technologies eliminated during the initial screening include:             • I

•      Pyrolysis was eliminated because emissions of metals mat volatilize below 2000° F
       would be difficult to remove using conventional air pollution equipment. Elements
       cannot be broken down to non-hazardous compounds using thermal treatment, j
•      Soil washing was eliminated because its effectiveness with soils and sediments I
       contaminated with low levels of mercury has not been demonstrated.         !   '
•      Hydrometallurgic extraction was eliminated because its effectiveness for use with low
       concentrations of heavy metals has not been demonstrated. In addition,  there

                                       -3-               .      -.  .

-------
               concern that toxic gases would be generated during the process.
        •      Oxidation-reduction was eliminated because it is not applicable to the wastes found at
               this site.                                             .
        •      Biodegradation was eliminated because the presence of heavy | metals such as mercury
               were expected to be toxic to the microorganisms utilized in the process.
        •      Landfarming was eliminated because the presence of heavy metals such as mercury
               were expected to be toxic to the microorganisms utilized in the process.
        •      Soil flushing was eliminated because  it would be very difficult to ensure the required
               contact betweeri the flushing agent and the contaminated media in place.
        •      Soil vapor extraction was eliminated  because it is  not applicable to inorganic
               contamination.                                            :
        •      In situ vitrification was eliminated because its effectiveness has not been well
               demonstrated, it is not applicable to large volumes, and there would be excessive
               power requirements due to the high moisture content of soils, which  would greatly
               increase cost.                                             :
                           •'   •            •     .        :          '      -       -         '
        No innovative technologies were eliminated during the three-criteria screening process.
                                      •                      •          '  •!'•      • •   - '      •   ,
        Innovative technologies eliminated during the detailed analysis include:
                                                   v     *                '•        • .
       ,•      Thermal desorption, RAA-6, was eliminated because it would require an extensive
               treatability study, which would increase the design time of the remedy.  In addition,
               RAA-6 was more costly than the selected remedy.           •>
11.
        Which of the nine criteria were weighted-most heavily in selecting the
        the nine criteria eliminate the innovative technology from being chosen?
        Which of the criteria supported the use of a standard technology?
       For those alternatives that were protective of human health and the environment
       ARARs, the criteria most heavily weighted in remedial technology selection
       effectiveness, and short-term effectiveness.
12.
       What cleanup goals were selected?  Jf the cleanup goal was based on
       ARAR?  What risk level was selected to establish cleanup goals?
                                                                        an ARAR, what was that
Contaminant
Non-Carcinogens
Mercury
Cleanup Level (ppm)

35 ppm
ARAR or Other Basis

!Risk
       As there are currently no ARARs for mercury, cleanup levels were developed
       soil/sediment concentration that would not result in an unacceptable hazard
       the baseline risk assessment.  A Hazard Index (HI) less than or equal to
                                              -4-
                                                                         techhology?  Did one of
                                                                           Jf so, which one?
                                                                                  and attained
                                                                              were long-term
                                                                                to estimate the
                                                                             using the results of
                                                                          1.0 was acceptable.
                                                                                                 141

-------
13.     Was the innovative technology eliminated because of the cleanup goals? If a standard
        technology was chosen, could it meet the cleanup goals?                           \   .
                                                                                       i   •.    .  -•        .J-
        Innovative technologies were eliminated primarily because they were not considered [suitable
        for the types of waste present at the site. No innovative technologies were eliminateid because
        of cleanup goals.  The standard technology selected could meet cleanup goals at the site.
                                                                        •     '   •       \        ..*••••  =r
14.     Were treatability studies conducted on the  innovative technology or standard technolpgy? ,

        No treatability studies were conducted.                                       '.  •  j    -
15.     What measures/criteria were used to compare alternatives?                        '

        The following measures were used to compare the alternatives;                     \

               Cost effectiveness                                                       I
               Waste left in place/institutional control                                    !
               Time to design                                                          I

                       -         '                  -•                              -.   -  | .   '     •
                                                                                       i .
16.     How are alternatives compared? .                                               \   ,   '
                                                                         "              i
        Cost effectiveness was determined by comparing the level of protectiveness achievedj with total     —^_
        cost. RAA-4 was eliminated because the addition of chemical fixation prior to off-silte             ^Of   }
        disposal would increase costs  but not increase protectiveness.  Alternatives that left Waste on
        site, such as fixation and capping, were considered to be less permanent than alternatives that
        removed or treated wastes.  Alternatives that required treatability studies, such as thermal
        desorption,  increased the time needed to design the remedy and decreased their shortj-term                  \
        effectiveness.                .                                          ..•'•'.          ••'• -
                                                                                       i            "  •        rr- •
                                                                                       i                      :','
                                                                                    '   I  '       •     ..'•'•
77.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the  selection of the remedy?
                                                                                       i  ' •
        The only technical characteristic that affected technology selection was that the high  moisture
        content of the contaminated soil/sediment resulted in the elimination of in situ vitrifie'ation as a
        potential remedial technology.  Technical considerations were not, primary in the selection of a
        remedial alternative  at this site.         ,                                          i
                                                                                       r
 142
                                               -5-

-------
                                  Garden State Cleaners
                         (same FS and ROD as South Jersey Clothing)

                                    Minotola, New Jersey
                                          Region 2
 GENERAL SITE INFORMATION
 1.
What were the principal contaminants,
contaminant levels, and media being
addressed in this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil (rag/kg)

       Tetrachloroethylene (PCE)
       Trichloroethylehe (TCE)
                            1.300
                            6.1
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                                                          Bad
EPA Fund-lead
PRPs: Garden State
       Clothing Company
FS prepared by: Ebasco
       Incorporated
2.      What volume of material is .to be
        remediated?

•        The volume of material to be remediated
        included:

        •     200 cubic yards of soil
3.     What type of site is this?

       Dry Cleaning.  An active dry cleaning facility.


TECHNOLOGY SELECTION -

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screenu g of technically feasible
       technologies were:
       Access restriction:
       Containment:
       Chemical treatment:
       Thermal treatment:
       Disposal:  •
                     Fencing, deed and zoning restrictions
                     Soil cap, multimedia cap, asphalt cap, concrete cap
                     Ex situ or in situ fixation
                     Incineration
                     Excavation, disposal at a RCRA facility, backfill treated soil
                                            -1-
                     .. 1988
                     3/89
                     8/12/91
                     9/26/91
                  ground
                                                              Cleaners, South Jersey
                                                                   ly
                                                                   Services
                                                                                              143

-------
        Was an innovative technology considered in the FS?  If so, which technology?       '

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                                     ;

        Biological treatment:   In situ bioremediation                                    ]
        Phys/Chem treatment:  Soil washing, soil flushing, in situ soil vapor extraction      |
        Thermal treatment:     Pyrolysis, low temperature thermal desorption, wet oxidation,
                             vitrification
6,      What was the cost estimate for the innovative technology?                         i

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs ^ere
        formulated, costs were estimated during evaluation by the nine criteria established by ithe NCP.
        The estimated costs were recalculated in the ROD.                                •'!
                                                         •                            i
                Cost Estimates for RAAs That Include Innovative Technologies        ,
                            (selected remedial alternative is in bold)                   ;
Alternative
RAA-SC-2
RAA-SC-3
RAA-SC-4
Innovative Technology
In situ soil vapor extraction
Excavation, low temperature thermal
desorption, backfill treated soil
Soil flushing
Estimated Costs
9 Criteria
$191,000
$220,000
$73,000
ROD
$649,000
$1,198,000
i
i • . •
$167,000
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-SC-1
RAA-SC-5
Standard Technology
No action
Excavation, off-site disposal, backfill with
borrowed material
Estimated Costs
9 Criteria
$0
$850,000
ROD
$l,7bo,000
$5,890,000
5.      If a standard technology was chosen, why?

       A standard technology was not selected.
   144
                                             -2-

-------
9.      If an innovative technology was chosen, why?

        All RAAs, except RAA-SC-1-'(No Action), would protect human health and the environment
        and attain ARARS.  The selected alternative, RAA-SC-2 (SVE for soils), was selected because
        it permanently reduces the level of contaminants in soil through treatment, is readily
        implementable, and creates no short-term risks. RAA-SC-3 (thermal desorption) was
        comparable to the selected alternative for most criteria, but would be more costly, create short-
        term risks by excavation,  require  significant soil preparation, and require numerous approvals
        to construct and operate the mobile thermal unit.  RAA-SC-4 (soil flushing) was eliminated
        because it would temporarily increase mobility of contaminants, increasing short-term risk, and
        was less implementable because of potential monitoring problems. Alternative RAA-SC-5
        (off-site landfill) offered maximum protection  of human health but had the greatest short-term
        risk to the community, short-term environmental impact, and cost.  ,|        '


 10.     If an innovative technology was not chosen, why not? At what stage'was the innovative
    '.   technology eliminated?                               •           !

       ; Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening;  during the screening of the ^three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.       .             ,

        Innovative technologies eliminated during the  initial  screening include:

        •      In situ bioremediation was eliminated because the technology  is difficult to control.
                Nutrients and oxygen must be distributed to  an area where contaminants are not
             '   uniformly distributed.  There was also concern that residual dontaminant levels would
                not be low enough to meet ARARs.  Further, when TCE and|PCE biodegrade, vinyl
                chloride (another toxicant) is produced.                    \
        "      Soil washing was eliminated because it would be difficult to implement and because  it
       '         generates relatively large quantities of waste that must be treated or disposed  of.         "
        •      Pyrolysis was eliminated because it has not been used in commercial applications,
                considerable waste stream pre-processing is required, and it is best applied to highly
                toxic organics.                                          I     •
        •      Vitrification was  eliminated because it is usually used for less mobile inorganic or
                mixed wastes.      '   •  -    '         -            .      |    .
        •      Wet oxidation was eliminated because it is not applicable to inon-pumpable soil.    ,     '

        No innovative technologies were eliminated during the three-criteria screening process.
           " . '                                                          '',''"'.-''
        Innovative technologies eliminated during the detailed  analysis include:        ,
                                                                     . • i     „       ,           .         •'
        »      Low temperature thermal desorption was eliminated because;it v/as not cost effective.
                It was considerably more expensive than the selected technology without providing
                additional protection to human health and the environment. !In addition, it would
;                create short-term risks by excavation, require significant soil (preparation, and require
                numerous approvals to construct and operate the mobile thermal unit.
         •      Soil flushing was eliminated because it would increase contaminant mobility, causing          .
                VOCs to be released into the aquifer  and necessitating additional remedial action. In
                addition, it was considered less implementable because of potential monitoring
                problems.

-   -••    '    '           ;    -        •   '••-••'      •       .      ''  !-'  •'•'-.   "   :  -  •'••'  145
                                     •   .   -    -3-     ,.'.•'.       .    •       •       - '     '

-------
   11.
  Which of the nine criteria were weighted most highly in selecting the technology? Did one of
  the nine criteria eliminate the innovate technology from being chosen?  If so, whic*h one?
  Which of the criteria supported the use of a standard technology?  ,            -   ;

  For the alternatives that were protective of human health and the environment and attained
  ARARs, the most heavily weighted criteria were long-term effectiveness, short-term •
  effectiveness, and cost effectiveness.
   72.
  13.
  14.
               8°al,SWere selected? Vthe cleanuP goal was based on an ARAR, what was that
           What risk level was selected to establish cleanup goals?                 i

  In the absence of any existing chemical-specific ARARs for soil, the New Jersey Department
  of Environmental Protection (NJDEP)  established Interim Soil Action Levels for VOCs in
  soil.  EPA regards this action level as a "to-be-considered" requirement. As such it can be
  used in determining the necessary level of cleanup for the protection of human health' and the
  environment.                                                                  !
                       Contaminant
                                  Cleanup Level (ppm)    ARAR or Other Basis
                   Carcinogens
                   ICE
                   PCE
                                                                          NJDEP
                                                                          NJDEP
 For carcinogens an excess upper bound individual lifetime cancer risk of between 10^ to lO'6
 was acceptable. For non-carcinogens a Hazard Index less than or equal to 1.0 was acceptable.


 Was the innovative technology eliminated because of the cleanup goals? If a standard
 technology was chosen, could it meet the cleanup goals?                           i

 In situ bioremediation was eliminated because of concerns that it may not be able to riieet
 established cleanup levels. A standard technology was not selected for soils at this site.

                                          '   '     '  :                          I    •
 Were treatability studies conducted on the innovative technology or standard technology?
                                                                      . ' •       -I
 No treatability studies were performed at this site, although a treatability study performed at
 the Nascohte Corporation, a site with  similar soil conditions, was used to develop the
 preliminary design system.                                                •      :
 75.
146
What measures/criteria were used to compare alternatives?

The following measures were used to compare the alternatives:

       Risk level achieved
       Impact on nearby populations
       Total cost       .                     .

                                      -4-

-------
16.    How are alternatives compared?
17.
       While all of the action alternatives would ultimately protect human
       environment, soil flushing would temporarily increase the level of risk
       from the soil would be flushed into groundwater.  Off-site disposal
       thermal desorption would impact nearby populations because excavation
       contaminated soils could potentially result in the generation of dust
       remedy, soil vapor extraction, would be less costly than off-site dispoi
       desorption. Although soil vapor extraction would be more costly thari
       preferred because it would not mobilize contaminants and cause them
       groundwater.
                                                               health and the
                                                                  because contaminants
                                                                  I low temperature
                                                                    aind transport of
                                                                  d vapors. The selected
                                                                  al iind thermal
                                                                  soil flushing, it was
                                                                  to enter the
What technical considerations were factors in selecting a remedy?
considerations primary in the selection of the remedy?.
                                                                       Were technical
        Soils at the site are mostly sandy, depth to the water table is about 25
        topography is flat with little or no surface runoff.  The granular naturi
        low moisture content in the vadose zone, and organic nature of the
        particularly amenable to the application of soil vapor extraction.  Also
        a mixed residential and commercial area; therefore, the impact on
        significant consideration. Technical considerations could be considered
        selection of remedy at  this site.
                                                                  feet, and^the surface
                                                                  of the soil, relatively
                                                               contaminants were
                                                                 >, the facility is located in
                                                                     populations was a
                                                                   primary in the
nearby
                                                -5-
                                                                                                    147

-------
                       General Motors (Central Foundry Division)
                                            QU-1
                                i- .          .          •       i
                                      Massena, New York
                                           Region 2
 GENERAL SITE INFORMATION
 1.
   What were the principal contaminants,
   contaminant levels, and media addressed in
   this feasibility study?

   Maximum concentrations of principal
   contaminants were:
        Soil/Sludge (rag/kg)

        PCBs
        Phenols
                       31,000
                       5,000
        Sediments (mg/kg)

        PCBs          '       5,700
                                                                  Site History
                                                     NPL Proposed;
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                     N/A
                     9/83
                     11/21/89
                     12/17/90
             Background

PRPJead
PRPs:  General Motors
FS prepared by: RMT, Inc.
2.      What volume of material is to be remediated?

        The volume of material to be remediated.included:

        •     253,000 cubic yards of PCB-containing materials (soil, sludge, and sediment)


3.      What type of site is this?                                         •-     / -      '

       Fabricated Metal Products. An active aluminum casting plant.


TECHNOLOGY SELECTION                            '

4.     What standard technologies were considered for selection in this FS?
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

                            Capping (concrete, asphalt, in situ soil admixtures, sprayed on, soil,
                            synthetic membrane, composite cover)
                            Chemical So1idifir.atinn/fiY5it!«r>                            ;
, Containment:
 148
                      synthetic membrane, composite
 Chemical treatment:   Chemical solidification/fixation
 Physical treatment:    Physical separation                    "
 Thermal treatment:    Incineration (rotary kiln, circulating bed, infrared)
 DlsP°sal:             Excavation and disposal off site, construction of facility on site
                                            -1-

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                       :

       Biological treatment:   In situ biodegradation, ex situ bipdegradation
       Chemical treatment:   Dehalogenation, chemical extraction         1
       Thermal treatment:    Thermal extraction                        ;
        What was the cost estimate for the innovative technology?      •",;"'
                               /,             t  *    ,               i • • - .            •   -     t
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation., The
        estimated costs then are recalculated during an evaluation based on niine criteria established by
        the NCP: long-term effectiveness and permanence;  short-term effectiveness; compliance with
        ARARs; protectiveness of humam health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.
                 Cost Estimates for FLA As That Include Innovative Technologies
                            (selected remedial alternative is in bold)    j
Alternative
RAA-6A
RAA-6B
RAA-6C
RAA-6E
RAA-7A
RAA-7B
RAA-7C
RAA-7E
RAA-8A
RAA-8B
innovative Technology
Solids excavation/biodegradation
Solids excavation/dehalogenation
Solids excavation/chemical extraction
Solids excavation/thermal extraction
Sediment dredging/biodegradation
Sediment dredging/dehalogenation
Sediment dredging/chemical extraction
Sediment dredging/thermal extraction
Soil/in situ biodegradation
Sediment/in situ dechlorination
Estimated Costs
3 Criteria
$102,000,000
$295,000,000
$210,000,000
$296,000,000
$7,100,000
.$15,000,000
$12,000,000 *'
$15,000,000
. N/A
$360,000
9 Criteria
$102,000,000
$295,000,000
$210,000,000
$296,000,000
$7,100,000
$15,000,000
$11,700,009
$15,000,000
eliminated
$360,000
                                               -2-
                                                                                               149

-------
    7.
How did the cost(s) compare to standard technologies?

          Cost Estimate- ?or RAAs That Include Standard Technologies
                    (selected remedial alternative is in bold)
             Alternative
            RAA-1
            RAA-2A
            RAA-2B
            RAA-3A
            RAA-3B
            RAA-4
            RAA-5
            RAA-6D
            RAA-6F
            RAA-7D
           RAA-7F
           RAA-9A
           RAA-9B
           RAA-10A
           RAA-1 OB
           RAA-11
                       Standard Technology
               No action
               In situ containment with soil cover
               In situ containment with composite
               cover
               In situ containment of river sediment
               with graded filter         •;
               In situ containment of river sediment
               with graded filter and sheet pile
               Ground water recovery and treatment
               Ground water containment
               Solids excavation/thermal destruction
               Solids excavation/solidification
               Sediment dredging/thermal destruction
              Sediment dredging/solidification
              Solid excavation/off-site landfill
              Solid excavation/off-site incineration
              Sediment dredging/off-site landfill
              Sediment dredging/off-site incineration
              On-site disposal
                                                                        Estimated Costs
                                                                   3 Criteria
                                                                   $1,300,000
                                                                   $6,200,000
                                                                  $10,000,000
                                                                   $3,600,000
                                                                   $4,500,000
                                                                  $3,900,000
                                                                  $7,600,000
                                                                 $339,000,000
                                                                 $146,000,000
                                                                  $17,000,000
                                                                  $9,000,000
                                                                 $322,000,000
                                                                $2,680,000,000
                                                                 $15,000,000
                                                                 $112,000,000
                                                                 $46,000,000'
                                                                        $1,260,000
                                                                        $6,200,000
 $12,700,000
 $3,610,000
  eliminated
 $3,870,000
                                                                       $7,600,000
$339,000,000
                                                                      $146,000,000
$17,000,000
 $8,900,000
                                                                       eliminated
 eliminated
 eliminated
$45,560,000
  8.     If a standard technology was chosen, why?

         A standard technology was not chosen^
  9.      !f an innovative technology was chosen, why?                                    \

         Excavation of sludge, soil and sediment, dewatering, and treatment by ex situ bioremediation
         another equivalent treatment or incineration based on treatability test results. This remedy was
         selected because: 1) it offers a permanent  solution utilizing an innovative technology  i) New
         York States preference for permanent remedies is met, 3) Mohawk Tribes primary concern for
         expeditious cleanup that supports removal of contamination from the Reservation and control
150
                                              -3-

-------
                                                                           I      .   - ,  .
       of further migration of contaminants from the GM site onto the Reservation, 4) reduces PCB
       toxicity and volume as opposed to addressing only mobility, 5) cost of biprernediation
       compared to other treatment, 6) available commercially.                |


JO.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                              \

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      No innovative technologies were eliminated in the initial screening.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                       ,   i

        •     In situ biodegradation was eliminated because no in situ PCB bipremediation projects
               are completed on a scale comparable to that'required at this site;! there are large
               volume of soil containing PCB at depth up to 30 feet and the  water table is below
               waste in many areas making it difficult to establish hydraulic control of the process;
               heterogeneity of waste and soil may make it more difficult to  achieve a high level of
               treatment effectiveness.                                      !

        Innovative technologies eliminated during the detailed analysis include the following:

        •      Dehalogenation, chemical extraction, and thermal extraction we're not selected as the
       '         treatment alternative of choice because they would cost more  than biodegradation.
                However, they have not been eliminated entirely.  Treatability sifudies will be used to
                determine if biodegradation is effective. If biodegradation is proved to be ineffective,
                other innovative technologies will be tested for implementation, i


 77.     Which of the nine criteria were weighted most heavily in selection of the technology? Did
        failure to meet one of the nine criteria result in the elimination of the innovative technology?
         If so,  which criterion?  Which of the criteria supported the use of a standard technology?

         The most  important factors in determining a remediation alternative were reducing contaminant
         levels with a cost-effective, long-term, and permanent solution and state acceptance.  A
         treatment  technology was preferred over containment, and biodegradation was the least
         expensive treatment technology available.                            j
                                                 -4-
                                                                                                     151

-------
72.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?                 \
                                                        -.'...    |      •'
Soil/Sludge                                              ',                  I
       Sediment
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens !
PCBS—St. Regis
Mohawk Indian
Reservation
PCBs — GM facility
Phenol
1
10
50
EPA PCB Guidance ;
and St. Regis Mohawk
regulations :
EPA PCB Guidance ;
and EPA Risk
Assessment
RCRA !
nt
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
PCBs — St. Lawrence
and Raquette Rivers
PCBs — Turtle Creek
1
0.1
i
Federal and NY 1
Interim Sediment i
Quality Criteria i
St. Regis Mohawk !
regulations3 i
               Turtle Creek is located on St. Resgis Mohawk Indian Reservation. This cleanup level
               is based on St. Regis Mohawk regulations.                              i

        The EPA risk assessment determined that 10 ppm PCB in soil at the GM facility wais
        protective of the Mohawk population.  EPA also determined that cleanup goals for St.
        Lawrence and Raquette River sediments corresponded to a 4 x 10"5 excess cancer risk.
                                                                                   i
                                                                                   i    ..  .  •
        For carcinogens, an excess upper bound individual lifetime cancer risk of between lO"4 to  10"6
        was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                                           j
                                                                    . -  .            i     ,
        Innovative technologies eliminated because of cleanup goals include:              :

        •      None                             •     •-•           '                 i
152
                                              -5-

-------
        Standard technologies eliminated because of cleanup goals include:   !            N

        •..    'None'  .           -        '              ..•'•".        .   'I''.'     .       ,      -

                 '•                          .                "              'r " '

14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.  Treatability studies will be conducted, however, prior
        to implementation of biodegradation.  If biodegradation is not effective, treatability studies will
        be  conducted on.other innovative treatment technologies.  •     '     •>
                                                                         'I

75.     What measures/criteria were used to compare alternatives?          }

        The following measures were used to compare the alternatives:       !

        -       Cost-effectiveness                                          i    ,
        -       Preference for treatment (vs. containment)                   I


16.     How are measures compared?                                      i

        The chosen alternative utilizes an innovative treatment  technology (biodegradation) to
        remediate site contaminants.  Source treatment was preferred  over containment because it
        reduces PCB toxieity and volume and not just mobility and therefore provides a permanent
        and long-term solution. This solution was considered cost-effective even though it is more.
        expensive than other alternatives because it provides increased protection.  The effectiveness of
        biodegradation will need to be tested prior to implementation. If biodegradation proves to be
        ineffective, other treatment technologies will be tested.  Incineration will be used only if all
        other treatment options fail treatability testing. The use of incineration 'was avoided because
        the public viewed it as the  least preferred  treatment technology.   '   \
                                                                        , i • •

17.     What technical considerations were factors in  selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                \

        While EPA plans to address all site contaminants during the cleanup, PCBs drove the remedy
        selection process. Moreover, because PCBs are persistent in the environment, there was a
        significant emphasis on reducing their toxieity and volume through treatment, as opposed to
        reducing their mobility through containment.  This consideration was primary in selecting a
        remedy.                    •                 .".                    <            "••-..
                                                                         i                      153
                                              -6-                '        !•       •  :   •   •

-------
                      General Motors (Central Foundry Division)
                                           OU-2

                                     Massena, New York
                                          Region 2
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal .
        contaminants were:
                                i

        Soil/Sludge/Debris (mg/kg)
 2.
        PCBs
        Phenol
                     41,000
                     11,000
                                                          Site History
                                             NPL Proposed:
                                             NPL Final:
                                             FS:
                                             ROD:
                     N/A
                     9/83
                     11/21/89
                     3/31/92
What volume of material is to be
remediated?

The volume of material to be remediated'
included:
               598,000 cubic yards of soil, sludge, and debris
             Background

PRP-lead
PRPs: General Motors
FS prepared by: RMT, Inc.
 3.      What type of site is this?                      .                                j

        An active manufacturing facility with several waste areas. This ROD addresses the East
        Disposal Area and the Industrial Landfill on the site.  Land use in the surrounding are!a
        consists of mixed residential and industrial uses.                                  i
 TECHNOLOGY SELECTION                                                   .     ;
                              • •     .                               •                 i    .   '
 4.      What standard technologies were considered for selection in this FS?               j
                                                         '             -    •  "      I
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                            i
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
154
                     Fencing, security
                     Cap (soil cover, composite cover), grading drainage control
                     Solidification
                     Incineration
                     Excavation, off-site/on-site disposal
                                             -1-

-------
             Was an innovative technology considered intheFS?  If so, -which technology?
                           :                 -         '-                   . '    \
             For this site innovative technologies were considered in the ROD.     !
                                                                          '  ' 'i          •
             Biological treatment:   Biological treatment                        >       "
             Chemical treatment:    Chemical dechlorination (KPEG), chemical extraction (BEST)
             Thermal treatment:     Thermal extraction (Taciuk process)          ]
o
             What was the cost estimate/or the innovative technology?           ;  •
                                                                1             r       '           ' .
             During the initial screening process, in which technically feasible technologies are identified
             (prior to the formulation of RAAs), the FS does not quantify costs. Ajfter the RAAs have been
             formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
             implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
             estimated costs are then recalculated during an evaluation based on ninie criteria established by
             the NCP.  The RAAs were changed in the ROD and therefore are presented separately.
                                                                             i    '        '
                      Cost Estimates for RAAs That Include Innovative Technologies             '
                                 (selected remedial alternative is in bold)     :

             Soil/Sludge/Sediment
Alternative
RAA-6a
RAA-6b
RAA-6c ^
RAA-6e
RAA-7a
RAA-7b
RAA-7c
RAA-7e
RAA-8a
i
Innovative Technology
Solids excavation and biological
treatment (Envirogen, Inc.)
Solids excavation and chemical
dechlorination (KPEG)
Solids' excavation and chemical
extraction (Basic Extraction Sludge
Treatment, BEST)
Solids exqavation and thermal
extraction (Taciuk process)
Sediment dredging and biological
treatment (Envirogen, Inc.)
Sediment dredging and chemical
dechlorination (KPEG)
Sediment dredging and chemical
extraction (BEST)
Sediment dredging and thermal
extraction (Taciuk process)
In situ biological treatment (land-based
materials)
Estimated Costs
3 Criteria
$102,000,000
$295,000,000
$210,OQ[),000
$296,000,000
• • i
$7,ioo;oocr
$15,00(1,000
$12,000,000
$15,000,000
i
N/A
|
9 Criteria
$102,000,000'
$295,000,000
$210,000,000
.$296,000,000
$7,100,000
$15,000,000
$12,000,000
$15,000,000
eliminated
                                                    -2-
                                                                                                      155

-------
Alternative
RAA-8b
Innovative Technology
In situ biological treatment (river
sediments)
Estimated Costs
3 Criteria
$360,000 ,
9C
$3i
riteria
>0,000
           East Disposal Area
Alternative
RAA-E3
RAA-E4
Innovative Technology
Excavation/on-site treatment (biological
treatment, dechlorination, chemical
extraction, thermal extraction)*
Mixed treatment (biological treat-
ment, dechlorination, chemical
extraction, thermal extraction)*/
containment
Estimated Costs
ROD
$34,000,000
to
$37,000,000 ;
$24,000,000
to . '
$38,000,000
           "This RAA includes treating contaminated materials with one or more of the following
           technologies: solidification, incineration, biological treatment, dechlorination, chemic'al
           extraction, thermal extraction.                                                 Y

           Industrial Landfill                               ,                             :
              Alternative
            RAA-L3
        Innovative Technology
Excavation/on-site treatment (biological
treatment, dechlorination, chemical
extraction, thermal extraction)* of
contaminated materials in landfill
                                                                      Estimated Costs
                                                                           ROD
 $61,000,000
     to
$203,000,000
          'This RAA includes treating contaminated materials with one or more of the following
          technologies: solidification, incineration, biological treatment, dechlorination, chemickl
          extraction, thermal extraction.                                                   •
156
                                                 -3-

-------
7.     How did the cost(s) compare to standard technologies?
                Cost Estimates for RAAs That Include Standard Technologies
                         (selected remedial alternative is in bold)
Alternative
RAA-1
,RAA-2a
RAA-2b
RAA-3a
RAA-3b
RAA-4
RAA-5
RAA-6d
RAA-6f
RAA-7d
RAA-7f
RAA-9a
RAA-9b
RAA-lOa ,
RAA-lOb
RAA-1 1

Standard Technology
No action
In situ containment (soil cover) of
solids
In situ containment (composite cover)
of solids
In situ containment of river sediments
(graded filter)
In situ containment of river sediments
(graded filter and sheet pile wall)
Ground water recovery and treatment
Ground water containment
Solids excavation and incineration
Solids excavation and solidification/
chemical fixation
Sediment dredging and incineration
Sediment dredging and solidification/
chemical fixation
Solids excavation and off-site
management (secure chemical landfill)
Solids excavation and off-site
management (thermal destruction
facility)
Sediment dredging and off-site
management (secure chemical landfill)
Sediment dredging and off-site
management (thermal treatment
facility)
On-site disposal
Estimated Costs
3 Criteria
$1,300,000
$6,200,GOO
$io,ooo,poo
$3,600,000,
$4,500,000 ,
$3;900,000
$7,600,000
$339,000,000
$146,000,000
$17,000,!000
$9,000,1300
$322,000,000
$2,680,000,000
$15,000,000
$112,000,000
I
$46,000,000
9 Criteria
$1,300,000
$6,200,000
" $12,700,000
.$3,600,000
eliminated
$3,900,000
$7,600,000
$339,000,000
$146,000,000
$17,000,000
$9,000,000
eliminated
eliminated
eliminated
eliminated
$46,000,000
                                           -4-
                                                                                       157

-------
           East Disposal Area
Alternative
RAA-E1
RAA-E2
RAA-E3
RAA-E4
RAA-E5
======
Standard Technology
No action
Capping/ground water containment
Excavatibn/on-site treatment
(incineration, solidification)*
Mixed treatment (incineration,
solidification)*/containment
Excavation/on-site disposal
' 	
Estimated Costs
ROD
$2,000,000
, $9,000,000
to
$11,000,000
$34,000,000
to
$37,000,000
$24,000,000
to
$38,000,000
$27,000,000
          'This RAA includes treating contaminated materials with one or a combination of the I
          following technologies: solidification, incineration, biological treatment, dechlorinatiori
          chemical extraction, thermal extraction.                                          ''

          Industrial Landfill
             Alternative
         Standard Technology
                                                                     Estimated Costs
                                                                          ROD
           RAA-L1
No action
                                                                       $2,000,000
           RAA-L2
Capping/ground water containment
                                                                       $9,000,000
                                                                           to
                                                                      $11,000,000
           RAA-L3
Excavation/on-site treatment
(incineration, solidification)* of
contaminated materials in landfill
                                                                      $61,000,000
                                                                           to
                                                                      $203,000,000
           RAA-L4
Excavation/on-site disposal
         This RAA includes treating contaminated materials with one or a combination of the !
         following technologies: solidification, incineration, biological treatment, dechlorination !
         chemical extraction, thermal extraction.                                          '[
15S
                                              -5-
                                                                                                            rL7

-------
8.     If a standard technology was chosen, why?                        ;

       East Disposal Area                                                              ,

       Under the selected alternative (RAA-E4 and RAA-L2), non-oily soil >yith PCB concentrations
       above  10 ppm and below 500 ppm in the East Disposal Area (approximately 115,000 cubic
       yards) will be consolidated,  regraded, and contained using a composite cover (RAA-E4).  A
       containment technology was selected because it can be implemented quickly with moderate
       amounts of dust and,therefore has a good deal of short-term effectiveness.

       Industrial Landfill
                         j                           '                   i,          •    -  ,
       Under the selected alternatives (RAA-E4 and RAA-L2), the estimated! 424,000 cubic yards of
       contaminated material in the Industrial Landfill will be contained with! a composite cover
       (RAA-L2).  Hotspots containing greater than SOO.ppm of PCBs which] are exposed during
       landfill regradmg will be treated in the  same manner described below ;for East Disposal Area
       contaminants.  A containment technology was selected because it can jbe implemented  quickly
       with moderate amounts of dust and therefore has a good deal of shortrtenn effectiveness.
       RAA-L2 involves less materials handling than alternatives which include excavation and
       treatment of wastes, and is therefore most easily implemented.       !
9.      If an innovative technology was chosen, why?

       East Disposal Area                                             ;

       Under the selected alternative (RAA-E4 and RAA-L2) non-oily soil with PCB concentrations
       above  500 ppm, all sludge, and all visibly oily soil (an estimated 59,000 cubic yards of
       material) will be excavated and treated to destroy PCBs permanently (RAA-E4). Biological
       treatment or an innovative treatment technology will be used wherever EPA determines it to be
       viable  and implementable.  In order to determine the effectiveness of innovative biological
       treatment at the General Motors site treatability studies will be performed.  At the conclusion
       of these studies, EPA will evaluate the effectiveness of biological treatment. Biological
       treatment of soil must result in PCB concentrations less than 10 ppm for the treatment to be
       considered successful.  If any material cannot be treated to meet the treatment residual level
       using biological treatment alone, incineration or one of the other innoyative technologies tested
       during design which has been demonstrated to achieve site treatment goals will be used.
       Preliminary bench-scale tests of site soil by General Motors have demonstrated up to 82
       percent reduction of PCBs, from 291  ppm to 52 ppm, after several months of anaerobic and
       aerobic biological treatment. In addition, there are indications of successful large-scale
       implementation at the French limited site.  Biological treatment is most efficient at reducing
       toxicity, mobility, and volume of contaminants.  New York State has expressed a preference
       for permanent remedies, which include the excavation and permanent treatment of the majority
       of the  PCB mass at the site. The Mohawk Tribe also supports the permanent treatment of all
       contaminated material at the site. The Tribe viewed all containment remedies as interim
       measures only.  Although there are short-term impacts associated whh biological treatment,
       these can be mitigated and will not pose an unacceptable risk to  the.surrounding community,
       General Motors workers, or remediation workers.  In addition, biological treatment is the least
     ,  costly  of all  treatment alternatives evaluated.                       !
                                              -6-
159

-------
   10.    If an innovative technology was not chosen, why not? At what stage was the innovative            	
          technology eliminated?                                                                        ^^ "\
                                                            '  ".  '     '              •        !           '  .     •--*
          In the ROD, biological treatment was selected as the first choice to treat contaminated soil and
          sludge.  If biological treatment does not prove effective, a different innovative technology
          (chemical dechlorination, chemical extraction, or thermal extraction) might be implemented at
          the site.                             .                                            !
                                                      :                  ' •                 i        .
          Innovative technologies could be eliminated from the remedial technology selection process at
          three stages: during the initial screening; during the screening of the three criteria of i
          effectiveness, implementability, and cost;  or during the detailed evaluation.           '<
                                                               •                            !  .        ' '          -
          Innovative technologies eliminated during the initial screening include the following:  I

          •      None                              .  '                      .   .   .     .  :
                                                                                         •  !'• •      •   '
                                                                                           t        .
          Innovative technologies eliminated during the screening of the three criteria include the
          following:                                                                        I
                                               . .,        •                "                 1
                                                                        •    .               i            •    •
          •      None                                                                    ;     '
                                                                                           j       l      •  .  ,
          Innovative technologies eliminated during the detailed analysis include the following:  '
                                                         "  '       •''•  .                      i
          *      Chemical dechlorination (KPEG) was eliminated but no specific reason was given.
                  The FS states that the reliability of this process has not been fully  documented.  The
                  principal uncertainties are the ability to construct processing equipment with a I
                  throughput adequate to manage the large volumes  of material at this site, and'the
                  treatment effectiveness on  site-specific materials.  The KPEG process has been: shown
                  to be effective in the destruction of PCBs on a limited  scale. The  availability  of this
                  technology for application  at the scale required on this  site, within the timetable to be
                  established, is uncertain.                                                   [
          •      Chemical extraction (BEST) was eliminated but no specific reason  was given.  The FS
                  states that the effectiveness of chemical extraction  has been demonstrated on a limited
                  scale. The FS further states that the technical feasibility of the BEST process  has been
                  commercially demonstrated, and documented in the U.S. EPA's SITE (Superfund
                  Innovative Technology Evaluation) project summary report.  This technology results in
                  the production of a PCB-rich extract which requires further treatment.         ' •
          •       Thermal extraction (Taciuk process) was eliminated but no specific reasonwas; given.
                  The FS states that to date there has been  no full-scale demonstration of the Taciuk
                  process on PCB materials.  The  reliability of this process has not been fully   ;
                  documented. The principal uncertainties  are the ability to construct processing ;  •
                  equipment with a throughput adequate to manage the large volumes of material at this
                  site, and the treatment effectiveness on site-specific materials. The availability of this
                  technology for application at the scale required on  this site, within the timetable to be
                  established, is uncertain.
160
                                                 -7-

-------
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       .which criterion? Which of the criteria supported the use of a standard technology?

       Soil/Sludge/Debris                                              |

       Overall protection of human health and the environment and long-term effectiveness and
       permanence were weighted most heavily hi selecting the chosen alternative. The selected
       alternative protects human health and the environment through the peiinanent treatment of the
       principal threat material in the East Disposal Area and through containment of less
       contaminated material. The  selected alternative reduces excess carcinogenic health risks to
       humans to levels within the acceptable EPA range of 10"4 to W6.  The selected remedy
       includes  excavation and treatment of contaminated materials and is therefore more permanent
       and effective over the long-term than remedies which involve containment alone.


12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup  goals?     j
                     Contaminant
Cleanup Level (mg/kg)   ARAR. or Other Basis
                 Carcinogens
                 PCBs
          10
EPA PCB Guidance*
               'This cleanup level.is based, in part, on EPA's risk assessment for the alternatives
               considered for the site, which indicates that 10 ppm is protective of human health, and
               on EPA's August 1990 PGB guidance which recommends soil cleanup levels between
               10 ppm and 25 ppm in industrial areas.
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                               !           .
        i                              i                             '/'','-

        Innovative technologies eliminated because of cleanup goals include: j


        •     " None                                             .      i;      '   - •

        Standard technologies eliminated because of cleanup goals include:  < •
                                        !>                    •"!]',
        • '•- '   None    .                    '        •           ,"'••'•''.•
                                                                     "If-''       - \


 14.     Were  treatability studies conducted on the innovative technology or standard technology?


        Treatability studies were not conducted.                           '
                                                                                                181

-------
    75.
 What measures/criteria were used to compare,alternatives?

 The following n   sures were used to compare the alternatives:

       Cost-effectiveness
    16.     How are measures compared?                                                *' \
                                                               - =                   '    "   i      •
                           '                l                                               !
           The selected remedy is cost effective because it has been demonstrated to provide overall
           effectiveness proportional to its costs. The selected remedy selects an innovative technology1
           and, as a last resort, incineration.  This is cost effective since innovative technologies are    -
           generally less expensive than incineration. Mixed treatment/containment is cost effective since
           EPA estimates ,t will result in a significant reduction, on the order of 90 percent, in PCB mass
           in the East Disposal Area.  Treatment of all East Disposal Area material would cost  !
           substantially more while resulting in treatment of only the remaining 10 percent of the PCB
           mass in this  area.                                                -
   17.
162
What technical considerations were factors in selecting a remedy?  Were technical  1
considerations primary in the selection of the remedy?                             ;

Technical considerations were not primary in selecting a remedy for this site.        |
                                                -9-

-------
                                  Genzale Plating Co.
                                Franklin Square, New York
                                         Region 2
GENERAL SITE INFORMATION
2.
What were the principal contaminants,
contaminant levels, and media being
addressed in this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil(mg/kg)

Trichloroethene 53
Barium 36,400
Chromium 37,300
Nickel 58,000 '
•
,r- -
Site History
i • •
NPL Proposed: N/A
;NPL Final: '! 7/87
FS: 2/91
ROD:/ ; 3/29/91

Background

EPA Fund-lead
PRPs: Genzale Plating Company
FS prepared by: Ebasco Services
Incorporated
       remediated?

       The volume of material to be remediated included:                ;

       •     93 cubic yards of soil containing volatile organic contaminants
       •     2080 cubic yards of soil containing inorganic contaminants  i
3.     What type of site is this?

       Electroplating.


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically
       feasible technologies were:
        Access restriction:
        Containment:
                     Land-use restrictions, warning signs
                     Cap (clay, asphalt, synthetic membranes, chemical sealants,
                     multimedia)
Physical treatment:    Mechanical aeration
Chemical treatment:   Encapsulation, stabilization/solidification
                                            -1-
                                                                                               163

-------
          Thermal treatment:     Incineration
          Disposal:
Excavation, construction of on-site RCRA landfill, transport to off-
site RCRA landfill
                                                                                                              i
          Was an innovative technology considered in the FS?  If so, which technology? ^     j

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:
                                                                                        i
          Biological treatment:   Biodegradation
          Chemical treatment:    In situ soil flushing (solvent), in situ hydrolysis, alkali metal1
                                dechlorination, soil washing (solvent) and extraction, supercritical
                                fluid extraction                        '               _    '
          Thermal treatment:   ,  In situ vitrification, wet air oxidation, enhanced volatilization
          Physical treatment:     In situ vacuum extraction                                 I
  6.      What was the cost estimate for the innovative technology?

          During the initial screening process,  in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs1 have
          been formulated, costs are estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation.  The estimated costs then are recalculated during an evaluation based on the nine
          criteria established by the NCP.                                                  ;       "

                  Cost Estimates for RAAs  That Include Innovative Technologies
                             (selected remedial alternative is in bold)                   i
Alternative
RAA-SC-3
RAA-SC-4
RAA-SC-5
Innovative Technology
In situ vacuum extraction/in situ
stabilization/solidification/soil cover
In situ vacuum extraction/excavation/ off-
site treatment and disposal/fill with clean
off-site soil
In situ vacuum extraction/surface
excavation of leaching pits/off-site
treatment and disposal/fill with clean
off-site soil
Estimated Costs
3 Criteria
$1,963,200
^ $7,179,700
$1,971,400
9 Criteria
$2,439,300
$8,974,600
1 -
$2,449,500
/-• i
164
                                               -2-

-------
7.      How did the cost(s) compare to standard technologies?
                Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-SC-1
RAA-SC-2
Standard Technology
No action
Surface excavation/off-site treatment and ,
disposal/capping
Estimated Costs
3 Criteria
$530,800
$1,464,100
' 1 ' '
9 Criteria
$650,000
$1,815,400
8.     If a standard technology was chosen, why?                        /             ,

       Off-site disposal of residuals from soil vapor extraction was selected.'  See discussion below.
9.     If an innovative technology was chosen, why?                      ;

       In situ vacuum extraction for volatile organics followed by surface e)iccavation and off-site
       treatment and disposal of excavated material at a Subtitle C facility, was selected for the
       following reasons:  1) removing the source to stop further groundwater contamination, 2)
       would eliminate direct contact (site located in residential area), 3) liniited space on-site for
       other treatment methods,, 4) commercially available technology and disposal facilities
       (although limited), 4) easy to implement, 5) cost of removing "hot spots" versus entire site,
       6) soils are optimum for in situ SVE, 7) long term effectiveness.    ;
10.    If an innovative technology was not chosen, why? At what stage was\the innovative
       technology eliminated?                                          >

       Innovative technologies could be  eliminated from the remedial technology selection process
       at three stages:  during the initial screening; during the screening of liie fihree criteria of
       effectivenesSi implementability, and. cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      Wet air oxidation was eliminated because it is primarily used! for pretreating complex
               organics for subsequent biological treatment. This technology is suitable for treating
               pumpable aqueous and sludge wastes and is not recommended for treating large
               volumes of dry contaminated materials.  Soil would have to Ibe slurried. This
               technology would require a large area for on-site treatment that is not available at the
                      .                                                        .
               Enhanced volatilization was eliminated because it is not effective for treatment of
               metals and space limitation would not permit on-site treatment.
               Alkali metal dechlorination was eliminated because APEG is used for the treatment
               of chlorinated compounds, primarily PCBs and the contaminants of concern are not
               PCBs but VOCs and metals.  Demonstration of APEG has nbt been effective in

                  '  ,'•               •          -3-   .     -             '  ::
165

-------
                  treating other organics such as VOCs. Also this technology would require a large        	
                  area for on-site treatment which is not available at the site.                              ^^F  \
          "      Soil washing and extraction was eliminated because 1) large volumes of                        -
                  contaminated waste water and/or spent extraction solution would be generated, which
                  would require further treatment, 2) The variety of metals would require a number of
                  solvents and acids with multiple washing and extraction steps, 3) would require a
                  large area for on-site treatment, which is not available at the site.
          •      Supercritical fluid extraction was eliminated because 1) it is not applicable for
                  removal of metals,  2) it is available from only one vendor and availability of
                  equipment would therefore be limited, 3) it requires  a higher capital cost and
                  involves more complex equipment than other technologies, 4) space constraints on-
                  site make this technology impossible to implement.
          •      Biodegradation  was eliminated because:   1) it is a developmental technology for
                  hazardous waste cleanup, which requires extensive bench and pilot scale testing to
                  verify its  effectiveness, 2) aerobic bioremediation is not demonstrated as effective in
                  remediating VOCs present at the site, 3) it would require long-term operation,. 4)
                  elevated levels of metals may have adverse effects on microorganisms, 5)
                  volatilization of VOCs may occur while mixing and  aerating soil.           1
          •      In situ soil flushing was eliminated because 1) it requires installation of vertical
                 groundwater barriers which requires reliance on an underlying nonpermeable j layer,
                 not present at this site, to act as a horizontal barrier,  2) could potentially accelerate
                 the spread of contamination and force contamination into the lower  aquifer.
          •      In situ-vitrification was eliminated because 1) it is not effective for VOCs because
                 they migrate laterally during the vitrification process and may escape untreated, 2)
                 requires exorbitant amounts of electricity, 3) requires large amounts of equipment to
                 be located on-site for the duration of the operation, 4) site is an active facility located
                 in a residential area, and 5) it would disrupt existing  operations  and the residents in
                 the area.                                                                i
          •      In situ hydrolysis was eliminated because  1) it is in the early developmental  stages
                 and is generally  unproven at Superfund sites, 2) requires isolation of contaminated
                 areas (not  possible at this site) due to migration of hydrolysis chemicals and products
                 in groundwater and  making it difficult to capture all of the chemicals and products,
                 3) not applicable for removal  of VOCs and metals present at the site.        !     '
                                             .••''•                                   i  •
         Innovative technologies eliminated during the screening of the three criteria include the
         following:                                                                      |     .,
                                                      ••                          •        i    ••"
         •       None                                             .                      i
                                                                                         f
         Innovative technologies eliminated during the detailed analysis include the following:!

         •       None  '                                          •  •  -,                    j :
.                                                '                               -!._,,

  11.     Which of the nine  criteria were weighted most heavily in selecting the technology? Did
         failure to meet one of the nine criteria result in the elimination of the innovative technology?
         If so, which criterion? Which of the criteria supported the use of a standard technology?

         The most heavily weighted criterion was protectiveness of human health and the environment
         through long-term  and permanent reduction in the toxicity, mobility, and volume of site

186
                                               -4-                   .  --  •  .             '  v   -    •

-------
       contaminants.  Implementability was of major importance because of the small size of the
       site.  The deciding factor between two equally protective and effective alternatives was cost.

       Several of the innovative technologies were eliminated during the initial screening because
       they would not remediate the appropriate contaminants or because they were not
       implementable given the site's limited space.                       '
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was
       that ARAR?  What risk level was selected to establish cleanup goals?

       Cleanup goals are low enough so that any leachate generated from the soil would not cause
       ground water contaminant concentrations to exceed their corresponding cleanup levels
       (MCLs). These concentrations were estimated using a leaching model. Contaminants with no
       ground water ARARs would be remediated to background levels.
Contaminant
Cleanup Level (mg/kg)
ARAR or1 Other Basis
Carcinogens !
Trichloroethene
Chromium
0.0084 (FS),
1 (ROD)
6.67
Leaching Model
'i
1
Leaching Model
andMCL
" i
Noncarcinogens , . ,
Barium
Nickel
3,500
30
Bacikground
Bacikground
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?  ,      '                     \

       Innovative technologies eliminated because of cleanup goals include:

       •  ,   None '.-•''         '  '            !          .     ;|                 ,

       Standard technologies eliminated because of cleanup goals include: j

       •     Capping                                               •

                                                                  -  • ;j ' . s

14.    Were treatability studies conducted on the innovative technology or 'standard technology?
                                              ' '                      :!•'.-

       No treatability studies were conducted.                           •
                                             -5-
                                                                                              167

-------
  75.     What measures/criteria were used to compare alternatives?                     '
                                                               •     '     '   •'        "'      '
         The following measures were used to compare the alternatives:                  i
                  :  •                      •                         •     .             I'    -
                Cost-effectiveness                      ,                              (
                Preference for treatment (vs. containment)
                Impact on nearby populations                                          |

                                                                                     -i
  16.     How are measures compared?                                                i
                                                                                     i
         A source treatment technology was preferred over containment because it offers greater
         protection of human health and the environment, long-term effectiveness, and permanence.
         Treatment was proposed in three of the five alternatives.  The chosen alternative utilized an
         innovative treatment and it was chosen because it is the most cost-effective of the three
         treatment options. RAA-2 was eliminated because excavation could generate fugitive dust
         and vapors, potentially posing a health risk to nearby residents. .               .  j


  17.     What technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?
                                                                                     " I
         Protecting drinking water quality was the technical consideration in selecting a remedy. The
         site is located over the Upper Glacial aquifer (a nonpotable water source), which covers the
         Magothy aquifer, Loop Island's principle water supply. Without a confining layer, the two
         aquifers are connected hydraulically.                                           ;
                                                          •  '         ' .               i'
         The lack of a confining layer precludes the use of any technology that requires horizontal or
         vertical barriers.  Both in situ soil flushing and in situ hydrolysis were eliminated since they
         actually could enhance the migration of contaminants into the aquifer.
                                                                                     -'''
        The proximity of residential homes also was a consideration in choosing a remedy, One
        alternative (RAA-SC-2) was eliminated primarily because of the potential risk to residents
        from the generation of fugitive dust and organic vapors during excavation.         !
                                                      "'•--'                   ( -    I      ,
        These technical criteria were factors in the selection of a remedy but they were not primary.
168
                                              -6-

-------
                                Global Sanitary Landfill
                                          OU-1

                             Old Bridge Township, New Jersey
                                         Region 2
GENERAL SITE INFORMATION

/.      What were the principal contaminants,
       contaminant levels, and media .addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       No data were collected in the landfill.
2.     What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       •      2,400,000 cubic yards of waste
             SitelHistpry
                ;|
NPL Proposed:        N/A
NPL Final:      i     3/89   '
FS:             L  .2/91
ROD:         '       9/11/91

             Background

EPA Fund-lead   •   '
PRPs:  Not listed ;
FS prepared by:  Killam Associates
3.     What type of site is this?

       Municipal Landfill.  An inactive landfill.
                                                                    1-
TECHNOLOGY SELECTION                                         !

4.      What standard technologies were considered for selection in this FS?i

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:          .                                 .1                      ,

        Access restriction:     Security, fencing                         ;
        Containment:         Cap (vegetative cover, NJDEP solid waste, NJDEP hazardous waste,
                            RCRA, bentonite), slope stabilization       j
        Chemical, treatment:   Stabilization      ..              .        ;
        Physical treatment:    Leachate management       ,           .  •
        Disposal:            Excavation, off-site disposal               ;
                                                                                             169
                                             -i-

-------
   5.      Was an innovative technology considered in the FS? If so, which technology?
                                                • -   '                               : -    I  '
           Innovative technologies considered during the identification and screening of technically
           feasible technologies were:                                                     |
                                                                   .'"•-.    i-
           Biological treatment:  In situ bioreclamation             .                       |  ,
           Phys/Chem treatment:  In situ soil flushing
           Thermal treatment:    In situ vitrification                                       i
           What was the cost estimate for the innovative technology?

           During the initial screening process, in which technically feasible technologies are identified
           (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
           formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
           implementability, and cost) to  identify alternatives that merit a more detailed evaluation, The
           estimated costs then are recalculated during an evaluation  based on nine criteria established by
           the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
           ARARs; protectiveness of human health and the environment; reduction in contaminaht
           mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
          community acceptance.

          No innovative technologies were incorporated into remedial alternatives.
   7.      How did the cost(s) compare to standard technologies?

                    Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
Standard Technology
No action/long-term monitoring ;
NJDEP solid waste cap
NJDEP hazardous waste cap
RCRAcap
Bentonite clay cap
Modified hazardous waste cap
Estimated Costs
3 Criteria
N/Aa
$13,142,000
$23,262,000
$20,202,000
$14,905,000
$15,823,000
9 Criteria
$3,228,000
$13,946,000
$25,365,000
$22,305,000
$15,709,000
$16,627,000
         The "no action" alternative was not developed until the detailed analysis stage.
  8. If a standard technology was chosen, why?
170
RAA-6 was chosen because of all the proposed alternatives it offers the greatest protection to
human health and the environment.  The modified hazardous waste cap proposed in RAA-6

                                      '-2-       •          -                     !

-------
        will reduce the infiltration of rainwater and thereby reduce the generation of leachate. It will
        also provide protection from direct exposure to contaminants.  The cap proposed in RAA-6 is
        relatively light, which is important given the instability of the side slopes of the landfill. This
        cap assures the greatest factor of safety against side slope failure. This alternative can be
        implemented easily, and in minimal time.  Materials and equipment required for this cap are
        readily available.  This cap minimizes impact to the nearby wetlands.'' (The ROD also included
        solidification/stabilization and off-site disposal as primary remedies.) iOf the alternatives, the
        selected remedy affords the highest level of overall effectiveness proportional to its cost and is
        therefore the cost-effective alternative.                             i                ••..''•
9.     If an innovative technology was chosen, why?                          -

       An innovative technology was not chosen.
                                                           "  •     •      i      ••                  . '  •

10.    If an innovative technology was not chosen, why not? At what stage vitas the innovative
       technology eliminated?                                           1.'

       Innovative technologies could be eliminated from the remedial technology selection process at
      ' three stages: during the initial screening; during the screening of the fhree criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      In situ bioreclamation was eliminated because it would not address'all,site
               contaminants.  Furthermore, segregation of waste prior to the implementation of this
               technique would be required because of the heterogeneous nature of the site?s waste.
       •      In situ soil flushing was eliminated because it would not  address all site contaminants.
               Furthermore, segregation of waste prior to the implementation1 of this technique would
               be required because of the heterogeneous  nature of the site's >jvaste.
       •      In situ vitrification was eliminated because it would not address all site contaminants.
               Furthermore, segregation of waste prior to the implementation! of this technique wpuld  ,
               be required because of the heterogeneous  nature of the site's \yaste.  '

       Innovative technologies eliminated during the screening of the three ciriteria include the
       following:                              '..'.'..'           !

       •      None             •                               '.,'•''

       Innovative technologies eliminated during the detailed analysis include: the: following:

      / •      None •.    ''.             •  •   • .           '•      •'.  •      i         .


11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The  criteria  that were weighted most heavily in the choice of a remedial alternative were cost
       and protection of human health and the environment.


       ..'.   •       -"   •'         •   .     -3-    ••  ".'  ••'•  --I:"   ;.;'      •   •    171

-------
   12.
  13.
  What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR? What risk level was selected to establish cleanup goals?                  "
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens '
Total volatiles
Total base neutrals
Arsenic
Beryllium
Cadmium
Chromium
Lead
Petroleum
hydrocarbons
PCBs
1
10
20
1 . • *
3
100
250-620
100
1-5
NJDEP
NJDEP
NJDEP i
NJDEP
NJDEP
NJDEP
NJDEP !
NJDEP
NJDEP
Noncarcinogens ;
Antimony
Copper
Mercury
Selenium
Silver
Thallium
Zinc
10
170
14
4
5.
1
1 350
NJDEP
NJDEP
NJDEP
_ NJDEP
NJDEP .1
NJDEP
NJDEP
                                                                                               «b
                "New Jersey Department of Environmental Protection tentative soil action cleanup
                levels will constitute TBCs (to be considered) in the absence of State or Federal
                ARARs.                                                            ;
Was the innovative technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None                                                                ;
172
                                            -4-

-------
       Standard technologies eliminated because of cleanup goals include:   i

       •       None                                                                         ,


14.     Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.


15.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:
         '-                -    '     '            '     .'                    1        .   .    • '
             Cost-effectiveness
             Impact to wetlands

                               ''     -       -        -           _         ' J
16.     How are measures compared?                                    i
                                                                       "l
       The chosen alternative was preferred because it provided the greatest reduction of infiltration
       and the least impact on wetlands.  The costs associated with the chosen alternative were
       proportional to its superior protection of human health and the environment. Therefore, it was
       cost-effective.
17.    - What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Two technical considerations were primary in selecting a remedial alternative. The instability
        of the landfill sideslopes, which had previously caused the landfill tojcollapse, precluded the
        use of a NJDEP hazardous  waste cap (RAA-3) or a RCRA cap (RAA-4).  Potential impact on
        wetlands was another consideration that led to the elimination of two] alternatives (RAA-3 and
        RAA-4).    ''.'•'                                 '.     . .;
                                                .5.

-------
                                        Hertel Landfill

                                       Plattekill, New York
                                            Region 2
  GENERAL SITE INFORMATION
minants,
addressed in

rincipal

.--

2
'0.8
1 '
0.9
2
0.4
109
64

Site History 1
NPL Proposed: 10/84
NPL Final: 6/86 - • ;
FS: 7/91 I
ROD: 9/27/91
Background !
i
EPA Fund-lead ! .
PRPs: Not listed
FS prepared by: TAMS Consultants,
Inc. and TRC Environmental
Consultants, Inc. i . „
.' • i

68,100
  1.     What were the principal contaminants,
         contaminant levels, and m<
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil/Sediment (mg/kg)

         Benzo(a)anthracene
         Benzo(b)fluoranthene
         Benzo(k)fluoranthene
         Benzo(a)pyrene
         Chrysene
         Indeno(l ,2,3-cd)pyrene
         Arsenic
         Chromium
         Manganese
 2.      What volume of material is to be remediated?                                    ]

         The volume of material to be remediated included:

         •      300,000 cubic yards of soil/waste matrix                                  !    .


 3.      What type of site is this?           '        '                                   !

         Municipal Landfill. A former municipal landfill.


 TECHNOLOGY SELECTION                                                        ;

 4.      What standard technologies were considered for selection in this FS?               j     •

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:

         Access restriction:     Deed  restriction, fencing
         Containment:         Capping (clay, synthetic, asphalt, concrete, and multilayer)
         Chemical treatment:   Stabilization/solidification
        Thermal treatment:     Incineration (fluidized bed, infrared, and rotary kiln)
174
                                              -i-

-------
       Physical treatment:
       Disposal:
Mechanical aeration
On-site landfill, off-site landfill
5.      Was an innovative technology considered in the FS? If so, which technology?
          -                                                             I             -  •
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                      .

       Biological treatment:   In situ biodegradation, landfarming         j
       Phys/Chem treatment:  Soil washing (extractant solution), dechlorination, oxidation/reduction,
                             in situ soil flushing, in situ soil venting     j
       Thermal treatment:    In situ vitrification, radio frequency heating ,
        What was the cost estimate for the innovative technology?                            ,
                                                     /              * .   !   ;             •     -
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a,more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based cin the nine criteria established
        by theNCP.                                                     I

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial  alternative is in bold)    i
Alternative
RAA-7
i
Innovative Technology
In situ vitrification/ground water
extraction and on-site treatment
Estimated Costs
3 Criteria
$110,000,000
9 Criteria
eliminated
 7.      How did the cost(s) compare to standard technologies?            i,

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)    ,'  . .
Alternative
RAA-1
RAA-2
RAA-2A
Standard Technology
No action/ground water monitoring
Fencing/deed restrictions/multilayer cap
Fencing/deed restrictions/multilayer
cap/slurry wall
I Estimated Costs
3 Criteria
$2,5(K),000
$7,0()0,030
$1.5iOpO,000
9 Criteria
$2,509,000
. $7,182,000
$13,238,000
                                               -2-
                                                                                              175

-------
Alternative
RAA-3
RAA-4
RAA-4A
.RAA-5
RAA-6
=====
Standard Technology
Excavation of soil and waste/off-site
disposal/ground water extraction and
treatment off site
Fencing/deed restrictions/multilayer
cap/ground water extraction and standard
treatment on site/discharge to surface
water
Fencing/deed restrictions/multilayer
cap/ground water extraction and
innovative treatment on site/discharge
to surface water
Excavation of soil waste matrix/on-site
rotary kiln incineration/ground water
extraction and treatment/surface water
discharge
Excavation of soil waste matrix/off-site
rotary kiln incineration/ground water
extraction and treatment/surface water
discharge
Estimated Costs
3 Criteria
$190,000,000
$8,200,000
$7,900,000
$120,000,000
$510,000,000
9 Criteria
eliminated
$8,744,000
$8,207,000
1
I
i
eliminated
eliminated
gg'j '
   8.     If a standard technology was chosen, why?

          The standard technology selected for this site includes regrading and compacting the landfill
          mound to provide a stable foundation for cap placement, and constructing a 13 acre multi-layer
          cap over the landfill with an associated gas venting system. The following reasons were given
          for selection of this remedy:  1) will minimize infiltration of rainwater and snow melt into, the
          landfill and eliminate/reduce leachate seeps emanating from the landfill, thereby reducing the
          quantity of water percolating through the landfill materials and leaching out contaminants, 2)
          size of the landfill and lack of identified on-site hot spots that represent the major sources of
          contamination preclude a remedy in which contaminants could be excavated and treated
          effectively, 3) eliminates exposure to surface soil contamination, 4) deed restrictions on use
          will eliminate future land use causing exposure and possible compromise of the integrity of the
          cap.                               ,                                            ,
   9.      If an innovative technology was chosen, why?

          An innovative technology was not chosen.
176
                                                 -3-

-------
10.    If an innovative technology was not chosen, why not? At what stage vvas the innovative
       technology eliminated?
                                                     '"•!••
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the; following:

        •      Soil washing was eliminated because several different washing solutions would be
               required to treat all types of soil contaminants.
        "      Dechlorination was eliminated because it would not be effective for inorganic
               contaminants and it would not be applicable to municipal solid waste materials.
        •      In situ biodegradation was eliminated because it would be ineffective for inorganics
               and for large volumes of municipal solid waste materials.    ;
        •      Landfarniing was eliminated because it would be ineffective for inorganic
               contaminants and for large volumes of municipal solid waste materials.
        •      Soil venting was eliminated because it would be ineffective for inorganic contaminants;
        •      Radio frequency heating was eliminated because it has not been demonstrated on a
               large scale or on large volumes of municipal solid waste materials.
        •      Soil flushing was eliminated because it is only effective for medium solubility organics
               and would be ineffective for inorganics,  and it would not be; applicable to municipal
               solid waste materials.                                     ;

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                 ,                                     •-,'..•

        •      In situ vitrification was eliminated because: 1) the effectiveness as applied to a
               municipal landfill has not been previously proven, 2) the number of vendors is limited,-
           :    3) treatability studies would be required to confirm the effectiveness of these
               methodologies prior to design, 3) cost would be high.       i

        Innovative technologies eliminated during the detailed analysis include the following:
                             '                   .           '             I     .
        •      None     .                      '••'''••.             ' '
 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion? Which of the criteria supported the use of a standard technology?

         Criteria that weighted heavily in selection of a technology were: 1) implementability - capping
         technologies are well developed and reliable; 2) reduction of toxicity, mobility and  volume
         through installation of a cap - the NCP deems containment remedies; appropriate where
         treatment of the waste is impracticable (e.g.5 mixed waste of widely varying composition); and
         3) cost.  No innovative technologies were included in the detailed analysis, however cost and
         implementability eliminated innovative technologies during the .3-criteria screening.
         Implementability and cost supported the standard technology.
                                                -t-           •          •

-------
   12.
  What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?                       '
Contaminant
Carcinogens
Benzo(a)anthracene
Benzo(b) fluoranthene
Benzo(k) fluoranthene
Benzo(a)pyrene
Chrysene
Indeno(l,2,3-
cd)pyrene
Cleanup Level (rag/kg)
ARAR or Other Basis

0.26
0.26
0.26
0.26
0.26
0.26
NYSDEC"
NYSDEC
NYSDEC
NYSDEC
NYSDEC
, NYSDEC
Noncarcinogens
Arsenic
Chromium
Manganese
0.06
. 25
2
Risk"
Risk
Risk
                "NYSDEC, 1989: Sediment criteria. Bureau of Environmental Protection, Division of
                Fish and Wildlife.
                "Risk-based cleanup level derived from a future use residential scenario (children)
                producing a compound specific hazard quotient of 1.0 or less.
 13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

No technology could meet the chemical specific ARARs for soils.  By designing the final cap
to meet New York Solid Waste Management Facility closure regulations, the alternative will
comply with action specific ARARs.
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.  A treatability study is proposed to be carried out
        however, prior to the full implementation of the suggested ground water treatment technology.


 15.    What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:
178
       total cost
       waste left in place/institutional controls
       proven reliability

                                      -5-

-------
      16.    How are measures compared?                                  ,  j     .

             All proposed source treatment technologies were eliminated because they were not cost-
             effective. The construction, operation, and maintenance costs of incineration and in situ
             vitrification were considered grossly excessive when compared to their overall effectiveness.
             Furthermore, containment technologies were considered appropriate because the landfill
             contained mixed wastes. Treatment was considered impractical for wiastes that were not highly
             toxic or mobile. The reliability of capping versus undemonstrated technology was considered..
                                                 -'                            'L                  '

      17.    What technical considerations were factors in selecting a remedy? Were technical
             considerations primary in the selection of the remedy?

             Since the site is bordered by wetlands, location-specific ARARs were! a consideration. This
             factor did not play a primary role, however, in selecting a remedy.   i_
II
                                                                             '                           179

-------
                                  Industrial Latex Corp.
                                           OU-1

                            Wellington, Bergen County, New Jersey
                                          Region 2
  GENERAL SITE INFORMATION

  1.     What were the principal contaminants,
         contaminant levels, and mt
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil/Sediments (mg/kg)

         PCB Aroclor 1260
         Heptachlor epoxide
         Arsenic
         Beryllium
         Lead
         Benzo(a)anthracene
         Benzo(a)pyrene
         Benzo(b)fluoranthene
         Benzo(k)fluoranthene
         Benzo(ghi)perylene
         Bis(2-ethylhexyl)phthalate
         Chrysene
         3,3-Dichlorobenzidine
         Ideno(l,2,3-cd)pyrene

         Sludge (mg/kg)
minants,
addressed in

incipal



4,000
0.22
49.4
2.2
89.9
13
11
13

Site History
NPL Proposed: 6/88 i
NPL Final: . 3/89 \
FS: 7/92
ROD: 9/30/92
Background

EPA Fund-lead
PRPs: Five PRPs were identified for this
site; however, these were not
named
FS prepared by: ICF Technology Inc.

•• - „ ;
11 - . ' . - ' '
5.1
280
21 •',,*" . - ' •
6
6.4
        VOCs
        PCBs
        Phthalates
        Metals
2,800
22,000
5,600
13,000
                                                          *:>
 2.     What volume of material is to be remediated?

        The volume of material to be remediated included:

        «      32,000 cubic yards of soil
        •      2,700 cubic yards of soil and sediments in a drainage channel
        "      6 cubic yards of sludges from the septic tanks
130
                                           -1-

-------
3.
What type of site is this?
       Rubber and Plastics Products. The Industrial Latex Corporation manufactured chemical  .
       adhesives, and natural and synthetic rubber compounds from 1951 until 1980. Intermittent
       processing of latex compounds continued at the site until October 1983, when all operations
       ceased.  The property encompasses 9.67 acres in a mixed residential/industrial neighborhood.
TECHNOLOGY SELECTION
                                     :   -            _         ,           i
                                                                        I •"
4.      What standard technologies were considered for selection in this FS?

                                                                   !   '  !  \
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                         ,

        Access restriction:     Fencing, deed restrictions                               .
        Containment:          Capping (RCRA cap, multimedia cap, asphalt; cap, soil cap)
        Chemical treatment:    Stabilization, solids processing              :
        Thermal treatment:     On-site/off-site incineration      '      ,    i              ,
        Disposal:       ,       Excavation, on-site/off-site landfill          J

                                                                        ,j
5.      Was an innovative technology considered in the FS?  If so, which  technology?,

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
                                                       r      ^- ;         ,i -              .   '
        Biological treatment:  , Biological-treatment (in situ biodegradation, Land treatment, bioreactor)
        Phys/Chem treatment:  Solvent extraction, critical fluid extraction, soil vapor extraction, in situ
                              soil flushing, dechlorination (KPEG)         !
        Thermal treatment:     Low-temperature thermal desorption, in situ vitrification, in situ radio
                              frequency heating
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives thai; merit a more detailed
        evaluation. For this site, costs were calculated during an evaluation based on nine criteria
        established by the NCP.                                         !

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)    ;
' Alternative
RAAS-4
Innovative Technology
Low-temperature thermal desorption
[Estimated Costs
3 Criteria
N/A
9 Criteria
, $17,100,000
                                                -2-
                                                                                               131

-------
Alternative
RAAS-5
RAAS-6
Innovative Technology
Dechlorination
Solvent extraction
Estimated Costs
3 Criteria
• N/A
N/A
9 Criteria
$16,800,000
$23,700,000
  7.      How did the cost(s) compare to standard technologies?
                       Cost Estimates for RAAs That Include Standard Technologies
                                 (selected remedial alternative is in bold)
Alternative
RAAS-1A
RAAS-1B
RAAS-2
RAAS-3
RAAS-7
RAAS-8
Standard Technology
No action
Minimal action
Capping
In situ stabilization
On-site incineration
Off-site landfill
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$83,000
$3,434,000
$7,090,000 '
$11,200,000
$25,300,000
$13,600,000
 8.      If a standard technology was chosen, why?                    •','..

        The selected remedy includes excavation of the septic system and its transportation off site for
        treatment or disposal. No standard technology was selected for remediating on-site soils.
 9.      If an innovative technology was chosen, why?

        The selected remedy RAAS-4 involves excavating contaminated soils, treating them on site
        with low-temperature thermal desorption (LTTD), and backfilling treated material.  Data
        available from the treatability study show that PCBs have been reduced to 2 ppm, the
        treatability study treatment goal.  It is anticipated that the EPA remediation  goal of 1 ppm can
        be satisfied by modifying treatment conditions such as residence time and temperature, if
        necessary. Full-scale treatment has been demonstrated to achieve concentrations as low as 2
        mg/kg.  Based on this performance data, the type of soil matrix at the Industrial Latex  site,
        and the relatively low concentration of contaminants in the soil, there is a high  degree of
        reliability in achieving target cleanup levels for soil using this treatment. RAAS-4
        substantially reduces the toxicity, mobility, and volume of contamination by extracting  organic
        compounds from the soil and further treating the residuals off site.  The LTTD process has
        been demonstrated to be effective for a wide range of volatile and semivolatile organic
        contaminants.  The technology is implementable using commercially available equipment
        (X*TRAX technology) and materials. Risks associated with treatment system mobilization and
132
                                              -3-

-------
        startup are expected to be minimal.  Finally, RAAS-4 satisfies EPA remediation goals and
        RCRA Land Disposal Restrictions for hazardous wastes as they apply to backfilling of treated
        soil.-      '      '  '        '••-'         • .    '  •  -    •'   ".         ',:;   -

        The ROD states that at that time the State of New Jersey did not yet concur with the selected
        soil remediation alternative.                                '        ;
10.     If an innovative technology was not chosen, why not? At what.stage was the innovative
        technology eliminated?                         '

        mnovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        •      Critical fluid extraction was eliminated because solvent extraction using triethylamine
               was retained as the representative solvent extraction technology for consideration in the
               development of RAAs.  A disadvantage of this technology mentioned in the FS is that
               it does not extract metal contaminants from soil.                     .  .           .
        •      Soil vapor extraction was eliminated because the technology has not been
               demonstrated effective in  removing PCBs from soil.  The FS cites the following
               disadvantages of this technology: it requires control of vented vapors to mitigate
               atmospheric discharge of hazardous chemicals, and it would not be expected to be
               effective for PCBs which  do not readily volatilize.           ;,
        •      In situ soil flushing was eliminated because of difficulties in implementation and
               questionable effectiveness for removing PCBs to the required cleanup goals.  The FS
               cites the following disadvantages of this technology: it must be implemented in
               conjunction with ground water collection and treatment, though ground water flow
               characteristics required to design an extraction system are not; fully understood at this
               site; and PCBs, the most ubiquitous contaminant, are not highly soluble in water and
               would be difficult to remove from the soil matrix to which it is absorbed.
        •      Biological treatment (in situ biodegradation,  land treatment, ex situ bioreactor) was
               eliminated because of the complexity of the process, the lack of demonstrated
               effectiveness,  and availability of other solids treatment technologies for the site. The
^              FS cites the following disadvantages of this technology: microorganisms that  can
               degrade PCBs have different environmental requirements than those  that can degrade
               most PAHs; there is no conclusive demonstration of the effectiveness of
               bioremediation for Aroclor 1260; and the technology is not effective in removing    ;
               metal contaminants from  soil.                              i
        »      In situ vitrification was eliminated for the following reasons: prganics might volatilize
               during treatment and pose risks  to nearby residents, and emission would need to be
               captured; this technology  is unproven in large-scale applications; the presence of
               ground water greatly increases the cost of treatment; and this technology restricts
               future land use.                                           !                     ,
        •      In situ radio frequency heating was eliminated because it's experimental  and  pilot test
               equipment is not available.                                I    ,
                                                                                                   183

-------
           Innovative technologies eliminated during the screening of the three criteria include the
           following:

           B      None

           Innovative technologies eliminated during the detailed analysis include the following:

           «      Dechlorination was eliminated but no specific reason was given.  During the
                  evaluation of alternatives the ROD states that there was some uncertainty as to the
                  residuals associated with this treatment technology and toxicity testing would have to
                  be performed prior to its implementation.                             •
           "      Solvent extraction  was eliminated but no specific reason was given.  During the
                  evaluation of alternatives the ROD states that the long-term effectiveness of solvent
                  extraction was less certain than that of other technologies because of the uncertainty
                  about the fate of the residual solvent used in the treatment process.
   77.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 Protection of human health and the environment and long-term effectiveness and permanence
 were weighed most heavily in selecting an alternative for this site. The selected alternative is
 protective of human health and the environment because the soil is treated to remove the risk-
 causing contaminants. RAAS-4 deals effectively with the threats posed by the contaminarits
 which were identified and will attain  a 10"4 to 10* risk level for carcinogens and the HI will be
 less than 1 for noncarcinogens.  In addition, the selected alternative is one of the most
 effective alternatives in the long term and the most permanent because contaminants are
 removed from site soils and destroyed.  Treatability study results show that LTTD provided
 significant removal of PCBs from site soils. The long-term effectiveness of other alternatives
 is less certain:  there is uncertainty about the fate of the residual solvent used in solvent
extraction, off-site landfilling relies on the long-term integrity of off-site disposal facilities,
stabilization is less certain because it relies on the ability of soil-fixing techniques to   :
permanently immobilize the contaminants, and capping requires continued maintenance:for an
indefinite period of time.

  12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
          ARAR?  What risk level was selected to establish cleanup goals?                     !
134
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
PCB Aroclor 1260
Heptachlor epoxide
Arsenic
Beryllium
Lead
1
0.1
3.6
0.48
,500
Risk1"
Risk8
Background0
Background*
Risk2
                                       -5-

-------
Contaminant
Benzo(a)anthracene '.
Benzo(a)pyrene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Behzo(ghi)perylene
Bis(2-ethylhexyl)
phthalate
Chrysene
3,3-Dichlorobenzidine
Ideno(l ,2,3-cd)pyrene
Cleanup Level (ppm)
0.4
0.1
.0.5
0.8
3
46
13
1.4
0.2
ARAR or Other Basis
' Risk8
; Risk8
i Risk8
Risk8
Risk8
Risk8
i .
| Risk*
, Risk8
Risk8
              "EPA Region 2 Remediation Goals (RG) developed according; to the methodology
              outlined in the Risk Assessment Guidance for Superfund (RAGS) Part B. The RG
              applies to both surface and subsurface soils.  For carcinogens; an excess upper bound
              individual lifetime cancer risk of 10"6 was acceptable.
              'The New Jersey Department of Environment and Energy (NJfDEE) has proposed
              surface soil and subsurface soil cleanup standards for PCBs of 0.45 ppm and 100 ppm
              respectively.  Proposed surface soil standards apply only to soils in the 0 to 2 foot
              depth interval.
              cThe remediation level for arsenic is the background concentration. The corresponding
              RG is 0.4 ppm.                                          !
              dThe remediation level for beryllium is the background concentration.  The
              corresponding RG is" 0.2 ppm.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                           '•  \ -

       Innovative technologies eliminated because of cleanup goals include:

       •     In situ soil flushing was eliminated in part due to questionable effectiveness for
              removing PCBs to the required cleanup goals.
                                        /                              ii
       Standard technologies eliminated because of cleanup goals include:   ,

       •     None              .
14.     Were treatability studies conducted on the innovative technology or standard technology?

        The results of a treatability study performed by IT Corporation examining the effectiveness of
        LTTD on samples of contaminated soil from this site demonstrated that the process was
        effective in reducing Aroclor 1260 concentrations ranging from 9.9 mg/kg to 779 mg/kg in the
        untreated soil to less than the study target level of 2 mg/kg.  .
                                              -6-
185

-------
    15.     What measures/criteria were used to compare alternatives?                                      ^& \

           The following measures were used to'compare the alternatives:

           -  ,  Cost-effectiveness
                Proven reliability                            •''<.''                 •'
                Preference for treatment (vs. containment)


    16.     How are measures compared?

           The selected remedy was determined to be cost effective because it provides the highest degree
           of protectiveness among the alternatives evaluated, while representing cost value. LTTD was
           selected because it is implementable using commercially available equipment and materials.
           By treating contaminated soil on site through the use of an innovative process, the selected
           remedy .addresses the threats posed by the site through the use of treatment technologies.


   17.     What technical considerations were factors in selecting a remedy?  Were technical                  '
           considerations primary in the selection of the remedy?

           Technical considerations were not primary in selecting a remedy. In situ soil flushing was
           eliminated  because of the heterogeneous nature of the soils at the site; the washing solution
           might not have contacted all the soil particles

ise                                      •    .7-      '     .     .               .   "    ;:          ".    .:'       !'

-------
                           Islip Municipal Sanitary Landfill
                                      Islip, New York
                                         Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Sample were collected from ground water,
       landfill gases, and ambient air. No soil
       samples were reported. The contaminants of
       concern were:

       Vinyl chloride
       Arsenic
       Beryllium
       Antimony
       Thallium
       Benzene
       Trichloroethene
       Tetrachloroethene
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1/87
3/89
6/92  ;
9/30/92
             Background

PRP-lead         ].
PRPs:  Town of Isilip, Department of
       Environmental Conservation
FS prepared by: OJMCE of New York,
       P.C.      '
2,     What volume of material is to be remediated?                     !

       The volume of material to be remediated included:                ;
                         .     .-.         ••''••              r  '
       •     The volume of the landfill is not provided. The proposed cap will cover 54 acres.


3.     What type of site is this?                                       j!         /
                                                            .-        I          ~*
       Municipal Landfill. A former municipal landfill.    '             j         .
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:      ,                              ,        i ..'-'"'-.
                                             -1-
                                                                                             187

-------
            Access restriction:
            Containment:
Deed restrictions
Capping (clay, soil, asphalt, multilayer, synthetic membrane additive
derived), slurry wall, grout curtains, sheet piling, various soil mixture
walls, horizontal barriers
            Was an innovative technology considered in the FS?  If so, which technology?

            Innovative technologies considered during the identification and screening of technically
            feasible technologies were:

            No innovative technologies were proposed for source  treatment.
    6.      What was the cost estimate for the innovative technology?

           During the initial screening process, in which technically feasible technologies are identified
           (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
           formulated, costs are typically estimated as part of a three-criteria screening process
           (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
           evaluation. In this case the estimated costs were calculated during an evaluation based on nine
           criteria established by the NCP. Alternatives were renumbered in the ROD and these changes
           are presented parenthetically.  No innovative technologies were incorporated into RAAs'.


    7.      How did the cost(s) compare to standard technologies?

                     Cost Estimates for RAAs That Include Standard Technologies
                                (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
(RAA-3A)
RAA-4
(RAA-3B)
RAA-5
(RAA-3C)
RAA-6
(RAA-4A)
Standard Technology
No action
Landfill cap/monitoring/institutional
actions
Landfill cap/pump and treat all ground
water with aeration and activated carbon
Landfill cap/pump and treat all ground
water with chemical precipitation and
air stripping
Landfill cap/pump and treat all ground
water with UV peroxidation
Landfill cap/pump and treat ground
water above 50 ppb VOCs with
aeration and activated carbon
Estimated Costs
3 Criteria
N/A
' N/A
N/A
N/A
N/A •'
N/A
9 Criteria
$0
$15,226,200
$21,214,310
$26,311,710
$40,145,570
$19,430,640
                                                                      4ft
188
                                                -2-

-------
Alternative
RAA-7
(RAA-4B)
RAA-8
(RAA-4C)
Standard Technology
Landfill cap/pump and treat ground
water above 50 ppb VOCs with
chemical precipitation and air stripping
Landfill cap/pump and treat ground
water above 50 ppb VOCs with UV
peroxidation .
Estimated Costs
3 Criteria
N/A .
N/A
9 Criteria
$23,491,000
$33,372,470
8.      If a standard technology was chosen, why?                        '[
                         '  •               '    -       '         •         -i
       The chosen alternative, RAA-6 (RAA-4A), was preferred because it is proactive, technically
       feasible, and implementable at the lowest cost.  Capping will be an effective means of
       reducing the mobility of contaminants through the waste layers because it restricts the
       infiltration of precipitation and surface water runoff.  This, in turn, reduces percolation and
       subsequent transport of contaminants to ground water.  Capping the landfill also will be an
       effective mechanism of controlling the mobility of vapor phase contaminants because it
       controls the transport of subsurface gases to the air through passive vents..  The risk associated
       with direct contact with landfill waste will be eliminated after the cap  is completed.  Deed
       restitutions further eliminate human exposure to landfill waste and ground water.  The
       synthetic membrane cap was preferred because it is chemical resistant  and relatively
       impermeable. This alternative provides long-term effectiveness because contaminants will be
       immobilized.  Capping and  proposed ground water treatment will act together to eliminate
       contaminants permanently from ground water and restore the aquifer to drinking water
       conditions. This alternative should be easily implemented since technologies for capping  are
       readily available.  A 52- acre cap, however, is a relatively large construction project, and  some
       technical problems could  be encountered.  RAA-6 is the cost-effective alternative. No
       treatment for landfill waste  was proposed because it would be impractical! due to the large
       quantity of waste and the waste's location under an interim cap where hot spots can not be
      . identified.                                            <                           '   .
                                        '                   '            !
       The recommended alternative in the FS was RAA-2.  RAA-2 was recommended because
        ground water treatment was expected to cause the release of VOCs to the; atmosphere, and it
        was uncertain if ARARs  would be technically or financially attainable thirough ground water
        treatment.  The FS also stated that the benefit to health due to ground water treatment was not
        great since the aquifer did not need to be used as a drinking water source.  RAA-6 (RAA-4A)
        was the selected alternative in the Proposed Plan.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not recommended.
                                               -3-
                                                                                                  189

-------
    10.     If an innovative technology was not chosen, why not? At what stage was the innovative
           technology eliminated?

           Innovative technologies could be eliminated from the remedial technology selection process at
           three stages:  during the initial screening; during the screening of the three criteria of
           effectiveness, implementability, and cost; or during the detailed evaluation.
                                                     -                        .  ,
           Innovative technologies eliminated during the initial screening include the following:
                               •
           •      None

           Innovative technologies eliminated during the screening of the three criteria include the
           following:

           "      None            '                .         '  .            ..              '
                                  "*•'                 •                                    "-•
           Innovative technologies eliminated during the detailed analysis include the following:

           •      None
                                                                                         i
                                                               -'--'".-
   11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
           to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
           which criterion? Which of the criteria supported the use of a standard technology?

           The most heavily weighted criteria in selecting a remedial  technology were long-term
           effectiveness, short-term effectiveness, and cost-effectiveness. Capping was considered
           important because it would ensure greater long-term effectiveness. Capping was proposed in
           most RAAs and other criteria directing the choice of an RAA was aimed at ground water
           remediation. The chosen alternative was the most cost-effective because it is more protective
           than natural attenuation but not as  extreme as treating all ground water, which would be more
           costly.  The chosen alternative also will be more productive in the short-term because it will
           treat "hot spots" of contaminated ground water.  While the chosen alternative will capture high
           levels of contaminants immediately, it would take approximately 5 years for RAA-3A, RAA-
           3B, and RAA-3C to begin capturing similar levels of contaminants. The advantage of
           removing contaminants quickly is that contaminants will not sink deeper into the aquifer.
           Long-term cleanup will depend on natural attenuation as well
                                                         ' -  •     ••              -  -  '    i  -
                                                                                         ;
   12.      What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
          ARAR?  What risk level was selected to establish cleanup goals?
                                                                                         1         .

          No cleanup goals were established  for source control.  The capping of the landfill will impact
          and enhance the  cleanup of the underlying aquifer.
190
                                                -4-

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                                i

       Innovative technologies eliminated because of cleanup goals include:  ;

       •     None
                                                                        !l
       Standard technologies eliminated because of cleanup goals include:

       , •      None
      '                                     '                             'i   '

 14.     Weretreatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.


 75     What measures/criteria were used to compare alternatives?                   •  •  ,

        The following measures were used to compare the alternatives:

               Time to design/construct/operate

•          '          '       '            '                   '        "' .   . :i  i     ,'   .
 16.     How are measures compared?

        The chosen alternative was preferred because it proactively addresses; ground water
        contamination. Treating ground water "hot spots" was preferred over natural attenuation
        because it will take less time to achieve ARARs.  Hot spot treatment was preferred over
        treatment of all ground water because it will address highly contaminated water more quickly
        and it will reach ARARs in a longer but acceptable amount of time. Addressing "hot spots"
        was deemed to be important because they threaten the underlying aqiiifer.
                 '. •     •'   . •                                      •••'!!

  17.     What technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?             j
                                                                        i
         No technical considerations were primary in selecting a remedial alternative.
                                                                                                   191

-------
                                        Juncos Landfill
                                              OU-1

                                        Juncos, Puerto Rico
                                             Region 2
   GENERAL SITE INFORMATION

   L      What were the principal contaminants,
           contaminant levels, and media being
           addressed in this feasibility study?

           Maximum concentrations of principal
           contaminants were:

           Soil (mg/kg)

           1,4-Dichlorobenzene   3
           Total  phenols         0.5
           Arsenic              17
           Cadmium            3
           Copper              168
           Nickel               41
           Lead                 63
           Mercury              49
           Zinc                 165
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
9/83
4/91
9/24/91
             Background
PRP-lead
PRPs: Becton Dickinson Puerto Rico, Inc.
FS prepared by:  McLaren/Hart Environ-
       mental Engineering Corporation
                                                 -n^.
   2.      What volume of material is to be remediated?

          The volume of material to be remediated included:

          «      290,000 to 870,000 cubic yards of waste materials and soils
   3.      What type of site is this?

          Municipal Landfill. Inactive municipal waste landfill.       \


   TECHNOLOGY SELECTION                                                       :   •

   4.      What standard technologies were considered for selection in this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:                                        •.:''"'

          Access restriction:     Fencing, deed restrictions
          Containment:         RCRA cap, single-barrier cap, revegetation, gas venting system,
                              regrading landfill slopes
192
                                              -1-

-------
       Thermal treatment:     Fluidized bed incineration, rotary kiln incineration, infrared thermal
                              treatment
       Disposal:              Excavation, off-site disposal                ;

                                                                        *         ,• •
5.     Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                                             ,

       Biological treatment:   In situ biodegradation, on-site solid-phase bicjdegradation, on-site slurry
                              phase biodegradation, composting           i
       Phys/Chem treatment:  Chemical extraction, in situ chemical treatment, soil washing, soil
                              flushing                 .                •  \
       Thermal treatment:     Vitrification, pyrolysis
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs,  .After the RAAs have been
        formulated, costs are estimated as part of the three criteria (effectiveness, implementability,
        cost) screening process to identify alternatives of sufficient merit to undergo detailed
        evaluation. The estimated costs are recalculated during evaluation by the nine criteria
        established by the NCP.  All innovative technologies were eliminated in the initial screening
        process.  Costs were not estimated at this point.
7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4A
Standard Technology
No action: monitoring/assessment every
five years
Fencing/institutional controls/erosion and
sediment control/monitoring
Regrading the landfill/RCRA Subtitle C
cap/passive gas control system/leachate
control system/fencing/erosion control/
monitoring/institutional controls
Regrading landfill/single-barrier cap with
clay barrier/passive gas control system/
leachate control system/fencing/erosion
control/monitoring/institutional controls
Estimated Costs
3 Criteria
$1,088,000
$1,488,000
$7,1<)8,ODO
/'
' i
$6,272,000
9 Criteria
$1,088,000
eliminated
$7,108,000
$6,272,000
• ' -2-
                                                                                                      193

-------
Alternative
RAA-4B
RAA-5
Standard Technology
Regrading landfill/single-barrier cap
with geomembrane/passive gas control
system/leachale control system/fencing/
erosion control/monitoring/institutional
controls
Regrading landfill/soil cap/passive gas
control system/leachate control system/
fencing/erosion control/monitoring/
institutional controls . " •
Estimated Costs
3 Criteria
$4,420,000
$5,022,000
9 Criteria
$4,420,000
1
$5,022,000
   8.      If a standard technology was chosen, why?

           A single-layer cap with geomembrane (RAA-4B) was selected because it is protective of
           human health and the environment, prevents on-site contaminant contact and leachate
           generation, minimizes air emissions, and reduces the migration of contaminants.  With the
           exception of no action (RAA-1) and fencing (RAA-2^all three action alternatives involved
           some type of capping.  The selected remedy offers a higher degree of permanence and
           protectiveness than the no action, fencing, and soil cap alternatives and has a similar degree of
           protectiveness as the RCRA cap alternative.  A RCRA cap (RAA-3) would be much more
           expensive and its increased ability to prevent infiltration of precipitation is not necessary since
           RCRA hazardous waste cannot be proven to have been disposed at the site. A single-barrier
           cap with clay barrier (RAA-5A) was more expensive than the selected alternative. The three
           capping alternatives were  rated very similarly;  the major difference between them was cost.  It
           was determined  that the selected alternative offered the highest level of overall  protectiveness
           proportionate to cost.  The increased cost of the other capping alternatives was  not reflected in
           greater protection of public health and the environment.
   9.      If an innovative technology was chosen, why?

          An innovative technologies was not chosen.
   10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?

          Innovative technologies could be eliminated from the remedial technology selection process at
          three stages:  during the initial screening; during the screening of the three criteria of
          effectiveness, implementability, and cost; or during the detailed evaluation.
                                                       ,                                   l
          Innovative technologies eliminated during the initial screening include:

          •      Chemical extraction was grouped into the general category "physical/chemical :.  '
                 treatment,"  which was considered to be an ineffective method  of cleanup due to the
                 heterogeneous nature of the landfill.  Contaminant concentrations at the surface of the
                 landfill were low, so large volumes of waste would have to be processed to remediate
194
                                                -3-

-------
              small amounts of contaminant.  Excavation of waste for treatment was expected to
              pose a threat of exposure to workers and local residents.  Treatment would produce
              residuals that would have to be further treated, and a treatability study would be
              required.  Implementation would be costly.                  !
       •      In situ chemical treatment was grouped into the general category "physical/chemical
              treatment" and eliminated for the same reasons as chemical extraction.
       •      Soil washing was grouped into the general category "physicaiychemical treatment" and
              .eliminated for the same reasons as chemical extraction.
       •      Soil flushing was grouped into the general category "physical/chemical treatment" and
              eliminated for the same reasons as chemical extraction.
       •      In situ biodegradation was grouped into the general category "'biological treatment,"
              which was not considered effective due to the heterogeneous type of waste found at
              the landfill.  In addition, a treatability study would be required and the implementation
              of the technology would be costly.  Biological treatment is most appropriate for hot
              spots, and no hot spots had been detected at this landfill.     |
       •      Solid-phase  biological treatment was grouped into the general category "biological
              treatment" and eliminated for the same reasons as in situ biodegradation.
       •      Slurry phase biological treatment was grouped into the general category "biological
              treatment" and eliminated for the same reasons as in situ biodegradation.
       •      Composting was grouped into the general category "biological treatment" and
              eliminated for the same reasons as in situ biodegradation.    !
       •      Vitrification was grouped into the general category "thermal treatment (on site)," which
              was eliminated because the site lacked the necessary space for its implementation.  In
              addition,  significant material handling would  be required, products of incomplete
              combustion  would be difficult to control, and implementation:would be costly.
  r"    •      Pyrolysis was grouped into the general category  "thermal treatment (on site)," which
              was eliminated for the same reasons as vitrification.

       No innovative technologies were included in RAA, therefore, none were eliminated during the
       three-criteria screening process or during detailed evaluation.
                                                                        '!,.''

11.     Which of the nine criteria were weighted most highly in selecting the technology? Did one of
       the nine  criteria eliminate the innovative technology from  being chosen?  If so, which one?
       Which of the criteria supported the use of an standard technology?  (
         '    •'      •   .         '               ••'•,'
       Cost-effectiveness was weighted most highly  in selecting a remedy.  The selected alternative,
       RAA-4B, offered the highest level of overall  protectiveness proportionate to cost. The  higher
       costs of  the other capping alternatives were not reflected by greater protection of public health
       and the environment.                                   .
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?   What risk level was selected to establish cleanup goals?

        For carcinogens an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
        was acceptable. For non-carcinogens a Hazard Index less than or equal to 1.0 was acceptable.
        An unacceptable risk of adverse non-carcinogenic effects was estimated for exposures of
        children to landfill soil.  Remedial action objects were developed to eliminate direct contact
        with on-site surface soils  and to reduce and control leachate generation.. No specific cleanup
        levels for soils/sediments were described.                          ;
                                               -4-
                                                                                               195

-------
    13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
           technology meet the cleanup goals?

           The cost for removal, disposal, and filling operations for this landfill would be approximately
           $100 million.  There were no hot spots to be removed or treated; low concentrations of
           contaminants are dispersed throughout the landfill.  Therefore, on-site and in situ treatment
           technologies were eliminated in the screening process due to excessive cost and
           impracticability. No innovative technologies were eliminated because of cleanup goals.  The
           standard technology selected could meet cleanup goals.



    14.     Were treatability studies conducted on the innovative technology or standard technology?

           No treatability studies were conducted.                                            -


    15.     What measures/criteria were used to compare alternatives?
                                                                                         \  ' :        -           i
                                                                      '                  " !                      i
           The following measures were used to compare the alternatives:

                  Cost effectiveness
                  Risk level achieved                                                                     .
                                                                                                     , •  .

   16.    How are alternatives compared?                                                              ^Mr   |
                                                             •-   .                                          • -**y'^ -1
                                                                                       '                  "l
          Of those alternatives that would reach a level of risk protective of human health and the
          environment, the selected alternative was the least costly  The1 higher costs of other
          alternatives would not provide a commensurate increase in the level of protection.

                                                                                                               I
                                                                                         1                      I
   17.    What technical considerations were factors in selecting a  remedy?  Were technical      ' .'             . '  i
          considerations primary in the selection of the remedy?

          The landfill is bordered by  two streams into which runoff from the landfill flows.  According
          to a study by the U.S. Army Corps of Engineers, the site is beyond the 500-year flood
          potential line.  The potential for localized flooding during heavy precipitation was recognized.
          However, hydrogeology did not play a primary role in remedy selection. Treatment
          technologies for landfills are considered to be feasible only if hot spots are found and if there
          is a small to moderate volume.  Furthermore, as stated in the NCP, EPA expects to contain                .
          large volumes  of low concentrations of material. The volume and nature of contamination at
          this site was primary in the  selection of a remedy.
196
-5-

-------
                                     Kin-Buc Landfill
                                           OU-2

                                Edison Township, New Jersey
                                          Region 2
GENERAL SITE INFORMATION
1.    ,  What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Sediment (mg/kg)

       PCBs         290
2.      What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       •      2,200 cubic yards of sediment
             Site! History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
10/81
7/92
9/28/92
             Background

PRP-lead
PRPs:  Kin-Buc, Incorporated and SCA
       Services, Inc.
FS prepared by: Wiehran,Engineering
       Corporation
3.      What type of site is this?
                                                    • i               1    :
       Municipal Landfill.  An inactive landfill that accepted municipal, industrial, and hazardous
       wastes.  The site is located in an industrial and commercial area.    i
TECHNOLOGY SELECTION
4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                             \
                                                           1         *
       Access restriction:     Fencing, land use restrictions              i
       Containment:         Capping (synthetic membrane, soil cover, composite, sediment
                            accumulation)                           !
       Chemical treatment:   Stabilization/solidification            .•;••'
       Thermal  treatment:    Incineration (rotary kiln, fluidized bed, infrared, commercial)
       Disposal:            Excavation, off-site disposal
                                             -1-
                                        197

-------
            Was an innovative technology considered in the FS? If so, which technology?

            Innovative technologies considered during the identification and screening of technically
            feasible technologies were:

            Biological treatment:  Bioremediation (in situ, on site)
            Phys/Chem treatment: Solvent extraction (Basic Extraction Sludge Treatment, Low Energy
                                 Solvent Extraction Process), detergent extraction, KPEG     ;
                                 dechlorination, APEG dechlorination, sediment washing, in situ
                                 vacuum extraction
            Thermal treatment:    In situ steam extraction, on-site low-temperature thermal treatment
                                 (X*TRAX, by Chemical Waste Management Inc.), in situ vitrification,
                                 on-site vitrification                         ,              \   •
    6.      What was the cost estimate for the innovative technology?

            During the initial screening process, in which technically feasible technologies are identified
            (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
            formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
            implementability, and cost) to  identify alternatives that merit a more detailed evaluation.  The
            estimated costs then are recalculated during an evaluation based on nine criteria established bv
            the NCP.

            Since RAA-2 was eliminated in the FS, alternatives were renumbered in the ROD and these
            new numbers are presented parenthetically below.        .    .   .

                    Cost Estimates for RAAs That Include Innovative Technologies
                                (selected remedial alternative is in bold)
Alternative
RAA-3C
(RAA-2C)
Innovative Technology
Excavation/solvent extraction, low-
temperature thermal treatment, or
dechlorination/disposal .
Estimated Costs
3 Criteria
$6,110,000
9 Criteria
$6,325,000
    7.      How did the cost(s) compare to standard technologies?

                     Cost Estimates for RAAs That Include Standard Technologies
                               (selected remedial alternative is in bold)
198
Alternative
RAA-1
RAA-2
Standard Technology
No action/long-term monitoring
Fencing/land use restrictions/long-term
monitoring/natural attenuation
Estimated Costs
3 Criteria
$300,000
$456,000
9 Criteria
$261,000
eliminated

-------
Alternative
RAA-3A
(RAA-2A)
RAA-3B
(RAA-2B),
RAA-4
(RAA-3)
RAA-5
(RAA-4)
Standard Technology
Excavation/dewatering/containinent in
OU-1 on-siite containment site
Excavation/dewatering/off-site disposal
Relocate stream/in situ single-layer
cap/fencing/land use restrictions
Limited stream, relocation/slurry wall/
cap/consolidate remaining sediment/
cap/fencing/land use restrictions
Estimated Costs
3 Criteria
$3,610,000
5,110,030
$5,315,000
1
$5,270,000
9 Criteria
$3,637,000
$5,268,000
$5,230,000
$5,009,000
8.      If a standard technology was chosen, why?
                                                  '      ' •         '  ' '  i      .
       RAA-3A was chosen because it protects human health and the environment since it will
       prohibit the migration of contaminants from the sediments into the aquatic and terrestrial food
       chain. The source of the contamination will be removed from direct contact with the wetlands
       that border the landfill and will be placed on site in a containment system.  This alternative
       can be implemented in the shortest amount of time and minimizes long- and short-term
       impacts on the wetlands.  RAA-3A utilizes reliable techniques, can be easily implemented, and
       is cost-effective.  While other, alternatives (RAA-3B and RAA-3C) would offer greater
       protection through treatment technologies,  their  higher costs would not be in proportion to
       their increase in protection. RAA-4 and RAA-5 were determined to be less effective and more
       costly.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If ah innovative technology was not chosen, why hot? At what stage was the innovative
       technology eliminated?                                           |

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of.
       effectiveness, implementability, and;cost; or during the detailed evaluation.
                    t                   :                -                '!    '
       Innovative technologies eliminated during the initial screening include the following:

       •      Detergent extraction (soil washing) was eliminated because its effectiveness has not
               been demonstrated.                                       j               • '     -
       •      Sediment washing (in situ) was eliminated because it would be impractical since the ,
               site is characterized by long, shallow stretches of contaminated sediment that would
               require extensive surface water control.                    ;
      , •      In situ  vacuum extraction was eliminated because it would not address PCBs.
                                              -3-
199

-------
         •      In situ steam extraction was eliminated because it would not address PCBs.
         •      KPEG dechlorination was eliminated because it has not been widely used on
                sediments and APEG dechlorination is mpre applicable.
         • -     In situ-vitrification was eliminated because the area is frequently saturated with water
                and the products generated by PCS pyrolysis are unknown and might be toxic (e.g.,
                dioxins).      -                                     .                    .
         "      On-site vitrification was eliminated because the effectiveness of the process on
                sediment has not been demonstrated and the  products generated by PCB pyrolysis are
                unknown and might be toxic (e.g., dioxins).
         •      In situ or on-site bioremediation was eliminated because no method has been
                developed that would address the site's PCBs.

         Innovative technologies eliminated during the screening of the three criteria include the
         following:

         •      None                           ,•   ,   .                                ,-•'...

         Innovative technologies eliminated during the detailed analysis include the following:

         "      Solvent extraction was eliminated because treatability studies would be too  costly.
         «      Low-temperature thermal extraction was eliminated because treatability studies would
                be too costly.
         •      APEG dechlorination was eliminated because treatability  studies would be too costly.


         Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion?  Which of the criteria supported the use of a standard technology?

         The criteria that were weighted most heavily in selecting a standard technology were  /
         protection of human health and the environment and cost.  While other treatment technologies
         would offer slightly more protectiveness than the chosen alternative, the chosen alternative was
         preferred because it was the least expensive.     ,

         Three innovative technologies were proposed in RAA-3C, but this alternative was eliminated
         because of the excessive costs of treatability studies and the high  unit cost associated with on-
         site treatment.
 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?
Contaminant      Cleanup Level (mg/kg)
                                                                 ARAR or Other Basis
                 Carcinogens
                 PCBs
                                             EPA" and EP Method"
               "EPA Guidance on Remedial Actions for Superfund Sites with PCB Contamination.
               bEPA's Interim Equilibrium Partitioning Method.
:00
                                               -4-

-------
       Was the innovative technology eliminated because of the cleanup goals? \Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include: •.  -.

       •  '  " 'None   .      '      '               -           •  .         '  'I  .    '   '

       Standard technologies eliminated because of cleanup goals include:     j

       •     , None                          '         •     •            :  .  .  .
 J4.     were treatability studies conducted on the innovative ^^^^

        No treatability studies were conducted.                           ,!,"'..'


. 15.    What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:        |

              Cost-effectiveness
        -     Time to design/construct/operate


 '16     How are measures compared?





         selected remedy could be implemented in the shortest amount of time.

                                                                         i
   17     What technical considerations were factors in selecting a remedy? Were technical   ,      ;
          considerations primary in the selection of the  remedy?              ;

          Two technical considerations were primary in the selection of an ^native . F** the
          medium of concern was sediment and its satura^^pr^ud^te ™«^
            chnoogies (vitrification, in situ sediment wash^.
          sedimenS were located in wetlands and two alternatives (RAA-4 and ^A-5) were
          eliminated, in part because they were invasive to wetlands.
                                                                                                201
                                                  -5- '      '              i

-------
                                Mattiace Petrochemical Co., Inc.
                                               OU-1

                                        Glen Cove, New York
                                              Region 2
     GENERAL SITE INFORMATION

     1.      What were the principal contaminants,
            contaminant levels, and media addressed in
            this feasibility study?

            Maximum concentrations of principal
            contaminants were:

            Soil (mg/kg)

            Tetrachloroethene           410
            1,2-Dichloroethane           4.2
            Carbon tetrachloride          3.8
            Methylene chloride           35
            Trichloroethene             37
            4-MethyI-l,2-pentanone      210
            Xylenes                     2,600
            Aldrin                      0.21
            Alpha chlordane             9.1
           Heptachlor epoxide          0.93
            1,4-Dichlorobenzene          12
           Chromium                   101
           Arsenic           •           16
           Beryllium                   2
           Antimony                   22
           Lead            '     •       204
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
7/85
5/86
7/90
6/27/91
             Background

EPA Fund-lead
PRPs:  N/A
FS prepared by: Ebasco Services
       Inc.           !
    2.      What volume of material is to be remediated?

           The volume of material to be remediated included:

           •      17,349 cubic yards of soil
           •      208 cubic yards of pesticide-containing soil


    3.      What type of site is this?

           Chemicals and Allied Products.  An inactive liquid storage and redistribution facility located in
           an industrial area.                                     '               >
202
                                               -1-

-------
TECHNOLOGY SELECTION

4.      What standard technologies were, considered for selection in this FS?

        Standard technologies considered during the identification and screening oiF technically feasible
        technologies were:
        Access restriction:
        Containment:
        Thermal treatment:
        Disposal:
Warning signs, fencing
Capping (clay; asphalt, concrete, synthetic mernbrame, multilayer)
Incineration (rotary kiln, circulating fluidized bed)
Excavation
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                     ,   I

        Biological treatment:   In situ biodegradation     .   ,   •            ;
        Phys/Chem treatment:  In" situ soil flushing, soil washing, in  situ vacuum extraction
        Thermal treatment:    Low-temperature thermal stripping, wet oxidation, in situ vitrification,
                              in situ steam stripping                      ;
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        theNCP.                                                      .  !.
                                                                         !
                                                                       .  i
                  Cost Estimates for FAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)     ;
Alternative .
RAA-3A
RAA-3B
RAA-3C- -
Innovative Technology
In .situ vacuum extraction of general
area/excavate all "hot spots"/off-site
treatment and disposal
In situ vacuum extraction of general
area and nonpesticide "hot spots"/
excavate pesticide "hot spots'Voff-site
treatment and disposal •
In situ vacuum extraction of general site
area and nonpesticide "hot spots"
Estimated Costs
3 Criteria
$18,100,000
,i
$3,230,000
$2,730,000
9 Criteria
$18,097,733
$3,500,242
$3,004,068
                                                                                    203
                                                -2-

-------
Alternative
RAA-4
RAA-5
RAA-7
Innovative Technology
In situ steam stripping/carbon
adsorption/underground storage tanks
(UST) removal/excavation/off-site
disposal/incineration
Low-temperature thermal treatment of
general site area and all "hot spots"
In situ bioremediation/UST removal/
off-site disposal
Estimated Costs
3 Criteria
$36,960,000
$11,340,000
$3,860,000
9 Criteria
eliminated
$11,344,791
eliminated
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-6
'" • • • 	 -'-- " ' "•
Standard Technology
No action
Multilayer cap/UST removal/off-site
disposal ,
Excavation/UST removal/off-site
disposal/incineration '
=========================================
Estimated Costs
3 Criteria
$246,000
$2,080,000
N/A
================
9 Criteria
$245,656
eliminated
eliminated .
' —
                                                                                                        D
8.     If a standard technology was chosen, why?

       A standard technology was not selected.
9.      If an innovative technology was chosen, why?

       RAA-3B was selected because it protects human health and the environment by reducing site
       soil contaminants to health-based cleanup levels through the use of in situ vacuum extraction
       and the excavation of pesticide "hot spots" not amenable to the vacuum extraction technology
       This remedy complies with all ARARs.  this alternative most rapidly reduces site risk'.
       associated with contaminated soil since it involves excavation and off-site disposal of high risk
       areas of contamination.  Treatment-related impacts will be minimal.  Short-term risk posed to
       site workers will be minimized through development and adherence to appropriate health and
       safety protocols. This alternative will be implementable in terms of the availability of
       necessary materials  and services, as well as  existing administrative requirements or restrictions
       The performance of treatability studies will  be required to determine the essential  design
       parameters for in situ vacuum extraction.  It is the cost-effective option since  its overall
                 204
                                              -3-

-------
       effectiveness is proportional to its cost. The removal and treatment of soil permanently and
       significantly reduces the toxicity, mobility, and volume of hazardous substances in the soil
       thereby permanently eliminating all the principal source threats of contamination at the site.
10.    If an innovative technology was not chosen, why not? At what stage Vyas the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; ,or during the detailed evaluation.
                                                            i         .   -f •'...••-•
       Innovative technologies eliminated during the initial screening include the following:
                                            •    ...                      i . •
                                                                      .  i
       •.      Wet oxidation was eliminated because it would not effectively eliminate the levels of
               contamination encountered at the site.
       •      Soil washing was eliminated because it would not be feasible given the small site area
               and the large system required for the soil washing technology1.
       •      In situ  vitrification was eliminated because it is not recommended for volatile organic
               contamination, the flammable organics found on the site might also present safety
               problems, and it would cost more than other in situ options.  "- :
       •      In situ  soil flushing was eliminated because it would  not be feasible since the clay
               lenses found throughout the site would preclude effective treatment of soils beneath
               these lenses.  Furthermore, slurry walls would have to be constructed to key into the
               horizontal barrier, mechanically isolating the contaminated source and applied ground
               water.                                               •     i"        ,      '
                                                                        !  '
       Innovative technologies eliminated during the screening of the three  criteria include the
       following:                                                       I
              .                                             -             '            £          -
       •      In situ  steam stripping was eliminated because it was unclear if contaminant levels
               would be reduced below ARAR criteria, particularly for the  semi-VOCs. In addition,
               implementation of the technology might present technical difficulties if the steam
               condensation in the contaminated soil could not be prevented.  To prevent this
               condensation, extraction and injection wells would have to be' spaced close together,
               which would escalate the cost.  Finally,  a pilot study would  bb necessary to determine
               the operating criteria and level of performance.              i
       •      In situ  biodegradation was eliminated because its implementability and effectiveness
               on these high levels of chlorinated organics has not been  demonstrated.  This
               alternative would be difficult to assess and, thus, the  long-term effectiveness in
               protecting human health and the environment can not be insured.  "The geology of the
               site does not seem to be  conducive to bioremediation due to the clay lenses inhibiting
               treatment beneath the lenses.  It would not treat all site contaminants."  Also, the
               concentrations of organic contaminants might be too  high and toxic to microbial
               populations and the low organic carbon  content of the soil (less than 1 percent) would
               not sustain the bacterial population.  The long-term effectiveness of this technique
               would be difficult to assess since this technology has not been proven effective for
               highly  chlorinated solvent waste.                           '•    '•     .
                                                                                      205
                                               -4-             :              •

-------
77.
72.
        Innovative technologies eliminated during the detailed analysis include the following:

        *      Low-temperature thermal treatment was eliminated because it would be more
               expensive to implement than the chosen alternative and it would not provide greater
               protection. Furthermore, its treatment-related impacts would be greatest since it would
               require excavating the largest amount of contaminated soil and it involves on-site
               thermal treatment of all contaminated soil.             '
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 The criteria weighted most heavily in selecting a remedial alternative were protection to human
 health and  the environment and cost. Of the three most protective alternatives (RAA-3B,
 RAA-3A, and RAA-5). RAA-3B was chosen because it is the least expensive alternative that
 offers the greatest protection.           ,

 Two innovative technologies, in situ vitrification and low-temperature thermal treatment, were
 eliminated, in part because of their high costs.        .


 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?               ,   <.'
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens - ^
vTetrachloroethene
Trichloroethene
Aldrin
Alpha chlordane
Heptachlor epoxide
0.6
0.07
6.04
0.5
0.07
Risk3
Risk
Risk
Risk
Risk
Noncarcinogens
Xylenes
4-Methyl-l,2-
pentanone
. 259
52.1
Risk
Risk
              "Soil cleanup levels were based on achieving an excess lifetime cancer risk of 1O6 for
              carcinogens and a Hazard Index of 1 for noncarcinogens.
                   206
                                             -5-

-------
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •     -In  situ steam stripping

       Standard technologies eliminated because of cleanup goals include:

       •      None                                                    j        -
                          •'   •                  •.'...     .         '   i   •    - '
                      •                    '               •    •   •         '
14.    Were treatability studies conducted on the innovative technology or standard technology?
           \           .                          ,                       ;'                '
       Treatability studies were not conducted.


75.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Cost-effectiveness                           .   . .
 16.     How are measures compared?                                    j
                                                                       "i .  .• •
        Despite its higher cost, RAA-3B was preferred over RAA-3C because the high cost
        cprresponded to an increase in protection to public health.


 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        No technical characteristics were primary in  selecting a remedial alternative; however, some
        were considerations. For example, soil washing was eliminated because it would be infeasible
        given the small size of the site, and in situ biodegradation was  eliminated because the clay
        lenses would inhibit remediation beneath them.                    i
                                                                                         207
                                                -6-

-------
                                    Nascolite Corporation
                                            OU-2

                                      Millville, New Jersey
                                           Region 2
 GENERAL SITE INFORMATION
 1.
2.
         What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:
        Soil (rag/kg)
        Acetone
        Trichloroethene
        Benzene
        Toluene
        Ethylbenzene
        Styrene  .
        Total xylenes
        2-Methylnapthalene
        Di-n-butylphthalate
        Butylbenzylphthalate
        Bis(2-ethylhexyl)phthalate
        Benzoic acid
        Polymethyl methacrylate
        Cadmium
        Mercury
        Copper
        Selenium
        Zinc                '
                                    10,700
                                    5
                                    5
                                    2
                                    13
                                    71
                                    29
                                    2    '
                                    15
                                    76
                                    19
                                    130
                                    33
                                    1,900
                                    58
                                    1 .4
                                    174
                                    6   ,
                                    868
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                     N/A
                     9/83
                     9/90
                     6/28/91
             Background

PRP-lead
PRPs:  Not listed
FS prepared by: Ebascb Services,
       Incorporated
                                                  3
             volume of material is to be remediated?

       The volume of material to be remediated included:

       •      8,000 cubic yards of unsaturated and wetlands soil

3.      What type of site is this?

       Rubber and Plastic Products.  An inactive acrylic and plexiglass sheet manufacturing plant
       located in a wooded area surrounded by residential and industrial property.           '

               208            '                              '   '•";  '   •'-..•;-  ,-••

-------
TECHNOLOGY SELECTION                    .-                       ^

4.      What standard technologies were considered for selection in this FS?  j

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                                                                         i      -  •
        Access restriction:     Fencing, deed and zoning restrictions               ,
     "   Chemical treatment:   Solidification/stabilization
        Physical treatment:    Size reduction, size separation                i
        Thermal treatment:    Incineration        ,
        Disposal:             Excavation, off-site disposal            ..,"!'.
5.      Was'an innovative technology considered in the FS? If so, which technology?
                                      -                                  i           . , .
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                  "      !

        Biological treatment:   Biodegradation, composting
        Phys/Chem treatment:  Soil flushing (solvent), soil washing (solvent), dechlorination, soil
                              yapor extraction                           |
        Thermal treatment:     Wet oxidation, radio-frequency heating, pyrolysis
 6.      What was the cost estimate for the innovative technology?               ~

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the costs were calculated during an evaluation baised on nine criteria
        established by the NCP:  long-term effectiveness and permanence; short-term effectiveness;
        compliance with ARARs; protectiveness of human health and the environment; reduction hi
        contaminant mobility, toxicity, or volume; implementability; cost; statp/support agency
        acceptance; and community acceptance.                            i

                  Cost Estimates for RAAs That Include Innovative Techniologies
                             (selected remedial alternative is in bold)     |   "                .

Alternative
RAA-2

Innovative Technology
Excavate soil with greater than
500 ppm of lead/soil washing/backfill
Estimate!
3 Criteria
N/A
1 Costs
9 Criteria
$2,627,000
                                                -2-
                                                                                      209

-------
 7.     How did the cost(s) compare to standard technologies?
9.
10.
                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-3
Standard Technology
No action
Excavate soil with 500 ppm of lead/
stabilization-solidification/ backfill
Estimated Costs
3 Criteria
N/A
N/A
PCriteria
$0
$2,237,000
8.      If a standard technology was chosen, why?

        RAA-3 was selected because it will reduce the risk from exposure to site contaminants through
        a solidification/stabilization process.  Solidification/stabilization will immobilize the
        contaminants by binding them in an insoluble matrix which will be covered by top soil.
        Institutional controls also will be implemented to deter activities that would disrupt the
        solidified mass.  (Additional remedies include off-site disposal of some soils.)  This alternative
        was preferred because it is easily implemented, and solidification/stabilization units and
        equipment are readily available for immediate use. Furthermore, solidification/stabilization is a
        proven technology and offers the greatest certainty that treated soils  will meet cleanup levels.
        If on innovative technology was chosen, why?

        An innovative technology was not chosen.
       If an innovative technology was not chosen, why. not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      Biodegradation (ex situ) was eliminated because the process would be inhibited by
              heavy metals.
              Composting was eliminated because it would be inhibited by heavy metals.
              Wet oxidation was eliminated because it would not be effective for remediating metals.
              Radio-frequency heating was eliminated because it would not be effective for
              remediating metal.
              Dechlorination was eliminated because it would not be applicable to site contaminants
              Soil flushing was eliminated because ground water could be contaminated.
              Soil vapor extraction was eliminated because it is not effective for organics in   •
              saturated and wetland soils.


                                              -3-      •                         '         :

-------
       »      Pyrolysis was eliminated because it would not be applicable to soil with high metal
              concentrations.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Soil washing was eliminated because it would be more difficult to implement, it would
              generate waste solution, and its effectiveness is less certain than that of the chosen
              alternative.                                               ;
11.
12.
 13.
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?

The criteria that were weighted most heavily in selecting a remedy were protectiveness of
human health and the environment and implementability!  Soil washing was eliminated
because it would be difficult to implement, requiring construction of a ground water treatment
system and custom-designed processing equipment.  Furthermore, wastewater would be
.generated which also would require treatment.                     ;
 What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?    :             -
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens ,
Lead
500
OSWER"
        "OSWER Directive No. 9335.4-02                         \'  ,'..


 Was the innovative technology eliminated because of the cleanup goals? Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:!
                                                                i
                                                 . .  '    . •       'i                .  '
 •      Soil washing

 Standard technologies eliminated because of cleanup goals include:  1 .

 •      None   •...-'''''••             "       'i
                                                                                       211
                                               -4-

-------
 14.
        Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were conducted to investigate two technologies: soil washing and vacuum
        extraction.  Studies showed that these technologies were potential options for remedial action.
15.
        What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

              Risk level achieved
              Proven reh' ability
16.     How are measures compared?

        Two alternatives were expected to meet cleanup levels and therefore reduce risk to acceptable
        levels.  Of these, the chosen alternative was preferred because there was less uncertainty
        associated with its effectiveness and implementation.

        Further, because no treatability tests were performed for solidification/stabilization a literature
        review  of the SITE program was carried out to determine the potential use of this technique.
17.
       What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
       Technical considerations were not primary in selecting a remedial alternative. The site's
       residential nature, however, was a factor in selecting a remedy.  There are several homes
       located on the boundaries of the site and over 60 homes located within a half-mile radius
       Because of the potential future risk of human exposure to site contaminants, the lower end of
       EPA soil cleanup levels was chosen.
           212
                                             -5-

-------
                            Naval Air Engineering Center
                                          OU-1

                                  Ocean City, New Jersey
                                  s      Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
 .      contaminants were:

       Site 10 - Soil (mg/kg)

       Petroleum hydrocarbons       10,820

       Site 16 - Soil (mg/kg)

       Toluene   '                 0.009
       2-Methylnapthalene          220
       Phenanthrene               0.41
       Beta-BHC                 " 0.026
       Petroleum hydrocarbons      14,097

       Site 17 - Soil/Sediment (mg/kg)

       Toluene                    0.007
      Petroleum hydrocarbons      0.227
      2-Butanone                 6
      4-Methyl-2-pentanone        29
      Toluene                   .34
      Ethylbenzene                13
      Xylenes                    139
      Phenanthrene                91
      Fluoranthene                18
      4,4-DDD               -    1.4
      Beryllium    ••              3,g
      Cadmium                   49
      Chromium                  1,270
      Lead                       870
      Mercury                    1.4
      Vanadium                  100
      Zinc                       427
      Cyanide                    26.6
      Petroleum hydrocarbons       36,898
NPL Proposed:
NPL Final:
FS:
Interim ROD:
             Site History
 N/A
 1987
 9/90
'2/91
             Background

Federal Facility
PRPs:  Navy, Depijutmient of Defense
FS prepared by:  Naval Energy and
    ,   Environmental Support Activity
       at the Naval, Air Engineering
       Center
                                                                                213
                                          -i-

-------
2.     What volume of material is to be remediated?                                 .   •   .

       The volume of material to be remediated included:

       «      A volume Was not provided.


3.     What type of site is this?                                          .

       Military.  An active naval base.  The OU-1 consists of three sites—#10, #16, and #17—which
       were used for barrel and gasoline tank storage, firefighting training, and an underground tank
       farm.  Land use in the area includes residential, woodland, wetland, and associated flood plain.


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       No initial screening was conducted. This study was of limited scope because it was for an
       interim remedy.  Only one source control technology was discussed (see below).


5.     Was an'innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                                     :

       Chemical treatment:    In situ soil flushing


6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  In  this case, the estimated costs were  calculated during an evaluation based on
       nine criteria established by the NCP.
           214
                                              -2-

-------
                 Cost Estimates for RAAs That Include Innovative Techitolojgies
                            (selected remedial alternative is in bold)
Alternative
RAA-2
Innovative Technology
Ground water pumping/removal of
free producf/recharge/in situ soil
flushing
. Estimated Costs
3 Criteria
N/A
l
9 Criteria*
N/A
       "Detailed cost estimates, including present worth costs, were not provided;, only direct capital
       and operation and maintenance costs were provided.                !
7.     How did the cdst(s) compare to standard technologies?             ^

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-3
, Standard Technology
No action
Ground water pumping, treatment, and
discharge to surface water
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria*
N/A
N/A
       'Detailed cost estimates, including present worth costs, were not provided; only direct capital
       and operation, and maintenance costs were provided.
8.      If a standard technology was chosen, why?

       A standard technology was not selected.
9.      If an innovative technology was chosen, why?                                     '

       RAA-2 was selected because it provides the greatest overall protection to human health and
       the environment through treatment of ground water and soils.  This alternative calls for the
       utilization of soil  flushing to address the contaminants in soil and ground water treatment.
       RAA-2 is an interim action and therefore  is intended to be a short-term fix.  If the interim
       remedial alternative proves to be effective, however, it will be incorporated and/or modified to
       become the final action.  RAA-2 reduces  the mobility and toxicity of ground water
       contaminants through ground water treatment.  RAA-^2 in the short-term will halt the  migration
       of contaminated ground water and residual amounts of floating product from entering the
       ecologically sensitive areas.  It also will stop the migration of contaminants to a tributary of
       the Manapaqua Brook,  which feeds a major recreational lake.  This action prevents the
       degradation of the aquifer and limits contaminant exposure risks to the population using the
                                              -3-
                                                                                     215

-------
        lake.  Furthermore, because soil flushing will be implemented, the remediation process will be
        accelerated. Soil flushing will aerate and enhance biological activity and contaminant
        decomposition.  This alternat: e involves conventional technologies with proven reliability.  It
        is cost-efficient and expected to attain ARARs.       ,


10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the .screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.          ,

        Innovative technologies eliminated during the initial screening include the following:

        •      An initial screening was not conducted

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                       .

        •      A three-criteria, screening was not conducted                           x

        Innovative technologies eliminated during the detailed analysis include the following:     ,

        •      None


11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        Protection of human health and the environment and short-term effectiveness were the criteria
        weighted most heavily in selecting a remedial alternative.  RAA-2 provides the greatest
        protection to human health since it addresses both ground water and soil. It also provides
        protection in the shortest amount of time.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR,  what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        Cleanup levels were not established.


13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                                ,

        Innovative technologies eliminated because of cleanup goals include:

              None                                                                                   /^^ ~\
             216
                                              -4-

-------
        Standard technologies eliminated because of cleanup goals include:
        •      None
                                                -  '                 •     ('      •'   -
14.     Were treatability studies conducted on the innovative technology or standard technology?
        Treatability studies were not conducted.
                                                      •,'''''
75.     What measures/criteria were used to compare alternatives?
        The following measures were used to compare the alternatives:
        -  ,     Time to design/construct/operate         '
               Preference for treatment (vs.  containment)
                               f         •  '        ,            .      '    !'     -
16.     How are measures compared?
       ••    -       .             ^                -.                . ^  ,     i
        RAA-2 was preferred because it will treat both the soil and ground water. Furthermore, the
        incorporation of in situ soil flushing acts to accelerate remediation.   T

17.     What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?               j
       Technical considerations were not primary in selecting a remedy.
                                                                                   217
                                             -5-  ,                      ,

-------
                            Naval Air Engineering Center
                                         OU-2

                                Ocean County, New Jersey
                                        Region 2
             Site History
                                fj
NPL Proposed:       N/A
NPL Final:           1987
FS:                 9/90
ROD:               12/90

             Background

Federal Facility
PRPs:  Navy, Department of Defense
FS prepared by:  Naval Energy and
       Environmental Support Activity
       at the Naval Air Engineering
       Center
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Toluene                    0.38
       Ethylbenzene                0.8
       Xylenes                    2.400
       2-Methylnaphthalene         4.783
       Naphthalene                 1.761
       4-Chloroaniline              0.356
       Isophorone                  0.246
       Cadmium                   81
       Copper                     515
       Lead        ,              357
       Petroleum hydrocarbons       4.031

       Sediments (mg/kg)

       Toluene              .     0.005
       PAHs                      0.88
       Petroleum hydrocarbons       0.221
       4,4-DDT                    2.7
       4,4-DDD                    12
       4,4-DDE                    0.31
       Cadmium                   10
       Copper                     340
       Chromium                  130
       Zinc                        385
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:         ,

       •      A volume was not provided. The contaminated soil is spotty and generally confined to
              the drainage swales between the test tracts and the former pump house and
              underground tank.
              218
                                           -i-

-------
3.      What type of site is this?                                         :
                                                   •  .    •        .      \ •
       Military. The site is located on an active air base and  consists of the launching end of five
       test tracks and ancillary facilities including a drainage system, a series of dry wells, and
       several underground storage tanks.  Land use in the area includes residential, woodlands,
       wetlands, and associated flood plain.                                          ,
TECHNOLOGY SELECTION
-"• ' "••     '"  '" ••'    ' '                    '                        .         %,                   _ '
    - .           '                :              '                  '   . !    \    ••    '          *
4.      What standard technologies were considered for selection in this FS?
                                                 '-            '         ~ \    '    •
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        No initial screening was conducted.  The scope of this study was limited because it was for an
        interim remedy.  Only one source control technology was discussed (see below).
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Physical treatment:     In situ soil flushing     .
        What was the cost estimate for the innovative technology?

        During ,the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria scbening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during 
-------
  7.     How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
         Soil/Sediment
            Alternative
                             Standard Technology
                           No action
                           Ground water pump-and-treat/ discharge
                           to surface water
                                                                 N/A         $550,000
                                                                               and
                                                                             $100,000
         'Detailed cost estimates, including present worth costs, were not provided; only direct capital
         and operation and maintenance costs, respectively, were listed.
                                                                         Estimated Costs*
                                                                                    9 Criteria
                                                                                                   '•fa^bfj^
 5.      If a standard technology was chosen, why?

        A standard technology was not selected.                               '.-'''••


 9.      If'an innovative technology was chosen, why?

        RAA-2 was selected because it protects human health and the environment through treatment
        of ground water and in situ soil flushing:  In situ soil flushing will aerate and enhance
        biological activity and contaminant decomposition.   The incorporation of in situ soil flushing
        hnLnhttSted .™atlve was Preferred because it provides the greatest overall protection to
        human health;and the environment through the treatment of both ground water and soil. In the
        short term this alternative prevents degradation of the aquifer and halts the spread of
        contaminated ground water and residual amounts of floating product from entering ecologically
        sensitive areas, the Manapaqua Brook and Pine Lake.  RAA-2 has the added benefit of
        flushing the soil of contaminants and increasing the  hydraulic gradient, thus speeding up the
        remediation process. The flushing actions help release contaminants adhering to the soil
        facilitating the interim  cleanup action.  RAA-2 reduces contaminant toxicity and mobility and
        involves conventional technologies with proven reliability.  It complies with all ARARs and is
        cost effective Since this is an interim action, long-term effectiveness cannot be addressed
        rZfrTi'   ,    acTtion  ;fueffective * wi" be incorporated and/or modified to become the final
        remedial action.  It will be implemented in 3 years
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the imUal screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
            220
                                             -3-
                                                                                                             -I

-------
       Innovative technologies eliminated during the initial screening include the following:

       •      An initial screening was not conducted                      !                 .
                                                                       • i       • -
       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      A three criteria screen was not conducted.                   i

       Innovative technologies eliminated during the detailed analysis include the following:
                      '                            -                     ' !
     1  •      'None        -  '   '       ,      •        . .       '          '.'!•
                                                                        i '                     *


11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
          ""•                     ,                                        i
                                                                     t ,  !-  ,        •
       The criteria weighted most heavily in selecting a remedial alternative were protection of
       human health and the environment and short-term effectiveness.  The selected alternative
       provides the greatest overall protection and the fastest remediation because it incorporates a
       soil  treatment technology.                                      '   i
                                                                       .-i,
                                    •                       '    .         i

12.,    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

    >   No cleanup goals were established for soil/sediments.

                                                                        -I

13.     Was the innovative technology eliminated because  of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                                j
                                                                        i      i  '
        Innovative technologies eliminated because of cleanup goals include: j

        •      None                                               _

        Standard technologies eliminated because of cleanup goals include:   !

        • •     None                 ,           '•    - •                   -j              .    ,  ,


14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.
                                                                                       221
                                               -4-    •      '-'''    J.              '•   :".

-------
 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Percentage risk reduction
             Time to design/construct/operate


 16.     How are measures compared?                                                      '

        RAA-2 was selected because it was more protective overall since it addressed both ground
        water and soil through treatment technologies.  Furthermore, this alternative will accelerate the
        remediation process because it addresses soil.


17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

       Technical considerations were not primary in selecting a remedy.
         222
                                            -5-

-------
                                National Lead Industry

                                          OU-2
                                 Pedricktown, New Jersey
Region 2
GENERAL SITE INFORMATION
1. ' What were the principal contaminants,
contaminant levels, and media being
addressed in this feasibility study?
• - • ' , , , : •
Maximum concentrations of principal
contaminants were:

Slag Piles (mg/kg):
Lead 252,010
Cadmium 1,460
Arsenic , 3,580
Antimony , 19,000
.
L*ad Oxide Piles (mgTkg):

Lead 437,000
Cadmium 650
Arsenic 614
Antimony 2,790


Site History

NPL Proposed: N/A
NPL Final: 9/83
FS: , 6/8/90
FFS, OU-2: 7/17/91
ROD, OU-2: 9/27/91
Background

EPA Fund-lead
PRPs: ML Industries, Inc., National
Smelting of New Jersey, National
Smelting land Refining Company,
Standard Metals Corp, and
generators;
FFS prepared by: EPA Region 2


2.      What volume of material is to be remediated?



       The volume of material to be remediated included:



       •      9,800 cubic yards of kiln slag in four piles

       •      200 cubic yards of lead oxide





3.      What type of site is this?



       Primary Metal Products. An abandoned secondary lead smelting facility. Pollution originated

       as a result of secondary smelting of lead bearing materials, including batteries.





TECHNOLOGY SELECTION



4.     What standard technologies were considered for selection in this FS?
                        ^    ' :           '              ."            ' -  I


       Standard technologies considered during the identification and screening of technically feasible

       technologies were:                 .

-------
        Access restriction:
        Chemical treatment:
        Physical treatment:
        Thermal treatment:
        Disposal:
                       Upgrading site security
                       Stabilization/solidification
                       Hazardous waste handling
                       Rotary kiln incineration
                       Excavation, hazardous waste handling, on-site disposal, off-site
                       disposal          ,                      ,
                       'o
5.
 Was an innovative technology considered in the FS? If so, which technology?

 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:

Phys/Chem treatment:  Ex situ waste washing, in situ waste flushing, hydrometallurgical
                      leaching process
Thermal treatment:     In situ vitrification, flame reactor
6.       What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness
       implementabihty, and cost) to  identify alternatives that merit a more detailed evaluation  'The
       estimated costs then are recalculated during an evaluation  based on the nine criteria established
       by tne NCP.                                                                           v


                Cost Estimates for RAAs That Include Innovative  Technologies
                            (selected remedial alternative is in bold)
          Alternative
        RAA-SP-2
        RAA-SP-3
        RAA-SP-4
                       Innovative Technology
                 On-site vitrificatidn/on-site or off-site
                 disposal                           .
                Off-site flame reactor
                On-site hydrometallurgic leaching/on-
                site or off-site disposal
                                                                     Estimated Costs
                                                                3 Criteria
                                                                $5,927,200
                                                                $4,215,100
                                                                $3,269,500
 9 Criteria
eliminated
                                                                         $4,215,100
$3,269,500
                                                                                                D
              224
                                             -2-

-------
 7.      How did the cost(s) compare to standard technologies?
                                                            I
                  .Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-SP-1
RAA-SP-5
RAA-SP-6
RAA-SP-7
Standard Technology
No action
On-site stabilization/solidification/
on-site disposail
Off-site stabilization/solidification/
off-site disposal
Off-site disposal
Estimated Costs
3 Criteria
$439,900
$3,465,200
' ' , !
- 1
$6,159,100
• i
$4,795,600
9 Criteria
$439,000
$2,303,100
eliminated
eliminated
8.      If a standard technology was chosen, why?

        The alternative RAA-SP-5 (on-site stabilization/solidification, on-site disposal) was selected
        because it is highly effective in treating inorganic contamination and will inhibit leaching of
        contaminants, on-site treatment reduces the chances of spillage of hazardous waste in transit, it
        does not involve handling of hazardous treatment chemicals, it is relatively simple to
        implement because it involves a one-step mixing and placement process, it is proven for
        CERCLA waste contaminated with metals, mobile treatment units are available, it is  expected
        that treated  materials would meet RCRA regulatory levels, it is the least expensive alternative,
        it is able to maintain permanent protectiveness over the long term, sen/ices and materials are
        readily available, and it satisfies the  statutory preference for treatment.'
                     '    --    i         .  •                   .   .             , '     ' -
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.
If an innovative technology was not chosen,  why not? At what stage was the innovative
technology eliminated?
                           -           -                 '           i ..   '        '
Innovative technologies could be eliminated  from the remedial technology  selection process at
three stages:  during the initial screening; during the screening of the RAAs; or during the
detailed evaluation.

Innovative technologies eliminated during the initial screening include Jhe following:
                                                                  'i                   ' •
•    -  .Ex situ washing/extraction was eliminated because available information indicate that
       soils from battery recycling operations, in general, are not highly responsive to soil
       washing conditions tested by EPA.  Contaminated materials that Imve undergone years
       of weathering may not readily re'spond to washing.  Lead cannot by physically
       separated  from the contaminated material by particle size separation. The presence of

     v           '          ••  •.     -3-           "           ;    ..'-:'..   225

-------
11.
              metals other than lead may makeJead extraction agents ineffective. Multiple steps of
              washing may be required.  Extracted solution needs extensive treatment.     ;

       Innovative technologies eliminated during the RAA screening include the following:

       •      On-site vitrification (RAA-SP-2) was eliminated because of the limitation in
              availability of the electric pyrolyzer, its lack of effectiveness in treating volatile metals,
              low processing capacity, lack of full-scale data, and high costs.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Flame reactor (RAA-SP-3) because its implementability  on a commercial scale has not
              been proven, it has not been  used at any Superfund site,  markets have not been
              identified for process by-products (may further increase costs), regulatory permits must
              be' obtained, implementation  depends on availability of an operating facility at the time
              of remediation, and it is  more expensive than the selected technology.  -

       "      Hydrometallurgical leaching (RAA-SP-4) was eliminated because long-term
              monitoring is required, uncertainty exists about its effectiveness and implementability
              since.it has not been  applied to  similar waste material, it is more  complicated than .the
              selected technology, it requires handling of hazardous materials, it may require a series
              of steps to leach  multiple contaminants, it would produce a slag and lead oxide residue
              that would require disposal, it would produce large amounts of liquid wastes that
              would require disposal, and it is more expensive than the selected technology.
Which of the nine criteria were weighted more heavily in selection of the technology? Did
failure to meet one of the nine criteria result in the elimination of the innovative technology?
If so, which criterion?  Which of the criteria supported the use of a standard technology?

For those alternatives that were considered protective and attained ARARs, the criteria
weighted most heavily were implementability and cost.  Implementability was most important
in the elimination of the flame reactor and hydrometallurgieal leaching alternatives.

12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
Arsenic
20 .
NJDEP
Noncarcinogens
Lead
Cadmium
Antimony
100
3
10
NJDEP
NJDEP '
NJDEP
                                                                                                            )
              226
                                               -4-

-------
              •New Jersey Department of Environmental Protection—Environmental Cleanup
              Responsibility Act Guidelines.

       For carcinogens an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable. For noncarcinogens a Hazard Index less than or equal to 1.0 was acceptable.
13.
Was the innovative technology eliminated because of the cleanup goals?  If a standard
technology was chosen, could it meet the cleanup goals?             |               ,
       No innovative technologies were eliminated because of cleanup goals.
       technologies selected could meet cleanup goals.
14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Total cost
               Proven reliability
               Single vs. multi-step treatment


16.     How are alternatives compared?

        The reliability of the off-site flame reactor (RAA-SP-3) and on-site hydrometallurgical
        leaching (RAA-SP-4) was a significant concern.  Flame reactors have not been proven on a
        commercial scale or at a Superfund site. In addition, markets have not been identified for the
        process byproducts, which could increase costs.  Hydrometallurgical leaching is a proven
        technology within the hydrometallurgical industry, however, the process has not been used for
        similar applications on waste materials.  In addition, it may require a series of steps to leach
        multiple contaminants and would produce  a slag and lead oxide residue, which Could require
        disposal.  The selected remedy, solidification/stabilization (RAA-SP-5) is  relatively simple to
        implement because a  one-step mixing and placement process is used. The technology is
        readily available and has been proven effective on similar waste sites  In, addition, the selected
        remedy is the least expensive treatment and disposal alternative for treating the slag and lead
        oxide piles.
                                                                  The standard
 17.     What technical considerations were factors in the, selection of a remedy?- Were technical
         considerations primary in the selection of the remedy?

                                                                      base
 .The NL Industries facility ,is in an industrial park, near a military
 from the Delaware River. A thin layer of topsoil overlies sandy
 heterogeneous nature of the waste matrices precluded the use of many
 such as those that flush contaminants from waste or entrap
                                                -5-
           and a mile and a half
     subsurface soils.  The
           in sjtu technologies,
contaminants, and therefore, was a
                                                                                        227

-------
primary consideration for their elimination. The nature of the waste was most important in
selection of a remedy.  Technical considerations did not appear to be primary in the selection
of a remedy at this site.
    228
                                   -6-

-------
                           Paisley Solvents and Chemical, Inc.

                                   Hempstead, New York
                                          Region 2
GENERAL SITE INFORMATION

7.      What were the principal contaminants,
       contaminant levels, and met
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Trans- l;2-Dichloroethene
       1,1,1-Trichloroethane
       Trichloroethene
       Tetrachloroethene
       Toluene
       Xylene
       Di-n-butyl phthalate
     '  Naphthalene
       Bis-(2-ethylhexyl) phthalate
       Fluoranthene
ninants,
addressed in
-
mcipal



82 . '
470
120
270
470
35
150
43

Site
NPL Proposed:
NPL Final:
FS:
ROD:

History
N/A
6/10/86
2/92
4/24/92
Background

PRP-lead


PRPs: Commander Oil Company, Pasley
Solvents

FS prepared by: Metcalf and Eddy,
Incorporated


120
110




       What volume of material is to be remediated?                    -L
                                . • ,              '         '            I '"  .  .
       The volume of material to be remediated included:                 !
                                                                     '
       •      13,000 cubic yards of soil                               ,|
                                    '         '                       Ji


       What type of site is this?     <        .                           ;              •

       Chemicals and Allied Products. A former tank farm that was used for the storage of oils,
       solvents, and chemicals. ,
TECHNOLOGY SELECTION
                                                                     i
4.     What standard technologies were considered for selection in this FS?
                                                                • •• .  i •   ' '   ' '  -  '
       Standard technologies considered during the identification and screening of .technically feasible
       technologies were:                 •           '  .       ,         '
       Access restriction:
       Containment:
Deed restrictions                         :
Cap (concrete, clay, and polymeric), dikes, berms
                                             -1-
                                                                                     229

-------
        Chemical treatment:
        Thermal  treatment:
        Disposal:
.In situ stabilization/solidification
 Off-site incineration, on-site incineration
 Excavation, off-site disposal at RCRA facility
        Was an innovative technology consideredin the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   In situ biodegradation, ex situ biodegradation
        Chemical treatment:    Soil washing (aqueous solutions), soil flushing (aqueous solutions)
        Physical treatment:     Soil vacuuming
        Thermal treatment:     In situ vitrification
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. The ;
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        bytheNCP.

        The RAAs discussed in the ROD are presented parenthetically under the list of alternatives.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)                        ,
Alternative
RAA-7 (RAA-5)
RAA-8 (RAA-6)
RAA-9
(RAA-7)
Innovative Technology
Soil flushing
Soil vacuuming
Soil vacuum extraction/soil flushing
if needed
Estimated Costs
3 Criteria
$185,000
$1,562,000
$1,649,000
9 Criteria
$185,000
$1,562,000
$1,649,000
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action/deed restrictions
Estimated Costs
3 Criteria
$66,000
9 Criteria
$66,000
         200
                -2-

-------
Alternative
RAA-2
RAA-3
(RAA-2)
RAA-4
(RAA-3)
RAA-5
RAA-6
(RAA-4) .
Standard Technology
Excavation of top 4 feet of soil/off-site
disposal/impermeable cap
Excavation of all contaminated soil/off-
site disposal
Excavation of all contaminated soil/off-
site incineration
Excavation of all contaminated soil/on-
site incineration
Excavation of all contaminated
soil/stabilization/sdlidification
Estimated Costs
i
3 Criteria
$5,09.5,900
i
$8,675,000
$43,970,000
$13,890,800
$2,105,000
9 Criteria
eliminated
$8,675,000
$43,977,000
eliminated
$2,108,000
8.      If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?                       1"

       The selected alternative includes soil vacuum extraction and/or soil flushing in conjunction
       with groundwater extraction and treatment.  This remedy was selected because: 1) it would
       immediately remove VOCs in the vadose zone and enhance biodegradation of semi-volatiles,
       as well as remove semi-volatile and metals with long term soil'flushing if needed, 2) easily
       implementable, 3) cost effective, 4) treatment reduces soil as a source of contamination to
       groundwater, 5) .avoids excavation.                        *          i
10.    If an innovative technology was not chosen, why not? At what stage wtis the innovative
       technology eliminated?                                            j
                       .                                                  i
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the tliree criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial  screening include the following:
                                                                    •-..}••'•     ••'.'-
       •      Soil washing was eliminated because it would involve excavation and subsequent
               treatment on-site; be more expensive than soil flushing; and would not offer any
               greater benefit.                                            j
       •      In situ  biodegradation was eliminated because it has not been proved effective for
^              chlorinated organics.  In addition, the site's heavy metals could inhibit microbial
               growth.
       •      Ex situ biodegradation was eliminated because it has not been demonstrated on a wide
               scale and because heavy metals could adversely affect microbial activity.
                                               -3-
                                                                                          231

-------
11.
12.
        »      In situ vitrification was not incorporated into a remedial alternative but the reason for
               its elimination was not discussed.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      None

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?

The most heavily weighted criteria in the selection of an innovative technology were
implementability; reduction of mobility, toxicity and volume; and cost effectiveness.


What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens ,
Trichloroethene
Tetrachloroethene
Bis(2-ethylhexyl)
phthalate
1
1.4
50
MCL"
MCL
NYAWQS"
Noncarcinogens '
Trans 1,2-
dichloroethene
1,1,1 -Trichloroethane
Toluene
Xylene
Di-n-butyl phthalate
Naphthalene
Fluoranthene
0.5
1
1.5
1.2
50
50
50
MCL
MCL ;
MCL
MCL
NYAWQS
NYAWQS
NYAWQS
              "No chemical-specific cleanup levels exist for soils, soil remediation levels protective
              of ground water were estimated based on Maximum Contaminant Levels (MCLs).
              bNew York Ambient Water Quality Standard.                              .
          232
                                      -4-

-------
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                                !

       Innovative technologies eliminated because of cleanup goals include: j'  -   ,             ' . '

       •      None                                                              :           ,

       Standard technologies eliminated because of cleanup goals include:

       •      None
                                                    1            ';      , i

14.    Were treatability studies conducted on the innovative technology or standard technology?    -.
               .                       .
       No treatability studies were conducted.


75.    What measures/criteria were used to compare alternatives?
               :            '                    .                       '                    ,
       The following measures were used to compare the alternatives:       i

     ,  -,.      Cost-effectiveness                                         |
       -       Preference for treatment (vs. containment)                               '
                                                                       . i,                   , j
                                         •                               ! •     "         •'     '
16.    How are measures compared?

       The selected alternative employs treatment technologies instead of excavation and disposal.
       Treatment technologies were preferred over excavation and disposal because site contaminants
       would be directly addressed and short-term risk would be reduced sinpe treatment would be
       conducted in ,situ.  Cost-effectiveness also was an important factor in (selecting the preferred
       alternative. Several alternatives (RAA-5 and RAA-6) offered a similar degree of protection,
       but would be much more expensive to implement; therefore, the chosen alternative was the
     ,  most cost-effective.                                              ;
 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?              !

        Site characteristics were not factors in selecting a remedy.           [
                                                                                          233
                                               -5-                      ., T  •      '

-------
                        Pittsburgh Air Force Base Landflll-022
                                           OU-1

                                   Plattsburgh, New York
                                         Region 2
 GENERAL SITE INFORMATION
L
        What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:
      Soil (rag/kg)

      DDD
      DDE
      DDT
      Waste (mg/kg)

      Carbon tetrachloride
      Chloroform
      Bis(2-ethylhexyl)phthalate
      PHCs
      Aluminum
      Cadmium
      Chromium
      Copper
      Iron
      Lead
      Manganese
      Silver
      Sodium
      Zinc
                                   16
                                   0.855
                                   3.505
                                   0.116
                                   18,000
                                   19,000
                                   1,700
                                   2,100
                                   128,000
                                   151
                                   412
                                   5,150
                                   130,500
                                   974
                                   7,355
                                   18
                                   23,300
                                   33,300
                                                              Site History
                                                  NPL Proposed:
                                                  NPL Final:
                                                  FS:
                                                  ROD:
                     N/A
                     11/21/89
                     7/92
                     9/93
             Background

Federal Facility
PRPs:  U.S. Air Force Strategic Arms  .,
       Command, Department of Energy
FS prepared by:  ABB Environmental
       Sendees, Inc.
2.     What volume of material is to be remediated?                          .         .

       The volume of material to be remediated included:

       •     524,000 cubic yards of fill material


3.     What type of site is this?                                                     ;

       Military.  An inactive landfill on an Air Force Base.  The site is located in a suburban ;area.

         234                           _,_

-------
TECHNOLOGY SELECTION            r                              |
                        ' •                        '                --'I'-     '           '  '
4.      What standard technologies were considered for selection in this FS?\

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                ;
                          '       '                 c          "      -   • •  '    '
        Containment:         Cover (soil, clay), hydraulic barrier cover     |   ,
        Chemical treatment:   In situ stabilization
        Thermal treatment:    Incineration                                !
        Disposal:             Excavation, disposal in permitted landfill, landfill closure
5.      Was an innovative technology considered in the FS? If so, which tecfmolpgy?

        Innovative technologies considered during the identification and screeiiing of technically
        feasible technologies were:    .                                    |
                                               -•- .        '           •     \  I-
        No innovative technologies were considered.
6.      What was the cost estimate for the innovative technology?
                                                                        I           . -   .
                                              " •   ' '         '      •     '!•'•'        •
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.                                j        -

       No innovative technologies were considered for remedial alternatives.


7.      How did the cost(s) compare to standard technologies?

    •     •        Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action .
Site grading/vegetative cover/landfill
closure
Low-permeability barrier cover system
Excavation/incineration
Solidification/stabilization
Estimated Costs
3 Criteria
N/A'
'N/A
i
. MA
N/A
N/A
9 Criteria
$676,000
$2,114,000
$5,062,000
eliminated
eliminated
                                              -2-
235

-------
8.     If a standard technology was chosen, why?                    ,                                         )
       The selected remedy was chosen because it permanently reduces risks to human health and the
       environment by eliminating, reducing, and  controlling exposures to human and environmental
       receptors through engineering controls.  The cover eliminates direct exposure to site
       contaminants.  It also reduces infiltration of precipitation into the landfill waste material and
       minimizes the potential for contaminant migration from waste materials. It was estimated that'
       the cover will reduce infiltration by 9 percent.  The cover will not pose short-term risk or
       cross-media impacts because of erosion controls, maintenance, and monitoring that will
       mitigate potential impacts. It is easily implemented, attains all ARARs, and is cost-effective.
9.     If an innovative technology was chosen, why?                             ,

       An innovative technology was not selected.


10,    If an innovative technology was not chosen,  why not? At what stage was the innovative
       technology eliminated?
 1                                            :
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                                         >"  •   '     •'       •    '•    :      ;
       Innovative technologies eliminated during the initial  screening include the following:
                                                             •
                                                                               .       •  •
       •      None                     ,                    '

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                                     !  .

       •      None                   •                                         '

       Innovative technologies eliminated during the detailed analysis include the following:

       •      None         '  .                                              '
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?, If so,
        which criterion? Which of the .criteria supported the use of a standard technology? .
                                        /              •
        The criteria that were most heavily weighted in selecting a remedial alternative were long-term
        effectiveness and cost.  The chosen alternative provides  adequate long-term protection at
        minimal cost.                                                                 ..       .
              236
                                              -3-

-------
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARARs, what was
       that ARARs?  What risk level was selected to establish cleanup goals?,
     '   '           '                        . '          •                  i -
       Cleanup levels were not established for this site because discrete source areas were not found.

                                                                        I
13.    Was the innovative technology eliminated because of the cleanup goalts? Could the standard
       technology meet the cleanup goals?                         ^       i

       Innovative technologies eliminated because of cleanup goals include:    i

        •   "  None    '                    •        •  .             .    i  •  .      '      !  ;.
     •                    ''                        '       ,               !
       Standard technologies eliminated because of cleanup goals include:   j                      '

        •  •    None,    ...          .           •                 '       j
           '                                 ''     , •.                         ' . •           •
                                          '  .      , •                '     i '
                                                                        I
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.                            I   ,


15.     What measures/criteria were used to compare alternatives?
                                                                        i                  ,
        The following measures were used to compare the alternatives:

       '         .-*--.         '                 .             '     I       '
             Cost-effectiveness                                          ^

                                                                        i        •

 16.     How are measures compared?

        The  chosen alternative was preferred because it offers longrterm effectiveness at the lowest
        cost.  RAA-3 would have offered slightly greater long-term effectiveness but it  would be more
        costly.  RAA-4 and RAA-5 were eliminated in the three-criteria evaluation because they would
        be too costly.
                                                              • .  .     -  i  ,   •,               '   •
            "*            '                      '                         i  .

 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?              ]

        No technical considerations were primary in selecting a remedial alternative.
                                                                                           237
                                                -4-.    '                  :

-------
                          Plattsburgh Air Force Base Landllll-023
                                             OU-3

                                     Plattsburgh, New York
                                           Region 2
                                                                  Site History
NPL Proposed:
NPL Final:
ROD:
                                                                  Background
                                                     Federal Facility                  .,
                                                     PRPs:  U.S. Air Force Strategic Arms  -.'
                                                            Command, Department of Energy
                                                     FS prepared by:  ABB Environmental
                                                            Services, Inc.
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Fluoranthene                122.5
       Naphthalene   •             2.725
       2-Methylnaphthalene          2.125
       Acenaphthalene              12.825
       Dibenzofuran                7.325
       Phenanthrene                0.144
       Anthracene                  25.7
      Pyrene                      105.5
      Benzo(a)anthracene           36.5
      Chrysene                    35
      Benzofluoranthene            37
      Benzo(a)pyrene        '      21.2
      Indeno(l,2,3-cd)pyrene        4.65
      Dibenzo(a,h)anthracene        2.8
      Fluorene                     12.325
      Benzo(g,h,i)perylene           3.85
      Aroclor 1254     .            0.19
      Silver                       0.013
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      406,000 cubic yards of landfill waste


3.     What type of site is this?

       Military.  An inactive landfill  on a U.S. Air Force base located in a suburban
                                                                          N/A
                                                                          11/89
                                                                          5/92
                                                                          9/92 ,


                                                                           area.
            238
                                            -i-

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                         _               ,       !
                                                                    1    •!      '         •'   ' •   '
       Containment:          Capping, surface water management, vegetation establishment
       Chemical treatment:    In situ stabilization/solidification             i
       Thermal treatment:     Incineration                               ,
       Disposal:             Excavation, off-site disposal                 ,
                                                                        l
                                               "'     •    •              ' i  '  •    '  •'   .  .  .•'
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                  .      i

       No innovative technologies were considered.
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case the estimated costs were calculated during an evaluation,based on nine
        criteria established by the NCP. No innovative technologies were incorporated into remedial
        alternatives.                      '                              I
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)     i
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Site grading/vegetation establishment
Low permeable barrier cover system
Excavation/incineration
In situ stabilization/solidification
Estimated Costs
3 Criteria
N/A
N/A
N/A
.. N/A
N/A "
9 Criteria
$793,0000
$1,975,00
$3,586,000
eliminated
eliminated
                                               -2-
                                                                                       239

-------
3.      If a standard technology was chosen, why?                ,          <•

        The selected remedy was preferred because it offered the greatest protection to human health
        and the environment and the greatest long-term protection. The selected alternative minimizes
        risk associated with exposure to site contaminants in surface soil through the implementation
        of a low permeable barrier cover.  This remedy also minimizes the infiltration of precipitation,
        thereby reducing the potential for contaminant migration to ground water and for leachate
        discharge to wetlands.  The implementation of the remedy will not pose any unacceptable
        short-term risk or cross-media impacts. The selected remedy meets all ARARs.  The selected
        remedy is cost-effective since the overall effectiveness will be proportional to its costs. .
9.
JO.
If an innovative technology was chosen, why?

An innovative technology was not selected.


If an innovative technology was not chosen,  why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

*      None

Innovative technologies eliminated during the screening of the three criteria include the
following:
                                                                                i
*      None                                  ,            .                     •'.'''

Innovative technologies eliminated during the detailed analysis include the following:

•      None
       Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?, If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment and long-term effectiveness were the criteria
       most heavily weighted in selecting a remedial alternative.  Though it was more costly and
       more difficult to implement, the selected alternative was preferred because it offered the
       greatest protection and long-term effectiveness of all of the alternatives considered in the
       detailed analyses.                                            ,                    :
          240
                                              -3-

-------
 12.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?  ,   '
                                  1          -                    I '                 '  -

Cleanup goals were not established for soil contaminants. Chemical-specific ARARs are not
available.  Risk-based cleanup goals were not established for LF-023 source control because
discrete source areas (e.g., hot spots) were not found.                !
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                               i
                                                                 -.      - i          .
        Innovative technologies eliminated because of cleanup goals include:
        1 '                                                               i   ,      •       '
                                                                        !'
        •  .    None     .                   :                           I

        Standard technologies eliminated because of cleanup goals include:

        •      None                                ,       -
14.     Were treatability studies conducted on the innovative technology or standard technology?
                          •  :  •                        '                  ,1  '  •
                                                                        .1       '   ,     '
        Treatability studies were not conducted:   :
75.     What measures/criteria were,used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved                                         \ .    . ''
        -  .   Total cost     •                                             'i
             Short-term risk                                              '.
             Proven reliability        ,                                   I


16.     How are measures compared?                              •"      ],-                   '
                                 .                                  •      i
        The chosen alternative was preferred because it reduces site risks  more than other alternatives
        included in the detailed analyses, thereby providing the greatest protection. Other technologies
        (stabilization,  incineration) were eliminated after the three criteria analyses.  Stabilization was
        eliminated because it would be very expensive, would require a treatability study, and would
        be difficult to implement.  Incineration was eliminated because it  would be very expensive and
        could pose'short-term risk  during excavation.      -                 i
17.     What technical considerations were factors in selecting a remedy? Were, technical
       considerations primary in the selection of the remedy?     "    .     {
                        -.                  . .                             i
       No technical considerations were primary in selecting a remedial alternative.  The unknown
       depth of contaminants and the lack of any identified hot spots caused the elimination of
       incineration and stabilization.                         ' " ;. .         .1   '•"..,
                                              -4-
                                                                             241

-------
                             Preferred Plating Corporation
                                          OU-2

                                  Farmingdale, New York
                                         Region 2
GENERAL SITE INFORMATION

I.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
       Soil (mg/kg)

       Arsenic
       Beryllium
       Cadmium
       Chromium
       Copper
       Lead
       Magnesium
       Nickel
       Silver
       Zinc
       Cyanide
       Chloroethane
       1,1 -Dichloroethane
       1,1,1 -Trichloroethane
       1,2-Dichloroethene
       Tetrachloroethene
       Trichloroethene
2.5
1
468
1,890
151
158
7,900
141
14.9
243  .
678
5.9
20
270
15
5.4
5
                             Site History
                 NPL Proposed:
                 NPL Final:
                 FS:
                 ROD:
                     10/15/84
                     6/10/86
                     7/92
                     9/28/92  .
             Background     '

EPA Fund-lead
PRPs:   Preferred Plating Co.
FS prepared by: Malcolm Pirnie,
       Inc.                   i
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      7,200 cubic feet of soil                              .


3.      What type of site is this?

       Electroplating.  A former metal plating company located in a light industrial area.
          242
                                            -i-

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS? |      ,
                                                                       i. -                     •
     '.  Standard technologies considered during the identification and screening of technically feasible
;       technologies were:

       Chemical treatment:   Fixation, stabilization/solidification
5.      Was an innovative technology considered in the FS?  If so, which technology?
                                •     .         - '               ,  -    '   i'-
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                       I
                                                        '               i    ' '
                                                                       i '
        Chemical treatment:   Oxidation/reduction, in situ soil flushing, ex, situ soil washing
        Thermal treatment:    In situ vitrification
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically.feasible technologies are identified
        (prior to the formulation of'RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial  alternative is  in bold)
Alternative
RAA-3
RAA-6
RAA-7
Innovative Technology
Ex situ soil washing
In situ soil flushing via vertical ground
water wells
In situ soil flushing via horizontal
ground water wells '
i
Estimated Costs
3 Criteria
rt/A ;
IR/A
1
N/A
9 Criteria
$2,761,150
eliminated
eliminated
                                               -2-
                                                                                      243

-------
  7.      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-4
RAA-5
=====
Standard Technology
No action
Excavation/off-site stabilization and
disposal
In situ stabilization by in situ soil
mixing
In situ stabilization by jet grouting
'
•
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
." 	 Li i i- .^^^— ^^_
—^ ^SSi
9 Criteria
$132,947
$1,423,700
eliminated
eliminated
==^ —
 8.      If a standard technology was chosen, why?

        RAA-2 was selected because it protects human health and the environment. RAA-2 is
        designed to be protective by eliminating cross-media impacts posed by highly contaminated
        site subsurface soil to the underlying ground water.  Since the site is located in a sole source
        aquifer area, restoration of the aquifer quality is crucial.  By removing the contaminated soil
        this alternative ensures that no leaching of contaminants will occur. The elimination of cross-
        media impacts will facilitate future implementation of the ground water restoration program.
        The selected remedy treats the site's inorganic and organic contaminated soil  through ;
        excavation, off-site stabilization/solidification, and disposal.  This alternative provides long-
        term effectiveness and permanence since the potential for future release of contaminants to the
        underlying  ground water will be permanently eliminated. Extraction and treatment of the, site's
        soil reduces the toxicity and mobility of the site contaminants.  No short-term adverse impacts
        and threats  to human health and the environment are expected as the result  of implementing
        the selected remedy.  To minimize and/or prevent worker exposure to  contaminants, personal
        protective equipment will be utilized. This alternative complies with all ARARs and is cost
        effective since it fully protects human health and the environment at the least  cost.
9.
If an innovative technology was chosen, why?

An innovative technology was not selected.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                                           ;

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
        244
                                       -3-

-------
      Innovative technologies eliminated during the initial screening include the following:
          -          '                       •           ,                  j   '''.•'•
      •      In situ vitrification was eliminated because it would use a great deal of energy and
              require special equipment and trained personnel.  In addition, the vitrified soil would
              compress when cool, leaving large voids in the soil.  Unless voids created by
              vitrification can be backfilled as cooling is taking place, the building slab and
              foundation could be undermined.                           ;
       •      Oxidation was eliminated because it would not be effective for metals  given their high
              oxidation state.
       •      Reduction was eliminated because it has only been used for hiexavalent chromium  and
              hexavalent selenium, which are not contaminants of concern at this site.

      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                                            :

       •      In situ soil flushing with vertical wells was eliminated because the technology could
              increase ground water contamination!  Constructing an effective collection system  in
              the highly permeable site sands would be difficult.  In addition,  the affected area
              cannot be easily identified or controlled; associated environmental and public health
              risks could be increased.                                    .
       •      In situ soil flushing with horizontal wells was eliminated because this technology has
              not been previously used for the  extraction of heavy metals in soil and due  to the
              problems associated with recovering flushing fluids in highly permeable  site soil.
                                                              1    '     'I               , •
       Innovative technologies eliminated during the detailed analysis include the following:

       •      Ex situ soil washing was eliminated because it would be too costly and its
              implementability is somewhat uncertain.  The technology has been implemented only
              on a limited basis in the United States and would, therefore, require treatability studies.
              Further, this technique has been used in Europe on a full-scale basis only for the
        '      removal of heavy metals.  The high cost associated with this technique is based on the
              assumption that the treatment facility necessary for performing this process  would be
              available only overseas by the'implementation time; therefore, transportation costs
              would be high.                                            i


77.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,   ,
       which criterion? Which of the criteria, supported the use of a standard technology?
             •      .  '  -                          .                       i
       The criteria most heavily weighted in selecting a remedial alternative; were protection to human
       health and the environment and cost. The selected remedy was the least expensive treatment
       option.                                                    >     I .  '
                                                                        L,               • '
       In situ soil flushing was eliminated because it would be infeasible to;implement because of
       highly permeable site soil. Ex situ soil washing was eliminated because its costs would be too
       high and its implementability is uncertain. ..-.'•              |   '        ,
                                                                                  245

-------
 12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        No cleanup levels were established.                                             :
                                                                                                            I


 13.    Was the innovative  technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?       .                                                            j

        Innovative technologies eliminated because of cleanup goals include:                                ,

        •       None

        Standard technologies eliminated because of cleanup goals include:

        •       None                                 .


14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.


75.     What measures/criteria were used to compare alternatives?                                  ".-.'"'

        The following measures were used to compare the alternatives:                     :             MB   |

             Cost-effectiveness                                                                              :
             Proven reliability             /                                                         '      '   ;|
             Capital costs                                                             ;


16.    How are measures compared?

       RAA-2 provides protection to human health and the environment at the least cost.  RAA-3
       might provide equal  protection and would provide a higher degree of long-term effectiveness,
       but it would be more costly, and its implementability was less certain. The capital cost for
       RAA-3 would be high  based on the assumption that the treatment facility necessary for
       performing this process would be available only overseas and not in this country by the time
       the remedy would be implemented.  Therefore, transportation costs would be high. The
       implementability of RAA-3 was less certain because the proposed technology, ex situ soil
       washing, has been performed only on a limited basis in this country.  A treatability study
       would be necessary to determine the exact nature of the extraction fluid to be used for
       contaminant removal and most of the operating treatment facilities for soil washing are in
       Europe.
               246
                                             -5-

-------
17.     What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?              !
                                                                       i     . •           , ' -
       While some technical site characteristics were considerations, they were not primary in
       selecting a remedial alternative.  The high soil permeability would make it difficult to control
       in situ soil flushing and implementation of this technology could causle ground water
       contamination.  In situ stabilization could not be implemented because it would require the
       demolition of existing buildings.        .•    -
                                               -6-
                                                                                     247

-------
                                       Ramapo Landfill
                                             OU-1

                                      Ramapo, New York
                                           Region 2
                                                  j)
 GENERAL SITE INFORMATION
 1.      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

        The remedial action objectives for this site
        were based on containment and reduction of
        contaminated landfill leachate into ground
        water, rather than treatment of soil
        contaminants. Soil samples were collected
        and analyzed during the remedial
        investigation and were included in the risk
        assessment; no. principal soil contaminants,
        however, were addressed in the FS.
 2.      What volume of material is to be
        remediated?
              Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1982
9/83
9/91
3/31/92
             Background

PRP-lead
PRPs:  Town of Ramapo
FS prepared by:  URS Consultants;
       Inc:
        The volume of material to be remediated included:

        •      2 million cubic yards of fill material


3.      What type of site is this?

       Municipal Landfill.  An inactive landfill site.  A portion of the site is currently being used as a
       trash compaction and transfer facility by the town of Ramapo.


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?
                                                                                   i

       Standard technologies considered during the identification and screening of technically'feasible
       technologies were:                                                            '

       Access restriction:     Fencing, posting, deed restrictions                              '
       Containment:         RCRA cap, multimedia cap,  soil cap
       Physical treatment:     In  situ solidification/stabilization
       Thermal treatment:     Incineration
       Disposal:             Excavation, disposal at a RCRA facility
         248
                                            -1-

-------
                                                                       •hnoloKV?
5.       Was an innovative technology considered in the FS? If so, which tec

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:    In situ bioreclamation
        Chemical treatment:    In situ soil flushing
        Thermal treatment:     In situ vitrification
6.      What was the cost estimate for the innovative technology?
                                                                       I   •'      '  -
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives thai: merit a more detailed
        evaluation.  For this site, the estimated costs were first calculated during an evaluation based
        on nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
x       reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance. The costs were recalculated in the ROD.
           i                            -               . •  '   ••          '
           ^                            '                                !
        No innovative technologies were included in remedial action alternatives.
        How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)    '
Alternative
RAA-1-
RAA-2
RAA-3
RAA-4A
Standard Technology
No action/ground water and air
monitoring
Posting/fencing/deed restrictions/
optional alternative water supply/
ground water and air monitoring
Posting/fencing/deed restrictions/
ground water extraction wells/ improved
leachate collection and discharge to
POTW/ground water and air monitoring
Multimedia cap/deed restrictions/
ground water extraction wells/improved
leachate collection and discharge to
POTW/ground water and air
monitoring/passive gas collection and
venting
Estimated Costs
9 Criteria
$3,260,000
$3,970,000
1
$2,530,000
$27,530,000
i
t
,
i
ROD
$3,260,000
$3,380,000
to
$3,970,000a
$6,206,000
to
$14,210,000"
$29,190,000
to
•$35,760,000b
                                               -2-
                                                                                     249

-------
Alternative
RAA-4B
RAA-5
RAA-6
Standard Technology
Same as RAA-4A, except modified
multimedia cap
Multimedia cap with soil side slopes/
deed restrictions/ground water
extraction wells/improved leachate
collection and discharge to POTW/
ground water and air monitoring/
passive gas collection and venting
Multimedia cap/deed restrictions/
alternate water supply/ground water
extraction wells/improved leachate
collection and discharge to POTW/
ground water and air monitoring/ active
gas collection and venting
Estimated Costs
9 Criteria
$23,230,000
$19,800,000
$33,533,000
— - 	
ROD
$24,890,000
to
$30,880,000"
$21,410,000
to
$28,050,000"
eliminated
        The higher end of the cost range reflects the additional cost for an optional alternative water
        supply.
        bThe higher end of the cost range reflects the additional cost for optional items such as
        alternative water supply, ground water pretreatment, and treatment of landfill gases,   :
                                                                                        !

8.      If a standard technology was chosen, why?

        The selected remedy includes: cap installation, ground water extraction, leachate collection,
        perimeter drain, deed restrictions. This remedy was selected for the following reasons: 1) it
        mitigates ground water contamination by reducing the amount of infiltration into the landfill,
        2) size of the landfill, 3) reduction .of vapors, 4) prevents erosion and surface water runoff 5)
        reduces contact with contaminated soil, 6) steep slopes limited capping options, 6) technically
        implementable.                           ,

        RAA-4B was selected as a contingent remedy.
9.
If an innovative technology was chosen, why?

An innovative technology was not chosen.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?           '

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of  ;
effectiveness, implementability, and cost; or during the  detailed evaluation.
         250
                                              •o-

-------
       Innovative technologies eliminated during the initial screening include the following:

       •      In situ bibreclamation was eliminated because in situ treatment is not considered
              feasible for the depth of waste at the landfill (up to 80 feet),  j
       •      In situ soil flushing was eliminated because in situ treatment is, not considered feasible
              for the depth of waste at the landfill (up to 80 feet).        •'.-[•
       •      In situ vitrification was eliminated because in situ treatment is not considered feasible
              for the depth of waste at the landfill (up to 80 feet).
                                                                        j-
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                        !
                                                          •'             [  '
       •      None                                                     !  ,                   ,

       Innovative technologies eliminated during the detailed analysis include the following:
                                                                        i
       »      None        •                                      •.      T
11.     Which of the nine criteria were weighted most heavily in selecting the .technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily was implementability.  Though capping does not fully
       comply with action-specific ARARs for landfill closure, it was chosen because it meets the
       remediation objectives and is the easiest to implement.              j
                                                                        I

12.     What cleanup goals were selected? If the cleanup goal was basedonanARAR,  what was that
       ARAR?  What risk level was selected to establish cleanup goals?

       No soil cleanup goals were developed because the primary objective is to reduce the migration
       of contaminants to ground water. As a result, containment, instead of treatment,  was the
       preferred remedial action.
                                                      ,'.''.   |              '
       For carcinogens an excess upper bound individual  lifetime cancer risk of between 10  to 10"
       was acceptable. For  nbncarcinogens a Hazard Index less than or equail to 1.0 was acceptable.
       AH  human health risk assessment results were within EPA acceptable levels.
                                    ,  ,                         .'•!"•

13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                                ;
                                                                        i • •       '             '
       Innovative technologies eliminated because,of cleanup goals include: j  .
                                                                        i •
        »      None        •              "                      •'!•'••••
                                                                        i        • •

        Standard technologies eliminated because of cleanup goals include:   ;

        •      None


                                                                                     251
  -   •  .             •  -        "       „          -4-                       i

-------
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
 15.
 What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

       Proven reliability
       Waste left in place/institutional controls
16.     How are measures compared?

        Although the large size of the landfill and the steep slopes make capping the site challenging
        the selected technology is implementable and vendors are readily available for construction
        Containment met the remedial objectives to reduce human and animal contact/prevent
        inhalation of vapors and mitigate leachate to ground water.
17.
 What technical considerations were factors in selecting a remedy?  Were technical
 considerations primary in the selection of the remedy?

 Technical considerations were primary in the elimination of the three innovative technologies
 considered.  The depth of debris (80 feet) at the landfill precluded use of these technologies
 In addition, the landfill's steep side slopes would make implementing a multimedia cap
difficult and more expensive.
         252
                                             -5-

-------
                               Roebling Steel Company
                                          OU-2

                                   Roebling, New Jersey
                                         Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
2.
       Slag(mg/kg)

       Arsenic
       Carcinogenic PAHs
       Chromium (total)

       Soil (mg/kg)

       PAHs
                           64
                           35
                           2,210
                            13
                                                               Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FFS, OU-2:
                                                   ROD,  OU-2:
                                                                 12/82
                                                                 9/83  ,
                                                                 6/91
                                                                 9/26/91
                                                                Background
                                                                    i

                                                   EPA Fund-lead
                                                   PRPs:  Roebling Steel Company, CF&I
                                                          Steel Corporation, unidentified
                                                          other PRPs,
                                                   FS prepared by: Ebasco Services
                                                          Incorporated
What volume of material is to be
remediated?     •                           ,

The volume of material to be remediated included:

•      1,458,000 cubic yards of slag material
•      160 cubic yards of soil
3.     What type of site is this?                           .

       An inactive production facility for steel wire and cable, as well as recent use for various
       industrial operations.                                       .    l   ."•''.-
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?\
                                      r                .              '  /
                                                                    \    .  •  •            '  -
       Standard technologies considered during the identification and screening of technically .feasible
       technologies were:                                            ,I      :
       Access restriction:     Site fencing, deed restrictions, monitoring
                                            -1-
                                                                                253

-------
         Containment:

         Chemical treatment:
         Thermal treatment:
         Disposal:
                        Clay cap, synthetic membrane cap, chemical sealants, soil cap,
                        multimedia cap, vertical barriers
                        In situ solidification, stabilization (of slag areas)
                        Incineration                                       -
                        Off-site disposal at RCRA landfill, on-site disposal at RCRA landfill,
                        off-site disposal in nonhazardous waste disposal site, on-site disposal'
                        in nonhazardous waste disposal site
 5.
 Was an innovative technology considered in the FS? If so, which technology?

 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:

 Biological treatment:   Biodegradation
 Phys/Chem treatment:  Supercritical fluid extraction, soil washing and extraction, in situ
                       flushing
 Thermal treatment:     In situ vitrification
6.
 What was the cost estimate for the innovative technology?

During the initial screening process, in which technically feasible technologies are identified
(pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
formulated, costs are estimated as part of a three-criteria screening process (effectiveness
implementability, and cost) to identify alternatives that merit a more detailed evaluation 'The
estimated costs then are recalculated during an.evaluation based on the nine criteria established
by the NCP.


All innovative technologies were eliminated during the initial screening and, therefore  have no
associated cost estimates.                                                        ':
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
       Slag
Alternative
RAA-SA-1
RAA-SA-2
RAA-SA-3A
Standard Technology
No action
Limited action
Excavation/on-site stabilization/
backfilling of hot spots/soil or
vegetative cover of entire slag area
Estimated Costs
3 Criteria
$318,200
$404,300
$9,684,500
9 Criteria
$397,700
. $505,400
$12,105,600
           254
                                             -2-

-------
Alternative
RAA-SA-3B
RAA-SA-4
RAA-SA-5
RAA-SA-6
Standard Technology
Excavation/off-site treatment and
disposal of hot spots/soil or vegetative
"cover of entire slag area
Containment — multimedia (RCRA) cap
Excavation/on-site stabilization
(solidification)/backfilling
In situ solidification
Estimated Costs
3 Criteria
$25,136,800
$21,12o,300
$46,055,700
i
i-
$175,969,200
9 Criteria
$31,421,000'
$26,407,900
eliminated
eliminated
       1 RAA-SA-3B underwent detailed evaluation in the FFS but was not considered in me ROD.
       A Proposed Plan was not available to explain this difference between ithe EPS and ROD.
                                                   1       •          i

       Soil     •         -         '       '         • •     , '     '       |
Alternative
RAA-PS-1
RAA-PS-2
RAA-PS-3
Standard Technology
No action
Limited action
Off-site treatment and disposal
Estimated Costs
3 Criteria
$78,900
$199,000
$91,600
9 Criteria
$98,600
$248,800
$114,500
8.      If a standard technology was chosen, why?

       Slag

       The selected technology, RAA-SA-3 (on-site stabilization of hot spots, capping), was selected
       because it is protective, attains ARARs, provides the most permanence of the alternatives
       because highly contaminated areas would be treated, reduces the mobility of contaminants, and
       affords the highest level of overall effectiveness in proportion to its cbst.  RAA-SA-1 and
       RAA-SA-2 would not be protective of human health and the environment. RAA-SA-4 might
       pose the same risks as RAA-SA-1 or RAA-SA-2 in the long run if the cap system fails or
       deteriorates. RAA-SA-3 and RAA-SA-4 would provide overall protection by reducing the risk
    '   of public exposure, but RAA-SA-3 was chosen because it would be more cost-effective and
       more permanent than RAA-SA-4.
                                                                    i
       Soil       .      ;,      .-,-.'.'      '•.'            j  •   .

       RAA-PS-3 was selected to remediate park soils because it would provide overall protection of
       human health and the environment by removing the contaminated material and reducing the
       risk of public exposure. In addition, there are ho O&M costs for this alternative. , RAA-PS-1
       and RAA-PS-2 would not provide protection of human health and thb environment or attain
       ARARs since contaminated soil would remain  in place.            i
                                                                                  255
                                             -3-

-------
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.                                                           ^J


10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                                          ;       '  .

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening by the three criteria of     '
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies  eliminated during the initial screening include:

       •      Soil washing and extraction was eliminated for the slag material and soil because the
              type and number of contaminants would require a variety of washing and extraction
              solutions and a number of washing stages to reduce contaminant levels. In addition,
              the volume of park soil is too small for a washing and extraction system.  Capital and
              O&M costs  would be high.  Bench-scale tests would have to be performed to!
              determine if cleanup levels could be reached.
       •      Supercritical fluid extraction was eliminated because it is not applicable to the
              numerous types of heavy metals  in the slag material and park soil.  In addition, the
              volume of park soil is too small for a  supercritical fluid extraction system.  Capital and
              O&M costs  would be  high. The technology has not been demonstrated at a hazardous
              waste site.                                                     ,-                       —   -
       •      Biodegradation was eliminated because it is not applicable for treating metal                     J
              contaminated materials in the slag material. The volume of park soil is too small for a
              biological treatment system. It is a developmental technology that would require
              extensive, bench and pilot scale testing. Uncertainty exists regarding its effectiveness
              in remediating PAH contaminated materials.  Capital and O&M costs would be
              moderately high.                                                         ;
       «      In situ flushing was eliminated for the  slag material because its non-homogeneous
              nature (fractured) would be difficult to control the flushing process and achieve
              cleanup  levels. It would not be feasible for the park soils because of the small areas
              of contamination and it is only surface soil.  The numerous types of metals and PAHs
              in the slag material would require several types of flushing solutions and many stages
              to remove the contaminants. Capital costs would be moderately high and O&M costs
              would be high.
       •       In situ vitrification  was eliminated because many of the heavy metals in the slag
              material would vaporize, requiring air emissions controls. Dewateririg of the slag area
              would be difficult because of the  fractured nature of the material and the material
              abuts the Delaware River.  It would not be feasible for the park soil because  the
              contamination is located in two small separate areas near the surface. Capital costs
              would be moderately high and O&M costs would be high.              '    ".

      No innovative technologies were eliminated during the three-criteria screening process or
      during the detailed analysis.
           256
                                            -4-

-------
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                                    •]:'•'
       For those alternatives that were protective and attained ARARs, the criteria weighted most
       heavily is selecting  a remedy were long-term effectiveness and cost.  Innovative technologies
       were not included in any RAA, therefore, they were not evaluated using the nine criteria.
       Innovative technologies were eliminated during the initial screening based on effectiveness,
       implementability, and cost.                                       ;
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR?   What risk level was selected to establish cleanup goals?     '
                    • '.  '  •            •               '                  i   .    '
                        , .                          ^             .     (
              Soil Remediation                                         ,
                   Contaminant      Cleanup Level (rag/kg)     ARAR or Other Basis
                Carcinogens
                Carcinogenic PAHs
           10
       NJDEP
              "New Jersey Department of Environmental Protection Interim Soil Action Levels,
              February 1990.                    •                   '   i
              Slag Remediation
                   Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
                Carcinogens
                Arsenic
                Carcinogenic PAHs
                Chromium VI
          20
           10
     100 (total Crb)
       NJDEF
       iNJDEP
       NJDEP
                Noncarcinogens
                Chromium IJJ
     100 (total Crb)
       NJDEP
              "New Jersey Department of Environmental Protection Interim Soil Action Levels,
              February 1990.      '                                     i      .
              "Total chromium is assumed to be 95 percent Chromium IJJ arid 5 percent Chromium
              VI.

       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10;4 to 10"6
       was acceptable. For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
                                                                                    257
                                            -5-

-------
13.     Was the innovative technology eliminated because of the cleanup goals? If a standard
        technology was selected, could it meet the cleanup goals?                                        ^&   \

        Innovative technologies were eliminated primarily because of the various types (organic and
        inorganic) of contaminants and the volume of contaminated material rather than cleanup goals.
        The standard technologies selected, ex situ stabilization and capping, could meet cleanup goals.


14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


75.     What measures/criteria were used to compare alternatives?    '   •   >

        The following measures were used to compare the alternatives:

               Impact on  neatby populations                                            ;
               Preference for treatment                                       ,                              .
               Total cost                                                               !~
               Waste left in place


16.     How are alternatives compared?                                                                       :

                                                                                                    ^1^ '
       The selected remedy will significantly reduce the risks associated with exposure to slag                   '
       contaminants and reduce contaminant migration to the environment through treatment and
       containment. The selected remedy will reduce any potential risks associated with direct
       exposure to the contaminated park soil through excavation and off-site treatment and disposal.
       Of the two alternatives for remediating the slag material that were considered protective, RAA-
       SA-3 was less costly that RAA-SA-4 and included treatment (rather than containment) of
       highly contaminated material.  Of the alternatives for remediating the park soil, other than no
       action, RAA-PS-3 was less costly than RAA-PS-2 (limited action) and would not leave waste
       in place.

                                                                               '       •
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       The  slag area, which borders the Delaware River shoreline, ranges in  thickness from several
       inches to 30 feet, with the thickest deposits generally located adjacent to the river. Depth to
       groundwater ranges from zero to 10 feet. The river is subjected to tidal influence (6.9 feet).
       The  slag fill contains both organic and inorganic contaminants and is  believed to contain
       numerous fissures and voids due to its very coarse nature.  Although the proximity to Aground
       water and to the Delaware River led  to the elimination of some technologies, the volume  and
       nature of the contaminated material was  more important in selection of a remedy. Technical
       considerations could not be considered primary in remedy selection at this site.
             258
                                              -6-

-------
                    Rowe Industries Ground Water Contamination
                              Town of Sag Harbor, New York
                                         Region 2
 GENERAL SITE INFORMATION

 1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)  •      ,  •'

       Trichloroethene             0.098
       1,1,1-Trichloroethane        0.008
       Tetrachloroethene           67
       Xylenes                    0.001
       Toluene                    0.001
       Ethylbenzene               0.002
       Acetone            •        0.006
       Methylene chloride           0.001

       Dry well sediment (mg/kg)

       Tetrachloroethene           9.1
       1,1,1-Trichloroethane        53
       Trichloroethene             27
       1,1-Dichloroethane          2,4
       1,2-Dichloroethene           28
       Xylenes                    20
       Toluene                    27
       Ethylbenzene               2,3
       Acetone                    19
       Methylene chloride           0.44
       Freon 113                   230
NPL Proposed:
NPL Final:
FS:
ROD:
             Site History
N/A
6/10/86
7/92
9/30/92
             Background
                 i
PRP-lead
PRPs: Nabisco Incorporated, Sag
       Harbor Industries
FS prepared by:  LEG Engineering
       Services, Inc.
2.     _ What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      365 cubic yards of soil/sediment
                                                                               259
                                           -i-

-------
3.      What type of site is this?

        Electrical Equipment.  An active electronic devices manufacturing facility located in an
        industrial area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?              :

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
                      Deed notations
                      Slurry-cutoff wall, capping
Chemical treatment:    Stabilization/solidification (lime-based, portland cement, thermoplastic,
                      in situ)
Physical treatment:     Heavy metals separation
Thermal treatment:     Incineration (rotary kiln, mobile electric fluid wall, infrared, plasma,
                      fluidized bed), dehydration        .
Disposal:             Disposal (on-site landfill, off-site  landfill)
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Composting/landfarming, liquid-soil contact digestion, white rot
                              fungus, in situ biodegradation, off-site biodegradation, augmented
                              bioreclamation
        Phys/Chem treatment:  Supercritical water oxidation, liquified gas solvent extraction, solvent
                              extraction, in situ soil flushing, soil washing, Basic Extraction Sludge
                              Treatment Process (BEST), soil vapor extraction
        Thermal treatment:     Pyrolysis, low-temperature treatment, in situ radio frequency, in situ
                              vitrification, steam stripping
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated  costs are then recalculated during an evaluation based on nine criteria established by
        the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.
          260
                                               -2-

-------
                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
        Ten-year present worth to 30-year present worth.
Alternative
RAA-4
Innovative Technology
Soil vapor extraction/monitoring
Estimated Costs
3 Criteria'
'$144,000 to
$218,000
9 Criteria
$144,000 to
$218,000
 7.      How did the cost(s) compare to standard technologies?             i

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-5
Standard Technology
No action
Deed notation/physical restrictions/
monitoring
RCRA cap/deed notations/physical
restrictions/monitoring
Excavation/off-site disposal
Estimated Costs
3 Cnteria"
$0
$162;000to
$281,000
$111,1000 to
$164,000
$245,000 to
$245,000
9 Criteria
$0
$162,000 to
$281,000
$lll,000(to
$164,000
$245,000 to
$245,000
       Ten-year present worth to 30-year present worth.
8.      If a standard technology was chosen, why?

       RAA-5 was selected because it provides the greatest protection to human health and the
       environment by removing a continuing threat to ground water posed by the on-site
       contaminated soils.  In addition, it protects the sole source aquifer drinking water supply. Soil
       with concentrations  exceeding the recommended soil cleanup levels wiill be excavated and
       disposed of off site. This alternative is  the most protective because it ensures that all the
       contaminated soil and  any residual contamination will be completely removed from  the site.
       The selected remedy provides a very high degree of long-term effectiveness and permanence
       because contaminated  soil will be removed and the contaminated areas! restored.  The
       excavation  of soil will effectively reduce the mobility  of contaminants by eliminating this
       pathway as a continuing source to ground water. The toxicity and volume of contaminated
       soil will also be reduced. The short-term effectiveness and implementability of this  remedy is
       also high in that it will be conducted in  a short time and have minimal effects on the  -
       surrounding community. It  complies with all ARARs  and  is cost-effective. Though the
       selected remedy is the most expensive option, it provides the greatest overall protectiveness.
                                             -3-
                                                                                     261

-------
P.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial  screening include the following:

        •      Low-temperature thermal treatment was eliminated because the site's soil contains
               more than 10 percent organics.                   :
        •      Composting/landfarming were eliminated  because the site's soil contains chlorinated
               solvents that are not readily biodegradable and cannot be treated  by this process.
        "      Liquid-soil contact digestion was eliminated  because the site soil contains chlorinated
               solvents that are not readily biodegradable and can not be treated by this process.
        »      White rot fungus was eliminated because it has not been proved in field applications.
        •      Basic Extraction Sludge Treatment was eliminated because the site's soil does not
               contain oil.                                       ,   ..
        •      Solvent extraction "was eliminated because obtaining a solvent or solvent mixture
               capable of extracting the contaminants of concern at the site^ would be highly1 unlikely
               and might be prohibitively expensive.
        •      In situ biodegrodation was eliminated because the site's soil contains chlorinated
               solvents which are not readily biodegradable and cannot be treated by this process.
        •      Off-site biodegradation was eliminated  because the site's soil contains chlorinated
               solvents which are not readily biodegradable and cannot be treated with this process.
        •      Augmented bioreclamation was eliminated because the site's soil contains chlorinated
               solvents which are not readily biodegradable and cannot be treated with this process.

        Innovative technologies eliminated during the screening of the three criteria of the technologies
        include the following:

        •      Soil washing was eliminated because of high costs.
        "      Super critical water oxidation was eliminated because of high costs.
        •      Liquified  gas solvent extraction was eliminated because the size of the equipment
               needed and the  mobilization/demobilization effort required to implement the
               technology would be best suited for sites  larger than Rowe.
        •      In  situ soil flushing was eliminated because obtaining a solvent or solvent mixture
               capable of extracting all of the site's contaminants would be highly unlikely and might
               be prohibitively expensive.
        •      In  situ radio frequency was eliminated because the implementability of this technology
               would be limited by many factors, including soil type, moisture content, depth of
               contamination, boiling points of contaminants; continuous monitoririg and experienced
               field personnel would be required;  and  costs would be high.
        •      In  situ vitrification was eliminated because of high costs.
        •      Steam stripping was eliminated because of high costs.

             262
                                                -4.                   '

-------
       •      Pyrolysis was eliminated because it would be inappropriate for treating the site's soil
              constituents.                                   ,
                                    ,^        ;.         -*- --         '        i..
       Innovative technologies eliminated during the detailed analysis include the following:

       •      Soil yappr extraction was eliminated because obtaining a vendor to implement the
              technology for such as small area (20 ft by 20 ft) makes it infeasible.
11,    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment and long-term effectiveness were the criteria
       weighted most heavily in selecting a remedial alternative. The chosen  alternative was
       preferred because it offers the greatest protection and permanence-even though it is the most
       expensive alternative. One other alternative, soil vapor extraction, that would offer almost
       comparable protection and permanence and would utilize an innovative technology was   »
       eliminated because it would be difficult to find a vendor.            ;                      .

       Many innovative technologies were eliminated at least in part because  of cost. These include
       solvent extraction, soil washing, super critical water oxidation, in situ soil flushing, in situ
 .  .   . radio frequency, in situ vitrification, and steam stripping.
12.     What cleanup goals were selected? If the cleanup goal was based oh\an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?     j
                     Contaminant
Cleanup Level (mg/kg)   ARAR or Other Basis
                 Carcinogens
                 Benzene
                 Tetrachloroethene
                 Trichloroethene
         0.05
          1.5
Ground water3
Ground water
                              Ground water
                 Noncarcinogens
                 Xylenes
                 Ethylbenzene
                 Toluene
                 1,1 -Dichloroethane
                 1,1,1 -Trichloroethane
                 1,1 -Dichloroethene
                 1,2-Dichloroethene
          1.2
          5.5
          1.5
          0.2
          0.5
          0.5
Ground water
Ground water
Ground water
Ground water
                              Ground water
Ground water
 Ground water
                                               -5-
                                                                                    263

-------
                "Soil cleanup levels were generated to restrict the concentration of compounds in the
                soil to a level that would ensure that contaminants in the soil do not further
                contaminate ground water.
                                                                                                    .Ji
 13.
                                                                  \
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 "       None

 Standard technologies eliminated because of cleanup goals include:

 •       None                                      ,                                   .
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 Treatability studies were not conducted.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Preference for treatment (vs.  containment)
               Waste left in place/institutional control
                                                                                              m
16.     How are measures compared?

        The chosen alternative was preferred because it provides the greatest protection and long-term
        effectiveness. Institutional controls would not be protective since contaminants would continue
        to leach to ground water. Institutional controls would offer a lesser degree of long-term
        effectiveness since the likelihood of adequately enforcing deed notations and physical
        restrictions cannot be guaranteed.  Containment would not be as protective because it would
        only minimize infiltration and reduce leachate.  It also would offer a lesser degree of Ipng-
        term effectiveness by eliminating the exposure pathway.  Diligent maintenance of the cap and
        long-term monitoring would be required for it to be fully effective.  Additionally, capping
        would not fully eliminate the possibility of contaminated soil acting as a source of ground
        water contamination if horizontal flow is present within some portion of the lower 12 ft of
        contaminated soil.
17.
Wltat technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

No technical considerations were primary in selecting a remedial alternative.
            264
                                              -6-

-------
                                    Sinclair Refinery
                                          OU-2

                                   Wellsville, New York
                                         Region 2
GENERAL SITE INFORMATION
1. What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
- • ' . ' . .
Maximum concentrations of principal • _ .
contaminants were:

Surface Soil (mg/kg)

Arsenic 43
Lead 1,190

Subsurface Soil (mg/kg)

t Arsenic ,88
" Lead 791


Site His

NPL Proposed:
NPL Final:
FS:
ROD:
-
Backgn

PRP-lead '
PRPs: Atlantic Richfi
FS prepared by: Ebasi
Incorporated

- ,
Xylene 26 • .
Naphthalene 3


tory'

1981
9/83
3/91
9/30/91 :

mnd


ild Company
;o Services


,

''
2.     What volume of material is to be'remediated?

       The volume of material to be remediated included:

       •     7,710 cubic yards of surface soil
       •     44,000 cubic yards of subsurface soil



3.     What type of site is this?

       Petroleum Refining. A former refinery. .


TECHNOLOGY SELECTION

4.   .  What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                  .
                                                                                    265
                                             -i-

-------
        Surface Soil

        Access restriction:
        Containment:

        Thermal treatment:
        Chemical treatment:
        Disposal:

        Subsurface Soil

        Access restriction:
        Containment:

        Chemical treatment:
        Thermal treatment:
        Disposal:
Public awareness program
Clay cap, asphalt cap, concrete synthetic membrane/multilayer cap,
soil cap                             ,
Incineration
Solidification/fixation (in situ and ex situ), thermoplastic solidification
Excavation, on-site disposal, off-site disposal at RCRA landfill
Public awareness program
Clay cap, asphalt cap, concrete synthetic membrane, multilayer cap,
soil cap, sheet piling, grout curtains, slurry walls
Solidification/fixation (in situ and ex situ)
Incineration
Excavation, on-site disposal, off-site disposal at RCRA landfill
        Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                               .     ' ' :

        Surface Soil

        Chemical treatment:   Soilwashing
        Biological treatment   Biodegradatipn (ex situ)                                 :

        Subsurface Soil

        Biological treatment:  In situ bioremediation, landfarming
        Phys/Chem treatment:  Soil washing, soil flushing, vacuum vapor extraction
                                                                     m
D.
6.      What was the cost estimate for the innovative technology?                        ;

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
       estimated costs then are recalculated during an evaluation based on the nine criteria established
       bytheNCP.                                      .

       No innovative technologies were proposed for surface soil remediation.
                266
                                              -2-

-------
               Cost Estimates for RAAs That Include Innovative Technologies

                          (selected remedial alternative is in bold)       i
      Subsurface Soil
=====
Alternative
RAA-2G
RAA-2D
RAA-2E

Innovative Technology
Vacuum vapor extraction/off gas
treatment/long-term monitoring
In situ soil flushing/ground water pumping
and treatment/long-term monitoring
In situ bioremediation/ground water
pumping and treatment/long-term
monitoring . 	 	
Estimated Costs
3 Criteria
$3,750,600
$7,930,600
j
1-
$3,310,600
i
i
1.
i
9 Criteria
$2,766,100a
eliminated
eliminated
       This decrease in estimated cost was not explained.  It reflects a decrease in the estimated

       initial cost.                           •
   -.-•••                           •          .        .           -
7.      How did the cost(s) compare to standard technologies?    '           |   \



                 Cost Estimates for RAAs That Include Standard Technologies

                           (selected remedial alternative is in bold)
       Surface Soil
Alternative
RAA-1A
RAA-1B
RAA-1C
RAA-1D
RAA-1E

Standard Technology
No action/public awareness/institutional
controls/long-term monitoring
Soil cap/revegetation/long-term monitoring
Consolidation of soils in CELAb/fixation/
RCRA cap/backfill/long-term monitoring
In situ fixation/long-term monitoring
Excavation/off-site landfill disposal/backfill
Estimated Costs
3 Criteria
$263,500
i
$390,000
$562,000
$6i25,600
$1,862,000
9 Criteria
$743,000a
$1, 583,200"
$1,505,000"
$2,394,600"
eliminated
        "Large changes in estimated cost between the two screening processes were not explained.

        'They reflect increases in both initial costs and O&M costs.

        bCentral elevated landfill area.            »
                                                                                       267
                                               -3-

-------
         Subsurface Soil
Alternative
RAA-2A
RAA-2B
— ==^=
Standard Technology
No action/public awareness/institutional
controls/long-term monitoring
Excavation/backfill/off-site disposal at
RCRA landfill
Estimated Costs
3 Criteria
$353,600
$17,192,200
=====::
9 Criteria
$882,100
$22,869,800
t
 8.      If a standard technology was chosen, why?                                 ',

        The selected alternative for surface soils, RAA-1C (on-site fixation) would be protective,
        provide a permanent remedy, involve simple construction and implementation using proven
        technologies, restores contaminated areas to ambient conditions, reduces mobility of
        contaminants, satisfies the preference for treatment, and is cost effective. RAA-1A (no action)
        would not be protective of human health and the environment and would not attain cleanup
        goals.  RAA-IB (capping) offered a less protective cap than the chosen alternative and would
        not meet cleanup goals. RAA-1D (in situ fixation) would not be as effective in the long term,
        would not return the area to natural conditions, and the technology was less readily available '
        RAA-IE (off-site landfill) would not be cost-effective.

        The selected alternative for subsurface soils, RAA-2A (no action) would be cost effective in
        that it provides protection of human health and the environment because there are no known
        exposure pathways, would not disturb subsurface soils, and would restrict future site access.
        All other alternatives (off-site disposal,  soil vapor extraction) were considered excessive in
        both protection and cost.                         ,
9.     If an innovative technology was chosen, why?

       No innovative technologies were selected.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

Surface Soil                                   _

•      Soil washing was eliminated because no commercially available package units exist to
       implement this complex and labor-intensive technology.
•      Biodegradation (ex situ) was eliminated because  the contaminants of concern, lead and
       arsenic, are not amenable to this type of treatment.
             288
                                       -4-

-------
Subsurface Soil

•      Soil washing was eliminated because the presence of volatile,! seraivolatile, and metal-
       contaminants would make the development of a washing solution to remove all
       contaminants difficult. In addition, due to the low partition coefficients of the
       semivolatile and metal contaminants, remediation would require excessive washing and
       would produce substantial amounts of waste materials requiring further treatment.
•      Land/arming was eliminated because it would not address heavy metals.  It would
       require excavation, which would be very disruptive to the current site users. To
       facilitate the treatment beds required for the amount of soil, the current site owners
       would lose use of their property until the soils were treated to cleanup goals.       •
       Excavation, treatment, and disposal would have to be performed in accordance with
       LDRs.
                                              '                  '    •  v
Innovative technologies eliminated during the, screening of the three criteria include the
following:                       ,                               :
                         •             "             '        '     !     ' '  •
Surface Soil                                                    j

•   i'  None             •                  •                     I'        '             "' .,
                                                                i             •
Subsurface Soil                                     .            j
                                                                ,|._       ^         , ,
•      In situ soil flushing (RAA-2D) was eliminated because it has j not been demonstrated to
       be effective for complete removal of VOCs from soil.  Treatability studies would be
       required.  Uniform and reliable distribution of the surfactant would be difficult due to
       the nature of the site; extensive subsurface foundations and piping.  It would provide
       no substantive improvements in effectiveness or implementability than soil vapor
       extraction.
•      In situ bioremediation (RAA-2D) was eliminated because it has not been demonstrated
       to be effective in remediating unsaturated soils.  Treatability tests would be required.
       Uniform and reliable distribution of oxygen and nutrients would be difficult due to
       areas of low subsurface permeability and underground foundationi and piping. Pockets
       of untreated soil may remain on site.                       f                     .
                                                   -        ' :     '
Innovative technologies eliminated during the detailed analysis include the following:

Surface Soil                                                    }  '    .

«      None              .            •'--".•        j  '

Subsurface Soil
                             ...           ,           . •     i
                                                                !      '          '
•      In situ vapor extraction was eliminated because it-is ineffective for the cleanup of
       metals and its implementability is questionable in regard to.achieving cleanup levels
       due to areas of low permeability and low porosity in subsurface soils.  No risks
       presently exist from subsurface soils due to the lack of a known exposure pathway,
       and subsurface soils do not appear  to be acting as a significant source of groundwater
       contamination. Institutional controls could provide sufficient; protection to human
       health and the environment.


                                                                            269
      ••-',.          -5-                      f

-------
 77
72.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 Surface Soil                                               -                    .

 Of the alternatives that were protective of human health and the environment, long-term
 effectiveness and cost were the most heavily weighted criteria in the choice of a remedy.  One
 innovative technology, in situ soil flushing, was eliminated because it was not cost-effective.

 Subsurface Soil

 Of the alternatives that were protective of human health and the environment, implementability
 and cost were the most heavily weighted criteria.                                 '-'•""


 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that,
ARAR?  What risk level was selected to establish cleanup goals?                   \

       Surface Soil                                                            i
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Lead
• 25 .
1,000
Risk*
OSWER"
              "EPA directed that an arsenic soil cleanup level, corresponding to a carcinogenic risk
              of 1  x 10"5, be used at the site.
              bEPA OSWER Directive (EPA, 1989) interim soil cleanup level for lead.     :
              Subsurface Soil
Contaminant
Carcinogens
Arsenic
Lead
Benzene
Xylene
Naphthalene
Cleanup Level (ug/kg)
ARAR or Other Basis

25
1,000
0.024
0.98
0.72
Risk
OSWER
Model8 and MCL
Model and MCL
Model and MCL
              "For some contaminants, the Summers model was used to estimate the contaminant
              concentrations in the soil,  which will produce ground water contaminant concentrations
              at an acceptable level based on Maximum Contaminant Levels (MCLs)
               270

-------
       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
13.     Was the innovative technology eliminated because of the cleanup goals? If a standard
       technology was selected, could it meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      Soil vapor extraction (subsurface soils)

       The standard technologies selected could meet cleanup goals.
14.     Were treatability studies conducted on the innovative technology or standard technology?
                                     1   -.   •           i          "      .  r  •         '  •  '
        No treatability studies were conducted.  .                           |
                                                                       'i      •
                                                                      -[.'•"
                                                                        i  ,           ,
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

        -       Risk level achieved
               Cost effectiveness
               Proven reliability                                 . *  •
                                  •  '    .     ,       '                   -i
                                                                        \      _
                                                     "          '      '         '
                                                                        i
16.     How are alternatives compared?                    '

        The selected remedy for surface soils would achieve a 10"5 risk level; achievement of a 10"6
        risk level would require cleanup levels  below background concentrations of arsenic.  On-site
        disposal of excavated surface soils is more cost effective than off-site disposal and offers an
        equivalent degree of protectiveness. No action for subsurface soil is cost effective in that it
        offers the same level of protectiveness as soil vapor extraction and excavation but at
        considerably less cost. The short-term  effectiveness and implementability of the surface soil
        excavation  alternative is high in that it  involves use  of proven technologies.
 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the, remedy?             !
                                                  "..                     r  '         •
        Technical considerations were not primary to the selection of the remedial alternative.
                                                                                      271
                                               -7-     -     .     .'    •.  i     .. -         ;   .

-------
                            South Jersey Clothing Company
                         (same FS and ROD as Garden State Cleaners)

                                    Minotola, New Jersey
                                          Region 2
 GENERAL SITE INFORMATION
 1.
What were the principal contaminants,
contaminant levels, and media being
addressed in this feasibility study?

Maximum concentrations of principal
contaminants were:
        Soil (rag/kg)

        Tetrachloroethylene (PCE)
        Trichloroethylene (TCE)
                            0.82
                            3.9
2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:

        *     1,400 cubic yards of soil
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     1988
                     10/89
                     8/12/91
                     9/26/91
             Background

EPA Fund-lead
PRPs:  Garden State Cleaners, South
       Jersey Clothing Company
FS prepared by:  Ebasco Services
       Incorporated
3.     What type of site is this?                   •    .-                 '            '

       Dry Cleaning.  A former clothing manufacturer and dry cleaning facility.


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                    .

       Access restriction:     Fencing, deed and zoning restrictions                      :
       Containment:         Soil cap, multimedia cap, asphalt cap, concrete cap          ;
       Chemical treatment:    Ex situ or in situ fixation                                ;    .
       Thermal treatment:     Incineration                                    ''.-.-
       Disposal:             Excavation, disposal at a RCRA facility, backfill treated soil
              272
                                     \

-------
5.      Was an innovative technology considered in the FS? If so, which technology

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
       Biological treatment:   In situ bioremediation
       Chemical treatment:    Soil washing, soil flushing, in situ soil vapor
       Thermal treatment:     Pyrolysis, low temperature thermal desorption,
                             vitrification
extraction
  wet oxidation,
       What was the cost estimate for the innovative technology?
                  ~                        •                           '
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  Aifter the RAAs were
       formulated, costs were estimated during evaluation by the nine criteria established by the NCP.
       The estimated costs were recalculated in the ROD.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative ,
RAA-SC-2
RAA-SC-3
RAA-SC-4
Innovative Technology
In situ soil vapor extraction
Excavation, low temperature thermal
desorption, backfill treated soil
Soil flushing
Estimated Costs
9 Criteria
$191,000
$220,000
$73,000
ROD
$649,000
$1,198,000
$167,000
       How did the cost(s) compare to standard technologies?              i

                 Cost Estimates for RAAs That Include Standard Technologies
          '                  (selected remedial alternative is in bold)     i
Alternative
RAA-SC-1
RAA-SC-5
Standard Technology
No action
Excavation, off-site disposal, backfill with
borrowed material
Estimated Costs
9 Criteria
i$o
. $850,000
i
ROD
$1,700,000
$5,890,000
- •!
        If a standard technology was chosen, why?

        A standard technology was not selected.
                                                                                     273
                                              -2-

-------
P.      If an innovative technology was chosen, why?

        All RAAs, except RAA-SC-1 (No Action), would protect human health and the environment
        and attain ARARS.  The selected alternative, RAA-SC-2 (SVE for soils), was selected because
        it permanently reduces the level of contaminants in sojl through treatment, is readily
        implementable, and creates no short-term risks. RAA-SC-3 (thermal desorption) was
        comparable to the selected alternative for most criteria, but would be more costly, create short-
        term risks by excavation, require significant soil preparation, and require numerous approvals
        to construct and operate the mobile thermal unit. RAA-SC-4 (soil flushing) was eliminated
        because it would temporarily increase mobility of contaminants, increasing short-term  risk, and
        was less implementable because of potential monitoring problems. Alternative RAA-SC-5
        (off-site landfill) offered maximum protection of human health but had the greatest short-term
        risk to the community, short-term environmental impact, and cost.


10.    V °n innovative technology was not chos'en, why not?  At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of                  '
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated  during the initial screening include:

       «      In situ bioremediation was  eliminated because the technology is difficult to control         4fc -
              Nutrients and oxygen must be distributed to an area where contaminants are not            ^^ . )
              uniformly distributed. There was also concern  that residual contaminant levels would
              not be low enough to meet  ARARs,  Further, when TCE and PCE biodegrade>  -vinyl
              chloride (another toxicant) is produced.                               •
       «      Soil washing was eliminated because it would be difficult to implement and because it
              generates relatively  large quantities of waste that must be treated or disposed of.          ••
       "      Pyrolysis was eliminated because it has not been used in commercial applications,
              considerable waste stream pre-processing is required, and it is best applied to highly
              toxic organics.                                                 .      ,   •    .    •
       •      Vitrification was eliminated because it is usually used for less mobile inorganic or
              mixed wastes.
       •      Wet oxidation was eliminated because it is not applicable to non-pumpable soil.  v

       No innovative technologies were eliminated during the three-criteria screening process.

       Innovative technologies eliminated during the detailed analysis include:

       «     Low temperature thermal desorption was eliminated because it was not cost effective
             It was considerably more expensive than the selected technology without providing
             additional protection to human health and the environment.  In addition, it would
             create short-term risks by excavation, require significant soil preparation, and require
             numerous approvals  to construct and operate the mobile thermal  unit                               :
       •      Soil flushing was eliminated because it would increase contaminant mobility, causing
             VOCs to be released into the aquifer and necessitating additional remedial action  In        Jfe  \
             addition, it was considered less implementable because of potential monitoring              ^P  /!
             problems.                                                               '                 •     t

             274
                                            -3-

-------
11.     Which of the nine criteria were weighted most highly in selecting the technology?  Did one of
       the nine criteria eliminate the innovative technology from being chosen? If so, which one?
       Which of the criteria supported the use of a standard technology?     }

       For the alternatives that were protective of human health and the  environment and attained
       ARARs, the most heavily weighted criteria were long-term effectiveness, short-term
       effectiveness, and cost effectiveness.                                 j


72.    What cleanup goals were selected?  If the cleanup goal was based on 
-------
 16.     How are alternatives compared?
                                                                                      :
        While all of the action alternatives would ultimately protect human health and the
        environment, soil flushing would temporarily increase the level of risk because contaminants
        from the soil would be flushed into groundwater.  Off-site disposal and low temperature
        thermal  desorption would impact nearby populations because excavation and transport of
        contaminated soils could potentially result in the generation  of dust and vapors The selected
        remedy, soil vapor extraction, would be less costly than off-site disposal and thermal
        desorption.  Although soil  vapor extraction would  be more costly than soil flushing, it was
        preferred because it would not mobilize contaminants and cause them to enter the
        groundwater.


17.      What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary  in the selection of the remedy?

       Soils at the site are mostly sandy, depth to the water table is about 25 feet, and the surface
       topography is flat  with little or no surface runoff.  The granular nature of the soil  relatively
       low moisture content in the vadose zone, and organic nature of the contaminants were
       particularly amenable to the application of soil vapor extraction.  Also, the facility is located in
       a mixed residential and  commercial area; therefore, the impact on nearby populations was a
       significant consideration. Technical considerations could be  considered primary in the
       selection of remedy at this  site.
                                                                                                ~\

                                                                                                »'
27o
                                 -5-

-------
                         Swope Oil and Chemical Company
                                         OU-2

                            Pennsauken Township, New Jersey
                                        Region 2
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?
                     i
       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       Acetone                    230
       2-Butanone                 41
       Ethylbenzene                320
       4-Methyl-2-pentanone         150
       Tetrachloroethene            360
       Toluene                    490
       Trichloroethene              620
       Xylene                     1,900
       Bis(2-ethylhexyl)phthalate     15
       Isophorone                  1
       Naphthalene                 85
       Phenol        .             52
       Total VOCs                 3,991
       Total Semivolatiles           275
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
N/A
5/91
9/27/91
             Background

PRP-lead           ;|
PRPs: 'Not listed    |           ,
FS prepared by: Geraghty and Miller,
       Inc: ,       • '! '   '     '  '.
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      153,000 cubic yards of soil


3.      What type of site is this?

       Recycling.  A former chemical reclamation facility.
                                                                                 277
                                           -i-

-------
6.
                     were

        Access restriction:
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?


                J^°!°giCS considered during to identification and screening of technically feasible


                             Fencing, deed restrictions

       Ph-m-  i*   ^       ^P^8011'concrete, asphalt, multilayer, synthetic membrane)
       Chemical treatment:    Stabilization/solidification
       Thermal treatment:     Incineration
       Disposal:             Excavation, on-site disposal, off-site disposal


       Was an innovative technology considered in the FS? ,Ifso, which technology?

     ,  Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Biological treatment:    In situ or ex situ biodegradation                                ,
       Phys/Chem  treatment:   In situ soil flushing (solvents, surfactants), ex situ soil washing
                             (solvents, surfactants), dechlorination, oxidation/reduction, soil vapor
                            extraction                                                      .
       Thermal treatment:    Enhanced volatilization, ex situ thermal desorption, in situ vitrification
                            ex situ vitrification, pyrolysis
      What was the cost estimate for the innovative technology?

      During the initial screening process, in which technically feasible technologies are identified
      (pnor to the formulation of RAAs), the FS does not quantify costs.  After fhe RAAs have been
      formulated, costs are typically estimated as part of a three-criteria screening procTsto Wentify

      ±ualVneSh   H^3 ^ detaUed CVaIUati0n- F°r this Site' costs wereeLiated during 2
      evasion based on the nine criteria established by the NCR Costs were reevaluated in th!
      ROD since the selected RAA was a modification of the RAA proposed in the FS.

               Cost Estimates for RAAs That Include Innovative Technologies
                          (selected remedial alternative is in bold)
          Alternative
        RAA-2
        RAA-2-
        modified
                                 Innovative Technology

                        In situ soil vapor extraction/in situ
                        bioremediation/multilayer cap
                       ^B^_.^__
                        In situ soil vapor extraction/potential
                        incidental in situ bioremediation
                                                                         Estimated Costs
 9 Criteria
^i^_

 $2,520,000,
   N/A
   ROD
   ~™^"™™™™™

 $2,09p,000

"•

 $2,099,000
             278
                                                                                                           .1
                                             -2-

-------
       How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action/ground water monitoring

Estimated Costs
9 Criteria
N/A
.

ROD
$1,014,000
8.      If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?

       Only two options were proposed for this site:  no action or an innovative technology.  The
       chosen alternative utilizes soil vapor extraction to remove volatile and semivolatile organic
       compounds (VOCs and semivolatiles). The remedial action selected includes; in-situ vacuum
       extraction (with potential enhancement by biodegradation), treatment of air emissions using
       carbon adsorption or thermal destruction, if necessary, and groundwater monitoring. The
       remedy was selected because: 1) a pilot test conducted at the site indicated that SVE over a 1
       year period would effectively reduce VOC parameter concentrations, 2) further studies of site
       soils indicated that microorganisms exist at the site that will biodegrade semivolatiles,  3) SVE
       is a proven technology for removal of VOCs from soils, 4) operates without emissions or
       noise, 4) will operate with out impacting site surroundings and the local community, 5)
       reduces soil contaminants that are impacting shallow groundwater.           !

       The FS also recommended a cap after treatment, but it was not part of the final remedy (the
       ROD did not include a cap).  A decision on,capping the site was postponed until'after
       implementation of SVE.  If a cap is not required, it will allow a greater degree of unrestricted
       usage of the site.                                         '
10.     If an innovative technology was not chosen, why not?  At what stage was the \innovative
       technology eliminated?                                                  I

       Innovative technologies could be .eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.   |
      ,                                   \                        •             i '
       Innovative technologies eliminated during the initial screening include the following:
                                                                     -    .  -   r  ' .
                                                                             • 1 •'        -  :
       •     'In situ vitrification was eliminated because 1) the environmental impact of the off-gas
              generated, 2) the high cost, and 3) the depth of contamination which extends to 80
              feet.
                                                                                    279
                                              -3-

-------
         •      In situ soil flushing/washing was eliminated after 1) a treatability study was conducted,
                that indicated arsenic and mercury at the site could not be removed with this method,
                and 2) it would increase the contaminant concentrations in the groundwater.
         •      Enhanced volatilization by  steam stripping was eliminated because 1) the costs are
                high, 2) the condensate provides a pathway where soil contaminants can migrate to
                underlying shallow groundwater, and 3) demonstrated steam stripping treatment
                systems generally effect soils to a depth of 30  feet or less.
         •      Thermal desorption was eliminated because it requires excavation of soils and it is not
                possible to excavate to 80 feet.
         •      Ex situ soil washing was  eliminated because: 1) excavation is required, 2) it is limited
                to soluble organic compounds, it has a limited  number of full-scale effective
                demonstrations, 3) the cost  is high, 4)  there are too many site constituents to formulate
                a washing agent without strict operational controls.
         •      Dechlorination (KPEG) was eliminated because 1) depth of contamination precludes
                excavation, 2) volume of waste is  increased which must be further treated as
                wastewater, 3) the cost is very high, and 4) it is only applicable  to chlorinated
                organics.
         •      Ex situ bioremediation was  eliminated because depth of contamination precludes
                excavation.
         •      Ex situ vitrification was eliminated because 1) depth of contamination precludes
                excavation, 2) it is not cost  effective, 3) high energy requirements, and 4) the resulting
                gas emissions must be captured and treated.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      None                             ,

        Innovative technologies eliminated during the detailed analysis include the following:

        "      None

11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 Only two alternatives were proposed: no action and in situ soil vapor extraction. The chosen
 alternative incorporates an innovative technology.  Implementability and short term
 effectiveness were key in selecting the remedial alternative.
12.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?

VOCs and semivolatiles in subsurface soil had migrated into the underlying shallow aquifer,
threatening the ground water quality of the potable deep aquifer. Remedial action was
necessary to remove contaminants from the subsurface soil.  New Jersey Department of
Environmental Protection (NJDEP) Interim Soil Action Levels were used as soil cleanup goals
to protect ground water.                                                           !
          280
                                              -4-

-------
Contaminant
Carcinogens
Total VOCs
Total semivolatiles
Cleanup Level (mg/kg)

1
10
ARAR or Other Basis
'
i
NJEiEP
NJE»EP
                                                                            Could the standard
13.     Was the innovative technology eliminated because of the cleanup goals?
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None
14.    Were treatability studies conducted on the innovative technology or standard technology?
       Treatability studies tested several soil treatment options, including solidification/fixation, soil
       flushing, vapor extraction, and biorernediation.  These studies determined that   ,
       solidification/fixation and soil flushing would not be effective for site remediation as
       solidification/stabilization is not a proven method to fix organics and soil flushing would
       mobilize site constituents to the ground water.  Furthermore, these studies showed that soil
       vapor extraction was applicable as it would recover VOCs in subsurface soil.  Biodegradation
       was applicable to reduce site semi-volatile organics in subsurface soils.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Preference for treatment (vs. containment)


16.     How are measures compared?                                         j    ..'.'.-
                                             :  ' •                           ' 'I
                                                                             r
      ,  The chosen alternative reflects a preference for treatment over containment. The chosen
        alternative utilizes two innovative treatment technologies to remediate site'soil.  This
        alternative is  a modification of the alternative originally  proposed in the FS and does not
        include a cap. The cap  was eliminated because EPA determined that treatment of soil would.
        be adequate to protect the ground water from continued  contamination.    I
                                                                                         281
                                               -5-

-------
17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?                            i •   .

The remedial goal was to prevent subsurface soil contaminants from leaching into the lower
aquifer, which is a drinking water source. Two technical criteria were primary in the choice of
a remedial alternative. First, contaminants were located in subsurface soils.  This made ex  situ
technologies that required excavation difficult to implement, and thermal technologies (in situ
vitrification and enhanced volatilization) much too expensive to implement.  Second, the lack
of a containment layer between the soil and aquifer made technologies that would mobilize
contaminants (soil flushing) inappropriate for site remediation. The chosen technologies could
be applied in situ and were effective at subsurface levels.
                                                                                                     •J,
          282
                                           -6-

-------
                                      Warwick Landfill
                                            OU-1

                                      Warwick, New York
                                           Region 2
 GENERAL SITE INFORMATION
1. ' What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of
contaminants were:

Unsaturated
Soil
(mg/kg)

Benzene "0.002
Chorobenzene —
Ethylbenzene 0.079
Xylenes 0.025
Arsenic 0.0046
Barium .0.111
Chromium 0.018
Lead 0.176
principal


Saturated
Soil
(mg/kg)
,,
0.004
0.028
0.22
0.049
0.0046


Site
NPL Proposed:
NPL Final-
PS:
ROD:
/
Back

EPA Fund-lead
PRPs: N/A
FS prepared by: Et
Inc.


0.0665
0.0246
0.136
2. What volume of material is to be remediated?
The volume of material to be
remediated included:
.

History
1985
3/89
2/11/91
6/27/91

ground



'asco Services




:'...*


              800,000 to 1,000,000 cubic yards of solid waste. The landfill
              including the side slopes, is estimated to be 22 acres.
imound surface area,
3.     What type of site is this?


       Municipal .Landfill.  An inactive municipal and industrial waste dispos.il site located in a
       semirural, residential area.                                        i
TECHNOLOGY SELECTION         -                             !

                                                                      ,1 -           i
4.      Wliat standard technologies were considered for selection in this FS?  j
                                             ' ,                        I             i

       Standard technologies considered during the identification and screening of technically feasible
       technologies were*                                               j


                                                                                 283

-------
        Access restriction:
        Containment:
                              Fencing
                              Slurry wall, sheet piling, grout curtains, synthetic liner, capping (clay,
                              synthetic membrane, RCRA cap)

 5.
        Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        No innovative technologies were identified in the initial screening.
6.
            t was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs.have been
        formulated, costs are typically estimated as part of the three-criteria (effectiveness,
        implementability, cost) screening process to identify alternatives of sufficient merit to undergo
        detailed evaluation.  In this case, the estimated costs were calculated during evaluation by nine
        criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support '
        agency  acceptance; and community acceptance.               ,                     ,

        No innovative technologies were incorporated into RAAs.
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action
Access restrictions/ground water
monitoring/point-of-use ground water
treatment i
Capping/point-of-use ground water
treatment ,
Capping/ground water pump and
treatment/chemical precipitation/point-
of-use ground water treatment
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$887,800
$1,523,800
$14,279,600
$19,013,100
             284
                                             -2-

-------
• " • ' •• •' i ' -
Alternative
RAA-5
t
Standard Technology
Capping/subsurface barrier/ground water
pump and treatment/chemical precipita-
tion/carbon adsorption/point-of-use
ground water trieatment
Estimated Costs
3 Criteria
*'N/A|
'1
I
9 Criteria
$30,241,300
8.     If a standard technology was chosen, why?.

       RAA-3 was chosen because capping the landfill protects human health and the environment
       since it reduces the mobility of contaminated materials off site. The cap eliminates the
       infiltration of rainwater and snowmelt into the landfill, thus reducing the quantity of water
       percolating through the landfill and leaching out contaminants.  This also significantly reduces
       leachate seeps that contaminate nearby surface water and the leaching of contaminants into the
       wetlands and aquifers.  The carcinogenic and noncarcinogenic risks associated with ground
       water ingestion and inhalation will be eliminated for current ground watet users with the
       provision of point-of-use treatment systems on residential wells.  This alternative meets all
       ARARs and provides long-term effectiveness and permanence because the closure cap
       proposed is a permanent technology  that will be maintained at regular intervals to ensure  its
       structural integrity and impermeability. Short-term risks posed by construction activities will.
       be mitigated through the use of both proper construction techniques and operations procedures
       and of protective equipment and health and safety  training. This alternative will be easily
       implemented since the procedures, materials,  and earthworking equipment, are conventional and
       are used extensively in  standard commercial and industrial applications. Furthermore, the
       technologies1 are readily available and the  alternative is cost effective.   j
9.      If an innovative technology was chosen, why?

       An innovative technology was not selected.  .
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                   •                           i

       Innovative technologies could be eliminated from the remedial technology  selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                         '•''''                            'I
       Innovative technologies eliminated during the initial screening include:  i
                                                                           I        '
       '•     , None    •.     '   .                      ,              •      i    .

       Innovative technologies eliminated during the screening of the three criteria include:
                                                                          . i" ••
       •      None                          '                        •'••!'
                                                                                     285
                                              -3-

-------
        Innovative technologies eliminated during the detailed analysis include-                           -«^-
                                                 .  ,   -  •                 *          .             .'  • flB  ""'
        "      None                                                                               ^^ ,.


 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The criteria weighted most heavily in selecting a remedial alternative were implemeritability,
        short-term risk, and cost. The selected alternative was preferred over other alternatives (RAA-
        4 and RAA-5) that would be difficult to implement administratively since they would require
        an extensive monitoring program and operation and maintenance of the ground water treatment
        facility. These alternatives also were more costly.  RAA-5 was also not chosen because the
        excavation necessary for a subsurface barrier might require specialized operations and
        equipment from nonlocal sources. In addition, RAA-5 posed  short-term risk to ecosystems
        and nearby wetlands during excavation.                                         ,


 12.     What cleanup goals were selected. If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
                                                                                     I
        There are no ARAR-based cleanup levels for soils in New York State.  Results from health-
        based risk assessment and leaching studies of contaminants exceeding background levels were
        used in considering cleanup goals.  When estimating human risk, an excess upper bound          ^^
        individual lifetime cancer risk of between 10"4 to 10'6 was acceptable and for rioncarcinogens a     |H|
        Hazard Index (HI) less than 1.0 was acceptable.  These studies determined that direct exposure
        to or ingestion  of soil/sediment did not pose an unacceptable health risk. Furthermore, it was '
        determined that leaching of soil/sediment would not cause ground water contamination in
        excess of ARAR-based cleanup levels.  Therefore, no soil/sediment cleanup levels were
        established.


13.     Was the innovative technology eliminated because of the cleanup goals?  Could the  standard
        technology meet the  cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •       None          ,       :,..-'

        Standard technologies eliminated because of cleanup goals include:

        "       None


14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.
                286
                                             -4-

-------
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Cost-effectiveness                                .
             Impact on nearby populations


16.     How are measures compared?

        RAA-3 was preferred over RAA-4 and RAA-5 because it provides overall protection
        proportional to its cost and is therefore cost effective.  Further, RAA-5 was not selected
        because the extensive excavation and the implementation of a slurry wall would adversely
        affect nearby wetlands and ecosystems.
17.
     ,  .                            ,         • .                   i
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?         .   •;•...,

The nearby wetlands and fractured bedropk were primary technical considerations in selecting
a remedial alternative.  The subsurface barrier proposed in RAA-5 could result in adverse
environmental impacts to-adjacent wetlands.  Further, necessary excavation in the vicinity of
the wetlands would cause sedimentatiqn and disruption of the .ecosystem. The heavily
fractured nature of the bedrock could limit the effectiveness of the slurry wall proposed in
RAA-5.                                                         i
                                             -5-
                                                                          287

-------
                 Aberdeen Proving Ground (Michaelsville Landfill)
                                         OU-1

                      U.S. Army Aberdeen Proving Ground, Maryland
                                        Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Acetone                    41
       4,4'-DDD (PPDDD)          0.007
       4,4'-DDE (PPDDE)          Q.003
       4,4'-DDT (PPDDT)          0.004
       Endosulfan sulfate (ESFS04)   0.006
       Endrin aldehyde (ENDRNA)   0.013
       Heptachlor (HPCL)           0.011
       Heptachlor epoxide (HPCLE)  0.002
       Methylene chloride (CH2CL2)  0.81
       Chromium (CR)              19.7
       Copper (CU)                12.5
       Zinc '(ZN)                   44.4
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
4/85
10/4/89
7/12/91
6/30/92
            Background      .
                             i
Federal Facility                ;
PRPs: U.S. Army \
FS prepared by:  Dames and Moore
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       •     No volume was given; however, the site covers an area of 20 acres.        : ,


       What type of site is this?                                                •

       Military. The site is an unused municipal solid waste landfill in an Army complex. ,In the
       immediate vicinity of the landfill is an industrial sector, a large firing range, an ammunition
       receiving and shipping  building, a pistol range, and a scrap metal yard. Barracks and on-post
       family housing, the City of Aberdeen, and the City of Perryman lie within 4 miles of the site.
             288
                                          -i-

-------
  ICHNOLOGY SELECTION
       What standard technologies were considered for selection in this FS?
       Note: The FS "presents a focused feasibility study (FFS), which evaluates cap and cover
       system remedial alternatives for the Michaelsville Landfill (MLF)."  Some excavation/
       incineration technologies are introduced in the ROD.                     ;
                                               .            '                 i    ••'-.'•
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Containment:          Capping
       Thermal treatment:     Rotary kiln incineration
       Disposal:            ,Off-site disposal, ori-site disposal (ash1)
5.      Was an innovative technology considered in the FS? If so, which technology?
                                  •                 .   '.                     i   .'•''.
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
               None
       What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  In this FS, no three-criteria screening was carried out.  The estimated costs are
       calculated during an evaluation  based  on nine criteria established by the NCP.

       No innovative technologies were selected.
 7.      How did the cost(s) compare to standard technologies?
                                                  .                          I
                  Cost Estimates for RAAs That Include Standard Technologies
                   '         (selected remedial alternative is in bold)         i
                                                                            r-
          Alternative
       Standard Technology
                                                                      Estimated Costs
3 Criteria
9 Criteria
          RAA-1
No action
   N/A
    $0
          RAA-2
Redressing existing cap with clay cap/
grading/topsoil and grass/gas venting  ,
system                       ,
                                              -2-
   N/A
$7,442,400
                                                                                    289

-------
Alternative
RAA-3
RAA-4
RAA-5'
RAA-1A8
RAA-2A3
RAA-3A"
Standard Technology
New, multilayer clay cap to Maryland
Department of the Environment
(MDE) requirements/gas venting
system
New, multilayered cap in accordance
with RCRA requirements/gas venting
system
New, multilayer synthetic membrane
cap in accordance with MDE
requirements/gas venting system
Excavation/disposal at off-post
hazardous waste landfill/refilling with
clean fill
Excavation/mobile rotary-kiln
incineration/refill with nonhazardous
ash
Excavation/temporary storage/lining
the cavity/multilayer cap in
accordance with MDE requirements/
gas venting system
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$9,616,600
$10,001,000
$9^07,000
$135,520,000
$182,795,000
/
$21,825,000
                                                                                                          3
       Note: RAA-5 was listed in the FS as a siibalternative of RAA-3.
       "Introduced in the ROD.
5.      If a standard technology was chosen, why?

       The selected remedy is expected to be very effective in limiting risks associated with 'the site
       under current and future  land use conditions.  Risk reduction will be achieved by covering the
       buried waste material with a capping system to reduce the potential for exposure to arid/or
       transport of contaminants that could be associated with surface water runoff or surface water
       infiltration and subsequent leachate generation or ground water contamination. The capping
       alternatives provide a much greater level of short-term effectiveness than the excavation
       alternatives because the waste would remain in place and would not pose an increased threat to
       human health or the environment during excavation activities. Capping was preferred because
       of the size of the landfill, excessive costs associated with the excavation alternatives, and the
       difficulties of implementing the excavation alternatives. The selected remedy is  consistent
       with the Superfund program policy of containment, rather than treatment, for wastes that do
       not  represent a principal threat at the site and  are not highly toxic or mobile in the
       environment. Of the capping alternatives, RAA-5 is the most cost-effective. The remedy  has
       community, EPA, and MDE acceptance.
               290
                                                                                                           )i
                                              -3-

-------
  9.      If an innovative technology was chosen, why?

         An innovative technology was not chosen.
  10.
12.
13.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?                                           i            :
                          - "  •  • '     ' "     ,      •            ' ;   '  ' f     '    •
  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages:  during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.
                                      '  ,       "          ,        - i "
  Innovative technologies eliminated during the initial screening include! the following:

  •      None                            .'•.-'               '!

 Innovative technologies eliminated during the screening of the three criteria include the
 following:                                                       I
          .  •      •    .      '     •          ..                                 •  .
 •      None                                  •        .      '
        -  •        •                                      •'-•-.   i         ,     '
 Innovative technologies eliminated during the detailed analysis include the following:

 •      None
        Which of the nine criteria were weighted most heavily in selecting-the,technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so
        which criterion?  Which of the criteria supported the use of a standard technology?       '

        Short-term effectiveness, implementability, and cost were the criteria weighted most heavily in
        selecting a technology. The selected remedy provides a much greater level of short-term
        effectiveness than the excavation alternatives, because the waste would remain in place and
        would not pose an increased threat to human health or the  environment during excavation
        activities; implementing a synthetic cap is straightforward;  and the multilayer cap is the most
        cost-effective of the new caps, and is much cheaper than any of the excavation alternatives
                         ,                                  was based on an ARAR>
                     risk level was selected to establish cleanup goals?     {
       N6 soil cleanup levels were given.
Was the innovative technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?
       Innovative technologies eliminated because of cleanup goals include:

       •      None                         ,
                                              -4-
                                                                                   291

-------
       Standard technologies eliminated because of cleanup goals include:

       »      None
3
14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.


75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Cost/unit risk                                                              ,
             Preference for treatment (vs. containment)                                   '
             Waste left in place/institutional control                            ,    ' •     -
16.    How are measures compared?

     .  RAA-5 was the most cost-effective of the capping alternatives. Treatment technologies were
       not considered because "no treatment technologies are currently available that would eliminate
       the risks associated with a municipal landfill in a cost-effective manner." The selected remedy
       is consistent with the Superfund program policy of containment, rather than treatment, for
       wastes that do not represent a principal threat at the site and are not highly toxic or mobile in
       the environment. Capping technologies were compared to excavation in regard to short-term
       risk of excavating material.     ,                                      ,               ,
17.     What technical considerations were factors in selecting a remedy?  Were technical   ,-
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedy. The size of the landfill was
        listed as one of the factors precluding remedies involving excavation and any form of
        treatment.                              ,                                        :
             292
                                               -5-

-------
                                     Abex Corporation
                                           OU-1

                                     Portsmouth,. Virginia
                                        ,  Region 3
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Surface and Subsurface Soil (rag/kg)
       Lead
       Antimony
       Nickel
       Tin
       Copper
       Zinc
       Cadmium
       Silver
       Total PAHs
       Total PCBs
58,000
10
23,
224
1,200
1,175
21
26
32
12
                                            Site History
                               NPL Proposed:
                               NPL Final:
                               FS:
                               ROD:
                    ,.N/A
                     N/A
                     2/92
                     9/29/92
             Background
                .j         •  --
PRP-lead         !
PRPs:  Abex Corporation
FS prepared by: GjEO Engineering,
       Incorporated
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:
                                         "             .              j
       »      59,883 tons, or approximately 49,000 cubic yards of soil near i the foundry


3.     What type of site is this?

       Fabricated Metal.  A former brass and bronze foundry and associated'jdisposal area.  The site
       is located in a residential and commercial/light industrial area.       j


TECHNOLOGY SELECTION  '                             -'."..

4. v    What standard technologies were considered for selection in this FS?

       Standard technologies considered during the Identification and screening of technically feasible
       technologies were:
       Access restriction:      Fencing, deed restrictions


                                            -1-
                                                           293

-------
       Containment:
       Chemical treatment:
       Disposal:
       Thermal trt. ment:
Capping, containment barrier
Stabilization/solidification
Excavation, off-site disposal
Smelter flux substitute (recycling)
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Phys/Chem treatment:  Soil washing                                        .
        Thermal treatment:    Vitrification
6.       What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, estimated costs were calculated during an evaluation based on nine
        criteria established by the NCP: long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.  A large range of costs were developed in the
        FS due to the wide range in soil volumes that are proposed for intervention. The costs were
        more clearly defined in the ROD and these costs are also presented hi  the chart below.

        No innovative technologies were developed into RAAs.                          '
                                                                              >
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
, Alternative
RAA-1
RAA-2
Standard Technology
No action
Building decontamination/excavate
surface soil exceeding 500 mg/kg lead/
off-site disposal at RCRA landfill/deed
restrictions/maintain existing caps
Estimated Costs
9 Criteria
$0
$6,689,000 to
$39,695,000
ROD
$0
$4,888,930
                  294
                                              -2-

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7

Standard Technology
Building decontamination/destroy
existing site caps/excavate residential
surface and subsurface soil exceeding
500 ppm/excavate surface soil
exceeding 500 ppm and subsurface soil
exceeding 1,000 ppm/off-site disposal
Building decontamination/destroy
existing site caps/excavate residential
surface and subsurface soil exceeding
500 ppm/excavate surface soil
exceeding 500 ppm and subsurface
soil exceeding 1,000 ppm/on-site
stabilization/off-site disposal ,
Building decontamination/excavate
residential surface and subsurface soil
exceeding 500 ppm/excavate surface
soil exceeding 500 ppm and subsurface
soil exceeding 1,000 ppm/on-site
stabilization/off-site disposal/asphalt cap
over existing site caps/institutional
controls " '
Building decontamination/excavate
residential surface and subsurface soil
exceeding 500 ppm/excavate surface
soil exceeding 500 ppm and subsurface
soil exceeding 1,000 ppm/on-site
stabilization/off-site disposal/remove
existing site caps/in situ stabilization/
asphalt cap/institutional controls
Building decontamination/excavate
surface soil exceeding 500 ppm/ .
excavate subsurface soil exceeding 500
ppm to a depth of two feet/stabilization
of excavated soil/off-site disposal/
institutional restrictions
Estimated Costs
9 Criteria
$4,384,000 to
$31,757,000
(•
$6,205,000 to
$29,873,000
$4,078,000 to
$19,407,000
$6,334,000 to
$31,454,000
. 1..
$4,2017,000 to
$25,478,000
ROD
$37,895,000
$28,891,000
$22,097,930
, $23,677,930
$16,169,450
8.      If a standard technology was chosen, why?

       RAA-4 was chosen because i£ provides the greatest protection to human health and the
       environment since it remediates all lead-contaminated surface and subsurface soils to. health
       based cleanup levels in residential areas.   The removal of lead-contaminated subsurface soil in
       residential areas was preferred because if contaminated soil was left in place, future activities
       such .as gardening or construction would be detrimental to human health. These activities
       could be avoided by implementing use restrictions, but the EPA does; not support these
                                                                                         295
                                              -3-        .        '   •   i

-------
        restrictions unless no other feasible alternative exists:  The chosen alternative will be:protective
        in the long-term since the lead-contaminated soil will be stabilized and disposed of off site.
        Furthermore, lead will be immobilized by the stabilization process.  RAA-4 represents the
        most cost-effective option.

        At the time of the Proposed Plan, RAA-7 was preferred.  A more in-depth analysis, however,
        revealed the effects of allowing lead-contaminated soil to remain below two feet.  That is, if'
        lead-contaminated soil were left below two feet, use restrictions would be necessary for
        residential areas with soil lead levels of 500 to 5,000 mg/kg and in nonresidential  areas with
        soil lead levels  of 1,000 to 5,000 mg/kg.  These restrictions would significantly impact the
        activities of current and  future residential populations.  During the public comment period, the
        public expressed a strong desire to have a remedy that guarantees the protection of human'
        health and the environment and would not restrict their future activities.  If this could not be
        provided, they would prefer to be permanently relocated.  The EPA decided to select RAA-4
        instead of RAA-7 since all subsurface soil would be remediated to cleanup levels.


9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.


10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                                           '•'   -
                                                                                  ^~    '             x^l^^P ""^V'
        Innovative technologies could be eliminated from the remedial technology selection process at      "??   J
        three stages:  during the initial screening;  during the screening of the three criteria  of
        effectiveness, implementability, and cost; or during the detailed evaluation.     -

       Innovative technologies eliminated during  the initial screening  include the following:

        •      Vitrification (ex situ) was eliminated because lead would be present in the offgases
              generated during  the process.
       "      Soil washing was eliminated because of its high cost and the lack of bearing capacity
              of the  clean sand.

       Innovative technologies eliminated during  the screening of the three criteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis  include the following:

       •      None                                                                       \(
             296
                                                                                                             i

-------
11.
12.
13.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

,The criteria weighted most heavily in selecting a standard technology were protection of
 human health and the environment and cost effectiveness. No innovative technologies were,
 carried to detailed analysis.
 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?
              Contaminant
                                        Cleanup Level (rag/kg)   ARAB! or Other Basis
                Carcinogens
                Lead (residential)
                Lead (noriresidential)
                                          500
                                          1,000
OSWER"
lOSWER"
                        Directive No. 9355.4-02.
 Was the innovative technology eliminated because of the cleanup goals? Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      None                             ,    '

 Standard technologies eliminated because of cleanup goals include:

 •      Gapping
14.     Were tredtability studies conducted on the innovative technology or sandard'technology?

        No treatability studies were conducted.                        .
75.     What measures/criteria were used to compare alternatives?
                         • ---              *    '          '  .   *-  '   j
        The following measures were used to compare the alternatives:

             Cost-effectiveness
        -     Waste left in place/institutional control
        -     Impact on nearby populations
                                              -5-
                                                                                       297

-------
16.     How are measures compared?

        Only RAAs that would permanently reduce and remove site contaminants were considered
        sufficiently protective. The complete removal of lead-contaminated soil from the site was a
        concern because it was found in several residential areas.  RAA-1, RAA-2, and RAA-7 were
        eliminated because they were not protective since lead would be left in place.  These
        alternatives depended on use restrictions or institutional controls and were not considered
        adequately protective since future residential activities such as gardening could be hazardous to
        human health.  In  addition, the negative impact imposed by use restrictions on future activities
        of local residents was not preferred by either EPA or local residents. RAAs that proposed
        containment of contaminants were not considered  adequately protective either.  RAA-5 and
        RAA-6 were eliminated because they would leave contaminants contained on site and would
        require long-term maintenance.  Two alternatives, RAA-3 and RAA-4, offered  comparable
        protection. The chosen remedy, RAA-4, is the more cost-effective of the two alternatives.
17.
What technical considerations-were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

Current land use at the site is a mixture of residential and commercial/light industrial. \ The site
is expected to remain residential and there is speculation about developing the site in the
future. Future site use was a primary consideration in selecting an alternative that permanently
removed contaminants. Only alternatives that remediated lead-contaminated surface and
subsurface soil to cleanup levels were considered appropriate for the site.            \
             298
                                             -6-

-------
                          Arrowhead Associates/Scovill Corp.
                                  (Arrowhead Plating)

                                     Montross, Virginia
                                         Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:.

       No specific contaminant concentrations were
       reported. The contaminants of concern were
       VOCs, semi-VOCs and cyanide in surface
       soil and VOCs in subsurface soil.
2.
3.
       What volume of material is to be
       remediated?
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
6/88
2/90
9/12/91
9/30/91
                                                                Background

                                                   PRP-lead         |
                                                   PRPs: Scovill Incorporated
                                                   FS prepared by:  IGF Kaiser Engineers
       The volume of material to be remediated included:

       »      750 to 1,000 cubic yards of soil  '    •;


       What type of site is this?

       Electroplating. A manufacturing facility that formerly produced cosmetic cases using
       electroplating, lacquering, and enameling processes. It is located in a mral area.
TECHNOLOGY SELECTION                 .                      .'
                                *           '                         "
4.     What standard technologies were considered for selection in this FS?
     '.              •                   '     -    •
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                              ,
       Access restriction:
       Containment:
       Chemical treatment:
       Thermal treatment:
       Disposal:
                            Deed restrictions
                            Capping, slurry wall
                            Stabilization/solidification
                            Incineration
                            Excavation, RCRA-permitted landfill (on-site, ioff-site)
                                             -1-
                                                                                299

-------
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Phys/Chem treatment:  In situ soil flushing, in situ spjl vapor extraction, in situ passive
                             venting
        Thermal treatment:     Low-temperature thermal aeration, in situ vitrification
6.      What was the cost estimate for the innovative technology?
                                                                 I               '
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation ' The
       estimated costs then are recalculated during an evaluation based on nine criteria established by
       the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
       ARARs; protectiveness of human health and the environment; reduction in contaminant
       mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
       community acceptance.

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-2A
RAA-3A
RAA-4A
Innovative Technology
In situ vapor extraction/ground water
extraction and treatment by
precipitation, air stripping, and
adsorption
In situ vapor extraction/ground water,
extraction and treatment by
precipitation, UV oxidation, and
adsorption
In situ vapor extraction/ground water
extraction and treatment by
precipitation, steam stripping, and
adsorption
Estimated Costs
3 Criteria
$8,600,000 to
$13,200,000
$8,500,000 to
$12,900,000
$10,100,000
to
$15,000,000
9 Criteria
$13,177,000
$12,919,000
$15,015,000
               300
                                             -2-

-------
7.      How did the cost(s) compare to standard technologies?
                                                               '   '      ! '
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)     '
Alternative
RAA-1
RAA-2B
RAA-3B
RAA-4B

Standard Technology
No action
Excavation/off-site incineration/off-site
disposal/institutional controls/ground
water extraction and treatment by
precipitation, air stripping, and carbon
adsorption
Excavation/off-site incineration/off-site
disposal/institutional controls/ground
water extraction and treatment by
precipitation, UV oxidation, and
adsorption
Excavation/off-site incineration/off-site
disposal/institutional controls/ground
water extraction and treatment by
precipitation, steam stripping, and
adsorption
Estimated Costs
3 Criteria
$1,250,000 ,
$8,600,000 to
$13,200,000
* I
i
i ' . '
['
$8,500,000 to
$12,900,000
r
i
$10,100,000
to •
$15,000,000
9 Criteria
$1,250,000
$17,573,000
$17,328,000
$19,415,000
 8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
        If an innovative technology was chosen, why?                      |
                                                                        I           '     /
        The chosen alternative was preferred because it reduces the migration of contaminants from
        soils to ground water and reduces risks from irigestion and dermal coititact of soil by future
        residents. Treatment of the site's contaminated soil is expected to eliminate secondary sources
        of contamination that contribute to ground water contamination. This alternative is expected to
        remove contaminants permanently from the soil, thereby reducing contaminant toxicity,
        mobility, and volume. With soil vapor extraction, soil contaminants will be collected and
        treated.  Used carbon will be sent off site for destruction or regeneration. Minimal short-term
        risk will be posed by this alternative since excavation is not required and gas emissions will be
        closely monitored.  Furthermore, gas emissions will be treated by carbon absorption to
        eliminate potential impacts on workers and the nearby community. This alternative would be
        the easiest to implement because  air stripping technology is simple.  Finally, the chosen
        alternative is cost-effective since it provides as much protection as severed other proposed
        alternatives, but costs less.                                       j           •
                                                -3-
                                                                                                    301

-------
 10.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?                                                            '

  Innovative technologies could be eliminated from the remedial technolc^  selection process at
  three stages:  during the initial screening; during the screening of the three criteria of  "
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  •      In situ passive venting was eliminated, but no explanation was provided.

  Innovative technologies eliminated during the screening of the three criteria include the
  following:

  •      Low-temperature thermal aeration was eliminated because incineration is more
         effective and less costly to implement.                                      .
  •      Soil flushing was eliminated because its effectiveness has not been proved, and its
         implementation would be difficult because  of the  complexities of maintaining an
         optimum washing fluid.
  •      In situ vitrification was eliminated because its implementation would be difficult.  The
         technology is technically complex, site soils are heterogeneous, and additional  site tests
         would be required.  Moreover, its effectiveness  is uncertain and it is very costly.

 Innovative technologies eliminated during the detailed analysis include the following:

 •      None                 '          '     -       ,            '                 : •
11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 In the ROD, the chosen alternative was preferred because its  ground water remediation
 components provide the greatest long-term effectiveness and permanence, and is the easiest to
 implement. When considering source remedies, short-Term risk and cost were weighted most
 heavily.  Only two source remediation technologies, in situ vapor extraction and incineration,
 were proposed.  Of these, in situ  vapor extraction would be less costly and would pose ino
 short-term risk,  since excavation would not be required.

 Low-temperature thermal  aeration was eliminated because of cost.  Soil flushing and in • situ
 vitrification were eliminated because they would be difficult to implement and in situ
 vitrification would be very costly.
72.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?

No cleanup levels were derived for soil.  Cleanup will continue until the underlying ground
water quality is no longer threatened by soil contaminants.  Established ground water cleanup
levels must be met, and soil cleanup levels will be established in the remedial design  phase
 302
                                              -4-

-------

 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                      •
                                                                        i •           ,
        Innovative technologies eliminated because of cleanup goals include: |
                                                                        i      ••     " • •
       . • '•    None                  .            :          •         ''•''•'',"'

        Standard technologies eliminated because of cleanup goals include:

• .       •      None   ;.'.-•'     -'     .     •         .'      '•!'".
                                       -                                   -

 14.     Were  treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                            i


 75.     What  measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

      .  -     Cost-effectiveness


 16.     How are measures compared?

        Cost-effectiveness was a determining factor. Alternatives such as off rsite incineration and
        disposal were eliminated because they would be more costly than the chosen alternative.
        Furthermore, RAA-4A was considered equal to the chosen alternate in protection and
        effectiveness, but was eliminated because of cost.
 17.    What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
                  .       -      '           :                  '       '    • i •
        No technical criteria were primary in selecting a remedy.            !
                                                                                               303
                                                -5-      •               ' i    :

-------
                                     Brodhead Creek
                                           OU-1

                            Borough of Stroudsburg, Pennsylvania
                                          Region 3
 GENERAL SITE INFORMATION
 1.
2.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Subsurface Soil (mg/kg)

Ethylbenzene                0.061
Total Xylenes               0.1
PAHs                      450
Arsenic                     4.1
Total unidentified organics     0.17
Total phenolics              0.13
                                                                Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    Interim ROD:
N/A
12/82
1/91
3/29/91
                                                                Background

                                                   PRP-lead
                                                   PRPs:  Pennsylvania Power and Light
                                                          Company and Union Gas
                                                          Company
                                                   FS prepared by: Environmental
                                                          Resources Management, Inc;
What volume of material is to be
remediated?

The volume of material to be remediated included:

"      179 cubic yards of subsurface soil containing free coal tar
•      27,588 cubic yards of residual coal tar
3.     What type of site is this?

       Electric Power Production.  A former coal gasification plant located in a commercial and
       residential area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                       .

       Subsurface Soil With Free Coal Tar

       Access restriction:     Fencing, deed restrictions                                 ;
 304
                                            -1-

-------
        Containment:          Slurry wall, sheet piling, grout curtain, bottom sealing
        Physical/chemical:      Stabilization/solidification (in situ, ex situ), dewatering,  mechanical
                               enhanced volatilization, immobilization-chelation, immobilization-
                               precipitation, immobilization-polymerization
        Thermal treatment:     Incineration (on-site, off-site)               i
        Disposal:              Excavation, pumping, off-site TSD landfill, recycling/recovery, on-site
                           •    disposal, on-site replacement                i
                                    •           ;' .'       •              'I    •'•..'
        Subsurface Soils With Residual Coal Tar                        I

        Access restriction:      Fencing, deed restrictions    .
        Containment:           Slurry wall, grout curtain, sheet pile         !
        Physical/chemical:      Solidification/stabilization, immobilization precipitation, immobilization
                               polymerization
        Disposal:              Excavation, pumping, recycling, off-site disposal, on-site disposal


5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                        i

        Subsurface Soil With Free Coal Tar                              1

        Biological treatment:   Bipdegradation (aerobic, anaerobic, in situ)   I
        Physical/chemical:     Enhanced recovery (surfactant/steam), oxidation, reduction, in situ
                              solvent extraction, soil washing, ir, situ vacuum extraction, in situ
                              vitrification                                 :'.•"'
        Thermal treatment:     Low-temperature  thermal stripping


        Subsurface Soils With Residual Coal Tar

        Biological treatment:   In situ bioremediation                       '
        Physical/chemical:     In situ enhanced recovery, in situ vitrification, ivacuum extraction        '
                                                                        . "| • •             •         '
                                                       •  /      '    =  '   !  •     • •• .  "
6.       What was the cost estimate for the innovative technology?            i
                      •'                  .                                i
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not  quantify costs.  Aifter the RAAs have been
       . formulated, costs are estimated as part of  a three-criteria screening process (effectiveness,
     '   implementability, and cost) to identify alternatives that merit a more detailed evaluation.'"The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP: long-term effectiveness arad permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.                                            j

        Alternatives presented parenthetically represent designation changes in the detailed analysis
        and the ROD.                                                     |                    ,
                                                                         I      "       /            "


                                               2-                                               305

-------
                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)

       Subsurface Soil With Free Coal Tar
Alternative
RAA-6
(RAA-4)
RAA-3
(RAA-5)
Innovative Technology
Excavate subsurface soil/soil washing
Enhanced recovery of free coal
tar/disposal at off-site permitted
incineration facility
Estimated Costs
3 Criteria
$3,707,000
$4,058,000
9 Criteria
$3,954,000
$4,120,000
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)

       Subsurface Soil With Free Coal Tar
Alternative
RAA-1
RAA-2
RAA-4
RAA-5
(RAA-6)
RAA-7
(RAA-3)
Standard Technology
No action •
Limited action/deed restrictions/
fencing/pumping free coal tar/ship
recovered coal tar to off-site permitted
incineration facility
Excavation/off-site disposal in TSD
landfill
Excavate subsurface soils/off-site
incineration of soils
Excavate subsurface soils/on-site
stabilization/solidification
Estimated Costs
3 Criteria
$0
$1,183,000
$3,376,000
$6,816,000
$2,175,000
9 Criteria
$0
$1,176,000
eliminated
$6,227,000
$2,478,000
      Subsurface Soil With Residual Coal Tar
Alternative
RAA-1
Standard Technology
No action
Estimated Costs
3 Criteria
$0
9 Criteria
eliminated
306
                                          -3-

-------
Alternative
RAA-2
Standard Technology
Limited action, deed restrictions,
fencing
Estimated Costs
3 Criteria
$udo,oob
9 Criteria
eliminated
8.      If a standard technology was chosen, why?

       Off-site disposal of treatment residuals was selected.
9.     If an innovative technology was chosen, why?               ;
               '        '•    -  •     '        •        ,     .•'-''       !•     .-.•••
       The chosen alternative was preferred because it will remove free coal tar from the on-site
       subsurface soil and minimize the potential for contaminants to leach into ground water.
       Removing free coal tar will reduce the toxicity, mobility and volume of site contaminants.
       This alternative minimizes short-term risk to workers since it is in situ and does not require
       excavation. Excavation could cause the release of VOCs.  A treatability study will be required
       to ensure that remediation goals (60- to 70-percent  coal tar reduction) are met.  The selected
       remedy is cost-effective.   Elimination of the principal source of site contamination will ensure
       long-term protection. In addition, while stabilization  techniques would reduce only
      , contaminant mobility, the chosen alternative also would reduce contaminant toxicity and
       volume.
                                          )                              !•                  .
       Alternatives for subsurface soil with residual coal tar were not retained for the detailed
       analysis and no explanation was given.                     '     '"!      "
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative     •  ,
        technology eliminated?                                     .''•;-.."                ,
                                                                        i        '..>"•'
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
      "  effectiveness, implementability, and cost; or during the detailed evaluation.     ;
 •••.''                                         '
        Innovative technologies eliminated during the initial screening includs the following:
                                                 • .- •      .               • l.
        Subsurface Soils With Free Coal Tar                              ;

        •     Aerobic biodegradation (ex situ) was eliminated because it wpuld not be applicable to
               soils and wastes streams containing concentrated coal tar and metals.
        •   .  Anaerobic biodegradation (ex situ) was eliminated because it would not be applicable
               to soils and waste streams containing concentrated coal tar,  site organic contaminants,
               and metals.                                       ."'.-...'
        •     Oxidation  was eliminated because it would not be effective  on site metals and has not
               been tried  on soils with similar organic constituents.        i
        •     Reduction  was eliminated because it would not be effective on site metals and has not
               been tried  on soils with similar organic constituents.
                                                                                                 307
                                                -4-

-------
        "      Low-temperature thermal stripping was eliminated because it would not be applicable
                to waste streams containing coal tar.                                                     ^^  j
        •      In situ vacuum extraction was eliminated because it would not be applicable to free             ---^
                coal tar.
        •      In situ vitrification was eliminated because the high waiter table would preclude its
                implementation.
        •      In situ biodegradation was eliminated because it would not be applicable for soils with
                high coal tar.

        Subsurface Soils With Residual Coal Tar

        •      Enhanced recovery (in situ steam extraction) was eliminated because its effectiveness
                in subsurface soils is uncertain since die technique is  still in developmental stages.
        "      Vacuum extraction was eliminated because its application for coal tar-related volatile
                and semivolatile organics is unknown.                                     ;
        "      In situ vitrification was eliminated because it could not be implemented due to the         ,
                high water table and the soil's moisture content.                            !                 .
        •      In situ bioremediation was eliminated because its viability would be precluded by the
                insolubility "of coal tar, the limited availability of the coal tar to microorganisms, and
                the recalcitrance of certain coal tar fractions.  Furthermore, implementation would
                require an enhanced recovery pretreatrnent step to reduce residual tar levels for
                bioremediation.  Enhanced recovery is expected to have limited effectiveness in
                reducing residual coal tar levels.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                                       ;

        Subsurface Soils With Free Coal Tar                                              ;

        "      In situ solvent extraction was never incorporated into a remedial alternative and no
                explanation was given.

        Innovative technologies eliminated during the detailed analysis include the following: \

        Subsurface Soils With Free Coal Tar

        •      Soil washing was eliminated in the detailed analysis and no specific explanation was
                provided.                                              ,         ,


 II.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in  'the elimination of the innovative technology?] If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        Protection of human health and the environment and short-term effectiveness were the most
        heavily weighted factors in selecting a remedial alternative. Soil washing was not preferred
        because it would  require excavation and  would pose a short-term risk to site workers. ;
308
                                               -5-

-------
12.     What cleanup goals were selected?  If the cleanup goal was based onariARAR,what was that
       ARAR? What risk level was selected to establish cleanup goals?     f
                                                          ' -    *         l
       No specific cleanup goals were set for soils.  The performance goal defined in the ROD was to
       remove 60 to 70 percent of free coal tar.  Source removal was expected to prevent the future
       leaching of contaminants into the shallow ground water.


13.    Was the innovative technology eliminated because of the cleanup goals?,  Could the standard
      , technology meet the cleanup goals?           ,

       Innovative technologies eliminated because of cleanup goals include:!                .
                                                    .                   'i  \       '       '

       •      None                     ,                              !
       r               \                 -     •                                      -
                                                                           •'        •
       Standard technologies eliminated because of cleanup goals  include:  j
                                             1          "                I               .
       a      None          .   p  •    '   .    •      -                   !
                                    ,                                 '!""•,"•-.
                                 " -     "  .  .                     '      ' |          v     -
                                • .      .-                      • '         I.
                                                                   i    i                   ,
14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                                       i
       No treatability studies were conducted.


75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Impact on site workers                          .    '       j
        -,'  Preference for treatment (vs. containment)


 16.     How are measures compared?         ,                                  ,  -.

        The chosen  alternative  was preferred because it poses the least short-term risk to  site, workers.
        Since the chosen alternative is in situ, soil excavation will not be required.  Excavation would
        promote the release of  VOCs and allow direct contact with contaminated subsurface soil.
        Though the  ROD addresses an interim action, treatment was preferred over containment.
        Furthermore, though it was noted that long-term effectiveness was not an applicable criterion
        because of the ROD's interim status, the chosen alternative was noteid to offer long-term
        effectiveness and permanence through the elimination of the source, i

    •   '.     - '.•''      '  •      :   ••  •".-.',               •  '     '  i'-     •'•   ''  •     .
 17.     What technical considerations were factors  in selecting  a remedy?  Were technical
         considerations primary in the selection of the remedy?             j

         Technical considerations were not primary in selecting a remedial alternative.
                                                                                               309
                                                              .. -     '  i                    .-     i    ,
                                               -6-    .,                i  ,

-------
                                Brown's Battery Breaking
                                           OU-2

                                Tilden Township, Pennsylvania
                                          Region 3
 GENERAL SITE INFORMATION
1. What -were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (rag/kg)

Lead 170,000
Antimony 13.3
Cadmium 0.7
Cyanide 5.3
Mercury 1.9
Concentrations of BNAs, pesticides, and


Site History
«7
NPL Proposed: 10/84
NPL Final: 6/86
FS: 12/91
ROD: 7/2/92

Background

EPA Fund-lead i
PRPs: General Battery Corporation^
Te'rry Shaner (site owner) ;
FS prepared by: U.S. EPA
.-.'.'
       PCBs were not given.


2.     What volume of material is to be remediated?.

       The volume of material to be remediated included:
              39,500 cubic yards of soil in the containment area (created in the 1983 Immediate
              Removal Action, the containment area is located in the site's southwest quadrant)
              27,500 cubic yards of soil outside the containment area
3.     What type of site is this?

       Recycling.  An inactive battery-reprocessing site located in a primarily rural area.


TECHNOLOGY SELECTION                                                   "'*..••'•

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:
       Containment:
310
Fencing, signs
Berms, dikes, grouting


                -1-

-------
       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Stabilization/solidification, chemical precipitation
Screening, wet classification
Incineration, smelting
On-site storage, off-site disposal at RCRA landfill
5.     Was .an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                       {  •
                                                                       \  .
       Chemical treatment:   In situ soil flushing (solvent), soil washing (Bureau of Mines process)
       Thermal treatment:    In situ vitrification, fuming/gasification furnace
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP:  long-term effectiveness and permanence;  short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.

        RAA-5 was presented  for the first time in the revised Proposed Plan.

                 Cost Estimates for FLAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)                            .
Alternative
RAA-5
Innovative Technology
Excavate soil and battery casings/off-site thermal
treatment (fuming/gasification furnace) of soft; and
casings/energy recovery/lead recovery
Proposed
Plan
N/Aa
        "Only capital costs were provided.
                                               -2-
                                                                   311

-------
 7.      How did the cost(s) compare to standard technologies?            .

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action/fencing/long-term monitoring
Excavate soil and battery casings/on-site
stabilization-solidification/off-site
disposal
Excavation soil and battery casings/off-
site disposal at RCRA landfill
Excavate soil and battery casings/on-site
stabilization-solidification of soil/off-site
disposal of soil/off-site incineration (and
energy recovery) of casings/lead
recovery
Estimated Costs
3 Criteria
$296,350
$28,360,000
to
$34,526,000°
$49,444,000
to
$56,949,000
$24,850,000
to
$28,428,000
9 Criteria
$296,000
$28,360,000
$49,000,000
$24,631,000
!
       "The range of costs covers the difference in achieving soil cleanup levels of 1,000 mg/kg and
       500 mg/kg, respectively.
8.     If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?

       RAA-5 provides maximum reduction in waste volume via incineration of the casings, and
       maximum reduction in contaminant toxicity and mobility by excavating and removing
       contaminated soils and casings.  Excavation also results in maximum protection of the
       environment surrounding the site by avoiding the slight potential risk that would be posed by
       leaving treated materials on site, where they could cause some future environmental harm.
       RAA-5 provides for maximum reuse/recycling of the metals after their removal from the soil
       matrix and is the least costly of the soil alternatives.

       EPA acknowledges that RAA-5 includes an innovative technology which has not yet been
       tested in treatability or pilot studies. The proposed combination of technologies, however,
       have been used individually in other industrial applications and,  according to EPA, has a
       reasonable expectation of being successful. If not, the preferred alternative would be RAA-2,
       as originally chosen in the Proposed Plan issued 8/1/92.
 312
                                             -3-

-------
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.   .

        Innovative technologies eliminated during the initial screening include: the following:
                                                                        I      -
        •      In situ soil flushing was eliminated because' it might enhance migration of
               contaminants to the shallow water table.                    [
        •      In situ vitrification was eliminated because it would be difficult to implement given the
               shallow water table.                                       j
        "      Soil washing (Bureau of Mines process) was eliminated based on treatability study
               results that demonstrated that soil washing was not appropriate for the site.  The fine-
               grained nature and high carbon content  of the  site's soil would impede filtration.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                       ! "
          1                        •         '•               •                     '
        •    '  None-"   '            •     '     •   ' •       •     .'    '  '   I -  '       .      ]'   ' •

        Innovative technologies eliminated during the detailed analysis include; the following:
                                                 • •                 .     l
        •      None                                                     i
11.
Which of the nine criteria were weighted most heavily in selecting the, technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion? Which of the criteria supported the use of a standard technology?

The criteria weighted most heavily in selecting a remedy include reduction of volume and cost.
RAA-5 provides for maximum reduction in waste volume via the incineration of the casings,
as opposed to RAA-2, RAA-3, and RAA-4 which would increase the volume of the waste as a
result of the solidification/stabilization process.  In addition, RAA-5 would be protective of the
environment surrounding the site because the slight potential risk of the treated materials in
RAA-2, RAA-3, and RAA-4 causing some future environmental harm at the disposal site is
eliminated.  RAA-5 is the least costly of the alternatives.       ,    , i
12.     What cleanup goals were selected?  If the cleanup goal was based on \an ARAR,  what was that
       ARAR? What risk level was selected to establish cleanup goals?     j
                    Contaminant
                                Cleanup Level (rag/kg)
ARAR or Other Basis
                Carcinogens
                Lead
                                         1,000
                                                                         EF'Aa
              "OSWER Directive 9355.4-02:  Based on upper bound of residential range of 500 to
              1,000 ug/kg; future site use restricted to industrial use only,   f
                                              -4-
                                                                                            313

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Two treatability studies were conducted to evaluate stabilization/solidification and soil
        washing.  These studies determined that stabilization/solidification was an appropriate
        treatment for reducing lead leaching and that soil washing was not appropriate for the site
        because the fine-grained nature and high carbon content of the site soil would impede
        filtration.                                                            ,
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Cost/unit risk
               Proven reliability
               Reuse/recycling of materials
               Preference for treatment (vs. containment)
16.    How are measures compared?                                     •         •     '•    .
                                                                        1 •              i

       RAA-5 was judged to be the most cost-effective remedy.  Proven reliability was an uncertain
       factor in selecting RAA-5 because no treatability or pilot studies have been completed. The
       proposed combination of technologies, however, have been used individually in other industrial
       applications and, according to EPA, has a reasonable expectation of being successful. If not,
       the preferred alternative would be RAA-2, as originally chosen in the Proposed Plan  issued
       8/1/92. RAA-5 provides for maximum reuse/recycling of metals; although other alternatives
       were not compared .based on this criterion, it was an important consideration. RAA-5 provides
       for maximum reduction in contaminant toxicity and mobility at the site, by excavating and
       removing contaminated soils and casings.                                         ',
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a technology. The very shallow water
        table resulted in the elimination of the following innovative technologies:, in situ  soil flushing
        and in situ vitrification.  The fine grained nature, high carbon content of the site's soil also
        was considered, resulting in the elimination of soil.washing.
314
                                               -5-

-------
                                 C&D Recycling

                           Foster Township, Pennsylvania
                                     Region3
1- What were the principal contaminants
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:

Soil (mg/kg)
Jfad 324,000
Copper 85j000
Antimony 2,030
PCB 3.6
..
Ash (mg/kg)

Lead 706,666
C°PPer 105,655
Zlnc 8,362

Site
NPL Proposed:
NPL Final:
rS:
ROD:
History
9/85 -
2/21/90
1/10/92
9/30/92




Background
PRP-lead
' ' .

PRPs: AT&T Nassau Metals Corp.; 14
other (unidentified) owners of the
site, operators of the site, and
generators of material sent to
site.

the

FS prepared by: ERM-Northeast


Dioxins/Furans 0.0015
Sediments (mg/kg)
Lead 121,000
Copper 23,200
Zinc 3,660s
Antimony §342

-.'














2.
       concentrations were from leach pit data submitted during public lomment period.
 What 'volume of 'material is to < be remediated?   '

The volume of material to be remediated included:

•      26,273  cubic yards of soil
•      1 65 cubic yards of ash
•      1,200 linear feet of creek sediments
•      1,900 cubic yards of pond sediment
•      24 cubic yards of storm water sewer sediment
                                    -1-
                                                                                        315

-------
3.      What type of site is this?

       Recycling.  The site was used for a metal reclamation operation.  The site is located in a
       residential/agricultural area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:     Fencing
        Containment:         Capping (soil, multilayer)
        Physical treatment:    Stabilization
        Disposal:             Excavation, on-site disposal, off-site disposal
5. ,     Was an innovative technology considered in the FS? If so, which technology?       '.

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Chemical treatment:    Soil washing, electrokinetics                              '
 6.      What was the cost estimate for the innovative technology?                         ;

        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs  are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, estimated costs were calculated during an evaluation based on nine
        criteria established by the NCP. No innovative technologies were incorporated into RAAs
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No further action/continued main-
tenance of sedimentation and erosion
control systems/ash pile covers/fencing
Estimated Costs
3 Criteria
N/A '
9 Criteria*
$831,020
 316
                                               -2-

-------
Alternative
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
/
Standard Technology
Continued maintenance (as in RAA-
l)/common actions (see below)/
.excavation/consolidation/fencing
Continued maintenance (as in RAA-
l)/common actions (see below)/ excava-
tion/consolidation/fencing/soil cover
Continued maintenance (as in RAA-
l)/common actions (see below)/
excavation/consolidation/fencing/
multilayer cap
Continued maintenance (as in RAA-
l)/common actions (see below)/
excavation/consolidation/fencing/
stabilization/off-site disposal
Continued maintenance (as in RAA-
l)/common actions (see below)/
excavation/cbnsolidation/fencing/
stabilization/on-site disposal
Estimated Costs
3 Criteria
MA
N/A
i_
N/A
i
N/A
'
• • . i-
.
N/A
i
,i
9 Criteria"
$2,263,740
($2,270,531)
$3,302,210
($3,863,585)
3,919,220
($4,830,138)
$8,944,565
($11,985,717)
$5,706,345
($7,361,185)
"Costs given for cleanup level of 1,000 ppm lead and 500 ppm lead.  iThe 500 ppm costs are
in parentheses.  Note that Proposed Plan costs are for 500 ppm lead, i

                                                            1
The following common actions were carried out for RAAs 2 through ;6.
Common
Action
CA-1
CA-2
CA-3
CA-4
CA-5
CA-6
CA-7
CA-8
Description
Excavation/cement stabilization of pond and creek sediments/
remediation of pond bottom/temporary diversion of Mill Hopper
Creek
Excavation/possible stabilization of storm water sewer system
sediment/possible co-disposal with other soil of sediment
Decontamination of site buildings
Removal of casing and wire
Deed restrictions
Abandon all wells not used or considered part of groiund water
monitoring network
Monitoring of stream and/or pond water and stream biota ;
s ' . '
Phase IB archeological survey prior to any excavation soil
                                     -3-
317

-------
Common
Action
CA-9
Description
Soil toxicity testing after soil excavation and
regrading is completed
 8.      If a standard technology was chosen, why?

        RAA-5, by including stabilization as an integral remedial action in addition to containment,
        provides the greatest protection to human health and the environment!  The long-term
        effectiveness and permanence and the reduction in toxicity provided by ash, soil, and sediment
        stabilization are significant advantages over containment only.  In the FS, RAA-6 was chosen
        over RAA-5 because the on-site disposal facility, constructed with liners  and covers, meets
        RCRA requirements, .whereas the off-site disposal facility might not have been constructed
        with an impermeable liner; co-disposal  with other wastes and the continuous long-term
        operation of a commercial landfill could adversely affect the long-term effectiveness and
        permanence of stabilized materials; a commercial landfill might not be closed for several years,
        during which  time only daily covers would be installed, possibly exposing the stabilized
        material to storm water infiltration; transportation of the material would be required for off-site
        disposal; and off-site disposal would cost $3.2 million more than on-site disposal.  This
        decision was reversed in the ROD due to public preference for off-site disposal and state
        concerns over the design of the on-site containment cell's ability to comply with residual waste
        management regulations. However, if the PRPs can show within 180 days of issuance of the
        ROD that an on-site remedy is equally or more protective, is cost-effective, and complies with
        all ARARs, EPA will solicit public comment and possibly return to on-site disposal.
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen
JO.
318
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                                         ':

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the, screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      None

Innovative technologies eliminated during the screening of the three criteria include the
following (note that these technologies were not incorporated into RAAs but were subjected to
a three criteria analysis):

•      Soil washing was eliminated because the fine nature of the media, in particular ash and
        sediment, would mean the technology would not sufficiently remove target chemicals,
        the technology would result in a residual slurry, and further treatment would be
        required.

                                       -4-             ••          ..    •      •    :

-------
       •      Electrokinetics technology was eliminated because it requires saturated soils.  The
              technology could not be implemented at the site.             !
                                                                        l
       Innovative technologies eliminated during the detailed analysis include the following:

       •      None
11.
12.
13.
       Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                                       \
       Public and state acceptance were weighted heavily in selecting off-site disposal over on-site
       disposal.  Overall protection, long-term effectiveness and permanence, and reduction of
       toxicity and mobility through soil treatment as opposed to  containing the contamination were
       both strong influences on the selection of stabilization and containment over containment
       alone.

       What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup  goals?     j
                        >                    -                     '     i  '.  -               •
       Several cleanup goals  were originally selected for soil, sediment, and stabilized ash. It was
       later decided, however, that the area of contamination delineated by lead satisfactorily
       addresses unacceptable levels of other site-related contaminants.      j
                     Contaminant
                                        Cleanup Level (ppm)   ARAR!or Other Basis
                 Noncarcinogens
                 Lead
                                               500 ppm
Risk"
               "Based on a child blood level of 10 ug/dL.

        For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
        was acceptable.  For noncafcinogens, a Hazard Index less than or equal to 1.0 was acceptable.

                             • "              .                     '       ; \              '        "

        Was the innovative technology eliminated because of the cleanup goats?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        • ,     None

        Standard technologies eliminated because of cleanup goals include:

        •      None                                      .     ,   .
                                               -5-
                                                                                                   319

-------
  14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                                -   ,.  .   •   ..   .   •     •;      •
          Treatability studies were conducted to determine the effectiveness and unit cost of
          stabilization. Samples of soil and ash from the site were tested, .and the treatability study
          report confirmed that ash, soil, and sediment could be immobilized through stabilization.


  15.     What measures/criteria were used to compare alternatives?                     '•••"

          The following measures were used to compare the alternatives:

                 Risk level achieved                    .         ,                '''''.'
                 Total cost
                 Preference for treatment (vs.  containment)


  16.     How are measures compared?                                                   '     ,

          RAA-5 (off-site disposal) does not provide a reduction in risk beyond that provided by RAA-6
          (on-site disposal). The selected remedy (RAA-6), however, will eliminate the site risks.
          Transporting material off site (RAA-5) would involve higher short-term risks,  through possible
          accident and subsequent contact, and air pollution, than RAA-6.  RAA-5 and RAA-6 are
          compared in terms of cost, in that RAA-6 costs approximately two- thirds that of RAA-5.
          Preference for treatment was a factor in selecting stabilization and containment over
          containment alone.                                                                                -"Sk


  17.     What technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in the selection of the remedy?

          Technical considerations were not primary in selecting a remedy.  The fine nature of the
          media, in  particular ash and  sediment, was a factor in eliminating soil washing.
320
                                                -6-

-------
                                CryoChem, Incorporated
                                           OU-3

                                   Worman, Pennsylvania
                                          Region3
 GENERAL SITE INFORMATION

_ 1.      What were the principal contaminants,
     .   contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil (rag/kg)

        .Tetrachloroethylene    0.46
        1,1,1-Trichloroethane   22
        1,1-Dichloroethane     4
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:

        •      70 cubic yards of soil
                                    Site History
                       NPL Proposed:
                       NPLFinal:
                       FS:
                       ROD:
7/89
10/89
6/2/90
9/30/91
                                    Background

                       EPA Fund-lead
                       PRPs:  CryoChem, Incorporated; C.S.
                              Garber and Sons Incorporated;
                              other owners and operators of
                              CryoChem, Incorporated and the
                              property (not listed)
                       FS prepared by:  Dynarnac
                              Corporation ,
 3.     What type of site is this?

        Fabricated Metal Products.  A metal fabrication facility.
 TECHNOLOGY SELECTION
                                                                     i
 4.     What standard technologies were considered for selection in this FS?,

        Standard technologies considered during the identification and screening of technically feasible.
        technologies were:                                          -   j
        Containment:
        Thermal treatment:
        Disposal:
Clay cap                                i
Incineration                            '  i  •  ;
Excavation, off-site disposal at RCRA Subtitle C  facility
                                             -1-
                                                                  321

-------
 5.      Way an innovative technology considered in the FS?  If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Physical treatment:     In situ/ex situ vapor extraction


 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (pnor to the fonnulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are usually estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, estimated costs were calculated during an evaluation based on the
        nine criteria established by the NCR

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-5
(RAA-3)
RAA-5A
(RAA-2)
=======
Innovative Technology
In situ vapor extraction
In situ or ex situ soil vapor extraction/
excavation and disposal of soil at
RCRA Subtitle C facility
' " ' —^— — _ 	 _
Estimated Costs
9 Criteria
$58,000
N/A
ROD
$53,000 to
$66,400'
$106,000 to
$119,000
y
       "Costs were estimated for both in situ and ex situ options. The in situ optipn was always the
       higher estimate.
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
(RAA-5)
RAA-3
Standard Technology
No action/5-year review
Concrete cap
Excavation/disposal at off-site RCRA
Subtitle C landfill
======================— _=i
Estimated Costs
9 Criteria
$3,100
$16,700
$41,000
ROD
$0
$34,900"
eliminated
322

-------
17.     What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?               |

       No technical criterion was primary in the selection of a remedy.
                                              -5-
325

-------
                              Defense General Supply Center
                                            OU-1

                                      Richmond, Virginia
                                           Region 3
  GENERAL SITE INFORMATION

  /.     What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil (rag/kg)

         Antimony                  6.6
         Arsenic                     88
         Cadmium                  5    ,
         Chromium (VI)             Q.71
         Acetone                     0.27
         Carbon disulflde            0.033
         Chloroform                0.013
         Methylene chloride         0.063
         Toluene                    0.0064
         Xylene                     0.0028
         Benzoic acid                0.055
         Anthracene                 0.062
         Benzo(a)anthracene         0.35
         Benzo(a)pyrene             0.3
         Benzo(b)fluoranthene        1.5
        Benzo(g,h,i)perylene         0.22
        Benzo(k)fluoranthene        0.5
        Bis(2-ethylhexyl)phthalate    0.87
        Chrysene                   0.98
        Dibenzo(a,h)anthracene      0.046
        Di-n-octyl  phthalate         1.4
        Di-n-butyl phthalate         0.23
        Fluoranthene               i
        Indeno(lA3-cd)pyrene       0.2
        4-Nitrophenol               0.05
        Phenanthrene               0.17
        Pyrene                     1
        2,4-D                       0.13
        4,4'-DDD  .                 0.0042
        4,4'-DDE                    0.04
        4,4'-DDT                    0.22
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1984
1987
10/91
5/15/92
            Background

Federal Facility                >
PRPs:  Army Corps of Engineers
FS prepared by:  Law Environmental
                                                                                                   )i
326
                                           -1-

-------
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:
            ,                   >•                             '            i     •             •  •
        •      27,700 cubic yards of soil           '  ,          •          I      .


3.      What type of site is this?                   '              .'•','                     .

        Military. The site is used for the storage of drummed and containerized chemicals.  The site is
        located on a facility that manages and furnishes military general supplies.  Land use in the
        vicinity  of the facility is primarily single-family residential, intermixed with retail stores and
        light industry.                                    .                i


TECHNOLOGY SELECTION                 -                          j

4.      What standard technologies were considered for selection  in this FS?\

        Standard technologies considered during the identification  and screening of technically feasible
        technologies were:
                 '           •                       .    '                '  J          •  •
        Access restriction:     Fencing, warning signs, deed/zoning restrictions
        Containment:          Capping (clay, synthetic, asphalt, cbncrete, multi-media), vertical
                               barriers (sheet piling, grout curtain, slurry wall)
        .Chemical treatment:    Ex situ stabilization (microencapsulation, solidification)
        Physical treatment:     Soil aeration                               j
        Thermal treatment:     Ex situ thermal treatment
        Disposal:              Excavation, on-site landfill, off-site landfill, backfilling
              ' •              '              •'                             I1            >
                                                                         i              '          '
                                                          ;                   '        -N              -
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                    ,                                        .         '
                                                                         I  .    •'                     '•
        Biological treatment:   In situ biodegradation (nutrient/oxygen injection, microorganism
                               seeding, surfactant addition), ex situ biological treatment
        Phys/Chem. treatment:  In situ chemical oxidation, in situ solvent extraction (aqueous solvent,
                               miscible organic solvent, organic solvent), ex!'situ soil washing (solvent
                               extraction), in situ vacuum extraction
        Thermal treatment:     Ex situ vitrification, steam stripping                                  .    ' .
                                 .•'.,'             '              i

  6.      What was the cost estimate for the innovative technology?          j

         During the initial screening process, in which technically  feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
        . (effectiveness, implementability, arid cost) to identify alternatives that merit a more detailed
                                                                         I           •                    '


   '     .'     .              .            •        -2-      -:              !   ,          '.•    ''''327

-------
         evaluation.  The estimated costs are calculated during an evaluation based on nine criteria
         established by the NCP.
                                                                                    i

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
            Alternative
          RAA-4
        Innovative Technology
Excavation/soil washing/backfill with
clean soil
                                                                       Estimated Costs
                                                                   3 Criteria
                                                                   $4,294,000
9 Criteria
$6;067,578
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-4
RAA-5
RAA-6
— =====
	 	 ============================5=
Standard Technology
Multilayer, multimedia cap/grading/
surface water runoff collection/
monitoring wells/extended monitoring
program
Excavation/stabilization/solidification
Excavation/off-site treatment/
backfilling with clean imported soil
Deed restrictions/air monitoring
No action
	 -^rr^^r:
Estimated Costs
3 Criteria
$842,300
$1,239,000
$9,695,000
$15,000
$0
========
9 Criteria
$825,300
eliminated
eliminated
$15,000
:$0
8.     If a standard technology was chosen, why?                                      '

       RAA-5, institutional controls, was chosen because although risk-based soil action levels or
       background levels for arsenic and antimony were exceeded in one sample each, none of the
       constituents found in the soils are present in the ground water at concentrations greater than
       MCLs.  Additionally, the samples containing arsenic and antimony concentrations greater than
       the risk-based action levels or background levels were collected at depths greater than 5 feet
       Exposure to these constituents, therefore, would not be expected to occur unless  excavation
       activities take place at the site.  RAA-5 was selected to be the most effective and appropriate
       option.
328
                                             -3-

-------
9.      If an innovative technology was chosen, why?                      !                      ,

       An innovative technology was not chosen.                          t

                                       ..              :       •            I.   ' .  ^       '
                                '        •  :                              f'         ,
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
         '/                            .            •                       !
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      In situ biodegradation was eliminated because potential leachiate generation might
               contaminate deeper soil zones.
        •      In situ chemical oxidation was eliminated because the technology  would not be well
               demonstrated; and there would be a potential fot either incomplete reaction or
               application of excess reagents.
       .•      In situ vacuum extraction was eliminated because the primary contaminants are
               semivolatiles and the contamination is shallow.              !
        »      In situ steam stripping was eliminated because the technology would be more -
               applicable to deeper contamination..                       j
        •      In situ solvent extraction was eliminated because the technology would be more
               suitable to deeper contamination and there would be a high potential for ground water
               contamination.                                           !
        •      Ex situ biological treatment was eliminated because the technology would not be
               applicable to metals.
        •      Ex situ vitrification was eliminated because the technology w,ould be extremely
               expensive to implement and the soil is probably not amenable to treatment.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                              '

         •      . None           •    '            ,      .   • .       "      j

         Innovative technologies eliminated during the detailed analysis include  the following:
                                                                        i          •
         •      Soil washing would have the highest short-term exposure potential because the soil
                would be excavated;  it would be the  most difficult to implement since testing and
                treatability studies would be required in addition to treatment; and it would be the
                most expensive alternative. It ranked higher, however, than the other RAAs in long-
                term effectiveness; reduction of contaminant mobility, toxicity,  zind volume;
                compliance with ARARs; and overall protection.  The only explanation for its
               '•elimination is that no remedial action was chosen.
                                                -4-
                                                                                                329

-------
 U.
          Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
          to meet one  of the nine criteria result in the elimination of the innovative technology? If so
          which criterion? Which of the criteria supported the use of a standard technology?

          There was no clear indication as to which criteria were most important; however from the
          above discussion, Cost-effectiveness seems to be a deciding factor. The selected alternative
          institutional controls, provides overall protection to human health and the environment by
          restricting access to the site, thus reducing the principal threat of exposure through ingestion or
          dermal contact with the contaminated soils.  The remedy offers short-term effectiveness since
          no excavation is needed and there is no excess risk from exposure to surface materials as
          determined in the baseline risk assessment.  The remedy is very easy to implement because no
         . direct physical actions take place and it is the least costly alternative.

          No innovative technologies were considered under the nine-criteria screening.
12'
330
            A           oals were selected?  If the cleanup goal was based on an ARAR, what was that
         ARAR? What risk level was selected to establish cleanup goals?
—
Contaminant
i s^=:^=
Cleanup Level (mg/kg)
1 .1
ARAR or Other Basis
Carcinogens i . • .
Arsenic
Cadmium
Chromium (VI)
Chloroform
Methylene chloride
Benzo(a)anthracene
Benzo(a)pyrene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Bis(2- '
ethylhexyl)phthalate
Chrysene
Dibenzo(a,h)anthracene
Indeno(l ,2,3-cd)pyrene
4,4'-DDD
4,4'-DDE
4,4'-DDT
7.2
6.0
60
1,700
1,400
6.1
0.86
6.5
14
740
200
0.79
3.8
43
30
30
Soil background level8
Risk-based
Risk-based
Risk-based
Risk-based ! '•
Risk-based
Risk-based
Risk-based •.
Risk-based
Risk-based ',
Risk-based
Risk-based ;
Risk-based
Risk-based
Risk-based
Risk-based
                                               -5-

-------
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Noncarcinogens
Antimony
Acetone
Carbon disulfide
Toluene
Xylene
Benzoic acid
Anthracene
Benzo(g,h,i)perylene
Di-n-octyl phthalate
Di-n-biityl phthalate
Fluoranthene
4-Nitrophenol
Phenanthrene
Pyrene
,2,4-D
4.8
,1,200
1,200
2,400
24,000
48,000
3,600
41
240
1,200
480
48
85
11
120
Risk-based
Risk-based
Risk-based
i Risk-based
Risk-based
Pisk-based
Risk-based
Bisk-based
Risk-based
Risk-based
Risk-based
Risk-based
Risk-based
Risk-based
Risk-based
              The risk-based soil action level was lower than the background soil level, so
              background levels were used instead.


       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
       was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
                                       • '         '     - ' .         *
                                                      ...             .1
                                                 '         i      '      !         •
13.     Was the innovative technology eliminated because of the cleanup goals? Could the  standard

       technology meet the cleanup goals?                               [
                                                                '.'.'-'•'

       Innovative technologies eliminated because of cleanup goals include: i

                                                                    ..  i ' •
       • -•  None                                                   i     • •      •


       Standard technologies eliminated because of cleanup goals include:


       •     None
                                                                                                 331
                                              -6-

-------
   14.     Were treqtability studies conducted on the innovative technology or standard technology?

          No treatability studies were conducted.



   75.     What measures/criteria were used to compare alternatives?    '                   '   '   :

                 Level of contamination, depth of contamination, and lack of ground water
                 contamination


   16.     How are measures compared?

          The selection of RAA-5 was based on the fact that only two soil samples showed
          contamination above cleanup levels and this contamination was located more than 5 feet below
          the surface. Furthermore, no ground water contamination was observed.  For these reasons
          remediation was deemed to be unnecessary.
  17.
                                                                             i

What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?


Technical considerations were not primary in selecting a remedy.  One reason for eliminating
ex situ vitrification was that the soil probably would not be amenable to treatment.   \
332
                                              -7-

-------
                            Defense General Supply Center
                                          OU-5

                                    Richmond, Virginia
                                         Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Arsenic                     81
       Benzene                    0.001
       Chloroform                0.003
       1,2-Dichloroethane          0.015
       Tetrachloroethylene         1.5
       Toluene                    0.002
       Triehloroethylene           0.036
       Xylene                     0:003
       Bis(2-ethylhexyl)phthalate   0.81
       Di-n-butyl phthalate        0.24
        1,2-Dichlorobenzene        0.14
        Diethyl phthalate           0.12
        Di-n-octyl phthalate         0.41
        2-Methylnaphthalene        0.58
        4-Methylnaphthalene        0.11
        Naphthalene                0.11
        Phenanthrene               0.073
        Pyrene                      0.064
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1984
1987
10/91
3/25/92
             Background

Federal Facility   j
PRPs:  U.S. Army!Corp. of Engineers
FS prepared by:  Law Environmental
 2.     :What volume of material is to be remediated?

        The volume of material to be remediated included:

     ,    •      1,000 cubic yards of soil

                                                                     I • '

  3.      What type of site is'this?                                     ,

         Military.  The site consists of acid neutralization pits. The site is located on a facility that
         manages and furnishes military general supplies.  Land use in the vicinity is primarily single-
       '  family residential,  intermixed with retail stores and light industry.
                                              -1-
                                                                                             333

-------
   TECHNOLOGY SELECTION

   4.       What standard technologies were considered for selection in this FS?

           Standard technologies considered during the identification and screening of technically feasible
           technologies were:                                                              /   ,
          Access restriction:

          Containment:
                       Institutional controls (zoning and deed restrictions, restrictive
                       covenants, fencing, and warning signs)
                       Capping, vertical barriers                                 ]  '   .
 Chemical treatment:    Stabilization
 Physical treatment:     In situ soil aeration
 Thermal treatment:     Incineration (rotary kiln, fluidized bed, and circulating fluidized bed)
 n,cnocai-             Excavation, on-site landfill, off-site landfill
          Disposal:
  6.
334
 Was an innovative technology considered in the FS?  If so, which technology?

 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:                                                      :

 Biological treatment:  In situ biodegradation, ex situ solid phase, ex situ slurry phase
 Phys/Chem treatment: In situ chemical oxidation, ex situ soil washing, in situ vacuum
                      extraction                                               ,
 Thermal treatment:    Infrared thermal desorption, in situ steam stripping


 What was the cost estimate for the innovative technology?

During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
formulated, costs are estimated as part of a three-criteria screening process (effectiveness
implementabihty, and cost) to identify alternatives that merit a more detailed evaluation 'The
 "1      C°StS then "* recalculated durinS a" evaluation based on nine criteria established by
                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-7
Innovative Technology
Excavation/soil washing/backfilling with
cleaned soil
Excavation/solid phase biotreatment/
backfilling with treated soil
In situ vacuum vapor extraction/
capping
:=============================]
Estimated Costs
3 Criteria
$175,000
$75,000
$55,000
9 Criteria
eliminated
$194,208
$115,607
                                               -2-

-------
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-5
RAA-6 .,
RAA-8
RAA-9

Standard Technology
Multilayer, multimedia cap/grading/
surface water runoff collection
Excavation/solidification, stabilization/
backfilling with treated soil
Excavation/circulating1 fluidized bed
incineration
Excavation/off-site treatment/
backfilling with clean imported soil
Deed restrictions
No action
Estimated Costs
3 Criteria
$50,000
$180,000
$380,000
1 .
$350,000
• - i
$15,000
$0
9 Criteria
$43,135
eliminated
eliminated
eliminated
$15,000
$0
 8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
 9.      If an innovative technology was chosen, why?
                                                                        !        • i           •
        RAA-7, in situ vacuum vapor extraction, was chosen because it protects human health and the
        environment through the treatment of contaminated soils. This remedy also will mitigate the
        threat of contaminants leaching from the soils into the underlying ground water. RAA:7 meets
        all ARARs and treats soils to well below the proposed risk-based soil action levels.  It is the
        least costly of the alternatives identified that employ  treatment as a principal method of
        remediation.  By removing the contaminants of concern  from site soils, this option will
        effectively return the site to its original condition, and is therefore considered the most cost
        effective of the alternatives.  The selected alternative represents the maximum extent to which
        permanent solutions and treatment technologies can be utilized, and ikddresses the statutory
        preference of selecting a remedy that utilizes treatment,  which reduces the toxicity, mobility,
         or volume, as a principal element.


  10.     If an innovative technology was not chosen, why not? At what stage-was the innovative
         technology eliminated?
                   •     '   "           '            '•            *  ;..}•..('
         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages: during the initial screening; during the screening of the three criteria °f
         effectiveness, implementability, and cost; or during the  detailed evaluation.
                                                -3-
                                                                                                  335

-------
         Innovative technologies eliminated during the initial screening include the following:

         "      in S!*"biode8radation was eliminated because application of nutrients and surfactants
                 to shallow contaminated soils might eventually lead to the percolation both of
                 contaminants and of metabolic breakdown products to keeper zones of the soil and to
                 ground water, which is shallow at the site.
         •      In situ chemical oxidation was eliminated because adequate contact is generally
                 accomplished through mixing contaminated soils using augers, etc., and the use of
                 augers would be precluded by subsurface obstructions (i.e. the pits)
         •      In situ steam stripping was eliminated because, for application in the field, steam is
                 generally forced through hollow stem slotted augers, and the use of augers would be
                 precluded by subsurface obstruction (i.e., the pits).
         •   .   Ex situ slurry phase biological treatment was eliminated because the contaminated
                medium is primarily dry soil and large quantities of water would need to be added to
                achieve the appropriate solid/liquid composition; biological treatment does not achieve
                100-percent reduction of contaminants, an aqueous residual would  be generated that
                would require discharge or disposal; MCLs "are much lower for water than for solid
                media  and  therefore effluent controls on this process for the liquid wastestream
                would necessarily be more stringent than for a solid phase process" and would
                possibly require some form of secondary treatment or polishing step
                Infrared thermal desorption was_eliniinated because it was not selected as a
                representative thermal treatment.                                         ;    •-

                   teChn°10gieS eliminated during the screening of the three criteria include me
               Ex sou soil washing was eliminated. According to comments on soil washing, because
               removal efficiency is dependent on soil characteristics, the contaminants themselves
               and  he specific processes employed, the technology might not reduce contaminants'to
               low levels. Comments also state, however, that the technology would remove the
               source of contamination and leave soil clean, and that the site soils are conducive to
               implementation. It is therefore not clear why the technology was eliminated. :

        Innovative technologies eliminated during the detailed analysis include the following:

        "      ^ Si.tu S°"^se bi°trea"™nt was eliminated because the alternative will not satisfy
               treaSd'soll       * °r HaZard°US Waste Management Regulations for replacement of
                                                                                                     3
77.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? if so
 which criterion?  Which of the criteria supported the use of a standard technology?          '

Of the five balancing criteria, long-term effectiveness and permanence and reduction of
toxicity, mobility, and volume through treatment were the most heavily weighted  Bv
namnvinnr the Contaminants of cnnrv.rn  human t.ool+1, ancj jjj               o    •   j ,
       Failure to meet ARARs resulted in the elimination of RAA-4 (solid phase bibtreatmentX
336
                                              -4-

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?     \
•• . • ' , . ' • ' • 1
Contaminant
Cleanup Level (nig/kg)
ARAR oir Other Basis
Carcinogens
Arsenic
benzene
Chloroform
Tetrachloroethylene

Trichloroethylene.

Bis(2-
ethylhexyl)phthalate
5.7
360
1,700
200
0.58
16,000
0.20
740
Risk-based
Risk-based
Risk-based
Risk-based
Model
; Risk-based
Model
Risk based
Noncarcinogens
1 ,2-Dichloroethane
1 ,2-Dichlbroethylene
Toluene
Xylene
Di-n-butyl phthalate
1 ,2-Dichlorobenzene
Diethyl phthalate
Di-n-octyl phthalate
2-Methyhiapthalene
4-Methylnaphthalene
Naphthalene
Phenanthrene
Pyrene
110
0.022
1.3
2,400
24,000
1,200
1,100
9,700
240
600
480
48
85
11
Risk based
Model
: Model
Risk-based
Risk-based
Riisk-based
Risk-based
Risk-based
Risk-based
, Risk-based
Risk-based
Risk-based
Risk-based
Risk-based
                "Soil cleanup levels were calculated to protect ground water.] CeJculation parameters
                include K^., MCL, and a dilution factor of 55 (based on Summer's Equation).
                Other, cleanup levels were determined, but the chemicals were not found at
                concentrations exceeding those levels.
                                               -5-
                                                                                               337

-------
 13.
  For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6-
  was acceptable.  For noncarcinogens, a Hazard mdex less than or equal to 1.0 was acceptable.


  Was the innovative technology eliminated because of the cleanup goals? Could the standard
  technology meet the cleanup goals?                                ,  '     -      •

  Innovative technologies eliminated because of cleanup goals include:               '

  •      None

  Standard technologies eliminated because of cleanup goals include:                 '

  •      None                                .                                 '
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
 75.
 What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

      Total cost                                  .
      Time to design/construct/operate
      Preference for treatment (vs. containment)
16.    How are measures compared?

       RAA-7 is the cheapest alternative that employs soil treatment. RAA-4 and RAA-7 are
       compared in relation to the time needed to remediate the site, in that RAA-4 would complete
       remediation in a shorter time period. Preference for treatment was an important consideration
       in selecting in situ vacuum extraction, but was not used as a comparison between technologies
       Also, RAA-4 and RAA-7 are compared in terms of treatment in  that RAA-4 treats the • soil by
       breaking the contaminants into safe byproducts, whereas RAA-7 transfers the contaminants to
       carbon adsorption units.
17.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedy.  The presence of subsurface
obstructions prevented the use of augers, which eliminated in situ  chemical oxidation and in
situ steam stripping.  Also, possible contamination of the shallow  ground water was a factor in
eliminating in situ biodegradation.
 338
                                             -6-

-------
                            Dixie Caverns County Landfill
                                         OU-1

                                Roanoke County, Virginia
                                        Region3
.GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and mec
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Fly ash1 (KO61 Waste) (mg/kg)

       Antimony
       Arsenic
       Barium
       Cadmium
       Chromium
       Cyanide
       Lead
       Mercury
       Nickel
       Selenium ,
       Silver
       Thallium
       Zinc
linants,
iddressed in

ncipal

_\
g)
14
76
30
1,600
420
1.7
49,500
3.1
200

Site
NPL Proposed:
NPL Final:
FS:
Interim ROD:

History
'1/27/87
10/4/89
5/27/92
9/30/91
Background

EPA Fund-lead


PRPs: Roanoke County, Roanoke
Electric Steel Corporation (RES);
EPA identified other PRPs but
they are not listed.
FS prepared by: T

' --
1.5
31
0.9 ,
220,000
etraTech, Inc.






 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •    s  9000 cubic yards of fly ash
 3.      What type of site is this?

        Municipal Landfill.  A former municipal landfill in a rural setting.
     'This ROD is an interim action decision that addresses remediation of the fly ash pile only.
                                            -1-
                                                                                          339

-------
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?              '

          This Interim Action ROD was prepared before the RI/FS for the site was completed therefore
          technologies were not considered during an initial screening process.  EPA was able to
          develop this interim solution because sufficient information was available to determine the
          appropriate fly ash remedy.
  5.
 Was an innovative technology considered in the FS? If so, which technology?

 Innovative technologies were not considered.
  6,      What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to1 the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs typically are estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. The estimated costs then are recalculated during an evaluation based on nine
          criteria established by the NCP.  Costs were developed only in the Interim Action  ROD for the
          two interim remedial actions.  No innovative technologies were considered.
  7.
340
How did the cost(s) compare to standard technologies?

          Cost Estimates for RAAs That Include Standard Technologies
                    (selected remedial alternative is in bold)
            Alternative
          RAA-I
          RAA-2
                          Standard Technology
                  No action
                  Removal of fly ash and treatment in
                  off-site high-temperature metals
                  recovery facility
                                                                    Estimated Costs
                                                                     Interim ROD
                                                                           $0
                                                                       $3,927,158
 S.     If a standard technology was chosen, why?

        RAA-2 was selected because this alternative greatly reduces the risk of exposure to the fly ash
        pile by removing the waste from the site and using a recovery technology, High- Temperature
        Metals Recovery (HTMR).  HTMR reduces the toxicity of the fly ash and minimizes the
        volume of waste requiring land disposal. The mosf significant ARAR for RAA-2 is the RCRA
        Land Disposal Restrictions (LDRs).  Treating the fly ash via HTMR (which is the process on
        which EPA treatment standards in the KO61 LDR final rule were based) will assure that the
        fly  ash meets the KO61 treatment standards. EPA determined that HTMR represented the Best
        Demonstrated Available Technology (BOAT) for KO61 waste when the waste contains 15
                                              -2-

-------
       percent or more of total zinc (i.e., high zinc subcategory).  RAA-2 will be technically and
       administratively feasible. The excavation, removal, and transport of the fly ash is a standard
       site cleanup and construction procedure and should not present any unusual technical or
       administrative problems. An HTMR facility is also available.  The HTMR process has been
       proved to be an effective treatment method for fly ash material.

                                                                       i '•
9.      If an innovative technology was chosen, why?
             •                           •    '                  .       . i "'•.•'
       An innovative technology was not chosen.
                                                                   •    !'••--.
                                                                       i
                                                                         •
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                                                                       i,           •
       Innovative technologies could  be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                         '                         ~'
       Innovative technologies eliminated during the initial screening include the following:

       •      None

       Innovative technologies eliminated during the screening of the three c riteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis include the following:
                                                                    j
        •      None
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?
                                       -          •        '         '  •   !
        Overall protection of human  health and the environment, compliance with ARARs, and
        reduction of toxicity, mobility, and volume through treatment were heavily weighted in
        selecting RAA-2. RAA-2 protects human health and the environment from the risks posed by
        ingestion, dermal absorption, or inhalation of the fly ash by significantly reducing the toxicity
        and volume of the fly ash. The selected interim remedial action also includes  measures to  ,
        protect human health and the environment from accidental releases or migration of
        contamination from the fly ash through air emissions and  surface runoff.  In addition, RAA-2
        complies with all ARARs, particularly RCRA land disposal restrictions that apply to KO61
        wastes in the high zinc subcategory.
                                               -3-
341

-------
 12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Carcinogens
Lead
Cadmium
Cleanup Level (rag/kg)
ARAR or Other Basis

0.095
0.032
RCRA"
RCRA
                "Cleanup goals are based on on-site disposal criteria developed by EPA during the
                recent RCRA KO61 LDR ruling.
 13.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?       .

 Innovative technologies eliminated because of cleanup goals include:

 "      None                                                                  ;

 Standard technologies eliminated because of cleanup goals include:

 »      Stabilization (see Question 14) was eliminated because, based on currently available
        data, EPA was not confident that the  stabilization process could be readily 'operated at
        the site to achieve the appropriate health-based concentration levels.

14.
 Were treatability studies conducted on the innovative technology or standard technology?

 Roanpke County and Roanoke Electric Steel Corporation (RES) originally developed a
 stabilization and on-site disposal plan for remediation of the fly ash pursuant to the 1987
 Consent Agreement and Order with EPA.  Part of this plan consisted of preliminary treatability
 test data for stabilized fly ash from the site.  The EP Toxicity concentrations for lead and
 cadmium were 0.35 mg/L and 0.73 mg/L, respectively. These levels did not achieve the
 required treatment standards of 0.315 mg/L for lead and 0.063 mg/L for cadmium. However
 the disposal plan stated that with additional treatability efforts, the stabilization process could'
 be optimized to achieve these levels.   Since this treatability study was conducted significant
 changes were made in the delisting concentration level that must be achieved prior to on-site
 land disposal of the treated fly ash. The most  significant change occurred with respect to lead
 The LDR treatment standard using TCLP analysis for lead  is 0.37 mg/L.  Fly ash treated to
 this level would have to be disposed of in a RCRA Subtitle C/VHWMR hazardous waste
 landfill. For treated fly ash to be disposed of in an on-site RCRA Subtitle D/VSWMR solid
 waste landfill, TCLP analyses for lead would have to achieve  a level of 0.095 mg/L.  None of
the analyses performed using the RES stabilization process achieved the level of 0.095 mg/L
342
                                              -4-

-------
75.     What measures/criteria were used to compare alternatives?

       The following measures were used.to compare the alternatives:

    •   -    Cost-effectiveness
            Proven reliability
            Preference for treatment (vs. containment)


16.    How are measures compared?

       The selected interim remedial action is cost-effective because it greatly rediuces the risk posed
       by fly  ash at the site.  The HTMR process was selected because it has been proved to be an
       effective treatment method for fly ash material.  The selected remedy satisfies the statutory
       preference for treatment as a principal element.  RAA-2 addresses the primary threat of
       incidental ingestion of fly ash using the HTMR treatment process to reduce the toxicity,
       volume, and mobility of the fly ash.                                !
                                                                        I ' •
                                                                        i
                                           •  •      •                    -1
 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?
                                                                    'I
        Technical considerations were not primary in selecting this interim remedial action.
                                               -5-
                                                                                                343

-------
                                 Eastern Diversified Metals
                                      OU-1 and OU-2

                                 Rush Town hip, Pennsylvania"
                                           Region 3
                                                                                            „)
  GENERAL SITE INFORMATION

  /.     What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Fluff Piles (mg/kg)
         PCBs
         Lead
         Dioxin

         Soil (mg/kg)
               5,560
               40,000
               0.0185
DEHP
DNOP
PCBs
Dioxin
Lead
Copper
Zinc
Cadmium
3,300
720
240
0.071
1,920
108,000
1,230
7
        Sediment (mg/kg)
        DEHP
        PCBs
        Lead
        Copper
        Zinc
        Iron
        Aluminum
              4,000
              8.4
              1,300
              3,090
              7,850
              54,800
              30,500
                                                         Site History
                                            NPL Proposed:
                                            NPLFinal:
                                            FS:
                                            ROD:
                     N/A
                     10/5/89
                     1/8/91
                     3/29/91
             Background

PRP-lead
PRPs:  Theodore Sail, Incorporated
       AT&T Nassau Metals
       Coiporation
FS prepared by:  Environmental
       Resources Management
       Incorporated
 2.
344
What volume of material is to be remediated?

The volume of material to be remediated included:

"      500 cubic yards of dioxin-contaminated fluff
•      5,160 cubic yards of PCB-contaminated fluff
"      480 cubic yards of lead-contaminated soil
                                           -1-

-------
               120 cubic yards of metal-contaminated sediments
3.       What type of site is this?
                                                                         I
        Recycling.  A former metals reclamation facility that is bordered by both residential and
        industrial areas.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?    ,

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                                                                         \      '     •
        Fluff Piles
        Access restriction:
        Containment:
        Physical/chemical:
                      Fencing, deed restrictions  «                i
                      Capping (single layer, synthetic membrane, multilayer), revegetation
                      Stabilization/solidification, thermoplastic solidification
Physical treatment:    Recycling (bulk processing, physical separation, resin recovery),
                      grading^ dikes, berms, channels, ditches      f
Thermal treatment:    Incineration (on-site and off-site)
        Soil and Sediment
        Chemical treatment:    Stabilization/solidification, thermoplastic solidification
        Physical/chemical:      Physical separation
        Thermal treatment:.    Incineration (on-site and off-site)           |
        Disposal:              Disposal (on-site and off-site)
 5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Fluff Piles                                                      I

         Physical/chemical:     Contaminant extraction, in situ flushing     !
                                                                         I •         '
         Soil and Sediment       ,                                       i
  '  '  j                 ' -        -                     '                    i "       =
         Physical/chemical:     Contaminant extraction, in situ soil flushing
         Thermal  treatment:    In situ vitrification                        !,.    '
                                                , -2-
                                                                                                     345

-------
  6.      What was the cost estimate for the innovative technology?                -

         Turing the initial screening process, in which technically f-isible technologies are identified
         U '
-------
Alternative
RAA-3B &
GW-4
RAA-4 &
GW-2
RAA-4 &
GW-4
RAA-5 &
GW-2
(RAA-4)
RAA-5 &
GW-4 "
RAA-6

Standard Technology
Fluff recycling by plastics separation/
on-site incineration of fluff and soil/
stabilization of ash/off-site ash disposal/
shallow and deep ground water
collection and treatment
In-place closure/on-site incineration of
fluff and soil/stabilization of ash/off-site
ash disposal/multilayer cap/shallow
ground water collection and treatment
In-place closure/on-site incineration of
fluff and soil/stabilization of ash/off-site
ash disposal/multilayer cap/shallow and
deep ground water collection and
treatment
On-site incineration/stabilization of
ash/off-site ash disposal/shallow ground
water collection and treatment
On-site incineration/stabilization of ash/
off-site ash disposal/shallow and deep
ground water collection and treatment
Off-site disposal at RCRA permitted
landfill
Estimated Costs
3 Criteria
not proposed
i • ' -
$14,182,000
1
not proposed'
i
i
$149,7(X),000
to
$636,024,000
not proposed
- -. •
'
$88,650,000
-r
• \ - ' .
9 Criteria1
$16,187,000
to
$19,333,000
$14,804,000
$17,745,000
$150,322,000
to
$636,803,000
$154,013,000
to
$641,562,000
eliminated
"Ground water remedial actions were added to several alternatives in the detailed analyses
stage. The higher cost reflects the addition of ground water femediatijon.
        • '                           .                          !          •
Proposed Plan and ROD                                        j
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action
Limited action/ground water collection/
monitoring
Excavation/incineration/stabilization/
consolidation or disposal off site
Excavation/incineration/stabilization/
consolidation or off-site disposal/shallow
ground water collection, treatment, and
studies





ROD
$0 ' -
$966,000
$11,567,000
$12,429,000
                                       .4.
347

-------
               Alternative
             RAA-5
                                 Standard Technology
                    Excavation/incineration/stabilization/
                    consolidation or disposal off site/shallow and
                    deep ground water collection and treatment
                                                                                    ROD
                                                                                 $15,843,800
    8.      If a standard technology was chosen, why?

           Incineration, a standard technology, was preferred because it will destroy the greatest amount
           of organic constituents (phthalates, PCBs, and dioxin) in the fluff and soils.  In addition
           incineration will reduce the volume of contaminated media by 80 percent. Because of the
           presence of dioxins and PCBs, the incinerator will be required to achieve 99.9999 percent
           destruction efficiency for all hazardous organic constituents.  An on-site incinerator was
           suggested because it is readily available and will eliminate the need to transport contaminated
           matenals off site. The elimination of contaminants through incineration will be permanent and
           complete. Any residuals/metals in ash, soils, or sediments will be stabilized, a technology that
           is considered effective and proven to reduce toxicity and mobility of contaminants, this
           alternative was also preferred because it addresses ground water contamination.
   9.     If an innovative technology was chosen, why?

          An innovative technology was not chosen.
   10.
348
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                       .

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
                                                           •                     E
Innovative technologies eliminated during the initial screening include the following:

•       None                                                       -

Innovative technologies eliminated during the screening of the three criteria include the
following:

Fluff Piles
                                                                               !       '

*       Contaminant extraction (solvent extraction) was eliminated because of its limited
        effectiveness since the contaminants are adsorbed to the fluff and it might not remove
        lead. Furthermore, the availability of the technology is limited, it would generate
        wastewater that would require treatment, and pilot testing would be necessary;
»       In situ flushing was eliminated because it is not  appropriate for site contaminants,  its
        availability is limited, and it would require pilot testing.  Furthermore, it  would
        generate.wastewater that would require recovery and treatment and it could potentially
                       !                 .                            ,           ..""

                                       -5-        .           •        '           '

-------
                      increase ground water contamination.

               Soil and Sediment
                      Contaminant extraction (solvent extraction) was eliminated because its effectiveness is
                      unknown since site contaminants are bound to plastics.  It might not meet cleanup
                      goals, services would be limited, it would generate wastewater that would require
                      treatment, it would require excavation of fluff piles, and it would require a pilot study.
                      In situ soil flushing was eliminated because it would not be appropriate for site
                      conditions since recovery of flushing solution would be difficult and it could
                      potentially increase ground water contamination.  In addition, services are limited, the
                      elutriate would require treatment, and a pilot  study would be necessary.
                      In situ vitrification was eliminated because it would be too costly, it has not been
                      'demonstrated on a remedial scale, services are limited, and a pilot study would be
                      needed.
               Innovative technologies eliminated during the detailed analysis include the following:

               •      None
o
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Long-term effectiveness and the reduction of contaminant toxicity, mpbility, and volume were
       the criteria that were weighted most heavily in selecting a remedial alternative.  In situ
       vitrification was eliminated because of its associated excessive costs.        '
        12.     What cleanup goals were selected? If the cleanup goal was based on ah ARAR,  what was that
                ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens ,
Dioxin
PCBs
Lead
0.020
25
1000
\ EPAa
TSCA"
JOSWERC
                       "Previous EPA remediation level set for Times Beach, Missouri.
                       bToxic Substances Control Act.                           j
                       COSWER Directive #9355.4-02.
                                                       -6-
                                                                                                  349

-------
   75.     Was the innovative technology ei'-ninated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?
                                                               .                  j       .    '  '
          Innovative technologies eliminated because of cleanup goals include:

          •      Contaminant extraction in soil and sediment        '   ••

          Standard technologies eliminated because of cleanup goals include:

          •      None                                                          ,


   14.     Were treatability studies conducted on the innovative technology or standard technology?

          No treatability studies were'conducted.                    '


   75.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

               Proven reliability                                                    .


   16.     How are measures compared?                                                                  "__   .  ,

          The chosen standard technologies were preferred because .their effectiveness was well- known.      ^^ *
          Several innovative technologies were eliminated because their effectiveness was questionable.


  17.     What technical considerations were factors in selecting a remedy? Were technical
          considerations primary in the selection of the remedy?                                   ••'•'.

          The site has no subsurface impervious unit. Therefore, in situ soil flushing could not be   :
          implemented,  since it would be difficult to develop a elutriate collection system. This
          technique potentially could enhance the mobility of contaminants into the ground water. This
          factor was not primary in  selecting a remedy.
                                                                                                             W)
                                                                                                              ;
350
                                                -7-

-------
                               Eastern Diversified Metals
                                           OU-3

                                Rush Township, Pennsylvania
                                          Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Fluff Piles (mg/kg)
       PCBs
       Lead
       Dioxin
5,560
40,000
0.0185
2.     What volume of material is to be
       remediated?

     ,  The volume of material to be remediated
       included:

       •      239,000 cubic yards of fluff
                                            Site History
                               NPL Proposed:
                               NPL Final:
                               FS:
                               ROD:
                     N/A
                     10/5/89
                     1/8/91
                     7/2/92
             Background
                  i
PRP-lead
PRPs:  Theodore Sail, Incorporated,
       AT&T, Nassau Metals '
       Corporation     '•
FS;prepared by:  Environmental
       Resources Management
       Incorporated
3.      What type of site is this?    ,               '•.'',-

   '     Recycling. A former metals reclamation facility that is bordered by both residential and
        industrial areas.                                                  ••'
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS? \
                 '            • ;     •                                   !•...''
 ™             •                      '           '                      I          i  ,
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:     Fencing, deed restrictions                                 '   ,
        Containment:          Capping (single layer, synthetic membrane, multilayer), revegetation
      ,  Physical/chemical:     Stabilization/solidification, thermoplastic solidification
        Physical treatment:     Recycling (bulk processing, physical separation, resin recovery),
                             energy recovery, grading, dikes, berms, channels, ditches
        Thermal treatment:     Incineration (on-site and off-site)           .!..'.
                                              -1-
                                                                                              351

-------
   5.      Was an innovative technology considered in the FS?  If so, which :.chnology?

          Innovative technologies considered during the-identification:and screening of technically
          feasible technologies were:
                                    .                                                   r
          Physical/chemical:     Contaminant extraction (solvent extraction), in situ flushing
   6.      What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
          implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
          estimated costs then are recalculated during an evaluation based on nine criteria established by
          the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
          ARARs; protectiveness of human health  and  the environment; reduction in contaminant
          mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
          community acceptance.
                                                                                       i
          RAAs were condensed  in the ROD and are presented separately in the following section.

          No innovative technologies were incorporated into remedial alternatives.
   7.      How did the cost(s) compare to standard technologies?

                    Cost Estimates for RAAs That Include Standard Technologies
                               (selected remedial alternative is in bold)

          Feasibility Study
352
Alternative
RAA-1
RAA-2
RAA-3A&
GW-2
RAA-3A &
GW-4
Standard Technology
No action/long-term maintenance
Limited additional action/regrading
surface water control/deed restrictions
Fluff recycling by bulk processing/ on-
site incineration of fluff and soil/
stabilization of ash/off-site ash disposal/
shallow ground water collection and
treatment
Fluff recycling by bulk processing/ on-
site incineration of fluff and soil/
stabilization of ash/off-site ash disposal/
shallow and deep ground water
collection and treatment
Estimated Costs
3 Criteria
$966,000
$1,181,000
$8,536,000 to
$15,249,000
not proposed
9 Criteria3
$966,000
eliminated
$9,159,000
to
$15,872,000
$13,350,000
ito
$20,064,000
-2-

-------
Alternative
RAA-3B &
GW-2
RAA-3B &
GW-4
RAA-4&
GW-2
RAA-4&
GW-4 ,
RAA-5 &
GW-2
RAA-5 &
GW-4
RAA-6
Standard Technology
Fluff recycling by plastics separation/
on-site incineration of fluff and
soiystabilization of ash/off-site ash
disposal/shallow ground water
collection and treatment
Fluff recycling by plastics separation/
on-site incineration of fluff and
soil/stabilization of ash/off-site ash
disposal/shallow and deep ground water
collection and treatment
In-place closure/on-site incineration of
fluff and soiystabilization of ash/off-site
ash disposaymultilayer cap/shallow
ground water collection and treatment
In-place closure/on-site incineration of
fluff and soiystabilization of ash/off-site
ash disposaymultilayer cap/shallow and
deep ground water collection and
treatment
On-site incineration/stabilization of
ash/off-site ash disposayshallow ground
water collection and treatment
On-site incineration/stabilization of ash/
off-site ash disposayshallow and deep
ground water collection and treatment
Off-site disposal at RCRA-permitted
landfill
Estimated Costs
3 Criteria
$11,374,000
tp
$14,520,000
not proposed
$14,182,000
not proposed
$149,7013,000
to
$636,024,000
not proposed
$88,650,000
9 Criteria3
,$11,996,000
to
$15,142,000
$16,187,000
to
$19,333,000
$14,804,000
$17,745,000
$150,322,000
to
$636,803,000
$154,013,000
to
$641,562,000
eliminated
"The higher cost reflects ground water remediation costs, added to several illternatives during

the detailed analysis stage.
                                                               I    • '   '    '      .
                                                               1
Proposed Plan and ROD                          .                     ,
Alternative
RAA-1
RAA-2
RAA-3
1 Standard Technology
No action '
On-site recycling of flufffdisposal of nonrecyclab
and recycling residuals
RCRA multilayer cap


les

9 Criteria
$0
$13,100,000
to
$21,900,000"
$15,000,000
                                      -3-
353

-------
Alternative
RAA-4
Standard Technolog;
Excavation/incineration/off-site disposal of ash ,
9 Criteria
$150,000,000
to
$636,000,000
          "Costs will vary depending on the recycling technology used, the number of machines placed
          on site, the volume of nonrecyclables and recycling residuals, and whether the residuals are
          hazardous and need treatment.
  8.      If a standard technology was chosen, why?

          RAA-2 was selected because it will prevent exposure through dermal contact, inhalation, and
          ingestion, and the further release of hazardous substances from fluff materials into soils
          sediments, surface water, and ground water at the site. Recycling will reduce current and
          potential site risks by reducing contaminant mobility through the encapsulation of the
          contaminants  in a recycled product. Recycling will provide a high level of protection because
          the fluff will be converted to a nonhazardous form and will be removed from the site through
          distribution of the recycled product and the disposal of residuals.  The volume of the fluff
          piles will be reduced by 60 to 95 percent.  Toxicity will  be reduced because the recycling
          technology  will render the materials nonhazardous and physically inseparable from the product.
          This remedy provides a high degree of long-term effectiveness and permanence since the fluff
          piles will be removed from the site. Recycling can be easily implemented because standard,
          readily available machinery is used. Markets for recycled fluff products are expected to be
          easily identified.  RAA-2 is the most cost-effective alternative.                   ;
  9.      If an innovative technology was chosen, why?

          An innovative technology was not selected.
  JO.
354
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•     An initial screening was not done in this FS.

Innovative technologies eliminated during the screening of the three criteria include,the
following:

»     Contaminant (solvent) extraction was eliminated because it is unlikely that lead could
       be  extracted or washed from the surface of the plastic fluff as lead is thought to be an
                                                 -4-

-------
11.
              inherent component of the plastic.  Furthermore, the  availability of the necessary
              equipment and workers to implement the process is limited as jit is an emerging
              technique. It would generate wastewater that would require treatment, and pilot testing
              would be necessary.
       •      In situ flushing was eliminated because an impervious unit beneath the area of concern
              does not exist at the site which does not allow efficient collection of contaminated
              extraction fluid. Application of a flushing solution may enhance constituent mobility.
            ,  Installation of an elutriate collection system would require an extensive effort that may
              result in exposure to site contaminants.  There is limited availability of the necessary
              equipment and site  workers to implement the technology.  A treatment system for
              spent extraction fluid would be required. Costs would be very high because of the
              elutriate system.  Remediation time would be very long.
                                                                        ! '
       Innovative technologies eliminated during the detailed analysis includes the following:

       •      None                               - .              '!.''.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion? Which of the criteria supported the use of a standard technology?
  .  . •      •              '  •                   '         '          i
The criteria that were weighted most heavily in selecting a remedial alternative were  long-
term effectiveness and cost.  The chosen alternative was preferred because it will provide a
long-term and permanent reduction of contaminants and it is  the most protective alternative for
the least cost.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What, risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAB, or Other Basis
Carcinogens
Dioxin
PCBs
Lead
0.020
25
1000
1 EPAa
; TSCAb
OSWERC
               "Previous EPA remediation level set for Times Beach, Missouri.
               'Toxic Substances Control Act.
               COSWER Directive #9355.4-02.
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?         '       ,               j
                                          •             •                 !               •
        Innovative technologies eliminated because of cleanup goals include:

        •      None
                                               -5-
                                                                                           355

-------
          Standard technologies eliminated because of cleanup goals include:

          *      None


  14.     Were treatability studies conducted on the innovative technology or standard technology?

          No treatability studies were conducted.                                         ,


  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

               Cost-effectiveness
               Preference for treatment (vs. containment)
               Time to design/construct/operate                                 •        \  •     •  -


  16.     How are measures compared?

         RAA-2 was chosen because it treats site contaminants thereby reducing their toxicity  mobility
         and volume. Treatment was preferred over containment because site  contaminants will be
         permanently eliminated. The chosen alternative also was preferred because it is the most cost-
         effective option.  The estimated cost for RAA-2 is comparable to that for RAA-3 but RAA-2
         provides greater protection.  RAA-2 offers a  similar level of protection as RAA-4  but at a
         much lower cost. The time to implement was compared between alternatives in the ROD
         The selected alternative, RAA-2, would take  about 5 to 10 years, RAA-3 only 2 to 3 years but
         would  not be a permanent remedy, and incineration would take 9 to 87 years.   •'   i   . •'


 17.      What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                            :


        Since the site has no subsurface impervious layer, in situ soil flushing could not be
        implemented, because it would be difficult to develop a elutriate collection system  This
        technique could enhance the mobility  of contaminants into the ground water.  This factor
        however, was not primary in selecting a remedy.                                     '
                                                                                                          1
356
                                              -6-

-------
                   First Piedmont Corp. Rock Quarry (Route 719) j

                                     Danville, Virginia
                                         Region 3
GENERAL SITE INFORMATION
/. What were
contaminant
the principal contaminants,
levels, and media addressed in
this feasibility study?

Maximum
contaminants

Soil (mg/kg)

Arsenic •
Barium
Cadmium
Chromium
Lead
Nickel-
^ Vanadium
P Zinc
W/
O • '\A7hsit \if\litwtG

concentrations of principal
were:



135
9,900
34.5
39.5
145
66
23
7,13 , . •
nf -winter-in] FC tn h& r0mp/1iflt0s??.


Site History

NPL Proposed: N/A.
NPL Final: 7/21/87
FS: 1/91
ROD: 6/28/91

Background

PRP-lead
PRPs: First Piedmont Corporation,
Corning Glass Works, and The Goodyear
Tire and Rubber Company
FS prepared by: Westinghouse
Environmental and
Geotechnical Services,
Inc.
i
       The volume of material to be remediated included:

       •     65,000 cubic yards of industrial and agricultural landfill waste
       •     3,000 cubic yards of soil    "         .
       •     100 cubic yards of carbon black
       •     10 cubic yards of a separate waste pile              ,    ,
..3.      What type of site is this?                                      .     i   ,
            '  •  ' •    .     t        •      '            .              ,      l                •
        Industrial Landfill.  An abandoned rock quarry and associated landfill located in a rural/residential
        area.                          .                                  '!  '
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening pf technically feasible
        technologies were:              .                 (  ,               !  '

        Access restriction:     Fencing, deed restrictions
                                             -1-
357

-------
         Containment:
         Chemical treatment:
         Thermal treatment:
         Disposal:
Capping (clay, asphalt, concrete, multimedia), grouting
Stabilization/solidification, ion exchange
Incineration
Excavation, disposal (on-site, off-site)
         Was an innovative technology considered in the FS? If so, which technology?     •

         Innovative technologies considered during the identification and screening of technically feasible
         technologies were:

         Biological treatment:    Biological treatment (aerobic, anaerobic)
         Phys/Chem treatment:   Solvent extraction (soil washing)
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified (prior
        to the formulation  of RAAs), the  FS does not quantify costs.  After the RAAs  have been
        formulated, costs are typically estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  In this
        case, the estimated costs were calculated  during an evaluation based on nine criteria established
        by the NCP.  Innovative technologies were not incorporated into RAAs.


 7.      How did the cost(s) compare to standard technologies?          '

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Fencing/deed restrictions/ground water
monitoring
Institutional controls/excavation/off-site
disposal of non-landfill waste/landfill
cap/leachate treatment '
Institutional controls/excavation/
treatment and on-site disposal of non-
landfill waste/landfill cap/leachate
treatment
Institutional controls/excavation/
treatment and either on-site or off-
site disposal of non-landfill waste/
landfill cap/leachate treatment at
POTW
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$0
$285,400
$2,120,500
$2,035,000
$2,154,000
358
                -2-

-------
Alternative
RAA-6
RAA-7
' F
RAA-8
RAA-9
Standard Technology
Institutional controls/excavation/
treatment and either on-site or off-site
disposal of non-landfill waste/landfill
cap/on-site leachate treatment
Institutional controls/excavation/
treatment and either on-site or off-site
disposal of non-landfill waste/landfill
cap/slurry wall/leachate treatment at
POTW
Institutional controls/excavation/
treatment and either on-site or off-site
disposal of non-landfill waste/consolida-
tion of landfill waste including a liner
and an undei drain system, landfill cap/
leachate treatment on site or at POTW
Institutional controls/excavation/
treatment and on-site or off-site disposal
of non-landfill waste/in situ stabilization
of landfill waste/landfill cap
Estimated Costs
3 Criteria
N/A
-I
I
N/A
1
N)A
•N7A
i
i
9 Criteria
$2,340,000
$1,889,000
$4,450,000
$4,940,000
8.      If a standard technology was chosen, why?                         \  ~ '.   •  •
                                             '    '                      I '
       RAA-5 was  selected because  it protects  human health  and the environment  by reducing
       contaminant levels through the excavation and treatment of non-landfill waste. Treated waste w,ill
       be disposed of in an off-site facility.  It will ensure the elimination of exposure due to direct
       contact with the landfill wastes, by constructing  a RCRA Subtitle C cap over the landfill thereby
       meeting  RCRA closure requirements.   The implementation  of  deed restrictions to prohibit
       residential  development of  the  site will  further augment reducing  the  potential for direct
       contaminant exposure. Landfill closure will reduce the likelihood  of contaminant migration and
       contaminants  in the landfill  leachate will be reduced by leachate collection and treatment at a
       POTW.  It will pose no  short-term risk or cross-media impacts. Of all the alternatives, RAA-5
       provides the  best protection  of human  health  without  significant  adverse  impact to the
       environment.  It complies with all ARARs and will be the most technically feasible to implement.
       If an innovative technology was chosen, why?

       An innovative technology was not selected.
                                              -3-
359

-------
 10.
 If an innovative technology was not chosen, why not? At what stage was the innovative technology
 eliminated?                                                               "

 Innovative technologies could be eliminated from the remedial technology selection process at
 three  stages:   during  the initial  screening; during  the  screening  of the three  criteria  of
 effectiveness, implementability, and cost; or during the .detailed evaluation.

 Innovative technologies eliminated during the initial screening include the  following:

 •      Biological  treatment (aerobic,  anaerobic) was  eliminated because it would not be
        applicable to inorganic contaminants.

 Innovative technologies eliminated during the screening of the three criteria include the following:

 •      Solvent extraction (soil washing) was eliminated because it might generate heavy metal
        sludge, there would be potential for spills and for contamination to spread, the nature of
        the waste would not lend itself to this technology because it employs mixing, and,finally
        there is insufficient space on site to stockpile material.

 Innovative technologies eliminated during the detailed analysis include the  following:

 •      None
u.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

 Protection  of human  health arid  the environment, long-term effectiveness,  and  short-term
 effectiveness were the criteria weighted most heavily in selecting a remedial alternative. RAA-5
 was selected because it offers the greatest long-term protection while minimizing short-term risk
 and implementation time.
72.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
                    Contaminant
                                 Cleanup Level (rag/kg)
ARAR or Other Basis
                Carcinogens
                Lead
                                                 500
                                                                OSWER"
              "Office of Solid Waste and Emergency Response (OSWER) Directive 9355.4-02
  360
                                              -4-

-------
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •      None

        Standard technologies eliminated because of cleanup goals include:

        •      None
14.
Were treatability studies conducted on the innovative technology or standard technology?

Treatability studies were not conducted.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Time to design/coristruct/operate
        -     Preference for treatment (vs. containment)
             Impact on nearby populations
             Risk reduction/protection to human health


16.     How are measures compared?

        RAA-5 was selected because it offers the greatest protection in the long term while minimizing
        short-term risk and implementation time.  RAA-1 and RAA-2 were eliminated because they would
        not be protective of human health or the  environment.  RAA-3 arid RAA-4 would not  have
        provided a permanent solution as they relied on a passive leachate treatment system while the
        selected alternative will collect and treat leachate. Furthermore, RAA-5 will allow natural flushing
        of water through the landfill which will be collected and treated, thereby ultimately reducing the
        time needed for leachate treatment. RAA-5 offers greater long-term effectiveness that RAA-8 and
        RAA-9 which reduce but do not eliminate the flow of ground  water.   The on-site  leachate
        treatment system proposed in RAA-6, RAA-7, and RAA-8 was not preferred because it y/ould be
        in an unmanned location where a malfunction could go undetected. RAA-7, RAA-8, and RAA-9
        also were  not preferred because they would require landfill excavation which would pose short-
        term risk to site workers and the community. RAA-9 would be the most difficult to implement
        because it would require the excavation of buried drums prior to treating the landfill waste. RAA-
        8 would be  too complex to implement because it would be difficult to determine appropriate
        engineering controls to prevent the production of contaminated water or sediment that might occur
        from precipitation falling into the open face of the landfill during excavation of the landfill.
17.     What technical considerations were factors in selecting a remedy? Were technical considerations
       primary in the selection of the remedy?                       .

       Technical considerations were not primary in selecting a remedial, alternative.
                                             -5-
                                                                                      361

-------
                                  Halby Chemical Co.
                                          OU-1

                                  Wilmington, Delaware
                                         Region 3
GENERAL SITE INFORMATION

L      What were the principal contaminants,
       contaminant levels,' and met
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Lagoon Sediment (mg/kg)

       Arsenic
       Chromium
       Pyrene
       B enzo(a)anthracene
       Chrysene
       Benzo(b)fluoranthene
       Benzo(k)fluoranthene
       Benzo(a)pyrene
lihants,
addressed in

ncipal

>•

872
170
17,861
5,334
6,051
3,597
3,155
2,337
Site History
NPL Proposed: 9/85
NPL Final: 6/86
FS: 4/91
ROD: 6/28/91
Background

EPA Fund-lead ;
PRPs: Argus Chemical Coiporation,
Witco Corporation, Brandy wine
Chemical Company
FS prepared by: NUS Corporation


2.      What volume of material is to be remediated?       •                               •

       The volume of material to be remediated included:                        -

       •      10,300 cubic yards of soil3


3.      What type of site is this?

       Chemicals and Allied Products.  An active chemical processing facility in an industrial area.


TECHNOLOGY SELECTION                                     '

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
    The proposed plan and feasibility study for OU-1 included the remediation of the contaminated
lagoon sediments. In the RODy EPA decided to defer lagoon sediment to OU-2 to gather more
information regarding tidal and ground water movement in the lagoon.
362
-i-

-------
       Access restriction:
       Biological treatment:

       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
   Fencing, deed restrictions, zoning, warning signs ,
   Capping (clay, silt, concrete stone clean fill, multilayer RCRA), slurry
   wall, grout curtain, sheet piling                ,
   Stabilization/solidification
   Dewatering     ,                                 ,
   mcineration (off-site, on-site)     ,         . j
   Excavation, dredging, off-site landfill, on-site landfill
5.       Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Composting, bioreactor, in situ'biodegradatiori
        Phys/Chem treatment:  Soil washing (surfactant), solvent washing, critical fluid extraction, in
                             situ soil flushing, in situ  soil venting                   v
        Thermal treatment:    Low-temperature desorption, in situ vitrification, radio frequency
        i                     heating                                          '
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on niiie criteria established by
        the NCP.     .            ,                   .               '     |   ...''•'••
                                                               ,, •    '    I
        No innovative technologies were incorporated into remedial technologies.
       How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)

       Soil
           Alternative
         RAA-S-1
         RAA-S-2
         RAA-S-3
         RAA-S-4
        Standard Technology
No action/monitoring
Deed restrictions/fencing/monitoring
Asphalt cap/deed restrictions/
monitoring
Surface soil (top 6 inches)
stabilization/asphalt cap
                                                                        Estimated Costs
3 Criteria
 $655,000
 $696,000
$Ui88,000
$1,586,000
9 Criteria
 $655,000
 $696,000
$1,188,000
$1,586,000
                                               -2-
                                                                        363

-------
Alternative
(RAA-S-4A)"
RAA-S-5
Standard Technology
Stabilize soil above water table with
contaminants in excess of cleanup
levels/asphalt cap
Excavation/off-site disposal
Estimated Costs
3 Criteria
N/A
$5,610,000
9 Criteria
$2,700,000
$5,610,000 "
        *RAA-S-4A was developed in the ROD and represents a slight modification of RAA-S-4.

        Lagoon sediment0
Alternative
RAA-L-1
RAA-L-2
RAA-L-3
RAA-L-4
RAA-L-5
RAA-1-6
Standard Technology
No action/monitoring
Institutional controls/public awareness/
monitoring
Soil cap
Stabilization/on-site disposal
In situ stabilization
Excavation/off-site disposal
Estimated Costs
3 Criteria
$0
$75,000
$1,266,000
$6,524,000
$3,421,000
$11,233,000
9 Criteria
r$o
$75,000
$1,266,000
eliminated
$3,421,000
$11,233,000
        *Lagoon sediment RAAs were developed in the FS but they were hot carried through to the,
        ROD. In the ROD, the scope of OU-1 was defined as soil inside the process area and lagoon
        sediment was incorporated into OU-2.
8.      If a standard technology was chosen, why?

        RAA-S-4 was chosen because it reduces the human health risk associated with direct contact
        and ingestion of soil and with inhalation of particulates by immobilizing the contaminated soil
        and containing the treated soil beneath an asphalt cap. The chosen alternative reduces
        contaminant mobility through stabilization, and reduces infiltration and runoff due to rain
        water through capping.  This alternative reduces site risk to within acceptable levels of 107* to
        10'6. Deed  restrictions and fencing ensures that the cap is not disturbed, although long-term
        maintenance is required. The selected remedy will not require the,process plant to be shut
        down and it eliminates site health risk to workers at the Halby Chemical  site. RAA-S-4
        utilizes proven technologies and will be easily implemented in a relatively short amount of
        time. The chosen alternative is cost-effective since it will meet cleanup goals through'
        immobilization at much less expense than other proposed alternatives.              ;
364
                                              -3-

-------
J?.  ,    If an innovative technology was chosen, why?
                                                                          •
       An innovative technology was not chosen.

                                                                         i. '

10.    If an innovative technology was not chosen, why not?. At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability,  and cost;  or during the detailed evaluation.
                                           1'  •                           !
       Innovative technologies eliminated  during the initial screening include the following:

       •      Solvent washing was eliminated because it would not be feasible or effective on
               inorganic contaminants.   ,                                  j
       •      Critical fluid extraction  was eliminated because it would not lie feasible or effective on
               inorganic contaminants.
       •      Low-temperature desorption was eliminated because inorganics would remain in
               treated soil.
       •      Composting was eliminated because it would not be feasible for. inorganics.
       •      Bioreactor was eliminated because it would not be feasible foir inorganics.
       •      In situ biodegradation was  eliminated because it has limited effectiveness on complex
               PAHs and no effectiveness  on inorganics.
       •      In situ soil flushing was eliminated because of the risk of contjaminating ground water.
               Also, it would not be feasible due to extended treatment time.       ,
       •      In situ soil venting was eliminated because  most PAHs have low vapor pressure; that .
               would limit the effectiveness of the technology and inorganics; would not be treated.
       •      In situ vitrification was eliminated because  it would not be feasible at sites with high
               water tables.
       •      Radio frequency heating was eliminated because it would not be feasible due to the
               relatively low vapor pressure of site contaminants.                   ,
             1               *  .-           : •          "           "'                ' "
       Innovative technologies eliminated  during the screening of the three criteria include the
       following:                                                        !'.,..
                                ''                      -       -            I          /
       •      Soil washing  was  eliminated because its effectiveness was fpuitid to be limited in a
               treatability study that demonstrated that contaminants were noli removed.

       .Innovative technologies eliminated  during the detailed analysis include! the following:
                                                                         i
       • •     'None          .  '    '   •        .      .   ' ' -  •       '•'.'!'


11.    Which of the nine criteria were weighted most heavily in selecting the ^technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria that were most heavily  weighted in selecting a remedial alternative were cost and
       meeting cleanup levels. The chosen alternative meets cleanup levels for the least possible cost.
       Other alternatives would have been more protective since contaminated soil would have been
                                                                         I
         :       .           ,                      •        -               I - '-     - ' '

                                               4                                                    365

-------
        moved off site or soil would have been remediated to greater depths, but these alternatives
        were not considered cost-effective.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens .
Arsenic
PAHs
10
1.2
Background8
Background
               "No federal or state chemical specific cleanup levels for soil exist; therefore, the
               cleanup level for the site was based on background levels. Additional sampling will
               be conducted to establish more statistically representative background sample values,
               which will be used as the final cleanup levels for arsenic and PAHs.
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        »      None

        Standard technologies eliminated because of cleanup goals include:

        •      None
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies conducted during the RI determined that soil washing would not;be
        effective at the site (contaminants were not removed) and that stabilization would be
        appropriate for the site's soil. Further treatability studies will be necessary to ensure adequate
        immobilization of arsenic.     '                   •                                      ,
       What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Cost/unit risk                                        .
             Preference for treatment (vs. containment)
  366
                                              -5-

-------
16.    How are measures compared?                                      ,
                                                                       1            "
                                                                       •!
       The chosen alternative was preferred over some alternatives because it  both treats and contains
       contaminated soil. It was considered superior to RAA-3 because it minimizes risk subsequent
       to cap failure. RAA-4 was preferred because it is cost-effective; it meets cleanup levels at the
       least cost.  While RAA-5 would be more protective since contaminated soil would be moved
       off site, this alternative would be much more costly. Similarly, RAA-ftA would be somewhat
       more protective since greater depths of contaminated soil would be treated, but it would be
       more costly and it was not considered significantly more protective than the chosen alternative
       since contaminants would still remain on site.                      ;

                           '            •          •                      !
                                                                       i
                                                                       i
77.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?              \
                                                                       . i
      ,                                                        .if
       No technical considerations were primary in the choice of a remedial iilternative.  One
       innovative technology, in situ vitrification, was eliminated because the water table was too
       high.
                                             -6-
367

-------
                             Hellertown Manufacturing Co.

                             Northampton County, Pennsylvania
                                         Region 3
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Lagoon area soil (mg/kg)

       Trichloroethene       0.56
       PAHs                108
2.      What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       •      76,000 cubic yards of lagoon area soil
                                                          Site History
                                             NPL Proposed:
                                             NPL Final:
                                             FS:
                                             ROD:
1987
3/89
8/21/91
9/30/91
                                                         Background

                                             PRP-lead  ,
                                             PRPs:  Champion Spark Plug Company
                                             FS prepared by:  Environmental
                                                    Strategies Corporation
3.      What type of site is this?

       Electrical Equipment. An inactive spark plug manufacturing facility located in a residential/
       commercial area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:        •               ,
       Access restriction:
       Containment:
                     Deed restrictions
                     Capping, vertical barriers, liners, grout injection, interceptor trench/
                     collection system
Chemical treatment:    Stabilization, encapsulation                '       •  '     '
Thermal treatment:    Incineration (rotary kiln, fluidized bed, multiple hearth)
Disposal:             Removal, disposal, excavation
  368
                                            -i-

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?'
                                                                        I              f
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:            '                            I             '
                                                                        I-
       Biological treatment:   Landfarming, in situ bioremediation, bioremediation in lined beds,
                             bioremediation in waste piles, bioslurry, biodegradation in general
       Physical treatment:    Soil vapor extraction, soil washing        -'   j.   -
       Thermal treatment:    Pyrolysis, thermal desorption
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation/The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance. '           •                          -

        RAA designations changed in the ROD area are presented parenthetically.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-5
-
Innovative Technology
Capping/soil vapor extraction
Estimated Costs
3 Criteria
$14,843,000
9 Criteria
eliminated
How did the cost(s) compare to standard technologies? ,
Cost Estimates for RAAs That Include Standard Technologies .
(selected remedial alternative is in bold)
'
Alternative
RAA-A
(RAA-1)
RAA-1
(RAA-2)
RAA-2
(RAA-3)
Standard Technology
No action
Deed restrictions
Deed restrictions/capping
Estimated Costs
3 Criteria
$241,000,
$0
$408,000
9 Criteria
$241,000
$241,000
$408,000
                                               -2-
369

-------
Alternative
RAA-3
RAA-4
RAA-6
RAA-7
(RAA-4)
(RAA-5)
(RAA-6)1
Standard Technology
Capping/upgrade slurry wall
Capping/clay liner
Excavation/stabilization/capping
Excavation/removal/refill to grade
Ground water pumping and treatment
Ground water pumping and treatment
Impermeable cover/surface water
runoff controls/ground water pump
and treat
Estimated Costs
3 Criteria
$650,000
$3,630,000
$5,739,000
$20,069,000
N/A
N/A
N/A
9 Criteria
eliminated
eliminated
eliminated
eliminated
$1,806,700
$1,836,100
$2,250,000
        'RAA-6 was developed in the ROD.
5.      If a standard technology was chosen, why?

        RAA-6, first developed in the ROD, was chosen because it provides the greatest protection to
        human health and the environment by addressing both soil and water contamination with an
        impermeable cover that reduces the risk due to direct exposure to soil and reduces the mobility
        of site contaminants associated with the infiltration of rain water. Additionally, ground water
        treatment reduces contaminant toxicity and mobility in ground water. This alternative was
        preferred even though the site was determined to pose only low-level risks.  RI data showed
        that risk due to direct contact with site soil is within EPA's acceptable range.  Further, using
        Summers model it was concluded that soil contaminant concentrations were not sufficient to
        degrade ground water to levels that exceed MCLs.  This alternative is consistent with
        Superfund program policy of containment rather than treatment for wastes that do not represent
        a principal threat at the  site and are not highly toxic or mobile in the environment. Long-term
        protection can be provided by the cap with proper maintenance.  This alternative can be
        implemented easily, will not pose short-term risk, and is cost-effective.
9.
If an innovative technology was chosen, why?

An innovative technology was not chosen.
10.
If an innovative technology was not chosen, .why not? At what stage was the innovative
technology eliminated?                                                          ;

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
  370
                                             -3-

-------
   - •                        •                "        •              I " •         •
Innovative technologies eliminated during the initial screening include the following:

•      Pyrolysis was eliminated because it would not eliminate all organics and would
       produce a char that would require disposal as hazardous waste. Its effectiveness with
       soil  is unproven, the technique would be expensive and no more effective in
       destroying contaminants than incineration.
•      Thermal desorption was eliminated because it would be very expensive.
•      Bioremediation in general was eliminated because the site has low levels of VOCs and
       PAHs and therefore limited substrate for microorganisms to  grow.  Further, while high
       levels of PAHs would be amenable to biodegradation, the degradation of existing low
       levels of PAHs would not be assured.  ,                               '
•      In situ bioremediation was eliminated because its applicability would be limited by the
       highly variable quality and chemistry of the fill material, the lack of substrate to
       sustain biological growth, the low degradation rates expected for some PAHs, and the
       undesirable creation of wet conditions that could cause contaminants to leach into
   '    ground water.  Further, the rate of degradation and the final concentrations achievable
       would be impossible to predict.
•      Land)'arming was eliminated because the depth of the contaminated material would
       require excavation and spreading of materials over the site.  This process would be
        impractical because space at the site is limited.               |                       '
•      Bioremediation in lined beds was eliminated because it would be impractical to
        implement on  site due to limited space.                         '
•       Bioremediation in waste piles was eliminated because its effectiveness would be
        limited by the substrate available for microorganisms, the .time! required to achieve
        acceptable concentrations would be difficult to predict, and  the technique would be
        expensive. Further, lined beds would be constructed below thp ground water table,
        possibly requiring dewatering during construction—a process ihat would produce waste
        water that would require  treatment.
•      Bioslurry was eliminated because it would be impossible to implement since a  lot of
        the contaminated material in the lagoon consists of large objects that can not be
        suspended.  Further, this  treatment requires large amounts of power, must be closely
        supervised, and is best suited for fine grained material.
 •      Soil washing was eliminated because it would be  very complex to implement due to
        the varied nature of the fill. This technique requires careful management and an
        understanding of the side effects on the soil.  A washing solution that mobilizes one
        contaminant could precipitate, detoxify, or increase the toxicity of another contaminant.
        Also, the use of this technology could affect the physical nd chemical properties of the
        soil.                                     ,                 .                       '

 Innovative  technologies eliminated during the screening of the three criteria include the
 following:                                                  ;
                                                                  i
 «      'Soil vapor extraction was eliminated because the  ability of thiis technology to
        significantly reduce YOC levels is questionable since their  concentrations already are
        low. According to David Hazebrouk, a vendor, reaching low levels of VOCs (below
         1,000 ppb)  is only "potentially achievable."  Further, the technology would  not .
        address semiyolati.les or  metals.  Application of the technology would be difficult due
        to pockets of impermeable materials prohibiting drilling and voids that would short-
        circuit the system.  The  site sand is not optimal for this technique because its low
        permeability clay or silt  makes it difficult to blow air through the wells or to remove
        air from the soil.  Additionally, soil below the water table in the lagoons would require

                       •  ';          .          •               .'•'!''.'
 .   ,          .   :        '        "-     .4-                     .  \   • .  '                 ;
371

-------
                  ground water removal prior to treatment. The integrity of the cap could be
                  compromised in the drilling of vapor extraction wells.  It would be very costly.
                                                                                        • •'
          Innovative technologies eliminated during the detailed analysis include the following:

          *      None
   11.     ^hich of the nine criteria were weighted most heavily in selecting the technology?  Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
          which criterion?  Which of the criteria supported the use of a standard technology?

          The criterion that was weighted most heavily in selecting a remedial alternative was protection
          of human health and the environment.  The chosen alternative was the only alternative that
          addressed both soil and ground water concerns. Even though soil was determined to be only a
          low-level threat to both humans and the environment and it would not lead to the
          contamination of ground water above MCLs, the remediation of soil was preferred.

          Soil vapor extraction was eliminated because it would be difficult to implement, it is                :
          expensive, and its effectiveness is uncertain.


   12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
          ARAR?  What risk level was selected to establish cleanup goals?

          No chemical-specific cleanup goals were established for soil. The RI data indicates that           fAfe
          contaminants in site soil are within EPA's acceptable incremental individual lifetime cancer        ^^
          risk of W4 to 10'6 based on direct dermal contact and ingestion.



  13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the  cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          •      None                    :

          Standard technologies eliminated because of cleanup goals include:

          •      None                                                        •



  14.     Were treatability studies conducted on the innovative technology  or standard technology?

         Treatability studies were not conducted.
372
                                                -5-

-------
15.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Risk level achieved
16.    How are measures compared?                                    \- .    ~

       The chosen alternative was preferred because it provides the greatest level of overall protection
       since it addresses both soil and ground water.  Other alternatives wen? directed at either soil or
       water.
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
                                                                        \      .
                                                  • .  •                 •, |,    •
       The low permeability and high moisture content of the site's soil was; a consideration that lead
       to the elimination of soil vapor extraction.  This technical consideration was not primary in
       selecting a remedial alternative.      .
                                               -6-
373

-------
                                         Industrial Lane
                                              OU-2

                                 Williams Township, Pennsylvania
                                             Region 3
   GENERAL SITE INFORMATION

   1.      What were the principal contaminants,
          contaminant levels, and media addressed in
          this feasibility study ?

          Maximum concentrations of principal
          contaminants were:

          No principal threats, such as hot spot areas
          of highly toxic or highly mobile wastes,
          were found in conjunction with the site. The
          principal exposure pathway, ingestion and
          inhalation of volatile organic compounds
          (VOCs) in contaminated ground water, was
          addressed by OU-1.  OU-2 addresses the
          contaminated ground water and the
          relatively low-level threat caused by the
          unlined municipal landfill.
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1983
1984
8/86
3/29/91
             Background

EPA Fund-lead                 >.
PRPs:  PRPs 'are not discussed in the FS
       or the ROD    .
FS prepared by:  NUS Corporation
  2.      What volume of material is to be remediated?

          The volume of material to be remediated included:                                   *

          »     The estimated total volume of the waste in the landfill is 3 million cubic yards


  3.      What type of site is this?
                                                                              ' '       i

         Municipal Landfill.  An inactive unlined sanitary landfill (Chrin Brothers landfill). The site
         encompasses 30 acres. The area around the site is currently used for industrial, residential, and
         limited agricultural purposes.
  TECHNOLOGY SELECTION                                            ,

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
374
         Access restriction:     Monitoring

-------
       Containment:

       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Capping (synthetic membrane, clay, soil, multimesdia, asphalt, concrete,
chemical sealants), collection        /
Solidification/fixation
Grading and revegetation
Incineration
Excavation, RCRA facility (on-site, off-site)
5.      Was an innovative technology considered in the FS? If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Biological treatment:   Bioreclamation
       Chemical treatment:    Soil flushing                                             , •/
        What was the cost estimate for the innovative technology?            |

        During the initial screening process, in which technically  feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, no three-criteria or nine-criteria screening was conducted and the
        estimated costs were calculated during an evaluation based on four criteria: technical aspects,
        public health and environmental concerns, institutional issues, and cost]  A three-criteria and a
        nine-criteria screening of the RAAs were conducted in the ROD.      j        .

        Innovative technologies were not incorporated into the RAAs.
 7.      How did the cost(s) compare to standard technologies?
                                                                           i
    •  '            Cost Estimates for RAAs That Include Standard Technoiogies
                              (selected remedial alternative is in bold)

         Focused PS/Landfill Waste                                  '.'.!'
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
No action/monitoring
-Multilayer soil cap (clay)
Estimated Costs
4 Criteria
$0
$663,000.
$6,354,000
                                                 -2-
                                                                                                   375

-------
        ROD/Landfill Waste
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-4
Landfill
Closure'
Innovative Technology
No action
Access restrictions/monitoring
Extraction/treatment/discharge of
ground water to Lehigh River
Extraction/discharge of ground water to
POTW
Extraction/treatment/reinjection of
ground water .
Municipal landfill cap (clay)
Estimated Costs
ROD
$2,027,000
v $2,027,000
$12,775,000
(not including
landfill closure
costs)
$44,318,000
, (not including
landfill closure
costs)
$11,937,000
(not including
landfill closure
costs)
$8,000,000
(capital costs only)
       "Pennsylvania Department of Environmental Resources (PADER) notified the owner and
       operator of the Chrin Brothers Landfill in a letter dated 11/23/90 that the unlined landfill area
       must be closed according to Chapters 271 and 273 of the Pennsylvania Municipal Waste
       Management Regulations. The state closure requirements, estimated to cost
       $8 million, were integrated into the development and evaluation of the remedial alternatives
       for the site.

8.     If a standard technology was chosen, why?

       A low-permeability cap was chosen for the Chrin Brothers Landfill because it will significantly
       reduce the amount of leachate emanating from the facility.  The landfill, however, will
       continue to generate small quantities of leachate, which could act as a continuous source, of
       ground water contamination.  The remedy for OU-2, therefore, proposes ground water
       treatment in addition to capping. The primary remedy for the site (OU-1) and the contingency
       measures afforded by closure of the unlined landfill and by ground water extraction and
       treatment, provide overall protection of human health and the environment, either by reducing
       contaminants to remediation goals, or through a combination of mass reduction, and
       institutional and engineering controls.  The cap complies  with all ARARs for the site. The
       municipal landfill poses a relatively low level threat, and is therefore to be closed in
       accordance with Chapters 271 and 273 of the Pennsylvania Municipal Waste Management
       Regulations, including a cap. In addition, the advantages of using a soil cap over other types
       of caps include the availability of the material at the site, ease of construction and
       maintenance, and  lower cost. The construction methods involved in capping the landfill
376
                                              -3-

-------
       employ standard engineering practice and construction procedures commonly used on
       earthwork projects.                                               .
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                                '   . (

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.  ,

       This site has a focused feasibility study,  which does not include the usual three-criteria and
       nine-criteria stages of evaluation. The innovative technologies considered were eliminated
       during an initial screening process.

       Innovative technologies eliminated during the  initial screening include the following:

       •      Bioreclamation and soil flushing were eliminated because they are feasible only for
               landfills with liners  and a leachate collection system at the bottom of the landfill. If
               there is no bottom containment, the process could  accelerate [the rate of ground water
               contamination.

       Innovative technologies eliminated during the  screening of the three criteria include the
       following:

       •      None        .•',;'.•                     '   •

       Innovative technologies eliminated during the  detailed analysis include the following:

       •      None                 •'                                ' -I        .      "..
11.
 12.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to mee,t one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Which of the criteria supported the use of a standard technology?
        The selection of a cap for the Chrin Brothers Landfill was made
        Protection of human health and the environment,was the most
        selecting a cap. The selected remedy provides adequate protection
        environment through closure of the unlined landfill.
                                                            before this ROD was issued.
                                                          heavi! y weighted criterion in
                                                                 human health and the
cfl
What cleanup goals were selected?  If the cleanup goal was based en an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?

Cleanup levels were not developed for the landfill waste.


                                        4                                                377

-------
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard             \
         technology meet tn^ cleanup goals?                                      •                           —'

         Innovative technologies eliminated because of cleanup goals include:

         •      None

         Standard technologies eliminated because of cleanup goals include:

         •      None


 14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.


 75.     What measures/criteria were used to compare alternatives?                     •'•_•'-

         The following measures were used to compare the alternatives:

              Risk level achieved
              Cost-effectiveness       ,                                                 -
              Proven reliability


 16.     How are measures compared?

         The selected alternative provides the greatest 'protection of human health and the environment
         through a combination of mass contaminant reduction,  and institutional and engineering
         controls.  The chosen remedy also affords overall effectiveness proportionate to its costs and is
         therefore cost-effective. Capping was the preferred remedial action for the landfill because
         standard engineering practices and construction procedures commonly used on earthwork
         projects are used.                                                                :          •


 17.     What technical considerations were factors in selecting a remedy?  Were technical         "
         considerations primary in the selection of the remedy?

         Technical considerations were not primary in selecting  a cap for the Chrin Brothers Landfill.
                                                                                                            >
378
                                               -5-

-------
                      Letterkenny Army Depot (Southeast Area)
                                           OU-1

                                 Chambersburg, Pennsylvania
                                          Region 3
GENERAL SITE INFORMATION
L.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil (mg/kg)

       Trichloroethylene
       Trans-1,2-dichloroethy lene
                             779
                             131
                                                                  Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                             10/1/84
                             7/1/87
                             8/90
                             8/2/91
                                                          Background
Federal Facility
PRP:   U.S. Army Corps of Engineers
FS prepared by:  U.S. Army Toxic and
       Hazardous Materials Agency
2.     What volume of material is to be
       remediated?
•                      -
       The volume of material to be remediated
       included:

       •      8,000 cubic yards'of soil
3.      What type of site is this?                                    .

       Military.. An active U.S. Army depot.


TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:
       Containment:
                     Limit access, use restrictions, relocation, permanent relocation
                     Synthetic membrane, capping (clay, asphalt, multimedia, concrete/
                     chemical sealant, single-layered soil), slurry walls, grout curtain, sheet
                     piling, membrane wall, dewatering, soil aeration, in situ volatilization
Chemical treatment:   Fixation/encapsulation                      !
Thermal treatment:    High-temperature incineration, low-temperature incineration,
                     thermoplastic solidification, flaming/flashing
Disposal:             Excavation, landfilling                  -    i
                                             -1-
                                                                                     379

-------
  5.      Was an innovative technology considered in the FS?  If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                                 ,                    .

         Biological treatment:   Microbial degradation, soil aeration (landfarming)
         Phys/Chem treatment:  In situ soil  aeration (SVE), solution mining (soil flushing), soil
                               washing
         Thermal treatment:     Low-temperature thermal decomposition, in situ vitrification
         What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
         implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
         estimated costs then are recalculated during an evaluation based on the nine criteria established
         by the NCP.

                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-3A
RAA-3C
RAA-4A
RAA-4B
Innovative Technology
In situ volatilization (SVE)
Excavate/mechanically aerate (land-
farming to volatilize contaminants
Excavate/low-temperature thermal
decomposition
Excavate/soil washing
Estimated Costs
3 Criteria
$191,000
$1,103,000
$1,539,000
$3,878,000
9 Criteria
eliminated
eliminated
$1,539,191
eliminated
  7.     How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1A
Standard Technology
No action/long-term ground water
monitoring only , .
Estimated Costs
3 Criteria
$191,000
9 Criteria
$143,434
380
                                                -2-

-------

- Alternative
RAA-1B
RAA-2A
RAA-2B
RAA-2C
RAA-3D
RAA-3E

Standard Technology
No action/long-term ground water
monitoring/institutional and land use
controls
Synthetic membrane cap
Clay cap
Multimedia cap
Excavate/on-site high-temperature
incineration
Excavate/off-site high-temperature
incineration
- Estimate!
3 Criteria
$191,000
i ' •
.•
$202,000
$210,000
$254,000
$4,235,000
.
$20,688,000
;
I Costs
9 Criteria
$143,434
eliminated
eliminated
$254,150
$4,235,191
eliminated
 10.
8.      If a standard technology was chosen, why?

       A standard technology was not chosen.
                                                                       i
9.     If an innovative technology was chosen, why?
                                                                ' -  i    '
       Low-temperature thermal decomposition, RAA-4A, was chosen because it provides good long-
       term protectiveness; achieves ARARs; permanently and significantly reduces toxicity, mobility,,
       and volume; provides short-term effectiveness; and provides maximum long-term effectiveness
       and permanence through destruction of nearly all the VOC contaminants in the soil.  It is less
       costly  than incineration; has proven effective in a pilot-scale field test; has no associated O&M
       costs;  takes less time to implement than incineration; satisfies the statutory preference for
       treatment; Utilizes an innovative technology to the maximum extent practicable; utilizes  known
       technologies for which the necessary equipment and expertise is  readily available; and reduces
       risk associated with groundwater exposures.
        RAA-1A and RAA-1B were eliminated because they would not protect
        environment. RAA-2A, RAA-2B, RAA-3A, RAA-3C, and RAA-4B
        they would not meet ARARs.  RAA-3E was eliminated because it
        without providing additional benefit. RAA-2C was eliminated because
        containment and not treatment.
If an innovative technology was not chosen, why not?  At what stage
technology eliminated?   .
                                                                 human health or the
                                                               were eliminated because
                                                            would be unduly expensive
                                                                 it only would provide
                                                                       was the innovative
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                               -3-
                                                                                        381

-------
        Innovative technologies eliminated during the initial screening include the following:!

        •      Microbial degradation was eliminated because it had not been demonstrated on a full
               scale, and extensive testing would be required to determine its feasibility.
        »      Solution mining (soil flushing) was eliminated because it had not been demonstrated
               on a full scale, and extensive testing would be required to determine its feasibility.
        •      In situ vitrification was eliminated because it was not applicable for chlorinated VOCs.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        "      In situ volatilization (RAA-3A) was eliminated because it would not meet the cleanup
               objectives as demonstrated by a 1989 pilot study. Soil permeability was too low.
        •      Soil aeration (landfarming) (RAA 3C) was eliminated because it will not meet
               response objectives; only 76-79% removal is achievable.                             .
        •      Soil washing (RAA-4B) was eliminated because it would not be as effective as other
               alternatives, and some development would be required to implement.

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
11.
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?

The ROD states (p. 40) that short-term effectiveness and reduction of TMV were regarded as
the most decisive factors  in the selection process.  However, cost-effectiveness also appeared
to be heavily weighted.  Incineration and low-temperature thermal treatment both met all other
criteria, but low-temperature thermal treatment was much less expensive ($1 539 191 vs
$4,235,191).
12.    Wfiat cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
                Carcinogens
                Trichloroethylene
                    Contaminant       Cleanup Level (mg/kg)
                                                         ARAR or Other Basis
                                        0.225
MCL
       In Pennsylvania, soils must be cleaned to the extent necessary to meet the background ground
       water cleanup requirements. The ARAR for soil cleanup was developed based on the
       Maximum Contaminant Level (MCL) and the  soil-to-ground water ratio observed at the site.
       For trichloroethylene, the MCL was 5 u/L and the ratio of concentration of soil to ground
       water was 45 to 1. The acceptable soil cleanup  level developed was 225 ug/kg (45 x 5 u/L)
       or 0.225 mg/kg.                            ,
 382
                                              -4.

-------
       For carcinogens, an excess upper bound individual lifetime cancer risk
       was acceptable.  For noncarcinogens, a Hazard Index less than or e
equal
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      In situ volatilization
       •      Soil aeration (landfarming)

       Standard treatment technologies eliminated because of cleanup goals include:

       • .     None
14.     Were treatability.studies conducted on the innovative technology or standard technology?
       Two innovative technologies were tested.  Pilot scale testing of soils
       using low-temperature thermal decomposition. The results indicated
       for the site. In situ volatilization would 'not meet the response objecti
       1989 pilot study.     .''..'.
: of between KT1 to lO'6
  to 1.0 was acceptable.
   was conducted at the site
   (hat it would be suitable
   ives as demonstrated by a
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Cleanup goal   .  •'.         ,
               Preference for treatment (vs. containment)
               Cost-effectiveness
               Proven reliability                                     '


16.     How are measures compared?

        The chosen alternative provides a high degree of effectiveness and permanence through
        treatment, which was preferred to containment.  In addition, pilot studies proved that low
        temperature thermal treatment could be reliable and achieve the cleanup levels. One other
        alternative (on-site incineration) wa.s similarly effective, but it was almost three times as
        expensive, so the chosen alternative also was cost-effective.
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?              \
               "       :  '                    •                              S            , .

        Technical considerations were not primary in selecting a remedy. The most important
        technical consideration was that metals were not migrating into the  glroundwater, probably due
        to the retentive properties of the clayey soils with respect to metals. Therefore, source control
        remedies were hot needed for remediating metals.
                                               -5-
                                                                                                 383

-------
         Alternatives involving use of physical barriers were eliminated because the bedrock to which       j^
         thr barriers would be affixed was composed of porous limestone.  Several technologies were,       I^P  "*)}
         ni  applicable to chlorinated VOCs or did not apply to unsaturated soils. Three cap materials          ~~~^
         were eliminated because they were susceptible to degradation by VOCs and freezing and
         thawing stresses.
384
                                              -6-

-------
                                    Lindane Dump
                             Harrison Township, Pennsylvania
                                        Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
                                     ' -s

       Surface Soil/Subsurface Materials (mg/kg)
       Alpha-BHC
       Beta-BHC
       Gamma-BHC
       Delta-BHC
       4,4-DDT
       4,4-DDE
       4,4-DDD
       •Phenol
       Arsenic
             •f
       Chromium
       Copper
       Lead
       Mercury
       Nickel
       Silver
       Zinc
517
1.3
206
296
236
2
3.6
6
37
1,380
707
1,220
1.5
11,800
5   -
3,680
                       NPL Proposed:
                       NPL Final:
                       FS:
                       ROD:
                                   Site History
                     10/81
                     9/83
                     2/92
                     3/12/92
                                                               Background
PRP-lead
PRPs:  Elf Atocheni North America, Inc.
FS prepared by: Eckenfelder
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      1.2 million cubic yards of waste
3.      What type of site is this?

       Industrial Landfill. A former industrial waste disposal area located in an industrial area.
                                           -1-
                                                               385

-------
  TECHNOLOGY SELECTION                                       ,

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically, feasible
         technologies were:

         Surficial Soil

         Access restriction:     Fencing, deed restrictions                                 ,
         Containment:          Capping (clay, soil, revegetation,  asphalt, concrete, multilayer),
                               grading, surface water diversion
         Thermal treatment:     Incineration (rotary kiln, fluidized bed, infrared)
         Disposal:              Excavation, on-site disposal in RCRA permitted cell, off-site disposal
                               in RCRA landfill

         Subsurface Materials

         Access restriction:     Fencing, deed restrictions
         Containment:          Capping (clay, soil, asphalt, concrete, multilayer), grading, surface
                               water diversion
         Chemical treatment:    Stabilization/solidification, grout injection, soil mixing
         Physical treatment:     Dewatering
         Thermal treatment:     Incineration (rotary kiln, fluidized bed, infrared)
         Disposal:              Excavation, on-site disposal in RCRA permitted cell, off-site disposal
                               in RCRA landfill


  5.      Was an innovative technology considered in the FS? If so, which technology?       -,

         Innovative technologies considered during the identification and  screening of technically
         feasible technologies were:

         Surficial Soil

         Biological treatment:   Slurry-phase biodegradation, solid-phase biodegradation, composting
         Chemical treatment:    Critical  fluid solvent extraction, Basic Extraction Sludge Treatment,
                               soil washing, glycolate dechlorination,
         Thermal treatment:     Pyrolysis, vitrification, pyrolytic centrifugal reactor

         Subsurface Materials

         Biological treatment:   In situ biodegradation, composting, slurry phase biodegradation, solid-
                               phase biodegradation
         Chemical treatment:    In situ soil flushing (surfactant), Basic Extraction Sludge Treatment,
                               critical fluid solvent extraction, soil washing, glycolate dechlorination
         Thermal treatment:     In situ vitrification, pyrolysis, vitrification, pyrolytic centrifugal reactor
386
                                                -2-

-------
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the fprmulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  For this site, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP:  long-term effectiveness and peirmanence; short-term
       effectiveness; compliance with ARARs;  protectiveness of human health and the environment;
       reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
       agency acceptance; and community acceptance.
                                                                       i •
       Alternatives renumbered in the Proposed Plan and the ROD are presented parenthetically.

       No innovative technologies were incorporated into remedial alternatives.
        How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8A
RAA-8B
RAA-9A
(RAA-2)

Standard Technology
No action/long-term monitoring
Limited action
Excavation/on-site disposal
Excavation/off-site disposal
Excavation/on-site incineration/on-site
disposal
Excavation/on-site ihcineration/off-site
disposal
Excavation/off-site incineration/off-site
disposal
Topsoil and vegetative cover
Topsoil and vegetative cover/ground
water extraction and discharge
Clay and soil cap/upgraded leachate
collection and treatment/deed and access
restrictions/ground water monitoring
Estimated Costs
3 Criteria
N/A -
N/A
N/A
N/A
N/A
-
IN/A
IN/A
IN/A
IN/A .
. i
'
JN/A
/ -i, ,
9 Criteria
$2,262,500
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
$14,146,000
                                               -3-
                                                                                                    387

-------
Alternative
RAA-9B
(RAA-3)
RAA-10A
(RAA-4)
RAA-10B
(RAA-5)
(RAA-6)'
Standard Technology
Clay and soil cap/upgraded leachate
collection and treatment/deed and access
restrictions/ground water extraction and
discharge/ground water monitoring
Multilayer cap/upgraded leachate
collection and treatment/deed, and access
restrictions/ground water monitoring
Multilayer cap/upgraded leachate
collection and treatment/deed and access
restrictions/ground water monitoring/
ground water extraction and discharge
Combination multilayer and clay and
soil cap/upgraded leachate collection
and treatment/deed and access
restrictions/ground water monitoring /
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$15,136,500
$14,114,600
$15,105,100
$14,122,500
         * This RAA was first presented in the Proposed Plan.


 8.      If a standard technology was chosen, why?

         The chosen alternative was not developed in the FS, but was first presented in the Proposed
         Plan.  This alternative represents a combination of RAA-9A and RAA-10A. It was developed
         because of a concern that a multilayer cap could not be constructed over the site's .steep side
         slopes. This alternative proposes a clay cap for areas where slope stability might impede
         placement of a multilayer cap and a multilayer cap over the rest of the site. This alternative
         was chosen because it will reduce the infiltration of water through the fill area and thereby
         reduce the mobility of contaminants through the fill to the aquifer. In turn, such reduced
         mobility will help eliminate the current  ground water and seeps MCL violations.  The cap will
         eliminate the potential exposures  to site contaminants that could be in the surface or subsurface
         soils.  The multilayer cap was preferred over the soil cap, where feasible, because of its lower
         permeability and additional protection against infiltration.  An additional  14-percent reduction
         in infiltration would be provided by the multilayer cap, according to estimates.  The multilayer
         cap also was considered superior to the  clay cap because it offers greater long-term
        effectiveness and permanence.  The multilayer cap is less susceptible to failure in the long-
        term because it provides multiple defenses. Materials needed to produce  a multilayer cap are
        readily available and the technology can be easily implemented.
 9.
If an innovative technology was chosen, why?

An innovative technology was not chosen.
388
                                               -4-

-------
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?   *   -

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluiktion.

       Innovative technologies eliminated during the initial screening include the following:

       Surface Soil                                                    !..."'"'

        •      Pyrolysis was eliminated because the technology has not been fully developed and
               would  be ineffective for inorganic waste constituents.                                    ,
       1 •-     Vitrification was eliminated because the technology has  not been fully developed.
        •      Pyrolytic centrifugal reactor was eliminated because the,technology has not been fully
               developed.  ,    •                                         !
        •      Basic Extraction Sludge Treatment was eliminated because it has riot been used to treat
               soils and would be ineffective for inorganic waste constituents.
        •      Critical fluid solvent extraction was eliminated because  it would be ineffective for             >
               inorganics  and it has not been demonstrated on a large scale ifor wastewater sludges.
        •      Soil washing was eliminated because the technology has not been fully developed for
               site  constituents.
        •    '  Glycolate dechlorination was eliminated because its effectiveness has not been
               demonstrated and  it would be ineffective for inorganics.     |
        •      Composting was eliminated because the waste material is heterogenous and not all
               biodegradable.                                           j  ,
        »      Slurry phase biodegradation was eliminated because the was! e  material is
               heterogeneous and not all biodegradable.
        •      Solid-phase biodegradation.was eliminated because inorganic: constituents and some
               organic ones are not biodegradable.
                                                                        I    •      '              -   •       .
        Subsurface Material                                             .

        •      In situ vitrification was eliminated because it would not be suited for loosely packed
               rubbish or coal, the contaminant depth is too great  for implementation, and waste is
                present below the water table.
        •      In situ soil flushing was eliminated because subsurface soils are not conductive enough
                for  flushing.                                             i              '
        •      In situ biodegradation was eliminated because waste materials  are heterogeneous,
                many  of them are not biodegradable, and the waste materials exhibit low hydraulic
                conductivity.                                       .    j      '
    .'   •   .   Pyrolysis was eliminated because the technology has not been fully developed.
        •      Vitrification was eliminated because the technology has not been fully developed.
        •      Pyrolytic centrifugal reactor was eliminated because the technology has not been fully
                developed.
        •      Basic Extraction Sludge Treatment was eliminated because it treats primarily sludge,
                site wastes are heterogeneous, and it would be ineffective  for inorganics.
         •      Critical fluid solvent extraction was eliminated because it  would be ineffective for
                inorganics.     :  .                                   .
         •      Soil washing was; eliminated because the technology has not been fully developed for
                site constituents, and waste materials are heterogeneous:
                                                                   .•.j.

                   •'      ''  "'"  -          "-5--'  .  ;      •    '   -I"   •     •-  '•   •-      -'389

-------
          "      Glycolate dechlorination was eliminated because its effectiveness has not been
                 demonstrated and waste materials are heterogeneous.
          »      Composting was eliminated because waste materials are heterogeneous and many of
                 them are not biodegradable.
          »      Slurry-phase biodegradation was eliminated because waste materials are heterogeneous
                 and many of them are not biodegradable.                                      ,
          »      Solid-phase biodegradation was eliminated because the inorganic and some of the
                 organic constituents are not biodegradable.   ' .

         Innovative technologies eliminated during the screening of the three criteria include the
         following:    ,                                     ,                     .

         "      None

         Innovative  technologies eliminated  during the detailed analysis include the following:

         •      None
 12.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so
 which criterion?  Which of the criteria supported the use of a standard technology?

 The protection of human-health and the environment and implementability were the most
 heavily weighted criteria  in selecting^ remedial alternative. The multilayer cap was preferred
 over the clay cap because it would greatly reduce infiltration of the waste and thereby reduce
 the mobility of contaminants to the aquifer.  Because the multilayer cap  could not be
 implemented over the site's steep side slopes,  a clay cap had to be incorporated into the
 remedial alternative.                                         ,

 No innovative technologies were eliminated based on these criteria.


 What cleanup goals were  selected? If the cleanup goal was based on an ARAR, what was  that
 ARAR?  What risk level was selected to establish cleanup goals?

 No cleanup levels  were established for soil.  The remedial action is intended to prevent site
 contaminants from infiltrating the ground water.

 Health risk assessment analyses determined that under the worst case scenario, the greatest
 cancer risk value at the site is within EPA acceptable risk levels of lO"4 to 10'6.
                                                                                                    *.*
13.
Was the innovative technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None
390
                                              -6-

-------
        Standard technologies eliminated because of cleanup goals include:

        »      None                                        :


 14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                                           •
        No treatability studies were conducted.                        '

                                                                         i      ,  '

 15.     What measures/criteria were used to compare alternatives?          i
                                                        .                 i
        The following measures were used to compare the alternatives:       !

        -     Reduction of contaminant mobility
             Long-term effectiveness


                                                                         i' • •'
 16.     How are measures compared?                                '.I

        Source control options included a multilayer cap and a clay cap. The multilayer cap was
        preferred  over the clay cap because.it is less permeable to precipitation;and therefore is more
        effective at reducing contaminant mobility. The multilayer cap also wals preferred because it is
        less  susceptible to breakdown in the long term.
                                                                         1
             .
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                i
          ' -                                         '                     I
        In some areas of the site, steep side slopes precluded the use of a multilayer cap; a clay cap
        will  be implemented in these instances.  This site condition was primary in selecting a
        remedial alternative since a multilayer cap for the entire site would have been preferred.
                                              -7-
                                                                                                   391

-------
                            Mid-Atlantic Wood Preservers, Inc.

                                      Harmans, Maryland
                                           Region 3
  GENERAL SITE INFORMATION

  1.      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil (mg/kg)

         Arsenic                     1,200
         Hexavalent Chromium  *      0.7
         Total chromium               865
         Copper                    ,  1,280
 2.      What volume of material is to be
         remediated?
                                     Site History
                        NPL Proposed:
                        NPL Final:
                        FS:
                        ROD:
10/84
5/86
7/20/90
12/31/90
                                     Background

                        PRP-lead
                        PRPs:  Mid-Atlantic Wood Preservers
                        FS prepared by: Dames & Moore
        The volume of material to be remediated included:

        •     5,200 cubic yards of soil
 3.     What type of site is this?

        Lumber and Wood Products.  An active wood treating facility located in a mixed industrial/
        residential area.
 TECHNOLOGY SELECTION

 4.     What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
392
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
Fencing, land use restrictions
Capping (clay, synthetic), paving, graveling
Stabilization/solidification
Incineration
Excavation, disposal (on-site, off-site)
                                             -1-

-------
5.      Was an innovative technology considered in the FS?  Ifso> which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Biological treatment:   Biodegradation
       Chemical treatment:   Solvent washing, solution mining
       Thermal treatment:    Wet air oxidation, vitrification                           •
       What was the cost estimate for the innovative technology?
                                            •                     -. |   •'.'•"
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated asf part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that;merit a more detailed
       evaluation. In this case, the estimated costs were calculated during ari evaluation based on
       nine criteria established by the NCP: long-term effectiveness and permanence; short-term
       effectiveness; compliance  with ARARs; protectiveness of human health and the environment;
       reduction in contaminant mobility, toxicity, or Volume; implementability; cost; state/support
       agency acceptance; and community acceptance.

       No innovative technologies were incorporated into remedial alternatives.
       How did the cost(s) compare to standard technologies?
                                                                       i
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)      ,
Alternative
RAA-1
RAA-2
RAA-3
RAA-3A"
Standard Technology
No action/long-term monitoring
Cover soil treatment yard with gravel/
cover storage yard soil with geotextile
and gravel/construct drip pad/natural
attenuation of ground water/long-term
monitoring '
Pave soil with asphalt/construct drip
pad/natural attenuation of ground
water/long-term monitoring
Excavation/stabilization of hot spots
with arsenic in concentrations greater
than 1000 mg/kg/asphalt concrete cap
over soil with 10 to 1000 rug/kg
arsenic/construct drip pad/natural
attenuation of ground water/long-
term monitoring
Estimated Costs
3 Criteria
N/A
N/A
1
1
N/A
i
N/A,
•
.•
- f
9 Criteria
$45,000 .
$318,000
$312,200
$322,600
                                              -2-
                                                                                                   393

-------
Alternative
RAA-4
RAA-5
Standard Technology
Excavation/stabilization-solidification/
off-site disposal at RCRA facility
Excavation/stabilization-solidification/
regrade site/construct drip pad/natural
attenuation of ground water/long-term
monitoring
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$2,750,000
$1,080,000
         •RAA-3A was developed for the ROD.
  8.      If a standard technology was chosen, why?
                                                      '  t                              • :
         The chosen alternative, RAA-3A, was first presented in the ROD. It represents a modification
         of RAA-3 which was the preferred alternative in the Proposed Plan.  RAA-3A was modified to
         include the excavation, stabilization, and disposal of highly contaminated "hot spots" that are
         defined as soil with arsenic concentrations in excess of 1000 mg/kg.  Soil with arsenic
         concentrations between 10 to 1000 mg/kg will remain  in place and be capped. This alternative
         was preferred because it ensures a greater reduction of site contaminant toxicity and mobility.
         Additionally, it improves long-term effectiveness and permanence more than RAA-3.  The
         chosen alternative will reduce site risks to  10'5.  The construction of  a cap will eliminate risks
         due to direct contact with soil or inhalation of contaminated dust.  The preferred alternative
         minimizes short-term risk to workers and nearby residents because it only requires the
         excavation of small volumes of soil or "hot spots." Because  .arsenic  and hexavalent chromium
         are naturally bound to soil particles, excavation of all site soil was not expected to-greatly
         improve site risks.   The preferred alternative can be implemented in the shortest amount of
         time (3 to 6 months) and it is the least difficult of the  treatment alternatives to implement.  It
         is cost-effective.
 9.      If an innovative technology was chosen, why?

         No innovative technology was chosen.
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.         ;

         Innovative technologies eliminated  during the initial screening include the  following:

         •      Solvent washing (extraction) was eliminated because it likely would not be efficient
                enough to reduce soil metals to acceptable levels, metals are tightly absorbed to soil.
394
                                                -3-

-------
11.
12,
 13.
       •      Solution mining (soil flushing) was eliminated because the administration of strong
              acids to leach heavy metals could cause the migration of contaminants, reduce ground
              water pH, and increase environmental risk.
       •      Biodegradatipn was eliminated because it would not be effective for heavy metals.
       •      Wet air oxidation was eliminated because it would not be effective for heavy metals.
       •      Vitrification was eliminated because it is unproved, expensive, and generally
              unavailable.            v

       Innovative technologies eliminated during the screening of the three criteria include the
       following:
              None
       Innovative technologies eliminated during the detailed analysis include the following:
              None
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion? Which of the criteria supported the use of a standard technology?
                                                               i      '.    '
                    .
The most heavily weighted criteria in selecting a remedial technology were implementability,
short-term effectiveness, and cost.  The chosen alternative was prefeired over somewhat more
protective alternatives, such as RAA-4 and RAA-5, because they would not be cost-effective.
Further, these  two alternatives would be more difficult to implement and pose greater short-
term risks because they require excavating large volumes of soil.

No innovative technologies were eliminated for these reasons.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? 
-------
        ' Standard technologies eliminated because of cleanup goals include:

         •      Soil cover
  14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
 75.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Cost-effectiveness
              Preference for treatment (vs. containment)
              Impact on nearby populations
 16.    How are measures compared?

        The chosen alternative, RAA-3A, was preferred because it treats the highly contaminated soil.
        Treatment of the Highly contaminated soils was preferred over containment (RAA-3) because it
        ensures the reduction of contaminant toxicity and mobility. Two alternatives that would have
        offered more protection through the treatment or removal of all site soil were not chosen
        because they would be more expensive.  Because site contaminants are not very  mobile in soil,
        the benefits of these alternatives were not considered to be significantly greater than the
        chosen alternative.  These alternatives were, therefore, not cost-effective. These  alternatives
        also would require excavating large volumes of soil while the chosen alternative  would only
        require excavating hot spots. In addition, they would be more difficult to implement and they
        would pose a greater short-term risk to nearby populations.
 17.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

The absorption of site contaminants to soil was primary in selecting a remedial technology.
The chosen alternative was deemed protective enough because it treats contaminant hot spots.
Other alternatives that would treat all  site soil were not considered to offer much greater  "
protection because the contaminants were tightly bound to soil and therefore not very mobile.
Further, one innovative technology, soil  washing, was eliminated because it might not be
effective for contaminants tightly absorbed to soil.
396
                                               -5-

-------
                               Modern Sanitation Landfill
                                 York County, Pennsylvania
                                          Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       The landfill wastes were not sampled and
       analyzed.

       During the RI process ground water
       contamination was found to emanate from
       the unlined portion of the landfill.  Ground
       water contaminants of concern include:

       Benzene
       Chloroform
       Dichlorobenzene
       Carbon tetrachloride
       1,4-dichlorobenzene
       1,1-dichloroethane
       1,2-dichloroethane
       Trans-1,2-dichloroethene
       Methyl chloride
       Trichloroethane
       1,1-dichloroethene^           ,
       1,2-dichloroethene
       Tetrachloroethene
       Vinyl chloride
                                                          Site History
                                             NPL Proposed:
                                             NPLFihal:
                                             FS:
                                             ROD:
10/84
6/86
5/10/91
6/28/91
                                                          Background
                                                             i .
                                             PRP-lead      .  j  •
                                             PRPs:  Modern Trjash Removal of York,
                                                    Incorporated
                                             FS prepared by:  ICF Technology and
                                                    Golder Asisociates
3.
       What volume of material is to be remediated?

       The volume of material to be remediated included:
              The FS and ROD do not state the volume of waste material contained in the landfill.
              The landfill covers 362 acres.
What type of site is this?

Municipal Landfill. An active municipal and non-hazardous industrial waste landfill located in
a primarily residential and agricultural area.
                                             -1-
                                                                                         397

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:

         Access restriction;      Fencing, ordinances
         Containment:          Capping (clay, synthetic membrane, low permeability) slurry wall,
                               grout curtain
         Disposal:              Excavation, disposal off-site


 5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically    '
         feasible technologies were:    "               •

         Biological treatment:    In situ biodegradation
         Physical treatment:     Vapor extraction
         Thermal treatment:     In situ vitrification
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support '
        agency acceptance; and community acceptance.

                 Cost Estimates for RAAs That Include  Innovative Technologies
                            (selected remedial alternative is in bold)
398
Alternative
RAA-2A
RAA-2B
RAA-2C
Innovative Technology
Maintain current methane extraction
system
Maintain current methane extraction
system/cap
Maintain current methane extraction
system/augment ground water
extraction system/cap
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$16,963,500
$17,947,000
$3,509,000
                                              -2-

-------
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for FAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action/cease current extraction
system/monitoring
Estimated Costs
3 Criteria
N/A
I -
9 Criteria
$3,398,000
                                                                        I
8.     If a standard technology was chosen, why?
                          •''..•               '        '
       A cap was chosen. The chosen alternative, RAA-2C, was preferred bfecause it .provides the
       greatest protection of all the proposed alternatives.  The chosen alternative reduces 'site risk by
       eliminating direct exposure to site contaminants and reducing the mobility of site contaminants
       responsible for contaminating ground water.  The completion of the hpdfill. cover system will
       reduce the infiltration of precipitation into the landfill, thereby reducing die generation and
       mobilization of contaminants to ground water and leachate.
                                                     .'                  \

9.     Ij'an innovative technology was chosen, why?

       This  alternative maintains all currently existing vapor and ground water extraction  systems.
       Also, the ground water extraction system will be augmented.  This alternative reduces the
        greatest volume of leachate constituents through both vapor and ground water extraction
       technologies. Both the vapor extraction system and the augmented ground water extraction
        system will reduce the mobility of contaminants in the shortest timeftame.  The chosen
        alternative is reliable,  relatively simple to operate, and easy to implement.  This alternative is
        cost-effective.                                                    ,
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                    •    j    ,.'.•••
        Innovative technologies eliminated during the initial screening include the following:
                                                                         •
      :                       .      -                   '         '..!-.        '
        •      In situ vitrification was eliminated because it has not been demonstrated on a scale
                equivalent to that of the site and therefore testing would be required to determine if it
                is technically feasible.  Further, it would be extremely expensive.
        •   ,   In situ biodegradation was eliminated because  aerobic conditions would be necessary
                for the degradation of benzene. Aerobic biodegradation of chlorinated compounds,
                however, has been shown to be very slow (Berwanger and Barker, 1988). It has been
                postulated that the slow degradation of chlorinated compounds is due to a toxic effect
                                                                        I            - '     •,
                                                                        !         .
        :               .  •                 ,     -3-       •        "       l             -•      •
399

-------
                of the contaminants on the microorganisms, which would result in the slow               ^^
                degradation of benzene. Further, the low permeability of the landfill could slow          IB    \
                biodegradation. Oxygenatio;   f the landfill could have undesirable  side effects.           ^^ _/
                Generated heat could oxidize refuse materials.  Oxygenation of the downgradient
                aquifer would require the existing extraction system to shut down. Also, oxygenation
                could change the chemistry of the aquifer, resulting in the production of toxic
                compounds, a lower pH, and the precipitation of naturally occurring metals from rock.
                Anaerobic biodegradation also was eliminated because toxic compounds such as vinyl
                chloride could be produced.                                                      •

        Innovative technologies eliminated during the screening of the three criteria  include the
        following:

        B       None                                                                      ....  •

        Innovative technologies eliminated during  the detailed analysis include the following:

        •       None
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        The most heavily weighted criteria in selecting a remedial technology were protection of
        human health and the environment and the reduction of contaminants. This alternative offers
        the greatest protection of all the proposed alternatives since it reduces site contaminant
        exposures through both treatment and containment.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

      '  No cleanup levels were established for soil.
13.     W™ the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include;

        •      None                                                  r           '    •

        Standard technologies eliminated because of cleanup goals include:

        •      None


14.     Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.

400
                                              -4-               .        -             ;

-------
75.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

            Risk level achieved
            Time to design/construct/operate


16.    How are measures compared?
 17.
       The chosen alternative was preferred because, of all of the proposed
       the greatest risk reduction through containment and treatment.  It also
       the shortest amount of time.
What technical considerations were factors in selecting a remedy?
considerations primary in the selection of the remedy?
        No technical considerations were primary in selecting a remedial alternative
 Reference:
                                                              alternatives, it provides
                                                               will reduce site risks hi
                                                                     Were technical
        Berwanger, D., and J. Backer. 1988.  Aerobic Biodegradation of Aromatic and Chlorinated
       , Hydrocarbons Commonly Detected in Landfill Leachate. Water Pollution Restoration Journal
        of Canada. 23(3):460-475.  .
                                               -5-
                                                                                            401

-------
                                  Old City of York Landfill

                               Springfield Township, Pennsylvania
                                            Region 3
   GENERAL SITE INFORMATION
   L
nnai were me principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:

Refuse-Soil Cover (mg/kg)
Pesticides 0.014
PCB Arochlor 1260 2.1
SVOC (total) 1.2
Refuse-Deep Boring (mg/kg)
Lead 1,930
O*i
Sliver 15.9
Total VOCs 26.8
Note: 27 SVOCs "typically associated with

Site History
NPL Proposed: N/A
NPL Final: 12/82
FS: 9/16/91
ROD: 9/30/91

Background
PRP-lead
PRPs: City of York, Rite-Way Services,
and Alleco, Inc. (on behalf of
The Macke Company and Service
America Corporation)
FS prepared by: Groundwater
Technology, Inc.

         municipal landfill refuse" also were detected
         in deep soil borings.
         Vault Sediments (mg/kg)

         Acetone
         Chlorobenzene
         Di-n-butylphthalate
         Benzoic acid
         bis(2-ethylhexyl) phthalate
         Iron
         Lead
                            0.0002
                            0.00007
                            0.014
                            0.0013
                            0.001
                            453
                            0.0381
        Note: Stream sediments and deep sediments also were analyzed, but no cleanup actions were
        implemented for these media.
 2.
402
What volume of material is to be remediated?

The volume of material to be remediated included:

•      1,120 cubic feet of vault sediment
•      1.7 million cubic yards of refuse
                                            -1-

-------
3.
What type,of site is this?
       Municipal Landfill.  The site is an unused landfill located in a rural area.  The landfill was
       used mainly for municipal solid waste, with some disposal of commeircial and industrial
       wastes.  The land use around the site is primarily farmland and woodlands.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        General Response (applicable to refuse and vault sediments)
       Access restriction:
       Containment:
       Refuse

       Physical/chemical:
       Thermal treatment:
       Disposal:

       Vault Sediments

       Physical/chemical:

       Thermal treatment:
       Disposal:
                      Institutional actions (deed restrictions, access restrictions)
                      Cap (asphalt, concrete, synthetic membrane, soil, multilayer), vertical
                      barriers (slurry wall, grout curtains, sheet piles), horizontal barriers
                      (bottom sealing)
                      Stabilization/solidification                   j
                      On-site incineration, off-site incineration     I
                      Complete removal, partial removal, off-site disposal
                      Dewatering (centrifugation, gravity thickening, filtration, evaporation),
                      stabilization/solidification (cement, pozzolan) |
                      On-site incineration, off-site incineration     ]
                      Complete removal, on-site disposal, off-site disposal
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Refuse                                                          j
                  •  "                         .-                           [     . •
        Biological treatment:   On-site biodegradation, in situ bioreclamation,
        Physical/chemical:     Contaminant extraction (soil washing), soil flushing, vacuum extraction
        Thermal treatment:     Low-temperature thermal stripping, vitrification
                            '"••••           .            .           -, j- •
        Vault Sediments
        Biological treatment:   On-site biodegradation, in situ bioreclamation!
        Physical/Chemical:   .  Contaminant extraction (liquid solvents)     f
                                               -2-
                                                                                                   403

-------
   6.      What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify co,sts. After the RAAs have been
          formulated, costs are estimated as part of a three-criteria screening process ,(effectiveness, .
          implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
          estimated costs then are normally recalculated during an evaluation based on nine criteria
          established by the NCP.                  ....''                             :

          In this FS, the three-criteria screening was carried out on RAAs that did not address the entire
          site.  These RAAs were then  regrouped into site-wide RAAs for the nine-criteria analysis.
          Further, the selected remedy was a modified combination of two of the RAAs from the nine-
          criteria analysis.  No innovative technologies were incorporated  into RAAs.


   7.      How did the cost(s) compare  to standard technologies?              '

                       Cost Estimates for RAAs That Include Standard Technologies
                                          Three-Criteria RAAs
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8
Standard Technology
No further action (includes restrictive covenant and
public drinking water line)
Fencing/ground water monitoring
Ground water treatment
Restoring soil cover
Multilayer cap v
Complete source (refuse) removal/off-site
incineration
Partial source (refuse) removal/off-site incineration
Vault sediment removal/off-site disposal at
treatment/disposal facility
Estimated Costs
3 Criteria
N/A
$836,000
$1,190,000
$1,978,000
$1,636;000 to
$14,338,000*
$158,128,000
$41,091,000
$389,000
         "Cost depends on area of cap.
404
                                               -3-

-------
        Cost Estimates for RAAs That Include Standard Technologies
                       Nine-Criteria Site-Wide RAAs
  Alternative
             Standard Technology
 9 Criteria'
RAA-1
No further action (includes ground water
monitoring, restrictive covenant, public drinking
water line)                    -
  $384,400
RAA-2
Vault sediment removal/off-site disposal/ground  j
water treatment (Area #3)/ground water monitoring/
restrictive covenant/public drinking water line   [
 $2,504,700
RAA-3
Soil cover restoration/vault sediment removal/ bff-
site disposal/ground water treatment (Area #3)/  1
ground water monitoring/restrictive covenant/public
drinking water line                            '
 $5,214,200
RAA-4
Multilayer cap (Area #l)/vault sediment removal'
off-site disposal/ground water treatment (Area   |
#3)/ground water monitoring/restrictive covenant/
public drinking water line                     ;
 $5,291,300
($5,597,000)
RAA-5
Multilayer cap (part of Area #3)/vault sediment ,i *
removal/off-site disposal/ground .water monitoring/
restrictive covenant/public drinking water line   i
 $7,455,200
($7,355,600)
 RAA-6
 Multilayer cap (all of Area #3)/vault sediment   i
 removal/off-site disposal/ground water monitoring/
 restrictive covenant/public drinking water line   L.
 $20,866,500
($20,719,600)
 RAA-7
 Multilayer cap (all of areas #1 and #3)/vault
 sediment removal/off-site disposal/ground water
 treatment (areas #1  and #3)/ground water
 monitoring/restrictive covenant/public;drinking
 water line                                -   \
 $33,347,000.
($26,000,000)
                                                   - -".-,1
     presented parenthetically are from in the Proposed Plan and RpD.
                                      -4-
                                                                                           405

-------
           Selected RAA
              Alternative
            Selected RAA"
             Standard Technology
Restoration of soil cover/vault sediment
removal/off-site disposal/ground water
treatment (areas #1 and #3)/ground water
monitoring/gas venting and monitoring/
fencing/surface water monitoring/restrictive
covenant/public drinking water line
                                                                                Estimated
                                                                                   Costs
                                                                                9 Criteria
                                                                                $8,000,000
                                                                                                           •"***
                                                                                                           0
          The selected remedial action was a modified combination of RAA-3 and RAA-7.
   8.      If a standard technology was chosen, why?

          The preferred alternative, through ground water treatment in areas #1 and #3, effectively
          eliminates the potential risk to human health that might result from exposure to ground water  '
          at the site and restores ground water at the site.  The alternative effectively minimizes the
          potential for exposure to landfill refuse by restoring the soil cover. By removing the
          sediments from the vaults, the alternative also would eliminate the potential risk to aquatic
          organisms from a sudden discharge of sediment from the leachate collection vaults. By not
          constructing an  impermeable cap over any of the refuse areas, continuous flushing of areas #1
          and #3 is allowed through infiltration of precipitation into these areas. The continuous
          flushing action would permit the ongoing degradation of constituents in the refuse and
          eventually would reduce the mass of contaminants in areas #1 and #3. The preferred
          alternative "appears to provide the best balance of tradeoffs among the alternatives with respect
          to the nine evaluation criteria."
  9.      If an innovative technology was chosen, why?

          An innovative technology was not chosen.
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?

          Innovative technologies could be eliminated from the remedial technology selection process at
          three stages:  during the initial screening; during the screening of the three criteria of
          effectiveness, implementability, and cost; or during the detailed evaluation.

          Innovative technologies eliminated during the initial screening include the following:

          Refuse
406
                On-site biodegradation was eliminated because the technology would not be applicable
                due to the heterogeneity of refuse.
                                                -5-

-------
•      In situ bioreclamatipn was eliminated because the technology would not be applicable
       due to the heterogeneity of refuse.
•      Contaminant extraction (soil washing) was eliminated  because the technology would
       not be applicable due to the heterogeneity of refuse.
•      Soil flushing was eliminated because the technology would not be suitable for
       heterogeneous municipal landfill refuse.
•      Low-temperature thermal stripping was eliminated because the technology would not
       be applicable due to the heterogeneity of refuse.
•      Vacuum extraction was eliminated because a major limitation to vapor extraction
       would be the depth to ground water, which would preempt vapor migration, and
       because the technology is unproven for refuse material. ; At sites similar to the Old
       City of York Landfill, where saturated fill could be encountered at shallow depths,
       venting is "expected to be inhibited."  Venting is most efficient and effective for a
       source that exhibits uniform permeability and gradients.  In aoldition, the effectiveness
       of venting is reduced significantly in heterogeneous material siuch as refuse where
       uniform concentration and permeability gradients might not be established.  This could
       lead to untreated locations.                                j             '
•     In situ vitrification was eliminated because the technology is pnproven, there are
       potential hazards from  the generation of small amounts of hazardous material due to
       the temperatures involved, and process costs are very high due to high energy
       requirements.                                             j

Vault Sediments
                                                                 !••-.•
 •      On-site biodegradation was eliminated because the technology is not applicable to
        inorganic compounds.                                     i
 •      In situ bioredamation  was eliminated because the technology is not applicable to
        inorganic compounds.                    '                      ,
 •      Contaminant extraction (liquid solvent) was eliminated because human health and the
        environment could be adversely affected from exposure to fugitive dust and
        constituents during excavation and on-site processing for technology implementation;
        currently there is a limited availability of the necessary equipment and workers to
        implement this process, as it is an emerging technology; a treatment system for the
        spent extraction fluid would be required; and capital costs ar«5 expected to be high; as
        there is limited availability of services and multiple extraction stages would most likely
        be required.                                              I
          •                                                       'i
 Innovative technologies eliminated during the screening  of the three criteria include the
 following:                                                   ,   |
  ''••"'                              '                          .
 •  .    None    -       -                       .-•'-''     • j.  ' •   '
                 . .                                "               •!  .
 Innovative technologies eliminated during the detailed analysis include the following:
                                                  . '      '         I
 •      -None .        •                       '••"-.            i   '      .'
                                         -6-
                                                                                             407

-------
    1L     Which of the nine criteria were weighted most heavily m selecting the technology? Did failure
            to meet one of the nine criteria result in the elimination of the innovative technology? If so,
             "hich criterion? Which of the criteria supported the use of a standard technology?

            The nine-criteria screening focused almost exclusively on ground water treatment and
            exposure. Regarding source control, however, long-term effectiveness and permanence, and
            cost were weighted most heavily in selecting a remedy.  The decision to use a soil cap 'over a
            multilayer cap was related to long-term effectiveness and permanence, in that a soil cap would
            allow continuous flushing of areas #1 and #3 through infiltration of precipitation into these
            areas. The continuous flushing action would permit the ongoing degradation of constituents in
            the refuse and would eventually reduce the mass of contaminants in areas #1 and #3. The soil
            cap is considerably cheaper ($8 million) than the multilayer cap proposed for RAA-7 ($26
            million), making the preferred alternative the most cost-effective remedy.


    12,     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
           ARAR? What risk level was selected to establish cleanup goals?

           Cleanup goals were not selected for sediments or refuse.


    13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
           technology meet the cleanup goals?

           Innovative technologies eliminated because of cleanup goals include:

           •     None                                           •

           Standard technologies eliminated because of cleanup goals include:

           «      None                      ,,                                                        ''.'•'.


   14.     Were treatability studies conducted on the innovative  technology or standard technology?

           Treatability studies were not conducted,


   75.     What measures/criteria were used to compare alternatives?

           The following measures were used to compare the alternatives:

                Impact on nearby populations
                Total cost


   16.     How are measures compared?

           The impact on nearby populations is discussed in relation to the construction of a multilayer      '   ^  \
           cap, in that there might  be a risk to residents during the construction period.  The same            f•  /
           comparison was not made for construction of a soil cap. The soil cap  is considerably cheaper    ,. ™

408                                                                                       '                  ''

-------
       ($8 million) than the multilayer cap proposed for RAA-7 ($26 million), making the preferred
       alternative the most cost-effective remedy.
17.    What technical considerations were factors in selecting a remedy?  "Were technical
       considerations primary in the selection of the remedy?
                                                                       \
       Technical considerations were not primary in selecting a remedy. One reason vacuum
       extraction was eliminated, however, was because a major limitation to vapor extraction is the -
       local depth to ground water, which preempts vapor migration. At sites similar to the Old City
       of York Landfill where saturated fill may be encountered at shallow depths, venting is
       expected to be inhibited.
                                              -8-
                                                                                               409

-------
                                     Paoli Rail Yard
                                    Paoli, Pennsylvania
                                         Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Rail Yard Soil (ppm)

       PCB          6,000

       Fuel Oil Impacted Soil (ppm)
                                          ,•>

       PCB          4,900

       Residential and Other Soil (ppm)

       PCB          21

       Stream Sediments (ppm)

       PCB          190
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
N/A
6/28/91
7/21/92
             Background

PRP-lead
PRPs:  Southeastern Pennsylvania Transit
       Authority; The National Railroad
       Passenger Corporation;
       Consolidated Rail Corporation
FS prepared by: Groundwater
       Technology, Incorporated
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       •  .    28,000 cubic yards of rail yard soil
       •      14,000 cubic yards of fuel oil impacted soil
       •      1,000 cubic yards of residential and other soil
       •      785 cubic yards of steam sediments


       What type of site is this?

       Transportation. A rail yard.
410
                                           -1-

-------
TECHNOLOGY SELECTION                                            '
                          •  .    -    .        •   •  '                       •['  , •       .    .

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                                                 i         f
        Rail Yard Soil/Fuel  Oil Impacted Soil/Residential and Other Soil
        Access restriction:
        Containment:

        Chemical treatment:
        Thermal treatment:
        Disposal:
        Sediments

        Access restriction:
        Containment:

        Chemical treatment:
        Thermal treatment:
        Disposal:
Institutional restrictions, deed and zoning restrictions
Cap (soil, asphalt, concrete, and multilayer), synthetic liners, surface
controls
Solidification/stabilization
Incineration (rotary kiln, fluidized bed, and infrared)
Excavation, on-site disposal in containment cell, off-site disposal at
TSCA permitted landfill
Deed and zoning restrictions, fishing restrictipns
Cap (soil, multilayer, concrete, and geotextile liner with rip rap stone),
surface controls                               ,
Solidification/stabilization                   |
Incineration (rotary kiln, fluidized bed, and infrared)
Excavatiqn, on-site disposal in containment cejl, off-site disposal at
permitted landfill                           j
5.       Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screeriing of technically
        feasible technologies were:

        Rail Yard Soil/Fuel Oil Impacted Soil/Residential and Other Soil j

        Biological treatment:   Biodegradation
        Chemical treatment:   KPEG.dechlorination, DCR dechlorinatibn, solvent extraction,
                             supercritical water oxidation, soil flushing (surfactant)
        Thermal treatment;     Thermal desorption, in situ vitrification, UV radiation
                                            ,        -,       .      '    .> .    . .-
        Sediments

        Biological treatment:   Biodegradation
        Chemical treatment:   KPEG dechlorination,, DCR dechlorination, solvent extraction,
                             supercritical water oxidation, UV radiation, soil flushing (solvent)
        Thermal treatment:     Thermal desorption, in situ vitrification, pyrolysis
                                              -2-
                                                                  411

-------
 6.      What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives .that merit a more detailed
         evaluation.  For this site, costs were estimated only during an evaluation based on nine criteria
         established by the NCP:  long-term effectiveness and permanence; short-term effectiveness;
         compliance with ARARs; protectiveness of human health  and the environment; reduction in
         contaminant mobility, toxicity, or volume; implementability; cost; state/support agency
         acceptance; and community acceptance.

         Fewer RAAs were presented in the ROD than in the FS, and several were renumbered. The
         RAAs discussed in  the ROD are presented parenthetically for each media under the list of"
         alternatives.

         Present worth cost estimates were not'calculated during the initial/three-criteria screening for
         any alternatives.                                                       ,

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)

         Rail Yard Soil                                                                       ,

412
Alternative
RAA-4B
(RAA-4B)
RAA-5B
(RAA-6B)
RAA-6B
(RAA-5B)
Innovative Technology
Excavation of soil with greater than 500
ppm PCB/KPEG dechlorination/zoning
and deed restrictions
Excavation of soil with greater than 500
ppm PCB/KPEG dechlorinatibn/soil cap
for areas with 25-500 ppm PCB
Excavation of soil with greater than 25
ppm PCB/KPEG dechlorination
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$11,098,949
$15,398,276
$24,424,397
        Fuel Oil Impacted Soil
Alternative
RAA-2A
RAA-3A
Innovative Technology
Excavation of soil with greater than 500
ppm PCB/KPEG or DCR dechlorination
In situ biodegradation
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$58,330
to
$84,130
$2,296,198
                                               -3-

-------
Residential and Other Soil
Stream Sediments
Alternative,
RAA-4A \
(RAA-2)
Innovative Technology
Excavation of soil with greater than
2 ppm PCB/KPEG dechlorination
Estimated Costs
3 Criteria
N/A
9 Criteria
$1,506,005
Alternative
RAA-3A
(RAA-3)
RAA-5A
(RAA-4)
RAA-4A
Innovative Technology
Excavation of sediments with greater
than 10 ppm PCB/KPEG dechlorination
Excavation of sediments with greater
than 1 ppm PCB/KPEG dechlorination
Excavation of sediments with greater .
than 10 ppm PCB/soil cap over areas
with 1-10 ppm PCB
iEstimated Costs
3 Criteria
N/A -
I
N/A
. N/A
1 ' -. .
9 Criteria
$919,028
$5,89,2,_617
$5,426,905
How did the cost(s) compare to standard technologies?             1

         Cost Estimates for RAAs That Include Standard Technologies
           _       (selected remedial .alternative is in bold)     j
                                          *•                 ' r "
Rail Yard Soil
Alternative
RAA-1
(RAA-1)
_,RAA-2
(RAA-2)
RAA-3
(RAA-3)
RAA-4A
(RAA-4A) .
RAA-4C
(RAA-4C)
Standard Technology
No action/long-term monitoring
Deed and zoning restrictions
Soil cap over areas with greater than 25
ppm PCB/deed and zoning restrictions
Excavation/stabilization/solidification of
soil with greater than 500 ppm
PCB/deed and zoning restrictions
Excavation/incineration of soil with
greater than 500 ppm PCB/deed and
zoning restrictions
Estimated Costs
3 Criteria
N/A ,
N/A
N/A
N/A
N/A .
9 Criteria
$546,431
$556,431
$11,304,723
$8,413,618
$14,325,449
                                    -4-
413

-------
414
Alternative
RAA-5A
(RAA-6A)
RAA-5C
(RAA-6C)
RAA-6A
(RAA-5A)
RAA-6C
(RAA-5C)
RAA-7
(RAA-7)
=====
Standard Technology
Excavation/stabilization/solidification of
soil with greater than 500 ppm PCB/soil
cap of areas with 25-500 ppm PCB
Excavation/incineration of soil with
greater than 500 ppm PCB/soil cap of
areas with 25-500 ppm PCB
Excavation/stabilization/solidification
of soil with greater than 25 ppm
PCB/on-site disposal in containment
cell/deed restrictions/erosion and
sedimentation controls
Excavation/incineration of soil with
greater than 25 ppm PCB
Excavation of soil with greater than 25
ppm PCB/off-site disposal in TSCA
landfill
•
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$12,540,095
$18,624,736
$16,266,742
$29,165,600
$26,808,830
        Fuel Oil Impacted Soil
            Alternative
          RAA-1
          RAA-2
          RAA-3
        Standard Technology
No action/long-term monitoring
Excavation/stabilization or incineration
In situ stabilization
                                                                      Estimated Costs
                                                                  3 Criteria
                                                                     N/A
                                                                   .  N/A
                                                                     N/A
9 Criteria
 $47,130
 $58,330
    to
 $84,130
                                                     $19,752,579
        Residential and Other Soil
========
Alternative
RAA-1
(RAA-1)
RAA-2
RAA-3
,* - ' -
Standard Technology
No action ;
Deed and zoning restrictions
Soil cap of areas (37 locations) with
greater than 10 ppm PCB
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$0
$120,408
$878,740
                                             -5-

-------

Alternative
RAA-4B
(RAA-2)
RAA-4C
(RAA-2)
RAA-5
' L
Standard Technology
Excavation of soil with greater than
2 ppm PCB/incineration
Excavation of soil with greater than
2 ppm PCB/stabilization/disposal of
soil at the rail yard
Excavation of soil with greater than 10
ppm PCB/off-site disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$1,606,755
$1,196,004
$1,645,505
Stream Sediments
Alternative
RAA-1
(RAA-1)
RAA-2
(RAA-2)
RAA-3B
(RAA-3)
RAA-3C
(RAA-3)
RAA-4B
RAA-4C
RAA-5B
(RAA-4)
RAA-5C
(RAA-4) .
RAA-6
Standard Technology
No action/long-term monitoring
Excavation of sediments with greater
than 10 ppm PCB/geotextile liner with
,rip rap/long-term monitoring
Excavation of sediments with greater
than 10 ppm PCB/incineration
Excavation of sediments with greater
than 10 ppm PCB/stabilization
Excavation of sediments with greater
than 10 ppm PCB/incineration/soil cap
of areas with 1-10 ppm PCB
Excavation of sediments with greater
than 10 ppm PCB/stabilization/soil cap
of areas with 1-10 ppm PCB ,
Excavation of sediments with greater
than 1 ppm PCB/incineration
Excavation of sediments with greater
than 1 ppm PCB/solidification/
stabilization/disposal of treated
sediments at the rail yard
Excavation of sediments with greater
than 1 ppm PCB/disposal off-site
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A ' -
N/A
9 Criteria
$39,588
$851,508-
$920,648
$900,398
$5,428,525
$5,408,275
$5,909,217
$5,701,717
$5,917,517
-6-
415

-------
   8.      If a standard technology was chosen, why?
                               •     ;               •           ' •                 •      '    .                '     "\
           Rail yard soil - Excavation and on-site treatment with stabilization/solidification for soils with           -''
           PCB concentrations > 25 ppm and deed restrictions. After treatment the solidified material
           would be placed back on-site in a containment cell.

           Residential and other soil - Excavation of residential  soils to achieve an average PCB
           concentration of 2 ppm per property.  Excavated soils will be returned to the rail yard property
           and treated using solidification/stabilization.

           Stream sediments - Excavation of sediments with PCB concentrations exceeding 1 ppm.
           Contaminated sediments would be returned to the rail yard and treated using
           solidification/stabilization.

           Fuel oil impacted soils - Though alternatives  are developed in the FS for this area, no source
           control remedy is selected in the ROD.  The area containing fuel oil impacted soil is covered
           with an impermeable asphalt cover and will be remediated with ground water treatment.

           PRP did not concur with clean-up goals.  PRP proposed:  1) excavation of soils > 500 ppm and
           treatment by solidification/stabilization, 2) off-site soils with concentrations > 10 ppm to be
           excavated and treated in the rail yard by solidification/stabilization, 3) sediments with
           concentrations > 20 ppm excavated and treated in the rail yard by solidification/stabilization.

           PRP proposed remedy was picked because: 1)  it reduces the mobility of the chemical              ijjflk
           constituents in the soil and reduces potential for direct contact by (a) adsorption and                '^& -v^.
           microencapsulation, (b)  decreasing the surface  area of material across which a transfer or a                J
           loss of chemical constituents can take place, tc) limiting solubility of contaminants; 2) proven
           technology used at a number of sites: 3) if excavation was limited to areas of contamination
           above 500 ppm, than critical operations of the  railyard would not need to be shut down during
          remediation so that AMTRAK and SEPTA passenger service would not suffer adverse
          impacts: 4) relatively simple and can be employed using common construction methods; 5)
          addition of cement would create an impermeable mass with  a high compressive strength and
          not increase the volume of material, all of importance in .implementation at a rail yard; 6) cost
          effectiveness.  Final determination by EPA of the selected alternative considered these
          implementability factors, except for number 3.


   9.      If an innovative technology was chosen, why?

          An innovative technology for source control was not chosen.


   10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?

          Innovative technologies could be eliminated from the remedial technology selection process at
          three stages: during the initial screening; during the screening of the three criteria of
          effectiveness, implementability, and cost; or during the detailed evaluation.
416
-7-

-------
In the FS for this site, standard and innovative technologies were identified and screened based
on implementability, effectiveness, and cost as a single step. Technologies are only
incorporated into RAAs prior to the detailed analysis.               i  -

Innovative technologies eliminated during the initial/three-criteria screening include the
following:

Rail Yard Soil/Fuel Oil Impacted Soil/Residential and Other Soil/Sediment

•      Supercritical water oxidation was eliminated because its effectiveness is uncertain and
        implementation would be difficult since the soil would need to be made into a slurry.
•      UV radiation was eliminated because the process is still in developmental stages and
        its effectiveness has not been determined.  The process requires the soil to be
        converted into a slurry form, which would create material handling problems.
•      Biodegradation was eliminated because its effectiveness has not been proved for all
        chlorinated biphenyls outside of the laboratory.        . .   '  j
•      In situ vitrification was eliminated because the effect ofthe tejchnology on
        underground utilities at the rail yard and .the load-bearing capacity of the vitrified mass
        were uncertain; and too difficult  to implement for sediment in streams and tributaries.
 •      Soil flushing was eliminated because the implementability of the technique was
        uncertain.  PCBs could mobilize and spread due to the very high hydraulic
        conductivity of the site's soils; and not applicable for use on sediments in streams and
        tributaries.
                               •                                  i
 Innovative technologies eliminated during the three-criteria screening include the following:

 •       Thermal desorption was eliminated because: 1) a treatability study showed no
         significant difference in the reduction in PCB concentrations in the soil and, therefore,
         can't achieve clean-up standards, 2) leachable lead in the treated soil is twice the
         TCLP regulatory level of 5 ppm because natural lead in the soil was destabilized by
         the process, 3) paniculate carryover was significantly high and would require use of
         cyclone separators and baghouses, 4) high paniculate carryover would increase the
         amount of carryover dust and  filter cake needing disposal in a TSCA  landfill.
 •      Solvent extraction was eliminated because: 1) it could not attainthetreatment
         performance of < 2 ppm (maximum residual attained was 16 ppm), '2) large amounts
         of suspended fines were present in the extract which would require enhancement by
         high-speed centrifugation, which would increase the processing time and the cost.

 Innovative technologies eliminated during the detailed analysis include the following:
                       -                   "                       u
  •      DCR dechlorination was  eliminated because proposed treatability studies were never
         completed.                                              1
  •      KPEG dechlorination was, eliminated because 1) recommended design parameters from
         SDTX Technologies, Inc. with regard to reaction time and reagent composition were
         not met, 2) KPEG/C1 molar ratios for bench scale testing was '10; however, SDTX has
         determined that there is no advantage to full scale operation at KPEG/C1 molar ratios
         greater than 3, 3) decanted fines in the reagent would require  centrifuges or filters to
         recycle the reagent causing material handling difficulties and, delays in operation.
                                         -8-
                                                                                            417

-------
   11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 w.-dch criterion?  Which of the criteria supported the use of a standard technology?

 For all media, the criteria that were weighted most heavily in selecting a standard remedial
 alternative were: protection of human health and the environment; reduction of contaminant
 toxicity, mobility, and volume through treatment; implementability and cost-effectiveness
 Dechlorination was the innovative technology proposed for all media except rail yard buildings
 and structures.  Dechlorination was eliminated because of implementability.
   12.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?                      l
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
PCB (rail yard)
PCS (residential)
PCB (sediments)
PCBs (indoor
surfaces)
25
.-. 2.
1
10 ug/100 cm2
Risk"
Risk"
DOF, OSWER
TSCA"
                TCB cleanup levels for industrial soil (25 ppm) represents a 3.5 X 10'5 incremental
                cancer risk. These levels satisfy EPA's "Guidance on Remedial Actions for Superfund
                Sites with PCB Contamination," OSWER Directive No. 9355.4-01, August 1990.
                TCB cleanup level  for residential soils (2 ppm) represents a 1 X 10'5 incremental
                cancer risk.                                          .                  .
                °PCB cleanup levels for sediments in streams and tributaries is consistent with
                Department of Interior (DOI), Ocean Assessments Division document "A Discussion of
                PCB Target Levels in Aquatic Sediments" and with OSWER Directive No  9355 4-01
                August 1990.                                                             '    '
                "TSCA spill policy referenced in EPA's "Guidance on Remedial Actions for Superfurid
                Sites with PCB Contamination," OSWER Directive No: 9355.4-01, August  1990.
  13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
         technology meet the cleanup goals?              -      .

         Innovative technologies-eliminated because of cleanup goals include:

         •      Solvent extraction
         •      Thermal desorption
418
        Standard technologies eliminated because of cleanup goals include:

        •     Capping
                                              -9-

-------
       The standard remedy selected, solidification/stabilization, met the; clean-up goals.
14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were conducted for several technologies, including biodegradation, thermal
       desorption, solvent extraction, stabilization/solidification, and KPEG aind OCR dechlorination.
       Treated residual levels were compared to the equivalent performance standard of 2 ppm.
       Studies show that  biodegradation would reduce fuel oil contaminants (total petroleum
       hydrocarbons) and thereby would immobilize PCBs, but not remove them.  Studies also .show
       that thermal desorption. and solvent extraction would have difficulties reaching soil PCB
       cleanup levels in areas with high PCB concentrations (e.g., greater thikn 900 ppm). Thermal
       desorption and solvent extraction were eliminated as potential technologies for this reason.
       Treatability studies also show that stabilization/ solidification and KPEG dechlorination
       effectively reduce  PCBs.  The studies indicated, however, that the KPEG dechlorination
       process would create material handling/ operational difficulties.  Treatability studies on DCR
       dechlorination were never completed.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Total cost
             Proven reliability
             Preference for treatment (vs. containment)
             waste left in place                    ,


16.     How are measures compared?
                                                                        i

        Achievement of clean-up standards and risk reduction required was important in comparing
        alternatives.  Risk reduction was a source of contention between the PRP and EPA.  Proven
        reliability was very important and was based on past use of solidification/stabilization and the
        treatability study done for the FS. Preference for treatment, eliminated many standard
        technologies  such as off-site disposal and on-site capping.  Treated waste had to undergo stress
        and volume tests to ensure it could be used on site.


 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        Because PCBs persist and bioaccumulate, their long-term reduction was a primary factor in the'
        choice of a remedial alternative. The hydraulic conductivity (permeability) of the site (10~5 to
        10"6 cm/sec)  is higher than the levels thought to be suitable for soil flushing (10~2 to 10"4). The
        potential for high hydraulic conductivity to cause the mobilization arid spread of PCB was a
        primary factor in the elimination of this technology.                |
                                               -10-
                                                                                                    419

-------
                                          Raymark
                                            OU-1

                                Hatboro Borough, Pennsylvania
                                           Region 3
                           3
GENERAL SITE INFORMATION

1,      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Surface soil (mg/kg)

       Trichloroethene             0.018
       Tetrachloroethene            0.18
       1,2-Dichloroethene           0.15
       Benzo(a)pyrene              6.9
       Benzo(a)anthracene          5.1
       Benzo(b)fluoranthene        6.3
       Benzo(k)fluoranthene        6.6
       Ideno(l,2,3cd)pyrene     ,    3.4
       Benzo(g,h,i)perylene         2.5
       Phenathrene                 3.7
       Fluoranthene                 9.6
       Pyrene                      9.1
       Chrysene             .       5.4
       PCBs                       2.1
       4,4-DDE                    0.076
       4,4-DDT                    0.426
       Cadmium                  78.6
       Nickel                     755
       Arsenic                    7.9
       Beryllium                   1.7
       Vanadium                  40.4

       Subsurface soil (mg/kg)

       Trichloroethene             3,100

      Bedrock (mg/kg)

      Trichloroethene             310
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
6/88
10/89
7/9l
12/30/91
                                                                 Background

                                                    EPA Fund-lead
                                                    PRPs:   N/A
                                                    FS prepared by:  CH2M Hill
420
                                             -1-

-------
2.      What volume of material is to be remediated?                      :                      ;
                                                        1            "    i       •
        The volume of material to be remediated included:
                                                     ' -                  i            •          •
                                                                        I    '   '
        •      The volume of material to be remediated was not given.  The; site covers 4 acres.
                       r         •        '              '      '            - •  '          '-;••-
                                                                        I

3.      What type of site is this?
                                                             .-  '        i •    •   '           •   '
        Fabricated Metal Products. An active manufacturer of rivets and fasteners.  The site is
        bordered by mostly industrial and some residential areas.


TECHNOLOGY SELECTION                           .                \
                       •                                                 i               -  .
4.      What standard technologies were considered for selection in this FS?
                                                                        j      .     •          • ..
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                 ;
                i"                      '                '               r  '      •
        Access restriction:     Fencing, restricted land use
        Containment:      ,    Capping (soil, clay, asphalt, concrete, synthetic membrane, multilayer),
                              slurry wall, vibrating beam, grout curtain, sheet piling
        Chemical treatment:    Solidification/fixation, neutralization, ion exchange, crystallization,
                              photolysis                                 i
        Physical treatment:     Oil/water separation, media filtration, membnine processes,
                              evaporation, distillation, liquid-liquid extraction,  flow and strength
      ,.'                      equalization, ion exchange, greensand, irradiation, flotation,
        Thermal treatment:     Incineration, gaseous incineration
        Disposal:             Excavation, landfill disposal (RCRA, non-RCRA)
5.      Was an innovative technology considered in the FS? If so, which technology?
                                                                       i  j         .
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                        !
                                 -  ,                  .      '' •.     '     j .    .   .
        Biological treatment:   Biodegradatioh (aerobic, anaerobic, in situ, ex situ)
        Phys/Chem treatment:  Solvent washing, critical fluid extraction, oxidation/reduction,
                              dechlorination, in situ permeable treatment bejds, soil washing (water),
                              in situ soil vapor extraction, in situ soil/bedrqck flushing
        Thermal treatment:     In situ thermal evaporation, in situ thermal stripping, in situ
                              vitrification, pyrolysis, wet air oxidation
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
                                                2                                                   421

-------
         evaluation.  In this case, the estimated costs were calculated during an evaluation based on
         nine criteria established by the NCP.            •

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
Innovative Technology
Excavation of surface soil/ stabilization/
disposal at RCRA landfill/soil vapor
extraction of subsurface soil and
bedrock
Excavation of surface soil/incineration/
stabilization/disposal at RCRA landfill/
soil vapor extraction for subsurface soil
and bedrock
Asphalt, cap over surface soil/soil vapor
extraction for subsurface soil and
bedrock
Excavation of surface soil/ stabilization/
disposal at RCRA landfill/soil vapor
extraction for subsurface soil/flushing
for bedrock
Multilayer cap on surface soil/soil
vapor extraction of subsurface soil
and bedrock
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$3,419,200
to
$5,461,500
$3,873,500
to
$5,992,300
$3,369,200
to
$5,175,600
$2,412,500
to
$3,644,100
$3,654,400
to
$5,173,000
        How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action
Estimated Costs
3 Criteria
N/A
9 Criteria
$381,400
 8.
422
If a standard technology was chosen, why?

A standard technology was not chosen.
                                             -3-

-------
9.      If an innovative technology was chosen, why?
                                                                   - ..  _ -i -     _    •'       •  •
       The chosen alternative was preferred because it provides the greatest protection to human
       health and the environment.  This alternative is protective because it addresses both current
       and future site risks.  The cap significantly and expeditiously reduces  site risk posed by direct
       contact with surface soil.  The principal site risk, however, is posed by TCE, located hi
       subsurface soil and bedrock.  The leaching of TCE to ground water is expected to pose a risk
       in excess of 10"4.  The proposed cap will reduce the infiltration of pnbcipitation through the
       soil and protect ground water by minimizing leaching of residual  TCEi into ground water.  The
       Hydrological Evaluation of Landfill Performance (HELP) model was Used to calculate the
       reduction in infiltration provided by various caps.  The proposed cap will be designed specially
       to reduce infiltration of precipitation.  Infiltration rate will be an estimated 24 times slower
       than its current rate.  The treatment to be implemented at the site is sioil vapor extraction
       (SVE).  SVE will reduce the major contamination threat to ground waiter, primarily TCE, from
       subsurface soil and bedrock.  The combination of the cap and SVE is preferred because any
       residual contaminants will be addressed without having to rely on a ground  water remedy.
       The cap also decreases the soil's moisture content, which in turn  increases,the soil's porosity,
       thereby increasing the efficiency of SVE. Also, cleanup levels could  be exceeded by installing
       a cap and using SVE.  This alternative also was preferred because it will not require
       excavation or soil movement and therefore it minimizes short-term risk.  Further, because
       contamination has been found beneath buildings and in bedrock, excavation would not be
       practical. The effectiveness of SVE is certain because, according to previous treatability
       testing at the site, SVE could remove VOCs from the subsurface  soil  and bedrock on site:  The
       technologies proposed are easily implemented and the chosen  alternative iis cost-effective.
JO.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                      '

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include; the following:
         •  - ;     '                 ''            .                       ; ' I
        •      Oxidation/reduction was eliminated because it would not be applicable to site
               contaminants.                                                             ' «-
        «      Organic chemical dechlorination was eliminated because it wbuld not be applicable to
               the site's waste types.                              .       :  .
        •      Biodegradation (aerobic, anaerobic,  in situ, ex situ) was eliminated because the
               process is unproven for eliminating contaminants of concern. I
        •      In situ permeable treatment beds was eliminated because it would not be applicable
               due to geologic conditions (i.e., the saturated zone in bedrock).
        •      In situ vitrification  was eliminated because it would not be applicable to bedrock
               contamination.
        •      Pyrolysis was eliminated because it would not be applicable tp the site's waste types.
        •      Wet air oxidation was  eliminated because it would not be  applicable to the site's waste
               types.
                                               -4-
423

-------
         Innovative technologies eliminated during the screening of the three criteria include the
         following:

         "      Solvent washing was eliminated because it has limited effectiveness for metals;
                residuals would be retained and would require treatment or disposal; it would not be
                effective in clay and silt soil; and its implementability would be poor due to low soil
                permeability, the proximity of buildings, the large volume of soil requiring excavation,
                and the high cost.
         •      Critical fluid extraction was eliminated because its effectiveness would be limited due
                to cadmium in soil. Further, additional treatments for cadmium would still be
                required.
         •      In situ thermal evaporation (radiofrequency) was eliminated because its effectiveness
                in bedrock is uncertain and it would not be implementable in bedrock.
         "      In situ thermal stripping (steam or hot air) was eliminated because it would be more
                difficult to design and operate  than SVE and would require high maintenance and
                costs.  Also, increasing the temperature would not be expected to increase the
                effectiveness of extraction since contaminants of concern already have a high
                volatility.
         •      Ex situ soil washing (water) was eliminated because it would not be very effective in
                clay and silt, the process would generate many residuals that require treatment and  •
                disposal, excavation would be difficult due to both the large volumes of waste and the
                building proximity, and the process would be comparable in cost to in situ
                technologies, which are preferred. Finally; surface soils have limited TCE
                contamination.

         Innovative technologies eliminated during the detailed analysis include  the following:

         •      In situ soil/bedrock flushing was eliminated because of the potential mobilization of
                contaminants to ground water.


         Which of the nine  criteria were weighted most heavily in selecting the technology? Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion?  Which of the criteria supported the use of a standard technology?

         The most heavily weighted criteria in selecting a remedial alternative were protection of
         human health  and  the environment and permanent reduction of contaminants.  The chosen
         alternative offers the greatest protection in both the immediate  future and the long term
         because it proposes technologies that address surface soil and subsurface soil/bedrock.  The
         proposed technologies act synergistically to reduce site contaminants, possibly even exceeding
        cleanup levels.
                                                          *.)
 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?
424
                       Contaminant
                 Carcinogens
                 Trichloroethene
Cleanup Level (ppb)
ARAR or Other Basis
         50
                                                                            Model"
                                               -5-

-------
Contaminant
Cadmium
Benzo(a)anthracene
Benzo(a)pyrene .
Benzo(b)fluoranthene
Indeno( 1 ,2,3-cd)pyrene
PCBs
Benzo(k)fluoranthene
Cleanup Level (ppb)
86,905
1,214
176
1,259
757
263
2,668
ARAR or Other Basis
Risk"
; Risk
Risk
Risk
1 Risk
Risk
Risk
Noncarcinogens
Benzo(g,h,i)perylene
8,111
[ Risk
              aSuiiimers model was used to calculate cleanup levels of soil contaminants.  This
              model predicts the soil concentrations required to prevent ground water contamination
              from leaching.
              bCleanup levels correspond to a 1CT6 risk.
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include: j

       • ,     None            .                       ,       ' •    :    "'I    •..'..;.•_..

       Standard technologies eliminated because of cleanup goals include:

       •     None          .          .          .            '.        : |  .

   •  '•              .                              '               •       J    '-'",-'
14.     Were treatability studies conducted on the innovative technology or standard technology?
                                      •  ' .      :             '  -          I  '     '       ' .   '   '
                                                                 1      I'  :
       EPA conducted a treatability study on SVE and concluded that this  technology was effective
       and  could be used to remove VOCs from the site's subsurface soil and bedrock.
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Time to design/construct/operate                      '
        -     Proven reliability
                                              -6-
425

-------
    16.    How are measures compared?

           The chosen alternative was preferred because it provides the greatest reduction of site risk
           through both SVE and capping.  Contaminant levels are reduced, residual risk is addressed,
           and the combination ensures that residual contaminants will not be affected by the infiltration
           of precipitation. Capping provides the quickest solution to risk posed by direct site contact.
           SVE is a proven technology since it was previously tested at the site.
    17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

The site's physical setting was a primary consideration in selecting a remedy.  TCE, the
principal site contaminant, is currently located in subsurface soil and bedrock which in some
instances is under buildings. The major risk to the site is the future mobilization of TCE to
ground water. The treatment technology selected, SVE, was most technically appropriate
because excavation, which would be very impractical, would not be required.
426
                                                 -7-

-------
                                      Resin Disposal
                                           OU-1

                              Jefferson Borough, Pennsylvania
                                          Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       Acetone                     2.046
       Bis(2-ethylhexyl)phthalate     0.916
       Dibenzofuran      '          0.804
       Di-n-butyl phthalate          0.778
       Methylene chloride           0.031
       2-Methylnaphthalene          1.75
       Naphthalene            ,' .   9.397
       Benzo(a)anthfacene           0.912
       Benzo(a)pyrene               0,775
       Benzo(b)fluoranthene         0.757
       Benzo(k)fluoranthene       .  0.733
       Chrysene                    0.808
       Fluoranthene                 1.556 '
       Phenanthrene                2.113
       Pyrene                      1.176
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
12/82
9/83
5/91
6/28/91
             Background
                  i
PRP-lead
PRPs:  Hercules Incorporated
FS prepared by: Roy F. Weston,
       Inc.
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      92,000 cubic yards of landfill waste.and soil.
       •      23,000 cubic yards of downslope soil.
       What type of site is this?

       Industrial Landfill.  A former landfill surrounded by a suburban residential area.
                                            -1-
                                         427

-------
  TECHNOLOGY SELECTION

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
         Access restriction:
         Containment:
         Physical treatment:
         Thermal treatment:

         Disposal:
Fencing, deed notation
Capping (low permeability, soil, synthetic geomembrane, admixtures,
chemical sealants/stabilizers, multilayers), dikes, berms, grading,
revegetation, slurry wall, grout curtains, injection grouting, sheet
piling, bottom sealing, skimmer wells, recovery wells
Dewatering
Incineration (rotary kiln, fluidized bed, multiple hearth, high-
temperature fluid wall reactor)
Excavation, landfill, secure vault, deep well injection
         Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Biological treatment:   Composting, slurry phase biodegfadation, solid-phase biodegradation,
                               land application
         Phys/Chern treatment:  In situ chemical treatment, soil washing, in situ soil washing
         Thermal treatment:    Low-temperature thermal  stripping, in situ volatilization, in situ steam
                               stripping, wet air oxidation, molten salt combustion, pyrolysis, plasma
                               arc pyrolysis, vitrification, in situ vitrification
         What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  For this site, technologies
         were screened generally for all source media.  Technologies were then incorporated into media
         specific options for the three-criteria screening process (effectiveness,  implementability, and
         cost) to identify alternatives that merit  a more detailed evaluation.  Comprehensive site
         alternatives were  then developed for the detailed analysis and estimated costs were calculated
         during an evaluation based on nine criteria established by the NCP: long-term effectiveness
         and permanence;  short-term effectiveness; compliance with ARARs; protectiveness of human
         health and the environment; reduction in contaminant mobility, toxicity,  or volume;
         implementability; cost; state/support agency acceptance; and community acceptance.         >
428
                                                -2-

-------
                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)    i
       Landfill waste
       Downslope soil
Alternative
WM-5A
WM-6A
WM-6B
Innovative Technology
Excavation/low-temperature thermal
stripping
In situ biodegradation
In situ soil washing
, Estimated Costs
3 Criteria
eliminated
_
N/A
eliminated
9 Criteria
N/A
. N/A
N/A
Alternative
S-5A
S-6A
S-6B,
Innovative Technology
Excavation/low-temperature thermal
stripping
In situ biodegradation
In situ soil washing
I • - ; -
Estimated Costs
3 Criteria
eliminated
eliminated
eliminated
9 Criteria
.'. .N/A
N/A
. N/A
       Comprehensive site alternatives for detailed analyses, proposed plan, and ROD
Alternative
RAA-6
Innovative Technology
In situ biodegradation
Estimated Costs
3 Criteria
N/A,
1
1
9 Criteria
$11,765,000
to
$19,985,000
7.      How did'the cost(s) compare to standard technologies?
                 -         •   .                      •                i'

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)     |
       Landfill waste
                                           -3-
Alternative
WM-1
WM-2
Standard Technology
No action -
Fencing/deed restrictions/monitoring
Estimated Costs
3 Criteria
N/A
, N>A
9 Criteria
N/A ,
N/A
429

-------
Alternative
WM-3A
WM-3B
WM-4
WM-5B
Standard Technology
Closure/fencing/multilayer cap
Closure/fencihg/multilayer cap/skimmer
well system
Excavation/off-site disposal
Excavation/incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
. N/A
N/A
N/A
N/A
         Downslope soil
Alternative
S-l
S-2
S-3
S-4
S-5B
Standard Technology
No action
Fencing/deed restrictions/monitoring
Excavation/consolidate into landfill/
multilayer cap
Excavation/off-site disposal
Excavation/incineration
/Estimated Costs
3 Criteria
N/A
N/A
eliminated
eliminated
eliminated
9 Criteria
N/A
N/A
N/A
N/A
N/A
         Comprehensive site alternatives for detailed analyses, proposed plan, and ROD
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-4
RAA-5
Standard Technology
No action ,.
Fencing/deed restrictions/monitoring
Closure/fencing/multilayer cap
Closure/fencing/multilayer cap/
skimmer well system
Excavation/off-site disposal'
Excavation/incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$2,452,000
$2,860,000
$3,127,000
$4,348,000
$25,538,000
to
$300,239,000"
$92,597,000
to
$174,797,000
430
         The large range in cost is due to the possibility that some waste may need treatment prior to
         disposal.                 .                 .                                       ,
                                              -4-

-------
8.      If a standard technology was chosen, why?

        RAA-3B was chosen because it provides a high degree of protection to human health and the
        environment. The risk assessment identified ground water as the mosit significant exposure
        pathway affecting human health.  The chosen alternative, via engineering controls, impedes
        further migration of waste or contaminated soil from the landfill. It also protects human health
        by eliminating direct contact with site soils through access restrictions and the placement of a
        multilayer cap.  The alternative meets all ARARs.  The proposed cap and leachate collection
        and treatment system offer a high degree of implementability.  Implementation requires less
        time than for other treatment alternatives.  The alternative minimizes ?hoit-term risk since it
        does not involve intrusive  activities in the  landfill and offers moderate degree of long-term
        effectiveness and permanence. While no treatment of landfill waste is proposed, engineered
        controls would be utilized  to manage the waste and contaminated media on site.  Long-term
        maintenance, monitoring, and institutional  controls are required to ensiure the effectiveness  of
        this remedy in the long-term.  Further, because of the relatively low risk associated with the
        site, EPA has determined that more costly  treatment technologies would not be justifiable.
        This alternative is cost-effective.
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.     If an innovative technology was not chosen, why not? At what stage vitas the innovative
       technology eliminated?
                                                                        I
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •       Composting was eliminated because a typical open air operation can lead to
               uncontrolled release of volatile organics to the atmosphere.  Also, very limited land
               availability on site restricts  the implementability of this process option.
       •       Slurry phase biodegradation was eliminated because the slurry requirement would
               significantly increase effective waste volume. Very limited on-site land availability
               and odor concerns would restrict the implementability of this process option.
       •       Solid-phase biodegradation  was eliminated because very limited land availability and
               odor concerns would restrict the implementability of this process option.
       •       In situ chemical treatment was eliminated because it would not be applicable since
               inorganics  are not a concern at the site.
       •       Soil washing was  eliminated because of concerns about implementability and
               effectiveness. Fine-grained  site soil (clay) would be unfavorable.  The organic
               compounds of concern are strongly held within the tight clay-s;oil mixture, which
               would limit the method's effectiveness.  In addition, fine-grained clay particles would
               be difficult to remove from  the washing fluid.               !
       •       In situ volatilization was eliminated because of concerns about; its implementability and
               effectiveness. Fine-grained  site soils would be unfavorable foi> applying an effective
                                              -5-
431

-------
                vacuum for extraction purposes.  Also, naphthalene has a relatively low volatilityswith
                respect to VOCs normally removed with this process.
        •      In situ steam stripping was eliminated because of concerns about its implementability
                and effectiveness.  Fine-grained site soil is not conducive to air or steam circulation.
        »      Wet air oxidation was eliminated because of the availability of other thermal
                technology process options that are conventional and have demonstrated effectiveness
                for the aromatic organic compounds of concern at the site. It would not be appropriate
                for solid residues.
        •      Molten salt combustion was eliminated, because other thermal technology process
                options were available that are conventional and have demonstrated effectiveness for
                the aromatic organic compounds of concern at the site.
        «      Pyrolysis was eliminated because other thermal technology process options were
                available that are conventional and have demonstrated effectiveness for the aromatic
                organic  compounds at the  site.  Also, transportable units would not be readily
                available.
        •      Plasma  arc pyrolysis was  eliminated because other thermal technology process  options
                were available that are conventional and have demonstrated effectiveness for the
                aromatic organic compounds at the site.
        «      Vitrification was eliminated because other thermal technology process options were
                available that are conventional and have demonstrated effectiveness for the aromatic
                organic compounds at the  site.                   •
        •      In situ vitrification was eliminated because other thermal technology process options
                were available that are conventional and have demonstrated effectiveness for the  .
                aromatic organic compounds at the site.  In addition, an underground fire could start
                with the flammable waste  materials and coal deposits present at the site.
        «      Land application was eliminated because it could result in spreading contamination via
                infiltration and runoff if the compounds of concern are  not effectively  degraded by the
                microbes. Further, there is limited land availability at the site and odor concerns,
                which limit the implementability of this option.

        Innovative technologies eliminated during the  three-criteria screening include the following:

        Landfill waste

        •      Low-temperature thermal  stripping was eliminated because it is unlikely that low
                treatment levels could be reached.  The ability to achieve low treatment levels is
                highly unlikely because  of the high concentrations of waste material and the physical
                variability of the material. If treatment goals are not attained, additional treatment
                prior to off-site disposal would be required, rendering this option not cost-effective.
        •      In situ soil washing was eliminated because it would result in a large volume leachate
                stream requiring treatment and the ability to collect/retrieve extract would be uncertain.
                The ability to  achieve low treatment levels is highly unlikely because of the high
                concentrations of waste material and the physical  variability  of the material.  Further,
                if treatment  goals are not  attained, additional treatment  prior to off-site disposal would .
                be required, rendering this option not  cost-effective. Finally, there is limited
                demonstration of this technology and the level of treatment that can be achieved is
                unknown.
432
                                                -6-

-------
Downslope soil
        Low-temperature thermal stripping was eliminated because potential excavation would
        adversely affect the perched ground water in the unconsolida ed zone, unnamed site
        stream and the associated ecological community.  Excavation
might result in VOC
        emissions to the atmosphere.  In addition, unfavorable conditions for effective
        treatment exist because of the tight clay matrix of the soil anji the presence of lower
        volatility PAH compounds such as naphthalene.          '   j   '
•      In situ biodegrodation was eliminated because the site's low permeability soils would
        be unfavorable for effective distribution of oxygen, nutrients,,! and cultured microbes.
        "An additional complicating factor is the flow of perched ground water through the
        unconsolidated soil zone, with discharge to the site stream, which greatly hinders the
        ability to achieve the hydrogeological flow control necessary !to effectively implement
        this technology."                                          i
•      In situ soil washing was eliminated because site soil is unfavorable for effective
        treatment because of its  low permeability. The soil tightly holds contaminants in a
        clay matrix, hindering effective distribution of required treatment materials. Also, soil
        washing is a separation process that results in a liquid waste that would require
        treatment and the ability to collect and retrieve extract would be uncertain.  "An
        additional complicating factor is the flow of perched ground water through the
        unconsolidated soil zone with discharge to the site stream, which greatly hinders the
        ability to achieve the hydrogeological flow control necessary to effectively implement
        this technology."     .  .                                   .       *•      ;
                            '   '           '           •     ,  .    [  '    •••'''•'
Innovative technologies eliminated during the detailed analysis include the following:

•      In situ biodegradation was eliminated because implementation of this process would
        be expected to have major limitations.  Concerns were raised about the high
        contaminant concentrations in the waste material. Some degradable contaminants
        might prove toxic  or inhibitory to microorganisms at sufficiently high concentrations
        In addition the degradation of complex organics, such as BNA compounds, might be
        limited by their  aqueous solubility. Further, when contaminants exist as large
        aggregates, microbial activity, which  occurs at the contaminant-water interface might
        be limited by the surface area of the waste material itself.  These factors could limit
        the rate or extent of biological treatment achievable. Thus, the level of treatment
        achievability is undetermined.  Treatability tests would be required to define
        achievable treatment levels. The ability  to treat in a highly variable waste and soil
        matrix also must be demonstrated.  The implementation of this process is likely to be
        an extended process because of the high concentrations of contaminants involved.
        And because of a long treatment period, the potential  for undesirable impacts
        increases. Further, microbial activity could mobilize sorbed contaminants.  This can
      "lead to potential impacts if not properly controlled via recoveiry and or interception.
        Finally, this process depends on the subsurface conditions being amenable to
        controlled flushing, which might not be feasible in the landfill waste.
                                                     '                                  433
                                       -7-    '    •   '•        :   ,     •-.•-.

-------
   11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology? If so.
          which criterion?  Which of the criteria supported the use of a standard technology?

          The criteria weighted most heavily in selecting a technology included protection to human
          health and the environment, short-term risk, implementability, and cost.  RAA-3B was chosen
          because it offers protection that is comparable to other alternatives, it can be quickly
          implemented, it will have little or no adverse effects on the surrounding community, and it
          costs less.  The chosen alternative provides a high degree of protection, which is greater than
          that offered by RAAs 1, 2, 3A, and 4, but comparable to RAA-5 and 6. RAA-5 was
          eliminated because of short-term risk associated with the large amount of intrusive activity on
          the landfill possibly causing traffic impacts and VOC emissions.  RAA-6 was eliminated
          because of uncertain effectiveness and difficulties in implementation. The chosen alternative is
          the cost-effective remedy because it eliminates the exposure pathway at a relatively low cost.
          RAAs 5 and 6 are significantly more expensive and would not offer a proportional increase in
          protection.  RAA-3A is comparable to RAA-3B except for cost.  The higher cost of RAA-3B
          is justified because this alternative presents a more  effective solution for the contamination
          with the addition of a skimmer well network.

          RAA-6 proposed in situ biodegradation, and it was  eliminated because of uncertain
          effectiveness, implementation difficulties, and high  cost.

                   *                         ,                                          •
   12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was  that
          ARAR? What risk level was selected to establish cleanup goals?

          No cleanup  levels are developed for landfill waste or soil.


   75.    Way the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          •     None

          Standard technologies eliminated because of cleanup goals include:

          •     None
   14.     Were treatability studies conducted on the innovative technology or standard technology?

          Treatability tests were not conducted.
                                                                         t

   15.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

               Cost/unit risk
434
                                                 -8-

-------
             Time to design/construct/operate
             Proven reliability
             Impact on nearby populations
16.    How are measures compared?
                    •      -                                 '           ''''
       RAA-3B was chosen because it offers the greatest protection. Of all the alternatives that offer
       comparable protection RAA-3B could be implemented in the shortest amount of time.  RAA-
       3B could be implemented in 9 to 12 months compared, to 24 to 36 months for RAA-5, and 36
       to 60 for RAA-6.  Further, RAA-3B does not pose short-term risk to pie community since it
       does not require intrusive activities at the landfill as RAA-4 and RAA-5 would. RAA-3B also
       was preferred because it provides comparable protection to RAA-5 arid RAA-6 at a much
       lower cost; RAA-3A is comparable to RAA-3B in cost, however, the higher cost of RAA-3B
       is justified because this alternative presents a more effective solution for the contamination
       with the addition of a skimmer well network.  Finally, the chosen alternative has been proved,'
       while RAA-6 was eliminated because of many uncertainties regarding implementation and
       effectiveness.
17.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?
        ' •         '                                             i          •  .
                                         •                     i
No technical consultation was primary in selecting a remedial alternative
                                            -9-
                                                                                              435

-------
                              Rhinehart Tire Fire Dump
                                           OU-2

                                    Winchester, Virginia
                                         Region 3
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Zinc                 300

       Sediments (mg/kg)

       Zinc                 2,880
2.      What volume of material is to be
       remediated?
                                    Site History

                       NPL Proposed:        N/A
                       NPL Final:           N/A
                       FS:                  N/A
                       ROD:                9/92

                                    Background

                       EPA Fund-lead
                       PRPs:  N/A
                       FS prepared by:  This early remedial
                              action for OU-2 is being
                              addressed before the completion
                              of the final phase of the RI/FS.
       The volume of material to be remediated included:

       H      An unspecified volume of pond sediments

       H      1,125 cubic yards of soil


3.     What type of site is this?                        '

       Uncontrolled Waste Site. The site is a tire storage site at which a tire fire occurred.  The .
       operable  unit is a lined containment pond built for containment of water generated during
       firefighting and oil products from burning tires.  The site is located in a sparsely populated
       rural area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
       Disposal:
 436
Excavation/off-site disposal


                -1-

-------
             an innovative technology considered in the FS?  If so, which technology?
            ,t                           '   •   ' •                          I
        No innovative technologies were considered during the identification and screening of  ~
        technically feasible technologies                                  !            >,

                                                        1                '           '       ••
 6.      What was the cost estimate for the innovative technology?           I

        During the initial screening process, in which technically feasible technologies are  identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives thai; merit a more detailed
        evaluation. No three criteria screening was carried  out in this FS.  Estimated costs were
        calculated during an evaluation based on nine criteria established by the NCR No innovative
        technologies were considered.                                     J
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected  remedial alternative is in bold)
Alternative
RAA-1
RAA-2
;
Standard Technology
No action
Excavation/soil and sediment testing/
off-site disposal/water treatment
Estimated Costs
3 Criteria
N/A
N/A.
9 Criteria
$0
$1,300,000

       An expedited remedial action was selected.  The selected alternative ^as the only alternative
       that proposed any action, and, therefore, was the only available choice.  By treating the surface
       water and removing contaminated soil and sediments, the selected action will eliminate the
       migration of contaminated surface water and sediments off site and remediate the surrounding
       pond soils to acceptable levels. Contaminated soils and sediments will be removed leaving no
       residual environmental risk from the pond. The selected action complies with all ARARs.  The
       technologies involve standarid site cleanup and construction procedures and should not present
       any unusual technical or administrative problems.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
                                              -2-
437

-------
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        "     None •                                    •
                           -"                          '
        Innovative technologies eliminated during the screening of the three criteria  include the
        following:                                         .

        «     None

        Innovative technologies eliminated during the detailed analysis include the following:

        «     None
 11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the. use of a standard technology?

        Overall protection of human health and the environment, compliance with ARARs, long-term
        effectiveness and permanence, and implementability were the criteria weighted most heavily in
        selecting a technology. Overall protection of human health and the environment is achieved
        through treating the surface water and removing contaminated soil and sediments, thereby
        eliminating the migration of contaminated surface water and sediments off site and remediating
        the surrounding pond soils to acceptable levels.  The technology complies with all ARARs.
        Long-term effectiveness, and permanence is achieved because contaminated soils and sediments
        would be removed leaving no residual environmental risk from the pond. The action is easily
        implemented because the technologies involve standard site cleanup  and construction
        procedures and should not present any unusual technical or administrative problems.
                                                         *
 72.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?
                      Contaminant
Cleanup Level (ppm)    ARAR or Other Basis
                 Noncarcinogens
                 Zinc
         50
Background
                Note:  Soil and sediment also will be tested to determine if any of the media are
                considered to be a hazardous waste under RCRA.
438
                                               -3-

-------
    13.
Was the innovative technology eliminated because of the cleanup
technology meet the cleanup goals?                   ,
                                                                       goals? Could the standard
           Innovative technologies eliminated because of cleanup goals include:


           •      None  .


           Standard technologies eliminated because of cleanup goals include:


           •      None
    14.     Were treatability studies conducted on the innovative technology or standard technology?
          Treatability studies were not conducted.




   75.    What measures/criteria were used to compare alternatives?


          None




,  16.    How are measures compared?


•          No measures were used to compare alternatives.
                „                             ,
   17.     What technical considerations were factors in selecting a remedy?  Were .technical

          considerations primary in the selection of the remedy?


          Technical considerations were not primary in selecting a remedy.
                                                -4-
                                                                                                  439

-------
                              Saunders Supply Company'

                                 ' Chuckatuck, Virginia
                                        Region 3
                                              J
GENERAL SITE INFORMATION

7.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Arsenic                    266
       Total chromium             252
       Copper                    158
       Hexavalent chromium       1.836
       Pentachlorophenol (PCP)    5.1
       Dioxins                    0.0025
       Total petroleum hydrocarbons  572

       Sediments (mg/kg)

       Pentachlorophenol (PCP)    230
       Dioxins                    0.00325
       Total Petroleum hydrocarbons  797
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1/87
10/89
5/91
9/30/91
            Background

EPA Fund-lead
PRPs:  Saunders Supply Company
FS prepared by:  Ecology and
       Environment, Inc.
2.      What volume of material is to be remediated?                       .   '  .

       The volume of material to be remediated included'.

       •      20,000 cubic yards of soil               ,
       »      566 cubic yards of sediment


3.      What type of site is this?                             '                             ,

       Lumber and Wood Products.  An active lumber yard that previously chemically treated wood.
       It is located in a mixed residential and commercial area.
440
                                           -i-

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection injhis FS?

        Standard technologies considered during the identification and screening of technically feasible
     ,   technologies were:

        Access restriction:     Fencing, deed restrictions
        Containment:          Capping (asphalt, cement, concrete, loam/sane, multilayer)
        Chemical treatment:    UV photolysis
        Physical treatment:     Stabilization/solidification, encapsulation
        Thermal treatment:     Incineration (fluidized bed, fix hearth, infrared, multiple hearth, rotary
                              kiln), electric reactor
        Disposal:              Excavation, disposal (on-site, off-site)
5.
Was an innovative technology considered in the FS? If so, which technology?
                                                                 \i
Innovative technologies considered during the identification and screening of technically
feasible technologies were:                           ^
       Thermal treatment:
Biological treatment:   In situ bioremediation, white rot fungus, bacteria
Phys/Chem treatment:  Dechlorination, soil washing, chemical extraction, critical fluid
                      extraction, in situ soil flushing               j
                      Molten salt, molten glass, pyrolysis, plasma systems pyrolysis, in situ
                      steam enhanced vacuum extraction, in situ steam/air stripping, low-
                      temperature thermal desorption, in situ vitrification, in situ radio
                      frequency heating
6.       What was the cost estimate for the innovative technology?

       .During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP. Numbers presented parenthetically represent changes in
        the nine criteria detailed analyses and the ROD.
                                                                        i
                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)     !
          Alternative
         RAA-4
         (RAA-3A)
         (RAA-3B)
                          Innovative Technology
                  Dechlorination/off-site disposal
                  Dechlorination/on-site disposal
                                              -2-
                                                                       Estinnated Costs
                                                                    3 Criteria
N/A
N/A
            9 Criteria
$25,934,000
                                                                                  $14,097,000
                                                                                                441

-------
Alternative
RAA-5
(RAA-4A)
(RAA-4B)
RAA-6
RAA-8
(RAA-5)
Innovative Technology
Low-temperature thermal desorption
of soil/dechlorination of sediment/off-
site disposal
Low-temperature thermal desorption of
soil/dechlorination of sediment/on-site
disposal
Soil washing
In situ vitrification
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$20,485,000
$8,648,000
eliminated
$15,945,000,
  7.      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative •
RAA-1
RAA-2
RAA-3
RAA-7
Standard Technology
No action
Asphalt cap/ground water treatment
On-site incineration
Off-site incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$320,000
$3,459,000
eliminated
eliminated
  8.      If a standard technology was chosen, why?

          A standard technology was not chosen
   9.      If an innovative technology was chosen, why?

          RAA-4A was selected because it is the most protective of human health and the environment.
          This alternative eliminates risk.due to direct contact with site soil and sediment, and reduces
          future risk associated with ground water contamination, because it will permanently eliminate a
          potential source of leaching contaminants.  PCP contamination in the soil constitutes the major
          threat and human health risk at the site. The chosen alternative utilizes two innovative
          technologies to treat the soil and sediment and dispose of treated materials off site.  Low-
          temperature thermal desorption will effectively heat and remove PCP from the soil.  The
          dechlorination process will be used for, sediment and it will destroy all the organic
          contaminants, including PCP and dioxin. Long-term ground water monitoring and institutional
          controls ensure the progress of the work. The chosen alternative was preferred because it
442
                                                 -3-

-------
        eliminates site contaminants and disposes of treated soil and sedimerit off site  Through
        treatment and disposal, this alternative provides a permanent reduction in site contaminant
        toxicity, volume, and mobility.  Off-site disposal of treated soil increases the long-term
        effectiveness of this alternative as no contaminants will be left on site to leach to ground water
        in the future., .The technologies proposed in this alternative will be easily implemented Upon
        completion, this alternative will comply with all ARARs. This alternative is cost-effective.
                                                                        I

10.      If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        fonovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                                 '                       •!                       •
       Innovative technologies eliminated during the initial screening include the following:

        •      Molten glass was eliminated because it would be inappropriate for soil with high ash
              content, and it  is still in innovative developmental stages with regard to
              implementability.
       •      Molten salt was eliminated because it would not be appropriate for material with high
              ash content and it has not been demonstrated on dioxin-contaminated materials.
       •      Plasma systems pyrolysis was  eliminated because it is still in research stages for
              hazardous waste.     .                                     j
       •      Pyrolysis was eliminated because it has not been demonstrated as an effective method
              to destroy dioxins.
       •      Chemical extraction was eliminated because the complex mixlaire of contaminants
              might make it difficult to create an effective solvent, the fine fraction of the soil might
              remain contaminated, and the fine particles are often difficult ;to remove from the
              solvent. This process is generally limited to waste with organic content in excess of
              200 ppm.                                                  j
     •  •      Critical fluid extraction was eliminated because its application is undetermined for
              hazardous organic waste and its availability might be limited, j
       •      White rot fungus was eliminated because it would be difficult to meet cleanup levels
              for dioxins  and  furans,  land disposal restrictions might prevent the implementation of
              land farming,  and fine-grained  soil might make slurry bioreactor treatment effluent
              difficult to settle.           ,                               i
       •      Bacteria was eliminated because it might be difficult to reach cleanup levels.  Previous
              bench-scale testing suggests that bacteria can degrade PCP, but that PCP in
              concentrations greater than 500 ppm could be toxic to microorganisms. Also, land
              disposal restrictions  might prevent the implementation  of land farming, fine  grained
              soil might make slurry bioreactor treatment effluent difficult toi settle.
      •      In situ bioremediation was eliminated because it would not achieve cleanup  goals for
              metals and dioxins, and its effectiveness for PCP contamination is questionable due to
              the highly variable concentrations  of PGP that would cause inconsistent
              biodegradation.  The presence of heavy metals could be toxic to microorganisms  and
              the low permeability of soil would hinder the movement of waler and nutrient throueh
              the soil.         ,                                                              6
      •      In situ steam enhanced vacuum extraction was eliminated because it would not achieve
             cleanup goals for metals and dioxins, and the low permeability | of the soil and


                         •         '    ..     .   '    -         '  -      'J-  '     .   '•    ••     443
                                             -4-  •.••-...:••

-------
             •    heterogeneity of the soil conditions would reduce the overall effectiveness of PCP
                 removal.
         •      In situ steam/air stripping was eliminated because it would not achieve cleanup goals
                 for metals and dioxins. The technique is not well demonstrated and all the mechanism
                 are not well understood. Commercial availability of the equipment is limited.
         •      In situ soil flushing was eliminated because a suitable washing solution would be
                 difficult to formulate due to the complex mixture of contaminants, and the
                 effectiveness would be limited by the low permeability of the subsurface soil, and the       -•       1
                 high percentage (approximately 30 percent) of silts and clay found in the soil.  Further,
                 contaminants absorbed to clay are difficult to remove by  flushing and site
                 contaminants are primarily found in the clay/silt soil fraction.
         •      In situ radio frequency was eliminated because its effectiveness would be limited by
                 the low permeability and high clay/silt content of the soil, it would not be an effective
                 remedy for metals and dioxins.

       .  Innovative technologies eliminated during the screening of the three criteria include the  '
         following:                                 ,                                             .               ;.

         •      Soil washing was eliminated because of the questionable  effectiveness in achieving
                 cleanup levels and/or PCP RCRA treatment standardsThe clay/silt sludge generated
                 would be concentrated with contaminants that require further treatment and/or disposal               i
                 that might not be available since incineration cannot address arsenic and dechlorination
                 is not effective on silt  and clay. A pilot study conducted on soil washing at another
                 wood treatment facility showed that PCP in concentrations ranging from 5 to 115
                 mg/kg remained following treatment (Sheehan,  1991).  Only 7.4 PCP ppm is allowed      tifa  \
                 for RCRA-permitted disposal.                                                          ^VF   /

         Innovative technologies eliminated during the detailed analysis include the following:

         »      In situ vitrification was eliminated because it would not offer as much long-term
                 effectiveness and permanence as the chosen alternative.  Further it might not be as
                 easily implemented as  the chosen alternative and treatability testing would be
                 necessary.


  11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative  technology?  If so,          <
         which criterion?  Which of the criteria supported the use  of a standard technology?

         The criteria that were weighted most heavily in selecting a remedial alternative were protection
         of human health and the environment, compliance with  ARARs, long-term effectiveness and
         permanence, and cost-effectiveness. The chosen alternative was preferred because it was the                 ;
         most protective option.  Following soil/sediment treatment, treated materials will be disposed
         off site.  Off-site disposal will  provide greater long-term effectiveness and permanence because
         at the risk based soil cleanup level, PCP might leach  into  the ground water at levels exceeding
         ground water cleanup levels. RAA-3B, RAA-4B and RAA-5 were not chosen because they
         would not offer as much long-term effectiveness since contaminants would remain on-site.
         Both RAA-3B and RA-4B proposed on:site disposal of treated soil/sediment'and contaminants
         remaining in treated soil/sediment could leach into  ground water at concentrations in excess of
         MCLs.  RAA-5 also would contain contaminants on site in a vitrified mass and treatability
         studies would be needed to assess the magnitude of residual  risk.

444                                           5

-------
       Compliance with ARARs also was a concern.  RAA-3B and RAA-4B were not preferred
       because they might not comply with ARARs since they contain on-site disposal of treated soil
       and sediment.  Either alternative would meet the Virginia Solid Waste Management
       Regulations requirement for treatment to background conditions prior; to backfilling of treated
       soil/sediment on-site.                       .           ,          i

       Finally, while RAA-3A would have offered as much protection and piermanence as the chosen
       alternative it was not chosen because it would be more expensive and therefore not cost-
12.
13.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
Contaminant ,
Cleanup Level (mg/kg)
ARAR or Other Basis
•
Carcinogens ,
Arsenic
Chromium VI
Pentachlorophenol
Dioxin/furansb "
Dioxin/furans'
5i7
• 0.82
1.46
0.001 (TEP)
0.010 (TEF)
i Risk"
Risk
Risk
EPA"
EPA
i
Noncarcinogens •,'•
Chromium HI
Copper
559,000
2,600
Risk
Risk
              Tor carcinogens, an excess upper bound individual lifetime cancer risk of 10'6 was
              acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was
              acceptable.                                             j
              bUpper 1 foot of soil and sediment.                       !
              Toxicity Equivalent Factors.                             !     "        -
              dU.S. EPA, 1991, Correspondence (Waste Classification) witf'f A. Palestini,  U.S. EPA
              Region HI, Philadelphia, PA.  Also used at Times Beach, Missouri.
              eSoil below  1 foot.                                    -•  !,'
Was the innovative technology eliminated because of the cleanup goals?  Could the  standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

       White rot fungus
       Bacteria
       In situ bioremediation
       In situ steam enhanced vacuum extraction
       In situ steam/air stripping
                                             -6-
                                                                                       445

-------
           Standard technologies eliminated because of cleanup goals include:

           •      None


   14.     Were treatability studies conducted on the innovative technology or standard technology?

           Treatability studies on biological treatment were conducted during the RI. The results
           suggested that the presence of high concentrations of PCP (greater than 500 ppm) could be
           toxic to microorganisms.


   15.     What measures/criteria were used to compare alternatives?

           The following measures were used to compare the alternatives:        <                                   ,

                Percentage risk reduction
                Cost-effectiveness
                Preference for treatment (vs. containment)


   16.     How are measures compared?

           Cost-effectiveness was a deciding factor. Another alternative (RAA-3A) would have provided
           the same degree of protection-and effectiveness as the chosen alternative but it was not            jtfa   v
           selected because it would  have cost more.  The permanent reduction of risk through treatment      ^ir   J
           and off-site disposal was a prominent factor in selecting an alternative.  Other alternatives that
           would have left contaminants on site either in a vitrified mass or in disposed treated
           soil/sediment were not considered as protective as the chosen alternative. Contaminants left on
           site would be a future potential source of leachate into the ground water.


   77.     Wtiat technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in  the selection of the remedy?

          Soil characteristics were primary in selecting a remedial alternative. The low permeability and
          high clay/silt content of the soil precluded the use of in situ steam enhanced vacuum                        !
          extraction, in situ soil flushing, and in situ radio frequency. The high ash content of the soil
          precluded the use of molten salt and molten glass technologies.  And the fine particles of sand
          precluded the use of chemical  extraction.

          References                                                                                            ;

          Sheehan, P., April 1991, Personal communication, Regional Manager, Biotrol, Inc. Princeton,                '.',
          New Jersey.                   .                                                 .    '  '                •;'
446

-------
                                  Strasburg Landfill
                                         OU-3

                              Newlin Township, Pennsylvania
                                        Region 3
GENERAL' SITE INFORMATION
1. What were the principal contaminants,
contaminant levels* and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:
Sampling was not conducted directly in the
landfill. Sampling was carried out for
sediment around the leachate seeps.
Soil/sediment (mg/kg)
1,1-Dichloroethane 0.085
1,2-Dichloroethene 0.039
Toluene 0.023
4-Methylphenol 0.39.0
Benzoic acid 0.054
Antimony 34
Arsenic 53
Barium 903
Beryllium 3.4
Iron, 425,000
Manganese 2,090
Chromium 192
Nickel ' 33.5 ,
Mercury 0.27

Siteffiiitory
NPL Proposed: 6/88
NPL Final: 3/89
FS: '_ 9/91
ROD: 3/31/92
Background
EPA Fund-lead
PRPs: N/A
FS prepared by: ARCS Contract - no
company name was listed.
. . '
       What volume of material is to be remediated?
                               •      ,               '
       The volume of material to be remediated included:

       •      3 million cubic yards of waste and soil/sediment


       What type of site is this?
       Industrial Landfill. A former landfill that received industrial and heavy metal waste. It is
       located in a primarily residential and agricultural area.
                                           -1-
                                                                                     i
447

-------
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:                                               '
          Access restriction:
          Containment:

          Disposal:
Fencing                                          -       •   '
Caps, retaining dikes and berms, drainage control facilities, in situ
grouting
Excavation, disposal
   5.      Was an innovative technology considered in the FS? If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:

          No innovative technologies  were proposed.
          What was the cost estimate for .the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. In this case, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.  Alternatives presented parenthetically represent changes
          in the ROD.  No innovative technologies were  incorporated into remedial alternatives.
   7.      How did the cost(s) compare to standard technologies?

                    Cost Estimates for RAAs That Include Standard Technologies
                               (selected remedial alternative is in bold)
Alternative
RAA-1
(RAA-1A)
RAA-2
RAA-3
RAA-4
(RAA-2)
Standard Technology
No action/monitoring '
Limited action/monitoring/deed
restrictions .','
Provide alternative water supply/
ground water monitoring
Point of use ground water treatment
RCRA cap/passive gas collection
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$3,044,700
N/A
eliminated
eliminated
$10,420,850
443
                 -2-

-------
• - • • • - ' '.''..' ' • .
Alternative
RAA-5
(RAA-3)
RAA-6
(RAA-4)
RAA-7
(RAA-5)
Standard Technology
RCRA cap/passive gas collection/
leachate system
RCRA cap/landfill gas collection system
RCRA cap/landfill gas collection
system/leachate collection system
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$11,306,460
$10,998,140
$11,883,750
' • .--'.:. ..•.•••_,'•.
8.      If a standard technology was chosen, why?                       j
                                  ."'               •"                    i

        The chosen alternative RAA-5 (RAA-3) was preferred because capping tthe landfill with a
        RCRA cap reduces the amount of leachate generated by precipitation infiltrating through the
        existing landfill cap and the refuse.  Further, impacts to the ground water will be effectively
        reduced.  Landfill caps have been demonstrated to be very effective in preventing human
        health risks such as those posed at this site.  A leachate collection system collects and treats
        leachate that migrates^to the toe of the landfill.  Through leachate treatment, this alternative
        reduces contaminant toxicity, mobility, and volume.  These actions reduce human and
        environmental receptor exposure to acceptable levels. The technologies proposed in this
        alternative are readily available. This alternative is cost-effective.
9.   '   If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the'three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the  following:

•      None
       Innovative technologies eliminated during the screening of the three criteria include the,
       following:                  .j.
                                     f       '       ~                    i
       •      None                     ,                               :
       Innovative technologies eliminated during the detailed analysis include the following:
                                                                       i'  '  ••   •
       '•      None                         •'     '•'.'•'..[••
                                              -3-
                                                                                        449

-------
77. Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 Protection of human health and the environment and cost were the criteria that were weighted
 most heavily in selecting a remedial alternative. RAA-1 and RAA-1A would not be protective
 since they propose only access restrictions. Currently, recreational activity occurs on site even
 though warning notices are posted. RAA-2 also would not be protective enough because it did
 not adequately address leachate seeps, which are an identified source of contamination. The
 chosen alternative was preferred over RAA-4 and RAA-5 because they would offer only a
 small increase in protection but for a much higher cost.


72. What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR? What risk level was selected to establish cleanup goals?

 No cleanup levels were established for soil/sediment.       •


13. Was the innovative technology eliminated because of the cleanup goals? Could the standard
 technology meet the cleanup goals?
*     -     ,    *
 Innovative technologies eliminated because of cleanup goals include;
   •'
               1

 Standard technologies eliminated because of cleanup goals include:

 • None  •  ,


14. Were treatability studies conducted on the innovative technology or standard technology?

 Treatability studies were not conducted.       t


75. What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

  Cost/effectiveness  ~ , •


16. How are measures compared?

 Cost and protectivene.ss were the reasons RAA-3 was selected over RAA-4 and RAA-5. It
 was felt that the incremental increase in protectiveness offered by RAA-4 and RAA-5 was not
 enough to justify their increased cost.
450
       -4-

-------
17.     What technical considerations were factors in selecting a remedy?  Wen" technical

       considerations primary in the selection of the remedy?             :
                                               •-                      I

       No technical considerations were primary in selecting a remedial alternative.
                                                                                           451

-------
                                   Tonolli Corporation

                    Nesquehoning Borough, Carbon County, Pennsylvania
                                          Region 3
GENERAL SITE INFORMATION   ,.

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Waste Piles and Byproducts (mg/kg)

       Lead                 317,000

       Site Soil (mg/kg)

       Lead                 95,200

       Off-site Soil (mg/kg)

       Lead                 4,410

       Sediments (mg/kg)
                                    Site History
                       NPL Proposed:
                       NFL Final:
                       FS:
                       ROD:
6/88
10/4/89
1/31/92
9/30/92
                                    Background

                       PRP-lead
                       PRPs:  528 PRPs were identified for this
                              site. 46 PRPs entered into an
                              Administrative Consent Order
                              with EPA. Individual PRPs are
                              not listed.
                       FS prepared by:  Paul C. Rizzo
                              Associates, Inc.
        Lead
        Arsenic
        Copper
600
34
33.3
        Landfill/Solid and Hazardous Waste (mg/kg)

        Lead                 68,300
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        »      The waste piles and byproduct materials include approximately 13,000 cubic yards of
               battery casings, 2,020 cubic yards of treated sludges, 243 cubic yards of dust, 210
               cubic yards of excavated lagoon soils, and 250 drums of melted plastic.
        •      Approximately 39,000 cubic yards of site  soils contaminated with lead above a
               concentration of 1,000 ppm will be excavated from on-site areas.  7,300 cubic yards of
               soils containing the highest total lead concentrations will be treated (see Question 8).
        "      The quantity of off-site  soil to be  remediated was not given.
        •      The quantity of sediments to be remediated was not given.
 452
                                              -1-

-------
        •      Approximately 105,000 cubic yards of solid and hazardous waste are contained in the
               landfill which covers 10 acres.                            !

 3.      What type of site is this?

        Recycling.  A former battery recycling and secondary lead smelting plant which ceased
        operating in January 1986. The site covers approximately 30 acres and is located in an
        industrial park.
TECHNOLOGY SELECTION
                                                                       : I         '

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                               !
                             \ •
        Access restriction:
        Containment:

       , Chemical treatment:
        Physical treatment:
        Thermal treatment:

        Disposal:
Institutional controls (deed restrictions)
Capping (clay, asphalt, concrete, synthetic membrane, composite, soil),
vertical barriers
In situ stabilization/solidification            |
Beneficiation (resource recovery), on-site chemical bonding (alumina
silicates), resource recovery (smelting, extraction/electrolytic recovery,
leaching/microfiltration)
On-site and off-site incineration (rotary kiln, jfluidized/bed combuster,
infrared, plasma arc)
On-site landfill, off-site landfill (CERCLA, municipal waste, residual
waste)   •    ,                                          ~
        Was an innovative technology considered in the FS?  if so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                           .             i
                      1                    '                              '!•'''

        Chemical treatment:    In situ electroreclamation, in situ soil flushing, on-site solids
                              washing/leaching (BOM Process, ETUS, Inc., Canonic Process)
        Thermal treatment:     In situ vitrification, pyrolysis, on-site molten glass
6:      What was the cost estimate for the innovative technology?           !

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria scnsening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  A three-criteria screening was conducted for this site but no costs were generated
        during this process.  Instead,  the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.  The designation of RAAs changed into the ROD.  These
        changes are presented parenthetically below.,                       j
                                              -2-
                                                                      453

-------
        Cost Estimates for RAAs That Include Innovative Technologies
                    (selected remedial alternative is in bold)

Alternative
RAA-4
Option a and
Option b"

RAA-5
Option a and
Option ba

RAA-6
Option a, b, c
anddb













RAA-7
Option a and
Option ba






i
Innovative Technology
Soil capping/resource recovery (off-site
lead smelter)/RCRA cap on landfill


On-site soil disposal in landfill/resource
recovery (off-site lead smelter)/RCRA
cap on landfill/decontaminate buildings/
natural attenuation
On-site soil treatment (soil washing
and solidification/stabilization)/
resource recovery (off-site lead
smelter)/RCRA cap on land-
fill/decontaminate building







,



Off-site soil treatment (stabilization)/
resource recovery (off-site lead smelter)/
RCRA cap on landfill/decontaminate
building




Estimated Costs
9 Criteria
$9,000,000
RAA-4a
$9,200,000
RAA-4b
$9,400,000
RAA-5a
$12,300,000
RAA-5b
$16,800,000
RAA-6alc
$16,900,000
RAA-6a2
$24,100,000
RAA-6bl
$24,200,000
RAA-6b2
$26,100,000
RAA-6cl
$26,200,000
RAA-6c2
$37,900,000
RAA-6dl
$38,000,000
RAA-6d2
$27,700,000
RAA-7alc
$27,800,000
RAA-7a2
$43,700,000
RAA-7bl
$43,800,000
RAA-7b2
ROD
$9,200,000
(RAA-4)
eliminated

eliminated

$12,310,000
(RAA-5)
eliminated

eliminated

eliminated

$24,179,000"
(RAA-6)
eliminated

eliminated

eliminated

eliminated

eliminated

eliminated

eliminated

$43,760,000
(RAA-7)
"Option a:  Action Level - 3,200 mg/kg lead (calculated risk-based level).
 Option b:  Action Level - 1,000 mg/kg lead (evaluated at EPA's request).
bOption a:  Stabilization, Action Level - 3,200 mg/kg lead (calculated risk-based level).
 Option b:  Stabilization, Action Level - 1,000 mg/kg lead (evaluated at EPA's request).
 Option c:  Soil Washing, Action Level - 3,200 mg/kg lead (calculated risk-based level).
 Option d:  Soil Washing, Action Level - 1,000 mg/kg lead (evaluated at EPA's  request).
cOptions 1  and 2 (e.g., RAA-6al and RAA-6a2) specify ground water treatment techniques.
 Option 1 incorporates natural attenuation of ground water and Option 2 incorporates ground
water flushing.
                                       -3-

-------
        *The selected RAA was modified in the ROD and the final estimated present worth cost for
        the modified RAA was $16,616,000 (see Question 8).,
 7.      How did the cost(s) compare to standard technologies?
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)

Alternative
RAA-1
RAA-2
RAA-3
Option a - soil
cap
Option b -
asphalt cap
Option c -
concrete cap

Standard Technology
No action
Limited action/institutional control
Soil capping/RCRA cap on landfill/
decontaminate buildings





Estimated Costs
9 Criteria
$550,000
$4,000,000
$5,700,000
RAA-3a
$6,2100,000
RAA-3b
$7,100,000
RAA-3c

ROD
$550,000
$4,000,000
$6,213,000
(RAA-3)
eliminated

eliminated


8.      If a standard technology was chosen, why?

       The selected alternative RAA-6b2 is a modified version of the Preferred .Alternative described
       in the July 18, 1992, Proposed Plan.  During the public comment period, EPA received new
       information which indicated that EPA's remedial action objectives ami health-based cleanup
       levels could be met by an alternate approach to treating contaminated site; soils.  This
       information also indicated that such an alternate approach to soils treatment would be more
       cost-effective.  Based on an evaluation of this information, EPA selected a different "trigger"
       level  to define soils that pose a principal threat and that require treatment prior to their
       consolidation in the on-site landfill.  The modified Alternative 6 requires the treatment of
       contaminated soils defined as a principal threat (i.e., soils with lead levels exceeding 10,000
       mg/kg, or one order of magnitude greater in concentration than the cleanup level) via on-site
       stabilization prior to consolidation in the on-site landfill.  Remaining soils (i.e., soils
       containing lead between 1,000 and 10,000 mg/kg) will be consolidated in the on-site landfill,
       in combination with a more passive treatment method designed to significantly reduce the
       potential for contaminant leaching. This passive treatment consists of adding a layer of
       crushed or pulverized agricultural limestone to the on-site landfill as part of the cap
       construction and landfill closure. The modified remedy also differs fijom the Proposed Plan in
       the estimated cost for remediation.  The modified remedy combines certain features (i.e.,
       handling of contaminated site soils) of Alternative 5 with Alternative J5. The estimated present
       worth cost of this modified alternative is $16,616,000 (this cost was first ireferred to in Section
       XI of the ROD, Explanation of Significant Changes). Other changes in the modified plan
       from  the preferred alternative in  the Proposed Plan include a month shorter implementation
       time,  and off-site soils will be consolidated in the on-site landfill prioir its closure rather than
       treated on site via stabilization.
                                              .4.
455

-------
        The modified remedy was chosen because the combination of treatment to address the              ^,
        principal threats and engineering controls (i.e., containment) to address lower level threats will             j
        effectively reduce and eliminate the potential risks posed by the site contaminants.  The     >       '    -^
        modified remedy was chosen because it provides an equivalent level of protection and long-
        term effectiveness as the originally proposed remedy, while being somewhat more cost-
        effective. The chosen stabilization converts the contaminated soils into a less soluble and less
        mobile form that meets the treatment requirements of RCRA Land Disposal Restrictions.  The
        on-site treatment of soils prior to disposal significantly reduces the threat posed by
        contaminated materials by reducing the toxicity and mobility of contaminants.  The
        stabilization process increases material volume by approximately 20 percent, but reduce
        toxicity and mobility. In addition, the selected modified alternative will attain compliance
        with all ARARs. The selected  alternative is implementable and utilizes readily available and
        reliable technologies. During the completion of the FS for this site, Chemfix  conducted a  '
        treatability study on Tonolli Corporation waste as a representative option for on-site
        solidification/stabilization.  This study was successful  in formulating a lead treatment system
        that reduces the leachability of lead in the waste to levels below the regulatory standard of 5
        ppm (see answer to Question 14).


 9.      If an innovative technology was chosen, why?

        The selected remedy also includes the off-site resource recovery (secondary lead  smelting) of
        approximately 13,000 cubic yards of battery casings and wastes. The toxicity, mobility, and
        volume of battery casings will be reduced due by shipping the waste off site for resource
        recovery. A treatability study conducted during the preparation of the FS confirmed that this       ^pr —,.
        remedial action  determined that battery case materials from the site could be processed in,                  }
        Exide's Reading, Pennsylvania, facility.


 10.    If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the  remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria  of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        •      In situ  electroreclamation was eliminated because the.presence of slag in the landfill
                and the high  iron content of site soils would reduce the technical reliability of this    :
                technology. Metal objects such as iron were reported to increase energy consumption      >         ;
                and remediation time.  This technology has not been  widely used and therefore does
                not have an adequate performance record. The FS  states that two in situ field
                experiments and one full-scale remediation  project have been performed  with this
                technology (Lageman et al., 1990)
         •      In situ soil flushing was eliminated because the flushing solution could not be captured
                for the unsaturated soils and debris media, given/the porous nature of the mine spoil
                and alluvium. The landfill constituents would not be amenable to soil flushing due to        ^^
                the heterogeneous nature of the material, the unknown distribution of the material, and       flip  V
                the potentially large pieces of slag (up to several feet in diameter) with high                       A
                concentrations of lead  (up to 3 percent) scattered throughout the landfill.

456                                                                                                         i
                                                -5-                •            '    •                      -

-------
 •      In situ vitrification was eliminated due to the high moisture content of the landfill. A
        significant portion of the site's soil consists of coal mine spoils that might generate
        more off-gases than could be controlled by the hood.  A recent pilot- scale project (not
        referenced in the FS) at another site failed due to off-gases [splattering molten glass
        (soil) into the hood.
 •      On-site solids washing/leaching (BOM Process, ETUS, Inc.) were eliminated because
        the Canoriie Process was chosen instead to represent solids washing/leaching treatment
        options in the development .of remedial action alternatives slince this process had been
        used at the Gould Site in Portland, Oregon.  The FS discusses the BOM Process as
        implemented by Foster Wheeler Enviresponse (Coles, 1990). TJie Environmental
        Technology (ETUS, Inc.) process uses a milder acid solution than the BOM process.
        "Other solutions that have met with little or no success include EDTA, anionic
        surfactant, tap water (Barth and Traver, 1990) and acid. This process was eliminated
        because it is unclear if the washing process would be  applicable and it is known that
        some materials such as EDTA chelate with lead making treatment extremely difficult."
 •      Pyrolysis was eliminated because it would not be an effective means of treating lead.
-•      On -site molten  glass was eliminated because this technology has not been
        demonstrated for battery wastes.
 •      Resource recovery: extraction/electrolytic recovery was eliminated because it would
        be ineffective for the site's low lead concentrations. According to a study by PEI
        Associates, removal efficiencies for this process approached 90 percent for chelate
        solutions with initial lead concentrations greater than 1 percent  while removal
        efficiencies were below 40 percent for a 0.2-percent lead solution.

 Innovative technologies eliminated during the screening of the three; criteria include the
 following:                                                     .

 •      Resource recovery: leaching/microfiltration was eliminated but  no reason was given.
        During the initial screening stage, the FS states that this technology would be a
        potentially effective treatment procedure for removing constituents that exist above a
        diameter of 0.1 microns. Since this particle size is likely to contain a significant
        portion  of lead  and other metals, this process option was retained.  The FS refers  to
        E.I. duPont de Nemours and Co., Inc. and Overlin Filter Co., and EPOC Water, Inc. as
      •  two of the available microfiltration processes that might be considered innovative.
                                                                  ,
 Innovative technologies eliminated during the detailed analysis include the following:

 •      Soil washing (Canonic Process) was eliminated based on the results of treatability
        screenings completed during the FS for this site. EPA preferred
        solidification/stabilization over soil washing.  The soil washing  technique was expected
        to be a  slower process  than on-site stabilization and would generate a hazardous
        residual requiring off-site treatment and disposal.  In addition, this technique was
        expected to be significantly more costly than  stabilization  for on-site soils. The soil
        washing process was eliminated based on cost, implementation time, and effectiveness.
        The stabilization treatment method better met the criterion (if reducing toxicity,
        mobility, and volume through treatment.
                                        -6-
457

-------
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting the remedy were overall protection of human
       health and the environment, long-term effectiveness and permanence, and reduction of toxicity,
       mobility or volume  through treatment. Because EPA anticipates the site will be used for
       industrial purposes after the cleanup, permanence and long-term effectiveness were  of critical
       concern. The selected remedy effectively reduces the contaminated area at the site  to one-third
       of its original area,  and minimizes the operation and maintenance requirements for the
       remedial activities.  Community acceptance also was critical in selecting the modified remedial
       action.  The original selected alternative  was modified based on EPA's consideration of new
       information and extensive comments submitted during the public comment period (particularly
       from a local water authority and from a group of PRPs for the site).  The Commonwealth of
       Pennsylvania has not concurred with the selected .remedial action.


12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

               On-site Soil/Waste Piles/Battery  Casings
                    Contaminant
Cleanup Level (mg/kg)   ARAR or Other Basis
                Carcinogens
                Lead
         1,000
EPAa
              "Cleanup level is based on present EPA policy which uses a range of 500 to 1,000
              mg/kg in residential areas to protect the health of young children, as supported by the
              Integrated Uptake/Biokinetic Model:  As there are currently no recognized methods for
              evaluating lead exposure in adults, EPA chose the upper bound of the "residential"
              range, as a reasonable cleanup level to protect the health of adult on-site workers.
              EPA believes that this soil cleanup level will protect ground water.

              Off-site Soil
                    Contaminant
Cleanup Level (mg/kg)   ARAR or Other Basis
                Carcinogens
                Lead
         500
EPA"
              •Cleanup level is based on present EPA policy which uses a range of 500 to 1,000
              mg/kg in residential areas to protect the health of young children, as supported by the
              Integrated Uptake/Biokinetic Model.

       Based on comments received from the-U.S. Department of Interior, Fish and Wildlife  Service,
       EPA deleted the reference to a 450 mg/kg-sediment cleanup level for lead that was included in
       the Preferred Remedy described in the Proposed Plan.  Additional sampling and bioassays will
 451
                                              -7-

-------
        be conducted to determine an appropriate cleanup level for the contaminated sediments that
        have been detected in Bear and Nesquehoning Creeks.                   .


 13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup  goals?
i             .                            '                               i
        Innovative technologies eliminated because of cleanup goals include:
                                                        /
        •      None                                                    I

        Standard technologies eliminated because of cleanup goals include:

        •      None          ..'-•••                            !

                                                   -           •          I"           ,  •   •
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        A small-scale treatability study was conducted by Canohie as a representative option for on-
        site solids washing/leaching at the Tonolli site. Canonic completed initial bench-scale
     •   treatability tests on the Tonolli site samples.  Analytical results indicate lhat the tailings
        material, plastic battery casings,  and  ebonite battery casing were all cleaned to pass TCLP.
        While the soil did not pass TCLP, an 80-percent reduction in total lead content was achieved.
        Based on the analytical and sieve analysis, Canonie feels that the +50 mesh fraction or .85
        percent of the soil and 90 percent of the tailings could be cleaned to jpass TCLP, and therefore,
        backfilled on site after treatment.
                                                                        i       *       .
        Chemfix conducted a treatability study on Tonolli waste as a representative option for on-site
        solidification/stabilization.  The goal  of the study was to formulate a lead treatment system that
        would reduce the leachability of lead in the waste submitted to levels bellow the regulatory
        standard of 5 ppm. Four treatment formulae were proposed and  applied to each waste to
        convert it into NaturfilR, a nonhazardous clay-like soil produced by the addition of Chemsetun
        reagents to the  industrial waste.  Chemical and physical analyses were performed to assess the
        effectiveness of each treatment.  All  the treatment formulae were successful.

        The University  of Pittsburgh  Center for Hazardous Materials Research (CHMR) and Exide
        Corporation, pursuant to EPA contract CR-818199-01-0 under the Emerging Technologies
        Program, are investigating the potential for using secondary lead smelters for the recovery of
        lead  from battery eases and other materials removed from Superfund sites.  The purpose of
        this investigation is to determine if these  materials, which typically contain lead in
        concentrations of 1 to 10 percent, can be processed  through existing secondary lead smelters in
        an ecpnomical fashion to reclaim usable lead. As part of this investigation, CHMR/Exide
        processed materials from the  Tonolli site in Nesquehoning, Pennsylvania, through Exide's
        Reading, Pennsylvania, facility. CHMR/Exide processed test materials from the Tonolli site in
        the reverberatory and blast furnaces at Exide's Reading smelter between September 9 and 13,
        1991.  One reverberatory furnace and one blast furnace were utilized to process the Tonolli
        material. A second reverberatory furnace  and blast furnace remained in normal routine
        operation, which allowed for  comparison  of the "test" furnaces with the "reference" furnaces.
        These tests showed that battery case  materials from  the site can be processed in the facility's
        blast furnaces with various modifications to the system. Battery case material from the site
        cannot  be processed without size reduction. Estimated processing costs on a unit rate basis


        ...              '     \             -8-
459

-------
         and estimated on Exide's method of operation were determined to be $0,15 per pound.  The
         projected volume of;
         cubic yards per day.
projected volume of site material that the Exide Reading facility could process is 30 to 45         VP  "\
  15.     What measures/criteria were used to compare alternatives?              .        i

         The following measures were used to compare the alternatives:                             -

               Risk level achieved                                                        ,
               Cost-effectiveness
               Proven reliability
               Preference for treatment (vs. containment)


  16.     How are measures compared?

         The site will be used for industrial purposes after the cleanup; therefore, the level of risk
         reduction achieved by the selected alternative was of critical concern. The modified remedy
         was chosen over the preferred alternative outlined in the Proposed Plan because it provides an
         equivalent level of protection and long-term effectiveness as the originally proposed remedy,
         but is more cost-effective. The combination of treatment and engineering controls proposed
         under the selected alternative effectively reduces  and eliminates the potential risks posed by
         the site in a cost-effective manner. Stabilization/solidification and smelting were selected
         because these technologies were easily available and reliable and proved effective in               J^fc->v
         treatability studies conducted during the completion of the FS. The selected remedy meets the      ^BP  J
         statutory requirement to utilize permanent solutions and treatment technologies to the                     '
         maximum extent possible. Treatment was selected to address the site materials and
         contaminated media posing the principal threats to human health and the environment. Four of
         the six categories of contaminated wastes or environmental media will be subject to treatment
         under this remedy.


  77.     What  technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?

         Technical considerations were not primary in selecting a chosen  remedy for the site.  In situ
         soil flushing was eliminated  because the flushing solution could  not be captured in the
         unsaturated soils and debris media, given the porous nature of the mine spoil and alluvium.


         References

         Barth, E.F. and R.P. Traver.  Treatment of Lead Battery  Contaminated Soil Utilizing Soil
         Washing and Solidification/Stabilization Technology; Proceedings of Hazardous Waste
         Treatment: Treatment of Contaminated Soils, Sponsored  by Air and Waste Management
         Association and U.S. EPA Risk Reduction Engineering Laboratory, February 1990, Cincinnati
         OH.                                                                                                '
460

-------
                                               • r               !
Coles E   Treatability Study Review of Soil Washing and Solvent Extraction Technologies far
Potential Applicability toTonolli Site; U.S. EPA Contract 68-C9-0033, Work Assignment OR-
008.                                                           !   ,

Lageman, R. et al.  Electroreclamation: State of the Art and Future Developments,
Proceedings of Hazardous Waste Treatment: Treatment of Contaminated Soils, Sponsored by
Air and Waste Management Association and U.S. EPA Risk Reduction Engineering
Laboratory, February 1990, Cincinnati, OH.                        r
                                                                                          461
                                        -10-

-------
                                Whitmoyer Laboratories
                                           OU-2

                              Jackson Township, Pennsylvania
                                         Region 3
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Vault Waste (rag/kg)

       Arsenic                     157,000
       Total organics                140,000
       (aniline, benzene, PCE, n-
       nitrosodiphenylamine)

       Lagoon Waste (mg/kg)

       Arsenic                     10,000
       Organics summed average     12
       (pentachlorophenol, bis(2-ethylhexyl)phthalate, n-n-nitrosodiphenylamine)
 10/84
,6/86
 2/90
 12/17/90
                                                                Background

                                                   EPA Fund-lead
                                                   PRPs:  Rhom & Haas and SmithKline
                                                          Beecham
                                                   FS prepared by:  Ebasco Services Inc.
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       «      4,500 cubic yards of vault waste
       •      24,000 cubic yards of lagoon waste


3.      What type of site is this?

       Pharmaceutical Manufacturing. An abandoned pharmaceutical manufacturing facility in a
       predominately agricultural and rural setting.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening'of technically feasible
       technologies were:
462
                                            -1-

-------
       Access restriction:
       Containment:
       Chemical treatment:
       Physical treatment:

       Thermal treatment:
                 •f
       Disposal:
  Fencing, deed restrictions
  Capping (clay, synthetic, RCRA), jet grouting, sluirry wall
  Fixation (stabilization, solidification), thermoplastic
  microencapsulation, macroencapsulation, clay pelletizing, reduction,
  neutralization
  Dewatering, sedimentation, detonation, solids processing (crushing,
  screening, magnetic separation)              j
  Incineration (rotary kiln, infrared, fluidized bed, circulating fluidized
  bed)             ,
  Excavation, recycle, salvage, on-site landfill, ojff-slte landfill
5.       Was an innovative technology considered in the FS?  If so, which technology?
    '  •                    '                         '                      '•'•'./
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:    Biodegradation (aerobic, anaerobic, in situ, ex situ)
        Chemical/physical:     In situ soil flushing, dechlorination, vapor extraction, other extraction
                              technologies such as BEST (Resources Conservation Co.), critical fluid
                              solvent extraction (CF Systems Corp.), EPA's mobile extraction system
        Thermal treatment:     Vitrification (in situ, ex situ), low-temperature thermal stripping (X*
                              TRAX system), radio frequency heating, pyrofysis (plasm arc, high
                              temperature fluid wall), wet air oxidation
        What was the cost estimate for the innovative technology?
                                                                            . '  •,
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. Typically after the RAAs
        have been formulated, costs are estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, the estimated costs were calculated during an evaluation based On
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
        Vault waste
            Alternative
          RAA-5
        Innovative Technology
Excavation/mix with other site wastes/
vitrification/disposal of treated waste on
site or off site in RCRA landfill
                                               -2-
                                                                         Estimated Costs
3 Criteria
   N/A
 9 Criteria
$38,800,000
     to
$58,000,000
                                                                       463

-------
       Lagoon waste
Alternative
RAA-5
Innovative Technology
Excavation/in situ vitrification/disposal
of treated waste in off-site landfill or
cap ,
Estimated Costs
' 3 Criteria
- N/A
9 Criteria
$16,400,000
to
$24,200,000
7.     How did the cost(s) compare to standard technologies?
       Vault waste
                 Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-6a
RAA-7"
Selected
remedy
Standard Technology
No action/ground water monitoring
Deed restrictions/excavation/disposal on
site in RCRA landfill/ground water
monitoring
Excavation/microencapsulation of upper
vault waste/fixation of lower vault,
waste/treated waste disposed on site or
off site in RCRA landfill
Excavation/incineration/fixation of
ash/disposal of fixed material on site or
off site in RCRA landfill
Excavation/disposal in on-site RCRA
landfill/long-term maintenance/deed
restrictions
Excavation/disposal off site-in RCRA
landfill
Excavation/cement fixation of upper
vault waste/incineration followed by
fixation of lower vault waste/treated
waste disposal in off-site hazardous
waste facility
Estimated Costs
3 Criteria
N/A
- N/A ."
N/A
N.A
N/A
N/A
•N/A
9 Criteria
$109,000
$1,379,000
$11,300,000
-to
$15,900,000
$15,630,000
to
$20,500,000
N/Aa •
N/Aa
$18,400,000
      a RAA-6 and RAA-7 were proposed by the former site owners and only are presented in the
      ROD.  No costs were estimated for these alternatives.
464
                                          -3-

-------
Lagoon waste
Alternative
RAA-1
RAA-2

RAA-3



RAA-4




RAA-6

-------
        Lagoon Waste:                                              ,

                                       •      '•                '         :  '           ''•
        The selected alternative was preferred because fixation treatment will eliminate and
        permanently immobilize site contaminants.  While alternatives RAA-4 and RAA-5 were
        considered more protective since they addressed organics, they were not chosen and no
        explanation is given. Other alternatives that proposed containment were not chosen because
        they would not  ensure long-term protection.  The selected alternative also was considered more
        protective because treated waste will be disposed off site. The potential of landfill failure from
        sink hole formation  was a concern because ground water could be contaminated.  Moreover,   '•
        Pennsylvania law prohibits a hazardous waste landfill immediately above carbonated bedrock.'


9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.


10.     If an innovative technology was not chosen,  why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated  from the remedial technology selection process  at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or  during the detailed evaluation;
                                                             "
                                                                                                          . ^

       Vault/Lagoon Waste:                                                                 ,

        •      In situ and ex situ biodegradation was eliminated because it was not  applicable to site
              contaminants. Effective treatment of site contaminants would require both aerobic and
              anaerobic techniques. Further, the breakdown  of some halogenated aliphatics would
              result in  vinyl chloride,  a toxic intermediate. Most important, the process might be
              inhibited by the  presence of arsenic,  which could not easily be removed from the
              waste and would not be addressed by biodegradation.                                            '
       •      Dechlorination was eliminated because it was not applicable to site contaminants.
       «      In situ radio frequency heating was eliminated because it is not "independently"
              applicable for the primary site contaminants.
       "      In situ vapor extraction  was eliminated because it was not "independently" applicable
              for the primary site contaminants.
       •      In situ soil flushing was eliminated because it was not applicable to site conditions of
              highly fractured  bedrock and the process is not "independently" applicable for the
              primary site contaminants.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       Vault Waste:

       •      Extraction technologies (solvent) were eliminated because they would not achieve
              remediation goals and would not be reliable with the site's contaminants. Further,
              since contaminants are already highly concentrated, attempts to concentrate further the '

  466
                                             -5-   '                            :

-------
              waste would not significantly reduce the waste volume.  In addition, it is unlikely that
              arsenic can be effectively separated from organic contaminants sinc« it is suspected
              that a significant amount of arsenic is present in its organic form.
      •      Wet air oxidation was eliminated because there was concern that the numerous
              components in the vault waste (steel fragments, paper, carbon, sludge, tar, and
              solvents) would hamper the waste from being shirried and therefore severely limit the
              effectiveness of this option.  Volatilized arsenic would be a health hazard, very few
              vendors perform this work, and the concentrations of organics lire Mgher than those
              typically considered feasible for oxidation.
      •      Low temperature thermal stripping was eliminated because it v/as laot expected to
              achieve the remediation goals.  Because of the low temperature employed, many site
              organics would not be volatilized and arsenic would not be changed into a form that is
              amenable to fixation.                                        >.
      •      In situ vitrification was  eliminated because the sodium and organic content  of the
              vaults limits its applicability. The sodium content reduces the electrical resistance of
              the waste thereby limiting the temperature that can be achieved.  The organic content
              could severely limit the rate of waste treatment because of air pollution  concerns.
                                                                        ••.
      Lagoon Waste:

       •      Extraction  technologies were eliminated because of their limited effectiveness in
              achieving remediation goals. Since arsenic is already present in substantial
              concentrations in the waste, little benefit would be gained froni attempts to concentrate
              waste.                                 •.••;•>
       •      Wet air oxidation was eliminated because the low organic concentration of the waste
              severely limits its effectiveness. The iron and arsenic also might interfere with the
              oxidation process.
       •      Low-temperature thermal stripping was eliminated because it Would be  ineffective with
              site contaminants. Most site organics are nonvolatile at the low temperatures
              employed by this process.  Further, arsenic would not be chanjged into a form that is
              amenable to fixation.                                       I

       Innovative technologies eliminated during the detailed analysis include| the following:

       Vault Waste:

       •       Vitrification was eliminated but no specific reason was given.
                                             "'.'•.       •           I     .             .:'
       Lagoon Waste:

       •       In situ vitrification was eliminated but no specific reason  was 'given.
                                                                         i
             -            '              "         -           '         .•'!'''••'•-
11.     Which of the nine  criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion? Which of the criteria supported the use of a standard technology?

       Vault Waste:
                                          i                     •         i, •           .

       The most heavily weighted criteria in the choice of a standard remedial technology for vault
        waste was the protection of human health and the environment through the permanent
                                               -6-
46'

-------
        reduction of site contaminants via treatment.  The selected alternative was preferred because it
        reduced organics in the upper vault and immobilized the arsenic in the upper and lower vaults
        through treatment. Alternatives that proposed landfilling were not considered as protective
        because they did not treat contaminants.  Further, alternatives that proposed on-site landfilling
        would not be protective due to  the potential for landfill failure, which would  result in ground
        water contamination.  Alternatives RAA-4 and RAA-5 were considered slightly more
        protective than the selected alternative and slightly more effective in the long term since they
        treated  organics in both the upper and lower vaults.  No reason was given for the preference  -
        for the  selected alternative above these two.

        No innovative technologies were eliminated due to the nine criteria.

        Lagoon Waste:

        The most heavily weighted criteria in the choice of a.standard remedial technology for lagoon
        waste was the protection of human health and the environment through the permanent
        reduction of site contaminants via treatment.  This treatment would also ensure that the remedy
        would be permanent and effective in the long term.   Other options were considered less
        protective because they did not treat contaminants. Moreover, the option to landfill on site
        was not chosen because of the potential for landfill failure due to sink holes and the associated
        contamination of ground water.  Treatment was preferred over containment because of future
        maintenance needs.  Finally,  several alternatives would not comply with ARARs since
        Pennsylvania law does not allow construction of a hazardous waste landfill above carbonate
        bedrock, and RCRA land disposal restriction standards do not allow the off-site disposal of
        waste expected to have TCLP and EP Toxicity leachate  concentrations above 5 mg/1 arsenic.

        No innovative technologies were eliminated due to the nine criteria.
12.
 What cleanup goals,were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?

Chemical specific cleanup goals were not provided. Cleanup is based on RCRA, CAA  CWA
and State .standards.                                                              '
13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

«       Extraction technologies were not expected to meet remediation goals.
•       Low temperature thermal stripping was eliminated for lagoon wastes because it was
        not expected to meet remediation goals.

Standard technologies eliminated because of cleanup goals include:

«       On-site landfill would not be in compliance with Pennsylvania hazardous waste facility
        criteria in Title 25, which prohibit the construction of a hazardous waste landfill over
        limestone or carbonate formations.
  468
                                             -7-

-------
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Vault Waste:  Treatability studies were conducted for cement/lime-based fixation and
        incineration technologies.  These studies examined the effectiveness of these technologies on
        lower vault waste. Cement/lime-based fixation was shown to reduce the arsenic teachability of
        the waste to below RCRA land disposal requirements.  Incineration followed by cementAime-
        based fixation was found to destroy all the organics and reduce arsenic mobility within levels
        necessary to comply with RCRA hazardous waste regulations. A treatability study was also
        carried out to test the  effectiveness of clay pelletizing/sintering and results showed that this
        technique was not applicable to site contaminants.                   |          •.•'.",
                                 '  .         _        '                 /       '
        Lagoon Waste:  A treatability study was conducted to study the effectiveness of incineration
        followed by cement/lime-based fixation methods on lagoon waste.  According to study results,
        these technologies would reduce arsenic mobility to comply with land disposal restrictions.


 75.     What measures/criteria were used to compare alternatives?

        The following measures were  used to compare the alternatives:

        Vault Waste:                              ,

              Proven reliability     ••,,.'

        Lagoon Waste:

              Proven reliability
              Preference for treatment (vs. containment)

                           '                                              '
  16.    How are measures compared?

        Vault Waste: Treatability  studies  were conducted to test the effectiveness of fixation and
        incineration of site media and contaminants. Also, microencapsulation (RAA-3) was
        considered less reliable than other technologies since there is limited; date concerning its
         effectiveness for immobilizing arsenic and organics.

         Lagoon Waste: Treatability studies were conducted to test the reliability of fixation of site
         sludge.  Also treatment was preferred over containment as it was considered a more permanent
         and long-term solution because site contaminants  would be permanently reduced and no long-
         term maintenance would be required.

                                                                         !   '  '
  •                                              .              .!'•'
  17.     What technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?

         The site geology was primary in selecting a remedial alternative. The site is underlain by
         carbonate (limestone) bedrock and studies by the Pennsylvania Topographic and Geologic
         Survey have shown that the limestone  can be dissolved by infiltratirijg rain water and ground
         water. Over time, this could destabilize  the overlying rock and soil pausing them to cave in
''
                                                                                                  469

-------
         (sinkhole collapse). Therefore, on-site landfllling was not preferred because of the potential

         for landfill failure due to sinkhole formation.                -                                  ~     \

                                                                         '         i               '          .if
                                                                                                         >
471
                                             -9-

-------
                               Whitmoyer Laboratories
                                          OU-3

                              Jackson Township, Pennsylvania
                                         Region 3
GENERAL SITE INFORMATION

1.    "  What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Arsenic                     28,200
       Aniline                     72
       n-Nitrospdiphenylamine      170
       Tetrachloroethene           14
       Trichloroethene             0.87
       1,2-Dichloroethene           0.84
       Benzene                 ,   0.85
       Pyrene                     25
       Benzo(a)pyrene             74
       Benzo(b)fluoranthene       84
       Indeno(l,2,3-cd)pyrene      75
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      116,000 cubic yards of soil
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
10/84
6/86
2/90
12/17/90
             Background

EPA Fund-lead    !
PRPs:  Rhom & Haias zind SmithKline
       Beecham   |
FS prepared by: Ebasco Services Inc.
 3.     What type of site is this?  '  '    \

        Pharmaceuticals. An abandoned pharmaceutical manufacturing facility in a predominately
        agricultural and rural setting.
  TECHNOLOGY SELECTION

  4.      What standard technologies were considered for selection in this FS?\

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
                                              -1-
                                                                                            471

-------
472
          Access restriction:
          Containment:
          Chemical treatment:
          Physical treatment:
          Thermal treatment:
          Disposal:
      Fencing, deed restrictions
      Capping (semipermeable, clay, bentonite, cement, asphalt, synthetic
      membranes, slurry wall, concrete walls, erosion control, clay
      pelletizing/sintering
      Fixation, microencapsulation, macroencapsulation, neutralization
      Dewater, sedimentation, detonation, solids processing      -
      Incineration
      Bulk excavation, discrete removal, dredging, landfilling (hazardous,
      non-hazardous), recycling, consolidation
  5.      Was an innovative technology considered in the FS?  If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were: •                                    .                • •  •*

          Biological treatment:  Biodegradation (aerobic, anaerobic, in situ, ex situ)
          Phys/Chem treatment: Oxidation, reduction, dechlorination, in  situ soil flushing, ex situ
                               solvent extraction, wet air extraction,  in situ vapor extraction
          Thermal treatment:    Pyrolysis, low-temperature thermal stripping, vitrification (in, situ, ex
                               situ), in situ radio frequency heating                          -


  6.       What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs. Typically, after the RAAs
         have been formulated, costs are estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify  alternatives that merit a more detailed
         evaluation. In this case, no three-criteria evaluation was conducted of RAAs and the estimated
         costs were calculated during an evaluation based on nine criteria established by the NCP.

                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
            Alternative
          RAA-6
        Innovative Technology
Bulk excavation/fixation of soil con-
taining contaminants in excess of
"principal threat'Ybiodegradatiqn of
soil with organic contaminants in
excess of "principal threat" cleanup
levels/consolidate soil containing con-
taminants in excess of unsaturated
soil cleanup levels in vadose zone/
treated soil disposed at off-site
intermediate landfill
                                                                         Estimated Costs
                                                                     3 Criteria
                                                                        N/A
 9 Criteria
$25,000,000
                                               -2-

-------
Alternative
RAA-8
RAA-9"
Innovative Technology
In situ vitrification of soil with
"principal threat'Vconsplidate and imper-
meable cap on soil with 450 to 1000
mg/kg arsenic/consolidate in vadose
zone soil with 210 to 450 arsenic/soil
cap on any remaining arsenic-
contaminated soil
Soil flushing/three-year pilot study
Estimated Costs
3 Criteria
N/A
' ' 1
N/A
9 Criteria
$44,000,000
N/A .
       This alternative was developed by the former site owners and was first presented in the
       Proposed Plan.
7.      How did the cost(s) compare to standard technologies?
                Cost Estimates for RAAs That Include Standard Technologies
                      ,    (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4A

Standard Technology
No action
Soil Capping
Excavate soil in excess of ground
water-based cleanup levels/consolidate
into vadose zone on site/clay cap/soil
cap over remaining soil with arsenic in
excess of 21 mg/kg
Bulk excavation/soil containing con-
taminants exceeding "principal threat"
disposed off site/soil with concentra-
tions greater than ground water-based
unsaturated soil cleanup levels placed in
intermediate landfill/remaining con-
taminated soil taken off site to
nbnhazardous landfill
Estimated Costs
3 C'riteria
N/A
N/A
N/A
N.A
9 Criteria
$56,000
$4,450,000
$8,300,000
$80,000,000
                                             -3-
                                                                                           473

-------
              Alternative
            RAA-4B
            RAA-4C
           RAA-5
         Standard Technology
 Bulk excavation/soil containing con-
 taminants exceeding "principal threat"
 disposed off site/soil with concentra-
 tions greater than ground water-based
 unsaturated soil cleanup levels placed in
 intermediate landfill/remaining soil
 exceeding ground water-based saturated
 cleanup levels relocated to vadose zone/
 soil remaining with greater than 21
 mg/kg covered with soil cap  .
 Bulk excavation/soil containing con-
 taminants exceeding "principal threat"
 disposed off site/soil with concentra-
 tions greater than ground water-based
 unsaturated soil cleanup levels placed in
 vadose zone with impermeable cap/soil
 in excess of saturated soil cleanup
 levels consolidated to vadose zone
Bulk excavation/soil containing con-
taminants exceeding "principal threat"
fixed and disposed off site/soil with
concentrations greater than unsaturated
soil-based soil cleanup levels con-
solidated in vadose zone and capped
           RAA-7          Bulk excavation/incineration of soil
                            with contaminants exceeding "principal
                            threat" cleanup levels/fixation of soil
                            with arsenic concentrations greater than
                            1,000 mg/kg/consolidation and imper-
                            meable cap for soil with arsenic concen-
                            trations of 210 to 1,000 mg/kg/soil
                            cover over surface soil in excess of 21
                            mg/kg arsenic
 8,      If a standard technology was chosen, why?

         Capping, a standard technology was chosen (see below).
                                                                           Estimated Costs
                                                                       3 Criteria
                                                                          N/A
                                                                         N/A
                                                                         N/A
                                             N/A
  9 Criteria
 $39,000,000
 $33,000,000
$27,000,000
$32,000,000
 9.     If an innovative technology was chosen, why?
474
        RAA-6 was chosen because it reduces site risk by immobilizing arsenic in the heavily
        contaminated soils with iron fixation and it eliminates organics through bioremediatiori.
        Though metals will not be destroyed, the long-term risk will be reduced since the treated soil
                                               -4-

-------
       will be disposed of in an off-site landfill, thereby permanently removing them from the site.
       Moderately contaminated soil will be consolidated and capped with an impermeable cap,
       which will reduce the mobility of contaminants.  A soil cover will be placed over site soils
       with low levels of arsenic.  Deed restrictions also will help prohibit access to the soil. This
       alternative minimizes short-term risk since heating is not involved. The technologies proposed
       in the alternative are proved, treatability studies showed that fixation irnmobilizes arsenic in
       the soil and allows biodegradation to occur.  Remediation  equipment is readily available.
       RAA-6 will attain all ARARs and is cost-effective.
                  "                                         '             !         •

10.     If an innovative technology was not chosen,  why not? At what stage was the innovative
       technology eliminated?                                      '

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial  screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial  screening include |the following:     ,

        •      Dechiorination was eliminated because the process would not be applicable to the
               primary site contaminants.
        •      Clay pelletizing/sintering was eliminated because  the process would not be applicable
               to the site's primary contaminants.                          I
        •      Anaerobic ex situ biodegradation was eliminated  because the process would not  be
               applicable to the site's primary contaminants.
        • !     In situ radio frequency heating was eliminated because the process would not be
               independently applicable to the site's primary contaminants and in situ treatment
               typically involves only one process  option.
        •      In situ vapor extraction was eliminated  because the process would not be
               independently applicable to the site's primary contaminants and in situ treatment
               typically involves only one process  option.
        •     In situ biodegradation was eliminated because the process would not be independently
               applicable to the site's primary contaminants and in situ treatment typically involves
               only one process option.

        Innovative technologies eliminated during the screening, of the  three criteria include the
        following:
                                                                    •     i                  .
        •     Ex situ solvent extraction was eliminated because a treatability study showed that its
               effectiveness would be uncertain and require long contact time, which would make
               subsequent dewatering very difficult.                          ,     .
        '•      Wet air oxidation was eliminated because effectiveness might be limited by the  site's
               low concentrations of  organics.  Iron and arsenic also might interfere with the process.
        •      Oxidation was eliminated because treatability studies showed piat the process would
              - not meet remedial objectives.
        •     Reduction was eliminated because it would  not be effective for treating the organics at
                the site.  While it could be a component of soil washing, treatabillity studies showed
                that the process would not meet remedial objectives,
        •      Pyrolysis was eliminated because it could produce arsine, a more mobile: and toxic
                form of arsenic.  Arsine, a noncondensable  gas, could lead to a significant discharge of
                arsenic to the atmosphere and pose risks to human health and the environment.  If

                                                                                                 475
          .'.•..       •                 -5-                •      j.  '

-------
                  treatment occurs off site, transportation and treatment permits would be required.
                  Also, there is limited availability of equipment for on-site pyrolysis
          •      Low temperature thermal stripping was eliminated because a previous EPA study
                  (1988) showed that the low temperatures would not be high enough to remove PAHs
                  that have higher boiling points.
          "      In situ soil flushing was eliminated because the treatability study showed that its
                  effectiveness would be uncertain due to the limited availability of appropriate lixiviants
                  to mobilize arsenic.   Further the heterogeneity of the soils and the fractured bedrock
                  could make it difficult to capture the lixiviant and result in mobilization of the
                  contaminants.
          •      In situ vitrification was eliminated because arsenic could volatilize, treatment
                  equipment and skilled workers would be available but limited, and it is costly.
          «     Aerobic ex situ biodegradation was eliminated as a single-treatment technology
                 because it would not address arsenic.  It was retained, however, for consideration in a
                 treatment train.

          Innovative technologies eliminated during the detailed analysis include the following:

          «      In situ soil flushing was reintroduced as a technology by the  former site owners in the
                 proposed plan. It was not chosen because it would require 3 years of testing prior to
                 implementation, and it would leave contaminants on site that could contaminate ground
                 water in excess of MCLs.  These also was concern that it would be difficult to capture
                 the flushing solution and that it would  take a very  long time (10,000 to 24 000 years)
                 to reach cleanup  levels.
          •       In situ vitrification was eliminated because it would pose short-term risk, would be
                 more costly than  the chosen alternative, and there might be limited availability of
                 skilled workers and treatment equipment.


  11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         ^  meet  one  of the nine criteria result in the elimination of the innovative technology?  If so
         which criterion?  Which of the criteria supported the use of a standard technology?        '

         The criteria that were most heavily weighted in  selecting a remedial alternative were long-term
         effectiveness, short-term effectiveness, and cost.  The chosen alternative provides long-term
         effectiveness since it treats and thereby permanently eliminates organics through
         biodegradation and immobilizes metals through fixation. Cost-effectiveness was  a factor since
         both RAA-2 and RAA-3 were  eliminated, even though they were less costly,  because they did
         not provide permanent treatment and would not be as effective protecting human health and
         the environment in the long-term. Alternatives  RAA-4A, RAA-4B, RAA-4C, and RAA-5
         were eliminated because they would be more costly.  RAA-7 (incineration) and RAA-8 (in situ
         vitrification) were eliminated because they were more expensive and they posed short-term risk
         due to the release of volatile organics during heating.
                           Wer£ selected? V the cl™™P goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?

        Cleanup levels were derived for surface soils based on direct exposures.  Other soils (saturated
        unsaturated (vadose.zone), and principal threat soils) were thought to threaten ground water   '
        quality, and therefore cleanup levels were developed
476

-------
Surface Soil
Contaminant
Cleanup Level (rag/kg)
ARAB: or Other Basis
Carcinogens
Arsenic ,
Benzene
Trichloroethene
Tetrachloroethene >
Benzo(a)pyrene
Benzo(b)fiuoranthene
Nitrosodiphenylamine
Aniline
Indeno( 1 ,2,3-cd)pyrene
21
14
38
8.2 .
0.13
0.93
85
73
0.56
Bisk8,
Ilisk
Risk
Risk
Risk
Risk
msk
Risk
Risk
Noncarcinozens
Pyrene
Trans- 1,2-
dichloroethene
1.6
1,000
Risk
Risk
  .  l          .                   •         ..               I •    •             ,
 "Risk-based cleanup levels correspond to an excess lifetime czincer risk of 1 x 10"
 posed by the surface soils following remediation under the residential use scenario.
 For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.


 Saturated Soil                                           !       .
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Benzene
Trichloroethene
Tetrachloroethene
Benzo(a)pyrene
Benzo(b)fluoranthene
Nitrosodiphenylamine
Aniline
Indeno(l ,2,3Tcd)pyrene
210
0.002
0.004
0,012
0.104(0.66)"
0.25 (0.66)
0.02 (0.66)
0.002(0.66)
0.52(0.66)
Ground water2
Ground water
Ground water
(Ground water
Ground water
Ground water
Ground water
Ground water
Ground water
                                  -7-
477

-------
478
                      Contaminant
 Cleanup Level (rag/kg)
                                                                  ARAR or Other Basis
                 Noncarcinogens
                 Pyrene
                 Trans-1,2-
                 dichloroethene
      0.033 (0.66)
         0.037
                                                                      Ground water
                             Ground water
                'Soil cleanup levels correspond to concentrations that would not cause ground water to
                exceed MCLs, or 10* excess cancer risk if MCLs do not exist.
                "Numbers presented parenthetically  represent the practical detection limit.

                Unsaturated (vadose zone) Soil
                      Contaminant
Cleanup Level (mg/kg)   ARAR or Other Basis
                 Carcinogens
                                                                     Ground water2
                                                                     Ground water
                 Tnchloroethene
                                                                     Ground water
                 Tetrachloroethene
                                                                     Ground water
                Benzo(a)pyrene
                                                                     Ground water
                Benzo(b)fluoranthene
                                                                     Ground water
                Nitrosodiphenylamine
                                                                     Ground water
                                              0.009 (0.66)
                            Ground water
                Indeno(l ,2,3-cd)pyrene
                            Ground water
                Noncarcinogens
                                                                     Ground water
                Trans-1,2-
                dichloroethene
                            Ground water
                                                               )
              •Soil cleanup levels correspond to concentrations that would not cause ground water to
              exceed MCLs, or 10'6 excess cancer risk if MCLs do not exist.
              "Numbers presented parenthetically represent the practical detection limit.

              Principal Threat (heavily contaminated) Soil
                                        Cleanup Level (mg/kg)   ARAR or Other Basis
                                            -8-

-------
13.
 14.
                                                                ARAR IDF Other
                               Cleanup Level (ing/kg)
                   Contaminant
              Trichloroethene
              Tetrachloroethene
               Benzo(a)pyrene
               Benzo(b)fluoranthene
               Nitrosodiphenylamine
               Indeno(l ,2,3-cd)pyrene
               Noncarcinogens
               Trans-1,2-
               dichloroethene
      -Cleanup levels are based on leachate .concentrations , exceeding -RCRAtoxicity
       characteristic levels, if available, or 100 time the W excess ciancer nsk in ground
       water.  Cleanup levels followed by an asterisk (*) were derived using TCLP
       methodology. All others were based on equilibrium partitioning using Koc and TOC.

                                                                I '        *
Was ^innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?       ,-'                       j

Innovative technologies eliminated because of cleanup goals include:

•      Soil flushing                          ,

Standard technologies eliminated because of cleanup goals include:   !

                                         •          -.-"..'
 •      Capping                              •-,'...-


 Were.treatability studies conducted on the innovative technology or standard technology?

 Treatabilitv studies were conducted to assess the effectiveness of several technologies
 SSS^oning. chemical  oxidation, and fixation.  According |to the results ehem«d.
 oxidation and 3oil washing would not be appropriate technologies ^^^
 studies also showed that iron fixation immobilized the arsenic in the soil and allowed
 biodegradation to take place.
  75.     What measures/criteria were used to compare alternatives?

         The following measures were used p compare the alternatives:

                                                -9-
                                                                                          479

-------
                  Cost                                      ,
                  Time to design/construct/operate
                  Proven reliability
                  Single versus multistep treatment
                  Preference for treatment (vs. containment)


   16.    How are measures compared?

          The chosen alternative was considered protective and effective in the long term because it
          treats site contaminants.  Treatment was preferred over containment because it is more
          effective in the long term and the potential for sink holes or erosion in not as great  Of the
          treatment alternatives, the chosen alternative is the least expensive.  A rnultistep treatment was
          preferred because it better addresses the mixture of site contaminants.  In fact, biodegradation
          was eliminated as a process to be used in isolation but was retained for consideration in a
          treatment tram.  Proven reliability and time to implement also were considered  The chosen
          technologies, fixation and biodegradation, were preferred because they had proved to be
          applicable in treatability testing. Conversely, soil flushing was eliminated because  it would
          require extensive testing and would take too long to reach cleanup levels.


   17.     What technical considerations were factors in selecting a remedy? Were technical
          considerations primary in the selection of the remedy?

          The heterogeneity of the soil precluded the use of soil flushing.  This consideration, however
          was not primary in selecting a remedial technology.                                       '      ^"^   "Y

          Reference:                                                             ,           '
                  r                                            of Surrogate Soils—Bench-Scale
         Tests, PEI and IT Corp., Contract No. 68-03-3389.
4SO
                                               -10-

-------
                                  Agricb Chemical Co.
                                          OU-1

                                     Pensacola, Florida
                                         Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       SoiUSludge (mg/kg)
2.
       Lead
       Fluoride
       Arsenic
              46,000
              510,000
              58
What volume of material is to be
remediated?

The volume of material to be remediated
included:

•      420,800 cubic yards of soil
»      32,500 cubic yards of sludge
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                     N/A
                     10/4/89
                     4/30/92
                     9/29/92
             Background
                 i'          '
PRP-lead
PRPs:   Conoco Incorporated, Freeport
       McMoRan Inc.
FS prepared by: Gcraghty & Miller,
       Inc.
 3.      What type of site, is this?

        Agricultural Chemicals. A former sulfuric acid and fertilizer production plant. The site is
        bordered by industrial and residential areas.
 TECHNOLOGY SELECTION       '                                      -       ,
             ••• "  '•' '                                       :          "•!'''

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification arid screening of technically feasible
        technologies were:

        Access restriction:     Fencing, deed restrictions
        Containment:         Capping (soil, synthetic, multimedia), slurry wall, high-density
                             polyethylene barrier, clay wall, sheet pile surface water diversion,
                             grading, berms, channels
        Chemical treatment:   Solidification/stabilization


           .            .•                      -1-             "•'  '   •
                                                                                      481

-------
        Thermal treatment:
        Disposal:
     Thermal treatment (not specified)
     Excavation, on-site disposal in RCRA vault, off-site disposal at RCRA
     facility
 5,      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Biodegradation
        Chemical treatment:    Soil washing


 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implernentability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, estimated costs were calculated during an evaluation based on nine
        criteria established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
           Alternative
         RAA-8
         RAA-9
        Innovative Technology
Clay cap/soil washing/institutional
controls
RCRA vault/soil washing/institutional
controls
                                                                       Estimated Costs
                                                                   3 Criteria
                                                                     N/A
                                                                     N/A
 9 Criteria
$28,488,000
 eliminated
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected  remedial alternative is in bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action/deed restrictions
Limited action/deed restrictions/access
restrictions
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
eliminated
$274,000
432
                                             -2-

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-10
RAA-11
Standard Technology
Clay cap/stabilization/institutional
controls
RCRA cap/slurry wall/stabilization/
institutional controls
RCRA vault/stabilization/institutional
controls
Soil cover/stabilization/institutional
controls
Clay cap/slurry wall/stabilization/
institutional controls
Clay cap/off-site disposal/institutional
controls -
Stabilization/off-site disposal/
institutional controls
Estimated Costs
3 Criteria
•N)A
i
N|A
; N/A
1
N^A "
I
Nl/A
N/A
N/A
i '
9 Criteria
eliminated
$10,730,000
eliminated
eliminated
$10,510,000
$39,946,000
eliminated
8.      If a standard technology-was chosen, why?                          \

       RAA-4 was chosen because it reduces site risks to acceptable levels. .It provides acceptable
       levels of overall protection through extraction and treatment of contaminated soil/sludge, it
       prevents dermal contact with and ingestion of contaminated soil/sludge, and minimizes
       infiltration of surface water and the resulting generation of leachate. Institutional controls
       implemented with this alternative further reduce exposure to on-site contaminants. This
       alternative minimizes short-term risk.  The alternative meets,the statutory preference for
       treatment through stabilization of contaminants. Stabilization in conjulnction with institutional
       controls provides a permanent solution by reducing the mobility of site contaminants. The
       RCRA cap proposed in this alternative was  preferred to the clay cap proposed in others
       because it offers a greater degree of protection. Implementation of this alternative achieves
       ARARs!  The chosen remedy employs a proven technology which can be easily implemented
       at the site.  This technology provides the most cost-effective treatment when compared to the
       other alternatives because of its ability to treat most effectively and limit further spread of
       contamination.  The chosen remedy represents the maximum extent to which permanent
       solutions and treatment technologies can be utilized in a cost-effective? mzinner for contaminant
       treatment at the site.
9.      If an innovative technology was chosen, why?

        An innovative technology was not selected.
                                               -3-
                                                                                                483

-------
  10,
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?

  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages:  during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  «      Biodegradation was eliminated because it would not be an effective technology for
         inorganic compounds which make up the majority of site contaminants.

  Innovative technologies eliminated during the screening  of the three criteria include the
  following:

  *      None

  Innovative technologies eliminated during the detailed analysis include the following:

  •      Soil washing was eliminated because it would pose short-term risk to the community
         from excavation and to site workers because of required soil handling.  This increased
         short-term risk reduced its  overall protectiveness as compared to the chosen alternative
         It would be more difficult to implement than the chosen alternative because it poses
         additional logistics problems.  Implementation of this technology would require
         adherence to strict operational procedures and a stringent monitoring and health safety
         plan to protect the community during remediation activities.  It is an emerging
         technology that has not been  put to wide-spread commercial use and therefore would
         require treatability studies.
                                                                                                    m
 n.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so
 which criterion? Which of the criteria supported the use of a standard technology?

 Long-term effectiveness, short-term effectiveness, and implementability were the criteria most
 heavily weighted in selecting a remedial alternative.  Other alternates (RAA-8 and RAA-10)
 which offered greater long-term protection were eliminated because the short-term risk they '
 would pose would reduce their overall protectiveness.  RAA-4 was preferred over RAA-7
 because it would offer greater long-term effectiveness since it proposed a RCRA cap instead of
a clay cap.                                                                         ,

One innovative technology, soil washing (RAA-8), was eliminated because it would pose
short-term nsk during excavation and treatment in excess of that posed by the chosen
alternative. It also would pose more implementation difficulties than the chosen alternative
484
                                              -4-

-------
12.
 13.
      What cleanup goals were selected?  I/the cleanup goal was based on an ARAR, what was that
      ARAR? What risk level was selected to establish cleanup goals?      |
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Lead
Arsenic
_ 500
16
UBKa
Risk"
Noncarcinogens
Fluoride
1,463 -
Model0
              The lead cleanup goal was determined by the lead uptake/biokinetic model (UBK),
              which predicts the concentration that would result in 95 percent of the hypothetical
              future child residential population having a blood lead concentration less than the
              Agency benchmark of 10 ug/dL.
              This cleanup level is based on an industrial scenario at the 1C]"6 risk level based on
              ingestion and inhalation pathways.   '
              This cleanup level is based on protection of ground water andl was determined by the
              Summers Model.
       Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None
14,     Were treatability studies conducted on the innovative technology or standard technology?

       A treatability study was conducted to investigate the effectiveness of isolidification/stabilization
       for treatment of the contaminated site soil and sludge.
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Total cost
               Proven reliability
               Impact on nearby populations
                                              -5-
                                                                                               485

-------
   16,     How are measures compared?

          The chosen alternative was preferred because it offers comparable overall protection to other
          alternatives with less short-term risk to the community. If fact, other alternatives that would
          offer greater long-term protectiveness were deemed to have less overall protectiveness.because
          they would pose short-term risk to the community. The chosen alternative had the lowest
          present worth cosi The chosen alternative was preferred because  it utilizes a proven
          technology that can be easily implemented without further development, while soil washing
          (RAA-8), an innovative technology, has not been put to widespread commercial use arid might
          require treatability studies.
   17.
What technical considerations were factors in selecting a remedy?  Were .technical
considerations primary in the selection of the remedy?

No technical considerations were primary in selecting a remedial alternative.
486
                                                -6-

-------
                     Alabama Army Ammunition Plant (AAAP)
                               OU-1, Soil Stockpile Area

                                 Talladega County, Alabama
                                          Region 4
GENERAL SITE INFORMATION

7.     What were the principal contaminants,
     - contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
       Soil(mg/kg)

       2,4,6rTrinitrotoluene
       2,4-pinitrotoluene
       2,6-Dinitrotoluene
       2,4,6-tirinitrophenyl-
         methylnitramine
       Lead
       Asbestos
6.06 ug/g
1.18 ug/g
0.68 ug/g

6.94 ug/g
185,000
<1 percent
chrysotile
                             Site History
                 NPLProposed:
                 NPL Final:
                ..FS:,- •  •••  "•-
                 ROD:
                     1984
                     1987
                     10/25/91
                     12/31/91
             Background

Federal Facility            ,
PRPs:  U.S. Army ICorps of Engineers
FS prepared by: .Mfesfoh Services, Inc.
       What volume of material is to be remediated?

       The volume of material to be remediated included:                "
                                          .                           I:

       •      24,300 to 25,650 cubic yards of soil
       •      1,350 to 2,700 cubic yards of asbestos containing material (ACM)
       What type of site is this?

       Chemicals and Allied Products., The site was used to manufacture explosives and chemicals.
       The site is presently in an inactive caretaker status with controlled access. Surrounding, land
       use is a mixture of recreational and industrial.
TECHNOLOGY SELECTION                .      .   .

4.      What standard technologies were considered for selection in this FS?
 •    •              '                 ,              '            '      i
       Standard technologies considered .during the identification and screening of technically feasible
       technologies were:                            •
                                            -1-
                                                          487

-------
         Soil

         Access restriction:     Fencing, access restriction signs
         Containment:          Cap
         Phys/Chem treatment:  Stabilization (cement, lime-based or pozzolanic, thermosetting organic
                               polymer)
         Thermal treatment:    Incineration (rotary kiln, infrared, fluidized bed, circulating bed), high
                               temperature electrically powered pyrolytic reactor (advanced electric-x
                               reactor, electric pyrolyzer)

         Asbestos Containing Material

         Disposal:             On-site disposal, off-site disposal
 5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Chemical treatment:    Critical fluid solvent
         Thermal treatment:     Molten salt destruction
         What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability,  and cost) to identify alternatives that merit a more detailed
         evaluation. A three-criteria screening of RAAs was not carried out in this FS. Estimated costs
         were calculated during an evaluation based on nine criteria established by the NCP.

         No innovative technologies were incorporated into RAAs.
  7.      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action
Estimated Costs
3 Criteria
N/A
9 Criteria
$0
488
                                                -2-

-------
Alternative
RAA-2
RAA-3
Standard Technology
Separation of soil and asbestos-
containing material (ACM)/on-site
thermal treatment (rotary kiln,
infrared, or fiuidized bed) of soil/
possible stabilization of fly ash or
treated soil/on-site disposal of treated
soil/topsoil cover/off-site disposal of
ACM'
Separation of soil and asbestos
containing material (ACM)/off-site
thermal treatment of soil/possible
stabilization of fly ash or treated
soil/off-site disposal of treated soil/off-
site disposal of ACMb
Estimated Costs
1
3 Criteria
N/A
• 1-"
l
. r
i
• i
N/A
i
i
^1 ' '
i ' .
9 Criteria
$10,672,400
to
$16,736,100b
$68,139,550
. \
       Currently, an asbestos repository exists at the AAAP. If this repository is approved for
       asbestos disposal, it will be considered for the disposal of ACM.
       ''No choice is made between the three incineration technologies.  Alsol costs do not include
       stabilization because it is not presently known how much material will require stabilizing.
       Stabilization  costs are estimated at $250 per cubic yard.              i
8.   .   If a standard technology was chosen, why?

       On-site thermal treatment and on-site disposal were chosen because nib waiting period is
       involved for implementation (a 3- to 5-year waiting period exists for off-site thermal
       treatment); the remedy does not require off-site transportation of contjiminated soils, thereby,
       eliminating the risks from spillage and dust emissions; the remedy is easily implemented since
       no  waiting period or off-site transportation is required; and the cost of the remedy is
       substantially lower, an estimated  15 to 25 percent less than the cost of the other remedial
       alternative. '     *                                                                     •
9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
10.     If an innovative technology was not chosen, why not? At what stage Was the innovative
        technology eliminated?                                                         ,
                                                                      . -t ••'         -
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                               -3-
489

-------
           Innovative technologies eliminated during the initial screening include the following:

           «      Molten salt destruction was eliminated because the technology has not been developed
                  to the point where it could be implemented for a large-scale facility-wide cleanup. In
                  addition, molten salt destruction would not be suitable for wastes with a high ash
                  content because frequent bed recycling and replacement would be required.
           •      Critical fluid solvent extraction was eliminated because it is an emerging technology
                  that has not been extensively tested for nitroaromatic compounds.             '   •

           Innovative technologies eliminated during the screening of the three criteria include the
           following:                               .                       .

           "      None

           Innovative technologies eliminated during the detailed analysis include the following:

           •      None
   77,     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology? If so,
          which criterion?  Which of the criteria supported the use of a standard technology?

          Short-term effectiveness, implementability, and cost were the criteria weighted most heavily in
          selecting a remedy. The remedy does not involve transporting contaminated spils off site,
          thereby eliminating the risks due to spillage and dust emissions.  Implementability was  •
          important; alternatives that require no waiting period (there is a 3- to 5-year waiting period for
          capacity in an off-site incinerator) and no off-site transportation are easier to implement. Cost
          was important in  that  the selected remedy is substantially less expensive, an estimated 15 to 25
          percent less than  the cost of the other remedial alternative.
   12.     What cleanup goals were selected?  If the cleanup goal was. based on an ARAR, what was that
          ARAR? What risk level was selected to establish cleanup goals?

          Cleanup of the explosives 2,4,6-trinitrotoluene, 2,4-dinitrotoluene, 2,6-dinitrotoluene, and
          2,4,6-trinitrophenylmethylnitramine was based on removing reactivity as determined under
          RCRA.                    ,               .
490
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Lead
Asbestos (in bulk soil)
5.0 mg/L in TCLP
extract
None if concentration
less than 1%
RCRA
TSCA 40 CFR 763
                                                 -4.

-------
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                                \

       Innovative technologies eliminated because of cleanup goals include:

       •      None                                                          .      '

       Standard technologies eliminated because of cleanup goals include:

                                                                        I
        •      None                                                    i          ,
                      •             '               "       ''••.-•  \.     '-'-
            . -                       .                        - ,     '    \-   '  '
 14.     Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.                             !
 75.     What measures/criteria were used to compare alternatives?
                                           '                             i •
        The following measures were used to compare the alternatives:                     -

             Risk level achieved                                         i
             Total cost                              ''.'..      \
             Time to design/construct/operate                             i
                                                                        i
                                                                    • -   |              ...

 76.     How are measures compared?
                                                                        i-..
        Off-site and on-site treatment were compared in the^above three catejgories.  On-site treatment
        had a lower short-term risk because no off-site transportation was required.  The total cost of
        on-site treatment was substantially less than that of off-site treatment:  And there was a 3- to
        5-year waiting period for off-site treatment compared to no wait for pn-site treatment.
                            -  •     '              .         .•   .      .-!•..•••.•         ^

 17.    What technical considerations-were factors in selecting a remedy?  Were, technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedy.  Qhe innovative technology,
        molten salt destruction, was eliminated partially because of the high ash content of soil.
                                                -5-
                                                                                                491

-------
                              Arlington Blending and Packaging
                                                          <<; in
                                Arlington, Shelby County, Tennessee
                                             Region 4
   GENERAL SITE INFORMATION

   L     What were the principal contaminants,
          contaminant levels, and media addressed in
          this feasibility study?

          Maximum concentrations of principal
          contaminants were:

          Surface Soil (pg/kg)

          Arsenic                    370,000
          Chlordane                 390,000
          Endrin                     70,000
          Heptachlor                 920,000
          Heptachlor Epoxide         20,000
          Pentachlorophenol          130,000

          Subsurface Soil (pg/kg)

          Chlordane                  120,000
          Endrin                     20,000
          Heptachlor                 34,000
          Heptachlor Epoxide         170
          Pentachlorophenol          8,500

          Sediments (pg/kg)

          Chlordane                  41,000
          Heptachlor                 2,800
                                                          Site History
                                             NPL Proposed:
                                             NPL Final:
                                             FS:
                                             ROD:
N/A
7/1989
1/18/1991
6/28/1991
                                                          Background

                                             EPA Fund-lead
                                             PRPs:  Arlington Blending and
                                                    Packaging
                                             FS prepared by: Ebasco Services Inc.
                                                                                              '
  2.     What volume of material is to be remediated?

         The volume of material to be remediated included:

         »      24,000 cubic yards of soils/sediments
  5.
492
Wliat type of site is this?

Agricultural Chemicals. An abandoned blending and packaging facility where pesticides,
herbicides, and other types of chemicals were formulated and packaged.  Located in a
predominantly agricultural and rural setting, it is bordered on the west by a Tennessee
Department of Transportation  facility and on the east by a residential housing development.
                                              -1-

-------
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Soil/Sediments

       Access restriction:
       Containment:
       Chemical/physical:
       Thermal treatment:
       Disposal:
Deed restrictions, fencing, soil and ground waiter monitoring
Capping (RCRA type), vertical barriers (slurry walls)
Solidification
Incineration (rotary kiln, infrared)
Excavation, extraction, disposal at RCRA-perrnitted facilities (on and
off site)
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening; of technically
        feasible technologies were:
        Soil/Sediments   ,

        Biological treatment:
        Chemical treatment:
        Thermal treatment:
In situ biodegradation, slurry-phase soil bioremed:
In situ soil flushing, soil washing
Pyrolytic incineration, low-temperature thermal
Model 200), in situ vitrification
   iiation

1 treatment (X*TRAX
                                                                        «.
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible tecl nologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives .that merit a more detailed
        evaluation. For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP: long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; arid community acceptance. Costs were recalculated in the ROD.
                                               -2-
                                                                  493

-------
                   Cost Estimates for RAAs That Include Inn -vative Technologies
                              (selected remedial alternative i   : bold)
          Soil/Sediments

Alternative
RAA-5" and
RAA-5A"




•
Innovative Technology
Excavation/on-site low-temperature
thermal treatment/solidification/ on-
site backfilling of contaminated
soils/activated carbon treatment and
discharge of ground water to surface
water or POTW
Estimated Costs
9 Criteria
$9,568,204
(RAA-5)

$9,325,909
(RAA-5A)

ROD
$12,170,167
(RAA-5)

$11,923,774
(RAA-5A)

          'RAA-5 would utilize approximately 15 extraction wells for removal of contaminated ground
          water from the site whereas RAA-5A would utilize approximately 8 extraction wells.
          'This technology is called ex situ thermal desorption in the ROD.
   7,      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)

          Soil/Sediments
494
Alternative
RAA-1
RAA-2
RAA-3" and
RAA-3A"
RAA-4" and
RAA-4A"
==3=S==
Standard Technology
No action/ground water monitoring
On-site cleaning caps/land use controls/
fence maintenance/ monitoring
Excavation/off-site incineration/
solidification/landfilling of contaminated
soils and building debris/activated
carbon treatment and discharge of
contaminated ground water to POTW
Excavation/on-site incineration/
solidification/on-site backfilling of
contaminated soils/off-site disposal of
building debris/activated carbon
treatment and discharge of contaminated
ground water to surface water or POTW
Estimated Costs
9 Criteria
$216,542
$68i;683
$37,040,675
(RAA-3)
$36,783,180
(RAA-3A)
$18,067,120
(RAA-4)
$17,885,427
(RAA-4A)
ROD
$249,023
$762,406
$41,348,205
(RAA-3)
$41,086,379
(RAA-3A)
$21,924,186
(RAA-4)
$21,679,158
(RAA-4A)
•- 	
         "RAA-3 and RAA-4 would use approximately 15 extraction wells for removal of contaminated
         ground water, whereas RAA-3A and RAA-4A would use approximately 8 extraction wells.
                                              -3-

-------
m
8.      If a standard technology was chosen, why?      -  ,   ' '             ;
              1                             ' "           ' '   'i   ' •   r      i
       Solidification/stabilization was selected in the ROD for some wastes.
                          ..                  -        ,          . • -:     •;       •  -  -     •    •

9.      If an innovative technology was chosen, why?          ,      :•      I             .
• '.'•'       •                •             '      '      '     i
       RAA-5 was selected because this alternative will immediately remove exposure pathways to
       the public. All the treatment components proposed are readily available and have been
       demonstrated to be effective in removing the contaminants of concern 'at the site. The chosen
       innovative technology (low-temperature thermal treatment) will permanently remove organic
       compounds from contaminated soils. This technology reliably  removes pesticides and
       pentachlorophenol from contaminated soils with efficiencies in excess ^>f 99 percent as
       required by RCRA regulations, with no expected significant risks frond products of  incomplete
       combustion;  Dechlorination of residuals was selected  in the ROD. The chosen innovative
       thermal treatment is more desirable than the standard thermal treatment of RAA-4 (on-site
       incineration) because it starts up and shuts down faster and it substantially reduces the waste
       volume. Also, once organic contaminants have been physically separated from site soils,
       process water will be further treated at  the site's  wastewater treatment facility.  The off-gas
       will be scrubbed by passing it through  beds of activated carbon before its release to the
       atmosphere, thus further reducing the toxicity of contaminated  soils.  In addition, this
       alternative complies with all applicable ARARs.  For the  wastes that cannot be treated to meet
       the applicable RCRA Land Disposal ^Restrictions, a Treatability Variance will be  sought
       pursuant to 40 CFR 268.44(h). Also, short-term risks  associated with implementing RAA-5
       are lower than with RAA-4 because the contaminants  do  not come into contact with a direct
       flame or with fuel combustion products.  Numerous vendors are available to furnish and to   '.
       operate the treatment equipment.  RAA-4 was selected as a contingency remedy.


10.    If an innovative technology was not chosen,  why not?  At what stage was the innovative
       technology eliminated?                                                                     .

       Innovative technologies could be eliminated from the remedial technology selection process  at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness,  implementability, and cost; or during the detailed evaluation.  This FS did not
       perform an initial screen but used a modified three criteria screen usinj* only effectiveness and
       implementability.
                                                                  ,1       '              •
       Innovative technologies eliminated during the initial screening  include the following:

       •      None                     ,                                j    '            " •
                                •              ^      •         .          'h '
                                                                        I             .  -      .  .  .'
       Innovative technologies eliminated during the screening of the three cijiteriia include the
       following:                                                           _
                                                                                             •-,
                                         ---              /                i                              .
       •      Pyrolytic incineration was eliminated because  it has not been demonstrated
               commercially on CERCLA wastes. The application of this technology  is contingent
               upon the successful demonstration of treatability studies.
       •      In situ vitrification was eliminated because it requires too much energy and is too
               costly. This technology has limited economic practicability in the site's soil with


                                               4-                                              495

-------
                 variable permeability and ground water because of the energy requirements for driving
                 off water.
         »      In situ soil flushing was eliminated because of the potential for adverse environmental
                 effects and anticipated difficulty in implementation due to site-specific characteristics.
                 Variable geology and a downward ground water gradient would prevent complete
                 recovery of the extraction fluids.                                        ,
         »      Soil washing was eliminated because site-specific conditions limit the effective
                 implementation of this technology.  The high clay content of the soil would limit the
                 effective treatment  of the washing fluids.
         »      In situ biodegradation was eliminated because it has not been shown to be effective
                 against pesticides such as chlordane and heptachlor.  Pertinent information concerning
                 biodegradation of pesticides has not been identified.  Test results to date have been
                 inconclusive.
         H      Slurry-phase soil bioremediation was eliminated since it has not been proved effective
                 with the contaminants of concern.  A treatability study would be required to establi .-
                 potential degradation rates for site-specific contaminants and to control and manipulate
                 environmental factors to develop the optimum bioremediation result.

         Innovative technologies eliminated during the detailed analysis include the following:

         «      None
         Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology? If so,
         which criterion? Which of the criteria supported the use of a standard technology?

         The criteria weighted most heavily in selecting an innovative remedial technology for this site
         were the protection of human health and the environment, and long-term effectiveness and
         permanence. The ROD states, however, that the selected remedy (RAA-5) provides the best
         balance of all nine criteria.                                               ,               .
 12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?  '

                Surface Soil
496
Contaminant
On-site Cleanup Level
(Mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Chlordane
Heptachlor
Heptachlor Epoxide
Pentachlorophenol
25,000
10,000
3,000
2,000
635
Risk3
Risk"
Risk"
Risk"
EPAC
                                               -5-

-------
     Contaminant
                        On-site Cleanup Level
                 ARAR or Other Basis
  Noncarcinogens
  Endrin
2,700
EPAC
The cleanup level for arsenic was derived on the basis of health-based risk and ground
water protection.  •
bCleanup levels are health-based and reduce risk to less than JO'5.               *  • •
°Value calculated by EPA Region 4 using available empirical data and model analysis
(model not specified).
Contaminant
Carcinogens
Arsenic
Chlordane
Heptachlor
Heptachlor Epoxide ' ,
1 Pentachlarophenol
Noncarcinogens
Endrin
Off-site Cleanup Level
(Mg/kg)

25,000
1,000
300
200
635

2,700
ARAR








/
or Other Basis

Risk3
Risk"
. Risk"
Risk"
EPAC

EPAC
The cleanup level for arsenic was derived on the basis of hesilth-based risk and ground
water protection.                                        ;
bCleanup levels are health-based and reduce risk to less than 10"6.
cValue calculated,by EPA Region 4 using available empirical data and model analysis
(model not specified).                                   !_

Subsurface Soil                                        I
Contaminant
Carcinogens
Chlordane
Heptachlor
Heptachlor Epoxide
Pentachlorophenol
On-site Cleanup Level
(ug/kg)
v
3,300
3,000
2,000
635
ARAF





or Other Basis

EPA"
Risk"
Risk"
EPA"
                               -6-.
                                                                            497

-------
498
                     Contaminant
  On-site Cleanup Level
         (jag/kg)
                                                                ARAR or Other Basis
                  Noncarcinogens
                •Value calculated by EPA Region 4 using available empirical data and model analysis
                (model not specified).
                bCleanup levels are health-based and reduce risk to less than lO'5.

                                                        '
                                       Off-site Cleanup Level
                     Contaminant
                                                                ARAR or Other Basis
                 Carcinogens
                 Chlordane
                 Heptachlor
                 Heptachlor Epoxide
                 Pentachlorophenol
                                               3,300
          300
          200
          635
                                 EPA1
Risk"
Risk"
                                 EPA"
                 Noncarcinogens
               "Value calculated by EPA Region 4 using available empirical data and model analysis
               (model not specified).       '   ,

               bCleanup levels are health-based and reduce risk to less than 10:e.

               Sediment
Contaminant
On-site Cleanup Level
(wg/kg)
ARAR or Other Basis
Carcinogens
Chlordane
Heptachlor
3,300
3,000
EPAa
EPA"
              •Value calculated by EPA Region 4 using available empirical data and model analysis
              (model not specified).
                   Contaminant
Off-site Cleanup Level
       (Mg/kg)
                                                              ARAR or Other Basis
                Carcinogens
                Chlordane
                                              3,300
                                EPAa
                                            -7-

-------
Contaminant
Heptachlor
Off-site Cleanup Level
(Mg/kg)
300
ARAR ii>r Other Basis
!EPAb
              'Value calculated by EPA Region 4 using available empirical data and model analysis
              (model not specified).                 •                    !
              •"Cleanup level is health-based and reduces risk to less than 10"16.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                                j

       Innovative technologies eliminated because of cleanup goals include:

       •     None                 '       '                         •  . [
                                                                       -!
       Standard technologies eliminated because of cleanup goals include:

       •     None
14.    Were treatability studies conducted on the innovative technology or standard technology?

       The Proposed Plan states that a treatability study is being conducted for RAA-5 and RAA-5A
       (low temperature thermal desorption) on representative site soils and debris to determine
       whether the innovative technology will meet soil cleanup levels. Although the results of the
       treatability study were to be available before completion of the ROD, ithis study is not
       discussed in the ROD.                                           S   •
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Cost effectiveness  '
               Proven reliability
               Preference for treatment (vs. containment)
 16.     How are measures compared?                           ,

        The selected remedy was chosen because it provides the best balance among the criteria used
        to evaluate the alternatives in the Detailed Analysis. RAA-5 achieves adequate protection of
        human health and the environment and meets the statutory requirements of Section 121 of
        CERCLA in a cost-effective manner.  The innovative technology chosen had been successfully
        tested on VOGs, polynuclear aromatic compounds, chlorinated organic contaminants, and
        PCBs.  Although this technology had not been fully developed, the pilot-scale units had been
        successfully tested by IT Corporation, Chemical Waste Management, Inc., and Weston
        Services, Inc. In addition, treatment was preferred over containment tecause it will
                                              -8-
499

-------
         permanently reduce contaminants in the site's ground water and soils, and it will provide for
         long-term protection against exposure from these contaminants.

 17,     Wtot technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection of the remedy?

         Site-specific conditions were primary in eliminating three innovative technologies  Because of
         the site soil's  variable permeability, in situ vitrification was eliminated. In situ soil flushing
         was likewtse eliminated due to the variable geology and downward gradient of the ground
         water flow which prevents the complete recovery of extraction fluids.  The high clay content
         of the soil limits the effective implementation of soil washing at this site.
500

-------
                                Benfield Industries, Inc.
                                 Hazelwood, North Carolina
                                         Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

     ,  Benzo(a)anthracene       '33      .
       Benzo(a)pyrene              14
       Benzo(b or k)fluoranthene   31
       Chrysene                   23
       Indeno(l,2,3-cd)pyrene       5.1
       Naphthalene                120
       Pentachlorophenol          19
3.-
                                                         Sitei History
                                            NPL Proposed;
                                            NPL Final:
                                            FS:
                                            ROD:
6/24/88
10/4/89
7/16/92
7/31/92
                                                         Background
                                            EPA Fund-lead
                                            PRPs:  Thomas G;. Benfield
                                            FS prepared by:  B&V Waste Science
                                                   and Technology Group
What volume of material is to be remediated?  '•   '

The volume of material to be remediated included:           '

•      4,600 cubic yards of soil


What type of site is this?                                  -•'•..''
                                                            i,
Chemicals and Allied Products. The site was occupied by a bulk chemical mixing and
repackaging plant until it burned down in 1982.  The site is surrounded by light industrial,
commercial,  and  industrial areas.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:     Land use restrictions, fencing
        Containment;          Capping (soil, clay, asphalt, asphaltic concrete, concrete, gravel,
         •                    synthetic membrane, RCRA multilayer, chemical sealants), slurry wall,
                                             -1-
                                                                                    501

-------
          Chemical treatment:
          Physical/chemical:
          Physical treatment:
          Thermal treatment:

          Disposal:
                               grout curtain, vibrating beam, sheet piling, rock grouting, grout
                               injection, block displacement, gradient control, surface controls,
                               dust/vapor suppression                                       ~
                               Neutralization (in situ, on-site), precipitation ,
                               Stabilization/solidification (lime-fly ash, portland cement), organic
                               contaminant stabilization/solidification,  microencapsulation,  Surface
                               encapsulation
                               Solids separation, decontamination '  '"'.' '  "
                               Incineration (rotary kiln, multiple hearth, fluidized bed, circulating bed,
                               high temperature fluid wall reactor, infrared)
                              Excavation, RCRA landfill (on-site, off-site)
5.
          Was an innovative technology considered in the F$? If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:

          Biological treatment:   Landfarming (on-site, off-site),  composting, slurry biotreatment, in situ
                                bioremediation
          Physical/chemical:     In situ soil flushing, oxidation (in situ, on-site), reduction (in situ, on-
                                site), water leaching, solvent extraction, soil washing, in situ soil vapor
                                extraction
          Thermal treatment:     Molten salt incineration, plasm  arc torch, low-temperature thermal
                                extraction, pyrolysis, vitrification (in situ, on-site)
  6.      What was the cost estimate for the innovative technology?    .'

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are usually estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation. For this site, the estimated costs were calculated during an evaluation based on
         nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
         effectiveness; compliance with ARARs; protectiveness of human health and the environment;
         reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support '
         agency acceptance; and community acceptance.

                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
502
Alternative
RAA-3
RAA-4
RAA-6
Innovative Technology
Soil washing/slurry biotreatment
Solvent extraction
In situ bioremediation
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$1,033,100
$2,630,500
$1,034,000
                                                -2-

-------
7.      How did the cost(s) compare to standard technologies?              j

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-5
RAA-7
\ . - ... ;
Standard Technology
No action
RCRA cap
On-site incineration
Off-site incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9Criteria
$100,000
$997,500
$7,262,700
$15,804,100
8.
If a standard technology was chosen, why?

A standard technology was not selected.
 9.      If an innovative technology was chosen, why?

        The chosen alternative was preferred because it reduces risk by decreasing the toxicity,
        mobility, and volume of site contaminants.  In  addition, by remediating to soil cleanup levels,
        the technique will protect the underlying ground water. The treatment proposed, slurry
        biotreatment, provides a long-term and permanent reduction of site contaminants. The
        permanent elimination Of site contaminants was preferred over containment because
        contaminants left on site could migrate to ground water during seasonal water table changes
        when leachate would be generated.  Slurry biotreatment was preferred over other innovative
        treatment technologies because its effectiveness is more certain and it will reach cleanup levels
        more quickly. Slurry biodegradatibn has been  successfully demonstrated under the EPA SITE
        program for wood preserving wastes .which have similar contaminants to those found at this
        site.  Slurry biotreatment was preferred over other innovative and standard treatment
        technologies that offered comparable protectiveness because it was more cost-effective.
 10.    If an innovative technology was not chosen, why not? At what stage was the innovative  .
        technology eliminated?                                    '    '  i

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial  screening includ|e the following:

         •      Oxidation (in situ, on-site) was eliminated because it has not been proved effective for
                PAH-contaminated soils.  Furthermore, contaminants may degrade into more toxic
                products.--
                                                -3-
                                                                                              503

-------
504
           «      Reduction (in situ, on-site) was eliminated because its effectiveness in tearing organics
                  has not been proved.                                                                   "~" .""\
           a      Water leaching was eliminated because the site's PAH contaminants have extremely           '-—/
                  low water solubilities; therefore, the process would be ineffective.
           a      Molten salt incineration was eliminated because mo full-scale demonstrations have
                  been completed on PAH-contaminated waste materials.    .                                       '
           a      Plasm arc torch was eliminated because it is applicable only to liquid organic wastes
                  and finely divided, fluidizable sludges.                                            .              •
           •*      Low-temperature thermal extraction was eliminated because it would hot be effective
                  in removing the four-and five-ring PAHs.                '                                       i:
           » .     On-site vitrification was eliminated because it is an experimental process that only has        , • '   &
                  been pilot tested. Material handling would be required to size/sort the contaminated                i
                  materials  before implementation                                                                , S
           a      In situ soil vapor extraction was eliminated because it would not be effective in                    |
                  treating the  semivolatile organic contaminants in the soils, since they have very low                *'
                .,.vapor pressures.                            ',                                                   !
           a      In situ vitrification was eliminated because She very high local water table would                   I
            i      interfere with implementation. The offgas system would not be completely effective in              i
            ,      capturing  all volatilized contaminants.               ',•*;,-.,.-•                                     r
           •      In situ soil flushing was eliminated because it would be difficult to collect the solvent
           ;       because of the high local water table.               "'*

           Innovative technologies eliminated during the screening of the tihree criteria include  the                     :t
           following:                                                                                    ^^^    ::

                                                                            '                        '"   vmSr ""****
           s-=    ^Landfarming (on-site) was eliminated because it would ^be less effective and take             ~7     J
                  longer to treat than slurry biotreatment, would require pilot testing,  might not be                    ;
                  completely effective in treating carcinogenic PAHs, and might not meet PAH cleanup               '
                  levels,                                                                                         r.
           *  "     Composting  was eliminated because it would be^less effective and take longer to treat               !;
                  than slurry biotreatment, would require pilot testing, might not be completely effective
                  in treating carcinogenic PAHs, and might not meet PAH cleanup levels.                        ':',:.
           K       Pyrolysis was eliminated because extensive permitting and performance requirements
                  could preclude its use, materials handling would be required,  the technique might  not
                  be acceptable in a residential area, and char might be hazardous and require  further     i '
                  treatment.
           B       Landfarming (off-site) was eliminated because it has not been fully demonstrated for                :
                  four- and five-ring PAHs.  It would be practical  only as a second option for  the
                  contaminated soil if soil volume is much larger than estimated in the FS.

          Innovative technologies eliminated during the detailed analysis include the following:

          »      Solvent extraction was eliminated because it would not be cost-effective.
          •      In situ bioremediation was eliminated because its effectiveness for remediating site
                 contaminants was less certain than that of the selected alternative.

                                                 -4-

-------
11.
Which of the nine criteria were weighted most heavily in selecting the
to meet one of the nine criteria result in the elimination of the i,
which criterion? Which of the criteria supported the use of a standard
       technology? Did failure
innovaiive technology? If so,
        technology?
       The criteria most heavily weighted in selecting a remedial alternative
       effectiveness and cost. Solvent extraction was eliminated because it
12.
What cleanup goals were selected? If the cleanup goal was based on
ARAR? What risk level was selected to establish cleanup goals?
                     Contaminant
                                 Cleanup Level (mg/kg)  | ARAR or Other Basis
                 Carcinogens
                                                                ivere long-term
                                                               was mot cost-effective^
                                                                        an ARAR, what was that
                 Benzo(a)anthracene
                 Benzo(a)pyrene
                 Benzo(b and/or k)
                 fluoranthenfe
                 Chrysene
                 Indeno(l,2,3-cd)
                 pyrene
                 Pentachlorophenol
                                          0.8
                                          0.3
                                           1.6
                                           1.6
                                           2.8
   Leaching Model3
                                                                         Risk"
   Leaching Model
    Leaching Model
    Leaching Model
                                                             Leaching Model
                 Noncarcinogens
                 Naphthalene
                                           10
    Leaching Model
  13.
        The risk assessment determined that soil did not pose an unacceptable risk to human
        health.  Soil cleanup levels were established, however, because the levels of
        contaminants in the son will continue to affect ground water quality for an estimated
        200 years. Soil remediation levels were developed based on!the contaminants ability
        to migrate through the soil and leach into the underlying ground water. The
        Multimedia Leaching model was used for generating cleanup goals.
        "The health-based goal for benzo(a)pyrene was more protective than the teachability
        goal. For carcinogens, an excess upper bound individual lifetime cancer risk of
        between 10"4 to 10"* was acceptable. For noncarcinogens, a JHazard Index less than or
        equal to 1.0 was acceptable.                              !
                 .                       .'•••".         i'
                »-"    . .                       -                 •'•             •     .•
                                                                i, , , •          '    •
  Was the  innovative technology eliminated because of the cleanup goals?  Could the standard
  technology meet the cleanup goals?                              |
                                          "  \                    ! '
                                                                I -.•-••
  Innovative technologies eliminated because of cleanup goals include:
   '
                                                                i                 . •
  •      Landfarming                                            J         ~
  •      Composting                                                  ,
                                                                                              505
                                                -5-

-------
          Standard technologies eliminated because of cleanup goals include:

          M      None                                               •'"•.,.


   / A     Were treatability studies conducted on the innovative technology or standard technology?    -             ^

          No treatability studies were conducted.                                                                 i.


   1$      What measures/criteria were used to compare alternatives?                                              *
                     t           .--'''.,                 -                            f '-
          The following measures were used to compare the alternatives:                                          s

               Cost-effectiveness                                         -                                     /
               Time to design/constnict/operate
               Proven reliability                                         '
               Preference for treatment (vs. containment)


  16.     How are measures compared?                                „                                        i,

         Slurry biotreatment was preferred over other treatment alternatives (solvent extraction                      I
         incineration) that were rated equally for nonfinanciai; criteria because it had the lowest present              ;
         worth cost.  While another innovative technology, in situ bioremediation, was less costly than      JH .  I
         slurry bioremediation it was not chosen because it would take longer to meet cleanup levels        ~  V
         and it has not been proved  effective for the remediation of PAHs. Slurry biodegradation was             -
         preferred because it is reliable.  It has been successMly demonstrated under the EPA SITE                 •'
         program for wood-preserving wastes that have similar contaminants to those found at the                   !
         Benfield site. Treatment was preferred over containment.  Although capping would be less
         costly, it  was eliminated because it would leave contaminants in place untreated as a                       I
         continuous source of ground water contamination. Seasonal water table fluctuations would                 '•!
         increase the  mobility of contaminants to ground water through the generation of leachate
         Time to meet cleanup levels was another consideration. The chosen technology was  preferred              !
         over other biological treatments such as landfarming and composting, because it would reach
         cleanup levels more quickly.


 If.     What technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection of the remedy?

         Technical considerations were not primary in choosing a remedial alternative. The high water
         table oid,  however, preclude the use  of in situ vitrification.
506
                                              '-6-

-------
                           Carolina Transformer Company

                      Fayetteville, Cumberland County, North Carolina
                                         Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and med'
      ._• this feasibility study ?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediments/Debris (mg/kg)

       PCB (Total)
       Dioxins/Furans
       Toluene
       Dichlorobenzene
       Chlorobenzene
       Trichloroethylene
       Tetrachloroethylene
       Copper
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •     5,780 cubic yards of on-site soil/sediments
        •     9,565 cubic yards of off-site soil/sediments
linants,
Addressed in
ncipal
)
2,100
0.00042
2.4
0.75
0.048
0.004
0.004
130
Site
NPL Proposed:
NPL Final:
FS:
ROD:
History .
7/22/87
N/A ,
3/4/91
8/29/91
Background
EPA Fund-lead
PRPs: Carolina 1
FS prepared by: I
and Techn


ransforrher Company
J&V Waste Science
ology Corp.


  3.      What type of site is this?

         Electrical Equipment.  Formerly the site of the CaroHna Transformed Company, which
         conducted an electrical transformer rebuilding and repair business from 1967 to 1982, the site
         has been vacant since 1986.  The site is located in a predominantly rural setting.  A food
         processing facility called Larry's Sausage is adjacent to the site. '
  TECHNOLOGY SELECTION                                       i

  4.     What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:                                           |     '          •  .

         Access restriction:     Deed restrictions, fencing, permits
                                               -1-
507

-------
     5.
   6.
508
             Containment:
    Chemical treatment:
    Physical  treatment:
    Thermal treatment:

    Disposal:
                                   Capping (native soil, clay, synthetic membranes, sprayed asphalt
                                   asphaluc concrete, concrete, multilayered cap), vertical barfers
                                   horizontal bamers, surface controls, segment control barriers
                                   Neutralization, solidification/fixation/stahilization
                                   Sojids processing, dewateririg, air emission/gas treatment
                                   toemton (rotary kiln, fMdized bed, circulating fluidized bed,

                                  Excavation, resource recovery, temporary storage, wastewater
                                  discharge, evaporation ponds, landfill (RCRA, non-RCRA, TSCA)
    Was an innovative technology considered in theFS?  IfSQ, which technology?




   Biological treatment:   Aerobic, biodegradation, anaerobic biodegradation new
  What
                    the cost estimate for the Innovative technology?
                   Cost Estimates for RAAs That Include Innovative Technologies
                               (selected remedial alternative is in bold)
          Soil/Sediment
                                    Innovative Technology
                            Excavation/on-site chemical
                            _                      	' ^^^""^™^^™™

                            Excavation/on-site solvent extraction
                            I a-tflf**n T7*«M^__ —A*	  f*-a  -m   —
                            	.. «.v^ fvjiTWiiK, CAilifCllllJ
                   (Basic Extraction Sludge Treatment
                   ri> t* o m i	*   \
                            [B.E.S.T.] system).
                                                   soil/sediments to 1 ppm, whereas "B"
alternatives treat soil/sediments to 10 ppm.

-------
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)     j
       Soil/Sediment
           Alternative*
         S/S-1
         S/S-2
         S/S-3A and
         S/S-3B
          S/S-4A and
          S/S-4B
                                 Standard Technology
                         No action
                         Fence/deed restrictions
                         Excavation/off-ske landfill
                         Excavation/on-site incineration
                                                                       Estimated Cosw
3 Criteria
                                                                      N/A
                                                                      N/A
                                                                      N/A
        aThe "A" alternatives treat PCB-contaminated soil/sediments to 1 ppm
        alternatives treat soil/sediments to 10 ppm.
                                                                                  9 Criteria
                   $0
                $172,000
               $9,228,800
                (S/S-3A)

               $8,463,600
                (S/S-3B)
              $18,019,300
                (S/S-4A)

              $16,301,200
                (S/S-4B)
                                                                        whereas "B"
                                                                        wastes at the site.
8.      If a standard technology was chosen, why?          . -    -

       A standard technology 03-3) was chosen to remediate the debris/splifl


9.      If an innovative technology was chosen, why?

       An innovative technology was chosen to treat contaminated soil/sediments at the site.
       Alternative S/S-6A was selected because it will protect the local corpmunity and the
       environment by chemically treating contaminated soil/sediments with PCB concentrations
       above 1 ppm.  In demonstration-scale projects, the solvent extraction process has removed over
       99 percent of PCBs from soils and sediments.  Similar removal efficiencies are expected for
       dioxin/furans and other organics. Although the process does not reduce ithe toxicity or volume
       of inorganic contaminants, metals such as mercury, lead, zinc, chromium, and copper are
       converted to their lowest solubility states, thus minimizing their mobility.  In addition, the
       selected remedy meets the statutory requirement of utilizing permanent solutions and treatment
       technologies to the maximum extent practical. In a sensitivity analysis conducted on each of
       the soil/sediment alternatives, the selected alternative S/S-6A shared! the highest rating with
       alternative S/S-5A.                                             |                       ,
                                               -3-
                                                                                                509

-------
    JO.     If an innovative technology way not chosen, why not? At what stage was the innovative
            technology eliminated?


            Innovative technologies could be eliminated from the remedial technology  selection process at
            three stages: during the initial screening; during the screening of the three criteria of
            ettectiveness, implementability, and cost; or during the detailed evaluation.

           Innovative technologies eliminated during the initial screening include the following:

            «       Ground freezing was eliminated because it would not be feasible in the region's warm
                   climate and it would not provide a long-term solution.
           «       Critical fluid extraction was eliminated because it would not be applicable to this site
                   No reason was provided.
           "      Aerobic and anaerobic biodegradatipn were eliminated because they would not be
                  applicable to most contaminants of concern.
           a      New biotechnologies were eliminated because they would riot be applicable to most
                  contaminants of concern.
           «      Land treatment was eliminated because it would not be applicable to most
                  contaminants of concern.                       '  ",  .
           •      Soil vapor traction was eliminated because it would not be applicable to this site
                  since low levels of VOCs are present.
           B      Soils flushing was eliminated because it would not be applicable to  this site  The
                  process  would solubilize currently immobile contaminants.
           "      Wet air  oxidation was eliminated because it would not be applicable to this site  No
                  reason was provided.

          Innovative technologies eliminated during the screening of the three criteria include the
          following:


          «     Bioreclamation was eliminated,because its effectiveness has not been demonstrated for
                 A SvJDS.                                                                  -       '
          "     Oxidation ^yas eliminated because it would be effective only for limited contaminants
                 and it might increase  ground water contamination problems.
          "     Reduction was eliminated because it would be effective .only for limited contaminants
                 and it might increase ground water contamination problems.
          »      Vitrification was eliminated because, although effective, it would require offgas
                 collection and treatment It is less appropriate for shallow soil contamination
          »      Pyrolysis was eliminated because, although effective, residuals might require additional
                 treatment.                                ,

          Innovative technologies eliminated during the detailed analysis include the following:

          »      Organic chemical dechlorination was eliminated but no specific reason was provided
                 This technology shared the highest rating with  the selected innovative technology in a
                 sensitivity analysis conducted for comparison purposes. The ROD states, however
                 that this alternative might not be in compliance with parts of TSCA chemical-specific
                 and action-specific regulations, including 40 CFR 761.60, 761,70, and 761.75
                 Soil/sediments with PCB concentrations exceeding 50 ppm are specifically required by
                 Part 761.60 (a)(4) to be disposed  of in an incinerator (761.70), chemical waste landfill
                 (761.75),  or by equivalent treatment (761.60 (a)). Chemical dechlorination would
                 require pilot treatment tests to be considered an equivalent treatment method since
510 •-•
->>'
                                                -4-

-------
              limited studies are available to document its effectiveness.  Effectiveness might vary
              with soil/sediment composition and other factors.            i
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                        - • -             '         -       I , .    - •
       Soil/Sediment

       The criteria most heavily weighted in selecting an innovative technology for soil/sediments
       were protection of human health and the environment, long-term effectiveness and
       permanence, and reduction in toxicity, mobility, and volume of contaminants through
       treatment.  The "A" alternatives are most protective because they chemically treat PCB-
       contaminated soil/sediments to  1 ppm, whereas the "B" alternatives only treat PCB-
       contaminated soil/sediments to  10 ppm.  The selected alternative, S/S-I6A, provides a permanent
       remedy that removes the contaminants from the associated media and disposes of the reduced
       contaminated waste stream off site.                 '...-•'(
                                                                      •i   •   "            "
       Debris/Solid Waste

       the criteria most heavily weighted in selecting a standard technology^ are protection of human
       health and the environment and compliance with ARARs. The selected alternative, off-site
       landfill, permanently removes contaminated debris/solid waste from l|he site and eliminates the
       threat of direct contact with PCBs.
       .                                                   •   .      .    |.'
       1                    •                    '..'.'    H
       No innovative technologies were eliminated due to the nine criteria. \   •
 12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?    I
                                                                       i         ~           '
               Soil/Sediments
Contaminant
Cleanup Level (sag/kg)
ARA1R or Other Basis
Carcinogens
PCBs (Total):
Dioxins/Furans
1 (10a)
1.2E-04
TSCAb
'Risk6
               "Alternative cleanup level.
               ''EPA PCB soil cleanup guideline to remove all soil/sediments with total PCB
               concentrations greater than 1 mg/kg would reduce the carcinogenic risk to
               approximately 10"5. The same degree of protection can be_abhieved by removing
               soil/sediment with a total PCB concentration greater than 10j mg/kg combined with
               placing ,10 inches of clean soil over any soil/sediments exceeding 1 mg/kg.
               cAn excess upper bound individual lifetime cancer risk of between 10"4 to 10"6 was
               acceptable.     •                     _  • •
                                               -5-
                                                                                               511

-------
  13.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      None    *                                   '      .  •--

 Standard technologies eliminated because of cleanup goals include:

 •      None
  14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Cost-effectiveness
              Preference for treatment (vs. containment)
              Impact on nearby populations
              Proven reliability


  16.     How are measures compared?                             ~     .  '

         The selected remedy provides a permanent and cost-effective solution. The selected remedy
         also meets the  statutory requirement of utilizing permanent solutions and treatment
         technologies to the maximum extent practical.  In addition, the potential impact on an adjacent
         food processing facility was a significant consideration in eliminating alternatives S/S-4A and
         4B.  Extensive stack emission controls would be required to ensure that the incinerator
         proposed in S/S-4A and 4B would not affect this facility. Finally, the chosen innovative
         technology, solvent extraction, was  selected because of its demonstrated PCB-removal
         efficiency from soils and sediments of over 99 percent.                         ,,
 17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedy. The depth of contamination
played a role, however,  in eliminating vitrification as a treatment technology because it would
be less appropriate for the site's shallow soil contamination.
512

-------
                             Carrier Air Conditioning Co.
                                    Collierville, Tennessee
                                          Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       Trichloroethene (TCE)       1.200
       1,2-Dichloroethene (DCE)      0.2
       Tetrachloroethene (PCE)      0.011
       Lead                        21.4
       Ziric'                        77.8
                                    SiteHist:ory

                       NPL Proposed:     |   6/88
                       NPL Final:        i   1990
                       FS:            .   !   4/92
                       ROD:             |   9/3/92

                                    Background
                                         I      ••  '
                       PRP-lead          |
                       PRPs:  Town of Collierville, Carrier
                              Corporation
                       FS prepared by:  Environmental and
                              Safety Designs, Inc.
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      76,500 cubic yards of soil
 3.      What type of site is this?

        Fabricated Metal Products.1 The site is used to manufacture residential heating and air
        conditioning units.  Land use in the immediate vicinity of the site is industrial/commercial and
        undeveloped.
 TECHNOLOGY SELECTION                                                               ,
     1  *                              '                                 ' " .
 4.      What standard technologies were considered for selection in this FS?\

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                       .
        Access restriction:
        Containment:
Fencing, deed restrictions
Capping (RCRA-type, clay, soil, synthetic, asphalt, concrete type),
vertical barriers (slurry wall, sheet piling), surface/sediment controls
(surface water diversion, sediment barriers), dust/volatile organic
compound controls (capping, revegetation, sp:ray-on suppressants, other
engineering controls)
                                              -1-
                                                                                              513

-------
        Physical treatment:
        Thermal treatment:
        Disposal:
Ex situ solidification} ex situ stabilization, ex situ microencapsulation
Incineration (fluidized bed, rotary kiln, infrared)
Excavation, off-site disposal, on-site disposal
5.      Was cm innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:          ,              ,

        Biological treatment:   Ex situ aerobic/anaerobic solid phase biodegradation, ex situ aerobic/
                              anaerobic slurry phase biodegradation, in situ aerobic/anaerobic
                              biological treatment
        Phys/Chem treatment:  Ex situ soil washing,  in situ chemical treatment (soil flushing with
                              solvents for extraction, chemical treatment with stabilizing or oxidizing
                              agents for treatment to degrade or immobilize), ex situ waste pile
                              vapor extraction, in situ vapor extraction
        Thermal treatment:     Ex situ low-temperature thermal desorption, in  situ vitrification
6.      What was the cost estimate for the innovative technology?

        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability,  and cost) to identify alternatives that merit a more detailed evaluation.' The
        estimated costs then are recalculated during an evaluation based on nine criteria established bv
        the NCP.                               *   '              ,                      .        *

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-3
RAA-4A
Innovative Technology
Continued operation of existing soil
vapor extraction/ground water
containment and treatment
Expansion of existing soil vapor
extraction/ground water containment
and treatment
Expansion of existing soil vapor
extraction/expanded ground water
containment and treatment via air
stripping
Estimated Costs
3 Criteria
$3,000,000
to
$4,000,000
$5,000,000
to
$7,500,000
$5,700,000
to
$8,000,000
9 Criteria"
eliminated5
($2,968,754
to
$4,064,847)
$5,500,000 to
$7,500,000
($5,568,140
to
$7,451,775)
$5,700,000 to
$7,900,000
($5,717,755
to
$7,932,765)
514

-------

Alternative
RAA-4B




RAA-5


.*

RAA-6A




RAA-6B



,


Innovative Technology
Expansion of existing soil vapor
extraction/expanded ground water
containment and treatment via UV
oxidation

Excavation/low-temperature thermal
desorption/expansion of soil vapor
extraction/ground water containment
and treatment

Excavation/low-temperature thermal
desorption/expansion of soil vapor
extraction/expanded ground water
containment and treatment via air
stripping
Excavation/low-temperature thermal
desorption/expansion of soil vapor
extraction/expanded ground water
containment and treatment via UV
oxidation

Estimated Costs
3 Criteria
$6,000,(XX)
to
$8,400,000


$9,500,000
to
$14,000,000


$9,800,000
to
$14,500,000


$9,800,000
to
$14,500,000


•
9 Criteria*
$6,000,000 to
$8,400,000
($6,054,423
to
$8,417,675)
$9,500,000 to
$14,000,000
($9,467,667
to
$13,956,482)
$9,800,000 to
$14,500,000
($9,788,616
to
$14,508,506)
$10,000,000
to
$14,900,000
($10,014,179
to
$14,851,035)
       "Costs in parentheses are for the ROD.
       bRAA-2 was eliminated after the three-criteria screening in the FS, but jvas presented in the
       ROD.                      '•'-••-•'
7.'     How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologic
                           (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
l
No action/discontinue existing soil
vapor extraction/discontinue ground
water containment and treatment
Estimated Costs
3 Criteria
$1,400,000 to
$2,200,000
I
9 Criteria"
$2,100,000
($1,437,223
to
$2,180,152)
       "Costs in parentheses are for the ROD.
                                             3-
515

-------
   5.     If a standard technology was chosen, why?
                                                               ••'.'•.           •   •          mum   -v
          A standard technology was not chosen.                                                      ,  ^^   \)


   9.     If an  innovative technology was chosen, why?

          RAA-4A was chosen primarily based on decisions pertaining to ground water treatment.  With
          regards to soil remediation, RAA-4 (soil vapor extraction) was selected because it irreversibly"
          removes VOCs from soils to levels at or below soil cleanup levels.  The remedy poses no
          short-term threats that cannot be readily controlled. In addition, no adverse cross-media
          impacts are expected from  the remedy.  By utilizing treatment as a significant portion  of the
          remedy, the statutory preference for remedies that employ treatment as a principal element is
          satisfied.


   10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?

          Innovative technologies could be eliminated from the remedial technology selection process at
          three stages:  during the initial screening; during the screening of the three criteria of       :
          effectiveness, implementability, and cost; or during the detailed evaluation.

          Innovative technologies eliminated during the initial screening include  the following:

          •      In situ biological treatment was eliminated  because of uncertainty with'implementation    fl)
                 and the complication of fugitive air emissions. Implementation of bioremediation          ^^  •
                 would require establishment of an environment that is supportive of the required
                 microorganisms and contact with the target contaminant. Although biological
                 degradation  of TCE has been seen to occur naturally  at Collierville, and it has been                i
                 stimulated and utilized as a remedy at other TCE-contaminated sites, site-specific
                 variables are not well understood. Significant treatability testing would likely be                  :
                 required. Volatilization and air emission of organic compounds during bioremediation             i'
                 could reduce contaminant levels more than actual metabolysis.  Therefore, air
                 emissions must be mitigated during treatment.  Note that the FS does not  specify that
                 this is in situ biodegradation; however, since both ex  situ biodegradation technologies
                 are eliminated  separately, this must refer to  in situ treatment.
          •       In situ chemical treatment was eliminated because of the proximity of the underlying
                 aquifer and uncertainty regarding the clay layer thickness.
          •       In situ vitrification was eliminated because the technology would not be applicable to
                 the site contaminants.
          •       Ex situ soil washing was eliminated because the technology would provide no
                 advantage in effectiveness over soil vapor extraction or low-temperature thermal
                 desorption for-volatile organic contaminants. There would  be the potential for fugitive
                 air emissions and the generation of liquid residuals  requiring further treatment.
         •       Ex situ slurry-phase bioremediation was eliminated because the technology would
                 provide no advantage in effectiveness over soil vapor  extraction or low-temperature
                 thermal desorption for volatile organic contaminants.  There would be the  potential for
                 fugitive air emissions and the generation of liquid residuals requiring further treatment.     A    V
         •       Ex situ soil (presumably waste pile) vapor extraction was eliminated because it  would     •»   I
                 be no more promising than in situ soil vapor extraction or low-temperature thermal        ^^    ;

516
                                                -4-

-------
11.
              desorption, and would pose the complication of fugitive air emissions, which would be
              more difficult to control than with the closed treatment systems.       ,
              Ex situ solid phase bioremediation was eliminated because with the primary
              remediation target TCE and natural degradation products, successful implementation, of
              bioremediation is more complicated than with'light, simple hydrocarbon compounds.
              This technology holds no advantage over waste pile vapor extraction or thermal
              treatment, and fugitive volatile compound emissions would be more difficult to
              control.                                                   [
       Innovative technologies eliminated during the screening of the three criteria include the    ,
       following:                          .
                           •  r       I               '       '    .    '      !            '    .'•'•.,'
                  •           .                      •  '          '         "
       •      None

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Ex situ low-temperature thermal desorption was eliminated because invasive
              excavation measures would affect ongoing manufacturing operations in a more
              disruptive fashion than would soil vapor extraction; excavation, would expose remedial
              workers to a greater potential for physical injury relative to the; less invasive soil vapor
              extraction; and excavation would increase VOCs and fugitive dust emissions.
              Although low-temperature thermal desorption combined with s^il' vapor, extraction
              would provide  certain and relatively rapid treatment of shallow source area soils,  it
              would cost significantly more than soil vapor extraction alone.
       Which of the nine criteria were weighted most heavily in selecting the [technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                  •           '           '           •
       Selection of RAA-4A was based primarily on ground water remediation; however, a choice
       between soil remediation technologies needed to be made.  The criteria weighted most heavily
       in selecting a remedy included short-term risk and cost. Short-term risk from RAA-5 and
       RAA-6 are higher than would be associated with RAA-3 and RAA-4 because excavation
       activities would increase VOCs and fugitive dust emissions.  Further, iinvasive excavation
       measures would affect ongoing manufacturing  operations in  a more disruptive fashion than
       would soil vapor extraction, and excavation would expose remedial workers to a greater
       potential for physical injury relative to the less invasive soil vapor extraction. In relation to
       cost,  although low-temperature thermal desorption combined  with soil vapor extraction would
       provide certain and relatively rapid treatment of shallow source area soils, it would cost
       significantly more than soil vapor extraction alone.
-12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
                     Contaminant
                 Carcinogens
                 Trichloroethene
                                        Cleanup Level (fig/kg)
ARAR or (Other Basis
                                                 533
        Model8
                                                                                              517

-------
                 *From EPA's Center for Environmental Assessment Modeling (CEAM) Exposure
                 Assessment Multimedia Model (MultiMed) to protect the aquifer.

          For carcinoeens, an excess upper bound individual lifetime cancer risk of between 10" to 10"6
          was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.


   75.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
          technology meet the cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          «      None                ,

          Standard technologies eliminated because of cleanup goals include:

          •      None
   14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
  75.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

                 Time to design/construct/operate
                 Short-term risk


  16.     How are measures compared?

          RAA-5 and RAA-6, which include low-temperature thermal desorption and soil vapor
          extraction, would take approximately 2 to 3 years to remediate site soils, whereas RAA-3 and
          RAA-4, which only use soil  vapor extraction, would jequire 3 to 5 years. Short-term risks
        1  from RAA-5 and RAA-6, however, are higher than those associated with RAA-3 and RAA-4
          because excavation activities would increase VOCs and fugitive dust emissions.  Further,
          invasive excavation measures would impact ongoing manufacturing operations more than soil
          vapor extraction would, and excavation would expose remedial workers to a greater potential
          for physical injury relative to the less invasive soil vapor extraction.
                                                                                                '1
                                                                                                •<**&*
  17.
What technical considerations were factors in selecting, a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedy. In situ chemical treatment,
however, was eliminated because of the proximity of the underlying aquifer and uncertainty
regarding the clay layer thickness.
518
                                               -6-

-------
                      Charles Macon Lagoon & Drum Storage

                        Cordova, Richmond County, North Carolina
                                         Region 4
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
1/87
7/87
7/91
9/30/91
                                                                Background

                                                   PRP-lead         |
                                                   PRPs:  Dorothy Macon, Nicholas
                                                          Dockery, Sairfax Dockery, John
                                                          C. Dockery, C&M Oil
                                                          Distributors line., Crown Cork
                                                          and Seal Coj. Inc., Acme
                                                          Nameplate & Mfg., Inc., Carolina
                                                          Aluminum Ifroducts Distributing
                                                          Co., Clark Eiquiipment Co.
                                                   FS prepared by: Siirine Environmental
                                                          Consultants
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Subsurface Soils/Lagoon 7 (mg/kg)

       Tetrachloroethene (PCE)     31

       Subsurface Soils/Lagoon 10 (mg/kg)

       Acenaphthene                31
       Acenaphthylene              310
       Anthracene                  160
       Benzo(a)anthracene          150
       Benzo(a)pyrene              140
       Benzo(b)fluoranthene        120
       Benzo(k)fluoranthene        120
       Chrysene                   140
       Dibenzo(a,h)anthracene      30
       Fluoranthene                 200
       Fluorene                    250
       Ideno(l,2,3-cd)pyrene        47
       Naphthalene                 3,100
       Phenanthrene                 1,300
       Pyrene                      410
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      1,300 cubic yards of subsurface soil from Lagoon 7
       •      1,000 cubic yards of subsurface soil from Lagoon 10 including 930 tons of creosote


3.      What type of site is this?
        ...    \. .      •.  :              -                      '

       Waste Oil.  This site is a former oil recycling and antifreeze manufacturing facility in a
       predominantly agricultural setting. Four residences are within 100 yards of the site.
                                            -1-
                   519

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:

         Subsurface Soils/Lagoon 7 and 10

         Containment:          Capping, subsurface barriers (slurry walls, grouting, sheet piling),
                              container piles                                 .
         Chemical treatment:   Stabilization/solidification (cement-based, silicate-based, thermoplastic
                              microencapsulation), modified clay-based stabilization
         Thermal treatment:     Incineration (transportable, commercial)
        Disposal:              Landfilling (commercial, on-site)
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Subsurface Soils/Lagoon 7 and 10

        Biological treatment:   Land treatment (bioremediation), bioreactor, enhanced biodegradation
        Chemical treatment:    Supercritical carbon dioxide extraction, Basic Extraction Sludge
                              Treatment (BEST) process, oxidation, reduction, supercritical waiter
                              oxidation, soil washing, soil flushing
        Thermal treatment:     Low-temperature thermal separation, soil vapor extraction, vitrification
6.      What was the cost estimate for the innovative technology?

        During the initial screening process,  in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. '"The
        estimated costs then are recalculated during an evaluation based on nine criteria established bv
        the NCR

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
SC-3
Innovative Technology
Soil vapor extraction (Lagoon 7) and
capping (Lagoon 10)
Estimated Costs
3 Criteria
$680,000
9 Criteria
$1,000,000
520
                                              •2-

-------
Alternative
SC-4
SC-5
Innovative Technology
Soil vapor extraction (Lagoon 7}/
bioremediation and cap (Lagoon 10)
Soil vapor extraction (Lagoon 7) and
off-site 'disposal (Lagoon 10)
Estimated Costs
3 Criteria
$890,000
$6401,000
9 Criteria
$1,500,000
$520,000
7.      How did the cost(s) compare to standard technologies?              j
                                                                       •\
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)     |
Alternative
SC-1
SC-2
SC-6
Standard Technology
No action
Capping (Lagoons 7 and 10)
Off-site incineration
Estimated Costs
3 Criteria
$100,000
.$776,000
$6,700,000
9 Criteria
$190,000
$690,000
eliminated
       If a standard technology was chosen, why?

       A standard technology was not chosen.
        If an innovative* technology was chosen, why?                      .
                           •            ,"              '                  '          •    '     '
        The selected alternative (SC-4) involves the operation of a soil vapor extraction (SVE) system
        at Lagoon 7 to remove tetrachloroethene (PCE), and biological remediation of Lagoon 10
        wastes in a controlled cell.

        SVE was chosen because this treatment will significantly reduce chemicals that affect ground
        water quality above the identified ARARs. SVE would permanently ijeduee the volume of
        PCE in soils by more than 90 percent, based on a reduction of PCE fijom 31 mg/kg to the
        target cleanup level of 3 mg/kg.  This technology would address the sble risk to ground water
        posed by PCE-contaminated site soils. Also, the target cleanup level can be achieved using
        standard SVE design and construction practices.  Site conditions are appropriate for the
        application of SVE.  A Superfund Innovative Technology Evaluation (SITE) Program
        demonstration showed that SVE systems are effective in soils with permeabilities of 10"8 cm/s
        when the porosity is sufficient for application.  The site soil's permeability is approximately
        2.5 x 10"5 cm/s, and calculated actual and effective porosities at the site are approximately 40
        and 20 respectively, which would be sufficient for application of SVE',.  The process also has
        been used successfully for full-scale remediation in the Piedmont region.  Even though a
        permeability barrier would exist in the perched water zone beneath some portions of the site, a
        simple, or horizontal SVE design could be implemented for soils lying  above the perched
                                              -3-
                                                                                              521

-------
          water and SVE used in conjunction with passive air inlet wells could be used for soils below      ^^
          the perched aquifer. In addition, SVE could incidentally remove SVOCs as part of the           *^  \
          primary objective of VOG removal, even though SVOCs are not targeted for removal through          —<*,
          SVE. Removal would be effected either through enhanced biodegradation due to increased
          oxygen levels in the subsurface or through direct volatilization.  Installation of the SVE system
          at Lagoon 7 could proceed concurrently with biological treatment of the Lagoon 10 soils.                  ;

          Bioremediation (land treatment) was chosen because its effectiveness on Lagoon 10
          contaminants has been demonstrated under a variety of environmental conditions and soil
          types. Previous studies have reported 80- to 90-percent removal of these compounds in fewer              i.
          than  4 months of treatment. This technology has been demonstrated at other sites and has
          been selected to treat similar compounds at other Region 4 sites. In 1983, biological treatment
          (landfarming) of site contaminants was conducted by EPA during an intermediate removal
          action. The data indicate that bioremediation of residuals in Lagoon 10 would also be
          successful. In addition, this technology was selected because Lagoon 10 wastes will be
          permanently destroyed and bioremediation would satisfy the Superfund Amendments and
          Reauthorization Act's  (SARA) preference for alternatives involving treatment. Also, land        <
          treatment can effectively treat Lagoon 10 wastes and maintain positive containment of
          relatively mobile intermediates, in contrast to enhanced biodegradation, which was eliminated
          from consideration because of its potential to produce vinyl chloride from PCE.                           -!


  10.     If an innovative technology was not chosen, why not? At what stage was the innovative                   ';
          technology eliminated?                                                               '

                                                               '              ..'•     "          '
          Innovative technologies could  be  eliminated from the remedial technology selection process at
          three stages: during the initial screening; during the screening of the three criteria of
          effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                                                             • I
          Innovative technologies eliminated during the initial screening include the following:

          •      Bioreactor wasi eliminated based on effectiveness and cost.  Monitoring and
                 maintenance requirements are far greater for bioreactors adding significantly to the
                 cost. Sizing requirements could effect the implementability of this technology when
                 applied to Lagoon 10 wastes. The FS referenced two sources of information, ECOVA
                 Corp., 1991, and EPA/540/2-88/004 (Technology Screening Guide for Treatment of
                 CERCLA Soils and Sludges), Sept. 1988, during the evaluation of this technology.
          •      Supercritical carbon dioxide extraction was eliminated because, according to an EPA
                 study, this technology  gives poor recoveries  of adsorbed organics from activated
                 carbon and synthetic resins (B.W. Wright, et al., 1986).  Also another EPA study
                 found that this  process removes greater than 40 percent of only 4 of the 23 organic
                 compounds tested (Ehntholt, D.J., 1985). Although pilot tests have been conducted
                 with this type of technology,  no full-scale operations have been applied.
          •     BEST processjwas eliminated because it would not be as cost-effective as other
                treatment alternatives, when used to treat limited volumes of soil. Only limited                    '"••
                volumes of Lagoon 10 soil need to be treated (Resource Conservation Company,                  . •:
                 1991).  The FS referenced material from EPA/540/2-88/004 during the evaluation of
                this technology.                                           -                      ,
          •     Oxidation was  eliminated  because this technology would be better suited for water         4jh   v
                than soil. The  solids in a soil slurry would interfere with the UV/hydrogen peroxide       ^P'   /
                or ozone reaction, thereby rendering this technology ineffective.

522   '      •                 .    .    •       '            •'•.          •     "   ;'    .    •    •;       •      .••;

-------
      •      Reduction was eliminated because of the limited number of site contaminants
            , addressed by the process and the lack of full-scale operation.
      •      Supercritical water oxidation was eliminated because the effectiveness of this
             technology on soils is not sufficiently demonstrated.  The FS refers to the MODAR
             system and emphasizes that a full-scale MODAR system has jnot yet been built.
      •      Soil washing was eliminated because site soils have an appreciable silt and clay
             content (approximately  50 percent), which would hinder the contaminant contact and
             mass transfer properties of surfactant solutions.  Soil washing was determined to be
             ineffective at a Michigan Superfund site for compounds with j similar or greater
             solubilities than at this  site.                     ,
      •      Low-temperature thermal separation technologies (LTTA, X'jTrax, LT3) were
             eliminated because they would not be effective for the removal of a number of the
             chemical residuals from Lagoon 10 soils based on the boiling points of these residuals
             and system operating temperatures.  Shortage of full-scale uniits makes it technically
             and economically unfeasible to mobilize a unit to a site unless there is at least 10,000
             cubic yards of material; only 1,300 cubic yards need to be treated at Lagoon 7.
      •      Enhanced biodegradation was eliminated because the potential of producing vinyl
             chloride from PCE precludes the use of this technology at Lagoon 7.
      •      Soil flushing was eliminated because of the concern that mobilized contaminants would
             not be recovered completely by the extraction system and therefore could affect ground
             water conditions.  Site  soil permeabilities are generally low sind somewhat variable
              making remediation to  an acceptable level  difficult. Furthermore, many of the site's
              compounds have high 'octanol-water coefficients, making thep difficult to remove  from
              soils.      ,  .                      '                    i         .
       •      Vitrification was eliminated because the site's soil moisture content would limit the
              effectiveness of this technology. Site soils are generally composed of a clay-silt-sand
              mixture. Since clays are very porous and aggressively retain water, soil moisture
              conditions at the site are a concern. Soil moisture content also is a concern in soils
              overlying a shallow perched water table. The moisture contained in the perched water
              table would inhibit soil vitrification at lower depths.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None                                 .      . .           ;                .     '  •

       Innovative technologies eliminated during the detailed analysis include the following:
                                         :       '•                      'i
       »•     None       •'•-.'•.                '               '       I    '   .    •
11.     Which of the' nine criteria were weighted most heavily in. selecting the technology?  Did failure
       •to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Subsurface Soils  '  i                                          -         .
                                                                      I

       The most heavily weighted criteria in selecting SC-4 were long-term effectiveness and
       permanence, and reduction of toxicity, mobility, or volume of contaminants of concern.  The
       migration of Lagoon 7 PCE to ground water would be permanently [controlled by capping (SC-
       2) or by SVE (SC-3, SC-4, and SC-5). While capping would greatly reduce the mobility and
                                               -5-
523

-------
        effective toxicity of contaminants in site soils, it would not reduce the volume of these
        com-minants.  SVE would permanently reduce the volume and mobility of site contaminants
        that could contaminate ground water above cleanup levels.  Bioremediation would effect a
        permanent but undetermined reduction in the volume of Lagoon 10 contaminants.
 12.
  What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR? What risk level was selected to establish cleanup goals?

        Subsurface Soils/Lagoon 7
                      Contaminant
                                    Cleanup Level (ppm)
                                                                  ARAR or Other Basis
                 Carcinogens
                 Tetrachloroethene (PCE)
                                             3.0
Model3
               "Cleanup level is based on a compound's potential effect on ground water. Chemical
               concentrations in subsurface soils that are protective of ground water were developed
               using the Vadose Zone Interactive Process (VIP) model.

               Subsurface Soils/Lagoon 10
                      Contaminant
                                    Cleanup Level (ppm)
                                                                  ARAR or Other Basis
                Carcinogens
                Benz(a)anthracene
                Benzo(a)pyrene
                Benzo(b)fluoranthene
                Benzo(k)fluoranthene
                Chrysene
                Dibenz(a,h)anthracene
                Idenopyrene
                                            2.0
                                          (Total)
Riskb
              "For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
              to 10  was acceptable.
13.
 Was the innovative technology eliminated because of the cleanup goals? Could the standard
 technology meet the cleanup goals?             "

 Innovative technologies eliminated because of cleanup goals include:

 »     None

Standard technologies eliminated because of cleanup goals include:

•      None           ..                                   ,
524
                                            -6-

-------
14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability study was conducted.  A treatability study was proposed, however, for the
       chosen bioremediation technology in the FS and the ROD to determine if the indigenous
       microbial population is capable of degrading the contaminants in Lagoon 10.

                                                                        i
                                                                  ''!'••'=''
75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:    .  |

             Cost/risk
             Proven reliability
             Single vs. multistep treatment
       -     Preference for treatment (vs. containment)

                                       •              •                      '
16.    How are measures compared?                                    I
                  '           •  •          '      '              '           i
       Although the selected remedy is the highest cost alternative, it is prel;erred because it provides
       a greater reduction in  risk.  SVE was chosen because, according to a SITE program
       demonstration, this technology is effective in soils with permeabilities and porosity similar to
       the site soils (Stinson, 1989). Also, SVE has  been successful in full-scale remediation projects
       in the Piedmont region (Vicellon facility, Fountain Inn, SC). Bioremjediation was  chosen
       because it had been demonstrated effective on Lagoon 10 contaminants Hinder various
       environmental conditions and soil types.  Previous studies have reported 80- to 90-percent
       removal of these specific compounds in less than 4 months of treatment (Mahaffey et al.
        1990). Using SVE and bioremediation would satisfy SARA'S preference for remedial  actions
       that involve treatment as a principal element.                                      '...'.

        Subsurface soil chemjcal concentrations that are protective of ground water were developed for
        this site using the Vadose Zone Interactive Processes (VIP) model.  !
                                 :          '    •.      ".'  •-    ••         ".i      •          '   ,  '•  '

 17.     What technical considerations were factors in selecting a remedy? Were technical  ,
        considerations primary in the selection of the remedy?                      ,

        Technical considerations were primary in selecting a remedy.
                                      •'                                  i  ' i     ••••',
        SVE was selected because soil permeability and porosity at the site are appropriate for the
        implementation of this technology. Site soils also were instrumental in eliminating several
        innovative technologies from further review.  Site soils have an appreciable silt and  clay
        content (approximately 50 percent), precluding the use  of soil washing as a treatment
        technology.  Also, site soil permeabilities are generally low and somewhat variable—a factor
        in eliminating soil flushing from consideration.  This site's soils are generally composed of a
        clay-silt-sand mixture, which is very porous and aggressively retains [water, and these soils are
        overlying a shallow perched water table. These soil moisture conditions were the primary
        consideration in eliminating in situ vitrification.
                                                                                                   52

-------
References:
       Ehntholt, D.J.  1985.  "Isolation and Concentration of Organic Substances from Water—An
       Evaluation of Supercritical Fluid Extraction."  U.S. EPA Project Summary  EPA-600/51-84-
       028.


       U.S. EPA.  1988. Technology Screening Guide for Treatment of CERCLA Soils and Sludges
       EPA/540/2-88/004, p. 63.


       Wright, B.W. and R.D. Smith.  1986.  "Supercritical Fluid Extraction of Paniculate and
       Absorbent Materials." U.S. EPA. EPA/600/54-86/017.
526
                                          -8-

-------
                          Ciba-Geigy Corp. (Mclntosh Plant)
                                          OU-2
                               .            ;
                                    Mclntosh, Alabama
                                         Region 4
GENERAL SITE INFORMATION

1.      What -were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Surface and Subsurface Soil (mg/kg)

       DDT                3,780
       DDD                8,590
       DDE                8,410
       AIpha-BHC          4,370
       Beta-BHC           751
       Delta-BHC          315
       Gamma-BHC        753
       Chlorobenzilate      650
       Diazinon            786
       Chloroform  <         16,600
       Toluene     .        6,360
       Benzene             5,650
       Chlorobenzene        414
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A,
9/83
1/90
9/30/91
             Background

PRP-lead
PRPs:  Ciba-Geigy [Corp.
FS prepared by: BCM Engineers Inc.
2.      What volume of material is to be remediated?             -                        '••     '
                                                                    j -    '
      , The volume of material to be remediated included:            .'!.',
                                                                    I
       •      65,000 cubic yards of highly contaminated soil and sludge
       •      62,300 cubic yards of moderately contaminated soil and sludge


3.      What type of site is this?                                        !

       Chemicals and Allied Products. An active chemical manufacturing cojnpany that has produced
       products such as pesticides, agricultural chelating agents, industrial secjuestering agents,
       laundry brighteners, plastics resins, and antioxidants.  Located in an industrial setting, OU-2
       consists of 18 former waste management areas.                                         •
                                            -1-
                                                                                         527

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:

        Chemical treatment:
        Physical treatment:


        Thermal treatment:
        Disposal:
Land use restrictions, fencing                                      :
Capping (soil, clay, synthetic membrane, asphalt, concrete, multilayer,
single layer), slurry wall (soil bentonite, cement bentonite)
Fixation/stabilization (Hazcon)
Stabilization (portland cement pozzolan), debris removal, screening
(vibratory, grizzly), crushing/grinding (hammermill), blending/mixing
(pugmill), magnetic separation              -
Incineration (rotary kiln, liquid injection, fluidized bed)
Excavation, on-site disposal
        Other standard technologies were listed.in the appendix but not referred to in the main FS text.
        Therefore, they are not represented in this list.
                                                                            J:
5.      Was an innovative'technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Biodegradation, bioslurry
        Chemical treatment:   Solvent extraction

        Many innovative technologies presented in the appendix were not mentioned in the main FS
        text and are not included in this list.  These technologies'were not incorporated into any RAAs
        and their elimination was not explained.
                                                                       ill
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify, costs. After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
       estimated costs then are recalculated during an evaluation based on nine criteria established by
       the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
       ARARs; protectiveness of human health and the environment; reduction in contaminant
       mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
       community acceptance.
                                         *•*                    -                         .
       Tables are provided for each of the 18 sites.  The RAAs were consolidated in the Proposed
       Plan and ROD and  are presented in separate  tables following the cost estimates provided for
       the three-criteria and nine-criteria screenings.


  528

-------
        Cost Estimates for RAAs That Include Innovative Technologies
                   (selected remedial alternative is in bold)     ;
Site 1
Alternative
RAA-7

Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/multilayer cap
Estimated Costs
3 Ciiteria
$5,047,000
9 Criteria
eliminated
Site 2 ''•';. ' ' . ,
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/multilayer cap
Estimated Costs
3 Criteria
$2,759,000
i
9 Criteria
eliminated
Site 3A '..• ^ ....-•
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
"returned to site/synthetic membrane. cap
Estimated Costs
3 Criteria
$3,568,000
"i
9 Criteria
eliminated
 Site 3B
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction prbcess/incinerate/ash .
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$1,609,000
: 1 •
• •
, 1
.;
i '
9 Criteria
eliminated
                                                                               529

-------
      Site 3C
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$3,983,000
9 Criteria
eliminated
      Site 3D
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/ synthetic membrane cap
Estimated Costs
3 Criteria
$1,953,000
9 Criteria
eliminated
      Site 3 General
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$19,261,000
9 Criteria
eliminated
                                                                                  b:
      Site 4A
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$714,000
9 Criteria
eliminated
' ~i
530
                                    -4-

-------
Site 4B
Alternative
RAA-7
RAA-8

Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/
treated soil returned to site/synthetic
membrane cap
Excavate/grizzly screen, shredder,
vibratory screen/incinerate solids/
hammermill, magnetic separator/
bioslurry/synthetic membrane cap .
Estimated Costs
3 Criteria
$5815,000
$563,000
9 Criteria
eliminated
eliminated
Site4C
, •• . • ' . i . . •
Alternative
RAA-7
RAA-8
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Excavate/grizzly screen, shredder,
vibratory screen/incinerate solids/crush,
magnetic separator/bioslurry/synthetic
membrane cap
Estimated Costs
3 Criteria
$800,00
$642,000
1" . •
9 Criteria
eliminated
eliminated
Site 5 , . ] '-.-.-
Alternative
RAA-7
Innovative Technology
Slurry wall/excavation/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
. returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$5,984,000
'i.
9 Criteria
eliminated
                          -5-
                                                         531

-------
     Site 6
Alternative
RAA-7
RAA-8
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Excavate/grizzly screen, shredder,
vibratory screen/incinerate solids/crush,
magnetic separator/bioslurry/synthetic
membrane cap
Estimated Costs
3 Criteria
$8,199,000
$7,394,000
9 Criteria
eliminated
eliminated
     Site?
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$8,001,000
9 Criteria
eliminated
     Site 9
Alternative
RAA-7
Innovative Technology
Slurry wall/excavate/remove debris/
screen, crush, magnetic separator/
solvent extraction process/incinerate/ash
disposal in RMP land vault/treated soil
returned to site/synthetic membrane cap
Estimated Costs
3 Criteria
$13,311,000
9 Criteria
eliminated
532

-------
      Proposed Plan and ROD for All Sites
Alternative
RAA-5













Innovative Technology
Excavate soil and sludge/remove
debris/possibly pretreat soil with
solvent extraction or low tempera-
ture thermal desorption or critical
fluid injection/incinerate soils with
high levels of contamination/
stabilization-solidification and
possible dechlorination of soils with
low level contamination/dispose ash
and solidified materials in RCRA
land vault/if cleanup levels are not
reached following excavation of 20
feet, in situ soil flushing, vacuum
extraction, or bioremediation
Estimated Costs
PP
Not proposed
in 7/30/90 PP
1
• ' _

i
i •
i.
i
•
f

i .
i
'
.
ROD
$94,000,000
to
$120,250,000






i


, •

7.     How did the cost(s) compare to standard technologies?
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Site 1 ' '
Alternative
RAA-1
RAA-2
RAA-3
V
RAA-4
RAA-5
Standard Technology
No action
Slurry wall/excavate/stabilization/
multilayer cap ,
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/ash
disposal in RMP land vault/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/stabilization/
disposal in on-site RPM land vault/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/fixation/
place fixed material into on-site RPM
land vault
Estimated Costs
3 Criteria
N/A
$1,920,000
$4,442,000
$3,(|98,000
L " i '
$5,216,1300
9 Criteria
$0
$1,920,000
eliminated
$3,098,000
eliminated
                                          -7-
533

-------
Alternative
RAA-6
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic
separator/incinerate/multilayer cap
Slurry wall/excavate soil/debris
removed/screen, shred, crush/incinera-
tion solids/soil fixation/return fixed soil
to site/multilayer cap/excavate sludge/
remove debris/screen, shred, crush,
magnetic separator/incinerate sludge/
disposal of ash on-site in RPM land
vault
Slurry wall/excavate sludge/remove
debris/screen, shred, crush, magnetic
separator/incinerate sludge/ash disposal
in RMP land vault/excavate soil/stabil-
ization/place in RMP land vault/
multilayer cap
omitted
Excavate sludge/remove debris/screen,
shred, crush, magnetic separator/
incinerate/disposal of ash in on-site
RMP land vault/excavate soil/stabilize/
place in RMP land vault
Estimated Costs
3 Criteria
$9,610,000
.$6,901,000
$5,887,000
omitted
N/A
9 Criteria
eliminated
eliminated
$5,887,000
omitted
$11,029,000
  Site 2
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action
Slurry wall/excavate/stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/disposal in on-site
RPM land vault/multilayer cap
Estimated Costs
3 Criteria
N/A
$1,027,000
$1,713,000
$1,418,000
9 Criteria
$0
$1,027,000
eliminated
$1,418,000
                                                       ';}
534

-------
Alternative
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excayate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/multilayer cap
Slurry wall/excavate soil waste/debris
removed/screen, shred, crash/ incinerate/
soil fixation/return fixed soil to site/
multilayer cap/excavate solid waste/
remove debris/screen, shred, crash,
magnetic separator/ incinerate/dispose
ash on-site in RPM land vault
Slurry wall/excavate solid waste/remove
debris/screen, shred, crash, magnetic
separator/incinerate/ash disposal in RMP
land vault/excavate soil/remove debris/
stabilization/place in RMP land vault/
multilayer cap
omitted
Excavate sludge/remove debris/screen,
shred, crash, magnetic separator/
incineration/dispose ash in on-site RMP .
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$1,986,00
j
$3,436,000
•j
r
$2,383,000
I
1
1 '"'
l
-. , «!'
I
$2,525,000
!'
omitted
N/A
-
l
1
9 Criteria
eliminated
eliminated
eliminated
$2,525,000
omitted
$1,280,000
Site 3A
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Slurry wall/excavate/stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crash/incinerate/fixation/
return fixed material to site/multilayer
cap
Estimated Costs
3 Criteria
N/A :
$9^1, 000
$2,067,000
1 ..
9 Criteria
$0
$951,000
eliminated
                         -9-
535

-------
Alternative
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred, blend/stabilization/dispose
in on-site RPM land vault/synthetic
membrane cap/incinerate debris
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/debris
removed/screen, shred, crash/incinerate
solids/soil fixation/return fixed soil to
site/multilayer cap/excavate sludge/
remove debris/screen, shred, crush,
magnetic separator/incinerate sludge/
dispose of ash on-site in RPM land
vault
Slurry wall/excavate solid waste/remove
debris/screen, shred, crush, magnetic
separator/incinerate/ash disposal in RMP
land vault/excavate soil/stabilization/
place in RMP land vault/synthetic
membrane cap
omitted
Excavate sludge/remove debris/screen,
shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$1,608,000
$2,518,000
$4,912,000
$3,783,000
$2,913,000
omitted
N/A
9 Criteria
$1,608,000
• (
eliminated
eliminated
eliminated
$2,913,000
omitted
$2,383,000
    Site 3B
Alternative
RAA-1
RAA-2
Standard Technology
No action
Slurry wall/excavate/stabilization/
multilayer cap
Estimated Costs
3 Criteria
N/A
$785,000
9 Criteria
$0
$785,000
536
-10-

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization /dispose in on-site
RPM land vault/incinerate debris/
synthetic membrane cap
Slurry wall/excavate/remove debris/ ,
screen, shred, crush/incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/debris
removed/screen, shred, crush/incinerate
solids/soil fixation/return fixed soil to
site/multilayer cap/excavate solid waste/
removed debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash on-site in RPM land Vault
Slurry wall/excavate solid waste/remove
debris/screen, shred, crush, magnetic
separator/incinerate/ash disposal in RMP
land vault/excavate soil/stabilization/
place in RMP land vault
omitted
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$1,686,000
$1,319,000
$2,017,000
$3,774,000
$3,039,000
$2,590,000
omitted
k/A
9 Criteria
eliminated
$1,319,000
eliminated
eliminated
eliminated
$2,590,000
omitted
$4,456,000
Site 3C

Alternative
RAA-1
i
Standard Technology
No action
,

Estimated Costs
3 Criteria
N/A
9 Criteria
$0
                         -11-
                                                          537

-------
Alternative
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-1 1
Standard Technology
Slurry wall/excavate/ stabilization/
multilayer cap
Slurry wall/excavation/remove debris/
screen, shred, crush/incinerate/ fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavation/screen, shred,
blend/stabilization/disposal in on-site
RPM land vault/synthetic membrane
cap/incinerate debris
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/multilayer cap
Slurry wall/excavate soil/remove debris/
screen, shred, crush/incinerate solids/soil
fixation/return fixed soil to site/
multilayer cap/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash on-site in RPM land vault
Slurry wall/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/ash
disposal in RMP land vault/excavate
soil/stabilization/place in RMP land
vault/synthetic membrane cap
omitted
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$869,000
$2,214,000
$1,650,000
$2,723,000
$5,425,000
$3,935,000
$3,062,000
omitted
N/A
9 Criteria
$869,000
eliminated
$1,650,000
eliminated
eliminated
eliminated
$3,062,000
omitted ||
$2,215,000
538
                         -12-

-------
Site 3D
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-1 1
Standard Technology
No action
Slurry wall/excavate/ stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap/incinerate debris
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/ fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/remove debris/
screen, shred, crush/ incinerate solids/
soil fixation/return fixed soil to site/
multilayer cap/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate solid
waste/dispose ash on site in RPM land
vault
Slurry wall/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/ash
disposal in RMP land vault/excavate
soil/stabilization/place in RMP land
vault/synthetic membrane cap
omitted
Excavate sludge/remove debris/screen,
shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
I Estimated Costs
3 Criteria
N/A
$438,000
$1,150,000
$877,000
.$1,395,000
•' " r
$2,637,000
$1,789,000
$1,4181,000
omitted
K/A
' , -13-, ' -
9 Criteria
$0
$438,000
eliminated
$877,000
eliminated
eliminated
eliminated
, $1,481,000
omitted „
$2,055,000
======
,....:. c
539

-------
    Site 3E
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8
RAA-9
RAA-1 0
RAA-1 1
Standard Technology
No action
Slurry wall/excavate/ stabilization/
multilayer cap
Slurry wall/excavate/remoye debris/
screen, shred, cnish/incinerate/ fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap/incinerate debris
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/synthetic membrane cap
Slurry wall/excavate/remove debris/
incinerate/ash disposal in RMP land
vault/treated soil returned to site/
multilayer cap
Slurry wall/excavate soil/remove debris/
screen, shred, crush/incinerate solids/
stabilize soil/dispose in RMP land vault/
excavate solid waste/ remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash on site in RPM
land vault
omitted
omitted
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
N/A
$1,439,000
$3,288,000
$2,373,000
$4,023,000
$7,925,000
$6,393,000
$4,621,000
omitted
omitted
N/A
9 Criteria
$0 .....
$1,439,000
eliminated
$2,373,000
eliminated
eliminated .
eliminated
$4,621,000
omitted
omitted
$4,428,000
540
                              -J4-

-------
Site 3 General
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-1 1
Standard Technology
No action
Slurry wall/excavate/ stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/ fixation/
return fixed material to site/multilayer
cap ,
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/ fixation/
place fixed material into, on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/ash disposal in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/debris
removed/screen, shred, crush/ incinerate
solids/soil fixation/ return fixed soil to
site/multilayer cap/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/inciherate/dispose
ash on site in RPM land vault
Slurry wall/excavate solid waste/remove
debris/screen, shred, crush, magnetic
separator/incinerate/dispose ash in RMP
land vault/excavate soil/stabilization/
place in RMP land vault/synthetic
membrane cap
omitted
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP I?K! vault
Estimated Costs
3 Ciriteiria
N/A
$6,085,000.
$13,080,000
$10,000,000
$16,2126,000
i ••
$27398,000
$23,2121,000
i
$19,167,000
i.
omitted
N^A
9 Criteria
$0
$6,085,000
eliminated
$10,000,000
eliminated
eliminated
eliminated
$19,167,000
omitted
$18,485,000
' :
f -
•• •/ . • . I5-. ' •- • ,'• • ; • -5
                                                             541

-------
 Site 4A
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-1 1

Standard Technology
No action
Slurry wall/excavate/stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incineration/
fixation/return fixed material to site/
multilayer cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/remove debris/
screen, shred, crush/incinerate solids/soil
fixation/return fixed soil to site/
multilayer cap/excavate sludge/remove
debris/screen, shred, crush, magnetic
separator/incinerate sludge/dispose ash
on site in RPM land vault
Slurry wall/excavate sludge/remove
debris/screen, shred, crush, magnetic
separator/incinerate sludge/dispose ash
in RMP land vault/excavate soil/stabil-
ization/place in RMP land vault/
multilayer cap
omitted
Excavate sludge/remove debris/screen, ,
shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
N/A
$473,000 .
$599,000
$509,000
$640,000
$860,000
$494,000
$466,000 ,
omitted
N/A
9 Criteria
$0
$473,000
eliminated
$509,000
eliminated
eliminated
eliminated
$466,000
omitted
$1,019,000
542

-------
Site 4B
Alternative
RAA-1
RAA-2
> - .
RAA-3
RAA-4
RAA-5
RAA-6
RAA-9
RAA-10
s
RAA-1 1
Standard Technology
No action
Slurry wall/excavate/ stabilization/ '
multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/ fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash in RMP land vault/excavate soil/
fixation/place in RMP land vault/
multilayer cap
Excavate/remove debris/incinerate solid
w^ste/dispose ash in RMP land vault/ .
stabilize soil/place in RMP land vault/
synthetic membrane cap
Excavate sludge/remove debris/screen,
shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabiiize/place
in RMP land vault
Estimated Costs
, 3 Criteria
N/A
, $505,000
$594,000
$490,000
$561,000
$627,000
$609,000
N/A
N/A
9 Criteria
$0
$505,000
eliminated
$490,000
eliminated
eliminated
eliminated
$558,000
$1,525,000
                         -17-
543

-------
     Site 4C
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-9
RAA-10
RAA-1 1
Standard Technology
No action
Slurry wall/excavate/ stabilization/
multilayer cap
Slurry wall/excavate/remove debris/
screen, shredu crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap/incinerate debris
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate solid waste/remove
debris/screen, shred, crush, magnetic
separator/incinerate/dispose ash in RMP
land vault/excavate soil/fixation/ .
multilayer cap
omitted
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
N/A
$539,000
$672,000
$580,000
$720,000
$960,000
,$882,000
$822,000
* N/A
9 Criteria
$0
$539,000
eliminated
$580,000
eliminated
eliminated
$822,000
eliminated
$1,099,000
    SiteS
Alternative
RAA-1
RAA-2
Standard Technology
No action >
Slurry wall/excavate/ stabilization/
multilayer cap ',
Estimated Costs
3 Criteria
,N/A
$2,062,000
9 Criteria
'. $0
$2,062,000
544
-18-

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
I
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred,, crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/remove debris/
screen, shred, crush/incinerate solids/soil
fixation/return fixed soil to site/
multilayer cap/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash on site in RPM land vault
Slurry wall/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash in RMP land vault/excavate soil/
stabilization/place in RMP land vault
omitted
Excavate solid waste/remove debris/ -'
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$3,930,000
$2,578,000
$4,548,000
$7,825,000
$6,712,000
$5,310,000
omifted
N/A
9 Criteria
eliminated
$2,578,000
eliminated
eliminated
eliminated
$5,310,000
omitted
$6,377,000
Site 6 . • ,
Alternative
RAA-1

Standard Technology
No action
? -19-
Estimated Costs
3 Criteria
N/A
9 Criteria
$0
' • • , ' ' ' • '
545

-------
Alternative
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-9 -
RAA-10
RAA-11

Standard Technology
Slurry wall/excavate/ stabilization/
multilayer cap ,
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/ fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate sludge/remove
debris/screen, shred, crush, magnetic
separator/incinerate sludge/dispose ash
in RMP land vault/excavate soil/
stabilization/place in RMP land vault
Excavate/remove debris/incinerate solid
waste/dispose ash in RMP land vault/
stabilize soil/place in RMP land vault/
synthetic membrane cap
Excavate solid waste/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
Estimated Costs
3 Criteria
$1,877,000
$5,666,000
$3,708,000
$7,129,000
$14,767,000
$11,793,000
$10,893,000
N/A
9 Criteria
$1,877,000
eliminated
$3,708,000
eliminated
eliminated
eliminated
$10,893,000
$8,705,000
   Site?
Alternative
RAA-1
RAA-2
Standard Technology
No action
Slurry wall/excavate/ stabilization/
multilayer cap
Estimated Costs '
3 Criteria
N/A
$1,251,000
9 Criteria
$0
$1,251,000
546
-20-

-------
Alternative
RAA-3
RAA^4
RAA-5
RAA-6
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/fixation/
return fixed material to site/multilayer
cap - • •
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/synthetic membrane
cap
Slurry wall/excavate/remoye debris/
screen, shred, crush/ incinerate/fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crash, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Slurry wall/excavate soil/debris
removed/screen, shred, crash/incinerate
solids/soil fixation/return fixed soil to
site/multilayer cap/excavate solid waste/
remove debris/screen, shred, crash,
magnetic separator/incinerate/dispose
ash on site in RPM land vault
Slurry wall/excavate solid waste/
remove debris/screen, shred, crush,
magnetic separator/incinerate/dispose
ash in RMP land vault/excavate
soil/stabilization/place in RMP land «
vault/multilayer cap
omitted
Excavate solid waste/remove debris/
screen, shred, crash, magnetic separator/
incinerate/dispose ash in on-site RMP
land vault/excavate soil/stabilize/place
in RMP land vault
'Estimated Costs |
3 Criteria
$4,649,000
$3,023,000
$5,876,000
$12,384,000
$10,471,000
$9,52(5,000
omitted
N/A
9 Criteria
eliminated
$3,023,000
eliminated
eliminated
. eliminated
$9,526,000
omitted ||
$6,581,000
Site 8 .-:'.-•
• • • . > • " •
Alternative
RAA-1 •

Standard Technology
No action
Estimated Costs
3 Criteria
N/A
9 Criteria
$0
-21-
547

-------
Alternative
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
Standard Technology _
Slurry wall/excavate/
stabilization/multilayer cap
Slurry wall/excavate/remove debris/
screen, shred, crush/ incinerate/fixation/
return fixed material to site/multilayer
cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/multilayer cap - . .
Slurry wall/excavate/fixation/multilayer
cap
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/multilayer cap
Estimated Costs
3 Criteria
$10,100,000
$38,801,000
$28,078,000
$35,542,000
$31,749,000
9 Criteria
$10,100,000
eliminated •
$28,078,000
eliminated
eliminated
  Site 9
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6

Standard Technology
No action
Slurry wall/multilayer cap
Slurry wall/remove structures/ excavate/
remove debris /screen, shred, crush/
incinerate/fixation/return fixed material
to site/multilayer cap
Slurry wall/remove structures/ excavate/
screen, shred, blend/ stabilization/
dispose in on-site RPM land vault/
synthetic membrane
Slurry wall/excavate/remove debris/
screen, shred, crush/incinerate/ fixation/
place fixed material into on-site RPM
land vault
Slurry wall/excavate/remove debris/
screen, shred, crush, magnetic separator/
incinerate/dispose ash in RMP land
vault/synthetic membrane cap
Estimated Costs
3 Criteria
N/A
$2,594,000
$11,806,000
$4,994,000
$13,122,000
$25,717,000
9 Criteria
$6
$2,594,000
eliminated
$4,994,000
eliminated
eliminated
                                                               *
548
                            -22-

-------
    Alternative
   RAA-8
   RAA-9
  RAA-10
  RAA-11
         Standard Technology
 Slurry wall/excavate soil/debris
 removed/screen, shred, crush/incinerate
 solids/soil fixation/return fixed soil to
 site/multilayer cap/excavate solid
 waste/remove debris/screen, shred,
 crush, magnetic separator/incinerate/
 dispose ash on site in RPM land vault
 Slurry wall/excavate solid waste/
 remove debris/screen, shred, crush,
 magnetic separator/incinerate/dispose
 ash in RMP land vault/excavate soil/
 stabilization/place in RMP land vault
 omitted
 Excavate sludge/remove debris/screen,
 shred, crush, magnetic separator/
 incinerate/dispose ash in on-site RMP
 land vault/excavate soil/stabilize/place
 in RMP land vault
Site 10
    Alternative
  RAA-1
  RAA-2
  RAA-3
  RAA-4
         Standard Technology
No action
Slurry wall/remove buildings and slab/
concrete cap
Remove buildings and slab/fixation/
replace buildings and slab
Remove buildings and slab/slurry wall/
excavate/incinerate/dispose in on-site
RPM land vault/concrete cap
Site 11
   Alternative
  RAA-1
  RAA-2
        Standard Technology
No action
Remove slab and fence/clay wall/
backfill/concrete cap

                   -23-
                                                                 Estimated Costs
                                                             3 Criteria
                                                            $12,747,000
                                                            $8,719,000
                                                             omitted
                                                               N/A
 9 Criteria
 eliminated
 $8,719,000
                                                          omitted
$21,171,000
                                                                Estimated Costs
                                                            3 Criteria
                                                              N/A
                                                            $423,000
                                                            $799,000
                                                           $1,694,000
 9 Criteria
                                                            $0
 $423,000
 $500,000
eliminated
                                                               Estimated Costs
                                                           3 Criteria
                                                              N/A
                                                            $746,000
9 Criteria
                                                            $0
 $746,000
                                                                                     549

-------
Alternative
RAA-3
RAA-4
Standard Technology
Remove slab and fence/clay wall/
excavate/remove debris/screen, shred, .
crush/incinerate/fixation/return fixed
material to site/concrete cap
Slurry wall/excavate/screen, shred,
blend/stabilization/dispose in on-site
RPM land vault/concrete cap/fencing
Estimated Costs
3 Criteria
$2,139,000
$944,000
9 Criteria
eliminated
$944,000
       Proposed Plan and ROD
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action .
Slurry wall/multilayer RCRA cap
Excavate soil and sludge/stabilization
and solidification/dispose on site in
land vault
Excavate soil and sludge/remove
debris/incinerate soils with high levels
of contamination/stabilization-
solidification soils with low level
contamination/dispose ash and solid-
ified materials in RCRA land vault
Estimated Costs
PP
$0
$23,404,000
$66,648,000
$95,000,000
to
$131,677,000
ROD
$0
$23,400,000
$41:250,000
. $90,000,000
to
$116,250,000
                                                                                                *:>.
8.      If a standard technology was chosen, why?

       A standard technology was not chosen.


9.      If an innovative technology was chosen, why?

       RAA-5 was chosen because it was the most comprehensive and protective option. It proposes
       the potential use of several innovative technologies. Four innovative technologies will be
       tested during the design phase to determine their effectiveness in pretreating the waste to
       enhance the efficiency of thermal treatment and solidification-stabilization or to replace these
       standard technologies.  Furthermore, several innovative in situ technologies will be tested and,
       if proven effective, used to remediate soil below 20 feet.  This alternative provided the greatest
       protection to human health and,the environment because it addressed both the excavated  soil
       and the underlying soil. Soils below 20 feet that did not meet cleanup criteria were  considered
       important because they could contaminate ground water. This alternative provides the most
       immediate response to removing contaminants closest to ground water.  In addition, this was
 550
                                             -24-

-------
       the only alternative that proposed treatment for contaminated soil belov^ 20 feet.  The chosen
       alternative also was preferred because it proposed incineration, a technology that has been
       demonstrated effective in destroying site contaminants. Therefore, incineration ensures the
       permanent reduction of contaminant toxicity, mobility, and volume and will substantially
       reduce risk over the long term. Furthermore, incineration ensures that RCRA hazardous waste
       regulations will be met.  New equipment might be designed  and constructed to meet thermal
       treatment capacity needs.

       The FS proposed approximately 10 RAAs for each of the 18 sites.  The preferred alternative
       for 1-7 sites included thermal treatment.  In the FS, containment was preferred for one site (Site
       8).  In the ROD, this site was deferred by EPA and will be addressed u) a future operable unit.
                                                                          i            ''
                                                                          i
       The original  Proposed Plan (6/30/90) identified nine RAAs, of which fiye were eliminated in
       the Amended Proposed Plan due to their similarities.  The preferred alternative in the
       Amended Proposed Plan was thermal treatment.  Following a review of j comments on the
       Amended Proposed Plan, a Modification to the Amended Proposed Plan was prepared. The
       Modification proposed an additional RAA that would rely on thermal destruction but would
       allow the flexibility to test and use appropriate ex situ and in situ innovative technologies.
       This additional RAA is comparable to RAA-5 in the ROD, the chosen silternative,


70.    If an innovative technology was not chosen,  why not? At what stage was the innovative
      • technology eliminated?                     : •

       Innovative technologies could  be eliminated  from the remedial  technology selection process  at
       three stages:  during the  initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or  during the detailed evaluation.

       Innovative technologies eliminated during  the initial screening include tike following:

       •      None •.               •                •   .         •        •                 '
                                                                          i            -

       Innovative technologies eliminated during  the screening of the three criteria include the
       following:                 :     „'                                 I

       •      Bioslurry, was eliminated but no explanation was given.

       Innovative technologies eliminated during  the detailed  analysis  include the following:
                                                    .            -;   •      i
       •      None                       -"     .          '•-..!'
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment and long-term effectiveness and permanence
       were weighted most heavily  in selecting a remedy.  The chosen alternative provides the best
       overall protection through treatment of contaminated soils that could be jexcavated and
       contaminated soils that would remain in place. The soils that would remain in place were
       considered important because they could contaminate ground water and inhibit its cleanup for
                                                                                               551

-------
       approximately another 100 years. Long-term effectiveness also was important and the chosen
       alternative was considered superior in this regard. Other alternatives proposed less permanent
       remedies such as containment, which would require long-term maintenance or
       stabilization/solidification, which could potentially allow waste to leach into thu ground water.
       Furthermore, there was concern that if excavated soil was found to have high levels of
       contamination, solidification/stabilization would not be sufficient to comply with RCRA
       disposal regulations.

       No innovative technologies were eliminated for these reasons.
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?

       Surface Soil                                                                   „

       Cleanup levels for surface soils (i.e., the top 12 inches of soil) are based on a worker exposure
       scenario and  assume commercial/industrial land use.  Cleanup levels also are based on a 1 x
       10'6 carcinogenic risk level and a hazard quotient of 1 for noncarcinogens.
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
DDT
DDD
DDE
Alpha-BHC
Beta-BHC
Delta-BHC
Gamma-BHC
17
24
17
1
3
2
4
Risk
Risk
, Risk
Risk
Risk
Risk
Risk
Noncarcinogens ,
Chlorobenzilate
Diazinon
39,922
1,796
Risk
Risk
        Subsurface Soils

        To protect ground water, cleanup levels for the contaminated subsurface soils are based on a 1
        x 10"4 carcinogenic risk level and a hazard quotient of 1 for noncarcinogens.  The health-based
        cleanup levels were calculated using either the Summers or Pestan model.  The Summers
        model was used in areas where contamination has extended to or near the ground: water (Areas
        1, 4, and 9) and the Pestan model was used for areas where an uncpntaminated zone exists
        between the contaminated soils and the ground water (Areas 2, 3> 5, 6, 7, 10, and 11).
 552
                                              -26-
! iyf
fit:

-------
 13.
                      Contaminant
                                        Cleanup Level (mg/kg)
                                           (Summers/Pestan)
                                                                 ARAR or Other Basis
                  Carcinogens
                 DDT
                 DDD
                 DDE
                 Alpha-BHC
                 Beta-BHC
                 Delta-BHC
                 Gamma-BHC  .
                                              5,034/7,500
                                              6,758/7,500
                                             16,527/17,250
                                                4/156
                                                17/152
                                                3/154
                                                 1/37
                                                                         Risk
                                                                         Risk
                                                                         Risk
                                                                         Risk
                                                                         Risk
                                                                         Risk
                                                                         Risk
                 Noncarcinogens
                 Chlorobenzilate
                 Diazinon
                                               209/340
                                                10/10
                                                                         Risk
                                                                        .Risk
                                                                   :   \    i         ,
        Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                               |         .
                  •  '               '     '     •'                        ' !

        Innovative technologies eliminated because of cleanup goals include:

        •      None                '                 ...


        Standard technologies eliminated because of cleanup goals include:


        "      Stabilization/solidification of soils with high levels of contamination might not meet
               KCRA hazardous waste disposal regulations.



14.      Were treatability studies conducted on the innovative technology or  standard technology?
                                      -   •                   ^          i
       No treatability studies were conducted.
75.
       What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:


            Time to design/construct/operate/remediate
            Proven reliability
                                            -27-
                                                                                           553

-------
16.    How are measures compared?

       The chosen alternative was preferred because it quickly remediated the site through treatment
       of underlying soils, whereas RAAs 1, 2, 3, and 4 would rely on natural flushing. It was
       estimated that natural remediation of underlying site soils would impede the remediation of
       ground water, causing cleanup to take 100 years. The chosen alternative not only removes the
       source of ground water contamination but also decreases the time  necessary to remediate
       ground water through pump-and-treat technologies.

       Proven reliability was also an important factor in selecting a remedy.  Thermal treatment was
       described as effective in the treatment of contaminants such as those found at the site. The
       effectiveness of stabilization/solidification with organic contamination  was considered
       uncertain.                 ,                   ,
17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        EPA concluded that it would be technically impractical to excavate to depths below -20 feet
        because the excavated area could cave in.  This restriction defined the amount of soil that
        could be treated ex situ; therefore, in situ technologies were necessary to treat contaminated
        soil below 20 feet.
                                                                                                    *

   554

-------
                         Ciba-Geigy Corp. (Mclntosh Plant)
                                          OU-4

                                    Mclntosh, Alabama
                                        Region 4              ,
GENERAL SITE INFORMATION

L      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Subsurface Soil (mg/kg)

       Volatile Organics

       Benzene     •  .  '           1.04
       Chlorobenzene               1.98
       Chloroform                 0.372
       m-Xylene     '    ' -         2,410
       o- and p-Xylenes             1,200
       Toluene                     3,150

       Base/Neutral Extractables

       1,2,4-Trichlorobenzene        1.36
       Nitrobenzene                0.269

       Chlorinated Pesticides                    ;

       Gamma-BHC               422
       4,4'-DDD      '             42
       4,4'-DDE                   27.8
       4,4'-DDT                   47.8

       Manufactured Pesticides

       Ametryn                    310
       Atrazine                    1,809
       Bladex                     ,23
       Cyanazine                   74.2
       Diazinon         ,           720
       Galecron                    750
       Methidathion (Supracide)     41
       Metolachlor (Dual),           150
      Prometon                   9.9
      Prometryn                 4,029
      Propazine                    1,180
      Simazine   '               321
      Terbumeton                 42
                                          -1-
             Site IHistory
NPL Proposed:
NPL Final:
FS:
ROD:
PRP-lead
PRPs:  Ciba-Geigy
FS prepared by: BCM
   N/A   /
   9/83
   1/90 (Final
   revision 2/92)
   7/14/92
             Background
Corp.
   Engineers Inc.
                                                                                         555

-------
       Terbutryn
       Terbuthylazine
       Tolban

       Metals

       Arsenic
       Chromium
       Copper
       Lead

       Cyanides, total
        75.5
        280
        3.9
        150
        1,490
        22.5
        180

        10.5
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      63,000 cubic yards of subsurface soil
        »      46,000 cubic yards of iron slurry waste
3.      What type of site is this?                                                               '

        Chemicals and Allied Products. An active chemical manufacturing company that produces
        products such as pesticides, agricultural chelating agents, industrial sequestering' agents,
        laundry brighiteners, plastics resins, and antioxidants.  Located in an industrial setting, OU-4 is
        the former waste management area, Site 8.
TECHNOLOGY SELECTION      .

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:

        Physical treatment:
        Chemical treatment:
        Thermal treatment:

        Disposal:
 Institutional controls (land and water use restrictions)              ,'
 Caps (multi- or single-layer:  clay, synthetic membranes, asphalt,
 concrete, soil mixtures), vertical1 barriers (soil bentonite slurry wall)
 Fixation/stabilization (lime-based pozzolan, portland cement pozzolan,
 silica based CHEMFIX process, HAZCON process), bulk removal
 (mechanical, manual, semisolid), screening (grizzly screen, vibratory
 screen), shredding (multiple blade), crushing/grinding (hammer mill),
 blending/mixing (pugmill), magnetic separation (rotating drum), in situ
. deep soil mixing, volatile organics/air mixture^treatment, air drying
 Neutralization
 Incineration (rotary kiln, fluidized bed, infrared, circulating bed),
 advanced electric reactor, liquid injection
 Excavation, on-site landfill                            •
  556
                                               -2-

-------

                                                 ' ,                       I
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                         \
                                                                        «-i     ,

        Biological treatment:   Anaerobic treatment, white rot fungus, co-oxidation, composting, solid
                              phase, bioslurry
        Phys/Chem treatment:  Chemical hydrolysis, chemical reduction, oxidation by hydrogen
                              peroxide, ozonation, oxidation by hypochlorite!, dechlorination (KPEG),
                              alkali metal/polyethylene glycol, solvent extraction, critical fluid
                              injection, in situ soil flushing, in situ  vacuum extraction
        Thermal treatment:     Pyrolysis, high-temperature thermal desorptiocl, low-temperature
                              thermal desorption, vitrification
6.       What was the cost estimate for the innovative technology?         ,

        During the initial screening process; in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  AJfter the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. '"The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP, The RAAs were consolidated in the Proposed Plan and ROD and are presented in
        separate  tables following the  cost estimates provided for the three-criteria arid nine-criteria
        screening.                                       .
                 '                           '                        ' •    !
                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)

       Feasibility Study
Alternative
RAA-11















Innovative Technology
Remove contaminated water/organic
solid waste and low-level contaminated
soil treatment (excavation to 20 feet
maximum, debris removal, drying,
grizzly screen, shredder, vibratory
screen, hammer mill, magnetic separa-
tor, on-site rotary kiln incineratibn, ash
disposal in on^site vault)/nonhazardous
solids treatment (on-site rotary kiln
incineration)/elevated-level contam-
inated soil treatment (pugmill stabiliza-
tion, on-site disposal in vault)/on-site
fixation iron cake waste treatment/
possible further treatment (backfilling
with sandy soil, vertical isolation wall,
soil flushing with ground water)
Estimated Costs
I
3 Criteria
$49,723,000
,
['
|'
.'l
I
,|
!
1
i
i
1
i
1
- • / |
•
i . .
9 Criteria
$49,723,000















                                            '  -3-
557

-------
      Fronted Plan and ROD
          Alternative
               Standard Technology
                                                                              Estimated
                                                                                 Cost
        RAA-4
Excavation/pretreatment could include solvent
extraction followed by liquid injection incineration, or
low-temperature thermal desorption followed by
volatile organics/air mixture treatment and/or critical
fluid injection followed by liquid injection
incineration/treatment could include solidification/
stabilization, possible blending followed by on-site
incineration, disposal in RCRA landvault, in situ soil
flushing, in situ vacuum extraction, in situ
bioremediation, and/or in situ fixation
$49,723,000
7.      How did the cost(s) compare to standard technologies?
                    Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5

Standard Technology
No action
Soil bentonite slurry wall/backfilling/
grading/multilayer cap/protective soil
cover/topsoil/vegetation
Soil bentonite 'slurry wall/excavation/
debris removal/grizzly screen/ shredder/
vibratory screen/hammer mill/on-site
rotary kiln incineration of nonhazardous
material/fixation/material returned to
site/multilayer cap
Soil bentonite slurry wall/excavation/
debris removal/grizzly screen/ shredder/
pugmill stabilization/on-site disposal in
RMP vault/debris decontamination/on-
site rotary kiln incineration of
nonhazardous solids/multilayer cap
Soil bentonite slurry wall/solid waste
fixed with in situ deep soil mixing/
backfilling/multilayer cap
Estimated Costs
3 Criteria
N/A
$10,909,000
N/A
$30,359,000
N/A
9 Criteria
N/A
$10,909,000
eliminated
r
$30,359,000
, eliminated
                                                                                                *   I
   558
                                             -4-

-------

Alternative
RAA-6
/
Standard Technology
Soil bentonite slurry wall/soil and solid
waste treatment (excavation, debris
removal, grizzly screen, shredder,
pugmill stabilization, disposal in RMP
vault)/organic waste treatment (excava-
tion, debris removal, drying, grizzly
screen, shredder, vibratory screen,
hammer mill, magnetic separator, on-
site rotary kiln incineration, ash disposal
in on-site RMP vault)/nonhazardous
solids treatment (on-site rotary kiln
incineration)/multilayer cap
ikstiimated Costs
3 Criteria
N/A •'.
9 Criteria
eliminated
 "Costs not given

 Proposed Plan and ROD
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Soil bentonite slurry wall/multilayer cap/possible
solidification/stabilization/institutional controls


•s
Excavatiqn/solidification/stabilization/on-site disposal in
landvault/backfilling/vegetation/in situ fixation/possible
institutional controls
If a standard technology was chosen, why?
Standard technologies were chosen as part of RAA-4 discussed below.
Estimated
Cost
N/A
$10,909,000
$30,359,000

If an innovative technology was chosen, why?
   : '           .                  '      .          -                 ' .
RAA-4 from the Proposed Plan and ROD was chosen because it is the most comprehensive
and protective option.  It proposes the potential use of several innovative technologies, which
will be tested during the design phase to determine whether pretreating [waste with them would
enhance the efficiency of thermal treatment and solidification-stabilization zind whether they
could replace these standard technologies. Furthermore, several innovative in situ technologies
will be tested and, if proved effective, used to remediate soil below 20 ;feet. This alternative
was the only one that proposed treatment for contaminated soil below 20 feet.  This alternative
provided the greatest protection to human health and the environment because it addressed
both the excavated soil and the underlying soil. Soils below 20 feet thait did not meet cleanup
criteria were considered important to address because they ,would remain a source of ground
water contamination.  This alternative provides the most immediate response to removing


                                       -5-                         I                      559

-------
       contaminants that are the closest to ground water.  The chosen alternative also was preferred
       because it proposed incineration/a technology that has been demonstrated to destroy site
       contaminants effectively. Incineration ensures the permanent reduction of contaminant
       toxicity, mobility, and volume and will substantially reduce risk over the long term.
       Incineration also ensures that RCRA hazardous waste regulations will be met. New equipment
       might be  designed and constructed to meet thermal treatment capacity needs. The iron slurry -
       waste will be treated by  in situ fixation because the waste is completely unsuitable for thermal
       treatment or stabilization.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                          .

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Site contaminants were categorized according to their treatability characteristics.  Technologies
       were then screened as to their effectiveness in reducing concentrations of the contaminant
       groups.  One objective of the evaluation was to select representative process options, if
       possible, for each technology type to facilitate further evaluation.  The representative
       technologies were then used to develop performance specifications during preliminary design.
       The following  innovative technologies were not selected as representative technologies during
       the initial screening and no explanation was provided:

               Anaerobic treatment
               White  rot fungus
               Co-oxidation (co-metabolism)
               Composting
               Solid phase
               Bioslurry
               Chemical hydrolysis
               Chemical reduction
               Oxidation by hydrogen peroxide
               Alkali  metal/polyethylene glycol
               Pyrolysis
               High-temperature thermal desorption
                                                 i
        Note: Bioremediation could be included in the final remedy; however, no technologies were
        specified.
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        Long-term effectiveness, permanence, and protection of human health and the environment
        were weighted most heavily in selecting a remedy.  The alternative was chosen because it
        provides the best overall protection through treatment of excavated contaminated soils, as well
        as of contaminated  soils that remain in place.  Treatment of excavated soils includes
        solidification/stabilization, dechlorination if proved effective during remedial design, and/or on-
 560
-6-

-------
       site thermal treatment (not specified). Treatment of soils remaining in J>lac« includes
       stabilization/fixation of iron slurry wastes, and soil flushing, vacuum extraction and/or       '•
       bioremediation, depending on the level of effectiveness or determined during the remedial
       design.  The soils that remain in place are a source of contamination tci ground water and
       could inhibit its cleanup for approximately another 100 years. The chosen alternative was
       considered superior in its long-term effectiveness.  Other alternatives proposed less permanent
       remedies,  such as containment, which would require long-term maintenance, or
       stabilization/solidification, which could caiise leaching of waste into the ground water.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?

              Surface Soil (top 12 inches of soil)
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens ,
Gamma-BHC
4
Risk8
Noncarcinogens
Diazinon
Bladex
Simazine
Atrazine
Prometryn
1,800
4,100
4,100
10,000
8,200
,

Risk
Risk
Risk

•
Risk
Risk
               aA 1 x 10'6 carcinogenic risk level and a hazard quotient of 1 for noncarcinbgens was
               used to establish cleanup level.                        '     !     .      .

               Subsurface Soils                              ,           j     .
                     Contaminant
Cleanup Level (mg/kg)
  (Summers/Pestan)
                                                                 ARAR or Other Basis
                 Carcinogens
                 Gamma-BHC
        1.0/105
                                                                          Bisk3
                 Noncarcinogens
                  Diazinon
                  Bladex
                  Simazine

                  Atrazine
        3.6/61
        2.0/37
       3.7/1,000

         3.6/19
                                                                          Risk
                                                                          Risk
Risk

Risk
                                               -7-
                                                      561

-------
                                          Cleanup Level (mg/kg)
                                            (Summers/Pestan)
                                                           ARAR or Other Basis
                 •Cleanup levels for the contaminated subsurface soils were derived to protect ground
                 water and are based on a 1 x 10"4 carcinogenic risk level and a hazard quotient of 1 for
                 noncarcinogens.  The health-based cleanup levels were calculated using either the
                 Summers or the Pestan model.   The Summers model was used in areas where
                 contamination has extended to or near the ground water and the Pestan model was
                 used for areas where an uncontaminated zone exists between the contaminated soils
                 and the ground water.                               ' '                     -
  13.     Was the innovative technology eliminated because of the cleanup goals? Cbuld the standard
         technology meet the cleanup goals?                                             ^anaara

         Innovative technologies eliminated because of cleanup goals include:

         •    '  None               •                                        •   •'          .

         Standard technologies eliminated because of cleanup goals include:

         •      Stabilization/solidification


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.
 75.
What measures/criteria were used to compare alternatives?

The following measures were used to compare the alternatives:

      Time to design/construct/operate/remediate
      Proven reliability
 16.     How are measures compared?

        The chosen alternative was preferred because it quickly remediates the site through treatment
        of In  r§,     ' NatUral remediation of underiyi*g *te soils would impede the remeSon
        of ground water causing ground water cleanup to take an estimated 100 years.  The chosen
        alternative not only would remove the source of ground water contamination but also wouW
        decrease the time necessary to remediate ground water through pump-and-treat technologies.

        Proven reliability also was an important factor in selecting a remedy.  Thermal treatment has
        been demonstrated to be effective in treating contaminants such as the site's. The
        effectiveness of stabilization/solidification with organic contamination  was uncertain.
562
                                              -8-

-------
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?               !      ,
                    • •                                 '        "          I-. •
       EPA concluded that excavating soils that are deeper than 20 feet would be technically
       impractical because the excavated area could cave in.  Since the amoiint of soil that could be
       treated ex situ was therefore limited, in situ technologies were necessary to treat contaminated
       soil below 20 feet.
                                                -9-
                                                                                                  563

-------
                                      Florida Steel Corp.
                                             OU-1
                                      Indianitown, Florida
                                           Region 4
  GENERAL SITE
  1.
2.
3.
          What were the principal contaminants
          contaminant levels, and media addressed in
          this feasibility study?

          Maximum concentrations of principal
          contaminants were:

          Emissions Control (EC) Dust (mg/kg)

          Cadmium
         Lead
         Zinc
                             956
                             27,600
                             242,000
        Soil/Sediment (mg/kg)
        Cadmium
        Lead
        Zinc
        PCBs
                             380    .
                             17,000
                             110,000
                             1,100
                                                                 Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                     N/A
                     12/82
                     3/13/92
                     6/30/92
                                                                 Background
PRP-lead
PRPs: Florida Steel Corporation
FS prepared by: Ardaman &
       Associates, Inc.
       Concentrations of principal contaminants in incineration ash and slag were not reported.
        What volume of material is to be. remediated?

        The volume of material to be remediated included:
             10,700 cublc yards of incinerator ash contaminated with metals
      What type of site is this?

      Prima, Meta, Product, A fonner «, mill bordered by
                                                                                                        «*».•••
  564
                                          -i-

-------
TECHNOLOGY SELECTION
                                                                       '! .          '
4.     What standard technologies were considered for selection in this FS?
                                               - '          •'             •'.
       This FS did not have an initial screening phase, therefore, standard technologies considered in
       the development of remedial alternatives were:                     j

       PCB-Containing Soil

       Chemical treatment:   Stabilization/solidification                  !
       Thermal treatment:    Incineration.                         .      j
       Disposal:         ,    Excavation, off-site disposal at RCRA/TSCA facility, pn-site disposal
           *                •             ••                    •        .!' •-,.'...
       Lead-Contaminated Soil/Sediment, EC Dust, and Incinerator Ash

       Containment:         RCRA cap                                \
       Chemical treatment:   Stabilization                             •                    .   , .
       Disposal:             Excavation, off-site disposal at "HTMR" facility, on-site disposal at
                             RCRA-type landfill facility                 !.     '
5.      Was an innovative technology considered in the FS? If so, which technology?

        This FS did not have an initial screening phase, therefore,  innovative technologies considered
        in the development of remedial alternatives were:                  t

        PCB-Containing Soil                                           j

        Biological treatment:   Biological treatment                       !.
                                          "                     '•!*'.•    ^
        Lead-Contaminated Soil/Sediment, EC Dust, and Incinerator Ash

        Thermal treatment:     In situ vitrification


 6.      What was the cost estimate for the innovative technology?          |

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the.FS does  not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, the estimated costs were calculated during sin evaluation based on
        nine criteria established by the NCP:  long-term  effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implemeritability; cost; state/support
        agency acceptance; and community acceptance.                            *
                                                                                                   585

-------
                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
       PCB-Contaminated Soil
Alternative
RAA-4
Innovative Technology
Excavation/biological treatment
Estimated Costs
3 Criteria
N/A
9 Criteria
eliminated
       Lead-Contaminated Soil, Sediment, EC Dust, Incinerator Ash, and Slag
Alternative
RAA-7
Innovative Technology
In situ vitrification
Estimated Costs
3 Criteria
N/A
9 Criteria
eliminated
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)

       PCB-Contaminated Soil
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Excavation/off -site disposal of soil
with greater than 50 ppm PCBs/on-
site solidification of soil with 25 to 50
ppm PCBs
Excavation/on-site incineration/disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$0
$306,750
eliminated
      Lead-Contaminated Soil, Sediment, EC Dust, Incinerator Ash, and Slag
Alternative
RAA-1
RAA-2
Standard Technology
No action/long-term monitoring
Excavation/off-site treatment at high-
temperature metal recovery facility/off-
site disposal
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$345,000
$21,160,000
 566
9.
"<-*-'% .iTfTT
  )
                                          -3-

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
Standard Technology
Excavation/on-site solidification/on-
site disposal in RCRA landfill with
RCRAcap.
Excavation/solidification/on-site
disposal in single-lined landfill with
RCRAcap
RCRA cap over contaminated area
Excavate/consolidate/RCRA cap
Estimated Costs
3 Criteria
. N/A
WA
. N/A
N/A
9 Criteria
$6,698,000
$6,098,000
eliminated
eliminated
8.      If a standard technology was chosen, why?

       PCB-containing soil:  A standard technology was chosen because it y ill. greatly reduce the risk
       of dermal contact and ingestion of PCB-containing soil.  PCB mobility will be reduced
       through treatment.  Stabilization of PCB-contaminated soil will provide a long-term and
       permanent solution. This technology is proven and readily available for implementation.  Soil
       with high levels of PCB contamination will be disposed of off site and therefore contamination
       will be reduced permanently.                                      !

       Lead-contaminated media: The chosen  alternative was preferred because it will greatly reduce
       the risk of dermal contact and ingestion of metal-containing soil, including EC dust, by
       solidifying the waste  and disposing of it in an on-site landfill.  It offers a permanence and
       long-term effectiveness because contaminants will be bound in a cement matrix.  Through
       solidification and disposal in a RCRA double-lined landfill, this alternative provides an extra
       measure of ground water protection.  This alternative is cost-effective;.           ,

       The preferred alternative in the FS  for lead-containing soil was RAA^4, considered  the most
       cost-effective alternative. In the Proposed Plan and ROD, however, :RAA-3 was deemed more
       cost-effective, and  became the  preferred alternative.  RAA-3 will be more protective of ground
       water since it proposes disposal in  a double-lined landfill instead of a single-lined landfill.
9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
 10.     If an innovative technology was not chosen^ why not? At what stage was the innovative
        technology eliminated?
                                                                          .
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implernentability, and cost; or during the detailed evaluation.
                                               -4-
                                                                                                     567

-------
        Innovative technologies eliminated during the initial screening include the following:

        •      None               ,

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      Biological treatment for soil with PCBs was eliminated because "discussions with EPA
               Headquarters, TSCA Branch indicated that the effectiveness of this technology for
               PCB contamination had not been  demonstrated."
        •      In situ vitrification for lead-containing soil was eliminated because it was not
               considered implementable for the  shallow  depth of EC dust requiring remediation.
               Also, the technology was regarded as unproven with excessively high costs but no
               significant advantage in performance.

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

 Protection of human health and the environment and implementability were weighted most
 heavily in selecting a remedial alternative.  No innovative technologies were eliminated,,
 however, based on these criteria.
72.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
 568
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Lead (soil)
Lead (slag)
PCBs
600
1,360
25
EPAa
Risk"
TSCAC.
              Tlie soil lead cleanup level was derived based on the leachability of lead from soil
              into the ground water.  EPA's cleanup level for lead in ground water, 15 ppb, was
              used as the basis for the derivation.
              bSlag lead cleanup levels were developed to protect human health in an industrial
              setting. Slag is not subject to cleanup levels based on ground water protection because
              it-produces low levels of lead in leachate and does not" threaten ground water at levels
              below  1,360 ppm.
              •Toxic  Substances Control Act PGB spill policy for areas with restricted access.
                                             -5-
                                                                                                    EiM

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                                !

       Innovative technologies eliminated because of cleanup goals include: |    . -
               '  -   .                  '                                        >  •
       •      None          .                                          j      .

       Standard technologies eliminated because of cleanup goals include:   ;
                                                                        I   .         -   t    ^  ,
       •      None
                                                                        i .    i .'.'..
                                   '                     .               f
14.    Were treatability studies conducted on the innovative  technology or standard technology?
                                    '•'••..            i        -
       No treatability studies were conducted. .
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Time to design/construct/operate
        -    Proven reliability             ,
                                                                        i              •        ,
                                                                                    •
                                    •  •••--                    |/

 16.     How are measures compared?
     •                                •           -                        i      '
        Time to implement the remedy was a consideration.  RAA-2 for lead contamination was
        eliminated because it would take significantly longer to implement depending on the off-site
        treatment/disposal facility's capacity to accept  waste. Proven reliability also  was a
        consideration. Two innovative technologies, in situ vitrification and biological treatment, were
        eliminated because their reliability was uncertain.                  i

                                                                        I1
 17.      What technical considerations were factors in  selecting a remedy?  Were technical
         considerations primary  in the selection of the remedy?                            ,

         No technical considerations were primary in selecting a remedial alternative.
                                                -6-
569

-------
                        Geigy Chemical Corp. (Aberdeen Plant)
                                           0U-4

                           Aberdeen, Moore County, North Carolina
                                          Region 4
 GENERAL SITE INFORMATION
 /.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
        Surface Soil (mg/kg)

        Aldrin
        Alpha-BHC
        Beta-BHC
        Delta-BHC
        Gamma-BHC
        DDD
        DDE
        DDT
        Dieldrin
        Endrin Ketone
        Alpha-chlordane
        Gamma-chlordane
        Toxaphene
        Heptachlor
        Heptachlor epoxide
        Endosulfan I
        Endosulfan sulfate
 14
 21
 4.1
 19
 3.2
 28
 11
 54
 9.7
 0.28
 0.045
 0.049
 450
 500
21
 18
2,000
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                                     6/88
                                     10/4/89
                                     3/92
                                     8/27/92
                                                        Background

                                           PRP-lead
                                           PRPs:  Ciba-Geigy Corp., Olin Corp.,
                                                  Kaiser Aluminum & Chemical
                                                  Corp., Lebanon Chemical Corp.,
                                                  Aberdeen and Rockfish Railroad,
                                                  Columbia Nitrogen Corp.
                                           FS prepared by: Sirrine Environmental
                                                  Consultants
                                                                                               r
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      Less than 1,000 cubic yards of soil (ROD)


3.      What type of site is this?                                                       '

       Agricultural Chemicals. Located in a sparsely populated residential area, the site is a former
       pesticide formulator and distributor of liquid and dry fertilizers.  A railroad traverses the site's
       southern portion.
570

-------
 TECHNOLOGY SELECTION                                           |

 4.      What standard technologies were considered for selection in this FS? \

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                               [            .

        Containment:          Cap                                     . T i    •     .
        Physical treatment:     Classification (pretreatment)
        Chemical treatment:    Stabilization/solidification
        Thermal treatment:     Off-site commercial incineration, bn-site incineration
        Disposal:              Off-site commercial landfilling, on-site landfill
                                                                       1.1 •
                                 . .                         '            ~         .               '

 5.      Was an innovative technology considered in the FS? If so, which technology?
                                          • •                '        '  •   [  .   ,
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                          '

        Biological treatment:   Land treatment, bioreactor, hi situ enhanced biodegradation  ,
        Phys/Chem treatment:  Supercritical CO2 solvent extraction, critical fluid solvent extraction,
                      '        Basic Extraction Sludge Technology (BEST) process,  soil washing, in
                              situ soil flushing, in situ vapor extraction     I
        Thermal treatment:     Supercritical water oxidation (MODAR, Inc.), jlow-temperature thermal
                              aeration (LTTA, by Canonie Environmental), X*TRAX system (by
                              Chemical Waste Management, Inc.), low-temperature thermal treatment
                              (LT3, by Weston Services, Inc.), low-temperalure thermal desorption,
                              vitrification
                                                       '          "       i                 .    -


,6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in  which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not  quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening procesis (effectiveness,
        implementability, and cost) to  identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.

        RAAs were revised and added in the ROD.  Two tables are provided, one; for RAAs in the
        Feasibility Study and one for RAAs in  the ROD-
                                               -2--       -    •  •   ,    \   .   ••            -.'571

-------
                  Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
         ROD
            Alternative
          RAA-4
               Innovative Technology
Excavation/low-temperature thermal desorption/soil
returned to original location
                                                                               Estimated
                                                                                 Costs
                                                                                 ROD
                                                                               $700,000
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)

        Feasibility Study
Alternative
RAA-1
RAA-2A
RAA-2B
RAA-3A
RAA-3B
- -===
Standard Technology
No action
Incineration and off-site disposal of 140
cubic yards of soil
Incineration and off^she disposal of 670
cubic yards of soil/off-site disposal of
foundation debris
Capping of 140 cubic yards of soil
Capping of 670 cubic yards of soil and
foundation debris
=====
Estimated Costs
3 Criteria
$140,000
$127,000 to
$330,000
$510,000 to
$1,500,000
$180,000
$350,000
9 Criteria
$140,000
$110,000 to
$470,000
$380,000 to
$1,500,000
$240,000
$280,000
       ROD
572
•
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Excavation/incineration (if needed) and off-site disposal
of top foot of soil exceeding remediation levels/off-site
disposal of foundation debris
Capping of soil exceeding remediation levels
============
Estimated
Costs
ROD
$140,000
$600,000
to
$2,440,000
$275,000
                                           -3-

-------
Alternative
RAA-5
Standard Technology
Excavation/homogenization and sizing/on-site inci
on-site disposal

leration/
Estimated
Costs
ROD
$1,327,100
8.      If a standard technology was chosen, why?

       By excavating the soil and disposing of it in an approved landfill (precede*! by incineration, if
       necessary) the soil is permanently disposed of and/or treated.  Given the small volume of soil
       that requires remediation, expensive and complex technologies would jnot be appropriate. Off-
       site landfilling and off-site incineration have been conducted successfully on site contaminants
       in the past. These technologies are reliable and cost-effective.
9.      If an innovative technology was chosen, why?

      " No innovative technology was chosen
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the piree criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                                               " -       -I       -           '
                                                                       •  I-
        Innovative technologies eliminated during the initial screening include? the following:

        •     Land treatment was eliminated because many chlorinated pesticides require anaerobic
               conditions before reductive dechlorination can occur. Landfarming fosters only
               aerobic biodegradation of organic compounds.
                Bioreactor was eliminated because successful biodegradation
of chlorinated pesticides
                requires sequential anaerobic/aerobic bioreactor systems. Effective monitoring and
                management of sequential processes would not be possible.
                Supercritical CO2 extraction was eliminated because an EPA study found it to give
                poor recoveries of adsorbed organics from activated carbon and synthetic resins, which
                might reflect the process's effectiveness on other solid residuals.  According to another
                EPA study, this process's removal levels were greater than 40 percent for only 4 of 23
                organic compounds tested.  While pilot tests have been conducted on this type  of
                technology, no full-scale operations have been applied.
                Critical'fluid solvent extraction was eliminated because the1 technology lacks sufficient
                development.  Though demonstrated under EPA's SITE program, the technology has
                not yet been demonstrated for the removal of pesticides from soils.  Additionally, no
                full-scale application of the technology has been conducted at a Superfund site.
                BEST (Basic Extraction Sludge Technology) process was eliminated because no full-
                scale application of the technology has been conducted at a pesticide-contaminated
                site. Though bench-scale tests using site soils indicate  that soils containing pesticide
                                                -4-
                          573

-------
11.
          concentrations in excess of 1,000 ppm could be remediated to levels of less than 1
          ppm, the technology was considered to be not fully developed.
  «      Supercritical water oxidation (MODAR, Inc.) was eliminated because the effectiveness
          of the process with soils has not been sufficiently demonstrated.
  •      Soil washing was eliminated because the treatment's duration is insufficient for a
          potential vendor to operate such a system.            ' •                     .
  •      Low-temperature thermal aeration, (LTTA, by Canonic Environmental) was eliminated
          because, given the small volume of site soils requiring remediation, the treatment
          would not be cost-effective.
  •     X*TRAX system (by Chemical Waste Management, Inc.) was eliminated because given
         the small volume of site soils requiring remediation, the treatment would not be cost-
         effective.
  •      Low-temperature thermal treatment (LT3, by Weston Services, Inc.) was eliminated
         because, given the small volume of site soils requiring remediation, the treatment
         would not be cost-effective.
  "      In situ vapor extraction (SVE) was eliminated because generating and maintaining a
         vacuum in surficial soils would not be a technically effective use of SVE
         Furthermore, pesticide residuals in the site soils are not amenable to SVE due to their
         low Henry's law values.
  •      In situ enhanced biodegradation was eliminated because biodegradation of chlorinated
         pesticides requires sequential anaerobic/aerobic conditions, and controlling these
         conditions within the upper foot of soil would be impractical.
  »      In situ soil flushing was eliminated because of concerns that mobilized contaminants
         would not be recovered completely by the extraction system and, therefore,  would
         degrade ground water conditions. Furthermore, site-related pesticides have relatively
         high Koc values, making them difficult to remove from soils.
  •       In situ vitrification was eliminated because the technology requires further
         development. During a recent large-scale test at a Superfund site, a fire occurred in a
         22IT1     °n SyStem'  As a result'the sole marketer suspended the technology and
         bPA Region 6 withdrew its  order to use in situ vitrification at a Texas Superfund site.

 Innovative technologies eliminated during the screening of the three criteria include  the
 following:                                                                 ,

 •      None


 Innovative technologies eliminated during the detailed analysis include the following:

 •      Low-temperature thermal desorption was eliminated because the low volume of
        contaminated soils requiring  remediation renders this alternative impractical at this site.


 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so
 which criterion? Which of the criteria supported the use of a standard technology?

Long-term effectiveness and permanence was an important criterion in selecting a remedy
Off-site disposal and incineration would result in a permanent reduction in  site risks  .Low-
temperature thermal desorption and on-site incineration also could reduce risks  These
technologies, however, were considered not implementable or practical given the small soil
volume requiring remediation..
                                                                                                         0
 574
                                              -5-

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?    [
 13.
Contaminant
Cleanup Level (ing/kg)
ARAR or Other Basis
Carcinogens
Aldrin
Alpha-BHG
Beta-BHC
Delta-BHC
Gamma-BHC
Alpha-chlordane
Gamma-chlordane
DDD
DDE
DDT
Dieldrin
Endrin ketone
Toxaphene
0.113
0.28
1.15
NCb - , '
1.5
1.4
1.43
7.6
5.5
4.75
0.13
. NC /..
2.0
Risk8
Risk
Risk
Risk
Risk
Bisk
Bisk
Risk
Risk
Risk
Risk
Risk
Risk
       Tor carcinogens, an excess upper bound individual lifetime cancer risk of between 10
       to 10"6 was acceptable.     %                              !
       bNot calculated.                                         |
                                                      '        I
Note: As decided in the FS, the rate limiting compound for site riskis was toxaphene.  The
removal of all toxaphene concentrations greater than 50 or 5 mg/kg youM result in a residual
LECR (not defined) of 10'5 or 10'6, respectively. Removing toxaphene also would reduce the
levels of BHC-isomers, DDT, and other pesticides concurrently. This decision was superseded
in the ROD by the cleanup levels presented in the table above.

                                                              i
Was the innovative technology eliminated because of the cleanup gotils?  Could the standard
technology meet the cleanup goals?
  ,               , ••                    "                        I
Innovative technologies eliminated because of cleanup goals include:

•     None

Standard technologies eliminated because of cleanup goals include:

•     None
                                               -6-
                                                                                                 575

-------
    14.
  Were treatability studies conducted on the innovative technology or standard technology?

  Treatability studies were conducted on the Basic Extraction Sludge Technology (BEST)
  process. Bench-scale testing using soils from the site indicated that soils containing pesticide
  concentrations in excess of 1,000 ppm could be remediated to levels of less than  1 ppm  No
  full-scale application of the BEST process, however, has been conducted at a site affected bv
  pesticides.  Because of its limited development, the BEST process was eliminated
                                                                                                             -—r;
    15.    What measures/criteria were used to compare alternatives?

           The following measures were used to compare the alternatives:  '

                   Cost/unit risk
                   Proven reliability
                   Preference for treatment (vs. containment)


    16.     How are measures compared?

           A large number of technologies were eliminated because the small volume of contaminated
           soils did not warrant using an expensive, complex technology. Furthermore, the selected
           remedy is most cost-effective because it permanently treats the waste.

           Proven reliability was another factor resulting in the elimination of a large number of
           innovative technologies. Again the issue of the small volume was considered, in that the use
           of such uncertain (and often expensive) technologies cannot be justified.

           According to a section of the FS about statutory determinations, the chosen technology
           satisfies the preference for treatment "by the use of off-site disposal which encompasses
           incineration for the soils containing characteristic hazardous waste and land disposal for the
           residual  soils at an approved RCRA landfill."  The issue of preference for treatment as
           opposed to containment, however,  is not expressed anywhere else in the report.
                                                                                                    )
   17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations  were primary in selecting a remedy.  The small volume of
contaminated soils resulted in the elimination of a number of innovative technologies because
or high costs.  Because the soils requiring remediation were very close to the surface certain
technologies, such as vapor extraction, were deemed to be unsuitable
576
                                                -7-

-------
                          Golden Strip Septic Tank Service
                               Simpsonville, South Carolina
                                        Region 4     ;
GENERAL BYTE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
                                             \
       Soil/Lagoon Sludge (ppm)

       Antimony                  1,940
       Arsenic                    76
       Cadmium                  12,000
       Chromium                 97,200
       Copper                    69,900
       Cyanide                   4,520
       Lead                       5,290
       Mercury                   13.8
       Nickel                     6,140
    >   Zinc                       77,600
       Acetone                   2
       bis(2-Ethylhexyl)phthalate   130
       2-Butanone                 0.28
       Chlorobenzene             38
       PCE                       18
    .   Toluene                   12
       Xylenes                    11
       1,2-Dichloroethene          0.077
       Ethylbenzene               1.9
       Methylene chloride         0.073
       Styrene                    0.19   .
       1,1,1-Trichloroethane       0.15
             Site History
NPL Proposed:
NPL Final;
FS:
ROD:
1/87
6/87
5/91
9/12/91
             Background
 •  '             .1     .      '
                 I     •  .
PRP-lead
PRPs:  Metal Products Corp., Sterling
       Drug, Inc., 'Colonial Heights
       Packing, Injc., E-Systems, Inc.,
       W.R.Grace & Co.-Conn., BASF
       Corp., and Carolina Plating and
     r' Stamping Corp.
FS prepared by: RMT, Inc.
2.,     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •     Approximately 28,000 cubic yards of soil and lagoon sludge
 3.      What type of site is this?

       'Uncontrolled Waste Site. An inactive waste hauling and disposal facility.
                                            -1-
                                       577

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Soil/sludge

        Access restriction:
        Containment:

        Physical/Chemical:
        Thermal treatment:
        Disposal:
Fencing, deed restrictions, conservation easement
Capping (asphalt, soil, clay, synthetic membrane, concrete,
multimedia), slurry wall, grout curtain
Physical separation, in situ precipitation, stabilization/solidification
Incineration (infrared, circulating bed, rotary kiln), roasting
Excavation, dredging, dewatering, landfilling (on-site, off-site)
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Soil/sludge

        Biological treatment:  Batch biodegradation, in situ biodegradation
        Physical/Chemical:    Soil washing (Laidlaw, GSW), in situ steam stripping (Toxic
                             Treatment), vacuum extraction
        Thermal treatment:    Vitrification (in situ, ex situ),  thermal separation
6.      What was the cost estimate for the, innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation, 'ihe
        estimated costs then are recalculated during an evaluation based on nine criteria established bv
        the NCP.                                                          /

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial! alternative is in bold)
Alternative
RAA-7A
RAA-7B
Innovative Technology
Ex situ vitrification/on-site disposal of
solids '
Soil washing/on-site disposal of solids
Estimated Costs
3 Criteria
$19,400,000
$13,800,000
9 Criteria
eliminated
eliminated
578

-------
Alternative
RAA-8A
Innovative Technology
In situ vitrification
Estimated Costs
3 Criteria
$13,2(K),000
9 Criteria
eliminated
7.      How did the cost(s) compare to standard technologies? '

                 Cost Estimates for RAAs That Include Standard Techncjlogies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-4
RAA-5
RAA-6
RAA-7C
RAA-8B
RAA-8C
- - ' i
Standard Technology
No action/long-term monitoring
Fencing/conservation easement
Composite cap
Multimedia cap
Excavation/stabilization/off-site disposal
of soil and sludge
Excavation/stabilization/off-site disposal
of sludge and capping of^soil
Excavatiori/on-site disposal of solids
Stabilization/solidification/on-site
disposal of solids
In situ stabilization/solidification
In situ precipitation
Estimated Costs
3 Criteria
$1,300,000
$1.400,000
$3,200,000
$3,500,000
$12,500,000
I
$$,1.00,000.
$7,0130,000
$4,5ittO,(M)0
-
1
'$4,100,000
$4,3tX),000
9 Criteria
$1,300,000
$1,400,000
$3,200,000
$3,500,000
$12,500,000
$6,100,000
eliminated
$4,500jOOO
$4,100,000
eliminated
 8.      If a standard technology was chosen, why?                      •  \
                            -  .                      '        ,             i    .• "  • •          -
         The chosen alternative was preferred because it offered the greatest protection of human health
         and the environment since stabilization will immobilize contaminants!  Stabilization will
         eliminate the threat to human health by preventing direct contact with the identified waste
         constituents. This technique also provides a "capping effect" over the less affected subsoils
         containing waste constituents.  This alternative can be carried out on site, which was preferred
         since short-term risk would be increased if truck traffic is necessary for transport of materials
         off site. This alternative will also provide long-term effectiveness and permanence since
         contaminants will be immobilized and reduced in both toxicity and mobility. This alternative
         is cost-effective.                                                 i
                                                 -3-
579

-------
  9.      If an innovative technology was chosen, why?

          An innovative technology was not chosen.
  10.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?                                 '

  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages:  during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  •      In situ steam stripping was eliminated because organics constitute only a small portion
         of site contaminants and a relatively flat topography is necessary to implement the
         technology successfully.
  »      Vacuum extraction was eliminated because organic constituents are a minor fraction of
         site contaminants.
  »      In situ biodegradation was eliminated because organic constituents are a minor fraction
         of site contaminants.
  «      Batch biodegradation  was eliminated because organic constituents are a minor fraction
         of site contaminants.

 Innovative technologies eliminated during the screening of the three criteria include the
 following:                                                         .

 "       f* s!1" vitriflcati°" was eliminated because it has not been demonstrated technical
         feasible for metal-bearing soils and sludges.  The process does not appear  capable of
         treating volatile metals, such as arsenic and cadmium.  The level of risk reduction
         associated with this technology can easily be achieved by other remedial options in a
         more cost-effective manner.
 •       Soil washing was eliminated because it would generate large quantities of hazardous
         waste water that would require further treatment.
 •      In situ vitrification was eliminated because its technical feasibility has not been
        demonstrated in the field. The level of risk reduction associated with this  option can
        be achieved by other remedial options in a more cost-effective manner.

 Innovative technologies eliminated during the detailed analysis include the following:
                                            \
 •      None
11.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so
which criterion?  Which of the criteria supported the use of a standard technology?

Protection of human health and the environment and cost were the most heavily weighted
cntena in selecting a remedial alternative.  Two innovative technologies, in situ vitrification
and vitrification, were eliminated due to their high cost.       •
530
                                               -4-

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?     !
1 Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
r "
Carcinogens ,
Cadmium
1 Arsenic
Chromium6
Lead
PCE
Nickel
bis(2-Ethylhexyl)
phthalate
Methylene chloride
Tetrachloroethene
65
18 .
580
500
56
1,300
200
,380
56
Risk8
Background1*
Risk
EPAd
Risk
Risk
'Risk
Risk
Risk
Noncarcinogens
Acetone
Antimony
Copper
Cyanide
Mercury
Zinc
2-Butanone
Chlorobenzene
1 ,2-Dichloroethene
Ethylbenzene
Styrene
Toluene
- 1,1,1 -Trichloroethane
Toluene
Xylenes
6,000
26
2,400
1,300
20
13,000
3,000
1,200
1,200
6,000
95
12,000
5,500
12,000
120,000
Risk
Risk
Riisk












Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
                Since no federal standards for toxics in soil exist, health risk-based calculations,
                assuming future residential use, were used to derive most clesinup levels.
                                               -5-
                                                                                               531

-------
 75.
                 Tor carcinogens, an excess upper bound individual lifetime cancer risk of 10'6 was
                 acceptable.  For noncarcinogens, a Hazard Quotient of 0.3 was used to allow for
                 exposure to multiple contaminant^  whose effects might be additive
                 Tor arsenic, an excess upper bour.J individual lifetime cancer risk of 10'5 was used
                 because background levels exceed the typical cancer risk of 10'6
                 "The chromium cleanup level assumes that 10 percent of total chromium is in the
                 hexavalent state.
                 "The lead cleanup level is based on EPA guidance for Superfund Sites  OSWER
                 Directive 9335.4-02.                                             '
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      None                                                                  .


 Standard technologies eliminated because of cleanup goals include:

 •      None                                 ,             -
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.
 75.
What measures/criteria were used to compare alternatives?

The following measures were used to compare the alternatives:

     Preference for treatment (vs. containment)
     Cost-effectiveness
     Short-term risk to site workers
     Proven reliability
16.    How are measures compared?

       Treatment was preferred over containment since containment would not be permanent or
       effective in the long term. Source removal was eliminated because of the short-term risks
       posed by transporting waste materials and the high costs.  Two innovative technologies  in situ
       vitnficanon and ex situ vitrification, were eliminated because they were not cost-effective
       v[t°riVfiL     "y T a ^T- TW° inn°Vative technol°gi^ in «tu vitrification and ex situ
       vitrification, were eliminated because their technical feasibility has not been demonstrated
       The chosen alternative proposed stabilization, a proven technology that is easy to implement

       Innov^^TV60,    °cgy',S°iI WaSWng (LaidISW' GSX)>  Was  Proved effecti^ in a Superfund
       Innovative Technology Evaluation (SITE) demonstration.  This technology, however was
       eliminated because it would generate waste.                                      '
582
                                             -6-

-------
17.     What technical considerations were factors in selecting a remedy?  Weft technical
       considerations primary in the selection of the remedy?      ,

       No technical considerations were primary in selecting a remedial technology.
                                              -7-
                                                                                              583

-------
                                 Interstate Lead Co. (ILCO)
                                             OU-1

                                        Leeds, Alabama
                                           Region 4
 GENERAL SITE INFORMATION
 1.
 2.
 What were the principal contaminants,
 contaminant levels, and media addressed in
 this feasibility study ?

 Maximum concentrations of principal
 contaminants were:

 Soil/Sediment (rag/kg)
        Arsenic
        Chromium
        Lead
        Antimony
              1,500
              71
              130,000
              1,600
What volume of material is to be
remediated?
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:.
                                                     ROD:
                     N/A
                     6/86
                     7/91
                     9/30/91
             Background

EPA Fund-lead
PRPs:  Interstate Lead Co.
FS prepared by:  CH2M Hill
       Southeast, Inc.
        The volume of material to be remediated included:

        •      123,700 cubic yards of waste material
3.      What type of site is this?

       Primary Metal Products. Located in a mixed industrial and residential area, the site consists of
       an 8.5-acre active lead smelting facility and seven subsites where waste (furnace slag  battery
       chips, and wastewater treatment sludge) was disposed.             ,


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of. technically feasible
       technologies were:                                                          . ••
       Access restriction:
       Containment:
                    Fencing, deed restrictions
                    Soil cover, cap (clay, asphalt, concrete, multilayer, synthetic
                    membrane, clay-geomembrane), block displacement, grout injection,
                    liners, surface sealing, grading, revegetation, drainage, curtain barriers
                  •  cofferdams, stream diversion '        '
584
                                            -i-

-------
       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
             •'                          "
  Solidification/stabilization, neutralization     [
  Dewatering                                i
  Incineration
  Excavation, dredging, on-site disposal in RCRA landfill, off-site
  disposal in RCRA landfill                  i
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:              .        %                 I                "
     •''"••          •  '          '  -     '  -        •    •     '         i'.  •
       Biological treatment:   In situ bioreclamation, on-site biological treatment
       Phys/Chem treatment:  In situ soil flushing, chemical reduction, soil \yashing, in situ soil
                             vapor extraction
       Thermal treatment:    In situ vitrification
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        .evaluation.  For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.

        No innovative technologies were incorporated into remedial alternatives.
        How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard techiuoloigies
                             (selected remedial alternative is in bold)
            Alternative
          RAA-SC-1
          RAA-SC-2
          RAA-SC-3
           RAA-SC-4
        Standard Technology
No action
Multilayer cap
Excavation/off-site RCRA landfill
disposal
Excavation/solidification/replacement
on site/RCRA cap

                 '   -2-
                                                                       \ Estimated Costs
3 Criteria
                                                                       N/A
                                                                       N/A
                                                                       N/A.
                                                                       N/A
                                                                                   9 Criteria8
               $5,000 to
                $33,000
              $310,000 to
               $3,690,000
               $820,000 to
               $28,830,000
               $680,000 to
               $12,780,000
                                                                                                  5S5

-------
              Alternative
             RAA-SC-5
                            Standard Technology
                    Excavation/move material to central
                    location/solidification/replacement on
                    site/RCRA cap
                                                                            Estimated Costs
                                                                       3 Criteria
                                                                          N/A
 9 Criteria8
 $1,230,000
     to
$12,780,000
           The FS presents the results of an analysis of five remedial action alternative for seven
           subsites.  These results are summarized in the ROD and in the table above.  The alternatives
           are the same for each subsite, except for cost, which varies by waste volume.  The costs
           presented above represent the range of costs across individual subsites.                     '


   &      If a standard technology was chosen, why?

           The chosen alternative was preferred because it eliminates the potential for human exposure to
           contaminants via direct contact and reduces contaminant mobility, thereby decreasing the
           potential for ground water contamination. Though it requires long-term maintenance, this
           remedy offers long-term effectiveness through treatment by solidifying the waste.
           Solidification was preferred because it is a proven technology and treatability studies have
           demonstrated that it will treat the lead-contaminated waste material to below RCRA Land
          Disposal Restriction levels. The chosen alternative minimizes short-term risk since it does not
          require the transport of waste. Also, it is the most cost-effective option since it offers greater
          protection than other alternatives but at a lower cost.
   P.      If an innovative technology was chosen, why?

          An innovative technology was not chosen.
   10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                              ,

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies  eliminated during the initial screening include the following:

«      In situ bioreclamation was eliminated because the process is not applicable to site
       contaminants.
«      In situ soil vapor extraction was eliminated because the process is not applicable to
       site contaminants.              ,                                  .
«      On-site biological treatment was eliminated because the process is not applicable to
       site contaminants.                                                             •
586
                                                -3-

-------
      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                                        |

      •      In situ soil flushing was eliminated because it would be difficult to implement at the
              site.  Because of the site's varied soil conditions, flushing would be inconsistent. High
              clay and/or silt content would reduce the percolation of .surfactant through the. soil.
      •      Chemical reduction was eliminated because it would be difficult to implement given
              the site's varied topography and subsurface obstructions.  Sandy loam soil is preferred
              to d&Y-                                            v            -^
      •      In situ vitrification was eliminated because it would be difficult to implement and less
              effective given the buried metals and combustible solids. The retention of volatile
              metals in the melt would be reduced nearer the surface.       j
       •      Soil washing was eliminated because site-specific treatability studies indicate that
              although implementable, the process would not be effective for the site conditions.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      None
11     ' Which of the nine criteria were weighted most heavily in selecting rfwj technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Cost and protection of human health and the environment were the mbst heavily weighted
       criteria in the selection of a remedial alternative.  Several innovative technologies (soil
       flushing, chemical reduction, and in situ vitrification) were eliminated because they would be
       difficult to implement.
 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

Contaminant
Cleanup Level (mg/kg)
AFAR or Other Basis
Carcinogens :
Lead (soil)
Lead (sediment)
Arsenic
Chromium
(hexavalent) .
300
50
10
'1,750
teachability3
RASPL"
Risk6
Risk
Noncarcinogens
Antimony
32
Risk
                "Soil remediation goal developed for protection of ground water. At this cleanup level,
                leaching would not cause the level of ground water contamination to exceed 15 ug/L.
                bRegional Aquatic Species Protection Level.
                                                -4-
587

-------
                 Tor carcinogens, an excess upper bound individual lifetime cancer risk of W6 was
                 acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was
                 acceptable.  ,        - -
  13,
         Innovative technologies eliminated because of cleanup goals include:
         19      None

         Standard technologies eliminated because of cleanup goals -include:

         •      None
 14.
 15.
17.
  Were treatability studies conducted on the innovative technology or standard technology?
   ah                                    ofstabilization/solidification on lead-contaminated
 soil from the site and another treatability study was conducted in 1990 on the waste and
 contaminated soil in one subsite.  Information from these studies was refernS tot thTpS and
 supported the use of a stabilization/solidification process for site soil/sedtat Motion.


 What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

        Cost-effective                                                          ,
        Preference for treatment (v. containment)
        Impact on nearby populations
16.     How are measures compared?                .

        The chosen alternative, RAA-4, was considered to be the cost-effective option since it offers
        comparable protection to RAA-5, but costs less.  It also was preferred because   ^
        short-term risk by requiring the transport of materials that would pose a risk to woricT
        the community  Treatment was preferred over containment since both direct ™re a
        contaminant mobility will be reduced; containment would address only direct exposure
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?
                                       '                                        characteristics.
       thnn o                     Slte S S011' 'oPWhy. and waste deposition, finding one     "
       technology that would be appropriate across all subsites was difficult. This technical
       consideration was primary in selecting and eliminating remedial technologies
 588
                                              -5-

-------
                           JFD Electronics/Channel Master
                                  Oxford, North Carolina
                                         Region 4
GENERAL SITE INFORMATION
1.
 2.
       What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sludge (mg/kg)
       Chromium
       Nickel
       Antimony
       Cadmium
       Copper
       Cyanide
       Zinc
                     24,000
                     11,000
                     120
                     N/A
                     N/A
                     N/A
                     N/A
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
PRP-lead
PRPs:  Unimax Coi-poration
       Master, Granville
       Developers
FS prepared by: B< chtel
       Environmertal, Inc.
        What volume of material is to be
        remediated?                           •  .

        The volume of material to be remediated included:

        •      3,000 cubic yards of soil/sludge
                     6/88
                     10/89
                     4/92
                     9/10/92
                                                                Background
   ion, Channel
ille Industrial
 3.     What type of site is this?

        Electrical Equipment. A former manufacturing facility that produced
        satellite systems, the site is bordered by industrial and residential areajs.
                                                                     television antennas and
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?
         Standard technologies considered during the identification and
         technologies were:
         Access restriction:     Fencing, deed restrictions
         Containment:         Capping (RCRA, non-RCRA), slurry wall,
                             block displacement
                                              -1-
                                                               screening of technically feasible
                                                                   sheet piling, grout curtain,
                                                                                             589

-------
         Physical/chemical:
         Thermal treatment:
         Disposal:
     Stabilization, surface encapsulation
     Incineration
     Excavation, landfill disposal (on-site, off-site)
                        3
         Was an innovative technology considered in the FS?  If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Biological treatment:  Biodegradation                         ;
         Physical/chemical:     Chemical extraction, soil washing, soil flushing (in situ, ex situ),
                              'chemical reduction-oxidation, in situ vacuum/steam extraction
         Thermal treatment:    Low-temperature thermal stripping, vitrification (in situ, ex situ/
                              Vortec), pyrolysis
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of.RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment-
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support '
        agency acceptance; and community acceptance.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
           Alternative
         RAA-4
         RAA-5
        Innovative Technology
Excavation/reduction-oxidation/
stabilization/backfill/cap
Excavation/on-site vitrification/
backfill/cap
                                                                        Estimated Costs
                                                                    3 Criteria
                                                                      N/A
                                                                      N/A
9 Criteria
$1,151,000
$1,119,000
590
                                              -2-

-------
7.      How did the cost(s) compare to standard technologies?               |
                      -               .                     '     '          j     •
                 Cost Estimates for RAAs That Include Standard Technoliogi(5S
                            (selected remedial alternative is in bold)
 8.
Alternative
RAA-1
RAA-2
RAA-3
• . '
Standard Technology
No action/reviews
Fencing/deed restrictions/concrete cap
Excavation/disposal at RCRA TSD
facility
Intimated Costs
3 Criteria
N/A
N/A
N;|A
i
9 Criteria
.$333,000
$862,000
$2,400,000
If a standard technology was chosen, why?

A standard technology was not chosen.
 9.      If an innovative technology was chosen, why?

        The chosen alternative was preferred because it will reduce site risks.  In addition, any further
        degradation of the ground water will be mitigated ,by reducing the toxiicity and mobility of
        contaminants in soil and sludge. The selected alternative will provide long-term effectiveness.
        Following treatment by oxidation-reduction, which will destroy the inorganics in the
        soil/sludge, stabilization techniques will immobilize remaining metals in the soil/sludge.
        Oxidation of cyanide is a proven method of destruction and leaves no hazardous residuals.
        Stabilization is a widely used treatment technology for inorganics.  Berth technologies are
        available from a large number of vendors.  Short-term risks to the cornmumity are negligible
        and workers' risk can be easily managed, The selected alternative wais deemed cost-effective.
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the tfiree criteria of "
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the following:

         '•       Chemical extraction was eliminated because it would not be Applicable for the
                 treatment of metals and cyanide.
         •       Soil washing was eliminated because it would not be applicable for sludges.
         •       Ex situ soil flushing was eliminated because it would not be applicable to cyanides.
         •       Low-temperature thermal stripping was eliminated because it would not be applicable
                 to cyanide or metals.
         •       Biodegradation was eliminated because it would not be applicable to cyanide or
                 metals.                                       .           '                       ,
                                                 -3-
                                                                                         531

-------
          "      Pyrolysis was eliminated because it would not be applicable to metals or cyanide
                 In situ vitrification was eliminated because it would not be applicable because of'the
                 proximity of the Bandag warehouse.                       *
          •      In situ soil flushing was eliminated because it would not be applicable to the
                 heterogeneous nature of the sludge waste and associated soil
          "      cyanlde^rmeSs""* 
-------
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard

       technology meet the cleanup goals?  ,                              ;


       Innovative technologies eliminated because of cleanup goals include:  j


       •      None                                    '


       Standard technologies eliminated because of cleanup goals include:


       •      None                   >



 14.    Were treatdbility studies conducted on the innovative technology or standard technology?


       No treatability studies were conducted.
                                                                        i

                            -                    "                        i
 75.     What measures/criteria-were used to compare alternatives?             '


        The following measures were used to compare the alternatives:       |

                                       •  '           •                    i
                                                                        i •          .
             Cost-effective

             Proven reliability                                           i
                                                                        I

                                                                        I, •
                                                                        !
 76.     How are measures compared?
   • ,     •  .  •            '   '                 -                -          i                •

        When  compared to three alternatives that offered treatment, the chosen alternative was

        preferred because it was the  most cost-effective and is a readily available, proven technology.

                                                        '.•,;., v     ;  •   •   /  .


 17.     What technical considerations were factors in selecting a remedy?  W^ere technical
        considerations primary  in the selection of the remedy?


        No technical considerations were primary in selecting a remedial alternative.
                                                -5-
593

-------
                           Marine Corps Logistics Base (MCLB)
                                            OU-3

                                       Albany, Georgia
                                           Region 4
GENERAL SITE INFORMATION

/.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants  were:

       PSC1 16 Subsurface Soil (rag/kg)

       1,2,4-Trichlorobenzene       80
       Hexachlorobenzene          2.2
       Pentachlorobenzene          60
       1,2,4,5-Tetrachlorobenzene    2
       Tetrachlorobenzene         200
      Trichlorobenzene            40
      Aroclor-1260 (PCBs)        310

      PSC 17 Surface Soil and Subsurface Soil
      (mg/kg)

      Benzo(a)anthracene           0.62
      Benzo(b/k)fluoranthene       1.4 ...
      Chrysene                    0.68
      Pyrene                      14
      Aroclor-1260                0.16
      Chromium (total)           49,000
      Chromium VI             87
      Lead                      3j900
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •     30 cubic yards of soil at PSC 16
        •     300 cubic yards of soil at PSC 17
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    Interim ROD:
N/A
12/89
7/92
8/14/92
                                                                Background

                                                    Federal Facility
                                                    PRPs:  Department of the Navy
                                                    FS prepared by: ABB Environmental
                                                          Services, Inc.
    Potential source of contamination (see Question 3)
594
                                           -i-

-------
3.      What type of site is this?                                           !

       Military.  MCLB Albany is an active facility with 24 potential sources of contamination
       (PSCs).   Of these, 12 PSCs were identified for the Remedial Investigation/Feasibility Study
       process and were divided into five operable units. OU-3 consists of PSC 16 and PSC 17.
       PSC 16 is a former transformer location and PSC 17 is a chrome plating waste spill area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS? [

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                   ,             i
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
Fencing, institutional controls
Surficial capping (clay, asphalt)
Stabilization
Incineration (rotary kiln)
Excavation, on-site RCRA landfill, off-site RC;RA landfill
 5.       Was an innovative technology considered in the FS? If so, which technology?
                                                                         \
         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                                        ;            '
                             ,            •              '                  .1    -    •    ' .    •
         Biological treatment:   In situ biodegradation    '                  |.     '
         Chemical treatment:    Soil flushing, soil venting, solvent extraction, phemical hydrolysis,
                               dechlorination, soil washing
         Thermal treatment:     Vitrification
  6.      What was the cost estimate for the innovative technology?           j

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs, ^fter the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability,;and cost) to identify alternatives that merit a more detailed
         evaluation.  For this site, the estimated costs were calculated during ah evaluation based, on
         nine criteria established by the NCP.

                   Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
- Alternative
RAA-5B
(PSC 17 only)
Innovative Technology
Excavation/soil washing

Estimated Costs
3 Criteria
N/A

9 Criteria
$606,100

                                                 -2-
                                                                    535

-------
  7.
  How did the cost(s) compare to standard technologies?
                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
                                   Standard Technology
          RAA-31
          RAA-4A
          (PSC 16 only)
         	:	   	
          RAA-4Bb
          (PSC 17 only)

          RAA-5A
          (PSC 16 only)
                           Limited action/access restriction/
                           monitoring
                   Multilayer cap
                   Excavation/off-site incineration
                   Excavation/off-site stabilization/
                   landfill disposal

                   Excavation/disposal at TSCA landfill
f
»gy
•
tion/

an
tion/
—
landfill
=====
	 : 	 	 .
Estimated Costs ,-J
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
•" 	
9 Criteria |
$0
$188,300
(PSC 16)
$99,900
(PSC 17)
$242,200 II
(PSC 16)
$190,000
• (PSC 17)
$327,800
$475,000 |
$198,200
        The selected remedy for PSC 16 is RAA-3.
        "The selected remedy for PSC 17 is RAA-4B.
8.     If a standard technology was chosen, why?
Sound w 1116™, R°D -Hat a^reSS6S °nly P3rt °f ** MCLB site «W does "<*   dr
ground water contamination.  The remedial actions described in the Interim ROD are
however, the final actions for soil at PSC 16 and 17.

PSC 16
                                                                                      any
596
          v                                  wil1 ™°
-------
       cover surrounding PSC 16 would readily support the installation of a cap with a paved cover
       abutting the existing parking lot and concrete pad storage area.  RAA--3 also will provide the
  •"     necessary long-term protection required for human health. The FS states that capping of waste
       materials is a proven technology and is commercially available. The selected alternative will
       meet federal and state ARARs, but will not meet the health-based TBCs (To Be Considered)
       because wastes are contained and not treated.
                                                                   .   •!•  -        •  j    '
       PSC 17                                                         I •'    '      '  .
                                                                       , •   •  .  '
       The selected remedy for PSC 17, RAA-4B, incorporates excavation aind transportation of
       contaminated soils to a permitted facility for stabilization and landfill jdisppsal. Stabilization of
       the soils will reduce contaminant solubility and mobility, thereby reducing the potential
       migration of contaminants. RAA-4B protects the public and the environment for all current
       and future conditions through the excavation and treatment of soils.  RAA-4B provides a
       permanent solution to the exposure scenarios and reduces the toxicity,and mobility of soil
       contaminants. Long-term  risks will not be posed by the stabilization ^nd disposal of soils
       from PSC 17 because the design mix for the stabilization of the confeimiriants in the soils
       ensures that the potential leachate will not exceed  RCRA Land Disposal Regulations       ;
       requirements (TCLP 5 mg/L).  In addition, the actual disposal method for stabilized soils
       ensures that the public and environment are protected from exposure ]to metals.  No long-term
       management  or operation and maintenance (O&M) requirements would be associated with
       RAA-4B. Also, the chemical technology used for stabilizing metals in soils has been proved
       for both on- and off-base applications.  Finally,  although the selected j alternative does not   ;
       satisfy the health-based federal and state TBCs because contaminants are only contained, all
       ARARs would be met by  this technology.


9.     If an innovative technology was chosen, why?                .     j

       An innovative technology was not chosen.                         i    •
                                .•'•"'            .             i.            '
                                                                        1                     '
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                             •-            '              -            '!''•.       '•        -
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial  screening; during the screening of the: three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      In situ biodegradation was eliminated because neither  PSC 16 nor PSC 17 would
               contain contaminants that are biodegradable.
        •      Soil flushing was eliminated because this  technology would not te effective  for PCBs
               and  might adversely affect the building foundation  at PSC 16.  Also, leachate would
               be difficult to collect and would require treatment prior to disposal.
        •      Soil venting was eliminated because it would not be effective on metals (PSC 17) of
               pesticides/PCBs (PSC 16).                               j
        •      Solvent extraction was eliminated because the technology has had only limited pilot-
               scale success on soils with high fines materials. The mix of contaminants might
               require several treatment steps and solvents.


 •    •   '•   .    ••       ,'    '    •     ,   .  .'••-4-""- '   '      '  -.'•['       /  '  '     ':     597

-------
         •      Chemical hydrolysis (in situ) was eliminated because this treatment was developed
                only for controlled industrial wastes.  This technology also could affect the existing
                building foundation and buried utility lines at PSC 16.
         •      Dechlorination (in situ) was eliminated because it would not be applicable to metals
                (PSC 17). The technology also could damage the building foundation and the
                electrical utility line at PSC 16.                                                  .
         "      Vitrification was eliminated because the volume of contaminated soil is less than the
                minimum system designs of 1,000 cubic yards.  The buried electrical conduit (PSC 16)
                would short-circuit treatment.

        Innovative technologies eliminated during the three-criteria screening include the following:

        «      The three-criteria screening process was not conducted in this FS.

        Innovative technologies eliminated during the detailed analysis include the following:

        «      Soil washing was eliminated because although this technology would reduce the
                mobility and volume of contaminants, it would not reduce toxicity.  Instead, this
                technology would concentrate contaminants into  a process residual which would
                require further treatment prior to its disposal off site at a permitted landfill facility.
                Specific pilot testing -would be necessary to evaluate the soil treatment unit's
                effectiveness and reliability before full operation could be implemented at PSC 17.
                The use of surfactants to extract the contaminants from the soils requires careful
                management and  knowledge of reactions that might adversely affect the treatment
                system. Water/surfactant systems pose some problems because a cost-effective
               leachate treatment system has not yet been developed to extract the contaminants
               selectively and pass the surfactants through intact for maximum recycling of the soil
               wash solution.  Implementation requires a high volume of water and electrical power
               for the mobile treatment system.
11.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Which of the criteria supported the use of a standard technology?

PSC  16 Soil

Short-term effectiveness, implementability, and costs were  weighted heavily in selecting the
remedial action for PSC 16. RAA-3 does not require soil excavation  and therefore minimizes
potential impacts  to the on-site building at PSC 16. In contrast, RAA-4A and RAA-5A both
would require excavating soils adjacent to and beneath the  building foundation. In addition
the costs for RAA-3 were  significantly lower than for alternatives RAA-4A and RAA-5A.
       Overall protection of human health and the environment, and reduction of toxicity, mobility  or
       volume were weighted heavily in selecting the remedial action for PSC 17. The chosen
       remedy protects the public and environment for all current and future conditions through the
       treatment of soils.  The chosen remedy, RAA-4B, reduces the contaminant toxicity and ,
       mobility. In contrast,  RAA-5B would not address the toxicity of soils but would concentrate
       contaminants into a process residual requiring further treatment prior to its disposal.
533
                                              -5-

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

       These target cleanup levels were developed in the FS; they were not discussed in the ROD.

              PSC 16 Soils                                                    ,
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens .
PCB-1260
5.8
Risk"
Noncarcinogens ,
Tetrachlorobenzene
(2 isomers)
96
Health-based"

Tor carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
to 10~6 was acceptable.
"Cleanup level based on health based Remedial Action Objective.
PSC 17 Soils
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
PCB-1260
PAHsb
Lead
Chromium (2 foot
depth of soils)
Chromium (greater
than 2 foot depth of
soils)
1
, 0,45
264
80
.-, 265
EPAa
Health-based0
EFAd
EPAe
EPA"

               "EPA regulatory guidance for recommended cleanup concentrations of PCB-1260,
               OSWER Directive No. 9355.4-01, August, 1990.
               "Carcinogenic PAHs were detected only in background sampleis. Though these
               contaminants were assumed to be unrelated to the source of contamination at PSC 17,
               a target cleanup concentration was set for them.             \
               'Cleanup level based on Remedial Action Objective.
               dEPA, Human Health Evaluation Manual, OSWER Directive 9285.6-03, 1991.
               eEPA, Supplemental Region IV Risk Assessment Guidance, March 26, 1991.
                                             -6-
599

-------
    13.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?


 Innovative technologies eliminated because of cleanup goals include:

 "      None

   14.
   75.
 Standard technologies eliminated because of cleanup goals include:

 «      None                      /                             "



 Were treatability studies conducted on the innovative technology or standard technology?


 No treatability studies were conducted.  According to the FS, however, treatability tests are
 necessary to demonstrate the effectiveness of stabilization and to select the most effective
 reagent process mix because the stabilization process (RAA-4B) is dependant on actual soil
 and contaminant characteristics.



 What measures/criteria were used to compare alternatives?


The following measures were used to compare the alternatives:

     Cost-effectiveness
     Proven reliability
     Preference for treatment (vs. containment)
  16.    How are measures compared?


         PSC16


         RAA-3 was considered cost-effective because it is protective of human health and the
         environment and is less expensive than RAA-4A and RAA-5A.

         PSC17


         ¥A:4B'JdthouSh significantly more expensive than RAA-3,,was considered more cost-

         ??A !!S   faUSe, RAA'4B Wi" eliminate current and P°tential foture exP°s"re pathways
         RAA-4B  also will not require O&M, as will RAA-3. The chemical technology used to '
         stabilize metals in soils is proven for both on- and off-base applications. The statutory
         preference for treatment over containment was satisfied at PSC 17 because the selected remedv
         employs a stabilization treatment.                                                 »^ucuy
600
                                               -7-

-------
17.     What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?

       Technical considerations were not primary in selecting a remedy. Toppgraphy and land
       features at both PSC locations were conducive for the constraction of a cap and the installation
       of monitoring wells.
                                               -8-
                                                                                                  601

-------
                                 Maxey Flats Nuclear Disposal
                                     Fleming County, Kentucky
                                             Region 4
    GENERAL SITE INFORMATION

    L
  What were the principal contaminants,
  contaminant levels, and media addressed in
  this feasibility study?

  Maximum concentrations of principal
  contaminants were:

  Soil/Radionuclides (pCi/g)
          Tritium
          Cesium-137
          Cobalt
                      560,000
                      0.8
                      0.3
          Soil/Organics (mg/kg)

          Toluene              0.25

          Soil/Inorganic (mg/kg)

          Arsenic               106

          Sediments/Radionuclides (pCi/g)

          Tritium               70

          Sediments/Organics (mg/kg)

          Methylene chloride
          Toluene
          Acetone
          2-Butanone
          Di-n-octyl phthalate,
          Phenanthrene
         Fluoranthene
         Pyrene
                      0.005
                      0.005
                      0.01
                      0.01
                      1.8"
                      0.51
                      0.41
                      0.38
                                                                    Site History
                                                       NPL Proposed:
                                                       NPL Final:
                                                       FS:
                                                       ROD:
                      1984
                      1986
                      12/88
                      9/30/91
             Background

PRP-lead
PRPs:  U.S. Department of Defense, U.S.
       Department of Energy, 82 PRPs
       including radioactive waste
       generators and transporters such
       as private companies in the
       nuclear industry, hospitals,
       research institutions, and
       laboratories
FS prepared by: Ebasco Services Inc.
  2.
602
What volume of material is to be remediated?

The volume of material to be remediated included:
                 ™           °f contaminated soil and sediment were not given in the FS or the
               ROD.  The proposed cap will cover approximately 40 to 50 acres. During the
                                             -1-

-------
              operation of the facility approximately 176,000 cubic yards of low-level, radioactive
              waste was disposed in 52 large, unlined trenches (some of which were up to 680 feet
              long, 70 feet wide, and 30 feet deep).                    '   |
3,      What type of site is this?

       Department of Energy.  A former nuclear disposal facility, the site is surrounded'by woodlands
       and open farmland. A number of residences, farms, and some small  commercial establishments
       are located on roadways near the site.   >                           j
TECHNOLOGY SELECTION
—Mil                         ""•"'             '                 '              |

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                         •   •  .\    .   '
                    '            '             '                  '         !;'      •••'••''-.
        Soil/Sediments                                                  j
   '           ""                      .        '                  '          I
        Access restriction:     Institutional controls, monitoring
        Containment:          Capping, bulk heads, sheet piling, grading, dikes and berms,
                              compaction
        Chemical treatment:    Neutralization, in  situ polymerization, in situ fixation/stabilization, in
                              situ chemical precipitation, solidification, activated carbon adsorption
        Physical treatment:     Solids processing, evaporation
        Thermal treatment:     Incineration                               ;
        Disposal:              Excavation, exhumation, on-site landfill, off-iiite landfill, deep well
                              injection, surface  impoundments
 5,      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                               ,       .    '

        Soil/Sediments
                                                                        !
        Biological treatment:    In situ biological processes,'permeable treatment beds       :
        Chemical treatment:    Soil flushing, chemical oxidation
        Thermal treatment:     In sita vitrification, cryogenic freezing
 6.    '  What was the cost estimate for the innovative technology?          j
                                                                        I ' •    .    • '      . ,. .  '
         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
         implementability, and cost) to identify alternatives that merit, a more detailed evaluation. The
                                                -2-
                                                                                                  603

-------
 7.
estimated costs then are recalculated during an evaluation based on nine criteria established by
the NCP. No innovative technologies were incorporated into remedial action alternatives.


How did the cost(s) compare to standard technologies?

Since the RAAs changed between the FS and ROD, separate tables are presented.

          Cost Estimates for RAAs That Include Standard Technologies
                    (selected remedial alternative is in bold)

Soil/Sediments

Feasibility Study
604
Alternative
L. 	 _
RAA-1
j— 	
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
I RAA-8
RAA-9
RAA-10
RAA-1 1
Standard Technology
No action/monitoring
Leachate removal/complete trench
grouting/horizontal flow barrier
Pile-supported structural cap/horizontal
flow barrier
Structural cap/leachate removal/
horizontal flow barrier (Structural
cap/dynamic compaction/horizontal flow
barrier)
Synthetic cover/Ieachate removal
Modified synthetic cover/leachate
removal/injected grout
Engineered soil cap/synthetic liner/
leachate removal/injected grout
Engineered soil cap/synthetic liner/
leachate removal/injected grout/north
cutoff wall
Engineered soil cap/synthetic liner/
leachate removal/dynamic compaction/
horizontal flow barrier
Engineered soil cap/synthetic liner/
leachate removal/dynamic compaction/
injected grout/horizontal flow barrier
Engineered soil cap/synthetic liner/
leachate removal/complete trench
grouting/horizontal flow barrier
Estimated Costs
3 Criteria
$7,000
$50,000
. $62,000
$47,000
$27,000
$27,000
$27,000
$28,000
$36,000
$37,000
$52,000
9 Criteria
$12,000,000
eliminated II
eliminated
$58,000,000
eliminated
$36,000,000
$37,000,000
$41,000,000
$49,000,000
$50,000,000
eliminated
                                            -3-

-------
•v1".
Alternative
RAArl2
RAA-13
RAA-14
RAA-15
RAA-16
RAA-17
RAA-18
RAA-19
RAA-20
RAA-21

Standard Technology
Engineered soil cap
Engineered soil cap/ground water
barrier
Engineered soil cap/leachate removal/
horizontal flow barrier
Engineered soil cap/leachate removal/
injected grout
Engineered soil cap/leachate removal/
injected grout/horizontal flow barrier
Engineered soil cap/leachate removal/
surface compaction " -. '
Engineered soil cap/leachate removal/
surface compaction/horizontal flow
barrier
Engineered soil cap/leachate removal/
dynamic compaction/horizontal flow
barrier ,
Engineered soil cap/leachate removal/
dynamic compaction/injected grout/ -
horizontal flow barrier
Engineered soil cap/leachate removal/
complete trench grouting/horizontal
flow barrier
Estimated Costs
3 Criteria
,$29,000
$32;000
$39,000
$37,000
$41,000
$37,000
$40,000
$46,0013
$47,000
$62,000
9 Criteria
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
eliminated
$57,000,000
eliminated
Soil/Sediments
[ .
ROD ,
Alternative
RAA-1
RAA-4
RAA-5
RAA-8
Standard Technology
Estimated Costs
PP and ROD
No action/monitoring $6,803,000
Structural cap/dynamic compaction/horizontal flow1 $65,507,000
barrier
Natural subsidence/initial cap/final engineered s oil $33,553,000
cap/synthetic liner/horizontal flow barrier — . •
"Natural Stabilization"
Natural subsidence/immediate engineered soil $47,407,000
cap/synthetic liner/horizontal flow barrier
: . '• -- - .' -«- -. .'• ; .-•; , 6C

-------
           Alternative
                                 Standard Technology
                                                                               Estimated Costs
                                                                                PP and ROD
          RAA-10
                   'Dynamic compaction/engineered soil cap/synthetic
                   liner/horizontal flow barrier
                                                                                 $44,328,000
          RAA-11
                   Trench grouting/engineered soil cap/synthetic
                   liner/horizontal flow barrier
                                                                                 $68,859,000
          RAA-17
                   Dynamic compaction/engineered soil cap/horizontal
                   flow barrier
                                                                                 $56,554,000
 8.      If a standard technology was chosen, why?

        RAA-5 was chosen in the ROD because the natural stabilization process will allow the
        materials to subside naturally to a stable condition prior to the installation of a final engineered
        cap.  Stabilization of the trenches by natural subsidence over a relatively long time period will
        virtually eliminate the potential problem of future subsidence expected with other alternatives
        in which the trenches would be stabilized by mechanical means and a final cap installed within
        a few years. The natural stabilization alternative, therefore, will reduce the redundancy of
        efforts necessary to construct and maintain the final cap.  Natural stabilization does not disrupt
        intact metal containers such as 55-gallon drams, thereby providing an extra measure of
        protection to prevent movement of radionuclides  to the hillsides.  The other alternatives have
        the potential of rupturing intact containers and releasing radioactive material immediately to
        the trenches. Additional  benefits of the natural stabilization alternative will be the opportunity
        for continued data collection and analyses and the ability to take advantage of technological
        advances  during the subsidence period.                                                   .
                                                                                                    -r
                                                                                                      •
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      Soil flushing was eliminated because it would not be implementable given site-specific
       conditions.  Many of the site contaminants have very low solubilities; therefore, very
       large volumes of water would be required to flush out these contaminants. In addition
       the method is not applicable to the site's soil and rock because of their low hydraulic '
       conductivities.  Also, since not all of the water injected would be recovered as
       leachate, off-site migration could result.
606
                                              -5-

-------
                Cryogenic freezing was eliminated because this technology would not be
                implementable at this site.  The technology would require not ^>nly an extensive and
                costly installation effort, but also long-term active maintenance and institutional care
                and control.  In addition, the technology lacks a Ipng-term performance record.
                In situ vitrification was eliminated because it could not be implemented and it lacks a
                suitable performance record.  A collection system to gather and tnsat the effluents
                generated by this process has not yet been designed or built for a site similar to Maxey
                Flats.  Also, trenches with a high metal content would pose a problem.
                In situ biological processes were eliminated because these processes would not affect
                ,radiological contaminants, the bulk of site contaminants.   Additionally, a major effort
                would be required to implement biological processes effectively and this technology
                has not been used at a site similar to Maxey Flat.
                Permeable treatment beds were eliminated because their applicability to site-specific
                conditions is limited by the nature of some of the contaminants.  Additionally, the low
                permeability of the site's soils and rock, and the indeterminate palthways and direction
                of  subsurface flows  make this technology difficult to implement.  This technology also
                 is difficult to implement because' the water level at this site is
relatively deep (25 to 30
                 feet), and treatment beds have limited lifetimes.
          •      Chemical oxidation was eliminated because it would not be effective for the
                 radiological contaminants,                                 !
      .  .     ^                    *                  . •                       i,       ,        •
          Innovative technologies eliminated during the screening of the three criteria include the
          following:                                                       I

          •      None                                                    j
)      .         '       ,                        '-             '    .         [•        •'..-•'•'•
          Innovative technologies eliminated during the detailed analysis include the following:

   .   '    •      None  ' .  • _              .,                 ,         '>•!.'•


  11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
          which criterion? Which of the criteria supported the use of a standard technology?
                                                                          I
          The difference between the six RAAs evaluated in the ROD were nol great except with regard
          to the following four criteria: implementability; reduction of toxicity, mobility, or volume;
          state acceptance; and community acceptance.  All RAAs provide the same  degree of long-term
          and short-term effectiveness, overall protection of human health and the environment, and
          ARARs.  RAA-5, however, is the least difficult to implement, using proven and reliable
          technologies to achieve final remediation, while not requiring- time-ceinsuming research and   .
          development prior to implementation.  It is less likely to result in container rupture (which was
          used to evaluate the alternatives reducing toxicity, mobility, and volume, thereby protecting
          containers within the trenches. Finally, both the state and community favor the Natural
          Stabilization technology.                                         .(
                                                                          I             •

   12..   What cleanup goals were selected?  If the cleanup goal was  based oh an ARAR, what was that
          ARAR? What risk level was selected to establish cleanup goals?        ;
                                                                          r
                                                                          I   . •         ;              • '  •
          Specific cleanup goals were not provided.                        ';.
                                                                          r


                                                 :6                       I                       607

-------
 13.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      None

 Standard technologies eliminated because of cleanup goals include:

 •      None
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
 75,     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Proven reliability


16.     How are measures compared?

        The selected remedy was chosen because it utilizes proven and reliable technologies to achieve
        final remediation and does not require extensive research and development prior to
        implementation.  In contrast, the state rejected the use of grouting (RAA-11) since the
        technology would have to be demonstrated prior to its implementation.
17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting an alternative. The state however
rejected the use of RAA-10 and RAA-17 for either ajjite demonstration or total site
remediation because of uncertainties regarding dynamic compaction's effect on the underlying
geologic strata. In addition, soil flushing was:eliminated because this technology is not
applicable to  the site's soil and rock because of their low hydraulic conductivities., Permeable
treatment beds were eliminated because of the low permeability of the site's soil and rock the
indeterminate pathways and direction bf subsurface flows, and the deep water level at this site
 608
                                              -7-

-------
                              Medley Farm Drum Dump
                                          OU-1

                                  Gaffney, South Carolina •
                                         Region 4
GENERAL STTH INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum .concentrations of principal
       contaminants were:                 ,
       Soil (rag/kg)

       1,1,2-Trichloroethane
       1,1,2,2,-Tetrachloroethane
       1,2-Dichloroethene
       1,2-Dichloropropane
       Ethylbenzene
       Methylene chloride
       Styrene
       Tetrachloroethene
       Trichloroethene
        Vinyl chloride
        1,2,4-Trichlorobenzene
        Butylbenzylphtalate
        Di-n-butylphthalate
        Di-n-octylphthalate
        Bis(2-ethylhexyl)phthalate
        Toxaphene
        PCB-1254
        Chloroform
        1,2-Dichloroethane
        1,1-Dichloroethane
        1,1-Dichloroethene
        1,1,1 -Trichloroethane
0.16
0.091
0.2
0.021
0.033
0.023
0.011
0.069
0.07
0.21
1.2.
1.1
1.1   '
5.4
33
0.52
 1.9
0.06
 3.7
 0.047
 0.014
 0.56
                             Site History
                NPL Proposed:
                NPL Final:
                FS:
                ROD:
                     6/86
                     3/90
                     3/91
                     3/29/91
             Background
                '  i
PRP-lead          |
PRPs:   Not listed
FS prepared by: Sirrine Environmental
       Consultants
  2.      What volume of material is to be remediated?

         The volume of material to be remediated included:

         •      53,000 cubic yards of soil
                                              -1-
                                                         609

-------
  3.      What type of site is this?
                         a rural area.
                                                                for the disposal of industrial waste
6.
  TECHNOLOGY SELECTION                  ,

  4.      What standard technologies were considered for selection in this FS?

                           65 C°nsidered during *» *»«&*<* and screening of technically feasible
                       Deed restrictions
                       Capping, slurry walls, grouting, sheet piling, bottom sealing
                       Stabilization, fixation                  .              *
                       Incineration (rotary kiln, infrared, fluiclized bed)
                       Off-site landfilling
        Access restriction:
        rh»         ,
        Chemical treatment:
        Thermal treatment:
        Disposal:
 5.      Was an innovative technology considered in the FS? If so, which technology?

                                        during the i
 Biological treatment:   Bioreactor, landfarming, in situ biodegradation
 Phys/Chem treatment:  Soil washing, soil flushing, chemical oxidation, in situ soil vapor
                       extraction                                              ,
 Thermal treatment:     Low-temperature desorption, in situ vitrification


 What was the cost estimate for the innovative technology?

During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs.  After fhe RAAs have been
formulated costs are estimated as part of a three-criteria screening process (eff^eness
implementability, and cost) to identify alternatives that merit a more detailed evaluation 'The
Se NCP C°StS ""* "* rCCalCuIated durin* m "valuation based on nine criteria established by


Alternatives presented parenthetically represent changes in the ROD.

         Cost Estimates for RAAs That Include Innovative Technologies
                     (selected remedial alternative is in bold)
          Alternative
        RAA-3
        (RAA-4)
                          Innovative Technology
                  Soil vapor extraction
                                                                      Estimated Costs
                                                                  3 Criteria
$500,000
9 Criteria
"~ ••      .—
 $620,000
610
                                             -2-

-------
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
(RAA-2)
RAA-2
(RAA-3)
Standard Technology
No action/long-term monitoring
Institutional controls/deed restrictions
Deed restrictions/low permeable cap/
long-term maintenance
Estimated Costs
3 Criteriia
$100,000
not proposed
$810,000
i
i.
9 Criteria
$140,000
$140,000
$1,000,000
8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
                                    .•                                  I. '   •     . •
 9.      If an innovative technology was chosen, why?

        An innovative technology, soil vapor extraction (SVE), was preferred jbecause it will reduce
        VOCs in the soils by more than 95 percent and thereby keep site soils from affecting ground
        water quality.  A treatment technology provides a permanent and long-term solution,
        mitigating principal threats at the site.  VOCs are the only site compounds  that can raise
        ground water contamination levels above MCLs,  In contrast to natunil degradation of VOCs,
        which would take 20 years, SVE will expedite the remediation of soil to approximately 1 year.
        SVE also will reduce semi-VOCs, though no remedial levels have been set for semi-VOCs as
        they will not raise ground water levels above MCLs. This technology was preferred because
        its effectiveness has been demonstrated.  SVE was shown to be effective in soil of similar
        porosity and permeability in a Superfund Innovative Technology  Evaluation (SITE)
        demonstration and for similar seiruVVOCs at another NPL site (Bluff Road, Columbia, SC).
        This alternative poses no short-term risks to on-site workers, is easily implemented, and is
        readily available.                                                i
 10.
 I- •., •
                                          <                     '      •    , '
If an innovative technology was not chosen, why not? At what stage ijvas the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      Bioreactor was eliminated because it would require excavation.
•      Land/arming was eliminated because it would require excayaitkm.
•      Chemical oxidation was eliminated because it would require excavation.
                                                -3-
                                                                                   611

-------
11.
         «      Soil washing was eliminated because it would require excavation.
         •      Low-temperature thermal desorption was eliminated because it would require
                excavation.                                                  ,
         «      In situ biodegradation was eliminated because the low permeability of site soils would
                limit its effectiveness. Furthermore, chlorinated VOCs at the site are resistant to
                biodegradation because of their sorption to soils.
         •      Soil flushing was eliminated because its effective application would be limited by the
                low permeability of site soil. Chlorinated VOCs also would be difficult to remove
                from soil.  The greatest concern was that mobilized compounds would not be removed
                completely by the extraction system and would contaminate ground water.  Also,
                washing fluids would solubilize chemicals impeding their subsequent treatment
                Finally, it was noted that soil flushing had recently failed an EPA demonstration test
         •      In situ vitrification was eliminated because it has not been widely used treating  soil
                depths similar to those at the site.'

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                          ,

        •      None
                                    1                           •»*                    '   ,
        Innovative technologies eliminated during the detailed analysis include the following:

        •     None                       ;
        Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so
        which criterion?  Which of the criteria supported the use of a standard technology?       '

        Long-term effectiveness and the permanent reduction of contaminants were the most heavily
        weighted criteria in selecting a remedial alternative.  No innovative technologies were
        eliminated, however, based on these criteria.
n'     JSfp?^8oaf,wer,eselectfd?  IfthecleanupgoalwasbasedondnARAR>whatwas'fa*
       AKAR/ What risk level was selected to establish cleanup goals?

       According to the baseline risk assessment, the cumulative chemical concentrations of surface
       soil do not pose a significant risk to human health.  Consequently, specific remediation goals
       for surface soils were not developed. The levels of contaminants in subsurface soils, however
       will continue to affect the ground water over an estimated 20 years. Therefore, remediation   '
       levels (the FS-specified remediation  goals and not cleanup levels) for subsurface soils were
       calculated based on a leaching model and MCLs for the protection of ground water
 612
                                        Cleanup Level (jig/kg)   ARAR or Other Basis
                                             -4-

-------
•'-•'• • ' • > ., .
Contaminant
Tetrachloroethene
Chloroform
Methylene chloride
Cleanup Level (jig/kg)
1,600
3,000
40
ARAR or Other Basis
Model/MCL
Model/MCL
Model/MCL
Noncarcinogens
Acetone
1 , 1 -Dichloroethane
1 , 1 -Dichloroethene
1 ,2-Dichloroethene
1,1,1 -Trichloroethane
1,1 ,2-Trichloroethane
12,000
100
270
2,100
26,000
160
Model/MCL
NJIodd/MCL
Model/MCL
Model/MCL
Model/MCL
ftjlodel/MCL
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?
                                                               '
       Innovative technologies eliminated because of cleanup goals include: |
                                               ' '    '                   i-'            •
               ••                                                       i         '           •
       •     None  -      •.  •         .        .   .    ' .               i, .

       Standard technologies eliminated because of cleanup goals include:

       »     None                   '                    •.            I                 .
                    •
  -                                        .       - ;     -.'./. i.

14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies  were conducted.


75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

       -    Proven reliability                       •'.;>..


16.    How are  measures compared?                                   j

       The chosen technology, SVE, was preferred because its effectiveness! has been demonstrated in
       a SITE.demonstration  for soils of similar porosity. It also has been shoAvn to be effective for
        semi-VOCs at another NPL site (Bluff Road, Columbia, SC).  Other
        eliminated because their reliability was unproven.  Soil flushing was
        uncertainties concerning the potential mobilization of contaminants. It was noted that soil
technologies were
eliminated because of,
                                               -5-
                       613

-------
           flushing had recently failed an EPA demonstration test (Hazardous Waste Consultant  1988) -
           In situ vitrification also was eliminated because its effectiveness at depths such as the site's
           was undetermined.
   77.
 What technical considerations were factors in selecting a remedy?  Were technical
 considerations primary in the selection of the remedy?

 The depth of the contaminated  soil, soil porosity, and soil permeability were all technical
 factors that were primary in selecting a remedial alternative.  Subsurface soil potentially
 requiring remediation extends to approximately 65 feet below land surface.  Since this .depth
 would preclude excavation, all in situ technologies requiring excavation were eliminated   The
 depth of the soil requiring treatment also was a factor for eliminating in situ vitrification  since
it had never been demonstrated at such great depths. Because of the low permeability of site
soils, in situ biodegradation and in situ soil flushing would not be effective. The soil
permeability and porosity were, however,  sufficient for SVE to be effective.
614
                                                -6-

-------
                         Oak Ridge Reservation (USDOE)
                                         OU-1
                     (United Nuclear Corporation, also OU-1)

                   Y-12 Plant, Oak Ridge, Anderson County, Tennesseje
                                       Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
      Drummed Soils/Sludges
      Strontium
      Nitrate
19.0   dpm/g
8,880  mg/L
       What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:
                                                               Site History
                                                  NPL Proposed:
                                                  NPL Final:
                                                  FS:
                                                  ROD:
                                            N/A
                                            12/21/89
                                            3/91
                                            6/28/91
                                                                Background

                                                   Federal Facility   ;
                                                   PRPs:  U.S. Department of Energy
                                                   FS prepared by: Science Applications
                                                          International Corporation
              1,958' cubic yards of drummed, cement-fixed sludge        |
              3,204 cubic yards of drummed contaminated soil
              288 wooden boxes of contaminated building and process equipment demolition debris
3.      What type of site is this?

       Department of Energy. An inactive uranium recovery landfill. It is one of several hundred
       waste disposal sites or areas of contamination at the Oak Ridge Reservation site requiring
       Superfund remedial action.
TECHNOLOGY SELECTION
_^__—^—^—.^^———^—^—~_      _                          ^
                         .
4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Fencing
       Containment:         Capping (RCRA cap, clay, asphalt, concrete, geosynthetic,
                            multilayered), underground barrier (vertical walls, horizontal walls)
                                            -1-
                                                              615

-------
  5.
          Chemical treatment-

          Physical treatment:

          Thermal treatment:
          Disposal:
                        Chemical aqueous waste treatment (neutralization/pH adjustment
                        precipitation/flocculation)
                        Waste processing, physical aqueous waste treatment (sedimentation
                        filtration, activated carbon, ion exchange)
                        Incineration                                •      -•
                        Landfill (off-site, 6n-site), treatment facility (off-site, on-site)
  Was an innovative technology considered in the FS?  If so, which'technology?

  Innovative technologies considered during the identification and screening of technically
  feasible technologies were:


  Biological treatment:   Biological wastewater treatment (aerobic, anaerobic  attached growth
                       anaerobic suspended growth)                                    '
  Phys/Chem treatment:  Chemical oxidation, soil washing
  6.
 7.
 What was the cost estimate for the innovative technology?

 During the initial screening process, in which technically feasible technologies are identified
 ft»L*  H  fT     ° °f,fAAs)' ^ FS d°eS n0t quantify costs- After the RAAs have been
 formulated, costs are typically estimated as part of a three-criteria screening process
 (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed

                                    costs were calculated during •" evaluation based on
                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
           Alternative
          RAA-3
                          Innovative Technology
                         1^M.^^•—••^___

                   Treatment using a combination of solid
                   waste processing/soil washing and
                   anaerobic fixed film/treatment of the
                   aqueous waste/modified RCRA cap
                                                                       Estimated Costs
3 Criteria

   N/A
 9 Criteria
"•"        i.

 $3,033,000
How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
           Alternative
         RAA-1
         —•ii  »^.

         RAA-2
                          Standard Technology
                  No action/site security
616
                  Multilayered capping
                                                                       Estimated Costs
                                                                   3 Criteria
  N/A
                                                                     N/A
9 Criteria

 $483,000
—  '     ' ._

$1,467,500
                                             -2-

-------
           Alternative
         RAA-4
        Standard Technology
Off-site shipment and disposal
                                                                       Estimated Costs
3 Criteria
                                                                      N/A
                                                                                  9 Criteria
              $14,073,000
8.      If ,a standard technology was chosen, why?

       RAA-2 was selected because potential nitrate and strontium-90 contarriinalion in ground water
       is remediated below the MCL under this alternative. Alternative RAA-J2 reduces the mobility
       of contaminants by encapsulating and isolating the source from the underlying aquifer system.
       This alternative minimizes farther leachate production and potential future contamination of
       ground water.  In addition, RAA-2 requires little handling or movement of the drums and
       boxes, thereby minimizing exposure to workers from fugitive dust. Also, RAA-2 is easily
       implemented because capping is a generally available technology and has been sufficiency
       demonstrated for final closures of landfills, and no further technical development is required.
       Similar caps have been extensively  used at the Oak Ridge Reservation.
9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
              '                    '         '          '         -         '!''••
 10.     if an innovative technology was not chosen, why not? At what stage \\>as the innovative
        technology eliminated?                                           I
 >   •   '            .           •         '-•••      .'..• •     ..'       •-,  I   ..
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the ^hree criteria of     .  •__
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:
                                                              ,  .        !         •  ,    •
        •     Aerobic biological treatment  was eliminated because it would! not be applicable to site
               contaminants.  The major contaminant of concern is nitrate, which requires an
               anaerobic environment for biological degradation.           I
    :    •  ,   Chemical oxidation was eliminated because it would not be applicable to site
               contaminants.  The contaminants of concern are  not oxidizablle.       ,

        Innovative technologies eliminated during the screening  of the three criteria include the
        following:  ,
                none
         Innovative technologies eliminated during the detailed analysis include the following

         •      Soil washing and anaerobic fixed film biological treatment were eliminated because
                these treatment technologies pose the greatest short-term risk}
                                               because of the extensive
                handling and movement of the drums. Also, these technologies are the most difficult
                to implement because of engineering, design, and administrative requirements.
                                                -3-
                                                                     617

-------
U.
           Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
           to meet one of the nine criteria result in the elimination of the innovative technology?  If so
           which criterion?  Which of the criteria supported the use of ^standard technology ?

           The most heavily weighted criterion in the selection of a standard remedial alternative was
           fJT- Upr0t£flon of human health and Ae environment.  The selected remedy, RAA-2  offers
           Uie highest degree of protection because  it  requires minimal worker exposure to wastes' and
           disruption of the site, eliminates the direct  contact exposure pathway, and ensures that future
           maximum nitrate concentrations in ground  water do not exceed the safe drinking water
           standard. RAA-3 and RAA-4 provide less  overall protection of human health and  the
          environment because of significant handling and processing of the waste and potential
          exposure to the environment.  The FS states, however, that the use of these treatment      ;
          technologies will reduce by 70 percent the  toxicity and volume of the main constituent  of
          concern, nitrate.  Of the technologies, only  these technologies reduce the toxicity and volume
          ot the nitrate in the source material.
                                 Sdectfd? V ^e cleanup goal was based on an ARAR, whatwasthat
                  What risk level was selected to establish cleanup goals?     .   "   ,
                       Contaminant
                                           Cleanup Level
                                                                   ARAR or Other Basis
                   Carcinogens
                  Strontium-90
                                                io-(
                                                                           Risk2
                  Noncarcinogens
                  Nitrate
                                                                      SDWA MCLb
                   in6              mUSt meet m excess uPPer bound individual lifetime cancer risk
                of 10  for strontmm-90 to prevent future contamination of ground water from landfill
                iVSStCS.

                bSafe Drinking Water Act maximum contaminant level.                  '
  13.
      Was the innovative technology eliminated because of the cleanup goals?  Could the standard
      technology meet the cleanup goals?                                            "unuum

      Innovative technologies eliminated because of cleanup goals include:

      •       None                                           .

     Standard technologies eliminated because of cleanup goals include:

     •      None
 14.     Were treatability studies conducted on the innovative technology or standard technology?
        Treatability studies were not conducted.
618
                                              -4-

-------
15.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

       -      Time to design/construct/operate                 -          »j
              Impact on nearby populations                              |                  ,
                                                                       i
                                p                       ,"                i
                                                                       i  ' .  '
16.    How are measures compared?                                     }

       RAA-3 was elimiriated partly because its implementation time is the longest of all the
       alternatives:  25 months, as opposed to 12 months for RAA-4, and 8 months for the selected
       remedy, RAA-2. The chosen alternative also will produce minimal exposure to workers from
       fugitive dust.  In contrast, alternatives RAA-3 and RAA-4 involve significant handling and
       processing of the waste, posing a higher risk of exposure to workers apd nearby populations.
                                                                       I

17.     What technical considerations  were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were  not primary in selecting a remedy.
                                               -5-
                                                                                                619

-------
                                Robins Air Force Base
                              (Landfill #4/Sludge Lagoon)
                                         OU-1

                                 Houston County, Georgia
                                        Region 4
 GENERAL SITE INFORMATTrw
 7.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:

Soil/Sludge Lagoon1 (mg/kg)
1,2-Dichloroethene 100
Tetrachloroethene 59
Trichloroethylene 2,500
Vinyl chloride 0.110
A *
Arsenic 45
Cadmium 599
Chromium-Total 6.4


Site History
NPL Proposed: N/A
NPL Final: 1987
FS: 2/91
ROD: 6/25/91

Background
Federal Facility Lead
PRPs: U.S. Department of Energy
FS prepared by: CH2M Hill
. •


Lead 972
       Soil/Landfill (mg/kg)

       Arsenic              12
       Cadmium            15
       Chromium-Total       52
       Lead                155
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •     15,000 cubic yards of soil in the sludge lagoon
       «     The volume of material in the landfill is not given; however, the landfill covers an
             area of 45 acres
   'The contaminated material in the Sludge Lagoon is a mixture of sludge, soil, and peat
620                                   _!.

-------
3.      What type of site is this?                                           j                  '

       Military.  The site is a logistics management and repair center for aircraft, missiles, and
       support systems. Operable Unit-1 includes a 45-acre inactive landfill and a 1.5-acre sludge
       lagoon.  Land use in the area is mixed residential and industrial. Part [of the site lies within
       the 100-year floodplain of the Ocmulgee River.                      j



TECHNOLOGY SELECTION                                            j

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                         .
                                                                         j

        Soil/Sludge Lagoon/Landfill                                      i          •
                                                                         i
                               /                         '                 !
        Access restriction:     Institutional controls (use restrictions, deed resstricCions, fences)
        Containment:          Capping (single-layer cap, multilayer cap), soil cover, horizontal
                              barriers, surface controls (surface sealing, grading,, soil stabilization,
                              clearing/revegetation, surface drainage)       |
        Chemical treatment:    Solidification                               ! '  '
        Thermal treatment:     Incineration (rotary kiln)                   :
        Disposal:             Excavation, on-site RCRA landfill, off-site RCRA landfill
           I                                  '                            f
                                                                   v     j                  ,
                                                                         |
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Soil/Sludge Lagoon/Landfill

        Biological treatment:   Slurry bioreactors, bioreclamation
        Chemical treatment:    Soil flushing, oxidation, chemical reduction
        Thermal treatment:    Low-temperature volatilization, soil vapor extraction, in $itu
                              vitrification
 6.      What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs, jjtfter the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria scrpening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation.  For this site, the estimated costs were calculated during sin evaluation based on
         nine criteria established by the NCP: long-term effectiveness and peirmanence; short-term
         effectiveness; compliance with ARARs;  protectiveness of human health and the environment;
         reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
         agency acceptance; and community acceptance.
                                                 2                                                621

-------
                 Cost Estimates for RAAs That Include Innovative Technologies

                           (selected remedial alternative is in bold)
       Soil/Sludge Lagoon
           Alternative
                          Innovative Technology
                                                                    Estimated Costs
                                                                3 Criteria
                                                                        9 Criteria
         RAA-2-SL
                   In situ soil vapor extraction/in situ

                   solidification
                                                                   N/A
               $6,300,000
         RAA-3-SL
                   Excavation/low-temperature volatiliza-

                   tion/solidification/onsite RCRA landfill
                                                                  N/A
              $14,300,000
7.
 How did the cost(s) compare to standard technologies?



           Cost Estimates for RAAs That Include Standard Technology

                     (selected remedial alternative is in bold)


 Soil/Sludge Lagoon
                                                                       les
          Alternative
        RAA-l-SL


        (RAA-IA-SL)
        RAA-4-SL
                          Standard Technology
                  No action
                  Limited action/institutional controls
                  Excavation/incineration/solidification/

                  replacement on site
                                                                   Estimated Costs
                                                               3 Criteria
                                                            N/A
   N/A
                                                                  N/A
                                                                        9 Criteria
                  $0
                                                                                 $0
              $17,500,000
      •RAA-l-SL and RAA-IA-SL are considered as one alternative in the FS and two in the ROD.


      Soil/Landfill                                       -
         Alternative
       RAA-la-L


       (RAA-1A-L)


       RAA-2-L
       RAA-3-L
                         Standard Technology
                  No action


                  Limited action/institutional controls
                 	•———;	__

                  Cover renovation/lagoon ground

                  water control
                 Multilayer cap/leachate and lagoon

                 ground water control
                                                                  Estimated Costs
3 Criteria


   N/A


   N/A
                                                                 N/A
                                                                 N/A
 9 Criteria
    •^MMBH


    $0



 $756,000
         	


$3,630,000b


          	


$12,200,000
622
JRAA-1-L and RAA-1A-L are considered as one alternative in the FS and two in the ROD,
                                          -3-
                                                                                                tr

-------
       bOnce selected, the cost estimate for this alternative was recalculated ijn the ROD due to the
       addition of clay in the cover renovation. The final estimated present yvorth cost of RAA-2 is
       $4.4 million to $13.3 million for a clay cover renovation, and $4.4 million for lagoon ground
       water collection and treatment.
8.      If a standard technology was chosen, why?                        ;

       Soil/Landfill         ,                                           j

       A standard technology with modifications was chosen to remediate contaminated soils in the
       landfill.  The modifications to the selected alternative, RAA-2-L, include the addition of clay
       to the cover and a leachate control system. The original RAA-2-L was rejected by EPA and
       Georgia Department of Environmental Protection (GDEP) because it jiid not comply with the
       RCRA ARAR requirement for a landfill cover of lower permeability man the underlying layer.
       The addition of clay to the landfill cover, however, will reduce infiltration-by increasing runoff
       of precipitation from the landfill cover, ensuring that the landfill cover permeability is less
       than the  underlying soil's, in compliance with the RCRA ARAR. R/^A-2-L also was selected
       because landfill leachate production will be reduced because surface water run-on will be
       diverted  from the landfill and the renovated cover will be sloped properly to minimize
       standing water.  In addition, the selected alternative is the simplest to implement.


 9.     If an innovative technology was chosen, why?

       Soil/Sludge Lagoon

       The selected alternative for soils in  the sludge kgoon, RAA-2-SL, combines in situ soil vapor
       extraction (ISVE) with in situ solidification.  An advantage of combining these treatment
        technologies is that hazardous substances can be treated without exciivatiion. This approach
        addresses the CERCLA preference for treatment while avoiding excavation, which poses short-
        term risks from release of VOG air emissions.  Thus, the treated material will not be subject to
        RCRA land  disposal restrictions (LDRs), which would have affected the implementability of
        the selected  alternative.  In compliance with ARARs, this alternative includes a cap over the
        sludge lagoon to minimize leaching and meet closure requirements. Once RAA-2-SL is
        complete it should be easier to achieve the chemical-specific, ground water ARARs. The
        practicable implementability of RAA-2-SL also is influenced by the high ground water table at
        the lagoon and the physical properties of peat.  By treating the soil in place, short-term risks to
        workers  and the community also will be reduced.  In addition, ISVE was chosen because the
        process  has  been demonstrated to be effective in removing VOCs from soil. RAA-2-SL
        removes an  estimated 75 to 90 percent of VOCs and greatly reduces! the risk of releases
        through  solidification of residual contaminants.

                                                                      1
 10.    If an innovative technology was not chosen, why not? At what stage was the innovative      ;
        technology eliminated?                                         !

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness,  implementability, and cost; or during the detailed evaluation.
                                                4-                                             623

-------
         Innovative technologies eliminated during the initial screening include the following:
                                                                                                  ,    ~   '\
         •      Soil flushing was eliminated because the heterogeneity of soils and lagoon contents             *—t-
                would preclude contaminant leaching from peat.
         »      Oxidation was eliminated because it would not be applicable.  No specific reason was
              .  given for its elimination. The FS states that the technology would be difficult to
                implement, but achieve good mixing in situ.                                                     r"
         •      Chemical reduction was eliminated because it would not be applicable. No specific
                reason was given for its elimination.  The FS states that the technology would be                  -
                difficult to implement in the lagoon's waste.                            .-                        "
         •      Bioreclamation (in situ) was eliminated because the site contaminants and soil type                I
                would preclude biological degradation.
         •      Slurry bioreactors were eliminated because the site contaminants and soil type would               ••'
                preclude biological degradation. _                                                            i

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                                                         j
                                                                                 • ~                •
        •      In situ vitrification was eliminated because its applicability is questionable and it             .    .' i'
                would not cost significantly less than demonstrated technologies such as incineration.              ;
                The high percentage of organic material in the peat could release a lot of energy as it               ;
                was heated and possibly damage the gas collection hood.  Further testing of the Btu
                value and inorganic chemistry of the peat would be required to assess whether in situ
                vitrification would be applicable.  The saturated portions of the sludge, soil, and peat
                mixture also makes this application .questionable.

        Innovative technologies eliminated during the detailed analysis include the following:

        •      Low-temperature volatilization (LTV) was eliminated because of concerns regarding its
               short-term effectiveness.  LTV would require excavation of soil, sludge, and peat
               which would create dust and erosion, thereby increasing the potential exposure of
               workers to hazardous substances.  Also, LTV would generate more noise than in situ
               treatment. LTV is part of RAA-3-SL which requires significantly more truck traffic
               than the other alternatives because of the need to import material to construct the
               RCRA landfill.  Verification was needed as to whether LTV could meet the LDR
               treatment criteria for F006 wastes. If the criteria were not met, treatability testing for
               solidification would have to be performed.  In addition, not all semivolatile compounds
               would be removed from the soil at the lower temperatures used in this technology
               EPA was planning a SITE demonstration of the LTV process on PCB-contaminated
               soils in 1990.                                                              '


11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result  in the elimination of the innovative technology? If so
       which  criterion ?  Which of the criteria supported the. use of a standard technology?

       Soil/Sludge Lagoon

       Compliance with ARARs was a major factor in selecting a remedy for contaminants in the    -
       sludge lagoon.  Under the selected alternative, hazardous substances can be treated without
       excavation; thus, the treated material would not be subject to RCRA land disposal restrictions

  624                                      5

-------
       (LDRs).  Short-term effectiveness also was important.  RAA-3-SL and RAA-4-SL would pose
       a greater risk for worker exposure to hazardous substances compared ito the selected
       alternative, because the sludge lagoon waste would be excavated and handled.
                     •    .       '    '  •           •           '           !       '
       Soil/Landfill

       Compliance with ARARs was a major factor in selecting a remedy foi- the landfill because
       action-specific ARARs (RCRA) affecting this site require a landfill cover that is less
       permeable than the underlying layer.  The selected alternative was the; only one that complies
       with ARARs by adding clay to the cover.  Overall protection of human health  and the
       environment also was a significant  factpr in selecting the remedy. Thie chosen alternative will
       achieve source control and attain remedial action objectives for protection of public  health and
       the environment.

       LTV was eliminated  because of concerns about its short-term effectiveness.
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
                                           '                            \           ,     •    . .  '
       Contaminant-specific cleanup goals were not established for soils at the sludge lagoon because
       they would depend on ground water goals (to be developed in Operable Unit 3). An RI/FS
       currently underway will develop goals for ground water based on potential receptor locations
       and fate and transport analyses.  The sludge lagoon cleanup goals most liikely will be based on
       meeting the ground water goals in a TCLP extract.
                                                          :,            I
                              '     '   '        -                         I           '
13.    Was the innovative technology eliminated because of the cleanup goqls? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

    ,   '• •',  None       "                                 '        .

       Standard technologies eliminated because of cleanup goals include:

       •      None         , • ,                                       !                  '


14    Were treatability studies conducted on the innovative technology or standard technology?
        '                           •       '    •      *             .     '        '' •     ."''.'
       Treatability studies were not conducted; however, pilot scale leachate: collection tests are
       planned, and bench and pilot-scale treatability testing of the landfill lieachate, sludge lagoon
       soils, and ground water will be performed.  The FS indicated that a treatability  study of a
       sludge lagoon sample program as part of the SITE demonstration will  indicate whether
       solidification would be effective for the contaminated soils at the.sludge lagoon. Results of
       this study were expected in July 1990.
                                               -6-                                                 625

-------
  15.
  What measures/criteria were used to compare alternatives?

  The following measures were used to compare the alternatives:

       Cost-effectiveness                     -
       Proven reliability
       Single-step vs. multistep treatment
       Preference for treatment (vs.  containment)
 16.    How are measures compared?                        ,

        The selected remedies were determined to be cost-effective.  Proven reliability was an
        important factor in comparing alternatives.  ISVE was chosen because the process has been
        demonstrated to be effective in removing VOCs from soil, and LTV also has been shown in
        both bench- and pilot-scale tests to remove more than 99 percent of chlorinated VOCs from
        soils. Because of the combination of organic chemicals and metals in the sludge lagoon
        which all have different characteristics, different technologies were combined to treat each
        substance.  For the sludge lagoon, ISVE treats VOCs and in situ solidification treats the
        remaining metals and organic compounds.  Another advantage of combining these technologies
        is that the contaminated sludge/soil mixture can be treated in place, thereby satisfying the
        CERCLA preference for treatment to reduce the toxicity, mobility, and volume of hazardous
        wastes.
 17.
 What technical considerations were factors in selecting a remedy?  Were technical
 considerations primary in the selection of the remedy?

 Technical considerations were not primary in selecting remedies; however, such considerations
 were factors in  the elimination and selection of treatment technologies.  Because of the high
 percentage of organic material in the peat, in situ vitrification was eliminated.  In addition the
 saturated portions of the sludge, soil, and peat mixture complicated  the use of this technology
The practicable implementability of RAA-2-SL is influenced by the high ground water table at
the lagoon and the physical properties of peat.  Unfavorable soilconditions, including low
permeability, high moisture content, and high humic content, could inhibit ISVE and
solidification. As a result, the long-term effectiveness of RAA-2-SL will have to be evaluated
further through site-specific predesign studies.
•it?
626
                                             -7-

-------
Sangamo Weston, Inc./Twelve-Mile Creek/Lake Hartwell PCB Contamination
                         OU-1 (Sangamo Weston, Inc.)

                           Pickens County, South Carolina        |
                                      Region 4
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil and Sediments (mg/kg)

       PCBs                      34,300
       Tetrachloroethene        ,    560
       Trichlorethene               2,500
       Xylenes                    270
       Bromodichloromethane       0.015
       Acetone                    100
       Bis(2-ethyhexyl) phthalate     0.70
       Di-ri-butylphthalate       ,    0.55
       1,2-Dichloroethene           0.062
       1,1,1-Trichloroethane         99
       1,2-Dichlorobenzene          0.57
       Ethylbenzene                41

       Lagoon Sludge (mg/kg)

       PCBs                      26,400
       Tetrachloroethene            0.011
       Trichlorethene               0.14
       Aluminum            ,      355,000
       Arsenic                    230

       Solid Waste (ppm)

       PCBs                      49,000
       Tetrachloroethene            910
       Trichlorethene  ...            8,300
       Xylenes                    5,200
       Phenol               •.:    56
       Benzoic acid                66
       Chloroform                 0.062
       2-Hexanone            .     5.7
       Isophorone                  6.5
 '.   ,   Bis(2-ethyhexyl) phthalate    '36
                                                            Site History
                                               NPL Proposed:
                                               • NFL-Final:.
                                               FS:
                                               ROD:
1/87
2/90
4/90
12/19/90
                                                           Background

                                               PRP-lead
                                               PRPs:  Sangamo "^feston, Inc.
                                               FS prepared by: RMT, Inc.
                                         -1-
                     627

-------
         Butylbenzylphthalate
         Di-n-butylphthalate
         Cyanide
         Aluminum
         Antimony
         Arsenic
         1,2-Dichloroethene
         1,2-Dichlorobenzene
         Ethylbenzene
         Toluene
         22
         40
         721
         210,000
         1.7
         200
         0.14
         7.9
         510
         960
        What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      48,200 cubic yards of contaminated soil and sediments
        •      23,000 cubic yards of lagoon sludges
        •      2,900 cubic yards of solid waste
3.      What type of site is this?

        Electrical Equipment.  A former manufacturing facility whose major products included
        electrolytic capacitors, mica capacitors, power factor capacitors, and potentiometers. This ROD
        addresses the Sangamo Plant site and six other disposal areas: Cross Roads site, Breazeale
        site, Dodgens site, Welborn site, Nix site, and John Trotter site.  Located in a predominantly
        rural area, the Sangamo Weston site is approximately 220 acres, most of which is forested.
        The Cross Roads site is about 5 acres and is heavily wooded.  The Breazeale site is about  7
        acres and vegetation consists primarily of grass cover.  The Dodgens site is 6.5 acres and
        vegetation consists of grass cover.  The Welborn site is about 4 acres and is marked by eroded
        areas with deep ravines. The Nix site is 7.5 acres and vegetation consists of grass-covered
        pasture with wooded portions.  The John Trotter site is 3 acres and consists of grass cover and
        wooded areas.  ,            .   '.      .       '
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:'
                                                                                             *
       Soil and Sediments/Sludge/Solid Waste

       Access restriction:     Fencing, deed restrictions
       Containment:          Capping (sprayed asphalt, soil, clay, synthetic membranes, concrete,
                                                                                                            •I1;"	
                                                                                " r
       Physical/chemical
       treatment:
composite cover), vertical barriers

Solidification/fixation, dewatering
       Physical treatment:     Preprocessing, mechanical dredging, hydraulic dredging
   628
                                              -2-

-------
       Thermal treatment:
       Disposal:
Incineration (rotary kiln)
Excavation, landfilling (on-site and off-site)
                                                                        I              , .
5.      Was an innovative technology considered in the FS? If so, which technology?
                           -   •                 '                       -I -           , '
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       SoU and Sediments/Sludge/Solid Waste                           i
                                                                        i       •       " "

       Biological treatment:   Batch biodegradatiori (composts), in situ biodejgradation
       Phys/Chem treatment:  Soil washing, glycolate dechlorination (KPEG process), vacuum
                             extraction, in situ steam stripping             j
       Thermal treatment:    Thermal separation (low-temperature thermal stripping (LTTS),
                             X*TRAX process), vitrification
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening protess (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        theNCP.                                                 -
                                             ''....                     i -
                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)

        Soil and SedimentsVSludge/Solid Waste                               .
Alternative
RAA-8b and
RAA-Sc
Innovative Technology
Limited ground water action/on-site
treatment of soil and sludge (LTTS
[RAA-8b]) or glycolate dechlor-
ination (RAA-8c)/on-site disposal
of solids
E<
3 Critei
RAA-8
$28,200,0
$45,500,1
RAA-S
$35,500,0
$57,000,1
timated Costs
ia
b
00-
300
c
00-
XX)
9 Criteria
RAA-8b
$28,200,058 -
$31,777,919
RAA-Sc
$35,523,616-
$41,890,406
                                               -3-
                                                                      629

-------
1^ — '
Alternative
RAA-9a,
RAA-9b
|RAA-9c, and
RAA-9d








RAA-lOb and
IRAA-lOc



-

RAA-llb and
RAA-llc




RAA-12b and
RAA-12C




RAA-13b and
RAA-13c



1

Innovative Technology
Treatment of ground water/limited
action on soils (in situ biodeg-
radation)/on-site treatment and
disposal of sludge (rotary kiln
incineration [RAA-9a]), LTTS
(RAA-9b), glycolate dechlorination
(RAA-9c), or physical stabilization
(RAA-9d)/off-site treatment and
disposal of solid wastes



Limited ground water action/on-site
treatment of soil or sludge (LTTS
[RAA-lOb] or glycolate dechlor-
ination [RAA-lOc] of soil and
sludge)/off-site disposal of solids
-

Treatment of ground water/on-
site treatment of soil and sludge
(LTTS [RAA-llb] or glycolate
dechlorination [RAA-llc])/on-site
disposal of solids

Treatment of ground water/on-site
treatment (LTTS [RAA-12b] or
glycolate dechlorination [RAA-
12c])/off-site disposal of solids
-

Consolidated remedy/no action/
limited action/excavation and
treatment of active and inactive
lagoon sludges (LTTS [RAA-13b]
or glycolate dechlorination [RAA-
13c])
Estimated Costs |
3 Criteria . •' 9 Criteria |
RAA-9a
$36,400,000

RAA-9b ,
$45,800,000-
$47,000,000
RAA-9c
$45,700,000 -
.$47,500,000
RAA-9d
$43,900,000
/
RAA-lOb
$48,000,000 -
$65,900,000
RAA-lOc
$55,000,000 -
$75,600,000

RAA-llb
$47,900,000 -
$63,300,000
RAA-llc
$55,300,000-
$78,400,000
RAA-12b
$62,400,000 -
$77,300,000
RAA-12c
$68,700,000 -
$91,000,000
RAA-13b
$13,400,000 -
$14,600,000
RAA-13c
$13,300,000 -
$15,100,000
RAA-9a
$39,569,065 -
$41,031,565
RAA-9b
$48,890,169 -
$49,189,169
RAA-9c
$48,838,169 -
$49,286,669
RAA-9d
$47,024,019-
$47,771,519
Eliminated in
FS but
presented again
in ROD.
Cost estimate
given in ROD:
$27,100,000
RAA-llb
$47,853,983 -
$51,707,063
RAA-llc
$55,285,102 -
$61,064,722
RAA-12b
$62,430,282 -
$66,145,752
1 RAA-12c ,
$68,715,557 -
$74,288,762
RAA-13b
$13,409,257 -
$13,697,857
RAA-13c
$13,345,115-
$13,778,015
    *In the evaluation of innovative and standard technologies, treatment of sediments was not
    discussed separately but was included in the discussion of treatment technologies for soil.
630
                                         -4-

-------
7.      How did the cost(s) compare to standard technologies?
                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
       Soil and Sediments/Sludge/Solid Waste

Alternative
RAA-1
RAA-2
RAA-3a and
RAA-3b


RAA-4a and
RAA-4b

- -




RAA-5




RAA-6




RAA-7

RAA-8a and
RAA-8d




Standard Technology
No action/monitoring
Limited action/institutional controls
Limited action for ground water/
containment of solids (composite cover
[RAA-3a] or multimedia cover [RAA-
3b])
Limited action for ground water/
containment of soil and sludge
(composite cover [RAA-4a] multimedia
cover [RAA-4b])/off-site disposal of
solid wastes

'

Limited ground water action/oh-site
disposal of solids



Limited ground water action/off-site
disposal of solids



Treatment of ground water/on-site
disposal of solids
Limited ground water action/on-site
treatment (rotary kiln .incineration
[RAA-8a] or physical stabilization .
[RAA-8d] of soil and sludge)/on-site
disposal of solids

Estimated Costs
3 Criteria
$5,100,000
$5,306,000
RAA>3a
$7,900,000
RA^i-3b
$8,600,000
. i
. i
i •
• !
RAA-4a
$10,3C)0,000
RAA-4b
$11,000,000
$12,700,000
"i
i
i
;
$57,01)0,000
1
I
1' ' '
,

$29,4130,000
i "
RAA-8a
$49,400,000
RAA-8d
$14,400,000
l ••
9 Criteria
$5,108,973
$5,276,164
RAA-3a
eliminated
RAA-3b
$7,851,810
Eliminated in
FSbut
presented
again in ROD
RAA-4a
$10,300,000
RAA-4b
$11,000,000
Eliminated in
FS but
presented
again in ROD
$12,700,000
Eliminated in
FS but
presented
again in ROD
$57,000,000
$29,363,716

RAA-8a
$49,414,312 -
$58,719,322
RAA-8d
$14,372,589 -
$15,677,496 |
                                             -5-
                                                                                          631

-------
            Alternative
          RAA-lOa and
          RAA-lOd
          RAA-llaand
          RAA-lld
          RAA-12a and
          RAA-12d
         RAA-13a and
         RAA-13d
         Standard Technology
 Limited ground water action/on-site
 treatment of soil and sludge (rotary kiln
 incineration [RAA-lOa] or physical
 stabilization [RAA-lOd])/ off-site
 disposal of solids
 Treatment of ground water/on-site
 treatment of soil and sludge (rotary kiln
 incineration [RAA-11 a] or physical
 stabilization [RAA-lld])/on-site
 disposal of solids
Treatment of ground water/on-site
treatment of soil and sludge (rotary kiln
incineration [RAA-12a] or physical
stabilization [RAA-12d])/off-site
disposal of solids
Consolidated remedy/no action/limited
action/excavation and treatment of
active and inactive lagoon sludges
(rotary kiln incineration [RAA-13a] or
physical stabilization [RAA-13d])
                                                                  3 Criteria
  RAA-lOa
 $64,300,000

  RAA-lOd
 $77,100,000
  RAA-lla
 $71,300,000

  RAA-lld
 $3.4,500,000
 RAA-12a
$85,100,000

 RAA-12d
$99,200,000
 RAA-13a
$14,100,000
                                                                 RAA-13d
                                                                $11,200,000
                9 Criteria
   RAA-10"
 $271,023,749

   RAA-lOd
 $27,100,000
   RAA-lla
 $71,302,695 -
 $81,320,704
   RAA-lld
 $34,541,148 -
 $35,946,432
  RAA-12a
$85,054,182 -
 $94,714,377
  RAA-12d
$99,166,517-
 $99,762,387
  RAA-13a
$14,086,297 -
 $14,836,657

  RAA-13d
$11,248,605-
       •RAA-10 is a modification of the a, b,"c, and d alternatives considered in the three-criteria
       section of the FS. RAA-10 incorporates only off-site incineration of contaminated materials.
8.     If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?

       The selected alternative, RAA-llb, has several components including:  treatment of ground
       water; excavation of materials contaminated with greater than 1 ppnuof PCBs at two of the
       disposal sites; excavation of materials contaminated with greater than 10 ppm of PCBs at the
       remaining four disposal sites; excavation of materials contaminated with greater than 25 ppm
       of PCBs at the Sangamo Plant site; and treatment of all excavated materials to 2 ppm of, PCBs
       using LTTS technology. Residuals from this treatment will be disposed of in an on-site
       landfill.  Of the treatment technologies considered, LTTS provides the best overall protection
       of human health and the environment. This technology uses an indirect heat source to remove
       contamination from the soil, thereby condensing it into a more manageable volume In
  632
                                                                             )i
                                            -6-

-------
                                                                       I
       addition, the removal efficiency of LTTS has been shown to be greater than 99.95 percent for
       PCBs.  Its effectiveness for treatment of volatile organic compounds also has been
       demonstrated.  On the basis of pilot studies, a treatment capacity of 5 tons/hour can be
       expected with this technology.  The FS states that the X'TRAX process is currently being used
       at a SITE demonstration in California.  Given the available demonstration data, this technology
       is fully implementable.  Furthermore, mis innovative technology offers pennanent treatment.
       Its combination of treatment and disposal in an on-siie secure landfill v/ill provide an effective
       means of reducing toxicity, mobility, and volume of waste constituents. Finally, RAA-llb will
       comply with all ARARs. Treatment of excavated materials over 25 pprh PCBs will meet the
       corresponding chemical-specific TSCA requirements.
                                                                       i.           '        .
                                                                       !                       '
                                                                       i,"         '
10.     If an innovative technology was not chosen, why not? At what stage wiis tlie innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.  There was no
       initial screening conducted in this FS.  Instead, a two-tiered, three-criteda approach was used.

       Innovative technologies eliminated during the first tier of the three-critpria screening  include
       the following:
                                                                       I     •       •
       •     In situ steam stripping was eliminated because it would not be applicable to PCB-
              containing areas. The FS states that EPA planned to conduct ik SITE demonstration of
              this process during the fall of 1989.                        !       ;
       •      Vitrification was eliminated because it has not been demonstrated at a CERCLA site
               with PCBs and VOCs. Also, the presence of cadmium impedes the implementation of
               this technology. The FS references three vitrification processes: the Westinghouse
               electric pyrolyzer; the Retech process; and the Geosafe Corporation process.
       •      Soil washing was eliminated because the formulation of a suitable washing fluid is
               difficult for complex mixtures.  Solvents react with or adhere to soil, reducing
               mobility. Fine particles may be difficult to remove from washing fluid. High humic
               content will limit desorption. The FS states that GSX of Greensboro, North  Carolina,
               offers a soil washing process that has successfully completed a SITE demonstration.
        •      Batch biodegradation was eliminated because anaerobic dechlprination of PCBs
               followed by aerobic degradation has hot been demonstrated Oil a Ml scale or at a
               CERCLA site.  The FS states that batch biological treatment of PCB-affected soil and
               sludge is commercially available through at least one vendor, Detox Industries.  The
               process  has been permitted in EPA Region 6.  Treatability studies would be  required
               to evaluate more fully the technology's effectiveness on Sangamo waste material.
                            •      •          •.                           ^     •  '          •   '
        Innovative technologies eliminated during the second tier of the three-jcritisria screening include
        the following:

        •     Vacuum extraction was eliminated but no reason was provided.  The FS did state,
               however, that this technology is effective in removing VOCs from soils but  not PCBs.
               It also mentioned that vacuum extraction has been demonstrated zit many sites
               including EPA's SITE program.
                                               -7-
633

-------
         Innovative technologies eliminated during the detailed analysis include the following:

         •      In situ biodegradation was eliminated because its technical implementability has not
                been demonstrated and the availability of experienced vendors is uncertain. In addition
                the long-term effectiveness of biodegradation is poor in areas where affected soils lie '
                above ground water.
         »      Glycolate dechlorination (KPEG process) was eliminated because it has not been
                demonstrated to be effective in the field and it is uncertain how protective this
                treatment would be. Also, since the technology is relatively new, it would be difficult
                to implement at the site. The FS states that the KPEG process is presently available
                on a commercial basis from Galson Services, Inc.  Galson has demonstrated the KPEG
                technology in the field in PCB-affected soil at an NPL site; however, the process is
                not yet permitted. Treatability testing would be needed to demonstrate the
                effectiveness of this process on the site's waste materials.  A:L. Sandpipe also offers a '
                similar treatment process that has not been as widely demonstrated as the KPEG
                process.
                                                                 J
        Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? if so
        which criterion? Which of the criteria supported the use of a standard technology?       '

        Soil and  Sediments/Sludge/Solid Waste

        The most heavily weighted criteria in selecting an innovative  treatment technology were long-
        term effectiveness and implementability. Treatment will eliminate waste constituent source
        areas, providing long-term, effectiveness. The chosen innovative technology is fully
        implementable based on demonstration data and test studies whereas other innovative
        technologies were eliminated because of a lack of demonstration data.

        Two innovative technologies, in situ biodegradation and glycolate dechlorination were
        eliminated because they would not meet the implementability .criterion.
72.
                         i T SdeCtfd? ?** deanUP 8°al WGS bOSed °n an ARAR> what
               What risk level was selected to establish cleanup goals?
                    Contaminant
Cleanup Level (ppm)    ARAR or Other Basis
                Carcinogens
              Tor carcinogens, an excess upper bound individual lifetime cancer risk of 10"6
              acceptable.
                                              was
  634
                                             -8-

-------
     13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
             technology meet the cleanup-goals?                                j

             Innovative technologies eliminated because of cleanup goals include:

             '•      None •            '             ,   •    ..         '  '       ,  •

             Standard technologies eliminated because of cleanup goals include:   i
                  •                      '               '           '           -!
             •      None                                                    :


      14.    Were treatability studies conducted on the innovative technology or standard technology?

             No treatability studies were conducted, During remedial design, however, a treatability study
             .will be conducted to determine'if any of the contaminated materials vfill irequire additional
             treatment beyond thermal separation in order to meet the 2 ppm criteria. If necessary, a ROD
             amendment will be completed to account for this required treatment.


      15.     What measures/criteria were used to compare alternatives?

              The following measures were used to compare the alternatives:

•'-'''       _     Proven reliability
                   Preference for treatment (vs. containment)                    !.
  .-.                              '    :                     '     *       • ;      I'-           '. .

                                                                             !,,"'•
       16.     How are measures compared?

              According to the FS, identification of remedial technologies for this ipite was based on: review
              of recent EPA guidance documents; review of SITE program results;] discussions with
              commercial vendors of specific technologies; and field observations of specific technology
              applications, both through the SITE program and private cleanups. Alternative RAA-1 Ib ,was
              chosen because its effectiveness in treating the contaminants of concern had been
              demonstrated.  The selected remedy emphasizes treatment over conbdnment, a preferred
              method because of its long-term effectiveness.
                     .                                                 'i              ' '' .
                               -.,             •        •• •    •     ,       •'-      i-

       77. •    What technical considerations were factors in selecting a  remedy?  'Were technical
               considerations primary in the selection of the remedy?

 '                              '         '                ~               j
               Technical considerations were not primary in selecting a remedy.;
                                                                                                    635
                                                      -9-        '             ! ":     '••:'.••

-------
                               Standard Auto Bumper Corp.
                                            OU-1

                                 Hialeah, Dade County, Florida
                                           Region 4
                                                                  I
  GENERAL SITE INFORMATTDNT

  /.      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:
         Surface Soil1 (mg/kg)

         Chromium
         Nickel
         Copper
         Lead
         Cyanide
         Zinc

        Subsurface Soil (nig/kg)

        Chromium
        Nickel
        Copper
        Lead
 2,300
 4,200
 600
 160
 12
 400 '
9,100
9,700
4,700
520
                              Site History
                 NPL Proposed:
                 NPL Final:
                 FS:
                 ROD:
                     6/8'8
                     10/89
                     8/92
                     9/28/92
             Background

EPA Fund-lead
PRPs:  Standard Auto Bumper
FS prepared by:  EPA
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •     2,500 cubic yards of contaminated soil


 3.      What type of site is this?                                •

       Electroplating. Standard Auto Bumper is an active chromium and nickel plating facility which
       has been in operation since 1959. The site is located in an industrialized area.
™ PpAv,,    subsurfaceusoi! did not exceed TCLP regulatory levels, indicating that there are
no RCRA hazardous wastes at the site. The TCLP results, however, do indicate contaminants
leach, thus contributing to ground water contamination.

636
                                              can
                                           -1-

-------
TECHNOLOGY SELECTION                                            i     .
                •                          '                              r
                                                      "  .      "          J
4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:     Institutional actions (deed restrictions)
        Containment:         Vertical controls (slurry walls, grout curtains, s;heetpile walls),
                             infiltration controls, capping                 ;
        Chemical treatment:   Stabilization/solidification
        Disposal:             Excavation, off-site landfill
 5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                       L
                                                                        i        •       •
        Chemical treatment:    Soil washing, soil flushing                 - i   -  •
        Thermal treatment:    In situ vitrification     •,',".'
 6.     What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP:

        RAAs designations changed in the ROD and are presented .parenthetically below.

                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-6
(RAA-3)
RAA-8
RAA-9
RAA-10
Innovative Technology
Excavation/on-site soil washing/on-site
soil replacement
In situ vitrification
Excavation/vitrification/on-site disposal
Excavation/vitrification/off-site disposal
Estimated Costs
, 3 Cjriteria
$1
3,650
$153,225
$l,b,2;25
N/A
9 Criteria
$891,650"
eliminated
eliminated
eliminated
          Total present worth costs are presented in Section 5.0 Comparative Analysis for Alternative
          Selection in the FS.
                                                 -2-
637

-------
  7.      How did the cost(s) compare to standard technologies?
                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
(RAA-2)
RAA-5
RAA-7
(RAA-4)
Standard Technology
No action
Deed restrictions/fencing
Capping/ground water monitoring
Excavation and off-site disposal
Excavation/consolidation/capping/
ground water monitoring
Excavation/stabilization/solidification/
on-site disposal/ground water
monitoring
Estimated Costs
3 Criteria
$94,700
$112,600
$198,850
$40,186
$198,850
$153,225
9 Criteria
$94,700"
eliminated
eliminated
$338,186
eliminated
$385,225
        Total present worth costs are presented in Section 5.0 Comparative Analysis for
        Selection in the FS.
Alternative
 8.      If a standard technology was chosen, why?

        The selected remedy RAA-4 (RAA-2) includes excavation of contaminated soils and
        transportation of them to a Florida Class I landfill. Treatment was found to be unnecessary for
        site wastes, due to the nonhazardous nature of the contaminated soil as defined by RCRA.  A
        cleanup action is, however, necessary to reduce the risk to human health and the environment.
        RAA-4 (RAA-2) was selected because risk of exposure from further migration of the
        contaminants through the soil is reduced by removing the contaminated soil to the cleanup
        levels.  The removal of waste off site will eliminate any long-term risks of exposure at the
        site, and no long-term monitoring at the site will be required.  This alternative also offers a
        high degree of certainty that it will be executed successfully and is considered to be an
        irreversible permanent remedy. The selected alternative provides protectiveness in a relatively
        short time (2 months). In addition the selected alternative does not require specialized
        materials and equipment beyond common excavation equipment and is a proven technique
        which would not require treatability studies.  The chosen remedy is the most economical
        alternative and offers similar protectiveness to the  other alternatives. This alternative can be
        readily implemented at the site  and complies with  all ARARs.

        The Proposed Plan identified RAA-7 (RAA-4) as the preferred alternative, in part because of
        the preference for an on-site treatment alternative.  During the public comment period,
        however, staff at Florida Department of Environmental Regulation (FDER) voiced a preference
        for RAA-4 (RAA-2) because this alternative does not require the long-term O&M that RAA-7
638
                                              -3-

-------
       would require.  In RAA-7, ground water monitoring for up to 30 years was necessary to
       ensure the integrity of the stabilization/solidification treatment.

       The Proposed Plan stated a cleanup goal for nickel only. EPA and FE>ER decided that a
       cleanup goal also was necessary for chromium.


9.     If an innovative technology was chosen, why?

       An innovative technology was riot chosen.


10.    If an innovative technology was not chosen, why not? At what stage iVas the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the | three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
             • .    '   •                .    -       •    •     '               j     . ',  '   '
       Innovative technologies eliminated during the initial screening includs the following:

        •      Soil flushing  was eliminated due to the complexity of its implementation. The FS
               states that this technology would have a number of potential pitfalls due to its
               sensitivities. In situ soil flushing depends on complete solvent contact with the waste,
               which is mainly a result of the hydraulic conductivity of the koil.. At this site, the
               average horizontal hydraulic conductivity is about 2.21 x 10':fcm/sec. Given the area's
               sandy soils, there also is the potential for uncontrolled migration of the contamination
             .  using the in situ method.  In addition, chromium removal would likely require use of a
               solvent (acid) for treatment, which could leave residual material in the soil.  Due to
               distribution uncertainties, large quantities of solutions must be applied.  Contact
               patterns and  residence time are less certain than  in the above|ground soil washing
               system. Also, this technology was chosen only at one site  iri 1990 to treat PCBs and
               metals  such as arsenic, chromium, lead, and cadmium.

        Innovative technologies eliminated during the screening  of the three criteria include the
        following:
                                                           '•"'!'                •           •
        •      In situ vitrification was eliminated because mis technology vrould be more costly  than
               the other treatment measures without providing substantially! greater public health and
                environmental protection, or technical reliability. This innovative technology would
                not offer the potential for comparable or superior performance or implementability at
                this site; fewer or lesser adverse impacts than other available approaches; or lower
                costs for similar levels of performance than demonstrated treatment technologies
                (CERCLA s330.430(e)(5)). Vitrification has not been demonstrated to be as
                technically feasible as the other treatment alternatives due tcj the subsurface conditions
                at the site. The combination  of relatively high soil permeability at the site and the
                presence of  ground water would create additional construction and economic demands
                on the process.  For the in situ process, temporary ground  water diversion would  be
                necessary. This treatment requires a minimum depth of treatment of 5 to 7 feet and
                the depth at the site is on the borderline of this  range. Vitrification also has excessive
                energy requirements to melt the soil which drive the cost uj; In addition, extremely


                                                -4-                     i                          639

-------
               httle information exists on the staged vitrification process proposed in RAA-9 and
               RAA-10.  This technology has not been actively utilized at a Superfund site and is
               only offered by three or four vendors. The success of this technology has been
               questionable, with a recent problem with off-gas collection.  Overall this process has
               not been shown to be effective on a wide-scale use and would not be justified with
               such a small quantity of soil to be treated at this site (2,500 cubic yards).

       Innovative technologies eliminated during the detailed analysis iiiclude the following:

       »      Soil washing was eliminated because this technology has not been demonstrated
               effective in attaining  the cleanup goals.  Soil washing has been selected as the
               remedial alternative at other Superfund sites (it has been selected at more than eight
               Superfund sites since 1986); however, the cleanup goals for these sites were higher
               than those for this site.  Also, soil washing was not shown to be as effective as
               stabilization/solidification for the site contaminants in small-scale treatability tests
               (process was not totally effective at removing the chromium) and soil washing would
               require a larger area for the process operation than the fixation alternative  This
               treatment technology  would reduce the volume of contaminated soil by washing the
               contaminants from the soil into a concentrated  waste stream, which would require
               additional treatment or off-site RCRA hazardous  waste disposal.  This alternative  also
               would require the longest implementation time of 5 to 7 months and therefore this
              process poses a risk of accidental exposure to the soil washing additive.  Because of
              the risk that cleanup goals might not be easily met during the soil washing process
              additional washes and additives would be needed, which would further slow the
              process.  This alternative requires treatability tests to determine effectiveness and
              optimal design prior to starting. Soil washing would require specialized equipment
              materials, and labor, which is available from a variety of vendors.  There are more'
              vendors available for stabilization/solidification that have demonstrated effectiveness
              than for soil washing.  Soil washing requires more elaborate process equipment than
              the other treatment alternative, stabilization, which would increase costs.  The nature of
              the contaminants and the characteristics of the soil have been shown to be more
              responsive to stabilization/solidification than soil washing.  <


      Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
      to meet one of the nine criteria result in the elimination of the innovative technology?  If so
      wkch criterion?  Which ofthe criteria supported  the use ofa standard'technology?

      In making the determination for off-site disposal, the modifying criteria of state acceptance
      p AY^i^vf1' Staff St ** EDER disagreed with EPA'S initial Pwfencd alternative
      KAA-/  (KAA-4) because the long-term monitoring was excessive and suggested that this
      requirement could be avoided by selecting a comparable alternative RAA-4 (RAA-2)  Upon
      re-evaluation of the two alternatives, EPA determined RAA-4 (RAA-2) Was more reliable
      long-term effective,  permanent, implementable, and cost-effective remedy for the estimated
      quantity of contaminated soil at, the site.  Long-term effectiveness and permanence also was
      weighed heavily in selecting the chosen alternative because the elimination of long-term risks
      of exposure at this site was necessary to protect ground water. The Biscayrie Aquifer is i
      located beneath the site and is the sole source of municipal drinking water for southeast
      Florida.                                                 '
640
                                            -5-

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR
Carcinogens
Nickel
Hexavalent chromium
370
52

F
Noncarcinogens
Total chromium
519
or Other Basis-

Model8
isk basedb
'.••
Ijtisk based
               Three ground water models were used to determine these soil cleanup levels.  The fate
               and transport model, MULTIMED, was used to calculate the levels of contribution to
               ground water that would be caused by given soil levels of nickel and  chromium. The
               geochemical, metals speciation model, MINTEQA2, was used to determine the relative
               mobilities of nickel, chromium, and other possible contaminants ait the site. Finally,
               the results of MULTIMED were cross-checked with a leaching-flow continuity model,
               the SUMMERS model, to arrive at the final soil cleanup level for nickel.
               "Although modeling was conducted, due to the uncertainties cjf modeling the fate and
               colloidal transport of trivalent chromium, a lexicological approach was used.  The
               cleanup levels for chromium are based on an inhalation risk, which also will ensure
               that any leachate from the site will not cause the state drinking water standard (0.1
               mg/L) or MCL (0.1 mg/L) for chromium to be exceeded. The; cleanup level was
               developed to provide a level that would result  in a risk level of less than 10"6 and a
               hazard index of less than 1.0.

        An additional performance standard was generated for this site that slates:

        •      All soil to be disposed of off site must be nonhazardous waste as defined  by the TCLP
               test (40 CFR 261).                                          :
        »      The landfill must meet FDER Class I landfill regulations.
 13.    Was the innovative technology eliminated because of the cleanup godls? Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •     Soil washing

        Standard technologies eliminated because of cleanup goals include:

        •     None                                            •. •    '.
                                               -6-
                                                                                                641

-------
 14.     Were treatability studies conducted on the innovative technology or standard technology?          HM

         According to small-scale soil washing treatability tests conducted at this site, soil washing
         would not be as effective as stabilization/solidification.  Screening-level treatability tests were
         performed during the RI and indicated site soil was not amenable to the use of test
         hydrochloric acid as an extracting agent.  Another treatability test would have been necessary
         prior to the actual application of this alternative.                                                    •      ,
                                                                       ,                  ,          _           . *
                                                                                                               c
                                                                                              '  •"' •     • ..  "   ; I:,
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Cost-effectiveness
             Proven reliability


16.     How are measures compared?

        The selected alternative would remove all waste to an off-site landfill, thereby eliminating any
        long-term risks of exposure at the site. After evaluating all of the alternatives which  satisfy
        the two threshold criteria of protection of human health and the environment, and compliance
        with ARARS, EPA concluded that the selected remedy offers the highest level of overall
        effectiveness proportional to its cost.  In situ vitrification was not chosen because it has not
        been shown to be effective on a wide scale.  Extremely little information exists on the staged
        vitrification process used in RAA-9 and RAA-10. This technology has not been  used at a
        Superfund site and is only offered by three or four vendors. RAA-4 (RAA-2) was chosen
        because this alternative incorporates proven techniques which would not require treatability
        studies.


17,     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                                      ,

        Technical considerations were primary in  selecting an alternative for this site. A soil cleanup
        level for nickel of 370 mg/kg was determined by EPA for the protection of ground water.
        This cleanup level is considerably more stringent than the protective level for direct exposure
        to soil calculated in the risk assessment (1,600 mg/kg).  EPA determined that soil cleanup
        levels are necessary to protect ground water at  this site because the Biscayne Aquifer  is
        located  beneath the site and is the sole source of municipal drinking water for southeast
       Florida.  In addition, two innovative technologies were eliminated in part because of technical
       considerations. Vitrification was eliminated because it would not be as technically feasible as
       the other treatment  alternatives due to the subsurface conditions at the site.  The combination
       of relatively high soil permeability at the site and the presence of ground water would create
       additional construction and economic demands  on the process.  For the in situ process,
       temporary ground water diversion would be necessary.  This treatment  would require a
       minimum depth of treatment of 5 to 7 feet and the depth at the site is on the borderline of this
       range.  Soil flushing was eliminated in part because with the sandy soils of the area there            J||| "\
       would be the potential for uncontrolled migration of the contamination  using this technology.         ^K /
  64:
                                              -7-

-------
                             Wrigley Charcoal Plant

                         Wrigley, Hickman County, Tennessee
                                     Region 4
GENERAL SITE INFORMATION
1. What were the principal
contaminants,
contaminant levels, and media addressed in
this feasibility study?



Maximum concentrations of principal
contaminants were:

Black Coal-Tar Waste
Site (rag/kg)
Carcinogenic PAHs



in Soil/Primary

24

Burn-Pit Wastes/Primary Site (ing/kg)

Lead
Chromium :
Copper
Zinc
Nickel
Cadmium
Barium
Black Coal-Tar Waste
Phenols
Total PAHs
VOCs
Copper
Lead
Nickel
Zinc
; Barium

1,600
- 270
7,900
2.300


Site

NPL Proposed;
NPL Final:
FS:
Interim ROD:

Bac
EPA Fund-lead
PRPs: Investigati
determine
are PRPs 1
operations
FS prepared by: 1

' ; ' •
160
36


History

NA
3/89
7/91
9/30/91

kground

sns are continuing to
whether or not there
o ftmd cleanup

ibasco Services Inc.


i

120
Leakage from Process Tanks/Primary Site (mig/kg)
- •' i ' ' •
20,000

737 , '
1,750 . • ' .
2,400
340 '
no.
110 ' .
50
Grease Pit Area/Maintenance Building (mg/kg)
Dibenzofurans-TEQ
Dioxin
0.0062 .
0.000076
       Waste and Debris Piles/Primary Site (mg/kg)

       Tentatively identified compounds
       (TICs) in tar-cubes          920
                                         -1-
                                                                                   643

-------
        Deep Sediments/Storage Basin (mg/kg)

        Semi-volatile compounds      74,032
        Metals                       6,025
        VOCs                        610

        Lagoon Sediments/Irrigation Field (mg/kg)

        Phenol                       0.013
        Toluene                      0.011
        Methylene Chloride            0.120
        Tetrachloroethene             0.005
        Lead                         0.091
        Arsenic                      0.031
        Copper                      1.2

        Soil/Athletic Field (mg/kg)

        Lead                         1,000
        Copper                      69,000
        Manganese                    3,100
        Zinc                        42,000
        Cobalt                        81
        Chromium                   56
        Barium                      640
        Aluminum                   9,400
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      3.5 cubic yards of black coal-tar waste in soil from the Primary Site
        •      15 cubic yards of burn-pit wastes from the Primary Site
        "      Approximately 19  cubic yards of black coal-tar waste leakage from the process tanks
               at the Primary Site                                      -
        •      Approximately 100 cubic yards of exposed black coal-tar waste visible in the spillway
               at the Primary Site
        •      Approximately 20  cubic yards of ACM contaminated soils at the Primary Site
        •      50 cubic yards of tar-cubes

       No interim remedial activities were proposed for the Grease Pit, Storage Basin, Irrigation
       Field, and Athletic Field.
3.      What type of site is this?

       Wood Charcoal Production. A variety of industrial operations were conducted on this site
       intermittently from 1881 to 1985. The majority of these operations consisted of pig iron and
       wood retorting/wood distillation byproduct manufacturing. The site  is located in a
       predominantly rural setting but is flanked by private residences.
  644
-2-

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                ;

        Soil/Sediments/Waste and Debris

        Access restriction:     Deed restrictions, fencing                    I
        Containment:          Capping (RCRA and non-RCRA type)
        Physical treatment:    Dewatering
        Thermal treatment:    Incineration (rotary kiln, infrared, fluidized bed)
        Disposal:             Excavation, on-site and off-site RCRA landfill, discharge to surface
                             waters           .                                              -
                                                                        i      .        •
                                                                   . '    i      •         .

5.   ,   Was an innovative technology considered in the FS? If so, which technology?
                                        '                 '               i
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                        I

        Soil/Sediments/Waste and Debris                                I

        Biological treatment:  Slurry-phase bioremediation     '           j
        Chemical/physical:    Soil washing, chemical dehalogenation  ,
        Thermal treatment:    Pyrolytic incineration,  in situ vitrification, low-ternperature thermal
                             extraction           >                                    .
                       • '    -                  •-          '   •     '         '                  • '
                                                                      •  \  ' '   •           '   '
 6.      What was the cost estimate for the innovative technology?                             *
                                                                        I'       '
        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs  are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability; and cost)  to identify alternatives that merit a more detailed
        evaluation. For this site, the estimated costs are calculated during an evaluation based on nine
        criteria established by the NCP: long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementabiljity; cost; state/support
        agency acceptance;  and community acceptance.

        No innovative technologies were incorporated into RAAs.
                                               -3-
645

-------
 7.     How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
        Primary Site
Alternative
IRAAM
IRAA2
IRAA3
IRAA4
IRAA5
Standard Technology
No action/institutional controls
Limited action: fencing/institutional
controls/site monitoring
Off-site treatment/disposal and on-site
containment of waste debris
On-site stabilization/solidification of
Storage Basin surface sediments/off-site
RCRA landfill treatment disposal of
Grease Pit soil and water debris
Soil capping with solidification at
Storage Basin/on-site treatment/off-site
RCRA landfill disposal of Grease Pit
soil and waste debris
Estimated Costs
3 Criteria
N/A
N/A
N/A
' N/A
N/A
9 Criteria
$36,000
$169,004
$953,668
($984,998)"
eliminated
eliminated
        "Interim Remedial Alternative Action.
        "Present worth cost for IRAA 3 in ROD.
8.     If a standard technology was chosen, why?

       The selected alternative was preferred because it addressed the most serious threats by
       removing or consolidating contaminated media at the Primary Site, and restricting access at the
       Primary Site and the Storage Basin.  The interim activities chosen would achieve significant
       risk reduction while a final remedial solution is developed. The selected alternative also meets
       ARARs as applicable to excavation,  transportation, treatment, stabilization, and disposal of
       contaminated media such  as coal-tar waste.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
                                                                                                           i, t,
                                                                                                           I
                                                                                                  ••sld^
    646
                                             -4.

-------
10.    If an innovative technology was not chosen, why not? At what stage was tlie innovative
       technology eliminated?    ,                                        |

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:- during the initial screening; during the screening of the tliree criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.            •
                                                        •  •  fl            i".''       '•..'"•    ' •
       Innovative technologies eliminated during the initial screening include Ithe following:

       •      Pyrolytic incineration was eliminated because it would require sophisticated equipment
               and other incineration methods were better suited for this particular application.
       •      In situ vitrification was eliminated because of the extensive energy and capital required
               to implement this technology.                               ,
       •      Low-temperature thermal extraction was eliminated because it [would be ineffective in
               remediating soils containing nonvolatile contaminants such as dioxins and
              'dibenzofurans.  .
        •      Chemical dehalogenation was eliminated but no  specific reason was given. The FS
               recognized, based  on bench-scale tests and field tests for otherJ sites, that this
               technology has obtained reduction efficiencies greater than 95 percent.  The FS also
               recognized that the APEG process has received approval from JEPA's Office of Toxic
               Substance under the Toxic Substance Control Act for PCB treatment.
        •      Slurry-phase bioremediation was eliminated due to the variety of Kite contaminants and
               the nonconformity of the site soil. In addition, the uncertainty
concerning the presence
               of dioxins at the site could complicate the use of this technology.
               Soil washing was eliminated but no specific reason was given.
               that several unfavorable characteristics of soil and waste could
The FS states, however,-
affect the effectiveness
               of this technology including: complex mixtures of waste type, variation in waste       .
               composition, and the treatment of clay soil containing semivolatiles.

        Innovative technologies eliminated during the screening of the three ciiteria include the
        following:

        •     None                                                     .
   '  •       -                     -                  .      '       . '  '
        Innovative technologies eliminated during the detailed analysis include the following:

        •'     None             '                                        i


 11.     Which of the nine criteria were weighted most heavily in selecting the^technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        The most heavily weighted,criteria in the choice of a -standard interims remedial technology for
        the site were reduction of toxicity, mobility and volume (TMV), and overall protection of
        human health and the environment.  IRAA 3 will reduce the TMV of Grease Pit and coal-tar
        contaminants, and the  mobility of surface waste by permanently removing wastes from the site.
        This  alternative also reduces or controls significant, immediate, and potential threats from
        direct exposure  to hazardous contaminants  at the site.
                                                -5-
                                                                                                  647

-------
 12.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?

Cleanup levels for the interim activities were not addressed in the FS or ROD because such
goals were beyond the limited scope of this action.
 13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•'     None

Standard technologies eliminated because of cleanup goals include:

•      None                                                                 ,
14.     Were treatability studies conducted pn the innovative technology or standard technology?

        Treatability studies were not conducted.


75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved                                            .
                                                                                                   !I,

                                                                                                 j
16.    How are measures compared?                -

       The interim RAAs were compared based on their potential to reduce risks at the Primary Site
       by eliminating or containing the most imminent and substantial threats to human health and
       the environment while permanent solutions are developed for the entire site.


17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?                              •   '

       Technical considerations were not primary in selecting an interim remedial action alternative
       for this site.                                              "
  648
                                             -6-

-------
                            Acme Solvent Reclaiming, Inc.
                                 (Morristown Plant), OU-2

                                Winnebago County, Illinois
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility ^study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sludges/Bedrock (rag/kg)

       1,1,1-Trichloroethane        0.01
       1,2-Dichloroethene           44
       Tetrachloroethene           31
       Trichloroethene     .        4.5
       4-Methyl-2-pentanone       1A
       Naphthalene                320
       Total PCBs                 290
       Aluminum                  17.9
       Arsenic                     0.0209
       Barium                     1-19
       Chromium              .   ' 14.5
       Iron                        54.9
       .Lead                       52.5
       Zinc                     •  4.44
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1982    '
9/83
7/25/90
12/31/90
             Background
•                . f '  ..
PRP-lead         |    ,
PRPs:  Acme Solvents Steering
       Committee!
FS prepared by:  Harding Lawson
       Associates |
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        Phase I1 of ROD:  Waste Areas
               6,000 tons-of soil and sludges
               Two 8,000-gallon storage tanks containing sludges and liquids
     'There are two. areas of concern at this site. The first includes the tanks
                 and waste areas; the
  second includes other less highly contaminated areas. Two documents were written during the FS to
  address these areas and the ROD is divided into two phases because the U.S. EPA and the Illinois
  EPA intend to remediate the tanks and the waste areas as quickly as possible (Phase I alternatives),
  prior to the remediation of the less highly contaminated areas (Phase H alternatives).
                                              -1-
                                          649

-------
         Phase H of ROD:  Remaining Soil and Bedrock

         «       Soil volume estimated between 4,800 and 9,100 cubic yards   .. u ~.
         »       Bedrock gas estimated at 391 pounds                       :atenai
                                                                                             *:>
 3.      What type of site is this?

         Recycling.  From 1960 to 1973, the site served as a disposal site for paints, oils, and still
         bottoms from the Acme Solvent Reclaiming, Inc., a solvent reclamation plant in Rockford
         Illinois. The site consists of approximately 20 acres of rolling uplands in a predominantly
         rural area.
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:                                                    .         .

         Access restriction:     Deed restrictions, site fencing
         Containment:          Capping (synthetic membrane, multilayer, multimedia, soil cover)
         Chemical treatment:    Fixation/stabilization
         Thermal  treatment:     Incineration (rotary kiln, multiple hearth, plasma arc, fluidized bed,
                              advanced electric reactor, "infrared), RCRA incineration
        Disposal:             Excavation RCRA landfill (on-site and off-site)

5.
 Was an innovative technology considered in the FS? If so, which technology?

Innovative technologies considered during the identification and screening of technically
feasible technologies were:

Biological treatment:   Composting, aboveground bioreactor, white rot fungus, microbial
                      degradation, soil aeration
Phys/Chem treatment:  BEST (Basic Extraction Sludge Treatment) Process, liquid gas solvent
                      extraction, soil washing, soil flushing/chemical detoxification,
                      chemical oxidation, soil vacuum extraction, dechlorination
Thermal treatment:     Thermal desorption, pyrolysis, in situ vitrification, radio frequency
                      heating
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. For this site, the costs were calculated for Phase I alternatives during an evaluation

  650
                                              -2-

-------
of the three criteria, and for Phase II alternatives during an evaluation
established by the NCP.              ,   .
based on nine criteria
         Cost Estimates for RAAs That Include Innovative Techn^lofpes
                    .(selected remedial alternative is in bold)
                                         :                    - i    '
There was no nine-criteria evaluation conducted; for Phase I RAAs.  Costs were calculated
during the three-criteria screening for each RAA and were recalculate^ in the ROD.
Phase I:  Waste Areas
Alternative
RAA-1
RAA-2
RAA-3a
RAA-3b
RAA-4a
RAA-4b ,:
RAA-5b
RAA-8a
RAA-8b
>, ' "
Innovative Technology
Soil vapor extraction/RCRA cap
Soil vapor extraction/in situ
solidification
Excavation/chemical oxidation/
solidification/off-site disposal
Excavation/chemical oxidation/
solidification/on-site placement
Excavation/soil washing/off-site
treatment of washing liquids and
contaminants/off-site disposal
Excavation/soil washing/off-site
treatment of washing liquids and
contaminants/on-site placement
Excavation, followed by low-
temperature thermal stripping/off-site
disposal
Excavation/low-temperature thermal
stripping/solidification/off -site
disposal
Excayation/low-temperature thermal
stripping/solidification/on-site
placement
Estimated Costs
3 Criteria
$1,162,000
$1,173,000
$7,990,000
$6,390,000
$6,080,000
'$4,680,000
$3,400,000
$4,30p,OCiO
$2,700,000
( •
ROD
$1,036,000
$1,173,000
$7,990,000
$6,390,000
f .
$6,080,000
$4,680,000
$3,400,000
$4,300,000
$2,700,000
 Differences in costs and RAA designations between the FS and the ROD are presented
 parenthetically below.
                                       -3.-
                                                                                      651

-------
        Phase II:  Remaining Soil and Bedrock
•"
Alternative
RAA-3b
(RAA-3)
RAA-5
RAA-6a
RAA-6b
— =s=s===
Innovative Technology
Thermal desorption (LTTS) and soil
cover
Soil cover and soil/bedrock vacuum
extraction (SVE)
Thermal desorption of soil/bedrock
vacuum extraction (SVE)
Off-site incineration and soil/bedrock
vacuum extraction (SVE)
============ 	
; 	 • 	
Estimated Costs
3 Criteria
N/A
N/A
. N/A
N/A
9 Criteria
$8,268,000"
($9,400,000 to
$14,210,000")
$9,726,000
> ($7,948,000
to
$12,475,000)
$12,657,000
($13,335,000
to
$19,186,000)
$34,605,000
($25,406,000
to
$42,140,000)
       Present worth costs are based on achieving a lO'5 risk level and on a 30-year return period
       Other costs were presented in the FS for W4 and 10'6 risk levels and a 5-year return period'
       Range corresponds to costs presented in ROD for cleaning up to a lifetime excess cancer risk
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)

       Phase I: Waste Areas
Alternative
N/A
RAA-5a
RAA-6a
RAA-6b
RAA-7
====3===
	 	 	 -==============
Standard Technology
No action
Excavation/off-site disposal
Excavation/on-site incineration/on-site
placement
Excavation/on-site incineration/
solidification/on-site placement
Excavation/off-site incineration
'
Estimated Costs
3 Criteria
N/A
$1,900,000
$13,001,100
$14,001,100
$13,000,000
========
ROD
N/A
. _
$1,900,000
$13,000,000
$14,000,000
$13,000,000
~
                                                                                           *)
                                         -4-
652

-------
     Phase II: Remaining Soil and Bedrock
         Alternative
       RAA-1
       RAA-2a
        RAA-2b
        RAA-2c
        RAA-2d
        RAA-3a
        RAA-4a
        RAA-4b
        Standard Technology
No further action following Phase I
Soil cover
 Soil cap
 Off-Site landfill disposal
 Soil fixation/stabilization
 Incineration and soil cover
 Soil cover and discharge of treated
 ground water to surface water
 Soil cover and reinjection of treated
 ground water           	,
                                                                    Estimated Costs
$5,519,000a
($2,900,000)
 $4,484,000
 ($3,700,000
     to
 $6,830,000")
 $7,352,000
 ($9,400,000
      to
 $14,210,000)
       •Present worth costs are based on achieving a 10'5 risk level and on a 30-year return period.
       Other costs were presented in the FS for 104 and 10'6 risk levels and a 5-year period.
       "Range corresponds to costs presented in the ROD for cleaning up to a lifetime excess cancer
       risk of lO"4 to 10*.                                            L
8.      If a standard technology was chosen, why?

       A standard technology was not chosen as the primary remedy.
       If an innovative technology was chosen, why?

       Phase I                             •-;..'

       RAA-8a provides the best overall protection of human health and the environment and
       provides 100 percent assurance of long-term reliability because contaminants are destroyed or
       completely removed from the site.  After implementation, RAA-8a (off-site disposal) will
       completely eliminate risks at the site, and RAA-8b (on-site placement) will allow a minimal
       risk of exposure. The selected remedial alternative relies on technologies that are relatively
        easy to construct and operate.  Low-temperature thermal  stripping ^desorption) has been
        successfully demonstrated at a U.S. EPA Superfund Innovative Technology  (SITE) project
        Because of the moderately low volume of materials to be removed and the moderately high
        throughput of the LTTS system (more than 300 tons per  day, as quoted by the vendor), the
                       '                           '                 I      '•,-'.
            .   .      c       •            '     -5-        •       -.;•':'..
                                                                      0653

-------
           time until protection is achieved is expected to be less than 3 months. In addition, the LTTS
           system has an offgas treatment system that will minimize community and worker exposure.
           Finally, RAA-8 is expected to comply with ARARs, and because this alternative either
           destroys, immobilizes, or removes the remaining concentrated waste materials from the site, it
           is expected to comply with the goal of permanence to the extent practicable.

           Phase H

           The selected alternative provides for both soil and ground water treatment and therefore
           provides the best overall protection of human health and the environment.  RAA-5 provides
           the best long-term effectiveness and permanence because this alternative treats contaminants in
           ground water, soils; and bedrock, in addition to including the soil cover or cap.
           Implementation  of the soil/bedrock SVE system to mitigate the potential for the affected
           soil/bedrock to affect underlying ground water provides additional protection to human health
           and the environment, and further reduces the toxicity, mobility, and volume of chemicals in
           the environment. Construction of the SVE system utilizes well-established, conventional
           construction techniques and should not require any unique operator skills or technology to
           operate. Vacuum extraction equipment  (SVE equipment) is commercially available  and has
           been  effectively demonstrated in U.S. EPA's SITE program. Finally, the selected alternative
           meets all  applicable ARARs.   '.
   10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                              ,

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      Pyrolysis was eliminated because inorganics form an insoluble char residue, which
        must be treated or disposed of.  This technology would not be cost effective for site
        soils with VOC concentrations less than 6 mg/kg.
»      Radio frequency heating was eliminated because it is ineffective against inorganics, it
        has been demonstrated only in one field test, highly chlorinated organics might not'be
        treatable, and it is not commercially available.
«      Composting was eliminated but no specific reason was given for its elimination.
•      Above ground bioreactor was eliminated because the site's soils do not have a high
        enough organic content to support a bioreactor.
*      White rot fungus was eliminated because this technology is not commercially available.
•      Microbial degradation (in situ) was eliminated because it has not been proven
        effective for mixed waste and the concentration of organics at the site is too low to
        support this technology.                                                '
•      Soil aeration was eliminated because it  is difficult to achieve good contact and in situ
        contact design is difficult.  In  addition, this technology has not been demonstrated and
        further development would be required.
»      BEST Process was eliminated because organic concentrations in site soil are too low
        for effective treatment.
•     Liquid gas solvent extraction was eliminated because organic concentrations in site soil
       are too low for effective treatment.
0654
                                                 -6-

-------
      •      Chemical detoxification (in situ) was eliminated because this pipcess has not been
             demonstrated fully.        ,                                 |
                                                    • • --             •    i                 • ,
      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                                        I

      n      Dechlorinatlon was eliminated on the basis of relative cost. The dechlorination
             process option would be an additional treatment step that would not provide any
             advantages over the other listed alternatives and would add considerable cost to
             treatment.
      •      Chemical oxidation (ex situ) was eliminated because this  technology would be no more
             effective than soil flushing, but its operation would cost more. Also, there are two
             potential problems with chemical oxidation: (1) the process generally is used with
             slurries with a suspended solids concentration of 3 percent or less, and (2) the lead  in
             organic sludges  will oxidize into a more toxic and mobile form (U.S. EPA,  1988); lead
             is present in some site soil.     -                         '  ' I   ''  .         .
       •     Soil washing was. eliminated because this technology would be no more effective than
              soil flushing, but would cost more to operate.               |                  ;
       •      In situ vitrification was eliminated because its performance has not  been demonstrated.
       •      Soi//Z«5Wng was eliminated but no reason was given for its elimination.  The FS
              states that this technology does not remove inorganics and that there are limited
              applications data.                                         i      •   • .     -.

       Innovative technologies eliminated during the detailed analysis include the following:
                                                                       !'         ••
       •      None         .                                 .  '' .'    |

                          • '         -"      '                           !
11     Which of the nine criteria were weighted most heavily in selecting the  technology?  Did failure
       to meet one of the nine criteria result in  the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                                        were weighed heavily in
Phase I and Phase II:  Soil/Sludges/Bedrock

Protection of human health and the environment and implementation
selecting remedial alternatives for Phase I and Phase E actions. Implementation of LTTS
treatment of waste area soils and sludges in Phase I, SVE treatment of remaining contaminated
soils  and bedrock gas in Phase II, and capping of all contaminated areas will protect against
risks  from direct contact with  soils.  In  addition, removing VOCs ftpm soils and bedrock
through SVE and LTTS will reduce  the source  of VOCs  to the aquifer  and will thereby reduce
the overall time required to remediate the aquifer.  All risks resulting from exposure will be
reduced to a 1 x 10'5 carcinogenic risk level or an HI  of  less than 1.,  RAAs incorporating
these technologies, therefore, provide excellent protection of human health and the
environment. Additionally., both of  the selected alternatives involve technologies that are easy
to construct and operate, and have been demonstrated successfully by the U.S. EPA SITE
 program.       ,
                                                                       I                        0655
                                                .7.    ...        \-  • •:..

-------
   12'    J^D^S^ 8°afS wereselected? Jfthe cleanuP Soal was based on an ARAR, what was that
          AKAKf What risk level was selected to establish cleanup goals?

          These cleanup levels are for the Phase I remedial action.  Soil vapor extraction will be
          implemented during Phase II in areas where VOCs in soil exceed the cleanup standards set
          forth below.

                 Soil Cover
0656
                       Contaminant
 Cleanup Level (ug/kg)
                                                                  ARAR or Other Basis
                   Carcinogens
                   Benzene3
                   Tetrachloroethene
                   Trichloroethene
                   Vinyl chloride3
                                                   7.9
                                                   140
                                                   16
          0.6
                                Modelb
                                                                         Model
                                                                         Model
                                                                         Model
                  Noncarcinogens
                   1,1,1 -Trichloroethane
                   1,1 -Dichloroethenea
                  1,1 -Dichloroethane3,
                  1,2-Dichloroethene
                  4-Methyl-2-pentanone
                  Naphthalene
         7,300
          0.8
          2.4
         1,430
         723
        4,550
                                                                         Model
                                                                         Model
                                                                         Model
                                                                         Model
                                                                         Model
                                                                         Model
                "While these contaminants were not detected in soil, soil cleanup levels were
                established to protect ground water.
                "Soil cleanup levels were developed using the Summers Leach Model to determine a
                VOC concentration in soils that would ensure, VOC concentrations in ground water
                would not exceed a 1 x 10'5 carcinogenic risk level. U.S. EPA's Hydrologic
                Evaluation of Landfill Performance (HELP) model was used to calculate the
                infiltration reduction provided by the soil cover and multimedia cap.  •

                Multimedia Cap with Flexible Membrane Liner:  These VOC cleanup levels are for
                LTTS residuals to be landfilled on  site.
                      Contaminant
Cleanup Level (ug/kg)
                                                                 ARAR or Other Basis
                  Carcinogens
                  Benzene3
                  Tetrachloroethene
                 Trichloroethene
                                                  69
                                                 1,200
                                                 140
                               Model"
                               Model
                               Model

                                              -8-

-------
13.
Contaminant
Vinyl chloride3
Cleanup Level (jig/kg)
0.52
ARAB or Other Basis
Model
/V pn rare inn gens 	 ...
1 ,1,1-Trichloroethane
l,l-Dichloroethenea
1 , l-Dichloroettianea
1 ,2-Dichloroethene
4-Methyl-2-pentanone
Naphthalene
64,000
6.9
21 .
13,000
6,100
40,000
. , Model
Model
Model
Model
Model
Model
      While these contaminants were not detected in soil, soil cleaniip levels were
      established to protect ground water.                                  j     •
      "Soil cleanup levels were developed using the Summers Leach Model to determine a
      VOC concentration in soils that would ensure VOC concentrations in groundwater
      would not exceed a 1 x 10'5 carcinogenic risk level. U.S. EPA's HELP model was -
      used to calculate the infiltration reduction provided by the soil cover and multimedia
      cap.          •                                          i
    ,  .   •             .                   .   .   '  .             i                      •
      In addition PCBs must be treated tp 10 mg/kg.            '!.."'.
          , '               .               "        •             I  ,  "      .        ,.

Was the innovative technology eliminated because  of the cleanup goals? Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include;

•     None              '                                    ]• ...'.•-'

Standard technologies eliminated because of cleanup goals include:
                                                              I .        -
 •      None                                                  !
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.
 75.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Cost-effectiveness
              Proven reliability
              • Preference for treatment (vs. containment)  ,.
                                                                                                 0657

-------
  16.     How are measures compared?

          Phase I, RAA-8 and Phase II, RAA-5 achieve significant risk reduction at a total present worth
          cost of 515,012,000 to $16,612,000.  Alternatives involving incineration offer a somewhat
          higher degree of permanence but at a significantly.higher cost. Other alternatives are less
          costly than the preferred alternatives, but provide less treatment. The chosen alternatives are
          therefore cost effective.

          Several innovative technologies were considered for Phase I.  LTTS followed by solidification
          was selected because it afforded a higher degree of certainty of achieving the remedial action
          goals For all contaminants than some of the less established technologies considered  Radio
          frequency heating and white rot fungus, considered for Phase H RAAs, were eliminated
          because of concerns about reliability and  commercial availability of these technologies.  Soil
          aeration, chemical detoxification, and vitrification, considered for Phase II RAAs,  were
          eliminated because these technologies have not been demonstrated.

          The selected remedies for Phase I and Phase II represent the maximum extent to which
          permanent solutions and treatment technologies can be utilized in a  cost-effective manner at
          this site. RAA-5 was chosen over RAA-4 for Phase II because RAA-4 would not treat: VOCs
          in soil and bedrock.
  77.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedy for this site. Because site
soils did not have a high enough organic content, the aboveground bioreactor, microbial
degradation, the BEST Process, and the liquid gas solvent extraction procedure were
eliminated from consideration.
 References

 U.S. EPA.  1988.  U.S. Environmental Protection Agency. Technology screening guide for treatment
         of CERCLA soils and sludges. EPA/540/2-88/004.
0658
                                              -10-

-------
                          Allied Chemical and Ironton Coke
                                         OU-2

                                      Ironton, Ohio
                                        Region 5
GENERAL STTE INFORMATION

/.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Coke and Tar Plant Soil (rag/kg)
  2.
        Benzo(a)pyrene
        Naphthalene        ,
        Benzene        •'   ' •

        Ice Creek Sediment (mg/kg)

        Naphthalene

        Lagoon Materials (mg/kg)

        Benzo(a)pyrene
        Naphthalene
        Arsenic
        Benzene
                          330
                          32
                          8
                           38
                           2,000
                           17,000 .
                           0.026
                           0.067
                                                      Site History
                                          NPL Proposed:
                                          NPLFinal:
                                          FS:
                                          ROD:
                    N/A
                    1983
                    7/90
                    12/90
            Background

PRP-lead        !
PRPs:  Allied-Sigrial, Corp.
FS prepared by: IT Corp!
What volume of material is to be remediated?

The volume of material to be remediated included:

•      40,000 cubic yards of soil
•      150,000 cubic yards of sediments in Ice Creek
•      579?,000 cubic yards of sediments and debris in lagoons
   3.      What type of site is this?                          ,
                                                                    K
          Coal Products.  An inactive coke plant and an operable tar plant located in an
          industrial/residential area, adjacent to Ice Creek, a tributary of the Ohio River.
                                               -1-
                                                                                           0659

-------
                                                                                                               J-'
     TECHNOLOGY SELECTION

     4.      What standard technologies were considered for selection in this FS?

                            Jgies considered during the identification and screening of technically feasible
                       Fencing, deed restrictions
                       Capping (asphalt, multimedia), slurry wall, grout curtain, sheet piling,
                       grout injection, block displacement, cultivation (in situ stabilization)
                       Solidification/stabilization (cement-based, silicate-based, thermoplastic-
                       based, organic polymer-based, lime-based, self-cementing)
                       Incineration (cyclone, infrared, rotary kiln, fluid bed, cement kiln
                       multiple hearth, high-temperature fluid wall, corona  glow, plasma arc
                       circulating bed, ocean), industrial boiler/furnace, glassification
                       Landfill (on site, off site)
            Access restrictions:
            Containment:

            Chemical treatment:

            Thermal treatment:


            Disposal:
                                                                                                    ;;t	:
                                                                                                   i
     5.
Was an innovative technology considered in the FS?  If so, which technology?

Innovative technologies considered during the identification and screening of technically
feasible technologies were:                                                        J

Biological treatment:   Land application, microbial degradation (in situ biodegradation)
Phys/Chem treatment:  Soil aeration, solvent flushing
Thermal treatment:     Low-temperature thermal stripping, molten salt incineration, in situ
                      vitrification, thermal desorptioh, pyrolysis
    6.      What was the cost estimate for the innovative technology?

            During the initial screening process, in which technically feasible technologies are identified
            (pnor to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
            formulated, costs are estimated as part of a three-criteria screening process (effectiveness
            implementabihty, and cost) to identify alternatives that merit a more detailed evaluation '-The
            the NCP  C°StS ^ ^ rCCalCUlated during m evaluatio«  based on nine criteria established by


                     Cost Estimates for RAAs That Include Innovative  Technologies
                                (selected remedial alternative is In bold)
0660
— ==============
Alternative
RAA-2
RAA-3
==============================================
Innovative Technology
Bioremediate lagoon materials and
soils/limited action — sediments/ground
water management control
Bioremediate lagoon materials and
soils/localized slurry wall/ground water
management control
=========================
Estimated Costs
3 Criteria
$39,912,100
$39,564,200
9 Criteria
eliminated
eliminated
                                                                                                    :f-

                                                                                                    • E
                                      -2-

-------
Alternative
RAA-4
RAA-5
 RAA-11A
 RAA-11B
 RAA-12A
 RAA-12B
  RAA-13
  RAA-14
  RAA-18
       Innovative Technology
Bioremediate lagoon materials/no
action—soils/limited action—
sediments/ground water management
control
Bioremediate lagoon materials/ landfill
soils on siteAimited action—
sediments/ground, water management
control
 Partially bioremediate/incinerate lagoon
 materials and soils on siteAimited
 action—sediments/ground water
 management control	.
 Partially bibremediate/beneficial use of
 lagoon materials and soils as a fuel in
 off-site industrial boilers/sediments/
 ground water management control
 Partially bioremediate/incinerate lagoon
 materials and soils on site/bioremediate
 Ice Creek sediments/ground water
 management control	.
 Partially bioremediate/beneficial use of
 lagoon materials and soils as a fuel in
 off-site industrial boilers/bipremediate
 Ice Creek sediments/ground water
 management control         A
                                                           Estimated Costs
                                                      3 Criteria
                                                     $36,863,800'
                                                      $39,264700
                                                     $124,331,100
                                                      $82,147,800
                                                     $127,321,700
                                                       $84,359,800
  Bioremediate/solidify and stabilize
  lagoon materials and soils/solidify arid
  stabilize Ice Creek sediments/ground
  water management control   .
                                                       $67,273,900
  Partially bibremediateAandfill lagoons
  materials and soils on site/limited
  action—sediments/ground water
  management control         	
  Bioremediation of Lagoons 1 through
  4 and beneficial use of Lagoon 5 as a
  fuel in on^site industrial boiler/
  bioremediation of coke plant soils/
  capping of tar plant soilsAimited
  action—sediments/ground water
  management control
                                                       $50,164,100
 9 Criteria
  eliminated
   eliminated
$121,745,000
   eliminated
 $131,728,000
  $77',578,000
                                                           eliminated
                                                            eliminated
                                                           NA*
   $49,528,000
 "This RAA was developed for the nine-criteria screen.
                                       -3-
                                                                        0661

-------
     7.      How did the cost compare to standard technologies?

                      Cost Estimates for RAAs That Include Standard Technologies
                                (selected remedial alternative is in bold)
OGG2
               Alternative
              RAA-1
              RAA-6
              RAA-7
             RAA-8
             RAA-9
             RAA-10
             RAA-15A
             RAA-15B
             RAA-16
             RAA-17
         Standard Technology
 No action
 Solidify/stabilize lagoon materials,
 soils, and sediments/ground water
 management control
 Landfill lagoon materials and soils on
 site/limited action—sediments/ground
 water management control
 Partial on-site incineration and
 beneficial use of lagoon material and
 soil as a fuel in off-site industrial
 boilers/limited action—sediments/
 ground water management control
 Landfill lagoon materials, soils, and
 sediments on site/ground water
 management control
 Landfill lagoon materials and soils off
 site/limited action—sediments/ground
 water management control
Partially solidify and stabilize/
incinerate lagoon materials and soils
on site/solidify and stabilize Ice Creek
sediments/ground water management
control
Solidify and stabilize/beneficial use of
lagoon materials and soils as a fuel in
off-site industrial boilers/solidify and
stabilize Ice Creek sediments/ground
water management control
Landfill lagoon materials, soils, and
Ice Creek sediments on site after
solidification and stabilization/ground
water management control
Landfill lagoon materials and soils off
site after solidification and stabili-
zation/limited action—sediments/
ground water management control
                                                                      3 Criteria
                                                                             $0
                                                                     $47,483,600
                                                                     $42,979,300
                                                                    $166,793,700
                                                                    $50,229,400
                                                                    $133,465,500
                                                                    $120,839,200
                                                                    $83,519,700
                                                                    $72,546,200
                                                                   $153,667,600
  9 Criteria
                                                                $0
  eliminated
  eliminated
 $161,120,000
  eliminated
  eliminated
  eliminated
,$85,677,000
 eliminated
 eliminated
                    -4-
                                                                             "y.

-------
Alternative
RAA-19
Standard Technology
Cap and slurry wall of lagoon
materials/no action oh soils/limited
action — sediments/ground water
management control
Estiimated Costs
3 Criiteriia :
N
A*.
9 Criteria
$30,946,000
       'This option was not costed in the three-criteria screening, but was added- later:


8.      If a standard technology was chosen, why?                                 ,  ,
                           •   '      "                .  .'  ..       -        t-     • \         .
        A standard technology was not selected.                      ,    i

                                                                  - -  .  L
                                  '.-,._                        i
9.     . If an innovative technology was chosen, why?            .   *     !

       RAA-18 was selected because it reduces and controls potential risks to human health and the
       environment posed by exposure from ingestion of contaminated soils; and ground water. The
       contaminated soils will be treated via bioremediation and waste fuel recovery to reduce their
       toxicity and carcinogenicity. The soils and waste will be treated so that risk levels associated
       with ingestion  of contaminated soil and waste will fall within the cumulative risk range of. 10"4
       to 10"6 for carcinogenic compounds and so that the  cumulative hazard indices for
       noncarcinogens will be less than one.  Implementation of this alternative will not pose
       unacceptable short-term risks or cross media impacts. ^The selected remedy is designed to
       meet all ARARs except where it will be necessary  to receive waivers form the State.  The
       waivers are justifiable because "compliance with such requirements is technically impractical
       from an engineering prospective" and "the remedial action selected will attain a standard of
       performance that is equivalent to that regarded under the otherwise applicable standard,
       requirement, criteria, or limitation, through the use  of another methods or approach."  The
        chosen alternative provides long-term effectiveness since two waste treatment technologies will
        be utilized at the  site.  Bioremediation and waste fuel recovery will be applied to soil and
        waste materials. Each of these technologies permanently destroys the waste constituents.  It is
        the most cost-effective option.
                         •           '          .                   .      I           •
        The selected remedy represents a slight modification to the original RAA-18 alternative, which.
        included the addition of land treatment bioremediation of Tar Plant |soils (thereby  increasing
        the volume of soil to be treated with bioremediation) and off-site disposal of the ash and
        scrubber wastes resulting from the waste fuel recovery.
                                                •          .     -        I       .  •     •
                                '               '                        j.  ,
                                                                       I-
 10.    If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?  .                                      ,                       .
                                   1  .                                 i             "   '
        Innovative technologies could be eliminated from the remedial technology selection process  at
        three stages:   during the initial screening; during the screening of tip three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                                -5-
0663

-------
         Innovative technologies eliminated during the initial screening include the following:

         •      Soil aeration was eliminated because of extended depth, composition, and large
                volume of waste involved.
         •      Solvent flushing was eliminated because of the large areal dimensions of the site and
                the presence of sticky tar-like substances indicate a substantial volume of fluid would
                be needed for flushing.
         •      Low-temperature thermal stripping was eliminated because it would not achieve the
                temperatures necessary to volatilize the semivolatiles in the wastes.
         •      Molten salt  incineration was eliminated because it would be unable to process either
                the semisolid, solid, or both forms of known wastes at the site.      "•   •
         •      In situ vitrification was eliminated because the technology would not be applicable to
                the waste zones with free flowing water.  At the site, the ground water table intersects
                the bottom-most wastes at the site.  In addition, the large amount of waste to be
                treated is a negative aspect.
         •      Thermal desorption was eliminated because it is hot applicable to treating all site
                wastes.

         Innovative technologies eliminated during the screening of the three criteria include:
                                                                                      t
         •      Land application was not incorporated into an RAA; however, no explanation for its
                elimination  was provided.                                ,
         •      Bioremediation of lagoon materials was eliminated because lagoon materials possess a
                high heating value and the process was deemed to be less effective than using this
                waste for beneficial fuel.  In addition, certain portions of non-solubilized contaminants
                may persist  in the environment.

         Innovative technologies eliminated during the detailed analysis include:

         •      None
                                                            '
 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion? Which of the criteria supported the use of a standard technology?

         The criteria weighted most heavily in selecting a remedial  alternative were long:term
         effectiveness and permanence, reduction of contaminant toxicity, and'cost.  The chosen
         alternative will provide the greatest permanent reduction of site contaminants for the least cost.
  12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
         ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Total carcinogenic
PAHs"*
Arsenic
0.97
0.56
Risk"
Risk
0664
-6-

-------
13.
Contaminant
Total carcinogenic
PAHs
Benzene
Cleanup Level (mg/kg)
1.4
0.485
Noncarcinogens
Naphthalene
650
ARARbr<
Grounc
Groun
r
Groun
              Total carcinogenic PAHs is defined as the total concentration of benzo(a)pyrene,
              chrysene, and ,dibenzo(a,h)anthracene.                        !'-''',.      •'  t
              "Cleanup levels are based on the site-specific risk assessment assuming the ingestion ot
              contaminated" soil by future residents,.and represent the concentrations that pose an
              excess upper-bound individual lifetime cancer risk of 10" .
              Cleanup levels were established to protect ground water and are meant to ensure that
              remaining contaminant levels will not exceed the ground water cleanup levels.

              *Two cleanup levels were developed for total carcinogenic
              soiywaste cleanup and one for the protection of ground water.
                                                                    PAHs at this site; one for
      Was the innovative technology eliminated because of the cleanup goals?  Could the standard
      technology meet the cleanup goals?  •    ,               '

      Innovative technologies eliminated because of cleanup goals include:

       •   '   None                     "  ' •           ,      •  .    ''   •

       Standard technologies eliminated because of cleanup goals include:.

       •      None     . •                             .


14.     Were treatability studies conducted on the  innovative technology or Standard technology?
                                                                       I
       Treatability study were not conducted.                             j
 75.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

                Cost/unit risk
                Proven reliability
               . Preference for treatment (vs. containment)
                                                -7r
                                                                                            0665

-------
   16.     How are measures compared?

          The selected remedy was preferred because through the destruction'of-waste and contaminated
          soil it will greatly reduce the threats to human health by reducing site contaminant toxicity
          Stabilization would have limited the potential for exposure of the waste to humans and the
          environment; however, the permanence of stabilization has not been fully demonstrated and
          would have to be modeled in a pilot study prior to implementation. Also, stabilization would
          be more difficult to implement given the uncertainty regarding the development of an effective
          solidification process. Capping was considered the least permanent option because none of the
       „  waste actually would be destroyed. The chosen option is cost effective because it is
          considerably less expensive than other alternatives which achieve similar effectiveness
   17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedial alternative.
68G

-------
                           American Chemical Service, Inc.
                                     Griffith, Indiana
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and mec"
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediment/Waste (mg/kg)

       BEXT Compounds
       Chlorinated Benzenes
       Chlorinated Ethenes
       Chlorinated Ethanes
       Ketones
       Phthalates
       PAHs
       Phenols
       PCBs
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      135,000 cubic yards of soil, sediment, and waste
linants,
iddressed in

ncipal



3,002
11
1,110
11
0.7
0.15
m-
2
Site History
NPL Proposed:
NPL Final:
FS:
ROD:
Back

PRP-lead
N/A
9/84
6/92
9/30/92
ground


PRPs: Not identified
FS prepared by: Warzyn Inc.




i
26 ' ' ' .-.-':•
 3.     What type of site is this?

        Recycling.  Formerly a solvent recovery facility, a chemical manufacturer now is located on
        the site, which is in a residential area.
 TECHNOLOGY SELECTION                   ,

 4.      What standard technologies were considered for selection in this FS.'
          ' •  •            '                   '                  .       ''             '
         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
                                      ' '                               i' .
         Access restriction:    Fencing, deed restrictions
         Containment:         Capping (clay, asphalt, concrete, multilayer), surface grading, injection
                             grouting, vegetative cover, dust control
                                              -1-
687

-------
  5.
  Phys/Chem treatment: Fixation (in situ, ex situ), in situ photolysis
  Thermal treatment:    Incineration (rotary kiln, infrared)
  Disposal:             Excavation, RCRA landfill (on-site, off-site)


  Was an innovative technology considered in the FS?  If so, which technology?

  Innovative technologies considered during  the identification and screening of technically
  leasiole technologies were:             .

  Biological treatment:   Biodegradation (aerobic, anaerobic, in situ, ex situ), bioreactor,
                        landfarming, bioharvesting
•  Phys/Chem treatment:  Oxidation/reduction (in situ, ex situ), dechlorination, vacuum vapor
                        extraction (in situ, ex situ),  solvent extraction (in situ, ex situ) soil
                        washing (in situ,  ex situ), in situ steam stripping, in situ radio
                        frequency
  Thermal treatment:     Low-temperature thermal treatment, in situ vitrification, wet air
                        oxidation
 6.
       was the cost estimate for the innovative technology?
          rin    ,K                PrOC6SS' in *hich technic*»y feasible technologies are identified
        (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have
        formulated, costs are typically estimated as part of a three-criteria screening pro^eVs
        SSST?1 ;7Iementf **-. ** cost> «° ^ntify alternatives that merila more detailed
        ^criteria                         C°StS W£re <" duri<* - Cation based on
                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
        Soil, Sediment, and Waste
           Alternative
         RAA-3B
         RAA-4
         RAA-5
         RAA-6A
                           Innovative Technology
                   Excavation/on-site low-temperature
                   thermal treatment of waste
                  —	—^	.	.	
                   In situ  steam stripping of buried waste
                   and soil
                  Excavation/on-site incineration of
                  buried waste/in situ vapor extraction of
                  soil

gy
— 	
rature
ed waste
ied waste
lOf
•action of
	 ! 	
Estimated Costs
3 Criteria
—
N/A
. N/A
N/A
N/A

9 Criteria
$43,150,000
_
$48,950,000
	
$31,050,000
$41,150,000

688
                                             -2-

-------

Alternative
RAA-6B
RAA-7B
RAA-8A
RAA-8B

Innovative Technology
Excavation and on-site low-tempera-
ture thermal treatment of buried
waste/in situ vapor extraction of soil/
on-site disposal/cap
On-site low-temperature thermal
treatment of buried waste and soil
Excavation and landfarming of buried
waste and soil
Excavation and slurry-phase bioreactor
treatment of buried waste and soil
Estimated Costs
3 Criteria
N/A
NJ/A
Isf/A
1>I/A
9 Criteria
$35,850,000
$62,450,000
$32,250,000
$41,250,000
7.     " How did the cost(s) compare to standard technologies?              I
                                  •                                     i •
                 Cost Estimates for RAAs That Include Standard Technologies.
                            (selected remedial alternative is in bold)     j
• Alternative
RAA-1
RAA-2 •_•
RAA-3A
RAA-7A
Standard Technology
No action
Slurry wall/natural flushing of waste,
soil, and sediment
Excavation and on-site incineration of
buried .waste
On-site incineration of buried waste and
soil
Estimated Costs
3 Criteria
H/A
N/A
1
1
N/A
i1
N/A
'
9 Criteria
$0
$10,050,000
$52,850,000
$82,650,000
 8.      If a standard technology was chosen, why?

        Solidification/stabilization and off-site disposal were selected for some wastes.
        If an innovative technology was chosen, why?                     '

        RAA-6B was chosen because it provides the greatest protection to humain health and the
        environment since it will reduce site risks to 10'6.  This alternative will reduce risks of direct
        contact to waste and soil. The treatment technologies proposed—low-temperature thermal
        treatment (LTTT) and in situ vapor extraction (ISVE)—will remediate site contaminants to
        required cleanup  levels for waste and soil respectively.  These treatment technologies
        permanently remove site contaminants, thereby providing long-ternj effectiveness and
                                                         •              i p    ..'•-.

       ,    '        -              ' "            -3-              -'      {•'•"'.           •
669

-------
         eliminating the need for long-term maintenance.  LTTT was preferred because it has been
         proved, affording a great degree of certainty towards achieving remedial cleanup.  While ISVE
         is less certain ofmeeting final cleanup levels, soils that fail to meet those levels will then be
         -ated with LTTT.  RAA-6 was preferred over alternatives that would require excavation
         • ,ich would pose short-term risks to workers and nearby residents.  The chosen alternative
         offers a great degree of protection. Though its costs are somewhat higher than for other
         alternatives, it is the most cost-effective. While incineration would provide comparable
         protection, LTTT was preferred because it is less expensive
 10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?

 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages:  during the initial screening; during the screening of the three criteria of
 effectiveness, implerrientability, and cost; or during the detailed evaluation.

 Innovative technologies eliminated during the initial screening include the following:

 »      Ex situ solvent extraction of waste was eliminated because of the very high levels of  '
        contaminants in the waste and because the waste matrix would not be amenable to
        phase separation by this technique.
 •      Soil washing (in situ,  ex situ) were eliminated for soil and waste because of their
        complex organic matrix, as well as the hydrophobic nature and high soil adsorption
        affinity of most of the detected VOCs and SVOCs. Because of the high organic
        concentrations, aqueous-based solutions would not be effective in extracting organics
        which would likely remain preferentially dissolved in the oil phase.
 •      Ex situ oxidation/reduction was eliminated because the cost would likely be
        prohibitive due to the  large volume of materials involved.
 »      Wet air oxidation was eliminated because it would be applicable only to aqueous waste
        streams, and not to solid, sludge, or slurry-phase waste matrixes.
 •      Bioharvesting was eliminated because the depths and concentrations of site
        contaminants would be too great for contaminant accumulation in plants
 »       In situ oxidation/reduction was eliminated because it would be  too difficult  to monitor
        and adjust in situ.
•       In situ solvent extraction was eliminated because implementation would be difficult
        Uniform distribution of contaminants would be necessary, and agitation and sufficient
        contact time  would be  required, which would not be possible in situ. Furthermore
        most extraction  solvents are toxic, which could affect ground -water if adequate    '
        collection systems are not developed.
•      In situ radio frequency for waste was eliminated because of the exorbitant energy
       requirements  associated with  volatilizing areas of concentrated waste.  Furthermore a
       health and safety risk could be posed  by uncontrolled VOCs emission that could either
       escape the capture system or  create a potentially explosive gas stream
•          /0"TewooaS eliminated because * would not be applicable to nonchlorinated
             and SVOCs, and there is presently no means of applying it to soils.

670
                                             -4-

-------
 Innovative technologies eliminated during the screening of the three criteria include the
 following:                                                         t

 •      In situ biodegradation (aerobic, anaerobic) was eliminated because: the incomplete
        degradation of organic contaminants could create toxic byproducts; chlorinated •
        compounds might not be amenable to aerobic treatment; the complexity of organic
        contamination at the site requires both anaerobic and aerobic treatment; uniformly
        distributing oxygen and nutrients would be difficult because of the nonhomogeneous
        zones of permeability; high levels of site contaminants are expected to be toxic to
        microorganisms; and no studies have demonstrated that this technique would be
        successful  in such a contaminant matrix.
 •      In situ vitrification  was eliminated because high organic 'contaminant levels could
        overload the  offgas treatment system; a combination of high soil permeability and the
        presence of ground water and buried drums could interfere with the technique, possibly
        causing electrical shorting; the soil moisture content that is constantly being recharged
        by the high water table would require dewatering and capping before the vitrification
        process; vitrified  source areas would interfere with present ground water flow patterns;
        the technique has not been demonstrated on  a full-scale  basis; iind volatilized gases
        could migrate away from the treatment zone and spread to gresiter depths.
 •      Ex situ low temperature thermal treatment was eliminated because no commercial are
        available presently.  .'    '.      ,
'••••.  Ex situ vacuum vapor extraction was  eliminated because it would be less effective and
        more costly than  in situ vacuum vapor extraction.             j
 •      In situ solvent extraction for soil was eliminated because it has not been demonstrated
        on a full-scale basis; vendor availability is limited; the. complexity of site contaminants
        would make  it difficult to identify a single solvent or appropriate mixture of extraction
        solution; waste would be generated that would require disposal; arid other processes
        offer comparable effectiveness at similar costs.               j
 •      In situ radio frequency for soil was eliminated because it would  not be amenable for
        treatment of  PCBs  and inorganic metals, it has not been demonstrated on a full-scale
        basis, and  it  has high operational costs!
 •      Ex situ biodegradation (aerobic, anaerobic) was eliminated because high organic
        contaminant  concentrations  would likely be toxic to microorganisms.
                 ''.'-•         •  '      '        .        ''•.!•''.••'•''-.•
 Innovative technologies eliminated during the detailed analysis include I the following:

 •      Landfarming was eliminated because its effectiveness and imp] ementability are
        uncertain.  The technique has  not been demonstrated on a contaminant matrix or scale
        analogous to the  site.  Furthermore, excavation would be required, which would
        present a short-term risk to  site workers and nearby residents.
 •      Bioreactor was eliminated because its effectiveness and impletnenliability are uncertain.
        The technique has  not been demonstrated on a contaminant matrix or scale analogous
        to the site. Furthermore, excavation would be required, which [would present a short-
        tejm risk to  site workers and nearby residents,     .  .         .                   "
 •      In situ steam stripping was  eliminated because it has not been [demonstrated on a full-
         scale basis, no known vendor is available, and the augers usedSto treat  the waste could
        puncture the clay-confining layer and introduce contaminants to  the lower aquifer.

-------
11.
12.
        Which of the nine cntena were weighted most heavily in selecting the technology? Did failure

        to meet one of the nine criteria result in the elimination of the innovative technology? If so

        nhich criterion?  Which of the criteria supponed the use of a standard             '
                                                        m°St heavily in selecti°g a
                 , ^   i                ** m°St 6ffeCtiVe a1*6™1"6 in Coving the risk posed by
        contanunated soil, the technique was eliminated because the excavation of waste and soil
        would expose site workers and nearby residents.


        Landfarming and bidreactor treatments were eliminated because of short-term risks to workers
        and residents. In situ radio frequency was eliminated, in  part because of its high cost.  In situ

                                       extraction were eiiminated because *
  672
                         ,                            8°al WaS based °n an ARAR' wh*t was that
                     risk level was selected to establish cleanup goals?


               Soil, Sediment, and Waste                  *
                     Contaminant
                                        Cleanup Level (mg/kg)   ARAR or Other Basi
                Carcinogens
                Tetrachloroethene
                bis(2-Ethy!hexyl)

                phthalate
                Trichloroethene
               Pentachlorophenol
               4,4'-DDD
               "    ^~m^.^—^_


               2,4-Dinitrotoluene
               1,1-Dichloroethene
               Carbon tetrachloride
               bis(2-Chloroethyl) ether
                                            -6-

-------
Contaminant
4,4-DDT
Chloroform
Hexachlorobutadiene
1,2-Dichlorethane
Methylene chloride
1 ,2-Dichloropropane
Hexachlorobenzene
gamma-BHC (lindane)
Cyclic ketones.
1,1,2-Trichlorethane
n-Nitrosodiphenylarriine
1,1,2,2-
Tetrachloroethane
Vinyl chloride
alpha-BHC
beta-BHC
, 2,6-Dinitrptoluene
4'4'-DDE
1 ,4-Dichlorobenzene
Heptachlor epbxide
Cleanup Level (rag/kg)
0.088
9.5
0.36
0.64
6.2
0.42
0.018
0.046
7.3
0,51.
12.0
0.28
0.031 :
0.0047
0.016
0.044
0.16
2.4
0.0033
ARAR or Other Basis
Risk
Risk
: Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Noncarcinogens . 11
Antimony
Toluene
Cadmium
Ethylbenzene
Barium
Chromium VI
Naphthalene
N-chain alkanes
Nitrogenated benzenes
1,1,1 -Trichloroethane
15-0.5
, 5,000-167
51-2
1,300-43
2,600-87
1,400-47
; 82-3 .
760-25
6.2-0.2
2,300-77
Risk"
Risk
Risk
^ Risk
Risk
Risk
Risk
Risk
Risk
Risk
-1- . . - ^ .--..'.
673

-------
                          Contaminant
                          Cleanup Level (mg/kg)
                                                                       ARAR or Other Basis
                     Branched alkanes
                     ———————

                     4-Methyl-2-pentanone
                                 630-21
                                 —™—>™^^M*


                                 490-16
                     Methyl propyl benzenes
                     Halogenated alkanes
                                2,300-77
                                •~-^—^—^^i^«i


                                0.63-0.02
                                —'      ...


                                1,300-43
                     Endosulfan I
                     Dimethyl ethyl

                     benzenes
                     1,2-Dichloroethene (cis)


                     2-Butanone
                                 250-8.3
                                 ———™«^


                                 620-21
                    Noncyclic acids
                                1,000-33


                                  85-3
                    Methylated

                    naphthalenes
                                                    2,400-80
                                                     •MHBWMb


                                                     150-5
Chlorobenzene
                    Xylenes (mixed)
                              26,000-867
                                     ii ii


                               1,200-40
                    Oxygenated benzenes


                    Diethyl benzenes
                    Propenyl benzenes
                    1,2,4-Trichlorobenzene
                                16-0.5


                               2,700-90
                   Chloroethane
                 •For carcinogens, an excess upper bound individual lifetime cancer risk of 10'" was

                          r,     noncarcinogens, a Hazard Index (HI) from 1.0 to 0.03 was acceplable
                        policy for unrestricted access sites.


                     »» of1cleanuPulevels ^ noncarcinogens corresponds to His of "1.0 to 003 "

                      0 03  value nught relate to a Hazard Quotient of 0.3 to allow for exposure' to '

                 multiple contaminants whose effects might be additive
674
                                               -8-
                                                                                                              i,,;

-------
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None '                 ,                                   [ •   '      :

       Standard technologies eliminated because of cleanup goals include:    |
                                                                        'I           .
      ; •      None
14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted. Treatabilities studies will be conducted to determine if
        in situ vapor extraction will be able to meet remediation levels.  If in isitu vapor extraction
        cannot meet cleanup levels, VOC/SVOC-contaminated soil will be excavated, treated with low-
        temperature thermal treatment to health-based standards, and redepositpd.  A pilot study of in
        situ soil washing using various surfactants performed jointly by the U.S. EPA and Air Force at
        the Volk Field fire, training pit showed no appreciable decrease in organic contaminant concen-
        trations  in soil following 7 days of flushing.  In situ soil flushing was jdeemed ineffective for
        contaminants with a high affinity for soil adsorption, such as the site contaminants.
 17.
 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

              Preference for treatment (vs. containment)
              .Impact on nearby populations
              Proven reliability


 16.     How  are measures compared?     .          .
                                                                         i
        The chosen alternative provides a high degree of effectiveness and permanence through source
        treatment, which was preferred over containment. The magnitude of risk to on-site workers
        and nearby  residents posed by excavating soil resulted in RAA-6B being chosen instead of
         RAA-7, the most effective alternative. Proven capability also was an
                                                                 important factor.  Two
         alternatives (landfarming and slurry-phase bioreactor treatment) were 3liminated due to the
         lack of proven reliability and the need for extensive treatability studies.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

Technical considerations were primary in selecting a remedy.  Biohatvesting was, eliminated
because the contaminants were too deep for it to be effective.  In situ biodegradation was
eliminated because it would be difficult to implement since the site w[as comprised of
nonhomogeneous zones of permeability. In situ vitrification was elinjiinated because the high
water table would make  it difficult and expensive to implement.
                                                -9-
                                                                                       675

-------
                   Berlin and Farro Liquid Incineration, Incorporated
                                    Swartz Creek, Michigan
                                           Region 5
  GENERAL SITE INFORMATION

  1.      What were the principal contaminants,
         contaminant levels, and media addressed in
       ,  this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil/Sediment (rag/kg)

         Arsenic              68
        Benzene             i
        Ethylbenzene         23
        Toluene              21
        Xylenes              240
        Lead                 118             1
        Hexachlorobenzene    7
                                                            Site History
                                               NPL Proposed:
                                               NPL Final:
                                               FS:
                                               ROD:
N/A
9/8/93
12/22/89
9/30/91
                                                           Background

                                              PRP-lead
                                              PRPs:  Berlin and Farro Trust Fund,
                                                     National Bank of Detroit, Trustee
                                              FS prepared by: Woodward-Clyde
                                                     Consultants
 2.      Wtiat volume of material is to be remediated?

        The volume of material to be remediated included:

        •     48,000 cubic yards of soil and sediment
3,      What type of site is this?

       Industrial Landfill. A former liquid incinerator and landfill.,


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?


                  weref" C°nSidered ^ ** identification and serening of technically feasible
       Access restriction:
       Containment:
  676
                     Fencing, deed restrictions
                     Capping (concrete, multimedia, clay, asphalt), synthetic membrane
                     revegetation, slurry wall, sheet piling, grout curtains, sprayed on liners
„,   .   ,             Sllt barners, vibrating beam, grout injection                        '
Chemical treatment:   Stabilization, precipitation, polymerization, detoxification, chelation

-------
       Physical treatment:
       Disposal:
Mechanical aeration
Excavation, off-site disposal at RCRA facility
5.      Was an innovative technology considered in the FS? If so, which technology?
                                                                         I
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:    "
                                                  i       '       L.      "  I'

       Biological treatment:    In situ aerobic degradation, in situ anaerobic degradation
       Chemical treatment:    Soil flushing (solvent), dehalogenation, hydrolysis, reduction
       Thermal treatment:     Low temperature thermal stripping, ground freejzing, in situ
                              vitrification, steam stripping                 j,
        What was the cost estimate for the innovative technology?  .
                                                                                     V       '
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       -implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        by theNCP.
                                            •-   •       '                 •  \
        No innovative technologies were incorporated into remedial alternativejs.
 7.      How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4

Standard Technology
No action/long-term monitoring
Fencing/deed restrictions/ground water
restrictionsAong-term monitoring
Fencing/deed restrictions/slurry wall/two
multimedia caps/ground water
monitoring ~ ' • ,
Fencing/deed restrictions/excavation of
soils with risk in excess of lO^/off-site
disposal/clay cap/ground water
collection, treatment, and discharge to
surface water
Estimated Costs
1
1
3 Criteria
$iob,ooo
$425,000 ,
$7,0^5,000
i
1
$7,420,000
1
..
9 Criteria
$100,000
$425,000
$7,045,000
$7,420,000
                                                                                                     677

-------
             Alternative
            —»^—^—••
           RAA-5
           RAA-6
          RAA-6A
          RAA-7
         RAA-7A
         RAA-8
         RAA-9
           Standard Technology
  Excavation of soils with risk in excess
  of ICTVon-site incineration/cap/ground
  water collection, treatment, and
  discharge to surface water
  Fencing/deed restrictions/excavation of
  soils with risk in excess of 10'6/
  multimedia liner/leachate collection/ on-
  site fly ash solidification/ground water
  collection, treatment, and discharge to
  surface water/long-term monitoring
  Deed restrictions/excavation of soils
  with risk in excess of lO^/off-site
  disposal at RCRA facility/backfill/
  reyegetation/ground water collection,
  treatment, and discharge to surface
  water
 Fencing/deed restrictions/excavation of
 soils with risk in excess of 10'6/
 multimedia liner/leachate collection/
 Portland cement solidification/ multi-
 media cap/ground water collection,
 treatment, and discharge to surface
 water
 Fencing/deed restrictions/excavation of
 soils with risk in excess of 10'6/
 multimedia liner/leachate collection/
 Portland cement solidification/multi-
 media cap/ground water collection, and
 off-site treatment and discharge
 Fencing/deed restrictions/excavation of
 soils with risk in excess of 10'6/fly ash
 solidification/multimedia cap/ground
 water collection, treatment and
 discharge to surface water for 10 years

Fencing/deed restrictions/excavation of
soils with risk in excess of lO^/fly ash
solidification/multimedia cap/ground
water collection, treatment and
discharge to surface water for 30 years
                                                                          Estimated Costs
3 Criteria
                                                            9 Criteria
                                                                      $8,645,000     $8,645,000
                                                                     $10,415,000    $10,415,000
                                                                    ,$13,100,000    $13,100,000
                                                                    $11,635,000
                                                                    $11,610,000
                                                                    $5,930,000
                                                                    $7,450,000
             $11,635,000
                                                                                                      i
             $11,610,000
             $5,930,000
            $7,450,000
678
                                              -3-

-------
          Alternative
         Selected
         Alternative
        Standard Technology
Deed restrictions/excavation of soils
with risk in excess of W*/fly ash
solidification/disposal of waste into
on-site RCRA containment cell/
remove free liquid/backfill/
revegetation/ground water collection,
treatment, and monitoring
                                                                      Estimated Costs
                                                                  3 Criteria
                                                                     N/A
9 Criteria
$8,119,300"
       This alternative is proposed for the first time in the ROD.
8.      If a standard technology was chosen, why?
                                            - '          '   .             'I            ,
       The selected alternative was developed and presented in the ROD. Fnim nine developed
       alternatives, EPA selected a remedy that combines the soil and on-site sediment excavation
       element of RAA 6 and the off-site sediment excavation and the groundwater treatment
       proposed in RAA 9. For the selected alternative, approximately 48,OOQ cubic yds. of on-site
       contaminated soil, sediment and drain sediments will be disposed of on-site in a cell which
       will meet the ARAR requirements of RCRA Subtitle C and Michigan Act 64.  Treatment will
       remove free liquids and solidify the materials.  The proposed cell will have: 1) more long-term
       effectiveness and permanence than RAA-6, the engineered cell described in the FS (treatment
       will be required for any excavated materials  exhibiting characteristics of RCRA hazardous
       waste), 2) Michigan has promulgated rules that specify general  standards for clean-up of
       contaminated sites in Michigan and which are considered ARARs (these rules establish criteria
       for three acceptable cleah-up types - type A  achieves background levels, type B achieves
       specific standard risk-based clean-up levels,  and type C is based on site-specific risk
       assessment - only those remedies which dispose of all materials which exiseed Type B clean-up
        standards in a cell that satisfies Michigan Act 64 and RCRA minimum technology
        requirements meets the type C criteria, 3) treatment of contaminated Soils and sediments to
        remove free liquids and stabilize  characteristic wastes reduces leachate migration, 4) uses
      1  common  construction equipment  and readily available technology.

        The selected remedy was different from the remedy in the Proposed P|lan (July 1990).  The   .
        Proposed Plan identified on-site incineration of approximately 38,000 cubic yards. PRPs and
        the public expressed strong opposition to on-site incineration.  Opposition was based pn the
        short-term  risk presented by the estimated 380 days of operation of the incinerator. In addition
        incineration is not considered an effective treatment for metals. Off-site disposal proposed by
        the community was not selected  by EPA because of the questionable 'availability of using
        hazardous  waste disposal capacity for materials with relatively low levels of contamination and
        the transportation risks associated with off-site disposal.
        .If an. innovative technology was chosen, why?

         An innovative technology was not chosen.
                                               -4-
                                                                                               679

-------
 JO.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?

  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages:  during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  •      In situ aerobic degradation was eliminated because soil constituents (metals) would
         inhibit microorganism metabolism.  Furthermore, the site's nonuniform hydrogeology
         and the soil's high moisture content would make implementing this technology
         difficult.                                                            .  • 6J
  «      In situ anaerobic degradation was eliminated because it would be a slow and
         incomplete process, which is considered an experimental technology for small
         quantities of waste materials.
  •      Soil flushing was eliminated because it is only for the most mobile elements/
         compounds and its effectiveness in clay soils has not been demonstrated
  •      Ground freezing was eliminated because the technology has not been proved and
         associated thermal maintenance costs would be high.
  •      Hydrolysis was eliminated because of the toxic byproducts that would be generated
         and it is an unproven technology.

 Innovative technologies eliminated during the screening of the three criteria include the
 following:

 »       Dehalogenation was eliminated  because it has been tested only on oily wastes and
         sludges containing PCBs; clay soils at the site would require extended reaction times
         special separation processing and result in poor solvent recovery;  no data is available
         on laboratory investigation of process effectiveness on C-series compounds, and- is in
         pilot scale development which is not sufficiently developed to warrant further
         consideration.
 «       Steam stripping was eliminated because it would not be effective in soils with low
         permeability, in saturated  soils, or in nonuniform hydrogeology.
 •      In situ vitrification was eliminated because it has  not been used in any large-scale
        commercial applications; long term effectiveness of the process  is unknown; saturated
        soils at the site would create large volumes of water vapor and overburden the off-gas
        emission control system, resulting in an increase in the volume of wastewater for
        treatment; higher electrical and operating costs would also result from treatment of
        saturated soils; consolidation of soils and sediments would increase treatment
        effectiveness  but would increase  short term impacts to the community; additional costs
        would be incurred in bnnging the required power to the site-ability of the off-gas
        collection system to capture  all generated gases is uncertain; cost estimate? are much
        higher than costs of other remedial technologies.        "
•      Low temperature thermal stripping was eliminated because it has not been proved
        effective.                              ,

Innovative technologies eliminated during the detailed analysis include the following:

•       None
6SO
                                             -5-

-------
11.
12.
 13.
Which of the nine criteria were weighted most heavily in selecting the \technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?
                   •"-'""•                '.     •      !
Community acceptance was a major factor in on-site disposal, because of the rejection of
incineration originally proposed by EPA. Compliance with state ARARs for clean-up were
also of major importance in selecting the remedy.     ,              -vj
                                                               .  i.   ' "
No innovative technologies were incorporated into remedial altemativeis.

       . •   •-"                                    •  •              -i
                                                                 i      .  •
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (rag/kg)
ARAR
or Other Basis
Carcinogens
Benzene
Lead
Arsenic
Hexachlorobenzene
(C-66)
0.02
20.8
10.6,
1.4

Risk8
Background11
Background

Noncarcinogens
Toluene
Xylene
Ethylbenzene
16
6
1-4
Risk

Michigan Actc
M
ichigan Act
Michigan Act
                "Cleanup levels are health-based and reduce risk to less than 10"6.
                bCleanup levels are based on natural background levels.
                These cleanup levels, determined according to Rule 299.5711. of the Michigan
                Environmental Response Act (Michigan Act 307), establish standards to prohibit
                ground water contamination.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?                               j

 Innovative technologies eliminated because of cleanup goals include:

 •     None           .  '                                       i      :
                                                                ''      •               >
                                                              '     •       , --  .
 Standard technologies eliminated because of cleanup goals include:   !

 •     None        •      '..          .           "'          '      . '•
                                                -6-
                                                                                          681

-------
 14.
 15.
 Were treatability studies conducted on the innovative technology or standard technology?

 Treatability tests were conducted for soil stabilization technologies by Hazcon, Inc.  Soil
 stabilization tests showed that volatile organics are released, and semivolatiles and metals are
 immobilized; several tested compounds are effective stabilizing agents; and fly ash is the least
 expensive stabilization agent, but generates higher metal leachate concentrations.


 What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:  >

        Risk level achieved                     ,
        Total cost
        Proven reliability
        Preference for treatment (vs. containment)
16.     How are measures compared?     ,                         •  '    ,

        The selected alternative was preferred because it reduces soil contaminants to the lowest risk
        level achieved (10') by a proposed alternative.  The chosen alternative emphasizes treatment,
        which was preferred over containment because of its long-term effectiveness. Of all the
        alternatives that incorporated waste treatment, the chosen alternative cost the least. The
        treatment technology proposed in the preferred alternative was deemed to be reliable  Two
        technologies (dehalogenation and low temperature thermal stripping) were eliminated because
        they are still under investigation and their reliability and effectiveness is uncertain
17.
Wliat technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

The nonuniform site hydrogeology and low permeability of the site soil were technical
considerations that were factors in the elimination of several innovative technologies including-
in situ aerobic degradation; steam stripping; soil flushing; and in situ vitrification.  These site
characteristics were considerations but were not primary in the selection of the remedy.
   682
                                              -7-

-------
                                Buckeye Reclamation
                                         OU-1

                        Richland Township, Belmont County, Ohio
                                        Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Soil

       No principal contaminants were addressed in
       the, feasibility study for the soils at the site.
       However, samples from the waste pit, soils,
       leachate, ground water, and surface water
       were analyzed. The following twelve
       contaminants were included in the risk
       assessment:
       Inorganics

       Arsenic
       Beryllium
       Lead
       Cadmium
       Chromium
       Nickel
              Organics

              Benzene
              Trichloroethene
              Carbon tetrachloride
              1,1-Dichloroethene
              Carcinogenic PAHs
              Toluene
       Waste pit contaminants (rag/kg)
Benzene
Toluene
Ethylbenzene
Xylenes
Chromium
                     19
                     142
                     303
                     907
                     0.276
                                                               Site History
                                                  NPL Proposed:
                                                  NPL Final:
                                                  FS:
                                                  ROD:
                                                                N/A
                                                                9/8/93
                                                                4/30/91
                                                                8/19/91
             Background

PRP-lead
PRPs:  Ohio Resource (Corporation;
       Cravat Coal Company; Ashland
       Chemical Company; Aristech
       Chemical Company (formerly
      ' U.S. Steel Corporation); Beazer
       East, Inc. (formerly Koppers
       Company, Inc.); Triangle PWC;
       SKF Industries; Kittle Hauling
FS prepared by:  Versar,  Inc.
2.      What volume of material is to be remediated?  ,

       The volume of material to be remediated included:

       •     1,300,000 cubic yards of soils

'                  •             ,         .               \
3.     What type of site is this?

       Municipal Landfill.  A municipal solid waste landfill site.
                                            -1-
                                                                                        683

-------
  TECHNOLOGY SELECTION

  4.       What standard technologies were considered for selection in this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:                                                                -

          Access restriction:     Deed restrictions, fences
          Containment:         Capping (clay/soil, asphalt, concrete, standard landfill cap, RCRA cap)
                               injection grouting                                  .
          Chemical treatment:   Solidification/stabilization, lime fly ash injection
         Thermal  treatment:     Incineration (rotary kiln, 'multiple hearth, fluidized bed, plasma arc,
                               infrared), high temperature fluid wall reactor
         Disposal:             RCRA landfill
         Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:

         Biological treatment:   Composting, solid phase treatment, in situ biodegradation, slurry phase
                               treatment
         Chemical treatment:    Chemical oxidation/reduction, soil washing (solvent), dechlorination, in
                               situ vacuum vapor extraction, soil flushing (solvent), in situ chemical
                               treatment
        Thermal treatment:  •  Thermal volatilization, wet air oxidation, molten salt incineration, in
                               situ vitrification, pyrolysis
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have be.en
        lormulated, costs are estimated as part of a three-criteria screening process (effectiveness
        implementabihty, and cost) to identify alternatives that merit a more detailed evaluation  'llie
        estimated costs then were recalculated during an evaluation based on nine criteria established
        by the NCP.  No innovative technologies were considered technically feasible during the initial
        screening process, therefore no costs were estimated.               '
'Ill;
 i
634
                                               -2-
 t v_

-------
7.'     How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-4A
RAA-4B

Standard Technology
No action
Institutional actions •', . .
RCRA, Subtitle C cap/chemical
treatment of ground water
RCRA cap/wetlands treatment
Ohio Administrative Code solid
waste (standard) landfill cap/
chemical treatment of ground water
Ohio Administrative Code solid
waste (standard) landfill cap/
wetlands treatment
Estimated Costs
3 Criteria
$0
$1,786,000
$196,913,0010
$193,084,000
$52,492,000
$48,663,000
9 Criteria
$0
eliminated
$196,913,000
$193,084,000
$52,492,000
$48,663,000
 8. '    If a standard technology was chosen, why?                       |      ,

        An Ohio Administrative Code solid waste landfill cap was selected because: 1) it would
        provide protection to trespassers by covering contaminated soil, 2) reliable technology for
        minimizing infiltration and reducing leachate, 3) the types of contaminants in the soils pose
        difficulties in implementing treatment, 4) short term health risks involved in excavation, 5)
        high cost of excavation and treatment versus little overall environmental benefit, and 6) it is a
        well proven technology.                                      .
 9.      If an innovative technology was chosen, why?                   . j.

         Wetlands treatment of leachate was selected because: 1) it is effective over the long term, 2)
         once established wetlands should be a self contained system, 3) will increase water quality
         which benefits wildlife habitats.
                                                                       i                _
  10.     If an innovative technology was not chosen, why not? At what stage\ was the innovative
         technology eliminated?                         -                ;       ' .

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.
                                                -3-
                                                                                                  635

-------
          u

          m
  Innovative technologies eliminated during the initial screening include the following:


  *      ?   >OSt"%' SOMPhase treatment' and in situ biode^-idotion were eliminated because
          tht  would not be effective for treating some inorgar,cs that are not readily
          biodegradable.                                                       *      '
  »      Slurry phase treatment was eliminated because of the large volume of material to be
          remediated.
  »      Chemical oxidation/reduction was eliminated because it would treat selected inorganics
          at specific PH ranges and would not be applicable for the type and range of organic
         'contaminants present at the site.
         Soil washing was eliminated because it is  only applicable when used in conjunction
         with other treatment technologies.
         Dechlorination was eliminated because chlorinated hydrocarbons are not the
         predominant contaminants at the site.

  *      ln fVu  "I™"™ Vap°r extraction was eliminated because, due to low soil permeability
         and the fractured bedrock around the site,  a vacuum system would be difficult to
         implement.
  "      Soil flushing was eliminated because the site soil's low permeability would impede the
         distribution and collection of treatment solutions.
  •      In situ chemical treatment was eliminated because, due to the presence of organic
         compounds in soils and the low permeability of soils, effective  distribution of reagents
         would be difficult.
  »      Thermal volatilization was eliminated because iMias been demonstrated for hazardous
         waste only on a pilot-study scale.
  •       Molten salt incineration was eliminated because the technology has not been proved
         on a large scale for the various wastes present at the site.
  "       In situ vitrification was eliminated because the technology only  has been demonstrated
         on hazardous waste in lab- and bench-scale tests.

 Innovative technologies eliminated during the screening of the three criteria include the
 following:                             '     •


 •       Wet air oxidation was eliminated because implementation would require excavation of
        large volumes of material  that pose potential health risks.

 Innovative technologies eliminated during the detailed analysis include the following:

 "      None                                                               .       .
if-
 11.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so
which criterion?  Which of the criteria supported the use of a standard technology?       '

Cost weighed and long-term effectiveness were weighted heavily in the selection of the
treatment technology.
636
                                               -4-

-------
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? Whatfisk level was selected to establish cleanup goals?
                                                            •           i
       No cleanup goals were specified for the remediation of soils because llhe selected source
       control response action was containment.
                           ' '                       p '       "'      ' .'•   '        •          '  "

13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?
                                                                      ' i       ,_'•••-
       Innovative technologies eliminated because of cleanup goals include:

        •      None
                                     '                         .'!'•'
        Standard technologies eliminated because of cleanup goals .include:  |
                                                     '                  !
        •     'None,  •        '-   -                            '     '•.   \' ''"''"   ^    • '

                                                                       \           -   '
 14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                      •  -               I-
        No treatability studies were conducted on source control remedies. However, treatability
        studies were planned for this site to assess the effectiveness of the wetlands treatment method.
        The objective of the treatability studies is to determine if the levels, of contaminants of
        concern, mainly metals, can be lowered to meet discharge limits.


 75.     What measures/criteria were used to compare alternatives?

        The  following measures were used to compare the alternatives:

               Total cost
               Waste left in place/institutional control
               Time to design/construct/operate
               Proven reliability


 16.    How are measures compared?

        The large volume of waste present at the site prohibited the use of technologies requiring
        excavation due to potential adverse impacts on workers, high costs, iind the time required to
        implement such measures. The option to contain wastes was therefore deemed the most
        feasible for the site.
                                                  1      -              ' !
                 •                   '                  "                 "I             .         "
  17.     What technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection  of the remedy?

         The landfill's slope was a primary technical consideration in selecting the Ohio Administrative
         Code solid Waste landfill cap.  The steep slope prohibited the installation of a RCRA cap.  The
                                                                       I     -             "_

   .  -  ;      '     -,   ':           '*'    '      -5-'   ".'•   .-•  '        i       ' :.             '637

-------
       presence of fractured bedrock, soil's low permeability, and the volume of waste to be
       remediated were all factors in selecting an appropriate remedy.
                                                                                                      F..	
                                                                                                      \,f-
638
                                          -6-

-------
                                Butterworth #2 Landfill
                                  Grand Rapids, Michigan
                                          Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
 2.
       Soil (mg/kg)

       Arsenic
       Beryllium
       Chromium
       •PCBs
       Dieldrin
                            43
                            8.5
                            43,000
                            72
                            5
What volume of material is to be
remediated?
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                     N/A
                     12/82
                     10/31/91
                     9/29/92
             Background
                 i   .  -
PRP-lead
PRPs:  Butterworth Landfill Steering
       Committee
FS prepared by:  McLaren/Hart
       Environmental Engineering
       Corporation
        The volume of material to be remediated included:
                                                                     i. ' •     >" :
        •      3,000,000 to 5,000,000 cubic yards of waste. The Butterwoitii Landfill encompasses
               approximately  180 acres.
 3.      What type of site is this?         '                          •    j

        Municipal Landfill.  The site is a former municipal landfill that received both residential and
        industrial wastes until 1973.  The site is located predominantly within the 100-year flood plain
        of the Grand River.  The area immediately surrounding the site is predominantly industrial.
 TECHNOLOGY SELECTION
 	:	:    :         '                        ,     .     |

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
         Access restriction:
         Containment:
         Chemical treatment:
         Thermal treatment:
                      Institutional controls (fencing, deed restrictions)
                      Capping (low permeability, soil cap)
                      Stabilization/solidification
                      Incineration
                                              -1-
                                                                                   639

-------
 5.
        Disposal:
                        Excavation, landfill (on-site, off-site)
  Was an innovative technology considered in the FS? If so, which technology?

  Innovative technologies considered during the identification and screening of technically
  feasible technologies were:

  Biological treatment:   Biodegradation, to situ bioremediation
  Chemical treatment:    Soil washing, soil flushing, solvent extraction, soil vapor extraction
  I nermal  treatment:     Dechlorination, in situ vitrification
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (pnor to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated  as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation  The estimated costs are calculated during an evaluation based on nine criteria
        established by the NCP.

        No innovative technologies were incorporated into the RAAs.
7.
How did the cost(s) compare to standard technologies?

          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)

The designation of RAAs changed in the ROD, These changes are presented parenthetically
DwJQ inr ,*                .                         .
630
=====
Alternative
RAA-1
RAA-2
RAA-6/
RAA-II
(RAA-2)
RAA-7/
RAA-IIA
RAA-8/
RAA-IIB
======================
Standard Technology
No action/monitoring
Institutional controls/monitoring
Soil cap (Michigan Act 641 cap)/
establishment of alternative
concentration limits (ACLs) for
ground water
Soil cap (Michigan Act 641 cap)/
upgradient vertical barrier for ground
water
Soil cap (Michigan Act 641 cap)/
ground water extraction
===========================,
Estimated Costs
3 Criteria
$1,400,000
$1,800,000
$15,230,000
. $16,820,000
$16,590,000
9 Criteria
$l,400,000a
eliminated
-~— — — __ __ _
$15,230,000
$16,820,000
$16,590,000
                                             -2-

-------
 9.
Alternative
RAA-9/
RAA-HC
RAA-10/
RAA-m
RAA-11/
RAA-fflA
(RAA-3)
RAA-12/
RAA-IHB
RAA-137
RAA-fflC
(RAA-4)
•
Standard Technology
Soil cap (Michigan Act 641 cap)/
downgradient vertical barrier for ground
water/ground water extraction
Low permeability cap (Michigan Act
641 cap)
Low permeability cap (Michigan Act
641 cap)/upgradient vertical barrier for
ground water
Low permeability cap (Michigan Act
641 cap)/ground, water extraction
Low permeability cap (Michigan Act
641 cap)/downgradient vertical barrier
for ground water/ground water
extraction
Estimated Costs
3C
$2(V
$24,!
$26,:
riteiria
wo.poo
)00,000
540,000
$26,310..,000
$30,
150,000
9 Criteria
$20,440,000
$24,900,000
$26,540,000
$26,310,000
$30,150,000
       The no action alternative presented in the ROD does not include mcjnitoring and therefore its
       estimated cost is $0.                           .     . •
8.      If a standard technology was chosen, why?                   'I
                                                                  '•    . I •       "         -   r
       The selected alternative RAA-2 includes the installation of a soil cap!, or the existing landfill
       covers will be repaired/retrofitted to meet the requirements of the Michigan Solid Waste
       Management Act 641. The selected alternative provides protection fjromi the major exposure
       pathways on site by preventing contact with site soils and the landfilil contents through
       capping.  RAA-2 provides long-term effectiveness by containing theilandfilled waste on  site
       through engineering controls.  Cap materials are expected to be obtainable from nearby
       sources, and the engineering expertise and construction practices, and equipment for
       installation, operation and maintenance of this  component.of the selected alternative are
       available and proven. The selected alternative also meets both fedeijal and state ARARs
associated with closure requirements for solid waste landfills, at the
alternatives.

                   !.
If an innovative technology was chosen, why?

An innovative technology was not chosen.
                                                                        lowest cost among the
 10.     If an innovative technology was not chosen, why not? At what stage, was the innovative
        technology eliminated?                                               v                ^

        Innovative, technologies could be eliminated from the remedial techijiology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

                                                -3-          •'••.
                                                                                          691

-------
          Innovative technologies eliminated during the initial screening include the following:

          •      Biodegradation was eliminated because it would be ineffective for inorganics  and
                 would require intensive handling of materials.  It also was rejected because treatment
                 would require excavation,  which is not considered feasible or cost-effective given the
                 large volume of waste material and potential greater risk to on-site workers and nearby
                 residents.                                                                       J
          •      In situ bioremediation was eliminated because implementation of this technology
                 requires homogeneous subsurface conditions. If heterogeneous subsurface conditions
                 exist, such as are found in solid waste (landfill) materials at the site, flow channels
                 would be formed by the injection of the biological inoculant.  Flow channels would
                 hinder the effectiveness of the remedy, as well  as the verification of performance   In
                 addition, this technology would not address the inorganic contaminants at the site
         •       Soil washing was eliminated because of the large quantity of contaminants that would
                 have to be treated and the high cost of implementing this technology.
         •       Soil flushing was eliminated because it would be difficult ,to implement this technology
                 because of the heterogeneous nature of the landfill, and because of the large volume of
                 contaminants.
         «      Solvent extraction was eliminated because it would involve intensive handling of
                materials, and it would be difficult to  implement based on the large volume of waste
                and associated cost of treatment.
         •      Soil vapor extraction was eliminated because its implementation would require
                homogeneous subsurface conditions.  If heterogeneous subsurface conditions exist
                such as are found in solid waste (landfill) materials at the site, flow channels would be
                formed by the injection of the air stream. Flow channels  would hinder the
                effectiveness of the remedy, as well as the verification of performance.  In addition
                this technology would not address the  inorganic contaminants at the site.
         •      Dechlorination was eliminated because it would require intensive handling of
                materials, and its effectiveness would be limited. Thermal treatment which requires
                excavation is not considered feasible or cost-effective given the large volume of waste
                material and the potential greater risk to on-site  workers and nearby residents
         «      In situ vitrification was eliminated because it would be difficult to implement because
                it is an innovative technology, and because of the heterogeneity of contaminants The
                large volume of contaminants and. associated cost of treatment was also a factor in  its
                elimination.

        Innovative  technologies eliminated during the screening of the three criteria include the
        following:

        •      None

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
692
                                              -4-

-------
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of'a standdnd technology?

       Overall protection of human health and the environment was weighed jmost heavily in selecting
       a standard remedial action for this site.  The major exposure pathways} of concern at this site
       are the potential for inhalation and ingestion of, and dermal contact with contaminated site
       soils. Based on these pathways of concern, the alternatives were evaluated on their ability to
       reduce exposure to soils.  The selected alternative is protective of human health and the
       environment because it eliminates the major exposure pathway by preventing contact with site
       soils through the construction of a landfill cover.  Short-term effectiveness also was weighted
       heavily in selecting the chosen alternative.  Community and worker health would be more
       difficult to protect under RAA-3 and RAA-4 because of the activity of excavating the
       landfilled waste to enable the installation of vertical barriers under these alternatives.
       Uncovering waste would increase the potential for exposure to hazardous constituents by direct
       contact and inhalation.                    ;         ,

       The selected alternative also  incorporates the establishment of ACLs, which are site- specific
       chemical concentrations for ground water at a site.  The State of Michigan has indicated that it
       does not agree with the use of ACLs  at this site and, therefore does not concur with, the
       selected alternative.                                  ,
 72.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        Cleanup goals were not established for this site.
   '             '                   v          •        '      •      ' -  ".  1 ''•>.''   .' •'      •

 13.     Was the innovative technology eliminated because of the cleanup goa!,s? Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •      None

:        Standard technologies eliminated because of cleanup goals include:

        •     ' None                                                    i        •


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.
 15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Cost-effectiveness
                                                -5-
693

-------
                Proven reliability
   16.    How are measures compared?

          The selected alternative is considered cost-effective because it provides protection from site
          risks at the lowest cost compared to all the other alternatives. RAA-3 and RAA-4 are more
          expensive than RAA-2,  and do not provide any additional reduction in site risks  The
          selection of a soil cap was influenced by the availability and proven reliability of engineering
          expertise and construction practices for capping, and by the availability of equipment for
          installation,  operation, and maintenance of landfill caps.
  17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not considered primary in selecting a remedy for this
                                                                                        site.
                                                                                                             • r
                                                                                                              8;
694
                                               -6-

-------
                                Cannelton Industries

                               Sault Ste. Marie, Michigan
                                       Region 8
GENERAL SITE INFORMATION
1.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (rag/kg)

Arsenic 3,600
Barium 10,300
Cadmium 341
Chromium 328,000
Lead 10,100
Mercury 25
PAHs 17

Site History


NPL Proposed: 6/88
NPL Final: 8/30/90
FS:
4/92
ROD: 9/30/92

Background

EPA Fund-lead


PRPs: Cannelton Industries, Inc.
'. Algoma Steel Corporation
FS prepared by: WW Engineering &
Science
. .

       Sediment (mg/kg)
       <           -
       Arsenic             29.6
       Barium              202
       Cadmium           26.1
       Chromium          40,000
       Lead               603
       Mercury            2.3
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •     199,700 cubic yards of soil, sediment and waste
                                             . -         -           I
                           -     .     "                .           \
 3.      What type of site is this?        .  -  •    -     >.               ,
                                                                  I     '
        Food and Kindred  Products. A former tannery located in a residential and light industrial area
        adjacent to Tannery Bay.
                                           -1-
                                                                                       695

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
        Access restriction:
        Containment:
        Physical treatment:
     Deed restrictions, fencing
     Capping (synthetic membrane, natural soil, clay, asphalt, concrete,
     multimedia), slurry wall,, vibrating beam, grout curtain, metallic sheet
     piling, clay wall, horizontal barriers
     Aeration, in situ soil aeration
        Thermal treatment:    Incineration (rotary kiln, liquid injection, fluidized bed, infrared)
        Disposal:
     Excavation, off-site disposal, on-site disposal
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Slurry degradation, microbial degradation
        Phys/Chem treatment:  Soil washing, oxidation, in situ soil flushing, enhanced volatilization,
                              soil vapor extraction
        Thermal treatment:     In situ vitrification


6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated-as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify  alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on -
        nine criteria established by the NCR  No innovative technologies were incorporated into
        remedial alternatives.
                                                                                 Ol:
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
          Alternative
         RAA-1
         RAA-2
 696
         Standard Technology
No action
Excavation/on-siiedisposal/dewatering/
ground water treatment/institutional
controls

                    '-2-
                                                                        Estimated Costs
                                                                    3 Criteria
                                                                      N/A
                                                                      N/A
 9 Criteria8
                                                             $0
$30,200,000
                                                                                                             I

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7*

Standard Technology
Excavation/off-site disposal/dewatering/
ground water treatment/institutional •
controls
Excavation/incineration/dewatering/on-
site disposal of ash/ground water
disposal off site/institutional controls
Excavation/incineration/dewatering/
ground water treatment off site/off-site
disposal of ash/institutional controls
Excavation/on-site disposal/ground
water treatment off site/institutional
controls
Excavation/on-site disposal/
dewatering/ground water treatment/
institutional controls/preservation of
on-site wetlands
Estimated Costs
3 Criiteria
N/A '
N/A
N/A
\
N/A
N/A
9 Criteria2
$34,800,000
$49,800,000
$51,500,000
$25,900,000
$19,700,000
                                                 t               '       ''
       *Developed in the ROD and, while similar to RAA-2, this alternative addresses a lesser
       volume of soil/sediment/waste since cleanup levels are different (an explanation is provided in
       the response to Question 8).
8.      If a standard technology was chosen, why?                     ,   j
                                                                       r.
       RAA-7 was selected because its implementation will reduce and control potential risks to
       human health and the environment posed by exposure to site contaminants by excavating soil
       and sediment above human health based cleanup criteria and containing it in an on-site .
       landfill.  The site risk will be reduced to a level of 10'6 for carcinogens and the Hazard Indices
       for noncarcinogens'will be less than one. Removal of .soil/sediment/waste reduces the source
       of ground water and surface water contamination. The selected remedy removes a lesser
       volume of soil and sediment than other alternatives, but the remaining chemical concentrations
       in'the wetlands and sediments have not been shown to be significantly toxic to organisms in
       the studies done to date, RAA-7 also protects the environment. The xemedy attempts to
       balance wetland preservation and reduction of dredging and potential resuspension  of
       contaminated sediments with removing contaminant threats from the environment.  Removal of
       tannery waste from the bay  will improve the physical habitat for benl;hic organisms and reduce
       the potential for resuspension of exposed waste on the shoreline of TJannery Bay.  The long-
       term effectiveness of this  option is a function of the long-term integrity of the landfill which is
       expected to be good if the landfill is well designed and maintained over time.  Treatment was
        determined to be impractical, and because of the low mobility of the principal contaminants,
        containment of the source material was considered to be a safe and reliable option.  This
        alternative poses no short-rieim risk, meets all ARARs, and is cost-effective. It protects human
        health and the environment for the least cost compared to other action options.    >
                                                                       I
                                               -3-
697

-------
          The selected remedy was modified in me ROD based on comments and additional information.
          Ihe derivation of cleanup standards was changed from ."20 times" the back calculated ground
          water concentration to health-based risk based on direct human contact.  This change was
          made because current ground water and surface water information show that these two media
          are only minimally contaminated and currently present no unacceptable risk to human health
          The soil/sediment cleanup levels proposed under the chosen alternative, including those to be
          derived by additional testing, would protect ground water and surface water, especially when
          taking into account the large flow volumes of both the ground water discharge and the St
          Mary's River,  It is also likely that after cleanup standards are derived and excavation is '
          complete, contaminant levels will remain above background. EPA believes that management
          of some mplace contamination under RAA-7  is protective of the environment, based on the
          relative effects of contaminants left in place compared to the effects of excavation and
          dredging activities.  The environmental benefits of removing all contamination must be
          weighed against the destructive nature of excavation activities that would be required
          Leachate studies will be conducted to ensure that the concentrations  of contaminants in
          leachate are evaluated against health-based standards for the medium with which it interfaces
          and its ability to comply with Michigan Act 307.  If leachate studies find the contribution of
          contaminants from the site soil/sediment to be within the range of the contribution from
          background soil/sediment, compliance with the Act will be considered attained "EPA's
         opinion is that large-scale destruction of a quality wetland habitat and dredging and possible
         resuspension of a large volume of sediments would degrade the environment more than
         leaving some elevated levels of chemical contaminants in place and may  not be cost effective "
 9.
       If an innovative technology was chosen, why?

       An innovative technology was not selected.
                                                                                                            )
10.
        If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

                Slurry degradation was eliminated because it would not remove metals from soil
                Enhanced volatilization was eliminated because it would not remove metals from soil
                Soil washing was eliminated because treatability  studies showed that soil washing had
                little effect on the major site contaminants of concern.
                Microbial degradation was eliminated because it does not treat metals.
                Oxidation was eliminated because it does not treat metals.
                In situ soil flushing was eliminated because treatability studies showed that the process
                had little effect on the major site contaminants of concern.
                Soil  vapor extraction was eliminated because it would not be effective for treatment of
                metals.                                          .
               In situ vitrification was eliminated because it cannot be implemented given the site's
               high water table.
698
                                              -4-

-------
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                        I
                                                                        I -
                                                                       J- •
       •  '    None              ,            .     '     ; .       :      '  , t
                                            -                            i

       Innovative technologies eliminated during the detailed analysis include the following:
               None
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting the technology were protection of human health
       and the environment, short-term risk, implementability, and cost effectiveness. The chosen
       alternative was preferred because it reduces site risk to human health as effectively as other
       alternatives but is more protective of the environment since it removes a lesser volume  of
       soil/sediment in the wetlands.  Minimizing the loss of Wetlands reduces the loss of habitat  for
       numerous birds, mammals, and amphibians that occupy the area. It ppses less short-term risk
       due to the release of contaminants during dredging activities.  Administratively, on-site
       landfilling is easier to implement because a permit for landfill construction would not have to
       be obtained from the State.  Finally, alternatives that proposed incineration were eliminated
       because they would not be cost effective and there was concern that metals would be
       mobilized  in the resultant ash.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARA»i or Other Basis
Carcinogens
Lead
Cadmium
Arsenic
Carcinogenic PAHs
Chromium VI
400
100 ,
12.8
0.33
23

Risk"
Risk
Elackgroundb


MDLC
. Risk
Noncarcinogens , v
Chromium in
Mercury.
5,300
TBDd

Risk
TBD
               Tor health-based risk estimates, an excess upper bound individual lifetime cancer risk
               of 10"6 is acceptable for carcinogens and a Hazard Index less than or equal to 1  is
               acceptable for noncarcinogens.
                                               -5-
699

-------
                "Background concentration was chosen as a cleanup level because the health-based risk
                level was below background.
                •Method detection limit (MDL) was used as a cleanup level because health-based
                levels were below the MDL.
                ''To be determined. EPA acknowledges that, while potentially compliant with the
                rules, the mercury levels at the site might not be protective of surface water; EPA
                believes that further assessment is warranted.
 13.
 14.
15.
  Was the innovative technology eliminated because of the cleanup goals? Could the standard
  technology meet the cleanup goals?

  Innovative technologies eliminated because of cleanup goals include:               x

  •      None                                              .

  Standard technologies eliminated because of cleanup goals include:

  "      None


  Were treatability studies conducted on the innovative technology or standard technology?

 In preparation for the FS, two bench-scale treatability studies were conducted on site
 soil/sediment to evaluate stabilization and soil flushing as potential technologies for treating
 contaminants at the site.


 Wfiat measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

      Risk level achieved
      Cost effectiveness
                                                                                                           1
16.    How are measures compared?                                                     .

       RAA-7 was selected because it reduces risk to health-based cleanup levels at the least cost and
       is therefore the cost-effective option.  Further, RAA-7 was selected because it will provide the
       appropriate balance between short-term and long-term risks.
17.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?
                                                                      F

One technical consideration that was primary=in selecting a remedial alternative was the
destruction of wetlands.  The chosen alternative was preferred because it would cause less
destruction of wetlands and preserve natural habitat better than all the other alternatives.  It
was determined by EPA that  lessening cleanup levels and decreasing excavation volumes was
appropriate and protective.                                         "   .
  700
                                              -6-
                                                                                                             "I1"'
                                                                                                             "If,

-------
                                                                                                       1
The high water table was another technical consideration, but was not primary in selecting a
remedial alternative.  The high water table caused the elimination of in situ vitrification.
                                      -7-
701

-------
                                 Carter Industrials, Inc.

                                      Detroit, Michigan
                                         RegionS
                                                 f
                                                 1
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?
       Maximum concentrations of principal
       contaminants were:

       Soil/Debris (mg/kg)

       PCBs   -                   12,000
       Arsenic                     5
       Lead                       28,000
       Cadmium                   34
       1,3-Dichlorobenzene          180
       1,4-Dichlorobenzene          3
       Xylene                      25
       Chlorobenzene              36
       Benzo(a)anthracene          5
       Pyrene                      11
       1,2,4-TrichIorobenzene       11  ,
       Pentachlorobenzene          700
       Tetrachlorobenzene          1,600
       1-Ethyl, 2-methylbenzene     1
       Copper                      17,000
       Zinc                        8,500
                                                 IT"
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
6/24/88
3/31/89
4/19/91
9/18/91
             Background

EPA Fund-lead
PRPs:  Carter Industrials, Inc., Spector-
       Carter Metal
FS prepared by:  B&V Waste Science
       & Technology
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      46,000 cubic yards of contaminated soil and debris


       What type of site is this?

       Recycling. A former scrap metal storage and salvage operation in an urban setting: The
       surrounding land use is mixed residential and light industrial.    ,
702
                                            -i-

-------
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?
                                                                        i
       The FS for this site supplements a 1986 Engineering Evaluation/Cost .Analysis prepared for
       EPA in which a number of technologies were developed for consideration and screened. No
       initial screening is conducted in the FS. Standard technologies incorpprat<;d into RAAs were:
       Access restriction:
       Containment:
       Chemical treatment:
       Thermal treatment:

       Disposal:
Institutional controls, site access restrictions
Multilayer cap                •     , :    '.
Pozzolonic solidification, quicklime treatment
On-site rotary kiln incinerator, Shirco Infrared System, circulating bed
combuster, advanced electric reactor, off-site JSCA incinerator
Excavation, on-site and off-site RCRA landfill! off-site TSCA landfill
                                                                   .• _   -h     '         .
5.      Was an innovative technology considered in the FS? If so, which technology?

        The FS for this site supplements a 1986 Engineering Evaluation/Cost .Analysis prepared for
        EPA in which  a number of technologies were developed for consideration and screened.  No
        initial screening is conducted in the FS. Innovative technologies incoijporated into RAAs
        were:                                                           !                .   .
        Chemical treatment:
        Thermal treatment:
Critical fluid (CF) extraction, on-site solvent e|xtra.ction
In situ vitrification, low-temperature thermal djesoirption (LTTD)
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that j merit a more detailed
        evaluation. For this site, the estimated costs are calculated during an evaluation based on nine
        criteria established by the NCP.                                                    ,,

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)

        Soil/Debris                                                ,      !
Alternative
RAA-3
RAA-9 or
Hybrid Alt.2
Innovative Technology
In situ vitrification
In situ vitrification/off-site RCRA
landfill
Estimated Costs
3 Criteria
NyJA
N;JA
9 Criteria
$23,461,000
$20,544,000
                                               -2-
                                                                                                 703

-------
Alternative
RAA-12 or
Hybrid Alt.5
RAA-13 or
Hybrid Alt.6
RAA-14 or
Hybrid Alt?
•
Innovative Technology
Critical fluid extraction/incineration of
residual PCB oils/off-site TSCA
landfill/off-site RCRA landfill
Solvent extraction/off-site incineration
of residual PCB oils/off-site TSCA
landfill/off-site RCRA landfill
Low-temperature thermal desorption
with incineration of residual PCB
oils/off-site TSCA landfill/off-site
RCRA landfill
=====^====
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$49,402,000
$20,542,000
$18,052,000
($19,508,000")
                                                                                                J)
       'Present worth value given in the ROD.
7.      How did the cost(s) compare to standard technologies?
                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)
       Soil/Debris
Alternative
RAA-1
RAA-2
RAA-4
RAA-5
RAA-6
RAA-7
Standard Technology
No action/continued operation and
maintenance of in-place stabilization
measures
On-site incineration:
Rotary kiln
f
Infrared
Circulating bed
Pozzoloriic solidification
On-site RCRA landfill
On-site capping
Off-site TSCA landfill
==================
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
N/A
-• N/A .
9 Criteria
$246,000
$40,864 to
$55,599
$25,030 to
$39,763
$13,107 to
$27,841
$3,913,000
($4,734,141)a
$4,167,000
$1,647,000
($l,856,000)a
$22,804,000
704
                                         -3-

-------
8.
Alternative
RAA-8 or
Hybrid Alt.l
RAA-10 or
Hybrid Alt.3
RAA-11 or
Hybrid Alt.4
RAA-15 or
Hybrid Alt.8
Standard Technology
Off-site TSCA incinerator/off-site ,
TSCA landfill/off-site RCRA landfill ,'
Off-site TSCA incinerator/off-site
TSCA landfill/off-site RCRA landfill
Off-site TSCA incinerator/off-site
TSCA landfiWoff-site RCRA landfill
Quicklime treatment
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$50,308,000
$100,719,000
$51,797,000
$3,662,000
The present value given in the ROD.


If a standard technology was chosen, why?

A standard technology was not chosen.,
9.     If an innovative technology was chosen, why?

       The selected alternative is a slight modification of RAA-14 by incdrpc|ratmg the construction
       of an on-site containment cell.  The selected alternative was chosen because:

        •      LTTD achieves substantial risk reduction through treatment of|the site's principal
               threat: PCBs. PCBs would be concentrated into a small volume iind incinerated.  Any
               contaminated residual material or contaminated material that cannot be treated would
               be contained on site.

        •      It involves much less off-site transport of waste materials, thereby lowering short- term
               risks from potential accidents and increased handling requireirentii.

        •      It meets all ARARs except for a Michigan Solid Waste Management Rule specifying
               isolation distances for sanitary landfills. This requirement willjbe waived pursuant to
               CERCLA Section 121(d)(4)(D) which allows the agency to select a remedy that does
               not meet an ARAR but attains a standard of performance equivalent to that required
               under the otherwise applicable standard, through use  of another method or approach.
               The selected alternative will attain the required equivalent standard of performance.
                                                                        \
        •      It permanently destroys PCBs segregated from soils.                    ,

        •      It uses an innovative technology that has undergone engineering scale testing to verify
               its effectiveness at the site and to facilitate the remedial design.

         •     It achieves the required risk reduction more completely than suiy other on-site
                treatment option  except in situ vitrification and at substantially less cost than the off-
                site treatment options.                                              ',,''..
                                                -4r
                                                                                          705

-------
         During the public comment period, the PRPs submitted a justification for a Type C cleanup
         under Michigan Act 307 to the state.  This justification was accompanied by a proposal to
         modify the original Proposed Plan (PP). Some elements of the PRPs' proposal were
         incorporated into the selected alternative,  The two key components of the original PP that
         were modified are:  (1) the original requirement of off-site landfilling of TCLP toxic material
         and the contaminated soils; and (2) treatment using LTTD of soil contaminated with PCBs at
         levels over 1 mg/kg. While it had not been demonstrated that the required cleanup level of 1
         rng/kg could be achieved, information suggests that PCB levels could be reduced to less than
         10 mg/kg.  In addition, EPA and the State of Michigan found that the modified alternative
         involves much less off-site transport of materials and is a protective and cost-effective remedy
 10.
11.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?

  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages: during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  "      None

  Innovative technologies eliminated during the screening of the three criteria include the
  following:

  •      None

 Innovative technologies eliminated during the detailed analysis include the following:

 •      In situ vitrification was eliminated because of its limited availability since only one
         hazardous waste contractor markets the technology.  This technology would not be as
         readily compatible with possible future remediation as remedies that permanently
        remove the contaminated material from the site.  In addition, this technology would
        take longer to implement (25 months) than the chosen alternative (12 months)
 •      Critical fluid extraction was eliminated because it would take the longest amount of
        time to complete and it may be difficult to implement in cold weather  Also this
        technology would generate large volumes of solids requiring on-site disposal'and
        would not be as cost-effective as the chosen alternative..
 •      Solvent extraction was eliminated because it could result in short-term risk from toxic
        air emissions. Air emission controls and air monitoring would be required.


 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine  criteria result in the elimination  of the innovative technology?  Ifso
which critenon?  Which of the criteria supported the use of a standard technology?        '

Overall protection of human health and the environment, compliance with ARARs, long-term
effectiveness and permanence, and cost-effectiveness were weighted most heavily The chosen
innovative technology achieves  the required risk reduction  more completely than any other on
sue treatment options (except for in situ vitrification) and at substantially less cost than other,
706
                                       -5-

-------
       off-site treatment options.  It meets all ARARs except for a Michigan Solid Waste
       Management Rule that specifies isolation distances for sanitary landfills.  An ARAR waiver
       will be invoked  Once the threshold criteria of protection of human health and the
       environment and ARARs compliance were satisfied, long-term effectiveness was used in
       remedy selection.                                               |   •
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level
ARAR or Other Basis
Cnrrinngens
PCBs
Lead
Cadmium
Arsenic .
Benzo(a)anthrazene
1 mg/kg
100 jig/kg
80 ug/kg
50 ug/kg
330 ug/kg
EPA8
Michigan Act 307b
Michigan: Act 307b
MIOL0
MDLC
Nonrnrrinngens ,_ 	 ^.
1 ,3-Dichlorobenzene
1 ,4-Dichlorobenzene
Xylene
Chlorobenzene
Pyrene
1,2,4-
Trichlorobenzene
Pentachlorobenzene
Tetrachlorobenzene
1 -Ethyl, 2-methyl
benzene
10,000 ug/kg
20 Mg/kg
6,000 ug/kg
2,000 ug/kg
4,000 ug/kg
200 ug/kg • • ;
100 ug/kg
40 ug/kg
MDLd
Michigan Act 307b
Michigan Act 307"
Michigan .Act 307"
Michigan Act 307b
Michigan Act 307b
Michigan Act 307"
Michigan Act 307b
Michigan Act 307"
MDLC
                aU.S. EPA's Guidance on Remedial Actions for Superfund .Siftes with PCB
                Contamination, 1989.                          '.'•.[.      '' \      .      -
                "Michigan Act 307, Type B cleanup achieved levels that protect ground water from the
                migration of soil contaminants into the ground  water; protects against unacceptable
                human health risks due to direct contact; and protects surface waiter quality.
                'Michigan Department of Natural Resources  acceptable Method Detection Limit
                (MDL) was used rather than the level based  on carcinogenic! risk.
                dNo specific cleanup level for this contaminant was given in the ROD.
                                               -6-
707

-------
  13.
          For carcinogens, an excess upper bound individual lifetime cancer risk of between 1Q-4 to \n*
          was acceptable.  For noncarcinogens, a Hazard Index less than or e^ua. t^Twas acceptaWe.

         Innovative technologies eliminated because of cleanup goals include:
         "      None                                  .

         Standard technologies eliminated because of cleanup goals include:
         "      None                                         '
14.    Were treatability studies conducted on the
 15.
                                                innovative technology or standard technology?
                                                      to <* FS °r «

              ion to demonstrate that a cleanup level of 1  mg/kg coul be reachd


       What measures/criteria were used to compare alternatives?

      The following measures were used  to compare the alternatives-

            Risk level achieved
            Single vs. multistep treatment
            Cost effectiveness
            Proven reliability
            Preference for treatment (vs. containment)
            Impact on nearby populations
16.    How are measures compared?

       Of the 15 alternatives considered, those involving thermal destruction of PCB contaminated
       matenal and secure containment of TCLP toxic material were considered to offer tt^S

       to  a muhn ,agr  6XTg S1? ^^^  The diversity of the waste materials readily lem  self
       L,7    H T  gy   m °f remediation' •"» hybrid RAAs were developed to combine
       of  w±   ±°  gl6S T remedial altematives ** addressed the various types andTantities
       of  wastes at the site and provide for cost effective treatment of the contaminated soils to the
       maximum extent possible. Four alternatives were considered most cost-efTtte^1-2  RAA
 70S
                                                                                                           )
                                             -7-

-------
       9, RAA-13, and RAA-14. The chosen alternative utilized an innovative treatment technology
       that had proven reliability because it had undergone engineering scale testing to verify its
       effectiveness at the site.  Treatment was preferred because it would ensure the greatest degree
       of long-term effectiveness and permanence. RAA-14 resulted in permanent destruction of
       PCBs. RAA-13 was eliminated because it posed short-term risk to sitip workers and off-site
       populations.                                             ,       [

                                                                      i
17.     What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the femedy?              j

       Technical considerations were not primary in selecting a remedy for ihis site.
                                               -8-
                                                                                                 709

-------
                                                                                                          Si.	
                          Central Illinois Public Service Company
                                        Taylorville, DUnois
                                            Region 5
   GENERAL SITE INFQRTvTATTDKr
_  What were the principal contaminants,
  contaminant levels, and media addressed in
  this feasibility study?

  Maximum concentrations of principal
  contaminants were:
         Soil (rag/kg)

         Xylene

         Sediments (mg/kg)

         Fluoranthene
         Dibenzo(a,h)anthracene
0.005
1.57
1.489
         Polyaromatic hydrocarbons    2.6
                                                                   Site History
                                                      NPL Proposed:
                                                      NPL Final:
                                                      FS:
                                                      ROD:
                                      1/13/88
                                      8/28/90
                                      5/91  '
                                      9/30/92
                                                        .   Background

                                              PRP-lead
                                              PRPs:  Central Illinois Public Service
                                                     Company
                                              FS prepared by: John Mathes &
                                                     Associates
  2.      What volume of material is to be remediated?

         The volume of material to be remediated included:                 '
                                                                                       v
         •      12,000 cubic yards of soil and sediment


 3.      Wtiat type of site is this?                                                          •    .


         Coal Products. A former gas production facility located in a residential area.    !


 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                            '

        Access restriction:     Land use restrictions
        Containment:          Capping, grading,  revegetation
        Thermal treatment:     Incineration
        Disposal:             Excavation (complete, partial), disposal (on-site, off-site)
710
                                             -i-

-------
       The chosen alternative includes a permanent remedy to address the residual contamination in
       ground water and thereby addresses the remaining principal threat posed by ground water
       through an active ground water pump-and-treatment program.  This remedy provides a
       permanent and long-term solution.  It is easily implemented and meets all ARARs.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
      .. technology eliminated?                                            !
                                                                        'i
                                                                        '!
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation, In this case, a
       three-criteria screening was conducted for both individual technologies and specific
       alternatives.
        Innovative technologies eliminated during the initial screening include
the following:
               None
        Innovative technologies eliminated during the screening of the three criteria of technologies
        include the following:

        •      None

        Innovative technologies eliminated during the detailed analysis include; the following:

        •      None
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The criteria most heavily weighted in selecting a remedial alternative were protection of
        -human health and the environment and long-term effectiveness.  The selected remedy was  the
        most  protective option since it addressed both soil/sediment and ground water.  Further, it
        addressed the residual risk associated with ground water with a permanent remedy.
 12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        Cleanup levels for soil/sediment were not established.                          ,
                                               -4-
                                                                                                713

-------
  75.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
         technology meet the cleanup goals?

         Innovative technologies eliminated because of cleanup goals include:

         •      None

         Standard technologies eliminated because of cleanup goals include:

         •      None


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Risk level achieved
               Preference for treatment (vs. containment)
               Waste left in place/institutional control


 16.     How are measures compared?

        RAA-5 was preferred because it provides the most protective and permanent remedy since it
        actively addresses the residual risk associated with ground water treatment.  RAA-3 was not
        preferred because it would have utilized institutional controls to address residual risk
17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedial alternative.
 714
                                             -5-

-------
                                     Chem Central
                     (Chem Central/Grand Rapids Corporation;*

                                   Wyoming, Michigan            ,.  ,|,
                                         Region 5
GENERAL SITE INFORMATION

1.  .    What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       1,1-Dichloroethylene          0.02
       Trichlofoethylene             0.22
       Tetrachloroethylene           81
       Bis(2-ethylhexyl)phthalate     57
       PCB                        0.32
       Toluene                     15
       Arsenic                     4.3
       Zinc                        66    :.
                                   Site History
                      NPL Proposed:
                      NPL Final:
                      FS:
                      ROD:
12/82
7/87
5/91
9/30/91
                                   Background
                                      . I  .
                      PRP-lead
                      PRPs:  Chem Central
                      FS prepared by: WW Engineering and
                             Science
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      6,200 cubic yards of contaminated soil
 3.      What type of site is this?

        Chemicals and Allied Products.  A chemical distribution plant.
 TECHNOLOGY SELECTION

                               ••     '         '               '  '    I '
 4. .    . What standard technologies were considered for selection in this FS?,

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
        Disposal:
Deed restrictions, fencing
Soil cap, sheet piling .
On-site excavation, disposal at a RCRA facility
                                             -1-
                                                                                          715

-------
  5.
  Was an innovative technology considered in the FS?  If so, which technology?

  Innovative technologies considered during the identification and screening of technically
  feasible technologies were:                                                      •

  Biological treatment:  Enhanced biodegradation, bioreclamation
  Chemical treatment:   Soil flushing (surfactant)
  Physical treatment:    In situ soil vapor extraction
 6.      What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the fonnulation of RAAs), the FS does not quantify costs. After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation. For this site, the estimated costs were calculated first during an evaluation based
         on nme criteria established by the NCP: long-term effectiveness and permanence; short-term
         effectiveness; compliance with ARARs; protectiveness of human health and the environment-
         reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support '
        agency acceptance; and community acceptance. The costs were recalculated in the ROD.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
7.
           Alternative

         RAA-2
         RAA-3
         RAA-4
                           Innovative Technology
                   In situ soil vapor extraction
                   In situ soil vapor extraction/soil
                   flushing

                   In situ soil vapor extraction/
                   bioreclamation
                                                                       Estimated Costs
9 Criteria
$170,000

$450,000
                                                                    $620,000
  ROD
$182,400

$450,000
               $620,000
How did the cost(s) compare to standard technologies?

          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-5
RAA-6
Standard Technology
No action/deed restrictions/ground water
monitoring
Soil cap/ground water monitoring
Fencing/ground water monitoring
.
Estimated Costs
9 Criteria
$410,000
$54,000
$31,000
b -2-
ROD
$410,000 .
$54,000 -
$31,000


-------
          Alternative
         RAA-7
         RAA-8
        Standard technology
Soil cap/fencing/ground water
monitoring
Excavation of on-site soils/disposal off
site in a Class n landfill8
                                                                       lEsttmated Costs
                                                                   9 Criteria
                                                                    $85,000
                                                                    $560,000
 ROD
$85,000
$560,000
       "If the soil must be managed as a hazardous waste, the estimated cost will be $13,000,000.

                    •              ,                                      i. "  •          •
                              .   - •                    ^                 \                  '
8.      If a standard technology was chosen, why?               '   >       !| '   -

       A standard technology was not chosen.


9.      If an innovative technology was chosen, why?

       The technology selected was in situ Soil Vapor Extraction.  The remedy was selected for, the
       because: 1) it reduces migration potential of contaminants to surface drainage, 2) migration of
       contaminants from soil to ground water will be reduced, 3) proven technology for VOCs in
       unsaturated soils, 4) easy to implement, 5) cost, 6) avoids removal and replacement of railroad
       track which would disrupt operations at this still active site, 7) excavation at the site would be
       difficult because of buildings which would require sheet piling along Buildings to protect
       foundations from collapse, 8) won't mobilize residual contaminants.


 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                              '

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

      .  •      None   •     '          •                  . •           '    ! '

        Innovative technologies eliminated during the screening of the three (criteria include the
        following:

        •      None                                                    !j
                                                                        I
        Innovative technologies eliminated during the detailed analysis include the following:
                                                                        I
                                                                   1     J    ' '     .
         •      Soil flushing was eliminated because it would be too costly Jind difficult to implement.
         •      Bioremediation (biodegradation and bioreclamation) was eliminated for the same
                reasons as soil flushing.                   ,
                                                -3-
                                                                       717

-------
 12.
         Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so
         which criterion? Which of the criteria supported the use of a standard technology?

         Cost-effectiveness and ease of implementation were weighted most heavily in selecting a
         technology.  In addition to meeting all the criteria, the chosen innovative technology is more
         cost-effective and the easier to implement than the other technologies.
             D             Were selected? Vthe clea™P goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (rag/kg)* | ARAR or Other Basis
Carcinogens
1 , 1 -Dichloroethylene
Trichloroethylene
Tetrachloroethylene
Bis(2-ethylhexyl)
phthalate
PCB
Arsenic
0.001
0.064
0.014
0.05
0.0004
6.0004C
Michigan Act 307b
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Noncarcinogens
Toluene
Zinc
,,,,
0.8C
28C
**"" -' ""!!!•!". ' -»— — —
Michigan Act 307
Michigan Act 307
~ '
               •Soil cleanup levels were established to protect ground water from leaching soil
               contaminants.  Cleanup levels were set at twenty (20) times the ground water cleanup
               level for each chemical.                                                        v
               Remedial action cleanup standards were based on Michigan Environmental Response
               Act 307, Type B cleanup criteria.  Cleanup levels developed by Type B criteria are
               health-based and reduce risk to less than  10"6.                               •
               TTiis value is based on a Chronic Oral Reference Dose.
                                                                                                    *
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None                               ,               •

      1 Standard technologies eliminated because of cleanup goals include:

       •      Capping
 718
                                             -4-

-------
14.    Were treatability studies conducted on the innovative technology or standard technology?
                                    :                 .    -   '         ,   i
       No treatability studies were conducted. Treatability studies might be conducted, however,
       during the operation of the soil vapor extraction system to determine if semivolatile
       compounds are reduced to below the soil cleanup levels.          •••"•..


75.    What measures/criteria  were used to compare alternatives?          !

       The following measures were used to compare the alternatives:       ': • .

             Total Cost
             Preference for treatment (vs. containment)
             Proven reliability


16.    How are measures compared?                                    ;

        The chosen alternative reflects a preference for treatment over containment.  Alternatives that
      •  utilized source treatment technologies were considered superior because they would reduce
        contaminant toxicity, mobility, and volume.  The selected alternative was considered a proven
        technology for the site contaminants and unsaturated soils. Alternatives that proposed
        containment technologies were eliminated because they would not prevent future ground water
        contamination and would require long-term maintenance.  While all the alternatives that
        offered source treatment would be equally protective, the  selected alternative is the most cost-
        effective./ •'        ••    ,'           - •      .'•       ..'"',.   5'/'                   '
                          '--•-••                       '  •   •   .   - ''
 17.-    What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in  the selection of the remedy?
                             ,    •  -   •              '-         ••'*•':''.       '..•'-
        Two alternatives, RAA-3 and RAA-4, required removing  a railroad line running onto Chem
        Central's property, which  would interrupt the company's  business for a short time period.  In
        addition, it would dramatically increase the cost and time needed to implement these remedies.
        This site characteristic was not primary, however, in the selection of a remedy.
                                                -5-
719

-------
                             City Disposal Corporation Landfill
                                        Dunn, Wisconsin
                                           Region 5
GENERAL SITE INFORMATION

L      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Acetone              20.25
       Methylene chloride    0.082
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:

        "      700,000 cubic yards of landfill waste
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                      6/9/81
                      9/21/84
                      3/24/92
                      9/28/92
             Background

PRP-lead
PRPs:  Waste Management of
       Wisconsin, Inc., Sara Lee
       Corporation, Garber Industries,
       Inc., Inland Container Corp;,
       Ohmeda, Sub-Zero Freezer Co.,
       and Webcrafters, Inc.
FS prepared by:  P. E. LaMoreaux and
       Associates, Inc.
3.      What type of site is this?

       Municipal Landfill. A former landfill located in a predominantly agricultural area.


TECHNOLOGY SELECTION                ,

4.     Wliat standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restrictions:    Fencing, deed restrictions
       Containment:         Capping (synthetic membrane, clay, composite clay/synthetic)
       Chemical treatment:   Stabilization/solidification
       Physical treatment:     Landfill gas collection system, leachate collection system
       Thermal treatment:     Incineration
       Disposal:             Excavation, on-site disposal, off-site disposal
720
                                            -i-

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                        !

       Biological treatment:    In situ bioremediation                       ,   .
       Chemical treatment:    Soil flushing (solvent)                       i
       Physical treatment:     Gas injection/gas extraction, in situ vapor extraction, vacuum heap
                              extraction                                  i
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs,  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case the estimated costs were calculated during an evaluation based on nine
        criteria established by the NCP: long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementabiliity; cost; state/support
        agency acceptance; and community acceptance.
                               '-                    -                    1 .  '
        The RAA designations changed in the Proposed Plan and ROD from the Feasibility Study and
        are presented parenthetically.

                 Cost  Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-5
(RAA-2)
RAA-6
(RAA-3)
RAA-7
(RAA-4)
Innovative Technology
Fencing/deed restrictions/synthetic
cap/landfill gas extraction/in situ vapor
extraction (cells 6 and 12)a/ground
water monitoring
Fencing/deed restrictions/composite
cap/landfill gas extraction/in situ
vapor extraction (cells 6 and
12)/ground water monitoring
Fencing/deed restrictions/clay
cap/landfill gas extraction/in situ vapor
extraction (cells 6 and 12)/ground water
monitoring
Estimated Costs
3 Criteria
N/A
'i -
N/A
1, • •
1
k/A .
9 Criteria
$3,905,200
$3,925,000
$3,617,000
         "Cells 6 and 12 were the landfill compartments where industrial waste was placed.
                                                -2-
721

-------
  7.      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                              (selected  remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
	
Standard Technology
No action/landfill gas extraction
Fencing/deed restrictions/synthetic
cap/ground water monitoring/landfill
gas extraction
Fencing/deed restrictions/clay
cap/ground water monitoring/landfill
gas extraction
Fencing/deed restrictions/composite
cap/ground water monitoring/ landfill
gas control system
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
t
— ^ 	
9 Criteria
$587,000
eliminated
eliminated
eliminated
 8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
 9,      If an innovative technology was chosen, why?

        RAA-6 (RAA-3) was selected because it is the most protective of human health and the
        environment since it prevents direct contact with site contaminants. Compared to the other
        alternatives, RAA-6 is cost-effective, providing the best overall protectiveness proportional to
        its costs.                ,     .                                             •   .        . -

        Source control will be achieved by covering the landfill wastes, thereby minimizing leachate
        production and contamination of ground water.  The proposed cap's design and construction
        have been proved effective and implementable.  The landfill cover complies with state
        requirements for closure of landfills containing solid and hazardous waste (NR 504 7
        Wisconsin Administrative Code), RAA-6 was the only alternative to propose a cap that
        complies  with hazardous waste landfill cover requirements.  Landfill gas control minimizes
        risks posed  by landfill-generated gases.

        Source removal will be accomplished through in situ vapor extraction, which will permanently
        and significantly reduce the volume and toxicity of VOCs in the landfill. The in situ vapor
        extraction and treatment system, which have been proved effective at other sites, will remove
        VOCs  from the waste and reduce site risks to within an acceptable risk range  of 10"4 to 10'6.
722
                                              -3-

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology election process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      In situ  bioremediation was not incorporated into a remedial alternative but no
               explanation is given for its elimination.
       «      Soil flushing was not incorporated1 into a remedial alternative but no explanation is
               given for its elimination.                                    ;
       •      Vacuum heap extraction was not incorporated into a remedial a|lteraativ& but no
              .explanation is given for its elimination.
        •      Gas injection/gas extraction was not incorporated into a remedial alternative but no
               explanation is given for its elimination.

       Innovative technologies eliminated during the screening of the three criteria include the
        following:"

        •      None                                                     i

        Innovative technologies eliminated during the detailed analysis include the following:
                                                        i                 i
                                                                         I
       : •      None                .                            ,'•.';          ''.''•


 11.  •  Which of the nine criteriaTwere weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the  elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The criterion that was weighted most heavily in selecting a remedial alternative was
        compliance with ARARs. Only the chosen alternative complies with source control state
        ARARs for closure of the site.  Source control alternatives that did not  comply with ARARs
        were  eliminated.          ,                                    ,    j!

        No innovative technologies were eliminated  due to this criterion.


 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was. that
        ARAR?  What risk, level was selected to establish cleanup goals?     |

         No soil cleanup levels were established.                            .}••',
                                                -4-
723

-------
  13.
  Was the innovative technology eliminated because of the cleanup goals?  Could the standard
  technology meet the cleanup goals?

  Innovative technologies eliminated because of cleanup goals include:

  •      None

  Standard technologies eliminated because of cleanup goals include:

  •      None
  14.
  Were treatability studies conducted on the innovative technology or standard technology?

  A treatability study of the biodegradation of site contaminants was conducted.  Contaminants
  currently found at the site were found to be biodegradable.
 15.
 What measures/criteria were used to compare alternatives?

 The following measures were used to compare the alternatives:

       Compliance with ARARs
       Risk reduction
       Total cost
 16.     How are measures compared?

        All the source control alternatives proposed capping and in situ vapor extraction  The
        alternatives were distinguished by the type of cap proposed. The chosen alternative was
        preferred because it complies with.all ARARs for hazardous waste landfills.  The caps
        proposed in the other alternatives would comply only with solid waste requirements  The cap
        proposed m RAA-5 would have been more protective of ground water since it would  provide a
        99-percent reduction in exfiltrate from the waste, compared to the chosen alternative's 80-
        percent reduction in exfiltrate.  RAA-5 also would have cost less and posed less short-term
        nsk since it would have required fewer track trips than the chosen alternative. The chosen
        alternative, however, was preferred because it was the only  alternative that satisfies all
        AJKAJRs.                                                     .              -      -
77.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary  in selecting a remedy.
724
                                              -5-

-------
                                  Clare Water Supply
                                          OU-2

                                     Clare, Michigan
                                         Region 5
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                                                                Background

                                                   PRP-lead          '    -
                                                   PRPs:  Colt Industries (now Coltec), Ex-
                                                          Cello Corporation, Ransburg
                                                          Corporation,, and United
                                                          Technologies Automotive
                                                   FS prepared by:  Djimes and Moore
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediments (rag/kg)

       Benzene     ,                0.027
       1,1,2-Trichloroethane          0.056
       Trichloroethene               1,100
       Tetrachloroethene             40
       Methylene chloride           6
       1,2-Dichloroethane            0.019
       Xylenes (total)                120
       Ethylbenzene                26
        1,1,1-Trichloroethane          510
       Trans-1,2-Dichloroethene      350
       Styrene                  '    0.015
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

 ,      •      54,800 cubic yards of soil


3.      What type of site is this?

       Uncontrolled Waste Site.  A public water supply located on the former
       industrial manufacturers and fuel storage companies.


TECHNOLOGY SELECTION                                      •   ;

4.      What standard technologies were considered for selection in this FS?
         11/82
         9/21/84
         5/92
         9/16/92
        Standard technologies considered during the identification and
        technologies were:
                                             -1-
       site of several
screening of technically feasible
                          725

-------
         Access restriction:
         Containment:

         Chemical treatment:
         Physical treatment:
         Thermal treatment:

         Disposal:
                       Fencing, deed restrictions
                       Capping (clay, soil, asphalt, concrete, synthetic, and multimedia)
                       slurry wall, sheet piles, drainage ditch
                       Stabilization/fixation, c 'crnical reaction
                       Drying beds,  mechanical  filtration
                       Incineration (rotary kiln, multiple hearth, fluidized bed, infrared
                       plasma arc)                                                '
                       Excavation, off-site disposal at a RCRA landfill, off-site disposal at a
                       sanitary landfill, on-site disposal in a RCRA landfill, on-site disposal
                       in a sanitary landfill                  .                         •
 5.
 Was an innovative technology considered in the FS? If so, which technology?

Innovative technologies considered during the identification and screening of technically
reasible technologies were:

Biological treatment:   Biodegradation (In situ), composting, bioharvesting
Physical treatment:     In situ soil washing (aqueous)
Chemical  treatment:    In situ vapor extraction; solvent extraction, chemical reaction
                      (oxidation)
Thermal treatment:     Thermal volatilization, in situ vitrification, molten salt
6.
             was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified

        oZla^d6   T ati°n 'T^' ^ FS d°eS n0t quantify COSts' After"*e RAAs have teen
       formulated, costs are typically estimated as part of a three-criteria screening process
       ^S^'p' imP.Iementa™itv> and cost) to identify alternatives that merit a more detailed
       evaluation. For djis site the estimated costs were calculated during an evaluation based on the
       nine cntena established by the NCP.  Estimated costs are recalculated in the ROD.

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
          Alternative
        RAA-4A
        RAA-5B
                         Innovative Technology

                  In situ soil vapor extraction/fencing/
                  deed restrictions/ditch rerouting
                 UV photochemical oxidation/shallow
                 injection wells/fencing/deed
                 restrictions/ditch rerouting/ground
                 water monitoring
                                                                       Estimated Costs
 9 Criteria
•^—•       n-
$20,467,000
                                                                  $11,374,000
   ROD
   •—»^^»^

$20,467,000
               $11,374,000
726
                                             -2-

-------
7. '     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)

Alternative
RAA-1
RAA-2
RAA-3
RAA-4B ,
RAA-5A

Standard Technology
No action/ground and surface water
monitoring
Fencing/deed restrictions/ditch rerouting
Same as RAA-2, plus a multimedia cap
Excavation/sheet piling/carbon
adsorption/off-site incineration and
disposal/deed restrictions/ditch rerouting
Ground water collection/air stripping/
carbon adsorption/shallow well
reinjection/fencing/deed restrictions/
ditch rerouting/ground water monitoring
Estimate*
9 Criteria
$2,886,000
$3,562,000
$4,291,000
$85,760,000
$23,616,1300
J Costs
ROD
$2,886,000
$3,562,000
$4,291,000
$85,760,000
$23,616,000
 8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
        If an innovative technology was chosen, why?

        RAA-4A was chosen for the remediation of the contaminated soil area because, in addition to
        fulfilling all of the nine criteria, it was the most effective means of reducing toxicity, mobility,
        and volume of soil contaminants. It would reduce residual risk from exposure to soil and
        sediment through treatment.  It could ultimately eliminate the need for long-term enforcement
        of institutional controls and provide a site-wide remedy that is effective in the long term.  I
        can be performed on soils located under buildings. It could enhance aerobic bacterial
        degradation of VOCs that may be occurring^  It is.a demonstrated technology, with adequate
        equipment and specialists available.  It is more cost-effective than  off-site treatment and
        disposal.  It satisfies the statutory preference for treatment.  RAA-1, RAA-2, and RAA-3 were
        eliminated because they would not include any treatment technologies arid thus would not
        significantly reduce the risk to human health and environment. RAA-4E. (off-site treatment
        and disposal) was eliminated because it would not be as effective in reducing the toxicity and
        volume of soil contaminants as RAA-4A. RAA-4B would require eiccavation, which would be
        infeasible for the 15,000 cubic yards of contaminated site soil that is under buildings. In
        addition, the cost of RAA-4B would be prohibitive.  RAA-5B also was chosen to complement
        RAA-4A by treating ground water.  While RAA-5A and RAA-5B both provide plans for
        ground water  remediation, RAA-5B was chosen because it is more cost-effective.
                                               -3-
                                                                                            727

-------
  10.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?                                                   ,

  Innovative technologies could be eliminated from the remedial technology  selection process at
  three stages: during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  «      Composting was eliminated because it would not be applicable.
  •      Molten salt reaction was eliminated because it has not been proved effective on a large
         scale for a wide variety of contaminants and no commercial units are available
  •      Bioharvesting was eliminated because not all site contaminants will bioaccumulate
  «      Solvent extraction was eliminated because it could  introduce additional  contaminants to
         the site.  It would not be applicable.
  "      Chemical reaction (oxidation) was eliminated because precipitation of iron and
         manganese oxides and hydroxides could clog delivery system  and reduce soil
         permeability.
  "      Thermal volatilization (in situ and ex situ) was eliminated due to the difficulty in
         preventing uncontrolled releases of volatiles to the atmosphere and because it is only
         effective for volatiles. Few full-scale operations have been completed; and capital and
         O&M costs are high.                                              ,
  »      In situ vitrification was  eliminated because there are few full-scale operations and it
         would limit future site use.  Capital costs are high and O&M costs are very high
  •      Biodegradation (in situ) was  not included in any RAA and no specific explanation was
         given.  Clay soils at some parts of the site may decrease its effectiveness. Difficulty
         in monitoring effectiveness may affect its implementability.
 »       Soil washing (in situ)  was eliminated because it was not considered  necessary within
         the remaining process options.  The permeability of the soil may be reduced.

 Innovative technologies eliminated during the screening of the three criteria  include the
 following:

 •       None

 Innovative technologies eliminated during the detailed analysis include  the following:

 •      None
11.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so
which criterion? Which of the criteria supported the use of a standard technology?        '  :

Protection of human health and the environment; ability to reduce toxicity, mobility and
volume of soil contaminants; and cost-effectiveness were weighed most heavily in the selection
of an innovative technology.
728
                                               -4-

-------
12.    What cleanup goals were selected? If the cleanup goal was based on
       ARAR? What risk level was selected to establish cleanup goals?
       Soil/Sediments
an ARAR, what was that
Contaminant
Cleanup Level (ug/kg)
ARAR or Other Basis
Carcinogens
Benzene
1 , 1 ,2-Trichloroethane
Trichloroethene
Tetrachloroethene
Methylene Chloride
1 ,2-Dichloroethane
Vinyl Chloride
20
12
60
14
100
. 8
0.4
i '
Noncarcinogens
Xylenes (total)
Ethylbenzene
Trans-1,2-
Dichloroethene
1 , 1 , 1 -Trichloroethane
Cis 1,2-
Dichloroethene
Styrene
6,000
1,400
2,000
4,000
'1,400
20
Michigan Act 307s
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
! MDLb
j MDL
'!"'-, "
Michigan Act 307
Michigain Act 307
Michigain Act 307
;!
Michigiin Act 307
Michigan Act 307
1
Michigan Act 307
               "Soil cleanup levels are 20 times the Michigan Act 307 Type B ground water criteria.
               •"Michigan Department of Natural Resources' acceptable Method Detection Levels in
               soil.
                                               ••'.'"    •   .         i"
        EPA has determined thatcleanup to this level achieves an aggregate risk level for carcinogens
        of 7 x 10-6.                           .       .                  i
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
         technology meet the cleanup goals?
                             •  :              '       .               ,   ,u        .
         Innovative technologies eliminated because of cleanup goals include:

         •      None           -          '                           ,
                                                                                            729
                                               -5-

-------
          Standard technologies eliminated because of cleanup goals include:

          •      Capping
  14.
  Were treatability studies conducted on the innovative technology or standard technology?

  Treatability studies were proposed to evaluate the implementability and effectiveness of soil
  vapor extraction. According to the FS, a pilot study on contaminated soil should be conducted
  to assess the effectiveness of removing the contaminants and to determine the spacing of vapor
  extraction wells needed to remediate the soil in a cost-effective manner.
  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

                Total cost
                Time to design/construct/operate
                Proven reliability
                Single vs. multistep treatment
                Preference for treatment (vs. containment)
                Impact on nearby populations


 16.     How are measures compared?

         Since the Clare Water Supply site is the only feasible source of drinking water for the 3 300
         residents of Clare, Michigan, the complete and expedient remediation of contaminated soils is
         important. The selected remedy, soil vapor extraction, satisfies the remedial action goals and
         achieves acceptable risk levels for all soil contaminants.  Combined with a ground water
         treatment system, it is the most cost-effective remedy and requires the least time to design
         construct, and achieve remedial action goals.  Soil vapor extraction has proven to be a reliable
         technology and, unlike other alternatives, requires no long-term management after completion
 17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were primary in selecting a remedy.  Because more than 15 000 cubic
yards of the contaminated soil is located beneath buildings on the site, soil vapor extraction
was preferred over excavation and disposal.        '
730
                                               -6-

-------
                               Dakhue Sanitary Landfill
                                          OU-1

                       Hampton Township, Dakota County, Minnesota
                              ,           Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Soil

       No soil samples from the landfill were
       collected arid analyzed.  Volatile organic
       compounds (VOCs) were found in
       monitoring  wells downgradient from the
       landfill. Leaching from the landfill was
       identified as the most likely mechanism for
       release of contaminants.  The prevention of
       leaching was the focus of the FS.
             Site History
NPL Proposed:
NFL Final:
FS:
ROD:
10/26/89
8/30/90
3/91
6/28/91
             Background  ..

EPA Fund-lead
PRPs:  Dakhue Sanitary Landfill, Inc.
FS prepared by:  U.S- Environmental
       Protection Agency, Region 5
2.      What volume of material is. to be
        remediated?

        The volume of material to be remediated included:

        •      1,500,000 cubic yards of soil


 3.      What type of site is this?        "'.'''.'

        Municipal Landfill. Former landfill for the disposal of mixed municipal and commercial
 '       waste.  It also accepted small amounts of industrial waste.
 TECHNOLOGY SELECTION                              '           •;     '   '

 4.  ''   What standard technologies were considered for selection in this FS? ^
                                                                     \
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Containment:          Capping (clay, synthetic membrane, bentonite,, bentonite/soil admixture,
                             cement and cement/soil admixtures, lime sludge and lime sludge/soil
                             admixtures, asphalt, and sand), encapsulation
        Thermal treatment:    Incineration    «                         j
                                                                                          731

-------
         Disposal:
  5.
  6.
  7.
                      Excavation and off-site disposal, excavation and on-site reburial in a
                      RCRA landfill
 Was an innovative technology considered in the FS?  If so, which technology?

 No innovative treatment technologies were considered because contaminant hot
 found and because of the volume and characteristics of the waste present.
 What was the cost estimate for the innovative technology?

No innovative technologies were considered.


How did the cost(s) compare to standard technologies?
          rinr     *? tial T6611111! ErOCeSS' ln Which technica»y feeble technologies are identified
         (pnor to the formulation of RAAs), the FS does not quantify costs.  After foe RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening proceT

                                                        altematives '** merit a more detailed
                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
           Alternative
          RAA-1

          RAA-2
         RAA-3
         RAA-4
                         Standard Technology

                 No action

                 Cover system with a clay barrier layer
                 that meets the Minnesota Rules for
                 Mixed Municipal Waste landfill covers

                 Cover system with a clay barrier
                 layer that meets the Minnesota Rules
                 for Mixed Municipal Waste landfill
                 covers, frost protection
                 	•	—	:	_
                 RCRA cover system for hazardous
                 waste closure
                                                                      Estimated Costs
 3 Criteria
    M^HHVK
     $0

 $7,800,000


——————
 $9,800,000





$13,000,000
 9 Criteria
    ^••^MM

     $0

 $7,800,000


•••'

 $9,800,000




~————™
$13,000,000
8.      If a standard technology was chosen, why?

       RAA-3 was chosen because it protects public health and the environment, is the most cost-
       effecuve alternative, and provides adequate long-term effectiveness because of the frost
       protection component.  RAA-1 would not adequately protect human health and the
       environment.  RAA-2 would not provide adequate long-term effectiveness because of the lack
 732
                                                                                         III
                                            -2-

-------
       of frost protection.  RAA-4 would provide adequate long-term effectiveness, but would not be
       as cost-effective as RAA-3.                                        i
9.      If an innovative technology was chosen, why?

       No innovative technology was considered.                           :

                                                               .         . ,| -    •
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?               ,                             j

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluaitiorii.
                                                      •  ,                'i'            '         /•
       Innovative technologies eliminated during the initial screening include the following:
                                                                         ii    .
        •      None

       Innovative technologies eliminated during the three-criteria screening mclrade the following:
                                                                         J        .'' '
        •      None                                                    '!•',.
                                                                    f    •'!
        Innovative technologies eliminated during the detailed analysis include the following:
                                                                         j
                          ;                       -                        i1
        •      None               •                   •'    '              i
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?.  Which of the criteria supported the use of a standard technology?
             '                               .         '                    ' ',''.'
        Protectiveness of human health and the environment, long-term effectiveness, and cost were
        weighted most heavily in selecting a standard technology.

                                                                  i

 72.     What cleanup goals were selected? If the cleanup goal was based on an ARAR,  what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        Because  treatment was not considered, no soil cleanup goals were established.  No soil risk
        levels were calculated.
   ;
 73,    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        »      None              ,            '             •,      '  '..     '       ••'•'•
                                                                                                 733

-------
           Standard technologies eliminated because of cleanup goals include:

           •      None
   14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
   15.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

                  Cost-effectiveness
                  Time to design/construct/operate


   16.     How are measures compared?

          Cost-effectiveness was the primary criterion used to compare alternatives  The chosen
          alternative reduces human health risk to an acceptable level at an acceptable cost. Lower risks
          could be achieved by another alternative, but the costs would be prohibitive   Ease of
          implementation also was considered in the selection process.  The construction time of the
          chosen alternative was expected to be less than other alternatives.
  17.
 What technical considerations were factors in selecting a remedy?  Were technical
 considerations primary in the selection of the remedy?                            •

 Technical site considerations were hot primary in selecting a remedy. Media conditions were
 much more important.  The hazardous waste was intermixed with municipal wastes at the
 landfill, making treatment of only the hazardous components impossible. The large volume of
 wastes in the landfill also made removal and treatment of the wastes inappropriate due to high
costs and high short-term risks. Incineration, excavation, and transport were ruled out because
of the potential release of air emissions. The coarse-grained texture of the material in the
landfill favored a continuous layer or gas control layer.  The impact of frost, burrowing
animals, drying, and differential settling were considered in choosing a barrier layer for the
landfill cap.
734
                                              •-4-

-------
                                 Electro-Voice, Inc.
                                        OU-1

                                  Buchanan, Michigan
                                       Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Dry Well and Lagoon Area Soil/Sludge
       (rag/kg)

       Arsenic                    0.014
       Beryllium                  0.0005
       Benzene                   1.6
       bis(2-Ethyhexyl)phthalate    14
       PCB-1254                  0.375
       Styrene                    3.4
       Tetrachloroethene          14
       Trichlorethene -           0.42
       Benzo(a)anthracene         0.85
       Benzo(k)fluoranthene       2
       Benzo(b)fluoranthene       2
       Benzb(a)pyrene            0.91
       Benzo(ghi)perlyene         0;37
       Chrysene                  0.83
       Dibenzo(a,h)anthracene     0.15
       Ideno(l,2,3-cd)pyrene        0.34
       Ethylbenzene               95
       Naphthalene                14
       Toluene                    330
       Xylenes                    0.006
       Lead                       0.083
       Cadmium                   0.735
                                                              Site History
                                                 NPL Proposed:
                                                 NPL Final:
                                                 FS:
                                                 ROD:
9/8/83
11/21/84
1/91
(5/23/92
                                                              Background
                                                                   ,i
                                                  PRP-lead
                                                  PRPs: Electro-Voic:e, Inc.
                                                  FS prepared by:  Fishbeck, Thompson,
                                                        , Carr & Huber
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      30,000 cubic yards of dry well soil
       •      30,000 cubic yards of lagoon area soil/sludge
                                           -1-
                                                                                        735

-------
  3.      What type of site is this?                             .       '

         Electrical Equipment. An active audio equipment facility located in a residential area.


  TECHNOLOGY SELECTION

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification  and screening of technically feasible
         technologies were:                                                           ,
5.
6.
         Dry Well Soil

         Access restriction:
         Containment:
         Chemical treatment:
         Thermal treatment:
         Disposal:
                        Deed restrictions, fencing, signs
                        Capping, slurry wall
                        Chemical fixation
                        Incineration
                        Excavation, landfill (on-site, off-site)
  Lagoon Area Soil/Sludge

  Access restriction:     "Deed restrictions, fencing, signs
  Containment:          Capping, slurry wall
  Chemical treatment:   Chemical fixation                                    ,
  Thermal treatment:     Incineration
  Disposal:              Excavation, landfill (on-site, off-site)


  Was an innovative technology considered in the FS?  If so, which technology?

 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:

 Biological treatment:   In situ bioremediation, composting
 Chemical treatment:    Solvent extraction, dechlorination
 Thermal treatment:     Soil vapor extraction, in situ vitrification, wet air oxidation


 What was the cost estimate for the innovative technology?

 During the initial screening process, in which technically feasible technologies are identified
 (pnor to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
 formulated costs are estimated as part of a three-criteria screening process (effectiveness
 implementability, and cost) to identify alternatives that merit a more detailed evaluation  '"The
 tte NCP °°StS the"  ^ reC3lCUlated during *" evaluation based on nine criteria established by


RAAs were developed for specific media in the three-criteria analysis and for site-wide media
m^^e"CflnaanfIySiSandtheROD-  Some RAAs were changed in the Proposed Plan
and ROD and these changes are presented parenthetically below
  736
                                                                                                  ,J
                                             -2-

-------
         Cost Estimates for RAAs That Include Innovative Technologies
                   (selected remedial alternative is in bold)
Dry Well Soil
Alternative
RAA-DW-3
RAA-DW-4A
RAA-DW-4B
RAA-DW-5
Innovative Technology
Soil vapor extraction/bioremediation/
cap
Soil vapor extraction/bioremediation/
partial excavation and incineration
Soil vapor extraction/bioremediation/
partial excavation/landfill disposal
Soil vapor extraction/bioremediation/ in
situ vitrification
Estimated Costs
3 Criteria
$1,100,000
$2,500,000
i
$1,500,000
$2,400,000
'i
9 Criteria
—
—
, ->- -
—
 Lagoon areas soil/sludge

 No innovative technologies were incorporated into remedial alternatives.

 Site-wide
Alternative
RAA-3
(RAA-3A)
(RAA-3B)
RAA-4

- -
Innovative Technology
Dry well area cap/soil vapor extraction/
bioremediation/lagoon area cap/ground
water extraction and treatment
Soil vapor extraction/excavation/
stabilization/landfilling of sludge
layer/lagoon area cap/on-site ground
water extraction and treatment/off-
site ground water monitoring .
Soil vapor extraction/excavation/
incineration of sludge layer/lagoon area
cap/on-site ground water extraction and
treatment/off-site ground water
monitoring
Dry well area soil vapor extraction/
bioremediation/partial excavation/
lagoon area cap/on-site and off-site
ground water extraction and treatment
Estimated Costs
3 Criteria
l .

i'
'
9 Criteria
$2,100,000
$4,100,000
49,400,000
$3,100,000

                                      -3-
                                                                                  737

-------
           Alternative
         (RAA-4A)
         (RAA-4B)
         Innovative Technology
  Dry well area soil vapor extraction/
  excavation and landfilling of sludge/
  lagoon area cap/on-site and off-site
  ground water extraction and treatment
 Dry well area soil vapor extraction/
 excavation and incineration of sludge/
 lagoon area cap/on-site and off-site
 ground water extraction and treatment
         RAA-5          Dry well area soil vapor extraction/
                         bioremediation/in situ vitrification/
                         lagoon area cap/on-site and off-site
                         ground water extraction and treatment
                                                                     Estimated Costs
                                                                 3 Criteria
               9 Criteria
                                                                               $5,700,000
                                                                              $11,010,000
                                                       $3,400,000
                                                                                                      "
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)

       Dry Well Soil
          Alternative
        RAA-DW-1
        RAA-DW-2
         Standard Technology
 No action
 Institutional controls
      Lagoon Area Soil/Sludge
         Alternative
        RAA-L-1
        RAA-L-2

        RAA-L-3
        RAA-L-4
        Standard Technology
No action
Institutional controls

Multilayer cap
Excavation/landfill disposal
                                                                    Estimated Costs
                                                                3 Criteria
                                                                   $0
                                                                 $48,000
              9 Criteria
                                                                   Estimated Costs
                                                               3 Criteria
                                                                   $0
$58,000
                                                                $180,000
                                                               $24,000,000
             9 Criteria
                                                      eliminated
             eliminated
738
                                           -4-

-------
Site wide
Alternative
RAA-1
RAA-2
(RAA-5A)
(RAA-5B)
Standard Technology
No action
Access restrictions
Excavate/landfill dry well areas soil and
sludge/cap lagoon areas soil/on-site and
off-site ground water pump and treat
Excavate/incinerate dry well area soil
and sludge/cap lagoon area soil/on-site
and off-site ground water pump and
treat
Estimated Costs
3 Criteria
, .1
- -r— •
I
• ![
1
' i' x-
9 Criteria
$0
$310,000
$8,900,000
>
$13,000,000
 If a standard technology was chosen, why?
          ' '              '             '                   '     '   ! '          -
 Solidification/stabilization and capping of residuals were selected for some wastes.

                                              ..  ' .  -            • . i            • •
 If an innovative technology was chosen, why?                      ,
                     <                                            'i                    ,
                                                                 i
 RAA-3A was chosen because it protects human health and the environment by reducing risk
 posed by ingestion of and dermal contact with contaminated ground water, and ingestion and
 inhalation of dry well soil  and lagoon area soil. This alternative provides protection through
 treatment of the principal threat (dry well area soil), treatment of the contaminated onsite
 ground water, capping of the lagoon area soil, and monitoring offsite ground water. Dry well
 area soil treatment will reduce site contaminants to below Michigan Act 307 Type B levels.
 The underlying sludge will be removed and, solidified if cleanup levels cannot be met with
 solvent vapor extraction (SVE).' Containment of lagoon area soil ensures long-term
 effectiveness and permanence by preventing contact with these soils, and eliminates
 infiltration, which minimizes, if not eliminates, contaminant movement in the soil column.
 Ground water pump and treatment for the onsite ground water remediates the most highly
 contaminated ground water first. Monitoring  the offsite ground water allows EPA to detect
 any changes in the offsite  ground water before selecting a final remedy.  This alternative
 provides long-term effectiveness sinceithe main threats  to the site, dry well soil and
 contaminated ground water, are treated first.  Treatment of dry well  urea soil and ground water
 permanently reduces contaminant toxicity, mobility, and volume. Capping the lagoon areas
 soil reduces contaminant mobility.  This alternative meets all state and federal ARARs. In
 accordance with Michigan Act 307, this alternative meets Type B cleanup criteria for dry  well
 soil and Type C cleanup criteria for lagoon area soil. The chosen alternative poses no
 unacceptable short-term risk. The technologies proposed, SVE and capping, are well-
 established technologies and should not be difficult to implement.  'Die chosen alternative is
 the least .expensive of the  treatment alternatives and has been deemeijl the cost-effective option.

 In the Proposed Plan, RAA-4A was the preferred alternative.  Since jpublishing the Proposed
 Plan, EPA determined that to use an operable unit approach is more appropriate at this time
                                         -5-
                                                                                     739

-------
          for this site than a final remedy selection. This decision was made after considering the
          substantial number of public comments that indicated a preference for monitoring, rather than
          remediating, the offsite ground water. EPA determined that the operable unit approach is more
          appropriate at this time because it is a more focused, logical approach that first treats the
          contaminated soils, which are the source of ground water contamination, and the more highly
          contaminated onsite ground  water.
   10.
740
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?

  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages: during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Dry Well Soil

  Innovative technologies eliminated during the initial screening include the following:

  •      Dechlorination was eliminated because it would not be applicable to aromatic
         compounds found in the dry well.
  »      Wet air oxidation was eliminated because it  has not been proved for the treatment of
         high-solid content waste.

 Innovative technologies eliminated during the screening of the three criteria of the technologies
 include the following:

 •       Composting was eliminated because it has not been demonstrated to  be effective for
         the remediation of organic contaminants in the well soil and its implementation might
         greatly increase the risk of exposure to contaminants.
 •      Solvent extraction was eliminated because it  would not be cost-effective given the
        small volume of contaminated soil.

 Innovative technologies eliminated during the detailed analysis include the following:

 «      In situ bioremediation was replaced by landfilling  and incineration in RAAs 3A  3B
        4A, 4B, 5A, and 5B, in the Proposed Plan and ROD; however, no explanation was '
        given for this change.
 •      In situ vitrification was not eliminated, but it was not included into an RAA and no
        explanation was given. Some discussion suggests  that negative aspects of the process
        include: site buildings could be damaged by the .process given  their proximity to the
        contaminated soil; and there is limited information regarding the efficiency and
        potential drawbacks of the process and therefore treatability studies would be
        necessary.

Lagoon Area Soil/Sludge

Innovative technologies eliminated during the initial screening include the following:

•      Composting was eliminated because it would not be applicable to primary lagoon
       contaminants.
                                               -6-

-------
11.
             lagoon contaminants.
             Dechlorination was eliminated because it would not be
             Solvent extraction was eliminated because it would not be applicable to primary

                                                                applicable to primary

                                                                   applicable to primary

                                                                      applicable to primary
             lagoon contaminants.
             Wet air oxidation was eliminated because it would not be
             lagoon contaminants.
             Soil vapor extraction was eliminated because it would not be
             lagoon contaminants.             -
      Innovative technologies eliminated during the screening of the nine criteria of the technologies
      in the FS include the following:

      •     In situ vitrificaiion was eliminated because this treatment would immobilize site
             contaminants; however, the metal contaminants on site are largely immobile in the soil
             matrix and are not leaching in quantifiable levels to ground water.  Treatment to
             prevent leaching, therefore, is not required.  Moreover, the capital costs would be very
             high. The feasibility would be limited by the lack of vendors for the technology.  This
             process is patented and the only commercial vendor licensed  to supply this process is
             Geosafe Corp.
          -               _                                             i:'           -
      Innovative technologies eliminated during the detailed analysis include the following:

      •     In situ bioremediation was replaced by landfilling and incineration in RAAs 3A, 3B,
             4A, 4B, 5A, and 5B, in the Proposed Plan and ROD; however, no explanation is given
          .   for this change.                                          >
                                                                    •jj

      Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
      to meet one of the nine criteria result in the elimination of the innovative technology? If so,
      which criterion? Which of the criteria supported the use of a standard technology?
                   •    •••           .       ,                 .        •[•••••'..';
      The criteria that were weighted most heavily in selecting an RAA we;re long-term protection
       and cost. The chosen alternative was the least costly of the alternatives that were deemed
       protective through treatment of source contaminants.               \ t
12.     What cleanup goals were selected? If the cleanup goal was based on art ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?

 1      In the FS, many potential cleanup levels were developed in accordance with Michigan Act 307
       Type A, B, or C criteria for both dry well soil and lagoon soil.  A m!ore abbreviated list of
       cleanup levels was presented in the ROD.  The cleanup levels presented in this review are
       those found in the ROD.

               Dry Well Soil                                          i
                      Contaminant
                                           Cleanup Level (ng/kg)    ARAB, or Other Basis
                 Carcinogens
                 Arsenic
                                                    0.4
;!   Background3
                                             , -7-
                                                                                             741

-------
                       Contaminant
Cleanup Level Oig/kg)
                                                                    &RAR or Other Basi
                                                                        Michigan 307b
                 bis(2-Ethyhexyl)
                 phthalate
                             Michigan 307
                                                                        Michigan 307
                                                                        Michigan 307
                 Tetrachloroethene
                                                                        Michigan 307
                 Benzo(a)anthracene
                                                                        Michiean 307
                 Benzo(k)fluoranthene
                                                                        Michiean 307
                Benzo(b)fluoranthene
                                                                        Michiean 307
                Benzo(a)pyrene
                                                                       Michigan 307
                Benzo(ghi)perlyene
                                                                       Michigan 307
                                                                       Michigan 307
                Dibenzo(a,h)anthracene
                                                                       Michigan 307
                Ideno(l,2,3-cd)pyrene
                                                                       Michigan 307
                Frichlorethene
                                                                       Michiean 307
                Noncarcinogens
                                         for cleanup levels •
             'Michigan Act 307 Type B soil cleanup criteria for aquifer protection
              • ?r href'h6-based risk assessments, an excess upperbound individual lifetime cancer
             nsk of 10-  was acceptable and a Hazard Index of 1 or less for noncarcinogens was
             flCCGtS
742
      Lagoon Area Soil/Sludge

      A Type C remedy developed pursuant to Michigan Act 307 has been determined to be relevant
      and I  appropriate for the lagoon area soils because these soils are located in a natural depression
      an unlikely area for future development.  Children, however, might currently and in the future
      trespass and play in this area.  The cap will be designed in accordance with the State of
      Michigan s Act 64. A hazardous waste cap will eliminate or decrease dermal contact with and
      mgestion of lagoon area soil. A cap also will eliminate or decrease infiltration into the soils
                                            -8-

-------
       thereby decreasing the mobility of cadmium, which is present at elevated levels in the lagoon
       area and could pose a future threat to ground water.           ,      '

                           •   N'-  •   • ,   ."'"'"•.. ,  -  '       '    ^   '}• '  '• ••           '   •
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                       •     .    •;'  s      •

       Innovative technologies eliminated because of cleanup goals include:
                                                                 f       :
•  •  '   ••      None'    -          ,                        '      '        J'     ' -  .'
        "  .                                        •                  *    i1
       Standard technologies eliminated because of cleanup goals include:   |

       •      None                                                             ,
                                        •                   '             !                   /

14.    Were treatability studies conducted on the innovative  technology or standard  technology?

       Treatability studies were not conducted.


75.     What measures/criteria were used to compare alternatives?         |

       The following measures were used to compare the alternatives:

             Cost-effectiveness                                                        ,
             Preference for treatment (vs. containment)          ,          ;
             Waste left in place/institutional control


16.     How are measures compared?
                                                                      -  1 • .
                                        • •                .               J
        RAA-3A, a treatment alternative, was preferred over RAA-2, a containment alternative,
        because treatment alternatives are more effective in the long term at eliminating risk
        than the containment alternatives. Furthermore, institutional controls might not
        guarantee reduced risks to human health or the environment in the future.   Of all the
        treatment alternatives, RAA-3A was the least expensive.

                                      ' •       -             •             I      '     •"''.'
 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
                                                            '            \    '                 •  •
        No technical considerations were primary in selecting a remedial alterative.  The proximity of
        buildings to contaminated site soil was a limiting factor in the use of in situ vitrification.
                                               .,.                '  ,V>'              743

-------
                                  Fadrowski Drum Disposal

                                      Franklin, Wise,   .in
                                           Region 5
GENERAL SITE INFORMATION

L      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study ?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       Total PAHs           24.3
       Toluene              1.8

       Test pits (rag/kg)

       Toluene              0.24
       Total PAHs            180
       4,4-DDT              0.31
       Aroclor 1254          1.9
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
N/A
1986
5/91
6/10/91
                                                                  Background

                                                     PRP-lead
                                                     PRPs:  Acme Printing Ink Company
                                                     FS prepared by: Warzyn Engineering,
                                                            Inc.
 2.     What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      142,000 cubic yards of soils with low-level contamination
        •      25 cubic yards of characteristically hazardous soils
 3.     Wliat type of site is this?

        Uncontrolled Waste Site. A former landfill, the site is in a semirural area surrounded by
        mixed residential, light commercial development.
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:     Deed restrictions, controlled land use, assess restrictions
744
                                            -1-

-------
       Containment:

       Physical treatment:
       Thermal treatment:
       Disposal:  '
  Capping (soil cover, clay and topsoil, clay, rooting zone, topsoil, NR
  504, multilayer RCRA)                      !
  Recycling
  Incineration
  Excavation, off-site disposal, oh-site disposal  ;
5.      Was an innovative technology considered in the FS?  If so, which technology?
       ^        '       •              ''  ••        ..'.''       •       ..I-'.--
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Thermal treatment:    In situ vitrification
        What was the cost estimate for the innovative technology?       .1
                        ,       •                 • •                       i       '     •    .  •
                   -     i •  •'   .  •               -                  -       '          '
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs typically are estimated as part of a three-criteria screening process   .
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, the estimated costs were calculated during ah evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementabililty; cost; state/support
        agency acceptance; and community acceptance.
                                                                        I
                 Cost Estimates for RAAs That Include  Innovative Techmoloipes
                             (selected  remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Fencing/deed restrictions/in situ
vitrification/ground water monitoring
Estimated Costs
3 Criteria
N/A
'* •
9 Criteria
$63,600,000
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
            Alternative
           RAA-1
           RAA-2
        Standard Technology
No action
Fencing/deed restrictions/ground water
monitoring


 '     .              -2-
                                                                        Esfimated Costs
3 Criteria
                                                                       N/A
                                                                       N/A
                                                                                   9 Criteria
                                                            $0
               eliminated
                                                                                               745

-------
Alternative
RAA-3A
RAA-3B
RAA-4
RAA-5A
RAA-5B
Standard Technology
Fencing/deed restrictions/ground water
monitoring/Wisconsin cap/leachate
collection/long-term monitoring
Fencing/deed restrictions/ground water
monitoring/RCRA Subtitle C compliant
cap/leachate collection/long-term
monitoring
Fencing/deed restrictions/excavate soil
and drums/off-site incineration and
disposal
Fencing/deed restrictions/ground
water monitoring/excavate contam-
inated soil and drums/recycle and off-
site disposal/Wisconsin cap/leachate
collection/long-term monitoring
Fencing/deed restrictions/ground water
monitoring/excavate contaminated soil
and drums/recycle and off-site
disposal/RCRA Subtitle C compliant
cap/leachate collection/long-term
monitoring
	 	 	 ^ 	
Estimated Costs |
3 Criteria
.N/A
/ N/A
N/A
N/A
N/A
9 Criteria 1
$2,030,000
$3,900,000
$11,400,000
$2,230,000
$4,110,000
. s
 8.      If a standard technology was chosen, why?                                  '            -

        RAA-5A was chosen because the Wisconsin cap provides protection to human health and the
        environment. The cap eliminates direct contact to site contaminants and reduces infiltration of
        water into the disposal area, thereby reducing contaminant mobility through the disposal area
        The chosen alternative also reduces contaminant toxicity and volume through excavation and
        off-site treatment and disposal of contaminated soil and drums. Recycling is the proposed off-
        site treatment, to be confirmed once the nature of the buried waste is identified. Because a
        portion of the site waste will be excavated prior to capping,  this alternative reduces the source
        of contamination to ground water more than containment alone would.  The long-term
        effectiveness of this alternative depends on appropriate monitoring and upkeep   This
        alternative incorporates standard technologies and is easy to  implement.  No unacceptable
        short-term nsk will be posed by this remedy.  Standard safety programs will  be implemented
        to mitigate the nsk  of explosion during the excavation of drums.  RAA-5A was deemed to be
        cost-effective.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
 746
                                             -3-

-------
10.     If an innovative technology was not chosen, why not? At whaVstage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the tiiree criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      None
                                       »  ' '  •-                            i  '   ,   '
       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis include; the following:

        •      In situ vitrification was eliminated because it would be too costly and extremely
               difficult to implement given the site's large variety of debris. Furthermore, this
               alternative would take seven times longer to implement than all other alternatives.


 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?
                                                                          i
        The criteria that were most heavily weighted in selecting a remedy were cost-effectiveness and
        the reduction of contaminant toxicity, mobility, and volume. The chosen alternative
        incorporates removal, treatment, and containment technologies to reduce site risks. In addition
        to reducing site risks from direct exposure to site wastes, the chosen alternative eliminates the
        source of ground water contamination.  Other treatment technologies that also would reduce
        contaminant toxicity and volume were not cost-effective.  The Wisconsin cap was preferred
        over the.RCRA Subtitle C cap because the RCRA cap was more expensive and provided only
        limited additional benefit.

        In situ vitrification was eliminated because it would be extremely difficult and time-consuming
        to implement, and it was prohibitively expensive.

    '  . ,  •       '              -             ,                            ,i  .
  12.     What cleanup goals were selected? If the cleanup goal was based on  an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup  goals?

         Cleanup levels were not established for this site.
                                                -4-                                             747

-------
   13.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 lecnnology meet the cleanup goals?                                           -    ,

 Innovative technologies eliminated because of cleanup goals include:              s

 1      None

 Standard technologies eliminated because of cleanup goals include:

 •      None
  14.
Were treatability studies conducted on the innovative technology or standard technology?

No treatability studies were conducted.
  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

               Cost-effectiveness
               Time to design/construct/operate
               Preference for treatment (vs. containment)


  16.     How are measures compared?
         anroth               Preferred'because il b<*h treats and contains site contaminants, an
         approach that reduces he source of ground water contamination more than containment alone
         would  In contrast to in situ verification, which takes 7 years to implement, the chosen
         alternative takes only J year.  The chosen alternative was deemed cost-effective. In addition
         to costing less than other treatment technologies, the chosen alternative was far more cost
         effective than containment technologies because of its greater benefits.  The Wisconsin cap

                     ^               ^^ ^ RCR        3S more expensive ^ less
 17.     What technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?

        No technical considerations were primary in selecting a remedial alternative.
748
                                              -5-

-------
                                   Folkertsma Refuse
                                          OU-1

                                     Walker, Michigan
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants*
       contaminant levels, and media addressed in
       this feasibility study?

       No principal contaminants were addressed in
       the feasibility study for the waste material,
       sediments, or muck at the site because
       containment was selected as the remediation
       technology.  The site's contaminants,
       however, include volatile organic
       compounds, semivolatile organic compounds
       (including pblynuclear aromatic
       hydrocarbons [PAHs],  and PCBs), and
       inorganics.
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1986
1989
6/19/90
6/28/91
             Background

EPA Fund-lead
PRPs:  None listed
FS prepared by:  PRC Environmental
       Management, Inc.
 2.      What volume of material is to be
        remediated?

        The volume of material to be remediated included:

        •      57,000 cubic yards of waste material
        •      1;300 cubic yards of sediments
        •      12,300 cubic yards of muck
 3.  •'   What type of site is this?

        Industrial Landfill.  A former industrial landfill.
 TECHNOLOGY SELECTION
                                                                     i
 4.     What standard technologies were considered for selection in this FS?
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                             !
        Waste Material/Sediments/Muck

        Access restriction:     Deed restrictions, site fencing
                                              -1-
                                                                                           749

-------
  5.
 6.
          Containment:

          Chemical treatment:

          Thermal treatment:

          Disposal:


          Sediments

          Disposal:
                       Capping (clay, asphalt, concrete, gravel, multimedia), slurry wall  grout
                       curtain, sleet piles, vibrating beam, grout injection, block displacement
                       Organic polymer solidification, cement solidification, HAZCON
                       solidification, Soliditech solidification
                       Incineration (rotary kiln, fluidized  bed, multiple hearth, infrared
                       plasma arc) off-site incineration, high temperature fluid wall reactor
                       Excavation, on-site sanitary landfill, off-site RCRA Subtitle C landfill
                       type H landfill, type HI landfill, off-site sanitary landfill
                      Mechanical excavation, hydraulic excavation, dewatering (drying beds
                      mechanical filtration, centrifugation, gravity thickening)
Was an innovative technology considered in the FS?  If so, which technology?

                                 during the identification •* screening of
         Waste Material/Sediments/Muck

         Biological treatment:   Composting, landfarming, biodegradation, bioharvesting, soil aeration
         Chemical treatment:    Oxidation, solvent extraction, soil washing (solvent), dfchlorination
                               vapor extraction                                                '
         Thermal treatment:     Thermal volatilization, molten salt reactor, in situ vitrification
     was the cost estimate for the innovative technology?
                                  ? °CeSS> ln Which technically feasible technologies are identified
                    f         " °f RAAS)' the FS d°eS ~n0t ^Uantify costs"  After t^ RAAs have been
         n         hr   are/Stln!ated SS ^ °f a three-criteria weening process (effectiveness,
        in plementabihty and cost) to identify alternatives that merit a more detailed evaluation

        S TCP  C°S,  rthaTCalCUlated dUri'ng m 6ValUati0n ^ °n "ine Criteria esSh
        the NCR  Costs at the three-cntena screening were calculated for independent remedial
        technologies and not for remedial action -alternatives.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
                                  Innovative Technology
                                                                                   9 Criteria
                                                                                   — t
                                                                                  $42,200,000
750
                                              -2-

-------
7      How did the cost(s) compare to standard technologies?             -  j

                 Cost Estimates for RAAs That Include Standard Technologus
                            (selected remedial alternative is in bold)
======
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8
^-f^=!!^^=^=^^^^=^^=^=^=^=i^=;
Standard Technology
No action
Clay cap
Concrete cap
Excavation/off-site disposal at RCRA ,,
Subtitle D landfill '
Excavation/off-site disposal at RCRA
Subtitle C landfill
Excavation/thermal treatment/on-site
disposal
Excavation/HAZCON or Soliditech
solidification/on-site disposal
In situ stabilization/solidification
Estimated Costs
3 Criteria
N/X"
N/A
N/A
N/A
i
N/A
N/A
N/A
I
1
'N/Aa '
9 Criteria
$561,000
$1,500,000
$3,300,000
$9,500,000
$23,000,000
$39,000,000
$23,000,000
$17,000,000
  8.      If a standard technology was chosen, why?

         A standard technology (RAA-2) was chosen because it reduces exposure to contaminants and
         reduces the potential for contaminants to migrate to ground water, doesn't require excavation
         or thermal techniques which would pose a risk to the community from fugitive dust and air
         emissions, and is the least costly.
  9.     If an innovative technology was chosen, why?

         An innovative technology was not chosen.
   10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?  "   '                                           .       -    ,

          Innovative technologies could be eliminated from the remedial technblogy selection process at
          three stages:  during the initial screening; during the screening of the three criteria of
          effectiveness, implementability, and cost; or during the detailed evaluation.
                                                 -3-
                                                                                              751

-------
           Innovative technologies eliminated during the initial screening include the following:

           "       Composting was eliminated because it would not be effective in treating the metals
                   present in the waste and the technology has not been proved effective for polynuclear
                   aromatic hydrocarbons (PAHs) 3 or more rings.
           •       Landfarming was eliminated because it has not been proved effective for the site's
                   wide variety of metallic and organic contaminants and it is very difficult to biodegrade
                   high-ringed PAHs to clean-up goals.                    ,                         -
           •       Biodegradation was eliminated because it has not been proved effective for PAHs with
                   three or more rings. Mixing also would be complicated by scrap in the landfill and it
                   would be difficult to monitor.
           •      Bioharvesting was eliminated because PAHs do not bioaccumulate.
           "      Soil aeration was eliminated because the contaminants have low vapor pressures and
                  are sorbed strongly to wastes and sediments.
           •      Soil washing was eliminated because contaminants have low water solubility, are not
                  volatile, and are  sorbed strongly to wastes and sediments.
           •      Dechlorination was eliminated because they would not be applicable to the site's
                  contaminants.
           "      Thermal volatilization was eliminated because the contaminants have low vapor
                  pressures and are sorbed strongly to wastes  and sediments.
           «      Vapor extraction was eliminated because it would not be applicable to site
                  contaminants.                                             .
           »      Molten salt reactor was eliminated because  it has not been proved effective on a large
                  scale for a wide variety of contaminants, and no commercial units are available
           •      Oxidation was eliminated because it is not effective for treating materials with high
                  organic content and  may oxidize metals (Cr) to more toxic forms.

          Innovative technologies eliminated during the screening of the three criteria  include the
          following:

          »      Solvent extraction was eliminated because it would not be  effective for the site's
                 contaminants.  Overall implementability would be hampered by the need for a solvent
                 treatment system  and additional materials. Capital and O&M costs would be high  It
                 was  not considered effective because the media requires further treatment and disposal
                 after the process is completed.  The solvents and contaminants  left in the treated
                 material could be more mobile than the original contaminants and would pose public
                 health and environmental risks.

         Innovative technologies eliminated during the detailed analysis include the following:

         •      In situ vitrification was eliminated because the effectiveness could be affected by the
                 amount of metal in the fill area, generation of air emissions pose a risk to community
                 time to complete is long, few vendors are available and the process requires      ;
                 specialized equipment and it's very costly.
„*'
752
                                                -4-

-------
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?
                                    ''.---        •'                  | .
        The most heavily weighted criteria in selecting the technology were reduction in mobility of
        contaminants, short-term effectiveness, implementability, and cost.  Sljiort-term risk, short-term
        effectiveness, and implementability eliminated the innovative technology.

                                                                         .. K     '    •
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to  establish cleanup goals?     !
                                                       .                  I    .     .     ,
        No cleanup goals were specified for the remediation of waste materials, sediments, or muck
   ^     because containment was the selected response action.             '.!:•'.

        For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10f
        was acceptable.  For noncarcinogens, a Hazard Index less than or .equal to  1.0 was acceptable.
                                                               /     ' '   I      '      .
                                                    , ' '                   i, . "
 13.     Was the innovative technology eliminated because of the cleanup goaj.s? Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:
                      '                     '   '                          i       !-     '
        •      None

        Standard technologies eliminated because of cleanup goals include:  [
                                                                         i    '         ^   .   '   . •
        "      None                 .              '  '        •        ."!•'•'       r  ,   -
                                                              ' ^  '      ',\
                                                                       • 1     '           -

 14.     Were treatability studies conducted on  the innovative  technology or standard technology?

        No treatability studies were conducted.      '        ,              j

                .                                           -             \\        ~   .         • "
                                                               •         i.                ,' '
 15.    What measures/criteria were Used to compare alternatives?         :\
                                                                        \\         '   ,  .
                                                                        ,' '             •
        The following measures were used to compare the alternatives:      j

                Total  cost
                Time to design/construct/operate
                Short-term effectiveness                                  [

                                                                        'i              ' •
                                                                        J             ' '
 16.     How are measures compared?   .                               \  :

         The selected remedy is the most cost-effective alternative proposed.  While other alternatives
.  •-'      would ensure greater long-term effectiveness, the selected remedy reduces site risks to within
         EPA's.acceptable risk range for carcinogens (10"4 to 10'6) and noncarcinogens (HI < 1) at the
         lowest cost.  The selected alternative does not emphasize treatment and does not meet the
                                                -5-
                                                                                             753

-------
          catena to reduce contaminant toxicity, mobility, or volume.  While two other alternatives
          (RAA-6 and RAA-9) would meet these criteria, they would pose greater short-term risk to site
          workers and the community during implementation, would take much longer to implement
          and would be more difficult to construct and operate.'                       .          '
   17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Folkertsma Refuse contains large volumes of low-level organic and inorganic waste material
which are best remediated by engineering controls such as capping.  Soil permeability was
another consideration in selecting a remedial  technology.
754
                                              -6-

-------
                                   Fultz Landfill
                                        OU-1

                                    Byesville, Ohio
                                       Region 5,
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study? .

       Maximum concentrations of principal
       contaminants were:

       Leachate Sediment (mg/L)
Methylene chloride
Toluene
Arsenic
Beryllium
Cadmium
Lead
Nickel ,
Chlorobenzene
Ethylbenzene
Xylenes (total)
Barium
Mercury .
Selenium
Thallium
Sediment (mg/kg)
1,1 Dichloroethane
Benzene
Toluene .
Pentachlorophenol
Arsenic
Beryllium
Cadmium
Lead
Nickel -
Chlorobenzene
Ethylbenzene
Xylenes (total)
Antimony
Barium
Chromium
Copper • .
0.01
0.024
0.022
0.00 1
0.003
0.049
0.039
0.057
' 0.064
0.008
0.831
0.0001
0.0007
0.0006
!
0.018
0.017
0.15
0.39
0.077
0.002
0.007
0.163
0.073
0.086
0.017
0.014
0.01 ,
0.113
- 0.028
68.5
            Site Histtory
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
N/A
6/91
9/30/91
                                                             Background

                                                 EPA Fund-lead   ;
                                                 PRPs:  Not listed
                                                 FS prepared by:  PRC Environmental
                                                        Management, Inc.
                                           -1-
                                                                                      755

-------
Mercury
Selenium
Thallium
14.3
0.002
0.002
          Surface Soil (mg/kg)

          Methylene chloride    0.056
          Toluene              0.12
          Arsenic               0.027
          Beryllium            0.001
          Cadmium             0.004
          Lead                 0.049
          Nickel                0.058
          Barium               0.265
          Chromium            0.037
          Copper               0.219
         Mercury               0.0002
          Selenium             0.002
  2.      What volume of material is to be remediated?

         The volume of material to be remediated included:

         •      770,000 cubic yards of landfilled material


 3.      Wliat type of site is this?

         Municipal Landfill. Closed sanitary landfill where hazardous industrial wastes were co-
         disposed with municipal waste. The landfill, overlies two abandoned coal mines, one of which
         is flooded and used as a source of potable water.


 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:

        Containment:
        Chemical treatment:
        Disposal:
Deed restriction, land use and development restrictions, fencing with
warning signs, zoning ordinances
Single-layer capping (soil, clay, concrete, or asphalt) multi-layer cap of
low permeability material and/or synthetic liners, subsurface support to
prevent mine subsidence, grading, and revegetation, sediment and
erosion control, slurry wall
Stabilization/solidification
On-site or off-site disposal
756
                                              -2-

-------
     an innovative technology considered in the FS?  If so, which technology?
Innovative technologies considered during the identification and screening of technically
feasible technologies were:

Chemical treatment:    Soil washing, in situ soil flushing, reduction/oxidation
Thermal treatment:     Vitrification, general in situ thermal treatment
Biological treatment:   General biological treatment               v  •   "
What was the cost estimate for the innovative technology?            ,

During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
estimated  costs then are recalculated during an evaluation based on nme criteria established by
the NCP.  No innovative technologies were incorporated into remedial action alternatives.

How did the.cost(s) compare,to standard technologies?              i
                                                                 i
          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action
Deed restrictions on land and water
use/public information: program/zoning
and ground water drilling ordinances/
fencing and sign positing/ development
of an alternative water supply/long-term
monitoring of air, surface water,
leachate, ground water, and sediments
RAA-2 with multi-layer RCRA (Subtitle
C) cap with gas venting system and a
leachate collection system/installation of
subsurface structural supports to prevent
collapse of the cap/wetlands
replacement ,
RAA-3 with ground water extraction
and on-site treatment
Estimated Costs
3 Criteriia"
N/A
N/A
i
•NiA
N/A
9 Criteria
$0
$2,300,000
$21,000,000
$21jOOO,OOOb
• • /
                                       -3-
757

-------
• Ilernative
RAA-5
RAA-6
RAA-7
RAA-8
RAA-9
RAA-10
Standard Technology
RAA-2 with RCRA (Subtitle C) on-site
landfill/excavation and compaction of
wastes and the site for reburial in
landfill/treatment of the abandoned
underground mine to prevent
subsidence/backfilling of the mine with
rock underdrain/erosion and sediment
coritrols/dewatering of excavated
materials/wetlands replacement
RAA-3 with subsurface barrier (slurry
wall)
RAA-4 without multi-layer cap and
leachate collection system
RAA-3 with an upgrade to the Byesville
Water Treatment Plan to prevent
potential contamination of the public
drinking water supply
RAA-4 and RAA-5
RAA-2 with a coal mine aquifer cut-off
barrier of low permeability compacted
clay/erosion and sediment controls/
dewatering of excavated material/
surface water control/wetlands
restoration
Estimated Costs
3 Criteria^
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$57,000,000
$21,000,000
eliminated
eliminated
eliminated
eliminated
        *No specific costs were given at 3 criteria stage.                                  •
        bln the ROD, the present worth cost given for RAA-4 was $19,480,700.


8.      If a standard technology was chosen, why?
                                                                         f
        A RCRA cap was selected because it is protective of human health and the environment; it
        meets state standards for closure of existing landfills, and solid waste landfill siting criteria,
        easy to implement with widely available equipment and materials and well established reliable
        methods.
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
738
                                             -4-

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                                                 "'•-,'•          . j          • • '
       Innovative technologies1 could be eliminated from the remedial technology selection process at
       three stages: during the initial  screening; during the screening of the three criteria of    .,,;..
       effectiveness, implementability, and cost; or during the detailed evaluation..       .    .

       Innovative technologies eliminated during the initial screening include: the following:

       •      Soil washing was eliminated because it would be difficult to implement due to the
               requirement to excavate and treat all landfilled wastes.      j
       •      Reduction/oxidation was eliminated because it would be difficult to implement due to
               the requirement to excavate and treat all landfilled wastes.               -
       •      Soil flushing was eliminated because it would be difficult to implement due to the
               requirement to excavate and treat all landfilled wastes.
       •      Vitrification was eliminated because the depth of the landfill, the low level of
               contamination, the soil  type, and the commingling of hazardous v/ith nonhazardous
               wastes would make the technology difficult to implement.
       •      In situ thermal treatment was eliminated because it could not ^be Implemented safely
               due to the danger of an underground fire starting within the landfill and spreading to
               the abandoned mines below.
       •      Biological treatment was eliminated because the depth of the landfill, the low level of
               contamination, the soil  type, and the commingling of hazardous v/ith nonhazardous
               wastes would make the technology difficult to implement.   !
                                       .                 -               i            .
       Technologies eliminated during the screening of the three criteria include the following:
                                                                       .i                -      .
       •      None                                                   ''.'..
                                                                       :j         . .          • -
       Technologies eliminated during the detailed evaluation include the following:

       •      None.  .     ..       ,       .           .  •     . •         i     '   ,   •         •   •
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Protection of human health and the environment and implementability wzis the criteria
        weighted most heavily in selecting a technology.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
                         '•'•••              '!
        No cleanup goals were established for soil or sediments. Risk were hot calculated for potential.
        exposures to soil and sediment.                                                i
                                                                                               759
                                               -5-         '

-------
  13.
  Was the innovative technology eliminated because of the cleanup goals? Could the standard
  technology meet the cleanup goals?                       .

  Innovative technologies eliminated because of cleanup goals include:

  •      None                                                          • •  .

  Standard technologies eliminated because of cleanup goals include:

  «      None                                                 ,
  14.
  Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

                Risk level achieved
                Time to design/construct/operate


  16.     How are measures compared?

         Remedial alternatives were primarily compared based on achieving the lowest risk levels from
         exposure to ground water and surface water during implementation.  Ease of implementation
         was a secondary measure.
 77.
 What technical considerations were factors in selecting a remedy?  Were technical
 considerations primary in the selection of the remedy?

 The abandoned room-and-pillar coal mines found under the landfill complicate the use of
 containment because of the potential for subsidence caused by the areas where the coal has
 been removed. A multi-layer cap was preferred over a single-layer cap because single-layer
 caps are less durable, require more maintenance, and do not meet ARARs.  The large volume
 of materials was a primary consideration in the evaluation of treatment technologies  that
 required excavation because it would be difficult to separate the hazardous components from
 the rest of the waste and all  landfilled materials would have to be treated.  Also, the volume of
 waste would create storage problems, volatile emissions, contaminated runoff from storage
 piles, and the need to dewater.  In situ thermal treatment was eliminated as unfeasible because
 of the danger of an underground fire starting within the landfill and spreading to the
underground mines.  In situ soil washing, vitrification, and biological treatment were
eliminated because the depth of the landfill, the low level of contamination, the soil type, and
the commingling of hazardous  with nonhazardous wastes made these technologies  difficult to
implement.
760
                                              -6-

-------
                                     G & H Landfill
                                           OU-1

                                 Shelby Township, Michigan
                                          Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?
                                          +•
       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       PCBs                 180
       BETX                10,000
       PNA                 880
       Chlorinated VOCs     4,030
 2.      What volume of material is to be
        remediated?
                                   Site History
                      NPL Proposed:
                      NPL Final:
                      FS:
                      ROD:
N/A
9/83
8/17/90
12/21/90
                                   Background

                       EPA Fund-lead    j
                       PRPs:  N/A       ,:•
                       FS prepared by: CH2M Hill
        The volume of material to be remediated included:                 |
                                            • ,                         i ,
        •      800,000 cubic yards of landfill material
                              •       '                                 1

 3.      What type of site is this?                                        J

        Municipal Landfill.  A inactive landfill bordered by industrial and residential areas.
 TECHNOLOGY SELECTION

 4.     What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
         Chemical treatment:
         Thermal treatment:
         Disposal:
Deed restrictions, fencing
Surface controls, capping (soil, clay, asphalt, concrete, single-layer,
multilayer, synthetic membrane, clay-geomenibrane) vertical barriers,
horizontal barriers
Solidification/stabilization                 j
Incineration                              i
Excavation, disposal (on-site, off-site)       |
                                              -1-
                                                                                              761

-------
   5.
  Was an innovative technology considered in the FS? If so, which technology?

  Innovative technologies considered during the identification and screening of technically
  feasible technologies were:

  Biological treatment:  In situ bioreclamation
  Phys/Chem  treatment:  In situ soil flushing, oxidation, reduction, in situ soil vapor extraction
  inermal treatment:    Low-temperature volatilization, in situ vitrification
   6.       What was the cost estimate for the innovative technology?

           During the initial screening process, in which technically feasible technologies are identified
           (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation  In this case, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.


                   Cost Estimates for RAAs That Include  Innovative Technologies
                               (selected remedial alternative is in bold)
             Alternative
           RAA-4A
                           Innovative Technology
                                                                                   $40,000,000
                   Soil-clay cap/slurry wall/ground
                   water extraction and treatment/(exca-
                   vation of soil with greater than 500
                   ppm PCBs/treat with incineration,
                   vitrification, or  other EPA-approved
                   destructive technology)"
                                          .

•Excavation and treatment of PCB-contaminated soil outside the slurry wall was added to the
chosen alternative in the ROD.  It is  not anticipated that soil with these high levels will be
encountered.                                                                   .
                                                                         Estimated Costs
3 Criteria

   N/A
                                                                                    9 Criteria
  7.
762
How did the cost(s) compare to standard technologies?

          Cost Estimates for RAAs That Include Standard Technologi
                     (selected  remedial alternative is in bold)
                                                                             es
Alternative
RAA-1
RAA-2
	 -=======
Standard Technology
No action
Fencing/deed restrictions/ground water
monitoring
•
Estimated Costs
3 Criteria
N/A
•N/A
9 Criteria
$0
$3,600,000
                                               -2-

-------
Alternative
RAA-3A
RAA-3B
RAA-4B
RAA-5A
RAA-5B
RAA-6A
RAA-6B

Standard Technology
Soil-clay cap
Soil-clay cap/slurry wall
Soil-clay cap/slurry wall/ground water
injection, extraction, and treatment
Soil-clay cap/slurry wall/ground water
extraction and treatment/excavation of
hot spots/disposal in on-site RCRA
landfill
Soil-clay cap/slurry wall/ground water
extraction and treatment/excavation of
all site waste/disposal on-site RCRA
landfill
Soil-clay cap/slurry wall/ground water
extraction and treatment/excavation of
hot spots/incineration of hot spots
Soil-clay cap/slurry wall/ground water
extraction and treatment/excavation of
hot spots/incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
'|
N/A
'i
N/A
i T
|
. N/A
9 Criteria
$29,000,000
$38,000,000
eliminated
eliminated
eliminated
$470,000,000
eliminated
8.      If a standard technology was chosen, why?

       Standard, technologies were chosen (see below).
        If an innovative technology was chosen, why?                       ;|

        RAA-4A was chosen because it reduces risk associated with direct exposure to site soil and
        contaminated ground water.'1 A cap that meets state and federal landfill closure criteria will
        provide a barrier to direct contact. It also will decrease the rate of precipitation infiltration
        through the landfill by approximately 80 percent. Implementation of ;the cap and slurry wall
        will further impede the mobility  of landfill contaminants and reduce  ground water contaminant
        loading into the aquifer outside the slurry wall.  Ground water pumping and treatment will
        restore the aquifer to usable conditions.  It offers long-term effectiveness since the ground
        water outside of the slurry wall will  be treated.  This alternative has  proposed soil excavation
        and treatment if PCBs in excess of 1 ppm are discovered in soil outside of the slurry wall.
        The excavated soil will be treated by either incineration, vitrification, or any other EPA
        acceptable destruction technology deemed appropriate.  This alternative  minimizes short-term
        risk since soil will be excavated only if high levels of PCBs are discovered outside of the
        slurry wall.  Implementation of this  alternative can be accomplished  iin 4 years and ground
        water cleanup standards will be  met in 30 years, making this the  most timely of all the
        alternatives.  Cap  materials  are readily available and implementation iwill be large scale, but
        straightforward. Implementation of  the slurry wall will require some, compatibility testing to
                                                -3-
763

-------
   10.
n.
                                           Slte'S WaSte
                                                                   The selected alternative is cost-
                                                                                                           r
                                       *"
                                                           A>
                      nnplementability, and cost; or during the detailed evaluate,

         Innovative technologies eliminated during the initial screening include the following



                                                         !t would not te
WOUld te dWcn"
           wouid
                                                                not
                                                                                   landfill
                                                                                          '
        foiling: teChn°10gieS eHminated dUring the SCreenin* °f the *« criteria include the




        "      ^'£ZeratUre V0latilization Was not -^orated into an RA but no explanation




        Innovative technologies eliminated during the detailed analysis include the following:


        •      None

764
                                             -4-

-------
' 12.     What cleanup goals were selected?  If the cleanup goal was based on
        ARAR?  What risk level was selected to establish cleanup goals?
                               an ARAR, what was that
                     Contaminant
Cleanup Level (rag/kg) |  ARAB, or Other Basis
                 Carcinogens
                 PCBs  ,
                          Michigan Act 307V
                               i  EPAb
               'Michigan Act 307, Type B cleanup achieved levels that are based on the reduction of
               contaminants to levels that pose an individual lifetime cancer risk of 10"6.
               ''EPA's Guidance on Remedial Actions for Superfund Sites with PCB Contamination,
                1989.
  13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
         technology meet the cleanup goals?                              i
                                   •  •  '  ,    '      '             '.     -i •       '.
         Innovative technologies eliminated because of cleanup goals include:

       •  •      None   ,                    -                           ''•.•'•,-
                                                                       !•
         Standard technologies eliminated because of cleanup goals include: j

         •      None          .                                       T
  14.     Were treatability studies conducted on the innovative technology or standard technology?

                                                                  •    i      .
         Treatability studies were not conducted.                         ;     /,
  75.    What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

               Cost-effectiveness
               Time to design/construct/operate
               Impact on nearby populations
   16.     How are measures compared?                             '     '

          Cost-effectiveness and time to reach cleanup levels were considerations in selecting a remedial
          alternative. The chosen alternative, RAA-4A, was very similar to RAA.-3A. Though slightly
          more .expensive, RAA-4A was preferred because it will achieve ground water cleanup levels
          within a reasonable time frame.  With the implementation of active ground water cleanup,
          cleanup goals will be reached within 30 years. Natural attenuation of ground water, as
          proposed by RAA-3, would take more than 30 years. Short-term risk to nearby populations
        -  also was a concern.  Though RAA-6A would more immediately reduce site contaminants,


                               .                 -5-       '•            •
                                                       765

-------
    17.

                         consider
-------
                                  H. Brown Co., Inc.

                                    Walker, Michigan
                                        Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soils/(Surface and Subsurface)1 (mg/kg)

       Lead                       649,000
       Antimony                  4,980
       Arsenic          ,          463
       Beryllium                  13.6
       Chrysene                   120
       Isopropene                 0.24
       Benzo(a)anthracene         15.95
       Benzp(a)pyrene             6
       Benzo(b)fluoranthene        15.7
       Benzo(k)fluoranthene        10.9
       Dibenzo(a,h)anthracene      3.9
       Ideno(l,2,3-cd)pyrene        4.3
       Bis (2-ethylhexyl)
        phthalate (BEHP)         120
       N-nitrosodiphenyl
        amine(NNDPA)           2.5
 -.    PCBs (Aroclor-1254)        9.6
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
3/29/85
6/10/86
6/29/92
9/30/92
             Background

EPA Fund-lead
PRPs:  Tessie Brown, H. Brown Co., and
    ''•"" approximately 1,400 PRPs
FS prepared by: PRC Environmental
       Management, lee.
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

      • ••-     180,000 cubic yards of soil
       •      Volume of sediments to be remediated was not given
    'Other data were presented in Table 11 of the ROD as "current"; however, it is unknown whether
these data were validated or used in the risk assessment.              .!-,•'
                                           -1-
                                                                                         767

-------
3.      What type of site is this?

        Recycling.  A former battery reclamation operation which had been operating since 1961.
        Prior to 1961, the site was an uncontrolled dump.  H. Brown ceased active reclamation,
        including battery shredding in 1981 or 1982. From then on, the operation has accepted scrap
        nonferrous metals that are sold to off-site purchasers. The site is located in a light industrial
        area.
TECHNOLOGY SELECTION                                                     ,

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:      Institutional actions (fencing, deed restrictions)
        Containment:          Capping (clay, asphalt, concrete, multicomponent)
     '   Phys/Chem treatment:  Solidification, soil aeration
        Thermal treatment:     Incineration, smelting
        Disposal:              Excavation, on-site landfill (RCRA, sanitary), off-site landfill (RCRA)


5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Ex situ aerobic biodegradation, ex situ anaerobic biodegradation, in
                              situ biodegradation
        Phys/Chem treatment:  Vapor extraction, soil washing, Bureau of Mine's (BOM) process,
                              modified lead leaching process
        Thermal treatment:     Vitrification


6,      What was the cost estimate for the innovative technology?                           ,     •

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost)  to identify alternatives that merit a more detailed
        evaluation.  The estimated costs then are recalculated during an evaluation based on nine
        criteria established by the NCP.  "
  768
                                              -2-

-------
               Cost Estimates for RAAs That Include Innovative Technologies
                          (selected remedial alternative is in bold)
Alternative
RAA-8
RAA-10
RAA-11
RAA-12
RAA-13
RAA-14
Innovative Technology
Pilot-scale treatment (modified leaching
process) and containment of soil/ground
water treatment/drainage remediation
Pilot- and full-scale soil treatment
(modified leaching process)/ground
water treatment^dramage remediation
Soil smelting/disposal/ground water
treatment/drainage remediation
Soil smelting/treatment/grpund water
treatment/drainage remediation
Soil smelting/containment/grbund water
.treatment/drainage remediation
\ _
Soil smelting/solidification and
containment/ground water treatment/
drainage remediation
Estimated Costs
3 Criteria
$6,300,000
$24,000,000
• . f
1
$36,(XX),000
$25,«)00,OQO
$12,(XX),QOO
i
$18,000,000
i'
1
9 Criteria
$6,300,000
(ROD-
$7,200,000)
$24,000,000
$36,000,000
$25,000,000
$12,000,000
$18,000,000
7.f     How did the cost(s) compare to standard technologies?           ]

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)   j
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
Standard Technology
No action
Limited action
Limited containment
Complete containment
Limited containment/drainage
remediation . • "
Complete containment/limited drainage
remediation
Soil containment/ground water
treatment/drainage remediation
Estimated Costs
3 Criteria
$0
$440,000
$4,500,000
$4,600,000
$4,500,000
$4,600,000
. .1 ' -
$6,()00,QOO
I ,
9 Criteria
$0
eliminated
eliminated
eliminated
eliminated
eliminated
$6,000,000
(ROD
$6,900,000)
                                           -3-
769

-------
             Alternative
                             Standard Technology
                                                                         Estimated Costs
                                                                     3 Criteria
 9 Criteria
           RAA-9
                    Soil disposal/ground water
                    treatment/drainage remediation
                                                                    $41,000,000
$41,000,000
           RAA-15
                    Solidification and containment of
                    soil'/ground water treatment/drainage
                    remediation
                                                                    $15,000,000
$15,000,000
         "Contaminated sediments to be treated and disposed along with contaminated soil.
 8.      If a standard technology was chosen, why?

         RAA-15 was selected because solidification and containment of all soil exceeding cleanup
         standards permanently reduces and controls existing and potential risks through treatment and
      .   engineering controls and provides the greatest overall protection and long-term effectiveness
         for the site.  This alternative also has a high degree of short-term effectiveness.  The
         solidification process substantially reduces the mobility of site contaminants and is easy to
         implement because vendors are readily available and the technology involved does not require
         pilot-scale studies or rely on off-site  treatment or disposal. In addition RAA-15 complies with
         all ARARs for contaminated soil at the site. The solidification process is a BDAT for treating
         lead-contaminated soils, and its use should provide compliance with Land Disposal Restriction
         (LDR) regulations and cleanup standards for all media at the site.  Because treatment will
         render the contaminated soil nonhazardous,  the construction of a RCRA-corhpliant
         multicomponent cap and a high-density polyethylene (HDPE) curtain will meet ARARs
         required for m-place closure under Michigan Hazardous Waste Management Act (Act 64)
         Finally the selected  alternative can be implemented at a moderate cost compared to the other
         alternatives.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
 10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      Ex situ aerobic and anaerobic biodegradation were eliminated because they would not
       be applicable due to the high concentrations of inorganic contaminants at this site.
•      Vitrification was eliminated because it would not be applicable to the site.  Battery
       chips might bum because of the very high temperatures used by  the process.
770
                                              -4-

-------
»      In situ biodegradation was eliminated because it would not be; applicable since
       biological treatment is effective only on certain organics.

Innovative technologies eliminated during the screening of the three criteria include the
following:

•      Vapor extraction was eliminated "because of low vapor pressure of organic
       contaminants in soil at the site, relatively low permeability of site soil for air, and the
       age of contaminants in the soil at the site, vapor extraction would not be effective in
     '  lowering the concentrations of organic target contaminants (TCs) in soil at the H..
       Brown site." The FS used the U.S. EPA Soil Vapor Extraction Technology Reference
       Handbook (EPA, 1991) to determine the applicability of vapor extraction for soil
       treatment at this site.                      '                 |
•      Soil washing was eliminated because it would not be effective for remediating soil at
       this  site because: the diverse nature of debris in the site's soil1 likely would clog the
       soil  washing system, slowing the washing operations, possibly affecting treatment, and
       adding to O&M costs; organic contaminants in the soil likely >vould cause problems in
       formulating a suitable washing^solution; and release of hydrogen isulfide gas during the
       regeneration of surfactant could result in potentially hazardous; working conditions.
•      BOM process was eliminated because the  modified lead leaching process was expected
       to be more effective than the BOM process, at a comparable cost. The BOM process is
       difficult to implement, it has not yet been tested on a,full-scale basis, and it is not
       available from any vendor; therefore, equipment involved in title process would have to
       be originally designed and fabricated. The FS states that this process also might be
       difficult to implement for the  same reasons as soil washing.

Innovative technologies eliminated during the detailed analysis include the following:
                                                                -\      .,     .  ,   •  . •
•      The modified  lead leaching process was eliminated because this technology would be
       more difficult to implement than standard technologies, primarily because no vendor is
       currently  available and the equipment for  treating the soil would have to be originally
       designed and fabricated.  In addition, pilot-scale testing would be required to determine
       whether full-scale treatment is possible. This technology also would have the lowest
       short-term effectiveness because of the required pilot-scale tesiting of the soil treatment
       process before implementing the rest of the alternative.  Any (alternative that requires
       treatment must meet federal LDR treatment standards (40 CFR 268). This ARAR
       might not be met if the lead leaching process is found to be ah ineffective treatment
       process.                                                   i
•      Smelting was  eliminated but no specific reason was given.  Smelting was proposed in
       RAA-11, RAA-12, RAA-13, and RAA-14.  These alternatives were eliminated due to
       issues related to  the other components of  the remedy and not specifically because they
       proposed smelting. The ROD states that RAA-11, RAA-12, RAA-13, and RAA-14
       would be somewhat difficult to implement because of the need for regulatory
       determination of compliance for the receiving facility.  The FS states that, although a
       smelter that would accept the lead contaminated soil has been identified, the ability of
       the  smelter to  comply with CERCLA off-site policy, and to maintain sufficient
       treatment capacity would have to be investigated.            !
                                        5                                               771

-------
        Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        Long- and short-term effectiveness were significant criteria in selecting chosen remedy for this
        site. Because all of the alternatives would meet ARARs, the greatest degree of variability was
        for long- and short-term effectiveness.  Alternatives that would leave untreated waste in place
        were judged to have  correspondingly low long-term effectiveness, whereas alternatives that
        would treat the waste before on-site containment were judged to have a high degree of long-
        term effectiveness and permanence. Alternatives that would require pilot-scale studies prior to
        implementation (such as the innovative alternatives) would have low short-term effectiveness.
        The selected alternative was considered to have a high degree of short-term effectiveness
        because it would be easily implemented with minimal planning and readily available vendors.
12.
What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?

Cleanup goals were not established specifically for sediments; however, sediments will be
consolidated with site soils and all soils/sediments exceeding cleanup standards will be treated
by an in situ solidification/stabilization process.
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Lead
Beryllium
Arsenic
NNDPA
PCBs
Benzo(a)anthraceneb
Benzo(a)pyreneb
Benzo(b)fluorantheneb
Benzo(k)fluorantheneb
Chryseneb
Dibenzo(a,h)anthraceneb
Ideno(l,2,3-cd) .
pyreneb
BEHP
500
0.6
6.6
0.33
1
0.33
0.33
0.33
0.33
0.33
0.33
0.33
0.33
Michigan Act 307a
Background
Background
,. Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Noncarcinogens
Antimony
0.5
Michigan Act 307
772
                                              -6-

-------
Contaminant
Isopropeneb
Cleanup Level (mg/kg)
90
ARAR or Other Basis
Michigan Act 307
              "EPA's selected soil cleanup standards for this site are in compliance with Michigan
              Act 307 and its implementing rules in that they meet the standard for selection of a
              Type C cleanup (R 299.5717(2) and 5719(1)).
              "Contaminant does not pose a significant risk, but its current cpncentration violates an
              ARAR.
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None


14.    Were treatability studies conducted on the innovative technology or standard technology?

       OBG Laboratories, Inc. (OBG) conducted a bench-scale treatability study for Ecology &
       Environment, Inc. (E&E) involving the identification  of solidification/stabilization methods for
       decreasing the leaching characteristics of lead-bearing waste fill material from the site.  OBG
       found that the H. Brown materials can be easily solidified to produce a material having
       improved structural integrity with improved leachability and permeability.  TCLP leaching
       tests on selected mix designs yielded generally favorable results with respect to contaminant
       fixation, 'especially with the wastes having lower initial lead concentrations.
             '"                                  •                         I-
        the treatability study was obtained from the Administrative Record; however, the Feasibility
        Study, Proposed Plan, and ROD do not refer to this treatability study,
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

              Cost-effectiveness
              Time to design/construct/operate
              Proven reliability
              Preference for treatment (vs. containment)


 16.     How  are measures compared?
        The cost of the selected alternative, RAA-15, is moderate compared
        Those less costly alternatives, however, would not offer permanent
                                                -7-
 1:6 the other alternatives.  .
solutions and are therefore
                                                                                                  773

-------
         less cost effective than the selected alternative.  The lead leaching process was rejected
         because it would be more difficult and take longer to implement, primarily because the
         equipment would have to be originally designed, and pilot-scale testing would be necessary to
         determine whether full-scale treatment is possible. The selected alternative was chosen
         because it utilizes proven and easily available technologies.  The statutory preference for
         treatment as a principal element of a remedy is satisfied by the 'selected alternative
         Alternatives leaving untreated waste in place were rejected because of their low long-term
         effectiveness.                         •                                      •  .•        •
 17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting a remedy, however, two innovative
technologies were eliminated in part due to technical considerations. Vapor extraction was
eliminated partly because of the "relatively low permeability of site-soil for air " and soil
washing and was eliminated because the diverse nature of debris in the site's soil is likely to
clog the soil washing system.
774
                                              -8-

-------
                                    Kentwood Landfill

                                     Kentwood, Michigan
                                          Region 5
 GENERAL SITE INFORMATION

. 1.      What were the principal /contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Landfill leachate has contaminated surface
        soils with the  following contaminants;
        (concentrations not found in the FS):

        Soil (mg/kg)                '  '     ,  .

     .   Acetone
        2-Butanone                 .
        Ethylbenzene
        Toluene
        Xylene
        Diethylphthalate
        4-Methylphenol
        Fluoranthene
        Phenanthrene
        Bis(2-ethylhexyl)phthalate
        Butylbenzylphthalate
        Di-b-buty Iphthalate
        Arsenic
       , Barium
        Chromium
        Iron
        Nickel
        Zinc
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
12/30/82
9/8/83
11/12/90
3/29/91
             Background

PRP-lead         j
PRPs:  City of Kehtwood, County of
       Kent
FS prepared by:  Fishbeck, Thompson,
       Carr & Huber
 2.      What volume of material is to be remediated?

         The volume of material to be remediated included:

         •      2 million cubic yards of soil
 3.      What type of site is, this?                                      ,           •   ,
                                                                     i .
                                                                     i.
         Municipal Landfill.  Municipal landfill that accepted garbage, rubbish, construction, and
         demolition waste.                              ,               i
                                              -1-
                                        775

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:
5.
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
                              Access controls and site monitoring
                              Cap improvements (grading, vegetation)
                              Stabilization, fixation
                              On-site or off-site incineration
                              Excavation, off-site landfill, on-site cells
        Way an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:          Composting
        Physical/chemical treatment:   Solvent extraction, dechlorination, wet air oxidation
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness
        implementabihty, and cost) to identify alternatives that merit a more detailed evaluation '"The
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        by the NCP. Alternatives numbered with  "-LF-" correspond to those presented in the three
        criteria screening and all other RAAs  correspond to those presented in the nine criteria
        screening and the ROD.

        No innovative technologies were incorporated into remedial action alternatives.


7.       How did the cost(s) compare  to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-LF-1/
RAA-1
RAA-LF-2/
RAA-2
	 	 	 •
Innovative Technology
No action
Access restrictions/site monitoring
=*===========;========,==,
Estimated Costs
3 Criteria
$0
$220,000'
9 Criteria
$0
; $1,000,000
  776
                                             -2-

-------
Alternative
RAA-LF-3/
RAA-3
RAA-4
RAA-LF-4/
RAA-5
RAA-LF-5
•-...•
Innovative Technology
Access restrictions/site monitoring/cap
improvements/landfill gas control/
leachate collection/on-site ground water
extraction wells/discharge of leachate
and contaminated ground water to a
POTW
Access restrictions/site monitoring/cap
improvements/landfill gas control/
leachate collection/on-site and off -site
ground water extraction wells/
discharge of leachate and con-
taminated ground water to a POTW
On-site incineration with off-site ash
disposal/on-site and off-site ground
water extraction wells/discharge of
contaminated ground water to a POTW
Excavation/off-site disposal
Estimated Costs
3 Criteria
$1,300,000
l' ,
not proposed
i
$160,000,000
$60,000,000
9 Criteria
,$5,200,000
$5,700,000
$160,000,000
eliminated
8.      If a standard technology was chosen, why?
                                  1                        >             -1                         '
       The chosen alternative (RAA-4) includes extraction and treatment of ground water and capping
       of the landfill.  Furthermore, this alternative provides the most extensive ground water
       extraction plan, which will lower the water table and minimize the production of leachate from
       laterally moving ground water. Capping reduces exposure to landfill: contaminants and reduces
       infiltrations of precipitation associated with leachate generation.  It protects the  environment by
       reducing risks of surface water discharges of contaminants and reduces ground water
       contamination. The selected remedy reaches remediation;goals within the shortest amount of
       time.  This alternative minimizes short-term risk to workers as it does not require excavation.
       This alternative was preferred because it is the most cost-effective option. While one other
       alternative proposed incineration, which would treat source contaminants in a more permanent
       .manner, it would be extremely costly. The chosen alternative was considered cost-effective
       since it would  meet cleanup levels as quickly as incineration.       > .     • •
        If an innovative technology was chosen, why?

        An innovative technology was not chosen.
                                               -3-
                                                                                                 777

-------
 10.
  If an innovative technology was not chosen, why not? At what stage was the innovative
  technology eliminated?         _


  Innovative technologies could be eliminated from the remedial technology selection process at
  three stages:  during the initial screening; during the screening of the three criteria of
  effectiveness, implementability, and cost; or during the detailed evaluation.

  Innovative technologies eliminated during the initial screening include the following:

  •      Solvent extraction was  eliminated because the technology would not be. effective with
         heterogeneous wastes and is not applicable to all contaminants.
  *      Composting was eliminated because of the large volume of waste, on-site space
         constraints, the lack of data on its effectiveness in treating large volumes of waste, and
         the potential health risks associated with associated excavation.
  •      Dechlorination was eliminated because it would not be applicable to many organic and
         inorganic contaminants found on site.
  •      Wet air oxidation was eliminated because it would not be suited for large-scale solids
         handling and contacting and its effectiveness for damp solid waste has not been
         demonstrated commercially.


 Innovative technologies eliminated during the screening of the three  criteria include the
 following:

 "     None


 Innovative technologies eliminated during the detailed analysis include the following:

 •      None      ,                                               .-••.'
11.
12.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so
 which criterion? Which of the criteria supported the use of a standard technology?


 The criteria that were weighted most heavily in selecting a technology were protection of
 human health  and the environment and cost-effectiveness. Innovative technologies were not
 incorporated into RAAs.



 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?


Contaminated  surface soils were grouped with the landfill contents in setting remedial action
objectives. No chemical-specific cleanup levels were established for soil.  Soil remediation
goals correspond to a maximum cumulative carcinogenic risk  range of 10"4 to 10'6 and a
Hazard Index below 1.
  778
                                              -4-

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:        .       ,

       •      None '          • .      •        ,     .'.-'•          •    |L  • •

       Standard technologies eliminated because of cleanup goals include:,  i
                                                                    ••!-••'
       •      None                                                    l              ,
                                            •          '           •[

14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.                             i                  ,
                                                                        -

15.    What measures/criteria -were used to compare alternatives?

       The following measures were used to compare the alternatives:

               Cost-effectiveness
               Time to reach remediation goals


16.    How are measures compared?                                    "
           *                   •            "      '               ,         |    '    '
       The selected alternative was preferred because it is the most cost-effective.  The one
       alternative that included treatment, and  therefore provide a more permanent and Idng-term
       solution, was not selected because it was much more costly.  Furthermore, the chosen
       alternative will reach remediation goals hrthe same amount of time as the other alternative,
       and in  a shorter time than most other alternatives.              ,.   - J
 17.     What technical considerations-were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
                                    '           '        •  '              \          '
        Technical considerations were not primary in selecting a remedial alternative.  The nature and
        volume of the waste were primary.  The site is comprised of a landfill that has waste below
        the natural ground water table.  This waste is in direct contact with laterally moving ground
       . water. Ground water is believed to be the major source of leachate, .which is produced both
        by infiltrating precipitation and by ground water moving through the landfill.  The selected
        alternative was chosen because it addresses both of these problems by preventing the
        infiltration of precipitation through capping and lowering the water table with extraction wells.
        Both of these actions will act to reduce the production of leachate.
                                               -5-
779

-------
                                   Kohler Company Landfill
                                              OU-1

                                        Kohler, Wisconsin
                                            Region 5
                                                                                              D
   GENERAL SITE INFORMATION
   7.
  2.
 What were the principal contaminants,
 contaminant levels, and media addressed in
 this feasibility study?

 Maximum concentrations of principal ~
 contaminants were:

 Waste/Soil (mg/kg)

 4-Methylphenol        1.5
 PCBs                 4.3
 Copper               110.
 Lead                 194
 Zinc                  207
 Cadmium             5.3
                                                                   Site History
                                                                              Jt
                                                      NPL Proposed:        N/A
                                                      NPL Final:           1983
                                                      FS:                  8/91
                                                      ROD:                3/92

                                                                   Background

                                                      PRP-lead
                                                      PRPs:  Kohler Company
                                                      FS prepared by:  Geraghty & Miller,
                                                             Inc.               ,
What volume of material is to be remediated?

The volume of material to be remediated included:

»      A volume of landfill waste was not provided.  The entire landfill spans 40 acres with £
       depth ranging from a few feet to 60 feet.
                                                                                                   ft)
  3.      What type of site is this?                '

         Municipal Landfill. An active landfill surrounded by undeveloped land and a few residences.


  TECHNOLOGY SELECTION

  4,      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:

         Access restriction:     Deed restrictions, fencing
         Containment:          Capping  (concrete, asphalt, soil, single-layer, multilayer, RCRA, clay,
                              native material, synthetic membrane, inert materials), grout injection,
                              slurry wall, sheet piling, diversion runoff system
         Chemical treatment:    Stabilization/solidification, neutralization
780
                                     .1-

-------
       Thermal treatment:    Incineration (rotary kiln, fluidized bed, circulating bed)
       Disposal:             Excavation, disposal (off-site, on-site)
5.      Was an innovative technology considered in the FS? If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                         .

       Biological treatment:    In situ bioremediation, slurry bioreactor, composting
       Phys/Chem treatment:   Solid/liquid extraction, soil flushing, soil vapcjr extraction
       Thermal treatment:     In situ vitrification, thermal extraction
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that'merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.                               i
                                                                        1 -   ;   ' ;
                 Cost Estimates for RAAs That Include innovative Technologies
                            (selected remedial alternative is in bold)    j
Alternative
RAA-5
Innovative Technology
Institutional controls/solid waste cap/
leachate treatment/soil vapor ,
extraction/air emissions controls
Estimated Costs
3 Criteria
J


9 Criteria
$5,977,000

7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action ,
Institutional controls
Institutional controls/State of >
Wisconsin solid waste cap/leachate
treatment

3C
I
Estimated Costs
nteiria
I/A
N/A
N/A
' ."•.•'. - -2- -
9 Criteria
$0
$89,000
$4,673,600
- . " - " • ' . '
                                                                                                731

-------
Alternative
RAA-4
Standard Technology
Institutional controls/RCRA cap/leachate
treatment
Estimated Costs
3 Criteria
N/A . .
9 Criteria
$7,089,700
8.      If a standard technology was chosen, why?

        RAA-3 was selected because it will protect human health and the environment by reducing and
        controlling potential risks through closure and capping of the landfill. Through containment of
        the waste, it minimizes the risk posed by direct contact, inhalation, or ingestion of site-related
        contaminants.  By reducing filtration, it reduces the potential for contaminant movement from
        the waste into the ground water. The institutional controls, by minimizing site access and
        controlling land and ground water use,  add to the alternative's protectiveness.  This alternative
        complies with all ARARs and is cost effective. Implementation of RAA-3 poses no short-term
        risk to workers and  dust suppression techniques will be used,to address the potential for
     •  paniculate emissions.  The  technologies used in the chosen alternative are technically feasible,
        readily available, easily implemented, and considered reliable. The proposed solid waste cap
        will take less time to implement than the hazardous waste cap .proposed in RAA-4.
9.     If an innovative technology was chosen, why?

       An innovative technology was not selected.
JO.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      In situ vitrification-was eliminated because  it has not widely been tested and likely
               would not be effective for the depth of fill (20 to 40 feet) that exists in many areas.
               The heating process in this technology also likely would produce air emissions, which
               might require further treatment.
       •      Soil flushing was eliminated because of uncertainties associated with its effectiveness,
               the unproved  nature of the treatment, and possible regulatory complications that the
               flushing agents could cause.  Use of this  technology in situ would be impeded by the
               difficulties associated with ground water recovery at the site and the prohibition of
               injection wells in the State of Wisconsin.
       •      Soil washing was eliminated because it would require excavation as well as substantial
               pilot testing to define the proper washing and extraction agents, and would result in a
               residual stream which would require additional treatment or disposal. Finally,  other
               options are more attractive and certain.
  732
                                              -3-

-------
       •      All biological treatment (in situ bioremediation, slurry bioreactor, composting) was
              eliminated because chlorinated compounds, which exist within! the source area, have
              been proven difficult to degrade through biological means,  llie technology for
              biological degradation of chlorinated VOCs is not commercially tested and its
              effectiveness is not proved.  In  many cases, an additional substrate would be required
              for microbial development which could cause additional, contamination problems. The
              elevated level of inorganic within the fill could inhibit the growth of microbes. Other
              technologies are better suited for this site.
       •      Thermal extraction was eliminated because excavation of the fill material would be
              required prior to treatment and this alternative would not be considered viable.
       •      Ex situ solid/liquid solvent extraction was eliminated because it would not be
              applicable to the entire landfill. While potentially applicable ito VOC source areas
              after excavation, other options are better suited to these contaminants.
                      '  -       '                                        j
       Innovative technologies eliminated  during the screening of the three cjriteria include the
       following:                                   ,                    ',                .        '

       •      None

       Innovative technologies eliminated  during the detailed analysis include the following:

       •      Soil vapor extraction (SVE) was originally the recommended option in the Proposed
              Plan but it was not the selected remedy in the ROD based on information made
              available during the public  comment period and in the comments submitted.  Public
              comments point out that  the SVE system is tied directly to grpund water quality since
              its primary objective is to reduce the source of VOCs to ground water.  The goal of
              the SVE system would be to cleanup levels of VOCs in the v/aste to achieve protective
              levels of VOCs in the ground water. A determination of cleanup levels for water
              cannot take  place until ground water cleanup levels are hi place. In addition,,to meet
              the stated remedial action objectives, the SVE must be designed and implemented to
              remove VOCs  from both the vadose and saturated zones of the landfill materials,
              which could require  the landfill to be dewatered.  SVE therefore will be considered an
              integral part of the ground  water remedy for this site and it will l>e reconsidered when
              the ground water alternatives are evaluated.
                                                                       'i   .

11.     Which of, the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedial alternative ware short-term
       effectiveness, implementability, and cost.  RAA-3 takes the shortest time to implement because
       it has no substantive permit  requirements,  such as RAA-5's. RAA-3 [also poses minimal risk
       to remediation workers and the community during the implementation period.  RAA-3 is easier
       to implement technically because it requires less construction, and administratively because it
       requires less coordination within the Wisconsin Department of Natural  Resources and  EPA.
       Finally RAA-3 is the least costly alternative that affords the protection of closing and  capping
       the site.  The selected  remedy is more reliable and can be implemented more quickly, with less
       difficulty, and at less cost than the other treatment alternatives.         „
                                               -4-                      i                          783

-------
  12'     ?2?» ofe™"P g0°k Were Jefecterf?  # 'fte cfea/"^ *oa/ was based on an ARAR, what was that
         AKARf What risk level was selected to establish cleanup goals?

         No soil cleanup levels were established.                                            ,
 75.
  Was the innovative technology eliminated because of the cleanup goals?  Could the standard
  technology meet the cleanup goals?

  Innovative technologies eliminated because of cleanup goals include:

  «      None

  Standard technologies eliminated because of cleanup goals include:

  "      None
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 Treatability studies were not conducted.
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

              Cost-effectiveness
              Time to design/construct/operate
              Waste left in place/institutional control


 16.     How are measures compared?

        The chosen alternative Was selected because it will take the least time to implement  RAA-3
        will take 8 months, RAA-4 would take 12 months, and RAA-5 would take at least 12 months
        but could be delayed further because of the need to conduct treatability studies.  The chosen
        alternative is cost effective because while RAA-2 is less expensive, it does not provide long-
        term effectiveness.  Furthermore, RAA-4 and RAA-5 are more expensive than the chosen
        alternative and they do not provide a proportional increase in effectiveness.  Institutional
        controls only were not selected because they would not be as protective as capping and they
        would not meet ARARs for landfill closure.
77.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

No technical considerations were primary in selecting a remedial alternative; however, the
landfill depth (20 to 40 feet) precluded the use of in situ vitrification.
734
                                              -5-

-------
                             La Grande Sanitary Landfill

                              La Grande Township, Minnesota
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Landfill waste was not sampled.  Sediments
       surrounding the landfill were  sampled in
       order to determine if there were isolated
       areas of contamination. No specific "hot
     • spots" were identified; therefore, site
       remediation focuses  on the landfill.

       Sediments/Surrounding Landfill (rag/kg)
        Arsenic
        Manganese
12.4
525
                                    Site History
                                        !'
                       NPL Proposed:        N/A
                       NPL Final:       ;    6/87
                       FS:                  7/92
                       ROD:            |    9/92
                                        1
                                        l
                                    Background

                       EPA Fund-lead    ;
                       PRPs:  Francis C. fcosgrove, Marlin F.
                              Torguson, Valley Disposal Corp.
                       FS prepared by:  Malcolm Pimie
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      500,000 cubic yards of waste


 3.      What type of site  is this?

        Municipal Landfill. A former landfill located in a rural area.
 TECHNOLOGY SELECTION                           ,
                                                                     i
                                                                     I           -
 4,     What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible.
        technologies were:

        Access restriction:     Deed restrictions
        Containment:         Capping, slope stabilization
        Thermal treatment:    Incineration
        Disposal:             Excavation, on-site disposal, off-site disposal
                                              -1-
                                                                                          735

-------
  5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                                       '

         No innovative technologies were identified.
                    «*       *        ^

  6.      What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation. In  this case, the estimated costs were calculated during an evaluation based on
         nine criteria established by the NCP.  No innovative  technologies were incorporated into
         RAAs.                                                                 r
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
            Alternative
          RAA-1
          RAA-2
          RAA-3
         Standard Technology
No action
Long-term gas and ground water
monitoring/construct gas vent well/seal
old Shop Well
Long-term gas and ground water
monitoring/construct gas vent well/
seal old Shop Well/slope stabilization/
institutional controls
                                                                        Estimated Costs
                                                                    3 Criteria
                                                                       N/A
                                                                       N/A
                                                                       N/A
 9 Criteria

     $0

 $279,000
$361,000 to
 $501,000"
       •Cost depends on the specific version of slope stabilization that will be used.
8.      !f a standard technology was chosen, why?

       RAA-3 was selected because it provides the greatest protection to human health and the
       environment and long-term effectiveness of all of the proposed alternatives.  Long-term
       monitoring will provide a direct indication that contaminant levels remain within health-based
       ground water quality standards. Monitoring combustible gas also will act to indicate changes
       in health risks related to the landfill.  RAA-3 provides the maximum long-term effectiveness
       because it includes stabilization of the western  slope of the landfill and covering of exposed
       waste.  This technology is likely to reduce the amount of precipitation entering the landfill
736
                   -2-

-------
       waste and reduce the potential for failure of the existing final cover system.  Toxicity,
       mobility, and volume of landfill contaminants will be minimized in thp future by slope
       stabilization and the covering of exposed waste.  This action helps to prevent the leaching of
       contaminants from the landfill into the environment. The sealing of the old Shop Well
       eliminates the potential for noncarcinogenic risk posed by the well by eliminating it as a
       source of potable water.  The conversion of a combastible gas monitoring, well to a gas vent
       well will reduce the potential for gas buildup.  Institutional controls ensure that active controls
       remain effective. This alternative will be easily implemented in a short time. Services are
       readily available in the area and on-site  materials likely can be used for slope stabilization and
       cover for the exposed waste. This remedy  complies with all ARARs jand it is cost effective.


9.      If an innovative technology was chosen, why?                      j
                                                   •                     i        '
       An innovative technology was not selected.                        J                    •


10.    If an innovative technology was not chosen, why not? At what stage \vqs the innovative
       technology eliminated?                                           ;    '

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                        i
       innovative technologies eliminated during the initial  screening include the following:
                                                                        i
        •      None  .    '•                        •              •                   ,

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •   '  • None  .           .    •                     .             !'  '     ,   . . '       . ;  - '

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None   -             ' •     ..   ; •  .      .:         •     •  ;! • -       ' •  . • • •


 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to  meet one of the nine, criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        Long-term effectiveness, implementability, and cost were the criteria weighted most heavily in
        selecting a remedial alternative.   RAA-3 ensures that the low-level risks at the site will
        continue to be monitored to verify the effectiveness of the remedy's minimal construction
        comppnents over the long term.  Because it requires minimal construction and restoration
        activities, it is easily implementable. Finally, when primary balancing criteria are compared,
        the remedy is cost effective.  ,
                                                -3-
737

-------
   12.
                  w
                  What risk level was selected to establish cleanup goals?
                                                                         °n an ARAR'
          No Cleanup levels were selected.  The results of the human health risk assessment indicate that
          the total potential increased cancer risk from possible exposure of residents to ground water at
          tie site ,s about 9 in 100,000 for adults and 4 in  100,000 for children. These risks are wiSuV
          UFA s acceptable risk range and are largely attributed to arsenic in ground water   Further
          arsenic is naturally occurring throughout the site and the RI indicated that the landfill did not
          appear to be the a source of arsenic.  Total pathway Hazard Indices for the possible exposure
          of residents to ground water are 1.8 for adults and 4.2 for children. This risk is largely due to
          manganese in the ground water and is based on the levels of manganese in the old Shop Well
          Manganese is also naturally occurring and the landfill does not seem to be a source of elevated
          manganese levels.
  13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?

      .    Innovative technologies eliminated because of cleanup goals include:

          •       None

         Standard technologies eliminated because of cleanup goals include:

          •      None


  14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.


 15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Waste left in place/institutional control
 16.     How are measures compared?

        Because the site poses a low-level threat, many identified technologies that would have
        required excavation or increased construction activity were eliminated. For example
        technologies such as capping and off-site disposal were eliminated because their increased
        snort-term nsk and additional costs could not be justified.


 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        No technical considerations were primary in selecting a remedial alternative.
758
                                              -4-

-------
                               Lemberger Landfill, Inc.
                                          OU-1

                                    Franklin, Wisconsin
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
       Soil (mg/kg)

       Aldrin
       Antimony
       Arsenic
       Benzo(a)pyrene
       Beryllium
       Dieldrin
       Barium
       Chromium (+3)
       Chromium (+6)
       Copper
       Cyanide
       Lead
       Manganese
       Mercury
       Nickel
       Selenium
       Vanadium
       Zinc
0.24
0.0062
0.0085
0.092
0.006
0.2
0.118
0.104
0.104
0.0751
0.0105
0.485
0.843
0.0011
0.0328
0.00093
0.0515
0.699
                                    Site History
                       NPL Proposed:
                       NPL Final:
                       FS:
                       ROD:
                     N/A
                     LL site: 6/86
                     5/10/91
                     9/23/91
                i   •
             Background

EPA Fund-lead
PRPs:  Lemberger Landfill, Inc.,
       Lemberger Transport &
       Recycling, Inc.
FS prepared by: B&V Waste Science
       and Technology Corp.
 2.      What volume of material is to be remediated?
              '           .           :       ' •        '        -                   ,
        The volume of contaminated soil was not determined separately from the volume of wastes
        deposited in the landfill. The volume of wastes in the Lemberger Landfill, including daily
        cover, but excluding the final cap, is .estimated at 479,000 cubic yard's.  With the final cap, the
        volume of waste is estimated at 565,000 cubic yards.              [
        What type of site is this?

        Municipal Landfill. The site contains two closed landfills, the Lemberger Landfill, Inc. facility
        (sanitary landfill) and the Lemberger Transport and Recycling, Inc. facility (hazardous waste
        landfill).  The site  is located in a rural area.                      ;
                                             -1-
                                                            789

-------
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?  •

           Standard technologies considered during the identification and screening of technically feasible
           technologies we-e:

           Access restriction:      Deed restrictions, fencing
           Containment:          Capping (native soil, clay, soil/synthetic membrane, asphalt, asphaltic
                                 concrete, concrete, multilayer, chemical sealants/stabilizers), surface  ,
                                 controls (soil stabilization, revegetation, drainage controls), vertical
                                 barriers (slurry wall, grout curtain, sheet piling, vibrating beam, rock
                       '          grouting), horizontal barriers (grout injection, block displacement)
          Chemical treatment:    Stabilization
          Thermal treatment:     Rotary kiln, fluidized bed,  multiple hearth furnace, circulating bed,
                                 high temperature wall reactor, infrared
          Disposal:              Off-site RCRA disposal, on-site RCRA disposal, on-site waste piles
                                                                                                    J
  5.
 Was an innovative technology considered in the FS? If so, which technology?      (

 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:

 Biological treatment:   Bioreclamation/aerobic respiration, composting, landfarming
 Pnys/Cnem treatment:  Solvent extraction, soil washing (chemical), soil flushing, oxidation,
                       vapor extraction, soil washing (aqueous)
 Thermal treatment:     Molten salt, low-temperature thermal separation, vitrification, plasma
                       arc torch pyrolysis
  6.
What was the cost estimate for the innovative technology?

During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
formulated, costs are typically estimated as part of a three-criteria screening process
(effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
evaluation. In this case, costs were calculated during an evaluation based on nine criteria
established by the NCP.

         Cost Estimates for RAAs That Include Innovative Technologies
                     (selected remedial alternative is in bold)
            Alternative
          RAA-8
                          Innovative Technology
                  Excavation/on-site incineration (molten
                  salt)
                                                                          Estimated Costs
                                                                     3 Criteria
                                                                        N/A
9 Criteria
eliminated
790
                                       -2-

-------
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
&
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
Standard Technology
No action
Institutional controls
Clay cap/institutional controls
Multilayer cap/institutional controls
Clay cap/slurry wall/institutional
controls
Multilayer cap/slurry wall/institutional
controls
Excavatioh/on-site incineration (rotary
kiln)
Estimated Costs
3 Criteria
N/A
N/A
-.- N/A
N/A
N/A
N/A
N/A
i
9 Criteria
$0
$0
$9,195,000
$10,795,000
$9,910,000
eliminated
eliminated
If a standard technology was chosen, why?

RAA-5 minimizes the risk of on-site receptors coming into contact with contaminants and the
migration of contamination off site as a result of wind or surface water erosion. The clay cap
and slurry wall work in conjunction to minimize the amount of water entering the waste areas
and to reduce the amount of leaching.  Institutional controls such as diced restrictions and
fencing help maintain the integrity of the cap over the long run. RAA:-5 meets  all  ARARs,,
presents little short-term risk, and is easily implemented. In addition,: the slurry wall protects
the public and environment to a greater extent than capping alone beciause the wall prevents
ground water from flowing through the wastes and minimizes the migration of contaminants
away from the site.                                           ., ,;  '•-•'"'
 9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative.
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the |three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                               -3-
                                                                                      7.91

-------
            Innovative technologies eliminated during the initial screening include the following:

            •      Bioreclamation/aerobic respiration was eliminated because it would not be feasible for
                   the varied wastes found in landfills.  The technology would not be effective for
                   treatment of metals, which might inhibit the activity of the microorganisms
            "      Composting was eliminated because it has not been proved on a full-scale operation
                   for hazardous waste.
            "      Land/arming was eliminated because it would be more  suitable for industrial sludges
                   and wastewaters, not for the municipal solid wastes at the site.
            •      Solvent extraction was eliminated because it would be most effective in removing
                   organic contaminants, not municipal wastes.
            •      Plasma arc torch pyrolysis was eliminated because it would be applicable only to
                   liquid organic wastes and finely divided, fluidizable sludges.
            "      °xi
                                                                                                      )
   77.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so
 which criterion? Which of the criteria supported the use of a standard technology?

 Cost-effectiveness, protectiveness, and short-term effectiveness were weighted most heavily in
 selecting the remedial technology.  RAA-8 (molten salt destruction) and RAA-7 (rotary kiln
 incineration), were eliminated because of their relatively high cost and the short-term risks
 posed by excavating contaminated wastes. The selected remedy, RAA-5 (capping and slurry
 wall , satisfies statutory requirements for protectiveness, poses little short-term risk, and is
highly cost-effective.
732

-------
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (fig/kg)
ARAR or Other Basis
Carcinogens
Aldrin
Arsenic
Benzo(a)pyrene
Beryllium
Dieldrin
20
200
50
320,000
20
Risk"
Risk
Risk
Risk
Risk
Noncarcinogens
Antimony
Barium
Cadmium
Chromium (+3)
Chromium (+6)
Copper
Cyanide
Lead
Manganese
Mercury
Nickel
Selenium
Silver
Vanadium
Zinc
30,000
3,200,000
30,000
65,000,000
320,000
2,400,000
1,300,000
40,000
13,000,000
20,000
1,300,000
200,000
200,000
450,000
13,000,000
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
ELisk
Risk
Risk
Risk
                Tor carcinogens, an excess upper bound individual lifetime cancer risk of 10^ was
                acceptable.  For noncarcinogens, a Hazard Index less than or
equal to 1,0 was
                acceptable.
                                              -5-
                        793

-------
    13.
              hnolome~*
            tecnnology meet the cleanup goals?

            Innovative technologies eliminated because of cleanup goals include

            •      None
                                            -     .          \         •.

            Standard technologies eliminated because of cleanup goals include:

            •      None                       ,
14.
           Were treatability studies conducted on the innovative technology or standard technology?

           No treatability studies were conducted.
   .75. .    What measures/criteria were used to compare alternatives?

           The following measures were used to compare the alternatives:

           •    Cost-effectiveness
           •    Impact on nearby populations
           •    Protectiveness of human health


   16.     How are measures compared?
                                  °n nearby P°PuIations> and Protectiveness of human health were
                                                            RAA'1 ^d RAA-2 would not provide  .
          RAA 5r               ,   C°ntaminants- RAA'3  and RAA-4 would not be as protective as
          c^tmin^d   they W°U   n0t ^^ a slui^ wa»  Deduce ground water flow through the
          contammated area thereby preventing the.migration of contaminants away from the site  Site
          assessors judged that RAA-6, which would  employ a  multilayer cap as opposed to a clay cap
          would provide a greater degree of protectiveness than needed at the site and so was le s cosf

                                                                                °
                                       to° costly and potentially threatening to nearby populations
  17.     W}iat technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in the selection of the remedy?

         Technical considerations were not primary in selecting the final remedy.
794
                                               -6-

-------
                                Main Street Well Field
                                          OU-2

                                     Eikhart, Indiana
                                         Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil and Paint Layer Soil (mg/kg)

 ,   •   Trichloroethene (TCE)        88

       Excel Property Soil (mg/kg)

       Trichloroethene (TCE)        570

       Durakool Property Soil (mg/kg)

       Trichloroethene (TCE)        5
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
12/82
9/83
12/90
3/29/91
             Background

EPA Fund-lead   ;
PRPs:  Excel Industries; Durakool, Inc.
FS prepared by:  Donohue and
       Associates, Inc.
2.     What volume ~of material is to be remediated?

       The volume of material to be remediated included:

       "     22,000 cubic yards of soil
       •     2,000 cubic yards paint layer soil                        !

                                             i  •        "            i ' '
                                                                   i        ,
3.     What type of site is this?                                      '''•'•,
      '      '          '           •            '                      •!
       Fabricated Metal Products. A  waterworks well field that serves as the primary water supply
       for Eikhart, Indiana contaminated by msssufaetuiers supplying parts to the auto industry.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                              _             1 -
                                             -1-
                                         795

-------
         Soil

         Access restriction:
         Containment:

         Chemical treatment:
         Thermal treatment:

         Disposal:
         Physical treatment:

         Paint Layer Soil

         Thermal treatment:
Deed restrictions, fencing
Slurry wall, grout curtain, sheet piling, bottom sealing, RCRA cap,
non-RCRA cap, entombment, macroencapsulation
Carbon adsorption,  solidification (cement-based, pozzolanic-based,
thermoplastic-based, organic polymer-based), in situ stabilization,
sorbents, stabilization by ion  exchange resins
Incineration (fluidized bed, rotary kiln, infrared, high- temperature
fluid wall reactor, blast furnaces, centrifugal reactor
Off-site secure landfill, on-site secure landfill
In situ soil flushing (water)
Off-site RCRA incineration
.1)
         Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                                          -   :

         Biological treatment:   Aerobic treatment, anaerobic treatment, in situ biological treatment,
                               land treatment, white rot fungus
         Chemical treatment:    Solvent extraction, supercritical extraction, soil washing (surfactant),
                               dehalogenation
         Physical treatment:     In situ vacuum extraction, electroacoustical soil decontamination,
                               electrokinetic removal
         Thermal treatment:     Molten salt combustion, in situ  heating, in situ vitrification, in situ
                               steam extraction, low temperature thermal desorption, pyrolysis,
                               ground freezing, high-temperature slagging
 6.       Wliat was the cost estimate for the innovative technology?              -    '

         During the initial  screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
         formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
         implementability,  and cost) to identify alternatives that merit a more detailed evaluation. 'The
         estimated costs then are recalculated during an evaluation based on the nine criteria established
         by the NCP.                                                                     '  ,
796
                                               -2-

-------
              Cost Estimates for RAAs That Include Innovative Technologus
                         (selected remedial alternative is in bold)
         Alternative
       RAA-5
       (RAA-2)8
       KAA-6
       (RAA-3)8
        RAA-11
        (RAA-4)*
        RAA-12
        (RAA-5)a
Innovative Technology
In situ vacuum .extraction (ISVE)/
maintain current well and air stripping
system               ,    -
Low-temperature thermal desorption/in
situ vacuum extraction under buildings/
maintain current well and air stripping
system -               •	
 In situ vacuum extraction (ISVE)/new
 interceptor well system/maintain
 current production well and air
 stripping system   	..  -    '
 Low-temperature thermal desorption/in
 situ vacuum extraction under buildings/
 new interceptor well system/maintain
 current production wells and air
 stripping system
                                                                   Estimated Costs
                                                               3 Criteria
                                                                  N/A
                                                                  N/A
                                                                  N/A
                                                                   N/A'
                                                      9 Criteria
$3,820,000
$8,500,000
$3,370,000
 $8,050,000
       'RAAs presented parenthetically are for the five alternatives retained for detaied analysis. In
       addition to the technologies described for each alternative, paint layer remova, deed
       restrictions, and ground water monitoring were added to the five remaining alternatives.
7.      How did the cost(s) compare to standard technologies?
                    Cost Estimates for RAAs That Include Standard Technologies
                               (selected remedial alternative is in bold)
           Alternative
         RAA-1
         (RAA-l)a
         RAA-2
          RAA-3
          RAA-4
  Standard Technology
  No action
  Limited action: maintain production
  wells and air stripping system
   Non-RCRA cap/maintain production
   wells and air stripping system  	
   On-site rotary kiln incineration/
   maintain production wells and air
   stripping system
                                              -3-
                                                                     Estimated Costs
                                                               3 Criteria
                                                                    N/A
                                                                    N/A
                                                                    N/A
                                                                    N/A
                                                         9 Criteria
                                                            $0
                                                         eliminated
                                                         eliminated
                                                         eliminated
                                                                                            797

-------
               Alternative
              ••••""••—••—•!

             RAA-7

            •"'  i   11—

             RAA-8


            —

             RAA-9


            "       II.—

            RAA-10


           "•"•  i     •

            RAA-13
                    Standard Technology
                    	—	
                    Off-site secure landfill/maintain
                    interceptor wells and air stripping unit
                    ~~~~~~~————————_________
                    Limited action: new interceptor wells/
                    maintain production well and air
                    stripping system
                    	—	'•	
                    Non-RCRA cap/new interceptor wells/
                    maintain production well and air
                    stripping system
                   	  ....
                    On-site rotary kiln incineration/new
                    interceptor wells/maintain production
                    well and air stripping system

                    Off-site secure landfilVnew interceptor
                   wells/maintain production well and air
                   stripping unit
                                                                           Estimated Costs
3 Criteria
    ——•»•.

    N/A

    —OBV^OB.

    N/A


   —»——™«.

    N/A




    N/A


   ~^-^^—^—.

   N/A
          This RAA is one of the five alternatives retained for further screening


          Va standard technology was chosen, why?               '

          A standard technology was not chosen
 9 Criteria
—
 eliminated
 eliminated
  9.
 JO.
Van innovative technology was chosen why?
                                      not
                                                        ? At •**
        Innovative technologies eliminated during the initial screening include the following:
                                                      wo"ld
               Aerobic treatment, anaerobic treatment, in situ biological treatment and land
               treatment were eliminated because the concentration/of site metals
798
                                     -4-

-------
                                                                            •  •         \
        microbial growth, and products of microbial degradation would persist and be more
        toxic than existing contamination.
 "      White rot fungus was eliminated ^ause the concentrations of site metals would
        inhibit fungal growth. The fungus is not readily amenable to in situ applications
        because it requires oxygen and is  less mobile in soil than bacteria.  The technology has
        not been proved effective outside  the laboratory.
 •      Supefcritical extraction was eliminated because the process requires a pumpable
        media.                                                    !
 "      Electrokinetic removal was eliminated because they are not applicable for the treatment
        of volatile organic compounds (VOCs).
 •      Dehalogenation was  eliminated because they are not applicable for the treatment of
        volatile organic compounds (VOCs).
 •      Electroacoustical soil decontamination-was eliminated because the technology is still
        being evaluated and is unavailable for commercial application.
 •      High temperature slagging was eliminated because it is unavailable in the U.S. for
        treatment of hazardous waste.
 •      Molten salt combustion was eliminated because the high ash content of the
        combustible material necessitates continuous ash removal and change of the molten
        salt.  The technology is still in development and adequate performance is not
        guaranteed.
 •      In situ heating was eliminated because it is not commercially available.
 •      In situ vitrification was eliminated because the configuration of the site does not make
        this a viable option; volume is reduced 25% and the  vitrification cannot be controlled
        enough to ensure building stability; not cost effective for use iii hot spot areas.
 •      Pyrolysis was eliminated because it has limited full-scale demonstrated success;
        available units have limited processing capacity; and costs are Mgh.

 Innovative technologies eliminated during  the screening of the three criteria include the
 following:                                                                •
                                                                  I •
                                                                  I
 •      Solvent extraction was eliminated because it had not  yet been fully developed for
        hazardous waste treatment and is more effective for treating PGBs, pesticides, and
        polynuclear aromatic  compounds than VOCs.
 •      Soil washing was eliminated because it would not be applicable for soils.
 •      In situ soil flushing was eliminated because in situ vacuum extraction would be more
        applicable for treatment of VOC-contaminated soils and is monS easily implemented
   i     for the treatment for soils underneath buildings.                       ,
 •      In situ steam extraction was eliminated because in  situ vacuum extraction would be
        more cost-effective for removing VOCs.
           .                   .                •                    I;
Innovative technologies eliminated during  the detailed analysis include ^he follow,ing:

 •      Low-temperature thermal desorptwn was eliminated because it is 1) costly,  2) would
        require excavation,  3) would trigger RCRA LDRs and regulations for closure that
        would be difficult to implement on site because of the large volume of soil and the
        restricted space at the site, 4) would disrupt business  operations, 5) would require
        bracing and building support, 6) implementation would be in a confined working area
        and would be disruptive to surrounding residential areas, 7) once mobilized, would
        have to complete all soil treatment because remobilization is costly..
                                       -5-
799

-------
 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        t* meet one of the nine criteria result in the elimination of the innovative technology?  If so,
            *h criterion? Which of the criteria supported the use of a standard technology?

        Cost, long-term effectiveness, and short-term effectiveness were weighted most heavily in the
        selection of the technology.  Cost-effectiveness and implementability were important in
        eliminating low-temperature thermal desorption.
 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?
                     Contaminant       Cleanup Level (mg/kg)   ARAR or Other Basis
                 Carcinogens
                 Trichloroethene
   0.1
Risk
        For carcinogens, an excess upper bound individual lifetime cancer risk of between 10J? to 10"6
        was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
 73.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:                 '

        •      None                              , .

        Standard technologies eliminated because of cleanup goals include:

        •      None         .--..-


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.


 75.     What measures/criteria were used to compare alternatives?     -        '

        The following measures were used to compare the alternatives:

               Risk level achieved
               Total cost                                                               ,
               Preference for treatment (vs. containment)
               Time to design/construct/operate                                        .
               Impact on nearby populations
SDO'
-6-

-------
                                                                                                                1
16.    How are measures compared?                                     ]'  '

       Only alternatives that could achieve a IxlO'6 or less excess cancer risk level for either the
       current or future risk scenarios were retained for evaluation during the detailed analysis.  Of
       those alternatives, cost-effectiveness was a primary consideration in the comparison and
       elimination of alternatives.  Treatment alternatives were preferred ovei; containment to control
       the source of contamination and to achieve the desired risk levels.  Also, contaminated soils
       near the on-site buildings are not readily accessible; Therefore technologies such as low-
       temperature thermal desorption would be difficult to construct and operate.
17.
What technical considerations were factors in selecting a remedy? Were technical
considerations primary in the selection of the remedy?

The presence of buildings on the site was a primary technical consideration in selecting a
remedy.  Innovative technologies, such as low-temperature thermal desorption that require
excavation of soil or reduce soil mass during treatment, were eliminateid because of potential
damage to building structures.
                                              -7-
                                                                                               801

-------
                                Michigan Disposal Service
                                  (Cork Street Landfill)

                                     Kalamazoo,  Michigan
                                          Region 5
GENERAL SITE INFORMATION

J.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Landfill Contents (mg/kg)
2.
        Arsenic
        Barium
        Chromium
        Manganese
                     20
                     126
                     15
                     292
What volume of material is to be
remediated?
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                                                                  6/87
                                                                  8/90
                                                                  4/26/91
                                                                  9/30/91
                                                                 Background

                                                    PRP-lead
                                                    PRPs:  City of Kalamazoo, Michigan
                                                           Disposal Services
                                                    FS prepared by: Canonic
                                                           Environmental Services Corp.
       The volume of material to be remediated included:

       •      1.8 million cubic yards of soil and waste   ,         '


       What type of site is this?

       Municipal Landfill. The site is a Type III landfill operated by the Michigan Disposal Service
       (MDS).  In the past, when the site was used as a municipal landfill and contained an
       incinerator, incinerator ash was disposed of on the landfill.  The immediate area is industrial;
       the general area is  mixed industrial, commercial, and residential.
TECHNOLOGY SELECTION

4.     What standard technologies -were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Institutional controls (fencing, deed restrictions, zoning)
       Containment:         Capping (clay, multimedia), surface controls/dust controls (diversion "
                            channels, site regrading, revegetation, and dust suppressants),
                            horizontal barriers (liners, injection grouting)              '
 802
                                             -1-

-------
       Chemical, treatment:
       Physical treatment:
       Thermal treatment-
       Disposal:
Lime neutralization, solidification/stabilization;
Ambient temperature aeration, aeration, solids jprocessing/size reduction
On-site incineration, off-site incineration
Excavation, on-site disposal (backfill, RCRA landfill, storage
permanent or temporary), off-site disposal in RCRA landfill
5.     Was an innovative technology considered in the FS?  If so, which technology?
                                                                        •\
                                                                        !' •                •
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
                                                                       - 1
       Biological treatment:   Composting, nutrient enhancement, enhanced aerobic biodegradation
       Chemical treatment:    Oxidation/reduction, liquified gas solvent extraction, solvent leaching,
  • • •"       ,                  in situ soil flushing    .                    i
       Thermal treatment:     Vitrification, low-temperature aeration, pyrolysis, freeze crystallization,
                              in situ vacuum extraction/soil aeration, in situ!radio frequency heating,
                              steam flushing, thermal stripping
6.      What was the cost estimate for the innovative technology?
                                           •  '-                     =..!-.*,•
                            1                            '                I
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, the estimated costs were calculated during a!n evaluation based on
        nine criteria established by the NCP.  No innovative technologies  wei?e developed into RAAs.
                                                                        rl  '
        How did the cost(s) compare to standard technologies?             i

                  Cost Estimates for RAAs That Include Standard Technjolojjies
                             (selected remedial alternative is in bold)

Alternative
RAA-1
RAA-2



RAA-3






Innovative Technology
No action
Institutional actions (fencing, posting
signs, deed restrictions, 5-year reviews)/
ground water treatment/ management of
migration
Institutional actions (fencing, posting
signs, deed restrictions, 5-year
reviews)/grading with clean fill, 2-foot
clay cap, topsoil, vegetation/ground
water treatment/management of
migration
Estimated Costs
3 Criteria
Kf/A
N/A
I

" • "
N/A





9 Criteria
$0
eliminated



$6,119,5010





                                                -2-
                                                                     803

-------
            Alternative
          RAA-4
          RAA-5
          RAA-6
          RAA-7
         Innovative Technology
 Institutional actions (fencing, posting
 signs, deed restrictions, 5-year reviews)/
 grading and surface water diversion/
 topography development by using the
 site as a Type m landfill,  2-foot clay
 cap, topsoil, vegetation/ground water
 treatment/management of migration
 Removal (and later replacement) of
 Type HLsolid wastes/excavation/on-site
 high-temperature incineration (rotary
 kiln used as representative)/sampling of
 soil and residuals/on-site disposal of
 treated soils and residuals as backfill/
 stabilization of treated soils and
 residuals/grading/surface water
 diversion/2-foot clay cap, topsoil,
 vegetation,  ground water treatment/
 management of migration
Removal (and later replacement) of
Type HI wastes/excavation/off-site
disposal/backfilling (with old and new
Type in wastes, inert materials, or clean
fill)/grading/surface water diversion/
topsoil and vegetation (unless Type HI
operations continue)/ground water
treatment/management of migration
Institutional actions (fencing, posting
signs, deed restrictions, 5-year reviews)/
grading/surface water diversion/topo-
graphy development by using the site as
a Type IE landfill, 3-foot clay cap, 2-
foot protective soil layer, topsoil,
vegetation/ground water treatment/
management of migration
                                                                         Estimated Costs
                                                                     3 Criteria
                                                                       N/A"
                                                                       N/A
                                                                       N/A
                                                                       N/A
  9 Criteria
 $4,646,000
$519,800,000
     to
$611,600,000
 eliminated
$8,418,000
S.     If a standard technology was chosen, why?

       RAA-3 was chosen because the technology will effectively, contain the source of the
       contamination, the cap will prevent exposure by direct contact, and the cap will minimize the
       production of leachate by preventing movement of precipitation down through the wa^te. The
       cap will reduce ground water contaminant loading to the aquifer, allowing the restoration of
       the aquifer in a reasonable time frame.  This  alternative is preferred over other cap alternatives
       because the cap is less likely to fail as a result of the higher compaction level of clean fill over
       Type III waste.  Short-term risks are reduced due to the short construction time, just 1 year.
804
                                              -3-

-------
9.      If an innovative technology was chosen, why?                  •   •  :,  •
                                                       • ' •   '        '    r
       An innovative technology was not chosen.                          !
                               •''              •             •         •
                                                                        .1
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                           :

       Innovative technologies could be  eliminated from/the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening includes the following:
                                '                                 ,.'.!'      '
                                                                        i
       •      Solvent, leaching (extraction) was eliminated because this technology has not been
               tested on a full scale for removing  VOCs in'the site's soils arid the technology would
               not be  effective for heterogeneous waste. Hie  solvent waste (Stream would require
               treatment, resulting in high operational costs.                !  '
     .   •      Oxidation/reduction was eliminated because the technology would be ineffective with
               the site's heterogeneous waste and  the presence of decaying cirgaitiic materials might
               produce undesirable oxidized compounds.                   !           ,
        •      Liquified gas solvent extraction was eliminated because the process has not been tested
               on a full scale for removing  the site's chemicals; the technology would not be effective
               for heterogeneous waste;  the process generates a waste stream, which would require
               additional treatment and disposal; and the technology would be costly.
        •      Freeze crystallization was eliminated because the technology jis best suited for sludge
               treatment, which  is not needed at the site.                   ]
        »      Low-temperature aeration was eliminated because the technology would not be
               applicable for treating or removing PCBs.                   [
        •      Composting was  eliminated because the heterogeneous nature of  the waste would not
               allow oxygen to reach all parts of the waste; benzene is present at very low
               concentrations and could not support microbial activities; and composting would
               neither degrade PCBs nor reduce the metals in the soil matri?;.
        •      Nutrient enhancement was eliminated because  the heterogeneous  nature of the waste
               would not allow  oxygen  to reach all parts of the waste; benzene is present at very low
               concentrations and could not support microbial activities; and, nutrient enhancement
               would neither degrade PCBs nor reduce the metals in the soili matrix.
        "      Enhanced aerobic biodegradation  (in situ) was eliminated because the physical site
               conditions would not be  suitable for the technology, the technology would require a
               fairly homogeneous waste to be implemented effectively, and the technology would
               primarily treat organic waste.    '..-...
        •      Steam flushing was eliminated because the physical site conditions would not be
               suitable for the technology, the technology would require a, fairly homogeneous waste
               to be implemented effectively, and the technology would treat primarily organic waste.
        •      Thermal stripping was eliminated because the  physical site conditions would not be
               suitable for the technology, the technology would require a fiiirly homogeneous waste   •
               to be implemented effectively, and the technology would treat primarily organic waste.
        •      Vitrification was eliminated because the physical site conditions would not be suitable
               for the technology, the technology would require a-fairly homogeneous waste to be
               implemented effectively, and the technology would  treat primarily  organic waste.
                                               -4-
                                                                                              805

-------
         •      In situ soil flushing was eliminated because the process might affect the City of          mmw
                Kalamazoo drinking water supply wells; the heterogeneous nature of the waste would      ^•^  '\
                impede uniform and effective treatment; treatment of water prior to injection often              V;
                changes the inorganic chemical characteristics (e.g., pH, TDS, and hardness) of
                extracted ground water, which might clog the injection system or the aquifer
                formation; sediments,  air bubbles, and microbial action might clog the injection
                system; and maintenance costs are relatively high.
         "      In situ vacuum extraction/soil aeration was eliminated because soil aeration would not            .  '
                remove the low levels of semivolatiles and PCBs, or the metals detected in the
                leachate and soil matrix; and the heterogeneous nature of the waste would preclude
                uniform treatment of the waste.
         •      In situ radio frequency heating was eliminated because a pilot study  would be required              !
                to determine the applicability of this process to the  site chemicals and conditions.  In
                addition, the technique would be too costly.                                                      j
         •      Pyrolysis was eliminated because rotary kiln incineration was selected to represent all
                high-temperature technologies.                                          "A

        Innovative technologies eliminated during the screening of the three criteria include the             _    ' •
        following:

        •      None                                                                                          r
                                                                                                            .  i
        Innovative technologies eliminated during the detailed analysis include the following:
                                   '
        •      None


11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet  one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        The criteria weighted most heavily in selecting a remedy include long-term and short-term   J  *
        effectiveness.  Because this alternative uses clean fill to develop acceptable grades at the site
        instead of  Type IH waste, handling the material during remediation poses less risk.  The
        heterogeneous  nature of Type HI waste would impede adequate compaction of the fill layer,
        which could later cause the cap to settle and crack.  Furthermore, because Type HI waste, by
        definition,  poses a greater risk to the ground water than clean fill, RAA-3 would pose less of a  "
        risk if the cap did fail.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that  '
       ARAR?  What risk level was selected to establish cleanup goals?

       Cleanup  levels  are not determined.  Successful remediation was based on preventing arsenic
       from leaching into the ground water using actions which substantially reduce or eliminate the
       infiltration  of precipitation.
806
                                              -5-

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?
                                                  '                      'I
       Innovative technologies eliminated because of cleanup goals include:

       •      None                                               '     I               •"  '

       Standard technologies eliminated because of cleanup goals include:   ;

       •      None                                                     i      .

                                                                        i        '           '
14.    Were treatability studies conducted on the innovative technology or standard technology?


       No treatability studies were conducted.


15.    What measures/criteria were used to compare alternatives?          i

       The following measures were used to compare the alternatives:

       -       Risk level achieved
               Time  to design/construct/operate
               Total  cost                                            --,'.",.
               Waste left in place/institutional control                  .    |


16.    How are measures compared?
                                                                        i '     '             •
       The time required to construct the remedy was considered with regard to risk to workers
       during  construction; RAA-3 requires the shortest construction time. Risk reduction-is
       discussed in relation to the three capping alternatives, in that very little change in risk would
       be experienced due to cap permeability.  Also, RAA-4 and RAA-7 would pose  a greater risk
       to ground water than RAA-3 because Type HI waste has a greater possibility  of releasing new
       chemicals.  Risk level is also discussed in relation to RAA-5 because pf exposure during
       transportation and treatment, and that it will provide the maximum lei/el of risk reduction    >
       through incineration.  During the three-criteria screening, the FS states that:  "Alternatives
       providing effectiveness and implementability similar to that of a another alternative ...... but at
       greater cost, are eliminated." Alternative RAA-6 was eliminated partly because it would  not
       satisfy  SARA statutory preference against off-site disposal of materials.
                                                                        •   •
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
                                                                  '      'i
        Technical considerations were not primary in selecting a technology, j
                                               -6-                      !                      807

-------
                                      Motor Wheel, Inc.
                                             OU-1

                                          Lansing, MI
                                           Region 5
                                                                                                J
 GENERAL SITE INFORMATION
 7.
 2.
 What were the principal contaminants,
 contaminant levels, and media addressed in
 this feasibility study?

 Maximum concentrations of principal
 contaminants were:

 Soil/Fill Material (mg/kg):

 Dieldrin                     0.737
 4,4-DDT                     0.05
 Bis(2-ethylhexyl)phthalate     1.308
 PAHs                        0.323
 Heptachlor                   Oi059
 Zinc                         0.244
                                                                   Site History
                                                     NPL Proposed: ,
                                                     NPL Final:
                                                     FS:
                                                     ROD:
N/A
10/4/86
5/91
9/30/91
                                                                  Background

                                                     PRP-lead
                                                     PRPs:  Motor Wheel Corporation, W.R.
                                                            Grace & Co., Goodyear Tire and
                                                            Rubber Company
                                                     FS prepared by:  ENSR Consulting
                                                            and Engineering
What volume of material is to be
remediated?

The volume of material to be remediated included:

•      210,000 cubic yards of soil and debris
3.      What type of site is this?

        Industrial Landfill.  An inactive industrial waste disposal site.  Earlier quarrying activities
        resulted in a large sand and gravel pit in the site's northern portion.
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:
       Containment:
80S
                     Fencing, deed restriction
                     Capping (multimedia, soil, synthetic geomembrane, concrete, asphalt,
                     and clay), surface grading, revegetation, surface diversipn and
                     collection systems, soil stabilization, grout injection
                                             -1-

-------
        Chemical treatment:
        Thermal treatment:
        Disposal:
Fixation/stabilization
Incineration
Excavation, off-site landfill, on-site RCRA cell
        Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                            •',!'.'
                   •               '                                     ''
            1       '          ' .                  •                       'i" •    '  '
        Biological treatment:   Bioremediation                            I
        Phys/Chem treatment:  In situ soil vapor extraction, oxidation, reduction, soil flushing, solvent
                             extraction                                  .
        Thermal treatment:    In situ vitrification, low temperature thermal clesorption
        What was the cost estimate for the innovative technology?          '   .

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. 'After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability,  and cost) to identify alternatives that merit a more detailed
        evaluation, For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.  The estimated costs were recalculated in the ROD.

                 Cost Estimates for RAAs That Include Innovative Technolo;pes
                            (selected remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Same as RAA-5, .plus in situ soil vapor
extraction
Estimated Costs
9 Criteria
$21,096,400
ROD
$32,169,800
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is In bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action/ground water monitoring
Fencing/deed restrictions/ground water
monitoring
Estimated Costs
9 Criteria
$1,941,200
$2,522,600
ROD
$1,941,200
$2,522,600
                                              -2-
                                                            809

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-7A'
RAA-7B*
RAA-8"
Standard Technology
Soil or multimedia cap/surface
grading/revegetation/surface water
diversion and collection/fencing/deed
restrictions/ground water monitoring
Same as RAA-3, plus ground water
extraction wells/ground water treatment
Multimedia cap/surface grading/
revegetation/surface water diversion
and collection/hanging slurry wall/
fencing/deed restrictions/ground
water monitoring
Excavation/off-site disposal in a RCRA
landfill/cap unexcavated fill/ ground
water extraction wells/ground water
treatment
Excavation/on-site disposal in a RCRA
cell/cap unexcavated fill
Excavation/on-site incineration/cap
unexcavated fill/slurry wall/ground
water extraction/ground water
treatment/fencing/deed restrictions/
ground water monitoring
Estimated Costs
9 Criteria
$7,768,100
$17,253,700
$19,646,900
'$160,854,400
$41,313,400
$145,552,800
ROD
$9,804,100
$26,352,600
$30,720,000
$160,854,400
$41,313,400
$154,590,100
       *In addition to the excavation of all fill materials, the FS also considered the excavation of
       "hot spots" and capping of unexcavated waste with a multimedia cap.  The costs to excavate
       "hot spots" only for RAA-7A, RAA-7B,  and RAA-8 were estimated to be $32,227,300,
       $31,922,900, and $22,705,500 respectively.  The partial excavation of fill was not considered
       in the ROD.
5.     If a standard technology was chosen, why?                                  ,

       A multimedia cap (Michigan Act 64) was selected as the remedy, because 1) it would reduce
       leachate generation from infiltration through the landfill and eliminate further contamination of
       ground water, 2) reduces direct human contact risks, 3) cost effective, 4) treatment not
       practical due to type of waste (landfill).
9.      If an innovative technology was chosen, why?,

       An innovative technology was not chosen.
810
                                              -3-

-------
10.    If an innovative technology was not chosen, why not? At what stage iWs the innovative
       technology eliminated?                          -

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria .of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial  screening include the following:

       •      Low temperature volatilization was eliminated because it would not be applicable for
               all site contaminants.
       •      Solvent extraction was eliminated because it would not be applicable since all
               compounds present can be treated.
       •      Soil flushing was eliminated because it would not be applicable. It is not possible to
               effectively flush the heterogeneous subsurface of a  landfill.  Not all compounds can be
               treated using this method.               •                  L
       •      Bioremediation was eliminated because it would not be applicable. It is not possible
               to effectively injeet nutrients into the heterogenous  subsurface of a landfill.  Not all
               compounds present can be treated by this method.
       •      In situ  vitrification was eliminated because it would not be applicable. The technology
               is still in the developmental stage and has not been proved for deep applications.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None '                   '        .        •        .         •     •     '
                                                        ....           !   •  '
       Innovative technologies eliminated during the detailed analysis include the following:
                                                                        I '
       •      In situ  soil vapor extraction was eliminated because the heterogeneous nature of the
               waste would make it difficult to implement.
                                                                                 '

11.    Which of the nine criteria were weighted most heavily in selecting this technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which  criterion? Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a technology were protecitiyeness of human
       health and the environment, and overall cost-effectiveness.  Due to the site's variable terrain,
       implementability also was an important criterion.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        There are no chemical-specific ARARs provided for soil.  The selected remedy, capping,
        prevents human and animal exposure (dermal and ingestion) to contaminants.

        The results of the human  health risk assessment were within EPA acceptable levels.  For
        carcinogens an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6 was
        acceptable. For noncarcinogens a Hazard Index less than or equal to 1.0 was acceptable.

                                                                                             811

-------
 13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                                                -

        Innovative technologies eliminated because of cleanup goals include:

        «      None

        Standard technologies eliminated because of cleanup goals include:

        •      None                                                                       '


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                     •                                  *


 75.     What measures/criteria were used to compare alternatives?
                                   • ,
        The following measures were used to compare the alternatives:

               Cost-effectiveness               ,  .                                       "
               Time to design/construct/operate                                                  ,     'sjgh.
               Proven reliability                                                                     IMF
                                                !                             ','•'' '-^^^^

16.     How are measures compared?

        Although the chosen remedy might require more time to achieve compliance with ground
        water ARARs, it is proven to be reliable.  Since the risks from exposure were within EPA's             '    \
        acceptable risk range, containment was considered an adequate remedial option. .                          I
                                                                            .
                                                                                                   '
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                                ,

        The topography of the fill mass and the amount and variety of waste contained in the fill were
        factors in selecting a remedy.  Quarrying activities created a sand and gravel pit, excavated to
        a depth of 50 feet, with relatively steep side walls. The near vertical slope of the sand and
        gravel pit might present technical challenges to cap installation. In addition, the installation of
        a hanging slurry wall could be difficult due to  the site's topography and geology.                       "   !
                                     1                           '                   '•'"''!
       The only innovative technology considered in the FS, in situ soil vapor extraction, was    •                 !
       eliminated because the heterogeneous nature of the waste  in the fill mass .would make it                     '
       difficult to implement.  Materials identified in the fill matrix are soils, railroad ties, tires,
       vesicular and glassy slag, demolition debris, asphalt, plastic* and glass fragments.  Along with               :
       the solid wastes, liquid wastes were disposed of on the site.  The success of soil vapor
       extraction would depend on the degree to which distinct volumes of materials containing           lib  'v
       volatile organic compounds could be located within the waste.                                    ^»*^  /


812                                                                                                    :   ;

-------
                        Muskego Sanitary Landfill

                             Muskego, Wisconsin
                                  Region 5
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
Soil (mg/kg)

Benzene
Toluene
Ethylbenzene
Xylene
Acetone
2-Butanone
4-Methyl-2-pentanone
Isophorone
                                   13
                                   130
                                   24 '
                                   100
                                   7.1
                                   13
                                   29
                                   3.6
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            Interim ROD:
                     N/A
                     9/18/85
                     11/91
                     6/12/92
             Background

PRP-lead        J
PRPs:   Waste Management of
       Wisconsin j
FS prepared by: Warzyn Incorporated
Soil in Drum and Refuse Trench Areas mug/kg)

Phenol                      3.2
,2-Methylphenol              0.43
4-Methylphenol           . .  0.55
Benzoic acid                0.17
Naphthalene                 5.6
2-Methylnaphthalene         1.3
Phenanthrene                0.11
Pyrene                      0.082
Chrysene                    0.081
Benzo(a)pyrene              0.14
Ideno(l,2,3-cd) pyrene        0.21
Dibenzo(a,h)anthracene       0.23
Benzo(g,h,i)perylene         0.19
Butylbenzylphthalate         1.0
Diethylphthalate             0.15
Di-n-butylphthalate           0.31
Bis(2-ethylhexyl)phthalate     0.44
Arochlor 1242               0.17
Arochlor 1248               0.2
Arochlor 1260               0.062
4,4'-DDT                   0.022
4,4'-DDE                   0.033
                                      -1-
                                                                                         813

-------
        Sediments (rag/kg)

        Acetone                      0.18
        1,1-Dichloroethane            0.011
        2-Butanone                   0.053
        Toluene                      Q.19
        Phenol                       0.79
        4-Methylphenol               0.96
        Benzoic acid                  0.23
        Naphthalene                  0.21
        2-Methylnaphthalene           0.2
        Pyrene                       0.11
        Bis(2-ethylhexyl)phthalate      0.68
        Di-u-butyl-phthalate            0.17
 2.      What volume of material is to be remediated?

        "      2,500,000 cubic yards of waste material


 3.    ,  What type of site is this?

        Municipal Landfill. A sanitary landfill occupying approximately 56 acres. The area
        surrounding the site is semirural, but is zoned to permit further development in the future.
        Several homes and businesses are in the vicinity of the property, and many at one time were
        served by individual private water supply  wells.                          ,
TECHNOLOGY SELECTION                   '                 '  , .     -

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                                    '
        Containment:

        Physical treatment:



        Disposal:
Cover upgrade, capping (NR 504 cap), vertical barriers, horizontal
barriers
Gas collection and treatment (active extraction, ground flare, carbon
adsorption, catalytic combustor), leachate collection and treatment
(extraction wells, off-site treatment by a  wastewater treatment facility,
on-site treatment)
Excavation and consolidation
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
       Chemical treatment:    In situ vapor extraction
 814
                                              -2-

-------
6.      What was'the cost estimate for the innovative technology?            |
                   '                    •       : •           '               J  ' '       .           '
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs Have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  For this site, costs were calculated during an evaluation biised on nine criteria
       established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-4
Innovative Technology
Capping/landfill gas control/leachate
control/in situ vapor extraction
(ISVE)
Estimated Costs
3 Cijiteria
N/A
t
9 Criteria
$9,914,000
 7.      How did the cost(s) compare to standard technologies?              |

                  Cost Estimates for RAAs That Include Standard Techmijlopes
                             (selected remedial alternative is in bold)     i
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Institutional controls
Capping/landfill gas/leachate control
Estimated Costs
-I
3 Criteria
N/A
N/A
'N/A /
9 Criteria
$0
$17,400
$8,737,000
 8.      If a standard technology was chosen, why?     •.  .                 i                    -
                                           '                             !                     •   •'
        The remedial action chosen for the site (RAA-4) incorporates both suindard and innovative
        technologies.  The standard technology consists of the installation of a Wisconsin NR cap.
        The cap reduces the percolation of rainwater through contaminated waste material and into the
        ground water by providing an impermeable layer above the waste material. This decreased
        permeability contains contamination within the fill areas and helps prevent migration off site.
        In addition, the decreased permeability will increase the ISVE zone ojf influence and therefore
        the effectiveness of this system (which is the innovative part of the selected remedy). The cap
        also provides added protection from exposure to contaminated materials via direct contact by
        utilizing added cover material.  RAA-4 meets current state and fedenil landfill closure
        requirements which are applicable to this site.  RAA-4 reduces the toxicity, mobility, and
        volume of methane and other volatile organic compounds (VOCs) in [the subsurface through
        extracting and treating landfill gas.  In addition, RAA-4 reduces the toxicity, mobility, and
                                               -3-:
                                                                                              815

-------
         volume of leachate by extracting and treating it and by constructing a low-permeability cap
         Tru  . lected remedy will not be difficult to implement because the chosen cap is common at
         other Superfund and landfill sites.                                                                  _x


 9.      If an innovative technology was chosen, why?

         The selected remedy incorporates ISVE to treat contaminated soil specifically in  the drum and
         refuse trench areas at the site.  RAA-4  reduces the mobility and volume of VOCs in certain
         areas of the site using ISVE.  VOCs in the waste and surrounding soils will be extracted
         through wells screened in the unsarurated zone and treated, if necessary, above ground. The
         risks of construction activities for RAA-4 will be adequately managed through dust
         suppression and the use of personal protective equipment for construction workers.  ISVE is
         becoming a common cleanup technology at various Superfund sites and implementation will           '
        be technically practical. Although ISVE is a relatively new technology when specifically
        being implemented in a nonhomogeneous landfill mass, this should not impede the
        implementation since a similar technology is being applied at the Hagen Farm Superfund site
        in Wisconsin.


 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at       -.
        three stages:  during the initial screening; during the screening of the three criteria of              H»
        effectiveness, implementability, and cost; or during the detailed evaluation.                        ^iP  )

        Innovative technologies eliminated during the initial screening include the following:

        •      None

        Innovative technologies eliminated during the screening of the'three criteria include  the
        following:                                                        '                     ,

        •      None                                                                          .

        Innovative technologies eliminated during the detailed analysis include the following:

        "      None


11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment, long-term effectiveness and permanence, and
       state acceptance were weighted most heavily in selecting a  remedy for this site. The selected
       alternative provides greater protection to human  health and  the environment than the other
       alternatives by upgrading the cap and providing'ISVE extraction for certain areas of  the site.      -   JB|| \
       The selected remedy adds a final element of protectiveness  by periodically monitoring existing       Hi" )
       wells that are more likely to indicate potential ground water contamination.  RAA-4 provides

 BIB
                                             -4-

-------
       the greatest degree of long-term effectiveness and permanence because it allows the greatest
       degree of remediation and containment of the contaminants.  The selected alternative provides
       additional assurance of long-term effectiveness by monitoring nearby wells. Though the state
       concurred with the selected remedial action, it did not feel that RAAj-1, RAA-2, or RAA-3
       were protective or would attain ARARs; therefore, these alternatives were not acceptable to the
       state.    •                '   ;.           -       .       '.'"'; 'j'          ,           :


12.    What cleanup goals were selected? If the cleanup goal was based on 'an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?    ,

       Since this interim action ROD addresses source control, site-specific cleanup standards for
       soils and ground water were not considered to be necessary for the areas where containment
       provides the primary source control. A performance-based cleanup sitandard, however, which
       would account for and incorporate ground water standards, was to be established for soils in
       the portion of the site where the source area will be treated as' well ats contained (the area
       covered by the ISVE system).  A cleanup standard was to be established because of the more
       concentrated nature of the hazardous materials located in this specific area.
                                   .  • •     .    ...                *                   >  '

13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?
                                                                       I •             '
       Innovative technologies eliminated because of cleanup goals include;^

       •      None        '         •        . -.       •                  :'          .

       Standard technologies eliminated because of cleanup goals include:

       •      None                                                   j  "

      .                                      _                  •         i   '
14.    Were treatability studies conducted on the  innovative technology or standard technology?

       Treatability studies were not conducted.                           'j


75.   ,  What measures/criteria were used to compare alternatives?                              -     ' •

       The following measures were used to compare the alternatives:     |
                                                                      . i
             Cost-effectiveness              .                           J
                                                                      •'!''..',
                              1                                       *  ' *          '          •  •

16.     How are, measures compared?                               .•>'."'.
                                                                       i                             •
        The selected alternative is more costly than other alternatives because it involves both capping
        and ISVE. The incremental cost of these significant additional remedial activities, however, is
       .rather small relative to the environmental benefit obtained.  The  selected remedy,  therefore, is
        cost effective.                                                  i


         .   •   '"   '    '-•'   ;-     '     -      '     ''   "  •'•   '.-'• '   !'•''      '.   ,   ' .   '  •  817
                                              . -5- .    .          .'.'."••           .

-------
17,     What technical considerations were-factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedial action for this site.
818
                                            -6-

-------
                                     Pagel's Pit, OU-1
                          (Winnebago Reclamation Landfill)

                                 Winnebago County, Illinois
                                          Region 5
GENERAL SITE INFORMATION

1.  ,    Wfiat were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Landfill wastes were not sampled and
       analyzed.
2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:
                                    Site History
                       NPL Proposed:
                       NPL Final:
                       FS:
                       ROD:
10/84
6/86
3/91
6/28/91
                                    Background

                       PRP-lead         I
                       PRPs:  Not listed.  The site is currently
                              operated by Winnebago
                              Reclamation Services, Inc.
                       FS prepared by:  V/arzyn, Inc.
               Approximately 4.7 million cubic                    .
               yards of waste (estimated to be approximately 6 million cubic; yards,at closure)
'3.      What type of site is this?
                                                                   •   I'      •   • .,
        Municipal Landfill.  An active landfill on a 100-acre site.  Municipal refuse and sewage
        treatment plant sludge have been the primary wastes accepted at the £ite.  Illinois special
        wastes (industrial process wastes, pollution control wastes, or hazardous wastes, except as
        determined pursuant to the Illinois Environmental Protection Act) also have been disposed of
        at the facility.  The site is located in a predominantly rural unincorpoirated area.  The Acme
        Solvent Reclaiming, Inc., CERCLA site is located east of this site.
 TECHNOLOGY SELECTION
                                                                      I
 4.      What standard technologies were considered for selection In this FS?

        Standard technologies considered during the identification and screerjing of technically feasible
        technologies -were:
        Access restriction:
        Containment:

        Chemical treatment:
Institutional measures, deed restrictions, fencing
Soil cover, capping (multilayer, soil, clay, multilayer with membrane,
clay-synthetic membrane cap), vertical barriers      -
Fixation
                                              -1-
                                                                                            819

-------
        Thermal treatment:
        Disposal:
Incineration
Off-site landfill
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies were not considered during the identification and screening of
        technically feasible technologies.


 6.      What was the cost estimate for the innovative technology?

        During the initial screening process,  in which'technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.  No innovative technologies were incorporated into
     •   remedial alternatives.
7.      How did the cost(s) compare, to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
820
======
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5' and
RAA-5Ab
RAA-611 and
RAA-6A
RAA-7 and
RAA-7A
	
Standard Technology
No action
Planned closure
Clay-synthetic membrane cap
Planned closure/off-site treatment of
ground water and leachate
Planned closure/on-site carbon
adsorption treatment of ground water
Planned closure/on-site air stripping
of ground water
Planned closure/on-site photolysis-
oxidation of ground water "
===== ======
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$0
$7,500,000
$13,100,000
$10,400,000
$11,000,000
(RAA-5)
$13,400,000
(RAA-5A)
$9,800,000
(RAA-6)
$11,000,000
(RAA-6A)
$11,400,000
(RAA-7)
$14,100,000
{RAA-7A)
                                             -2-

-------
Alternative
RAA-8
Standard Technology
In situ landfill waste fixation
Estimated Costs
3 Criteria
N/A '
9 Criteria
$989,000,000
       "U.S: EPA and Illinois EPA have selected either RAA-5 or RAA-6 as the most appropriate
       remedial action for this site. The ground water treatment system will| be selected during the
       system's design stage. ,                                           ;
       'The "A" alternatives treat ground water and landfill leachate.       ,
8.     -Ifa standard technology was chosen, why?

       RAA-5 and RAA-6 were chosen because they prevent further contamination of ground water
       by capping, and extracting and treating leachate. Under these alternatives, the landfill will be
       covered with a cap compliant with Illinois municipal landfill regulations.  Capping of the
       landfill reduces the production of leachate by reducing the amount of precipitation infiltration
       to the wastes.  The spread of highly immobile inorganic contaminants would be prevented by
       reducing the amount of leachate production in the landfill.  Capping iilso minimizes residual
       risks  associated with dermal exposure.  The reliability of the landfill pap is expected to be high
       if properly constructed and maintained.  The selected alternatives provide a high degree of
       long-term effectiveness and permanence because they use treatment to reduce hazards posed by
       ground water contaminants.   In addition, material and waste handling: requirements under
       RAA-5 and RAA-6 are not as extensive as for other alternatives.  Finally, the selected
       alternatives meet all ARARs.                                    i          ,
9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?      •                                    L          '             .
      .  •                 ,    •  •     '      /•     '      '            '     j .   •  .   •
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the! three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening includje the following:

        •      None                  "   .                               '
                                                                       i .            '      •
        Innovative technologies eliminated during the screening of the three Criteria include the ,
   /    following:                                                     !
                                        '       •             •        '"'!''
        •  .  .. None          '          •'            •.-••[.                   •
                                               -3-
821

-------
         Innovative technologies eliminated during the detailed analysis include the following:

         *      None
  11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so
 which criterion?  Which of the criteria supported the use of a standard technology?

 Long-term effectiveness and permanence, and implementability were important criteria when
 selecting remedial action alternatives.  The nonhomogeneous nature of the waste in the
 municipal landfill, as well as the potential presence of large objects, likely would interfere with
 in situ treatment processes such as fixation.  As recognized by the NCP and various EPA
 documents, treating the entire contents of a municipal landfill with a high volume of
 heterogeneous waste can be impractical. The selected alternatives which incorporate capping
 would be less complicated to implement than treatment alternatives.  The State of Illinois
 would not concur on this ROD. While the state agreed in principle that the selected
 alternatives will address site contamination, the state will lack the necessary approval rights
 over landfill closure and postclosure activities because the state will not be a party to anv
 settlement that is negotiated.
 12.
 13.
           ,    °ah WSre selected? Vthe cleanuP goal was based on an ARAR, what was that
         What risk level was selected to establish cleanup goals?

Specific cleanup goals were not provided.


Was the innovative  technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•       None

Standard technologies eliminated because of cleanup goals include:

•       None
14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.
75.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:
    822
             Cost effectiveness
             Preference for treatment (vs. containment)
                                              -4-

-------
16.     How are measures compared?                 '                   t
                                                       •  "  '            I     i
       RAA-6 is the least costly alternative that provides a barrier to impede tiie migration of
       contaminated ground water.  RAA-5 is estimated to be slightly more cbstly, but might provide
       some advantages treating the water. Thus, either alternative is cost-effective for providing the
       protection required at the site.  According to the FS, containment will be the main method of
       addressing landfill wastes, which pose only relatively low, long-term treats to human health
       and the environment.  The use of treatment to address the contaminated ground water,
       however, was significant in selecting the chosen alternatives.

       The Hydrologic Evaluation of Landfill Performance (HELP) computer program was used to
       estimate the rate of infiltration into the landfill waste for the final caps and grades evaluated.


 17.     What technical considerations were factors in selecting a remedy?,  Were technical       :
        considerations primary in the selection of the remedy?
                                                                       I   ' 'i
        Technical considerations were not  primary in selecting a remedy for this site.
                                                                                                   823
                                                -5-              •       :!.•••

-------
                                    Peerless Plating Co.

                                     Muskegon, Michigan
                                          Region 5
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil (mg/kg)

        Arsenic               14
        Cadmium             11,000
        Benzene              0.073
        Chloroform            0.028
        Trichloroethylene      16.6
        Vinyl chloride         1.7
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
1988
8/90
6/1/92
9/21/92
             Background

EPA Fund-lead
PRP:   Not identified
FS prepared by: SEC Donohue
       VOC levels in soil were estimated from
       ground water data using Summer's Transport Model.
2.      Wliat volume of material is to be remediated?

        The volume of material to be remediated included:

        •     8,800 cubic yards of soil contaminated with cadmium
        «     330 cubic yards of soil contaminated with arsenic
        •     6,500 cubic yards of soil contaminated with VOCs


3.      What type of site is this?

       Electroplating. Abandoned electroplating facility.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:        \    •      • .
       Access restriction:     Deed restrictions, fencing
       Containment:          RCRA cap, non-RCRA cap
  824
                                            -1-

-------
       Chemical treatment:
       Thermal treatment:

       Disposal:
Stabilization/solidification
Rotary kiln incineration, high-temperature fluid wall reactor, infrared
thermal treatment, circulating fluidized bed combustion
On-site landfill, off-site landfill             i
5.      Was an innovative technology considered in the FS?  If so, which technology?
                                                       ""                 ii .
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Biological treatment:   Aboveground aerobic biological treatment, anaerobic biological
                              treatment, white rot fungus, in situ biological;treatment
       Chemical treatment:    Supercritical extraction, dehalogenation, solvent extraction, soil
                              washing* in situ soil flushing                                  ;
       Thermal treatment:     Molten salt combustion, in situ steam vapor extraction, in situ heating,
                              in situ vitrification, low-temperature thermal liesorption, pyrolysis
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are; estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        by the NCP.                                    .                 ;
                                                                        I"
                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)            "
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
RCRA cap/in situ steam vapor
extraction (ISVE)/fencing/deed
restrictions/ground water monitoring
Aboveground aerobic biological
treatment of VOC-contaminated soil/
RCRA cap
ISVE of VOC-contaminated soil/
excavation and aboveground on-site
stabilization of metal-contaminated
soil/placement of stabilized material
in off-site landfill
Estimated Costs
3 Criteria
$800,000
$1,200,000
$2,!700,,000
9 Criteria
$945,000
eliminated
$5,440,000
( . t
- „ . ; ' . ,....'
                                                -2r
                                                                                                 825

-------
-
Alternative
RAA-6
RAA-7
RAA-8
=====
11
Innovative Technology
Aboveground aerobic biological
treatment of VOC-contaminated soil/
excavation and stabilization of metal-
contaminated soil/placement of
stabilized material in off-site landfill
Excayation/low^temperature thermal
desorption treatment of VQC/
stabilization of metal-contaminated
soil/placement of stabilized material in
off-site landfill
ISVE/in situ stabilization/monitoring
Estimated Costs
3 Criteria
$3,200,000
. $2,900,000
$1,100,000
9 Criteria
eliminated
*
eliminated
$1,181,000
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs that Include Standard Technologies
                             (selected remedial alternative is in bold)
            Alternative
          RAA-1
          RAA-2
        Standard Technology
No action/ground water monitoring
RCRA cap/fencing/deed restrictions/
ground water monitoring
                                                                         Estimated Costs
                                                                     3 Criteria
                                                                      $41,000
                                                                     $400,000
9 Criteria
 $41,000
$718,000
8.      If a standard technology was chosen, why?

        Part of the selected remedy is a standard technology.  Solidification/stabilization with off-site
        disposal was selected because 1) it produces an end product not bioacceptable by humans or
        animals, 2) immobilizes inorganics and prevents future leaching, 3) off-site disposal will
        eliminate institutional controls and a 5 year review, 3) off site disposal will eliminate
        institutional controls and 5 year review, 3) it is the most effective and permanent alternative as
        both organic and inorganic contaminants in the soil are treated and disposed of off-site  leaving
        no on  site residuals.                                                             '      6
9.     If an innovative technology was chosen, why?

       The remedy selected includes in situ soil vapor extraction of VOC-contaminated  ,
       soil/excavation; above ground on site stabilization of metal-contaminated soil; and off-site
       landfillmg of stabilized material. This remedy was selected because: 1) it is the most effective
       and permanent alternative as both organic and inorganic contaminants in the soil are treated
       and disposed of off-site, leaving no on site residuals, 2) established technology used
 82G
                                              -3-

-------
       extensively at a number of sites to contain VOC contaminants, and 3) operational flexibility is
       high since vacuum pump speed can be modified to adjust to changes in flow rate.
                                                ,  •    •      ' •'  •     ,     li-   .              :

10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                             !

       Innovative technologies could be eliminated from the remedial technology selection process at.
       three stages:  during the initial screening; during the screening of the three: criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial  screening include the following:

       •      Molten salt combustion was eliminated  because the technology is still being developed,
               and high ash content material would require  continuous ash removal and change of the
               molten salt.
       •      Supercritical extraction was eliminated because full-scale demonstration of the
               technology is limited and it is not projected to  be feasible for soil matrices.
  ,     •      Dehalogenation was eliminated because it is not applicable foi; the nonchlorinated
            ,   organic compounds at the site.
       •      White rot fungus was eliminated because the fungus is not as readily amenable to soil
               as bacteria and this technology has been demonstrated only in the laboratory.
       •      In situ heating was eliminated because  it has not yet been demonstrated on a
               commercial  scale for hazardous waste treatment; available performance data on
               hazardous waste is limited; installation  would require extensive .above ground area not
               available at the site; and it does not treat metals.
        •      In situ vitrification was eliminated because this technology has few demonstrated full-
               scale applications and would  require, significant electricity dernands.
        •      In situ steam vapor extraction was eliminated because the unit cost is greater than soil
               vapor extraction and it offer no advantage over soil vapor extraction.
        •      Solvent extraction was eliminated because it has not yet been fully developed for
               hazardous waste treatment applications and variations in waste; composition can lead to
               problems with process controls.
        •      Soil washing was eliminated  because the complexity of waste material (i.e., both
               organic compounds and metals) would  make the formulation of suitable washing fluids
               difficult.  Also, recovery of the washing fluids for reuse is cornplex and necessary fbr
               the economic viability of the process.
        •      In situ soil flushing was eliminated because  implementing the technology in such a
               small area would be difficult, and since only water soluble contaminants would be
               removed, achieving required  treatment  standards would be difficult.
        •      Anaerobic biological treatment was eliminated because of the [extended process time
               required for implementation,  the low concentrations of biodegradable contaminant, the
               extent of treatment is undefined, cost is greater than soil vapor extraction and
               treatment time  is greater than soil vapor extractions of biodegradable contaminant.
        »      In situ biological treatment was eliminated because the existing site conditions (e.g.,
               shallow depths of contamination and the small volume of waste) limit the effectiveness
               and-implementability of in situ biological treatment processes, Provides limited
               process control in terms of nutrient addition.                !
        •  '    Pyrolysis was eliminated because it does not destroy metals, and the residual char from
             ,  the process  must be  appropriately treated for metals; not appropriate for low
                                               '-4-      '            -'     i   •       •'   ''   ••••  -827

-------
           '     concentrations of organics at the site; offers not specific advantage over other thermal
                treatment methods.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:
        ii
               Aboveground aerobic biological treatment was eliminated because pilot studies would
               be required to ensure target cleanup concentrations were obtainable and to determine -
               optimum operating conditions.
        "     Low-temperature thermal desorption of VOGs was eliminated because it provides the
               same level of protection as ISVE, but is more expensive.

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
 11.
12.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so
 which criterion?  Which of the criteria supported the use of a standard technology?

Long-term effectiveness and permanence were weighted most heavily in selecting the
technology  The chosen technology was the most effective and permanent because both
organic and  inorganic soil contaminants are treated and disposed of off site, leaving no on-site
residuals.  After remediation, the site would be returned to unrestricted use.
                         r
                     risk level was selected to establish cleanup goals?
                                                             °nan ARAR'
                                                                                      was tliat
                    Contaminant
                                Cleanup Level (rag/kg)   ARAR or Other Basis
                Carcinogens
                Arsenic
                Benzene
                Chloroform
                Trichloroethylene
                Vinyl chloride
                                                 1.7
                                                0.02
                                                 0.1
                                         0.06
                                        0.0004
                                                              Background
                                                           Michigan Act 307
                                                           Michigan Act 307
Michigan Act 307
                                                                  Michigan Act 307
               Noncarcinogens
                Cadmium
                                                0.8
                                                             Background
      The Michigan Environmental Response Act (Act 307) provides for the identification risk
      assessment, and evaluation of contaminated sites within the state. EPA determined that Act

      nft±S r X,U  f6' CE?CLA:  ^ ACt 3°7 ml6S require that remedial action be P^iv
      of human health, safety, the environment, and the State's natural resources.  To achieve this
      standard of protectiveness, the Act 307 rules require that remedial action achieve a degree of
    828
                                             -5-

-------
       cleanup under either Type A (to background levels), Type B (to risk-based levels), or Type C
       (to risk-based levels under site-specific consideration) criteria.        \.

       Because pf the site's multiple contaminants, EPA based cleanup levels; on Type A or B
       criteria, whichever values were higher. Where the cleanup standard established for a
       contaminant is lower than the method detection limit for that contaminant,, the method
       detection limit was used as the cleanup standard.

       For carcinogens, the acceptable range of cumulative excess lifetime cajncer risk is 10"4 to 10"6
       was acceptable.  For noncarcinogens, a Hazard Index less than or equial to 1.0 is acceptable.
         .        -           . '               . .    •         •               K
        '                                 '  • '                •          •  ''  •''.'"
13.    Was the innovative technology eliminated because of the cleanup goats?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:                          ,

       •      None                                                    I  .          •        ,
                                                                  •  '    I
       Standard technologies eliminated because of cleanup goals include:
  '           '                                            '               '*'
      .  •      None     .                       '                       !                     .


14.     Were treatability studies conducted on the innovative technology or standard technology?
                     '•'••••                   '                 -  i
        No treatability studies were conducted.                             '\
                                                                        i  .             '
                     '          -       .              .             '".[•••      '              •
                                                 .-'••'         •   , ..i
75.     What measures/criteria were used to compare alternatives?         |

        The following measures were used to compare the alternatives:      j              }

               Time to design/construct/operate                           !
               Proven reliability                                         i
               Preference for treatment (vs. containment)
                                            >                           r

16.     How are measures compared?
                                         •                                         '
        The chosen alternative provides a high degree of effectiveness and permanence through
        treatment and disposal of treated residue off site. Treatment was preferred to containment
        because local businesses wanted to develop the site immediately afteir remediation was
        complete.  This technology was the only alternative that would allow; the site to be returned to
        unrestricted use after remediation.  Proven reliability also was an important consideration since
        treatability studies for unproven technologies would require too much time.

        VOC levels in soil were estimated from ground water data using Surnmer's Transport Model.
                                                6-                                              829

-------
 17.     Whnttechnical considerations were factors in selecting a remedy?  Were technical
        c  ^(derations primary in the selection of the remedy?                                              ~
                                                      •            '        •   ' •                •
        Some of the technologies initially considered would be effective only in a large site area. The
        Peerless Plating site is small, precluding the use of these technologies.
830                                                                                            W   :
                                             -7-

-------
                                   Rasmussen's Dump
                                          OU-1
                                                     ^  .
                     Green Oak Township, Livingston County, Michigan
                                         Region 5                  |
GENERAL SITE INFORMATION
1.
2.
       What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       .contaminants were:

       Soil(mg/kg)

       Toluene              71.0
       Xylene               9.1
       Ethylbenzene          2.4
       Chlorobenzene        3.7
       2-Butanone           74.0
       PCBs                5.2
       Naphthalene          35.0
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
1982
1983
1/16/90
3/28/91
                                                                Background

                                                   EPA Fund-lead
                                                   PRPs:  Not listed
                                                   FS prepared by: IJIUS Corporation
                                                          (Volume I); Warzyn Engineering
                                                          (Volume II and IE)
       What volume of material is to be remediated?
                                              i

       The volume of material to be remediated included:
              3,600 cubic yards of soil from Drum Disposal Area
              1,900 cubic yards of soil/waste from Industrial Waste Area
              4,100 cubic yards of soil/waste from NE Buried Drum Area
              15,300 cubic yards of soil from the top of the Municipal Lanidfill
       What type of site is this?             .  .

       Industrial Landfill.  Former industrial and domestic waste disposal aijea. The site is adjacent to
       the Spiegelberg landfill, another Superfund site.

       The site is divided into four areas of concern:  Industrial Waste Areai; Probable Drum
       Storage/Leakage/Disposal Area; Northeast Burial Drum Area; and Top of Municipal Landfill
       Area. Remedial action alternatives (RAAs) were determined, however, on a site-wide basis.
                                            -1-
                                                                                            831

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:                                                  •

         Access restriction:     Fencing,  deed restrictions
         Containment:          Capping (soil, multimedia), slurry walls, grout curtains, steel sheet
                               piling, block displacement grouting'
         Physical treatment:     Solidification
         Thermal treatment:     On-site incineration, off-site incineration, infrared treatment
         Disposal:              Excavation, on-site landfill, off-site landfill
 5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Aerobic biodegradation, anaerobic biodegradation, in situ
                              biodegradation
        Chemical treatment:    Dechlorination
        Physical treatment:     Soil flushing, soil washing, soil aeration
        Thermal treatment:     Vitrification, vacuum vapor extraction


6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs typically are estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, the estimated costs were calculated during an evaluation based on the
        nine criteria established by the NCP.  Estimated costs were recalculated in the ROD.

        While some innovative technologies were considered as possible remediation alternatives for
        individual areas of concern, they were not incorporated into RAAs because they did not have
        site-wide applicability.
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
 832
                                  Standard Technology
                                              -2-

-------

Alternative
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
Clay cap with no further excavation/
deed restrictions
Clay cap with further excavation/deed
restrictions
Multimedia cap with no further
excavation/deed restrictions
Multimedia cap with further excavation/
deed restrictions
Estimated Costs
9 Criteria
$2,340,000
$3,780,000
$4,940,000.
$6,330,000
ROD
$2,993,290
$4,539,062
$5,146,285
$6,691, '669
8.      If a standard technology was chosen, why?

       A clay cap was selected because: 1) cost of treatment option, 2) preseno
       action levels) which increases the short term inhalation risks to workers
       alternatives involving excavation due to fugitive dust, 3) large volurre
       4) no commercial landfills accept dioxin, 5) no vendors can treat dioxin
       of dermal contact, 7) limits potential for further migration of contam nants
 e of dioxin (below
 and the community for
and variability of waste,
 waste, 6) reduces risk
    to ground water.
9.      If an innovative technology was chosen, why?

       An innovative technology was not selected.
JO.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                              '                          .               !                      • '
            '                  '           '                     '         i
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during, the initial screening; during the screening of the: three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                       i.
                                               -                 '''I'.         ' .
       Innovative technologies eliminated during the initial screening include the following:
                   '                   • "'              '                 i-'     I •-
       •      In situ  Vitrification was eliminated because the topography of the site is not
               appropriate for vitrification; the landfill is too shallow for effective electrode
     ;         emplacement;  equipment use is unproven on a large scale basis; long-term leaching of
               organic contaminants is uncertain; control of volatilized organics during the process
               may be difficult.
       •      Soil flushing was eliminated because the site's geology could impede the flushing
               process and create further ground water  contamination.
       •      Dechlorination was eliminated because testing would be required; byproducts would be1
               produced by the process; and the high cost.
       •      Aerobic biodegradation (reactor) was eliminated because of maintenance problems and
               the difficulty in controlling the process.
                                               -3-
                      833

-------
         •     Anaerobic biodegradation was eliminated because of sensitivity to non-uniform waste
                streams; long retention times and production of methane gas.
         •     In situ biodegradation was eliminated because pilot testing will be required to
                demonstrate its effectiveness; poor process controls; contaminants are widely and
                intermittently spread throughout the soil (no hot spots).
         "     Vacuum vapor extraction was eliminated because it is not effective for metals  PCBs
                dioxms and base and acid extractable organics; of the presence of high concentration'
                wastes and buned drums; and it would have to be used in conjunction with other
                technologies to remediate the entire site.

         Innovative technologies eliminated during the screening of the three criteria include the
         following:

         •      Soil aeration  was eliminated because it would not meet RCRA treatment standards for
                waste containing total halogenated organic compounds in excess of 1,000 ppma
         "      Soil washing was eliminated because pilot testing will be required to  achieve clean-up
                levels; no vendors are available to reactivate dioxin or PCB in carbon units- not in
                compliance with  RCRA treatment standards for wastes containing total halogenated
                organic compounds in concentrations greater than 1000 ppm.

        Innovative technologies eliminated during the detailed analysis include the following:

        *       None
        Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so
        which criterion? Which of the criteria supported the use of a standard technology?

        CosMmplementability and compliance with ARARs were the determining factor in selecting a
72.
13.
                  ,                             8°al Was based on an ARAR>
      ?  What risk level was selected to establish cleanup goals? -

 No soil cleanup levels were derived once containment versus treatment was chosen for a
 remedy.

 For carcinogens, an excess upper bound individual  lifetime cancer risk of between W4 to 10'6
 was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.


 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?                                         ,     """"'"

Innovative technologies eliminated because of cleanup goals include:

•      None
  834
                                              -4-

-------
       Standard technologies eliminated because of cleanup goals include:

       •      None  • .      -..'-"...•••••      "              '   •!        -     '.'•'•'

                  '-,..'                                -            ' I   ' '    • ' ;
14.    Were treatability studies conducted on the innovative technology or'standard technology?

     .'"No.            '             '•     •      •                 '  ' -   'I   '     •-•    '  '
                     '•                       '                           -'I-,1               , '
                                        •   •     '      •             '.'   ' i     ,' .           ,
75.    What measures/criteria were used to compare alternatives?          >
                    . ~          '          '     '                 -        -I "
       The following measures were used to compare the alternatives:      ['     .       '

               Cost-effectiveness                                         j
               Proven reliability
               Single vs. multistep treatment


16.    How are measures compared?                                .     i

       A risk-based, cleanup is necessary  at Rasmussen's Dump  due to the close proximity of
       residential wells and the potential future use of ground water at and near the site. The chosen
       alternative, a clay cap with no further excavation, adequately meets remediation goals and is a
       proven reliable remedy.  Although four separate  areas of concern were targeted for soil
       remediation, a site-wide remedy was preferable to a multistep treatment because  of overall
       cost-effectiveness. In addition, since ground  water contamination presented greater risk than
       contaminated  soil and waste materials, containment of contaminated soil iind waste materials
       was considered preferable to treatment. Capping will significantly reduce the mobility of
       contaminants  and subsequently reduce the rate of leachate generation.  The selected remedy is
       the most cost-effective alternative.
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?
                     •                 .                             '     i                  •
        Technical considerations were primary in selecting a remedy.  The varied geological
        formations and diverse waste streams of each of the four areas of concern were fundamental in.
        the choice of containment over treatment. In addition, several innovative technologies were
        eliminated as a result of technical difficulties associated with implementation or maintenance.
                                               -5-
                                                                                                 835

-------
                               Savanna Army Depot Activity

                                        Savanna, Illinois
                                            Region 5
  GENERAL SITE INFORMATION

  1.      What were the principal contaminants,
         contaminant levels, and media addressed in
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil (mg/kg)

         2,4,6-Trinitrotoluene (TNT)   500,000
         2,4-DinitrotoIuene (2,4-DNT) 94
         2-amino-4,6-Dinitrotoluene   300
 2.     What volume of material is to be
        remediated?
                                      Site History

                         NPL Proposed:        N/A
                         NPL Final:           N/A
                         FS:                  12/91
                         ROD:  ,              3/92

                                      Background

                         Federal Facility
                         PRPs: U.S. Army
                         FS prepared by: Weston Services, Inc.
        The volume of material to be remediated included:

        "      18,230 cubic yards of soil
 3.      What type of site is this?

        Military. An inactive ammunition washout facility and associated lagoons located in a
        sparsely populated rural area.
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                          ,                       .
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
836'
Fencing, deed restrictions
Capping (synthetic, clay, concrete, asphalt, multilayer, RCRA)
regrading, revegetation, diversion, sedimentation pond, vertical  barriers
(slurry wall, grout curtain, sheet piling), horizontal barriers (grout
injection, block displacement)
Stabilization
Incineration (rotary kiln, fluidized/circulating bed)
Excavation, disposal (on-site, off-site)
                                             -1-
)!

-------
        Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
               ,         -      •           .            .            '."•["""      ""'
        Biological treatment:   Landfarming, composting, in situ bioreclamation
        Phys/Chem treatment:  Soil washing (water, solvent), solvent extraction, critical fluid
                             extraction, in situ soil flushing               i
        Thermal treatment:     In situ vitrification, pyrolysis, molten salt     ;
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-4
RAA-5
Innovative Technology
Composting/stabilization if necessary/
on-site disposal
Solvent extraction/stabilization if
necessary/on-site disposal
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$11,645,000
$8,778,000
7.      How did the cost(s) compare to standard technologies?      .    •    \      .
      ' '  '    •             '            '       i         • '          '"!•'
                 Cost Estimates for RAAs That Include Standard Technoliogies
                            (selected remedial alternative is in bold)      !
Alternative
RAA-1
RAA-2
RAA-3
RAA-6
Standard Technology
No action
Institutional controls
Excavation of lower lagoons/transport
of excavated waste to upper lagoons/cap
On-site incineration (rotary kiln)/on-
site disposal
Estimated Costs
3 Criteria
N/;k
N/A
N/A
N/A
, i
9 Criteria
$0
$271,000
$1,875,000
$10,251,000
                                              -2-
                                                                                            837

-------
Alternative
RAA-7
Standard Technology
Off-site incineration at Chemical Waste
Management (rotary kiln)/off-site
disposal
Estimated Costs
3 Criteria
N/A
9 Criteria
$24,302,000
 8.      If a standard technology was chosen, why?

        RAA-6 was selected because it is the most protective alternative since all explosives
        contamination above the cleanup levels will be removed and thermally treated. Furthermore,
        no process byproducts or residual solvents will remain in soil and transportation off site is
        unnecessary. It complies with all ARARs and is cost effective. This alternative results in a
        significant and permanent reduction in contaminants, thereby reducing the estimated current
        and potential future risk due to exposure.  The leaching of naturally occurring metals from
        treated soil poses limited risk; however, this is not expected.  If soils  do not meet Toxicity
        Characteristic Leaching Procedure (TCLP) criteria, they will be stabilized prior to'disposal.
        Minimal or no  long-term management will be necessary following the removal of the thermal
        treatment unit from the site.  This alternative provides long-term effectiveness by permanently
        eliminating any potential contaminant toxicity, volume, and mobility from the site. It satisfies
        the statutory preference for treatment. No unacceptable short-term risk or cross-media impact
        will be caused  by the implementation of this alternative.  The main short-term risk associated
        with RAA-6 is from incinerator air emissions.  Air emissions  will be  controlled by an offgas
        treatment system.  In addition, workers will be provided with  personal protective equipment.
        This alternative will be implemented in  10 to 14 months. A number of vendors are available
        to implement on-site thermal treatment technologies. The rotary kiln  incinerator has been
        thoroughly tested and has a well-documented history of successful performance on treating
        hazardous waste, including the treatment of explosive compounds in soil. Rotary kilns can
        accept a variety of wastes with little pretreatment since the maximum soil particle size is 6
        inches.  In addition, the rotary kiln has been submitted for review and has been approved by
        the Department of Defense Explosives Safety Board (DDESB) for treatment of explosive-
        contaminated soil.
 P.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.                           ,


 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of die three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        •      An initial screening was not conducted.
833
-3-

-------
Innovative technologies eliminated during the screening of the three criteria, include the
following:

•      Soil washing was eliminated because its effectiveness on site sciil is; questionable and
       must be determined by a treatability study.  Furthermore, because most organic
       compounds adhere to soil particles and are not very soluble in water, it might be
       necessary to wash soil a number of times before the desired residual contaminant
       concentrations are attained. Also, it might not be possible to attain these
       concentrations!  In addition, with each pass through the process, more waste volume is
       generated. A significant elutriate waste stream that contains wash solution, explosives,
       and fines would be generated that must be treated and disposed.  Residual
       concentrations of wash solution in treated soil also would be a poncem.
•      Land/arming was  eliminated because large volumes of soil woiild have to be treated
       and a large area would be required.  Time required for adequate degradation  is
       unknown and the  climate might not be conducive to this treatment technology; during
       the winter months, the frozen ground might decrease  microbial activity.  Land disposal
       regulations might be prohibitive. Degradation byproducts might  be; toxic.
       Landfarming involves the direct application of RCRA-listed soiil  on the ground, which
       is not allowed under the land ban.
•      In situ soil flushing was eliminated because its effectiveness would be uncertain.  The
       variability of the soil characteristics would limit the degree of effective contact
       between solvent and soil  particles.  A large portion of the site iis  located in a flood
        plain adjacent to the Mississippi River and seasonal ground water fluctuations can
        occur, making it difficult to predict ground water flow accurately sind to control the
        soil flushing process.  At the upper lagoons, implementing a flushing
        infiltration/retrieval system would be difficult because the lagoons are located a large
        distance above the water table (45 feet), allowing the flushing solution significant
        opportunity to spread out horizontally, and making it difficult llo  retrieve.  In addition
        the bedrock below the upper lagoons is fractured and the direction of ground water
        flow in localized  areas is difficult to predict.  Again the mobilization of contaminants
        and  their uncertain destination is of primary concern.  In addition, nitroaromatic
        compounds typically exhibit low solubility in water and preferentially adhere to soil.
        Finally, since the overall length of remediation effort is difficult to predict, a protracted
        program would likely diminish the cost advantages.
 •      In situ bioreclamation was eliminated because its effectiveness is uncertain since the
        biodegradation of nitroaromatic compounds has not been implemented on a full scale.
        The variability of the soil characteristics  would limit the degree of effective contact
        between nutrients and soil .particles. Furthermore, heterogeneous sioil  make adequate
        flow control more difficult.  The lower lagoons are  located inj a floodplain in the
        presence of a high water table.  The in situ bioreclamation process might be difficult
        to control since seasonal ground water fluctuations can occur, malting it difficult to
        predict ground water flow accurately.  The upper lagoons are far above the water table,
        giving the nutrient rich solutions that would be applied an ample opportunity to spread
        out  horizontally.  Furthermore, the bedrock below is fractured [making flushing solution
        retrieval difficult. In addition, there might be an adverse environmental impact given
        the toxicity and mobility of microbial degradation products.
 •      In situ vitrification was eliminated because even though it has been developed on a
        large scale and is ready for commercial deployment, it does nothave  a significant
        commercial experience base.  It is not proved for explosives-contaminated soil.
        Because this technology  would be implemented in situ, all afflicted soil could not be
        inspected to ensure that explosive compounds "hot spots" do riot present a safety

                                                                                            839

-------
                 hazard from the potential explosions.  Since the lower lagoons are located in a
                 floodplain within 10 feet of the water table, it is expected that an intensive energy
                 requirement would have to be met so that the soil's moisture would be vaporized prior
                 to vitrification.  Otherwise, the water table could be drawn down but this would
                 require treatment of a large volume of water.  Finally, the company exclusively
                 sublicensed for the commercial deployment of this technology, Geosafe, has
                 temporarily suspended full-scale commercial applications after a fire during an
                 operational acceptance test.
         «       Pyrolysis (Advanced Electric Reactor, AER) was eliminated because it cannot be
                 readily implemented and it has had limited applications.  AER currently is not being
                 marketed by any firm and therefore is not commercially available.  The cost is
                 expected to be high because of its energy-intensive nature and anticipated technical
                 difficulties.
         •       Pyrolysis (electric pyrolyser)  was eliminated because it is in an early developmental
                 stage and has not been extensively tested for organic compound destruction.  It is no
                 longer marketed by Westinghouse, it is not commercially available, and it cannot be
                 readily implemented.  The cost is expected to be high because of its energy- intensive
                 nature and anticipated technical difficulties.
         «      Molten salt was eliminated because its effectiveness on organic compounds has not
                been determined; it is in an early development stage and additional research and
                development must be conducted before this technology can be implemented on a large
                scale for site cleanup. This technology would not be suitable for soil with high ash
                content because frequent bed recycling and replacement would be required.  Site soils
                typically contain high ash content and therefore they would not be amenable to this
                treatment.  Costs are assumed to be high because of the frequent bed recycle and
                replacement.                                                     ,

        Innovative technologies eliminated during the detailed analysis include the following:

        "       Composting was eliminated because it would not be as protective as the chosen
                alternative and because it could leave process byproducts on site.  Compost piles
                remaining on site might pose a risk. The ability of this technology to achieve cleanup
                levels is undetermined and treatability studies would be required. It would take 5 to 7
                years to implement.
        •       Solvent extraction (ex situ) was eliminated because it would not be as protective as the
                chosen alternative; it might leave residual solvent in the soil. Its ability to achieve
                cleanup goals is undetermined and treatability studies would be required.  It would
                take 1 to 3 years to implement. There is a limited risk from leaching of residual
                concentrations of explosive compounds if the solvent is  not adequately removed from
                treated soil and acts  as a cosolvent with water.  And if residual solvent is present in
                the treated soil, it might increase the mobility of residual contaminants. It might be
                difficult to obtain preacceptance approvals for treatment of concentrated waste streams
               at an off-site facility because of limited capacity.  In addition, the  facility accepting the
               concentrated waste stream must be in compliance with CERCLA Off-site Disposal
               Policy.                                                                 F
        "      Critical fluid extraction was considered a solvent extraction technique and was
               eliminated for the same reasons as solvent extraction.
'*>
840
                                              -5-

-------
77.
        Which of the nine criteria were weighted most heavily in selecting the technology?.  Did failure
        to meet one of the nine criteria result in the elimination of the innovMve technology?  If so,
        which criterion?  Which of the, criteria supported the use of a standard technology?
                                                                          ~           •
        The criteria weighted most heavily in selecting a remedial  alternativejwere long-term
        effectiveness and permanence, and implementability,  RAA-6 will desjtroy all of the TNT to
        health-based cleanup levels and there will be no process byproducts of residual solvents in the
        soil.  RAA-6 does not require the transport of waste'mateijals.  RAA-6 am be implemented in
        a short timeframe.  Rotary kiln incineration is the only method that has been approved by the
        Department of Defense Explosives Safety Board (DDESB) for treatment of explosives-
        contaminated soil and a number of vendors are available and permits yvill not be required.
                  •                                                     t               .         ,
        Composting and solvent extraction were eliminated because their effectiveness was
        undetermined, they  might leave residual contaminants, by-products,  or solvents on site, and
        they would not be as implementable as the chosen alternative.       '
72.'
       What cleanup' goals were selected? If the cleanup goal was based on[an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?  '   \
Contaminant
Cleanup Level (rag/kg)
ARAR j or Other Basis
Carcinogens
TNT
2,4-DNT
2-A-4.6-DNT
RDX
21.1
9.3
1,191
5.75
Risk3
Risk
Risk
Riisk
Noncarcinogens , ,->..,
TNB
l,3-DNBb
NB
2,6-DNTb
HMXb
Tetrylb
3.7 ,
. 7.4
37.2
4.2
3,722
112
, Risk
Risk
, Risk
Risk ,
! Risk
Risk
             Cleanup levels are the levels to which contaminated soils must be excavated to protect
             human health at a target carcinogenic risk level of 10'6 and a hazard quotient of 1.
             The only exception is the cleanup level for 2,4-DNT, which is [protective of human
             health at a target carcinogenicity risk level of 10'5.
              Contaminants only found in ground water; however, these contaminants might be
             encountered in soils during the remedial activity.
                                             -6-
                                                                                          841

-------
  13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
         technology meet the cleanup goals?                                                           TOF   \
                                                                                    .   '       '  •   .        • j'
         Innovative technologies eliminate'd because of cleanup goals include:                            ,

         •       None

         Standard technologies eliminated because of cleanup goals include:    '

         *      None


 14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.
                                                                               • j          '

 15.     What measures/criteria were used to compare alternatives? •                                        '

         The following measures were used to compare the alternatives:

              Percentage risk reduction
              Cost-effectiveness
              Time to design/construct/operate
              Proven reliability                                                                 -


 16.     How are measures compared?

        The chosen alternative  was preferred because it would permanently eliminate site
        contaminants, it can be implemented within  about 1 year, and it utilizes a proven and reliable
        technology. RAA-4 and RAA-5 were not selected because there was uncertainty concerning
        their effectiveness, they might leave residual byproducts or solvents on site, they would take
     •   much longer than the chosen alternative to implement, and they would require treatability
        2Stm|'A ?!? Chf^ alternative is cost effective since it is more protective and less expensive
        than RAA-4 and RAA-7; though it is more expensive than others, it provides more human
        protectiveness than RAA-1, RAA-2, RAA-3, and RAA-5.


17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary  in the selection of the remedy?

        Technical considerations were not primary in selecting a remedial alternative. Some
        innovative technologies, however, were eliminated for technical considerations, such as
        location of the lower lagoons in a floodplain, the seasonal variation in water levels the
        fractured bedrock underlying  the upper lagoons, and the heterogeneous soil characteristics
842
                                              -7-

-------
                                  South Andover Site
                                          OU-2

                                    Andover, Minnesota
                                         Region 5
GENERAL SITE INFORMATION

/.      What were the principal contaminants,:
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
 2.
       Soil (mg/kg)

       Lead
       Antimony
       PAHs
       PCBs   ,
                     1,980
                     76
                    ,30
                     15
What volume of material is to be
remediated?
                                                        Site IHistory
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                     N/A
                     N/A
                     10/2/91
                     12/24/91
             Background ,
                 I /

EPA Fund-lead    I
PRPs:  Not listed  | •    •   '
FS prepared by: Dpnohue and
       Associates, Inc.
        The volume of material to be remediated included:

        •      11,400 cubic yards of soil
 3.     What type of site is this?

        Recycling. An auto salvaging operation.


 TECHNOLOGY SELECTION

 4.,'   What standard technologies were considered for selection in this

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:                                            |

         Access restriction:     Deed restrictions, fencing
         Containment:          Slurry wall, vibrating beam, RCRA cap, non-RCRA cap
         Chemical treatment:    Stabilization/solidification
         Thermal treatment:   '  Incineration (infrared, circulating fluidized bpd, and rotary kiln)
         Disposal:             Excavation, off-site disposal
                                              -1-
                                                                                             843

-------
      5.
     6.
     Was an innovative technology considered in the FS? Ifso, which technology?

    SST !ech°0!°gies ""leered during the identification
             feasible technologies were:
                                       and screening of technically
                                  —

   What was the cost estimate for the innovative technology
   formulated, costs
   implementability, and
   estimated costs Ln
   the NCP:
   ARARs;

                                                                                 s are identified
                                                                   costs^  **« the RAAs have been
                                                               SCreenin8 process W&ctivoess,
                                                                  & m°r6 detailed evaluation-  ^
                                                          f On ^^ °n nine criteria establish^ by
                                                            Ort"temi effectiveness= te™P«ance wij
            mobility, toxicity or volume    niem,n,   T,   environment; redu^ion in contaminant
            community accepted' lmplementablhty' cost> state/support agency acceptance; and


                    Cost Estimates for RAAs That Include Innovative Technologies
                               (selected remedial alternative is in bold)
844
              Alternative
             —*——«^_

            RAA-2


           	

            RAA-3




           -••ii .^•M

           RAA-4
         Innovative Technology

 Excavate Area la soil/ex situ aerobic
 biodegradation of Area 1 soil/cap Areas
j, 3, 4 and 7b/monitor ground water

 Excavate Area 1 soil/ex situ aerobic
 biodegradation/excavate and stabilize
 Areas 2, 3, 4 and 7 soils/monitor
 ground water
		
Excavate Area 1 soil/ex situ aerobic
biodegradation of Area 1, 5, and 6
soil/excavate Areas 2, 3, 4, and 7
soil/off-site disposal of Areas 234
and 7 soils                     '  '
* Area ] contains only PAHs

antfony.' * *' ** " ""^ *
                                                                         Estimated Costs
                                                             N/A
                                                            3 Criteria     9 Criteria

                                                              N/A        $2,500,000
                                                                         $4,000,000
                                                                                  $2,470,000
                                             °f -ntaminants including PCBs.PAHs, leaded
                                              -2-

-------
7.     How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action
j
Estimated Costs
3 Criteria
N^A , .
9 Criteria
$0
8.     If a standard technology was chosen, why?
                '  '                      '
       A standard technology was not chosen.
                               '
9.      If an innovative technology was chosen, why?
                                                                         I •         .         : '. ,.
       The remedy selected included aerobic biodegradation of one area and excavation and off-site
       disposal for all other areas. Biodegradation was selected for areas with only PAH
       contamination, off-site disposal areas were contaminated with lead.  Biodegradation was
       selected because: 1) demonstrated as effective for a 10 fold reduction iin PAH concentrations
       when the initial soil concentrations were greater than 100 ppm and theoretically feasible at low
       concentrations found at the site, 2) complies with OSWER directive 9380.0-17 that encourages
       the use of innovative technologies, 3) used in numerous applications 'alt a wide variety of sites,
       4) preference for treatment.                                 .
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                            ,

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.                   .

       Innovative technologies eliminated during the initial screening include the following:

       •     Anaerobic biodegradation was eliminated because its effectiveness for low
              concentrations of refractory organics (PCBs and PAHs) as substrate is not
              demonstrated.
       •     White rot fungus was eliminated because concentrations of melals may be inhibitory to
             ; fungus, fungus is less mobile than bacteria thus requiring more intensive mixing, and
              no demonstrations have been performed other than in the laboratory.
       •     Supercritical extraction was eliminated because it would not be effective for all site
              contaminants or practical use for such large volumes of waste.
       •     In situ soil flushing was eliminated because  site contaminants are not mobile in
             , soil/water matrix.            •.   '   • .
       •     In situ heating was eliminated because it is not commercially available and it would
              not be effective  for semivolatile organics or metals.
       •     In situ vacuum extraction was eliminated because it would be ineffective for metals.
                                              -3-
845

-------
       •      In situ steam extraction was eliminated because it would be ineffective for semivolatile
              organics and metals.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                       '

       •      On-site vitrification was eliminated because the technology requires too much
              electricity and is not readily available.
       »      In situ vitrification was eliminated for the same reasons as on-site vitrification.
       •      Soil washing was eliminated because formulation of washing fluids to limit toxicity of.
              residual materials may be difficult and require constant adjustment due to
              heterogeneity of wastes and it requires a separate treatment system to treat the more
              concentrated waste stream.
       •      Solvent extraction was eliminated because there would be a lack of process control due
              to variations in the waste  composition and separate treatment systems would be
              required to treat the more concentrated waste stream.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Low temperature thermal desorption was eliminated because it has not been
              demonstrated on a full-scale basis.
       •      In situ aerobic biodegradation was eliminated because of process control limitations,
              and the small volumes of contamination in the vadose zone doesn't lend itself well to
              in situ methods.                   .    _    '                   ,
       Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in the selection of an innovative technology were the
       protection of human health and the environment, and long-term effectiveness and permanence.
       Three alternatives, RAA-2, RAA-3, and RAA-4, offered comparable protection but  only RAA-
       4 proposed a permanent solution does not require long-term maintenance.
J
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
 846
Contaminant
Cleanup Level (mg/kg)
ARAR ot Other Basis
Carcinogens
PAHs
PCBs
4
2 '
Risk3
Risk8
Noncarcinogens
Lead
Antimony
500
25
Blood levels'1
Risk"
                                              -4-

-------
                "Cleanup levels were based on an excess upper bound individual lifetime cancer risk of
                between 2xlO'5 to 3xlO'5                                   |
                bCleanup levels were based on a 5 percent chance of exceeding blood lead levels of 10
                ug/dL.              ,                  .                    I                        ,
                cCleanup levels were based on reducing noncarcinogenic risk to a Hazard Index equal
                to or less than 1.0.                                  -•''!•
 13.
14.
15.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:               '

 •      None
                                .-              '         .        •
 Standard technologies eliminated because of cleanup goals include:   !
                                                        •'
 •      None          '                         -•         -,!,•.

                                                                  •i

 Were treatability studies conducted on the innovative technology or standard technology?
                                                                 '• i                  -
 No treatability studies were conducted.


 What measures/criteria were used to compare alternatives?          j

 The following measures were used to compare the alternatives:       !
                 - •                     >             -            i      ^
      Preference for treatment (vs. containment)                     !
      Waste left in place/institutional control                        !
      Cost/unit risk                               .
      Capital cost versus operating cost                             I   .
16.     How are measures compared?

        The chosen alternative was preferred because it emphasizes treatment over containment and
        leaves no on-site residuals. The-chosen alternative treats Area 1 soil and disposes of soil from
        Areas 2, 3, 4, and .7.  Other alternatives that treat Area 1 soil would ha.ye  contained soil in
        Areas 2, 3, 4, and 7, therefore requiring long-term maintenance of residual contaminants on
        site.  Risk versus cost were compared under each alternative.  Higher risk levels were selected
        based on cost and ability to detect clean-up level.  Operating costs were considered in decision
        to permanently treat and dispose of the contaminated soil.
17.
What technical considerations were factors in selecting a remedy? We[re technical
considerations primary in the selection of the remedy?
   '              '                             •                   - > '
The diversity of site contaminants (both semivolatile organics and metajls) was a primary factor
in eliminating innovative technologies such as soil washing and solvent extraction.
                                              -5-
                                                                                              847

-------
                                     Spickler Landfill
                                          OU-1

                                     Spencer, Wisconsin
                                         Region 5
GENERAL SITE INFORMATION

7.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Waste (mg/kg)

       Leachate sampling identified compounds
       such as asbestos, ethylbenzene, xylenes, and
       benzoic acid.

       Brine Pit Sludge (ppm)

       Mercury              30
             Site History

NPL Proposed:    ,    N/A
NPL Final:           7/87
FS:                  11/91
ROD:                5/92

             Background

PRP-lead
PRPs:   BASF Corp., Weyerhaeuser Co.
FS prepared by: Warzyn, Inc.
       Leachate sampling also identified contaminants such as calcium, magnesium, benzene,
       ethylbenzene, toluene, xylene, chlorinated ethenes, ketones, phenols, chlorinated aromatics,
       polyaromatic hydrocarbons, and phthalates.                .
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      134,000 cubic yards of landfill refuse
       •      2,600 cubic yards of brine pit sludge          ;


3.     What type of site is this?

       Industrial Landfill.  An  inactive municipal landfill and a mercury brine pit located in a
       sparsely populated rural area.
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                              ,       ,
   848
                                            -i-

-------
      Landfill Soil/Waste
       Access restriction:
       Containment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Deed restrictions, zoning restrictions          ]'-.'••
Capping (clay, root zone material, topsoil, synthetic membrane, NR
504, solid waste cap, NR 660 hazardous waste cap), horizontal barriers
(slurry layer, grout layer), vertical barriers (sluiry curtain, grout
curtain, sheet piles, hydraulic barrier)   ;
Stabilization/solidification                    ,
Incineration (rotary kiln, infrared)        ,
Excavation, disposal  (on-site, off-site, RCRA landfill, solid waste
landfill)                                   . (
       Brine Pit sludge

       Access restriction:
       Containment:
       Physical treatment:
       Disposal:
 Deed restrictions, zoning restrictions    •  '    i.
 Capping           -   .                      ;
 Stabilization/solidification
 Excavation, disposal (on-site, off-site, RCRA landfill, solid waste
 landfill)
5.      Was an innovative technology considered in the FS?  If so, which technology?
                                                                        ' i                 "
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        LandfillSoil/Waste
                                                                         1

        Biological treatment:   Composting, in situ biodegradation           .
        Phys/Chem treatment:  Oxidation, reduction, solvent extraction, soil Cashing
        Thermal treatment:     Vitrification, thermal volatilization           '

        Brine Pit Sludge                                                 i

        Phys/Chem treatment:  Solvent extraction, soil washing             j
                                                                         'i •

 6.      What was the cost estimate for the innovative  technology?

        During the initial screening process, in which  technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria scieeniing process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health, and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.
           '•.••'     '    '                     '               .!''•-•
        No innovative technologies were incorporated into remedial alternatives.
                                                -2-
                                                                   849

-------
   7.
How did the cost(s) compare to standard technologies?
                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
            Alternative
            ••"     i
           RAA-1
           RAA-2
          RAA-3
          RAA-4
          RAA-5
                         Standard Technology
                 No action
 Fencing/deed restrictions/NR 660 cap
 over landfill and brine pit/landfill gas
 control/leachate collection and
 tteatment/ground water monitoring

 Fencing/deed restrictions/NR 504 cap
 over landfill/NR 660 cap over brine
 pit/landfill gas control/leachate
 collection and treatment/ground water
 monitoring

 Fencing/deed restrictions, NR 504 cap
 over landfill/solidification and
 stabilization of brine pit and NR 660
 cap/landfill gas control/leachate
 collection and treatment/ground
 water monitoring
                                  ,.
 Fencing/deed restrictions, NR 504 cap
 over landfill/solidification and
 stabilization of brine pit and NR 660
 cap/landfill gas control/leachate
 collection and treatment/ground water
pump and treat
S.     If a standard technology was chosen, why?
                                                                       Estimated Costs
                                          3 Criteria
                                                                     N/A
9 Criteria

    $0

$5,220,000
                                                                       $4,590,000
                                                                     N/A
                                                                       $4,860,000
                                                                    N/A
                                                                      $6,410,000
       S   •  rl   •    /     aUSe " Provides Protection against direct contact with waste and
       reduces mfiltrauon of precipitation and leachate production and migration to ground wateT A*

       S£S£liSSSB    *" T1^ ^ Ph ^^ the wite disP°sed of in the Pitt


                                        -

                                                              is
                                                                effect
                                                                                -ter
850
                                           -3-

-------
        The selected remedy changed after the publication of the Feasibility Study and Proposed Plan.
        Originally, RAA-5 was the preferred alternative for the entire site. More recently, EPA
        determined that an operable unit approach is more appropriate for the iSite because it allows a
        more focused, logical approach, whereby the landfill, which is the source of ground water
        contamination, is remediated first. The results of this action are needed to make an informed
        decision on a final remedy.             - '    .                       I
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.
 Ifan innovative technology was notchosen, why not?'At what stage wasthe innovative
 technology eliminated?                                   '         i
                                                               '   |-          .     -'-
 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages:  during the initial screening; during the screening of the tliree criteria of
 effectiveness, implementability, and cost; or during the detailed evaluation.
                                             • ~     '.      •    •    i        •
 Innovative technologies eliminated during the initial screening include ithe following:

 Landfill Soil/Waste                                               I

 •      Composting was eliminated because it would not treat the wide variety of contaminants
        found at the site.                                           i
 •      In situ biodegradation was eliminated because it would not trealt the wide variety of
        contaminants found at the site.                                               •
 »      Solvent extraction was eliminated because it would not treat the; wide variety of
        contaminants found at the site.                              !
 «      Soil,washing was eliminated because it would not treat the widii variety of
        contaminants found at the site.                              \
 •      Oxidation was eliminated because it is not applicable to the trejitment of refuse.
 •      Reduction was eliminated because it is not applicable to the treatment of refuse.
 • ,   '  Thermal volatilization was eliminated because it is not applicable to the .treatment of
        refuse.                              ,
 •      Vitrification was  eliminated because it is not well suited for large quantities of refuse.
        Air emissions control equipment used in  the process are generally mot capable of
        handling the fluctuating emissions concentrations resulting from' vitrification  of
        heterogeneous refuse.  The lack of a sufficient water supply on site for use in offgas
        scrubbers, and the ultimate treatment and disposal of scrubber liquids, also sufficiently
        reduce the viability of this technology. Finally, GEOSAFE, soli3 marketer of the
        vitrification process, suspended commercial use of their process pending an
        investigation of a fire that occurred during a site remediation using vitrification.
        '                      '                        *           •!
Brine Pit Sludge

•       Solvent extraction for brine pit sludge was eliminated because, though it would remove
        mercury from the excavated brine pit material, the resulting treated waste still would
        have to be disposed of.                                      i             ..
                                             -4-
                                                                                      851

-------
       •      Soil washing for brine pit sludge was eliminated because, though it would remove
               mercury from the excavated brine pit material, the resulting treated waste still would
               have to be disposed of.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis include the following:

       »      None
77.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedial alternative were long-term
       effectiveness and permanence, and the reduction of contaminant mobility.  RAA-4 was more
       permanent because it permanently eliminates contaminant mobility in the mercury brine pit
       with stabilization/solidification and an NR 660 cap.
72.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?,

       Cleanup level were not established for soil/waste or sludge.
75.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       H      None                                                                        ,

       Standard technologies eliminated because of cleanup goals include:

       "      None


14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.
  832
                                              -5-

-------
15.     What measures/criteria were used to compare alternatives?          i

        The following measures were used to compare the alternatives:       i

             Risk reduction                                            ,,!.'.
             Preference for treatment (vs. containment)                     ';      ~
                                         -     '        •   -        .  .     i     . •
                                         •"•         '      •              ' 'i
16.     How are measures compared?

        The selected remedy was preferred because it provides the greatest reduction in risk through
        both treatment and containment of contaminated sources.  Stabilization/ solidification in
        combination with an NR 660 cap will ensure that  leachate in the pit will not enter the ground
        water and it will significantly reduce the production of leachate in the future.  Containment
        alone would not have accomplished this.                            \    '
17.    What technical considerations were factors in selecting a remedy?  Wdre technical
       considerations primary in the selection of the, remedy?               !

       Technical considerations were not primary in selecting a remedial alternative.
                                                                                            853

-------
                                 Stoughton City Landfill

                                    Stoughton, Wisconsin
                                          Region 5
GENERAL SITE INFORMATION
7.
2.
Wluit were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil/Sediment (mg/kg)

Only a limited waste sampling was
conducted.

Chromium                  40
Bis(2-ethylhexyl)phthalate     600
Benzoic Acid                2.8
Cadmium                   27
Lead                       460        '
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
N/A
6/86
6/20/91
9/30/91
                                                                 Background

                                                    EPA Fund-lead
                                                    PRPs:  Unirqyal Plastics, Inc.,
                                                           City of Stoughton
                                                    FS .prepared by:  ENSR Consulting
                                                           and Engineering
What volume of material is to be remediated?

The volume of material to be remediated included:

•      218,000 cubic yards of waste
3.      What type of site is this?
                                 /

       Municipal Landfill.  The site contains a 15-acre sanitary landfill, which was officially closed in
       1982.  It is in an urban area bordered by undeveloped land, wetlands, and a residential area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:
       Containment:
854
                     Deed restrictions, fencing                                  .
                     Cap repair and upgrade, single layer cap (clay, sprayed asphalt, paved
                     asphalt, corierete), multilayer cap (clay cap, synthetic geomembrane,
                     clay geomembrane), horizontal barriers (grout injection, liners), surface
                                             -1-

-------
        Thermal treatment:
        Disposal:
control (grading, soil stabilization, revegetationi diversion and
collection systems)                           [
Incineration                                 |
On-site RCRA landfill, off-site RCRA landfill |
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
                                   •     •     - •  '             •         '    V '          :
        Biological treatment:   Bioremediation                                     '
        Chemical treatment:    Solvent extraction, soil flushing, chemical oxidation, chemical
                              reduction
        Thermal treatment:     Low-temperature volatilization,  vitrification, soil vapor extraction
6.      What was the cost estimate for the innovative technology?            !
                                     • •'••,'•                        y •  •  ,           '-     .
        During the initial screening process, in which technically feasible technologies are identified \
        (prior to the formulation of RAAs), the FS does not quantify costs. After f:he RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that rrterit a more detailed
        evaluation.  For this site, the estimated costs were calculated during an'evaluation based on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness;  compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency acceptance; and community acceptance.                      !

                 Cost Estimates for RAAs That Include  Innovative Technologies
                            (selected remedial alternative is in bold)
7.
Alternative
RAA-8
Innovative Technology
Solvent extraction
Estimated Costs
3 Criteria
N/A
How did the cost(s) compare to standard technologies?
Cost Estimates for RAAs That Include Standard Technol
(selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action/monitoring
Cap repair and upgrade/fencing/ground
water use/deed restrictions
9 Criteria
eliminated
ogitss
Estimated Costs
3 Criteria
N/J
Nh
\
^
9 Criteria
$2,074,000
$4,409,000
-
2 835

-------
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
Standard Technology
Subtitle D multilayer clay cap/fencing/
deed restrictions/monitoring
Subtitle D multilayer clay cap/ground
water interceptor and barrier trenches/
optional consolidation of waste/fencing/
deed restrictions/monitoring.
Subtitle D multilayer clay cap/ground
water collection and treatment/fencing/
deed restrictions/monitoring
Subtitle D multilayer clay cap/physical
barrier/optional consolidation of waste/
ground water collection and treatment/
fencing/deed restrictions/monitoring
Subtitle D multilayer cap/consolidation
of waste/optional ground water collec-
tion and treatment/fencing/deed
restrictions/monitoring
Estimated Costs
3 Criteria
, N/A
N/A
N/A
N/A -
N/A
9 Criteria
$5,237,000
$12,349,000
to
$13,8 13,000
$6,228,000
$11,031,000
to
$12,445,000
$7,546,000
to
$8,524,000
 8.      If a standard technology was chosen,, why?

        RAA-7 was chosen because it is protective of public health and the environment and is cost-
        effective. This alternative is protective through institutional controls and through excavating
        waste currently exposed to ground water and disposing of it with other landfill wastes.  A
        Subtitle D multilayer cap reduces site risks by eliminating the potential for direct exposure and
        by reducing the infiltration of precipitation. The  mobility of site contaminants to ground water
        is reduced because the generation of leachate is reduced. Source control treatments in
        combination with the ground water treatment proposed by this alternative will reduce
        contaminant levels in the  aquifer to the State's standards.  This alternative also was preferred
        because it proposes the most effective long-term treatment, since waste in contact with ground
        water will be excavated and consolidated under the cap.  Implementation of this alternative
        will be difficult, but technically  feasible. This alternative, unlike others,  minimizes short-term
        risk and does not threaten nearby wetlands. Of the two alternatives that offer equal protection,
        RAA-7 is less costly.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
856
-3-

-------
 10.    If an innovative technology was not chosen, 'why not? At what stage wtas the innovative
        technology eliminated?                                           '                    ,  .

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implemeiitability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include!the following:
                                                                    /    l
        •      Bioremediation was eliminated because it would not be possible to inject nutrient
                solutions into the heterogenous subsurface of the landfill.  Not all compounds in the
                landfill could be treated using this technology.
        •      Solvent extraction was eliminated because it would not be possible to excavate all soils
                and waste from the landfill for treatment.                    I   .
        •      Soil flushing was eliminated because it would not be possible io flush the heterogenous
                subsurface of the landfill. Not all compounds in the landfill could be treated using this
                technology.
        •      Chemical oxidation was eliminated because it would not be pcissible to flush the
                heterogenous subsurface of the landfill.  Not all compounds in! the landfill could be
                treated using this technology.                          .'•[•'
        •      Chemical reduction was eliminated because it would not be possible to flush the
                heterogenous subsurface of the landfill.  Not all compounds in the landfill could be
                treated using this technology.
      ,  •      Low-temperature volatilization was eliminated because it would not be possible to
                excavate all soils and waste from the landfill for treatment.   i
        •      Vitrification was eliminated, because saturated soil conditions at the landfill would
                hinder implementation.                                    j
                                                                         r
        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      Soil vapor extraction  was eliminated because it would be applicable only to VOCs  and
                likely would not meet the goal of reducing THF.             !

        Innovative technologies eliminated during the detailed analysis include the following:

        •'      None'           '_                  .-  . .             :-   •   I

•.    •     '    •        •               •  '                           '••'!.'.        '      •'   •
 11.     Which of the nine criteria  were weighted most heavily in selecting the technology? Did failure
        to meet  one of the nine criteria result in the elimination of the innovattye technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?
        Protectiveness of human health and the environment, long-term effectiveness and permanence,
        and cost were weighted most heavily in selecting the preferred technology.  RAA-8 (vapor
        extraction) was eliminated because it would not effectively reduce concentrations of THF, and
        therefore would not provide an adequate degree of human health and environmental protection.
        While RAA-7 is among the most costly alternatives, it provides a high [degree of long-term
        human health and environmental protection by minimizing leaching of THF to ground water,
        removing contaminated soils currently in contact with ground water, arid, if necessary, treating
        ground water to meet ARARs.
                                               -4-
                                                                                              857

-------
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?

        No chemical-specific cleanup levels were established for soil, sediments, or wastes at the site.
        Site assessors expect that the selected alternative will reduce the leaching and migration of
        THF, barium, chromium,  and selenium from landfill wastes and soil to ground water.
        Implementation of RAA-7 will eventually reduce concentrations of these chemicals in ground
        water to below Wisconsin Ground Water Standards.
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                                                    -

        Innovative technologies eliminated because of cleanup goals include:

        "      Solvent extraction

        Standard technologies eliminated because of cleanup goals include:

        «      Cap repair and upgrade
                                                                                   .    '      •

14.     Were treatability studies conducted on the innovative technology or standard technology?

                                                                                              '
        No treatability studies were conducted.


75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

        •    Cost-effectiveness
        »    Protection of human health


16.     How are measures compared?                                                    •     •
                             '
        The chosen alternative represents the most protective alternative proposed. One other
        alternate, RAA-6, would have provided equal protection, but was much more costly.
        Therefore, the chosen alternative also is the most cost-effective alternative.
 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a final remedy.  The site does border
        wetlands, however, and RAA-6 was eliminated, in part because the physical barrier proposed
        in this alternative could adversely affect the wetlands.
85S

-------
                               Sturgis Municipal Well Field

                                      Sturgis, Michigan
                                          Region 5
 GENERAL SITE INFORMATION
1. What were the principal
contaminant levels, and
this feasibility study?

contaminants,
media addressed in


Maximum concentrations of principal
contaminants were:

Soil (rag/kg)

Trichloroethene
Tetrachloroethene
Cyanide
PAHs
PCBs




99
260
0.188
61.2
5.59
.


Site History

NPL Proposed:
NPL Final:
FS:
ROD:


N/A
\ . 11982
! 5/91
9/30/91
i
Background

EPA Fund-lead
PRPs: "N/A
FS prepared by:
Inc.

; ,
k
Warzyn Engineering,
i1
, i
* ' i
        What volume of material is to be
        remediated?                                                     ,

        The volume of material to be remediated included:    '

        »      10,000 cubic yards of soil to be excavated at the Kirsch property
        •      890 cubic yards of soil to be excavated at the Wade property   I
        What type of site is this?

        Fabricated Metal Products. The site was previously occupied by the Kirsch Company a former
        manufacturer and cyanide-based metal plating operations and the formei; Wade Electrical
        facility which has since burnt down:  It is located within the City of Sttirgis.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:  >
       Access restriction:
       Containment:

       Physical treatment:
Deed restrictions, fencing
Capping (soil, clay, synthetic membrane, MDNR Act 641 Solid Waste
Management cap, MDNR Act 64 Hazardous Waste Management cap)
Mechanical soil aeration
                                            -1-
                                                                                            859

-------
       Thermal treatment:     Incineration (rotary kiln, single chamber, teepee burner open pit,
                              multiple chamber, controlled air)
       Disposal:              Excavation, disposal  (on-site, off-site)
3
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   In situ biodegradation, ex situ biodegradation (in general), landfarming,
                              slurry reactor                                            -
        Chemical treatment:    Soil washing, solvent extraction, flushing, oxidation, dehalogenation
        Physical treatment:     Soil vapor extraction (SVE)
        Thermal treatment:     Enhanced thermal volatilization (pn-site, off-site), in situ vitrification
        What was the cost estimate for the innovative technology?

        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-3
Innovative Technology
Soil vapor extraction/solid waste cap or
hazardous waste cap
Soil vapor extraction/excavation of
PCB and PAH containing soil/off-site
disposal or incineration
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$1,610,000
or
$2,970,000"
$2,310,000
or
$6,460,000b
        The two costs refer to either a solid waste cap or a hazardous waste cap.
        bThe two costs refer to the choice of either off-site disposal of incineration.
880
                                               -2-

-------
7.      How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)    !
Alternative-
RAA-1
Standard Technology
No action
Estimated Costs
3 .Criteria
N/A
9 Criteria
$104,000
8.      If a standard technology was chosen, why?

        Off-site disposal of PAH/PCB contaminated soil was selected.
 10.
        If an innovative technology was chosen, why?                     !
                                                                  •' '   • ,|               '
        RAA-3 was selected because it protects human health and the environment though treatment.
        Implementation of this alternative eliminates the Kirsch and Wade properties as sources of
        ground water contamination, thereby reducing potential risk to human heiilth and the
        environment posed by possible use of contaminated ground water.  RAA--3 affords a high
        degree of effectiveness by treating with SVE the principal threat (VO^s) in the source area
        soils, and removing the remaining PAH/PCB contaminated soil for disposal off site. This
        alternative was also preferred because the permanent elimination of site contaminants will
        allow for unrestricted future land use.  No unacceptable short-term risk or cross-media impacts
        will be caused by the implementation of this alternative.  Standard safety programs, such as
        fencing, use of protective equipment, monitoring, and dust control measures should mitigate
        any short-term risks.  This remedy complies with all ARARs and is ciost-effective.  The clean
        closure of the source areas will permanently reduce contamination to acceptable levels and it
        does not cost significantly more than containing contaminated soil on-site.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

 •      On-site enhanced thermal volatilization was eliminated because it would be difficult to
        excavate the deep contaminated soil for treatment. Given the relatively small volume
        of soil  contaminated by high levels of-VOCs and the additional substantive
        requirements of on-site treatment, off-site treatment is more implementable.
, •      Ex situ biodegradation (general) was eliminated because its feffectiveness for
        TCE/PCE-contaminated soil has not been demonstrated, and costs would likely be high
        given the amount of treatability study work that would be required and given the
                                                                                                861

-------
                    length of time that biological systems typically take to degrade recalcitrant organic
                    compounds.
            •       Land/arming was eliminated because of a lack of space.
            •       Moving bed or rotary drum were eliminated because no applications of this sort have
                    been identified for soils with relatively low-level VOC contamination present in the
                    deeper soil.                                                   .
            •       Slurry reactor was eliminated because it would produce an aqueous waste stream
                    requiring treatment and disposal, and pilot testing would be required
            •      Soil washing was eliminated because it would not be very effective in treating the
                   relatively low levels of VOC present in the deeper levels of contaminated soil
                   Implementation would be more difficult than for some other options because the liquid
                   waste stream would need to be managed.         ,
            •      Solvent extraction was eliminated because it would not be yery effective in treating the
                   relatively low levels of VOCs present in the deeper levels of contaminated soil
                   Implementation would be more difficult than for some other options because the liquid
                   waste stream would need to be managed.
            "      ^ situ vitrification was eliminated because of the high cost of the power requirements,
                   difficulties in implementation due to nearby buildings, and the availability of other
                   effective treatment options.
            "      Flushing was eliminated because  its effectiveness has not been demonstrated and it
                   might not be implementable since it could cause further ground water contamination
                   In situ oxidation was eliminated because the effectiveness of chemically treating
                   relatively low levels of VOCs has not been demonstrated and therefore might not be
                   effective for the deeper levels of contaminated soil.  Furthermore, the inability to
                   control the reaction and the  potential for ground water contamination would present
                   problems in implementing this option.
           •       In situ dehalogenation was eliminated because the effectiveness of chemically  treating
                   relatively low levels of. VOCs has not been demonstrated and therefore might not be
                  effective for the deeper levels of contaminated soil. Furthermore, the inability to
                  control the reaction and the potential for ground water contamination would present
                  problems in implementing this option.
           •      In situ biodegradation was eliminated because it might produce hazardous substances
                  and because identifying and  maintaining a suitable environment would be difficult   '
                  The potential  for ground water contamination would limit the implementability of this
                  treatment. Two carbon sources and nutrients likely would have to be added to provide
                  a suitable environment for the microorganism.

          Innovative technologies eliminated during  the screening of the three criteria include the
          following:                                                                     .

          »      Enhanced thermal volatilization (off-site) was eliminated because soil vapor extraction
                  is a proven effective means of removing volatile compounds and this technique would
                  not offer any additional advantages such as the removal of PAHs.

          Innovative technologies eliminated during the detailed analysis include the following:

          "      None
.)
8G2
                                                -4-

-------
 11.
 12.
 Which of the nine criteria were weighted most heavily in selecting the* technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 The criteria weighed most heavily in selecting a remedial alternative vtere protection of human
 health and the environment, long-term effectiveness, and cost.  RAA-li was eliminated because
 it would not be protective of human health.  RAA-2 was eliminated because it would require
 long-term maintenance of the cap and permanent restrictions on the use of the contaminated
 land.  In RAA-3, the choice for treatment for PCB and PAH contaminated soil was
 incineration or off-site disposal.  Off-site disposal was selected because  it was significantly less
 expense than incineration.          ,           .           .',-!'.

                                        •,                  •      i    , •      •
 What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAB
Carcinogens .
Trichloroethene
Tetrachloroethene
Benzo(a)pyrene
Benzo(b)fluoranthene
60
14
330
330
Micl
L or Other Basis

rigan Act 307a
Michigan Act 307


MDLb
'MDL
               "Michigan Act 307 Type B cleanup, based on "20 times" the ground water standard.
               "Method Detection Level.      . ,                           i
13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None                                            .

Standard technologies eliminated because of cleanup goals include:

•      None              ,
14.     Were treatability studies conducted on the innovative technology or standard technology?
      ...           '                       •                          I
       Treatability studies were not conducted.
                                              -5-
                                                                                             863

-------
75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare me alternatives:

             Proven reliability
             Waste left in place/institutional control


16.    How are measures compared?

       RAA-3 was preferred over RAA-2 because it will be more reliable. Once RAA-3 is
       completed, it will neither depend on institutional controls nor require perpetual maintenance.
17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        No technical considerations were primary in  selecting a remedial alternative.
8G4
                                              -6-

-------
                                         Tar Lake
                                           OU-1

                                  Antrim County, Michigan
                                          Region 5
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?
   \,        _     ,       ,      . .   '

        Maximum concentrations of principal
" ,      contaminants were:
        Soil/Tars (mg/kg)

        Benzene
        Ethylbenzene
        Toluene
        Styrene
        Xylenes
        Acenaphthene
        Anthracene
        Benzo(a)anthracene
        Benzo(f)fluoranthene
        Benzo(k)fluoranthene
        Chrysene
        Di-n-butyl phthalate
        Fluoranthene
        Fluorene
        Naphthalene
        Pyrene
        2,4-Dimethylphenol
        2-Methylphenol
        4-Methylphenol
1.2
100
100
2.3
280
280
280 .
280
280
280
280
280
280
100
340
280
2,000
1,100
1,400
                              Site Elistory
                 NPL Proposed:
                 NPL Final:
                 FS:
                 ROD:
                     1:2/82
                     9/83
                     21/92
                     9/29/92
             Background

PRP-lead          !
PRPs:  Fifty-sixth Century Antrim Iron
       Works Comptany
FS prepared by: Environmental Safety
       Designs , Inc.
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:
              ^•-' '                    -                              '
        •      30,000 cubic yards of tar        ,
        •      20,000 cubic yards of soil with high levels of contamination (ail excess cancer risk
               equal to or greater than 10"2)
        •      20,000 cubic yards of soil with low levels of contamination (an excess cancer risk less
               than 10'2 and greater than 10'6)
                                             -1-
                                                                                           865

-------
   3.      What type of site is this?          ,

           Wood Charcoal Production.  A large natural surface depression filled with waste materials
           from a wood charcoal production operation.
                                                                           I)
   TECHNOLOGY SELECTION

   4.      What'Standard technologies were considered for selection in this FS?

           Standard technologies incorporated into RAAs were;
          Access restriction:
          Containment:
          Physical treatment:
          Thermal treatment:
          Disposal:
Deed restrictions
RCRA cap
Dewatering                         ;
Incineration          '
Excavation, off-site disposal at RCRA facility, on-site disposal in
RCRA cells
   5.     Was an innovative technology considered in the FS?  If so, which technology?

          Innovative technologies incorporated into RAAs were:

          Biological treatment:  Bioremediation
          Thermal treatment:    Thermal desorption             x


   6.     What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation  of RAAs), the FS does not quantify costs.  After the .RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. For this site, no three-criteria screening was conducted and the estimated costs
          were calculated  during an evaluation based on nine criteria established by the NCP.

                   Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
366
Alternative
RAA-2

Innovative Technology
Deed restrictions/excavation/on-site
incineration of tar and highly
contaminated soils/bioremediation of
remaining soils/RCRA cap/interim
ground water containment
Estimated Costs
3 Criteria
N/A

9 Criteria
$51,400,000


                                               -2-

-------
Alternative
RAA-4
RAA-7
Innovative Technology
Excavation/on-site incineration of tar
and highly contaminated soils/thermal
desorption of remaining soils/interim
ground water containment
Excavation/off-site disposal of tar and
highly contaminated soils at RCRA
facility/bioremediation of remaining
soils/interim ground water containment
Estimated Costs
3 Criteria
*
I1
I/A
/
I/A
9 Criteria
$64,200,000
$51,400,000
7.      How did the cost(s) compare to standard technologies?

               _' Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-3
RAA-5
RAA-6
Standard Technology
No action
Excavation/on-site incineration of tar
and highly contaminated soils/excava-
tion/off-site disposal of remaining
soils/interim ground water containment
Excavation of tar and all soils/dewater
tar/off-site disposal at RCRA facility/
interim ground water containment
Excavation and consolidation of tar
and all soils/on-site disposal in RCRA
cell/cover (cap)/interim ground water
containment
Estimated Costs
3 Criteria
i{r/A
N/A
' tf/A
N/A .
9 Criteria
$0
$58,500,000
$52,300,000
$20,100,000
' - ..-'••",
       If a standard technology was chosen, why?                        ,

       The standard technology selected includes excavation of tar and all soils; on-site disposal in a
       RCRA cell;  interim ground water containment. The technology was selected because: 1) it
       was the most cost effective, 2) minimizes risk by eliminating exposure (ground water and
       . ingestion) pathways, and 3) not subject to RCRA Land Disposal Regulations.
       If an innovative technology was chosen, why?

       An innovative technology was not chosen.
                                             -3-
867

-------
    10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?

 Innovative technologies could be eliminated from the remedial technology  selection process at
 three stages: during the initial screening; during the screening of the'three criteria of
 effectiveness, 
-------
Contaminant
Benzo(a)anthracene
Benzo(b) fluoranthene
Benzo(k) fluoranthene
Chrysene x
Cleanup Level (ppb)
100
100
100
100
ARAR or Other Basis
•i
Michigan! Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Noncarcinogens
Ethylbenzene
Toluene
Xylenes
Acenaphthene
Anthracene
Di-n-butyl phthalate
Fluoranthene
Fluorene
Naphthalene
Pyrene
2,4-Dimethylphenol
2-Methylphenol
4-Methylphenol
1,400
16,000
6,000
2,000
40,000
14,000
6,000
6,000
800
4,000
8,000
8,000
8,000
Michigan Act 307
, Michigan Act 307
Michigan Act 307
Michigan Act 307
- Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307
Michigan Act 307 <
Michigan Act 307
Michigan Act 307
•
Michigan Act 307
Michigan Act 307
       Remedial action cleanup standards were based on Michigan'Environmental Response Act 307,
       Type B cleanup criteria. Cleanup levels developed by Type B criteria an; health based and
       reduce risk to less than 10"6.  If local background concentrations are greater than the health-
       based criteria, then average local background concentrations can be used as final cleanup
       goals.                                                  .        i  -

                                       ,                   .      , -     i
13:     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?    ~    •

       Innovative technologies eliminated because of cleanup goals include:
     /            .                ,              "             :          •,._'•
       •      None'.          .'     .                   ..•",!•       ;

       Standard technologies eliminated because of cleanup goals include:
                    -                      '                "            !
       •      None                                                   '      .
                                              -5-
                                                                                               889

-------
    14.     Were treatability studies conducted on the innovative technology or standard technology?

            No treatability studies were conducted.


    15.     What measures/criteria were used to compare alternatives?

            The following measures were used to compare the alternatives:
                 Total Cost


    16.     How are measures compared?

            The selected alternative was chosen because it is the* most, cost-effective option. The selected
            alternative provides a high degree of protectiveness through the containment of contaminated
            soils. All other alternatives  (except RAA-1) would provide an equal degree of protection
            through a variety of treatment technologies. The selected alternative provides equal
            protectiveness at one-third the cost.
    77.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in the selection of a remedial alternative.
870
                                                 -6-

-------
                                 Thermo-Chein, Inc.
                                        OU-1

                              Egelston Township, Michigan
                                        Region 5
GENERAL SITE INFORMATION
1. What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:
Soil/Sludge (mg/kg)
Benzene
Toluene
Xylenes
Naphthalene
2-Methylnaphthalene
1 Aroclor-1254
Heptachlor
Dieldrin
4,4-DDT
Arsenic .
Chromium
Lead
Cyanide .

19
270
770 . '
.3
3 ...
1
0.2
0.2
0.03
10
978
' ' ' • '
I
Site History
I
NPL Proposed: i 10/84
NPL Final: 1 6/86
FS: ! 5/91
ROD: i 9/30/91
- i . >
Background
EPA Fund-lead
PRPs: Thermo-Chem, Thomas Solvent
Co. i ^ - •* :,
FS prepared by: Environmental
Resources Management-North '
Central, Incorporated
i

1
r
1,050 ' ••.!.'-
599 ' I
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      2000 cubic yards of soil and sludge
       •      157,000 cubic yards of remaining contaminated soil
      What type of site is this?


      Recycling. An inactive solvent and chemical waste reprocessing, refining, and incineration
      facility.
                                          -1-
                                                                                     871

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard .technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:

        Chemical treatment:
        Thermal treatment:
        Disposal:
Fencing, deed restrictions                  ,
Capping (clay, synthetic liners, concrete, asphalt, vegetative, multi-
layer), grout barriers, slurry wall, sheet piles, vertical barriers
Solidification/stabilization, neutralization
Incineration (fluidized bed, infrared, rotary kiln)
Excavation, disposal at RCRA facility/non-RCRA facility
5.      Was an innovative technology considered in the FS?  If so, 'which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:  In situ biodegradation (aerobic/anaerobic)
        Chemical treatment:   In situ soil flushing (solvent), oxidation/reduction
        Thermal treatment:    In situ vitrification, in situ vacuum vapor extraction, low temperature
                             thermal treatment
6.      What was the cost estimate for the innovative technology?                \

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are usually estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case, estimated costs were calculated during an evaluation based on nine
       criteria established by the NCP.

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-3A
(RAA-3)"
Innovative Technology
Fencing/deed restrictions/in situ
vitrification of Group 1 and 2a (2 and
3)b soil/ground water monitoring
Off-site incineration of Group 1 & 2
soils/in situ vacuum vapor extraction
of remaining soil/ground water collec-
tion, treatment, and disposal at
POTW
Estimated Costs
3 Criteria
-N/A
N/A
9 Criteria
$82,700,000
$24,300,000
  872
                                              -2-

-------
Alternative
RAA-3B
RAA-4A
(RAA-4)b
RAA-4B
Innovative Technology
On-site incineration of Group 1 soil/in
situ vacuum vapor extraction of Group
2 soil/ground water collection,
treatment, and disposal at POTW
Off-site incineration of Group 1 soil/in
situ soil flushing and biodegradation of
Group 2 soil/ground water collection,
treatment, and discharge to aquifer
On-site incineration of Group 1 soil/in
situ solvent flushing and biodegradation
of Group 2 soil/ground water collection,
treatment, and discharge to aquifer
Estimated Costs
3 Criteria
N7A
' E '-
N/A
N/A
9 Criteria
$23,000,000
$24,000,000
$24,000,000
        "Soils were designated as Group 1 or Group 2 soil for the purposes of [remediation,.
        'Text presented parenthetically represents corresponding changes in the? ROD.
 7.      How did the cost(s) compare to standard technologies?
Cost Estimates for RAAs That Include Standard Techno
(selected remedial alternative is in bold)
Alternative
RAA-1
RAA-5
Standard Technology
No action
Slurry wall/RCRA cap/ground water
collection, treatment, and discharge to
POTW
1
logics
Estimated Costs
3 Criteria
N;;A ••
- N/A - .
9 Criteria
$0
$32,000,000
8.     If a standard technology was chosen, why?

       Incineration was selected as a component of the remedy. It was selected to: 1) comply with
       the Michigan Act 307 Rules for a Type A/B clean-up given the potential residential use of the
       site, 2) to meet LDRs, 3) destroys organic and PCB/pesticides, 4) easy to implement because
       it's been used at other Superfund sites.                              i
9.      If an innovative technology was chosen, why?

       Soil vapor extraction was selected as a component of the remedy. It wks selected 1) to reduce
       toxicity, 2) it is easy to implement because it has been used at other Superfund sites, 3) it will
       take less than 4 years implement and 4) cost.
                                             -3-
873

-------
 10.    If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        *      Low temperature thermal treatment was eliminated but no explanation was given.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        H      None
                    v                              •                       •  •
        Innovative technologies eliminated during the detailed analysis include the following:

        •      In situ biodegradation was eliminated because it could not be performed during winter
                months, because it is a relatively new technology and EPA would need to perform
                treatability studies before implementing it.
        "      In situ soil flushing was eliminated because  it would take too long to remediate the
                site, cleanup levels.
        •      In situ vitrification was eliminated because of the technical and administrative
                difficulty is uncertain because the technology has not been applied fully at any
                Superfund site and the high cost.
 11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The most heavily weighted criteria in selecting an innovative technology were protectiveness
        of human health and the environment, cost, time to implement the technology and compliance
        with ARARs..  Of the three proposed innovative technologies that would offer comparable
        protection, compliance with ARARs, and reduction of contaminants, the chosen alternative is
        the least costly and the most rapid to implement. Thus, criteria that resulted in the elimination
        of innovative technologies were cost and implementability.
 12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
874
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Benzene
Aroclor-1254
. 10
1
Michigan Act8'0
Michigan Actb'°
                                               -4-

-------

Contaminant
Heptachlor
Dieldrin
4,4-DDT
Arsenic -
Chromium
Lead
Cleanup Level (mg/kg)
0.00004
0.0000006
0.00005
0.0004
0.04
9
ARAR or Other Basis
Miphigan Actb
Michigan Actb
Michigan Act*1
Michigan Aetb
Michigan Actb
Michigan Actb
Noncarcinogens
Toluene
Naphthalene
2-Methylnaphthalene
Xylenes -
Cyanide
2
0.6
0.2
1
0.08
Michigan Actb
Michigan Actb
Michigan Actb
Michigan Actb:
Michigan Actb
               The Michigan Environmental Response Act (Michigan Act 30[7) establishes the
               criteria for three acceptable cleanup types.  Under this statute, Type A cleanup
               generally achieves background or nondetectable levels. Type B cleanup achieves
  ^           levels that protect ground water from the migration of soil contaminants into the
  """           ground water; protect against unacceptable human health risks due to direct contact;
               and protect surface water quality.  Type C cleanup is based on site-specific criteria.
               EPA selected a Type A/E cleanup given potential residential use of the site. A 10"6
               risk level for carcinogens was chosen as the point of departure j for determining
               remediation goals.
               bBased on ground water protection.                         j
               cBased on 10"6 carcinogen risk associated with direct contact.


13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:
                                            •.                 '      .      i..       •      •
        •      None
                                                                         i   .
        Standard technologies eliminated because of cleanup goals include:      '
                                                                         •r

      '••-•      None                                                     I
14.
Were treatability studies conducted on the innovative technology or standard technology?

No treatability studies were conducted.                              j
                                               -5-
                                                                                        875

-------
                                                                                                           n
  /5.     What measures/criteria were used to compare alternatives ?
                                                     •    '      ''•"•'•'       .  •    •         0
         The following measures were used to compare the alternatives:                                       •••-;'

                Cost-effectiveness
                Time to design/construct/operate                      ,                                        I
                Proven reliability                                        .                        •          •  1 '
                Preference for treatment (vs. containment)

                                                                                            i .         •
  16.     How are measures compared?
                                                                                                          ,\
         The chosen alternative provides a high degree of effectiveness and permanence through source             '
         treatment, which was preferred over containment.  RAA-5 proposed no source treatment and
         was considered less effective.  Cost-effectiveness was also a primary factor.  One alternative
         (RAA-2) offered a comparable amount of protection through source treatment, but was                    !
         eliminated because it was hot cost-effective.  Other alternatives (RAA-4A and RAA-4B) were      ,       i
         eliminated because their time to operate was  too long.  Treatability studies would have been
         required due to the unproven reliability of the treatment technology (biodegradation).
                                                   '
                                                                                          "               '  i
  17.     What technical considerations were factors in selecting a remedy? Were technical                        \
         considerations primary in the selection of the remedy?                                           M^,
                                                                                                    Am
         No technical considerations were primary to the selection of a remedy.                            ^^  .
                                                                                                           I)
876
                                              -6-

-------
                                          Torch Lake
                                       OU-landOU-3

                                   Houghton County, Michigan
                                            Region 5
  GENERAL SITE INFORMATION
  .1.
wnai were tne principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Slag piles/Tailings (rag/kg)
11 Jf A: I " ' '
Metals: ,

Arsenic 118
Antimony 164
Beryllium 2
Chromium 745
Copper 13,500
Lead 113 .

Site History ,
NPL Proposed: 10/84
NPL Final: 6/86
FS: 4/92
ROD: 9/30/92

Background

EPA Fund-lead
PRPs: Universal Oil Products; Quincy
Mining Company
FS prepared by: SEC Donohue
Incorporated

         PAHs:

         Napthalene            .17
         2-Methynaphthalene    .24
         Acenaphthalene        .037
         Phenanthrene,          .27
         Fluoranthene          .4
         Pyrene                .39
         Chrysehe              .41
        What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      81,250,000 cubic yards of tailings
        •      150,798 cubic yards of slag piles
S3.      What type of site is this?.                      .

        Primary Metal Products. A copper milling and smelting facility.  OU-1  includes surface
        tailings and slag piles on the western shore of Torch Lake.  OU-3 consists of 12 tailing and
        slag locations throughout the mid-Keweenau Peninsula.
                                             -1-
877

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Slag piles

        Access restriction:     Fencing, deed restrictions
        Containment:          RCRA cap, non-RCRA cap, soil cap, vegetation
        Chemical treatment:   On-site solidification/stabilization, off-site solidification/stabilization

        Tailings                                                                       =

        Access restriction:     Fencing, deed restrictions
        Containment:          RCRA cap, non-RCRA cap, soil cap, vegetation


5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Slag piles                                                      ,

        Chemical treatment:   Hydrometallurgic reprocessing, heap leaching
        Thermal treatment:     Pyrbmetallurgic reprocessing


6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated,,'costs are estimated  as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more  detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.

        No innovative technologies were incorporated into remedial alternatives.
 878
                                              -2-

-------
 7.
How did the cost(s) compare to standard technologies?
                   Cost Estimates for RAAs That Include Standard Technplojjies
                       (selected remedial alternative is in bold)
        Slag Piles
Alternative
RAA-S-1
RAA-S-2
RAA-S-3
RAA-S-4
Tailings
Alternative
RAA-T-1
RAA-T-2
RAA-T-3
Standard Technology
No action
Fencing/deed restrictions
Soil cover/vegetation
Excavate/off-site disposal at permitted
landfill
Estimated Costs
3 Criteria
$0
$60i,000
$116,900
$11,148,000
•' • • .-i. • .
• 1 .
Standard Technology
No action
Soil cover/vegetation/deed restrictions
Non-RCRA cap/soil cover/vegetation/
deed restrictions
9 Criteria
$0
$60,000
$116,900
$11,148,000

Estimated Costs
3 Criteria
$0
$7,200,000
$26,000,000
'•
9 Criteria
$0
$7,003,000
eliminated
                                        ' .    '                            I                   t
8.      If a standard technology was chosen, why?                          i
                ' '                              ,                   '       l'K
       The selected remedy included soil cover/vegetation of specified slag'piles in areas, no action
       on other specified slag piles and a soil cover/vegetation/deed restrictions on the tailings pile
       The primary goals is to 1) protect ingestion and breathing of dust particles and contaminants
      .2) to minimize affect on ecosystems, ground water and sediments, 3) volume- of material 4)
       cost, 5) avoids excavation which would stir up dust.  Certain areas of tlie tailings pile were to
       remain uncovered in response to public comments.                   !
                                                                         I   . ' -

       For OU-3, assuming that this area will become a National Historic Park, the results of the risk
       assessment showed both carcinogenic and noncarcinogenic .risks to workers and visitors were
       below EPA s acceptable risk range.  However, the release of tailings from this location to the
       beach is ongoing. Further, if future site use is residential, unacceptable risks are attributed
       primarily to  ingestion of tailings by adults or children.  Therefore, RAAU-i was deemed   .
       sufficient to  address slag piles while a more protective remedy RAA-T-2 was selected for
       implementation with tailings.  This choice is protective of human heath and the environment
       since it eliminates the risk due to inhalation and ingestion and it minimizes transport of
       contaminants mto the lake.  The selected alternatives also,complies,with1 ARARs and offers   -
       long-term effectiveness.                                    ,         i
                                              -3-
                                                                                     879

-------
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
L):
JO.     If an innovative technology was not chosen,  why not? At what stage was the innovative
        technology eliminated?                                                                 •

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        •      Hydrometallurgic reprocessing was  eliminated  because 1) the recovery of
               copper as a treatment joption would be useful only if As, Be and Cr can also
               be simultaneously removed and there is no performance data to indicate this is
               feasible, 2) mineralogic characteristics of tailings are not favorable for efficient
               copper removal, 3) process would adversely affect surrounding ecosystems
               because tailings will have to be excavated, and 4) large volume to excavate
               makes it impractical.           ,                                ,
        B      Pyrometallurgic reprocessing was eliminated for the same reasons as  hydrometallurgic
               reprocessing.
        »      Heap leaching was eliminated because 1) no performance data is available on copper
               recovery, 2) potential for simultaneous removal of As, Be, and Cr is unknown, 3) As
               is present as a complex compound and is not likely to be removed by extraction, 4)
               effective only during warm periods  (70 - 90 F), 5) heap leaching piles would cover too
               extensive an area, 6) would interfere with plans to develop Quincy Smelter as a
               National Historic Park, 7) cost of excavation and consolidation is too  high, 8)
               excavation would generate dust and affect surrounding ecosystems.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        ii     None

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None                                                        ,    •


  11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one  of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Protection of human health and the environment and cost were the criteria that supported the
        choice of a standard technology.  Implementability and short term effectiveness were also
        important in decision making. No innovative technologies were eliminated due to these nine
        criteria.
   830
                                                -4-

-------
   12

        Innovative technologies eliminated because of cleanup goals include:'[.

     ,  • • .   None    ;      •             •     .    '        - r      ',   .


        Standard technologies eliminated because of cleanup goals include:   !

        ••    None ,         ,         -^               '••:!.-'         ;'



 14.  >   Were treatability studies conducted on ^ innovative technolo^ or






                                 "                         I


 IS..:  What measures/criteria were used to compare alternatives?         ]


       The following measures were used to compare the alternatives-       '   '
                         . • . "                    '           'I •
           Total Cost                                         ,|         .'....-

           Impact on nearby populations                    •       |            •  „ •
                  '                          - •  - ' •          '[•-'•'


16.    How are measures compared?                               !

"'    -";^zr;^;Trs,t:;y"se"carremedy? »«°^™«
                 /// uriury m me selection of the remedy?               |
                                                                           831

-------
            Tri-County Landfill CoTWaste Management of Illinois, Inc.
                                 (and Elgin Landfill)

                                     Elgin, Illinois
                                       Regions
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Arochlor-1242              3.0
       Benzo(a)anthracene         1.5
       Benzo(a)pyrene             1.3
       Benzo(b)fluoranthene       2.3
       Benzo(k)fluoranthene       2.3
       Chrysene                  1.6
       Indeno(l,2,3-cd)pyrene      0.6
       Trichloroethene            0.03
       Arsenic                   30
       Beryllium                  1.3
       Lead                      2,200
       Nickel                     260
       Antimony                  59
       Chromium    -            58
       Copper                   3,800
       Magnesium                81,000
       Zinc                      2,300

       Sediments (mg/kg)

       Aluminum                 14,000
       Arsenic                   380
       Barium                   2,600
       Beryllium                  1.1
       Calcium                   97,000
       Chromium                 27
       Cobalt                     44
       Copper                   92
       Iron          .             620,000
       Lead                      100
       Magnesium                50,000
       Nickel                     83
       Potassium                  4,900
            Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
3/89
7/24/92
9/30/92
            Background

EPA Fund-lead
PRPs: Not listed
FS prepared by:  WW Engineering &
   ,            Science
                                             1:)
832
                                          -i-

-------
        Sodium
        Vanadium
        Zinc
        2,900
        70
        230
 2.      What volume of material is to be remediated?                      !

        The volume of material to be remediated included:
                                                          •              .!            ' '   '  .'
        «      3.5 million cubic yards of soil                             |
        •      1,000 cubic yards of sediment                             I
                                                      •••'.'        J                    '

 3.      What type of site is this?

        Municipal Landfill. Tri-County landfill is an inactive landfill and Elgin landfill (which is
        adjacent to Tri-County landfill) once accepted residential and commercial wastes and continues
        to accept construction and  landscaping debris. The site is bordered by residential and
        agricultural land.
TECHNOLOGY SELECTION             .                              i
                                                      :                  '
4.      What standard technologies were considered for selection in this FS?\              .
                                                                        I             '

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Soil

        Access restriction:
        Containment:

        Chemical treatment:
        Physical treatment:
        Thermal treatment:
        Disposal:

        Sediments

        Containment:
        Thermal treatment:
        Disposal:
Fencing, deed restrictions
Capping (clay, synthetic membrane, asphalt, concrete, multimedia),
grading, flood control dikes, soil cover/revegetation
Fixation/solidification
Aeration, slump degradation, enhanced volatilization
Incineration
Excavation, on-site landfill, off-site landfill  ,
Capping (synthetic membrane, clay, asphalt, concrete)
Incineration
Excavation, dredging, on-site landfill, off-site landfill
5.      Was an innovative technology considered in the FS?  If so, which technology?
                                          i                              i.
                                                                        !   !
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
                                              -2-
                                                                                              883

-------
       Soil

       Biological treatment:   Microbial degradation
       Chemical treatment:   Soil flushing, soil washing, soil vapor extraction, in situ oxidation
       Thermal treatment:    Vitrification                          .                    -
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. For this site, the estimated costs are calculated during,an evaluation based on nine
       criteria established by the NCP.  No innovative technologies were considered.
7.      How did the cost(s) compare to standard,technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)

       Soil
Alternative
RAA-SW-1
RAA-SW-2
RAA-SW-3
Standard Technology
No action
Clay cap/fencing/deed restrictions
Multimedia cap/fencing/deed restrictions
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$0
$6,500,000
$12,600,000
       Sediment
Alternative
RAA-SS-1
RAA-SS-2
Standard Technology
Excavation/on-site containment
Excavation/off-site containment
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$24,000
$34,000
5.      If a standard technology was chosen, why?                            -

       RAA-SW-2 was chosen because it will decrease site risks by reducing ground water and air
       contamination. This alternative will limit the amount of precipitation which percolates through
       the landfill, thereby reducing leachate generation and contaminant mobility.  The cap also will
       eliminate exposure from the inhalation of contaminated particulates.  The alternative will
       provide a permanent and long-term solution, and is the most cost-effective option.
  884
                                              -3-

-------
        RAA-SS-1 was chosen because it will decrease site risks by reducing 1;he migration of
        contaminated sediments into the ground water or air.  This alternative Svill 'be effective in the
        long-term and will reduce contaminant mobility.                     j
                                              •                           1-               •
                                  -                 '                         '" .
             •          "  '                    '   •'    .       '             T
9.      If an innovative technology was chosen, why?                       I
                                                                        . i
  •  '                          •                                        •'  i
        An innovative technology was not chosen.                          j

                                                                         i                    .
                                                                         L *    '     •      ' j
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                            !
                                                                         i     .    -  .        •.

        Innovative technologies could be  eliminated from the remedial technology selection process at
        three stages: during the initial  screening; during the screening of the tlbree criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.
                                     '             ,                   ..'I..'-
        Innovative technologies eliminated during the initial screening include the  following:

        •      Soil washing was eliminated because it would require excavation of waste from its
            '   existing location.
        •      Microbial  degradation was eliminated because it would be difficult to implement
               because of the site's size  and the heterogeneity of the waste material.
        •      Soil flushing was eliminated because it would be difficult to implement because of the
               site's size  and the heterogeneity of the waste material.        j
        •      Soil vapor extraction was eliminated because it would be difficult  to implement
               because of the site's size  and the heterogeneity of the waste material.'
        •      Vitrification was eliminated because of the amount of energy required
        •      In situ oxidation was eliminated because it would be difficult to control because of the
               site's size  and heterogeneous nature.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                                     ....-•
                                                                         ,|

        •      None                                                     !
                                                                         ! .  . ' •
        Innovative technologies eliminated during the detailed analysis include the following:
                                                    ,.                 -i
        •      None         '     '       '    .  /,                       , i                   :
11.     Which of the nine criteria were weighted most heavily in selecting the ^technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protectiveness of human health and the environment and compliance with ARARs were
       weighted most heavily in selecting an alternative. Since all alternatives, however, offered
       adequate protection of human health and the environment and complied with all relevant
       ARARs, alternatives were eliminated based on cost-effectiveness.
                                              -4-            •  •     '     1  ."    '          '   835

-------
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?

             Soil
Soil Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Arochlor-1242
Benzo(a)anthracene
Benzo(a)pyrene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Chrysene
Indeho(l ,2,3-cd)pyrene
Trichloroethene
Benzene
Bis(2-ethylhexyl)phthalate
Dibenzo(a,h)anthracene
Tetrachloroethene
Trichloroethene '
Arsenic
Beryllium
Lead
Nickel
0.08
0.33
0.1
0.33
0.33
0.33
0.33
0.014
0.16
7.1
0.33
0.13
0.014
0.01
0.005
9
2
CRDL"
CRDL
CRDL
CRDL
CRDL
CRDL
CRDL
Ground waterb
CRDL
Risk0
CRDL
Ground water
Ground water
CRDL
Ground water
Ground water
Ground water
Noncarcinogens
Acenaphthene
Anthracene
BenzoCg.h.iJperylene
Butylbenzylphthalate
Di-n-butylphthalate
Dichlorobenzene
Ethylbenzene
Fluoranthene
86
9,100
120
4.4
8
4.1
27
1,200
Ground water
Risk
Risk
Ground water
Ground water
Risk
Ground water
Risk
836
                                         -5-

-------
•',-'.
Soil Contaminant
Fluorene
Methylphenol
Naphthalene
Phenathrene
Pyrene .
Toluene
Mercury
Total xylene
Antimony
Chromium
Copper
Magnesium
Zinc
Cleanup Level (mg/kg)
1,200
4
8
3.3
910
9
45
96
5
0.01
13
15,000
1.5
ARAR or Other Basis
Risk
Ground water
Ground water
Ground water
Risk
Ground water
Ground water
Ground water
Ground water
CRDL
CRDL
Ground water
Ground water
"CRDL is the Contract Required Detection Limits. The risk-based remedial action
levels are less than conventional analytical detection limits and therefore the detection
limits are proposed as remedial action levels.
""'Ground water" refers to the maximum concentration in soil that is protective of
ground water. This estimation procedure was obtained from Determining Soil
Response Action Levels Based on Potential Contaminant Migration to Ground Water:
A Compendium of Examples (USEPA, Oct. 1989).
'"Risk" refers to human health risk assessment calculations. For carcinogens, an
excess upper bound individual lifetime cancer risk between 10"4 to 10* was acceptable.
For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
Sediments

Contaminant
Cleanup Level (mg/kg)
AFLAR or Other Basis
Carcinogens
Arsenic
Cadmium
Beryllium
8.4
6
0.9
ffiPA"
ffiPA
ffiPA
Noncarcinogens
Aluminum
Antimony
15,000
,12
ffiPA
ffiPA
••''•-'• '/ • -6- : .':' "'". :' ;: " . • £
                                                    837

-------
Contaminant
Manganese
Selenium
Barium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Nickel
Potassium
Sodium
Vanadium
Zinc
Cleanup Level (mg/kg)
930
1.3
170
. 52,000
24
14
45
33,000
.70
21,000
.25
970
1,000
36
170
ARAR or Other Basis
ffiPA
ffiPA
ffiPA
ffiPA
ffiPA
ffiPA
ffiPA
ffiPA
BEPA
ffiPA
ffiPA
IEPA
ffiPA
ffiPA
ffiPA
                'Proposed sediment cleanup levels were calculated by the Illinois Environmental
                Protection Agency (IEPA) to account for different soil types' capacities to absorb
                contaminants.
 13.     Was the innovative technology eliminated because of the cleanup, goals? Could the standard
         technology meet the cleanup goals?

         Innovative technologies eliminated because of cleanup goals include:

         •      None                                                 .

         Standard technologies eliminated because of cleanup goals include:

         •      None


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        The selected remedy included a study of the potential impacts on wetlands and a program to
        mitigate, replace, and/or restore wetlands that  are affected by the remedy.
838
                                               -7-

-------
75.    What measures/criteria were used to compare alternatives?           \
                                        'r      '      '                     \
                                                   • • -                    \
       The following measures were used to compare the alternatives:       _|
    '                       •                ..  •                  •-(•-.
               Cost-effectiveness                                    ,
               Percentage risk reduction                                   I
            .          .            ...               . ,      •    '  ,      'I;     •     "  "

16.    How are measures compared?                                      j               ;

       The remedial actions for soil and sediment were chosen because they adequately reduce risk
       and are cost-effective.  The primary concern at the site was the  contamination of ground water
       through leachate generation and ground water contact with the waste mass.  Because the waste
       mass is so large, it could not be excavated and treated.  Thus containment was the only option.
       Though the multilayer cap  would provide a more effective barrier to precipitation, its increased
       effectiveness due to reduced infiltration, would not be significant because the waste mass
       would be in contact with the ground  water.  Also, the multilayer cap costs twice as much as
       the selected alternative; Of the two proposed sediment remediation  alternatives, the chosen
       alternative also was cost-effective since it provides equal risk reduction! for less cost.
17.    What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?

       Technical considerations were primary in the selection of a remedy. Because of the site's
       large size, containment was the only feasible alternative which did not iequire the excavation
      . of soil and waste materials.                                        '                .
                                                                                              889

-------
                            Twin Cities Air Force Reserve Base
                               (Sma!1 Arms Range Landfill)

                                    Minneapolis, Minnesota
                                           Region 5
  GENERAL SITE INFORMATION
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (mg/kg)

Antimony 26
Arsenic 13
2-Butanone 25
Magnesium 10,800
Nickel 191
Selenium 161

Site History
,
NPL Proposed: N/A
NPL Final: 1987
FS: 6/91
ROD: 3/92

Background

Federal Facility
PRPs: UiS. Air Force
FS prepared by: Engineering-Science,
Inc.

 2.     What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      17,000 cubic yards of waste in landfill


 3.     What type of site is this?

        Industrial Landfill.  An inactive industrial landfill bordered by an airport and a firing.range.


 TECHNOLOGY SELECTION

 4.     What standard technologies were considered for selection in this FS?

        Standard technologies considered during  the identification and screening of technically feasible
        technologies were:
                             Fencing, deed restrictions
                             Capping (single layer, multilayer)
Access restriction:
Containment:
Chemical treatment:    Fixation/stabilization
Thermal treatment:     Incineration
Disposal:
                            Excavation, disposal (on-site, off-site)
890
                                            -1-

-------
Was-an innovative technology considered in the FS?  If so, which technology?

Innovative technologies considered during the identification and screening of technically
feasible technologies were:                                  ,            ,
                                                                 •i •/''''
Biological treatment:   In situ biodegradation, composting/windrowingl land farming, soil
                      slurry, liquid-soil contact digestion
Phys/chem treatment:  Solvent flushing, in situ air stripping, soil washing, oxidation
Thermal treatment:     In situ vitrification,  in situ steam stripping
What was the cost estimate for the innovative technology?                                  ;
                                •                       .          'i
During the initial screening process, in which technically feasible technologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
implementability, and cost) to  identify alternatives that merit a more detailed evaluation.  The
estimated costs are then recalculated during an evaluation  based on nine criteria established by
the NCP.  No innovative technologies were incorporated into remedial alternatives, s
How did the cost(s) compare to standard technologies?              |

          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)
Alternative
RAA-1 •
RAA-2
RAA-3
RAA-4
RAA-5A
RAA-5B
RAA-6A
RAA-6B
RAA-7A '
RAA-7B
Standard Technology
No action
Natural attenuation/maintenance/ground
water monitoring
Natural attenuation/maintenance/site
access restrictions
Natural attenuation/maintenance/site
access restrictions/ground water
monitoring
Multilayer cap
Asphalt cap
Multilayer cap/ground water monitoring
Asphalt cap/ground water monitoring
In situ stabilization
In situ stabilization/ground water
monitoring
Estimated Costs
3 Criteria
$6
$704,000
$291,000
$737,000
$1,331,000
$442,000
$1,7615,000
$878,000
$1,958,000
$2,394,000
9 Criteria
* $0 .
$704,000
eliminated
$737,000
eliminated
eliminated
$1,766,000
.$878,000
eliminated
$2,394,000
                                       -2-
831

-------
Alternative
RAA-8
. Standard Technology
Excavation/off-site disposal
Estimated Costs
3 Criteria
$10,500,000
9 Criteria
$10,492,000
  8.      If a standard technology was chosen, why?

          The selected remedy, RAA-4, consists of natural attenuation of ground water contamination,
          access restrictions, site maintenance, and monitoring. Access restrictions and site maintenance
          achieve the objective of protecting public health and the environment from contact with
          landfill contaminants by inhibiting the completion  of exposure pathways.  The baseline risk    ,
          assessment indicated that air, soil, ground water, and surface pathways are currently not
          complete because of the lack of VOCs release, lack of surficial soil contamination, the location
          of the site within a semi-restricted area, limited access to the storm water  pond, no significant
          surface water contamination, and no current users of ground water at the site or down gradient
          of the site.  The selected remedy also provides protection against future, exposure through
          access and deed restrictions. Access restrictions include a physical barriers constructed around
          the site perimeter to restrict public access to the landfill surface. Deed restrictions limit future
          development of the site, even if the property is relinquished by the US AF.  It is probably the
          most effective option in the short-term because it can meet the responsiveness objectives in 1
          year through natural attenuation and minimal adverse impacts resulting from implementation.
          It will not require excavation or capping and therefore poses no short-term risk to site workers
          due to the release of VOCs.  It is the easiest alternative to implement since it requires little
          site work.  Site maintenance will be conducted to ensure the integrity  of the existing soil
          cover, the fence, and the monitoring system.  It is expected to meet ARARs and  is cost
          effective.                                                                    \
  9.      If an innovative technology was chosen, why?

         An innovative technology was not selected.
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation. ~
                                                                                        (
         Innovative technologies eliminated during the initial screening include the following:

         •      Solvent flushing was eliminated because the landfill debris might retard the flow of
                solvent resulting in incomplete solvent removal.  Significant risks would exist from the
                loss of solvents to the environment.
         »      In situ air stripping was eliminated because site characterization data do not  indicate a
                significant source of volatile organics  in the landfill.
822
                                                -3-

-------
       •      Soil washing was eliminated because the process requires excayation of all landfill
               debris, much of the debris might not be amenable to treatment, and contaminated
               materials might make up only a small percentage of the volume to be treated.
       •      Oxidation was eliminated because site characterization data indicate that organics were
               detected at relatively low concentrations which posed no threatj at Ihe site and might
               therefore not require treatment.  Furthermore, landfill debris might inhibit the
               introduction of oxidant to the subsurface, resulting in incomplete treatment.
       •      In situ steam stripping was eliminated because site characterization data do not
               indicate  a significant source of volatile organics in the landfill.         '
       •      In situ biodegradation was eliminated because the landfill debris might impede the
               flow of water and nutrient mix and prohibit complete remediation.
       •      Composting/windrowing was eliminated because flooding at the site precludes its use
               since soils undergoing treatment could be flooded. Additionally, contaminated landfill
               materials generally would not be soil only and would not be amenable to this
               approach. The land ban issue might also make this applicable itp only portions of the
               waste.                                                     I
       •      Landfarming was eliminated because flooding at the site precludes its use  since soils
               undergoing treatment could be flooded.  Additionally, contaminated materials in  a
               landfill generally would not be soil only and would not be amenable to this approach.
               The land ban issue might also make this applicable to only portions of the waste.
       •      Soil slurry was eliminated because it would require excavation] most of the debris
               would hot be amenable to treatment, and contaminated materials might make up  only a
              .small percentage of the total volume that would be treated. The land ban issue also
               might make this applicable to only a portion of the waste.
       •      Liquid-solid contact digestion was eliminated because the process requires make-up
               water through out the process and offgases must be treated by carbon adsorption.
               Additionally, contaminated landfill materials generally would not be soils only and
               would not be amenable to this approach. The land ban issue may also make this
               applicable to only portions of the waste.
       •      In situ vitrification was eliminated because landfill debris might impede penetration by
               electrodes and  deflect energy transfer resulting in incomplete treatment.  Much of the
               landfill debris might not be amenable to treatment and contaminated material and soil
               might make up only a small  percentage of the total volume thai would be treated.
               Costs would be excessive compared to other options.          '               ,

       , Innovative technologies eliminated during the screening of the three criteria include the
       following:

       • ;      None           '     "                    -          • ' .    !.     • •          •  .  •

       Innovative technologies eliminated during the detailed analysis include the following:

       •   .   None                                                     !
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedial  alternative v/ere protection of
       human health and the environment, short-term effectiveness, and cost. jThe selected remedy
                                              -4-
893

-------
          was preferred because it adequately addresses the protection of human health and the
          envkonment in a cost-effective manner.  Furthermore, it does not pose short-term risk to site       ^^   )|
          workers because it does not require treatment.                                                        --*


   12.     What cleanup goals were selected? If the cleanup goal wds based on an ARAR,  what was that
          ARAR?  What risk level was selected to establish cleanup goals?

          Cleanup levels were not established.


   13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          •      None

          Standard technologies eliminated because of cleanup goals include:

          •      None


  14.     Were treatability studies conducted on the innovative technology or standard technology?

          Treatability studies were not conducted.                       .                                .  ^UP  |


  75.     What measures/criteria were used to compare alternatives?

          The following measures were used to  compare the alternatives:

               Risk level achieved
               Cost/unit risk
               Time to design/construct/operate


  16.    How are measures compared?

         The selected alternative was preferred  because it will remediate the site in the same time, or
         possibly less, than other alternatives. The selected alternative also will reduce site risk in the
         long-term as well as other alternatives without posing any short-term risks. .Other treatment
         alternatives were not preferred because they might pose short-term risk during treatment, they
         would cost more, and they would not provide any greater reduction in risk.
                                                                        '   .
  17.     Wliat technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection of the remedy?




894
                                               -5-   .                     .  '.
                                                                                                              , i

-------
                                    Verona Well Field
                                           OU-2

                                   Battle Creek, Michigan
                                          Region 5
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil(mg/kg)

        1,2-Dichloroethane           2.4
        1,2-Dichloroethene (cis)       0.69
        1,2-Dichlproethene (trans)     0.69
        Ethylbenzene                0.75
        Methylene Chloride        '  1.4 '
        Tetrachloroethene            2,100
i       Toluene                     0.43
        1,1,1-Trichloroethane         0.62
        Trichloroethene              1,100
        Xylenes                     2.4
             Site History
                  •i
NPL Proposed:     'j   N/A
NPL Final:           7/82
FS:          '     >   2/91
ROD:             ]   6/91
                  I'      '
             Background

EPA Fund-lead     !
PRPs:  Thomas Solvent Company, Grand
       Trunk Western Railroad
FS prepared by:  CH^M Hill*
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      Approximately 62,000 pounds of contaminated soil
3.      What type of site is this?                                        .              "

       Chemicals and Allied Products. The site contains the Verona well field[ the Grand Trunk
       Western Railroad (GTWRR) Marshalling Yard, the GTWRR paint shop! the Thomas Solvent
       Raymond Road facility, and the Thomas Solvent Annex (the Annex) facility. The Battle
       Creek River flows through the site in a southwesterly direction. The GTWIiR paint shop and
       the Annex are the focus of this FS. The site is located in the northeast  corner of the city of
       Battle Creek and is surrounded by undeveloped land.
                                            -1-
                                    835

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
        Chemical treatment:
        Physical treatment:
        Thermal treatment:
        Disposal:
Deed restrictions, fencing
Capping (native soil, clay, synthetic membranes, sprayed asphalt,
asphaltic concrete, concrete, multilayered, chemical sealants/
stabilizers), surface controls (surface seals, grading, soil stabilization,
revegetation,  diversion/collection system), vapor suppression (foam
caps, portable dome)
Neutralization, precipitation
Excavation
Incineration                                    .
RCRA landfill, replacement
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Slurry bioreactors, land treatment, in situ bioreclamation
        Chemical treatment:   Soil flushing, oxidation/reduction
        Physical treatment:    Permeable treatment beds
        Thermal treatment:    Vapor extraction, vitrification, wet air oxidation, pyrolysis
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. For this case, the estimated costs are Calculated during an evaluation based on nine
       criteria established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)           .
Alternative
RAA-4
RAA-6
Innovative Technology
.Soil vapor extraction/modified blocking
well system/air and soil monitoring
Soil vapor extraction/ground water
treatment/air, soil, surface water, and
ground water monitoring
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$9,300,000
$15,300,000
 896
                                              -2-

-------
Alternative
RAA-8
Innovative Technology
Soil vapor extraction/ground water
treatment/in situ biological treatment/
air, soil, surface water, and ground
water monitoring
Estimated Costs
3 Criteria
' N/A
I
' i
9 Criteria
$15,800,000
7.     How did the cost(s) compare to standard technologies?
1 Cost Estimates for RAAs That Include Standard Technclogfes
(selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-5
RAA-7
Standard Technology
No action/continued operation of
existing blocking wells and air stripper
Modified blocking wells
Ground water collection and treatment
Soil excavation arid incineration/
modified blocking well system/air and
soil monitoring
Soil excavation and incineration/ground
water treatment/air, soil, surface water,
and ground water monitoring
Estimated Costs
3 Criteria
N/A ;
N/A
N/A
• N/A
N/A :-
9 Criteria
$2,500,000
$6,600,000
$11,700,000
$26,000,000
$31,100,000
8.      If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?
                                                                        i              ,
       RAA-6 was chosen because it is the least costly alternative that will provide protection from
       all identified current and future pathways of exposure to contaminated [soils at the site.  The
       proposed source treatment, soil vapor extraction (SVE), will reduce site soil contaminants.
       Source treatment in conjunction with ground water treatment will permanently reduce site risks
       to below 10"6. SVE was preferred because it would eliminate a greater volume of contaminants
       than other alternatives; therefore, it was considered very effective in the long term. This
       alternative also was preferred because it minimizes the time to reach soil and ground water
       remediation levels and it minimizes short-term risk.  SVE will be easily Implemented and
       equipment is readily available. SVE is a proven technology and has been successfully
       implemented at the Raymond Road source area, a part of the Verona \Vell Field site.
                                              -3-
                                                                                           897

-------
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the following:

         •      Slurry bioreactors were eliminated because the technique would not be applicable to
                sandy and VOC-contaminated soil.
         •      Land treatment was eliminated because it would not be applicable for VOC-
                contaminated soil (anaerobic treatment is needed for tetrachloroethene).
         "      Permeable treatment beds were eliminated because the technique would not be
                applicable to site contaminants.
         •      Vitrification was eliminated because the  technique would not be suited for site
                contaminants  and conditions.              .
         •      Wet air oxidation was eliminated because it would not be suited for site conditions.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •       Soil flushing was eliminated because its effectiveness in meeting the soil remediation
                action objectives has not been demonstrated. Soil  flushing is an emerging technology
                and there are few full-scale examples where it has achieved the low-level residual
                concentrations of organic contaminants reached by other process options.  The cost and
                technical difficulty of soil flushing were  also a concern.
        "       Pyrolysis was not included in any RAAs but was mentioned as a process that might be
                reconsidered in the design phase.
        •       Oxidation/reduction: was eliminated because toxic degradation products would be
                formed and it would be relatively expensive.  Furthermore, its effectiveness is       '
                uncertain because chlorinated compounds have a low oxidation reactivity and might            •    '
                require a catalyst that would necessitate in situ soil mixing, which is not commonly                 '
                employed.                                          _

        Innovative technologies eliminated during the detailed analysis include the following:

        »      Bioreclamation was eliminated because its effectiveness in treating chlorinated VOCs
               has not been demonstrated on a full-scale basis. Technical problems could cause
               delays or result in additional problems. Furthermore, a limited number of contractors
               are available to do the work. Permission would be needed from the State of Michigan              '
               to inject nutrients and substrates  into the  aquifer.                 '    ,


77.     Wh^h of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in  the elimination of the innovative technology?  If so,                '
        which criterion? Which of the criteria supported the  use of a standard technology?       '                !

       The criteria weighted most heavily in selecting the technology were protection of human health      (fife ),
       and the environment, ability to meet ARARs, short-term effectiveness, implementability, and         ™^

  898                                                                                                     1
                                 .    •         -4-                 .         •            •       •           •   !'

-------
       cost.  RAA-4 (the preferred alternative) is protective of public health and the environment in
       both the long- and short-term, meets ARARs, is easily implemented, aiid is the least expensive
       of the treatment alternatives. RAA-2 uses the same soil remediation technology as RAA-4
       (vapor extraction), but does not directly address ground water contamiriaticin and thus will not
       meet ground water ARARs,  RAA-6, which employs bioremediation, vras eliminated because
       of the technical difficulty in implementing the solution and because it lias not been
       demonstrated on a full-scale basis.  RAA-3 is costly, does not meet ground water ARARs, and
       poses potential short-term health risks due to possible fugitive VOC eniissions during soil
       excavation. RAA-5 is also costly and poses potentially serious short-tejrm health risks.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?      \
Contaminant
Cleanup Level (ng/kg)
ARAR or Other Basis
Carcinogens
Benzene
Carbon Tetrachloride
1,1-Dichloroethane
1 , 1 -Dichloroethene
1 ,2-Dichloroethane
Methylene Chloride
Tetrachloroethene
Trichloroethene
20
- 10
20
10
10
100
10
60
Michigan Act 307"
Federal TCLF*
Michigan Act 307
Federal TCLP
FederalTCLP
Michigan Act 307
FederalTCLP
Michigan Act 307
. Michigan Act 307
Michigan Act 307
Michigan Act 307
Noncarcinogens
1 ,2-Dichloroethene
(cis)
1 ,2-Dichloroethene
(trans)
Ethylbenzene
Toluene
1,U-
Trichloroethane
Xylenes
20
2,000
1,400
16,000
4,000
6,000
Federal TCLP
Michigan Act 307
Fedeiral TCLP
Michigan Act 307
Michigan Act 307
Michigan Act 307
Federal TCLP
Michigan Act 307
Michigan Act 307
              "Concentrations in soil that
              concentrations greater than
would be expected to leach into ground water at
Michigan Act 307 ground water cleanup limits.
                                            -5-
                                                     899

-------
                ""Concentrations in soil that would be expected to leach into ground water at
                concentrations greater than the ground water goals based on U.S  EPA TCLP
                procedures (40 CFR 261).
                                                                   •         •         '       -
        Cleanup levels for carcinogens would result in an excess upper bound individual lifetime
        cancer risk of no more than W6.  For noncarcinogens, cleanup levels would result in. a Hazard
        Index less than or equal to  1.0.
                                                                 /       ,                  . '
                                                                                  -

 13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        H       None

        Standard technologies eliminated because of cleanup goals  include:

        •       None
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Vapor extraction has been successfully implemented at the Raymond Road facility., a part of
        the Verona Well Field site addressed in a previous FS. A pilot study will be conducted prior
        to design of the vapor extraction system for the GTWRR Paint Shop and Annex locations


 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

        •    Cost-effectiveness
        •    Proven reliability
        •    Impact on nearby populations
        •    Time to design/construct/operate
                                                                -     , .,  •

 16.     How are measures compared?
                                 '         '                      •                           •
        RAA-6 was preferred for several reasons.  First, it would minimize short-term risk.  Other
        alternatives, RAA-5 and RAA-7, would have had greater potential for community exposure to
        VOCs because they require excavation.  Second, RAA-6 would more rapidly meet ground
        water cleanup levels (20-30 years) because ground water is remediated at the source. Other
        alternatives, RAA-4 and RAA-5, would take more than 50 years to meet ground water cleanup
        levels because the ground water would be treated downstream^  Third, SVE was preferred over
        incineration because it would be more easily implemented. Incineration was expected to have
        significant technical and administrative requirements for setup;! Incineration also would be very
        costly.  SVE was preferred over bioremediation because it is a proven technology.
        Bioremediation was eliminated because it has not been shown to be effective in remediating
        many of the site contaminants, it would require extensive  testing  prior to startup,  and there

soo
                                              -6-

-------

17.
       would be numerous administrative requirements associated with injection of nutrient into the
       aquifer.  In addition/only a limited number of experts are available to implement
       bioremediation.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?
                                          -•                      \. •

While none of the developed alternatives were eliminated solely for technical or site-specific
reasons, these factors did play a minor role in evaluating some of the alternatives. Site
conditions were favorable for the use of vapor extraction (RAA-4). Vapor extraction works
best in sandy soils and for treating contaminants with Henry's constants greater than 10"4
atmosphere per mole per cubic meter. Both of these conditions are met "at:  the Verona site.
                                             -7-
                                                                                            901

-------
                                  Zanesville Well Field

                                       Zanesville, Ohio
                                          Region 5
GENERAL SITE INFORMATION
/.      What were the principal contaminants,
        contaminant levels, and m>
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil (mg/kg)

        Lead
        Trichloroethylene
        1,2-Dichloroethylene (total)
        Barium
        Copper
        Cadmium
        Manganese
        Zinc
        Mercury
minants,
addressed in

rincipal



5,660
170
16
604
384
11
1,730
4,310


NPL
NPL
FS:
ROD




Proposed
Final:

:



Site History
: N/A
9/8/83
7/12/91
9/30/91
Background

PRP-lead ,
PRPs

: United
Inc.
Technologies Automotive,

FS prepared by: Geraghty and



Miller,


Inc.


4,130
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      37,800 cubic yards of soil
3.     What type of site is this?

       Industrial Landfill. The site includes the Zanesville well field and a manufacturing facility  ,
       owned by United Technologies Automotive, Inc. (UTA).  A former bulk solvent storage tank
       and two large storm sewer basins are located on the site.                                >
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:     Deed restrictions, security fencing, warning signs
 902
                                            -i-

-------
        Containment:

        Chemical treatment:
        Physical treatment:
        Thermal treatment:
        Disposal:
                                                                         ,1
                              Capping (soil, multimedia, and asphalt), synthejtic liner, slurry walls,
                              grouting, sheet piling, bottom sealing   .. •   \
                              Solidification                               (
                              Mechanical aeration, soil washing (aqueous)  i         .  • >
                              On-site incineration, off-site incineration     '
                              On-site RCRA landfill, off-site RCRA Subtitle D or C landfill
5.
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological-treatment:  Anaerobic bioreclamation, treatment beds      !
        Chemical treatment:   Soil flushing (chemical), chemical oxidation, hydrolysis, solvent
                             extraction                                    !
        Thermal treatment:    In situ vitrification, in situ vapor extraction     !
6.
       What was the cost estimate for the innovative technology?            \

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. Afller the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness
       implementability, and cost) to identify alternatives that merit a more detailed evaluation 'The
       estimated costs then are recalculated during an evaluation.based on the kne criteria established
       by the NCP.                           ^                            !
                                    ,  .    .   "                            i      -

                Cost Estimates for RAAs That Include Innovative Technologic
                           (selected remedial alternative is in bold)
Alternative
RAA-4
RAA-6
RAA-7
,'
Innovative Technology
In situ vapor extraction
Soil washing (aqueous)/sludge
disposal '
In situ vitrification
Es
3 Crit<
timated Costs
:ria
$896,SOO
$667,4
$29,286
00
,200
9 Criteria
$896,500
$667,400
$29,286,200
                                             -2-
                                                                                           903

-------
7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2 .
RAA-3
RAA-5
Standard Technology
No action
Multimedia cap/excavation/disposal
Excavation/off-site landfill disposal
Excavation/off-site incineration
Estimated Costs
3 Criteria
$0
$210,200
$8,325,000
$10,575,000
9 Criteria
$0
$210,200
$8,325,000 '
$10,575,000
                                                                                                  :3
8.     If a standard technology was chosen, why?

       A standard technology was not selected.


9.     If an innovative technology was chosen, why?

       The selected remedy included treatment of soil and source areas contaminated with VOCs by  .
       in situ vapor extraction, and; soil washing of soil contaminated  with inorganic compounds.
       Soil vapor extraction was selected because: 1) chemical characteristics of TCE favors use of
       soil vapor extraction, 2) sand-silt soils are permeable enough for air flow for applied vacuum
       conditions, 3) soil vapor extraction influences a broad area, and its effectiveness is not effected
       by  local concentration variations within the area, 4) although a pilot soil vapor extraction
       system was  unsuccessful,  modifications would increase extraction  rates, 5) soil vapor
       extraction will reduce potential for exposure to volatile organic  chemicals during excavation of
       inorganics, 6) will reduce contaminants leaching into ground water, &) equipment and services
       are readily available, 8) cost.  .
                                                                         i
       Soil washing was selected because: 1) it reduces exposure by reducing waste volume and
       removing the source, and  2) cost.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

"      Anaerobic bioreclamation was eliminated because its effectiveness would be limited
       due to the presence of chlorinated organics and inorganics, which biodegrade slowly.
       Also, there has been no effective full-scale application of anaerobic bioreclamation.
 904
                                              -3-

-------
11.
»      Treatment beds (walls) were eliminated because it is only suitable for shallow ground
        water tables, because a trench must be excavated to the bottom of the contaminated
        aquifer and ground water at this site is too deep.              |
"      Chemical oxidation (in situ) was eliminated because little infontnation is available
        regarding the application of chemical oxidation for in situ stabilization of organic
        wastes.  Other treatment technologies are better suited for the cheirucals of concern at
        the site.
•      Hydrolysis (in situ) was eliminated because the technology is still in the developmental
        stages for use at uncontrolled hazardous waste sites.  .In addition, the injection of
        chemicals into the potable aquifer was  not recommended.
•      Solvent extraction was eliminated because it would be difficult to implement and
        costly to operate.
                                                                   [
                                                            •  ' '    I-             (  ,
Innovative technologies eliminated during the screening of the three  criteria include the
following:                .                          ,                  ,
                                                       -•.-!-
•      Soil flushing was eliminated because the process could redistribute existing constituents
        in soil such that a larger soil mass requires subsequent remediation. Verification of
        the effectiveness of this  process would  require the collection of a large number of soil
        samples.  Flushing could cause further  contamination of the ground water.

Innovative technologies eliminated during the detailed analysis include the following:

•      In situ vitrification was eliminated because of the high cost to implement the
        technology.  Also, if the remedy fails (e.g., constituents are found which leach out  of
        the vitrified material), corrective measures would be extremely expensive.
                                                                   [
                       -  -  '     '  •             -              '     i "'  '
Which of the nine criteria were  weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard] technology?

The criteria weighted most heavily in selecting innovative and standard technologies included
cost, long-term effectiveness and permanence,  and reduction in toxicity, mobility, and volume
of contaminated materials. In situ vapor extraction and soil  washing together will reduce the
toxicity of contaminated soils at a  cost far below that of the other treatment: options, off-site
incineration and vitrification.
72.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens ,
Trichloroethylene
cis-1,2-
Dichloroethylene
0.0063
0.034

Leachability" Model
Leacha
bility Model
                                               -4-
                                                                                              905

-------
Contaminant
trans-1,2-
Dichloroethylene
Cleanup Level (mg/kg)
0.059
ARAR or. Other Basis
Leachability Model
Noncarcinogens
Lead
Cadmium
Barium
Copper
Manganese
Zinc
12
4
77
315
771
1,410
Risk
Risk
Risk
Risk
Risk
Risk
               The Summers model was used to calculate soil cleanup levels based on meeting
               established MCLs.

        For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10"6
        was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.


13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?
                                                        *
        Innovative technologies eliminated because of cleanup goals include:

        •      None

        Standard technologies eliminated because of cleanup goals include:

        •      None        .                  •      .                             ,


14.     Were treatability studies conducted on the innovative technology or standard technology?
                                                       1.    .           ,                i
        A pilot vapor extraction system was previously installed by UTA near a drum storage area.
        Due to the low levels of VOCs removed by this system, it was eventually shut down. Vapor
        extraction is still considered a viable technology for this site because it may be possible to
        increase extraction rates by installing a modified system such as one utilizing horizontal slotted
        pipe, rather than well  screens. Such a system could collect VOCs from a larger area than with
        wells.                            -                                       ,
75.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:
                                                  \
       •      Cost-effectiveness

   906

-------
               Impact on workers and nearby populations
               Preference for treatment (vs. containment)
16.    How are measures compared?

       Cost-effectiveness and preference for treatment over containment or disposal were the most
       important measures used to select the preferred remedial alternatives.  Vapor extraction (RAA-
       4) in conjunction with soil washing (RAA-6) were considered the mosjt cost-effective
       alternatives as a result of their ability to treat most of the organic contaminants and remove
       inorganic contaminants from soils at a relatively low cost.  The other :five alternatives either
       did not treat contaminated soils or were not as cost-effective.  RAA-4 and RAA-6 also were
       selected because they would create no additional short-term risks for \yprkers and nearby
       residents during implementation.                                  j

                                                                       i  •    •'.'•'.
17.    What technical considerations were factors in selecting a remedy? W&re technical
       considerations primary in the selection of the remedy?              -
                                                                       i                •
                                                                       i
       Technical considerations were not primary in selecting a remedy. Some technical
       considerations and site specific conditions were a factor, however, in eliminating some
       innovative technologies  during the initial  screening of alternatives. Fcjr example, the
       considerable depth of ground water at the site made  the use of treatment beds infeasible, since
       a trench must be excavated to the bottom of the contaminated aquifer.
-6-
                                                                                            907    -     -

-------
                               Cimarron Mining Corporation
                                            OU-2

                                    Carrizozo, New Mexico
                                           Region 6
 GENERAL SITE INFORMATION

 L     What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil/Sediment (mg/kg)

        Lead  (tank sediment)        46,400
        Lead  (waste piles)           18,900
        Lead  (surface soil)           10,409
 2.      What volume of material is to be
        remediated?
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
6/24/88
10/4/89
N/A
9/91
             Background

EPA Fund-lead
PRPs:   N/A
FS prepared by: CDM Federal
       Programs Corp.
        The volume of material to be remediated included:

        •     43 cubic yards of tank sediment
        •     182 cubic yards of material soil and rock
        «     345 cubic yards of discharge pit sediment arid site soil
3.     What type of site is this?

       Mining. An inactive milling facility in a rural area.
TECHNOLOGY SELECTION

4.      Wliat standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                             «»««c

       Access restriction:     Fencing, deed notices, zoning ordinances, temporary resident relocation
       Containment:          Capping, dust control
       Chemical treatment:    Neutralization, solidification
       Thermal  treatment:     Smelting
       Disposal:             Excavation, disposal (on-site, off-site)                       r

  90S
                                            -i-

-------
5.
Was an innovative technology considered in the FS?  If so, which technology?
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:      ,                                  i

       Biological treatment:    Biodegradation                             |
       Chemical treatment:    Soil washing, soil flushing, hydrometallurgical reprocessing
       Thermal treatment:     In situ vitrification, pyrolysis
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, estimated costs were calculated during an evaluation based on nine
        criteria established by the NCP. No innovative technologies were incorporated into RAAs.
       How did the cost(s) compare to standard technologies? .             I

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Institutional controls
Cement solidification/stabilization/
on-site disposal '
Cement solidification/stabilization/off-
site disposal
Off-site municipal and hazardous waste
landfill disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
< $48,000 ,
$119,000
$79,000
$235,000
$344,000

        If a standard technology was chosen, why?
                                                                 ' ''   •'  ' L  .     "   ,    •''.''
        RAA-3 was chosen because it is highly protective of human health and the environment, since
        wastes will be treated to the extent practical. Stabilization of soil and waste pile material with
        lead concentrations exceeding 500 ppm provides protection to human health and the
        environment by reducing the mobility of lead in the soil and its potential for contaminating
        ground water.  Treatment also ensures that the waste will not be a "significant" ingestiori or
        inhalation risk.  Hazard Indices for noncarcinogens will be less than 1 upon completion of this
        remedial  action.  Implementation of this alternative does not pose any short-term risk or cross-
        media impacts.  This alternative achieves compliance with all ARARsl  A high degree of long-
                                               -2-
                                                                                        909

-------
        term effectiveness and permanence will be achieved.  Stabilization is the "state-of-the-art
        technology" for immobilizing metals and has been utilized effectively for many years. This
        alternative reduces the toxicity and mobility of the waste through treatment.  Durability test are
        being conducted on the solidified material as part of the bench-scale treatability tests.  This
        information  will be utilized to determine the necessary optimum mixture ratios to ensure the
        long-term effectiveness of this option.  Implementation of this alternative should provide a
        reasonable degree of short-term effectiveness, provided appropriate precautions and dust
        control measures  are instituted during the remedial phase.  Implementation of this alternative is
        possible without undue technical or administrative difficulty. The selected alternative will be
        readily implemented since no special technologies are required and the remedy utilizes typical
        construction techniques.  This alternative is cost effective.
9.      If an innovative technology was chosen, why?

        An innovative technology was not selected.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      Soil washing was eliminated because the equipment requirements to implement this
               technology are substantial — greater than for other feasible soil treatments (e.g.,
               fixation); a separate liquid waste stream would be created; and its effectiveness can not
               be properly  evaluated without bench- and pilot-scale tests. Given the relatively small
               volume of material present at the site and the process's complexity and high costs, this
               alternative would not be cost-effective.
       •      Soil flushing was eliminated because this process would not be feasible for some of the
               site's waste  located aboveground.  Further, the remaining waste material is
               characterized by relatively thin layers of surficial soil and this material is not
               contiguous;  thus,  installation and operation of injection and extraction wells would not
               be practical.
       »      Hydrometallurgical reprocessing was eliminated because there is an insufficient
               volume of waste material to consider implementation  of an on-site reprocessing option
               and therefore an off-site reprocessing would be necessary.
       •      Biodegradation was eliminated because treatment of metal-contaminated tailing and
               soils has not been proved in full-scale applications and, therefore, the long-term
               effectiveness of this technology is unknown; there are currently many uncertainties
               associated with this technology; and the volume of waste is  small.
       •      In situ vitrification was eliminated because it would be difficult to, implement, would
               be complex  to construct and operate, has extensive equipment requirements, and would
               produce gas side streams which would  require further treatment.  Additionally, the
               availability of services, equipment, and skilled workers for this  group is limited.  Cost
               to implement this option would be very high compared to other feasible treatment
               technologies.

910
                                               -3-

-------
                                                                        I
        •      Pyrolysis was eliminated because it would be difficult to implement, would be
               complex to construct and operate, has extensive equipment requirements, and would
               produce gas side streams which would require further treatment.  Additionally, the
               availability of services, equipment, and skilled workers for this group is limited. Cost
               to implement this option would be very high compared to other feasible treatment
               technologies.                                             '

        A three-criteria evaluation was not conducted.                      |

        Innovative technologies eliminatedr during the detailed analysis include  the following:

        •      None
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

     .   Protection of human health and the environment, long-term effectiveness, and cost were the
        criteria that were weighted most heavily in selecting a remedial alternative. L RAA-3, at the
        lowest cost, provides the greatest protection and is effective in the long term.

        In situ vitrification and pyrolysis were eliminated because they would be difficult to implement
        and costly.                                                       !
12.     What cleanup goals were selected? If the cleanup goal was based on\an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup, Level (rag/kg)
ARAR
Carcinogens <
Lead
500
1
or Other Basis

DS\yERa
               "OSWER Directive 9355.4-02, EPA 1989.
13.
Was the innovative technology eliminated because of the cleanup goats? Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:
  1  -      •     .•.      -    - •'                        .              i"          • • •   - .
•     None                                                     i
                                                                 •I1     -      ,•'••.

Standard technologies eliminated because of cleanup goals include:   !

•     None
                                              -4-
                                                                                              911

-------
 14.     Were treatability studies conducted on the innovative technology or standard technology?
                                           •                      ,
         Bench-scale tests for solidification were preformed on representative samples of site waste.


 15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:                             .

              Protection achieved
              Total cost
              Proven reliability
              Waste left in place/institutional control


 16.    How are measures compared?

        The chosen alternative was preferred because it provides the greatest amount of protection and
        it will be effective in the long term.  Institutional controls were not chosen because they would
        provide less protection to human health and no protection to the environment.  Off-site
        disposal was eliminated because it would provide only a moderate degree of protection  since
        contaminated soil would not be treated.  Of the most protective alternatives, the chosen
        alternative is the least expensive.  While solidification is a well-proven technology, soil
        washing and biodegradation were eliminated, in part because their effectiveness is unknown.


 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        No technical considerations were primary in selecting a remedial technology.  The dispersed
        waste (e.g., aboveground, below ground) made it impractical to implement some technologies
        including soil washing and soil flushing.
912
                                              '-5-

-------
                                Double Eagle Refinery Co.
                         OU-1 (Source Control Operable Unit)

                                  Oklahoma City, Oklahoma
                                          Region 6
 GENERAL SITE INFORMATION
 1.      What were the principal contaminants,
        contaminant levels, and media addressed In
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        SludgeVSoil/Sediment (rag/kg)

        Lead                       20,000
2.      What volume of material is to be
        remediated?

        The volume of material to be remediated
        included:
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
87-88
3/89
6/92
9/28/92
             Background

EPA Fund-lead    !
PRPs:  EPA has identified 17 PRPs and
       is continuing the search for other
       unidentified PRPs
FS prepared by:  Fhior Daniel, Inc.
              42,000 cubic yards of contaminated sludge, soil, and. sediment
3.     What type of site is this?

       Waste Oil. The Double Eagle Refinery (DER) collected, stored, and re|-refined used oils, and
       distributed the recycled product.  DER was active as early as 1929, and accepted waste oil for
       storage until 1980.  This site is bordered by vacant lots zoned for industrial land use
                                         -I         .                    '       "          , •  • -
                                                                      I
                                                                      "I

TECHNOLOGY SELECTION                                           ;

4.     . What standard technologies were considered for selection in this FS? I

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
    'Waste sludges at the Double Eagle site represent over 90 percent of the contaminated media to be
remediated.  Soils and sediments, therefore, will be consolidated with the waste! sludges and
remediated using a single technology rather than separate technologies for each j medium. The remedial
alternatives generated in the ROD for the waste sludges,'soils, and sediments were based on the
technologies  best suited for the remediation of the sludge material.
                                            -1-
                                    913

-------
        Access restriction:
        Containment:
        Chemical treatment:

        Thermal treatment:
        Disposal:
Deed restrictions, fencing                                ,
Capping (clay, synthetic membrane, concrete, multimedia),  vertical
barriers, horizontal barriers, sediment control, dust control,
consolidation       -
Solidification/stabilization (sorption, pozzolanic agents, encapsulation),
neutralization
On-site incineration, off-site thermal  destruction
Excavation, on-site landfilling, off-site landfilling
 5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Slurry phase treatment, solid phase treatment (biological degradation),
                              composting
        Phys/Chem treatment:  Soil washing, chemical extraction, reduction/oxidation, soil vapor
                              extraction
        Thermal treatment:     Low-temperature thermal stripping, vitrification              .'


 6.      What was the cost estimate for the innovative technology?                .             .   .

        During the initial screening process, in  which technically  feasible technologies are identified
        (prior to the formulation of RAAs),  the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process.
        (effectiveness, implementability, and cost) to identify alternatives that merit a  more detailed
        evaluation. For this site, the estimated  costs were calculated during  an evaluation  based on '" '
        nine criteria established by the NCP.

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Excavation/on-site biological
treatment/capping of residuals
Estimated Costs
3 Criteria
N/A
9 Criteria
eliminated
7.     How did the cost(s) compare to standard technologies?                       "

       The designation of RAAs changed in the ROD and the new designations are presented
       parenthetically below.-
914
                                               -2-

-------
                  Cost Estimates for RAAs That Include Standard Technologies
                 ,            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
(RAA-3)
RAA-5A
(RAA-4)
RAA-5B
(RAA-5)
RAA-7A
(RAA-6)
RAA-7B
(RAA-7)
Standard Technology
No action
Limited action/minor construction
activities/consolidation of off-site
wastes/institutional controls
Containment (no treatment)
In situ stabilization/capping
Consolidation/neutralization/on-site
stabilization/disposal in on-site landfill
Consolidation/neutralization/on-site
stabilization/disposal in off-site
landfill
Excavation/dn-site incineration/on-site
capping of ash
Excavation/off-site incineration/off-site
disposal of ash
Estimated Costs
3 Criteria
N/A
N/A
i
1
N/A
N/A
i -
' N/A
i
N/A
i
N}A
'i. .
.N/A
9 Criteria
$0
$300,000
eliminated
$5,100,000
$7,300,000 ,
$6,400,000
$32,600,000
$23,900,000
8.      If a standard technology was chosen, why?                          j             ,

       The selected alternative, RAA-5B (RAA-5), was chosen because it incorporates stabilization
       technology as a treatment process for the waste material.  The stabilization process places the
       inorganic contaminants, like lead and other heavy metals,  in a less soluble form and, therefore,
       reduces the mobility of these contaminants.  Contaminant  migration will be restricted under
       this alternative by decreasing the surface area exposed to leaching and/or by isolating the
       wastes within  an impervious capsule. The lead and organic contaminants on site will be
       stabilized to the extent that the waste will not be considered RCRA hazardous waste under
       TCLP testing.  In addition, the selected alternative involves neutralizing the contaminated
       material, which reduces the RCRA corrosivity characteristic.  Consequently, following
       treatment the waste will not be considered hazardous and may be disposed of in a RCRA
       Subtitle D facility.  Although the treatment of waste under RAA-5B does not eliminate the .
       contaminants of concern, removal of the waste material from the site isi effective in eliminating
       the human health and environmental exposure pathways for contaminants at this site.
       Implementation of RAA-5B also will minimize or alleviate the need for long-term O&M,
       monitoring, application  of institutional controls, and 5-year reviews.  The selected alternative is
       considered technically and administratively implementable. Qualified contractors to perform -
       this work are available regionally.  In addition, transportation of the waste materials to a
       permitted off-site facility will be in  compliance with the U.S. Department of Transportation
       (DOT) regulations.  Finally, treatability studies conducted  as part  of the FS (see Question 14)
       indicate that stabilization is an effective technology for the wastes at thie DER site.
                                              -3-
                                                                                            915

-------
       The Proposed Plan identified RAA-5A (RAA-4) as EPA's preferred alternative for soil, sludge,
       and sediment contamination. At the same time, EPA requested the preference of the State of
       Oklahoma regarding the Proposed Plan.  The Oklahoma State Department of Health (OSDH)
       indicated that they preferred RAA-5B (RAA-5). OSDH cited the lower cost of the remedy and
       subsequent lower state match.  As a result of state and general public comments, EPA selected
       off-site landfill disposal rather than on-site landfill disposal.
9.     If an innovative technology was chosen, why?
                                    '
       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated  during the initial screening include the  following:
                                                                                ,
       "      Chemical extraction was eliminated because this technology is not proven for soil or
               sludges.
       •      Low-temperature thermal stripping was eliminated because it would not be applicable
               to this site since this technology only is effective for highly volatile organics.
       "      Reduction/oxidation was eliminated because it would not be applicable for
               concentrated organic waste  streams.
       "      Slurry phase treatment was eliminated because it would not be applicable due to the
               metal content in soil and sludge.
       •      Soil vapor extraction was eliminated because it would not be applicable to heavier
               weight petroleum compounds.

       Innovative technologies eliminated  during the screening of the three criteria include the
       following:                            .                       ,

       •      Soil washing was eliminated because it would not be effective for  combined organic
               and metal wastes.  In addition, high organic wastes would cause problems for soil
               washing systems, which would affect implementability.
       •      Composting was eliminated, but no specific reason was given.  Although it is
               potentially effective, this technology is not commonly applied to soils with
               hydrocarbons and process development might be required prior to implementation.
       •      Vitrification was eliminated but no specific reason was given. The FS states that the
               technology  is not proven on a full scale and it has high capital costs.  The FS also
               states, however, that this technology is very effective in the destruction of organics.
       •      Biological degradation was eliminated because this technology  would not reduce  or
               eliminate the toxicity or mobility of inorganic contaminants, such as heavy metals. In
               fact, the presence of high concentrations of heavy metals in a waste stream would
               inhibit biological activity. Considering the contaminant of concern at this site  is lead,
               biological treatment would  not be an effective remediation alternative.  In addition, this
               technology  would not be implementable because of the constraints of available area, at

                          .
                                           .   '-4-            '

-------
               the site to construct and conduct a land farming operation. The FS states, however,
               that for wastes associated with the oil refining industry, neutralization and biological
               treatment have been shown to be effective, and the ability of thus alternative to reduce
               organic waste toxicity, mobility and volume has been documented.

        Innovative technologies eliminated during the detailed analysis include the following:
                   -  -.          • •           '       •                       i •  -      '
        •      None         ,                        ••'••„..•      !
 11.
                                                                  |.         '
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Which of the criteria supported the use of a standard\ technology?

State and community acceptance, and cost were significant criteria in selecting a remedy  in the
Proposed Plan. EPA had selected an alternative involving on-site landfill disposal;  however,
as a result of state and general public comments, EPA finally  selected instead a remedy
incorporating off-site landfill disposal.  The state of Oklahoma prefers the off-site landfill
disposal alternative because it is less costly than EPA's proposed remedy. RAA-5B also  has
the advantage of saving the state the cost of perpetual operation  and mziintenance of the site.
In addition,  of all the alternatives evaluated for the contaminated sludge-Is, soils, and sediments,
the selected  alternative provides the best overall protection to human .health and the
environment with no unacceptable short-term risks.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
     ,   ARAR?  What risk level was selected to establish cleanup goals?
                     Contaminant
                                 Cleanup Level (ppm)
ARAR or Other Basis
                 Carcinogens
                 Lead
                 PAHs
                 PCBs
                                          500
                                          30
                                          25
                                                                        OSWER3
       TSCA"
                                                                       Risk based0
               "OSWER guidance on industrial land use.
               'Toxic Substances Control Act cleanup level for industrial land iise.
               The cleanup level represents a 10'5 excess cancer risk and was selected based on
               regional guidance for setting remedial goals for PAHs.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •       None                         .   '  .
                                              -5-
                                                                                                917

-------
       Standard technologies eliminated because of cleanup goals include:                                  _

                                                                                                            >
       •      None                                                                                      -~"[
                                                                                                           1  j
                                                                                             >

14.    Were treatability studies conducted on the innovative technology or standard technology?
                                                                                                             \
       The ROD states that treatability studies were conducted as part of the FS to determine if,                   j .
       stabilization/solidification is an effective technology for the wastes' at the DER site.  The,
       results of these studies indicate that this treatment is effective because  following treatment,                 1
       none of the TCLP chemicals were detected above their respective TCLP regulatory levels (40
       CFR Part 261.24).

       The information above on treatability studies was obtained from the ROD. The FS did not
       discuss these studies.

                                                                "
                                                                          '             '
15.    What measures/criteria were used to compare alternatives?                                 .  '

       The following measures were used to compare the alternatives:

             Risk level achieved
             Cost-effectiveness                                            .
             Proven reliability                                                       .            •
             Preference for treatment (vs. containment)
                                                                                     .
                                   -
16.    How are measures compared?

       The chosen remedy involves the "ultimate" removal of the waste material from the site,
       thereby eliminating the human health and environmental pathways of exposure to contaminants
       at this site.  The chosen alternative is cost-effective as it offers a degree  of protection similar
       to on-site landfilling and incineration but at a lower cost. EPA does not believe that the
       incinerator alternatives offer additional protection in line with the additional cost.  The chosen
       alternative was selected because it was known to be technically and administratively
       implementable.  Qualified contractors who perform the work required under RAA-5B are
       available regionally.  The selected alternative also will satisfy the preferences for treatment as
       a principal element of the remedy.

                                     •
                                                                             '
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection  of the remedy?

       Technical considerations were not primary in selecting the chosen remedy. Biological
       degradation was eliminated from consideration as a remedial action alternative due in part to
       technical considerations.  This technology would not be implementable at this site because of
       the constraints of available area to construct and  conduct a land farming  operation.  The on-
       site stabilization/capping alternative presented technical issues due to the uncertainty of treating
       contaminated material on site without excavating the material.                                 ,    if Hfe  \
                                               -6-

-------
                          Fourth Street Abandoned Refinery
                                          OU-1

                                 Oklahoma City, Oklahoma
                                         Region 6
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     N/A
                     3/89
                     6/92
                     9/28/92
GENERAL SITE INFORMATION
___^———————.^—^——^——^

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       SludgeVSoil/Sediment (rag/kg)

       Lead                        15,000
       What volume of material is to be
       remediated?                 >  '   •

       The volume of material to be remediated
       included:
              40,200 cubic yards of contaminated sludge, soil, and sediment
              [The ROD states that 42;000 cubic yards of material will be stabilized under Section
              X. the Selected Remedy. The FS, however, estimated 40,200| cubic yards and
              calculated costs based on this figure (see Question 3)].
             Background
   i       '       [ - -
EPA Fund-lead
PRPs:  The PRP search investigation is
       ongoing   |
FS prepared by:  FJuor Daniel, Inc.
3.      What type of site is this?         .                         ,     |     ,

       Waste Oil. The Fourth Street Abandoned Refinery (FSAR) collectedi stored, and re-refined
       used oils and distributed the recycled product. The refinery was active in the early 1940's
       through the early 1960's.  While industrial areas surround the FSAR site, the land use within a
       1-mile radius is mixed industrial and residential.  The FSAR and Double Eagle Refinery
       (DER) sites are essentially adjacent to each other, and contain very similar waste materials
       since both sites recycled used oils. Since these sites are in such close proximity and migration
       of contaminants in certain cases overlap, the ROD for the FSAR site makes  reference to the
       DER site as necessary.                                  ,
    'Waste sludges at the Fourth Street Abandoned Refinery site represent over 95 percent of the
contaminated media to be remediated.  Soils and sediments, therefore, will be consolidated with the
waste sludges and remediated using a single-technology, in lieu of separate technologies for each
medium. The remedial alternatives generated in the ROD for the  waste sludge, soil, and sediments
were based on the techniques best suited for the remediation of the sludge material.
                                             -1-
                                                                                           919

-------
  TECHNOLOGY SELECTION                        .         «    '


  4.      What standard technologies were considered for selection in this FS?


          Standard technologies considered during the identification and screening of technically feasible
          technologies were:

          SJudge/Soil/Sediment
  5.
920
         Access restriction:
         Containment:
                              Deed restrictions, fencing
                              Capping (clay, synthetic membrane, concrete, multimedia), vertical
                              barriers, horizontal barriers, sediment control, dust control,
                              consolidation
        Chemical treatment:    Solidification/stabilization (sorption, pozzolanic agents, encapsulation),
                              neutralization
                              On-site incineration, off-site thermal destruction
         Thermal treatment:
         Disposal:
                              Excavation, on-site landfilling, off-site landfilling
              an
                innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically      -
        feasible technologies were:

        Sludge/Soil/Sediment


        Biological treatment:   Slurry phase treatment, solid phase treatment (biological degradation),
                              composting
        Phys/Chem treatment:  Soil washing, chemical extraction, reduction/oxidation, soil vapor
                              extraction
        Thermal treatment:     Low-temperature thermal stripping, vitrification



6.       Wliat was the cost estimate for the innovative technology?


        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability,  and cost) to identify alternatives that merit a more detailed
        evaluation.  For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.


                Cost Estimates for  RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Excavation/on-site biological
treatment/capping of residuals
Estimated Costs
3 Criteria
N/A
9 Criteria
eliminated
                                                                                                              >
                                               -2-

-------
 7.      How did the cost(s) compare to standard technologies?        '    •'"{   •

        RAA designation changed in the ROD and the new designation is presented parenthetically
        below.                                                           ',!_'•       .
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Alternative
RAA-1
RAA^2
RAA-3
RAA-4
(RAA-3)
RAA-5A ,
(RAA-4)
RAA-5B
(RAA-5) .
-RAA-7A ,
(RAA-6)
RAA-7B
(RAA-7)
Standard Technology
No action
Limited action/minor construction
activities/consolidation of off-site
wastes/institutional controls
Containment (no treatment)
In situ stabilization/capping
Consolidation/neutralization/on-site
stabilization/disposal in on-site landfill
Consolidation/neutralization/on-site
stabilization/disposal in off-site
landfill
Excavation/on-site incineration/on-site
capping of ash
Excavation/off-site incineration/off-site
disposal of ash
Estiimated Costs
3 Criteria
N/A
;N/A '
N(A
N/A
"t
N;[A
N/A
N/A
WA
9 Criteria
$0
$300,000
eliminated
$5,100,000
$7,300,000
$6,400,000
$32,600,000
$23,900,000
8.      If a standard technology was chosen, why?

       The selected alternative, RAA-5B (RAA-5), was chosen because it incorporates a stabilization
       technology as a treatment process for the waste material.  The stabilization process will place
       the inorganic contaminants, like lead and other heavy metals, in a less soluble form and
       therefore, will reduce the mobility of these contaminants.  Contaminant1 migration will be
       restricted by decreasing the surface area exposed to leaching and/or by [isolating the wastes
       within an impervious capsule.  The lead and organic contaminants on site will be stabilized to
       the extent that the waste will not be considered RCRA hazardous waste under TCLP testing.
       In addition, the selected alternative involves neutralizing the contaminated material,  which will
       reduce the RCRA corrosivity characteristic. Consequently, following treatment the waste will
       not be considered hazardous and may be disposed of in a  RCRA Subtitle E> facility.  Although
       the treatment of waste under RAA-5B  does not eliminate the contaminjints of concern, removal
       of the waste ,material from the site is effective in eliminating the human health and
       environmental exposure pathways of contaminants at this site.  Implementation of RAA-5B
       also will minimize or alleviate the need for long-term O&M, monitoring, application of
                                                                                               921

-------
       institutional controls, and 5-year reviews.  The selected alternative is considered to be
       technically and administratively implementable.  Qualified contractors to perform this work are
       available regionally. In addition, transportation of the waste materials to a permitted off-site
       facility will be in compliance with the U.S. Department of Transportation (DOT) regulations.
       Finally, treatability studies  conducted as part of the FS indicate mat stabilization is an effective
       technology for the wastes at the FSAR site.
                                                                                              " *
       The Proposed Plan identified RAA-5A (RAA-4) as EPA's preferred alternative for soil, sludge,
       and sediment contamination.  At the same time, EPA requested the preference of the State of
       Oklahoma regarding the Proposed Plan. The Oklahoma State Department of Health (OSDH)
       indicated that they preferred RAA-5B (RAA-5).  OSDH cited the lower cost of the remedy and
       subsequent lower State matching cost. As a result of -state and general public comments, EPA
       decided to select off-site landfill disposal rather than on-site landfill disposal for this site.
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                                               •   ,
                                                                   '  '           -
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.             ,
                                                                                   •
       Innovative technologies eliminated during the initial screening include the following:

       •      Chemical extraction was eliminated because this technology has not been proven for
               soil or sludges.                                                      ,
       •      Low-temperature thermal stripping  was eliminated because it would not be applicable
               to this  site as this technology is only effective to highly volatile organics.
       "      Reduction/oxidation was eliminated because it would not be applicable for
               concentrated organic waste streams.
       •      Slurry phase treatment was eliminated because it would not be applicable due to the
               metal content in soil and sludge.                    ,
       •      Soil vapor extraction was eliminated because it would not 'be applicable to heavier
               weight petroleum compounds.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      Soil washing was eliminated because it would not be effective for combined organic  ,
               and metal wastes. In addition, high organic wastes cause problems for .these types of
               systems.
       •      Composting was eliminated because although it is potentially effective, this technology
               is not commonly applied to soils with hydrocarbons and development  could be
               required prior to implementation.
  922
                                             , ,-4-

-------
                h   vT™ •*? eliminated tecause ^ technology is not proven 0,1 a full scale and it
                has high capital costs.  The FS states that this technology is ver^ e feet "e ir^fhe
                des rucuon of organics and metals are encapsulated in c^stdlS mSx
                Biological degradation was eliminated because this technology woukUot reduce or
                ehrmnate the toxlcity or mobility of inorganic contaminants, Set The™^eSs In
                fac, the presence of high concentrations of heavy metals in a waste sS £Sto
                buriogicd actwuy.  Considering the contaminant of concern at tlK site^sTead
          .     b,ologlcal treatment would not be an effective remediation alterr^e   T\e FS states
                however  that for wastes associated with the oil refining industry1 neLu
                b,ologlcal treatment have shown to be effective, and th! ability^ th^
                reduce orgamc waste toxicity, mobility, and volume has beenlUentel

        Innovative technologies eliminated during the detailed analysis include tile following:

        •      None                                                      '.!.


72.
                    Contaminant

Cleanup Level (Ppm)    ARAR or <>ther Basis
                Carcinogens
               1     i
               Lead

               PCBs
               "    i.
               PAHs
        500

        25

        30
_OS\\'ER"
Risk biasedb
  TSC!AC
                                                                                   (TSCA,
                                           -5-
                                                 923

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None
'3.
14.     Were treatability studies conducted on the innovative technology or standard technology?

        The ROD states that treatability studies were conducted as part of the FS to determine if
        stabilization/solidification would be an effective technology for the wastes at the FSAR site.
        The results of these studies indicate that this treatment is effective for this site because
        following treatment, none of the TGLP chemicals were detected above their respective TCLP
        regulatory levels (40 CFR Part 261.24). The low levels of organic chemicals of concern
        (COCs) and PCBs allows the stabilization/solidification to occur, while immobilizing the lead
        as well. This information on treatability studies was obtained from the ROD. The FS did
        discuss these studies.
75.     What measures/criteria were, used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Cost-effectiveness
             Proven reliability
             Preference for treatment (vs. containment)
16.     How are measures compared?

        The chosen remedy involves the "ultimate" removal of the waste material from the site and
        therefore eliminates the human health and environmental exposure pathways of contaminants.
        The chosen alternative is cost effective since it offers a degree of protection similar to on-site
        landfilling and incineration at a lower cost.  EPA does not believe that the incinerator
        alternatives offer additional protection  in line with the additional cost. The chosen alternative
        was selected because it was known to be technically and administratively implemen table.
        Qualified contractors who perform the work required under RAA-5B are available regionally.
        The selected alternative also will satisfy the preference for treatment as a principal element of
        the remedy.
 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the'remedy?

        Technical considerations were not primary in selecting a treatment alternative for this site.
 924
                                               -6-

-------
                                Gulf Coast Vacuum Services
                                            OU-1

                                  Vermillion Parish, Louisiana
                                           Region 6
  GENERAL SITE INFORMATION
  7.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?                ..

Maximum concentrations of principal  ;
contaminants were:
        Sludge/Associated Soil (rag/kg)
        Arsenic
        Barium
        Benzene
        Total carcinogenic PAHs
                           74
                           47,800
                           529
                           44
        Total noncarcinogenic PAHs  729

        Soil/sediments (rag/kg)
        Arsenic
        Barium
                           64
                           22,900
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     6/88
                     3/89
                     7/92
                     9/92
             Background

EPA Fund-lead    j
PRPs:   N/A      .;
FS prepared by: Svjerdmp Corporation
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      15, 150 cubic yards of kludge and associated soil
        •      19,500 cubic yards of soil and sediment
                •      -       -
3.     What type of site is this?                                        !
                       '               '                 -             ' J.              -

       Industrial Landfill.  An inactive vacuum truck and oil field drilling mud plant that allowed
       unpermitted disposal of organic- and inorganic-contaminated materials, primarily from the oil
       industry, in several open pits. It is located in an agricultural area.     '
                                                      1        '       "!                  '
                                                 •    -                i              '
TECHNOLOGY SELECTION                                ,          |        ..",-


4..    What standard, technologies were' considered for selection in this FS?  I     '..
                                                                     I   '  \

                                    durfng the identificati°n and screening of technically feasible
                                           -1-
                                                                                 925

-------
       Sludge/Associated Soil

       Access restriction:
       Containment:
       Physical treatment:
       Thermal treatment:
       Disposal:

       Soil/Sediments

       Access restriction:
       Containment:
      •Physical treatment:
       Disposal:
Deed notices
Capping (clay, multimedia, RCRA, soil), vertical barriers
Solidification/stabilization (ex situ, in situ), dewatering
Incineration, cement kiln
Excavation, landfill (on-site, off-site)
Deed notices           .
Capping (clay, multimedia, RCRA, soil), vertical barriers
Stabilization/solidification (ex situ, in .situ), oil extraction
Excavation, landfill (6n-site, off-site)
       Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Sludge/Associated Soil   .

       Biological treatment:'   Composting, bioreactor, land treatment
       Thermal treatment:     Low-temperature thermal  desorption      '

       Soil/Sediments

       Biological treatment:   Biodegradation
       Physical treatment:     Soil washing
       Thermal treatment:     Vitrification
       Wliat was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs."  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  For this site, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
       effectiveness; compliance with ARARs; protectiveness of human health and the environment;
       reduction in contaminant mobility, toxicity, or volume; implementability;  cost; state/support
       agency acceptance; and community acceptance.

       RAAs presented parenthetically represent changes in the Proposed Plan and ROD.
926
                                             -2-

-------
                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
       Sludge/Associated Soil
          Alternative
       Innovative Technology
                                                                    Estimated Costs
                                                                3 Criteria
9 Criteria
         RAA-4
Excavation/biological treatment
(undefined, possibly land treatment)
                                                                eliminated
eliminated
       Soil/Sediments

       No innovative technologies were incorporated into remedial alternatives;.'
7.      How did the cost(s) compare to standard technologies?               \
                                               •                       \
                Cost Estimates for RAAs That Include Standard Technologic
                           (selected remedial alternative is in bold)

       Sludge/Associated Soil                                           1
Alternative
RAA-1
RAA-2
RAA-3A
(RAA-2)
RAA-3B
RAA-5
(RAA-3)
RAA-6
(RAA-4)
Standard Technology
No action •
RCRA cap
Excavation/stabilization-solidification/
on-site disposal/clay cover
In situ stabilization/solidification/clay
cover
Excavation/on-site incineration/
residue stabilization/solidification/on-
site disposal clay cover
Excavation/off-siteincineration/off-site
disposal
Estimated Costs
3 Crilieria
N/A
eliminated
N/A
eliminated
N/A
N/A
9 Criteria
$564,000
eliminated
$1,962,000
eliminated
$10,015,000
$26,605,000
Soil/Sediments
Alternative
RAA-1
Standard Technology '
No action "
Estimated Costs
3 Criteria
N/A
9 Criteria
$564,000
i- • ' ,
-' * ... -' '
-3- • " • '•'
                                                                                           927

-------
Alternative
RAA-2
RAA-3
RAA-4
RAA-5A
(RAA-2)
RAA-5B
(RAA-3)
Standard Technology
RCRAcap
Excavation/on-site disposal/RCRA cap
In situ stabilization/clay cap
Excavation/stabilization/on-site
disposal/clay cap
^-
Excavation/stabilization/off-site disposal
Estimated Costs
3 Criteria
eliminated
eliminated
eliminated
N/A
N/A
9 Criteria
eliminated
eliminated
eliminated
$2,445,000
$17,825,000
8.      If a standard technology was chosen, why?

        Sludge/Associated Soil:  RAA-3 was chosen because it provides greater protection to human
        health and the environment.  This alternative reduces contaminant mobility, volume, and
        toxicity through treatment.   Organic contaminants are destroyed through treatment, and
        inorganic residual is stabilized to mitigate, the risk of leaching into the ground water. This
        alternative offers a great deal of long-term effectiveness and, permanence since the organics
        will be destroyed and the inorganics will be stabilized.  A treatability study tested the
        effectiveness of thermal treatment and determined that organics are destroyed and the resulting
        ash passes the TCLP test by a  large margin. Potential short-term risk from excavation is
        minimized by engineering controls and monitoring.  This  alternative does not require the
        transport of materials and therefore minimizes the risk to  workers  and the community. This
        alternative can be quickly and  effectively implemented with labor  and materials easily
        available within the region.  This alternative is cost-effective.

        Soil/Sediment:  RAA-2 was selected because it substantially reduces the "risk from direct
        contact by stabilizing the contaminated media and covering the matrix with a clay cap.
        Stabilization will immobilize inorganic contaminants, the  principal contaminants in the site soil
        and sediment.  The inorganic material will be chemically  bound, thus mitigating its leaching
        potential into the ground water. Stabilization is an established and effective means of treating
        inorganic contamination in soil. Existing organic contaminants in  the surface soil are below
        health-based levels.  RAA-2 is effective in the long-term  because the major site contaminants,
        inorganics, are effectively treated with stabilization.  Since inorganics such as barium are
        elements that cannot be destroyed and,  therefore, toxicity  can not be reduced, stabilization
        provides the most effective treatment technology. Potential short-term risk will be minimized
        with engineering controls and monitoring.  This alternative can be easily implemented.  This
        alternative is cost-effective.             ...
9.     If an innovative technology was chosen, why?

       An innovative technology was not selected.
  928
                                               -4-

-------
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?
Innovative technologies could be eliminated from the remedial technology selection process at
three stages: during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Sludge/Associated Soil                                            !

Innovative technologies eliminated during the initial screening include the following:

•      Low-temperature thermal desorption was eliminated because it! would not be applicable
        because of the presence of nonvolatile organics.

Innovative technologies eliminated during a three criteria screening of technologies include the
following:                                                  .      I
                                                     -             i -•-'."

•      Composting was eliminated because it would not be amenable for inorganics; it would
        require space that might not be available; and it would require controlled conditions,
        time, large volumes of biomass, supervised labor, collection of i runoff/leachate, and
        means of disposing of product.  Moreover, heavy metals might1 inhibit the process.
•      Bioreactor was eliminated because  it would be  inhibited by heavy metals, high
        chlorides, and other salts. The process would require controlled conditions of pH,
        temperature,  dissolved oxygen, and nutrients. It is a labor intensive process that would
        not degrade or remove all organics  in the waste.              j

'>    •'       •                                  '"'       -   ••-'    i         •  -   >
Innovative technologies eliminated during a three, criteria screening of RAAs:
                  ' '                     '            . • '         '  I
•      Biological treatment (undefined, possibly land treatment) was eliminated because some
        recalcitrant organics would remain,  metals would remain and cpulcl adversely affect
        microbial growth, and a prolonged treatment time would be required.  A preliminary
        evaluation by EPA's Office of Research and Development indicated that concentrations
        of hydrocarbons and metals at most locations preclude the use of bioremediation.  This
        evaluation indicated that heavy metals  can be toxic to microorganisms, even at levels
        below 1 ppm, depending on their species.  Also, biodegradation of soil with total
        petroleum hydrocarbon concentrations above 2,000 mg/kg typkially would not be
        attempted.
                                                                  I     .,
Innovative technologies eliminated during the detailed analysis include [the following:

•      None          . •   •                 •  .  .                   |- ..'•'••.•
       • •   •                                  '                 "I
Soil/Sediment

Innovative technologies eliminated during the initial screening include Ithe following:

•      Biodegradation was eliminated because it would not be applicable to metals, and some
        organics are recalcitrant to .biotreatment.
•      Soil washing was eliminated because it would not be applicable: because of the high
        clay content of the soil/sediment.
                                       -5-
                                                                                            929

-------
       Innovative technologies eliminated during the three criteria screening of technologies include
       the following:

       •      Vitrification was eliminated because its process costs are grossly excessive compared
               to other alternatives.

       Innovative technologies eliminated during the three criteria screening of RAAs include the
       following:

       •      None

       Innovative technologies eliminated during the detailed analysis include the following:

       "      None
11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Sludge/Associated Soil: The criteria weighted most heavily in selecting a remedial alternative
        were protection  of human health and the environment and cost. -EPA preferred RAA-3
        because it is the most protective to human health and the environment through the reduction of
        organics and stabilization of inorganic contaminants. RAA-4 was considered to be slightly
        more protective since it proposed the off-site disposal of materials; but its cost were
        disproportionately high for its benefits.   .                         •   .

        Soil/Sediments:  The criteria weighted most heavily in selecting a remedial alternative was
        protection to human health and the environment and cost.  The chosen alternative provides the
        greatest protection to human health at a cost proportional to its benefit.  This alternative
        effectively immobilizes the main site contaminant. Another alternative that would be slightly
        more protective  because treated media would be disposed of off site was not selected because
        it would be much more costly. Further, it was pointed  out that overall environmental
        protectiveness would not be improved by off-site disposal because it only relocates the waste.  ,
12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

               Sludge/Associated Soil/Soil/Sediment
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Benzene
Total carcinogenic
PAHs
16
0.66
3
Background3
Risk"
EPA Region 6C
930
                                              -6-

-------
 13.
•-.... . . - ' • ";' • • . . ' • .
Contaminant
Cleanup Level (mg/kg)
ARAB: or Other Basis
Noncarcinogens
Barium
Total noncarcinogenic
PAHs
5,400
HI 1
Risk
EE'A Region 6
                "Upper background limit.                                  j
                bBased on an excess upper bound individual lifetime cancer risk of 10"6 or a Hazard
                Index less than or equal to 1.0.                             ;
                •Determined by EPA Region 6, Dallas, Texas.
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include: i

 •  '   " None          ''•       .                            .     ,  I            '  ".
                                                                  i                  . •
                                             •..'"'            i
 Standard technologies eliminated because of cleanup goals include:                       ,
                                  i            •                    '
 •      Stabilization/solidification
 •      Clay cover
14.
 Were treatability studies conducted on the innovative technology or standard technology?

 A preliminary evaluation of the waste/media with respect to the applicability of bioremediation
 was conducted by EPA's Office of Research and Development (1991))  A thermal treatability
 study conducted on soil and sludge indicated that the organic contaminants are destroyed and
 that the ash remaining from the incineration would pass the TCLP test by a large marsin
.(SverdrupM992)                  ..      ..    .
75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

            , Risk level achieved
             Cost-effectiveness
16.     How are measures compared?                                 ,

       In both instances (sludge and associated soil, and soil and sediment), health-based risk levels
       were met. Treatment technologies were utilized to the greatest extent ppssible for reducing or
       immobilizing site contaminants.  Cost-effectiveness  was a determining factor since the   •
       preferred alternatives were selected because they offer protection to huiinan health at a
       proportional cost.  In both cases, other alternatives that proposed off-silte disposal of treated

                     •••'.'          .   .  -7-    ' •   :"•       .       i   "
                                                                                               931

-------
       materials and somewhat more protection to human health were not selected because they
       would be more costly.  Further, off-site disposal was not considered more protective of the
       environment overall since contaminants merely would be displaced.
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       No technical considerations were primary in selecting a remedial alternative.
       References:

       EPA, 1991, Potential of bioremediation at the Gulf Coast Vacuum Services, Inc. Superfund
       Site.  Letter memo to U.S. Environmental Protection Agency-Region 6, from U.S. EPA Office
       of Research and Development, Cincinnati, Ohio.

       Sverdrup, 1992, Treatability Study Report for the Remedial Investigation/Feasibility Study at
       the Gulf Coast Vacuum services, Inc. Superfund Site, Vermilion Parish, Louisiana.
 932

-------
                               Gulf Coast Vacuum Services
                                            OU-2

                                 Vermillion Parish, Louisiana
                                           Region 6
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Sludge and Associated Soil (ing/kg)

        Total petroleum hydrocarbon   700,000
        Benzene                     529
        Arsenic                     73.7
        Barium                     47,800
        Total carcinogenic PAHs     44
        Total noncarcinogenic PAHs  729
             Site IHistory
NPL Proposed:
NPL Final:
FS:
Interim ROD:
6/88
3/89
7/92
9/30/92
             Background  .
                  I

EPA Fund-lead    '
PRPs:  Over 400 identified (not
       specified)
FS prepared by: Sverdrup Corp.
       An extensive list of volatile and semivolatile
       cornpounds was detected at the site; 77 contaminants were selected as fcontaminants of
       potential concern for the risk assessment.
2.     What volume of material is to be remediated?                      !
                                            '            ,    .-••!"'               •

       The volume of material to be remediated included:                  i

       •     7,700 cubic yards of sludge from the West Pit and Washout Pit
       •     1,300 cubic yards of associated soil from the West Pit and Washout Pit

                              '   .   •        .            '              i-       •".-.'•
3.     What type of site is this?                                         j

       Industrial Landfill. An inactive vacuum truck and oil field drilling mud plant operation that
       allowed unpermitted disposal of organic- and inorganic-contaminated materials, primarily from
       the oil industry, in several open pits. The site is located in an agricultural area.
TECHNOLOGY SELECTION
4.      What standard technologies were considered for selection in this FS?

       No initial screening of technologies was conducted .for this Interim FS. Six RAAs were
       developed using standard technologies and evaluated using the nine approved criteria:
                                             -1-
                                        933

-------
     Containment:
     Disposal:
Synthetic membrane          .
Excavation/on-site disposal (single pre-existing pit, lined holding area,
temporary holding tank)
     Was an innovative technology considered in the FS?  If so, which technology?

     Innovative technologies considered during the identification and screening of technically
     feasible technologies were:  .

     No innovative technologies were considered.
     What was the cost estimate for the innovative technology?

     During the initial screening process, in which .technically feasible technologies are identified
     (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
     formulated, costs are typically estimated as part of a three-criteria screening process
     (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
     evaluation. The three-criteria screening was not carried out in this FS.  For this site, estimated
     costs were calculated during an evaluation based on nine criteria established by the NCP. No
     innovative technologies were selected.
     How did the cost(s) compare to standard technologies?

               Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)
Alternative
RAA-1A
RAA-1B
(RAA-l)a
RAA-2
RAA-3A
(RAA-3)
RAA-3B
(RAA-4)
Standard Technology
Pump and treat collected rainwater
(lease system components)
Pump and treat collected rainwater
(purchase system components)
Pump and treat collected rainwater/
synthetic cap
Pump and treat collected rainwater/
excavate wastes/consolidate wastes
into single, pre-existing pit/cover with
synthetic membrane
Pump and treat collected rainwater/
excavate wastes/consolidate wastes in
lined holding area,
Estimated Costs
3 Criteria
N/A
N/A ,
N/A
-N/A
N/A
9 Criteria
$653,250
$566,850
$372,800
($395,700)"
$399,800
($525,200)
$646,840
($834,150)
                                                                                                        .)
934
                                            -2-

-------
Alternative
RAA-3C
(RAA-5)
Standard Technology
Pump and treat collected rainwater/
excavate wastes/consolidate wastes in
temporary holding tank
Estimated Costs
3 Criteria
h
/A
9 Criteria
$713,920
($858,700)
        "RAA designations that changed in the ROD are presented parenthetically. The costs of
        several of the alternatives differ from those in the Proposed Plan because the estimates,have
        been refined based on several factors, including public comments and 'minor changes in the
        description of the alternatives.                                     !
        bCosts presented in the ROD are shown parenthetically.              j
8.      If a standard technology was chosen, why?

        RAA-3 was selected because it is protective of human health and the environment.  RAA-3
        eliminates the risk of the Washout Pit leaching contaminants that can infiltrate through the
        underlying soils to ground water. With Washout Pitsoils and sludges! consolidated in the
        West Pit, the West Pit sludge will be more stable.  Since the sludge wjill be consolidated into a
        single pit, the exposed surface area of the material with the underlying soils will be reduced.
        Of the three alternatives that would be most protective of human health and the environment
        (RAA-3, RAA-4, and RAA-5), RAA-3 takes the least amount of time to implement and poses
        the least direct threat to workers since only one pit is excavated, as opposed to two.  The
        resources (both labor and equipment) are readily available in the area to implement RAA-3
        effectively.  Conventional earthmdving equipment is used to excavate and transport the
        material, and the liner system is commercially available locally. By excavating, consolidating,
        and containing the contaminated sludge and associated soil, RAA-3 is "'most protective of
        human health and the environment and most capable of reducing toxicity, mobility, and
        volume"; RAA-3 is cost-effective and quick to implement.          , |
9.      If an innovative technology was chosen, why?

       An innovative technology was not selected.
10.
If an innovative technology was not chosen, why not? At what stage w!as the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the tljiree criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
                                      '            •               '.        ! '  •
Innovative technologies eliminated during the initial screening include !the following:

•      None
                                              -3-
                                                                                              935

-------
        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      None

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Note that long-term effectiveness "is not applicable to interim actions."

        Protection of human health and the environment, and cost were weighted most heavily in
        selecting a remedy.  By excavating, consolidating, and containing the contaminated sludge and
        associated soil, RAA-3 is protective of human health and the environment. Of all the
        alternatives evaluated for the accumulated rainwater that included a component to excavate the
        pits, the selected alternative provides the best overall protection to human health and the
        environment.

        The residential community's comments indicate a preference for the excavation of both the
        West Pit and the Washout Pit in this interim action. RAA-3 is less costly than alternatives
        that offer comparable levels of protectiveness.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic (carcinogenic
and noncarcinogenic)
Benzene
Total carcinogenic
PAHs
16
0.66
3a
Upper background limit
, Risk
Region VIb
Noncarcinogens
Barium
Total noncarcinogenic
PAHs
5,400
Hazard index of 1.0
Risk
Region VIb
              "Expressed as benzo(a)pyrene equivalents.
              •"Determined by EPA Region VI, Dallas, Texas.
)* L
.)
 936
                                              -4-

-------
       For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to 10
       was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?                          '     t   .
   '                              •                  -               '"-'..,•
       Innovative technologies eliminated because of cleanup goals include:

       •      None                                                    j
    1     -        '"',',''                '             '        ^°
       Standard technologies eliminated because of cleanup goals include:              .

                              '           '   •                     '•'''!•'
       •    -  None                            /
14.    Were tr.eatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.                                      '

                            .   •                                       - !
75.    What measures/criteria were used, to compare alternatives?         " !.

       The following measures were used to compare the alternatives:       |

             Total cost                                                 i
             Time to design/construct/operate                             ;
             Proven technology                                         '                •   •

                                                                       i    '
16.    How are measures compared?                                    !

       Of the three alternatives that would be most protective of human health and the environment,
       RAA-3 is the least costly and takes the least amount of time to implement:—14 weeks.
       Conventional equipment is used to implement RAA-3 and the liner system is commercially
       available locally.                          .
 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedy.
                                                                                           937

-------
                              Mosley Road Sanitary Landfill

                                   Oklahoma City, Oklahoma
                                           Region 6
 GENERAL SITE INFORMATION

 7.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations bf principal
        contaminants were:

        Soil/Sediments (mg/kg)

        Soil borings in the landfill revealed no
        contaminant "hot spots" and  soil/sediment
        samples revealed no contaminants that
        exceeded  cleanup levels.
2.      What volume of material is to be
        remediated?
              Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
6/24/88
11/91
6/29/92
             Background

PRP-lead
PRPs:  WMO, Mobile Waste Controls,
       33 other PRPs
FS prepared by:  Colder Associates
       Incorporated
       The volume of material to be remediated included:

       •      10,420 cubic, yards of waste
3.     What type of site is this?                                        '    .

       Industrial .Landfill. A former landfill that used to accept industrial hazardous waste.
TECHNOLOGY SELECTION

4.      Wliat standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Fencing, warning signs, security, deed restrictions
       Containment:         Clay cap, asphalt cap, concrete cap, composite cap, slurry wall, grout
                            curtain, sheet pile liners, grout injection
       Physical treatment:     Solidification/fixation, aeration
       Chemical treatment:    Neutralization, stabilization/immobilization
       Thermal treatment:     Incineration
       Disposal:             Excavation, disposal at RCRA waste facility
   938
                                            -i-

-------
5.      Was an innovative technology, considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   In situ biodegradation, ex situ biodegradation, landfarming
        Phys/Chem treatment:  Soil washing (waste/solvent leaching), soil flushing (in situ.waste/
                              solvent leaching), air sparging (in situ aeration), in situ
                              oxidation/reduction                 '•-.-!   >   '  .
        Thermal treatment:     In situ vitrification                          ;
6.      What was the cost estimate for the innovative technology?           S
                                                                         I      '         ;
       i                          ,         •"'.,'          '
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. Xfter the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on the nine criteria established
        by the NCP,                                                      :
                                                                         1     ,   •  ,   '
        No innovative technologies were incorporated into remedial alternatives; therefore  no costs
        were estimated.         .                   '                          .
7.      How did the cost(s) compare to standard technologies?
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
Repair existing cap/vegetative soil
layer
Repair existing cap/clay cover over
waste pits/vegetative soil layer
Repair existing cap/RCRA type
composite cover over waste pits/
vegetative soil layer
Repair existing cap/clay cover over
entire landfill/vegetative soil layer
Addition of RCRA type composite
cover over entire landfill
Estimated Costs
3 Criteria
$3,1C)0,000
$3,3CJO,000
$4,100,000
$5,700,000
$11,6130,000
9 Criteria
$3,100,000
$3,300,000
/'
eliminated
$5,700,000
eliminated
                                               -2-
939

-------
8.      If a standard technology was chosen, why?

        The selected capping remedy (RAA-1) protects human health and the environment by
        eliminating the direct contact risk and reducing the potential for any contaminants to migrate               !
        from the waste pits to the ground water and a result of infiltration^ The NCP states  that                   !.
        containment technologies will generally be appropriate remedies for wastes that pose a
        relatively low level threat or where treatment is impracticable.  Removal of contaminated soil
        at municipal landfills is generally limited to hot spots, or when practicable, to landfills with a .             !
        low to moderate volume of waste.  No hot spots have been located at the site; therefore all
        source control remedies were capping.

        The selected remedy is the most cost-effective alternative. RAA-3 and RAA-5 were                ,    ' "•
        eliminated during the three-criteria screening process because the addition of a synthetic cover             •'
        (RCRA type) would cost significantly more but only minimally reduce  the amount of                   •  '
        infiltration. The higher cost would not be reflected in a proportional increase in                           !
        protectiveness. RAA-2 and RAA-4 were eliminated during detailed analysis  because they were
        more costly and the additional measures they contain do not provide additional protectiveness            •
        since it has been concluded that hot spots do not exist within the landfill.
                                                      •                         ,          .

9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.                                                             \
                                                       •                                                 •


10.      !f an  innovative technology was not chosen, why not? At what stage was the innovative             ^P  )l
        technology eliminated?                  •                                             ,              ~"V

        Innovative technologies could be eliminated from the remedial technology selection process at
        three  stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.                      ,

        Innovative technologies eliminated during the initial screening include the following:

        •      Ex situ biodegradation was eliminated  because the metal contaminants found at the
              site do not biodegrade.
        •      Landfarming was eliminated because the metal contaminants found at the  site do not
              biodegrade.
        •      In situ biodegradation was eliminated because adding nutrients to the landfill could be
              detrimental to surface and groundwater quality.  Furthermore, toxic by-products could
              be produced from contaminant degradation.
        "      Soil washing (water/solvent leaching) was eliminated because it is only  applicable to
              heavily contaminated  soils; placing  solvents in contact with soils containing low levels
              of organics (such as levels found at this site) may increase organic contaminant levels.
       •      Soil flushing (in situ water/solvent leaching) was eliminated because the leaching
              solution would be very difficult to deliver and recover uniformly. ,
       •      Air sparging (in situ aeration) was eliminated because the heterogeneous waste would
              be difficult to aerate uniformly. Furthermore, the process would have limited
              application, since it would not remediate semi-volatile organics.
       «      In situ vitrification was eliminated because the methane gas in the landfill would pose
              a potential explosive hazard and the technology  is very expensive to implement.

  940                                                                            ,
                                             '-3-                     •   '                    •

-------
        •      In situ oxidation/reduction was eliminated because of the difficulty in uniformly
               delivering the pxidants, recovering precipitated metal sludges, and the probability of
            '  unwanted by-products remaining in the soil.                 !

        No innovative technologies were incorporated into the RAAs; therefore no innovative
        technologies were eliminated during the three-criteria screening process or during detailed
        evaluation.                                                       j
11.     Which of the nine criteria were weighted most highly in selecting thekechnology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?
'  '                 .          :           •                    .            I'-. '    •
                                                                        I        •   -    "
        For those alternatives that provided protection of human health and the environment and
        attained ARARs, cost-effectiveness was the most heavily weighted criteria in selecting a      ,
        remedy.  No innovative technologies were evaluated based on the nine criteria.     ,
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
            >            '                                •               ^ i
                                                                        ,' *
        The only threat from soil/sediment contaminants at the site is their impact on ground water.
        The remedial goals for soil/sediment included the elimination of direct exposure to
        contaminants and the reduction of any soil/sediment contribution to ground and surface water
        contamination. Therefore, EPA's selected alternative does not address directly the content of
        the landfill, but instead inhibits-the generation of leachate due to water infiltration.

        For carcinogens,  an  excess upper bound individual lifetime cancer risjc of between 10"4 to  10~6
        was acceptable.  For noncarcinogens, Hazard Index less than or equal to 1.0 was acceptable.
        These estimates demonstrated that the landfill soil/sediments did not pose a threat to" human
        health.
13.     Was the innovative technology eliminated because of the cleanup goals? If a standard
        technology was selected, could it meet the cleanup goals?

        Innovative technologies were eliminated because they were not applicable to the contaminates
        at the site and because the large volume of low level contamination at the site would be more
        appropriately contained rather than treated.  No innovative technologies were eliminated
 -    •  because of cleanup goals.  The standard technology selected could meet cleanup goals for the
        site.  ;                    '...••,                .    !
14.     Were treatability studies conducted oh the innovative technology or standard technology?

        No treatability studies were conducted.           '
                                               -4-
941

-------
75.     W}iat measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:
                                                       *                         ''              '
               Total cost
               Risk level achieved                                              ,


16.     How are alternatives compared?

        Since all source control alternatives involved various capping scenarios, they were rated
        similarly for protectiveness, ARARs, long-term effectiveness, short-term effectiveness,
        reduction of TMV, and implementability.  The alternatives were compared based on cost.  No
        hot spots were found that required additional containment measures to control infiltration.
        Therefore, additional containment measures beyond repair of the existing cap would not
        achieve a higher level of risk protection that would justify their additional cost.
                                              ~

17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?                                    ..

        The landfill is in an undeveloped residential area. About 1.7 million  gallons of hazardous   ,
        liquids were disposed of in unlined waste pits over a six month period 14 years previously; the
        waste pits are now covered by up to 80 feet of municipal waste. Underlying the  site is
        unconsolidated sediments and a bedrock aquifer. North Pond lies  north of the landfill and
        South swamp lies south of the landfill. Hydrogeology did not play a  primary role in source
       control remedy selection.  Technical considerations could not be considered primary in      '
       selecting a source control remedy at .this site. The volume and nature of contamination at this
       site was primary in the selection of a remedy.
  942
                                             -5-

-------
                             Oklahoma Refining Company

                                     Cyril, Oklahoma
                                        Region 6
 GENERAL SITE INFORMATION

 1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/sediment (mg/kg)

       Arsenic                    236
       Benzene                    25
       Chromium                  24,020
       2-MethylphenoI             1,700
       4-Methylphenol             5,400
       Benzo(a)anthracene         300
       Benzo(a)pyrene             280
       Benzo(b)fluoranthene        120
       Benzo(k)fluoranthene        40
       Idenp(123/c,d)pyrene        84
       Pyrene                     190
       Dibenzo(a,h)anthracene      23
       Naphthalene                350
       Beryllium*                  L4
       Lead                       19,390
       Chrysene                   456
       2-Methylnaphthalene        2,000
       Phenanthrene               1,100
       Phenol                     4,200
       2,4-Dimethylphenol          200
             Site History

NPL Proposed:       N/A
NPL Final           6/88
FS             ';.)   12/91
ROD:               6792
                 i      .

             Background

EPA Fund-lead
PRPs:  Cyril Petrochemical Company
FS prepared by:  Bechtel Environmental,
       Inc.       i
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:
                                                                  i

       •     Approximately 120,000 cubic yards of contaminated soil and sediment
3.      What type of site is this?

       Petroleum Refining.  An abandoned refinery that is located in a rural area.
                                          -1-
                                                                                     943

-------
TECHNOLOGY SELECTION                                         '

4.      What standard tec/,'  -logies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:

        Physical/chemical:
        Thermal treatment:
        Disposal:
Fencing, warning signs, deed restrictions, deed notices
Capping (clay, asphalt, concrete, multimedia), surface controls, dust
controls
Neutralization, polymerization, stabilization, surface encapsulation
Incineration (rotary kiln, fiuidized bed, infrared)
Excavation, disposal  (off-site, on-site)
5.      Was an innovative technology considered in the F.S? If so, which technology?

        Innovative technologies considered during the identification and screening of technically    '
        feasible technologies were:

        Biological treatment:  Biodegradation, composting, soil slurry reactor, prepared bed reactor
        Physical/chemical:     Oxidation/reduction, hydrolysis, soil venting, soil flushing, chemical
                             dechlorination, chemical extraction, soil washing
        Thermal treatment:    Vitrification (in situ, ex situ), low-temperature thermal desorption,
                             electric pyrolyzer
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process  .
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
Containment/neutralization/biotreatment
In situ stabilization/neutralization/
biotreatment
In situ stabilization/recycling/
neutralization/in situ biotreatment/ ,
prepared bed reactor
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$10,977,563
$21,544,740
$24,044,056
                                                                       m
 944
                                              -2-

-------
          Alternative
          RAA-6
                          Innovative Technology
                 In situ stabilization/recycling/
                 neutralization/low-temperature thermal
                 desorption
                                                                        Estimated Costs
                                                                    3 Criteria
N/A
            9 Criteria
                                                                                  $52,645,422
 7.      How did the cost(s) compare to standard technologies?              !

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action
Limited action
Estimated Costs
3 Criteria
• N(A
' . N/A
9 Criteria
$15,302
$1,918,114
8.      If a standard technology was chosen, why?                         \
                                                               ' •  ,"       i
       In situ stabilization and,a cap of the residuals were selected for some \yastes.
9.      If an innovative technology was chosen, why?

       The chosen alternative RAA-5 was preferred because it protects human! health and the
       environment by treating 89 percent of the total waste.   All contaminant media in excess of
       cleanup levels are treated. In situ biotreatment is: performed in a lined 'surface impoundment
       and is expected to destroy 90 to 95 percent of the organic contaminants.  The biotreated
       residuals and the sediment and soil remaining with inorganic contaminants in excess of
       cleanup levels will be stabilized and contained on site.  Through treatment, this alternative
       reduces contaminant toxicity, mobility, and volume.  The proposed technology has been
       proved effective for the types of contaminants present at the site and is not expected to cause
       any unusual problems in its implementation. No specialized equipment is necessary to
       implement this alternative.  Reducing contaminant levels through treatment ensures the most
                                             -3-
                                                                         This alternative meets
effective and permanent remedy for contaminated soils and sediments.	„
all ARARS.  Risk from excavation and material handling will be minimized by providing strict
controls. This alternative is cost-effective. The ROD also selected ex isitu biodegradation
(unspecified) before remediation of some wastes.
                                                                                               945

-------
 10.     If an innovative technology was not chosen, why not? At-what stage was the innovative
        technology eliminated?                                                                                I

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        •      Oxidation/reduction (in situ) was eliminated because its limited applicability makes it
                difficult for the reagent to contact the hazardous materials because of the low
                permeability of the site's soils.                                   .
        •      Hydrolysis (in situ) was eliminated because it would not be applicable since waste
                materials are fully hydrolysed.                                . .
        "      Soil venting  was eliminated because it would not be applicable since the permeability   ,   :.'
                of site soils would not allow adequate air flow. Soil venting is effective when the
                subsurface media has a permeability of 10"4 to 10"6cm/sec, and the site soil has a
                permeability less than 10~6cm/sec.                                                      ,
        •      Soil flushing was eliminated because it would not be applicable since site soils are not
                very porous  and have relatively low permeabilities.
        •      Chemical dechlorination (in situ) was eliminated because it would not be applicable to
                the site  since there are few chlorinated compounds.
        •      Soil washing was eliminated because  it would not be applicable to the small grain size
                of soil/sediment.  The high silt and clay content of the site's soil could impede the            .^
                solid-liquid separation after washing.                                                   „  «|H
        •      Composting was eliminated because it has not been demonstrated to be effective for         •
                similar wastes.                          ...  .                       .
        •      Soil slurry reactor was eliminated because it would not be applicable to the small
                grain size of soil/sediment. The high silt and clay content of the site's soil could
                impede  the solid-liquid separation after washing.
        •      Electric pyrolyzer was eliminated because it would not be applicable to the metals
                content  in the site's soil.  Further, this process would require extensive air pollution
                controls and the large volume of ash generated would likely contain high levels of
                inorganics and might need to be stabilized prior to disposal.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      In situ vitrification was eliminated because it would be difficult to implement because
                of large areas  of contamination on site and high cost.
        »      Chemical extraction was eliminated because it would not be effective in clay soils.
        •      Ex situ  vitrification was eliminated because of the very high capital cost.

        Innovative technologies eliminated during the detailed analysis include the following:

         •      Low-temperature thermal desorption  (LTTD) was eliminated because it would not be
                cost-effective  compared to the chosen alternative since it would provide only  4
                percent increase in contaminant  removal for $28.6 million. LTTD would be more
                difficult to implement than the chosen alternative because it would require more             fflBh  \
                extensive material handling and  procurement of specialized equipment.                      "


946
                                                -4- •     .     '      '

-------
11.
 Which of the nine criteria were weighted most heavily in selecting the [technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

 The criteria weighted most heavily in selecting a remedial alternative 'iven; protection to human
 health and the environment, long-term effectiveness and cost. RAA-1 jand RAA-2 were
 eliminated because they would not protect human health and the environment. RAA-3 was
 eliminated because it could not ensure long-term effectiveness since true caps would need to be
 maintained.  RAA-4 was eliminated because it would not address all site wastes and therefore
 it was not protective of human health and the environment. Two alternatives would
 adequately address all site contaminants. Of these, the chosen alternative was cost-effective.
12.
What cleanup goals were selected? If the cleanup goal was based on\an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?

       Surface Soil/Sediment
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Beryllium
Cadmium
Chromium
Lead
Nickel
Benzene
Benzo(a)anthracene
Benzb(a)pyrene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Chrysene
Dibenzo(a,h)anthracene
Indeno(123/c,d) pyrene
25 or 305"
0.5
135
1,350 or 770
600 or 865
5,400
22 or 0.2
4.1
0.33
0.69
13
46
0.33
3.2
EPAborGWc ,
Detection limit ;
Risk"
Risk or GW
Model6 or GW
Risk
Risk or GW
Risk
Etetection limit
Risk
Risk
Risk
Detection limit
Risk
Noncarcinogens •
Barium
Mercury
Zinc
13,500
81
54,000
Risk
Risk
• Risk ..'•
                                            -5-'
                                                                                      947

-------
Contaminant
Ethylbenzene
Toluene
Xylenes
Acenaphthalene
Anthracene
Benzo(g,h,i)perylene
Fluoranthene
Fluorene
Naphthalene
Phenathrene
Pyrene
2,4-Dimethylphenol
2-Methylnaphthalene
2-Methylphenol
Phenol
Cleanup Level (mg/kg)
27,000 or 191
54,000 or 104
540,000 or 2,828
16,000 or 4,424
,81,000 or 55,752
1,080 * '.
10,800
10,800 or 8,888
79
1,080
8,100
5,400 or 66
1,080 or 510
13,500 or 14
162,000 or 125
ARAR or Other Basis
Risk or GW
Risk or GW
Risk or GW
Risk or GW
Risk or GW
Risk
Risk
Risk or GW
GW
Risk
Risk
Risk or GW
Risk or GW
Risk or GW
Risk or GW
             "When more than one cleanup level was estimated, the lower of the two numbers was
             used to determine the necessary action to address the contaminated media.
             bCleanup levels were set by EPA Region VI to be protective of human health in a
             residential setting.,                                                ,
             cCleanup levels were estimated to prevent leaching from contaminated soil/sediment
             into ground water.  This method can be found in an EPA guidance document entitled
             "Determining Soil Response Action Levels Based on Potential Contaminant Migration
             to Ground Water:  A Compendium of Examples" (EPA/540/2-89/057), October 1989.
             dCleanup levels were determined by health-based risk assessment. For carcinogens, an
             excess upper bound individual lifetime cancer risk of 10"6 was acceptable.  For
             noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
             TEPA Uptake/Biokinetic Lead model.

             Subsurface Soil
948
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Chromium
Lead
305 ,
770
865
GW3
GW
GW
                                            -6-

-------
Contaminant
Benzene
Cleanup Level (mg/kg)
0.2 '
ARAR or Other Basis
GW
Noncarcinogens
Naphthalene
Phenol
2-Methylphenol
4-Methylphenol
2,4-Dimethylphenol
2-Methylnaphthalene
79
125
12
14
66
510
GW
GW
GW
GW
GW
GW
               Cleanup levels were estimated to prevent leaching from contaminated soil/sediment
               into ground water. This method can be found in an EPA guidance document entitled
               "Determining Soil Response Action Levels Based on Potential Contaminant Migration
               to Ground Water:  A Compendium of Examples" (EPA/540/2-89/057), October 1989.
                                                                                  '  \

13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?  ,

       Innovative technologies eliminated because of cleanup goals include:

       •       None

     ,  Standard technologies eliminated because of cleanup goals include:

       •       None   . ,                   ••'•.".


14,    Were treaiability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.


75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:
                              /
             Risk level achieved                     *
             Cost/unit risk
             Preference for treatment (vs. containment)
                                             -7-
949

-------
16.    How are measures compared?

       The chosen alternative was selected because it would destroy 90 to 95 percent of the organic
       contaminants, thereby providing significant risk reduction,  li was preferred over another
       alternative, RAA-6, because it was cost-effective.  Thus, while RAA-6 would destroy 95 to 99
       percent of the organic contaminants, this 4-percent increase would cost an additional $28.6
       million.  The slight increase in effectiveness did not justify the increase in cost.  The chosen
       alternative was preferred over all of the other alternatives because it would reduce risk in a
       more complete and long-term manner. Further, treatment was preferred over containment as
       evidenced by the elimination of RAA-3.
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        The low permeability and high clay and  silt content of the soil precluded the use of:
        oxidation/reduction, =soil venting, soil flushing, soil washing, soil slurry reactor, chemical
        extraction.  This technical consideration  was not primary in selecting a remedial alternative.
  950

-------
                              Petro-Chemical Systems, Inc.
                                           OU-2
                                   '*  .
                                    Liberty County, Texas
                                          Region 6
 GENERAL SITE INFORMATION
 1.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
        Soil (mg/kg):

        Benzene
        Lead
        Naphthalene
                     28
                     24
                     320*
       'Sample did not satisfy all QA/QC
       requirements and is considered conditionally
       valid.  Results can be used for trending
       purposes.
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
             Background

EPA Fund-lead
PRPs:  ARCO
FS prepared by: Roy F. Weston,
       Inc. (9/91); Lockwood, Andrews
       & Newman, Inc. (3/91)
                                                                 Site History
                      1984
                     (5/86
                     9/3/91
                     9/6/91
2.     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •     302,800 cubic yards of soil          ,


3.     What type of site is this?

       Industrial Landfill.  Former petrochemical waste disposal area.


TECHNOLOGY SELECTION                                   .
  .^——^—M*^——«_^_^_
                                                                ;      f

4.     What standard technologies were considered for selection in this FS?  '

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                    .

       Access restriction:     Deed restrictions, fencing and posting warning sign;!
       Containment:         Capping with topsoil and vegetation, cement stabilized soil, asphalt,
                            concrete, clay, or clay/synthetic liner and cap, covering with a dome or
                                            -1-
                                                                                  951

-------
       Chemical treatment:
       Thermal treatment:
       Disposal:
synthetic membrane, vertical barriers (slurry wall, cement/bentonite
wall, grout curtain, sheet pile wall, or interceptor trenches)
Solidification/stabilization
Soil stripping (auger), fluidized bed, incineration, infrared incineration
Excavation, dredging, landfill (on-site or off-site)
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                  .

        Biological treatment:   Aerobic/anaerobic biodegradation, soil/slurry bioreactor, landfarming
        Phys/Chem treatment:  Vapor extraction, solvent extraction, soil washing (solvent/surfactant),
                              soil washing (water)
        Thermal treatment:     Vitrification, radio frequency  volatilization, supercritical water
                              oxidation, wet air oxidation, low-temperature thermal stripping
6.      What was the cost estimate for the innovative technology?

        During the initial  screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs  are typically estimated as part of a three-criteria screening process ,
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  The estimated costs then are recalculated during an evaluation based on nine
        criteria established by the NCP.

        Only estimated costs for individual technologies were presented in the FS. Present value costs
        for RAAs, however, were provided in the ROD.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-9
Innovative Technology
Ex situ biodegradation/landfill closure,
if necessary
Solvent extraction/excavation and
storage of soils on site/use of
decontaminated soils as backfill on the
site/off-site incineration of contaminated
solvents
Vapor extraction and catalytic
oxidation of extracted vapors'/long-
term monitoring
Estimated Costs
ROD
$41,100,000
$142,200,000
$26,430,000
        •Catalytic oxidation was added as a technology during the more detailed evaluation of RAAs.
952
                                               -2-

-------
 7.      How did the cost compare to standard technologies?
                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
;
Alternative
RAA-1
RAA-2
RAA-5
RAA-6
RAA-7
RAA-8

Standard Technology
No action/monitoring of the leachate
collection system for the temporary on-
site landfill/maintaining the integrity of
the road and road side drainage ditches
Slurry walls/multilayered caps/landfill
closure/long-term monitoring of the
site and ground water/possible deed
restrictions
Incineration/excavation and storage of
soils on site
Thermal stripping/excavation and
storage of soils on site
Excavation on-site/landfilling/
multilevel cover/leachate collection
system
Excavation off site/landfilling
Estimated Costs
ROD
il, 440,000
$8,500,000
$280,200,000
$]J21,000,000
$27,800,000
$72,400,000
8.      If a standard technology was chosen, why?

       Two RAAs, a, standard (RAA-2) and innovative (RAA-9), were chosen
                                                                        and will be
       implemented together. RAA-2 was chosen to improve the efficiency of the innovative
       technology, vapor extraction.  The cap will reduce the amount of surface air so that air pulled
       through the contaminated soil  via vapor extraction will be coming primarily from the air
       injection wells.  The slurry walls will prevent migration of contaminated ground water.
9.      If an innovative technology was chosen, why?

       In situ soil vapor extraction (SVE) was selected because: 1) it would not
       the contaminated soils prior to treatment, thereby reducing the short-term
       emissions, 2) treatability studies of SVE have been conducted at sites in
       Pennsylvania, with soils similar to those at this site, 3) cost, 4) reduces
       into ground water, and 5) avoids extraction and placement of RCRA hazardous
       therefor will not .need to comply with LDRs or other RCRA ARARs.
                                            -3-
                                                                         require excavation of
                                                                         risk from volatile air
                                                                        Florida and
                                                                       contaminant leaching
                                                                              waste, and
                                                                                           953

-------
JO,    If an innovative technology was not chosen, why not? At what stage was the innovative           ••••
       technology eliminated?                                                                        ^HF    V
                                                                                         '                 •"
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       "      In situ soil washing/soil flushing was eliminated because of the high clay content of
               the soil and inefficiency of the method.
       •      Radio frequency volatilization was eliminated because the technology has not been   .             |
               proved.              .                                                    -
       •      Vitrification was eliminated because of its significantly higher costs with no increase in
               effectiveness over other technologies.                                                          ~i
       "      Soil/slurry bioreactor was eliminated because of its higher costs without significant
               advantages over other technologies.                                                        .    !
       "      In situ bioremediation was eliminated because of the high clay content of the soil.
       "      Supercritical water oxidation was eliminated because  it is not commercially available,
               has not been demonstrated on similar waste to those at the site and difficulty in finding
               corrosion  resistant materials to be used in construction of full-scale units.
       "      Wet air oxidation was eliminated because treatment requires a 5 % by weight slurry              f
               and for the quantity of soil potentially requiring treatment, the technology would not
               be technically feasible.
       •      Permeable treatment beds were eliminated  because it  is not a proven technology.          J4uHi  \
                                                                                                     111  ;)
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                                                           [

       «      In situ low temperature thermal stripping was eliminated because it has not been
               previously demonstrated under similar  site conditions  and does not have significant      :         i
               advantages over in  situ vapor extraction.
       *      Landfarming was eliminated because of higher costs and lower effectiveness and              •  •-  ;
               implementability.

       Innovative technologies eliminated during the detailed analysis include the following:       -
                                                                        /-                                 ,  i - .
       •      Biological treatment (treatment bed) was eliminated due to the short term risk posed
               by the mobility of the volatile contaminants as the soil is excavated.                              i
       »      Solvent extraction was eliminated because it is not cost effective and the anticipated
               number of units of  equipment to treat the amount of soil at the site may not be
               available.
       •      Low temperature thermal stripping (thermal desorption) was eliminated because in the         '
               short term it is not  cost-effective, the mobility of the contaminants will increase as the.
               soil is excavated, and the anticipated number of equipment units may not be available.
954
-4-

-------
 11.
        Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Short term effectiveness, cost and reduction of toxicity, mobility or volume weighted most
        heavily in selecting the technology.                           •                    -
12.
13.
        What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?      j
Contaminant
Cleanup Level (ppm)
ARAR <»r Other Basis
Carcinogens
Benzene
Lead
10 (at soil depths less
than 10 feet)
0.35 (at depths greater
than 10 feet)
• 500
MC!L, Model"
GSWER"
Noncarcinogens
Naphthalene
70
Risk
               "Soil cleanup level is based on the potential of benzene in soil to leach into the
               underlying ground water aquifer.  The MCL for benzene in driiiking water used the
               SESOEL model to calculate ground water levels of benzene.
               bOSWER Directive on the Interim Guidance on establishing Soil Lead Cleanup Levels
               at Superfund Sites, September 7, 1989.
        For carcinogens, an excess upper bound individual lifetime cancer risk
        was acceptable. For noncarcinogens, a Hazard Index less than or equal
                                                                         of
       Was the innovative technology eliminated because of the cleanup goals'.
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

       •      None                                 "      .    .    •
14.     Were treatability studies conducted on the innovative technology or standard
       Treatability studies were conducted on biological treatment and
       showed that remedial levels could be achieved.
                                              -5-
  between 10"4 to 10'6
to 1.0 was acceptable.


  Could the standard
                                                                              technology?

                                                                 solvent-extraction.  Results
                                                                                              95
                                                                                                    5

-------
15.
       Although no treatability studies were conducted on thermal stripping at the site, treatability
       studies conducted at similar sites showed that remedial goals for benzene could be achieved.
       Additional treatability studies, however, might be needed to optimize the stripping process.
       While no treatability  studies were conducted on vapor extraction, treatability studies conducted
       at similar sites in Florida and Pennsylvania showed that vapor extraction with catalytic
       oxidation of the extracted vapors effectively reduce the mobility, toxicity, and volume of
       contaminants in mixed clay and sand soils such as those at the site.
        What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Total cost
               Impact on nearby populations
               Proven reliability
               Preference for treatment (vs. containment)
16.    How are measures compared?

       The preference for treatment of contaminants, along with the desire to leave wastes in place to
       reduce fugitive air emissions during excavation, were the major measures used to distinguish
       between alternatives. Vapor extraction with catalytic oxidation (RAA-9) was the only
       alternative that would allow for treatment without excavation.
17.    Wftat technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       Shallow gravels at the site ruled out the use of sheet pile walls for containment.  Clay soils at
       the site reduced the potential efficiency of biodegradation and soil washing.
956
                                               -6-

-------
                               Prewitt Abandoned Refinery

                                     Prewitt, New Mexico
                                           Region 6
  GENERAL SITE INFORMATION
  1.
  What were the principal contaminants,
  contaminant levels, and media addressed in
  this feasibility study?
                                      V
  Maximum concentrations of principal
  contaminants were:

  Surface Soil (mg/kg)

  Asbestos             above background
  Benzo(a)anthracene   265
  Lead                129^000
 Benzo(a)pyrene       215
 Benzo(b)fluoranthene 146
 Benzo(k)fluoranthene 146
 Chrysene             220

 Separator Sludge and Waste Pit Soil
 (mg/kg)
        Ethylbenzene
        Benzene
                     4.2
                     0.23
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
N/A
8/30/90
2/92
9/30/92
                                                                Background

                                                    PRP-lead         |
                                                    PRPs: Atlantic Ridhfield Company, El
                                                          Paso Naturajl Gas Company
                                                    FS prepared by: Mprriiion Knudsen
                                                          Corporation!
 2.
 What volume of material is to be remediated?                    '  \,
                                              ' '          '     I' '. '  -      '

Hie volume of material to be remediated included:                  ;.     ^
                                                     "        •[->'-.

 •      15 cubic yards of asbestos contaminated material             !
 •      i.SOO cubic yards,of PAH contaminated soil
 •      665 cubic yards of lead contaminated soil
 •      80 cubic yards of separator sludge, contaminated waste pit soil jandl soil under the
       separator    .         '                .                '  . i
3.      What type of site is this?
                                           -i-
                                                                               957

-------
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                   .        .
        Soil - Lead

        Access restriction: •
        Containment:
        Chemical/physical:
        Chemical treatment:
        Physical treatment:
        Disposal:

        Soil • Asbestos

        Access restriction:
        Containment:

        Chemical treatment:
        Disposal:

        Soil - Hydrocarbons

        Access restriction:
        Containment:
        Physical/chemical:   ,
        Disposal:

        Waste Pits

        Access restriction:
        Containment:
        Chemical/physical:
        Disposal:

         Separator Sludge

         Access restriction:
         Containment:
         Physical/chemical:
         Thermal treatment:
         Disposal:
Deed restrictions, fencing
Capping (clay, soil, synthetic membrane, chemical sealants)
Stabilization (ex situ, in situ)
Soil stabilization
Drainage control
Excavation, RCRA landfill
Deed restrictions, fencing
Capping (soil, clay, synthetic membrane, chemical sealants), drainage
controls
Soil stabilization
Excavation, permitted landfill
 Deed restrictions, fencing
 Capping (soil), drainage control
 Stabilization
 Off-site industrial landfill
 Deed restrictions, fencing
 Capping (soil), drainage controls
 Stabilization
 Excavation,, off-site landfill
 Deed restrictions, fencing
 Capping (concrete)   ,
 Stabilization
 Incineration                   ••
 Excavation, RCRA permitted landfill
958
                                                -2-

-------
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Soil-Lead  "

        Chemical treatment:   Soil washing

        Soil - Hydrocarbons

        Biological treatment:   Landfarming, thin spreading

        Waste Pits

        Biological treatment:   Landfarming, thin spreading

        Separator Sludge        .

        Biolbgical treatment:   Landfarming
        Chemical treatment:    Solvent extraction


6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs, /ifter the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated  costs then are recalculated during an evaluation  based on nine criteria established by
        theNCP:  long-term effectiveness and permanence; short-term effectiveness1; compliance with
        ARARs; protectiveness of human health and the environment; reduction in contaminant
        mobility, toxicity, or volume; implementability; cost; state/support agency acceptance;  and   '
        community acceptance.  In this case, some alternatives were eliminated in the detailed analyses
        and reintroduced in the ROD.  Information presented parenthetically refers to the ROD.

                 Cost Estimates for RAAs That Include Innovative  Technjologies
                           (selected remedial alternative is in bold)

  '      Soil with;Hydrocarboris
Alternative
RAA-4I
(RAA-4E)
RAA-4J
(RAA-4F)
• ,
Innovative Technology
Excavation/landfarming
Excavation/thin spreading
Estimated Costs
3 Criteria
$1,286,300
$156,000
9 Criteria
eliminated
$1

56,000
ROD
$1,286,300
$156,000

                                              -3-
                                                                                               959

-------
       Waste Pits
Alternative
RAA-3D
(RAA-3C)
RAA-3E
(RAA-3D)
Innovative Technology
Excavation/landfarming
Excavation/thin spreading
t
Estimated Costs
3 Criteria
$1,142,400
$134,800
9 Criteria
eliminated
$134,000'
ROD
$1,142,400
$134,000
       * Represents cost without a bottom liner, which could increase cost substantially.

       Separator Sludge                   .                  .
Alternative
(RAA-5B)
Innovative Technology
Excavation/off-site treatment
and disposal/landfarming, soil
washing, or off-site
incineration if soil under
separator is contaminated
Estimated Costs
.3 Criteria
not
proposed
9 Criteria
not
proposed
ROD
$116,000
7.      How did the cost(s) compare to standard technologies?              ;

                Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)

       All Soils
Alternative
RAA-4A
Standard Technology
No action
Estimated Costs
3 Criteria
$0
9 Criteria
$0
       Soil with Lead
Alternative
RAA-4B
RAA-4C
(RAA-4B)
Standard Technology
Use and access restrictions/soil cap
Excavate soil with lead/off-site
disposal in RCRA landfill
Estimated Costs
3 Criteria
$224,900
$1,605,000
9 Criteria
eliminated
, $1,605,000
960
                                            -4-

-------
Alternative
RAA-4D
\ • •
Standard Technology
Use restrictions/in situ stabilization/soil
cover
Estimated Costs
3 Criteria
$415,200
9 Criteria
eliminated
Soil with Asbestos
Alternative
RAA-4E
RAA-4F
(RAA-4C)
Standard Technology
Use and access restrictions/soil cap
Excavate soil with asbestos/off-site
disposal in industrial facility
Estimated Costs
3 Criteria
$44,200
$9,300
9 Criteria
eliminated
$9,300
Soil with Hydrocarbons
Alternative
RAA-4G
RAA-4H
(RAA-4D)
Standard Technology
Use and access restrictions/soil cap
Excavate soil with hydrocarbons/off-site
disposal in industrial landfill
Estimated Costs
3 Criteria
$174,600
$681,300
i .
9 Criteria
eliminated
$681,300
Waste Pits
Alternative
RAA-3A
RAA-3B
RAA-3C
RAA-3F
(RAA-3E)
Standard Technology
No action
Soil cap
Excavation/off-site disposal at industrial
landfill
In situ stabilization/soil cover
Estimated Costs
3 Criteria
. $0
$27,300
$544,600
$83,400
"' '
9 Criteria
$0
. $27,300
eliminated
$83,400
                                   -5-
961

-------
       Separator Sludge
Alternative
RAA-5A
RAA-5B
Standard Technology
No action/use restrictions/fencing/
monitoring
Excavation/off-site disposal in RCRA
facility
Estimated Costs
3 Criteria
$7,200
$116,000.
r
9 Criteria
$7,200
$116,000. ,
8.      If a standard technology was chosen, why?
                 :       -                  '•                       •           '
       Soils with Lead and Asbestos

       A standard technology was chosen to remove source contaminants completely and permanently
       by excavating and disposing of soils off site.  This remedy is permanent and effective in the
       long term. It will completely eliminate any exposure to lead and asbestos by permanently
       remediating these contaminants to cleanup levels.


9.      If an innovative technology was chosen, why?                             *

       Soil with Hydrocarbons, Waste Pits,  Separator Sludge, and Potentially Soil Below the
       Separator

       An innovative technology was chosen for the remediation of waste pit soil, soil containing
       hydrocarbons, separator sludge, and soil below the separator, if found to be contaminated.
       This technology was chosen because it will reduce the concentrations of waste to remediation
       levels.  This is particularly important since this area is expected to be used for residential
       purposes in  the future. The technology was preferred because it will eliminate contaminants
       thereby reducing their toxicity, volume and mobility. This reduction in contaminants will be
       permanent and therefore effective in the long term. It was considered superior to containment
       options as long-term maintenance will not be required to ensure its success.  Landfarming also
       was a reliable option.  A treatability study was conducted that determined that this technology
       could remediate 90 percent of the contaminants following the addition of nutrients and water,
       thereby complying with cleanup levels.
10.
 962
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                                        ,

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•     Soil washing of soil contaminated with lead was eliminated because there was not a
       large enough volume of soil.

                                       -6-

-------
        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      Landfarming for the waste pits and the soil with hydrocarbons was eliminated because
                it would achieve no greater protection than thin spreading but would be more costly.
        •      Solvent extraction was eliminated because of its extremely high cost.

        Innovative technologies eliminated during the detailed analysis include the following:

        •      Thin spreading was eliminated because instability studies showed that it would not'
                successfully remediate site soils. Moreover, this technology might not meet RCRA
                regulations to ensure the degradation of contaminants in the treatment zone prior to
                their transport into ground water.                          i
 11.
12.
 Which of the nine criteria were weighted most heavily in selecting the1 technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so
 which criterion?  Which of the criteria supported the use of a standard technology?

 For all media, the criteria most heavily weighted in selecting a remedial technology were long-
 term effectiveness and permanence. These criteria ensure the greatest protection to health and
 the environment.
                                                                 p         "
 In the FS, landfarming was initially eliminated because it would not bik as cost-effective as
 thin spreading.  When thin spreading was shown to be ineffective for Ithe iremediation of the
 site s waste, landfarming was selected instead.

Solvent extraction was eliminated due to excessive cost.
                          W£re selected?  If the cleanup goal was based on lan AFAR, what was that
               What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (ppm)
ARAB: or Other Basis
Carcinogens
Asbestos
Benzo(a)anthracene
Benzo(a)pyrene
Benzo(a)fluoranthene
Benzo(k)fluoranthene
Chrysene
Lead
Lead
Remove all
9
0.9
0.9
0.9
90
500 .
1000
Background
Risk8*
Risk8
Risk8*
Risk8*
Risk8*
£>SWERC
OSWER"
                                             -7-
                                                                                         963

-------
               'Health-based risk levels correspond to an excess upper bound individual lifetime
               cancer risk of 10"*. The health based risk estimates were developed by EPA Region 6.
               bSince these contaminants have no slope factors, their cleanup levels are based on the
               contaminants' relative potency to benzo(a)pyrene.
               •EPA Office of Solid Waste and Emergency Responses Directive #9355.4-02 for soil
               up to 2 feet in depth.
               dEPA Office of Solid Waste and Emergency Responses Directive #9355.4-02 for soil
               below 2 feet in depth.

                                                                                                 t
13.    'Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      Thin spreading

       Standard technologies eliminated because of cleanup goals include:

       •      Stabilization


14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were conducted to study the effectiveness of landfarming and thin              •''IIP "*i
       spreading for waste pit soil and hydrocarbon soil. It was determined that landfarming could        "™  ;J
       reduce site contaminants by 90 percent with the addition of nutrients and moisture and meet
       cleanup levels. Thin spreading was shown to be ineffective  for the site's waste because while
       waste biodegraded rapidly initially, additional nutrients and moisture needed to be added to
       complete the process.  The addition of nutrients and water are not included in the thin
       spreading technique.                                                                        :


75.    Wliat measures/criteria were used to compare alternatives?

       The following measures  were used to compare the alternatives:

               Proven reliability
               Impact on future populations


16.    How are measures compared?                  .        •
                                        i          '-          --  •      '             v      •
       Because the area is expected to be used for future residency, it was important to permanently
       reduce contaminant levels for the safety of future populations. The reliability of remedies,
       based on results of the treatability studies, was •also a concern.  In this case, landfarming was
       shown to be effective and thin spreading ineffective.  Furthermore, stabilization had uncertain
       reliability and effectiveness over the long term  and was eliminated for these reasons.
 964
                                               -8-

-------
17.
What technical considerations were factors in selecting a remedy? VVere technical
considerations primary in the selection of the remedy?             i

Analyses of composite waste samples determined that they were deficient in nitrogen and
phosphorous. Therefore, for biodegradation to occur, nutrients and water had to be added to
the waste. While thin spreading was initially proposed in the PS, it was later rejected in favor
of landfarrmng, which does not require the addition of nutrients and water
                                           -9-
                                                                                      965

-------
                    29th and Mead Ground Water Contamination
                                          GU-2         -.-'..•

                                     Wichita, Kansas
                                         Region 7
GENERAL SITE INFORMATION
1.
2.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (rag/kg)

Trichloroethene              13
1,1,1-Trichloroethane          6.1
Tetrachloroethene            0.041
cis-l,2-Dichloroethene        0.52
1,1-Dichloroethene     ,       0.37
Toluene                     140
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
N/A '
2/21/90
7/2/92
9/29/92
                                                                Background

                                                   PRP-lead
                                                   PRPs:  The Coleman Company and
                                                          Evcon Industries
                                                   FS prepared by: Groundwater
                                                          Technology, Inc.
What volume, of material is to be
remediated?

The volume of material to be remediated included:

•      453,000 cubic yards of soil
3.     What type of site is this?

       Fabricated Metal Products.  The site is an industrial area occupied by two furnace and air
       conditioning systems manufacturing plants and an administration and engineering building.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

        Standard'technologies considered during the identification and screening of technically feasible
        technologies were: ,                        '

        Containment:         Capping (low permeability, asphalt, cpncrete, synthetic liner,    :
                            multilayered)      ,
        Chemical treatment:    Fixation/stabilization
        Disposal:          "  Excavation
                                                                                             I')
 966
                                     -1-

-------
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                       :

        Biological treatment:   Biodegradation
        Physical treatment:     Soil vapor extraction (SVE)        '        !
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify, costs.  After the RAAs have been
       formulated, costs are typically estimated,as part of a three-criteria.screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.                                                  ,

                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)     '
Alternative
RAA-2A
RAA-2C
RAA-3A
RAA-3B
RAA-3C
RAA-4A
RAA-4B
Innovative Technology
No further action/continued operation of
soil vapor extraction system
No further action/continued operation of
soil vapor extraction system/continue
ground water recovery/add another
recovery well
Expand soil vapor extraction system/
continue ground water pump and treat
Expand soil vapor extraction system/
south-end* enhancement of ground
water recovery system
Continue soil vapor extraction system/
enhance south-end ground water
recovery system
Expand soil vapor extraction system/
continue ground water pump and
treat/aquifer sparging
Expand soil vapor extraction system/ .
enhance south-end ground water
recovery system/aquifer sparging
Estimated Costs
3 Criteria
N/A
N/A
• • " i [•'
.1
N/A /
; N/A
•
N/A '
N/A
j
' N/A
' I •
'
9 Criteria
$772,164
$972,334
$1,450,513
$1,638,456
$2,042,339
$1,746,227
$1,799,523
                                             -2-
                                                                                                967

-------
Alternative
RAA-4C
Innovative Technology
Expand soil vapor extraction system/
expand ground water recovery
system/additional south-end ground
water pump and treat/aquifer sparging •
Estimated Costs
3 Criteria
N/A .,
9 Criteria
$1,711,410
       *In the southern boundary area.
7.      How did the cost(s) compare to standard technologies?
        *                                                '
                 Cost Estimates for KAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2B
RAA-2D
Standard Technology
No action
No further action/continued ground
water pump and treat
No further action/continue ground water
recovery/additional south-end
enhancement of ground water system
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$623,310
$802,953
$983,131
                                                                                                      D
8.     If a standard technology was chosen, why?

       A standard technology was not selected.
9.     If an innovative technology was chosen, why?

       RAA-3B was selected because it provides adequate protection of human health and the
       environment by removing contaminants in the soil and ground water and thus eliminating the
       risk posed by those contaminants.  Overall concentrations of VOCs will decrease over time
       with implementation of the preferred alternative. This alternative provides long-term
       effectiveness and permanence by significantly reducing the volume and mobility of VOCs in
       the soils through soil vapor extraction (SVE) and preventing future migration of VOC
       contaminants into ground water. Enhanced ground water recovery assures hydraulic control,
       providing permanent control of the migration of VOC contaminants.  The preferred alternative
       reduces soil and ground water contaminants through treatment and recovery (volume); controls
       the migration of contaminants from the site by providing hydraulic controls, which prevent
       contaminated ground water from escaping from the property (mobility); and provides for
       treatment of contaminated ground water and soil to acceptable levels determined by EPA and
       the Kansas Department of Health and the Environment (toxicity).  The selected alternative
       promotes the utilization of a treatment for both  soil and ground water.  Reducing VOC
968
                                             -3-

-------
         contaminants in soil (volume and mobility) greatly increases the overall effectiveness of
         cleanup and decreases the time needed for cleanup. It was estimated that the preferred
         alternative will accomplish cleanup within 10 to 20 years. The known effectiveness of SVE
         supported the expansion of this technology in the chosen alternative.  Pilot studies conducted
         on SVE at the site demonstrated the implementability of this technology and the existing SVE
         has been documented to remove 14,323 pounds of VOC contaminants in less than 5 years
         This alternative might, however, pose technical difficulties given the Ideations of source areas
         in relation to on-site buildings and operations.  When considering the rapid and dramatic
         reduction in  soil and ground water contaminants provided by the inclusion! of one additional
         ground water extraction well and the enhanced SVE system, the cost of this alternative is not
         prohibitive when compared to the costs of implementing other alternatives. In addition the  *
         preferred alternative prevents further ground water contamination and migration of
         contaminants for a relatively low increase in cost over less effective remedies.  The selected   '
         remedy is cost effective because it provides the best balance among the evaluation criteria  It
         provides a higher degree of overall protection man the less costly alternatives because it treats
         all known source areas and prevents the migration of contaminated ground water from the
         area,       ;       • '    ,.     .       •  .   ...    .       ..  ' . •     • I •   •  .
 10.
 If an innovative technology was not chosen, why not? At what stage -was the innovative
 technology eliminated?                                            \.

 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages:  during the initial screening; during the screening of the ttiree criteria of
 effectiveness, implementability, and cost; or during the detailed evaluation.

 Innovative technologies eliminated during the initial screening include the following:

 "      Biodegradation was eliminated because it is not well established for the remediation of
        chlorinated aliphatic compounds. In addition, implementation of the technology
        beneath building structures might be impractical and the process is already naturally
        occurring.                                                 I             .    •

 Innovative technologies eliminated during the screening of the three criteria include the
 toilqwing:
                                                    " •              !        •          '
 *      None                                                      I
   '.    -   '                 '        -  -       •                •    -i'-  '  . \    if    • .

 Innovative technologies eliminated during the detailed analysis include the following:

 • '     None,        -       '•'•''     '        '       '      '  '   ''(  .  .       .     -  :•
11.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so
which criterion? Which of the criteria supported the use of a standard technology?        '

The most heavily weighted criteria in selecting this remedial alternative were protection of
human health and the environment; the reduction of site,contaminant toxicity, volume and
mobility; and long-term effectiveness and permanence.  The chosen alternative actively
                                             -4-
                                                                                           969

-------
      addresses contaminants in both the soil and ground water, thereby providing a very effective
      and permanent elimination of site risks.                                              _
72.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
                                                                         1            '
       No source control cleanup goals were developed for this site. .

       No specific ARARs exist for .contaminated soil. Performance criteria for the expanded SVE
       system, however, will be developed during remedial design. Performance standards will be
       based on monitoring data from the performance of the existing SVE system.  This will both
       allow for the development of the criteria for the expanded SVE system and will determine
       when operation of the existing system may be discontinued.


13.    Was  the innovative technology eliminated because of the cleanup goals? Could the standard
       tecttnology meet the  cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

        •      None

        Standard technologies eliminated because of cleanup goals include:

        •      None                                           .
                                                                                                          i	'	
14.    Were treatability studies conducted on the innovative technology or standard technology?

       A treatability study was conducted to investigate soil vapor extraction. This test revealed that
       SVE will remove contaminants from site soils.
75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Risk reduction                           •
             Cost-effectiveness
             Time to design/construct/operate
             Proven reliability
76.     How are measures compared?                                                   '.'••'

        The chosen alternative was preferred because it reduces site risk by eliminating the source of
        ground water contamination from the soil. The treatment proposed in this alternative will meet
        cleanup requirements within a moderate amount of time (10 to 20 years) because df the
        addition of SVE systems and ground water treatment.  Alternatives that would accomplish
        cleanup in a slightly shorter time were more expensive and therefore not considered cost
 970
                                              -5-

-------
       effective.  The reliability of the SVE technology also supported the choice of SVE as an
       appropriate technology. On-site SVE pilot studies have conclusively sho'ivn the effectiveness
       of SVE on the soil contamination.  The existing SVE has been documented to have removed
       14,323 pounds of VOC contaminants in less than 5 years.    ^      i             .
17.     What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
          -                     •               .  '                -I-         '

       No technical considerations were primary in selecting a remedial alternative.
                                            .6-                                              971

-------
                             E.I. Dupont De Nemours & Co.
                                    (County Road X23)

                                      West Point, Iowa
                                          Region 7
                                                                                                          8,1,
 GENERAL SITE INFORMATION

 L      What  were  the  principal  contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum  concentrations   of   principal
        contaminants were:
       Soil (rag/kg)

       Lead
       Selenium
       Cadmium
38,950
177
510
2.     What volume of material is to be remediated?

       The volume of material to be remediated
       included:

       *     14,200 cubic yards of soil
                                     Site History
                        NPL Proposed:
                        NPL Final:
                        FS:
                        ROD:
                     6/88
                     9/90
                     1/16/91
                     5/28/91
             Background   --

PRP-lead
PRPs:  E.I. Dupont De Nemours
FS prepared by: Woodward-Clyde
       Consultants
3.     What type of site is this?

       Chemicals and Allied Products. A paint waste disposal site.
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                                 ;

       Access restriction:     Fencing, deed restrictions
       Containment:         Cap (soil, clay, soil/synthetic membrane, asphalt, concrete, multilayer),
                            revegetation, slurry wall, grout curtain, sheet piling, vibrating beam, grout
                            injection
       Chemical treatment:   Stabilization/solidification
       Thermal treatment:     Incineration (rotary kiln, fluidized bed, multiple hearth, circulating bed,
                            plasma arc torch, high temperature wall reactor, and infrared)
       Disposal:             Excavation, off-site RCRA landfill, on-site landfill, on-site waste piles
  972
                                            -i-

-------

        Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically feasible
        technologies were:                                                              •
       Biological treatment:
       Chemical treatment:
       Thermal treatment:
In situ aerobic biodegradation, anaerobic biode^adation, white rot fungus
Soil washing (solvent),  soil vapor extraction, liquid  gas extraction,
dehydrochlorination, dehalogenation, electronjemforane  reactor process
(chelation)                                ,
In  situ  vitrification,  heated  air  stripping,  low temperature  thermal
treatment, wet air oxidation           '.''',.'            ,   ,•
6.      What was the cost estimate-for the innovative technology?           i

       During the initial screening process, in which technically feasible technologies are identified (prior
       to :the formulation of RAAs), the FS  does not quantify costs.  After"the RAAs have been
       formulated, costs are usually estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation.  In this
       case, the estimated costs were calculated during an evaluation based on nine criteria established
       by the NCP:  long-term effectiveness and permanence; short-term effectiveness; compliance with
       ARARs; protectiveness of human health and the environment; reduction in contaminant mobility,
       toxicity, or volume; implementability; cost;  state/support agency acceptance;  and community
       acceptance.  The RAAs discussed in the ROD  are presented parenthetically under the  list of
       alternatives.                                                      j
           .'           -                        ,                        • ! '         '• '
                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-E2
RAA-E3
RAA-E4
1. ' , - :• '
Innovative Technology
Excavation/aerobic biodegradation/
soil washing
Excavation/heated air stripping/soil
washing
Excavation/soil washing
Estimated Costs
3 Criteria
N/A
'.:N/A
- j .
" N/A '"•
9 Criteria
eliminated
eliminated
eliminated
                                             -2-
                                                              973

-------
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-A
(RAA-1)
RAA-B
(RAA-2)
RAA-C1
(RAA-3)
RAA-C2
RAA-C3
(RAA-4)
RAA-Dla
(RAA-5)
RAA-Dlb
(RAA-6)
RAA-D2 '
RAA-E1
(RAA-7)

Standard Technology
» :
No action
Fencing/deed restrictions/periodic .
monitoring •
Fencing/deed restrictions/periodic
monitoring/clay and soil, cap
Fencing/deed restrictions/periodic
monitoring/asphalt cap
Fencing/deed restrictions/periodic
monitoring/multimedia cap
Excavation/off-site disposal at RCRA
landfill
Excavation/on-site or off-site
treatment/off-site disposal at RCRA
landfill
Excavation/off-site incineration at
RCRA facility
Excavation/on-site stabilization and
fixation
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$0
eliminated
$1,800,000
eliminated
•'"•%!- ' .
$2,000,000
$8,000,000
$10,700,000
{
•eliminated
$1,200,000
 8.      If a standard technology was chosen, why?

        Excavation with on site stabilization and fixation was selected because: 1) long term risks
        associated with direct contact and migration would be eliminated since contaminants bond to
        solidified matrix and there would be a reduction in surface area exposed to ground water and
        surface water, 2) proven and reliable technology^ 3) cost, 4) preference for treatment, 5) easier
        to implement administratively because it requires less coordination with relevant agencies, 6)
        can be implemented quickly, and technically easy to implement.          .
  974
                                              -3-

-------
 9.      If an innovative technology was chosen, why?                      ;

        An innovative technology was not chosen.                         ;


 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                         '[•''-
                             '        •          - .     '             '     j   ..---.•.    (• •  :
        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evalujition.
                               1                                          .          •         '•
        Innovative technologies eliminated during the initial screening include the following:

        •      Soil vapor extraction was eliminated because it would be ineffective due to the site
               soil's low porosity.       •                        .           .
        •      Liquid gas extraction was eliminated because the technology has not been proved
               effective.
        •      Dehydrochlorination was eliminated because it would not be applicable to site
               contaminants.                           .                  -j
        •      Dehalogenation was eliminated because it would not be applicable! to site
               contaminants.  ,
        •      White rot fungus was eliminated because the technology has not been proved effective.
        •      Electromembrane reactor process was eliminated because the technology has not been
               proved effective.
        •      Wet air oxidation was eliminated because the technology has mot teen proved
               effective.
        •      In situ vitrification was eliminated because the technology has not been proved
               effective,                                                  j
       •     Anaerobic biodegradation was eliminated because it is more effective in degrading
               halogenated compounds and less proven on other compounds, and it is less reliable
              than aerobic methods.                                 ."'!'•'
       •      Low temperature thermal treatment was eliminated because it does not treat metals;
       •      Centrifugal reactor was eliminated because it is an unproven technology.
       •      High temperature slagging was eliminated because there is no fuel value to soils.
       •      Pyrolysis was eliminated because there is no fuel value to the soils.
       •      Vitrification was eliminated because it is an unproven technology.
                                                    '                    h
       Innovative technologies eliminated during the screening of the three criteria include the
       following:

       •      In situ aerobic biodegradation with soil washing was eliminated because its
              effectiveness in removal of target compounds is questionable; treatability testing would
              be required; implementing combination of treatment technologies is questionable; soil
              washing is unproven; treatment may not meet Land Disposal Regulations; high capital
              and operation and maintenance costs.                        '
       "      Heated air stripping with soil washing was eliminated because its iimplementability is
              questionable; treatability studies would be necessary; leachate treatment and/or disposal
              would be necessary; may not meet Land Disposal Restrictions; ijiigh capital costs of
              operation and. maintenance.
       •      Soil washing was eliminated because it is not a proven technology for removing metals


.    ''            '.    ,     •     '             -4-             ,          'I    .  '  '        •   '"  '
975

-------
11.
12.
 13.
       at high enough efficiency to adequately lower metals concentrations; implementability
       is questionable; treatability studies would be required; Land Disposal Regulations may
       not be met; high capital and operation and maintenance costs.

Innovative technologies eliminated during the detailed analysis include the following:

•      None                                ,


Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?

The most heavily weighted criteria in selecting a standard technology were protectiveness of
human health and the environment, long-term effectiveness, implementability and cost. No
innovative technologies were retained for detailed analysis.


What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Lead
Cadmium
350
20
EPA Advisory"
Risk
Noncarcinogens
Selenium
10
Risk
        *A health-based cleanup level for lead was determined by utilizing an equation that
        back calculates soil lead levels given a specific target blood lead level. A target blood
        lead level of 8 ug/dL was selected because it is below the EPA advisory range of 10
        to 15  ug/dL for warranting concern.


 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      Soil washing

 Standard technologies eliminated because of cleanup goals include:
                                              •'   '."                      *
 »      None
 976
                                        -5-

-------
 14.
 Were treatability studies conducted on the innovative technology or standard technology?

 No treatability studies were conducted.
 75.
 What measures/criteria were used to compare alternatives ?

 The following measures were used to compare the alternatives:

        Cost-effectiveness
        Proven reliability
        Preference for treatment (vs. containment)
16.     How are measures compared?                               .     ]

        Two alternatives (RAA-E1 and RAA-Dlb) provided the greatest protection to human health
        and the environment. Of these two alternatives, RAA-E1 was chosen because it is less
        expensive and therefore the more cost-effective alternative. Other .proposed alternatives (RAA-
        Dl, RAA-D2) were eliminated because their high costs were not paralleled by a proportional
        increase in protectiveness. Proven reliability was another principal factor in the selection of a
        remedy. The selected alternative was considered to be a reliable treatment Conversely
        technologies such as aerobic biodegradation and soil washing were eliimnated because their
        reliability was not proved for the site's contaminants.  The selected alternzitive employs a
        treatment technology. Several other alternatives were eliminated because lihey would not
        ensure long-term protection through treatment of the source.
17.
What technical considerations were factors in selecting a remedy?
considerations primary in the selection of the remedy?
                                                                      Wt re technical
       The low porosity of site soils was a technical consideration in the	„
       extraction, an innovative technology. No technical considerations were
       selection of a remedy.
                                                             elimination
                                             -6-
      of soil vapor
primary in the
                                                                                          977

-------
                                      Ellisville Site
                            (Amendment for Bliss portion of site)

                                     Ellisville, Missouri
                                          Region 7
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       2,3,7,8-Tetrachlorordibenzo-p-dioxin 0.087
2.      What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       »      7,000 cubic yards of soil
3.      What type of site is this?                 .

       Waste Oil. A former waste oil disposal site.
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                                                                         N/A
                                                                         10/81
                                                                         7/26/91
                                                                         9/30/91
                                                                 Background

                                                    EPA Fund-lead
                                                    PRPs:  Syntex, Northeast Pharmaceutical
                                                           and Chemical Company, Indepen-
                                                           dent Petrochemical Corporation
                                                    FS prepared by:  CH2M Hill
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Deed restrictions, warning posts, fencing
       Containment:          Soil cover, clay cap, synthetic membrane cap, clay geomembrane cap,
                             revegetation, regrading           ,
       Physical Treatment:    Quicklime, ultraviolet photolysis
       Thermal treatment:     Rotary kiln incinerator, infrared incinerator, fluidized bed incinerator*
                             multiple hearth incinerator
       Disposal:            • Excavation, on-site storage, off-site storage
 978
                                             -i-

-------
 6.
 7.
                                                    ,             ' I'               - '
  Way an innovative technology considered in the FS?  If so, which technology?

  Innovative technologies considered during the identification and screenim' of technically
  feasible technologies were:                                      1                 ,

  Biological treatment:   Biodegradation            -                 |
  Chemical treatment:    APEG dechlorination, solvent washing      ;|
  Thermal treatment:     Molten salt, supercritical water oxidation, in situ vitrification, steam
                        stripping, microwave  volatilization, plasma pyrolysis, wet air oxidation
   • '   '        "      '          /             •                   "!      •               >

  What was the cost estimate for the innovative technology?           |.

  During the initial screening process, in which technically feasible technologies are identified
  (pnor to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
  formulated, costs are estimated during an evaluation based on nine criteria, established by the
.' NCP and again in the ROD:  long-ierm effectiveness and permanence;1 short-term
  effectiveness; compliance  with ARARs; protectiveness of human health anid the environment-
  reduction in contaminant mobility, toxicity, or volume; implementabiliiy; cost; state/support '
  agency acceptance; and cpmmunity  acceptance).                     '
                     '           • •         "                   •"*  i-    ••.';'
  No innovative technologies were proposed for remedial alternatives.


  How did the' cost(s) compare to standard technologies?              !
            •  -    ,            •   "     _      • •        '             • i "  -      •.   •
           Cost Estimates for RAAs That Include Standard Technologies
                      (selected remedial alternative is in  bold)
Alternative
RAA-1
RAA-2
RAA-3
,\
RAA-4
.
Standard Technology
No action/fence maintenance/long-term
air monitoring
Improve vegetative cover/erosion
control .
Excavation/backfill and revegetate
site/on-site storage/fence/long-term
monitoring
Excavation/rotary kiln incineration/
ash disposal as appropriate, possibly
at RCRA facility
Estimated Costs
9 Criteria
$0
$1,130,000
$13,70p,OCK)
$17,53li),000
ROD
$0
$1,130,000
$13,700,000
$17,530,000
8.      If a standard technology was chosen, why?
         • .    ,    '   '         -!            .                              !                ' ^

       RAA-4 was selected because thermal treatment is the only demonstrated technology with
       proven effectiveness at destroying dioxin on a full scale.  RAA-1 was eliminated because it
                                             -2-
                                                                                         979

-------
       would not be protective of human health and the environment.  Although RAA-2 and RAA-3
       are less costly than the selected remedy, they would only reduce mobility and would provide a
       low degree of permanence because contaminants are not destroyed and continual maintenance
       of containment systems would be required.


9.     If an innovative technology was chosen, why?
                                                                                                          i
       An innovative technology was not chosen.                       ,   •                                  I

                                                                                              --''-.    i"'"
                                                                      , .     . '                              i-
10.    If an innovative technology was not chosen, why not? At what stage was the innovative                    j
       technology eliminated?            '                                  ,                                ,

       Innovative technologies could be eliminated, from the remedial technology selection process at             j
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.                           .    |

       Innovative technologies eliminated .during the initial screening  include the following:
                                                   *                .     • >          •     , •     .            >
                                                                            •
       •      Molten salt was eliminated because the technology has not been proven effective for
               dioxin, nor has it been developed for full-scale application.
       •      Supercritical water oxidation was eliminated because the technology has not been
               demonstrated on  a  scale sufficient to treat the volume of contaminated soil at this site.      ^.^
       •      In situ vitrification was eliminated because it would not be feasible for surface soil         ||l|^ "\
               contamination.            ,                    .        :                               • *^,  ^
       »      Dechlorination was eliminated because it has not been developed for full-scale use.
       •      Biodegradation was eliminated because it has not been proven effective for materials
             •  with low concentrations of contamination.-
       •      Microwave volatilization was eliminated because it has not been proven effective for
               dioxin wastes.
       •      Steam strippingwas eliminated because"it would not be effective for dioxin waste.               j
        •      Solvent washing  was eliminated because it would not be feasible for such a large
               quantity of soil.        .                                                                     j'
        •      Plasma pyrolysis was eliminated because it is not applicable to soils..                            !
        •      Wet air oxidation,  although considered a feasible technology, was not carried forward
               from the initial screening into a remedial action alternative. No reason for excluding              |
               wet air oxidation was given.

        No innovative technologies were eliminated during the three-criteria screening or during                  f
        detailed analysis.                                                                      ;           ,


 II.    Which of the nine criteria  were weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The protectiveness of human health and the environment and long-term effectiveness through a
        permanent solution were the most heavily weighted criteria in selecting a standard technology.
        No innovative technologies were evaluated in the nine-criteria, evaluation.          .


   980

-------
  12.
 13.
 14:
  What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?
                      Contaminant
                                   Cleanup Level (ppb)
                                                                  ARAR br Other Basis
                  Carcinogens
                 Dioxin
                                                   1
                                                           RCRA1'and ATSDR"
        •Resource Conservation and Recovery Act Land Disposal Restrictions (40 CFR
        268.41).                                            ,           ,   .   •       .  •
        "Agency for Toxic Substances and Disease Registry health consultation issued in 1986.

 For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to W*
 was acceptable. For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.


 Was the innovative technology eliminated because of the cleanup goals? If a standard
 technology was selected, could it meet the cleanup goals?             ]

 Innovative technologies were eliminated because they were determined not to be feasible for
 dioxm-contaming soils or had unproven effectiveness.  They were not eliminated because of
 the cleanup goals at the site.  The standard technology selected, incineration, could meet
 cleanup goals for the site.                                          h
 Were treatability studies conducted on the innovative technology or staridard technology?

Nb.treatability studies were conducted.   ,
15.
What measures/criteria were used to compare alternatives?

The following measures were used to compare the alternatives:

       Proven reliability
       Permanence
       Cost effectiveness
16.     How are alternatives compared?                '' •     •              i

       Most innovative and standard technologies were eliminated in the initial 'screening based on a
       lack of proven reliability for treating dioxins in soils to required levels.  The RAAs were
       compared primarily on the basis of permanence. Capping and on-site storage would not
       destroy dioxins and would be dependent on continued maintenance to prevent future releases
       Even though the selected alternative, incineration, was the most costly remedy it was
       considered more cost-effective because it provides a permanent remedy for the dioxin
       contaminants destroyed.                             -                !
                                             -4-
                                                                                                981

-------
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       The site lies in a relatively flat valley that is a groundwater recharge area.  However, dioxin
       was not found to be bound tightly in surface soils and was not contaminating groundwater.
       Land use in the vicinity is a mixture of residential, rural, and recreational.  Although
       increasing residential development in nearby areas may have contributed to the emphasis oh a
       permanent remedy, technical considerations do not appear to be primary in the selection of the
       remedy at this site.              '               .
   982
                                              -5-

-------
         Containment:

         Thermal treatment:
         Disposal:
                       Capping (RCRA Subtitle C landfill cap, Nebraska sanitary landfill cap)
                       grading, revegetation                      ;
                       Incineration (on site, off site)
                       Excavation, RCRA landfill disposal (on site,! off site)
         Was an innovative technology considered in the FS?  If so, which technology?
                        -                            -  -         .        j •
         Innovative technologies considered during the identification and screening of technically   "
         feasible technologies were:
         I                                               •          '»!*••          '   '

         Biological treatment:   In situ bioremediation                     i
         Physical treatment:    Soil vapor extraction
 6.
7.
 What was the cost estimate for the innovative technology?

 During the initial screening process, in which technically feasible technologies are identified
 (prior to the formulation of RAAs), the FS does not quantify costs, jjtfter the R^ havg
 formulated, costs are typically estimated as part of a three-criteria screening process
 (effectiveness, implementability, and cost) to identify alternatives that! merit a more detailed
 evaluation  In this case, the estimated costs were calculated during an evaluation based on
 nine criteria established by the NCR

          Cost Estimates for RAAs That Include Innovative Technologies
                     (selected remedial alternative is in bold)     '
           Alternative
         RAA-5
                          Innovative Technology
                   Soil vapor extraction (SVE)
                                                                       Estimated Costs
                                                                   3 Criteria
                                                                      N/A
 9 Criteria
 $1,095,000
How did the cost(s) compare to standard technologies?
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
           Alternative
         RAA-1
         RAA-2
         RAA-3A
                          Standard Technology
                  No action
                  Access restrictions/ground water
                  monitoring
                  Access restrictions/ground water
                  recovery/air stripping/reinjection
                                                                       Estimated Costs
                                                                  3 Criteria
                                                                     N/A
                                                                     N/A
                                                                     N/A
9 Criteria
                                                                             $0
 $557,000
$2,013,000
984
                                             -2-

-------
Alternative
RAA-3B
RAA-3C
RAA-3D
RAA-4A
RAA-4B
RAA-4C
RAA-4D

Standard Technology
Access restrictions/ground water
recovery/air stripping/reuse
Access restrictions/ground water
recovery/UV oxidation/reinjection
Access restrictions/ground water
recovery/UV oxidation/reuse
Access restrictions/ground water
recovery/air stripping/reinfection/
Nebraska sanitary cap
Access restrictions/ground water
recovery/air stripping/reuse/Nebraska
sanitary cap
Access restrictions/ground water
recovery/UV oxidation/reinjection/
Nebraska sanitary cap
Access restrictions/ground water
recovery/UV oxidation/reuse/ Nebraska
sanitary cap
Estimated Costs
3 Criteria
N/A
s N/A
N/A
N/A
N/A
/•• .
N/A
N/A ..
9 Criteria
$2,394,000
$3,666,000
$3,954,000
$3,006,000
$3,364,000
$4,635,000
$4,924,000
8.      Jf a standard technology was chosen, why?

       The exact designation of the selected alternative is never specified but it appears to be one of
       the RAA-4 alternatives.  The selected.alternative includes improving the existing cap as
       necessary and in accordance with the Nebraska Solid Waste Management Rules (NDEC Title
        132, Chapter 6) which appears to be equivalent to a Nebraska sanitary landfill cap as proposed
       in RAA-4. Further, the technology for ground water treatment, while still undecided, will
       consist of either UV .oxidation or air stripping, and the treated water will be either reinjected
       or reused.  Thus, the existing cap will be evaluated and improved as necessary. The improved
       cap provides containment and minimizes infiltration through the. landfill to ground water which
       will decrease the volume of contaminants.  Additionally, the surface will be revegetated to
        decrease erosion, and access restrictions will be implemented to maintain cap integrity.  The
        selected remedy will be protective of human health and the environment because the interim
        actions reduce contaminant concentrations in the aquifer to levels at or below 10"4 cancer risk.
        In  addition, the interim actions will stabilize the migration of ground water contaminants and
        prevent further degradation of the ground water through the rapid mass removal and hydraulic
        plume control.  Thus, the threat to private well users and the exposure from irrigation wells
        will be abated. This alternative meets appropriate ARARs, is easily implementable, and is cost
        effective.                                                                 '•   :    -,

        The SVE component provided for in the June 1991 Proposed Plan will not be.implemented at
        this time because upon reevaluation of the site, EPA determined that insufficient information
        regarding the amount of contamination in the vadose zone was available and therefore the high
                                               -3-
                                                                                                  985

-------
        cost of SVE could not be justified.  Monitoring of the vadose zone wijl be conducted during
        the implementation of the interim action and EPA will reevaluate the infoirmation gained to
        determine the need for SVE as an additional source control measure.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not selected.
10.
11.
        If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the tliree criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:
                                                  *                       I .         •

        •      In situ bioremediation was eliminated because the primary conliaminants of concern are
               chlorinated organics, which have a slower biodegradation rate than non-chlorinated
               organics and therefore would have an increased remediation time.  Furthermore,
               chlorinated organics might degrade into more toxic breakdown products.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                      , j.
                                               ••.-'•            •     '     I ••     '     :
        •      None  -             •-..-,..         "     •"  •'     ,|     ''..-'••    -   .

        Innovative technologies eliminated during the detailed analysis include the following:

        «      Soil vapor extraction was eliminated because there was insufficient information
               available concerning me amount of contamination present in the vadose zone and
               therefore it was not possible to justify the cost of SVE.
       Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
      which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment and cost were the criteria weighted most
       heavily in selecting a remedial alternative. The selected alternative addresses the main threat
       to human health posed by ground water and reduces migration of source contaminants through;
       containment. Since the concentration of contaminants of concern were ;tiot well established,
       the high cost of soil treatment with the innovative technology, SVE, coiild not be justified.'

12.
      What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
      ARAR? What risk level was selected to establish cleanup goals?       i
                       \    '      '            '     -            ,          | •'> i         •      _
      Cleanup levels were not established.
986

-------
f
•\
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       tecltnology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •      None               ,                                                  '

       Standard technologies eliminated because of cleanup goals include:

       •      None                                                          •-•..'


14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.                                                ,


75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:                   ;

             Risk level achieved


16.    How are measures compared?

       This ROD proposes an interim action; therefore, the action was  aimed at achieving an
       acceptable excess  cancer risk.  Since the degree of underlying contamination in, the vadose
       zone was uncertain, source treatment was postponed until further information could be   i
       attained.  The selected remedy reduces risk to an acceptable level and reduces migration of
       contaminants from soil to ground water.


17.     What technical considerations-were factors in selecting a remedy?. Were technical
       considerations primary in the selection of the remedy?

       Technical considerations were not primary in selecting a remedial alternative.
                                                        -5-
                                                                                                   987

-------
                                 John Deere & Company
                                Qttumwa Works Landfill

                               Ottumwa, Wapello County, Iowa
                                          Region 7
  GENERAL SITE INFORMATION

  1.     What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?
                                i
        Maximum concentrations of principal
        contaminants were:

        Soil and Waste Material (rag/kg)
 Total carcinogenic PAHs
 Total PAHs
 Naphthalene
 Arsenic
 Beryllium
 Lead
 Aluminum
 Zinc
 Copper

 Sediments (mg/kg)

 Arsenic
 Barium
Cadmium
Chromium
Nickel
  19
  84.5
  1.2
  26
  3
  810
  7,500
  860
-  24
                                   0.64
                                   8.7
                                   1.2
                                  '3.5
                                   8.5
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                                       6/88
                                       2/90
                                       7/10/91
                                       9/23/91
                                                                Background

                                                   PRP-lead
                                                   PRPs:  John Deere & Company
                                                   FS prepared by:  Geraghty & Miller,
                                                          Inc.
       What volume of material is to be remediated?
                                                                    I

       •      670,000 cubic yards of contaminated soil, waste material, and sediments
3.     What type of site is this?
                                                              ''-  '   .""I '               • '
  :                  '         '       '         •        - •              '       •
       Fabricated Metal Products.  An active agricultural equipment manufacturing and assembly
       facility.  Land use in the area is predominantly residential with wetlands located within 1 000
       feet of the site across the Des Moines River. All of the site lies within the 100-year, floodplain
       or the  Des Moines River.
988
                                           -1-

-------
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
       Access restriction:

       Containment:   •
                     Institutional restrictions on land use and land access (deed restrictions),
                     fencing, environmental monitoring                              .
                     Capping (concrete, asphalt, solid waste cap, RCRA subtitle C cap),
                     grouting
Chemical treatment:   In situ stabilization/solidification (kiln dust reagent, fly ash reagent,
                     silicate reagent, portland cement reagent, synthetic reagents)
Thermal treatment:    Plasma arc incineration, on-site incineration (fluidized bed, rotary kiln)
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Bioremediation (in situ, heap leaching)
        Chemical treatment:    Soil flushing (water solution, surfactant solution), chemical oxidation
        Thermal treatment:     In situ vitrification, soil vapor extraction            s


 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, the costs were calculated during an evaluation based on nine criteria
        established by the NCP. No innovative technologies were incorporated into RAAs.
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is ira bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Institutional controls/ground water
monitoring
Concrete cap/institutional controls
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$0
$103,600*
$2,667,900 >
                                               -2-
                                                                                         989

-------
Alternative
RAA-4
Standard Technology
In situ stabilization/solidification/
concrete cap/institutional controls
'Estimated Costs
3 Criteria
N/A
9 Criteria
$26,470,100
          The total present worth cost of implementing RAA-2 is estimated to be 354,000 in the ROD
          because ground water monitoring is not included. The total present worth cost in the ROD is
          based solely on the cost of lodging deed restrictions.
  8.     If a standard technology was chosen, why?                         -
                                                  .                •''-.• 1''         • '
         The RI shows that contaminant levels in all media are low enough to allow unlimited use of
         the site and affected media with the exception of children exposed directly to the waste
         material.  The selected remedy, RAA-2, would be protective of human health by providing
         institutional controls that require maintenance of the existing 8-foot high chainlink fence
         topped with barbed wire;  RAA-2 also requires lodging deed restrictions, which prevents the
         development of residences or other future on-site exposures.  These measures ensure that in
         the long term children are not exposed to site waste, thereby preventing the only potentially
        , unacceptable exposure scenario from occurring.  In addition, short-term risk will not be
         increased  during implementation of the selected remedy because no construction activities are
         required and an effective perimeter fence is" already in place. Finally, [the selected remedy is
         cost-effective because its overall effectiveness is proportional to its cost, and it  is the least
         costly of remedies that were judged to provide equal protection of human health.
  9.      If an innovative technology was chosen, why?

         An innovative technology was not chosen.
  10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?
            I            ,'             -          •          •       i .'  -

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the tliiree criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
                                   i'          .-*..               i      -        •» ' -
Innovative technologies eliminated during the initial screening include the following:

•      In situ bioremediation was eliminated because it would be ineffective for inorganics
       and it would be difficult to evenly distribute nutrients and inoculate microorganisms
       throughout the fill material. In addition, in situ biological processeis are difficult to
       control and nutrient additives might migrate to the, underlying siquiifer.and contaminate
       ground water.   .
•      Bioremediation-heap leaching was eliminated because it would be ineffective for
       inorganics, might create unpleasant odors, and requires the complete excavation of the
       fill material, which could endanger human health and the environment.
990
                                               -3-

-------
       •     In situ vitrification was eliminated because the heterogeneous nature of the fill material
              might impede complete vitrification. Also, this technology is unproven for large-scale
              applications and might not be readily available.
       •     Soil vapor extraction was eliminated because it would be ineffective for removing
              inorganics and nonvolatile organics.
       •     Soil flushing (water solution and surfactant solution) was eliminated because of its
              limited effectiveness in removing low solubility organics and inorganics, and the fill
              material has not proved to be amenable to soil flushing.
       •     Chemical oxidation was eliminated because its effectiveness in treating inorganics is
              limited, and the technology has not been proved for treating solid material.
                                              i            '      '   •                 '         •  •
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                   .      "
                                                    '         '      '       ,     •  '        '•..
       •     None                                                                         '

       Innovative technologies eliminated during the detailed analysis include the following:

       •     None


11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the  innovative technology? If so,
       which criterion?  Which of the criteria supported, the use of a standard technology?    .

       The ROD states that the selected remedy RAA-2 represents the best balance of trade-offs
       among the alternatives. RAA-2 was selected over other alternatives because of its cost and                i
       shbrt-term effectiveness. The selected remedy is the least costly of remedies that were judged
       to provide equal protection of human health.  The costs associated with RAA-3 and RAA-4
       are considered by EPA to be excessive when compared with the marginal increase in                      ;
       protectiveness these alternatives would offer compared to RAA-2. The selected remedy
       provides a high degree of short-term effectiveness because no construction activities are ,
       required.  Risks associated with the present use of the site are not considered excessive and             "  '. •
       will not be increased by implementation of this alternative.  ,

                                                                                            ,  . .        - - .  • i -
12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?   .

       Federal and State cleanup goals for the contaminants of concern were not established.        '
                                                         -,       •   ,           '             ' _              , . ;„ c

13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                                                      •      ,       .
                                                                                  '•
                                                                                                '
       Innovative technologies eliminated because of cleanup goals include:        '                             |
                                                                          . i .         '                     . ,]•-	
       •      None
                                               .4-        . •"           .'   '.                    991

-------
       Standard technologies eliminated because of cleanup goals include:

       •     . None  '            •'            •'    :-."•-.          •    '!.  ..-''.-,.,           .   - —
                                  .           •                    "     "L           .'•   . -           -  ' •

14.     W,ere treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.                            L

75.     What measures/criteria were used to compare alternatives?         [                    .
                            '•--"'                '            ,'       'f •  .' .    '         .      ••'•..
       The following measures were used to compare the alternatives:      |

             Cost effectiveness                  .                            '                      .
             Waste left in place/institutional control
                   >••.'•,-'        ' -   •     '..  ••        •      }••.'   .-.  "  '    '-•••••
                                                                      i"            '                ..
16.     How are measures compared?                                    [

       The selected remedy is cost-effective because it provides overall effecitiveriess proportional to
       its cost.  The costs associated with RAA-3 and RAA-4 are considered by EPA to be excessive
       when compared with the marginal increase in protectiveness these alternadves offer compared
       to RAA-2. Data provided in the RI shows mat contaminant levels in all media are low, which
       allows all but children unlimited use of the site.  Results of the baseline risk assessment
       indicate that site conditions do not require treatment of contaminated soil/waste if children do
       not live on site or are not allowed similar exposure to the soil/waste material.  Institutional
       controls were considered adequate.       ".•'•••
                                                                      •!'•          '

17.     What technical considerations were factors in selecting a remedy? Were technical          ,
       considerations primary in the selection of the remedy?            .. i.
                                       •        •                  •-,)'••-,
       Technical considerations were not primary in selecting a remedy.  Thu presence of an aquifer
       underlying the site, however, was a factor. Biological treatment processes were eliminated
       because of the potential migration of nutrients into the aquifer.  The lieterogeneous nature of
       the fill material resulted in the  elimination of in situ vitrification.
 992
                                              -5-

-------
                                       Lee Chemical

                                      Liberty, Missouri
                                          Region 7
 GENERAL SITE INFORMATION
 1.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:         '    '
        Soil/Alluvial aquifer (mg/kg)

        Trichloroethylehe (TCE)
        1,1,1-Trichloroethane (TCA)
                                   11
                                   2
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     N/A
                     5/20/86
                     12/24/90
                     3/21/91
             Background

PRP-lead
PRPs:  City of Liberty
FS prepared by: Layne Geosciences,
       Inc.
       While the site soil is contaminated,,the FS
       and ROD consider the soil and the alluvial
       aquifer as a single medium throughout the
       screening process and definition of process
       options due to their close hydrogeologic
       relationship.
2.     What volume of material is to be remediated?                              .

       The volume of material to be remediated included:

       •      2.5 acres of soil                                           .


3.     What type of site is this?
                                                                          /

       Chemicals and Allied Products. Former water treatment plant and chemical repacking and
       distributing facility.
TECHNOLOGY SELECTION                              ,

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Fencing, deed restrictions
                                                                                             993

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:

       Biological treatment:   In situ bioremediation     >
       Physical treatment:    In situ aqueous soil flushing (giavity induced) flushing with clear
                             " water       •          ./''.•         !   ,';          ';
6.      What was the cost-estimate for the innovative technology?         j.

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementabilityj and cost) to identify alternatives that merit a more ^detailed evaluation.  The
        estimated costs then are recalculated during an evaluation based on nine criteria established by
        the NCP: long-term effectiveness and permanence; short-term effectiveness; compliance with
        ARARs; protectiyeness of human health arid the environment; reduction in contaminant
        mobility, toxicitjf, or volume; implementability; cost; state/support agency acceptance; and
        community acceptance.                                         i

                 Cost Estimates for RAAs That Include Innovative Technologies
                       i     (selected remedial alternative is in bold)
Alternative |
-RAA-4 I
i
' 1
RAA-5 ;
• ' S
1 •
RAA-6
RAA-7 |
i
Innovative Technology .
In situ aqueous soil flushing/fencing/
deed restrictions/ground water, air, and
surface water monitoring
In situ aqueous soil flushing/ground
water extraction/fencing/deed
restrictions/ground water, air, and
surface water monitoring
Same as RAA-4, plus in situ
bioremediation
Same as RAA-5, plus in situ
bioremediation
Estimated Costs
3 Criteria
$860,000
• t i
.i
$550,000
$950,000
. $640,000
' . • [
9 Criteria
$860,000
$550,000
$950,000
; $640,000
*" • •
   994
                                              -2-

-------
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Fencing/deed restrictions/ground water,
air, and surface water monitoring
Same as RAA-2, plus ground water
extraction
Estimated Costs
3 Criteria
$0
$814,000
$767,000
9 Criteria
$0 ,
$814,000
$767,000
8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
9,     If an innovative technology was chosen, why?

       The selected alternative includes in situ soil flushing; ground water extraction; fencing; deed
       restrictions; ground water, air and surface water monitoring.  This technology was selected:  1)
       to remediate site soils so that no further ground water contamination can occur, 2) technology
       is an enhancement to the remedy already being implemented at the site under a remediation
       plan currently in effect, 3) implementation time frame is substantially shorter, 4) cost, 5) state
       preference (this is a state lead site).

       Soil Flushing and bioremediation (RAA-7) was recommended for use in the FS, but was
       changed to RAA 5 in the Proposed Plan.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?        •                                    :

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation. •

       Innovative technologies eliminated during the initial screening include the following:

       •      None

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                 ,

       •      None
-3-
                                                                                               995

-------
        Innovative technologies eliminated during, the detailed analysis include the following:

        •      In situ bioremediation was eliminated due to the cost and time; needed to implement
               the treatment.                                             1
                                                                                                   J
 11.     Which of the nine criteria were weighted most heavily in selecting the\ technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,   -
        which criterion? Which of the criteria supported the use of a standard technology?

        Implementability and cost-effectiveness provided the basis for the selection of in situ aqueous
        'soil flushing.                            .                     ,       ,           ,

                                      •      "      '.        ' '•        '' •• {.  '   "        '•.-"'
 12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What  risk level was selected to establish cleanup goals?
13.
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens _
TCE
0.005
SDWA"
Noncarcinogens :
TCA -
0.2
SDWA
               Cleanup levels are based on the Safe Drinking Water Act (SDWA) because soil and
               the alluvial aquifer are considered a single media throughout the FS and ROD.

       For carcinogens, an excess upper bound individual lifetime cancer risk! of between 10"4 to 10"6
       was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
Was the innovative technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?                                 ;              .
                         •                        '                .'!  l
                                      .                       .    'i-"      •.••••
Innovative technologies eliminated because of cleanup goals include:   j

•  '    None   •..                         .            '    -  • ' '    1 .. •  '      '    -

Standard technologies eliminated because of cleanup goals include:

•      None     ,                        ,                        !
14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted. '.,•"•'
 996
                                              -4-

-------
15,    What measures/criteria were used to compare alternatives?                         ^

       The following measures were used to compare the alternatives:
                                                 :                                         /
             Cost-effectiveness                 '  .                             ;
             Time to design/construct/operate
             Preference for treatment (vs. containment)
             Proven reliability


16.    How are measures compared?                      ,                    .

       Alternatives were compared to reliability and preference for treatment. The combination of a
       new extraction well and soil washing system quickly removes contaminants, thus helping to
       prevent further migration of contaminants.  Cost-effectiveness and the time required to
       implement an alternative were also important criteria used when comparing remedies with
       similar results.
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       Throughout the FS and ROD, the soil and alluvial aquifer were considered as a single medium
       due to their hydrogeologic relationship.  Since contaminated groundwater was considered to be
       the greatest threat to human health and the environment, an in situ aqueous soil washing
       system to remediate contaminated soils will be installed to eliminate further ground water
       contamination.                                ,
                                             -5-
997

-------
                             Lehigh Portland Cement Co.

                             '  Mason, Gordo County, Iowa
                                         Region 7
GENERAL SITE INFORMATION
1.
2.
       What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Cement Kiln Dust (CKD)

       The kiln dust at the Lehigh site is a RCRA
       special study waste, not a RCRA hazardous
       waste. Contaminants included arsenic,
       chromium, and  lead; concentrations were not
       given.
       What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:
                                                               Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                     1988
                     8/90
                     4/91
                     6/28/91
             Background

PRP-lead         j
PRPs:  Lehigh Porltland Cement
       Company
FS prepared by:  Layne Geosciences,
       Inc., A Layhe-Western Subsidiary
ROD prepared by: (Iowa Department
       of Natural Resources
              The volume of CKD in the LPCC area is not given (see Question 3),
              439,000 cubic yards of CKD in the LCNC area (see Question
                                                                   3).,
3.      What type of site is this?
       Construction.  The Lehigh Portland Cement Co. site is composed of two £ireas: the 150-acre
       Lehigh Portland Cement Company (LPCC) cement production facility,| and the 410-acre Lime
       Creek Nature Center (LCNC). From 1911 to the present, the LPCC has manufactured cement
       products. Land use in the area is rural, agricultural, and industrial.


TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screenmg of technically feasible
       technologies were:                                            !
       Containment:
                           Slurry walls, synthetic membranes, grout curtain,, hydraulic isolation,
                           surficial capping (natural or synthetic infiltration caps)
  998
                                           -i-

-------
       Chemical treatment:
       Disposal:
In-place stabilization
Disposal (on-site, off-site)
5.     Was an innovative technology considered in the FS?  If so, which technology?
       o                          ••               /•  "•"'','•".        '•

       Innovative technologies were not considered.
6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       .formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. For this site, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.  Innovative technologies were not incorporated into
       RAAs.           v     • -                    _
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)

       CKD/LPCC                                                       ,
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Drainage of quarries/water treatment ,
CKD isolation capping/quarry
drainage/acid neutralization/dilution
blending water treatment/(this RAA
includes all activities of RAA-2)
Waste stabilization/(this RAA includes
all activities of RAA-2)
Pond drainage/CKD isolation in on-site
engineered landfill/french drain/ground
water extraction/water treatment/(this
RAA includes all activities of RAA-2)
Estimated Costs
3 Criteria .
N/A
N/A
N/A
N/A
N/A
9 Criteria
$0
$1,039,200-
$1,522,401
$2*076,713 -
$3,473,529
$25,223,291 -
$25,356,106
$19,041,820
                                                                                                          L-	
                                             -2-
                                                                                            999

-------
         CKD/LCNC
Alternative
RAA-1L
RAA-2L
RAA-3L
RAA-4L
Standard Technology
No action
Consolidation and isolation of CKD
deposits '
Waste stabilization
Disposal in an off-site engineered
landfill^
Estimated Costs
3 Criteria
N/A
N/A
" I
N/A
JWA
9 Criteria
$0
$947,000-
$1,609,000
$6,810,000
$4,779,000
                                                                                                       J
 ,8.     If a standard technology was chosen, why?                    "   '                      l

     •   LPCC  -             ••-•••                  '        ,:_  •-..-.   •
          .   .       ..      '-     . • •     ' '     •  •-.    •        '-      •   ;i ,            ,  • .
        RAA-3 is a comprehensive, readily applicable, and cost-effective remedy for implementation in
        the LPCC area. RAA-3 was chosen because the isolation of CKD coupled with the ongoing
        treatment of contaminated ground water and surface water, would result in the alleviation of
        the major ground water concerns.  The hydraulic isolation of the CKD deposits will result in
        an effective long-term site remedy. The process of hydraulic isolation, resulting from the
        drainage of site ponds and capping, will effectively eliminate ground Water contact with the
        CKD; therefore, no pathway for impacted water migration will exist. By  isolating the CKD
        from interaction with meteoric water, ground water, and surface water, the mobility of
        contaminants derived from the CKD will be eliminated. RAA-3 is more effective in the short-
        term, as it takes less time to implement than either RAA-4 or RAA-5.J Although RAA-3
        requires a "difficult level of implementation," the technology is proven and the equipment is
        available; therefore, it could be implemented with  greater assurance of effectiveness than the
        other alternatives. The cost of the selected alternative is substantially lower than for the
        alternatives that address CKD on the site.  Finally, RAA-3 complies with ARARs.

  ,  -    LCNC     •  .;      ••    •          -        -  .      '•'•,••'''
        1               •                               "                 ! '         '
                                                                       I •,               '
        RAA-2L "was chosen  because through CKD isolation and gradual dilution, the area ground
        water quality should eventually reach background or near background levels. Because LCNC is
        a public access area, the capping of the CKD deposits in the area will'remove it from public
        contact, thus safeguarding the public. In addition,  isolating the CKD ifrom direct contact with
        the water systems at the LCNC area will result in an effective and permanent remediation. By
        isolating the CKD from interaction with meteoric water, ground water] and surface water, the
        contaminants, which might migrate to the ground water system,  will be greatly reduced.
        Finally the earth moving and pumping technologies are readily available in the Mason City
        area and are not complex.                                       ,1
 9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.
1000
                                              -3-

-------
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                                        ..

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        "      None                                          -

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                                    '         ;

        •      None                       .   .     ,                                       •

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None


 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the- criteria supported the use of a standard technology?

        CKD/LPCC

        Protection  of human health and the environment, implementability, and cost were weighted
        heavily in selecting RAA-3 for LPCC. RAA-3 was considered protective of human health and
        the environment because this alternative drains the contaminated surface water (and some
        ground water) as well as treats the CKD and prevents it from interacting with water on the
        site, at least in a way that would cause further leaching of high pH water onto the site.  In
        addition, the selected alternative can be implemented with greater assurance of effectiveness,
        and at a substantially lower cost than the other alternatives.

        CKD/LCNC

        Protection of human health and the environment, short-term effectiveness, and cost were
        weighted heavily in selecting RAA-2L for LCNC. The selected remedy is protective of human
        health and  the environment because through its implementation the area ground water quality
        should eventually improve to background or near background levels. The selected alternative
        also has a greater assurance of effectiveness, without risk of adverse off-site impacts associated
        with the removal of kiln dust to another location, and can be accomplished at a substantially
        lower cost.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?,             -

        Cleanup goals were not selected.



                                                                                            low

-------
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                                j

        Innovative technologies eliminated because of cleanup goals include:

        •      None

        Standard technologies eliminated because of cleanup goals include:

        •      None
14.     Were treatability studies conducted on the innovative technology or standard technology?
                                     '                               '    r  .
                                                                        I , '
        Treatability studies were not conducted.
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Cost effectiveness
             Proven reliability
16.     How are measures compared?

        LPCC
       The selected alternative was chosen because it uses proven technology land available
       equipment. The cost of RAA-3 is substantially lower than other alternatives (RAA-4, RAA-5)
       which address CKD on the site. The selected remedy is cost-effective because it is the least
       expensive action alternative and yet provides a high degree of overall protection.

       LCNC '                       .          -       .       •'...'.  '   .,  '  .    •  .-,  '.
                                                                        I
       .The earth moving and pumping technologies used in the selected alternative are readily
       available in the Mason City area and are riot complex. The selected alternative can be
       accomplished at a substantially lower cost than RAA-3L or RAA-4L.
17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedy for this site.
1002
                                              -5-

-------
                                                                                                       1', -1
                            Mid-America Tanning Company

                                   • Sergeant Bluff, Iowa
                                         Region 7
GENERAL SITE INFORMATION             ,
                            \
1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediment (mg/kg)

       Chromium            43,000
2.      What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       "      12,000 cubic yards of soil
       •      44,500 cubic yards of sediment
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                                                                        6/88
                                                                        3/89
                                                                        6/91
                                                                        9/24/91
                                                                Background

                                                   EPA Fund-lead
                                                   PRPs:  U.S. Tanning Company
                                                   FS prepared by: U.S. Environmental
                                                          Protection Agency
3.     What type of site is this?

       Food and Kindred Products.  A former leather tannery.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                            •           ~
       Access restriction:
       Containment:

       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
                           Fencing, deed restrictions
                           Clay cap, soil cap, RCRA multilayer cap, soil-synthetic membrane,
                           slurry wall, sheet piling, grout injection, low permeable liner
                           Stabilization, fixation                        .
                           Dewatering
                           Incineration .
                           'Excavation, on-site disposal, off-site disposal
                                           -1-
                                                                                        1003

-------
                            Mid-America Tanning Company
                                       s  '

                                    Sergeant Bluff, Iowa
                                          Region?
GENERAL SITE INFORMATION

1.  '   What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?    :_

       Maximum concentrations of principal
       contaminants were:

       Soil/Sediment (rag/kg)

       Chromium            43,000
       What volume of material is to be
       remediated?

       The volume of material to be, remediated
       included:

       •      12,000 cubic yards of soil
       •      44,500 cubic yards of sediment
                                                          Site History
                                             NPL Proposed:
                                             NPL Final:
                                             FS:
                                             ROD:
6/88
3/89
6/91
9/24/91
                                                         Background
                                                             :|
                                             EPA Fund-lead
                                             PRPs:  U.S. Tanning Company
                                             FS prepared by:  UiS. Environmental
                                                    Protection Agency
3.     What type of site is this?                ,

       Food and Kindred Products.  A former leather tannery.
              \     \         -             "...."


TECHNOLOGY SELECTION                                         i.
              " "~ '"                        ,      •             ,        • i  -       :

4.     What standard technologies were considered for selection in this FS?
                                                      (              !           '
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                  .
       Access restriction:
       Containment:
                     Fencing, deed restrictions
                     Clay cap, soil cap, RCRA multilayer cap, soil-jsyrithetic membrane,
                     slurry wall, sheet piling, grout injection, low permeable liner
Chemical treatment:    Stabilization, fixation
                     Dewatering
                     Incineration
                     Excavation, on-site disposal, off-site disposal
       Physical treatment:
       Thermal treatment:
       Disposal:
                                            -1-
                                                                                        1003

-------
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Inn     .-e technologies considered during the identification and screening of technically
        feas     echnologies were:

        Biological treatment:   Landfarming, biodegradation, composting
        Chemical treatment:   Solvent extraction, soil flushing (solvent), soil washing (solvent),
                             chemical reactions, oxidation
        Thermal treatment:     In situ vitrification, thermal volatilization, thermal desorption
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are usually estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on the
        nine criteria established by the NCP.                          •

        No innovative technologies were incorporated into remedial alternatives.
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Excavation/off-site disposal/soil
cap/long-term ground water- monitoring
Excavation/on-site disposal/installation
of liner and leachate system/soil cap/
long-term ground water monitoring
Excavation/immobilization/on-site
disposal/soil cap/long-term ground
water monitoring
In situ immobilization/soil cap/
long-term ground water monitoring
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
*
N/A
9 Criteria
$0
$6,675,000
$7,018,000
$8,900,QOO
$4,875,000
8.     If a standard technology was chosen, why?                            •        ,

       The selected remedy requires immobilization (using cement and additives) of contaminated
       soils, sediment and trench sludge on-site followed by either on-site or off-site disposal;
 1004
                                              -2-

-------
        removing and disposing of debris off-site, and; discharging impoundniient water through an
        NPDES permitted outfall or treatment, if needed, with off-site discharge to a publicly owned
        treatment works; capping contaminated areas; and implementing institutional controls.  The
        remedy was selected because 1) it involves treatment of contaminants! in addition to
        engineering controls, 2) mobility of the contaminants,will be reduced through bonding to the
        solidified matrix and through reduction in the surface area exposed to ground or surface water,
        3) direct contact will be prevented through the use of soil/clay caps in th« less contaminated
        areas, 4) dewatering involved in other alternatives would create odors[ 5) depends on
        conventional immobilization technologies that are proven and reliable; 6) cost was the least
        expensive.                                                      ,;                .

                         ,       "                  ' .         •           •'[•'/".
P.      If an innovative technology was chosen, why?                      I
               -.         ,                      '                         "•!""';           •
        An innovative technology was not chosen.                         !                  /


10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                       '            "               '                     i
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening;  during the  screening of the liiree criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:
                                   •                 "       ,    '  •.      I'      • • '   '       ''    '
       •      Landfarming was eliminated because it would not be effective for remediating
              inorganic compounds.
    ,   •      Solvent extraction was eliminated because it would  not be effective for remediating
              inorganic compounds.
      ••••...   Soil washing was eliminated because it is only effective for soiils that are
              predominantly sand and gravel.
       •      Thermal volatilization was eliminated because it would not be effective for remediating
           :•   inorganic compounds.
       •      Thermal desorption was eliminated because it would not be effective for remediating
              inorganic compounds.                                   .                  ,
       •      Biodegradation was eliminated because it would not be effective for remediating
              inorganic compounds.
       •      Chemical reaction (oxidation) was eliminated because it would not be effective for
              remediating inorganic compounds.                           r
       •      Composting was eliminated because it would not be effective for remediating inorganic
              compounds.                                      .                      •
               ' '   '  . •                 '       .          -            ' i     .   -
      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                                        i              ,
                            •              "         .                ~ ' :i           .  '   '   •  '
      •     In situ vitrification was eliminated because implementation would be too  expensive
      •     Soil flushing was eliminated because the solvents could transport contaminants into the
             underlying aquifer.
                                            -3-
1005

-------
       Innovative technologies eliminated during the detailed analysis include the following:

       •     None                             .
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion? Which of the criteria supported the use of a standard technology?

       The most heavily weighted criteria in selecting a standard technology were protectiveness of
       human health and the environment, long-term effectiveness through treatment, and cost.  Of
       the two alternatives, RAA-4 and RAA-5, that were comparable with respect to providing
       permanent and long-term protection through treatment, RAA-5 was selected based on cost.

       No innovative technologies were incorporated into remedial alternatives.


12.    What cleanup  goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to, establish cleanup goals?
                    Contaminant
Cleanup Level (mg/kg)   ARAR or Other Basis
                Carcinogens
                Chromium
        2,000
Risk8
       *Since no federal or state cleanup levels for chromium exist, the cleanup goal is the estimated
       concentration that is associated with an excess upper bound individual lifetime cancer risk
       level of 10-4.    .
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •      None                                        ,        ,

        Standard technologies eliminated because of cleanup goals include:

        »      None                          ,        •                               '


14.     Were treatdbility studies conducted on the innovative technology or standard technology?

        No treatability studies were conducted.                                       ,
  1006
                                              -4-

-------
 15.     What measures/criteria were used to compare alternatives?         !
                                    "                            '   .   j  - - '             ""
        The following measures were used to(compare the alternatives:

               Cost-effectiveness                                       ;
               Preference for treatment (vs. containment)                  I


16.    How are measures compared?  l                      ••         • j

       The selected alternative was the most cost-effective. One other alternative (RAA-4) was as
       protective of public health and the environment as the  selected alternative, but it would be
       more expensive to implement. The degree of permanence offered by the  selected alternative
       through a treatment technology was considered superior to the protection provided by other
       alternatives (RAA-2, RAA-3) that did not employ treatment.


17.    What technical considerations were factors in selecting a remedy? Were  technical
       considerations printary in the selection of the remedy?              i

       No technical considerations were primary in selecting a remedial alternative.
                                            -5-
1007

-------
                               Peoples Natural Gas Co.
                                          OU-1

                                      Dubuque, Iowa
                                         Region 7
GENERAL SITE INFORMATION
L
2.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?      ,  .

Maximum concentrations of principal
contaminants were:

Soil (rag/kg)

Benzene                     55
Total PAHs         .         8,000
Total Carcinogenic PAHs   .   1,800
Ethylbenzene                 110
Toluene                     29  ,
Cyanide                     1,100 .
                                                               Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
6/88
8/30/90
5/15/91
9/16/91
                                                               Background

                                                   PRP-lead
                                                   PRPs: Midwest Gas, Iowa Department
                                                          of Transportation, City of
                                                          Dubuque
                                                   FS prepared by: Barr Engineering
What volume of material is to be
remediated?

The volume of material to be remediated included:

•      24,200 cubic yards of contaminated soil
3.     "What type of site is this?

       Coal Products. The site is a former coal gasification plant.  The City of Dubuque currently
       maintains a public works garage on the site.  The Iowa Department of Transportation-plans to
       build a highway across the western portion of the site. The site is located 300 feet from the ,
       Mississippi  River.                                                                  •
TECHNOLOGY SELECTION                            .

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                             •

       Access restriction:     Deed restrictions, fencing
   1008
                                            -i-

-------
       Containment:
       Chemical treatment:
       Physical treatment:
       Thermal treatment:
       Disposal:
Capping (soil, clay, flexible membrane, RCRA type), vertical barrier'
(bent-soil slurry wall, bent-cement .slurry wall, grout curtain, sheet
piles, vibrating beam)                      |
Stabilization    ,                    "    •  ''   ';•:,'
Soil washing                       -      i     .
Incineration                              I '                '
On-site disposal, sanitary landfill, RCRA vault
5.     Was an innovative technology considered in the FS?  If so, which technology?       •  '.
                   •  '     '  •                     •     '            '    ~:\ "  '    '  '       . ' '
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                      i                    ,

       Biological treatment:   Land treatment, biological reactor, in situ biodegradation
       Phys/Chem treatment:  Soil flushing, in situ vapor extraction, in situ chemical treatment, in
                             situ electroacoustic soil decontamination, soil! washing
       Thermal treatment:    In situ vitrification, low temperature thermal stripping
6.      What was the cost estimate for the^innovative technology?          !
                                •            •            -             - -i' -          ''          '
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to  identify alternatives that merit a more detailed evaluation. The
        estimated costs then are recalculated during an evaluation based on tlhe nine criteria established
        by theNCP.                                                                         .    ;

                Cost Estimates for  RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
Limited soil removal and incineration,
disposal, or biological treatment/ground
water extraction and treatment/monitoring
Limited soil removal and incineration,
disposal, or biological treatment/ground
water extraction and treatment/capping
and slurry wall containment of source
soils/in situ bioremediation of silty
sands/monitoring .
/Limited soil removal and incineration,
disposal, or biological treatment/ground
water extraction and treatment/source soil'
removal and incineration/monitoring
Estimated Costs
3 Criteria
$6,300,000.
$7,3(K),000
$10,000,000
9 Criteria
$6,200,000
to
$6,300,000
$7,200,000
to
$7,300,000
$10,000,000
to
$10,600,000
• • fl - , •
. '• . :• *••' :•.-•• •-;•• ' l
                                                                                            1009

-------
Alternative
RAA-4&5
Innovative Technology
Soil removal and incineration/ground
water extraction and treatment/in situ
bioremediation of silty sands/
institutional controls/monitoring
Estimated Costs
3 Criteria
not evaluated
1
9 Criteria
$8,000,000
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
Standard Technology
No action
Soil removal and incineration/
monitoring/institutional controls
Estimated Costs
3 Criteria
$0 :
$3,900,000^
9 Criteria
$0
$3,900,000
8.      If a standard technology was chosen, why?

       RAA-6 incorporates both a standard technology (off-site incineration) and an innovative
       technology (in situ bioremediation).  The alternative provides the greatest degree of human
       health and environmental protection by excavating and incinerating soils exceeding cleanup
       gpalSj excavating and incinerating contaminated soils in contact with ground water sources and
       bioremediating contaminated soils in the silty sands area. In situ bioremediation in the silty
       sands area is expected to reduce ground water contaminant levels much faster than with just
       ground water extraction and treatment and will permanently eliminates residual risk. The
       alternative maximizes long-term effectiveness and reduces the toxicity, mobility, and volume
       of wastes to the greatest extent practicable. The alternative also poses minimal short-term
       risks. RAA-1 is not protective of human health and the environment. RAA-2 reduces the
       toxicity, mobility, and volume of contaminated soils, but does not treat ground water and
       therefore neither provides adequate" protection of human health and the environment nor attains
       chemical specific ARARs for ground water..  RAA-3 is protective of human health and the
       environment but does not involve the excavation and treatment of source soils and therefore
       would not permanently eliminate residual risk at the site. RAA-4 is similar to RAA-3, but
    ,   uses  a combination of in situ bioremediation and capping to reduce risks associated with silty
       sands not addressed by RAA-3.  RAA-4, however, leaves a large Volume of source soils
       untreated that could potentially leach chemicals of concern  into ground water.  RAA-5
       addresses the source soil area through excavation and incineration,  but relies on ground water
       extraction and treatment to remove contaminants from the silty sand area. Without in situ
       bioremediation of the silty sands area, RAA-5 is expected to require a much longer period to
       reduce contaminant levels in ground water to acceptable levels.
 1010
                                             -3-

-------
 9.     If an innovative technology was chosen, why?                      |
     "  • "      •               ' " .   "      "     •      •     ''                  •' '                 ,   - '
        As discussed above, RAA-6 employs both standard and innovative technologies.
        Bioremediation of the silty sands area was incorporated into RAA-6 because it is expected to
        accelerate ground water restoration.  Ground water extraction and treatment by itself (as in
        RAA-3 and RAA-5) will not restore ground water quality as quickly in the absence of
        enhanced bioremediation.                                         i
                                                    '                 '                '
.10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation. V
                                                                    j     'I- •     -.     .     '     '
         ...                    -                                           i
         Innovative technologies eliminated during the initial screening include th« fqllowing:

         •      In situ vitrification was eliminated because it would not be effective in treating soils
                with relatively high permeability and moisture content.  In addition, the depth of
                contamination and the presence of ground water at the site make this technology
                infeasible.  A lack of sufficient demonstration was also cited.
         •      In situ vapor extraction was eliminated because it is only applicable to, organic
                compounds that are highly volatile at ambient temperatures. Many^of the, PAHs in
                coal tar have low volatility. Vapor extraction also is not effective in treating
                contaminated soils below the water table with relatively low permeability at the site.
         »      In situ chemical treatments (other than soil flushing and stabilization, including solvent
                extraction and oxidation-reduction) were eliminated because Ihey are not considered
                demonstrated treatment technologies  for treating soils containing coal-tar derived
                contamination.
         •      In situ electroacoustic soil decontamination Was eliminated because it is in the
                evaluation  stage and has not been applied in situ. Its potential is greatest for treating
                fine grained clay soils containing inorganic contaminants.        ',•'..
         "      Low temperature thermal stripping was eliminated because it is not effective in
                treating PAHs with relatively low volatility.
         •      Soil washing was eliminated because of the presence of fine Drained soils, which make
                post-treatment of the wash solution difficult and strong adsorptive bonds between clays
                and SVOCs. Success in treating soils containing PAHs is not well documented.

         innovative technologies, eliminated during the screening of the three criteria include the
         following:                                                   .  -  I-                       .
                                                  ' ' ••            '  -  .-   !        "        '•     i '
         •      Soil flushing was not included in the RAAs, though no explicit reason  was stated.  The
                FS states that not all technologies that survived the screening process are included  in
                RAAs. The RAAs were assembled to highlight technologies; for individual operable
                units that enhance the effectiveness of other remedial technologies.               .
             - '  '   .   "          '         •                 _              I                  •-'
         Innovative technologies eliminated during the detailed analysis include the following:
                                ••".'.       '   •       '       •            •}• ••    •     •   ,-    '.:
         •      Land treatment was eliminated because they have not been demonstrated to effectively
                reduce concentrations of all PAHs to environmentally acceptable levels for the
                                                                                                  10.11

-------
               quantities of excavated soils which would be generated at the site. Residual
               contamination may be present after treatment.  .
               Biological reactor was eliminated because they have not been demonstrated to
               effectively reduce concentrations of aU^PAHs to environmentally acceptable levels for
               the quantities of excavated soils which would be generated at the  site.  Residual
               contamination may be present after treatment.
ll.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,  •
which criterion? Which of the criteria supported the use of a standard technology?

Protectiveness of human health and the environment, long-term effectiveness and permanence,
and reduction of toxicity, mobility, and volume of contaminants were weighted most heavily in
selecting the preferred alternative. RAA-4 & 5 addresses all sources of ground water
contamination and therefore offers the greatest reduction in toxicity, mobility, and volume of
site contaminants, maximizes long-term effectiveness, and protects human health and the
environment to the greatest extent practicable.
12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup. Level (mg/kg)
ARAR or Other Basis
Carcinogens
Benzene
Total Carcinogenic
PAHS
850
100
Risk8
Risk"
•« • '
Noncarcinogens
Total PAHs
Ethylbenzene
Toluene
Cyanide
500
68,000
200,000
3,400
Risk0
Riskc
Risk6
Risk0
              "Cleanup level, is based on achieving an excess upper bound individual lifetime cancer
              risk of 10"6.
              ""Cleanup level is based on achieving an excess upper bound individual lifetime cancer
              risk of 5.8 x ID"4.
              cCleanup level is based on achieving a Hazard Index less than or equal to 1.0.

                                                                                                   t™	
 1012
                                             -5-

-------
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                              i

       Innovative technologies eliminated because of cleanup goals include:          ,        ,

       •      Land treatment          '                               I
       •      Biological reactor
                                                                      I      •    • . .     -  , •. ,
       Standard technologies eliminated because of cleanup goals include:

       •      None
                                                                     r standa
14.    Were treatability studies conducted on the innovative technology or standard technology?

       While no treatability studies were conducted, a pilot study of in situ bioremediation of the silty
       sands area will be conducted prior to full-scale implementation. The study will determine the
       types and amounts of nutrients and engineered organisms needed to stimulate natural
       biological degradation at the site.  s                    ,         |
75.     What measures/criteria were used to compare alternatives?                            .
                                       '             '    •              I -      '
  •      The following measures were used to compare the alternatives:   >'\
                                     . -    - -       •         '           1        ",      ,"   -   '   •
               Risk reduction                                          i
        -       Time to design/construct/operate       ,                          :


16.     How are measures compared?                                   '     ,

        RAA-4 & 5 was selected primarily on the amount of risk reduction achieved and the amount
        of time needed to  restore ground water quality to  acceptable levels, i Because RAA-4 & 5
        addresses both source soils and the silty sands area, it is expected to achieve the greatest
    '.   reductionin site risks by permanently destroying virtually all site contaminants.
17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?            !.

       " Technical considerations were not a primary factor in selecting a final remedy.  The nature of
        site soil conditions (high permeability and moisture content), however, .were a factor in
        eliminating a number of innovative technologies during the initial screening phase. These
        technologies were:                                             j
                                                                     . .1        "  •
       ' '           ''  !         •         .       ' -                  '•('•'.     •  •         '
        •      Vitrification
        •      Vapor extraction                                   :  •'  *• \     j,
        •      In situ electroacoustic soil decontamination.               |                •
        •      Low temperature thermal volatilization.
                                                                                            1013

-------
                            Pester Refinery Co. (Burn Pond)
                                          01

                                     El Dorado, Kansas
                                         Region 7
 GENERAL SITE INFORMATION

 1.      "What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil/Sludge (mg/kg)

        Benzo(a)anthracene    78
        Chiysene             150
        2-Methylnaphthalene  '75
        Naphthalene          7 .
        Phenanthrene         220
        Pyrene               160
        Xylenes              4
        Chromium           121
        Lead    -           157
                                    Site History
                        NPL Proposed:
                        NPL Final:
                        FS:
                        ROD:
'N/A
 1/31/89
 6/17/92
 9/30/92
                                    Background

                        EPA Fund-lead
                        PRPs:  Fina Oil and Chemical
                              Company
                        FS prepared by: Metcalf & Eddy,
                              Incorporated
       What volume of material is to be remediated?

       The volume of material to be remediated included:

       »      20,000 cubic yards of sludge
       »      70,000 cubic yards of soil
3.     What type of site is this?

       Petroleum Refining. A pond adjacent to a refinery where petroleum waste products were
       deposited.                                           '•     .  .      .s   •    .
                                                                          I-,.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                " ,                '
       Access restriction:
Deed restrictions
  1014
                                           -i-

-------
        Containment:

        Chemical treatment:
        Thermal treatment:
        Disposal:
                                          !
Clay cap, asphalt cap, vegetation, slurry walls, interceptor trenches,
cutoff walls                       .   ,
Solidification/stabilization, refining, detergents
Incineration, waste fuel recovery in cement kiln
Excavation, on-site disposal, off-site disposal
5.      Was an innovative technology considered in the FS? If so, which technology?
                                                                       .1  .'-,/•'.
        Innovative .technologies considered during the identification and screening of technically
        feasible technologies were:
               •  -             •              "  .          "      '         i'"         -     •  .
        Biological treatment:   Bioremediation
        Phys/Chem treatment:  In situ soil flushing, oxidation
        Thermal treatment:     Thermal desorption
                                                                       r
6.      What was the cost estimate for the innovative technology?          1

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  j\fter the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives thai: merit a more detailed
       evaluation. In this case, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP:  long-term effectiveness and pemianence; short-term
       effectiveness; compliance with ARARs; protectiveness of human health and the environment;
       reduction in contaminant mobility, toxicity, or volume; implementabil ity; cost; state/support
       agency acceptance; and community acceptance.                     j
                                                         ''••'   \     ':'''•  ~   '"'.
                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-2A2
RAA-2B2
RAA-5B
Innovative Technology
Excavate sludge/dewater/off-site
solidification of sludge/in situ soil
flushing/bioremediation of soils
Excavate sludge/dewater/off-site re-
refining of sludge at RCRA refinery/
in situ soil flushing/in situ bioreme-
diation of soils and recirculated water
Excavate sludge/off-site use of sludge
as a hazardous waste fuel for
incineration/in situ soil flushing and
bioremediation of soils
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$2,160,000
$2,374,800
$5,402;iOO
                                              -2-'
                                                                                              1015

-------
 7.      How did the cost(s) compare to standard technologies?
                  Cost Estimates for RAAs That In.  ide Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-1A
RAA-2A1
RAA-2B1
RAA-3
RAA-4
RAA-5A
Standard Technology
No action
Deed restrictions/pump interceptor
trench
Excavate sludge/dewater/off-site
solidification of sludge/cap soils
Excavate sludge/dewater/off-site re-
refining of sludge at RCRA refinery/cap
site soils
Dewater sludge/RCRA cap over sludge
and soils/leachate collection and
treatment
On-site solidification of sludge/cap
soils/leachate collection and treatment
Excavate sludge/off-site use a hazardous
waste fuel for incineration/clay cap over
remaining soil
Estimated Costs
3 Criteria
N/A ' ,
N/A
N/A ,
i
N/A
N/A
N/A "
N/A
9 Criteria
$0
$238,300
$2,572,900
$2,787,720
$2,646,200
$3,353,600
$5,815,000
8.     If a standard technology was chosen, why?

       A standard technology was not chosen.
9.      If an innovative technology was chosen, why?  •      '

       The selected remedy includes removing and dewatering sludge from a RCRA regulated sludge
       pond; sludge processing at an off site refinery; in situ soil flushing of contaminated soils
       through the use of interceptor trenches  with accompanying bioremediation; and bioremediation
       of pond waters. The remedy was selected because 1) it would mitigate migration of
       contaminants into the river with an interceptor trench, 2) treatment in an asphalt plant would
       require delisting of the material while reuse through recycling provisions provides exclusions
       for certain recyclable materials from most of the RCRA regulations, 3) anticipated to attain
       clean-up goals, 4) will permanently remove contaminants in the soil, and 5) is cost effective.
1016
                                             -3-

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                          .|.:    .

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of  .
       effectiveness, implementability, and cost; or during the detailed evaluation.  Three criteria
       screening was not completed in this FS.
        ~J                             .                   r          •• 4
       Innovative technologies eliminated during the initial screening include the following:

       •    ,   Thermal Desorption was eliminated because they have no significant effect pn most
               metals and it is not cost effective.                        1 .   '•                v-

       Innovative technologies eliminated during the screening of the three criteria include the
       following: ,                         .._-'-         i

       •       None                                                    !

       Innovative technologies eliminated during the detailed analysis include the following:

       •       None
11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the use of a standard technology?

        The permanent reduction of site contaminants and cost were the criteria weighted most heavily
        on selecting an innovative technology,
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant ,
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens |
PAHs
13
! Risk2
               "Cleanup levels were based on the concentration of total PAHs which would result in
               an excess upper bound individual lifetime cancer risk of 10"6,;
13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?                                       .   ..  .
        .       "              '      .   '      -       '          '         !  .'             .
        Innovative technologies eliminated because of cleanup goals include:
                                      ..    '         -         '           I
        •      None --•'••            '  .  ' -.            '••.':•'•!
                                              -4-
                                                                                             1017

-------
        Standard technologies eliminated because of cleanup goals include:

        •      None                                          '
 14.    Were treatability studies conducted on the innovative technology or standard technology?

        A treatability study was conducted to determine the feasibility of solidification/stabilization as
        a treatment technology for the remediation of sludge. The study determined that the process
        produces a stabilized material that achieves the leachability objectives.
 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Cost-effectiveness
             Preference for treatment (vs. containment)
             Waste left in place/institutional control
16.     How are measures compared?

        The chosen alternative reduces site risk to 10* through the implementation of an innovative
        treatment technology.  The preference for treatment was a factor and, several alternatives
        (RAA-2A1, RAA-2A2, RAA-2B1, and RAA-3) were eliminated because they did not propose
        source treatment.  In addition, since off-site treatment of site contaminants was preferred,
        solidification/stabilization techniques were eliminated because contaminants would have '
        remained on site.  Of the two alternatives that included soil treatment technologies, the chosen
        alternative was the most  cost-effective option.                            '
17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

No technical considerations were primary in the selection of a remedial alternative.
1018
                                             -5-

-------
                                   Shaw Avenue Dump
                                           OU-1

                                     Charles City, Iowa
                                          Region 7
 GENERAL SITE INFORMATION
2.,
        What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Chemical fill/soil (mg/kg)

        Arsenic              264,000
        Ortho-nitfoaniline  .   95,000
       .PAHs                200
What volume of material is to be.
remediated?             '

The volume of material to be remediated
included:

•      370 cubic yards of chemical fill and soil
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                     N/A
                     7/87
                     9/21/91
                     9/26/91
             Background  •

PRP-lead          j
PRPs:  Charles City, Solvay Animal
       Health, Inc. j
FS prepared by: Conesltoga-Rovers &
       Associates
3.     What type of site is this?

       Municipal Landfill. An'active waste site located in a residential area.
TECHNOLOGY SELECTION
4.     What standard technologies were considered for selection in this FS?
                                           •               .           \     .     •        '•   •
       Standard technologies considered during die identification and screening of technically feasible
.       technologies were:
       Access restriction:
       Containment:
       Physical treatment:
       Thermal treatment:
       Disposal:
                     Deed restrictions, access control
                     Capping (RCRA, non-RCRA)            ,       :
                     Stabilization/fixation
                     Incineration
                     Excavation, disposal at RCRA landfill (on-site, off-site)
                                            -1-
                                                                                  1019

-------
 5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Bioremediation
        Chemical treatment:   Solvent extraction
        Physical treatment: °  Soil washing, soil vapor extraction
        Thermal treatment:    Low-temperature thermal extraction, in situ vitrification
6*.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based.on
        nine criteria established by the NCP:  long-term effectiveness and permanence; short-term
        effectiveness; compliance with ARARs; protectiveness of human health and the environment;
        reduction in contaminant mobility, toxicity, or volume; implementability; cost; state/support
        agency  acceptance; and community acceptance.

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-6
Innovative Technology
Deed restrictions/ground water
monitoring/in .situ vitrification
Estimated Costs <
3 Criteria
N/A
9 Criteria
eliminated
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Deed restrictions/ground water
monitoring
Cap/deed restrictions/ground water
monitoring
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$34,800
eliminated
$145,250
 1020
                                             -2-

-------
• . ..- -. • • • ; ^ :; •• : . • '--; • iv;.- • ;. . ".
Alternative
RAA-4
RAA-5
Standard Technology
Excavation/off-site disposal at RCRA
facility
Cap/deed restrictions/ground water
monitoring/solidification/fixation
Estimated Costs
3 Criteria
N/A
M/A ' ,
9 Criteria
$845,000
$513,400
8.      If a standard technology was chosen, why?               -        >f
                               '                  '             •  '       '[
       The chosen alternative was selected because it protects human health and the environment
       through the containment and treatment of contaminated soil. Stabilization/fixation binds and/or
       entraps the contaminants, thereby immobilizing them and preventing future releases.
       Stabilization/fixation also eliminates  any threat posed by direct contact with the chemical fill
       or contaminated soil as well as threats  posed to future users of the site.  A cap placed on the
       solidified material prevents direct contact and protects the solidified mass. Implementation
       involves conventional techniques that are readily available, proven, arid reliable.  This
       alternative imposes no short-term impacts.  Stabilization/fixation techniques reduce site   '
       contaminants to cleanup levels and prevent the leaching of contaminants to ground water.
       The chosen alternative is cost-effective.
9.      If an innovative technology was chosen, why?

       An innovative technology was not selected.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                            .               !

       Innovative technologies could be eliminated from the remedial techno log],' selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      Soil washing was eliminated because its effectiveness is questionable for some
               contaminants and implementation costs could escalate dramatically if several wash
            i   stages are necessary.
       •      Soil vapor extraction was eliminated because it would not address inorganic
               contaminants.                                             i
       •      Solvent extraction was eliminated because it would be ineffective in addressing
               inorganic contaminants.                                    j
       •      Low-temperature thermal extraction was eliminated because it would be ineffective for,
               inorganics and impractical since there is only a small volume of soil.
       •      Bioremediation (ex situ) was eliminated because it would not be effective for
               inorganics, degradation of a mixture of contaminants is uncertain, and degradation
               products could be toxic.
                                              -3-
1021

-------
12.
        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      In situ vitrification was eliminated because it is still in experimental stages and its
                effectiveness is unclear.  Moreover, the cost of this technology at such a small site
                would be prohibitive.  This technique was described as most useful at sites were
                remediation techniques would pose a short-tern risk to site workers or the community
                and this is not the case at Shaw Avenue.

        Innovative technologies eliminated during the detailed analysis include the following:

        »      None
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

 The criteria that were weighted most heavily in selecting a remedial alternative were protection
 to human health and the environment and cost.  The chosen alternative provides a great deal of
 protection through the utilization of both  capping and stabilization techniques. In addition, it
 costs much less than off-site disposal or vitrification.

 In situ vitrification was eliminated, in part due to excessive cost.


 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens .
Arsenic
Cadmium
50
20
Risk8
Risk
               "For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"*
               to 10"6 was acceptable,  For noncarcinogens, a Hazard Index less than or equal to 1.0
               was acceptable.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •       None

       Standard technologies eliminated because of cleanup goals include:                    .

       •       None

 1022                                          '
                                              -4-

-------
14.     Were treatability studies conducted on the innovative technology,or standard technology?

       Treatability studies were not conducted.                             |


15.    • What measures/criteria were used to compare alternatives?           |
                           ''•     .          .                   •  .   '    .  t''       •','•'
                                                                       ,  *!     • .
       The following measures were used to compare the alternatives:       i
                                '             . -     '      ,                i '       '"  ,
             Cost-effectiveness                                           '
             Proven reliability ,                                .           ;
                                      •• -  .    •               • -     -     '-.!'"'"        '      ',
    •-..-'        .'            '   •   •   '       '              • •       .!-•'.
16.    How are measures compared?-                                     i                   '

       The chosen alternative was preferred because it offers the greatest benefits! for the cost.  An
       alternative proposing off-site disposal was not chosen because it would have cost more and the
       benefits would not have increased significantly.  The chosen alternative also utilizes proven
       and reliable technologies. One innovative technology, in situ vitrification, was eliminated
       because its effectiveness is uncertain and its cost would be excessive. |

17.     What technical considerations were factors in selecting a  remedy?  Were technical
       considerations primary in the selection of the remedy?

       .Technical considerations were not primary in selecting a remedial alternative.
                                                -5-
                                                                                              1023

-------
                               Anaconda Co. Smelter
                                       OU-11

                         Anaconda, Deer Lodge County, Montana
                                      Region 8
 GENERAL SITE INFORMATION
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

,

Maximum concentrations of principal
contaminants were:

Flue Dust (rag/kg)
Aluminum
Antimony
Arsenic
Beryllium
Bismuth
Cadmium
Calcium
Chromium
Cobalt ,
Copper
Iron
Lead
Manganese
Mercury
Molybdenum
Nickel
Silver
Silicon dioxide
Selenium
Zinc



6,300
2,120
80,00
0.35
3,22 ,
3,59
78,000
30

Site History

NPL Proposed: N/A
NPL Final: 9/8/83
FS Phase I: 5/25/89
RI/FS: 6/4/91 '
ROD: 9/91
Background

PRP-lead ,
PRPs: Atlantic Richfield Co. (ARCO;
Cleveland Wrecking Co.)
FS prepared by: Dames and Moore
•

71.6
244,000
175,000 ',.•'•
32,300
500
218 •..-,."
1,150 . ' - •
110 .
290 :
265,000
49 . \ . . .- - ' ' ••'•• - "
49,000
2.      What volume of material is to be remediated?


       The volume of material to be remediated included:


       *      316,536 cubic yards of flue dust

3.      What type of site is this?
      Primary Metal Products.  An abandoned smelter located in and adjacent to the community of
      Anaconda.
 1024
                                        -i-

-------
TECHNOLOGY SELECTION                                         i

4.'     What standard technologies were considered for selection in this FS?

        Standard technologies considered during the original [FS I] identification and screening of
        technically feasible technologies were:
                    ''"..'    ''           •            •       L  .'  '        '    '  ' '-
        Access restriction:     Restrictive covenants, land use zoning restrictions, drinking water bans
        Containment:          Single-layered soil cap, multilayered soil/synthetic membrane cap,
                             establishing grassy vegetation, compacted soil liners, synthetic
                             membrane liners
        Chemical/physical     Thermoplastic stabilization, surface encapsulation, cement7based
        treatment:             stabilization/fixation (HAZCON, MSE, Inc.){ cement-and fly-ash-
                             based stabilization/fixation (Dames and Moore), silicate-based
                             stabilization/fixation (CHEMFDC Environmental Services), gravity
                             separation
        Thermal treatment:     Rotary kiln, flame reactor, electric arc furnace
        Disposal:              Excavation, permanent on-site disposal, off-siite disposal, interim on-
                             site storage                         •     j
                   ", -  -  •          '           "          "1       •  j"    •         •

5.       Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                      ;
                                                                     I
          " • -.                     •      }  -             '   '      "'      V             ' "
        Biological treatment:   In situ biological treatment
        Chemical treatment:    In situ chemical treatment, hydrometallurgical processes (Dowa,
                             Cashman, Kenneeott, Shenyang, ammonium leach, Bureau of Mines
                             alkaline leach, Metallhute Carl Fabusch, Anaconda Research,
                             Anaconda Modified Dowa, chloride leach, sulfur dioxide leach, Con
                             Mine, sulfide  precipitation, and ambient acid leach)        ,     '
      -Thermal treatment:     Vitrification, pyrometallurgical processes (PLASMADUST, arsenic
                             volatization)

        Processing at commercial hydrometallurgical/pyrometallurgical facilities also was considered
        under two representative processes, A and B, at the following facilities (the processes are not
        described):         -                                 ,,         i
       Option A:
              Koaka Smelter, Dowa, Japan
              Nercb Con Mine Arsenic Plant, YeHowknife, Northwest Terptory, Canada
              Falconbridge, Ltd., Kidd Creek, Timmins, Ontario^ Canada
       Option B:
              Falconbridge, Ltd., Kidd Creek, Timmins, Ontario, Canada
              Metallurgy Hoboken-Overpelt, Olen, Belgium
              Norddeutsche Affinerie, Hamburg, Germany
              Outokompu Oy, Harjavalta, Finland
                                              2                                             1025

-------
  6.      Wluit was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. For this site, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.

          RAA designations that were changed in the ROD are presented parenthetically.

                  Cost Estimates for RAAs That Include Innovative Technologies     .
                              (selected remedial alternative is in bold)
Alternative
RAA-6A-1
RAA-6A-2
RAA-6B-1-A
(RAA-5A)
RAA-6B-1-B
(RAA-5B)
RAA-6B-2
RAA-6C-1
(RAA-6)"
RAA-6C-2
Innovative Technology
Excavation/on-site hydrometallurgical
treatment using Dowa process/possible
stabilization/fixation/on-site disposal
Excavation/on-site hydrometallurgical
treatment using Dowa process/possible
stabilization/fixation/off-site disposal
Excavation/on-site hydrometallurgical
treatment using Cashman process/
stabilization/fixation/on-site disposal
Excavation/on-site, hydrometallurgical
treatment using Cashman process/on-site
disposal
Excavation/on-site hydrometallurgical
treatment using Cashman process/
possible stabilization/fixation/off-site
disposal
Excavation/on-site hydrometallurgical
treatment using ambient acid leach
process/possible stabilization/fixation/
on-site disposal
Excavation/on-site hydrometallurgical
treatment using ambient acid leach
process/possible stabilization/fixation/
off-site disposal ,
Estimated Costs
3 Criteria
N/A
N/A
N/A
- N/A
N/A
1 N/A
N/A
9 Criteria
eliminated
eliminated
$50,200,000
$40,100,000
eliminated
$19,189,569
eliminated
I	r
         'Includes stabilization/fixation.
1026
                                               -3-

-------
7.      How did the cost(s) compare to standard technologies?            \.   ~

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)    |
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-3C
(RAA-2)
RAA-4
(RAA-3)
RAA-5A-1
(RAA-4)
RAA-5A-2
RAA-7AC
RAA-7BC
Standard Technology
No action
Institutional controls .
Excavation/on-site disposal in existing
FDS facility/cap/vegetatibn/institutional
controls
Excavation/on-site disposal in upgraded
existing FDS facility (to RCRA Subtitle
C TSD design standards)/cap/
vegetation/institutional controls
Excavation/on-site disposal in new
repository facility (constructed to
RCRA Subtitle C TSD design stan-
dards)/cap/vegetation/institutional
controls
Excavation/off-site disposal in RCRA
Subtitle C TSD facility
Excavation/separation and on-site
disposal of debris/cement- or silicate-
based stabilization/fixation/on-site
disposal in an engineered repository
Excavation/separation and on-site
disposal of debris/cement- or silicate-
based stabilization/fixation/off-site
disposal in a RCRA Subtitle C TSD
facility
Excavation/on-site pyrometallurgical
treatment using electric arc furnace
(Elkem)
Excavation/on-site pyrometallurgical
treatment using rotary kilri
1 . • . *
Estimated Costs
3 Criteria
N/A
N/A
N/A
• '!
N/A '
l
'
[N/A
• - -i
:i
- ',!
1
IN/A
|N/A .'
;i ..
i
'i
NA
i
eliminated
.1
.a
eliminated .
9 Criteria
$0
eliminated
eliminated
eliminated
$6,911,000
$71,933,000
$21,866,000
eliminated
eliminated
eliminated
       Eliminated after being considered but before three criteria screening.
                                           -4-
                                                                                    1027

-------
&      If a standard technology was chosen, why?

        RAA-4 was chosen because it would p-ovide the greatest overall protection through the
        containment of the stabilized waste.  an effective long-term material and in a timely manner (3
        years). Stabilization/fixation provides a high degree of long-term effectiveness and
        permanence by immobilizing the hazardous constituents through stabilization. Also, since it is
        a proven technology, the uncertainties associated with long-term effectiveness and permanence
        are less than for the hydrometallurgical technologies. Treatability testing indicated that the
        stabilized materials would immobilize arsenic, cadmium, and lead to meet regulatory limits and
        provide for long-term stability as determined from leaching test used by the American Nuclear
        Society. By having the least number of untreated flue dust handling and  transportation steps,
        risks to workers and the environment are less than for any  other option. The technology is
        demonstrated, uses standard equipment, and would be easily implemented.
                                                                                        •• •   .             -'   i	•••

9.      If an innovative technology was chosen, why?

        An innovative technology was not chosen.


10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                                                                                         i    I -
       Innovative technologies eliminated during the original initial screening [FS I report] include                 |
       the following:                                             -

       «      Hydrometallurgical process (Kennecott) was eliminated because the level of
               development of the technology is questionable. The technology produces a solid                    i
               residue that would contain arsenic and lead in oxidized, mobile forms; thus, the
               process would not be effective in reducing the mobility or toxicity of flue dust                      ;
               contaminants.               ,,                                    .         •
       «      Hydrometallurgical process (ammonium leach) was eliminated because the level of                . "\
               development of the technology is questionable. The technology potentially produces a
               solid residue that might contain arsenic in oxidized, mobile forms; thus the process
               would not be effective in reducing the mobility or toxicity of flue dust contaminants.                !
       "      Hydrometallurgical process (U.S. Bureau of Mines alkaline leach) was  eliminated                   !
               because the level of development of the technology is questionable.  The technology
               potentially produces a solid residue that might contain arsenic in oxidized, mobile                   t
               forms; thus, the process would not be effective in reducing the mobility or toxicity of                '
               flue dust contaminants.                                                                          I
       "      Hydrometallurgical process (Metallhute Carl Fabusch) was eliminated because of
               potential incompatibilities With the chemical characteristics of flue dust. Flue dust is                ;
               predominantly sulfate-based, rather than chloride-based, and thus the initial
               dechlorination step would be inappropriate.  Additionally, the flue dust  contains                     T
               arsenic.  Since the reaction pathways for arsenic are uncertain, this process might not       4|lk   \
               be effective.                                                                         - ^[Jr   ./


1028                                                                                                   1
     t                                                          :                                              \'
                                              -5-   •  .              '     -  .              ..        •    •     .;""

-------
•      Hydrometallurgical process (chloride leach) was eliminated because it would produce
       a metal residue byproduct that contains arsenic and lead in potentially mobile forms.
       The metal residue would not be saleable because of its elevated arsenic concentrations.
•      Pyrometallurgical process (PLASMADUST) was eliminated bescause the technology has
       not been demonstrated to be effective for the treatment of copper smelter flue dusts.
•      Pyrometallurgical process (cyclone smelting) was eliminated because the technology
       generates a byproduct dust that contains arsenic, cadmium, and lead in potentially
       mobile, oxidized forms. The dust constitutes nearly 40 percent of the original volume
       of material treated.            -                            I          .          •
•      In situ leaching was eliminated because the characteristics of the flue dust locations
       would limit control of in situ leaching treatment; and the physical characteristics of the
       flue dust (i.e., degree  of compaction), and chemical characteristics of the flue dust
       (such as extent of compositional variation) might limit its applicability.
•      In situ biological treatment was eliminated because the flue dust locations would limit
       control of in  situ leaching treatment; and the physical characteristics of the flue dust
       (degree of compaction), chemical characteristics of the flue dust (extent of
       compositional variation), and the lack of an organic matrix acid a nutrient base to
       support the biosystem would limit its applicability.                  .

Innovative technologies eliminated during the 'second initial screening; criteria include the
following:                :
                      •"-.'''            .           •         i'
•      Hydrometallurgical process-(Dowa) was eliminated because pilot tests at the facility
       could not be secured.                                                     ,
•      Hydrometallurgical process (sulfide precipitation) was eliminated, but no explanation
       was given. The technology  is confidential business information  (CBI).
•'     Pyrometallurgical process (arsenic volatization) was eliminated  because treatability
       testing indicated insufficient arsenic removal through volatization.
•      Commercial  hydrometallurgical/pyrometallurgical processing was eliminated because,
       though Falconbridge, Ltd., responded favorably, testing at the Kidd Creek facility
       would take up to 10 years because of limited facility capacity. Additional reasons
       include: (1) the lack of process-specific data on flue dust trealability; and (2) treatment
       of flue dust at Kidd Creek would require transporting hazardous materials across •
       international boundaries. No other facilities reported, favorably to inquires regarding
       the processing of the flue dust.
•       Vitrification  was eliminated because of the volatization of arsenic: during the process.
                                         •                      -i-
The treatability tests were followed by a summary stating: "Based on the results of ... tests ...,
three treatment technologies ...  will be subjected to detailed technical analyses.  CementTbased
stabilization/fixation was selected as being representative of the stabilization/fixation
technology type, while the Cashman process and the ambient acid leach process were selected
as being representative of the hydrometallurgical processing technology  type. Pyrometal-
lurgical processing and commercial  processing did  not indicate promising results relative to
treating Smelter Hill flue dust."

Representative technologies were chosen because the remaining hydrometallurgical and
Pyrometallurgical options  and stabilization/fixation technologies were! similar. Following the
treatability studies, the selection of representative technologies were modified, resulting  in the
elimination of the following hydrometallurgical processes prior to the> three-criteria screening:

 •      Shenyang                .                 •-.''•


•   ••          .'.'',:"'      '    •  •'--      .           .    "    •-•.'   '"."•   1029

-------
        •     Anaconda Research
        c     Anaconda Modified Dowa                     .,.,-.                 /
        c     Sulfur Dioxide Leach
        •     Con Mine                    .                                        '

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                   .                            ,     -

        •     None.'  .

        Innovative technologies eliminated during the detailed analysis include the following:

        •     Hydrometallurgical process (Cashman) was eliminated because it would take longer (7
               to 10 years) to achieve the same level of protection as stabilization/fixation; its success
               would be less certain than with stabilization/fixation; short-term risks could be posed
               that could affect workers and the environment, including the production of additional
               waste streams; a relatively complex processing facility would have to be built, which
               would require exceptionally expensive construction materials; maintenance of the
               facility would be more difficult than stabilization/fixation; the technology has not been
               proved on a full scale; its implementability is considered uncertain; and, based on a
              . sensitivity analysis, the cost could vary greatly ($27 million to $88.4 million ) with
               additional stabilization.
        «      Hydrometallurgical process (acid ambient leach) was eliminated because it would take
               longer (7 to 10 years) to achieve the same level of protection as stabilization/fixation;
               its success would be less certain than with stabilization/fixation; short-term risks could
               be posed that could affect workers and the environment, including the production of
               additional waste streams; a relatively complex processing facility would have  to be
               built, which would require exceptionally expensive construction materials; maintenance
               of the facility would be more difficult than stabilization/fixation; the technology has
               not been proved on a full  scale; its implementability is considered uncertain; and,
               based on a sensitivity analysis, it has a high degree of cost variability ($6.5 million to
               $34.7 million).
11.
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion?  Which of the criteria supported the use of a standard technology?

Three criteria were important in selecting the technology.  First, stabilization/fixation has been
demonstrated to provide the greatest overall protection through containment of stabilized Waste
in a timely manner. While the alternatives that included hydrometallurgical treatment might
provide the same degree of protection, hydrometallurgical treatment would take longer to
complete than stabilization/fixation.  Second, stabilization/fixation provides a high degree of
long-term effectiveness and permanence by immobilizing the  hazardous constituents:  Also, it
is a proven technology. The long-term effectiveness and permanence are less certain for the
chosen technology than for the hydrometallurgical technologies.  And three, it provides the
greatest short-term effectiveness by having the least number of untreated flue dust handling
and transportation steps.
 1030
                                              -7-

-------
       12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
              ARAR?  What risk level was selected to establish cleanup goals?   ••!.-•'
                                                   ,...'•'•'       -   ',.,.!•.-

              Cleanup goals were not provided.  The flue dust will be treated to render the material
              nonhazardous by meeting RCRA TCLP regulatory limits (Maximum Concentration of
              Contaminants for the Toxicity Characteristic, ARM § 16.44.324, as detennined by the Toxicity
              Characteristic Leaching Procedure).                             -
       13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
              technology meet the cleanup goals?                                      :
       •\           • •'  ''"'      '        •  -       '        ''"'    " •     -  '  "•    . :l  v- •••••'
              Innovative technologies eliminated because of cleanup goals include:
                                          •           •"                        I     '     '••".-.
              •      None                                                   |
            i                        • '                              '          !                  • •
                                     ~      .     -'         ••' '         •        1  ...-'
              Standard technologies eliminated because of cleanup goals include:   |
                                                                            1          '   ',*•.-
              •      None
O
14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were performed on die following technologies:   ;
                              ''"'.".'        -     '            . !'•'.•
              Cement-based stabilization/fixation (HAZCON and MSB, Inc.)
              Cement- and fly-ash-based stabilization/fixation (Dames and Moore)
              Silicate-based stabilization/fixation (CHEMHX Environmental Services)
              Hydrometallurgical process:  Cashman
              Hydrometallurgical process:  Sulfide precipitation
              Hydrometallurgical process:  Ambient acid leach
              Pyrometallurgical process: Arsenic volatization
              Commercial processing (Falconbridge, Ltd.)
              Gravity separation process (PASAR)
       75.    What measures/criteria were used to compare, alternatives?

             The following measures were used to compare the alternatives:

                   Time to design/construct/operate
           '  -     Proven reliability                             ,
             -     Single vs. multistep treatment


       16.    How are measures compared?

             Stabilization/fixation would be completed in 3 years compared to the hydrometallurgical
             processes which would take between 7  and 10 years. The treatability j studies showed that there
             were uncertainties concerning hydrometallurgical processes'  success and implementability;
             these uncertainties do not exist for stabilization/fixation.  For short-teitn effectiveness,
                                                    -8-
                                                                                          1031

-------
          stabilization/fixation has fewer steps involving transportation of untreated flue dust than any of.
          the other options; this process, therefore, minimizes the hazards associated with flue dust
          transportation.


   17.     What technical considerations were factors in selecting a remedy? Were technical
          considerations primary in the selection of the remedy?

          Treatment considerations were not primary in selecting a remedy. The site is capable of
          accommodating on-site disposal.  Since the transportation of flue dust presents  hazards to
          workers and the environment, on-site disposal was preferred. The physical characteristics of
          flue dust locations also were factors.  The applicability of in situ treatment was limited because
          only  two of the nine flue dust locations are lined.  Of the remaining seven locations, one has a
          low-permeability cap, which would limit the extent to which leaching solution could be
          brought into contact with the flue dust. Since the remaining six flue dust locations are not
          lined, maintaining the control of in situ leaching treatment would be extremely difficult.
103?
                                                -9-

-------
                              Broderick Wood Products
                                         OU-2

                                 Adams County, Colorado
                                        Region 8
GENERAL SITE INFORMATION  ,        ,

1.      What were the principal contaminants,
  '     contaminant levels, and media  addressed in
       this feasibility study?

       Maximum concentrations of principal '
       contaminants were:              ,

       Soil (surface/subsurface in ing/kg)

       Carbazole                  21.4/77.3
       Naphthalene                11,000/2,500
       Phenathrene                14,000/680
       Pyrene                     7,800/306
       Benzo(a)anthracene         1,200/72
       Chrysene            .      2,200/99.5
       Benzo(b)fluoranthene       200/11.1
       Benzo(k)fluoranthene       500/100
       Benzo(a)pyrene             500/100
       Dibenzo(a,h)anthracene      500/100
       Indeno(l,2,3-cd)pyrene      500/100
       Benzene                   0.33/0.625
       Toluene                   4.7/25
       Xylene    ,                 21.4/160
       Pentachlorophenol          8,600/380
       2,3,7,8-Tetrachloro-
         dibenzo-p-dioxin ,
       Pentachlorodibenzo-p-dioxin
       Hexachlorodibenzo-p-dioxin
       Heptachlorodibenzo-p-dioxin 5.65/0.9596
       Octachlorodibenzo-p-dioxin  42.7/3.0066
       Arsenic                   187/11.4
       Cadmium                  193/2.4
       Lead                      7,140/208
                            Site History
                NPL Proposed:
                NPL Final:
                FS:
                ROD:
9/83
9/84
6/91
3/92
                            Background
                PRP-lead       ;
                PRPs:  Brodericl; Investment Company
                FS prepared by:  N/A
0.00155/0.0007
0.0079/0.001
0.31/0.0269
        Sediment (mg/kg)

        PAHs
0.00665
                                            -1-
                                                    1033

-------
 2.      What volume of material is to be remediated?                     ,

         The volume of material to be remediated included:

         •      59,100 cubic yards of organics-contaminated soil                       ,
         •      120 cubic yards of organics-contaminated sediment                              .
         •      800 cubic yards of metal-contaminated soil


 3.      What type of site is this?                                       .

        Lumber and Wood Products.  A former wopd treatment facility located in an industrial area.


 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:      Deed restrictions, fencing
        Containment:          Capping (clay, multilayer, asphalt, concrete)
        Chemical treatment:    Fixation
        Physical treatment:     Size separation, dewatering
        Thermal treatment:     Incinerator (infrared, rotary kiln, fluidized bed, circulating bed, process
                              kiln)
        Disposal:           •   Excavation, land  disposal, raw material use (asphalt blending)


5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:  Biological treatment (in  situ, ex situ), composting, liquid/solid slurry
        Phys/Chem treatment:  In situ chemical flushing, in situ air stripping, soil washing, solvent
                             extraction (RCC's BEST Process, CF System's Supercritical
                            . Extraction)
        Thermal treatment:     Thermal desorption
6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. The estimated costs are calculated during an evaluation based on nine criteria
       established by the NCP.                 ,                          -.
 1034
                                             -2-

-------
Initially, remedial alternatives for each contaminated media (organics^ontaminated
soil/sediment, metal-contaminated soil, ground water, and buildings), i were assembled from
applicable remedial process technology options and were screened for effectiveness,
implementability, and cost. For the detailed analyses, alternatives for each media passing the
initial screening were combined into alternatives that addressed all media and costs were based
on a NT* risk level.  In the ROD, alternatives were divided once again by media and
excavation and cost estimates were based on a Itf5 risk level. These Variations in alternatives
are presented in separate tables  below.
Cost Estimates for RAAs That Include Innovative Technologies
(selected remedial alternative is in bold)
1 ' • !' •
Organics-contaminated Soil/Sediment Above 10"4 Cleanup Level
Alternative
RAA-4
RAA-5
RAA-6
RAA-9
RAA-10
Innovative Technology
In situ surface biological treatment
Ex situ surface biological treatment
Solvent extraction/on-site landfill
Thermal desorption/on-site landfill
Thermal desorption/off-site landfill
Estimated Costs
3 Criteria
$274,000
$1,144,000
$4,270,000
$3,940,000
$6,5134,000
9 Criteria
retained
retained
eliminated
retained
retained
Organics-contaminated SoiVSediment Above 10* Cleanup Level
Alternative
RAA-5
RAA-6
• ,. ' •> • ,•
Innovative Technology
Thermal desorption/on-site landfill
Thermal desorption/off-site landfill
Detailed Analyses
Alternative
RAA-2
RAA-3
Estimated Costs
3 Ciiteria
$50,235,000
$131,235,000

Innovative Technology
In situ surface biological treatment of soils with ,
organics above lO^/excavatibn and in situ biological
treatment of sediment/off-site landfill for metal-
containing soil above 1 (^/institutional controls for soil
between ICT* and W6
Excavation/ex situ biological treatment of soil
containing organics above 10"Vexcavation/fixation of
metal-containing soil above lO'Vinstitutional controls
for soil between 10"4 and 10"6
9 Criteria
.eliminated
eliminated

Estimated
Costs
9 Criteria
$4,551,000
$5,350,000
                                    -3-
1035

-------
        Alternative
       RAA-4a
       RAA-4b
       RAA-5
       RAA-6
       RAA-7a
       RAA-7b
       RAA-8
       RAA-9
               Innovative Technology
Excavation/on-site theraial desorption and on-site
landfilling of soil containing organics/excavate
sediment above 10"4 and chemical fixation of soil
containing metals above lO^/institutional controls for
soils between IV4 to 10"6
Excavation/on-site thermal desorption and off-site
landfilling of soil containing organics/excavate
sediment above 10"4 and chemical fixation of soil
containing metals above 10~Vinstitutional controls for
soils between W4 to 10'6
In situ surface biological treatment of soils with
organics above lO^/excavation and in situ biological
treatment of sediment/chemical fixation of soil
containing metals above lO^/institutional controls for
soils between 10"4 and W6
.Ex situ surface biological treatment with organics
 above lO^/excavation and in situ biological treatment
 of sediment/chemical fixation of soil containing
 metals above lO^/institutional controls for soils
 between 10"4 and
 Excavation/on-site thermal desorption and on-site
 landfilling of soil containing organics/excavate
 sediment above 10"4 and chemical fixation of soil
 containing metals above KTVinstitutional controls for
 soils between 10"4 to
 Excavation/on-site thermal desorption and on-site
 landfilling of soil containing organics/excavate
 sediment above 10"4 and chemical-fixation of soil
 containing metals above KTVinstitutional controls for
 soils between 10"4 to 10'6
 In situ surface biological treatment of soils with
 organics above KTVexcavation and in situ biological
 treatment of sediment/chemical fixation and on-site
 landfilling of soil containing metals above 10"4/
 institutional controls for soils between 10^ and 10*
 Ex situ surface biological treatment of soils with
 organics above ICTVexcavation and in situ biological
 treatment of sediment/chemical fixation and on-site
 landfilling of soil containing metals above 10"4/
 institutional controls for soils between 10"4 and 10"6
                                                                               Estimated
                                                                                  Costs
 9 Criteria
$10,515,943
$12,509,818
$11,675,000
$12,474,000
$17,639,733
$19,633,609
$12,870,000
$13,669,000
1036
                                            -4-

-------
7.
Alternative
RAA-lOa
RAA-lOb
ROD
Alternative
RAA-2
RAA-3
RAA-4
,i
Innovative Technology
Excavation/on-site thermal desorptiori and on-sitfe
landfilling of soil containing organics/sediment aibove
lO^/excavation and chemical fixation and off-site
landfilling of soil containing metals above 10"
"/institutional controls for soil between 10"4 to
10"6 (same as 7a except additional groundwater
treatment)
Excavation/on-site thermal desorption and on-site
landfilling of soil containing organics/excavate
sediment above W4 and chemical fixation of soill
containing metals above lO^/institutional controls: for
soils between W4 to W*
Estunated
Costs
9 Criteria
$17,639,733
$19,633,609

r .
Innovative Technology
Thermal desorption of organics-contaminated soil-
sediment/fixation of soil contaminated with metals/
off-site disposal
In situ bioremediatiqn of organics-contaminated soil-
sediment/fixation-of soil contaminated with/off-sile
disposal '.••'•'.
Ex situ bioremediation of organics-contaminatf ;d
soil-sediment/Hxation of soil contaminated with
metals
Estimated
Costs
ROD
$32,388,000
$3,039,000
$4,493,000
How did the cost(s) compare to standard technologies?            j
                           '       -        -            •"['•*.'

         Cost Estimates for RAAs That Include Standard Technologies
                   (selected remedial alternative is in bold)  *
Organics-contaminated Soil/Sediment Above ID"4 Cleanup Level
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Institutional controls
Multilayer cap
Estimated Costs
3 Criteria
$6
$51JOOO
$7,053,000
9 Criteria
$0
. eliminated .
eliminated
                                  -5-
                                                                          1037

-------
Alternative
RAA-7
RAA-8
Standard Technology
Fixation/on-site landfill
Off-site incineration ,
Estimated Costs
3 Criteria
$3,242,000
$26,857,000
9 Criteria
eliminated
eliminated
       Metals-contaminated Soil/Sedinient Above W4 Cleanup Level
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Standard Technology
No action
Institutional controls
Multilayer cap
Fixation/on-site landfill
Fixation/off-site landfill
.Estimated Costs
3 Criteria
$0
N/A
$1,814,000
$219,000.
$171,000
9 Criteria
retained
eliminated
eliminated
eliminated
retained
Organics-contaminated Soil/Sediment Above 10"5 Cleanup Level
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action
Institutional controls
Multilayer cap
Off-site incineration
Estimated Costs
3 Criteria
$0
$51,000
$30,140,000
$481,621,000
9 Criteria
retained
retained '
eliminated
eliminated
        Detailed Analyses
Alternative
RAA-1
Standard Technology
No action
Estimated
Costs
9 Criteria
$0
ROD
Alternative
RAA-1 ,
Standard Technology
No action
Estimated
Costs
ROD
$0
1038
                                          -6-

-------
  8.
!f a standard technology was chosen, why?                       '  .

Fixation of metals-contaminated soil and off-site disposal of residuals were selected.
  9.
If an innovative technology was chosen, why?
                           -                          protect human hea1   a.id the environment by
                   t    ,    if1"'  ™!S {dteraative reduce* contaminant toxicity,, mobility, and volume
                treatment via bioremediation of organics contaminated soil/s^iment, and fixation of
                               * ^ Provideslon^nn effectiveness because treated soil/s^ment
        ™nl   H     ,  *nsin?re* waste management units and institationai controls will be
        employed.  Following the implementation of these treatments the contaminated levels of the
                  d ^anics-contaminated soil/sediment will be reduced to c,r below the 10" cancer
                  P    "u *" mdUStnal USe SCenari°- ^ rcmedv Complies witib ARARs and is cost
                  Ex situ bioremediation is a relatively simple treatment technology that will be «£?

                                                                       ~    '
              °d      ^ ide"tified RAA-3 (in situ bioremediation) as he preferred alternative
                              "nd excavation volume based 0" a 10"4 action level for all soil
                 s, but-only presented a cost and excavation volume for the lO'5 action level for ex
        smi bioremediatipn.  In the ROD, the EPA analyzed all soil remediation levels at ^ for
        easons of comparison. EPA has determined that the increased cost of implementing a  lO'5
                   °reVat   i JUStified by *e '***** ™ lon^nn effectiveness and'
                                    S ! reSUlt °f greater SOUrce «*"«ion, for I^und water.  In
        voWP  f       -           r°dUCeS a greater reductiori in the toxicity, mobility, and '
        volume of contaminants through treatment. The only criteria that favcired a .iff* ^ti?n level
        were cost and short-term effectiveness. Short-term effectiveness is notia significant factor
        however, because it can be easily addressed.  The cost between the  two iSonSSb
        selected remedy was not substantial. When considered in terms of the selected remedy
        increase in cost of using the 10'5 action level is accompanied by  a proportional i

        e°ffect ve6         " "*"* ""*" " ^ C°ndUSi°n  ^ US6 °f ^  10 '
10.


       Innovative technologies could be eliminated from the remedial technology selection process at

       SStitfess ±1 "  ^^ SCTing; dUrfng *e SCreeninS °f ** *™ criteria of       '
       effectiveness, implementabihty, and cost; or during the detailed evaluation.
                                          "         . ''      '.             I      - •,-','
       Innovative technologies  eliminated during the initial screening include ihe following:

       •      In situ air stripping was eliminated because it would be most appropriate for VOC
              ± b'T n°t1S18niflCant «iinants at the site. Furthermore  it would co t more
              than biological treatment and it would not be effective for shallow, relatively
              impermeable surface and subsurface soil.                     !
       «      In situ chemical flushing Was eliminated'because it would result1 in ground water
              contamination from flushing chemicals and the technical implementability of this ,
                                            -7-
                                                                                       1039

-------
             process at theTTte is uncertain.  If surfactant flushing was utilized the resulting
             emulsions of ;wafer, surfactant and contaminant would be difficult to treat on the
             surface.  In addition, surfactant tends to disperse and suspend clay and silt particles,
             which eventually might result in the formation of a plug decreasing the local
             permeability.  In turn, this might lead to channeling, decrease the process control, and
             threaten the aquifer. Alkaline and alcohol flushing are not as well studied and were
             deemed not sufficiently developed to consider further.  Alkaline flushing might alter
             the soil chemistry and other aspects of the local ecosystem.
      •      Soil washing was eliminated because it is not a  demonstrated, full-scale technology.
             Furthermore, the volume of residuals is higher than with solvent extraction.
      •      Composting was eliminated because it has not been demonstrated on creosote
             contaminated soil.  Furthermore, surface biological treatment is the most appropriate
             biological treatment for this site.
      •      Liquid/solid slurry was eliminated because.it  has been demonstrated on creosote
             contaminated soil but it has most often been applied as an in situ process for closure
             of surface impoundments containing wastewater and sludge. In at least one case,
             residuals had to be further treated in a surface treatment system.

      Innovative technologies eliminated during the screening of the three criteria include the
      following:

       •      Solvent extraction for organics-contaminated  soil/sediment was eliminated because its
              effectiveness would need to be verified in treatability tests, and it might not be easily
          '    implemented because it is  an innovative untested alternative which would require
              specialized equipment and personnel.  Furthermore, it would not provide greater
              overall protection than other alternatives and it would be more expensive.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Thermal desorption was eliminated because it would be more expensive to implement
              than the chosen remedy.  It also would pose the greatest short-term risk of the
              proposed alternatives due to the threat of air emissions.
       •      In situ bioremediation was eliminated because  it would not provide as much
              protection, long-term effectiveness, or reduce contaminant toxicity, mobility and
              volume as well as the chosen  alternative.  It would address only surface soil and
              treated soil which might contain residuals would not be contained.
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment, long-term effectiveness, reduction in
       contaminant toxicity, volume and mobility, and cost were the criteria weighted most heavily in
       selecting a remedial alternative.  RAA-4 was preferred over RAA-3 because it would be more
       protective since surface and subsurface soil/sediment would be excavated, treated and isolated
       in an engineered  containment structure. RAA-3 also would not treat subsurface soil and
       therefore could not reduce contaminant toxicity, mobility and volume or provide long-term
       effectiveness as well as the chosen alternative.  The chosen alternative was the cost-effective
       option. RAA-2 also would pfovide high overall effectiveness but it would be much, more
       expensive than the chosen alternative. RAA-3 would be much less expensive than the chosen
 1040
-8-

-------
12.
alternative but it would not provide as great a degree of long-term effectiveness or reduction in
contaminant toxicity, volume and mobility.
What cleanup goals were selected?  If the cleanup goal was based en an ARAR, what was thai
ARAR?  What risk level was selected to establish cleanup goals?

Cleanup levels were derived for both the excavation of soil/sediment and the treatment of
soil/sediment.
       Excavation of Soil/Sediment
Contaminant
Carcinogens
Carbazole (soil)
Carbazole(sediment)
Benzo(a)anthracene
Chrysene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Benzo(a)pyrene
Dibenzo(a,h)anthracene
Indeno(l ,2,3-cd)pyrene
Benzene
Pentachlorophenol '
Pentachlorodibenzo-p-dioxin
Hexachlorodibenzo-p-dioxin
Heptachlorodibenzo-p-dioxin
Octachlorodibenzo-p-dioxin
Arsenic
Cleanup Level (mg/kg)

2,222.22
23.2
1,250
5,988.02
146.41
117.51
15.02
13.91
578.03
2,557.54
1^90.36
0.000303
0.001517
0.015175
0.151745
6.134969
AKAR or Other Basis

Risk"
Ecologicalb
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
i Risk
Risk
Risk
      "Health-based cleanup levels ensure that a cumulative cancer risk' level of 10'5 is
      achieved in unexcavated soil.
      'The cleanup level for carbazole in sediment is-based on ecological risk factors.

      Treatment of Excavated Soil
              Contaminant
                                         Cleanup Level (mg/kg)
                                                           AIIAR or Other Basis
        Carcinogens
        Benzo(a)pyrene
                                                  15.2
Risk8
                                    -9-
                                                                              1041

-------
Com liant
Dibenzo(a,h,onthracene
2,3,7,8-TCDD equivalent
Pentachlorophenol
Lead (K001 Constituent)
Arsenic
Cadmium
Lead
Cleanup Level (rag/kg)
13.9
0.0006
90-99%
99-99.9%
5
1
5
ARAR or Other Basis
Risk
Risk/treatment level"
LDRsc
LDRs
TCLP"
TCLP
TCLP
Noncardnogens
Naphthalene
Phenanthrene
Pyrene
Toluene
Xylene (Total)
95-99%
95-99%
95-99%
0.5-10
0.5-10
LDRs
LDRs
LDRs
LDRs
LDRs
               These treatment levels fall within the 10"6 to 10'7 risk range for an industrial use
               scenario.                                        .
               "Laboratory detection limitations may not allow measurement to this level. In that
               case, the detection limit will be the treatment level.  The currently recognized  detection
               level of 1 ug/kg corresponds to a cancer risk level close to 10"5.
               "Remedy will comply with LDRs through a Treatability Variance. Treatment  levels or
               percent reduction ranges that ex situ  bioremediation will attain are presented.
               •"Action levels are based on non-wastewater TCLP (mg/L).
 75.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                •

        Innovative technologies eliminated because of cleanup goals include:              ,

        "     None

        Standard technologies eliminated because of cleanup goals include:           ,   ,
     t                •                                           ' •                 *
        •     None          '   •
 14,    Were treatability studies conducted on the innovative technology or standard technology?
        The efficiency of several technologies'was evaluated for the screening of alternatives. .
        Technologies evaluated include: in situ surface biological treatment, ex situ surface biological
        treatment, solvent extraction, chemical fixation, and thermal desorption;
1042
                                               -10-

-------
 15.     What measures/criteria were used to compare alternatives?         i
     '     •      -  '                         X*            .          :     |            '.        ' "
        The following measures were used to compare the alternatives:     i
                                                 • '                     !
              Risk level achieved                                        I
              Cost-effectiveness                                         i            .-.-•
              Proven reliability
              Waste left in place/institutional control


 16.     How are measures, compared?

        Ex situ bioremediation was preferred over thermal desorption because it would be more easily
        implemented. Ex situ bioremediation is a relatively simple treatment technology, easy to
        construct and operate, and has been successfully implemented at other sites  Thermal
        desorption is a new and more complex technology and requires specialized equipment and
        knowledge which makes it more difficult to procure, construct, and operate. In addition air
        quality matters in the Denver Metropolitan area might make thermal desorption more difficult
        to implement.  In situ bioremediation was not preferred because it would not treat subsurface
        soils and control of residual risk would  be more dependent on institutional controls  The
        chosen alternative is cost effective.  RAA-2 also would provide high Derail effectiveness but
        it would be much more expensive than the chosen alternative.  RAA-3 would be much less
        expensive than the chosen alternative but it would not provide as great a degree of long-term
        effectiveness or reduction in contaminant toxicity, volume, and mobility
17.
What technical considerations were factors in selecting a remedy? Were technical    •
considerations primary in the selection of the remedy? ,

Technical considerations were not primary in selecting a remedial alternative. Impervious site
soil, however, would preclude the use of in situ air stripping.
                                            -11-
                                                                                        1043

-------
                                Central City-Clear Creek
                                          OU-3

                         Gilpin and Clear Creek Counties, Colorado
                                         RegionS
GENERAL SITE INFORMATION
7.
      What were the principal contaminants,
      contaminant levels, and media addressed in
      this feasibility study?        .

      Maximum concentrations of principal
      contaminants were:

      Tailings/Waste Rock (mg/kg)
       Arsenic
       Lead
                            630 ,
                            2,810
 2.
       What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:
                                                                Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     N/A
                     9/83
                     9/91
                     9/30/91
             Background

PRP-lead            .
PRPs:  not yet determined
FS prepared by: Camp Dresser &
       McKee Inc.
       •   .   1,170,800 cubic yards of taijings/waste rock piles


3.      What type of site is this?

       Mining. An ore mine..                            ,              .


TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                                •

       Access restriction:     Inspection, resident relocation, fencing, deed restrictions
       Containment:         Retaining walls, recontouring, grout stabilization, synthetic liners,
                            pavement cap, soil cap, cement cap, clay cap, RCRA cap, vegetative
                            cap                            ,'•••••
       Chemical  treatment:   Neutralization
       Thermal treatment:    Incineration
       Disposal:
                              .U * W* A* V*. Mfc* v»             -  •                     ^
                              Excavation, on-site disposal, off-site disposal at RCRA landfill
  1044
                                              -i-

-------
 5.
  Was an innovative technology considered in the FS? If so, which technology?


  Innovative technologies considered during the identification and screening of technically
  feasible technologies were:                                       ;
                                                       ,-          i

  Biological treatment:  Biodegradation

  Chemical treatment:    Soil washing, soil flushing, hydrometallurgical njprocessing-chemical

                       leaching, hydrometallurgical reprocessing-froth flotation

  Thermal treatment:    Pyrolysis, in  situ vitrification, pyrometallurgical reprocessing
                "             '                -                   I
 : -             ...      .._-••                 •  j
            ~! -              '                   '    '              ' !  '    -"'        '

  What was the cost estimate for the innovative technology?          '••.  '


 During the initial screening process, in which technically feasible technologies are identified

 (pnor to the formulation of RAAs), the FS does not quantify costs.  After me RAAs have teen

 formulated costs are estimated as part of a three-criteria screening proceiss (effectiveness

 implementabihty,  and cost) to identify alternatives that merit a more Detailed evaluation   The

                       KCaICUlated during M Cation  based on the nine criteria established
       No : innovative technologies were incorporated into remedial action allernatives and no cost
       estimates were made.
7.
 How did the cost(s) compare'to'Standardtechnologies?              '


 Media-specific remedial alternatives (i.e., tailings/waste rock) were developed for the three-
 cntena screening process, and site-wide remedial alternatives were developed for the detailed
 analyses.  The results of these two processes are presented separately.!


          Cost Estimates for RAAs That Include Standard Technologies
                     (selected remedial alternative is in bold)


Tailings/Waste Rock Alternatives
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action/annual inspection
Access restrictions/slope recontouring/
sediment traps/on-site disposal of
collected sediment
Excavation/hydrometallurgic
reproces$ing-froth flotation/ on-site
disposal
Recontouring/installation of retaining .
walls/soil cap/sediment traps/use
restrictions
Estimated Costs
3 Criteria
$110,000
$3,590,000
$33,3(K),000
$3,780,000
- ••• v" " • . -2- -. V ; . ; \. :' ',.
9 Criteria
retained
retained
eliminated
retained
1045

-------
         Alternative
       RAA-5
       RAA-6
       RAA-7
        Standard Technology
On-site consolidation/disposal cell
development/land acquisition/
excavation/transport/on-site disposal/use
restrictions

Excavation/transport/off-site disposal/
use restrictions
• ..  i.^u^^-*m
Fixation of tailings and waste rock/use
restrictions
                                                                     Estimated Costs
                                                                 3 Criteria
                                                                $15,490,000
                                                                 $23,350,000
                                                                 $5,570,000
            9 Criteria
                                                          retained
            eliminated
            eliminated
      Site-Wide Alternatives:  these combine the Tailings/Waste Rock Alternatives and the Surface
      Water Alternatives and were the only alternatives that, underwent detailed evaluation.
          Alternative
         ••—^p*—«—•
        RAA-1
        RAA-2
        RAA-3
         RAA-4
         RAA-5
         RAA-6
         Standard Technology
 No action/annual inspection/ground and
 surface water monitoring
         	_^^^—^•^•••^•^^••^^^••^^•••^•'''•^—
 Access restrictions/slope recontouring/
 sediment traps/oh-site disposal of
 sediment/passive discharge and water
 treatment in artificial wetlands
                                                                      Estimated Costs
                                                                 3 Criteria
N/A
                                                                    N/A
 Recontouring/installation of retaining
 walls/soil cap/sediment traps/use
 restrictions/passive water treatment
  Recontouring/installation of retaining
  walls/soil cap/sediment traps/use
  restrictions/active discharge and water
  treatment
                                                                     N/A
  Recontouring/installation of retaining
  walls/soil cap/sediment traps/use
  restrictions/passive discharge and water
  treatment in artificial wetlands/pump
  and treat ground water
                                                                     N/A
                                                                     N/A
  On-site consolidation/disposal cell
  development/land acquisition/
  excavation/transpqrt/on-site disposal/use
  restrictions/discharge water treatment/
  pump and treat ground water
                                                                      N/A
                                                         9 Criteria
$550,000
            $23,890,000
            $24,080,000
            $33,400,000
            $28,630,000
             $50,820,000
                  4»
1046
                       -3-

-------
 5.
            Alternative
           Selected
           Alternative
                            Standard Technology
                    Institutional controls/soil cap/passive
                    treatment of some discharge water/
                    active treatment of some discharge
                    water/pump and treat ground water
                                                                        Estimated Costs
                                                                   3 Criteria
N/A
                                                                           9 Criteria
$23,510,000a
 The selected alternative and associated costs were developed and presented in the ROD.
                                                                '

 If a standard technology was chosen, why?
                                                                          critical components
               -5 and RAA-6. /The selected alternative combines institutional controls and runoff
        barriers for mine waste piles at active mill sites, soil capping of the olher mine wastTpUes
        active treatment^ one tunnel, passive treatment of one tunnel, and a grounTater p^mp wd-
        treat system,  Tins provides the greatest protectiveness of human health and the enSoTmeT
        complies with ARARs, reduces mobility of waste contaminants, reduces toxicity of wateT
        contaminants, minimizes implementation time, and is the most cost-effective  RAA-1 was not
        chosen because lt would  not provide adequate protection of human health and aquatic
        of I± T TPlyATh. A^ARS- RAA'2 WaS 6liminated because * would not be
        life   RAA ^"L ' ^ f^-4 W^ diminated beCaUSe they WH^1  ^t protec
        hfe.  RAA-5 was eliminated because it would not be cost-effective. RAA-6 was eliminated

                                             to five times longer
9.
                                       .                                      . -
If an innovative technology was chosen, why?


An innovative technology was not chosen to remediate tailings and waste rock. An innovative
10.
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the thSe criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include tljie following:

       •      Biodegradation was eliminated because it^^ would not be effectivib for inorganic
              contaminants such as arsenic and lead.                       [
       •      Soil flushing was eliminated because solvent loss during the recovery process
              potently could contaminate the environment. In addition, regiilatory agency
              approval would be difficult to attain                       *    CI^aSency
                                            -4-
                                                                                  1047

-------
1L
•      Pyrometallurgical reprocessing was eliminated because no space exists to build a
       smelter, and disposing of generated slag would be difficult.
•      Hydrometallurgical reprocessing (chemical leaching) was eliminated because of
       potential implementation difficulties.  Site metals are present in an insoluble sulfide
       form, which would require oxidation prior to leaching, and oxidation technologies for
       sulfides have not been developed fully.                                      j-,
•      Pyrolysis was eliminated because the technology would be expensive and not readily
       available, and implementation  would be difficult due to site topography.
•     ' In situ vitrification was  eliminated because the technology would be expensive and not
       readily available, and implementation would be  difficult due.to site  topography.
•      Soil washing was not incorporated into an RAA for detailed analysis, even though it
       was not eliminated explicitly during initial screening. Its effectiveness was questioned
       because the leaching process would be inhibited if metal contaminants were
       incorporated into crystal matrices.

Innovative technologies eliminated during the screening of the three criteria include the
following:

 •      Hydrometallurgic  reprocessing (froth floatation) (RAA-3) was eliminated because it
        would not be cost-effective in comparison to other alternatives that  provide similar
        levels of protectiveness (on-site consolidation and removal and off-site disposal).
            ^                                            '
 No innovative'technologies were eliminated during the  detailed analysis.


 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

 The most heavily weighted criteria used to select a standard technology were cost-effectiveness
 and protectiveness of human health and the environment.  One innovative technology,
 hydrometallurgic reprocessing (froth flotation), was eliminated because it would not be cost-
 effective.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?   What risk level was selected to establish .cleanup goals?
   1048
                     Contaminant,
                                  Cleanup Level (rag/kg)
                                                                 ARAR or Other Basis
                 Carcinogens
                 Arsenic
                                            130
                                                                         Risk8,
                 Noncarcinogens
                 Lead
                                            500
                                                                    OSWERb, Model0
               The action level for arsenic was determined based on a target cancer risk level of 10'5.
               Remediating arsenic to a level that reflects a cancer risk level of 10"6 (11 mg/kg) was
               proposed initially, but this level was expected to be impossible to reach, since the
               geometric mean background levels were greater (13 mg/kg).
                                               -5-

-------
                                                                           •-       .

                 'Office of Solid Waste and Emergency Response Directive No. 9355 4-02

                                                           esdmates *)»* lead Iev^ in children
                                                           reSUlt of ^ "odel was in accordance
                           technohgy eiimin^^                            Va
         technology was chosen, could it meet the cleanup goals?

         No innovative technologies were eliminated because of cleanup goal Tie standard
         technology selected could meet cleanup goals.                   • •! '     sranaaM
  14.
Were treatability studies conducted on the innovative technology or standard technology?
                                various fixative alternatives and reprocessing technologies.  These
                    ic ,nH      i «  Otatl°n W3S ^ best suited reProcessirig technology for use on a
                    is and several fixation treatments remove metals from leachates.
 15.    What measures/criteria were used to compare alternatives?


        The following measures were used to compare the alternatives:

               Total cost
               Permanence
               Time to design/cbnstruct/operate


 16.    How are alternatives compared?
                                                                                      .
       longer implementation time and much higher cost.               ™*f*a. oecause ot its
17.


                                           -6-
                                                                             1049

-------
                               Chemical Sales Co., OU-1
                                  Leyden Street Location

                                     Denver, Colorado
                                         RegionS
GENERAL SITE INFORMATION.

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       1,1,1-Trichloroethane 1        ,
       Trichloroethene      0.95
       Tetrachloroethene    80

       Table 5-1 presented on page 5-2 of the FS
       provides a list of contaminants detected in
       soils. The units, however, are presented as
       ug/L and the contaminants do not coincide
       with those listed in the ROD as
       contaminants of concern.
             Site .History
NPL Proposed:
NPL Final:
FS:
ROD:
6/88
8/90
2/91
6/28/91
             Background

PRP-lead
PRPs:  Chemical Sales Co., Interstate
       Distribution Center Associates
       (ICDA), Ltd.
FS prepared by: Engineering-Science,
       Inc.
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        •      Approximately 225,000 cubic yards of soil
        What type of site is this?

        Chemicals and Allied Products. This site was used as a product warehouse. The site
        contained warehouse, tank farm, and fenced yard, and is located in an industrial area.
        •Previous land use may have included landfilling activities between the mid-1950s and the early
        1970s.                                                     .
   1050
                                              -i-

-------
TECHNOLOGY SELECTION                                          !

4.       What standard technologies were considered for selection in this F&?
                                                                 , -    . |   • '"
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                  .            i

       Access restriction:     Fencing, land use controls (deed restrictions~"Industry Only Use",
                             removal/relocation of structures, excavation restrictions)
       Containment:          Clay cap, asphalt/concrete cap
       Physical treatment:     Soil spreading (evaporation)
       Thermal treatment:     Incineration
       Disposal:              Excavation, off-site hazardous waste facility
6.
                                                                   .              .
       Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification, and screening of technically
       feasible technologies were:
                                                                      i,               •
       Biological treatment:  Biological slurry reactors, in situ aerobic degradation, in situ anaerobic
                            degradation
       Phys/Chem treatment:  Soil washing with chemical oxidation, in situ surfactant-enhanced soil
                            washing, vapor extraction
       Thermal treatment:    Low-temperature thermal ,desorption, in sito radio frequency heating
                                   ,.   •               --                 •               • •   •-
      What was the cost estimate for the innovative technology?          '               '
               .      •       .   .   :          .  .    ,  • .                 |

      During the initial screening process, in which technically feasible technologies are identified
      (prior to the formulation of RAAs), the FS does not quantify costs. ^e:r the RAAs have been
      formulated, costs are estimated as part of a three-criteria screening prbcesis (effectiveness
      implementability, and cost) to identify alternatives that merit a more detailed evaluation ' The
       Stl      GOStS theD m recalculated during an evaluation based on npe criteria established by
                               '                                      '               •    '
               Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
Soil vapor extraction/ground water
extraction and treatment
Soil vapor extraction/ground water
extraction and treatment
Soil vapor extraction/ground water
collection and treatment
Estimated Costs
3 Ciiteria
$2,886,400
$3,391,000
$2,452,0)0
•'•'•, - -2- ' - ' ';:
9 Criteria
$1,922,000
eliminated
$2,031,000
•f '-r\
                                                                                         1051

-------
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-6
Scenario 1
RAA-6
Scenario 2
.Standard Technology
No action
Institutional actions (fencing, land use
control, well restrictions, public ,
awareness)/point-of-use ground water
treatment
Additional ground water treatment
Additional ground water treatment
Estimated Costs
3 Criteria
, $769,210, %
$605,000
$1,763,000
$769,469
9 Criteria ;
$301,000
eliminated
j
eliminated
eliminated
 8.      If a standard technology was chosen, why?

        No standard technology was chosen
 9.      If an innovative technology was chosen, why?

        RAA-5 reduces the toxicity, mobility, and volume of contaminants in soil through vapor
        extraction. Soil vapor extraction pilot tests were carried out at the site.  Based on the high
        VOC removal rates, large radius of influence, and homogenous nature of the soil, the results of
        these tests indicated that vapor extraction is extremely effective in removing site contaminants.
        Release of emissions from this treatment would be negligible and would pose minimal risk.
        Vapor extraction was selected to eliminate the need for excavation. Excavation would cause
        disruption to buildings at the site. All RAAs proposed the same soil treatment technology:
        vapor extraction.  Therefore, an RAA was selected based on ground water treatment
        technology effectiveness.
  Id.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages: during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the following:

         H     Soil washing with chemical oxidation was eliminated because the technology has not
                been proved.
   1052
-3-

-------
11.
         •      Biological slurry reactors were eliminated because the technology has not been proved
                for chlorinated contaminants.       ,
         •      In situ surfactant enhanced soil washing was eliminated because it requires very coarse
                soils and additional ground water treatment to remove/separate surfactants.  Also  the
                technology has not proved on a full scale.
         •  ,    In situ aerobic biodegradation was eliminated because it has been proved only in an
                aqueous laboratory reactor. It has not been proved for soils applications and would
                not degrade tetrachloroethene.
         •      In situ anaerobic biodegradation would degrade tetrachloroeithene and would produce
                vinyl chloride as a degradation product.  It also would be difficult to maintain
                anaerobic conditions in situ.
         •      Low-temperature thermal desorption was eliminated because: large quantities of soil
                would be excavated. Excavation would disrupt existing buildings and structures and
                volatile contaminants could lead to unacceptable worker exposures.
        •.      In situ  radio frequency heating was eliminated but no explanation was provided.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:
            •  '    '          -'•;•'•'..••.          :        •.    ',[.-.      •'.   •    •
        •   .   None-       /   •''-.'      .  . •  '        '•   • -       i-     • •       '•'-..'
                                                                     • 'i ''     -.",'',

        Innovative technologies eliminated during the detailed analysis include the following:
        '  i                    *          ''                       l                .           "     '
        •      None                                •"'•"•              i                  -
Which of the nine criteria were weighted most heavily in selecting tfie technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so
which criterion? Which of the criteria supported the use of a standard technology?

Soil vapor extraction was the only remaining soil technology. Therefore, the nine-criteria
screening had no impact on the choice of technology.
12.
                         ,   ,          ? Ifth£ CleaWP 8°al WOS based <^ an ARAR, what was that
                    risk level was selected to establish cleanup goals?
                    Contaminant
                                 Cleanup Level (ppm)
                Carcinogens
                Tetrachloroethene
                Trichloroethene
                1,1,1 -Trichloroethane
                Noncarcinogens
                1,1 -Dichloroethene
                1,1 -Dichloroethane
               Vinyl Chloride
                                               0.150
                                               0.115
                                        4.400
                                        0.105
                                        0.090
                                        0.012
                                            -4-
                                                                ARAR or Other Basis
                                                               ; MCL
                                                                        MCL
                                                                       MCL
                                                                       MCL
                                                                    10I6 risik level
                                                                       MCL
                                                                                 1053

-------
13.
                                                               ARAR or Other Basis
                                Cleanup Level (ppm)
       Note- Soil remediation cleanup levels were determined based on the leaching of soil
       contaminants into the underlying ground water.  Cleanup levels were calculated by
       multiplying the acceptable concentration of leachate from the soil by the site-specific
       partition coefficient for the soil (based on batch and column adsorption studies for OU-
       2 at the site).                                      ':'.-'•


Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•     In situ anaerobic biodegradation

Standard technologies eliminated because of cleanup goals include:

•     None   -.'"'•
 14.     Were, treatability studies conducted on the innovative technology or standard technology?

        Successful pilot tests were conducted for soil vapor extraction.  VOCs were rapidly removed
        from the subsurface.                                              .
 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Proven reliability
             Time to design/construct/operate
             Capital costs vs. operational costs
             Impact on nearby populations
 16.    How are measures compared?                                       •

        The lack of proven reliability was used to eliminate a number of technologies during the initial
        screening.  The time taken to reach cleanup levels using RAA-5 (less than 10 years) versus
        RAA-3 (30 years) was a primary factor in choosing RAA-5. Operational and maintenance
        (O&M) costs and capital costs are compared for RAA-3 and RAA-5. It is noted that RAA-3
        has lower capital and O&M costs, however, because of the longer implementation time of
        RAA-3, present worth costs are similar.  The impact on local populations (and site workers) is
        mentioned as a benefit of in situ technologies such as vapor extraction.
  1054
                                               -5-

-------
17.
 What technical considerations were factors in selecting a remedy?,  Were technical
 considerations primary in the selection of the remedy?                 "cnnical

                                                               .1   .   •

 Pilot tests on soil vapor extraction at the site indicated that the soils Within the test area
 rda^y homogenous  and that there is a large radius of influence  (due ,o Sati

ZL  8   f f ?B?ae**aX* Soil vaP°r extra<*°" is therefore extremely sui  Tte
dominance of sand and permeable soils on the site, and the relatively low organic content of
the soils are both factors which improve vapor recovery.            I


Consideration was given to preserving existing structures located on the site For th« r^™
                                                                                        *
                                          -6-
                                                                              1055

-------
                                 Denver Radium Site
                                          OU-8

                                     Denver Colorado
                                         Region 8
GENERAL SITE INFORMATION
1, What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?
Maximum concentrations of principal
contaminants were:
Soil(mg/kg)
Equivalent radium-
226 cone. 570 pCi/g
Arsenic 598
Lead 1,260
Molybdenum 48,800
Selenium 7,980

Site History
NPL Proposed: N/A
NEL Final: 9/8/83
f\ //\1
FS: 9/91
ROD: 1/28/92
Background
PRP-lead
PRPs: N/A
FS prepared by: Colorado Dept. of
Health1

 2.      What volume of material is to be
        remediated?                                                     ,

        The volume of material to be remediated included:

        •      49,000 cubic yards of soil                        ,                  .


 3.     What type of site is this?                                    ,

        Mining.  The site is a former minerals processing facility located in an urban area. The land
        use around the site is commercial/industrial.
  TECHNOLOGY SELECTION   ,

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies considered during the identification and screening of technically feasible
         technologies were:            -

         Access restriction:     Fencing, deed restrictions                 ,
         Containment:          Capping, subsurface barriers                    •      .
         Chem/Phys treatment:  Stabilization (bitumen or asphalt, cement, resins), mechanical
                              separation, physical concentration
                                                        'ft-,
    1056
-i-

-------
5.
       Thermal treatment:    Incineration
       Disposal:             Excavation, off-site disposal, on-site disposa
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                            N

        Biological treatment:  Biological treatments (unspecified)
        Phys/Chem treatment: In situ solution mining, sulfuric acid leachinji/sulfate conversion soil
                             gas extraction                             i                  '
        Thermal treatment:    Ex situ vitrification (electric furnace fusion, lotaiy kiln), in situ
                             vitrification
6.
       What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       fcTl  t H  fT      ' rf*AA»>. the FS does not quantify costs.  Met the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  A three-criteria screening of the RAAs was not carried out in this FS.  Estimated
       costs were calculated during an evaluation based on nine  criteria established by the NCP.

                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
======
Alternative
RAA-4
RAA-7
'
Innovative Technology
Facility removal/excavation/on-site
consolidation/vitrification/compacted
soil cap
Facility removal/excavation/mechanical
separation/on-site chemical leaching/
backfilling with decontaminated soil/
off-site disposal
. ' •
. ' • • ' '
Estimated Costs"
3 Criteria
N/A
i
1
N/A
i •
•
9 Criteria
$38,300,000
($42,400,000)
$43,300,000
($47,400,000)
     "Costs in parentheses are for costs presented in the Proposed Plan.
                                                                                       1057

-------
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-5
RAA-6

Standard Technology
No action
Restrict site access (fencing, deed
restrictions)/excavation/on-site
disposal/off-site disposal/monitoring
Facility removal/excavation/on-site
consolidation/clay cap/institutional
controls
Facility rempval/excavation/stabiliza-
tion/on-site disposal/compacted soil
cap
Facility removal/excavation/off-site
disposal/backfilling with clean soil
Estimated Costs*
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$323,000
($400,000)
$6,300,000
($6,300;000)
$15,000,000
($19,100,000)
$26,600,000
($30,700,000)
$36,800,000 to
$48,800,000
($40,900,000)
         •Costs in parentheses are for costs presented in the Proposed Plan.
 8.      If a standard technology was chosen, why?

         In the Proposed Plan, RAA-6 was the selected remedy. Following public comment on the
         statutory preference of the Comprehensive Environmental Response, Compensation, and
         Liability Act (CERCLA) for onsite remedies and for remedies that reduce toxicity, mobility, or
         volume through treatment, a reevaluation of alternatives was initiated.  Following the
         reevaluation, RAA-5 was selected.  Both alternatives attain the threshold criteria; however,
         stabilization appears, based  partially on new information, to be preferred given the balancing
         criteria The selected remedy protects human health and the environment through excavation
         and removal of contaminated soils at part of the site, and consolidation and stabilization of
         these soils and other contaminated soils at the site.  The selected remedy reduces site risks to
         potentially exposed populations by stabilizing and capping the contaminated soils. The site
         will not pose a threat to nearby residents and workers after remediation is completed.  The
         selected remedy attains the health protection requirements of CERCLA and the National
         Contingency Plan (NCP).  The selected remedy immobilizes the source of  ground water
         contamination. Restoration of ground water quality is expected to occur through attenuation
         over time  Of all the alternatives, the selected remedy provides the best overall effectiveness
         proportional to its cost.  The selected remedy  provides long-term effectiveness and permanence
         by reducing the radon emanation of the contaminated soils, shielding gamma radioactive
         material to near background levels, and reducing the potential for contaminants to leach to
         ground water.  The selected" remedy utilizes treatment to reduce contaminant mobility. The
  1058
-3-

-------
        selected remedy effectively reduces the hazards posed by all of the contaminants at the site at
        a lower cost than the other alternatives.                            i
                        -•'•-.    .'_'•'             •'    ,     '•-        |  . ' .        :  •
    '  ,            '        :      -        -   .                .          ; -_^                     . ,
9.      If an innovative technology was chosen, why?                      I

        An innovative technology was not chosen.
                        •               .._-."      '            "       |.,   -       .          .
                          -'•.•.                  '      -        .      i      '.     ',."'".'••
10.     If an innovative technology was not chosen, why[not? At what stage v?as the innovative
        technology eliminated?

      -  Innovative technologies could be eliminated From the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the iW criteria of
        effectiveness, implementability, and cost; or during the detailed evaluajtiorii.

       Innovative technologies eliminated during the initial screening include the following:

        •      Biological treatments were eliminated because although certain aromatic organic
              compounds are biodegradable  at dilute levels, heterocyclie organics and polycyclic
              aromatics (such as those observed in contaminated soil at  the siite) are generally less
              biodegradable or essentially non-biodegradable.  Furthermore, high concentrations of
              heavy metals might adversely  affect biodegradation of some contaminants.
       •      In situ solution mining was eliminated for the following reasorls:  Bench-scale
              chemical extraction treatability studies performed in support of this FS showed
              removal efficiencies of greater than 90 percent for uranium; however, removal
              efficiencies were lower for many of the contaminants present on the site, e.g., thorium-
              230. While the studies indicate that the extraction process can be modified to attain
              greater than 90-percent removal of thorium-230, the process studied involves in-plant
              treatment of the soil after particle size reduction rather than in situ treatment. Further
              the treatability study proposed  is a staged, sequential treatment technology requiring
             , the use of many hazardous reagents.                         !
       •     Ex situ vitrification was eliminated because the two. processes (electric furnace fusion
             and rotary kiln) are considered to be technically unfeasible because: of the lack of a
             suitable facility, uncertainty with environmental control of the process, plus problems
             of dismantling and disposing of a potentially radioactively  contaminated process
             facility.
       •     Soil gas extraction was eliminated for the following reasons: This technology would
             not be successful for treating semivolatile contaminants at the site (e.g., anthracene
             chrysene, and phenanthrene). These polynuclear aromatic compounds are relatively
             nonvolatile, having minimal vapor pressures at temperatures of less than approximately
             200 C. Accordingly, insignificant concentrations of these species are present in  soil
             gas at ambient temperatures (i.e., approximately 20°C) and, therefore, soil gas
             extractionis not an(effective technology  for such contaminants.!  Preliminary field
             measurements indicate that VOCs are present over some relatively large subsurface
             soil areas on the property. Additionally, windrowing and aerating VOC-contaminated
             soil can be accomplished  during the removal/disposal alternative. Lastly, the
             technology would not eliminate radioactive contaminants.
                                             -4-
1059

-------
      Innovative technologies eliminated during the screening of the three criteria include the
      following:  .            •                              .   .

      •      None

      Innovative technologies eliminated during the detailed analysis include the following:

       •      In situ vitrification was eliminated because the longer time period required to
              implement RAA-4 would allow for exposure of workers to gamma radiation., This
              concern stems from the length of exposure and the proximity to the gamma radiation
              sources.  The technical feasibility of adequately dewatering the site to facilitate in situ
              vitrification was of "significant concern." In addition, the implementability of the
              technology on a large scale is uncertain since the technology is innovative and
              experience with large-scale implementation is very limited. Further, stabilization is
              expected to achieve the same results for less cost.
       •      Sulfuric acid leaching/sulfate conversion was eliminated because RAA-4 (excavation
              and off-site disposal) would achieve similar results for less cost and without the added
              uncertainty  of operating a chemical process facility on the site.
                                                         J iL
11     Which of the nine criteria were weighted most heavily in selecting the technology? .Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of,a standard technology?

       The reduction of toxicity, mobility, or volume through treatment, and the cost balancing
       criteria were weighted most heavily in selecting a technology.  RAA-5 (stabilization) is more
       feasible than RAA-4 (vitrification) because similar results  are expected for less cost; and RAA-
       6 (excavation and off-site disposal) is more feasible then RAA-7 (onsite chemical leaching)
       because similar results are expected for less cost arid without the added uncertainties of
       operating a chemical process facility. RAA-5 satisfies the statutory preference for treatment by
       reducing mobility.  RAA-6 would not satisfy this preference. RAA-6 is estimated to cost
       $10.2 million to  $22.2 million more than RAA-5, the range indicating the uncertainty
       associated with the disposal cost at a location which is currently the only commercially
       available facility.  RAA-6 may not be cost effective in proportion to its overall effectiveness
        and it does not appear to be as cost effective as RAA-5.
 12.     What cleanup goals were selected?  If the cleanup goal was basedfon an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level
ARAR or Other Basis
Carcinogens
Radium-226
Gamma radiation
Radon progeny
Uranium-natural •
5/15 pCi/g"
20 microRoentogens/hr
(above background)
0.02 working levels
75 pCi/g
40 CFR 192.12(a)
40 CFR 102.12(b)(2)
40 CFR 192.12(b)(l)
U.S. DOE 5480.1
   1060
-5-

-------
                      Contaminant
                  Thorium-230 in soil
                  Arsenic
Cleanup Level
   42 pGi/g
                                               160 mg/kg
                                                                  ARAR or Other Basis
                                                                  Calculated from radium
                                                                          levels
                             Risk
                 Noncarcinogens
 73.
        For carcinogens, an excess upper bound individual lifetime cancer risk of between 1Q-4 to lO"6
        was acceptable.  For noncarcinogens, a Hazard Index less than or equiil to 1.0 was acceptable.
                                                      of the cleanup goal>? Could ^standard
        Innovative technologies eliminated because of cleanup goals include:  \

        •      None        •        "      ' .               •,...••'    !
                                                                       - i

        Standard technologies eliminated because of cleanup goals include:

        •'      None      "          ,         '.'.'•    •        -•
14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were conducted on'the following standard technologies:

       "      TTeay>Mty sto&es of physical separation were conductedto test the technical
              feasibility of screening the soils to reduce the volume of radioactive soils.  The results
              obtained (by both Colorado Department of Health and Shattuck|Chemical Company  a
              prev10us owner of a portion of the site), indicate significant vokme reduction might be
              technically feasible. The studies showed that for some of the contaminated soils  wet
             .screening separates the contaminantssuch that only theTine particlesrequire    '
              management as contanunated material, thereby reducing the volume of contaminated
              matenals.  Since the treatability studies were not extensive enough to definitively
              detennme the overall cost, effectiveness, and implementability oif screening, the
              ootential volume reduction that screening could account for was not factored into the
             Treatability testing of stabilization of site soils vvas conducted bir the Shattuck
             Chemical Company. The tests showed that stabilization immobilized the contaminants
             reduced radon emanation (to below the 40 CFR 192 Subpart A'topa-1 stSoS
             pCi/m /s) and resulted in a concrete-like stabilized mass. Large-scale pilot testing
                                            -6-
                                              1061

-------
             would be necessary prior to full scale implementation in order to refine design
             parameters and as additional verification of the implementability of the technology.

      Treatability studies were completed on the following innovative technologies:

      •      Bench-scale chemical extraction treatability studies performed in support of in situ
             solution mining for this FS obtained removal efficiencies of greater than 90 percent for
             uranium, however, -less than that for many of the contaminants present on the site, e.g.,
             thorium-230.  While the studies performed  indicate that the extraction process can be
             modified to attain greater than 90-percent removal of thorium-230, the process studied
             involves in-plant treatment of the soil after particle size reduction rather than in situ
             treatment.  Further, the treatability study proposed is a staged; sequential treatment
             technology requiring the use of many hazardous reagents.  The physical character of
             the contaminated soil in place at the site is not suitable for the type .of contact required
             to achieve appropriate removal efficiencies for all target contaminants.  There are
             significant uncertainties with respect to the ability to intercept the hazardous solutions
             bearing dissolved contaminants with drawdown recovery wells.  The inability to
              intercept such solutions could result in increased  ground water degradation.
       •      A bench-scale test of vitrification was conducted. The test showed that over a period
          '    of about 6 hours the soils melted. After cooling, the mass assumed a glass-like
              structure, which  effectively immobilizes heavy metals and radioactive contaminants.
              Larger scale pilot testing would be necessary prior to full-scale implementation in
              order to refine design parameters and as additional verification  of the implementability
              of the technology.                                 ,       	     ,, .    .,
       •      Treatability studies were performed  to explore the feasibility of utilizing sulfuric acid
              leaching/sulfate  conversion to remove radioactive contaminants from site soils.
              Chemical treatment was demonstrated as a means of removing  the contaminants  from
              the soils, enabling the bulk of the contaminated soils  to be placed back on the site.
              The contaminants would be concentrated, resulting in a smaller volume of higher
              toxicity materials, which would be disposed of off site.
75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Preference for treatment (vs. containment)
             Waste left in place/institutional control


 16.     How are measures compared?

        RAA-5 (stabilization)  satisfies the statutory preference for treatment by reducing mobility
        through treatment. RAA-6 (excavation and off-site disposal) would not satisfy this preference.
        In comparing RAA-5  and RAA-6, it was discussed that stabilization wastes would remain on
        site, limiting future land use and requiring long-term monitoring and maintenance.
1062
-7-

-------
17.
What technical considerations were factors in selecting a remedy?
considerations primary in the selection of the remedy?
                                                  '
                                                                    Were technical
       d                                        Selecting a rcmedy- * silu soluti°« "Amg was
       ehimnated, however, because the physical character of the contaminated! soil in olace at the
       s^ ,s not suitable for the type of contact required to achieve "iWR^^SSSiL
       for aH target contarmnants.  Further, there are significant uncerSnties with respect to ie
       abihty to mterceprthe hazardous solutions bearing dissolved contaminants with drawdown

                         ^   l° '*                    C°uld resullt fa -creas - g-unTwater
                                          -8-
                                                                            1063

-------
                                  Denver Radium Site
                                          GU-9

                                     Denver, Colorado
                                         Region 8
GENERAL SITE INFORMATION
L
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil (rag/kg)

       Lead
       Arsenic
       Zinc
              35,800
              490
              32,050
 2.
 What volume of material is to be
 remediated?
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                    N/A
                    1983
                    7/31/91
                    12/31/91
             Background

EPA Fund-lead
PRPs:  U.S. Bureau of Mines
FS prepared by:. URS Consultants,
       Inc.
        The volume of material to be remediated included:

        •      16,540 cubic yards of soil


 3.     What type of site is this?
                                                                 e
        Mining. An abandoned brick plant located in an industrial area.


 TECHNOLOGY SELECTION

 4.     What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
         Access restriction:
         Containment:
         Chemical treatment:
         Disposal:
                      Deed restrictions, zoning
                      Capping (clay, soil, asphalt, concrete, multimedia synthetic membrane)
                      Solidification/stabilization
                      Excavation, disposal (off-site, on-site)
   1064
                                              -i-

-------
 5.
  Was an innovative technology considered in the FS?  If so, which technology?
 Innovative technologies considered during the identification and screening of technically
 feasible technologies were:                                       !          ••
 Thermal treatment:    Vitrification                               i    .
 6.
7.
 What was the cost estimate for the innovative technology?
      ''                   '      - .        -                      -  !
 During the initial screening process, in which technically feasible tecllnologies are identified
 foZM H6 fT    °n °f R^As)'.the FS does not I™*"? costs. After the RAAs have been
 formulated costs are estimated as part of a three-criteria screening process (effectiveness
 implementabihty, and cost) to identify alternatives that merit a more detailed evaluation 'The
 estimated costs then are recalculated during an evaluation based on nine criteria established by
 I? ff   long-term effectiveness and permanence; short-term effectiveness; compliance with
 ARARs; protectiveness of human health and the environment; reduction in contaminant
                                                 state/suPP°« ^ncy acceptance; and
RAAs were renumbered in the ROD; these changes are presented parenthetically below.
No innovative technologies were incorporated into remedial alternativels

How did the cost(s) compare to standard technologies?
          Cost Estimates for RAAs That Include Standard Technologies
                    (selected remedial alternative is in bold)
Alternative
RAA.l
RAA-2
\
RAA.-3
(RAA-2)
>
RAA-4
(RAA-3)
RAA-5
(RAA^4)
RAA-6
(RAA-5)
11
Standard Technology
No action
Demolish existing structures/clay-soil
cap
Utilize concrete floor and asphalt
parking lot as cap/clay cap surrounding
areai
Utilize concrete floor and asphalt
parking lot as cap/soil cap
surrounding area
Excavatiori/off-site disposal/institutional
controls
Excavation/solidification-stabilization/
on-site disposal/institutional controls
Estimated Costs
3 Criteria
$174;300
$9,330,200.
$2,65<),000
| . •
$1,701,900
•- • i
$10,392,200
-- i
$9,912^000
9 Criteria
$174,300
eliminated
$2,656,000
$1,702,000
$10,392,200
$9,912,000
                                                                                        1065

-------
8.     If a standard technology was chosen, why?

       RAA-4 was chosen because it eliminates direct contact with, and inhalation or ingestion of
       contaminated soils at the site through a combination of engineering, capping, and institutional
       controls. Long-term maintenance is required to ensure long-term effectiveness.  The chosen
       alternative was preferred because it takes the least amount of time to implement and involves
       the least disturbance of contaminated materials, thereby presenting the least nsk to on-site
       workers and the surrounding communities.  The preferred alternative utilizes standard
       technologies and is readily implementable.  The chosen alternative complies with all ARARs
       and is cost-effective.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not selected.
 JO.    If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                                 .

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages: during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

         •      In situ vitrification was eliminated because it would not be as available or
                implementable as stabilization/solidification.  Also the cost would be much greater
                than for stabilization/solidification.  Further, laboratory and pilot testing would be
                necessary to demonstrate its effectiveness.

         Innovative technologies eliminated during th& screening of the three criteria include the
         following:      •

         •      None

         Innovative technologies eliminated during the detailed analysis include the following:

         »      None                           •                             ,         '
         Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion? Which of the criteria supported the use of a standard technology?

         Short-term effectiveness and cost were the criteria weighted most heavily hi selecting a
         remedy. While all other action alternatives offered comparable protection and long-term
         effectiveness, the chosen alternative provides the best short-term effectiveness and is the lowest
         in cost.
   1066
                                                 -3-
                                                                                                               [,,.

-------
   12.
  13.
75.

                           /                                 WaS bon an ARAR, what was that
                       risk level was selected to establish cleanup goals?                       .     •
                       Contaminant     |  Cleanup Level (mg/kg) j  ARAR or Other Basis
                  Carcinogens
                  Noncarcinogens
                  ••^	

                  Zinc
                Tor carcinogens, an excess upper bound individual lifetime
                to 10  was acceptable.  For noncarcinogens, a Hazard Index
                was acceptable.
                "Interim Guidance on Establishing Soil Lead Cleanup Level'
                OSWER Directive 9355,4-02, September 7, 1989.    .  '   '
                                                                       cancer risk of between 10"4
                                                                        less man or equal to 1.0

                                                                        at Superfiind Sites,
        Was the innovative technology eliminated because of the
        technology meet the cleanup goals?
                                                             cleanup goals?  Could the standard
        Innovative technologies eliminated because of cleanup goals include:

        •      None

        Standard technologies eliminated because of cleanup goals include:

        •      None
14.     Were treatability studies conducted on the innovative technology or,

        Treatability studies were not conducted.
        What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Cost-effectiveness   -                      .
  -;    .-.'.      Time to design/construct/operate


16.     How are measures compared?

       The chosen alternative was preferred because it is comparable in pr
       and long-term protection with all the other action alternatives but it p
       term effectiveness and is the least costly.  Containment was preferred
                                             -4-
                                                                           Risk*
                                                                         OSWER"
                                                                           Risk
                                                                      .Si andard technology?
                                                                  protqction, implementability
                                                                    provides the greatest short-
                                                                      over treatment
                                                                                           1067

-------
                                                                                                          -tfl
                                                                                                          u
       (solidification) because treatment would only reduce mobility without changing toxicrty, it
       would increase volume, and it would cost five times as much.  The soil cap was preferred over
       the clay cap since it is less costly. While excavation and off-site disposal was preferred by the
       City and County of Denver and a vicinity landowner, this option was dismissed since off-site
       disposal without treatment is the least preferred option under CERCLA. Finally the chosen
       alternative posed the least short-term risk and could be implemented in the shortest time.
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?

       No technical considerations were primary in  selecting a remedial alternative;
                                                                                                          •!,'
 1068
                                               -5-

-------
                                     Hill Air Force Base
                                            OU-3

                                Davis and Weber Counties, Utah
                                           Region 8
  GENERAT. srrc

  L      ^m^^L^^(.^^^
                                   °f
        Soil(mg/kg)


        Sodium hydroxide migration through soil was
        indicated   by  the  nH  *it r
        „„ j   •  •           pii>  alkalinity,  and
        conductivity of the soil.
2.
                   of material is to be remediated?

                   of material to be remediated
                                                                 Sit« History
                           NPL Proposed:
                           NPL Final:
                           FS:
                           Interim Action
                           ROD:
                                       Backgrciund
                          Federal Facility
                          PRPs: Hill Air Force Base
                          FS prepared by:  James M.
                                Montgomery
             No voiurne was provided, however, the site area is


           type of site is this?
                                 28,900 square feet.

     technologies were:

     Cbntainment:
     Physical treatment:
         during the identification and
screening
Asphalt cap
Tank removal
                                        -1-
             N/A
             1987
             9/91

             9/92
                                                                   £ind maintaining aircraft.
                                           of technically feasible
                                                                                  1069

-------
5.     Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically feasible
       technologies were:

       No innovative technologies were identified!.


 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified (prior
        to the  formulation of RAAs), the FS does not quantify costs.  After the  RAAsijiave been
        formulated, costs are typically estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  In this
        case, the estimated costs were calculated during an evaluation based on nine, catena established
        by the NCP.  No innovative technologies were  incorporated into RAAs.

                                                                                   . V
 7.     How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)                     v
            Alternative
          RAA-1
          RAA-2
        Standard Technology
Underground storage tank removal
Underground storage tank
removal/capping
                                                                        Estimated Costs
                                                                    3 Criteria
                                                                       N/A
                                                                       N/A
9 Criteria
    $0
                                                         $55,343
  8.      If a standard technology was chosen, why?

         RAA-2 was selected because it protects human health and the environment since it prevents
         exposure of receptors to contaminated soil by eliminating human dermal and inhalation contact.
         Capping also reduces the rate at which sodium hydroxide migrates to the water table. Reducing
         vertical migration will not reduce the concentration of sodium hydroxide, but it will reduce the
         volume and mobility of leachate reaching the water table. This provides long-term protection as
         long as the cap is kept intact. A substantial reduction in contaminant mobility will be achieved
         by reducing infiltration to the site, the driving force for downward contaminant migration. The
         equipment required for construction is readily available and reliable. This is an interaction;
         therefore, the chosen alternative provides a preliminary step in achieving action-specific ARARs
         for soil, which will be addressed more fully in the final remedial action for OU-3.  A waiver will
         be invoked for RCRA closure requirements since this is an interim action.  It is the most cost-
         effective option.
   9.      If an innovative technology was chosen, why?

          An innovative technology was hot selected.
   1070                                    .2.

-------
                    ive technology was not chosen, why not? At what stage was the innovative technology


              itjve technologies could be eliminated from the remedial technology selection process at
              stages:  during  the  initial screening;  during the screening' of  the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

." • '•    *      None      -  -    '      .        • •       -•'-,.   :|..    ..  •        • •  •

        Innovative technologies eliminated during 'the screening of the three crilleria include the following:

        •      None                                                   |
                       •                                                \
         • -        '           -                      -       '        .  '   "I"   ,     ...
        Innovative technologies eliminated during the detailed analysis include the following:

        •      None,  ,      '.'•.'-..'    •               .-••"!'   •  •  -.  "     '           •"  '


11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so
       which criterion!'Which ofthecriteriasupported the use of a standard technology ?         '
                                -?d ** envir0nment ** reduction of contabikant mobility were the
       catena weighted most heavily in selecting a remedial alternative. RAX-2 was preferred because
                              selected? If the cleanup goal was based on an ARAR, what was that
                    risk level was selected to establish cleanup goals?

      Cleanup levels were not established. No contaminant-specific ARARs eiist for sodium hydroxide
      •mwl and potential ground water ARARs will be addressed in the final remedial alternative for

                    '  '     •    '   '                 '                  •  I   '
                            •                  •             '            i'
                                  1       '       •               «•'.'!••'         .' '• i   '    -
    •  Was the innovative technology eliminated because of the cleanup goals? Could the standard
      technology meet the cleanup goals?                            .                  wnaara

      Innovative technologies eliminated because of cleanup goals include:

      •      None

      Standard technologies eliminated because of cleanup goals include:

      •      None
                                             3                                            1071

-------
14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conduct? 1


75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:    ,

             Risk level achieved                               .
             Cost-effectiveness                                                    ,


16.    How are measures compared?                               !

       RAA-2 was preferred over RAA-1 because it would provide greater protection. RAA-2 eliminates
       human dermal and inhalation exposure to contaminated  soil and it prevents   the downward
       mobilization of contaminants.  RAA-1 would not provide as great protection since it would not
       reduce the mobility of contaminants.  RAA-2 also represents the cost-effective option because if
       interim action is not taken, contamination will continue to migrate into soil and/or ground water,
       probably increasing the ultimate remediation  cost of OU-3.                     .


77.    Wliat technical considerations were factors in selecting a remedy? Were technical considerations
       primary in the selection of the remedy?

       No technical considerations were primary in  selecting a remedial alternative.
D

 1072
                                               -4-

-------
                                Idaho Pole Company

                                   Bozeman, Montana
                                       Region 8
GENERAL SITE INFORMATION
1.      What  were  the  principal  contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum   concentrations   of   principal
       contaminants were:

       Soil (rag/kg)

       Pentachlorophenol (PCP)    380
       Fluoranthene               12
       Benzo(a)pyrene             4.8
       Anthracene                8.1
       Pyrene                     10
       Benzo(a)anthracene          5.8
       Benzo(b)fluoranthene        13
       Benzo(k)fluoranthene        6.7
       Benzo(g,h,i)perylene         2-2
       Chrysene                   10
       Indeno(l,2,3-cd)pyrene       2.7
      Phenanthrene               46
      TCDD TE                  0.00179

      Sediments (mg/kg)

      Pentachlorophenol          25
      Fluoranthene               1.7
      Benzo(a)pyrene             0.72
      Anthracene                 0.52
      Pyrene                     20
      Benzo(a)anthracene          4.6
      Benzo(b)fluoranthene        1.2
      Benzo(k)fluoranthene        1.9
      Benzo(g4i4)perylene          0.27
     .Chrysene                   7.1
      Indeno(l,2,3-cd)pyrene       0.26
      Phenanthrene               2.3
      TCDD TE                  0.0342
                                                   ;         jSite JHislory

                                                 NPL Proposed:        1984
                                                 NPL Final:           1986
                                                 FS:              I    4/92
                                                 ROD:            I    9/92
                                                                 i     " "
                                                            Background

                                                 EPA Fund-lead    !
                                                 PRPs:   The Idaho Pole Company,
                                                       Burlington Northern Railroad
                                                 FS prepared by: MultiTech Services,
                                                       MSE,Inc.
                                         -1-
                                                                                   1073

-------
                                                        •
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:                                                   • -J\

        •      2,683 cubic yards of sediment
        »      39,304 cubic yards of soil                                                                  ''  \

                                                                                                            I
                                                                                                            I •
3,      What type of site is this?                                                              '-•.'..',.

        Lumber and Wood Products.  An active wood treating facility in a light industrial area.

                                                                                                       •     i.
                                                         •
TECHNOLOGY SELECTION                                                                                ;

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible             '
        technologies were:                                               •.-••'

        Soil/Sediment

        Access restriction:    Fencing, land use control
        Containment:          Capping (asphalt, clay and soil, concrete, revegetation)
        Chemical treatment:   Fixation/stabilization
        Thermal treatment:    Incineration (rotary kiln, fluidized bed, plasma fusion, infrared)
        Disposal:             Excavation, disposal (on-site, off-site)
                                                                              •  .        ,      !

5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically feasible
        technologies were:

        Soil/Sediment

        Biological treatment:   Aerobic, anaerobic, land treatment, slurry phase, white rot fungus, in situ
                             bioremediation                    .
        Phys/Chem treatment:  Dechlorination,  oxidation/reduction, solvent extraction,  soil  washing,
                             steam stripping, air stripping, in situ soil flushing, vacuum soil venting
        Thermal treatment:    Pyrolysis, in situ vitrification                     ;


6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified (prior
        to the  formulation of RAAs), the FS does  not quantify  costs.   After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation. For this
        site, the estimated costs were  calculated during an evaluation based on nine criteria established
        by the NCP. Because some alternatives were eliminated between the three-criteria screening and

 1074
                                              -2-          •   -       .           •  •    •   •

-------
       the nine-criteria analysis, RAA designations changed. These changes are presented parenthetically.

                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)     | •
Alternative
RAA-5
(RAA-4)
RAA-7
(RAA-5)
RAA-6
RAA-8
RAA-9
RAA-10
.' ' . • ' /
Innovative Technology
Excavation/oily wood treating fluid'
recovery/solid phase (surface land)
biological treatment or slurry phase
biological treatment
Excavation/oily wood treating fluid
recovery/critical fluid solvent extraction
In situ soil flushing/in situ biological
treatment of residuals/land treatment
unit
Excavation/soil washing/ dechlorination
In situ soil flushing
In situ bioremediation
Estinnated Costs
3 Criteria
N/A
1
i •
• ' i
''\
N/A1
N/A
- i
i
, N/A
N/A
• • f
N/A
9 Criteria
$8,164,357 to
$12,816,185
$82,232,520
$10,841,429
eliminated
incorporated
into RAA-6
eliminated
7.      How did the cost(s) compare to standard technologies?          -    >,
       '-                    '        -                - •                f

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)     |
Alternative
RAA-1
RAA-2
RAA-3
(RAA-2)
RAA-4
1 (RAA-3)
RAA-1 1
RAA-12
Standard Technology
No action
Institutional controls .
Capping
Excavation/incineration (on-site or off-
site)
Excavation/on-site landfilling
Excavation/off-site landfilling
Estimated Costs
3 Criteria
N/A!
N/A
N/A
N/A
N/A
N/A
9 Criteria
$0
eliminated
$1,329,577
$63,000
to
$211,900,000a
eliminated
eliminated
       "Costs were developed for both on site and off site incineration options.
                                           -3-
1075

-------
8.     If a standard technology was chosen, why?

       A standard technology was not selected.         ,
                                                                                       \

9.     If an innovative technology was chosen, why?                     ,

       A combination  of two  innovative alternatives were selected to address contaminated soil and
       sediment. In situ soil flushing and in situ biological treatment (RAA-6) were chosen for treatment
       of soil and sediment under plant structures and excavation and biological treatment (RAA-5) were
       selected for  treatment of accessible soil and sediment. . Solid phase biological treatment was
       selected over slurry phase biological treatment because it has been proved at other hazardous
       waste sites.  RAA-6 is the only  soil alternative that can be implemented in the active plant area
       since it does not require demolition of existing structures and excavation of contaminated soils.
       Furthermore, it is the only alternative that allows continued operation of the plant while reducing
       exposures to within an acceptable risk range.  RAA-6 also will remediate soil under Interstate 90
       without the impractical replacement of the highway. RAA-5 was selected to treat the excavatable
       site soil and  sediment.  Solid phase biological treatment is a proven remediation technology that
       has met community acceptance at other sites, and is relatively inexpensive,. In addition, biological
       treatment is readily implementable in a surface land treatment unit.  Biological treatment of the
       contaminated soiysediment converts contaminants to nontoxic compounds and eliminates the threat
       of exposure through direct contact with or ingestion of contaminated soil/sediment. The remedy
       will be effective in the long-term because of the significant reduction in contaminant toxicity and
       mobility achieved through biological treatment of the soil/sediment.  All short-term risks can be
       readily controlled and no adverse cross-media impacts are  expected from the remedy.  These
       alternatives comply with all ARARs and  are cost-effective.  Implementation of these  alternatives
       will  result in long-term effectiveness by reducing residual carcinogenic risks to within  the
       acceptable risk  range through permanent treatment.


 10.    If an innovative technology was not chosen, why not? At what stage was the innovative technology
       eliminated?

       Innovative technologies could be  eliminated from the remedial technology selection process at
       three stages:   during the initial screening; during  the  screening of  the  three  criteria of
        effectiveness, implementability, and cost; or  during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        »       Air stripping was eliminated because it would not be effective given the low  volatility of
                the contaminants of concern.                                                     ,
        "       Pyrolysis-was  eliminated because.it would not be effective for the contaminants of
                concern.
        H       Vacuum soil venting  was  eliminated  because  it  would  not be  effective for the
                contaminants of concern.
        a       In situ  vitrification was eliminated because it would not be  effective or implementable
                given the site's shallow ground water.

        Innovative technologies eliminated during the screening of the three criteria include the following:

        «       Dechlorination  was eliminated  -because  "there would  be a potential for the  highly

 1076

-------
11.
              chlorinated dioxins to be reduced to lesser  chlorinated but more; toxic compounds."
              Furthermore, these technologies would be very costly and would not address PAHs that
              would remain in the waste stream and require further treatment.
       •      In situ bioremediation (as a stand alone technology) was eliminated because it is most
              successful for use in porous soil and the site's contaminated soil includes low porosity
              clay and silt layers.  Further, the activity microorganisms are veiy sensitive to changes in
              soil temperature, which varies seasonally at the site.           j
                      :                    '•••-.     '        i            '
       Innovative technologies eliminated during the detailed analysis include the following:

       •      Critical fluid extraction was eliminated because it would not reduce the toxicity, mobility,
              and volume of site  contaminants as effectively as the chosen alterative and  it would be
              more expensive.  This alternative also was  deemed  the most difficult to implement
            •  because  it would require a specially designed and constructed unit  to contain waste
              material  during treatment. A vendor is available,  but there might be delays in optimizing
              the processing. This alternative would require planning with the local government. The
              fate of extracted hazardous substances would be uncertain because  contaminants are
              concentrated in the  extract, but are not destroyed and may pose; residual risk.,
       •      Slurry phase bioremediation was eliminated because it has not beein proved  as effectual
              as  solid phase bioremediation.
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Whichof the criteria supported the use of a standard technology?

The criteria weighted most heavily in selecting a remedial alternative were cost, implementability,
and short-term effectiveness. While the chosen technologies are not as protective and do not offer
as much long-term  effectiveness and permanence as incineration  and critical fluid solvent
extraction, they are preferred because they offer appropriate protection and permanence and are
less expensive, pose less short-term risk, and are more easily implemented. Furthermore, only in
situ technologies could be implemented since it  is not practical to excavate soil/sediment.
12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
PCP
Total B2 PAHs
TCDDTE
48
15
0.001
Risk8
Risk
Risk
Noncarcinogens .
Total D PAHs
145
Risk
               Tor carcinogens, an excess upper bound individual lifetime cancer, risk of 10"6 was
               acceptable. For noncarcinogehs, a Hazard Index less than or equal to 1.0 was acceptable.
                                                                                            1077

-------
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:       '

        •      None

        Standard technologies eliminated because of cleanup goals include:

        *      None                                                 ,                  '


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Cost-effectiveness                                          .                  ,
             Proven reliability
             Preference for treatment (vs. containment)
             Impact on nearby populations


16.    How are measures compared?           '

       Short-term risk and cost-effectiveness were factors in selecting a remedial alternative. Incineration
       and  critical fluid extraction were eliminated for these reasons.  Incineration was not selected
       because it would have posed the greatest opportunity for impacts to site workers and nearby
       populations from air emissions. Furthermore, there would have been a risk associated with off-site
       incineration from the transportation of large quantities of hazardous substances over public roads.
       Critical fluid solvent extraction was not selected because it would also pose a threat to on-site
       workers if not properly designed or operated from air emissions and the use of pressurized solvent.
       Workers  also  might  encounter risks  from  concentrated  extract  and  treatment residuals.
       Incineration and critical fluid extraction were not preferred because they would be more expensive
       than the chosen alternative and would not  offer a proportional  increase in  benefit.   Proven
       reliability also played a role in selecting a remedial technology. Solid phase biological treatment
       was selected over slurry phase biological treatment because it has been proved at other hazardous
       waste sites. The choice of a remedial alternative also reflects a preference for  treatment over
       containment; capping was  not chosen because it is  less protective of human health  and the
       environment and would not reduce contaminant toxicity, mobility, and volume.
t'i
        r
1078
                                              -6-
                                                                                                   0);

-------
17.    What technical considerations were factors in selecting a remedy?  Were technical considerations
       primary in the selection of the remedy?                            I  .
                     •''              .     '         "            '          i -     ' "         -
       One technical consideration that was primary in selecting a remedial alternative was the inability
       to excavate all contaminated soil/sediment.  Contaminated soil/sediment was located in several
       areas which could be excavated but also under buildings and Interstate 90, which could not be
       excavated for practical reasons.  Furthermore, it was preferable to Keep the facility operating.
       Because it was decided that  it would be impractical to excavate soil/sediment under existing
       structures and under Interstate 90, in situ technologies were selected to address these soils. Ex
       situ technologies were chosen for soil/sediment that couldbe excavated.
                                               -7-
1079

-------
                                   Ogden Defense Depot
                                            0U-1

                                         Ogden, Utah
                                           Region 8
 GENERAL SITE INFORMATION
 L
 2.
 What were the principal contaminants,
 contaminant levels, and media addressed in
 this feasibility study?

 Maximum concentrations of principal
 contaminants were:
        Soil (mg/kg)

        PCBs
        2,3,7,8-TCDD
        Lead
        Zinc
                            3.6
                            0.000026
                            1,000
                            11,000
What volume of material is. to be
remediated?
                                                                  Site History
                                                     NPL Proposed:
                                                     NPL Final:
                                                     FS:
                                                     ROD:
                      1984
                      7/87
                      5/11/92
                     ,6/26/92
             Background

Federal Facility
PRPs: Defense Depot Ogden, Utah
FS prepared by: James M.
       Montgomery Consulting
       Engineers Inc.            ,
       The volume of material to be remediated included:

       "     4,000 cubic yards of soil


3.     What, type of site is this?            .                               .        :

       Military. The site is a defense distribution depot., The operable unit of this site consists of
       two burial units and a backfilled canal.  The site is located in a semirural setting bordered by
       several small communities.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Access limits
       Containment:         Capping (clay, synthetic, multilayer, pavement) grouting, slurry wall,
                            block displacement     .          .       .
       Chemical treatment:    Fixation/stabilization
       Thermal treatment:     Incineration (plasma, infrared)
 1050

-------
       Disposal:
Excavation, RCRA landfill
5.      Was an innovative technology considered in the FS?  If so, which technology?
            ' '  '        •-          •   •             '         :     ' -        '      '          ' * ^
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                        ;

       Biological treatment:   Biodegradation (aerobic, anaerobic, in situ, ex| situ)
       Chemical/Physical:     Washing/extraction (in situ, ex situ), oxidation (in situ, ex situ),
                              dechlorination, electrical/acoustical (in situ, ex situ)               •
       Thermal treatment:     Vitrification (in situ, ex situ), low-temperature deisorption, in situ steam
                              stripping                                  '          -
        What was the cost estimate for the innovative technology?                     ,

        During the initial  screening process, in which technically feasible teclinologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. JVfteir the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that' merit a more detailed
        evaluation.  For this site, the estimated costs were calculated during an evaluation  based on
        nine criteria established by the NCR                               ;

        In the FS, only soil technologies were evaluated during, the three-criteria analyses, and site-
        wide alternatives were developed to include ground water remediation at the detailed analyses
        stage.  The RAA  designations for the alternatives developed in the  deitailcd analyses and the
        ROD are presented parenthetically.

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-5
RAA-6
.Innovative Technology
Excavation/dechlorination or
incineration/off-site RCRA landfill
In situ vitrification
,1 . .
Estimated Costs
3 Criteria
N/A
i.
N/A
9 Criteria
eliminated
eliminated
 7.      How did the cost(s) compare to standard technologies?
                  t              :                -.         .  •            l
                  Cost Estimates for RAAs That Include Standard Technologies
                            . (selected remedial alternative is in bold)    i
Alternative
1 RAA-1
.Standard Technology
No action
Es timated Costs
3 Criteria
N/A
9 Criteria
$254,000
••••'•• .'• '•: •'•- "; •'".': ' -2- - ••••'• ';'.•:.;, • ' '' 10

-------
Alternative
RAA-2
RAA-3
RAA-4
(RAA-3)
(RAA-2)
(RAA-4)
(RAA-5)
Standard Technology
Institutional controls
Containment/cap/slurry wall/or RCRA
landfill
.Excavation/incineratlon/off-site
disposal/ground water treatment with air
stripping.
Excavation/off-site (disposal/ground
water treatment with air stripping
Excavation/off-site disposal/ground
water treatment with spray aeration
Excavation/incineration/off-site
disposal/ground water treatment with
spray aeration
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
eliminated
eliminated
$15,000,000
$2,200,000
$2,200,000
$15,000,000
 8.     If a standard technology was chosen, why?

        Off-site disposal (RAA-2) was selected because it reduces the site risk by removing the
        potential source of contamination observed in the ground water and it eliminates the potential
        for exposure to site contaminants in soil.  RAA-2 complies with ARARs; is the easiest action
        alternative to implement; provides long-term effectiveness since contaminated soil will be
        disposed of off site; reduces contaminant mobility, toxicity, and volume through proposed
        ground water remediation; and is cost-effective. It will not pose any short-term risk and it will
        minimize cross:media impacts.
 9.      If an innovative technology was chosen, why?

        An innovative technology was not selected.
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                   '

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:
                               1  .          "•,-.-        -         . '
        •      Washing/extraction (ex situ) was eliminated because treatability testing would be
               required for dioxin/furan removal and the process/technology would be expensive.
1082
                                              -3-

-------
       •       Washing/extraction (in situ) was eliminated because precise jp-ound water control
               would be required and its effectiveness would be difficult to measure and the
               process/technology would have high cost.                   i
       •       Oxidation (in situ, ex situ) was eliminated because extensive Streatability testing would
               be required for dioxin/furan removal and the process/technology would have high cost.
       •       Electrical/acoustic (in situ, ex situ) was eliminated because extensive treatability
               testing would be required, it is unproven, effectiveness is not; exacted, and the
               process/technology would have high cost.
       •       Ex situ vitrification was eliminated because incineration produces a more acceptable
               waste product for replacement on site and high cost.
       •       Biodegradation (aerobic, anaerobic, in situ, ex situ) was eliminated because it would
               not be as effective on low levels of contamination.
       •       Low-temperature desorption was eliminated because the temperature would be
               insufficient for dioxin/furan destruction.
       •       In situ steam stripping was eliminated because it would be difficult to prove
               effectiveness, it would not be suitable for dioxin/furans, and ^he process/ technology
               would be expensive.                                       \

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                       i
                                   •          -              -             [. '
       "  .     In situ vitrification was eliminated because there was spme concern that it might cause
               contaminants to migrate to deeper soils producing a zone of partially vitrified and
               contaminated soil surrounding the vitrified mass.  In addition}, vitrification becomes
               cost-effective when the depth of soil to be treated is greater ithan 8 feet and the
               maximum depth of contaminants in site soil is only 6 to 7 fe^et. Furthermore, because
               the process would not be efficient in saturated soil, it could Ijecome necessary to
               install a dewatering system at the site making the economic viability  of the treatment
               questionable.
       •       Dechlorination was eliminated because it would not be cost-effective compared to off-
               site landfilling, it would have administrative difficulties since it is an innovative
               technology, and it would require treatability testing to optimize its effectiveness and
               costs.                                      .          ,

       Innovative technologies eliminated during the detailed analysis include the following:
                                            ''''".-'      .      -       !-          ".*••
       •       None                                                    r
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion? Which of the criteria supported the use of 'a standard technology?
                                                                       •l       -         .
                                             -          .  •             j     ' •-       '          ~ ~, •
      , Implementability was-weighted most heavily criteria in selecting a remedial alternative. The
       chosen alternative was preferred because it was the most implementable of the action
       alternatives.  RAA-3 and RAA-5 would have provided greater protection and long-term  •
       effectiveness but were eliminated because they were not implementable. RAA-3 and RAA-5
       were not implementable because an  incinerator permitted for dioxin and furan destruction is
       currently not, available.  In addition, the proven technology employed for ground water
       remediation in RAA-2 is more technically implementable than the less proven technology
       proposed in RAA-4.
                                               -4-
1083

-------
        In situ vitrification and dechlorination were eliminated in the three-criteria analyses, in part,
        because they would not be cost-effective and their effectiveness was uncertain.
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Trichloroethene
Vinyl chloride
Arsenic
PCBs
2,3,7,8-TCDD
490
3.2
35
25
0.001
Risk"
Risk
Risk
FJPA*
DDAGC
Noncarcinogens
cis-l,2-Dichloroethene.
Zinc
700
1,500
Risk
Risk
               Tor carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
               to W6 was acceptable. For noncarcinogens, a Hazard Index less than or equal to 1.0
               was acceptable.                    ,         ,
               "EPA Directive 9355.4-01 FS, "A Guide on Remedial Actions at Superfund Sites with
               PCB Contamination."
               TDioxin Disposal Advisory Group Regarding Penta-Chlorophenol Waste (also PCBs),
               by P. des Rosiers, Nov. 1988.
13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       " ,    None                                             -

       Standard technologies eliminated because of cleanup goals include: .                •

       •     None
14.     Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.
  1084
                                             -5-

-------
17,
 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Proven reliability
        -   •  Waste left in place/institutional control
        -   .  Implementability


 16.     How  are measures compared?

        The choice of a remedial alternative appeared to be based mainly on irnplementability. It was
        chosen over RAA-3 and RAA-5 because these alternatives were not implementable.  It was
        chosen over RAA-4 because the ground water technology proposed in RAA-4 was not as
        proven and therefore would not be as easily implemented. In addition,' containment was not
        earned to detailed  analyses because it would require high maintenance and restrict future site
        use. Two innovative technologies were eliminated in the three-criteria [screening because they
        would require treatability studies to optimize their effectiveness and costs.  It was stated that
        treatability studies  would not be done unless alternatives employing proven technologies were
       found to be unacceptable.
                                                                                                             1
What technical considerations were factors in selecting a remedy?
considerations primary in the selection of the remedy?
                                                                     Were technical
       No technical considerations were primary in selecting a remedial alternative. The shallow
       depth of the contamination was a consideration in the elimination of in s,itu vitrification.
                                                                                            1085

-------
                                 Ogden Defense Depot
                                          OU-3

                                       Ogden, Utah
                                         Region 8
GENERAL SITE INFORMATION
1.      What were the principal contaminants,
       contaminant levels, and met
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)

       Arsenic
       Barium
       Lead '
       Mercury
       n-Nitrosodiphenylamine
       Trichloroethene
       1,1,2 ,2,-Tetrachloroethane
       Zinc
       Mustard
       Adamsite
       Thiodiglycol
       Chloroacetophenone
linants,
addressed in

ncipal



559
248
44
9.8
0.75
OJ51
0.13
74.5


NPL

Site History
Proposed: 1984
NPL Final: 7/87
FS:
ROD


N/A
: 8/21/92
Background

Federal Facility
PRPs
: Defense Depot Ogden
FS prepared by: James M.




5,000
134 ' ' '
120
3
Montgomery Consulting
Engineers, Inc.






       What volume of material is to be remediated?                              '    "

       The volume of material to be remediated included:

       •      530 cubic yards of soil and debris


       What type of site is this?

       Military.  The site is a defense distribution depot.  The operable unit consists of several burial
       sites and a water purification table burial area.
TECHNOLOGY SELECTION                                  .

4. ,     What standard technologies were considered for selection in this FS?             .'•

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
 1086

-------
       Access restriction:
       Containment:

       Chemical treatment:
       Thermal treatment:
       Disposal:
Fencing, deed restrictions
Capping (clay, synthetic membrane, multilayer
grout injection
Solidification/stabilization, fixation, immobiliaation
Incineratipn (DOD, plasma, infrared)
Excavation, disposal (on-site, off-site)
5.      Was an innovative technology considered in the FS?  If so, which technology

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:
        Biological treatment:
        Physical/chemical:

        Thermal treatment:
Biodegradation (aerobic, anaerobic, in situ, ex
Oxidation (in situ, ex situ), electrical/acoustic (in
washing/extraction (in situ, ex situ)
Vitrification (in situ, ex situ), steam stripping
desorption
•, pavement), slurry wall,

 ion, lime neutralization*
 situ)
 in situ, ex situ),

 low-temperature thermal
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  j\fter the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For thisxsite, the estimated costs are calculated during an evaluation based on nine
        criteria established by the NCP.                                         •

        Some alternatives were developed in greater detail in the detailed ansjlyses. The RAA
        designations for these changes are presented parenthetically in the table l«low. No innovative
        technologies were incorporated into remedial alternatives.
        How did the cost(s) compare to standard technologies?             i      .

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)    j
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
(RAA-3A)
Standard Technology
No action
Institutional controls
Clay cap
Excavation and debris separation/
transport contaminated soil off site/
stabilization if necessary /off-site
disposal
Estimated Costs
3 Criteria
N/A;
N/A
isr/A
N/A
9 Criteria
$11,300
$201,000
eliminated
$362,000

2- 1087

-------
Alternative
(RAA-3B)
RAA-5
(RAA-4A)
(RAA-4B)
Standard Technology
Excavation and debris separation/trans-
port contaminated soil off site/incin-
eration if necessary/off-site disposal
Excavation/transport all soil off site/
stabilization/off-site disposal
Excavation/transport all soil off site/
incineration/off-site disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A , •
9 Criteria
$570,000
$420,000
$1,792,000
  8.      If a standard technology was chosen, why?

         Because the nature of the items and the chemical contaminants present in burial areas varies,
         no single RAA was suitable for all of the burial areas.  The selected remedy consists of two
         RAAs. RAA-3A was chosen for the chemical warfare agents (CWA) Identification Kit and
         the Riot Control  and Smoke Grenade burial areas, and RAA-4 A was chosen for the
         Miscellaneous Items, Water Purification, Tablet, and the Compressed Gas Cylinder burial
         areas. At all areas, CWAs will be taken to a licensed DOD chemical munitions disposal
         facility.  The major difference between these two alternatives is that RAA-4A removes all area
         soil for disposal off site and RAA-3A will first sort soil and debris and remove only
         contaminated soil for disposal off site.

         These alternatives were deemed protective of human health and the environment since
         contaminated soil will be disposed of off site, removing the potential for direct
         exposure to contaminants in soil and the potential source of ground water
         contamination. In both instances, short-term risk will be minimized by utilizing
         specially trained individuals to implement the remedy. These alternatives will achieve
         long-term effectiveness and permanence through off-site disposal. While greater
         permanence would be achieved through  incineration the extra cost associated with
         incineration was not deemed justifiable.  Both alternatives reduce contaminant
         mobility.  These alternatives are technically and administratively implementable and
         cost-effective.              ,''.-.•

         RAA-3A was the most appropriate alternative for the Riot Control and Smoke Grenade burial
         areas because there is less than 1 cubic yard of contaminated materials in these areas and the
         contaminants in the soils are not known  to be above health-based levels.  RAA-3A, therefore,
         was selected for these areas because it is the least expensive action option.  RAA-3A provides
         greater long-term effectiveness and permanence for the CWA Identification Kit burial area
         because this area  is contaminated with arsenic which would not be destroyed by incineration.
         Incineration could lead to uncontrolled release of arsenic.

         RAA-4A was more appropriate for the Miscellaneous Items burial area since this alternative
         provides greater long-term effectiveness  and permanence in an area that is a threat to ground
         water quality. RAA-4B would have provided more protection  but because there is no direct
         health  threat at this area, the increased cost of RAA-4B  could not be justified.
  I"1
)
1088
                                               -3-

-------
9.      If an innovative technology was chosen, why?

       An innovative technology was not chosen.
10.    If an innovative technology was not chosen, why not? At what stage
       technology eliminated?
        Innovative technologies could be eliminated from the remedial technology
        three stages: during the initial screening; during the screening of the
        effectiveness, implementability, and cost; or during the detailed evaluation
was the innovative
      selection process at
 three criteria of
        Innovative technologies eliminated during the initial screening induce the following:

        •      Oxidation (in situ) was eliminated because it would not be suitable for site
               contaminants.
        •      Electrical/acoustical (in situ) was eliminated because it would riot be suitable for site
               contaminants.
        •      Washing/extraction (in situ)  was eliminated because it would not be suited, for
               conditions at OU-3.                                      j                   !,
        •      Vitrification (in situ) was eliminated because it would be significantly more expensive
               than other technologies.                             •''•'..
        •      In situ biodegradation (aerobic, anaerobic) was eliminated because it would not be as
               effective oil metals.                                        '
        •      Steam stripping was eliminated because it is not expected to1 be effective, it would be
               expensive and its effectiveness would be difficult to prove.                     .
        •      Washing/extraction (ex situ) was eliminated because it would be ineffective on buried
               materials at OU-3.                                      ,
        •      Oxidation (ex situ) was eliminated because it would be ineffective on buried materials
       . .  '  '   at OU-3.,  '         '     •"•'...'.    '        •-     |  "
        •      Electrical/acoustical (ex situ) was eliminated because it is umproven and extensive
               treatability studies would be required.  .
        • •     Vitrification (ex situ) was eliminated because it would produce more unacceptable
               , waste product on site.               .   _
        •      Ex situ biodegradation (aerobic, anaerobic) was eliminated because it would not be
               suitable for contaminants  and concentrations at OU-3.      I,
        •      Low-temperature thermal desorption was eliminated because it would not be effective
               on contaminants at OU-3.  In addition, it would be expensive and it would not be a
               practical solution.    _                                   j

        A very generalized statement was made in the FS that stated that nci innovative technologies
        were selected for developing RAAs because they would not offer significant benefit in terms
        of effectiveness, implementability or fewer adverse impacts over proven technologies. In
        addition, some innovative technologies would not comply with ARARs (none specified),
        especially with respect to the possibility of CSM (riot defined) or Chemical Warfare Agents
        contamination. Finally, no cost savings would be realized through implementation of
        innovative technologies at this,site.   •  -  '
                                                -4-
                        1089

-------
  11.
  12.
          Innovative technologies eliminated during the screening of the three criteria include the
          following:                   v

          •      None                                             .   ,           „

          Innovative technologies eliminated during the detailed analysis include the following:

          •      None
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion?  Which of the'criteria supported the use of a standard technology?

 The criteria weighted most heavily in selecting a remedial alternative were cpst and protection
 to human health and the environment. The chosen alternative provides adequate protection to
 human health and the environment for the least cost.  Other alternatives that employed
 incineration would have provided greater protection and long-term effectiveness; however,
 these alternatives were eliminated because of their much greater costs.                       .


 What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?
Contaminant.
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Trichloroethene
1 , 1 ,2,2-Tetrachloroethane
n-Nitrosodiphenylamine
35
490
30
1,250
Risk8
Risk
Risk
Risk
Noncarcinogens
Mercury
2
Risk
                'For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
                to 10- was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0
                was acceptable.
                                                                                                             I
                                                                                                           )
 13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?                          .

Innovative technologies eliminated because of cleanup goals include:

•      Not specified                          ,
1090
                                               -5-

-------
14.
Standard technologies eliminated because" of cleanup goals include:

•   •   None'    -            .        ' .        •         •       |  '.  '   , '        -
                                       v                        I" '        -

Were treatability studies conducted on the innovative technology or standard technology?

Treatability studies were not conducted,                           i           . .'•
15.  '  What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

              Cost-effectiveness
16.    How are measures compared?                      •           '!''-.'

       RAA-3A was preferred because it is the least expensive  action alternative.  Even though RAA-
       4B would offer greater reductions in contaminant toxicity, mobility, ibd volume through
       incineration, RAA-4A was preferred over RAA-4B for the Miscellaneous Items burial area.
       RAA-4B would have been six to seven times more expensive to implement.  Further, because
       the major threat to the-Miscellaneous Items burial area is cross-media contamination rather
       than a direct health hazard, the additional cost associated with RAA-4B was not justifiable.
   I            :  '  •         ,                  •      • :      •   '" '     I''-'.'.'.

17.     What technical considerations were factors in selecting a remedy"? V^ere technical
        considerations primary in the selection of the  remedy?

        The potential for a burial area to be a source of ground  water contaniination was a primary
        technical issue that was primary in selecting a remedial  technology.  [Thus,.if there was -a threat
        of ground water contamination RAA-4A was preferred over RAA-3A because it would be
      >  more protective.
                                               -6-
                                                                                      1091

-------
                                    Ogden Defense Depot
                                            OU-4

                                         Ogden, Utah
                                           Regions
  GENERAL SITE INFORMATION
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:

Soil (mg/kg)

Lead 1,400
VOCs 193 .
PCBs 15
Hydrocarbons . 43,000
Dioxins/furans 0.067s
Toxicity Equivalency Factor.

Siie History ; ;

NPL Proposed: 1984
NFL. Final: ,7/87
FS: 12/91
ROD: 8/3/92

Background
1 •
Federal Facility
PRPs: Defense Depot Ogden
FS prepared by: James M.
Montgomery

 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        *      4,500 cubic yards of soil
 3.      What type of site is this?                                         .      "

        Military.  The site  is a defense distribution depot. The operable unit consists of two burial
        units.  The site is located in a semirural setting bordered by several small communities.
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                       ,                       •

        Access restriction:    Restricted entry  .
        Containment: •       Capping (clay, synthetic, multilayer, pavement), grouting, slurry wall,
                            block displacements RCRA liner and cap
        Chemical treatment:   Fixation/stabilization
1092
                                            -1-

-------
       Thermal treatment:    Incineration (plasma, infrared)
       Disposal:             Excavation, off-site disposal
5.      Was an innovative technology considered in the FS? If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were: -       .                               v

       Biological treatment:   Biodegradation (aerobic, anaerobic, ex situ, iiii situ)
       Chemical treatment:   Washing/extraction (ex  situ, in  situ), oxidation (ex situ, in situ),
                             dechlorination                             ;
       Physical treatment:    Electrical/acoustical (ex situ, in situ)        !
       Thermal treatment:    Vitrification (ex situ, in situ), low-temperature desorption, in situ steam
                             stripping
        What was the cost estimate for the innovative technology?         .:\

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process         :
        (effectiveness, implementability, and cost) to identify alternatives thai merit a more detailed
        evaluation.  In mis case, the estimated costs were calculated during aln evaluation based on  ,
        nine criteria established by .the NCP.                              I
                                                     • •                 i .    . . • •         •
        RAA designations were changed between the three-criteria analysis aind (the detailed analysis
        because some alternatives were eliminated.  Furthermore, ground water treatment was
        incorporated into the remaining alternatives.  Changes in RAA designations are presented
        parenthetically.         '                     . "  ' "              j                        ,

                 Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)      -
           Alternative
          RAA-5A
          (RAA-4A) ,
          RAA-6
          (RAA-7A)
        Innovative Technology
Excavation/dechlorination/ground water
treatment with air stripping and GAC
(granular activated carbon)
In situ vitrification
Excavation/dechlorination/ground water
treatment with UV/ozone
                                                                        Estimated Costs
3 Criteria
  •N/A
eliminated
9 Criteria8
$6,800,000
    or
$7,600,000
               $6,900,000
                   or
               $7,600,000
        "Present worth is given for 5 years or 10 years.
                                               -2-
                                                                                            1093

-------
  7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
1 	
Alternative
RAA-1
	
RAA-2
RAA-3A
	 __ 	
RAA-3B
(RAA-2)
(RAA-3A)
RAA-4A
(RAA-3B)
RAA-5B
(RAA-4B)
(RAA-5)
(RAA-6A)
(RAA-6B)
(RAA-7B)
Standard Technology
No action
Institutional controls
Excavation/slurry wall/cap
Excavation/on-site landfill/cap/ground
water treatment with air stripping and
GAG
Excavation/off-site landfill/ground
water treatment with air stripping
and GAC
Excavation/off-site incineration/off-site
disposal/ground water treatment with air
stripping and GAC
Excavation/on-site incineration/ground
water treatment with air stripping and
GAC
Excavation/on-site landfill/cap/ground
water treatment with UV/ozone
Excavation/off-site landfill/ground water
treatment with UV/ozone
Excavation/off-site incineration/off-site
disposal/ground water treatment with
UV/ozone
Excavation/on-site incineration/ground
water treatment with UV/ozone
Estimated Costs
3 Criteria
.N/A
eliminated
eliminated
N/A
—
N/A
N/A '.
— -
, — , . •
—
• — —
9 Criteria11
$113,000 or
$186,000
- . 	 .
	
$3,000,000
or
$3,900,000
$3,800,000
or
$4,500,000
$18,000,000
or
$19,000,000
$7,000,000
or
$7,800,000
$3,100,000 1
or
$3,900,000
$3,900,000
or
$4,600,000
$18,000,000
or .
$19,000,000
$7,100,000
or
$7,800,000
       "Present worth is given for 5 years or 10 years.
8.     If a standard technology was chosen, why?
       The chosen alternative, (RAA-3A), will excavate contaminated soil and transport it off site for
       disposal.  During excavation, TCLP testing will be preformed periodically to confirm the
1094
                                            -3-

-------
        characteristics of the soil and its suitability for land disposal.  If "a soil sample fails the TCLP
        criteria, the soil volume represented by this sample will be treated with stabilization/fixation
        techniques. If treatment is unsuccessful for dioxins, the failing material will be transported to
        an incineration facility.  While no permitted incineration facilities exist for dioxin destruction,
        storage will be undertaken until permitting is completed.  The chosen alternative protects
        human health and the environment because it removes all contaminatixl soil and thereby
        eliminates the source of ground water contamination with organics and eliminates the potential
        for exposure to these contaminants in soil.  This alternative will not pose any short-term risk
        to human health, the environment, or endangered species and their habitats nor will the site
        present any unacceptable risks after completion of the remedy.  The selected remedy also
        minimizes cross-media impacts through the use of air emissions controls if necessary.  The
        proposed alternative satisfies all ARARs.  The selected remedy is cost effective because it
        provides maximum effectiveness proportional to its cost compared to the other alternatives
        analyzed.  The selected alternative costs less than the off-site incineration alternative, and
        provides a greater degree of protectiveness to human health and the  environment when
        compared to the on-site remediation alternatives. The selected remedy will be protective in the
        long term because it removes the source of ground water contamination from the site, and
        allows clean closure of the site in a cost-effective manner.   1
9.     If an innovative technology was chosen, why?
                     • -            _              ,."-•.•          •[•"•          •
       An innovative technology was not selected.                         j                   .
                                                                         ,1       • '     '     . * "-


10.    If an innovative technology was not chosen, why not? At what stage vyas the innovative
       technology eliminated?                            ,                >

       Innovative technologies could be eliminated from the remedial technology selection process  at
       three stages:  during the initial screening; during the screeningof the three criteria of    .'"••'
       effectiveness, implementability, and cost;  or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:
                                                    "                , '   • f '•»•.*•
       •      Washing/extraction  (ex situ) was eliminated because treatabilily studies would be
               required for dioxin/furans.              -
       •      Oxidation (ex situ,  in situ) was eliminated because extensive treatability studies would
               be required for dioxin/furans.                                I                 ;
       •      Electrical/acoustical (ex situ, in situ) was eliminated because extensive treatability tests
           -   would be required and the technology has not been proved. •                         ,
       •      Vitrification (ex situ) was eliminated because incineration would produce a more
               acceptable waste product on site.
       •      Biodegradation (aerobic, anaerobic, in situ, ex situ) was eliminated because it would   ,
               not be effective on low levels of contamination.              i
       •      Law-temperature desorptidn was eliminated because the temperature would be
               insufficient for dioxin/furan destruction.
       •      Washing/extraction  (in situ) was eliminated because precise ground water control
               would be required and it would be difficult to measure effectiveness.
       •      In situ steam stripping was eliminated because it would be difficult to prove its
               effectiveness and it  would not be suitable for dioxin/furans.
                                               -4-   ,.                  j                     1095

-------
  11.
                       * ,     '               -•
  Innovative technologies eliminated during the screening of the three criteria include the
  following:                                                           '
                                            1      '            .
  «      Vitrification (in situ) was eliminated because implementation could potentially cause
         the contaminants to migrate to deeper soils. This could produce a zone of partially
         vitrified and contaminated soil surrounding the vitrified soil mass.  The technical
         implementability of the process is poor because pf the questions regarding contaminant
         migration, the shallow depth of contamination, and the high water table conditions
         These technical difficulties put the technology's ability to comply with ARARs in
         question when compared to other remedial alternatives. In addition, vitrification
         becomes cost effective when the depth of soil to be treated is greater than 8 feet and
         the water table is below the contaminated zone (Geosafe Corporation, 1989). The
         contaminated soil in OU-4 extends to a depth of only 9 to 10 feet and the water table
         is also at this depth. The economic viability of this process is questionable.

 Innovative technologies eliminated during the detailed analysis include the following:

 •      Dechlorination was eliminated because it would require a treatability study to confirm
        the ability of this technology to treat PCB, dioxin, and furan-contaminated soil.
        Furthermore, "the administrative difficulties associated with pn-site dechlorination as
        an innovative technology make implementation of this alternative more difficult."

                                                                    t            '
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 The criteria that were weighted most heavily in selecting a remedial alternative  were
 implementability and cost.  While alternatives that utilize technologies such  as incineration or
 dechlorination would provide greater long-term effectiveness and greater reduction in
 contaminant mobility, toxicity, and volume, these alternatives were not chosen because of
 implementation problems and cost.

 In situ vitrification was eliminated because of implementation difficulties and because it  would
 not be cost-effective.
  12.
What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?                  ,
1096
Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Benzene
Vinyl chloride
Lead
PCBs
35
210
• 3.2
500
25
Background8
Riskb
Risk
OSWERC
EPA"
                                               -5-

-------
Contaminant ,
Dioxin/furans
Cleanup Level (mg/kg)
0.001
ARAR or Other Basis
! DDAGe
Noncarcinogens • - .
cis- 1 ,2-Dichloroethene
700
1 Risk
               "Cleanup levels correspond to a 10"4 cancer risk as concentrations corresponding to a
               lO"5 cancer risk are below naturally occurring background levels.
               bCleanup levels correspond to a cancer risk of 10"5 under a future residential soil
               ingestion scenario.                              .          [
               °Cleanup level was chosen because it "is a typical remediation criterion for residential
               soils at CERCLA sites",                                  j.
               "EPA Directive 9355.4-01FS "A Guide on Remedial Actions at Superfund Sites with
               PCB Contamination:"
               "Cleanup levels derived from the "General Approach Used by the Diqxin Disposal  .
               Advisory Group (DDAG) Regarding Pentachlorophenol Waste (also PCBs)," by P. des
              .Rosiers, November 1988.                                   .
13.    Was the innovative technology eliminated because of the cleanup gotils?  Could the standard
       technology meet the cleanup goals?               ~               !

       Innovative technologies eliminated because of cleanup goals include:

       •      In situ vitrification

       Standard technologies eliminated because of cleanup goals include:

       •      Slurry wall and cap
14.    Were treatability studies conducted on the innovative technology or standard technology?

       No treatability studies were conducted.
75.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Total cost
             Proven reliability,                .          .
16.     How are measures compared?

       Incineration was not chosen because no U.S. facilities were permitted for dioxin and furan
       destruction. Furthermore, alternatives that incorporated incineration had much higher costs.
       Dechlorination was eliminated because it would require treatability studies to determine its
       effectiveness for contaminants at OU-4 and the suitability of treated spil for replacement in
                                              -6-
1097

-------
          excavated areas.  If treatability studies were not satisfactory, or treated soils could not be
          S^ackfilled on site, the alternative would not achieve any greater reduction in mobility, toxicity,
          or volume, or long-term effectiveness than the selected remedy.
  17.     What technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in the selection of the remedy?
                                                         \  •             '.         • •  .  '    •
          No technical considerations were primary in selecting a remedial alternative.  In  situ
          vitrification was eliminated because of the depth of the contamination and the shallow water
          table.                                                           .     .
         References:

         Geosafe Corporation.  1989. Application and evaluation considerations for in situ vitrification
         technology:  A treatment process for destruction and/or permanent immobilization of
         hazardous waste materials.  GSC 1901 (April).              ,
109S
                                                 -7-,

-------
                     Portland Cement Company (Kiln Dust 2 & 3)
                                •••••-  -OU-2  ... -     -  .;  •  '• •;.   •
                                                                    I
                                                     '"               \   -
                                    Salt Lake City, Utah
                                         Region 8                   !
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil (rag/kg)

        Arsenic              13.92
        Cadmium            1.9
        Total chromium      27.5
        Chromium VI        1.25
        Lead                 772
        Molybdenum         43       '
2.     What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:

       •      488,000 cubic yards of soil, of which
              levels for lead
       •      120 cubic yards of chromium-bearing
                 Site History
    NPL Proposed:
    NPL Final:
    FS:
    ROD:
9/84
6/10/86
11/91
3/31/92
                 Background
    PRP-lead
    PRPs:  Lone Star Industries, and Site
           landowners: Williamsen
           Investment ipo., L.D. Williamsen,
           S.M. Hormjln, V.H. Horman,
           Horman Family Trust,
           C.B.Brown,'and Southwest
           Investment, Inc.
    FS prepared by: Tejtra Tech
27,000 cubic yards exceed health-based cleanup
                     I •
                     !'.„•,.        ,
bricks (coated with cement Iciln dust)
3.      What type of site is this?                                        ,
                     '                *     '        ' •                 I    . "
       Construction.  A former cement plant located in an industrial area that fis bordered by low-
       density residential and vacant or agricultural land.                  I


TECHNOLOGY SELECTION                                          ,!   .
                                           "..•'-.            -.'-.•'}'.       '    ,    '      '
4.      What standard technologies were considered for selection in this FS? \

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                  _                           ;
                                                         . -          i  '   .
       Access restriction:      Property deeds, land use restrictions, zoning ordinances
                                           -1-
                                     1099

-------
          Containment:
          Chemical treatment:
          Physical treatment:
          Disposal:
Soil cover              .      '
Chemical fixation, solidification
.Recycling
Disposal (on-site, off-site)
   5.      Was an innovative technology considered in the FS? If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:                                  ,

          Chemical treatment:    Dissolution and recovery of chromium, soil washing with precipitation
                                and recovery of lead
          Thermal treatment:     Batch vitrification                                   '
   6,      What was the cost estimate for the innovative technology?                                  •

          During the initial screening process, in which technically feasible technologies are identified .
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been '
          formulated, costs ate typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a, more detailed
          evaluation. For this site, estimated costs were calculated during an evaluation based on nine
          criteria established by the NCP. No innovative technologies were incorporated into remedial
          alternatives.
   7.      How did the cost(s) compare to standard technologies?

                    Cost Estimates for RAAs That Include Standard Technologies
                               (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3


RAA-4

• Standard Technology
No action
On-site fixation of chrome-bearing
bricks/off-site disposal/soil cover/
institutional controls
On-site solidification of soil/disposal
off-site/on-site fixation of chrome-
bearing bricks/off-site disposal/soil
cover
On-site solidification of soil/on-site
fixation of chrome-bearing bricks/on-
site disposal/soil cover
Estimated Costs
3 Criteria
N/A
N/A
N/A


N/A

9 Criteria
$0
$2,935,799
$6,418,434


$5,653,956

1100
                                                 -2-

-------
 8.     If a standard technology was chosen, why?                         !
 "                 '     '                      •   .            '       '.!-'•
        RAA-3 was chosen because it offers long-term effectiveness and the greatest protection to
        human health and the environment. The proposed treatment addresses site; soil and chromium-
        beanng bricks.  Cleanup levels will be reached; lead and arsenic contaminations will be
        reduced to 500 and 70 ppm, respectively, and chromium will be reduaid to 5 mg/L or less as
        measured by TCLP analyses.  Stabilization/fixation eliminates site risk from direct contact with
        sodlor chromium-bearing bricks. Further, treatment of site soil and bricks reduces contaminant
        toxicity and mobility permanently by removing a source of ground water contamination  This
        alternative also provides the greatest long-term effectiveness  and permanence since site
        materials would be treated and disposed of off site in a controlled solid waste landfill
        Disposal in an off-site solid waste landfill was preferred because it provides  greater long-term
        effectiveness since the release of contaminants can be prevented since it is a more controlled
        environment and does not rely on institutional controls. This alternative complies with all
        ARARs.  Short-term risk posed by die implementation of this alternative is; comparable to that
        of other alternatives. Fugitive dust generation during brick crushing arid excavation and soil
        treatment can be  minimized by dust suppression measures,  air monitoring, and  appropriate
        personal protective wear. This alternative can be implemented within the year. The
        equipment for treating the contaminated soil and chromium-bearing bricks is  readily available
        from several vendors and the treatment technology is well demonstrated,  tiquipment for
        crushing brick is  available from several vendors.  Presently there is sufficient capacity at
        existing off-site solid waste landfills to accommodate the anticipated amounts of treated and
        solidified soil and brick.  This alternative was the most accepted by the community and is
        cost-effective.
                                   ' '        •                  .   •    •• r   ,     -.-•..•-.'-
        The preferred alternative for the proposed plan was on-site  treatment arid on-site disposal
        During the public comment period several factors were brought out thai influenced the
        decision to change the preferred alternative to on-site treatment and off-site disposal  These
        factors included: treated material would be subject to changing environmenfal conditions at the
        site; the proposed alternative would rely heavily on  institutional control!?; off-site disposal
        provides greater permanence and assured effectiveness; and the cost difference between on-site
        and off-site disposal is relatively  small.
9.
10.
       If an innovative technology was chosen, why?

       An innovative technology was not chosen.
       If an innovative technology, was not chosen, why not? At what stage wai the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technoloiJy selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       fonovative technologies eliminated during the initial screening include th'e following:

       •      Batch vitrification was eliminated because it could not be used oh site by the same
              vendor to treat both chromium-bearing bricks and lead contaminated soil. Further
              "vitrification involves technical problems due to the high melting temperature of the
                                             -3-
                                                                                          1101

-------
                 furnace." Off-site vitrification was not desirable since shipment of chrome-bearing
                 bricks off site as a hazardous waste would be expensive because of DOT regulatory
                 requirements, would cause additional short-term risks, and would be contrary to RCRA
                 Land Disposal Restrictions.  Some vendors do not have crushing facilities and bricks
                 would need to be crushed prior to shipping.  This was considered highly undesirable
                 since it would increase short-term risk.
          •      Soil washing was eliminated because compared to stabilization, it could not address
                 chromium- and lead-contaminated materials simultaneously, it would not be as well
                 suited to treat large volumes of waste and it would be more expensive.
          •      Dissolution with precipitat ion and recovery of chromium was eliminated because it
                 could not be used on site by the same vendor to treat both chromium-bearing bricks
                 and lead-contaminated soil.  '•

          Innovative technologies eliminated during the screening of the three criteria include the
          following:                                                             .•'.' .

          •      None  ,                                                 .             f

          Innovative technologies eliminated during the detailed analysis include the following:

          •      None
  11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
          which criterion?  Which of the criteria supported the use of a standard technology?        -.

          Protection to human health- and the environment and long-term effectiveness and permanence
          were the criteria weighted most heavily in selecting a remedial alternative. RAA-3, the
          selected alternative, was preferred over RAA-1 and RAA-2 because it is more protective since
          it treats both lead-contaminated soil and  chromium-bearing bricks.  RAA-3 was preferred over
          RAA-4 because.it disposes of treated materials off site in a landfill as opposed to on site.  This
          was considered better in the long term because the landfill is a controlled environment that can
          prevent the release of contaminants in the event that the treatment breaks down (e.g.,
          breakdown of stabilized mass).                                                    ;

          No innovative technologies were eliminated due to these criteria.

                                                        i                          ,
  12.     What cleanup' goals were selected?  If the cleanup goal was based on an ARAR, what was that
          ARAR? What risk level was selected to establish cleanup goals?

                 Cleanup levels were presented both in the ROD and the FS.                 •
                                                                 ...        .     ..  .                    .   3
1102
                                                -4-

-------
Feasibility Study
Contaminant
Cleanup Level (mg/kg)
ProduceVNonproduceb/
Total6
ARAR or Other Basis
Carcinogens
Arsenic
130/190/77
Risk"
Noncarcinogens . \ .
Lead
Cadmium
Chrome (ffl)
Chrome (VI)
Molybdenum
500
38/1,100/37
640,000/NA/410,000
3,200/5,600/2,000
130/4,500/120
Blood6
Risk
Risk
Risk
Risk
The action level calculated for a future use scenario in which a residential popu
is exposed to produce grown in site soils. .
The action level calculated for a future use scenario in which a residential population
is exposed to site soils.      .
The action level calculated for a future use scenario in which a residential population
is exposed to site soils and produce grown in site soils.     '
"teased on an acceptable cancer risk of 10"4.           '    '
•Basedon IU/BK Model prediction of 10 ug/dL blood lead concentration.
                               '               '        !        '         '
.'ROD     ,            '     '     *  .     '•••,'.••••  \     .   ;   ,.   '..;
~ Contaminant
Cleanup Level (mg/kg)
ARAIL or Other Basis
-' • . - •
Carcinogens '
Arsenic
70
F^isk"
Noncarcinogens K
Lead
500
Blood"
Cleanup level is health based.  For carcinogens, an excess upper bound individual
lifetime cancer risk of 10"4 was acceptable,
"Cleanup level is based on IU/BK Model prediction of 10 ug/dL blood lead
concentration.                     .                    j
                               -5-
                                                                             1103

-------
   13.
        Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

       ' Innovative technologies eliminated because of cleanup goals include:

        •      None           .

        Standard technologies eliminated because of cleanup goals include:

        •  •    None
                                                                                                            1
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.                                               .


 15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Preference for treatment (vs. containment)
             Impact on nearby populations
             Waste left in place/institutional control


16.    How are measures compared?

       In an effort to  ensure the protection of human health and the environment, treatment of site
       soil and bricks was preferred over containment. Further, following public comment, RAA-3
       was preferred over RAA-4 because stabilized materials would be disposed off site.  The public
       preferred this option because of the potential for breakdown of the stabilized materials and
       because site use would be restricted.  Impact of nearby populations was a concern and
       vitrification was eliminated because of the risk associated with the transport of waste materials
       off site.                                                          . .  •
                                                                                                     if
  77.
       What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?   .

       No technical considerations were primary in selecting a remedial alternative.
1104
                                              • -6-

-------
                    U.S. Department of Energy Rocky Flats Plant
                                          OU-2

                                     Golden, Colorado
                                         Region 8
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
       Soil (rag/kg)

       VOCs
       Plutonium (Pu)
       Americium (Am)
       Aluminum
       Arsenic
       Barium
       Cadmium
       Calcium
       Iron
       Mercury
       Manganese
       Lead
       Antimony
       Vanadium
       Zinc
1.700
457 pCi/g
lOOpCi/g
25,300  /
30.8
216
6.2   .
175,000
42,700
0.33
1,080
22.8  .
115
50.5
65.8
             Site History  .
                 ';!
NPL Proposed:    i    N/A ' ..
NPL Final:            N/A
Interim Measures/
Interim Remedial  |
Action Plan/      j
Environmental    J
Assessment       :
(IM/IRAP/EA):        9/10/92
              •  ' '. i
             Background
                '• [ -
                 i -
Federal Facility    j
PRPs:  U.S. Department of Energy
FS prepared by:  EG&G Rocky Flats,
       Inc.       i
2.    . What volume of material is to be remediated?

       The volume of material to be remediated included:
                                           i
       •      Volume of soil to be remediated was not given.
       What type of site is this?                                       i
                            -  •.       •        .     -  '•'     •          '!••'''
       Department of Energy.- The site is part of a nationwide nuclear weapons research,
       development, production, and plutonium reprocessing complex. .A government-owned,
       contractor-operated facility on the site has been in operation since 1951 and manufactures
       components for nuclear weapons and conducts plutonium reprocessing;. Plant buildings are
       located within an area of approximately 400 acres, which is surrounded by a buffer zone of
       approximately 6,150 acres.  The site is located in a rural area.       }
                                            -1-
                                                                                       1105

-------
  TECHNOLOGY SELECTION

  4.      What standard technologies were considered for selection in this FS?

         Standard technologies were not considered in the IM/ERAP/EA.
  5.      Was an innovative technology considered in the FS? If so, which technology?

         The following innovative technologies were considered in the IM/IRAP/EA:

         Biological treatment:   Bioremediation            '   -                            ,
      .   Phys/Chem treatment:  Dehalogenation, oxidation, steam stripping, vacuum-enhanced vapor
                              extraction
 6".      What was the cost estimate for the innovative technology?
                                                                                            }
         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process (effective-
         ness, implementability, and cost) to identify alternatives that merit a more detailed evaluation;
         Estimated costs are recalculated during an evaluation based on nine criteria established by the
         NCP.  For this site no costs were given for any of the technologies discussed.

                 Cost Estimates for RAAs. That Include Innovative Technologies
                             (selected remedial alternative is in bold)
y
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
Innovative Technology
In situ dehalogenation
Chemical oxidation
Steam stripping
Bioremediation
Vacuum-enhanced vapor extraction
Estimated Costs
IM/IRAP/EA
N/A
N/A
N/A
N/A
N/A
1106
                                              -2-

-------
7.'     How did the cost(sj compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Techno logiies
                            (selected remedial alternative is in bold)
. Alternative
RAA-6
\
Standard Technology
No action .
Estimated Costs
IM/IRAP/EA
N/A
5.     If a standard technology was chosen, why?

       A standard technology was not chosen.


9.  •   If an innovative technology was chosen, why?

       In situ vacuum-enhanced vapor extraction was chosen for removing volatile organic
       compounds (VOCs) from vadose and saturated zones at three different OU-2 subsurface
       environments.  This technology coupled with water table depression satisfies the following
       criteria: it achieves the IM/IRAP/EA objective; it addresses the source of the dissolved-phase
       ground water plume; and it minimizes the risk of spreading contamination.  The primary
       objective of the IM/IRAP/EA is to collect information that will aid in {selecting and designing
  .     final OU-2 remedial actions that address subsurface residual free-phase VOC contamination.
       The selection of in situ vacuum-enhanced vapor extraction will provide data that will be useful
       in selecting and designing of a final action as it  is potentially applicable at all OU-2 solvent ,
       spill or burial sites.' This technology addresses the source of the dissolved-phase ground water
       plume and reduces the likelihood of additional contaminants migrating from the vadose zone
       to the saturated zone.  Since this technology does not involve subsurface injection of liquid
       reagents,' there  is; little probability of spreading the VOC contamination.  In addition,
       mobilization of radionuclides that might be present is not expected because no change  in _
       ground water pH is expected.  Subsurface IM/IRAP/EA operations and maintenance activities
       would be performed in accordance with Operational Safety Analysis (OSA) procedures.
       Considering the unconfmed nature of the work areas and administrative controls, potential
       worker exposures to airborne VOCs would be very low.  Airborne VOC concentrations would
       be lower, which reduces the potential for exposure of odier on-site personnel and the general
       public because of their greater distance from the source.             h

       In situ steam stripping is also being considered for investigation  as part of the IM/IRAP/EA
       because  it has the  potential to recover both VOCs and radionuclides, and the technology is
       currently being tested by DOE. An additional project phase might, therefore, be added to the
       selected  remedial action at the site to conduct an in situ steam stripping pilot test after, the
       results of treatability studies currently being conducted on this technology are assessed.

       The Colorado Department of Health (CDH) expressed concerns regarding the IM/IRAP/EA
       analysis. DOE expects to resolve all ARAR issues prior to finalizing the IM/IRAP/EA.
                                              -3-
                                                                                           1107

-------
    10.     If an innovative technology was not chosen, why not? At what stage was the innovative
           technology eliminated?                                                -

           For this site innovative technologies were discussed and eliminated in the IM/IRAP/EA.

           Innovative technologies could be eliminated from the remedial technology selection process at
           three stages:  during the initial screening; during the screening of the three criteria of
           effectiveness, implementability, and cost; or during the detailed evaluation.

           Innovative technologies eliminated during the initial screening include the following:

           •      None                ,

           Innovative technologies eliminated during the screening of the three criteria include the
           following:                                                                        ..   ..

           *      None            .                     .

           Innovative technologies eliminated during detailed analysis in the IM/IRAP/EA:

           •      In situ dehalogenation was eliminated but no specific reason was given for its
                 •elimination.  Process uncertainties are associated with this technology, however, with
                  respect to uncontrolled mobilization of radionuclides that-might be present in the
                  subsurface.  The dehalogenation solutions might, for example, lower the pH of the
                  ground water or degrade subsurface humic materials, potentially increasing
                  radionuclide mobility.
           •      In situ chemical oxidation  was eliminated but no specific reason was given for its
                  elimination.  Process uncertainties are associated with this technology, however, with
                  respect to uncontrolled mobilization of radionuclides that might be present in the
                  subsurface.                                                        ,    ,
           •      In situ bioremediation was eliminated but no specific reason was given for its
                  elimination.  Bioremediation has successfully treated many  nonhalogenated
                  hydrocarbons, but has been less successful with halogenated compounds.  At this time,
                  inclusion of bioremediation investigations at this site was considered premature.
          Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
          to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
          which criterion? Which of the criteria supported the use of a standard technology?

          Implementation weighed heavily in selecting an interim action for this site. The simplicity of
          design, fabrication using commonly available materials, ease of maintenance and potential for
          cost-effective operation made in situ vacuum-enhanced vapor extraction an attractive remedial
          technology.  Vapor extraction is a proven technology that has been successfully applied at
          many sites. Regeneration services for the GAC adsorption units are readily available, and
          special labor skills are not necessary to construct and operate the vapor extraction and
          treatment equipment.                               .,
1108
                                                -4-

-------
12.     What cleanup goals were selected?  If the cleanup goal was based on
       ARAR? What risk level was selected to establish cleanup goals?

       Cleanup goals were not selected for this site.
                                                                       an ARAR, what was that
                                                                        •?  Could the standard
13.     Was the innovative technology eliminated because of the cleanup goals
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •     None

       Standard technologies eliminated because of cleanup goals include:

       •     None
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.


75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Proven reliability                       .


16.     How are measures compared?

        Vapor extraction was chosen because it is a proven technology that has been successfully
        applied at many sites.
 17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting an alternative for this site.
                                               -5-
                                                                                             1109

-------
                                Silver Bow Creek/Butte Area
                      Warm Spring Pond Inactive Area Operable Unit
                                1             OU-12

                           Upper Clark Fork River Basin, Butte, Montana
                                            Regions           ,
    GENERAL SITE INFORMATION

    L      What were the principal contaminants,
           contaminant levels, and media addressed in
           this feasibility study?

           Maximum concentrations of principal
           contaminants were:

           Sediments, Tailings Deposits, and
           Contaminated Soils (rag/kg)
   2.
          Arsenic
          Cadmium
          Copper
          Lead
          Manganese
          Zinc
              1,850
              66
              9,390
              1,920
              9,320
              7,900
What volume of material is to be
remediated?
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
                     N/A
                     1983
                     10/89
                     6/30/92
             Background

PRP-lead
PRPs:  Atlantic Richfield Company
       (ARCO)
FS prepared by: Montana Department
.  .'    of Health and Environmental
       Services (MDHES) and CH2M
       Hill
          The volume of material to be remediated included:

          »      About 3.4 million cubic yards of contaminated sediments, tailings, and soils.


   3.      What type of site is this?                                          ,
                                                                    i            , '
          Mining.  A mining operation which covers the largest geographic area in the nation being
          addressed under Superfund. This site has been impacted by over 100 years of mining and
          processing operations in the Butte and Anaconda areas. Mining operations stopped in 1982,
          and mining and milling operations resumed in 1986.  This ROD addresses the Inactive Area
          Operable Unit, Pond 1,, the area below Pond 1, and the downstream portion of the Mill-Willow
          bypass (lower bypass). The site covers approximately 2,500 acres, 1,000 of which are taken up
          by open water associated with the pond system, tailings deposits and contaminated soils cover
          about 420 acres, the remaining acreage is characterized by grasslands and marshes.
1110
                                              -1-

-------
 TECHNOLOGY SELECTION
 4.      What standard technologies were considered for selection in this FS? !:

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Sediments, Tailings Deposits, and Contaminated Soils
        Access restriction:  '

        Containment:

        Chemical treatment:

        Physical treatment:
        Disposal:
Institutional controls (zoning ordinances, easements and covenants,
land use restrictions, regulations and legal barriers,, permits), fences
Capping (native soil, clay), surface controls (surface sealing, grading,
revegetation), dust suppression, berm protection, berm stabilization
Soil/sediment stabilization (sorption, pozzolanic agents), solidification,
fixation, water leaching, neutralization .  •'     j   • .
Solids dewatering                        s  |
Excavation, land disposal (RCRA landfill, non-RCRA landfill, surface
impoundments)
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                        |  ,

        Biological treatment:   Aerobic and anaerobic biodegradation, new biotechnologies, land
                           .  treatment                                         '
        Chemical treatment:   Chemical reduction, oxidation, solvent extraction, «x situ soil vapor
                   ,          extraction, soil washing, ex situ reduction, electrochemical,
                             dechlorination              ,                t
        Thermal treatment:     Low temperature thermal desorption,  ex situ steam extraction,
                             crystallization, pyrolysis, wet air oxidation, in siitu vitrification
6.      What was the cost estimate for the innovative technology?            ;
                                                                        I          ' -
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  Alter lihe RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementabilityrand cost) to identify alternatives that merit a more detailed
       evaluation. For this site, the estimated costs were calculated during an!evaluation based on
       nine criteria established by the NCP.  Innovative technologies were not incorporated into
       RAAs for this site.
7.      How did the cost(s) compare to standard technologies?

       The RAAs developed for this site changed in the ROD. These changes
       separate box below. -                '
                                            are presented in a
                                                                                            1111

-------
              Cost Estimates for RAAs That Include Standard Technologies
                        (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
Standard Technology
Solidify pond sediments/remove soils
from bypass/construct a new treatment
pond and a flood impoundment/
excavate contaminated soil with pond
disposal and solidification/ground water
treatment ,
Stabilize pond berms against a PMP
and the MCEb/remove soils from
bypass/upgrade treatment system/add
flood impoundment/excavate
contaminated soil with off-site
disposal/ground water treatment
Stabilize pond berms against a partial
PMP and the MCEVremove soils from
bypass/upgrade treatment system/add
settling basin/excavate contaminated soil
with Pond 1 disposal/cap Pond I/ground
water treatment
Stabilize pond berms against a partial
PMP and the MCEb/remove soils from
bypass/upgrade treatment system/add
settling basin/cap and revegetate con-
taminated soil/ground water treatment
Stabilize pond- berms against a partial
PMP and the MCEb/remove soils from
bypass/modify treatment system/add
settling basin/cap and revegetate
contaminated soils/ground water
collection with wetlands treatment
Stabilize pond berms against a partial
PMP and the MCEVremove soils from
bypass/modify treatment system/flood
contaminated soils and cap Pond I/
ground water collection with wetlands
treatment
No action
Estimated Costs
3 Criteria
N/A
N/A
N/A
' N/A
N/A
N/A
N/A
9 Criteria
$1,191,000
\
$241,000,000
$71,000,000
$77,000,000
$66,000,000
$55,000,000
$0
     "Probable Maximum Flood
     "Maximum Credible Earthquake
1112
                                       -3-

-------
        ROD
5.
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8
RAA-9
RAA-10
RAA-11
Standard Technology
Dry close Pond I/removal below Pond 1
Dry close Pond I/wet close below Pond 1
Dry close Pond I/dry close below Pond 1
Wet and dry close Pond I/remove tailings
below Pond 1 '
Wet and dry close Pond I/wet close below
Pond 1
Wet and dry close Pond I/dry close below
Pondl
No action
Removal of Pond 1 and area below Pond 1
to East Hills Repository
Removal of Pond 1 and area below Pond 1
to Pond 3 Repository
Removal of Pond 1 and area below Pond 1
to Opportunity Ponds Repository
Removal of Pond 1 and area below Pond 1
to Anaconda Ponds Repository
Estimated Costs
ROD
$29,100,000
$27,500^000
$28,000,000
$21,200,000
$18,100,000
1 ' ,
$18,800,000
$0
. $50,500,000
,$50,000,000
$49,500,000
$50,700,000
If a Standard terhnnlnpv wtix rhn*t>n whv? . • . " ~ .
       RAA-5 was selected because it prevents human and environmental contact, and decreases
       migration of the contaminated material to ground water. No significant risks will remain
       relative to the potential for migration of the contaminants. The wetclosure proposed under
       RAArS will substantially eliminate the tailings as a source of contamination by providing a
       reducing environment, to immobilize the metals. Toxicity will be reduced by chemically fixing
      .dissolved or soluble metals in a less soluble state through lime treatment iind maintenance of a
       high pH environment. In addition, RAA-5 includes dry closure below Pond 1, which will
       result in less risk of recontamination from floods  in Silver Bow Creeks than the other
       alternatives. RAA-5 will leave contaminants within the historic flood plain below Ppnd 1 but
       will protect them up to the 0.5 PMF and the MCE through construction of flood protection
       dikes along the Mill-Willow Bypass. RAA-5 will have the least impact because it does not
       require the removal of materials. In addition, RAA-5 can be fully implemented over a  2-year
       construction period. RAA-5 also will have the least impact on the  existing wetlands below
       Pond 1. In fact, RAA-5 maximizes the area of enhanced wetlands both, within and below Pond
       1, The wet closures associated with this  alternative in the eastern third! of Pond 1 and in the
       area below Pond  1 will result in an expansion of waterfowl habitat. RAA-5 also is supported
       by the public.
                                                                                          1113

-------
 9.      If an innovative technology was chosen, why?

         AJI innovative technology was not chosen.
 10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages: during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the  following:

         •      Oxidation was eliminated because it is not applicable to the waste  characteristics.
         •      Solvent extraction was eliminated because it is not applicable to inorganics or to sites
                conditions and volumes of water are too large.
         •      Low temperature thermal desorption was eliminated because it is not applicable to
                inorganics.
         •      Ex situ steam extraction was eliminated because it is not applicable to waste
                characteristics and site conditions and volumes of .water are too large.
         •      Ex situ soil vapor extraction was eliminated because it is not applicable to waste
                characteristics.                                                                  .
         •      Crystallization was eliminated because it is not applicable to waste characteristics and
                site conditions.                     .
         «      Soil washing was eliminated because it is not applicable to inorganics.
         "      Ex situ reduction was  eliminated because it is not applicable to site conditions and
                volumes of water are too large.
         "      Electrochemical was eliminated because it is riot applicable to site  conditions and
                volumes of water are too large.                              .
         »      Dechlorjnation was eliminated because it is not applicable to inorganics and aqueous
                wastes.
         •      Aerobic and anaerobic biqdegradation was eliminated because it is not applicable to -
                inorganics and is not technically implementable.  '
         •      New biotechnologies was eliminated because it is not applicable to inorganics and is '
                not technically implementable.
         »      Land treatment was eliminated  because it is not applicable to inorganics and is not
                technically implementable.
         •      Pyrolysis was eliminated because, it is not applicable to inorganics and is not
                technically implementable.                                                     .
         »      Wei air oxidation was  eliminated because it is not applicable to inorganics and is not
                technically implementable.                                               .
        •      In situ vitrification was eliminated because it is not applicable  to site conditions and
                volumes of water and waste are too large.
1114

-------
        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                        i

        »      Chemical reduction was eliminated because it would not be implementable.  Soil
               concentrations are too low for effective recovery. The recovery operation might
               present greater hazards than the soils-do now and--this treatment is costly.
               •'            "  -      -            .        •                  r  .        ,  '    -
        .  .-  ..          ,     .         •  •   • .        .             _          ^        ..-..,.
        Innovative technologies eliminated during the detailed analysis include the following:

        •      None               •                               •'..;'
 11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
        to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?
-      ' -             '                  -                 i     '   -      •   I
        Protection of human health and the environment, implementability, anti  cost were weighted
        most heavily in selecting the chosen alternative. RAA-5 provides protiictiveness that equals or.
        exceeds the other alternatives considered, offers the .potential for being a permanent remedy, is
        implementable, is cost effective, and provides the greatest environmental Isenefits that can be
        practically achieved. RAA-5 is the most easily  implemented alternative because construction
        equipment and services required to implement RAA-5 are readily available. The selected
        alternative is also the most cost effective, both in initial construction costs; and from a total
        present-worth  standpoint.            *                              {
                    ,  •            •        ''            •                   '  -     '
                  -•       -                     '       •   •               P \          . '
 12.     What cleanup  goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?     :
                                                            • N        ;'    i      '       -
                             -" '     '          '        -      "  '    ,       |-                -'
        Cleanup levels were not established for this site but remediation goals were established by
        EPA and MDHES as part of the FS process.
 13.   .  Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?
                           *••      •        •   ' '      -                       ].'".'•:•.
        Innovative technologies eliminated because of cleanup goals include: I      ,

                         •                  '   '         '                  i          " , .       '
      -  .•.     None  ."•••''          •  .     •       •        -          ,!,•,,'•
     - -                *                -•             •                      j ...'-,.'•
             -..--.        , -             '          -      (             !:•/',
        Standard technologies eliminated because .of cleanup goals include:
               .           ,              ^               ..  ^      ''  ; J. "  .  j :      • "     ..'•'.
        «  •    None        '        '   '-    ,              . .         •    'i  '  .   _  •   ;      •

                          '            '         •      '            '..•'['          '.'"'.•
 14.     Were treatability studies conducted on the innovative, technology or standard technology?

        Treatability studies were not conducted.                ,     \  '•  .
                                                                                                  1115
                                               -6-  '   '•     '•""..      I •     v      .'  :         -    -


-------
15.     What measures/criteria were used to compare alternatives?                     ,

        The following measures were used to compare the alternatives:

             Cost effectiveness                                             ,
             Proven reliability
             Preference for treatment (vs. containment)


16.     How are measures compared?

        The selected alternative is the lowest cost alternative examined in the Proposed Plan, except
     •  for the no action alternative. Alternatives involving total removal of contaminants (RAA-8
        through RAA-11) cost significantly more than the selected alternative, and yet did not provide
        significant additional overall protection of human health and the environment* The
     *   components of the selected remedy are well-developed technologies and are expected to be
        easily implementable. The selected  alternative utilizes lime addition to many areas of
        contamination within the inactive area. Lime addition, followed by wet closure, reduces the
      "  mobility of contaminants.  The remedy utilizes treatment.                    „   ' '  •
17.    What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in The selection of the remedy?

       Technical considerations were not primary in selecting a remedy.
1116
                                             -7-

-------
                            Wasatch Chemical Co. (Lot 6)

                                   Salt Lake City, Utah
                                         Region 8
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
      .this feasibility study?                 '

       Maximum concentrations of principal
       contaminants were:

       Soil (mg/kg)
      ' 4,4',-DichlorodiphenyIdichloro-
        ethane (4,4',-DDD)
       4,4',-Dichlorodiphenyldichloro-
        ethene (4,4',-DDE)
       4,4',-Dichlorodiphenyltrichloro-
        ethane (4,4', DDT)
       Alpha-Chlordane
       Gamma-Chlordane
       Heptachlor
       2,3,7,8 Tetrachlorodibenzodiosdn
       Hexachlorobenzene (HCB)
       Trichloroethene (TCE)
       Tetrachloroethene (PCE)
       2,4-Dichlorophenoxyacetic acid
       Pentachlorophenol (PCP)
       2,4,5<-Trichlorophenoxyacetic acid

       Sludge (mg/kg)

       4,4',-Dichlorodiphenyldichloro-
        ethane (4,4',-DDD)
       4,4' ,-Dichlorodipheny Idichloro-
        ethene (4,4',-DDE)
       4,4' ,-Dichlorodipheny.ltrichloro-
        ethane (4,4', DDT)
       Alpha-Chlordane
       Gamma-Chlordane
       Heptachlor
       2,3,73 Tetrachlorodibehzodioxin
       Hexachlorobenzene (HCB)
       Trichloroethene (TCE)
       Tetrachloroethene  (PCE)
       2,4-Dichlorophenoxyacetic acid
       2,4,5-Trichlorophenoxyacetic acid
0.4

4.5

8.1
520
890
5.3
0.011
66
1.8
22
30.768
250
1.111
0.28

6.3

2.8
520
680
26
0.013
49
440
200
0.634
0.3
                         Site! History
            NPL Proposed:
            NPL Final:
            FS:
            ROD:
                     1/87
                     2/11/91
                     8/22/90
                     3/29/91
             Background
                i          ' '
PRP-lead        '            '••'.'•
PRPs:  Entrada Industries, Inc., Mountain
       Fuel Supply Co., Inc., Interstate
    x  Brick Co., ^and Quester Corp. (the
       Entrada Group); McCall Oil and
       Chemical Co., and d/b/a Great
       Chemical Co. ([the Great Western
       Group); Hiintsman-Christensen
       Corp., Ladid E. Christensen, and
       A. Elaine Huntsman, Jr. (the
       Huntsman-Christensen Group);
       Lawnlife Corp.;  and Peter Ng
FS prepared by: Elarding Lawson
       Associates
                                            -1-
                                                                                          1117

-------
 2.      What volume of material is to be remediated? ,

         The volume of material to be remediated included:       '

         •      2,370 cubic yards of waste sludge
         •      2,328 cubic yards of soil                          .


 3.   ,   What type of site is this?

         Agricultural Chemicals. The site has been used for the formulation/blending, and repackaging
         of cleaners, acids, caustics, herbicides, pesticides, and fertilizer. The site is located in an
         industrial area.
•I
 TECHNOLOGY SELECTION                                  .

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:

        Access restriction:     Fencing, warning signs, deed restrictions, access restrictions
        Containment:          Capping, surface sealing
        Chemical treatment:    In situ stabilization, stabilization/solidification (cement-, asphalt-,
                              pozzolan-, polymerization-based), neutralization, sorbent addition
        Thermal treatment:     Incineration (fluidized bed, rotary kiln, infrared), plasma torch
        Disposal:              Excavation, on-site/off-site disposal
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                      .    ,         ,

        Biological treatment:  In situ biodegradation, slurry phase biodegradation, solid phase
                             biodegradation, rotating biological contractors, white rot fungus,
                             landfarming
        Phys/Chem treatment:  On-site chemical extraction (Best Extraction Sludge Treatment, or
                             BEST), glycolate dechlorination (APEG), critical fluid extraction,
                             oxidation, soil washing, in situ soil flushing, reduction (iron, zinc^ and
                             aluminum metal powers reduction), in situ vacuum extraction
        Thermal treatment:    In situ steam stripping, vitrification (electric pyrolyzer), pyrolysis, low-
                             temperature thermal stripping, molten salt, molten glass, in situ
                             vitrification (Geosafe process was referenced in the FS)
1118
                                              -2-
                                                                                                    <*)

-------
                                                                      ^v
6.      What was the cost estimate for the innovative technology?            |

       During the initial screening process, in which technically feasible technologies are identified
     -  (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify-alternatives that merit a more detailed
       evaluation. For this site, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.                               j

                 Cost Estimates for RAAs That Include  Innovative Technjoloj'ies
                            (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
RAA-6
RAA-8
'
Innovative Technology
Excavation/vacuum extraction/off-site
incineration/landfarming
Excavation/vacuum extraction/in situ
vitrification/landfarming
Excavation/vacuum extraction/on-site
glycolate dechlorination/off-site
incineration
Excavation/vacuum extraction/ , •
landfarming
Excavation/vacuum extraction/off-site
disposal/landfarming/off-site
incineration
Estimated Costs
3 Criteria
N/A
• . • r
N/A
N/A ;
, , ij-
-1
N/A
N/A
[ - ,
9 Criteria
eliminated"
$3,300,000
$4,100,000
•eliminated
$1,700,000
  7.      How did the cost(s) compare to standard technologies?            ,,

                   Cost Estimates for RAAs That Include Standard Techijiologies
                             (selected remedial alternative is in bold)    |
   8.
If a standard technology was chosen, why?

A standard technology was not chosen.
Alternative
RAA-1
RAA-2
RAA-7
Standard Technology
No action
Institutional controls
Capping/off-site incineration
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$24,000
eliminated
$660,000 '.
                                                -3-
                                                                                               1119

-------
  P.      If an innovative technology was chosen, .why?

         The selected alternative RAA-4, which incorporates in situ vitrification (ISV) is the most
         protective alternative (in terms of overall protection of human health and the environment)
         because the site contaminants will be destroyed permanently and rendered harmless applying
         this technology on site. Landfarming soils contaminated with xylene and toluene provides an
         extra measure of protection by reducing the levels of these hydrocarbons through biological
         degradation and volatilization. The long-term effectiveness criteria would be achieved and
         health risks would be reduced substantially.  The ISV process is permanent and irreversible
         and best meets the criterion of reduction of toxicity, mobility, or volume through treatment.'
         Thus, the SARA (Superfund Amendments and Reauthorization Act) preference for  innovative
         permanent treatment technologies is met. The Geosafe ISV process is an innovative
         technology that provides a permanent treatment remedy.  Wastes are permanently destroyed
         with high destruction removal efficiencies. Through permanent treatment, the use of ISV will
         result in residual carcinogenic risks of 10'6 based on continued industrial use of the site  The
         selected alternative would exceed all ARARs. Note that a waiver for the relevant and
         appropriate LDRs (Land Disposal Restrictions) during staging of the waste materials prior to
         treatment would be required. Upon completion of treatment, LDR requirements would be met
         The ISV process would equal or exceed the destruction and removal.efficiency of any other
         treatment process, including incineration.  Contaminants removed by the off-gas treatment
         system are subject to treatment in a subsequent ISV melt, thus increasing the destruction and
         removal efficiency (DRE).  Treatability studies for ISV showed removal efficiencies of
         between 99.9997 and 99.99995 percent of all organic contaminants of concern "considered
        together," and, in particular, is expected to destroy or remove 99.9999 percent of dipxins.
        RAA-4, although using an innovative technology, is the most readily implemented overall
        The processing  of contaminated materials below grade is inherently safer than handling and
        treating  materials above ground.  Unlike the availability of an off-site incinerator, there is no
        facility problem associated with ISV. This is the only alternative with the potential  to
        reembody the former evaporation in place," which would substantially minimize materials
        handling concerns,  such as dust generation. When considering these benefits, the ISV'process
        is safer than competing treatment processes for occupational, public, and environmental
        exposure risk. In addition, the total cost of ISV compared favorably with the total costs of
        competing treatments. Finally, ISV has the potential to enhance ground water remediation by
        removing and treating possible source areas.
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

"      Critical fluid extraction was eliminated because the technology is primarily applicable
       to high-oil-content waste.              .        -
•      Oxidation was eliminated because of problems with incomplete oxidation and reagent
       consumption byproducts.  This technology also was eliminated as a result of limited
       test data, and reagent delivery and recovery problems.
1120
                                             -4-

-------
       Pyrolysis was eliminated becauseof limited test data.        ;
       Vitrification (electric pyrolyzerjv/as eliminated because of limited test data.
       Molten glass was eliminated because of limited test data.     j
       Molten salt was eliminated because of limited test data.                         .
       In situ biodegradation was eliminated because the effectiveness of the technology is
       questionable  given the existence of multiple sources of TCL chemicals, heterogeneous
       geology, and the presence of inhibitory heavy metals and pesticides. Given the
       difficulty in effectively delivering the materials and controlluiig the overall process in
       soils with substantial TCL chemical concentration variances, in situ biodegradation is
       not well suited to the site.                                  |                   •
•      Solid phase biodegradation was eliminated due to the relative resistance of dioxin,   •
       ehlordane, and other pesticides to biodegradation.  The process currently is in a
       developmental stage and the majority of tests have been perfornwjd only at bench
       scale.  Full-scale implementation of this process is, therefore, not feasible at this time.
•      In situ vacuum extraction was eliminated because the technology is not applicable UK
       the indicator chemicals in site soils, except for the VOCs and the more volatile BNAs.
•      In situ steam stripping was  eliminated because the increased  costs of this technology
       would not provide increased effectiveness as compared to vacuum extraction.
•      On-site chemical extraction (BEST process) was eliminated because the current policy
       of the company that developed the technology (Resource Conservation Company) does
       not allow treatability bench-scale testing of dioxin containing materials exceeding 1
       ppb and treatability testing is necessary to evaluate the attainment of treatment goals.
•      Low-temperature thermal stripping was eliminated because the ttschnology is not
       applicable to the indicator chemicals in site soils, except for the VOCs and  the more
       volatile BNAs.  "
•      Soil, washing was eliminated because this technology is not capable of addressing the
       very fine particle size range found at the site, thus precluding the treatment of the
       waste sludge material.  Additionally,  soil washing as applied to  soils containing
,  ,     pesticides  and dioxin would not be effective and probably  would be applied as a
       volume-reduction technology concentrating the soil fines for further processing by a
       second technology.                '                        j           .
•      Slurry phase biodegradation was eliminated because of the relative
       nonbiodegradability of dioxin, ehlordane, DDT and other pesticides in site soils.  In
       addition, full-scale treatment applications are limited.
•       White rot fungus -was  eliminated because the technology has not been developed to the
       point where  an assessment  of large-scale feasibility is possible.
•      In situ soil flushing was eliminated because of limited test data gind reagent delivery •
        and recovery problems.                                                        ,
•      . Reduction (iron, zinc, aluminum metal powders) was eliminated because of limited test
        data and reagent delivery and recovery problems.

Innovative technologies eliminated during the screening of the three  Criteria include the
following:   ,                                                   .

•      None                                         -    ~      ;   •             '

innovative technologies eliminated during the detailed analysis include tide following:

 •      Glycolate dechlorination (APEG process)  was eliminated because the alternative that
        includes this technology, RAA-5, while it provides high overall effectiveness, costs
        more than the selected alternative. The cost of the APEG treatment is higher than that
                                        -5-
                                                                                     1121

-------
               of any other alternative evaluated during the detailed analysis of remedial action
               alternatives.  The effectiveness of this technology in treating some herbicides has not
               been confirmed, and treatment of material with high concentrations of herbicides might
               require off-site incineration. Although the probability of traffic accidents and spills is
               small,  such incidents potentially could involve a large population and unknown
               environmental risks. APEG treatment residuals could require a delisting step prior to
               remediation.  Finally dust generation associated with crushing the oversized materials
               to 4-inch size, as required by the APEG process, poses potential short-term risks to
               workers.                                                 ,     -
11.
12.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 •which criterion? Which of the criteria supported the use of a standard technology?

 Long-term effectiveness and permanence, implementability, and reduction of toxicity, mobility,
 or volume were weighted most heavily in selecting the technology. The in situ vitrification
 process ranks highest in terms of reducing toxicity, mobility, and volume through thermal
 reduction of all organic contaminants. ISV ranks highest in terms of long-term effectiveness
 and permanence since there would be no residuals after treatment. Problems with
 implementability were identified for all the alternatives that were subjected to detailed analysis
 except RAA-4.  ISV is implementable, the required equipment and support services are
 available, treatability studies have shown it to be technically feasible at the site, and, it would
 be the easiest to implement.


 What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level
(ppb)*
ARAR or Other
Basis
Carcinogens
4,4' ,-DichlorodiphenyIdichloroethane
4,4' ,-Dichlorodiphenyldichloroethene
4,4',-Dichlorodiphenyltrichloroethane
Alpha-Chlordane
Gamma-Chlordane
Heptachlor
Tetrachlorodibenzodioxin (Total)
Hexachlorobenzene
Trichloroethene
Tetrachloroethene
26,000
19,000
19,000
7,000
7,000
2,000
20
7,000
103,000
22,000
Risk .
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
  1122
•_*>;
                                           1  -6-

-------
               'Cleanup levels are for soils only; no cleanup levels were developed for waste sludges.
               For carcinogens, an excess upper bound individual lifetime risk of between 10"" to 10"*
               was acceptable.                                          ;

                    "                 ''         "                   ••'' '   !•'•   '    •'           •
73. !   Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?        ^ •...                   •;

       Innovative technologies eliminated because of cleanup goals include:!

   '    •,      None      -•        ••              ••","•,.•'

       Standard technologies eliminated because of cleanup goals include:

       ' •      None   '•        •   .     -            .       •   ,     -  •  •!       •'-..-.
                                  1 '  "       - .  ' ,      •         '        '•          '            '

14.    Were treatability studies conducted on the innovative technology or standard technology?


       Treatability studies were conducted on the following standard technologies:
       -'                      •    -           ,                •          "j. *"•'•,.'
                              • "            "      •              ""       i
       -• •     None'   .             •          '                  .      -j  ' '   . '               .

       Treatability studies were completed on the following innovative technologies
                                                                       j  '    ,    . •        '   - •
        •      Treatability studies were conducted for ISV. The tests performed on site media
               demonstrated that destruction and removal efficiencies in the range of 99.9997 to
               99.99995 percent can be achieved for all site contaminants including dioxins.
        •      Treatability studies were performed  on glycolate dechlorinatibn (APEG process). The
               tests performed on soils and sludges showed a destruction and removal efficiency of
               99.96 percent for dioxin.  Substantial reductions in the level of other highly
               chlorinated compounds, such as pesticides, also were observed. The effectiveness of
               glycolate dechlorination in treating some herbicides has not been  confirmed, and
               treatment of material with high concentrations of herbicides might require off-site
               incineration.
 75.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare,the alternatives:

             On-site vs. Off-site treatment


 76.     How are measures compared?
.  t              .            -                      .        ,             | ' '   .
        On-site vs. off-site treatment is discussed particularly in comparing RAA-4 (ISV) and
        RAA-5 (APEG).  The APEG process would require materials to be trailsported off site for
      -  incineration possibly posing risks during handling and transportation:! less handling and no offr
        site transport is required for ISV.                         c       !
                                               -7-
1123

-------
  17.
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?

Technical considerations were not primary in selecting the chosen alternative.  Because of the
existence of multiple sources of TCL chemicals, the site's heterogeneous geology, and the
presence of inhibitory heavy metals and pesticides on site, the effectiveness of in situ
biodegradation was considered questionable.  Additionally, soil washing was eliminated
because it would be inappropriate for the  very fine particle size range found at the site, and
also is not effective for soils containing pesticides and dioxin.
1124
                                              -8-

-------
                              Advanced Micro Devices 901
                   (combined with Signetics and TRW Microwave)
                                   Sunnyvale, California
                                         Region 9
 GENERAL SITE INFORMATION
 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Soil (mg/kg)

        Dichlorobenzene (DCB)       242
        Trichloroethene  (TCE)        80
        Tetrachloroethene (PCE)       35
        Dichloroethene               0.072
2.     What volume of material is to be
       remediated?,

       The volume of material to be remediated
       .included:

       •      37 cubic yards of soil
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
10/84
6/86
3/91
9/91
             Background
                '-•V       '.   •'
PRP-lead         i
PRPs:  Advanced Micro,Devices
FS prepared by: Harding Lawson
       Associates, Engineering-
       Science, Inc.,   Emcon
       Associates, Weiss Associates
3.      What type of site is this?                                ..        .•
                                                                 •   ,1          •

       Electrical Equipment.  A semiconductor manufacturing facility located in an industrial park
       surrounded by, commerciaVlight industrial and residential areas,      i
TECHNOLOGY SELECTION
                       .       ' f     .,'"..„,',,    •--,'.'.
4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Thermal treatment:    Incineration
       Disposal:             Disposal (off-site)
                                           -1-
                                   1125

-------
5,     Was an innovative technology considered in the FS?  If so, which technology?

       Ii.- ' /alive technologies considered during the identification and screening of technically
       feasible technologies were:                                                    .

       Biological treatment:   Biodegradation (enhanced, in  situ)
       Chemical treatment:    Soil flushing
       Physical treatment:     Vacuum extraction
6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.

                Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-4
RAA-5
RAA-6
Innovative Technology
Soil flushing
Vacuum extraction
Heated air-assisted vacuum extraction
Steam-assisted vacuum extraction
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$2,828,000
$2,829,000
$2,931,000
$3,547,000
7.      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs Thai Include Standard Technologies
                           (selected remedial! alternative is in bold)
Alternative
RAA-1
RAA-3
RAA-7
*
Standard Technology
No action >
Soil aeration
Excavation/ofT-site disposal/
incineration
Estimated Costs
3 Criteria
N/A
N/A :
N/A •
9 Criteria
$1,515,000
$2,700,000
$2,651,000
                                                                                                         L 1


                                                                                                        j
 1126
                                             -2-

-------
 8.     If a standard technology was chosen, why?                        !

        RAA-7 was selected because it offers the greatest protection of human health and the
        environment in a reasonable time frame. Furthermore, it is the only ipmedial alternative that
        complies with all pertinent ARARs in a reasonable amount of time.  It provides the greatest
        reduction in toxicity, mobility, and volume of soil contaminants through excavation and
        incineration. This alternative provides the greatest long-term effectiveness because the soil
        contaminants are removed from the site and eventually destroyed at aik off-site treatment
        facility. Removal prevents the soil from acting as future source of ground water
        contamination and prevents soil contaminants from volatilizing.
 9.
 If an innovative technology was chosen, why?

 An innovative technology was not selected.
•10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?                                           I
                             ".          '           -             • !         •   •       ' '
 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages: during the initial screening; during the screening of the three criteria of
 effectiveness, implementability, and cost; or during the detailed evaluation.

 Innovative technologies eliminated during the initial screening include the following:

 •      Enhanced biodegradation (ex situ) was eliminated because it wfould not be an effective
        technology for the site since chlorinated aliphatic hydrocarbons, are; volatile at ambient
        temperature.
 »      In situ biodegradation was eliminated because the anaerobic process' for chlorinated
        aliphatic hydrocarbons results in the accumulation of undesirable end products (vinyl
        chloride) and the aerobic process is less effective for highly halogenated compounds
        such as those in the study area.

Innovative technologies eliminated during the screening of the three criteria include the
following:                 .

A three-criteria screening was riot conducted.                        i
•••''•   , ' .         ...      '    '             "           '     h  -
Innovative technologies eliminated during the detailed analysis include the following:

•      Soil flushing was eliminated because it might not effectively reinove PCE and DCB
       from the soil.                                            ,  t
»       Vacuum extraction was eliminated because it would not effectively eliminate PCE and
       DCB since they are tightly bound to the soil.
•      Heated air-assisted vacuum extraction was eliminated  because ii would take hundreds
       of years to reach cleanup levels given the physical properties of DCB and PCE.
       Furthermore, this is  an evolving technology and pilot tests at the site would be needed
       to determine its effectiveness. There was concern that the techiiology_would remove
       volatile organics but might leave elevated  levels of DCB in the soil
                                             -3-
                                                                                 1127

-------
                                                                                                         n
              Steam-assisted vacuum extraction was eliminated because it would take hundreds of
              years to reach cleanup levels given the physical properties of DCB and PCE.
              Furthermore, this technology is evolving and pilot tests at the site would be needed to
              determine its effectiveness. There was concern that it would remove volatile organics
              but might leave elevated levels of DGB in the soil.             ,
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       Protection of human health and the environment and compliance with ARARs were the criteria
       weighted most heavily in selecting a remedial alternative. The selected remedy is the only
       alternative that would remove site contaminants permanently in a reasonable amount of time.

       Soil flushing, soil aeration, vacuum extraction, heat-assisted vacuum extraction, and steam-
       assisted vacuum extraction were eliminated because their compliance with cleanup level was
       questionable. Moreover, if they could reach cleanup levels, it would require hundred of years.


12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
                    Contaminant
Cleanup Level (ppm)    ARAR or Other Basis
                Carcinogens
                Total VOCs
          1
RWQCB*
               'Since there are no ARARs for soil, target cleanup levels were based on guidance
               provided by the Regional Water Quality Control Board (RWQCB) and the Department
               of Health Services (DHS) for the protection of ground water from leaching chemical-
               bearing soils.
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       "      Soil flushing                                                        •
       »      Vacuum extraction                     .                              .
       B      Hot air-assisted vacuum extraction
       "      Steam-assisted vacuum extraction       .        ,                  ,         .

       Standard technologies eliminated because of cleanup goals include:

       "      None
1128
                                              -4-

-------
77.
14.     Were treatability studies conducted on the innovative technology or standard technology?
   1              .                             -           ,      ,.,.,.:•'•
   •'•-.''       .     '      -       '          ,     .     ' '    .        '  ! 1  •  "
                                          \          "-                   IN           '
        Treatability studies  were not conducted.                          •!.-'.'



75.     What measures/criteria were used to compare alternatives?


        The following measures were used to compare the alternatives:
             Percentage risk reduction
             Time to design/construct/operate
76.    How are.measures compared?                                 '}.•''

       RAA-7 was preferred because it will immediately prevent the soil from acting as a source of
       ground water contamination and will prevent soil contaminants from volatilizing and
       eventually migrating into confined spaces of dwellings at the surface.  Other alternatives were
       not preferred either because their effectiveness was uncertain or they would require hundreds
       of years to reach cleanup levels.                                  !                -
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?
         '   .  '      -     '  '    •  :    '  ,  VV
Technical considerations were not primary in selecting a remedial alternative.
                                             -5-
                                                                                           1129

-------
                                   Atlas Asbestos Mine

                                    Coalinga, California
                                         Region 9
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       .contaminants were:

       Tailings and waste ore (mg/kg)

       Asbestos             1,000,000

       Soil/Sediment (mg/kg)

       Asbestos             60,000
2.     What volume of material is to be
       remediated?

       The volume of material to be remediated
       included:
                                                         Site History
                                            NPL Proposed:
                                            NPL Final:
                                            FS:
                                            ROD:
N/A
9/84
3/90
2/14/91
                                                         Background

                                            EPA Fund-lead
                                            PRPs:  The Atlas Minerals Division of
                                                   the Atlas Corporation, Vinnell
                                             ' '     Mining and Minerals
                                                   Corporation, Wheeler Properties,
                                                   Inc., California Mineral Corp;,
                                                   The U.S. Bureau of Land
                                                   Management
                                            FS  prepared by: Woodward-Clyde  .
                                                   Consultants
              3 million cubic yards of asbestos
              ore, asbestos mine and mill tailings, and contaminated soil
3.     Wliat type of site is this?

       Mining.  An inactive asbestos mine located in a rural area.
TECHNOLOGY SELECTION      "

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
       Access restriction:
       Containment:
                     Fencing, personal protective wear, suspend private development
                     Vegetative cover, capping (soil, asphalt, soil-cement, gunite, RCRA),
                     containerization,  sediment retention dams
Chemical treatment:  • Fixation (plant processing, pressure grouting, deep soil mixing, area
                     mixing)                            ;
1130
                                             -i-

-------
        Physical treatment:
        Disposal:
Slope stabilization, reprocessing, dust suppression
Disposal (off-site)                          !
        Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Thermal treatment:     In situ vitrification, plant processing vitrification
6.      What was the cost estimate for the innovative technology?
                          •           '                   *-        •   -,  • 4-<.             , .     - •
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. In this  case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.  No innovative technologies wen; incorporated into
        RAAs.                                           -               !
7.
How did the cost(s) compare to standard technologies? . „
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold) [
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
RAA-5
RAA-6
RAA-7
RAA-8
RAA-9
Standard Technology
No action ,
Access restrictions
Stream diversion/sediment trapping
dams/access restrictions/revegetation
Stabilization/stream diversion/sediment
trapping dams/access restrictions/
revegetation
. Capping/access restrictions/stream
diversion
Chemical fixation/access restrictions/
stream diversion
Off-site disposal '
Construction of a dam ,
Enlarge pond basin
"»•«.
Estimated Costs
3 Criteria
N/A
N/A
. , N/A -
N/A
N/A
N/A
N/A
N/A
N/A
9 Criteria
$833,200
$561,200
$4,228,900
$9,401,800
$14,620,500
$103,473,200
$234,326,000
,$16,500,000
eliminated
                                              -2-
                                                              1131

-------
S.     If a standard technology was chosen, why?

       RAA-3 was chosen because it protects human health and the environment by reducing site risk
       from inhalation of asbestos-containing air at the mine and nearby areas and by restricting
       access to the mine area. The stream diversion and sediment retention dams minimizes the
       release of asbestos from the mine into -local creeks. RAA-3 does not disturb the protective
       crust on the stock piles to a great extent.  The revegetative element of this alternative, if     .
       successful, will help stabilize disturbed areas, minimize erosion, and reduce future releases of
       contaminants. Minor, regrading improves surface drainage and increases the Stability of the  .
       mines  and stockpile areas.  RAA-3 provides long-term effectiveness since it reduces asbestos
       release to air and surface water and restricts access to those areas where asbestos has been
       transported. This alternative minimizes short-term risk and can be implemented in the shortest
       amount of time.  The selected remedy is cost-effective because it provides, overall effectiveness
       commensurate to its cost.
9.   .  If an innovative technology was chosen, why?

       An innovative technology was not selected.

                                                             ;  '        .'..-.         i
JO.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                 ,
                                                                  ••'''•'               •
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      In situ vitrification was eliminated because its technical implementability for asbestos-
               containing waste ore and mill tailings is open to question given their relatively high
               proportion of non-asbestos minerals.  In addition, vitrification is not implementable
               because of the extremely high volume and highly variable depth of the tailings
               materials, the large areas of rugged and possibly unstable terrain of the site that would
               potentially be inaccessible to the nominally mobile yet ponderous vitrification
               equipment, and  the extremely high electric energy demands of the vitrification
               equipment at a site remote from sources of power.
       •      Plant-processing vitrification was eliminated for the same reasons as in situ
               vitrification.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                   '                                                       ,

       •      None                                                   '             - , •  ••

       Innovative technologies eliminated during the detailed analysis include the following:

       »      None                 '                ,                         •'•-..;
                                                                                            *
                                            ' "  •        .            -               '         ' . •
1132                          .        ;.   .   •  :  ;•.   .  '••  -/    "   •    •      '.   ....
                 -           '                 • -3-     '  "  ' '                     ••'•-..-

-------
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion? Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedial alternative were protection to human
       health and the environment and cost.  RAA-3 provides as much protection as cither alternatives
       but at a much lower cost.
72.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
   .                   .           '             '      •      .            :r      • •  .      .
       No cleanup levels were established.
13.    Was the innovative technology eliminated because of the cleanup goah?  Could the standard
       technology meet the cleanup goals?                .               i       ,

       Innovative technologies eliminated because of cleanup goals include:

       •      None

       Standard technologies eliminated because of cleanup goals include:

     .  •      Construction of a dam
14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.

      _                 '                 .              _ /   •            :.*'_,
75.    What measures/criteria were used to compare alternatives?         j
                          ..'         •     '    """    '   •       •     "     '!•
       The following measures were used to compare the alternatives:
                                                                      -i,
            Cost/unit risk
            Time to design/construct/operate                            j
  .   ,  -    Preference for containment (vs. treatment)                    |
            Impact on nearby populations                               i


16.    How are measures compared?                    ,               ;                   •
                                          "...     •     •     .'        i        ,           . •  '
       Implementation time was a factor in selecting an alternative.  The chosen alternative only takes
       4 months to implement, while RAA-6 and RAA-7 would have taken 4 and 10 years,
       respectively.  The selected remedy was chosen because it is cost effective  since its cost is one-
       half that of RAA-4 and one-third the cost of RAA-5; RAA-4 and RAA-5 offer only a
       comparable level of public health and environmental protection.  Treatment was not possible
       because there is currently no known cost-effective, permanent treatment that would control the
                                                                                         1133

-------
         release of asbestos from soil at the site.  Fixation was considered in RAA-6; however, it was
         eliminated because of difficulties associated with implementation and high cost.


  17.    What technical considerations were factors in selecting a remedy? Were technical
      •   considerations primary in the selection of the remedy?       -

         No technical considerations were primary in selecting a remedial alternative.
1134
                                             -5-

-------
                                  FMC (Fresno Plant)

                                    Fresno, California
                                         Region 9
GENERAL SITE INFORMATION
What were the principal contaminants,
contaminant levels, and
this feasibility study?

media addressed in


Maximum concentrations of principal
contaminants were:

Soil (mg/kg)

Aldrin -
Dieldrin
Toxaphene
DDT"
Chlordane
Endosulfans*
EDB
Heptachlor
Disyston
Phorate
Dimethoate

*


170
100
15,000
1,700
8.7.
3.000 • • , .'
6.7
',.-', '\
Site History
••''.- 1
NPL Proposed: ! 10/15/84
NPL Dropped: 10/4/89
FS: 5/91
ROD: 6/91
' ' 1 ' • • • •
Background
1 ' ' '
PRP-lead
PRPs: FMC ' 1 ' ' .
FS prepared by: Bechtel
Environmental, Inc.
•;1 ' • '
i
1.3 '"- . , •• '' ' ••
280 j
2,000 x
24 . • ••''-. •'•- ' ;.. .. . , :>
       "includes DDE and ODD
       Includes endosulfan I and endosulfan
2.      What volume of material is to be remediated?

       The volume of material to be remediated included:

       • '     19,000 cubic yards of soil               :

            '  '   - •         '              •                   ' .

3.      What type of site is this?

       Agricultural Chemicals.  A pesticide formulation facility located in an urban area.

                                                          »      .   'i -'-_...

TECHNOLOGY SELECTION                 '                        i         -    '
                                                            '        'i  '   '           '  '
            ~                  .        .   .     '            ,          i.
4.      What standard .technologies were considered for selection in this FS? \
                J                     '        ''"".-'         ' ! •      '"

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:
                                                                                     1135

-------
       Access restriction:
       Containment:
       Chemical treatment:
       Thermal treatment:
       Disposal:
Deed restrictions       .
Capping (clay, asphalt, soil, multimedia, soil cement/asphalt)
Stabilizatior 'fixation, enhanced photodegradation, hydrolysis
Incineration trotary kiln, circulating bed, infrared)
Excavation, RCRA landfill (on-site, off-site)
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Enhanced biodegradation
        Phys/Chem treatment:  Soil washing (B.E.S.T., MTARRI AEMC), oxidation/reduction,
  *•                          enzymatic degradation, KPEG dechlorination, soil flushing, solvent
                             extraction
        Thermal treatment:     Vitrification, wet air oxidation ,  .
6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
    ,  implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
       estimated costs are then recalculated during an evaluation based on nine criteria established by
       theNCP.                                           :

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-6
RAA-7
RAA-8
Innovative Technology
Excavation/soil washing/stabilization/
capping/institutional controls
Excavation/solvent extraction/ . .
institutional controls/capping
Excavation/vitrification/capping/
institutional controls
Estimated Costs
3 Criteria
$7,700,000
$12,300,000
$19,900,000
9 Criteria
$10,103,654
$15,660,298
$25,649,695
                                                                           7).
1136
                                             -2-

-------
7.      How did the cost(s) compare to standard technologies?             ,

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-4
i.
RAA-5
RAA-9
Standard Technology
No action
Institutional controls
Institutional controls/capping
Excavation/on-site RCRA landfill/
capping/institutional controls
Excavation/stabilization/institutional
controls/capping
On-site incineration/capping/
institutional controls
I Estimated Costs
3 Criteria
$0
$95,000
$1,300,000
$7,600,000
' l
$4,-[00,000
$21,ikOO,,000
• r
9 Criteria
$0
$93,192
$1,498,027
$9,747,198
$5,806,139
$27,721,216
8.     If a standard technology was chosen, why?

       Stabilization and capping were selected for residuals.
       If an innovative technology was chosen, why?

       RAA-6 was selected because it will be protective of human health arid the environment.  This
       alternative addresses the threat of exposure to contaminated soil in seiveral ways. First, by
       capping the site and implementing institutional controls, .the threat caused by ingestion and
       direct contact is removed. By eliminating the soil exposure pathway,! the: remedy attains a
       carcinogenic risk of 10"* and a noncarcinogenic Hazard Index of less than one. By excavating
       and treating surface soil to risk-based cleanup levels, the remedy also provides long-term
       protection from ingestion and direct contact with soil, should capping ami institutional controls
       fail.  By implementing institutional control, capping, and the associated {(round water remedy,
       the threat of exposure to deep subsurface soil that could potentially migrate to ground water
       also is addressed.  The selected remedy uses soil washing and stabilization treatment
       technologies to reduce the volume of contaminated soil. Additionally, a cap will be placed
       over the site to reduce the mobility of soil contaminants left in place,  It offers a high level of
       long-term effectiveness since it achieves contaminant destruction, complies with ARARs, and
       is cost-effective.                               ,               ,'.!
                                              -3-
1137

-------
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?                                          ,                                     \

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the  following:

         •      Wet air oxidation was eliminated because it requires an aqueous media, therefore, soil
                would have to be mixed with large amounts of water to form a pumpable slurry that
                could be fed into the reactor. The resulting waste stream would be far more difficult
                to handle than the soil. In addition, the water would ultimately have to.be separated
                from the soil and might require further treatment prior to disposal.  Second, the
                quantity of inert  solids, such as sand,, in the soil might cause an erosion .problem in the
                oxidation of a conventional wet air oxidation system.  These systems are not designed
                to handle waste containing large quantities of inert solids such as sands. Finally, the
                concentrations of oxidizable  organics in the soil are tod low to be economically treated
                with this process.     .
         «      Enhanced biodegradation was eliminated because the organochlorine pesticides are
                very resistant to biodegradation, as well as being toxic to microorganisms.  While they
                are susceptible to partial transformation, most of them are not mineralized.  There
                appears to be some limited potential for dechlorination  under anaerobic conditions, and
                oxidative degradation under aerobic conditions.  Furthermore, while there has been
                some success  with the biodegradation of specific pesticides  in the laboratory, it is            ^pr---,
             .   unknown  whether biodegradation  would be effective in a soil that contains a variety of             V
                pesticides at a wide range of concentrations. It would be difficult to develop and
                optimize a biodegradation treatment system that would effectively degrade all of the
                site contaminants. In addition, compounds with a high octanol-water partition
                coefficient tend to sorb onto soils and might remain unavailable to  microorganisms.
                Under such conditions, the time needed for effective degradation is uncertain.
        •       Oxidation was eliminated because it has not yet been proved to be effective  for the
                range of site contaminants. Furthermore, oxidizing agents are nonspecific and. might
                oxidize all organics and inorganics including those that comprise the soil, reducing
                natural organic matter in the soil and resulting in decreased  sorption capacity for some
                organics.  Ozonation (an oxidizing agent) has been shown to transform some
                pesticides into other compounds that are more resistant to oxidation. In addition,
                oxygenated degradation products are expected to be more polar and therefore more
                mobile than the parent compound. Byproducts might be more toxic than the parent
               compound.
        •      Enzymatic degradation was eliminated because the enzymes necessary for the
               breakdown of organophosphorus pesticides are not widely available. Furthermore,
               producing specialized enzymes to  address the range of pesticides on site would not be
               feasible.                       ,                                    .
        •      Hydrolysis was eliminated because it would not be effective and it is unproved for
               halogenated pesticides.
        •      KPEG  dechlorination was eliminated because vendors and researchers expressed
               uncertainty about its ability to detoxify chlorinated cyclic alphatics,  such as dieldrin          j|i,
               and aldrin.  This technology would not effectively treat nonchlorinated pesticides (eg.,       111)
               organophosphorus, carbamate pesticides) or volatile organics found in the soil.  Other'        >
               technical concerns associated with the KPEG process include washing the soil after the

1138
                                              -4-                    .           '            •

-------
m
               treatment and recovering the reagent at the end of the process!  Galston Research
               Corp. has a newly emerging technology process which incorporates the use of DMSO
               into the KPEG process.   However, there is concern that DMSO is dangerous to handle
               and might decompose to H2S under increased temperature conditions.
        •      In situ vitrification for subsurface soil was eliminated because the contaminants are
               located too deep for the process which is capable of treating soil only up to 30 to 50
               feet. The soil also is located too close to the water table and the high moisture content
               would greatly increase the electric power requirement.        |
       .'•      Soil flushing for subsurface soil was eliminatedbecause it is ain emerging technology
              (which has not been tested in full-scale studies.  The permeability of the site soils (10"4
               to 10"5 cm/sec) is not optimal for this process since permeabilities of 10"3cm/sec are
              'best.  Additionally, site contaminants are at best sparingly soluble and adsorb very
               strongly to  the soil matrix.  Finally, there would be a risk that the flushing solution
               might mobilize the contaminants and transport them to previously clean soils or
               aquifers..                  '                                     ,
  '                                                "           ,         "  J
        Innovative technologies eliminated during the screening of the three ciriteria include the
        following:

        •      None

        Innovative technologies eliminated during the detailed analysis include the following:
 ,'      .  : '  "'    "         '      .        .          ....'•       i    :     i
        •      Solvent extraction was eliminated because of the high cost associated with its
               implementation, the required equipment was not immediately available, and off-site
               transportation might pose a threat in the event of an accident.
        •      In situ vitrification was eliminated because of the high cost associated with its
               implementation, it would only be available through one vendor, arid the technology has
               not been commercially demonstrated.

           .  .         ,  '      •            •               -               .'• /        •
11.     Which of the nine criteria were weighted most heavily in selecting the  technology? Did failure
        to meet one of the nine criteria result in the  elimination of the innovative technology?  If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        The criteria weighted most heavily in selecting a remedial  alternative were protection of
        human health and the environment, long-term effectiveness, and cost.  [The selected remedy
        provided greater protection and long-term effectiveness than RAA-1, Ep\A-2, RAA-3, and
        RAA-4.   Of the options that  would provide  long-term effectiveness and protection (RAA-6,
        RAA-7, RAA-8, and RAA-9), the chosen alternative was the least expensive.
   '  .        /'.•'•     •           •''.'••_._       '               . •'': . •    •
        Solvent extraction and vitrification were eliminated due to  their high cost and difficulties in
        implementation.
                                                      **

-------
   12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
          ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
Aldrin
Dieldrin
Toxaphene
DDT"
Chlordane ,
EDB
Heptachlor
21.8
23.2
337
1,092 ,
285
2.2 .
82.6
Risk1
Risk
Risk
Risk
Risk
Risk
Risk
Noncarcinogens .
Aldrinc .
Dieldrin
DDT"
Chlordane
Endosulfansd
Heptachlor
Disyston
Phorate
Difnethoate
2.4
•4
43.2
4.8
4.0
40
3.2
8
16
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
Risk
                 "Health-based cleanup levels were derived based on an excess carcinogenic risk of 10"4
                 and noncarcinogenic health-based cleanup levels were based on a hazard index of 1.
                 The selected health-based cleanup level is the most conservative value.
                 'Includes DDE and DDD.
                 "Carcinogenic and noncarcinogenic health-based cleanup levels were developed in the
                 ROD for five chemicals.                      .'    ''.                      .
                 Including endosulfan I and endosulfan H.
  13.
Was the innovative 'technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None                                              .•'.'".
1140
                                               -6-
                                                                                                           •(*-..

-------
        Standard technologies eliminated because of cleanup goals include:

     ^.  •'     None           '  ,   •-.-     '      '•  ''   '•"   -       ;   '  "I" .......  '• '•'...
                                      .  .'    •          '.   •-          •• i"
           . .   •   •      .        •'   ••   '        •.       •;_•-.-    -  l:     •••" •     -   .  '.
 14.    Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.                            j

              '           "  •"     '-"     •  •     "'"•  ;   "•   '       .     \  -   •  •
 15.    What measures/criteria were used to compare alternatives?          }

        The following measures were used to compare the alternatives:

        r       Cost-effectiveness
             ,  Preference for treatment (vs. containment)                   1
               Impact on nearby populations
  _.--••    Waste left in place/institutional control                      ii
                                           -"•"''                 .i-         '

 16.     How are measures compared?                                     , I -
                                                                  "•--•''           '
        RAA-2 was not selected because it offered a low level of protection since there is no
        guarantee that institutional controls will be maintained over time and it: would not meet
        ARARs. RAA-3 and RAA-4 were not preferred because they did not "incorporate treatment
        and would not be as protective.  RAA-5 was not preferred because it would not provide a
        greater reduction in contaminant tbxicity, mobility, and Volume than the  chosen alternative.
        RAA- 7, RAA-8, and RAA-9 were not selected because of their high cost. EPA felt that it
        could not justify the high cost of these alternatives given some soil contaminants would still be
        left in place.  Furthermore,  there was some concern over the implementability of RAA-7 and
        RAA-8.  RAA-7 would not have been immediately available though it was expected some
        time in 1992, and RAA-8 is only available through one vendor. The state was concerned
        about residual solvent associated with RAA-7 which could increase the; mpbjlity of remaining
        site contaminants. Finally, it was anticipated that the community would have objected to
        RAA-9.                                                                 ,


17.      What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
                                                    •  '        ,         i-j'
       Technical considerations were not primary in selecting a remedial alternative.  The site's low
       soil permeability, however, precluded the use of soil flushing.
                                             -7.

-------
                                 Hassayampa Landfill

                                Maricopa County, Arizona
                                        Region 9
GENERAL SITE INFORMATION

1.      What were the principal, contaminants,
       contaminant levels, and met
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Waste/soil (rag/kg)

       o,p-Dichlorobenzene
       1,1-Dichloroethane
       Benzene
       1,1-Dichloroethene
       Dichloromethane
       1,2-Dichloropropane
       Total xylenes
       Acetone
       Ethylbenzene
       Toluene
       Methyl ethyl ketone
       Tetrachloroethene (PCE)
       1,1,1-TrichIoroethane
       1,1,2-Trichloroethane
       Trichloroethene (TCE)
       Trichlorotrifluoroethane
linants,

addressed in Site History
NPL Proposed:
ncipal NPL Final:
FS:
ROD:
N/A
7/87
5/92
7/92
Background
97
47 PRP-lead
1 PRPs: N/A
1,630 FS prepared by:
990 Associates, Inc.,
207 and Associates
350
2,540
57 •
510
405
600
23,000
20
590
12,000



Enrol L, Montgomery *& "
Conestoga- Rovers










'}
       What volume of material is to be remediated? .

       The volume of material to be remediated included:

       »      12,670 cubic yards of waste
       •      91,400 cubic yards of soil

               *           f ---                  i            •          '      • •  ' •
       What type of site is this?

       Industrial Landfill. The hazardous waste area of an active landfill in a rural area.
                                                                                                   J!
 1142
                                           -1-

-------
TECHNOLOGY SELECTION                                          j
                ,     -                       '         -             ',-!.'          '
                                       -"                               '!      '   :
4.      What standard technologies \vere considered for selection in this FS?


        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                               ",                \
        Access restriction:
        Containment:
        Chemical treatment:
        Thermal treatment:
        Disposal:
Deed restrictions
Capping (RCRA,  soil)                      |
Fixation/stabilization
Incineration (rotary kiln, circulating bed, off site, on site)
Excavation, disposal  at RCRA landfill        ,
-5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Bioremediation (ex situ, in situ)
        Phys/Chem treatment:  Soil washing, soil flushing                 j
        Physical treatment:  '  Soil vapor extraction, steam injection and spjirging
        Thermal treatment:    Vitrification, thermal desorption
 6.      What was the cost estimate for the innovative technology?          !

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
        implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
        estimated costs are then recalculated during an evaluation based on mine criteria established by
        the NCP. RAA designations were changed in the Proposed Plan and! ROD and die new
        designations are presented parenthetically below.           ,        |
                                    /•-..     •               L         /I        >,
                 Cost Estimates for RAAs That Include Innovative Technologies -   .             ••
                            (selected remedial alternative is in bold)   .
Alternative
RAA-4
(RAA-3)
RAA-5
Innovative Technology .
Deed and access restrictions/cap/
removal/soil vapor extraction/ground
water extraction, treatment, and
reinjection
Deed and access restrictions/removal/
soil washing/ground water extraction,
treatment, and reinjection
Estimated Costs
3 Criteria"
$6,100,000
to $'',200,000
• i
I
$4,800,000
to
$8,000,000
9 Criteria
$6,100,000
to
$9,200,000
eliminated
                                              '-2-
                                                                                         1143

-------
Alternative
RAA-7
RAA-8
(RAA-4)
sssssssssssss— =—=
Innovative Technology
Deed and access restrictions/cap/
removal/on-site incineration/soil vapor
extraction/ground water extraction,
treatment, and reinjection
Deed and access restrictions/cap/
removal/soil washing/soil vapor "
extraction/ground water extraction,
treatment, and reinjection
	 —
Estimated Costs
3 Criteria1
$9,900,000
to
$13,100,000
$7,200,000 to
$10,300,000
'"
9 Criteria
eliminated
$7,200,000
to
$10,300,000
         The range of costs is due to the type of ground water treatment to be chosen.


 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
(RAA-2)
RAA-6
Standard Technology
No action
Deed and access restrictions/ground
water extraction, treatment, and
reinjection
Deed and access restrictions/cap/ground
water extraction, treatment, and
reinjection
Deed and access restrictions/cap/
removal/incineration/ground water
extraction, treatment, and reinjection
.
Estimated Costs
3 Criteria8
$0
$3,200,000
to
$6,300,000
$3,700,000 .
to
$6,900,000
$7,600,000
to
$10,700,000
==^==-_=
9 Criteria
$0
eliminated
$3,700,000
to
$6,900,000
eliminated
=^=
        The range of costs is due to the type of ground water treatment to be chosen.

                                             1"                    •

8.      If a standard technology was chosen, why?


        A standard technology was not selected as the primary remedy.  Treatment residuals will be
        capped.
9.      If' an innovative technology was chosen, why?                                  -


       RAA-3 was selected because it will employ soil vapor extraction until soil cleanup levels that
       are protective of ground water quality are met, thereby ensuring that vadose zone contaminants
 1144
                                            -3-

-------
       will not migrate to ground water.  This alternative addresses the threat of ingestion and contact
       with contaminated waste and soil through the use of a cap and access and! deed restrictions.
       The cap also minimizes infiltration and limits the migration of vadose zone contamination to
       ground water.  This alternative complies with all ARARs and is cost effective. The selected
       remedy permanently reduces contaminant volume and mobility through soil vapor extraction
       and treatment, and capping.  No short-term risks are posed by this remedy.  It is easily
       implemented since it relies on demonstrated technologies and proven, effective methods and
       equipment.  .  ;     •
10.    If an innovative technology was not chosen, why not? At what stage \fyds the innovative
       technology eliminated?                                           i.

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                                                       ,  • -.            'i-'   .•
       Innovative technologies eliminated during the initial screening include the following:

       •     In situ bioremediation was eliminated because it would be better suited for low-level
              contamination areas where nutrients might be introduced into the  contaminated matrix
              with infiltrating water. The water can be collected following the introduction of
              nutrients and the production of leachate. This technology would not be readily applied
              to hazardous waste areas in situ.                                          '
       •     Ex situ bioremediation was eliminated because it would only Ibe able to treat a small
            .  portion of the waste targeted for remediation, there is a low probability of success for
              some significant contaminants (1,1,1-TCA,  1,1,2-TCA, TCE,  PCE), waste waters from
              the process would require treatment and/or disposal,  and the desert environment would
              cause extensive evaporation, thus requiring  constant  irrigation,;
       •     Vitrification was eliminated because it has not yet been fully  demonstrated oh a wide
              range of wastes; moreover, the depth of ground water and the extent of ground water
              contamination would drastically increase energy requirements because of the large
              volume of soil required for treatment. This technology would be  more suitable for
              inorganics and metals stabilization where migration through leaching is a concern.
              Vitrification volatilizes VOCs, which necessitates a complex vapor collection system
              and fugitive losses can occur.' Since the site contaminants are mainly organic and
              thermal treatment can be done more cost effectively  through incineration or thermal
              desbrption, vitrification was considered impractical for this application.               '
       •     Thermal desorption was eliminated because it is still in developmental stages, the
              technology would be more expensive than other available technologies, volumes that
              are located over a large number of. small, isolated pits of waste require treatment, and
              collected organics would require further remediation. Furthermore,  fugitive air
              emissions would potentially affect on-site personnel  and off-site areas. Open
              excavation could result in the leaching of contaminated liquids to  the ground water if
              precipitation entered the excavated area and contacted the waste materials or
              contaminated soil.                            .            |'                 .
       •     Steam injection and sparging was eliminated because without a confining layer,
              condensed steam could migrate into the ground water or away from the hazardous
              waste area.  The technology is applicable to depths of 30 feet [(contamination reaches
              to 60 feet), below which high temperatures  are difficult to maintain and condensation
.              of steam might occur.  This would cause infiltration  of the  condensed steam through
                                                                                            1145

-------
77.
        the contaminated zone possibly increasing the level of ground water contamination.
        This factor could make the process difficult to control and monitor. The pressure of
        both a fine-grained and coarse-grained unit in the saturated zone makes injection of
        steam difficult to implement and control ultimate flows.  In addition, construction and
        startup costs of steam injection/ sparging are higher when compared to soil vapor
        extraction due to the requirement for an on-site steam-generating facility.
 •      Soil flushing was eliminated because it could promote contamination of underlying
        ground water.

 Innovative technologies eliminated during the screening of the three criteria include the
 following:

 •      Soil washing as a stand alone technology was eliminated because it would not address
        soil gas contamination. Furthermore, it would not address soil beneath Pit  1 or in
        Special Pit areas and the proposed excavation process might result in the release of
        VOC emissions.

 Innovative technologies eliminated during the detailed analysis include the following:

 •      Soil washing in conjunction with soil vapor extraction was eliminated because it would
        provide only a slightly greater reduction in toxicity, mobility, and volume through
        treatment than the selected remedy and  at a significant increase in cost.


 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion?  Which of the criteria supported the use of a standard technology?

The criteria weighted most heavily in selecting a remedial alternative were protection to human
health and the environment; reduction of contaminant toxicity, mobility, and volume; and cost.
RAA-3 was selected over RAA-1  or RAA-2 because it is more protective since it reduces soil
vapor contamination to levels that protect ground water quality. RAA-4 would have provided
a slight increase in protection of human health and the environment and reduction of toxicity,
mobility, and volume through treatment; however, EPA did not believe these marginal  benefits
were necessary or justified the additional costs.
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?
1146
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
1 , 1 -Dichloroethene
1 ,2-Dichloropropane
Tetrachloroethene
1 , 1 ,2-Trichloroethane
Trichloroethene
140
12
14
60
64
Risk0
Risk
Risk
. Risk
Risk
                                                                                                   O
                                              -5-

-------
... ' •-..'.- ' . .... ' - • •
Contaminant
Noncarcinogens
o,p-Dichlorobenzene
Dichloromethane
Total xylenes
Acetone
Ethylbenzene
Methyl ethyl ketone
1 , 1 , 1 -Trichloroethane
Trichlorotrifluoroethane
Toluenfc
Cleanup Level (mg/kg)
AIIAR or Other Basis

1,500
94
200,000
14,000
14,000
3,400
4,000
4,200,000
20,000 -
Risk
Risk
Risk
, Risk
Risk
Risk
Risk
Risk
Risk
               "Cleanup levels were developed using the results of the human health risk assessment,
               For carcinogens,  an excess upper bound individual lifetime cancer risk of 10"4 to 10"6
               was acceptable.  For noncarcinogens, a Hazard Index"iess thaii or equal to 1.0 was
               acceptable.                                               !
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                \ ' .
             • ' ,                            •                    '         ! "
        Innovative technologies eliminated because of cleanup goals include:

..•-•;     None       •;         '                 '      _ •       .     .;  .'      •.--•''

        Standard technologies eliminated because of cleanup goals include:

        •      Capping
14.    Were treatability studies conducted on the innovative technology or standard technology?
                               '  '             -                     *     I-
       Treatability studies were conducted to evaluate several remedial technologies:  soil washing,
       bioremediation, soil vapor extraction, and thermal desorption.
75.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

              Cost-effectiveness
              Time to design/construct/operate
              Preference for treatment (vs. containment)
                                              -6-
                                                                                          1147

-------
  16.     How are measures compared?                          '

         Of the two soil treatment alternat-    proposed, the selected alternative was preferred because
         it is protective>since waste/soil wiu be treated cost-effectively.  It is the most cost-effective
         option because, although it offers slightly less protection than RAA-4, it also is less expensive.
         RAA-4 would require more construction time because a larger soil vapor extraction system
         would be needed. It also was deemed the least implementable alternative given the excavation
         of waste  and the startup and trail tests involved in a soil washing system.  Capping as a stand-
         alone remedy was not preferred because it would not address waste/soil contaminants.
                     *                     •                              -

  77;    ' What technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection of the remedy?            '

         Technical considerations were not primary in selecting a remedial alternative. The mixture of
         fine- and coarse-grained soil and the lack of a confining layer, however, precluded the use of
         steam injection and sparging.
1148
                                               -7-

-------
                               Indian Bend Wash Area
                                      OU-1,4,5, 6

                     Scottsdale and Tempe, Maricopa County, Arizona
                                         Region 9
GENERAL SITE INFORMATION

.1.     What, were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Vadose Zone1 mg/kg

       Trichloroethylene     10
       Tetrachloroethene     4.9
       1,1-Dichloroethene    1.6
       Trichloroethane        0.14,
       1,1,1-Chloroform      0.6
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
                                                                  9/82
                                                                  9/1/83
                                                                  4/91
                                                                  9/12/91
                                                                Background
                                                                     -1
                                                   PRP-lead
                                                   PRPs:  Advanced Auto Supply, Beckman
                                                          Instruments, Diclcson Electronics,
                                                          Marro Plating, Motorola,
                                                          PlainvUle West, Salt River
                                                          Project, Sieniens Corporation, and
                                                          Strip Joynt
                                                   FS prepared by:  CH2M Hill      .
What volume of material is to be
remediated?

The volume of material to be remediated
included:

The specific volume of soil to be remediated is not given; the ROD states estimates from soil
and soil gas concentrations indicate trichloroethylene is present in the vadose zone at some-of
the potential source areas in quantities from tens to hundreds of pounds.         .
                                                               t      •       ' .  •
The FS estimates between 270 and 1,100 kg of trichloroethylene are present in soils in Area 7,
and 20 to 30kg of trichloroethylene are present in Area 8 (see Question 3).
3.      What type of site is this?

       Electrical Equipment. This ROD addresses North Indian Bend Wash (NffiW), the northern
       portion of the Indian Bend Wash Superfund site. Various electronics manufacturing and metal
       plating facilities, as well as other industries, have been active at NIBW since at least the
       1950s. Operations at many of these facilities have included the use and disposal of organic
       solvents. In many of the potential source areas, buildings and other structures covering large
       portions of the areas continue to be used for industrial and commercial, operations.
    'Vadose zone includes soil matrix, soil gas, and liquid adhering to the soil matrix.
                                      •        -        '               • ! •
          .              -"'',." •.-.    -i-               -       -i1-   "•  •
                                                                                   1149

-------
           The NIBW study area encompasses 10 square miles; 8 square miles of NIBW are. within the
           City of Scotl.-.lale, while approximately 1 square mile is within the City of Tempe and another
           square mile i.1 -.Art of the Salt River Pima-Maricopa Indian Community: Approximately 70
           percent of NI* W is residential, 23 percent is commercial/industrial, and 7 percent is developed
           open space.                                                                         ,

           Thirteen areas for possible soil remedial action have been identified at NIBW.


    TECHNOLOGY SELECTION

    4.      What standard technologies were considered for selection in this FS?  ,

           Standard technologies considered during the identification and screening of technically feasible
           technologies were:                                                             .....'•-
           Access restriction:
           Containment:
           Chemical treatment:
           Physical treatment:

           Disposal:
Institutional controls (deed restrictions, use restrictions)
Capping (native soil, clay cap, synthetic membranes, sprayed asphalt,
asphaltic concrete, concrete cap, multilayered cap), vertical barriers
(soil-bentonite slurry wall, cement-bentonite "slurry wall, vibrating
beam, grout curtains, sheet piling), horizontal barriers (grout injection,
liners), surface controls
Neutralization, precipitation, ion exchange
Solids processing (crushing and grinding, shredding and chopping,
screening, classification), flotation
Removal (excavation)
   5.      Was an innovative technology considered in the FS?  If so, which technology?

           Innovative technologies considered during the identification and screening of technically
           feasible technologies were:

           Biological treatment:   Aerobic processes, anaerobic processes, bioreclamation
           Phys/Chem treatment:  Soil'washing, solvent leaching, oxidation, chemical reduction, in situ
                                 oxidation                   .
           Thermal treatment:     Soil vapor extraction (SVE)


   6.      What was the cost estimate for the innovative technology?

           During the initial screening process, in which technically feasible technologies are identified
           (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
           formulated, costs are typically estimated as part of a three-criteria screening process
           (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
           evaluation.  For this site the estimated costs were calculated during an evaluation based on
           nine criteria established by the NCP.
I
                                                                                                               ;!*••
          There was no three-criteria screening conducted for this site.
1150
                                                 -2-

-------
               Cost Estimates for RAAs That Include Innovative Technologies
                          (selected remedial alternative is in bold)
Alternative
RAA-2
Innovative Technology
Soil vapor extraction
Estimated Costs
9 Criteria
$1,006,0010*
ROD
$1,006,000
       "This cost is the combined cost for treatment of two areas at the site, Area 7 and Area 8.
       Separate costs for Areas 7 and 8 are $619,000, and $387,000, respectively.
                                               .  "       -' -           "i         •     ,
             '             ' •      '      -•-.          '           '       •''...      '•'•'.
7.      How did the cost(s) compare to standard technologies?              i
                        •                      •                                 ' •
                Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-1A
Standard Technology
No action (Areas 1, 2, 4, and 10)
No action/monitoring (Areas 3, 5, 6,
9, 11, and 12)
Estimated Costs
9 Criteria
' • , #0 ' • ' •
$0
ROD
$0
$249,375*
       'Combined cost for monitoring in listed areas.
8.     If a standard technology was chosen, why?

       The no action alternatives (RAA-1 and RAA-1 A) were chosen for Areas 1, 2, 4, and 10
       because few or no VOCs were detected in these areas.

       Based upon available information, Areas 3, 5, 6, 9, 11, and 12 do no* appear to pose
       significant risks due to direct exposure to contaminated soil and soil gas.  For these areas,
       however, more information is needed to estimate the amount of VOGs that are present and to
       evaluate their potential impacts.
 9.      If an innovative technology was chosen, why?

        RAA-2 was chosen as the selected remedy for Areas 7 and 8. This alternative was. chosen
        because SVE will reduce the mobility of most of the contaminant mass by sorbing it onto
        activated carbon.  RAA-2 will also meet chemical-specific, location-specific, and action-
        specific ARARs.  Past performances of SVE systems indicate that the! use of this system will
        significantly, reduce VOC contaminants present in unsaturated soils diiring the useful life of
        equipment and wells.  Several case histories of SVE are available. Extraction rates from 20 to
        more than 300 pounds of VOCs per day have been documented.  Extraction rates of VOCs
        usually decrease with time, generally removing up to 50 percent of the contamination gases
                                             -3-
                                                                                          1151

-------
            during the first 10 percent of operating time. At a site in Puerto Rico, which combined
            remedial actions consisting of concrete capping, groundwater extraction, and SVE, contaminant
            concentrations in nearby ground water monitoring wells dropped over 99 percent.  Based upon,
            extraction rates cited in these studies the SVE alternative would be expected to remove the
            bulk of the vadose zone contaminant mass within several years. As a result, the threat to
            ground water quality would be reduced significantly faster than under RAA-1. SVE is useful
            since much of the contamination is beneath buildings or structures. Whereas excavation would
            require demolition or exposure of structural support of buildings and structures, SVE could
            remove contaminants from beneath a building without the major effects of demolition  and
            exposure of structure supports. A  pilot study was performed at the Phoenix-Goodyear Airport
            (PGA) site in Phoenix, Arizona, in 1988. The PGA site is similar to NIBW in the type of
            contaminants, and shallow vadose  zone lithology. The depth to ground water at the NIBW site
            is greater than at PGA, but the results of the PGA pilot study generally are applicable  to
            NIBW.                                                                   ,

            For both Areas 7 and 8, the VLEACH model, or a similar analytical tool determined
            acceptable by EPA, will be used to evaluate  the continued threat to ground water and,
            therefore, the need to continue operation of the SVE system and/or install additional soil vapor
            monitoring wells.
    10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?                       '           ,

 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages: during the initial screening; during the screening of the three criteria of
 effectiveness, implementability, and cost; or during the, detailed evaluation.

 Innovative technologies eliminated during the initial screening include the  following:

 •      Soil washing was eliminated because soil removal would not be feasible.
 »      Solvent leaching was eliminated because it would not be applicable given the waste
        characteristics.
 •      Oxidation was eliminated because it is an unproven technology with possibly
        hazardous by-products.                       .                             .
 •      Chemical reduction was eliminated because it is unsuitable for removal of a wide
        variety of inorganics and organics.
 •      Aerobic processes were eliminated because this process is unproven for eliminating the
        contaminants of concern. Also, soil removal would not be feasible.
 "      Anaerobic processes were eliminated because this process is unproven for eliminating
        the contaminants of concern.  Also, soil  removal would not be feasible.
 •      In-situ oxidation was eliminated because it is a theoretical, unproven technology for
        eliminating the contaminants of concern.
 •      Bioreclamation was eliminated because it is an unproven technology for the major
        waste constituents at the site.                     •

Innovative technologies eliminated during the screening of the three criteria include the
following:                                                                     .

«      None                                     .
                                                                                                       
-------
        Innovative technologies eliminated during the detailed analysis include the following:

        •      None                             ,
 11.
 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the. elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?
            •            -  -                   ' .     -             '  -
 Overall protection of human health and the environment, implementability, and state and
 community acceptance were weighted most heavily in selecting the remedy for the site. The
 SVE alternative offers greater overall protection since uncertainty regarding the fate of vadose
 zone contamination is reduced. At NTOW, the principal risk to human  health is through
 contact with and ingestion of contaminated ground water.  By removing VOCs from the
 vadose zone and by carefully monitoring the fate of VOCs currently in the Upper Alluvial
 Unit (UAU), which is overlain by the vadose zone, the selected alternatives will help to ensure
 that the ground water underlying NffiW is returned to levels acceptable for drinking water use
 in a reasonable timeframe.  SVE has also been implemented successfully l:o remove VOCs
 from soils. The state supports the RAA-2 over RAA-1 for vadose zonies that present a
 potential threat to ground water quality. Finally community members jit the public meeting
 expressed a strong preference that potential threats from all possible source areas should be
 cleaned up.                        _                            [
12.     What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected to establish cleanup goals?      !

        Cleanup levels for soils were not given in the ROD. The following cleanup levels were
        presented in the FS.                                               '  .
Contaminant
Cleanup Level (fig/kg)
ARAR or Other Basis
Carcinogens
Trichloroethylene
Tetrachloroethylene
Noncarcinogens
1 , 1 -Dichloroethene
320
67
Health-based*
Health-based

700
Health -based
              'Arizona Department of Health Services (ADHS) suggested health-based cleanup levels
              for contaminants in soils.                                   \,.
13.
Was the innovative technology eliminated because of the cleanup goals? Could the standard
technology meet the cleanup goals?                                 !

Innovative technologies eliminated because of cleanup goals include:

•      None                                        ,                      -
                                             -5-
                                                                                     1153

-------
       .  Standard technologies eliminated because of cleanup goals include:

                                                 :-    " •'•-•   '             '-'-••"
         •      None                                                 '


 14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.

                                             '           '            "'       -   '    '    '     ' '
                                                                 .'            '      ('.-•"'
 15.     What measures/criteria were used to compare alternatives?
    *                                -                  •                 :               '     '     '

         The following measures were used to compare the alternatives:

              Cost effectiveness
              Proven reliability                         >         ,                   .

                                                                           .

 16.     How are measures compared?
                                                    •  •         -••'••'     '
         EPA considers the costs for the vadose zone treatment to be proportionate to their
         effectiveness in removing the potential for hundreds of years of ground water contamination
         and avoidance of the substantial monitoring and cleanup costs that such contamination would
         entail.  The performance of SVE systems in the past indicates that the use of this system
         results in a significant reduction of VOC contaminants. The results of a pilot study at a site          |   ~'\
         similar to NIBW are generally applicable to NIBW.                     ,                               i)f


 77.     What technical considerations were factors in selecting a remedy? Were technical
         considerations primary in the selection of the remedy?

         Technical considerations were not primary in selecting a remedy for this site.
                                                                                                    .*  f
1154
                                               -6-

-------
                                   Iron Mountain Mine
                             Boulder Creek Operable Unit

                                  Shasta County, California
                                          Region 9
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

      ,  Maximum concentrations of principal
        contaminants were:

        Waste Piles

        Samples from four of the waste piles
        exceeded regulatory levels for arsenic,
        cadmium, lead, and zinc in California Total
       Threshold Limit Concentration (TTLC) and
        Soluble Threshold Limit Concentration
        (STLC) tests.
             Site History
NPL Proposed:
NPL Final:
FS:
Interim ROD:
N/A
9/8/83
5/92
9/30/92
             Background

FJPA Fund-lead
PRPs:  Rhone-Poulenc Basic Chemicals,
       Iron Mountain Mines, Inc., T. W.
       Arman                       .
FS prepared by: CH2M Hill
2.     What volume of material is to be
       remediated?

       The volume of material to be remediated included:

       •      30,000 to 50,000 cubic yards of wastes
3.      What type of site is this?

       Mining. The Iron Mountain Mine (IMM) site includes the inactive mines on Iron Mountain
       (including the Richmond, Lawson, and Hornet mines) and areas when; hazardous substances
       released from the mines are now located. The site covers approximately 4,400 acres of land
       that is predominantly forested.  The adjacent land is largely undeveloped  wilderness  This
       interim ROD addresses the Richmond and Lawson portal Acid Mine Drainage (AMD)
       discharges and seven waste piles on site.  The waste piles include tailings from beneficiation
       activities at the mine, the dumping of mine cars with sulfide contents below processing
       facilities, and rock wasted during mining operations. Collectively these waste piles are the
       third largest source of AMD at the site, contributing an estimated 3 to120 percent of the metals
       to Boulder Creek.                                 '••":!'.
                                            -1-
                                     1155

-------
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:                                      '          .•''.'.-'•

          Containment:          Capping (shotcrete, clay, geosynthetic membrane), grading, diversion
                                systems           •                               .                ,
          Phys/Chem treatment:  Stabilization (pozzolanic agents), resource recovery (neutralization,
                                flotation)        A.
          Disposal:              Excavation (backhoes and bulldozers), RCRA landfill, non-RCRA
                                landfill
   5.      Was an innovative technology'considered in the FS? If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:

          Phys/Chem treatment:  Acid leaching
   6.      What was the cost estimate for the innovative technology?

          During the initial  screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation.  For this site, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.

          Innovative technologies were not incorporated into remediation action alternatives.
   7.      How did the cost(s) compare to standard technologies?

                    Cost Estimates for RAAs That Include Standard Technologies
                              (selected remedial alternative is in bold)

          Waste Piles'               ,,'.''-,
1156
Alternative
RAA-WO
RAA-W1
RAA-W2
Standard Technology
No action
Capping waste piles in place
Waste pile removal, treatment, and
'disposal
Estimated Costs
3 Criteria
N/A
N/A •>
N/A
9 Criteria
$0
eliminated
$5,918,000
                                                -2-

-------
Alternative
RAA-W3
Standard Technology
Consolidating and capping waste piles
on site -
I Estimated Costs
3 Criteria
I'N/A
. r i
'',' f
9 Criteria
$2,970,000
       aAlthough RAAs were developed in the FS for. contaminated seeps land tributaries, and for
       sediments, these RAAs were not addressed in the interim ROD.   '
8.      If a standard technology was chosen, why?                       :   /
                  . •      •            •       .     '                  ,!-'',
       RAA-W3 was selected because consolidating and capping the seven waste piles, with proper
       remedial design and maintenance, essentially will "eliminate" the current discharge of AMD
       from this source.  By excavating the waste piles, the selected alternative will be "very
       effective" at reducing the long-term metals loading to Boulder Creek.  The exact amount that
       metals loading to Boulder Creek will be reduced is unknown, but if implemented with other
       source control alternatives, RAA-W3 might provide a measurable incremental reduction in
       metals concentration in downstream surface waters (RAA-W3 will provide at least by the next
       rainy season, an estimated 1  to 10 percent reduction in metals loading to Boulder Creek).  The
       process of consolidating and capping the wastes will effectively eliminate both the processes
       currently mobilizing the metals: the leaching  action of infiltrating precipitation and ground
       water as it  travels through the waste piles, and the erosion of material from the surface of the
       piles.  This alternative will involve limited risk to workers during construction.  The dust
       suppression measures during waste hauling are less stringent than for RAA-W2 because
       hauling distances are shorter, and all waste materials remain within the Superfund site
       boundaries. Excavation of some of the waste piles would be technically challenging; however,
       the equipment and techniques required have been successfully employed on other earth moving
       projects. The technical implernentability of the cap design is well proven. The equipment and
       work force necessary for implementing RAA-W3 are readily available in Northern California,
       and the specialized materials for constructing the cap are available from several commercial
       vendors in  the United States.                     "              ',.'-.'                   ,

       All of the RAAs fall short of meeting ARARs in the receiving waters because the Boulder
       Creek Operable Unit does not contain all of the contaminant sources and these alternatives
       address only a part of the sources in the Boulder Creek Operable Unit. The RAAs are interim
       measures with a best case expectation of making a significant contribution toward final
       cleanup. The small anticipated reduction in metal discharges resulting from RAA-W3 is a
       significant  contribution to final cleanup standards on the site. Because the Boulder Creek
       Operable Unit is an interim remedy, it can qualify for ARAR waivers. The ARARs that are
       being waived for the purposes of this operable unit are the water quality objectives/standards
       established by California in the Central Valley Basin Plan and Fish and Game Code Section
       5650.
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
                                              -3-
1157

-------
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?                                                        •

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages:  during the initial screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial screening include the following:

         •      Acid leaching was eliminated because of the lack of demonstrated effectiveness; if data
                become available that indicate adequate resource recovery is economically possible, the
                FS stated the technologies would be reconsidered.  The FS states that the removal
                efficiencies of these processes are expected to be low because the in situ metals
                concentrations in the piles are relatively low. The implementability  and effectiveness
                of these treatment options could not be evaluated; laboratory or bench-scale testing is,
                required to provide sufficient  information to conduct these assessments.
  I,,;
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology? If so,
         which criterion? Which of the criteria supported the use of a standard technology?

         Cost and overall protection of human health and the environment were the criteria weighted
         most heavily in  selecting RAA-W3.  The selected remedy was chosen over RAA-W2, which
         includes off-site treatment and landfilling of the waste, because RAA-W2 would cost nearly
         twice as much as on-site landfilling of untreated waste. The selected remedy will "essentially"
         eliminate the environmental threats posed by the waste piles and is therefore protective of
         human health and the environment.               ,                                  •    >
 12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
         ARAR?  What risk level was selected to establish cleanup goals?   .                   .

         Cleanup goals were not selected for this interim ROD.               ,
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
         technology meet the cleanup goals?                           .

         Innovative technologies eliminated because;of cleanup goals include:

         •      None                                                  •

         Standard technologies eliminated because of cleanup goals include:           '

         "      None                                             •             ,
 14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.

1158
v
                                               -4-

-------
15.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Cost-effectiveness
       -     Proven reliability


16.    How are measures compared?

       The selected remedy was chosen because it will cost substantially less
       RAA-W2 and is therefore^more cost-effective.  RAA-W3 also was chosen
       can be performed with existing technology, and landfilling is a well
     to implement than
         because excavation
   established technology.
17.    What technical considerations were factors in selecting a remedy?
       considerations primary in the selection of the remedy?
   Were technical
       Technical considerations were not primary in selecting the chosen remedy
       eliminated, however, because capping would not be very effective wii
       for ground water infiltrating into the piles as a result of the high
       and surface-water runoff that occur near many of the waste piles.  In
       remote and steep locations of the waste piles, capping the piles in pi;
       extremely difficult.  New road construction to many of the piles would,
ground
   lace
                                              -5-
       RAA-W1 was
ithout additional controls
    water levels, springs,
 addition, because of the
   was. considered to be
 1 be required.
                          1159

-------
                                   Jasco Chemical Corp.

                                  Mountain View, California
                                          Region 9
  GENERAL SITE INFORMATION

  1.      What were the principal contaminants,
         contaminant levels, and met
         this feasibility study?

         Maximum concentrations of principal
         contaminants were:

         Soil (mg/kg)

         1,1-Dichloroethane
         1,1-Dichloroethene
      •   1,2-Dichloroethene
         1,1,1-Trichloroethane
         Acetone
         Benzene
         Diesel or Kerosene Mixture
         Ethylbenzene
         Methanol
         Mcthylene chloride
         Tetrachloroethene
         Toluene
         Trichloroethene
         Xylene
ninants,
addressed in

incipal



3
1.7
0.015
61
100
3
6,700


Site History
NPL Pi-oposed:
NPL Final:
FS:
ROD:
6/4/88
10/4/89
5/21/92
9/30/92
Background
i
PRP-lead
PRPs: Jasco Chemical
FS prepared by: OHM
Services Corp..

.
1.2
60
21 ••••-::••
4
110
0.05
37


Corp.
Remediation



•






  2.      What volume of material is to be remediated?

         The volume of material to be remediated included:

         "      2,159 cubic yards of soil
  3.      What type of site is this?

         Chemicals and Allied Products. A chemical repackaging and solvent manufacturing facility
         located in an urban area.                                        ,.-•'.,
1160
                                             -i-

-------
TECHNOLOGY SELECTION
4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                               ;
        Access restriction:
        Containment:
        Physical treatment:
        Thermal treatment:
        Disposal:
Deed restrictions
Capping (clay, synthetic liner)
Carbon adsorption, resin adsorption
Incineration (on-site, off-site)
Excavation, disposal at RCRA facility
5.      Was an innovative technology considered in the FS? If so, which technology?,
                   . '  •       :        '           :                       i
        Innovative technologies considered during the identification and screeining of technically
        feasible technologies were:
  1  -.                  "          "                '         -             j     '  ;
        Biological treatment:   Biodegradation (enhanced bioremediation, X-19 bioremediation
                              process)                                  |
        Phys/Chem treatment:  Spil washing (Excaliber treatment), dechlorinatioia, neutralization,
                              vapor extraction
        Thermal treatment:     Thermal desorption, heat stripping, in situ vitrification
        What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that mesrit a more detailed
        evaluation. In this case, estimated costs were calculated during an evaluation based on nine'
        criteria established by the NCP.                                  j
                             •  .          .         ,                 '     i  •'
                  Cost Estimates for RAAs That Include Innovative Technologies
            !                 (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5
Innovative Technology
Excavation/enhanced bioremediation/
vapor extraction/off -site disposal of
residuals
Excavation/X-19 bioremediation
treatment
Excavation/soil washing with the
Excaliber process
Estimated Costs
=
3 Criteria
. N/A
N/A
i
N/A
i
9 Criteria
$365,000 to
$448,000*
$278,500 to
$318,500
$338,000 to
$470,000
                                                -2-
                                                                                            1161

-------
         'Based on past experience, the range of costs reflects the variation in treatment cost per cubic
         yard of soil.                                                                  .
  7.     'How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
/*
Standard Technology
No action
Excavation/off-site treatment,
probably incineration
Estimated Costs
3 Criteria
N/A
N/A
9 Criteria
$0
$1,683,000
 5.     If a standard technology was chosen, why?              "

        A standard technology was not chosen as the primary remedy.  Off-site disposal of residuals, if
        necessary, was selected.                            '


 9.     If an innovative technology was chosen, why?

        A combination of two alternatives, RAA-2 and RAA-3, was selected for site remediation. Site
        soils will be cleaned using the enhanced bioremediation treatment proposed in RAA-3.  If site
        cleanup levels are not achieved by this method, treated soils not meeting cleanup levels will be
        sent to the appropriate off-site RCRA treatment and/or disposal facility. If the backup method
        of off-site incineration is required, the soil will likely have to be transported out of the state
        since there are "no incinerators" in California. Treatability studies have shown that RAA-3
        would most likely meet ARARs.  Organic hydrocarbons are  more biodegradable than
        chlorinated hydrocarbons, but the chlorinated hydrocarbons are very volatile and will be
        absorbed in carbon beds. These alternatives ensure long-term effectiveness since chemicals of
        concern will be permanently degraded. Furthermore, contaminant toxicity, mobility, and
        volume will be reduced.  Implementation of this alternative will not pose short-term  risk since
        any potential short-term risk can be mitigated by a health and safety plan.  The technology
        proposed in these alternatives is easy to construct and operate.  The  alternatives are cost
        effective.                                                       /              .        .
10.
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                            -

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
1162
                                              -3-

-------
        Innovative technologies eliminated during the initial screening include-, the! following:
                                                                       i  .   '    ./   •
        •      Dechlorination was eliminated because the majority of site constituents are not highly-
               chlorinated and could not be successfully treated by these processes.

        Innovative technologies eliminated during the screening of the three criteria include the   '
        following:                                                                     .    '

        •      Thermal desorption was eliminated because of the high energy, requirements for a
               relatively small volume of soil and because it would not be practical or publicly
               acceptable to operate a volatilizer in a residential community.  Thermal treatment
               processes are comparably more expensive than ex situ vapor extraction or enhanced
               bioremediation, which would be equally effective.                             -
        •      Heated stripping was eliminated for the same reasons as thermal desorption; the
               energy and cost requirements would be high compared to other options.
        •      In situ vitrification was eliminated because it does not appear |to be implementable at
               the site. This technology is expensive, designed for larger sites where no other option
               is feasible.  It is most appropriate for inorganic waste  and mixed waste as organics
               volatilize from soil. The area to be treated is located near the Southern Pacific
               Railroad tracks. The melt would extend to the tracks and  any soil volume loss would
               damage the structural integrity of the tracks.  The vent hood, which is 50 feet by 50
               feet, could not be extended over the active tracks.      '
        •      In situ bioremediation was eliminated because the contaminants 'are in clay soils and
               treatability tests would be needed.
        •      In situ vapor extraction was eliminated because of the clay and silt content of the soil.

        Innovative technologies eliminated during the detailed analysis include: the; following:

        •      Soil washing with Excaliber treatment was eliminated  because! its effectiveness is not
               as well proved as that of the chosen technology.            !
        •      Biodegradation with X-19 treatment was eliminated because its effectiveness is not as
               well proved as that of the chosen technology and a treatability study must be
               conducted.


11.      Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the  use of a standard technology?

       Long-term effectiveness and cost were the criteria weighted most heavily in selecting a
       remedial alternative. .The chosen technology was the only on-site treatment expected to meet
       ARARs without treatability tests.  The effectiveness of enhanced bioremediation will be
       supported by off-site incineration.  While off-site incineration also would have to meet   «.
       ARARs, it was not preferred as a stand alone option because it would be  more expensive.
                                                                                             1163

-------
  12.     Wliat cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
         ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Benzene
1 , 1 -Dichloroethane
1 , 1 -Dichloroethene
1 ,2-Di :hloroethane
Methylene chloride
Pentachlorophenol
Tetrachloroethene
Trichloroethene
Vinyl chloride
0.3
0.6
2
0.03
0.2 .
200
7
3
0.02
Model8
Model .
Model
Model
Model
Model
Model
Model
Model
Noncarcinogens
c-1 ,2-Dichloroethene
Ethylbenzene
Toluene
1,1,1 -Trichlorqethane
Xylenes
Acetone •
Chloroethane
Diesel or kerosene
mixture
Methanol
Methyl ethyl ketone
1
3,000
1,000
100
2,000
30
4,000
10,000
200
9
Model
Model
Model
Model
Model
Model
Model
Model
Model
/ Model
                "Cleanup levels were developed for the protection of ground water and were estimated
                using MCLs and the Summer's Leachate model (EPA, 1989)., For carcinogens, an
                excess upper bound individual lifetime cancer risk between 10"4 to 10"6 was acceptable.
                For noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.
1164
                                              -5-

-------
 13,     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                                I

        Innovative technologies eliminated because of cleanup goals include:

    -   • •'   ., None •       .                .    f        ". '          :    p..-.'

        Standard technologies eliminated because of cleanup goals include:   !

        *      None^,            ...   •   . '  - '-       ,        •           _!•'..'•,


 14.     Were treatability studies conducted on the innovative technology or standard^technology?

        Treatability studies were not described in the Feasibility Study; however, «he ROD states that
        "treatability studies have shown that Alternative 3 would most likely comply with ground
        water ARARs."                                                  !

                                         '.   -           '   -    / •'        i -.''.-•
 15.     What measures/criteria were used to compare alternatives?          j

        The following measures were used to compare the alternatives:        i

        -       Cost/unit risk
               Proven reliability                                          j


 16.     How are measures compared?

        Treatability tests have shown that the chosen alternative will most likeliy comply with ARARs.
        The Excaliber process is being demonstrated under EPA's SITE program and initial results.are
        encouraging, however, it has not been extensively demonstrated and testability studies would
        be required at the Jasco site. The Excaliber process  also was deemed llhe most difficult to
        operate since a full-scale system has not yet been built.  The Excaliber soil washing process is
        a new technology and its effectiveness has not yet been established, therefore it also would
        require additional testing prior to implementation at the site. Off-site ijicineration was not
        selected as a stand-alone option because it would be  too expensive.


17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?                i
                                                                        'i -
                -' -  -              '                                    .'  il            •-         ' . *
       Technical considerations were not primary in selecting a remedial alternative, however, in situ
       vitrification was eliminated in part because its implementation was limited by physical
       constraints  (railroad tracks).                                        !
                                                           •  '     '     - \   • '  . -

       References:                      .   '   • .
       EPA. 1989,  U.S. Environmental Protection Agency.  Determining soil response action levels
       based on potential contaminant migration to ground water: a compendium of examples.
                                             -6-
1165

-------
                        Lawrence Livermore National Laboratory
                               U.S. Department of Energy

                                    Livermore, California
                                          Region 9
 GENERAL SITE INFORMATION

 1.     What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:

        Sediments (mg/kg)

        Trichloroethene              6
        Fuel hydrocarbons (FHCs)     11,000
        Aromatic hydrocarbons        4,800
 2.     "What volume of material is to be
        remediated?                 •

        The volume of material to be remediated
        included:
                                     Site History

                        NPL Proposed:       N/A
                        NPL Final:           7/87      •
                        FS:                  12/90
                        ROD:                7/92

                                    Background

                        Federal Facility
                        PRPs:   Department of Energy       '
                        FS prepared by:  Lawrence Livermore
                               National Laboratory, Weiss
                               Associates, Inc., Science
                               Applications International Corp.,
                               Woodward-Clyde Consultants
        •      2.94 million cubic yards of sediment contaminated with volatile organic compounds
               (VOCs)                 •
        «      11,200 cubic yards of sediment contaminated with benzene, ethylbenzene, toluene, and
               xylene isomers (BETX)            .    •   '_        .
        •      4,500  cubic yards of sediment contaminated with total fuel hydrocarbon (TFH)


 3.      What type of site is this?                                                    .

        Department of Energy. A U.S. Department of Energy research and development facility that is
        surrounded by industrial, urban, and agricultural areas.
•):
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:
1166
Permit restrictions, land use restrictions
Capping (asphalt, clay, synthetic liners), slurry wall, grout curtain
                                            -1-

-------
       Disposal:
Excavation, off-site disposal
5.     Was an innovative technology considered in the FS? If so, which technology?
                                                         'i -       .

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:
                                                        ',••''                   " !
       Biological treatment:   Bioremediation (in situ, ex situ)
       Chemical treatment:    Oxidation (thermal, catalytic)
       Physical treatment:     Vacuum extraction, radio frequency enhanced extraction, sorption
                             granular activated carbon (GAC)            j
       Thermal treatment:     Steam enhanced extraction, in situ vitrificatioiu
6.      What was the cost estimate for the innovative technology?          |

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs,  v^fter the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case, the estimated costs were calculated during ail evaluation based on
       nine criteria established by the NCP.                                         .

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Innovative Technology
Vacuum extraction/vapor treatment
via catalyzed oxidation/GAC if
necessary
Estimated Costs
3 Criteria
•' : N/A
1 - -
9 Criteria
$1,114,000
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Techn clones
                            (selected remedial alternative is in bold)
Alternative
RAA-2
Standard Technology
Deferred action/monitor/extract and treat
ground water
i- • •- . '
Estimated Costs
3 Criteria
N/A
l
9 Criteria
$852,000
                                              -2-
                                                            1167

-------
   8.      If a standard technology was chosen, why?

           A standard technology was not selected,
  ,9.      If an Innovative technology was chosen, why?

           RAA-1 was selected because it reduces risk by actively removing contaminants from the
           sediment, which is a potential source of ground water contamination. It was determined that
           site sediment did not pose a direct threat to human health except through the migration of
           contaminants to ground water.  Vacuum-induced venting of the unsaturated zone removes
           subsurface VOCs.and FHCs and prevents contaminant migration to ground water.
           Implementation of this remedy poses no unacceptable short-term risk and does not adversely
           affect the adjacent subsurface media. It complies with alllARARs and is cost effective.
           Although the selected remedy is more expensive than the other alternative, cleanup will  be
         •  more rapid. The remedy permanently .removes contaminants from the sediment and thereby
           provides long-term effectiveness.  The selected remedy immediately and permanently removes
           and breaks down contaminants, thereby reducing contaminant toxicity, volume, and mobility.
           It is technically and administratively feasible and supported by available services, materials
           and skilled labor.                                                    '  ..'           '
   10.
 If an innovative technology was not chosen, why not? At what stage was the innovative
 technology eliminated?
                                                  »   "  :
 Innovative technologies could be eliminated from the remedial technology selection process at
 three stages:  during the initial screening; during the screening of the three criteria of
 effectiveness, implementability, and cost; or during the detailed evaluation.

 Innovative technologies eliminated during the initial screening include the following:

 •      In situ vitrification was eliminated because it is considered experimental, would be
        very intensive, and would not be likely to have any advantages at the site.
 «      In situ bioremediation was eliminated because chlorinated solvents are less amenable
        to biological destruction, and efficient destruction has not yet been demonstrated for
        halogenated compounds.  Bioremediation of FHCs was not considered because of the
        depth of the FHCs and the sensitivity of microorganisms to in situ conditions, which
        are difficult .to control and introduce substantial uncertainties in the applicability of the
        process.
 "      Ex situ bioremediation (slurry ,phase) via a bioreactor was eliminated because it would
        require complex operations.
 •      Steam enhanced extraction was eliminated "because heat would not be required."
 •      Radio frequency enhanced extraction was eliminated "because heat would not be
        required."

Innovative technologies eliminated during the screening of the three criteria include the
following:                                                            •               '

•      None                          ,
                                                                                                               •'IE.
1168
                                                -3-

-------
       Innovative technologies eliminated during the detailed analysis include the following:
                                                                     - 'i  '
       •     None  .                              '                   f.
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
 •       •     N            •   :•    •   •'-.     /  .   •-.•-.•    ' -   •  i , •.  •    •    -':-.,'
       The criteria weighted most heavily in selecting a remedial alternative were reducing
       contaminant mobility and short-term effectiveness.  The chosen alternative permanently
       reduces contaminant mobility in sediment, thereby preventing contaminant migration to ground
       water. This alternative was preferred over deferred action (RAA-2) because it requires 10
       years to achieve the remediation goals while RAA-2 would have taken 90 years.
                                                               ,' ;      i
                                                                       l'i            -
12.    What cleanup goals were selected? If the  cleanup goal was based on an ARAR, what was that
    .   ARAR? What risk level-was selected to establish cleanup goals?

       Cleanup levels for sediment were not established.  The decision of whether or not an area
       requires cleanup will be based on unsaturated  zone monitoring and ground water modeling. If
       modeling indicates that hazardous materials will affect ground water iln concentrations above
       an MCL, remediation will be implemented.
13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       technology meet the cleanup goals?                                                    ,

       Innovative technologies eliminated because of cleanup goals include:
                                    '-'''..,'•'•         !
       •     'None               -                -    ••-''.     ' T '•..''"•'
             •  " '      '         '        ,    •         -    .'••"    -.  '         •  ' '         •
       Standard technologies eliminated because of cleanup goals include:   :

       •   -  None   _       ;          •:     '          •'.  '             L    • •           .


14.    Were treatability studies conducted on the innovative technology or standard technology?

     "  Treatability studies were not conducted.
15.     What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

              Cost/unit risk             .
              Time to design/construct/operate
                                                                                         1169
                                              -4-        ,.  .       '  .  :   •          '   '

-------
  16.    How are measures compared?                                               ,*

         RAA-1 was considered cost effective even though it is more costly than RAA-2 because it
         would enable a more rapid cleanup. It also was preferred because it reaches remediation goals
         in 10 years while RAA-2 would take 90 years.
  17.    "What technical considerations were factors in selecting a remedy?  Were technical
         considerations primary in the selection of the remedy?                         ,

         Technical characteristics were not primary in selecting a remedial alternative.  Given the depth
         of the contaminants (FHCs) in the vadose zone (up to 100 feet), excavation is  impractical.
                                                                                                          ';,!*	
1170
                                              -5-

-------
                                 Monolithic Memories
      (National Semiconductor Corp. and Advanced Micro Devices—Arques)
          '.'..'-.•.•'     .'•       .  OU-1  •''.-•••••   •,;  -   .  •' -,..'  "••
                           Sunnyvale and Santa Clara, California
                                        Region 9        :
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?         ,

       Maximum concentrations of principal
      .contaminants were:

       Soil/Subunit 1 (National Semiconductor
       Corp. Facility) (mg/kg)           ';..'•

       Tetrachloroethene (PCE)     9.6
       1,2-Dichloroethene          0.93
       1,1,1-Trichloroethane        159
       Trichloroethene             4.6
       Xylenes                    3,300
       Ethylbenzene               18,000

       Soil/Subunit 2 (Monolithic Memories
       Facility) (mg/kg)

       Solvents (PCE, xylenes, TCE,
        chlorobenzene, 1,2-DCE)    400
       PNAs (naphthalene, pyrene,
        phenol)                   270
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
10/15/84
7/27/87
6/14/91
9/91
            Background

PRP-lead  /
PRPs:  National Semiconductor
       Corporation, Advanced Micro
       Devices-Argues, Hewlett Packard,
       United Technologies Corporation
FS prepared by:  Harding Lawson
       Associates
2.      What volume of material is to be remediated?
                                       ', .          '                I   ...

       The volume of material to be remediated included:
        -            '      '       '            " '"          .          t        -         • ,
                                                                  "I             ,  '   ;•
       •     There is no reference in  the FS or the ROD to the quantity of soil to be remediated in
             Subunit 1.  The FS states that the soil remedial unit at the Natiomd Semiconductor
             Corp. (NSC) and former United Technologies Corporation (UTC) sites is comprised
             of:                         •...,;,  ,/    •-    , |.   •    :

             —    "shallow" (less than 5 feet bgs) vadose zone soils that require remediation of
-,-.'•'           volatile organic compounds (VOCs), and

             —    "deeper" vadose  zone soils, from approximately 5 feet!bgs to the historical
                    surface of the water table at approximately 12 feet bgsj, that require
                    remediation of VOCs.
                                          -1-
                                                                                       1171

-------
               There is no reference in the FS or the ROD to the quantity of soil to be remediated jn
               Subunit 2 (Monolithic Memories).
 3.      WJiat type of site is this?

        Electrical Equipment. The two sites, although listed separately on the NPL, contaminate the
        same ground water; for this reason, the investigation and evaluation of, cleanup options was
        combined. Operable Unit 1 has been divided into three subunits for ease of description.

        Subunit I/National Semiconductor Corporation (NSC)

        NSC is a semiconductor manufacturing operation that occupies approximately 60 acres of land.
        This facility has been in operation since 1967 and is located in an industrial park setting.  The
        NSC site also includes the former UTC facility, which adds another 10 acres to the site.

        Subunit 2/MonoIithic Memories, Inc., Advanced Micro Devices (AMD-Arques)

        AMD-Arques is a semiconductor manufacturing operation that ceased production in 1989.
        Operations were begun at the facility by Monolithic Memories, Inc., in 1970. The facility is in
        the same industrial park  as NSC.

        Subunit 3 •

        Subunit 3 consists of the areas  downgradient from Subunits 1 and 2, and extends to the
        leading edge of the ground water contaminant plume. Subunit 3  does not contain any facilities
        that are known sources of the solvent ground water plume that emanates from Subunits 1 and
        2.  The selected remedial action for this site only includes treating contaminated soil in
        Subunits  1 and 2.
TECHNOLOGY SELECTION         '

4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening pf technically feasible
        technologies were:                                                                '
        Containment:


        Chemical treatment:

        Physical treatment:

        Thermal treatment:

        Disposal:
Vertical barriers (grout curtain, slurry wall, steel sheet piling),
horizontal barriers (grouting, block displacement), capping (clay, soil,
asphalt, concrete, synthetic liner), surface water controls
Precipitation, asphalt batching, solidification (cement based, silicate
based, pozzolanic based, thermoplastic, surface microencapsulation)
Distillation, dewatering, filtration,  screening, ion exchange, membrane
separation
Incineration (rotary kiln, multiple hearth, fluidized bed, circulating bed,
infrared, mobile, advanced electric reactor, flare, catalytic)
Source soil excavation, on-site disposal, off-site disposal (landfill)
1172
                                              -2-

-------
5.      Was an innovative technology considered in the F$?Ifso, which technology?
                                                                       ,.r           '
        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                                -"-..'.
                                                    •             '•!'••'
        Biological treatment:   Aerobic and anaerobic biodegradation
        Phys/Chem treatment:  Oxidation, reduction, hydrolysis, dechlorination, vacuum extraction,
                             soil flushing/soil washing, solvent extraction, supercritical extraction
        Thermal treatment:     Pyrolytic combustion, wet ah- oxidation, thermal desoiption, steam
  ,                           stripping,  in situ vitrificatipn, in situ radio heating
                                                                        I '  ' ••    '

6.      What was the cost estimate for the innovative technology?           I
                                                                      i  i
        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation. For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NGP.

        The RAAs developed in the FS changed in the ROD and, therefore,1 tijiese are discussed
        separately below.          ."...','         .,."'.-.

                 Cost Estimates for RAAs That Include Innovative Technologies
                           (selected remedial alternative is in bold)    j

        FS/Soil/Subunits 1 and 2                                          !
Alternative
RAA-4a
RAA-4b
Innovative Technology
Enhanced interim Remedial Measure
(IRM)a [ground water treatment]/soil
remediation (soil vapor extraction, SVE)
to proposed cleanup standards
Enhanced IRM (ground water treat-
ment)/soil remediation (SVE) to 10"6
risk levels
Estimated Costs
3 Ciitetia
N/A ' ; '
N/A
9 Criteria
$5,900,000
$5,900,000
       This site has existing on-site and off-site ground water extraction arid trezitment systems,
       which were the IRM for this site.
                                                                                            1173

-------
       ROD/Soil/Subunits 1 and 2
Alternative
RAA-2
RAA-3
Innovative Technology
Ground water extraction and
treatment/SVE in Subunit 2
Ground •water extraction and treat-
ment/SVE in Subuiiits 1 and 2/with
contingency to excavate and aerate
shallow soils unresponsive to SVE
Estimated Costs
ROD
$5,500,000
$8,400,000
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)

       FS/Soil/Subunits 1 and 2
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action/monitoring/institutional
controls
Current IRM (ground water treatment)
Enhanced IRM (ground water treatment)
Estimated Costs
3 Criteria
, N/A f
N/A
. N/A '
9 Criteria
$2,400,000
$3;500,000
$4,300,000
        ROD/Sbil/Subuhits 1 and 2
Alternative
RAA-1
Standard Technology
No action/monitoring/institutional
controls .
Estimated Costs
ROD
$3,200,000
 8.      If a standard technology was chosen, why?

        A standard technology was not chosen.
 9.      If an innovative technology was chosen, why?
        The selected alternative RAA-3 incorporates the use of SVE to treat contaminated soils. SVE
        was selected because it is reliable for achieving long-term reductions in soil with chlorinated
1174
                                             -4-

-------
       solvent concentrations, is generally easy to implement, and causes only minimal disturbance of
       site activities.  SVE treatment systems are durable and require replacement of few components,
       with the exception of the catalytic incineration or vapor phase carbon equipment used to treat
       off-gas. SVE effectively reduces the toxicity, mobility, arid volume of soil containing VOCs
       by removing the VOCs from the soil. The nature of the VOCs and properties of the on-site
       soils together with experience with this technique on other similar sites in the area indicate that
       SVE will be effective in achieving the soil cleanup standards at the NSC/MM site.  The
       ultimate performance of this technology at the site, however, only can be reliably predicted
       based on full-scale operation.  RAA-3 will contain migration of contaminants in the polluted
       aquifers. Under RAA-3, the soils in Subunit 1 will be treated in  addition to those in Subunit
       2. This difference significantly reduces cleanup time from greater than 100 years (when soils •
       in Subunit 1 are left untreated, they will remain above acceptable risk levels  for greater than
       100 years) to a 50-100 year range for Operable Unit 1. The selected alternative can provide a
       cleanup that achieves an acceptable risk level within a reasonable time period (50-100 years).
       If proposed cleanup standards are achieved, the residual carcinogenic [risks for this alternative
       are 3.1 x 10"6 and a hazard index of 0.87. The selected alternative will attain all pertinent
       ARARs for this site. The state's antiklegradation policy, Resolution (58-16 (which is an
       ARAR for these sites), is met because further degradation of a potential drinking water supply
       will be prevented. If certain shallow soils that are contaminated  with lower volatility
       compounds do not respond well to SVE,  there is a contingency plan ijnder RAA-3 to excavate
       and aerate these soils at the surface. If this occurs, air emissions during excavation and
       aeration will be regulated under the Bay  Area Air Quality Management District (BAAQMD)
       Regulation 8, Rule 40. If meeting the BAAQMD permit levels requires emissions control such
       as activated carbon, disposal of spent carbon will have to be managed in accordance with
       RCRA Land Disposal Restrictions.  Thermal carbon regeneration risks associated with this
       process will be mitigated through proper engineering controls and hazardous waste
       management practices.


10.     If an  innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial  screening; during the screening of the;three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:
                                                  •'            -          I              -      '
       •      Pyrolytic combustion was eliminated  because incinerators would not be readily
               available or permitted in California for treatment of hazardous waste-contaminated
               soils containing the chemicals of potential concern at the NSC/UTC  sites.  Incinerators
               that are available for soil treatment are located outside Califojrnia. and soil excavation
               and transportation costs would be very high relative to other treatment processes.
       •      Wet air oxidation was eliminated because it would not be  applicable to soils.
      - •      Reduction was eliminated because it would not be applicablej to organic constituents in
               the soil.          ,                     .                 L
       •      Hydrolysis was eliminated because it would not be applicable toorganic constituents in
               the soil.
       "      Dechlorination was eliminated because it would not be applicable to organic
               constituents in the soil.
        •      Steam stripping was eliminated because it would not be  applicable to soils.
                                               -5-
1175

-------
                Thermal desorption was eliminated because it would not be applicable to soils.
                Soil flushing/soil washing was eliminated because it would not be effective for the
                organic constituents in NSC soil.
                Solvent extraction was eliminated because it would not be applicable to soils.
                Supercritical extraction-v/as eliminated because it would not be applicable to soils.
                Aerobic and anaerobic biodegradation were eliminated because these technologies
                would not be effective for the constituents found in NSC soil. Biological treatment is
                not considered effective or implementable for NSC or UTC soil because of the
                refractory nature of the chemicals. That is,  some of the chlorinated chemicals (e.g.,
                trichloroethene) present in NSC and UTC soils are difficult to biologically degrade.
                Practical bioremediation techniques for these compounds has not yet been
                demonstrated. Furthermore, some degradation pathways lead to the production of
                other, sometimes more hazardous, intermediate products such as vinyl chloride.
        »      In situ radio heating was .eliminated because it is a new technology that has not been.
               fully developed.       .                                                       •
        •      Oxidation was eliminated but no reason was given.
        •      In situ vitrification was eliminated but no reason was given.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        "      None

        Innovative technologies eliminated during the detailed analysis include the following:

        •      None       •  '                                                                ;
1L
Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
to meet one of the nine criteria result in the elimination of the innovative technology? If so,
which criterion? Which of the criteria supported the  use of a standard technology?

Protection of human health and the environment was weighted heavily in selecting
RAA-3 as the  remedial alternative for this.site.  Under RAA-2, only soil contamination in
Subunit 2 would be addressed.  Without additional soil remediation, contaminated soils in
Subunit 1 would continue to serve as an ongoing source of contamination to the affected
aquifers, extending the cleanup time to longer than 100 years.  The selected alternative goes
further than RAA-2 in that it would treat soils in both Subunits 1 and 2.
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Total VOCs ._
Polynuclear Aromatic
Hydrocarbons "(PNAs)
Cleanup Level (ppm)
1
10
ARAR or Other Basis
Risk"
Risld1
1176
                                              -6-

-------
               "Site-specific health protective standards were set considering ARARs and calculated
               cancer risks and hazard indices.  For carcinogens, an excess upper bound individual
               lifetime cancer risk of between 10"4 to 10"6 was acceptable.  For noncarcinogens, a
               Hazard Index less than or equal to 1.0 was acceptable.
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?    •'••'-.                     !

        Innovative technologies eliminated because of cleanup goals include:  I

;       *      None                                                  "   i / .  •  .-  .

        Standard technologies eliminated because of cleanup goals include:

      -  :•   .   .None         ;          •.             -                    -I •        "'•...'.


 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.                                       ••':'&'
      '             .                            •••             '          'i-       ; '
                                   . •      •        "  >   .                  -i-         >       .
                                     - '                   '         •       I'','-'
 75..    What measures/criteria were used to compare alternatives?,

        The following measures were used to compare the alternatives:       |
                       •         .         '     '.','.'',.''..       i-          ' .
             Cost-effectiveness                                                     ,
        -    Proven  reliability                          ,                                ,..-.•
      ,  -    Preference for treatment (vs.  containment)
                                                                         i  '      " ,
                                                                        • '!"     • •  •'

 16.     How are measures compared?     •                                j

        An evaluation of the alternatives considered shows the selected remedy to be a cost-effective
        response.  Although the cost of the selected remedy is $.1.7 million more than that of RAA-2,
        the other active remediation alternative considered in the ROD, that additional cost reduces the
        time necessary to achieve cleanup standards from more than 100 years to a  50-100-year time
        frame.  SVE is a proven technology for effectively removing VOCs frorn soil. Experience with
        SVE on similar sites in the area indicate that this technology would be effective in achieving
        the soil cleanup standards at the NSC/MM site and influenced its selection for this site.
        Through treatment, RAA-3 actively addresses both soil and ground water contamination at the
        sites, thus satisfying the statutory preference for permanent solutions  an!d remedies that employ-
        treatment as a principal element,                                   i
                                               -7-
                                                                                            1177

-------
   17.     What technical considerations were factors in selecting a remedy? Were technical
          considerations primary in the selection of the remedy?

          Technical considerations were not primary in selecting a remedy for this site.  The ability of
          the SVE technology to achieve soil cleanup standards, however, is dependent upon site specific
          factors that include chemical distribution in soil, soil lithology, and soil moisture content.
1178
                                               -8-

-------
                           National Semiconductor Corp.
          (Monolithic Memories and Advanced Micro Devices, Site #149)
                                        OU-1
                          Sunnyvale and Santa Clara, California
                                       Region 9
GENERAL SITE INFORMATION
1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil/Subunit 1 (National Semiconductor
       Corp. Facility) (rag/kg)     _

       Tetrachloroethene           9.6
       1,2-Dichlorqethene          0.93
       1,1,1-Trichloroethane       150
       Trichloroethene            4.6
       Xylenes                   3,300
       Ethylbenzene              18,000

       Soil/Subunit 2 (Monolithic Memories
       Facility) (mgVkg)

       Solvents (PCE, xylenes,     400
        TCE, chlorobenzene,
        1,2-DCE)
       PNAs (naphthalene,         270
        pyrene, phenol)
                                                             Site History
                                                 NPL Proposed:
                                                 NPL Final:
                                                 F$:
                                                 ROD:
10/15/84
7/27/87
6/14/91
9/91
                                                 ,            Background
                                                                 I             "
                                                 PRP-lead        !
                                                 PRPs:  National Semiconductor
                                                        Corporation, Advanced Micro
                                                        Devices-Arques, Hewlett Packard,
                                                        United Technologies Corporation
                                                 FS prepared by: Harding Lawsdn
                                                        Associates
 2.     What volume of material is to be remediated?
                                        .    '                •••''!.•'
       The volume of material to be remediated included:    .                     ;
                                .    .         .   •              _           ,      ....
       •     There is no reference in the FS or the ROD to the quantity of soil to be remediated in
              Subunit 1.  The FS states that the soil remedial unit at the National Semiconductor
              Corp. (NSC) and former United Technologies Corporation (OTC) sites is comprised
 .'        .    of-.     ...    •    '.     '      ''..'•;: i..      ••'•     .-.'••'
                                             •        •           '
              —     "shallow" (less than 5 feet bgs) vadose zone soils thiat require remediation of
                     volatile organic compounds (VOCs), and         . j
              —     "deeper" vadose zone soils, from approximately 5 fe^t bgs to the historical
                     surface of the water table at approximately 12 feet bgs, that require
                     remediation of VOCs.                            ,
                                           -1-
                                                                                     1179

-------
                  There is no reference in the FS or the ROD to the quantity of soil to be remediated in
                  Subunit 2 (Monolithic Memories).                                               ,
    3.      What type of site is this?                                                  •   •    -    .

           Electrical Equipment.  The two sites, although listed separately on the NPL, contaminate l:he
           same ground water; for this reason, the investigation and evaluation of cleanup options was
           combined.  Operable Unit 1 has been divided into three subunits for ease of description.

           Subumt I/National Semiconductor Corporation (NSC)

           NSC is a semiconductor manufacturing operation that occupies approximately 60 acres of land.
           This facility has been in operation since 1967 and is located in an industrial park setting.  The
           NSC site also includes the former UTC facility, which adds another 10 acres to the. site.

           Subunit 2/MonoIithic Memories, Inc., Advanced Micro Devices (AMD-Arques)

           AMD-Arques is a semiconductor manufacturing operation that ceased prpduction in 1989.
           Operations were begun at the facility, by Monolithic Memories, Inc., in 1970. The facility is in
           the same industrial park as NSC.

           Subunit 3

           Subunit 3 consists of the areas downgradieht from Subunits 1 and 2, and extends to the
           leading edge of the ground water contaminant plume.  Subunit 3 does riot contain any facilities
           that are known sources of the solvent ground water plume that emanates from Subunits 1 and
           2. The selected remedial action for this site only includes treating contaminated soil in
           Subunits 1  and 2.
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?

          Standard technolbgies considered during the identification and screening of technically feasible
          technologies were:                 '-.;•'•           .
          Containment:


          Chemical treatment:

          Physical treatment:

          Thermal treatment:

          Disposal:
Vertical barriers (grout curtain, slurry wall, steel sheet piling),
horizontal barriers (grouting, block displacement), capping (clay, soil,
asphalt/concrete, synthetic liner), surface water controls
Precipitation, asphalt batching, solidification (cement based, silicate
based, pozzolanic based, thermoplastic, surface microencapsulation)
Distillation, dewatering, filtration, screening, ion exchange, membrane
separation        .            .                            .
Incineration (rotary kiln, multiple hearth, fluidized bed, circulating bed,
infrared, mobile, advanced electric reactor, flare, catalytic)
Source soil excavation, on-site disposal, off-site disposal (landfill)
                                                                                                      0
11SO
                                                -2-

-------
5.      Was an innovative technology considered in the FS? If so, which technology?

       Innovative technologies considered during the identification and screening of technically,,
       feasible technologies were:                                       ;
                     ".,""'                          '    . ,    'I
       Biological treatment:   Aerobic and anaerobic biodegradation
       Chemical treatment:   Oxidation, reduction, hydrolysis, dechlorination, steam stripping, soil
      .                '       flushing/soil washing, solvent extraction, supercritical extraction
       Thermal treatment:    . Pyrolytic combustion, wet air oxidation, thermal desorptioh, vacuum
                             extraction, in situ vitrification, in situ radio heating
6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives matt merit a more detailed
        evaluation. For this site, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.                             j

        The RAAs developed in the FS changed in the ROD and, therefore, these are discussed
        separately below.                                                j
             ' •   '                 '                        '        .I'"''''
                 Cost Estimates for  RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)

        FS/Soil/Subunits 1 and 2                                         i
Alternative
RAA-4a
RAA-4b
Innovative Technology
Enhanced Interim Remedial Measure
(IRM)8 [ground water treatment]/soil
remediation (soil vapor extraction, SVE)
to proposed cleanup standards ,
Enhanced IRM (ground water
treatment)/soil remediation (SVE) to 10"
6 risk levels
Estimated Costs
3 Criteria
N/A
N/A '.
9 Criteria
$5,900,000
$5,900,000
       This site has existing on-site and off-site ground water extraction and treatment systems,
       which were the IRM for this site.
                                              -3-
1181

-------
           ROD/Soil/Subunits 1 and 2
Alternative
RAA-2
RAA-3
Innovative Technology
Ground water extraction and'
treatment/SVE in Subunit 2
Ground water extraction and
treatment/SVE in Subunits 1 and
2/with contingency to excavate and
aerate shallow soils unresponsive to
SVE
Estimated Costs
ROD
$5,500,000
$8,400,000
   7.     How did the cost(s) compare to standard technologies?  .

                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)

          FS/SoiySubunits 1  and 2                                   .  ,
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action/monitoring/institutional
controls
Current IRM (ground water treatment)
Enhanced IRM (ground water treatment)
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$2,400,000
$3,500,000
$4,300,000
          ROD/Soil/Subunits 1 and 2
   8.     If a standard technology was chosen, why?

         A standard technology was not chosen.
Alternative
RAA-1
Standard Technology
No action/monitoring/institutional
controls
Estimated Costs
ROD
$3,200,000
.'It
•'''it
1182
                                             -4-

-------
9.      If an innovative technology was chosen, why?
                                            '••'-.'               ':          '         '
       The selected alternative RAA-3 incorporates the use of SVE to treat contaminated soils. SVE
       was selected because it is reliable for achieving long-term reductions iin soil with chlorinated
       solvent concentrations, is generally easy to implement, and causes only minimal disturbance of
       site activities.  SVE treatment systems are durable and require replacement of few components,
       with the exception of the catalytic incineration or vapor phase carbon equipment used to treat
       off-gas.  SVE effectively reduces the toxicity, mobility, and volume of soil containing VOCs
       by removing the VOCs from the soil.  The nature of the VOCs and properties of the onsite
       soils together  with experience with this technique on other similar sites in the area indicate that
       SVE will be effective in achieving the  soil cleanup standards at the NSC site. The ultimate
       performance of this technology at the site, however, vonly can be reliably predicted based on
       full-scale operation. RAA-3 will contain migration of contaminants in the polluted aquifers.
       Under RAA-3, the  soils in Subunit 1 will be treated in addition to those in Subunit 2. This
       difference significantly reduces cleanup time from greater than 100 years (when soils in
       Subunit 1 are left untreated, they will remain above acceptable risk levels; for greater than 100
       years) to a 50-100 year range for Operable Unit  1. The selected alternative can provide a
       cleanup that achieves an acceptable risk level within a reasonable time period (50-100 years).
       If proposed cleanup standards are achieved, the residual carcinogenic risks for this alternative
       are 3.1 x W6 and a hazard index of 0.87. The selected  alternative .will attain all pertinent
       ARARs for this site.  The  state's anti-degradation policy, Resolution 68-16 (which is an
       ARAR for these sites), is met because  further degradation of a potenlial drinking water supply
        will be prevented.  If certain shallow soils that are contaminated with  lower volatility
        compounds do not  respond well to SVE, there.is a contingency plan under RAA-3 to excavate
        and aerate these soils at the surface. If this occurs, air emissions during excavation  and
        aeration will be regulated underthe Bay  Area Air Quality Management District (BAAQMD)
        Regulation 8, Rule 40. If meeting the BAAQMD permit levels requires emissions control such
        as activated carbon, disposal of spent carboff'will have to be managed in accordance with
        RCRA Land Disposal Restrictions. Thermal carbon regeneration risks associated with this
        process Will be mitigated through proper engineering controls and hazardous waste
        management  practices.                                          i       .

                                                                       -!'•       '   '     '
 10.    If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?                                          i       /

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the:  three criteria of
        effectiveness, implementability, and cost; or during the  detailed evaluation.

        Innovative technologies eliminated during the initial screening induce the following:

         •      Pyrolytic combustion was eliminated because; incinerators would not be readily
                available or permitted in California for treatment of hazardous waste-contaminated
                soils containing the chemicals of potential concern at the NSC/UTC sites.  Incinerators
                that are available  for soil treatment are located  outside California and soil excavation
                and transportation costs  would be very high relative to other treatment processes.
         •      Wet air oxidation was eliminated because it would not be applicable to soils.
         •      Reduction was eliminated because it would not be applicable  to organic constituents in
                the soil.                                                  •
                                                                                              1183

-------
                  Hydrolysis was eliminated because it would not be applicable to organic Constituents in
                  the soil.                  .
                  Dechlorination was eliminates because it would not be applicable to organic
                  constituents in the soil.                                           .       ,
                  Steam stripping was eliminated because it would not be applicable to soils.
                  Thermal desorption was eliminated because it would not be applicable to soils.
                  Soil flushing/soil -washing was eliminated because it would not be effective for the
                  organic constituents in NSC soil.                                        ''.',.
                  Solvent extraction was eliminated because it would not be applicable to soils.
                  Supercritical extraction was eliminated because it would not be applicable to soils.
                  Aerobic and anaerobic biodegradation were eliminated because these technologies
                  would not be effective for the constituents found in NSC soil.  Biological treatment is
                  not considered effective or implementable for NSC or UTC soil because of the
                  refractory nature of the chemicals.  That is, some of the chlorinated chemicals (e.g.,
                  trichloroethene) present in NSC and UTC soils are difficult to biologically degrade.'
                  Practical bioremediation techniques for these compounds has not yet been
                  demonstrated.  Furthermore, some degradation pathways lead to the production of
                  other, sometimes more hazardous, intermediate products such as vinyl chloride.
          »       In situ radio heating was eliminated because it is a new technology that has not been
                  fully developed.
          »       Oxidation was eliminated but no reason was .given.             .
          •      In situ vitrification was eliminated but no reason was given.

          Innovative technologies eliminated during the screening of the three criteria include the
          following:

          *      None           .

          Innovative technologies eliminated during the detailed analysis include the following:

          •      None                                                        .
  1L
Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
which criterion?  Which of the criteria supported the use of a standard technology?

Protection of human health and the environment was weighted heavily in selecting
RAA-3 as the remedial alternative for this site. Under RAA-2, only soil contamination in
Subunit 2 would be addressed.  Without additional soil  remediation, contaminated soils in
Subunit 1 would continue to serve as an ongoing source of contamination to the affected
aquifers, extending the cleanup time to longer than 100 years. The selected alternative goes
further than RAA-2 in that it would treat soils in  both Subunits 1 and 2.
1184
                                                                                                      0
                                                -,6-

-------
        What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
        ARAR?  What risk level was selected tp establish cleanup goals?  \'
Contaminant
Total VOGs
Polynuclear Aromatic
Hydrocarbons (PNAs)
Cleanup Level (ppm)
1
io
,
ARAR or Other Basis
Risk"
; Risk1
               "Site-specific health protective standards were set considering ARARs and calculated
               cancer risks and hazard indices. For carcinogens, an excess upperbound individual
               lifetime cancer risk of between W4 to 10"6 was acceptable.  For noncarcinogens, a
               Hazard Index less than or equal to 1.0 was acceptable.
13.
14:
 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:

 •      None
                       .'     •'          . •   V „              '•;[:-.•    -   .    .

 Standard technologies eliminated because of cleanup goals include:

 « .     None       •          '      "-.•-."..'-.-      1        .  .' '
Were treatability studies conducted on the innovative technology or standard technology?

Treatability studies were not conducted.
15.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Cost-effectiveness
             Proven reliability
             Preference for treatment (vs. containment)
16.     How are measures compared?                                  i

       An evaluation of the alternatives considered shows the selected remedy to be a cost-effective
       response.  Although the cost of the selected remedy is $1.7 million more than that of RAA-2,
       the other active remediation alternative considered in the ROD, that ildditional cost reduces the
       time necessary to achieve cleanup standards from more than 100 years to a 50-100ryear time
       frame. SVE is a proven technology for effectively removing VOCs from soil. Experience with
       SVE on similar sites in the area indicate that this technology would be effective in achieving
       the soil cleanup standards at the NSC/MM site ,and influenced its selection for this, site.
                                             -7-
                                                                                   1185

-------
          Through treatment, RAA-3 actively addresses both soil and ground water contamination at the
          sites, thus satisfying- the statutory preference for permanent solutions and remedies that employ
          treatment as a principal element.


   17.    What technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in the selection of the remedy?                     ...

          Technical considerations were not primary in selecting a remedy for this site.  The ability of
          the SVE technology to achieve soil cleanup standards, however, is dependent upon site specific
          factors that include chemical distribution in soil, soil lithology, and soil moisture content.
1186
                                               -8-

-------
                                  Purity Oil Sales, Inc.
                                          OU-2

                                    Malaga, California
                                         Region 9
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?.

       Maximum concentrations of principal
       contaminants were:

       Soil/Buried Waste/Sediment (rag/kg)
       Lead
       Ethylbenzene
       Chlorobenzene
       Toluene
       Trichloroethylene
       Tetrachloroethylene
       Xylene
       2-Butanone
       4-Methyl-2-pentanone
       Methylene chloride
.34,000
 19
 2.9
 20
 0.01
 3.2
 120
 8.7
 9.1
 0.62
                              Site History
                 NPL Proposed:
                 NPL Filial:
                 FS:
                 ROD:
                     N/A
                     12/82 ..
                     4/12/89
                     9/30/92
             Background

EPA Fund-lead
PRPs:  EPA issued! General Notice
       letters to 146 FRPs
FS prepared by: CH2M Hill, Black &
       Veatch, ICF, PRC, Ecology and
       Environment
2..     What volume of material is to be remediated?

       The volume of material to be remediated included:

       •    .  172,000 cubic yards of buried wastes and contaminated soil and sediment


3.    '  What type of site  is this?                                       ;
        '        • ;   '           '.       •   -         .         '•••'.•   -V •    '      ••
       Waste Oil. An abandoned oil recycling facility .located in an industrial area and surrounded by
       a mixture of agricultural, industrial, and commercial land.
                                      '.*',.              "I"        '      '
                  ;     '  '   • '    -' .•    •    '      '     :     •••'        \-  '            '   • '. .

TECHNOLOGY SELECTION                                         '

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Deed restriction, fences
                                            -1-
                                                   1187

-------
          Containment:
          Chemical treatment:

          Physical treatment:
          Thermal treatment:
          Disposal:
Capping (native soil, clay, synthetic membranes, sprayed asphalt,
concrete, multilayer, chemical sealants/stabilizers), vertical barriers,
horizontal barriers, grading             ,
Solidification, fixation, stabilization (encapsulation), neutralization,
precipitation
Water leaching, flotation, oil-water separation, filtration
Incineration
Excavation, off-site RCRA landfill, non-RCRA landfill, on-site
disposal
  5.      Was an innovative technology considered in the FS?  If so, which technology?

          Innovative technologies considered during the identification and screening of technically  •
          feasible technologies were:                                        .
                                                           !                  '             '

          Biological treatment:   Aerobic processes, anaerobic processes, bioreclamation
          Chemical treatment:    Solvent extraction (SVE), soil vapor extraction, oxidation, chemical
                                reduction
  6.      What was the cost estimate for the innovative technology?                    >
      *                                                          I                            .
          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation.  For this site, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.      .                             .

                   Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)                 ,
Alternative
RAA-S2
RAA-S3
RAA-S4
RAA-S7
RAA-S8
i
Innovative Technology
Soil vapor extraction/capping
Excavation/on-site incineration/soil
vapor extraction/capping
Excavation/off-site RCRA facility/
soil vapor extraction/subsurface
capping
Excavation/off-site incineration/soil
vapor extraction/capping
Excavation/on-site solvent
extraction/soil vapor extraction/
capping
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
9 Criteria
$6,901,000
$46,390,000
$54,199,000
$126,225,000
$22,450,000
1188
                                                -2-

-------
      The RAAs presented in the ROD differed from those presented in the FS and are shown
      separately below.                     :            ,  ,   •
Alternative
RAA-R3
RAA-R4
RAA-R5
RAA-R6
RAA-R7
RAA-R8
Innovative Technology
Soil vapor extraction (SVE)/RCRA
equivalent cap with slurry walls
Excavation/on-site incineration (0 to 14
feetySVE/capping
Excavation/solidification (0 to* 10
feet)/SVE/capping
Excavation/solidification (0 to 14
feetySVE/capping
Excavation/solidification (500 ppm
leadySVE/capping
Excavation/off-site treatment and
disposal (0 to 14 feet)/SVE/capping
Estimated Costs
ROD
$36,254,000
$74,756,000
$41,918,000
$53,073,000
$55,861,000
$63,659,000 .
7.     How did the cost(s) compare to standard technologies?

               Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold) .
Alternative
RAA-S1
RAA-S5
RAA-S6
Standard Technology
No action
Excavation/on^site incineration/capping
Excavation/off-site RCRA facility
Estimated Costs
9 Criteria
$0
$103,516,000
$110,995,000
The RAAs presented in the ROD differed from those presented in the FS and are shown
separately below. •
Alternative
RAA-R1
RAA-R2
-. • i **
Standard Technology
,No action
RCRA equivalent cap
Estimated Costs
ROD
$0
, $24,686,000

                                         -3-
                                                                                1189

-------
 8,     If a standard technology was chosen, why?                                       >

        A RCRA cap was chosen in addition to an innovative technology under RAA-R3,  These are
        discussed below.


 9.     If an innovative technology was chosen, why?

        Under the chosen alternative RAA-R3, soils from 0 to 14 feet will be covered by a RCRA .
        equivalent cap, and soils from 14 feet to the water table will be treated with SVE.  Soil from 0
        to 14 feet is contaminated witlroil and grease which would greatly inhibit the effectiveness of
        SVE wells.  Therefore, SVE wells will Heat soils from 14 feet to the water table. A significant
        amount of the VOCs in soil deeper than  14 feet (approximately 24,387 pounds) will be
        removed by the SVE system. Approximately 25 percent, or 17,950 pounds, of VOCs in soil
        from 0 to 14 feet are expected to be drawn into the lower layers of soil and treated by the
        SVE system. Thus, the treatment will reduce the toxicity, mobility, and volume of
        contaminants in the upper and lower layers of soil.  The SVE system will be drilled through
        the RCRA cap  and will operate in place underneath the cap. The selected alternative leaves
        waste in place in the upper layers of soil; however, the waste will be^ isolated by the cap and
        slurry walls, thus eliminating direct contact with the waste material and minimizing leaching to
        ground water.  RAA-R3 will undergo a review  every 5 years to ensure protection of human
        health  and the environment.  The selected alternative employs a treatment technology that has
        been proven effective in the field.  Where the technology has been applied, it has proved.very
        effective in removing large  quantities of contaminants.  The FS states that SVE is a technology      —t
        gaining rapid acceptance for the removal of VOCs from soils.  In addition, RAA-R3 complies      llw ••-„'
        with all ARARs.   -                                                                         "I™,  J


 10.     If an innovative technology  was not. chosen, why not? At what stage was the innovative
        technology eliminated?
                                   ,          ' ,  • •                                '                   -    ,  1*

        Innovative technologies could be eliminated from  the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria  of
        effectiveness, implementability, and cost; or during the detailed evaluation.                                !

        Innovative technologies eliminated during the initial screening include the following:'                 ':''.[
                                                                      . '             '                  :     \
                                                  •  '                                                       !:
        •      Oxidation (in situ) was eliminated because this is a theoretical, unproven technology
               for removing the contaminants of concern.                                                ,     i
        •      Chemical reduction (in situ) was  eliminated because this is an unproven technology for
               removing the contaminants of concern.    ,
        »      Bioreclamation was eliminated because  the inorganics present in the waste  may be
               toxic to microorganisms, and subsurface debris would make bioreclamatipn difficult.
        «      Aerobic processes were eliminated because they would be unsuitable for the waste
               characteristics.  Aqueous wastes do not  have sufficient organic  content to support
               biological treatment.                      .
        •      Anaerobic processes were eliminated because they would be unsuitable for the waste
               characteristics.  •                      •   •                •
1190
                                              -4-

-------
         Innovative technologies eliminated during the screening of the three criteria include the
         following:      '                              :                  I

       '  •.      None"    "'.•'".•/       .              .  -:  '         [  '.''''.'"
                                   •..••-.       •.'''•     j         • •      '  "•'' '
         Innovative technologies eliminated during the detailed analysis ineludfe the following:
                -              •      •                    '                "i '          '
         •      Solvent extraction was not considered in the ROD but was evaluated under RAA-S8 in
                the FS. No specific reason is given for its elimination.  The FS states that air
                emissions^from the solvent extraction process would have to tfe controlled if RAA-S8
                were implemented and an off-site facility would have to accent the concentrated oil
                waste for treatment, disposal, or recycling,  the FS also states! thatt further evaluation
                including bench- and/or pilot-scale studies of the process would be necessary to
                determine the effectiveness of solvent extraction at the site,   i
 11.
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so
 which criterion? Which of the criteria supported the use of a standard technology?

 Protection of human health and the environment, state acceptance, and cost were weighted
 heavily in selecting RAA-R3. The selected remedy protects human health and the
 environment through treatment of VOCs in soil deeper than 14 feet, thereby eliminating them
 as a source of ground water contamination. Also, approximately 25 percent of the VOCs in
 the upper 14 feet of soil will be drawn down to the lower layers by this action of the SVE
 system and be treated.  The California Department of Toxic Substances supports the preferred
 alternative. RAA-R3 also provides overall effectiveness proportionate .[to its costs.  This
 remedy will cost less than treatment of all the soil layers or off-site disposal            .
12.
 What cleanup goals were selected?  If the cleanup goal was based on kn ARAR, what was that
ARAR?  What risk level was selected to establish cleanup goals?     i
     -•             "              -      . . -  •             "         i:
Cleanup goals were not selected for this site in the ROD.             I
13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?                                i ,

Innovative technologies eliminated because of cleanup goals, include:  !

«      None

Standard technologies eliminated because of cleanup goals include:

•      None                         "
                                             -5-
                                                                                             1191

-------
14.    Were treatability studies conducted on the innovative technology or standard technology?

       The ROD states that treatability studies performed on site waste showed that incineration and
       stabilization were effective in treating contaminated soil. The FS based its evaluation of the
       .SVE-technology on information gained from the SVE pilot test at the Phoenix-Goodyear
       Airport Superfund site in Goodyear, Arizona.
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Cost effectiveness
             Proven reliability
             Preference for treatment (vs. containment)
16.    How are measures compared?                        .         ,

       The selected remedy provides overall effectiveness proportionate to its costs, such that it
       represents a reasonable value for the money that will be spent. By treating the contaminated
       soils by SVE, the selected remedy addresses one of the principal threats posed by the site.
      , Selecting a remedy that treats the contaminated*soil is consistent with program expectations
       which indicate that highly toxic and mobile wastes are a priority for treatment.  Such treatment
       is often necessary to ensure the long-term effectiveness of a remedy.  Lead, the other principal
       threat  at the site will not be treated; however, the cap and slurry wall will prevent direct
       contact with contaminated soil, thereby eliminating the exposure pathway for lead.
17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?          .           ,

        Technical considerations were not primary in.selecting an RAA for this site.
 1192
                                               -6-

-------
                         Rhone-Poulenc, Inc. (Zoecen) Sandpz
                                          OU-1

                                 .East Palo Alto, California
                                         Region 9
GENERAL SITE INFORMATION
1.
2.
3.
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil(mg/kg)

       Arsenic
       Cadmium
       Lead
       Mercury
       Selenium
                     54,000
                     1,500
                     13,000
                     1,900
                     1,000
                                                                Site History
                                                                     '"
                                                                         10/15/84
NPL Proposed:
NPL Dropped: 10/SJ9
FS:               j   11/91
ROD:                3/92
             Background
                  i
PRP-lead          !
PRPs: Rhone-Pouleiic, Inc.
FS prepared by: Geomatrix
       Consultants, Inc.
What volume of material is to be                                 !
remediated?                    ,        •   '.             '     |

The volume of material to be remediated included:                 '
                                         ,            '  '       i        -  .  •    . •
•      91,000 cubic yards of soil                                i
       •  '.       '      ,                     '.  '         '•      '! :       ...'..
    •       .-   .   ."    .   '         •     • -      •'   '  '  ''       i  '''""'        •
What type of site  is this?                                        j

Agricultural Chemicals. A former herbicide manufacturing and packaging facility located in
an industrial park adjacent to residential areas and wetlands.              '
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Deed restrictions, local ordinances, fencing
       Containment:          Capping (soil, concrete, asphalt), revegetation
       Chemical treatment:    Solidification/stabilization
       Physical treatment:    ..Evaporation, dust suppressants, wind screens, aeration
       Disposal:             Excavation, disposal (on-site, off-site)
                                            -1-
                                                                                    1193

-------
   5.           in innovative technology considered in the FS?  If so, which technology?

          L      we technologies considered during' the identification and screening of technically
          feaiiDie technologies were:

          Biological treatment:   Biodegradation (in situ, ex situ)
          Phys/Chem treatment:  Soil washing (in situ, ex situ), solvent extraction, vacuum extraction
          Thermal treatment:     Vitrification (in situ, ex situ), steam stripping

                                                 \       -  -         ,  :      * ^              '
   6.      What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
          formulated, costs are typically estimated  as part of ,a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. In this case, the estimated costs were calculated during an evaluation based on
          nine criteria established by the NCP.  No innovative technologies were incorporated into
          RAAs.                                    .
   7.      How did the cost(s) compare to standard technologies?                 \

                    Cost Estimates for RAAs That Include Standard Technologies
                              (selected,remedial alternative is in bold)
Alternative
RAA-A
RAA-B
RAA-C
RAA-D
Standard Technology
No action
Removal of all soil containing arsenic
concentrations greater than 5,000
mg/kg/paving/excavation/deed
restrictions/slurry wall/ground water
monitoring/surface cap
Removal of all soil containing arsenic
concentrations greater than 5,000
mg/kg/paving/excavation/deed
restrictions/ground water extraction
system and treatment
Removal of all soil containing arsenic
concentrations greater than 5,000
mg/kg/excavation/fixation of soil
containing arsenic contamination greater
than 1,000 mg/kg /slurry wall/deed
restrictions/surface cap : ,
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
9 Criteria
$900,000
$5,800,000
$6,200,000
$7,800,000
1194
                                                -2-

-------
Alternative
RAA-E
RAA-F
RAA-G
- - -
Standard Technology
Removal of all soil containing arsenic
concentrations greater than 5,000
mg/kg/excavation/fixation of soil
containing arsenic contamination
greater than 500 mg/kg/slurry
wall/deed restrictions/surface cap
Removal of all soil containing arsenic
concentrations greater than 5,000 ,
mg/kg/excavation/fixation of soil
containing arsenic contamination greater
than 500 mg/kg/grpund water extraction
and treatment/deed restrictions/surface
cap
Removal of all soil containing arsenic
concentrations greater than 5,000
mg/kg/excavation/removal of soil
containing arsenic contamination greater
. than 20 mg/kg
Estimated Costs
3 Criteiria
, N/A
N/A
N/A
9 Criteria
$9,100,000
$9,500,000
$85,000,000
8.      If a standard technology was chosen, why?

       RAA-E was selected because it protects human health and the environment from threats due to
       ingestion and  inhalation of metals in contaminated soil. Under the selected remedy, treated
       soil is returned to the ground only once it lias been stabilized and meets the performance  '
       criteria.  The selected remedy addresses the threat of exposure to contaminated soil in several
       ways. First, capping the site and implementing institutional controls removes the threat caused
       by  ingestion and direct Contact with contaminated soil. By eliminating this exposure pathway,
       it attains acceptable carcinogenic risk.  Treatment of soils to health-based cleanup levels also
       provides long-term protection from ingestion and inhalation should capping and institutional
       controls become ineffective at some point in the;future.  The selected remedy provides, long-
       term  protection within the acceptable risk range and long-term effectiveness since it utilizes
       treatment.  It will result in significant reduction in the mobility, and volume of contaminated
       soil by binding the contaminants in the soil. Implementation of RAA-E results in the
       treatment of 84  percent of the total mass of arsenic remaining after concentrations greater than
       5,000 mg/kg are removed. Results of the treatability studies indicate TCLP standards will be
       met.  It complies with all ARARs and is cost effective.
        If an innovative technology was chosen, why?

        An innovative technology wasn't selected.
                                               -3-
                                                                                            1195

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        "      Ex situ soil washing was eliminated because it would have limited effectiveness based
               on bench-scale studies, which showed it to be ineffective for the arsenic concentration
               and soil type at the site.                                  .
        •      Ex situ biodegradation was eliminated because it would be incompatible with site
               contaminants.              .           .
        •      Ex situ vitrification was eliminated because of high costs and hazardous arsine gas
               production.
        •      In situ vitrification was eliminated given the site's high ground water table and
               because it would require high rates of electrical power input to vaporize the moisture
               in the soil, and would produce large volumes of steam and arsine gas, both possibly at
               unsafe levels.
        «      In situ soil washing was eliminated because the technique Would be ineffective given
               the site's impermeable shallow soil and the high concentrations of chemicals in the
               soil. In addition, the results of bench-scale testing showed it to be ineffective for
               reducing arsenic concentration in the site soil.
        •      Vacuum extraction was eliminated because of incompatibility with the site's chemicals
               since they are not volatile.                                               ,
        •      Steam stripping was eliminated because  of incompatibility with the site's chemicals
               since they are not volatile.                                                 .
        »      Solvent extraction was eliminated because of incompatibility with the site's chemicals
               since arsenic cannot be extracted using immiscible solvents.
        •      In situ enhanced biodegradation was eliminated because of incompatibility with the
               site's chemicals and because it would not meet remedial action goals since arsenic
               cannot be degraded:               .                                         .

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      None                                        ,

        Innovative technologies eliminated during the detailed analysis include the following:

        «      None
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
       The criteria weighted most heavily in selecting a remedial alternative were long-term     .
       effectiveness, short-term effectiveness, implementability, and cost.  RAA-B and RAA-C were
       not selected because they would not provide long-term protection.  RAA-G was not preferred
1196
                                              -4-

-------
12.
because it would be very costly, implementation would be difficult aiid lengthy, and it would
pose short-term risk to the community.  RAA-F was not preferred because it would not include
a slurry wall and therefore would require more maintenance.  RAA-E was selected over RAA-
D because it is the most cost-effective option.                     ,,j                ' ..  '  ,

                      :           •.-••        '             i     '  '          ,.  'I
What cleanup goals were selected? If the cleanup goal was based'on an ARAR, what was that
ARAR? What risk level was selected to establish cleanup goals?

       On-site                                                  ;
Contaminant
Cleanup Level (mg/kg)
I • (
ARAR or Other Basis
Carcinogens
Lead
Arsenic ,
Cadmium
450 •
. 500
1,000
i Model8
! Risk"
Risk
Noncarcinogens
Mercury
Selenium
300
6,000
I Risk
Risk
                                                                      I
              "Based oh EPA's preferred method, Lead Uptake/Biokinetic Model (Version 0.5, April
              1991).
              bBased on commercial/industrial use.  For carcinogens, an excess upper-bound
              individual lifetime cancer risk of between 10"4 to W6 was acceptable.  For
              noncarcinogens, a Hazard Index less than or equal to 1.0 was acceptable.   :

              Off-site        .
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Lead . .
Arsenic
Cadmium
120
70
250
Model"
Risk"
Risk
Noncarcinogens . i •
Mercury
Selenium
100
2,000
Risk
Risk
              "Based on EPA's preferred method, Lead Uptake/Biokinetic Model (Version 0.5  April
              1991).           .   ; ...                    •'-'.'•]     .'"•.
              bBased on future residential use.  For carcinogens, an excess uppeir bound individual
              lifetime cancer risk of between IV4 to W6 was acceptable.  For noncarcinogens,  a
              Hazard Index less than or equal to 1.0 was acceptable.
                                            -5-
                                                                                   1197

-------
 13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?

        Innovative technologies eliminated because of cleanup goals include:

        •      Bioremediation
        •      Soil washing (in situ, ex situ)          ,                          .

        Standard technologies eliminated because of cleanup goals include:

        «      None                  .                                  ,
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Tr .liability studies were conducted to evaluate the effectiveness of soil washing and five
        fixation technologies.                                            ,
 75.     What measures/criteria were used to. compare alternatives?

        The following measures were used to compare the alternatives:

             Time to design/construct/operate
             Impact on nearby populations
             Waste left in place/institutional control


 16.     How are measures compared?

        RAA-B and RAA-C, which proposed institutional controls, were not preferred because they
        would not be protective of human health since they would not eliminate potential exposure to
        contaminated soil and ground water above cleanup levels. Furthermore, they would not offer '
        long-term effectiveness since they would rely on continued and proper maintenance.  While
        RAA-G would have provided the greatest protection and long-term effectiveness, it was not
        preferred because it would be very expensive and difficult to implement, and would not
        provide short term effectiveness.  It would be ineffective in the short-term since it would
        require closure of businesses, extensive excavation, and transport of contaminated materials.
        RAA-G also would take the longest time (6 years) to implement.
 17.     What technical considerations were factors in selecting a remedy?  Were technical .
        considerations primary in the selection of the remedy?
        While technical considerations were not primary in selecting a remedial alternative,
        impermeable site soil and the high ground water table did preclude the use of in situ  soil
        washing and in situ vitrification respectively.    '        \             ,

                                        "            '
                                                                                                            IfU	
1198
                                               -6-

-------
                     Sacramento Army Depot Oxidation Lagoons
                    .    :•    •      •        OU-3 , '   '  •    .   •-   j  •

                                  Sacramento, California
                                         Region 9                  [
GENERAL SITE INFORMATION

1.,,     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal'
       contaminants were:

       Soil (mg/kg)

       Ethylbenzene         2,100
       Xylene               11,000
       Tetrachloroethene     39            /
       2-Butanone          15
2.     What volume of material is to be
       remediated?
       The volume of material to be remediated included:

       •     1,000 cubic yards of contaminated soil
             Site History
NPL Proposed:
NPL Final:
FS:
ROD:
N/A
8/21/87
8/2/91
12/9/91
             Background/

Federal Facility  \
PRPs:   U.S. Army
FS prepared by: IQeinfelder, Inc.
 3.     What type of site is this?                                      r                    ,

       Military. A U.S. Army depot in a commercial/light industrial area. Until approximately 1980,
       Tank 2 was a 1,000 gallon underground storage tank used to store waste solvents.  Soil around
       the tank has been contaminated with VOCs.  The Tank 2 Operable iWt encompasses
       approximately 875 square feet.
 TECHNOLOGY SELECTION                                       J.
                     •   -  •     '    '  >          •                    I      . '  , -'      ' r  '
 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
       , technologies were:                       "                   j

        Access restriction:    Deed restrictions        ..'••-         ,
        Containment:         Capping, liner        •    ,
        Chemical treatment:   Silicate pozzolan stabilization, asphalt-based jmicroencapsulation
        Thermal treatment:    Incineration                                '
                                            -1-
                                     1199

-------
          Disposal:
Excavation, disposal (on-site, off-site)
   5.      Was an innovative technology considered in the FS? If so, which technology?

           Innovative technologies considered during the identification and .screening of technically
           feasible technologies were:                    .

           Biological treatment:   Aerobic degradation, surface aerobic biodegradation, slurry phase
                                biodegradation
           Phys/Chem treatment:  Vapor extraction,  steam stripping, soil flushing, soil washing, oxidation
           Thermal treatment:     Low temperature thermal desorption, thermal vapor treatment,
                                pyrolysis, in situ vitrification
   6,      What was the cost estimate for the innovative technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation. In this case the estimated costs were calculated during an evaluation based on nine
          criteria established by the NCR The designation of RAAs changed in the ROD.  In the
         • following tables, these changes are presented in parentheses. In addition, the present worth
          cost of three alternatives differed in the ROD compared to those presented in the FS.  The cost
          presented in the ROD is presented in parentheses for each of these three RAAS.

                   Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
1200
Alternative
RAA-2
(RAA-2b)
RAA-3
(RAA-3b)
RAA-4
(RAA-2a)
RAA-5
(RAA-3a)
Innovative Technology
In situ treatment by soil venting/ .
treatment of extracted vapor by
activated carbon/treatment of
entrained water
In situ treatment by soil venting/
treatment of extracted vapor by
activated carbon/off-site disposal of
entrained water
In situ treatment by soil venting/
treatment of extracted vapor by thermal
vapor treatment/treatment of entrained
water
In situ treatment by soil venting/
treatment of extracted vapor by thermal
vapor treatment/off-site disposal of
entrained water
Estimated Costs
3 Criteria
$614,000
$615,000
1
$483,000
$483,000
9 Criteria
$599,000
($614,000)
$599,000
($615,000)
$483,000
$763,000
($483,000)
                                                -2-

-------
>. • ' '
Alternative
RAA-6
(RAA-2c)
RAA-7
(RAA-3c
RAA-8
(RAA-4
RAA-10
(RAA-6a
RAA-11
(RAA-6)
RAA-12
(RAA-7a) V
RAA-13
(RAA-7b)
RAA-14
(RAA-8)

Innovative Technology
In situ treatment by soil venting/vapor
recovery/Xcondensation of .extracted
vapor/treatment of entrained water
In situ treatment by soil venting/vapor
recovery/condensation of extracted
vapor/off-site disposal of entrained
water
Excavation/on-site soil washing/vapor
treatment by activated carbon/off-site
disposal of wash liquid/backfill
Excavation/on-site low temperature
desorption/vapor treatment by activated
carbon/liquid stream treatment/backfill
Excavation/on-site low temperature
thermal desorption/vapor treatment by
incineration/liquid stream
treatment/backfill
Excavation/low temperature thermal
desorption/vapor treatment by activated
carbon/off-site disposal of liquid
stream/backfill
Excavation/low temperature thermal
desorption/vapor treatment by
incineration/off-site disposal of liquid
stream/backfill
Excavation/on-site surface aerobic
biodegradation/backfill
Estimated Costs
3 Criteria
$763,000
•' i
$766,000
$666,000
$764,000
$771,000
i ,( •
$786,000
$775,000
.-$701,000.
9 Criteria
$763,000
$766,000
$666,000
$764,000
$771,000
$786,000
$775,000
$701,000
7.     How did the cost(s) compare to standard technologies?
                Cost Estimates for RAAs That Include Standard Technioloj»ies
                         (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-9
(RAA-5)
Standard Technology
No action
Excavation/on-site incineration/backfill

Estimated Costs
3 Criteria

$2,f
. •-. . ••.'.'
$0
Q7,
-------
8.      If a standard technology was chosen, why?            s

        A standard technology was not selected.                            '          '.  ,  *


P.      If an innovative technology was chosen* why?

        The selected remedy will remove contaminants from the soil so that the carcinogenic risk to
        future on-site residents will be reduced from 4.5E-4 to 4.5E-6.  The noncarcinogenic HHI will
        be reduced to approximately  1.  By removing the contaminants from the soil,  the selected
        remedy permanently prevents direct exposure to harmful concentrations  in the soil or in the
        ground water.  In fact, the selected remedy will remove and destroy 99 percent of volatiles in
        the zone of maximum contamination.  The technology utilized in the selected remedy is well
        developed. The results of a treatability study suggest that a soil ventilation rate of 200 cfm
        can meet cleanup levels over a period of 6 months. The extracted vapor will be treated by gas
        phase adsorption, the typical  organic destruction efficiencies of which are 90 percent.  As an in
        situ process with treatment not limited to a specific volume (as with alternatives involving     ;
        excavation), soil  ventilation has the advantage of potentially affecting  contaminants outside the
        area of concern.  Soil ventilation does not require long-term maintenance or controls.  The
        selected remedy complies with all ARARs for the site.


10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?
                                                                               '        '          .    ltWF-""\
        Innovative technologies could be eliminated from the remedial technology selection process at            , V
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.              .

        Innovative technologies eliminated during the initial screening include the following:

        •      In situ aerobic degradation was eliminated because of effectiveness and
              implementability constraints.  The low permeability and heterogeneity of the soils on
              site could reduce effectiveness.  Low natural microbial activity and some toxicity was
              indicated  in,sample analyses.  Additionally, uniform  infiltration and recovery of
              nutrient solutions would be difficult because of soil conditions. Transport of
              contaminants to ground water would be possible without complete control of nutrient
              solutions.
        •      Slurry phase biodegradation was eliminated because of the cost of this technology.
        •      In situ vitrification was eliminated because of the cost of this technology and, once
              solidified, the treated  mass would be difficult to handle and would require placement
              at a site.
        •      Steam stripping was eliminated because of cost and implementability concerns.  This
              technology would  generate a contaminated water stream, which would require           ~
              treatment or disposal. Recovery of condensate might be difficult given the low
              permeability and heterogeneity of the soil. Demonstrated applications use auger
              equipment, which would  not be practical for this site, given its access constraints.  -
       "      Soil flushing was eliminated because of  effectiveness and implementability constraints.      *m*.
              The effectiveness of this  technology is reduced in low permeability and heterogeneous      Wm V
              soils.  This technology would be difficult to implement given the heterogeneity, of the            /
              site's soils.  Ground water contamination also would  be possible  if flushing reagents

1202

-------
              are not effectively captured.  Recovered flushing solvent requires treatment prior to
              reuse or discharge.                                         |  '
       •      Pyrolysis was eliminated because of the cost of the technology^
                             -'        '  -  -               '               i"  '  •    '   .   .
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                     ''•..••"•'.
                "         " '  '  '  •           '   '   '           - '           4    " '
                                 1     .          '         -.'•[•
      ..;• •  . ;  .None,      •.  ;         .  ..'  •      ...     •    ,-,'•''!    '   •- .'
                                                   '             •.'.,• .1 ..-•      ••'''.
       Innovative technologies eliminated during the detailed analysis include the following:
                                     ,              -           . "   •       !
       •      Low temperature thermal desorption was eliminated because this treatment technology
              is less readily available than other specified technologies.
       •      Soil washing was eliminated because, according to the results pf treatability studies,
              the commercially available wash reagents and wash procedures employed during the
              treatability testing did not reduce the leachate levels of the chemicals of concern in the
              soil below the maximum levels allowed under Land Ban regulations.
       •      Surface aerobic biodegradation was eliminated because it mig,ht not  meet Land Ban
              requirements.
11     Which of the nine criteria were weighted most heavily in selecting ite technology? Did failure
       tb meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                                        \    . • J
       Protection of human health and the environment, short-term effectiveness, and implement-
       ability were weighted heavily in selecting the chosen remedy. RAA-2b will meet the cleanup
       levels set for this site, thereby reducing the estimated total carcinogenic risk posed by the site
       by more than 90 percent to 4.5E-6 and reducing the estimated Hffl tcj approximately 1.0. In
       addition, soil ventilation is anticipated to have the greatest short-term jefftsctiveness. This
       technology presents the least amount of risk to workers and to the environment. As an in situ
       process, it minimizes contact  with the soil and produces little to no emissions during the well
       installation process. By minimizing excavation, this process  releases jless dust and fewer odors
       to the atmosphere than the other alternatives.  The chosen remedial alternative also will be  the
        simplest to construct and operate.  Placement of extraction wells is a simple process  and the
        soil ventilation system requires little monitoring or maintenance. By [constructing additional
        wells at the  site, treatment of additional soil areas can be incorporated easily.
 12.     What cleanup goals were selected? If the cleanup goal was based off. an ARAR, what was that
        ARAR? What risk level was selected to establish cleanup goals?    \
Contaminant
Carcinogens
Tetrachloroethene
Noncarcinogens
Tetrachloroethene

Cleanup Level (mg/kg)

0.2

0.2

ARAR or Other Basis

Risk-based

Risk-based

                                                                                                  1203

-------
Contaminant
Ethylbenzene
Total xylenes
2-Butanone
Cleanup Level (rag/kg)
6
23
1.2
ARAR or Other Basis
Risk-based
Risk-based
Risk-based
                 For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
                 and 10"6 was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0
                 was acceptable.           '   ,      ..  ,            ,                     _<_.."
  13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
          technology meet the cleanup goals?                                                   .

          Innovative technologies eliminated because of cleanup goals include:

          •      None

          Standard technologies eliminated because of cleanup goals include:

          •      None



  14.     Were treatability studies conducted on the innovative technology or standard technology?

          A treatability study using a computer modeling approach was conducted to assess the soil
          ventilation system of RAA-2b.  The results  of this testing suggest that a soil ventilation rate of:
          200 cfm can accomplish the remediation over a period of 6 months.

          A treatability study indicated that 75 percent of volatiles and 99 percent of semivolatiles would.
          be removed from contaminated soils using soil washing. These studies also indicated that this
          technology would not meet Land Ban requirements if the same wash liquids and procedures
          used in the treatability study were employed on the site.

          A treatability study indicated that using low temperature desorption would remove 99.9 percent
          of volatiles from the soils.



  15.      What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

                Cost effectiveness
                Proven reliability                   .     .
                Preference for treatment (vs. containment)
                                                                                                      4»
1204
                                               -6-

-------
 16.     How are measures compared?      "                            •  i
                                          • . i            "        •         I' -          ' .       •
\       The selected alternative is cost effective in mitigating the principal risk posed by the presence
        of contaminants in soil that could migrate to ground water in the future.  The estimated cost of
        the selected alternative is less than that of any other alternative except RAA-2a and RAA-3a.
        The costs of RAA-2a and RAA-3a, however, might increase as a result of stringent
        requirements for monitoring dioxin emissions. These two alternatives also were not selected
        because of potential difficulties in implementation since the treatment 'specified (extracted
        vapor is treated by thermal vapor treatment) in these alternatives is an innovative technology.
        Low temperature thermal desorp'tion was eliminated during the detailed analysis of alternatives
        because it is less readily available than other technologies. Soil washing was eliminated
        because commercially available wash reagents and wash procedure employed would not reduce
        the leachate levels of chemicals of concern to the required levels. The selected remedy
        satisfies the statutory preference for treatment as a principal element sjince it will remove
        contaminants from the soil at the Tank 2 operable unit.              !
 17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?'                        ,
                              .'••,:.'.....      .       '         I -••.-.
        The low permeability and heterogeneity of the soils on site resulted in the; elimination
        of aerobic degradation, steam stripping, and soil flushing from consideration as   *
        possible remedial technologies. Although some concern existed regarding the
        effectiveness of the selected alternative given the relatively low pernujability of site
        soils, careful design of the chosen system should overcome this concern.  Technical
        considerations, therefore, were not primary  in selecting a remedy.
                                                -7-
                                                                                                1205

-------
                      Sacramento Army Depot Oxidation Lagoons
                                          OU-4

                                   Sacramento, California
                                          Region 9
 GENERAL SITE INFORMATION

 1.      What were the principal contaminants,
        contaminant levels, and media addressed in
        this feasibility study?

        Maximum concentrations of principal
        contaminants were:
       Soil (mg/kg)

       Antimony
       Arsenic
       Cadmium
       Chromium
       Cobalt
       Copper
       Lead
       Mercury
       Nickel
       Silver
       Zinc
397
40
1,960
2,340
23
1,230
1,460
3.46
416
54
10,900
                                           Site History
                              NPL Proposed:
                              NPL Final:
                              FS:
                              ROD:
                     N/A
                     8/21/87
                     3/13/92
                     9//30/92
             Background

Federal Facility
PRPs:   U.S. Army
FS prepared by:  Kleinfelder, Inc.
       What volume of material is to be remediated?

       The volume of material to be remediated included:                              '

       •      12,000 cubic yards of soil in the lagoons
       •      3,500 cubic yards of soil in the drainage ditches and Old Morrison Creek soil
3.      What type of site is this?                                          .

       Military. "The site consists of four inactive oxidation lagoons that received most of the
       industrial and domestic wastewater generated at the site.  Most of the wastewater appears to
       have been generated by electroplating operations at the Depot.  The site also includes
       associated soil in the drainage ditches and Old Morrison Creek soil.  These are located within
       the army depot in a commercial/light industrial area.          '
                                                                                                      - fir
1206
                                           -1-

-------
 TECHNOLOGY SELECTION
                                                   .          '        •  "i     •
 4.      What standard technologies were considered for selection in this FS?
                  •-                   "-      .,•'.-''        '         !       /       , ,   '
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                       '
                                         ' •  •            ." .   •       • ~ |  •''              '
        Access restriction:     Deed restrictions, fencing
        Containment:          Capping (clay, asphalt, concrete, geomembrane), liner (clay,
                              geomembrane, composite, RCRA)           !
        Chemical treatment:    Stabilization/fixation                        '
        Thermal treatment:     Incineration
        Disposal:              Excavation, disposal (on site, off site)        !
        Was an innovative technology considered in the FS?  If so, which technology?
             •    • • .      -            •     •       .   •        •     -  :  '   \   .  ',  n   .  •
        Innovative technologies considered during the identification and  screening of technically
        feasible technologies were:                     ,                   [

        Biological treatment:   Bioremediation, vegetative uptake              •
        Chemical treatment:    Soil flushing, oxidation, soil washing         >
        Physical treatment:     Vapor extraction
        Thermal treatment:     Heat-enhanced aeration, vitrification (in situ, eic sito)
6.      What was the cost estimate for the innovative technology?
                                                                        f
       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. In this case the estimated costs were calculated during an evaluation based .on nine
       cntena established by the NCP. Many alternatives were eliminated following the three-criteria
       analyses and their designations were changed for the detailed analyses and  the ROD. These
       designation changes are presented parenthetically.
                          .        •                ,        '     - •     •  i  '       '
                Cost Estimates for RAAs That Include Innovative Technologies
(selected remedial alternative is in bold)
Alternative
RAA-4 «..
(RAA-2)
RAA-5
Innovative Technology
Excavation/on-site soil washing/on-site
treatment of wash liquid/backfill with
washed soil/off-site disposal of metals
Excavation/On-site soil washing/on-site
treatment of wash liquid/relocate
washed soil on site/off-site disposal of
metals

Estimated Costs
3 Criteria
N/
N/J
^
V
9 Criteria
$5,020,000
eliminated
                                             -2-
1207

-------
Alternative
RAA-6'
JtV/V/V" •
(RAA-3) ,
RAA-8 •
RAA-9
Innovative Technology
Excavation/on-site soil washing/on-site
treatment of wash liquid/off-site
disposal of washed soil/off-site disposal
of metals
Excavation/on-site soil washing/off-site
treatment of wash liquid/backfill with
washed sbil/off-site disposal of metals
Excavation/on-site soil washing/off-site
treatment of wash liquid/relocate
washed soil on site/off-site disposal of
metals
Excavation/on-site soil washing/off-site
treatment of wash liquid/off-site
disposal of treated soil/off-site disposal
of metals ' .
Estimated Costs
3 Criteria
N/A
N/A
N/A.
t •
N/A
9 Criteria
eliminated
$4,556,000
eliminated
eliminated
  7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-10
(RAA-4)
RAA-1 1
RAA-12
RAA-13
(RAA-5)
RAA-14
Standard Technology
No action
Excavation/RCRA cap
Excavation/off-site disposal
Excavation/stabilization/backfill with
stabilized soil
Excavation/stabilization/relocate
stabilized soil on site
Excavation/stabilizalion/off-site disposal
of stabilized soil
Excavation/stabilization/backfill with .
stabilized soil/cap
Excavation/stabilization/relocate
stabilized soil on site/cap
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A
.9
N/A
N/A
9 Criteria
$0 '
eliminated
eliminated
$2,547,000
eliminated
eliminated
$3,800,000
eliminated
1208
                                           -3-

-------
        If a standard technology was chosen, why?

        Off-site disposal of residuals in sediment was selected.
 9.
10.
 If an innovative technology was chosen, why?                      j










tolrTb^* *? °TShe ^Iamati°n C6nter-  ^ *e selected ^medy redtS
^nfdZ "?'       T6 °f Contaminants through treatment Fuithermore, me^wi!! be
removed from me site resulting in a permanent and long-term solution;;  While riste oosed bf

                                                                                   "
       coed                                                               ca
       controlled. This alternative meets all ARARs. This alternative is implemented through a
       process that has been proved in the laboratory and is believed to be fLSelSTaf
       sponsored pilot studies to evaluate the performance of certain soil washing realms ™d to

                                  TterS- A Pll0t StUdy WiU to ^ducted ^heltefo
                              m ^f *e Prt«ess Prior to ^-ale -plantation.  The selected remedy
       hehh  nH              roost expensive option, but is more effective ta prdtecting human
       health and the environment, and is more permanent that the other options
                s                ,                                 no0   Sieon process at
            stages,  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.


       Innovative technologies eliminated during the initial screening include the following:
                           aeration was eliminated because it would not be effective with metals
              Vapor extraction was eliminated because it would not be effective with metals

                     ^
             In situ vitrification was eliminated because it is an experimental Itechnolosv
             Oxidation was eliminated because it would not be effective with metals
             Bioremediation was eliminated because it would not be effective with metals
                teChn0l08ieS elimin^d during the screening of the three criteria mclude the
             Soil flushing was eliminated because its effectiveness would be decreased in tight soils
             as are found in the oxidation. lagoons or in heterogeneous zones of vi
                                           -4-
                                                                                  1209

-------
                permeabilities.  Furthermore, the even application of permeant soil flushing solution
                can be difficult and could spread contamination to a much larger mass of soil.

         Innovative technologies eliminated during the detailed analysis include the following:

         •      None
  11.     Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
         to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
         which criterion?  Which of the criteria supported the use of a standard technology?

         The criteria weighted most heavily in selecting a remedial alternative were protection of
         human health and the environment, long-term effectiveness, and short-term effectiveness.
         RAA-2 and RAA-3 were deemed-to be more permanent and provide greater long-term
         protection since the contaminants would be removed from the site.  RAA-2 will provide better
         short-term effectiveness than RAA-3 because RAA-3 involves transporting hazardous rinsate
         off site for treatment, which could temporarily increase human health and environmental  risks.
         RAA-2 was preferred over RAA-4 and RAA-5 because it provides greater permanence since
         the contaminants will be removed from the site.
  12.    What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
         ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
Arsenic
Cadmium
5 •
40
Risk3
Risk
Noncarcinogens , '
Lead
174
DTSC"
                 "Cleanup levels were established from the health-based risk assessment. For
                 carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4 to
                 10'6 was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0 was
                 acceptable.                  .
                 bThe Department of Toxic Substances Control developed health-based soil lead levels
                 (174 ppm for 1- to 6-year old children; 275 ppm for women of child bearing  age;.and
                 3,000 ppm for development construction workers).
  75.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?                ,

          Innovative technologies eliminated because of cleanup goals include:

          •      None                                       .
1210
                                                -5-

-------
        Standard technologies eliminated because of cleanup goals include:   !

        •      None                                                     ;
                                                   ' •          '•           ,! - '     "               ' '
           :.               '        '         ,        .    .'...'.      I '•    .  ,
14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were conducted for two technologies: soil washing| and stabilization.

        Soil Washing.  Because the first treatability study conducted on soil washing demonstrated low
        removal efficiencies for cadmium and lead, additional testing was conducted using two
        different processes.  The test results obtained by Process #1 suggest a J99.5 percent removal for
        cadmium and 97 percent removal for lead using a chelating agent as the leach solution and a
        reaction time of 2 hours (test run 2).  The test results obtained by Process #2 suggest a
        removal efficiency of 99 percent for cadmium and 95 percent for lead using strong acids as the
        leach solution, low operating pH, and a reaction time of 1 hour (test run 2). The results of
        these tests indicate that both processes can attain the cleanup levels required in the ROD.  Due
        to differences between laboratory testing and full-scale testing, however, pilot testing was
        recommended prior to implementing remediation.   .                 !

        Stabilization. Treatability testing of the stabilization process was conducted using a 20%
        cement:soil ratio and 10% sodium silicate (by weight).  The performance standards for the
        stabilized soil included compressive strength, permeability, and teachability. The results of
        treatability testing suggest that the stabilized soil did not pass the compressive strength
        criterion. The permeability and soluble concentration by TCLP analysis were met. However,
        the solubility criterion for cadmium by WET analysis was not achieved. The test results
        reflect partial effectiveness of the stabilization process for the treatment of Oxidation Lagoon
        site. Should stabilization be considered as the remedial alternative of choice, testing  with  new
        fixating agents (composition and/or concentration wise) will be required.   • .'   •
                                                                      ..   t .   ,

75.     What measures/criteria were used to compare alternatives?          I         "

        The following measures were used to compare the alternatives:     •   I

      ,-.      Preference for treatment (vs. containment)                    !
               Impact on nearby populations                               !
        -       Proven reliability
      '~.       .  •                      ••.'.."•"••'       ' ]•' •'       '  ',       '^

16.     How are measures compared?                                      >

        The selected remedy satisfies the statutory preference.for treatment as ia principal element.
        Soil washing will reduce heavy metals concentrations through treatment.
        RAA-3 was not selected because it would pose greater short-term risks; to nearby populations
        since soil washing fluid would be transported off site.  Soil washing was chosen because it has
        been used effectively for the removal of heavy metals from some soils
                                               6                                             1211
                                              -O-                         -v

-------
   17.     What technical considerations were factors in selecting a remedy?  Were technical
          considerations primary in the selection of the remedy?

          Technical considerations were not primary in selecting, a remedial alternative.  One
          innovative technology, soil flushing,  was eliminated because its effectiveness would be
          decreased in the tight soils found in the oxidation lagoons or in the heterogeneous
          zones of varying permeabilities.                                  ,
1212
                                                -7-

-------
                                         Signetics
          (combined with Advanced Micro Devices and TRW JMici-owave)
                                .'    .  -     •' •      '"         '•       .[•
                                   Sunny vale, California
                                         Region 9                   i
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil contaminants were not provided;
       however, trichloroethene, 1,2-dichloroethene,
       Freon 113, and 1,1,1-trichloroethane were
       detected in the underlying aquifer.
2.     What volume of material is to be
       remediated?              -:  •  .

       The volume of material to be remediated
       included:,   ,           -

       •      A volume was not provided.
                                    Site History
                       NPL Proposed:
                       NPL Dropped:
                       FS:
                       ROD:
10/84
10/89
3/91
9/91
                                    Background
                               "'•.'.-'  i
                       PRP-lead         |
                       PRPs:  Signetics Company
                       FS prepared by: Harding Lawson
                              Associates,! Engineering-
                              Science, Inc.,  Emcon
                              Associates,! Weiss Associates
3;     What type of site is this?                     •   _,          "     i

                         '        '                /•''':    '\
       Electrical Equipment. A semiconductor manufacturing facility located in an industrial park
       bordered by  light industrial and residential areas.                               ,
TECHNOLOGY SELECTION
                          '                     •             •        ^             -
.4..    What standard technologies'were considered for selection in this FS1'

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                          .
       Access restrictions:
       Thermal treatment:
       Disposal:
Deed restrictions
Incineration
Excavation, disposal (off-site)
                                            -1-
                                                                                        1213

-------
 5.      Way an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies cons'dered during the identification and screening of technically
        feasible technologies were:

        Biological treatment:   Biodegradation (enhanced, in  situ)
        Phys/Chem treatment:  Soil flushing, vacuum extraction
 6.      What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
        evaluation.  In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.       •

                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-2
RAA-3
RAA-4
Innovative Technology
Deed restrictions/continue on-going
ground water extraction and soil-vapor
vacuum extraction
Deed restrictions/enhance ground water
extraction/continue on-going vacuum
extraction •
Deed restrictions/enhance ground
water extraction and vacuum soil-
vapor extraction
Estimated Costs
3 Criteria
N/A
N/A
" N/A
9 Criteria
$3,943,000
$3,946,000
$4,113,000
7.     How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology ...
No action
Estimated Costs
3 Criteria
N/A
9 Criteria
$1,439,000
1214
                                             -2-

-------
8.      If a standard technology was chosen, why?                        |

       A standard technology was not selected.                          j                        .

                                                                      ri-  '        .  •  .    .  '   /
                              ^           •' ~       •       '        .     I      •    . '           • '-
9.      If an innovative technology was chosen, why?

       RAA-4 was selected because it will protect human health and the environment by removing
       soil contaminants with vacuum extraction techniques and through the extraction and treatment
       of ground water.  Ground water extraction prevents the further migration of the plume.  Deed
       restrictions protect against use of the aquifers before the cleanup is completed. This cleanup
       will result in a reduced cancer risk range of 3/7 X 10"4 to 6 X 10* and a reduced Hazard Index
       of 0.44.  This alternative attains all ARARs.  It reduces the toxicity, mobility, and volume of
       contaminants that could volatilize into soil gas and eventually into surface air.  Therefore, it
       also eliminates the potential for long-term exposure to volatilized contaminants that would be
       emitted from the soil and accumulate inside buildings.  The selected remedy utilizes proven
       technologies and implementation is expected to be relatively easy.  The selected alternative is
       cost effective and meets rapid cleanup requirements and accelerates tike remediation of hot
       spots..  '"          '         '   .                ,    -.''-•'•''•..'.'-"-.,.


10.    If an innovative technology was not chosen, why not? At what stage i!ww the innovative
       technology eliminated?   -.

       Innovative technologies could be eliminated from the remedial technology selection, process at
       three stages: during the initial screening; during the screening of the three criteria of        .
       effectiveness, implementability, and cost; or during the detailed evaluation. .

       Innovative technologies eliminated during the initial screening include the following:

  :     •      Enhanced biodegradation was eliminated because it would not be an effective
             . technology for the site since chlorinated aliphatic hydrocarbons are volatile at ambient
               temperatures.
       •      In situ biodegradation was eliminated because the anaerobic process for chlorinated
               aliphatic hydrocarbons results in the accumulation of undesirable end products (vinyl
               chloride) and the aerobic process is less effective for highly tialogenated compounds
               such as those in the study area.

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                                      [    ,.
   '.    '  •       "           "                      '                    I       '    '  '    :
       A three-criteria screening was not conducted.

       Innovative technologies eliminated during the detailed analysis include the following:

       •      Soil flushing was eliminated because the 811 Arques building; and the three basement
               dewatering systems would prevent the implementation of an effective  flushing system.
               The basement dewatering systems control the flow of ground water near the source
               areas and would prevent ground water from flowing through soil where flushing would
               be desired.  The addition of water beneath the buildings also 'might adversely affect
      .          .    - - •            •   ;       •   " .      •           .'    • i         .   ' r  -         \


•"•      :.    .'  '*'.   -   '  "    •   "-        •      '""•••-•  '•    '-I':"             '-•'.  1215
         •/    -      •-.-•.          .   • - '-3--.       .             I   .  '     -   "     . ' '  • .

-------
                 building foundations that were designed with dewatering systems to mitigate the effect
                 of saturated soil.
  11.
  12.
• Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology? If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 The criteria weighted most heavily in selecting a remedial alternative were protection of
 human health and the environment, reduction of contaminant toxicity, mobility, and volume,
 and cost-effectiveness.  The selected alternative was preferred because it effectively addresses
 soil and ground water contamination and because it is the most cost-effective alternative since
 it most rapidly meets all cleanup requirements for only a small additional cost.


 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level \vas selected to establish cleanup goals?
                      Contaminant
                                  Cleanup Level (ppm)   ARAR or Other Basis
                  Carcinogens
                 Total VOCs
                                                                       RWQCB*
                'Since there are no ARARs for soil, target cleanup levels were based on guidance          ||||l
                provided by Regional Water Quality Control Board (RWQCB) and the Department of
                Health Services (DHS) for the protection of ground water from leaching of chemical-
                bearing soils.                         .                                          ,
 13.
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?

Innovative technologies eliminated because of cleanup goals include:

•      None                                                     ,   •

Standard technologies eliminated because of cleanup goals include:

*      None                       .
 14.     Were treatability studies conducted on the innovative technology or standard technology?

        Treatability studies were not conducted.     •                                       •
1216
                                             -4-

-------
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Percentage risk reduction
               Cost-effectiveness              .
        -       Time to design/construct/operate


16.     How are measures compared?

        RAA-4 was preferred because it reduces site risk to acceptable levels!. Furthermore this
        alternative was selected because it is the most cost-effective since it rapidly meets all cleanup
     ,   requirements for a present worth cost of $4.1 million as compared to the $3.9 million present
        with cost of RAA-2 and RAA-3.  Essentially, the additional $0.2 million cost of RAA-4
        supports the accelerated remediation of hot spots.


17.     What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?             [ -,

       Technical considerations were not primary in selecting a remedial alternative.  The on-site
       buildings and dewatering systems, however, did preclude the use if soil flushing as a remedial
       technology.
                                             -5-
1217

-------
                         Spectra-Physics (Teledyne Semiconductor)

                                    Mountainview, California!
                                            Region 9
                                                                   Site History
                                                      NPL Proposed:
                                                      NPL Final:
                                                      FS:
                                                      ROD:
6/88
N/A
11/26/90
3/22/91
                                                                  Background

                                                      PRP-leao*
                                                      PRPs:  Spectra-Physics, Inc.
                                                      FS prepared by:  Levine-Fricke
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Soil(mg/kg)

       Tetrachloroethylene (PCE)    0.5
       Trichloroethene (TCE)       18
       1,2-Dichloroethene (DCE)     2.2
       Toluene                     1
   2.      What volume of material is to be
          remediated?
          The volume of material to be remediated included:                           '

          "      Approximately 6,000 cubic yards of soil containing concentrations of TCE above 2.5
                 ppm will be treated.
          What type of site is this?

          Electrical Equipment.  The Teledyne Semiconductor site comprises two Superfund sites:  the
          Teledyne semiconductor site, a semiconductor manufacturing facility, and the Spectra-Physics
          site, a laser and related components manufacturing facility;  The contaminated medium at the
          Teledyne Semiconductor site is ground water. This analysis addresses the Spectra-Physics site
          since the contaminated media are soil and ground water.                   V
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in^this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:

          Access restriction:     Deed restrictions, fencing, zoning restrictions
          Containment:          Capping (clay, asphalt, concrete)
          Physical treatment:     Air stripping
                             ',*"-;
1218
                                               -1-

-------
Disposal:
Excavation, RCRA landfill (on site, off site)
Was an innovative technology considered in the FS?  If so, which technology?

.Innovative technologies considered during the identification and screening of technically
feasible technologies were:                                       !    „

Biological treatment:   Enhanced biodegradation, soil aeration (composting)
Phys/Chem treatment:  Soil flushing, soil vapor extraction, steam extraction and ELF radio
                      frequency heating                          <
Thermal treatment:     Vitrification                               i
                                                                -
What was the cost estimate for the innovative technology?           !      .•."-.

During the initial screening process, in which technically feasible teclinologies are identified
(prior to the formulation of RAAs), the FS does not quantify costs.  Mies the RAAs have been
formulated, costs are typically estimated as part of a three-criteria-screening process
(effectiveness, implementability, and cost) to identify alternatives thatj merit a more detailed
evaluation. For this site, the estimated costs were calculated during ah evaluation based on
nine criteria established by the NCR                               !
Cost Estimates for RAAs That Include Innovative Technologies
(selected remedial alternative is in bold)
Alternative
RAA-4
RAA-5
RAA-6
Innovative 'Technology
Expansion of existing soil vapor
extraction system* and continued
operation of existing ground water
extraction system
Expansion of existing soil vapor
extraction system and additional ground
water extraction
Expansion of existing soil vapor
extraction system8 and continued
operation of existing ground water
extraction system to achieve
background levels in ground water
Estimated Costs
3 Criteria
N/A
KT/A
N/A
9 Criteria
$2,729,595
$4,882,162
. $2,676,845
"In 1987, Spectra-Physics installed a soil vapor extraction system as ail interim removal action
to reduce VOCs in the soil.
                                      -2-
                                                                 1219

-------
 7.      How did the cost(s) compare to standard technologies?

                   Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
Standard Technology
No action
Institutional actions
Soil excavation with existing ground
water extraction
Estimated Costs
3 Criteria
N/A
N/A
N/A ,
9 Criteria
N/Aa '
$794,811
$6,723,538
         "The present worth cost of RAA-1 was not given.  According to the FS, the total direct and
         indirect costs for this alternative are $1,280, and the annual operation and .maintenance costs
         are $53,160.
 8.      If a standard technology was chosen, why?

         A standard technology was not chosen.
 9.     If an innovative technology was chosen, why?

        The proposed plan recommended RAA-5 as the selected alternative because of the additional
        ground water extraction wells required under this alternative.  Based on comments provided by
        Spectra-Physics during the public comment period, and a review of the information contained
        in the administrative record for the sites, the California Regional Water Quality Control Board
        (RWQCB) and EPA selected RAA-4 with a requirement that the effectiveness of the system be
        evaluated in 2 years.                             ,                                 •

        The selected alternative, RAA-4, was chosen because this alternative provides soil treatment by
        expanding the existing soil vapor extraction system.  This technology will reduce the volume
        of volatile organic compounds (VOCs) in site soils and reduce the risks associated with
        contaminants leaching out of soils into the ground water. The soil vapor extraction system
        will be designed to remediate VOCs in the upper .10 feet of soils in excess of 2.5 ppm TCE
        and soils in excess of 0.5 ppm TCE below 10 feet.  This technology removes the threat of
        migration and exposure to VOCs in soil.  Soil remediation under RAA-4 will reduce toxicity,
        mobility, and volume of contaminants through treatment. Since a vapor extraction system has
        operated at the site since February  1989, the technology under the selected remedy is already
        partially implemented and the construction of additional soil vapor extraction wells is reliable
        and easily implemented.  The existing system his proved effective at removing VOCs from
        soils; the removal to date represents most of the estimated total VOCs in soils in the area of
        the site where the system has been installed. Vapor extraction also has relatively low capital
        and operating and maintenance costs compared to other removal technologies. In addition, this
        alternative complies with all ARARs.
1220

                                               -3-

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                              :
     "               *"        .      -               '       '         ; t     v.    ,.",....
       Innovative technologies could be eliminated from the remedial technoloj?y selection process at
       three stages: .during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      Chemical reduction was eliminated'becaus'e it would not be applicable for inorganic
               metals. This technology has not been utilized successfully for removing metals or
               treating soils (U.S. EPA, 1988); chemical extraction has been u«ed primarily for
              . treating sludges  contaminated with hydrocarbons.              I
        •      In situ vitrification was eliminated because it would not be applicable to the site given
               the presence of ground water and variable soil conditions at this site.  In addition, this
               technology is considered impractical when applied over large areas because of the
               heterogeneity of the mass to be vitrified, maintenance of process control over  large
               areas,  and the presence of shallow ground water (U.S. EPA, 1985).
        •      Pyrometallurgical reprocessing was eliminated during the mitial screening stage for
          .     tailings in the Smelterville Rats and the CIA because it would  krt be feasible with
               low-concentration wastes and would be applied more appropriately to higher
               concentration materials.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:                                                         ;
                                - .-*-        '              .                  *i            .  f   > \
        •      In situ leaching for metals was eliminated based on its anticipated lack of
               effectiveness, problematic implementation, and/or high costs relative to other equally
    (           effective options. The history  of using this technique for uranium recovery suggests
               that aquifer protection and restoration could be long-term problems due to the
               potentially hazardous nature Of the solvents used.  Treatability  studies conducted by
          .the University of Idaho using site samples showed that a strong oxidant is required to
                dissolve the amounts of metals at the site, and acceptable metals extraction  occurred
                only under extreme acidic conditions. The recovered leach solution would produce a
                waste sludge that probably would be contaminated with the mejtals of concern and
                would require treatment and disposal.                        !
         •      Hydrometallurgical reprocessing was eliminated because metals' mobility in the
                processed tailings would increase substantially because of grinding and classification
                during processing.  Additionally, neither suitable milling or refining facilities are
                currently available to handle site materials nor is a suitable disposal site available for
                subsequently produced materials. This process .also would have a high capital cost.

         Innovative technologies eliminated during the detailed analysis include the following:      '

         •      None                                           i
                                                 -4-
                                                                                                 1257

-------
   12.    Wliat cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
          ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (ug/kg)
ARAR or Other Basis
Carcinogens
Tetrachloroethylene
(PCE)
Trichloroethene (TCE)
5
5
State*
State8
Noncarcinogens
Toluene
100
State8
                 "State of California's maximum contaminant level.


   J3.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          "      None                                                            .

          Standard technologies eliminated because of cleanup goals include:     -

          •      None                                        :
   14.     Were treatability studies conducted on the innovative technology or standard technology?

          Treatability studies were not conducted.  '                                      .


   15.     What measures/criteria were used to compare alternatives?

          The following measures were used to compare the alternatives:

               Cost-effectiveness
               Proven reliability
               Preference for treatment (vs.  containment)


   16.     tiow are measures compared?

          The ROD states that the selected remedy is cost effective. An effective vapor extraction
          system has been operational at the site since 1989.  The decrease in VOC removal rate after 5
          weeks of operation shows that the system effectively removed the majority of VOCs in soils in
          a relatively short time period.  The chosen remedy utilizes permanent treatment technologies to
1232
                                                -5-

-------
       the maximum extent practicable and satisfies the statutory preference for remedies that employ

       treatment as a principal element.                          .
           •                                   '          ~              . i      '      '        '


17.     What technical considerations were factors in selecting a remedy? Were technical

       considerations primary in the selection of the remedy?                j

            •    ' •   ,         '         '            "  •  '     ••     •'   .f:  '     •    '  •
       Technical considerations were not primary in selecting a remedy for this; sits.
                                              -6-
                                                                                          1223

-------
                                 Valley Wood Preserving, Inc.

                                        Turlock, California
                                             Region 9
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Surface Soil (mg/kg)

       Arsenic                     140
       Hexavalent chromium        30

       Subsurface Soil (mg/kg)

       Arsenic         .            232
       Hexavalent chromium        68
                                                                   Site History

                                                      NPL Proposed:        6/88
                                                      NPL Final:           3/89
                                                      FS:                  6/91
                                                      ROD:                9/91

                                                                   Background

                                                      PRP-lead
                                                      PRPs:    Valley Wood Preserving, Inc.
                                                      FS prepared by:  Geosystem
                                                             Consultants, Inc.
          What volume of material is to be remediated?

          The volume of material to be remediated included:

          •      15,000 cubic yards of soil
   3.      What type of site is this? •        .        .                ,                    ;

          Lumber and Wood Products. An inactive wood preserving facility located in an agricultural
          and residential area.                                              '.'•..'
   TECHNOLOGY SELECTION                                            ''.-..'•

   4.      What standard technologies were considered for selection in this FS?                  .,  '
                                                                                    i

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:

          Access restriction:    Fencing
          Containment:         Capping  (synthetic membrane, bentonite, asphalt arid/or concrete,
                              multilayer), vertical barriers, hydraulic barriers
          Chemical treatment:   Fixation
          Thermal treatment:    Incineration (flame-reactor)
1224
                                              -1-

-------
       Disposal:
Excavation, off-site disposal
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:

        Surface and Subsurface Soil

        Chemical treatment:    In situ soil flushing, soil washing
        Thermal treatment:     In situ vitrification
6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies
       (prior to the formulation of RAAs), the FS does not quantify costs.
       formulated, costs are typically estimated as part of a three-criteria
       (effectiveness, implementabittty, and cost) to identify alternatives that merit
       evaluation. In this case, the estimated costs were calculated during an
       nine criteria established by the NCP.
                                        Alter 1
            are identified
       (the RAAs have been
screening process
         a more detailed
    evaluation based on
                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-3
Innovative Technology
In situ soil flushing of soil with
hexavalent chromium/excavation and
fixation of soil with arsenic
Estimated Costs
3 Criteria
N/A
I
I - • •
9 Criteria
$332,000 to
$1,323,000*
       *The range of costs depends on the volume of arsenic containing soil.
                                                                       -t
7.      How did the cost(s) compare to standard technologies?               L  K

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)      !
Alternative
RAA-1
RAA-2
Standard Technology
No action
Capping
Estimated Costs
3 Criteria
N/A
N/A
. 9 Criteria
$0
$216,000
                                             -2-
                                                                                          1225

-------
Alternative
RAA-4
Standard Technology
Excavation/fixation
Estimated Costs
3 Criteria
N/A
9 Criteria
$1,119,000
to
$1,853,000*
        'Cost depends on the volume of soil remediated.
8,     If a standard technology was chosen, why?

       RAA-4 was selected because it provides the greatest overall protection to human health and,  .
       the environment. Fixation of contaminated soil reduces direct contact and inhalation risks, and
       protects ground water, thereby reducing site risks to 10"6.  This alternative will be effective
       since fixed soil will either meet leaching criteria or be placed in lined cells. Fixation
       eliminates the teachability and mobility of hexavalent chromium and arsenic in soil.  It
       complies  with all ARARs. The long-term effectiveness of fixation will be dependent on long-
       term maintenance and monitoring of the fixed soil mass and liner system. If the technique is
       implemented properly and institutional controls are maintained, fixation is expected to provide
       long-term effectiveness.  It is implementable and all equipment and services are readily
       available  through several companies.
9.     If an innovative technology was chosen, why?

       An innovative technology was not selected.
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                             .

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

       •      In situ  vitrification was eliminated because  the technology is still in the developmental
               stage and widespread application has not been reported.  In addition, the near-surface
               soil at the site consists of fine-grained sands to silty sands which are likely to have
               high permeability and the ground water table is at depths of 4 to 8 feet which is too
               shallow for implementing in situ vitrification.  Field testing has not shown the   ;.
               technology to be effective in either high permeability soil or where the ground water
               table is shallow.    •                                                            ;
       •      Soil washing was eliminated because of the degree of site disturbance, the need to
               recondition the soil following treatment and prior to backfilling, and the associated
               higher cost.,                              ,


  1226
1
                                               -3-

-------
       Innovative technologies eliminated during the screening of the three criteria include the
       following:
                                                                        i                "
                     '     •   '  '                 :                    '•    i        '
       •      None                                       ,          ;  |

       Innovative technologies eliminated during the detailed analysis include the following:

       •      In situ soil flushing was eliminated because site conditions might limit the feasibility
               and effectiveness of the technology. This technology might not comply with all
               ARAR.S  if site conditions limit its ability to achieve ground water cleanup standards.
               Its long-term effectiveness would be uncertain since the technology is unproved and
               would require treatability studies.  It would not be acceptable jto the state or the ,
               community until its effectiveness is proved.
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedial  alternative jwere protection of
       human health and the environment, compliance with ARARs, long-term effectiveness, and
       state and community acceptance.  RAA-4 was selected because it best! protects human heath
       and the environment,  is the only alternative that complies with all ARAKs;, is more effective,
       and is acceptable to the state and community because it is  a proved technology.
                                           '            i        '         ^     '              -
       RAA-3, in situ soil flushing was eliminated because its overall protection, effectiveness, and
       ability to comply with ARARs is uncertain.                         '
12.    What cleanup goals were selected?  If the cleanup goal was based on\ an ARAR, what was that
       ARAR? What risk level was selected to establish Cleanup goals?     l
                                                         ...      -i                 *
               Surface Soil                          .
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
Arsenic
Hexavalent chromium
2 . '-
- "- 4 ' -•



Risk*
Risk
               "Surface soil cleanup levels are based on potential health risks from inhalation and
               direct contact and correspond to a 10"6 excess cancer risk.    i..   .
                                      •• -.       .     ", . •                 i'        •'  •
               Subsurface Soil                                          !
Contaminant
Cleanup Level (ppb)
ARAR lor Other Basis
Carcinogens
Arsenic
Hexavalent chromium
: 5
5
i DIM*
DLM
•;'.-•'• '• -4- . .-. > ;. : . ! ' . '.-. •
                                                                                               1227

-------
                   "Subsurface soil cleanup levels are based on the Designated Level Methodology for
                   characterizing waste in soil adopted by the Central Valley Regional Water Control           ^"^  \
                   Board in June 1989. The levels are established to protect ground water from                   - *
                   contaminated leachate from the soil.              .


     73.     Was the innovative technology eliminated because of the cleanup, goals?  Could the standard
            technology meet the cleanup goals?     *                            ,'               .

           = Innovative technologies eliminated because of cleanup goals include:

            "      In situ soil flushing                                              ,

            Standard technologies eliminated because of cleanup goals include:

            »      Capping


     14.     Were treatability studies conducted on the innovative technology or standard technology?

            Treatability studies were not conducted.                           .


     75.     What measures/criteria were used to compare alternatives?     '•'.',
                                                               •  " '  •     '                           •    ^Hf \
            The following measures were used to compare the alternatives:                                          )

                   Proven reliability
                   Preference for treatment (vs.. containment)             ,         .                  ,
                   Community acceptance


     16.     How are measures compared?

            The selected  technology was preferred because it is proven and reliable.  In situ soil flushing
            was not acceptable to the state or community because its effectiveness was unproved at the
            site.  Treatment was preferred over containment because capping would be only partially  '
            protective of ground water, it would leave contaminants on site, it would not attain ground  ,
            water ARARs, and it would not be acceptable to the state or community.    -                ,


     17.     What technical considerations were factors in selecting a remedy?.  Were technical
            considerations primary in the selection of the remedy?

            Technical considerations were primary  in selecting a remedial alternative. In situ soil flushing
            was not selected because site conditions (not specified) might limit  its feasibility and thereby
            make its overall protection  and effectiveness uncertain.                                      ,
1228       .   .        "   -       .     v.     -.,
                                                   -5-

-------
                                 Van Waters & Rogers
                                    San Jose, California
                                         Region 9
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
    '   contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:      •

       Soil (mg/kg)          '

       Tetrachloroethene (PCE)     250
       Trichloroethene (TCE)       37
       1,1,1-Trichloroethane (TCA)  997
       Acetone                     500
       1,1-Dichloroethene            24
       1,2-Dichloroethene            7.5
       Methylene chloride            210
       Vinyl chloride               1
                                                                Site History
                                                                    '
                                                   NPL Proposed:    i    10/84
                                                   NPL Dropped: 10/89  .
                                                   FS:                  2/91
ROD:
                                                                        9/91
                                                                Background
                                                   PRP-lead
                                                   PRPs: Univar Coiporation
                                                   FS prepared by:  Gieosystem
                                                          Consultant!!, Inc.
2.      What volume of material is to be remediated?

        The volume of material to be remediated included:
              8,100 cubic yards of soil containing greater than 10 mg/kg PCpE, TCE, and TCA-
              46,000 cubic yards of soil containing 1 mg/kg volatile organic compounds (VOCs)
 3.      What type of site is this?                                       i
  -              '          '   '            .       "         -         .  r~ ,.-•'-.
        Chemicals and Allied Products. A commercial chemical storage, handling, and distribution
        facility located in a commercial and  industrial area.    .
 TECHNOLOGY SELECTION                                         i
-'•         ;  '~r~-       ]               '    '      ,     .        •    .    Jr..   ..••.•.•:
 4.      What standard technologies were considered for selection in this FS?              •

        Standard technologies considered during the identification and screeniing of technically feasible
        technologies were:                     ^           •''.-[

        Access restrictions:    Deed restrictions
                                            -1-
                                                                                       1229

-------
         Containment:
         Physical treatment:
         Thermal treatment:
         Disposal:
Capping (synthetic membranes, low-permeability soil, bentonite,
asphalt, concrete, multilayer), slurry wall, grout curtain, sheet pile wall,
hydraulic containment                                       .  ,
Aeration
Incineration
Excavation, disposal
 5.      Was an innovative technology considered in the FS? If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:    -

         Biological treatment:  Bioremediation                                  .
         Chemical treatment:   Soil flushing, soil washing
         Physical treatment:    In situ vapor extraction
         Thermal treatment:    In situ air/steam stripping, on-site steam stripping, low-temperature
                              thermal desorption
 6.      What was the cost estimate for the innovative technology?                '

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation.  In this case, the estimated costs were calculated during an evaluation based on
         nine criteria established by the NCP.

                  Cost Estimates for RAAs That Include Innovative Technologies
                             (selected remedial alternative is in bold)
Alternative
RAA-3
RAA-4
RAA-5B
Innovative Technology '
In situ vapor extraction (ISVE) of soil
containing greater than 10 ppm PCE,
TCE or TCA/ground water remediation
Capping of soil containing greater
than 1 ppm VOCs/in situ vapor
extraction of soil containing greater
than 10 ppm PCE, TCE, or TCA/
ground water remediation
Excavation of soil containing greater
than 1 ppm total VOCs/low-temperature
thermal desorption/ground water
remediation ,
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria
$4,931,000
$4,997,000
, *
$17,699,000
to
$17,756,000a
1230
                                               -2-

-------
          Alternative
        Innovative Technology
                                                                      Estimated Costs
3 Criteria
 9 Criteria
         RAA-5C
In situ vapor extraction of soil
containing greater than 1 ppm VOCs/
ground water remediation ,
   M/A
$11,012,000
       "Range of costs is dependent on indirect capital costs.
7.      How did the cost(s) compare to standard technologies?             \
           ••  "     '     .          '  .             •        ' '          • •  i
                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)   .1 •  .
8.
Alternative
RAA-1
RAA-2
RAA-a
Standard Technology
No action
Capping of all soil containing greater
than 1 ppm VOCs/ground water
treatment
Excavation of all soil containing greater
than 1 ppm VOCs/on-site aeration/
ground water remediation
Estimated Costs
3 Criteria
N/A -
• '3
•. ' "]
If a standard technology was chosen, why?
N[/A
VA
9 Criteria
$2,309,000
$4,335,000
$11,876,000
to
$11,934,000

       . A cap to enhance soil vapor extraction was selected.
9.-,    If an innovative technology was chosen, why?             - ,    •  ,!  --      ', v

       RAA-4 was selected because it will be protective of human health and die environment by
       reducing the potential excess cancer risk associated with the ingestion or inhalation of organic-
       containing ground water to less than 1 X 10"4.  The selected alternative provides a greater '
       degree of protection since it combines capping which will prevent direct contact with site soil
       and leaching of VOCs from soil to ground water and ISVE, which will reduce VOC
       concentrations in soil.  It complies with all ARARs and is cost-effective.  Through capping
       this alternative results in reduced contaminant volume, toxicity, and mobility and thereby
       provides permanence, and long-term effectiveness.  It will be easily implemented as the
       construction of the ISVE system is straightforward. The implementation of this alternative
   ,    will not create any unacceptable short-term risk.                  ,|            ,
                                              -3-
                                                                                           1231

-------
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
        technology eliminated?

        Innovative technologies could be eliminated from the remedial technology selection process at
        three stages:  during the initial screening; during the screening of the three criteria of
        effectiveness, implementability, and cost; or during the detailed evaluation.

        Innovative technologies eliminated during the initial screening include the following:

        "      Bioremediation was eliminated because most of the contaminants of concern requiring
               remediation are chlorinated organic compounds that are generally toxic to most
               microorganisms and have not been proven to be amenable to bioremediation.
               Additionally, the low permeability of the native vadose soil would make installation of
               a system capable of uniformly delivering oxygen and nutrients difficult.  This process
               is therefore unlikely to be successful at this site.                                  •
        •      Soil flushing was eliminated because it was not considered technically implementable
               at the site because the low permeability of the site soils might preclude the installation
               of an adequate solvent delivery system.                                     '
        •      In situ air/steam stripping was eliminated because it was not considered technically
               implementable at the site as the technology is relatively unproven for most of the
               chemicals of concern.  Additionally, the degree of site disturbance is relatively high as
               compared to other, lower cost in situ remediation technologies.  Accessibility of die
               soils to be remediated also was a limitation to the application of the technology due to
               the depth of soil and surface obstructions.  The maximum depth that .can be remediated
               is 30 feet and soil beneath surface structures can not be accessed.
        •      On site steam stripping was eliminated because it  is relatively unproven.  Additionally,
               the cohesive, fine-grained nature of the soils at the site would require considerable
               effort and energy (fuel) to be expended to effectively strip the organic chemicals from
               the soil and then dry out the treated soil.
        •      Soil washing was eliminated because it is not well proven for treating fine grained soil
               containing organic chemicals.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      None
                                                                                                »
        Innovative technologies eliminated during the detailed analysis include the following:

        "      Low-temperature thermal desorption  was eliminated because it would require
               excavation, which would pose short-term risk. Additionally, it would not be practical
               to implement this technology at an operating facility and it would not be cost-effective.
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                               t         •      .          . ._
       Protection of human health and the environment, short-term risk, and implementability were
       the criteria weighted most heavily in selecting a remedial alternative.  RAA-4 was preferred
       because it would  provide greater protection than RAA-2 and RAA-3.  RAA-4 was preferred
 1232
                                              -4-

-------
       over RAA-5 because it will be more easily implemented and will not create an unacceptable
       short-term risk.                                s           - •   j  • -
12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
       ARAR?  What risk level was selected to establish cleanup goals?

       Due to inaccessibility problems in the area of the underground tanks, soil will be remediated in
       two phases.  Both interim and final soil cleanup requirements were established.  Interim soil
       cleanup levels will minimize the potential for migration of contaminants to ground water. The
       final soil cleanup levels will be accomplished after the underground tanks are removed.
Interim soil cleanup levels /
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens
Tetrachloroethene
Trichloroethene
1 , 1 , 1 -Trichloroethane
10
10
10
Model8
Model
Model

              aARARs are not available for soil and therefore the objective j of soil remediation was
              to minimize the potential impact of contaminated soil on ground water.  The SESOIL
              model was used to determine an acceptable concentration of contaminants at which no
              leaching of chemicals to ground water could occur.        ;                 ,
                                                                    • I          : •         .  -
              Final soil cleanup levels                                 !
Contaminant
. Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens ' ^
Total volatile organic
compounds
1

Model8
               "ARAKs are not available for soil and therefore the objective] of isoil remediation was
               to minimize the potential impact of contaminated soil on groiimd water. The SESOIL
               model was used to determine an acceptable concentration of contaminants at which no
               leaching of chemicals to ground water could occur.
13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?                              j    .      >

        Innovative technologies eliminated because^ of cleanup goals include:;

        •      None             ,            :
                                              -5-
1233

-------
         Standard technologies eliminated because of cleanup goals include:

         •      None
  14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were conducted for aeration, low-temperature thermal desorption, and in
         situ vapor extraction. ,                               .           ,,
 15.     What measures/criteria were used to compare 'alternatives?

         The following measures were used to compare the alternatives:

              Risk level achieved
              Cost-effectiveness
              Impact on nearby populations
              Preference for treatment (vs. containment)
 16.    How are measures compared?

        The preferred alternative was selected because it incorporates two soil remediation
        technologies and therefore provides greater protection than RAA-2 and RAA-3. .RAA-5 was
        eliminated because it would pose short-term risk to nearby populations and workers since it
        would involve open excavation during which significant quantities of organic vapors would be
        expected to volatilize particularly if aeration of soils was used as a principal means of
        remediation. RAA-5 also was not. preferred because it would be the most difficult to
        implement and would involve extensive site modifications which would not be practical at an
        operating facility.  Finally, RAA-5 would not be cost-effective.
ill"1
 17.    What technical considerations were factors in selecting a remedy?  Were technical
        considerations primary in the selection of the remedy?

        Technical considerations were not primary in selecting a remedial alternative. The low soil
        permeability and fine-grained nature of the soil, however, precluded the use of several
        innovative technologies  including bioremediation, soil flushing, air/steam stripping, and soil
        washing.
1234
                                              -6-

-------
                   Westinghouse Electric Corp. (Sunnyvale Plant)
                        •         ;       ''••-."'         '      :' .   i •
                                   Sunnyvale, California             I
                                         Region 9
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant .levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:
       Soil (rag/kg)

       PCB
42,000
2.     What volume of material is to be
       remediated?

       The volume of material to be remediate^ -
       included:

       •     400 cubic yards of soil
                             Site1 History
                NPL Proposed:
                NPL Final:
                FS:
                ROD:
                     10/15/84
                     6/1/86
                     12/90
                     10/91
             Background
                j
PRP-lead        |
PRPs:  Westinghoiiise Electric Corp;
FS prepared by: E1MCON Associates
3.     What type of site is this?                  ,                     !

       Electrical Equipment.  A manufacturing facility that previously manufactured and stored
       transformers. The facility is located in a light industrial, commercial^ and residential area.
 TECHNOLOGY SELECTION                                .    .     I
' '         •            .'-,--                    '  '              !~           •
 4. ~    What standard technologies were considered for selection in this FS?
                                            ,   •       '   -    -       '!         ".''''•".'
        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
                                                              '  "    i •  -     '
        Access restriction:     Deed restrictions                     '.  • !-                .
        Containment:          Capping (RCRA, asphalt, concrete, soil)    |
        Chemical treatment:    Fixation                       '     '    \
        Thermal treatment:     Incineration (rotary kihi, circulating bed, infTiared)        ;
        Disposal:             Excavation
                                                                                       1235
                                             -i-

-------
         Was an innovative technology considered in the FS?  If so, which technology?

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:                                    .            ,

         Biological treatment:   Biodegradation (ex situ, in situ)
         Chemical treatment:   Solvent extraction (in situ, ex situ), dechlorination, oxidation
         Thermal treatment:    In situ vitrification
 6.      What was the cost estimate for the innovative technology?

         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation.  In this case, the estimated costs were calculated during an evaluation based on
         nine criteria established by the NCP.  No innovative technologies were incorporated into
         remedial alternatives.                                       .
 7.      How did the cost(s) compare to standard technologies?

         The volume of contaminated media to be remediated was changed for two alternatives in the
         ROD. These changes are presented in a separate table below.

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
Alternative-
RAA-1
RAA-2
RAA-3
RAA-4
Standard Technology
No action/monitoring
Soil cap/ground water hydraulic .
containment
Soil excavation to 10 inches/off-site
incineration or disposal/capping/ground
water containment
Soil excavation to 4 feet/off-site
incineration or disposal/capping/ground
water containment
Estimated Costs
3 Criteria
N/A
N/A
N/A
' •*-,
N/A
9 Criteria
$3,555,000
$5,838,000
$5,887,000
• , or
$6,148,000a
$6,060,000
or
$7,367,000
-------
        ROD
Alternative
RAA-1
RAA-2
RAA-3A
RAA-3B
RAA-4A
RAA-4B
Standard Technology
No action .
Soil capping j
Excavation to 8 feet/off-site disposal/capping/
ground water containment
Excavation to 8 feet/off-site incineration/ [
capping/ground water containment *
Excavation to 32 feet/off-site disposal/capping/ j
ground water containment
Excavation to 32 feet/off-site incineration/
capping/ground water containment
Estimated Costs
: ROD
$3,744,000
, , $6,474,000
$6,874,000
$8,263,000
$7,840,000
$12,882,000
&•     If a standard technology was chosen, why?                         !

        RAA-3B was selected because it protects human health and the environment since it addresses
        soil with greater than 25 ppm PCB, which represents a lO"6 risk in the! industrial setting. This
        soil will be removed to a depth of 8 feet and incinerated off-site. Eiglit feet of clean soil, an
        asphalt cap, and land use restrictions will further prevent potential contact with the surface or
        subsurface soils. Subsurface soil will be remediated because it would pose a potential risk to
        future site workers.  Land use restrictions for excavation or future development in the area
        where contaminated soils remaining at depths greater than 8 feet will prevent future excavation
        and therefore exposure to buried contaminated soil.  Soils left in-place do not represent a
        principal threat since they are located at depths greater than 8 feet and do not significantly
        affect ground water. The decision to choose the more expensive option of incineration is
        based on the strong statutory preference for treatment. Additionally, these soils are classified
        as principal threat soils and such wastes are to be treated rather than kind (disposed wherever
        practical [NCP, 40 C.F.R. 300.430(a)(l)(iii)]. Incineration reduces toxicity,  mobility,  and
        volume by destroying the PCBs in the excavated soil.  Incineration, therefore, is the more
        permanent option for excavated soil since PCBs are destroyed. This alternative is technically
        and administratively feasible.  The technologies  are practical and provein.  No short-term risk
        of exposure will be posed to nearby residents and proper health and safety procedures can
        mitigate the risk posed during excavation.  This  remedy complies with ARARs and is cost
        effective.                                  -                 •
9.      If an innovative technology was chosen, why?

       An innovative technology was not selected.
                                                                                          1237
                                               -3-

-------
  10.     If an innovative technology was not chosen, why not? At what stage was the innovative
         technology eliminated?      .

         Innovative technologies could be eliminated from the remedial technology selection process at
         three stages: during the initial  screening; during the screening of the three criteria of
         effectiveness, implementability, and cost; or during the detailed evaluation.

         Innovative technologies eliminated during the initial  screening include the following:

         •      Biodegradation (ex situ, in situ) was eliminated because the PCB in the study area,
                 Aroclor 1260, is considered nonbiodegradable as a result of its high degree of
                 chlorination.
         •      Oxidation (ex situ, in situ) was eliminated because it has not been developed for PCB-
                 contaminated soil and its effectiveness would be uncertain.
         •      In situ  vitrification was eliminated because it would be appropriate only for
                 undeveloped areas since it would vitrify utilities and cause soil settling, which would
                 damage adjacent structures.

         Innovative technologies eliminated during the screening of the three criteria include the
         following:        v

         •      In situ  solvent extraction was eliminated because it might not be effective at the site
                 since the heterogeneous soils could cause "short circuiting" and the solvent could
                 bypass the most heavily affected low-permeability material and potentially promote
                 PCB migration across the aquitard.  It has not been  developed commercially and
                 reliable cost estimates are not available.
         •      Ex situ solvent extraction was eliminated because it would require preprocessing of .the
                 heterogeneous soil to produce uniformly sized material, and the heterogeneous soil
                 would  require excessive amounts of solvent that would require careful handling and  •
                 treatment. Even after preprocessing, the process would require several stages and the
                 PCB removed by the treatment would have to be transported off site and  incinerated.
                 This process has not been commercially developed.
         »      Dechlorination (in situ, ex situ) was eliminated because it would not be implementable
                 or cost effective.  Suitable processing equipment would need to be developed based  on
                 an extensive treatability program.  According to contractors with experience using
                 these .technologies, this remediation program is  too small for such options to be cost
                 effective; that is, the contractors would charge Westinghouse the same amount they
                 would  charge for a project many times greater,  resulting in a cost of perhaps as much
                 as $1,200 per cubic yard;  Furthermore, at least some of the treated soil would have to
                 be disposed of off site  because the total volume would be too large to backfill. The
                 disposal costs present an additional cost.                      .

         Innovative technologies eliminated during the detailed analysis include the following:

          •      None                                         .                        .
                                                                                                            :1
1238
                                                 -4-

-------
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of"the criteria supported the use of a standard technology?

       The criteria weighted most heavily in selecting a remedy were protection of human health and
       the environment; permanent reduction of contaminant toxicity, mobility, and volume; and cost
       effectiveness.  Excavation to 8 feet and incineration was preferred ovejr capping because they
       were more protective since site contaminants are permanently removed.  The selected
       alternative was preferred over excavation to 32 feet and incineration (RAA-4) because it is
       more  cost effective.                                              i          .
12.    What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?
13.
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens \
PCBs
. 25
. OSWERa
              "OSWER Directive No. 9355.4-01, Guidance on Remedial Actions For Superfund Sites
              With PCB Contamination, August 1990.                    |
Was the innovative technology eliminated because of the cleanup goals?  Could the standard
technology meet the cleanup goals?                     •           <        ,

Innovative technologies eliminated because of cleanup goals include:                .

••     None                                  .

Standard technologies eliminated because of cleanup goals include:

•      None.         '           .                ,
14v-    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were not conducted.                          •  i
75.   ' What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

       -     Risk level achieved
       -     Cost-effectiveness
  .     -     Preference for treatment (vs. containment)   -
             Waste left in place/institutional control
                                              -5-
                                                                                          1239

-------
     16.     How are measures compared?

            The selected alternative was preferred because it provides a protective and cost-effective
            remedy. Containment through capping was not preferred necause relying on land use
            restrictions and fencing to prevent any potential exposures to soil below the cap would pose a
            much higher risk. Furthermore, it is the least permanent solution of all of the options.
            Excavation to 32 feet and soil removal would not be cost-effective because it would not reduce
            risk significantly more than the selected remedy but it would cost much more. The decision to
            remove soil in this area to a maximum depth of 8 feet, rather than capping it was deemed
            reasonable because shallow excavation activities might occur on this industrial property in the
            future.  Removing all soil to the depth of the water table (32 feet), however, does not achieve
            a measurable reduction in risk due to direct contact exposure because there is no plausible
            expectation that subsurface work would occur below the 8-foot level.  Therefore, the additional
            costs for the 32-foot excavation is not justified since land use restrictions preventing
            subsurface work would provide adequate protection in these circumstances. The selection of
            incineration over off-site disposal is based upon the  statutory preference fot treatment and
            permanent solutions.


     17.     What technical considerations were factors in selecting a remedy?  Were technical
            considerations primary in the selection of the remedy?                                     '

            Technical considerations were not primary in selecting a remedial alternative.
                                                                                                                t;_-

                                                                                                               I|, Hi
1240
                                                  -6-

-------
                              Bangor Ordnance Disposal
                                Naval Submarine Base
                                          QU-1

                                   Bangor, Washington
                                        Region 10
                                                                Site History
                                                   NPL Proposed:
                                                   NPL Final:
                                                   FS:
                                                   ROD:
N/A
7/22/87
12/18/89
12/10/91
GENERAL SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?         -

       Maximum concentrations of principal
       contaminants were:

       Soil (rag/kg)

       2,4,6-Trinitrotoluene (TNT)  300
       Dinitrotoluene (DNT)       20
       Hexahydro-l,3,5-trinitro-
        1,3,5-triazine (RDX)       1.3
       Lead                       2,400
2.      .What volume of material is to be
       remediated?
       The volume of material to be remediated included:
              7,100 cubic yards of soil
       What type of site is this?
                                                                   '! '
       , -                    -           -                    - .       -t         v
                   - ' -                     -               "      .     I --.'•/
       Military.  A former explosive ordnance detonation and disposal site located in a rural and
       lightly residential area. The site includes a burn area that was used to detonate and incinerate
       various ordnance materials and two debris areas where inert solid wasite nnaterial from the burn
       area was deposited.                                           i
                                                               Background

                                                   Federal Facility
                                                   PRPs:  U.S.Navy'|
                                                   FS prepared by:  Hartcrowser Earth
                                                        .  and Environmental
                                                          Technologies       .
TECHNOLOGY SELECTION             ,

4.     What standard technologies were considered for selection in this FS?

       Standard technologies considered during the identification and screening of technically feasible
     '  technologies were:
                                                                    i
       Access restriction:     Fencing, warning signs, deed restrictions, zoning changes,
                            fishing/hunting restrictions, health and safety (equipment
                                            -1-
                                                                                       1241

-------
         Containment:
         Chemical treatment:
         Physical treatment:
         Thermal treatment:
         Disposal:
Capping (revegetation, synthetic membrane, clay, asphalt, asphalt
concrete, portland cement, multimedia), dust control, liner (synthetic
membrane, clay, multimedia, grout injection)
Sorbent stabilization, surfactant stabilization, solidification
Sieving/screening
Incineration (rotary kiln, infrared)                        •
Excavation, off-site landfill (RCRA, solid waste, demolition debris)
                                                                                                             >
                                                                                                           •~»S"
  5.      Was an innovative technology considered in the FS? If so, which technology?
                                      \              .

         Innovative technologies considered during the identification and screening of technically
         feasible technologies were:    -       .                .                             ,
                                              *                      *.=
         Biological treatment:   Composting, in situ biodegradation, slurry phase treatment,
                               landfarming
         Chemical treatment:    In situ vitrification, stabilization
         Physical treatment:     Soil washing, in situ soil washing,  in situ vacuum extraction, leach
                               basin (introduced in an RAA)
         Thermal treatment:     In situ vitrification, molten salts, pyrolysis
  6.      What was the cost estimate for the innovative technology?
                                                '                  /                             \
         During the initial screening process, in which technically feasible technologies are identified
         (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
         formulated, costs are typically estimated as part of a three-criteria screening process
         (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
         evaluation. In this case, estimated costs were calculated during an evaluation based on nine
         criteria established by the NCP. The bum area soil and the debris area soil were incorporated
         into sitewide alternatives for the detailed analyses and in the Proposed Plan and ROD;
         therefore, they are presented separately...
         Burn Area
                  Cost Estimates for RAAs That Include Innovative Technologies
                              (selected remedial alternative is in bold)
Alternative
RAA-1
RAA-2
RAA-3
RAA-5
RAA-6
RAA-7
Innovative Technology
Soil washing/natural photolysis
Soil washing/UV oxidation
Soil washing/carbon adsorption
Leach basin/natural photolysis
Leach basin/UV oxidation
Leach basin/carbon absorption
Estimated Costs
3 Criteria
N/A
N/A
N/A1
N/A
N/A
N/A
9 Criteria
eliminated
eliminated
eliminated
—
, ' —
— •
1242
                                               -2-

-------
       Debris Area: No innovative technologies were"developed for debris area soil.
                                                  '    ' ,    • ,'  .  •   !'  .
       Sitewide for Detailed Analyses                                  j
Alternative
RAA-5
RAA-6
RAA-7
Innovative Technology
Leach basin/natural photolysis/off-site disposal of
debris area soil
Leach basin/UV oxidation/of f-site disposal of
debris area soil -. ^ ..
Leach basin/carbon adsorption/off-site disposal of
debris area soil ,
Estimated Costs
9 Criteria
$918,000
$1,428,000
'.-*' N/A
Sitewide Alternatives for the Proposed Plan and ROD
Alternative
No number
Innovative Technology
Soil washing in a leach basin/natural photolysis
or UV oxidation or carbon adsorption/off-site
disposal of debris area soU
Estimated Costs
PP & ROD
$890,000"
       This cost estimate does not include treatment costs since .the treatment methods will address
       both soil and ground water remediation.  If ground water remediation is not conducted the cost
       of this alternative might range from $1.2 million to $1.6 million.    |             ,
7.      How did'the cost(s) compare to standard technologies?            [

                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)    \
Burn Area v i
Alternative
RAA-4
RAA-8 ,
RAA-9
RAA-10
RAA-11
RAA-12
Standard Technology
Incineration
Limited action
Synthetic membrane cover
Off-site disposal
Solidification • • ,
No action
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
N/A
N/A '
9 Criteria
eliminated
—
• —
eliminated
' • — •
•' • . —
                                             -3-
1243

-------
           Debris Area
Alternative*
RAA-1
RAA-2
RAA-3
Standard Technology
Off-site disposal in RCRA landfill ,
Off-site disposal in solid waste landfill
No action
Estimated Costs
3 Criteria
N/A
N/A
N/A
          Sitewide for the Detailed Analyses, the Proposed Plan, and ROD
Alternative
RAA-8
RAA-9
RAA-1 1
RAA-12
Standard Technology
Limited action
Cover
Solidification
No action
Estimated Costs
9 Criteria
$497,000
$671,000
$866,000
N/A
ROD
& PP
$800,000
$1,530,000
$1,850,000
$670,000
   8.      If a standard technology was chosen, why?

          Off-site disposal was selected for debris-area soil.
   9.      If an innovative technology was chosen, why?

          Soil washing in a leach basin was selected because it is protective of human health and the
          environment-through the extraction and treatment of contaminants in soil and ground water.  It
          reduces site risk due to direct contact, inhalation, or ingestibn of soil and removes the potential
          threat of ground water contamination. The contaminants will be permanently removed from
          the soil. Laboratory test have shown that water is effective at irreversibly leaching at least 95
          percent of TNT from soil. Treatment of collected water with UV oxidation will reduce
          toxicity by destroying over 99.99 percent of contaminants in water.  It provides long-term
          effectiveness and permanence since it reduces contaminant toxicity, mobility, and volume.
          The soil washing alternative provides the most reliable long-term performance because it uses
          treatment to reduce risk permanently from site contaminants.  No long-term maintenance is
          required.  This alternative complies with all ARARs. The selected alternative is cost-effective
          because its effectiveness is proportional to its costs. The selected remedy is  comparable in cost
          to many other alternatives; however, it uses an innovative technology, results in the on-site
          destruction of contaminants, and recharges the extracted and treated ground  water to replenish
          ground water supplies. It can be implemented in  a short time. Soil washing will contain
          contaminated soil within about 3 months and the treatment will be completed within about  1
          year.  Short-term risk to the community is negligible because the site is located on a high
          security facility. The risk to on-site workers during implementation can  be eliminated by
          standard control and monitoring activities.
1244
                                                -4.

-------
       The alternative utilizes soil treatment technologies with a sound, theoretical base and         ;
       demonstrated laboratory performance. The soil treatment system is innovative since it has
       rarely been used in full-scale operations and unforeseen operational problems might occur that
       require system modifications. Soil materials can be obtained from on-site or nearby sources.
       Other materials such as synthetic membrane can be obtained from suppliers in the state.

                              - •'       '  ,                   '             i
10.     If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation. In this case, a
       three-criteria screening was conducted for both individual technologies .luid specific
       alternatives.                                                             .
                                       .'•  '•               "          '      .i             •'     . -
       Innovative technologies eliminated during the  initial screening include the following:

       •     In situ vitrification as a solidification technique was eliminated because it would not
              be feasible for organic contaminants.                              :
       •     Molten salts were eliminated because it would not be feasible for materials with high
              ash content.                                           ,    '\/~ .
       B     Pyrolysis was eliminated because it would not be applicable to compounds containing
              nitrogen.                                                   i            -
       •     In situ biodegradation was eliminated because it would not  be feasible given the low
              permeability of the near-surface soils.
       •     In situ soil washing was eliminated because it would not be feasible  given the low
       ,       permeability of the near-surface soils.                      ."('"'
       •     In situ vacuum extraction was eliminated because it would not l>e feasible given the
              low permeability of the near-surface soils.                     i               ,

       Innovative technologies eliminated during the  screening of the three criteria of technologies
       include the following:                                              j         .

       •     In situ vitrification as a thermal technology was eliminated because a commercial
              facility is not yet available, its effectiveness is unproven, and it would have high costs.
       •     Composting was eliminated because it has not been proved, breakdown products might
              be toxic, it might require many years to implement,  and it is expensive.
       B     Slurry phase treatment was eliminated because it has not been proved, breakdown   '-.
              products might be toxic, and it is expensive.                  j     -.
       •     Landfarming was eliminated because it has notbeen proved and breakdown products
              might be toxic.                            .       k

       Innovative technologies eliminated during the  screening of the three criteria of RAAs include
       the following:

       "     Soil washing was eliminated because of the questionable reliability of the washing
              process together with the high cost.
                                              -5-
                                                                                           1245

-------
         Innovative technologies eliminated during the detailed analysis include the following:

         •      None
  11.
       *                      *.                    .                                  .
 Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
 which criterion? Which of the criteria supported the use of a standard technology?

 The criterion that were most heavily weighted in selecting a remedial alternative was long-term
 effectiveness and permanence. The chosen RAA provides the greatest long-term protection to
 human health and the. environment since it permanently reduces site contaminants. Other
 alternatives that proposed capping or institutional controls  were not preferred because they
 would require maintenance or compliance to be effective in the long term. Further, the
 elimination of site contaminants permanently through soil washing was preferred over the
 immobilization of contaminants through stabilization.
  12.
 13.
 What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
 ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis
Carcinogens
.TNT
DNT
RDX
Lead
33
1.5
9.1
2,500
MTCAa
MTCA
MTCA
MTCA
       "Washington State Model Toxics Control Act, which utilized risk-based criteria and
       applicable state and federal laws to derive  site-specific cleanup levels.


Was the innovative technology eliminated because  of the cleanup goals?  Could the standard
technology meet the cleanup-goals?

Innovative technologies eliminated because of cleanup goals include:

•      None                                               ,

Standard technologies eliminated because of cleanup goals include:

•      None
 14.     Were treatability studies conducted on the innovative technology or standard technology?
        Treatability studies were not conducted.                                              '

1246
                                               -6-
                                                                                                  "V T

-------
15.    What measures/criteria were used to compare alternatives?

       The following measures were used to compare the alternatives:

             Preference for treatment (vs.  containment)                    |
       -     Waste left in place/institutional control                       }                    ,

                                                                       i
16.    How are measures compared?
               -                 -         -       •                - .    x •  i -.
       The selected alternative was preferred because the treatment it will permanently reduce site
       contaminants.  This was preferred over containment since containment would require long-term
       maintenance to ensure protection. Further, treatment was preferred over institutional controls
       that would require compliance and cannot address ecological risk.    ;  .
17.    What technical considerations were factors in selecting a remedy? Were technical
       considerations primary in the selection of the remedy?   '           ,
                                   '           '    ,            -.'"   i"  '",'.''.
       No technical considerations were primary in selecting a remedial alternative. In situ
       biodegradation and in situ soil washing, however, were eliminated in the initial analysis
       because they would not be feasible given the low permeability of the near-surface soils.
                                              -7-                                            1247

-------
                         Bunker Hill Mining and Metallurgical
                                           OU-1

                                  Shoshone County, Idaho
                                         Region 10
GENERAL SITE INFORMATION
1.
2.
What'were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       SoU (rag/kg)

       Lead
       Arsenic
              17,800
              267
What volume of material is to be
remediated?

The volume of material to be remediated
included:
             Site History

NPL Proposed:        N/A     '
NPL Final:           9/83
FS:                  4/91
ROD:                8/91

Background

EPA Fund-lead
PRPs:  Gulf Resources and Chemical
       Corporation   ,
FS prepared by: CH2M Hill
              640,000 cubic yards of soils (for the selected alternative, which includes removing the
              top one foot of contaminated soils).
3.      What type of site is this?

       Mining. An inactive mining and smelting facility located in a residential area.
TECHNOLOGY SELECTION

4.      What standard technologies were considered for selection in this FS?
                                                                      i
       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                                            .
       Access restriction:

       Containment:
                     Deed notices, fences, sod/grass requirements, excavation regulations,
                     health intervention program             ,               .
                     Capping (soil, clay, synthetic membrane, sprayed asphalt, concrete,
                     multilayer, chemical sealants), horizontal barriers, surface controls, dust
                     suppression
Chemical treatment:   Stabilization/solidification, pH adjustments
Physical treatment:    Deep tilling                              ,
  1248
                                            -1-

-------
       Disposal:
Debris removal, .excavation, sod removal, solids processing, waste
storage, deep mine disposal, waste repository I
5.     Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification arid screening of technically
       feasible technologies were:                                       !
                                                                      1
       Chemical treatment:   Ex situ soil washing, in situ soil leaching     i
       Thermal treatment:    In situ vitrification                         !
                                                                      i
6.     What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  After the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation.  The
       estimated costs then are recalculated during an evaluation based on nine criteria established by
       the NCR                                  . "                  - i"
                     '                                                 !
                Cost Estimates for RAAs That Include Innovative Techniolojpes
                           (selected remedial alternative is in bold)
Alternative
RAA-9
Innovative Technology
Excavate 1 foot/backfill/soil
smelting/institutional controls
Estimated Costs
3 Criteria
$48,5pO,CK)0
9 Criteria
eliminated
7.      How did the cost(s) compare to standard technologies?             i
                                               .''.•-       -'      '• i-   ,   '
                 Cost Estimates for RAAs That Include Standard Technologies
                           (selected remedial alternative is in bold)
Alternative
RAA-,1
RAA-2
RAA-3
RAA-4
. Standard Technology
No action
Institutional controls
Excavate 1 foot/backfill/disposal in
on-site repository/institutional
controls
Cap/institutional controls
Estimated Costs
3 Criteria8
$0
$1,600,000
$22,500,01(0
i
- i •• •
$16,80p,0()0
9 Criteria
$0
eliminated
$41,300,000
eliminated
                                             -2-
                                                                                     1249

-------
Alternative
RAA-5
RAA-6
RAA-7
RAA-8
Standard Technology
Sod removal/sod replacement/disposal
in on-site repository
Deep excavation to 7 feet or cleanup
level is reached/backfill/disposal in on-
site repository
Permanent relocation of residents/
demolition/capping .
Excavate 1 foot/stabilization-
solidification/backfill/disposal in on-site
repository/institutional controls
Estimated Costs
3 Criteria8
$14,800,000
$75,200,000
$93,000,000
$36,500,000
9 Criteria
$28,600,000 .
$193,000,000
eliminated
$56,000,000
          *"Costs developed in the three-criteria screening are in order of magnitude based on cost
          curves, scale-up/scale-down factors, and preliminary quantity estimates."  The costs presented
          in the nine-criteria screen are based on more detailed, information.
  8.      If a standard technology was chosen, why?

          The chosen alternative, RAA-3, was preferred because it provides protection to human health
          through the elimination of lead-contaminated soil in residential areas. Lead absorption by
          small children is the most significant health risk posed by the site.  In order to reduce lead
          exposures, the selected remedy will replace lead-contaminated soil with clean  fill. Modeling
          scenarios estimate that the established soil cleanup level will result in a site wide mean blood
          lead level of 2.7 to 3.9 ug/dL.  In the ROD, excavation was extended to 24 inches in areas
          where produce gardening will occur thereby reducing the exposure associated  with the
          consumption of garden produce.  Household dust also has been identified as a significant lead
          exposure pathway.   In residential areas, the installation of a soil and sod barrier over the clean
          fill will help reduce direct exposure to contaminated soil and the generation of contaminated
          dust. This alternative will provide a degree of permanence because it will remove surficial
          layers of contaminants. The layer of clean fill that is added prior to the sod also improves the
          long-term effectiveness. The remedy will be effective in the long-term as long as institutional
          and maintenance controls are upheld. Continued blood lead monitoring and residential soil
          monitoring will measure the success of the selected remedy.   This alternative can be
          completed in 4 to 6 years. It will minimize short-term risk because only the top  12 inches of
          soil will be excavated unless it is a garden area where excavation will be to a depth of 24
          inches. This alternative will employ well-developed, reliable technologies that are technically
          feasible and require moderate effort.  The chosen alternative is cost-effective.
  9.     If an innovative technology was chosen, why?

         An innovative technology was not chosen.
1250
                                                 -3-

-------
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                           ,!'
                       •        ,     •        , -     •                     . i •     '     -        -  •
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following;

       •     Ex situ soil washing was eliminated because it has not been proved effective for
              relatively low concentrations of inorganics.                  i
       •     In situ vitrification was eliminated because it would be aesthetically unacceptable, it  is
              still in research stages, its implementability is uncertain, and strong negative public
              reaction would be expected as treatment takes place and land use is restricted.
       •     In situ soil leaching (soil flushing) was eliminated because reseiarch is currently lacking
              and its ultimate effectiveness would be uncertain, implementability has not been
            .  proved, arid strong negative public reaction would be expected as treatment takes place
          •    and land use is restricted.                             _

       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                 ..-:'

 -  ' •   «  ".   None  '   '       -    •'    /         "••'  'i  '

       Innovative technologies eliminated during the detailed analysis include the following:

" ••    ••-   . None'   ' •"    --••-.   .'•.'.-        ' '      •''.•: \'      ;
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
                                                    .            ':.."!•

       The criteria that were weighted most heavily in selecting a remedial technology were long-
       term effectiveness and cost-effectiveness. Long-term effectiveness was the primary reason for
       selecting RAA-3 over RAA-5.  Twelve inches of soil and sod provide a much more permanent
       barrier to potential exposure than a simple sod barrier. Further, while an in situ soil treatment,
       such as solidification proposed in RAA-8, would have been optimal, solidification would not
       be appropriate for use within a residential yard and no other in situ technologies are known to
       be effective in removing metals from soil.  Cost-effectiveness was the main reason for
       eliminating both RAA-6 and RAA-8.  Both of these alternatives would provide only marginal
       increases in benefit over the chosen alternative but would cost much more. In situ vitrification
       and smelting were eliminated because they would be too expensive.   !
                                                                                            1251

-------
    12.     What cleanup goals were selected?  If the cleanup goal was based on anARAR, what was that
            ARAR?  What risk level was selected to establish cleanup goals?
                         Contaminant
Cleanup Level (rag/kg)
ARAR or Other Basis
                     Carcinogens
                    Lead
        1,000
                                                                           Health"
                   The cleanup level for lead is intended to decrease the exposure of lead-contaminated
                   residential soils such that 95 percent or more of children in the area have blood lead
                   levels below 10 ng/dL and that less than 1  percent have blood lead levels greater than
                   15 ug/dL.
    13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
           technology meet the cleanup goals?

           Innovative technologies eliminated because of cleanup goals include:

           "      None

           Standard technologies eliminated because of cleanup goals include:.

           •      None                  •


    14.     Were treatability studies conducted on the innovative technology or standard technology?

           Treatability studies were not conducted.


    75.     What measures/criteria were used to compare alternatives?  -

           The following measures were used to compare the alternatives:

                Cost-effectiveness                              .                                 '
                Time to design/construct/operate
                Impact on nearby populations                     ,   .
   16.    How are measures compared?

          The principal difference between the chosen alternative and two other alternatives is
          excavation depth. RAA-5 proposes sod excavation and replacement and though it would be
          less expensive, it was eliminated because it would not be protective in the long-term.  RAA-6
          proposed excavating 7 feet, but it was eliminated because it was considered excessive,
          providing only marginal benefit  but at a substantially higher cost.  RAA-8 proposed excavating
          12 inches followed by stabilization, thereby immobilizing contaminants. Because contaminants
          would be adequately immobilized when disposed of in a properly contoured landfill, as is
          proposed in the chosen alternative, RAA-8 was determined to be excessive and not cost-
1252
                                                          o

-------
       effective.  The chosen alternative also was preferred over RAA-6 andjRAA-8 because it
       requires less time to implement.                                  ,   ,

       Impact on nearby populations also was considered in selecting a remedial  alternative.  OU-1
       encompasses the populated residential areas.  Both in situ vitrification and stabilization were
       eliminated because they would not be appropriate for residential areas!. Further, excavation
       depth was carefully evaluated because of the close proximity of peoplle to the contaminated
       soil. And the final remedy presented in the ROD was amended from the proposed plan to
       extend excavation depths in garden areas to 24 inches.
17.     What technical considerations were factors in selecting a remedy?  W}ere technical
       considerations primary in the selection of the remedy?          •  • j

       No technical considerations were primary in selecting a,remedial altematjve.
                                                                                             1253
                                              -6-

-------
                          Bunker Hill Miming and Metallurgical
                                           OU-2
                                   Shoshone County, Idaho
                                          Region 10
 GENERAL SITE INFORMATION
 L
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
        Soil (mg/kg)

        Arsenic
        Cadmium
        Lead
        Zinc
        Carbonate
        Sulfate
        Sulfur-Total
        PCBs
                     160,000
                     127,000
                     860,000
                     754,000
                     6,190
                     405,000
                     164,000
                     218
2.      What volume of material is to be
        remediated?

        The volume of-material to be remediated
        included:

        •     18,000,000 cubic yards of tailings
3.     What type of site is this?
                                                                 Site History
 NPL Proposed:
 NPL Final:
 FS:
 ROD:

 Background
                                                                         N/A
                                                                         9/83
                                                                         5/1/92
                                                                         9/22/92
PRP-lead
PRPs:  Asarco Inc., Callahan Mining
       Co., Coeur d'Alene Mines Corp.,
       Hecla Mining Co., Stauffer
       Management Co., Sunshine
       Mining Co., Sunshine Precious
       Metals Co., Union Pacific
       Railroad, Gulf USA Corp.,
       Pintlar Corp.,  Bunker Hill Mining
       Co. (U.S.) Inc., BH Properties,
       Inc., Syringa Minerals Corp.,
       Highland Surprise Consolidated-
       Mining Co., Silver Bowl, Inc.
FS prepared by:  McCulley, Frick .&•'
       Oilman,  Inc.     :
       Mining. An inactive mining and smelting facility .located in a residential area.  The site
       encompasses a 21-square-mile area. The ROD addresses contaminated nonpopulated areas of
       the site and those aspects of the populated areas not covered in the residential soil ROD
       (August 30, 1991).  Five areas of the site have source contamination:  Hillsides, Smelterville
       Flats, Central Impoundment Area (CIA), Smelter. Complex, and Mine Operations Area (MOA),
1254
                                            -i-

-------
 TECHNOLOGY SELECTION                                           I

 4.      What standard technologies were considered for selection in this FS? \
                   '              '               -      ' '               '   \    '  '  ' •            ' '
        Standard technologies considered during the identification and screenmg of technically feasible
        technologies were:                       . v   .                 •
        Access restriction:

        Containment:
                      Deed notices,.legal restrictions of access and cm hind use, fencing or
                      other barriers                              i
                      Revegetation, capping (soil, sawdust or rock barriers, soil/clay cover,
                      geosynthetic, asphaltic or geotextile systems) dust control (surface
                      armoring, polymeric/chemical surface sealers,'neutral or artificial wind
                      breaks), general decontamination, surface runoff/erosion controls,
                      (detention/sedimentation basins, retaining walls, revegetationj,
                      impoundment liner, systems                 J
Chemical treatment:    Stabilization/fixation (grout injection, polymeric/chemical surface
        Thermal treatment:
        Disposal:
                      sealers)
                      Incineration (infrared, fluidized bed)         !
                      Excavation and removal, on-site/off-site disposal
5.      Was an innovative technology considered in the FS?  If so, which technology?

        Innovative technologies considered during the identification and screenling of technically
        feasible technologies were:                                           , .      .
                                                         '               \"-
        Phys/Chem treatment:  In situ leaching for metals extraction, chemical extraction
        Thermal treatment:     In situ vitrification, on-site/off-site reprocessinjj/reuse
              1               (hydrometallurgical reprocessing, pyrometallurgical reprocessing)
       What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs.  Aifter the RAAs have been
       formulated, costs are estimated as part of a three-criteria screening process (effectiveness,
       implementability, and cost) to identify alternatives that merit a more detailed evaluation. The
       estimated costs then are recalculated during an evaluation based on nine criteria established by
       the NCP.  Innovative technologies were not incorporated into RAAs.
7,      How did the cost(s) compare to standard technologies?

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
Alternative
RAA-1
Standard Technology
No action
Estimated Costs
3 Criteria*
N/A
-'•'-~ ' • '
9 Criteria
$0

                                             -2-
                                                                                 1255

-------
Alternative
RAA-2
RAA-3
RAA-4
Standard Technology
Source and institutional controls
Source controls (in-place caps and
institutional controls/treatment .
(materials will be reprocessed,*
recycled, or treated via cement-based
stabilization)/umovative treatment of
ground water and surface water
(wetland treatment)
Removal (disposal in engineered reposi-
tories)/source control (conventional
engineering and institutional controls)/
treatment of ground water and surface
water
Estimated Costs
3 Criteria1
N/A
N/A
N/A
9 Criteria
$31,549,000
$52,035,000"
$120,291,000
       'Under this alternative, some of the higher concentration-wastes might be sold as recycled
       materials or shipped off site for reprocessing. The method of reprocessing was not specified
       in the FS or the ROD.                        J            -
       'The total present worth (5 percent discount rate) for the selected remedy also was estimated in
       the ROD at $47,049,000.                                    ,
8.      If a standard technology was chosen, why?       .                    ,

       RAA-3 was selected because actions specified under this alternative are expected to have
       significant water quality benefits, limit direct exposure to the most contaminated soils on site,
       and re-establish vegetative cover over the exposed areas of the site. This alternative, therefore,
       will reduce and/or eliminate the mobilization of soil/source materials.  The principal difference
       between the selected remedy and the other alternatives is the amount of treatment involved in
       RAA-3. The other alternatives call for source containment that provides a less effective means
     .  of protecting human health and the environment since no water treatment is included as is the
       case for RAA-3. RAA-3 removes, controls, or treats significant contaminant sources and
       effectively addresses site-wide Remedial Action Objectives. The toxicity, volume, and
       mobility of source materials available for transport is effectively reduced.  RAA-3  addresses
       human health and environmental concerns without significant threats to Workers  and the
       community and is considered effective in the short term. RAA-3 also is readily  implementable
       using standard  construction/remediation techniques.  Additionally, RAA-3 focuses on    ,
       reprocessing/recycling or treatment of the principal threat materials from the Smelter Complex,
       therefore, RAA-3 goes further toward satisfying the statutory preference for reduction of
       toxicity. Finally, this alternative will meet ARARs dealing with soil/source materials.
       Relevant and appropriate requirements of RCRA Land Disposal Restrictions (LDRs) for
       cement-based stabilization or principal threat waste are  expected to be obtained.
9.     If an innovative technology was chosen, why?

       An innovative technology was not chosen.
                                              -3-

-------
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?                                             I

       Innovative technologies could be eliminated from the remedial technoloigy selection process at
       three stages: during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include Ihe following:

       a      Chemical reduction was eliminated because'it would not be applicable for inorganic
               metals.  This technology has not been utilized successfully for removing metals or
               treating soils (U.S. EPA, 1988); chemical extraction has been used primarily for
              . treating sludges contaminated with hydrocarbons.
       •      In situ vitrification was eliminated because it would not be applicable to the site given
               the presence of ground water and variable soil conditions at this site.  In addition, this
               technology is considered impractical when applied over large areas because of the
               heterogeneity of the mass to be vitrified, maintenance of procesis control over large
               areas, and the presence of shallow ground water (U.S. EPA, 1985).
       •      Pyrometallurgical reprocessing was eliminated during the initial screening  stage for
               tailings in the Smelterville Flats and the CIA because it would not be feasible with
               low-concentration wastes and would be applied more appropriately to higher
               concentration materials.                                     !
       *     • ,                                  '               .".-_'              ,      -
       Innovative technologies eliminated during the screening of the three criteria include the
       following:                                         ,            .1
                      •'.          .                       ' • ,       -         I
       •      In situ leaching for metals was eliminated based on its anticipated lack of
               effectiveness, problematic implementation, and/or high costs relative to other equally
               effective options.  The history of using this technique for uranium recovery suggests
               that aquifer protection and restoration could be long-term problems due to the
               potentially hazardous nature of the solvents used. Treatability studies conducted by
               the University of Idaho using site samples showed that a strong oxidant is required  to
               dissolve the amounts of metals at the site, and acceptable metajis extraction occurred
               only under extreme acidic conditions.  The recovered leach solution would produce a
               waste sludge that probably would be contaminated with the metals of concern and
               would require treatment and disposal.                        i          .
        •    ,  Hydrometallurgical reprocessing was eliminated because metals' mobility in the
               processed tailings would increase substantially because of grinding and classification
               during processing.  Additionally, neither suitable milling or refiming facilities are
               currently available to handle site materials nor is a suitable disposal site available for
             •  subsequently produced materials.  This process also would, have a Mgh capital cost.
        Innovative technologies eliminated during the detailed analysis include

        •      None
the following:
                                                -4-
                                                                                                1257

-------
11.    Which of the nine criteria were weighted most heavily in selecting the technology? Did failure       	
       to meet one of the nine criteria result in the elimination of the innovative technology? If so,              j
       which criterion? Which of the criteria supported the use of a standard technology?                        '

       Protection of human health and the environment, long-term  effectiveness, and cost were
       weighted most heavily in selecting RAA-3.' By combining containment, treatment, and            ,      '
       institutional controls, RAA-3 addresses all on-site pathways and is protective of human health
       and the environment. In addition, it effectively improves downstream water quality.  This
       alternative provides a high level of protectiveness, minimizes exposure pathways identified for
       soils and source material, and obtains site-wide soil RAOs for human health protection.  The
       overall long-term effectiveness of RAA-3 is expected to be  high based on the degree to which              1
       it addresses site-wide RAOs and the reliability and permanence of the prescribed controls.     ,
       RAA-3 provides enhanced long-term effectiveness relative to the other alternatives through                  .!
       treatment of principal threat wastes.  Long-term effectiveness was the primary reason for                   '
       selecting RAA-3 over,RAA-2. The treatment included in the selected remedy provides more  '
       permanent controls. Finally, the cost of removal in RAA-4 was too high compared to RAA-3,
       considering the associated incremental improvement in performance.


12.    What cleanup  goals were selected?  If the cleanup  goal was based on an ARAR, what was that
       ARAR? What risk level was selected to establish cleanup goals?

       Cleanup goals were not established.              .  •


13.    Was the innovative technology eliminated because of the cleanup goals?  Could the standard
       teclmology meet the cleanup goals?

       Innovative technologies eliminated because of cleanup goals include:

       •     None ..                               '   '....''      ','.,'•''

       Standard technologies eliminated because of cleanup goals include:

       »     None    .                  '


14.    Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were conducted by the University of Idaho on the potential use of in situ
       leaching for metals recovery at the site.  Based on the results, this technology was eliminated
       from consideration.

       Treatability tests for cement-based solidification of one of the major principal threat material
       accumulations on site (copper dross flue dust moved to the Smelter Complex) indicated that
       attainment of percent reduction goals based upon TCLP protocols is likely under RAA-3. Due
       to the varying solubilities of contaminants of concern through a range of pH values, EPA has
       determined that the acid leaching aspects of the TCLP test protocol are not appropriate for
       wastes consolidated in the smelter closure, and elected to design a stabilization mixture that
       will achieve LDR treatment goals at a pH reflective of actual on-site conditions. A rainwater
       leach test has been determined to be more appropriate than an acid leach test.

 1258                                    .

-------
 11.     Which of the nine criteria were weighted most heavily in selecting the technology? Didfailu
        to meet one of the nine criteria result in the elimination of the innovative technology? If so,
        which criterion? Which of the criteria supported the use of a standard technology?

        Protection of human health and the environment, long-term effectiveness, and cost were
        weighted most heavily in selecting RAA-3.  By combining containment, treatment, and
        institutional controls, RAA-3 addresses all on-site pathways and is protective of human healtf
        and the environment. In addition, it effectively improves downstream water quality.  This
        alternative provides a high level of pSrotectiveness, minimizes exposure pathways identified fo
        soils and source material, and obtains site-wide soil RAOs for. human health protection.  The
        overall long-term effectiveness of RAA-3 is expected to be high based on the degree to whicl
        it addresses site-wide RAOs and the reliability and [permanence of the prescribed controls.
        RAA-3 provides enhanced long-term effectiveness relative to the other alternatives through
        treatment of principal threat wastes.  Long-term effectiveness was  the primary reason  for
        selecting RAA-3 over RAA-2.  The treatment included in the selected remedy provides more
        permanent controls.  Finally, the cost of removal in! RAA-4 was too high compared to RAA-;
        considering the associated incremental improvement in performance.


12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was thi
        ARAR? What risk level was selected to establish cleanup goals?
                                           •            i     •'        '
        Cleanup goals were not established.               '
                                                      1

13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
        technology meet the cleanup goals?               !
                                      .     ' •         '  i            '   •  "   •
        Innovative technologies eliminated because of cleanup goals include:
                                                     '  i          .
                                                   i    '                    •
        •       None            .

        Standard technologies eliminated because of cleanup goals include:

        •       None
14.     Were treatability studies conducted on the innovative technology or standard technology?

       Treatability studies were conducted by the. University of Idaho on the potential use of in situ
       leaching for metals recovery at the site.  Based on tlhe results, this technology was eliminated
       from consideration.                        .•].-.'

       Treatability tests for cement-based solidification of one of the major principal threat material
       accumulations on site (copper dross flue dust moved to the Smelter Complex) indicated that
       attainment of percent reduction goals based upon TCLP protocols is likely under RAA-3.
       tonhe varying solubilities of contaminants of concern through a range of pH values, EPA n
       determined that the acid .leaching aspects of the TCI.P test protocol are not appropriate for
       wastes consolidated in the smelter closure, and elected to design a stabilization mixture that
       will achieve LDR treatment goals at a pH reflective !of zictual on-site conditions. A rainwater
       leach test has been determined to be more appropriate than an acid leach test.

 1258                   '   •      .'•    "      .  ;    j.-:::      •   "  "    .'    '-
                 .            '  •    •   .       -5-       ...    --.       •',.   •   •     .   '

-------
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?

       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementabiJity, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial screening include the following:

        •      Chemical reduction was eliminated because it would not be applicable for inorganic
               metals. This technology has not been utilized successfully for removing metals or
               treating soils (U.S. EPA, 1988); chemical extraction has been used primarily for
               . treating sludges contaminated with hydrocarbons.
        •      In situ vitrification was eliminated because it would not be applicable to the site given
               the presence of ground water and variable soil conditions at this site. In addition, .this
               technology is considered impractical when applied over large areas because of the
               heterogeneity of the mass to be vitrified, maintenance of process control over large
               areas, and the presence of shallow ground water (U.S. EPA, 1985).
        •      Pyrometallurgical reprocessing was eliminated during the initial screening stage for
               -tailings in the Smelterville Flats and the CIA because it would not be feasible with
               low-concentration wastes and would be applied more appropriately to higher
               concentration materials.

        Innovative technologies eliminated during the screening of the three criteria include the
        following:

        •      In situ leaching for metals was. eliminated based on its anticipated lack of
             '   effectiveness, problematic implementation, and/or high costs relative to other equally
                effective options.  The history df using this technique for uranium recovery suggests
                that aquifer protection and restoration could be long-term problems due to the
                potentially hazardous nature of the solvents used.  Treatability studies conducted by
                the University of Idaho using site samples showed that a strong oxidant is required to
                dissolve the amounts of metals at the site, and acceptable metals extraction occurred
                only under extreme acidic conditions.  The recovered leach solution would produce a
                waste sludge that probably would be contaminated with the metals of concern and
                would require treatment and disposal.
         •      Hydrometallurgical reprocessing was eliminated because metals' mobility in the
                processed tailings would increase substantially because of grinding and classification
                during processing. Additionally, neither suitable milling or refining facilities are
                currently available to handle site materials nor is a suitable disposal site available for
                subsequently produced materials. This process also would have a high capital cost.

         Innovative technologies eliminated during the detailed analysis  include the following:

         •      None                                     '                                   '
                                                                                                  1257
                                                 -4-

-------

 75.     What measures/criteria were used to compare alternatives?         'i
     •       •      .        .     '           "     •     .       •     '       • i •"    '     '-'.'•-
        The following measures were used to compare the alternatives:      j

        -     Cost-effectiveness                                         i
             Total cost                                                 1    ,
             Preference for treatment (versus containment)             •.  ',          , .

              . .        •  •         ~  _""'". ~   ~    ,           '',.''   r             '
 16.     How are measures compared?                                    ;

        The selected alternative RAA-3, while significantly lower in cost than RAA-4, provides
        comparable net protection due to innovative surface and ground water treiltmeht methods ;and
        the use of reprocessing/recycling technologies. Although RAA-4 would remove more
        contaminated materials for consolidation on site, the associated cost of $120.3 million was
        substantially  higher than the cost of the selected remedy; the added effectiveness would be
        marginal with respect to the additional cost.  RAA-3 therefore was determined to be more
        cost-effective. Because RAA-3 proposes treatment of principal threat!! in soils and source
        materials, it satisfies the statutory preference for treatment of hazardous wastes.
                                          •             ' •          '.      - i    ,.      -   '.  t • •
                          '           •      -        -""*,.            i-      •

17.     What technical considerations were factors in selecting a remedy? Were technical
        considerations primary in the selection of the remedy?              |           .

        Technical considerations were not primary in selecting a remedial alternative.


References:                                                             i

       U.S. EPA.  1985.  U.S. Environmental Protection Agency.  Remedial iaction at waste disposal
       sites (revised). EPA/625/6-85/006.                             ,   ],

       U.S. EPA.  1988.  U.S. Erivironmental Protection Agency.  Technology screening guide for
       treatment of CERCLA soils and sludges.  EPA/540/2-8/004.
                                              6                                           1259

-------
                                Joseph Forest Products

                                 Wallowa County, Oregon
                                         Region 10
GENERAL SITE INFORMATION

1.     What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Surface Soil (mg/kg)
       Arsenic
       Chromium
       Copper
26,120
11,300
22,200
       Subsurface Soil (mg/kg)
       Arsenic
       Chromium
       Copper
104,000
46,100
34,400
             Site History

NPL Proposed:        6/88
NPL Final:           3/89
FS:                  7/92
ROD:                9/92

             Background

EPA Fund-lead
PRPs:  Joseph Forest Products and the
       Estate of Clifford Hinkley
FS prepared by: ICF Technology, Inc.
 2.      What volume of material is to be remediated?

        The volume of material to be remediated included:

        »      2,796 cubic yards of soil
 5.      What type of site is this?                                                  '.   .

        Lumber and Wood Products. A former wood treatment facility located outside the City of
        Joseph in a rural area.                                                  '          .
 TECHNOLOGY SELECTION                          ,          .

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:                                                                 ,

        Access restriction:     Fencing, deed restrictions                                  „
        Containment:          Capping (clay, synthetic membrane), slurry wall, grout curtain, sheet
                             piling, bottom sealing
 1260
                                             -1-

-------
        Chemical treatment:   Solidification, fixation, precipitation, chelation'-soiption, ion exchange
        Thermal treatment:    Incineration                            •'!''•
        Disposal:             Excavation, disposal (on site, off site)-        j
        Was an innovative technology considered in the FS? If so, which teciinology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:                           <   ''        |    .

        Biological treatment:   Biological treatment (in situ, ex situ)         !
        Phys/Chem treatment:  Oxidation, reduction, soil washing, solvent extraction, air stripping,
                           "  electrokinetics                  <  •  .        j
        Thermal treatment:     Vitrification                     .'•'.,  \
6". .     What was the cost estimate for the innovative technology?

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that taerit a more detailed
        evaluation. In this case, the estimated costs were calculated during an evaluation based on
        nine criteria established by the NCP.                                ;

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
           Alternative
         RAA-5
        Innovative Technology
Excavation to background/soil
washing/on-site disposal
                                                                       Estimated Costs
                                                                   3 Criteria
                                                                      N/A
9 Criteria*
   N/A
       'Net present worth costs were not calculated.  Only cpsts for total capital zmd O&M were
7      How did the cost(s) compare to standard technologies?               [

                 Cost Estimates for RAAs That Include Standard Technologies
                            (selected remedial alternative is in bold)
•- ' - '
Alternative
RAA-1
RAA-2
Standard Technology
No action
Excavation to background/off-site
disposal
• , • . • •:
Estimated Costs
3 Criteria
N/
N/
A
A
9 Criteria*
N/A
N/A

                                             -2-
                                                                1261

-------
Alternative
RAA-3
RAA-4
RAA-6
Standard Technology
Excavation to background/fixation/ oh-
site disposal
Excavation of surface soil to 10"5
cleanup level and subsurface soil to
W* cleanup level/off-site disposal
Excavation of all soil to 10"4 cleanup
level/off-site disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A
9 Criteria*
N/A
N/A ,
N/A
         "Net present worth costs were not calculated.  Only costs for total capital and O&M were  .
         given.       .                                                    .
  8.     If a standard technology was chosen, why?

         RAA-4 was selected because it provides long-term protection to human health and the
         environment by removing the contaminated soil, thereby eliminating it as a potential source of
         ground water contamination. These measures also eliminate exposures via inhalation and
         ingestion of contaminated soil particles, dermal contact with contaminated soil, and ingestion
         of contaminated ground water.  No unacceptable short-term risk or cross-media impacts will be
         caused by implementation of the remedy.  Exposure during soil excavation will be eliminated
         through the use of air monitoring, proper dust control during implementation, and by
         implementing a strict site-specific health and safety plan. It complies with all ARARs. The
         selected remedy provides a permanent solution with a proven technology.  It poses minimal
         uncertainty and long or short-term risk.  The selected remedy was more reliable, cost-effective,
         and could be implemented with less difficulty than other alternatives.
   9.      If an innovative technology was chosen, why?

          An innovative technology was not selected.
   10.     If an innovative technology was not chosen, why not? At what stage was the innovative
          technology eliminated?

          Innovative technologies could be eliminated from the remedial technology selection process at •
          three stages:  during the initial screening; during the screening of the three criteria of
          effectiveness,- implementability, and cost; or during the detailed evaluation.

          Innovative technologies eliminated during the initial screening include the following:

          •      Solvent extraction was eliminated because it would not be applicable to metals.
          •      Air stripping was eliminated because it would not be applicable to metals.,
          •      Biological treatment (in situ, ex situ) was eliminated because it would not be
                 applicable to metals.
1262
                                                 -3-

-------
                                                                         1           '  •
        Innovative technologies eliminated during the screening of the three criteria include the
        following:
        •      Electrokinetics was eliminated because it might not be effective given the coarse low
               moisture content soil found at the site.                      i
        •      Vitrification was identified as a technology to be considered for remedial alternatives;
               however, it was never incorporated into an RAA and no explanation was given.
        •      Oxidation was identified as a technology to be considered for jrenitedial alternatives; .
               however, it was never incorporated into an RAA and no explanation was given. It was
               noted that it would only be feasible for the treatment of arsenic.
        •      Reduction was identified as a technology to be considered for remedial alternatives;   '
               however, it was never incorporated into an RAA and no explanation was given. It was
               noted that it would only be feasible for the treatment of chromium.
                                                    '         "            I
                                                                         I-  .
        Innovative technologies eliminated during the detailed analysis includes  the following:
                                               •  '            -    -        ' i'  : '     ,-''•'-..
        •      Soil washing was eliminated  because it is an unproven technology and offers less
               certain long-term effectiveness than other alternatives.  Furthermore, it would be the
               least implementable since it would require treatability tests.  The long-term
               effectiveness of this alternative also would depend on more ccjntrols than the other
               options since it involves on-site disposal and relies on the* use of treatment
               technologies to separate contaminants for off-site disposal.  Sciil washing was expected
               to pose greater short-term risk given the potential for contaminant release during
               washing. Finally soil washing would  be costly.


11.     Which of the nine criteria were  weighted most heavily in selecting the technology? Did failure
        to meet one of the nine criteria  result in the elimination of the  innovative technology? If so,
        which criterion?  Which of the criteria supported the use of a standard technology?
     *.                                              t          • • •       ' ..  "'h •          _  ,.    =. .   -
        Protection of human health and  the environment, long-term effectiveness and permanence, and
        cost were the criteria weighted most .heavily in selecting a remedial alternative.  The selected
        alternative will be protective since health-based cleanup levels estimated for residential use
        will be attained.  This option also was preferred because it uses a proven technology-and its
        long-term effectiveness is certain.  This option will attain cleanup levels at the lowest cost.
 1  -                         •      .                 -'     '                 i  '•.••'•
        Soil washing, an innovative technology was eliminated because it is costly and its
        effectiveness is uncertain, as it is an, unproven technology.
72.
Whatch
ARAR?
mnup goals were selected? If the cleanup goal was based on
What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
Surface Soil/
Subsurface Soil
ARAR
Carcinogens .
Arsenic
Chromium
36/336 V
1,135/1,135


an ARAR, what was that
or Other Basis

Risk8
Risk

                                              -4-
1263

-------
Contaminant
Cleanup Level (mg/kg)
Surface Soil/
Subsurface Soil
ARAR or Other Basis
Noncarcinogens
Copper
10,000/10,000
Risk
                *For carcinogens, an excess upper bound individual lifetime cancer risk of between 10"4
                to 10"6 was acceptable.  For noncarcinogens, a Hazard Index less than or equal to 1.0-
                was acceptable.
  13.     Was the innovative technology eliminated because of the cleanup goals? Could the standard
         technology meet the cleanup goals?

         Innovative technologies eliminated because of cleanup goals include:

         «      None

         Standard technologies eliminated because of cleanup goals include:

         •      None.                                    .   .      •   -                 .


  14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.
  75.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

              Risk level achieved                         '
              Cost-effectiveness
              Proven reliability
  16.     How are measures compared?                                                        <

         The selected alternative was chosen because, except for RAA-2, it provides the greatest
         reduction in risk. RAA-5 was eliminated because it utilizes an unproven technology and offers,
         less certain long-term effectiveness than other alternatives. Furthermore, it would be the least
         implementable since it would require treatability tests. The long-term effectiveness of this
         alternative also would depend on more controls than the other options since it involves on-site
         disposal and relies on the use of treatment technologies to separate contaminants for off-site
         disposal. Soil washing was expected to pose greater short-term risk given the potential for
         contaminant release during washing. Finally, soil washing would be costly.
1264
                                                -5-

-------
17.     What technical considerations were factors in selecting a remedy?  Were technical
       considerations primary in the selection of the remedy?
       Technical considerations were not primary in selecting a remedial alternative
       and chelation-sorptibn, however, were eliminated because they woqld
       soil type found at the site.                  ,
      . Electrokinetics
not be effective in the
                                             -6-
                                                                                           1265

-------
                                  Umatilla Army Depot
                                           OU-1

                                     Hermiston, Oregon
                                         Region 10
GENERAL SITE INFORMATION
1.
2.
Wliat were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

Maximum concentrations of principal
contaminants were:
       Soil (mg/kg)
                                   87
                                   0.66
2,4,6-Trinitrotoluene
Hexahydro-l,3,5-trinitro
  -1,3,5-triazine (RDX)
Octahydro-l,3,57,-tetranitro-
  1,3,5,7-tetrazocine (HMX)  0.1
1,3,5-Trinitrobenzene        0.047
2,4-Dinitrotoluene (2,4-DNT) 0.016
                                                                 Site History
                                                    NPL Proposed:
                                                    NPL Final:
                                                    FS:
                                                    ROD:
                     10/15/84
                     7/22/87
                     4/92
                     9/92
             Background

Federal Facility  -   !
PRPs:  U.S. Army
FS prepared by: CH2M Hill and
       Morrison Knudsen
       Environmental Services
"What volume of material is to be remediated?

The volume of material to be remediated included:

»      30,000 cubic yards of soil  •    -
       What type of site is this?       '                                               v

       Military. An active U.S. Army munitions storage facility that previously functioned in
       ammunitions demolition, renovation, and maintenance. It is located in an agricultural/rural
       area.                                                  , • '          ,
TECHNOLOGY SELECTION
                   •                            ..                 '•

4.     What standard technologies were considered for selection in this FS?                      ,

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:

       Access restriction:     Fencing, warning signs, deed restrictions
       Containment:         Capping (soil, revegejation, single-layer, multilayer), surface controls
       Chemical treatment:    Solidification/stabilization
                                                                                               ,}
1266
                                            -i-

-------
       Physical treatment:
       Thermal treatment:
       Disposal:
  Sieving/screening
  Incineration (rotary kiln, infrared)
  Excavation, disposal (on-site, off-site)
5.      Was an innovative technology considered in the FS?  If so, which technology?

       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                                      i          ,

       Biological treatment:   Composting, in situ biodegradation, slurry phase treatment
       Phys/Chem treatment:  Oxidation, reduction, aqueous soil washing, solvent extraction, in situ
                             vacuum extraction
       Thermal treatment:    Vitrification (in situ, ex situ), low-temperature thermal decomposition

                                  ..   • ' .       •            •    '  -/'    --I-'  .  .           '   '
6.  .    What was the cost estimate for the innovative technology?          j

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does riot quantify costs. After the RAAs have been
       formulated, costs are typically estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation.  In this case, the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.           ,
                                                       .  ''             I  v          .-
                 Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)   j
Alternative
RAA-3
Innovative Technology
' Excavation/composting/on-site
disposal
Estimated Costs
3 Criteria .
N/A
9 Criteria
$1,900,000
to
$8,2000,000°
        "Cost is dependent on the depth of excavation and the specific type of composting used.
 7.      How did the cost(s) compare to standard technologies?

                  Cost Estimates for RAAs That Include Standard Technologies
                             (selected remedial alternative is in bold)
            Alternative
        Standard Technology
                                                                        Estimated Costs
3 Criteria
9 Criteria
          RAA-1
No action
   N/A
    $0
                                               -2-
                                                                                                1267

-------
Alternative
RAA-2
Standard Technology
Excavation/incineration
Estimated Costs
3 Criteria
N/A
9 Criteria
$4,100,000
to
$12,800,000
 8.      If a standard technology was chosen, why?

         A standard technology was not selected as the primary remedy. A clean soil cover will be
         used after treatment.
 9.     If on innovative technology was chosen, why?

        RAA-3 was selected because it reduces excess cancer risk in treated soil to 7 X W6 (industrial
        use scenario) and reduces site concentrations of systemic toxicants to levels at which no
        adverse effect would be expected'considering factors of uncertainty. It reduces plant stress
        associated with high concentrations of explosives. Following treatment, the soil will be
        disposed of on site and the provision for a clean soil cover will minimize direct contact with
        underlying treated soil that might contain residual contaminants. This remedy is expected to be
        consistent with future ground water remediation since it provides a substantial reduction in
        near-surface soil concentrations and a cover of clean soil. In combination with low
        precipitation and high evaporation rates in the region, negligible leaching of residual
        contaminants is expected. This alternative provides  long-term effectiveness and a permanent
        reduction in contaminant toxicity, volume, and mobility. Composting has been demonstrated
        in site-specific pilot-scale treatability  studies in which it has degraded and immobilized 97 to
        99 percent of the explosives.  It can be readily implemented. RAA-3 is an innovative
        application of an existing technology, and site-specific treatability studies have been
        completed. A final optimization study is nearing completion and will allow implementation of
        the  remedy in about 1 year.  The equipment and materials required to implement RAA-3 are
        readily available from local sources and national vendors. The alternative is cost effective.
 10.
1268
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.

Innovative technologies eliminated during the initial screening include the following:

•      Vitrification (in situ, ex situ) was eliminated because it has hot been tested for the
       site's soil contaminants, and it has not been demonstrated on a full-scale basis.
•      Low-temperature thermal decomposition was eliminated because it was found to be
       ineffective in U.S. Army Toxic and Hazardous Materials Agency (USATHAMA)
       treatability studies at the site to reduce explosives contamination in soil (IT 1987- Rov
       F. Weston, Inc., 1991).                                                      '    •
                                              -3-

-------
      •      In situ biodegradation was eliminated because it has been relatively unsuccessful in
             vadose zone applications at other sites due to difficulties in maintaining a relatively
             uniform and constant distribution of nutrients, moisture, and oxygen. At the site,
             nutrient distribution would be a primary limiting'factor. Further, soil handling and site
             disturbance would require mixing large volumes of amendment into the soil, thus
             negating two of the primary benefits of in situ treatment. Finally, it may not be
             effective at low explosive concentrations.                        !
      •      Slurry phase treatment was eliminated because in treatability studies to date, less than
             90-percent destruction and removal efficiency has been achieved 0\rgonne National
             Laboratory,  1991).                                           :!
      •      Aqueous soil washing was eliminated because treatability studies indicate explosives
             removal efficiency is low, ranging between 49 to 99 percent in one study (ARCO,
             1982) and 23 to 83 percent in another study (EPA, 1992, references  not listed in FS).
      •      In situ vacuum extraction was eliminated because it would not be feasible given the
             low vapor pressure and low volatility of explosives.                             -
      •      Oxidation was eliminated because explosives are not susceptible to  abiotic oxidation
             (IT, 1987).
      •      Reduction was eliminated because it has not been demonstrated for these contaminants
             and soils and it might produce toxic byproducts (IT, 1987).

      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                                            j

      •     Solvent extraction was  eliminated because it would not be a final treatment and there
             would be difficulty eliminating the final extract. It was suggested that the extract
             could be incinerated; however, mis would be unacceptable to  the ,&rmy because of the
              stringent requirement imposed on facilities that process detonatable concentrations. In
             addition, it is unlikely that a commercial incinerator would be willing to accept a
              potentially explosive mixture.  This process would not be easily implemented
              technically or  administratively.  Considerable equipment would be  needed for
              remediation, and the design of the fractionation system would have to incorporate
              potentially costly explosion safety controls.  Administratively, the^ process is unproven
              for explosives, Treatability studies would be necessary to demonstrate viability.  Cost
              would be high because of the additional treatability studies, the design and
              mobilization of expensive equipment, and the need to have process equipment for each
              of the  several phases.                   ,

       Innovative technologies eliminated during the detailed analysis include thb following:

  '. •    •      None                                                        '
                                                                     > *     '      '       '        ~ •  '
                      ,                * •                      .            • ' i      ,              •
                                    '                 -      •                i,          .   «  •
11.    Which of the nine criteria were weighted most heavily  in selecting the technology? .Did failure
       to meet one of the nine  criteria result in the elimination of the innovative technology? If so,
       which criterion? Which of the criteria supported the use of a standard tischnology?

       The criteria most heavily weighted in selecting a remedial technology weire protection of
       human health and the environment, long-term effectiveness, and cost. Of  the two alternatives
       that were protective and reduced site risk permanently and to acceptable levels, the most
       inexpensive option was chosen.
        •  •   . ' '       -         • .      •'           '     '.          ,     •    ..I-'"-  •  '    '.'.-••     „

                                                                                              1269
                                               -4- '  '   - '           ...;..'".          '      •   ,  .

-------
  12.     What cleanup goals were selected? If the cleanup goal was based on an ARAR, what was that
          ARAR?  What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level
(mg/kg)a
ARAR or Other Basis
Carcinogens •
2,4,6-TOT
2,4-DNT
RDX
Noncarcinogens
1,3,5-TNB
1,3-DNB
HMX
NB
RDX
4/8,4
0.17/0.37
6.2/33

0.96/6.7
1.9/13
946/6,669
10/67
217/5,723
Risk"
Risk
Risk

Risk
Risk
Risk
Risk
Risk
                 *Cleanup levels are risk based and correspond to residential land use scenario/industrial,
                 land use scenario.
                 "For carcinogens, an excess upper bound individual lifetime cancer risk of 10"6 was
                 acceptable, and for noncarcinogens, a Hazard Index less than or equal to 1.0 was
                 acceptable.
  13.    Was the innovative technology eliminated because of the cleanup goals? Could the standard
         technology meet the cleanup goals?    .         •

         Innovative technologies eliminated because of cleanup goals include:

         «      None

         Standard technologies eliminated because of cleanup goals include:

         »      None                                                                     •
  14.     Were treatability studies conducted on the innovative technology or standard technology?

         Since the early 1980s, USATHAMA has performed bench-scale arid pilot-scale studies on
         composting. Studies conducted using contaminated site soil indicated that the extractable
         concentrations of the explosives in the soil were significantly reduced (by 90 to 99 percent) by
         aerobic microorganisms (Roy F. Weston, Inc., 1991).
1270
                                               -5-
                                                                                                              '„*

-------
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

             Risk level achieved
             Cost-effective
        -     Proven reliability


16.     How are measures compared?                                    '<

        RAA-3 and RAA-2 were determined to reduce excess cancer risk to 1 X 10"6 and 7 X
        ID"6, respectively. A Hazard Index (HI) of less than 1 will be reached for all explosives except
        1,3,5-TNB in RAA-3, which could have an HI as high as 7.  While itjis telieved that
        substantial degradation of 1,3,5-TNB will occur, the elevated HI for 1,3,5-TNB in RAA-3 was
        acceptable because of uncertainty regarding its biodegradation; this estimzite assumes no
        degradation.  Further, RAA-2 would result in the permanent  destruction of 99.99 percent of
        site explosives while RAA-3 has been demonstrated to degrade or immobilize 97 to 99 percent
        of explosives. While RAA-2 would provide slightly greater  protection and long-term
        permanence than RAA-3, RAA-2 was not chosen because it  would cost twice as much to
        implement.                                              .       i

        Proven reliability was an influencing factor in selecting an appropriate! technology. The
        chosen technology (composting) was determined to be effective in a site-specific treatability
        study.  Other technologies (low-temperature thermal decomposition, slurry phase treatment,
        aqueous soil washing, oxidation, and reduction) were eliminated because they had been shown
       to be ineffective for the remediation of explosives.


17.     What technical considerations were factors in selecting a remedy? Ware technical
       considerations primary in the selection of the remedy?              ''' •
          '  '   •         '              •         '   •'     '.''••      |  '••  '    ••••••''
       No technical considerations were primary  in selecting a remedial technology.


       References
                               '                   ,                    i
       ARCO.  1982. Engineering and development support of general decon technology for the U.S.
       Army's Installation/Restoration Program.  Prepared for the U.S. Army Toxic and Hazardous
       Materials Agency.-  DAAK 11-80-C0027.                           |

       Argonne National Laboratory. 1991. Evaluation for the feasibility of biodegrading
       explosives-contaminated soils and groundwater at the Newport Army Ammunition Plant.
       Prepared for the U.S. Army Toxic and Hazardous Materials Agency. ipElHA-TS-CR-9200
       (June).,                                                         | ......

       IT. International Technology Corporation. 1987. Interim response action feasibility study,
       Area P Lagoons, Louisianan Army Ammunition Plant, final report. Prepared for the U.S.
       Army Toxic and Hazardous Materials Agency.  DACA45-87-C-0103 (August).
                                            -6-                                           1271

-------
          Roy F. Weston, Inc. 1991. Optimization of composting for explosives contaminated soil,

          final report.  Prepared for the U.S. Army Toxic and Hazardous Materials Agency (November).
1272
                                              -7-
                                                                                                        ' , ff,,-

                                                                                                         ; i'
                                                                                                        . ,t,

                                                                                                         i it'
                                                                                                         |,.E(,,l'i

-------
                              Union Pacific Railroad Co.

                                  •    Pocatello, Idaho
                                        Region 10
GENERAL SITE INFORMATION

7.   .   What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study?

       Maximum concentrations of principal
       contaminants were:

       Sludge/Soil (mg/kg)
                   \    .       -•..'.•'
    ..   Benzo(k)fluoranthene          33
       Benzo(a)anthracene           23
       Chrysene  ,                '23
       Benzo(a)pyrene               17
       Indeno(l,2,3-cd)pyrene 12
       Arsenic                     27.4
       Beryllium                   1.2
       Tetrachoroethene             56
       1,1-Dichloroethene            8.3
       Methylene chloride            86
       Trichloroethene               51
       n-Nitrosodiphenylamine       54
       1,4-Dichlorobenzene          10
       1,1,2,2-Tetrachloroethane      0.99
       Chloromethane               2.5
       Cadmium                   40.2
       Chromium                   136
       Copper                     242
       Zinc     ~   -. •              1,530
       Antimony                   3.3
       Vanadium                   45.8
       1,2-Dichloroethene       ..    107
       Lead                        1,460
2.-.-'-    What volume of material is to be remediated?

       The volume of material to be remediated included:

       •      2,500 cubic yards of soil
       •      1,700 cubic yards of soil ,
NPL Proposed:
NPL Final:
FS:
ROD:
             Background

PRP-lead
PRPs:  Union Pacific Railroad
FS prepared by: Applied
       Geotechnology Inc.
             Site Hisltory
9/83
9/21/84
4/91
9/91
                                            -1-
                                                                                          1273

-------
   3.      What type of site is this?

          Transportation.  An active rail yard located in a mixed commercial and light industrial area
          with some residential areas.
   TECHNOLOGY SELECTION

   4.      What standard technologies were considered for selection in this FS?

          Standard technologies considered during the identification and screening of technically feasible
          technologies were:  .                            .
          Access restriction:
          Containment:
          Chemical treatment:

          Physical treatment:
          Thermal treatment:

          Disposal:
Deed restrictions, fencing
Capping (clay, asphalt, concrete, multimedia), slurry wall, grout curtain
Neutralization, precipitation, polymerization, solidification,
microencapsulation
Recycling, dewatering, soil venting            ,    '  •  .
Incineration (rotary kiln, fluidized bed, multiple hearth, high-
temperature fluid wall reactor, plasma arc)
Excavation, off-site disposal, on-site disposal         .','-.•
  5.      Was an innovative technology considered in the F.S? If so, which technology?

          Innovative technologies considered during the identification and screening of technically
          feasible technologies were:                                              •

          Biological treatment:   Biodegradation (aerobic, anaerobic, in situ, ex situ)
          Phys/Chem treatment:  Oxidation (in situ, ex situ), reduction (in situ, ex situ), dechlorination
                                (in situ, ex situ), soil flushing, hydrolysis (in situ, ex situ), ex situ
                                solvent flushing
          Thermal treatment:     In situ vitrification, steam injection, radio frequency heating, ground
                             .  freezing, pyrolysis, molten salt incineration
                                                                        *
  6.      What was the cost estimate for the innovative, technology?

          During the initial screening process, in which technically feasible technologies are identified
          (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
          formulated, costs are typically estimated as part of a three-criteria screening process
          (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
          evaluation.  In this case, no specific costs were generated; cost categories (e.g., high, low)
          were used instead. The estimated costs were calculated during an evaluation based on nine
          criteria established by the NCP     "      .

          For this site, alternatives were renumbered in the detailed analyses and are presented
       '   parenthetically below.                        •                                         ,
1274
                                                                                                                if;
                                                 -2-

-------
                Cost Estimates for RAAs That Include Innovative Technologies
                          (selected remedial alternative is in bold)
Alternative
RAA-3
(RAA-4)
RAA-4
(RAA-9)
RAA-5
(RAA-11)
(RAA-5)
(RAA-6)
RAA-10
Innovative Technology
Off-site disposal/excavation/backfilling/
soil flushing/ground water treatment with
dissolved air flotation (DAF)
Off-site disposal/excavation/backfilling/
soil flushing/ground water treatment with
carbon adsorption
On-site incineration/excavation/
backfilling/soil flushing/ground water
treatment with DAF
Off-site incineration/excavation/
backfilling/soil flushing/ground water
treatment ,
Off-site disposal/excavation/backfilling/
asphalt cap/soil flushing/ground water
treatment with DAF
Off-site disposal/excavation/backfilling/
asphalt cap/soil flushing/ground water
treatment with carbon adsorption
Ex situ bioremediation/excavation/
solidification/backfilling/capping/on-site
disposal
Estimated Costs
3 Criiteriia
$5,443,590
to
$7,731,390
N/A-
t
1 • '-
$8,365,590
tb .
$18,38!6,790a
$8,409,240
to
$27,218,790"
N/A
- N/A
$1,553,450
to
$1,780,150"
9 Criteria
$3,073,150
to
$7,731,390*
$6,333,250
to
$69,819,563a
$8,121,750
to
$24,865,250*
$8,198,050
to
$40,287,150a
$3,192,950
to
$3,797,550'
$6;452,850
to
$6,984,750°
eliminated
       "Cost depends on specific amount of sludge excavated and disposed/treated.
       bCost depends on choice of either asphalt or multimedia cap.
7.      How did the cost(s) compare to standard technologies?

                Cost Estimates for RAAs That Include Standard Technologies
                          (selected remedial alternative is in bold)
                                           -3-
Alternative
RAA-1
RAA-2
RAA-6
RAA-7
Standard Technology
No action
Institutional controls
Asphalt cap
Multimedia cap

Estimated Costs
3 Criteria
$635,300
$840,350
$1,011,150
$1,218,850
9 Criteria
$635,300
$669,850
eliminated
eliminated
1275

-------
Alternative
RAA-8
(RAA-7)
RAA-9
(RAA-7)
RAA-8
Standard Technology
Silicate-based solidification/excavation/
backfilling/on-site disposal/ground water
treatment with DAF
Chemical fixation/excavation/backfilling/
capping/on-site disposal/ground water
treatment with DAF
Solidification/excavation/backfilling/
capping/on-site disposal/ground water
treatment with carbon adsorption
Estimated Costs
3 Criteria
$1,287,450
to
$1,514,150"
$1,247.600
i,,-
$1,474,300"
N/A
9 Criteria
$8,054,350
, $8,054,350
$11,345,500
    8.      If a standard technology was chosen, why? .

           Off-site disposal of some soil was selected as a primary remedy. An asphalt cap was selected
           to cover residuals in treated soil on site.
    9.      If an innovative technology was chosen, why?                               ''  >

           The selected remedy was preferred because it will be protective of human health and the
           environment. Excavation and off-site disposal of contaminated soil will significantly reduce
           the threat of exposure from ingestion, dermal contact, and inhalation of site contaminants.  Soil
           flushing and extraction and treatment of ground water will -eliminate the threat of exposure
           from ingestion or inhalation of contaminated ground water.  This alternative meets all ARARs.
           Short-term risks will be low and are not expected to increase significantly during remedial
           activities since control strategies such as dust suppression, air monitoring, and protective
           clothing will be implemented. The selected remedy is cost-effective because it has been
           determined to provide overall effectiveness proportional to its costs for the remediation of
           contaminated sludge, soil, and ground water. Since the technical feasibility of excavating
           through soils is uncertain, it is assumed that only 4,200 cubic yards will be excavated.
           Additional protection will be necessary for contaminants remaining in unexcavated soil. The
           asphalt cap over the sludge pit provides added protection against contaminants leaching from
           infiltration of the rain or snow melt.  Additionally, it will reduce the lateral and vertical
           migration of contaminants possibly remaining after excavation of the contaminants in soil both
           downgradient of the sludge pit and near areas of highest ground water contamination. The risk
           from ground water contamination is permanently reduced through soil flushing and treatment
           to acceptable exposure levels without transferring the risk to another media. This alternative is
           easily implemented technically since excavation of 4,200 cubic yards of sludge and soil, its
           transportation and disposal at  the RCRA landfill, and capping of the excavated pit are routine
           operations.                                                    '-....     •''.'.
1276
                                               .   -4.

-------
10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?
                 '   -     - - i '            .        .  '          ."•-'"/!,:       •' '        •
       Innovative technologies could be eliminated from the remedial technology selection process at
       three stages:  during the initial screening; during the screening of the three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.
                  *              '           '               -              ,          '            •
       Innovative technologies eliminated during the initial screening includes the following:  -  *

       •      In situ oxidation was eliminated because sludge constituents would not be amenable to
               the process         ,_  ....... , _              .."     .       j
       •      In situ reduction was eliminated because sludge hardness might make the addition of
               reducing agents difficult, the technology would be more appropriate for liquid waste
           ,   Streams, and the permanence of reduction in unknown.       '
       • .     In situ dechlorinatioh was eliminated because contact between sludge constituents and
               solvent would be difficult to ensure.                        .
       •      In situ hydrolysis was eliminated because it would not be applicable for sludge
               constituents.                                                                    ,
       •      In situ soil venting was eliminated because it would not be applicable for sludge
               constituents.
       •      Ex situ oxidation was eliminated because it would be more appropriate for a
               wastewater stream,                          ,
       •      Ex situ reduction was eliminated because it would be more appropriate for a
               wastewater stream.
       :«      Ex situ dechlorination was eliminated because it would be more appropriate for a
               wastewater stream.        '                 .
       •      Ex situ solvent washing was eliminated because the dense nature of the sludge would
               not permit adequate  contact with the sludge.                 i
  •'.,.•      Ex situ hydrolysis was eliminated because it would be more appropriate for. very
               specific wastes such as esters, amides, and carbamates.       |                 :
       •      Ground freezing was eliminated because it would not be a peirmaiient solution.
       •      Radio frequency heating was eliminated because it is an experimental technology still
               being tested in pilot  studies.  In addition, it would not be effective for heavy metals.  -
       »      Steam injection  was  eliminated because  it is an experimental technology still being
               tested in pilot studies. Li addition, it would not be effective for heavy metals.
                                    - •                    •        •  '     i-                    -'•
       Innovative technologies eliminated during the screening of the three cntena include the
       following:                                                        j                     /

       •      In situ anaerobic biodegradation was eliminated because treatment might not be
               possible since the  range of organic contaminants capable of degradation through an
               anaerobic process  is  limited.                   •            "
       •      In situ vitrification was eliminated because it is a relatively new technology requiring
               special equipment and significant electrical supplies.  It is in developmental stages and
               is costly.                                                  ]
       •      Ex situ anaerobic  biodegradation was eliminated because treatment might not be
               possible since the  range of organic contaminants capable of degradation through an
               anaerobic process  is  limited.                          .
       •      Molten salt was eliminated because it would not be particularity effective for sludges of
               high ash content (UPRR sludge ash content approaches 50 percent). Further, it is a
                                                                                              1277

-------
  11.
 12.
         new technology, it would be costly, and it is used mainly for liquids and might not be
         as effective for solids.
 •      Pyrolysis was eliminated -Because it is a new technology in the developmental stages.

 Innovative technologies eliminated during the detailed analyst include the following:

 "      Bioremediation (aerobic, ex situ) was eliminated because low concentrations of
         contaminants would not be readily or practically addressed by the bioremediation
         technology. A variety of reasons were given including: PAHs and chlorinated
         hydrocarbon concentrations might not be reduced below acceptable risk levels; metals
         toxicity and teachability might increase following bioremediation; metals might inhibit
         microbiological activity or even prove toxic  to microbes; additional treatment
         technologies would be needed to.address remaining problems (e.g., solidification and
         capping); initiating and propagating (i.e., blending oxygen arid nutrients)
         bioremediation would be difficult to achieve given the consistency of the sludge; the
         effectiveness of bioremediation on benzo(a)pyrene and potential bacterial toxicity is
         unknown; time required for site remediation  is unknown because of the character of
         the sludge, type of bacteria required, soil matrix, and the adaptability of bacteria to the
         site's contaminants; and the availability of the treatment technologies might be limited.
         (It was noted that these issues were discussed with EPA, and that EPA said that
        bioremediation could be eliminated.)
 •      In situ aerobic biodegradation was not explicitly eliminated.


 Which of the nine criteria were weighted most heavily in selecting the technology? Did failure
 to meet one of the nine criteria result in the elimination of the innovative technology?  If so,  ;
 which criterion? Which of the criteria supported the use of a standard technology?

 Protection of human health and the environment and  long-term effectiveness were the criteria
 weighted most heavily'in selecting a remedial alternative. Solidification was not preferred
 because  its effectiveness over time was uncertain. Incineration was not preferred because it
 produces ash as  a byproduct and metals might become more mobile in the ash, necessitating
 further treatment.  Further, because of the high contaminant concentrations in the sludge, the
 effectiveness of  incineration at  reaching cleanup levels was uncertain.  Finally, the asphalt cap
 proposed in the selected remedy was preferred because it will act to immobilize any residual
 contaminants.

 Bioremediation was eliminated  because it might not meet cleanup levels and  it might be
 difficult  to implement.

 What cleanup goals were selected?  If the cleanup goal was based on an ARAR, what was that
ARAR?   What risk level was selected to establish cleanup goals?

Chemical-specific cleanup levels were not finalized, with the exception of lead, as a result of
incomplete data regarding the background concentrations of contaminants.  Final cleanup
levels will be based on background concentrations, lowest practical quantitation limit, or risk-
based cleanup levels, whichever is highest.  Health risk-based cleanup levels will be based on
a 10* cancer risk or a Hazard Index of less than or equal to 1.
                                                                                                               „[,„:„
1278
                                                                                                      IF
                                                                                                      >"',(
                                                                                                      '::if

-------
 13.
Contaminant
Cleanup Level (ppm)
ARAR or Other Basis
Carcinogens \.
Lead
500
OSWR/ModeP
        •OSWER directive #9355.4-02 and the EPA Lead Uptake Bic|kinistic Model were used
        to determine this cleanup level.



 Was the innovative technology eliminated because of the cleanup goals?  Could the standard
 technology meet the cleanup goals?

 Innovative technologies eliminated because of cleanup goals include:;

 •      Bioremediation

                        •                                  '      '!
Standard technologies eliminated because of cleanup goals include,  j

 •      None             ~                                      !
14.
Were treatability studies conducted on the innovative technology or standard technology?

No treatability studies were conducted.
15.     What measures/criteria were used to compare alternatives?

        The following measures were used to compare the alternatives:

               Proven reliability
               Single versus multistep treatment
        -       Impact on nearby populations


/6.-    How are measures compared?
                                                                [„,:
       The impact on nearby populations was a concern. It was noted that short-term compliance
       with air quality standards could be more difficult with alternatives thai: proposed incineration
       and solidification because of the air process emissions associated with Ithose treatment options
       Proven reliability also was a factor in selecting a remedial alternative., Solidification was
       eliminated because the successful implementation and maintenance of the solidified mass was
       uncertain given the oily consistency of the sludge. Further, elevated metal concentrations
       found in the sludge present significant uncertainty in the incineration tischnology's ability to
       achieve target cleanup levels, The preferred alternative was selected because it offers greater
       protection and ensures effectiveness through a multistep treatment.  Thus, ;after the upper levels
       of sludge and soil are removed and disposed off site, lower levels of soil are treated with soil
       flushing to remove any remaining contaminants. Further, an asphalt cap will be placed over
       the excavated pit to inhibit infiltration and the mobility of any remainiing contaminants.
                                              -7-
                                                                                                1279

-------
    17.    What technical considerations were factors in selecting a remedy?  Were technical
           considerations primary in the selection of the remedy?                     .   ,

           The nature and depth of the contaminated media was primary in selecting a remedial
           alternative.  While many alternatives assumed that sludge and soil would be excavated to
           cleanup goals, it was suggested in the ROD that excavating soil beneath the "visible" sludge
           may be technically impracticable, if not impossible, because of its extremely coarse nature
           (i.e., dense mixture of gravel, cobbles, and boulders ranging up to 9 feet in diameter).
           Excavation, therefore, would likely be limited to practical depths, resulting in the removal of
           approximately 4,200 cubic yards of sludge and soil.  Thus, the chosen alternative is the most
           effective and protective because it will best address all contaminants by excavating to a
           practical limit, treating remaining soil via in situ soil flushing, and implementing a cap.
                                                                                                               ", It:
                                                                                                                fit-
1280
                                                 -8-

-------
                           Wyckoff Company/Eagle Harbor
                          West Harbor Operable Unit, OU-3

                               Bainbridge Island, Washington
                                         Region 10
GENERAL.SITE INFORMATION

1.      What were the principal contaminants,
       contaminant levels, and media addressed in
       this feasibility study? .

       Maximum concentrations of principal
       contaminants were:    '                 , s

       Intertidal and Subtidal Sediments (mg/kg)
       Mercury
95
       Maximum concentrations of principal
       contaminants besides mercury were not
       given in the FS or the ROD. Other
       contaminants detected include:  LPAH,
       Naphthalene, Acenaphthylene,
       Acenaphthene, Fluorene, Phenanthrene,
       Anthracene, 2-Methylnaphthalene, HPAH,
       Fluoranthene, Pyrene, Benzo(a)anthracene, Chrysene, Total benzofluoranthenes,
       Berizo(a)pyrene, Ideno(l,2,3-c,d)pyrene, Dibenzo(a,h)anthracene, and Benj!io(g,h,i)perylene.
                                    Site History
                       NPL Proposed:
                       NPL Final:
                       FS:
                       ROD:
                     9/85
                     7/87
                     11/91
                     9/29/92
             Background

EPA Fund-lead
PRPs:  Wyckoff Company (now Pacific
       Sound Resources), 10 parties
       were notified of potential liability
FS prepared by: CH2M Hill
2.      What volume of material is to be remediated?                      !

       The volume of material to be remediated included:      ,   '                           .
        •     '        '      .                           '    ••           r
       •      5,355 cubic yards of intertidal mercury contaminated sediments
       •      67,320 cubic yards of subtidal mercury contaminated sediments
       •      7,650 cubic yards of intertidal PAH contaminated sediments
                                         -  '               .        •  \          '

3.      (What type of site is this?                                      i  ;

       Lumber and Wood Products. This site includes Eagle Harbor and the Ifbnner Wyckoff wood
       treating facility. This ROD addresses the west harbor operable unit, onle off three operable units
       at the site. Ship building, maintenance, and repair activities have been conducted at this site
       since the turn of the century. Land use in the vicinity of the site is principally residential, with
       some commercial and industrial use.                  .    :, •                       -
                                                                                         1281
                                            -i-

-------
 TECHNOLOGY SELECTION

 4.      What standard technologies were considered for selection in this FS?

        Standard technologies considered during the identification and screening of technically feasible
        technologies were:
        Access restriction:
        Containment:

        Physical treatment:
        Thermal treatment:
        Disposal:
Institutional controls, hazard education programs
Capping (active materials, inert materials, synthetic or manufactured),
lateral containment (isolation barriers)
Dewatering, solidification/stabilization
Incineration, thermal extraction
Excavation, dredging (mechanical, hydraulic, specialty), confined,
unconfined
5.      Was an innovative technology considered in the FS? If so, which technology?

        Innovative technologies considered during the identification and screening of technically
        feasible technologies were:  \

       Biological treatment:   In situ biological treatment, land treatment, slurry treatment
       Chemical treatment:   PCB dechlorination
       Physical treatment:     Soil washing, solvent extraction


6.      What was the cost estimate for the innovative technology?

       During the initial screening process, in which technically feasible technologies are identified
       (prior to the formulation of RAAs), the FS does not quantify costs. After the RAAs have been
       formulated, costs are typically  estimated as part of a three-criteria screening process
       (effectiveness, implementability, and cost) to identify alternatives that merit a more detailed
       evaluation. For this site the estimated costs were calculated during an evaluation based on
       nine criteria established by the NCP.       ''•-.'                 '

                Cost Estimates for RAAs That Include Innovative Technologies
                            (selected remedial alternative is in bold)
Alternative
J
K
M
Innovative Technology
Removal/treatment by soil washing
(viable for PAH only)/disposal
Removal/treatment by solvent extraction
(viable for PAH only)/disposal
Removal/treatment by biological slurry
(viable for PAH only)/disposal
Estimated Costs
3 Criteria
N/A
N/A
N/A •
9 Criteria
eliminated
eliminated
$303,000,000
s>
  1282
                                             -2-

-------
      Estimated costs for this site were recalculated in the PP. Except for Alternative N, costs for
      each RAA were not presented in the ROD.
7.
Alternative
M
Innovative Technology
Removal/treatment by biological slurry
(viable for PAH only)/disposal
f - L
Estimated Costs
PP
$100,800,000
to
$204,900,000
How did the cost(s) compare to standard technologies? '
Cost Estimates for RAAs That Include Standard Technologies
(selected remedial alternative is in bold)
Alternative
A
B
C
D
E
-F
G
H
I
M

Standard Technology
No action/natural recovery
Institutional controls/natural recovery
Capping
Removal/consolidation/confined
aquatic disposal
Removal/consolidation/near-shore
disposal
Removal/consolidation/upland disposal
on site
Removal/consolidation/upland disposal
at off-site commercial RCRA landfill
(viable for mercury only)
Removal/treatment by incineration
(viable for PAH only)/ disposal
Removal/treatment by solidification or
stabilization (viable for mercury
only)/disposal
In situ treatment by
solidification/stabilization (viable for
intertidal areas with mercury only)
Estimated Costs
3 Criteria
N/A
N/A
N/A
N/A
MA
N/A
MA
N;A
MA
N/A
9 Criteria
$1,370,000
$1,760,000
$31,900,000
$65,800,000
$145,000,000
eliminated
$103,000,000
$420,000,000
$33,760,000
$3,500,000
                                          -3-
1283

-------
Alternative
A
B
C
D
E
G
H
I
M
N
Standard Technology
No action/natural recovery
Institutional controls/natural recovery
Capping
Removal/consolidation/confined aquatic
disposal
Removal/consolidation/near-shore ;
disposal •
Removal/consolidation/upland
disposal at off-site commercial RCRA
landfill (viable for mercury only)
Removal/treatment by incineration
(viable for PAH only)/ disposal
Removal/treatment by solidification
or stabilization (viable for mercury
only)/disposal
In situ treatment by solidification/
stabilization (viable for intertidal areas
with mercury only)
Low-impact capping
Estimated Costs
PP
$800,000
to
$1,200,000
$1,200,000
$15,200,000
to
$25,100,000
$22,700,000
to
$48,600,000
$73,600,000
to
$110,700,000
$50,000,000
to
$104,000,000
$174,500,000
to
$274,100,000
$17,400,000
to
$34,500,000
$4,500,000
$2,100,000
to
$3,600,000'
       "Estimated costs for Alternative N were recalculated in the ROD. Using computer modeling the
       U.S. Corps of Engineers developed a type of low-impact capping defined as Thin-Layer
       Placement in March 1992. Thin-Layer Placement is the basis for the revised costs for
       Alternative N presented in the ROD, which are $2.2 million.
8.      If a standard technology was chosen, why?                   .

       The selected remedy combines the following remedial alternatives B, C, G or I, and N. The
       estimated total present worth costs for the entire remedy are $6.2 million to $16 million.

       This remedy combines upland source control, removal of hotspot sediments, capping of
                 contaminated sediments, low-impact capping of marginally contaminated

                                             -4.                        -  .

-------
       sediments, and institutional controls. Upland source control is intended to reduce or eliminate
       future contaminant discharges which could recontaminate sediments. Removal of hotspot  ..._
       sediments will eliminate a significant source of mercury contamination to the marine
       environment. Capping large areas of subtidal sediments with clean materials is an effective
       means of quickly protecting the environment with minimal short-temt effects.  Within areas to
       be capped, use of a meter-thick cap will limit potential redistribution of mercury and address
       more significant environmental risks. Low-impact capping in marginzilly contaminated areas
       will reduce surface  sediment chemical concentrations to levels protective of human health and
       the environment without unnecessary cost.  Under the selected remedy mercury source
       sediments will be solidified before landfill disposal. Solidification and appropriate  landfill
       selection will be "relatively" permanent. Finally, the capping component of the preferred
       alternative involves no dredging, storage, dewatering, or processing of contaminated sediment,
       arid removal of the  mercury source sediments can be done from land at extreme low tide.
       These options are more readily implementable than most of the other active cleanup
       alternatives.
9.      If an innovative technology-was chosen, why?
     '       !         -              "               .-.''.            ',[•"_
       An innovative technology was not chosen.                         j


10.    If an innovative technology was not chosen, why not? At what stage was the innovative
       technology eliminated?            .
 - '                           '    -       " , '                               I-      ' -                -
       Innovative technologies could be  eliminated from the remedial technology  selection process at
       three stages: during the initial  screening; during the screening of the^ three criteria of
       effectiveness, implementability, and cost; or during the detailed evaluation.

       Innovative technologies eliminated during the initial  screening include the following:
                         "                '• -        >               ,•'"•!''*
       •      In situ biological  treatment was .eliminated for the intertidal land subtidal mercury areas
               because this technology would not be applicable for use with mercury-contaminated
    ,           sediments; mercury is not biodegradable.                   ,
       •      Land treatment was eliminated for the intertidal arid subtidal mercury areas because
               this technology would not be applicable for use with mercury-contaminated sediments;
               mercury is not biodegradable.                             j
       •      PCB dechlorination was eliminated because  at this tirne, known PCS contamination of
               sediments in Eagle Harbor has not been demonstrated to be a direct threat to either
               human health or the environment; therefore,  sediment remediation  will not specifically
               target PCBs. Process options were not carried forward for the PCB technology type
               screening.             ,        -                         t
        »      Slurry treatment was eliminated for the intertidal and subtidd mercury areas because
               this technology would  not be applicable for use with mercury-contaminated sediments;
               mercury is not biodegradable.                             J
        •      Soil washing was eliminated for the intertidal and subtidal nsercury areas because this
               technology is not proven for use with metal-contaminated sediments.       -
        •      Solvent extraction was eliminated for the intertidal and subtidal mercury areas because
               this technology is not proven for use with metal-contaminatejd sediments.
                                                                       }                 1285
                                               -5-     •  •    -  ' '       ••'••.     -

-------
         Innovative technologies eliminated during the screening of the three criteria include the
         following:                                                                                          Y

         •      Soil washing was eliminated for the intertidai PAH area because the effectiveness of
                this alternative is not known for marine sediments and treatability studies would be
                required. It might be technically feasible to implement soil washing at this site, but               .
                there are uncertainties associated with its ability to treat the heterogeneous sediment                i
                consistently. After soil washing, the concentrated waste stream would have to be
                disposed of or treated. This treatment alternative was not carried forward because of
                the uncertainties  mentioned above and because other available treatment alternatives
                accomplish a comparable level of treatment with fewer uncertainties.
         •      Solvent extraction was eliminated for the intertidai PAH area because this treatment
                has not been used to treat soils or sediments, and the likelihood its success at the site
                is uncertain. The process equipment is complex, and its suitability for use at,the site is
                uncertain. Other treatment alternatives appear capable of achieving comparable results
                with less uncertainty.

         Innovative technologies eliminated during the detailed analysis  include the following:                    '' t

         •      Biological slurry treatment Was eliminated because long-term protectiveness would be
                contingent on effective source control. If additional PAH inputs were mot controlled,
                removal might not provide effective protection of the environment because of the
                possibility-for recontarnination of jemediated  area.  Removal and disposal of                ^llk
                contaminated sediments also could temporarily increase levels of contamination in the       lj|lr
                ah-, thus there would be potential public contact with contaminated sediment during              -
                excavation/dredging, and storage because disturbed sediments might be transported               J
                onto beaches. Treatment could produce air emissions. In addition this treatment
                alternative should meet ARARs, although possibly  with more difficulty than other     ,,           •
                alternatives. Finally, although biological slurry treatment is a proven technology it is  "*
                subject to site-specific variation in destruction efficiency.                               '.       •   '[


 11.     Which of the nine criteria were weighted most heavily in selecting, the technology? Did failure
        to meet  one of the nine criteria result in the elimination of the innovative technology?  If so,
        which criterion?  Which of the criteria supported the  use of a standard technology?
                                                           ''     •  ';      •••'•'            .'      v  :il
        The criteria weighted most.heavily in selecting a remedy were protection of human health and
        the environment, long-term effectiveness, and cost.  The preferred remedy is protective  of both
        public health and the environment. It removes source metals, addresses-human health risks
        from consumption of contaminated seafood by continuing the existing advisory until
        contaminants are below levels of concern, and isolates sediment from adversely affected
        marine organisms. Upland disposal of the mercury hotspot sediments is appropriate for
        reasons of long-term effectiveness and permanence,  because it permanently removes the most
        concentrated mercury contamination from the marine environment.  This important criterion
        outweighed the advantages of in situ solidification/stabilization and other alternatives. In
        addition  the selected remedy is cost effective.  By tailoring the remedy so that removal and
        any necessary treatment are applied to small-volume, high-concentration  sediments, and by
        using lower-cost containment alternatives for the large areas of moderate to marginal
        contamination,  the selected remedy cost-effectively provides an  appropriate level of protection
        for each  area. Allowing natural recovery in areas where cleanup objectives will be achieved in


1286
                                  '   .  .       -6-       •            .' •      .

-------
12.
10 years, and allowing biological testing to modify the selected remedy and perhaps eliminate
cleanup areas, avoids costly and unnecessary remedial actions.

 '                - '•             •-'••••                    i             "
What cleanup goals were selected?  If the cleanup goal was based on}an ARAR, what,was that
ARAR? What risk level was selected to establish cleanup goals?
Contaminant
Cleanup Level (mg/kg)
ARAR or Other Basis '
Carcinogens .
HPAH
Benzo(a)anthracene
Chrysene
Total
benzofluoranthenes
Benzo(a)pyrene
Ideno(l,2,3-c,d)pyrene
Dibenzo(a,h)
anthracene
5,300
270
460
450
210 ':.
88 -
33
MC:ULm
" MCUL
MCUL
MCUL
MCUL
MCUL
MCUL
Noncarcinogens ,
Mercury
LPAH
Naphthalene
Acenaphthylene
Acenaphthene
Fluorene
Phenanthrene
Anthracene
2-Methylnaphthalene
Huoranthene
Pyrene
Benzo(g,h,i)perylerie
Q.59 mg/kg (dry weight)
780
170
66
57
, 79 -
480
1,200
64
1,200
1,400
78
•- MCUL
MCUL
MCUL
MCUL
MCUL
MCUL
MCUL
MCUL
; MCUL
MCUL
MCUL
MCUL
        The sediment cleanup objective for this site combines an ovejrall site-specific cleanup
        objective develojped according to the State of Washington Sedimesnt Management
        Standards with supplemental objectives developed by EPA to address specific
        concerns. The measurable site-specific objective is the MCUll (Minimum Cleanup
                                                                                   1287
                                       -7-

-------
                 Level), and achievement of the MCUL is the primary focus of remedial action in this
                 operable unit.                                              ,
  13.     Was the innovative technology eliminated because of the cleanup goals?  Could the standard
          technology meet the cleanup goals?

          Innovative technologies eliminated because of cleanup goals include:

          •      None           ,  '  '                        .-...-

          Standard technologies eliminated because of cleanup goals include:                       "

          •      None                                                .        ,


  14.     Were treatability studies conducted on the innovative technology or standard technology?

         Treatability studies were not conducted.
  15.     What measures/criteria were used to compare alternatives?

         The following measures were used to compare the alternatives:

                Cost effectiveness
                Proven reliability
                Impact on nearby populations
                                                                                                      ,.l!
 16.     How are measures compared?               •

         The selected remedy is cost effective as it provides overall protection proportional to its costs.
         By tailoring the remedy so that removal and any necessary treatment are applied to small-
         volume, high-concentration sediments, and by using lower-cost containment alternatives for the
         large areas of moderate to marginal contamination, the selected remedy cost-effectively
         provides an appropriate level of protection for each area. Allowing natural recovery in areas
         where cleanup objectives will be achieved in  10 years, and allowing biological testing to
         modify the selected remedy and perhaps eliminate cleanup areas, avoids costly and
         unnecessary remedial actions.Only one treatment alternative,  stabilization/solidification, was
         carried forward for detailed evaluation for mercury-contaminated sediments, because of
         technical uncertainties associated with other treatment alternatives".  Biological sludge treatment
         was eliminated in part because the removal and disposal of contaminated sediments could
         temporarily increase levels of contamination in the air, thereby affecting nearby populations
 17.
1288
What technical considerations were factors in selecting a remedy?  Were technical
considerations primary in the selection of the remedy?                  ..

Technical considerations were not primary in selecting a remedy for this site.  Soil washing for
PAH removal for sediments was eliminated in part because the heterogeneous grain size
                                                                                                     .*>
                                               -8-

-------
 problems.      ' •                           '   ,
I     .        ,  '                 _'-'!"•       .
                                                          1289
                            -9-

-------
                                      Yakima Plating Co.

                                       Yakima, Washington
                                            Region 10
     GENERAL SITE INFORMATION
    1,
What were the principal contaminants,
contaminant levels, and media addressed in
this feasibility study?

• •

Maximum concentrations of principal
contaminants were:

SoU (mg/kg)

Arsenic
Total Chromium
Chromium VI
Lead
Nickel
DDD
DDT
DDE
Dieldrin
Copper
Barium
Cadmium
Selenium
Cyanide




32.7
7,870
7.04
7,580
218,000
4.3 - • . : ' .
19.4

Site History
if '
NPL Proposed: 6/88 ,
NPL Final: 3/89
FS: , 8/91
ROD: 9/91

Background

EPA Fund-lead
PRPs: Yakima Plating, Robert Mastell
FS prepared by: Ecology and
Environment, Inc.


18
0.9
46,700
595 . •,,/''
14.6
10.1 • , .
495
    2.     What volume of material is to be remediated?

          The volume of material to be remediated included.

          •      540 cubic yards of soil                              •                 :


    3.     What type of site is this?

          Electroplating. An inactive nickel-chrome automobile bumper replating facility.  It is located
          within a mixed lightly commercial and residential area.
                                                                                                        I
1290
                                             -i-

-------
TECHNOLOGY SELECTION

4.     What standard technologies were considered for selection in this FS?\

       Standard technologies considered during the identification and screening of technically feasible
       technologies were:                                              - .;               '
                               • .   '                   '            •     'i        •
       Containment:          Capping (single-layer, multilayer, asphalt, cement, concrete).         >
      .Physical/Chemical:    Immobilization, solidification/stabilization
       Thermal treatment:    Incineration (rotary kiln, multiple hearth, fluiclized bed, infrared)
       Disposal:              Landfill (on-site, off-site)                               .

                                                          '"         *     i" •         •     "      -  -

5.     Was an innovative technology considered in the FS? If so, which technology?
                                                          '             -i •
       Innovative technologies considered during the identification and screening of technically
       feasible technologies were:                   .                    -j   •''-.'.
                                                                        L            '       '
       Physical/Chemical:    Soil washing, in situ soil flushing           }
       Thermal treatment:    Wet air oxidation, vitrification (in situ, ex situi), molten salt
6.      What was the cost estimate for the innovative technology?           |                  .

        During the initial screening process, in which technically feasible technologies are identified
        (prior to the formulation of RAAs), the FS does not quantify costs, After the RAAs have been
        formulated, costs are typically estimated as part of a three-criteria screening process
        (effectiveness, implementability, and cost) to identify alternatives that [merit a more detailed
        evaluation. The estimated costs then are recalculated during an evaluation based on nine
        criteria established by the NCP.  RAAs presented parenthetically represent changes in the
        Proposed Plan and the ROD.                                      >
                                                                '  •   •  '.i • '      '     .
                                                                ,        i          .          ...
                 Cost Estimates for RAAs That Include Innovative Technologies       '
              ,,             (selected remedial alternative is in bold)     i
v, . - •
Alternative
RAA-4
RAA-5
(RAA-2)
Innovative Technology
Excavation/on-site vitrification/off-site
disposal at RCRA landfill
Excavation/on-site soil washing/on-site
disposal •--•'"•

Estimated Costs
3Ci
$5,i:
•iteiia
36,000
$322,000
9 Criteria
eliminated
$322,000
                                              -2-
                                                                                         1291

-------
      7.      How did the cost(s) compare to standard technologies?

                       Cost Estimates for RAAs That Include Standard Technologies
                                 (selected remedial alternative is in bold)
$
Alternative
RAA-1
RAA-2
(RAA-1)
RAA-3
RAA-6
(RAA-3)
RAA-7
Standard Technology
Capping '
Excavation/off-site treatment and
disposal at RCRA landfill
Excavation/stabilization/splidification/
off-site disposal at RCRA landfill
In situ stabilization/solidification
No action/ground water monitoring
==r!=^====^======
Estimated Costs
3 Criteria
$126^000
$330,000
$285,000
$208,000
$109,000
9 Criteria
eliminated
$265,000 to
$330,000
eliminated
$208,000
eliminated
     8.      If a standard technology was chosen, why?

            RAA-2 was chosen because it provides long-term protection to human health and the
            environment by removing the contaminated soil and eliminating it as a potential source of
            ground water contamination.  These measures also eliminate exposures via inhalation and
            mgestion of contaminated particles, dermal contact with contaminated soil, and ingestion of
            contaminated ground water. Off-site treatment and disposal restricts contaminant mobility.
            This alternative presents no unacceptable short-term  risks or cross- media impacts.  Air
            monitoring and dust control measures eliminates any potential exposure caused by excavation
            This alternative complies with all ARARs. It provides a permanent solution with a proven
            technology. It provides minimal uncertainty and minimal long- and short-term risk. It is the
            most reliable option and. can be implemented with less difficulty and no greater short-term
            impacts than  the other treatment alternatives.. It can  be readily implemented since there are
            two suitable landfill sites in the Pacific Northwest and licensed haulers are readily available for
            transport of the waste.  It is the cost-effective option since other treatment options require
            treatabihty testing which could significantly increase costs.
    9.      If an innovative technology was chosen, why?

           An innovative technology was not chosen.
    70.
1292
If an innovative technology was not chosen, why not? At what stage was the innovative
technology eliminated?                                  .

Innovative technologies could be eliminated from the remedial technology selection process at
three stages:  during the initial screening; during the screening of the three criteria of
effectiveness, implementability, and cost; or during the detailed evaluation.
                                                 -3-

-------
     Innovative technologies eliminated during the initial screening include the following:

     •      In situ soil flushing was eliminated because the upper unit of the overburden presents a
             complex geologic system of silts and clays that could .direct flushing solutions into the
             underlying aquifer.                                        ' •   .'       ••'....
     •      Wet air oxidation was eliminated because volatile metals could vaporize, a significant
             concentration of metals would remain in the byproducts requiring disposal in a secure
             landfill or further treatment, and costs would be high.
     •      Molten salt was eliminated because volatile metals could vaporize, a significant
             concentration of metals would remain in the byproducts requiring disposal in a secure
             landfill or further treatment, and costs would be high.        i

      Innovative technologies eliminated during the screening of the three criteria include the
      following:                                           ,

      •      Ex situ vitrification was eliminated because its effectiveness is uncertain. Contaminant
             mobilization could occur during excavation.  The technology has not been widely
             adapted from the nuclear waste industry to the hazardous waste industry. Also,
             because of the small volume  of waste,  using an on-site waste unit would be most
             efficient.  According to Horsehead Resource Development Company, who have
             developed a flame reactor that is presently being studied under the EPA Superfund
             Innovative Technology Evaluation (SITE) demonstration program, it would not be
             cost-effective to construct a unit on site to treat such a small volume of waste.

       Innovative technologies eliminated during the detailed analysis inclucje the following:

       •      On-site soil washing  was eliminated because its effectiveness and reliability are
              uncertain and it would require treatability studies.  The studies would increase the time
              to implement the alternative  and increase the costs. This alternative would l?e the most
              difficult to  implement. The  technology requires that mobile iequipment be transported
              to the site.  The reliability of this process is not well- known, a Mi-scale study has not
              been completed and it is not considered widely available for use. The equipment and
              personnel would have to be  highly specialized.  This alternative would pose
              considerable short-term risk  due to dust generation because of the required soil
              handling.         .
                        ' '    '        '    *                    '   •   '  l  -               .
11.    Which of the nine criteria were weighted most heavily in selecting the technology?  Did failure
       to meet one of the nine criteria result in the elimination of the innovative technology?  If so,
       which criterion?  Which of the criteria supported the use of a standard technology?
          '                                                                                  '.
       The criteria that were weighted most heavily in selecting a remedial alternative were protection
       of human health and the environment, impiementability, and cost, llie chosen alternative
       protects human health through treatment of site soil and is readily ithplementable.  Other
       alternatives, RAA-2 and RAA-3, would provide as great or greater protection but would be
       more difficult to implement due to uncertainty associated with their reliability and
       effectiveness and both would require treatability testing prior to implementation.  Treatability
       studies in turn could lengthen the time required for these alternatives or increase their costs.
       Soil washing was eliminated due to difficulty in implementation and  potentially high costs.
                                                                                          1293

-------
   12.
                         ,,                                     based on an ARAR- what was
                  What risk level was selected to establish cleanup goals?
=======:
Contaminant
Carcinogens
Arsenic
Chromium
Lead
Nickel
DDT
Noncarcinogens
Barium
Cadmium
Selenium
Cyanide
"""" — 	
1
Cleanup Level (mg/kg)
T========s:
ARAR or Other Basis

20
400
250
1,600
2.9
MCTA"
. Riskb
MCTA
Risk
MCTA .

4,600
40
240
1,600
===^===
Risk
Risk
Risk
Risk
'
                'Cleanup levels were set at natural background as determined by Washington State
                Toxics Control Act (MCTA) Method A.                           .
                ••Risk was calculated by Ecology and Environment, according to MCTA Method B
           .     cleanup standards for residential sites. An acceptable range of risk includes for
                carcinogens, an excess upper bound individual lifetime cancer risk of between lO"4 to
                10 and for noncarcinogens, a Hazard Index less than or equal to 1.0.


        Was the innovative technology eliminated because of the cleanup goals? Could the standard
        technology meet the cleanup goals?       •                                      ««««««*


        Innovative technologies eliminated because of cleanup goals include:

        "      None

        Standard technologies eliminated because of cleanup goals include:

        •      Capping                                                              .
14.     Were treatability studies conducted on the innovative technology or standard technology?  •

       Treatability studies were not conducted.
1294
                                             -5-

-------
15.     What measures/criteria were used to compare alternatives?          i    '

        The following measures were used to compare the alternatives:

      .  -     Proven reliability                                           i
             Impact on nearby populations
                              .•-•..       .'•.'•'              ,\

16.     How are measures compared?                                           .'..--
                                                             ;  •         l
        Proven reliability played a major role in selecting a remedial alternative.  The chosen
        alternative removes site contaminants and treats and disposes of them off site.  This alternative
        utilizes readily implementable and reliable technologies.  The chosen alternative was preferred
        over treatment on  site, either with  stabilization or soil washing, because these technologies
        would require treatability studies.  Treatabijity studies could in turn significantly increase the
        time and cost to complete these alternatives.  The community was another factor in selecting a
        remedial alternative: Dust generated during soil washing was a source: of concern-due to .the
        potential for worker or community inhalation exposure.  And on-site stabilization was not
        preferred because it would restrict  future site  use.                   I


17.     What technical considerations werefactors in selecting a remedy'!'Were technical
        considerations primary in  the selection of the remedy?,

        The complex geological system of clay and silts precluded the use of soil flushing due to the
        potential for flushing solutions into the aquifer. This factor, however, jwas not primary in
        selecting a remedial alternative.
                                                                                              1295
                                                                        V :      • '  -           '
                                              -6- '  •      "•   .•-.',       ...         .   '   '  •.••  ',

-------
i-a.
'.It

-------