vvEPA
                United States
                Environmental Protection
                Agency
               Office of Water &
               Waste Management
               Washington D.C. 20460
  SW809
                Solid Waste
  November 1979
&?kS 000809
Siting of Hazardous Waste
Management Facilities
and Public Opposition
V';

-------
r

-------
  SITING OF HAZARDOUS WASTE MANAGEMENT

    FACILITIES AND PUBLIC OPPOSITION


              Final Report
This report (SW-809) was prepared under

 contract for the Office of Solid Waste
   U.S. ENVIRONMENTAL PROTECTION AGENCY
                  1979

-------
This report was prepared by Centaur Associates, Inc., Washington, D.C., under
contract number 68-01-5012.

Publication does not signify that the contents reflect the views and policies of
the U.S. Environmental Protection Agency but are solely the responsibility of the
contractor.  It is also noted that inclusion of specific sites or facilities does
not represent endorsement by either the contractor or U.S. Environmental Protection
Agency of  those establishments or the technologies employed.  Mention of commercial
products does not constitute endorsement by the U.S. Government.

An environmental protection publication (SW-809) in the solid waste management
series.

-------
                            ACKNOWLEDGEMENTS
Each siting attempt or operating facility described in this project was
included with the approval of the appropriate facility sponsor or
operator.  Thus special thanks are due to the industry and public agency
officials responsible for these siting attempts or facilities who agreed
to participate in this project.  Scores of state and federal regulators,
state and local elected and appointed officials, representatives of
local organizations and private citizens provided valuable information
for the case studies, and their cooperation is particularly appreciated.

In addition, a large number of EPA regional, state regulatory, and
industry officials were contacted in the process of identifying and
selecting a sample of cases.  These officials provided a significant
amount of general information and insights into siting and more general
hazardous waste problems.

Clark-McGlennon Associates assisted in the development of the framework
for collecting data and played a particularly useful role in outlining
issues to be addressed and considered.

Finally, the helpful assistance of the EPA project office is gratefully
acknowledged.

-------

-------
                             CONTENTS
I.     INTRODUCTION	

II.    BACKGROUND INFORMATION	    4

III.   PUBLIC RESPONSE	 .    9

IV.    ATTEMPTS TO SECURE SUPPORT...	   16

V.     FINDINGS AND CONCLUSIONS	   22

VI.    IMPLICATIONS FOR THE FUTURE	   27


APPENDIX A:  CASE STUDIES                                       •

       MONSANTO INDUSTRIAL CHEMICALS COMPANY:
        BRIDGEPORT, NEW JERSEY..	 i... .........   35

       FRONTIER CHEMICAL WASTE PROCESSORS, INCORPORATED:
        NIAGARA FALLS, NEW YORK	   46

       GULF COAST WASTE DISPOSAL AUTHORITY:
        TEXAS CITY, TEXAS	   54

       CHEMICAL RESOURCES, INC.:  TULSA, OKLAHOMA.	   88

       MASSACHUSETTS BUREAU OF SOLID WASTE DISPOSAL:          '
        STURBRIDGE, MASSACHUSETTS.		   98

       3M/CHEMOLITE:  COTTAGE GROVE, MINNESOTA.....	  110

       KANSAS INDUSTRIAL ENVIRONMENTAL SERVICES:
        FURLEY, KANSAS	 .  120

       BOB' S HOME SERVICE:  WRIGHT CITY, MISSOURI.	  I34

       WES-CON, INCORPORATED:
        GRAND VIEW AND BRUNEAU, IDAHO.	-.-..	  144
                                    I.

-------
                        TABLE  OF  CONTENTS  (Cont.)



                                                                    Page

       SCA/EARTHLINE:   BORDENTOWN, NEW JERSEY	    157

       ALLIED CHEMICAL:  ROSSVILLE, MARYLAND.	    176

       STATE OF MINNESOTA	    190

       STARR INDUSTRIAL SERVICES:
        STARR COUNTY, TEXAS	    207

       INDUSTRIAL ENVIRONMENTAL  SERVICES:
        KIRKSVILLE, MISSOURI	   220

       IT CORPORATION:  BRENTWOOD, CALIFORNIA.	    233

       PADRE JUAN:  VENTURA,  CALIFORNIA.	    245

       SCA CHEMICAL WASTE SERVICES, INCORPORATED:
        MODEL CITY, NEW YORK	    256

       ENSCO ENERGY SYSTEMS COMPANY:
        EL DORADO, ARKANSAS	,	    280

       CALABASAS, LOS ANGELES COUNTY SANITATION .DISTRICTS:
        LOS ANGELES, CALIFORNIA	.....	    292

       SCA/EARTHLINE,' INCORPORATED:
        WILSONVILLE, ILLINOIS	    303

       RESOURCE RECOVERY CORPORATION:
        PASCO,  WASHINGTON.	    317


APPENDIX B:  NEW ENGLAND REGIONAL COMISSION REPORT.	    332


APPENDIX C:  INFORMATION ON STATE REGULATORY AGENCIES..	    352
                                   II.

-------
EXECUTIVE SUMMARY

The major conclusion  of  this  study  is  that  public  opposition to  the
siting of hazardous waste management facilities, particularly landfills,
is a critical problem.   It  is the most critical problem  in  developing
new facilities, in the opinion of most government  and  industry officials
interviewed for this  project.  Once a  facility is  sited, problems with
public opposition are not over.  Local communities can and  have  forced
operating facilities  to  close.

Opposition is rooted  in  fears of major and  long-term risks  posed by
facilities to the health and  welfare of the surrounding  community.   It
reflects a loss of faith by local residents in the ability  of government
and private industry  to  solve environmental problems and at  the  same
time to consider and  protect  local  interests.

If problems with public  opposition  cannot be solved, the implications
may be enormous.  The implementation of RCRA will  lead to the closing
of facilities now receiving hazardous  waste and to much greater  demand
for proper disposal sites.  Recent  efforts to clean up abandoned sites,
including the superfund  proposal, will produce even more hazardous waste
that must be disposed of properly.  If public opposition continues to
frustrate siting attempts,  there may be no place to put all  this     :
hazardous waste, and the national effort to regulate hazardous waste may
collapse.

The sensitivity of the problem was  demonstrated early  in this project.
It was decided that each site visit would be made  only with  the  approval
of industry and key regulatory officials.  While over  80 sites appeared
to be suitable for the study, only  21  sites were visited.  Many  industry
and some regulatory officials  thought  interviews with  opponents  would
only increase opposition to sites and  that participating in  this project
presented risks to sites and  did not offer corresponding benefits.   They
thought public opposition needed to be studied, but were opposed,
sometimes strongly, to having facilities they operated or regulated
studied.  These officials preferred to "let sleeping dogs lie."

Public opposition involves  a  wide range of people, often amassing
considerable resources.  Those who  have raised concerns or .voiced
opposition in cases studied for this project have  included grandmothers
and U.S. Congressmen, factory workers  and university scientists, those
who never graduated from high school and those with doctorates in
ecology and physical sciences.  What unites these  people is  their
concern and opposition to facilities in their communities.   Opponents
have sometimes shown remarkable skill  in political organizing (sometimes
drawing on the public opposition experiences of the anti-Viet Nam war
movement) and have often acquired technical expertise  to support their
positions.
     /                                                           .

The controversies surrounding particular sites or facilities have
reached levels of stridency impossible to convey in reports such as  this
                               III.

-------
one.  In one case studied, an.angry mob was prepared to blow up a
facility, but was convinced not to.  There were two reports, impossible
to confirm, of threats of death or physical harm to key individuals or
their families.  In one case the threat was reportedly made to a
facility sponsor, in the other to a local official who opposed a
facility.

Based on the experience studied for this project, public opposition
often arises as soon as the community learns of a. proposed facility.
Excluding hazardous waste generator-owned facilities, the facility
sponsor is either unknown to the local community or, if known, may be
associated with problems at other facilities.  The community envisions
few benefits from the proposed facility — a few jobs and perhaps some
tax revenues.  Risks are often seen as overwhelming — a ''Love Canal" in
their community, polluted water supplies threatening the entire
community, decades of uncertainty, hundreds of trucks carrying thousands
of drums of hazardous waste on local roads.  The industries that produce
these wastes may be hundreds of miles away.  Because local communities
perceive the risks to be great, they demand that the probability of
something going wrong be low or, more often, non-existent.

The facility sponsors are often surprised by the vehemence of public
concern and opposition.  Their technical studies present arcane data to
show that the proposed facility meets all regulations.  Yet opponents
are often able to hire experts who can refute the facility's sponsors
claims.  As opposition continues, the facility sponsor may offer to
change the proposal to suit the community.  From the community's
perspective, these offers are too little, too late.  Opponents question
the fairness of having their town bear such a large share of the
environmental costs of modern industry.  Facility sponsors rarely, if
ever, address this question of equity.  (Throughout this process the
community talks in terms of risks and fears, the facility sponsor in
terms of regulations and technology.  The terms of one are often not
understood by the other.)

The state regulatory agency often is caught in the middle.  The agency
seeks to protect the environment by encouraging proper disposal
facilities.  Opponents may accuse the agency of destroying the
environment and endangering the public health by granting the facility
sponsor a permit.  If the agency preempts local controls, it may further
incur the wrath of a community that feels powerless to control its own
development.  Thus state regulatory officials are subjected to the same
suspicion and hostility as the facility sponsors.

Should present approaches to siting facilities continue, the data of
this project indicate that the prospects for successful sitings in most
regions of the country are dubious at best, and grim at worst.  National
publicity concerning abandoned sites has made citizens and local
officials increasingly aware of hazardous waste problems.  They are also
likely to be increasingly aware of actions taken by others to stop
sitings.  Opposition will, in all likelihood, become more widespread
                                IV.

-------
and sophisticated.  Even if not ultimately successful, opponents may
increasingly turn to the courts and delay sitings for months or years
with costly law suits.

Overcoming this opposition will require diligence and imagination.,
States will have to play the lead role in siting.  States must be
perceived as the arbiters in the siting process.  They must strike a
delicate balance between the need to protect the public health through
environmentally sound disposal, and the economic viability of industry.
Industry must be sensitive to and anticipate the broad range of public
concerns.  Unless circumstances change dramatically, EPA has no direct
role in siting.  EPA, however, should support continued research to
develop hazardous waste management technologies to be used by states and
industry and develop guidance to the states on the management and
regulation of facilities.  EPA should also join with the states to
provide more public information.  That information must demonstrate that
there are positive solutions to what has unquestionably been defined by
EPA, the media and others, as a major environmental problem.
                                V.

-------

-------
I.
PROJECT OVERVIEW
Project Purpose

The purpose of this project was to provide insights into those factors
which give rise to public opposition to the siting and operation of
hazardous waste management facilities, and to identify the actions 'taken
to try to reduce or to overcome that opposition.  The project was to
address cases where no opposition occurred, where opposition was
overcome, and where opposition led to either an abandoned siting attempt
or the closing of a facility.

Methodology

Because no centralized data existed on public opposition to siting
attempts or operating facilities, it was necessary to identify a sample
of cases suitable for the project.  Specifically, 30 cases conforming to
the following range of situations were to be studied.

       •     Situation 1.  No public opposition; new facility,
             successfully sited; six cases.

       •     Situation 2.  Public opposition; facility  siting attempt
             successful; six cases.

       •     Situation 3.  Public opposition; facility  siting attempt
             unsuccessful; six  cases.

       •     Situation 4.  Public opposition; operating facility       :..:
             continues to  operate;  four  cases.

       •      Situation 5.  Public opposition; operating facility  forced
              to  cease operations; four cases.

       •      Situation 6.  Public opposition to planned or actual       :
              expansion of  a  facility;  four cases.             .          .

 In addition to the conditions  specified by the  situations, individual
 cases were identified according to  the following criteria -- disposal   ':
 method,  ownership, location  by EPA  Region, wastes  handled, urban versus
 rural location,  and adjacent land use.  The use of these criteria was1,
 based on the assumptions that  the criteria were linked to public
 opposition and that with more detailed initial  descriptions a sample
 which allowed for diversity  within situations and comparability between
 situations could be identified.                              •

 Data used to identify a sample were gathered through telephone .
 interviews of EPA regional office staffs, state regulators, and (in a
 few instances) local regulatory officials.  All EPA regional offices and
 39 state regulatory agencies were contacted and eventually 90 cases were
 identified that could be tentatively classified by the six situations.

-------
 After identifying potential cases,  a sample of 30 cases and six
 alternate cases were selected.   (The alternates were to be used,  if
 needed,  to replace recommended cases.)  Several factors influenced the
 selection of this sample:   the desire  to have a sample  that was diverse
 yet which allowed for analysis of comparable facilities in different
 situations;  the desire to  have a sample that reflected  national
 patterns, (for example,  regional distributions as reflected in earlier
 facility inventories); and the  recommendations of EPA regional office
 and state regulatory agency staffs  familiar with local  controversies.

 The final step in determining which cases were to be studied was  the
 acquisition  of approval from key parties.  It was originally decided
 that no  site visit would be conducted  without the approval of  the
 facility sponsor.1  This approval was  made with the  understanding that
 those involved in the opposition to particular facilities  would be
 interviewed.   Facility sponsors  were often reluctant  to  grant  needed
 approvals.   Some  were vehemently opposed to the very  idea  of the
 project.   One facility sponsor threatened to  sue both EPA  and  Centaur if
 his facility was  included  in the sample.   Another suggested  that  if a
 site visit was conducted the local  sheriff should accompany  Centaur
 staff to his facility.   Without  doubt  this proved to  be  the most
 difficult problem in developing  a final sample.

 This problem has  substantially affected the  overall  project and is
 illustrative  of the sensitivity  of  the public opposition issue  and of
 hazardous waste problems in general.   In practice  five approvals — from
 the facility  sponsor,  EPA  headquarters,  EPA regions,  state regulatory
 agencies,  and Centaur  — had to  be  obtained before a  case  was included
 in  the sample.  For one-third of  those identified  cases, facility
 sponsors  declined to participate  in the  project.   For another
 one-quarter  of  the cases it was  determined  that  because  of substantial
 regulatory violations  or ongoing  state  investigations of possible
 violations, those cases  should be excluded.  Pending permit reviews and
 other  factors led  regulators  to  disapproval of additional  cases.
 Primarily because of case  approval  problems, the  final sample was
 reduced to 21 cases, Situation 6 cases were eliminated,  and a report on
 the New England Regional Commission's hazardous waste program was
 prepared.

 The  final sample, then, is necesarily skewed,,  This has  overall
 implications for  the project.  Of the largest national waste service
 companies, only one (SCA Services,  Inc.) is represented  in the  sample.
Thus there is probably an underrepresentation of problems that  may be
associated with larger companies that operate and/or are attempting to
site several facilites.  It is also possible that more controversial
   For the sake of clarity, "facility" is used to refer to hazardous
   waste mangement facility and "sponsor" refers to a company or  agency
   that has sponsored a siting attempt or is operating a facility.

-------
sitings or facilities were excluded. ,  If this is true then this report
underestimates the extent of public opposition.   Conversely,  some
actions that,have been effective in reducing opposition may not have
been identified.   A large number of cases where  opposition had
dissipated were excluded, because facility sponsors feared that
opposition might  resurface if local leaders were interviewed by Centaur.
In spite of these possibilities, there is every  evidence that the•final
sample is representative of current problems.  Factors that gave rise to
opposition and the issues raised by opponents tended to be common to
most cases.  Furthermore, actions in response to public opposition
showed many similarities between cases.

Interviews and reports, newspaper articles and other secondary sources
were used to prepare case studies.  Local officials and representatives
of local civic and special interest groups provided most information on
public concerns and opposition issues.  In some cases where no
opposition arose it was necessary to restrict interviews to selected
local officials in order to gain the facility sponsor's agreement to
participate in the project.

Report Organization

The report is composed of six sections  and three appendices.  Section II
presents background information on the  21 cases.   Sections III and  IV
discuss  public response  and attempts to secure  support, respectively.
Findings and conclusions are delineated in Section V, and in  Section VI
the implications  of  these data  on the  future siting  of  hazardous waste
management facilities are discussed.

In Appendix  A are the 21 case studies.   For  a more complete under-
standing of  siting problems, the  reader is  encouraged to  refer  to these
case  studies.  Each  case study  provides background information  on the
specific site, facility, and local .community.   The history of facility
development  and  public response is presented chronologically.   Based on
those data the attempts  to  secure support are identified  and  analyzed,
the major  issues are summarized,  and the factors  leading  to public
support and/or acceptance  are  listed.   Finally, various views of  those
interviewed  are  presented,  including retrospective views  of the
particular case  and  more general  views on hazardous  waste management
 problems.   While the focus  of  these  latter views  varies widely, they  are
 included because they have  been generated by the  specific case history
and they elucidate what  are perceived  to be major problems  related  to
 siting facilities and solving  hazardous waste problems.  Appendix B is  a
 report on the New England Regional Commission's hazardous waste program.
 This was included in the project  to  illustrate  new governmental
 approaches to siting.   Appendix C presents, for states  in the sample,
 basic data on state regulatory agencies and programs and  regulatory
 officials' views on siting and governmental involvement in siting.

-------
 II.
BACKGROUND INFORMATION
 Various data were collected for each proposed or operating  facility
 studied.   These data are  presented in a  table, at the  end  of this
 section.   The location of each case studied  is shown  in the accompanying
 The  sample  of  cases  studied was  national  in  scope and included
 facilities  using  four  distinct technologies  —  land  disposal, treatment,
 incineration,  and deep well injection.  The  sample was intended to be
 representative, not  random.  As  indicated below, the locational
 distribution is generally not inconsistent with the  national
 distribution of operating facilities.  The clear exceptions are an
 underrepresentation  in the sample  of EPA  Region V, which data indicate
 has  the largest number of facilities, and an overrepresentation in EPA
 Regions VI  and VII.  In terms of the technologies used at or proposed
 for  facilities in the  sample, the  sample  is  heavily  weighted in favor of
 land disposal  and under represents  treatment  and incineration
 technologies.  Each  of those technologies is represented in the sample.
 as shown in the table  on the following page.
                  Locational Distribution of Sample and
                  National Distributions of Facilities
                              (in percent)
EPA Region

I
II
III
IV
V
VI
VII
VIII
DC
X
        Snell Report1      Straus  Report2     'Centaur  Sample
              6%
             16
              8
              6
             25
              9
              7
              1
             17
              5
 4%
14
10
 4
31
11
10
 0
12
 4
 5%
19
 5
 0
14
19
14
 0
14
10
   Foster D. Snell, Inc., "Potential for Capacity Creation in the
   Hazardous Waste Management Service Industry," National Technical
   Information Service, August, 1976.

   Matthew A. Straus,  "Hazardous Waste Management Facilities in the
   United States—1977," U.S. Environmental Protection Agency,
   January, 1977.

-------
                  Technologies Utilized in Sample and
                       in Operating Facilities*
                              (in percent)
Technology

Land disposal-*
Treatment/processing
Incineration
Injection well
Other4
Straus Report'

       53%
       58
       28 ,
        5
        4
Centaur Sample

        86%
        19
         5
         5
         0
When generator-owned facilities are excluded, only one facility in the
sample does not intend to accept a broad range of hazardous wastes.  For
most facilities it was easier to define wastes not accepted (e.g., no
facility studied accepted radioactive waste) than to define the wastes a
given facility would accept.  For the general public the most signific-
ant wastes that a facility can accept are what have been termed "politi-
cal wastes" such as PCBs, 2,4,5T, Kepone and Dioxin.  These are wastes
that have achieved public notoriety and some facility sponsors have
indicated they will not accept such waste solely because of that
notoriety.

The cases in  the sample are located in a full range of settings from
urban industrial areas to remote underdeveloped areas.  A similar
diversity is  shown in site size and site life.  Landfills ranged in size
from five to  260 acres and from one to 60 years in projected life.

Market areas  for facilities (excluding those designed to serve a
specific waste generator) also showed wide  diversity in geographic size
and were related to facility ownership.  The smallest market areas were
composed of the waste generators in one urban area.  All facilities with
local markets were publicly owned.  Conversely, all multi-state market
areas are associated with private commercial facilities.  Some of those
interviewed for this study explained that to be economically feasible a
commercial facility must serve a multi-state area.  In addition, the
    Because one facility may encompass more than one technology
    (e.g.,  landfill and incineration)  columns add to more than 100 per-
    cent.

    Straus, see .previous table.

    Includes landfills, landfarms,  lagoons and pits.

    Includes ocean disposal and  storage.

-------
size of the market area for a substantial number of commercial
facilities appears to indicate two things.  One is that the commercial
service industry is becoming increasingly centralized.  The other is
that a permitted operating facility fills a dire need for such
facilities and can expect to receive a large volume of business from
generators hundreds and even thousands of miles away.

-------
                          Background Information on  Cases  Studied
Situ.- EPA Facility
Case tlon Region Type
Monsanto
Bridgeport, HJ
Frontier Chemical
Watte Processor. ,
Niagara Falls, NT
Gulf Coast Waste
Disposal Authority
Texas City, IX
Chemical Processors
Tulsa, OK
BSUD
Sturbrldge, HA
3H/Chemollt«
Cottage Grove, KN
KIES
Furley, KS
Bob1 8 Home Service
Bright City, HO
WES CON
Bruneau, ID
SCA/Earthllne.
Bordentown, HJ
Allied Chemical
Ros.vllle. MD
MPCA/EPA
State of Minnesota
Starr Industrial
Starr County, TX
IES
Klrfctvllle, HO
IT Corp.
Oil Well, CA
Fadre Juan
Ventura, CA
SCA Chemical
Wastes Services
Hodel City, ta
ENSCO
El Dorado, AR
•Calabasaa
Los Angeles, CA
SCA/Earthllne
Wllsonvllla, II.
Resource Recovery Corp.
Fasco, WA
1 11 Landfill
1 II . Treatment

1 VI Landfill
Landfam

1 VI Injection
Well
2 I Landfill
2 V Landfill
2 VII Landfill
Treatment
2 VII Landfill

2 I Landfill

3 II Landfill

3 III Landfill
3 V Landfill
Treatment
3 VI Landfill

3 VII Landfill

3 IX Landfill

3 IX Landfill
4 II Landfill
Treatment

4 VI ' Incinerator

4 IX Landfill
5 v Landfill
%
S X Landfill

Hastes
Accepted
Generator1*
Wastes Only
Broad Range
Liquids Only

Broad Range


Broad Range
Liquid. Only
Selected
Range
Generator* a
Hasten Only
Broad Range

Broad Range

Broad Range

Broad Range

Generator's
Vastes Only
Broad Range
Broad Range .

Broad Range

Broad Range

Broad Range
Less Hazardous
Broad Range

Broad Range

Location
Rural
Urban

Urban


Urban
Suburban
Suburban
Rural

Rural

Rural

Urban

Urban
Suburban
t Rural
Rural

Rural

Rural

Suburban
Suburban

. Urban

Broad Range , Surburban
Less Hazardous
Broad Range

Broad Range

Rural

Rural

Adjacent Site Size
Land Use (Acres)
Industrial
Induatrial

Industrial


Industrial
Residential
Undeveloped
Industrial
Agricultural

Residential

Undeveloped

School

Industrial
Residential
Varied
Agricultural

Agricultural

Agricultural

Agricultural
Residential
Industrial
Undeveloped

Industrial

Residential
Undeveloped '
Residential
Agricultural

Agricultural

6
8

200


4
105
S
80

15

20

S .

38
200
40

192

160

28-135
200

45

260
130

250

Site Life
(Years)
5
H.A.2

30


500+
6+
1
18

5-10

10

1-2

12
5
3-4

18-20

40-60

1-254
20-25

H.A.*

3-40
20

SO

Ownerahip
Private,
Generator
Private,
CoBoercial

Public


Private,
Commercial
Public
Private,
Generator .
Private,
Commercial

Private,
Coomercial

Private,
Commercial

Private,
. Commercial

Private,
Generator
Public
Private,
Commercial

Private,
Coanerclal

Private,
commercial

Public
Private,
Commercial

Private,
Commercial

Public
Private,
Commercial

Private,
Conmerclal

Market
Area
H.A.I
Multi-
State

Local


Multi-
State
State
R.A.I
Multi-
State

Multi-
State

Multi-
State

State

N.A.1
State
state

Multi-
State

State

Local
Multi-
State

Multi-
State

Local
Multi-
State

. Multl-
Stete

1  Because this facility is owied by and serves only the generator, a*rket area does not apply.

*  Facility treats hazardous waste and theoretically haa an infinite life.
3  facility 1. a «... I I-mdflll U d«lBnatlon U.cd In California).  Wile «... I landfill, can accept .11 hazardous «.«.. this facility
   restrict* waitca to thooc of a less hazardous nature.

*  Facility la «n Incinerator and theoretically haa an infinite 111*.

-------
                                                  Location of Cases Studied
00
LEGEND

• Landfill
DTreatment, processing facility
• Incinerator
O Injection Well

-------
III.   PUBLIC RESPONSE              ,

The siting and/or operation of nearly all the hazardous waste management
facilities visited has given rise to at least some public concern or
opposition.1  Only a few received some support from the public, tacit
or otherwise, and in most cases this public support was due to actions
taken by the sponsor.  These actions and their results are described
below in Section III, "Attempts to Secure Support".  Only if this
support was due to pre-existing conditions or coincidental but unrelated
events is it described in this section.  Therefore this section is
primarily concerned with opposition to facilities.

Factors Which Have Given Rise to Public Opposition

Public opposition to the siting/operation of hazardous waste1management
facilities is so widespread that it might be thought to be unavoidable.
To what extent this might be true, it is also clear from the case  •
studies that the extent and ultimately the effectiveness of public
opposition is influenced by identifiable factors.  These factors include
actions taken (or not taken) by the sponsor, pre-existing conditions,
and coincidental but unrelated events.  To the extent that these factors
are beyond the control of the facility sponsor they might be thought of
as expected risks.   It must be noted that few if any of these  factors
are necessarily,important for all sites, and that  in each situation the
sponsor will have to face a different set of problems.

Public relations— Actions taken or not taken by  the sponsor  which give
rise  to public opposition center around public relations.  One factor  in
particular which has been blamed for the demise of a number  of sites and
potential sites is the failure to inform local residents and elected
officials of development plans, so  that they are presented with a fait
accompli  in terms of site location  and facility plans.  Another is
informing the local  public of these plans in such  a way that the lack  of
local input is readily apparent.  An egregious example of this sort of
approach  is found in the Minnesota  case study.  Local residents were not
informed  of the siting process until the number, of potential sites had
been  reduced  to four, and then only by the local press.  The ensuing
uproar has been cited as the major  reason for the  failure of this siting
attempt.  Early discussions of disposal problems and plans with local
elected officials has on the other  hand led to public support  (3M).2
    The only site which faced no discernible public  concern or
    opposition was Gulf Coast Waste Disposal Authority in Texas  City,
    Texas.

    Case studies named parenthetically throughout.this and following
    sections illustrate the points raised.   However,  examples  can
    usually be found in other case studies.   For more detailed
    information, refer to the cited case study(ies)  in Appendix  A.

-------
 A public relations campaign which stresses primarily the  danger
 associated with hazardous  wastes (Minnesota)  can also lead  to  public
 opposition, as can unfortunate statements by  employees of the  sponsor.
 In one case (SCA/Wilsonville),  the site owner was quoted  in the  local
 press as saying that although they were not at that  time  disposing  of
 nerve gas,  they could if they wanted  to.   A positive public relations
 effort can, conversely, lead to public support or at least  vitiate
 public opposition (3M).  However,  such an effort can backfire  if it is
 based on untruths.   The Wilsonville facility  was first announced as a
 mine  reclamation/resource  recovery center,  and the local  public  felt
 betrayed when they found it was actually a hazardous waste  landfill.

 On the other hand,  in certain circumstances a low-profile approach, with
 no public relations or public information effort,  has  worked very well.
 Both  Chemical Resources and Gulf Coast,  whose sites  were  located in
 heavy industrial areas, adopted this  strategy.

 Public information — Another related factor  is  technical or other
 information supplied to the public by outside parties,  some of whom may
 be opposed  to the site or  who wish to conceal its  existence (Padre
 Juan).   This problem can be exacerbated  if  the sponsor fails to  provide
 the public  and local elected officials with available  information which
 is favorable to the site (IT Corp.).   Equally,  there may be difficulties
 if the  sponsor is unable to respond satisfactorily to  public concerns
 (Allied).

 Technical studies supporting proposed or  extant  sites  and facilities can
 contribute  to  public support if  they  are  produced  by a neutral body
 recognized  by the public as such,  for example, a local  technical
 official  (Monsanto)  or state or  federal regulatory agencies  (Ensco).
 Conversely,  such third party reports  can  fail  to have  any effect on
 opposition  (SCA/Model City).

 Credibility of  sponsors and regulatory agencies —   The credibility of
 the sponsor is  a  major factor in the  forming  of public attitudes toward
 the site.   Credibility is a  function  of public perceptions of the past
 history of  the  facility sponsors.  If  the developer  is perceived to have
 a  questionable history, and  especially if this involves the operation of
 similar sites,  then  the public  is  unlikely  to  accept his assurances that
 this particular operation will be  properly conducted.  Ensco's previous
 problems with  its Shakopee,  Minnesota  facility accounted for the
 opposition  to its operation  in Arkansas.  SCA  Services has faced
 credibility  problems  since  its Wilsonville facility was shut down by the
 courts.  On  the other hand, a firm such as Monsanto,  well known and
 respected in the  local community, was able to make use of this good will
 in gaining public support for a facility.  Evidence that the sponsor is
willing to negotiate  in good  faith with the community to allay local
concerns can have the same effect  (Monsanto, BSWD).
                                     10

-------
Credibility is also an function of the successes of previous siting
attempts.  If other communities have been unwilling to accept the
facility, this will not be perceived as a recommendation for it.  The
Ventura ^Regional County Sanitation District's attempt to site a facility
in Padre Juan Canyon was defeated due, among other things, to the
failure of previous attempts to site the facility elsewhere on account
of adamant public opposition.  State regulatory agencies' perceived lack
of credibility may also have a similar result (SCA/Model City).  Agency
credibility can, however, have the opposite effect (BSWD).

National publicity given hazardous waste — The,timing of national
publicity given hazardous waste in general and sites such as Love Canal
in particular is an important coincidental but unrelated factor behind
public opposition to facilities.  It can be an influential factor in
setting the tone of public response.  Although this was specifically
mentioned as a factor behind public opposition at only two sites
(SCA/Model City, IBS), it seems.very likely that the increasing public
awareness of the hazards associated with hazardous waste — a factor
underlying a large part of public opposition — is due to this
publicity.                                                           ,

Political wastes—  Another factor which has often given rise to
opposition to a particular facility is the acceptance of "political
wastes" (Ensco, Resource Recovery Corp., SCA/Wilsonville).  "Political
wastes" are substances such as PCBs and Kepone which have achieved
particular notoriety in the public mind, generally due to publicity in
the national media.

Public attitudes — Local public attitudes toward hazardous waste vary
considerably across the country.  For instance, the population in the
vicinity of the Wes-Con facility in Idaho has a history of public trust
in government.  They have also taken the position that one should be
able to do what one wants on one's own land.                     ,

Facility operations — Especially if a facility is already operating,
potential or actual operational problems may give rise to concern.
These problems include odors (KIES), fires (SCA/Model City), and spills
and subsequent damage to flora and fauna (Resource Recovery Corp.).  If
the site itself is perceived as being obviously unsuited for hazardous
waste disposal, such as Padre Juan Canyon overlooking the Pacific, this
may also be a factor behind public opposition.

Local political organization — One pre-existing condition of particular
importance is the political sophistication of the population in the
vicinity of the proposed or operating site.  If the area has a history
of political activism (Allied) or previous experience opposing a
facility siting attempt (SCA/Bordentown), then it is likely that
organized opposition to the siting attempt will appear that much sooner.
As discussed below, the organization of liaison committees by the
sponsor has sometimes had the same effect (BSWD).

-------
Issues And Concerns Raised During The Course Of Opposition

After public opposition to a hazardous management facility has arisen,
certain issues and concerns are often seized upon in an attempt to stqp
either the siting or the continued operation of the facility in       -.
question.  These issues may reflect public concern and thus are often
the result of the public education that often accompanies opposition.
Alternatively, however, they may be chosen solely on the basis of their
potential usefulness in stopping the facility siting or operation.  Some
of the issues described below tend to overlap with factors described in
the previous subsection.  Indeed, many factors that give rise to
opposition become issues that sustain opposition and are focal points of
debate during opposition.  On a general level, the distinction between
factors and issues cannot always be clearly drawn.  In specific cases,
however, it is usually possible to identify those conditions or events
that have sparked and galvanized opposition (defined for this report as
factors) and those arguments and concerns that are used by opponents to
support their position (defined for this report as issues).  These
issues fall into several groups or categories, described below.

Site and facility characteristics — Issues which have been raised
include particular aspects of site suitability, such as soil
permeability (SCA/Wilsonville) and seismic stability (Padre Juan);
problems associated with site operations, such as odors or fires, and
the existence of contingency plans (IT Corp.); the possibility of
environmental pollution, especially groundwater contamination (3M); more
appropriate or higher uses for the site (Starr); and provisions for
long-term maintenance (SCA/Model City).

Siting process — There were also concerns with the siting process
itself, including the 'possibility that other, superior sites had not
been considered (BSWD) and that subjective siting criteria were used
(Minnesota).  The lack of substantive public input in the siting process
has been mentioned as an issue in many cases (KIES, Minnesota), as has
inadequate public information and the failure to notify the public of
either the process or of their potential role in it (SCA/Wilsonville).

Sponsor and regulatory agency credibility — If the credibility of the
sponsor does not initially give rise to public opposition, it is often
raised subsequently during the course of public debate (IBS,
SCA/Bordentown, Ensco).

Transportation —  Possible problems associated with the transportation
of hazardous wastes to the facility have often been cited, including the
possibility of waste spills (Chemical Resources) and damage to highways
and property caused by heavy trucks (Calabasas).

Wastes to be disposed of at the proposed facility —  The types of
wastes to be accepted at the facility are also likely to be a matter of
public concern.  This includes "political wastes", which, as noted
above, are often a factor in the rise of public opposition, and if not,
will almost invariably be raised as an issue during the opposition (Wes-

-------
COB.).  Hovrever, h.azardou.8 waste in general is also of concern.  This has
been blamed on the national publicity accorded Love Canal and other
cases of improper disposal of hazardous waste.

Local residents also seem to perceive that their community's image will
suffer if it becomes known as a "dumping ground" for such wastes
(SCA/Model City).  Furthermore, in some cases the possibility has been
raised that the community will then be unable to keep out other such
facilities if one is permitted (3M).

Local publics have of ten questioned whether there is really a need for a
hazardous waste management facility at all in their region (Minnesota). ,
This belief, which is generally incorrect from any sort of objective
point of view, can sometimes be traced to public misinformation on the
extent of the hazardous waste disposal problem.  More typically, this,is
believed because local industries do not themselves produce large
amounts of hazardous wastes or because the public is under the
impression that alternative technologies, such as resource recovery,
could be relied upon to perform the same function (Padre Juan).

In addition, if hazardous wastes to be disposed of are not locally
generated, the public often manifests opposition to the disposal of
wastes from other areas, especially if the wastes are from out of state
(Resource Recovery Corp., SCA/Wilsonville).  Residents of rural areas
have expressed opposition to accepting wastes generated by urban
industries (Minnesota, Starr).  Their objections are based on the
likelihood that they would.be bearing risks associated with these wastes
while others receive the benefits.

Effect of the facility on the surrounding area—  Another category of
issues raised concerns the area surrounding the proposed or operating
site.  These include the contention that the area is too populated
(KIES), that property values will suffer (Allied, SCA/ Wilsonville), or
that the aesthetics of and quality of life in the area would be
adversely impacted (Calabasas).

Economic issues —  Another major.category of issues involves economic
concerns — economic disbenefits or lack of economic benefits.  In the
case of government—owned sites, the issue of loss of property taxes has
been raised (Minnesota).  Hazardous waste facilities generally provide
few if any jobs for the local community, although in isolated cases jobs
reportedly were promised (Starr, SCA/Wilsonville).   Actual or expected
losses to local.agriculture supposedly attributable to facility
operations can become an issue in rural areas (Resource Recovery Corp.).
Finally, the lack of compensation for the nuisances and risks which are
perceived to accompany such facilities may be a concern (Minnesbta).  In
other cases, a direct tie between the proposed facility and jobs can
give rise to local public support (Monsanto, 3M), although if these jobs
are not located in the immediate area the effect is considerably less
significant (Allied).

Local control — Local control of land use (Allied, IT Corp.) and
hazardous waste management (IES) has occasionally been raised as an
issue.
                                      13

-------
Site-specific issues — In addition, site-specific issues have also been
raised by those opposed to a particular site or facility.  For example,
the impact of a facility on Shell Oil Company's oil and gas producing
operations also located on the site was an issue in the IT Corporation
case.                                                     .

Tactics Used by Facility Opponents

The most common tactics used by local residents and elected officials in
opposing hazardous waste management facilities are testimony at public
hearings, initiating or threatening to initiate lawsuits against the
facility sponsor to have the site closed, and hiring outside experts to
testify or develop a technical case against the facility.

The effectiveness of the public hearing as an opposition technique
usually depends upon the ability of the public or of local officials to
use hearings as a vehicle for demonstrating the extent of their
political influence.  Technical experts hired by opponents have at best
been able to stalemate the situation.  Most lawsuits initiated by
opponents to'date have been unsuccessful in the courts, but have been
moderately successful as a delaying tactic.  They have also added
substantially to the sponsor's cost.  Other more or less prevalent
tactics include letters to the media and regulatory agencies (SCA/Model
City), editorials in the local media (Ensco), and petitions (IBS).

Local elected officials have almost always been involved in the
opposition, either of their own accord or in response to pressure from
local residents.  In addition to taking part in the above-mentioned
activities, such officials have also passed resolutions against the
facility (IES, SCA/Bordentown), promulgated a local ban on the
acceptance of PCBs (Ensco), ordered a facility to close down (Resource
Recovery Corp.), and — supposedly to resolve a drainage problem —
have had a ditch dug across the entrance to a facility (Wilsonville).
Local officials have considerably more power to influence the course of
events in states where permits from local (including county)
jurisdictions are required to site and/or operate a facility (e.g.,
California).  In these cases, officials can deny a permit or impose
stringent conditions before one is issued (3M).

In only one case (Gulf Coast Waste Disposal Authority) did a local
elected official take active steps to support a siting attempt.  This
official acted to benefit a local industry which formed the economic
basis of the community.  This official acted in the absence of any
public response, either for or against the siting attempt.

Ad hoc groups are also quite frequently found to have been involved in
opposition to a given facility.  Besides organizing the opposition and
originating or participating in some of the actions previously
mentioned, ad hoc groups have sponsored public debates on facility
siting between themselves and the sponsor (SCA/Bordentown).
                                      14

-------
The final category of opposition tactics reported includes civil
disobedience (SCA/Wilsonville) and other actions which violate the law.
Threats of violence have been made, both against the facility itself
(SCA/Wilsonville) and against state personnel sent out to prospective
sites (Minnesota).
                                      15

-------
IV.
ATTEMPTS TO SECURE SUPPORT
In the cases studied for this project diverse responses have been made
to the concerns and issues raised by the public.  While the ideal goal
of these responses is to secure support for the given site and/or
facility, the practical goal in almost every case is much more modest.
At a minimum it is generally hoped that concern and opposition can be
reduced to a manageable level (defined as that level which does not
block siting or close the facility).  This minimal level is generally
not exceeded.  In a minority of cases, responses to public issues and
concerns were able to elicit a significant level of public acceptance.

Attempts to respond to public concerns and opposition can be subdivided
into two groups.  One includes efforts to secure support or reduce
opposition to specific sites and/or hazardous waste management
facilities.  The other includes efforts to secure support for hazardous
waste regulatory programs and procedures.  Support for regulatory
programs and procedures in most cases leads directly or indirectly to
support for specific sites and/or facilities.  In this section, the
actors who make these attempts, the tactics they use, and the issues
raised in support of facilities are discussed.

Actors Involved in Public Support

Seemingly everyone agrees that hazardous waste disposal is a major
problem that must be solved.  However, when a specific solution (i.e.,
facility) is proposed the consensus collapses.  Based on the experiences
studied during this project, the facility sponsor usually has the active
support of few if any parties.  Those who have actively supported
facility sponsors are described below.

Private facility sponsors — The majority (15 of 21) of planned or
operating facilities surveyed in this project were initiated by private
industry.  For obvious reasons these private facility sponsors were the
most active parties in soliciting support for their own facilities.  Of
these private facilities, 12 were commercial facilities and three were
on-site facilities owned by and for the exclusive use of hazardous waste
generators.  For the commercial facilities, the primary motive for
development was profit.  For captive facilities, the motives for
development included solving the generator's own disposal problems,
reducing costs by not using commercial facilities, and responding to
state and/or federal regulations.

Government planning and management agencies — In six of the cases
studied, government agencies were to be the owners and/or operators of
the facility.  Three of these were state agencies and three were county
or multi-county agencies.  These agencies played the same role as
private facility sponsors.  However, these governmental agencies were
significantly more susceptible and sensitive to political pressures and
were significantly more responsive to the concerns of the public.
                                     16

-------
Governmental agencies became involved in hazardous waste management
primarily in response to the need of generators within their
jurisdictional bounds.  Their involvement was an extension of their
roles as providers of environmental services and was not perceived as a
revenue-generating activity.

The one major exception to this general description was the case" of the
Minnesota Pollution Control Agency (MPCA), which sponsored an EPA-funded
facility siting attempt.  Unlike the other governmental facility
sponsors, MPCA is also responsible for regulating hazardous waste
management.  Thus MPCA was the only governmental agency which could have
been in the position of regulating its own facility.

State regulatory agencies — In theory, state regulatory agencies are
neutral parties in siting attempts.  In practice, these agencies often
are perceived by the public to be proponents of specific sites and/or
facilities.  When public knowledge of, siting occurs only after
substantial review by state agencies (e.g., KIES, Monsanto), agencies
may have already decided to issue the required permit.  By defending
their permit review (i.e., trying to secure support for hazardous waste
regulatory procedures), these agencies are, either directly or indirectly
acting as proponents and attempting to overcome opposition to the
proposed facilities.

Once a facility becomes operational, the regulatory agency position
becomes more clearly one of supporting or seeking support for the
facilities.  The regulator's goal becomes that of ensuring that the
facility operator continues to operate within permit conditions.  When
operational problems arise, regulators are often in the position of
working with operators to seek solutions while opponents demand facility
closure (SCA/Model City, Resource Recovery Corp.).

Hazardous waste generators — In only one case studied in this project
(SCA/Wilsonville) did generators take active steps to generate support
for a commercial facility.  As the primary beneficiaries of disposal
facilities, generators have a clear self—interest in their development
and operation.  They are thus conspicuous by their absence as facility
proponents.

Tactics to Secure Support

The actors described above have used a wide variety of tactics to gain
support or to reduce opposition.  Most tactics have, been employed by
facility sponsors and have had mixed results.  The most significant
tactics follow.

Presentations at public meetings and hearings — With rare exceptions,.
public meetings or hearings were held during each of siting attempts
studied, either as a standard procedure in the state permit application
review or in response to public concern and opposition.
                                     "  17

-------
Thus presentations at  these meetings  by  facility  sponsors and  state
regulators were the most common attempt  to explain or to defend the
facility and  the application  and  thereby directly or indirectly to
reduce opposition.  In addition to presentations, comments and questions
from those in attendance were made at these meetings.   It should be
noted that these public meetings  and  hearings provided  for only the most
limited substantive discussion and primarily served as  forums  for
expounding positions for or against proposed of operating facilities.

Discussions between regulators, facility sponsors and local leaders —
These meetings were the second most frequently used tactic to
communicate with key individuals  at the  local level.  Because  these
meetings usually involved smaller numbers of individuals they were
significantly more likely to  generate substantive discussions between
facility opponents, regulators and proponents than were public meetings.

Public relations campaigns — In  a minority of cases facility  sponsors
developed public relations campaigns  to  provide additional information
to local communities.  In one case (Minnesota) this information stressed
the negative  aspects of improper  disposal while in most cases  (3M,
SCA/Model City, Ensco) the ability of the facility sponsor to dispose of
waste in a safe manner and the economic  value of  hazardous waste
generators or of materials recycled and  reclaimed at the facilities was
stressed.  Most such campaigns were surprisingly  ineffective.  In cases
where information on types of waste to be accepted and  the use of land
disposal technology was downplayed (SCA/Wilsonville), the campaigns were
later seen by opponents as outright deceit.  Effectiveness appears to be
based on an ability to discuss hazardous waste management positively and
to capitalize on the credibility  of the  facility  sponsor's past history,
and the facility's potential  economic contribution to the community
(3M).

Debates with  opponents — In  two  instances (IES,  SCA/Bordentown),
facility sponsors debated opponents during siting attempts to try to
provide more  information to the public and to refute the claims of
opponents.  These particular  debates  were either unable to sway
opponents or  added to opposition  by raising issues involving still more
potential risks or unanswerable questions.

Siting strategies — Several  strategies were used either to avoid or to
preempt public opposition.  Most  facility sponsors avoided publicity at
least in the earliest stages  of land acquisition and application
preparation.   The most extreme low-profile approach (Gulf Coast Waste
Disposal Authority) eschewed  involving the general public throughout the
siting attempt.  Similarly, a few sites in industrial areas (Gulf Coast.
Waste Disposal Authority,  Frontier Chemical Waste Processors,  Chemical
Resources) or at existing landfills (SCA/Bordentown)  were consciously
chosen on the assumption that these sites were more acceptable to the
public.   When the public is unaware of a siting attempt, they are
unlikely to oppose it.   Except for the cases cited immediately above,

-------
the general public eventually learned of the siting attempt.  The choice
of sites in industrial areas in most cases appeared to avoid or reduce
opposition.  The choice of other types of sites—at existing landfills
or in remote areas—did not in general avoid the public opposition.

Involving government in siting—Several facility sponsors (Gulf Coast
Waste Disposal Authority, IT Corp.) sought to involve local government
directly in developing proposals.  These actions were designed to
respond to local concerns and to enlist local support.  Similarly, a
number of facility sponsors (KIES, Bob's Home Service) worked in close
cooperation with state regulatory agencies for generally the same
purpose.  A related action taken by a regulatory agency was having local
elected officials review and approve a permit (SCA/Model City).  This
tactic was often successful in gaining the additional support of the
state agencies or local officials, but rarely had an effect on public
opposition.

Amending proposals/operations — In a significant minority of cases
proposals or operations were amended to address public concerns.
Specific examples include revising siting criteria (Minnesota), changing
access to facilities (Padre Juan), reducing hours of operation (Allied),
upgrading operations to reduce odors (KIES), and generally cleaning up
sites (SCA/Model City).  In almost every case these efforts failed to
reduce opposition because they were seen as too little and too late by
the public.  Indeed, most revisions were made only after sustained
opposition had developed.

Direct Incentives to local communities —  Various inducements have .been
discussed or offered during siting attempts — amenities such as
developing parks (Allied) or providing fire equipment (Wes-Con) and
•financial compensation to host communities (BSWD, SCA/Bordentown, SCA/
Wilsonville).  Similarly, facility operators have paid local costs
involved in monitoring activities (SCA/Model City, 3M).  For the same
reasons that revisions to proposals were not always well received, these
incentives were sometimes ineffective.

Exceptional regulatory actions — Regulatory agencies have taken some
exceptional actions to demonstrate their credibility and to assuage
opposition.  These include publicizing the restrictiveness of permits
(KIES), and promises by U.Si EPA to take action if regulations are
violated (SCA/Model City).  When agencies followed through on their
promises of tough regulation (KIES), public concern was reduced.  When
they did not follow through or when the public felt they did not
(SCA/Model City), opposition intensified because government was seen as
contributing to the local community's problem.

Establishing or utilizing local task forces — Public facility sponsors
have in two instances  (Padre Juan, BSWD) set up special task forces to
serve as contacts between local communities and facility sponsors during
siting processes.  For operating facilities, one state regulator
(SCA/Model City) has helped to form such a group to try to reduce
                                     19

-------
communications problems.  Similarly, one  facility operator  (Monsanto)
has worked with an existing Ipcal environmental commission  to address
local complaints, most of which  related to  odors.  In cases of operating
facilities these task forces appear to be helpful in reducing public
concerns and/or demonstrating a  willingness on the part of  regulators or
facility operators to address concerns.   When established during the
siting process, task forces have helped to  improve communications but
have also served to organize local opposition.

Use of technical experts — In addition to  using consultants in the
preparation of permit applications, facility sponsors (SCA/Model City,
Allied) have also used technical experts  to buttress their  proposals and
to refute claims of opponents.   Opponents,  however, have not normally
been persuaded by such technical arguments  and can usually  find experts
with the opposite view.

Enlist support of hazardous waste generators — Facility sponsors have
sought to gain the active support of those  industries that  would use
their facilities both during siting (Minnesota, IT Corp.) and after
operations began (Earthline).  Generators have not been eager-to defend
or to publicly support siting attempts.   When they have, they have not
tried to address the local community directly,

Appeal to governor — In one case (Allied), a facility sponsor appealed
to the state governor to intervene on its behalf in a siting
controversy.  The governor's support was  won, but opposition continued.

Legal tactics— In one case (Bob's Home  Service) a facility sponsor
entered into an out-of-court settlement to  reach a compromise with a
facility opponent which effectively reduced that opponent's concerns.

Good neighbor policy — Several  facility  operators have taken a wide
variety of steps designed to demonstrate  a  willingness to help the local
community.  Some of these steps  include free disposal service for
selected groups (Wes-Con, Bob's  Home Service), contributions to local
civic and charitable organizations (Wes-Con, SCA/Model City), the
preferential use of local businesses for  goods and services (KIES), the
opening of the facility for tours (Wes-Con, SCA/Model City).  This is
only a partial list.  Some facility operators have shown substantial
imagination in demonstrating their desire to be "good neighbors."  The
effectiveness of these efforts is dependent on the level of controversy
surrounding a facility.  When there are major substantive unresolved
issues, they overshadow these public relations efforts..  When issues are
largely resolved, these efforts  can significantly improve the operator's
standing in the community.                               ,   .

Issues Raised in Support of Facilities

While facility proponents have used numerous tactics to gain public
support, they have raised only a few major  issues in support of
facilities.  These issues necessarily focus on the need as opposed

-------
to the desirability of facilities and the reduction of risk as opposed
to the possibility of benefit.

Need for hazardous waste disposal facilities — The primary issue raised
by facility proponents has been the need for safe disposal sites.
Hazardous waste generators who sponsor facilities (Allied, Monsanto, 3M)
have been the most vocal in expressing their needs for their specific
sites and in linking their needs directly to the industrial facilities
they operate.  Commercial and public facility sponsors have also argued
the need for sites; however, they are necessarily less able to link this
need to specific local industries.  State regulators have also
consistently raised the issue of the need for disposal sites.
Regulators generally focus on the needs of the jurisidiction they serve
(i.e., state, region, nation) and the need for the jurisdiction to be
responsible for its own disposal problems.

Viability of specific sites or technologies — Facility sponsors have
often gone to great lengths to substantiate the viability of their
sites.  Most efforts focused on the impermeability of soils and the
protection of water supplies.  These arguments are also directly tied to
land disposal technology.  Where treatment and processing technologies
are to be employed, the environmental safety and desirability of these
technologies have been stressed.  Occasionally, the economic benefits
from reclaiming or recycling material have also been presented.

Economic and other benefits — Hazardous waste generators who sponsor
facilities have argued that without disposal options their industrial
plants might close and thus jobs in local communities would be lost.
This same argument has not been uniformly made by other facility
sponsors primarily because links between generators' jobs and local
communities are more tenuous or non-existent.  Some commercial facility,
sponsors (Starr, SCA/Model City, SCA/Wilsonville) have argued that the
facility itself will provide jobs to the local community.

In two cases (SCA/Model City, Frontier) the development of facilities
was considered a boost to an area's industry base either by expanding or
diversifying it.  (It should be noted that one of these facilities is a
treatment facility; the other was generally perceived by the public as a
treatment facility.)  The fact that industries that produce hazardous
waste provide all of us with benefits and that disposal facilities are
the necessary consequence of those benefits has occasionally been raised
by facility proponents.

Illegal and improper disposal — Various facility proponents have
contrasted proposed or operating disposal facilities with "midnight
dumping."  These proponents argue that facilities such as those surveyed
for this study are not only the necessary alternative to dumping but are
essential if such dumping is to be eliminated.
                                  21

-------
V.
FINDINGS AND CONCLUSIONS
Introduction/General Conclusions *

The promulgation of hazardous waste management regulations under RCRA is
imminent.  It is anticipated that these regulations will exacerbate the
problem of hazardous waste disposal site availability both because they
will dramatically increase the demand for proper disposal sites and
because they will result in the closing of a number of marginal sites.
This problem may well be compounded, since facility sponsors are finding
it increasingly difficult to site and operate hazardous waste management
facilities.  The principal reason for this is increased public
opposition.  This increase in public opposition can in turn be traced to
the national publicity given environmental problems, particularly to the
hazardous waste problem.  This publicity has focused almost exclusively
on the disastrous results of improper management of hazardous wastes.
The public is thereby unable or unwilling to distinguish between
patently improper sites for hazardous waste disposal such as Love Canal,
and properly managed disposal sites.

Understanding the problem in this case does not suggest an answer.  It
is unlikely, even if it were possible, that countervailing publicity
alone would succeed in reassuring the public.  It is obvious that public
opposition is a difficult problem to solve and one that will become more
so in the future, especially as efforts are made to identify and correct
the problems of abandoned sites.

The case studies suggest that certain actions or situations will
certainly give rise to public opposition.  For instance, if a facility
sponsor has a bad previous history as a facility operator, or if he
decides  to dispose of what are locally perceived as political wastes, he
will almost invariably face intense public opposition.  However, there
is no corresponding certain or simple solution to the problem of public
opposition to facilities, either to avoid public opposition or to
mitigate it once it has arisen.  Below are indicated, based on the
findings of the case studies, partial solutions to the problem in terms
of what  should and should not be done during siting and operation.  As
has frequently been stated elsewhere in this report, no single action or
set of actions could be recommended for all siting situations.

Public Opposition During Siting

The problems faced by a facility sponsor during a siting attempt are
somewhat different from those faced during operation.  An obvious
    Conclusions  with regard  to  government  roles  are  addressed below
    in Section VI.
                                  22.

-------
example of this diffefence is the likelihood that perceived operational
problems such as spills or the lack of them will probably be the
principal determinant of whether .the site faces public opposition once
operations have begun.  In addition, a different set of problems is   ;
faced by commercial sites than by generator-owned sites.  On-site
facilities in particular are less likely to face credibility problems
because the generator is known and respected, and they carry a built-in
economic rationale because of the jobs the generator provides*  Based on
the case study findings, overcoming public,opposition requires taking
specific actions or negotiating certain conditions and thereby
convincing the community that:         ,

       •"     Complete.information is available about the operation of
             the site and proposed waste streams,

       •     The public and local officials will be substantively
            . involved in the siting process,

       •     The'operator is a person or organization of lasting integ-
             rity,

       •     The risks of catastrophic or insidious dangers are slight,

       •     There are significant benefits to the local area to, offset
             the risks,,

       •     The site and its operation are not in conflict with other
             enterprises or existing activities in the area, nor are
             there any better and more feasible higher land uses for the
             site,   '                    , ,                  ,i,-..-

       •     The government has sufficient resources and expertise to
             judge independently the merits of site design and oper-
             ation,

       •     There a,re sufficient government regulations, and resources
             to guarantee safe operations,

       •     There are sufficient resources and government regulations
             to ensure that the facility will be properly maintained
  '          . after closure, and

       *     The technical merits of the selected site and facilrty are
             unquestioned.                                          ,

All of these conditions have not been met in any of the cases .studied.
It is much more likely that only a minority are met in.the average
siting attempt.                                        '

Probably the most important single factor in addressing public        .„'
opposition to siting is coordination and communication with the public \
and local officials.  This includes informing the public and

-------
local officials of the siting attempt and the nature of the'proposed
facility before a final decision is made on a specific site. , It also
includes responding to local concerns, in particular those about
possible hazards associated with the facility.

In the case of commercial facilities, industries which will use the
facility are potentially a very significant public by virtue of their
economic and political influence.  For whatever reason, in these case
studies they are conspicuous by their absence as facility proponents.

Under certain circumstances, such as when the site.is in a heavy
industrial area and not in the public view, a low-profile approach may
be warranted.  There is at least some evidence that opposition will not
arise in these cases, so that there is no need to alert the public and
thereby create a potential for opposition.        ,         .         .

The question of operator credibility will probably have been settled for
better or worse if the operator is a generator planning an on-site
facility or has operated hazardous waste facilities elsewhere.
Otherwise, little can be done to convince the local public of the
operator's credibility other than to conduct the siting attempt in an
open and receptive manner.

It is also unlikely that the public can be convinced, that the dangers of
a hazardous waste facility are slight, given national publicity.on the
subject.

Furthermore, hazardous waste management facilities are often perceived,
as bringing with them economic disbenefits, and do not, except for
on-site facilities, necessarily provide local economic benefits.
However, providing such benefits for purely public relations reasons has
often mitigated public opposition, although this is;not always perceived
as sufficient compensation for the risks and nuisances which are
expected to accompany such a facility.  Examples of such.benefits
include the payment of a tipping fee to the local government and
providing jobs and/or services to the local population.

Sites which do not conflict with surrounding land uses include those
located in clearly defined industrial areas and those in truly isolated
areas.  However, many sites which appear to facility sponsors to.be
remote or not in conflict with adjacent land uses are not perceived in
the same way by local residents. Most of the sites visitied which were
located in rural areas faced opposition for this very reason.  The four
sites visited which faced little or no opposition were all located in  >
industrial areas.  Other sites in industrial areas did face opposition,
however because local residents perceived more favorable uses for the
land.                     .         ;                           •

Local reaction  to the siting attempt will to some degree depend on the,
local perception of the state regulatory agency and the attitude the
agency takes.  Although state regulatory officials are ostensibly
neutral during  the siting process, in several cases studied in  this
                                    24

-------
project state officials were active proponents of the siting attempt.
Active support for siting attempts is not at all inconsistent with   •
stringent regulation.  -On the contrary, in some cases testimony by state
officials that the proposed facility has been subject to a stringent
review process was quite successful in mitigating public opposition.
However, if the credibility of the state regulatory agency is questioned
by the public, its support may compromise the project.

Currently, hazardous waste management site and facility regulations vary
from state to state.  However, it is anticipated that many of these
differences will be eliminated when RCRA establishes minimum regulatory
requirements.  Local perceptions of the way these regulations are
enforced will likely continue to differ.  In states which now give local
government a significant role in permitting sites, this too is not
likely to change.  While the perception of substantial local control
over hazardous waste facilities will ease public opposition, based on
this issue in particular, such control is likely to be exercised to veto
any proposed facilities.  Siting a new facility in such areas may well
be considerably more difficult.                                 '„•'"-'

The focus of this study has been on perceived technical viability of
sites as opposed to any objective attempt to determine that viability.
Experience has shown, however, that in cases where facilities face
sustained public opposition, the local public almost without fail has
been able to seize upon technical faults in the proposal and to use them
either before the state regulatory agency or in the courts to defeat the
siting attempt.  While technical perfection is obviously an unattainable
goal, egregious technical faults have been and are likely to be the
basis of successful opposition to siting attempts, particularly if the
credibility of a state regulatory agency is questioned.

Public Opposition During Operation

Many of the conclusions reached by this study with regard to facility
siting also carry through to facility operation.  In particular, if a
problem is not resolved or addressed during siting, it will very likely
come up during operation.

Experience shows that it is much more difficult for public opposition to
shut down an operating facility than to prevent a facility siting.  A
major reason for this is that, unless the facility is violating state
regulations in its operations, the state regulatory agency will probably
feel obliged to defend its regulatory process and thus the site.  This
implies that public opposition during operation, to be successful, must
have considerably more political and technical resources than would be
necessary to defeat a siting attempt.  Only if a locally granted permit
must be periodically renewed is this not necessarily true.

Facility operators contacted during this study also noted, however, that
these operations always proceed against a background of public distrust,
                                 25

-------
and that very small problems during operations could have very large
public relations ramifications.  This is true even with no history of
operational problems or opposition during siting.

Two primary concerns in avoiding public opposition during site operation
are maintaining communication with local officials and the public, and
avoiding operational problems that are apparent to the public.  A
practical way to maintain communications is to set up a grievance
procedure, so that residents and/or officials with a complaint about the
facility will be able to make this known to facility personnel and, if
possible, have it resolved.  In this way potential public relations
problems can be avoided.  Operational problems such as spills and odors
will, if not infrequent, be perceived as indications that the facility
is not properly run.

-------
VI.
GOVERNMENT INVOLVEMENT IN SITING FACILITIES
Based on the data collected during this project, a wide range of actions
that government has taken or might take to solve the hazardous waste
disposal problem can be defined.  Government  involvement can be at the
local, state, multi-state, and federal levels, and can range from review
of proposals to owning and operating sites.   Thus, at one extreme, local
governments are given no controls over siting and states review and
approve permit applications developed by private industry, which is
totally responsible for siting and developing facilities.  At the other
extreme, the federal government sites, constructs, owns and operates
facilities.

To date, this project has placed only secondary emphasis on what roles
government might play.  The data developed by this project, however,
suggest that states will have to play the pivotal government role in
siting.  There are three definite reasons for this:

       •     States now play the pivotal governmental role and intend to
             continue to do so.

       •     EPA intends for states to implement RCRA and has shown no
             desire to become directly involved in siting.

       *     States are the most logical level of government to play the
             lead role because federal agencies are in general too far
             removed from local problems to be able to respond
             effectively to them, and because local governments are
             unlikely to voluntarily accept facilities.

Given that states should play the leading governmental role in siting,
the results of this study indicate that they  should become arbiters of
the siting process.  State regulatory agencies should be seen as
knowledgeable neutral parties which can carefully and independently
judge the merits of facility proposals.  Because so many siting attempts
have become entangled in disputes, states may also have to serve as
negotiators between parties (i.e., facility sponsors and opponents) with
widely divergent interests.  States cannot ignore public concerns, but
must be able to respond to the range of issues raised by local
communities.  Scrutinizing proposed facilities clearly contributes to
better hazardous waste disposal practices.  Responding to public
concerns will not necessarily win public acceptance but can win public -
respect for the siting process.  Without this public respect the siting
process can become mired in political and legal battles over sites.
These can cost hundreds of thousands of dollars, delay siting for years,
and exacerbate already strained relationships between local residents,
the facility sponsor, and state regulators.

While the significance of the role of states  in siting is certain, this
project can only tentatively discuss the variety of roles that states

-------
 and  other levels  of  government might  assume.  An optional second phase
 to this  study would  examine  in detail these  potential roles.
 Government,  particularly at  the  state level,  is rapidly evolving new
 conceptions  of  its responsibility and authority in developing new
 hazardous waste disposal capacity.  The notoriety of abandoned sites and
 the  attendant widespread publicity has helped to spur major new
 initiatives  by  both  state  legislatures and state agencies.  The demand
 for  capacity is the  major  impetus behind these initiatives, but state
 actions  also reflect a  clear concern  with public opposition to siting :
 and  a desire to resolve problems that opposition causes.  A better
 understanding of  these  governmental initiatives is needed and government
 agencies  would  greatly  benefit from more knowledge of the actions of
 other agencies.   The second  phase of  this project could be a significant
 step in  examining these recent developments.

 The  following discussion highlights the major options that appear to be
 available to government at the state, multi-state, federal, and local
 levels.   This discussion should  serve as a starting point for a much
 more thorough examination  of  government involvement in siting.

 Options for  States

 States are the  level of government most deeply involved in the siting of
 hazardous  waste facilities.   This will continue to be true into the
 foreseeable  future.  The implementation of RCRA will provide continuity
 in state  programs.   However,  individual states have taken and will
 continue  to  take  different approaches to siting because the urgency of
 hazardous  wastes  problems varies substantially from state to state.  In
 the  future any  national hazardous waste program must recognize these
 variations and  must  be  able  to respond accordingly.

 Public participation in the  development of facilities (e.g., in the
 state review of permit  applications)  is largely the responsibility of
 states.   The question of how  to involve the public exists regardless of
 the  state's  siting approach.  In addition, the public often demands that
 it have a  voice in the  decision to develop a  facility.

As defined by the states, public participation appears to have three
 discrete  functions.  One, it  can serve to inform the public of
 government actions.  Two, it  can allow for technical input by the public
 into government decision-making.   Three, it can allow the public to
 provide substantive  input to  technical and non-technical aspects of
 government decision-making.   For almost all cases studied in this
 project public  participation  involved the first two functions only.  The
 third function, a substantive public  role, was not common.

The question of what role public participation should play in siting
hazardous waste facilities is not easily answered.   Even if a state has
 clearly defined the  function  of public participation, facility opponents
may demand greater involvement than the state has assumed the public
will have.  If opponents feel sufficiently frustrated by their lack of
                                  28

-------
involvement, they may turn to political leaders or to the courts.  On  .
the other hand, if given too large a substantive role, opponents.will
probably block all siting attempts.  If major local roles in siting were
to become widespread, this would very probably be disastrous for siting.

There appear to be five major options for states with respect to siting
facilities.  The two major variables which,define these options are the
degree of state involvement in siting and the role of private industry.
All of these options are currently being employed by states. . The five
options are:                   ,                         ,  ..  ".•.-•,     .

       •     State review of private siting attempts using  data provided
             by private industry.                             •'•',.•      ? ,

       •     State evaluation of private siting attempts based on data
             generated by themselves or independent third parties.

       *     State involvement in hazardous waste management planning.

       •     Joint state-private sector involvement in facility ,
             ownership and operation.          ,,-".-

       •     Total state control of facility ownership and.operation.

The majority of ;the states, visited in this project limited  their
involvement in siting to reviewing permit applications prepared by  •  ..', ,
facility sponsors.  For many of these states all data used  to determine
the viability of the site and the proposed facility were provided by the
facility sponsor.  The state decision to rely on.those data was usually
a matter ,of practicality.  State resources were limited and demands
placed on the state were great.  For facility opponents, state reliance
on the facility sponsor's data was a major problem.  Opponents were
.suspicious of the reliability of the data and ,of facility sponsor
willingness to present objectively data that would weaken the permit
application.  Thus-this option for state involvement in siting   •
inherently tended to engender public opposition.    ,             „

Other states developed their own data:when .evaluating permit       ,,   :
applications.  For exap.ple, some states conducted soil tests to,
determine permeability.  In another case state officials toured a  ;   . -
facility operated .in another state by the facility sponsor.  These
actions allowed them to judge independently the soundness of.permit
applications.  By demonstrating an ability to critically.evaluate the  ;
proposal, state regulatory agencies enhanced their credibility in the
eyes of the public.               ,.;

A third state approach to. siting is a logical extension of  independent
development of data. .A few states visited were directly involved in
planning for .facilities either on a site-specific basis or  on a more
general basis.  Typically, a state regulatory agency would  work closely
with a facility sponsor throughout the planning process in  areas .such as
determining the most suitable sites, developing engineering plans, and
                                     29

-------
establishing monitoring requirements.  Such actions tended to ensure
that the proposed facility met all genera:! and specific requirements set
by the state regulators.  They also served tp demonstrate to the public
the effectiveness of the agency and thus reduce public concerns.  A
related state role involved negotiating conflicts between facility
sponsors and opponents over specific site and facility plans and
attempting to reach compromises acceptable to both parties.  On a more
general level, state planning efforts have included statewide surveys to
determine the most hydrogeologically suitable areas for facilities.
More comprehensive planning efforts by states have included making
specific estimates of their needs for facilities, locating centers of
hazardous waste generation, developing siting criteria, and planning for
other aspects of hazardous waste management.  Such planning has
substantially improved the state's understanding of its problems and
served to enhance the credibility of state regulatory agencies.

A few states visited had joined with private industry to develop
facilities, either by acquiring sites or by proposing to operate
facilities.  The two major reasons for this joint public-private
development were: 1) an extension of other waste disposal activities
(e.g., industrial waste water treatment) conducted by the state; and 2)
a determination by the state that facility development by private
industry faced substantial, possibly insurmountable, obstacles.  In some
cases, state agencies had two particular advantages (not enjoyed by
private industry) in acquiring sites.  One was the preemption of local
zoning and the other was the power of eminent domain.  By becoming
directly involved in developing facilities, states faced essentially the.
same opposition as did private industry.  However, opponents appeared to
see state agencies as more credible than private facility sponsors,
because these agencies were perceived as being .concerned primarily with
environmental problems rather than with commercial interests.

Finally, a few states have decided to assume total control over facility
development, ownership, and operation.  This decision has apparently
been spurred by the absence of private facilities or the conviction that
private industry faced insurmountable obstacles in developing
facilities.  Another rationale for total state control is that the state
will exist longer than any individual private company.  Thus in the
event of post-closure problems, the state will be in a position to
respond quickly.  (This rationale has also been used to support state
ownership of facilities which are operated by private industry.)  As
this project has shown, total state control in no way avoids public
opposition.  It is not at all certain that states would have appreciably
more success in siting than private industry.

While the above options are presented as relatively discrete, in
practice most states combine aspects of the first three options (i.e.,
relying on facility sponsor's data, generating independent data, and
becoming involved in planning activities).  However, many state
                                   30

-------
regulatory officials felt that direct state involvement in facility
development was probable or inevitable.   Whether states will in fact
play a major direct role in facility development will in all likelihood
depend on whether the states perceive hazardous waste problems as
critical.

Options for Local Jurisdictions

Based on the findings of this project, there are two major options for
local government:

       •     Zoning and other regulatory controls.

       •     Facility development.

Local jurisdictions exercise regulatory control primarily through
zoning, but they may also have responsibilities for local solid waste
planning.  If these controls can hold veto power over site development,
then the primary role of local jurisdictions will be to block siting
attempts. Even when local controls are minimal, local governments have
substantially delayed siting attempts or frustrated facility operations.

Conversely, local  governments have also developed facilities.  Except
for the fact that  several California counties  own and operate
facilities, the prospects for local government playing any significant
role in  promoting  sites would appear to be minute.

Options  for Regional Government

At  least three multi-state  regional agencies have recently developed
hazardous waste  programs.   One of  these programs, "sponsored by the  New
England  Regional Commission, was  examined  for  this  project.   Based on
quite  limited  information on these regional agency  efforts, there appear
to  be  three roles  that  the  agencies could  play:

       •    Support to states.                             ,

       •    Public education and information  programs.

       •    Facility  development.

 Support  to  states  can  parallel  state  planning  efforts  in developing
 information on facility needs,  siting strategies, and  other areas  of
 hazardous  waste management.  Support  can also  encompass  coordinating
 individual  state efforts in order to minimize  interstate problems  and to
 maximize the  efforts of individual states.

 Regional agencies  can  also play a significant  role  in  disseminating'
 information and educating  the public.   To .the  extent that this can
    See Appendix B of this report.
                                   31

-------
 contribute to public confidence in facilities as a solution to hazardous
 waste disposal problems, regional agencies can help reduce opposition to
 siting.                                          ,

 While regional agencies have contemplated site acquisition or facility
 ownership and operation, this would not appear to be a likely
 possibility.  Based on the limited experience of the NERCOM program,
 states appear quite reluctant to relinquish their own authority and
 responsibilities to regional agencies.

 Options for U.S. EPA

 Based on EPA's current activities and the views of  regulatory officials
 and others interviewed during this project,  there are five major roles
 EPA can play which can influence the siting of facilities.

        o     Public information and education.

        o     Research and development.

        o     State program funding.

        o     Liability funding.

        o     Facility development.                                   '

 According to  many regulatory officials,  public information released  by
 EPA has  clearly  demonstrated that  hazardous waste disposal is a  problem
 that must be  solved.   Thus  the  public  is generally  aware of the  dangers
 of  improper disposal.   What is not generally understood or believed  is
 that there are any reliable solutions  to this  problem.  Thus EPA can"
 significantly reduce  general public anxiety by developing  information
 that shows that  the problem can  be solved.

 Directly related  to this  need for  positive information is  the perceived
 need for research on more effective hazardous  waste management
 technologies.  Facility proponents and opponents  stressed  the
 desirability  of technologies  that eliminated the  burial of  hazardous
 waste.   Many  felt that more research would lead to better  technical
 solutions  to  disposal problems.  In addition there are a large number  of
 non-technical  issues  (e.g.,  institutional arrangements and market
 structure) surrounding hazardous waste management which need to be
 addressed.

 RCRA provides substantial funds for state hazardous waste programs.
 This EPA funding  fills a clear need in many states for additional
 resources with which to regulate and monitor facilities and plan for
future state needs.

A specific role that EPA could assume is funding for long-term liability
of facilities.  State regulators considered long-term liability for
closed facilities a critically important issue.  Because liability costs

-------
could be substantial and problems could arise long after facility
operators had closed sites, some state regulators thought that
government must eventually assume liability for closed facilities.
Because state resources are limited, EPA was seen as a logical source of
liability funding.  This raises the difficult question of who should
ultimately pay for this liability funding.

Finally, a minority of those interviewed during this project felt EPA
should site, own, and operate facilities.  While most holding this view
were local officials and residents distrustful of state regulatory
agencies, some state regulatory officials felt that siting problems and
public opposition might grow so large that they would overwhelm state
agencies.  In that event, these state regulators saw federal facilities
as a last resort solution.
                                   33

-------

-------
 APPENDIX A




CASE STUDIES

-------

-------
                 MONSANTO INDUSTRIAL CHEMICALS COMPANY

                        BRIDGEPORT, NEW JERSEY
I.
INTRODUCTION
In the fall of 1978 Monsanto Industrial Chemicals Company began
operation of a secure landfill at its Delaware River Plant outside of
Bridgeport, New Jersey.  The facility -only accepts wastes generated at
that plant.  Operations began after almost three years of planning and
development for the facility by Monsanto, including lengthy negotiations
with New Jersey Department of Environmental Protection (NJDEP)
officials.

The facility was formally endorsed by local officials and the;local
environmental commission.  Although it did meet with some opposition and
raised concerns in the local community, this opposition was relatively
minor and was overshadowed by local endorsements.  Local acceptance was
based on an acknowledgement of Monsanto's disposal needs and Monsanto's
local image as a trustworthy and responsible company.

The most visible attempts to secure support for the facility were  those
required by the state  permit procedures, primarily the public hearing.
These were augmented by ongoing relationships which Monsanto had
established with local environmentalists and the community in general.
Conscious attempts  to  secure support  for the landill only partially
explain local acceptance which developed prior to the public hearing.
 II.
 BACKGROUND INFORMATION
 The  Monsanto  facility  occupies  six acres  within  the  bounds  of  the
 Delaware River Plant. ,  The; plant is bounded by the Delaware River,  U.S.
 130, and undeveloped land.   It, is relatively isolated,  only a  few
 residents are nearby,  and the facility is not visible from  U.S.  130,
 which passes  by the  plant.   The landfill  site is 150 feet from the  river
 and  1,000 feet from'Birch Creek, which drains into the Delaware River.
 The  soil underlying  the site has a permeability, according  to  Monsanto,
 of 2 X 10~7 cm/sec.   Site life is projected to be five years;  this
 estimate is subject  to variation according to the amount of dewatering
 that occurs to sludges disposed of at the facility.

 The facility itself  is a secure landfill with two clay liners  (18"  top
 liner, 12" bottom liner) separated by a layer of sand.   The facility ^
 accepts sludges from the plant's pollution control facilities  and solids
 which are by-products  of manufacturing processes and of pollution
 control equipment such as insoluble pitch, rocks from lime  .slaker
 operations, and contaminated filters.  Sludges are dewatered;  solids are
 buried; all wastes are generated on-site.  A collection system above the
 top liner allows any leachate to be reprocessed  by Monsanto's  waste-
 water treatment plant.  Between  the liners is a  leak detection system
                                  35

-------
 which checks for failure of the top liner,.  In addition, there are five
 monitoring wells on the plant grounds.  Samples are analyzed by an
 independent lab.

 Monsanto's closure and post-closure provisions for the landfill conform
 to proposed state regulations, which call for quarterly monitoring of
 the site over a three-year period, at the end of which the state reviews
 monitoring records and may reduce the frequency of monitoring to once a
 year if site records indicate that such an action would be justified.
 Primary responsibility for perpetual maintenance rests with Monsanto.
 All state regulations concerning funding mechanisms after site closure
 are unwritten pending U.S.  EPA action in this area.

 The secure landfill is operated as an adjunct to Monsanto's chemical
 manufacturing plant, located two miles from,Bridgeport.  The plant was
 established in 1961 and currently employs about 180 workers, including
 the senior environmental engineer responsible for waste disposal.   It is
 one of 200 plants and laboratories operated worldwide by the Monsanto
 Company.  Monsanto is one of the largest U.S.  chemical companies,  with
 1977 sales of $4.6 billion  and assets of $4.3 billion, according to the
 1978 Fortune 500 directory.

 Bridgeport (1978 estimated  population: 900) is an unincorporated town
 within Logan Township.   The town is in a relatively sparsely populated
 section of southern New Jersey,  approximately 30 miles south of
 Philadelphia.   Major employers in the area are chemical and petroleum
 companies  with a number of  facilities along the Delaware River.     ;
 Bridgeport is  also  the  site of a Rollins Environmental Services
 hazardous  waste disposal facility that has met with strong  local
 opposition.

 Ill-    HISTORY  OF FACILITY  DEVELOPMENT AND PUBLIC  RESPONSE

 The  State  of New Jersey preempts  local zoning  controls over  special
 waste  faciliti.es.   As a result,  there are  no  local  permits  or
 regulations applicable  to these  sites.   In developing  its facility,
 Monsanto needed only a  permit  from NJDEP's Solid Waste Administration
 (SWA),  which takes  the  responsibility  for  having permits reviewed by
 appropriate environmental (e.g., air  and water quality) and  other state
 agencies.

 Monsanto first  began planning  for  its  current  secure landfill in late
 1975 and early  1976.  The impetus  for  this  planning came from several
 sources.   The first was an  existing landfill at the Delaware River Plant
 was reaching capacity and was  not  designed  to  meet all of the plant's
 disposal needs, particularly for sludge  disposal.  At  the time, sludge
 was being  stored at  the plant's wastewater  treatment facility.
 Secondly,  off-site disposal facilities were not an effective means of
 solving  disposal problems.  There were no  facilities in New Jersey for
 sludge disposal.  The use of these facilities  was also considered too
costly.  Finally, without a long-term solution to its  disposal problem,
Monsanto would have to reduce maufacturing operations at the plant.
                                  36

-------
Thus the decision to develop an on-site facility met Monsanto1s primary
need for a sludge disposal facility and ensured continued plant
operations as well.  Monsanto would have added control over its waste
stream and would reduce disposal costs.  Risk involved in the
transporting of wastes off-site would be eliminated.  The decision to
develop a secure landfill allowing for the dewatering of sludge and the
burial of solids was dictated by the nature of the plant's wastes and
influenced by Monsanto's experience with various technologies employed
at both on-and off-site facilities.

Monsanto sought information from New Jersey's DEP relatively early in
the development stage.  During preliminary planning Monsanto had general
discussions with DEP to learn what state requirements and regulations
would apply to the facility and to inform DEP of Monsanto's needs for
such a facility.  Discussions and negotiations between Monsanto and'DEP
continued throughout the development period, including the period of
permit application review.

In the fall of 1976 Monsanto submittted a permit application  to SWA for
an 18-acre secure landfill to be located at its Delaware River Plant.,
It appears that this application encompassed the major objectives and
design concepts of the facility eventually developed by Monsanto.1  In
December of 1976, the consulting engineer retained  by Logan Township
reported to the township on the application.  His report indicated an
agreement with the concept proposed by Monsanto-and recommended that the
township be kept abreast of the application's progress.

SWA denied Monsanto's request for a permit in the winter or spring of
1977.  The 18-acre landfill would have had an expected life of 15 to 18
years.  In SWA's judgment this was too long a site  life for a special
waste facility, and  for  that reason it denied the application.

In response, Monsanto reworked  its application, reducing the  site size
to six acres, thereby reducing site life to about five years.  This
revised permit was submitted to  SWA in July of  1977.

Following standard procedures,  SWA notified local agencies and officials
in nearby jurisdications of the  permit application  within days of
receiving it.  Those notified  included the mayor of Bridgeport, the
Logan Township health officer,  the Logan Township Environmental
Committee, and  the Gloucester  County  planning agency.

After  this notificaton Monsanto  discussed plans for the  landfill with
local officials  including  the  Logan Township  Environmental  Commitee.
These  discussions  led to the  committee's endorsement  of  the  application.
At Monsanto's request,  the commission contacted SWA and'asked that  the
permit  be'reviewed as expeditiously as possible.
    The transfer of Monsanto personnel involved with this application
    and the passage of time limited data availability for the original
    permit.                                                 •
                                  37

-------
 In the months  that followed  the submission of  the  application,  SWA and
 Monsanto  entered  into  what in  effect  were  negotiations over the landfill
 design.   In reviewing  the application,  SWA's major concern was  over  the
 impermeability of the  landfill's  lining.   Monsanto originally proposed a
 single clay liner.   According  to  Monsanto's senior   environmental
 engineer, the  thickness  of the soil underneath the landfill site more
 than compensated  for the fact  that it was  twice as permeable as the
 state requirement of 1 X ICT^cm/sec.  xhe  state requested  a double
 liner system and  Monsanto responded with a proposal for  two 12-inch
 liners.   SWA then asked  that the  top  liner be  an artificial (Dupont
 hypalon)  liner.   Monsanto disagreed with this  request on the grounds
 that clay has  better long-term characteristics  than plastic liners and
 that general quality control is better  with clay liners.   The state   :
 agreed with Monsanto on  the condition that the  top liner thickness be
 increased to 18 inches.  Monsanto agreed and the final design
 incorporated an 18-inch  top liner and a 12-inch bottom liner.

 In December of 1977  the  Logan  Township  engineer reported to the  township
 on the second  Monsanto application.   The engineer's report indicated
 that the  only  major  change from the original application was the reduced
 size of the landfill.  For the second time, the engineer's report
 indicated general agreement with  the  preliminary design of Monsanto's
 landfill.   Monsanto's  proposed liner  material,  however, did not  conform
 with the engineer's  understanding of  SWA's requirements of other
 landifll  facilities.   Accordingly, he wrote SWA asking for a
 clarification  of  their requirements.

 In January  of  1978,  SWA  staff  met with  local elected  officials to
 discuss the permit application.   The  meeting was intended  as a
 preparation for the  upcoming public hearing and  was held as a part of
 SWA's  standard procedures in reviewing  permits.  The  same month SWA
 responded to the  township engineer's  request for information on state
 requirements for  liner materials.  That letter  from SWA stated in  turn
 that SWA did not  accept  clay as landfill liner material, that individual
 cases  determined  the acceptability of clay, that clay was acceptable for
most municipal and some  industrial waste facilities, and finally that
 clay was generally not acceptable for hazardous  waste landfills. ;

The  public  hearing on  Monsanto's  permit application was held in  ,
 Bridgeport  in  February of 1978.   SWA conducted the hearing and stated in
 opening remarks that it  was not an adversary proceeding and,  as a
result, would not involve questions and answers between the public and
 the  applicant.   Monsanto,.however, was  free to  respond to public comment
if it so desired.   A Monsanto engineering specialist in pollution
control,  who along with  the plant manager  represented the company,
explained that the landfill was needed if manufacturing were  to continue
and  that off-site disposal facilities were not available in the area.
He also described the  site,  wastes to be handled, facility design and
operation, and provisions for handling  leachate.
                                 38

-------
Public comments followed from local officials and private citizens.
Those making comments expressed positions ranging from total opposition
to full support.  In general, most comments appeared to 'indicate at
least general support for Monsanto and/or the proposed landfill.  Most
questioners sought additional information about the facility, particu-
larly contingency plans in the case of accidents and post-closure
provisions.  Monsanto provided responses to all comments either
providing additional information about the facility or indicating
Monsanto1s existing and future commitments to the Bridgeport plans and
to Logan Township in general.  The comments made during the public
hearing included those from three representatives of public bodies.

The Logan Township Environmental Committee (now Commission) had earlier
formally endorsed Monsanto's application and this endorsement was
restated during the public hearing.  The Commission is an agency of the
township, chartered by the township.  The seven commission members are
appointed by township elected officials and provided with a small annual
budget.  The commission reviews matters of consequence to the environ-
ment and advises the township on these matters.  Informal procedures
have also been established with area industries whereby a commission
member investigates environmental complaints (e.g., odors).  It was
formed in 1974 partly as an outgrowth of an earlier private group of
area environmentalists.  Although commission members had some major  '
concerns about the facility (e.g., proximity to the river, contamination
of water supplies, operating hours), six of the seven members voted in
support of the facility.  The quality of facility design and provisions
for; monitoring and leachate collection were the most immediate reasons
for this decision.  Equally important, according to a commission member,
was the impression that Monsanto, had anticipated many concerns and dealt
with them responsibly.  She indicated that commission members employed
at area petrochemical plants were also sympathetic to Monsanto's needs
for a disposal facility.  .                       ,

The township engineer stated at the hearing that the township was not
opposed to Monsanto1s application.  He referred to the two reports
previously prepared for the township which had agreed in concept with
the facility design.  His only question was in reference to SWA's
position on clay as a liner material and the contradictory explanation
SWA had given the township in January of 1978.  At the public hearing
SWA agreed that the earlier explanation was confusing and that a
clarification would be made.  As of this writing, the town engineer had
heard nothing.

The only substantial opposition to the Monsanto permit voiced at, the
public hearing came from the Gloucester County Environmental Health
Coordinator.  She opposed the facility on the following grounds: 1) its
proximity to the Delaware River (150 feet) and to Birch Creek (1,000
feet); 2) the subsidence potential of the marsh and made land of the "
area potentially leading to ruptured liners and to water supply
contamination; 3) the high water table at the site as indicated by test
bores; and 4) the fact that Monsanto's existing landfill was listed as a
                                  3S

-------
pollutant by  the area's  Section  208 water quality management plan.   In
addition, she asked what action  would be taken if one or both liners
ruptured and what monitoring provisions were established.  Monsanto
responded with an explanation of how ruptures in the liner would be
repaired and procedures  for quarterly monitoring with testing by
independent labs.  Monsanto also indicated that data on which she had
based some concerns was  of dubious value as Monsanto's data refuted her
contentions on the depth of the  water table.  Monsanto also suggested
that the 208 plan had been based in part on older data.1

The February, 1978 public hearing was the last major instance of public
response to the permit application.  The major subsequent actions
involved state review of the permit and Monsanto's construction of the
facility.  By May, SWA had completed most of its work on the application
and told Monsanto formal approval would be given in June.  According to
SWA this allowed Monsanto to begin site preparations and reduce the pos-
sibility tha plant operations would be disrupted by lack of the facil-
ity.  In June, SWA formally approved the facility and construction con-
tinued throughout the summer.  In October, 1978 Monsanto began disposal
operations at the facility.

Since operations began in October local residents have made periodic
complaints about odors from the  facility.  These complaints have usually
been made to the Logan Township  Environmental Commission which has es-
tablished grievance procedures with Monsanto as well as other area
industries.  One commission member has been responsible for contacting
Monsanto and inspecting  the landfill to determine whether the odors
originated there.  She indicated that odors have been and will continue
to be a concern.  However, her inspections have shown that complaints
about Monsanto are not always justified and odors can be traced to
several other plants in  the area.

Monsanto's landfill should reach capacity by 1983.  Site life will
depend in part on the extent to which sludge is dewatered.  When
capacity is reached, the facility will be covered and post-closure
monitoring will begin as described earlier in this report.

IV.    CHRONOLOGY OF EVENTS

Late 1975, early 1976 — Monsanto begins planning for HWMF.

Fall 1976 — Monsanto submits application to NJDEP for 18-acre secure
             landfill.
   When interviewed by Centaur, an SWA official said that older
   landfills such as the Monsanto landfill cited by the 208 plan were
   assumed to have leachate plumes.  These landfills predate the
   creation of SWA and the implementation of state landfill regulations
   in 1971.

-------
December, 1976 — Logan Township engineer's report favorably reviews
                  permit application for Township.

Winter, spring, 1977 — NJDEP denies Monsanto permit on grounds that
                        facility life projection too long.

July, 1977 — Monsanto submits permit application for six-acre secure
              landfill with reduced site life.  NJDEP, following
              standard procedures, notifies local officials and agencies
              of permit application.

Summer 1977 — Monsanto discusses proposal with local officials and
               agencies, receives endorsement of Logan Township
               Environmental Committee.

Summer and fall 1977 — NJDEP and Monsanto negotiate site design and
                        engineering.

December, 1977 — Logan Township engineer's report again favorably
                  reviews permit application, questions clay as liner
                  material.

January, 1978 — NJDEP responds to Township on clay liners and,
                 following standard procedures, meets with local
                 officials prior to pubic hearing.

February, 1978 — NJDEP holds public hearing in Bridgeport.  Monsanto
                  and NJDEP make presentations and respond to questions,
                  concerns, and some opposition from those in
                  attendance.

May, 1978 — NJDEP informs Monsanto that permit will be approved and
             that site preparation may begin.

June, 1978 — NJDEP approves permit.

October, 1978 — Monsanto begins operations at secure landfill.

1983— Projected closure of facility when capacity reached; Monsanto
        begins quarterly monitoring.

1986 -— NJDEP and Monsanto review monitoring data, possibly reduce
        frequency of monitoring.
V.
ATTEMPTS TO SECURE SUPPORT
Direct attempts  to  secure  support for Monsanto's landfill were few.  The
major efforts were:

       o     Early  discussions between Monsanto and interested officials
             and agencies  in Logan Township.
                                  41

-------
VI.
o     The public hearing held in Bridgeport by SWA in February,
      1978.                                                    ;

o     The establishment of procedures to allow the Logan Township
      Environmental Commission to investigate complaints con-
      cerning facility operations.

SUMMARY EVALUATION
The efforts outlined above were almost certainly necessary but not suf-
ficient for achieving public acceptance of Monsanto's landfill.
Monsanto's discussions with local leaders clearly led to either
statements of support or of non-opposition.  The company was able to
convince key individuals both of the need for the facility and the    :
adequacy of its design.  Monsanto's ability to work with local
environmentalists and establish procedures to deal with complaints
reinforced the company's position as a responsible corporate citizen of
Logan Township.  These two efforts indicated that the company and the
community could work together.  This cooperative attitude reflects the
more basic condition that Monsanto was known and respected by local
leaders prior to submitting the application.

The public hearing had little if any impact on public acceptance.  Both
the township and the environmental committee had earlier decided to
support Monsanto's plan.  The public hearing then became a forum for
pre-determined positions.  It had extremely limited objectives with
respect to either substantively examining the permit application or
addressing any issues raised.  It is noteworthy that while Monsanto
willingly responded to questions and comments, the company did so at its
pleasure.   SWA specifically stated that this was not required.  In
effect the public hearing was an administrative ritual.

A number of issues and concerns were raised by the public during the
siting process.  These are outlined below.  Excluded are specific issues
raised by SWA in reviewing Monsanto's permit application because these
were not part of the public response.  Issues raised by the public
generally encompassed those raised by SWA.

Site Suitability — The proximity of the site to Birch Creek and the
Delaware River and the instability of the area's soil were considered to
be major disadvantages of the site.  Both raised concerns over
contamination of water supplies by leachate from the site.

Facility Operations — Odors from the facility have been a continuing
concern.  Linked to this are concerns over the facility's operating
schedule (i.e., 24 hours daily).

Contingency Plans — Because any ruptures of the clay liners could
result in contamination of water supplies, Monsanto's procedures for
detecting leaks in liners and for repairing the liner were of concern.
                                  42

-------
Long-Teria Maintenance —- Concerns over long-term maintenance  focused  On
the specifics of site monitoring for leachate as well as on Monsanto's
general commitment to be responsible for any problems that might arise
after the facility was closed.

The.concerns raised by local public officials and private citizens never
became major points of contention between  those persons and Monsanto.
No major organized opposition arose to Monsanto's plans for the
landfill.5  The consensus among those interviewed was that Monsanto's
stature in the community obviated the development of opposition.
Monsanto has been in Bridgeport almost 20  years, provides a substantial
number of jobs, has the confidence of community leaders, and  was
responsive to community concerns.  Monsanto makes chemicals and southern
New Jersey is replete with chemical and similar manufacturing plants.
These industries are economically important to the area and area
residents are familiar with and sympathetic to these industries.  These
conditions were the most significant reasons for the successful siting
of Monsanto's landfill.  Equally important, Monsanto's stature in the
community appears to have been established well before the permit
application was submitted to SWA.                                ..;/

Because of Monsanto's credibility,'SWA's role in the siting process ap—
.pears to have had little impact ,from the point of view of local of-
ficials.  SWA's most visible role was conducting the public hearing
which allowed comments to be entered into  the public record.  Because
most if not all local parties had determined their positions  by the time
of this hearing, its value in generating public acceptance was quite
limited.  SWA's negotiations with Monsanto over facility design
contributed-to the perception that Monsanto had anticipated public con-
cerns and designed the facility accordingly. • SWA's role in these nego-
tiations, however, was generally not acknowledged by local officials.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE  '•'•  '      :     -

Concerns over Monsanto's proposal for the  secure landfill developed as a
result of the following.                            •'..-.*•'

       o     Early notification by SWA of  local officials and agencies
             of the permit application and early discussions  between
             Monsanto and local agencies provided preliminary informa-
             tion on the proposed facility.              •"'•-• •---.''

       o     Reviews of that information raised concerns among some
     •        local agencies as to the environmental damage which might ,
             result'from the facility.        ,

The general public acceptance of the proposed landfill can be attributed
to the following factors.                                      :

       o     Monsanto's credibility in the eyes of the community and  the
             effective rapport between them prior to Monsanto's
             submitting the permit application.
                                    43

-------
        o     Early discussions between Monsanto and local leaders,  many
              of whom became convinced of Monsanto's need for the facil-
              ity and of the care taken in the design and operation of
              the facility to protect against damage to the environment.

        o     The reports by the township engineer who found no essential
              reason for the township to oppose the facility.

        o     The limited impact,  if any, of the facility in terms of
              visibility, traffic,  and (at least from Monsanto's perspec-
              tive) the generation of new odors in the area.

        o     The fact that.the facility serves Monsanto's needs and is
              not a commercial facility,  which means that wastes are
              known and unchanging  in terms of types and volumes.

        o     The clearly perceived link between hazardous waste disposal
              and jobs provided by  a hazardous waste generator.

VIII.   RETROSPECTIVE VIEWS

In retrospect,  only one criticism  of the siting process  for  Monsanto's
landfill was  raised.   From the local perspective there was no guarantee
that any local  party,  public or private, could have a substantive impact
on the  siting process.   Because the state preempts local controls,  the
community has no  meaningful voice.   As  indicated earlier,  the public
hearing requirement places no demands on either the state or the
applicant to  respond to issues.  Because of  this,  it  has the potential
of underscoring the powerlessness  of the local community thereby  de-
creasing, not increasing,  public acceptance.

Lack of a meaningful local role did not  become an issue  because Monsanto
was seen as responsive and responsible.   Indeed,  Monsanto feels that to
meet local concerns  it  has in some  respects  overdesigned its land-
fill.
IX.
GENERAL COMMENTS
Local of.f:L<".Lais also commented on siting issues in more general terms.
The need for meaningful local input into siting decisions was
emphasized.  Monetary compensation to host communities as an inducement
drew mixed reactions; it was seen as a "payoff" in the pejorative sense
but also as a strong incentive for public acceptance if enough money was
given to a community.  The added costs of compensation for industry were
seen as potentially driving industry out of an area requiring
compensation.  The feasibility of using arbitration, negotiation, or
mediation to settle siting disputes was considered questionable because
of the lack of informed and disinterested parties.  The use of panels of
experts (e.g., in the areas of law, medicine, chemistry) was seen as an
alternative to individual dispute settlers,,   Comments on governmental
                                   44

-------
roles focused on the need for unannounced independent monitoring of
sites "to keep industry honest."  State resources to do this were seen
as extremely limited,....           „                      •

A representative of Monsanto also stressed the need of the state or EPA
to monitor sites.  Government should also provide the public with more
information on hazardous wastes and disposal risks to reduce misinfor-
mation and allay unfounded fears.  Compensation was seen as a
conceivable inducement to some community members but not to those
totally opposed to disposal sites.  Arbitration and other techniques to
resolve conflicts were seen as effective in the case of technical
conflicts (e.g., between industry and regulators).  When strong
opposition arose to a site such  techniques could, however, alter site
design and operation in a way that reduced the total integrity of the
facility.  States views on siting and potential governmental involvement
are discussed under state program descriptions elsewhere in this report.

-------
                FRONTIER CHEMICAL WASTE  PROCESSORS, INC.

                        NIAGARA FALLS, NEW YORK
I.
INTRODUCTION
Since the fall of 1974 Frontier Chemical Waste Processors has operated a
hazardous waste treatment facility in Niagara Falls, New York.  This
facility replaced another Frontier facility located in Pendleton, New
York, ten miles east of  the Niagara Falls.site.  The Pendleton site
began operations, in 1958 and by late 1974 had stopped accepting almost
all hazardous wastes.  Both facilities were designed to process liquid
waste but the Niagara Falls site, unlike its predecessor, has no on-site
disposal capacity.  Treated liquid effluents are discharged into the
city's sewer system while solid residues are buried at area hazardous ;
waste landfills.

The Pendleton site was closed following a substantial amount of public
opposition arising from concerns over facility operations.  The move to
Niagara Falls, however, led to no opposition and attracted little public
attention.  What little attention the new facility did attract appears
to have been favorable.  Frontier has refrained from publicizing its
Niagara Falls facility.

(Although the original Frontier facilty was not intended to be the
subject of this case study, some discussion of that facility is
included.  Problems with that original facility caused Frontier to seek
its current site.  The contrast between the public response to the
facilities sheds some additional light on the reasons why Frontier has,
subsequently been able to. avoid similar problems.)
II.
BACKGROUND INFORMATION
Frontier's facility is located in an industrial area of Niagara Falls.
The seven-acre site was formerly occupied by a chemical manufacturing
commpany which maintains ownership of the land and leases the site.to
Frontier.  A Union Carbide chemical plant is adjacent to the site on two
sides and undeveloped land surrounds the other two sides.  The closest
non-industrial development is a residential area about one-quarter mile
west of the facility.

The site has a number of locational advantages.  An interchange of 1-190
is one-half mile away and the route to that interchange passes almost
entirely through industrial development.  The site is served by a rail
spur.  It also is served by the Niagara Falls sewer system as well as
other major utiJLities.

The majority of materials handled by Frontier are aqueous wastes
contaminated with organics.  Treatment involves pH adjustment,
oxidation, the precipitation of solids, and other procedures.  The
                                 46

-------
effluent from this process is discharged into the city sewer system.
Frontier monitors all liquid effluent to ensure that it stays within the
limits prescribed by Frontier's discharge permit.  In addition to the
treatment of aqueous waste, Frontier recovers and reclaims materials
such as waste oils and solvents; it also serves as a broker for wastes
that it cannot handle at its facility.  Storage of liquid wastes is
limited by site size and available facilities.  No long-term storage
capacity exists and treatment procedures have been specifically designed
to expedite processing and minimize storage needs.  No landfilling
occurs on-site; all solid residues are contracted out to hazardous waste
landfills permitted by the New York Department of Environmental
Conservation (DEC).  Frontier generates an estimated 50 tons of solid
residual monthly.

Frontier was incorporated in the 1950s by two buffalo area lawyers and
an individual who described himself as a practical chemist.  A 1960
Buffalo Courier Express article described the company founders as being
motivated by general concern with improper or inappropriate disposal of
industrial wastes and a conviction that the procedures that they had
developed represented a major innovation in disposal of liquid wastes.
In its 20 years of operation Frontier has concentrated on upgrading its
treatment procedures.  It has also branched out into hauling.  Total
employment is approximately 70 workers.  Although it owns the Pendleton
site, the Niagara Falls facility is Frontier's only operating facility.

Frontier has always concentrated on providing services to generators in
western New York and these firms constitute the bulk of the firm's
market area today.  As indicated, Frontier handles only liquid wastes,
the majority of which are aqueous wastes.  While a relatively broad
range of such wastes is accepted, the following are excluded:
radioactive wastes, explosives, carcinogens, highly toxic pesticides and
herbicides, and PCBs.

Niagara Falls is located within Niagara County (1967 estimated
population 240,000) and within 15 miles of. Buffalo.  While Niagara Falls,
has been linked historically to the beauty of American and Horseshoe
Falls and to the attendant tourist industry, the city is a major
manufacturing center'of chemicals, electrical machinery, and paper
products.  Together with Buffalo, the entire metropolitan area is the
second largest in New York state.  It is the major trade, service,
financial, cultural and transportation center for western New York and
southeastern Ontario.

In recent years Niagara Falls has received national attention because of
events surrounding Love Canal and other dumping sites once used by the
Hooker Chemical Company.   On a regional level opposition has arisen to
two operating hazardous waste landfills, both of which are permitted by
DEC.  Opposition has also arisen to a storage facility in Niagara County
which contains the world's largest concentration of radium and which is
reported to be leaking radiation.  In March of 1979 DEC released a draft
report listing 36 dumping sites (one active, 35 inactive) in Erie and
                                   47

-------
Niagara Counties with substantial amounts of hazardous wastes and an
additional 116 sites (47 active, 69 inactive) which might have
significant amounts of hazardous wastes.  In the past three years,
hundreds of articles on specific area sites and hazardous waste problems
in general have appeared in area papers.  More than any other area of
the country, Niagara Falls has had problems of and issues surrounding
hazardous waste disposal emblazoned on the public consciousness.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

When Frontier began operations at its Niagara Falls facility, the two ap-
plicable regulatory requirements were local zoning and a state sewer
discharge permit.  The site was already zoned industrial and Frontier
inherited the SPDES (state pollution discharge elimination system)
permit of the chemical plant which had been operating at the site.  In
1977 revisions to state solid waste regulations required Frontier to
submit an application to DEC for an operating permit by February of
1979. That application was submitted to DEC, which had 90 days to review
it and make a decision.  A public hearing on the application is not
required, but at DEC's discretion one may be held if public response is
significant.  A DEC official indicated that Frontier's application had
attracted no attention and would likely not be the subject of a public
hearing. He also indicated that, barring the unlikely possibility that
data submitted by Frontier are inaccurate, DEC will issue the operating
permit.

Frontier's first facility began operations in 1958 in the town of Pen-
dleton, New York.  Operations included treatment of liquid wastes to
reduce their hazardousness and incineration of flammable wastes.  The
site included a former clay quarry covering 20 acres which Frontier used
as a lagoon for the storage of treated effluents.  The surrounding area
is rural in character but did include scattered residences.

From relatively early in its operating history this facility generated
some local opposition because of smoke coming from the incinerator.
Concerns over smoke, noise, truck traffic, and odors sustained local
dissatisfaction with Frontier throughout the 1960s and early 1970s.  In
June of 1973 seven drums of waste exploded a few hours after being
delivered to the site.  As a result about 100 residents were evacuated
from an area surrounding the site for a period of 45 minutes.  While no
one was harmed by the explosion and the company delivering the waste to
Frontier was reportedly at fault, the explosion did little to assuage
local concern over the facility.

In the summer of 1973, Frontier decided to expand its operations and
attempted to acquire additional land adjacent to the Pendelton site.
According to Frontier's president, the original local zoning for the
site had been changed in 1963 from industrial to non-conforming     :
residential use.  Frontier belatedly learned of the zoning change in
1973 when planning of the expansion began.  As a result of the zoning
change any expansion would have required a variance from the town zoning
regulations. , Accordingly, Frontier went to several town board meetings,
                                48

-------
but was unsuccessful in persuading town officials to grant the needed
variance.  Subsequent efforts to get the variance from the zoning board
of appeals were similarly unsuccessful.  Frontier considered but
rejected legal actions to acquire the variance on the grounds that such
actions would produce more harm than good.  By August, 1973 the town's
opposition had escalated from concern over expansion to attempts to
restrict the operation of the existing facility.  As reported by the
Niagara Falls Gazette, the town attorney advised Frontier that not only
would expansion not be allowed but that Frontier would have to close
lagoons it was then using.

Faced with few prospects of favorably influencing the decisions of lor.al
officials, Frontier in early 1974 attempted to improve the operating
facility in lieu of expanding.  It was hoped that by upgrading equipment
and procedures the company could increase handling capacity but continue
to operate within the bounds of the original site.  Not entirely
convinced that their efforts would be successful, Frontier also began to
consider acquiring a new site outside of the Pendleton area.

In the spring of 1974 Frontier began to investigate other sites.   It
first looked at the Niagara Falls site in April or May.  The site
offered a number of advantages.  Because it had been operating as a
chemical plant, many of the site's existing structures and equipment
could be adapted for waste treatment and processing.  The site provided
a discharge into the city sewer system.  Because the city's sewage plant
would provide physical-chemical treatment, Frontier's discharge permit
did not need to meet the more stringent requirements of discharging into
a biological treatment system or directly into a water body.  The site
had been used for manufacturing chemicals for 60 years and was in an
industrial area; Frontier's operations would then conform to adjacent
uses, be relatively inconspicuous and be consistent with previous
activities at the site.  Similarly, the site was zoned for industrial
use and no zoning changes were required before Frontier could operate.
While not considered essential, the proximity of the Niagara Falls site
to the Pendleton facility eased the move to the new site and had little
impact on the market served by Frontier.   The only major disadvantage of
the site was the lack of storage capacity and the inability to dispose
of treated residuals on-site.

The site met Frontier's needs and the company sought to purchase it from
the chemical company.  A sale could not be consummated and Frontier
arranged to lease the site.  .The move to the new site began in September
of 1974 and by late fall operations began.

The transition to the Niagara Falls site did not bring a complete end
either to operations at the Pendleton site or attempts by officials to
restrict those operations.  By December of 1974, DEC and the Niagara
County Health Department (NCHD) ordered a stop to all discharges into
Frontier's lagoon at Pendleton.  The only exception would be for
colorless and odorless liquids; all handling of materials at the site :
stopped in 1977.  Frontier's major concern since that date has been to
                                   48

-------
maintain the integrity of the lagoon as a storage facility so that
leakages are prevented.

The start-up of operations at the Niagara Falls facility did not  .  .
stimulate any vocal response from area residents or the general public.
Frontier's operation was within the bounds of then applicable permits
and regulations.  There was no need to apply for changes in regulations
and thereby involve local officials and possibly the general public in
the siting process.  One indication of the reception that Frontier was
given was an editorial in a February 1975 edition of the Niagara
Gazette.  Entitled "Welcome Frontier" the editorial greeted Frontier's
arrival in the city because as a small firm it added diversity to a
local economy dominated by large firms.  It specifically praised
Frontier's reprocessing of industrial waste, noting, that such treatment
had a "...bright future in an economy where pollution and waste of
resources are not tolerated as they once were."  Although the editorial
also expressed some reservations because of odor complaints made against
the Pendleton facility, overall it was favorable to the new facility.  A
county health officer responsible for monitoring Frontier noted during
the site visit that the nature of Frontier's operations obviated public
opposition.  As a treatment facility Frontier does not require
large-scale land disposal of wastes.  The relatively small volumes of
solid residuals are land disposed by other firms.  Thus, in the health
officer's opinion, Frontier has not used the disposal technique most
objectionable to the public.

Since the start of operations Frontier has constantly upgraded its
treatment procedures.  This continues the firm's long-standing practice
of developing improved techniques.  A major incentive for these
improvements is the fact that Frontier's SPDES permit places inflexible
limits on specific pollutants it may discharge.  Consequently, an
increase in volume of wastes processed must be balanced by reductions in
pollutants per unit of discharge.  Frontier has also studiously avoided
publicizing its operation or in other ways providing information to the
public.

In response to revised state regulations, Frontier submitted to DEC an
application to operate its facility.  The application was submitted in
February, 1979, and according to Frontier's president will subsume all
applicable regulatory permits other than zoning.  DEC has 90 days to re-
view the permit, to approve or deny it, and may at its discretion hold
public meetings on the application.  A DEC official indicated that
Frontier's application was virtually certain to gain approval.
IV.
CHRONOLOGY OF EVENTS
1958 -- Frontier begins operations at Pendleton site.

1960 through 1975 — Opposition to site develops and continues as a
                     result of operational problems.

June, 1973 — Explosion at Pendleton site causes 45-minute evacuation.of
              surrounding area.
                                 50

-------
Summer,  1973  — Frontier  unsuccessfully seeks  local approval for:ex-  :
                panslon of site  to  enlarge  facility operations.  ,

August,  1973•'•*•- Town of Pendleton announces its  intention to .close
      "* '         lagoons at the site.         ,             •     ,

Early  1974  	Frontier attempts  to  upgrade  existing operations at Pen-
              dleton site.                  ,                  ;

Spring/Summer, 1974 —Frontier  seeks  replacement  sites,  determines  that
                       Niagara Falls site meets  needs,  and arranges
                       lease of  that site.

Fall,  1974  — Frontier moves to  Niagara Falls  site and  begins  oper-    . '
              ations.                                -'.'•  ''

December, 1974 — DEC and NCHD prohibit Frontier from accepting  all  '
                  wastes, except for odorless  and  colorless  wastes,  at
                  Pendleton site.

February, 1975 — Generally favorable  Niagara  Gazette editorial
          ,   ,     welcomes Frontier,to Niagara Falls.

1977— All acceptance of wastes at Pendleton  site stopped.

February, 1979 — Frontier submits application for operational ;permit
                  for Niagara Falls facility to  DEC.         'V

May, 1979 — Deadline for DEC action on Frontier permit application.   ..-'

V.     ATTEMPTS TO SECURE SUPPORT   -..:;.-'     '         •-'    ,

Frontier made no attempts to provide public information about  its
Niagara Falls facility to potentially  interested parties  nor was there
ever any need or occasion to respond to  publicly raised issues or con-
cerns .           '          ..                           ,

VI.    SUMMARY EVALUATION        .                          •'.    ,        .:

Frontier was able to site its Niagara  Falls facility without generating'
public concern.  This experience, however,  should  not suggest  that such
non-concern was inevitable.   The pubic reaction  to  Frontier's Pendleton
site is ample witness to  the possibility that  a  hazardous  waste
treatment facility is not inherently innocuous.  On the other hand,  the
above-cited editorial and comments from state, county,  and Frontier
officials indicate that the treatment  of hazardous waste,  as opposed to
burial, is publicly perceived as an acceptable and desirable technology.
The public apparently perceives Frontier's  Niagara  Falls  facility as
generating not only lower environmental risks  but  also  economic benefit
by virtue, of its capacity to  reclaim and recover valuable  materials.
This perception is in marked contrast  to public  perceptions, of hazardous
waste landfills visited during this project.  . .                    ;    . •

-------
The characteristics of the two Frontier facilities differ greatly,
contrast as do the operations of the facilities at those sites.  Those
contrasts suggest causes for the non-response to Frontier's Niagara
Falls facility.  The Pendleton facility is at odds with its immediate
environment.  Frontier operated an industrial facility in a semi-rural,
historically non-industrial area.  The Niagara Falls site is in an
urban, industrial area and the site had been used for decades as a
chemical plant.  Frontier's move to the site did not inject an alien use
into that environment, but in a real sense served to perpetuate its
historic use.  Because Frontier's Niagara Falls site, unlike its
Pendleton site, precludes the use of large holding lagoons, it is
literally and figuratively less visible to the public.  Finally,
Frontier's use of other firms' landfills for its non-liquid residuals
can be seen as an exportation of potential public concerns.

It should not be assumed that Frontier's experience is so anomalous that
it has no bearing on future sitings.  Sites within industrial areas and
unused but adaptable industrial facilities are not unusual.  The ap-
parent lack of significant public interest in Frontier's Niagara Falls
operation suggests its neutral image both as a site and a facility.

There have been no public concerns or issues raised with respect to the
Niagara Falls site.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Acceptance is a less accurate term in this situation than public
non-opposition.  The factors contributing to this "non-opposition"
follow.

       o     Frontier's adaptive re-use of a former chemical plant which
             had access to the city sewer system.

       o     The lack of need to receive new regulatory approval to be-
             gin operations, thereby minimizing contacts between
             Frontier and public officials or the general public.

       o     Public comment which saw Frontier's benefits substantially
             outweighing risks.

       o     Frontier's "low-profile" approach to public relations.

VIII.  RETROSPECTIVE VIEWS                                           /

Regulatory officials and Frontier's president agreed that the siting of
the Niagara Falls facility proceeded smoothly and in retrospect no
changes in that process would be warranted.  Should the siting be re-
peated today Frontier would have to apply for a DEC permit.  Based on
the response to Frontier's February, 1979 permit application, however, a
DEC official felt that no public concerns would be raised.  This, he ex-
plained, was consistent with similar facilities which require SPDES
permits.  With some minor exceptions, there has been no public
opposition to the granting of these permits.

-------
Frontier's president cautioned that the company's experience did not
translate into public acceptance of hazardous waste treatment
facilities.  He felt, in direct contrast to the view held by the DEC
Official, that public concern and opposition to the land disposal of
hazardous wastes could easily be aimed at Frontier's Niagara Falls
facility.  The public, being only marginally informed, cannot make
distinctions between technologies or reputable and disreputable firms.
The tarnished public image of current hazardous waste management is a
critical problem with serious implications.  The most serious
implication is siting, and.if the public is given the power to the final
decision, he felt no sites could be obtained.  Bad publicity has also
made lending institutions leery of the industry and exacerbated capital
formation problems.  Frontier's president felt that industry attempts to
improve this image have been and will be only counter-productJ.ve.
IX.
GENERAL COMMENTS
Frontier's president saw a need for an increased governmental role in
siting and an increase in the sophistication of regulatory agencies.
Because hazardous waste facilities are so unpopular, local elected
officials who support them do so at the risk of their public careers.
It is difficult for these officials to play a constructive role in
siting.  Thus the state needs the power (i.e., preemption of local
zoning or eminent domain) to override local opposition in such a way
that local legal recourses are minimized;  Such recourses could delay
siting for years, and companies willing and able to spend three years to
secure a "site are few.  Regulatory agencies also need to be conscious of
the implications of their regulations on the industry, particularly in
terms of the amount of time required for the impacts of regulations to
take full effect.  Frontier's president was doubtful that regulatory
agency staffs had the requisite knowledge of and experience with the
hazardous waste management industry to make informed and reasoned
decisions.

State agency comments are presented in the state program write-up
elsewhere in this report.                       ; ••_..•
                                    53

-------
                   GULF  COAST WASTE DISPOSAL AUTHORITY

                            TEXAS CITY,  TEXAS"     '
 I.
INTRODUCTION
The  Gulf  Coast Waste Disposal  Authority.- was  granted a  permit  by  the
State  of  Texas to  operate  a hazardous  waste  landfill and landfarming
operation in  Texas  City.   The  Authority is a public corporation
established by the  state in 1969  to  operate  industrial wastewater  and
solid  waste disposal facilities for  three counties in  the Houston-
Galveston area.  The permit for the  200-acre site was  granted in early
1978 by the Texas Water Quality Board.  This marked the  successful
completion of nearly two years of site selection and planning by the
Authority.    The Authority hopes  to  start disposal operations in early
1980.

The  site,  which was  suggested  by  the local political establishment, is
located in a  highly  industrial area.   Although  the site  is within  view
of a weekend  recreational  community, it did  not arouse any public
opposition prior to,  during, or after  public hearings.

A major element of the Authority's successful plan to  site its facility
has  been  an effort  to assume a low public profile.  Staff has argued
against extensive public relations and education campaigns in favor of
dealings  with local  politicians.  Had  significant public opposition
developed over this  site,  the  Authority has  indicated  that it would have
withdrawn its plans  for the facility.        .    •                  •     ,
II.
BACKGROUND INFORMATION
The site of the proposed 200-acre landfill and  landfarming operation is
in the incorporated limits of Texas City, Texas.  The existing city
sanitary landfill and the Authority's industrial wastewater treatment
plant are located to the north of the site; Swan Lake, a shrimp and crab
nursery for the Bay, is located  to the east; a  commercial deep-well
injection disposal site is located,to the southeast, along with an
industrial disposal pit; and a railroad and highway are located to the
west.  Across the highway and about one mile to the west is a new
private recreational community of custom weekend waterfront homes.  Many
of these homes literally face the site as well as other petrochemical
industry facilities.   Also to the west is an abandoned hazardous waste
disposal pit that the state is trying to have cleaned up.  Texas City,
which contains all of the waste  generating plants that will use the  ,
disposal site, is located less than five miles to the north of the site.
La Marque is a bedroom community adjoining Texas City to the northwest
of the site.  The land is currently being used for livestock grazing.
It was owned by the University of Texas before it was purchased by the
Authority for the disposal site.

The state permit makes provisions to compensate for. any deficiencies in
the site's hydrogeology.  Accordingly, all landfill trenches must be
                                    54

-------
lined either with four feet of existing soil with a permeability of at
least 10"' cm/sec or with liners of three feet of compacted soils with
permeability of at least 10~7 cm/sec if existing soil cannot meet the
permeability criterion.  Any groundwater-bearing sediments encountered
during excavation must be dewatered prior to installing liners.

The 200-acre landfill and landfarming area will be divided into
individual sites, the first of which will be eight acres in area,
providing a four-year waste disposal capacity.  The total capacity of
the area is expected to be approximately 30 years.  The permit has been
approved for the entire 200-acre site, although the Texas Water Quality
Board will be approving each individual disposal site as it is opened
for operation.

The landfill portion of the site will accommodate scrap materi.als, coke,
carbbn, metals and catalysts.  The landfarming portions will accept    :
water oil tank bottoms and sludges.  A separate set of trenches, will
accept fluoride solutions, acid solutions and caustic solutions.  The
proposed landfill and landfarm areas will be built in increments as they
are needed.  This procedure is desirable because the amount of rainfall
runoff which Will have to be treated is thus minimized.  Each section is
completely self-contained and when exhausted will be closed to further
waste disposal.  After new soil borings are taken and their analysis
completed, the next site will be selected and constructed in the same
manner as the previous site.  All equipment will be moved to the next
site and the closed site will be seeded for vegetation.  A new site
within the permitted area will then be chosen after consultation with
the Texas Water Quality Board.

Scrap materials, coke, carbon, metals and catalysts require no
pre-treatment for disposal other than mixing of liquids with soil•  All
such wastes will be collected and dumped into trenches.  Deposited
wastes will be covered with soil once a week.  Dust and fine powder
materials may require more frequent coverage.  Water and sludge wastes
will be suitable for disposal through landfarming operations.  Waste
sludges and liquids will be spread over the landfarm site using two
methods.  The preferred method will be the direct application by the
truck that delivers the wastes to the site*;  An alternative will be used
during wet weather.  The wastes will be delivered to an earthen tank and
stored until the farm is dry.  Then the wastes will be pumped, onto the
farm through distribution pipes.

The landfarm treatment works by absorption and biological decay.  To   '
assist this process, the site will be cultivated, mixing residues with
the soil and thereby allowing continuation of the bibdegradation
process, while at the same time exposing fresh soil to receive new <  "-
wastes.                •-                  •

Runoff water from the landfarm will be collected and pumped to the
adjoining Gulf Coast Waste Disposal Authority wastewater treatment
plant.  The fluoride, acid and caustic solution wastes will require
special handling.  Some of these wastes require special treatment to
                                  55

-------
neutralize  the pH prior to placement in the trenches.   This  group of
wastes will be divided  into compatible  sub-groups:   fluoride solutions,
acid  solutions and centrifuge  filter cake.   Each sub-group will  be
deposited in a separate disposal  area and covered daily with earth.
Liquids  will be mixed with soil.

The facility design incorporates  a  number of other  safeguards.   A series
of ditches  will divert  surface runoff from  active disposal areas.
Monitoring  wells  will be constructed for approximately  every 20  acres
and samples will  be analyzed monthly for the first  year, quarterly
thereafter.  Dikes will surround  disposal sites  to  protect against major
floods and  the entire site will be  fenced.

As described above,  the facility  will accept a broad range of wastes.
The wastes  will be in solid, semi-solid, and liquid states.   All wastes
to be accepted are those generated  within the jurisdictional area of the
Authority,  primarily from petrochemical industries  in Texas  City.

The Gulf Coast Waste Disposal  Authority is  a quasi-governmental
authority which operates  four  treatment plants for  industrial clients.
In addition, the  Authority provides assistance to area  municipalities,
helping  to  solve  their  waste treatment  problems.

Texas City  (1978  population: 45,000).is located  on  Galveston Bay,  ten
miles from  Galveston and 30 miles from  Houston.   The economy of  the
Texas City  area is  strongly based on the petroleum  and  petrochemical
industry.   Area residents and  officials have a long history  of both
depending on these  industries  economically  and cooperating with  them to
solve industry-related  problems.

III.   HISTORY OF  FACILITY DEVELOPMENT  AND  PUBLIC RESPONSE

Under Texas law,  commercial-industrial  waste sites  not  owned and
operated by and located within 50 miles of  the waste generator must
receive  a permit  from the Texas Water Quality Board.  The law also
requires public hearings  on such  commercial-industrial  waste disposal
permits.  The  discharge permit issued by the Board  is the only state
permit required in developing  a commercial  landfill.  No local permits
are required,  and  land  use controls  are generally non-existent
throughout  Texas and do not apply to  the site.

The Gulf Coast  Waste Disposal  Authority was  created in  1969  to own and
operate  industrial wastewater  treatment facilities.  The authority was
created as a public corporation by  the  State  of  Texas with the power to
issue tax-exempt bonds  to  finance its disposal operations in three
counties in  the Houstori-Galveston area.

It was modeled after the  regional water pollution agency in the  Ruhr
Valley of Germany and was  to be a special-purpose district covering
seven counties  in the Houston-Galveston area  with regulatory and
operating authority.  Local elected  officials opposed this type  of
authority because it diminished their existing landfill and wastewater

-------
responsibilities.  Some industries, especially those that had mounted
effective water pollution control programs of their own, opposed the
Authority and the possibility of further government regulations.  The
general public also expressed some opposition to the taxing authority
proposed for the Authority.

The final state legislation created a smaller (three-county) Authority
and provided seed funds to start its operation.  The final legislation
also limited the Authority to waste disposal operational responsibili-
ties.  Regulatory responsibilitj.es were left to other state and federal
agencies.  (The enabling legislation can be found in Appendix 1.)

Since the creation of the Authority, its public profile has faded to the
point where most citizens are probably not aware of its existence.  At
the height of public opposition to its creation, however, the Authority
was accused of acting solely to benefit industry by using its power to
issue tax-exempt bonds for the construction of industrial wastewater
treatment facilities.   No counter campaign was mounted by the Authority
even though local environmental groups were quite vocal on this issue.
Since 1970, other issues have occupied local citizen groups.       '
Furthermore, the subsequent increase in Gulf shrimp and oyster catches
in nearby waters has reduced any potential environmental concerns over
wastewater pollution controls.

Since the Authority began operations, the General Manager has countered
public opposition with the effective and respected operation of the  -.
Authority.  There have been no campaigns to secure support for the
Authority.  His rationale for a low-profile strategy came from his years
of experience as a city manager involved in many forms of public
opposition.

In 1976, the Authority sought the advice of the mayor of Texas City and
a local county commissioner on potential sites for a new venture into
industrial hazardous waste disposal.  Based on their review of other
siting attempts in Texas, the Authority decided first to contact local
elected officials.  Members of the Authority had attended public
hearings in other parts of the state to learn what the siting problems
were and how to fight them.  As a result of this review, the Authority
concluded that the site had to be located in an industrial area with the
help of local politicians and that no amount of public education would
make the public willingly accept a hazardous waste site.  In other
words, they felt that, "to know a hazardous waste site is not to love
it."  The Authority was convinced that educating the public on hazardous
waste disposal techniques and site suitability was not useful and
probably counterproductive since it gave the proposal an unnecessarily
high profile.  They felt that siting was a purely political problem that
should be left to local politicians.

The decision to focus on political problems of siting was made possible
because much of the area under the Authority's jurisdiction is or can be
made technically suitable for hazardous waste disposal.  Sites not    :  ,
                                    57

-------
already  technically  suitable can be made so  with engineering
modifications  such as  dikes  or  clay liners,  which Would  change  only  the
cost  of  operation.

The mayor  of Texas City  suggested a suitable site in the spring of 1977,
and an application for a permit for this site was prepared  and  submitted
to the Texas Water Quality Board in the  autumn of that year.  Public
hearings were  held shortly thereafter  in Houston and Austin as  a
standard part  of  the permit  process.   Required notice of these  hearings
was given; however,  in keeping  with the  Authority's  low-profile ,
approach,  no steps beyond the legal requirements were taken to  inform
the public of  the  hearings.   No opposition whatsoever was voiced at
these hearings.   Only  the state and members  of the Authority were
present at these hearings.   The Texas  City mayor had been scheduled  as a
witness  in support of  the proposal,  since all of the wastes were to  be
generated  by plants  in the Texas City  area,  but  his  testimony was not
required.  Although  advised  of  the meeting through newspaper notices, no
local residents appeared at  the hearing  or gave  any  other indication of
being opposed  to  the facility.   Following the public hearings,  the Texas
Water Quality  Board  issued the  Authority a permit for the site  in
February of 1978.

During the two-year  period leading up  to the issuance of the permit, no
public opposition  was  voiced.   The Authority indicated that had there
been  significant opposition,  the site  plans  would have been dropped.
The Authority  is expected to  begin disposal  operations early in 1980.
IV.
CHRONOLOGY OF EVENTS
1969 — Gulf Coast Waste Disposal Authority is created.

1976 — The Authority seeks the advice of local officials on potential
        sites for a hazardous waste disposal facility.

Spring, 1977 — The mayor of Texas City suggests a suitable site.

Autumn, 1977 — The Authority submits an application for a permit for
                the site to the Texas Water Quality Board.  Public
                hearings on the application are held in Houston and Aus-
                tin.  There is no indication of any opposition to the
                facility.

February, 1978 — The Texas Water Quality Board issues a permit for the
                  site.

Spring, 1980 —   Expected date on which disposal operations will begin
                  at the site.
V.
ATTEMPTS TO SECURE SUPPORT
Actions taken by the Gulf Coast Waste Disposal Authority to secure sup-
port for this facility include the following:
                                     58

-------
VI.
o     They solicited the advice of local Apolitical officials and
      allowed them ..to choose the-site.

SUMMARY EVALUATION              .-.'",
There are four  reasonsrwhy  the  Gulf  Coast  Waste Disposal Authority was
able to  si,te  a  hazardous  waste  disposal facility without public
opposition:   1)  they  kept a low public  profile;  2)  the  site is  in a
heavily, industrial  area; "3) :,they had local ...political support; and 4) the
wastes to be  disposed of  there  are generated  locally.   Each of  these is
discussed below.  It  does not seem that the Authority's being a ,
state-created public  corporation affected  the site  approval process.
Their success is  in, sharp contrast to many other siting attempts in
Texas which have  been intensely opposed by the public.           '

Industrial Area —  The perceived .impact of a  hazardous  waste facility on
the environment and/or quality  of life  in  an  area is likely to  be
greater where similar operations do  not already exist.   There have been
waste disposal  operations in the Texas  City-La Marque area for  many
years.  A municipal landfill, an industrial disposal pit,  a wastewater
treatment plant and a commercial deep-well injection site  adjoin the
proposed hazardous waste  site.   There is also an abandoned hazardous
waste pit in  the  area which has received some sporadic  public attention
but has not created any sustained concern  about  hazardous  wastes.
Therefore, although the site' is in plain view of a  recreational
community —  weekend  waterfront homes --there was  no public outcry.

Local Wastes  - In addition  to having  learned  to  live with  waste disposal
in an industrial  area, the  local public is also  clearly aware of the
fact that the area's  prosperity is due  to  the petrochemical industry.
The Mayor of  Texas City said that fourteen years ago a  series of
meetings was  held between industry and  the public to explore the
undesirable side-effects  of the industry and  ways to minimize their
pfoblems.   Since t-hat time  the citizens have lived  harmoniously with
industry.  The local  residents  appreciate  the fact  that these industries
must dispose  of wastes and  that  a disposal site  in  their area is just
one more fact of  life.

Political Support - Although having a waste disposal facility in the
area did not arouse any opposition, it  was  still necessary  to involve
local politicians in  the  selection of a particular  site.   The Authority
left this decision entirely up  to the local political leadership.   The
mayor of Texas City had previously been involved  in  siting  a municipal
landfill and based on this  experience he recommended that the hazardous
waste disposal facility be  sited,in an  adjoining,area.  The, entire
region is endowed with low-permeability clay  formations making  the
difference between specific  locations a matter of proper site
engineering.   Therefore,  the site most  politically acceptable was also
technically acceptable.   This minimized the possibility of  local
political opposition.   It was felt,by the  Authority  that the mayor's
decision reflected the public,1 s preference.   :

-------
Low Profile — Having reviewed the experiences of other agencies and
corporations trying to site hazardous waste facilities in Texas, the
Authority felt that trying to educate the general public on hazardous
waste disposal issues in support of site selection was unnecessary.
They argued that a public education and awareness program was not useful
because the public could not be expected to willingly accept such a site
simply because it understood the problem.  Furthermore, they felt that
such a program might be counterproductive, since it might create opposi-
tion where none would exist otherwise.  The Authority did provide all
the necessary public announcements, hearings, and media coverage of its
intent to site and operate a disposal facility.  However, they did not
conduct a public relations campaign to secure support for the site.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

In summary, the major factors contributing to the successful siting
were:

       o     The area has a heavy concentration of petrochemical plants
             that generate the wastes to be disposed.

       o     The inhabitants of surrounding areas both within and
             adjoining Texas City are dependent, on the continuing tax
             base and employment opportunities represented by the
             petrochemical plants.

       o     The site was suggested and strongly supported by the local
             political leaderships.

       o     Other municipal, commercial and industrial waste disposal
             facilities have been in operation in the area for many
             years.

       o     The Authority maintains a low profile with regard to its
             waste disposal activities to avoid generating public op-
             position.

       o     The Authority has established a good reputation in
             wastewater disposal enterprises over the past nine years.

VIII.  RETROSPECTIVE VIEWS

For officials of the Authority the successful siting of a hazardous
waste disposal facility has confirmed their original strategy of
maintaining a low public profile and selecting an industrial area with
the help of local political leaders.  They have indicated that they have
no cause to regret this strategy and intend to repeat it in future waste
disposal facility plans.

The Mayor of.Texas City, who actively participated in the site selection
process, also felt that everything done in the siting of this facility
represented a proper and effective course of action.  If given a chance
to participate in a similar site selection process, he has said that he
would do it the same way.


                                  60

-------
             APPENDIX:




    ENABLING LEGISLATION FOR THE    .
          *             "' " •

GULF COAST WASTE DISPOSAL AUTHORITY
                61

-------
   Chapter 409, Acts of the 61st Legislature  of the
        State of Texas, Regular  Session,  1969
                  As Amended By
  Chapter  202,  Acts  of the  62nd Legislature of the
 State of Texas, Regular Session,  1971; Chapters 258
    and 466, Acts of the 63rd Legislature  of the
      State of Texas, Regular Session, 1973; and
  Chapter  443,  Acts  of the  64th Legislature  of the
        State of Texas, Regular Session,  1975
                (Originally Codified  as

    Article 7621d-2, Vernon's Texas Civil Statutes)
THE GULF COAST WASTE DISPOSAL AUTHORITY
                                             Compiled  July  1, 197'
                              62

-------
                              TABLE OF CONTENTS
                                                                               Page
Subchapter 1. Goner.=i I'H -visions	:	   I
    Section 1.01 -i'i:rpo>o	.;. . - -	-	- -   1
    Section 1.02 - l-'i-uhna- and declaration of policy :	   1
    Section 1.03" Dolini'.u.n.s  .	   J

Subchapter 2. Adinii-istrative Provisions	   2
    Section 2.01 - (.'ration of Authority	 .  .	,....-.......,	   2
    Section 2.02 - l)< Sv.ription	   3
    Section 2.03 - B .ard  .,..,...'.		- . .-..	 .	   3
    Section 2.04 - Q-iaHI'ication of directors	   3
    Section 2.05 - TVr:n> of directors and appointment procedures .	 .,	   3
    Section 2.06 - Qualification by directors  ...........	, . -   4
    Section 2.07 - Meetings and action.^ of the board	   4
    Section 2.08 -Organization of board	-	   4
    Section 2.09 - Interest in contract	   5
    Section 2.10 - Director's compensation	   5
    Section 2.1 1 - Genera! Manager  ..'..'	............   5
    Section 2.12 - Directors' and employees' bonds   .........	   5
    Section 2.13'- Principal officer	.- .   5
    Section 2.14- Records  ....... '. . '. .	   6
    Section 2.15- Seal	,		• ;•  •	• -   6
    Section 2.16-Suit  	... ....	-	-  - - . . -	   6

Subchapter 3. Powers and Duties	 .."..	   6
    Section 3.0! - General powers and duties	   6
    Section 3.02 - Authority rules	 .•'..	   7
    Section 3.03 - Inspections and investigations	',_	  '7
    Section 3.04 - Hearings	   7
    Section 3,05 - Penalties  ....	......	,		   7
    Section 3.0ft - Court review	   8
    Section 3.07 - Authority of local governments	 ......   8
    Section 3.08 - Water quality standards and criteria  	   8
    Section 3.09 - Enforcement of state water standards	:........  9
    Section 3.10 - Master plan	   9
    Section 3.11- Regulation of solid waste disposal	.10
    Section 3.1 2 - Septic tanks	10
    Section 3.! 3 - Disposal of waste from watercraft  	;	,11
    Section 3.14 - Acquisition, con.struction, and operation of disposal systems  	11
    Section 3.15- Waste disposal contracts	  11
    Section 3.16- Sale of water and. by-products	  12
    Section 3.17 - Permits from Texas water ri«hts commission  .	12
                                            63

-------
    Section 3.18- Eminent domain	  12
    Section 3.1^ - Rilo.-ai.ion of facilities	•	- •  '2
    Section 3.20 - iSc of public easc-inents  	•  12
    Section 3.21 - Acq-.u-ition and disposition of property	  12
    Section 3.22 - Facilities	-	13
    Section 3.23 - Contracis generally  	-	-13
    Section 3.24 - Cooperative agreements	- -  H

Subchapter 4. General Fiscal Provisions	  14
    Section 4.01 - Disbursement of funds  . .	,	14
    Section 4.02 - I'e-.-s and charges	  15
    Section 4.03 - loans and grants	  15
    Section 4.04 - fiscal year and audit by state auditor	  15
    Section 4.05 - Slate auditor's report	  15
    Section 4.06 -Cost of state auditor's audit	  15
    Section 4.07 - Independent audit   	.-.. -	  15
    Section 4.OS - Depository banks  	•	'1.6

Subchapter 5. Bond and Tax Provisions  	:.. . .  16
    Section 5.01 - Bonds	,	  16
    Section 5.02 - Refunding bonds  	...........'	  17
    Section 5.03 - Approval and registration of bonds	  1,8
    Section 5.04 - Bund election  	.......	  18
    Section 5.05 - Maintenance tax	18
    Section 5.06 - Election	- - -	  IS'
    Section 5.07 - Rendition, assessment, equalization, levying, and collection of taxes  .  I1)
    Section 5.08 - Tax limit			-'.	  19
    Section 5.09 - Bonds authorized investments	..20

Subchapter 6. Pollution Control Districts  	20
    Section 6.01 - Pollution control districts	20
    Section 6.02 - Establishment of districts	20
    Section 6.03 - Boundaries and addition of territory		22
    Section 6.04 - Taxation	• 23
    Section 6.05 - Bonded indebtedness	23
                                         64

-------
                    SL'BCH-UMt.R  I.   GHNHRAL  PROVISION'S

                                       Purpose               '                ,

            Scv.t:oi]  ''.'!!.   I: ie purpose.of this Act is  to establish an instrumentality for
developing and el'f-.vM.ir.'i:  tor Chambers. GaKeston. and Harris Counties a regional water
quality  management  progiim including provision of Waste disposal systems and regulation
of disposal  of w..i-us.

                         i-'indings and declaration  of policy

            Sec.  l.'i'.   It  is hereby  found  and declared that the quality of waters in
Chambers. Cialwstou. ;.nd Harris Counties is  materially  affected by the disposal of wastes
throughout  those ..-.unities:  thai regional approaches to studying water pollution in these
counties,  to planmnsi corrective and  preventive measures, to providing coordinated  facilities
for wa^le disposal, .ird Jo rcgi.-ating waste disposal would be far more effective than efforts
on  a county-wide. «.:ty-\vk!e. i>r smaller scale: that solid wastes, as well as other kinds
of waste, may  imp.i-r water quality by seepage, drainage,  and otherwise:.that  creation
of the diilf Coast Waste Disposal Authority  would advance  the established policy of the.
state to  maintain the q u;!i:y of the w.tters  in  the .state consistent with the public health
and  public enjoyment then of. the  propagation and protection  of terrestrial and aquatic
life, the opcraticn of c\Kti:i;j industiies, and the economic development of .the state: and
that  impending  short.ipe of water  in  the  district  for beneficial uses requires  that  all
reasonable 'measures  u> be  taken to prevent and abate  water  .pollution,  .and to reclaim
polluted water  for  buK-ficial uses.

                                     Definitions
this Act.
            Sec.  1.0.'.  (a) in  this Act. unless the context requires a different definition,
            •(!-)   "Authority" means the Gulf Coast Waste Disposal Authority created by
(2)
                  "Board"  mvans the board  of directors of  the  authority.
            (?)   "Director" means a member of the  board.
            (4)   "District" means the  territory  included  in  the authority.
            (5)   "I'erson"  means .my  individual, public or private  corporation, political
subdivision,  governmental  agency, municipality,  copartnership,  association,  firm, trust,
estate or any  other entity  whatsoever.
            {<•>)  "Oualifs board" means the "I exas Water Quality Board created by Chapter
313.  AUs of the <>Uth  I.cuM.itiire. Regular Session. 1S)67 (Article 762 Id- 1 . Vernon's Texas
Civil  Statutes), tir  its  succvssr.rs.
            (7)   "Rule"  includes  regulation.
            ('S>  "Water" means grbundwater.  percolating or otherwise; lakes,  bays, ponds,
impounding reservoirs, springs.. rivers, streams,  creed.s. estuaries, marshes, inlets, canals, the
dull'  of Mexico within  the district, and all other bodies of surface water, natural or artificial,
inland or coastal, fresh  or salt,  navigable  or non-navigable,  that are wholly or pariiaily
svithin  the  district.                                                           .
                                             65

-------
            (;»   'W.t.-i-i"  means sewage,. uuhistiial  waste,  municipal waste,  recreational
waste. agri.'ulS'.ira1 \a-i.-.cr other  waste,  as  defined  in  this section.                 ,
            (i()i   'St\\.ir\" means waterborne human or  animal waste.
            (11)  "Muc- >  pal waste" means \\aterborne liquid. gaseous, m; solid substances
that ro.\  i-isjharge lY-nn a publicly owned sewer s\ stem, tivainsent  facility.,
or  disposal sy-ti ir..
            ( 11 >    " K .-..eational  waste"   means  watcihorne  liquid. gaseous,  or solid
substances tli.i' cm.sMaK  trom any  public  or private  park,  beach.,  or  recreational area.
            (1.?)    " Agricultural  waste"   means  waierborne  liquid. g.iseous.  or solid
substances that u"ise from any type of agricultural activity, including \\atcrborne poisons
and insecticides  US.M  i:i agricultural activities.
            (1.4 J  ' Industrial waste" means waterboine liquid, gaseous, or solid substances
that result  from  any  process of industry,  manufacturing,  trade,  or business.
            (15 I   'Other  \\.iste"  means garbage, refuse, decayed wood, sawdust, shavings.
bark. vmd. li:n.%. . ihders. ashes, offal, oil.  tar. dyestuffs. acids, chemicals, salt water, or
any other subst.m. >..  other than sewage,  industrial  \\.iste.  municipal waste,  recreational
waste, or agriculti-r: ! waste, that may cause-iinp:iirmenr of the qualit>  of the water in
the state.
            (Ifi)    "Solid  waste"  means  any putrescibL-  or non-putrescible  discarded
material,  including  but  not .limited to garbage and  reiuse.
            (17)   "\\;iter  pollution"' means  the  alteration  of the physical, chemical, or
biological  quality  of. or  the contamination  of.  water that renders the  water harmful.
detrinHMH.il or iniur; HIS  to humans, animal  life, vegetation or property or to public health.
safety, or welfare,  or impairs  the  usefulness  or  the public enjoyment  of the. water for
any lawful  or u-asoiuible  purpose.
            (18)   "Sewer s\stem"  means  pipelines, conduits, canals, pumping stations.
force mains, and all other constructions, devices, and appurtenant  applicances  used to
transport  waste.                                                          •
            (I1))  "Treatment facility" means any plant, disposal field, lagoon, incinerator,
area devoted  to sanitary landfills, or other facility inst-.Uied for the  purpose  of treating.
neutrali/ing, or stabilizing waste.
            (.20)  "Disposal system" means any system for disposing of waste, including
sewer systems  and  treatment facilitic.s.
            (21)   "Local  government"  means an incorporated city, a county,  a river
authority, or a water  district or authority  acting  under Article III, Section 52.  or Article
XVI. Section  59. of the  Texas Constitution.
            (22)   'Outside the district" means the area contained  in counties adjacent
to  the district.

                Sl'BCHAPTFR 2.  ADMiNISTRATIVh  PROVISIONS

                               Creation  of authority.

            Section 2.01.   There is  hereby created,  pursuant to Article  XVI.  Section  51'..
of  the Texas  Constitution,  a conservation  and reclamation district  to ho known as  the
                                            66

-------
Gulf  Coast  W:sjo,i! Authority, which slutil  be  a governmental agency and body
politic aivd ci.-rpor '•'•••  '••  :ii-.'-State of f'exus. A •c.iit'inn.ition election .shall not be necessary.

                                     Description

            Sev.  1.1)2   1 he authority's ierritoix. consists oi  i:,e area inside the h'-.tiularie--
of ("li.imbers.Ci i!vvM'>; . hul  Harris Counties.  The le'r^Ltiure'd.vl:!rv'-> That a!!  riie-area
included in  the district  'will  be benefited,  by -the exercise oi  the.powers conferred h%  this
Act.          ':              -.'      - ..     '    -              •--•..    '   /  ••• '• '

                                       Board    •                   ;         '       "

            Sec  203.   (a) The  authority's powers,  rights,  duties, and   functions are
exercised  by a  bo.srd of directors.
            
-------
 each munici|-aiitic  u •>:,.•  ih-pM-.a! Council  shall meet at :i :ime and. place designated by
 its tempor.ir. .-ii.iJM'.a i  .rio-- notice o! the time and place D! that meet mi: has been mailed
 by  the temporary  i- iirn .in to i-.iv.-h  member  of  the  council at least 4x luutrs prior to
 the time  fixed f. .- : ...   :. i-. ctiiu:.   A; that me-Mini:. the  council shall  elect a chairman.
 vice-chairman. :ni  K.CI.-I i: c. and  -h.i!! adopt Mich  bylaws ivl.itin.u  to ihe conduct of it*
 alTairs as the  v-i.-u.-ii --hil: determine  to be necessary.
            (d)    \V.h_--: ; director's term expiies.  his successor shall be appointed by the
 same source a;u!  n.- ;l!e - :me  manner as was  the director whoso term  expired.
            (e)    Ui.ei; a  doctor's  olfice  becomes  vac.mt' by  death,  resignation, or
 removal, the une.\:vrvd  term sluli be  filled by  the same source and  in the same-manner
 as  was the  direct.•!  whose oifice IMS  become  vacant.

                             Qualification  by  directors

            Stc   .!.')6.   To (i»a!ilV for office, each director must
            (1)    t ko  the oath of office prescribed by Article !(•>. Revised Civil Statutes
 of Tcxat,  1925:
            (2)   s^ocutc  a bond in  the  amount  of 55.000  with a corporate surety
 authorized  to  do  business in this state conditioned on the faithful per.forma.nco of his
 duties; and
            (3)   file a copy  of his bond  with  the secretary of state, and  with  the
 commissioners court of the  count},  from which  he is appointed.

                         Meetings and actions  of  the  board

            Sec. 2.07.    (a) The  board shall  meet  at  least once each  month,  and  may
meet at  any other time provided in  its  bylaws.
            (b)   Except as otherwise provided in  this  Act. the vote of a majority of
directors is  required for board action.
            (c)   The hoard slus!! adopt  bylaws at its  tiiM meetinu or as soon thereafter
as possible.

                               Organization  of board

            Sec.   2.08.    (a)  The board  shall elect  from its members a  chairman.
vice-chairman, secretary,  and other officers  it deems necessary.  A  person who, is elected
to a hoard  office  shall  servo for  two years  in that capacity or until he ceases to be a
director, if  this  event   occurs  within  two  years.   Officeis1 terms shall commence on
September  I.
            (b)   At its September meetini: each  year, the board  shall elect officers for
the offices  to  be  filled.
            (c)    If a vacancy occurs in a board office, ihe directors at the next monthly
meeting shall  elect a person to serve  until the next September meeting of the board.
            (d)   The board's bylaws  shall  prescribe llse powers, duties,  and procedures
for removal from  board office of officers  that it  elects.
                                             68

-------
                                  Interest in  contract

            Sec.  T-O-'i   A director v.ho is financially interested in a contract to he executed
bv the authoritv  '.;•>.. ;;-j f-.ucluise ui  properly  --r the constructionof f.ic'ili'.ies shall disclose
thru  fact  to lii •   >'aj  ,1,rectors  a"d may  not  \o!c on  liie  acceptance ol.the contract.

                              Director's  compensation                               :,

            Se>..  2.10.   (a) -\ director is entitled  to  re.ceive ail allowance of S25 a day
and  reimburseme-;!  tor actual and necessary  expenses incurred
            (1)   ;'or  each dav  he spends  attendir.i!  meetings of the  board: and
            (2)   'or each day he spends attending  to  the business of the authority which
is  authorized  I\v  a  resolution ui  tlu-  hoard.  '
            (bi    X director is. not ciuiiled  to receive  a  per diem  allowance for more
than  12(1 days h;  >:-.\  one calendar \ear.

                                  General  mannijer'

            Sec.-2.1 i.   (aV.The board shall  employ  a  general manager for a term and
salary set by  the boatJ,                •          .                            •     .
            (bi   The  general  mai:ager  is  the  chief  executive officer  of the authority.
Under policies established by the  board." lie is  responsible  to the  board for
            (1)   administering  the directives of  the  board:
            (2)   keeping the  authority's records,  including  minutes  of   the -board's-;
meetings:
            (3)   coordinating with state,  federal, and  local  agencies:
            (4)  .developing plans  and programs  for the board's approval:
            (5)   hiring,  supervising, training, and  discharging the authority's employees:
            (6)   contracting for or retaining technical, scientific, legal, fiscal, and other
professional services: and                                                    •
            (7)   performing auy other  duties  assigned to  him by  the  hoard.
            (c)   The  board  may discharge  the genera! manager  upon a majority \ote
of all the  qualified directors.

                           Directors" and employees*  bonds              ,

            Sec.  2.12.   (a)  The  general manager  and each  employee of the authority
charged  with  the collection, custody.  or payment of auy'money  .of the authorit\  shall
execute  a fidelity bond.  The board, shall  approve the form, amount,  and .surety of the
bond,                             ,      •                              <
            (b)   The authority shall pay  the  premiums on  the employees'  bonds under
this  .section and  the directors'  bonds  under Section  2.0o  (2) of this Act.

                                   Principal  office                    ,           j   ;

             Sec.  2.13.   The authority  shall  maintain its principal office inside the district.
                                             69

-------
                                       Records

             Se«.   ' I 4,   ;i:!  Tii-.- authority Mi.-!l keep  complete and accurate, -accounts of,
 it's business Ins !••:. i •>  •>  11  a'-cord-iiice with  generally accepted  methods  of accounting.
             l:>-   "I iv  : :!'i'>rit\ sh.il! keep complete and accurate minutes Mi" its meetings.
             (-•'   "I ic  :•  ! l.ority  sit si! keep its accounts. ciKiM'.tcts. documents,  minutes.
 and other  ree«r economics uf  operation of industries.
             (e)   1 xc-'pt ,i  {••!•• i\ idod in Subsection (d) of t'ni.s section, the authority shall
 permit reasonahv i-uhii-: ii-spection of its  records during  regular business hours.

                                         Seal

             S.-c.  _'. .•».  "Hi.- authority shall adopt  a  soul.'the  form of which it may alter
 from  rime  to tstr-e

                                         Suit
                               •                   .                          "
             S-v.  2.1 i'-..   The authority  may sue and  be sued  in  its  corporate  name.

                     SM5OIAITI.R 3.  POWKRS  AND  DUT1HS  .

                              Genera!  powers  and  duties

             Sec. .1.01.  (a)  The authority  sh-all  administer and  enforce the  terms of this
 Act and  shall use its  fa.-ilities  and powers to  accomplish  the purpose  of this  Act.
             (bj   '1 he authority shall  conduct studies and research for the control  of water
 pollution and  waste dipsosal within the  district.   It shall cooperate  with  the Gaheston
 Bay Study  of  the quality board  and utilize  the  results of that  study.
             (c)    The regulatory  powers of the authority under this Act extend  to every
 person, .is  that term  is defined in  this Act.                               '  -. .
             (d)   Kxcept  as expressly limited by  this Act. the  authority shall  ha\e all
 powers,  rights,  .iiul privileges necessary and  convenient ior accomplishing  the purposes
 ot this Act  conferred by genera! law  upon any conservation aiid reclamation district created
 pursuant  to Article X\'I. Section 5l>. of  the Texa<  Constitution.    •
             ("e)   SuHect only  to the authority vested by general law., and particularly
 the Texas Water  Quality  Act (Article 7o21d-l. -Vernon's Texas  (i\i! Suti.uesi. ;IS MOW
 or hereatter amended, in the-qualiiy  board and  the state agencies repivsented on the quality
 board, the  authority  is empowered  to control .water pollution  and waste diposal within
 the district.                                     .                 .         •-.•••,-
            (f)    The powers granted to  the  authoirty in this  Act are cumulative of all
 powers granted  by other laws, now  or hereafter existing, which are In their ternis applicable
to the authority.
                                           70

-------
                                 .  AuthoriU  rules

            Se«..  i.'l. .  ( t.' The authority shall adopt and enforce rules reasonably required
to effectuate t!-e p'vv:-.io|.>  ot tin-. Act. including rules governing procedure and practice
before the b<'^-\.                                                     •
            (hi   In .-d-v.'iing rule-., the  bo.trd shall  compix. as appropriate, with  the
requirements t-l •.'I'.ip'c  274.  Acts of the 57th Legislature. Regular Session.  1U(>1, as
amended  (Artic;c  '>j:52' Lv  V'ernon's  Texas Civil Statutes).
            (o  . H;e  noard .'shall  print  its- rules and  turnish copies to any person on
his  written  reiujs...:.

                            Inspections and investigations

            Se>..  3 (.'3.   (a)  Under  the same provisions  and restrictions applicable to the
quality  hoaro  or it-- successor,  the authority  ma\  enter public  or private  property for
the purpose ol i-is-.n cling and investigating .conditions relating to water quality and waste
disposal  in  the liNniet.                      •    ..'••'.
            (h)   The   authority   >hall   transmit  the  results  of  its  inspections  and
investigations  to  the mu'ity board.                                               •
                               *
                                      Hearings

            Sec.  .:.('4   The board may
            (1)   imld  hearings, receive pertinent tind  relevant  proof from  any party in
interest who appears before  the  board, compel the attendance of witnesses, make findings'
of fact and  determinations  with respect  to administering  the .provisions of thU Act or
of any  orders  or rules  of the authority:  and
            (2)   delegate  to  one or  more  of its members or to one or imore  of its
employees,  the authority to take  testimony  in any  hearing called by  the authority, or
authorized by  the  authority to be held, with power to administer oaths, but all orders
entered shall be  m.:de  by and in the name of  the  authority  after its official action  and
attested  to  by the  proper members  of the board  of dhectors.

                                      Penalties

            Sec.  3.05.  (a) A person who violates a  rule, permit, or order of the authority
is subject to  a civil penally of not  less  than  $50 nor more than S1.000  for each  day
of violation.   The  authority  ma>  sue  to recover the  penalty in a distric;  court in the
county  where  the  violation occurred.   Penalties shall  be paid  to the  authority.
          ,  (b)   The  authority may sue  for  injunctive relief-in a district court in the
county  where  a violation of its rule, permit,  or order occurred or is  threatened.  In any
such  suit, the  court sliall have.jurisdiction  to grant  to the authoritv.  \\itliout  bond or
other undertaking,  sue!', prohibitory and mandatory injunctions as the facts may  warrant.
including temporary restraining orders, after notice and  hearing, temporary ".injunctions,
or permanent  injunctions.
                                             71

-------
 proceeding.
 suction.
(c)    ~1 h.*  :!Jt;u»rify  may  sue  l<-.r  injnnctivc  relief and penalties in the same

(ih     !.')  -\ person  who  is adversely affected by a rule.  act. or order
 of the authority'may sue t'u- authority in  a district court to set aside  the  rule. act. or
 order.  The suit  s'l.dl he hU-d within 60- days  after the day on which  the  rule, act, or
 order  took effei?.
             (hi    Venue  for suits  under Subsection (a) of this section  is in any  county
 in  the district.

                           Authority  of local, governments

             Sec.  307.   (a) Under the same provisions and restrictions as are  applicable
 to  the authority,  a  lo.'.il government  may  go in and  on public and private property to
 make  inspections  to i let ermine, compliance with  the  rules,  permits, or  orders of the
 authority. A local government shall transmit the results of its inspections  to the authority.
            (b)    \ local government, upon  formal resolution of its governing bcxly. may
 sue to enforce the provisions of Section 3.05  of this Act and for the penalties and injunctive
 relief provided theiei-i.  The authority is a necessary party  to a suit under this subsection.
 Penalties  recoveied in such actions shall  lie paid  to the  authority.

                         Water quality standards and  criteria

            Sec.  3.08.   (a) After  public hearing,  the authority shall  prescribe standards
 and criteria  for the  waters in the district.
            (b)    After the authority  has prescribed standards and criteria, it shall forward
 a copy of the standards  and criteria  to the  quality board  for approval.
            (c)    The quality  board  shall  consider, the standards and  criteria.
            (d)    If the quality board objects to the standards and criteria in any respect.
 it  shall -.o notify  the  authority  in  writing  within  <;() days after receiving the proposed
 standards and criteria, stating the objections  and  the reasons therefor.  '1 he authority shall
 amend  its standards  and  criteria  in light of  the  quality board's timely objections.  When
 the authority  has amended  the standards  and  criteria in light  of the quality board's
 objections, the quality board shall promptly evidence its approval of the amended standards
 and criteria  in writing.
            (o)   If the quality  board  does not notify the authority that  it objects to
 the standards and criteria within ^0 days after receiving thorn,  they are  operative at the
end of the 90-day period.  If the quality  board notifies-the authority within the- C)0-day
period that  it  objects to the  standards and criteria.  tho> are operative from  the date the
quality board  approves  them.
                                             72

-------
                       hnlm cement  ol  state water standards

            Sec   >.' l)   I "pi  The  authority shall prepare a master plan encompassing plans
for the maxiinu'! i abatement  and prevention of water  pollution, plans for  the control
of waste • disposa";   m.I'plans and methods for the treatment and control of waste  water
that would other .v.se c.iuse pollution. The master plan shall show at least:  (1 ) the nature
and  location of  existing  w.iste  disposal  systems  in  the district: and (2) the nature and
location  of proposed waste disposal  systems which will  be needed in the district within
stated  periods  of time to  maintain  desired  water quality.  The master plan shall be a
guide  for devcU-p'iu-n't of such  systems by  the  authority  and by other persons.
            (b)   Tie  master plan shall be filed with  the quality board,  for its re vie w
and approval.  If the quality board shall -not notify  the authority "" writing of its disapproval
of the plan in any  respect within LSD days  of filing,  its app<     shall not be required.
Any objection^ to the plan  by  the  quality board shall  be sui-......ed  in writing to the
authority,  and when the objections'are met to  the satisfaction of the quality board, it
shall promptly evidence its  approval in  writing.
            .(c)   The  master plats so approved  shall  be available for'inspection by the
public  at the authority's principal office.
            (d>   "I he  master plan may  be  amended or supplemented  by the authority.
provided that a copy of such amendment or supplement to the master  plan shall be filed
and  approved  in  accordance  with Subsection (b) of  this section.
            (e)   The  first master plan,  as  amended or supplemented, shall be effective
for a  period of  10 years.   Upon the expiration of each  10-year period,  the  authority
shall revise  its master  plan and  a copy  of said revised plan shall be filed  and  approved
in accordance  with  Subsection (b) of this-section.
            (f)    Prior to the adoption of a  master plan, or any amendment, supplement,
or revision effecting any substantial  change,  the authority shall give  notice to the public
that it  proposes to adopt such master plan, amendment, supplement, or revision, by causing
a notice  describing  its  general nature to be published once  in a newspaper  of general
circulation in each  county in the district.   In addition  to such publication,  a copy of
such notice shall be transmitted  by mail to the county judge of each county Within the
district, to  the  mayor  of each incorporated  municipality within the  district, and to the
manager  or presiding director of  every water district within the district which has registered
with the Texas Water Rights Commission under Chapter 62. Acts of the 54th  Legislature.
Regular Session.  1955,  as amended (Article  X280--7. Yernon's Texas 'Civil Statutes), such
notice  to  be mailed not less than 20 days before  the regular meeting  at which the .master
plan, amendment, supplement, or revision is to be considered  for the first  time.  Failure
in delivery of  notice does  not invalidate the action taken.
            (g)    Such  master  plan, amendment,  supplement,  or  revision  may  be
considered and approved at the  regular meeting of the hoard next following the last date
                                           "73

-------
of  publication or  \v:t'i«-ii?  fi'inlier  notice, at any regular  meeting thereafter.  However,
any amemhM-.-nt. -urp .• u til.  or revision to a duly approved and liled master plan \vhich
is made  cftcc.tr. '  ">>  I.A\  >i by  original  action of tire qualiu  hoard sluil  not be subject
to  the notice  ret; li e:>u n ;• of  Subsection  (f) of this section.
            (h)   1:;-. :i I •!-native vote of at least a majority or" .ill the directors is required
for  the  approv.,1  o;  ;!><.  -luster plan, amendment, supplement, or. revision.
            (i)    At:cr t.ie master  plan  has  been tiled \vitit and 'approved by the quality
board, a copyo.  siv p':.n of  any  waste disposal system or water pollution abatement
proposal, or o! ';:ii.' ivqiu-sr tor permit  or authority  submitted to the quality  board, to
be  operative  wi'iun  the   district,  not  now  or  hereafter exempted  by  law  from  the
requirement  for  .1.o. i.ri.'ig  .1 permit, shall  be submitted in such  form  as the authority
shall require to  -h*  ai'.thortty  at its principal office by  the  party making  the proposal
or request.   In c t^ • the proposed plan or request is one b>  law requiring action  by the
quality board, til-1 . i.tliority shall have the right to present its viesvs and recommendations
to  the quaht\ h->:rt  and receive notice  of any  hearings conducted by  it  in  the matter.
Should the  propt-s <.!  plan  or request he  one  not requiring by  law action  by the quality
board, then the ..u hori'ty shall  hold a hearing at  which  the  proponents of the proposed
plan  or  request  in i\  pivsent  their  evidence  and  recommendations.
            Ij")     ri:e authority' -.hall approve such proposal requiring only  its action, if
it finds  such  proposal  Compatible  with the  authority's  master plan: final  approval  or
disapproval  slut!!  issue from the authority within °0 days after receipt of  a cop>  of such
proposal  or request.
            (k)   If approved.  Mich proposal or request shall be  incorporated into  the
master plan.

                         Regulation  of  solid  waste  disposal

            See.  3.11.  (a) The authority shall establish minimum standards-of operation
for  all aspects of solid  waste h.indling,  including but not  limited  to  storage, collection,
incineration, sanitary  landfill,  or composting.    Before establishing such  standards,  the
authority shall:
            (1)   hold  public hearings after  having  given  public notice in the time and
manner  prescribed by  the  rules of  the  board; .
            (2)   consult  with  the quality board, the Texas Air Control  Board, and  the.
Texas State Department of Health to insure  that the standards are not inconsistent with
established criteria:  and
            (3)   find that the standards are  reasonably necessary for protection of public
health or welfare from  water pollution  or other environmental  harm.
            (b)   To  amend standards,  the authority shall follow the  same procedures
required  for establishing standards.
            (c)    The authority may make rules  reasonably necessary  to 'implement solid
waste  disposal  standards.   These  rules may  include  issuance and  revocation of  permits
for operation of solid waste disposal sites and  other aspects  of solid  waste  handling.

                                    Septic tanks

            Sec.  3.12.   (a) If it  finds that  because of the  nature  of the soil or drainage
in the area  it  is neccessary to  prevent  water pollution  that  ma>  directly or  indirectly
injure the public  health, the authority  by rule  may

-------
            (1)   provide limits  on the-number and kind of septic tanks In any  area
defined in  the  rule;
            (2)   forbid the use of septic tanks  in  the area; or   -
            (3)   forbid the installation of  new septic tanks in the area.
            (b)   The  board shall  consult with  the-  Texas State Department of Health
and the quality board prior to the adoption of a'rule under Subsection (a) of this section.
            (c)   The  board  may  provide in the order for a gradual and  systematic
reduction of  the  number or kind,  of septic  tanks in-the area and  may  by rule provide
for a system  of licensing and issuing permits for the installation of new septic 'tanks in
the area affected, in which event no person  may install septic tanks in the area without
a license  or permit from the board.   ,
            (d)   The  board may  not  issue a rule under Subsection (a) of this section
without  first  holding a public, hearing  in  the  area to  be affected  by the  rule.

                         Disposal of waste from  \vatercraft                  :

            Sec. 3.13.   (a)  The  authority may enforce  within  the district the rules of
any agency of the  State  of  Texas concerning the disposal  of waste from v/atercraft.
            (b)   It also  may  make and enforce- its own  rules concerning the disposal
of waste  from watercraft. after public  hearing  and  finding that such rules are  reasonably
necessary to'minimize  water pollution.

            Acquisition,  construction,  and operation of  disposal systems


            Sec. 3.14.  (a) The authority                                «
            (1)   may  acquire and provide by purchase, gift or lease any disposal systems
within or outside the district;           i      •
            (2.)   may;"' construct and  provide disposal  systems \vithin  or outside   the
district;  ;          ,'''"•,'.'"     •
            (3)  'may'  operate and  sell any disposal systems "that  it constructs or acquires;
           .(4)   may  contract with any  person  to  operate  and maintain  any  disposal
system belonging  to the'person;'and
            (5)   may  contract with any  person  to  train or supervise  employees  of a
disposal system.                                                                 ,.

                              Waste disposal-contracts

            Sec. 3.15.   (a)  The  authority may contract  to receive  and treat  or dispose
of  wastes  from any person  in  the district.
            (b)   In contracts  under Subsection (a)  of this section, the authority shall
set  fees  on the basis of  '                                     .
            (1)   the quality  of the .waste;                                    ''••'.-"''
            (2)   the quantity of  the waste;
            (3)   the difficulty encountered in treating  or disposing of  the  waste;
                                            75

-------
(4)
operation. and inaii-1 -innn. .•
any  oilu i^ reason, •! I
                                             e%p:nses and debt retirement  services: and
                           Sale of ua;er nnO by-products

            Sec. 3.1(i.  'I Ji.; authority n .iv store .uul >•!!. water that it collects under Section
3.15 of this Act!  and ni.:\ furni-.li  \\ iler ot a specified quality.  It aisv  may  store and
sell any hy-prodiiet  from  iN -operation..

                    Permits from  Texas  wnu-r rights commission

            Sec. 3.17.   (a)  Io:  the  pnrpo->c  of . maintaining establishes water quality
standards in the hays  and esman-.s v.it'.'n   'he district,  .the. authority may apply to 'the
Texas  Water Rights  Commission for v.:rs.V  . ij-pn. pi ialion  permits.
            (h)   The authority :n.i\   i\  | 'j.  K>:  water storage  or use petniits from the
Texas  Water Rights Commission, to stoiV snJ ^-il \\ater under the proviMons  of Section
3.16 of this Act.                          "

                                  Hninent  domain

            Sec. 3. IS.  The authorii\ trj;  acquire property of any kind  within or outside
the district, appropriate for the exercise <>!' its function^ through the exercise of tiie power
of eminent domain under the pnnKions c!' Title 52, Revised Civil Statutes of Texas. \l>25,
as now  or  later amended.

                               Relocation of fncilitie.%
                                          •                      ,

            Sec. 3.19.   In the event  that  the authority,  in the exercise of  the power
of eminent domain  or power  oi  relocation, or  any  oilier power,  makes necessary the
relocation, raising,  rerouting or changing  the grade of or altering the construction of any
highway, railroad, electric tran>mission line, telephone  or te'euraph properties and facilities.
or pipelines, all such necessary relocation, raising, rerouting,  change  in grade or alteration
of construction, slul!  be accomplice. I at lii.' -sole  c\;vi-.e  of the authority.   The  term
"sole expense" shall mean the actual cost  of such relocation, raising. lerouting. char.ge
in grade ur alteration of grade or construction in providing comparable replacement without
any enhancement of siuh. facilities, .at-cr deducting therefrom the net salvage  value derived.
from the old  facility.                                                                .

                               Use nf public .easements

            Sec. 3. JO.  The -authority  shall Have tl'.e rigiit, power,  and  authority to use
any  and all public roadways,  sire. t.s. alless. or  public  easements within or outside the
district in the accomplishment of ii-. purposes, without the necessity of securing a franchise.

                       Acquisition and disposition of property

            Sec. 3.21.  ia) 'Ihe authority may purchase, lease, acquire by gift, maintain.
use. and operate property of  any kind  appropriate  for the exercise ot  irs functions.
                                           76

-------
            (h)    S:.k-s of  property not authbri/ed by  any other provision  of this Act
are hereby authuri/.cd. subject to the following limitations:  (1) 1 he board, by affirmative
vote of seven din. cu-rs. Shall determine that the property is not needed by the authority:
(2) sales shall iv :>\  .•ompetitive  bidding  if ihe value of  the  property as appra>ed by.-
the board exceed-.  SHUK.'O. (3)  notice of the propoed sale sliAH be published once each
week for  three (.oi.^t'-.i!i\c weeks in a  newspaper having general circulation in t'ne county
or counties in winch  t!u- property is  situated if the value of the  property  as appraised
by  the  board exceed-*  S2.000:  (4") the specific terms of the  sale--.shall be approved by
the board, an affirmative vote of seven directors being required for  this purpose/unless
the value  of the  property  as appraised  by the board is $2.000 or less, in'which; event
the board  by iit'l n utive  vote  of seven directors  may authori/e the general  manager to
sell on  such tern^  .is he deems advisable.

                                      Facilities

            Sec.  .i.r.2.  The authority may acquire in any lawful manner, construct, extend.
improve, maintain, reconstruct,  .use, and operate any facilities necessary or convenient to
the exercise of its  po\\ers.  riglu*.  duties, and  functions.

                                 Contracts  generally                  •-•...-

            Sec.  3.23.  (a)  The authority  may make contracts and execute instruments
that are necessary or convenient to  the exercise of its powers, rights, duties, and functions.
A contract may.be  for  any  term  not to exceed  50 years.
            (b'l   Any construction or repair contract,  or contract  for the  purchase of
material, equipment or supplies,  or any contract for services (other than technical, scientific:"
legal, fiscal or other professional services) shall  be  awarded to the lowest and best bidder
therefor,  after publication  of a notice to bidders  once  each week for  three,consecutive
weeks before the dale set  for awarding the contract,  if the contract will require an estimated
expenditure of more  than ,510.000, or if  the contract  is  for a term of more than  two
years.  In the event of an emergency, the authority may let such contracts as are necessary
to  protect and preserve the public  health and  welfare or the properties of the authority.
without such bidding procedures:
            (c)   The notice is sufficient if it states the  time and place, when and where
the bids  will be opened, the general  nature  of the work to  be done, or  the"-material,
equipment, or supplies to  be purchased,  or the nonprofessional services to be;rendered.
and states  the terms  upon  which  copies of the plans, specifications, or other  pertinent
information may be obtained.                                                •
            (d) •  Publication  of  the  notice shall be   in  a  newspaper  having  general
circulation  in the county  or counties in which..the contract is uThe performed.  In addition
to publishing notice in a newspaper 'having general circulation, the notice may  aNu be
published  in any other appropriate publication.                               ,
            (e)   Anyone  desiring to  bid  on the construction  of any  work advertised as
herein  provided, shall, upon written application to the board,  be furnished with  a  copy
of the  plans and specifications  or other engineering and architectural documents showing
                                            77

-------
  the work  to  bo done, and all the details thereof, providing that a charge may be made
  therefor to cover  the  cost of making such copy.   All bids to do any such work: shall
  be in writing, and sealed and delivered to the board, and shall be accompanied by a certified
  check upon sonic responsible bank  in the State of Texas or a bid bond from a company
  approved by the board, for at least  one  percent of the total amount bid, and"the amount
  of said check  or bond shall  be forfeited to the authority  in  the'event such successful
  bidder shall fail or refuse  to enter into  a proper contract therefor, or shall fail or refuse
  to furnish bond therefor  as required by law.   Any or all bids may  be rejected  by the
  board.
             (0    Bids shall be opened  at the  place specified in  the published notice and
  shall be announced by the board.   The  place where  the bids are opened and announced
  shall always  be open to the  public.                                            .• .  I
             (g)    The  contract price  of all construction contracts of the authority may
  be made in partial payment as the  work progresses,  but such  payments shall not  exceed
  90 percent of the amount due  at  the  time of such payment as shown  by the report
  of the general manager of the district.  The board shall at all times during the progress
  of the work, inspect  the same or cause  the same to be inspected by the general manager
  or his assistants, and upon  the completion of any contract in  accordance with such terms,
  they shall  pay the balance due  thereon.
            (h)    The  person, firm* or corporation  to whom  such contract is let shall
 provide such performance  "and payment  bonds'as are required  by law.   •
            (i)    The,  provisions of  this  section do not prohibit the authority from
 purchasing surplus property from the  United States by negotiated contract and without
 necessity for advertising bids.                    .      •
            (j)    An  officer, agent,  or  employee of the authority  who is-financially
 interested  in  a contract of the types  enumerated in  Subsection  (b) of this section shall
 disclose that fact to the board before the board votes on the acceptance of the contract.
            (k)    Notwithstanding any  provision of any charter of any city  or town,
 contracts between the authority  and  any city or town need  not be submitted to  the
 electorate.

                              Cooperative agreements

            Sec. 3.24.  The authority  may enter into cooperative agreements with other
 local governments, state agencies, or agencies of  the  United  States of America
            (1)   to perform  water  quality and waste disposal management, inspection,
 and enforcement  functions and give technical  aid and education services to any  entity
 that is  a  party to the agreement: and
           • (2)   to transfer money or  property  to  any entity  that  is a  party to the
 cooperative agreement for the  purpose of water quality and waste disposal, management,
 inspection,  enforcement, and technical aid and  education.

                   Hearings Concerning  Groundwnter Withdrawal

            Sec.  3.25.  (a)  The authority is hereby authorized  to work in cooperation
with and lend assistance  to. any permanent standing committee  or interim study committee
                                             78

-------
authorized by the Legislature of  the Stats of Texas,  or the Coastal and Marine Affairs
Covmc\i.  and to expend any money  specifically appropriated  by the legislature to the
authority, or money  appropriated specifically to the Texas Water Quality Board or any
other state  agency for a  contractual arrangement  between such state  agency and the
authority, for the first phase of a subsidence control  program for Harris and  Galveston,
Counties.  Such program is  intended  to  develop regional information relating to water
demand,   present  and future,  surface  water supply  sources,  present and future,  and
groundwater pumping zones, and to prepare methods  to redistribute water in the future.
The authority is specifically authorized to cooperate with  and  contract with the United;-
States Geological.  Survey and any  other  federal or  state agencies concerning the results
of  such  program.  It is specifically provided that the  authority shall not be required to
expend any of its funds fur the purpose specified in  this section unless such  funds are
specifically appropriated by the legislature or specifically designated for such purpose from
contractual arrangements.                                      .
               SUBCHAPTER 4.   GENERAL FISCAL PROVISIONS
                               *            ,  -              •              • "
                              Disbursement of funds

            Section  4.01.   The authority's money  is disbursable only by  check, draft,
order,  or other instrument, signed  by the person  or persons authorized to  do  so in  the
board's bylaws, or by resolution of the  board.


                                Fees and charges

            Sec. 4.02.  The authority shall establish fees and charges which may not be
higher than necessary to fulfill the obligations imposed on it  by this Act.


                                Loans,and grants

            Sec. 4.03.  (a) The authority  may borrow money for its  corporate purposes.
            .(b)   The  authority may  borrow money  and  accept grants  from private
sources,  the United States of  America, the state, and local governments.  The  authority
may enter into any agreement in connection with the loan or grant which is not in conflict
with the  constitution and laws of  this state.
            (c)   The sources of any  funds accepted  by the authority  shall  be public
information, both as  to amount and  any restrictions  placed  by the  donor  on their
expenditure.                '•                •
                                           79

-------
                      Fiscal  year and audit by state auditor
                                                                             i    ,
            Sec. 4.04.  (a) The authority's fiscal year shall be established by the board.
            (b)    The board shall keep separate books and accounts of all money received
from the State of Texas, and the state auditor shall audit annually such books and accounts
in a manner enabling him  to report  to the Legislature the manner  and purpose of the
expenditure of the .authority's money received from the state during each fiscal year.

                              State  auditor's  report

            Sec. 4.05.  (a) The state  auditor shall make  a  report of his audit promptly.
            (b)    The state auditor shall  file  a copy of the  report with the governor,
the quality board, the commissioners court of each county in the district, and as may
otherwise be provided by law.

                           Cost  of state  auditor's audit

            Sec. 4.06.  (a) After  completing the report required by  Section 4.05 of this
Act, the state auditor shall prepare a  detailed statement  showing the actual cost of the
audit  and  certify  the statement  to the authority  for payment.
            (b)    Upon receipt of the  statement, the authority shall pay the state treasurer
the cost of the audit.
            (c)    The state treasurer shall  credit the payment to the general revenue fund.

                                 Independent  audit

            Sec. 4.07.  (a) The authority  shall  keep  a complete system of accounts  and
an audit of its affairs (except as  provided in Section 4.04(b) above) for each  year shall
be prepared  by an  independent  certified  public accountant, or a firm of independent
certified public accountants,  of recognized  integrity  and ability selected  by the board.
The cost  of said  audit shall  be  paid  by  the authority.                             ,
            (b)    The authority  shall file  copies of  the  independent audit with  the
Governor of the State of Texas,  the quality board, and the commissioners court of each
county  in  the district; and the board  shall keep at least one copy of such audit at the
office of  the  district open to inspection by any  interested person during normal  office
hours.

                                 Depository banks

            Sec. 4.0N. (a) The board shall  designate one or more banks within the district
to serve as depository for the funds of the authority. All funds uf the authority shall
be deposited in such depository bank or banks except that bond proceeds and funds pledged
to pay  bonds may,  to the extent provided in  a trust indenture, be deposited  with  the
trustee  bank named in the tru->t  indenture, and except that  funds shall be remitted to
the bank  of payment for the payment of principal  of and mtere.st on bonds.  To  the
                                           60

-------
            t'l)   frind-  ^ccured by  ad valorem  taxes:
            (2)   bos d-.  .secured'.by  a  pledge of  all or part of the revenues accruing to
the  authority, in--U ,!-ng  without limitation  those received from- sale of  water or other
products, :reru!itu n  i f si rvice, tolls,  charges, and from  all  other sources other than  ac!
valorem  luxe*:
            (.} •   horn's •••ecured by a combination pledge of all  or part of the revenues
described in $;..! UIVM >;  (2) of this  subsection,  and  t.txe.-..
            (b) '  Sin.ii i-onds  shall be authori/.cd by  resolution of the board and shall
be issued in tin  name of the authority, signed by  the chairman  or \ice-chairman, attested
by  the secretary a ul shall  bear tiie .seal of the  authority.  It is provided,  however, that
the  signatures  i'I:  he chairman, the  vice-chairman or  of the secretary or of  both may
be printed, or  Iiiii (graphed  on  the bonds if authori/ed by the board, and  that the seal
of the authont>  ,ni\ be impressed on  the bonds or may be printed or lithographed thereon.
The  bonds  shall  be in such form  as shall  be  prescribed b>  the  board, shall  be in such
denomination or. denominations, shall  mature  serially  or.otherwise in not to exceed  50
years from  .tru-ii  -Lie. shall  bear  such  interest,  and may be sold  at a price and  under
terms determined bv the board to  be the most advantageous reasonably obtainable, and
within the discretion of the board, may be made  callable, prior  to maturity at such times
and  prices as may be preseribed.in the bonds, and  may  be made  registrable as to principal
or a-; to hot!; princip.il and interest. Such bonds may  be further secured by an indenture
of trust  with a  corporate  trustee.                   :             -          -
            (c)   Ho ids  may be issued in more than one series, and from time to time.
as required  for carr>irg out the purposes of this Act.  Any pledge of revenues may reserve
the right, under  conditions therein  specified, to issue  additional bonds  which will  be on
a parity  with.  <>r  be secured  by a lien  senior to or subordinate to the  bonds then being
issued,           •              '                                              -.-"'•
            (d)   The  resolution  authorizing the  bonds or the  trust indenture further
securing  such bonds ma\  specify additional provisions which shall  constitute a contract
between  the authority and its bondholders. The  board shall have full discretion in providing
for such additional provisions including the authority  to provide  for a corporate tru>iee
or receiver  to  take  possession  of  facilities  of  the authority  in  the'event  of default on
the part  of the  authority in  fulfilling  the  covenants  rheiein made.

                                  Refunding bunds

            Sec. 5.02. The authority is authorized  to issue refunding bonds for the purpose
of refur.ding any outstanding bonds authori/.ed  by this Act and  interest thereon.  Such
refunding bonds  max  be issued to  refund one  or more series of outstanding  bonds and
combine the pledges  for the outstanding bonds  for the security  of the  refunding bonds.
and  may  be secured by  other or additional revenues.  The provisions  of this law with
reference to the issuance by  the authority of other  bonds, their security* and their approval
by the attorney general and the remedies of the  holders shall be  applicable to refunding
bonds.   Refunding  bonds  shall he registered  by tiie comptroller upon  surrender and
cancellation of the bonds to  be refunded, but in  lieu  thereof, the resolution authori/ing
their  issuance may provide  that they shall be sold and  the  proceeds thereof deposited
                                           81

-------
 in  the  bank  wh-%r.' the original- bonds are payable, in which, case  tiie  refunding bonds
 may be issued in :-r- a.n>'ii:u  suilicienl to pav  the princip.il  i»i" and the interest on the
 original  bonds  to !H.'ir ro-ion  date or maMriU  date, and tlk comptroller siiall' register
 them without ton  i-ru- -i surrender and'cancellation of the  original bonds.

                          \pprovai  nnd registration of bonds

            Set.-xO.v  .vl'tcr  any bonds  (including rcl'uiKling bonds) are authori/ed by
 the  authority.  %iu'h  ho-id-. .ind the record relating  to their  issuance shall be submitted
 to  the  attorney  :e:ieral  tor  his  examination as to  the validity thereof.  If Mich bonds
 recite that thev  :r.- se -ured  by a pledge of the  proceeds of a contract  theretofore nude
 between the, authority und ::«iy city or other governmental agency,  authority or district.
 a copy of such  vntract and the proceedings of the city or other governmental agency,
 authority or  dis-n.-t aullu-n/ing such contract shall  also be  submitted to the attorney
 general.   If he  rind- that  such  bonds have  been authon/ed and such contracts have been
 made in accordant.  v\ith the  Constitution and laws of the State of Texas, he shall approve
 the  bonds and si.ch contracts and  the bonds then .shall be registered by the comptroller
 of  public account-.   Thereafter the bonds, and  the contracts, if any. shall be valid  and
 binding and shall be  incontestable for any cause.

                                   Bond election

            Sec. 5.04.  \o bonds payable wholly or partially from ad valorem taxes (except
 refunding bonds) -h.ill.be issued unless authori/.cd by an election at which only the qualified
 property  tax-paying voters of  the  district  may vote and unless a majority of the votes
 cast in  such election  is in favor of  the  issuance of the bonds.   Refunding bonds  and
 bonds not pit\able wholly or partially from ad valorem taxes  may be issued  \\ithoutan
 election.  Such elections  shall  be held  in  accordance with  the provisions hereinafter set
 forth governing ad  valorem  tax  elections.

                                  Maintenance  tax

            Sec. 5.05.  The  board shall have the powei  to levy and collect ad  valorem
 taxes for the maintenance of  the  authority and  its improvements,  in  such amounts as
 are  voted  in  accordance  with   the procedure hereinafter  set  forth; provided  that  the
 maintenance tax shall  not exceed  the  maximum rate  voted,  and said  rate shall  remain
 in effect until  or  unless changed by subsequent vote, and that in no event shall the tax
 rate exceed the limit specified  in  Section  5.0s of this Act.

                                      Election

            Sec. 5.0').  No such maintenance tax shall he levied or collected and no bonds
 payable \vhol!y or partially  from  ad  valorem  taxes shall be issued  unless  an election is
held in the district and any such taxes or bonds are duly and favorably voted by a majority
of the qualified property  taxpaying voters  of  the district,  voting at  the election,  t'ach

-------
polling' pi. icev  i:u
election shall. 'i. ;!)
in a newspaper of
with  ihc ;int,T\ il
 such election  ->!;:il! he  c.iMvd  h\  i ebullition  of the board.  The election resolution  shall
 set '.forth  lljie  d.iK- . rf  i -v  .-'s-vlion.  !he proposition to  be  submitted and  voted o,n. the
                      t> < t;u-i  matters  deemed a.Msahlc by  the  board.  Notice of said
                     :? b. :% fl-Mslim;: a substantial copy of the resolution calling the election
                     r'.-i i! •-.  i .-nl.iti.in m  the district not lev. than twice in such news-paper,
                     ' .v. .. i  v.u-h pu!>ii-vJio.ns, to be at least  one week, and  with the first
 of each  of said  p. i' !>,:—> MS to 'be nt ieas't <>0 days prior to the date set for the' election.
 To the .extent ;u t iiv.i-r-i-i-.-nt \\itii the provisions hereof,  the  elections. Herein  provided
 for  shall be held  PI  :;,o>:d.!nee 'with  the provisions  of the  Texas Election Code.

         Rendition, assessment, equalisation.  levying, and collection of taxes •

            Sec.  i-(-1-   The  rendition and  assessment of property for  taxation,  the
 equalisation o! -?.i!.us.  and  the collection of taxes for the benefit  of the authority shall
 be in  accord:! IK „•  \vi!l- the  I iw. applicable to counties, insofar as  such  law can  be  rriade
 applicable,  and cx.x.n  a.s IK rcinafter specifically  provided.    The  board may act as  the
 board  of equali/af ••».-  for the  authority, or  may appoint a separate board of equalization
 to consist  of fi\e  :oMikm.  qualified  \pters who own  taxable property in the district.   In
 either  case, the bond of cquali/ation. shall ha\e the powers. -functions, and duties of the
 commissioners yourU •-)!' ciHinfi.es»in equa!i/.ing property values in accordance with law
 applicable  to counties. ns.>i':iras such laws can be made applicable. .It is provided, however.-"
 that renditions -hail  be nntdc  to t!ie county  tax assessor and  collector  of  the county in
 which  the  proper! >  r  located and the  tax  assessor  and  collector  of  each, .county,
 respectively, shall :» -i j^ t've  tax assessor and collector for the authority for property located
 in such  count}.   It. -.lull be the duty  of the tax assessor and - 'collector in, each county
 to cause to be  pkued  on. ihe county  tax rolls, such additional  column or columns as  are
 needed to  show Hu'  taxes levied by  the authority  and the amount thereof, based on  the
value of sii.eh.pi-op.-r.ty  as .i.ppnned finally by the  authority's board, of equalization.  .The .'
 fee of eacli  count \  tax assessor and collector for  assessing  and co,ile'ctinsi  taxes shall Ibe
one  percent  of the t.ixes collected. snchTee to be  paid over and  disbursed in each county
as are  other fees  i-f  ;)fflce.  All o!' the  laws  for the /enforcement of , state and county
 taxes_ .shiill  be  avail ll-:o to  the authority.  The authority shall have the right to cause
 the office! < of each lountx  to enforce and collect. the taxes due to ' tho1 authority, in that
county,  .!-.  provided  m the  law for  the •.enforcement  of state and  county  taxes. Taxes
assessed  a:ul levied ' Mr the  benefit  of  the authority shall be payable and  shall become
delinqiier:t at the vinie  time. in. the same manner, and subject to  the same discount  for ;.-..
advance  paynvnt as taxes levied by and I'or the benefit of the county in which the property
is  taxable   'Ihe fee  for cullectini:. delinquent  taxes throuyh  prosecution of suit  shall  be
 I>  percent ot  the- taxes collected  by such suit, such  fee to be  paid over and disbursed
in each county as  arc other fees ot oiYice.  Concurrently "'with' the levy  of  county taxes
by the commissioners courts,  the  board  shall levy the tax on  all taxable property in the
district which  i> .subix-ct to  such taxation and shall immediately certify  such  tax rate to
the tax  assessor and  collector of the counties  comprising the authority/    /

                                     Tax limit

            Sec. 5.()x.   HH; maximum  rate  of .tax which  may be levied  by the board
in any fiscal year for all purposes, oilier than  taxes levied pursuant  to Section 0.05, shall
not exceed ten cents (lUc) on each SI 00 of assessed; valuation of taxable  property.
                                            83

-------
                           Bonds authorized  investments

            Sec.  v')1''   Al! bonds and refunding "bonds  of the authorilv shall be and are
hereby declared '«• lc  1-gil. eligible and  authori/cd  investments for banks: savings and
loan associations  'n^iunce companies;  fiduciaries; trustee*: the sinking hinds oi  cities.
towns, villages. CIH iilie-. •>• boo! districts, or an> other political corporations or stibdnisions
of the State of -lex.iN   ;:u!  for  all  public funds of tlu-  State of Texas or its agencies.
including  the  St'ife Permanent School Fund.  Such bond.-, and refunding  bonds shall be
eligible to secure  the  deposit of any  and all public funds of  the  State of Texas, cities,
towns, villages,  .visnties, school  districts,  or other political corporations  or subdiviMons.
of the State of Texas: and  such bonds shall be  lav/ful and sufficient security for said
deposits to  the e>Unt of their face value, when accompanied  by all unmatured coupons
appurtenant thereto.

             SUBCHAPTER 6  - POLLUTION CONTROL DISTRICTS

            Section KOI.  The  authority  may establish one or more "Pollution Control
Districts"  for  the  purpose of accomplishing any of the powers, purposes, rights, privileges
or authority vested  in  the authority.            .

                             Establishment of districts

            Sec. M52.  (a) Pollution  Control  Districts may be established by the procedures
contained in this  Section.
            (I.)   The board may adopt a  resolution calling for the creation of a Pollution
Control District,  definiti" the boundaries thereof, estimating the principal  amount  of and
stating the  purpose  of bonds proposed to  be issued by  the authority on behalf  of the
proposed  Pollution Control District,  declaring that  taxes for the payment of the proposed
bonded l.iclebtcJ.-.css shall be  levied-exclusively  upon  the taxable  property within  the
proposed  Pollution Control District, and  fixing a time and place for a public  hearing on
the matters set out in the resolution; or
            (2)   The board may adopt a  resolution calling for the creation of a Pollution
Control District, defining the boundaries thereof, declaring that taxes for the maintenance,
of the authority and its improvements shall be levied upon the taxable property  within
the proposed Pollution Control  District, and fixing'a  time and place for a public hearing
on  the  matters set out in the  resolution.
            (b)   The  resolutions  authorized by Section  6.02(a)  may  be  adopted
simultaneously and simultaneous hearings  on proposed  bond and maintenance taxes may
be held.                             "                            ,
            fc)   The  public hearing  may  be conducted by a quorum of the board of
directors,  or one  or more directors, or  one or more  employees who may be  designated
by  the board.   If someone other than a quorum of the board -conducts  the hearing, he
shall  have posver to accept evidence and  make recommendations upon Which the  board
may act.  The board may alter,  modify or change any  pro\ision of the resolution  calling
for the creation of the proposed Pollution Control District subsetiucrst to the public hearing:
                                             84

-------
 provided,  however,  t;i;.t  the boundaries of  the  Pollution  Control  District may not be
 enlarged or  expand-.1*;  without  further notice .is hereinafter  provided.
             (d) .   Ncticc of the public hearing shall be published in a newspaper of general
 circulation-within  fie  proposed I'oilution  Control District once not  less than fifteen (IS)
 nor more than th-ny (  »0-.' days prior to the public hearing.  To the extent not inconsistent
 with the provisit-a-.  lu :\ .it.  notice  of the  public hearing  shall also comply with Article
 6252-17. VernonV  'ie\a> Civil  Statutes, as amended.
             fe.)   ;AI1 public hearings on creation of a Pollution Control District shall be
 held within  the  boundaries  cif the  propo.iecl  Pollution Control District,  and may  be held'
 concurrently, or in  connection  with any  other public hearing,  meeting  or  proceeding
 conducted by tin  ncard.
             (F)   Any  interested  person,  including persons residing or owning property
 within the authority, may appear at the public  hearing and,present evidence  relevant to
 the  matters  set tor!h in  the resolution calling for the creation of the proposed  Pollution
 Control  District   \!1  persons residing within or owning  property  within the  proposed
 Pollution Control Di-trict shall  have the right to  appear at the public hearing and  .present
 evidence with regard to whether they will receive benefits from the proposed improvements
 or  taxation.   Failure  to appear at the public  hearing shall  constitute a waiver of all
 objections which the .absent part-y might hau- had to all matters set forth in the resolution
 calling for the  creation  ol  -the  proposed  Pollution  Control District.
             (g)   1 he board shall reuew .the findings and recommendations resulting from
 the  public hearing, and  may adopt  a resolution creating  the  Pollution Control  District,
stating the purposes for which the Pollution Control  District has been created,  designating'
 the  boundaries ot  the Pollution-Control  District, declaring that  the  indebtedness to be
incurred or  the  cost of services to be rendered  by  the authority for the benefit of the
Pollution Control  District  shall  be  payable from taxes le\ led upon property within the
Pollution Control District, finding  thai the property within the Pollution Control  District
will benefit  from "the  indebtedness proposed to  be  incurred or the services proposed to
be rendered  by  the authority on us behalf, and. calling'for an election within the. Pollution
Control District to authorize said indebtedness and/or said maintenance tax.  Said resolution
shall further state  the  date of the  election, the  proposition or propositions to  be voted
on,  the location of the polling places, and  the names ,of the officers  of the election.  Said
election  may be held in'Conjunction with a general  election, or any  special election other
than a  primary  election.   The  provisioiis  of the Texas- Llection Code shall  govern the
election  unless  contrary  to any provision of this Act.
             (h)   The  resolution of  the board creating a Pollution  Control District shall
be  final  and conclusive, and  shall  not be  subject  to -'review by  any  court except upon
the basis of  whether the resolution is supported  by  substantial evidence.  Said resolution
shall be  filed in  the  deed records of the county  or .-counties wherein the territory within
the Pollution Control District is situated.  Any action or proceeding wherein the validity
of the board's resolution  creating a  Pollution Control District or of the proceedings  relative
thereto  is  contested, questioned or denied, shall  be commenced within thiny (30) days
from the effective date of  the resolution: otherwise, said  resolution and  all  proceedings
relative  thereto,  including the creation of  the  Pollution Control District, shall  be held
to be valid  and in  every respect  legal and  incontestable.
                                           85

-------
                        Boundaries and addition of territory

            Sec. ••>  );.  '':••) The boundaries •>!  a Pollution Control District  may  include
any territory  within ti-c authority.-whether  or  not  the  u-rritoi-y contains non-contiguous
parcels of land. a:rd xvhiti-.cr or not the terriiorv is located within the boundaries of any
incorporated vs!/. town, village, or any other governmental entity or political subdivision
of  the State of T.exas.  it any portion of the territory  i.f a  proposed Pollution  Control^
District falls \\iil\ni the boundaries 01  within the exclusive .extraterritorial jurisdiction of
an  incorporated uiv. town or village, the  board shall not create said Pollution  Control
District until  it has obtained the consent of said city, town or village.  Said  consent may
contain such  co'un.ion-; as may be mutually agreed  upon by the authority and said c;iy.
town  or village, .n.d  shall be evidenced  by  a  duly enacted  ordinance of the governing,
body  of said cit>.  town  or  village.
            (b)   Proceedings  for  the annexation  of  territory  to  an existing  Pollution
Control District h.:y be  initiated by  a  resolution of the board, or by a  petition signed
by the owners of ^0"' or more of  the  value of the land subject to  tho proceedings, or
by a  petition  signvd  by  a majority of the residents of  the  land  to  be  annexed.  The-,
petition shall, insotar as is practicable, set  forth substantially those mailers, set forth in
a  resolution calling for the creation of a Pollution Control  District, and  shall  request,  a
public hearing..by the board  on the matters set  out in  the petition.  The public hearing
shall be held in substantial compliance with the provisions set forth herein  for a-public;
hearing on creation of a  Pollution  Control  District.  If the board determines that  the
annexation should  be accomplished, it may adopt a resolution  catling separate elections
on the matter  of annexation to  be  held within the existing  Pollution Control  District
and within the  land to be  annexed.  The annexation shall not become final until approved
by a  majority of the qualified voters  within the existing Pollution Control  District:  and
until a majority of the qualified voters  within  the  boundaries of the land to be annexed'
approve said annexation  and  elect to  allow the land to be annexed  to be taxed  for
maintenance  purposes and/or to assume its  pro rata share  of  indebtedness- theretofore
authorized and/or tuxes necessar\ to support the voted  but  unissued  tax or tax-revenue
bonds of  the authority which are to be issued on behalf of the existing Pollution  Control
District, and  authori/.e the board  to levy a  tax on  the  ptoperty therein for payment for
such unissued bonds, when  issued.   Said elections shall conform to the  Texas 'election
Code, insofar as said Code is  not inconsistent with the provisions of this Act. The board's.
resolution canvassing  the  return.-  of such elections  shall redefine the boundaries of the
Pollution  Control District and  shall  be recorded in the deed records of the county within
which  the annexed territory lies.                        .
            fc)   Proceedings for the  addition of territory to  an existing Pollution Control
District on which kss than three (3) qualified voters reside mav  be  initiated  by a "petition
signed by the owner  or owners thereof praying that die land described  therein he added
thereto and become  a  part  thereof.  The petition  shall,  insofar as applicable set forth
substantially  those  matters set  forth in a resolution calling for the creation of a Pollution
Control District and shall request a public hearing  bv  the board on  the matters set  out
tn  tho petition. The public hearing .shall be held in subsiasitia! compliance with provisions
set forth herein for a public hearing on "creation of a  Pollution Control  District. . If tho
board determines that the addition should  be  accomplished, it may adopt a resolution
adding such land.   If taxes or bonds  have been aulhori/ed  within the  Pollution Control
District prior to the addition of said land, said resolution adding the land shall be temporary
and the addition shall  not become final until  approved  by a majority  of the  qualified
voters within tho Pollution Control  Di.strict as  it exists after said addition.  Such election-
shall  be held as soon as  practicable after said  addition  cm the proposition of approving
said addition, unifying tin- unissued tax  or lax-re-.cm:e bonds of tho authority which are
to  hi- !<>.-i.«.l
K.-
                        f:>..,.,.t iv,

-------
levy a tax on the property .within-the. Pollution Control District as enlarged for payment
of said unissued  bonds when issued and/or  for the maintenance of the authority.  Such
election  shall  conform to the Texas Election Code so far as such Code is not inconsistent
with  the provisions of this  Act.  The  board's resolution canvassing the returns of such
election  or adding the territory shall  redefine the boundaries  of the  Pollution Control
District and shall be  recorded in the deed records of the county within, which the added
territory lies.      .                              ,      ,                      ;  ....

                                     Taxation                              ,

          '  Sec.  6.04.  fa) If the qualified voters in the elections called pursuant to Section
6.02  and/or Section  6.03 authorize the authority  to incur indebtedness for the benefit
of a Pollution Control  District, the board shall have authority to. Issue bonds as'provided
in Subchapter 5 of this Act; provided, however, that taxes levied for the purpose of making
payments of  the interest on or principal of said bonds shall be levied only on taxable
property within  the  Pollution Control  District.
            (b)   Notwithstanding, any  provision of this Act  to the  contrary,  if the
qualified voters in the elections called pursuant to Section 6.02 or Section 6.03 authorize
the authority  to  levy and collect ad valorem  taxes for  the maintenance of the authority
and  its  improvements, the  board shall have authority to levy, assess and collect  said
maintenance tax as provided in Subchapter 5 of this Act; provided, however, that said
maintenance tax shall be levied only  on taxable property within the  Pollution Control
District.                                   .   - ';  '•...;.-   r    ,

                                Bonded -indebtedness

            Sec.  6.05.  The board may incur all such indebtedness as  may be necessary
to provide all  improvements, and  the maintenance  thereof, requisite to the achievement
of the purposes  for which any  Pollution Control District is organized,  and the authority
is authorized  to  levy and collect  all  such  taxes as may be necessary  for the payment
of the interest thereon and  the  creation of a sinking fund  for the payment thereof, and
such  taxes shall be a lien  upon  the  property assessed  for the  payment  thereof.       .

                            Annexation  by  Municipalities                 .           -

            Sec.  6.06.  If any city, town or village which has consented to the'-creatton
and boundaries of a Pollution Control  District as provided in Section 6.03(a)  of this Act
thereafter annexes any part  or  portion,  of  the  territory  within  such Pollution  Control
District,  the agreement referred  to in  said  Section 6.03fa)".shall be deemed to provide
and include the provisions of Chapter 128, Acts of the 50th Legislature,  1947, as amended
(Article  1182c-l, Vernon's  Texas Civil  Statutes),  or  Chapter  228, Acts  ol the :>6tn
Legislature,  1959, as amended (Article  1182c-5,  Vernon's Texas Civil Statutes), as may
be applicable  to  the  specific-district, and. any such annexing city, town or village shall
assume all or the proportionate part  of physio:.!  assets,  properties,  facilities, intangible
assets, bonded indebtedness.  li-.liHities. obligations and any  oilier debts of  the 1 ollutioa
Control  District  aft'octetl  by  such  annexation.
                                                 87

-------
                        CHEMICAL RESOURCES,  INC.

                             TULSA, OKLAHOMA
I.     INTRODUCTION
Chemical Resources, Inc., was incorporated in January of 1979.   It had
been operating as a commercial injection well for hazardous wastes under
the name of Lamberton Acid Well Disposal since 1973.

Since its opening, the site has experienced no organized public opposi-
tion to its hazardous waste disposal operation.  There are thousands of
similar waste brine injection wells in Oklahoma and three other indus-
trial, waste-generator owned disposal wells in the Tulsa area.   Local
residents have expressed no significant concern over the Lamberton well
apart from a few isolated complaints about odors.  The nearby oil re-
fineries are generally blamed for most odors in the area.  Public
opposition did surface briefly during the off-loading of an out-of-state
barge loaded with pesticide wastes en route to the Lamberton well.
However, the opposition was directed primarily at the barge and at the
possibility of accidental spills in the river if more such out-of-state
barges came to off-load their wastes in Tulsa.  Because of the lack of
public concern or opposition towards the Lamberton well there has been
no need to take specific steps to secure public support.

II.    BACKGROUND INFORMATION

The injection well is situated on a four-acre site within a 265-acre
parcel owned by the operator.  The entire area is zoned heavy indus-
trial.  The well site was formerly cattle grazing land.  Horses and
cattle are still periodically allowed to graze the area to keep the
grass down.                      •

The site is situated at the edge of an industrial area containing a
major railroad yard, two large oil refineries, several steel galvanizing
plants, a chemical plant, and a pipeline tank farm.  The immediate
neighbors of the well site are a commercial stable owned by the
Lamberton family, a chemical products firm making ink, and a steel
galvanizing plant.  One side of the well site is undeveloped land owned
by the operator and used for grazing and horseback riding.  On this side
is also a series of hills which separate the site from the nearest
residential area about one mile away.  The site is across the Arkansas
River and about three miles from downtown Tulsa.

The geology of the area is very suitable to injection well disposal.
The site overlies the Arbuckle formation, a limestone aquifer that
covers almost three quarters of Oklahoma and is approximately a quarter
of a mile thick.  At the site of the well the aquifer is approximately

-------
 2,100  feet below the surface and extends to 3,300 feet,  at which point
 the  bedrock formation begins.   This  aquifer is  well below the fresh
 water bearing  formations  which are generally tapped for drinking water
 at 20 to  60 feet  below the  surface.   The operator remembers that back in
 the  1930s  the  Arbuckle formation in  this area was tapped  for salt water
 from which commercial salts were manufactured.   However,  those opera-
 tions were soon stopped when it was  learned that the salt water was
 naturally  radioactive.

 The  site itself contains  an injection well, a pump, and three storage
 tanks to  temporarily hold wastes while balancing the volume of incoming
 waste streams  with the injection rate.   Also on the site  is a mobile
 trailer office.   The entire area is  surrounded  by a chain link fence.
.The  site appears  relatively clean and neat.  The adjacent undeveloped
 land contibutes to the favorable appearance of  the site.   The operator
 estimates  the  life of the site to be at least 500 years.   Private-
 injection  wells in the Tulsa area using the same limestone aquifer have
 been operating at much higher  injection rates for over 20 years with no
 noticeable decline in capacity.

 The  waste  disposal operation at the  facility is one of deep-well injec-
 tion.   The wastes are piped in directly from local steel  plants in the
 neighboring industrial area.   In addition,  the  facility receives wastes
 by tanker  trucks, rail tank ears and barges.  The-x>perator owns a short
 rail spur  several hundred yards  from the site which is connected by
 pipeline directly to the  well.   He also owns an off-loading fatcility at
 the  nearby Port of Catoosa.   His own small  fleet of tanker trucks serves
 the  barge  off-loading facility and several  local industri.es in the Tulsa
 area.   With the exception of the piped-in wastes and those delivered by
 his  own trucks, all wastes  arrive by commercial haulers or are trans-
 ported by  the  waste generator.

 The  wastes are sometimes  stored  temporarily when the volume of the
 arriving waste stream exceeds  the injection rate of the well or the
 wastes need to be segregated before  injection.   The well  normally opera-
 tes  at a rate  of  3 barrels  per minute (126  gallons per minute) and under
 an injection pressure of  360 pounds  per square  inch (psi).  The pressure
 can  be increased  with the addition of another pump, thereby increasing
 the  injection  rate.   The  well  has been operated under a pressure of 500
 psi,  which resulted in an injection  rate of 2,000 gallons  per minute.
 This higher rate  is used  when  a large shipment  is accepted,which exceeds
 the  storage capacity of the  tanks..

 The  wellfis constructed of  a five-inch  steel  casing within which is a
 three-inch fiberglass pipe.  The bottom of  the  fiberglass  pipe is open
 to the 2,100-foot level in  the Arbuckle limestone formation.   The
 annular space  between the fiberglass pipe and steel casing is sealed at
 the  top and bottom and filled  with oil  under  a  higher pressure than the
                                     89

-------
expected waste stream injection pressure.  By monitoring the oil pres-
sure, leaks can be detected either in the fiberglass in the inner pipe
or the steel casing.  Furthermore, the higher pressure of the oil will
prevent hazardous wastes from escaping the fiberglass in the event of a
leak.  The steel casing is also surrounded by cement from top to bottom.

Some of the wastes are blended before injection to reduce the corrosive-
ness of a particular waste stream and thereby protect the piping.  The
limestone aquifer further neutralizes the wastes.  Since the operation
began there has never been a positive pressure in the aquifer after
waste injection has ceased, indicating no buildup of pressure in the
aquifer.  There are three private injection wells in the area, all using
the same Arbuckle formation, with much higher injection volumes and with
similar histories of no pressure buildups.  The other three wells han-
dled approximately 400 million gallons in 1979, compared to Lamberton's
well which processed about 12 million gallons.

The site will soon operate twenty-four hours per day with three two-
person shifts.  Currently, the site operates only sixteen hours per day.

Contingency and post-closure provisions follow state regulations.  The
owner has a $10,000 bond and $500,000 worth of liability insurance.  The
insurance amount meets state standards.  However, the bonding limit to
cover closure and post-closure monitoring has yet to be determined by
the state.

The facility accepts a relatively broad range of wastes from a large
market area.  Out-of-state wastes come fromm Texas, New Jersey,
Louisiana, Ohio, Colorado, Mississippi, Tennessee, and Arkansas.  These
wastes include sulfuric acid solutions from plating operations, waste
oil, and pesticide rinse waters.  The operator does not handle highly
corrosive wastes which would damage the piping and storage tanks.  He
also does not accept chlorinated hydrocarbons which contaminate the
piping and storage tanks for subsequent use of these facilities for
waste oils that are shipped to the refinery for reprocessing.  The
facility handles an average of 1.5 million gallons per month.  During a
one-month period in 1978, 4.5 million gallons were received and disposed
of.

The owner of the well is a petroleum engineer with drilling experience
dating back to 1926 when his family purchased some oil wells that are
still in operation near the site.  He is a third-generation oil man.
His experiences have also included deep-well injection of brines from
oil well operations.  He claims that there are over 10,000 such injec-
tion wells in the state.  The injection well is the only hazardous waste
disposal facility focused on in this study which was owned by the opera-
tor.  Although Tulsa is no longer the "oil capital of the world," its
primary industry still is oil and associated petrochemical industries.
The site is near one of the oldest parts of town, where the oil boom in
this area first started in the early 1900s.   The neighborhood is now
                                     90

-------
predominantly a lower middle class blue-collar area viewed by one of its
inhabitants as the "wrong side of the tracks" from the rest of Tulsa.
The site is within Tulsa County and the Tulsa SMSA, which has approxi-
mately 425,000 people.  Tulsa is the major trade and service center for
eastern Oklahoma.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

When the operation started in 1972, there were no specific regulations
covering hazardous waste injection.  The state had passed a Solid Waste
Management Act in 1970 which covered hazardous waste disposal in land-
fills but not in deep-well injection facilities.  At that time the State
Corporation Commission granted all well drilling permits for oil, gas
and waste injection wells, and the Water Resources Board granted waste
injection permits.  In 1976, however, the state adopted the Oklahoma
Controlled Industrial Waste Act, which specifically covered deep-well
injection of hazardous wastes.  The Act provided guidelines for both the
construction and operation of such wells, including a provision for
public hearings if one is requested.  The statute also prohibited the
importation of wastes from any state that was not willing to accept
hazardous wastes from Oklahoma.  In July of 1977, rules and regulations
were promulgated for the Act and the authority over deep-well injection
of hazardous waste was transferred from the Water Resources Board to the
state Health Department.  Under an informal grandfather clause, .existing
operators were permitted to continue operations while their operating
conditions were evaluated for new Health Department permits based on the
rules and regulations of the 1976 Act.  The portion of the Act dealing
with the reciprocity agreements between states over wastes shipments was
later struck down by a. federal court.

In 1978, the state passed an amendment to the Act tightening some of the
provisions of the 1976 Act.  Revised rules and regulations are now being
drafted and are expected to be promulgated in the summer of 1979.

The state, under contractual arrangements with the City/County Health De-
partment, has delegated the responsibility of inspecting the injection  _
well disposal facilities to the county.  The county reports its findings
to the state and the state has the authority and responsibility to
enforce compliance with the regulations.

The federal government under the Safe Drinking Water Act of 1974 has
also developed proposed regulations covering underground injection of   *
wastes and the protection of underground sources of drinking water.
However, these regulations will presumably allow states such as Oklahoma
with their own legal authorities to have primary enforcement responsibi-
lities for an underground injection control program if it meets or
exceeds federal standards.

The history of events that led to  the hazardous waste disposal opera-
tions of Chemical Resources, Inc., formerly the Lamberton Acid Well
                                     Si

-------
Disposal, started in 1957 when the operator had his land holdings in
West Tulsa rezoned from agricultural to heavy industrial.  The operator
had lived in the area since 1918 and operated oil wells on this property
since 1916.  However, the primary use of the land was cattle grazing.
Since 1957 several pieces of land were sold, including one piece to a
steel galvanizing operation.  Cattle grazing continued during this
period and the operator noticed some harmful effects on the cattle from
the acid wastes which were being disposed of by the galvanizing opera-
tion in evaporation ponds.  These wastes occasionally escaped the ponds
and contaminated a local creek used by the cattle.  This situation led   '
to the idea of an acid waste injection well to serve the steel industry
in the area.

In 1972 the operator made arrangements with the area's steel plants to
accept their acid wastes for disposal in an injection well.  The
arrangement included having the wastes piped directly to a four-acre
site where the well would be drilled, several hundred yards from the
steel plants.  In 1973 the operator received a State Corporation
Commission permit and the well was drilled.  At that time the operator
owned 265 acres of primarily undeveloped land around the well site.

In 1973 the State Water Resources Board granted the operator a permit to
inject acid wastes into the Arbuckle limestone formation.  Waste dis-
posal operation began in 1973 and for two years the site-continued to
handle only the acid wastes from the nearby steel plants.  During this
time another commercial waste injection well operated in the area and
the Lamberton operation received frequent requests to handle its         i
oversupply of wastes.  Therefore, in 1975 Lamberton decided to expand
the operation by accepting non-local waste shipments in addition to the
direct, piped acid wastes.  Waste shipments were received by tank truck,
rail and barge from as far away as New Jersey.

Up to this time the facility was operated under a permit granted by the
Water Resources Board.  In 1976 Oklahoma passed the Controlled
Industrial Waste Disposal Act which specifically addressed deep-well
injection of hazardous wastes.  Rules and regulations under this Act
became effective in 1977 and the authority for underground hazardous
waste disposal shifted to the State Health Department.  Technically, the
Water Resources Board permit was no longer valid and a new Health
Department permit was required.  However, under an informal grandfather
clause, the facility continued to operate while certain housekeeping and
operating activities were-changed to meet the new regulations.  There is
no established schedule to meet these requirements, and as soon as the
state is satisfied with the improvements, a new permit will be issued.
Some improvements have already been made, such as diking around the well
and installation of an impermeable liner under the off-loading area.
Other improvements (e.g., barbed wire strands above the existing
chainlink fence) have not yet been made.                 .               :

-------
At the end of 1977, the operator filed suit against the Health Depart-  .
ment over one provision in the new Act.  This provision prohibited.the  .
importation of hazardous wastes from any state that was unwilling to
accept Oklahoma's hazardous wastes.  This.legislation was the direct
result of a hazardous waste landfill operation in southern Oklahoma
which was receiving over 60 percent of its wastes from outside the
state.  There was a growing fear that the state would "fill up" with
toxic wastes from other states.  The operator argued that a sweeping ban
on importation of wastes where no reciprocity agreement existed should
not apply to disposal technologies which have virtually unlimited
capacities such as deep-well injection, incineration, distillation, and
neutralization.  When these metho'ds are employed there is little chance
of "filling up" the state.  Furthermore, the/ operator argued that only a
small portion of the total hazardous wastes disposed in Oklahoma were
imported.  In the case of the Tulsa area injection wells only about 5   .
million out of 400 million gallons disposed of in one year were from  ,
outside sources.  In September of 1978, the federal .court agreed with
the operator and a temporary injunction was granted preventing the state
from enforcing the reciprocity agreement.  Both the operator and the
state expect that the court will issue ,a permanent injunction shortly.

A short while after the litigation over the reciprocity issue, an inci-
dent occurred which aroused the first local public attention to
hazardous waste disposal.  In October of 1978 a barge loaded with pesti-
cide rinse water from Mississippi attempted to unload at the Port of
Catoosa serving the Tulsa area.  The wastes were destined for the
Lamberton injection well.  Under the new Act, the state required .that  •
all shipments of hazardous wastes be covered by a disposal plan which   .
was to be filled out by the waste generator.  There is some confusion
over why this plan was not submitted.  According to the state, some of
this confusion may have been the result of the lengthy litigation with
the operator and a misunderstanding over whether this requirement was,
still in effect.  At any rate, at the last minute the operator requested
permission from the state to off-load the wastes*  The state quickly
asked the county to inspect the situation and to advise the state on the
safety of the off-loading operation.  The county's involvement then trig-
gered the news media and according to one county official the situation
became an instant media event.  For several days, while the barge
awaited state approval to off-load, the local Tulsa papers and televi-,.  .,
sion carried news about the barge, the possibility of polluting the
Verdigris River (which leads to the Arkansas river), and the realization
that Tulsa was becoming a "dumping ground" for out-of-state wastes.  The
officials and townspeople of two towns with water supply intakes
downstream from the Port of Catoosa became alarmed at the possibility of
having their water,supply contaminated by an off-loading accident.  They
also felt threatened by continued use of the port for similar hazardous ,
waste shipments.

-------
The state finally granted approval  for  the  shipment  to be off-loaded
onto tanker trucks and transported  to the Lamberton  well.  The off-
loading took place without  incident.  Almost all  of  the news cov-
erage during this three to  four week period was aimed at the barge and
the prospects of further shipments  of hazardous wastes into the Tulsa
area.  Only one article was found which dealt specifically with the
Lamerton injection well and what this technology meant to the area.  The
article praised injection wells as  a disposal technology.  Indeed, it
began with a quotation attributed to an EPA official saying "Except for
shooting the stuff to the moon, injection wells are  the next best
thing."A

With the exception of this  incident there had been virtually no public
opposition to the injection well operation.  Both the state and the
county had received a few phone calls voicing concern over the.operation
and a couple of calls complaining about odors.  There is no odor ordi-
nance in Tulsa but the county did check on  the complaints and was unable
to verify the allegations.  The operation was never  charged with creat-
ing a nuisance.

Conversations with two long-time residents  in the nearby residential
area indicated that most people were aware  of the hazardous waste dis-
posal operation but were not concerned about it.  They were more con-
concerned about stopping industrial development in the vicinity of the
well to protect a series of scenic  hills that separate the well from the
nearest residential area.   When asked about possible odors from the op-
eration, 'they said that local odors were primarily the result of two
large refineries in the area.  One  of the residents  who was on the prev-
ious mayor's planning commission for Project 2000 (a future development
plan for Tulsa) felt that under the current administration there was
very little input for public paticipation in the affairs of this
neighborhood, where the injection well was  situated.  She felt that this
predominantly blue-collar area was  treated  as though  they were on the
"wrong side of the tracks" and frequently not given  all the information
about developments in the area including information about the injection
well.   Both residents agreed that the public is generally apathetic
towards the waste disposal  operation.

In January of 1979 the Lamberton operation, which had been operating as
an individual proprietorship, was incorported as Chemical Resources,
Inc.  Steps are still being taken to comply with all the new operating
requirements imposed by the Controlled Industrial Waste Disposal Act.
IV.
CHRONOLOGY OF EVENTS
1957 — Lamberton property is zoned for heavy industrial use.
   It should be noted that the EPA'official's statement was meant to
   underscore the viability of injection wells, not to seriously propose
   disposing of hazardous waste in space.
                                   94

-------
1972 — Negotiations undertaken with local steel plants to accept acid
        was tes.

1973 — Corporation Commission approval granted and well is
        drilled.

1973 — Water Resources Board grants acid waste disposal permit.

1973 — Operation begins accepting acid wastes from local steel plants.

July, 1975 — Operation is expanded by accepting non-local wastes by
              truck, rail and barge from Oklahoma and out of state.

1976 — State passes the Oklahoma controlled Industrial Waste Disposal .
        Act.

July, 1977 — New rules and regulations under the Act become effective.
              Authority over underground hazardous waste disposal trans-
              ferred from Water Resources Board to Department of Health.
              More stringent operating procedures automatically apply to
              the Lamberton well and must be met before Health De-
              partment operating permit is granted.

December,  1977  -- Operator files suit against state to overturn statute
                  requiring reciprocity agreements with other states
                  over hazardous waste shipments.

September, 1978 — Federal court grants temporary injunction prohibiting
                   state enforcement of reciprocity agreements over
                   hazardous waste shipments.

October,  1978 -<- Major news event occurs when state refuses to allow a
                 barge loaded with pesticide wastes to be  off,-loaded and
                 transported to the Lamberton well.

January,  1979  — Operator  incorporates the business under  the name of
                 Chemical  Resources, Inc.

April,  1979  — All  operating procedures under  the new regulations had
                not been meet and operating permit still pending full
                compliance.
 V.
ATTEMPTS TO SECURE SUPPORT
 Because there has never been significant opposition to the injection
 well,  there has been no need to address  public concerns or issues.
 There were also no specific attempts to  secure support for the injection
 well.
                                 95

-------
VI.
SUMMARY EVALUATION
At the time the operation began, there was no public opposition to the
project and very little awareness of its existence.  Since that time
there have been a few isolated complaints over odors from the site but
no organized or persistent opposition. . No attempts were made to respond
to the public interest and the media coverage that developed over the
barge incident, largely because the interest was not directed specific-
ally at the Lamberton operation.  The only steps now being taken by the
operator, which might prevent future public opposition, are those
housekeeping and operational procedures required by the 1976 Act.  These
include surrounding the area with dikes to prevent accidental runoff
lining the unloading area with an impervious material, and adding barbed
wire to the fence.  Finally, no attempts were made by the operator to
publicize the fact that the injection well is probably a much safer way
to dispose of locally generated hazardous wastes than the previous use
of evaporation ponds.  During the barge incident, one lengthy news arti-
cle did appear in the Tulsa paper, written by a medical reporter, that
objectively covered the known pros and cons of injection wells and de-
scribed the Lamberton operation.

The Lamberton deep-well injection facility has operated successfully for
the past six years primarily for the following reasons:

       Accepted Technology — The operator estimates that there are at
       least 10,000 injection wells in Oklahoma disposing of oil dril-
       ling waste brines.  His facility is nothing new to the area and
       is accepted as a simple offshoot to Oklahoma's oil and
       petrochemical industry.

       Site Location — The site is situated in an industrial area con-
       taining oil refineries steel and chemical plants and a railroad
       yard.  By comparison, the relatively clean appearance of the
       small four-acre site is hardly recognized as a hazardous indus-
       trial waste disposal area.  The family-owned riding stable and
       horseback riding trails immediately adjacent to the well con-
       tribute to the favorable appearance of the site.

       Public Apathy — The neighborhood closest to the site is made up,
       of blue-collar workers heavily dependent on the petrochemical
       industry.  The existence of the well and the waste disposal oper-
       ation are treated as a way of life for these people and have not
       aroused their special interest.  They are aware of the operation
       but not concerned about it.

       Media Interest — Everyone interviewed agreed that the flurry of
       media interest in the barge incident was -over an isolated event
       and did not reflect long standing or deeply felt public views on
       hazardous waste disposal.  It is difficult to say what triggered
       the' media interest other than it was a newsworthy event in the
                                    96

-------
       light of national publicity over hazardous wastes.  However,
       public interest has been awakened and although the public has not
       shown its opposition to the Lamberton operation it has strongly
       opposed a proposal to construct a similar injection operation
       near Tulsa.  -   '

VII.   FACTORS LEDING TO PUBLIC OPPOSITION/ACCEPTANCE

The following factors contributed to public acceptance, or rather, to
the lack of public opposition:

       o     The site is located in an area dominated by many larger and
             more obvious industrial faciltie's.

       o     The site is buffered from residential areas by a large
             parcel of undeveloped land.                            :  ,

       o     Waste injection wells are common in Oklahoma.

       o     The site is small and relatively clean, indicating no ob-
      :•.-'     vipus nuisance.             •  .                       ;     v

       o     Nearby residents are either not aware of or unconcerned by
             yet another industrial activity in the area.

       o     Occasional odors from the site are easily mistaken for the
             more  frequent  odors of the  local.refineries.

VIII.  RETROSPECTIVE VIEWS                            ,

There were no  specific retrospective views on the part of  the operator
or  the government  officials.  One of the nearby residents, however, felt
that more information  regarding  the operation should have  been made
available for  neighborhood  planning efforts.
                                    97

-------
                         MASSACHUSETTS  BUREAU OF
                          SOLID WASTE DISPOSAL

                       STURBRIDGE, MASSACHUSETTS


I.     INTRODUCTION

The Massachusetts Bureau of Solid Waste Disposal (BSWD) is currently
investigating the feasibility of developing a secure landfill for
hazardous waste near the town of Sturbridge, Massachusetts.  Preliminary
engineering reports have indicated that the Sturbridge site appears to
be technically suitable for the disposal of metal finishing (hydroxide)
sludges and oil spill debris, wastes of the most immediate concern to
BSWD and other state agencies.  A decision on whether to develop the
Sturbridge site was originally expected to be made by the fall of 1979.
That decision has been postponed at least until the spring of 1980.

Although the siting process is in an interim stage, public concern and
opposition to the possible development  of the site have been voiced by
residents and officials in the Sturbridge area.  Concerns have been
raised not only about the site's qualifications and facility development
plans but also about potential impacts  of a facility on the area's
tourist industry.

In December 1978, at the suggestion of BSWD, the town appointed a task
force of local officials and residents.  The task force has acted to
keep residents informed, to communicate with BSWD and other state
agencies, and to marshall resources which may be used to assure local
input into the siting process.  BSWD and other state agencies have made
a concerted effort to inform the community of the progress of the
project and to respond to community questions and concerns.  The town,
however, continues to express concern and opposition.

II.    BACKGROUND INFORMATION

The site being investigated by BSWD occupies 105 acres near the
intersection of the Massachusetts Turnpike (Interstate 90) and
Interstate 86, about 45 miles west of Boston and two miles northeast of
the town of Sturbridge.  The land is privately owned and undeveloped,
although it had recently been considered as a site for a waste-to-energy
facility and/or regional sanitary landfill project.  There are a few
small business establishments in close proximity to the site.   To the
north of the site is a development of relatively expensive homes which
surround Walker Pond and which depend on private wells for water.

The geology of the Sturbridge site has required a preliminary design
meeting the intent of proposed RCRA regulations where it has  not been

-------
possible to adhere strictly to those regulations.1  The site's soils,
(primarily gravels and tills) due to their permeability, are not  "   r
suitable for liner material.  These soils in depths of 20 to 45 feet
overlie a fractured bedrock which transmits groundwater.  Groundwater
appears to discharge into Hobbs Brook which flows through the western
portion of the site.  The wetland area of the East Marsh section of the
site flows into Walker Pond, just north of the site, and Walker Pond in
turn flows into Hobbs Creek.

These factors have directly impacted site design.  The central portion
of the site could be developed using the existing soil as liner material
if a Hypalon (i.e., synthetic) liner is also used.  Development of the
East Marsh would require the excavation of saturated soils down to the
level of the underlying tills.  Surface water runoff would be diverted
away from the site to adjacent water bodies.  Development of the East
Marsh section of the landfill would also incorporate a Hypalon liner.
The entire developed area would be served by a leachate collection sys-
tem which would capture leachate within the secured impoundments.

If developed as a secure landfill the central portion site would have a
minimum life of about six years.  Additional development of the site as
a landfill could increase gross capacity by 80 percent.  Net increases
to capacity would depend on specific engineering plans  (e.g., whether a
number of smaller fill areas would be planned, allowing for greater
segregation of wastes but decreasing capacity).                      ,

The preliminary design report included needed appurtenances and es-  .
timated capital costs.  Appurtenances included buildings, fencing, and
two monitoring wells downgradient from each impoundment.  Construction
and capital costs were estimated at $1.8 million for development of  the
central portion only and at $2.7 million for development of the central
and East Marsh portions.

The preliminary plan also addressed site operations.  Recommendations
for ongoing operations included daily covering of wastes, handling of
   Assessments of  the  Sturbridge  site  employed proposed RCRA
   regulations (Section 300'4, dated March 24, 1978) as design criteria.
   The most  immediate  requirements were  those pertaining  to  sites
   located over usable aquifers.  Those regulations called for a
   five-foot thick liner  of  a permeability  less  than10-? cm/sec.
   Because of the  shallowness of  groundwater and permeability of in situ
   soils, the site would  not meet the  letter of  the draft regulations/
   (Based on regulatory definitions almost  all of New England would be
   classified as a usable aquifer because"of shallow  groundwater
   conditions.)  Other design criteria relate to: 1)  the  containment and
   removal of leachate; 2) the  thickness and permeability of liner
   materials; 3) the quality and  characteristics of soil  liners; and 4)
   the protection  of those liners.

-------
leachate, a manifest system to maintain accurate records on wastes
accepted and random sampling of those wastes.  Monitoring of groundwater
was recommended at monthly intervals.  The importance of monitoring the
site after closure was stressed although most specific provisions were
left to the state to develop.  Annual operating costs were estimated at.
$280,000; site closure capital costs were estimated at $330,000 to
$590,000, depending upon whether the East Marsh area were developed.

The landfill was designed with the assumption that it would accept
primarily plating wastes (metal hydroxide sludges), but it would also
accept oily solids resulting from oil spills and other Solids and
sludges if space were available.  The landfill was developed to help   ,
solve Massachusetts' waste problem.  While no final determination has
been made on accepting out-of-state wastes, BSWD can restrict the
facility to serving only Massachusetts.

The site would be developed by BSWD which is a state agency within the
Department of Environmental Management.  BSWD is a planning and
management agency concerned with a range of solid and hazardous waste
problems in Massachusetts and works with private industry to solve .those
problems.  It has no regulatory power and is subject to the regulatory
authorities of other state agencies.  BSWD does have power of eminent
domain and, unlike private industry, does not need local regulatory
approval to develop sites.  Operation of the facility would probably be
by a private firm under contract to BSWD; however, final arrangements
have not been determined.

The town of Sturbridge has a population of 5,550 (1976 U.S.  Census) and
is located in the central part of Massachusetts.  It is the home of Old
Sturbridge Village, a not-for-profit institution which is, after Cape
Cod, the most popular tourist attraction in the state.  While some
smaller industries operate in and around Sturbridge, it is also a      ;
bedroom community for persons working in Worcester and other larger
urban areas.  Sturbridge residents were characterized by local officials
as being in middle to upper middle income brackets.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

As of May, 1979, state regulation of hazardous waste facilities was
shared by two divisions of the State's Department of Environmental
Quality Engineering (DEQE), with one division primarily concerned with
the transportation of such waste, the other with its disposal.  Under
new state legislation expected to take effect by 1980, a new division
will be created within DEQE with sole regulatory authority for hazardous
waste management.  This new division will acquire the powers currently
within DEQE and add to those the power to regulate generators.  Local
communities exercise substantial power in siting by virtue of their
power to grant local assignments for privately developed hazardous waste
facilities.  Without such local approval a private company may not
develop a facility.  BSWD, however, is exempt from this local control
and needs only to comply with state regulations.
                                  too

-------
The impetus for investigating Sturbridge as a HWMF site emerged from a
series of unrelated but coincidental events.   By late 1977, all major
disposal sites used for hazardous waste originating in Massachusetts
were closed.  These sites were located as far away as western New York
and southern New Jersey, some of which have since reopened.  With normal
disposal options unavailable, state agencies including BSWD and the
Division of Water Pollution Control (DWPC) decided it was imperative to
find suitable sites in Massachusetts.  The need for sites was
underscored by a recent estimate cited by BSWD's assistant director that
60 to 75 percent of hazardous wastes produced in Massachusetts are being
dumped "indiscriminantly".

To find potential sites, DWPC examined sites in the state that had
previously been proposed for waste disposal facilities.  Because the
sites had previously been proposed for facilities, some data describing
the sites were available.  Based on these data, DWPC's chose ten sites
for more thorough study.  In February of 1978 DWPC.hired Camp Dresser
and McKee, Inc. (COM) to develop siting criteria and to evaluate the
proposed sites using those criteria.  The objective of CDM's evaluation
was to recommend three sites which would be investigated more
extensively.        ,           •  .    ,•

Because of the perceived crisis in hazardous waste disposal, BSWD
entered into a separate contract with COM to assess the feasibility of
implementing a hazardous landfill at Sturbridge as soon as possible.
(Sturbridge was one of the original ten sites which DWPC asked COM to
evaluate.  When BSWD accelerated the investigation of Sturbridge, DWPC
replaced it with an eleventh site.)  The major reason for selecting
Sturbridge for accelerated study was that based on the data then
available, the Sturbridge site appeared to have the most suitable
hydrogeology.  Thus it appeared to be the most promising of,the ten
sites and the one that could be developed most quickly.

The contract between BSWD and,COM was signed in late February.  In March
BSWD officials met with and first notified Sturbridge elected officials
of the hazardous waste siting  project.  BSWD's director indicated that
the Sturbridge site was being  investigated for the disposal of,special
wastes, that it site would be  state owned and privately operated, that
the tonnage of wastes  to be disposed could not be estimated, and that
there would be ample time to keep officials informed prior to any
decision.  Those officials expressed opposition and, according to a
local newspaper, were shocked  at the possibility that a regional
industrial sludge landfill might be developed in the area.  Local,media
indicated that the potential site had been considered for the
development of an energy, recovery facility and sanitary landfill.  This
project had been reviewed by local officials and, despite some concern
and opposition, had been given local regulatory approval.  Acceptance of
the energy recovery plant (the town had signed a contract with the
developer in February  of 1977) was based partially on anticipated
revenues from  the facility.  Thus, the energy plant was seen as a..more
desirable use  of the site.                            ,.
                                 101

-------
While the first contact between BSWD and Sturbridge officials generated
a few articles in local newspapers, the siting investigation attracted
little attention until the late summer of 1978.  In August BSWD again
contacted local officals to inform them of the investigation's general
progress.  At that time BSWD told officials that the agency had the
power of eminent domain and in addition would not require local
regulatory approval (specifically, an assignment by the local board of
health).  Within a month of this contact a petition opposing the site
had been circulated locally by area residents and several hundred
signatures had been collected.  In September copies of the petition were
forwarded to the Governor and the Department of Environmental
Management, BSWD's parent agency.

In the fall of 1978 a number of events made it apparent that BSWD was
seriously considering Sturbridge as a site.  The state informed the
Sturbridge Board of Selectmen (i.e., the elected officials of the town)
that an environmental impact report would have to be prepared by the
state before a facility could be developed.  A DWPC official was cited
by the local press as stating that Sturbridge was one of two sites
chosen for a disposal facility.  While the DWPC official's statement
indicated that a facility would be developed, the same article repeated
BSWD's policy that no final decision had been made on the Sturbridge•
site.  According to a press report, DWPC would offer $.50 to $1.00 to
towns for each ton of hazardous waste disposed.  BSWD, during the site
visit, indicated that such compensation could in fact be provided to the
town.

During this time, opposition to the facility began to build and the :
outlines of issues emerged.  Local officials consistently expressed
"surprise" or "shock" at announcements concerning the site.  Issues were
generally framed in environmental/public health or economic terms.   The
site's proximity to water recharge areas and floodplains, with the
attendant potential for contamination of water supplies was the primary
environmental issue.  The impact on Sturbridge's tourist industry
which brings $50 million into the local economy and tax structure were
described as primary economic issues.  In addition, it was indicated
that the development of the energy recovery facility should be the top
priority for the site.  By early 1978, however, that project had been
abandoned for reasons unrelated to BSWD's site investigation.

CDM, by December 1978, completed its preliminary design investigation.
The major conclusion of this report was that the central portion of the
site was "immediately amenable to development of a hazardous waste
landfill, if consideration of artificial liner systems was included."

Within a few days, BSWD provided the Board of Selectmen with copies of
CDM's report and suggested that a task force be appointed to work with
the agency.   This suggestion was also made by the area's state
representative and a local resident.   In late December the selectmen
appointed a six-member task force representing the Board of Selectmen,
town agencies,  environmental and public interest organizations,  and
                                102

-------
private citizens.  The task force was charged with collecting and
disseminating relevant information, assuring coordinated and
constructive public input into decisions, and leading any discussions
and negotiations with state agencies.  Since its creation, the task
force has spearheaded public concern with and opposition to the siting
process.
    i  -•'•'.                    .•  .  . .           .    •
In early January of 1979 the task force issued a report based on its
review of CDM's study.  That report reiterated issues that had been
developing publicly in the fall and criticized inadequacies in the CDM
report.  A prime concern was the potential of a significant threat to
groundwater supplies, not only in the Sturbridge area but also
downstream in areas served by the Quinebaug River after which is fed by
Hobbs Creek.  Provisions for site monitoring during operations and after
the facility was closed were considered inadequate, and CDM's
recommendation of Hypalon liners over a superior but more costly liner
was sharply criticized.  The task force generally concluded that CDM's
report left too many unknowns with respect to impacts on the
environment.  The report noted that the task force would seek state
funds to conduct an independent assessment of the site.

Soon after the task force issued its report, the local League of Women
Voters sponsored a public meeting in Sturbridge to discuss the siting
project.  Staff from EPA Region I and several state agencies were
invited and made presentations.  The federal and state regulatory
officials discussed RCRA, the general problem of hazardous waste from
generation to disposal, and the development of a state plan for
hazardous waste management, including the need for cooperative public
participation.  BSWD's assistant director discussed the Sturbridge
siting study and its relationship to the state plan.  A question-
and-answer period followed the presentations.

While BSWD and  the other agencies received generally positive comments
from  the community for the presentation, the community remained,
skeptical of the siting process and  opposed to the development of the
facility.  Task force members indicated that BSWD had provided an honest
review of progress to date and an accurate picture of the site's
potential for development.  At the same time the information available
was considered  incomplete by task force members and other area residents
and,  at least in the area of impacts on  Sturbridge's tourist industry,
completely  inadequate.  A major impression of the presentation (as
stated  in a local editorial the following day) was that "...like it or
not,  if the  state decides to locate  an industrial waste landfill in
Sturbridge, there is little the town can do."  This impression of
potential inevitability was coupled  with the perception that Sturbridge
was at  the  top  of the list for development in spite of the state's
assurances  that no final decision would  be made until after further
study.

By late January of 1979, the task  force  was trying to determine what
resources,  particularly financial, could  be made available,to  it to
pursue  its  objectives and what avenues of protest were available.  BSWD
indicated that  state  funds might be  available for an  independent review
of the  site.  The task force also approached the area's U.S. congressman

                                 103

-------
 to see if federal funds could be found for the same purpose.   No funds
 had yet been made available and it was uncertain if funds would be
 available.   The Sturbridge Conservation Commission had been petitioned!.
 by the task force to see if the state's Wetlands Act provisions applied
 to the site.   Considered but dismissed by local officials were local
 controls over the transportation of hazardous waste over local roads.
 Local zoning's potential for blocking the site had been investigated.

 In January,  the area state representative had filed a bill banning
 hazardous waste landfills within a set distance of any well.   The
 representative felt that any final legislation would be different from
 his  proposed  bill,  but  that the bill served as a starting point for
 negotiating within the  state legislature.

 The  task force had also solicited support from various agencies and
 organizations.   Several local agencies (e.g., the town water  and sewer
 commission, the conservation commission)  had formally protested
 development of the  site primarily because of potential water  pollution.
 The  Army Corps of Engineers,  which has jurisdiction over nearby water
 basins,  had been approached,  as had various environmental organizations.
 None had responded  as of January,  1979.

 The  task force,  as  the  official representative of Sturbridge,  began to
 mount  a  determined  effort to  block development of the site.   While
 acknowledging the severity of the hazardous waste disposal problem and:
 the  consequent need for sites,  it  viewed  the Sturbridge  site  as
 involving unacceptable  risks  to the local environment and economy.   If,
 utilization of  the  site was inevitable, however,  the task force was
 prepared to negotiate.   Only  the BSWD and state regulatory agencies had
 taken  a  position in favor of  the site.  The area's  state representative
 was  in a potential  position to  act as a negotiator between BSWD and the
 town.   By January he had taken  no  official  position vis-a-vis  the  site.
 BSWD indicated to local leaders that a number of  issues  raised by  the
 community (e.g.,  site access, operating hours,  monitoring provisions)
 were negotiable.

 The  next  important  action was the  public  announcement of potential  sites
 recommended by DWPC for development  as hazardous  waste disposal
 facilities.   The town was eager to compare  Sturbridge to those sites to
 determine its relative  merits.                       '

 The  Centaur site  visit  was  conducted in late  January;  in late  May
 Centaur  again contacted BSWD to determine  the status  of  the siting
attempt.  In  the  intervening four  months the  state's  approach  to siting
 had  become more  comprehensive.   One  result  of this  development was  a
reduction in  the  sense  of  urgency  with respect  to the Sturbridge site.

 In February,  DWPC announced the  results of  the  COM  survey of ten sites
in the state.  CDM had  recommended that two  sites be  further studied for
the development of hazardous waste facilities.  Two towns—Taunton and
Amesbury—then joined Sturbridge as  prospective "sites.   According to
BSWD, subsequent  discussions by  state agencies led  to a decision to drop
                                  104

-------
Amesbury as a potential hazardous waste site in favor of pursuing its
feasibility as an interim and back-up landfill for a resource recovery
facility.  Dartmouth, one of the ten sites evaluated by CDM, was then
designated as a backup hazardous waste site.  Public opposition has
developed in Tauton and Dartmouth as a result of these actions.

According to BSWD the announcement of these additional sites has had
some impact on opponents to- the Sturbridge site.  Those opponents have
now had the. opportunity to compare its characteristics with other sites.
The site is no longer the "number one" prospect, according to BSWD, but
is at the same stage of development as the other announced sites.  While
these developments have addressed'some of the issues raised by
Sturbridge residents, opposition has not diminished.  To some extent
opposition has reportedly shifted to the potential economic impact of
developing a facility on tourism generated by Old Sturbridge Village.

The state's approach to siting has evolved substantially, which may have
much greater implications for Sturbridge than the DWPC announcement.  A
second survey of sites has been initiated and will be completed by late
1979 or early 1980.  BSWD has been investigating potential sites on
federal and state land.  In addition, private landowners have been asked
to recommend sites and those sites are also being investigated.  BSWD
expects to have a pool of prospect sites as a result of this survey and
it is 'at least possible that these sites may be more suitable than
Sturbridge or other currently identified sites.                  •

BSWD is also developing a state hazardous waste plan which should be
completed by early 1980.  According to BSWD's assistant director, recent
agency experience has indicated a need for greater state involvement, at
least insofar as BSWD must be more knowledgeable about non-technical,
non site-specific issues.  Accordingly the state plan will discuss,
among other things, the need and justification for a state role in
hazardous waste management, general siting criteria, institutional and
management policies, and regional and industrial concentrations with
respect to hazardous waste generation.  The plan may also classify
specific wastes by degree of hazard, by susceptibility to treatment
and/or processing and by their compatibility for disposal with other
hazardous waste.                                      ,

Had the state's original schedule been followed, a decision to proceed
with one of the announced sites would have been made by late April or
early May.  An environmental"assessment would have then been initiated
and completed by late summer or early fall of 1979.  Necessary permits
would then have been applied for.

With the development of the new site survey and the state plan, that
schedule has been abandoned.  The state plan and related pool of poten-
tial sites will be completed in early 1980.  An environmental impact re-
port (EIR) on those sites will then be prepared.  If, as is possible, 20
to 25 potential sites are identified, then preparing the EIR may be a
protracted process.  After the EIR is completed site acquisition(s)
                               105

-------
will be made and necessary permits applied for.  Thus any final decision
on the Sturbridge site has been substantially delayed.
IV.
CHRONOLOGY OF EVENTS
Late 1977 —
       Crisis in hazardous waste disposal leads state
       agencies to decision to investigate potential
       disposal sites in Massachusetts.
February, 1978 *— DWPC contracts with CDM to investigate ten
                  sites; BSWD contracts with CDM to investigate
                  suitability of Sturbridge site.

March, 1978 — BSWD notifies Sturbridge officials that site is
               being investigated; some opposition surfaces and media
               cover age appears.

August, 1978 — BSWD informs Sturbridge of investigation progress.

September, 1978 — Local petition opposing site is circulated and
                   sent to governor and state agencies.

Fall of 1978 — Sturbridge informed that EIR must be prepared.  DWPC
                reportedly delcares that Sturbridge has been chosen as
                disposal site; BSWD denies making a final decision.
                Local opposition increases.

December, 1978 — CDM completes report on Sturbridge; BSWD
                  provides local officials  with a copy of CDM re-
                  port.  Local task force to respond to investiga-
                  tion is established.

January, 1979 ~ Task force issues report critical of CDM report;
                 opponents seek political and financial support for
                 their fight against proposal.  League of Women Voters
                 holds informational meet ing attended by EPA, DWPC,
                 BSWD, and local resi dents.

February, 1979 — DWPC announces that Amesbury and Taunton are
                  also prospective sites for hazardous waste
                  facilities.

Spring of 1979 — BSWD begins second site survey and state plan,
                  postpones any immediate action on pursuing
                  Sturbridge or other announced sites.

Early 1980 — Expected completion date of state plan and second
              site survey.  Possible starting date of EIR on
              potential sites.
                                    106

-------
V.
ATTEMPTS TO SECURE , SUPPORT
Attempts have been made to secure support both for BSWD's siting process
and the general need for facilities.  -Major actions include:

       o     BSWD's early and continued notification of local officials
             of the site investigation and its progress.  An important
             part of this notification process has been the conscious
             attempt by BSWD to be both open and responsive.

       ,o     The informational meeting sponsored by the League of Women
             Voters in January 1979 and the agency presentations made
  ,    ,       at that meeting.

       o     The statement by a DWPC official that compensation is
             available to communities with disposal facilities.
VI.
SUMMARY EVALUATION
Conflict which has arisen over the Sturbridge site has not been resolved
to date.  There are several major reasons for this: 1) BSWD has not made
a final decision on the site's feasibility; 2) additional work will be
done by BSWD before a decision is reached; and 3) BSWD's decision and
additional data will significantly contribute to the final disposition
of issues raised by the Sturbridge community.  Thus no resolution has
been achieved, nor is there any reason why issues should be resolved at
this time.

As indicated above, BSWD and other agenices have met with the Sturbridge
community to provide information and to respond to local concerns.
These dealings with officials and citizens in Sturbridge.have met with
mixed results.  BSWD has established credibility with local officials;
task force members feel that BSWD has been honest and above board with
them.  This has helped communicate the need for dispoal sites to local
officials and private citizens.  Consequently this need has been
recognized and acknowledged even by those most opposed to a facility ,in
Sturbridge. EPA's regional office and Masachusetts regulatory agencies
have contributed to this recognition.

In spite of this, Sturbridge opposes any development of a facility at
the site.  The COM report commissioned by BSWD is considered generally
inadequate by task force members.  To meet technical issues, raised by
the community, BSWD has indicated that state funds may be available for
Sturbridge to commission its own investigation.  This would clearly meet
with local approval as the task force has actively sought such funds.
Whether such a report would overcome locally expressed concerns is un-
certain.  Even if such a report reaffirmed CDM's conclusions, a task
force member felt that a considerable "selling job" would be required to
convince locals of the site's suitability.  Among other concerns, the
task force wanted to compare Sturbridge to other potential disposal
sites in Masachusetts.                      •
                                107

-------
BSWD has also indicated that aspects of site design (e.g., access,
screening) and operation (e.g., monitoring, working hours) are nego-
tiable. If site development is inevitable, task force members have
indicated a desire to negotiate with BSWD to ensure that the safest and
most responsible plan for site development is prepared.  The area's
state representative feels he is a potential negotiator for Sturbidge.
In discussing possible negotiations he reiterated the major issues
outlined by the task force and by BSWD.  He also indicated that the
state might provide some compensation to Sturbridge by funding projects
to support the area's tourist industry.

A range of issues has been raised by local officials and citizens.
These generally relate to the viability of the site, the plan for facil-
ity development, the potential economic impact on the area, and the site
investigation of Sturbridge compared to other potential sites in Mas-
sachusetts.

Site viability — The proximity of the site to a marsh, a pond, and a
creek which might be contaminated by leakages from a facility is a major
concern.  There are private wells in the area and sites that might in
the future be developed as public wells.  The area is an aquifer .which
must meet stringent requirements to avoid contamination of drinking
water supplies.  BSWD acknowledges these facts but does point out that
almost all, if not all, of New England would be classified as an aquifer
under existing regulations.

Facility development plan — The task force has criticized CDM's report
for not addressing a number of issues in sufficient detail, from the  '.
specific wastes to be accepted to provisions for post-closure moni-
toring.  Primary among these criticisms is that engineering will not
compensate for hydrogeological flaws of the site.   BSWD has responded by
indicating that additional engineering and an environmental review have
yet to be prepared and that these will address many of the issues
raised.  In addition, if site development occurs,  both sides have
indicated a desire to negotiate the details of site design and facility
operation.

Economic impacts — Community representatives feel that the development
of a hazardous waste landfill is inherently incompatible with the area's
tourism.  Regardless of other risks associated with a facility, they
feel its very presence could adversely affect tourist business. (Ac-
cording to task force members interviewed, tourists spend $50 million
annually in the Sturbridge area and that the area is second only to Cape
Cod as a Massachusetts tourist attraction.)

Sturbridge versus other potential sites — Community representatives
want to compare this site to others being investigated in the state.
They feel Sturbridge is the front runner because of its central location
and accessibility.  Without data on other sites they are extremely
skeptical of statements and evidence which describe the site as suit-
able for hazardous waste disposal.  By the spring of 1979 these data
were available.
                                   108

-------
VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE       ,

Opposition and concern arose to consideration of Sturbridge as a hazard-
ous waste disposal site almost as soon as BSWD informed local officials
of its site investigation.  In the one-year period since officials were
first informed of the investigtion, opposition, has grown and issues have
become more clearly defined.  The factors contributing to opposition
include the following.

       o     BSWD's decision to push the investigation of Sturbridge
             ahead of DWPC's survey of other potential sites in the
             state.

       o     The sense among local residents that Sturbridge was the
             front runner among sites in the state despite BSWD's
             statement that no final decision has been made.

       o     The perceived incompatibility of a hazardous waste"disposal
             facility with area development, particularly the tourist
             industry.

In spite of the opposition, there appeared to be some opportunity to ar-
rive at a negotiated agreement on the site.  This potential could erode
over time; however, a number of factors contribute to the potential for
development of areas of agreement between BSWD and local concerns.

       o     The state's power of eminent domain which preempts local
             regulation.

       o     BSWD's credibility in the eyes of .local leaders, resulting
             from BSWD's openness and responsiveness.         ,

       o     Two local options for negotiators—the task force which
             is so charged and the area's state representative.

       o     BSWD's willingness to negotiate issues and the local
             perception that negotiation is desirable if the facility
             is inevitable.

VIII.  RETROSPECTIVE VIEWS

The Sturbridge case is an example of an ongoing siting process; hence,
retrospective views would amount to pre-judging an incomplete process
and are therefore not included as part of this case study.
                                   109

-------
                             3M/CHEMOLITE

                        COTTAGE GROVE, MINNESOTA
I.
INTRODUCTION
In early 1978, the Chemolite Division of the 3M Company joined with
local residents to successfully oppose an attempt by state and regional
agencies to site a hazardous waste landfill on their property.  Little
more than a month later, Chemolite was informed that it could not
continue co-disposing of certain hazardous wastes in a nearby landfill,
and was obliged to attempt to site a hazardous waste facility of its
own.

Chemolite immediately contacted local .officials on learning that it
would have to make new arrangements to dispose of these wastes and
conducted a relatively effective but largely low-key public relations
campaign.  They were successful in obtaining local support for a
temporary hazardous waste landfill on their property.  In the long run,
however, they expect to have to ship their hazardous wastes to an
out-of-state landfill.  Given local attitudes toward hazardous waste at
that time, their success in gaining approval even for a temporary
landfill was noteworthy.
II.
BACKGROUND INFORMATION
The 3M Company's Chemolite landfill is located on land adjacent to its
Chemolite complex in Cottage Grove, Minnesota.  The site occupies
approximately five acres of the 820-acre 3M property, and is surrounded
on all sides by this property.  Of the other 815 acres, 385 are
developed, 250 are non-buildable and 280 are reserved for future
expansion.  (Portions of the undeveloped area are used for outdoor
weather testing of products and as a recreational areas, and the
remainder is leased on a yearly basis for agricultural uses.)  The land
is presently zoned for general industry.  The soils of the area are
silty and sandy surface soils underlain by sand.  These are moderately
to highly permeable.  Groundwater flow in the area is toward the
Mississippi River, which borders the 3M property on the north.

In order to ensure that the groundwater is not contaminated, the
landfill and the surrounding berm are lined with bentonite clay.  This
also allows the collection of leachate for analysis.  Lysimeters are
located adjacent to the disposal area to collect any percolating water
to determine whether any substances are being leached into the
groundwater.  Finally, samples of groundwater from the Chemolite Plant
Well No. 4, the closest well to the site, are periodically analyzed for
contamination.  The landfill accepts wastes only from the Chemolite
facility — wastewater sludge (including incinerator scrubber sludge)
and boiler ash.  The 3M Company operates a rotary kiln incinerator at
the Chemolite plant which burns hazardous wastes (e.g. oily rags and
                                  110

-------
sludges).  Both the incinerator scrubber sludge and incinerator ash are
hazardous, (particularly because of their heavy metal content) and must
be landfilled.  Incinerator ash was previously disposed of in the 3M
landfill, but is now hauled to a hazardous waste facility in Milwaukee,
Wisconsin.   The remaining wastes are mixed prior to burial in the
landfill.  The MPCA is of the opinion that the resulting mixture is
sufficiently alkaline that leachate is not a problem. 'Each year, the
Chemolite facility produces about 14-15,000 cubic yards of wastewater
sludge, (of when 30% is incinerator scrubber sludge), less than 1,000
cubic yards of incinerator ash, and about 6,500 cubic yards of boiler
ash.  Approximately 1.5 acres of the landfill have not yet been filled,
so that the maximum remaining life of the landfill, at current rates of
disposal, is .about two years.

The 3M Company is a major chemical producer with over 90 plants located
around the country.  Its chemicals are used in the production of various
coated materials (from adhesive tape to recording tape) which 3M
produces.  With fiscal year 1978 sales revenues of over $4.6 billion, 3M,
was ranked fiftieth in the 1979 Fortune 500 listing of U.S. industrial
corporations.  3M does operate waste disposal facilities, at some plants.
However, the Cottage Grove facility is the only one designed to take
hazardous wastes.

Cottage Grove is located in Washington County, Minnesota, part of the
Minneapolis-St. Paul metropolitan area (1976 population: 2.0 million).
The town has a population of about 18,000, the majority of whom'are
white-collar workers  employed elsewhere in the region, and has one of
the highest per-capita incomes in the region.  The only major industries
in the town are the Ghemolite plant and a Whirlpool appliance assembly
plant.  The prevailing land use in the surrounding county is
agricultural.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

Any solid waste disposal site for hazardous or other wastes in Minnesota
is required to have a Solid Waste Disposal Permit issued by the
Minnesota Pollution Control Agency (MPCA).  Initially, they recommend
that the prospective permittee discuss the scope and nature of the
project with MPCA staff.  A preliminary application must then ,be
submitted to the MPCA.  This application must include data on the
proposed site, facility design and engineering, access, clientele, type
of wastes, and some estimate on the environmental impacts of site
development and operation.  The MPCA then responds to the preliminary
application and suggests changes which are incorporated into the final
application.  In addition to receiving MPCA approval, the final
application must also be approved by the Metropolitan Council-'- if the
proposed facility is in the seven-county Mihneapolis-St. Paul region,
arid must be reviewed by the Minnesota Environmental Quality Board to
   The Metropolitan Council is the regional planning agency for the
   seven-county Minneapolis-St. Paul metropolitan region.
                                  Ill

-------
determine whether an Environmental Impact Statement is required.  If the
application is approved, the MPCA must give public notice, and can hold
a public hearing if one is requested.  The permit if granted is for the
development and operation of the facility for the life of the site,
given that monitoring and reporting requirements are met.  (Once the
site has been developed, a statement is required from a registered
professional engineer that the site has been developed according to the
permit).

No other state agency requires permits for the development and operation
of hazardous waste facilities.  However, a number of counties and towns
in Minnesota do.  Washington County and the City of Cottage Grove are
among these.  Washington County has an ordinance which regulates the
development and operation of landfills, and requires that they receive a
permit to generate.  The City of Cottage Grove requires that a hazardous
waste facility must have met MPCA standards and received an MPCA permit.
Within the state  of Minnesota, local zoning generally cannot be
preempted to site hazardous waste facilities.  Within the seven-county
metropolitan area, the Metropolitan Waste Control Commission (MWCC) can
preempt local zoning to site its own. hazardous waste facilities.1
Elsewhere in the state, the counties have this power.  However, they
cannot preempt zoning for sites owned by other government agencies or by
private industry.

From June of 1975 through March of 1978, the MPCA with the aid of a U.S.
EPA grant, attempted to site a hazardous waste landfill in Minnesota.
This attempt was ultimately unsuccessful.*  One of the final four
sites considered was located on land owned by the 3M Company in Cottage
Grove, although not on the same land on which the 3M site was to be
located.  Two public meetings were held in Cottage Grove (in November
1977 and February 1978) to receive public comment on this proposed site.
Public opposition to the proposed site was intense.  About 1,900 people
came to the November meeting to voice this opposition.  Although fewer
people came to the February meeting, they were of the same opinion about
the proposed facility.  At this February meeting, 3M spokesmen gave a
presentation detailing the company's opposition to the proposed site.
The reasons for their opposition were: 1) concern that if contaminants
leaked from the facility this would taint water in company wells and
disrupt production; and 2) that the construction of the facility would
deny the company the option of future expansion at that location.
Specialized production operations at the Chemolite facilty demand large
quantities of consistently pure water.  Since the groundwater flow in
the area of the proposed site was toward Chemolite wells, any leakage
from the proposed facility would have jeopardized these operations.

Of the 820 acres owned by 3M, 385 were already developed and 255 were
non-buildable, leaving 180 acres for possible future expansion.  The
entire 180 acres would have been included in the proposed MPCA site.
   See the Minnesota case study elsewhere in Appendix A.
                                   112

-------
Until March 15, 1978, the Chemolite facility disposed of sludge from its
wastewater treatment plant and ash from its incinerater at the Pine Bend
landfill in Dakota County.  (Boiler ash was buried on-site.)  However,
on that day the MPCA informed the landfill owner/operator that from then
on wastes from Chemolite would have to be buried separately from the
municipal solid wastes which comprised the greater part of the wastes
handled at this landfill.  MPCA was of the opinion that acids produced
by decomposing organic materials in municipal waste could leach heavy
metals out of the Chemolite waste and into the groundwater.  The
Chemolite waste alone is sufficiently alkaline that there would be
virtually no danger of this happening if the wastes were not mixed.
Dakota County officials then informed the owner/operator that such a
change in operating procedures would require an amendment to their  '
existing landfill permit.  The owner/operator in turn decided to resolve
this problem by not accepting any more wastes from Chemolite, and so
informed the company.  Chemolite has been storing sludge and ash wastes
on its Cottage Grove property since March 24, 1978.

Chemolite's decision to store these wastes on their property —albeit
in the absence of any immediately available alternatives — immediately
put them in technical violation of city, county and state law.

In late March, 3M officials consulted with Cottage Grove officials about
their hazardous waste storage problem, and in early May the company
applied for a city permit to establish a temporary hazardous waste
landfill on the Chemolite site.  There was not public discussion of the
proposal until late June, when the proposal was discussed at a Cottage-
Grove City Council meeting.  In the meantime, 3M had also applied to the
MPCA for a permit to -store hazardous waste on its property.

In July the 3M Corporate  Secretary and the Manager of Environmental
Affairs gave a presentation to the Cottage Grove Planing and Zoning
Commission in support of  their permit application.  They reiterated
their opposition to the MPCA/MWCC siting attempt and noted several
significant differences between the two proposals. ' In particular, they
pointed out that their site was not located in the area proposed for
future expansion; that it would cover five rather than 200 acres; that
they had complete control over the wastes buried in the landfill; and
that the wastes they were disposing of would not pose a threat to their
own operations.                                    ,

Also during July, the Metropolitan Council staff tentatively approved
3M's proposal  to temporarily store hazardous wastes at the Chemolite
facility, and  3M signed a stipulation agreement by which they promised
to come into compliance with MPCA regulations (i.e., either  to obtain an
MPCA permit or dispose of these wastes elsewhere) within one year.

There was little immediate reaction to the proposal from the public or
local officials.  The response of the Cottage Grove City Council is said
to have been concern about the possible hazards, posed by the facility,
but not outright opposition.  The reasons  for this concern were two-
fold.  First,  the public  information campaign during the MPCA/MWCC
siting attempt had  emphasized  the hazards  of improperly disposed
                                  113

-------
hazardous waste.  By virtue of this program, the public was made acutely
aware  of the problems associated with hazardous waste but not with
possible solutions.  Second, 3M had previously operated a landfill site
in a neighboring community.  Some material dumped at this site had
leached into the water table and into private wells.  3M had had to put
in two wells to pump out the contaminated groundwater and this operation
is still continuing.  The landfill was closed, and 3M received heavy
criticism from residents and public officials.  After this landfill was
closed 3M installed the rotary kiln incinerator.  Local residents were
also said to be afraid that if 3M were given permission to open a
hazardous waste landfill, the town would be unable to keep out other
such facilities.

Notwithstanding 3M's previous landfill experience, there was no outright
opposition to the facility due to the town's economic dependency on 3M,
and to 3M's reputation in the community as a competent and responsible
firm which would be there long after the site is filled.

The only significant criticism of the 3M proposal came from, state and
regional officials, some of who had been involved with the MPCA/MWCC
siting attempt.  An official of the Minnesota Geological Survey stated
that he opposed the facility because the site is over a Jordan1 sandstone
formation that contains a major water supply.  A member of the MPCA
board questioned what he saw as the double standard being applied to
3M's application.  He felt that the 3M proposal was being evaluated ,
against less strict standards than had been the MPCA/MACC proposal be-
cause of 3M's local political and economic connections.

On August 22, the Cottage Grove City Planning Commission voted to recom-
mend that the City Council consider levying a fine against 3M for stor-,
ing manufacturing wastes on its property without a permit. Concerns
expressed by the Planning Commission included the inherent conflict of a
landfill with the proposed uses of the Mississippi River Critical
Area* inappropriate soil type and bedrock conditions.  The following
week, however, the Planning Commission seemingly reversed itself and
voted to recommend that City Council grant 3M a temporary permit to
store hazardous wastes through December of 1978.  The Commission also
called for periodic testing for leachate from the landfill.

The Cottage Grove City Council voted in September of 1978 to give
preliminary approval to 3M's application to store hazardous wastes until
December, 1979.  The conditions of the permit were that the wastes
eventually be removed from the site; and that if testing showed seepage
from the landfill, the wastes must be removed immediately.  The final
resolution to grant the city permit was approved on October 4.  The
   The Mississippi River Critical Area is a cooridor along both
   sides of the river for which certain strict development controls ap-
   ply.  The recommended uses for this land are recreation and open
   space, but existing uses and related development are allowed under
   certain conditions.                                                 :
                                  114

-------
stipulation was added that 3M must pay for periodic studies to determine
whether any wastes were leaching into the groundwater.  Accordingly, 3M
developed the landfill.  To resolve permanently its waste disposal -
problem, 3M has a number of options, not all of which include an on-site
landfill.  The principal options are:                                •

       o     To dispose of all their ash and sludge wastes in an on-site
             landfill;

       o     To ship all these wastes to an out-of-state hazardous waste
             facility;

       o     To split this waste stream into hazardous and non-
             hazardous wastes, ship the hazardous wastes out-of-state,
             and dispose of non-hazardous wastes in their own landfill
             or at the local municipal waste landfill.

       o     To site a facility elsewhere in Minnesota, either on their
             own property or in an area seeking industrial development.

Currently, 3M is planning to adopt the third option.  All incinerator
ash is already being hauled to a hazardous waste facility in Milwaukee,
Wisconsin.  The MPCA has told 3M that if incinerator scrubber sludge is
separated from the rest of the wastewater sludge, the wastewater sludge
will then be non-hazardous and could be disposed of, separately, in any
sanitary landfill which would accept it.  The incinerator scrubber
sludge would then also be hauled to the Milwaukee landfill.
Furthermore, if 3M can reduce the levels of contaminants in leachate
from this sludge to within an order of magnitude of levels specified in
the U.S. Public Health Service drinking water standards, they would be
allowed to co-dispose of the sludge with municipal wastes in the Pine
Bend landfill.  Levels of contaminants in leachage could be reduced by
mixing boiler ash and lime with the wastewater sludge to increase its
alkalinity.  3M plans to adopt this option and to cease disposing of
wastes on-site as of December, 1979.  From 3M's point of view, the least
costly option would have been to establish a permanent on-site disposal
facility.  According to an official of the MPCA, local opposition to a
permanent facility is to blame for 3M's not being able to do so.
IV.
CHRONOLOGY OF EVENTS
January 19, 1978 —3M announces its opposition to the location of a
                    proposed chemical waste landfill on land at its
                    Chemolite complex in Cottage Grove.

March 15, 1978 — MPCA tells Pine Bend landfill to no longer mix Chemo-
                  lite wastes with municipal solid wastes.  The landfill
                  owner/operator informs 3M that no more Chemolite
                  wastes will be accepted.
                                  115

-------
June 20, 1978,— 3M announces that it is considering a plan to build
                 a chemical waste landfill on its Chemolite site.

June 27, 1978 — Official of the Minnesota Geological Survey says he is
                 opposed to the 3M plan; that the proposed site lies
                 over a Jordan sandstone formation that contains a major
                 water supply.
July 18, 1978 —


July 24, 1978 —
Metropolitan Council staff tentatively approves 3M
proposal to store chemical wastes.

3M officials make a presentation to Cottage Grove Plan-
ning and Zoning Commission in support of their permit
application.
August 22, 1978 — Cottage Grove Planning Commission recommends that the
                   City Council consider levying a fine against 3M for
                   storing manufacturing wastes on its Chemolite
                   property without a permit.

August 29, 1978 — Cottage Grove Planning Commission votes to recommend
                   that the City Council grant 3M a temporary permit to
                   store hazardous wastes through December, 1978; calls
                   for periodic testing for leachate from these wastes.

September, 1978 — Cottage Grove City Council votes to give preliminary
                   approval to allow 3M to store hazardous wastes until
                   Decemer, 1979, with the proviso that these wastes
                   eventually be removed, and if testing shows seepage,
                   that they be removed immediately.

October 4, 1978 — City Council approves final resolution to allow 3M to
                   store wastes.  3M agrees to pay for periodic studies
                   to determine whether wastes are leaching into the
                   groundwater.

February 9, 1979 — 3M announces that the future of the Chemolite plant
                    depends upon their finding an acceptable way to
                    dispose of hazardous wastes.

December, 1979 —   Expected closing date of 3M landfill.

V.     ATTEMPTS TO SECURE SUPPORT

There were few attempts made to secure support for the facility.  These
included:

       o     Discussions about 3M's hazardous waste disposal problem be-
             tween 3M and Cottage Grove officials soon after the closing
             of the Pine Bend landfill to 3M and prior to any public
             disclosure of the problem.
                                   116

-------
 VI.
o     The presentation given by the 3M Corporate Secretary and
      Manager of Environmental Affairs to the Cottage Grove Plan-
      ning and Zoning Commission.

o     The slide show and talk -.- which stressed 3M's economic
      value to the community and its competence in safely
      disposing of its own wastes — which was given
      before all involved government bodies.

SUMMARY EVALUATION
 This  siting attempt  is  noteworthy because  it  so  closely  followed  an
 unsuccessful  siting  attempt  and because  it was  successful,  albeit only
 temporarily.   The major factors in 3M's  being able  to  site  a hazardous
 waste landfill on virtually  the same  site  where  a public agency had been
 unable to only a few months  previously are the firm's  credibility and
 economic leverage, the  small size of  the proposed facility, and 3M's
 ability to control the  .wastes being dumped there.,   Local officials and
 residents seem to feel  that  3M  is competent,  responsible and committed
 to the welfare of the community,  notwithstanding the previous
 3M/Chemolite  landfill experience.   Furthermore,  the Chemolite  facility
 employs about  1,100  people,  roughly 40 percent of whom live in Cottage
 Grove,  and pays approximately $700,000 per year  in  property taxes,  about
 40 percent of  the county's industrial tax  base.

 These  advantages notwithstanding,  the 3M Company mounted a considerably
 more  effective public relations effort had the MPCA and  MWCC.  The
 effort  was low key but  nonetheless reasonably successful.   In
 particular, local public officials were  consulted shortly after the
 siting  attempt  was begun, and public information stressed 3M's
 competence in  dealing with these  wastes.   This contrasts sharply  with
 the earlier attempt, wherein local officials  were not apprised of  the
 progress of the siting  attempt  until after the first set of sites  had
 been  selected,  and wherein public  information stressed the dangers  of
 improperly disposed  chemical wastes.  While ,it is presumably true  that
 3M learned from the  earlier  attempt, it  is also true that their task was
 made more difficult  by  extensive  public  knowledge of the hazards
 associated with chemical wastes.  A 3M official noted that during  their
 testimony in opposition to the  MPCA/MWCC project they should have made
 it clear that they were soon going to face a  similar situation.  He
 further stated  that  their major problem  was timing:  that  they needed to
 site a  facility so soon after a previously unsuccesful attempt.  Not
•only did their  effort suffer because of  the public  information program
mounted during  the earlier attempt, but  local officials had already
 taken  positions opposing any hazardous waste  facilities,  and it would
have been counterproductive  to  bring in  the MPCA to  testify on their
behalf  before local  officials which otherwise could have been done  to
help gain local support.  If the MPCA and MWCC had conducted a
well-designed public relations  effort, he  felt,  the  3M facility could
have been permanently sited.
                                  117

-------
Only a few issues and concerns were raised by the public and local of-
ficials during the siting attempt, although these few were strongly
felt.  These included:

Site Suitability — The 3M property had previously been rejected a un- ,
suitable for a hzardous waste landfill, in particular due to the
permeability of the soil in the area.

Chemical Wastes — Due in large part to the public information campaign
mounted in the previous siting effort, residents were acutely aware of
the many hazards associated with improper storage and/or disposal of
chemical wastes.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Public opposition developed as the result of the following.

       o     Public awareness of the hazards associated with chemical
             wastes, which was largely due to the public relations ef-
             fort mounted during the previous (MPCA/MWCC) siting at-
             tempt.

       o     Local public opposition to siting hazardous waste
             facilities following the state attempt to site
             a facility in Cottage Grove.

       o     Local public feeling that if this facility were sited,
             others would be able to come in.

This opposition was blunted and partially overcome due to the following
factors.

       o     3M's credibility in the eyes of the community.

       o     The economic ties between 3M and the community: in
             particular, employment and taxes.

       o     Early discussions between 3M and Cottage Grove officials
             about their problem and plans immediately following 3M's ex
             clusion from the Pine Bend landfill.

       o     3M's public relations campaign, which stressed their compet
             ence and willingness to deal with their hazardous waste
             problem.

VIII.  RETROSPECTIVE VIEWS

 It was noted by an official of the MPCA that, while the 3M siting
attempt is instructive, it does not point the way to the future of
hazardous waste facility siting in Minnesota.  Most firms which produce
                                -116

-------
chemical wastes do not produce enough to warrant maintaining on-site
disposal facilities, nor would the MPCA1 be amenable to such a
decentralized approach because of the difficulty of enforcing
regulations which this would imply.  Furthermore, most firms have
neither the credibility nor the economic leverage that 3M has.  Local
officials were generally sympathetic to 3Mfs problems and had no
criticisms to make of the way in which 3M handled the siting process,
but indicated that it would have been politically impossible for them to
accept a permanent site so soon after rejecting the state attempt.  They
did feel that since these wastes were being generated in their town and,
in part, to their benefit, there was no rational argument to be made for
letting someone else bear the risk of their disposal.
IX.
GENERAL COMMENTS
A representative of 3M stressed that people who live in the immediate
vicinity of any proposed site should be contacted individually before a
public .announcement of the site is made.  If their particular concerns
can be determined, some might be ameliorated (e.g. concerns about
traffic associated with the site).  This would also help determine the
suitability of the location.  The next step is to contact local elected
representatives.  Only then should the public announcement be made.

He noted as well that public participation in decision making can be
either good or bad, depending upon the procedure followed; that if local
"opinion leaders" can be brought into the process early on, public
hearings can be conducted on a rational basis.

3M also does not view long-distance hauling as a permanent solution to
its hazardous waste problem, and is cooperatng wth MPCA in their'
attempts to site a statewide facility.
                                 119

-------
                KANSAS INDUSTRIAL ENVIRONMENTAL SERVICES

                             FURLEY, KANSAS
I.
INTRODUCTION
In February of 1977 Kansas Industrial. Environmental Services (KIES)
received a permit from the Kansas Department of Health and Environment
(KDHE) to operate a hazardous waste disposal facility.  This event
capped a one-year siting and development process which was marked by
close cooperation and coordination between KIES and KDHE.  By the time
of the Centaur site visit, KIES had modified its original land burial
and treatment lagoon operations and was adding new treatment
capabilities at the site.

The successful siting attempt was not accomplished without public
opposition.  Area residents organized within days of the first public
announcement of the proposed facility.  They raised concerns about
potential ground and surface water contamination and other issues.
While these concerns led to the filing of a suit to enjoin the issuance
of the permit, no sustained effort to block the siting developed.  Since
KIES began operations, residents have complained about odors from the
facility and have sought additional state requirements to reduce
potential problems with the facility.

KDHE was the major party which effectively reduced the public
opposition.  By developing stringent permit regulations with the advice
of state legislators and citizens, KDHE was able to address major
concerns and, for the most part, convince opponents that effective
regulation of the site would occur.  While KDHE received almost all of
the public credit for allaying concerns, the head of KDHE's solid waste
section attributed much of the success to the cooperation the state
received from KIES.  KIES officials attempts to address opponents'
issues met with much less success during the siting process.  KIES has,
however, gained some credibility with area residents through
conscientious efforts to resolve operating problems and a more general
"good neighbor" policy.
 II.
BACKGROUND  INFORMATION
 The KIES facility occupies an  80-acre  tract of land in northeastern
 Sedgwick County  about  15 miles from Wichita.  An additional 80-acre
 tract adjacent to the  site has recently been purchased for future
 expansion  but  to date  has not  been developed.  The land was previously
 used as'grazing  land,  and adjacent land is used primarily for
 agricultural purposes  or as  small  homesteads.  No zoning regulations
 apply to that  area  of  the county.  Though close to Wichita, the site
 itself  is  relatively remote  and the only resident who could see the KIES
 building sold  her land to KIES.  Access to the site is by county roads.
 The Kansas Turnpike (1-35) passes  within ten miles of the site.
                                  120

-------
The site lies within a band of Wellington Clay Shale, which is
particularly impermeable.  Within the bounds of the site, clay depths
range between 80 and 109 feet from ground level to a permeable limestone
stratum beneath the site.  Clay depths from the bottom of disposal
trenches to the limestone are about 65 feet.  The clay has a
permeability in the range of 10~9 to 10"^ cm/sec and a plasticity
index greater than 45.  There is a perched aquifer within the clay
stratum in one area of the site, but this has been specifically excluded
from development as a disposal area.

As first developed, the facility design encompassed burial of drummed
waste and evaporation of liquid wastes.  A total of 30 acres was
engineered for burial with the assumption that this would provide 30
years of capacity.  Four small treatment ponds for acid neutralization,
chrome waste stabilization, oxidation and other treatment were
originally developed.  Two large (400 by 200 feet) evaporation ponds
were also a part of the original design.                            ,

Based on its operating experience, KIES has changed and expanded its
operational capabilities.  Wastes 'are now buried in small trenches
designed to accommodate a specific waste stream.  These can be closed
fairly quickly and used year-round.  (The large "bath tub" originally
used for burial was restricted to about six months of operation and
involved periodic pumping to eliminate standing water).  KIES has added
63,000 gallons of liquid storage capacity for wastes which it sends to
reclaimers or incinerators.  Treatment capability for cyanide and
hexavalent chromium waste was being developed during the Centaur site
visit.                          ..•..-

The entire site is ringed by a 200-foot buffer strip of unused land.
Catchment ponds are designed to receive all on-site drainage and can
hold the equivalent of two 100-year storms in a two-day period (about 12
inches of rain in 24 hours).  Ponds are monitored quarterly.  Off-site
runoff is diverted from the site.  Monitoring wells are tested.monthly.
All tests are done by an independent lab approved by KDHE.

KIES's permit requires a complete post-closure plan one year prior to
closure.  KIES has already submitted this plan to the state but expects
to upgrade it in response to new state regulations developed in response
to RCRA.

KIES was established in 1976 specifically for the purpose of developing
this facility.  While KIES had no prior experience with hazardous waste
management, its two principals combined operating experience with
wastewater treatment facilties and a long-standing commitment to
environmentally sound land use practices.  Key administrative people
with laboratory research, pollution control, and hazardous waste
management and planning experience were recruited from Vulcan Chemicals
Company and a consulting engineering firm.  KIES employs about ten
operational staff at the facility.  A separate division of KIES provides
hazardous waste hauling services and employs an additional 12 to, 15
                                   -121

-------
persons.  KIES owns a fleet of a dozen trucks in a range of sizes to
handle any specific hauling need.  Hauling is regulated by the Kansas
Corporation Commission and applicable federal regulations.  In addition
the KDHE permit specifies a manifest system to track all wastes hauled
and disposed of by KIES.  While most KIES monitoring tests are performed
by an independent laboratory as a condition of the permit, KIES has its
own on-site lab.  At the time of the site visit, KIES was planning to
redevelop its lab facilities.

KIES accepts a broad range of hazardous waste including acids,
alkalines, solvents, small amounts of pesticides, and some
PCB-contaminated material (e.g., electrical transformers).  Specifically
excluded are radioactive waste, bulk pesticides, and large volumes of
PCBs.  Some wastes which are accepted by KIES are not disposed there but
are hauled to other facilities.  Typically these are wastes that should
be incinerated or that can be reclaimed using technologies that KIES has
not developed.

KIES1 most immediate market area is Wichita and nearby areas of
Oklahoma.  In its short operating history, however, it has dramatically
expanded its effective market.  KIES had disposed of wastes from as far
away as Minnesota, Tennessee, Colorado and Texas.  Some,of these market
areas are ones which KIES hopes to serve with future facilities.

KIES has initiated a rather ambitious campaign to develop new sites.
Work on an Oklahoma site has been underway since 1977 and a final permit
application was expected to be submitted in March, 1979.   By the end of
1979, KIES hopes to submit plans for facilities in Missouri and Iowa.
Additional sites in two other states are contemplated.

KIES is located a few miles from Furley, Kansas, a town with a
population of about 50.  The northeastern corner of Sedgwick County is
largely devoted to farming, small-scale oil production, and small
homesteads for those working in the Wichita area.  Wichita (1977
estimated population, 263,000) is the largest city in Kansas and a major
center for small aircraft manufacturing.  With a broad range of goods
and services available, the Wichita-Sedgwick County metropolitan area is
a major trade and service center for south central and southwestern
Kansas.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC REPSONSE

To operate a hazardous waste landfill in Kansas a facility must have a
permit from KDHE.  The need for a local permit depends upon whether the
site is subject to local zoning.  The area of Sedgwick County where KIES
is located does not have zoning.  (The majority of Kansas counties do
not have county-wide zoning.)  As a result, KIES required only the KDHE
permit in order to operate.

KDHE permit procedures involve a two-stage process.  When an application
has been fully prepared through the stage of engineering design, KDHE
authorizes facility construction by letter.  When construction is
                                    122

-------
completed and meets state requirements, a permit is issued and
operations may begin.   According to the chief of KDHE's solid waste'
section, only pennittable facilities will reach the stage of
construction authorization.  . Emphasis is placed on extensive involvement
by the state in the development of the application from site selection
through construction.   In this manner, KDHE can be assured that the
final application for a permit meets all requirements and is approvable.
Once a permit is issued, operational changes and facility expansions
need only KDHE approval rather than a new permit application.  In
addition to granting a permit to operate, KDHE must approve each
hazardous waste by source before it may be accepted by a facility.

Planning for the KIES facility began in early 1976.  The principals of
KIES had determined that a" market for industrial waste disposal existed
in the state.  Consulting engineers experienced in the design of  •
hazardous waste facilities in Oklahoma were retained and KIES approached
KDHE in April to determine what state requirements and regulations.would
apply to the proposed facility.

At that time Kansas had no regulations specifically applicable to
hazardous waste landfills.  The only existing state regulations were
those for sanitary landfills.  The development of the KIES facility thus
provided the initial impetus for the development of state hazardous
waste disposal regulations.  (Continuing local concern 'with KIES and the
passage of RCRA have ensured the continued upgrading and expansion of
the state's regulations.)  The need to develop these regulations
contributed to the close working relationship between KDHE and KIES
during the development of the permit application.

KIES1 siting process (as described by KIES1 general manager and KDHE's
solid waste section chief) began with preliminary surveys of state
geology.  With state concurrence, this survey narrowed the area of
potential sites to a band of Wellington Clay Shale, which has particu-
larly low preineability characteristics.  Within that clay band, areas
with unsuitable hydrogeology (e.g., presence of aquifers subject to
vertical percolation) and topography (e.g., floodplains) were excluded.
Aerial surveys were conducted to judge transportation access, population
density, and topography.  By that process ten sites were selected for
soil tests by a private soils engineer.  In the spring of 1976, tests
run on the sites included assessments of the proportion of clay to other
soils the presence of perched and major aquifers and, by laboratory
analyses, the clay's permeability, plasticity, shrinkage potential, and
reactivity to specific chemicals.  Following these analyses five sites
were selected as qualified for development.

The final site selection rested on several additional considerations.
The Furley site is not subject to local zoning.  The site, though not on
the market at that time, could be purchased from the previous owner.
The site was purchased quietly, with no publicity.
                                123

-------
 In late May, KIES submitted  an  application  to KDHE for approval to
 establish and operate an industrial waste landfill.  The application was
 accompanied by preliminary plans  for  site design and facility operation.
 Also submitted to KDHE in late  May and early June were; soil reports,
 monitoring well design, and  drainage  plans.  All were prepared by KIES
 consultants.

 In late June of 1976, KDHE notified local officials that it would hold
 an informational meeting on  the KIES  facility.  This was the first
 knowledge officials and residents of  the Furley area had of plans for
 the disposal site.  Although work on  site testing and engineering design
 was not complete, KDHE indicated  that a permit would probably be granted
 to KIES.

 The notification, given about a week  before the meeting, produced a
 quick and vocal response by  area residents.  An article in the Wichita
 Eagle reported that about 150 residents were "fighting mad" and would
 take any legal steps necessary  to stop KIES.  Concerned residents met
 two days before the meeting, organized a committee, and hired attorneys.
 Prior to the meeting, residents expressed concerns about potential
 environmental and economic impacts, the site location and opportunities
 for local participation in decision-making.  They foresaw the potential
 for air and water pollution  and felt KIES could not predict what
 pollution would occur.  Drainage from the site was feared.  One resident
 noted that local regulations had banned runoff from feedlots into the
 area's streams and that the  impacts of chemicals would be far more
 serious than those of manure.   Several residents predicted that land
 prices would fall.  Residents felt the site was in too populous an area,
 which in 20 years would likely  become part of Wichita.  Residents did
 not like the thought of being known as "the dumping ground of Kansas" or
 "a guinea pig for the rest of the state".  Finally, the fact that only a
 few days' notice of the meeting was given left the impression that
 facility development was being  rushed along without the local
 community's knowledge.                           .

 The informational meeting was held in Witchita on June 30, 1976.   It was
 conducted by KDHE's director of the Division of Environment and attended
 by about 200 local residents.  KIES' engineering consultant was also in
 attendance.  KDHE made a presentation and KIES' consultant responded to
 concerns voiced by attendants.  Opponents doubted the validity of
 research prepared for KIES,  specifically soil tests indicating low
 permeability.  Although KIES' consultant responded to these concerns, he
 was unable to convince opponents that there would be no detrimental
 impact on the environment.   Indeed, some in attendance felt that neither
 KDHE nor KIES' consultant could satisfactorily answer any of the
 questions raised by residents.  An attorney for the opponents declared
 that the public had not had  sufficient time to consider the proposal and
 demanded more time.  KDHE agreed to a second public meeting.   The
 meeting did little to allay  public concerns.  Opponents'  earlier threats
 to sue in order to stop the  proposal were repeated at the end of the
meeting.
                                 -124

-------
Subsequent to the first public meeting, KIES .submitted additional soil
test results to KDHE.  By early August, KDHE was satisfied that all .data
requirements had been fulfilled and work proceeded on a draft of the
permit for the KIES facility.  By mid-October, 1976, KDHE was close to a
final version of the permit and scheduled a second public meeting.

On October 14, the second public meeting was held in the Wichita area.
KDHE's Division of Environment director again conducted the meeting and
outlined the regulations which would be applied" to KIES.  The permit was
developed by KDHE with recommendations from a study group established
after the second public meeting by the Kansas legislature and a
citizens' group.  The permit restrictions were considered extremely
stringent by state elected and appointed officials and were described by
EPA Region VII staff as among the tightest in the nation.  Comments by
proponents and opponents, both at the time of meeting and during
Centaur's site visit, indicated that the permit, had a substantial impact
on reducing opponents' concerns.  In addition to imposing stiff controls
on KIES, KDHE also strongly supported the development of the facility.
KIES had also come prepared, and presented a complete flowchart of
proposed facility operations, the manifest system to be used, quality
controls over facility construction and operation, and  fire fighting
safeguards.  KDHE told those at the meeting that KIES had .not only
submitted all required information, but also exhausted  all data
possibilities in preparing the application.

The major conditions of that permit included the following: approval by
KDHE of  all wastes accepted; approval  by KDHE of all  transportation
routes;  maintenance  of records of wastes received and analyses of those
wastes;  payment  of an  annual fee  for KDHE on-site inspection- costs; cost
and security bonds;  liability insurance; and criminal and civil
penalities  to  insure compliance.  Although not  developed  at  the  time  of
the meeting, a  post-closure  plan  would be required before the final
permit was  issued.   The  permit was  issued subject to,annual  review  and
approval and  to  amendment at any  time  based on  the development of. new
regulations  and requirements.  The  permit did allow KIES  to  expand  the
facility or  change procedures subject  to KDHE approval.

 In mid-November, KIES  agreed to all conditions;of the permit and KDHE
authorized  facility  construction  in accordance  with approved, plans  and
specifications.   Construction began, and with some  additional
modifications required by KDHE was  completed in late  January of  1977,
 On February 1,  KDHE  issued  the permit  allowing  KIES to  begin operations.

 While the  second public  meeting substantially reduced public concerns,
 it did not  eliminate them altogether.   After that meeting the  area's
 state representative said she  and othe'r  legislators would seek to delay
 permit issuance until after the legislative session began in January  of
 1977.   In late January,  a group  of  local  opponents  sought a  temporary
 restraining order on the permit issuance.   The  suit was based  primarily
 the fact that some KIES engineering work had been signed by  an engineer
 registered in Oklahoma,  but not in Kansas.

-------
 According to a KDHE official, opponents resorted to this technicality
 because they could find no substantive dispute with the permit.  The
 matter was settled out of court and no permanent injunction blocking
 permit issuance was ever obtained.

 In March of 1977 KIES accepted its first load:;four five-gallon cans of
 pesticide.  Since that inauspicious start, the volume of wastes handled
 has increased substantially, to the point where the original site life
 of 30 years has been reduced by as much as 40 to 50 percent.  KDHE
 estimates about 70 percent of this waste is from out-of-state
 generators.  KIES' general manager explained that more than fifty
 percent of the present volume would be diverted to new sites KIES hopes
 to develop in the future.

 Facility operations have been changed since operations began.   Small
 trenches have been added for burial of individual waste streams and
 allow for greater control than did large disposal trenches.   Storage :
 capacity of 63,000 gallons for liquid wastes has been added.   At the
 time of the site visit KIES was developing waste treatment capabilities
 for cyanide and chrome wastes.

 Since operations began,  the most frequently cited complaint  by local
 residents has been odors.   On several occasions  the treatment  of wastes
 has generated obnoxious  odors,  in one case for a period of about two
 days.   According to area residents,  these have been a continuing source
 of  irritation.   KIES has responded in two ways.   First,  it has improved
 its operating procedures  to minimize any odors.   Secondly, it  has
 sometimes helped state health officials  find the source of odors,  not
 all of which have come from its site.  According to KIES, odors have
 been tracked to  old gas wells,  ruptured  pipelines,  manufacturing plants,
 feedlots,  and in one case,  the barnyard  of the resident who  had lodged
 the complaint against  KIES.   In spite of  this, residents appear to  blame
 KIES for most odors in the area.

 In  addition to  attempting  to  respond conscientiously  to  odor complaints,
 KIES has  pursued a  "good neighbor" policy  in small  ways.  KIES helps to
 maintain local  roads  in winter  by  plowing  snow with it  own equipment and
 has  helped pull  residents'  cars  out ,pf snow drifts.   It has provided
 free earth moving service  to  a  local farmer.   To  the  extent possible,
 KIES uses area businesses  for needed parts  and fuel oil.  A KIES
 employee  lives on-site and local  residents  have  shown little reluctance
 to  contact him with concerns or complaints.

 According to  the  former chairman of  the opponents' organization, KIES
 has  gained a  certain respect  locally.  He  indicated  that KIES has been
able to reduce odor problems.  On the other hand, he felt that  some
 promises made by KIES  and KDHE at  the public meetings had not  been kept.
 He cited the case of runoff after a  particularly bad rain, and mentioned
 the KIES statement  that this would not happen.   (According to KDHE, the
rain was the equivalent of a 500-year storm, which overtaxed the site's

-------
safeguards designed for two 100-year storms in two days.  KDHE also
stated that no adverse impacts resulted from the runoff.)  He also
referred to KIES1 projection of a 30-year site life versus the current
projections and the KIES purchase of an additional 80 acres for
expansion.  He also felt the state had not inspected KIES weekly as
promised and nor had it seemed sufficiently concerned about its
regulatory responsibilities.  A major problem, he felt, was reliable
information which could conceivably show that local concerns were
unwarranted.

The ex-chairman and KIES general manager both indicated that, while lo-
cal concerns had been reduced, major opposition could easily revive.
This uneasy relationship has been reflected in the local media's cov-
erage of KIES.  In January of 1978, the Wichita Eagle ran a full-page
article on the site.  The article described of the KIES facility in the
context of state and national efforts to upgrade hazardous waste
disposal.  While making some reference to past opposition, the article
described KDHE's support for KIES and was generally favorable.  In
October, 1978 several articles appeared following some discussion of
constructing an incinerator at KIES.  The incinerator proposal was not
pursued.  However, residents interviewed at the time repeated issues and
complaints that had been raised since June of 1976.  Although the
articles reiterated support for KIES on the part of state and local
health and environmental officials, the overall impression was one of
local hostility.  After those articles were published, KIES played the
major role in cleaning up a nitric acid spill at a titan missile silo.
According to KIES1 general manager, local media generally praised KIES
for its activities.

KIES' current status with local residents appears to be one of cautious
and concerned co-existence.  The day Centaur spoke with the ex-chairman
of the opponents' organization, another ex-leader of the opponents was
in Topeka to discuss developing new legislation with the area's state
representative.  The bill, if proposed, would be aimed at reducing odor
problems at KIES.  These discussions underscored the feeling that res-
idents did not want to close KIES but did want to make sure that every
precaution would be taken to safeguard operations.
IV.
CHRONOLOGY OF EVENTS
Early 1976 —KIES begins planning for facility, hires consultants.

April, 1976
Late May,
Early
June, 1976 —
Late
June, 1976 --
        KIES and. KDHE hold initial discussions over facility de-
        velopment.
       KIES submits preliminary plans for approval by KDHE and
       submits supporting test results.
       KDHE announces proposal publicly, holds first information
       meeting, and promises second meeting.

-------
August,  1976  — KDHE informs KIES that all  data requirements to date  -
                have been met.

October,  1976 —  Second public meeting held, concerns are substantially
                  reduced by KDHE permit restrictions.

November,  1976 — KDHE authorizes facility  construction.

January,  1977 —  Citizens suit to enjoin permit issuance is filed but
                  resolved without injunction.  Construction of facility
                  is completed.

February,  1977 — KIES permit to operate is granted by KDHE.

March, 1977 — First wastes are accepted.

1977 — Problems  with handling oil refinery waste lead to citizen com-
        plaints of odor.  Periodic odor compliants,continue to
        recur, although at a reduced rate.

January,  1978 — Wichita paper writes long  and generally positive
         article on KIES and general topic  of hazardous waste
         management.

October,  1978 — Possibility of constructing an incinerator at KIES
                 generates media attention  to residents' concerns and
                  complaints about KIES.

1979 — KIES handling of nitric acid spill  in titan missle silo attracts
        favorable media attention.

Spring of 1979 — KIES develops new treatment capabilities for cyanide
                  and chromium waste.
V.
ATTEMPTS TO SECURE SUPPORT
The following are the major efforts to inform the public of KIES and ad-
dress public concerns.

       o     The June, 1976 public meeting where KDHE and the primary
             consultant for KIES first explained the proposed facility
             and state regulations and responded to opponents'  concerns.

       o     The October, 1976 public meeting where KDHE outlined the
             permit restrictions which would apply to the facility.

       o     Efforts by KIES staff to reduce odor problems and to help
             identify sources of odors.

       o     A range of efforts and actions by KIES which amount to  a
             "good neighbor" policy.
                               -128

-------
VI i
SUMMARY EVALUATION
The cumulative effect of the attempts to generate support has been to
reduce what was initial total opposition to the development of the
facility.  Currently there appears to be a cautious willingness on the
part of nearby residents to let KIES operate.  This by no means trans-
lates into local support for KIES, but more nearly reflects the attitude
of a "good loser," as one resident termed it.

The major factor in effectively overcoming public opposition was KDHE's
ability to demonstrate tight controls over facility design and oper-
ation.  As described earlier, KDHE's performance at the second public
meeting met with general expressions of satisfation from those who had
opposed the facility.  Just as important as KDHE's response to public
concerns was its steadfast support for the KIES proposal as a desired
solution to hazardous waste disposal problems.  Commendations for KDHE's
role have been made by a range of parties from KIES officials to local
opponents whose individual'interests were divergent and sometimes
completely opposed.  KDHE's solid waste section chief suggested that the
agency's general credibility with citizens was a significant factor in
allaying, specific concerns about KIES.  KDHE was in this case able to'
perform the delicate balancing act of safeguarding the public health and
at the same time encouraging and supporting environmentally sound
hazardous waste management.

The ability to allay public concerns is more significant in light of the
earlier public meetings and post-operational attempts to secure support.
That the .first public meeting was unsuccessful (one regulatory official
called it a disaster) in reducing concerns is evidenced by the fact that
a second public meeting was held.  Various regulatory officials
indicated that the failure of the meeting was attributable to poor
preparation.  Despite the fact that the bulk of site investigation and a
significant amount of site engineering had been completed, KIES was
unable to persuade the public that the proposal was credible.  The
failing then was not primarily defined in terms of information, but
rather in terms of communications and public relations.  Newspaper
articles prior to the meeting citing KDHE's almost certain approval of
the proposal undoubtedly added to area residents' concerns.

Since operations have begun, KIES has worked in many ways to gain the
trust and respect of area  residents.  Based on limited contacts with
former opponents, it appears that KIES has had some success.  However,
residents* deeply rooted concerns (e.g., eventual water contamination)
have changed little*  This experience suggests that even the operator of
the best managed facility has very real limits placed on its ability to
reduce public concerns.  More simply, the local community may never
accept and never completely trust the facility operator.
                                    123

-------
 Facility opponents raised a number of issues.  The major issues follow:

 Contamination of water and other media — Opponents felt that the site,
 its design and regulations did not adequately protect surface and
 ground-water from potential contamination from chemical wastes disposed
 of at  KIES.  Less well defined were concerns that the soil and air
 would also be polluted.  They also felt that KIES could not predict the
 facility's environmental impacts.

 Site location — Opponents felt that the site was not sufficiently
 isolated.   While that section of the county is not densely populated,
 opponents  stressed its proximity to Wichita (about 15 miles) and the
 potential  in the future for urban development to envelop the area.

 Economic disbenefits — Residents feared that nearby land values would
 fall if the facility were developed.

 Equity issues and local image — There were general concerns about the
 equity of  choosing the Furley area as a site.   Opponents did not want  to
 gain the notoriety of being the industrial dumping ground of Kansas.
 Similarly,  they did not want to become the "guinea pig"  for developing
 appropriate hazardous waste disposal  practices.   This latter concern
 reflected  a more general concern over the reliability of these
 practices.

 Public participation opportunities — The outcry prior to and during the
 first public meeting was compounded by the complaint that local
 residents were not being adequately informed and were not given  any
 meaningful  role in the decision-making process.

 Since KIES  has begun operation two issues have  evolved:  odors, and site
 monitoring.

 Odors — These  are the most  salient impact  of operation  and  have
 generated the  bulk of the complaints.   These complaints  have diminished
 because  of  KIES efforts  to control  odor  problems  and (perhaps) because
 of  odor  surveys which have  shown  barnyards, pipelines, and other  sources
 of  odors in the area.                                  ;

 Site  monitoring — There  appears  to be  some concern  over  whether the
 state is adequately  performing  its monitoring and inspection functions.
KDHE  states  that monitoring  is  performed  weekly,  but  opponents seem to
 doubt  this.  They  also feel  uninformed  about the  results  of  on-site
monitoring.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

The following were major  steps leading to public opposition.

             KDHE's announcement of the first public meeting to acquaint
             the public with the KIES proposal.       '

-------
       o     Statements by KDHE officials reported by the press prior to
            . the first meeting that nothing in the proposal would
             disqualify the site on technical grounds.

       o     The inability of KIES and KDHE to convince opponents of the
             soundness of the proposal and of state controls over the
             facility in the course of the first public meeting.

The reduction of public concern and opposition was attributable to the
following.

       o     KDHE's demonstration at the second public meeting of strong
             regulatory controls over KIES.

       o     The ability of KDHE to include state legislator and
             citizen concerns in the development process for the KIES
             permit.

       o     The close cooperation between KDHE and KIES throughout the
             siting process, particularly in regard to the
             development of KDHE's regulatory program for hazardous
             waste management.

       o     A final important factor may have been the lack of major
             national publicity of hazardous waste problems during the
             siting.  Love Canal and other hazardous waste disasters be-
           •'- came general public 'knowledge subsequent to the issuance of
             the KIES permit.

VIII.  RESTROSPECTIVE VIEWS

Comments  on the siting process by area residents have focused  on two re-
lated  issues: ongoing provisions  to ensure safe operations and the
public availabilty of reliable information pertaining to those opera-
tions.  At the  close  of  the  second public meeting  residents indicated a
need to be reassured that adverse  impacts would be eliminated  or re-
duced.  During  the  site  visit a former opposition  leader reiterated  this
concern and stated that  the  lack  of information on site monitoring
prevented citizens  from  knowing what  impacts  had  occurred.  Locals did
not know  the state of affairs and might  have  no cause to worry.  He  felt
that a small citizens' committee  with the  resources  to  independently
analyze water samples  from monitoring wells  would  provide  a means to
reliably  inform residents  on facility operations.
 IX.
GENERAL COMMENTS
 The KIES general manager (who had previous hazardous waste experience as
 a consultant and state official)  made a number of comments regarding
 state and industry roles in siting.   As in the KIES siting process,  he
 felt states should play a strong  role but were constrained by a shortage
 of well-qualified staff in hazardous waste offices and a lack of oper-
 ational experience with facilities.   By consulting with other state
                                    131

-------
 agencies, hazardous waste offices could substantially increase available
 expertise.  This pooled talent could help states scrutinize permit ap-
 plications and focus on permit deficiencies.

 While a strong state review of permits was critical, the ,KIES official
 felt this should not slow down the permit process.   Three to six months
 should be allowed for permit review, with definite time limits placed on
 other state agency and public comments.   Lengthy review periods would
 substantially increase industry costs and begin to drive out smaller
 companies with limited capital.

 Public participation was seen by KIES as a state function.   State
 agencies should take the lead in conducting public meetings and not  '.
 place the burden on industry  to provide all information on facilities
 and safeguards.  From industry's point of view, public input should help
 point out problem areas which industry and the state can then address
 and correct.   The KIES general manager cited the format employed in
 Oklahoma as a possible model for public  input.  In  that state,  public
 commenters may only address technical issues and only under oath;
 cross-examination is allowed.

 A final public agency role is  the development, and dissemination of
 reliable public information.   Distinctions between  Love Canal and sound
 disposal practices need to be  publicly understood.   The desirablity of
 incineration  and other techniques over the burial of any hazardous waste
 should be publicized.   The KIES official felt that  the  public,  the
 media,  and even some regulatory officials are not sufficiently
 knowledgeable about current management practices and as a result  impeded
 the development of sound hazardous waste management.

 One role which KIES felt to be inappropriate for government was site
 ownership.  The inevitable increase  in administration would not result
 in any greater public acceptance of  sites.   Financial and institutional
 arrangements  would be chaotic.   This  approach might  also lead to
 increased centralization in industry (because larger companies  could
 demonstrate greater experience)  without  any guarantee that  this would
 result  in better disposal  practices.

 From KIES'  perspective,  this siting  experience has  provided two particu-
 lar  lessons for future  siting.   Given the need for a  strong  state role,
 the  disposal  industry should help  pay state costs.   By  providing  the
 state a.  share of gross  revenues  (KIES provides about  5  percent),
 industry can  defray part of  the  costs of monitoring  sites and
 administering  regulations.   Industry  also needs  to amass as  much
 information as possible when developing  new sites.   In  many  cases this
 will require  significantly more  data  than minimally required  by states.

 To date, EPA  Region VII has played a  minor  role  in siting.   It has not
 reviewed  any  permit  applications nor  has it  asked to  do  so.    Instead it
has  provided  quiet  support for sites  which  states have determined  to be
good.  In rare  instances,  Region VII  staff  have  discussed general

-------
problems of hazardous waste management and the need for sound disposal
sites with opponents of specific sites.

According to regional staff the implementation of RCRA could drastically
change the EPA role, impede siting, and change the status of disposal in
the region.  It was considered possible that some Region VII states
would ask EPA to implement RCRA.  Yet only one-third of the estimated
personnel needed by the office to implement RCRA has been budgeted.
Recently issued regulations for public particiption could add six months
to two years to the siting process.  This could drive public
participation costs to a level equal to the rest of siting costs.  If
these estimates are at all accurate, siting costs will mushroom and a
number of potential facility sponsors will drop out.  This would clearly
result in a slower rise in regional disposal capacity.  That disposal
capacity could drop drastically when RCRA is implemented, as the office
expects only two sites in the region to meet the new regulations.

The regional office sees the major siting issues as follows:  Do sites
meet, or preferably exceed, minimum technical standards for safety?  Are
funds for all post-closure costs and eventualities available
perpetually?  Are  facility sponsors and operators qualified and
trustworthy?  Can  site proponents communicate clearly and effectively
with local  officals and concerned citizens?

-------
                            BOB'S  HOME  SERVICE
                          WRIGHT CITY, MISSOURI
 I.
INTRODUCTION
 Bob's Home  Service  (BHS)  is  a  hazardous waste  landfill which began
 limited  operations  in 1976 and received a permit for full operation in
 May, 1977.  That  permit was  issued by Missouri's Department of Natural
 Resources (DNR) which played an active role in the development of the
 facility's  transformation from a  sanitary landfill to a hazardous waste
 landfill.

 Opposition  developed  prior to  the issuance of  the DNR permit and con-
 tinued for  several  months.   Two different groups expressed opposition:
 a homeowner's association representing a second home development
 adjacent to the site  and  permanent residents of Wright City.  While much
 opposition  was based  on general objections to  the development of any
 hazardous waste disposal  facility, the potential contamination of
 surface and groundwater were specific issues.                          ,

 Several attempts were made by  BHS and DNR to address general concerns
 and specific issues.  These  included specific  operational procedures
 taken by BHS to monitor and analyze runoff from the site.  It appeared
 that these  actions  were largely successful in  reducing expressed con-
 cerns.  It  was indicated, however, that this partial success by no means
 suggested public acceptance  of the facility.
II.
BACKGROUND INFORMATION
The BHS site is located approximately five miles south-southwest of
Wright City.  The facility is within the bounds of a 150-acre farm owned
by BBS's owner/operator who is also at the site.  Inter-city access, is
via 1-70; the route to BHS goes directly through Wright City.1  The
site is surrounded by forest, which lowers the its visibility.  There is
a small number of year-round homes along the half-mile road which gives
direct access to the site.  Immediately south of the site is a develop-
ment of vacation homes built around a lake.

The hydrogeology of the site was described by DNR and by Reitz and Jens
(engineering consultants to BHS) as being particularly suited to
   BHS representatives indicated that an alternative route to the
   site which involved passing by fewer residences is available.   This
   route, however, is longer and because DNR does not regulate routes
   is not used by trucks coming to BHS.
                                   134

-------
hazardous waste disposal.  The uppermost geological stratum is glacial
till with a rated permeability in the range of 10-8 to io-9 cm/sec.
According to Reitz and Jens, this till is not subject to shrinkage as is
clay.  Beneath the till is a shale and limestone formation approximately
160 feet thick.  This formation reportedly has a low permeability and
carries little groundwater.  A stream bed which has an intermittent flow
crosses the site and eventually empties into the lake around which the
vacation home development has been built.

The facility operates as a landfill for sludges and solids.  The
original design called for two large trenches (20 x 30 x 200 feet), each
of which would accept drummed and bulk wastes.  One trench was for
acidic wastes; the other for alkaline waste.  At DNR's direction this
design was changed to four trenches to allow for the segregation of
drummed and bulk wastes.  Currently the use of trenches has been
abandoned in of favor small holes (3 feet in diameter, 27 feet in depth)
which can accommodate eight drums.  The use of holes has eliminated the
need for pumping standing water from trenches.  This water would have
had  to be held in ponds, analyzed, and land applied^  This new disposal
procedure also allows for greater isolation of individual waste streams,,
surer cataloging of buried wastes, and involves fewer problems with
operating equipment.  There are only minor changes in the site's
capacity.

A broad range of hazardous waste is accepted including acids, bases,
organics, and flammables; specifically excluded is radioactive waste.
Virtually no liquid waste is accepted except in extremely small
quantities.  While the St. Louis area is the primary market area for
BHS, out—of—state waste has been accepted from as far away as Georgia.

The  facility encompases 15 acres and the life expectancy was estimated
at five to ten years.  BHS's original intent was to develop the entire
150-acre site.  This was reduced 90 percent because of DNR's requests
for monitoring wells at 100-foot intervals around the perimeter of the
site.  BHS considered this too costly.  The final plan includes 16
monitoring wells.  .                                                 ,

Post-closure provisions will, at a minimum, adhere to state require-
ments.  As proposed, state regulations specify operational procedures
for  facility closure and the development of a post-closure fund to cover
contingencies when the facility operator cannot be held legally liable.

BHS  is a privately owned company.  Prior to the development of the
hazardous wast landfill, BUS operated a sanitary landfill at the same
site.  In addition to the landfill, BHS also hauls wastes.  For the
first year of its operation, BHS hired Chem-Dyne to manage daily
operations.  Since then BHS has hired its own operations staff.  The•
Wright City facility is the only BHS disposal operation.
                                     135

-------
 Wright City (1976 population:  1,170) is located in Warren County (1976
 population:  12,430) about 50 miles west of St.  Louis.   Until the late
 1960's the County was solely a farming area.   Since then there has been,
 an increase in the number of residents who live  in the  county and
 commute to the St. Louis metropolitan area.  Due in part to the lack  of ,
 county zoning, the area has been particularly attractive to the
 development of small homesteads.

 III.    HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

 In Missouri,  primary regulatory responsibility for hazardous waste
 facilities rests with DNR.  DNR regulations do not override local
 zoning;  however, Warren County has no zoning.  The county does license
 landfills, but this licensing cannot, in the  opinion of Missouri's
 attorney-general,  apply to hazardous waste landfills.   Thus,  in the case
 of BHS,  the state permit was the  only applicable regulation.

 In the summer of 1976 DNR had only rudimentary regulations covering the
 disposal of special wastes (i.e.,  those "requiring handling other than
 that  normally used for municipal  wastes," as  defined by then existing
 state law).   According to DNR,  the permitting, of BHS as a disposal site
 was based on  the professional judgment  of DNR staff who determined what
 restrictions  would apply to,a given site on a case-by-case basis.

 The origin of BHS's facility was  tied to the  need of a  St.  Louis
 Monsanto facility  to dispose of sludge  generated in a silicone  purifi^
 cation process.  According to DNR,  Monsanto had  been disposing  of  that
 sludge at a landfill about 15 miles  from the  BHS site.   Because of  the
 marginal geology at that site,  the state stopped Monsanto  from  taking
 its sludge there in 1976.   Their major  problem then was  to  find a
 suitable site.   One option was  for Monsanto to dispose  on-site.  Ac-
 cording  to BHS,  Monsanto had a  temporary  permit  to  do that  but  only
 under the condition that the company  eventually  exhume  the wastes.
 Another  option was  to  landfill  the  sludge at  BHS.

 In the summer  of 1976  arrangements were made between BHS, Monsanto, and
 DNR for  disposing  of Monsanto1s sludge.  According  to BHS, Monsanto con-
 tacted the company  about using  its site and BHS  in  turn contacted DNR.
 A  DNR official said that the department was aware  that  the  geology of
 the BHS  site was good  and  wanted to discontinue Monsanto's use  of the
 other site.

 BHS then hired engineering consultants who  began to  investigate the
 site's potential for hazardous waste  disposal.  According to Reitz and
Jens,   the results of soil  tests conducted in August  of  that year con-
 vinced DNR of the site's suitability.  DNR  then encouraged BHS to close
 down  the  sanitary landfill operations and develop the site as a haz-
ardous waste facility.  Accordingly, a trench was developed to accept
Monsanto's sludge.   BHS first accepted sludge in August of 1976.
                                  136

-------
For the first month, BHS accepted the sludge under the state's "good
graces."*  In the latter part of September DNR issued a temporary
permit allowing BHS to accept the Monsanto sludge for 90 days.  This
permit was subsequently extended until May of 1977, when a permanent
permit was issued.  In encouraging BHS to develop a hazardous waste
facility, DNR stipulated that a detailed engineering plan be developed
by BHS and approved by DNR before a permanent permit wo.uld be issued-.
As described earlier, BBS's original plan for two trenches was changed
to four trenches at DNR's request.  The original plan for engineering
the entire 150 acres was reduced to 15 acres because of the state's
demand for monitoring wells and the cost of those wells.  The final
agreement on providing safeguards against the migration of chemicals
also included the excavation of any sand lenses uncovered during the
excavation of the trenches.                                      '    ,

Following standard operating procedures, DNR did not provide for public
participation during the review of the permit application.  On May 24,
1977, DNR notified state and local elected officials that approval had
been given to BHS.  The following day the permit was formally issued.

The same day that the permit was issued (i.e., May 25), the attorney for
the second home developments adjacent to the site filed suit to close
the facility.  The petition filed with the court argued that the  ,
facility was a nuisance and that it was accepting toxic wastes.  The
petition reportedly listed those materials which BHS was allowed to
accept under, the DNR permit.  The petition also claimed that the wastes
were flowing toward the plaintiffs' property.  The judge issued a
restraining order which temporarily closed the facility.  The order also
called for BHS to show why the operation should not be closed perma-
nently.  A hearing was set for June 24 to allow for further arguments
with respect to the injunction.

About two weeks later the director of DNR publicly announced the permit
approval during an industrial waste exchange conference in St. Louis.
Local electronic and print media publicized the directors's June 6 an-
nouncement.  This media attention provided the broad public knowledge of
the facility and began to raise some concerns among local residents in
Wright City.

On June 22, two days before a scheduled hearing on the temporary injunc-
tion against BHS, an out-of-court settlement between BHS and the de-
velopments was announced.  In that settlement BHS agreed to post a
$75,000 bond guaranteeing that no pollutants would leach out of the
   As  explained  by  a  DNR official,  BHS  began operations  with DNR's
   full  knowledge but without  a  formal  state permit.   Because DNR was
   convinced  of  the BHS  site's suitability,  it had confidence that  the
   permit  would  be  issued shortly,  and  thus  DNR allowed  operations  under
   its "good  graces."

-------
 site.  BHS also agreed  to monitor the inlet where the creek passing
 through the site  emptied into the lake.  For the first year BHS would
 analyze water samples monthly; thereafter samples would be analyzed
 quarterly.  In exchange for these provisions the developments' attorney
 agreed to drop the suit against
While  the problems BHS had had with the developments had been amelio-
rated  by late June, other problems with permanent residents of Wright
City still existed.  In the latter part of June, DNR agreed to attend a
public meeting in response to concerns raised by area residents.  The
meeting was arranged by the University of Missouri Extension Service and
held in Warrenton, the Warren County seat.  The meeting was attended by
several DNR officials, BHS's engineering consultant and over 100 area
residents.  DNR, with the help of the consultant for BHS, made a
presentation on the facility, its operation, and provisions to guard
against pollution.  The presentation was followed by a question-and-
answer period that allowed residents to express their concerns.   Ac-
cording to a local official the major issue raised by area residents was
the potential for the contamination of water supplies.  During this
meeting a resident asked DNR not to convince residents that the  site was
good but to explain how to get rid of it.   A DNR official who had gone
to the meeting with the assumption that rational explanations would
persuade opponents felt that this segment was the most telling comment
made.  The request convinced the DNR official that area residents would
never  accept the facility.

Several weeks after this meeting DNR was contacted by one of the Warren
County judges.   The judge asked DNR to explain the BHS facility to .
the county court (i.e., to all the county judges) and DNR agreed.  Prior
to this meeting a local pilot flew over the BHS site.   According to BHS,
the pilot,  seeing a bluish substance on the ground and assuming  it to be
Monsanto sludge, complained to DNR that BHS was operating improperly.
DNR closed BHS pending an analysis of the material.   That analysis de-
termined that the material was clay which BHS had excavated from the
site.  Although DNR reportedly attempted to assuage those who had been
concerned,  BHS indicated that the incident raised significantly  the
level  of general opposition to the facility.

The meeting requested by the county judge  was held in August.  DNR ex-
pected to brief the county court; however, the meeting had attracted
over 100 officials and residents including the area's  state elected of-
ficials.   The meeting became quite heated  and most if  not all elected
   Although that suit was never pressed,  BHS contended that it would
   not have been successful.   The major weakness  was  that  the  petition
   had listed all wastes from the permit  and claimed  that  they were
   buried at the site.  According to BHS, only Monsanto sludge had been
   accepted when the petition was filed.

   In Missouri,  .county judges are the chief elected officials  of
   counties; they are not judicial officials.
                                -138

-------
officials spoke against the facility. .The area's state representative,
who was minority leader of the state house, argued that local officials
should sue BHS on the grounds that there should be county control over
the facility.  He indicated that he would ask the state Attorney-
General for an opinion on the question of what legal controls the county
could exercise.  According to DNR, the local prosecuting attorney
indicated at the meeting that there was little likelihood that such a
suit would be successful.  (At the time of this meeting the regulation
of hazardous waste facilities was based on 1975 state solid waste law
and regulations.  A new state hazardous waste law had been passed by the
state legislature.  That law, however, would not take effect until
September 28, 1977.)

On October 6, 1977 the Attorney-General of Missouri issued an opinion
letter in response to the state representative's request.  That opinion
held that counties were authorized to regulate in substantial fashion
solid waste management systems under the 1975 solid waste law.  The new-
ly enacted hazardous waste management law, however, subsumed the earlier,
law as it pertained to hazardous waste.  Thus for hazardous waste
facilities regulation, authority rested with state government and local
governments could not regulate facilities which had been granted state
permits.

The Attorney-General's opinion marked the end of.major local efforts to
restrict or to close BHS.  Since that time there have been some requests
for state inspections for the facility and DNR has responded to these
requests.  The relative quiet has not indicated a lack of concern or op-
position to BHS.  During the Centaur site visit in March 1979, a DNR of-
ficial said he had recently been contacted by the attorney for the
second home developments adjacent to BHS.,  The attorney, described as a
former aide to a Missouri governor, had asked how severe a violation of
state regulations would have to occur in order to close BHS.        y

BHS has made some operational changes since opening.  As indicated in
Section II, trenches have been replaced with much smaller holes for
burying wastes.  BHS has severed its contract with Chem-Dyne and now has
its own operating staff.  BHS has maintained a relatively low profile
and refrained from any active public relations.  The firm does, however,
maintain the county road leading to the site and provides free waste
disposal for residents along the road.  These residents, according to
BHS and others interviewed, have never given any support to local cit-
izens trying to close the facility.
IV.
CHRONOLOGY OF EVENTS
 1976 —  Monsanto precluded from using landfill, resulting in need for
         alternative disposal site.

 June/July  1976— Monsanto contacts BHS, BHS contacts DNR, initial
                   arrangements for disposal of Monsanto sludge at BHS
                   made.  BHS hires engineering consultants.
                                  139

-------
 August, 1976 — BHS accepts first sludge for disposal under "good
                 graces" of DNR; soil tests and engineering for facility
                 proceed.
 September,  1976
             DNR grants temporary permit for disposal of Monsanto
             sludge.
 Late 1976/
   early 1977
          BHS  and DNR negotiate over design of  facility
May,  1977 — DNR notifies selected officials of permit approval;  DNR ap-
              proves  permit.   Attorney for  second home developments  sues
              BHS;  court temporarily closes BHS as a result.

June,  1977 — DNR director announces permit approval publicly.  Out-of-
               court  settlement  reached between BHS and attorney for
               second home developments,  allowing BHS to reopen.   DNR and
               BHS  consultant  attend public meeting to explain facility
               to area residents.

July,  1977 — BHS  temporarily closed by  DNR,  following charge of
               improper operations.

August,  1977  —  Second public meeting  over BHS;  area's  state represen-
                 tative argues for  suit against BHS based on local con-
                 trols  over hazardous waste management.

September,  1977  — State  hazardous  waste law  enacted.

October,  1977  — Attorney-General of Missouri  renders  opinion that  state
                 law precludes  local regulation of hazardous waste  man-
                 agement.                                             :

1979 — Attorney for second home developments"contacts DNR requesting
        information  on conditions required to  close BHS.
V.
ATTEMPTS TO SECURE SUPPORT
The following steps were taken to secure support and/or address con-
cerns.

       o     The out-of-court settlement resulting in the BHS posting of
             a $75,000 bond and increasing monitoring of facility oper-^
             ations.                              ,    .,

       o     Responses made by DNR and BHS officials during the two
             public meetings.

       o     BHS provides solid waste disposal and other services to re-
             sidents along the county road leading to the site.

-------
VI.
SUMMARY EVALUATION
The various attempts to secure support for the BHS operation have been
moderately successful in reducing concerns, but probably not successful
in gaining any substantial support for the facility.  The out-of-court
settlement appears to have been the most clear-cut case of BHS being
able to offer services (i.e., defined safeguards) in return for the
plaintiffs' acceptance of the facility.  That an out-of-court settlement
was reached suggests that both parties were interested in resolving
differences.  BHS's interests for this are self-evident.  It was
suggested that the plaintiffs as well had definable reasons for arriving
at a compromise as well.  The actual property owners are not permanent
residents and had left the questions of objecting to BHS to the
developer.  The developer, not wanting to endanger property values by
undue publicity, sought an effective, expedient solution that would
increase safety provisions.

Direct attempts to reduce the concerns of permanent residents appeared
to have largely failed.  Much more significant in overcoming this
opposition was the absence of any legal means by which the county could
control the facility.  DNR did not significantly allay any concerns but
the law strongly suggested that continuation of BHS operations was
inevitable as long as BHS adhered to state regulations.

Finally, BHS does appear to have at least gained acceptance from its
closest permanent abutters.  Because BHS's owner lives at the site,
these abutters are also his long-time neighbors.  BHS's conscious
attempts at a "good neighbor" policy have largely succeeded.  These
abutters, however, constitute only a small number of persons.

Overall, the successful siting of BHS is probably significantly linked
to the lack of widespread public knowledge of the facility until after
the permit was granted.  Once the permit was granted opponents had few
means of effectively fighting the facility.  Over time, opposition has
waned; however,-there is little to suggest that this lack of opposition
means acceptance.  There is some evidence that opposition would arise in
the future if opponents felt they had a reasonable chance of restricting
or closing facility operations.

There were only a few issues raised during the controversy.  They in-
clude the following.                                  :

Potential water contamination — A major concern was that runoff from
the site would flow into and pollute the lake near the site.  Less
clearly defined was the concern of contamination to groundwater by
chemicals migrating through the soil.

Improper operation — Opponents charged BHS with lax operational proce-
dures after a pilot spotted bluish material lying about the site.   DNR
later refuted the charges of mismanagement.
                                141

-------
 The exlstense of BHS — For some opponents the mere existence of  a.
 hazardous waste management facility such as BHS was the most  majorc
 issue.                                                             )

 VII.    FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

 The following factors led to public opposition.

        o     The existence of the facility.

        o     DNR's  announcement  of the permit  approval.

        o     The evidence (later refuted)  that BHS  was  improperly
              dumping Monsanto's  sludge.

 The following factors led either to acceptance or a waning of
 opposition.

        o     The willingness of  the plaintiffs in the court suit to
              compromise.

        o     The overriding  of local hazardous waste regulation by state
              law.

VIII.   RETROSPECTIVE  VIEWS

In  looking at future  hazardous waste facility  siting, BHS saw a need for
better  provisions for communicating with the public.  In particular,
local leaders  should  be educated both  through  small meetings with
leaders  and tours of  facilities  or  sites.  The major thrust would be to
demonstrate credibility to these leaders prior to public meetings or
other events  that are more conducive than public meetings to reasoned
discussions.   BHS perceived  state agencies as  being strictly neutral
parties  in siting attempts.  EPA was seen as having no major role in
siting attempts.
IX.
GENERAL COMMENTS
Representatives of BHS also had more general comments on hazardous waste
management.  Publicity about improper disposal generated by EPA could
possibly create backlash against good facilities, making it more diffi-
cult for the private sector to secure future sites.  EPA regulations
should address the degree of hazard in wastes so that the need for
facilities could also be geared to the degree of hazard.  This could
reduce the demand for facilities capable of handling extremely hazardous
wastes.  Finally, if an operator has followed all regulations but some
spill or other accident occurs, the operator should not be held liable.
Instead, the government should establish a fund with payments from
hazardous waste generators to cover liability costs.
                                 142

-------
To date, EPA Region VII has a minor role in siting.  It has not reviewed
any permit applications and has not been asked to do so.  Instead, it
has provided quiet support for sites which states have been determined
to be sound.  In rare instances, Region VII staff have discussed general
problems of hazardous waste management and the need for sound disposal
sites with opponents of specific sites.

According to regional staff, the implementation of RCRA could
drastically change their role and the status of disposal in the region.
Only one-third of the estimated personnel needed by the office to
implement RCRA have been budgeted.  Recently issued regulations for
public participation could add six months to two years to the siting
process.  This could drive public participation costs up to a level
equal to the rest of siting costs.  If these estimates are at all
accurate, siting, costs will mushroom and a number of potential facility
sponsors will drop out.  This would clearly result in a slower rise in •
regional disposal capacity.  That disposal capacity could drop
drastically when RCRA is implemented, as the office only expects two
sites in the region to meet the new regulations.

The regional office sees the major siting issues as follows:  Do sites
meet, or preferably exceed, minimum technical standards for safety?  Are
funds for all post-closure costs and eventualities available
perpertually?  Are facility sponsors and operators qualified and
trustworthy?  Can site proponents communicate clearly and effectively
with local officials and concerned citizens?

State agency comments are described in the state program write-up
elsewhere in this report.
                                  143

-------
                             WES-CON, INC.

                     GRAND VIEW AND BRUNEAU, IDAHO
I.
INTRODUCTION
Both the Grand View and Bruneau facilities of Wes-Con, Inc., are
discussed in this report because their histories are so closely
intertwined.  The sites are located in the same county, only 40 miles
apart.  Many of the same residents and local elected officials sat in on
public hearings and county commission decisions for both sites.  The
sites are identical abandoned Titan missile silo facilities and many of
the state's operational disposal guidelines developed for the Grand View
facility were later improved and adopted for the proposed Bruneau
facility.  In addition, the County Commissioners viewed the permission
to operate at Bruneau as a simple extension of their previous approval
at Grand View.

Public opposition to both sites was very mild.  There were a few
complaints about odors which were checked by the state, but absolute
verifications of the odors were never made.  Neither the state or the
county has an odor ordinance.  However, several operational changes were
made to minimize the potential odor nuisance.  Following the national
publicity on Kepones and the announced possibility of their being
disposed of in Grand View, a few citizens voiced alarm.  In response to
this opposition and as part of the state's re-evaluation of the permit
conditions, a public hearing was held over the Grand View operation.
Although some opposition was voiced, the state felt that it was minimal
and easily assuaged by certain operational changes and stricter controls
on the disposal operations.

Approximately a year and a half later a public hearing was also held for
the proposed Bruneau site.  No significant opposition developed at this
hearing.  Wes-Con received a similar conditional use permit and signed a
consent decree for the Bruneau operation.

Public support for both facilities came primarily from local elected
officials and civic leaders.  They assumed a traditional attitude in
this area that if one owned the land, they were entitled to do with it
what they wanted to.  The public also assumed that state and federal
organizations such as EPA and the State Department of Health and Welfare
would supervise and enforce the safe operation of the sites.  Wes-Con
undertook several public relations initiatives to become good neighbors
and earn the continuing trust of the community.  The Cattlemen's
Association is the only organized interest group in the area and they
supported the proposed activities of Wes-Con because they saw no
conflict with the agricultural and ranching economy of the area.
                                  J44

-------
II.
BACKGROUND INFORMATION1
Both sites are located in remote areas of Owyhee County.  The Grand View
site is 10 miles from the town of Grand View (population: 260)^  The
Bruneau site is 20 miles from the town of Bruneau (population: 100).
The nearest rancher is two miles away at the Grand View site and 20
miles away at the Bruneau site.  The remaining abutting land on both
sites is BLM grazing land.  There are no zoning ordinances in effect in
Owyhee county.

The hydrogeology of both sites is particularly well suited to hazardous
waste disposal.  The well log at the Grand View site revealed numerous
thick layers of blue clay underlying the missile silos.  Since clay is
highly impermeable, especially at the reported depths and pressures, the
chance of groundwater contamination in the event of leachate escape is
almost non-existent.  The site well logs report that first water was
encountered at approximately 3,000 feet.  Although it was not documented
by a well log, a shallow water table reportedly existed in the general
Grand View area at 300 to 400 feet.  However, it was determined that the
water table was not a flowing aquifer and was not present in all
locations in the Grand View area.

The hydrogeologic characteristics of the Bruneau site are similar to
those of Grand View but rendered somewhat more complicated by a
shallower water table, approximately 2,000 feet below the silos, and
intervening layers of volcanic rock instead of clay.  However, the lack
of vertical fractures, the relatively impermeable deep formations, and
the high pressure of the deep artesian aquifer indicate that under
normal circumstances the deep aquifer would not be contaminated by
hazardous wastes.

Both the Grand View and Bruneau sites are identical in terms of the
silos and underground vault complexes.  Each site has a number of silos
and two large underground vaults that can be used for temporary storage,
long-term warehousing or final disposal of wastes.  Each site consists
of an approximately 20-acre fenced portion and an additionnal 100-acre
buffer zone.  The underground structures were designed to withstand a
ground-zero atomic blast and to contain an internal explosion and fire
   Most of this background information is derived from a technical
   evaluation of Wes-Con which was provided to Centaur by Wes-Con. • This
   evaluation has allowed for a much more detailed description of     -
   background and information than has been generally possible for case
   studies in the project.  The evaluation was conducted by TRW, Inc.
   under contract to U.S. EPA.  See Case Study No. 4 in Study of   ,
   Selected Landfills Designed as Pesticide Disposal Sites, TRW Systems
   Group, U.S. Environmental Protection Agency, 1976, published as PB
   250-717 by the National Technical Information Service, Springfield,
   Virginia, 22161.
                                  145

-------
in the event.of an accidental ignition of the missile propellant.  The
walls and floors are steel reinforced concrete treated to withstand,
complete water immersion.  The silos are approximately 50 feet wide-and
160 feet deep with up to 6-foot thick walls and 13-foot thick floors.
The silos and vault areas are interconnected by tunnels which are sealed
with bomb-proof doors.  Each silo has a 100-ton reinforced concrete
cover door which will be sealed when the silo is completely filled with
wastes.  Preparation of the silos and vaults consisted of salvage
operations to recover metal structures and to collapse floating floors.
The Grand View site is completely prepared and operational.  The Bruneau
site is still under preparation.

Wes-Con is also operating a landfill trench at the Grand View site which
allows them to segregate some of the more volatile wastes and thereby
reduce the risk of fire and extend the life of the silos.

The walls and floors at both sites were poured within a gunite form
which was constructed by excavating the original earth then recompacting
and finally "shooting" with a 6- to 12-inch thick gunite pad.  The
excavation and recompaction of the entire area would also disrupt any
natural geological strata which might be evident in the upper sand and
clay layers and would thereby eliminate the possibility of underground
infiltration of surface water into the disposal area.  To even further
minimize the chance of groundwater contamination, Wes-Con was required
to incorporate a clay soil mixture in the silos with each waste load in
order to eliminate any free-standing liquids in the silos.  Both sites
are also protected from surface water problems by being situated on
knolls and in an area with an average precipitation of 10 inches and
evaporation of 72 inches.

Initially the silos were to be filled simply by dropping drums of wastes
into the opening at the top of the silo.  This practice was later
replaced by a crane lowering the loads to help prevent sparking caused
by the impact of free-falling drums.  In addition to the drums of waste,
bentonite clay is added in equal proportions to the waste volumes to
suppress odors and to make a "mud-mix" from the liquid wastes that leak
out of the ruptured drums.  Every fifty feet or so a complete clay lid
is placed over the wastes to absorb further liquid wastes and to help
eliminate odors and prevent fires.

Both water and clay are available at the lip of the silo opening to be
bulldozed into the silo in case of fire.  A fire truck is also available
on-site for additional water and foam pumping capacity.  Other safety
features include protective clothing for the operators, showers in the
event of bodily contact with waste materials, and periodic physical
checkups with complete blood and urinalysis tests.  Employees are
protected by regular monthly blood tests they are required to undergo at
a poison control center in Boise.  Also, the final paycheck of a
terminating employee is withheld until they have arranged for a complete
physical.  Access to the site is encouraged but limited to appointments
only in order to prevent an authorized entry which could be dangerous.

-------
 Wes-Con does not own or operate its own waste hauling trucks.   Under
 agreements  with some of the major clients,  however,  hauling of the
 wastes  is Wes-Con's  responsibility.  Wes-Con hires commercial  waste
 haulers for hauling  in wastes  from these clients.   Only licensed
 commercial  waste haulers are admitted to the disposal site. Currently,
 Wes-Con does not have on-site  laboratory facilities  for waste  analysis
 and  the customers are required to identify  the contents of  their
 shipments.   In most  cases,  major waste producers  send a technical
 representative along with the  waste shipment to assure that the waste
 load reaches its intended destination and that the waste is disposed of
 properly.   The customers are usually consulted and their recommendations
 on proper waste handling methods and pretreatment  procedures are
 solicited.   Wastes received at the site are disposed of immediately.

 The  capacity of each site is approximately  1.5 million cubic feet.   At
 the  projected rate of use the  anticipated life of  each site is
 approximately 10 years.   At the Grand View  site, Wes-Con has recently
 started a landfill trench adjacent to the silos in order to increase the
 capacity of the operation.   They are also considering incineration and
 some form of resource recovery operation in the future to concen-
 trate the hazardous  wastes  and recover some valuable products.
 Implementation of these  plans  will extend the  life of the site.
 However, no. estimates are available at this time as  to the  total life of
 the  operation.   At the moment  there are no  site closure plans  short of
 sealing the silo doors and  reseeding the areas., The state  has  no  rules
 regarding bonding or other  forms  of financial  responsibility during or
 after the operation  of a site.           ,

 The  Wes-Con sites have been approved by the state  as a pesticide waste
 disposal facility and have  a "blanket"  permit  for  accepting pesticide
 wastes.  Disposal of hazardous  wastes other than pesticides, however,
 requires specific state  approval  which is granted  on a case-by-case
 basis.  As  a matter  of policy,  however,  Wes-Con keeps  a record  of all
 pesticide and non-pesticide  wastes  which it  handles  and the records are
 available to  the  state for  review upon request.

Wes-Con accepts  a broad  range  of  wastes  in  addition  to  pesticides.  The
 other wastes  are  miscellaneous  hazardous wastes, including  PCBs,
 laboratory wastes, electroplating  sludges, etc.  Some  hazardous  wastes
 are  not accepted:  Kepones,  radioactive materials, military poison gas
 and  pressurized gas.

Through agreements with major  power  companies and  the  Bonneville Power
Administration, Wes-Con is currently handling most of  the PCBs generated
within  the  Pacific Northwest.   Some  of  the wastes come  from as fair away
as Hawaii and negotiations have been conducted with,an  Australian firm.
Most of the wastes handled at Grand View and projected  for  Bruneau will
be from out of state.
The name Wes-Con stands for Western Containment.
emphasize the positive aspects of the operation.
It was selected to
The company
                                147

-------
intentionally stayed away from such names as refuse disposal, hazardous
waste disposal, and indusrial waste disposal, which were considered to
be psychologically less appealing to the public than the name Wes-Con.

Wes-Con is an Idaho Corporation composed of the following three major
stockholders:  the president (a former associate professor at the
University of Idaho); a Twin Falls owner of a chemical supply company;(
and an attorney.  When all start-up activities are completed they will
employ six people at the Grand View site and plan to employ two persons
at Bruneau.  Although the sites are very similar the additional trench
disposal at Grand View and greater mechanization at Bruneau account for
the difference in employment.  At the moment Wes-Con owns only the Grand
View and Bruneau disposal sites.  However, they are looking ahead to
recycling and resource recovery operations as an adjunct to the disposal
activities.

Owyhee County is a ranching and agricultural area with a population of
approximately 7,600 persons and an area of approximately 7,000 square
miles.  Thus it is sparsely populated, with approximately one person per
square mile.  The people in the county are poor, with the poorest sector
being the large number of senior citizens.  Some of the land has been
purchased by outside interests, mainly California investors, but they
take little or no interest in local activities such as the waste
disposal sites.  The region used to be much better off economically.
There was a major silver mining operation in the nearby Owyhee Mountains
and many Basques used to have large sheep herding operations there.
However, now the area exists on sugar beets, potatoes, alfalfa, hay and
livestock.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

As of March, 1979 there were no state laws in Idaho specifically
pertaining to hazardous waste disposal in Idaho.  There was, however,
proposed legislation which was modeled after RCRA, with the exception
that Idaho might classify wastes by degree of hazard.  There were no
local permits or regulations which applied to either of the Wes-Con
facilities.

Prior to the Wes-Con facility development, the state had no experience
in hazardous waste disposal issues and none since the siting of these
two operations.  In issuing the conditional use permit, the state relied
on its solid waste disposal laws and on the proposed federal hazardous
waste regulations.  They anticipate all future issues concerning
hazardous wastes to be covered by federal regulations.  The state also
has no requirements for public hearings, leaving it up to the county
commissioners to conduct local hearings and grant permission on waste
disposal.

The concept of using abandoned missile silos for hazardous waste storage
evolved in 1973.  Wes-Con's president had had extensive experience in
selling chemical products and as a university professor and an
                                -148

-------
 agricultural extension agent familiar with pesticide uses and handling
 procedures.  He implemented his idea with the creation of Wes-Con.  He
 purchased the Grand View site in 1973 and prepared an environmental
 assessment as part of an application to the state.

 Although it was not required under any applicable regulations, at the
 very beginning, Wes-Con discussed its waste disposal plan with the
 Owyhee County Commissioners and solicited and received their approval.
 According to Wes-Con, county approval reflected a strong local tradition
 of allowing one the freedom to do with one's land what one wanted to.
 In June of 1973 Wes-Con was granted a Conditional Use Permit for the
 Grand View site by the Idaho Department of Health and Welfare.'  The
 permit was fashioned out of existing solid waste management regulations
 and proposed federal hazardous waste regulations.  Commercial operations
 started in November of 1973.

 Wes-Con1s management staff have been well known locals in the area for
 many years, and from the start of their operation they undertook an
 aggressive public relations campaign.  Wes-Con donated steel stairs,
 valves, pipes and other materials salvaged from the site to local
 schools, farmers and private citizens.   The company replaced a "no
 admittance" sign with "visitors welcomed" sign and invited local
 citizenry and representatives from universities, industry and
 governmental agencies to see the site and its operation.   To avoid
 adverse publicity, Wes-Con intentionally stayed clear of nuclear wastes
 and nerve gases, even though the site was considered to be most suitable
 for the containment of such wastes.   The .company's public relations
 activities included hiring employees locally, accepting pesticides and
 other hazardous waste from area ranchers and local public facilities
 free of charge, providing free diaposal services for emergency
 situations, allowing area ranchers to use free of charge Wes-Con's heavy
 equipment, supporting local charities,  and providing first aid classes
,to neighbors.

 As a result of its public relations  program,  Wes-Con's Grand View
 facility did not receive public opposition or major complaints from
 local citizenry, with the exception of  the nearest neighbor to the Grand
 View facility.   In this instance a woman residing about two miles from
 the site complained about odors and the inherent dangers  associated with
 handling hazardous chemical wastes that had devalued her  property.   The
 State made a routine check of the odor  complaints, but was unable to
 verify .them.   In tj.me the woman sold the property to a ranch developer
 who improved the property and resold it.  The property is now being
 ranched and no  further complaints have  arisen from this abutting
 neighbor.   The  sale,  improvement, and resale  of the property indicate
 that the nearby hazardous waste disposal facility has not adversely
 affected the value of the property.                     .   .  /. •

 In June of 1976,  EPA,  which had formed  a special task force to
 coordinate Kepone disposal,  recommended that  the Wes-Con  facility be
 used for those  Kepone-contaminated materials  that could not be
                                   149

-------
incinerated.  Allied Chemical approached Wes-Con with a request to
dispose of some of their Kepone wastes.  Allied Chemical also contacted
the state, which had to give its permission before Kepone could be added
to Wes-Con's waste stream.  The State Department of Health and Welfare
recommended in favor of the Kepone disposal on environmental grounds;
however, they conceded that it was a politically sensitive issue that
should be decided by the governor.

A flurry of media attention was given to the Wes-Con facility over the
possibility of Kepone disposal in Idaho.  Much of this publicity focused
on the fact that the governor had publicly campaigned against the
disposal in Idaho of radioactive waste and nerve gas which would be
brought from other states.  Finally, in November of 1976, the governor
issued a statement that he had asked Wes-Con not to accept the Kepone
wastes, suggesting that there were numerous disposal sites closer to
Baltimore (the source of the Kepone) which can encapsulate hazardous
materials, thereby avoiding the danger and cost of shipping the wastes
to Idaho.  Wes-Con's refusal to accept the Kepone wastes saved the
governor from an obvious political dilemma.  Because most of the waste
Wes-Con handled was from out-of-state he could not insist that only
Idaho wastes be buried at Grand View nor could he argue against .EPA's
recommendation at the same time the people of Idaho were voicing strong
opposition to the Kepone issue.

In the same statement over Kepones, the governor said that the state was
conducting a technical re-evaluation of the integrity of the Grand View
site and its operation but there was no evidence to suggest that the
operation of the site needed to be changed drastically.   This
re-evaluation was instigated by several fires that had occurred in
October at the Grand View site.  In November public hearings were called
in Owyhee County to investigate the operation of the site.  It was
theorized that the dropping of barrels into the 160-foot silo caused
sparking and the possibility of fires.  The revised conditional use
permit issued in March of 1977 that resulted from this hearing ordered
Wes-Con to lower the barrels by crane and to have on hand additional
fire fighting equipment.  The fire truck purchased to meet state
requirements became an important public relations-symbol since it was
the only such truck available to local ranchers and farmers.  Another
important outcome of the re—evaluation was the requirement for Wes—Con
to sign a consent decree.   This consent decree meant that Wes-Con would
cease operations and have its permit automatically revoked in the event
of another fire,-without any legal or administrative action on the part
of the state.  Similar consent decrees had been used by the state in air
pollution control situations.

In the spring of 1977 Wes-Con decided to expand its operation by
purchasing the Bruneau facility.  This was an identical titan missile
silo complex, although its geology was somewhat less favorable than that
of the Grand View site.  However, a consulting engineering and geology
firm with over 30 years of local USGS experience was hired to
investigate the possibility of hazardous wastes leaching into the
                                  150

-------
groundwaters.  In the summer of 1977, Wes-Con submitted to the state an
environmental assessment of the Bruneau site.  Wes-Con again met with
and secured the approval of the County Commissioners and civic leaders,
who saw this as a simple extension to the Grand View operation, and
applied to the state for a permit with another environmental assessment.

In July of 1978 public hearings were held in Bruneau prior to granting
Wes-Con a permit.  The hearings produced no local public opposition.
There was some opposition from an outsider (Boise) but locals were
willing to allow the site on the premise that state and federal laws
would guarantee its safety.  Thus, the state granted a conditional use
permit.  This permit adopted all the improved operating features of the
Grand View site.  Wes-Con also signed a consent decree covering the
Bruneau site.  In December Wes-Con applied for and received permission
from EPA and the state to dispose of PCBs in the Grand View silos.
Permission is still forthcoming from EPA and the state for a request to
dispose of PCBs in trenches alongside the Grand View silos.

The Grand View site has been operating successfully with no public op-
position since , the Keppne incident and no opposition has surfaced re-
garding the proposed Bruneau site which will go into operation in the
summer of 1979.   However, Wes-Con feels that this lack of opposition
could change suddenly if an accident occurred such as a truck accident
spilling hazardous wastes along the highway.  All of Wes-Con1s good will
built up over the years could easily be erased by such an incident, re-
gardless of whether such a truck was leased to Wes-Con or belonged to a
waste generator.
IV.
CHRONOLOGY OF EVENTS
1973 —An associate professor at the University of Idaho working as an
        agricultural extension agent conceives the idea of Western Con-
        tainment (Wes-Con), Inc.  His plan is to operate a hazardous
        waste management company using abandoned missile silos for the
        containment of agricultural and industrial wastes.

1973 — A 17-acre missile silo and underground vault complex with a 100-
        acre buffer zone near Grand View is purchased.

April, 1973 — Wes-Con prepares an environmental assessment and applies
               to the State Department of Health and Welfare for permis-
               sion to operate a pesticide and hazardous waste disposal
               facility at the Grand View site.

1973 — Wes-Con receives approval from the Owyhee County Commissioners
        to operate a waste disposal site.

June, 1973 -- Wes-Con receives a state conditional use permit to use the
              missile silos for the disposal of pesticide wastes, elec-
              troplating sludges, and laboratory wastes.
                                 151

-------
November, 1973 — Formal commercial operation begins at the Grand View
                  site.

1974/1975 — Abutter complains of odors and loss of property value.  Her
             property is sold to ranch developer and complaints cease.

June, 1976 —At EPA's suggestion Allied Chemical approaches Wes-Con on
             the disposal of Kepone wastes at the Grand View site.

October, 1976 — Several fires prompt the state to re-evaluate the oper-
                 ation of the Grand View site.

November, 1976 — Local and national news media cover the-possibility
                  of "ultimate" Kepone disposal in abandoned missile
                  silos in Idaho.  Governor asks Wes-Con not to accept
                  Kepone wastes.  The state holds a public hearing on
                  the operation of the Grand View site.
March, 1977
 Wes-Con receives  a  revised  state  conditional use  permit
 and  signs  a consent decree  agreeing  to cease operation in
 the  event  of  another fire at  the  Grand View site.
Spring of 1977 — Initial payment on the purchase of approximately 100
                  acres of land including abandoned missile silos and
                  underground vault complex near Bruneau, Idaho.

July, 1977 — Wes-Con submits an environmental assessment of the
              proposed operation at the Bruneau facility.

Summer of 1977 — Meetings with civic leaders in the Bruneau area to ex-
                  plain the future operation of the hazardous waste dis-
                  posal site.  Wes-Con extends invitation to the general
                  public  to visit the facility.

July, 1977 — Final payment is made on the land and missile silo
              complex, and application to the Idaho Department of Health
              and Welfare for permission to operate the Bruneau site is
              made.
April, 1978 -


July, 1978 —
- State approves  the silo disposal of  PCBs  at Grand View
  site.

 EPA approves the disposal of PCBs in  missile silos at
 Grand View.   State holds public hearings in Bruneau to
 solicit public comment on proposed Bruneau site.   Wes-Con
 receives conditional use permit from  the state Department
 of Health and Welfare.  Permit also includes a consent de-
 cree similar to  the one 'signed by Wes-Con for the Grand
 View site.                                             ;
                                  J52

-------
December, 1978 — Wes-Con applies to EPA and state for a permit to dis-
                  pose of PCBs in clay-lined trenches adjoining the mis-
                  sile silos at Grand View.

March, 1979 — State and EPA approvals expected on PCB disposal in
               trenches at the Grand View site.

Summer of 1979 — Start of Bruneau operation.

V.     ATTEMPTS TO SECURE SUPPORT

The first step in securing public support for the disposal operation was
the elimination of nerve gas and radioactive materials from the proposed
waste streams to be handled.  These materials would have generated
strong public opposition and the governor was campaigning to rid the
state of these wastes.  The wisdom of this decision was later proven
when public opposition erupted over the arrangements to dispose of
Allied Chemical's Kepone wastes.  Cancelling the arrangement with Al-
lied Chemical neutralized local public opposition and gained the support
of the state government.  The state government was in a difficult
political dilemma over public opposition to the importation of Kepone
wastes after EPA had recommended their disposal at the Grand View site.

Other attempts to secure public support were a series of public re-
lations actions including:

       o     Replacing a "no admittance" sign at the entrance of the
             facility with a "visitors welcomed" sign.

       o     Hiring local employees and asking them to bring their rel-
             atives and friends to.the site for tours.

       o     Accepting for disposal free of charge the spent pesticide
             containers from local ranchers and farmers.

       o     Providing free disposal services for local hazardous wastes
             from hospitals, county facilities, and educational
             facilities.

       o     Providing free disposal under emergency conditions for
             materials within Idaho, including highway wrecks and flood
             disasters.

       o     Providing access to the facility for state and federal ex-
             perimental studies, demonstrations and training.

       o     Volunteering the use of bulldozer and other heavy equipment
             to local residents.

       o     Supporting local firefighting efforts with personnel and
             equipment.
                                  153

-------
VI.
o     Contributing to local fund-raising campaigns to help out
      residents in time of sickness and other personal disasters.

o     Paying the way for the children of local residents to
      visit 4-H camps and the 4-H Congress.

o     Organizing a local corporation with native and long-time
      residents in ownership positions.

o     Making no secret about the type of wastes to be disposed or
      their local and out of state origins.

o     Training local doctors on nature of hazardous waste and
      providing first aid classes for local residents.

o     Donating an ancient Indian cave to the university for
      archeological studies.  Will also pay to publish the
      findings and donate them to a local museum.

o     Guaranteeing the bills incurred by workmen in local com-
      mercial establishments in the event that they skip town.
      (This was a prevalent problem during the construction of
      the missile silos.)

SUMMARY EVALUATION
The most effective step in securing public support for both sites was
the neutralization of public opposition that would have arisen over the
handling of radioactive materials and nerve gas disposal and later the
cancellation of the Kepone arrangements with Allied Chemical.  The
operator was aware of the political liability associated with these
wastes, especially since the governor had campaigned to rid the state of
such wastes.  By anticipating the governor's dilemma over these wastes,
the operator gained valuable political support on a statewide basis.

It is impossible to separately evaluate the remaining public relations
actions of the operator in gaining the support of the community.  How-
ever, it is safe to say that none of the extensive public relations
activities hurt and taken together they all helped smooth the way
through public hearings, permit re-evaluation and the issuance of
conditional use permits.

There were five major factors which characterized the overall success of
this operation:

Technical Adequacy — The sites are obviously of superior structural
design and physical surroundings.  Built to extraordinary military
specifications, the sites are more than suitable to contain hazardous
wastes.  The hydrogeology of the sites is excellent with water tables at
approximately 2,000 and 3,000 feet below the silos.  The 10 inches of
precipitation versus 72 inches of evaporation are also ideal conditions
                                  154

-------
to minimize surface runoff.  Finally, the sites are extremely remote
from population centers in a county that has a population density of
only one person per square mile.

Local Attitudes — The people in the area have a traditional "live and
let live" attitude.  They respect the fact that if you owned the land
you should be allowed to do with it what you wanted to — even if it is
to operate a hazardous waste disposal site.

Public Trust— Local residents .trust that the state or federal
government or both will supervise and enforce the, safe operation of the
sites.  This trust is reinforced by the governor's pressure to cancel
the controversial Kepone disposal and the state's re-evaluation of
permit conditions after the fires at the Grand View site.  Public trust
is also enhanced by EPA's endorsement of the operating Grand View site.

Demographic Characteristics — This is.a poor agricultural area with
simple lifestyles.  The hazardous waste disposal site is not perceived
as a real and present danger.  Most of the wastes at the sites are
pesticide residues which local farmers have been handling long before it
became fashionable to call them hazardous or persistent wastes.

Public Relations — An extensive public relations campaign in a general-
ly poor community helped to sell the operation of the sites.  This
campaign also served to guarantee the "good neighbor" image of the oper-
ator.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Both the Grand View and Bruneau sites have been accepted by the local
public.  The Grand View site is in full operation, having passed a
public hearing and complete re-evaluation of its operation following a
few fires as well as a minor flurry of publicity over the possiblity of
•Kepone disposal.  The Bruneau site is now being readied for operation,
having passed a public hearing for a conditional use permit.  The
factors that led to public acceptance are:                      ,

       o     A traditional attitude in the area that if you owned the
            . land you were entitled to do with it what you wanted to.

       o     An existing history of public acceptance of an outside
             activity that posed a threat to the area —namely, the
             missiles themselves.  Also, many of the local citizens
             worked on the sites during their construction and were  ..''.
             aware of their extreme structural integrity.

       o     An extensive  public relations campaign by the operator to
             become a good neighbor and to win the continuing trust of
             the community.
                                  155

-------
              A pair  of  sites  that had  unquestionably  good  hydrogeologic
              and  surface  water  characteristics as  well as  excellent
              structural features.

              An operator  who  was  a long-time  resident of the  area  and
              intimately aware of  the • pesticide wastes generated  in the
              area that  are  part of the operation's waste stream.

              An operator  who  was  politically  astute and had a good work-
              ing  relationship with the state  government.   This political
              sensitivity  lead to  initial  rejection of radioactive  and
              nerve gas  wastes and  later to  the rejection of Kepone
              wastes.
       o     An operator who used his  years of experience as a chemical
             products salesman  to "sell" the public on his waste
             disposal operation.

       o     Local public  trust in  the supervision of state and federal
             agencies which have endorsed the site.

       o     An opportunity to  rid  pesticide wastes (e.g., spent con-.
             tainers) from the  community's sanitary landfill.

VIII.  RETROSPECTIVE VIEWS

With the exception of having been denied the opportunity to dispose of
Kepone wastes, the Grand View and Bruneau sites are an operational suc-
cess.  The only thing the  operator  would have done differently is to  put
more emphasis on. the use of a public relations firm.  He would have used
such a firm earlier in the planning process to anticipate problems
rather than having to react to  them.   This was .especially true for the
Kepone incident, the intensity  of which caught the operator unprepared.
The operator would also have liked  to  have the federal government assume
a stronger and more dominant role in hazardous waste issues, especially
in siting facilities.  He  feels that state governments and certainly
county governments are too easily intimidated by local political
interests.
IX.
GENERAL COMMENTS
The operator thinks that his sites are competitive in spite of their
remoteness.  However, he feels that there is insufficient federal or
state enforcement on waste generators because of a lack of suitable
sites, thus reducing the demand for existing sites or the incentive to
create new sites.
                                 156

-------
                            SCA/EARTHLINE

                         BORDENTOWN, NEW JERSEY
I.
INTRODUCTION
In the spring of 1978 Earthline, a subsidiary of SCA Services, submitted
an application to the Solid Waste Administration (SWA) of the New Jersey
Department of Environmental Protection.  That application sought a
permit to operate a small commercial landfill for the disposal of
hazardous waste.  In March of 1979 SWA denied that application.

Earthline1s application sparked local concerns which in time evolved
into strident opposition voiced by a broad range of public officials and
private citizens.  Of particular concern to the opponents were the
site's proximity to a major aquifer and a high school; the credibility
of Earthline, SCA and SWA; and numerous attendant potential social,
economic, and cultural impacts.

Attempts to provide public information, to elicit public response,
and/or to address concerns and issues were made by SWA and Earthline.
The most salient of these was a two-day public meeting held by SWA;
others included smaller informational meetings and debates.  Ultimately
these failed to make any significant impact on the opposition to the
Earthline application.
II.
BACKGROUND INFORMATION
The Earthline proposal called for the development of a five-acre secure
landfill within the bounds of an existing operating 100-acre sanitary
landfill.  The site is located within Bordentown township to the west of
U.S. 130.  The site is across a local street .from Bordentown Regional
High School.  That local street provides access to the existing sanitary
landfill and would have also provided access to the hazardous waste
landfill.

The sanitary landfill is within a larger area known ,as the Church Brick
Clay Pit.  That area is immediately underlain by four geologic
formations — the Pensauken formation, the.Woodbury Clay, the
Merchantville formation, and the Magothy-Raritan formation.  According
to reports prepared during the siting attempt, the Pensauken formation
is uppermost of these and has been largely excavated as a result of
historic 'site use.  Where present, it is typcially three to twelve feet
thick and does contain perched water tables.  The second stratum, the
Woodbury Clay, which is zero to 40 feet thick and has a lab-tested
permeability of 1.3 x 10~^ cm/sec." The third stratum is the
Merchantville formation with an average thickness of 39 feet and a
                                 157

-------
lab-tested permeability of 1.8 x 10~6 cm/sec.1  Beneath these three
formations is the Magothy-Raritan formation (actually two interconnected
formations) which is 330 feet thick.  The Magothy-Raritan is a major
aquifer used by industry and the public.  In 1976 this aquifer provided
80 percent of the groundwater pumped in Burlington County.

As proposed by Earthline, five acres of the 100-acre sanitary landfill
would have been developed as a secure landfill.  The design called for
five cells within the five acres to separate different types of indus-
trial waste.  Cells would have been separated by a clay berm minimally
ten feet thick.  Beneath the cells would be two feet of compacted clay,
a 40-mil Hypalon liner, six inches of sand, and a minimum of ten feet of
clay beneath the sand.  The five-acre secure landfill would have been
surrounded by a ten-foot-thick clay berm incorporated into the Woodbury
Clay.  Four monitoring wells on each side of the secure landfill were
proposed.  Provisions for long-term care were to be in comformance with
state regulations.   Those regulations are being revised to conform with
anticipated RCRA requirements.

The secured landfill, as originally envisioned by Earthline, would have
disposed of residuals from an Earthline hazardous waste treatment and
   The 39-foot figure was .provided by the New Jersey Geological
   services.   Earthline's application, based on data developed by
   Wehran Engineering for the 1976 application for the sanitary
   landfill,  described the Merchantville formation as being 60 feet
   thick.  The permeability figure is from the same 1976 application.
   In a 1976  letter to Wehran, SWA questioned the usefulness of the 1.8
   x 10   cm/sec figure as the test was on a sample taken from the top
   of the formation and state geologists indicated the possibility of
   greater permeability at the bottom of the Merchantville formation.
   State reviews of geological data also cited evidence that when the
   Woodbury Clay was exposed to normal operations at the landfill the
   clay would dry out and porosity would increase.   This would have
   potential, but uncertain, negative impacts on the integrity of the
   clay as a  liner.  Furthermore,  reviews of the Earthline application
   by opponents' engineering consultants stated that permeability rates
   were based on the flow of water,  not leachate.   Citing the
   undefined  nature of leachatefs  effect on these clays,  the question
   was raised as to whether the lab-tested permeability rates had any
   significance in defining the site's ability to prevent groundwater
   contamination.

   The point  of this footnote is to  illustrate part of  one facet  of
   the technical dispute  that arose  during this siting  attempt  and the
   lack of consensus on those data most easily quantified.   As  will be
   discussed  in Section III the technical dispute was but one of  many
   that arose.
                               158

-------
processing facility in Newark.  According to an attorney retained by
Earthline, SWA had asked that other hazardous wastes generated in. New
Jersey be disposed of at the proposed facility.  (Earthline agreed on
the condition that those wastes be tested at the Newark facility to
determine whether they were suitable for burial at the Bordentown site.)
In any event the Bordentown facilty was primarily designed to serve the
New Jersey market area.

Earthline is a subsidiary of SCA Services which has hazardous waste
management facilities in Illinois, New Jersey, New York, and South
Carolina.  SCA Services is one of the largest waste services companies
in the nation.  In fiscal year 1978, the company reported total revenues
of over $180 million.  The majority of SCA operations are in the
municipal and commercial waste management field.

The Bordentown area is located about ten miles south of Trenton in
central New Jersey.  Bordentown city has a population of about 5,000
and, according to the mayor, has a racial and economic profile
reflecting the state as a whole.  Bordentown township, which surrounds
the 'city, has a population of about 8,000, almost totally white with
somewhat higher incomes than  those for the city.  Both the city and
township are within Burlington County (estimated 1977 population:
361,300).  The employment base of the Bordentown area is broadly
dispersed among economic sectors within the greater Trenton metropolitan
area.

HI.    HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

The state of New Jersey preempts local zoning controls over special
waste facilities.  As a result there are no local permits or regulations
applicable to these facilities.  In planning for the hazardous waste
landfill Earthline needed only a permit from the Solid Waste
Administration (SWA).  During the course of the approval process, SWA
has other appropriate state agencies (e.g., air and water pollution
control  agencies) review the  application.                       ,

The controversy surrounding the Earthline permit application has been
connected to  events surrounding two other facilities in the area: the
municipal landfill owned and  operated by Interstate Waste Removal ,and  a
chemical  tank farm proposed by Dow  Chemical.   (Nationally publicized
hazardous waste sites also have had an impact and will be discussed
subsequently.)  The siting and operation of the municipal landfill
introduced SCA to Bordentown  leaders and generated  concerns among those
leaders  as to the integrity of the company.  The Dow proposal was a
major  impetus for area  residents  to organize politically.

In mid-1977  Interstate Waste  Removal began  operating a  100-acre.
municipal landfill at a site  across the street  from Bordentown  Regional
High  School.  Area leaders had expressed some  concerns during this
                                  159

-------
 landfill's siting process and local jurisdictions  sued the state on
 jurisdictional grounds.   The suit argued that  local  jurisdictions  should
 have control over solid  waste management decisions.   The courts  ruled
 that SWA had authority in this area and  could  preempt local controls
 (i.e.,  zoning).   The development of the  sanitary landfill was  deemed
 important because of the limited number  of  sanitary  landfills  in the
 area.    Local leaders indicated that,  in keeping with this reasoning,
 Interstate had promised  the facility would  always  be used for  municipal
 waste.   A July,  1977 article in the Trenton Times  claimed that the
 landfill would give SCA  subsidiaries a significent advantage in  bidding
 for municipal waste collection contracts in the Trenton area.
 Interstate also  has had  the contract to  collect municipal waste  in
 Bordentown city.   In recent years the  city  and Interstate have been in
 court a number of times  in connection  with  the contract.   Interstate has
 sued to prevent  the city from awarding the  collection contract to  firms
 submitting lower bids than Interstate's  on  the grounds  that those  bids
 were unresponsive.   City officials  claimed  that Interstate has been
 guilty  of mismanagement  and poor service.

 In  discussing the city's problems with Interstate, the  mayor of
 Bordentown city  referred to articles on  the New Jersey  garbage industry
 in  the  Trenton Times.  These articles  described the  city's  legal fights
 with Interstate.   They generally characterized that  industry as
 increasingly centralized to the  point  of being monopolized in some
 regions  of  the state and as being dominated  statewide by  eight SCA
 subsidiaries.  The  garbage  industry  pursued  "hard-nosed business
 practices"  using  "high-powered  lawyers".  Interstate, however, was
 specifically excluded from any  links to the  most strident  charges.
 Although the articles  referred to "reports  of mob-style incidents," it
 did state that no indictments had been made  in connection with these
 incidents.   State regulatory agencies  through  ineptness and scarce
 resources were characterized in  the articles as generally ineffectual in
 regulating  garbage  firms.

 The significance  of  the  articles  was that they reflected  the views of
 some local  leaders.  Prior  to the Earthline  permit  application, an SCA
 subsidiary  had generated  anger and resentment  in the Bordentown area.
Local leaders perceived  SCA as a high-powered,  politically powerful firm
 that warranted little  trust.  The state was  considered incapable of
 providing independent control and enforcing  existing regulations.

In mid-1977, Dow Chemical announced plans for a chemical tank farm to be
located  on  the Delaware River in Bordentown Township.  Area residents
opposed  to the project organized Help Our Polluted  Environment (HOPE)
which currently claims a membership of  300 area residents.  Supported by
voluntary donations, HOPE spearheaded citizen opposition to the Dow
proposal.  A protracted debate ensued and opposition grew in size and
sophistication.  By June  of  1978, HOPE  held a non-binding referendum on
the Dow proposal.  According to HOPE almost 1,500 Bordentown residents
                                  160

-------
voted two-to-one against the Dow proposal.   In August Dow sought a re-
view of the proposed 52-acre facility by Bordentown Township to obtain a
conditional use permit for the site.   Within ten days the township pas-
sed an ordinance banning the facility.  Newspaper reports at the time
suggested that Dow considered suing the township to force acceptance of
the facility.  Dow, however, filed no suit  and in December,  1978, re-
portedly elected not to renew an option on the proposed site.

By mid-1978 the Bordentown area had acquired a particular sensitivity to
environmental issues.  Furthermore, local citizens, including lawyers
and scientists, had developed an organization (i.e., HOPE) that had
acquired local political clout and  a successful track record in
mobilizing resources.  Added to this was an established skepticism of
the credibility of SCA.  It was within this context that Earthline sub-
mitted its application to SWA for the secure landfill.               -,

Earthline1s planning for the secure landfill in Bordentown began in 1977
and is directy linked to an Earthline facility in Newark and the absence
of commercial off-site landfills for hazardous waste in New Jersey.1
Earthline's siting of the Bordentown landfill has been managed by an at-
torney retained by SCA.  This attorney was instrumental in developing
New Jersey's hazardous waste regulations when he was with the state at-
torney general's office and has had extensive experience with solid and
hazardous waste management in New Jersey.

Earthline's Newark facility began operations in 1977.  The facility is
designed  to process liquid chemical wastes and produces two residual
products: a liquid effluent and solid and sludge residuals.  The ef-
fluent is discharged into the sewage  system after being tested by Earth-
line and  approved  for discharge by the company and regulatory officials.
The solid and sludge residuals must be landfilled.  Earthline has hauled
these residuals some 450 miles to an  SCA facility in Model City, New
York.  The desire  for a more accessible facility was the  impetus for de-
veloping  a secure  landfill in Bordentown.

In selecting a site Earthline surveyed existing municipal landfills.
(An SWA official indicated about 30 sites in New Jersey had been
investigated by Earthline.)  Earthline felt that an existing municipal
    In 1976, NJDEP  closed  the 220-acre Kin-Buc landfill in Middlesex
    County because  of  extensive  violations  of state regulations.  A small
    portion of  the  site had  been used as a  chemical waste landfill.  In
    February of 1979,  the  U.S. EPA and U.S. Department of Justice filed
    suit against Kin-Buc,  Inc.,  and  seven other  firms for operating an
    illegal disposal site.   It was the first enforcement action under
    RCRA.   With the closing  of Kin-Buc, the state had no operating off-
    site landfills  for hazardous waste.
                                   161

-------
 landfill would imply initial public acceptance of  waste disposal,
 thereby reducing potential public opposition.   The major concern was  the
 geology of potential sites,  particulary sub-surface clay deposits.  The
 lack of clay as a natural liner  eliminated a  large number of  sites
 surveyed and the underlying clay formations were the primary  advantage
 of the Bordentown site.   That site had several other advantages
 including access to the  New Jersey Turnpike and 1-295,  a location in  the
 central area of the state,  and an operating municipal landfill in place.
 Because the Interstate landfill  had recently  been  sited,  a substantial
 amount of data existed on the site's  hydrogeology  and an environmental
 impact statement had been prepared on the municipal landfill.  In
 addition, Interstate is  a subsidiary  of SCA.

 The Bordentown site then met Earthline's' criteria  for a  secure landfill
 and was selected as the  site.  Earthline's lawyer  stressed that  the
 decision to  develop a portion of  the  Bordentown site as  a  hazardous   ;
 waste facility was  independent of the original decision  to develop the
 municipal landfill.   If  that had  not  been true he  suggested that a much
 larger amount  of  land would  have  been purchased originally and that the
 municipal landfill  would have  been designed differently.

 Earthline submitted its  permit application to  SWA  on June  2,  1978.
 Materials (including the engineering  report and EIS) that  had been
 prepared for the  Interstate  landfill  permit were upgraded and submitted
 as  a part of the  application.

 Following standard  procedures, SWA notified local  officals and agencies
 of  the  application  in a  letter dated June 30.   The  letter indicated that
 t,he recipients would be  allowed to make  comments during a 30-day period.
 The  letter, although the  first formal notification  to the community, did
 not  necessarily represent the  community's first knowledge  of  the
 proposed facility.   HOPE's president stated that at  least  two months
 prior to the application's submittal HOPE had  learned informally that
 Earthline wanted  to  develop a hazardous waste  landfill at the Interstate
 landfill site.

Within  two weeks  the first request  by a  local  official for an extension
 of the comment period was sent to the SWA director.  .The Burlington
 County Health Department  in a July  13 letter requested a 90-day
 extension.  SWA granted a 30-day extension.   Subsequent  to that request
 the Planning Board of Bordentown Township and the director of the
 Burlington County Board of Freeholders also  asked SWA for a 90-day
 extension.  In late July  the state  senator for the eighth district,
which includes the Bordentown area, wrote the commissioner of NJDEP
requesting a 90-day  extension.  In  response to these requests, SWA
extended the comment period for 90 days, through October 3.  As a
standard preparation for a public hearing on the permit  applicaton SWA
also scheduled a meeting with local officials, for September 29.
                                 162

-------
In early August the mayo.r of Bordentown City requested a 120-day   .
extension of the comment period.  At that time Betz Converse Murdoch
Inc. (BCM), consulting engineers for the city, was studying the city's
water system.  The mayor's request sought time to have BCM assess the
impacts of the proposed landfill on the city's water supply.  SWA denied
the request.  As a result, the city sued SWA to stop the permit
application review process until BCM completed the water system study.
In an out-of-court settlement SWA agreed to receive comments on the
application until December 15, 1978.  This necessarily postponed any  '
final SWA decision on the application until after December 15.

Also in August the New Jersey Turnpike Authority formally opposed the
proposed facility.  Because the site would be within close proximity  of
the turnpike, the turnpike authority felt the smoke from fires at the
site could dangerously reduce visibility on the turnpike.  Other
concerns were that fire equipment would not be able to respond quickly
to any fires, that SWA had insufficient staff to monitor on-site
operations properly, and that truck traffic from the site would
interfere with turnpike ramp traffic.

In the summer of 1978 the Earthline application had generated
substantial concern among local officials whose major response was to
seek additional time.  Other events took place that summer which had  no
relation to Earthline's actions but which would subsequently have
substantial impact on the opposition.  As described above, local
officials' actions in August effectively quashed Dow's plans for a
chemical tank farm; these actions lent credibility not only to those
officials' powers but also to HOPE which had played a lead role in     •
opposing Dow.  Also in August the trial concerning the Earthline
hazardous waste landfill in Wilsonville, Illinois ended and the local
judge ordered that landfill closed and its contents exhumed. .While the
exhumation order was subsequently stayed during the appeal of that
judgement, the closing of the site was perceived as a major victory for
the  citizens of Wilsonville.  Earlier in the summer the New York State
Department of Health declared a health emergency in the area around Love
Canal in Niagara Falls, New York.  The publicity surrounding Love Canal
has been nationwide and has dramatized the problems of improper
hazardous, waste disposal.                                          •

On  September 18 one of Bordentown's state assemblymen introduced a bill
into the state legislature.  The bill called for a ban against the
   The  disputes over Love Canal and Wilsonville are markedly
   different.  Wilsonville has operated with a state permit from the
   Illinois EPA and has been supported by U.S. EPA, industry, and trade
   associations.  Love Canal was closed in the early 1950's, 20 years
   before any state hazardous waste laws were enacted,  it lacks
   most if not all of the precautions now considered necessary for the
   burial of hazardous wastes.
                                    183

-------
 development of a hazardous waste landfill within 1,000 feet of a school.
 As  written, the bill would have prohibited the development of  the
 Earthline facility.   Over the next four months, that bill would be
 substantially amended as it made its  way through ,the state legislature.,

 On  September 28 HOPE held an informational meeting  attended by about  150
 persons.   HOPE's purpose in holding the meeting was to warn residents of
 the risks involved in Earthline's proposal.   Speakers at  the meeting
 included:  1) the assistant attorney  general of Illinois  who was in
 charge  of Illinois'  case against the  Wilsonville facility;  2)  the
 special attorney for Wilsonville residents in the same .case; 3) members
 of  the  Love Canal Home Owners Association;  and 4) local officials from
 Lewiston, New York who were opposing  an operating SCA hazardous waste.
 facility  in Model City,  New York.   As reported in the Trenton  Times the
 various speakers described the disabling health effects linked to Love
 Canal and campaigns  against other operating SCA facilities.  The
 assistant Illinois attorney general claimed that the Bordentown proposal
 was similar to the Wilsonville facility except that  the Bordentown
 facility  would overlay a water supply.   The possibility of  endangering a
 water supply was,  he claimed,  "insane."

 In  early  October SWA asked EPA's Region II  office to  review the
 Earthline application.   EPA agreed and arranged for  Battelle Memorial
 Institute to perform the review.   In  subsequent interviews  SWA and EPA
 officials stressed that  EPA's  review  did not imply  that EPA would play a
 major role  in the  decision to  approve or deny  the permit.   According  to
 the head  of Region II's  solid  waste branch,  that office's policy was
 that SWA  was the permitting agency and  therefore was  responsible  for  the
 final decision.

 On  October  6,  the  Stevens Institute of  Technology submitted its  report
 on  the  Earthline application to  Bordentown  township and Burlington
 County, both of  which had retained the  institute.  The  report  questioned
 the  benefits to  New  Jersey of  developing  a  small secure landfill  and
 noted the inconsistency  of the five-acre site  size listed in the
 application's  supporting  documents  and the  100-acre size found in  the
 application itself.   A large number of deficiencies in  the  application
 were discussed,  including  descriptions of existing conditions and vague
 or meaningless data  on operating procedures, wastes accepted, liners,
 and monitoring provisions.   Noting  the proposed  location .over an
 aquifer,  the report  found  an absence  of  soil tests and  leachate
 generation estimates.  The  report  recommended  the development of an EIS,
 the  correction of  data inadequacies, and  reconsideration of  siting such
a facility near  an important aquifer.

About a week later, two Bordentown  state assemblymen announced that they
had  petitioned New Jersey's  governor  to deny the application.  They
declared that "the tragedy of Love  Canal cannot be  permitted to repeat
 itself in New Jersey."  They based  their appeal  on the potential risks
                                 164

-------
to the water supply of nearly one million people and deficiencies in the
application cited in the Stevens Institute of Technology report.    ''','•

Beginning in October, local jurisdictions and organizations began to
communicate their formal opposition to the proposed facility.  Based
largely on the Stevens Institute, Bordentown township and Burlington
County passed a joint resolution against the application.  The
resolution cited the proximity to the high school, the population
density of the area, economic disbenefits, and a fear of Bordentown  .
becoming the dumping ground for the state as well as other states.  That
resolution also sought local control over such sitings.  The Board of
Education of the high school also opposed the proposal.  In addition to
issues raised by the township-county resolution, the board of education
cited "grievous" public health problems at other SCA facilities and the
lack of guarantees by Earthline, the state, or any financially
responsible party of the site's safe operation.

On October 23, SWA met with local officials as a standard procedure
preparatory to a public meeting on the application.  This meeting had
been originally scheduled for late September but had been delayed
because of the suit by, Bordentown City against SWA.  The meeting
provided an opportnity for SWA officials to explain the application and
regulatory procedures to local leaders.  The next day, SWA wrote to
Earthline seeking more data for the application.  (A second SWA request
for more data was sent to Earthline in mid-November.  By January of
1979, Earthline had responded to the first request, in part by providing
more data, in part by reaffirming previously submitted data.  According
to an SWA official, Earthline had not responded to the second request.)

Earthline also tried to deal directly with local leaders.  According to
the attorney for Earthline, his  offer to meet with local leaders was
deferred several times and never agreed to.  An offer by Earthline to
provide some compensation  to Bordentown in return for development of the
facility was flatly rejected by  local officials, according to an SWA
official.  Earthline1s attorney  also went on local radio and  television
shows to "debate" opponents of the facility.  According to opponents
these debates did little to change anyone's mind.                    _

In November, opposition began  to solidify and opponents escalated their
tactics.  The city,  township, and county began to discuss openly the
prospect of suing SWA claiming:  1) that  the secure landfill  fell within
the jurisdiction of  local  solid  waste management  planning and was
therefore  subject to local controls; and  2) that  SWA should  not process
applications until  regulations required by RCRA were issued.  Eventually
a suit  based  on  the jurisdictional dispute was filed, but  the court's
decision reaffirmed SWA's  sole authority  over hazardous waste facility
siting.

In  anticipation  of  the  SWA-sponsored public hearing, HOPE organized  a  ••
week  of "anti-Earthline",  "pro-people" events.  On  Sunday, November  12
                                    165

-------
 HOPE organized a parade and rally complete with floats, banners, and a
 car  caravan.   It was  reported to  have  lasted three hours.  On the 14th
 and  15th,  a film crew from ABC's  "Close Up" news  program filmed some of
 HOPE's  activities against  the Earthline proposal.* The following night
 (November  16)  the local NBC affiliate  also filmed local citizens'
 efforts to stop the facility.  HOPE's  other actions during the fall
 included a petition drive  and the placement of  ads in local papers.

 Every available source strongly indicates  that  by the time of the
 hearing, area  residents  were intent on stopping Earthline.  As the
 Trenton Times  reported the morning of  the  first day of the hearing,
 "suddenly,  almost everyone here (i.e., in  the Bordentown area) has
 become  an  environmentalist."  The article  quoted  a fairly broad spectrum
 of local residents, including student  leaders at  the high school, as
 being opposed  to the  facility  and referred to a petition against the
 facility signed by almost  80 percent of the high  school student body.

 On November 17  and 18,  SWA held the public hearing on the Earthline
 application at  the Bordentown  Regional High School.  Over the two-day
 hearing approximately 50 persons  in addition to SWA and Earthline
 representatives  spoke.   The hearings took  a total of 13 hours, and the
 hearing record  ran to 600  pages.

 The hearings began with  presentations by SWA and Earthline
 representatives.   Earthline officials  specifically declared that
 adequate provisions (i.e.,  the clay base and liners) had been made to
 prevent leaching  into  groundwater.  What followed was a series
 of statements and presentations by a broad spectrum of public leaders
 and  citizens from within and outside the Bordentown area.   Speakers
 included the area's state  legislators,  local elected officials,  HOPE's
 president,  and members of  the  legal and engineering staffs of the
 Illinois attorney-general's  office, some of whom had spoken at HOPE's
 September 29 meeting.   All previously voiced issues were repeated during
 the hearing.  The  Illinois  officials charged Earthline officials with
mismanagement and misleading the public in connection with the
Wilsonville facility.   Pleas were made  to SWA by state and local elected
 officials and private citizens to deny  the permit.  On the grounds that
no relevant federal or state regulations were in place,  HOPE's president
 claimed that industry was determining the nature of  hazardous waste
management  practices.   Consequently,  he stated,  SWA's  decision on
the application and the public hearing  had no credibility.   One  state
legislator  announced he would seek a one-year ban on chemical landfill
applications until state guidelines for application review had been
established.
   The Bordentown siting controversy was included in a "Close Up"
   report on hazardous waste problems.   That program was  aired on March
   29, 1979.
                                  166

-------
Outside the hearing, Earthline's attorney reportedly characterized much
of, the public testimony as emotional and fear-ridden because of
distortions of real issues.  He claimed that the technical design for
the proposed facility was sound and that SCA would develop a perpetual
care fund for post-closure maintenance.                               >

Within two days of the public hearing, the New Jersey Senate passed by
voice vote a resolution banning chemical waste dumps in locations where
they endangered public water supplies.  Specifically referencing the
Bordentown proposal, the resolution termed the site "unacceptable".
While the resolution.had no legal standing, its sponsor hoped it would
sway SWA's thinking.  The same day, the commissioner of the Department
of Environmental Protection, SWA's parent agency, announced that no
decisions on any chemical waste landfill would be made until state  '
hazardous waste regulations were issued.  The commissioner indicated
late January 1979 as the earliest possible decision date on the
Earthline application.

Formal opposition  to the Earthline proposal also continued to mount
during November.   The Burlington Township Environmental Commission and,
Wrightstown, a city in Burlington County about ten miles southeast of
Bordentown, passed resolutions against the proposal.  The Wrightstown
resolution asked the governor to intervene in the decision, and argued
that  the profits that would accrue to Earthline could never compensate
for  the risks to the health and welfare of hundreds of thousands of  .
people.

On November 30 BCM submitted its report on potential groundwater impacts
to Bordentown city.  The major conclusion of that report was that      :
"unless it can be  shown that leachate  from the proposed landfill can
never escape  and contaminate the underlying aquifers, then it is our
opinion that  this  in itself should be  sufficient cause to reject the
permit application."  This conclusion overrode  the BCM finding that -the
secure landfill would have little impact on the  existing water supply
and  distribution system.   The report  covered much of the same ground and
reached  conclusions similar to that of  the earlier Stevens Institute
report.   It  also,  however,  analyzed more carefully the use of a hypalon
 liner and pointed  out the  potential for certain  compounds to attack the
 liner material  and seriously degrade  the liner's  integrity.  From
Earthline's  application, BCM found that these compounds were within
 classes of wastes  proposed for burial at the  site.   .     -----    Y

 In mid-December SWA responded to various officials who had communicated
 concerns  to the  state.   In a letter to a local  jurisdiction SWA  .
 explained the state's need for  safe disposal  facilities  to accommodate
 the large volume  of hazardous wastes  generated by the state.  SWA  also
 explained the status  of  the application review  to one of New Jersey's
 U.S. Senators who had been contacted  by the  Bordentown Regional Teachers
 Association.  On December 15 the comment period  for  the Earthline
 application closed.
                                    167

-------
 On January  12,  1979,  SWA held hearings  on proposed hazardous waste
 regulation.  Representatives  of HOPE and  others active in the Bordentown
 siting  controversy  spoke at those  hearings.  Following state procedures,
 those regulations would  be officially promulgated approximately two
 months  after the hearings.  Given  the earlier  statements of state
 regulatory  officials, the date for a decision  on the Earthline
 application was mid-March at  the earliest.

 By late January the state legislature had acted on the bill originally
 designed to ban hazardous waste landfills within 1,000 feet of a school.
 In the  four months  since its  filing, the  bill  had changed substantially.
 In its  final form,  it placed  a moratorium on state consideration of
 applications for hazardous waste landfills pending a state-developed
 comprehensive plan  for siting such facilities.  Such a plan would far
 exceed  the  scope of then proposed  state regulations.  In that form the
 bill was unanimously passed by both houses of  the state legislature.
 SWA had lobbied the governor  not to sign  the bill.

Also in January EPA's Region  II office released Battelle's review of the
Earthline permit.   That  review, requested  by SWA in October, was
generally favorable and  specifically commended the site's geological
qualities and the use of liners to protect groundwater.  The review did
call for additional monitoring and safety  provisions as well as an
expanded EIS.  SWA said  they would add the report to the thousands of
pages of technical and public comments received to date in making their
final decision.

Field interviews were held in January, 1979.   At that time no final SWA
decision had been reached and the various parties were weighing options
for the future.  Earthline's attorney was confident that SWA would grant
the permit;  he dismissed  most of the opponents' issues as emotional or
specious.   The feeling that SWA would grant the permit was  shared by
HOPE's president and at  least some local officials.   If SWA granted the
permit,  the mayor of Bordentown city said local jurisdictions would
appeal.   He indicated a willingness to spend up to $250,000 for legal
talent,  to hire the "F.  Lee Bailey of environmental law," that is, the
best lawyer available.   SWA would make no comment on how the decision
would be made.

On March 23, SWA denied Earthline's application.  In its five-page
administrative order,  SWA cited the following major reasons for the
denial.

       o     The secure  landfill would reduce needed space already
             committed to use as a sanitary landfill.

       o     The proposed facility would be inconsistent with and
             disruptive  to the area's solid waste management planning.

       o     No compelling need to  bring hazardous wastes to the
             Bordentown  site had been established.
                                   168

-------
       o     Hazardous wastes,  if disposed of  at the site,  would
             potentially threaten air and water quality  and diminish
             future productive  use of the site.

       o     The application failed to delineate specific wastes to  be
             disposed of, thereby raising serious uncertainties  as to
             proposed site design and operations.

       o     The application failed to supply  adequate analysis  of man-
             agerial and operational procedures, and of  social,  ec-
             oiiomic,, and cultural impacts.

       o     The ability of Earthline to operate the facility
             properly had not been demonstrated.

In .discussing these reasons SWA cited the 1977 application  for the
sanitary landfill, specifically the "convincing evidence" presented
therein to substantiate a "compelling public need" for a sanitary
landfill.  SWA stated that the site's proximity to the Bordentown Re-
gional High School presented a "needless and unwarranted burden upon and
risk to" the high school's students.  In questioning the management  and
operations reliability of Earthline, SWA specifically referenced the
trial judge's decision in the Wilsonville case.  While SWA  acknowledged
New Jersey's need for environmentally sound hazardous waste disposal    -
facilities, it declared the risks associated with the Earthline proposal
outweighed any potential benefits.

Following SWA's announcement, Earthline's attorney indicated that the
company would consider an appeal to the courts of the application's  de-
nial.

By late March the legislation calling for a moratorium on SWA review of
permit applications until the development of a state comprehensive
facility siting plan had not been signed by the governor.  Bordentown
residents reportedly speculated that a political deal had been struck.
By taking no action to sign the bill, the governor would in effect veto
the bill and the entire process of developing hazardous  waste disposal
facilities would not be derailed.  In return,  the Earthline application
which gave rise to the bill would be denied.
IV.
CHRONOLOGY OF EVENTS
The following chronology of events applies only to those stemming from
Earthline's permit application.  Other indirectly related events de-
scribed in the previous section are excluded for the sake of clarity.

1977 — Planning for Earthline facility begins.

February, 1978 — HOPE first learns of Earthline's interest in de-
                  veloping a HWMF in Bordentown.
                                   163

-------
 June,  1978 — Earthline submits permit application to SWA.   SWA informs
               local agencies of permit application and of 30-day comment
               period for those agencies.

 July,  1978 — The area's State Senator,  the Burlington County Health De-
               partment  and Planning Board  of Bordentown Township, acting
               individually, seek 90-day  extension of  comment period.
               SWA grants 30-day extenstion.

 August,  1978  —  The Director of the Burlington County Board  of
                 Freeholders seeks a 90-day extension;  the Mayor of  the
                 City of Bordentown seeks a 120-day extension so an  on-
                 going city water study can assess impacts of proposed
                 landfill.   New Jersey  Turnpike Authority  formally op-
                 poses proposed facility.   City of Bordentown files  suit
                 until city water study completed;  out-of-court  set-
                 tlement extends comment  period until  December 15, 1978.

 September,  1978  — Meeting between SWA and local  officials scheduled and
                    then postponed.  HOPE holds public meeting in Borden-
                    town to inform citizens  of permit  application.   State
                    legislation filed to ban  HWMFs  within  1000 feet  of
                    schools.                                      .

 October, 1978 — EPA Region II submits permit application to Battelle
                 for  review.   Stevens  Institute Report submitted to SWA.
                 Board  of  education of Bordentown  Regional High  School
                 formally  opposes  facility,  as does Bordentown Township.
                 SWA meets  with local  officials prior to public  hearing.
                 SWA requests  more  data on permit  application from
                 Earthline.  Area  legislators ask  Governor to deny
                 permit.

November, - 1978 — HOPE  stages  a week of events to highlight  opposition
                   to  proposal.  SWA holds two-day  public hearing in
                  Bordentown.  SWA requests more data from Earthline.
                  State Senate passes resolution against facility.
                  Burlington Township Environmental Commission and
                  Wrightstown  formally oppose facility.  SWA delays de-
                  cision until state regulations are issued.   BCM report
                  to Bordentown city submitted.

December, 1978 — City,  township, and county sue SWA claiming local
                  authority over hazardous  waste management.   SWA writes
                  to local jurisdiction explaining need for  HWMFs in New
                  Jersey and to U.S. Senator explaining status  of permit
                  review.  Comment period closes.
                               170

-------
January, 1979	State legislation to stop all permit reviews by SWA un-
                 til full state hazardous waste plan developed sent to
                 governor for his signature.  Public hearing on state
                 hazardous waste regulations held.  EPA/Battelle favor-
                 able review of permit submitted to SWA.  Local suit
                 challenging SWA jurisdiction over solid waste man-
                 agement dismissed by court.

March, 1979 — SWA denies Earthline's application for a permit.

V.     ATTEMPTS TO SECURE SUPPORT

A clear distinction should be made between SWA's actions designed to in-
form the public about permit review procedures and general hazardous
waste needs and Earthline actions intended to generate support or soften
opposition to the specific proposed facility.  Actions by both
organizations are listed below.                  •

       o     SWA notification of local officials of the receipt of the
             Earthline permit application.

       o     SWA's meeting with local officials preparatory to the
             public hearing.

       o     Earthline's unsuccessful attempts to meet with local,
             officials.

       o     Debates between Earthline and opposition representatives
             aired by local radio and television stations.

       o     The presentations by SWA and Earthline at the public
             hearing.

       o     Communications by SWA to various officials either
             explaining the course of events or the general need in New
             Jersey for disposal facilities.
VI.
SUMMARY EVALUATION
The March, 1979 decision by SWA is essentially irrelevant to the
question of whether attempts to secure support for the Earthline
proposal could in any way be termed successful.  Even without that
decision it was clear that there was no support for the facility locally
nor was there any evidence of neutral parties.1  An approval by SWA would
have been met with continued opposition.   ;

It is certainly possible to suggest that the entire experience,
including SWA's actions and perhaps even Earthline's, increased local
support for environmentally sound solutions to hazardous waste disposal
problems.  Opposition leaders, however, clearly distinguished between
their support for such solutions and the Earthline proposal.  The role
which the
                                 171

-------
 attempts  outlined  in Section V  played  in this process is most likely
 minor  compared with  other actions which  provided Bbrdentown area
 residents with information  on hazardous  waste problems and solutions.

 Attempts  to address  issues  raised by local opponents were relatively
 few.   They were certainly made  after opposition had solidified.  The
 majority  of Earthline's  efforts focused  on preparation and defense of
 its application and  the  provision of some additional data  requested by
 SWA.   These SWA-Earthline exchanges were quite distinct from the public
 response  to the proposal and any attempts to react to that response.

 A number  of issues were  raised  by opponents and the major issues are
 summerized below.  Among these  issues  some were clearly important and
 less susceptible to  ambiguity in terms of strengthening the opposition
 and impacting SWA's  decision.   These issues can be characterized as
 pertaining to credibility,  political sensibilities, and institutional
 factors.  These issues,  in  combination with the broad-based political
 resources amassed by opponents,  appear to have been decisive.

 Credibility of Earthline and SCA ;— Opponents claimed that Earthline and
 SCA could not prove  that reliable development and operation of the
 facility would be guaranteed.   This was  largely based on company claims
 made during the development of  the Interstate sanitary landfill and on
 the Wilsonville case.

 Site location — Location above  an aquifer and proximity of the site to
 the Bordentown Regional  High School were considered unacceptable risks.

 Credibility of SWA — Opponents  doubted SWA's ability to make an
 independent, reasoned judgement  on the application.  This was based
 largely on assumptions that SWA was predisposed to approve the
 application (or at least be more concerned about waste disposal than
 public health), that SWA had no  guidelines (particularly siting
 criteria) by which to judge the  application,  and that SWA's limited
 qualifications and resources prevented a thorough,  independent review.

 Technical suitability — Opponents considered engineering and geological
 safeguards for the proposed facility insufficient to eliminate adverse
 impacts, particularly the contamination of the Magothy-Raritan aquifer.
 Technical studies by consultants to opponents supported this view while
 those prepared for Earthline and EPA's Region II office came to
 essentially the opposite conclusions.

Other impacts on the community — Opponents did hot want Bordentown to
become the hazardous waste "dumping ground" for the state.   They also
feared that the site's development alone would create general economic
disbenefits to the area.
                                 172

-------
Legal jurisdiction over solid and hazardous waste management -- Local
officials claimed authority for waste management planning and therefore
claimed a legal role in facility siting.  This argument was dismissed by
the court.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

The following are the major factors which led to the development and
coalescing of opposition to the Earthline proposal.

       o     A predisposition on the part of at least some local leaders
             to mistrust solid waste companies in general, and SCA sub-
             sidiaries in particular, based on prior experiences with
             these firms.                  ,  ,

       o     A history of local leaders and the general public opposing
             the siting of facilities considered to be objectionable.

       o     Ultimately successful efforts to block the siting of the
             Dow tank farm, thus creating a successful track record and
             a loosely working coalition between local environmentalists
             and elected officials.

       o     SWA's notificaton of local officials and agencies of the
             permit application.

       o     National publicity surrounding Love Canal.

       p     Numerous requests to SWA and a law suit by Bordentown City
             to extend the comment period.

       o     The decision in the Wilsonville, Illinois case.

       o     Actions by state elected officials to introduce legislation
             against the facility and to appeal to the governor.

       o     HOPE's informational meeting in September.

       o     The Stevens Institute report submitted to the township and
             the county.

It is probably impossible to determine when opposition reached a stage
where maintenance of that opposition was at least as important as
further growth.  By late October, however, it would appear that most
parties were irrevocably opposed to the proposal even if formal
positions had not been taken.  The following actions can then be said to
serve as demonstrations of opposition and hence as sustainers of
opposition.

       o     HOPE's activities in the week prior to the public hearing.

       o     The public hearing.
                             173

-------
        o     The Senate resolution against  the  facility.

        o     The BCM report  to  Bordentown city.

        o     The city-township-county  suit  against SWA on  jurisdictional
              grounds.

        o     The bill sent to the  governor  banning permit  reviews until
              the development of a  state  facility  siting plan.

VIII.   GENERAL COMMENTS                .....,,.

The  siting experience in Bordentown provided key  participants with a
wide range of insights and views on siting  and  other hazardous waste
problems.  These are described  below.

One  local elected official felt that the onus for disposal should be
placed  on hazardous  waste generators.  He had no  faith in state or
federal bureaucrats  playing  major  roles  because they lacked competence.
Commercial disposal  firms could either not  be trusted or lacked
financial resources  commensurate with  risks entailed.  This left .larger
generators as the responsible implementors; these firms had sufficient
assets  to guarantee  that any problems  could be paid for.  To pay for
disposal, costs  should be included  in  product prices.  Finally, disposal
techniques should stress rendering  wastes harmless and avoid land burial
of hazardous waste altogether.

A state  elected  official differed sharply on governmental roles.  While
questioning the  usefulness of an expanded state role, he saw potential
for  major changes in federal and/or multi-state agency roles.  One
action would be  for  EPA to survey the  state to determine if any areas
are  suitable for  disposal sites.  While his ideas were less fixed on
ownership/ operation arrangements,  he  considered complete federal and/or
regional agency  control, or  federal or regional agency ownership coupled
with private operation as the two most viable options.

HOPE'S president made both specific and general comments.   Echoing the
complaints of other  opposition  leaders, he  felt that the costs to local
governments and  organizations for technical studies of the Earthline
application were unfair.  A mechanism needs  to be developed to redress
the  imbalances in resources  available to state agencies and private
industry and those available to communities  which are asked to live with
the  consequences of  state agency/private industry decisions.   Public
input, he felt,  was critical to siting because such scrutiny would more
thoroughly test  the viability of proposed facilities.   To  ensure that
reasoned decisions are made,  the state should develop siting criteria
before analyzing any permit application.   In the event of  technical
disputes by presumed experts, a scientific panel or "court" would be the
best way to settle such conflicts.   Site ownership should  be in state
                                 174

-------
hands because states are more likely to make environmentally sound
decisions on site selection than industry.  States could then contract
out operations to private firms.  The .federal government should promote
"cradle to grave" monitoring of waste.  Finally, the most critical need
is for perpetual maintenance and monitoring of sites after site closure.

Earthline's attorney considered existing siting procedures to be
satisfactory for the most part.  He did feel that EPA should work to
improve the integrity of state regulatory agencies so that the public
will be more trusting of those agencies.  On the other hand, he saw New
Jersey's disposal problems as particularly severe because there, are .no
commercial hazardous waste landfills and state and federal policies have
increased the demand for these facilities.  Thus new secure landfills
must be found.  He considered the Earthline application a demonstration
project not only of a facility but of the state's ability to develop
disposal capacity.  During Centaur's interview he said that if the
Earthline permit were denied, the state would demonstrate its inability
to solve its hazardous waste problems.

State comments are included in the state program write-up elsewhere in
this report.
                                175

-------
                            ALLIED CHEMICAL

                          ROSSVILLE, MARYLAND
I.
INTRODUCTION
Since 1974, the Allied Chemical Corporation has unsuccessfully attempted
to establish its own private landfill in Rossville, Maryland.  The
proposed landfill would be owned by Allied but operated by the Maryland
Environmental Service (MES), an agency within the Maryland Department of
Natural Resources.  The site would be used for exclusive disposal of
chrome ore wastes generated at Allied!s chrome plant in nearby
Baltimore.  Allied was forced to seek out the site when the Maryland
Port Administration (MPA) announced early termination of its 40-year
disposal agreement with Allied.  Allied has been unable to develop the
Rossville site to date because the county has denied Allied a special
zoning exemption.  Opposition to the landfill developed soon after the
first public knowledge of Allied's intention.  Opposition has centered
on technical, operational, and political issues and has become
deeply-rooted and strongly emotional.  The opponents' fight against the
facility has involved all major political leaders in the area as well as
the governor and lieutenant governor.

Allied and MES have made concerted efforts to address publicly raised
issues and/or to refute opponents' changes.  While Allied has been
credited with being open and forthright in dealing with opponents, these
efforts have had little discernible effect on the opposition.
II.
BACKGROUND INFORMATION
The proposed landfill site is located at the intersection of
Philadelphia Road and Route 40, about five miles east of Baltimore.  The
land is currently zoned for light manufacturing and owned by the Arundel
Corporation which operates a brick manufacturing plant on the location.
All clay needed for the brick manufacturing operation is excavated from
two large pits on the 60-acre property.  The property is actually part
of a several-hundred acre Arundel-owned plot which includes an
immediately adjacent industrial park development.  The site is bordered
by several private homes.  A hospital and community college are located
within a mile of the brickyard.

The site has particular advantages for Allied.  It is less than ten
miles from Allied's chrome processing plant in Baltimore and is well
served by highways and a rail line.  The site had already been excavated
for clay used in brickmaking thereby providing a 38-acre repository with
at least 12 years dumping capacity (given Allied's yearly chrome
production rates).  Study showed that the clay lining and iron stone
underlayers made the pits impervious to water.  According to Allied's
engineering consultants, the site is located on the Arundel Clay
formation composed of two clay strata which would,contain any leachate
for a period of 335 years.
                                 176

-------
According to Allied's engineering plans, total waste confinement was to
be achieved by complete encapsulation of each day's deposit of chrome
ore refuse within an impermeable clay envelope.  The bottom and sides of
the pits provided at least five feet of clay lining and ten feet of
rock.  This would protect underlying groundwater from leachate
contamination.  Each day, the waste would be covered with clay to
prevent saturation of the refuse and/or surface runoff.  The waste
material itself has a built-in safety shield, that is, an ability to
hold considerable amounts of water without leaching.  Finally, Allied
proposed to install observation wells for monitoring leachate and
holding ponds to capture any possible surface runoff caused by
precipitation.  Runoff would be confined there, tested for hexavalent
chromium content and treated if necessary.  Allied agreed to give WRA
access to all monitoring and testing information.  Allied also agreed to
comply with the state's evolving hazardous waste management regulations
regarding maintenance and closure.  Included among these is a proposed
$100,000 a .year permit fee for each year of operation.  The fee would
provide a contingency fund to help compensate for possible damages after
the facility closed.                                        .

Allied Chemical is one of the nation's largest chemical maufacturers: in
fiscal year 1978 it reported total sales of over $3.2 billion.  The
company has a fairly extensive program to provide for its own waste
disposal needs; however, not all plants have their own facilities.,
Allied operates one of the three chrome processing plants in the
country.  The chromium chemicals produced at Allied1s Baltimore plant
are used in a wide variety of industrial applications including metal
finishing, leather tanning, pigment manufacture and oil well drilling.
In most cases, chromium applications are considered vital and       :   , .
irreplaceable where used.                                     ,

Rossville itself is a largely working class community of industrial
parks, shopping centers and scattered homes about four miles east of
Baltimore.  The area has traditionally attracted manufacturing and
processing operations otherwise unattractive to the. metropolitan area.
Recently, however, Rossville has experienced an increase in moderate to
middle income housing development due to the area's affordable home and
land prices.  This growing trend is expected to continue accompanied by
a local policy encouraging compatible industrial growth.  ,

There are no incorporated cities or townships in Baltimore County (1977
population, 644,000).  Rossville, therefore, simply refers to a small
neighborhood or concentration of development under the direct
jurisdiction of the county government.  The county government consists
of a locally elected council and an executive administrator.
III.
HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE
During the development of its plans Allied had to obtain regulatory
approval from the state and from Baltimore County.  State permits from
the Water Resources Administration (WRA) included a groundwater
                                 177

-------
discharge permit and a facility permit.  In addition to state permits,
Allied also needed local zoning approval before it could operate the
landfill.  The Arundel property was zoned for light manufacturing.  A
special zoning exemption for heavy manufacturing was required for waste
disposal.  Baltimore County regulations for landfills also require sign
offs by the fire department, the highway department, and the local
health department once zoning has been approved.  Finally, some local
parties contend that a zoning change to heavy manufacturing would
constitute a change in the county's solid waste master plan.  This, in
turn, would require formal review and approval by the County Council.

A by—product of chromium processing is an odorless, non-combustible
refuse.^  Allied's Baltimore plant produces approximately 93,000 cubic
yards of this refuse per year.  Its disposal is essential to the plant's
operation.  For years, Allied disposed of its chrome ore waste at an
85-acre landfill adjacent to the Maryland Port Administration's (MPA)
Dundalk Marine Terminal.  In 1967, Allied sold the parcel to MPA with
the agreement that Allied would continue dumping up to 6 million cubic
yards of refuse on the property.  The agreement included financial
penalties for Allied's failure to use the MPA landfill.  MPA intended to
use the filled land for expansion of Dundalk.

Disposal continued at Dundalk until mid-1974.  At that time, MPA
notified Allied it would no longer accept waste after January, 1975 due
to curtailment of its marine terminal expansion plans.  Allied,
recognizing that someday it might need a contingency landfill site, had
already negotiated with a private sanitary landfill in case of emergency
disposal needs.  Allied proceeded to use that landfill exclusively until
MPA, under a remaining 32-year obligation to Allied, provided an
alternate site at Hawkins Point in Baltimore City.  The Hawkins Point
site, however, only had two years remaining capacity.  Allied was once
again forced to consider alternative disposal arrangements.

Allied began to look for environmentally sound sites suitable for
long-term waste disposal as early as 1970.  The search began in earnest
in late 1974.  Siting criteria included proximity to the
   Chrome ore waste has the consistency of a moist, heavy sand
   and contains about 20 percent water by volume.  The material is
   principally a mixture of iron oxides, calcium, magnesium and
   aluminum.  The waste material, however, also contains about 0.2
   percent water soluble and 1.3 percent acid soluble hexavalent
   chromium.  In its solid, damp state, the waste causes no problem.
   However, hexavalent chromium concentrations greater than 0.05
   milligrams per litre render water unacceptable for drinking;
   concentrations greater than 0.1 milligrams per litre are harmful to
   aquatic life.  The chromium ion therefore is considered a hazardous
   waste requiring special handling (i.e., prevention of leachate) in
   disposal.                   "
                                   178

-------
Baltimore plant, transportation access and cost of site preparation.
The most important criteria were proper soil type and amount for waste
containment, adequate size to hold at least ten years of Allied refuse
and overall availability for use.  Of 60 sites considered, two appeared
promising.  One was eliminated because it required massive clearing and
excavation and because the zoning department of the county in which it
was located clearly opposed use of the land for waste disposal.  The
second site was Rossville.

Since Allied had recently suffered from $20 million fines and bad
publicity associated with Kepone contamination in Hopewell, Virginiaj
the company was particularly wary of any disposal method or site that
demonstrated risk of environmental pollution.  The decision to dispose
of the chrome ore wastes in carefully constructed cells of impervious
clay was made only after a thorough investigation by Allied and WRA of
alternate means for handling and disposal.  A number of methods to
reduce the hexavalent chromium content of the waste through additional
chemical treatment proved incomplete. , Such processing resulted in new
and significant amounts of chlorides which still needed.land disposal.
Ways of recycling the hexavalent chromium into alternate, commercially
useful materials also proved infeasible.  By June 1975, WRA agreed with
Allied that landfilling the chromium waste was the most viable disposal
method at least until another alternative became known.

This research underscored the importance of identifying the Rossville
site for development as a landfill.  Favorable technical reports by
Allied's engineering consultants boosted Allied's interest and
confidence in the site.  Allied envisioned grading the site once filled
then putting the land to higher use, possibly as an extension of the
neighboring industrial park.  By mid-1975, Allied had reached a purchase
agreement (which to date has not been consummated) with the Arundel
Corporation.  The Arundel Corporation would retain an access strip from
the road to the brickyard which it would continue to operate for some
time.  Allied, in turn, would receive rights to use the access roads to
the highway, rail line and other area roads.

In July 1975, Allied sought a state discharge permit for the landfill.
Typically, the Maryland State Health Department approves all landfill
applications, but because the Health Department code does not
specifically address hazardous waste disposal, Allied was referred to
WRA.

WRA, a department within the Maryland Department of Natural Resources,
is responsible for issuing NPDES (surface water) and state discharge
permits to all point sources.  WRA recognized Allied's need for a
landfill site.  It also recognized a state responsibility to assist
Allied since another state agency (i.e., MPA) was partly responsible for
the company's dilemma.  WRA reviewed Allied's plans and determined that
although certain technical problems still remained, the site appeared
eligible for a groundwater discharge permit and a hazardous waste
permit.  WRA also suggested that Allied request the assistance of
                             179

-------
the Maryland Environmental Services (MES) in developing a landfill at
Rossville.  WRA believed that MES's participation in the project would
help ensure the technical quality of the operation and greater local
acceptance of the landfill.

MES was established as a corporate utility agency of the state in 1970.
The agency operates as a non-profit enterprise to assist local
governments, industries and other state agencies in matters of waste
management and water supply.  Its purpose is to serve both public and
private interests by supporting efforts to achieve environmental
quality.  MES recovers its costs through contract arrangements with its
clients.  MES has no regulatory functions or police powers and must
conform to all regulations and decisions of other state agencies.

After several meetings in the summer of 1976, Allied formally invited
MES to submit a proposal to assist Allied in developing a landfill.  MES
responded in September, 1976, thus becoming a partner in the venture.
MES agreed to help Allied through the regulatory process, to supply
technical review and advice where possible, and to operate the landfill
facility once it was established.

A preliminary assessment by Allied and MES indicated no insurmountable
problems in securing necessary permits and approval.  Allied anticipated
that its first request for a zoning change would be denied but that a
special exemption eventually would be granted because the plans met all
federal regulations and county requirements.  The only major problem
anticipated was securi.ng county approval. regarding the planned.
landfill's compatibility with the county solid waste master plan.  On
this point, Allied planned to contest a negative decision on grounds
that the county plan did not provide for waste disposal beyond ten
years.

Public  response to Allied1s proposed facility was strong and
well-organized early in the regulatory approval process.  Although
rooted  in emotional objections to  the presence of a HWMF in their
neighborhood, -community opponents challenged the plans on the grounds  of
technical issues related to specific site characteristics.  The
opposition drew strength from unity among local community improvement
groups  and political clubs as well as the backing of local elected
officials.

The public first became aware of Allied1s landfill plans shortly after
MES became involved in the project.  MES encouraged Allied to meet with
state and county officials early, both as a courtesy to them and to
avoid announcing the landfill plans amidst  the anxiety of a public
hearing atmosphere.  Alli.ed took MES's suggestion and invited the state
representative, senator and county councilman representing the Rossville
area to discuss the plans with Allied.  The officials seemed interested
in  the  proposed landfill, especially since  it offered eventual
improvement of the unsightly brickyard pits and possible industrial/
commercial development for Baltimore County.  The state  senator
                                 180

-------
suggested  that a public meeting be held  to  present  the  plans  to  the
greater public.  The Greater Rosedale Community Council, an umbrella
group representing  17 local groups, was  contacted to notify other
interested publics  of the upcoming meeting.1

The informational meeting was held in November, 1976.   Approximately 80
people including local officials and representatives of community groups
attended.  MES introduced the agenda, discussed state involvement in the
project, and outlined the project's lifespan and general operations.
With the help of its consultants, Allied explained  the nature of the
facility (e.g., material to be disposed, safeguards, plans for future
use) and the company's need for disposal.   Throughout the discussion,
Allied spoke candidly about potential problems and  risks in operating
the proposed landfill.  The public was invited to ask questions  to which
MES, Allied and Allied's engineering consultants responded.

The impact of the meeting was somewhat greater than Allied or MES
probably expected.  Both parties anticipated some negative response,
especially in view  of the history of public reaction to hazardous waste
management facilities, Allied's recent Kepone publicity and the  presence
of organized community groups.  But by the  end of the meeting, the
audience had developed what the newspapers  referred to as a "polite, yet
antagonistic attitude toward representatives from the chemical company
and an engineer from their consulting firm".  The local county
councilman who before the meeting indicated support for restoration of
the Rossville site, spoke out in strong  opposition  to the landfill at
the end of the evening.  The councilman  spoke of his desire to uplift
the area rather than further degrading it with a "poison pit".   The,
Greater Rosedale „Community Council strongly supported the councilman's.
position in a membership vote taken immediately after the meeting.  The
state senator, although reserving comment until Allied  answered
technical issues raised, also showed some displeasure with the proposal.
His displeasure would grow within a short time into adamant opposition
to Allied's plans.

A number of technical concerns were raised  by members of the attending
audience.  Primary  concerns focused on risk of groundwater contamina-
tion, surface water runoff from precipitation, nuisance (e.g. , dust,
noise, traffic congestion) and safety factors associated with hauling
seven days a week,  and indefinite safeguards for future site
.development.
   Although the area is not heavily populated, a number of local
   political and neighborhood improvement groups have been; organized in
   and around Rossville.  These groups have lobbied successfully in the
   past for tax relief, road repair and other community concerns.  In
   some cases, individual neighborhood groups have rallied under the
   umbrella organization to add focus and strength to their common
   efforts.  The proposed landfill siting was the area's first
   experience with a controversial environmental issue, of such
   magnitude.
                                 ±81

-------
Allied and its consultants offered assurances that the pits' clay lining
would prevent leachate, that the holding ponds and monitoring provisions
would deter surface runoff, that hauling hours would be adjusted to
avoid disturbing neighboring residents, that tarp covers on trucks would
eliminate blowing dust and that WRA's participation would ensure proper
oversight of the landfill after closure.  Despite these answers, the
public felt Allied was speaking in generalities, unprepared to address
some of the issues raised and unable to offer adequate reassurances to
balance risks.

The audience drew parallels between Rossville and Norris Farms and Hart
Miller Islands, two other landfills with serious leachate problems.
Spokesmen for the Greater Rosedale Community Council complained of
burdening Rossville with wastes generated in other communities just for
the convenience of Allied.  A number of people noted they were tired of
getting everyone else's waste.  Because of past and ongoing court
situations depicting Allied as a "polluter", many residents simply did
not want to take a chance with a landfill.

Following the meeting, the local press carried a number of articles and
editorials highlighting the "hazardous" nature of Allied's wastes and
the extent of public opposition to the landfill.  The councilman and
state senator petitioned the County Executive not to bring Allied's
special zoning exception request to the council in hopes of frustrating
Allied*s siting attempts.  The senator also petitioned the governor's
office to oppose Allied's siting attempt. In January, 1977, the
lieutenant governor issued a response noting that "the governor thought
the entire undertaking should be abandoned".  By that time, it was clear
to  the director of MES that although Allied's proposal was  technically
sound, the facility would never get off the ground unless the adjoining
neighborhoods withdrew their objections.

Also, in January, the Greater Rosedale Community Council invited a
representative from MES to speak about the landfill at a monthly
meeting.  The president of the Council made it known that although the
organization was firmly opposed to the facility, it was willing to hear
all sides.  The MES representative's presentation was received better
than Allied's presentation at the informational meeting, but was still
incapable of  swaying the public's position.

A month later the County Zoning Commission denied Allied's  zoning
petition on the basis of what it called  "a contradiction of terms"
arising from  the stated water imperviousness of  the clay and  the need
for the soil  to pass a percolation test  for establishing sewers.   (Since
more  than four persons would  be employed  at the  site, Allied was obliged
to  install sewer lines.)   The denial of  the zoning request  was not
unexpected.   Indeed, Allied's attorneys,  expecting such a decision,
deliberately  withheld expert  testimony and special witnesses until the
appeals process  so  that all  testimony  would be  recorded and so  that
Allied could  protect its position from premature "attack.  The Greater
                                     182

-------
Rpsedale Community Council established a "Landfill Defense Fund" to
fight. Allied in.its zoning appeals.  The state senator became attorney
for the group and the county directed the people's counsel to further
assist the Rosedale group.

The area's state senator introduced legislation in February that would
have prohibited the development of the Allied landfill.  That
legislation called for no hazardous waste landfills to be sited within
1,500 feet of a residence in Baltimore County.  Within,two months that
legislation had passed both houses and was sent to the governor for his
signature.   .'-......                                            ,

Allied appealed the zoning commission's decision and again tried to
assuage public concerns.  In March, Allied sponsored a second public
information meeting regarding its zoning appeal.  Stiff local opposition
arose at this time.  Neighboring residents testified that they witnessed
water soaking into the soil at the site thereby challenging Allied's
claim that the soil is impervious.  A local pastor spoke about declining
property values due to the landfill and lack of community control over
the land.  A local hospital spokesman voiced concern over possible
health effects from chromium ore dust in hauling.  The County Planning
Board and the Industrial Development Commission also took stands against
Allied's proposal for fear of contamination of nearby streams.

In April, Allied requested a special audience with the governor
regarding approval of the senator's bill restricting hazardous waste
management facilities near residences in Baltimore County.  Calling to
the governor's attention the employment and income effects that could
result from closing the Baltimore plant, Allied urged the governor to
veto the bill.  The governor apparently reconsidered his position and
did indeed veto the bill.  The county executive was also opposed to the
bill because of its possible effects on the county solid waste plan.
The executive viewed the bill as a tool to phase out all landfills in
the county.

Also in April Allied applied to WRA for a facility permit.  A complete
plan for the development and operation of the facility was submitted
with this application.  At Allied's request, WRA considered this
application a continuation of the discharge permit application submitted
in July, 1975.

The zoning appeals hearing began in September, 1977.  At the. first ...
hearing the local communities' challenged the validity oif Aliped's
technical reports.  Allied's engineers again restated proposed measures
to assure protection of the groundwater.  Allied also announced plans to
fill eight acres in the northwest corner of the site during the first
three to five years of operation.  This area then would be developed as
a park for community use.  Allied reminded the audience that its
Baltimore-plant employed 350 people and that no suitable alternative to
disposal by landfill had been found for chrome ore waste.   The company's
presentation did little to reduce public opposition.
                               183

-------
The  pattern established  in the  first  appeals hearing  continued  through
four subsequent hearings.   Each time, the community (through the Greater
Rosedale Community  Council, individual  spokesmen  or elected officials)
continued to challenge Allied on the  basis of potentially harmful
community effects.   The  Greater Rosedale Community Council hired its own
consultants who claimed  that although the clay at Rossville might prove
adequate to  prevent leachate, the  site  was actually spotted with sand
lenses which permit seepage through the clay.  In response, Allied hired
another consultant—this time from the  local university—who again
supported their engineer's  report  favoring soil characteristics at the
Rossville site.  Another real estate  broker was brought  in to refute
claims that local property values  would decline.  Allied also tried to
appease the  public  by giving a  greater  role to public agencies  in
managing the landfill.   At  the  third  appeals hearing, Allied announced
that MES would operate the landfill for five years after its closure.
After that time, WRA would  assume  control over the facility thereby
placing the  site under public control.

All  of Allied1s retorts  did little to sway public opinion.  In March,
1978 by the end of  the fifth appeals  hearing, the Zoning Commission was
no closer to approving the site.   The County Planning Board and Board of
Health began bringing in reports of visible chromium  leachate from the
Hawkins Point site  on the Chesapeake  Bay.  This aroused  greater public
ire  due to concern  over  regenerating  the bay.

The  same month that the  appeals hearings ended, MPA announced, as a
result of compromise legislation,  that  it would allow Allied to dispose
of its chrome ore waste  at  Hawkins Point until July,  1979.  Local papers
reported that the MPA, WRA, and the area's state  senator had reached
this compromise so  that  disposal would  not become a major constraint for
Allied's processing plant.

•The  site visit occurred  in January, 1979; at that time a decision on
Allied's zoning appeal was  expected in  March, 1979.   Although Allied
continued to petition the appeals  boards, a reversal  of  the Zoning
Commission's original decision  was considered highly  unlikely.  Allied
has  not produced conclusive data to refute the opponents' technical
criticisms nor has  it offered appropriate incentives  to win the support
of the public.  Furthermore, local opposition has been too deeply rooted
in emotional issues  at this time to be  appealed to through reason.
Although it has supported Allied's proposed landfill  the state has not
been in a position  to reverse the  local ruling since  the state does not
have authority to preempt local zoning  decisions.  Allied and MES will
continue the appeal to settle a number  of lingering legal issues (e.g. ,
does an industrial  waste landfill  have  to be consistent with the county
solid waste master  plan)  and to pave  the way for other landfill sites in
Maryland.  Allied and MES have  learned  valuable lessons  through this
experience.

Compatibility of the proposed landfill  with the County solid waste
master plan was also still  in dispute.  Allied claimed that the facility
                                184

-------
should be approved since the county plan did not adequately address
industrial waste disposal — a critical problem in the greater Baltimore
area.  The WRA notified Allied that permitting procedures would be sus-
pended until the solid waste master plan question was settled.  The
question was moot however, until zoning was approved.

In the meantime, Allied continued to use a private landfill site.  Dis-
posal costs have tripled over the past year and the state estimated only
three to five years of remaining disposal capacity in Baltimore County.
MES, with the support of WRA, was still working with Allied to find a
suitable landfill site.  Since a negative or at least too tardy decision
was expected on the Rossville zoning decision, Allied was proceeding
with another survey of alternate landfill locations.  Allied will pre-
sent its development plans to selected candidate communities after MES
conducts a technical review of the sites and makes its own recom-
mendations regarding preferred suitability.  Allied will then make a
final site decision.  Allied will solicit the public's assistance in de-
veloping site selection criteria and in making the final choice.  The
legislature is expected to be keenly interested in the activities, es-
pecially since highly developed areas will be considered.  Ownership and
operation arrangements had not been decided.

In April, 1979, the appeals board granted Allied the needed special ex-
emption.  This decision was appealed to the circuit court by the
people's counsel.  As of late May, 1979, the circuit court was expected
to receive the complete files of the appeals board.  When that was ac-
complished the court would begin to decide on hearing dates.
IV.
CHRONOLOGY OF EVENTS
1974 — MPA informs Allied that disposal at Dundalk must stop in Janu-
        ary, 1975.  Allied switches to private landfill until MPA  ,
        provides  for disposal at Hawkins Point.  Allied begins concerted
        effort for disposal site.

June, 1975 — Allied and WRA agree on rejecting non-landfilling options
              for chrome waste.  Allied reaches purchase agreement on
              Rossville site.

July, 1975 —• Allied seeks state discharge permit from WRA which refers
              Allied to MES.

September, 1976 --After a series of meetings, MES formally agrees to
                   assist Allied.

November, 1976 — Allied and MES attend local informational meeting.

January,  1977 —MES attends Greater Rosedale Community Council board
                  meeting.  Lieutenant governor indicates that he and
                  governor oppose facility.
                                    185

-------
February, 1977 — County zoning commission rejects zoning change; Allied
                  appeals to county board of appeals.  Area's state
                  senator introduces anti-facility legislation.

March, 1977 — Allied attends second informational meeting.

April, 1977 — Allied applies for state facility and apppeals to
               governor for meeting prior to his action on senator's
               bill.

May, 1977 — Governor vetoes senator's bill.

September, 1977 — Hearings before county board of appeals begin.

March, 1978 — Hearings end.  MPA agrees to Allied's disposal at Hawkins
               Point until July, 1979.

April, 1979 — County board of appeals granted special exemption.

May, 1979 — People's counsel appeals decision to circuit court.

V.     ATTEMPTS TO SECURE SUPPORT

The following.major actions were taken by Allied and/or MES.

       6     The November, 1976 informational meeting arranged by the
             area's state senator.

       o     The MES presentation to the board of the Greater Rosedale
             Community Council.

       o     The March, 1977 informational meeting sponsored by Allied.

       o     Allied's appeal to the governor.

       o     Amenities and technical data offered by Allied during the
             zoning appeals process.
VI.
SUMMARY EVALUATION
The various actions  taken by  Allied  and MES have  failed  to  reduce  public
opposition.   Indeed,  that opposition has escalated  during the
controversy and  for  large numbers  of area  residents and  officials
appears  to have  become deep-rooted and unalterable.

Allied's piecemeal attempts to  respond to  public  concerns put the
company  in a  suspicious  light.   For  example, no mention  was made of
covering trucks  with tarp to  prevent spreading chrome  ore dust until the
local  opposition raised  the issue.   Similarly, truck scheduling at the
site was not  adjusted to hours  agreeable to local residents until
neighboring residents complained of  anticipated traffic.congestion,
                                186

-------
noise and general nuisance.  This approach made Allied appear
unresponsive to community concerns.  While MES1 presentation to the
Greater Rosedale Community Council was considered to be better (i.e.,
more informative), that agency was no more successful in changing local
views than Allied.                               :

Allied1s legal strategy on presentation of data during the zoning
approval process seems to have backfired.  Allied's legal counsel
advised the company to withhold detailed presentations until the hearing
process when proceedings would be recorded.  Unfortunately, this put
Allied in a defensive position.  The company did not anticipate, a
well-informed public armed with specific technical criticisms of the
site.

This inability to sway opinions may be explained by the fact that in the
final analysis, Allied's general approach demonstrated overall
insensitivity to the community's self-image and priorities.  For'
example, the community appeared to be developing into a bedroom
community.  As such, jobs in the community itself may not have been as
important as would seem at first glance.  Development would be
particularly undesirable if new jobs brought in unsightly or dangerous;
industries.  The community was trying to change its self-image away from
the "dumping grounds of Baltimore County".  Even though Allied promised
to restore the brickyard to original grades, the intermediate steps to
fill the land (i.e., trucking  in hazardous material) did not complement
the community's improvement plans.  Nor did the promise of a park since
new homes in the area have adequate land for backyards and since clean
fill could be brought in to fill the clay pits at less risk.  Allied's
overall inability to determine community priorities made it impossible
for them to determine local motivations and appropriately corresponding
incentives.

Finally, Allied failed  to  fully capitalize on  its support from the
state.  A more active role by  the Water Resources Administration may
have helped allay public fears about groundwater contamination and
damage liability after  site closure.  As an impartial regulatory agency,
WRA could have helped settled  conflicting  technical reports about site
suitability.

Allied was not totally  without success.  It would appear that the
company's appeal  to  the governor contributed to a complete reversal  of
the governor's position on the landfill.   Gaining the support of the
governor, however, had  no  discernible impact on local sentiment.

The unexpected decision by the appeals board to grant Allied  the special
exemption has given  the siting attempt new life.  Regardless of the
outcome of  the appeal to  the courts, the overwhelming evidence suggested
that opposition will not be overcome.  Should  the landfill be developed,
it will be  developed without community support or approval.   The
                              187

-------
 Rossville case illustrates the strength and stamina of  public opposition
 once  it  has  formed.   Community groups  and their leaders  have  been able
 to  mobilize  a sizeable number of political,  financial, and technical
 resource when local  interests have  been threatened.   While the technical
 issues raised by citizens  can be said  to be merely tactics to support
 emotionally-based concerns,  they cannot be easily  resolved or refuted.

 The protracted opposition  has centered around  a number of  major issues
 that  are summarized  below.

 Allied's credibility — National publicity regarding Kepone poisoning at
 Hopewell,  Virginia had surfaced shortly before Allied's  first local
 meeting  in Rossville.   Fear  of a similar disaster  in Rossville was
 therefore  a  primary  public concern.  Despite Allied's direct  statements
 to  the contrary,  the  public suspected Allied  might  secretly  haul in
 Kepone from  Virginia.   Furthermore,  even if  Kepone was not imported,
 chromium ore still bore the  label "hazardous waste."  As such,  chrome
 wastes were  assumed  to have  the same possible  effects on the  public as
 Kepone no  matter  how Allied  proposed to handle the waste.

 Site  suitability  —  Allied engineers seemed  unable to refute
 contradicting  technical reports prepared by  the opposition's  engineers.
 The latter reports referred  to sand lenses throughout the  site's  clay
 formation  as well  as  stress  patterns which might disrupt the  sealed
 encapsulation  effect.   The reports  therefore supplied ample fuel  for  the
 opposition's position  and grounds for  denying  the  zoning permit.   The
 basic fear has  been  that groundwater would be  contaminated.

 Operational  procedures  and provisions— Traffic in  and out of  the site
has been seen not  only as a  nuisance but  also  a safety hazard because of
 traffic  congestion and the potential for spilling  chrome ore  waters.
 Procedures for  preventing surface water  contamination for  runoff  were
 seen  as  unreliable.  Allied  was able to  respond some  of these concerns.

Post-closure provisions — The  facility  was  thought  to present  long-term
problems which  would render  the  site unsuitable for industrial
development.  This conflicted with an  expressed commmunity goal of
developing employment  opportunities.

Community  image — The landf ij.1  was seen  as  one of a  series of
objectionable facilities being  sited in  an area with more  than  its fair
share of such projects.  Residents did not want to see the  area further
degraded to  suit Allied's disposal needs.  Moreover,  the community has
recently experienced more residential development, thus making the
landfill increasingly  in non-conforinance  with  area development  trends;
                                 188

-------
VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

The following contributed to and sustained opposition.

       o     A local history of political organization and activism
             particularly with regard to projects perceived as unac-
             ceptable.

       o     Allied1s severely tarnished environmental reputation fol-
             lowing the Kepone controversy.

       o     Allied's first notification to local leaders of the
             proposed facility after the company was committed to, the   ;
             site.

       o     The inability of Allied or MES to respond effectively to an
             exhaustive number of questions and concerns raised at the
             informational meetings.

VIII.  RETROSPECTIVE VIEWS

Local leaders and officials were pleased with the course of events up
through the time of the site visit.  They felt the community and its
political representatives had done an effective job of raising concerns
and organizing to fight the landfill.  Local leaders expressed a desire
for continued local control over siting in the future.

Allied and.MES have learned valuable lessons through this experience.
The company still needs a disposal area for its chrome ore wastes. ,In
developing an alternate site, Allied planned to consult with local com-
mittees earlier in the process to iron out problems before the plans
reach the public hearing stage.  Allied advocated more state control in
siting hazardous waste facilities so as to introduce a regional perspec-
tive in the regulatory process.  In the absence of this change, however,
Allied plans to work closely with MES and WRA in selecting and de-   ,
veloping a new site.               ,

-------
                           STATE OF MINNESOTA
I.
INTRODUCTION
In 1974 EPA requested proposals for the development of a chemical waste
landfill as a demonstration of the best available technology for land
disposal of hazardous wastes.  The grant was awarded to the Minnesota
Pollution Control Agency (MPCA) in 1975, but the facility was never
sited, and the grant was terminated by mutual agreement in 1978.

The proposed facility never received the support of the public, local
officials or industry.  This was primarily due to the press coverage the
project received before any of these groups had been involved in the
siting process, and before the public information program had begun.

Subsequent attempts to secure the support of these groups were
unsuccessful, largely because the agencies involved with the project and
the siting process itself had little credibility after the initial
announcement.
II.
HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE
All solid waste disposal sites in Minnesota are required to have a Solid
Waste Disposal Permit which is issued by the MPCA.  Initially, it is
recommended that the prospective permittee discuss the scope and nature
of the project with MPCA staff.  Next a preliminary application must be
submitted to the MPCA.  This must include data on the proposed site,
facility design and engineering, access, clientele, type of.wastes, and
some estimate of the environmental impacts of site development and
operation.  The MPCA then responds to the preliminary application and
suggests changes which are incorporated into the final application.  In
addition to the MPCA, the final application must be approved by the
Metropolitan Council if the proposed facility is in the seven-county
Minneapolis-St. Paul region, and the Minnesota Environmental Quality
Board must review it to determine whether an Environmental Impact
Statement is required.  If the application is approved by all parties,
the MPCA must give public notice, and can hold a public hearing at its
discretion if one is requested.  A permit authorizes the development and
operation of a facility for the life of the site,  given that monitoring
and reporting requirements are met.   Once the site has been developed,  a
statement is required from a registered professional engineer that the
site has been developed according to the permit.

No other state agencies require permits for hazardous waste management
facilities, but a number of counties and towns in Minnesota do so, es-
pecially those in the Minneapolis-St. Paul metropolitan area.   Within
the seven-county metropolitan area,  the MWCC can preempt city and county
zoning in siting hazardous waste facilities.   Elsewhere in the state,
counties can preempt local zoning for this purpose.
                                  190

-------
In 1974, the Office of Solid Waste of U.S. EPA requested proposals to
develop a demonstration chemical waste landfill.  The request was
limited to state, regional and local authorities.  Of the 24 initial re-
sponses, eight were selected to present detailed final proposals.  The
grant was ultimately awarded to the Minnesota Pollution Control Agency.
The bases for this award were:  the State of Minnesota had in existence
laws governing the storage, transportation and disposal of hazardous  •
industrial wastes; the Minneapplis-St. Paul area had a good cross-
section of industry and thus of industrial wastes; and the grantee had
available the required 25 percent matching funds.

The objectives of U.S. EPA in sponsoring this demonstration project, as
noted in the "Chemical Waste Landfill Facility Plan" (Henningsoh, Durham
and Richardson), included the demonstration and evaluation of siting
criteria and the siting process; of site development; and of site oper-
ation, including technical procedures, economics, and other impacts.  It
was intended that the site be operative before U.S. EPA would begin de-
veloping its own regulations covering the storage, transportation and
disposal of hazardous industrial wastes.  The facility was to provide
information to be used by EPA in the development of programs for the Re-
source Conservation and Recovery Act.                              ,  :

Certain constraints were put on the project.  These included that the
site should be a chemical waste landfill, that it be in a metropolitan
area, and that it would require technical upgrading to meet standards
(i.e., that the site not necessarily be geologically ideal).

The grant was awarded, in June, 1975.  The Minnesota Pollution Control  •
Agency  (MPCA) was the grantee.  However,  since  the MPCA is a regulatory
agency, it was obligated to subcontract with another (operating) public
body or agency to do  the work.  Initially,  this  public body was  to be
Hennepin County, one of the several counties which make up the
Minneapolis-St. Paul metropolitan  area.   However, about this time the
Minnesota state legislature transferred the power to site hazardous
waste landfills  in  the metropolitan area  from county government  to  the  •
Metropolitan Waste  Control.Commission (MWCC).   The MWCC then became the
subcontractor  for  the MPCA for  this grant,  and  agreed  to  acquire and  be
responsible for the operation of the  proposed facility.  -The MWCC in
turn contracted with  a local  consulting engineering firm  to develop the
criteria for siting the landfill and  to select  several sites.  The MPCA
remained, responsible  for  project administration and  the public .  ••
information program.                                            •

The MPCA was interested in developing regulatory expertise.  However,  it
was largely concerned with state needs.   The MWCC wanted  a hazardous
waste landfill  that would  serve as a  disposal site  for wastes which
because of  industrial pretreatment standards could  no  longer be  disposed
of in  sewers.   They were  primarily interested in the, capability  of  the
facility  to meet the  needs* of  the  metropolitan  area.   .
                                   191

-------
 The first  siting attempt  began in June,  1975.   The  siting  procedure was
 the same in all  three  attempts.1   Site criteria and the  data base were
 developed  first.   Then, a number  of  "search areas"  were  identified in
 the region.   These are areas  with conditions generally favorable for the
 siting  of  hazardous waste landfills.  The Minnesota Land Management
 Information System (MLMIS), a computerized  land use data base which
 contains information on each  40 acres of land  in the Minneapolis-St.
 Paul metropolitan area, was used  in  this part  of the analysis.

 Next, the  search areas were subject  to an in-depth  analysis and
 candidate  sites  were selected.  The  number  of  candidate  sites was then
 narrowed down to  three or four  on the basis  of  site visits.  The final
 site was selected based on further analysis, in particular, of site
 geology and  access.

 Site selection criteria used  to develop search  areas in  the first siting
 attempt were limited to information  available  for the MLMIS system.
 These included:  1)  land use,  2) hydrology,  3)  topography, and 4)
 geology.

 Based on these criteria,  45 search areas were  identified in the region.
 Twelve candidate  sites were identified in these  search areas by applying
 the  following  additional  criteria:   1) accessibility, 2) land
 availability,  3)  availability of  utilities,  4) air  quality and
 climatology  (wind direction and area dispersion  characteristics),
 5) natural ecosystems, and 6) site-specific  topography, soils, geology,
 topography and land  use.  Four of  these sites were  located in each of
 Scott and Carver  Counties, two in Dakota County, and one in each of
 Hennepin and Washington Counties,  for a total of 12.

Each of the  twelve candidate sites was visited, and additional data
gathered.   Four sites were selected for further investigation.   All were
located in agricultural areas.  These sites were:

       o     Bongards
             Section 29,  Benton Township
             Carver County

       o     Dahlgren
             Section 17,  Dahlgren  Township
             Carver County
   While no locally acceptable sites were found during the
   demonstration project,  eight individual sites were proposed at one
   time or another.   In all,  there were three attempts to select  a site
   and two sets of selection criteria.   The second set of criteria was
   used with some modification for the  third as well as the  second
   attempt.
                                    192

-------
       o     Button Lake
             Section 26, Sand Creek Township
             Scott County

       o     Castle Rock
             Sections 23 and 24,  Eureka Township
             Sections 18 and 19,  Castle Rock  Townships
             Dakota County

On December 16, 1976, thefour candidate sites selected for further
on-site analysis were presented by the engineering firm to a joint staff
meeting of the MWCC and the MPCA.  The meeting was open to the public
and there were members of the local press in attendance.   The next day,
December 17, local newspapers provided residents of the metropolitan
area with their first information of any kind about the demonstration
project and the siting process.  Local reaction to the project and the
process was uniformly negative, and this was especially true in areas in
the vicinity of the proposed sites.  Local residents and officials were
outraged that they had not been contacted prior to the release of this
information to the press and that such a dangerous facility should be
located in their vicinity.

The public participation program for the siting process did not begin
until late 1976.  A public relations consultant had been hired by the
MPCA in early December, 1976.  However, the consultant withdrew from the
project shortly after the unexpected press release.  A slide show and
brochure explaining Minnesota's hazardous wastes program and the siting
process were developed  by MPCA, but these were not released until
September, 1977.

In January,  1977, in reaction  to severe criticism in the press and from
local officials,  the MPCA held three public meetings in the vicinity of
the four  candidate  sites.  These meetings served only to allow local
residents  to express their opposition  to the  proposed sites, and did not
succeed in ameliorating public opposition.  In  addition, the Carver
County  Board passed a resolution opposing siting a chemical waste
landifill on prime  farmland  and  criticizing the siting process, and the
Scott County Board  passed a  resolution opposing siting the landfill in
their county.   Furthermore,  the Metropolitan  Council1 and  the
Metropolitan Inter-County Council2  demanded greater involvement in the
project and  in the  reevaluation  of  the site selection process.
    The Metropolitan Council is  the  regional  planning agency  for the
    Minneapolis-St.  Paul metropolitan area.

    The Metropolitan Inter-County Council is  comprised  of  the
    commissioners of the seven counties  which make up the  Minneapolis-St.
    Paul metropolitan area.
                                 .193

-------
 In early February, the MWCC announced that it had decided to postpone •
 indefinitely its planned inspections of the four candidate-sites until
 the counties and the Metropolitan Council were able to review the site
 selection process and recommend new criteria.   Officials of the. three
 counties concerned had told the MWCC that attempts to gain access to the
 sites would be met by landowner resistance.     .   .          -

 The main objections to the initial criteria were:   1) they .did not take
 cognizance of Metropolitan Council development policies; 2) they did-not
 necessarily take into account local land use plans;  and 3) not, enough
 emphasis was placed upon siting the facility away from commercial
 agricultural areas.*  There was also strong objection to the lack of
 public and local official input to the siting  process.   Development of •
 agricultural land is a particularly strong political issue in rural  -
 areas of Minnesota, especially development which is  perceived as .being
 largely for the benefit of urban residents. ,

 A second site selection process was developed  to take into account
 issues raised in previous public hearings and  the  development policies
 of the Metropolitan Council.   In response to an MWCC request,  the staff
 of the Metropolitan Council prepared a memorandum  outlining  a site
 selection procedure based on their policies.

 During March and April,  1977,  public meetings  were held  in each  of  the
 seven counties to gather local public input on siting process  and
 criteria.   Using these suggestions,  a new set  of criteria  was  developed
 with which to define the "search areas".   These criteria defined areas
 in which the hazardous  wastes  landfill could, not be  located, as
 follows:   1) floodplain,  2)  wetlands,  3)  water courses and water bodies,
 4)  groundwater  recharge  areas,  5)  erodible  slopes, 6) commercial
 agricultural region,  7)  land with soil suitable for  cropland,
 8)  regional  parks  and  open space (existing  and proposed),  9) existing  ,
 and authorized  state lands,  and 10)  1975  metropolitan highway  system.  . .

 The main difference between  the two  sets  of  selection criteria was  the
 extent of  their  reliance  on  existing  state  and  regional  regulations.  .In
 the absence  of  any  state  hazardous  waste  siting  regulations, the  first
 set  of criteria  was  based solely on  technological and physical
 considerations.   The  second  set of  criteria, developed in  response  to
 the critical public  and official reaction which greeted  sites selected
 according  to  the  first criteria, took  cognizance of state  and regional
regulations and  policies.  These regulations and,policies  included in
 particular regional  and local  land use and development plans, rather
than hazardous waste regulations per se.
   The Metropolitan Council's Development Policies are designed to,
   among other things, protect the region's rural areas from development
   pressures.  The Commercial Agricultural Region is that part of the
   Metropolitan Region where development is discouraged.
                                   194

-------
Potential.search areas were identified based on these criteria.
However, when local planning constraints were also taken into account,
the entire metropolitan area was found to be unsuitable for landfill
development.

The criteria were then reviewed to determine if any criteria could be
eliminated.  Since the groundwater recharge map was not considered
accurate, this constraint was removed as a search area criterion, and
groundwater recharge applicability was instead evaluated on a site-by-
site basis.

In the meantime, at a joint meeting held on February 25, 1977, MWCC
board members had blamed the MPCA for the premature announcement of the
selected sites.  The MPCA had in return faulted the MWCC for not using
Metropolitan Council site selection procedures and criteria.  Mutual
recriminations continued throughout the life of the project.

In early May, 1977, the MPCA staff asked its board to approve transfer
of total project responsibility to the MWCC.  However, the MWCC board
felt strongly that the MPCA should stay on the project.  The MPCA board
voted to continue administering the project but to hand over public
relations responsibilities to the MWCC.  At the same time, a joint ad
hoc committee was set up, comprised of three members from each of the
boards of the MPCA, MWCC and Metropolitan Council.  This committee was
to mediate between the three agencies and to exercise overall control
over the landfill project..

The MWCC assumed responsibility for public education and involvement
programs in August, 1977.  The demonstration project was publicized with
a brochure previously developed by the MPCA, in articles in the MWCC
newsletter and in periodic informational letters to elected arid
administrative officials and other interested persons.  A talk and slide
show explaining the hazardous waste problem was given throughout the
region during September and October, 1977.

During the summer, EPA had announced that it was considering withdrawing
its support from the project because of the delays in the site selection
process.  In September, however, EPA announced that it had decided to
continue supporting the landfill project.  In agreeing to continue the
funding, U.S. EPA required the MPCA and MWCC to follow a firm timetable
—three or more sites were to be identified by December 15, 1977; the
final site proposed by April, 1978; and operations begun by October,
1978.

Based on the revised set of criteria, six new search areas were
identified by early October, 1977.  Two of these, the Chanhassen/Eden, ,
Prairie and Pine Bend/Cottage Grove search areas, were supposedly
recommended because an industrially oriented area would constitute a
more compatible land use rather than a rural, less populated area.
                                 195

-------
However, the major  factor  in  their  selection was  that  they  were  the  only
areas outside the Commercial  Agricultural  Region.!   Public  and media
reaction to this attempt to find  a  site was  no  less  favorable than to
the previous one.   For example, a newspaper  article  about the selection
of the six search areas was headlined  "Landfill Site for Poisons
Sought."  Major factors underlying  the opposition included  the
perception by rural parts  of  the  metropolitan area that their land was
being used as a dumping ground for  wastes  generated  in urban areas;  the
belief that since this was a  "federal demonatration  project".it would be
experimental and would have to accept wastes .from all, over :the country;
and the fact that siting criteria had been changed midway through the
project.  Other issues which  were raised included the lack  of provisions
for compensation for loss  of  tax  revenues  and for services  demanded  by
the facility; and the fact that the state  had only a general idea of, the
quantities and types of wastes produced in the  region.

On November 10, 1977 it was announced that the  search areas had been
narrowed down to two—Chanhassen/Eden Prairie and Pine Bend/Cottage
Grove, which had been recommended in the previous report.   Three public
hearings were held  in these areas.  Again, reaction  from the public  and
local officials was uniformly unfavorable.   They  continued  to express
the same concerns.  At the Cottage  Grove meeting  on  November 15,
approximately 1,900 people came to  voice opposition  to any  site in their
vicinity.  The strong public  reaction again  prompted officials to
consider further delay in  siting  the landfill.  The  ad hoc  committee
decided to seek the advice of the state legislature. . It w,as recognized
that this further delay might have  prompted  U.S.  EPA to pull,out of  the
project.                                     ,     .     - .

A meeting of the ad hoc committee with a committee of state legislators,
held on December 21, succeeded in gaining  the support of urban
legislators—whose constituents included hazardous waste generators—but
not of rural legislators in whose districts  the facility might be sited.
The legislative committee  as a whole advised the  ad hoc committee to
continue the search for a  site.   The ad hoc  committee decided to delay
the choice of the final group of  sites past  the December 15 deadline.
The final four candidate sites were announced on  January 19, 1978.   The-
se were located in the towns of Rosemount, Roseport, Cottage Grove,  and
Eden Prairie.   On February 13, 1978 the ad hoc committee, members of the
staffs of MPCA,  MWCC and the Metropolitan  Council, consultants, members
of the news media and other interested persons;were  taken on a bus tour
of these sites.   They were met by protesters at each site.
   The Metropolitan Council's Development Policies are designed to,
   among other things, protect the region's rural areas from development
   pressures.  The Commercial Agricultural Region is that part of the
   Metropolitan Region where development is discouraged.  Use of this
   criterion forced the proposed site to be less than geologically
   optimal.  Preferred geological areas were all located in the
   Commercial Agricultural Region.
                                 196

-------
Public meetings were held in each town in late February and early March.
Public reaction was again negative, based on the same concerns as be-
fore.  At the Rosemount meeting, the Director of the Minnesota Geologi-
cal Survey stated that none of the proposed sites were geologically
suitable. The 3M company, which owned the land on which the proposed
Cottage Grove site would have been located, threatened to take legal ac-
tion to, prevent the siting if necessary.

The Metropolitan Council decided' on March 10, 1978 that all four sites
were inadequate, and .that the search for a landfill site should not re- •
sume until the state adopted regulations for hazardous waste management.
Responses cited by the Council in announcing their decision included the
inappropriate geological characteristics of the sites, the proximity of
all four sites to national parks or wildlife refuges, and the likelihood
that urban growth would reach all four in 20 years.  The ad hoc com-
mittee, on siting the landfill agreed to abandon the search on March 13,
and on March 28, the staff of the MPCA recommended that the agency ter-
minate the U.S. EPA grant.  The U.S. EPA concurred with this action.  A
final report, Chemical Waste Landfill Facility Plan, which describes -in
detail the siting process and the proposed facility, was prepared by the
consulting engineers and issued in September, 1978.
III.
BACKGROUND INFORMATION
No  single  site was ever decided upon during this project.  This section-
therefore  briefly describes the four final candidate sites that were
most  seriously proposed, and  the proposed facility.  Although no
facility was constructed during the demonstration project, the U.S. EPA
grant called for a hazardous  waste landfill which was to be designed to
handle the following wastes:
        o
        o
        o
        o
        o
      Cyanide Wastes            .
      Acid Wastes
      Alkaline Wastes
      Heavy Metal Wastes
      Miscellaneous and Unidentified*
13,600 gal/month
26,400 gal/month
47,600 gal/month
31,700 gal/month
85,000 gal/month
 The five-year  life  of  the  landfill was  stipulated in the grant.  Other
 stipulations of  the grant  were that the facility not compete with
 existing chemical waste management operations and that the waste stream
 be pretested before landfilling.

 The area of the  proposed site was to be approximately 200 acres.  This
 would have included a  landfill area of  90  acres and a 73-acre, 300-foot
 wide buffer zone.  The remaining  acreage was  to have been used for
 processing facilities  and  landfarming of wastes.  There would be three
    Mostly paint and other sludges.
                                    19?

-------
buildings on the site—for  the laboratory and administration, for
receiving and storage, and  for pretreatment processing.  Proposed
treatment processes included the following: (1) equalization,
(2) neutralization, (3) ozone/ultraviolet process, (4) chemical
precipitation and clarification, (5) sulfide process.  Provision would
also have been made for the treatment of wastes for these processes.

A landfill capacity of 30 acre-feet was estimated to be sufficient for
the five-year period of the demonstration grant.  The landfill would be
underlain by a double liner and a leachate collection system.  The
capital cost of the facility (1975) was estimated at $3.75 million; the
annual operating, maintenance and capital cost was estimated at $0.8
million.  The facility would have been operated by the Metropolitan
Waste Control Commission (MWCC).                                     :

Closure and long-term care  procedures were not specifically defined,
except that they would be in accordance with MPCA and/or EPA
regulations.  Currently, proposed MPCA regulations would require that as
part of the permit procedure the facility owner/operator must provide a
plan for closure and long-term care.  The latter is not necessary if the
state decides to assume liability.

A large number of sites were considered for the facility during the
siting attempt.  Before the siting attempt was abandoned a final group
of four sites had been proposed.  These are described in Table 1.

The Minneapolis-St. Paul Metropolitan Region is comprised of seven
counties—Anoka, Carver, Dakota, Hennepin, Ramsey, Scott and
Washington—and has an area of approximately 3000 square miles.  Nearly
45 per cent of the land is in agricultural use, another 20 percent
residential and commerical, and the remainder is open space, forest, or
water.  The population in 1976 was 1,993,245 and the 1980 population is
projected to be 2,031,400.  The region's industrial base is quite
diverse, such that the largest industry employs three percent of the
labor force.
IV.
CHRONOLOGY OF EVENTS
1974 — Office of Solid Waste, U.S. EPA, requests proposal to develop a
        demonstration chemical waste landfill.
                                               H
June, 1975 — Grant is awarded to MPCA, which subcontracts with MWCC to
              perform the work (with the exception of public relations).
              The MWCC in turn hires an engineering consulting firm to
              develop siting criteria and select three or four candidate
              sites.

December, 1976 — Public relations consultant hired by MPCA.
                                198

-------
                                Table 1

       LOCATION AND DESCRIPTION OF THE FINAL FOUR CANDIDATE SITES,


                             COTTAGE GROVE                 -   .' ,
Eastern portion of. Section.27,. T.27N, R.21W., north of Chic,ago,  -
Milwaukee,- St. Paul arid Pacific R.R., east of Chemolite Road, and south
of U.S. Highways 10'and 61, Washington County.                 -.

Pros — .     Highway access is good.
       .     The site is well buffered on three sides.   .  .
       .     The topography is good  for landfill development.
       .     Erosion potential is minimal.
             The site is adjacent to the 3M Chemolite plant and is zoned
             industrial.          ,                   .
       .     There are no homes on site or in the immediate,area.
             The depth to ground water is probably greater than, 50-,feet.

Cons - .     The area is underlaid by sand and gravel.
       .     The site is south of a  regional park.
             The land is classified as good agricultural land by Cottage
             Grove.                                         .  •     ,
       .     Pumping from the 3M Chemolite Plant may affect ground water
             movement.                                      .,--.--
       .     The southern ^half of the site is in the Mississippi River
             Corridor Critical Areas and has been designated a Rural
             Open Space District.
                              EDEN PRAIRIE
Southwest 1/4 of Section 28, T.116N., R. 22W., north of U.S. Highways 169
and 212, south and west of Flying Cloud Airport, Hennepin County
Pros -
Cons
Highway access is good.
Depth to ground water could be over 50 feet.
A 120 foot thick clay layer is located approximately 75
feet below the surface.
The area is not cultivated.      ,
The site is adjacent to the Flying Cloud Airport.
The site is well buffered.
The property was for sale.

Highway congestion could be a problem.
The site is just north of a National Wildlife Area.
The site is underlain by sand and gravel.
                                 199

-------
                          Table 1 (Continued)
                               ROSEMOUNT
Eastern portions of Section 19 and western portions of Section 20,
T.115N., R. 18.W., north of County Road 38 and southwest of Minnesota
Highway 55, Dakota County.

Pros - .     Highway acess is good.
             The site is adjacent to the Rosemount Treatment Plant.
       .     The topography is good for landfill development.
             The site is adjacent to the North Star Chemical Company and
             is partly zoned industrial.
       .     The site is not cultivated.
             The population density in the surroundings area is low.
             The property is for sale.

Cons - .     The site is underlain by sand and gravel.
             The ground water flow could be affected by irrigiation well
             pumpage found in the area.
             The site is one-half mile from Spring Lake Park.
       .     The area is planned by Rosemouunt as a "Neighborhood
             Center".
                                ROSEPORT
Western portion of Section 13 and Eastern portion of Section 14,
T.115N., R. 19.W., east of Rich Valley Blvd., west of the Chicago and
North Western R.R., and south of the Rosemount village boundary, Dakota
County.

Pros - .     The site is adjacent to Koch Refining.
             Depth to bedrock is nearly 200 feet.
             Depth to ground water is probably greater than 50 feet.
             The residential density is low. ,

Cons - .     The area is underlain by sand and gravel.
       .     The ground water system is probably the most complex of
             the four sites.
             The site would be visible to local residents.
             Three pipelines cross .the site.
       .     The site is zoned agricultural.
       .     There is one house on the site.
Source:  Henningson, Durham and Richardson, Chemical Waste Landfill
         Facility Plan, v.7, p. 433-434
                                200

-------
December 16, 1976 —Four candidate sites are presented to joint staff
                     meeting of MPCA and MWCC.  Press is in attendance.

December 17, 1976 — Newspapers provide region with first news of sit-
                     ing process.  Local reaction is uniformly negative.

January, 1977 — Three public meetings are held in the vicinity of the
                 four candidate sites.  These have no positive impact on
                 local reaction.

February, 1977 — MWCC announces it has decided to postpone indefinitely
                  its planned inspections of the four candidate sites
                  until the counties and the Metropolitan Council review
                  the site selection process and recommend new criteria.

March/April, 1977 — Public meetings are held in each of the seven coun-
                     ties in the Metropolitan Region to gather local
                     public input to the siting process and criteria.

May, 1977 — MPCA board approves the transfer of public relations re-
             sponsibilities to the MWCC.  First site selection attempt
             based on new criteria fails to find any suitable areas in
             the Metropolitian Area.

June 1, 1977 — Ad Hoc Committee on the landifll, comprised of three
                members of the MPCA, MWCC and the Metropolitan Council,
                hold first meeting.  Committee is formed to alleviate
                management problems due to large number of parties
                involved in all decisions.  First decision is to relax
                groundwater constraint and try again to find a site.

September 7, 1977 — U.S.  EPA, which had considered withdrawing from the
                     project because of the delays, announces it has de-
                     cided to continue supporting it.  However, U.S. EPA
                     requires the MPCA and MWCC to follow a firm
                     timetable—three or more sites must be identified
                     by December 15; the final site proposed by April,
                     1978; and operations begun by October, 1978.

October 13, 1977 —Six new search areas are named.

November 10, 1977— Two search areas - Chanhaseen/Eden^Prairie and Pine
                     Bend/Cottage Grove - are selected for further
                     study.
November 14, 1977
through
November 17, 1977
Three public meetings are held in the two search
areas.  Public reaction is no less unfavorable
— 1,900 people show up at the meeting in Cottage
Grove to oppose any site in that area.
                                 201

-------
December 1, 1977 — Ad Hoc Committee votes to postpone selection of can-
                    didate sites past U.S. EPA deadline due to public
                    opposition.

December 12, 1977— Ad Hoc Committee meets with legislative committee
                     to seek advice; are told to proceed with landfill
                     siting.

January 19, 1978 — Final four candiate sites are announced.

February 13, 1978 — Ad Hoc Committee, staff of MPCA, MWCC and
                     Metropolitian Council, consultants, news media,
                     etc., tour four candidates sites, and are met by
                     protesters at each site.

February 20, 1978
through March 6, 1978 — Public meetings are held in the vicinity of
                         each site.  Public response is still very un-
                         favorable.  At the Rosemqunt meeting, the
                         Director of the Minnesota Geological Survey
                         states that none of the proposed sites are
                         geologically suitable.

March 10, 1978 — The Metropolitian Council decides that all four can-
                  didate sites are inadequate, and that the search for
                  sites should not resume until the state adopts plans
                  and regulations for hazardous waste management.

March 13, 1978 — The Ad Hoc Committee agrees to abandon the search for
                  the site.

March 28, 1978 — MPCA agrees to terminate U.S. EPA grant, and U.S. EPA
                  concurs.
V.
ATTEMPTS TO SECURE SUPPORT
Prior to the appearance of'newspaper accounts of the siting process and
the four candidate site (December 17, 1976), virtually no attempt had
been made to secure support for the proposed facility.  The subsequent
adverse response from elected officials and the public did result in ef-
forts to secure such support.  However, this task was made that much
more difficult by the initial adverse publicity.  Attempts to secure
support included:

       o     Public meetings

             —    to discuss the first four candidate sites;
             —    in each county in the metropolitan area to get public
                   input to the siting process and criteria;
                                2U2

-------
VI.
            to discuss the Chanhassen/Eden Prairie and Pine
            Bend/Cottage Grove search areas;
            to discuss the final four candidate sites

o     Meetings with county environmental officers and re-
      presentatives of the Metropolitan Inter-County Council to
      inform them of the second set of site selection criteria.

o     Efforts to involve industries which generate chemical waste
      in the process.                         ,

o     A talk and slide show on the hazardous waste problem in
      Minnesota and the siting process given thrpughout the
      metropolitan area.

o     A brochure explaining the problem and the siting process.

o     Articles in the MWCC newsletter, letters and press .releases
      on the siting process and its progress..

o     A meeting of the ad hoc committee with members of the state
      legislature succeeded in gaining the support of urban
      legislators, but not of their rural counterparts.

SUMMARY 'EVALUATION            '
It is clear that actions taken by the MPCA and MWCC to regain public
support after the initial publicity given the siting effort were not
always well-advised.  However, it is questionable whether any sequence
of actions after this publicity would have succeeded in regaining public
confidence in the siting attempt.

Public meetings seem to have had little if any impact on public at-
titudes toward the sites.  Efforts to involve county officials in the
development of new site selection critieria were successful, but it was
not possible, given the preceedlng events, to obtain their support for
the facility itself.  Local industries, mindful of the bad publicity the
siting attempt was receiving, were reluctant to become involved.  Urban
legislators whose constituents included industries which generate chemi-
cal wastes and in whose districts the facility was not likely to be
sited gave it their support.  However, rural legislators, who perceived
the facility as being primarily for the benefit of urban residents, and
in whose districts it might well have been sited, remained opposed to
the facility.

In the opinion of the agencies involved, however, there were other
problems inherent in this project.  One in particular was that U.S. EPA,
MPCA and MWCC each seem to have had different reasons for pursuring the
project and therefore different expectations regarding it.  The U.S.
                               203

-------
EPA's objective in funding this project was to demonstrate site selec-
tion, development and operating procedures; and to analyze economic and
other social/institutional aspects of hazardous waste management.   They
therefore imposed a number of constraints on the process which made the
siting somewhat more difficult.  The MPCA-like the EPA was inter-
ested in developing regulatory expertise.  However, they were largely
concerned with state, rather than national problems, and were interested
in meeting the statewide need for such a facility.  The MWCC wanted a
hazardous waste landfill so that they could enforce their pretreatment
regulations and clean up the sewers, which were then the primary means
of disposal of solid wastes.  Therefore, they were primarily interested
in the capability of the facility to meet the needs of the metropolitan
area.

Finally, the project was hampered because:

       o     there were no applicable state regulations;

       o     there was no state plan fpr hazardous wastes management;

       o     state and regional agencies had only a very general idea
             of quantities and types of wastes produced in the
             region.

Local officials and the public raised a number of other issues and con-
cerns during the siting process.  These included:

Need for the facility — In part because the public information program
began so late in the siting process, and in part because this was a
"federal demonstration" project, the public was never convinced of the
need for the facility.

Site suitability — Due to the constraints imposed first by U.S. EPA as
part of the grant conditions, and then by the Metropolitan Council, the
agencies concerned were never able to tell the public that they had
chosen the "best" site.

Development of agricultural land — Use of agricultural land for other
purposes has become a political issue in'Minnesota, particularly de-
velopment which is perceived as being largely for the benefit of urban
residents (e.g. high-voltage power lines).  Rural residents were opposed
not only to the facility itself, but also to the industrial development
which it might have attracted.

Facility operations and long-term maintenance — Concerns were
frequently expressed over the possibility of environmental pollution
either as a result of facility operations or after closure.
                                204

-------
VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Public opposition to this siting attempt seems to have developed as the
result of the .following:

       o     Underestimation, by all parties involved in the siting
—      ,      attempt, of public concern about chemical wastes and
             chemical waste disposal sites.             ...    . , / -
       o -

       o
The fact that this was a federal demonstration project.

The fact that the agencies involved were not expecting
public input until their process called for it; and that
the initial siting criteria did not recognize the
political nature of the siting process.

No information was provided to the public about the siting
process or proposed sites until the first four candidate
sites were "announced" in the local press.

Lack of accurate public information.  The information
"vacuum" led to press accounts which stressed local res-
idents' emotional response, and general acceptance by the
public of incorrect information.

Siting criteria were no longer perceived as objective when
it became apparent that political pressure could change
them, and thus the location of the facility.

MPCA/MWCC were not experienced in public relations.  When
public information efforts began, they educated the public
primarily about the negative aspect of hazardous wastes.

The public was never convinced even of the need for such a
facility, and this siting attempt was perceived as an ad
hoc effort.

U.S. EPA's need for a less than perfect site was never ful-
ly explained to the public.  The public expected the state
to come up with the best possible site.  The informed
public—a vocal minority—favored geologically suitable
sites over those which had to be engineered up to standard
and treatment/recovery over landfillirig.

Perception by rural parts of the metropolitan area that
their land was being used as a dumping ground for
urban-generated wastes.  Urban development of
agricultural land is a sensitive political issue in
Minnesota, and it was felt that the proposed facility would
attract industry.
                                   205

-------
       o     The fact that no provision was made for compensation of
             local residents for loss of tax revenues and for services
             demand (e.g. roads, fire protection) by the facility.

VIII.  RETROSPECTIVE VIEWS

In retrospect, officals of the 3M Company (on whose land was located one
of the four final sites) and the Metropolitan Council cautioned that it
would be short sighted to regard the project as an utter failure merely
because a site was not found.  They felt that one possible result of any
siting process, especially when geographical, time and other constraints
are imposed, should be that there is no suitable site.

A new, long-term effort to site a hazardous waste management facility is
currently underway in Minnesota.  In many ways this attempt reflects
what the agencies involved in the previous effort — particularly the
MPCA — feel are the lessons to be learned from the experience.  State
comments and these revised plans are discussed in the state program
report elsewhere in this study.
IX.
GENERAL COMMENTS
The agencies involved in the siting process and local officials stressed
the need for some sort of compensation for communities in which such
facilities are located and a provision of such compensation may be
included in the planned siting process.  Types of compensation proposed
included payments in lieu of taxes, direct payment for services demanded
(e.g., roads, fire protection), and fees per unit volume of waste
processed.

Without exception, the parties involved in the siting attempt indicated
that they think U.S. EPA should confine its involvement in the siting of
industrial hazardous waste management facilities to giving technical
assistance.  It was felt that the states, with or without private
industry, are capable of carrying out the other aspects of siting.  An
offical of the MPCA did suggest that the siting process would be made
easier if RCRA regulations distinquished different degrees of hazardous
waste.  In that case, he suggested, there might be a need for a few EPA-
managed regional sites for very hazardous waste (and perhaps also
"political wastes" such as PCBs).

Both the MPCA and the Metropolitan Council perceived a need for
national, regional (multi-state) and state planning before hazardous
waste management facilities are sited.  The EPA would be involved in
planning for national facility needs, but regional and state
coordination could be accomplished by the states themselves.
                                  206

-------
                         STARR INDUSTRIAL  SERVICES

                           STARR COUNTY, TEXAS
 I.
INTRODUCTION
 Starr  Industrial Services, a  private  disposal company, is currently
 seeking state approval  of a proposed  hazardous waste landfill in Starr
 County, southern Texas.  The  Texas Water Quality Board denied Starr,
 Industrial's initial permit request primarily on the.basis of local  >
 public opposition to the facility.  After the Texas District Court
 struck down public opposition as  insufficient grounds for permit denial,
 Starr  Industrial resubmitted  its,application.  Starr County has appealed
 the lower court's decision in an  effort to sustain the Board's original
 ruling against the site.  The Board's second decision will be issued,
 pending the appeals court decision, which is expected to be handed down
 in summer, 1979.

 Starr Industrial approached political and business leaders of the' com-
 munity before the permit hearing  took place. Company representatives ex-
 plained the nature of the facility, reasons why the area was selected
 and employment benefits that  would accrue to the community.  Although
 the community leaders were initially  open to the proposed hazardous .
 waste facility, unified opposition materialized just before and at the
 time of the hearing.  Opposition  focused on possible contamination of
 the Rio Grande River (the area's major water supply), explosions ,or
 fires at the landfill site and political issues such as further de-
 gradation of the area and discrimination against Mexican-Americans.
 Athough the state approved the site on technical criteria, local op-
 position was strong .enough to pressure denial of the initial permit re-
 quest.  Despite additional attempts by Starr Industrial to gain local
 support, opponents working through the county are still hoping to defeat
 the landfill in an appeal to  overturn a lower court ruling in favor of
 the permit.  Because the technical merits of the site are so strong and
 because Starr Industrial is determined to establish the facility,  it
 appears that the landfill indeed may be developed despite opposition.

 II.   : BACKGROUND INFORMATION                  ,      >  . '

 The site for the proposed landfill is a 40-acre parcel rented by Starr
 Industrial from a local rancher.  It is part of a larger 800-acre  parcel
which the company hopes to develop in stages.   Land surrounding the site
 is undeveloped and is used as grazing land.   The closest'town is El Sauz
 (population 85),  two miles to .the north;  Rio Grande City is eight  miles
 to the south.   Access to the site is by state highways.   The proposed
 site has ideal geological formations,  reportedly found nowhere else in
 the state.  It has soft sedimentary rock with clay minerals extending
 800 feet below the surface.   Such rocks containing large amounts of clay
minerals not only have low permeability but  they have the added
advantage of being flexible or plastic enough not to be permanently
cracked,  fissured or faulted by minor  deforming forces.   Even if
                              207

-------
earthquakes, land flextures, compaction and settling, or any other minor
deforming force changed the shape of the soft clay-rich sedimentary rock
body, its permeability would remain low.

The particular clay at the Starr County site is montmorillonite, which
has adsorptive and swelling properties especially favorable for
hazardous waste containment.  Whenever water and/or many other polar
liquids come in contact with montmorillonite, the liquid is attracted to
the mineral surfaces, causing the flat plate-like crystals to be
separated or pushed apart.  Any small amount of pore space originally
contained in the rock is reduced by this swelling.  The permeability of
the soil is thereby further reduced, sometimes to the point of zero
permeability.

The proposed landfill is removed from groundwater sources and major,
wells.  Groundwater in the area is only sufficient to support the
sparse population and grazing cattle.  Rainfall is low (i.e., about 18
inches per year) while the evaporation rate far exceeds precipitation
(approximately 102 inches).  The area's topography is dominated by
gently rolling surfaces sloping from southwest to northeast, away from
the Rio Grande River.  The grade minimizes water infiltration while
avoiding excessive erosion.  The site is located outside of the flood-
prone area of the Rio Grande and the closest arroyo.  There have been no
recorded earthquakes in Starr County.  Indeed, many geologists consider
the county the most seismically stable region in North America.

Starr Industrial proposes to landfill drummed and bulk Class I wastes.
According to state waste classifications, Class I includes all com-
mercial and industrial wastes including PCBs.  Most of the waste Starr
Industrial expects to treat and dispose will come from petrochemical
manufacturers and oil drilling operations, primarily in the Houston
area.

The proposed disposal method consists of mixing wastes with soil in a
5:1 ratio then burying the waste in cells covered with more of the
impervious native clays.  Those wastes which might become odiferous, ex-
plode or self-ignite when exposed to the atmosphere will be buried in
55-gallon drums.  Each drum will be placed in a separate trench with
sufficient clay encapsulation to achieve the same 5:1 soil-to-waste
ratio if and when the drum  corrodes or otherwise releases its contents.
Waste oils and oil sludges  will be received in a tank from which
gravity-separated oils can  be reclaimed.  Sludges, cleaning/processing
water and inorganics will be moved to a slurry tank where they will be
blended with oil and buried.  Incompatible wastes will be deposited in
separate cells.  All solvents and volatile hydrocarbons will be tested
for compatibility with the  clay liner prior to burial.

Rainfall in potentially contaminated areas will be captured within
levees and  drained to the  slurry mix tanks from which it will be
landfilled  in the manner  of bulk liquid wastes.  A three-foot high berm
and  drainage ditch will serve to control surface  runoff from the site.
Facility design allows all-weather entrance and exit by way of gravel
roads.  A six-foot fence will surround  the site to prevent  stray entry
                                   208

-------
of children, animals, etc.  The gate entrance will be supervised and
shipping tickets will be received from incoming trucks for recordkeeping
purposes.  Site supervisors will be responsible for overall safety.

The topography of the area is such that surface waters originating out-
side the site can easily be controlled by diversion ditches and berms.
Drainage will be to an unnamed creek adjacent to the site, thence into
Los Almos Creek, thence into the Rio Grande River.

For safety precautions, Starr Industrial proposed six monitoring wells
and eight lysimeter wells for monthly pH and total organic carbon con-
tent checks.  The presence of pH changes or hydrocarbons indicates
leachate movement from the filled cells into the surrounding soils.  If
such leachate movement is detected and determined to constitute a
significant threat to the environment, Starr Industrial proposed to
either discontinue use of the cell, excavate the cell and move the con-
tents to a second cell or install a wellpoint system for capture and
subsequent treatment or disposal by other means.  Starr Industrial also
proposed periodic on-site testing of wastes, rainfall runoff content,
etc., to ensure proper handling and burial.

The proposed landfill has a projected life of three to . four years—
the time estimated to reach disposal capacity of 13 million gallons of
liquid waste.  Upon closure of the facility, Starr Industrial has
offered to fertilize, seed and irrigate the site and to return it to a
state visually compatible with the surrounding land.  The area would be
fenced and marked off to prevent unauthorized trespassing and possible
site disturbance and/or contamination.

Original impetus for a Starr County landfill came from the Alice
Specialty Company which has been involved, in hazardous waste handling
for a number of years.  During this time, the company became concerned
with illegal dumping practices of truckers and waste disposal companies.
These practices not only damaged the environment but also hurt the
ethical trucking companies' competitive position.  "Outlaw" firms merely
poured wastes indiscriminately or hauled them to illegal sites.  This
allowed these dealers to charge lower rates for waste removal.
Companies like Alice Specialty had to charge more (or at least incurred
greater expenses) because of the care they took in handling wastes and
in selecting well-managed disposal facilities.  Inspired by corporate
self-interest and environmental awareness, associates of Alice Specialty
created an independent disposal company: Starr Industrial Services.
Major stock holdings were retained by the owner of Alice Specialty.1  The
new company's purpose was to establish an environmentally sound landfill
for safe hazardous waste disposal.

The city closest to the proposed landfill is Rio Grande City (population
       , the largest community in Starr County.   Starr County occupies
1
   Population estimates from the 1973 Texas Almanac.
                                 209

-------
a 1,211-square mile area with a total population of 19,600.   The
population is predominantly low-income Mexican-Americans whose principal
source of employment is low-yield farming and ranching.   Population
density in the area is among the lowest in the state.   This  is due to
the scarcity of water and the very low agricultural productivity of the
land.  With the exception of Rio Grande city there are only  two
communities with more than 1,000 people in the County.  These are  -
located miles away, from the site on the Rio Grande.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE    ',  ,

Under Texas law, commercial-industrial waste sites, if not owned and
operated by and located within 50 miles of the waste generator, must
receive a permit from the Texas Water Quality Board.  The law also
requires public hearings on such commercial-industrial waste disposal
permits.  The discharge permit issued by the Board is the only state
permit required in developing a commercial landfill.  No local permi.ts
or approvals are required, because Starr County does not have zoning
regulations.

Starr Industrial began its siting efforts in mid-1975 with a costly
statewide search for the most technically and demographically
appropriate landfill location.  Studies were conducted by Starr
Industrial's engineering consultants from Houston and a geologist from
the University of Texas.  The search was guided by siting criteria
proposed by the Texas Water Quality Board.  The criteria call for a site
with impervious soil, little or deep groundwater sources, low rainfall,
high evaporation, low population concentration, and low or non-existent
flood or earthquake risks.  Such a site was found in Starr County.

In late 1975 and early 1976, approximately six months prior to the Starr
Industrial Services' application for an industrial waste disposal permit
from the Texas Water Quality Board, active steps were taken to explain
the  facility to local public and private groups.  Meetings were held
with city, county, Chamber of Commerce, and council of government
officials both in the county where the site was to be located and
downstream from the site in adjacent counties along the Rio Grande River
Valley.  The company's consultants presented technical descriptions of
the  waste facility and the extraordinary environmental suitability of
the  local area.  Although the proposed site would handle wastes from the
Houston area,; several hundred miles away, Starr Industrial
representatives explained that a thorough environmental analysis of
environmental criteria had resulted in the selection  of the Starr County
site.  Furthermore, the majority stockholder in Starr Industrial was a
waste materials hauler who assured the county safe and reputable
transportation services.

During these early meetings discussion centered on the technical oper-
ation of the site and the suitability of the physical surroundings^
Little mention was made of benefits to the area and its inhabitants^ from
                                  210

-------
 the operation of:the hazardous waste facility.   There was little evi-
 dence of public opposition at this time.   The general attitude of the
 public,  as represented by the local officials,  was one of wait and see.

 Starr Industrial submitted a permit application for a 40-acre facility
 to the Texas Water Quality Board in June,  1976.   The Starr Industrial
 permit application was reviewed by the Board's  technical staff and a
 review committee made up of other state agencies..  The Board staff  -
 conducted an on-site inspection in July.   The proposed landfill met with
 the staff's  overall approval on technical  acceptability and site
 suitability.   The staff introduced .several concerns that were later
 included as  special provisions in the  draft permit.   These provisions
 included maintenance of a bond or other financial assurance (not less
 than $40,000)  for  proper and adequate  closing of  the facility and a
 $15,000  trust  fund for surveillance, repairs  and  monitoring: during the
 proposed 36-month  closure period.   Other provisions  referred to specific
 waste handling and monitoring details.  The staff report to the
 directors of the Texas Water Quality Board suggested that  if Starr
 Industrial adhered to its proposed plan of activities  and  to the special
 provisions in  the  draft permit,  no environmental  damage would result
 from the landfill's  operation.

 The technical  staff  of the Board indicated that the permit application
 was one  of the best  received to  date.   The credentials  of  the geologic
 consultant, a  professor of geology from the University  of  Texas,  were
 considered impeccable.   Furthermore, the major stockholder  o£ Starr
 Industrial, an industrial waste  hauler, had a good  reputation among
 state  agencies for proposing a manifest system for  disposing  of
 hazardous wastes and in helping  to make the state aware of  haulers who
 clandestinely  dump their  hazardous wastes  along highways,  drainage
 ditches  and other  unauthorized places.  The result  of  the  Board's
 technical staff  review and the state agencies review committee was a
 proposed  permit which was presented in  a public hearing  in Starr County
 in September.                                                      .

 Opposition to  the  site  surfaced after the  permit  application.  There was
 considerable confusion among  local officials  and  residents  over exactly
 when the  opposition was started and by whom.  The opposition  seems to
 have been spearheaded  by  the  County Judge  and the Court  of County
 Commissioners.  (The Judge  is the elected  executive of the county,
 serving a  four year  term along with four district commissioners.  The
 County Court of Commissioners is the executive and administrative head
 of  the county.)  The County Judge is one of a very small handfull of
 medical doctors in the area, highly respected by the local inhabitants
 and by his peers, who in  1977 gave him a nationwide AMA-sponsored
 Bicentennial Award for public service.   His opinions on the matter of
 hazardous waste are widely respected because of his medical training and
 because he is one  of the few doctors serving the mostly poor
Mexican-American community.  Regardless of  the origin of the opposition,
 the county commissioners announced opposition to the facility in a
 letter sent to the Texas Water Quality Board in August.
                              211

-------
During the summer, opposition was also voiced by the Chamber of
Commerce, Industrial Foundation, Rotary, Kiwanis and a local women's
study group.  The thrust of the opposition was the emotional issue of
hazardous wastes from outside the county being disposed of in their
"back yard".  Starr County, in the minds of its inhabitants, has the
image of being a community of poor, second class citizens that is
generally being "dumped-on".  Local officials said that this image is
'reinforced by the bad publicity the county receives over the reputed
drug traffic across the Mexican border, and cited a national magazine,
which recently rated Rio Grande City as one of its choices for the "ten
meanest  towns in America."  The public hearing record referred to a 1975
EPA report on the "Quality of Life Indicators" which ranked the
surrounding area between Laredo and McAllen as having the lowest
economic and political qualities of 95 SMSAs under 200,000 in
population.  Starr County inhabitants have an average per capita income
that is  approximately one third of the state and national average.  The
elected  officials as well as  those trying to increase the economic
prosperity  of the area saw the introduction of a hazardous waste
facility as contributing to  this bad  image and as a further sign of
being  "dumped-on".  These groups were  opposed to the image of a waste
dump as  well as  the inevitable  risks  in  transporting, disposing and
final  site  closure associated with hazardous wastes.  They were also
opposed  to  the  fact that  their  county  would be used as  a dumping site
for Houston's wastes.  The Chamber of  Commerce and Industrial Foundation
were eager  to have  the community's economic base grow in conjunction
with the increasing prosperity  of  their  neighbors in Mexico.  The
hazardous waste site,  however,  would be  inconsistent with  these plans.

Opposition from organizations and agencies  in Rio Grande City and  Starr
 County was  manifest by the  end  of August.   In early September, the Texas
Water Quality  Board published notices of a public hearing  on  the permit
 application.   The hearing,  a standard part  of the Board's  permit review
 process, was scheduled for late September.

 Opposition to  the proposed landfill expanded.   The  opposition was  not
 restricted to Starr County.   Letters were received  in response  to  the
 public hearing notice from neighboring counties,  towns  and citizen
 organizations  that felt threatened by the site  and  its  potential hazard
 to agriculture in the Rio Grande River Valley and their water supplies.
 The concerns expressed in these letters were  over  the impact  on  drinking
 water supplies, funding to pay for possible damage,  more technical
 information as to the dangerous mixing of chemical substances,  and more
 information on long-term soil stability.  One of the letters,
 representing several women's groups summed up this  opposition:   "We are
 aware that this group (Starr Industrial) is a group of responsible
 people well-versed in safety procedures for the handling and disposing
 of the wastes produced by their businesses; but we do not want these
 wastes transported to, much less disposed of, in Starr County...  We know
 that safety procedures are set up to operate in every instance when they
 are needed, but we do not want to live with that potential hazard in our
                                 212

-------
area.  Our soil may be impermeable,  and the chances of waste products
escaping into our underground water may be slight,  but we do not want
this hazard here, however slim this hazard may be described.",

By the time of the public hearing, there were no letters or other
documents favoring the site other than the original application for a
permit.

The public hearing held in Rio Grande City was attended by 81 opponents,
30 observers, 12 proponents and 10 members ;of the Board.  Starr
Industrial alleged that the majority of those attending were local,
county, city and school district employees.  Of those in favor of the
application, all had direct Starr Industrial connections.

Representatives of Starr Industrial presented a technical description of
the site and its operation.  During the expert testimony of Starr
Industrial's consulting geologist it was pointed out that "based on the
factors earlier set out regarding geology and rainfall, and based on the
fact that other suitable sites are surrounded by more densely populated
areas, the proposed site is the best in the State." In connection'With a
question as to whether the applicant had adequately informed the local
citizenry, it was pointed out that of the abutting landowners one was
agreeable to selling a right-of-way easement, one wanted to develop a
similar facility, one would not sell (but indicated no objection to the
facility) and one would sell a piece of property to Starr Industrial.
The applicant also testified that several meetings had been held with
the Chamber of Commerce and the Rotary Club.  Both a citizen and a local
geologist pointed out that these limited meetings were inadequate from
the point of view of informing the public at large and furthermore,
there was still a question as to why this site was chosen over other
suitable geologic sites that exist in the state.

Several other witnesses appeared at the hearing, either in a represent-
ative or individual capacity, to testify against the site.  One adjunct
landowner opposed the site proposal based on his fear of fires,
explosions and possible spills or migrating wastes which could ruin
water wells or kill crops.  During the hearing it was pointed out that a
flood protection and recreational reservoir in the area of the proposed
disposal site had been in the planning stages for some time.  Although
it was felt that this would be a higher valued use of the land, no
specific decisions had been reached, or for that matter were pending, on
the construction of the dam.

The County Commissioners made the statement that they should have been
made officially aware of the Starr Industrial proposal much earlier in
the planning  process.  In addition the Commissioners stated that they
did not believe  that this type of industry would encourage other
industrial growth which would employ more people in the area, and that
there would be present and long-term problems from fireSj traffic
mishaps or flooding.  The commissioners felt that although there was
good technical preparation for this hearing and that the applicant was a
                              213

-------
reputable businessman, the problem with the proposed site was mainly a
"people issue".  Since much of the wastes to be disposed of  come from
the petrochemical industry around Houston they should be disposed of
there and not in Starr County, hundreds of miles away.

Following the public hearing opposition to the proposed facility
continued to be registered.  In October the county commissioners passed
a resolution opposing the facility and a state senator from a district
adjacent to Starr County stated his opposition.  The senator based his
opposition on the questionable reliability of data on long-term soil
characteristics, the impacts of buried wastes on those soils, inadequate
bonding provisions, and the potentially limited liability of Starr
Industrial.  He was also generally concerned about long-term impacts on
agriculture in the area.

In December, a summary of the September public hearing was  released by
the Board.  In that summary, the hearing the Hearing Commissioner found
that the proposed site met all the technical and legal requirements of
the Texas Water Code, Texas Solid Waste Disposal Act and the rules and
procedures of the Texas Water Quality Board.  However, the  Hearing
Commissioner questioned whether, if an applicant wants to use his land
in a legal and safe manner and is ready to proceed, the Board should
deny such use based on some speculated future use of land and water in
the area; and whether the Board should deny the proposal because the
wastes proposed for disposal would not be generated in the area but
would have to be hauled several hundred miles to the site.

Because of these remaining policy questions, the Hearing Commissioner
did not make a recommendation to the Board on the proposed site.
However, in an addendum to his report, the Hearing Commissioner pointed
out to the Board that the Board had previously denied a permit in a
similar situation on the basis that the inhabitants of the county, some
of whom lived in the general area of the site, believed that the future
development of their county was incompatible with having in their county
a major industrial solid waste disposal site, especially one where the
wastes were derived from activities remote from the county.

In January, 1977, as a result of the hearing report and the later
addendum, the Board denied the permit.  The denial was based primarily
on their finding that "the adamant local opposition to the application
for a proposed industrial solid waste management site (is to the effect
that) the granting of a permit would be contrary to the welfare of the
people in the area."

In March, 1977 following the Board's denial, Starr Industrial attempted
to gain the county commissioners' approval and thus pave the way for a
rehearing with the Board.  They presented petitions of citizens in favor
of the site, more evidence and physical demonstrations of the disposal
practices as well as  the economic benefits of  the site.  The benefits
would be four  jobs on site plus "many" opportunities for entry into the
waste hauling  business  through owner-operated  trucks in conjunction with

-------
the site.  The County Commissioners again voted a resolution against the
proposal.

Starr Industrial then appealed the rejection of their application to the
Texas District Court arguing that the permit denial was based not on the
facts but on a not-so-similar site in another part of Texas which had
received over 6,000 letters opposing it.  In January of 1978, the court
ruled in favor of Starr Industrial stating that adamant local opposition
to the permit application does not constitute a proper legal basis for
the Board order denying the permit.  There were several other minor
technical points regarding the proposed site to which the Board had
objected and these were also dismissed by the Court.

The Board dropped out of the case after its findings were overruled.
However the County Commissioners have taken up an appeal to the court
order.  They are still opposed to the site.  Several new Commissioners
have recently been elected, including a new County Judge.  Although the
County Judge campaigned on the basis of opposing the site, he has stated
that he will keep an open mind on the proposal till shown its risks and
benefits.  In March 1979, however, the new County Judge flatly refused
to reconsider the county's appeal of the court decision.  This reaf-
firmation was prompted by yet another appeal to the county court by
Starr Industrial.  The retired County Judge has reiterated his position
that no benefits can be worth the risks posed by the proposed site.
Starr Industrial is continuing its effort to obtain a permit for this
site to protect its investments to date as well as to set a precedent
for future sites that will otherwise face similar obstacles.

The current procedural and legal status of the proposed hazardous waste
•facility is in limbo.  Having been overruled by the State District Court
in its denial of a permit on the basis of adverse public opinion, the
Texas Water Quality Board has withdrawn from the case.  Presumably the
Board can now issue the permit, although it has chosen not to act at
this time pending the County's appeal to the court ruling.  The County
•Commissioners have taken up the appeal to the Judge's ruling hoping to
reinstate the Board's original denial of the permit.  Starr Industrial
on the other hand is planning to oppose the county commissioners in an
attempt> to defend against the upcoming appeal and thus have the permit
granted.  Starr Industrial is also trying to persuade the County Com-
missioners, outside of court, from proceeding on the appeal and let the
Judge's  ruling stand.

The court's decision on the county commissioners' appeal which had been
expected in February, 1979 was later postponed until the summer of 1979.
Thus  the'earliest conceivable date for granting Starr Industrial a
permit would also be summer^ 1979, approximately four years after it be-
gan the  siting process.
                                215

-------
 IV.
CHRONOLOGY OF EVENTS
 1975 — Starr Industrial Services is founded and the statewide search
        for a technically and demographically appropriate hazardous
        waste landfill site is begun.

 Winter, 1975 — Starr Industrial meets with public officials and
                businessmen from towns downstream from Rio Grande City
                to discuss the proposed facility.

 February, 1976 — Starr Industrial makes a presentation describing the
                  proposed facility to the Rio Grande City Chamber of
                  Commerce.

 June, 1976 — Starr Industrial files an application for a permit for an
              industrial waste landfill with the Texas Water Quality
              Board.

 August, 1976 — The Texas Water Quality Board receives letters from the
                Starr County Judge, County Commisisoners and the Rio
                Grande City Chamber of Commerce stating their oppositon
                to the propsed facility.

 September, 1976 — Board receives letters from downstream city and coun-
                   ty leaders opposing the facility.   Board holds public
                   hearing on permit application in Rio Grande City.
                   Local residents without exception express opposition
                   to the facility.
October, 1976 —


December, 1976 -
          Starr County commissioners  pass a resolution  opposing
          the facility.   State senator opposes  facility.

         - Hearing Commission's report is published.  Starr
           Industrial becomes  aware that decision on permit may
           be made on other than technical grounds; unsuc-
           cessfully attempts  to gather political support.
January, 1977 — The Texas Water Quality Board denies the permit.

March, 1977 —' Starr Industrial attempts to get support of the Starr
               County commissioners for a rehearing.  When this fails,
               they initiate legal action against the Board.

January, 1978 — Court rules in favor of Starr Industrial, stating that
                 adamant local opposition to the permit applications
                 does not constitute a proper legal basis for denying
                 the permit.  The Board drops out of the case.  However,
                 the Starr County commissioners appeal the court order.

Summer, 1979 — Expected date of appeals court ruling on the  Starr Coun-
                ty appeal.
                                216

-------
V.
ATTEMPTS TO SECURE SUPPORT
The  only attempts  to  secure  support  for  the Starr Industrial facility
were made by the Company and its consultants and the technical staff of
the  Texas. Water Quality Board.  These  include the following:

       o     The Company held meetings with local elected officials and
             community leaders prior to  submitting their permit ap-
             plication to the state.  At these meetings the unique en-
             vironmental suitability of  the site was presented as well
             as the technical operations of the facility.  Attempts
             were also made  to indicate  the potential employment op-
             portunities connected with  the site.

       o     Following the Texas Water Quality Board's denial of a
             permit,  Starr Industrial again sought the support of local
             elected  officials with additional technical presentations
             and demonstrations in the hopes of getting a rehearing with
             the Board.

       o     Support  from the Board staff was primarily in terms of
             their favorable technical review of the permit application.
VI.
SUMMARY EVALUATION
Attempts to secure support have been successful on some points but
overall have failed to secure any significant support from local leaders
for the proposed facility.  At least some opponents have acknowledged
that Starr Industrial is a responsible and reputable company.  Moreover,
some major technical aspects of the proposal have not been disputed.
Yet, opposition to the facility has not waned.

Starr Industrial expects that their permit application will ultimately
be approved.  They feel that they have a technically, financially and
legally superior proposal.  Furthermore, they believe that something has
to give in the growing dilemma between waste disposal siting and citizen
opposition.  They feel that the constantly increasing amounts of
industrial wastes generated and the need for a reputable and responsible
hazardous waste operator will tip the scales in their favor.
Furthermore, Starr Industrial feels that hazardous waste disposal is  a
good business and worth waiting for.  They pointed out that many waste-
generating industries in the Houston area are warehousing their wastes
until such time as disposal provisions can be made.

The County Commissioners, on the other hand, have indicated their wil-
lingness to continue the fight against the proposed site.   They see en-
vironmental and public risks as well as the continuing deterioration of
the county's image if the site is developed.  They also fail to see any
real benefits to the community.  The Chamber of Commerce,  the leading
organization looking out for the business interests of Rio Grande City,
is backing the Commissioners in this fight.
                                217

-------
The conflict over the proposed Starr Industrial hazardous waste site is
not yet over.  The final court appeal has yet to be heard and the final
decision by the Texas Water Quality Board as to the permit has yet to be
handed down.  However, to date very little has been done to resolve lo-
cal conflicts, especially those over technical misunderstandings, the
lack of community benefits to offset risks, and the risk to the
community's self image posed by the hazardous waste site.  Both Starr
Industrial and the state's technical staff tried to let the proposed
site sell itself to the local officials and Texas Water Quality Board on
the basis of its technical merit.  Very little was done to deal with the
intense local political pressure that developed over dumping Houston's
hazardous wastes in Starr County.

There were no mediation efforts by respected neutrals on the scene.  It
appears as though the protagonists for the site, members of Starr
Industrial, and antagonists, the county commissioners and business
leaders, are at a stalemate with no indication of possible compromise.
Furthermore, the stalemate can probably be broken only by direct order
of the courts or an entirely new approach by Starr Industrial to provide
Starr County with data about direct or indirect benefits to offset the
negative image and minor risks of the site.

There are four broad areas of conflict over the proposed siting of the
Starr Industrial Services hazardous waste site.  First, there is the
inevitable controversy over -technical issues with "expert" witnesses on
either side of the question.  Second, there is concern over appearances
and the self-image of the county, the disposal site and the operator.
Third, there is the question of whether the site would provide suffi-
cient local benefits to offset the risks.  Fourth, there is confusion
over the legal standing of public opposition in the denial of a permit.
Highlights of each of these areas of conflict are listed below:

Technical — Site selection appears to have been carried out in a
thorough and straightforward manner.  The site met all of the en-
vironmental and safety criteria established by the Texas Water Quality
Board.  However, in spite of scientific evidence presented by Starr
Industrial and the Board, expert witnesses for the county have
questioned the environmental and public safety of the site.

Local Image— County elected officials and businessmen believe that the
proposed facility would have a negative impact on the area's image.
These spokesmen describe the community as ,the unwilling recipient of
Houston's industrial wastes.  Starr Industrial, on the other hand, sees
the waste disposal facility as a good business opportunity for both
themselves and community residents.

Benefits vs. Risks — Local residents feel that the risks associated
with the facility far outweigh any benefits. . In fact, very few benefits
would be provided by the facility.  Technical evidence was presented
which verified the environmental and public safety of the site.
However, the public seems to be demanding that the site be built only if
there is absolutely no risk, a condition which cannot be met.
                                218

-------
Legal Status of Local Opposition — Opponents claim that the proposed
facility is not in the interest of local residents and that this is a
legally valid ground for denying Starr Industrial's permit.  The Texas
Water Quality Board, in denying the permit, clearly gave substantial
consideration to this contention.  The court just as clearly found this
arbitrary and capricious.  The current" appeal of the court's decision
hinges in substantial part on this issue.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION         "               '

The following were the major factors leading to the continuing op-
position.

       o     Initial information on .the proposal provided by Starr
             Industrial to public and private agencies.

        o    Expert witnesses with conflicting testimony on both sides
             of the issues.

       o     Abundant technical misinformation on site characteristics
             and facility operations.

       o     Inability on the part of the company to convince locals of
             site benefits to offset risks.                      ,

       o     Image of a hazardous waste site unnecessarily contributed
             to an already poor community self-image held by local
             business leaders.

       o     Administrative misinformation on correspondence dates,
             origin of petition lists, and meeting attendees added to
             confusion and site opposition.

       o     Short-term permit required by the state for the first of
             many proposed tracts contributed to site operators'
             hit-and-run image.

VIII.   RETROSPECTIVE VIEWS

The major participants in the Starr Industrial proposal to site a
hazardous waste management facility were asked what if anything they
would do differently if given the chance.  The local business leaders
and local elected officials said that their opposition has been
steadfast throughout the conflict.  They see no way of having conducted
their opposition differently within the confines of their authority over
siting issues.

The position of the technical staff of the Texas Water Quality Board is
similar to that of the local officials.   They have steadfastly approved
the site on technical considerations but had no authority to consider
the issue of public opposition.
                               219

-------
                   INDUSTRIAL ENVIRONMENTAL SERVICES

                          KIRKSVILLE, MISSOURI
I.
INTRODUCTION
In late February, 1979, Industrial Environmental Services (IBS) withdrew
a permit application for a hazardous waste disposal site.  The with-
drawal was made after a particularly long and heated public meeting held
in Kirksville.  By that action, IES scuttled work to develop the site
that had been in progress for over 18 months.

Opposition arose from many major groups within the area and was based on
a broad range of issues.  County officials, faculty and students at
Northeastern Missouri State University (NMSU), state elected officials,
and abutters were among those that expressed outright opposition or
major concerns about the proposed facility.  These concerns covered the
site, its design, and facility operations as well as the credibility of
Missouri's Department of Natural Resources (DNR), which regulates
hazardous waste management and the hazardous waste management industry.

IES and, to a lesser extent, DNR attempted to generate support and to
allay public concerns by providing more information to the community.
While these attempts did address some concerns, they did not produce any
significant change in the public response.  On the contrary, most of
those interviewed, on both sides of the dispute, felt that these
attempts only increased problems with public opposition.
II.
BACKGROUND INFORMATION
The IES proposed site was about three.miles north of Kirksville,
Missouri just off U.S. 63.  The total land area under IES control was
682 acres, of which 33 acres were designed for a muncipal landfill and
192 acres were designed as a secure landfill for hazardous waste.  The
secure landfill was bounded on some or all of three sides by a one-half
mile strip of undeveloped land owned by lES's president or by the
municipal landfill.  Surrounding land use is primarily agricultural.
The soil directly underlying the site is Kansas till which IES bores
indicated was over 150 feet thick.  Tests showed the till's permeability
to be in the 10~^ 10~^ cm/sec range.  The Missouri Geologic Survey
indicated no usable groundwater within Adair County, although the
possibility of small perched aquifers beneath the site existed.  lES's
consulting engineers concluded that the site was "well suited for its
proposed use" and any anomalies at the site could be corrected by
engineering.

The facility plan called for a three-stage development.  In the first
phase, 20 disposal trenches would be developed with a net capacity of 24
million cubic feet and a projected life of approximately six years.
                                220

-------
A service road, a 2,640-square foot building, and holding lagoons would
also be constructed.  The building would include laboratory facilities
for spot checks of incoming wastes.  Eight monitoring wells would also
be installed.  The entire area would be fenced.  The second phase would
involve the development of an additional 13 trenches and four monitoring
wells.  This would extend site life by six to seven years.  In the third
phase an additional 11 trenches and five monitoring wells would be
developed and site life would increase by about five years.  Total site
life was estimated at 18 to 20 years and total capacity at 2.5 million
cubic yards of hazardous waste.  The development plan stated that
post-closure monitoring and maintenance would be done "in accordance
with governing rules and regulations."

Personnel for the site included a site manager, a chemist responsible
for on-site analysis of wastes, and a minimum of five additional staff
for site operations and administration.  A consulting engineer would be
retained.  Oil-site records would include generator and hauler
descriptions of wastes accepted, receipt logs, and locations of wastes
buried on-site.

IES, the facility sponsor, was incorporated for the specific purpose of
developing this facility and as a corporation has had no other
experience in hazardous waste management.  IES is an independent
corporation not connected with other firms.  lES's president, however,
owns and operates Missouri Dispose-All, a solid waste collection and
hauling company in Kirksville, and had  formerly operated a sanitary
•landfill in  the Kirksville area.   IES intended in addition to offering
disposal services to act as a broker for hazardous wastes which could be
reclaimed or recycled, to haul hazardous waste, and to develop in the
future some  treatment capacity on-site.  The anticipated market area for
the site was Northeastern Missouri, the St. Louis area, and possibly the
Kansas City  area.

The city of  Kirksville has a  current estimated population  of  19,000, and
serves as a  trade center for  a multi-county  area  in Northeastern
Missouri.  Kirksville is about 220 miles north of St. Louis and  165
miles  northeast  of  Kansas City.   The area is  predominantly agricultural,
although several industries in Kirksville employ  almost  2,000 persons.
Kirksville  is  the home  of NMSU and the  Kirksville College  of  Osteopathic
Medicine.   Because  of the  presence of these  institutions,  and because  of
the town's  role  as  a regional service  center,  the city has a
disproportionately  high  number of  professional and technical workers.

III.   HISTORY OF FACILITY  DEVELOPMENT  AND PUBLIC RESPONSE

 In the state of  Missouri,  a HWMF requires a  permit  from  DNR before  it
may operate.   Under the 1973  Solid Waste Management  Law,  a HWMF  must  be
 issued a special operating permit which is based  on  case-by-case
 negotiations between DNR and  applicants.  As of March 1979, new
hazardous  waste  regulations were in  draft  form and  final promulgation

-------
 was scheduled for October,  1979. DNR's  regulations and authority do not
 overrule local zoning.   Adair  County, however, has no zoning.
 required only the DNR permit to  operate.
Thus, IBS
 Two  major incentives  gave  rise  to  this project:  first, IBS had
 determined that  a market existed for a HWMF in the Kirksville area;
 second,  the development of a municipal landfill at the site would
 complement Missouri Dispose-All's  collections and hauling business and
 reduce problems  related to the  city-owned municipal landfill.  While
 these  facilities  would be  two distinct operations, revenues from the
 HWMF were expected to subsidize the operation of the municipal landfill.
 Without  the HWMF,  ZES's president  felt that the sanitary landfill would
 not  be economically feasible.

 Planning for the  project began  in  July, 1977.  The first ten months were
 spent  in selecting the site, acquiring options on the site, and seeking
 preliminary approval  of DNR.  The  site was selected on the basis of
 accessibility to  U.S. 63,  proximity to Kirksville, and the geology of
 the  level.   Other sites were not considered.  By May, 1978, options had
 been acquired on  the  682-acre site.  At that time, IBS applied to DNR
 for  preliminary approval of the site.

 Preliminary approval  entailed an initial site investigation by DNR.
 Using  secondary materials  and some field work (e.g. test bores) DNR
 staff  analyzed the site's  geology  and accessibility.   These analyses
 indicated no  geological conditions which would exclude further
 consideration of  the  site  as either a solid .or hazardous waste disposal
 facility.   With preliminary approval given in August 1978, DNR indicated
 that IBS must make a  formal application complete with a detailed
 engineering plan.

 In June  1978, in anticipation of DNR's preliminary approval,  IBS
 retained Environmental Engineering, Inc., to prepare the detailed
 engineering plan.  Environmental Engineering had previous experience in
 both solid  and hazardous waste  engineering including  the engineering
 design of the Earthline facility in Wilsonville, Illinois.1  Field
work began  that same month with additional test bores at the  site.   Work
 continued through the fall and by December the permit application was
 ready  for submission.   On December 12, 1978,  the permit application was
made and a  four-part engineering report (development  plan,  operating
plan, geology and hydrology, and municipal landfill plan) with
appendices was submitted.   DNR received that  application and  requested
additional  data which Environmental Engineering forwarded to  DNR on
January 22,  1979.

In December 1978, IBS  approached the city of  Kirksville to discuss  the
proposed facility.  IBS and the city focused  on the proposed  municipal
   See the case study for Earthline/Wilsonville, Illinois  elsewhere
   in this appendix.
                               222

-------
 landfill.   Relatively  little  attention was  given to  the HWMF although
 IBS  told the  city  that revenues  from the HWMF were needed  in order  to
 make the municipal landfill economically feasible.   The city was  quite
 receptive to  the proposed  municipal  landfill.   The city manager
 explained that although the city-owned landfill could be expanded at its
 current site, the  city would  be  happy to get  out of  the landfill
 business.  The landfill, which serves a multi-county  area,  is a costly
 operation to  the city  and  a continuing source  of management problems
 including problems with meeting  DNR regulations. An IBS municipal
 landfill would receive a majority of the city's refuse, thus reducing
 the need for  and  justification of the city^-owned facility. The proposed
 IES facility  would have been  a major benefit  to the  city.   IBS asked
 city officials to  hold these  discussions  in confidence until DNR's
 public notice was  issued.   The city agreed to this request; however,
 soine local leaders had already learned of  the proposed municipal
 landfill through informal  channels.

 On January 3, 1979, DNR publicly announced that the  permit application
 had been received, and invited citizens to comment on the proposed
 facility.  Comments were to be accepted until January 26.  ^e
 notification listed wastes which would be,accepted at the, "industrial
 waste  disposal site" as "wastewater treatment plant  sludges,  industrial
 sludges, industrial liquids and other potentially hazardous wastes".
 The announcement briefly,described existing state regulations  and the
 fact that DNR approval was required for each type of industrial waste
 accepted by  the HWMF.  It also stated that if requested or considered
 necessary, DNR would hold a public meeting in Kirksville  before making a
 final  decision on  the  permit.

 DNR's  announcement was the first public knowledge of the  proposed,
 facility,  and it  generated an immediate response from area residents.
 In  January,  DNR received  eight,  letters of  concern and opposition, many
 from owners  of land near  the  proposed site.  On January 25, DNR
 responded  to those individuals  and announced that a meeting would be
 held February 22  at NMSU.  The  meeting would allow  for public comment,
 and representatives of DNR,  the applicant, and  the  applicant's engineer
 would  be present  to answer questions  about state regulations, facility
 design and facility operations.  The  letter also stated that  DNR had
 investigated concerns that disposal operations  had  already begun at the
 site.   No  operations  had  in  fact begun.  DNR publicly announced  the
 meeting on February 3.

 DNR's  public announcements touched  off  a  general, increasingly heated
  discussion of the proposal in the Kirksville area.   The first major
  public forum was  a local  radio station's  morning "talk show   which asked
  listeners to phone in with comments and concerns.   The proposed  site
  sparked heated discussions.   People spoke of  their  concerns and  fears,
  and solicited the support of others to fight  the site.  According  to
  some of those interviewed, information disseminated by  the show  inflamed
  area residents,  particularly the possibility of nuclear and radioactive
-  wastes being accepted by  the facility.  During one  show,  a resident
                                   223

-------
 suggested that a petition against the facility be circulated, and
 volunteered to be responsible for the petition.  By the time of the
 public meeting (about one month later), over 3,000 signatures had been
 collected.

 In early February, the pace of events quickened and opposition began to
 solidify.  Within a week of the announcement of the public meeting, the
 Adair County Court (i.e., the elected officials of the county) passed a
 resolution formally opposing the HWMF, although the court did indicate
 its support for the municipal landfill.   Faculty and students at NMSU
 began to review the permit application and other materials pertaining to
 hazardous waste disposal. (Because of public pressure, DNR made a copy
 of the permit application available to the public at its Macon office,
 about 35 miles south of Kirksville.   When interviewed, some local
 residents charged that the application could not in fact be photocopied,
 and that only handwritten notes  could be made of its contents.)
 Research by opponents included discussions with farmers familiar with
 the area's land and older residents  who  had worked in shaft mines in the
 county in the 1930s.   Two county-level special purpose government
 agencies in the area—a water district and a soil conservation
 service—went on record against  the facility primarily because of fears
 of water supply and soil contamination from leachate.   The city of
 Kirksville never took a formal position,  although like the county court,
 it supported the proposed municipal  landfill.

 On February 13,  the Community Betterment  Council held  a meeting at  the
 city hall to present  issues  surrounding the proposed facility.   The
 council is  one  of a number of such councils  set  up across  Missouri.   Its
 city-appointed  members  review a  broad range  of  community concerns,  seek
 to inform the public  of  these issues  and  advise  elected  officials.   In
 pursuit of  its  goal of  public education,  the council  invited  lES's
 president and a  representative of the opposition to  speak  at  the
 meeting.  At the meeting, lES's  president acknowledged  the public
 concerns  that had been raised and stated  that residents  should  be
 concerned because of  the nature  of wastes  to  be  handled.   He  also stated
 that he  felt community support was necessary  for  the project and that
 without  such support  he would not pursue  his  plans.  He  qualified his
 statement by saying that he  did not want  to give up the  project because
 of  emotional objections which were not based  on  substantive issues.  At
 the meeting he explained the  project and its safeguards, state
 regulations  including the required DNR approval for each hazardous waste
 accepted, his intention to serve the northeastern Missouri market, and
 another IES project.  (That project is a planned waste-to-energy
 facility that would produce steam for a local customer.) The project
 opponent  expressed concerns about the facility including the fear that
 buried drums would leak and potentially threaten water supplies.

After this meeting, a local radio station invited lES's president and
 two NMSU professors opposed to the facility to speak on a local radio
 program.  All three accepted the invitation and discussed the project
and responded to listeners' questions phoned in during the show.  The
                              224

-------
meeting and the radio show were the two major opportunities for IBS and
opponents to discuss and debate issues prior to the public meeting.
While those interviewed felt that these discussions led to,some positive
response (e.g., the option of illegal dumping was raised in general
support of the IES proposal), the general consensus was that the more
people heard, the more they objected.  As more information became
available, more questions were asked and more information was requested.
Information made available was considered too vague, too incomplete, and
unreassuring.

On February 18, the Kirksville Daily Express, in continuing its coverage
of the proposed site, ran an article entitled "Proposed Waste Disposal
Site Becomes Heated Controversy."  The article served to describe the
sense of the community prior to the public meeting.  The manager of the
local Chamber of Commerce indicated initial support for the project as a
local business.  During the site visit the manager explained that the
position reflected the Chamber of Commerce's general support for local
business development.  He did indicate that the statement was made
conditioned on an assessment of the environmental impact of the facility
and that the Chamber had taken no formal position on the matter.  Most
local and state elected officals, while expressing concern over
environmental impacts, adopted a "wait and see" posture which deferred
to the public response at the upcoming public meeting.  The presiding
county judge (i.e., the most senior county elected official) was
concerned-over the lack of letters the county judges had received.  The
judges wanted documentation of residents' feelings about the facility
and had received only five letters by that time.  The article mentioned
that the presiding county judge had contacted state elected officials to
determine what legal resource citizens could use to stop the site.

On February 22, DNR held the public meeting at the NMSU student union.
DNR officals from the solid waste program, a state geologist, lES's
president, and representatives of lES's consulting engineers attended,
as did a representative of EPA's Region VII office.  (EPA had no offical
involvement  in the permit or the meeting and was present as an observer
at the invitation of the area's state representative.)  Also in
attendance was a standing-room-only crowd of several hundred local
residents and officals.

The public meeting provided the most visible evidence of public
opposition.  Given lES's publicly professed desire  for  local support,
the meeting  marked the facility's demise.  DNR officals explained both
the permit application procedures and the technical qualifications  of
the site.  The state geologist explained that any new geological data
presented at the meeting would be considered before a final decision was
made.  The public response involved  four hours of prepared statements
followed  by  several more hours of "questions and answers."

It would  appear that every  issue of  concern  to local residents was
raised and that these covered every  conceivable issue that could be
raised.   They  ranged from those  questioning  the  legitimacy of  the  site's
                                225

-------
 geology to those attacking  the integrity  of  DNR and IBS.  Opponents
 pointed to experiences  at an area mine and a quarry which suggested the
 existence of  substantial underground water supplies.  The permeability
 of  soils was  questioned based  on  the area's  history of leaky ponds.
 NMSU  faculty  members  critized  the permit  application for being
 incomplete, vague and too open-ended, particularly in terms of wastes
 (i.e.,  application  listed in effect  all organic and inorganic materials
 as  being acceptable).   Because many  opponents felt that DNR had endorsed
 the IBS application even though no formal DNR decision had been made,
 the very vagueness  of the application was considered a clear sign of
 DNR's inability  to  understand  hazardous waste management and the,
 implications  of  this  particular proposal.  (During the site visit, an
 official of the  Community Betterment Council indicated that DNR had a
 tarnished record with some  local  leaders  who felt DNR had not been an
 effective environmental agency.   She indicated  that this perception
 compounded DNR's credibility problems during this siting attempt.)
 Local officials  charged that wastes  would leach into public water
 supplies and  demanded 100 percent  assurance  that this would not happen.
 They  felt that the  monitoring  provisions  proposed for the facility were
 inadequate.   Added  to these  and other technical concerns were fears of
 property devaluation and the notoriety of being known as the "dumping
 ground"  of the Midwest.  Opponents'  reviews  of  the permit application
 led to  the belief that  nothing would prevent out-of-state wastes from
 being brought in.   They felt the site's large capacity would guarantee a
 multi-state market  area.  Comments were not  confined to technical,
 political, or economic  issues  but  also personally attacked lES's
 president and state officials.

 While those interviewed differed dramatically in their views on how well
 the meeting was  handled by DNR, all  agreed that the meeting produced a
 fierce and emotional opposition to the project.   The response was
 heightened by a  sense of powerlessness on the part of local officials
 and residents.   They felt,  according to some of those interviewed, that
 DNR would make a decision regardless of local response and "ram it down
 the throats" of  local residents.   Over 3,000 of those residents had
 signed a  petition against the  facility, and  by the time of the public
 meeting  215 local residents had written the  county judges opposing the
 facility.  At one point a vote was taken,  and virtually all opposed the
 facility.  None  supported it.  During the meeting, DNR announced that it
 would accept public comment on the permit  application until March 6.

 The day  following the public meetings, IBS announced that the  ap-
 plication would be withdrawn.  The opposition at the public meeting con-
 vinced IBS's president that there was no public  support.   He also an-
 nounced  that the land for the proposed site would be sold.   During the
 site visit IBS's president  said that if DNR had  approved  the applica-
 tion,  public opposition would have probably continued and increased.   He
would have anticipated legal action to close the facility and  ongoing
harassment by opponents.

The withdrawal of IBS's application stopped the  siting  process.   DNR
 took no further action.   Several public and private agencies (e.g.,  the
 city and Chamber of  Commerce) which had not taken a formal position for
or against the facility were relieved of the  need to  do so.
                                226

-------
Representatives of those agencies, however, felt that they almost
'certainly would have passed resolutions against the proposed facility.
One  long-'term impact of this experience may be countywide zoning which
the  county  judges are considering as a means of increasing local control
over development in the county.

IV.    CHRONOLOGY OF EVENTS

July,  1977— IES begins facility planning and site acquisition
              procedures.

May, 1978	 Options acquired  on site; IES seeks preliminary approval
             for facility  from DNR.

June,  1978  -<- Field work by IBS's consulting engineers  begins.

August,  1978 ~ DNR gives  preliminary approval and go-ahead for  formal
                application.                             -

December,  1978 -•— IES submits  formal permit application with detailed en-
                  gineering plan.   IES discusses facility with city  of-
                  ficials.

January, 1979 — DNR announces receipt of permit application and public
                 .comment period and receives additional engineering  data
                  for application.   Opposition voiced  during local  radio
                  talk  show and by  some local officials.

 February, 1979'-- The  attempts to  discuss publicly the issues  for  and
                   against  the  facility add to the  already  growing  op-
                  position.  DNR holds public meeting,  in which  over-
                  whelming public  opposition is  displayed.  IES
   ,               withdraws  permit application.  The siting attempt  is
              ,.    stopped.
-V.
ATTEMPTS TO SECURE SUPPORT
 The following are the major attempts to secure support for the proposed
 facility:

        o     lES's discussions with Kirksville city officials stressing
              the advantages to the city of the proposed municipal
              landfill and the economic necessity of the HWMF.

        o     The Community Betterment Council's meeting, where IES and
              opponents presented arguments and explanations for and
       •       against the facility.

        o     The radio talk show debate during which IES argued in
              favor of the facility and against claims of opponents.

       ,o     DNR's making the permit application available in its
              regional office following public demands for information.
                                 227

-------
VI.
o     The public meeting at NMSU designed to provide DNR with
      technical data previously overlooked.

SUMMARY EVALUATION
 The attempts  to  generate support  for  lES's  permit application failed
 completely.   Indeed,  the argument  can be made that most of these
 attempts  only added to  the  opposition.  The more IES or DNR tried to
 anticipate concerns or  to respond  to  questions, the more they became
 mired  in  the  increasingly widespread  and vehement opposition.  The one
 major  exception  to this  is  the favorable response city and county
 officials gave to the proposed municipal landfill.  The issues
 surrounding the  HWMF, however, overwhelmed  any advantages that the
 municipal landfill may  have  lent the  overall project.

 The failure of these  efforts is undoubtedly the result of numerous
 interrelated  causes and  conditions.   A number of these, however, stand
 out.   Opposition began  and quickly developed prior to any major attempts
 by  IES or DNR to discuss  or  explain in detail the proposal and state reg-
 ulations.  Opposition then began on the basis of limited information,
 and appears to have mushroomed because of unanswered fears.  Some ac-
 cusations (e.g., that nuclear waste would be accepted by IES) were
 completely unfounded, but nevertheless had  the apparent effect of
 solidifying a  deep-rooted opposition.  IES  and DNR were then in the
 position  of defending (as opposed to  explaining) the proposal by the
 time they responded publicly.  Although lES's president went to some
 lengths to explain the restrictions that DNR would place on the site's
 design and operation, opponents were  not satisfied.  They either raised
 questions unanswered by those regulations or placed different
 interpretations  on them than those made by  IES or DNR.   The fact that
DNR's  regulations were pending and that the same was true of U.S.  EPA
 regulations intensified public unease.  From the local perspective,
 information that was made available was belated,  unwillingly shared,  and
most importantly, incomplete.  In spite of  this information,  too many
 "what  if's" remained unanswered.

The public response and attempts  to address issues were made in an
atmosphere lacking in dialogue and compromise.   A reconciliation of
divergent viewpoints appears never to have been seriously considered  by
all the interested parties.   Coupled with this was the absence of  a
trusted and knowledgeable party with no direct interest in the result of
the conflict.   For the most part,  each party was seen as having its  own
ulterior motive.

A great many issues were raised by opponents.   Those described in
Section III were not exhaustive as they excluded the most stridently
expressed.  These emotional  objections were not instructive because they
did not specifically pertain to the siting and operation of the proposed
facility.   They did,  however, reflect the general  hostility that
 (regardless of justification) people felt toward the facility  sponsor
                            22S

-------
and regulatory agencies.  That hostility became a concrete factor in the
controversy which chararcterized the siting process.

The major issues raised by opponents were the following:         •

Suitability of the site — Opponents questioned ,the soil's ability to
contain wastes and the claims that there was no significant underground
water supply beneath the site.  They feared contamination of public and
private water supplies and of the soil itself.

Operational risks — Opponents objected to the range of wastes that IBS
wanted to handle and to the importation of wastes from outside the
northeastern Missouri Region.  They feared that containerized wastes
would leak from containers and pollute soil and water.  They felt that
monitoring of the facility was insufficient.

Impact on local image and land values  —Opponents did not want
Kirksville to be known as the Midwest's hazardous waste dump and felt
that the proposed size of the facility guaranteed this.result.  They
felt land values, particularly those of land adjacent to the site, would
fall.

Credibility of the hazardous waste management industry -— The notoriety
of Love Canal and the publicity associated with Wilsonviile, Illinois,
as well as other information, contributed to a local image of the
hazardous waste management industry as irresponsible.  Locals also saw
public information as vague and euphemistic and thus they saw the
industry as being secretive and evasive.

Credibility of regulators •— For some residents, DNR was seen as a
previously ineffectual agency which would not do its-job of regulating
IES properly.  While not all felt that DNR had a bad track record, many
saw DNR's performance with respect to the IES application as inept, and
indicative of a staff without sufficient qualifications to judge the
applications or the resources to do a thorough job regardless of
qualifications.  DNR's information was seen as being just as vague and
unreassuring as that provided by IES.

Status of regulations and research — Coupled with the previous issue
was the fact that neither DNR or EPA hazardous waste regulations were
promulgated.  This gave rise to a sense that DNR had no basis for
permitting or regulating IES and, for some, a feeling that there would
be no controls over the facility.  Opponents also questioned the
state-of-the-art of hazardous waste disposal technology which they saw
as environmentally unsound.  Present knowledge about the nature of
hazardous waste (e.g., the degree of hazard and length of time.specific
wastes would be hazardous) was considered uncertain and therefore
unreassuring.

Local powerlessness — The lack of any local regulatory power angered
some local officials and residents.
                                 228

-------
VII.   FACTORS LEADING TO PUBLIC OPPOSITION /ACCEPTANCE

Opposition arose primarily because of the following factors, listed in
essentially chronological order.

       o     DNR's announcement that the application had been made
             provided the first public information and basis for
             opposition.

       o     A local radio talk show provided a public forum for
             opponents to discuss their concerns and enlist general
             support.

       o     Early information, some of which was completely incorrect,
             generated fears before IBS or DNR responded publicly.

       o     Two forums to "discuss" the proposal increased the amount
             of information available.  This only provided opponents
             with more issues of potential concern.

       o     The strong emotional and political reaction brought
             together traditional political rivals (e.g. the city, the
             county, NMSU).

       o     To this force, the intellectual and technical credibility
             of NMSU faculty was added.  Some residents felt the respect
             accorded these professors was the critical factor in the
             opposition.

       o     The public meeting provided an opportunity for opponents to
             mobilize at once their considerable political and technical
             resources against the proposal.

VIII.  RETROSPECTIVE VIEWS

Comments from those interviewed concerning the siting process were
primarily concerned with information made publicly available.  Local of-
ficials and leaders invariably felt that more information should have
been available earlier in the process.  This would have helped to reduce
concerns that the public was not being fully informed and that suf-
ficient time was not available to study the proposal carefully.   Had
this been available, some felt that there might have been greater op-
portunity to discuss the IES proposal in a reasonable non-adversarial
manner.                      -

The public meeting was the most dramatic event in the siting process.
It was praised by opponents because it allowed all opponents to express
their concerns and because it was conducted reasonably well given the
highly emotional atmosphere.  On the other hand, it was criticized by
the city and IES for its lack of a sense of order and reason (i.e., it
was felt that the meeting was allowed to get out of control).
                                230

-------
Kirksville's city manager felt that the meeting's purpose was never made
clear and that the issues to be discussed should have been clarified
before public comments were made.  The timing of the meeting was also
criticized.  Opponents felt that not enough time elapsed between the
announcement of the meeting and the meeting itself.  lES's president
felt the meeting should have been held much earlier in the process, at
the time of DNR's preliminary approval, so that any information on
anomalies of site hydrogeology would have been available prior to
developing detailed engineering plans.
IX.
GENERAL COMMENTS
Comments also touched on more general siting issues.  A number of
opponents of the IES proposal felt that if sites served local needs they
would be more acceptable to the public.  This line of reasoning
contemplated more smaller sites and a rationale emphasizing an area's
responsibility for solving its own problems.  The fact that available
land may not be the most suitable land for disposal was seen as a major
flaw in current siting procedures.  Most interviewees felt that sites
should be in extremely remote settings where potential impacts, on people
would be minimized.

Views differed widely on the question of appropriate roles for EPA, the
state, or the private sector in this process.  A minority of
interviewees (e.g., IES, the Chamber of Commerce) felt that hazardous
waste management should remain largely a private business with no
increase in governmental involvement.  According to this view, the
private sector should initiate public relations which "sell" a site by
demonstrating safety and potential benefits.  More local officials and
leaders, however, envisioned greater governmental involvement,
particularly for EPA, because hazardous waste is a national problem and
because EPA has more expertise than state agencies.  In this view, the
potential for federal disposal sites and for EPA management of RCRA was
stressed.

A major role contemplated for EPA by an NMSU faculty member was to,
advance the state-of-the-art in hazardous waste management and to
publicize these advances.  EPA was seen as creating problems by defining
hazardous waste problems, but failing to define and/or to demonstrate
that  there  were solutions to those problems  (e.g., environmentally safe
disposal sites).  A number of local leaders  felt that further research
would reduce problems in several  ways:  first, by changing manufacturing
processes  in ways designed to reduce  the volume of  hazardous wastes;
second, by  developing new treatment procedures, whereby hazardous wastes
could be rendered less  hazardous  or non-hazardous;  third, by defining
degree of hazard, whereby EPA could help the general public define risks
associated  with hazardous waste  disposal and thereby better judge new
sites such  as  IES.                                         •
                                231

-------
State comments focused on the public's perception of DNR's  role and the
outcome of the siting attempt had IBS not withdrawn the  permit.  A DNR
official felt that opponents had wanted DNR to criticize IES during the
meeting, whereas DNR saw the meeting as a means of getting  public input
of a technical nature.  Had IES not withdrawn its application, this
official speculated that pressure might have been placed on the governor
to delay any decision until state regulations were issued.
                              232

-------
                             IT CORPORATION

                          BRENTWOOD, CALIFORNIA
I.
INTRODUCTION
The IT Corporation in 1973 and 1974 attempted to site a hazardous waste
management facility near Brentwood, California.  The attempt was
unsuccessful, due to opposition from the local public and officials and
from the Shell Oil Company.

Local opposition to the facility was based on IT Corp.'s image among
local residents as an irresponsible and technically inept organization.
This image was due to IT Corp.'s operations at a facility in Antioch,
California, five miles north of Brentwood.  It should be noted that
state and EPA Regional officials believe IT Corp. to be one of the best
qualified hazardous waste management firms in California.  Shell Oil
Company's opposition was based on  their contention that the proposed
facility would have been incompatible with the company's high-pressure
gas producing operations.  Shell has operations that are within the
bounds of the proposed IT Corp. site.

The facility was supported by local industry—in particular by hazardous
wastes generators including the Shell Oil Refinery in Martinez—and
labor unions.  Other than presentations which were made to community
organizations, the corporation made no attempt to inform or involve the
local public outside of the required public hearing process.
II.
BACKGROUND INFORMATION
The IT Corp. "Oil Well" facility, as it came to be known, would have
been located on a 160-acre  site  two and one-half miles west of
Brentwood, California.  The northeastern half of the site is a plain
bisected by Sand Creek; the southwestern half, two parallel ridges and
the valley that separates them.  In the area proposed for waste disposal
use, slopes ranged up  to 20 percent.  The  southwestern part of the
property—in which disposal operations would have been located—is
underlain by beds of claystone and does not contain any good groundwater
supply*  The northwestern part of the property is underlain by clayrock
bedrock, which is eroded and  overlain by alluvial sediments.  These
alluvial sediments might comprise important groundwater sources in some
places,* and therefore would  not be suitable for hazardous waste
disposal.  A study conducted  for IT Corp.  by an engineering consulting
firm indicated that  the Tertiary Deposits  in the southwestern section
would meet all Class I requirements of the Regional Water Quality
Control Board.
    Communication  from Professor  Irwin  Reiason of  Stanford  University
    to  the  Contra  Costa County  Planning Department, March  21,  1974.
                               233

-------
The site had been used as low-order grazing land and  to grow feed
grains, but at the time of the proposal there were no surface uses.
However, it contained seven oil and gas wells and was under lease to
Shell Oil Company for subsurface oil production; an underground Pacific
Gas and Electric natural gas pipeline across the southwest corner of the
site; and Contra Costa powerlines across the northeast corner of the
.site.  Although oil wells were located on  the adjacent properties to the
north and east, the predominant use of these properties was as
agricultural land (rowcrops and orchards).  Northwest of and contiguous
to the site was the Brentwood yard of the  Shell Oil Company, which
served as the center of that company's small oil-production activity in
the area.  Adjoining land on the south and west was in its natural
grassland state and was sometimes used for grazing.

The site was zoned A-3, Heavy Agricultural, by the Contra Costa County
zoning ordinance.  The A-3 district restricts uses to agricultural and
related activities.  Access to the proposed site could be gained from
California Route 4 between Brentwood and Antioch.  Direct access was
along Sand Creek Road.  The latter was a minor, two-lane rural road.

Development .plans for the proposed Oil Well site included areas for  ,
chemical processing, solar evaporation, biodegradation, and trench
burial.  Initial operations would have included development of the
burial and biodegradation areas, a small laboratory and an evaporation
pond.  Later phases would have included closed reaction tanks with
associated equipment, tanks, and covered storage areas.  Interconnecting
pipes would have made it possible to transfer wastes  from one area or
process to another.  The phasing of site development  would have depended
upon how rapidly the firm's Antioch site was phased out.

It is estimated that the proposed facility would have handled
approximately 30,000 barrels of liquid wastes per month (bbl/mo).  Of
this, approximately 4000 bbl/mo would have been biodegradable
materials; 4500 bbl/mo, oil and water; 15,000 bbl/mo, acid waste
solutions; 5000 bbl/mo, waste basic solutions; and 1500 bbl/mo, other
materials.  The latter would include approximately 100 drums of
containerized liquids.  The site would not have handled pesticides,
radioactive wastes or "political" wastes (i.e. , controversial wastes
such as PCBs).  In addition, Bay Area Air  Pollution Control District
regulations would have effectively prevented the acceptance of such
wastes as solvents, concentrated acids, and light hydrocarbons.

At the time of the siting attempt there were no regulations, state or
otherwise, governing closure or long-term  maintenance.  Currently,
however, State Department of Health Services regulations state that  the
operator is liable for proper closure and  long-term maintenance.  No
specific provision is made for funding liability.

The projected life span of the facility would have been 50 years, plus
or minus ten years.  The long life of the  site is due to the fact that
chemical processing, evaporation and biodegradation, which were planned
to be the primary methods for dealing with hazardous  wastes in this
                               234

-------
facility, do not require as much land as conventional landfilling.  Only
sludges from treatment processes require landfill disposal.  Drum burial
would have only been a very minor part of operations (about 100 drums
per month).

The proposed facility would have served only industries located
primarily in Contra Costa County.  The county is the heavy industrial
center of northern California.  Major industries include petrochemicals
and primary metals (e.g., steel fabricators).  Although employment in
these industries has declined over the last two decades,1 the heavy
industrial sector is still among the largest in the county's economy.
Most of the industries served would have been located within 20 miles of
the proposed facility, and all within the nine-county San Francisco Bay
Area.

In addition to its hazardous waste processing and disposal operations,
IT Corporation is active in the transportation of solid and liquid
products and wastes and in heavy-duty cleaning of industrial tanks and
related facilities.  IT Environmental, a subsidiary of IT Corporation,
operates hazardous waste management facilities in Martinez and Benicia,
California (complementary facilities) and a hazardous waste collection
and transfer station near San Jose.  They are presently attempting to
site a hazardous waste management facility near Saugus (in Los Angeles
County).  As noted above, IT Environmental's hazardous waste operations
are thought—by Federal and state officials—to be among the best in  the
state, both in terms of the relatively sophisticated technology used and
the competence with which these activities are undertaken.

The proposed project site was located in the pastern portion of Contra
Costa County, in an area whose primary type of land use is agricultural.
The surrounding communities of Oakley, Brentwood, and Byron were small
farm communities with developing residential areas extending into the
farmlands.  The population of the City of Brentwood in 1975 was only
3,662;2 median annual household income was $9,778 in 1975, as compared
to  the Contra Costa County median of $15,026.3  xhe East County
Planning Area in which the facility would have been located contained
approximately 40 percent of the County's agricultural land.  During
recent years however, there has been a reduction in the acreage
 1
   One-factor  underlying  this  decline has  been the  difficulty  in
   siting  such industries  in the county  in recent years.   For  instance,
   an attempt, by Dow Chemical  to site a  major petrochemical  facility
   near  Pittsburgh  in Contra Costa County  was abandoned after  extensive
   public  debate and considerable  difficulty in obtaining  necessary
   permits.                                                  ,

   Contra  Costa County Planning Department,  Contra  Costa County - A
   Profile,  October, 1977.

   Ibid.
                            235

-------
devoted to agriculture in the area—farmland has been turned to
residential and recreational uses.  This trend is continuing.

III.   HISTORY OF FACILITY DEVELOPMENT AMD PUBLIC RESPONSE

In order to develop and operate a hazardous waste management facility in
California, at least three permits are needed.  These are:  1) land use
permit-, 2) Regional Water Quality Control Board Waste Discharge
Requirements (permit), and 3) Department of Health Services permit.  The
land use permit, which is issued by the local city or, in unincorporated
areas, county plannning board, certifies that development and operation
of the proposed facility would not conflict with existing land use or
land use plans.  In practice, it indicates that the facility has local
political support.  A significant factor in gaining this support is
facility compatibility with local land use.  This permit is a
precondition for the granting of the other two permits.   The decision of
the local planning board can be appealed to the local board of
supervisors.

The Regional Water Quality Control Board Waste Discharge Requirements
specify what kinds of wastes the facility may receive and what measures
must be taken to prevent groundwater pollution.  These requirements are
in effect a permit since they will not be issued if the geology and/or
hydrology of the site are inappropriate.  The Department of Health
Services permit is for the most part based on the existence of proper
procedures for above-ground handling of chemical wastes.  These
procedures must include a contingency plan in case of "an accident or
ace idental di scharge."*

In addition, two other permits are often required, depending on the
particular types of storage, processing or disposal of chemical wastes
that are proposed.  If hazardous wastes are to be disposed of with
municipal solid wastes, then the state Solid Waste Management Board must
grant a permit for the facility.  This permit regulates the disposal of
residential and commercial refuse so that nuisances are not created.
The power to grant this permit can be granted by the Solid Waste
Management Board to local political entities, such as the local city or
county government.

If some sort of evaporation, neutralization or incineration process (or
any other process which will produce a significant amount of atmosphere
emissions) is proposed, a permit will be required from the Regional Air
Pollution Control District.  Evaporation ponds, for instance, are
treated as emission points.  Depending on existing air quality in the
region, this permit can be very restrictive as to types of processes
   California Department of Health Services, Hazardous Waste
   Regulations, Chapter 2, Article 4, "Hazardous Waste Permit".
                             236

-------
and/or wastes accepted.  Permits may also be required from agencies  such
as the Coast Regional Commissions if the proposed site is located in any
of the areas which are under  their  purview.

The proposed IT Corp. facility at Oil Well required a land use permit
and permits from the Regional Water Quality Control Board, the
Department of Health Services and the Regional Air Pollution Control
District.  In this case, permits from the state Solid Waste Management
Board arid the Coast Regional Commission were not required.

In the late 1960's the zoning of property adjacent to IT Corp's, Antioch,
California facility was changed from heavy industrial to residential
despite IT Corp's opposition.  Subsequent to this change, housing
developments were built fairly close to the facility.  Public opposition
to the facility began, and increased as residential areas encroached
upon the site.  In 1970 the Antioch City Manager contacted IT Corp. and
requested that they consider moving to another site in order to avoid a
conflict with these developments.  Public opposition continued to mount
with the support of the local media.

During the early 1970's, then, IT Corp. began looking for a new site for
a hazardous waste management facility.  In June, 1971, they became
involved in an unsuccessful attempt to site a facility on a 480-acre
parcel of land in Ginochio, California.  This proposal — which involved
disposal of municipal as well as industrial wastes —; was ultimately
unsuccessful because it became entangled in a long series of hearings
and studies about the garbage disposal needs of eastern Contra Costa
County.

Renewed attempts to identify a new site to replace the Antioch site were
begun in late 1972/early 1973.  A number of possible sites in eastern
Contra Costa County were evaluated.   Parameters in this evaluation
included geology, access, site development and zoning, adjacent land
use, and distance to markets.  Six sites were thus selected for further
study.

On April 5, 1973, IT Corp. officials and members of the Contra Costa
County Planning Department staff toured these sites.   The planning
department, in a letter dated April 25, 1973,. identified two of these
sites as the "least objectionable".   One of these two was being held in
trust and was not available for development.   The other, the "Oil Well"
site, was ultimately leased by IT Corp. for the purpose of developing an
industrial waste disposal facility.   This lease was contingent upon IT's
obtaining the necessary permits for  this facility.   An application for a
land use permit for the proposed facility was submitted by ,IT Corp.  to
the Contra Costa County Planning Department on October 1, 1973.   More
than 25 letters from area industry — including one from the local Shell
Oil refinery — in support of this application were received by the
planning department during the next few months.
                              237

-------
IT Corp. submitted a preliminary Environmental Impact Report (SIR) on
the site to the planning department at the same time as the land use
permit application.  The planning department decided, however, that in
order to obtain an impartial evaluation of the environmental impacts of
the proposed facility it would be necessary to hire an outside con-
sulting firm to prepare the full EIR.  A consultant was hired by the de-
partment in January, 1974.  (The consultant's fee was paid by IT Corp.)
Also during January, a full-scale geologic investigation and report on
the site was completed by a consultant hired by IT; and IT filed for
Waste Discharge Requirements with the Regional Water Quality Control
Board in Sacramento.

In March 1974, the Regional Water Quality Control Board announced that
dumping of Group 1 liquid industrial wastes * at the IT Corp. Antioch
facility would be prohibited after October 1, 1974.  This of course
increased the pressure on IT Corp. to find a new site.  The Board also
issued tentative discharge requirements for the Oil Well site.  Final
discharge requirements could not be issued until IT Corp. received a
land use permit from the county.  However, the issuance of tentative re-
quirements was tantamount to the granting of Board approval of the site.


During the Spring of 1974, officials of IT Corp. gave presentations to
community associations such as Rotary in the Brentwobd area, stressing
the need for such facilities and IT's competence in operating them.

The EIR was completed in July, 1974.  It identified 21 adverse impacts
which it predicted would be associated with the development and oper-
ation of the proposed facility.  Major possible impacts included the
"eventual contamination of the groundwater in Lone Tree Valley and the
alluvial plain to the east", odors emanating from evaporation ponds and
biodegradation impacts, and "corrosion and crop damage from acidic
vapors from evaporation ponds".  The EIR also concluded that the oper-
ation of the proposed facility "will demand a level of capability in the
fire protection service that is probably beyond the resources of the
Brentwood (volunteer) Fire Department."
   Group 1 wastes are defined  to include those wastes which consist
   of or contain toxic substances.  Group 2 wastes consist of or contain
   chemically or biologically  decomposable material which does not
   include toxic substances or those capable of significantly impair-
   ing the quality of useful waters and includes municipal solid waste.
   Group 3 wastes consist entirely of non-water soluble, nondecomposable
   inert solids (California State Water Resources Control Board).  A
   Class 1 landfill can accept wastes in Groups 1, 2, and 3, a Class 2
   landfill Groups 2 and 3, and so on.
                               238

-------
IT Corp. officials subsequently responded to the EIR.  They noted that a
highly impenetrable layer of material underlay the site and that this
layer would severely limit if not eliminate the potential for ground-
water pollution; that plans for the site included berms around the
storage tank area and the placement of a positive hydraulic barrier
around the levees to detect and retain any sub-surface migration of
wastes;.and that the company would work with the local fire department
in developing an adequate system of men and equipment for fire •
prevention and response.                                        ' -'" ~

In late July, the IT Corp. Martinez facility was named by the Bay Area
Air Pollution Control District as the source of foul odors which had
intermittently plagued northern Contra Costa County.  IT Corp. officials
were quoted as blaming a mechanical breakdown for the problem. This
received extensive coverage in the local media, in particular in the
vicinity of the proposed site.

On August 23, 1974, the Planning Commission of the City of Brentwood
adopted a resolution opposing the proposed facility.  This was the first
of many such resolutions adopted by boards, commissions and
organizations in the Brentwood-Antioch vicinity.  The Brentwood City
Council, for instance, passed a resolution declaring its opposition on
September 10.  The resolutions cited the issues raised by the EIR and
preemption of local land use planning as reasons for the opposition. *•

The planning department staff recommended to the planning commission on
September 13 that approval of the land use permit, would be "premature",
and' that the application should be deferred until after the East County
Review  Committee had made its report.  This committee, which was made up
of local residents and officials, was at that time studying the general
land use plan of the eastern par.t of Contra Costa County.  If this
option  were not pursued, the staff then recommended that the application
should  be denied.

The first public hearing on the project was held five days later before
the Contra Costa County Planning Commission.  The purpose of this
hearing was to consider both the EIR and IT Corp.'s land use permit
application.

Approximately 250 people attended the hearing.  Speakers in favor of
granting the permit included representatives of local unions and
industry.  Residents from the Brentwood-Antioch area spoke against
granting the permit.  The planning commission decided to hold a second
public  meeting on October 1 to allow for further debate on the issue.

On September 27 the Regional Water Quality Board, in response to the
delay  in the land use permit application decision, granted IT Corp. a
   Although  the  proposed  site  was  outside  the  Brentwood city  limits,
   it  was  within the  area covered  by  Brentwood's  proposed  general  land
   use plan.  The  proposed future  land  use for the  site was residential.
                                239

-------
90-day delay in the closing of its Antioch facility.  However, it also
required that that site no longer accept any odor-producing wastes or
any acids greater than 15 percent concentration.

The second hearing on October 1 again focused on the EIR and the land
use permit.  Conflicting testimony was presented by experts for the two
sides.  The one important change was that the production division of
Shell Oil Company, who owned and operated a number of oil and gas wells
on the site (see above, Section II), indicated  that they might be op-
posed to such a facility in close proximity to  these wells, but that
they had not yet made a determination.  The EIR hearing was closed at
this meeting to give the planning commission staff 60 days to prepare
written answers to questions raised about the EIR.  The land use permit
hearing was continued until December 3 with IT  Corp's consent.  At the
end of this meeting the commission announced the receipt of a letter
from another waste disposal firm, requesting delaying the Oil Well de-
cision until a decision had been reached on the Ginochio site.  IT Corp.
officials later speculated that the purpose of  this request was solely
to attempt to defeat their proposal.  The request was subsequently de-
nied on the grounds that the Ginochio site proposal was no longer vi-
able.

The Shell Oil Company announced in late November, 1974, that it would
oppose the development of a hazardous waste management facility on the
Oil Well site.  A Shell official was quoted in  the Pittsburgh
(California) Post-Dispatch as saying that "a thorough investigation of
the Industrial Tank Inc. proposal... has disclosed that it would not be
compatible with the high pressure gas producing operations at the Brent-
wood Field site."

The final hearing on the land use permit application was held on De-
cember 3.  Again, expert testimony was provided on both sides of the
permit application issue.  Shell Oil officials  testified that a chemical
waste dump on the site would hamper their oil and gas drilling oper-
ations and that chemicals dumped might corrode  Shell wells and lines.
Furthermore, they stated that it was their position that Shell had ex-
clusive right to use the land under the  terms of its lease.  The plan-
ning commission then voted to deny the permit.  The main reason cited
was that the site was technically unsuitable.'

Shortly thereafter, on January 2, 1975, the IT  Corp. Antioch facility
was closed by the Regional Water Quality Control Board.  IT Corp. sub-
sequently indicated its intent to appeal the planning commission's de-
cision to the County Board of Supervisors.  However, in the face of
increasing opposition from local residents and  Shell Oil, the firm
withdrew its application and cancelled the appeal in May of 1975.  IT an-
nounced at the same time plans for upgrading and expanding its existing
Martinez site.
 IV.
CHRONOLOGY OF EVENTS
Late  1960's  — Zoning  of  property adjacent  to  IT  Corp.'s  Antioch
                facility is changed from heavy  industrial  to  residential.
                              240

-------
                Housing developments are later constructed close to the
                facility, and public opposition to its continued oper-
                ation develops.

 1970 — Antioch City Manager requests that IT Corp.  consider moving
         its operation to another site.

 June, 1971  — IT becomes involved in an ultimately unsuccessful attempt
               to site a facility in Ginochio,  California.

 Winter, 1972 — IT Corp.  search for a new site for a hazardous
                 waste management facility begins.

 April 5,  1973 — IT Corp.  officials and Contra Costa County  Planning De-
                  partment staff tour six proposed  hazardous  waste man-
                  agement  sites.                  ,

 April 25, 1973 — Letter  to  IT  Corp.  from the  Planning Department iden-
                   tifies  two "least objectionable" sites.

 October 1,  1973 — IT Corp.  submits an  application for a land use permit
                    for the "Oil Well" site  to  the  Planning Department.

 January 24,  1974  — IT Corp.  files  for  Waste Discharge Require-
                     ments  with  the  Regional Water Quality Board.

 March,  1974  — Regional Water Quality Board prohibits dumping
                of Group  1  liquid industrial wastes at IT
                Corp.'s Antioch  site after October  1,   1974;
                this  in effect closes the site as of that date.

 March 20, 1974 — Regional Water Quality Control Board issues tentative
                   discharge  requirements for the Oil Well site.   These
                   requirements cannot be finally acted upon until IT
                   Corp. receives a  land use permit from the county.

July  18, 1974 —  The  draft version  of Environmental Impact Report on the
                  proposed  facility, prepared by an independent en-
                  gineering consulting firm, is completed and released.

July 23, 1974 — IT Corp. Martinez facility is named  as source
                  of foul odors plaguing north Contra  Costa County.

August 23, 1974 — The planning commissioners of the  city of Brentwood
                   adopt a resolution opposing the proposed facility.

September 10, 1974 — Brentwood City Council passes a resolution de-
                      claring its opposition to the facility.

September 13, 1974 — The staff of the Contra Costa County Planning  De-
                      partment recommends that approval of  the land  use
                      permit  would be "premature" and that  approval  be
                      deferred,  or else denied.
                             241

-------
September 18, 1974 — The first public hearing on the EIR and the land
                      use permit is held before the Contra Cos.ta County
                      Planning Commission.  The hearing is continued un-
                      til October 1.

September 27, 1974 — Regional Water Quality Control Board defers clos-
                      ing of the Antioch site until January 1, 1975.
                      The board requires that the site not accept any
                      odor-producing wastes or acids greater than 15
                      percent concentration.

October 1, 1974 — Second public hearing on the EIR and the permit ap-
                   plication.  The EIR hearing is closed and the plan-
                   ning department staff directed to prepare answers to
                   questions on the EIR.  The hearing on the permit is
                   continued until December 3.

November 25, 1974 — Shell Oil Company announces that the proposed
                     facility is incompatible with the company's1 high-
                     pressure gas producing operations, and that it will
                     oppose the facility.

December 3, 1974 — Contra Costa County Planning Commission votes to
                    deny land use permit application; IT Corp. announces
                    it will appeal the decision to the County Board of
                    Supervisors.

January 1, 1975 — Antioch facility is closed.

May 20, 1975 — IT Corp. withdraws its application for a land use permit
                for the Oil Well site; cancels its appeal of planning
                commission denial of the permit; announces plans for up--
                grading and expanding its existing Martinez site.
V.
ATTEMPTS TO SECURE SUPPORT
Few attempts were made by IT Corp. to secure support for the Oil Well
facility.  These attempts include:

       o     Involving the County Planning Department in the initial
             site selection process.

       o     Requesting the support of the local industry and labor
             groups during the land use  permit application  evaluation.

       o     Presentations to community  associations (e.g., Rotary) in
             the Brentwood area stressing the need for such a facility
             and the  care with which it  would be operated.
VI.
SUMMARY EVALUATION
With the  exception of  IT  Corp. officials, the  consensus  of  opinion  on
                               242

-------
this siting attempt seems to be that the problem was not so much with
the siting process as with the site itself.  The site may well have been
technically suitable but it was, in a broad sense, politically un-
suitable.  The site was approximately five miles from IT Corp.'s Antioch
facility, which had already achieved a certain notoriety.

IT Corp. has indicated that its corporate philosophy at the time of the
siting attempt was to keep as low a profile as possible.  IT approached
the permitting process through official channels and the news media were
not informed of the intention to site such a facility nor of the
progress of siting*  Neither were any public information or
participation options considered, other than presentations to a few
selected community associations.

The public hearings on the EIR did provide substantial information on
the pros and cons of the facility to the interested public.  However, by
this time public attitudes toward the site were already fixed, and this
information had little if any effect on them.  The hearings allowed the
County Planning Commissioners to gauge the direction and extent of
public feeling on the issue, a not insignificant factor in their final
decision.  Thus, even though the proposed site was on unincorporated  .
land, local residents were,able to provide some meaningful input to the
Planning Commission decision.  Local public opinion was that they would
not have succeeded if they had not had Shell Oil Company on their side.

The issues and concerns raised by the public reflected those raised in
the EIR.  These are listed below.                                  ,

Site suitability - Questions about site suitability focused on the
impact of the facility and surrounding agricultural and residential land
uses, as well as on the permeability of soils underlying the site, and :
the likelihood of contamination of groundwater supplies.

Facility operations - Because of similar problems associated with other
IT-operated sites, odors- from the facility were a concern.  Air
pollution from evaporation ponds and other processes was also mentioned
as a possible adverse impact.

Access - Site access would have been along a minor two-lane rural road.
Fears were expressed about the possibility of spills.

Contingency plans - Particular concern was expressed over the presumed
inability of the local (volunteer) fire department to cope with the
fires at the facility.  This concern was based at least in part on
adverse experience with IT Corp.'s Antioch facility.

Land use planning - Although the site was outside the city limits of
Brentwood, it was cla'ssified as a future residential area in the
Brentwood proposed land use plan.  Local officials and residents saw the
siting attempt as an attempt to preempt local land use control.
                                243

-------
VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Only those who would have benefited from the facility (e.g., local
unions and-industry) accepted this particular facility, although nearly
all concerned claimed they were aware of the need for this type of
facility in Contra Costa County.  Factors leading to public opposition
included:

       o     Public recognition and/or perception of problems with IT
             Corp.'s Antioch and Martinez facilities.

       o     Proximity of the proposed facility to the Antioch facility.

       o     Lack of public information supporting the proposed
             facility.

       o     Efforts by Brentwood City Council and other local public
             bodies to organize public opposition.

VIII.  RETROSPECTIVE VIEWS

Facility opponents stated they would not have done anything differently.
An official of IT Corp., on the other hand, felt that the siting process
had two principal shortcomings.  The first was IT Corp.'s failure to
make substantive efforts to involve the public in the siting process
before a definite site was chosen and public opinion formed.  The second
was the California permit process.  He indicated that it would make more
sense to evaluate the site on technical grounds first and then, if the
site were  technically acceptable, to use this information as an input to
the final, political decision of whether to allow the facility to be
constructed on that site.  Currently, the political decision (which
seems to include the most opportunity for substantive public input)
precedes the technical decision.  In his mind, the key factors in siting
a facility are the developer's technical competence and his ability to
communicate this competence.
IX.
GENERAL COMMENTS
Industry and  local  officials were  united  in  their  feeling  that  there was
no need for EPA  to  play a role in  the siting process.  Negotiation,
mediation  or  arbitration were not  thought to have  any useful  role  to
play in this  process.  This is both because  no necessarily neutral
parties were  perceived to exist  and because  it was felt  that  the system
could be made to work properly without  this  (if  it did not already work
properly).
                                244

-------
                                PADRE  JUAN

                           VENTURA,  CALIFORNIA
I.
INTRODUCTION
The Ventura .Regional County  Sanitation  District  (VRCSD)  attempted  in
1974, for  the  third time  in  three  years,  to  site a landfill which  would
accept both hazardous wastes and non-hazardous solid wastes.   The
proposed site  was located in the area around Padre Juan  Canyon,
northwest  of the City of  Ventura.  After  an  Environmental  Impact Report
(EIR) was  prepared and  a  series of public hearings held, the  VRCSD Board
voted to abandon the siting attempt.

Rather than attempt to  develop support  for the facility  among
constituent groups which  could be  expected to support  it,  VRCSD's  effort
seemed to  have been directed toward alleviating  concern  about the -..
facility among the residents in the vicinity of  the proposed  site.
These efforts  were largely unsuccessful.  Local  residents  were able to
muster sufficient political  support to  defeat the  siting attempt.
II.
BACKGROUND INFORMATION
The proposed Padre Juan facility would have been located  in Ventura
County,, California, approximately 45 miles northwest of Los Angeles and
seven miles northwest of the City of Ventura.  The entire Padre Juan
Canyon area lies over the Ventura oil field, an active oil-producing
area.                                       ,

Access to the area is gained via U.S. Highway  101, to either  the Solimar
Beach exit or the Seacliff exit to Pacific Coast Highway  (old Highway
101).  At the tj.me of the siting proposal, the route to the area was via
the Padre Juan overcrossing of U.S. 101 to an oil company road.
However, the project as proposed would have included an interchange on
U.S. 101 which would have provided direct access to the facility.
Across U.S. 101 from the proposed site are a number of .expensive summer
homes which faced the Pacific Ocean.              .

The Padre Juan facility would have been owned• and operated by the VRGSD.
It was primarily intended to receive hazardous wastes from Ventura
County, although it was anticipated that it would have also served Santa
Barbara County (located directly to the northwest of Ventura County).
Ventura County is among the most rapidly growing counties in the nation.
The county population increased by 21.4 percent between 1970 and 1977.
Ventura County's Pleading source of income is still agriculture, which is
a source of some chemical wastes (e.g., pesticides).  Major industries  >
include electronics and other high-technology sectors. '
                                 245

-------
The facility would have included up to four separate disposal sites.
These four sites are discussed and compared in the Environmental Impact
Report (EIR) which was prepared for the Padre Juan facility.^  The
area, expected lifetime, and capacity of each site are shown in Table 1.

The permeability of the soil underlying these sites ranges from 10-3
to 10-5 cm/sec.  Average slope in the proposed landfill areas of the
sites ranges from 8 percent in Site 2 to 20 percent in Site 4.  The area
as a whole is located in Zone III (high severity) of the Maximum
Expectable Earthquake Intensity Region for California.  Sites 1 through
3 were covered with natural vegetation.  Site 4 was a highly disturbed
area polluted by oil sludge with large bulldozed areas, and covered by
degraded, non-native vegetation.

The Padre Juan facility was never designed since the site was abandoned
prior to this step in the process.  Nevertheless, the EIR does include a
general description of the processes that would have been used.  The
facility would have been a Class I sanitary landfill,2 very similar to
the existing VRCSD facility in the, Simi Valley.  Three disposal methods
were in use at the latter facility; soil blending, soil spreading, and
pit methods.  Oily wastes, aqueous liquids, and semi-liquid wastes would
have been spread on and blended with soil.  All other wastes would have
been buried.  Containers of less hazardous wastes would have been
emptied into a prepared pit, while more dangerous, containerized wastes
would have been placed in such a pit directly.  These materials would
then be covered by three to four feet of soil.  Hazardous wastes would
not have been mixed with Group 2 wastes^ (e.g., municipal solid waste)
as is currently the practice in some other California sites.  Group 2
and 3 wastes would be disposed of separately at this facility.  It is
estimated that the facility would have received on the order of 40,000
gallons per day of liquid Group 1 wastes.  These wastes would have
reportedly been similar to those accepted at the Simi Valley facility,
of which approximately 70 percent was paint sludge and purifax sludge.
   Ventura Regional County Sanitation District, Padre Juan Canyon
   Class I Sanitary Landfill, Ventura County, California; Final
   Environmental Impact Report and Technical Appendices.
2  „
    Class I disposal sites are those at which complete protection is
   provided for all time for the quality of ground and surface waters
   from all wastes deposited, therein, and against hazard to public
   health and wildlife resources".  California State Water Lawsj
   Subchapter 15, Article 1.

   Group 1 wastes are defined to include those wastes which consist
   of or contain toxic substances.  Group 2 wastes consist of or.
   contain chemically or biologically decomposable material which does
   not include toxic substances nor those capable of significantly
   impairing the quality of useful waters and includes municipal solid
   wa'ste.  Group 3 wastes consist entirely of non-water soluble,
   nondecomposable inert solids (California State Water Resources
   Control Board).       '•..'.
                               24€

-------
                                Table 1

                    Site Area,  Lifetime and Capacity
  Site
Area
Lifetime
1
2
'3
4
28
135
51
125
acres
acres
acres
acres
1
25
10
25
year
+ years
+ years
+ years
        Capacity

    200,000 cubic yards

250,000,000 cubic yards

  4,000,000 cubic yards

 26,000,000 cubic yards
Sites 1 and 2 were within the drainage of the Padre Juan Canyon;  Site 3,
part of Jovan Canyon to the westj  and Site 4 in Faria Canyon to the
east.  All four sites are within two miles of the Pacific Ocean.
Although so close to the coastline, the area is an oil producing area,
and in this sense was in industrial use.  There were no producing wells
within any of the sites proper, but wells did border each of the sites.

Other than these oil-producing operations, land immediately adjacent to
the sites was undeveloped.  However, land immediately to the north of
the area was in agricultural use,  and land along the coastline in
residential use.
                              247

-------
 The VRCSD proposed to develop Site 1 as a short-term facility to be
 utilized while one of the larger sites was being developed.   Ultimately,
 three or all four of the sites would have been developed.  However, the
 sequence of development was not determined prior to the abandonment of
 the siting attempt.

 III.    HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

 In order to develop and operate a hazardous waste management facility in
 California, at least three permits are needed.   These are:  1) land use
 permit;  2) Regional Water Quality Board Waste Discharge Requirements
 (permit); and 3) Department of Health Services  permit.   The  land use
 permit,  which is issued by the local city or, in unincorporated areas,
 county planning board,  certifies that development and operation of the
 proposed facility would not conflict with existing land use  or land use
 plans.   In practice,  it indicates that the facility has local political
 support.   A significant factor in gaining this  support is facility
 compatibility with local land use.   This permit is a precondition for
 the granting of the other two permits.   The decision of the  local
 planning  board can be appealed to the local board of supervisors.

 The Regional Water Quality Control Board Waste  Discharge Requirements
 specify what types of wastes the facility may receive and what measures
 must be taken to prevent groundwater  pollution.   These  requirements  are
 in effect a permit since they will not be issued if the geology and/or
 hydrology of the site are inappropriate.

 The Department  of Health Services  permit is  for  the most  part  based  on
 the existence of proper procedures for aboveground handling  of chemical
 wastes.   The procedures  should include  a contingency plan for  "an
 accident  or accidental  discharge."1

 In addition,  two  other  permits are often required,  depending  on the
 particular  types  of storage,  processing  or disposal  of  chemcial  wastes
 that are  proposed.   If hazardous  wastes  are  to be disposed of  with
 municipal  solid wastes,  then  the  State  Solid Waste Management  Board
 grant a permit  for  the  facility.   This  permit regulates  the disposal of
 residential  and commercial refuse  so  that nuisances  are not created.
 The  power  to grant  this  permit can be granted by  the Solid Waste
 Management  Board  to local political entities, such as the local city or
 county government.                            .

 If some sort  of evaporation, neutralization  or incineration process or
 any other process which will produce a significant amount of atmospheric
 emissions is  proposed, a  permit will  be required  from the Regional Air
Pollution Control District.  Evaporation ponds,  for  instance, are
permitted as  emission points.  Depending on  existing air quality in the
region, this permit can be very restrictive as to types of processes
and/or wastes accepted.
   California Department of Health Services, Hazardous Waste
   Regulations,  Chapter 2, Article 4, "Hazardous Waste Permit".
                                248

-------
Permits may also be required from agencies such as the Coast Regional
Commission, if the proposed site is located in any of the areas which
are under their purview.

The Padre Juan facility would have required permits or approvals from
the following agencies:                                         ,
       o
       o
       o
       o
       o
       o
       o
       o
Ventura County Planning Commission
Ventura County Board of Supervisors
Regional Water Quality Control Board
California State Department of Health Services
California State Solid Waste Management Board.
South Central Coast Regional Commission
California State Highway Commission
California State Utilities Commission
The approval of the last two agencies would have been required for the
VRCSD to construct an interchange, which would have in turn necessitated
the moving of a railroad right-of-way.  In the case of the Padre Juan
facility, a permit from the Regional Air Pollution Control District
would not have been required.

The responsibility for disposal of solid wastes in Ventura County was
transferred by the County Board of Supervisors to the VRCSD on July 1,
1972.  As noted above, Ventura County has been one of the fastest
growing areas in the country over the last deoade and the VRCSD
recognized that it faced a critical solid waste problem.  In addition,
it was at that time anticipated that the Santa Clara landfill in Ventura
County—which accepted Group 2 and 3 wastes—would be closed in 1976 in
compliance with a Ventura County ordinance which prohibits renewal of
land use permits for privately operated landfills.  The only existing
site for the disposal of Group 1 (hazardous) wastes was a landfill
located in the Simi Valley, over 30 miles from the Ventura City area.
Therefore, the VRCSD felt it: necessary to site a new facility for the
disposal of both hazardous and other wastes in the latter area.

In the summer of 1972, the City of Ventura and VRCSD filed for and
received a grant from U.S. EPA to develop a model sanitary landfill.
However, the site chosen for, this landfill—known as the Lake Canyon
site—was shown to have environmental problems that could not be
mitigated.  In particular, trucks going to and from the facility would
have had to travel through a residential area and by a school.  As a
result, there was intense public opposition to this site.  The
opposition was initially expressed at meetings held by the VRCSD to
receive local public input to the siting process.  Local elected
officials played a significant role in having this siting attempt
abandoned.  This was accomplished when the City of Ventura, the. "Lead
Agency" for the EPA grant, decided to abandon it.  ,

The VRCSD then retained a consulting firm to evaluate other potential
landfill sites in the vicinity of the City of Ventura.  The report
prepared by this consultant indicated that a site in Welden Canyon would
                              249

-------
 be the most suitable for use as a landfill for hazardous and municipal
 solid wastes.  However, a subsequent investigation by VRCSD revealed
 that the area had "groundwater development potential and.;.was
 potentially suitable for housing".1

 It was therefore decided to remove this site from consideration.  The
 search for sites was then moved away from the City of Ventura to the
 coastal area northwest of the city to avoid conflicts with existing
 residences and residential development.  This decision was made in-house
 at VRCSD and was not subject to public review.  Officials of VRCSD have
 indicated they felt that the proposed landfill would not be incompatible
 with existing oil producing activities.  The Padre Juan Canyon area was
 identified as a potential site, and studies of its geological and
 geotechnical feasibility were conducted for VRCSD by consulting firms.
 These studies indicated that there were suitable sites within the canyon
 area for a Class I landfill.

 During the Spring of 1974,  while the search for a site along the north
 coast was still going on,  VRCSD sought a citizens group to talk to.
 This  was done in order  to  try to head off public opposition,  a lesson
 learned during the Lake Canyon siting attempt.  During the Lake Canyon
 attempt it was found to be  very difficult to  elicit  public concerns
 outside of the formal and often adversarial public hearing process.
 However,  there was no citizens  group in the Padre Juan area.   Therefore,
 VRCSD called a public meeting at a local school.  ' At this meeting they
 described the siting process and the type of  facility they were trying
 to site,  and invited those  in attendance to form a liaison committee.
 Such  a  committee  was formed,  made  up entirely of  local residents.

 In a  short  time,  however, the liaison committee became the  focus  of
 opposition to  the committee.  Led  by a woman  who  was  a substantial
 landowner in the  area,  the  commitee  marshalled the support  of  both
 summer  and year-round residents  of  the area.   The committee did not
 attempt  to  negotiate with the VRCSD.   Instead, it took its  case directly
 to county elected officials,  some  of whom had homes  in the  vicinity of
 Padre Juan  Canyon.   Due  in  part  to the  affluence  of the affected
 community,  the committee-was  eventually very  successful in  enlisting  the
 support of  these  political  leaders in  their opposition  to the  facility.

 Because of  the scope of  this  project, an Environmental  Impact  Report was
 required  (as per  the California Environmental  Quality  Act of 1970).  On
 June 20,  1974, VRCSD announced that  it  had hired  a consulting firm to
 prepare this EIR.  Analyses of the environmental  impact of  the proposed
 facility were carried out during June,  July and August, 1974.  The first
 Public Opportunity meeting—to receive  public  input and comment on the
 proposed site and facility—was held on  July 17.   The reaction of the
 public, and of local  officials to all four proposed sites was entirely
negative.  Public concerns expressed at  this meeting included the wisdom
of selecting a site  in a seismically sensitive area so near the ocean;
   VRCSD, Padre Juan Canyon final EIR, ibid.
                             250

-------
odors, dust and litter from the facility; the possibility the facility
would attract scavengers (i.e., seagulls and rodents); traffic; and the
effect on the quality of life in Ventura County, especially in terms of
induced development.  Other problems frequently mentioned were the
possibility of contaminating the ocean and the visual impact of the
facility on what is otherwise a relatively unspoiled area.  There was
also considerable feeling that the problem of hazardous waste disposal
could be mitigated or avoided if a comprehensive resource recovery
program were established.  Finally, there was opposition to accepting
wastes from neighboring Santa Barbara County.   A second Public
Opportunity meeting was held on August 22.  Again, no support for these
sites was expressed and the same public concerns were voiced.

The draft EIR was submitted to the VRCSD board on September 26.  Adverse
impacts identified in the EIR included the production of noxious odors
and gases from fill-areas, particularly from Site 4; that an area of
Site 4 would be visible to some residents along pld Route 101 and to
traffic on U.S. 101; that there would be .an increase in truck and auto
traffic,(if the interchange directly to the facility were -built, this -
increase would be very small); and that there would be an increase in
erosion, runoff and dust from the canyons.  The VRCSD Board held a
public hearing'on the EIR on November 14.  All 15 speakers—all of whom
were residents .from the Padre Juan vicinity—at .this hearing spoke
against the use ,of these sites as landfills of any type.  Letters from
the public received by the board were also in opposition to the
facility..  Concerns expressed included the facility's,impact on the
aesthetics of the area and the adverse impacts projected in the EIR.
However, comments from state agencies on the EIR were generally
favorable, in that  they concurred with the findings.  The only
criticisms of the report were' in effect requests for more information.

At the November 14 meeting the Board deferred its decision on whether or
not to go ahead with the facility until Deconber 12 to give the    ,
consultant time to respond to comments on the draft EIR.  The December
12 meeting was later postponed to January 30, 1975 to give the
consultant more time to respond to these comments.  In response to
public and official comments, the final EIR proposed  several changes in
the project.  These included:  1) limitation of all project operations
to the area more  than 1,000 yards from the coast;! and 2) construction
of an interchange on Route 101 to provide direct access to the site.
However, these changes did not materially affect the  level of opposition
to the facility.  The Board held its second hearing on the EIR on
January 30,  1975..  This hearing attracted about 175 people, a large
percentage of whom  were residents from the Padre Juan Canyon vicinity.
It was.reported in  the local press  that the only people to voice support
for the facility  were VRCSD staff members.  Concerns  expressed by the
public were generally the  same as at the  first hearing — aesthetics,
environmental pollution, and traffic impacts in particular.
  To  limit  the  intrusion of  the  facility  into  the  Coastal  Zone.
                            251

-------
The Board  then voted  to conclude  the  public  hearing but  to continue  the
meeting until February 13 to allow themselves time to discuss the mat-
ter.  On February  13, the Board voted (13-8) to abandon  the  proposed
site.  One particular reason for  the  outcome of the vote was that the
three members of the  County Board of  Supervisors on the VRCSD Board were
all opposed to the project.  These three members constituted a majority
of the County Board of Supervisors.   They would have been able to deny
the project its land use permit even  if the  Planning Commission had de-
cided to grant one.
IV.
CHRONOLOGY OF EVENTS
July 1, 1972
         Ventura County Board of Supervisors transfers re-
         sponsibility for county solid waste to VRCSD.
1973 — VRSCD tries but fails in two hazardous waste facility siting at-
        tempts.                                        .

Spring, 1974 — VRCSD holds public meeting in north coast area to de-
                scribe the siting process.  Assists in the formation of
                liaison committee.  Committee subsequently becomes
                source of opposition to the facility.

June 20, 1974- — VRCSD announces it has hired an engineering consulting
                 firm to prepare an EIR for the Padre Juan sites.
July 17, 1974
          First Public Opportunity meeting held by engineering
          consulting firm to receive public input and comment.
          The reaction to the facility is entirely negative.
August 22, 1974 — Second Public Opportunity meeting is held with same
                   result.

September 26, 1974 — Draft EIR is submitted to the VRCSD board.

November 14, 1974 — VRCSD board holds hearing on draft EIR.  All 15
                     speakers speak against the proposed site.  Decision
                     on site is deferred to December 12 to give en-
                     gineering consultant time to respond to comments.

December 12, 1974 — Meeting postponed to January 30, 1975 to give con-
                     sultant more time to respond to comments.

January 30, 1975 — VRCSD holds second hearing on EIR.   Hearing is
                    well-attended.  Of all speakers, only VRCSD staff
                    support the facility.  Board votes to conclude hear-
                    ing but to continue the meeting until February 13 to
                    allow themselves time to disucss the matter.

February 13, 1975 — VRCSD board votes, 13-8, to abandon the proposed
                    site.
                                252

-------
V.
ATTEMPTS TO SECURE SUPPORT
As noted above, the VRCSD's efforts were directed more  towards
alleviating concern about the facility among residents  in the vicinity
of the proposed site than to developing support for it  among other
concerned groups.  These efforts included:

       o     The public meeting held in Spring, 1974 for residents in
             the vicinity of the proposed site to:

             -     describe the proposed facility and the siting
                   process; and
             -     assist in the formation of a citizen liaison
                   committee.
VI.
o     Public Opportunity Meetings held to receive public input
      and comment on the site for inclusion in the EIR.

o     Individual responses were sent to all communications
      received in regard to the facility.

SUMMARY EVALUATION
Ultimately, insufficient support for the Padre Juan site was generated,
yet while the actual attempts to secure support for the facility cannot
be faulted, they did not go far enough.  The prevailing mood in the
county at that time was not at all favorable for siting this facility,
as is evidenced by the failure of two'. previous siting attempts.  In
particular, it appears that not enough effort was made to secure support
for the facility from either the industries which would use it or from
county residents who did not live in proximity to the proposed site.
One such person—who was involved in the opposition to the Lake Canyon
site—noted that while she had been in favor of the Padre Juan site, she
had not become involved and had not attended any of the public hearings.
No explicit attempt was made to involve such interested persons.
Although technical issues were raised by the EIR and in the public
hearings, the ultimate-decision not to pursue this siting attempt was
based on political rather than technical factors.  The failure by VRCSD
to marshal the support of those of its constituencies who had reason to
favor this site (i.e., industry and non-abutters) enabled the residents
of the Padre Juan Canyon area to gather sufficient political support to
defeat the, project.  ..;•.-•'

During the series of public hearings, a -number'.of issues and concerns
were raised by the public.  These are summarized below.

Site suitability - Particular concern was expressed at the selection of
a site so near the coast.  Aspects that were frequently mentioned were
the possibility of contaminating the ocean and the visual impact of the
facility on what is otherwise a relatively unspoiled area.  Another
issue was the technical suitability of the site itself.  Here concern
was expressed about the likelihood of waste materials leaking out of the
facility, especially given the possibility of a severe earthquake in the
area.

                             253

-------
 Facility Operations - Odors, dust and litter from the facility were a
 concern, as was the possibility that the facility would attract
 scavengers (i.e., seagulls and rodents).  Traffic induced by the
 facility—as well as the attendant noise and air pollution effects—was
 also an issue.

 Quality of Life in Ventura County - The public, and especially local
 residents, expressed concern about the effect the facility would, have on
 the quality of life in Ventura County.  Their perception was that this
 quality of life was strongly tied to the relatively underdeveloped state
 of that part of the county and the lack of environmental pollution.
 They expected the proposed facility to increase development and to
 pollute the environment.

 Resource Recovery - There was considerable public feeling that the whole
 problem of waste disposal could be avoided if a comprehensive resource
 recovery program were established.

 VII.    FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

 The following were major factors leading to public opposition to the
 proposed site.

        o     The proximity of the site to  the Pacific Ocean and to an
              area of expensive homes.
       o

       o

       o
      Failure  of  two  previous  siting  attempts.

      Location of  the site  in  an  area of high seismic activity.

      The public  expectation that the site would accept wastes
      from Santa Barbara County.
VIII.  RETROSPECTIVE VIEWS

Area residents' comments on the siting process were generally consistent
with their satisfaction with the result of the siting process.  The only
concern expressed was with the VRCSD for even attempting to site a waste
disposal facility in what they perceive as a sensitive area.  An
official with the Regional Water Quality Control Board noted that there
had been better sites than Padre Juan available to VRCSD at the time,
from both technical and public relations standpoints.  However, the
Padre Juan site was chosen because it would have been less costly to
develop than the alternative sites.
IX.
GENERAL COMMENTS
The VRCSD general manager stated that siting hazardous waste facilities
had become sufficiently difficult that the state or federal governments
would have to at least own, if not operate them.  He felt that rather
than trying to purchase new sites, a preferable location would be
somewhere on the tremendous amounts of land already owned by government.
                            254

-------
There are, he felt, a number of infrequently mentioned factors which are
important in finding a truly acceptable site.  These are:  1) access by
rail, since this has the potential to be the safest way of transporting
hazardous wastes; and 2) more use of resource recovery to reduce the
quantities of wastes which are disposed of.

Limiting, at least initially, the types of hazardous wastes accepted at
a new facility was mentioned as a possible strategy for gaining public
acceptance.  Relatively less hazardous waste would be accepted during
the first' few years of facility operation. -Only then, when the local
public presumably has confidence in the facility, will more hazardous
waste be accepted.                                             ,

-------
                 SCA CHEMICAL WASTE  SERVICES  INCORPORATED

                          MODEL CITY,  NEW  YORK
 I.
INTRODUCTION
 Since  1972 a hazardous waste  facility, now  owned by  SCA  Services, has
 operated  in Model  City, New York.  While  the  facility has expanded  its
 operations over the years, the basic technologies — landfilling,
 treatment, and storage — employed at  the site have  not  changed since
 operations began.  The Model  City facility  replaced  an earlier, similiar
 facility  located in Blasdell, New York, some  30 miles to the south.

 The facility was sited and began operations without  opposition.
 Beginning in 1973  area officials and residents began to  raise concerns
 about  on-site operations and  spills from  trucks transporting waste  to
 the facility.  Concerns have  evolved into opposition and a substantial
 group  of  local residents and  officials appear to be  unalterably
 committed to closing the facility.

 During the seven years of the facility's  operation a variety of attempts
 have been made to  provide public information, to solve problems giving
 rise to opposition, and to address in other ways public concerns.
 Although  there is  widespread  acknowledgement  of some changes for the
 better, these changes have not substantially  altered the positions held
 by opponents.
II.
BACKGROUND INFORMATION
The Model City facility is located a few miles west of Ransomville, New
York within the Towns of Porter and Lewiston.*  Prior to its develop-
ment as a hazardous waste facility, the site was federally owned and
known as the Lake Ontario Ordinance Works.  It was used for research
purposes by Olin-Mathison as a part of the Manhattan Project until the
1960s.  The resulting radioactive contamination precluded any use of the
site until a government "clean-up" effort reduced contamination to a
level acceptable for industrial use.  Much of the surrounding land
remains in the hands of the federal government.  Abutting the site are a
number of government or government-sponsored facilities including a
tower immediately to the south which contains the world's largest
concentration of radium.  (The tower is reportedly leaking radioactivity
and is a source of concern to area residents and officials.)  The
closest non-industrial uses are a public school complex and scattered
residences within a mile and one-half of the site.
   In New York, the town is the jurisdictional level immediately
   below that of the county.  As in a township, residents of a town
   elect a board of supervisors and the town government provides some
   basic services (e.g., sewers) to its residents.
                             25B

-------
Access to the site is by a,two-lane road and the site is about five
miles from the Robert Moses Parkway, a limited access divided highway.
The site is also served by a rail spur; however, rail service was
discontinued in 1978 because of track deterioration.

SCA environmental officials characterized the hydrogeolbgy of the
developable portion of the site as good.  (They indicated that a maximum
of 200 acres would be developable.)  An environmental assessment1 of
the site listed a range of permeabilities for jLn situ soils at levels
significantly more permeable than the pending RCRA standard.  The site
is also traversed by Four Mile Creek which empties into Twelve Mile
Creek and Lake Ontario.  Both creeks are subject to intermittent flows
particularly during the dry summer months.

The facility provides  treatment, processing, and disposal services.
There are seven existing landfills, a number of which are closed, as
well as a proposed eighth  landfill.  Because of the permeability of in
situ soils, SCA uses a compacted clay liner (minimally two-feet of
10~7 cm/sec clay) underlain by a Hypalon liner.2  A leachate
collection is installed above the clay  liner.   SCA staff estimated that
developable landfill capacity could have a remaining life of  20 to 25
years.

Treatment facilities are primarily designed to  handle aqueous waste
streams.  Facilities for the distillation of  solvents and for fuel
blending are also on-site.  There are  five lagoons  for the  storage of
treated  liquid  effluent.   According  to a Niagara County Health
Department official, SCA is currently  storing about 90 million gallons
of effluent  suitable  for discharge.  Also on-site  are a  temporary drum
storage  area and  a laboratory  for analysis of incoming wastes.   SCA also
operates a waste  hauling service and,  according to  the  draft EIS,  80
percent  of accepted  wastes are  hauled  by SCA trucks.  Provisions for
post-closure care will follow  applicable  state  or  federal  regulations.

The facility accepts  a broad  spectrum  of hazardous  wastes.   Specifically
 excluded,  however,  are shock-sensitive, radioactive,  flammable  (unless
capable of  being  blended  for  fuel),  and extremely  hazardous wastes  such
as dioxin.   These wastes come  from a multi-state region  as  well  as  the
 province of  Ontario.   According to the draft EIS,  1.7 percent of  accepted
 wastes are generated in the Erie-Niagara  counties  area,  42 percent
 within New York state, and the remaining  58 percent from out of  New York
 state.
    Draft Environmental Impact Statement for a SCA Chemical Waste
    Services, Inc. Facility in Model City, New York, prepared by Fred C.
    Hart Associates, Inc. for the New York Department of Environmental
    Conservation, Region 9 Headquarters on behalf of SCA Services,
    Boston, Massachusetts, February 27, 1979.

    Opponents claim that the earliest landfills, developed prior to
    SCA's ownership, are unlined.
                            257

-------
 The Model City facility is but one of four hazardous waste facilities
 owned by SCA Services of Boston,  Massachusetts.   SCA staff estimated
 permanent employment at Model City at 60 to 75 workers.   The number of
 workers increases significantly in the summer when soil  is neither
 frozen nor so muddy as to restrict work on the site.  SCA's other
 hazardous waste facilities are in Illinois, New Jersey,  and South
 Carolina.  SCA is the third largest waste services company in the nation
 and reported total revenues of over $180 million in fiscal 1978.

 Model City is located in northern Niagara County (estimated 1976
 population,  240,000).  That section of the county is relatively rural in
 character and historically has been a farming area.   More  recently it
 has developed residentially as employees from Niagara Falls have  moved
 into  the  area.   Model City is  within ten miles of Niagara  Falls and
 within 25 miles of Buffalo.  While Niagara Falls has been  linked
 historically to the beauty of  American and Horseshoe Falls  and  the
 attendant tourist industry,  the city is a major  manufacturing center of
 chemicals, electrical machinery,  and paper products.   Together  with
 Buffalo,  the entire metropolitan  area is the  second largest in  New York
 state.  As such it is the  major trade,  service,  financial,  cultural  and
 transportation center for  western New York and southeastern Ontario.   In
 recent  years  Love Canal  and  other less  publicized  hazardous  and radio-
 active  waste dumps have  made area residents extremely  sensitive to the
 dangers of improperly disposed wastes.

 Ill-    HISTORY OF FACILITY  DEVELOPMENT AND PUBLIC RESPONSE1

 When originally sited in the early  1970s  the  facility was subject  to
 local zoning  and state health  department  regulations enforced by  the
 Niagara County  Health Department  (NCHD).   The state Department  of
 Environmental Conservation (DEC)  was  formed in 1972 and began issuing
 permits for waste  management facilities in  1973.   In 1977 these
 regulations were revised,  in part to  address more  specifically  hazardous
 waste.  As a result,  existing hazardous waste management facilities were
 required  to apply  for new, more restrictive permits.

The Model City  facility is subject  to  the latest DEC permits (there are
separate construction and operation permits).   Because of the facility's
   The history of facility operations and the public and regulatory
   response to those operation is one that has become increasingly
   complicated.  To clarify this flow of events, a number of incidents
   have not been described in this section; these generally are
   spills either at the site or on roads leading to the site,  some
   smaller fines imposed by DEC as a result of these spills, and tactics
   considered but not actively pursued by opponents.  The implications
   of these omissions are subsumed by other events described in this
   section.
                            258

-------
need for discharging treated effluent and due to other peculiarities of
the site and facility operations (addressed later in this section) a
number of other permits or approvals are required.  As listed in the
draft EIS, these include a U. S. Corps of Engineers dredge and fill
permit, state certification that no water quality standards are
contravened during construction of the eighth landfill, several permits
from DEC and others from the state transportation department in
connection with installing a pipe to discharge into the Niagara River,
and three local permits.  Local permits have been the subject of
extensive legal action (as will be described) and it is unclear if all
local, permits would be required.                       ,

The existing Model City facility replaced a similar facility located in
Blasdell, New York just south of Buffalo.  According to local papers,
the facility was the brainchild of two Buffalo area men with extensive
backgrounds in chemical manufacturing.  'These men founded Chem-Trol
Pollution Services, Inc. in  1969 with the concept of recovering valuable
materials from waste streams, destroying the remaining hazardous wastes,
and burying the innocuous residuals.  The 20-acre Blasdell  site was
purchased in August 1969, and initial operations began in July, 1970.

The Chem-Trol facility operated at Blasdell for almost two  years; that
period was marked by a growth  in operational capabilities and  in volume
of business.  Incrementally, facilities  for thermal oxidation  (i.e., an
incinerator), waste neutralization,  the  removal of metals from wastes,
the positive control of salts resulting  from treatment procedures (i.e.,
impoundments), and  laboratory  analysis were added.  Because there was  a
need to  stockpile an inventory of wastes, lagoons and  storage  tanks  were
added.   During  this period  employment grew from five  to  35  workers.

The operation of',the Chem-Trol  facility  in Blasdell did:not proceed
without  public notice.  Opponents of the Model City facility,  citing
local  officials  in  the Blasdell  area, and  the  local press/reported  that
the facility on numerous  occa.sions operated in violation of applicable
environmental, regulations and  that  six.formal  pollution  complaints  were
lodged.   In July,  1972, several hundred  drums  exploded and  burned at the
site.   Area residents  reportedly  feared  that  the  explosion would  lead to
pollution of an  area creek.  As late as  August,  1978,  (over six years
after  closure),  residents complained of  odors  from  the site and
expressed skepticism about  claims that  wastes  buried  on-site were
neutralized.

By late 1971 Chem-Trol's  growth led company  officials to seek another,
larger site.   According  to  an  article  in the  Buffalo  Courier-Express,
"Chem-Trol officials with the help of the Army Corps  of Engineers
surveyed several  sites.   In early 1972 the  General  Services
Administration (GSA)  declared the Model City site surplus  property.
                             259

-------
 According to newspaper accounts and those interviewed1,  the selection
 of the Model City site was based in part on.its size,  its hydro-
 geological characteristics, and its relative isolation.   Chem-Trol
 purchased 240 acres of land and in February,  1972,  closed the Blasdell
 facility and began to move to the Model City site.

 When the Model City facility was developed few regulations applied.   Be-
 fore GSA declared the site surplus federal property, the Atomic Energy
 Commission stipulated that, because of radioactive  contamination on-
 site,  the property would  be restricted to relatively inactive uses;   The
 zoning status prior to Chem-Trol's purchase was industrial;  thus the
 proposed industrial use was not out of conformance  with  local reg-
 ulations.   The major regulatory action was conducted by  NCHD which at
 that time implemented the state health department's sanitation code reg-
 ulations for waste facilities.   Chem-Trol submitted its  plan for de-
 veloping the facility to  NCHD.   That plan called  for waste water treat-
 ment,  secure landfilling,  recycling of waste,  and waste  disposal via
 fuel blending.  At that time Chem-Trol had arranged for  the  lease of
 tanks  to store liquid wastes prior to their treatment.   The  original
 plan also  included an incinerator,  but this operated for only a  short
 period before it  was closed because of air pollution problems.   NCHD  re-
 view of  the  plan  included a review by the Town of Porter which wrote
 that it  had  no objections to the proposal.  NCHD  then granted a one-year
 permit for 1972.   In 1973  NCHD  renewed the  permit for an additional
 period of  one year.

 In May,  1972 the  Model  City facility began operations after  investing
 about  $2 million  in land and equipment.   For more than a  year  the facil-
 ity  operated without  particular concern on the  part of the public.  Con-
 tinued growth led  to  expansions  in  employment  so  that by  late  1972 there
 were 80  workers, more than double  the  number when Blasdell closed.

 The  lack of  concern during  this  period appears  to have stemmed from a
 lack of  any  noticeable operational accidents and a perception of the
 facility as  a resource recovery  and  reclamation operation, not a land
disposal operation.  While land disposal has always been part of the
 facility's operations, area  residents  claim that  the higher costs of re-
covering and treating hazardous wastes led Chem-Trol to change
   The original founders of Chem-Trol are no longer associated with
   the Model City facility.  Some of those key figures subsequently
   founded a waste service company in Niagara Falls, a subsidiary of
   which operates the only other DEC-permitted hazardous waste
   landfill in New York.  As of April, 1979, that company was under
   attack from local officials and citizens.  Concerns had been raised
   over the hazardous waste landfill and charges had been made that the
   company was trying to monopolize solid waste collection in the
   Niagara Falls area.   The latter charge stemmed from the company's
   contract with Hooker Chemicals to provide solid waste for a planned
   Hooker waste-to-energy recovery plant.
                             ,360

-------
operations.  Consequently there was an increased use of landfilling
contrary to original plans and intentions.  Press coverage of«. the
facility during this initial period was quite favorable and focused on
the recycling of wastes and the destruction of the hazardous residuals.
Chem-Trol officials were quoted as saying that their treatment and
processing procedures resulted in "no effluent whatsoever..." arid that
the only substances leaving the site were saleable residues, steam, and
carbon dioxide.. The solid remnants remaining after treatment were
buried in "scientific landfills"  developed according to a proprietary
process.  Company officials claimed "zero ground percolation."  The
articles clearly portrayed Chem-Trol as an environmentally innovative
company which provided alternatives to the dumping of wastes on land or
into waterways.                                                   •

The initial response to the facility was apparently predicated.on this
image of recycling and recovery.  The then president of Chem-Trol made
presentations to local officials during this period and reportedly
stressed the recycling aspects of the facility.  A Lewiston town
supervisor indicated that at that time recycling was ranked with
motherhood and  that the general response to recycling was very positive.
A  Porter town supervisor  indicated that the return of that land to local
tax roles was viewed as a benefit by the town and a reason for the early
favorable  response.

In 1973 Chem-Trol was bought by SCA Services of Boston, Massachusetts.
With this purchase  Chem-Trol became an SCA subsidiary and retained its
•original management staff.

Local attitudes began to  shift  in September of  1973.  That month  piles
of salts generated  by operations were discovered by local officials.
The salts  were  reportedly haphazardly stored and had resulted  in  the
destruction of  trees and  other  vegetation.  While the piles of salt were
the focus  of  concern, a Lewiston official also  charged  that chemicals
had been dumped in  the wrong places.  Reportedly Chem-Trol made no
effort  to  clean up  the salts and the Lewiston  town board  threatened the
firm with  a lawsuit to force a  clean-up.

The following spring a spill in Four Mile Creek resulted  in a  fish kill.
In March of  1974, NCHD concluded  that  phenol  in the  creek which had
originated from Chem-Trol was  responsible for  the  fish  kill.   Chem-Trol
denied  responsibility.

In September  of 1974, Lewiston and Porter officials  charged  that
Chem-Trol  was discharging liquid wastes  (variously described as aqueous.
wastes  and as untreated  acids)  illegally into  Four Mile Creek  and
thereby into  Lake Ontario.   There  are  a  number of  abandoned  sewer lines
underlying the Model  City site.  Lewiston officials  were reportedly
registering significant  use of these  lines  at  a lift station in  the  area
but could  not explain where this "sewage" was  coming from.   In September
a Porter official noticed wastes  flowing in Four Mile Creek.   Upon
 investigation he found that the wastes were coming from an abandoned

-------
 sewer line which ran two feet underneath the creek bed.  According to
 that official the creek bed had been excavated above the line and the
 line had been broken allowing wastes to flow into the creek.  On
 learning this Lewiston plugged the abandoned lines.  .

 Subsequent to the plugging of the sewer lines,  Chem-Trol reportedly
 constructed a number of storage lagoons on the site.  Three months later
 in December, 1974, DEC granted Chem-Trol a State Pollution Discharge
 Elimination System (SPDES) permit to discharge liquid effluent into the
 Niagara River.   Chem-Trol, however,  had no direct access to the river
 and that lack of direct access has continued to plague the facility up
 to the present  day.

 In the summer of 1975 SCA began to take more direct control of
 Chem-Trol.   A manager of an SCA solid waste operation in Connecticut was
 sent to Chem-Trol to serve as a troubleshooter.   In a relatively short
 period the top  management of Chem-Trol was fired.   The troubleshooter
 was promoted to vice president of operations (i.e.,  the  top management
 position at the facility).   In a 1977 interview with the Niagara
 Gazette,  the vice president described on-site conditions when he arrived
 as appalling, with "...thousands of  drums...  piled recklessly all
 around,  some of them rusty and leaking,  or covered with  rainwater."   He
 characterized the dangers of these conditions as "very real."
 Consequently SCA began  a  campaign to  reduce a backlog of unprocessed
 wastes,  to  re-engineer  parts of  the  facility, and  to make additional
 changes and  improvements.   Over  the next two to  three years  SCA
 reportedly  spent between  $500,000 and $1 million on improvements to  the
 facility.

 In 1975 local jurisdictions  showed signs of continued concern over the
 facility.   In July the  Lewiston  Town  Attorney was  told to consider legal
 actions to restore vegetation  to areas affected  by the salt piles.  In
 November  the Town of Porter  issued a  notice of violation of town zoning
 law.1  This was  appealed  to  the courts by Chem-Trol.  A  Porter town
 supervisor also  claimed that Chem-Trol was  polluting  the  town's  air and
 water.

 In early  1976 two incidents at the site fueled local  concerns and led to
 an increase in individual actions against Chem-Trol.  In  January a
 reported  1,500 gallons of wastewater containing phenols, dissolved
 metals, and organics spilled into Four Mile Creek, turning the creek and
 the snow along its banks blue.  Chem-Trol spent $50,000 cleaning the
 water and NCHD claimed the spill posed no danger.  The following month a
landfill caught  fire and burned for several hours.   A series of
explosions was reported during the fire.
   The specific basis of this action was not determined.   Subsequent
   legal actions by the local jurisdictions and the decisions of
   appellate courts would suggest both probable motives of the town
   (i.e., restrictions of Chem-Trol operations) and cast doubt on their
   legal viability.
                              262

-------
Regardless of the environmental or public health impacts, area residents
were alarmed.  In the next few months the rate of complaints from
citizens in the area markedly increased.  Though unsubstantiated, there
were reports of small explosions on the site.  Beginning in January
officials from Lewiston and Porter began to work together to pressure
DEC into stricter enforcement of state regulations.

In July of 1976, Chem-Trol received.a shipment of 200 tons of pesticides
from Massachusetts.  The director of DEC's regional office in .Buffalo
ordered a halt to the processing of the pesticides.  Citing recent
spills and other incidents at the site, the director stated that
procesing could not continue until Chem-Trol could prove that no
environmental damage would result.  Chem-Trol's vice president claimed
that the company already had permits to dispose of pesticides and had
been doing so for four years.  In addition he explained that DEC's
Albany office had been notified of the shipment.  After a meeting
between officials of Chem-Trol, DEC's Buffalo office, and NCHD, DEC
issued approval for the disposal of the pesticides subject to several
conditions.

In September, DEC's Buffalo office director requested Chem-Trol to stop
using one of its landfills because it had become filled,with a reported
3 million gallons of rainwater.  Claiming that the order,would stop most
or all site operations, Chem-Trol ignored the request.

In October, another spill took place at the site when a lagoon wall
collapsed.  The wall had been undermined by a bulldozer.  Chem-Trol said
the bulldozer operator's actions were an unintentional mistake; local
critics claimed it was intentional. .DEC investigators studying the
spill from the lagoon discovered a hose leading from a treatment lagoon
to a manhole which connected to Four Mile Creek.  Although investigators
saw no material flowing into the manhole, local critics were convinced
that Chem-Trol was illegally discharging into the creek.  DEC's
investigation led to a fine against the company for the lagoon spill.

During this same period resident and officials' attitudes began to
change from concern towards opposition.  In September, before the lagoon
spill, a Porter town supervisor citing residents' complaints of noxious
odors 1 called for a closing of the facility.  In October residents .-
began a petition drive which eventually collected about 2,000
signatures.  The petitions, which called for an end to pollution caused
by Chem-Trol, were delivered to the town boards of Porter and Lewiston.
The village board of Youngstowti, a community five miles northwest of the
site, called for the closing of the facility.  The town board of
Lewiston asked  the town attorney to determine how a local government
   An NCHD official explained during the site visit that odor
   complaints are most frequent during summer months.  Because of
   seasonal thermal inversions odorous gases are prevented from rising
   thus  leading  to their  dispersion in the area around the site.
                                263

-------
 Chem-Trol.  Also in October, citizens from around the area formed a
 group called Operation Clean with the purpose of closing the facility.

 By the end of 1976 the local opponents had begun to seek additional
 avenues for fighting Chem-Trol.  Local jurisdictions had begun to seek
 consultants to perform independent analyses of the site.   Local
 residents claiming the facility posed a danger to the water table sought
 state and federal action to close it.  The area U.S. congressman had
 also  become involved.   Having asked DEC and U.S.  EPA to investigate
 citizens'  complaints,  he had received assurances  that Chem-Trol was
 following those agencies'  recommendations for improvements.   DEC
 indicated it would regularly report to the congressman on Chem-Trol.

 In December of 1976,  the Niagara Gazette reported that DEC had given
 serious consideration to a summary abatement order which would have
 closed Chem-Trol.   Without explanation,  the report indicated that DEC
 rejected taking such an action.   Subsequently the director of DEC's
 Buffalo office,  who had earlier criticized the company,  termed it an
 essential service for  disposing of toxic wastes and stated that
 Chem-Trol was making a determined effort at correcting past  problems.

 In January of 1977,  the state supreme court issued a decision on the
 Town  of Porter's zoning suit against Chem-Trol which had  been initiated
 in November,  1975.   Overturning  a lower  court decision, the  court ruled
 that  after the fact opposition by the town could  not stop Chem-Trol from
 developing the site.

 The same month Chem—Trol announced that  it would  no  longer process
 liquid wastes and  that it  planned to lay off about 70 employees,  over
 half  the peak work  force.   The company explained  its  decision  in  terms
 of the public concerns raised about liquid wastes and new DEC
 requirements  for handling  such wastes.   It was  claimed that  these
 requirements  would  cost $30,000.   Solid  waste disposal would continue.
 In spite of this statement  and subsequent  problems,  liquid wastes
 continued  to  be  accepted.

 In February a spill containing phenol occurred; a leak was found  and
corrected.  Although DEC admonished Chem-Trol,  it  took no further
 action.  This  failure  by DECjjito  take  stronger action was  cited  as
contributing  to citizens' disillusionment  with  DEC.   As a result  DEC
became  part of the problem  from  the point  of  view of  local opponents.

By March the  local  jurisdictions  had  hired  a Buffalo  consulting firm to
test for pollution at  the site.  Although  the firm spent some months
attempting to  collect  data, local  officials  indicated a complete  report
was never  prepared.  The partial results of the study were considered
very unsatisfactory.   Those officials  pointed particularly to
Cheia-Trol's refusal to allow the consultants on the site as a cause of
the report's  incompleteness.
                               264

-------
Ihroughout this period Chem-Trol's problems with discharging treated
affluent had not been solved.  By the spring of 1977 one .options for
resolving the problem had been identified.  That option would be to use
a 42-inch sewer line owned by the Town of Lewiston.  The line ran to the
Niagara River and was not in use.  With the active support of DEC
Chem-Trol sought to lease the line from the town.  As Chem-Trol already
had a DEC^permit to discharge into the river, the lease of the sewer
line represented the only barrier to disposing of millions of gallons of
treated effluent.  The line has reportedly been contaminated and some
opponents claim the contaminant is PCB-laden sludge.  It was also
reported  that Chem-Trol offered to decontaminate the line if the company
was allowed to use it.  Without the use of the line, Chem-Trol claimed
it would  have to close.  Whether the town board of Lewiston would
approve Chem-Trol's request became a major focus of the controversy.

In late spring and early summer of 1977, the controversy began to heat
up and positions began to polarize.  In May DEC specifically asked
Lewiston  to approve Chem-Trol's use of the sewer line.  An NCHD
official, responsible for weekly monitoring and inspection of the
facility, declared that the closing of Chem-Trol would precipitate a
decline in   the economic and environmental health of the area and a
rise in illegal dumping of hazardous wastes.  He said that Chem-Trol's
top management had done a "tremendous" job in the past year, cleaning up
the site.  Opponents were declaring that the Chem-Trol management was
inept, incompetent, and dishonest.  The president of an  industrial park
near the  site claimed adverse impacts to his ability to promote the park
because of Chem-Trol.  In June local officials and representatives
appealed  to the governor of New York to intercede on their behalf.  In
an editorial that month the Niagara Gazette defined pollution as the
sole legitimate issue.  Should the company be able to operate without
perceptibly lowering environmental quality, the paper said it would be
happy to  have Chem-Trol in Niagara County.

At a June meeting the Lewiston town board delayed a vote on the sewer
line question and asked Chem-Trol for a list of hazardous wastes
accepted  by the facility.  On the basis that the data were proprietary,
Chem-Trol denied the request.  In a related action, DEC announced  that
it would  hold a public hearing in late July on a Chem-Trol permit
modification including the land  application of treated  effluent.

In July the Town of Porter again served Chem-Trol with  a notice of
zoning violation.  The town charged that  the company did not receive a
local excavation permit before developing  a new landfill.  Chem-Trol
ignored the notice and appealed  to the courts.  The state  Supreme  Court
then temporarily enjoined  any further  excavation work during  the  appeal,
Before the  Supreme Court,  Chem-Trol argued that DEC had  sole authority
over hazardous waste management  facilities.  DEC,  however, denied  this
and affirmed the validity  of the local permit.   In late  July the  Supreme
Court ruled  that  the  local excavation  permit was necessary before  work
could be  resumed on the landfill.  Town officials  indicated they would
closely  study  the  application  for the  excavation permit.
                               265

-------
 Also  in July the Niagara County legislators established the Niagara
 County Environmental Management Council (NCEMC).   Composed of various
 county elected and regulatory officials NCEMC was designed to act as a
 neutral party and to issue  a report  on Chem-Trol.   A. budget of $15,000
 was allocated for the study.  Chem-Trol pledged full  cooperation with
 the study,  provided NCEMC with requested data and opened  the facility  to
 commission members.   Over the next  six months NCEMC proceeded with its
 work.

 In September the Porter  town board by  a one-vote  margin denied
 Chem-Trol's request for  an  excavation  permit.   The actual vote was three
 to two  for  granting  the  permit.   However,  the Niagara County Planning
 Board  had  denied Chem-Trol  a special excavation permit three days'
 earlier.  As a result of the planning  board's  action,  Chem-Trol needed
 four out of five town board votes to receive the  excavation permit.
 Again,  Chem-Trol appealed the town board decision to  the  local zoning
 appeals board and asked  for a stay of  the ban on excavating.   Although
 DEC entered into the appeal in support of  the company the zoning appeals
 board  denied the permit  application  in October.

 In mid-November the  area's  U.S.  congressman arranged  a meeting of
 opponents and officials  from Chem-Trol,  NCHD,  DEC,  and U.S.  EPA.   Prior
 to that meeting local officials  had  appealed to the congressman for
 support and he reportedly asked  the  U.S.  president, to compel  U.S.  EPA  to
 monitor Chem-Trol.   At the  meeting itself  the  congressman declared that
 "...our biggest problem  is  that  the  people  here don't trust [elected and
 regulatory]  officials."   The deputy  administrator of  EPA  Region II
 provided information on  RCRA and indicated  that he  was  not  at  the
 meeting to  close down the facility.  According,to  Chem-Trol opponents,
 however, the EPA official promised that  the Region  II office  would take
 direct  action if it  could be proved  that Chem-Trol  polluted any
 navigable water.   Perhaps the most dramatic statement  was made by an
 NCHD official.   He explained that the  original permit issued  by NCHD had
 been reviewed and approved  by town officials.   This statement  was
 reportedly  met with  disbelief by the assembled citizens.

 By the  end  of 1977 Lewiston elected  officals  directed  the town attorney
 to begin legal  action against Chem-Trol, DEC,  and U.S. EPA.   This
 decision was  made  after  a December spill which resulted in  another
 DEC-iinposed  fine.

 In January  of  1978 a  series  of meetings were held between Chem-Trol  and
 DEC officials.   The  meetings  were designed  to  provide  solutions  to
 Chem-Trol problems with  liquid waste disposal.  Specifically DEC  would
 determine whether  a  temporary permit for liquid wastes granted by DEC's
Albany office  in October  of  1977  would be continued.  By  mid-January
Chem-Trol had submitted  a management plan which called for  applying  for
a permit for  an additional storage lagoon by late February, identifying
outfalls for  treated  effluent by mid-March, submitting monthly  waste
water reports, and limiting  Chem-Trol's acceptance of liquid wastes  to
 450,000  gallons a month.  DEC  declared  that the plan  had  fulfilled the
                                266

-------
agency's requirements.  DEC, which had threatened to revoke the
temporary permit if.the plan was unacceptable, extended the temporary
permit until mid-March, 1978.

Various other parties involved in the controversy also took actions in
January.  NCEMC, which had been, formed in July, 1977 by county
legislators, issued its report.  That report found laws to be vague but
that Chem-trol appeared to be complying with those laws.  It stated that
the facility should continue to operate but that monitoring should
increase.  Long-term care was considered to be the major issue and the
ultimate objective for the site (i.e., its post-closure use) should be
defined.  To facilitate communications between the concerned parties it
recommended that a panel of regulatory agency officials and citizens be
established.                                                        :

In late January a state appeals court lifted the ban on excavating a new
landfill.  The ban had been in effect since July of 1977 when the Town
of Porter claimed that the company needed a local excavation permit. ' In
its decision the court stated that "...(the) record fails to show how
(the landfill) will result in irreparable injury..." and that delaying
excavation would be punitive to. Chem-Trol.

In January another spill occurred which discharged a "green acid" into
Lake Ontario.  According to local officials, the spill ran for:five days
while local and DEC officials argued over whether the spill was from the
Chem-Trol facility.  DEC finally determined that it was.,  By February,
armed with data generated by technical consultants that showed pollution
of navigable water, local officials and residents went to Region II to
seek federal monitoring of the facility.  EPA declined tp do so.
Instead, according to local residents, EPA; indicated that such requests
were routinely turned over to state agencies (i.e., to DEC).  Local
residents felt that* EPA had broken the promise to act made at the
November, 1977, public meeting.

In mid-March DEC finally held,public hearings on the water, discharge
permit.  These hearings had originally been scheduled for the previous
July but had been postponed several times because of intervening events.
At issue was whether effluent could be discharged into Four Mile Creek
and thus into Lake Ontario.  Although the existing permit allowed for
discharging into the Niagara River, Chem-Trol had no direct access to
the river.  The Lewiston town board had not allowed the use of its sewer
line to the Niagara River.  The company reportedly wanted to pursue both
discharge options.

The hearings proceeded for four days.  The question of discharge into
Four Mile Creek was complicated by the fact that there is substantial
water flow in the creek only during a one-month period in the fall and
another in the spring.  Any effluent discharge by Chem-Trol would have
to take place during these peak flow periods.  Chem-Trol and its
consultants testified that the discharge would have no effect on fish in
the creek and that samples of fish from the creek showed no build up of
toxic materials.  Opponents openly doubted the reliability
                               267

-------
of Chem-Trol's consultants  and  claimed  the  company  had  no  credibility.
They also questioned  the company's ability  to monitor its  discharges.
On the last day of  the  hearings  Chem-Trol offered to pay the  Town  of
Porter to hire a security agency for  24-hour surveillance  of  discharge
operations.

In early April, three weeks after the hearing closed, DEC  approved a
permit allowing Chem-Trol to discharge  up to 450,000 gallons  a day into
Four Mile Creek.  This  was  subject to the condition that the  volume of
discharge not exceed  5  percent of the volume of water in the  creek. DEC
also announced that it  would monitor  discharge operations.  Discharges
were then made by Chem-Trol and  the company paid Porter to have the
operations surveilled.  During  the discharge operations a  Porter town
supervisor acknowledged that more monitoring was taking place than ever
before but that he  was  still scared by  the  potential impacts  of the
facility.

In June, 1978 the New York  Department of Health declared a state of
emergency in the area around Love Canal, some ten miles south of Model
City site.  This official confirmation  of the disaster surrounding Love
Canal gave added impetus to the  concerns of Chem-Trol's opponents.
Operation Clean and local officials had developed some ties to citizens
active in the Love  Canal fight.   In addition, various local leaders  .
indicated that Niagara  Falls residents  fearful of the impacts,of Love
Canal had moved into  Lewiston and Porter and had joined those concerned
about Chem-Trol.

Despite local attempts  to restrict Chem-Trol's operation the  company had
been able to expand its site.-  Through  a number of  purchases  beginning
in 1976, the land owned by  SCA was increased so that by June  of 1978 a
total of 860 acres  were owned.   In July, SCA confirmed a number of  local
rumors by announcing  that it was  considering purchasing an old chemical
plant in Lewiston.  If  bought, the plant would be converted into a
treatment facility  for  hazardous  wastes.  (At the time of the site
visit, no further evidence  of such a  purchase could be determined.)

In late summer and  early fall of  1978,  actions against Chem-Trol
increased.  In early  September a  resolution was proposed to the Niagara
County legislature  to oppose all  permits allowing Chem-Trol to
discharge.  Opponents argued that there was a 50-50 chance of
contamination resulting from disposal operations while others countered
that the area should  be responsible for the hazardous wastes  it
generated and that  the  resolution was too broadly written.   The
resolution was defeated by  a vote of eight to four.   The following month
local officials and citizens appealed to the state  attorney—general to
investigate the site.    The  attorney-general's office subsequently began
an investigation.   Citizens opposed to  the facility also received  a
boost when the United Auto  Workers and  the Farm Bureau independently
passed resolutions  supporting the efforts of Operation Clean.

U.S.  EPA became directly involved with  Chem-Trol when the Region II
office granted a PCB  disposal permit in October.   During the public
                                  268

-------
comment period EPA received a number of letters from area residents.  An
EPA official, however, indicated that most complaints related to
discharge, not directly to PCB disposal.  For some opponents EPA's
permit approval resulted in a wholesale plummetting of. the agency's
credibility.                                              ,

In December opponents organized an informational meeting which attracted
a reported 700 persons.  Speakers included local opposition leaders, the
assistant attorney-general of Illinois who had prosecuted SCA for its
Wilsonville facility, and a cancer researcher from the Roswell Park
Memorial Institute.  The cancer researcher decried the burial of mixed
hazardous wastes and argued that thermal destruction was the only
responsible disposal method.  She also stated that the Chem-Trol
facility could be the "Love Canal" of the future.  The Illinois official
declared that Chem-Trol could be worse than Wilsonville.1  A Lewiston
town supervisor urged the state attorney-general to close Chem-Trol and
called on industry to neutralize the hazardous waste it generated.

In early 1979 opponents began to focus their attention on the Porter
town board and a proposed pipeline.  Operation Clean presented that
board with a petition signed by 6,500 persons; the petition urged the
town to close the site.^  Soon after the petition, SCA-^ presented
plans to Niagara County officials for a 32,000-foot pipeline from the
site to the Niagara River.  The pipeline, which would provide SCA access
for discharging into the river, required approvals from the Town of :
Porter, Niagara County, DEC, the state transportation department, and '
U.S. EPA.  Operation Clean opposed the pipeline and in late January the
Porter town board unanimously voted to oppose the plan.  In March
Niagara County gave its approval for SCA to construct the: pipeline on  ,
county right-of-ways.  Yet by mid-April Porter officials had still not
acted on SCA's request that the town approve the pipeline.  The town's
continuing opposition was based on the view that the line was an,
industrial use and any leakage would pose a threat to the areas
traversed by the pipe including an area dedicated to residential use.
The pipeline crossed one water line and paralleled another, raising
fears of contamination of drinking water supplies.

In late January DEC called a meeting of Lewiston and Porter officials,
along with other area officials at the county, state, and national
    In  of  August  1978, a  trial  judge  ordered  an SCA subsidiary  to
    close  a  hazardous waste  facility  in  Wilsonville,  Illinois and to
    exhume all  buried waste.  The  exhumation  order  was  stayed while the
    decision was,  appealed.

    The petition  was also sent  to  Lewiston, Niagara County, and state
    officials,  as well as to the governor, U.S.  EPA,  and  the president.

    In  late  1978  or early 1979  the facility1s name  was  changed  to SCA
    Chemical Waste Services,  Inc.
                                  269

-------
 levels.   This was the first in a series of  meetings  between DEC  area
 officials1 and local  opposition leaders.   According to  DEC,  the meetings
 were designed to facilitate the exchange of accurate information on the
 SCA site,  hazardous  waste  problems,  state regulatory procedures,  and
 DEC's attempts to regulate SCA.

 The following month  SCA submitted to DEC an application for an operating
 permit under  revised state hazardous waste  regulations.  The new
 regulations subsumed earlier state regulations  and all operating
 hazardous  waste facilities were required to apply for  new permits.   The
 SCA permit also included some expansion to  the  facility, principally a
 new landfill.   DEC anticipated holding  public hearings  on the
 application in May of 1979 prior to  making  any  decison on the
 application.

 In  early March SCA was  fined $15,000 by U.S. EPA for improper storage of
 PCBs.  This was the  second fine levied  against  SCA in  1979; in
 mid-January DEC had  fined  the company because of odors  and  other
 charges.

 In  mid-April  (when the  site visit was conducted) the conflict over  SCA's
 facility appeared  not to be near  resolution and showed  signs of renewed
 activity.  Long-standing opponents (i.e., local officials and citizens
 organized  as  Operation  Clean)  had begun  to  seek the support of Canadians
 across the Niagara River in Ontario.  In the first several  months of
 1979  those Canadians  were  reportedly organizing their  own anti-SCA
 group.  Canadian officials at the local  and provincial  level had
 contacted  DEC to  express their concern  over  the possibility of SCA
 discharging into  the Niagara River which is  a source of water for some
 Canadian jurisdictions.  Opponents appeared  to be concentrating their
 energies on the anticipated public hearings  on  the new  DEC  permit for
 the  facility.    Operation Clean was also  preparing to study health
 problems in the area to  determine if they were  related  to the SGA
 facility.  In  the  longer term, opponents looked to the state attorney-
 general's  office  as  the  most probable, and  perhaps only, means to close
 the facility.    Opponents specifically called for a suit analogous to the
 one  pressed by the Illinois attorney-general against the Wilsonville
 facility.

 While a substantial,  apparently immutable group sought closure, other
 actions in 1979 were directed  toward upgrading facility safeguards.
 Thus  in January the  state  attorney-general's office reportedly
 recommended the creation of  a  state  closure  authority as a mechanism for
 additional control of hazardous waste facilities,  particularly after
 those  facilities were closed.  The Porter town board was pressing
 Niagara County legislators  to enact a perpetual care law that would
 apply strong standards.

 SCA was still  faced with the  problem of discharging its treated
effluent.   Its only recourse in April was to discharge  into Four Mile
 Creek.  That option was  severely restricted by the fact that the
stream's  flow could only accommodate discharge for short periods  in the
                                 270

-------
spring and fall.  Estimates of the amount'of  treated  effluent  SCA had
on-pite ranged from 40 to 90 million gallons.  Long-te^rm -jsolutip-ns re-
qui^red either the use of the Lewiston  sewer line  or the construction of
SCA,'s own pipeline.  Both solutions required approvals by local of-
ficials who showed few, if any, signs  of granting such approval.  A'
Porter town supervisor expected a suit would be pressed against SCA  if
it tried to construct the pipeline, even though he doubted  the town.
could win such a suit.  In February SCA'changed. its top management at
the facility.  For at least one local  official .who has been a  long-time
opponent, this change in management may have created  the potential for
resolving the conflicts.  Most opponents, however, seemed unchanged  in
their attitudes.  .SCA staff also ,'saw little chance for any  change in the
•basic outlook of area residents over the short- or medium-term future.
IV.
CHRONOLOGY OF EVENTS
April, 1969 —Chem-Trol incorporated.                        ,    ,

August, 1969 -— Blasdell site purchased.     .

July, 1970 — Operations begin.             :

.1971 — Search for new site begins.                   ,

Early 1972 — GSA declares Model City surplus federal
              property; Chem-Trol purchases site.         .  ,  , •• .

February, 1972 --- Blasdell site is closed; move to Model City begins.

Spring 1972 —• NCHD.grants Chem-Trol operating permit.               .

May, 1972 — Model City site begins operations.                      •

July, 1972 — Fire and explosion occurs at Blasdell site.

1972 •-- Chem-Trol makes presentations to local officials stressing rec-
        lamation and recycling aspects of facility operations.

1973 — SCA purchases Chem-Trol; original management retained.

September, 1973-..— Salt piles and damaged vegetation discovered by local
             --.-.-  officials.        ,                   •„•••.-,     -,

March, 1974— Phenol-contaminated spill results in fish kill.   NCHD de-
               termines material was from Chem-Trol.

September, 1974— Local officials charge that Chem-Tro!-, illegally dis-
                   charges wastes into Four Mile Creek via abandoned
                   sewer lines.  Town plugs line; subsequently lagoons
                   reportedly developed on site.,               •
                               271

-------
December, 1974 — DEC grants Chem-Trol SPDES permit for discharge into
       j      ,     Niagara river.

Summer 1975 — SCA replaces original Chem-Trol management, new man-
               agement begins concerted effort to clean up facility.

July, 1975 — Lewiston Town Attorney directed to investigate legal
              actions against Chem-Trol.

November, 1975 — Porter issues notice of zoning violations to Chem-
                  Trol; Chem-Trol appeals decision to courts.

January, 1976 — Wastewater from Chem-Trol spills into Four Mile Creek.
                 Local officials begin meetings to push for DEC en-
                 forcement.

February, 1976 — Fire and explosions occur in landfill.

June, 1976 — Chem-Trol acquires more land, owns a total of 407 acreas.

July, 1976 — Shipment of pesticides received; DEC Buffalo office orders
              halt in processing pesticides; DEC and Chem-Trol develop
              plan allowing for processing of pesticides.

September, 1976 — Porter town supervisor calls for closing of faciltiy;
                   DEC requests halt to use of landfill filled with
                   rainwater; Chem-Trol ignores request because it would
                   idle facility.                                   •

October, 1976 — Spill at site occurs when bulldozer undermines lagoon
                 wall; DEC investigators find hose leading from  treat-
                 ment pond to manhole.  Residents begin petition drive
                 against facility and form Operation Clean.  Youngstown
                 village board calls for closing of facility.

November, 1976 — Area's U.S. congressman asks DEC and U.S. EPA to mon-
                  itor site.  DEC.reportedly considers, then rejects,  an
                  order to close facility.

January, 1977 — State Supreme Court rejects town zoning suit against
                 Chem-Trol.  Chem-Trol management claims it will stop
                 receiving liquid wastes but it does not.

February, 1977 — DEC admonishes facility for spill; lack of stronger
                  action by DEC reportedly leads to local disil-
                  lusionment with that agency.

March, 1977 — Local jurisdictions hire consultant to analyze Chem-Trol.

May, 1977 — DEC advises Lewiston to allow Chem-trol to use a town sewer
             line for discharge into Niagara River.
                                272

-------
June, 1977— NCHD official argues for the continued operation of Chem-
              Trol.  Opponents appeal to governor for help, openly
              charge company with incompetence and dishonesty.  Lewiston
     j         delays vote on Chem-Trol use of sewer line.

July, 1977 — Porter issues zoning violation to Chem-Trol claiming com-
              pany must have excavation permit.  Chem-Trol ignores order
              to stop excavation until order affirmed by state supreme
              court.  NCEMC created by county legislators to be neutral
              party investigating the controversy.  DEC public hearing
              on permit for wastewater discharge postponed.

August, 1977 — Porter holds hearings on Chem-Trol application for ex-
                cavation permit.

September, 1977 — Niagara County Planning Board denies special permit
                   to allow Chem-Trol to construct landfill; Porter de-
                   nies excavation permit for landfill; Chem-Trol ap-
                   peals town's decison and DEC supports Chem-Trol1s ap-
                   peal.

October, 1977— Area's U.S. congressman asks president to compel U.S.
                 EPA to monitor Chem-Trol.

November, 1977 — Congressman arranges meeting with officials from U.S.
                  EPA, DEC, NCHD, and local jurisdictions and with area
                  residents.

December, 1977—Spill discovered at Chem-Trol; DEC criticizes Chem-
                  trol for number of spills and violations; company
                  fined by DEC.  Lewiston Town Attorney is directed to
                  take legal action against Chem-Trol,  DEC, and U.S.
                  EPA.

January, 1978 — Series of meetings between DEC and Chem-Trol results in
                 plan for handling liquid wastes and extension of liquid
                 waste permit for two months.  NCEMC issues report
                 finding Chem-Trol generally in complance with state
                 laws  but calls those laws vague.  State appeals court
                 lifts ban on excavation of Chem-Trol landfill.

February, 1978 — U.S. EPA refuses to monitor Chem-Trol in spite of op-
                  ponents' data on previous month's spill.  Opponents
                  consider U.S. EPA to have broken promise made at
                  November, 1977 meeting.

March, 1978 — DEC holds four-day public hearing focusing on Ghem-Trol's
               plans to discharge treated effluent.

April, 1978 ~ DEC approves discharge of facility's effluent into Four
               Mile Creek; Chem-Trol pays Town of Porter for surveil-
               lance of discharge operations.      ,
                                 273

-------
June, 1978 — Chem-Trol now owns 860 acres.
        I   -.      >  )
July, 1978 — SCA announces that it is considering buying Stauffer
              Chemical plant in Lewiston to convert into treatment
              facility.

September, 1978 — Resolution to oppose all permits for Chem-Trol dis-
                   charge defeated by Niagara County legislators.

October, 1978 — UAW and Farm Bureau declare support for Operation
                 Clean.  Opponents appeal to state attorney-general's
                 office which begins investigation.of Chem-Trol.   EPA
                 grants PCS disposal permit.

December, 1978 — Opponents organize informational meeting;  700 attend.

Late 1978, early 1979 — Facility name is changed to SCA Chemical Waste
                         Services, Inc.

January, 1979 — DEC imposes $5,000 fine for violations.  Operation
                 Clean obtains 6,500 signatures on petition to close
                 facility. SCA announces plans for 32,000-foot pipeline
                 to Niagara River, Porter town board votes to oppose
                 plan.  Local officials meet with DEC to discuss SCA
                 facility and general problems of hazardous waste.
                 Attorney-general's office recommends creation of state
                 closure authority for hazardous waste facilities.

February, 1979 — SCA changes top management at facility, submits ap-
                  plication for revised DEC permit.  Porter town board
                  encourages county to adopt perpetual care law.
March, 1979 —
        Niagara County gives approval for SCA pipeline to cross
        county right-of-way.  U.S.  EPA fines SCA $15,000 for
        improper PCB storage.
Spring, 1979 — Operation Clean seeks and obtains support of Canadian
                residents; Canadian officials express concerns to DEC
                over SCA discharge into river.
V.
ATTEMPTS TO SECURE SUPPORT
Numerous attempts have been made to gain support for the facility, to
address or to correct specific and broad concerns of local residents, or
to create a means for addressing those concerns.  The most significant
of these follow.

       o     The review of the original NCHD permit by the Porter town
             board.

       o     Early presentations by Chem-Trol to local officials
             stressing recycling and reclamation techniques.
                                274

-------
VI.
o     The clean-up effort begun when SCA placed its own  ?
      management personnel  in charge of the  facility.    "

o     Chem-Trol's offer to  decontaminate Lewiston's sewer line  if
      it could be used to discharge into the Niagara River.

o     Various statements by NCHD and DEC officials arguing that
      Chem-Trol was an environmental and/or  economic asset.

o     Meetings and other actions by the area's congressman
      directed towards greater monitoring of the facility and
      better communications between key parties.

o     U.S. EPA's reported promise to intervene if navigable
•-.•..   waters were polluted.                         .     ..-•

o     NCEMC's creation as a neutral party and its report  on
      Chem-Trol and state law and regulation.

o     DEC's March, 1978 public hearings on the modification of
      Chem-Trols's state permit.

o     Chem-Trol's payment to Porter of the costs of surveilling
      discharge operations.              .

o     Meetings in early 1979 between DEC and local officials.

o     Anticipated public'hearings to be held by DEC in May of
      1979 in connection with the issuance of a revised operating
      permit.      .                          ,   ., -v-  ,

SUMMARY EVALUATION
In its first year or so of operation Chem-Trol operated with a degree of
support from local officials.  This can be said to stem in part from the
review of the permit by Porter officials and early Chem-Trol public re-
lations efforts.   Approval of the NCHD permit was due to the benefits
officials attributed to the development of the faciltiy,:including the
return of a sizeable piece of land to local tax rolls and, more
generally, the broadening of the area's industrial base'.  Equally
important was the impression given local leaders that the facility would
recycle and reclaim industrial wastes.  It is probable that Chem-Trol
stressed these facets of the operation and downplayed the burial of
anything other than innocuous residues.

Subsequent attempts to secure support or address concerns did not occur
until three years after the facility opened.  All have clearly failed to
generate support for the facility.  Few if any gains have been made in
overcoming public concern and opposition.  The simplest and perhaps most
accurate explanation of this failure is that in the eyes of area
residents the attempts • were too little and too late.     '•-,_'•
                               275.

-------
Opposition to the facility evolved over a relatively long period of
time.  Most opponents described this as starting with concern over
spills or other operation problems which continued over time; repeated
problems deepened concerns.  The perceived failure of DEC to recognize
the gravity of these problems added disillusionment; the perceived un-
willingness first of DEC and later U. S. EPA to firmly and quickly en-
force applicable regulations added frustration.  The continued spills
and accidents, intentional or unintentional, reduced SCA's credibility
to near zero.  Finally, outside events added a clear element of fear.
To paraphrase an opposition leader, Love Canal demonstrated that
landfills can kill and U.S. EPA demonstrated that there is no such thing
as a secure landfill.1  Over time opposition became more widespread
and more profound.  Attempts to deal with this appear not to have
matched  the magnitude of the opposition.

Since at least September of 1976, opponents have called for the closing
of the facility.  Thus for more than two years opponents have stated
their major goal as being completely at odds with the facility's
attempts to reduce spills, to upgrade monitoring, and to make other
reforms.  A clear impression from all key parties is that there is
almost no middle ground, no room for compromise.  There is some sense
that better public education/ information may in the long run persuade
residents that'SCA's facility is an environmentally appropriate response
to hazardous waste disposal problems.  However, there is an equal if not
greater sense that opposition will continue until every tactic to close
the facility has been tried.

A great many issues have been raised, and major issues have changed as
events have changed, a prime example being the concerns the Town of
Porter has over the proposed SCA pipeline to the Niagara River.  There
are overriding issues, however, which encompass most of the shifts of
focus. There are listed below.

The safety of landfills — The burial of hazardous wastes is seen as a
continuing and long-term danger extending beyond the operational life of
the facility.  It is also seen as a low-cost, high-risk disposal tech-
nique.

Perpetual care — Linked to the concern over landfills is concern over
provisions for maintaining and monitoring the integrity of the facility
after it is closed.
   A U.S. EPA-sponsored study found that leachate was migrating from
   over 80 percent of 50 industrial waste land disposal facilities,sur-
   veyed.  The study concluded that groundwater contamination at such
   facilities is a common occurrence.  It should be noted that some of
   the study's data were challenged by state agencies.  See The Preval-
   ance of Subsurface Migration of Hazardous Chemical Substances at
   Selected Industrial Waste Land Disposal Sites, EPA/530/SW-634, Oc-
   tober, 1977.
                               276

-------
Operational safeguards — Opponents feel that there have been too many
odors, spills and accidents.  Many see these accidents as intentional
actions by the company to solve its discharge problem.  SCA's
credibility has been consistently questioned and doubted.  A major focus
of concerns over operations has been the discharge of effuents.  These
are seen as major pollutants of Lake Ontario and potentially the ^Niagara
River, the latter being a source of public water supplies.

The credibility of regulatory agencies — Residents seriously doubt that
DEC is willing to implement a strong regulatory program.  DEC is seen as
insufficiently responsive when violations of state regulations occur.
While most of these regulatory concerns have been directed at DEC, the
credibility of U.S. EPA has also been questioned.  These agencies tend
to be seen as being biased towards SCA and against opponents.

Equity — Area leaders have stated that provisions should be made for
hazardous wastes generated in the area.  At the same time, opponents
feel that the area is being asked to bear the costs, while a much larger
group of others reap the benefits of those industries which generate
hazardous waste.                                    ."..'.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Initial acceptance of Chem-Trol was primarily the result of the
following factors.

       o     The return of the Model City site to local  tax rolls.

       o     The'desire of local officials to increase  the area's
             industrial base.

       o     The image of Chem-Trol as a recycling and  reclamation
             facility utilizing innovative, non-polluting techniques.

The subsequent creation of  local concern and opposition resulted from
the following.

       o     Spills, odors, and other operational problems at  the site
             and in  the transport of wastes to the site.

       o     The perception that Chem-Trol turned increasingly to the
             burial  of hazardous wastes as a disposal technique.

       o     The conviction that DEC, and to a lesser extent U.S. EPA,
             were  not fulfilling their regulatory responsibilities and
             were  not helping to solve problems at the  facility.

       o     The events surrounding Love Canal and a variety of
             information which confirmed the potential  dangers
             of hazardous waste disposal and cast serious doubt  on the
             integrity of landfills as a disposal technique.
                             -277

-------
 VIII.   RETROSPECTIVE  VIEWS

 Almost  everyone  interviewed  felt  that  if  the  initial  promises  and
 proposals  made in connection with the  Model City  facility  had  been
 adhered to,  opposition would not  have  developed.   For local  leaders  this
 primarily  meant  that  no burial  of hazardous materials would  have taken
 place.   For  SCA  and regulatory  officials  this meant that no  spills or
 other accidents  would have occurred.   An  NCHD official also  indicated
 that if the  original  proposal had encompassed some permanent method  of
 discharging  effluents much of the controversy could have been  avoided.
 Given that there have been a number of operational problems, those
 interviewed  agreed that opposition was inevitable.
IX.
GENERAL COMMENTS
Local  leaders  saw a number  of general  problems with current hazardous
waste  management.  'RCRA was strongly criticized for condoning
landfilling  of hazardous waste and  for limiting "perpetual care"
provisions to  a 20-year period.   Implementation of hazardous waste
programs  should be carried  out by one  lead agency as opposed to the
array  of  agencies with some regulatory control over these problems.
Greater responsibility should be  placed on hazardous waste generators
although  one official cautioned that this might place undue burdens on
small  businesses.  More monitoring  of  sites was considered critical
although  it  was acknowledged that DEC  has limited staff resources.  When
violations occur fines should be  much  larger.  It was argued that a
$1,000 or $5,000 fine made little difference to disposal companies.
These  leaders  also saw the  transportation of hazardous wastes as a major
problem.  Finally, one local official  felt that problems might ease in
two to three years as regulatory  agencies gained more expertise and
thereby gained the confidence of  the public.

These  local  officials and residents agreed that the state or federal
government must own disposal sites  and be responsible for operations.
Industry  was seen as being naturally concerned with reducing cost and
therefore not  willing to spend the  required money for proper disposal.
They also called for complete treatment of wastes to render them
non-hazardous  and the burial only of harmless residuals.  Several of
those  interviewed pointed to European  treatment facilities that
reportedly operated in such a fashion.  The facility being proposed by
the state of Michigan was also seen as a model.  A national approach was
emphasized so  that no state would become a haven for hazardous wastes.
Finally,  there is a need for compensating local areas for costs from
studies commissioned by local governments and from legal fees as well as
the more general costs associated with being a host community for a
disposal  facility.

An NCHD official also felt state  or federal ownership of sites may be
the only viable option.   With the use of eminent domain the government
could  acquire the best possible site regardless of whether the site was
for sale.   Government could contract with private industry for facility
operations.   A major concern was  perpetual care and who would be
                             27B

-------
responsible if problems arose 20 or 100 years after closure.  He argued
that government would be there to solve problems long after private
industry had left the scene.

SC.A officials also felt that eminent domain may be necessary in some
cases because public opposition will be a major obstacle in securing
future sites.  They, also saw this potential increase in governmental
involvement as making siting more cumbersome and problematic.  In the
longer run, they felt, public education by government and industry is
the only real way to overcome opposition.  They saw a need for
widespread understanding of the societal impacts .created by contemporary
industry.  People need to realize the inevitable costs -- both financial
and environmental — of the products that cpntribute to the present
standard of living.  It was hoped that such an understanding would lead
to greater confidence in the ability of government and private industry
to solve hazardous waste problems.  Finally, these officials felt that
there should be stricter government regulation and stronger enforcement
of existing regulation, including fines tied to costs.  These
regulations should impose high standards for disposal and require
greater quality control for operations.

State views are discussed in state agency reports elsewhere in this
report.
                           -279

-------
                      ENSCO ENERGY SYSTEMS COMPANY

                          EL DORADO, ARKANSAS
I.     INTRODUCTION

Ensco is in the business of disposing of industrial waste chemicals by
high-temperature incineration.  They operate a facility in Union County
near El Dorado, Arkansas.  The facility consists of a modified incinera-
tor and storage tanks left over from an abandoned oil refinery.  The
facility has been operating commercially since 1977.  In 1978, Ensco
requested permission from EPA to incinerate PCBs-'-.  However, before
this request could be acted upon, the county passed an ordinance
prohibiting the transportation, storage or disposal of PCB wastes in the
county.  EPA had scheduled but subsequently postponed a test burn of
PCBs to ensure the effective and safe destruction of these wastes by the
Ensco facility.

At the present time, the company is continuing to dispose of non-PCB
hazardous wastes.  The company is also fighting a court case against
the county ordinance forbidding PCB storage, disposal and transportation
activities.  Pending a decision in this case, EPA will again reschedule
a test burn to verify the incinerator's effectiveness in PCB disposal.

There has been local public opposition to this facility almost since its
inception.  This opposition was initially based on adverse publicity
surrounding a previously unsuccessful Ensco waste disposal facility in
Minnesota.  Ensco's decision to request permission to incinerate PCBs
then raised the level of public opposition, due to the public awareness
of the hazards associated with PCB wastes.   Although the facility
appears to be technically adequate and represents the current
state-of-the-art in high temperature incineration, the management and
physical appearance of the facility and the past history of the company
have provided the public with issues on which to base their opposition.

Various attempts by Ensco have been made to assuage public concern, and
a number of technical studies and reports have generally upheld the
facility's viability.  These various actions have had little impact on
general public opposition.

II.    BACKGROUND INFORMATION

The site of the Ensco facility occupies 45 acres in an industrial park
within the unincorporated portions of Union County, Arkansas.  The site
is part of what was an abandoned oil refinery that was converted into an
industrial park.  It is zoned for industrial use and is completely
surrounded by other industrial uses.  Every phase of the oil industry
   Under the provisions of the Toxic Substances Control Act, EPA
   must approve any such operation.
                             280

-------
operates in this area — exploration, drilling, production, refining,
sales and transportation.  Within the county there are several
refineries, a chemical fertilizer plant and several bromide plants.
However, the site is also immediately adjacent to the city limits of El
Dorado and less than a mile from populated areas.  The Ensco facility
makes use of several storage tanks and an incinerator that were part of
the abandoned refinery.  The basic incinerator consists of a primary
combustion area (3000 ft3) and a retention chamber (3000 ft3)
separated by a 180-degree bend and a brick baffle.  The primary
combustion area has two burners:  Model 6514-9 Fire-All Dual Burner
manufactured by North American.  The waste is fed into a central nozzle
in each burner and atomized with 100 psi air.  Two annular rings
encircle each nozzle, one to deliver secondary air and one to provide
natural gas to act as a pilot light and a flame stabilizer.  Mounted on
the rear wall of the primary combustion chamber are two spray nozzles
which are used to inject well water into the flame front to control the
temperature of incineration.  The incinerator is equipped with a venturi
scrubber, and a cyclone de-mister for removal of particulates, HC1 and
S02.

The incineration process proceeds as follows.  Drums full of waste are
first dumped into grinding mills that shred any packaging so that it
will burn better.  The combined packaging and chemical waste then falls
into a hopper and is dumped into a 34-foot rotary kiln.  The kiln is
lined and turns constantly.  The waste retention time is 30 minutes.
The temperature inside the kiln reaches 1,500 degrees.  Organic material
is turned to an inert ash.  The ash and non-combustible organic
materials, which together comprise the solid waste output of the
incinerator, is suitable for landfilling.

The incinerator burns both liquid and solid wastes.  Liquid wastes are
used as fuel for the incinerator.  Waste air and vapors are pulled out
of the grinder and recirculated into the system.  The combustion system
operates under negative pressure, so that air would be drawn into rather
than out of any hole in the structure.  Pressure-sensitive switches ,
automatically close down the system if interior pressure exceeds given
parameters.  Ash is.dumped out of the kiln and gases are recirculated.
The kiln temperature is increased to 2,200° to break liquids into a
fog.  A wet scrubbing system then removes dust and acid vapors.  In the
smoke stack a de-mister removes dirty water from the resultant gases,
leaving clean flue gases.  The stack gases are monitored to ensure that
they include no harmful materials.                           ,

In addition to its incinerator, Ensco has storage tanks originally used
by the refinery.  The company maintains a laboratory on the site.  All
wastes received are analyzed before incineration and samples of waste
are kept.  Ensco also has four tanker trucks to provide hauling services
for hazardous waste.  There are about 80 employees.

The Ensco facility accepts a relatively broad range of solid and liquid
wastes suitable for thermal destruction, including chlorinated
                                281

-------
hydrocarbons.  Wastes are accepted from generators and in some cases
other disposal firms that lack incinerators.  Most wastes are from
out-of-state and the market area served by the facility is national.

Ensco is a privately owned firm which has evolved from an earlier
disposal firm with a hazardous waste landfill which operated between
1965 and 1976 in Minnesota.  As will be described in Section III, Ensco
is also linked to an El Dorado firm with which it merged in the early
1970s.  The El Dorado facility is the only one currently being operated
by Ensco.

El Dorado is located in southern Arkansas, 120 miles from Little Rock.
The estimated population of El Dorado was 26,500; that of Union County,
46,500 (1977 figures).  Average family income in El Dorado was $10,617.
Major industries located in the county include the oil industry,
chemical industry and the lumber and wood products industry.  El Dorado
also has the largest poultry processing plant in the South.

III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

To operate an incinerator in the state of Arkansas, one is required,to
have a permit from the Arkansas Department of Pollution Control and
Ecology (DPCE).  This permit specifies what can be burned in the
incinerator.  In this case, for instance, the permit had to be amended
to allow the burning of PCBs.  As noted above, permission from the EPA
to incinerate PCBs was required under the provisions of the Toxic
Substances Control Act.  No regional or local permits were required for
this facility.

In March of 1971, American Oil Company (Amoco) donated to Union County
certain property to be used for industrial development purposes.  The
donation was made since Amoco had closed a refinery there and had moved
from the Union County-El Dorado area.  In August of 1973, a lease-
purchase agreement was entered into between Union County, the El Dorado
Industrial Development Corporation, and a private individual who was
personally associated with Pollution Controls, Incorporated (PCI).   The
agreement covered several lots on the old Amoco properties.  In March of
1974, a sub-lease agreement was made between that individual and Grace
Properties, Incorporated for approximately 45 acres.  The 45-acre site
included an abandoned oil refinery and storage tank facilities.  The
abandoned equipment was to be the nucleus of ah incineration process for
hazardous chemical wastes.  This arrangement was approved by Union
County and the El Dorado Industrial Development Corporation.  Graco
Properties soon became known and referred to as Graco Chemicals.  Graco
Chemicals subsequently took the name of Pollution Controls,
Incorporated.  This was in essence a merger with PCI, a Shakopee
(Minnesota) chemical disposal firm.  (PCI was founded in Shakopee,
Minnesota, in 1965.  The Shakopee plant was closed in 1975, following
continuous complaints from residents and continuous disputes with the
Minnesota Pollution Control Agency.)
                              '282

-------
  PCI s first contact with DPCE in connection with the development of the
  incinerator came in 1973.   Following these discussions PCI submitted an
  application for a permit for the El Dorado site. In July of 1974  DPCE
  granted PCI a permit for the construction of a chemical waste disposal
  facility.  The major component of PCI's facility plan was an incinerator
  which would be constructed over a period of about 18 months.   The
  facility plan also included the use of existing storage tanks for the
  storage of hazardous waste.   By offering storage services,  PCI could
.begin to accept wastes as  soon as the permit was granted.   As a result
  PCI was able to generate revenues during the incinerator construction '
  period.   The wastes were to be stored until they could be incinerated.

  In  early 1975 the  future plant engineer for PCI,  a  chemical engineer who
  was  then a professor at  the  University of Arkansas,  spoke as  a :  '
  representative of  PCI with local civic groups on company plans for  a
  waste  disposal incinerator in El Dorado.   At  these  initial  meetings  with
  elected officials  and public groups  it was explained that the plant
  would  be less  hazardous  than existing  industries  now operating  in the
  S^i  N°  noti"abl\opPOSition t0   PCI's plans  was  expressed.  However,
  shortly thereafter  the local  newspaper  started a  campaign opposing the
  proposed site.,   The  main themes  of the  news  story were PCI's  previous
  difficulties in  operating  a  chemical waste disposal  facility  in
  ppf?Pee;- The ne^PaPer ^ronicled,  the major public  opposition to that.
  PCI facility and foresaw similar problems if PCI moved to El Dorado.
  The newspaper  also quoted  the plant managers as saying that if Minnesota
  prevented them from disposing of Dioxin at their  Shakopee site  the
 material eventually would  be moved to a new incinerator planned in El
 Dorado.  The paper alerted its readers to the "lethal" nature of Dioxin
 and previous accidents that had occurred  in other parts of the country
 through mishandling of the chemical.   The paper also portrayed PCI as
 incompetent and as operated by people of questionable integrity.

 In June of 1976, PCI, in cooperation with the EPA, shredded
 approximately 7,000 pounds  of capacitors containing PCBs.  PCI had PCBs
 in storage at this time but had not yet completed construction of its
 incinerator.   The incinerator's shredder, however, was operational.
 This shredding was done under control and direction of the EPA and the
 Arkansas Department of Pollution Control and Ecology.  The shredded
 capacitors  were packaged, in drums and shipped to the Rollins
 Environmental Services incinerator at Houston,  Texas.   The PCB materials
 were incinerated by.Rollins and testing was done to  determine  the
 destruction efficiency of the incinerator while  incinerating PCB solids.
 The  results of those tests  indicated  a destruction efficiency  of greater
 than 99.99  percent.   These  tests confirmed that  incineration is  an
 effective means of  destroying chlorinated hydrocarbons such  as PCBs.

 In September  of 1976,  the Arkansas Department  of  Pollution Control and
 Ecology approved  a modification  to the  earlier  (1974)  construction
 permit.   This  allowed PCI limited operation of the incinerator for
 purposes of curing refractories and testing design calculations.
                                 283

-------
Two months later PCI suffered an accidental spill while transporting a
chemical waste to the El Dorado facility from Kansas.  Based on what
Ensco thought was in the waste load, no alarm was sounded over the
spill.  However, the load was inislabeled and severe wildlife kills
resulted along the stream where the spill took place.  The accident and
especially the mislabeling fueled public opposition to the PCI
operation.  Residents were not only fearful because wastes being brought
to El Dorado were lethal but also because if those wastes were
mislabeled, there would be no way of knowing what the dangers really
were.  These fears added to existing concerns over odors from wastes
being stored at  the PCI site.

In January of  1977 the mayor, responding to concerns over the spill and
odors and general citizens' fears over the development of a hazardous
waste facility,  appointed a committee  to investigate PCI.  On the
committee were represented local elected officials, business leaders and
the  general public.  The committee  hired a noted.consulting firm with
experience in  this area to conduct  a technical investigation of the PCI
facility and  its operation.   During the consultant's investigation,
PCI's president  answered the  public opposition with his  own letter to
the  editor.   He  admitted  to and  explained  some of  the  odor  incidents and
tried to dispel  the  fears of  fires  and explosions.   The  letter described
the  operation of the plant  and the  sophisticated monitoring systems.
PCI  also was  said to expect that the consultant's  report, OSHA reports
and  EPA ambient air  quality studies would  confirm  the  safe  operation  of
the  plant  and,  if necessary,  correct any shortcomings.   The president  of
PCI  noted that there were chemical  industries in the area producing
hazardous  materials  in much greater concentrations than those  handled  by
 PCI, and pointed out that PCI did not  generate the wastes,  but merely
 treated them and rendered them harmless.

 In February construction of the incinerator was  completed and a  month
 later it came on line.  In the summer of 1977 PCI publicly announced its
 name change to Ensco and its  intent to operate a thermal oxidation
 (incinerator) process on the El Dorado site.

 EPA had had tests conducted on the Ensco incinerator in June of 1977.
 The final report of the EPA contractor,  published in May of 1978, called
 the test one of the most intensive and exacting tests ever performed on
 a commercial-scale incinerator.  The tests were conducted on four
 consecutive days.  The materials incinerated were polychlorinated
 liquids similar in chemical structure and combustion characteristics to
 PCBs.  Test results showed the destruction efficiency to be greater than
 99.99 percent,  and confirmed the operational capability of the unit.

 In  July of 1977 a permit was granted  by the state for full operation of
 the incinerator as  long as no fuel was burned which is  recognized to  be
 more difficult  to thermally decompose than polychlorinated hydrocarbons,

-------
unless such materials were burned under test conditions supervised by
EPA and state officials.  Included in these permitted wastes were liquid
PCBs.  Public opposition to the facility continued during 1977 from
individual citizens using the paper's editorial page as a forum.  Their
opposition centered on the inherent danger of dealing with hazardous
substances, the possibility of fires, toxic fumes, plant malfunctions,
transportation spills and odors.  Odors seemed to be the most frequent
public complaint.  Although other odor-producing industries are in the
area, most of the complaints were leveled at Ensco.  One of these odor
problems was traced to Ensco's poor handling of mercaptan, an odor-
producing additive for natural gas.  The company discontinued accepting
mercaptan in an attempt to assuage public opposition, but to no avail.

In March of 1978 Ensco submitted an application to the state for
incineration of PGB solids — such as capacitors, fluorescent light
ballasts and, clean-up from spills — and PCB liquids.  Also curing
early  1978, EPA reported in a public newsletter that in cooperation with
the  state of Arkansas it had recently conducted a highly successful
incineration test at El Dorado, destroying toxic chemical wastes
(chlorinated hydrocarbons).  Ensco subsequently received approval from
the  state  to incinerate drummed solids, semi-solids and liquids such  as
PCB-impregnated capacitors.  Also, under provisions of the Toxic
Substances Control Act, EPA made a public announcement: that it  was going
to conduct a test burn of PCBs at Ensco in July of 1978.   (The  previous
test had been- of polychlorinated liquids similar  to PCBs, not of PCBs
proper.)

Public opposition was exacerbated by the announcement of the PCB test.
Because of this  opposition and  attendant political pressure, .the test
was  soon put off by EPA until September, 1978.  A local radio station
broadcast  a  strong  editorial  against  the test  burn.  The editorial
pointed out  the  extreme danger  posed  by PCBs,  which had been linked to
cancer and birth defects.  The  editorial then  asked whether  it  was in
the  community's  best  interest to have  PCBs transported to  El Dorado and
then disposed  of near populated areas; and  if  approval were  given  for
PCBs,  what toxic chemicals would be  added in the  future.   The station
received  a large number of  letters,  all  in  opposition  to  the'PCB test
burn and  Ensco.  No letters  were received in favor of  the  operation.

Under  the equal  time  provisions, Ensco responded  to  the  station's
editorial, citing  EPA's announcement in  the  Federal  Register that
incineration is  the only currently available means of  destroying PCBs.
Ensco's response described the  uses of PCBs, the  plant's  safe  operating
 procedures and the successful testing of  the incinerator  that  previously
had been done by EPA.  Ensco noted that  while  PCBs  are toxic,  they are
not flammable  and  pose no threat unless  improperly handled.

 Sensing the  rising pitch in public opposition over the PCB issue,, Ensco
 engaged a public relations expert and proceeded to run large ads  in the
 paper in support of their operation.   These  ads explained the  sources of
 PCB wastes,  alternative methods of disposal, and the Ensco facility.
                             -285

-------
 Ensco also suggested  to  the municipality  that  their  incinerator could be
 used to help them dispose of their municipal wastes.   (The capacity of
 the local sanitary landfill was rapidly being  exhausted.)

 By now the letters to the editor had dropped the odor  issue in favor of
 the more emotional PCS issue.  The opposition asked why EPA did not
 provide its own incinerator to dispose of PCBs, and the health of the
 community became the key issue.  The site was said to be too close to
 populated areas and short-term tests proposed by EPA were said not to
 answer questions about long-term effects.   Concerns were voiced about
 the safety of future generations.  Questions were again raised about
 Ensco's reputation and past track record in Minnesota.

 In the latter part of August 1978, Union County attempted to pass 'an
 emergency ordinance banning incineration,  shipment or storage of PCBs in
 the county.   The emergency ordinance failed to pass.   However,  the same
 ordinance minus the emergency status passed a week later.   In the
 intervening week,  Ensco voluntarily ceased accepting  any PCB wastes,
 hoping that the ordinance would not pass.

 In early September of 1978,  EPA held a public hearing in El Dorado on
 its proposal  to conduct a test  burn of PCBs.   The hearing  was attended
 by over 450 persons.   The testimony reiterated many of the concerns
 voiced earlier  in  the press  over the company's  financial stability, past
 spills,  fire  hazards  and their  Minnesota track record.   Witnesses  were
 brought  from  Minnesota to bolster  the opposition's  contention that the
 owners of  Ensco had a questionable past and that El Dorado did  not want
 this  type  of  operation.   Ensco  replied with its own presentation which
 restated much of the  information Ensco had already  made available  to  the
 public.  A 4,600-signature petition was introduced  into the  hearing
 record stating  citizen opposition to the EPA test burn of  PCBs.
 Petitioners felt that  the dangers  of PCBs  were  too  great in  an area
 surrounded by residential properties.   The public hearing  demonstrated
 EPA's  limited technical  role and provided  a  forum for  both sides of the
 local  issue.  The  public hearing  did not dampen public  opposition.

 After  the  public hearing, the letters  to the  editor continued to voice
 opposition to the Ensco  plant.  They  pointed  out  that out of 1,256
 personal contacts in El  Dorado,  1,200 opposed the plant and  the
 importation of wastes from out of state and out of  the  county.  The
 letters also congratulated the county commissioners for their decision
 to pass a resolution against further storage, disposal  or transportation
 of PCB materials.

 Ensco filed a complaint in the U.S. District Court  to reverse the county
 ordinance.  It argued, among other things, that the ordinance is
 unconstitutional in view of the federal Toxic Substances Control Act
which preempts local law, the interference with interstate commerce, and
 the interference with Ensco's right to engage in business.   This case
has not yet been heard but most people on both sides of the question
                               286

-------
.agree that the county has  a weak case especially  since recent state and
 federal  Supreme Court rulings  in similar  cases  have been in favor of the
 waste disposal operations.

 At the end of September,  1978,  the consultant released his final report
 to the Mayor's Committee.   The evaluation did not uncover any serious
 problems.   The Ensco staff was said to be knowledgeable, informed,
 courteous, and well trained.  The report  concluded that Ensco should be
 able to  conduct its operations without endangering or significantly
 degrading  the safety, health,  or welfare  of the community.  However,
 according  to El Dorado's mayor, there were a few blatant errors in the
 evaluation which helped discredit the report, thereby failing to
 diminish public fears over Ensco1s operation.

 At the close of 1978 the Mayor's Committee reported that Ensco was not
 the type of industry that the Committee would solicit for location
 inside the city limits of El Dorado or immediately adjacent to-it.
 However, the Committee's role was not to recommend an industry for El
 Dorado but rather to evaluate an existing industry.  Based on available
 data, the Committee felt that with upgraded facilities, a careful
 monitoring program, a system of periodic inspections, and a system  of
 approvals by state and federal authorities for each new waste stream to
 be handled, the Ensco facility could  be  safely operated.

 The Mayor's Committee went  on  to note that a citizens group had  recently
 been  formed to become involved in environmental  issues  concerning
 Ensco's operations.   The Committee was concerned over whether  a  local
 group could possibly have  the  technical  expertise  to  evaluate  so
 sophisticated  a  technology as  environmental  impacts.   It  felt  that such
 a group would  become  simply a  publicity-oriented sounding  board  for real
 and  imagined  issues.

 The  group known  as the  Citizens for  a Safe Environment was incorporated
 in  January of  1979 with the purposes of  promoting a safe environment by
 advising  the  public of  environmental abuses,  educating- industry and the
 public, and securing community support for environmental matters.   A
 spokesperson for the group said that it  was  up to the people rather than
 the government to monitor the actions of Ensco.

 No  further action is taking place regarding  the  PCB test burn until the
 court case over the county ordinance is  settled.  However, it appears
 that public opposition will not be a determining factor in EPA's de-
 cision to approve or not approve the Ensco application to incinerate
  PCBs.  EPA's decision will be based on technical grounds regarding stack
  emissions and residues.  The State Department of Pollution Control and
  Ecology is in a similar situation.

  IV.  '  CHRONOLOGY OF EVENTS

   1971 ~ Amoco donates abandoned refinery property to Union County
          to be used for industrial development purposes.
                                 - f\
                                  287

-------
 1973 — County reaches  lease-purchase agreement with El Dorado
        Industrial Development and a private individual associated with
        Ensco for 45-acre  tract within  the former refinery.  Ensco
        initially approaches DPCE about hazardous waste incinerator.

March, 1974 — Sub-lease agreement is made between a private individual
               and Graco Properties (later Ensco) for part of the re-
               finery property, to be used as the site of a hazardous
               waste incinerator.

July, 1974 — DPCE grants  Ensco a construction permit for incinerator.

1975 — PCI (a Shakopee, Minnesota chemical waste facility) is closed
        following complaints from local residents and disputes with the
        Minnesota Pollution Control Agency.  Ensco1s future plant en-
        gineer presents description of projected Ensco operations to lo-
        cal elected officials and civic groups.  Local newspaper begins
        a campaign opposing the Ensco facility.

June, 1976 — Ensco, in cooperation with the EPA, shreds approximately
              7,000 pounds of capacitors containing PCBs, and ships them
              to the Rollins Environmental Services Incincerator.

September, 1976 — The Arkansas Department of Pollution Control and
                   Ecology approves a modification of an earlier (1974)
                   construction permit.  This allows Ensco limited oper-
                   ation of the incinerator for curing refractories and
                   testing design calculations.

November, 1976 — Ensco suffers an accidental spill while transporting a
                  mislabeled chemical waste to the El Dorado facility.
                  Severe wildlife kills result.
January, 1977 — Mayor's committee is formed to investigate the Ensco
                 operation.  The commitee hires a consulting firm to
                 conduct a technical investigation of the Ensco facility
                 and its operation.

February, 1977 — Incinerator construction completed.

March, 1977 — Incinerator comes on line.

June, 1977 —EPA contractor conducts tests on the Ensco incinerator.
             These tests confirm its operational capability.

July, 1977 — The Arkansas Department of Pollution Control and Ecology
              grants Ensco a permit for full operation of the
              incinerator so long as no fuel is burned which is
              recognized to be more difficult to thermally decompose
              than polychlorinated hydrocarbons.
                                288

-------
March, 1978 — Ensco submits an application to the state for permission
               to incinerate PCBs.  .Permission is received shortly
               thereafter.

Spring, 1978 —• EPA makes a public announcement that it is going to con-
                duct a test burn of PCBs at Ensco in July, 1978.  Due to
                intense public opposition, this test is postponed until
                September.

August, 1978 — Ensco voluntarily ceases accepting any PCB wastes.
                Union County passes an ordinance banning the
                incineration, shipment or storage of PCBs in the county.

September, 1978 — EPA holds a public hearing in El Dorado on its
                   proposal to conduct a test burn of PCBs.  The hearing
                   does not dampen public opposition.  Ensco files suit
                   in U.S. District Court to reverse the county ordi-
                   nance.  Consultant's report concludes that Ensco
                   should be able to conduct its operations without en-
                   dangering or significantly degrading the safety,
                   health or welfare,of the community.

December,  1978 — Mayor's committee reports that the Ensco facility
                  could be safety operated.

January, 1979 — Citizens for a Safe Environment incorporated to advise
                 the public of environmental abuses and, in particular,
                 to monitor Ensco's operations.
V.
ATTEMPTS TO SECURE SUPPORT
In an effort to secure local support for their operations, Ensco under-
took several actions.

       o     They  hired  a  public  relations  consultant  and  took out
             several newspaper ads  to help  the public  understand the
             nature of the wastes being processed,  the incineration
             process itself, the  safety precautions, and the reasons for
             locating in El Dorado.

       o     They  responded to media editorials  and letters to the
             editor with their own  letters  and public  notices.

       o     They  participated in talks to  local civic and government
             groups.

       o     They  complied with and advertised their degree of
             compliance  with federal and state regulations.

-------
 VI.
o     They suggested the future use of their incinerator to help
      the city dispose of municipal wastes.  (The local sanitary
      landfill was rapidly being exhausted.)

o     They cooperated with outside tests and evaluations of their
      facility.

SUMMARY EVALUATION
 The  conflict  over Ensco's  operation in El Dorado  has  not been resolved.
 Although the  company is operating at the moment,  incinerating chemical
 wastes  that are  less dificult  to dispose of  than,PCBs,  they have yet  to
 win  EPA approval for the commercially attractive  PCB  disposal.   Their
 attempts to gain public support  have failed  and the emotional level of
 the  controversy  has risen.

 The  company's attempt to educate the public  and to comply with state  and
 federal regulations has missed the  point of  public concern.   The,
 citizens of El Dorado do not want to be educated  on hazardous waste
 disposal or on safety precautions.   Their concern seems  to be over the
 past and present integrity of  the owners and the  physical image of the
 site, and of  course, over  the  potential hazards associated with PCBs.
 More attention to and display  of open and above-board business  dealings
 as well as to site appearance  may have done  more  good than all  the
 technical education on chemical  wastes and their  treatment.

 Ensco may well gain all the necessary state  and federal  approvals to
 expand  their  existing incineration  facility  to  handle PCBs.   They also
 stand a good  chance to win their court case  against a local county
 ordinance banning PCBs.  However, a significant part  of  the local
 population will  remain frustrated in their attempts to not have
 hazardous wastes  imported  to El  Dorado  for disposal.  The major issues
 in this controversy are:

 PCB  disposal  —  The hazardous  nature of PCBs  has  generated a highly
 emotional opposition to  their  disposal  regardless  of  the manner of that
 disposal.

 Operational and  other problems connected with the  facility —Odors at
 the  facility,  the  unpleasant appearance of the  facility,  and  a  spill of
 wastes  en route 'to the facility  have been major sources  of complaints.
 The  mislabeling  of spilled  wastes added to general  concerns about the
 nature  of wastes  handled at the  facility.                .-.,..        ,

 Importation of wastes  — Because many  of  the  wastes are  delivered from
 out  of  state, residents feel they are bearing the  burden of others'
 problems.  They  do not want El Dorado  to  become a  dumping ground for
 other states.                                                 ,

 The  integrity  of Ensco — Based  primarily  on major  problems with the
Minnesota landfill,  citizens have serious  questions as to the ability of
 Ensco to operate the  incinerator  in a safe and  efficient  manner.

-------
Local control and the unresponsiveness of regulatory agencies — Local
officials in response to citizen pressure have tried to establish local
controls over Ensco.  Opponents feel that DPCE and EPA, in only
addressing technical questions, fail to consider other equally important
questions.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

The factors contributing to public opposition are:
       o     Poor image of the owners based on questionable track record
             of waste disposal in Minnesota, inadequate financial re-
             serves, past accidental spills en route to Ensco, and the
             appearance of wheeling and dealing in connection with site
             acquisition.

       o     Most of the wastes are imported from out-of-state sources.

       o     The company's management is made up of out-of-state
             individuals with no previous business history in the area.

       o     The site is situated in an industrial park but too close to
             the city limits and populated areas.

       o     The site is visually unattractive with, rusting storage
             tanks arid construction debris.

       o     National news on cancer and birth defects attributable to
             PCBs has fueled local editorials in opposition to Ensco1s
             operation.

       o  •   EPA is viewed by the local public as having an interest in
             only the technical merits of the facility and unable to do
             anything about local public opposition.

VIII.  RETROSPECTIVE VIEWS

The final outcome of the Ensco operation is still uncertain.  The case
against the county ban on PCBs is still in court and public opposition
to EPA's forthcoming test burn is still strong.  Very few participants
in this situation had any comment as to what could have been done dif-
ferently.  Ensco felt that they should have started their public re-
lations campaign earlier, prior to the PCS controversy.  They also felt
that had they set up a local corporation with local financial interests,
the opposition might have been reduced or at least there could have been
more support.                               .

State comments are listed in the state agency write-ups elsewhere in
this report.

-------
                               CALABASAS

                LOS ANGELES COUNTY SANITATION DISTRICTS
                        LOS ANGELES, CALIFORNIA
I.     INTRODUCTION

The Los Angeles County Sanitation Districts' (LACSD) Calbasas landfill
began operations in 1961 and began accepting hazardous wastes in 1965.
Several years later, however, a residential development was constructed
immediately adjacent to the facility.  When the LACSD announced in 1973
that it planned to move its operations closer to and into the view of
the housing development, they met with intense opposition from the
residents of this development.  The issue was not resolved at that time.

Although the LACSD did meet with community leaders regarding the
dispute, their overall strategy was to maintain a low profile.  It has
become apparent to them that this approach has not been particularly
successful.  They now plan to adopt a more open policy when they bring
the issue up again in the next year or so.

II.    BACKGROUND INFORMATION

The Calabasas landfill site, which is owned and operated by the LACSD,
occupies a total area of 416 acres.  A conditional use permit has been
obtained for the whole site.  However, only 300 acres are covered by
Regional Water Quality Control Board Waste Discharge Requirements.  Of
these 300 acres, 260 are planned for the disposal of Group 1 and Group 2
wastes, and the remaining 40 acres for Group 2 wastes only.-'-  The
remaining area is comprised of an 80-acre parcel to the north of the
site and a 30-acre parcel to the east.  The LACSD plans to apply for
Waste Discharge Requirements for use of these parcels as Group 1
disposal sites.

The site is located approximately one-half mile north of U.S. Highway
101 (the Ventura Freeway), one mile east of Agoura, California.   It is
surrounded on the east, west and north by undeveloped land which is
used, if at all, for grazing or oil producing operations.  Immediately
   Group 1 wastes are defined to include those wastes which consist
   of or contain toxic substances.  Group 2 wastes consist of or contain
   chemically or biologically decomposable material which does not
   include toxic substances nor those capable of significantly impairing
   the quality of useful waters and includes municipal solid waste.
   Group 3 wastes consist entirely of nonwater soluble, nondecomposable
   inert solids (California State Water Resources Control Board).  A
   Class 1 landfill can accept wastes in Groups 1, 2, and 3.

-------
to the south of the site, between i"t and the Ventura Freeway, is located
a development of moderately expensive suburban homes.  The population of
this community is comprised mainly of upper-middle income professionals.
(House values are in the range of $150,000-$200,00d).

The site is underlain by sandstone conglomerates and shales.  Steep dips
in these layers of material restrict horizontal movements of liquids, so
that wastes deposited in the greater part of the site will be
hydraulically isolated from groundwaters of adjacent canyons.  Test data
indicate permeability values of 10-20 gallons per day per square foot.
The only exception to this is a small alluvial area which is not
approved for the dumping of hazardous wastes.

The landfill handles municipal solid wastes as well as hazardous solid
and liquid wastes.  The  operation of the facility is as  follows.  Early
each day a tractor builds a dam of municipal wastes, and a  "pond" is
formed between the dam and the previous day's wastes.  Hazardous liquid
wastes are dumped into this pond and municipal wastes are then pushed in
to absorb the liquid.  At the end of each day the pond is filled with
refuse, compacted and covered with earth.  Liquid wastes disposed of in
this manner  include relatively innocuous substances  such as  oil field
brines and paint sludges.  Odorous, flammable or reactive liquids are
disposed of  in injection wells which have been drilled into  areas
previously filled with refuse. .Hazardous solid wastes and  other special
wastes are buried in excavations in the waste pile.

The facility accepts two general classes of  hazardous wastes.  The  first
is oily waste from petroleum refineries.  The second class  includes
biological products such as discarded  culture .tests, chemicals from
manufacturing industries, spent acids  and caustic solutions  from the
metal finishing  industry, pesticides,  tannery wastes, and  refined
petroleum products.  These wastes may  present more of a  hazard —
they are often  reactive, toxic, flammable, or  infectious and must be
handled with care.  The  Calabasas landfill is not suitable  for and  does
not accept very  hazardous  or highly reactive wastes  (for example,
cyanide and  water reactive wastes), except in  small  quantities.
Explosives and  radioactive wastes are  not  accepted at  all.

The facility currently  accepts approximately 2,400 tons  of  wastes per
day,  including  250  tons  per day of hazardous wastes.   The  existing
 disposal  area  has  capacity for another 15  million cubic  yards of  refuse;
if disposal  is  ultimately  permitted  on the whole  site, remaining
 capacity may be on the  order  of  50 million cubic  yards.   Given current
densities'of approximately 1,4'00  pounds  per  cubic yard,  the life
 expectancy of  tiie existing disposal  area is  approximately  13 years, and
 is  40 years  or  more if  the whole  site  is  permitted.

 The  facility serves  western Los  Angeles County and  to  a  lesser  extent
 Ventura County.   However,  even wastes  from out of state  have been
                                - Oi
                                 293

-------
accepted in the past.  The LACSD operates one other, very similar
hazardous/municipal waste landfill at Palos Verdes.  However, they plan
to close this site in 1980.  In addition, there is a commercial
hazardous waste management facility in West Covina and one is currently
proposed in the Sauges/Newhall area.  Los Angeles County is the
industrial center of southern California.  Major industrial sectors
which produce significant amounts of chemical wastes include
electronics, petroleum and natural gas.  The area is also a major
agricultural center.
II.
HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE
In order to develop and operate a hazardous waste management facility in
California, at least three permits are needed.  These are: 1) a land use
permit, 2) Regional Water Quality Board Waste Discharge Requirements
(permit), and 3) State Department of Health Services permit.   The land
use permit, which is issued by the local city or, in unincorporated
areas, county planning board, certifies that development and operation
of the proposed facility would not conflict with existing land use or
land use plans.  In practice, it indicates that the facility has local
political support.  A significant factor in gaining this support is
facility compatibility with local land use.  This permit is a
precondition for the granting of the other two permits.  The decision of
the local planning board can be appealed to the local board of
supervisors.

The Regional Water Quality Control Board Waste Discharge Requirements
specify what kinds of wastes the facility may receive and what measures
must be taken to prevent groundwater and surface water pollution.  These
requirements are in effect a permit since they will not be issued ,if the
geology and/or hydrology of the site are inappropriate. The State
Department of Health Services permit is for the most part based on the
existence of proper procedures for above-ground handling of chemical
wastes.  These procedures must include a contingency plan for "an
accident or accidental discharge."

In addition, two other permits are often required, depending on the
particular types of storage, processing or disposal of chemical wastes
that are proposed.  If hazardous wastes are to be codisposed with
municipal solid wastes, then the state Solid Waste Management Board must
grant a permit for the facility.  This permit regulates the disposal of
residential and commercial refuse so that nuisances are not created.
The Solid Waste Management Board may authorize local political entities,
such as the local city or county government, the power to issue
municipal waste permits.

If some sort of evaporation, neutralization or incineration process or
any other process which will produce a significant amount of atmospheric
   California Department of Health Services, Hazardous Waste
   Regulations, Chapter 2, Article 4, "Hazardous Waste Permit".
                                -294

-------
emissions is proposed, a permit will be required from the Regional Air
Pollution Control District.  Evaporation ponds, for instance, are
treated as emission points.  Depending on existing, air quality in the
region, this permit can be very restrictive as to types of processes
and/or wastes accepted.  Permits may also be required from agencies such
as the Coast Regional Commissions if the proposed site is located in any
of the areas which are under their purview.

The Calabasas landfill required a land use permit and permits from the
Regional Water Quality Control Board, the State Department of Health
Services, and the State Solid Waste Management Board.  In this case,
permits were not required from the Regional Air Pollution Control
District and the Coast Regional Commission.          ;

The LASCD began planning for a municipal solid waste landfill in the
western part of Los Angeles Country during the late 1950s.  This
planning was in response to increasing residential and commercial
development in that part of Los Angeles County.  There were no
publicly operated landfills in this area prior to that time.  The
Calabasas site was one of several considered, and was chosen on the
grounds of its superior access and geology.  In the spring of 1958, Los
Angeles County made application to the Regional Planning Commission-
(RPC) for a zone exception (land use permit) approving the use of the
Calabasas site as a landfill.  A public hearing on the zone exception
case was held on May 23, 1958.  Several persons spoke in opposition to
the zoning exception, on the grounds that the facility would be
detrimental to a proposed school and to the health, safety and general
welfare of property owners in the vicinity.  The Zoning Board
nevertheless approved the application.  However, because the LACSD did
not begin dumping in the next two years, the zoning exception expired.
The county submitted a request for a new exception to the RPC on
September 12, 1960.  This was approved on October 4 and forwarded to the
County Board of Supervisors, who approved it on April 25, 1961.

Meanwhile, the Regional Water Quality Ccontrol Board had, in December,
1960, set requirements for waste discharge at the Calabasas landfill.'
The site at that time was planned to accept only Group 2 and 3 wastes,
i.e., non-hazardous wastes.  The site began operating in mid-1961, '
accepting only Group 2 and 3 wastes.  In 1965, the LACSD announced its*
intention to adapt the Calabasas landfill so that it could accept
certain Group 1 wastes.  Group 1 waste discharge requirements for the
Calabasas landfill were adopted by the Regional Water Pollution Control
Board in September, 1965, and Group 1 industrial wastes, subject to some
limitations, were accepted beginning in late 1965.

During the development and first several years of operation of the
Calabasas landfill, the surrounding land was largely undeveloped.  The
only uses found there were grazing and oilfield operations.  In 1968,
however, a developer purchased the tract of land lying between the
landfill and the Ventura Freeway.  The eastern and northern border of
this parcel is bordered by the access road to the landfill.  As a
                               '295

-------
condition of the site, the previous owners of the land petitioned the
RFC for a change in the zoning of the parcel from heavy agricultural to
residential.  This petition described the surrounding area as "presently
undeveloped acreage," and made no reference to the adjoining landfill.
The zoning change was granted in June, 1964.  The parcel, subsequently
named Saratoga Hills, was developed in three phases.  Development of the
first tract, furthest away from the landfill, was begun in 1968; the
second, in 1969, and the third, in 1972.  (The parcel is now almost
fully developed.)  The information sheet on the development provided to
prospective property owners1 during the first two phases made no
mention of the landfill.  The one provided during the third phase states
that the "tract is located three-fourth mile south of dump site (sic).
Heavy truck traffic along north side of tract may be noticeable to
prospective residents."

Notwithstanding the proximity of the landfill to the development, there
were no recorded complaints about it or its operation until 1973.  In
July of that year, the LASCD posted a sign — in two canyons located 350
feet from the closest homes — which stated that they intended to use
these canyons as landfill space in the near future.  Prior to that time,
all dumping operations had been carried out in the back part of the
landfill, behind a ridgeline and out of sight of Saratoga Hills
residents.  A local association — the Community Association of Saratoga
Hills (CASH) had been established earlier as a forum for concerns.  CASH
became the focus of opposition to the proposed movement of landfill
operations in the front canyons.  At a meeting of CASH officers in
September, 1973, it was decided to call a general meeting of the
community to decide how to respond to the LACSD action.  Such a meeting
was held in autumn of 1973, and was well attended.  The primary concern
of local residents was the effect the new landfill area would have on
their view of the hills.  Other concerns included those related to
odors, rats and other scavengers, landslides, fires, spills, and the
behavior of truck drivers.  Residents reported that truck drivers had
been involved in several unpleasant incidents, including shouting
obscenities at teenage girls in the tract.  In subsequent months,
concern was expressed over the geology and hydrology of the front
canyons, which were said by local residents to be inappropriate for a
landfill.  At this meeting it was decided that the strategy CASH would
adopt in opposing the landfill extension would be to approach their
local political representatives, as well as the LACSD, to try to have
the decision revoked.  Therefore, starting in late 1973 and continuing
through mid-1975, CASH representatives met several times with their
state representatives, the Los Angeles County Supervisors, the RFC and
the LACSD in an attempt to gain support for their plans.1  These
meetings had some immediate results but were ultimately inconclusive.
   Since these meetings were informal, and since many of the
   principal participants have left either the development or the
   respective government agency, neither their dates nor precise
   sequence could be determined.

-------
CASH did get support for its position from the local state senator,
assemblyman and County Supervisor, and as well.from the Los Virgenes
Homeowners' Association, the Agoura-Los Virgenes Chamber of Commerce and
the Los Virgenes School District.  The County Supervisor directed the
LACSD to work out an agreement with CASH, and proposed that they should
operate only in the back portion of the site.

The LACSD offered to resolve the dispute by moving the landfill access
road away from and out of sight of the development (at a cost in excess
of $1 million).  They also informed the community that, if dust or trash
from the landfill was blown onto their property, they had only to call
the LACSD to have it quickly removed.  However, the LACSD refused to
limit their operations to the back part of the landfill.  They noted
that this would reduce the capacity of the landfill by 60 to 70 percent.
This counter-offer was accepted at first by CASH officers, but the
membership as a whole voted to reject it, because the front canyons
would still have been used as landfill space.  Although discussions
continued in 1975, no progress was made, arid the result was a stalemate.
During their meetings, the LACSD made some attempt to respond to local
concerns.  They stated that if the landfill is properly operated t;here
should be no danger of rats, landslides or fires.  They did acknowledge
that there have been some spills of materials along the access road.
Local residents reported in this regard that they have had difficulty
getting the county health department to investigate spills, and that on
one occasion when they did come, the material was sent to LACSD for
testing, in the residents' eyes a not unbiased evaluation.  As recently
as April, 1978 a truck on its way to the landfill overturned and spilled
its load of construction wastes onto a car parked next to the housing
tract, wrecking it but causing no injury to its occupants.  On the other
hand, the LACSD has found a way to keep seagulls away from unburied
garbage — by  stringing wires which interfere with their flight above
the current waste area, and they are currently undertaking a full-scale
investigation of site geology and hydrology to determine whether these
are suitable.

Another issue which was frequently raised, but which was not at all a
point of contention between CASH and the LACSD, .was the incorrect
information about the landfill which the developer had provided to
prospective property owners.  Furthermore, residents reported that the
developer stated as far back as 1969 that the landfill would become a
park in "10-15 years".  To compound the confusion, residents also
maintained that the L.A.  County Regional Planning Commission until
recently had the Calabasas landfill on its maps as a park.  As noted
above, if the whole landfill is developed, it will not become a park for
another 30-50 years.

Since 1973, when the dispute first surfaced,  residents have become more
aware and thus more concerned about the dumping of hazardous wastes in
this facility.  In October of 1976, 2,500 gallons of nitric acid were

-------
pumped into a well containing traces of sulfuric acid.  The resulting
reaction sent a cloud of toxic gas over the Saratoga Hills tract, but
the gas was dissipated before it reached the ground.  Local residents
have indicated that aesthetic concerns are still primary in this
dispute, but that they expect the safety of hazardous waste operations
to be an issue when the LACSD again moves to bring its operations into
the front canyons.

The LACSD has decided not to pursue moving into the front canyons until
a year and a half from now.  At that time they intend to conduct
workshops and if necessary use other means to•open lines of com-
munication to the community in order to amicably resolve, if possible,
the dispute.1  LACSD attorneys have determined that they must file an
Environmental Impact Report if they wish to expand the landfill into the
front canyons.  It is expected that the EIR will be prepared and
submitted in or. about 1980, and that local residents will at that time
file suit to overturn the EIR and in that manner prevent dumping near
their homes.
IV.
CHRONOLOGY OF EVENTS
June, 1958 —The Los Angeles County Regional Planning Commission (RFC)
              grants the LACSD a zone exception, approving the use of
              the Calabasas site as a disposal facility.

June, 1960 — Zone exception expires.

October, 1960 — RFC again grants LACSD zone exception for the Calabasas
                 landfill.

December, 1960 — The Regional water Quality Control Board adopts Class
                  II waste discharge requirements for the landfill.

April, 1961 — The Los Angeles County Board of Supervisors approves the
               zone exception for the landfill.

Summer, 1961 —The Calabasas landfill begins accepting Class II and III
                wastes.

1963 — Developer acquires the parcel of land between the.landfill and
        the Ventura Freeway.  The land is rezoned from heavy
        agricultural to residential.                             .
   Workshops differ from public meetings in that the number of
   public attendees is limited and there are relatively many staff
   members from the sponsoring organization — one for every eight or so
   of the public.  In this way all questions can be answered and public
   input received.  Furthermore, the discussion format is not so
   conducive to confrontation as that of the typical public meeting.
                                '238

-------
 965 — LACSD applies for and receives Regional Water Quality Control
        Board Class I requirements for the Calabasas landfill; begins
        accepting Group 1 wastes.

1968 -— Construction of housing is begun on parcel of land between
        landfill and highway.

July, 1973 — The LACSD posts a sign in the front canyons— in close
              proximity to the housing development — announcing its
              intention to begin dumping in these canyons in the near fu-
              ture.

September, 1973 — Officers of the Community Association of Saratoga
                   Hills (CASH) decide to hold general meeting to organ-
                   ize opposition to the landfill extension.

October, 1973 — General meeting is held.  Decide to approach local
                 politicians to try to revoke LACSD decision to move
                 operations into the front canyons.

Autumn, 1973/Winter, 1974 •— CASH representatives meet with local
                             politicians, RFC and LACSD to try to gain
                             support for their position.

Summer, 1974 — The LACSD offers to change the route of the access road
                but refuses to consider limiting dumping to the back
                part of the site.  CASH refuses to accept this offer.

Autumn, 1974/Summer, 1975 — Meetings between CASH and, respectively lo-
                             cal officials and the LACSD continue, but
                             to no avail.

October, 1976 --Accidental mixing of two acids in landfill sends cloud
                 of toxic gas over the housing development.

1980 — Expected date of the LACSD EIR on the movement of operations to
        the front canyons, and of CASH action to overturn the EIR and
        prevent the movement.
V.
ATTEMPTS TO SECURE SUPPORT
During the early stages of this dispute, the LACSD underestimated the
effect public opposition could-have on their activities.  Therefore, at-
tempts to secure support were limited.  These attempts included the fol-
lowing:                                    ;

       o     Meetings were held with CASH representatives to attempt to
             settle the dispute.

-------
VI.
o     The LACSD offered to re-route the access road to take it
      further away from residences, in return for CASH support
      for their using the front canyons.

o     The LACSD promised to take immediate action to remove any
      dust or trash blown from the site into the housing tract.

SUMMARY EVALUATION
The LACSD has not yet solved its problem at the Calabasas landfill.
They acknowledged that gaining local public acceptance would have been
considerably easier if they had invested more time in working with the
public.  For instance, it was not wise  to announce that the LACSD
expected to be dumping soon in the front canyons merely by erecting a
sign which said as much.  Consultation  with community leaders might have
given them a better chance at gaining initial approval.  Furthermore,
while their response to the public outcry against this dumping did
indicate that they were aware of the threat that this opposition posed,
it was not sufficient to head it off.   Subsequent public relations
efforts made by the LACSD at other landfills were more sophisticated
(see below).

An official of the Regional Water Quality Control Board commented that
the mere fact that the landfill had preceded the residences should not
be relied upon to ameliorate public relations problems.  He felt that
this would make little if any difference to the perspective of local
residents.

The issues and concerns raised by the local residents during the attempt
to move operations included the following:

Aesthetics — One of the amenities which this housing development has to
offer is the view of the surrounding hills.  Local residents object to
dumping in the front canyon because this view would be adversely af-
fected.

Facility operations —  There was considerable feeling in the local com-
munity that the landfill is not operated as competently as it might be,
and that their problems as a result of  this"would be exacerbated if the
landfill operation was that much closer to their homes.  Particular con-
cerns include odors and blowing trash and dust.

Traffic — The truck traffic to and from the facility is considered by
local residents to be both a safety hazard and a nuisance.

Hazardous wastes — Following the accident in 1976, residents have be-
come concerned about the possibility of a serious accident or fire due
to mishandling of hazardous wastes.   They percieve that the danger will
be greater if these operations are closer to them.
                               300

-------
Site Suitability — Local residents have questioned whether the geology
and hydrology of the front canyons are suitable for landfilling, and
particularly for hazardous waste disposal.  LACSD's analysis may resolve
this issue when it is complete.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

The following factors can be said to have led to public opposition to
the proposed dumping in the front canyons.

       o   .  Residents' reaction to discovering the proximity and ex-
    ,         pected life of the landfill after having been misled by the
             developer.

       d     The anticipated impact of this dumping on the aesthetics of
             the area.

       o     The LACSD's announcing their plans to dump in the front
             canyons by posting a sign to this effect.

       o     Incidents involving truck drivers and the local residents,
             including but not limited to traffic accidents.

VIII.  RETROSPECTIVE VIEWS

The LACSD in retrospect perceived two major problems in their handling
of the Calabasas landfill.  The first was their failure to provide for
buffer space around the landfill.  Their experience shows that the mere
fact that land around a landfill is zoned for agricultural (or other
non-residential) use when the landfill is sited should not be grounds
for assuming that no residences will ever be built there.  Zoning is not
an adequate tool to prevent residential development.  The only exception
to this need for buffer space would be if the facility is located in a
developed industrial area.

An official with the Regional Water Quality Control Board commented,
similarly, that land use questions are very important in siting
hazardous waste facilities.  By this he meant not just adjacent land but
also any development expected in proximity to the planned facility
during its lifetime.  It is necessary first that some provisions be made
for a permanent buffer zone unless existing surrounding land use is not
only compatible but very likely to remain so.  He recommended that local
planning commissions not be free to allow subdivisions near existing
sites.         ,                                           ,

The second LAGSD critique of their own strategy relates to the
low-profile approach to public relations they had adopted at that time.
They now feel that it is necessary to make the public aware of their
operations, but recognize that this in and of itself is not sufficient
to guarantee public acceptance.   Local residents seemingly agree with
the latter point.  They felt that they had had a very difficult time
getting information from the LACSD.
                                301

-------
Some of these ideas have subsequently been put into practice.  When
residential construction began around their Palos Verdes landfill, the
LACSD attempted to ensure that all prospective purchasers were aware of
the landfill, and even offered tours of the operation to anyone who
wanted them.  When people had moved into these houses, workshops were
held to describe the operation, to answer questions and to make clear to
the residents whom they could get in touch with if there were any
problems.  However, the public relations problem at this particular
landfill was not so difficult because the landfill was to close in five
years or so, and part of it which had already been closed had been
converted to a botanic garden.  Notwithstanding these very significant
differences, the LACSD now believes that if it were possible to
virtually eliminate public opposition at Palos Verdes, it will also be
possible to do so at Calabasas.  One tactic they are considering is to
fill in the front of the "front canyons" first, had thereby construct a
barrier between their operations and the housing development.  They do
realize that a major problem they still face is that of correcting the
effects of past bad publicity.
                             -302

-------
                       SCA/EARTHLINE,  INCORPORATED

                          WILSONVILLE,  ILLINOIS
,1*
INTRODUCTION
 Earthline,  Inc., a  private  disposal  company  which  is  now a  division of
 SCA Services  of Boston,  Massachusetts,  is  currently appealing a "circuit
 court  decision which  required  them to close  a  hazardous  wast,e landfill
 in Wilsonville, Illinois/   In  1976 the  Illinois  Environmental Protection
 Agency (IEPA)  granted Earthline  a  permit to  operate the  facility.
 However,  five months  after  the start of operations, local townspeople
 learned of  a  shipment of PCB-contaminated  soil to  the facility and
 within a  matter of  days  became violently opposed to it.   The town  (and
 shortly thereafter  the state Attorney General) .took Earthline to court
 to close  the  facility and subsequently  won their case at the circuit
 level.

 Most attempts  to secure  public support  for the Earthline facility
 occurred  prior to  this litigation.   During the litigation,  only one
.(unsuccessful) attempt was  made  to regain  public support.   However,
 support was received  from industry,  state  and  local officials during
 this time.  Since the resolution of  the lawsuit  is still in doubt,  the
 effectiveness of this support  is not yet apparent.
 II.
BACKGROUND INFORMATION
 The Earthline hazardous  waste management facility occupies approximately
 130 acres,  90 of  which are  within the  boundaries  of  the  village  of
 Wilsonville,  Illinois.  This land is the site of  an  abandoned
 underground coal  mine  formerly owned by the Superior Coal Company.   The
 general geological profile  of the site shows a surface layer of  about 10
 feet of loess (wind blown silt and clay material) underlain by about 40
 to 65 feet  of till material.  Permeability studies conducted during site
 design measured a permeability of 10-^ cm/sec for the till material.
 About 40 acres of the  site  is covered  by a pile of mine waste (or "gob
 pile") made up of coal,  shale and clay.   No reclamation  procedures  had
 been carried  out  after the  mine was closed.  Water passing through  the
 gob pile had  become acidic  due to oxidation of the pyrites in the waste.
 The landfill  was  designed so that excess soil from the trenches  in  which
 wastes were buried would be used to cover the surface of the gob pile.
 This would  retard the  flow  of water into the pile and thus reduce the
 flow of acid  mine drainage.

 The site is bordered on  the north by residential  land in the village of
 Wilsonville and on the east, west and  south by agricultural and/or
 undeveloped land.  The waste burial area is located  one-quarter  mile
 from the northern boundary  of the site.   The facility's  main gate is
                               303

-------
 located at the end of the main street of Wilsonville.   While the
'facility's burial area is not immediately visible from the village,
 on-site buildings and the surrounding fence are within 100 feet ,of some
 residences.  Truck access to the site is via Wilsonville1s main street.

 The hazardous waste facility is primarily a landfill,  but  also includes
 facilities for short-term storage of recyclables and for landfarming of
 waste.   All types of hazardous wastes were accepted by the facility,
 with the exception of radioactive wastes, strong acids and explosives.
 Although the site is reported to have received wastes  from as far away
 as Texas, industries from the St. Louis area comprise its  primary
 market.  The site is projected to have a 20-year landfill  capacity.

 Provisions for long-term post-closure maintenance of the site were in
 accordance with state regulations (i.e., Illinois Pollution Control
 Board Rules and Regulations).  Currently, these require that:

        The owner or operator of a sanitary landfill shall  monitor gas,
        water and settling at the completed site for a period of three
        years after the site is completed or closed.

        The owner or operator shall take whatever remedial  action is
        necesary to abate any gas, water or settling problems which
        appear during the three-year period.

 These regulations are expected to be amended shortly to comply with RCRA
 requirements.

 Originally a privately owned corporation, Earthline was purchased in
 October of 1976, by SCA Services of Boston, Massachusetts.  The
 Wilsonville facility is one of four hazardous waste management
 facilities owned by SCA.  Others are located in New Jersey, New York,
 and South Carolina.  SCA is the third largest waste services company in
 the nation and reported total corporate revenues of over $180 million in
 fiscal 1978.

 The population of Wilsonville (700) is comprised largely of low- to
 middle-income Italian and Polish-Americans whose principal sources of
 employment are the coal mines in the area.  Wilsonville is located in
 Macoupin County, about 50 miles northeast of St. Louis, Missouri and 60
 miles south of Springfield, Illinois.  The economy of Macoupin County is
 based largely on farming and mining.  Area residents also  commute to
 employment centers in the East St. Louis metropolitan area.

 III.   HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE

 The state of Illinois preempts any local regulatory control over the
 siting of hazardous waste facilities.  Regulatory powers rest with IE PA.
 The IEPA landfill permit process is a three-step process.   First,
                                304

-------
 application must be made, for a permit to develop the site, at which time
 a complete description of the site and proposed processes must be
 furnished to IEPA.  If this permit is granted and development proceeds,
 then the finished site must be: inspected by IEPA personnel to ensure
 consistency with the site descriptions in the development application
 and with State of Illinois regulations.  Only then can an operating
 permit be issued.  Finally, supplemental permits are required for each
 type of hazardous waste from each given source.

 Earthline, Inc., was chartered in 1974 by a Springfield, Illinois
 consulting engineer who had previously served as manager of the IEPA
 division of land pollution control.  He has stated that he had become
 aware of serious environmental problems caused by co-disposal of
 hazardous and municipal wastes—then and now a common practice in
 Illinois.  Therefore, given the likelihood of more stringent state and
 federal regulation of industrial waste disposal, he thought that a
 hazardous waste management facility would be a good investment.

' After leaving IEPA to found his own consulting engineering firm, he
 began a search for an appropriate site for a hazardous waste facility in
 Illinois.  Primary considerations in the site selection process were
 proximity to major industrial areas,  hydrogeological data, and whether
 the area surrounding the site was developed.

 Several sites were considered.   The Wilsonville site which was
 ultimately chosen had first been considered as a possible recreational
 site in connection with another project of his.  The site is,  however,
 partially covered by a pile of  mine wastes and had also been used as an
 open dump by village residents.   This rendered it unfit for recreational
 use.   Earthline's founder indicated that it then occurred to him that a
 mine slag pile reclamation operation and a hazardous waste landfill
 might be able to operate in concert,  such that earth removed in  burying
 hazardous wastes would be used  to cover the mine slag pile.

 At some point in late 1975 or early 1976,  he reached an agreement with
 the owner of the site on the financial terms under which the site could
 be developed.   The original site owner retained ownership of the land.

 The inital application,  submitted in February of 1976,  proposed  five
 processes.   These were:  1)  hazardous  wastes  landfilling;  2)
 acid-alkaline neutralization; 3)  chemical fixation;  4)  short-term
 storage of recyclables;  and 5) medium-term storage of recyclables. '  IEPA
 rejected the application oil the  grounds  that it would not approve
 medium-term recyclable storage.   The  application was  resubmitted in  May
 of 1976 without this process, and a development permit  was granted
 Earthline in July of 1976.

 A letter of  notification describing  the  proposed facility was  sent by
 Earthline to various local  officials  and residents  in February,  1976.
 The letter stated that the  Wilsonville Research Division  of  Earthlinp
                                 305

-------
was planning to build a facility which would assist in "conserving our
precious resources and protecting our environment," implicitly promised
that there would be jobs for local residents, and stated that the
facility would eventually reclaim the site, which was then partly
covered by a pile of mine wastes.  The function of the facility was said
to be "the recovery, treatment, storage and containment of industrial
residues."

Initial development of the site took place from February through
November of 1976.  During this time, facilities for secure landfilling
of hazardous wastes and short-term storage of recyclables were prepared.

Earthline, Inc., was sold to SCA,Services on October 1, 1976.  Earth-
line's founder had had previous contact with SCA through his work for
SCA-owned firms in the St. Louis area.  He was retained by SCA as the
consulting engineer for the facility.  According to the Illinois
Attorney General's Office, under the sales agreement he is also to
receive two percent of the gross receipts of the facility.  A separate
agreement was reached between  SCA and the owner of the land, who was
made regional director for SCA Services.

The operating permit for the facility was granted in early November,
1976.  Operations began November 15, 1976.  That same day, an open house
was held for local residents to acquaint them with the facility.  The
open house consisted of a luncheon, presentations by SCA personnel, and
a tour of the facility.  Shortly thereafter, a meeting was held between
SCA and the board of the village of Wilsonville for the same purpose.
Accounts of exactly what SCA told the residents on these occasions
differ widely.  Earthline's founder claims that the nature of the wastes
to be disposed of was made clear.  The mayor of Wilsonville and other
village residents maintain that the facility was presented as a center
for the "recovery of industrial residues" and as a way to reclaim the
mine site.

Residents of Wilsonville say that there were only minor problems in
SCA-village relations during the following four months of facility
operation.  There were some complaints about odors from the facility,
and that the facility did not  hire as many local residents as the
residents felt they had been led to expect.  Trucks traveling to and
from the facility caused some  damage to local streets,and property; and
there were a few spills of hazardous materials.  In general, however,
local public feeling about the facility during this period has been
characterized as neutral to slightly positive.

On April 4, 1977, the Missouri Department  of Conservation contacted
the U.S. EPA Region VII office to request help in the disposal of earth
contaminated with waste oil containing PCBs and other chemicals.  The
oil had been illegally dumped  and had polluted a creek near Dittmer,
Missouri.  U.S. EPA and the U.S. Coast Guard are responsible for the
                               ^306

-------
 removal of oil or any hazardous substance discharged into the waters of
 the United States.i                                           •

 To  prevent further  water pollution,  all the contaminated soil was
 removed from the dump site and stored in drums.   It was not feasible to
 incinerate this  waste,  and the only  alternative  was to place it  in a
 chemical waste landfill.  The closest such landfill was the facility at
 Wilsonville.   An emergency supplemental permit to accept these wastes
 was granted Earthline by IEPA.

 Newspaper accounts  of the spill stressed the toxicity of PCBs and noted
 that the wastes  were  to be taken to  Wilsonville.   Wilsonville residents,
 who seem to have been previously unaware of the  function of the
 facility,  very quickly  became violently opposed  to the contaminated soil
 being dumped there.   Their principal concern at  this time was the
 toxicity of PCBs.   On Friday  April 15,  State Senator DeMuzio held an
 "information meeting" in the  village.   Although  the manager of the
 hazardous  wastes  subdivision  of IEPA spoke  in favor of the facility,  the
 meeting served to intensify the fears of the village residents.   On'
 Sunday morning (April 17)  a local parish priest  reportedly told
 parishoners in his  sermon the facility was  a danger to them and  should
 be  shut down.  By Sunday evening  tensions had increased  to the point
 where some residents  had armed  themselves and were prepared to use these
 arms  in some  way-against either the  facility or  the trucks bringing  in
 wastes.   These armed  residents  had gathered into  an angry mob.   Some  in
 the  crowd  reportedly  had sticks of dynamite  under  their  belts  and
 threatened to blow  up the  facility.   By  this time,  however,  the  priest
 and  some other residents had  contacted a recently  retired circuit court
 judge and  the State's Attorney  for Macoupin County with  regard to
 obtaining  a court injunction  to forbid the  facility to accept  any PCBs.
 The  retired judge agreed to serve as  special attorney  for the  village,
 but only on the grounds  that  no violence should take place.  A blockade
 of  trucks  coming  to Earthline planned  for Monday morning  was called off
 because  of  its potential for  violence, and none subsequently occurred.

 Legal  proceedings against  Earthline were begun by  the village's attorney
 on Monday,  April  18.  The  presiding  judge of  the Macoupin County  Circuit
 Court  immediately granted a temporary restraining order against burying
 any of  the  contaminated  soil  in the Wilsonville landfill.  However, this
 restraining order was soon appealed,  and was overturned in ail  Appellate
 Court.   The facility  then  remained open until shortly after  the circuit
 court decision against Earthline (September, 1978).  IEPA filed an
 amicus  curiae  brief in favor  of Earthline as part of this appeal  and
again during the trial.  The village  of Wilsonville was joined in the
 suit  by Macoupin County and the County Farm Bureau,

That  same day  (Monday, April  18th) Earthline's founder called IEPA and
requested that IEPA protect Earthline's trade secrets'and customer list
by keeping all supplemental hazardous waste disposal permits
   Under Section 311 of the Clean Water Act.
                                307

-------
confidential (as permitted under Section 7 of the Illinois Environmental
Protection Act).  The confidentiality of these permits eventually became
a legal issue since the permits provide a record of the types of wastes
that are buried in the landfill.*

During this time, tensions beween the village and Earthline were made
worse due to misinformation and some public statements ascribed to
Earthline officials.  For example, during the early stages of the
litigation between the village and Earthline—when the litigation only
dealt with PCB shipments—the site manager was quoted in a local
newspaper as saying that there were much worse things than PCBs buried
in the site.  Next some local residents confused PCBs with PBBs.  The
contamination of cattle feed by the latter substance had resulted in
birth defects in calves, severe deformities in cattle, and had
necessitated the destruction of hundreds of cattle in Michigan.  Local
farmers reportedly became concerned that they would soon be in the same
situation.  And third, an unfounded report to the effect that nerve gas
was being buried in the site was circulated.  The owner of the land was
then quoted in a local newspaper as saying that although there was no
nerve gas in the site at that time, Earthline was free to store nerve
gas there if it wished.

Illinois State Geological Survey personnel visited the Wilsonville site
for the first time on May 10 at Earthline's request, and again in July.
Four months later, ISGS issued a generally favorable report on the
hydrogeology of the site.

On May 17, the circuit court judge denied a motion by Earthline to admit
U.S. EPA into the suit because, he said, it was "not a necessary party
in the legal sense."  U.S. EPA was eventually admitted to the suit as a
friend of the court.

In early May, the Illinois Attorney General, who had been representing
the IEPA in court, had visited the site and decided that its continued
operation was not in the public interest.  Therefore on May 25, he
advised the agency to retain its own counsel and announced plans to file
suit to close down Earthline.  This proceeding was later consolidated
with Wilsonville's request for an injunction against the landfill
accepting PCBs.  The Attorney General later amended his complaint to ask
for removal of all wastes buried at the facility and $1.24 million in
fines.

Five days later (May 30), the Governor of Illinois issued a 45-day
moratorium on the issuance of new supplementary permits.   This had no
impact on facility operations due to the large number (over 200) of
   This issue Was eventually resolved by a compromise by which the
   State Attorney General's Office could have access to all informa-
   tion on these permits with the exception of the name and location
   of the generator.
                               •308

-------
outstanding  supplemental  permits  previously  issued by IEPA.   The
following day, on the basis of  this moratorium,  the mayor  of  Wilsonville
stopped five 'trucks  from  entering the  landfill.

On June 8, a U.S. EPA technical evaluation team  visited Earthline to
evaluate" the landfill's technical suitability.   This team  issued a
report the following October which concluded that the Earthline facility
"is a well-designed, 'secure landfill which provides disposal  by
environmentally acceptable methods" and  "...is capable of  managing
PCBs." However, the  only  criteria used in  this analysis  were  the rules
for managing and disposing of PCBs, since  regulations for  the treatment,
storage and/or disposal of hazardous wastes  under the Solid Waste
Disposal ,Act (as amended  by RCRA) had  not  been promulgated at that time.

Midway through the trial, SCA officials  asked for and received a meeting
with local officials.  At this  meeting,  SCA  asked if anything could be  ;
done to settle the lawsuit out  of court.   It is  reported that they
offered to settle all outstanding damage claims  by village residents
against Earthline, and to pave  the village main  s'treet which  was used by
trucks hauling wastes to  the facility.   The  response of  the Wilsonville
officials present was that the  only thing  SCA could do to  end the
lawsuit was  to close down the facility and remove the wastes  already
burled there.                              '   ',     "

The trial lasted for 16 months.   Extensive testimony was presented by
both sides (eventually filling  14,000 pages  of record).  The  major
issues in the trial  were  the technical suitability of the  site and the
concomitant  threat posed by the site to the  health of local residents.
Specific technical issues raised  during  the  trial included the
permeability of the  soil and the  potential for subsidence.  As  noted
above, permeability  studies conducted during site design measured a
permeability of 10~8 cm/sec.  Subsequent measurements made* by
geologists working for the village of Wilsonville found  the permeability
to be 10~6 cm/sec. The implication of the  latter  figure  is that  it
would take a given waste  1/100  as long to  permeate a layer of soil than
if the permeability were 10~^ cm/sec.                    '  ,.  ...

The potential for subsidence of-land above an abandoned  mine  was  also an
issue.  Geologists from the Illinois State Geological Survey  (ISGS)
maintained that the  potential for problems due to  subsidence  is
negligible, but this was disputed by mining  experts  hired  by  the
village.

Other issues raised  during the  trial included the  contention  that
disposal was frequently carried out in a manner  contary  to state
regulations.   Smoking was allowed on the site.   Containers were
reportedly emptied and reused rather than  buried with the  wastes.   No
record was kept of the location of buried  wastes during  the first  few
months of facility operation.   The facility  was  said  to  produce
offensive odors.   The local population also  expressed concern about  the
possibility of health problems  due to the  facility,  and  about  the  fact
that the facility had" had an adverse effect upon local property  values.
                                 309

-------
On August 14, 1978, the circuit court judge ruled that Earthline must
close the landfill and remove all wastes previously dumped there.
Earthline immediately requested permission from the Appellate Court to
keep the landfill open during the appeals process.  However, before the
Appellate Court reach a decision on this, the village of Wilsonville be-
gan culvert repair work to control flooding.  This required digging a
trench across the access road to the Earthline facility, and effectively
closed the facility.  On September 14, the Appellate Court denied Earth-
line's request to remain open during the appeals process.  That same
month, the Governor directed IEPA not to issue any more supplemental
permits to Earthline for the Wilsonville facility and prohibited all
IEPA personnel from any further participation in the court action.  It
is reported that officers of a number of industries in the state wrote
to him cricitizing these actions.  The Illinois Manufacturers' As-
sociation subequently released its letter to the Governor in which it
stated that the "Earthline facility.. .is one of the best landfill sites
for industrial wastes in the United States", and that "[this] case seems
to boil down to emotionalism on one side, and scientific state of the
art on the other."  They requested that the governor reconsider his
position.

The appeals court is not expected to reach a decision before September
of 1979.  Moreover, it is expected that this decision will in turn be
appealed to the Illinois Supreme Court.  Two issues form the basis of
the appeal.  These are 1) whether the Macoupin County Circuit Court has
jurisdiction over such disputes; and 2) whether the Circuit Court erred
in its findings on the safety of the site.  With regard to the former,
the state Environmental Protection Act gives authority to the Illinois
Pollution Control Board to "conduct hearings upon complaints charging
violations of this Act or of regulations thereunder."  During'the trial,
Earthline had requested a change of venue to the Board, but this was de-
nied them.  As' of June 1979, EPA Region V was reviewing an Earthline ap-
plication for a permit to dispose of PCBs.  It was not expected that
this application would be acted upon until the lawsuit is resolved.
IV.
CHRONOLOGY OF EVENTS
February, 1976
           First application submitted to IEPA for a development
           permit for the Wilsonville facility.  Application re-
           jected.
February 11, 1976 — Letter of Notification sent out by Earthline to lo-
                     cal officials and residents.

May, 1976 — Application resubmitted with changes.

July, 1976 — Development permit granted.

October 1, 1976 — Earthline, Inc., sold to SCA Services.

November, 1976 — Operating permit granted.
                                 3,10

-------
November 15, 1976— Operations begin.  Open house held for village res-
                     idents.  Shortly thereafter, meeting held between
                     SCA and the village board.

April, 1977  —Wilsonville facility selected for disposal of con-
                taminated soil. •

April. 4, 1977 --.Missouri Department of Conservation requests U. S..EPA,
                 assistance in cleaning up spill of oil containing PCBs
                 in Dittmer, Missouri.

April 15,.1977— State Senator holds "informational meeting" in Wilson-
                  ville.                                     .
April 17, 1977
  Wilsonville parish priest asks parishioners to block
  delivery of contaminated soil.•
April 18, 1977	Legal proceedings begin against Earthline at Macoupin
                  County Courthouse in Carlinville, Illinois.  IEPA re-
                  quested to protect Earthline's trade secrets and
                  customer list by keeping all supplemental hazardous
                  waste disposal permits confidential.  Blockage of
   1           • .  trucks coming to Earthline  threatens to  turn violent
  , •      .  ; : ,   '•"' and .is called off.               .   • • .

May 10,  1977 — Illinois State Geological Survey personnel visit Wilson-
   .-             ville site at Earthline1 s request.

May 17,  1977— Macoupin County Circuit Court Judge denies Earthline mo-
                tion .to admit U.S. EPA into the suit.

May 25>  1977	Illinois Attorney General advises IEPA to get its own
      '   .  .     lawyer, and announces plans to file suit to close down
                Earthline.

May 30,  1977 — Governor issues a 45-day moratorium on issuance of sup-
   ; .        ,.   plemental permits to Earthline, which turns out to be
            i    ineffectual due to large numbers of outstanding sup-
                plemental permits already issued by IEPA.

May 31,  1977— Acting on the basis of governor's moratorium,
                Wilsonville village Mayor stops .five  trucks from
                entering the landfill.

June 1,  1977—Attorney General requests injunction  against Earthline.
June 8,  1977
U.S. EPA Technical Evaluation Team visits Earthline to
assess landfill's suitability.  Issues a report in Oc-
tober, 1977 which concludes that the facility is well-
designed, secure and capable of managing PCBs.

-------
July 1, 1977 — Attorney General amends complaint to ask for removal of
                all wastes buried at Earthline and $1.25 million in
                fines.                                 ,

July 19, 1977 — ISGS staff makes second visit to Earthline; takes
                 samples.

November 3, 1977 — ISGS issues a generally favorable report on the
                    Wilsonville site.

April 6, 1978 — Trial testimony ends in Macoupin County
                 Court.                        ..-.,.,

August 14, 1978 — Judge rules that Earthline must close its landfill
                   and remove all previously deposited wastes.

September 1, 1978 — Governor directs IEPA not to issue any more sup-
                     plemental permits to Earthline for the Wilsonville
                     landfill and prohibits all IEPA personnel from any
                     further participation in the court action.

September 6, 1978 — Village of Wilsonville begins culvert repair work
                     to control flooding.

September 14, 1978 — Appellate court denies Earth!ine's request to re-
                      main open during the appeals.process.

September, 1979 — Likely date for decision on Earthline's appeal of
                   circuit court order.               ,  .
V.
ATTEMPTS TO SECURE SUPPORT
Attempts to secure support for the Wilsonville hazardous waste man-
agement facility can be divided into two categories:  1) attempts to
secure support from local residents prior to the PCB-dumping contro-
versy; and 2) attempts to secure support from industry groups and local,
state and federal officials during subsequent litigation.  Attempts to
secure local residents' support included:

       o    ' The letter of notification sent to various local officials
             and residents in February, 1976.

       o     The open house held for village residents at the facility.

       o     The meeting held with village officials to explain the
             operation of the facility.         '

       o     The meeting held with village officials, midway through the
             trial, to attempt to settle the dispute out of court.
                                 312

-------
Subsequent to the events of April, 1977, most attempts to secure support
for the facility were directed at industry and state and federal of-
ficials.  These included:

       o     Earthline's attempt to have U.S. EPA admitted into the
             suit.                                             ,

       o     The Illinois Manufacturers' Association letter-writing
             campaign protesting the Governor's decision to forbid IEPA
             any further participation in the suit.
VI.
SUMMARY EVALUATION
Earthline's efforts to secure industry, state and federal support seem
to have been successful.  It remains to be seen whether this support
will be sufficient to allow them to reopen the facility.

Very few things could have been done, given the location of the
facility, to avoid the confrontation that arose between the village of
Wilsonville and Earthline.  Even if Earthline had decided not to accept
the PCB-contaminated wastes, it does not seem likely that local
residents would have remained forever ignorant of the true nature of the
facility. Some problems might have been avoided if Earthline had made
clear from the outset that it was preparing to build and, operate a
hazardous waste  landfill.  However, it is equally possible that had
this been done, the facility might have faced opposition from the >very
beginning.

While Earthline's initial efforts to secure local public support—the
letter of notification and open house for village residents—were
successful in the short run, they were certainly unsuccessful and
possibly counterproductive in the long run.  However, the point has been
raised that this might not have been the case if Earthline's actions
subsequent to the beginning of operations had been different.  First,
Earthline might have made a greater effort to meet local residents'
expectations which had been raised by the letter of notification.-  In
particular, providing jobs for more local residents would have both
given the community an economic interest in the facility and opened up
more avenues of communication between Earthline and village residents.
Second, Earthline might have responded more rapidly and more
substantively when residents became concerned about the PCB shipments.
Officials of SCA did eventually meet with village officials to see if
anything could be done to resolve the dispute, but only when the trial
was.well underway.  At least some Wilsonville residents and officials
suggested that if such a meeting had been held shortly after the initial
controversy, some sort of accommodation might have been reached.

Earthline lost most of its credibility among residents of Wilsonville
when it was discovered that PCB-contaminated wastes were to be shipped
there and that the facility was actually a hazardous waste landfill.
Furthermore, its public image was damaged by some statements attributed
to Earthline and SCA personnel.
                                313

-------
The key issues and concerns in  this dispute differ according  to  the
perspective of the participant.  These issues and concerns are outlined
below.

Fear of the unknown - According to Earthline's founder and IEPA, fear of
the unknown is a major issue.  This includes such things as a lack of
understanding of the need for and operations of the facility, and the
linking of any kind of hazardous waste management facility to increased
risks of cancer and birth defects, and the confusion of PCBs with PBBs.

Site suitability - As noted above, a major issue in the trial has been
the suitability of the Wilsonville site as a hazardous waste landfill.
Both IEPA and U.S. EPA have stressed the  technical suitability of the
site, while Wilsonville residents and technical experts hired by them
note many technical shortcomings.  At issue here are the permeability of
the soil and the possibility of mine subsidence.

Another concern expressed by local residents is the proximity of the
site to the village of Wilsonville (the waste burial area is located
one-quarter mile from the nearest residences).  In this case, the
concern stems from two factors:  first, the possibility that existing
residents might experience health problems due to the facility; and
second, that the presence of the facility has had a very adverse effect
on the market for houses in Wilsonville.

Facility operations — Residents who have witnessed facility operations
have testified that dumping was frequently carried out in a manner
contrary to state regulations.  The no-smoking rule was reportedly not
enforced on the site.  Containers were reportedly not buried with wastes
but emptied so that they could be reused.  No adequate record seems to
have been kept of the location of buried wastes.  Odors from the
facility have been a concern since shortly after it began operating.

Transportation of wastes to the facility - Concerns were expressed over
the danger of spills of hazardous wastes and over damage to local
streets and private property caused by trucks going to and from the
facility.  These concerns became and" have remained major points of
contention between the village of Wilsonville and Earthline.

VII.   FACTORS LEADING TO PUBLIC OPPOSITION/ACCEPTANCE

Factors which led to the initial acceptance of the facility by residents
of Wilsonville include:

       o     The letter of notification sent by Earthline to local
             officials and residents describing the proposed facility.
             This letter was thought by the recipients to indicate that:

             -     the 'facility would be a resource recovery and mine
                   reclamation project;
                               314

-------
              -      the  facility would provide jobs  for local residents;
                    and

              -      the  facility would ultimately reclaim the abandoned
                   .coal mine.         .    .                      •  .-..••

       o      The  open house  held at the completed facility for village
 ••-..;.        .residents. ... ,  ,                      ,     •

       o      The  meeting held  by SCA officials  with village officials  to
              explain  the function of the facility.

 In retrospect,
-------
area and trucks  going  to  and from the site travelled down the main
street.   This might have  been ameliorated  if  access  to  the  site  had  been
by  some  other road.

Officials  of IEPA  and  the State Attorney General's Office agreed that,
had Earthline given the community a  financial stake  in  the  operation
such as  employing  local residents or paying a fee on wastes brought  in,
the local  community might have been  less ready to have  the  facility
closed.   Earthline1s founder felt that neither compensation to nor
negotiation with the community would prove especially useful  in  siting
hazardous  waste  management facilities.  The former,  he  stated, will  not
be  perceived as  sufficient recompense for  the risk the  community is
bearing  and the  latter procedures are subject to judicial review.
It  was suggested by the Attorney  General's office that  the  lawsuit could
have been settled  if Earthline had agreed  within a week or  so of the
initial  filing not to  bring in the PCB-contaminated  wastes.   This  again
presumes that residents would not have subsequently  become  aware of  the
other substances in the landfill.

Both local officials and  the Attorney General's office  criticized  lEPA's
role in  the siting of  the facility.   Although they recognized the  need
for  hazardous waste disposal sites,  they felt that IEPA did not  have the
expertise  necessary to judge the  suitability  of the  site  and  its.
operation.  The  Attorney  General's office  questioned the  wisdom  of
relying  on the judgments  of a consulting engineer who had a financial
stake in the outcome,  and recommended that IEPA hire outside  experts to
review future permit applications for hazardous waste disposal sites.

Local officials  expressed considerable dissatisfaction  with the  total
lack of  a substantive  local role  in  the siting process.   It was  noted
that local residents might have petitioned the Illinois Pollution
Control  Board to conduct  a public hearing  which would have given them at
least a  nominal  role in the process.   However, this  assumes that the
local populace was aware  of their opportunity to petition the board,
which in this case did not seem to have been  true.   In  fact,  the siting
process  was completely in the hands  of the facility  sponsor except for
technical  review by IEPA.

IX.    GENERAL COMMENTS

Opinions differed  somewhat on the extent of U.S. EPA's  role in the
siting of hazardous waste  management  facilities.  Local officials felt
that the only way  to resolve  the  problems  of  siting  and long-term  care
was to put such facilities  on federal lands under U.S. EPA management.
The Attorney General's Office  thought  that U.S. EPA's primary role
should be to provide technical assistance  to  state agencies such as
IEPA.  Earthline's founder felt that  U.S.   EPA should  not  take an active
role, but that it should  force the states to  take a stronger role.
                             316

-------
                     RESOURCE RECOVERY CORPORATION

                           PASCO, WASHINGTON
I.
INTRODUCTION
In the fall of 1972, Resource Recovery Corporation began disposing
hazardous waste in a leased portion of an existing sanitary landfill
operated by Basin Disposal.  The owners of Resource Recovery also owned
the Preservative Paint Company of Seattle, and had a solvent manu-
facturing and reclamation operation calle4 Chemical Processors, Inc.,
also of Seattle.  The wastes produced by Chemical Processors had been
disposed of in local landfills and in an abandoned coal mine outside of
Seattle.  However, their activities were terminated after several  .
accidental fires.  Resource Recovery was then formed with the leasing of
Basin Disposal's facilities to dispose of paint wastes as well as other
industrial and agricultural wastes.                        ''.""'

The facility operated for two years during which time public opposition
to the site grew as a result of its pesticide waste disposal 6peration.
For some' time prior to the operation of the site local grapegrowers had ••
complained about crop dataage from an herbicide {2,4-D), which was being
used in aerial applications by wheat growers.  The disposal of 2,4-D
sludges at the Pasco site added fuel to this controversy, especially
since their wastes were being imported from Oregon.;  Finally, the County
Commissioners ordered the closure of the agricultural and industrial
waste disposal operation in December of 1974.

The only support for the site came indirectly from the technical
approvals given by the State Department of Ecology as a result of '
reports prepared by the state following their official investigations.
The State Department of Ecology and the State Department of Agricultural
had studied.the situation and found that the site could be operated
safely with no ill effects to the vineyards 12 miles away.  They
concluded in their report that grape damage had dccured prior to the
site's disposal  of hazardous wastes, and was probably due to windbprne
herbicides from wheat spraying operations.  Nonetheless, public
opposition forced  the County Commissioners to not renew the land use
permit for the hazardous waste operations.                   •      •
 II.
BACKGROUND  INFORMATION
 The  Pasco  site  had  been used  as  a  sanitary landfill  since 1958.   Farm •
 land surrounds  the  site.   The 250-acre site is  about 2 miles east of
 Pasco,  3 miles  north of the Columbia River and  2.6 miles  northwest of
 the  Snake  River.  The climate in the area is semiarid and average
 precipitation is  eight inches, with most of the precipitation occurring
 as rain and light snow during the  winter months.   The mean annual
                                317

-------
 temperature is 56° F.  Daytime temperatures often exceed 100° F during
 the summer.  Annual evaporation potential is about 60 inches per year
 with about 80 percent of the evaporation occurring from May through
 October.

 The Pasco facility was planned as a landfill operation with evaporative
 lagoons to be used as a means of concentrating wastes either for
 eventual  resource recovery or final burial.  The actual on-site
 facilities were several evaporation lagoons and trenches for the burial
 of drums.   The Pasco site is in an excellent climatic location for
 ground disposal (by evaporation) of industrial solid wastes if proper
 safeguards are observed.   The arid climate,  with approximately eight
 inches of annual precipitation, prevents leaching of solid  wastes
 disposed  to the ground.   Thus there is  little likelihood for migration
 of hazardous elements vertically through the ground to the  water table
 or laterally to be exposed at ground surface at lower elevations.   The
 climate and low humidity of the air is  conducive to on-site evaporation
 and concentration of liquid wastes where a  large surface area of the
 liquid is exposed to the atmosphere.  However,  the hydrogeology of  the
 site is not acceptable to dispose of liquid wastes directly to  the
 ground in unlined pits or trenches.   The water table is relatively
 shallow at the disposal  site (approximately 60-80 feet) and there are no
 sub-surface impermeable  zones that would prevent movement of the liquid
 to the groundwater although the alternating,  nearly horizontal  layers of
 sands,  silts,  and gravels would tend to spread the liquid and impede
 downward  percolation.  The silt and  sand would  also  remove  some elements
 from the  liquid by adsorption and ion exchange.   Under a carefully
 controlled operation and  proper research on  soil/waste reactions,
 selected  and limited liquid wastes could be  disposed directly to the
 ground without adverse effects.

 Resource  Recovery leased  a portion of the Basin Disposal  landfill with
 the intent of  storing some wastes for eventual  resource recovery
 operations  and permanent  storage  of  other wastes.   The Pasco  facility
 involving  the  hazardous waste operation7 employed about 9  persons at the
 site.  The  wastes  accepted at  the  Pasco  site  by  Resource  Recovery came
 from the Pacific  Northwest area and  included  paint wastes,  empty
 pesticide and  herbicide containers,  wood  treatment wastes, etching
 solutions,  metal  casting  wastes,  MCP and  2,4-D tars, and  chrome  plating
 wastes.  Much  of  the  waste contained potentially valuable materials such
 as  copper,  chrome  and other elements that may occur  in small  amounts  in
 industrial  debris.

 Resource Recovery constructed a series of evaporation lagoons (50 ft.  x
 100 ft. x 6 ft.) at  the site.   Liquid wastes, with almost 90 percent of
the waste being fluid, were poured into the lagoons.  The water quickly
evaporated  in  the dry Eastern Washington  climate.  About 6,000 gallons
can be evaporated in one  day  in the hot sun.  These lagoons  were lined
with impervious materials.  Deep  in  the ground beneath the bottom of the
lagoons the company installed sensors which measured moisture and could
detect any leaks in the lagoons.  An impervious layer, manufactured from
                                 318

-------
a waste material, was placed over the dried material in the lagoons and
topped with three feet of soil.  Grass was planted to prevent wind
erosion.

Some of the lagoons became permanent disposal areas and their contents
were not to be recycled.  They had more extensive impermeable liners and
moisture sensors.  On these lagoons three feet of soil covered the dry
sludges topped with another impervious layer, another layer of soil and
finally grass.

It was assumed that eventually, perhaps not for years, there would be a
demand for some of the stored materials in the lagoons and it would be
worthwhile to dig them out for reprocessing and re-use.  Chemical
Resources had planned to operate the site for approximately 50 years.

Paint wastes, insecticide and herbicide wastes with no recovery
potential were stored in covered trenches in drums.  Soil was mixed with
the drums to make up a safe mixture to prevent waste flows from leaking
drums from escaping the trenches.

Forty test wells were drilled  around  the disposal site.  Water samples
were analyzed regularly to be  sure that groundwaters were not
contaminated by wastes leaching from  the storage area.

Resource Recovery at  the time  of its  operation was not required  to  post
any bonding or closure costs.  However, after their land use permit was
not renewed they sought a  temporary extension during which they  were
required to post a closure bond and promise to carry out post-closure
monitoring.

Resource Recovery Corporation was  connected  to  three other corporations
— Chemical Processors  (which was  the majority  stockholder in  Resource
Recovery)  and  Preservative Paint Company  (which owned  Chemical
Processors).   While  Resource  Recovey  had no hazardous  waste management
experience prior to  the development  of the  Pasco facility,  Chemical
 Processors had been  operating since  1959.   Chemical  Processors had
experience with hauling, reclaiming  and processing hazardous  waste
generated  by  Preservative  Paint  Company and other  industries  in  the
 Pacific Northwest.   Basin  Disposal,  with extensive experience  in solid
 waste disposal,, had  a minority interest in Resource  Recovery.   The  Pasco
 site  was  the  only  facility ever  developed  by  Resource  Recovery.

 Pasco (1979 estimated population:  16,000)  is  located in southeastern
 Washington.   Along  with Richland and Kennewick,  Pasco  forms  the
 Tri-Cities urban area with a population of over 100,000.   The Tri-Cities
 is a  rapidly growing urban area  because of the  federally owned Hanford
 Reservation,  a production center for nuclear fuel.   Historically the
 southeastern part  of Washington has  been a sparsely  populated  area  with
 an agriculturally based economy.                             ,
                                 319

-------
 III.    HISTORY OF FACILITY DEVELOPMENT AND PUBLIC RESPONSE1

 When the Pasco facility first started accepting hazardous wastes in
 1972, the only permits required were a county zoning variance and a
 county health department permit.  Shortly thereafter the state
 Department of Ecology required a waste discharge permit to.guarantee a
 zero  hazardous discharge into the waterways.

 In 1959 Basin Disposal started a sanitary landfill operation near Pasco,
 Washington serving the Tri-Cities area.   Franklin County granted a
 zoning variance to allow the agriculturally zoned land to be used as a
 sanitary landfill.   However, through an oversight by the owner of basin
 disposal this zoning variance lapsed in 1961  unbeknownst to either the
 county or the owner.

 Preservative  Paint Company of Seattle has been  in operation for about
 fifty years.   It  formed a solvent manufacturing and reclamation
 operation called  Chemical Processors.   Chemical Processors  also
 collected and hauled industrial  solvents,  crankcase oils, contaminated
 diesel  fuels  from ships and paint wastes.   The  impetus  for  developing
 the Pasco site as a hazardous waste  facility  came from  Chemical
 Processors  which  had,  up until 1972,  disposed hazardous  wastes  in
 abandoned coal mines and sanitary landfills in  the Seattle  area.   There
 had been  several  fires  at these  sites  and  public  concern over  these
 fires had mounted to the point where  the  company  sought  an  acceptable
 hazardous waste site.   Basin Disposal  offered Chemical  Processors  the
 opportunity to lease a portion of their sanitary  landfill for  a
 hazardous disposal  operation.  The lease arrangement was coupled  with
 the formation, by Chemical  Processors  and  Basin Disposal, of a  new
 company called Resource Recovery  Corporation.

 The intent  of  the Resource  Recovery operation,  which was started  in
 1972, was to  recover materials (e.g.,  copper  and  chrome) from waste
 streams,  primarily  through  evaporation of  the largely liquid wastes.
 Since many  of  the valuable  products in wastes came  in small quantities
or the technology for their recovery was not  yet economically feasible,
Resource Recovery intended  to  temporarily  store these products  in dried
lagoons or  trenches until recovery operations were more profitable.
 Some wastes, of course, were  destined  for  permanent disposal.
   During the site visit, the State Department of Ecology asked
   Centaur not to interview local officials and leaders' so as not to
   interfere with the state attempt to site a hazardous waste disposal
   facility on the Hanford Reservation.  This request was honored and,
   consequently,  secondary sources were used to determine much of the
   public response to the Resource Recovery facility.  Despite this
   restriction, this case study provides valuable information for the
   overall study of public response.
                              320

-------
Resource Recovery submitted an operational plan for the Pasco hazardous
waste disposal site to the Benton-Franklin County Health District in
September of 1972.  In November of 1972, the Health District granted
approval of the operation on an interim basis pending a new forth-
coming state permit system.  Resource Recovery applied to the State
Department of Ecology in November of 1972 and was granted a waste
discharge permit in March of 1973.  The discharge permit from the state
was described as an inverted pyramid permit.  This pyramid permit
allowed the firm to handle specified wastes approved by the state.  It
started out with a/few items like paint, copper-bearing sludges, and
insecticide wastes.  Then as the company found new wastes, the state
certified the site for their disposal and the pyramid base grew broader.

Since the site was already an operational landfill, dating back to 1959,
the company felt that there was no apparent need for coordination with
local officials or a public relations campaign for the addition of a
hazardous waste disposal operation.  However, in an attempt to gather
new business, the president of Resource Recovery outlined his operation
in a news article in the summer of 1973.  As a result of this exposure,
the public learned for the first time of the extent of the hazardous
waste operation and especially of the disposal of herbicide waste
containers, specifically 2,4-D.  The state, various newspaper accounts
and company officials described public, concern as becoming uncomfortable
with the knowledge that a hazardous waste site was operating in their
area.  The public was also unhappy over the fact that.these wastes were
shipped to the Pasco area from out of state.

In August of 1973, the state began studying the 2,4-D disposal problem
partly because of. large-scale 2,4-D damage .that had been inflicted on
the grape industry that year.  The damage to the grape crop was among
the most extensive ever recorded and the grape growers felt their
economic livelihood was at stake.  The grape growers were angry at the
wheat growers because of their use of 2,4-D in aerial spraying
operations.  The herbicide in minute quantities is very dangerous to the
grape leaves during their rapid growth cycle.  It was assumed by the
state that the herbicide spray had strayed from wheat fields as far away
as Oregon to affect the vineyards near Pasco.  However, the grape
growers voiced concern over the possible connection between disposal of
2,4-D wastes and damages inflicted on their vineyards.  There was no
specific proof as to the source of the 2,4-D that was damaging the
grapes.  However, it was generally believed by Resource Recovery that
the wheat growers .pointed the finger at the Pasco disposal operation
which was handling 2,4-D wastes to take the "heat", off their spraying
operations.

In the'Fall of 1973, studies were conducted by the State Department of
Agriculture to determine if the disposal site was the source of the
herbicide.  They even planted grape plants at the dump site.  These
grape plants were able to grow at the site.  The studies could not
determine any link between the Resource Recovery operation and damage to
the grape crop.  They concluded that the operation was not damaging to
the local environment.  ••
                               321

-------
With all this  attention by the association of  wheat growers  and grape
growers  co-operative,  the County  Commissioners became  alarmed.   They
were surprised to learn of the extent of  the hazardous waste operation.
They had not realized  that hazardous  wastes  were  being imported from out
of  state to be disposed in Pasco.   They intended  to investigate this
matter and if  necessary stop  the  operation.

In  September of 1973 Resource Recovery had voluntarily stopped  accepting
2,4-D wastes.   However,  public pressure mounted with almost  daily  news
articles appearing on  the 2,4-D dumping.   (According to Resource
Recovery and the State Department of  Ecology,  a local  reporter  became
extremely active in the opposition.   Consequently,  the local paper
became a major force behind the opposition and served  to place
additional pressure on the County  Commissioners to  close the operation.)
The County Commissioners,  in  October  of 1973,  finally  ordered a halt to
the dumping of all industrial wastes.  Resource Recovery did not comply
with this order,  arguing that they had contracts  to honor and would wait
for the  outcome of a full  public hearing  on  their right to dispose
industrial wastes since they  had  a valid  discharge  permit from  the
state.   At this time,  the  state was also  feeling  the pressure of the
wheat and grape growers  and ordered a halt to  the disposal of 2,4-D
pending  further studies.   This move on the part of  the state was a
complete reversal of their earlier stand  that  the operation  posed  no
threat to the  environment.

Towards  the end of 1973^  the  County Commissioners held a public  hearing
on  the continued operation of the  Pasco site.   The  hearing revealed for
the first time that the  firm  had no legal zoning  permit to operate a
landfill.  Therefore,  the  county again ordered Resource Recovery to
cease operations  at the  Pasco site on the basis of  an  invalid zoning
permit.   The company immediately filed for a belated zoning  permit and
another  hearing was scheduled.

At  this  second hearing,  Resource Recovery appealed  the order  to
terminate their operation  and requested a new  zoning permit.  Evidence
was  presented  on  the safety of  the operation based  on  past studies by
the agriculture and ecology departments.   The  company  also presented
expert geological  evidence  to counter  allegations that 2,4-D was
escaping  the disposal  site.   However,  the grape growers  threatened to
take legal action  against  the county  and  the firm if the  county  did not
close the hazardous waste  site.  Under public  pressure,  the  county
denied the zoning  permit and  allowed  the  company to  continue  its 2,4-D
industrial disposal till May  of 1974.  It was  hoped  that current
activities by  the  state  to  locate  another  hazardous  waste disposal site
would solve the contractual problems  that the  Pasco  closure would  cause
the firm.

The May deadline was later  extended to December of  1974, after
negotiations with  the  county.   Resource Recovery made  several
concessions to  the county.  The company agreed  to post  a  $5,000 bond to
assure that no  dumping would  take  place after  the December closing date.
                               322

-------
A $30,000 performance bond would be put up to guarantee that Resource  ,
Recovery maintained and operated the site properly.  The $30,000 could
have been used to correct any problems that might have developed on the
land after closure.  Furthermore, Resource Recovery agreed to monitor
the site for two years after closure with supervision by the state.

The site was eventually closed to hazardous waste, at the end of 1974.
It continues to operate as a sanitary landfill.

During this period^ the Department of Ecology began intensive efforts to
locate a single hazardous waste  site for the entire state.  A history of
this effort closely parallels the Pasco experience and is therefore ap-
pended to the end  of this case study.
IV.
CHRONOLOGY OF EVENTS
 1959  — Basin Disposal  starts  a  sanitary landfill  operation serving  the
        Tri-Cities area.  Franklin  County grants a  zoning variance for
        the  site.

 1961  — The  zoning variance  lapses  and  due  to  an oversight  is  not
        renewed.  However, operations of the sanitary  landfill
        continue.

 1972  — After several fires  in local landfills and an  abandoned coal
        mine, Chemical  Processors searches  for a new site for  paint  and
        solvent wastes.   Basin Disposal offers to  lease a portion of
        their sanitary landfill  to  Chemical Processors for  industrial
        wastes.   Resource Recovery, Inc. is formed with ownership links
        to Chemical  Processors and  Basin Disposal.

 September, 1972 *~ Resource  Recovery submits an operational plan of  a
                   hazardous disposal site  and requests approval from
                   Benton-Franklin  County Health District.

 November,  1972   —Health District  approves operation  on an interim
                   basis pending a  forthcoming permit  system.   Resource
                   Recovery  applies for a waste discharge permit from
                    the State Department of  Ecology.
 March, 1973 —.Waste discharge-permit is granted by the state.
                includes mercury,  paint and insecticide wastes.
                                                          Permit
 Summer of 1973 —Anew business-type article promoting Resource Re-
     s' ,    "         covery's hazardous waste operation indicates that
                   2,4-D wastes are handled at Pasco site.

 August of 1973 —State Departments of Agriculture and Ecology and
                   County Health Department meet to discuss the safe
                   disposal of 2,4-D at the Pasco site.
                                  323

-------
 Fall  of  1973  -
- Wheat farmers face an angry grape industry following the
  worst 2,4-D damage ever recorded.  Grape growers voice
  concern over the possible connection between disposal of
  2,4-D and the 2,4-D damage inflicted on their vineyards.
  State Department of Agriculture conducts tests to de-
  termine whether grapes grown in the disposal site are
  affected by 2,4-D.  No damage is found.  County Com-
  missioners become alarmed over theehazardous waste site
  not realizing that it is being used for! out-of-state
  wastes.
September,  1973 — Resource  Recovery voluntarily halts  shipments  of  2,
                   4-D  for disposal  until  investigations  as  to  the con-
                   nection between these wastes and grape damage  are as-
                   sessed.

October, 1973  — Franklin County  Commissioners order  a  halt  to  indus-
                 trial  dumping.   Resource  Recovery continues non-2,4-D
                 operation pending hearing.   The State  Department of Eco-
                 logy orders Resource Recovery to stop  disposing  of
                 2,4-D.

November, 1973 — County Commissioners hold hearing to  determine  if  the
                  dump  violated zoning laws.  Resource  Recovery learns
                  that  their zoning  variance  had long since  lapsed.  Re-
                  source Recovery applies  for a renewed zoning  variance
                  (operating permit).  County Commissioners  again order
                  the company to  stop their industrial  operation.

December, 1973 — Public hearing  is  held for new zoning permit  with
                  testimony pointing to the safety of the site  along
                  with  abutting farm owners complaints  over crop  damage.

April, 1974 — County Commissioners  deny zoning permit  application and
               allow operation until May 1974.

May, 1974 — Resource Recovery offered concessions in return for  permis-
             sion to operate until the end of the year.   The concessions
             included posting a $5,000 bond 'to cease  operating  by De-
             cember 31  and a $30,000 bond  to operate  properly up  to and
             through the closure  period.   Resource Recovery also  agreed
             to monitor the site  for two years after  closure.

June, 1974 — Public hearing was  held on Resource Recovery's request for
              operating permission until the end of the year.   Permis-
              sion was granted.

December, 1974 — The hazardous waste disposal operation at Pasco ends.
                  The sanitary landfill operation continued.
                                  324

-------
V.
ATTEMPTS TO SECURE SUPPORT
Direct attempts to .secure support for the Pasco operation were few.

       o     Technical evidence was presented by Resource Recovery at
    i         public hearings to show that the site was safe.  The firm
             had hired expert consulting geologists to counter al-
             legations that 2,4-D was escaping from the site and damag-
             ing the grape vines.                       ,

       o     The firm voluntarily stopped the disposal of 2,4-D in the
           .face of growing pressure from both wheat and grape growers,
VI.
SUMMARY EVALUATION
The efforts outlined above proved to be insufficient to achieve public
acceptance of the operation.

Although the technical evidence did exonerate  the  site insofar as caus-
ing the grape damage it did not conclusively identify the  true source of
the herbicide damage.  Since  the damage affected the very  livelihood of
local agricultural interests  they were not willing  to take uncessary
chances on the hazardous disposal site.  Furthermore, since  the site was
primarily a service to outside industry, it generated very little local
sympathy.  Finally, concurrent efforts on the  partof ithe  state to -lo-
cate a single hazardous waste site for the entire state lessened the
pressure on county officials  to keep the Pasco site operating even
though it was the only licensed hazardous site in the state  at that
time.                                         .            .

The oversight on the expired  zoning variance proved to be  the most con-
venient vehicle  by which the  county was able to stop the hazardous waste
disposal operation.

In summary, the  most important factors in the  closing of  the Resource
Recovery operation were:

State responsibility — State efforts to locate a  single disposal site
for the entire  state provided the county with  a convenient alternative
which appeased the grape growers and relieved  the  county of  having the
responsibility for  the only approved hazardous site in  the state.

Intensity of 2,4-Q  issue — The  animosity between  wheat and  grape
growers over 2^4-D had existed for some time prior  to the  Pasco disposal
operation.  Resource Recovery's  disposal of  2,4-D  tars was a convenient
scapegoat during a  period  of  unusually heavy herbicide damage  to  the
vineyards.                                                           ,

-------
VII.   FACTORS  LEADING  TO  PUBLIC  OPPOSITION/ACCEPTANCE

The general  public  opposition to  the  Pasco site  can  be  attributed  to  the
following  factors:

       o      Public became aware  of herbicide disposal  at  the  site
              through  company  efforts  to  advertise  their business.

       o      Uncertainty over the cause  of 2,4-D herbicide damage  to
              local  vineyards  and  the  possibility that it might have
              originated at the disposal  site.

       o      Discomfort over  the  fact that Pasco was being used  to dis-
              pose of  industrial and agricultrual wastes  generated
              outside  of Franklin  County  and  throughout  the Pacific   !
              Northwest.

VIII.  RETROSPECTIVE  VIEWS

In retrospect,  Resource Recovery  thought that there were three areas
that could have been  handled  better.   First, the County  Commissioners
should have been approached much  earlier as soon as public opposition
surfaced.  This would have provided the  Commissioners with technical
information to  fend off the pressures  of the wheat and grape growers.
Secondly, the oversight on the lapsed  zoning variance should never have
been allowed  to happen.  With a valid  permit, the firm would have had
more time to work out solutions to public opposition.  And finally, more
attention should have been paid to countering the news articles against
the Pasco operation.                                     ,

The state had no retrospective views especially since it is in the.midst
of its own publ3.c opposition battles with regard to a single centralized
hazardous waste site  for the entire state (see appendix).
                                326

-------
                      APPENDIX TO PASCQ CASE.STUDY
              A HISTORY OF EFFORTS  TO ACQUIRE  A HAZARDOUS
                 WASTE  SITE IN  THE  STATE  OF  WASHINGTON

                     By Tom Cook and Jim Knudson—
Introduction

It is necessary to understand a bit about the climate and geography of
the State, of Washington to see where and how our search was farrowed t(°
Federal lands.  Western Washington is populous, contains most of the
industry and receives considerable rain except for three or four months
in the summer.  Eastern Washington receives as little as 6 inches of
rain per year because the Cascade Mountains remove most of the Pacific
Ocean moisture.  Eastern Washington also is sparsely populated, largely
agricultural ir nature.  The area around Richland, Pasco, and Kennewick,
however, is an exception because of the presence of the Federal Govern-
ment Hanford Works.  The Tri-Cities boasts of a population of 100,000
and is rapidly growing.

Hazardous wastes produced in the state include heavy metal sludges from
oil refineries, pesticides from agriculture, plating wastes from aircraft
manufacture, and chemical wastes from the electro-chemical industry.
Electrical utilities also produce P.C.-B.s from facilities that  include
numerous dams on the Columbia  River.

Early  Efforts - Pfivate/Non-Federal Sites

Private  industry began  the effort  to develop  disposal  sites dedicated  to
hazardous waste in 1971.  After one unsuccessful  attempt  at Badger   •
Junction, a  private chemical  waste  firm  opened a  site  near  Pasco and
adjacent to  an  existing sanitary  landfill.   The site accepted  a large
va'riety  of  industrial  wastes  from  Western Washington and  some  agricul-
tural  pesticide wastes  as well.   The  site operated  until  1974  when  the
 issue  of 2,4-D  disposal was  raised by  nearby grape  farmers.   2,4rD  is  a
broad-leaf  herbicide used by wheat farmers  extensively.   Grape growers
 have historically fought the use  of such chemicals  because of  spray
 drift that  can severely damage grape  plants even  in minute quantities.
 The general public furor, publicity,  and clamor was enough to  force
 closure of  the state's first recognized chemical  waste disposal site.
 As a result, the  private firm and others turned to  the State of Washing-
 ton, Department of Ecology  for help in locating another site.

 We began this effort by contacting Atomic Energy Commission officials
 about use  of federal lands.   Our request was rejected until all other
 efforts were exhausted.  This led us to searching state lands, mainly
 Department of Natural Resource lands.
                                          Twenty sites were evaluated ana
 I/   Tom Cook is Chief, Hazardous Waste Section, Solid Waste Management
      Division, Department of Ecology, State of Washington; Jim Knudson
      is a member of the Hazardous Waste Section.


                                  327

-------
 narrowed to three sites.  The most acceptable of the three was in Frank-
 lin County. ^It was known as the Eltopia site. Its fate was similar to
 that of the original Pasco site - public pressure brought to bear on
 county officials who had no choice, in view of the intense political
 pressure, but to oppose the site.  The project was abandoned in mid-1975
 before the land was even purchased.  As a result of continuing failures
 to locate sites on private or state lands, the Department of Ecology
 returned to federal lands.

 The Search on Federal Lands

 In addition to the earlier AEC talks, the department approached federal
 authorities in the Department of Army in 1974.  The site was the Yakima
 Firing Range,  a desert-type training ground used for tank maneuvers and
 troop warfare  training.  The site was rejected because  of insufficient
 cover material.

 In 1975,  formal efforts to locate a hazardous waste site on the Hanford
 Reservation were begun.  The Hanford Reservation is located in south
 central Washington State, in the Columbia Basin.   Rainfall is  6 inches
 per year  with  pan evaporation rates of 50 inches  per year.   The 540-
 square mile reservation was taken over.by the U.S.  Government  during
 World War II for the production of weapons-grade  plutonium.  The site
 was choosen for its isolation and proximity to the Columbia River and
 abundant  supply of cooling water used in some of  the nation's  first
 nuclear reactors.   The reservation has become a  center  for research and
 development of nuclear fuels reprocessing and nuclear waste disposal.
 Both high-level (i.e., spent reactor fuel elements)  and  low-level  radio-
 active wastes  are  being stored on the reservation awaiting  a solution  to
 the long-term  disposal question.   The reservation is also becoming  a
 nuclear energy park with one nuclear reactor  operating and  three  under
 construction.

 Such land uses made the reservation a natural choice for the siting  of a
 non-nuclear hazardous  waste  site.   Discussions with  federal officials of
 the Atomic  Energy  Commission (now the Federal Department of Energy)  soon
 revealed that:

      (a)  Federal  officials  desired state ownership  of the waste
          and  hence  the land upon  and  in which the waste was to be
          disposed.  Leasing the  land was therefore  rejected.

      (b)  The  site was  to be located  away from any existing nuclear
          activities on the  reservation.

Legal council  at the state level also  revealed that the State of Washing-
ton did not have the legal authority  to purchase federal land for the
purpose of owning a hazardous waste facility.  That authorization was
therefore inserted into hazardous waste legislation enacted by the State
of Washington  in March  of 1976.

Federal Department of Energy officials then presented a series of possi-
ble sites  for the department's evaluation.  The same criteria was used
to judge the proposed six sites   ->»
                                  328

-------
After considerable discussion and evaluation,  the  department chose
Section 15 in the southern part of the Hanford Reservation as the most
acceptable site of the given six.  Section 15  is located about 12 miles
from the center of Richland and 3 1/2 miles from the nearest resident to
the south.  Desert sagebrush land, devoid of any activity, acts as  a
buffer zone between the site and any residents.  Ground water is 125
feet below the site and the nearest surface water is the Columbia River,
7 miles to the east.  The land is flat, with no possibility of flooding
or erosion even during occasional desert downpours.   The site is acces-
sible and served with power and telephone facilities.  Work began on the
writing of a draft environmental impact statement (EIS) for the proposed
site.  In August 1977, the department held four statewide hearings  on
the draft EIS whicti covered not only the proposed site, but also, draft
regulations to implement the State Hazardous Waste Disposal Act of  1976.
Benton County officials were briefed two weeks prior to the hearing on
the nature of th*» project and its location.

Little citizen comment was heard at the public hearings, including  one
in the City of Richland.  One real estate agent did make informal comments
on the proximity of the site to potential home sites near the southern
boundary of the Reservation, 3 1/2 miles away.  After the meeting was
covered by the media, protests over site location led local legislators
to ask for another informational meeting.

The second meeting was held in mid-September and saw about 50 concerned
citizens and considerable media interest.  The City of Richland's Ecolog-
ical Commission testified on both the site and the proposed regulations.
Many commentors were technical persons working either directly or indirect-
ly with federal governmental activities.  Also represented were real
estate interests and citizens of no particular identified affiliation.

The Department of Ecology spent the next three months preparing the
final EIS and responding to criticism on the site location and the  draft
EIS.  Worst case scenarios were constructed for fires, explosion, spills
to ground water, arid dust storms.  Attempts were made to relate overall
risks of concentrating hazardous1 waste as opposed to continued disposal
at the local level.  Every written comment was included in the final EIS
and a written response prepared.  The final EIS was issued in mid-
December 1977 and the regulations signed into effect in late January
1978.

Despite the efforts of the department to satisfy the City of Richland  ir.
the final EIS, the city felt the need to bring court action against the
department for its choice of site locations.  The City of Richland
approached the Governor and also contacted members of the Washington
Congressional Delegation.  Because all federal land transfers require
the review and approval by the House Governmental Operations Subcommittee,
the Washington delegation asked for a hold on the transfer of land to
state ownership.  The directive to the state was to settle its differences
with the City of Richland.  This, in effect, dictated that a new site  on
the reservation be found and that the acquisition process begin anew.
                                  329

-------
This process resulted in the selection of a new site, Section 1, which
is 3 1/2 miles to the northwest of the previous site, Section 15.  With
assistance from the Governor's Office, representatives of the City of
Richland and the Department of Ecology hammered out a memorandum of
understanding on how the department will proceed with the new acquisi-
tion.  The Ecological Commission, a Department of Ecology advisory
board, held a hearing in Richland in early June 1978 to hear public
comments on the Memorandum of Understanding.  The City of Richland
testified asking for frequent consultation in the preparation of the
draft EIS supplement.

The Department then began preparation of a draft supplemental EIS on
Section 1, with frequent and early consultation with the City of Richland.
A public hearing in December 1978 drew an audience of 50 persons.  The
City of Richland commented upon the draft but generally in a positive
tone.  Of four additional commentors; two state legislators were still
opposed to the general location of the site.  The final supplemental EIS
was issued in February 1979.  The department expects to complete site
acquisition by mid-1979.

This is where the acquisition of a hazardous waste site stands today.
Some obstacles have been overcome, but some in the Richland area continue
to resist the site location.  A private firm has also made its presence
felt in arguing against the need for a second site within 80 miles of
its Oregon facility, which it claims as a regional site already.  The
department has felt that every state should have its own hazardous waste
facility to guarantee a place for politically controversial wastes.

Although the site development monies were appropriated by the Legislature,
along with site acquisition monies, the site controversy resulted in all
but the site acquisition money being revoked.  As a result, the depart-
ment is looking for private funding to develop the site.  The operator
would recover all capital costs from disposal changes, according to this
plan.

Conclusions

Acquiring federal land for this site is complicated by the numerous
federal agencies involved and the approval mechanisms.  Very long lead
times are therefore necessary before successful transfer can occur.

The other aspect is that of the role that local communities do or do not
play in controlling the activities that occur on federal lands.  Even
though activities on federal lands are somewhat autonomous, it is criti-
cal that early and constant communication and involvement of the local
community be maintained so they can be fully informed of all activities.

The difficulties of writing EISs for hazardous waste facilities should
not be underestimated.  The sponsoring agency must be prepared to spend
the time and money in answering "what if" questions in great detail.
                                    330

-------
Recommendations

It is difficult to draw parallels between siting problems that are a
continent apart.  However, I would advise the following:

     1.   Provide current state laws and regulations which detail and
          authorize the system you want to implement for siting hazardous
          waste facilities.

     2.   Hiring of appropriate staff (planners, chemical engineers,
          chemists) is vital to the ultimate success of such an under-
          taking.

     3.   Where federal lands are concerned, the involvement of congres-
          sional level politicians should be actively sought.

     4.   Some method of selecting and involving the local community
          must be found that does not lead to the familiar cycle of
          protest and outrage.  Perhaps a region-wide publicity effort,
          coupled with financial incentives, would be more productive
          especially if private lands are to be chosen.  This would call
          for local' communities to make application for such a site.  A
          final choice could be made based upon an evaluation of the
          ffiost favorable environmental choice. Quite clearly, any process
          which reverses that process is bound for trouble from citizen
          protests.

     5.   If. a regional concept is recommended,  guarantees of waste
          acceptance of all hazardous wastes will need to be provided.
          Otherwise, the concept of a regional site cannot and will not
          make sense. The role of private enterprise in constructing
          competing sites will also have to be clarified.
                                   33i

-------
             APPENDIX B




NEW ENGLAND REGIONAL COMMISSION REPORT
                 332

-------
                    NEW ENGLAND REGIONAL COMMISSION '

                   HAZARDOUS WASTE MANAGEMENT PROGRAM
I.
OVERVIEW OF,PROGRAM
In April of 1978, the New England Regional Commission (NERCOM) formally
resolved to seek a regional solution to New England's hazardous waste
problem.  As a result of that, resolution a multi-faceted program was
developed to address a range of issues from preparing an inventory of
hazardous waste generated in the region to providing for public input
into the program.  A major component of NERCOM's program is a study of
the need for disposal facilities and procedures for siting such
facilities.

When NERCOM first embarked on this program the agency had no experience
with hazardous waste management although it had been involved in a few
solid waste projects.  Because of the agency's economic development
activities, however, it had established good working relationships,with
New England businesses that generate hazardous waste.  To provide needed
expertisej advisors from state agencies, industry, and public interest
and other organizations have been utilized.  In addition, private
consultants have been hired to develop much of the program.

The current work of the program will be completed in September, 1979 and
presented to-NERCOM's governing board.  The governing board will then
determine what activities should be continued by NERCOM and which will
be taken up by the individual states in New England.
II.
THE NEW ENGLAND REGIONAL COMMISSION
NERCOM was created in 1966 to address problems of potential and real
economic decline in the New England region and to seek to reverse what
was perceived to be incipient economic deterioration.   The legislative
mandate for NERCOM was Title V of the Public Works and Economic
Development Act of 1965 which created a number of .other regional
commissions across the country.  The act and subsequent amendments- are
administered by the U.S. Department of Commerce.

NERCOM serves six states --Connecticut, Maine, Massachusetts,  New
Hampshire, Rhode Island, and Vermont.  The governors of the^six states
along with a presidentially appointed federal co-chairman serve as the
governing board which determines overall policy.   NERCOM maintains a
permanent staff of research and administrative personnel; these in-house
capabilities are expanded through the use of state agency staffs and
outside consultants in each of the program areas addressed by the
agency,              ...-••                     ••.:..-•
                              333

-------
The primary concern of NERCOM is economic development in the six-state
region and this concern is addressed by short-term programs for specific
problems as well as long-term planning towards the establishment of
regional economic development priorities.  There are two other major
areas of concern — energy and transportation.  The former is concerned
with solutions to the region's substantial reliance on imported energy
resources.  The latter is oriented towards the development of an
integrated regional transportation system and major emphasis is placed
on rail systems.

III.   ORIGIN OF THE HAZARDOUS WASTE PROGRAM

In January 1978 the governor of Rhode Island first approached NERCOM
about hazardous waste management problems in New England.   According to
NERCOM1s hazardous waste program director, industry officials in Rhode
Island had come to the governor to express their concerns  about the
impact of RCRA on Rhode Island.  Those officials foresaw major problems
for hazardous waste generators because of a lack of disposal facilities
that would meet RCRA standards.  The governor, feeling that hazardous
waste disposal was a problem difficult for individual states in the
region to manage, turned to NERCOM and asked its staff to  prepare a
background paper.

By mid-March the six New England governors and the federal co-chairman
had called for a meeting to discuss a regional approach to hazardous
waste management.  That meeting, held at the end of March, brought
together government officials from the six states and EPA's Region I
office and representatives of generators and disposers of  hazardous
waste.  At the meeting individual states discussed their hazardous waste
programs and industry representatives discussed their current methods of
managing hazardous waste.  The major conclusion of the meeting was that
a regional approach to hazardous waste management was required.  It was
also decided that NERCOM's first task should be an inventory of the
region's generation of hazardous waste.

By the end of April NERCOM was ready to make a formal commitment to the
hazardous waste program.  The issues that needed to be addressed had
been outlined and an organizational framework had been developed.
Initial estimates by NERCOM had indicated.that 4,500 industries would be
impacted by forthcoming RCRA regulations.  On April 27, NERCOM's
governing board passed Resolution 182 which committed NERCOM to seeking
a regional solution to New England's hazardous waste management problem.
IV.
THE NERCOM HAZARDOUS WASTE MANAGEMENT PROGRAM
Resolution 182 established the broad tasks of the program.   An advisory
group -- composed of representatives of each state,  EPA Region I,  and
the hazardous waste generation and disposal industries — was  to be
created.  The state representatives were gubernatorially appointed,
                               334

-------
senior-level officials from the state environmental agencies.  EPA's
representative was appointed by the EPA Regional Administrator^ and the
industry officials' by NERCOM's governing board.  This group was to
develop a work plan for.the consideration of NERCOM's governing board.
The work plan would outline a regional plan, activities needed to  ,
implement this plan, and potential funding sources.  Earlier attempts by
NERC0M,to, inventory, tjie region's hazardous waste generation, would be
refined.  Comments at that time by state and industry officials-involved
in the early efforts suggested that a regional plan would be the most
cost-effective approach to hazardous, waste problems.  By expeditiously
developing an effective plan New England would not only help "to retain
existing industries.but.also attract new industries.  One of the; biggest
obstacles to implementing a regional approach would be public opposition
to siting facilities.                                              ?

In late May the advisory group held its first meeting and began to - .
organize  its efforts.   The major substantive action was the  agreement on
the major components of the regional plan.  Those were: 1) regionwide
inventory of waste generation and  disposal,facility.needs, 2) site
selection process  and siting criteria, 3) institutional and
organizational structures  (including facility operation), 4)
institutional barriers  (including  importation bans), 5) implementation
strategy, 6) environmental assessment, and 7) citizen, involvement. ,. The
preparation of issue papers on the first five components was assigned to
the various, New England states and NERCOM.  The development...of  issue
papers  on the last two  components  was  postponed.   The  issue  papers were
designed  to serve  as  the ,f irst step  in developing  a  regional, hazardous
waste management  plan.  ,; The preparation  of  a work, program for  the,.plan
was  scheduled to  coincide with NERCOM's  timetable  for  fiscal year 1979
budget decisions.   At the  meeting  it was also decided  to establish a
technical committee,  composed of  advisory  group members, to  perform and  •
coordinate  technical  tasks  among  the six states.;            ,

 In August NERCOM sponsored a workshop  for  advisory group members  to
•inform them of  hazardous waste  problems  in other areas, of  the country.
At the workshop  regulatory officials  from Minnesota,  Texas and
Washington related specific experiences  with attempting to  site disposal
'facilities  in their respective  states. .                            •

 The day following the,workshop  the advisory group held its  second
 meeting.   At the meeting,presentations were made: on the.progress.of
 individual issue papers which had been prepared after the May meeting.
 The meeting also focused on the advisory group's future activities  and
 recommendations to be made to NERCOM's governing board.  The advisory
 group agreed on the .need for maintaining itself as a means  to coordinate-
 state efforts,  influence U.S.  EPA actions and policy, oversee public
 involvement in hazardous waste management, and direct .any future . ~-,
 consultant work.   'With regard to the last item, it was agreed to .
                               335

-------
recommend a consultant study to examine resource recovery, facility
needs and financing, site selection process, long-term care and
liability, and management options.               •

The State of Massachusetts was responsible for preparing the issue paper
on site selection process.   Siting criteria developed by Camp Dresser
and McKee for Massachusetts Division of Water Pollution Control were
summarized.  Criteria for land disposal were accessibility,
hydrogeological conditions, adaptability, environmental impact,
compatibility with existing and proposed zoning and land use, and
relative construction and operating costs.  It was  noted that no one
site was likely to meet all criteria.  Accordingly, Massachusetts had
adopted a policy that physical characteristics were less important than
the site's proximity to waste generators, in part because of reduced
hauling costs, but more importantly because employment opportunities
with generators might offset inevitable opposition  to any site.  For
incinerators, sites with good atmospheric ventilation and remoteness
from particularly sensitive activities (e.g., hospitals, schools) should
be selected.

The siting issue paper stated that local acceptance of a designated site
was possibly the single most important factor in siting.  Public
education was seen as critical to establishing an awareness of existing
disposal problems and thereby support for solutions to these problems.
Compensation in the form of payments per unit of disposed waste to host
communities was seen as a potential incentive.  Finally, the use of
eminent domain or the threat of its use was seen as a potential last
resort if opposition could not be overcome and if a clear need for a
facility site existed.

The issue paper examined NERCOM's role in siting.  Citing earlier
advisory group discussions which considered the development of a single
regional disposal facility, this approach was thought to be unjustified
because of the potential for greatly reducing the volume of residual
hazardous waste through treatment and processing.  Accordingly the
following tasks were suggested for NERCOM:  the dissemination of
information on safe intrastate disposal technologies, the provision of
technical assistance on specific disposal problems, the promotion of the
region's only waste exchange facility, the avoidance of choosing any
specific site and concentration on siting criteria  to be applied within
individual states, and investigation of the feasibility of a regional
reprocessing center.

By late September the advisory group had prepared recommendations for
the NERCOM governing board.  Acting on those recommendations the
   Because the major emphasis of Centaur's project is public
   response to the siting and operation of HWMFs,  this issue paper is
   summarized here and appended to this report on NERCOM's hazardous
   waste program.
                               336

-------
 commissioners  passed  Resolution 195 on September 22.   This  resolution
 expanded  the advisory group  by  adding  six public-members  (e.g.,  local
 officials,  representatives of environmental  and public interest  groups)
 and  created a  steering committee of advisory group memebers serving  in
 an ex officio  capacity.   In  addition,  the advisory group .was charged
 with ensuring  the  compatibility of  the six states'  individual hazardous
:waste programs,  developing interim  strategies and solutions to hazardous
 waste management problems, surpervising medium- and long-term,planning
 efforts,  directing any NERCOM-sponsored consultation  work,  and
 implementing a public information/participation program.  To provide
 support for this effort,  $245,000 was  allocated to the program.   These
 funds were  allocated  primarily  to consultation work ($190,000) and the
 public information/participation program ($50,000).  Within two  weeks a
 public information sub-committee, was formed  and a request for proposals
 had  been  reviewed  and revised by the full advisory group.   To help in
 the  selection  of a consultant and to work with the  selected, consultant
 during the  contract period,  a consultant committee composed of advisory
 group members  was  created.   On  October 13 the request for proposals  was
 distributed to 36  prospecti\js contractors.

 The  request for  proposals called for a six-month contract not to exceed
 $190,000  in cost..   Five major tasks were outlined in  the scope of work:
 1) a regionwide  hazardous waste inventory organized by management option
 was  to be prepared;*  2) a site  selection process was  to be  developed
 to .provide  a vehicle  for  the identification  of,  but specifically not
 identify, one  or more regional  disposal facilities  and consider
 acquisition methods,  public  acceptability and incentives.   Roles of
 public and  private parties were to  be  examined as were the  relationship
 between the location  of generators  and site  selection;  3) management
 options were to  be examined.  These included the number and types of
 facilities  required by New England, various  public/private  arrangements
 for  facility planning,  construction, ownership and  operation, and
 financing arrangements; 4) provisions  for long-term care and legal
 liability in case  of  incident were  to  be studied;.5)  the previous four
 tasks were  to  be integrated  into a  .set of realistic scenarios and
 implementation options.   Included within these options  would be  specific
 references  to  the  number  and type of facilities needed in New England
 and  their respective  service areas.

 By early  January NERCOM announced the  selection of  Arthur D.  Little
 as the consultant  for the study.  Work began on the contract in
    Earlier:.efforts  to aggregate individual state inventories had
    been  frustrated  by variations  in  the  data collected and  tabulated by
    the individual states.
                               337

-------
mid-February and was due to be completed in mid-August of 1979.
NERCOM's consultant committee organized smaller groups around each of
the major tasks of the contract.  These groups have played an active
role meeting with the consultant on at least a monthly basis to review
the project's progress and to make recommendations and advise the
consultant.

While this contract will be the major focus of NERCOM's efforts in
fiscal year 1979, the public information program has also been active.
In December, 1978, the public information committee (as with other
committees, also composed of advisory group members) met for the first
time and defined its goals as the promotion of public understanding of
New England's hazardous waste concerns, the encouragement of public
involvement in finding solutions to those problems, the promotion of
environmentally sound disposal facilities, the identification of key
groups and their concerns, the ensuring that all management options, are
explored, and the monitoring of the Arthur D. Little contract.  A broad
range of possible key groups that could play a major role in NERCOM's
hazardous waste program (e.g., environmental groups, hazardous waste
generators) were identified and the most critical of these were targeted
for particular attention.  A list of methods for implementing the
committee's goals was also developed.'  The committee met; for a second
time in late.January.  At the meeting it was decided to include the
following efforts in the public information program:  a speakers bureau,
a slide show, brochures, facility tours for advisory group members,
media efforts, special meetings, contributions to conferences, arid a
film.  The committee will also utilize a public information consultant
to assist in implementing the program.  The public information committee
expected to begin parts of the program (i.e., slide show, brochures,
speakers bureau) in the summer of 1979.

By late May of 1979, the NERCOM program was .proceeding as planned with
no major problems.  The Arthur D. Little contract was roughly at
mid-stage. From those interviewed it was clear that a broad range of
issues had been examined.  This was particularly true of issues directly
relating to the siting and development of facilties.  Equally clear was
the fact that any final recommendations to come out of that study would
have to take into consideration a range of technical, economic, legal,
institutional, and political considerations which vary significantly
among the six New England states.  Decisions on what to do next would be
made by the NERCOM governing board in September, '1979.
V.
VIEWS ON THE NERCOM PROGRAM AND FUTURE ACTIONS'1
Two views stand out from discussions with those invo.lved in or
potentially impacted by NERCOM's program.  One is support for a regional
   The material in this section is based on interviews with state
   and EPA officials in New England who have either worked on NERCOM's
   advisory group or are directly involved in state hazardous waste
   management efforts.
                             338

-------
approach to hazardous waste management and the attendant perception of
NERCOM as the obvious agency to promote a regional approach.  The other
is the view that individual states, rather than NERCOM, must play the
major role in the implementation of any hazardous waste program,
particularly with regard to the development of specific facility sites.
The two views are not necessarily conflicting, but do underscore the
need (and desire) for careful consideration of future roles of NERCOM
and the states.

NERCOM's continued role has been defined in a number of ways.  The basic
distinction between these conceptions of NERCOM's' role is whether NERCOM
will be supportive of state actions or will take the lead iii identifying
sites and developing facilities.  According to NERCOM and state
officials, the latter role, which could involve the development of a
regional hazardous waste authority, is unlikely.  More likely is that
NERCOM will be asked to continue to support the advisory group.  At a
minimum the advisory group would then continue to monitor and coordinate
the states' programs to try to ensure compatibility and would also
continue its public education/information efforts.  NERCOM might also
serve as a proponent of specific facilities proposed by the private
sector.

Decisions on government roles in siting will in all likelihood be left
to the individual states.  Because of variations between the
states,* there will be varied responses to the siting.  To date
Massachusetts" has taken the most direct action in siting.  Efforts to
identify and acquire facility sites have been active since early
1978.2 The state is currently preparing a statewide plan focusing on
Management, institutional and other non site-specific aspects of
hazardous waste management.  The NERCOM study will be used as input to
this plan.  Connecticut is studying its hazardous waste generation and
developing siting criteria.  Connecticut expects to identify candidate
areas for facility sites by eliminating areas in the state which are
unsuitable because of hydrogeoldgy and/or land use.  Connecticut
officials are scheduled to meet with Arther D. Little staff three times
during the course of the NERCOM-sponsored study.  NERCOM's study should
provide analyses which Connecticut can use along with its own study.
   For example, Maine encompasses about half the land area of New
   England, but has less than  10 percent of the region's population and
   3 percent of the hazardous  waste generators.  Massachusetts, on the
   other hand, has 12 percent  of the land area, 48 percent of the
   population, and 45 percent  of the generators of the region.

   See the Sturbridge, Massachusetts case study and the         .
   Massachusetts agency write-up elsewhere in  the appendices to this
   report.
                                 339

-------
Most states do not envision direct involvement by states in developing
specific sites.  Most of those interviewed saw states as being arbiters
for siting processes initiated by the private sector.  The primary goal
of the states was thus seen as not only developing strong and effective
regulatory programs but also becoming much more sophisticated with
respect to the needs of hazardous waste generators, the options
available to the disposal industry, the concerns of the public, and
other critical aspects related to the development of specific
facilities.  It was expected that NERCOM's program would provide states
with a substantial amount of information which would enable them to
analyze more critically the proposals of private industry.  By serving
as a knowledgeable arbiter but not as a developer or proponent of
specific facilities, states could avoid real or perceived problems of
credibility or conflict of interest.  By leaving facility ownership and
operation in private hands, cost-effectiveness would increase and the
potential for public subsidies of useful but uneconomic, facilities
would be eliminated.

Massachusetts and Connecticut have between them 70 percent of the
region's identified industries which generate hazardous waste.   These
states contemplate an active state role in siting.  Massachusetts has
committed itself to acquiring one or more facility sites which would
probably be developed by private industry.  Three potential sites have
already been designated and an ongoing site survey could produce
considerably more sites.  An environmental review of these sites
preparatory to acquisition is scheduled to begin in 1980.   As stated
earlier, Connecticut expects its current study to identify areas within
the state that would be suitable for disposal facilities.   The state
expects public opposition to any potential site to be vigorous.
Accordingly, state acquisition of sites and operation of facilities has
been considered with state or federally owned land being a potential
source of sites.  The Connecticut Resource Recovery Authority, a state
agency which contracts with private vendors for waste-to-energy
facilities, might be a means for state control of hazardous waste
facility operations.

EPA has played an active role in the NERCOM program.  However, in the
future, EPA, from its own and from the states'  perspective, would focus
on ensuring the development of state programs required by  RCRA and on
abandoned sites.  EPA would have a role in any continued NERCOM program
but little if any role in siting of new facilities.
                              340

-------
              NERCOM Issue Paper:  Site Selection Process


Submitted by:  The Commonwealth of Massachusetts

Prepared by:  David Standley, Commissioner, Department of Environmental Quality
     Engineering, and Anthony D. Cortese, Director, Division of-Air and Hazardous
     Materials

Date:  August 7, 1978

     In our opinion the principal criteria to be employed in siting hazardous waste

disposal facilities will ultimately be determined by the final regulations pronul-

gated by EPA under Subtitle C, Hazardous Waste Management, of the Resource Conservation

and Recovery Act (RCRA).  According to our best information, EPA hopes to have

Section 3001, Identification and listing of hazardous wastes, ready for public

distribution by January 1979.  Region I of EPA is of the opinion that April 1979

is a more realistic date.  The. public hearing and review process will take at

least six (6) months.  Therefore, October 1979 is the earliest date by which

Section 3001 will be ready.  Sections 3002-3011 inclusive, and more particularly

Section 3004 which addresses  standards applicable to owners and operators of

hazardous vrasta treatment, storage, and disposal facilities, will not be promul-

gated until the final definitive Section 3001 has been issued.

     In the meantime draft versions of Subtitle C Sections 3001-3011 inclusive

are being circulated to all interested parties for review and comment.  Of

particular interest to State regulatory agencies concerned with land and water

use are the "cradle-to-the-grave" supervision of all hazardous wastes, the "no

endangermGnt"  concept with respect to ground-water resources, the dispute now

going on within EPA as .to whether or not the protection  of ground water is

properly within the jurisdiction of the  Solid Waste Program, and the regulatory

implications of long-term facility monitoring and  in-perpetuity maintenance and

repair;.  Of continuous concern  to regulatory agencies responsible for protecting

air quality standards are'the interstate implications of air pollutant transport


                                        341

-------
(i.e., Che New Jersey case), especially with respect to possible emissions from




a hazardous waste disposal incinerator.  Recognizing that the situation within




EPA is dynamic and subject to change between now and October 1979, the following




criteria for disposal of hazardous waste by landfill techniques or incineration




are proposed for consideration.



Land Disposal




     The technical, environmental and institutional factors affecting the criteria




for identifying and evaluating potential sites for land disposal of hazardous wastes




have been rather comprehensively addressed in the Camp Dresser and McKee (CD&M)




report entitled "Site Selection and Evaluation for Disposal of Hazardous Wastes -




First Report," dated July 1978, prepared under contract to the Massachusetts




Division of Water Pollution Control.  A listing and brief summary of their siting



criteria is, as follows:




     1.   Land requirements (site capacity) - For disposal by landfill




          technology, the required jt:-aa will be dependent upon the form




          in which the wastes are delivered to the site, the volume of




          wastes generated in the area served by the landfill, and the




          contemplated serviceable life of the facility.  Barreled wastes




          will consume available site capacity at a greater rate for a




          given waste volume than disposal sites accepting bulk wastes.




     2-   Location - Preferably centrally located with respect to the




          region of largest generation of hazardous wastes.  A single




          site within a state may impose excessive hauling costs for waste




          generators remote from a central site;-  Therefore, consideration




          should be given to establishing smaller, more local sites to,serve




          the needs of -other waste generators, too remote from a central




          facility.



                                     342

-------
Accessibility - The characteristics  of  the  roadway  to  the disposal




site will affect haul  times and overall safety of transportation



operation.




Geological/hydrogeological Conditions - Given primary  importance b}'




CD & M are the natural characteristics  of a site -  its soil  types,




ground-water levels, and site drainage  conditions.  If possible, sites




within the watershed of public surface  water supplies  should not b.e




considered in initial  site selection.   Sites underlain by extensive




deposits of sands and  gravels should be avoided unless overlain by




substantial thicknesses of fairly impermeable materials.  Sites




considered appropriate would consist of low-permeability underlying




soils such as clays, silts or glacial tills.




Adaptability - Characteristics of hazardous wastes necessitate an




absolutely secure landfill.  This can be both engineered and




constructed at any site, but an area of level or gently sloping



terrain will facilitate construction of the base liner and perimeter




embankments.  The area method of landfilling is recommended  as the



most suitable.




Environmental Impact - Land disposal of hazardous wastes may have




an impact on air, land and water quality which can be eliminated




or reduced to acceptable levels by competent engineering design of




the facility, proper operation, and continuous taaintenance.  One of




the problems of landfill disposal of hazardous wastes not yet




addressed by RCRA or EPA is the possibility of very long-term release




of hazardous or toxic substances into the environment.   Provision for




long-term facility monitoring,  active site closure,  and in-peirpetuity




maintenance and repair should be included in the design phase.   Funding




such activities is a new institutional problem to be solved.





                           343

-------
     7.   Compatibility with Existing and Proposed Zoning and Land Use - Because




          of the nature of the wastes, the best location for a hazardous waste




          disposal site is in an area of low population density isolated from




          most public activities.




     8.   Relative Construction and Operating Costs - Capital costs include site




          acquisition and preparation, such as lar.d clearing, grading, liner




          preparation, installation of drainage facilities, access roads, buildings,




          fencing, sanitary facilities, extension of utilities to the site, special




          site preparation, planting or buffer strips, leachate collection and/or




          treatment facilities.  The major operating costs to be considered are




          adequate suitable cover material, equipment operation, utilities,




          personnel and operation of a leachate treatment system, if required.




          Some gross haul cost estimate should be made or integrated into the




          evaluation process for the relative costs of different sites.




     Obviously no single site will be able to satisfy completly all of the foregoing




criteria.  Some trade-offs will be necessary between environmental, public health,




political, economic and social considerations.  In Massachusetts, the Department




of Environmental Quality Engineering, a regulatory agency, has adopted the policy




that the physical characteristics of a site are less important than its physical




proximity to the largest generators of hazardous wastes.  Public opposition to the




siting of a hazardous waste facility will be generated whenever and wherever a




particular site is designated.  This opposition should be moderated or offset




by the employment opportunities offered by a large waste generator.  Locating a




facility within the major area of waste generation not only saves transportation




costs, but, even more importantly, may result irTless public opposition.




     In terms of purely physical characteristics, geological/hydrogeological




conditions form the single most important criterion. 'This is due to the re-




quirement that there be no degradation of ground-water or surface water, which







                                     -344

-------
in effect general!}  means total containment, with provision for collection and




treatment of, any.Icachate..  Where natural geological conditions cannot provide the




required containment, artificial barriers may be used, but these must be in




the form of a 5-foct thickness of soil having specified characteristics.  Synthetic




liners may not be t.sed in place of earthen barriers.  A.consideration of great




importance is the requirement that funds and procedures must be provided for in-




perpetuity maintenance and repair.               . .     .




     The proposed I.CRA regulations do not at present consider any variation ±n




the degree of hazard, of the various materials which will come under the definition




of "hazardous waste."  If, as appears to be the case, "highly" hazardous wastes




account for only a small percentage of the total volume of hazardous waste




generated, there may be an advantage in dealing with the two categories in separate




facilities.  A landfill for the less hazardous materials would still be required




to meet stringent RCRA standards, but may nevertheless offer the following potential




benefits:  1) it would create less of an environmental and public safety danger,




while solving a large part of the disposal problem for industry; 2) it may engender




less public and political opposition;.and 3) it would allow the very best site




(geologically and environmentally) within a wide area (probably larger than New




England)  to be reserved for disposal of the most dangerous wastes.




Incinerat ion




1.   A  site should be located in an area of good atmospheric ventilation such




that there will be good dilution and dispersion  of  the emissions  (i.e., not in




a valley).




2.   A  site should be located in a rural area such  that there are no sensitive




receptors proximate  (hospitals, nursing homes, schools, etc).  In addition, there




should  be a buffer zone.  This  buffer zone,  should be  to protect against upset




conditions and  the area- of  the  buffer zone  should be  sized such that if an upset
                                     345

-------
 occurs  concentrations  of  the  contaminants or. its complete or incomplet products:




 of combustion would not exceed one half of applicable threshold limit values outside



 the buffer zone.




 Public  Acceptability




     Perhaps the single most  important factor to be taken into account in siting




 a hazardous waste disposal facility is local acceptance of a designated site.




 Public  oppostion to the siting of solid waste disposal facilities for non-hazardous




 wastes  is a matter of  historical record.  How then can we hope to overcome the




 opposition which can be anticipated to the location of a proposed hazardous waste



 disposal facility?




     Various factors affect the acceptability by the public of a hazardous waste.




 disposal facility..  The public must be educated, establishing general public support.




 Compensationcan be a useful incentive in gaining some local support of hazardous




 waste disposal facilities.  A method of site acquisition must be established which




 is generally acceptable but implementable given inevitable local opposition.



 Public Education




     To establish general public support for a solution to the hazardous waste




 problem, an awareness  of  the existing disposal problem must be created.  The




 public must be educated through well-controlled passage of information to interested




 groups, key individuals, etc.   The aim should be to communicate the importance




 of siting a facility for the region-wide benefit and develop public pressure




 to achieve that goal.   The establishment of effective cooperation between industry




and citizens groups should ease the passage of information and therefore communicate




the necessity of siting a facility.   State sup'pbrt of industry must be displayed




openly.  Legislative mandates  should be obtained to involve the state in assisting




industry with hazardous, waste  disposal.




     To enlist specific local  support for siting a hazardous waste disposal




facility,  a combination of support from local officials and community groups must




                                   346

-------
be gained.  Environmental laws have provided the opposition with tools to support,




their views.  The requirements for environmental impact statements have given




groups increased power to.block or delay possibly environmentally adverse or even




environmentally reasonable projects that are deemed undesirable.  There is also a




traditional and legal commitment to local autonomy and local control over .land




decisions as demonstrated in the manner zoning has developed.  The number of




examples that demonstrate that local or other special interest groups can block




the siting of potentially dangerous facility (prisons, nuclear power plants, ns-.tural




gas facilities, solid waste disposal sites, oil rafineries, tanker docks) is  '.




increasing.



      Ideally, it would.be nice to achieve voluntary local  acceptance of a facility




through bargaining and sound  environmental  and  technical arguments.  However, some




people who  deal with  local public opposition will  cite the "irrationality"  of the




public response to many  issues.  This may be particularly  true  for a hazardous waste




facility, as  the  track record for both  solid waste dumps and hazardous waste




handling  companies  is poor.   Because such a poor history pf disposal operations




can be cited, perhaps it is misleading  to term  public reaction  to the  siting  of




another,  even less  attractive waste facility, as "irrational".   However,  such




 irrational  local  opposition  to facilities  that  may,  to some people,  appear  ben&ficial




must be  considered  in siting  such a facility.   If  there is enough opposition to  a




 specific proposal,  a very rational argument can almost .always  be developed  and




 used to  influence the  decision-making process.




      This works at  cross purposes to the ..common approach to siting a facility.




 The approach is to  develop technical and economic  arguments so sound that any




 ensuing political battles can be easily weathered under the roof of sound reason.




  However,  the determining issues are frequently more than technical.  The  political




  process can uncover a  variety  of  opposing goals  and vested interests, and




  technical arguments can be  found  to support or refute any conclusion offered.




  This is illustrated by the  difficulties the courts  have  had in hearing many




                                     347

-------
 environmentally  related  cases.   Particularly,  for  these  cases, and similarly foe




 arguments  opposing facility  siting,  technical  arguments  can be "on the  frontiers




 of scientific knowledge,"  and  proof,  in  fact,  cannot be achieved.  But even for




 well known scientific subjects,  opposing  technical arguments  can be; formulated.




 Judge Bazelon of the B.C.  Circuit  Court has  expressed the Court's uneasiness with




 judging technical facts: "...in cases  of  great technological  complexity,  the bast




 way for courts to guard  against unreasonable or erronebus administrative  decisions




 is not for the judges themselves to  scrutinize the technical  merits of.each decision.




 Rather, it is to establish a decision  making process  that assures a reasoned decision




 that can be held up to the scrutiny  of the scientific community and the public.''•




         A  community should be informed of a  decision  to  investigate a specific site




 within its boundaries for  the possibility of hazardous waste  disposal.  Public




 meetings should concentrate  on  allox-ring citizen input into the .decision-making




 process.  Before meetings  are conducted,  it  is necessary to have a good understanding




 of all relevant facts and  environmental impacts associated with site  acquisition and




 development




         It is important  to note at this point  that financial  and manpower  resources




 are necessary for public education needs  to  be met.





 Compensation




     In the siting of resource recovery plants, it  has been shown  that the  payment




of a "bonus" of one dollar  a  'ton for solid wastes accepted from outside  the immediate




area can be a useful incentive for communities  to accept  negatively  viewed  facilities.




In the case  of siting a hazardous waste disposal facility, considering  that  it may




be relatively more dangerous, a similar compensatory approach requiring payment  of




a greater monetary sura may reduce local opposition.  Following the determination




of a fair compensation sum by all parties concerned (local government, industry, and




state ), a statutory basis for comensation must be established.




Acquisition                                                                        ~ 34
-------
    necessary to the public good.  Experience with State use. of eminent domain •




    powers when locating socially dangerous facilities, such as prison siting,




    illustrate why a state is reluctant to use this power,   However,  when local




    opposition cannot be overcome by public education and financial incentives,




    and when the need for siting a hazardous waste disposal facility clearly exists,




  •  exercising the power of eminent domain must be seriously considered.




         The most realistic approach to siting a hazardous  waste disposal




    facility will probably be a combination of the above mentioned approaches.




    Various types of bargaining techniques may be employed, such a mediation.   It




    appears that compensation and, at least, the threat of  eminent domain will be




    involved if all parties are to bargain from positions of strength.  It is




    becoming clear that lack of public involvement in the decision-making




    process may lead to serious confrontations when the decision is ready to




    be implemented.  Unfortunately, there is no assurance that full public




    involvement from the beginning will lead to a more acceptable decision.




         "The siting of a hazardous wasLe facility warrants care in planning the




    approach to dealing with the local group to be negatively impacted by the




    facility.  In particular, the timing and degree of public involvement in the




    decision-making process is important.  A delicate balance will have to be




    struck between the traditional completely technical approach and a possibly




    protracted and unwieldy citizen participation".




Technical Considerations





         Public opposition _to the siting of a hazardous waste disposal facility




    will unquestionably be successful unless the following  technical factors have




    been thoroughly considered and evaluated for their potential impact as either




    a public nuisance or a threat to public safety:




         (1)  All of the siting criteria suggested by CD&M;




         (2)  Screening and distance separation from residential areas;






                                        343

-------
      (3)  Transportation routes to and from the facility;/
      (4)  Spill planning;    •...-..          .     ..•_,.:  ••,•;•.-,   ;t-,;,        :;-
      (5)  Noise control;                               -,,„,._.     ,     ., ...  ,..>j.  :  v
      (6)  Failsafe engineering for prevention -of explosion and leakage;
      (7)  Controlled access to site to prevent accidental trespass by    •
          children or domestic animals.
The Role of NERCOM in the Site Selection Process       .	   ..
     At the last meeting of NERCOM the Commonwealth of Massachusetts, in conjunction
with, the other New England states, was contemplating the idea of. a single regional
hazardous waste disposal facility which could serve the needs of the entire region.
Since that time we have thoroughly researched the need within Massachusetts for
such a facility.  We have reached the conclusion that the largest volume of so-
called "hazardous wastes" generated .in the State are capable of being detoxified
or stabilised to a point where they can safely be disposed of by special landfilling
practices or by incineration.  We have developed and implemented a policy for the
environmentally safe disposal of metal hydroxide sludges, liberally borrowing
from the Connecticut guidelines.  We are now in. the process of developing state
policy for handling and disposal of oil spill debris, reprocessing solvents, and
latex wastes.  When we have solved the disposal problem for these four  (4) types
of wastes, we anticipate that the total volume of residual hazardous wastes shall
be greatly reduced.  For the remaining hazardous wastes we advocate disposal at
one of the existing hazardous waste disposal facilities, either in New York or
New Jersey.
     We believe that the other New England states would benefit from a similar
evaluation of their own "hazardous wastes" volumes.  If similar satisfactory
techniques and state - sponsored disposal practices can be developed and
implemented in each of the-New England states, there is a strong possibility that
the total remaining volume of "hazardous wastes" would be insufficient to justify
the establishment of a New England regional disposal facility.
                                     350

-------
     If that should prove to be the case, we believe that NERCOM can provide a

valuable function as an institution:                          --.-'._•••

     (1)  to dissemirate information about policies and procedures for safe

          intrastate disposal of "hazardous wastes";          ;

     (2)  to provide technical assistance on specific chemical wastes .and

          suitable methods for their safe immobilization and-disposal;

     (3)  to publicize the existence and availability of the only privately

          operated waste exchange facility in New England, the Natural Resource

          Recycling Center, 286 Congress St., Boston, MA;

     (4)  to avoid activities designed toward site selection of a suitable

          New England site and concentrate on the suitability of the siting

          criteria tc be applied within the individual states; and

     (5)  to investigate the feasibility of establishing a New England regional

          reprocessing center for resource recovery rather than disposal.
                                     Reference
 1.   International Harvester Co. V. Ruckelshaus, U.S. App.
      D.C., 411, 448 478 F.2d 615, 652, 673

-------
               APPENDIX C




INFORMATION ON STATE REGULATORY AGENCIES

-------
ARKANSAS DEPARTMENT OF POLLUTION CONTROL AND ECOLOGY

In the state of Arkansas the primary responsibility for regulatory
hazardous waste management facilities rests with the Department of
Pollution Control and Ecology (DPCE).  A hazardous waste management act
became law in Arkansas in March, 1979.  Interim regulations are expected
to be promulgated by July, 1979.  The discussion below refers to these
regulations.

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  21

Agency Budget:  $132,000 (FY 1978)

Commercial HWMFs:  1 permitted facility

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — DPCE has the right of access to hazardous waste
management  facilities to determine whether they are in compliance with
the regulations.  What institutional arrangements will be used to carry
out these inspections has not yet been determined, but it is expected
that there will be a group of inspectors working out of the central
office in Little Rock.

Enforcement Actions —In the case that there is an imminent hazard, the
DPCE is empowered to issue a cease and desist order (the recipient of
the order then has 10 days to contest this in court).  There are also
civil and criminal penalties for violating the regulations, but these
must be handed down by the courts.   At present the DPCE must work
through local prosecutors to take a  violator to court.  However, an  .
enforcement branch is now being organized which will enable them to  do
this for themselves.

Monitoring  — The hazardous waste management act allows the DPCE to
establish monitoring  programs for hazardous waste management facilities.
It is expected that these programs will follow EPA guidelines.
Facilities  may require different  types of monitoring depending  on  the
type of operation and types of  wastes being stored, treated, or disposed
of.

Manifest System — The new regulations establish a manifest system for
cases in which a generator is disposing of wastes in a commercial  site.
On-site  disposal  is not  covered,  and they  have not yet decided  whether
shipments  to off-site, captive  facilities  will be covered.  In  making
this  decision  the DCPE will  probably follow EPA's lead.   Also,  it  is not
certain whether special  wastes  (e.g., waste oil) will be  covered by this
system.                   .    ,
    DPCE has authority for 11 positions as of July 1,  1979.

-------
Defining Hazardous Waste — The definition of hazardous waste closely
follows the EPA definitions, with two exceptions.  Hazardous waste is
defined as:

       A solid waste, or combination or solid wastes, which because of
       its quantity, concentration, or physical, chemical or infectious
       characteristics, may, in the judgment of the department —

             (a)   cause or significantly contribute to an increase in
                   mortality or an increase in serious, irreversible, or
                   incapacitating reversible, illness; or,

             (b)   pose a substantial threat or potential hazard to
                   human health or the environment when improperly
                   treated, stored, transported, or disposed of, or
                   otherwise improperly managed.

The underlined sections were added by the DPCE.

Coverage of Permit System — Any facility which stores, treats and/or
disposes of hazardous wastes, and any person who develops and/or
operates such a facility must first receive a DPCE permit.  For a given
operation, this permitting  can be done together or separately.

AGENCY VIEWS'

The DPCE feels that  siting  of hazardous waste management  facilities will
be the most difficult problem they will face in the hazardous waste
field in coming years, and  that gaining public acceptance for these
facilities will be the reason it is so difficult.  The technical
problems they face are not  that great.  There are  technically acceptable
areas for hazardous  waste facilities in the state.

The DCPE has an embryonic public awareness program which  is being set up
to  try  to  deal with  this  problem, but  the  extent of  this  program is very
limited because the  state legislature declined to  fund it sufficiently.
They now hope to  get EPA assistance  in this area.  However, they are not
sure that  such a  program can be effective.

Respective government  roles in siting depend, the  DPCE has  indicated, on
the  type of  facility being  sited.  A facility which  intends to  accept
PCBs, for  instance,  would obviously need much more federal  involvement
than would one which does not.   Generally,  though, they  feel- that EPA
should  have  a supporting  role—providing technical assistance and
funding.   The  states should themselves be  directly involved to  the
extent  that  direct government  involvement  is necessary  (e.g., public
awareness).  Local  governments were  seen to  play a critical role, but
not  to  be  officially involved  in  the process per se.   They  are
considering options  such  as fee-splitting  to give  local  government
officials  an acceptable reason for supporting the  siting  of such
facilities in  their  districts.
                                 354

-------
CALIFORNIA"DEPARTMENT ?QF. HEALTH. SERVICES
Within, the state of California, the.regulation,of hazardous, waste
management,is primarily the responsibility of.the State Department of
Health Services (DH.S).  However, other .state and, local. agencies also
play a significant role in the regulation of such facilities and
operations.  The,more important of these latter agencies, include the
.Regional Water Quality Control Boards, the Regional Air Pollution
Control Districts, and the local.planning board.

AGENCY CAPACITIES AND COMMERCIAL HWMF           ....

Staff Positions:, 291  '."'..            :.:-...•'•

Agency Budget:   $1,489,0001

Commercial HWMFs:  11 permitted facilities

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM             ,

Facility Inspections — DHS regulations allow Department representatives
to enter any "factory, plant, construction site, waste disposal site,
transfer station or other area where wastes are stored, handled,
processed or disposed of" to "inspect the premises and gather evidence
on existing conditions and procedures."  Vehicles suspected of
transporting hazardous wastes may also be stopped and inspected.  No
specific schedule of inspections is required.

Enforcement Actions—The DHS maintains an inspection and compliance
program, with inspectors permanently in. the field.  DHS response to
violation of regulations can'range from merely requesting that the
conditions or practice be corrected to criminal prosecution.  The latter
must be undertaken by the state Attorney General.  Sanctions are
identical to those proposed by the EPA.

Monitoring — Monitoring is not required by DHS regulations.  Monitoring
of ground and surface water is required, however, by the Regional Water
Quality Control Boards.  These programs are established on an individual
site basis.  For processes and operations which may affect air quality,
monitoring may be required by the Regional Air Pollution Control
Districts..

Manifest, System — The regulations require that all hazardous waste
transported off-site, except those transported by .pipeline, must be
accompanied by a manifest.  This manifest must first be filled out by
   Source: U.S. Government Accounting Office, ."Hazardous Waste
   Management Programs Will Not Be Effective," January 23, 1979.
                                 355

-------
the producer, who must provide a'description of the waste including the
type, chemical composition and special handling instructions.  Both the
hauler and the off-site facility operator are required not to accept any
wastes without a properly completed manifest, and the operator must
inspect the wastes before accepting them to ensure that the manifest
description is correct.  The producer, hauler and operator must each
submit a copy of each manifest to the DHS.

Defining Hazardous Waste — "Hazardous waste" is defined in DHS
regulations as "any waste material or mixture of wastes which is toxic,
corrosive, flammable, an irritant, a strong sensitizer or which
generates pressure through decomposition, heat or other means, if such a
waste or mixture of wastes may cause substantial injury, serious illness
or harm to humans, domestic livestock or wildlife."

Coverage of Permit System — Permits are required for any facility which
"handles, stores, treats or disposes of a hazardous waste" and which
contains at least one area where "hazardous wastes are stored, mixed,
handled, treated, discarded or disposed of."  The only exceptions are
for facilities "using a biological process on the property of a producer
treating oil, its products and water..."  The DHS is required to review
each permit at least every five years.  Haulers of hazardous waste are
required to hold a valid registration issued by the DHS.

AGENCY VIEWS

The DHS role in the regulation and planning of hazardous waste
management activities in California has been expanded during the last
several years.  From 1973 through 1978 their role was purely advisory.
Since 1978 a DHS permit has been required for operation of hazardous
waste facilities, and starting January 1979, DHS is to provide statewide
planning for hazardous waste site identification and assessment.

The agency feels that the following factors are most likely to cause
difficulties in siting facilities:

    o    public opposition;

    o    time required to obtain environmental reviews and required
         permits;

    o    cost of providing environmental impact reports and other
         information required for approval of proposed facilities;

    o    environmental conditions at proposed sites;  and

    o    cost of transporting wastes to the proposed site.

-------
They report that it currently takes three to five years to establish a
site, and that during the years 1970-1976, only two of seven proposed
sites were approved.

The criticism.most frequently voiced of the current system of hazardous
waste regulations in California is that there are too many agencies
involved in this process.  The proposed Padre Juan facility, admittedly
an,exceptional case, would have required permits form eight agencies.
One result of this problem is that wastes which are considered hazardous
by one agency are not necessarily so regarded by the other agencies
concerned.  For instance, brines are considered hazardous by the
Regional Water Quality Control Boards, but not by the DHS, and asbestos
is considered hazardous by the Regional Air Pollution Control Districts,,
but not by the Regional Water Quality Control Boards.  It is reported
that a coordinating committee has been set up to resolve such problems
and to establish a one-step state-level permit process.

With the exception of these institutional problems, it is generally
thought in California that their system of hazardous waste regulations
go beyond and are superior to RCRA.  One example of this which was'cited
is their monitor reserve fund.  In California, the fund is based on the
estimated cost of site closure — not a fixed cost for. all sites— and
is revised and updated annually.  This fund can be borrowed from for
emergency corrective action.  In addition to this individual fund for
each site, there is a statewide revolving fund — based on a per unit
disposal charge — which would be used if an owner's fund is exhausted.
The attitude in California seems to be ,that they do not need EPA.
                                357

-------
IDAHO DEPARTMENT OF HEALTH AND WELFARE              ,  •     .>  :',

In Idaho the principal responsibility for the regulation of hazardous
waste management rests with the state Department of Health and Welfare
(DHW).                                                   ;

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  3     '                                  ' .

Agency Budget:  $83,0001

Commercial HWMFs:  2 permitted facilities                 .  ,

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM  •  -:

Currently, there are no state laws specifically pertaining to hazardous
waste disposal in Idaho.  However, there are regulations which govern
the disposal of solid waste, and legislation covering hazardous waste
disposal is now being prepared by the DHW.

The proposed legislation is expected to be roughly equivalent  to EPA's
proposed RCRA regulations, with the exception that DHW might classify
hazardous waste into several categories.

Facility Inspections — The present solid waste disposal law provides
for the inspection of all solid waste disposal sites, which therefore
covers all sites at which hazardous solid waste is disposed.   The
proposed legislation would extend this to all hazardous waste disposal
sites.

Enforcement Actions— DHW's first step in enforcing regulations is to
provide technical assistance.  If this is not successful, they now have
authority to take the offender to court, as a result of which fines up
to $1000 per day per violation can be assessed.

Monitoring — Existing regulations do not require any monitoring.  The
proposed regulations would require the monitoring of ground and surface
water.

Manifest System — Neither the existing regulations nor the proposed
legislation has a provision for a manifest system.  It is still possible
that such a system will be added to the proposed legislation.
   FY 1978; FY 1979 figure is $106,000.
                                358

-------
Defining Hazardous Waste — Existing regulations define only solid
waste.  The proposed legislation, on the other hand, defines hazardous
waste very broadly.  It refers to any solid, liquid or gaseous .material
which is toxic, corrosive, flammable, bioconcentrative, infectious, or
which causes an increase in mortality.  It does not include high-level
radioactive wastes which are subject to other Idaho state regulations.

Coverage of Permit System — The current system of regulation includes
an approval process for all solid waste disposal sites.  The proposed
legislation would include a requirement that all hazardous waste
storage, treatment and disposal facilities be permitted.

AGENCY VIEWS                     :-....,..

The DHW has indicated that it feels there are three broad categories of
problems to be faced in siting and operating'hazardous waste facilities:
public acceptance,.technical assessment and operation..  Project
acceptance by local elected officials was not, however, seen as a
problem.  National media emphasis on the hazards associated with
chemical wastes was blamed for much of the public opposition.  Technical
assessment of proposed sites was felt to be a problem due to the
difficulties of assessing the role of improbable events.  They recommend
that the site and operation be able to manage a "worst case".  Potential
operational problems include financial responsibility, bonding, daily
site operation, employee safety and accident prevention.

T,he DHW proposes that specific authority to review and establish the
suitability of sites in advance of specific proposals would be, in their
case, useful.  They also noted that government agencies should provide
technical assistance, inspection and review of hazardous waste  ,
management facilities, and that they would support a state or federal
waste disposal tax to be used in case of accidents or for long-term
care.
                              '353

-------
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY                       ;  :.

The regulation and planning of hazardous waste management in the state
of Illinois is primarily the responsibility of the Illinois
Environmental Protection Agency (IEPA).

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  71                   .

Agency Budget:  $124,OOO1

Commercial HWMFs:  2 permitted facilities2

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — The IEPA is authorized "to conduct a program of
continuing surveillance and of regular or periodic inspection.. .of the
refuse disposal sites'1.^  The Division of Land Pollution Control's
Regional Environmental Protection technicians have as one of their
responsibilities to routinely inspect and report on the operational
status of all refuse disposal sites in Illinois, including hazardous
waste management facilities.

Enforcement Actions — Cases involving serious.or repeated violations of
IEPA regulations are taken before the Illinois Pollution Control Board,
and the IEPA is represented there by the state Attorney General's
office.  The Board has the authority to levy fines up to $10,000 plus
$1,000 per day per violation.

Monitoring — There are no requirements for monitoring.  Any data the
IEPA requires are gathered by its own technicians during their routine
inspections.

Manifest System — New Special Waste Hauling Regulations took effect on
July 1, 1979 in Illinois.  Special wastes are in essence all wastes
except garbage, and include hazardous wastes.  A manifest is required
for all such waste generated in Illinois and hauled for storage,
disposal and/or treatment within or out of state, and for all such waste
hauled into the state.
   Source:  U.S. General Accounting Office, ."Hazardous Waste
   Management Programs Will Not Be Effective", January 23, 1979.

   Illinois has 2 permitted HWMFs, only one of which is currently
   operating.  In addition there are approximately 50 facilities which
   co—dispose hazardous and solid waste.

   Environmental Protection Act, Title 1, Section 4.
                               360

-------
 Defining Hazardous Waste — Hazardous waste is defined as "solid waste
 with inherent properties which make such waste difficult to manage by
 normal means including but not limited to chemicals,  explosives,
 pathological wastes,  radioactive materials, and wastes likely to cause
 fire."*

 Coverage of Permit System — A permit is required to  engage in any
 treatment,  storage,  transportation or disposal of hazardous waste.   The
 only exception is for "any person engaged in agricultural activity who
 is  disposing of a substance which would normally be classified as
 hazardous if that substance was acquired for use by that person on his
 own property."^

 AGENCY VIEWS                      .

 The IEPA already has  a system of hazardous waste regulations.   However,
 they anticipate that  these regulations will soon be changed to conform
.with EPA's  RCRA regulations.   They expect that this will result in their
 regulation of hazardous waste management being considerably more
 stringent.   At the same time,  they feel that EPA and  RCRA have created
 more problems than solutions.   In particular,  they noted the failure in
 RCRA to distinguish between the degrees of hazard posed by different
 types of hazardous waste.   Notwithstanding these planned changes, they
 feel that it will become increasingly difficult if not impossible for
 private firms to site hazardous waste facilities, and that more direct
 government  involvement will be necessary.   This involvement could be
 limited to  perpetual  maintenance,  or the site itself  might have to be
 owned by state or federal  government and leased to a  private operator.
 IEPA is not enthusiastic about the latter option, but feels it may be
 necessary.   With this in mind, they saw no role for EPA in siting now,
 but a substantial role in the future.

 The state of Illinois can now preempt local zoning to site hazardous
 waste facilities.   However, this was not seen as a solution to the
 siting problem because it cannot avoid due process.   Preemption does,
 however,  allow local  elected officials to save face by protesting
 publicly against the  site  while otherwise cooperating.   In siting new
 facilities,  they suggested that it might be wiser to  first determine
 what sites  are politically acceptable and only then conduct a thorough
 technical review,  rather than the  other way around, since the former
 factors are more likely to cause problems.
    Illinois  Pollution Control Board Rules  and  Regulations,  Chapter
    7,  Part  1.

    Illinois  Environmental  Protection Act,  Section  21(e).
                                 361

-------
KANSAS DEPARTMENT OF HEALTH AND ENVIRONMENT

In Kansas regulatory responsibility for hazardous waste rests with the
Department of Health and Environment (DHE).

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  5

Agency Budget:  $251,000

Commercial HWMFs:  1 permitted facility.          '

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM      '        ''

Facility Inspections — DHE has the authority to inspect facilities and
one DHE staffer's primary responsibility is the inspection of Kansas'
only commercial disposal facility.  Inspections are regular and
frequent.

Enforcement Actions — A variety of actions 'may be taken to enforce
state law and regulations including orders to alter procedures,
suspension or revocation of permits, and, in addition to other penalties
provided by law, fines of up to $500 per Violation per day.

Monitoring — Environmental quality monitoring systems are required for
all hazardous waste facilities.  DHE establishes specific requirements
for monitoring wells, air monitoring stations, frequency of sampling,
analyses required, and post-closure monitoring on a case<-by-case basis.

Manifest System — State regulations require the use of manifests by
generators, transporters, and facility operators.  Copies of the
manifest must be sent to DHE by generators and facility operators.

Defining Hazardous Waste •— State law defines hazardous wastes as those
which are harmful to human health or the environment because of their
quantity, concentration, or physical, chemical or infectious
characteristics.

Coverage of Permit System — Generators, transporters, storers, and
disposers are covered by state regulations and/or permits.  Permits must
be obtained for facilities that store, transfer, process, or dispose of
hazardous waste.

AGENCY VIEWS   '                         '    :\  "  i:;    :   :;.;;;;'

DHE officials noted that Kansas is in a fortunate position with repsect
to hazardous waste management.  The state is not a major generator of
                               362

-------
hazardous waste and so the one commercial facility in the state should
serve its needs.for a considerable period.  In addition DHE felt much of
the waste brought into the state can be rendered non-hazardous.

Nevertheless they did consider siting to be probably the most difficult
obstacle to overcome in implementing RCRA.  A number of factors were
seen as contributing to the siting problem.  People do not have great
trust in EPA or state agencies.  It has become more difficult to
convince localities of the need for siting commercial facilities,
particularly in remote areas where local economies do not depend on the
industry which generates hazardous waste.  Local communities .see.no
economic benefit flowing to their communities and there is no extant .
system for rewarding communities for the economic damage they may
suffer.  If, as is likely, facilities would need to import wastes from
out of state to be economically viable, the economic disbenefits would
be perceived as being even more remote.  Regardless of facility design
or operation, risk cannot be eliminated.  For these reasons local
opposition to facilities was seen as expected and in keeping with
growing opposition to siting of any number of facilities such as
airports, dams, and nuclear generating stations.

EPA was seen as contributing to the problem.  EPA was criticized for
focusing on traditional.regulatory sanctions and on hazardous waste
problems, while ignoring the need for creative solutions to the siting
problem.  Concern was also expressed over the fact that siting will
become increasingly complicated and long as RCRA takes effect.  As the
siting process becomes more intricate, the chance for procedural error
increases and thus the chance for legal action based on procedural error
increases.                      .

The siting problem was thought to be sufficient to lead to more    :.
governmental involvement.  Veto power over local zoning may have to be
given to state or federal agencies.  (It was noted, however, that a
facility spqnspr, could simply avoid sites regulated by local zoning.)
Should this governmental power be used to benefit private industry,
precautions would need to be taken to prevent abuse, and utility-type
regulations might have to be applied to disposal facilities.    .

If in the next  several.years the siting problem cannot be resolved then
government ownership of sites may have to occur.  .Actual facility
construction and operation could be accomplished by private industry.
While such an option would not address many or any public concerns,
government ownership could guarantee the best available site selection
and perpetual care of closed facilities.  These are two issues of
critical concern to DHE.

-------
MARYLAND.WATER RESOURCES ADMINISTRATION

The Maryland Water Resources Administration (WRA) regulates hazardous
waste management.  Maryland Environmental Services (MES) has planning
and management responsibilites for a variety of industrial waste
problems, including hazardous waste.        ,

AGENCY CAPACITIES AND COMMERCIAL HWMFs                       .       ,

Staff Positions:  71

Agency Budget:  $265,OOO1

Commercial  HWMFs:  4 permitted facilities        . ,•           .   •  .

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — Regulations require that WRA representatives be
given access to facilities at any reasonable time to inspect facilities,
review records, or gather any needed information.

Enforcement Actions — WRA may modify, suspend, or revoke in whole or in
part any permit or other approval it has granted.  Violations are also
subject to civil and criminal penalties.

Monitoring— Facility sponsors must include plans for the design and
installation of piezometers, ground and surface water monitoring
systems, and air emission sampling stations.  The frequency and extent
of monitoring activities and reporting requirements are determined
individually by WRA.

Manifest System — Generators, transporters, and facility operators must
use a manifest sytem and facility operators must submit manifest reports
to WRA periodically.               •   •   ..

Defining Hazardous Waste — Maryland defines hazardous substances in
three classes by degree of-hazard.  Criteria which include and go beyond
•those defined by RCRA are used and specific substances are listed.

Coverage of Permit System — Generators, transporters, and facility
operators are covered by regulations and/or permits.   Permits must be
obtained for storage, treatment, and disposal facilities.
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23, 1979.
                                364

-------
"AGENCY VIEWS

WRA officials considered local opposition to siting a major problem in
developing new disposal capacity.  Easing these problems and overcoming
public fears might be possible by demonstrating' safe operations at a
facility; however, if no facility can be sited then it becomes difficult
to demonstrate a successful operation.

WRA noted several factors  that could improve siting processes.  The .
probable location of sites can fall into two categories — remotes sites
which are "hidden" from public veiw and industrial sites which are
"camouflaged" by surrounding  industrial development.  Public involvement
should begin early before  positions are hardened and opposition becomes
emotional.  Public education  should be stressed so that local residents
can become valuable  contributors.  Education should stress the benefits
from industries which generate hazardous waste.

Regardless of these  or other  actions, it was considered likely that
local  opposition  could not be overcome.  Given that the lack of disposal
capacity will have a severe  impact on industry, states may have to
acquire and  operate  sites.  If  this  option is  chosen, WRA already has
the power to condemn land  for sites.

MES has had  more  experience  in siting then WRA and expects to be more
 directly  involved in future  siting efforts. MES  feels  there  is a clear
need  for  state  assistance  in developing  one, or more secure landfills.
 It was involved in an unsuccessful siting  attempt for  a facility  to
 serve Allied Chemical  (see the Allied  case study  elsewhere in this
 report).   In part because of that experience MES  feels  that a
 multi-county regional approach to developing  facilities should be
 adopted with facilities  serving all  regional  generators.   This would
 reduce problems associated with single  industries siting  facilities
 outside of  the community which receives economic  benefits from that
 industry.   A regional  approach might also  reduce  political pressures  on
 local officials.   If states were to  take strong positions,  possibly by
 overriding local controls, then political pressures could be  directed
 away from the local level and towards  the state level where  they  could
 be more easily endured.   Because most  facilities  would likely be  located
 in rural communities distant from industry, amenities and financial
 compensation may be politically necessary incentives.   However,  the use
 of such incentives in and of themselves was seen as probably ineffective
 in overcoming opposition.

 Industry was seen as being in a position to facilitate siting.   Industry
 could publicize its need  for disposal facilities to make the public
 aware of the hazardous waste problem.   More effective use could also  be
 made of industry's political power to ensure that government is aware of
 its needs.
                                  365

-------
MES officials felt that EPA should probably not  require all states to
have hazardous waste landfills.   States would Resent  this federal
intrusion which would likely involve an unnecessarily large and
burdensome set of regulatory and administrative  requirements.  Only if
states are totally unable to solve the hazardous waste problem should
EPA become directly involved in  siting.
                            366

-------
MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL DUALITY ENGINEERING

The Massachusetts Department of Environmental Quality Engineering (DEQE)
has regulatory responsibility for hazardous waste.  The responsibility
for hazardous waste planning and management rests within the Department
of Environmental Management (DEM).

AGENCY CAPACITIES AND' COMMERCIAL HWMFs
Staff Positions:  4J
Agency Budget:  $100,000
                        1
Commercial HWMFs:  28 licensed firms''

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — DEQE may inspect any facility at reasonable
times on reasonable notice for purposes of examining the facility, its
records and inventory and taking any samples of wastes.

Enforcement Actions — Violations of regulations are subject to fines of
up to $1,000.DEQE may also revoke any license subject to applicable
hearing requirements.

Monitoring — Existing regulations do not specify any monitoring
requirements.  In developing plans for a facility in Sturbridge,
however, proposed RCRA regulatory requirements were followed by DEM,
including the provision of monitoring wells.

Manifest System —- Transporters of hazardous waste must carry records
describing the origin, quantity, and destination of their loads.  These
records must be retained for one year, and monthly summary reports must
be forwarded to DEQE.
    Source:  U.S. General Accounting Office, "Hazardous Waste
    Management Programs Will Not be Effective," January 23, 1979.
    Data refer to DEQE.          ,

    In 1978 DEQE records showed 22 commercial firms licensed for the
    storage of hazardous waste, the majority of which handled waste oils
    or oil spill debris.  Of six licensed  commercial treatment and
    disposal firms, half were  restricted to waste oils or solvents.  No
    major commercial  facilities which ultimately disposed of a broad
    range of hazardous waste were licensed.  Consequently, out-of-state
    facilities were used.
                                 367

-------
 Defining Hazardous Waste — The definition encompasses waste which is or
 may be dangerous to public health or the environment by virtue of its
 chemical, radioactive, flammable, explosive,  or other characteristics.
 These wastes are also classified by groups, and disposal methods
 emphasizing reuse or detoxification are prescribed for each group.

 Coverage of Permit Sytstem — Transporters, storers, and disposers  are
 covered by the regulations, as are facilities for the storage,
 treatment, reclamation,  incineration,  and land disposal of  hazardous
 waste.  Generators are exempted from existing regulations but will  be
 covered by new legislation expected to take effect by early 1980.

 AGENCY VIEWS

 A DEQE official saw essentially two roles for that agency.   One  was to
 encourage in a general fashion the development of disposal  facilities.
 In support of this role  the agency sponsored  an evaluation  of  ten
 prospective sites  in the state;  it also  has made public presentations to
 explain the nature of the state's hazardous waste problem.   The  other
 major  role is the  enforcement  of  existing regulations  to  ensure  proper
 disposal of waste.

 DEM as a planning  and management agency  is more directly  involved in the
 siting of specific facilities  and managing the disposal  of  waste.   A DEM
 official indicated that  the agency has taken  a position of  promoting
 waste  reduction, the use of waste exchanges,  and processing and
 treatment over land disposal which is  considered a last  resort solution.
 Hazardous waste management  was  seen as a  private sector problem
 requiring a private sector  solution.   Industry faces  formidable
 obstacles to  siting facilties,  however, and DEM can  play a needed role
 in overcoming that barrier.  (Unlike private  industry, DEM does  not need
 local  approval  to  acquire a disposal site.)   While DEM originally
 envisioned a  role  primarily confined to  site  acquisition and facility
 planning,  its recent  experience has led  to  greater involvement.  A
 DEM-sponsored state plan is being  prepared which  addresses a range  of
 general hazardous waste  issues and may lead to  greater state control
 over the  treatment  and disposal of waste.   In  part this evolving role
has resulted  from public concerns  expressed over the potential
 development of  disposal  facilities at three sites in the state.*'
Among  the  options  to be  considered is compensation to host communities
 to  offset  the disincentives  of developing a facility.

From OEM's perspective, EPA must be willing to support the states which
are attempting  to develop,facilities and must  be willing to  absorb the
inevitable abuse and criticism from opponents  of state efforts.  Because
of its public credibility, EPA can play a major public relations  role.
EPA's Region I office was considered quite useful in supporting state
   For a discussion of OEM's siting experience, see the Sturbridge,
   Massachusetts case study in Appendix A.
                                 368

-------
efforts.  On the other hand, EPA headquarters was seen as having a more
academic understanding of problems, but not being implementation
oriented and having no practical experience.  As a result, EPA
headquarters was seen as having no appreciation of the real problems in
siting hazardous waste facilities.  One role DEM specifically did not
want EPA to play was that of needlessly scrutinizing and criticizing
minor points of state efforts to site facilties and thereby avoiding any
real involvement in or support of state efforts.  Finally EPA was seen
as a potential provider of liability funds in case of operational,
problems at facilities.  Liability and long-term care of facilities was
seen as a governmental (though not necessarily federal) function because
these burdens could markedly discourage any private sector involvement.

-------
MINNESOTA POLLUTION  CONTROL AGENCY

The regulation of hazardous waste management in the state of Minnesota
is primarily the responsibility of the Minnesota Pollution Control
Agency  (MPCA).  Hazardous waste regulations in Minnesota have only
recently  been approved and take effect in June 1979.  It is anticipated
that these regulations will be challenged in court by a group of
industries which generate hazardous waste.

AGENCY  CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  41

Agency  Budget:  $140,OOO1

Commercial HWMFs:  None^

SELECTED  ASPECTS OF  STATE HAZARDOUS WASTE PROGRAM

Facility  Inspections — The MPCA does have the authority to inspect
HWMFs,  but there is  no requirement that they do so on a periodic basis.

Enforcement Actions — The MPCA itself has authority to invoke sanctions
such as site closure to enforce its regulations, although such a severe
penalty is not common.  A stipulation agreement requiring the correction
of a violation is a more likely result if regulations have been found to
have been broken.  The regulations do not provide for specific civil or
criminal  penalties for violation other than site closure.

Monitoring — MPCA regulations require that the operator of a hazardous
waste management facility have in operation a monitoring system before
accepting any hazardous wastes.  The nature and extent of the monitoring
system  depends on the type of facility and is determined on a case-by-
case basis, subject to approval by the MPCA.

Manifest  System — The regulations require that each generator prepare a
manifest  ("shipping papers") for each shipment of hazardous wastes.  The
hauler and management facility operator in turn are required to sign the
manifest  and are forbidden to accept any wastes not accompanied by a
manifest.   On-site facilities and generators and haulers of waste
crankcase oil are exempted from these requirements.

Defining Hazardous Waste — Hazardous waste is defined as "any refuse or
discarded material or combinations of refuse or discarded materials
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Program Will Not Be Effective", January 23, 1979.

   The 3M Company operates an incinerator and landfill (temporary)
   for its own hazardous wastes in Cottage Grove, Minn.
                              370

-------
in solid, semi-solid, liquid  or gaseous  form which  cannot  be  handled  by
routine waste management techniques because they  pose a  substantial
present or  potential hazard .to human  health pr  other human organisms
because of  their chemical, biological or physical properties."1
Wastes specifically- excluded  include:

    !   o     wastewater discharge  pursuant to an  NPDES or  State  Disposal
             System permit;

       o     air contaminants or emissions pursuant- to an  Emission
             Facility Operating Permit;

       o     radioactive wastes covered  by other  regulations; and
        o
              asbestos  in taconite wastes.
 Coverage of  Permit System — An MPCA permit is required for any facility
 "used  for the  management  of-hazardous waste,"2 including transfer,
 stations and storage,  treatment and disposal facilities.  Such a permit
 is  required  to .construct  a new facility or modify an existing one,  as
..well as,,to operate an existing facility.   The only exceptions are for
 on-site facilities that are  operated solely to recycle wastes produced
 by.that generator, and for hazardous waste containerized storage  ,
 facilities with  capacities of.less than 5000 gallons, if no other
 hazardous waste  facilities are located on the same site.  Such storage
 facilities are not required  ,to have an'MPCA permit.

 AGENCY VIEWS           /'     /           ,                   .......

 MPCA officials have noted four factors which have.caused particular
 difficulties in  attempting to site hazardous waste management
 facilities.   These are:                                              ,

        o     public misperceptions of the hazards associated with
              properly sited  and operated hazardous waste management
      ,   ,, ,.  facilities,

        o  .   the difficulties' involved in developing a mechanism for
              public participation in the siting process,

        o     institutional barriers, in-particular existing zoning and
              development  plans, and

        o  ,  economies of scale — whether the state produces enough
              hazardous waste to justify a facility.
    Laws Relating to the Minnesota .Pollution Control Agency, Section
    116,06, subd. 13.

    State of Minnesota Hazardous Waste Regulations, Section HW-1,
    A. 16.     ,..'..,.         •      ,     -         .-

-------
 Reacting to these and other problems,  the MPCA has  proposed  several
 strategies  for  siting hazardous waste  management facilities, as follows:

       o     state ownership of the site and of a buffer  zone,  ,   .

       o     state preemption of local zoning  and/or use  of  eminent
              domain,

       o     financial compensation for the affected community to make
              up for disincentives such as lost property tax  revenues and
              to provide an incentive,  and

       o     a  public participation program that involves interested
              publics  in the siting process from the beginning.

 They noted  in particular that on-site  facilities have not faced such
 difficulties  and do not require such strategies.

 The MPCA recommended  then  that the federal government role in siting of
 hazardous waste management  facilities  be limited to coordinating the
 development of  regional facilities.  They felt that state governments,
 on the other  hand,  could either be directly involved in the  siting
 process—through preemptive zoning or  eminent  domain—or  could merely
 encourage the development of sites by  other parties (e.g., industry or
 regional governments).   They stressed  that an  important issue to be
 resolved in this  regard is  the issue of site ownership.

 The state should,  they felt, also be responsible for public  education
 and participation and for long-term liability  if the federal government
 is not.   They proposed that local government be involved  in  the long-
 term planning for hazardous waste management facilities as well as in
 particular  siting attempts,  but that they not have veto power over sites
 within their  jurisdiction.

 With regard to  Minnesota's  particular  situation, an MPCA  official has
 stated that the state  must  take either of two options to enable the
 future siting of  hazardous  wastes facilities.  One would  be  to permit a
 site in  the face  of local zoning and then let the local government
 concerned take  them to court (assuming  that'the MPCA would win such a
 case).   The other  is for the legislature to grant the state the power of
 eminent  domain, either for  a particular hazardous waste facility or for
 any such facility.

 The private disposal industry has been contacted by the MPCA with regard
 to siting a hazardous  waste facility in Minnesota,  but is said to have
 adopted a wait-and-see attitude.   Currently both the market and the
 political climate  are  uncertain.   The  only option now available to most
 firms which produce chemical wastes is long distance hauling to sites in
 other states.   This is  not  a viable long-term solution because of the
hazards involved, and  for economic and political reasons.
                                 372

-------
The MPCA saw no technical reason that there should not be  a site  in
Minnesota, although it was noted that there are  few if any desirable
sites close to generators in the Minneapolis-St.  Paul  metropolitan area
where the bulk of the state's industry is  located.
                               373

-------
MISSOURI DEPARTMENT OF NATURAL RESOURCES

The Missouri Department of Natural Resources (DNR) has sole regulatory
responsibility for hazardous waste management in the state.

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  21

Agency Budget:  $60,000*

Commercial HWMFs:  3 permitted facilities

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Missouri's hazardous waste law was enacted in 1977 and it called for the
adoption of all rules and regulations by September, 1979.  The .following
material is taken from the 1977 law and proposed regulations developed
as a result of that law.

Facility Inspections ~ Missouri law allows DNR representatives to
inspect facilities at reasonable times on reasonable notice for purposes
of investigation and of enforcement of rules and regulations.

Enforcement Actions — A broad range of enforcement options are defined.
These include meetings to persuade violators to correct inappropriate
actions, written abatement orders, the modification or revocation of any
DNR-issued permit and penalities up to $50,000 per day and/or  two years
in jail for repeated violations.

Monitoring — The law permits DNR to require any monitoring activities
considered necessary.  Proposed regulations require groundwater
monitoring wells for landfills and monthly analyses of samples.
Monitoring provisions are also established for incinerators and
landfarms.

Manifest System — Regulations establish a manifest system to  describe
and to track waste from generator to transporter to disposer and these
parties must retain copies for three years.  Disposers must file copies
with DNR quarterly.

Defining Hazardous Waste — State law defines hazardous waste  as that
which poses a threat to human health or other living organisms by virtue
of its quantity, concentration, or physical, chemical, or infectious
characteristics.                                ,
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23,  1979.
                              374

-------
Coverage of Permit System -— All generators, transporters, storers, and
disposers of hazardous waste are covered by state regulations and/or
permits.  Permits must be obtained for all storage, treatment, and
disposal facilities with the exception of on-site interim treatment
facilities.

AGENCY VIEWS

In recent years DNR has had experience with one successful and one
unsuccessful hazardous waste landfill siting attempt.   Both involved
substantial oppostion from area residents.  That experience has
convinced DNR officials that many facility opponents are not motivated
by a desire to guarantee safe facilities but by the desire to prevent
any facility from being developed.

A natural outgrowth of this finding is DNR's conclusion that the only
apparent solution to siting is to have a state regulatory agency willing
to issue permits in the face of political pressure and citizen
opposition which may reach strident levels.  Two additional factors are
seen as significant.  One is whether local zoning exists.  (In much of
Missouri which is suitable for developing disposal facilities no zoning
exists.)  The other is the existence of a strong state regulatory
program to enhance public confidence in governmental decision-making.
The final promulgation of Missouri's hazardous waste regulations in late
summer,, 1979, was seen as a major step in enhancing DNR's credibility.
  > \   '   •- '                   • "
In addition to issuing strong regulations state agencies should create
more publicity for proper hazardous waste management than improper
management.  A DNR official, however, did note that the media's
predilection for hazardous waste disaster stories has made it difficult
for the other side to be heard.  The use by states of special authority
to override local decision-making (e.g., zoning regulations) was seen as
a last resort option.  It was felt that such actions would be seen as an
unwarranted intervention in local government affairs and would generate
stiff opposition.

It was considered possible that localities with major industrial
development would support the development of disposal facilities .and
would be able to overcome zoning problems.  In some cases local
governments could own sites with private industry developing and
operating facilities.

DNR saw one role the federal government should play and one it should
avoid.  EPA could make a concerted effort to create favorable publicity
for proper hazardous waste management practices.  It was specifically
suggested that EPA release ten favorable press releases for every press
release describing improper practices.  The federal government, however,
should not develop any special authority whereby it became directly
involved in siting.  Such actions would delay sitings for years and lead
to major cost increases.  Opposition to siting might well increase
because of a general dislike for federal intervention in local actions.
                                375

-------
Finally, the inability of the federal government to site radioactive
disposal facilities after years of efforts was seen as dubious evidence
of the likelihood of successful federal action in the area of hazardous
waste.

-------
NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION
In New Jersey hazardous waste management is primarily the responsibility
of the Solid Waste Administration (SWA) of the New Jersey Department of
Environmental Protection.

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  71

Agency Budget:  $225,OOO1

Commercial HWMFs:  1 permitted treatment facility^

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM             '

Facility Inspections —  As of January, 1979 the New Jersey state
legislature was considering legislation that would require SWA to
inspect all special (i.e., hazardous and chemical) waste facilities on a
weekly basis.  For SWA a critical question with respect to the
legislation was whether funds would be appropriated to cover the costs
of inspections or whether it would have to allocate existing scarce
resources to cover these inspections.

Enforcement Actions—SWA has an enforcement section responsible for
inspecting facilities on a routine basis.  Criminal and/or civil actions
are possible.  Civil actions may be carried out at three levels.  In
order of increasing severity they are notice of violation (the most
routine action), notice of prosecution (this may include levying of
fines), and administrative order for appropriate action (including the
option of closing facilities).  Actions may begin at any level and may
progress from lower to higher levels of severity.

Monitoring — State regulations cover monitoring in two areas.
Provisions for monitoring ground and surface water must be established
at special waste facilities prior to the beginning of operations and the
acceptance of wastes.  Analyses of monitoring must be submitted to SWA
as determined by SWA.  Based on gas generation potentials•of accepted
wastes, SWA may require the implementation of a gas monitoring '
program.                                         '••        ' ,
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23,  1979. ' ":

   SWA has granted permits for six on-site hazardous waste
   facilities.

   Proposed new rules and amendments concerning the operation,
   registration and engineering plan requirements for special waste
   (chemical and chemical waste) facilities.  These proposed regulations
   were expected to be adopted by late spring 1979.
                               377

-------
Manifest System — The Special Waste Manifest Regulations provide for a
manifest system covering the transport of special wastes and include
requirements for facilities to maintain records and provide reports 
-------
a'rrive at sound, independent conclusions on the viability of specific
sites.   (Currently, SWA's lack of resources compel the agency to rely
primarily on industry-generated data.)                            •

Various  dispute resolution techniques were seen as having limited
impacts  on siting.  Based on recent state experience, industry offers of
compensation and/or amenities to host communities were not seen as being
effective inducements.  Negotiation or other methods of reaching
compromise between host communities and facility sponsors would likely
not have any impact on siting because, from a local perspective,
facilities would not be seen as inevitable.  Siting opponents would not
•feel compelled to compromise so long as their major goal was not to have
the facility developed.

Finally  SWA saw a major long-term trend towards fewer commercial
disposers.  Because the costs of securing sites and operating facilities
will inexorably rise, small firms with little capital will drop out of
the market.  An SWA official speculated that in ten years' time, only a
half dozen large companies will be operating hazardous waste facilities
on a national basis.                                             ,
                               379

-------
NEW YORK DEPARTMENT OF ENVIRONMENTAL CONSERVATION

In New York state, authority for regulating hazardous waste management
activities rests with the Department of Environmental Conservation
(DEC).

AGENCY CAPACITIES AND COMMERCIAL HWMFs

Staff Positions:  71                                          ;

Agency Budget:  $140,000*

Commercial HWMFs:  3 permitted facilities^

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — The responsibility for inspecting HWMFs  may be
delegated by DEC to county health departments if those departments can
demonstrate the requisite expertise.  All three HWMFs permitted1 by DEC
are in Niagara County and the Niagara County Health Department has
assumed the primary responsibility for inspections, which are conducted
as frequently as once a week.

Enforcement Actions — DEC uses consent decrees as the primary means of
enforcing state regulation and individual permit conditions.  In
practice the Niagara County Health Department documents violations and
forwards this documentation to DEC.  Violations may result in fines.  In
extreme cases DEC may close a facility by issuing a summary abatement
order.

Monitoring — For landfills state regulations require a minimum of three
monitoring wells, two of which must be downgradient from fill areas.
More wells may be required if deemed necessary by DEC.  The permit for
the facility will specify the testing and frequency schedules of the
water monitoring program.  Secure landfils must also monitor leachate
collection and treatment systems.

Manifest System — State law has established a manifest system for the
transportation, storage, and disposal of hazardous wastes; this system
conforms to RCRA requirements.

Defining Hazardous Waste — State law defines industrial hazardous
wastes as those that contribute to irreversible or incapacitating
illness or
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23, 1979.

   One facility provides treatment and processing; the others
   provide land disposal and some treatment and processing.
                               380

-------
that pose a substantial hazard to human health or the environment.
Waste is also defined by criteria derived from RCRA regulations.

Coverage of Permit System —Permits must be obtained for any facility
that stores, treats, processes, incinerates,-or land disposes of
hazardous waste.  Regulations apply to generators, transporters, and
disposers of such waste.

AGENCY VIEWS

Public opposition has arisen to the two HWMFs in New York which use land
disposal technology.  Given this experience, DEC considers public
opposition to be one of the major problems in developing and maintaining
disposal facilities.  Two manifestations of this opposition—citizen
lawsuits resulting in court injunctions and restrictive local laws—were
specifically noted.

Overcoming this opposition to the extent of achieving local public
acceptance of facilities may be impossible.  Two approaches, however,
can contribute to reducing opposition.  Public education was considered
helpful but by no means a panacea.  Probably more important were
concerted efforts to upgrade disposal technologies to reduce the need
for land disposal.  Specifically, technologies_which destroy the
hazardous components of waste must be developed.  Recent European
experience with such facilities was cited as a model for the U.S.

The Niagara Falls area of New York has received enormous publicity
because of Love Canal and other disposal sites.   This publicity has
stimulated a great deal of government.action which has helped to upgrade
New York's hazardous waste program.  (A DEC official described that
program as the least mature of the state's environmental programs.)  The
recent interest in disposal problems plus the current problems     •'....
associated with developing facilities may lead to a need for direct
government involvement.  Thus it was considered possible that states may
have to site and construct disposal facilities and use general funds
and/or user fees to defray costs.  Finally, EPA musf insure that
hazardous waste management be a national program.  For the program to be
effective, no state can become a haven for the disposal of hazardous
wastes.                    ,     •   .                           \. ,.,  '
                                 381

-------
OKLAHOMA STATE DEPARTMENT OF HEALTH

Primary responsibility for the regulation of hazardous waste management
in Oklahoma rests with the state Department of Health (ODH).  The
regulations covering hazardous waste management (Rules and Regulations
for Industrial Waste Management) have recently been modified.  These
modified regulations took effect on June 12, 1979.  The discussion below
refers to these revised regulations.    *       ';"     '  -,      7;   ;

AGENCY CAPACITIES AND COMMERCIAL HWMFs   '        \

Staff Positions:  21

Agency Budget:  $80,0001

Commercial HWMFs:.  3 permitted facilities

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM

Facility Inspections — Inspection per se is not- mentioned in ODH
hazardous waste regulations.  However, Oklahoma case law has determined
that when a person applies for a permit and/or receives a license or
permit he has waived the right to a search warrant.  On this basis the
ODH conducts periodic inspections of hazardous waste facilities (with
the exception of storage facilities:  see below).

Enforcement Actions — Enforcement of ODH regulation is carried out by
the state Attorney General or by county district attorneys with the
assistance of ODH attorneys.  Sanctions include injunctive action,
permit revocation or suspension and civil or criminal penalties.   Civil
penalties range up to $2,500 per violation per day, and criminal
penalties up to 30 days in jail per violation per day.

Monitoring — State regulations provide for monitoring of ground and
surface waters and, in certain cases (e.g., incineration or disposal of
volatile hydrocarbons), air monitoring.

Manifest System — The regulations require that every shipment of
hazardous waste must be accompanied by a manifest which specifies the
generator, hauler and disposal plan, and "information regarding
emergency procedures to be used in the event of spillage, leakage, or
accident."2

Defining Hazardous Waste — In these regulations hazardous waste is
termed "controlled industrial wastes," and is defined as solid or
   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23, 1979.

   Rules and Regulations for Industrial Waste Management, Section
   11.3.1.2.
                                382

-------
liquid refuse products which are to be discarded by the producer and
which are toxic to humans, animals or plants and which are produced in
such quantities that they cannot be safely disposed of in state-approved
sanitary landfills, or in waste or sewage treatment facilities.  This
does not include radioactive wastes.  In addition, state law excludes
oil and gas,brines and drilling muds from ODH purview.

Coverage of Permit System — The permit system covers all hazardous
waste processing, treatment and disposal facilities, with the exception,
as implied above, of oil and gas field operations.  Permits are not
required for storage facilities, which do, however, require ODH
approval.  The latter differs from a permit in that it is not subject to
a public hearing and does not have insurance and bonding requirements.

AGENCY VIEWS                              .             ,.  ' "        '

The ODH has in the past few years sucessfully sited a hazardous waste
landfill and a few injection wells.  Such siting attempts have only
recently begun to face public opposition, and this opposition has been
successful only in those cases where the proposed site was not
technically suitable. „,. Although the. ODH does think that ,it is possible
that public opposition may become more of a problem in the future,
currently they feel that site selection can be left to industry.  They
do propose that some sort of general public education program be
developed to alleviate "unfounded" fears about hazardous waste
management facilities.  Another problem they are aware of but do not yet
have a solution to is the effect of such sites on surrounding property
values, .particularly in non—industrial areas.

In summary, the ODH position is that proposed solutions to the siting
problem such as eminent.domain or even government-owned and operated
sites are not yet necessary because the private sector is doing an
adequate job at this time.

-------
TEXAS DEPARTMENT OF WATER RESOURCES           ......

The Texas Department of Water Resources (DWR), formerly called the Texas
Water Quality Board, has principal responsibility for the regulation of
hazardous waste management in Texas.  The Texas Department of Health
(DOH) has jurisdiction over municipal solid waste disposal sites which
currently accept some low-level hazardous wastes.  However, the DOH is
of the opinion that EPA1 s proposed new regulations will preclude these
sites from accepting any hazardous wastes.  The disposal of drilling
muds and brine wastes from oilfield operations is regulated by the Texas
Railroad Commission.

AGENCY CAPACITIES AND COMMERCIAL HWMFs                ,

Staff Positions:  32.51

Agency Budget:  $753,1221

Commercial HWMFs:  25 (including 3 permitted hazardous waste landfills).

SELECTED ASPECTS OF STATE HAZARDOUS WASTE PROGRAM . .

Facility Inspections — The DWR has the authority to inspect all
permitted hazardous waste management facilities, as is specified in
their permits.  Inspections are conducted out of the 12 DWR regional
offices to ensure that these facilities are being operated in accordance
with their permits.

Enforcement — "The Executive Director is authorized to institute or
cause to be instituted  [by the state Attorney General's office]...legal
proceedings for injunctive relief or to recover a civil penalty [or
both]...".2   Injunctive relief might mean site closure or merely
future adherence to the regulation violated.  The civil penalty can
range from $50 to $1,000 per day per violation.          .

Monitoring — Permit stipulations require that each facility monitor
groundwater.  Monitoring data—usually less than 10 parameters—are
required to be submitted monthly the first year of the permit and
quarterly thereafter.   Air quality is under the jurisdiction of the
Texas Air Control Board, which, however, does not require gas monitoring
programs.                                                       t

Manifest — A "Shipping Control Ticket" must accompany all shipments of
Class I industrial waste being hauled to off-site facilities.  Neither
    Source:   U.S.  General Accounting Office,  "Hazardous Waste
    Management  Programs  Will Not  Be Effective," January 23, 1979.

    Texas  Department  of  Water  Resources, Rules of  the Texas Water
    Development Board Pertaining  to Industrial Solid Waste Management,
    156.22.01.011.
                                384

-------
haulers nor management facility operators are allowed to receive any
Class I waste without this ticket.             , ;

Defining Hazardous Wastes— "Hazardous Industrial Waste" is defined as
any waste or combination defined as such by the EPA.  However, some
sections of the DWR regulations do not make use of this term and refer
instead to Class I wastes.  Class I wastes are defined as "any
industrial solid waste" or mixture of industrial solid wastes which
because of its concentration, or physical or chemical characteristics,
is toxic, corrosive, flammable, a strong sensitizer or irritant, a
generator of sudden pressure by decomposition, heat or other means, and
may pose a substantial present or potential danger to human health or
the environment when improperly treated, stored, transported or disposed
of or otherwise managed, including hazardous industrial waste."I
Specifically excluded are wastes which result from oilfield operations
and material in sewage and irrigation return flows.

Coverage of Permit System — All hazardous waste management         •
facilities—storage, treatment, processing and disposal—are required to
have a permit to operate.  However, such a permit may be obtained,
depending on the type of facility, from the DOH or other state agency.

AGENCY VIEWS2                                       	

Texas DOH officials view political .and public opposition to the siting
of hazardous waste management facilities as an insurmountable problem.
Many Texas public officials have informed DOH that they are unwilling to
subject their communities to public hearings involved in the issuance of
permits and that they are certainly unwilling to advocate facilities.
Indeed, these officials have told DOH that such advocacy would be
tantamount to political suicide and they would actively resist siting
attempts.

DOH feels that public opposition is associated automatically with any
hazardous waste.  Because current EPA regulations do not distinguish
between degree of hazard, DOH feels that EPA has magnified the public
opposition problem and foreclosed the opportunity to dispose of less
hazardous'• wastes in ways that would not engender public concern.
Specifically, DOH feels that through the application of sound scientific
and engineering principles, existing solid waste disposal sites can
provide capacity for a large portion of hazardous  waste that is
hazardous only if improperly handled.
   Texas Department of Water Resources, op. cit. ,  156.22. .01 (c).

   These views are derived primarily from communications between the
   Director, Division of Solid Waste Management,  Texas  Department of
   Health and U.S. EPA.  Views of the Department of Water Resources,
   also communicated to U.S.  EPA were not available to  Centaur in time
   to be included here.
                              385

-------
In DOH's view, by demanding that every hazardous waste disposal  facility
be engineered to stringent standards designed for the most  hazardous
waste, many sites will be overengineered and disposal costs will be
unnecessarily high.  In turn, this will lead to more illegal disposal
practices.                                                   ,
                               386

-------
 WASHINGTON DEPARTMENT'" OF ECOLOGY                                    :

 The agency in the state of Washington with the principal responsibility
 for regulating hazardous waste management is the State Department of
 Ecology (WDOE).  The Washington Department of Agriculture has authority
 over matters  involving  pesticides,  including inspection of disposal
 areas and investigation of complaints of injury to' humans or to land.
 The Washington Utilities and Transportation Commission regulates garbage
 and refuse collection companies,  and the Washington State Patrol
 regulates the transport of dangerous materials over state highways.1

 AGENCY CAPACITIES AND COMMERCIAL  HWMFs

 Staff Positions:   42

 Agency Budget:   $100,OOO2

 Commercial HWMFs:   None

 SELECTED,ASPECTS  OF STATE HAZARDOUS  WASTE PROGRAM

 The WDOE  currently has  only limited  authority to  regulate hazardous
 waste management.   They have proposed legislation which would give  them
 much broader  authority  and would  bring them into  compliance  with
 EPA/RCRA  requirements.   However,  this legislation is not expected to be
 enacted until 1981 at the earliest.

 Currently,  the  WDOE only regulates the transportation,  storage and
 disposal  of extremely hazardous wastes.   Extremely  hazardous  wastes are
 those  wastes  which are  acutely toxic  or which are persistent  and
 represent a long-term hazard (and are a subset of hazardous  wastes).
 The WDOE  has  the authority to force a generator to  dispose of extremely
 hazardous  wastes  in an  approved facility, and as of this  summer will
 implement  a manifest, system for all extremely  hazardous wastes.
 Otherwise,  even their authority over  extremely hazardous  wastes  is
 limited to  their soon-to-be  operational, extremely hazardous waste
 disposal  site on  the Hanford Reservation.   At  this  facility, which WDOE
 will own  but which  will  be  privately  operated, they will  regulate the
 methods of  treatment, storage and disposal.

 AGENCY VIEWS

WDOE comments on the siting  process,  hazardous waste management, and the
EPA role can be found in the Appendix to the Resource Recovery
   U.S. EPA, State of Hazardous Waste Regulations and Legislation.

   Source:  U.S. General Accounting Office, "Hazardous Waste
   Management Programs Will Not Be Effective", January 23, 1979.
                                 387

-------
Corporation case study, "A History of Efforts to Acquire a Hazardous
Waste Site in the State of Washington."  Briefly, these comments
indicate that WDOE feels the following are major aspects to be
considered in siting hazardous waste facilities:

       o     the need for state laws and regulations to detail and
             authorize the siting implementation system,

       o     the involvement of local elected officials,

       o     the hiring of appropriate staff, and

       o     the involvement of the local community in a way that does
             not necessarily lead to its being opposed to the facility;
             this might include intelligent publicity and financial
             incentives.
                                                               yo  1869
                                                               SW-809
{tU.S. GOVERNMENT PRINTING OFFICE: 1979-632-755/232

-------
                          EPA REGIONS
U.S. EPA, Region 1
Solid Waste Program
John F. Kennedy Bldg.
Boston, MA 02203
617-223-5775

U.S. EPA, Region 2
Solid Waste Section
26 Federal Plaza
New York, NY 10007
212-264-0503

U.S. EPA, Region 3
Solid Waste Program
6th and Walnut Sts.
Philadelphia, PA 19106
215-597-9377

U.S. EPA, Region 4
Solid Waste Program
345 Courtland St., N.E.
Altanta, GA 30308
404-881-3016
U.S. EPA, Region 5
Solid Waste Program
230 South Dearborn St.
Chicago, IL 60604
312-353-2197

U.S. EPA, Region 6
Solid Waste Section
1201 Elm St.
Dallas, TX 75270
214-767-2734

U.S. EPA, Region 7
Solid Waste Section
1735 Baltimore Ave.
Kansas City, MO 64108
816-374-3307
U.S. EPA, Region 8
Solid Waste Section
1860 Lincoln St.
Denver, CO 80295
303-837-2221

U.S. EPA, Region 9
Solid Waste Program
215 Fremont St.
San Francisco, CA 94105
415-556-4606

U.S. EPA, Region 10
Solid Waste Program
1200 6th Ave.
Seattle, WA 98101
206-442-1260

-------
•4
 •
     x:
I
         B
         \r

-------