Of I*-000 Jฃ3
            DRAFT    GUIDANCE
    STANDARDS APPLICABLE TO OWNERS AND OPERATORS
OF HAZARDOUS WASTE TREATMENT,  STORAGE, AND DISPOSAL
  FACILITIES UNDER RCRA, SUBTITLE C, SECTION 3004
  Financial Requirements;  Interim Status Standards
              (40 CFR 265, Subpart H)
This report (SW-913) was prepared under contract no.
      68-01-5794 for the Office of Solid Waste
        U.S. ENVIRONMENTAL PROTECTION AGENCY
                        1981

-------
-if   •,!
    :1  ,'*

-------
                          i       PREFACE
                          I

     This draft guidance document has been prepared by the International
Research and Technology Corporation.  In preparing this document, we
have sought and incorporated the advice of the Office of Solid Waste,
Environmental Protection Agency (EPA).  The Regional Offices, the Office
of General Counsel, and the Office of Enforcement have not yet reviewed
this draft guidance document; therefore, this document does not repre-
sent EPA's final views and opinions.


-------

-------
LIST OF TABLES.
                                     CONTENTS
                                                                     .v
1.0   INTRODUCTION	.	,	1-1

2.0   BASIC RULES FOR THE  CLOSURE COST ESTIMATE....... ......... .....ป„.. .2-1

3. 0   BASIC RULES FOR THE  POST-CLOSURE COST ESTIMATE	.3-1

4.0   PREPARING AND DOCUMENTING THE CLOSURE AND POST-
        CLOSURE COST ESTIMATES.	4-1

      4.1   Costs Based upan Experience of the Owner or
              Operator.	4-1
      4.2   Contractor Estimates	......4-2
      4.3   Cost Estimating Handbooks	4-3
      4.4   Workups from Labor, Material and Equipment
              Requirements.	4-4

5.0   ADEQUACY OF THE CLOSURE COST ESTIMATE	5-1

      5.1   Activities Relevant to All Facilities	5-4
            5.1.1   Treating, Disposing or Removing Inventory	5-4
            5.1.2   Decontaminating the Facility	5-6
            5.1.3   Monitoring	5-6
            5.1.4   Prof esisional Engineer Certification	5-6
      5.2   Costs Required Only of Landfills and Surface
              Impoundments.	 5—7
            5.2.1   Cover.,.	5-7
            5.2.2   Vegetation.	ซ	5-8
            5.2.3   Optional Measures	.....5-9

6. 0   ADEQUACY OF THE POST-CLOSURE COST ESTIMATE	6-1

      6.1   Inspections and Facility Visits	6-3
      6.2   Reestablishing Cover and Vegetation	6-5
      6.3   Fertilizing... ,i	6-5
      6.4   Mowing	„	.	6-5
      6.5   Ground-water Monitoring	;.....	6-6
      6.6   Maintaining and Replacing Fences	6-6
      6.7   Collecting, Removing and Treating Leachate.	....6-6

7.0   REVISING THE CLOSURE AND POST-CLOSURE COST ESTIMATES	....7-1
                                  iii

-------
8.0   ADJUSTING THE COST ESTIMATES TO ACCOUNT FOR INFLATION.	8-1

9.0   SAMPLE COST ESTIMATES	9-1
      9.1   Introduction.	• • •	
      9.2   Example - Surface Impoundments	•	
      9.3   Example - Land Treatment Facilities,	ซ
      9.4   Example - Landfills	ซ	•	
      9.5   Example- Incinerators	......	•	<
      9.6   Example - Multiple Process Facility With Tanks
                      and Surface Impoundments.ป	9-91
      9.7   Example- Post-Closure Cost Estimates...	9-114
.9-1
,9-2
.9-31
.9-56
.9-75
                                                                             1
                                                                            :v	ฅ
                                   iv

-------
                                                                                   I
                             LIST OF TABLES

Table                                                        ,      Page

5-1   CLOSURE COST ESTIMATE RAPID CHECKS.	5-3

6-1   COSTS OF SELECTED POST-CLOSURE ACTIVITIES.	 6-4

8-1   HYPOTHETICAL SAMPLE PAGE OF SURVEY OF CURRENT
        BUSINESS	 8-3


-------

-------
                           1.0  INTRODUCTION

     EPA has developed standards for financial requirements for owners
or operators of hazardous waste facilities as part of the Interim Status
Standards — Subpart H Financial Requirements.  This guidance document
covers only those portions of Subpart H promulgated on 19 May 1980 and
the technical amendments to those regulations.  These portions require
the owner or operator to prepare cost estimates for closure and post-
closure .  At later dates, Subpart H will also contain final regulations
covering liability requirements and financial assurance mechanisms.

     The purpose of the  cost estimation requirements is to determine
the amount of financial  assurance needed.  These requirements are pre-
sented in 40 CFR ง265.142 for closure and 40 CFR ง265.144 for post-
closure.  Each of these  sections contains a requirement for a written
cost estimate available  on  the premises (40 CFR ง265.142(a) and 40 CFR
ง265.144(a)), a requirement for revisions in the cost estimate whenever
changes are made in the  applicable plans  (40 CFR ง265.142(b) and 40
CFR  ง265.144(b)) and a requirement for annual adjustments in the closure
and post-closure cost estimates to reflect inflation (40  CFR ง265.142(c)
and 40 CFR  ง265.144(c)) . All owners or operators of hazardous waste
facilities, except those facilities owned or operated by  states and the
federal government, must prepare closure cost estimates.  All owners or
operators of  facilities  in  which hazardous wastes will remain after
closure, except  those facilities owned or operated by states and the
federal  government, must prepare a post-closure cost estimate.  The
closure  cost  estimates must be  available  on  the premises  on the effective
date of  these regulations,  i.e., November 19, 1980, for those facilities
not  required to  have  a post-closure plan.  Owners or operators of  land
disposal facilities,  or  facilities closed as  such, will not be required
 to have their closure and post-closure cost  estimates  available  until
 six months from the effective date of these  regulations,  i.e., Hay 19,
 1981, because of the complexities  involved  in developing  plans and
 estimates for these types of facilities.
                                    1-1

-------
     The purpose of this document  is  to assist the Regional Offices in
implementing those sections of  the interim status regulations relevant
to closure and post-closure cost estimates.  Since the bases for the
cost estimates are the closure  and post-closure plans, this section
        • 	i	  .MI     :   •:' '•'•'.     :    .  	  .•. •.  ' ••.„  &••  •• , !.•; .I/.     ..<  .    „
should be read in association with the guidance for closure and post-
closure plans.  The remainder of this document is divided into eight
sections:  basic rules for the  'closure cost estimate;  basic rules for
                                                         111 I "   r
the post-closure cost estimate; preparing and documenting the closure
and post-closure cost estimates; adequacy of the closure cost estimate;
  ' / ' -   .. • , .(	I   '!'', .           '        . , '  .      '•  I;,,, -•'  •'!  • I'-';-  "  *  I " _  j
adequacy of the post-closure cost  estimate; revising the closure and
post-closure cost estimates; adjusting the cost estimates to account
for inflation; and sample cost  estimates for various types of facilities,
The emphasis throughout this document is upon interim status.   This is
particularly important to the sections on adequacy of  cost estimates,
which are designed for rapid review and inspection.
      Sample  cost estimates have been developed for several kinds of
 facilities in  the final  section of this document.  The purpose of these
  !ป         t:i! (,,"           '               :"  ' •'         .'' •' '  ! ' "
 samples  is to  illustrate the concepts involved in closure and post-
 closure  cost estimates and the formats which might be appropriate.  The
 samples  are  developed through a series of worksheets designed to illus-
 trate an appropriate format for demonstrating the scope and nature of
 the activities involved  and the key unit cost elements used in arriving
 at  the final estimate.   Closure and post-closure costs will be highly
 site-specific,  and as a  result, these worksheets should be viewed as
 only general guidance and are unlikely to be applicable in any specific
 case. In no case should the unit costs used in the samples be regarded
 as  proper and  accurate costs to be used in developing cost estimates.
                                   1-2
                                                         , i'li'ji	il-'l.

-------
             2.0  BASIC RULES FOR THE CLOSURE COST ESTIMATE

     In developing closure cost estimates for interim status, the
following concepts should be used for guidance.

2.1  The closure cost estimate is based upon the methods described
     in the closure plan.
                           I   ,           -            :        •
     A cost estimate should, be prepared for each activity or sub-activity
listed in the closure plan.  The cost estimate is based upon the ac-
tivities, quantities and methods indicated in the closure plan.  For
example, a cost estimate should be prepared for treating, disposing or
removing inventory.  It must account for managing the maximum inventory
expected as indicated in the closure plan.  The method used for treating,
disposing or removing the inventory would be identical to that indicated
in the closure plan.  For example, if the closure plan indicates managing
1000 tons of waste, of which 800 tons are to be disposed or treated
on-site and 200 tons removed to an off-site TSDF, the cost estimate
must include estimates for these respective costs.

2.2  "The estimate must equal the cost of closure at the point in the
     facility's operating life when the extent and manner of its opera-
     tion would make closure the most expensive, as indicated by its
     closure plan."*      .            -

     The goal of the cost estimate is to ensure that if at any point in
time a facility had to begin closure for reasons unrelated to a catas-
trophe at the site, the costs of the closure would not exceed the cost
estimate.  Thus, the conditions on which the cost estimate is predicated
will probably differ significantly from anticipated conditions at the end
of normal facility life with respect to amounts of undisposed or un-
treated wastes on-hand, status of processing equipment,  and area of-the
facility in disturbed condition.
*EPA Interim Status Standards, 40 CFR ง265.142(a).
                           i                      - -
                                   2-1

-------
     For example, for purposes  of the cost estimate, the estimate of
maximum inventory on-site  should include the maximum normally expected
  f;"'"' '•  .  '  •,••'  ').[   ':     '   '     •' ••      •     .'•,.,  •	".'• '-, ;  I  • |'' ' • • '•
bn^site.  This estimate  should  take account of any long-term cycle of
inventory on-hand, and should take account of predictable events which
may occur over the life  of the  facility, such as adverse weather condi-
  I1"  .     ":     , ,i |           " n'     '  . ; ,11, ,   •    | ' * ,  " ' „  "I'ii \' • ,   '" ! i"  ! "  . '.'''
tions preventing normal  activity at a landfill and "down time" to
periodically rebrick the refractory of an incinerator.  The initial
estimate need not, however,  include provisions for highly unusual
contingencies unless they  exist at the time the facility submits its
initial cost estimate.   For  example,  the cost estimate need not include
provision for  such unusual contingencies as the effects of the 50-year
storm or the failure of  a  liner in a major trench calling for removal of
  '":'.  '.    ] ::, 'i./ '-".i i    ...'••  •  •   "  ,      .  ., i;  '  -if  'i: ,   i•<  i •• •  -,  •.;  •
all waste in that  trench.   If  such events occur over the life of the
            	            „       ,          „,„,,,!
facility and cause the original maximum inventory estimate to be
exceeded, the  owner or operator should revise the closure plan to
  ffi;: ,i;' ,' ;  i' I;;  ;;"ti    „ " :  ••' ", " ',    , ; •   ;;  ..;.''• .;'•.	,'•., v"', ,,'|.,<.  | ; '.'  :  ;..,•'
reflect the current situation unless he can immediately correct the
situation so that his original  estimate of maximum inventory  is not
exceeded.  In  cases of doubt,  the Regional Administrator's office should
be contacted as  to  the advisability of revising the cost estimate.  In
no case, however,  should the initial cost estimate list a maximum inven-
                                                            r
tory less than that actually on-site.  If normal operating  procedures
include steps  which would  reduce closure costs, such as dredging of an
impoundment or capping portions of a landfill, it should be assumed that
closure will occur just  before  these, activities.   Thus,  in  the closure
cost estimate  all  costs  associated with such procedures should be
included.  This  assumption is  to ensure adequate funds  in the closure
cost estimate  for  the situation of forced closure due to an unforeseen
                                                           .1
event such as  business  failure of the facility's owner  or operator.
     If  experience shows that the initial cost estimate over-  or  under-
 estimated the most' expensive conditions likely to occur  over  the life
 of the  facility,  or if those conditions are no longer possible,,  then
 revisions may be made in the cost estimate as appropriate  (see Section
  ?..'•    :,•	';  , .11.;   " , -          '     ,        • :,  , 	  s • s ";  '•  i ,j• • ••)•'!••'-'  '.
 7.0).   For example, if late in the life of the facility  the total
                                    2-2

-------
disturbed area is only 10 acres but had  exceeded 20 acres  earlier,  it
would be appropriate to revise the cost  estimate downward.

2.3  Cost estimates are to be based upon the  operating  costs  to  the
     owner or operator of carrying out the  planned  activities.
                           i                              "',.""
     This means that in developing the cost estimate the owner's  or
operator's depreciation costs, capital recovery  factors, and  interest on
debt need not be included as part of the costs.   For example, capital
recovery and depreciation factors for earth-moving  equipment  owned  by
the owner or operator and costs of land  already  owned need not be
considered as part of the costs of disposing  of  inventory  at  a landfill.
If equipment must be rented to complete  closure  activities, however,  the
costs of this rental must be .part of the cost estimate.  If the  owner or
operator plans to contract' out a specific activity  (e.g.,  sandblasting
and steam-cleaning the equipment pn-site, planting  vegetation),  the full
costs of that contract would be the correct cost  estimate.

2.4  The cost estimates .should include all  associated costs necessary to
     carry out closure procedures.

     A cost estimate for a given activity must include  all costs  asso-
ciated with this activity, Including fully  loaded labor costs (i.e.,
including fringe benefits and overhead),  any  costs  of supervision, .fuel
and maintenance costs for the equipment  used,  administrative costs, and
provisions for normal contingencies.  Administrative costs include  all
costs associated  with taxes and insurance, as well  as costs of routine
administration,  paperwork and reporting.   "Provisions for normal  contin-
gencies" means that the cost estimates should include a factor for
unforeseen events that may increase costs,  such as those routinely  put
into most initial cost estimates.   Such contingencies include adverse
weather and other unanticipated complications.  Given the absence in  the
closure plan of  detailed engineering designs, the uncertain nature of
precise facility conditions at the time of  closure,  and the lack  of
provision for inflation during the closure  period (which, in some cases,
can be quite lengthy), the provision for contingencies should be

                                   2-3

-------
  ป-, . , ,     ' i, I!"1*":  ,., ! •  .   „' ,'< • ' ,  I;   	! ', •  . '.   •  ' 	 •	•  . " • .K'j	., • I
generous.  Standard  engineering practice  shows  that  in most cases
a provision for contingencies  could reasonably  be expected to fall
within the range of  15  to 25 percent.   The lower  end of the range
is appropriate for smaller facilities  which  require  a short closure
period and have fewer uncertain variables.   The higher end of the
raSige accounts''for larger facilities which may  require extensive
  ,. ,   •	,   -                 .   ..  	;   ,.	   ;;;,	 ;„ ..[   ,' ..;	
activities and a longer closure period, for  which unusual weather
conditions or uncertain decontamination needs could  seriously affect
the cost of closure.

    A cost estimate  for treating  inventory in an  incinerator would
include fully loaded labor costs,  supervision,  maintenance,  utilities,
any chemicals and catalysts employed,  administration, andprovisions
for contingencies.   Although  the  cost  estimate  should include all of
these cost Clements, they need not be  documented  separately.  Thus, for
example, well documented unit  costs for treating  inventory are
appropriate even if  they do not include separate  documentation for
maintenance, utilities, or all energy  costs. This point is further
discussed in Section 4.0 and  examples  of  an  appropriate approach
arฐe shown in Section 9.0.

2.5 The cost estimates  should  be  based upon  costs in the year in which
    the estimate is  prepared;  there is no need  to provide for inflation
    in developing the  cost estimate, as this will be provided for in
    the adjustment procedure.

  :,•         •,,::..'     ,    ,  . .  '    „      ,   -,   .  ,   ;	     i,      .  ",  • .
    Costs should be  based upon current costs.   For practical purposes,
this means costs within one year  of the time of preparation of the cost
estimate.  There is  no  need to adjust  data or cost estimates based
          „ "'"';'  ', ,,!|	 	'   ,„;  •'     '"  „  ,„, „  " ,„,     ,,	 „  '  ,!„,   t - '  „ ! ' , ,1   ,;,,',',,
upon data within the current year to the  exact  month for which the
cost estimate  is dated.
                                    2-4

-------
          3.0  BASIC RULES FOR THE POST-CLOSURE COST ESTIMATE

     In developing a post-closure cost estimate for interim status, the
following concepts should be used for guidance.
                           j.        -     .
3.1  A post-closure cost estimate must be prepared for all facilities
     at which hazardous wastes remain on-site after closure.

     Post-closure cost estimates are required for landfills and surface
impoundments and land treatment systems at which any hazardous wastes
remain on-site following final closure.  If an owner or operator of
a surface impoundment originally plans to close it as a storage or
treatment facility ay removing all hazardous waste, hut later decides to
close it as a disposal facility, he must immediately prepare a post-closure
plan for the facility.  In similar fashion, if the -owner or operator of a
land treatment facility originally prepares a closure plan based on the
assumption that treatment will render the waste non-hazardous but tests
show this is not the case, he must immediately prepare a post-closure
plan and cost estimate.

3.2  The post-closure cost estimate is based upon the methods described
     in the post-closure plan.

     The post-closure cost estimate is based upon the activities, quan-
tities, and methods indicated in the post-closure plan.  A cost estimate
should be prepared for each activity or sub-activity listed in the post-
closure plan.  For example, a cost estimate should be prepared to cover
maintenance activities.  It must reflect the methods to be used in the
post-closure plan and the rates of fertilization, mowing, sprinkling,
and other-activities listed, in the post-closure plan.

3.3  The post-closure cost estimate should be prepared for the entire
     area expected to conta,in' hazardous waste at the time of final
     closure.
                                   3-1

-------
     The post-closure estimate should  provide for post-closure care for
   f't1'"- "   '  • ••  ",!•!  -         ••     .    ,'•    '    -   :  ' , v. •  ; H .:);>.'"     	
the entire facility as it is expected  to  exist  at the  time  of final
closure.  Thus, if a ISO-acre facility is expected to  be filled at a
             '!•:',  • I            ,             ii,,.;       ,„,   ,ii  •   i ;i,iiiniiil || „ i,   ,  ' IM
rate of 10 acres per year,  the initial post-closure cost estimate must
                                                              ii
reflect the costs of post-closure  care  for the full 180 acres.
                                                              i
3.4  The post-closure cost estimate  should reflect the costs of
     purchasing all necessary labor, materials and equipment to carry
     out post-closure requirements.  Unlike the closure cost estimate,
     it may riot be assumed that  the  owner or operator already has
     adequate equipment for  the  purpose.
             I,   . i    '     .  •   •    .•       	, ,,, ..    :  . j •  ,     ) .
     It is highly uncertain  whether  the entire period of post-closure
care 'will be carried out by  the  owner  or operator himself, and whether
   '!"ป'        ••'.'•  ;"   '       '.•          •••.:•      •.,••'•,'.•' ':••-.   ']'  i '- ..•..•;• ••:
on-site labor and equipment  will be  available.  Therefore, the cost esti-
mate should assume that all  services required for post-closure must be
contracted for in order to ensure  financial adequacy.  The post-closure
cost estimate must therefore include adequate allowance for profits on
the post-closurecare services.  For example, if regular mowing is part
   jiH?  ,  •  .  ,;'!;!  r. "f .; i  i';  • •••„• •
of the post-closure plan, the costs  must reflect the costs of hiring a
service to carry out this mowing,  rather than the cost of having a laborer
of the owner or operator using mowing  equipment already in use elsewhere
by the owner or operator.  Similarly,  monitoring costs must be estimated
assuming it is necessary to  hire outside help both to take the necessary
samples and to conduct the necessary laboratory tests.

3.5  The post-closure cost estimate  must be complete and include all
     associated costs necessary  to carry out post-closure procedures.
                                                            •  i
     A cost estimate for a given activity must include all costs asso-
ciated with thisactivity, including fully loaded labor costs, any costs
of supervision, fuel and maintenance costs for equipment used, adminis-
             1 'i  :"    •   "  "  '          "'   '   "  ':  '   ,' ' ' "I'1'1:, -  ; ;  | •,   ; .
trative costs, and provisions for  normal contingencies.  Administrative
   "'          in '''  • ',     ,   '','!'   '                  !' "',',' *", H '  ' I'1!  l|   ' '   "    '
cosiis include all costs associated with taxes and insurance, as well
as costs of routine administration,  paperwork and reporting.   "Provisions
                                     3-2

-------
for normal contingencies" means  that  the cost estimates should include a
factor for unforeseen events  that may increase costs, such as those
routinely put into most initial cost  estimates.  Such contingencies
include adverse weather and other unanticipated complications.  Given
the absence in the post-closure plan  of detailed engineering designs,
the uncertain nature of precise facility conditions at the time of post-
closure, and the uncertainty of the kinds of maintenance to be required
during the post-closure period, the provision for contingencies should
be generous.  Standard engineering practice shows that.the provision
for contingencies could reasonably be expected to fall within the
range of 13 to 25 percent.  As with closure costs, the documentation
for the cost estimate need not break  out all of these headings
separately; they must, however, be included in any unit or activity
cost estimates (see Sections 4.0 and  9.0).  It is particularly important
in the case of post-closure care to  include supervision and inspection
requirements that normally might be neglected in the cost, estimate.
Since labor may no longer be readily  available on-site, such routine
functions as facility inspection and  supervision and review of work
must be explicitly included.
                           i
3.6  The post-closure cost estimate  covers the period beginning at the
     completion of closure of the facility and lasts for 30 years there-
     after.

     The post-closure cost estimate  does not cover the cost of main-
taining any partially closed portions of the facility during facility
life.  However, the fact that partial closure has occurred for portions
of the facility does not in any way  shorten the period of post-closure
care required for the purposes  of the post-closure cost estimates.  The
post-closure period begins with the  professional engineer's certifica-
tion of adequate closure.  As a result, provision should be made for any
normal  remedial measures early  in the post-closure period, such, as
significant portions  of  the  vegetation  failing  to develop adequately.

-------
Si,"
  f         '•('  ,,.i	,     '        "   •      :   . ',    i   L ,  -   .''
3,7  Post-closure expenditures can be expected to occur  in two  cate—
  n .     ii, ill   *	 	pit" .'" .,  "!r , , ,   ,il .n,. •     	i:.1" ,,l i   ,i", .' . • :,  ii ,'„':,  '    "f: ,i,,,i,  i;'   I I 	| i „ซ • ,     	;, ,    ,' „
     gories;  regular annual expenditures and expenditures that occur
  (l '    	, •  ' !•.[' ,">V"  ..„:,  '•'   •:•.; >: *;:  -fv,-",  .;:	it-   J,  .,•*.: • 	' ;	'V .,,:,:" &\ ; .•:' i'fcrli-l;' '•: ,.•   ""•:  •'••   •
     with less than annual frequency.  The  written estimate of  the
     annualcost  of post-closure monitoring and maintenance Is  equal to
     the  sum of regular annual expenditures plus the expected number of
     ndh~anriual expenditures times their costs.
                                         • '                   ii
                                                             !
     This can be written as the following formula:
                                                             |
                                V N
                                 i i
  .  ,     ,       ,                  o31
where  P is the annual post—closure cost estimate, A is the size of
expenditures occurring annually, F^ is the  number of times over 30 year;
non-annual expenditure i  is expected to occur, and N^ is the cost  of
  "" , ' I	A,   ,'    ',| Jl  '"'IFIl1 ' , ,?" "     ",||     	'' '    ' '  	 I,'  '  	  ,1,  ' 1 ;, ' , ''Mi'? '   ! !!l , |. , ', ," - II  ' Illi  ''
non-annual expenditure i.   There may, of course,  be several kinds  of
  :'i!'". I   ,"!;! i-, j,:4i! 'fiiir ;;.  , .•	,  •!•:;•. .,','. , .; .  • '•   ' .... .1	 .;.'!  •-,- "  ... • *;'•	,iป^\}.[-•.ซ• ..,,:-. .•.'.•, .,  ;•
atmual expenditures and several kinds of non-annual expenditures.
Specific  types of non-annual expenditures that need to be considered
include provisions for special activities resulting from unusual
weather,  replacement of equipment, and provisions for replanting and
other  similar activities in the two to five years following closure.
                                              3-4

-------
                    4.0  PEffiPARING AND DOCUMENTING THE
                 CLOSURE AND POST-CLOSURE COST ESTIMATES
          '. :            " . .         '        -               '    .
     Although written closure and post-closure  cost  estimates are
required, the regulation does not specify format or  documentation  suit-
able for this cost estimates.  As a result, the  ultimate  requirements  in
this area will be up to the discretion of the Regional Administrator.
Certain general guidance may, however, prove useful.  The  cost estimate
must ultimately contain at least enough detail  so that the Regional
Office can make a reasonable evaluation of its  validity  at the time
of inspections during interim status.

     The overall goal of the cost estimate and  its documentation is  to
provide an estimate of the costs and the documentation necessary
to demonstrate the reasonableness of the estimate.  It is  not
required that the cost estimate have the kind of detail  and accuracy
appropriate to a contractor preparing a bid for a job.   There is  little
need for a highly polished cost estimate since  these cost  estimates are
for a hypothetical task that is to take place in the rather distant
future.
                                                                   •
                                           _
                            -
     Four basic approaches which might be used  in developing  costs for
the activities listed in the closures plan are:

     •  Costs based upon experience of the owner or  operator
     •  Contractor estimates
     •  Cost estimation handbooks
     •  Workups from labor„ material and equipment requirements
                           I
                           I
4.1  COSTS BASED UPON EXPERIENCE OF THE OWNER OR OPERATOR
                           I                  •               -
     The most directly relevant source of cost  information, in many
cases, will be the experience of the owner or operator in  operating the
                                 4-1

-------
facility.  An  example would be the costs of treating or disposing of
inventory on-site,  which will normally be a simple continuation of the
normal operating practices of the business.  In the simplest  case,  cost
of treating  or  disposing of inventory may be computed as  the  annual
          costs divided by the fraction of a year required  for  adequately
treating or  disposing of inventory.  Such an estimate could  then be
documented by  the past year's accounts, the amount of material treated
or disposed"  over that year, and evidence that the year had involved
relatively1 "typical activities ' (e.g., if, for a	landfill, no  trench
had to be dug  or covered over the course of the year, then the year
  F'l,.)' ", ,;„; ;$t>r,ia' " ; .,: ••    ,. i,\i,. ,   ;••;,•'". ;• ,v" .  i"-:,:.„ ;••	•',&"• !,:;:•! ••• IIM^'J,,	.';  .*v. • ••ซ;	  • TH	-'
might not be considered a suitable example from the viewpoint of
assuming the most expensive closure conditions likely to occur over the
life of the  facility).   Given that the requirement that a cost estimate
be available on-site is either six or twelve months after notification
  f .i T ., . !   !!"y!l til  '   '   . , .. • !i> '  .;  	I;1'1 •'. , •!  •. • • lr> ,", I' •' .;l\, , f'ji	.•'•I,.;1 hi •',*:!• lii ' .'"I,: ,• ' •  ••  " " ':• ,-Uf:
of the cost  estimation requirement, a variety of closure activities could
be documented  from noting the costs of the activity as they  occur over
                                                           i
tile interim^period.*  For example, for a landfill, the costs and activities
involved in  partial closures could be documented and used as a base for
  '!!  '   -I :  ,]!li|!!;l  "	  .      : • i, .:   : .    	:     •	• .   i;.  	 ,;i, .  r , I .    :••   L , ••    	 • • i *n,
urlit cost isti|nates of the cost of final cover.

  ;   Similarly,  costs of monitoring tests during post-closure w'ill be
similar tothe costs of monitoring tests during facility life, though
gathering samples will be more expensive due to the need to  assume
purchased labor and travel to the facility.  Possibly the best source
for costs and frequency of many kinds of post-closure non-routine
expenditures is the actual experience in maintaining currently partially
closed" portions of a landfill.
4.2   CONTRACTOR ESTIMATES
                                            , ,               ;j
  'i|l'      . .   ''/!'' Ill  ''B'l ',iJ!i  i „                    „   ,  ',   '     !,!. ป ij1,, , •   I • i| '    !'
      A variety of  costs, particularly if services are  to be  purchased
from a contractor  or contractors by the owner or operator, may be
*As discussed in Section 1.0, owners or operators of land  disposal
facilities,,,,	.are.,	not, .required to have their cost estimates available
until  twelve months after the effective date of;these  regulations.
Owners or  pperators of other facility types must have  an estimate
available  within six months of the'effective date of these regulations.
        :   ::" '  '-   '  '     '          4-2

-------
obtained  from  contractor  estimates.   For  example,  an owner or operator
could ascertain  the  costs of  certification by an independent professional
engineer  by asking several professional engineers  for estimates  of  the
costs of  certifying  the completion of activities listed  in the closure
plan.  If an owner or operator plans  to send  either  inventory or con-
taminated residues to an  off-site TSDF, inquiries  to ascertain distances,
hauling costs, and treatment  or disposal  costs would be  in order.   It  is
not necessary  for purposes of documenting,,  to have written and validated
cost estimates.  Adequate documentation could note who was contacted
and their approximate estimates.

4.3  COST ESTIMATING HANDBOOKS

     There are a variety  of commercial engineering cost  estimation manuals
that provide guides to equipment and  labor needs and  unit  costs  of
specific  operations that  may  be relevant  to various  activities associated
with 'closing hazardous waste  facilities.  Such manuals may be reasonably
used as a source for-cost  estimates for closure  costs.   Care  must be
taken in  using such manuals.  They vary widely with  respect  to whether
or not unit costs cited include such  factors  as  administration,  normal
contingencies, profits, and whether or not .allowances must be made to
adjust theoretical work rates to normal field conditions.

     From the owner's or  operator's view,  care should be taken that an
overestimate is not produced by using estimates which allow for profits
and capital recovery on equipment when this is not required if he is using
his own•equipment for closure.  Distinct underestimates are possible if
attention is not given to  the indicated need for adjustment of theore-
tical work rates to normal field conditions and for administrative costs.
As a result, suitable documentation for a cost estimate for an activity
based upon such a handbook would be a copy of the relevant pages  of the
handbook,  including those pages providing instructions as to the  use of
the unit cost estimates and any adjustments from the cited costs  used in
arriving at the unit cost estimate employed in the cost estimate  itself.
                                   4-3

-------
                                                                             1 '•*
4.4  WORKDPS FROM LABOR, MATERIAL AND EQUIPMENT REQUIREMENTS
  '11 "       "              '       '  r    •       • '   •••      '
              ,
  ,i , ,   -"    i   , ....... u
     In some cases, there may be no way to arrive at a useful cost
estimate other than by a detailed workup of the costs.  Such a workup
would include an estimate of the labor, equipment, energy and material
needs for the activity to be estimated, the basis for these assumptions,
and the total time required for the activity.  Allowance would then
need to be made for supervision and administrative costs and any
necessary adjustments for fully loaded labor and equipment costs.
                                   4-4
                                                       	,	J.

-------
                5.0  ADEQUACY  OF  THE  CLOSURE COST ESTIMATE

     For the closure cost estimate to  be  judged  adequate, it must meet
the following criteria:

     1.  The closure cost estimate must contain  cost estimates for all
activities presented in  the closure  plan.   The cost  estimate must also
reflect the quantities and methods associated with all of the activities
presented in the closure plan.   (Note  that  the adequacy of the cost
estimate' is therefore dependent  on the adequacy  of the closure plan.)

     2.  The closure cost estimate must be  documented in order that the
bases for the cost estimate can  be checked.

     3.  The resulting cost estimate must reflect the actual costs of
carrying out closure.  This can  be determined by a check of the sources
listed for documentation providing that Rule 2 has been met.  A cross-
,che,ck can be made by using alternative sources,  i.e., if the owner's or
operator's cost estimate is based upon a contractor  estimate,  this may
be.checked through reference  to  a cost estimation manual, experience of
other owners or operators, or inquiries to  other contractors.

     The cost estimate must be available upon the premises for inspec-
tion during interim status.   As  a result, it will be useful to have
available simple and rapid checks as to the  adequacy of the cost esti-
mate.  The remainder of  this  discussion is  devoted,  in part, to a discus-
sion of simple  checks, that could be  accomplished in  less than an hour  or
two with the aid of the  closure  plan and  a  visit to  the facility to deter-
mine the adequacy of the closure plan  (see  Section 12.0 of the draft
guidance for Subpart G, Closure  and  Post-Closure Care).   These checks
are not intended for use by owners or  operators  and  may not be used as a
method for developing a cost  estimate.
                                5-1

-------
                                        11        -i,, '.".  i ; 'I,
     If an initial check raises questions  as  to  the adequacy of the cost
           , ;  	ii;  •        ,      .,,        ,	••	;,  •;'   •  | .;
estimate, several steps may be taken.  First,  a  copy  of  the complete
cost estimate may be required and reviewed, and  a check  made of the
documentation.  It is quite possible that  the  cost estimate  could be
accurate and fall outside the ranges indicated in the discussion below.
If, after review, the cost estimate still  seems  inadequate,  the owner or
operator could be specifically requested to make the  desired alterations.
If this approach fails to result in a satisfactory cost  estimate, there
are two possible recourses during.interim  status.  The Regional Adminis-
trator could bring an enforcement case or  he  could request  part B of the
permit application and thus revise the cost estimate  as  part of the permit
  fill ' '       ;   ;,;)i  '.':•'•               ,    •   I   •  ; j  I  .  '
application process.
  <". .        ,|,  '^ ,                  .    .           ,    ,	",   ,.'!'
              1 /iH     ,         ,11                   '
  t   Unfortupatj&ly, the annual report of the  facility, though it must
include the cost estimate, does not contain adequate  information to
                                                            i
                                                            i
determine the accuracy of the cost estimate.   For example,  the amount
ofinventory on-hand is not a required element of the permit application.
Therefor^, in order to check on the accuracy  of  the cost estimate, it
may be necessary to visit the facility.  An inspector could then obtain
copies of the closure plan and cost estimate,  and conduct a quick review
of the key variables for the closure plan, as  discussed  in  Section 12.0
of the draft guidance for Subpart G, Closure  and Post-closure Care.
  ' > I        ' !   ' '<     •    .          . -                  ;, '  •  : ••  I •.
  :"' :.•      '•  \:  ,;   ••  ,   ..          •          ,:  •  :,',:  (!:.|
     Table 5-1 shows the key elements involved in verifying the closure
cost estimate, listed by major types of activity involved.   For each
  1, "jJLi '       ,;,'!  i M •'    ,.•!, M,,   ,,      ' | , „     f  ;     ,,  „' N,  ' ' i, "iir  |,1  | , I J,, ,:, I „
activity, the major elements required to check the adequacy are the
activity indicator  (the variable that determines the  degree of the
activity, e.g., quantity of inventory, volume of contaminated soil),
unit costs (estimates of the unit costs for each activity•'of the facility
                                                            ,
in question), and sources for variation in unit  costs from  facility to
facility.  Also included in this table  are current typical  costs of each
required activity.  A relatively wide range  is used due  to  variations
depending upon the  region and upon  the nature of the  wastes (e.g., high
 * i ;• , ;N.  •    ' •  .'ii!      . .  :;             •        •     ?,, i,	::   • j r  |.,
hazard wastes have  greater costs than lower hazard wastes).  As these
  I	', :'      ' '•:   -i'!     • •       •                .•  - •  '  ,i!  •  , M  |:
costs are national  averages, more accurate estimates  would  be obtained

                                    5-2

-------
                                                           TABLE 5-1

                                         CLOSURE  COST  ESTIMATE RAPID  CHECKS
















Ui'
1
u>






















Required of All Sites
1. Inventory Disposal






2. Decontamination and
Decommissioning

•




3. Monitoring

4. Certification

Required of Landfills and
Some Surface Impoundments
1. Cover
ซ. Clay


b. Synthetic Liners


2. Vegetation



Optional
1. Leachate Collection,
Removal and Treatment
2. Gas Monitoring and
Collection
3. Additional closure
requirements
ACTIVITY INDICATOR

Quantity of inventory
Quantity of residues





Volume of contaminated soil
Volume of wastewater
Amount of equipment and





Number of tests

Man-hours of professional
engineer time



Acres not covered, depth of
cover

Acres not covered


Acres not vegetated, type
of vegetation









UNIT COSTS

On-Slte: 30-80Z of average
off-site disposal costs
Off-Site: 100X of average
off-site disposal costs
and hauling


.,

On-Site: 30-80* of average
off-site disposal costs.
Off-Site: 100X of average
off-site disposal costs
and hauling




Average costs of tests

$/liour of professional
engineer time




















*In verifying the closure cost estimate, local updated costs are preferable. See Text.
SOURCES OF VARIATION IN
UNIT COSTS

Throughput, type of site.
quality of disposal,
nature of waste




Throughput, type of site,
quality of disposal.
nature of waste





Regional, monitoring plan
requirements
Regional




Terracing, nature of cover.
design of cover, type of
soil
Terracing, liner material,
thickness of liner
material
Terracing, nature of cover,
design of cover, type of
soil, type and density of
seed, provision for
replanting







TYPICAL 1980 COSTS*

Off-site disposal costs by type of
facility:
Incinerator - $100-200/ton
Landfill - $ 80-150/ton
Surface
impoundment - . $ 10- 30/ton
Land treatment - $ 10- 40/ton
Hauling costs - $ .02-$. 10
per ton mile
Off-elte disposal costs by type of
facility:

.Landfill - $ 80-150/ton
Surface
impoundment - $ 10- 30/ton
Land treatment $ 10- 40/ton
Hauling costs - $ .02-$. 10
per ton mile
$200-500/uell**

$SO-100/hour of professional
engineer time



$500-1,500 per foot per acre


$500-20,000 per acre


$400-1,500 per acre











"These costs are for ground-water monitoring analyses as specified In the regulations; air and soil
  monitoring are not Included.  The 'estimate Is based on the moat  extensive monitoring that could be
  required within a six month closure period.

-------
                                                                             i '*
                                                            3 must be
                                                           ii
 . 1        . >,	;                              . ' \; , ,  .'    ' I ' I .   '    "     "
using average costs for the specific area.   These costs also  must be
adjusted annually for inflation.  A mechanism for making this inflation
adjustment is discussed in Section 8.0.
                                                           I
     For example, to check the adequacy of the cost  estimate  of  treating
or disposing of inventory, one would:
                                            ,'•', V ,',i ; J'.
     (1)   Determine the adequacy of the estimated amount of inventory
       ' •'  ' ,',  '. I,  „  'I '!. "   '  I     	    ' i  ,     "'..i ''' .'ซ' "!  .','., IN    | ,<  i |j I i     .„        '   ,1
          (this  could most readily be done by examining the closure plan
          and facility conditions to determine whether the closure plan
          adequately reflects inventory needs of the facility);
     (2)   Determine whether, in the case of treatment facilities (including
          incinerators), provision has been made for treating, disposing,
          or removing residues off-site which result from treating inventory;
     (3)   Multiply the quantity of inventory in the closure plan by the
          unit costs given in the .Table; and                        (
     (4)   Consult the variability factors listed in the Table (e.g.,
          throughput, type of facility., nature of" waste, on- or off-site
          disposal), to determine whether the facility should be at the
          high or low end of the range for unit costs.

5,1  ACTIVITIES BELEVANT  TO AT.T. FACILITIES

5.1.1  Treating, Disposing,  or Removing  Inventory

     For  facilities  not engaged  in disposal  requiring  post-closure care
              	     "             '       ...,.,,,   if     , , n , .,,    .i
(all types of facilities  except  landfills, and surface impoundments and
land treatment facilities in which hazardous wastes  remain after closure),
treating, disposing  or removing  inventory will frequently be the largest
single cost:  element.  The exceptions  to'this rule  of thumb will normally
be situations in which unusual  decontamination problems occur,  such as
large amounts of waste water accumulating  at the facility.  The key unit
parametersin determining the costs of treating,disposing or removing
inventory to an off-site  TSDF are the amount of  inventory on-hand and,
 i,         :: ^,1! 'ij. 'ป!..„, '       •'."!  •.   ' ' •   'i      ' '   " " •' "*  h   ' * • i'1 '	•  ' i ;' i|" "''   '  "' ,-. r        ';•' i
for  incineration  and processes  involving treatment,  the relationships
 i,         1!   "             .                              :  i ,                 i

           ..  : ••       	         • 5-4                  '  i!

-------
 between inventory processes and residues to be disposed of or treated
 on-site or removed to an off-site TSDF.  The quantity of inventory on-
 hand will vary enormously depending on the type of facility, the annual
 throughput of the facility, and management practices.  For some types of
 facilities, inventory can be minimal.  For example, some landfills accept
 only trucked-in wastes on a. space-available basis.  For such a landfill,
 there would very seldom be any inventory at all.   It is also possible,
 however,  that start-up problems or, in the case of landfills, failure of
 a major cell or cells could lead to a situation in which there is an
 enormous  amount of invento^ which cannot be quickly worked dff,  and this
 would have to be accounted for in the cost estimate.

      The  unit costs of removing inventory are dependent upon whether the
 inventory is to be disposed of or treated on-site'or removed to an off-
 site TSDF.'  In the vast majority of cases at disposal facilities,  the
 disposing or treating of inventory will take place on-site.   If disposal
 or treatment takes place on-site,  the unit costs can be expected  to
 fall between 30 and 80 percent of  the prevalent Regional costs for
 removing  the inventory to  an off-site TSDF.   On-site costs will be less
 than off-site costs because closure costs  need only include  the immediate
 operating costs  of disposing or treating  inventory and  not factors for
 capital recovery,  land,  etc,,   The variation will depend  upon  the type  of
 facility,  its  normal throughput (because  of economies of scale, small
 facilities will have higher unit costs than  large  facilities  for almost
 all  types  of  facilities),  the  quality  and  safety of  disposal  practices
 at the facility, and  the nature  of  the wastes.  For  a landfill which always
maintains  adequate  open  trench  capacity, inventory disposal costs  could
be a very  small  fraction of normal  off-site landfill disposal costs.  This
 is because  the costs  of building the trench would not need to be included,
 and the costs  of cover and vegetation are covered separately.  Under these
 circumstances,  costs  for treating or disposing of inventory could
 be lower  than the  30  percent: indicated.  For  inventory or residue  that
must be removed  to an off-site TSDF, unit costs will be 100 percent of
normal off-site costs in the Region, plus appropriate hauling costs.
                                   5-5

-------
            IB1"!!	'^p'lyi BIIIIS';, 111! ;	'i	;	 ,	,=' "!:!	I!1"" , '	i"; •• "  	     I             111 11
         S.I.2  Decontaminating the Facility

              Under certain circumstances,  decontaminating the facility could be
         thglargest cost element  for  the facility.   This could be the case if
         large quantities of soil  are  contaminated,  as might occur at any poorly
         run facility or at many improperly run surface impoundments, or if large
         amounts of waste water have accumulated at  the facility.  Fฐr many
''f11   •!    facilities,"1	liowever, decontamination will be a relatively minor cost
         element requiring only general cleanup of equipment and facilities.  The
         key activity indicators for decontaminating the facility are: quantity
         of contaminated soil; quantity of contaminated waste water; and amount
         of equipment and facilities requiring" cleaning.
;;;.         ;.        .;.	u  .;              .         ,      ,   .  • ^ •.	  .,   |
              For contaminated soil and waste water, the relevant unit costs will
                                                                      I
         be those cited for disposing  or treating inventory, i.e., costs for
         disposing or treating the soil and water on-site or off-site.  For
         equipment and  facilities, the costs  will depend uponcleaning costs
         themselves  and whether  or not the residues resulting from cleaning will
         require  treatment as hazardous waste.
    : i      <"?<     •    ;;;;;'	;    ...          ,           .     _,,, ,   •;'!,'           ••  ••

         5.1.3  Monitoring

              A facility  must continue monitoring practices during the closure
         period;  therefore,  some costs must be included for monitoring.  The
         costs  may be  estimated  using the current lab costs for  the  tests  in
         the Region  and will vary regionally and according to  the monitoring  plan
         in place for  the facility.
    , ,       , ,      ,  „   ,,,              i           ,            ,	      | „
         5.1.4   Professional Engineer Certification

              The closure cost estimate must include provisions  for  the costs of
         certification by an independent professional engineer.  Like monitoring,
         this will normally be a relatively minor'cost  element.  The activity
     i      f,, iL : ,   "	 ' ,,,,n 'I!;1"!1"  'i i"1, "'   ' i       '   ",  '."'•"',,,    i    '•• ' "   • ,. , „' j1!.,1 •   i !.•!  J i  •     r
         indicator for certification is  the hours spent  on~site  by the professional
         engineer, which will normally  depend  upon  the  length  of the closure  period
         and the amount of activity which must take place.  The  unit cost  parameter
          is dollars  per hour of professional engineer time  in  the Region.
SI,   I ":„    ;       '..',„;.        ,           ,            •  . .  ji:   • ,| i  j
	      "       '   '   "                     5-6 '                 ' '  :

-------
 5.2  COSTS REQUIRED ONLY OF LANDFILLS AND SURFACE IMPOUNDMENTS

 5.2.1  Cover

      Some form of cover will usually be required for both landfills and
 surface impoundments which have hazardous wastes remaining after
 closure.  Cover and the associated vegetation (see Section 5.2.2)  will
 normally be the dominating element in determining the costs of closure
 for a landfill or surface impoundment.

      The materials to be used will depend on the types of soil available
 on-site as well as the conditions  of the facility.'  Since purchasing
 soil off-site  is costly, it :is likely that most  owners or operators
 will use soil  available on-site, if at  all possible,  for  the final cover,
 i.er;  the layer with low permeability and the layer  capable of supporting
 vegetation,  if applicable.   It is  possible to improve the quality  of
 available soil by blending  various soils,  using  soil  additives,  or making
 other-provisions which would  provide equivalent  protection.   For example,
 soil blending  and synthetic additives may decrease the permeability of
 the on-site  soil as  well as make certain soils more capable of supporting
 vegetation.  In addition to improving the quality of  available soil,
 the Agency anticipates that many owners  or operators  will use  membrane
 liners  protected above and  below by buffer soil  layers  instead of  com-
 pacted  clay  for the  layer of  the cover with  low  permeability.  These
 membrane  liners  may  be cost effective if  adequate on-site soil material
 is  unavailable  or an acceptable degree of  compaction  is not possible at
 a particular facility,  given  the wastes  disposed or facility conditions.

     When  clay  is  used  as a liner material,  the key activity indicators
 are acres not yet  covered and  the depth of the cover.  As noted in the
 closure plan, decisions as  to  the depth of the cover and  the adequacy of
 on-site materials  are  dependent on engineering judgment and are not
 covered in this  guidance document.   The costs associated with such cover
may vary from $500 to  $1500 per foot per acre of cover.  The key sources
of variation are:
                                   5-7

-------
     (1)   The amount and nature  of  terracing to be used in the cover;
     (2)   The depth of the area  to  be filled in the case of surface
          impoundments;
     (3)   The nature of the  cover,  including whether or not"treatment
          |s required to achieve proper degrees of impermeability; and
     (4)   The design of the  cover.
 h"';  For synthetic  liners,'	the key activity ""indicator" is "the  acres not	
covered.  The costs"associated with: such covers -vary .Videly,  depending
 '•"' ',,  ,t	,  , '.[IIBII i1! if i  i" • •" .,'• 'i.  i,'1",  '  .  ,  i. '  :   •   ;:i  ,',;'", f  --i	ป  ','i *>" I .1  t. .    . -   •'    • '
op the type of material chosen and the thickness needed to  ensure adequate
low permeability,   it  is  not the'purpose of" this" document to" assess
alternative materials  of to provide guidance as to  the  level  of  per-
nlf^iiity'1''whicl 'is  acceptabiel  The costs associated1 with "'installed
liner materialJper  acrevary from $5,000 to $20,000per acre.  The key
sources  of variation are:
      1 ,..  	:: ";;;::  • •        • ..        .         .        :;:  .,  ,   j
          	'•	     '  "             .                    ''   i
 ,!!, I1,!'  i , '   ,ซ!'  Oil!',:!1 , !< iW • '  in ''  , „ If1 ' , ป  n, ", ,„   ,  ' '   ljl   "' ''  ' •  ,:'  - ', 	     /!:il l| ' '. . -   '"  "    .  '.   '!
      (1)  Theamount and nature of terracing to be used in the cover;
 I;: ,  ^ "Type'of "liner"material chosen; and
 •'•''•'• ' ,:  '-is!? lii:!0li	'•	 ,'.	*.:•;:.  "!:"	,  •: . •  	'..'1	:   ',    .'••'•   ••  '•   *.,-. H'^:| •.  ,"   i !-    '     "
      (3)  Thickness of material necessary to achieve desired degree of
 f'"1"  ' "   '"""jieriieability.
                                                            I

 5.2.2  Vegetation

      For mostfacilities,  some vegetation will be required in order to
 stabilize thecover and  prevent erosion problems.   The key activity
 indicators are the number of  acres in need  of  vegetation (which  may include
 areas previously seeded  but for which vegetation, has not properly
 developed) and the type  of vegetation to be employed.  Unit  costs can
 be expected to range from $400 to  $1,500 per acre.  The  lower end of
 the range would represent the costs  of minimum fertilization and planting
 with no provision  for  reseeding and replanting of  any kind.   The maximum.
 costs, would represent  the costs of providing a lawn-type cover.   Other
 key variables in determining  cost of vegetation are:
                                    5-8

-------
      (1)  The type of soil (including determining the degree of
           fertilizer required); and
      (2)  The type of seed used.

 Establishing complete vegetation within the 90 days to six months over
 which closure will normally take place cannot be attained.  As a result,
 some costs associated with developing and establishing vegetation will
 probably take place early in the post-closure period.   Therefore, the
 adequacy of the closure plan with respect to vegetation should be checked
 in coordination with an examination of the provisions  for maintaining
 vegetation in the early years of the post-closure plan.

 5.2.3  Optional Measures

     Three kinds of optional measures,  bearing significant costs,  may be
 necessary at some facilities:   collection,  removing and  treating  leachate;
 collecting gas;  and additional measures  required to protect human health
 and the environment.   Even for facilities with leachate  collection systems,
 the cost of leachate collection,  removal,  treatment and  disposal  for
 closure will normally be the relatively  minor cost  of  occasionally
 collecting the  leachate and hauling  it away to an off-site TSDF.   In
 certain rare cases,  leachate build-up may be great  enough to require
 an extensive on-site  treatment and disposal system.  If  this is the
 case, this  could  be a significant cost during the closure period.
 Maintaining an  existing gas  collection system normally will be a  rela-
 tively minor cost.  At  certain facilities,  additional  activities  may
 be required to  ensure the  protection of  human health or  the environment,
 such as  those discussed  in Section 9.0 of the draft guidance for  Subpart G.
 Such measures could be  extremely expensive  and would constitute a  large
 share of closure  costs;  however, the exact  combination of necessary
measures will be  extremely site-specific.
                                 5-9

-------
                                                •y;-	•;'

                                                                                                                                                                                                            (-,  "f
                                                                                                                                                                                                            ill  :'
.'>   ltfl.1:

-------
             6.0  ADEQUACY OF THE POST-CLOSURE COST ESTIMATE  .

     For the post-closure cost estimate to be judged adequate, it must
meet the following criteria:
                            l
     1.  The pbst-iclosure cost estimate must contain cost estimates for
all activities presented in the post-closure plan.  The cost estimate
must also reflect the quantities and methods associated with all of the
activities,presented in the post-closure plan.  (Note that the adequacy
of the cost estimate is therefore dependent on the adequacy of the post-
closure plan.)

     2.  The post-closure cost estimate must be documented so  that the
bases for the cost estimate can be, checked.  Documentation may be
performed in a variety of ways; however, it must be provided  in such
a way that the .sources can  be reviewed and judged by an outside party.
For example, if an owner or operator states that a cost estimate was
taken from an engineering cost estimation manual, the estimate could
be easily verified.

     3.  The resulting cost estimate must reflect the actual costs of
carrying out post-closure activities.  This can be determined  by a check
of the sources listed for documentation providing that Rule 2  has been
met.  A cross-check can be  made by using alternative sources,  i.e., if
the owner's or operator's cost estimate is based upon a contractor
estimate, this may be checked through reference to a cost estimation
manual, experience of other owners or operators, or inquiries  to other
contractors.

     The cost estimate must be available on the premises for inspection
during interim status.  As a result, it will be useful to have available
simple and rapid checks as  to the adequacy of.the cost estimate.  The
remainder of this  section is devoted to a discussion of simple checks
of the costs of specific activities that could be used with the aid of
the closure plan and a visit: to the facility to determine the  adequacy
of the post-closure plan (sซe Section 12.0 of the draft guidance for

                                   6-1

-------
Subpart G, Closure and  Post-Closure Care).  These checks  are  not
intended for use by  owners and operators and may not be used  as a method
for developing a cost estimate.
            ..   'ซ• !'     .         "           -•        '  "  ""!.:  ' 	' '-I It'.'" :  :.•• .  	  ': !
     If an initial check raises questions as to the adequacyof the cost
estimate, several  steps may be taken.  First, a copy of  the complete
cost estimate may  be requested and reviewed, and a check made of the
documentation.   It is quite possible that the cost estimate could be
   if! !! i,,  ,,11   !, ' ""i,,!,  .„ ' .       i , ' ,  ,   '  i ,   ' • ll1,    • ' '   . 'i  „' '  • , ' ,","''•', i" I ii.ii, 'jj  l,r, ,:	,,.fl|| • ' ' ,11   ' '.
acciirate and* "fall  outside the ranges indicated in the discussion below.
If, after review,  the cost estimate still seems inadequate, the owner or
operator could be  specifically requested to make the desired  altera-
tions.  If this  approach fails to result in a satisfactory  cost estimate,
thefre  are two possible recourses during interim status.  If the cost
estimate is obviously completely inadequate, the Regional Administrator
may start an enforcement action or he may request part  B of the permit
application and  revise the cost estimate aspart of the permit applica-
   l:'!!" i       ;i,	i  '    ••   .  , ,       ';'	 :,  .,   ' ' ' 'ii •   |ป- ..•.;il:|i; :: J p|'r: t"1;1  • "  ;; ,•	', • ;;,,''/.
tion processJ

     Unfortunately, the annual report of the facility,  though it must
   i," ' :>   '   ' '. •!   '       '      .      . •             ., 1"ป	 . .: - , i ... i, ..,  c   -   ..  ' ..
include the  cost estimate, does not contain adequate  information to
   1. ' i,, i.,       , :"!P	", ..      I!1  .;,,.•     ,         ,   .:. r   „ niji '	•,    i .1 ||  ,,,. ,   ,
determine the  accuracy of  the cost estimate.  Therefore, in order to
check  on the adequacy of the cost estimate, it may be necessary to visit
the facility.   An inspector could then obtain copies  of the post-closure
plan and cost  estimate and conduct a quick review  of  the key  variables
for the post-closure plan, as discussed  in Section 12.0 of the draft
guidance for Subpart G, Closure and Post-Closure Care.
   -	         -   "         '        .           .. 	:.''.'' ' .      i
     Table  6-1 shows the costs of certain activities  which may be asso-
ciated withpost-closure cost estimates.  This is  a  list of selected
major  activities, and is not intended to reflect all  possible post-
closure activities .  These activities have been broken  down by key cost
elements rather than by elements of  the  post-closure  plan.  For example,
   	 '  .     ' >:s:  I1' V"!        " ' '    ' ' !   ',   : ,    ' , ''   ,'•'' '•'!' i "li'i1:' .  lln'ii ". '"  , ' 'Inl , I  ' '."', '  '!'  '"!	    '"
one heading in Table 6-1 is "Inspections and  Facility Visits."  The  table
  VI! '•      :•.•-.' , ,'lj.j .    ,      ,.      ' ,  ....  -   •, •   .;..:••  • ,;'"/*>  lit,,,'	   ,' „ i,,n (..'.•.'•  . .v .
simply shows the expected  costs  of  such  visits per hour on-rsite.  Deter-
mining the  number of inspections and facility visits  required will be

            • •    :                    6-2

-------
highly  site-specific  and will  depend  upon the  post-closure plan.   Further,
these inspections and facility visits may serve  a variety of purposes  in
the post-closure plan.  For example,  inspections and  facility visits may
be for  the purpose of ensuring adequate  erosion  control,  maintaining
surveyed benchmarks,  obtaining ground-water monitoring  samples, or check-
ing the adequacy of leachate collection  facilities.

     Table 6-1, for each activity  indicated, shows an estimate of  unit
costs and notes the sources of variation in these unit  costs.   The unit
costs are given in 1980 dollars.   In  order to  maintain  the accuracy of
Table 6-1, it should  be updated on an annual basis to reflect inflation.
A discussion of the methods for adjusting the  cost .estimates to account
for inflation is provided in Section  8.0.  The sources  of variation in
unit costs are specific to the headings  listed.   Two  generic sources of
variation* however, have not been  noted.   First,  all  costs can be
expected to vary regionally and locally.   Ideally, these  national  esti-
mates of unit costs should be  replaced by  costs  developed from experience
for the region or state in which the  facility  is  located.   Second,  all
costs will, vary with  the remoteness of the facility.  Since most post-
closure activities are relatively  small  in.scale  and  may  involve only
a few days on-site, significant travel time to and from the facility
will have a noticeable effect  on almost  all costs.

6.1  INSPECTIONS AND  FACILITY  VISITS

     As noted above,  inspections and  facility  visits  may  be needed for a
variety of purposes.  The unit costs given will thus  be relevant in
checking the costs of a variety of activities.  The estimated unit, costs
in 1980 dollars are $20 to $100 per hour on-site.  The chief source of
variation in these unit costs will be the  professional level of the
personnel involved.   It will normally be useful to have an inspection or
facility visit by a professional engineer  at least once a  year.  Inspections
and facility visits by less,technically  qualified  personnel will depend upon
the specifics of the post-closure plan,  the climate,  and the size and
nature of the facility.

                                   6-3

-------
                                                       ''"'"I"	I I'
                                                       ":;;	r
                                TABLE 6-1

                COSTS OF SELECTED POST-CLOSURE ACTIVITIES
     ACTIVITY
UNIT COSTS*
SOURCE OF VARIATION
    IN UNIT  COSTS**
   1,  Inspection/Facility
•" • ';'   Visits

   2.  Reestablishing
      Cover and Vegetation
   3.  Fertilizing
ป;vjป s.  Groundfwater
      Monitoring

   6,  Maintaining and
      Replacing Fences

   7.  Collecting, Removing
      and Treating Leachate
$20-100/hr. on-site
$300-1500/acre
$50-200/acre


$10-30/acre

$200-600/well


$.20-.80/ft./yr.


$.20-.80/gallon
Professional  level
of personnel

Amount  of  erosion
Nature  of  cover
Type of soil
Amount  & density
  of seed

Amount  of  fertilizer
Method" "of  spreading
    ...    .   i   V  '!ป
Monitoring  plan
requirements
•   :.;  p. .;   ;
Type  of  fence
Climate
.•":„;:••[	-  'x.  •••  •   ..
Chemical composition
   1980 dollars.
 **
  "All costs of all activities vary by region and with the remoteness
   of the	facility.
i'l'l	
                                  6-4

-------
6.2  REESTABLISHING COVER AND VEGETATION

     Reestablishing cover and vegetation may be necessary for a variety
of purposes, including:

     o  Replanting to establish vegetation not adequately established
        during closure;
     •  Replanting to repair minor erosion or  rodent control
        problems;           !
     •  Reestablishing cover lost as a result  of a major contin-
        gency, such as a major storm or flood; and
     •  Reestablishing cover to correct for subsidence problems.

     The costs of this activity in 1980 dollars may range from $300 to
$1,500 per acre.  This cost'will vary according to the nature of the
cover, the type of soil used,, and the amount and density of seed.  In
addition, the costs can be expected to vary according to the amount of
erosion or subsidence which necessitates replacing the topsoil or cover
material.  The lowest costs are for simple replanting, and the highest
are for reestablishing and compacting as well  as reseeding substantial
portions of the clay cover and topsoil.

6.3  FERTILIZING

     Depending upon the vegetation, topsoil employed, and climate, some
fertilization may be necessary.  The frequency will be highly variable.
The estimated range of costs for this activity is $50 to $200 per acre
with the variation dependent upon the amount of fertilizer and the
method of spreading it.

6.4  MOWING

     Mowing is necessary in any climate in which deep rooted vegetation
may readily be established.  In most cases, it will be the most cost
effective means of preventing such deep rooted vegetation.  In some

                                   6-5

-------
climates, mowing  requirements may be Tn-f.ni.mal or  there may be more cost
 i, "i     ,  .. "lllih  ''Si  I1 I'  • ' ,M	I .  ' ;.  l' ", ปJi .1 ii"',;,;, 	('"'L '	iiii'1 '.iv "'"'i V l^i*!1 "' " ii"l|"' i'i	!.'!''*'"' "',''" I '"'"-"" '''
effective methods than mowing for ensuring that  deep rooted vegetation
does not become established.   The estimated range  of costs in 1980
 fell1. ..I  , ,   !','!•!"  ii'S! ft 	 	•• • !• ,  '    , .'.,  • :  4	 '•',. !*., . • :. 	I	 ',  , , I , j,,.1,,•*".''.   ;y*;>   '   I- • ! -it";
dollars is $10 to $30 per acre.
                                                            i
                                                            i,
6.5  (SOUND-WATER MONITORING
 li'i ,,'! , ., •', ,  	'!!	||  S /Illl   ,  :,'• ,      '    ' ,   	 •  ,    ..„ "     " ,  ' 	,,
 ,!  ,    '   Ji'J  //ifi   .  .-   ,   :   '     ;     ' _  '  ...;,'• :";' ; $ •; .
     At alฃ facilities,  a ground-water monitoring  program" of some kind
will be required.  In*addition to the costs of associated site visits
togather samples,  these costs will be based on  the average costs of
the tests required,  which are the result of the  monitoring plan require-
ments .     _,  ,,	        ,       	     i    		      I

6.6  MAINTAINING  AND REPLACING FENCES
                                                            i
     Many  facilities will be required  to have some kind of fence as
security during the post-closure period.  Assuming the  use of some type
of chain link fence, provision will need to be made for replacing the
fence at least once over the 30-year post-closure  period.  In addition,
some provision must be made for inspecting and maintaining the fence.
It is estimated that the cost of such maintenance  and  replacement will
be $.20 to $.80 per linear foot of fence per year. The variation is
dependent  upon the  type  of fence used and  the severity  of the climate.
 f         ,;;;:,;  ;;      >      .	" . •.   v	,:.'   , ;•. \ • -..  •  • •
           ..•  •.	     •             i           	.;„  •.       i
6,7  COLLECTING,  REMOVING, AND TREATING LEACHATE
 	      ' Hill -  ,i|l|l"ll[l' "    I ,1 ' 	t''  '     . I. , .  . 	 ,. , 	''I- •:••' ' 1 ' . 1 i^l'j .  >... Hi |   ",

     At some  facilities, a system for  collecting!,  removing, and treating
                                                    f ' '   '"  . !!
leachate may  be required during post-closure.  The estimate given here is
based on  the  assumption that a small amount of leachate will be collected
periodically  and  removed to an off-site TSDF.  The costs of an extensive
leachate  collection system requiring treatment on-site  would normally be
much higher.  The estimated range in costs is from $.20 to $.80 per
gallon  of  ieachate  removed, with the range in the  costs depending in part
upon the  chemical composition of the leachate.
                                    6-6

-------
     7.0   REVISING THE CLOSURE AND POST-CLOSURE COST ESTIMATES

     The closure and post-closure cost estimates must be revised when-
ever a change in the closure or post-closure plan is made that affects
the costs of closure or post-closure care.  Changes to closure and post-
closure plans are discussed in Sections 11.1 and 11.2 of the guidance
for Subpart G of the Interim Status standards.  Changes in the closure
plan which may cause a revision in the closure cost estimate include:

     •  Change in facility size and/or capacity;
     •  Changes in technology that may affect:treatment and disposal or
        decontamination techniques, type of cover chosen, etc.;
     •  Changes in the closure schedule which alter the length of
        the closure period by greater than one month (e.g., severe
        weather conditions may halt construction activities and
        extend the closure period by more than one month);
     •  Changes in  the schedule of periodic activities which
        affect activities required at closure (e.g., failure to
        partially close a facility would mean that a larger area
        than previously estimated would need to be closed at
        closure; the closure plan must always account  for the
        maximum extent of the operation open at any time over  the
        life of the facility);
     •  Changes in  types and/or quantities of wastes that affect
        activities  required at closure (e.g., the type and/or
        quantity of waste on-site at  closure will affect the
        choices of  treatment and disposal; for example, the amount
        of waste removed to -an off-site TSDF by the owner or operator of
        an incinerator depends on the types and quantities of  resid-
        uals that remain after burning the wastes.  The
         types  and  quantities of waste can also  affect  monitoring
         requirements and cover  requirements);
                                 7-1

-------
                       v .. ...... i*,; ....... Mid . ..... n ...... f ' v ..... ihiHi'i ...... 1 ** n1;. , ป• , '  ' . ram ...... m< liiii,,1!! •• im1 | ..... v
     •  Change in maximum quantity of inventory ever expected  on-
  ;.. '    site;  "         .',   '   'i       '  .     '   '  "  """'  '  ' .'..,       '     :
     •  Change in cover requirements from what was originally
  •„' '    proposed;       ......         '   '          .............. "
     •  Changes in ground-water monitoring requirements as a result
        of an owner's or  operator's operating experience or new data
        which was not: available when the plan was written 1  The ground-
  ,,  •'     •!}'ป' !.*!!",l  *  r 'I1'-; ' ...... ,n .......  '•  :ซ ; ..... •'   '., ..... ,! '*  . •. I!1,-'!1 '" ''* > . ..... I; | • n ..... ',. •! .........   " ' '
        water monitoring  regulations stipulate that all or part of the.
    ;•  "  p  ;:: ;,"  :"   ;  ":      ....".  "- "  .. • "  ..... . ' ..... : ...... •;.  " ..... ,  ;, !,:'/ .......     ,
        requirements may  be waived if there is a low potential  for
        pollution (ง265.90).  Revisions will also be likely when the
        EPA  provides more guidance and technical engineering data on
        the  kinds of monitoring appropriate for hazardous waste facil-
        ities; and
     •  Operating contingencies during closure which may affect closure
        requirements  (e.g. , inclement weather causes construction
        problems; more  contaminated soil needs to be disposed
                                                         .
        at closure  than anticipated as a result  of problems occurring
        during operation) .

     Changes in  the post-closure plan which may  cause" a revision in the
post-closure cost estimate include:

     •  Change in facility size which will affect the  extent  of
        maintenance required;
     •  Changes  in monitoring requirements as a  result of an
        owner's  or  operator's operating experience, new data  which was not
  f" ,    ,   AS I- ''dUii  i ., ..   i"  •ซ   •    i,1!, , ,  .'•.,'    i' 'i, ,-.,:' ..... ;•;• , i ..... 3 'IV ,  I :i •[•'.:    '!•  . '
        available when the plan was written  or modifications  approved by
        the  Regional  Administrator  (e.g. , changes in  the number of wells
  :'":,"        ii| ......... Bi               .....        i     ii" ...... ......... ' , i ,,    • ,. i ' „ ||
        monitored and  samples, the  frequency of  analyses, types of
        analyses required).  During the 30-year  post-closure
        period,  the owner or operator may petition  the Regional
        Administrator to discontinue or alter the monitoring
  i      I   "iiiiii.1!, "S'ii  ' .       •   •"• '  ''• ' ,• i'1 .)  •  i  '   • . ..... i, ' ';••  ..... 'is"' * ..... ' ' i ' II . , -    • •     '
        re(|tiirements ;  alternatively, under certain  circumstances,
                                    7^2

-------
the Regional Administrator may require an owner or operator
to continue monitoring beyond 30 years.  Revisions will also
be likely when the EPA provides more guidance and technical
engineering data on the kinds of monitoring appropriate
during post-closure;
Changes in annual routine maintenance, including changes
in the nature* and frequency of the activities required
(e.g., a more extensive erosion control program may be
required than originally anticipated);
Changes in activities required on an intermittent basis
or changes in the frequency of these activities (e.g., an
accelerated replanting schedule or more frequent replace-
ment of wells than anticipated);
Operating contingencies which occur during the life of the
facility or post-closure which a'ff'ect post-closure ac-
tivities (e.g., severe weather conditions affecting acti-
vities required for erosion control, cover maintenance,
or maintenance of diversion structures);
Changes in surrounding land use (e.g., if the population
density increased, the measures needed to maintain
facility security might change; .ground-water monitoring
program might be affected);
Changes in monitoring and maintenance technology; and
Modifications approved by the Regional Administrator; the
owner or operator may petition the Regional Administrator
to allow some or all of the requirements for post-closure
to be discontinued or altered before the post-closure period
is ended; any such changes can only be made after the
post-closure period begins and would constitute a revision
to the post-closure plan made during post-closure.
                          7-3

-------
                     e desirable  that either raise or lower  the  closure
     Post-closure cost estimates.   For example, the closure  cost  estimate
may"need to fie revised and  increased if partial closure schedules  are
   [•i11 '    •  .'.lit  ; lit 'i '•  *;: •   ";  J • ;	'. ..••• , . „'   - •   	',','.• :f["  ,, ,f R'XI :f .."• ,  ' 'is •
no1^  met  or if there is unexpected  accumulation of inventory  due  to
   i.  i   •• '    ;  ; Hi         ,   '    '"       ''     ''.v',1,1 'ป! ,ซi;i; Si'"  '' '•' 1;; • i '•; ',• i
temporary problems at the facility.   It is quite possible,  however,  that
the  cost estimate may need  to be revised downward.. A facility may have
verl larSe  inve,n^ory due to temporary start-up problems at  the time  the
cost,,estimate is first developed which is  later reduced to a more  normal
inventory.  In such a situation, revising the closure  cost estimate
downward would be reasonable.  It is  also  possible,  given the rapid
development in some types of hazardous  waste disposal,  that new technol-
   111111 '     ' '  11"1|l!1 "  " "  	      ' ' '     ""   '            :„  !  , "::•:	" ' !i ' "
ogies may offermuch less expensive means  of carrying out certain
activities  than are now envisioned.   This  would also  be a legitimate
cause for revisions of the plan and cost estimate.
                                   7-4

-------
                    8.0  ADJUSTING THE COST ESTIMATES
                           TO ACCOUNT FOR INFLATION

     Subpart H of the,Interim Status Standards requires that both the
closure and post-closure cost estimates be adjusted annually for infla-
tion.  This adjustment is to take place on the anniversary of the
effective date'of the regulations, November 19, 1980.  Although owners
or operators of land disposal facilities are not required to have
estimates available until May 1981 (six months from the effective date
of these regulations), all owners or operators are required to adjust
their estimates beginning in November 1981 and annually thereafter.  •
Adjustments of the post-closure cost estimate for inflation need not
take place once the facility is closed.

     Data for calculating the inflation adjustment factor must be ob-
tained from the "...annual Implicit Price Deflator for Gross National
Product as published by the U.S. Department of Commerce."*  This price
deflator is published in the Survey of Current Business, a U.S. Depart-
ment of Commerce, Bureau of Economic Analysis, publication, and in
Economic Indicators, a Council of Economic Advisors publication.  These
documents are published monthly and subscriptions may be obtained from
Superintendent of Documents, U.S. Government Printing Office,
Washington, D.C., 20402.  This information also may be obtained by
calling the Bureau of Economic Analysis, U.S. Department of Commerce.

     The GNP price deflator was chosen as an appropriate inflation index
and is more accurate than the more readily available Consumer Price
Index and Wholesale Price Index.  However, it is not as widely published
as the other two indices.  Thus, the typical hazardous waste facility
owner or operator, in the normal course of his business, will not have
data on the implicit price deflator for GNP or copies of the Survey of
Current Business or Economic Indicators.  Copies of these publications
*EPA Interim Status Standards, 40 CFR ง265.142(c)

                                   8-1

-------
    also may  not be readily available in small libraries  to which the
    owner  or  operator might have easy access.  As  a  result, the EPA
        :"::!:"':   .  '.	:'  "':""        •   :     '. .    . • '   ":'  	: 	 '  '  "': "  '.''-' t:  .  .  '" '
    Regional  personnel must have available the most  recent editions of
    theSurvey of Current Business or Economic indicators,and provide the
    necessary adjustment factor to owners or operators  who telephone or
    write  for this Information.
         Table 8-1  shows a sample of the section in  the  Survey of Current
    Business in which the GNP implicit price deflator may  be  found.   The
    table is constructed to show how this section might  appear on 19 Novem-
    ber 1981, the  "first anniversary of the effective date of the regula-
                                                                  i
    tion."  The numbers shown are hypothetical, as this  guidance  document is
        li,      :   'iii; ii,  filjijiillilll!1 	  '  : 	• !  • 'il"1',  '    / ' v  ,  '! ' ;' /  '"  v j;l|l|li:l '' 'TIS i;1:1! ': /s i;, hf",, i, :,|, :   v  " ^',
    being written in  May 1980.   The implicit price deflator to be used is
    the first for which numbers appear, i.e., the one labeled Gross  National
                                                        /          i
    Product as underlined in Table 8-1.  The note "Index,  1972=100"  may be
    ignored.  The method of calculating the inflation adjustment  factor
    required by the regulation makes the index year  chosen and changes in
        li-	' !	>•[!> .' iaill  KJi'ii r     |.' , , '.'   ,  .,    , "' ~ I'".  ..' . •'•.   .'i1  • 'i,11'! Jillilf1,- 'tf'rt '   ,,'i ':L j ',:• '", !'  t ;', i,
    the index year  irrelevant.   The regulation states:
                                                    /  ,           '
         "The inflation factor must be calculated by dividing the
         latest published annual Deflator by the Deflator  for the
         previous year."*

    GNP deflators are normally developed both quarterly  and annually.  The
    regulation requires the use of the deflator listed in  the column headed
    "annual totals."   The quarterly data should be ignored entirely.  The
    calculation of  the inflation adjustment factor should  use,  for the
    latest published  annual implicit price deflator, the deflator for 1980
    (circled in the chart).  The deflator for the previous year will then be
    EPA Interim  Status Standards, 40 CFR ง265.142(c).
                                         8-2
	ill it	Ill III In    i   Hill  ill	I

-------
                       TABLE 8-1
HYPOTHETICAL SAMPLE PAGE OF SURVEY OF CURRENT BUSINESS


1978
1979
1980
Annual Total
1978
III
IV
1979
I
II
III
IV
I960
I
II
III
IV
1981
I
GKNBKAL BUS1NUSS INDICATORS— Quarterly Series—Continued
NATIONAL INCOHK AND 1*KODUCT— Con."
Quarterly Data Seasonally Adjusted
implicit price deflators;
Cross National product 	 Index, 1972-100....
I'orsoiml consunipt Jon expenditures 	 do....


Grotin private domestic investment:






152.05
(Bป
(nsTu)
153.45
156.68
160.22
163.81
167.20
__
170.74
170.74
175.34
______
176.61
177.41
	 —
178.31
II 1 III

_ ._;_
179.46
_-;-___
181.56

-------
                                             >"' Hi*1':!!	' I!,;!	i	:<:	ISIl , -II	i:t'*ttm	IIUWMKIVB!*IB III'1"!! ilfS'l-.ซSN '""	il'"!:!"! "i' '''('I'll!'": "" S	I'll: IF
          the deflator for 1979 (also  circled in the chart:).*   Using the example

          provided,  the inflation adjustment factor is then calculated as the

          annual  implicit GNP deflator for 1980 divided by the  annual implicit GNP

          deflator  for 1979, as follows:
           ||: i ;   • '  '•:?!• 5f(j|    ..... - , ..... i,. ......... , . . .,    ..••< .........  -    • ' -, •, ;. ' ..... : i";  , , , ;,  -.j,,;;
           ;:';• i .   ;   "i '" "  .       :;     .     175.13          " ,"""   ', '  [
           :>;.   .  ••  . ;" ";!     •'  : .....     . '•••  165.50'   ' " ..... ' ;;;  ' "."  ;

          resulting in an inflation  adjustment factor of 1.053.  This number is

          then multiplied by the last  cost estimate to obtain the new current cost

          estimate.  These numbers are hypothetical and do not  represent actual

               data; they are presented solely to illustrate how to  use the Survey
          of Current Business to make  the  necessary calculation.
          *The GNP implicit  price deflator for a given year may be subject  to
          revision.  If the  figure cited in a previous issue is different from
          the figurecited for the samequarter in  the currentissue, the owner
          or operator should use the current figure.   If the owner or operator
          is requesting this information by telephone, he should ask for the GNP
          implicit price  deflator for the previous  year and for the year prior
          to the previous year.
                                              8-4
::•ป. •
           ii	:
                 '• '.;	•!!  ill!

-------
                        9.0  SAMPLE COST ESTIMATES

 9.1  INTRODUCTION

      This section provides samples of cost estimates for closure of
 surface impoundments, land treatment facilities, landfills, inciner-
 ators,  and a multiple process facility with tanks and small surface
 impoundments.  A sample post-closure cost  estimate for landfills is also
 provided.  The purpose of these sample cost estimates is to illustrate
 the concepts involved in a proper cost estimate and suitable formats
 which might be employed.   However, neither the cost estimates in total
 nor the unit costs are designed to be applicable to any specific
 facility.   Neither the total, costs.nor the unit costs used  in
 these cost  estimates  should be  considered  targets  when the  owner or
 operator prepares his  own cost  estimate.

      The cost estimates are prepared  in the form of a series  of  work-
 sheets.   This was considered the  simplest  mechanism for providing a
 careful,  easily checked cost estimate.  In the  sample cost  estimates
 given,  each worksheet  is  accompanied  by an explanation of each item on
 the worksheet.  These  explanations are designed  to  help  indicate  how the
worksheet was  developed.   Explanations of  this  type  would not be  appro-
priate in the cost estimate  prepared by the owner or  operator.   Instead,
the owner or  operator  would  include, for each item  in  the cost estimate,
reference to  the appropriate section of the closure or post-closure plan
as applicable, and any necessary documentation as to  the accuracy of
specific unit costs.
                                9-1

-------
   'i'JiiTI	' 9 IW" ''III11 ill'1"!' '
"IS
                               EXAMPLE - SURFACE IMPOUNDMENTS
     Sludge  from an industrial wastewater treatment plant is pumped to
a four-acre  surface impoundment for  stabilization.  It is assumed that
at the time  of  closure, the contents of  the impoundment will measure a
depth of 3 feet; this material will  be 90 percent water and 10  percent
  J.',,M' " •'	if'irif	!  Hi, ;,!• 	.•  ,,  •  :;i	 I  '  • '  :•".. ป'•,••     • •: •..$•<	•'••,' •• , • ;; '.ป, .. T*,"K!', ••:'". '"   :<"•'•::
solidsludges.   The total depth of the impoundment will be 5 feet
(allowing 2  feet of freeboard above  the  surface of the liquids).   It
is further assumed that all necessary equipment required to complete
closure wilฃhave to be rented, as none  is available on-site  (the
costs of equipment rental and manpower will be factored into the unit
  I	  '     I, "'.I ' 1   ,;.i'|l||J!  , ,  ' '  ' " I1 "II t j,     l ; | 	   ^f   ;,    |1| n||, , ii, .ji^  .-  ' | i '  I '   '   ' ' , ' „
cost estimates  for various operations).   The costs of closure are
developed for two options: 1) completely disposing of wastes on-site,
and 2) removingall hazardous materials  from the facility prior to
         closure.
                                                                       (••„;
                                                                                         13!  !.  ,  'ป!!
           I;1':; !•  !"    ••';,
            'i	    t  • " ''*?
           'i	   •: I,
                                              9-2
                                                                     ,!.='  	
                                                                              1! .; 	
                                                                                 *! "f
                                                                                 ป	, 'i'

-------
              SAMPLE CLOSURE COST ESTIMATING WORKSHEETS:
         SURFACE IMPOUNDMENTS IN WHICH WASTES REMAIN AT CLOSURE

A.   Removing Free Liquid and Decontaminating the Facility
     In this case, it is assumed that free liquids can be removed by
evaporation.  Alternative possibilities that might be necessary and would
result in somewhat different cost estimates are the transporting of free
liquids to an off-site TSDF and the disposing of free liquids into surface
waters after suitable treatment, either through a treatment facility already
in place or a package treatment facility.  For this example, all contam-
inated soil is disposed of in the impoundment; therefore, no additional
costs are associated with decontaminating the soil.
      1.  Method used:  As noted above, the method used for removing the
free liquid is evaporation.
      2. * Time required to evaporate liquid: . The calculations to justify
this time would be taken from the closure plan.  It is assumed that 70 days
would be required for evaporation of free liquids.
      3.  Cost of routine operations per day:  This includes the cost of
inspecting the facility required once a week and any minor maintenance
work that would need to be done as a result of these inspections.
      4.  Cost of maintenance during evaporation (Line 2 x Line 3):  Cost
of routine operations at $10 per day times 70 days results in a total cost
of maintenance of $700.
      5.  Volume of remaining sludge:  The volume of the remaining sludge
is given as 1936 cu. yds. based on the initial assumption that the liquid
in the pond is 10 percent sludge.
      6.  Source of sorbent materials:  In this case, the sludge is to be
solidified and buried on-site in the surface impoundment.  As a result,
sorbent materials are needed. • It is assumed, for the example, that sorbent
materials must be purchased off-site.
      7.  Cost of sorbent materials:  Assume that sorbent materials (e.g.,
cement kiln dusts) are needed on a one-to-one ratio to the sludge and must
be purchased with a delivered cost of $3.25 per cu. yd.  The total cost
is $6,292.                                   ;
      8.  Unit cost of mixing and stabilization:  The unit cost of mixing
sorbent material with sludge is assumed to be $1.60 per cu. yd.
                                   9-3

-------
              ?'   Cost of *^ing  and stabmzation:   |his is calculated as 1936  cu.
         yda" ฐf s*udge plus 1936 cu-  ^s. of sorbent material, for a total of 3872
         CU! yds>  ^is 1s multiPliedtimes ,.$1..60  per cu. yd., to  give a total cost
       .  of	$6,195.  MI	      .  	n|	   |T_'	

             10. Total cost of removing free liquids  and sludge stabilization
       •  .,   I	  ,.J!  """' .,' "	SfB, 5i	I'   .  ';' .  'A	V  .•  •'.•:'.'• .• "  ",>,  ,,...'(	',ป.;•.	i..'/.sii,; •..ซ*•.•. i	.'••iNKiitMr.;;•*,;• •:• .*••;•;	   :i,   •
        (Line 4 -f- Line 7  + Line 9):  The sum of the above costs is  $13,187.
             11. Decontaminate equipment:  The assumed  costs for decontaminating
       . •  . ,.  ":";,; ;,   ,,  .,,"",;,,;.' ,;;;	;,;,, ". •  ;•" ,„"' . •.	 „.' 	 "'     ;  ...;,„;,  „„,,'	ฐ ...;:	  :,;.;:,,'r|,',;,:',. ,::.• ,'„;	":  .•,.,   ...
       {equipment is $500.
             12. Decontaminate and  flush any pumps or liquid lines:   The assumed
        costs for decontaminating equipment is $2000.
             13. Disposing or treating residues from  decontamination:  Assume that
            f 'it ,  , |M   : ::,K i .:":!   ...  "' , i	N	 iii.."''	 iฐ...  •• , u; .I."1: - . ..... „ ^ „,; •,  ir. „;, i,	 	i	Mr,,, ; ',1,,'!,„!	;.;„„! 4; in.; , ...'., v    '• „ .'. ;„  '
        the costs for  disposing or  treating liquids and residues from the above
        decontamination processes is $1000.
             14. Total costs of all  activities on Worksheet: A (Line 10 + Line 11 +
       . "    I";      "1"1 :v;"illi!	.,$ '    "'    ;•"''•. T  :  •. .  ,; j'1'  ',  • ': :   '.',;;ป:,/" !,"'i 't'-vli ;ll,,.lS!i: I'.',,/ ui ,.',(: j,	,, .  ,f ..,'.'•      ; ! i
      '[Line	12 + Line 13) :  The  sum of  these, activities  is $16,687.
       B.     Placing Final Cap
             1.  Area to be capped:  The area directly  requiring a cap  is  4 acres
       (19,360 sq. yds.)   In addition,  it is assumed that an additional  acre of
       land area (4840 sq. yds.) surrounding the impoundment, containing  dikes,
       etc.7 will require vegetation  and, therefore, must undergo some prepara-
     1 " tionV
   •i;   ;'•   ,  ; ; ,    •   •  ..... ;  ;•,,   . ,    ;   ;,'il  ;  ,     . .,.  .    , ,   '      ''^' ', .'"' ,; ,"."} ',, .  : •. ' .....  '; ,. .    :
             2.  Required  impermeable  material:  It is  assumed that  25,813  cu. yds.
       of impermeable material will be  required (19,360 sq. yds. x  4 ft.  depth).
     j  ,!     ll'W'i I '   ' - I1!,, "ill. n 'i.|, .HLlr ''tV'lllll ,1 .1 'I 'i i  Ml .....  ' ......... '•'.,. I. . if  ' il,' ป 1, ' ,,l|, .,„ „ , ,  „, ซ;;  'ป ,  ,| ' II,  ..... ,, ,'.„,' ....... ', ..J, .fl,," 1, Ji i|||| ' .liftj" ,!l I fl ' ,(' i , '..' / \ ,.(, ' |, I1. | f I  i „. Jn."  ,„ ..... ซ ,,,|  /   ,
             3.  Source of  impermeable material:  It is assumed that suitable
       impermeable material can be obtained through bulldozing dikes and  other
     ,  appxir'tenances ............ '6ri~s'ite.
     |  ;{     :';4.  Cost^ bf^jnaterial^:'  Since the material,,, is available  pn-site,  there
I;;11 .....    ' i!      "5.  Required  topsoil:  At  the sample  facility, it is assumed that 2 feet
        of  the topsoil wiH be required in order to ensure adequate cover so that
        roots of the vegetation will not penetrate the cap.  It is, therefore,
        assumed that 16,13'3 cu. yds. of topsoil (24,200 sq. yds. x 2/3 yd.  depth)
       ri'wilX ...... be required'."  '       '                          ........ ......
           j ...... 16.  Source  qf topsoil:  In this case, it  is assumed that  topsoil is
       •••  '  S.i     •' '• lift   "!J:;:; .. „   / .  i-'t", * ...... .•  v ,  " .......  • . i,    .;  ..:'..'• i1. :,  ;'ii:1;.-. ..... ' .', " ..... i  >, I ' ':'•'  ",  .;. '     ...
        available on-site at a relatively short haul.
           '  ..... ................           9-4 .....       .......... ' .......

-------
      7.  Cost of topsoil:   Since  the  topsail ฑs available on-site, there
 will be no cost.
      8.  Cost per  cubic yard for  hauling,  compacting and grading:
 It is assumed in this case that the unit  cost of those services  is
'$1.60.
      9.  Cost of placing impermeable  portion of cap  (Line 2 x  Line
 8):  The result  of  these assumptions is  that the cost of the cap
 in.place (with suitable grading) is $41,301.  :
      10.  Cost  of  placing topsoil (Line 5  x Line 8):  The cost of
 placing the topsoil,  given the above assumptions, is $25,813.
      11.  Total cost of cap (Line 4 + Line 7 + Line 9 + Line 10):
 Summing the above elements,  the total  cost  for the capping operation
 is $67,114.

 C.    Planting Final  Vegetation
      1.  Area to be  vegetated:  The area to be vegetated is assumed to
 be 5 acres.                                   •                       .
      2.  Type of vegetation to be used:  The closure plan specifies that
 coarse field grass  (a mixture of rye grasses and Kentucky fescue) will
 'be employed, for  final vegetation.
      3.  Quantity  of seed per acre:  Based on discussions, with facility
 operators,  we assume  that 150  pounds of  seed will be used per acre.
      4.  Cost of seed per pound:   Calls to local suppliers determined
 that seed is available at $.50  per  pound.
      5.  Total  cost  of seed (Line  1 x Line 3 x Line 4):  Given the
 above assumptions,  the total cost  of seed will be $375.
      6.  Type of fertilizer to be  used:  Given the topsoil and
 climatic conditions at the sample  site,  10/10/10 fertilizer is
 assumed to be adequate.
      7.  Quantity  of fertilizer per acre:  Discussions with local
 suppliers indicated that  .25  tons per acre would be a reasonable
 fertilizer application rate.
      8.  Cost of fertilizer  per ton:   Calls to local suppliers determined
 that fertilizer  is available  for $200 per ton.:
      9.  Total  cost  of  fertilizer  (Line 1 x Line 7 x Line 8):  Given
 the above assumptions,  the total cost of fertilizer will be $250.
                                    9-5

-------
                                                           i|lllllllhili|li, kni.ll'ULI.I.IIIPLdl'jilillliil!!/!
                                                                  '
         10>   Cฐ;:S*:,Of so^ Preparation  per acre:   Soil preparation, including
        ^^^.^^tate?* -is Assumed to be $135 per acre (including
  Equipment	rental,costs).

         ^Total cฐst of Preparing soil (Line  1 x Line 10):  The total cost
  |f P*e^aSjfeS..	soil ^exp^ud^Lng materials)  is  assunied	to bft,,^675,,   ,'
  7: ,? ?;:?*?::-	TCli^,;per acrf for ?eed*nS:   Ifc is .assumed	that^seeding the
  W1^	S&S.Sri  cฐ,st ง200 per acre  (including  equipment  rental costs).
        13.  Total  cost of seeding (Line 1 x Line 12):   The total cost of
  seeding (excluding materials)  is assumed to be  $1000.

 , Ei:"l, M^ii^,^>^*>ฐฃ* nn^*xg.!., The cost, per	acre, of purchasing
  and applying a hay mulch  is  assumed to be $140.
        ^'   Tqlai cost of Aching (Line 1 x Line 14):" The  total  costs of
 mulching (including the costs  of hay) are assumed to be $700.
        16.   Total costs for vegetation (sum of Lines 5, 9, 11, 13, and  15):
 Total  cฐstsfor establishing vegetation are  $2950.

  lilillHU  ,,i  'ii ' i, ' I'ii/lS'ii,. -, ii'liiiiiiil • i i!1',''"' "iiilC  : •' ii'  C.  ' ป•    '' '',••, „, ","   ,i  • "ii '   i,|ii:.i!''',',: '• ' ",,i • If  i'1  '"ป!'   ,''.', ,  .. ' '',' ''' V
 D.  Ground-water Monitoring
  -."•'• Assume, that .clpsure of the surface impoundment will require a total
 ฐf 9ฐ days*   ^,order to, d?teri?i^e the maximum  possible ground-water
 ^itoring  cosjs,  the inp;st	.extensive monitoring  needed at  closure is
 a:,SV?ied',:,: „ :'^SU?ling„ that ^roun^a-ter Duality analyses  are  required
 annually and ground-water contamination analyses  are required  semi-
 annually, the most  expensive case is that in which both sets of  analyses
 are required during the  90-day  closure period.
       1"  NUmber ฐf wells ^aitored:   For the sample surface impoundment,
 it,, is  assumed jhat^ six, we.lls  would need .to be monitored. ' ' \
       2'  Number of samples^ per well:   One sample is taken per well  for
 both analyses*

  fe,; -  3'  *i5ai AUmbfr •*=. pf, ^ฐurs":;r:equired, for collecting the... sample:  It is
 assumed  that experience has shown  that  two hours are sufficient to gather
 samples  from each well.
      5.  Total  number of hours required  for  collecting the samples
 ^LSJ% 3. ฃ MS-e ft*   ?or six samples,  12 hours would b
-------
       6.   Number of hours required for preparing and delivering the sample:
 It is  assumed for the example that this can be done in two hours.
       7.   Person-hour costs  for collecting samples:  Assume that the fully-
 loaded costs  for labor required for sample collection,  preparation and
 delivery  averages $15 per hour.
       8.   Total  sample and collection costs ((Line 5 + Line 6)  x Line 7):
 This results  in  total sampling and collection costs of  $210.
       9.   Number of ground-water quality analyses:   One analysis must
 be made for each well sample,  for a total of six.
       10.  Number of ground-water contamination analyses:   One  analysis
 must be made  for each well sample,, for a total of  six.
       11.  Unit  cost of  ground-water quality analysis:   It  is assumed
 that the  cost  of an analysis  for the following parameters is $77 per
 sample:
                          Chloride -  $6.00  per sample
                          Iron -  $12.00  per sample
                          Manganese -  $12.00  per  sample
                          Phenols  -  $25.00  per sample
                          Sodium - $12.00 per sample
                          Sulfate  -  $10.00  per sample
       12.  Unit  cost of ground-water  contamination analyses:  It is
assumed that the  cost  of  an,analysis  for the  following parameters is
 $108 per sample:
                          pHi- $4.00 per sample
                          Specific Conductance - $4.00 per sample
                          Total Organic Carbon - $25.00 per sample
                         Total Organic Halogen - $75.00 per sample

      13.   Total ground-water quality analysis costs (Line 9 x Line 11):
For six samples at $77 per analysis, this yields a total cost of $462.
      14.   Total ground-water contamination analysis costs (Line 10 x
Line 12):   For six samples at $108 per analysis, this yields a total
cost of $648.
      15.   Total analyses costs (Line 13 + Line 14):  The total analyses
costs,  therefore, are $1,110.
                                   9-7

-------
       16.  Numfeer,of technical hours,for administratipn;  This includes all
• PR!1 'I1' il.
 time necessary to administer and report the data from the analysis and is
 estimated as eight hours.
       17.  Person-hour technical costs:  The fully- loaded cost required
 for this work is assumed to be $30 per hour.
       18.  Total technical costs for administration .(Line 16 x Line 17):
 Given the above assumptions, total costs for administering the tests are
 assumed to be $240.
ii. ....... in. ..... • , ........ v ..... ; "yiiii - ;J  , . :,  .....  ;-,   • .    ..... ,  . ,    ,  (| ...... ,/ i i   •• ... • _;> i ..... I ..... -
       19.  Number of clerical hours:  Assume for this cas.e that five hours
 of clerical time are required to produce the necessary reports.
       20.    erspn-hour clerical costs:  Assume the .fjujLly- loaded costs for
 clerical work are $8 per hour.
                                                            i
       21.   Total clerical costs (Line 19 x Line 20):  Given the above
                                                            i
 assumptions, the total clerical costs are $40.
       22.   Total administrative costs (Line 18 + Line 21):  The sum of
 technical  and clerical costs are then $280.
       23.   Monitoring equipment maintenance:  It is assumed that an
 average of $150 is required for a 90-day period to ensure adequate
 maintenance of monitoring equipment and wells.
       24.  'Total monitoring costs (Sum of Lines 8, 15, 22, and 23):
 Total monitoring costs, excluding administration and contingencies, are
 then $1750.

 E.   Fence  Maintenance
       In this case, it is assumed that the area to be enclosed is 5 acres
 (24,200 sq.  yd*)*  Assuming that the site is square, each side is 156
 yards.  The perimeter of the site is then 624 yards.
       1.  Length of fence to be replaced:  Since this facility is to retain
 hazardous  compounds, the integrity of its security fence is important.
 Our estimate is that 10% of the existing perimeter security fence will
                                                            !
 have to be replaced due to wear and corrosion.
       2.  Unit cost of replacing fence:  The security fence is a galvanized
  Mi  '    '   III I   I     11 "  I  • ,    .ii'. .....   ,:„    , -"- " ....... .:  *i, ..... I", ... , I • I   ,', 1  ...
 6-Ioqt high chain link fence made of #9 wire.  The installed unit cost
 of  replacement sections is $13.06 per linear foot.
                                    9-8

-------
       3.  Total  cost  of replacing fence (Line 1 x Line 2):
The  cost  of  replacing the damaged fence sections is the product of the
length of fencing needing replacement  and the unit cost of  replacing
the  fence, for a total of  $2429.

F.     Professional Certification
       1.  Number of person-hours  required for inspections:   It  is  assumed
that 80 hours are required for periodically  inspecting all  aspects of
closure of the surface impoundment.
       2.  Cost per person-hour:   In this  case,  assume  that  a registered
independent  professional engineer may  be  hired  at  a cost of $75  per hour.
       3.  Total  costs  of independent professional  engineer's  time  (Line
1 x Line  2):  This yields  a total cost of $6000 for the independent
professional engineer.
       4..  Number of technical hours required  for administrative  duties:
Assume that  eight hours are required from the owner's  or operator's  staff
for administrative duties  connected with  employing  an  independent
professional engineer.
      5.  Person-hour  costs for technical administrative duties:   It is
assumed that the total fully-loaded .costs  for the owner's or  operator's staff
are $30 per hour.
      6.  Total  administrative costs for  technical  labor (Line 4 x Line
5):  Given the above assumptions, the  total administrative  costs for
technical labor are $240.                               ...
      7.  Number of clerical hours required for administrative duties:
Assume that five hours of clerical time are required for the necessary
typing and certification.,
      8.  Person-hour costs :for clerical administrative duties:   Fully-
loaded costs of clerical tijiie are assumed to be $8.
      9-.  Total administrative costs for clerical labor (Line 7, x Line 8) :
Given the above assumptions, total clerical costs are $40.
      10.   Total administrative costs  (Line 6 + Line 9):  Summing
technical and clerical labor,, the total administrative costs are $280.
      11.   Total certification costs (Line 3 +. Line 10):  The total costs
for certification,  including the engineer's fees and administrative costs,
is then $6280.

                                   9-9

-------
           G,    Total Coats Including Administration and Contingencies
                Items 1 through 6 give  the  costs  of all activities on each of the
           preceding worksheets.  'Line  "7 is the"total of Lines 1 through 6,
           $97,210.  "   "                           :  	  '	
                8.  Administration:  For administrative tasks, including taxes,
           insurance, and administration and supervision not included elsewhere,
           a total of 15 percent of total costs from Line 6 is used.
           si,,,', ii „  ,,   ,:.,!,'  f '5"!  pi'i ,    > „  ,i 'I'i'uS  '" \. ป  >,(. •• , :,:;",' I •   •  ,,A: „ • t   n, ./& \ .'•   | .,i ,iปf 'iiii I 	   . "..i.   ,!•ป''
           *1":  ,  9.	Contingencies:	A general "pro vis ion "for contingencies of 15
           percent of Line 6 has been included.
           ir:V,i  10. 	fotai 'costs of closure "(line 7 + Line 8 + Line 9):  The"
           estimated total costs for closing the  surface impoundment for the situation
            , ,     " 	  	         	                     n  in   	   	|
           in which all wastes remain in the impoundment are estimated  for the sample
           case to be $126,373.
Fill, . •,!
                                              9-10
                                                                             "'I

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes remain in impoundment)
                    WORKSHEET A - REMOVING FREE LIQUID
                    .AND DECONTAMINATING THE FACILITY
  1.
  2.
  3.
  4.

  5.
  6.
  7.

  8.
  9.
10.

11.
12.

13.

14.
 Method used
 Time required to evaporate liquid
 Cost of routine operations per day
 Cost of maintenance during evaporation
 (Line 2 x Line 3)
 Volume of remaining sludge
 Source of sorbent materials
 Cost of sorbent materdlals
 ($3.25/cu.  yd.;  1.1 ratio)
 Unit cost of  mixing
                   *
 Cost of mixing and  stabilization
                                   •a
 Total cost  of removing; free liquids and sludge
 stabilization (Line  4 + Line 7 + Line 9)
 Decontaminating  equipment
 Decontaminating and  flushing pumps and liquid
 liners
Disposing or  treating residues from
decontamination
Total costs of all activities
 (Line 10 + Line 11 + Line 12 + Line 13)
 Evaporation
 70 days
 $10
 $700

 1936  cu.  yds.
 Of f^-site
 $6292

 $1.60/cu. yd.
 $6195
 $13,187

 $500
 $2000

$1000

$16.687
                                   9-11

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes  remain in impoundment)
                        WORKSHEET	B'-" F'iNAL1 CAP	
 1.    Area to be capped
 2.    Require!  impermeable material (including
      provision for suitable slope)
 3.    Source of material
 4.    Cost of" material
 5.    Require!  tbpsoil
 6.    Source of topsoil
 7.    Cost of topsoil
 8.    Cost per  cu". yd. of hauling, compacting, and
      grading impermeable material
 9.    Cost of impermeable portion of cap
      (Line 2 x Line 8)
10.    Cost of placing topsoil (Line 5 x Line 8)
11.    Total cost of cap (Line 4 + Line 7 + Line 9 + Line 10)
 19,360 sq.  yds.
 25,813 cu.  yds.

 On-site
" 6
 16,133 cu.  yds.
 On-site
" o" "  '	":"
 $1.60

 $41,301

 $25,813
 $67.114
                                      9-12

-------
                            SURFACE IMPOUNDMENTS
                     (All wastes remain in impoundment)
                  WORKSHEET C - PLANTING  FINAL VEGETATION
  1.
  2.
  3.
  4.
  5.
  6.
  7.
  8.
  9.

1Q.

11.
12.
13.
14.
15.
16.
 Area to be vegetated
 Type of vegetation to be used
 Quantity of seed per acre
 Cost of seed per pound
 Total cost of seed (Line 1 x Line 3 x Line 4)
 Type of fertilizer to be used
 Quantity of fertilizer per acre
 Cost of fertilizer per ton
 Total cost of fertilizer (Line 1 x Line 7 x
 Line 8)
 Cost of.soil preparation per  acre (excluding
 materials)
 Total cost  of  preparing  soil  (Line 1 x Line 10)
 Cost  per acre  of seeding (excluding materials)
 Cost  of seeding (Line  1  x Line 12)
 Cost per acre  of mulching
Total mulching costs (Line 1 x Line 14)
Total costs for vegetation
 (Line 5 + Line 9 -f- Line 11 + Line 13 + Line 15)
 5 acres
 Coarse grass
 150 Ibs.
 $.50/lb.
 $375
 10/10/10
 .25 tons
 $200/tor
 $250

 $135

 $675
 $200
 $1000
 $140
$700

$2950
                                   9-13

-------
        SURFACE IMPOUNDMENTS
 (All wastes remain in impoundment)
WORKSHEET D - GRdUND-WA'TER MONITMllG
1.   Number  of wells  monitored
2.   Number  of samples per well
3.   Total number of  samples (Line 1 x Line 2)
4*	'' '' Number1'	of	hours' required for' collecting'"'"the
     sample  (per sample)
5.   Totalnumber of  hours required for collecting
     the samples (Line 3 x Line 4)
6.   Number  of hours  required for preparing and
  ;; , delivering'samples^  '       " ',        |    ' '  	^	
7.   Person-hour costs for collecting samples
8.   Total sampling and collection costs
      ((Line5+ Line 6) x Line 7)
9.   Numberof ground-water quality analyses
10.    Number of ground-water contamination  analyses
11.    Unit cost of ground-water quality  analysis
12.    Unit cost of ground-water contamination
      analysis
13.    Total ground-water quality  analysis  costs
  ""'"' '  (Line 9 x" Line  11)
14.   Total ground-water contamination analysis costs
      (Line 10x  Line 12)
15.   Total analyses  costs (Line  13 + Line 14)
16.   Number  of  technical  hours  for administration
      (e.g.,  reporting data to EPA)
17.   Person-hour technical costs
18.   Total  technical costs for administration
      (Line_16 x Line 17)
19.   Number of  clerical hours
20.   Person-hour clerical costs
21.   Total  clerical  costs (Line 19 x Line 20)
  :!!ป'?ซ•  111 „ ,, " ..  ..fci  '.Hij   . .  .'' • i • ••""",  •  •  •" .1 ' ,   •    " i1;. •-. ,  •'.   i"! ;
  ii',. 'i, ' ,     ,„ i vii	:!s!?!     '• ...      ,     '  ,•        : :• ""     \ '.•<•
                                     9-14
                                           6 wells
                                           1 sample
                                           6 samples
                                           2 hrs.
                                           12 hrs.
                                           2 hrs.
                                        :;i'  '"$15	
                                           $210
                                           6 analyses
                                           6 analyses
                                           $77
                                           $108
                                            $462

                                           1 $648

                                            $1110
                                            8 hrs.

                                           ! $30
                                            $240
                                         :,  ii •'•
                                        ""'  IL'5 hrs.

                                            $40

-------
WORKSHEET D (continued)

22.  Total administrative costs (Line 18 + Line 21)   $280
23.  Monitoring equipment maintenance                 $150
24.  Total monitoring costs                           $1750
     (Line 8 + Line 15 + Line 22 + Line 23)
                                9-15

-------
                          SURFACE IMPODNDMENTS
                   (All wastes relhain in impoundment)
                    WORKSHEET E - FENCE MAINTENANCE
1.   Length of fence  to be replaced
2.   Unitcost of  replacing fence
3.   Total cost  of replacing fence
     (Line 1 x Line 2)
186 feet
$13.06 /linear ft.
$242*9 	
          if".  rasl
                                                                             i is*,,', SJiv,!,.,,, '	i'3
                                    9-16

-------
                           SUBtfACE IMPOUNDMENTS
                     (All wasteis  remain in impoundment)
                 WORKSHEET F ~ PROFESSIONAL CERTIFICATION
 1.
 2.
 3.

 4.

 5.

 6.

 7.

 8.
 9.

10.
11.
Number of person-hours  required  for  inspections
Cost per person-hour
Total costs of  independesnt  professional engineer
certification   (Line  1  x Line 2)
Number of technical hours required for  administrative
                                             ป
duties
Person-hour costs for technical  administrative
duties
Total administrative costs  for technical labor
(Line 4 x Line 5)
Number of clerical hours required for administrative
duties                  ;
Person-hour costs for clerical administrative duties
Total administrative costs  for clerical labor
(Line 7 x Line 8)
Total administrative costs  (Line 6 + Line 9)
Total certification c~sts (Line 3 + Line 10)
80 hrs.
$75
$6000

8 hrs.

$30

$240

5 hrs.

$8
$40
                                      9-17

-------
                          SURFACE  IMPOUNDMENTS
III,:  •; .*••,„,'•;*• •;>ฃ  .   (All wastes remain in impoundment)
'•WORKSHEET	G - TOTAL" COSTS INCLUDING' ADMINIstRATlbll1"^" CC-NT*INGENCIES
1.
2.
3.
41.

5""t
INI1'1 ' *'
6.
I*
fillli'
8.
*-
10,
i, . i, '
n
Cost of removing free liquid and decontaminating
the surface and ancillary facilities (From Worksheet
Cost of final cap (From Worksheet B)
Cost of planting fdnal vegetation (From Worksheet C)
Cost of ground-water monitoring (From Worksheet D)

Cost of fence maintenance (From Worksheet E)
i' i1 	 ii"' ' .in mi i ,i ' • ' • 	 ' ','i:r ซ 	 'v •' ft • I.M " ' •' ,i ' .I, '!• • '• iiiii'i'1" iป I'll 11 • .iiiiir " ni::. , , 	 • i i i •
Cost of professional certification (From Worksheet F;
Total of 	 Line 1 through Line 6
",i, ', • ' . iiiijii , , ••: . , ";' ,: , •,•!"' • •.'.:'. "• • . • • • 	 :".• "• . v , i 	 ' !,• ': i I,/!.
Adminis tr at ion
Contingencies
Total costs of closure (Line 7 + Line 8 + Line 9)
,illh ?i , Si' iHIK , ,'!:!"|'|l|j!!| i,i' ' tf 	 ,.„,„'! ' ป',„,. !',,, ,„ , • •', , 	 j,, •, • ',„ ,. .; ,,,'., "."NiH'ijij!!! l",1 ," 'HUji.,!"!!!
$ 16
W
$ 67
$ 2
$ 1

$ 2
,
$ 6
$97
$ 14
$ 14
$126

,687
,114
,950
, 750

,'429
""' 	 • ' 'ii 'iiiji
,280
,210
,"581.50 	 :":
,581.50
,373 	
&:••• - 'i "J'J.!
„ ' . H, ' .,,. 	 i' l :.,"":i|
                                     9-18


-------
                SAMPLE CLOSURE COST ESTIMATING WORKSHEETS:
       SURFACE IMPOUNDMENTS FROM WHICH WASTES ARE REMOVED AT CLOSURE

 A.    Removing All Free Liquids and Sludge
      It is assumed in the sample case that free liquids will be removed
 through evaporation and that sludge will be placed in a tank truck and
 disposed off-site.   A variet3r of other options are available. For'removing
 free liquids, both transporting to an off-site TSDF and treating and
 discharging to surface waters are other options that could be used.   For
 removing sludge,  solidification could take place at the site, and the
 solidified sludge either disposed in an off-site landfill or in a landfill
 on-site,  if there was  one with interim status  or a permit on-site.
      1.   Method used:   As noted.above, it is  assumed in this case that
 evaporation is the  method used to remove free  liquids.
      2.   Time required to evaporate liquid:  Based on calculations  that •
 would be  shown in the  closure plan, it is assumed for the sample case that
 70 days would be  required to  evaporate liquid.
      3.   Cost of  routine operations per day:   This factor includes  the
 required weekly inspection of the surface impoundment and a minimum  allot-
 ment  for necessary  maintenance revealed by such inspections.  This is  esti-
 mated to be  $10 per day.
     4.  Cost  of maintenance  during evaporation (Line 2 x Line  3):   The
 total cost of maintenance  of  the  surface impoundment  is equal to  70  times
 $10 for a  total of  $700.
     5.  Estimated  volume  of  sludge:   Given the size  of the surface  impound-
 ment and the  assumption  of  10  percent  sludge, 1936  cu. yds.  of  sludge will
 remain after  evaporation of free  liquids.       :
     6.  Cost per cu. yd. of removing sludge off-site:  It is assumed
 that off-site removal of sludges can be obtained for $40 per cu. yd.  This
 cost takes into account the fact  that  the off-site TSDF facility will
have to mix and stabilize  the sludges,  and assumes  that they will, therefore,
 charge a premium for this service.
     7.  Removal costs per cu. yd.:  It  is assumed  for the sample facility
 that removal costs are $1.60 per cu. yd.  (including equipment rental).
                                   9-19

-------
     8.  Hauling costs per cu. yd. :   It is assumed that the nearest land-
fill is 20 miles away.  Unit costs of trucking the sludge from the impound-
  '•, ..... n ..... •*!:  ..... , ''fi iMKi1'!! ii'lJih]   i1  SI  ;   , " ..... ป•    .  " ........ • ,. ,L , , n ,   ....... ... ,,i, ...... ..... /, ....... .iin.,,' .'ii'ini, ...... „ i  ' i, ;, iปi| ,,:"•,• ,.,,.'.|,"  >.,ป, ........   . ,,.„, ...... ••
meiit" to the  landfili is assumed  to be $3/cu. yd., based on discussions
with trucking industry personnel.
     9.  total costs  (Per cu- ydซ) of disposal (Line 6 H- Line 7 + Line 8):
Total  costs  of off-site disposal are $44.60 per cu. yd.

  ll^'io. ..... " Cost oi 'removing . sludge  (Line  5  x Line'""9)": ........ Given these  assumptions,
the cost of removing sludge, is $86,346.
    11.  Total  costs (Line 4 + Line 10):   Total costs for removing free
 ' liir. .1 '  „ ii-.ii .  'a!1 .illi'.ii.  ' "'i mi, 1 1 ' ii   , I'll" ,,:",' l! :;'i,,,  ""  ฅ ' '!•,   • '' ป, iin  '•    ,„', ,   ! •ป ...... ,, ' .....  yiH1  ',|ซ i1 ! i|. „ " ' ,i ,, • ]„ 'il'i,, ' ' . :': •   ..,'.'":    ', n1!", ' ', !i; il
liquids and sludges is $87,046.

B.  Decontaminating the Facility
      1.   Surface area of contaminated soil:  It is assumed  that 19,360
sq. yds.  (the entire surface  area of the surface impoundment)  has contami-
nated soil.,'	            ,   ,              '	'	
      2.   Depth of removal:  It  is assumed in the sample  case that this soil
                                        •*                    ii
must  be  removed to a depth of 1 foot to ensure that no soil  contaminated
with  hazardous waste remains  in the surface impoundment.
  ii-i I  3. :?' Total "'voiume''to"''be removed""' (Line 1 x Line 2)":  'the  resulting total"'"'
volume to be removed is  6453  cu. yds.
      4.   Cost of removal per  cu. yd.:  The assumed cost  of removing soil is
$1.60 per cu. yd. (including  costs of renting equipment).
  161   5.   Total cost of removal  (Line 3 x Line 4):  The  resulting costs for
  IJiJF     '    ' Hi',,1"! ,'iu'Ui,! , r "'    ,  ,   :;• "",';;,     • • M ,;, if!  .,,  , ,  ;,„, ' Xim,1,1!!, . ",, '"!!, iJi"!1, . iini1".;1:.,!!. J|i,,i 'i":,11' ,' I Ifl!1!,, |i|	T •,,!,'": ' '',,"   ',,  ' , .„, " ,
the sample case of removing the contaminated soil are $10,325.
      6.   Cost"of hauling to off-site landfill per cu. yd.:   the assumed
hauling costs to an off-site  landfill for final' "2'is'posai"of ""the contaminated
  	   •  ,  .          .      	,   -       •     • ••   ,:•. - .,.	 ',	.,i(.   '. .-i, -	  ,. , ..-I-,.,;:    , .   • • 1
soil  are $3 per cu. yd.
      7.   Total cost of hauling  (Line 3 x Line 6):  The  resulting total
costs of hauling are $19,359.
  :" i  8.   Fee per cu. yd. for  disposal in off-site landfill:   It is assumed
  I'''	 , '"'      '"' || 'I'	"''' ™"       ,    	  n        i...     , • M. ป  i . i   r     mi I  11	i"  •  .     	
 that  the charge per cu.  yd.  for off-site disposal at  the chosen landfill
has been determined to be  $30 per cu. yd.
      9.   total cost of  disposal  (Line 3  x Line  8):  The total costs for
 disposal, excluding hauling and soil removal,  are then  $193,590.
                                    9-20

-------
    10.  Decontaminating equipment:   It is assumed that equipment can be
 decontaminated for $500.
    11.  Decontaminating and flushing pump and liquid lines:   Assume that
 this can be done at the sample facility for $2000.
    12.   Disposing or treating residues from decontamination:   It is
 assumed that residues resulting from the above decontamination steps
 must be disposed of at a  cost of $1000. .
    13.  Total costs (sum of Lines 5,  7,.9,  10,  11, and 12):  The total
 costs for decontaminating the surface and ancillary facilities
 are $226,744.

 C.   Ground-water Monitoring;
     Assume that  closure of the surface impoundment  will  require a  total
 of  90 days.   In  order to  determine the maximum possible  ground-water
 monitoring costs,  the moat extensive  monitoring needed during  closure  is
 assumed.   Assuming that ground-water  quality analyses  are required annually
 and ground-water contamination analyses are required  semi-annually,  the
 most expensive case is  that in which  both sets  of analyses are required
 during  the 90-day closure  period.
     1.  Number of  wells  monitored:  For the sample surface impoundment,  it
 is  assumed that  six wells would need  to be monitored.
     2.  Number of  samples per well:  One sample  is taken per well for
 both  analyses.             I
     3.  Total number of  samples  (Line  1  x Line 2):   Given the above
 assumptions, six  samples are required.
     4.  Number of  hours  required for collecting  the  sample:  It  is assumed
 that  experience has shown that  two hours are sufficient to gather samples
 from  each well.
    5.  Total number of hours required for collecting the samples:  (Line 3
 x Line  4):  For six samples, 12 hours would be required for collecting
 the samples.                         ,
    6. Number of hours required for preparing and delivering the samples:
 It is assumed for the example that experience has shown that this can
be done in two hours.
                                  9-21

-------
                                                                               :" ill*1?"'A1,ii1'!!,,1'!!"!:.I,ill"i
    5.   Person-hour costs for technical administrative duties:   It  is
assumed  that the total fully loaded costs for the owner's  or  operator's
staff  are $30	per hour.	 '	'	'	'
  :"	 6.   Total administrative" costs'''for''technical	Iab"6r":(Line  4  x Line  5):
 Given the above assumptions, the total administrative costs  for  technical
		' "    	' '	[	-	;,	I ' t , i     .       \   \
 labor are $240.
     7,  Number of clerical hours required  for  administrative duties:  Assume
that five hours of clerical  time are  required for the necessary typing and
certifications.
     8.  Person-hour  costs for  clerical administrative duties:  Fully-loaded
costs of clerical time  areassumed  to be $8.
     9.  Total  administrative costs for clerical labor (Line 7 x Line 8):
G|ven the "aBove assumptions,  total  clerical cost's are $40.
    10.  Total  administrative costs (Line 6 + Line 9):  Summing technical
arid clerical labor,  the total administrative costs are $280.
    11.  Total  certification costs  (Line 3 + Line 10):  The  total costs  for
certification,	including the'engineer's fees and administrative costs, is
  	:	'	  II 	       	
tfien  $4780.
E.   Total  Costs of Closure Including Administration and Contingencies
     Items  1 through 4 summarize the costs of the activities  on  each  of
the previous worksheets.
     5.   Total of Lines 1 through 4:  The totalcosts  for'the activities
listed in Lines l through 4 are $320,350.
  [. ,. ;• ฃ  '''A^nistralion:  '"The cost's for "administration,	which"'includes
insurance,  taxes, and supervision and administration not included elsewhere,
are  assumed to be 15 percent of Line 5.
      7.   Contingencies:  A provision for contingencies of  15  percent, of
Line 5 has been included.
  ; 	  8.  Total costs of closure  (Line 5'+ Line  6 +  Line 7)'":  the total
 costs  of closure including administration and contingencies for the sample
 surface impoundment, in the  case where  all wastes  are  removed from the
  HIM1 i	T" ''  ,|" 'I '! tf' I,1,'1 !,in&'l  JllilliPI'l  • ', V  •' !	,	•',.!', 11"          '''    '
  illliil'i i, ' I '  .i,,i 'I'll' i'1! liiiillH I"  lli'ltUi'l	• V * 'L jf'	'	
 impoundment,  are $41o,
                                :,  '-;;9-22 „
                                                        	"1-i
.. IP 1	

-------
     7.  Person-hour costs  for collecting samples:   Assume that the fully-
 loaded  costs  for  labor  required for collecting,  preparing and delivering
 the  samples averages $15  per hour.
     8.  Total  sample and collection  costs ((Line  5  + Line 6)  x Line 7):
 This results  in total sampling  and  collection costs of  $210.
     9.  Number of  ground-water quality analyses:  One analysis must be
 made for each well sample, for  a  total  of  six.
   10.  Number of  ground-water contamination analyses:   One analysis must
 be made for each  well sample, for a total  of  six.
   11.  Unit cost  of ground-water  quality analyses:   It  is assumed
 that the cost of  an analysis  for  the following parameters is  $77  per
 sample.
                        Chloride - $6.00  per sample
                        Iron - $12.00 per sample
                        Manganese -  $12.00 per sample
                        Phenols  - $25.00  per sample
                        Sodium - $12.00 per sample
                        Sulfate  - $10.00  per sample
   12.  Unit cost  of  ground-water contamination analysis:  It  is assumed
 the  cost of an analysis for the following parameters is  $108  per
 sample.
                        pH - $4.00 per sample
                        Specific Conductance - $4.00  per  sample
                        Total Organic Carbon - $25 per sample
                       Total Organic Halogen - $75.00 per sample
   13. Total ground-water quality analysis costs (Line 9 x Line 11):
 For  six samples at $77 per analysis, this yields a total cost of $462.
   14. Total ground-water contamination analysis costs (Line 10 x
Line 12):   For six samples at $108 per analysis,  this yields a total
cost of $648.
   15. Total analyses costs (Line 13 + Line 14):   The total analyses
costs, therefore,  are $1110,,
   16. Number of technical hours for administration:  This includes
all time necessary to administer and report the data from the analysis
and  is estimated as eight hours.
                                  9-23

-------
   17.  Person-hour technical  costs:   The fully-loaded cost required for
this ....... work ..... is assumed, .to ......... be  $30 per hour.
   18.  Total technical costs  for administration (Line 16  x Line 17):
                                           1   '   '          I
Given the above assumptions, total costs  for  administering the tests are
assumed to be $240.
  ;.-•' ;19. "'^ ..... ^..Number^'of „ .clerical "hours :  . Assume .. for .."this , case " tfoat .. "five' hours
of clerical time are required  to produce  the  necessary reports.
   20.  Person-hour clerical costs:  Assume the fully-loaded costs for
I  I  I   I I  I III I.  'III    .     I     ........ I1 I "• '  ' '••' :        ....... I      'ii' '• •'
clerical work are  $8 per hour.
   21.  Total clerical costs (Line 19  x Line  20) :   Given  the above
assumptions, the total clerical costs  are $40.
   22.  Total administrative costs (Line  18 + Line  21):  The sum of
technical and clerical costs are then  $280.
   23.  Monitoring equipment maintenance:   It is assumed  that  an average
of $150 is required for a 90-day period to ensure adequate maintenance
of monitoring equipment and wells.
   24.  Total monitoring costs (sum  of Lines  8, 15,  22, and 23):  Total
monitoring costs,  excluding administration and  contingencies,  are then
•' ''iK v 
-------
                           SURFACE IMPOUNDMENTS
                    (All wastes removed from impoundment)
             WORKSHEET A - REMOVING ALL FREE LIQUIDS AND SLUDGE
 1.   Method used                                              Evaporation
 2.   Time required to evaporate liquid                        70 days
 3.  . Cost of routine operations per day                       $10
 4.   Cost of maintenance during evaporation                  '$700
      (Line 2 x Line 3)                                    .
 5.   Estimated volume of sludge                               1936 cu. yds.
 6.   Cost of  removing sludge off-site per cu.  yd.             $49
 7.   Removal costs per cu. yd.                        ;        $1.60
 8.   Hauling costs per cu. yd.                                $3.00
 9.   Total costs per cu. yd. of disposal                      $44.60
      (Line 6 + Line 7 + Line 8)
10.   Costs of removing sludge (Line 5 x Line 9)               $86,346
11.   Total costs (Line 4 + Line 10)                   '        $87,046
                                     9-25

-------
                                    SURFACE IMPOUNDMENTS
                           (All wastes  removed from impoundment)
             WORKSHEET B - DECONTAMINATING SURFACE ANDANCILLARY FACILITIES
           1.    Surface area of contaminated soil
           2.    Depth of removal
           3.    Total volume to be removed (Line 1 x Line 2)
           4.    Cost of removal per  cu.  yd.
           5.    Total cost of removal  (Line 3 x Line 4)
            i;;'!;    'U!" ' ':	illllli Hill" , "!,.),• :. •*,?ป.•. 'i ••;•'.' .•,.•	"'•,•,:  ,!,:ซ'.   •, Vซ. >.. •.  ; .;•,	.;
           6S    Cps,t of hauling to off-site landfill per cu. yd.
           7.    total cost'o'f hauling  (Line 3 x Line 6)
           8.    Fee per cu. yd. for  disposing in off-site landfill
           9.    Totalcost of disposal (Line 3 x Line 8)
          10.    Decontaminating equipment
          11.    Decontaminating and  flushing pump and liquid lines
          12.    Disposing of residues  from decontamination
          13.    Total costs (sum of  Lines  5, 7,  9, 10, 11, and
            :r  , 12)                                         '   '
! (Hi/;  : ' it
                                              9-26

-------
                           SURFACE  IMPOUNDMENTS
                   (All wastes removed  from impoundment)
                  WORKSHEET C - GROUND-WATER MONITORING
 1.   Number of wells monitored                           6 wells
 2.   Number of samples per well                          1 sample
 3.   Total number of samples  (Line 1 x Line 2)           6 samples
 4.   Number of hours required for collecting the         2 hrs.
      sample (per sample)
 5.   Total number of hours required to collect           12 hrs.
      the samples (Line 3 x Line 4)
 6.   Number of hours required for preparing and          2 hrs.
      delivering samples
 7.   Person—hour costs for collecting samples            $15
 8.   Total sampling, and collection costs ((Line          $210
      5 + Lin6 6) x Line 7)
 9.   Number of ground-water quality analyses             6 analyses
10.   Number of ground-water contamination analyses       6 analyses
11.   Unit cost of ground-water quality analysis          $77
12.   Unit cost of ground-water contamination analysis    $108
13.   Total ground-water quality analysis costs           $462
      (Line 9 x Line 11)
14.   Total ground-water contamination analysis costs     $648
      CLine 10 x Line 12)
15.   Total analyses costs (Line 13 + Line 14)            $1110
16.   Number of technical hours for administration        8 hrs.
      (e.g., reporting data to EPA)
17,   Person-hour technical costs                         $30
18.   Total technical costs for administration            $240
      (Line 16 x Line 17)
19.   Number of clerical hours                            5 hours
20.   Person-hour clerical costs                          $8
21.   Total clerical costs (Line 19 x Line 20)            $40
22.   Total administrative costs (Line 18 4- Line 21)      $280
                                   9-27

-------
                                                                                             I	Ill
23.    Monitoring  equipment maintenance

24.    Total monitoring  costs
•i  SAiT	  Will!1 'HIM" ,  "  "	- :  /Nil  :ii, ,  i ;,•• •  ..,,>.:ซ ;• , •.•l:.	!'
       (Line 8 + Line 15  + Line  22 + Line  23)
     $150
      $1750
S'-'/i: 'r ii-
                                                            -SS'r'i
             na  ;•:'*
                                                       .•  >• ',"ซ	"K >;  >•'.•• i J  I
                                         9-28

-------
                           SURFACE IMPOUNDMENTS
                   (All wastes removed from impoundment)
                 WORKSHEET D - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required for inspections          60 hrs,
 2.   Cost per person-hour                                     $75
 3.   Total costs of independent professional engineer         $4500
      certification (Line 1 x Line 2)
 4.   Number of technical hours required for administrative    8 hrs.
      duties
 5.   Person-hour costs for technical administrative duties    $30
 6.   Total administrative costs for technical labor           $240
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative     5 hrs.
      duties
 8.   Person-hour costs for clerical administrative duties     $8
 9.   Total administrative costs for clerical labor            $40
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)             $280
11.   Total certification costs (Line 3 + Line 10)             $4780
                                     9-29

-------
                                       SURFACE  IMPOUNDMENTS
                              (All wastes removed from impoundment)
                         WORKSHEET E - TOTAL COSTS OF CLOSURE INCLUDING
                                 ADMINISTRATION  AND CONTINGENCIES

II  III  I  I     .  li'lil'l li, '   i :ป 	illPillllllll,1 .ilKi'lifi „    • „ i   ,'	 ' 	lit' 'i' '•	iป""" 
-------
9.3                EXAMPLE - LAND TREATMENT  FACILITIES

     The following cost estimates were developed  for  a  land  treatment
•facility consisting of 50 acres  of active  fields  for  the"processing  of
biodegradable hazardous waste.   In addition  to  the  disposal  fields,  the
land treatment facility is equipped with a surface  impoundment  for waste
storage and a separate-surface impoundment for  collecting run-off water.
     The land treatment facility is designed to receive organic industrial
sludge of high liquids content.  This waste  is  applied  to the land treat-
ment fields at an application r.ate of 100  wet tons/acre (solids applica-
tion rate ~5 tons/acre).
     Waste received by the facility is stored in  a  lined surface impound-
ment.  The surface impoundment is 5 feet deep (3  feet of waste  and 2 feet
of freeboard) and has a surface  area of 1.23 acres.   This corresponds to
a waste holding capacity of 160,700 cubic  feet.  A  pump system  is avail-
able for transferring this liquid waste to the  tank trucks.
     The waste from the waste storage surface impoundment is spread  on
the fields using tank trucks.  During the  first 90  days of the  planned
closure period, all of the waste inventory will be  disposed  on  the fields.
This disposal will require one application to the field.   Later in the
closure period, run-off water from the separate run-off water surface
impoundment will be disposed of  in the same  manner.   This run-off water
will have a very low concentration of hazardous wastes.  Disking of  the
fields will be conducted shortly after each  spreading to mix the waste
with the soil and a second disking will be done two to  three weeks after
each spreading.  Periodic disking will continue on  a  bimonthly  basis
thereafter.                 :
     During this prolonged closure period, the  surface  impoundments  will
be closed as well.  Each of the  two surface  impoundments has its own
closure plan as shown elsewhere  in this guidance  document.   Therefore,
the costs of decommissioning the surface impoundments are not computed
in this example.•
                                    9-31

-------
                           SAMPLES CLOSURE COST ESTIMATING WORKSHEETS:
                                    LAND  TREATMENT FACILITIES
           A.    Disposing of Waste Inventory
                                                                          !
                 1.   Maximum inventory to be disposed:  For this  case,  the waste
           storagesurface impoundment is filled  to  its maximum capacity of 5000
           tons of low solids waste  (or 1,198,878 gallons with a  waste density
           similar to water) .        	['
                 2.   Amount of r^n-off, water to be disposed:   a similar
	    amount	of.somewhati contaminated water, is	expected to be disposed of
            from the surface water run-off impoundment.  This mildly contaminated
            water is to be disposed of  in the same  manner as the inventory.
                 3.   total material  to be disposed (Line 1 + Line  2):  All of these
            impounded liquids (waste  and run-off) are to be disposed of on-site  by
lii1' ,11111:1' j  ' " 1 ;',! 	l!ii   ",„'' llllfllf"1!1:,,1'"!",!, llllllliil,:, ^       	t!f	 ."iiilfi;  ;"!" :li]!i,i!||	•;, piXI; i: ,„ป, ';ii '" m 	ill's ,	,i,,-"Ii ;„ I'!-!,	i11,],!!!1,; 'll'ISriii,,, .li,,,!"!!-, ,"1 ,  j, :"ii|,li;:l	'  "HO1 ,rli	SN1,; 1 ilr" "L f |. HI	; '"	 '	l"s ..'lil'Siss's.; '' < ,.!f!' '	 :, - ,"." i! 'fill; lli|il:11'
j;;::;;j:;:: ;';.;.:';  ",'spreading on  the land treatment facility  fields.
I*1?:'!	' Hf  ;'"' !!::!:?rtl:|l4l	'"I1"1|-pf|caฃ:j:o^1"ra1tlel;  'the' waste "'is to	Be'applied'1 to'Tfie	fTeld"t>y"
I1; III: I''	+ii I . fill   j. 18;,i 'I:/..,'W.	sli^  i	ill"1 i in	! :. ป:ซ:	•	ir:i ;'i. •;'	.""'if1	ri'-'xjw*""! rii"'1 •< ••''•• •&•	i;: i	- 'i	IIH* ' aiBt	:	,!ซ•. j(B.iit:,(fiPti.^;.,S"'	i	ITIF" • •'••;, iXi-i;/ stm:m,'f-t
"'"	'	' •'•*"•'' "!  '  mians"" of tank trucks equipped with spray  bars.  The application rate of
            100  tons/acre corresponds to a solids application rate  of 5 tons/acre.
            This application rate has been found to be acceptable based on the
             		 "	 :i	   	 I 		I	
            opeiating experience of the facility.
Ill l||||||||||i| i i i|| i  II  -  , !Jij, "I	ijp -'SflitililH. " i	PI	It,. ':• Illlill 'I	i!.!, •;:ป" 'f-,;.Ill: .INI"	*:(,,'. ป( , "'iiii'lli',:!	I; iili'iISB"!," i,,;, W ,
-------
     9.   Number of diskings required:  A total of  ten diskings will be
required throughout the closure period.  Four of the diskings will be
carried out in the first part of the closure period (immediately after
each of the two applications and several weeks after each application).
Six additional diskings will be conducted throughout the rest of the
closure period.
    10.   Unit cost of disking:  The unit cost for disking  the land treat-
ment fields is the sum of tractor and implement costs and equipment
operator labor costs.  The equipment cost for disking is $.79 per acre.
The cost is for both the tractor and the tandem disk.  It includes
insurance, taxes, repairs, fuel and lubrication but it does not include
interest and depreciation.  The labor cost (fully-loaded) is $20 per
hour.  The disking is accomplished at the rate-of .167 hours per acre.
In addition, extra labor time is required for related handling and care
of the equipment.  Thus, the actual labor time per acre is 1.2 times the
implement time, yielding a. labor rate of $4.01 per acre.
    11.   Total cost of disking (Line 5 x Line 9 x Line 10):  The cost of
disking the land treatment fields is the product of the acreage utilized,
the number of diskings reqiuired during closure and the unit cost of
disking.
    12.   Total costs for disposing of inventory (Line 8 + Line 11):
The  total cost for disposing of the waste inventory and run-off water is
the  sum of the total spreading costs and the total disking  costs.  After
completing the land treatment, the hazardous waste will be  completely
decomposed.

B.   Decontaminating the Land Treatment Facility ,
     1.   Area of facility contaminated:  It should be noted that the
1200 sq. yds. of contaminated soil does not include any of the land
treatment fields where controlled decomposition is occurring.
     2.   Depth of material removed:  The contaminated so,il is removed
to a depth of 1 foot (.33 yds.).  The soil at this land treatment facility
is relatively impermeable.  This makes a depth of. 1 foot realistic for
the excavation for the contaminated soil (since the mobility of the
hazardous waste is restricted).  The soil density is 90 Ibs./cu.  ft.
                                  9-33

-------
                                                                                  1	11  I	II
     3.   Unit cost  for removal:  The contaminated soil is removed and
   	                                                    i      i
loaded into spreaders  using rented earth-moving  equipment.  This excava-
tion and "loading operation is estimated  to cost  $1.60 per cu. yd. of
contaminated soil.
     4.   Cost of removing contaminated  soil  (Line 1 x Line 2 x Line 3):
The cost of excavating, removing and loading  the contaminated soil is
'   If 1  I I 111   I II II III I  Illllli I I ll    I I   I  I I     I          I    111       ll|lllllll 111 I   I 111 II I  I     I   ','„''"'•',
the product of '"t'ti'e volume  of the soil handled and the unit cost of the
   I'll I Hi  i  I I |IF I  IIIPIlillI     fl   I  Illllli  i  I '!'•     r,,  ,"  '  !• .,!.> " • ." ' '* .',' "Illii	 ป 'I)1 nil1!'1 I ': ' • I i |."'': "'ป,. , '   ': T.:,, ," „   ,,, r
operation.  	           	      '      "     	''''	'	''	'	
     5.   Quantity disposed on-site:  All of  the contaminated soil is to
bedisposed on the land treatment fields (on-site).  The contamination
^i,,,^^ ฃ'isp35e3	soil will"'decompose under supervised	conditions.  This
contaminated soil will be  spread after the waste inventory has been  dis-
posed.  The contaminated soil will be spread  on the fields at least
sefi'iral	weeksr after  the	last of  the""_waste _inventory~is spread." _   "^
     6,   Quantity disposed off-site:  No contaminated soil  is to be
   liijll'iil   ' "i:  i Ii 'iiiliiilllllllliiilii' i jDilillinu  j mi	11111:11 ii, sili1, i'1	 in	i',,*, 1:1,1   • ' I'J • ., *	ll ' 1,11i|]l,,, '" jป';ii' lIMn,;1',	ii	'"I,1,: III	Illllillillillini/'liiiปi'i'"i:	,;ll. ,11. '''li Ill IT1 . ,; ii -I 'lillll:	iili'i I'll	:IIK '"•	™ '|ii','i|l|i'l:i
disposed off-site due to the much higher cost of off-site disposal and
the availability of  the land treatment fields.
     7.   Application rate:  An  application  rate of 10 tons of contami-
nated  soil per acre  is used.  This  solids application rate is acceptable
because thewaste concentration  in  the soil  is quite low.
   "•'I	ฃ."	""'Acreage"'utilized":"  the contaminated	soil Is""spread on  the
entire 50 acres  of  the land treatment  facility.
     9.   Number of  applications:   Only  one  application is required  to
dispose of the entire Volume of  contaminated soil.
    10.   Unit cost  of spreading:   The unit  cost for the  spreading of
the contaminated soil is the sum of tractor  and implement costs  and
   	'  	 '  	:	i	 .   ..:   	
equipment  operator  labor costs.  The equipment cost for  spreading  the.
                                                      " ' •      'i    '
waste  is  $.95  per acre.  This  cost  is  for both the  tractor and  the spreader.
Itincludesinsurance,taxes,  repairs,  fuel and lubrication  but it does
not includeinterestand depreciation.   The laborcost (fully-loaded)  is
$20" per	Itiour'.  	The""" spreading "of	the waste is accompTis'hed' at" the rate  of
 .211. hours per acre.   In addition,  extra labor time is required  for  re-
   	"   '"  '  	:	i	:	I	 "	
lated  handling and  care of the equipment.  Thus,,  the actual  labor  time
per acre  ^s  ^'^  fcimes  t*16 implement time, yielding  a  labor rate  of $5.06
per acre.   	       	     "         	'	     	:!
   		i  i.   V"   i..                 'i         '..	 ,,i i -in t
   -  •       	       9-34

-------
     11.  Total cost of spreading (Line 8 x Line 9 x Line 10):  The cost
of spreading the soil is the product of the acreage and the unit cost
per acre.
     12.  Number of diskings:  The spread soil is disked to mix it with
 *
the soil of the land treatment fields.  This one disking is conducted
shortly after the contaminated soil is spread on the fields.
     13.  Unit cost of disking:  The unit cost for disking is $4.08/acre.
This cost includes equipment costs of $.79 per acre for the tractor and
the-tandem disk.  This cost includes insurance, taxes, repairs, fuel and
lubrication; but it does not include interest and depreciation.  Labor
cost is included at a cost of $20 per hour.
     14.  Total cost of disking  (Line 8 x Line 12 x Line 13):  The total
cost for this disking is the product of the acres disked and the unit
cost per acre.                                               .
     15.  Total cost of disposing of contaminated soil (Line 4 4- Line
11 + Line 14):  The total cost of disposing of the contaminated soil is
the sum of the cost of removing  the soil, spreading the soil, and disking
the spread soil.'
     16.  Cost of decontaminating equipment:  At the end of the closure
period, the equipment used on-site will be decontaminated by washing
with detergents.  The run-off cleaning water will be collected for dis-
posal.  A cost of'$1000 is estimated for this task.
     17.  Disposing or treating  of residues from equipment decontamina-
tion:  The wastewater from the washing and other cleaning residues will
be disposed off-site at a cost of approximately $1000.  Off-site disposal
of this residue is required because the land treatment facility is
ceasing operation.
      18.  Total  cost of decontaminating the facility  Line  15 + Line 16 +
Line  17) :  The  total cost  of decontaminating tfhe land treatment facility
is the  sum of the  costs of soil  disposal, equipment decontamination,
and  decontamination  residue  disposal.
                                   9-35

-------
 C.   Monitoring Activities (Ground-Water and Soil)
                                                             i
 ground-Water Monitoring
  [[[ ,  n  .............. ,  ,   ......  ........     ........... '  in  ................................... ,  ,|j , ,  : ' ................ '  .....
     It is  assumed that closure of the land treatment facility will  re-
 _,ji^j ,^ .ฃoซฃ ซ.| ^.u months.  In order to determine the maximum possible
 [[[ ; [[[ ' ............  ..................... ; [[[ , ....... ;;; ........... |; ............... /:-; - ;n il::1 :;;:";; ....... / "',„ ....... :  ' ":
 ground-water monitoring costs, the most extensive monitoring needed
 during  closure is assumed.  Assuming that ground-water quality analyses
 are  required" annually and ground-water contamination analyses are required
 semi-annually , the most expensive case is that in which  two ground-water
 [[[ [[[ : [[[ : ..... , .......... "' 1 ............ ......................... ............
 quality analyses and three ground-water contamination analyses are required
      1.    Number of wells monitored:  Eight sampling wells are  operated
 to monitor the composition of the ground-water at the land treatment..,
 site.  Seven of the wells are downgradient from the land treatment  fields
 and  one well is up gradient.
      2.    Number of samples taken:  Thee "cycles" of ground-water  samp-
ling will be conducted during the 15-month long closure period.  Two
ground-water quality analyses and three ground-water contamination
analyses  are to be carried out.  One sample may be used for both the
ground-water quality and the ground-water contamination analysis .  There-
fore,  during the closure period, a total of three samples are  taken
..from. .each. well. ..........................
     3 .    Total number of samples (Line 1 x Line 2) :  The total number
                                                             i
of  ground-water samples taken during the closure period is the product
of  the number of monitoring wells and the number of samples taken from
each well.
     4.    Number of hours for collecting the sample (per sample):  Taking
ground-water samples is a. rather time-consuming practice.  The well is

-------
     6.   Number of hours for preparing and delivering the sample:  The
ground-water samples must also be prepared and delivered to the labora-
tory for analysis.  This work requires about three hours for a set of
eight samples (one from each monitoring well).
     7.   Total number of hours for preparing and delivering the sample:
(Line 2 x Line 6):  The total number of ground-water sample preparation
and delivery hours in the closure period is the product of the number
of sets of samples (cycles) and the unit operation requirement of three
hours labor.
     8.   Person-hour costs for collecting and handling samples:  The
personirhour fully-loaded labor rate for taking and handling the ground-
water sample is $15 per hour.  This is the same labor rate as during
the operating period of the land treatment facility.
     9.   Total ground-water sampling and collection costs ((Line 5 +  '
Line 7) x Line 8):  The total cost of ground-water sampling is computed
by multiplying the hours required by the labor rate of $15 per hour.
    10.   Number of ground-water quality'analyses:  Sixteen ground-water
quality analyses are required during the closure period.  Two analyses : '
are required for each well.                                         .
    11.   Number of ground-water contamination analyses:  Twenty-four
ground-water contamination analyses are required during the closure
period.  Three analyses are required for each well.
    12.   Unit cost of ground-water quality analysis.  It is assumed
that the cost of an analysis for the following parameters is $77 per
analysis.                  ;
          Chloride.                 $ 6/sample
          Iron                     $12/sample
          Manganese        |        $12/sample
          Phenols                  $25/sample
          Sodium                   $12/sample
          Sulfate                  $10/sample
    13.   Unit cost of ground-water contamination  analysis:  It is
assumed that the cost of an analysis for the following parameters is   •
$108 Per analysis:
                                   9-37

-------
                                          	     .                                       	            ^
                   pH                         $  4/sample
                   Specific Conductance      $  4/sample
 lllllll I   I   I    Bill  III  I  I  "l	,	 ...	I,,,: 	I	F	,	, 	•	I,.	1		i	 	
	.••—..., .  , 	-, „.	„=„	Total Organic Carbon      $25/sample
                   Total Organic Halogen    $75/sample
              147-16.   Total ground-water chemical analyses costs:   The unit costs
         per analysis  are multiplied by  the  number of analyses  to  yield the costs
         for each  type of analysis.  These two costs are added  together to compute
                        	 	" 	 		 	 ! 	I	 	
         the total analyses costs.
         Soil Monitoring
              17.  Number of soil core samples:   Soil core samples  are taken
      "11 throughout  tEe "closure	period.	Four	samples1 are	ta'k'en" in" each	quarter
         of the first year.   In the fifth  quarter of the closure period, 50
      al'' ''.'", • JH^^^^^^^^^^         f lllllll' ifปI-:; II	Hill	IE if 1 ^m&> I	:;,!ปI!*' WsMrfi SI; la	B1 tl-li'Hltt'ii .'M'	!}ปป,• „; ?'	f * IIII1: i: 12: .• i••*. "-illlKlk ' "Si-	/' v "•; ' .|>ji	lii'iniBi 'jil	11':
     :	•"• p'&rSmater",	cosTs"	$5.  Thus, the net cost per soil sample  is $60.
                                            9-38
                      I I  III ill

-------
      22. Total soil core sample chemical analysis cost  (Line 17 x Line 21):
 The total chemical analysis cost for the soil core samples is the product
 of the number of samples taken and the unit analysis cost per sample.

 Lysimeter Sampling of Soil Moisture
      23. Number of lysimeter samples:  Soil moisture samples are taken by
 means of a lysimeter.  This extracted water is then analyzed for contami-
 nation in the same way that the ground-water samples are chemically analyzed,
 Four soil moisture samples are taken during each quarter of the closure
 period.  Since there are 5 quarters, a total of 20 samples are taken.
      24. Labor hours required for each lysimeter collection of soil
 moisture:  One hour of labor is required for collecting and handling each
 sample.  This includes time spent moving about.the field.
      25. Labor unit cost for collecting samples:  The unit labor cost for
 collecting these samples is $15 per hour fully-loaded.
      26. Total sampling cost for lysimeter collection of soil moisture
 (Line 23 x Line 24 x Line 25):  The total cost for collecting soil moisture
 samples is the product of the number of samples taken,  the labor required
 for each sample, and the labor rate.
      27. Unit cost for moisture sample analysis:  The unit cost for each
 chemical analysis is $150.   This is based on the land treatment facility's
 experience with ground-water contamination analysis and soil moisture
 chemical analysis.
      28. Total cost for moisture sample chemical analysis (Line 23 x
'Line 27):  The total cost for the soil moisture chemical analysis  is
 the product of the number of samples taken and the cost of chemically
 analyzing each sample.                                                    •
                             I
 Administrative Costs
      29. Number of technical hours  for administration:   The land treat-
 ment facility also requires the allocation of  some technical supervisory
 labor to administer the closure monitoring program.   Approximately two
 days of such supervisory labor will be required  in small blocks  of  time
 expended throughout the closure period.
                                  9-39

-------
        '"• -"••'•30.	iPersfon-hour" technical	costs:	The' fully-IoaSed' "labor ' cost'"for
                                                                      II
        these  technically qualified employees  is $30 per hour.
   ./!, :*
    [ ............. ..3.1, ...... ,,|pt,al  technical n cost s for administration ....... (Line_ 29  x..Line 30):
 The cost of this  technical  administration  is the product  of the required
 technical administration hours and the  technical labor  rate.
      32. Number of clerical hours:  Clerical support is required for the
 monitoring administration activity.  Two days of clerical labor will be
 needed in small blocks of time expended throughout the 'closure period.
                     ::?:."*'";.;.• ........ . ..... ; ....... -'"IT.: ...... ;""',: ...... :'::.":: :.":::' ;::::," "::'""•::,.:: ",:, ;:,:"„ i: ;"/„:" ...... "  ' " .....
    ii'iii" 33 . Person-hour clerical .cost: ........... The fully-loaded labor rate for
 clerical labor  at the land  treatment facility is $8 per hour.
 ,,',ii!i'34. ..... Total  'clerical' costs' (Line 32  x' Line 33) s  The total clerical
, "'^ jg^'fo'j.f ..... 'a^minTstering ....... the "monitoring ....... activity" ' Is""" the"" product '" oฃ the
  i " IWซ I !l,  •.);>* ..... , ••'"> ........ I, ;..;:*' ;" r ,  'if
 hours required  and the clerical labor rate.
 . ,  I!! h i ""(! '!'!' 'i "'! ', ;Jni !lii,'!',:!ปIIIHI:!!iv  flll IIIIII I . iilli •!,,„, VI ,i ซ ' ....... 'C :'!" J1V4I '.'4 ',,'lliii ' '''< ..... 'r,\ ^V\ ....... it:;,)!! ..... v* ill1" , ' I : ' I ,  I"1 :''..'' ">!l" -!' 
-------
    •  40.,  Total administrative costs (Line 35):   The total administrative
 costs,  both clerical and technical,  for the monitoring program are repeated
 here.
      .41.   Total monitoring costs (Line 37 + Line 38 t Line 39 -H Line 40):
 The total  cost  for the  entire closure period monitoring program is the
 sum of  the costs of ground-water monitoring, soil core testing, lysimeter
 testing,.and .the .administrative costs.  All of  these costs,are reliably
 known from the  operating experience  of the facility.
               !        "   . '       .'
 D.    Fence Maintenance
      For a land  treatment facility consisting of 5.0 acres  of  active fields,
 assuming that the site  is square, each side is 1475.8  feet..  The perimeter
 of the  site is  then 5903.2 feet.
      1.    Length of fence to  be replaced:   Since the land  treatment facil-
ity, has  a prolonged closure period and possible post-closure activities,
 it is necessary  to maintain the security fence along the field perimeters
 in good condition.   We  have estimated that  10% of the  fencing will be
 corroded and damaged to the point of  requiring replacement.
      2.    Unit cost of  replacing fence:  The security  fence is. a galvanized
 metal 6-foot high chain link  fence made  of  #9 wire.  The installed unit
 cost  of replacement sections  is  $13.06 per  linear foot.
    •3.    Total  cost  of replacing fence  (Line 1  x Line  2):  The cost of
 replacing  the damaged fence sections  is  the  product  of  the length  of the
 fence needing replacement  and the unit cost  of replacement, for a  total
 of $7705.                                     .'.''•'•'

 E.    Repair of Drainage Channels
      1.    Length  of drainage channels:  The  land  treatment facility's
 drainage channels are an important part of the containment system.  They
 channel run-off water to a surface impoundment.   Our estimate  is that
500 feet of these channels will have  to be replaced during the  closure
period.
     2.    Channel volume per unit length:  The channels have a  square
 cross  sectional area measuring 3 feet by 3 feet.   "-This results  in a
volume of 0.33 cu. yds.  per linear foot of. channel length.         "     '   '

                                   9-41

-------
iil'1; 'tiilllllinif'Lil
	                   .,   .,	,.,                                j		,,
        3.   Channel  excavation unit  cost:  The unit cost  of excavating  the
   channels with a backhoe is $.67 per cu. yd.  This work  wouli be performed
                               	   	'	  - 	*	 '   J" I]"1 "" • •    	  -' • •
   by a contractor and is base	"4 KI,	, ,	JIVT  , f	l>, < '   ,11  '<,,  • •>, "' I"
    checks the  progress of the facility operations: spreading, disking,
      1	11 J',,, .i""1 ',,1	*ii!il!!iiliซ|! ' " ill''!!!!!'" ,1-,'' „;" •'&';,. ••:  ' '-',  • ,i   ' 	nil	:/,. •    i,;w •  . :	r "  i,It-Ill  	 i -if |i": '.  >"'  "• J! '  •• 	
    sampling, decontamination, etc.
         3.  Duration of closure period:   To allow the  hazardous waste to
    decompose,  theclosure period must be 15 months in  duration.

      :|::" '•   ''',""  ,:::l!!' *'*• : ' " '"' '  • ': '   ';""   '!9-42

-------
      4.   Total technical management person-hours required for inspections
 (Line 1 x Line 2 x Line 3);  The technical hours required for the actual
 inspections are the product of the number of hours for each inspection
 and the total number of inspections required.
      5.  Person-hour costs for technical management duties:  The person-
 hour cost for this technical supervisory labor is $30 per hour (fully-
 loaded labor rate).
      6.,  Total technical management costs for inspections (Line 4 x Line
 5):  The technical cost for the inspections conducted throughout the
 closure period is the product of the total inspection technical hours
 and the technical labor rate.
      7.  Additional technical management labor required:   A small amount
 of  additional technical time will be required for managerial tasks
 associated with the inspections (such as writing, reports).  Approximately
 8 percent to 10 percent of the inspection time is required for  this
 additional work.
      8.   Total cost of  additional technical management  labor (Line 5  x
 Line  7):   The cost of this aidditional technical labor is  the product  of
 the additibnal hours  required and the technical labor rate.
      9.   Total cost  of  technical  management  labor (Line 6  + Line  8):
 The total  cost of  all the  technical  labor  required is. the  sum of  the
 labor directly spent  on inspections  and  the  labor related  to inspections.
    10.  Number of  clerical hours required:   Clerical labor is needed  to
 support the  periodic  inspections  of  the  land  treatment facility.   Only
 a modest amount of clerical labor is  required.
    11.  Person-hour  costs for  clerical  labor:  The labor  rate for
 clerical  labor  at  this  facility is $8 per hour.   (This is  a fully-loaded
 labor rate.)                                                    x
    12.   Total cost  for clerical  labor (Line  10'x Line 11):  The  total
 cost for the needed clerical labor is the product of the clerical hours
and the clerical labor  rate.'                             '
    13.  Total inspection cost  (Line 9 + Line 12):  The total cost of the
inspection program is the sum of the technical labor costs and the cleri-
cal labor costs.
                                   9-43

-------
          Gs   Professional Certification
               1.  -Number of person-hours required for inspections:  Approximately
111  I   i   ":, "  , Illii! "' • •: K1 iS'lif !"111 ...... !•' i iSiJllr - *!l!li '!> *!' '' !. ' '•(: ' ' ....... '  ' ;: * ..... ;" ........... . Rill "i; ......... ;l • I . ".' ' '"el ...... il~i 'S!"i: S ..... I " '"'I ...... " '• Hit ............ I ."'& ';"5 Sei!1'!!!!!' >'. "i : i "i* if Lll'tiJIf i illli" : : ';' iSi.' i '• ..• 'Sin "if '•  t '. • "i '
          ofie week of professional  time will be required  to  certify the proper
          closure  of the land treatment facility.  Most of this professional  work
          will be  an independent professional engineer as specified by the interim
                                   ,, .....  , ,„,                                 l' l    ' 'l'ป"  i  '"   '""'
          status  regulations.  The professional engineer will be assisted by a  soil
          specialist who will evaluate  the soil samples taken during the closure
              .  ,           "   •''•'•• ";l E 'r iijซ . '•ป : :    i   '               ......  i - -I '    '. '""' Vit.  ,
          period .                                                                   '
                2.  Cost per person-hour:  The contracted cost of these professionals
          ig  ง75  per hour based on  their current quotes for these services.
          '"*^"3^" ..... Totai ....... 'costs"" of"' ..... professional' engineer's  time (Line 1 x Line  2):
           lluiii'!!!1 l|!:' '• .l|"<'l:||'i.il>l :."":r ' „ •' lll:!'  ' " 'li
          The total cost for these  contracted professional services is the  product
          of  the  number of hours  ireSuil:ed ^^ tiie  
-------
and  the  administrative  costs.

 H"  Total Costs Plus Administration  and  Contingencies
     Items 1 through 7  give  the costs of  each major  closure  function on
each of  the preceding worksheets.  Line 8 is the  total  of Lines  1  through
7, $39,389.      '
     7.  Administration:  All additional  administration costs are  com-
puted by multiplying the subtotal  (Line 8) by 15  percent.
     8.  Contingencies:  Allowance for contingencies is  computed by
multiplying the subtotal (Line 8) by  15 percent.
     9.  Total costs of closure (Line 8 + Line 9 + Line  10):  A grand
total for land treatment facility closure costs is computed by adding
together the costs from the worksheets and the allowances for additional
administration and other contingencies.
                                  9-45

-------
                                                   •in inn 11111111 ii illinium iiinini in n in i iiiiiiiiniinnnn in n iiiiiiiiiiinnnn 111111111111111 nininni n niiiiiiiiiiiiiiiinnnn inn nun niiiini n ininiii in in i 11 in mini inn i inn nun nun nun imimmmi n mi minium in
                                                   ii 11 n i i  mm n linn m inn in I inn i i in nun mi inn in HIM in INI inn i mum HI  inn i n in
 IIIIIII
      i in
                                     LAND TREATMENT FACILITIES
            Method of Disposal:  Spreading  on the Land Treatment Fields
            1.   Maximum  inventory to be  disposed
 2.
  Ill'
 3.
 4.
 5.
 6.
 7.
 8.
 9.
10.
^!!!'!"
121"!"
 Run-off water to  be disposed
 Total material  to be disposed  (Line 1 + Line
 Application rate  (wet weight)
 Acreage utilized
 'Number"	"of	applications  in'' the	closure' period
""Unit'""	cost	"of ""spreading
 Total  cost of spreading (Line  5  x Line 6  x Line  7)
 Number of diskings required during the
 closure  period  (excluding one  disking for
 decontamination)
 Unit cost of disking  (equipment  cost and  labor)
 Total  cost of disking  (Line 5  x  Line 9 x  Line  10)
  II  I Illll II III II  Illlllll III     I 1   III II 111    I  I      (I II     III  ll I i,l; ill''Weil \iilli ills tin-Hi*::
    i nun nun ii  n in nil i    i n   in ill      n n                  j 	"li""n	
 Total cost  for disposing of  inventory  and
 run-off water  (Line 8 + Line  11)
5000  tons of
liquid waste
5000  tons
 ll I  v'j't;: • ''iti'iayi •• "  ,"i
10,000 tons
 I   ........... ,   .....
100  tons /acre
 i
50 acres
                                                                             2
                                                                                  acre
                                                                              o
 $4.80/aare
"lJ246d
'.'"!!.!!'; ii'-'S,	If is1 ;lil	,-,!!' ',.
 $7200
I1!	CHU'ilIn ,1 i:;,HlI '.	I :'
                                                                 ,1 i1" i1'!1"! in. : '.'iin'iii1!1,, 'iฐ > ' '• i .'*i'',i r
    i, JlkLl "IILlLii  '.:''  1H1 ill' iiii'Ll,;	,.,;ป*: ,:i"
                                                            i1"1	iiii|,'ซ if, >|i , !,"
                                                    9-46
           <: • i  iiiiii,iii
-------
                       LAND TREATMENT FACILITIES
               WORKSHEET B, '- DECONTAMINATING THE  FACILITY
 1.   Area of facility contaminated
 2.   Depth of material removed
 3.   Unit cost for removal (including machinery rental)
 4.   Cost of removing the contaminated soil
      (Line 1 x Line 2 x Line 3)
 5.   Quantity of contaminated soil disposed on-site by
      landspreading
 6.   Quantity of contaminated soil disposed off-site
 7.   Application rate -     !
 8.   Acreage utilized
 9.   Number of applications
10.   Unit cost of spreading (equipment  cost and labor)
11.   Total cost for spreading the contaminated  soil
      on the land treatment fields (Line 8  x Line 9
      x Line 10)           ,
12.   Number of 4-skings  carried out  to  assist
      in disposing  of  contaminated soil
13.   Unit cost of  disking  (equipment  cost  and labor)
14.   Total cost for disking the  spread  soil into the
      land treatment soil (Line  8 x Line 12  x Line 13)
15.   Total cost of disposing of  the contaminated soil
             /
      (Line 4f Line 11 + Line 14)
16.   Cost ofLfecontaminating equipment
17.   Disposing of.residues from  equipment decon-
      tamination
18.   Total eft of decontaminating the  facility
      (Line iy- Line 16 + Line 17)
  1200 sq. yds.
 .33 yds. (1 ft.)
 $1.60/cu. yd.
 $633.60

 396 cu. yds.
 (481 tons)
 0
 10  tons/acre
 50  acres
 1
 $6/acre
 $300
$4.80/acre
$240

$1173.60

$1000
$1000

$3173.60
                                   9-47

-------
LAND TREATMENT FACILITIES

	
WORKSHEET C - MONITORING ACTIVITIES
(GROUND-WATER AND SOIL J^^Q^Q)
Ground-Water Monitoring
i
1. Number of wells monitored
	
Illllll! i-tJWf i'T'
1 Illllll II 1 II
ii ''Wiiiii, i 'if!' M fi ii1,'
! iiflB-it:,1,1!'!',!11;! iir: "'ii!1
Ill II 1 "'iff"!111'! "i'ii
II 1 HI 1 ii ' ill" • ibiii
( ill "ill ill
1 1 :,i ' i jlijJB1''
1 III liilF''!!''*!,;1!!,
1 1 III 1 1 'i'i,,, ,1,,,' lit, II 	
iiiiiii1 vi'li'fi'lii

"i 'Bur ' i*"*1'™
ill, 1" fillllP' :I!,\L Liiilli''';!!.!'!!!!!"!
Li.lIB ! ":i'"|!l; 	 I'liil,
iiiiTiiiii'iiiii,,, H,1',,!'"'!'!' iiiiiiiif
Hi, iiiiiiiiii I,;' linn iii'ii .
il^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
2.
3.
4.
5.
T Iiiii, *
6.
7.
8.
9.
10,
III II 1
11.
12. 	
13. 	
,, ii 	 nil' ;
14.
,! ' iiri,!
ii IE1 11 ;ii
llllllii'il"! if!' '
I!1!1'"''1' ' ' III1'' ,T',ll|| '
15.
16 "' 	 '";
Soil

17.
18.
19.
', ., Fii1' :::
'• •" i!!!1!1!'1! 1
'' iiii'i, ,! :
	 ii 	 iiil
Number of samples taken at each well (1 per cycle)
Total number of samples (Line 1 x Line 2)
Number of hours for collecting the sample (per sample)
Total number of hours for collecting the samples
(Line 3 x Line 4)
i,^^^^^^^ 	 IF;,-.! 	 tK;, :.W,& 	 ' 	 ',';; ^l^iU^'EMii 	 li' 	 ••>;": ,iitI*Si 	 !, 	 'illiiii 	 iimi 	 h:!f;:j 	 IfflflM:
Number of hours for preparing and delivering sample
(per each sampling cycle of eight wells)
	 ; 	 ; 	 : 	 ; 	 t 	 : 	
Total number of hours for preparing and delivering
sample (Line 2 x Line 6)
Person-hour costs for collecting and handling samples
Total ground-water sampling and collection costs
((Line 5 + Line 7) x Line 8)
Number of ground-water quality analyses
Number of ground-water contamination analyses
Unit 	 figst 	 of Aground -water quality analysis
1 ""•
8 wells
3 samples
24 samples
2 hours
48 hours
.!"!• 	 i"'';,1"1, 	 I 	 Si'!11' I?:'" 	 iil;,!1.!:;!:1'!.;:.'^!!!!, Jill 	 IMI
3 hours
9 hours
$15 /hour
$855
i ^i^k.
16 analyses ^M
n ii 1 1 ii in i 1 1 ii n i i mi ^^^^
24 analyses
$77
tjnj.'t 	 cgst 	 of ,n ground-water contamination analysis $108
' ,',i" 'i i'!"' iin , I iiim: ' '!•!:,' f i , 	 mi 	 if 'i"1:'"1 • 'if:! 	 , : 	 if • : •• j> , •?• ..s *i 	 ic'i" 	 *'iป ป • 	 r **r, 	 : 	 	 v~ > i 	 w 	 isji,'"?, t1:": ซ• ,. iiii^ ww 'iiii> ป wf wis.s rv 	 J fซ 	 w •- • KV v t'lii,'! •?.. i< iii-'iiir ttsir , ' \m
Tplal ground-water quality analysis costs $1232
i • -: si: iiiii ;;!'ii<:i''siii^^^^^^^^^^^^^^^ "i 'iiiiiii i iia "iif.3 si 	 ii >KnHiL •• < r B f "' ' *•• 1 1 ": <•• "t; •; -SK : . i; '; f ni ; , '< • i 'ia^-iwii ' 	 i '• • • liiiEii ma 	 , i "ill f ' AVK: , 'v-n, • " iiiBii, ;. 	 i •. m jf *y i"< !•; JU' " • ;, si f
(Line 10 x Line 12)
Total ground-water contamination analysis costs
,(Llne 	 	 11 	 xLlne 	 13) 	 i 	
;: I ; "is 'iiS , liilllK • Illllll ' ' iS! 	 i " ,'iiiiiE ',i ,^ ii ;' *\ " t * ; ' VI"-. ,-! • ' ^ ii>M' : 1 • -JH ซ '"; 	 :• ' WSKtfti "i V i ' i IB "!" ":i->3i'i ;| r '| Is i,
Total ground-water chemical analyses costs
(Line 14 -t- Line 15) 	 ' 	 '"'
Monitoring
Soil Core Sampling:
Number of soil core samples taken during the
closure period
Labor hours required for each core sample
(includes movement between sampling locations)
Labor unit cost for collecting core sample
,,!"" ..: 'ifl'l'liil". iiliaiW illllliiil .I!'1'; ,„ ""'if 'Hi'MlifTI" (I .'-'Y'ii;, 	 	 "'!'![, 'I'l'llli! "i' "if •'. 	 ': i 	 IKi 	 I* iiii'iii 	 I'i'.'B 	 'Ml" -nii i'l'-'lS ilfll-'
"P'in :' |ill,,ui, '!;'''iilll '"', "I 111' ' „ซ" i|i: 	 , ,' I „,, v ,n i ,'i'l"' i I"" 'v'ili!,, ' „'' '; 	 /'^ ,' I'llii I;,!!! ,"" 	 :''!'i"i "',,'|l|;! ,' ',!',,, II* V' :,:,!' 1 ^ Ijl; .JKI'';!!! 'li||;ii ',
	 ^ 	 9-48
i, 	 T,, 'Vii'iM 'ir,,''i':i,ii''i: ii'ii 	 ii 	 iii!" 	 '"'i'1'1'1' 	 i'1 i' ",'„ ,'i", i 	 ii''1 ', i,''"',::r',,iiiiปi'' ''; "'ii1'1' i"hl'ii' !„,'!' jii'ii'ii'i'iii, ,;ii;i '"'i1';,, ifiii'ii.'..'!.!"! ii! k'"
"IS 	 r,," jlill''':.!!!!:? > , jiii ,'ii- ,,'ii'!"i , 'i!:,i 	 I',;)"),!' i" :l, ' , „ "f,,, i"'1"::'!,'.!! 	 i" I';,'!"..! 	 iif :,)"i iLi,!''':!;,;!" " lliii; ilii''i'M ; "''l''!^';^^'!^

'ii, J'SI'!', 'Hii; .iiliiili:', '! "' "'ili, ' li^^^^^ '111!': i'llHii'1 ,!"' :,{ 	 lil'
$2592
::^'; 	 ii!iii-''',,"i:i,,,i 	 iafiปjซ. '•$ฅ*&•&
$3824
66 samples
.5 hours
$15 /hour 	 ^^ 	
,':,i"'>:::'':|ii,,r" .iiillllill11!: ; " ,,,,'" 	 itr 	 i:ilii'',iii,lflll!,il|):,il 	 ^^V
i;,i:L j,"1,' '"I'lBf, i,'1; " ,,' ' ''.'fMifaK .ffW lii!" 'x! 1
K^^^^^^^^^^^^ 	 ii,,'!,;;:!! 	 id^ 	 ii

-------
 WORKSHEET C (continued)
 25,
 26,

 27,
 28.
 20.  Total cost of collecting soil samples for the entire
      closure period (Line 17 x Line 18 x Line 19)
 21.  Unit soil core sample analysis cost (10 parameters)
 22.  Total soil core sample chemical analysis cost
      (Line 17 x Line 21)
      Lysimeter Sampling of Soil Moisture;
 23.  Number of lysimeter samples taken during the
      closure period
 24.  Labor hours required for each lysimeter collection
      of soil moisture
      Labor unit cost for collecting samples
      Total sampling cost for lysimeter collection
      of soil moisture  (Line 23 x Line  24  x Line  25)
      Unit  cost for moisture sample analysis
      Total cost for moisture sample chemical  analysis
      (Line 23 x Line 27)
Administrative Costs
29.   Number of technical  hours  for administration
      Person-hour technical  costs
      Total technical costs  for  administration
      (Line 29  x Line 30)
      Number  of  clerical hours
      Person-hour clerical cost
      Total clerical  costs (Line 32 x Line 33)
      Total administrative costs (Line 31 + Line 34)
Maintenance Costs
36.  Monitoring well maintenance  (includes maintenance
      of associated equipment)
Cost  Summaries for Monitoring
37.  Total cost of ground-waiter monitoring for the
      closure period  (Line 9 + Line 16 4- Line  36)
38.  Total cost of soil core sample monitoring for
     the closure period (Line 20 + Line 22)
30.
31.

32.
33.
34.
35.
                                                               $495

                                                               $60
                                                               $3960
 20

 1 hour

,$15/hour
 $300

 $150
 $3000
16 hours
$30/hour
$480

16 hours
$8
$128
$608

$750
                                                              $5429
                                                              $4455
                                   9-49

-------
'	" '*" III!!11 ''Wfl'	BUI	H	'fWOfi,	lll:!llM I"	II!1"	III	V'	IE1!!1	Ill If' !ih'"""  ' "I; l J'3	"' '"'	i, "fi	II! "ซ•	I1"'':!!!"1 H!"'S	i'i!	i 'Will	"I /llllfllli:''!1'! "i. 'I11!!!1*:; IT)'!"	ESI	MV- ii'DTW1.1 ,'li' •'.	"I I'1' '"H,  'ill Ifflllll111
 WOEKSHEET C  (continued)
 39.   Total cost  for soil  moisture  (lysimeter) monitoring
   IE i"   1 '''V jt • "i	'•	* ''i11 - ' ' 	•	ini1. -JBLV	r	linn .t ini,"!"s, sv	~
                  ""1'        26 4- Line  28)
     $3300
,,, I f.v.
                                                                            • 'lib1,,:','|J :,
 40.   Total administrative costs  (Line  35)                            $608
   ii!"'!",! .i, ii'i."ซปtWHซi'uKH'twE'-!iii'iP,!',"';!HBซA.iiiii'51''	"• j!?'"-^' ^ S-'iiiy-''-1111	• -s;&'.*:'"'"\m&j,.'r>''f." •"': i '-'"li1" ••, kJi' "^X'Si
 41.   Total monitoring  costs  for  the entire closure                ?13,79Z

       period  (Line  37 + Line  38 + Line  39 + Line  40)
                                                                            ..n	|:
                                                                              ii
                                              .9-50

-------
                       LAN!) TREATMENT FACILITIES
                    WORKSHEET D - FENCE MAINTENANCE
1.   Length of fence to be.replaced                        590 feet
2.   Unit cost of replacing fence                          gn nA/n
,                                                          513.06/linear ft,
J.   Total cost of replacing fence (Line 1 x Line 2)        $7705
                                9-51

-------
1.
2.

3.
4.
5.
6.
7.
8.

9.
                      LAND TREATMENT FACILITY
             WORKSHEET E - REPAIR OF DRAINAGE  CHANNELS

  Length of  drainage channels  requiring excavation
  Channel volume per unit length

  Channel excavation unit cost
  Total channel excavation  cost
,ซ!,,,; (Line	1,'x Line^ 2|ii;x, Line"3)	
  Unit cost for hand grading
  Channel surface ""area "to be prepared by  hand
  Total  costof hand grading(Line 5 x  Line 6)
  Total  replanting  cost (including ieed,
  fertilizer and mulch)
  Total channel repair cost
   (Line 4 4- Line  7  + Line 8)
                                                                        500 feet
                                                                        .33 cu. yds.
                                                                        per linear  ft.
                                                                        $.67/cu.yd.
                                                                        $11.05.
                                                                        $.02"/sq.  ft.
                                                                        4500 sq.  ft.
                                                                        $90
                                                                        $50
                                                             1	"I!'
                i'HI
                                      9-52
                                                                                   I I	I  "
..... iiii ..... in; ' i Jin,, i; ' : ..... 14 ......... t ' ..iiiiH- .iiii'i-:, ฃ ',1:1. is ',( 14 iiiii MI& ,i iiiiiiK   ,,L 'i
                            ...... i,!: ...... li! >i!, .'i; a™! fiซ ...... :•!
-------
                          LAND TREATMENT FACILITIES
                  WORKSHEET F - MANAGEMENT INSPECTION OF LAND
                         TRJSATMENT FACILITY OPERATIONS
  1.
  2.
  3,
  4.
 5.
 6.

 7.

 8.

 9.

10.
11.
12.
13,
 Number,of technical management person-hours
 required for each inspection of the land treatment
 facility
 Inspection frequency
 Duration of closure pieriod
 Total technical management person-hours required
 for  inspections during the closure period
 (Line 1  x Line  2 x Line 3)
 Person-hour costs for  technical management  duties
 Total technical management costs  for land treatment
 facility inspections  (Line 4  x Line 5)
 Additional technical management labor required
 related  to the  inspection  program
 Total cost of the additional  technical  management
 labor (Line 5 x Line 7)
 Total cost  of technical management  labor
 (Line  6 +  Line  8)
Number of  clerical hours required
Person-hour costs for clerical  labor
Total cost for  clerical labor  (Line 10 x Line 11)
Total inspection  cost (Line 9 + Line 12)
                                                               8 hours
 1 per month
 15 months
 120 hours
$30
$3600

10 hours
 *
$300

$3900
                                  9-53

-------
                          	                FACILITIES
                          WORKSHEET G-"PROFESSIONAL CERTIFICATION
n i (
lillili1
 1.	

 2.
 ,3".	

 4.,	

 5.
 6.

 7 •	

 8.
 9.

10'	
11.
              Numberofperson-hours required for inspecting            40 hours
              the land '(treatment  facility and its operating records
              Cost per person-hour                                      $75
              Total "costiof professional engineer's time               $3000
              (Line 1 x Line2)' \""" '	'	'" ^" ^ _^ " "^ \'""^	"_ " "~	 ["  |'        ^^ ]'	^	\ ^'[""™ ^
              Number of technical hours  required for administrative     8 hours
              duties
              Person-hour costs for technical administrative  duties     $30
              Total	administrative;	costs '"for	technical	labor	|	$240
              (Line 4 x Line 5)
Number of clerical hours required for administrative
 i • i inn n  in n • i  i i iiiii i     i   i  i i i i                        i
duties
Person-hour costs  for clerical administrative  duties
Total administrative costs for clerical labor
     4
(Line 7 x Line 8)

Total adtagnฃs'|ya^:j^e;' ""Costs'1 (Line ...... 6 ........ + "'Line""9)
  ........ i pill " ..... •!• , m ซ' MSWI J ...... mm ...... t s ...... >f * E B> $ & PIK i, i. ...... isf ........ iiii!;" ' ...... i m \ ...... i ..... B ,:i ...... (:
Total certification cost (Line 3 + Line  10)
                                                                         8 hours

                                                                         $8/hour
                                                                         $64
                                                                         $"304
                                                      M, : ....... i> m:> ..... ^ i
-------
                         LAND TREATMENT  FACILITIES
               WORKSHEET H - TOTAL COSTS PLUS ADMINISTRATION
                              AND CONTINGENCIES
 1.   Cost of disposing of inventory  (From Worksheet A)       $  7,200
 2.   Cost of decontaminating the facility (From Worksheet B) $  3,173
 3.   Cost of monitoring (From Worksheet C)                   $13 792
 4.   Cost of fence maintenance (From Worksheet D)            $  7 705
 5.   Cost of repairing drainage channels (From Worksheet E)  $   251
 6.   Cost of management inspections  (From Worksheet F)       $  3 964
 7.   Cost of professional certification of closure           $  3,304
      (From Worksheet G)
 8.   Total of Line 1 through Line 7                          $39 339
 9.   Administration                                          $5 903
10.   Contingencies                                           $ 5 908
11.   Total costs of closure (Line 8 + Line 9 + Line 10)      $51,205
                                   9-55

-------
IlilitBI! 'iii l:" Mil	
              IB	-i,il, f!;,,ป"ป  *"inP'',Bป ซ>'!> . 8"",:•ป"'	I* >,,'i.:!l*:ซ 'I'.;  '!'!',"!."? 'i	I "ill""!'  :.:":" V'Sil!!
                                                                                                "3IE ;
I	!' II!	!>:;!;	i,  i
         9.4
                 '"'' •"'•;':''' ;!:EXAMPLE" - ฃANDFILLS:l
                   illugtratiye purposes, a sample  cost estimate  has been developed
        ':,'!iซ     il!1:1!,!'1!, ,|J"I I!"?:-11:; JIB Jill	HIIW^^    '-ilK" t, ป''"!	I' '"•"'	"S'i	 ' '	I'"'1"!1' "">' "I"'"'1'''"' "•ซ" "-1'"' •' '"""i''' 	 !;	"	I"1'	'	":'S""	'"'	V"'Si"'i'" T5" "i	*	V	''	' ""
         for  a landfill with the following characteristics:  the landfill has  been

        'la operationfor15years' and  covers approximately 75  acres.   Sixty-five
                                                                                 i
         acres have been  partially closed (i.e.,  they have been filled with  waste,

         an adequate cap  and vegetative cover established and maintained).   Ten

         acresof  the landfill are currently in active use and  have not received

         final cap"or'cover but  are largely  filled.   Of the 65  acres which have

         received  final cap and  cover,  it is assumed that approximately 5 acres

         are' 'in need of revegetation  due to  failure of original vegetation over

         the  life  of the  facility.  The landfill  accepts  hazardous  solid waste re-


         ceived in trucks.   Waste is  received for  this site in  55-gallon drums.
!!' IflFl'J, "!,'":ซ
IF IK' ! ""i I	'*(
ilk'111	!' ' i ! l! Hr
1!	IN
Si i
liiiitii 'I1* i

III)! 'f
I"'-1!!*!'1' Hi
SI "ill"-" S'-iii!!
 'iiiliiT ' '"il'JB
'-i"' .. *
'ij.ii'	!
jM"1" '' 'ill
                            fill
                                       >>'';: ! :ir ;  r',11  ' nil';:1 "f, ' ' '-n	|ซ ,,'
                                      . :.f > ""' ' '''"•'' ,'J 'il<'  :J!~ "'
                                                                       : aif/ill	I , I,	"I /I1' Ii
.;..	'	 r. . iiiVJ'i,"  	'"",]!: ii : !) '"M	fi'iiinmni	 V!i ," • 'S"i:i
 !':'("', ,,.'1',,;: !i(ซ.,lr  'ffy  •. ''Hi !'!;(•ซ" .'Kf,:?: :•{
 ,-' '-.'t"' . i1!!" i !!  'V.'  ,.M ill!'1*'1!.*!1!!!!!' 'tilt'l'"' 'iMliUL'iiii.
                                                                                              !l"'i"lllll il J! '' 'i' 1,11
                                                  9-56

-------
           SAMPLE  CLOSURE COST ESTIMATING WORKSHEETS:   LANDFILLS

A.   Disposing  of Inventory
     1.   Volume of waste when processed  for landfill  disposal:   It is
estimated from  the closure plan  that  the most  expensive  closure conditions
likely to occur over  the life of facility would result in 900 55-gallon drums
of waste  to be  disposed  and no trench yet constructed for their disposal.'
This situation  would  occur when  existing trenches had been filled  but not
yet capped, and waste continued  to be accepted for  further disposal.
This estimate should  be  based on the  volume of the  waste  after  conducting
the necessary processing prior to disposal.  For example,  if  sludge is
taken in,  the proper  volume to be used is  that of solidified  sludge, not
the volume of the sludge as it enters the  facility.   In this  case, since
waste is  accepted in  drums only,  there is  no need for further calculation.
     2.   Estimated volume of  contaminated  soil residues disposed
of through on-site landfill operations:  This  volume  is determined from
Worksheet B.
     3.   Total  volume of wastes  to landfills on-site  (Line  1  + Line 2):
In this case, the total  volume to be  landfilled on-site is  the volume of
inventory (800  cu. yds.)  plus  the estimate volume of  residues and  con-
taminated material to be  disposed of  on-site from Worksheet B (600 cu.
yds.).  It is possible in some cases  that not  all inventory could be
disposed  of on-site.  For example, if two wastes normally are neutralized
by combination, and there is  inadequate volume  of one of the wastes to
complete neutralizing the second waste at the  time closure commences,
some portion of the second waste would have to be disposed of off-site.
    • 4.  'Estimated cost of constructing a trench:  The cost of construct-
ing a trench adequate for 1400 cu. yds.  of material of the type indicated,
including adequate liner, is estimated as $18,000,  based upon past trench
construction experience at the facility.
     5.  Estimated cost of placing wastes in trench (excluding final
cover and vegetation):  Based on the annual volume and operating costs
of the facility (excluding profits and depreciation),  it is estimated
that the  costs  of  placing this waste will be $6000.
                                  9-57

-------
      6.  Total cost of disposing  of  inventory (Line 4 + Line 5):  The
                                                             I,	
 total cost of disposing of inventory are  then the sum of Lines 4 and 5.
 B.   Decontaminating the Facility
      1.  Area  of  facility  contaminated;  It is assumed in the example  that
 at the end of facility life, approximately  1800 sq.  yds.  of the surface of
 th,ง facility will show sufficient  contamination to justify its disposal
• ;,  il i' i'i ;: .1 .'ML i .iii'ii if "Si1  i            ,'   . '	' i 	    'i  ii.' • •'..  .• i'5;ป , •. i. :* 'i • • /, •.  "••,	 i
 as hazardous waste.
   iij-M I.";	i" '"• lE:^ [.jjiji '.'•,       :    ;    ,....,'.'   ;••   !   "•. i, ซ  i|":i ' ';•„' k :j"!•   "-  •'' ••
      2,  Depth of material removed:  It'is  assumed that  removal to 1 foot
 willr be necessary.
      3.  Cost of removal:  The assumed  cost of removing  this material
 is $1.40 per cu. yd. for a total cost of  $840.  This does not include
   111!1!1'"1!11'   '< "' ',  -Ml'"1	IKil!  i   •    i     ..  • .   / . •  .  . ,...   "•,'	  *  . •  ;i/ '	•	,, n	|  . •  .       .
 the costs of disposing of the material.
      4.  Quantity disposed on-site:  For  the sample  problem, it is
 assumed that all 600 cu, yds. will be disposed on-site.
      5.  Quantity disposed at an off-site TSDF:  None of  the material
                                                             i
 removed will be disposed off-site.
      6.  Cost to decontaminate equipment:   It  is  assumed  that $1000  will be
 sufficient for: decontaminating equipment.
      7.  Volume of waste resulting from decontaminating equipment:  It
 is estimated that 25 cu. yds. of material will need  to be disposed of
 as a result of  decontaminating equipment.
      8.  Unit cost of off-site disposal:  Contact with other area
 hazardous waste disposal facilities  indicates  that land disposal for
 these wastes would currently cost  $40/cu. yd.
      9.  Unit cost of hauling:   Hauling this small quantity of residue
            ,  ,„ ,            „    ,       ,      	   ,   	   , , „ il , „
 20 miles  tonearest landfill will  cost  $10  per cu. yd. according to
   '''        	  ' ''              '      „  •  i     I  ' .      	 . „    ,1 i • jj     ,   IM.
 local trucking concerns.
  1 •li;" ,,.10,  Total cost of off-site  disposal  (Line 7  x Line  8):   Total costs
 of disposing residue are then $1000.
     11.  Total cost of hauling (Line 7  x Line  9):  Total  cost of hauling
 isthen the unit cost of hauling times  the  total  volume of residues to
   ;,;	" .   ;	•< ;,   , 	    	-     '   ,  : . ,      	•..".,	:;;;;,;  ;; ; •; -   ; ' . ;J ;  • „	' ••
 be disposed.
     12.  Total cost of decontaminating  the  facility  (.Line 3  + Line 6 H- Line
 Hf	V Line 11) :	 Total costs are  then $2850.   "	'	 """|   |/"'_
                                     9-58

-------
C.   Placing Final Cap
     As noted in the summary of this example, it has been assumed that
the equipment for all necessary earth work is available on-site.  As a
result, costs for placing a final cap over the fill area include only
labor, operating costs, and materials, not costs associated with rent-
ing equipment or capital recovery factors for purchased equipment.
     1.  Area to be capped:  The example assumed that 10 acres, or 48,400
sq. yds., will remain open ..and require both a clay cap and topsoil.
     2.  Type of material used for impermeable layer:  Clay is the
impermeable material specified in the closure plan.
     3.  Depth of impermeable layer:  It is assumed that 2 ft. of clay
will provide an adequate cap.
     4.  Volume of material required (Line 1 x Line 3):  The amount of
clay required is 32,428 yds. (48,400 x .67 yds.).
     5.  Source of impermeable material:  It is assumed that clay is
available on-site as a result of previous excavations, at a haul distance
of 800 yds. or less.
     6.  Cost of impermeable material:  Because the material is available
on-site, the cost is zero.
     7.  Depth of topsoil required:  It is assumed that 2 ft. of topsoil
will be adequate to ensure that the roots from vegetation of the fill
area do not penetrate the clay cap.
     8.  Volume of topsoil required (Line 1 x Line 7):  The amount of
topsoil required is 32,428 cu. yds.
     9.  Source of topsoil:  Again, it is assumed that adequate topsoil
is available on-site from previous excavations.
    10.  Cost of topsoil:  The cost in this case is zero, since the
material is available on-site. (If topsoil were not available on-site,
a cost estimate would have to be developed through discussions with local
suppliers, etc.)
    11.  Cost per cu. yd. for hauling, spreading and compacting clay and
topsoil:  In the example, it is assumed that this can be done for $1.20
per cu. yd.
    12.  Cost of placing impermeable portion of cap (Line 4 x Line 11):
Based on these'assumptions, the costs of placing the impermeable portion

                                   9-59

-------
                                             ' I" 'Si'*. '' •: M"!:1, '"j
                                                            i'!!l	.iii'l'l'l'
of the qap would be $38.914.
  liii'11" ,  ,!!lL ' ' ,„  ,  I'1 •'  " ilili  •    ''„  '  '         ! ,„•   !' '   , „        • , I'll!!	i „ ซ  ', ' ป,  ||      • '.  :    	
     13.  Cost  of placing topsoil  (Line 8 x Line 11):  Based on  the assump-
                                                              i1
tions. the costs of placing topsoil are also $38,914.
 !ป lllPlWfl    ,„,	 i |	• .;;, ji,,  ,. 1p|< ii|  ,, ,   '    ,••••;   • ,i ,  ||,;|	 '  , ,	 ,   t	 |nl,, ,']i  "" • |l'  ซ  , 'if „,,>,,   , i ..  jj ,  ,>  , i   „• •    ;•
     14.  Total costs of final cap  (sum of Lines 6, 10, 12, and  13):   The
total costs of the final capping  operation will be $77,828.  This does
not include administrative expenses or contingency planning, both of
which are calculated on Worksheet G.
D.   Planting  Final Vegetation.                 •      ' "
     As in  the above worksheets, it is  assumed that all necessary  equip-
ment: is available on-site, but that material and  labor costs will  be
accrued during the closure exercise.
  i..;;,'"' ;  ... • f 	.;•..!...ฐ ,-,_„..          ,,  .   • , ;  ••      '     .      	    .;•.(•.
     1.  Area  not yet vegetated:  The area remaining open at the time
of closing  is  10 acres.
  |....    i in •  ;r>.  XH  .   ,            ,,,,,.,    ' ,;"'•	 - •   .. .j!;;  ,   ! " 1 "i   :    '•;
     2.  Area  already closed but requiring replanting:  It is assumed
in this case that 5 acres of the closed portion of the landfill require
replanting,- due to the failure of original vegetation efforts.
     3.  Total area to be planted (Line 1 4- Line 2) :  The sample
case provides  for 15 acres to be planted during closure.
  t ,j. i  '    . 'j.'a,  HIM   :„   ,  .'    -  „:•      -.  ' , .    ,  , ;	 ... ,]!-,..,.   ._,; , j.  j    , . •	;,,   :  .; .
     4.  Type  of vegetation to be used:  In this  example, it is assumed
  i" >  i'   . .  . .'ST!;  .; , '   •','••   • ..'     ...; '  ' ป	   ; •	   "i  '.'.i';!."   '"i. '  I! ...  • ;(. :" - '•.:'   • '••• •• •
that coarse field grass  (a mixture of rye grass and Kentucky fescue)
will be employed for final vegetation.
     5.  Quantity of seed used per acre:  According to industry suppliers,
150 Ibs. of seed should  be applied per  acre.
  T	 :,..    ;;;;[.  "."i .  '! , !  :    ".   •     : '  :  ' .    .  • '  :i .  .?'..   ;.!  I-' •' ..   .' ''  '  -.
     6.  Cost  oฃ seed per pound:  Calls to local  suppliers determined that
seed is available at $.50/lb.
     7,  Total cost of seed (Line 3 x Line 5  x Line 6):  Given  the above
assumptions, the total cost of seed will be $1125.
  I';., '"       'I'll  I.'';, i  ,   j •	ill1!1  >    ,:..'••   '   -1.  '"'I ,.' . 'il. ' :!i; '': "  " -I ' .1 , !,"  .     :'  "
  :-  8.  Type  of fertilizer to be used:  Given the topsoil and  climatic
conditions,  10/10/10 fertilizer is assumed to  be  adequate.
     9.  Quantity of fertilizer per acre:  .25 tons is assumed  to  be
reasonable,  given the quality of topsoil and the  climatic conditions.
    10.  Cost  of fertilizer per ton:  According to local suppliers,
fertilizer  is  available  for $200/ton.
                                    9-60

-------
     11.  Total cost of fertilizer  (Line 3 x Line 9 x Line 10):  Given
the above assumptions, the total cost of fertilizer is $750.
     12.  Cost of soil preparation per acre:  Preparing the soil includes
both disking and fertilizing and is assumed to be $100 per acre.
     13.  Total cost of preparing soil (Line 3 x Line 12):  The total
cost of preparing soil, excluding materials such as fertilizers, is,
given the above assumptions, $1500.
     14.  Cost per acre of seeding  (excluding cost of seed):  It is
assumed for the sample facility that seeding will cost $150 per acre.
     15.  Total cost of seeding (excluding seed) (Line 3 x Line 14):
Given the above assumptions,, the total cost of seeding for the facility  is
$2250.
     16.  Cost per acre of mulching:  The cost per acre of purchasing and
applying a hay mulch is assumed to be $120.
     17.  Total mulching costs (Line 3 x Line 16):  Given the above assump-
tions, total mulching costs, including costs of hay, are $1800 for the

     18.  Total costs for vegetation (sum of Lines 7, 11, 13, 15, and 17):
The total costs for establishing vegetation are $7425.

E.   Gjound-rUater Monitoring                             •
     Assume that closure of the landfill will require a total of 90 days.
In order to determine the maximum possible ground-water monitoring costs,
the most extensive monitoring needed at closure is assumed.  Assuming
that ground-water quality analyses are required annually and ground-water
contamination analyses are required semi-annually, the most expensive
case is that in which both set's of analyses are required during the 90-
day closure period,
     1.   Number of wells monitored:  For the sample landfill, it is assumed
that eight wells would need to be monitored.
     2.   Number of samples per well:   One sample is taken per well for
both analyses.
     3.   Total number of samples (Line 1 x Line 2);  Given the above
assumptions, eight samples are required.
                                   9-61

-------
     4.   Number of hours required for  collecting the sample:  It  is
assumed  that  experience has shown that  2  hours are sufficient to
gather samples  from each well.
     5.   Total number of hours required  for collecting the samples
(Line 3  x Line  4):   For eight samples,  16 hours are required for collec-
ting the samples.
  I'll I i I . ;,-':! ป' Si!!!	I" '(	Bl i . '  -   !:i: ซ  <	 ! 'V, 	i '.••'• ,  ,-',;, :,i,f "? ' v'i , ,,i  '"il !';,*v, 8H',i!	h ":,•":> I, il'!",!" ill, I" "I'i, i"' .''•:, ,';  ,  '•    '",":!,	H, ;""
     6.   Number of hours required for  preparing and delivering the
sample:  It is  assumed for the example  that experience has shown that
this can be done in 3 hours.
     7.   Person-hour costs for collecting samples:  Assume that the
fully-loaded  costs, for labor required for collecting, preparing and
delivering the  sample averages $15 per  hour.
                                                             il
     8.   Total sampling and collecting costs   ((Line 5 + Line 6) x Line 7):
  if'ii.i  'I"   ''., i^iliiiii, •. Mil • ",'• 5: '"'' 'ii:i';ปi  ,'•  :•:..,.'. ,ir<,:,' ;, ;,.';,„'  -''i J. v;1;  ; ';! 1 ,   Ai;1'" ;,  :.;•• i >ii>.'iil*ii	:'•'(.':   .i-,"    •".•'•. it	:i*l'i!iiii •	
This results  in total sampling and collection  costs of $285.
     9.   Number of ground-water quality  analyses:   One analysis must
be made  for each well sample, for a total of eight.
    10.   Number of ground-water contamination analyses:  One analysis
must be  made  for each well sample, for  a  total of eight.
    11.   Unit  cost of ground-water quality analysis.  It is assumed
that the cost of an analysis for the following parameters is $77 per
sample:    	         '     '     '            '    	\
          Chloride                  $ 6/sample
          Iron                      $12/sample
          Manganese                $12/sample
          Phenols                   $25/sample
          Sodium                   $12/sample
  :   •    • Sulfate '       |         i $10/sample	^ ^^  i     ^ .
    12.   Cost  of  ground-water contamination analysis.  It is assumed
that an  analysis for the following parameters  is  $108 per sample:
          pH                        $ 4/sample
          Specific  Conductance     $ 4/sample
          Total Organic Carbon     $25/sample
  y 2,; ;      \          ,    ' ' 	  ' "   • '    ':;:", i"ฐ  '„    ;" i"";""i'ii' , •    •• • L:;I;; „   ';„!,{
          Total Organic Halogen    $75/sample
    13.   Total ground-water quality analysis  costs (Line 9 x Line 11):
For eight samples at $77 per analysis,  this yields a total cost of $616.

  I	••  :    '  ;>| !"':*;! ;„;,    : ,/,  •   ,'. , ';9-62

-------
     14.  Total  ground-water contamination analysis  costs'(Line 10 x
Line 12):   For eight  samples at $108  per  analysis, this  yields  a total
cost of $864.
     15.  Total  analysis  costs  (Line  13 + Line  14):  The total  analyses
costs, therefore,  are $1480!.
     16.  Number of technical hours for administration:  This includes
all time necessary to administer and  report  the data from  the analyses
and is estimated as 8 hours.
     17.  Person-hour technical costs:  The  fully-loaded cost required
for this work is assumed  to  be  $30 per hour.
     18.  Total  technical costs for administration (Line 16 x Line  17):
Given the above  assumptions,  total costs  for administering.the  tests
are assumed to be  $240.
     19.  Number of clerical .hours:   Assume for this case  that  5 hours of
clerical time, are  required.to produce the necessary  reports.
     20.  Per-hour clerical  costs:  Assume the  fully-loaded costs for
clerical work are  $8  per  hour.
     21.  Total administrative  costs  (Line 19 x Line 20):  Given the above
assumptions, the total clerical costs are $40.
     22.  Total administrative  costs  (Line 18 + Line 21):  The  sum  of
technical and clerical costs  are  then $280.
     23.  Monitoring  equipment  maintenance:  It is assumed that an  average
of $150 is required for a 90-day  period to ensure adequate maintenance of
monitoring equipment  and  wells.
     24.  Total monitoring costs  (sum of Lines  8,  15, 22, and,23):  Total
monitoring costs,  excluding administration and  contingencies, are then
$2195.                      ;
                                        '

F.   Fence Maintenance     :
     For a 75-acre site,  assuming that the site is square,  each side of
the site is 1807 feet  in  length.  The perimeter of the site is then
7228 feet.
     1.   Length of fence to be replaced:  It is expected that some
sections of the facility's security fence will have corroded and will
have to be replaced.   Our estimate is that 10% of the perimeter fence
will have to be replaced.  ,                  ;
                                  9-63

-------
      2.   Unit cost  pfreplacing fence:   The security fence around  the
 facility perimeter is  a galvanized metal chain link fence 6 feet high.
 this fence is made of  #9 wire.  The unit replacement cost for this
 fence is $13.06 per  linear foot.
      3.   Total cost of replacing fence  (Line 1 x Line 2):  The cost  of
 fence replacement  is the product of the  length of fence needing re-
 placement andthe  unitcostof replacement,  for a total of $9442.

 G.   Professional  Certification
      1.   Number of person-hours  required for inspections:   It  is
 assumed that  ง0  hours are required  for periodically inspecting  all as-
 pects of closure of the landfill.
      2.   Cost per person-hour:   In this case, assume that  a registered
                                                                ||
 independent professional engineer may be hired at a cost  of $75 per hour.
     V,\ ' •*    :" ,•' ..... ! il,'. T!i'"'!l||,li ' "',!'', • "' '„ '•'„ ..... I ..... !'" if I'M1 ''• ir1 '" I:1!! i '"l|,',iii, ..... "ill:1:,,, 'I!,1 ' III' !'n "iNi:1 i1!1 up  „, " il'ti Illli IHl'i, "I'll,:, Jib ffi'M ...... .Jnli!1''1 .'l|, "!!,,,i '!' ,i'"l' I III1 ' ปiil|| ,l!!'i ' " '•'•: ,,  ...... I'll , , '" • ',  '  i.
      3.   Total  costs of independent professional engineer's time  (Line
 ,'l x ..... Line 2) :'  '""""This yields" a total cost of $6000"" lor" "tie ...... independent ......
 ""professional  "engineer.  ............... .........     ....... ................ " ........ ................
      4.   Number of technical hours required for administrative duties:
     liiiLiiiir i ' i i  " i"" ..... ;"iii!iir mi w i ..... ,  ..... . i ..... /iii'i'ik!,' "iLiv;1"   ' , , ", ir ni'ii'ii1 ,,. .• , i. •? ; ....... ', ,  : :i'. .inn iin \v '\^i'f."".t',vimtf vi • ""," i i,;; '| ' " •  ' ir, ..... ;,, ...... i*   •> i* ปii
........ Assume that '8*'" "hours "are ..... required" 'from ...... the ........ owner /operator's  staff for
 administrative duties connected with employing an independent professional
                                                                l!
 engineer.
     ^-5. i ....... Person^hour .costs'' for technical" administrative  duties:'  It' is
 assumed that  the total fully-loaded costs for the owner/operator's rtaff
l" ...... [.>!"' -i", ,  i"i'''  >{' ..... '|i jt'l-iill "fi  S' ' '" t1 fl'.'.V ..... • ' i ", : .' • ....... i •;, .. • > ' : il: ill1' . i ,'..'• .li'iii1"'!' .. ;, I 'i J ' r; .........   t J.
 are $30 per hour.
     ......... e". ' ..... Total  "administrative  costs " for" "technical ........ labor  (tine 4 x Line 5):
 Given the above  assumptions, the  total administrative  costs for technical
 labor are  $240.
       7.   Number of  clerical hours required  for administrative  duties:
                                                                !!
 Assume that 5 hours of  clerical time are required for the necessary typing
 and certifications.
       8.   Person-hour  costs  for clerical administrative duties:. Fully-
 loaded costs of clerical  time  are assumed to be  $8.
'i. '"I '"'ii'l',!*1 • Ill"  III I ,'" I
             ,               ....  ,   ,, ...    ,     . ,„     ,,,  ... ,,„ ,,   . ,,
       9.  Total administrative costs for  clerical labor (Line 7 x Line  8):
     ........................................ : ......... : .................. ' .......... : ......... : ............................... , ................ |  .................
  Given the above Assumptions, total clerical costs are  $40.

-------
   . 10.  Total administrative costs  (Line 6 •+• Line 9):  Summing  technical
and clerical labor, the total administrative costs are $280.
    11.  Total certification costs (Line 3 -f- Line 10) :  The total costs
for certification, including the engineer's fees and administrative costs,
is then $6280.

H.   Total Closure Costs Including Administration and Contingencies
     Lines 1.through 7 of this Worksheet simply summarize the total closure
costs, excluding administration and  contingencies, from each of  the prior
worksheets.

      8.   Total of  Lines  1 through 7:  The total costs for the activities
 listed in Lines 1  through 7 are  $130.020.
      9.   Administration:   For  administrative  tasks,  including taxes,
 insurance,  and administration  and supervision not  included elsewhere,
 a total of 15  percent  of  total costs from Line  8 is  used.
     10..  Contingencies:   A general provision  for contingencies  of  15
 percent of total costs has been  included.
     11.   Total closure costs (Line 8 + Line 9 + Line 10):   The  estimated
 total closure  costs  are  then $169,026.
                                    9-65

-------
             	i  .'  (  ^ if;	   '  LANDFJLLS;,
                 WORKSHEET  A - DISPOSING OF INVENTORY'
                                                           I- ii •	 T :;'
         ., ซii"ii ป>i ,  '.	• i
                                              ••j : ;;::	;  •	:fej! f
1.   Volume of waste when processed for  disposal
2.   Estimated volume  of residue and contaminated
     soil to be  disposedthrough on-site landfill
  'i .ji'in,;:!!1" i ,  i!     ii   i    , ,',n;; IFI,,, ,,i  ,i    i • ;, • ,n< i   	 „ • • 	  •  <   mil1 f i f,	%„
     operation
3.   Total volume  of waste to be landfilled on-site
     (Line 1	+ Line 2)	   '  '    '"    '	 "
4.   Estimated cost of constructing trench
5.   Estimated cost of placing waste in
     trench
6.   Total cost  of disposing of inventory
     (Line 4 + Line 5)
                                                        800  cu.  yds.
                                                        600  cu.  yds.
                                                        1400  cu.  yds.
                                                       $18,000
                                                       $  6^000
                                                        $24,000
         ;'M- '••ill
            .11	il
                                                         I,,, ",'
                                                                                  III  I
!•	H
                                 9-66

-------
                                 LANDFILLS
                WORKSHEET B - DECONTAMINATING THE FACILITY
 1ป   Area of facility contaminated                       1800 sq. yds.
 2.   Depth of material removed                           .33 yd. (1 ft.)
 3.   Cost of removal               "                      $840
 4.   Quantity disposed on-site (see Worksheet A          600 cu. yds.
      to develop cost)
 5.   Quantity disposed off-site                          0
 6.   Cost to decontaminate equipment                     $1000
 7.   Volume of waste resulting from decontaminating      25 cu. yds.
      equipment
 8.   Unit cost of off-site disposal ($/cu. yd.)
 9.   Unit cost of hauling ($/cu.  yd.)
10. ,  Total cost of disposing off-site  (Line 7 x Line 8)
11.   Total cost of hauling (Line 7 x Line 9)
12.   Total costs of decontaminating the facility
      (Line 3 + Line 6 + Line 10 + Line 11)
                                    9-67

-------
   i	   :;
                                 LANDFILLS
                   WORKSHEET c - PLACING FINAL" CAP
 1.   Area to be capped (include sum of all portions
      of thefacility remains open and any portions of
  ;  ;"""',,the„ faciiity  opened to' dispose" of "inventory' an';!
      wastes from the process of decontamination)
 2.   Type of material used for impermeable layer
   i	ii
                ./.Hi
                ill,
 3.   Depth of material of impermeable layer
 4.   Volume of material to be used for impermeable
    |:	layer (Line  1  x Line 3)
 5.   Source of impermeable material
   fit
         lnl i   , IjJl];1 II i"'!;,!!!,! ;  	I, ',   i ' ,|    '    ' '  !ป  	'
6.   Cost of  impermeable material
7. .''..Depth "of" topsoil	
8.   Volumegf Jppsoil (Line 1 x Line 7)
9.   Source qf topsoil
10.   Cost of  topsoil
11.   Cost per cu.  yd.  for hauling, spreading  and
      compacting
12.   Cost of  impermeable portion of cap
    Jiiii,:,!!'1  •   '	' ",;i!iLII!ll'illl  .1 'iniipr  •• n	 , urn1,  •'.     ,„...',.  • , 	   !, :• r    ; , ;'
    :':",i (Line 4"	x Line 11)
13.   Cost of  placing topsoil (Line 8 x Line 11)
14.   Total costs (Line 6 + Line 10 + Line 12  +  Line
                                                       ฅ" •••
                                                      "'•iiiii, ,i
                                                           48,400 sq. yds.
                                                           (10 acres)
                                                           Clay with perm-
                                                                    of 10~7
                                                      13)
                                                          •'•'. .„•'.: ;;;i; .   ..... .  ',' •    „;;
                                                           ....... f , ' i   .I.  , ,     I.
                                                           .667 yds. (2 ft.)
                                                           32,428 cu. yds.
On-site from
previous exca™
	II	'
yatipns
o	''':
.667 yds,  (2  ft.)
32,428 cu. yds.
On-site from
previous exca-
vations
b	
$1.20

$38,914"
 k "HI U |i < 'i '  i    T	< ..    , .nil
$38,914
$77,828
                                    9-68
   t	•.;
                                         .:	.:	•	::;	:	1;	'

-------
                                 LANDFILLS
                  WORKSHEET D - PLANTING FINAL VEGETATION
 1.   Area not yet vegetated (should be approximately
      equivalent to area remaining open)
 2.   Area already closed but in need of some replanting
      prior to final closure
 3.   Total area to be planted (Line 1 + Line 2)
 4.   Type of vegetation to be used
 5.   Quantity of seed per acre
 6.   Cost of seed per pound
 7.   Total cost of seed (Line 3 x Line 5 x Line 6)
 8.   Type of fertilizer to be used
 9.   Quantity of fertilizer per acre
10.   Cost of fertilizer per ton
11.   Total cost of fertilizer (Line 3 x Line 9 x
      Line 10)
12.'   Cost of soil preparation per acre
13. .  Total cost of preparing soil (excluding
      materials) (Line 3 x Line 12)
14.   Cost per acre of seeding (less materials)
15.   Cost of seeding  (Line 3  x Line 14)
16.   Cost per acre of mulching
17.   Total mulching costs  (Line 3 x'Line 16)
18.   Total costs for vegetation
      (Line 7 + Line 11 + Line 13 + Line 15 + Line 17)
10 acres

5 acres

15 acres
Coarse grass
150 Ibs.
$.50
$1125
10/10/10
.25 tons'
$200
$750

$100
$1500
                                    9-69

-------
                                 LANDFILLS
                   WORKSHEET E - GROUND-WATER MONITORING
                               i        i      
-------
WORKSHEET E - continued
23.  Monitoring equipment maintenance
24.  Total monitoring costs; (Line 8 + Line 15 +
     Line 22 + Line 23)
$150
$2195
                                   9-71

-------
            "I1!
                                LANi)FILLS
                     WORKSHEET F  - FENCE MAINTENANCE
                                   '''.''  '  ' •'  '•> ' .'  i :" •• 'I:. ,i""'k'
1.   Length  of fence to be replaced
2.   Unit  costof replacing  fence

3.   Total cost of replacing fence
  i|p;  ' (Line 1 x Line 2)
   723 feet
 1  $13.06/
"! '""linear ft.
   $9442
               11 "nil
                                     9-72


-------
                                LANDFILLS
                  WORKSHEET G - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required for inspections
 2.   Cost per person-hour
 3.   Total costs of independent professional engineer
      certification (Line 1 x Line 2)
 4.   Number of technical hours required for administrative
      duties
                            l
 5.   Person-hour costs for technical administrative duties
 6.   Total administrative costs for technical labor
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative
      duties
 8.   Person-hour costs for clerical administrative duties
 9.   Total administrative costs for clerical labor
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)
11.   Total certification costs (Line 3 + Line 10)
80 hrs,
$75
$6000

8 hrs.

$30
$240

5 hrs.

$8
$40
                                   9-73

-------
                LANDFILLS
w	 H- TOTAL COSTS OF CLOSURE  INCLUDING
    ADMiNISTRATiON AND CONTINGENCIES
                                    " |i "
                                      *'•:,„ '
P                "V  •     ;  •          •  •        "	    <  ••  ( ,,   ; i
      ;,     ,  Hj,  : ..j  ,    , ,'•;''   .  •    ,;   ., ,  ;  :'• .'a  •	 •.-'-	 ,i:* . ,• 	,:,i:is
 1.    Cost of disposing of inventory (From  Worksheet A)
 2.    Cost of decontaminating  the  surface and ancillary
      facilities (From Worksheet B)
 3.    Cost of placing  the final cap  (From Worksheet C)
 4.    Cost of planting final vegetation (From Worksheet  D)
 5,    Cost of ground-watermonitoring (From Worksheet ,E)
 6.'	';	Cost ""'""'of''"'fence maintenance ""(From Worksheet F)
 7.    Cost of professional certification (From Worksheet G)
 8."	  Total of Line I ""through  Line"/7	  •	   ^	
 9.	/'Administration
10.    Contingencies
11.    Total costs  of  closure (Line 8 + Line 9 + Line  10)
 '".|, , !|, ซ"i!| I,,	jli'1',  , 'ซ "'. ' ,
 "I"	2l,b8'd
  $   2,850

  $  77,828
'  $   7,425
  $   2,195
  $  9,442
  $  6,280
'  $130,020
  $ 19,503
•''$	19,503
  $169.026
                                                                 '"si I*
                      9-74

-------
 9.5
EXAMPLE - INCINERATORS
     A 12-acre  incinerator  facility has bulk storage  facilities  for  120,000
gallons of slop oil, 120,000 gallons of phenolic wastewater,  and 1,000ป000
gallons of organic sludge.  Waste is also delivered in 55-gallon drums;  a
maximum of 600  drums may be stored at the facility.   In addition to  these
delivered wastes, the facility normally contains an "inventory of 50  drums
of non-combustible ash from, the incinerator.
     The incinerator is designed to operate  at 16 gpm with the following
feed mixture: 4 gallons of slop oil, 4 gallons,of wastewater, and 8  gallons
of sludge (a 1/1/2 ratio).  The total operating horsepower of the incinerator
(including pollution control equipment in the form of a caustic  scrubber
used to remove chlorinated compounds emitted from the slop oil)  is 350 HP.
The following worksheets are based on this facility description.
                                  9-75

-------
         SAM?LE CLOSURE COST  ESTIMATING WORKSHEETS:  INCINERATORS
                                                              i
A. ''''Xl'haracter'i'z'lng the Waste Inventory          	     '"'•".
  " ป;!': Worksheet:^ A	"is used  to describe each waste accepted a,t the site,  For
the example, woricsheets must  be prepared for each of the following wastes:
slopoil,phenolic wastewater, and biological treatment sludges.  For each
waste product  accepted, the following information is required:
 '•" |;:1.	''Describing the waste: ' -Describing the origin	and general nature
  t,, •"'i",ill ' i, '  ,' , 'i "'i jiLiij  " i'iKi '	  "  ."   I,,,'11'""'  '   "  '  ป ,     •    . •:•   ,  ' .' ,• i: V1 ", i i  i:l :• r " • "    •'.           i
of the waste.1""  '""         ''           '                 	   . '  ,\''  .         ป
     2.  Chemical composition:-  Chemical composition should be expressed
in weight percents for major  components and parts per million (ppm) for
tracecomponents.  This information should be readily available to  the
ppelltbr from  the bill of">lading for each waste shipment.
     3.  Physical state of  the waste:  this describeswhether the waste is
a liquid, solid, or mixture.   This information is utilized in making,estimates
of solid residues requiring disposal (Worksheet B).
     4.  Heat  of combustion of the waste:  The heat content  (expressed in
BTU/lb., or BTU/gal.) of  the  waste products.  This information is used in
determining auxiliary fuel requirements  (if any) on Worksheet C.
     5.  Specific gravity of  the waste:  The specific gravity of .the waste
at 60ฐF  referenced  to water at 60ฐF is used in the exampleproblem.
     6.  Closure inventory:   For the example, it has been assumed that the
operator has identified  from experience  that the maximum inventory  tie has
   ill  ' ii, ,   „„ ป  i, MM!1  ,i:i:!!lป!,l  ,   j         • „    : ' •         ,   1	• '• iliiV: „ J1  ', •! ,,,,! , ,|| !',''•• • ;' : ' '  "i1 ,ป;„      , "  • , ;•• "I
ever, had stored pn-site was a 14-day backlog.  We will  assume  that  this
inventory  iscomprised  of the total components:  224 drums of slop oil
 (12,320  gallons),  224 drums of phenolic wastewater (12,320  gallons)  and
152"  drums  of sludges (8,360 gallons);  the bulk storage  tanks contain 28,000
gallons  of slop oil, 28,000 gallons of phenolic  wastewater,  and  233,560,
gallons  of organic sludges.   Under these conditions, the incinerator will
be able  to treat its inventory through seven days of burning its optimum
 feed mixture,  and seven days  of burning  sludges  alone  (through  the  addition
     "                                                         i
 of auxiliary fuels).                                   .                  '
                                       9-76
'i : _ i iJifS, i , :;!!ซ!!
                                                           ' i , if*' jiifl'1 11' •ซ>•

-------
 B.   Treating  the  Inventory
      It is  assumed that  the  Inventory  on-hand at  the  time of closure will
 be incinerated on-site.  All equipment necessary  for  the  operation of the
 incinerator is assumed to be in complete working  order.
      1.  Time  required for treating the inventory:  It will  require 336 hours
 (322,560 gallons of waste 4-  960 gallons throughput per hour).  If  it is'
 further assumed that the incinerator is on-stream 90% of  the  time,  the total
 time required  for  treating on-site inventory  is 373 hours.
      2.  Manpower  requirements for treating the inventory:  The total number
 of personnel required to operate this facility (including plant operators,
 equipment operators, guards, maintenance persons,  and laboratory personnel)
 is estimated as six.  Therefore, total man-hour requirement for treating
 the inventory is 2238 hours.
     .3.  Cost of manpower:   The average hourly wage rate of a plant operator
 (including fringe benefits  and labor burdens)  is assumed to be $20.
      4;  Total  costs of operating labor during inventory treatment (Line 2
 x Line  3):   Given the above  assumptions,  labor costs  for this phase of
 closure are $44,760.
      5.  Fuel requirements for  treating the  inventory:   These represent both
 the cost of utilities  consumed  in  order to treat the waste inventory, plus
 any auxiliary fuels which had to be purchased. Each of  these items is
 separately  costed'below.      ''•''•'
      6. Electricity requirements  for treating the inventory:  The  inciner-
 ator  is actually in operation for  336 hours.   Electricity  requirements for
 the example'are equal to  350  HP x  .746  g- x  336 hours = 87,730 kwh.
      7. Costs  of electricity:  Electricity  is assumed to be  available at
 a  cost  of $.06/kwh.                                                     - '   ..
     8.  Total  costs of electricity (Line 6 x  Line 7):  Total  electricity
 costs for the example are $5264.
     9.  Auxiliary  fuel requirements:  During  the  first 168 hours of'inven-
 tory treatment,  the incinerator will be receiving an input feed of 25% slop
 oil, 25% phenolic wastewater, and 50% organic,sludges.   This feed has a
heat value of 2900 BTU/lb. and will burn autogenously.   During the remaining
168 hours, the feed will be comprised entirely of sludges,  with a heat
value of 700 BTU/lb..; this mixture does  require auxiliary fuel inputs.

                                   9-77

-------
'';  :,  j|lp. ^Ty^e	of auxiliary  fuel used:	  It is assumed that'"#6  fuel oil is
!„!  ,  llllijllll III!1 ''i'l'll ' ',d,"' jit"'",! i'1 jfLlI/Tiji'11  f'Wti 1JI i,n :,. "'j!1'1 ' ป',„",' "' "'i1'" ' ซf  '"  ' : '" iT ..'„ป'. "'I '  ' !i" i' '" '  • , "!'ป,!!!ป! '''', 'lii.i liiliCli! i;11*1'!!''!]*,* i,," *'• 'I "' ""I'1" • '!'"."'.,iปป	j|u	"i||",'  ': i , "."f1 !!!< i'i'.
'"'used	as  the auxiTiary  fuel.
      11.  Quantity of fuel required:   Using engineering  analysis, and
 assuming  an average heat value  of154,000 BTU/gal.  for  fuel oil, total
                               '   '   	,	  i,        .  *
 auxiliary fuel requirements are estimated at 10,456 gallons.
":  "" ?'ฃฃ''	'gSst	'ol	'&^l^^/&li''i:^''aaami'	that'	II""	fuel "oil "'Is''"available"
 to  the operator" at $.90  per gallon.
       13.  Total cost of auxiliary fuels (Line 11 x Line  12):  The total
     	     	;	  |	
 cost  of auxiliary fuel inputs  is $94lO.
       14.  Total fuel costs  (Line 8 + Line 13):  Total fuel costs are $14,674.
       15.  Chemical requirements:  This  category includes all chemicals,
 Italy's ts,	adsorbents,	"and  other	supplies'" "consumed " during " inventory ""treat-
 ment.   In theexample, the  only chemical required is"the causticconsumed
 during flue gasscrubbing of  chlorine  entrained  inthe  incinerator waste
                                                                 i
 stream*  i   i i	    _     ^	          :	
     I" 16. Type of chemicals  used:  It is  assumed  that the caustic will  be
                                                                 i
 purchased as a  50% solution.
       17. Quantity  of  chemicals required:  There  are 40,320 gallons  of  slop
  oil	in the Waste inventory'assumed to  be present at the time of closure.
  This is  equivalent to  319,334  Ibs. of  slop  oil  (40,320  x .95 specific
  gravity  of  slop oil  x 8.34 Ibs./gal. water).   Since the chlorine content
  of the slop	oil	is  assumed to"  be no  greater "than" 3  "percent, "the maximum
  quantity of  chlorine to  be scrubbed  is 9,580 Ibs.   (270 moles).  Assuming
  thaf'l ''mo! e"";ol 1|OH is	Required"" fcb	"neutralize	'i" mole "of chlorine,	270  moles ""
  x 40':'ibs. "NaCfk/mole ป l6'",8db'!' Ibs. '"JtaOH cons'ump'tion	
       18. Cost  of  chemicals required:  Caustic is assumed to  cost  $.0825/
  dry Ib.
  -_  ;|j:	if:l9.""; Total "cost' of 'chemicals' (Line ^7  x Line 18) {^ The "total" cost  of
  chemicalsconsumed during  inventorytreatment is $891.
        20. Disposing or treating residues  -generated during inventory  treatment:
  The residue generated Quiring''''inventory'treatment	is" a "powdery solid, inciner-
  ator ash.   The ash has a specific gravity  of 2.5,
       21. Amount of residue on-s"ite after treating  the inventory:'  There
  are 50 55^ga":[::Lo~	drjims'of"	ash	stored "on-site "at	th"e"'point  of"closure " (each
  Weighing":'il56=	"iFaV, for" a "total "of 57"",500  Ibs"".)".	   In	addition",  residues
                                         9-78

-------
 are generated by processing the waste inventory.  The sludges incinerated
 in the example are assumed to be 10 percent solids; one-third of  the solids
 are assumed to'be non-combustible.  The slop oil and wastewaters  processed
 .by the incinerator produce no ash.  Therefore, the amount of new  residue
 generated = (total amount of sludge in inventory times specific gravity
 of the non-combustible portion of the materials times the portion of the
 sludge that is non-combustible), or:
          241,920 x (2.5 x 8.34) x .0333 = 167,968 Ibs.
 Total residue to be disposed,of is equal to 167,968 Ibs. and 57,500 Ibs. -
 225,468 Ibs.
      22.  Method of disposing |of ash:  It is assumed that the incinerator
 ash is put into drums and transported to a secure landfill.   The residue
 .generated during inventory treatment can be placed in 146 drums, making
 the total number of-drums to be* disposed of 196.
      23.  Unit  costs of disposing of  residue:   The costs  of disposing in
 a  landfill are assumed to be $50/drum,  according  to  industry specialists.
      24.  Total costs  of disposing of residue  (Line  21  x  Line 23):   Total
 costs  for the  sample  case are  $9800.
      25.  Costs of hauling residue to landfill for disposal:   In  the example,
 it is  assumed  that the nearest landfill  that  will accept the drummed
 residue is 50  miles away, and  that trucks  with  a  carrying capacity.of 40
 drums  are rented at an hourly!  cost of  $60.  At  a  speed of 40 mph,  and
 assuming  four  hours for loading/unloading  each  trip, the  total hauling
 costs  are estimated at $1950.
     26.  Total cost'of  treating and disposing of inventory (sum  of Lines
 4,  14,  19, 24, and  25):   Given the above assumptions, the total  cost of
 inventory disposal will be $72,075.

 C.   Decontaminating the  Facility
     In order  to completely decontaminate the incinerator facility, the opera-
 tor must  see to it  that all storage tanks and liquid waste feed  lines are^
 cleaned,  that wastewaters from the cleaning process are properly disposed
 or treated, that all equipment:  structures and containers  left on-site are
 decontaminated,, and that all contaminated soil is  removed properly.  These
various activities are individually costed below.

                             I      9-79

-------
Ji i!
                                                                il
  Ivnii! ! ',,  'H,,;! J' ' ..'liil'l'I , i, JOi  ' • •'      T ii,,!v ',   r ••ป ,,  •' , i, ';>',,;, •  ' •> ' •  ' /I- i';i!|,'"in; "i'l:|i. , | |,;|i|r ,,',,„,, pi <,i< ; • ,,J;l ] ป;;i	llV! i'  , ,,i '  Jh,." ; , '  ;• i'

Tank"" 'cleaning 	"	'  ' '	'	
     1.    Storage tank cleaning:  The  total volume of storage capacity  to
becleaned is 1,240,000 gallons  (120,000 gallons of slop oil storage,
120,000  gallons of phenolic wastewater storage,  and 1,000,000 gallons of
organic  sludge storage).
     2.   Method used:  The cleaning method selected for the'sample case
is  s team-cleaning.
     g.   Unit cost of cleaning:   Renting equipment, labor,  and operating
  BIIIP ,l	ii"'i,|i,.",11	if	IIIEIIII:,	HP| "i,Will , "•,!,„   IB,:,,, .Ji I'!!?! 	IFm • "ii!1" .ill!1;::*'"11 iHi,!1"]:,,r i,i''W1' I	, 'iiillli'"':!!1!' , "Bliiii/VI. 'llPli' 'Li."!'.'.*.! T "B	!'" '""1| 'J1	 "•' "  	
edits  lor 1ง06gal./hour of cleaning equipment are assumed  to be approxi-
matelyง.02/gal.  of capacity  cleaned,  based  on information  from the  Means
construction  cost guide.
  |l|  I        111  Illlllllllll   III    I     	 ,','!', 	 ; „' :,'•'! " ' '' >>!'!" lll,l|!'!1! " i'l'i::;.! „,">	 J,'-'	"I"""1"" ' <.'''', .I,,'!'i	1,1 '"• ,,!!!!	I' ,,,',"'i'i:'	ป Hi' T	,':	illl'l" •:: •"..	11'	"•'	:_•	 •'  	
waste treatment sites  issued  by the Texas  Department of Water Resources,
'tig;	amount	o!f/lcontam^a'ted'll'washwaters '"produced by steam-cleaning  can be
 assumed to  be equal  to .125  times  the volume of  the  tank being  cleaned.
  ;'=•'!' 6. 'Quantity' of  cleaning" residue	generated	(fine"" 1	x"" Line" 5) :
 155,000'!gallons' of contamined'washwa'ter''are"'generated  in" the example.
      7.   Method of disposing  of residue:   In the sample,case,  residues are
 aiitime'd "to "be	transported	by tank  truck"" to" a	surface"	impoundment  for
  " 1  I        11111  II III  III                     II I     111 1      l| I  I ill         ;     1 111
 evaporation.
  I    8.   Unit costs  for disposing  of residues:   Based on waste disposal
 industry  estimates,  it will cost $.05/gal. to dispose of residues in an
 impoundment.
  Ill"'" I" ".in1":	r	l! JIB" „ in mini'. ,,r '.  ;,:'„' , ,,",' '", .51 '    .,,"„:,,            ,_ .    ..   _ .    ov    _ .. •ป	
      9.   Total costs for disposing of  residues  (Line 6 x Line  8):  Total
  •pin ki'f'h,;  	 ' i ' • Jlllllliillliii1, \ '!l!!",,ililllllli,, i'"ii|,'<''i	11 ,' ' i • ' '" J.III' ,,  , Ii," l'  ":•, n, "Si,1',,' ,   ;< „' I/M!	'," III!,, ,.ii!|i"! I   II I I I 111     II   ||    ':' ,!! •, ", ,!<9"|,!l ' , ป  , '":
 costs of  cleaning residue disposal, given these assumptions,  are $7750.
     10.  Hauling costs for residues:   In the  example, hauling cost  esti-
 mates ate based  on  the following assumptions  - the distance between the
 incinerator and  the surface  impoundment is  100 milesone-way,  a 7000-gallon
  trailer is used, the average trip  speed is  40 mph, and the hourly rental
  1 i   i       i ill    ii   i  ii      i         MI           ii  i n  mil  ii j          Aoftn  " "	"': •	"
  cost  of  truck  and driver  is  $60.  The cost  of one round trip is ?300.
  1    11.  lumber  of trips  required:  The number of trips required for the
                                                                I
  c"ase  is  23.
                                                                                               liiii	I/ 11; :;ป ,,ii
                                                                         I I   'hll'ii ''I1''1" "I'l'llMhrMiF1,,, ! '  if  ,"'. '" . .'! 'Jilih I1',,! ?!	i"'  ""iT	"I
                                                                                          -I K ir,ft',""li:'l"',:, „

-------
      12. Total hauling costs for residues  (Line 10 x Line 11):  The hauling
 costs for residue disposal are estimated at $6900.

 Decontaminating the Facility                                '        '     .
      13. Flush out liquid waste feed lines:  The estimated cost of flush-
 ing out all liquid residues from feed lines on the facility (before the
 storage areas and incinerators are cleaned) is,assumed to be roughly one-
 eighth of the costs of tank cleaning, or $3000 /
      14. Pump out and backfill sumps:  Sumps are to be decontaminated to
 prevent the possibility of rain water accumulating and contaminating these
 portions of the facility.  The estimated costs of this activity are
 $2000.
      15. Removing contaminated soils:  Because of spills and other
 accidental releases,  certain areas  of the waste disposal site such as
 the dikes in areas around storage  tanks may be contaminated.   We have
 assumed in this example problem that  2.5 percent of the area of the site
 (exclusive of reservoirs,  ponds, and  basins) is  contaminated.
          Contaminated area -  .025 x 12  acres x 4840 sq. yd./acre
                            =1452 sq. yds.
      16. Depth of  soil removal:  For  this example,  the  assumed depth of
 soil removal is  one foot.
      17. Total amount  of  soil removed (Line 15 x Line  16):  The total
 amount  of soil removed in  this  example  is (1452  x  .333),  or 484 cu. yds.
      18.  Unit  cost of  removing soil:  Costs of removing soil  (including
 equipment rental) are  estimated at  $1.60/cu. yd.
      19.  Total cost of soil removal (Line 17 x Line 18):  Given the above
 assumptions,  the cost  of removing the contaminated soil from the inciner-
 ator  site is $774.
     20; Costs for disposing of contaminated soils:  The contaminated soil
 is assumed to be disposed in a sanitary landfill.  Based on current esti-
mates, the soil can be landfilled at a cost of $30/ton.
     21. Total cost of disposing of soil (Line 17 x Line 20):  The  cost
of disposing of the contaminated soil  is $14,520.
     22. Hauling costs for contaminated soil:   In- this  example, the
nearest landfill is assumed to be 50 miles away,  the truck used for hauling

                                  9-81

-------
                                                                                I 111
  Ill  i      i  i   ,1:  ; 	  , •  • •	,                     I i i    i  1     I  II
has a carrying capacity of 44,000  Ibs., and is rented at  a hourly cost
        	 ;._	  _t;  ,    ..  ;  	_		^   vv;..  . .. .  _	_	,.;_,.;,L. . :	;	
     23.  Number'1 of trips "required:  "'"Assuming	•	an	average "speed of 40 mph,
22trips  will be required.
     2*4.  xo'taihauling  costs for contaminated soil  (Line  22 x Line 23):
Given  th.:!   J, ............. '   •
      2.  Number of  samples required:  The  inventory treatment phase  of
 closure "is "es tฑmate?', ': ,m '":<  '. •  ' •  V ";i    ""i'-1;;1: -I?  	 ;	.R	,•   '" ar'f!, 'V	Mi' jjii/r ••,..•„• ')•;,.   •   •'.• .wv.i
"'siorial,,engineer.	  	   	     i        ^  ^     | •	
  L : ,4."' Number7of  technical hours required for	administrative ^duties :	
                           •n" 'iihi'ii, ' ," M |	iiM nil , ' ']" i hj', N'ป J  , , 'ij, ' j! i,, f 'j,, ,,,[''," '"ijiiii,!! „}„ ^jivift'	''''' ''	J' '" '•'l""1' ' 	'""' ' ' t    ฑ, -G JS  g
                IE< r W1 .''j^wSff1'	i e,''"" \ I,,,;.,;1 '• "1"1 , ;,|liy .•  f1' '"" ^ !l  ^ ') ^"^ \ ' ^. jni;: • i1 ,. i ''txi* i" >: '  y.:  5 "  '"j '" '''!":"' *t* '' ''	w
                 duties" connected  with employing an independent professional
 engineer.
               if I
               ','11
                                      9-82

-------
      5.  Person-hour costs for technical administrative duties:  It is
 assumed that the total fully-loaded costs for the owner's or operator's staff
 are $30 per hour.
      6.  Total administrative costs for technical labor (Line 4 x Line 5):
 Given the above assumptions, the total administrative costs for technical
 labor are $240.
      7.  Number of clerical hours required for,administrative duties:
 Assume that five hours of clerical time are required for the necessary
 typing and certifications.                     •
      8.  Person-hour costs  for clerical administrative duties:   Fully-
 loaded costs of clerical time are assumed to be  $8.
      9.  Total administrative costs for clerical labor (Line 7  x Line 8):
 Given the above assumptions,  total clerical cos,ts are $40.
     10.  Total administrative costs (Line 64- Line 9):  Summing technical
 and clerical labor,  the  administrative  costs are $280.
     11.  Total certification  costs  (Line 3  + Line 10):  The total costs  for
 certification,  including  engineer's fees and administrative costs,  are
 $1780.

 Ft   Total  Costs  Including Administration and Contingencies.
     Line 1  through 4:  These lines  simply  require the transfer of  the
 cost information  supplied in Worksheets B through E.
     5.  Preliminary closure ,cost estimate  (sum  of Lines 1  through  4):
 For  the sample facility, total worksheet costs are qual to  $137,299.
     6.  Administration:  The costs  for administration, which include
 insurance, taxes, and supervision and administration not included else-
where,  are assumed to be 15 percent of Line 5.
     7.  Contingencies:  A provision for contingencies of 15 percent of
Line 5 has been included.
     8.  Total costs of closure (Line 5 + Line 6 + Line 7):   The total
costs of closure, including administration and contingencies, for the
sample incinerator are $178,489.
                                   9-83

-------
   ::;'.',..;•	,,;;' ™~.::,	,./. ..;'.,./;;,,	"  INCINERATORS ;,;;; /.";  ";'. %
                  WORKSHEET A - CHARACTERIZING THE WASTE (#2)
   llnf", Illlh '     ill!  , , illl'illli '! , Illll, • I   • , '  ''	'<	 " , '<„,  i "  ',/!',       'i  '<.,'!"  !' il'P  '  , '' ! ' 	I in   '  i , '!', I ,,'  , , 	
This worksheet should be used tq describe each wasteaccepted at  the facility,
            	il!"!; i  l;vli
           " Siillii flllilj'
1.   Description of .the waste:
          Phenolic wastewater
2.   Chemical composition of the waste:
          1000 ppm phenols
3.   Physical state of  the waste:
   I!!!" i',;," * : '  '" t" ' ' ,  t' ,,ll!!ii,,,i!"  •" Flilliil	   '.'I'i  - "" •' .•  ,.    , '  • „  '• •
          Liquid
4.   Heat of combustion of the waste:
   1	-•••   •••  o	"'
5.   Specific gravity of the waste:
          1.0
6.   Closure inventory:
          40,320 gal.
                                     9-84

-------
                              INCINERATORS
                WORKSHEET A - CHARACTERIZING THE.WASTE  (#3)

This worksheet should be used to describe each waste accepted at  the facility,

1.   Description of the wast
-------
                                      INCINERATORS
                         III     I     l mil     I     Mil      MM 111   III  III
                         WORKSHEET  B  - TREATING THE INVENTORY
      1.   3,ime_p required for treating the inventory
      2.   Manpowerrequirements  for treating the inventory
      3.   Unit cost of labor
      4.   Total cost of labor  -  treating the inventory
            (Line 2 x Line 3)
      :5.   Fuel requirements
      6.   Electricity requirements
     ""'?.	Unit'cost	of"""'electricity	
      8.   Total costs of electricity (Line 6 x Line  7)
      9.   Auxiliary fuel requirements
      ,  ;,   II;.  'ป:.,:... II ill:{	', ••• "..'-	': '••••   ' ;••
      10.   Type of fuel used
      11.    Quantity of fuel required
      12.    Unit cost of fuel oil
      13.    total "cost of auxiliary fuels
            (Line 11 x Line 12)
      14.    total fuel 'costs' for treating inventory
           	 (Line" 8 T Line "13)	
      15,    Chemicalrequirements
      16.    Type of chemicals used
      17.    Quantity of  chemicals  used
      18.    Unit cost of chemicals
      19.    Total cost  of chemicals  (Line 17 x Line  18)
      20.    Residues generated  during  inventory  treatment
      21.    Amount of residue  generated
      22.   Method  of  treatment
      23.   Unitcost  of disposing of residue
      24.   Total costs of disposing of residue
            (Line 21 x Line 23)
      25.  	Hauling	costs	for' disposing of"residue
      26.  	total costs	of "treating	and disposing of
            inventory  (sum of Lines 4, 14,  19, 24, and 25)
           	   ,,  ,9-86
                            373 hours
                            2238 man-hours
                            $20/hr-.-
                            $44,760	
                            Yes
                            87,730 kwh
                           ""Yes	/"for" 'input
                            feed B
                            #6 fuel oil'
                            10,456 gal.
                            $.90/gal.
                            $94ll)
                               - I
                            $14,6'74	

                            Yes	!	
                            Caustic,  50%  solution
                            10,800 Ibs.
                            $. 08*25 /lb.
                            $891
                            Incinerator ash
                            225,!468  Ibs.
                                i
                            (196 drums)
                            Landfill
                            $507drum
                            $9800
                            $1950
                            $72,075
IIUM, t ,.,ป 	It,	Si	i :
IIIIH^
           IliilHiTlj:' II JILhiif11
 '" ...... t . , ifllut.-'tJiBi, *!*
,i. ...... liiilM^^^^^^^       ..... Jll!i,.i
, "it ..... 't i"! '• :" '.HI!1 ,,' i i > .3"t> -iii'i" ; v. (I.!*;, <:':!'iri:! - 1 ] ..... Ovilli'l ..... IbE <
   ii,.ti^^^^^^ .....    • ........ IJB^^^^^^^      ....... liliiM^^^
ii/vi:!::-!	.i-i1! 'flif .jiiiiiBftjs:11
  •fiiiir SJ

-------
                               INCINERATORS
                WORKSHEET C -- DECONTAMINATING THE FACILITY
 1.   Volume to be cleaned
 2.   Method used
 3.   Unit costs of cleaning
 4.   Total costs of tank cleaning (Line 1 x Line 2)
 5.   Cleaning residue generation rate
 6.   Amount of residue generated (Line 1 x Line 5)
 7.   Method of disposal
                             I
 8.   Unit cost for disposing; of residue
 9ซ   Total costs for disposing of residue
      (Line 6 x Line 8)
10.   Unit cost for hauling-residues
11. .  Number of trips required
12.   Total costs of hauling residues
      (Line 10 x Line 11)
13.   Cost of flushing liquid waste feed lines
14.   Cost to pump out and backfill sumps
15.   Amount of contaminated soil area
16.   Depth of soil removal
17.   Total amount of soil removed (Line 15 x Line 18)
18.   Unit cost of removing soil
19.   Total cost of removing soil (Line 17 x Line 18)
20.   Costs for disposing,of contaminated soils
21.   Total.cost of disposing of soil (Line 17 x Line 20)
22.   Unit costs of hauling contaminated soils
23.   Number of trips required
24.   Total cost of hauling soils (Line 22 x Line 23) .
25.   Total costs of decontamination (sum of Lines
      4, 9, 12, 13, 14, 19, 21, and 24)
1,240,000 gal.
S team-cleaning
$.02/gal. capacity
$24,800 .
.125 x volume of tank
155,000 gal.
Surface impoundment
$.05/gal.
$7750

$300/trip
23
$6900

$3000
$2000
1452 sq. yds.
1 ft.
$774
$1.60/cu. yd.
$774
$30/ton
$14,520
$150
22
$3300
$63,044
                                   9-87

-------
                                      INCINERATORS
                               WORKSHEET D - MONITORING
"„","„: (!:''";;1.,    Cost'of'"air" sampling  ' '  "    ""  '  '  	   i ""	_	$25/day
      2,    Number of samples required                           16
      3ฃ    Total costs of air monitoring (Line 1 x Line 2)      $400
                                                                                            II1"'";1' K; ,.,, ',.
                                               9-88

-------
                               INCINERATORS
                 WORKSHEET E - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required for inspecting the     20
      facility
 2.   Cost per person-hour                                   $75
 3.   Total costs of independent professional engineer       $1500
      certification (Line 1 x; Line 2)
 4.   Technical hours required for administrative            8 hrs.
      duties
 5.   Person-hour costs for technical administrative duties  $30
 6.   Total administrative costs for technical labor         $240
      (Line 4 x Line 5)
 7.   Number of clerical hours required for Administrative   5 hrs.
      duties
 8.   Person-hour costs for clerical administrative duties   $8
 9.   Total administrative costs for clerical labor          $40
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)
11.   Total certification costs (Line 3 + Line 10)
                                    9-89

-------
        1	iTiniiii Illlllllll II
                                      INCINERATORS
                       -TOTAL COSTS INCLUDING ADMINISTRATION AND CERTIFICATION
                                                             „ ' idji li,™ .', . •"'	it ' ',!,"
n p    n  ih
1. I  c?sts 'I of, treating and disposing  inventory'" (From
     Worksheet B)
2.   Costs of decontaminating the  facility (From
     Worksheet C)
3.   Costs of monitoring (From Worksheet D)
4.   Costs of professional certification (From
     Worksheet E)
5.   Estimated basic costs of closure (sum of Lines
     1,  2, 3, and 4)
   IP  ;  ''I'lNiiS''	uiiirii nim is   ' •   ; <•	• i	 ii'Mi1!. I ;•• ,  . • M  ••; 'ป - •:
6.	Administration
7.   Contingencies
8.   Total costs of closure
 $  72,075
' " |!

 $  63,044


 $     400
'4  1,780
 ii	

 $137,299
 |!      • '
''.'"Jl,j '[!!." , \, , '  T
 $  20,595
 "J  20,595
 ^178,489
                                                \
                                             9-90
                                                                    	I,

-------
9.6          EXAMPLE - MULTIPLE PROCESS FACILITY WITH TANKS
                         AND SURFACE IMPOUNDMENTS

     A 2-acre hazardous waste treatment and storage facility has storage
tanks for 60,000 gallons of waste solvents and 10,000 gallons of slop
oil.  Waste is received at the facility both from tank trucks and in
55 gallon drums; the facility has a maximum storage capacity of 200
drums.  There are~"two"tre,atment processes undertaken at the facility.
There is a 30,000 gallon (50' x 20' x 4') concrete-lined surface
impoundment used for the gravity separation of oily wastes into solvent,
slop oil, and sludge phases.  The normal composition of the oil wastes
accepted is 80 percent solvent, 15 percent oil, and 5 percent sludge.
There is a 30,000-gallon clay-lined surface impoundment (also 50' x 20'
x 4') for solidifying pickling liquor wastes.  A storage pile holds
     ' +                               '
up to 8,000 cu. ft. .of solidified pickling wastes; it is surrounded
by a clay-lined surface impoundment that collects drainage and run-off.
                                   9-91

-------
             ll(i|l!i!9!ซIW	'Iliimi',	'tmf	liSi'lii11!!!!'	IW	"PlI	III!!!1!!'!!''! '!"";	•>!	I	',	;!	IIUIK^^^^^^^     	!1Rm    	!*''!:1K^^^^^^	i!W^^ 	Ill1- fiTMUW	Slii	'	''
         SAMPLE CLOSURE  COST ESTIMATING WORKSHEETS:  MULTIPLE PROCESS FACILITY
    jf" ' '- i1      '    ii  ii   iii             iii        'i      i i  J||  i       '     I
    ' i     l         n   i  II il   11      i1            i                        '(          •     •
     A.    Characterizing  the Waste
         	'"'	""    	,  i"1   	•	'   ' 	
           Worksheet A  is used to describe each waste accepted at  the  facility.
     For example, separate worksheets  must be prepared for each  of the following
     wastes:  oily wastes  and pickling  liquor wastes (the two types of  wastes
     processed at the storage facility)  and the three end products of  the treat-
    '" ment^actions performed (waste organic solvents,  slop oil, and solidified
     pickling liquor wastes).  For each  waste product specified, the following
                                                                       i        ,
     information is required:
         ::1.	 Describing  "the waste:  'Describe the origin	and general nature
     of  the waste.	
           2.   Chemical  composition:  Chemical composition should be expressed
     in  weight percent's for the various  major components, and iii parts per million
     (ppm) for any trace  components.   This information may be readily  available
     to  the operator from the bill of  lading for each waste shipment.
           3.   Physical  state:  This describes whether the waste  is a liquid,
         •illllk'l!1 . "       Illlll II  III II  .	   'in n , "i,11!"1,. i"	',''i	'I  !	|'''I..:.N ป  Mililiii"! '.i	i,1 A '!',	,;ii< i '':,,  I!1 !,i;  ii'lliiii  v V nil I'll /ill i:,"i!'" i.'!1:,." i,,!,  "I ilillilillijl'iiiii' M ;•.'ป. ,',!„. '; '	IM1',,. ,:'l". ',; ,!,",:,;ป ; .'S1 ,i X; •• .|
     solid, or mixture.   This information  is used in  making estimates  of solid
     residues requiring disposal (Worksheet B).
         	^.  ,.Heat	oฃ	combustion, of .the  waste:  Represents the heat content
     (expressed in ^jj-^b.  or BTU/gal.)  of the waste  products.   The information
     is  used  to determine auxiliary fuel requirements if the waste is  to be
     disposed of through  incineration.
    '.     f-%.,   Specific  gravity of the  waste:  The specific gravity of  the waste
     at  60 F  referenced to  water at 60ฐF.
                                                                       n
         IEVซ  ,1  • I'J'i,,;1' . , ป ' ป  i1:, i'; !:, < i .jinl'i'M,	;I||J| i1 lll'il'ijiiiH.'liii"!' 'II• il B . ;:|< |.,,I'.'i,,!,!;.'  J	'", '.l:,,.', „: 'i ,i " ii, * i 	il
     tity  of  each waste that  can be present  at the  facility in storage tanks,
     drums, or surface  impoundments, during any point in the facility's active
     life.   In the example,it is assumed that there  are times in which the stor-
     age capacity of this  facility is completely utilized.   This would therefore
     represent the maximum inventory for  developing the  closure cost  estimate.
    ,;ป  "- 5itป i"' .'i.'  .' 	.'••\r.-i ii	ill  !1 ". :	',,, I","'"' /"'"ii '  ' 	'' ••' .•'"ป'.• ':"( ',"" , u'.r;  L^;T /.tV'V f.if"s':j(|:ie?i''''-ซ^ i:r •tii"'iป;|.'J',f1; jjifi'i1'   '. ".'
     In the sample case, the closure inventory would  consist of 65,500 gallons
     of waste solvents,  10,000 gallons of slop oil, 35,000  gallons  of oily waste,
     30,000 gallons of pickling liquor waste and 8,000 cu.  ft. of solidified
    	"pickling wastes.
                                             9-92
                                                                       i
                                                                       I-
a	\Lisa>jfi	.i	iii	i,4a^^^^^	h,^^^   	''ji	iii^^^^^ 	iiiiiiia^^^^^^^^^^^	i,i:<'a;ii	iiii^  	;..i	m^,^	'aiiiii	11^^^^^^^^^^^^^^^	,.	iiiB	Jiii^^^               	ii	i

-------
B.   Treating Inventory
     1.  Waste inventory:  As noted in  the waste characterization  section
of this example, the sample facility is assumed to have  the following waste
products on-site at the time of,disposal: 35,500 gallons of oily waste,
30,000 gallons of pickling liquor wastes, 65,500 gallons of recovered waste
solvent, 10,000 gallons of recovered slop oils, and 8,000 cu. ft.  of solidi-
fied pickling wastes.
     2.  Methods of treatment or removal:  These materials will be removed
of in a variety of ways, as indicated below:
         a.  Solvents - it is assumed that the facility can find other manu-
facturing/commercial establishments that will use the waste solvents (which
have a BTU content of 135,000 BTU/gal.) as boiler fuel.
         b.  Slop Oils - pumped out of storage and hauled to an incinerator.
         c.  Oily Wastes - placed in surface impoundment for separation
into its component parts.  Solvents and slop oils recovered from this pro-
cess are disposed of in the same manner as (a) and (b) above.  Sludges left
in the basin are to be dredged, stabilized.and hauled to a landfill.
         d.  Pickling Liquor Wastes - solidify with cement and transfer
the resulting solid waste to a landfill.
         e.  Solidified Pickling Liquor Wastes - transfer to a land-
fill.                       ;
         Since treatment of inventory categories (c)  and (d) will generate
additional waste products in categories (a), (b) and (e), these preliminary
processing phases will be discussed first.

Disposing of Oily Waste
     3.  Composition of oily wastes:  It is assumed that the normal compo-
sition of the oily wastes is 80 percent solvent, 15 percent slop oil, and
5 percent sludge.
     4.  Amount of wastes produced after settling:   Using this percentage
mix, settling out the inventory of oily wastes will produce 28,400 gallons
of solvent, 5,325 gallons of slop oil,  and 1,775 gallons of sludge.
     5.  Sorbent requirements:   It is assumed that the sludge will be mixed
with an equal volume of sorbent material, with a specific gravity of 1.8.
The specific gravity of the sludge is estimated at 1.2.
     6.  Cost of sorbent:   It is assumed that sorbent material is available
on-site for no cost.
                                   9-93

-------
                                                                                          UK: ilUI, 'ill:	• 4!': iiriilJ
                 7.  Amount  of  residue generated:   After stabilization, approximately
                                                                          !
            22 tons of residue  will need to be. landfilled.
                 8.  Unit  cost  of disposing of residue:  It is  assumed that a  land-
            fill will charge $50/ton to dispose of the stabilized residues.
                 9.  Total costs of disposing of residue (Line  7 x Line 8):  Given
            these assumptions,  the total cost of disposing of facility sludge  resi-
            dues will be $1100.
                10.  Costs  of  hauling residue:   It is assumed  that the nearest  land-
            fill1 is 100".miles	one-way	from' the	site".  Trucks" with'	a 44,000-lb.
            capacity can be rented at a cost  of  $60 per hour  (including driver);
            the average traveling speed of  the  truck is 40 mph.   For one round  trip,
                                                                         i          	
            the cost of residue hauling is  $300.
             i i  ii      i in iiiiiiii  i
                11.  Number of hauls required:   1
            one trip by a 44,000 Ib. capacity truck will be required.
11.  Number of hauls required:   With 22 tons  of waste (line  7),  only
                12.  Total cost of hauling  residue (Line 10 x Line 11):  Given
            these assumptions,  the total cost of hauling residue is $300.
                13   Cost of disposing of oily waste  (Line 6  + Line 9 + Line  12):
   jii1:1!;1;'!1,, i: "if    I I     	   u      i i   -, i,      i               	    i  j i      ป    i     in • i	i	„ ,,	m-	,!,,.
            The total  cost of disposing of  oily waste is then the sum of sorbent
            material costs, costs of disposal, and costs of hauling for a  total of $1400.

            Disposing  of Pickling Liquor Waste

                14.- In order to solidify  the pickling  liquor wastes in the  closure
   II  I I     ,i iH"ill, T .I   ' ". • HniillllR'1 , lyillllll ''"run IJl,li ,ii'l J "I,1 - ,t  ,'H, •',' ,•	i '  , "lii,, '"ป• ,-' I • '  •	'''"' ,4' 'i'1:,"!, ' i"|,	":i,H,,1"!!T, ft 
-------
           Liquor  =30,000  gal x 1.05  S.G.  x 8.34 (water weight)  =
                    262,800 Ib.
           Cement  =  3,000 sacks x 94 Ibs/sack = 282,000 Ibs.
         •..---•     262,000 Ibs + 282,000  Ibs = 544,800 Ibs =
                    272.4 tons
     19.   Other on-site residues:   Waste  category (e)  represents
previously solidified  pickling wastes stored on-site.   It is assumed
that there:is 8,000 cu. ft.  of  this material currently in storage," and
that the material weighs approximately 135 Ib/cu.  ft  (similar to a
mortar-like cement).   Therefore,  the  total weight of  this residue
would be 1,080,000  Ibs. (540 tons).
     20.   Total amount of  pickling  residue (Line 18 -f Line 19):   Total
solid residues from treatment of  the  pickling wastes  are 812.4 tons.
     21.   Unit cost  of disposing  of residue:   As in Line 8 above,  it  is
assumed that a landfill will charge $50/ton to dispose of such residues.
     22.   Total cost of disposing of  residue  (Line 20  x Line 21):   Total
disposal costs are  estimated to be  $40,620.
     23.   Costs of hauling residues:   The  costs and method of hauling
residues are the  same  as Line 10  above.
     24.   Number  of  hauls  required:   Given truck capacity of 44,000 Ibs.
(22 tons),  it will  take 37 round  trips  to  haul the solidified pickling
wastes.
     25.   Total cost of hauling residues:   Given the above assumptions,
the total  hauling costs will be $11,100.
     26.   Cost of disposing  of pickling liquor waste  (Line 17 + Line  22
+ Line 25):  The total cost  of disposing of pickling liquor waste  is
then the sum of. costs  of materials, residue disposal and hauling,  for  a
total of $59,220.        ;
     27.   Amount of solvent  on-site:  Including  the solvents  recovered
during the  settling of inventoried oily waste,  the total  inventory of
waste solvents at the  sample facility are  60,000 gal.  (storage tank) +
5,500 gal.   (drums) + 28,400  gal. (surface impoundment) = 93,900 gal.
     28.  Method of disposal:  It is assumed  that  the waste  solvents  can
be provided to manufacturers  as a boiler fuel.
                                 9-95

-------
                 29.  Cost of disposal:   It  is assumed that  the users of the  solvents
                 pay the  costs of pumping and hauling the solvents to their facilities.
            No additional credit is awarded  to the owner/operator of the tank facility.
      ' i     Treating Slop  Oil
                                                                                         •H'Vi iiซ! I'll ill
                                                                        I
                 30.  Mount of slop oil  on-site:  Including the slop oils recovered
            during the 'settling of inventoried oily waste,  the total inventory of
            slop oils are 10,000 gal.  (storage tank) + 5,325 gal. (surface impound-
            ment) =ป 15,325 gal.
Illlllllll  I   I     I 111 I   '      '         i .11,,.	,	„ r	  .. i":1.	 .,.'	i,ri,,ii!.., .'.si.:'.,,	•'	 i ,r; ,t:	,	'	u	: ',-, •	n. ",i|!	i •. :." 	ซi	i    ,•••	i, •,„!!,, jks	f ,",;<
                 31.  Method of treatment:  It is assumed  that the slop oils will be
11 in  i i i       I I 11   i  i  ii i ii ii  niiiiiii j    /"-,	i':'	i • 'it ' si!1	i!1:11 ซ•  i • • •	•,'"", :i'n • * ''' .• 'ii !	 J *' ,	i.."":' • 'M; i  SL sii • •:| • "Tur:ii11 - u • "MiiiH1, "t" ^ ' ™	 i '' „ ,,lr r" • •,	•ซ •• • v •; * • s ini: r,,,	 : • •' if , 'n i1 '•ซปl' s> i	hiiii', • c • .1 ftrป, • vn: if H
            trucked to  an incinerator.
              :;'-'32.  Cost of treatment:   The estimated  fee  paid to the incinerator
            for treating  the wastes is  $0.60/gallon.
              '!',  „ 33".	Total	costs	of	treatment" (Line" 3'0"  x" Line	32):  Given  the  above
11 III  |        I I ji  i	r'iV™ , f ijitj' •> fjjii •;.. i'' , '" J, B :,a i	,":i j	I	ii)' r. i j. • i, i v j: ii i'' i,i :,iiii l'';.,; Tii'  t	i i '<', I	"'ป i!;-,'-iii,, Mljm iif	ii.	S;'|i • im 'i 4 i' iii 'liiiw'i/1 ii), i •."- si ;.i:	.1 > " •: <' "inii • • i-i	i; v. :; .ii>] 5
l||,( i|| I  i  11     '"assumptions.  It will cost $9,195  to  treat  the  slop oil inventory.
                 34.   Costs of hauling:   It is assumed that the nearest  incinerator
            "ls'50 'miles	away,' that  the'wastes 'will be'transported	in a 7,bOO-gallon
       1     "capacity	truck,"	at"" an'average'" speed" of'""4'0'mpti".	The	hourly" rental  cost
            for  truck  and driver is $60.
	       ;;;,; I;=35.   Number of hauls required:   Given trailer capacity, ' it will
            require three trips to  haul the slop oils  to the incinerators.
                 36.   Total costs of hauling:Given  the above assumptions,  hauling
	costs'" a'r"!	"estimated at  $450.
                 37.   Total costs of treating slop oil (Line 33 + Line 36):  The total
                   bf treating slop  oil are then the  sum of the costs of  disposal and
            hauling, for a total  of $9,645.
                  38,  Total costs of disposing of inventory (sum of Lines  6,  9, 12,
            17,  22,  25, 29, 33, and 36):  The total  costs of the above activities
            are  estimated to be $70,265.
            IK' i!1;. '  '   I I II   I 11
            ill	 ' :•  II II III  I I 111
                                               9-96

-------
 C.   Decontaminating  the  Facility

 Tank Cleaning

      1.  Cleaning method:   In  this  example,  the  storage tanks  are
 steam cleaned.
      2.  Volume:  In the sample case, there are  60,000  gallons of
 solvent storage capacity and 10,000 gallons of oil storage capacity
 to be cleaned, for a total of 70,000 gallons.
      3.  Unit cleaning costs:  For a 2,000 gallon-per-hour steam cleaning
 unit (capable of washing a 16,000-gallon area of storage capacity/hour),
 costs of equipment rental, labor, and operation are equal to $.02/gallon
 of capacity cleaned.
      4.  Total costs of steam cleaning (Line 2 x Line 3):  Total cleaning
 costs for the storage tanks is,$1400.
      5.  Type and quantity of residues generated:  Steam cleaning
 generates residues in the form of contaminated washwaters.   The rate of
 residue generation is 1 gallon of waste/8 gallons of tank volume.   In
 the example,  total residues are 70,000 -5- 8,  or 8750 gal.
      6.   Method of disposal:  It is  assumed  that the residues are hauled
 to a surface  impoundment and evaporated.
      7.   Cost of disposal:   Impoundment  disposal of washwaters  is
 estimated to  cost $.05/gallon.
      8.   Total cost  of  disposal (Line 5 x Line 7):   Costs of  disposing
 of these cleaning residues  will be $438.
     •9.  .Cost of  hauling cleaning  residues:   For  one round  trip, the
 cost of  hauling  residues is $600.  The cleaning residues will be hauled
 in a 7,000-gallon tank  truck, with an average  truck speed of  40 mph.
 The hourly rental cost  for  truck and driver is $60; the  nearest
 available surface impoundment is'assumed  to be 200 miles away.
     10.  Number of hauls required:  Given  the assumption on residue
 generation and truck capacity, two trips will be  required, at $600/trip.
     11.  Total costs of hauling:  Total hauling costs are $1200.
    12.  Total costs:  The sum of the costs of steam cleaning, disposal
and hauling yields a total of $3038.
                                 9-97

-------
m * "!„••„, si ,.v
            Decontaminating the Impoundment

                 13.   Cleaning method for  Impoundment 1:   It  is  assumed that the
            concrete-lined impoundment will be sandblasted.
                 14. '' 'Area of concrete impoundment to be cleaned:   The area requiring
            sandblast ing"! ............ based" on "the '"sample "facility ...... "description", ....... Is"" equal "'to the
            base area (50.' x 20',  or  100 sq. ft.) plus  the area of the site
            walls  (2' x 50' x 4' + 2' x  20' x 4', or 560 sq.  ft.),  for a total of
            1560 sq.  ft.
      ;;„   ,'*.:" :' ' IS."""' ..... Costs pi "sandblasting:" ....... A' 6" cu." "ft", "capacity compressor "will
            be used  in the sample  estimate.  The unit rents for  a $Ibo7week, and
            costs  $1.75/hour to operate;  labor costs are estimated at $20/hour.
 1:11 '  '•' ' ';iil"" '  ' ' f The  unit' 'can ""clean' 40 "sq. ...... ft.  of concrete/hour.   Consequently, sand-
            blasting costs are estimated at $.60/sq. ft.
• 'it'1'!11: ..... •• a .......  •  F'lHi11! " • I'lv1*' ••'  in ..... mil ma ..... iiWW  jซ ..... ' ..... '"*', ...... i,'"'1: •". • i ..... • .....  ', > •   ' , " a '"„, ......... , ., .""i11";, ...... : f<\ ' i1'1'. ',,,'pi  ^iip1 ii,,:,'1 ..... ; • ••! \ 'i; i m,"1 j/, ..... .",ii',;i ....... ..iiW',,!"1.,, ,
                 16.   Total costs  of  sandblasting (Line 14 x  Line 15):  Sandblasting
 .................................. costs ...... are .......... estimated to be $936.
                 17.   Type and quantity  of residue generated:  The residues will
 '" .......... '   •'  '""Xnsis'l  o? contaminated' sanSs.  ..... It" was' ....... as'sSmeS ....... that ......... 4000"" 'ibsT (2 ....... tons)
 It!1  'I     .:  fit!':1!'1"  ...... ">:.  'iifl: 'Mill  ';••;"•. ..... Bui". 4? •; T .if •:' ......... .'.":•! .-.,' •.,•,*.'  "• .......... f, t:"'! ..... Lll.'.r.^i': -i'v ' I ii. ::\-"f> ........ Si ..... t.i" *J>V ........ ซ ..... ,T'  i III1 .i  !•';', ........... :,l
 .....     "" ..... o:f sand  residue will" be" generated.
                 18.   Unit costs of disposal:  The sands will be landfilled at a
 "'I   .' .,      "disposal ....... cost" of $50 /ton".   "         '  "  . [[[
 Si]  i J ; ,::     i'V ; ...... '::i9.  ........ ^ Total, costs  of  disposal  (Line 17  x' Line ........... IS)": ..... Total  disposal
            costs  will be equal to $100.
                 20.   Cleaning method for Impoundment 2:   All contaminated clays
            from the clay-lined impoundment will be removed and hauled to  a landfill.
                 21.   Area of clay impoundment to be  decontaminated:   Since  the dimen-
            sions  of this impoundment are the same as those of the concrete-lined
   • -,;     .  Jl-Lmpoundment ""discussed ......... above, the ..... surface area  to  be contaminated is the
            same as  that estimated in Line 14 of this worksheet, or 1560 sq. ft.
                                                  "                    "  i;
                 "'22.'' ................. 'Amount """ofciay"  removed:' "it" ""is '"assumed  ..... that "the  clay in  the
                                                                        |           ,  , ..... '   • ;,
            pickling liquor impoundment has been contaminated to a depth of one
            foot.   Therefore, 1560 cu.  ft. of  clay, or  57.8 cu.  yds., must be
                                                                        I

-------
     23.  Unit cost of removing clay:  Clay removal will be performed
with a backhoe.  Including costs of equipment rental and labor, the
costs of removing the clay is estimated to be $1.60/cu. yd.
     24.  Total costs of removing clay (Line 22 x Line 23):  Given the
above assumptions, the costs of removing the soil are $92.
     25.  Disposing of contaminated clays:  Clays will be hauled to a
landfill for disposal.  The costs of disposal are estimated to be
$30/cu. yd.
     26.  Total costs of disposal (Line 22 x Line 25):  The total costs
of disposal are $1734.

Removing Soil and Miscellaneous Activities

     27.  Removing contaminated soils:  Because of spills and other
accidental releases, certain areas of the waste disposal facility, such
as diked-in areas around storage tanks will be contaminated.  It is
assumed for the sample facility that 2.5 percent of .the total site area
is contaminated.
          Contaminated area = 2 acres x 4840 sq. yd./acre x .025
             rate of contamination - 242 sq. yd.
     28.  Amount of soil removed:  The depth of soil removal required
to remove all hazardous contaminants is assumed to be 1 foot.  Thus,
the  total amount of soil removed - 242 sq. yd. x .33 yd. =80.7 cu. yds.
     29.  Unit cost of removing soil:  As in Line 23, removing soil can
be accomplished at a cost of $1.60/cu. yd.
     30.  Total cost of removing soil (Line 28 x Line 29):  Total cost
of removing soil is $129.
     31.  Disposing of contaminated soils:  Contaminated soils are also
hauled  to a landfill, where they may be disposed at a cost of $30/
cu.  yd.
     32.  Total costs of disposal (Line 28 x Line 31):  Given the above
assumptions, disposing of soils will cost $2421..
                                 9-99

-------
                 	tJKT'74 '"fUl'SH1' "* fl	IIF'I'l	!',	 "	•	 •';:	!. 'I	!' i ':"l	ii1 l!l:,liS!1 "!' 'ป'•• HI	ill'1.	'!< \V-"mii'f"'Wat Si', Sf I III* •" I "Hill: ,(!!. JKaKf't.ytHl	f. !!"' Kill1!' I". fillli:' ll'f "li 1
 (i  i;	33.  	Hauling costs for decontamination wastes:   The wastes described
in Lines  17,  22,  and 28 of this Worksheet will be  hauled to the landfill
in a 44,000-lb.  truck.   The landfill is assumed  to be 100 miles away; the
hourly cost of  truck and driver is $60 and the average trip speed is
40 mph.   Adequate dividers will be supplied so that  mixed loads can be
carried.                                      "                ]
   Illiiir  	 .;, I I  ill III ill i1 'i  "i. VM' . '" " ,::' ','|n   '   ', '",' 'II1, ir. I, i ,. '.  	 !,.  '  .'Vlillillipl, IliilliL'''" J,  ''11 "' "'IIUl'  • 'MI!  'I1. '
     34.  Number of  trips required:  If it is assumed that a cu.  yd. of
                                                             * i
earth weighs  approximately 2000 Ibs., the hauling  of these waste  residues
will require  seven trips.
     35,Costs  of hauling decontamination residues  (Line 33 x Line 34):
At $300 per round trip, total hauling costs would  be $2100.
                                                              j!
     36.  Flush pumps and transfer lines:  All pumps and piping used to
transfer  hazardous waste are flushed to remove	contaminants.	This	'
process is assumed to cost $2000.
     37.  Decontaminate equipment:  All materials  handling equipment
used on-site  must be decontaminated.  This is assumed to cost $500.
     38.  Decontaminate containers:  In the example, it  is assumed that
         „                     •                                I
all drums kept  on-site  will be crushed and buried  in a landfill,  at a
total cost of $1000.
     39.  Total  costs ofdecontaminating facility  (sum of Lines 4, 8,
11, 16, 19, 24,  26,  30, 32, 35-38):  Total costs of  decontaminating the
facility, based on the  above assumptions, are estimated  to be $14,070.
   ~	'"	 	.'"' „!"  „ ,   I',,,	  '	'	 ,   ' '	' ,. ".'".,'_','	,'.".",!.'	',,   ,''.  ,  , '
D.Professional Certification
     1,   Number  of person-hours required for inspections:   It is assumed
that 16 hours  are required for periodically inspecting  all  aspects of
closing the  tanks and impoundments.
     2.   Cost per person-hour:  In this case, assume that  a registered
independent  professional engineer may be hired at  a cost  of $75 per hour.
     3.   Total costs of independent professional  engineer's time (Line 1
x Line 2):   This  yields a total cost of $1200 for  the independent pro-
fessional engineer.
                                   9-100

-------
    .4.   Number of technical hours required for administrative duties:
Assume that 8 hours are, required from the owner's or operator's staff for
administrative duties connected with employing an independent professional
engineer.
     5.   Person-hour costs for technical administrative duties:  It is
assumed that the total fully-loaded costs for the owner's or operator's
staff are $30 per hour.
     6.   Total administrative costs for technical labor (Line 4 x Line 5):
Given the above assumptions, the total administrative costs,for technical
labor are $240.
     7.   Number of clerical hours required for administrative duties:
Assume that 5 hours of clerical time are required for the necessary
typing and certifications.
     8.   Person-hour costs for clerical administrative duties:  Fully-
loaded costs of clerical  time are assumed to be $8 per hour.
     9.   Total administrative costs for clerical labor (Line 7 x Line, ,8):
Given the above assumptions, total clerical costs are $40.
    10.   Total administrative costs (Line 6 + Line 9):  Summing technical
and clerical labor, the administrative costs are $280.
    11.   Total certification costs,(Line 3 + Line 10):  The total costs
for certification, including engineer's fees and administrative costs, are
$1480.

E.   Total Costs Including Administration and Contingencies  .

  ,.. .Items 1 through 3 give the costs of all activities on each of the
preceding worksheets.   Line 4 is the total of:Lines 1 through 3, .$85,815.
     5.   Contingencies:   A general provision for contingencies of 15
percent of Line 4 has  been included. •
     6.   Administrative and supervisory cost:   For administrative tasks,
including taxes,. insurance,, and administration and supervision not included
elsewhere, a total of  15 percent of total costs from Line 4 is used.,
     7.   Total costs  of closure (Line 4 4- Line 5 + Line.6):  The
total costs for closing the tanks and impoundments are estimated for
the sample case to be  $111,559.

                                  9-101

-------
                            MULTIPLE  PROCESS FACILITY
                 WORKSHEET A - CHARACTERIZING THE WASTE  (#i)
 1.    Description of the waste
          Organic solvent
 2.    Chemical composition
 	(Not given)	
 3,    Physical state of the waste
          Liquid
 4.    Heat  of combustion of the waste
           18,000 BTU/lb.(135,000 BTU/gal.)
< I1 :i'i !• i' ',< • "' • in i     1  ii  1 mi  n inn in in  ii  ii  i ii               '.?": ,, •!!!
 5.    Specific gravity of the waste
 :	:™	    .9                                 '''"'::''
 6.    Maximum inventory of the waste
           60,000 gallons bulk storage
            5,500 gallons in drums
 7.    ID  numbers forareas holding these wastes
 	Tanks T-l to T-4
                                                                                           .Tiii!1;:11):'1!!	ure ''npin,,,,
  ill  '•   111
                  (i 111  Illlllill
                                                                                       ( I 1 Illlllill
 1111    I       Illlllill I        II III  I 111
II Illlllill I III I II 111     Illlllill I  111 III III  Illlllill  Illlllllllll
                                           9-102
                                                                                           : JU:' : ',-1 !ซ,"M
                                                                                   ij: ,; ,„ " ,ii''"mill11 li'snip i	,v ';'	,:'Viaiiii
                                                                                  ^III;:!,:!,!,':;!:,;	            I

-------
                    MULTIPLE PROCESS  FACILITY
           WORKSHEET A - CHARACTERIZING THE WASTE (#2)
Description of the waste
    Slop oil
Chemical composition
    (Not given)
Physical state of the waste
    Liquid
Heat of combustion of the waste
    16,000 BTU/lb.(126,720 BTU/gal.)
Specific gravity of the waste
    .95
Maximum inventory of the-waste
    10,000 gallons bulk storage
ID numbers for areas holding these wastes
    Tank T-5
                              9-103

-------
         MULTIPLE PROCESS FACILITY
WORKSHEET A - CHARACTERIZING THE  WASTE (#3)
1.    Description  of the waste
:;:; ^.i'  :|,:, ,\,0:iiy wastes	
 2.    Chemical composition
          (Not given)
 3.    Physical state of the waste
          Mixture]~(95Z 'liquids'',' 5% sludge)
 4.    Heat of combustion of the  waste
          (Not given)
 5.   "	Specific"""	gravity "of the'	waste
          (Not given)
      Maximum inventory of the waste
Ml    111      I   111111  III II III        I    II              ;; ":'!'' , "
          30,000  gallons in holding basin
           5,500  gallons in drums
'.7.   "!pi'^n?^ซ.i3. ^l?111"??.'81 kฐ?-dillS these  wastes
          Impoundment S-l
                                                                         •iii,""	:Ai,:"!:"ii
                        9-104
                                                                in '   v • ' list: "t .' ' iii 11

                                                                .'"• • '•' ' -  I'* 'i/':, " '"'I'
                                  •i', 'II!1-,1,: :• Hill  W> i ,il ,)',-	 I '•, |,
                                  	  	 I, ' I'  " lit "I1 !„ lin,  I'1"1 I,, 'I "lj|
                                                                                      ill  Hi'
                                                                   111	iii1

-------
                       MULTIPLE PROCESS FACILITY
                WORKSHEET A - CHARACTERIZING THE WASTE (#4)
1.   Description of the waste
         Pickling liquor waste
2.   Chemical composition
         (Not-given)
3.   Physical state of the waste
         Liquid
4.   Heat of combustion of the waste
         0
5.   Specific gravity of the waste
         1.05
6.   Maximum inventory of the waste
         30,000 gallons in holding basin
7.   ID numbers for areas holding these wastes
         Impoundment B-l
                                     9-105

-------
     ^^^^	!
                                                              !
                                                              i
                       MULTIPLE PROCESS FACILITY
               WORKSHEET A - CHARACTERIZING THE WASTE (#5)
1.   Descriptionof the waste
         Solidified pickling liquor wastes
2.   Chemical composition
         (Not given)
3. '	""^hys'ica^C	'siiEate 'of	the waste	
         Solid
4. l	J'"He,at	of""'	combustion  of the waste
   ;;: ;•/'  ;': (Not	given)'
5.   Specific gravity of the waste
         2.2	
6.   Maximuminventory of the waste
         8,000  cu. ft. in storage pile
7.    ID numbers for areas holding these wastes
         None
                                                            ?.'	I'

	I!"
                                       9-106

-------
                                                                                       1
                         MULTIPLE PROCESS FACILITY
                    WOBKSHEET B - TREATING THE INVENTORY
  1.   Waste inventory at time of closure
           Waste solvents
           Slop oil
           Oily wastes
           Pickling liquor wastes
           Solidifed pickling wastes
  2.   Methods  of treatment or removal
           Waste solvents
           Slop oil
           Oily wastes
 5,
 6.

 7,
 8.
 9.

10.
11.
12.
13.
         Pickling liquor wastes
         Solidified pickling wastes
Disposing of Oily Waste
3.   Composition of waste                    •
         80% solvent, 15% slop oil, 5% sludge
4.   Amount of waste produced
         28,400 gal. solvent, 5,325 gal. slop oil,
     Amount of sorbent used in sludge treatment
     Cost of sorbent used
     a.  Cost of materials
     Amount of residue generated
     Unit cost of disposing or removing residue
     Total cost of disposing or removing residue
        (Line 7 x Line 8)
     Costs  of hauling residue .
     Number of trips required
     Total  cost of hauling residue (Line 7  x  Line 10)
     Costs  of disposing or removing oily waste
        (Line 6 + Line 9 + Line 11)
 65,500  gal.
 10,000  gal.
 35,500  gal.
 30,000  gal.
 8,000  cu. ft.

 Reuse as boiler fuel
 Incinerate
 Separate; recover solvents,
 incinerate slop oils, landfill
 sludges
 Solidify, landfill
Landfill
               1,775 gal. sludge
               1:1 ratio with oils
               0
               0
               22 tons
               $50/ton
               $1100

               $300/trip
               1
               $300
               $1400
                                   9-107

-------
WORKSHEET B  (continued)
Treating or Removing Pickling Liquor Waste
14". ................. :'imiSinii: "of cement  required' for 'solidification
15.  Total amount  of cement required
16.  Cost of cement
17.  Cost of materials (Line 15 x Line 16)
18.  Amount of residues produced by treating inventory
     Amount of other residues already ori-site
19.
20.
      Total amount of pickling residues
         (Line 18 * Line 19)-
21.  Unit"'cost:  of  disposing or removing residue
22.  Total  cost of disposing or removing residue
         (Line 20 x Line 21)
23.  Costs  of hauling residues
 . , ii         ii i in i mini ..',:, ' •'  to1' , ,!•	i'1:1	•','w M •  '"','' '•'. . n|  i1* i ' • . i '  ••  ,;,'i, , • ,!„ ""' .
24.  Number of  trips  required
25.  Total  costs of hauling (Line 23 x Line 24)
26".	 Costs'	of "disposing or	removing"pickling' liquor
         waste (Line 17 + Line 22 + Line 25)
Removing Waste  Solvent
27.  Amountof  waste solvent
'••   	ซ""S!a."::	"ASSun't1	of solvent  in inventory
   E-:ii'b.  Amount of solvent  obtained from oily
   ""„'	"_'""_	"_	waste" inventory	treatment
 28.  Method of  removal

 29.   Cost of removal
 Treating Slop Oil
 30.  Amount of  slop oil-on-site
      a.  Amount in inventory
      b.  Amount generated  from disposing or
             treating oil waste  inventory
 31.  Method of  treatment
 32.  Unit  costof treatment
 33.  Total cost of treatment  (Line  30 x Line 32)
 34.  Unit  costs of hauling residues
Isack/10 gal.
3000 sacks
$2.50/sack
$7,500
27 2.4	tons'	
540 tons
812.4 tons

$50/ton
$40,620

$300/trip
^37		'"
$11,100
$5*9,220	
                                                            93,900 gal.
                                                            64,500 gal.
                                                            28,400 gal.
                                                            Recovery and reuse
                                                            as boiler fuel
                                                            15,325 gal.
                                                            10,000 gal.
                                                            5,325 gal.

                                                            Incinerate
                                                            $0.60/gal.
                                                            $9,195
                                                            $i50/trip
                                    9-108

-------
WORKSHEET B  (continued)
35.  Number of trips required
36.  Total costs of hauling (Line 34 x Line 35)
3
$450
37.  Costs of treating slop oil                            $9 645
38.  Total costs of treating inventory                     $70 265
        (Sum of Lines 6, 9, 12/17, 22, 25, 29,              T
         33 and 36)
                                 9-109

-------
                                	Si!	i'lUWWIiMHi	Jim I-'::'1}!'!]-!.!);1"!!	lllliH^^^	KV-V	I''"!!;	i	I	tHVtfW'i	|I|IH^	Illi'^	SI!!!'	If">:;!"	III!	IS!' '{•*MT'lW
                                     MULTIPLE PROCESS FACILITY
                            WORKSHEET C -  DECONTAMINATING  THE FACILITY
	      Tank Cleaning
           1,    Cleaning method used                         Steam cleaning
i|	|i i :li ;:ซ; :2.	C4ซฑ5 tฐ	be cleaned" '  	• "	70,000 gallons
ซ'ซ•••' ••* •' •ปป" !:"!3.'	;;i •"'tfn'ircTeanlni'	costs1	'""":' 	::" ':":''":	: •'       : •":	'•';: $ • 02/gallon	'	
r!'—1 ;.:':"••;'..•""ป :4.:   Total costs of steam cleaning
iiijii!         * iiii,'is(Line 2 x Line 3)                            *  ป
I;::  ::::, '  3.	Quanti'ty' '^nd • type	of residues	generated 	8,750 gallonk of  contaminated
            i  i|lT(,ijl|f','j;:,,' vf'i," JP ilflf, lilt' •'' '''iiii I'liiiiiitv,!,',!i	ijl"	t ':'!#'.',. i ;>  '"j"'in t • •, •  '  •: •ซ "S":1  ',",, ••) I1 '',-„'."  ; :• 'Xi-'iKrt 7'J-v--}i-i	
        i  9.    Cost of hauling  residues                     $6007 trip
        "	I i1/ '!• Illll]' '111 11	< "Hi; tMW''aป i.j:i:l;l!i	1	,!''!'",:W, iii:lis1" . ••' : ,1, i.H. •"!"    •  :.  ' Ji.1*  ,,„ป-'"'i,	wt	,	  '-'; .t	 I "is-" '-i "	•' •;	".",  ' ••'.'* •(,'	i1:,'	', J
           10,    Number  of trips  required                     2
!"".:'!  : :':. iii	Total'	costs" o'f hauling (Line	9	x" Line  10) $1200
:ป1-::L";:;;;.;;	 12!""	^Totei'1 costs' "of	tank" cleaning 	$3538
           Decontaminating the Impoundment
;S'i	'il'l%	'is"	cleaniig	method u-d _ Svirฃaee Impound-   Sandblasting
*™t™	r"::,;, U".    Ar'ea"ฃo be cleaned   ;'  mSnt	3.560	sq.	ft.	
    'itijl'^l- 15	"	   unit'cosS  of sandblasting''"'1"  " "	"'  "'i":';"::	:"$-60/sq. ft.
           lgI"  Total  costs of sandblasting
                   (Line  14  x Line  15)                          $936
    ;'::;r';;:;;\;if:	:  Quantity  of residues generated'  : "!'"'''"''  	'	""""^	tons	of ""contaminated sand
    ''.I	''":,;"  """""is	Unit	""costs	of"	disposing"'of  residue         $50/ton
    !;|!:|^:'	if	"!	"•	ffl1	m&!ฎ^w&i*ฐ*™ti&	""	!"	"	'^m	
    ,! '"i/ir'i'l, • \A •. '• m'f't, (Line	17	x" "Line	18)                                      '
            20.    Cleaning method used - Surface  Impound-    Clay  removal and landfill
                                                  2                disposal
            21.    Area  to be cleaned                           1560  sq. ft.
              iiiii i    i   i  linn  mi iiii  i     n   i  i i            '•.:,•••'  *• "i-i. "•'j|" c^ o  ซ,,  trHa
            22.    Amount  of clay removed                       =>' -s  cu- yas-
            23.    Unit  cost of  removing clay                  ^V?^" ?'
                     11   inn i  i • •            i      n        'i,,' '   i 	  "ii J'11
            24.    Total cost of removing  clay
              •Hi,    ^Line"	22™^ Line""23)	^ ^  ^ 	^	|	^	^		^
              Illll I     'W I,':, lift  iiiail!'1 f.', v: ;-i '	.'i'1  ,'• ',' " ..si", r"  ''	 Q—110


-------
 WORKSHEET C  (continued)
 25.  Unit cost of disposing of residue (clay)
 26.  Total costs of disposal
      (Line 22 x Line 25)
 Soil Removal and Miscellaneous Site Cleanup
 27.  Soil area contaminated
 28.
 29.
 30.

 31.

 32.

 33.

 34.
 35.
 36.

37.
38.
39.
 Amount of soil removed
 Unit cost of removing soil
 Total cost of removing soil
 (Line 28 x Line 29)
 Unit costs of contaminated soil
 disposal
 Total costs  of disposing of .soil
 (Line 28 x Line 31)
 Hauling  costs for  decontamination
 wastes (including  impoundment  cleanup)
 Number of  trips  required
 Total costs  of hauling
 Costs of flushing  pump and  transfer
 lines
 Decontaminate equipment
 Decontaminate containers
 Total costs  of decontaminating the
facility
                                           $30/cu. yd.
                                           $1734
 2.5% of site area
 (242 sq. yd.)
 80.7 cu. yd.
 $1.60/cu.  yd.
 $129

 $30/cu.  yd.

 $2421

 $300/trip

 7
 $2100
 $2000

 $500
 $1000
$14,070
                                  9-111

-------
                                MULTIPLE PROCESS  FACILITY
                         WORKSHEET D - PROFESSIONAL CEBIlfTfiiTIOS'
         1.    Number of person hours  required for inspections      16 hours
         2.    Cost per person-hour: engineer                       $'5
         3.    Total costs of independent professional engineer's   $1200
              time (Line 1 x Line  2)
                                                                     i
         4.    Number of technical  hours required for               8 hours
        '. 	1	: "	'	""	:	'"::,'	M	•:•'- 	:" '	 :;"".	".:	:'. " 	"  :'	i"1"" ;'.:':•,"	••"; .": r:	"I	"	:;-•..•.:
              administration
         5.    Cost per person-hour: technical                      ?30
         fi".	T"ot.a.ฃ	adniniistrative	costs for	technical      ^       $240
        ••" "i 'i  , labor (Line	4' x'tine	5)
        1(I	a	Number	of _,clerical	hours ^ required ^ f or	5	hours
              administration
         8.   Costs per person-hour:  clerical                      ?8
         9.   Total administrative costs for clerical labor        $40
         	(Line 7	x Line" 8)	  ^ ['	^ ^	™ "^	"	"'^ ^ ^	^ *^ ] ^	| '	^	
        10.   Total  administrative costs (Line 6  + tine 9)         $280
        11.   Total  certification costs  (Line  3 + Line 10)         51480
         n  i       ill  in 1          i         in             i  i   in    i i  i i
                                            9-112
;A	Will	lllilL	ilniiiifr1'	IH^
ii^^^^^^^
                                                                  	l|	
I

-------
                       MULTIPLE PROCESS FACILITY
                   WORKSHEET E - TOTAL COSTS INCLUDING
                   ADMINIST3JATION AND CONTINGENCIES
1.   Costs of disposing  of  Inventory                       $  70 265
     (From Worksheet B)
2.   Costs of decontaminating  the  facility  (From           $  14,070
     Worksheet C)
3.   Costs of professional  certification  (From              $   1,480
     Worksheet D)
4.   Subtotal                                               $  85j815
5.   Contingencies                                          $  12  872
6.   Administration                                         $  12  872
7.   Total closure costs                                    $111  559
     (Line 4 + Line 5 + Line 6)
                                  9-113

-------
      9.7
I,' ! , I"!1!'
EXAMPLE - POST-CLOSURE COST ESTIMATES
              large  flat  landfill of  200 acres  has  been closed in accordance
                                                                	I""
            the EPA interim status  regulations.   This  landfill consists
       ol  rather  closely spaced narrow trenches  that are protecte'cl by clay
       covers  and cover vegetation.  The facility soil is a soil which is
       mostly  clay in content.   All of the facility is planted with grass to
       resist  erosion.
            The post-closure operations at this  facility have been planned to
       carry out  therequirements of the interim status regulations.  The ac-
       tivities planned areas  follows:
            •  periodically inspecting the facility
        —:; ,  •	mowing                             _               '
            •  routine erosion repairs
            •  replacing security fences (as needed)
            •   fertilizing
            *   leachate pumping and disposal
            •   ground-water monitoring
            •  monitoring well replacement (as needed)
            •   repair of severe erosion caused by storms
            •  post-closure administrative services
       These activities are costed in the attached annotated worksheets.  All of
       these activities are costed based on the assumption that the facility is
       completely closed and that no "free" assistance is available from an
       active portion" of the facility.  This means that some of the supporting
       facilities such as office space  that are available during closure are
       not automatically available during the post-closure period.
                                          9-114

-------
               SAMPLE POST-CLOSURE COST ESTIMATING WORKSHEETS

 A.   Periodically Inspecting; the Facility
      1.  Number of technical management person-hours required for each
 inspection;  Each inspection at this closed hazardous waste facility
 will be conducted by two people in a rented vehicle.  We are of the
 opinion that two people are needed to conduct the inspection of the
 large closed waste disposal .area (200 acres) and that an extra measure
 of safety is afforded by having two inspectors.  Each inspection takes
 a full day of work by two technically trained managers.
      2.  Annual number of routine inspections:  Six routine inspections
 will be conducted during each year of the post-closure period.  These
 will be conducted on a bimonthly basis.
      3.  Person-hour costs for technical management labor:   The fully-
 loaded labor rate for this technically trained labor is $30 per hour.
      4.  Technical labor costs  for annual routine inspections  (Line  1 x'
 Line 2 x Line 3):   The technical labor cost for "these annual routine
 inspections  is  the product of  the person-hours required for each inspec-
 tion,  the number  of  inspections  planned,  and  the  technical  labor rate.
      5.   Annual number of  engineer-supported  inspections:   In  addition
 to  the  routine inspections  described  above, two annual  engineer-supported
 inspections  are planned.   These  inspections use a team  of professional
 engineers  and one  of  our technical managers,.   The engineer  is  a  state-
 certified  professional engineer  from  an independent  firm that  is contracted
 to  supply  professional services  to the hazardous  waste  disposal  facility.
      6.  Number of independent state-certified engineering hours for each
 engineer-supported inspection:   For each inspection, eight hours of  the
 engineer's time is required.
     7.  Number of technical management hours  for each engineer-supported
 inspection:   For each inspection, eight hours of  technical labor is
 required.  This requirement is in addition to the engineering labor that
 is required.                 ;
     8.  Person-hour cost for a professional engineer:  The quoted cost.
of engineering services is $75 per hour.  These services will be obtained
from an independent engineering firm.

                             1      9-115

-------

                                                                                          ......                 I
                  9. Engineering  labor  costs for the engineer-supported  inspections
ii ii inn   i  ii MI i     nil in  i • • hiTr'" 	IT ฐ
li SI, .  l	!!'!  .(Line 5 x Line 6 x Line 8):   The cost of the engineering labor is the
If I llllll I I I III llllll  I   I                                                                I                	•!
           product of the number of engineer-supported  inspections, the  number  of
           engineering hours needed for each inspection, and  the person-hour cost
::::::"::":	::::':::  "of ""engineering services.
II,	'.	"I	"'.	!  II	10 i	Teciinical' labor	costs for	the'" eng"inee r-supporfed  inspections
jj^l™™  (JLlne's'x	"Line	3 x Line 7):   The technical managerial labor  costs for
           theengineer-supported inspections  is the  product  of the labor rate  for
^^^'•••-"yy ^'ec|^^c~'j[i'ฃa5orj tne number "of inspections'" required, and the technical
"":!~r';',';;""'Sl"  laSor"' hours	required	for" "each	ins'pection.
                 11. Labor costs for the engineer-supported inspections  (Line 9  4-
           Line  10):  The total labor  costs for the engineer-supported  inspections
           *'is  tne'sum	of" 'the	eng^^eVi!ngllh labor'''anei!1' tecnnl''cal'lliabbo1r1'costs: ' '	'
           'I 'EC1^."	Cost'ol "renting"'"1	the truck	for"each  inspection:  A rented pick-
              iiiiiii:; i"s iii i •' 9 ™	s, i fii" n i „ si • iiiiiiiiiiiiij. ปii!; 'i jiiiiiiiiiij'. ,i•; fiii: iiiiii'1 ...' ^' • \iiHh ifinii1 L i f! •>•'	iiiiii " 'l!i i;, i'ii'' .i*" P™"	"i • . iiiiii, liiii.; i', i • •' '• i; i;1,' •v ,, ":.'.. !i:' i,' i:, lijiiiiii'i;;' 'j 'i: ,'iii''. i? iiiiii? i "ii'. 'i ,A iiป m i' ii liiiiii;, 4iii!i liviiiisi1ซ. I1 i,: i' riiii1.: i ni in i! ^ ••'i:'"™'"ซ'J •' -" - !|1 ' ™ h'''
           uptruck isuged fortransporting  the inspectors throughout  the hazardous
           pilte  disposal facility.   The q^ted rate  for the  truck is $25 per  day and
                             ^ ซ|^|gj™^ ฃke'''Center"1 must	supply	gasoline.  The"  mileage
                each inspection"'1^^	'miles'	'^^ll^''''^^^'''^^^                 facility
                therentalagency.  This  results in  a total cost for  the  truck of
           ':;S36	per	day	($25	rental^'$7" mileage," and"" $"'4	gasoline) .  The gasoline
     ,'i	iiif1!; lililil ,' ป.: 'iiRi f .ป" ซn
           value  is estimated based  on  a truck mileage  of  15  mpg  and a gasoline
 ;™i'.';i: ;:;:"•":price  of $1.20 per gallon.
 !'== [^"j" ' •'• :, *f!':Vl|I	^AnnuaT"co'itlof ^renting _the  truck for inspections	(Line^ 2 +  Line	

 •'liiisi'..! .iiii"i11'.rii" .ii'.,; TtiiiLi!..i-isiiiiiTiiiii.!	iiiiii    ' iinii.!jw.'ih'i1.1!. s;	vc1.''-K''< v	in", mn^s,	i:'sawiป^('.i.'..'!^!!" ?	M C'Ow^ajp'wti^ruwfk.'iaJi?'i:jwf*iflM: i1*	r.;/. WKI:IL '.. s i'jj.	•" •	"	'	"• '•'	'ซ	"	
 '!;,ซ                         	'inspections  needel	(both routine	and  engineer-supported)
 ;™';'";;|	|;;;;":"":	^	M|; "the	Jaily ,truck	rental	cost	;_	^^	
 l^l^jjitl,: 14 .ป^,^7"^^^~^niMl':^spe1cticป cost	(Line 4 + Line  11 + Line 13):   The
            total  cost of conducting this post-closure  inspection  program is  the sum
 si f	.,j	i' plil:.ti?eปฃ	'tie'	"Innlal'"	total' laij'or'" costs	' for" "the	routJn'e	^spect'ibns"",	the annual
 I llllBs; I'liili. i,1!' iiVlll1  ' li mi:	.:' iiiiiiini	Ill	-'li1; .nil1	ill..: 11.1 iiiiiiiinE^^^^^^^^^ " iiiiiiii1'	.-1:1	nil. i Bui..;;1!!	n ..;i	l:!1!"!11 r	ill'	> .ii,,:)'!. IR 'i. .-.'ii'i- iiiPii.'!!	l1., l ir •<•' • m .1;..."! 'im!	< i""].1- iriiiiiiiiVjiiiLiaii. iiiiiffi....!!.:.':!!!^^^^^^^^^^^ .iti'. 'nKi	i .IBIHI	iiiiiw ,>iiiis.|i. . 	"iintii.". i . i	i'- .1 -i."; iiKi' i	'iiiiiii..!. ".mil	i ,>i	' " ..i

 ] ~ ',	.!	I  1" cost s  f or the truck.
                                                    9_ll6

-------
 B'   Routine Monitoring and Maintenance Activities
 Mowing Operations
      1.  Facility acreage:  The waste disposal area of this hazardous
 waste facility is 200 acres,,  This area includes the cover of the waste
 disposal trenches and land close to the trenches.
      2.  Mowing labor:  The waste disposal area is to be mowed periodically
 to promote the growth of cover vegetation and to inhibit the .growth of
 large deep-rooted vegetation such as young trees.   This mowing is to be
 carried out  on a contract basis by a mowing service.   The quoted labor
 rate  for this  service is $14.28 per acre mowed.
      3.   Mowing equipment:   The quoted rate for the mowing equipment is
 $5.37 per acre mowed.   This  rate includes fuel and all equipment costs.
      4.   Unit  mowing  cost (Line 2 + Line 3):   Adding  the labor rate and
 the equipment  rate yields the  total contracted mowing rate (unit cost)  for
 each  acre mowed.   Cheaper agricultural methods cannot be used because of
 the impact of  the heavier equipment on the  cover.
      5.   Annual frequency of mowing:   Mowing  of  the waste disposal  area
 is required once a year  during  the  post-closure  period.   This  frequency
 of mowing will  encourage  the growth  of  cover vegetation  and will suppress
 the growth of  trees and  other deep-rooted vegetation.
     6.  Annual cost of mowing  (Line 1 x Line  4 x Line 5):  The  annual
cost of mowing  is the product of  the facility  acreage, the unit  mowing
cost,  and  the annual frequency of mowing.

Routine Erosion Damage Repair
     7.  Annual routine erosion rate:  The annual routine loss of soil
from the facility is computed using the Universal Soil Loss Equation
(USLE).
             A = RKLSCP
       •• A ป Average soil loss, tons/acre
         R = Rainfall and run-off erosivity index
         K = Soil erodibility factor
         L = Slope - length factor
         S = Slope - steepness  factor
         C = Cover/management: factor (type of vegetative cover)

                                   9-117

-------
  I ili II
                         llllllllll
                      P  ซ Practice factor (terracing,  contour  plowing)
I	iHijiiplf ! iiii,,i  ii.,i, if t1 'i" '"I Iii! i':' I*•.:! 'fljrtfflC• ""I	i!!l!>ill!!!''liiiiti!!ii 'I!:'*''	! 1	Mftt: IS!1! ''ii'SSi 'I!' """'P1!1!	'iii!1' !• 'i;,'f>;illM.i J'Siii1'""'i' MH'Mi!: WMIMSlH''*"'i: .(H't i' I'1 i"i*	 ,*	Ii,"	:"i	ifM'j '" -i" 'Sit,I
1JS^'HJ i  '''!:"'' This	'ejquatio'n	'comp'ute"d ' f of	the'"sample  facility's  location  yields  an
           annual  soil loss of 0.12 tons per acre.   With a soil  density  of approxi-
           mately  100  Ibs.  per cu.  ft., 0.089  cu. yds.  are lost  from  each acre.   In
           oursubsequent  computations, we  make the  very conservative assumption
           thatall oฃ the lost soil will have to be replaced and reseeded.
                 8.   Total  annual routine erosive loss  (Line  1 x  Line  7):  The total
           annual  routine  soil loss is the  product  of  the acreage times  the  annual
II",1 • •Ili'lj1  i Jii i"'i||!i||li"''!'i|.' I'.ljli ' l; ,,!• ,llซl!|llllilf S.li'Mii 	PUi: WiAJH^^     	I'Mllli'1:,!!11'!1!,!' miE: •,'!' W,	miiiM1 ,: '!"l!|i:''!'i,,|l , ill1 i:i"l|i|iillll!JI .PlOJli'iil'P1 I!:1'	 ' i,'1" ,!!!!	',< !K Illllllilil11"J"11! 'll'IH!1'; 'l.iil'i'MPiCl^	II :U#i'U nlnii'EKhil'iii,'! '+!!1!,vt/,, ' iiu'illi'liHi"!'!!1,	•" , \\"\':"\i ",
"ซป'' "fii  i'i'i'ii ^oil loss per acre.
                 9.   Unit cost for  land excavation of soil:   Replacement soil will be
           obtained on-site at the facility.   Since  the amount of soil  required  is
           very small  compared to  the  daily capacity of earth-moving  machinery,
	'	ft'm-.-M'vji nan(f	i^or  will	be used to  excavate the  soil.  The rate  stated here is
JiSLPi'i!  i:'/1'!1'' "'ii'!"'1: I                                                                       I1
^^''"''::'= a'fully-loaded  rate for union labor working for  an independent  contractor.
           Thisunit  cost  is  based on  contractor quotes.
?*r*;T"!.,!;;^ '^"16.  Unit  cost for  on-site  transportation of  soil:   The  excavated
           soil is transported by  truck on-site  to  the location  where  the  erosion
,"	'"",,,,	" i,r"|/",p rep"^r" ""is	ฃ0"	be"	Jjjjฃie".	"^'is	service''will' b"e	provid"e3	by	an	iiiae'pendent
     •ill"' i f i1'In llilL 'Liiii11 , i'1!1' "U ! :> illllllllllillfr •' 91k , ? UK:, • l' ll, I'll	''IBII'i'illllllilii,ป illlliilH' Ii : in i * < il 11 :'i:	, < -1!	'•• ,i,P"l :l ,,,i"!	',< • IH	"', >' , I1"1!" iiinliป <" ,Jln|l	In-!" ',111	' I! iH1ซ: I"., ",,i' s 'nil, JI1!:'' "I11'1' I, III! ;iill|lill li ' J1111!!,: lllllili Ji	ll'tlil' 'i!:",' „„  "II!,, 4 ,i Jlili'i! nil 11,1, •! tfiiil118' "if1"' 11 lilllllll,'' i -ti'1!1' I !l|i"i Pi"' !i", „" '„' ' ."„ lllh	,
	fi'lirj-fiij1'c^pLJeractpr.	
                 11.  Unit  cost for compacting  the  soil  by hand:   The unit cost  of
           hand compacting  the new  soil as a  repair  for erosion damage is  estimated
'•"•  ' ' '  l|"l!" to bVthe  sSe  as 'for  hand excavation of"'the""so:itl."	""'This  service	will	
            be  provided by  an  independent  contractor.
                 12.   Unit  cost of  seeding:   The cost  of seeding  is a  function  of
:	aiiiiiiiiiiifii'i I'l'vi ji • n: ii1"  , < ipppiiiPi:' iiprcu,1 > R'i-'.iHiiU'i iniii'iiiniiiiiiiiinii; uIIPIIIPIIIIIIIIII .HKIU'"!,!"!! .i.'iiiiip1 • i!111:!;""1:1;;!**'1 in ," " riiii'"Hi  ni,:K, 'ifrii/'iiiimiir";: -u i1,^"!!!'"!!:!!!! iriiw i *	IPP:	IITINIIII,.!iP,i,Miv^             	iiiUBPi'iw in1, iiipaiL"'*'!!'!	', "mill,;: di1 i"";iv /'i/."ii,1 ii'iiiiii'; PIP' ii'vimnm1 '!ซ
:;	••	ii,	• i, ii  • - gies^	surface area of  the  new bare" soil.    In  our  estimates, we^ assume
!:'":::  ';"•" ':"::,":, tha't" a	small	gully"	(or 'gullies')	Have	'formed'.	The	ratio  of "surface  area
J!:1!ifi i"!!!1'!/1  Illy ":i """'' 'Ili"!! '"I „ !|lli:T!, i'!1' ''['IK    JVWWKciJ, ;•	(• J[	iii VI t;'" i:i""!'i"ii1 f ::S:;KiiJSit'/i'.'Wi'ia!	H1('tft8KปfttJ*'ifซlilซ!WHn*ปi•!"lilS	8tiliiiHS'	nt'K: 'iiiiirl'lllii'';^'"	'	':"	'in '"'''"'-"ii'"	," 	'	,'"'i"'	'	'' i
'sratit.™ i™ .'to'Ibll'volume  is  small.   This  new soil  is  seeded with the  same type  of
;:ซ W! il Fii'IliE "ii' "R' lllllil ft: j? '*v4;'T*i''.aiB(i \mi • "I	m, W^>	ซ:: W,	•:-	;	i	>( T>,i S>	fl	ซR"ir'.'!f1K :!i"'ปWW!i ''Iii!! 'liFiFfi, •-'f I il'' tl!'fii!!;.;"fll. "'i „ :ir W-i if! ™	I I'm, n	IF m\t', ,l:'"i
            grass as  is used for  the original  cover  vegetation.
~'~::;:;:,";'"'":::::', V^Z'lS.  	AggregVte 'unit' cost of repairing' routine soil erosion  damage
	            i      ,            I! '      ,. -
':'—.";7ri;':.^""'i(LJS,e"^	+"Line"""10"+' Line"'ll"+  Line 12):   The aggregate unit  cost of
IS. '::1,,1  lit le'|liri^g""t:h"e':	fo:u:g'|n'e":	:|oii"	erosion	is	tfie "sum  of  the excavation unit
               jiiiiiiT'ii'' 'iliri'iiii "in iLijiriiiii'iiiyiii;! liijiiniiiiiiiiii'':!' "''iiiiiiiiiiiiiiiii!  wi'ifVL         ,:!,'! fnii s • "if!11 'L'ii'ii1,!;",;!"!!1 ป,.'! In1!11 
-------
 repairs under average rainfall conditions is the product o.f the amount
 of soil lost and the unit aggregate cost for erosion damage repairs.
      15. Adjustment factor to account for unusually wet seasons:  The
 .above cost (Line 14) is computed for average rainfall conditions at the
 facility location.   A safety factor of 2 is applied which is the equiva-
 lent of increasing  the rainfall and runoff erosivity index (within the
 Universal Soil Loss Equation) from 150 to 300.   This changes the facility's
 rainfall from its actual mid-Atlantic level to  the high southern levels.
 This conservative assumption is required to allow for the annual variation
 in routine rainfall-caused erosion.
      16.  Adjusted annual cost for repairing routine erosion damage (Line
 14 x Line 15):    The adjusted annual cost for erosion repair of a routine
 nature  is the  product of the average annual cost and' the adjustment fac-
 tor.

 Replacing the  Fence
      17.  Frequency  of replacing the fence:   Security at  the facility is
 provided  by  a  6-ft.  high chain link fence that has  been  established along
 the  entire perimeter of  the  facility (11,808 ft.  in length).' This  fence
 is made of galvanized #9 wire.   Operating experience-at  this hazardous
waste facility  indicates that:  the  fence must be  replaced every  15  years.
Thus, during the  anticipated  30-year duration of  the closure period,  the
fence will have to be  replaced  once.
   .  18.  Facility perimeter: ; The  length  of  the security fence  is  the
length of the facility perimeter (11,808  ft.).
     19. Unit cost of replacing the  fence:  .Quotes were  obtained from
fencing suppliers for a new fence of equal specifications.  The value
given here is a unit cost per linear foot for an installed  fence.
     20. Total cost of fence replacement  (Line 18 x Line 19):  The cost
of replacing the perimeter security  fence is  the product of the perimeter
footage and the unit cost of the installed fencing.
     21. Pro-rated annual cost of fence replacement:  The total cost of
replacing the security fence is pro-rated to each year by dividing the
total cost (Line 20) by  the number of years in the post-closure period
(30 years).             -

                                   9-119

-------
       Fertilizing
            22 ..... . ...... Unit ...... cost of 'fertilizing: ' The hazardous" waste ...... disposal ........ facility'"
       has relatively poor soil resulting in  the experienced necessity of annual

       :-	•'fertilizer	applications -until the vegetation has  Become established,  &
       " litiiiii,; : i,; ; " III* II! i!lil";l;= *MM lllllll1-!,.! I1;" B":	1,5	. •' *• • • "W	i	":•• :!ii," r v..':.? u::„!f:i w ;ปTlas;",;;'	;.'i:":iii" :'\mi 'ปj\\ \ f-sx^	,,ura' -i	*• :•, -1 i;  ป i
                                                                                               i • ............ . ........ " •
                                                                                                   ........ ' ........
'lit:]!. ' i >i '•••, !! ...... it

       ;Lfi:
                                               ,
                 Equipment                    $  5. 00 /acre
       Preiiqus ......... ejcperience ..... at  this ' "facility ..... ftas ' Sfi0'^ ...... ttiat ...... tn'is  application ..........
       ..... .'  • jmvซ ........ : '. ..... liffi >" "f>mฃ: •; Jllllll •!" 1 ..... .'" '!,„ ,ซ ซ'!;; ซซ||;i ., ,;( ...... Ei - ' v", J- , ! ' f ! .; : , ; • ...... •.; JitE ....... j ..... •; ', , iri? i, ป: .......... ,i,: at! ' ".! "SB ' !M ..... "C i!!liป!!1 , ป: ..... lEiii! ..... ;l|i S : ', ' 3 ' • ". Si! ; . , • ' • '-. lii ........ I .......
       rat!  for fertilizer is  satisfactory  to maintain  the vegetation.
                                                                         P
             23.  Number of applications of  fertilizer  for the  first 3 years:   One
       application of fertilizer is needed  each year  for a total -of 3 applications.
             24. .Number of applications of  fertilizer  for remaining. -years  of  post-
       closure (fears 4 through 30):- One application  of fertilizer is  needed every
       5  years, ....... or .......... a" total of  5 applications  for the  remainder of post-closure.
             25.  lotal  costs of fertilizing for the first 3 years oฃ post-
       closure (Line  1  x Line  22 x Line 23):   The cost  of fertilizing for  the
       : f'l,rat;.n,3, ..... year's" ........... is ......... the ...... product "oฃ the  acreage fertilized,  the unit cost  of
       .fertilization .......... and the .......... frequency of application during the first  3 years.
       The'" costs "o'f .......... fertilizing '"for"" the first 3 years are then $80,460.
             ii,-26. Total costs of  fertilization for years  4 through 30 of post-
            , , IllijSr f: '"'iiiiit:!!!,!1! 'iiiiiiii 'i^ >:9 ...... "j1"1"1!; "Pf'i ' i;iniB;''DBSIt;"''|aiftl ft,"1"".""' ...... ;tIv:"Mi" ms^Aiiir^ni^jjfii 'it&nramn.}' ..... iSfiiiiNitiisi'] ;;'.•• ""Li; ..... ;:"•' ''.HAIII.
          eilqsure ....... (Line  1 x Line 22  x Line 24) :  The "cost "of fertilizing is  the
                --  ...... O'f"
                                                                                          t'"i: till1 : :-fH
                       ..... acre'ag'e ....... fertilized,  the unit  cost ..... of fertilizing,  and
        the frequency of application during the years 4 through  30.  The  costs

....... ...... .,
          'for ......... fertilizing ......... for the: ..... "remainder "of ..... pbst-cibsure 'is ........ th"en
          '•  iiiiirl? . " Tot'ai 'cos'ts" of" fertilizing ......... during' ..... poist-'closure*. (Line 25 + Line
         '  ,: • iliiiil'il. ซ" JB;'1' .ii ' li|j';:i: ..... i ''"I""1 Willillli1 ,  liiiiliilll! '' ..... I "'I1 .""iHiliil'liniK''!!'!'!1 ..""'Illi'1!' !|i|i|,i,iji'l!!'i, :•!' .Lun!'1!' : '1JP'iป,.'.!i!;i:i ...... Nil' '!l i.i:"i'iilii# ,ifi, ,'A<, ... ii iihihiiiilBIM!,:,!!1!!^ "I:!i:11!!!:,!!!,:1 VL!T"l:!:!!!E!i,:i!!r\!!:1 '"' ,,,"',; ! :!L;T!'!,!!!!|!i 'I11 11''1'!,:',, ,' ',,:'!':', .i!!!'::!!!!1,,,," ' r :,! I!1!!"1 ,;:!!'!,„: ' ' :!,
         • 26) :  The  total fertilization costs are the sum of ..... the  costs' for ferti-
          ,':! ...... , '''B^WITW. ifSป ...... 'jWW'FVi; ir^W?**'?.^1''1''?^''^^': \'^ ..... *..•''.' ....... I ...... *i ......... B1*?* ...... iifflsiiiJBiwh, ........ •<**, ......... >•&•• < ....... fw  •
          lining "'during'" the first  3 years  and the 5 applications  required durzng
          j^^ remainder of post-closure.   The total costs for fertilizing
                                                                            I
          the, .......... entire ..... 3,0-year period are then  $214,560.
           :  :::„: 28. Total annual costs of fertilizing  (Line 27 4- 30):  The
          :. ; ' , iiiiJ ...... iv*. ...... 'fiw ...... :; ซr.4n Wft ....... t ........ KM: ; ........... V1 ....... KL: ..... r , .J1 1 ..... 'ii? t"r ...... i ....... ;' ..... i ..... • ..... •• •' <• • i ..... mm ........... - * ..... . ..... • w< ..................... as :,ซf ;; ......... K ...... ^ • •.  •* ....... •*< ...... <•
           total ....... costs ..... [for ............. fertilizing for  the 30-year period .......... is .......... divided by ..... the
                                                                              for
                                                                                          ,• ....... , ............... L ................. :
rfm 	 ! 	 f||1|i|i| 	 ( 	 J 	 r| ( 	 , ,_ 	 r,Tt
;~ i;/:;:-',,- .;.., ;--:- ;;• ,,",|::"," ' ::•'[*
	 	 	 , 	
j,!"! | ||f 'I.Jijji | •; i < 	 ! |i if, f'i1 ,,!;!. ' J!1;;; 'i"i' , ;,i' ' i|>j||

,, IIIIIIIB^^^^^^^^^^ ! ."M,. "" 	 	 'H'r'i,;' , ' lE.U,,,, 	 '/ 'K,,,, ' /lilllii
1 i||| Illlllllllllllllii , Jllihillllli'l 1 liHI'Vf, .Inllilllill i „ ,r!P ''111" " < illilrrilllli, ,, fiti V ,111! 	 illiillllp;11 : i jlh 'illlPilllllllllllllll,, "

|lrj| , lh| h|||| , if 	 	 	 || ,,,, 	 ,, 	 1 ,, , , 	 „ _ H 	 ^ 	 ., ,||r 	 ,|||,,||, 11(.,| „,,„,,,„„, „, ^ ...
:;:i=i: :,' 	 •", 	 •,: ;:,-•.. ... : "' ..- 9-120 	
	 	 , , 	 ,,,,„, 	 ,, 	 	 | 	 	
i*!! •••: ', , ,„ ;„ „ ' ; • i,j; ! -: , " ' ' , ,'""•' 	 ;, "! i '„!, " , i, i "s si,", >• is , '• ' , '',* ' ,w, ' "PM IV't 	 	 5 1 * , s IF i!ซ ,, ',• „ i ;;;! 	
	 •• 	 • " 	 	 • 	 •" •• 	 • 	 - • ••• '" 	 i 	 ! 	 •
IIIIH"!!, '• II, '; 	 !',',' I'f, ,: ), i1",!-!!- ,; 'pill Jl'.'.I , ,, , i till!,,;! , ; „ 	 !,:,],, 1 	 	 ,iji, I ,', 	 HI'1!"1;, 	 I i. " ,f-if. 'i,|, !"l 	 lllSm- I', ',i, ,'
, 'IIPIIIIIIIIIIIIIIIIIII ,n ',..:];.,: !:,|:1! " 	 J 	 Pllllllill 	 	 ll't'lii, ป,! .PIPPII 	 Ullllllll , pill III! 'I 'nllPi.PIH :!!,! 	 llll'l'llll: 1 1 	 1, 	 !,. , i , IJI! "It! ,iinl .IPIIIII 	 1 	 Illlf'lJiiiPh I!.! 1*111!, I ,' ' IIP ' !ซ,,! ' : "PI'll „!: IP! 	 III!' t! !" 	 Illil I1 illll ' lli..lllllllll|lllป:l!!'ll:: PlIIIIIPP !!, ,! llllll 	 IP ' PIIIIIIPI I Illlll IlLllllllllllll! 	 II 	 1 'iPlllillllllllllllllll'p

| 	 ^


>'1HW-


:'is?ฃt;

,,! 	 	 fifn
	
	 ; 	
•• ," ,'iซ.iiปrrijป

', • ',,1,1 ,; ',ซ" ,",,ii in;; 	 i!
,.;;,:.,;, ;ซ:!', 
-------
  30 years oฃ  the post-closure period  to yield  an  annual  cost  of  $7152.

  Ground-Water Monitoring Well Replacement
      29. Unit cost for-well replacement:  The lowest observed depth of
  the water table has been closer to the surface than 50  ft. throughout the
  active operation of the facility.  A replacement well to a depth of
  aprpoximately 50 ft. will cost $425 when installed by an independent
  contractor ($8.50 per vertical linear ft.).   This quoted price includes
  a suitable casing.
      30. Number of wells needing replacement:  The monitoring wells have
 a relatively long useful lifetime as do residential wells.  It is antici-
 pated that  two wells will have to be replaced during the post-closure
 period.
      31. Total cost of monitoring well replacement (Line 29 x Line 30):
 The total post-closure period cost of well replacement  is the unit cost
 of each  well multiplied by the number of  wells required in the post-
 closure  period.

 Leachate Pumping  and  Disposal
      32.  Frequency of  removing  the leachate:   Leachate  is  removed perio-
 dically  from the hazardous waste  facility risers  by means  of  a vacuum  truck.
 Every month,  the  truck circulates  to  each riser Dumping  out the  collected
 leachate.  This service  is performed  by an independent  contractor.
      33. Average total monthly  leachate withdrawal:  Since  the facility's
 cover system  is quite  effective in reducing infiltration, only 2000 gals.
 of leachate  (average value) will have to be removed each month.   This
 leachate Is removed to an off-site  disposal area.
     34. Unit cost of  removing the  leachate to an active off-site disposal
 area:  The unit cost of removing the  leachate  includes driving the vacuum
 truck to each riser at the facility and removing the leachate and deliver-
 ing the truckload of leachate to the  off-site  disposal area.  A relatively
 high per-gallon removal cost is quoted because of the necessity of collec-
 ting a small amount of leachate from each of the. widely  dispersed risers
 throughout the large facility.I  This cost includes, transportation to the
TSDF.
                                   9-121

-------

1 11
     I          II II  I II11 II I11  I  ' V, 'I ,  , , 'il	 '    ' , 111 ;ป' ,, ' , ' • ซ HI  <„  i 'Til''!'•,,ill	I	, , J'! "'Bill I 'i;l	lllll'"l'l''ll|l|!l	 'I ' I ,."i':i"ll' ll'iill,,;, ,i ," ,'i|i,'i|i||n  I, 'ii'.'ll'hiii jjH"'	 '.' nl"
       35. Total annual cost  of removing the leachate (Line 32 x Line  33 x
  Line 34 x 12):"	The	annual  leachate'rimbval'cost	is	the product  of the
  monthly leachate volume removed, the number of months in a year, and the
  unit cost per gallon removed.
     Ill IIII III II III III I II IIIIIIIIII III 11 III Illlll III I  I III II    I    II I I I II   11	' .  1!, "•' 1,1 ,ป,..'	'"''i,!,,, 	 lii ,,,! .'i:1,,',,:!! 'i,', , , |. .SViilMMi"1',11 ,,I"'!!H "." t1	••"	I'iMlliinli'"!11:,'*! I"	^lijjii.^i'is.ii'i'i	 iW' "'-""	•ป''' '- _. •• - 	 '
       36. Unit cost for  removing leachates  to an  off-site TSDF:   The unit
  cost for off-site disposal  of the leachate."%nia"teritai is $.05/gal.   This
  material is disposed of in a surface impoundment.
     	 37. Annual costs  for off-site^ disposal" ^(Line ^ 32 "x" Line ' 133 ^ x ^ Line	36
  x 12):  The  cost of  disposing of the material in the off-site  surface
  Impoundment  is the product of the amount  of leachate disposed and  the
  .unit,, cost	for  the.disgosal.	
       38. Total annual cost for  removing  and disposing  of  leachates  (Line
  |3	+ 'Line'37")':	The "total cost  for  leachate removal and disposal is the
  sum of  the .removal cost and  the disposal cost.

  Ground-gatefMonitoring

   !''^39?''	NtSber	of wells monitored: " This hazardous waste'facility  has
  •,'|jT	|row5-|a|er	monitoring' wells.''""' One "'we'll 'Is'11uygซฃฃent	iH<| 11 wells
	:; •: are"'"downgradient from  the  disposal area.
       ;"ฃJ	]	flSSe?	of" samples 'laken'per'well	(annual)	:	Two""	^cycies" of	
  ground-water sampling  will be conducted annually.  One ground-water
  quality"" analysis "and'"two""'ground^water ' conFaininatibn	analyses are  to be
  carried out.  One sample may be used for  both the  ground-water  quality
  and  ground-water contamination analyses.   Therefore,  two samples  are
   takenfromeach well annually.
     	41. Total	number ^of^ sables ^annual) _ "(Line_"39 ^^ Line "46) V jTbe^	total
  numberof ground-water samples taken  annually is^theproduct ofthe
   number of monitoring wells and the numberofsamplestakenannually from
   I  Illlll I I I  I Illlll  Illlll  Illlll  I                      i,,,' ';,;,; !•..., I1:,,,,;,,, ',;;"! IW J illtt!	::: vt- If"' I '.it;"!" .nHS :' :l!'*"!;,'", :• ;' ,111  ft •;".'' it iilJIII,,
   each well.                             	
        42. Number of  hours forcollecting  the sample(persample):   Each
   sample requires two hours  of collection  time.   The well must be pumped
   dry andallowed1 to  refill.  Then a sampleis taken.The  facility ex-
   perience is that  approximately two hours  are required for each  well
                     ie some" tine" for "moving about"	"tie	fields).
                                              9-122
 inn ii 11111 ii 11 iigi in nig inn 11 n i

-------
     43.  Total number of hours for collecting the sample (Line 41 x
Line 42):  Annually, 24 samples will have to be collected, requiring
48 hours of labor.
     44.  Total number of hours for preparing and delivering the sample:
The total number of hours required for packaging and delivering the
samples is six hours per year.
     45.  Total sample handling hours (Line 43 + Line 44):  The annual
total time for collecting and delivering the ground-water samples is
54 hours.
     46.  Person-hour costs for handling ground-water samples:  The
person-hour costs for handling the samples is based on the facility ex-
perience of $15 per hour fully-loaded.
     47.  Total sample handling costs (Line 45 x Line 46):  The total
labor cost for handling the samples is the product of the hours required
and the unit labor costs.
     48.  Unit cost of ground-water quality analysis:  The unit cost
of an analysis for the following parameters is $77 per analysis:
          Chloride                  $ 6/sample
          Iron                      $12/sample
          Manganese                 $12/sample
          Phenols                   $25/sample
          Sodium                    $12/sample
          Sulfate                   $10/sample
     49.  Unit cost of ground-water contamination analysis:  The unit
cost of an analysis for the following parameters is $108 per analysis:
          pH                        $ 4/sample
          Specific Conductance      $ 4/sample
          Total Organic Carbon      $25/sample
          Total Organic Halogen     $75/sample
     50.  Total cost of ground-water quality analysis (annual) (Line 39
x Line 48):  The annual cost for analysis of water quality is the product
of the number of wells and the unit cost of the analysis.
     51.  Total cost for ground-water contamination analysis  (annual)
(Line 41 x Line 49):  The annual cost for analysis for ground-water
contamination is the product of the number of sample sets to be analyzed
and the unit cost of the analysis.
                                  9-123

-------
Ill Illllll 1	IlilliSl^KB
                        r.ปi! *"ซll|	II":'! ,1
INlllll1


11	Illllll1
      rsiiiiii- if.'i   iif H	•;  ii	if.;;
       lifll:,	SI I	;:  liliit! ,1;,'!	JtK*:
                                        :,/,'ill,,:'"!  "!,"!-„:,I1;;,   nc.'if; ..'ii	?m,"
                                                                                      J*1: •  :rili;"4	1 iJi^t*if
                                                                                      l^n'^i;	ฃ m	ililSfi  >	i
                                                                                                                                                 	;ji	,,,,	];:i,;ii:i;iii::i, _;	,,



                                                                                                                                                 'liai'lllllll:,!	Illllll!", Illllll;, 'W'H^
                                Tglal	annual, ground-water  monitoring  costs  (Line  49  + Line  50  +
        ^ I _'' ~ _ | Line n_ 51) (:	The ^ total	^ annual i_	co s t  for ^ ground-water | analy sis | is	the	sum pp f	^	^	
                                                                                                                  contamination
      I'1 a I, I :i'll!!iJ"

      !' '.H.1 I nt'tt!

        i: 11''II!::, 1 I,'?'
                      iiii-il'lliii'lilW!lISIlMI'lii 'lii-llfli!!!	 .'I'llHl  .'  '	'„	""M":I"':;,,,1, ]'.(, ';"'! '',!!  „  ::"!"";]   „:I'!11,',::"!'	Ill,", I;.',  " ;  III,,!,;,!, :":"ill,:ilt, .,'illi'lli "I'i'llll	•• (KIF.T^!'i: (I,ซ('rt :*":ซ,,	, '!" '! ;!',,lli,i!!',,i!l i,,1   ','.,'" .

                      Ill,; |'1,11!!1! I C	I; III!!,'  ;;	lull!!' illl'lltl' ' ! i1 ;,„'I:!'1' ' gill;, 	 ,,,, ' I',1!,;!!!!!',;' ,,li"    a,,'1':' !'  ' li;!!,:;ii!'i' 3!	ii,	,!",,: :;'l	 ,,,:,'"!''  I,;,,!,::,;::1 MIKiiuli; ", 'iiiill!,'!,, I, Jill,1 ,,|;!!!'rill; "",'', '", I,,'!;,,! Hi,;,,, : :'•,; ''',':'• ."Hi;;!"!!:'1,	:",;„:



     ,,„::;,:	",.::gputSHe. Maiijtfinan'c'i	• SnnrniatiQn    "."	.".'".'."..'.        .."  '".."."'".'	'   '",'''','„,'"'	„"',"'	, ""	'"'	'	
          mill r it,,1 ',"ii ,i ' iiiiiinnniiiiH^^	iiiiii'ii'i'iiiinniii1',:, i	,,,i, n,, , jiai'i""'1,,1;; HIT	i* iiinnnni  ', 	r?	•„  • i<

          '•ilii'ill I*': '    ' iiii,'iilliir"M ""liii'iiiiiiiiiiii,; h,,, if' ;;iii,,;,!';w^      !•'ii""ii:,i,""',''';'  ,::'iin:"i'ii,''ii,,  i";,'1'! ,IMI ';;'i  ;„ "',;;i,",ii,,,:''ii


                                  ili'llli	IIIIH lilill M, ,1'l'i,,,"''"	I	:,„ l:l!,':'	lulti" •	" i'li >„ ,,11, >,';;	II; ,"	iMV'*	"'.I,,'!"
                                                                                             II i jr:1, a ' '||!, , ft1,  ','„,!, H  ,:|,i| lliplllR, Li "'"Hi	I
IllJIliilllilEL
It'll'! 'lillll'i:  I ',,,|,
Illllll:'!]' I ''i,:
            *1!|™,;';""' ';S,rtj^7ijปU '•w^!friaJH^$Q>\ iP,3 I'	f -f $$&ป S^T^n;	..f^jM^S^BfRฎ?	f^im


            ,4^'^iiitoring1'	operations" are	"added"	together 'to  yield  the"'1" total''cost  ('annual).
        .,,..„__
        ,„!! 7IIS1; , Ililllt  'I' ','|,|,
        ill, -in, (lips	it ,
                                                                                           yield  the	total	cost  (annual)

                                                                                           ."iiijB	iiliiii'iJiii^^          iriiiiiwIV  ',' i1:

                                                                               tive  costs which .are  computed   on  a
                                                                               ill'i'll'"!!'!'!: I! WIV* "SI' I.'IM i"iiaปSซ	EWWri' kHSl;,;1 Jr.' 'I li:,l!",'i|S,.,		   ,".,	
                                                                               I'll,),''!, {'"	!',i"ii;	' ::r "i:: 7f i iqil!: Irllfl .'I'liiilillii'lllB^ I'.')';!!.!!!'!:!!'	IIR,:]' i	;'Mm .fj'';'' :li,i!' f,  '';',''i:|l"l i'.!;!!1:::	"•,! :t
                                                                                 !ป:,!'.'	'''' liillii"'-"!!',-'!
               	.ng  operations  are  added  togethe
               I'llldrlillA^ 	  <,,ซ	r,,	I	"M,	'	n,	„,: n	n' : in '	„	'	i,,''	ii' ' "	,;i	', „!' i'
              ii.':',:"[!	iiiii'iii,'iiiiii|iB  i 'Biiiiii',',:' > JIIIIIIB 	11	i,iii:ii,:iit,i' :i:,iiiiii!' i'u, laiiiiiw^ iiiisii'ii'ii, 'i',,," 'i, nil" M',;H""";i"' 'ii, m ,",<

              cost does  not  include  administra_.
              irn^^^    	li'i 'illlllM^^^^^^^	'1'imS', HI	t; :l"illii!"ปl	I! I	K itl" 'iilllif:':"" •Il<"'':: ^   " ^  -
           ,,	H||l;!! !iซ^^^^         i iJllH .1' ,li! i! i 'liiii!1,' 'III' B ,'IK^^^^^^  IB!:! !'' "i!!'  1 f Vป*	IIEIIIH'''!	

         parade  worksheet  (Line 53  + Line  54 +  Line  55  4-  Line  56  +  Line  57 +

	Hi: ••        i:iiiif::mum	^.si*i"'^ ?;,ซ!'ซ"	j. ^	'	^ r •• an	iii	K .* rT . i i	a	i	m	F	i%ซ.;'	•• m w;i B • NM-'	m	

	,;,;,;-.Lijae	58. Jh	Line	59).	


,;:i 'Vki. ' "  ii',' iiiill!1"!"1" up1"  iii"".:in,i  ..  innniiiniiiir'  iiiiiiiiiiiu;1:,;,ป,;;ii'.\ u:,"ป  \ ,,,', h, •	.xitun11:, ,
          ll	i	ii'tii, 'i    iliiiiiiiii) u,,i, 'i!:,!"1!.!
                                     .illlUII!"'"  iltllllilll"!''!"1  ."it  ",S1	
                                                                                           i" ill Iliii'llll1"!'1'1!1!1'1;"!,,*1!"!,"! ill!,':!,!)..',' F, I'1'1	 I '!	•JfWVi1	-t!'i,,;,i '
                         ,1.1 Nr '" ilfll1 'I'I""
                                                                                                       '"mil, "  iiui"" ii1: Hi'
                                                                                                                     ,,1,1 'I III" I I' I 	' i, I'll „ *    'I'	Illill'
                                                                                                                                                 11111 u'liii:' n'1' 11 UN .iniiiii1 '"Vii:
  IWi! Illllll lllh V i  Thl" liilli'tlii:
                        ' li'ltH'l' " ' 'I'ill	Ill1 III." 'I'iliiill'K1'!'' , I'l'iiIllllii	Ill'1 ',
                                                                                              ji 'ill1'11 ":	"i'11', 'ป.; ii|1J'i,r!',i ,
<1HBL,|:!:U'| l"Hu  •''i  • •ซ!, i '*• !ป,,,; \_  W*,; ป**': •'   ')",	  ,'!    I1;,; "i!:|"l|:';'; \  ..""f1 :| :   'i:;'i



'"	' ,,:':;ii i r iT \ •. ^ *•  iiiEitii;	k *":!''!': '• A \'  :;;" ''OIF  iii!;:;iJ i', "i";: i;:1:"!"':  ':;;i •>  ' • • 'i	i' • '^ $f   • „. i'!  ,. *%
      	lii,,!::,f'''.	I,'!.  !'  , , iliiiri i,'i'"   '11,*.?  ..- '.iHiI:  I'1 illllll  •.>.->	L>.	i1"   • ''*  ' , '  „•
      ' in	i' * ,' "':,in  ,  , i iii	"    "t, ',  'ijiii, mi  n,,',i•• i'  i  !',i  	   M ,	"mi:
                                                                                                                 .

                                                                                                  lfl'  :>'*•.':ซ;'.ป?•  ii'
                                                                                                  V:,;!1   i'!' ,	Ii"'!,1"'1!,,;1!,  iill I II
                                                                                                  ;;1, ,,,;  unfii' 'im , I'll	mi, , '  	
                                                                                              iMuT'l'1"!! "1|!'i"
                                                                                                                                                   i  i  i inn   in      in
                                                                                                                                                   	i   I,.
• liUiH1,1!!1
                             	l,;l:	!l,::"i ajililill;'' ''I'llilll '„*';,'":'!'„ it-.	' ,"1:',' >Si	„' 	!•.'
                                                                                                      Sill! "l if llUli!1,,, '!'	 'ifc'vltll^'JlV1**  „:,'*'	I'',:, ',i''"i:"ll
                                   ;'' nil IIIIH I,, ''Hlllllllll
                                                                                             III'1,,!!,''',,'I ll j,,", ' i' ''[tilh1"!'1	
                                                                        :   9-124

-------
C.   Erosion Damage Contingency Scenario
     1.  Percentage of vegetation removed:  Some unplanned events that
will create additional demands for care will occur during the duration of
the post-closure period.  This worksheet  computes the additional cost
that would result from such an unplanned  event that removes 30% of the
vegetative cover from the hazardous waste facility.  After the vegetation
is removed, the soil remains! bare for one month expos'ed to normal rainfall.
Resulting erosive damage is repaired and  the bare acreage is revegetated.
The one month lapse between the damaging  event and the revegetation allows
for delays in the discovery of the damage and the time required for the
revegetation steps.                                            '
     2.  Facility acreage:  The entire facility is impacted by the event.
     3.  Acreage reduced to bare soil (Line 1 x Line 2):  The acreage
stripped of vegetation is the product of  the percentage of vegetation
removed and the total acreage of the facility.
     4.  Annual per acre soil loss rate (without vegetative cover):  The
                                              ;               ~   j-
annual soil loss for each acre of bare soil is computed using the Univer-
sal Soil Loss Equation (USLE).
             A - 5KSLCP
         A = Average soil loss, tons/acre
         R = Rainfall and run-off erosivity index
         K = Soil credibility factor
         L = Slope - length factor
         S = Slope - steepneiss factor
         C * Cover/management factor (type of vegetative cover)
         P = Practice factor (terracing,  contour plowing)
This equation is for erosion resulting from rainfall subsequent to the
event  that removed the vegetation.
     5.  Monthly bare ground soil loss rate:  The annual loss rate
computed in Line 4 is converted to a one  month loss rate.  This conver-
sion is accomplished by dividing the annual loss rate by 12.
     6.  Amount of soil lost before repairs are instituted:  The amount
of soil lost from the bared ground is the product of the monthly loss
rate per acre and the acreage of the facility that is exposed.  This
product is then multiplied by two to allow for soil lost during the

                            i       9-125

-------
  removal of the vegetation.  The ground is assumed to be bare  for about
  one month before the repairs  and replanting are completed.  The  conversion
  to  volume of soillost is carried outassuming a soil density of 100 Ibs.
  per cu. ft.
 _    "7. ".tTnit	Icoit for "excavating'and loading' soil: 	The unit 'coat"for	
  excavating and loading replacement soil is computed using a 2 cu.  yd.
  frontend loader.  This operation will be performed under contract.
       8.  On-site haul of excavated soil to the area needing repair:   The
  excavated soil is transported on-site over a 2000 ft. distance by  trucks
   .;  ;;;;;;;;;:	;,;.;„	.'::. .;;=;.'.—; -.". .  '	  ,   ....  ,	,;.. ii:,.;.... ;,:,.  4,;., ,::i,:.  . , ..
  operating under contract.
       9.  Filling and compacting eroded areas of the facility:  The replace-
 ment soil is filled and compacted into the eroded areas using a  dozer
  operating under contract.
      10.  Total unit cost for  replacing soil (Line 7 + Line 8  + Line  9):
 The  totalunit cost of replacing soil is the sum of the excavation-
  loading,  hauling and filling  unit costs.  These unit costs were  obtained
            ""'                                                    !:
  from estimates made by a local  contractor.
      11.  Cost of replacing the  lost .soil (Line 6 x Line 10):  The  total
 best for  replacing the lost soil is  the product of the amount of soil
 losttimes,the unit cost for  soil replacement.
      12."  Unit cost for seeding  the bare soil:' ' '.The .unit.^ cost ..'.for seeding
                                                  '  	  	j,	
  the  bare  acreageis computed  from the sum of the labor, materials  and
 equipment costs.
..!'    !;;,!".  ''•  ;': " !,liงbqr        ,  .        ,$69.10/acre               ]
      :	  "Materials    	$13.90/acre:	'	  ' 	'
'^  •  "•'- ">'•   (" .Equipment     	   $ 5.00/acre	 '"	
 The  grass planted is Kentucky bluegrass  available from a local supplier
 at $0.32  per Ib. in 50-lb.  bags.  The application rate for this seed is
 1 Ib. per 1000  sq.  ft. (or 43.56  Ibs.  per acre).   This  is less than one-
   " ,   mi: 'Hi1"!,   , "'h'lii'i . I'liiii ' iri'Bii i " i, '  " •!  LI,/ 14  •!'! ••'  '' ;;!i, i,!1. • .(''!"" ซi "  ii '",„	 /i,," i' Hi1;: IPS •„:,•: .i'i''n,, irtiiirii,,/!' jniiiu11'1!:	•• r iiFi, li i.:!iii,,'i*v	MI	• t^vit "!•;' ,• :  '"Mil „
 thirdof  the seedapplication rate used  for  home  lawns.   Experience has
 shown this  seeding rate to be satisfactory.
      2,3.   Unit  cost for fertilizing:   Since  the soil at this  hazardous
 wast€ facility  is quite poor,  fertilization  is necessary.   Type 10/6/4
 fertilizer  costing $0.12 per Ib.  (in  50-lb.  bags)  is applied at a rate
                       v                               .          i1
 of 500  Ibs. per acre.   This corresponds  to a nitrogen application rate
	i, .,    ii!'11' ;  i  • r  , ''"'iijii • ii/wi, v • ,,'!.„ '  ' ,,r  ,	    * ,  ,„,	 ,  ,,   , .„, .,„ •	 P „„, i	F €,,	,,.,	.I,		
                                      9-126
i	   <;  in    '   
-------
of 50-lbs. per acre.  The unit cost of fertilization is the sum of the
labor, materials and equipment costs.
         Labor                      $69.10/acre
         Materials                  $60.00/acre
         Equipment                  $ 5.00/acre
Previous experience at this facility has shown that this application
rate for fertilizer is satisfactory.
     14. Unit cost for mulching with straw:  Since the soil is bare, pro-
tection from erosion must be provided while the grass starts to grow.
This is achieved by using straw mulch at an application rate of 1 ton
per acre.  The unit cost of mulching is the sum of the labor, materials
and equipment costs.
         Labor                      $34.50/acre
         Materials                  $85.00/acre
         Equipment                  $ 5.00/acre              .
     15. Total unit replanting cost (Line 12 + Line 13 + Line 14):  The
total unit replanting cost is the sum of the seeding, fertilizing, and
mulching costs.  Lime is not applied at this facility because it is not
recommended by the Agricultural Extension Service (USDA).
     16. Total replanting costs (Line 3 x Line 15):  The total replanting
cost for the facility is the product of the acreage to be replanted and
the unit cost of replanting each acre.
                            I                  .
     17. Number of erosive incidents expected in the post-closure period:
It is anticipated that such highly erosive incidents will occur twice
during the post-closure period.  These will be either major storms or
floods.
                            I        •        •
     18. Total cost for repairing damage from erosive incidents (Line 11
4- Line 16 x Line 17) :— The total post-closure cost for repairing the damage
from such incidents is the sum of the repair costs for each incident
(soil and vegetation) multiplied by the number of incidents expected in
the 30-year post-closure period.      ,
     19. Total annual cost for repairs required by erosive incidents
(Line 18 -r 30 years):  The total cost of repairing the damage from the
                                    L
two incidents is divided by the 30 years of the post-closure period to
yield the annual cost for contingency repairs'.

                                   9-127

-------
                 ni
 D.    InitialReplanting  to  Establish Vegetation
       1.   Percentage failure of vegetation per year:   It is estimated
,I;F!!I , • ,  iisii,  i  ,|, , .1,1," ''I* iiiiiii"::1 |L iiiiiiii 'i ; 111 -'I11:	n.< ' 	; ,;  i,1?  , ป -• nfc. ', f "inn"? ' "i1 in!:',iii, ""'..i'liU'; i iiiiiiiiii^^^^         :. i,,"1* n	uiriiiiiii' uiw	wsniiii11 r. 'niiiJinpi	ป '•' „ •	J:
":[tha^',in, thi^^^cliia.te"^ 10 percent "of	the' vegetation	will	fail	per" year ""due
 ,,"to' inadequate initial establishment.
       2.   Number of years required for full vegetation:   I-t is estimated
',.   , i,].','  .!• in1 i,, i ^inmui' , ' 'Uiiini11::' <:!'iiiiiiiiini  iiซ  ••!• "!!!,!'*ซ., i1"	•',#  • i".' ,;• „!ป!:•, in    i  i    HI HI    mil i inn in    i i i  ||j nil i    i     - ,•':''
 that  three years will be necessary for full establishment of vegetation
 to  the point replanting  will no longer be necessary.
       3.   Facility acreage:  Facility acreage is 200 acres.
     	   „      	   	   lln  	in	;	n	I	
       4.   Total acres to  be  replanted due to initial failure  of vegetation
 (Line 1  x Line 2 x- Line  3):  Total acres to be replanted are then 60
     limn          inn in  mi in mi i                   i                i  in        || i i           '"
 acres.
       5.   Annual per acre soil  loss:  The annual soil  loss for each acre
                                                                 i
 of  bare  soil is computed using the Universal Soil Loss  Equation (USLE).
               A - RKLSCP
                                                                 I
           A * Average soil loss,  tons/acre
           R * Rainfall and run-off  erosivity index
           K ซ Soil erodibility  factor
        i."  L' ซ slope' _ length 'factor
                                                                ' \
           S  ป Slope - steepness factor
           G  ป Cover/management  factor (type of vegetative cover)
           P  • Practice factor (terracing, contour plowing)
 This equation is for erosion resulting from rainfall  subsequent  to the
 mveiit  that  removed the vegetation.
      6.   Monthly bare ground soil  loss rate:  The annual loss rate com-
 puted  in Step  4 is converted to  a  one-month loss rate.   This  conversion
     inn ii    i  mi n i in i mi  mi    nun  i  in i n   mi   i     i     i     i i    HIM  inn  i i  i n  11    ,	 'i.  ij|vi i t; ' < iji|iHn<<
 is  accomplished by dividing the  annual loss rate by 12.
       7.   Amount of soil  lost before repairs are instituted (Line 4 x
                	 '	•	'	•	j!	
 Line6):  Theamount of  soil lost  from the bared ground  is the product
 of  the monthly loss rate per acre  and the acreage of  the facilitythat
 is  exposed.   This  product is then multiplied by two to  allow  for soil
 lost during the removal of the vegetation.  The ground is  assumed to be
 bare for  about one month before  the repairs and replanting are completed.
 The conversion to volume of soil lost is carried out assuming a soil
                                                                 I
 density of  100 Ibs. per cu. ft.
                                     9-128
                                        ',,',,,  '       ,:!" ,  , ,!!' '! ,'" !,!! !!',!!' '   ' ,,!,,"' , jl
                                ,,, ,     ,„	    ' I ' „  '"  'nil,	' 	  	Ill' ii

                           '••i	;:':	::"	':~	:	:	•:"":	:	"":	••'	:	'	:•'•:	"	"""	-	:	:	::	: ••;	F;:

-------
     8.  Unit cost for excavating and loading soil:   The unit cost for
excavating and loading replacement soil is computed using a 2 cu. yd.
front end loader.  This operation will be performed under contract.
     9.  On-site haul of excavated soil to area needing repair:  The
excavated soil is transported on-site over a 2000 ft. distance by trucks
operating under contract.
    10.  Filling and compacting eroded areas of the facility:  The replace-
ment soil is filled and compacted into the eroded areas using a dozer
operating under contract.
    11.  Total unit cost for soil replacement (Line 8 + Line 9 + Line 10):
The total unit cost of soil replacement is the sum of the excavation-
loading, hauling and filling unit costs.  These unit costs were obtained
from estimates made by a Iqcal contractor.
    12.  Cost of soil replacement (Line 7 x Line 11):  The total cost for
replacing the lost soil is the product of the amount of soil lost times
the unit cost for soil replacement.
    13.  Unit cost for seeding bare soil:  The unit cost for seeding the
bare acreage is computed from the sum of the labor, materials and equip-
ment costs.
             Labor                  $69.10/acre
             Materials              $13.90/acre
             Equipment              $ 5.00/acre
The grass planted 'is Kentucky bluegrass available from a local supplier
at $0.32 per Ib. in 50-lb. bags.  The application rate for this seed is
1 Ib. per 1000 sq. ft. (or about 40 Ibs. per acre).  This is less than one-
third of the seed application rate used for home lawns.  Experience has
shown this seeding rate  to be satisfactory.
    14.  Unit cost for fertilizing:  Since the soil  at this hazardous
waste facility is quite  poor, fertilization is necessary.  Type 10/6/4
fertilizer costing $0.12 pซir Ib.  (in 50-lb. bags) is applied at a rate
of 500  Ibs. per acre.  This corresponds to a nitrogen application rate
of 50 Ibs. per acre.  The unit  cost of fertilizing is the sum of the
labor,  materials and  equipment  costs.
         Labor             !         $69.10/acre
         Materials         :         $60.00/acre

                                   9-129

-------
          Equipment                  $ 5.00/acre
 Previous experience at  this  facility has shown that this application
 ratefor fertilizer is  satisfactory.
      15. Unit  cost for  mulching with straw:   Since the soil is bare,
 protection  from erosion must be provided while the grass starts to grow.
 This is achieved by using straw mulch at an  application rate of 1 ton
 per acre.   The unit cost of  mulching is  the  sum of the labor, materials
 and equipment  costs.
          Labor                      $34.50/acre
          Materials                  $85.00/acre
          Equipment                  $ 5.00/acre
      16. Total unit replanting  cost  (Line 13 + Line 14 + Line 15):  The
 total unit  replanting cost is the sum of the seeding,  fertilizing, and
 mulching costs.  Lime is not applied at  this facility  because it is not
 recommended by the Agricultural Extension Service (USDA).
      17. Total replanting costs (Line 4  x Line 16)': The total replanting
 costs for the  entire 30-year period  are  then $20,796.
                                                               I!
      18. Total costs for initial replanting  to establish vegetation (Line
 12 + Line 17):   The total costs^ for  the  initial replanting to establish
 vegetation  are then $20,847.
      19. Total annual cost (Line 18  4- 30):   The total  cost for the initial
                                                               i1
 replanting  toestablish vegetation is divided by the 30 years of the post-
 closure period to  yield the  total annual cost,  for a total of $695.

 E.   Administrative Services  ,
    ซ  I.  Number of technical hours required  for administrative duties
 (annual):   Since the facility is closed,  all of the required administration
 is an extra cost that must be carefully  accounted for.   This facility esti-
 mates that  an  average of three  weeks of  labor by a manager is required to
 administer  the complete set  of  specified post-closure  activities.  This
 average administrative  requirement includes  the administration of the
 occasional  contingent events  described in Worksheet. C.
      2,  Person-hour cost for technical  administrative  duties:  The labor
 rate for facility  technical  labor is $30 per hour fully-loaded.
      3.  Total administrative costs  for  technical labor (Line 1 x Line 2):
II     i'7 , 1.1,1  ,	 S III ' lilii"'Ml!  ill ' . • •', ,'   , i"  •.   '" ' i, •''  ... •" ,i, '	,   ,; "'I1 " ป •'. . .„ ? Ail.' • ', lif'Si .iiE 'iii"i ' ',.•• In1!.,, II1 I"! '•' ill,' ' i' , ''I;1 .U""1

     	       •      •  •   9-130

-------
The total cost for administrative technical labor is the product of the
hours required and the labor rate.            ;
     4v  Number of clerical hours required for administrative duties:
Three weeks of clerical work is required to support the technical adminis-
trator.
     5.  Person-hour costs for clerical administrative duties:  The fully-
loaded labor rate for clerical labor at the facility is $8 per hour.
     6.  Total administrative costs for clerical labor (Line 4 x Line 5):
The total cost for administrative clerical labor is the product of the
hours required and the labor rate.
     7.  Office or trailer rental:  The total annual administrative cost
also includes the rental of office space during the busier times of each
post-closure year.  This includes typewriter,- telephone and supplies.
     8.  Total annual administrative costs for post-closure activities
(Line 3 + Line 6 + Line 7):  The  total cost of administration is the
sum.of the costs of technical labor, clerical labor, and office rental;

F.   Total Costs Including Administration and Contingencies
     Items 1  through 5 summarize  the total annual costs of the post-
closure functions taken from the  cost worksheets.  The erosion contingency
repair cost (Line 3) used is the  annual cost  of the two major erosion
events expected in the post-closure period (30 years).
     6.  Total of Lines 1 through 5:  The total costs of the activities
listed in Lines 1 through 5 are $40,206.
     7.  Contingencies:  Fifteen  percent of the sum of the above costs  is
taken  as an allowance for contingencies.  This contingency allowance .is
made in addition  to  the costs expected from the two major post-closure
erosion events.
     8'.  Administration:  An additional 10 percent of Line 6  is  included
for fees,  insurance  and related needs.
      9.  Total  annual costs of post-closure  (Line  6 + Line  7  + Line 8):
The total  sum of  the annual post-closure  costs  is  $50,258.
                                   9-131

-------
                                  POST-CLOSURE
                  WORKSHEET A - PERIODIC FACILITY INSPECTION
   1.   Number  of  technical management  person-hours
        required for each  routine  inspection of  the
        closed  facility
   2.   Annual  number of routine inspections
   3.   Person-hour costs  for  technical management labor
   4.   Technical  labor costs  for  annual routine inspections
        (Line 1 x  Line 2 x Line 3)
   5.   Annual  number of engineer-supported  inspections
   6,   Number  of  independent  state-certified engineering
      nil i   i   i in in n inil inn           i   n               ill
        hours for  each engineer-supported inspection
   7.   Number  of  technical management  hours for each
        engineer-supported inspection
   8.   Person-hour cost for a professional  engineer
   9.   Engineering labor  costs for the engineer-supported
        inspections (Line 5 x Line 6xLine8)
  10.   Technical  labor costsfor  theengineer-supported
,.	inspections (Line 3	x Line	5 x	Line  7)
  11.   Labor costs for the engineer-supported inspections
        (Line 9+ Line 10)
  12.   Truck rental cost for each inspection
  13,   Annual truck rental cost for inspections
        (Line 2 + Line 5 x Line 12)
  14.   Total ^mu^i inspection cost (Line 4 + Line 11 +
        Line 13)


Labor
16 hours
	 6 	
$30
$2880

2
8 hours
8 hours

$75 	
$1200

$480

$1680

$36
$288

$4848
                                     9-132
                                                              	ii	-
               ii I  i ill

-------
                               POST-CLOSURE
        WORKSHEET B - ROUTINE MONITORING AND MAINTENANCE ACTIVITIES
 Mowing Operations
 1.   Facility acreage       :
 2.   Mowing labor (per acre)
 3.   Mowing equipment (per acre)
 4.   Unit mowing cost (Line 2 •+ Line 3)
 5.   Annual frequency of mowing
 6.   Annual cost of mowing (Line 1 x Line 4 x Line 5)
 Routine Erosion Damage Repair
 7.   Annual routine erosion rate
 8.   Total annual routine erosive loss  (Line 1.x Line 7)
 9.   Unit cost for hand excavation of soil
10.   Unit cost for transporting of soil on-site.
11.   Unit cost for hand compacting soil (repairing
      erosive damage)
12.   Unit cost of seeding
13.   Aggregate unit cost of repairing routine soil
      erosion damage (Line 9 + Line 10 + Line 11 4- Line 12)
14.   Total annual cost for repairing erosive damage of
      a routine nature (Line 8 x Line 13)
15.   Adjustment factor to account for unusually wet seasons
16.   Annual cost for repairing routine erosive damage
      (Line 14 x Line 15)
 Fence Replacement
17.   Frequency of replacing fence

18.   Facility perimeter
19.   Unit cost of replacing fence
200 acres
$14.28
$5.37
$19.65
Once a year
$3930

0.12 tons
per acre
(.089 cu.
yds./acre)
17.8 cu. yds.
$21.21/cuป yd.
$2.13/cu. yd.
$21.21/cu. yd.

$l/cu. yd.
$45.55/cu.'yd.

$810.79
$1621.58
Once during
post-closure
period
11,808 ft.
$13.06/linear
ft. (installed)
                                    9-133

-------
WORKSHEET B  (continued)

20.  total cost  of  fencereplacement(Line 18 x Line 19)
21.  Pro-rated annual  cps,t qf  fence replacement
Fertilizing
22.  Unit cost for  fertilizing
23.  Number of fertilizerapplications for first 3'years
24.  Number of fertilizer  applications during remainder
     of post-closure (Years 4-30)
25.Total costs of fertilizing for first  3 years
     (Line 1 x Line 22 x Line  23)
26.  Total costs of fertilizing for post-closure
     years 4-30  (Line 1 x  Line 22 x Line 24)
27.  Total fertilizing costs (Line  25 + Line  26)
28.  Annual cost of facility fertilization (Line 27  4- 30)
Ground-water Monitoring Well Replacement
29.  Unit cost for  replacingwell
30.  Number of wells needing replacement during the
                                                               $154,212.48
                                                               $ ...... 5,140.41
                                                            ,' III,,,!!1;,,, !,„. j, "Bl, :•.,'' "!' ,;,, ."Hi .iff1 "','!.,' ,|i '" *'„ 'I1' HKiJIiHI1/
                                                               $134.10/acre
                                                                ..... ............ '3" ........... ' .......
                                                               $ 80,460

                                                               $134,100

                                                               $214,560
                                                               $  7,152

                                                               $425 /well
                                                               2
     post-closure period
31.	Total, cost	of^monitoring well replacement  during        '  $850
     the entire post-closure period  (Line  29 x  Line  30)
Leachate Pumping and Disposal
32.  Frequency of removing the Ieachates                       Once/month
33.  Average monthly total leachate withdrawal                 2000 gals.
                                                             i
34.  Unit cost of removing the leachate to an active           $0.18/gal.
     off-site TSDF
35.  Total annual cost of removing leachate                    $4320
     (Line 32 x Line 33 x Line 34 x 12)
36.  Unit cost for disposing of leachate off-site  (at          $.05/gal.
     a surface impoundment)
37.  Annual costs for disposing off-site (Line  32 x            $1200
     Line 33 x Line 36 x 12)
38.  Total annual costs for removing and disposing of          $5520
                                                             i
     Ieachates (Line 35 + Line 37)
                                   9-134

-------
WORKSHEET B (continued)

Ground-Water Monitoring
39.  Number of wells monitored                             12 wells
40.  Number of samples taken per well  (annual)             2 samples
41.  Total number of samples per well  (annual)             24 samples
     (Line 39 x Line 40)
42.  Number of hours for collecting the samples  (per       2 hours
     sample)
43.  Total number of hours for collecting samples          48 hours
     (Line 41 x Line 42)
44.  Total number of hours for preparing and delivering    6 hours
     samples
45.  Total sample handling hours (Line 43 + Line 44)       54 hours
46.  Person-hour costs for handling ground-water samples   $15
47.  Total sample handling costs (Line 45 x Line 46)       $810
48.  Unit cost of ground-water quality analysis            $77
49.  Unit' cost of ground-water contamination analysis      $108
50.  Total cost for ground-water quality analysis          $924
     (annual) (Line 39 x Line 48)
51.  Total cost for ground-water contamination analysis    $2592
     (annual) (Line 41 x Line 48)              :
52.  Total annual ground-water monitoring cost (Line 49    $4326
     + Line -50 + Line 51)
Routine Maintenance Summation
53.  Annual mowing cost (Line 6)                           $3930
54.  Annual cost for repairing routine erosive             $1621.58
     damage (Line 16)
55.  Annual cost for replacing fence (Line 21)             $5140.41
56.  Annual cost for fertilizing (Line 28)                 $7152
57.  Annual cost for replacing well (Line 21 4- 30)         $28
58.  Annual cost for removing leachates (Line 38)          $5520
59.  Annual cost for ground-water monitoring (Line 52)     $4326
60.  Total annual cost for routine activities              $27.717.99
                                   9-135

-------
                                                 ' ','L, ".!i,il|i|iiซi]" ปl|llilirill|ii!l .1:'  ill, illlllihr M.HIII i
                                                  ,|,|,|,	! I'!™!',1!''"!,,!!'"!,,"",''!'!'!''I!!'",",,!''
                        POST-CLOSURE
 III  nil ill i          ' i   i      i	   in  ซ  i ™    i   '  i    I
TOKSHEET C  - EROSION DAMAGE cONTINGENCt
ill  'I
1.
2.
3.
4.


5.





6.



7.


8.

9.

10.


11.
12.

13.
14.
IS.
16.

17.

18.

19.

Percentage of vegetation removed
Facility acreage
Acreage reduced to bare soil (Line 1 x Line 2)
Annual per acre soil loss rate (without
vegatative cover)

Monthly bare ground soil loss rate
ป i ,, ,,,ซ„,


, -, 	 ; 	 , 	 - , , , 	 	 	 i 	
111 i i i i HUM i i in i ,,,i, ^ ,, , 	 , ,,; i 	 u, „ i1 , v „ , ' ,,'',,,, " i , 	 j1 ,,,,:! v ,1,1, 	 ;, n ,;,,|ii' ii iiiiiiiiiii' i,,,,in ,; ,,
Amount of soil lost before repairs are instituted
(Line 3 x Line 5 x 2) (The factor of 2 adjusts for
,,,, ,,,, 	 ,, , 	 „ 	 , , 	 	 , 	 ', 	
immediate soil losses)
Unit cost: for excavating and loading soil (on-site

operations using a 2-cu. yd. front end loader)
On-site haul of excavated soil to area needing
repair
Filling and compacting the eroded areas (using
a dozer) '/ , "_ 	 , ."'" " _ , ' " "_ 	 ' _
Total unit cost for soil replacement
" i (Line 7 + Line 8 + Line 9)
' II III * 1 1 1 	 1 	 , , , , • , 	 .J. 1 	 . •• ;
Cost of replacing lost soil (Line 6 x Line 10)
Unit cost for seeding the bare soil
II ' 	 '•!•' 	 "'"'1 	 1!1 1" 	 "' 	 	 "I' ป '' ' • 	 ' "'• 	 1'* ' 	 '''ป "' 	 	 	
Unit cost for fertilizing
Unit cost for mulching with straw
Total unit replanting cost (Line 12 + Line 13 + Line
Total replanting cost (Line 3 x Line 15)

Number of erosive incidents expected in the post-
closure period
Total cost for repairing damage from erosive
incidents (Line 11 + Line 16 x Line 17
Total annual cost for repairs required by erosive
lii incidents "(Line1 18 4 30)
30%
i •
200 acres
; 	 II 	 " 	 '" 	
60 acres
' | 't 	 ' , ,; 	 •. , 	
12 tons
per acre
! '' ,
1 ton per

	 I acre1 	 : 	
(.741 cu.
. yds. /acre)
u.ji.,1 ' Hi ' i, ' ' , ' > •. .;,,i,l,|i.lii "'i1 • " .. ." '" ,!L"!!ป i'1' !! 'U!*1'1 ,!!!ป!:' .ป
120 tons
(89 cu. yds.)
, j| , 	 ,;„, „, , 	 	
II

' ' "
cu. yd.
$0.85 per ^j
cu . yd .
$1.25 per
,, 	 ii,,-,, 	 , ' ' „, 	 ,„„, 	
cu. yd.
. "| ^ $2.31 per _ ' t ^ ^ ' '
cu. yd.
lil:" "' "I1 ; '|I'!!'IJ ' 'l!- "" 	 ' "• 	 	 	
$205.59
$88/acre
'I'""!,!' ' 'ij! 	 .'"| 	 '''""' 	 1 '• " 'lll! 	 	 	 • '. 	 II ' 'I'1
" '"'I::"$i34/acre
$124.50/acre
14) $346.50/acre
$20,790
li
2
' 1!
j
$41,580

$1386 m
: ,, ,.. :„, . : ^
                             9-136

-------
                                POST-CLOSURE
         WORKSHEET D - INITUiL REPLANTING TO ESTABLISH VEGETATION
 1.   Percentage failure of vegetation per year
 2.   Number of years required, for full vegetation
 3.   Facility acreage
 4.   Total.acres to be replanted due to initial
      failure of vegetation (Line 1 x Line 2 x Line 3)
 5.   Annual per acre soil loss rate (for areas with
      inadequate vegetative cover)
 6.   Monthly bare ground soil loss rate

 7.   Amount of soil lost before repairs are
      instituted (Line 4 x Line 6)                  -
 8.   Unit cost for soil excavation and loading
      (on-site operations using a 2-cu. yd. front end loader)
 9.   On-site haul of excavated soil to area needing
      repair
10.   Filling and compacting eroded areas (using a
      dozer)
11.   Total unit cost for soil replacement
      (Line 8 + Line 9 + Line 10)
12.   Cost of soil replacement (Line 7 x Line 11)
13.   Unit cost for seeding bare soil
14.   Unit cost for fertilizing
15.   Unit cost for mulching with straw
16.   Total unit replanting cost (Line 13 H- Line 14! + Line 15)
17.   Total replanting costs (Line 4 x Line 16)
18.   Total costs for initial replanting to establish
      vegetation (Line 12 + Line 17)
19.   Total annual cost (Line 18 T 30)
10 percent
3
200 acres
60

6 tons/acre

.5 tons
(.37p6;cu.
yd./acre)
30 tons
(22 cu. yds.)
$6.21 per
cu. yd.
$0.85 per
cu. yd.
$1.25 per
cu. yd.
$2.31 per
cu. yd.
$50.82       '
$88/acre
$134.10/acre
$124.50/acre
$346.60/acre
$20,796
$20,847

$695
                                    9-137

-------
                                 POST-CLOSURE
                   i'	w	MI	•	ป&	if i	;rv. •	! ; ;>f vf	::i	F	, i tf ;* if..	WK,	8 v ,*ii!!	ill .:.ซ:
                   WORKSHEET E - ADMINISTRATIVE SERVICES
                                                                         Vila \.C ii!	• 1 J
                                                                         i    '''
1.

2.
3.

4.

5.
6.

7.

8.
 Number" of ""technical hours'" required"'for 'administrative''  . '120  hours
 duties (annual)
 Person-hour cost for technical administrative  duties      $30
 Total administrative costs for technical labor            $3600
 ""(Line 1 x Line  2)	    '   .  .. . '     	'	 '  		
                 1 .1 I! ''' ,;, <   	, I'lilllll i	, l,ซl " Jif" Jii,	|ji . „ Jl ' IJ	 ,! I > , 	„ , III! il, 	
 Number of clerical hours required for "a&"l5is tratlve      12"0  hours
  duties'"
|l|   I || 111 | ll  || 111| 11    ,      | |l|  ,i|l. /..  .1, ,,1 ,n,'  , ,„ '"in"	 ,Jซi llihillN " ll 11'"i,"', I ,, I"! II* Hill ,.|i'IU,i .1!,'	Ov, 'i	llfilllmiJ'!1'"* S ,lป,". ป' frW	 i ".ll'i'ii"1! ,'""'. '|ir Hr'li  ' 'Ifl!
  Person-hour costs for clerical  administrative duties     $8
  Total administrative costs for  clerical labor            $960
••• (Line "4	x "Line 5)   	       "    "       	'	
  Office or trailer rental  (includes equipment  and         $1000
  supplies)
  Total annual  administrative  costs for  the post-closure   $5560
  activities (Line 3 + Line 6  + Line 7)
                                                              ""	'ii"
                                      9-138

-------
                                POST-CLOSURE
                   WORKSHEET F - TOTAL COSTS INCLUDING
                     ADMINISTRATION AND CONTINGENCIES
1.   Cost of inspections  (From Worksheet A)                     $  4,848
2.   Cost of routine monitoring and maintenance                 $27,718
     (From Worksheet B)
3.   Cost of contingency  erosion repairs (From Worksheet C)     $  1,386
4.   Cost of initial replanting to establish vegetation         $    695
     (From Worksheet D)
5.   Cost of post-closure administrative services               $  5,560
     (From Worksheet E)
6.   Total of Line 1 through  Line 5                         .    $40,207
7.   Contingencies                                               $  6,031
8.   Administration, including fees, insurance, etc.            $  4,021
9.   Total annual costs of post-closure                         $50,259
     (Line 6 + Line 7 + Line  8)
                                                               va 1990
                                                               SW-913
                                   9—139     *U.S. GOVERNMENT PRINTING OFFICE:  1981  345-932/8290 1-3

-------
I  mi"',11,	  ,:  '   /"SI':    .iijllil1"!!!"1!1",1,,:1!1,  ป'•'        IP   ,

-------

-------
I	

-------

-------

-------

-------

                            I* 1 ".!'  '-	   i"  ,;:J|f   ซ:
                            iik:  "!"  .V  .  i.tf  '-"JUt   ::'*
                                                )
-------