vyEPA
          United States
          Environmental Protection
          Agency
             Research and
             Development
             (RD681)
EPA/540/AR-92/017
August 1992
Babcock & Wilcox
Cyclone Furnace Vitrification
Technology

Applications Analysis Report
                SUPERFUND INNOVATIVE
                TECHNOLOGY EVALUATION

-------

-------
                                               EPA/540/AR-92/017
                                               August 1992
Babcock & Wilcox Cyclone Furnace
       Vitrification Technology

       Applications Analysis Report
     Risk Reduction Engineering Laboratory
      Office of Research and Development
     U.S. Environmental Protection Agency
            Cincinnati, Ohio 45268
                                       Printed on Recycled Paper

-------
                                                Notice
The information in this document has been funded by the U.S. Environmental Protection Agency (EPA) under the
auspices of the Superfund Innovative Technology Evaluation (SITE) Program under Contract No. 68-CO-0048 to Science
Applications International Corporation (SAIC). It has been subjected to the Agency's peer and administrative review,
and it has been approved for publication as an EPA document.  Mention of trade names or commercial products does
not constitute an .endorsement or recommendation for use.                            :

-------
                                              Foreword
The Superfund Innovative Technology Evaluation (SITE) Program was authorized in the 1986 Superfund Amendments.
The Program is a joint effort between EPA's Office of Research and Development and Office of Solid Waste and Emergency
Response. The purpose of the program is to enhance the development of hazardous waste treatment technologies necessary
for implementing new cleanup standards that require greater reliance on permanent remedies. This is accomplished by
performing technology demonstrations designed to provide engineering and economic data on selected technologies.

This project consists of an analysis of the Babcock & Wilcox (B&W) Cyclone Furnace Vitrification Technology. The
Demonstration Test took place at the B abcock & Wilcox Research and Development pilot facility located in Alliance, Ohio.
The goals of the study, summarized in this Applications Analysis Report, are: 1) to evaluate the technical effectiveness and
economics of this technology relative to its ability to treat soils contaminated with heavy metals, radionuclides, and
organics; and 2) to establish the potential applicability of the process to other wastes and Superfund sites.  The primary
technical objective of this project is to determine the ability of the process to produce a non-leachable vitrified material that
immobilizes heavy metals and radionuclides. The process is also being evaluated for its ability to destroy any organic
contaminants present in the Synthetic Soil Matrix (SSM).

Additional copies of this report may be obtained at no charge from the EPA's Center for Environmental Research
Information, 26 West Martin Luther King Drive, Cincinnati, Ohio  45268, using the EPA document number found on the
report's front cover.  Once this supply is exhausted, copies can be purchased from the National Technical Information
Service, Ravensworth Building, Springfield, Virginia, 22161 (703) 487-4650.  Reference copies will be available in the
Hazardous Waste Collection at EPA libraries.
                                                       E. Timothy Oppelt, Director
                                                       Risk Reduction Engineering Laboratory
                                                    111

-------
                                                 Abstract
This document is an evaluation of the performance of the Babcock & Wilcox (B&W) Cyclone Furnace Vitrification
Technology and its applicability as a treatment technique for soils contaminated with heavy metals, radionuclides, and
organics.  Both the technical and economic aspects of the technology were examined.

A demonstration of the B&W vitrification technology was conducted in the fall of 1991 using B&W's pilot-scale unit
located at its Alliance Research Center in Alliance, Ohio.  Operational data and sampling and analysis information were
carefully compiled to establish a database against which other available data, as well as the vendor's claims for the
technology, could be compared and evaluated. Conclusions concerning the technology's suitability for use in immobilizing
metal and radionuclides in soils as well as destroying organic contaminants were reached.  Extrapolations regarding
applications to different contaminants and soil types were made.

The following conclusions were derived primarily from the Demonstration Test results and supported by other available
data:  (1)  the treated soil did not leach any metals at levels above the regulatory limits; (2) the process achieved a
Destruction and Removal  Efficiency (DRE) of greater than 99.99 percent  for each Principal Organic Hazardous
Constituent (POHC); (3) particulate emissions were below the regulatory limit;  (4) the non-volatile metals were retained
in the slag; and (5) simulated radionuclides were immobilized.
                                                      IV

-------
                                                 Contents
Section

Notice	       ii
Foreword	       iii
Abstract	       iv
Contents  	       v
Tables	      viii
Figure  	       x
Abbreviations	       xi
Acknowledgments	      xiii

1. Executive Summary	       1

   1.1 Introduction 	       1
   1.2  Conclusions	       1
   1.3  Results	       1

2. Introduction  	       3

   2.1  The SITE Program	       3
   2.2  SITE Program Reports	       3
   2.3  Key Contacts  	       4

3. Technology Applications Analysis	       5

   3.1  Introduction	       5
   3.2  Conclusions	       5
   3.3  Technology Evaluation	       5
        3.3.1   Slag Characteristics	       6
        3.3.2   Metals Partitioning  	       7
        3.3.3   Air Emissions	       8
        3.3.4 .  Quench Water	       9
   3.4  Ranges of Site Characteristics Suitable for the Technology	       10
        3.4.1   Site Selection	       10
        3.4.2   Surface, Subsurface,  and Clearance Requirements	       10
        3.4.3   Topographical Characteristics	       10
        3.4.4   Site Area Requirements	       10
        3.4.5   Climate Characteristics  	       10
        3.4.6   Geological Characteristics	       10
        3.4.7   Utility Requirements	       10
        3.4.8   Size of Operation	 .       11
   3.5  Applicable Media	       11
   3.6  Regulatory Requirements	       11
        3.6.1   Federal EPA Regulations  	       12
        3.6.2   State and Local Regulations	       14

-------
                                       Contents (Continued)
    3.7   Personnel Issues	14
          3.7.1  Training	14
          3.7.2  Health and Safety	14
          3.7.3  Emergency Response	14
    3.8   References	;	14

4.  Economic Analysis	15

    4.1   Introduction	15
    4.2   Conclusions	15
    4.3   Issues and Assumptions	15
          4.3.1  Costs Excluded from Estimate	15
          4.3.2  Maximizing Treatment Rate	16
          4.3.3  Utilities	......	16
          4.3.4  Operating Times	16
          4.3.5  Labor Requirements	16
          4.3.6  Capital Costs	16
          4.3.7  Equipment and Fixed Costs	16
    4.4   Basis of Economic Analysis	16
          4.4.1  Site Preparation Costs	17
          4.4.2  Permitting and Regulatory Costs	17
          4.4.3  Equipment Costs	17
          4.4.4  Startup and Fixed Costs	18
          4.4.5  Labor Costs	18
          4.4.6  Supplies Costs	19
          4.4.7  Consumables Costs	19
          4.4.8  Effluent Treatment and Disposal Costs	19
          4.4.9  Residuals and Waste Shipping, Handling, and Transport Costs	19
          4.4.10 Analytical Costs	19
          4.4.11 Facility Modification, Repair, and Replacement Costs	19
          4.4.12 Site Demobilization Costs	,	20
    4.5   Results of Economic Analysis	20
    4.6   References	22

Appendix A-Process Description	23

    A.I   Introduction	23
    A.2   The Cyclone Furnace	23

Appendix B - Vendor's Claims	25

    B.I   Site Demonstration Vendor's Claims	25
    B.2   Comparison of Performance Results from the Two SITE Emerging Technologies Projects
          with the Vendor's Claims	25
          B.2.1  Synthetic Soil Matrix and Feed Conditions	25
          B.2.2 Performance Results	26
    B.3   Comparison of Performance Results from the SITE Demonstration with the Vendor's Claims	26
          B.3.1  Synthetic Soil Matrix and Feed Conditions	26
          B.3.2 Performance Results	26
    B.4   Summary	27
    B.5   Reference	27
                                                      VI

-------
                                       Contents (Continued)
Appendix C - SITE Demonstration Results	28

    C.I  Introduction	28
    C.2  Slag Characteristics	28
         C.2.1 Leachability	28
         C.2.2 Volume Reduction	29
    C.3  Metals Partitioning....	30
    C.4  Air Emissions	31
         C.4.1 Particulate	31
         C.4.2 DRE	31
         0.4.3 PICs	!	31
         0.4.4 CEMs	32
    C.5  Quench Water	32

Appendix D - Case Studies	33

    D.I  Municipal Solid Waste, (MSW) Ash Testing	33
    D.2  Emerging Technologies Testing	33
         D.2.1 Introduction	33
         D.2.2 Phase I	33
         D.2.3 Phase II	34
                                                    VII

-------
                                                Tables
Number                                                                                            Page

 1     B&W SITE Demonstration Test Results and Potential Incineration ARARs  	        2

 2     Total Concentrations of Spiked Components Measured in the SSM	        6

 3     Total Concentrations of Spiked Components Measured in the Slag	        6

 4     TCLP Results	        7

 5     Metals Partitioning from the Cyclone Vitrification Process 	        8

 6     Summary of Particulate Emissions	        8

 7     Excavation Costs	       17

 8     Treatment Costs for 3.3 tph Cyclone Furnace Vitrification System
       Treating 20,000 Tons of Contaminated Soil	       20

 9     Treatment Costs as Percentages of Total Costs for 3.3 tph Cyclone Furnace
       Treating 20,000 Tons of Contaminated Soil	       20

10     Treatment Costs for 3.3 tph Cyclone Furnace Vitrification System
       Operating with a 60% Online Factor  	       21

11     Treatment Costs as %  of Total Costs for 3.3 tph Cyclone Furnace Vitrification
       System Operating with a 60% Online Factor	       22

12     Treatment Costs for the Remediation of 100,000 Tons of Contaminated Soil Using
       Cyclone Furnace Vitrification System Operating with a 60% Online Factor	       22

13     Treatment Costs as Percentages of Total Costs for Cyclone Furnaces
       Treating 100,000 Tons of Contaminated Soil	       22

B-l    B&W Claims for Cyclone Vitrification Technology	       25

B-2    Phase I & Phase n Performance vs. Vendor Claims	       26

B-3    SITE Demonstration Performance vs. Vendor Claims	       26

C-l    Averages TCLP  Results from B&W SITE  Demonstration Runs 	       29

C-2    Percent of Leachable Metals from B&W Cyclone Furnace 	       29
                                                   vm

-------
                                      Tables (Continued)
C-3   Leachability  Index of Simulated  Radionuclides    	




C-4   Volume Reduction 	




C-5   Summary  of Metals Emissions   	




C-6   DREs   	




C-7   Summary  of Volatile  Organic Concentrations in Stack Gas from B&W SITE Demonstration




C-8   Summary  of NOX, CO, and THC CEM Data	




C-9   Summary  of CO2 and O2 CEM Data  	




C-10  Quench Water from B&W SITE Demonstration  	




D-l   Total Metals in Soil,  Slag,  and Multiple  Metals Train Particulates  	
29




30




30




31




31




32




32




32




34
                                                 IX

-------
                                            Figure
Number




 A-l  Cyclone Test Facility	      23

-------
                                           Abbreviations
AAR      Applications Analysis Report

ANS       American Nuclear Society

ARAR     Applicable or  Relevant  and Appropriate
           Requirements

ASTM     American Society for Testing and Materials

B&W      Babcock and Wilcox

CAA      Clean Air Act

CEM      Continuous Emission Monitor

CERCLA  Comprehensive  Environmental  Response,
           Compensation, and Liability Act

CO        Carbon Monoxide

CO2       Carbon Dioxide

CPR       Cardiopulmonary Resuscitation

CWA      Clean Water Act

DOD      U.S. Department of Defense

DOE      U.S. Department of Energy

DRE      Destruction and Removal Efficiency

EPA       Environmental Protection Agency

gr/dscf     grains per dry standard cubic foot

gpm       gallons per minute

MSW      Municipal Solid Waste

NPDES    National Pollutant Discharge Elimination
           System
NOX        Nitrogen Oxides

O2         Oxygen

ORD       Office of Research and Development

OSHA      Occupational Safety and Health Act

OSWER    Office  of  Solid  Waste  and  Emergency
            Response

PIC        Products of Incomplete Combustion

POHC      Principal Organic Hazardous Constituent

ppm        parts per million

POTW      Publicly-Owned Treatment Works

psig        pounds per square inch gauge

RCRA      Resource Conservation and Recovery Act

RREL      Risk Reduction Engineering Laboratory

SARA      Superfund Amendments & Reauthorization
            Act

scf         standard cubic feet

scfm        standard cubic feet per minute

SDWA      Safe Drinking Water Act

SITE       Superfund Innovative Technology Evaluation

SSM        Synthetic Soil Matrix

SVOC      Semi-Volatile Organic Compounds

TCLP       Toxicity Characteristic Leaching Procedure
                                                   XI

-------
                                Abbreviations (Continued)
TER      Technology Evaluation  Report




THC      Total Hydrocarbons




tph       tons per hour




tpd       tons per day




TSD      Treatment,  Storage,  and Disposal




VOC      Volatile Organic Compounds




VOST     Volatile Organic Sampling  Train
                                               xu

-------
                                         Acknowledgments
This report was  prepared under the direction and coordination of Ms. Laurel Staley, EPA Superfund Innovative
Technology Evaluation (SITE) Program Manager in the Risk Reduction Engineering Laboratory (RREL), Cincinnati,
Ohio.  EPA-RREL contributors and reviewers for this report were Robert Stenburg, Randy Parker, and Kim Lisa
Kreiton.  Babcock and Wilcox contributors and reviewers were Jean Czuczwa, Dan Rowley, Hamid Farzan, William
Musiol, James Warchol, and Stanley Vecci.

This report was prepared for EPA's SITE Program by the Technology Evaluation Division of Science Applications
International Corporation (SAIC) in Cincinnati, Ohio for the U.S. EPA under Contract No. 68-CO-0048.  The Work
Assignment Manager for this project was Ms. Margaret M. Groeber.
                                                  xui

-------

-------
                                                Section 1
                                         Executive Summary
1.1     Introduction
This report summarizes the findings of an evaluation of
the Cyclone Furnace Vitrification Technology developed
by Babcock & Wilcox (B&W). The study was conducted
under the  Superfund Innovative Technology Evaluation
(SITE) Program. A Demonstration Test of the technology
was performed by U.S. Environmental Protection Agency
(EPA) as part of this program.  The results of this test
and supporting  data  from other testing performed by
B&W constitute the basis for this report.
1.2     Conclusions

A  number  of conclusions may be drawn from the
evaluation  of this  innovative  technology.   The  most
extensive data were  obtained during the SITE  Demon-
stration Test. Data from other testing activities have been
evaluated in relation to SITE Program objectives.  The
conclusions drawn are:

•       The  slag  produced   complied  with  Toxicity
        Characteristic  Leaching  Procedure  (TCLP)
        regulatory requirements for cadmium, chromium,
        and lead.

•       Ninety-four  percent  of the  non-combustible
        portion of the soil was incorporated within the
        slag.

•       Most of the non-volatile metals remained in the
        slag.   On  the  average,  the  percentages for
        chromium, strontium, and zirconium retained in
        the slag were 76, 88, and 97 percent, respectively.
        Metals which  partitioned to the flue gas  were
        captured by the baghouse.

•       A volume reduction of  29 percent from  the feed
        Synthetic Soil Matrix  (SSM)  to the slag was
        achieved on a dry weight basis.
         Destruction and Removal Efficiencies (DREs)
         for each  Principal Organic Hazardous Consti-
         tuent (POHC) were greater than 99.99 percent.

         An average of 0.001 grains per dry standard cubic
         foot  (gr/dscf) of  particulate (corrected to 7
         percent O2) was emitted,  which  is less than the
         Resources  Conservation   and  Recovery  Act
         (RCRA)  regulatory limit of 0.08 gr/dscf  at 7
         percent O2.

         The simulated radionuclides were immobilized
         within the slag according  to American Nuclear
         Society Method  16.1.

         The  process  formed  products  of incomplete
         combustion; however, concentrations were in the
         parts per trillion range.

         The  cost  to   remediate  20,000   tons  of
         contaminated  soil  using  a 3.3-ton  per hour
         cyclone furnace vitrification system is estimated
         at $465 per ton if the system is online 80 percent
         of the time or $529 per  ton if the system is online
         60 percent of the time.
1.3    Results

The objectives of this Applications Analysis are to assess
the ability of the process  to comply with Applicable or
Relevant and Appropriate Requirements (ARARs) and to
estimate the cost of using this technology to remediate a
Superfund site.  This analysis includes determining if the
cyclone furnace can produce  a non-leachable  vitrified
material that immobilizes a significant percentage of the
metals,  particularly  chromium.    It   also   includes
determining DREs and air emissions from the  process.
Table  1 lists  the unit's performance as  it  relates  to
ARARs.

-------
Table I.  B&W SITE Demonstration Test Results and Potential Incineration ARARs

  Contaminant                                   Average                 Range
                                    ARARs
TCLP frng/L)
SSM
Cadmium
Chromium
Lead
Sag
Cadmium
Chromium
Lead
ORE (%)
Anthracene
Dimethylphthalatc
Slack Emissions
Particulatc matter
Nitrogen oxides (NO,, ppm)
Carbon monoxide (ppm)
Total hydrocarbons (ppm)
Cadmium (Ib/hr)
Chromium (Ib/hr)
Lead 0b/hr)


49.9
2.64
97.3

0.12
0.22
0.31

> 99.997
> 99.998

0.0008
a
a
a
3.27X10'6
2.70xlO'5
1.88xlO's


31.0 - 75.3
1.30 - 4.32
72.2 - 128

0.03 - 0.30
0.07 - 0.81
<0.25 - 0.66

> 99.996 -> 99.997
> 99.998 - > 99.998

0.003 - 0.0014
310 - 435
4.8 - >54.1
<5.9 - 18.2
9.4xlO'6 - 1.5xlO'4
2.1X10'5 - 1.9xlO'4
4.8xlO's - 7-lxlO"4


1.0
5.0
5.0

1.0
5.0
5.0

99.99
99.99

0.08
b
<100
<20
c
c
' c
 a        Average concentration for each run is presented in Appendix C. Average concentration for the entire Demonstration was not calculated.

 b        Allowable emissions limits established on a case-by-case basis as per the requirements of the Clean Air Act.

 C        Less than those established by EPA Guidance on Metal Emissions from Hazardous Waste Incinerators.
 Other results regarding the ratio of slag-to-flyash, metal
 partitioning, volume reduction, and characterization of
 feed soil and baghouse solids are also addressed.
A full discussion of the SITE Demonstration Test results
is  included   in  Appendix  C  and  supported   in
Appendix D, Case Studies.

-------
                                                Section!
                                             Introduction
2.1    The SITE Program

In 1986, the U.S. Environmental Protection Agency (EPA)
Office  of  Solid  Waste  and  Emergency  Response
(OSWER) and  Office of  Research and  Development
(ORD) established the Superfund Innovative Technology
Evaluation (SITE) Program to promote the development
and use of innovative technologies to clean up Superfund
sites across  the country.  Now in its fifth  year,  SITE is
helping to provide the treatment technologies necessary to
implement new Federal and State cleanup standards aimed
at permanent remedies rather than quick fixes.  The SITE
Program is composed of three major elements:  the Dem-
onstration Program, the Emerging Technologies Program,
and the Measurement   and Monitoring  Technologies
Program.

The major focus has been on the Demonstration Program,
which is designed to provide engineering and cost data for
selected  technologies.    To  date,  the Demonstration
Program projects have not involved funding for technology
developers.  EPA and  developers participating in  the
program share the cost of the demonstration. Developers
are responsible for demonstrating then- innovative systems
at chosen sites,  usually Superfund sites.   The  EPA is
responsible for sampling, analyzing, and evaluating all test
results. The result is an assessment of the technology's
performance, reliability,  and costs.   This information is
used hi conjunction with other  data  to select the most
appropriate  technologies  for the cleanup  of Superfund
sites.

Developers  of innovative  technologies apply  to  the
Demonstration Program by responding  to EPA's annual
solicitation.  EPA also  accepts  proposals any time a
developer  has  a Superfund waste  treatment  project
scheduled. To qualify for the program, a new technology
must be at the pilot- or full- scale and offer some advan-
tage over existing technologies. Mobile technologies  are
of particular interest to EPA.
Once  EPA has  accepted a  proposal, EPA and  the
developer work with the EPA regional offices and state
agencies to identify a site containing waste suitable for
testing the capabilities of the technology.  EPA prepares
a detailed sampling and analysis plan designed to evaluate
the technology thoroughly and to ensure that the resulting
data are reliable.  The duration of a demonstration varies
from a few days to several months, depending  on  the
length of time and quantity of waste needed to assess the
technology.  After  the  completion of  a  technology
demonstration,  EPA prepares two  reports, which  are
explained in more  detail in  the following paragraphs.
Ultimately,  the  Demonstration  Program  leads  to  an
analysis  of the  technology's overall  applicability  to
Superfund problems.

The second principal element of the SITE Program is the
Emerging Technologies Program, which fosters the further
investigation and development of treatment technologies
that are still at the laboratory scale. Successful validation
of these technologies could lead to the development of a
system ready for field demonstration and participation in
the Demonstration Program.  The third component of the
SITE  Program,  the  Measurement  and Monitoring
Technologies  Program,  provides  assistance in  the
development and demonstration of innovative technologies
to characterize Superfund sites better.
2.2     SITE Program Reports

The   analysis   of  technologies   participating  in  the
Demonstration Program is contained in two documents:
the  Technology Evaluation  Report  (TER)  and  the
Applications Analysis Report (AAR). The TER contains
a  comprehensive  description  of  the  demonstration
sponsored by the SITE program and its results.  It gives
detailed descriptions of the technology, the waste used for
the demonstration,  sampling and analysis during the test,
the data generated, and the quality assurance program.

-------
The scope of the AAR is broader than the TER  and
encompasses estimation of the Superfund applications and
costs of a technology based on all available data.  This
report compiles and summarizes the results of the SITE
demonstration, the vendor's  design and  test data,  and
other laboratory and field applications of the technology.
It discusses the advantages, disadvantages, and limitations
of the technology.

Costs of the  technology for different applications are
estimated based on available data on pilot- and full-scale
applications.  The AAR discusses the factors, such as site
and waste  characteristics,  that have a major impact on
costs and performance.

The amount of available data for the evaluation of an
innovative technology varies widely. Data may be limited
to laboratory tests  on synthetic  waste or  may  include
performance data on actual wastes treated at the pilot- or
full-scale level. In addition, there are limits to conclusions
regarding Superfund applications that can be drawn from
a single field demonstration.  A successful field demon-
stration does not necessarily ensure that a technology will
be widely applicable or fully developed to the commercial
scale. The AAR attempts to synthesize whatever inform-
ation is available and  draw reasonable conclusions.  This
document is very useful to those considering a technology
for Superfund cleanups and represents a critical step in the
development  and commercialization  of the treatment
technology.
2.3     Key Contacts

For more information on the demonstration of the B&W
technology, please contact:

1.      EPA  Project   Manager   for   the   SITE
        Demonstration Test:

        Ms. Laurel Staley
        U.S. Environmental Protection Agency
        Risk Reduction Engineering Laboratory
        26 W. Martin Luther King Drive
        Cincinnati, Ohio  45268
        (513) 569-7863

2.      Process Vendor :

        Mr. Lawrence P. King
        Research and Development Division
        Babcock & Wilcox
        1562 Beeson Street
        Alliance, Ohio  44601
        (216) 829-7576

-------
                                                Section 3
                                Technology Applications Analysis
3.1     Introduction

This section addresses the applicability of the Babcock &
Wilcox (B&W) Cyclone Furnace Vitrification Technology
to various contaminated soil matrices where heavy metals,
radionuclides, and various organics  are the pollutants of
primary  interest.  Recommendations are based on  the
results obtained from the SITE demonstration as well as
additional data from B&W. The results of the demonstra-
tion provide the most extensive database, conclusions on
the technology's effectiveness, and its applicability to other
potential cleanups. Additional information on the B&W
technology, including a brief process "description, vendor's
claims, and a summary of the demonstration results are
provided in Appendices A through C.
3.2     Conclusions

Soil contaminants  are  either immobilized, thermally
destroyed (oxidized), or volatilized in B&W's cyclone
furnace.  It successfully produced a non-leachable, vitrified
slag that immobilized heavy metals and radionuclides. The
technology  also  destroyed  the organic  contaminants
present in the soil.

A  review  of the  Demonstration  Test indicates  the
following results:

•        The slag  produced  complied  with  Toxicity
         Characteristic  Leaching  Procedure   (TCLP)
         regulatory requirements for cadmium, chromium,
         and lead.

•        Ninety-four percent  of the  non-combustible
         portion of  the soil was incorporated within the
         slag.

•        Most of the non-volatile metals remained in the
         slag.   On  the  average, the  percentages  for
         chromium,  strontium, and zirconium retained in
         the slag were 76, 88, and 97 percent, respectively.
         Metals which partitioned to the flue gas were
         captured by the baghouse.

         The volume of slag produced was 29 percent
         smaller than the feed soil on a dry weight basis.

         Destruction and Removal  Efficiencies (DREs)
         for Semi-Volatile Organic Compounds (SVOCs)
         were greater than 99.99 percent.

         An average of 0.001 grains per dry standard cubic
         foot (gr/dscf)  of  particulate  corrected to  7
         percent O2 was emitted,  which is less than the
         Resource  Conservation   and   Recovery  Act
         (RCRA) regulatory limit of 0.08  gr/dscf at 7
         percent O2.

         The   simulated    radionuclides  (strontium,
         zirconium, and bismuth) were immobilized within
         the slag according to American Nuclear Society
         (ANS) Method 16.1.

         The process formed  products  of incomplete
         combustion; however, concentrations were in the
         parts per trillion range.
3.3    Technology Evaluation

The 6-million Btu/hr  pilot-scale furnace used  in  this
demonstration is a scaled-down  version of the B&W
commercial coal combustion cyclone furnace. This unit
employs  high temperatures  to vitrify  high inorganic
hazardous wastes (e.g., soils) that may also contain organic
constituents.  The technology was demonstrated using a
Synthetic Soil Matrix (SSM) provided by the EPA Risk
Reduction Engineering Laboratory  (RREL) in  Edison,
New Jersey.  The contaminants used to spike the SSM
were  chosen in order  to produce  a feed with con-
tamination problems  similar to those  encountered  at

-------
Supcrfund sites, Department of Defense (DOD) facilities,
and Department of Energy (DOE) facilities. The SSM is
a well characterized, clean material used for technology
evaluations  which has been spiked  with heavy  metals,
SVOCs, and simulated radionuclides [1].

Simulated radionuclides are non-radioactive metals, the
behavior of which in the cyclone furnace will simulate true
radionuclidc species. The simulated radionuclides selected
were strontium, bismuth,  and zirconium.  Bismuth was
used as a surrogate for volatile  radionuclides found  at
DOE/DOD sites such as cesium (cold cesium was origin-
ally proposed but found to be excessively expensive). Cold
strontium was used  as  a surrogate  for radioactive
strontium (the cold version of the radionuclide is the best
possible  surrogate).   Zirconium was  considered  an
excellent surrogate for radioactive thorium and uranium
from  the standpoint  of  both  volatility  and chemical
behavior.

Data  regarding  simulated   radionuclides  are  suspect
because the method  has  not been validated for  these
metals.  Since the method accuracy and precision ar& not
well  quantified, the  data  are  used  for informational
purposes only.

Table 2 is a summary of the spiked components and their
concentrations in the SSM.  The chosen spikes allow for
proper evaluation  of the  technology without  risk  to
personnel safety and limit the generation  of hazardous
products.

Table 2.  Total Concentrations of Spiked Components Measured in
         the SSM
                            Concentration (me/kg)
Analyte
Heavy Metals
Cadmium
Chromium
Lead
Simulated
Radionuclides
Bismuth
Strontium
Zirconium
Organic
Compounds
Average

1260
4350
6410


4180
3720
4070

Range

1000-1800
3800-4680
3880-7510


2810-7210
3300-4100
3660-5000

Anthracene
Dimethyl-
phthalatc
4710
8340
3300-7800
4800-10000
The following paragraphs present information available on
the B&W  cyclone  furnace  and its  performance  and
summarize observations and conclusions on the process as
they relate to the SITE demonstration.
33.1     Slag Characteristics

3.3.1.1  Leachability

Ninety-four percent of the non-combustible portion of the
feed is transformed from loosely packed soil to a brittle,
glass-like  slag.    The remaining  6 percent  becomes
particulate matter in the flue gas. Table 3 summarizes the
concentrations of the spiked components in  the resultant
slag.

Table 3.  Total Concentrations of Spiked Components Measured in
         the Slag
                           Concentration (me/kg)
Anatyte
Heavy Metals
Cadmium
Chromium
Lead
Simulated
Radionuclides
Bismuth
Strontium
Zirconium
Organic
Compounds
Average

106
1610
1760

730
3210
3640

Range

62.7-177
922-2110
1270-2420

522-949
1890-3830
2080-4420

                                                            Anthracene

                                                            Dimethyl-
                                                            phthalate
                         <0.24"


                         <3.89"
(0.04)b-<0.34


  <0.33-llc
                                                           a       If a result was undetected, the detection limit was used in
                                                                   calculations for averages.  This represents worst  case
                                                                   scenario.

                                                           b       Estimated value above instrument detection limit but below
                                                                   method quantitation limit.

                                                           c       The  analysis  of  the field blank yielded similar values
                                                                   indicating the  sample may have been contaminated.

                                                           B&W claims its vitrification technology produces a non-
                                                           leachable, vitrified slag.  For the demonstration, TCLPs
                                                           were performed on both the feed SSM and the slag. The
                                                           SSM was tested  to  determine the   leachability of heavy
                                                           metals  prior  to  treatment.   The slag was tested to
                                                           demonstrate compliance with TCLP regulatory limits. The
                                                           teachabilities of the  heavy metals in the feed soil and the
                                                           slag are summarized in Table 4, which includes TCLP
                                                           regulatory levels.

-------
 Table 4.  TCLP Results from B&W SITE Demonstration (mg/L)
 	Cadmium	Chromium	Lead
 Regulatory
 Limits
                    1.0
                                 5.0
                                              5.0
 SSM
Average
Range'
Slag
Average
Range*
49.9
31.0-75.3

<0.12b
< 0.03-0.30
2.64
1.30-4.32

0.22
0.07-0.81
97.3
72.2-128

<0.31b
< 0.25-0.66
         Range represents low-to-high values of the 27 samples taken
         over the Demonstration period.

         If a result was undetected, the detection limit was used in
         calculations  for averages.  This represents worst case
         scenario.
 TCLP results for the slag indicate the cyclone furnace can
 treat metal-contaminated  soils to  the  extent  that the
 leachate from the resultant slag will comply  with the
 allowable limits.  When TCLPs were performed on the
 feed, the concentrations of lead and  cadmium in the
 leachate were greater than the regulatory limits; however,
 this was not the case for chromium.  It is not known why
 chromium remains relatively fixed  in the  soil.  TCLP
 results   from  previous  testing  by  B&W  (refer to
 Appendix D  - Case Studies) also indicated the leachate
 contained  concentrations  of chromium  less  than the
 regulatory limit.    For  the  demonstration,  chromium
 concentrations were  triple that  of levels from  these
 previous tests; however, the leachate still did not exceed
 the regulatory limit.

 The cyclone vitrification process not  only produces a slag
 that complies with TCLP requirements, but decreases the
 leachability  of metals  in  the  slag.  This decrease in
 teachability is caused by the physical/chemical properties
 of the SSM  changing as it passes through the cyclone
 furnace.

 The leachability of the  simulated radionuclides from the
 slag was determined according to ANS 16.1 - "American
 National Standard Measurement of the Leachability of
 Solidified Low-Level Radioactive Wastes by a Short-Term
 Test Procedure." This method provides a measure of the
 release of simulated  radionuclides  from  the  slag at
 ambient temperatures.   A leachability index of six or
 greater indicates these metals are immobilized within the
 slag.  In order to account for the irregular shape of the
 slag material, the method used to quantify the  external
 surface area of the slag  was modified.

Although all  other  equations  and  data  reduction
 procedures remain the  same,  the method has not  been
validated for  the material in question and accuracy and
 precision are not well quantified; therefore the data are
 suspect.   The  slag's  leachability  index for  bismuth,
 strontium,  and  zirconium  were  13.4,  13.1,  and  8.7,
 respectively.    These  results  indicate  the  simulated
 radionuclides are immobilized.

 3.3.1.2  Volume Reduction

 The vitrification process reduces the volume of the feed
 SSM.  Approximately 20 percent of the SSM is made up
 of materials that combust as they pass through the cyclone
 furnace. These materials include carbonates, sulfates, and
 organics.  Their combustion  results in a decrease in
 volume. Percent volume reductions were determined by
 comparing the volume of dry SSM introduced  to the
 furnace to the volume of dry slag produced. The average
 volume reduction was 29 percent.  Bulk densities of the
 SSM and slag are almost equivalent; therefore any volume
 reduction is the result of this combustion, not a change in
 bulk density.
 33.2    Metals Partitioning

 As the SSM  goes through the cyclone furnace, metals
 partition  to either the flyash or the slag.   Their fate
 depends on the relative volatility of the metal.  The non-
 volatile  metals  such  as  chromium,  strontium,  and
 zirconium remain mainly in the slag.  The more volatile
 metals  such as  bismuth,  cadmium, and  lead tend to
 partition to the flue gas where they are collected by the
 baghouse. During the demonstration, over 75 percent (by
 weight) of the chromium in the SSM was incorporated in
 the vitrified slag.  This percent of retention is consistent
 with retentions obtained during previous tests (refer to
 Appendix D - Case Studies).  In addition, approximately
 88  and  97 percent  of the  strontium  and  zirconium,
 respectively, remained in the slag.   The more  volatile
 bismuth, cadmium, and lead had lower retention (27, 12,
 and 29 percent, respectively).

 Almost all of the total mass of metals which partition to
 the flue gas are captured by the baghouse.  A very small
 portion of the mass of metals  pass through the baghouse
 and out the stack. However, as long as these levels do not
 exceed the furnace's  permit limits (as determined by a
 site-specific risk  assessment),  no  significant changes to
 emission  treatment  need  be   employed.    Table  5
 summarizes the  distribution  of the  metals  during the
 demonstration.

Results from the TCLP analysis of the baghouse solids
indicate the TCLP limits for cadmium and chromium were
exceeded. The baghouse solids therefore require disposal
as a hazardous waste. During the demonstration, 6,000
pounds  of SSM  were  treated  and  approximately  150
pounds of baghouse solids were collected. This is a

-------
Table 5.   Metals Partitioning from the Cyclone Vitrification
         Process (%)
 Metal	Slag	Baghouse	Stack gas
 Bismuth*
  Average
  Range

 Cadmium

  Average
  Range

 Chromium

  Average
  Range

 Lead

  Average
  Range

 Strontium*

  Average
  Range

 Zirconium*

  Average
  Range
  26.8
25.7-28.4
  11.8
113-12.7
  75.8
73.7-793
  29.2
24.3-33.2
  87.8
85.0-893
  965
95.7-97.4
  73.1
71.6-743
  88.1
87.3-88.8
  24.2
20.7-26.3
  70.8
66.8-75.7
  12.2
10.7-15.0
   35
 2.6^.3
 <0.08b
< 0.06-0.11
  0.04
 0.01-0.17
  0.04
 0.01-0.11
   0.05
 0.01-0.13
   0.01
0.003-0.03
   0.02
 0.02-0.03
a        These are included for informational purposes only since the
         accuracy and precision of these data are suspect.

b        If a result was undetected, the detection limit was used in
         calculations  for averages.   This represents  worst case
         scenario.

significant decrease in the amount of material requiring
disposal as hazardous waste.

Modifications have been proposed that would recirculate
the baghouse solids  through the furnace, allowing the
system additional opportunities to trap the metals within
the slag.  This modification may eliminate the need  to
dispose of or treat the flyash as a hazardous waste.
 333    Air Emissions

 3.3.3,1 Paniculate

 During theDemonstration Test, particulate emissions were
 measured directly after exiting the furnace outlet (prior to
 the air pollution control equipment) and at the stack (after
 the baghouse).  Emissions out of the stack easily met the
 RCRA emissions  limit  of  0.08  gr/dscf corrected  to
 7 percent oxygen (O2).  Table 6 summarizes particulate
 data from the Demonstration Test.   The table includes
both measured values and values corrected to 7 percent
O2. The correction factor of 14 * (21 - percent O2) takes
into account the dilution factor in the stack gas caused by
excess air needed for combustion.

Table 6.  Summary of Particulate Emissions
                        Concentration (gr/dscf)
Run No.
1
2
3
Location
Furnace Outlet
Stack
Furnace Outlet
Stack
Furnace Outlet
Stack
Measured
0.858
0.0016
0.864
0.0009
1.058
0.0003
7%O2
0.765
0.0014
0.817
0.0008
0.837
0.0003
Rate (Ib/h)
557
0.017
5.76
0.009
6.89
0.004
By comparing the particulate emission rate from the stack
test at the furnace outlet with the amount of slag produced
per hour by the cyclone furnace, the slag-to-flyash ratio
was determined for each run.  The average slag to flyash
ratio from the Demonstration was 13.7.  In addition to
providing  a relationship from  which baghouse solids
production can be estimated, this result demonstrates the
cyclone  furnace is capable of treating the contaminated
soil without  experiencing major  losses as  particulate
emissions.
3.3.3.2  ORE

The measure used to evaluate organic destruction during
the Demonstration Test is the DRE.  This parameter is
determined by analyzing the concentration of the Principal
Organic Hazardous Constituent (POHC) in the feed SSM
and the stack gas. RCRA regulations define DRE for a
given POHC as follows:
                                         DRE (%) =
                                          Win -_Wout
                                         Where:
                                         W:n
                                   =   Mass feed rate of the POHC of interest in
                                       the waste stream feed

                                   =   Mass emission  rate of  the same POHC
                                       present in exhaust emissions prior to release
                                       to the atmosphere
                                         POHCs identified for the demonstration were anthracene
                                         and dimethylphthalate. These compounds were selected
                                         as representative  stable compounds for the purpose  of
                                         evaluating  the furnace's  ability  to  destroy  organic
                                         compounds.

                                         The cyclone furnace achieved DREs greater  than 99.99
                                         percent for both  of these  organics.  This indicates the

-------
 cyclone furnace is capable of achieving the DREs required
 for a RCRA hazardous waste incinerator (99.99 percent).
 Because  the concentrations of both anthracene  and
 dimethylphthalate in the stack gas were below detection
 limits, these results  do not indicate the maximum DREs
 the cyclone furnace  is capable of achieving. Measurable
 quantities of POHCs were expected in the stack gas since
 high levels of POHCs were spiked in  the SSM (refer to
 Table 2) and their corresponding detection limits are low.
 This indicates the furnace obtained better-than-expected
 results.

 For the Demonstration Test, the gas temperature exiting
 the cyclone barrel was approximately 3000°F, while the gas
 leaving the furnace had a temperature of over 2000°F and
 a 2 second residence time.  Similar operating conditions
 are projected for the commercial-scale system. Because
 anthracene  and dimethylphthalate are relatively difficult
 organics to  destroy,  it is projected that the commercial-
 scale cyclone furnace will be capable of achieving DREs
 of 99.99 percent or greater for all or nearly all organics.  -
3.3.3.3  Products of Incomplete Combustion (PICs)

Volatile Organic Compound  (VOC)  emissions  which
reflect the formation of PICs, were detected in the parts
per  trillion range  for the cyclone  furnace.    Organic
compounds spiked  in the  SSM were non-chlorinated;
therefore,  PICs from  this process  should also be non-
chlorinated.   However,  several chlorinated compounds
were detected.

In order to account for these chlorinated compounds,
three samples of the feed SSM were analyzed for trace
levels of chlorine. The chlorine levels ranged from <0.01
percent to 0.03 percent.   These trace amounts probably
resulted in the formation of chlorinated VOCs.

Higher  concentrations of  chlorinated VOCs may be
detected in the stack gas if a feed soil contains chlorinated
compounds; however, it is expected concentrations would
be very low. Soils contaminated with chlorinated organics
would  also form  hydrogen chloride  (HC1) gas from the
cyclone  vitrification process which  would  have  to be
controlled by a scrubber.
3.3.3.4 Continuous Emission Monitors (CEMs)

CEMs were used  to  measure  nitrogen oxides (NOX),
carbon monoxide (CO), total hydrocarbons (THC), carbon
dioxide (CO2), and O2 emissions during the Demonstration
Test.

NOX emissions are  generally  a result of the combustion
process rather than the nitrogen content of the feed.  The
NOX concentrations from the demonstration were relatively
 low;  however, a unit larger than the pilot system may emit
 significant levels of NOX, which may make it  a major
 source under the Clean Air Act.  Allowable emissions of
 NOX will be established on a case-by-case basis.

 CO and THC emissions were relatively low and indicate
 relatively complete combustion occurs within the cyclone
 furnace, as also indicated by the low PIC concentrations
 (refer to Section 3.3.3.3). Results from the demonstration
 do not indicate the cyclone furnace will have difficulty in
 meeting the RCRA limit of 100 parts per minion (ppm)
 for CO. THC emissions from the demonstration, however,
 were  close to the RCRA limit of 20 ppm.    Careful
 monitoring of THC emissions from the furnace will be
 required in order for the unit to operate in compliance.

 CO2 and O2 in the stack gas were analyzed by CEMs and
 Orsat analysis.   Values obtained from  both  analyses
 compared favorably with one another.  O2 levels in the
 stack gas indicate excess air values from the combustion
 process.  Operating at low excess air values may result in
 incomplete combustion;  too high  values  may  reduce
 combustion temperatures or increase fuel requirements.
 O2 values obtained reflect typical excess air values for a
 natural gas-fired furnace.
33.4    Quench Water

Slag exiting the cyclone furnace is cooled and collected in
a tank filled with quench water.  Quench water samples
collected before and after  each run were' analyzed to
determine if any of the metals present  in the slag or
infusible matter leached into the quench water.  Analyses
of the quench water from the baseline run and  the three
test runs indicated minimal increases in the concentrations
of certain metals during the test runs. Concentrations of
cadmium, chromium, lead, and strontium were so close to
the detection limits that it cannot be determined if the
process causes any increase/decrease in concentrations.
Concentrations of bismuth and zirconium remained below
detection limits throughout the testing period.

Quench  water  samples collected before  and  after  the
second and third test runs were analyzed for anthracene
and dimethyl  phthalate to determine  whether  these
chemicals leached into the quench water.  Concentrations
of both chemicals  remained below method  quantitation
limits throughout both test runs.

When the Demonstration Test was complete, the quench
water was found to be suitable for discharge to a sanitary
sewer and was disposed of in accordance with the terms of
B&W's  wastewater discharge agreement  with  its local
Publicly-Owned Treatment Works (POTW). It is project-
ed  that  the quench water  from the  commercial-scale
system will be suitable  for discharge to a sanitary sewer,
but this must be determined on a site-specific basis.

-------
Water that came in contact with the SSM (wash and rinse
water  from  demonstration equipment  cleanup) was
collected, stored apart from other wastes, and disposed of
as a hazardous waste. The nature of the wash water and
rinse water will be site-specific.  It may be a hazardous or
radioactive waste at some sites; at other sites it may be
suitable for discharge to a sanitary sewer.

In the commercial-scale cyclone furnace soil vitrification
system, the slag quench water, wash water, and rinse water
will only occasionally discharge.  It is projected that the
commercial-scale system will continuously discharge water
from a quench tower, which will use water to cool the flue
gas (the pilot-scale system did not include a quench
tower).   The water from the  quench  tower should be
suitable for discharge to a sanitary sewer.
equipment, such as the baghouse, scrubber, water quench
tower, heat exchanger, and feed system. A small building
must be constructed to house the controls for the system.
The lime required by the scrubber should be stored in this
building or in a separate facility.

3.4.4    Site Area Requirements

A minimum area of 3000 square feet is required for the
cyclone furnace vitrification system and the pad used to
support the system. Additionally, separate areas should be
provided where wastes generated during treatment may be
stored and where feed preparation activities can proceed
prior  to treatment. Since the furnace can be configured
into any position, the shape of the site is inconsequential
except when it limits access to the equipment.
3.4     Ranges of Site  Characteristics Suitable
        for the Technology

3.4.1     Site Selection

The   current   pilot-scale   cyclone   furnace  is  not
transportable; however, it is projected the commercial-
scale unit will be able to be moved from site to site.  The
following discussion of suitable site characteristics applies
only to the commercial-scale unit.

Although the geological features of a site have an effect on
the equipment that may be used within the contaminated
area, normally the cyclone furnace may be erected within
the confines of the contaminated area or positioned so
that the waste can be easily transported  to the furnace.
Ultimately, in order for the furnace to be used onsite, the
characteristics of the  site must allow for the construction
of a pad and the assembly of the system.
 3.4.2    Surface,   Subsurface,   and   Clearance
         Requirements

 A level graded area capable of supporting a pad holding
 the equipment is needed. The foundation must be able to
 support the weight of the cyclone  furnace  (at least  20
 tons), heat exchanger, water quench tower, feed system,
 baghouse, and scrubber. The total weight of all system
 components is expected to be at least 200 tons.  The site
 must be cleared to allow construction and access to the
 facility.
 3.43    Topographical Characteristics

 The  topographical characteristics of the site should be
 suitable for the assembly of the furnace and all ancillary
3.4.5     Climate Characteristics

This treatment technology may be used in a broad range
of different  climates.   Although prolonged periods of
freezing temperatures may interfere with soil excavation,
these temperatures would not affect the operation of the
furnace itself.
3.4.6    Geological Characteristics

Generally, any site that is sufficiently stable to handle the
weight of the furnace facility is suitable for this technology.
However, this B&W cyclone furnace  should not  be
employed in areas  with  landslide  potential,  volcanic
activity,  and fragile geological formations that may  be
disturbed by heavy loads or vibrational stress.
3.4.7    Utility Requirements

In order to operate the cyclone furnace, access must be
available to electrical power, water, compressed air, and
natural gas supplies.  In order to install and operate the
furnace, a 3-phase electrical source capable of providing
440 volts at 140 amps is required. To maintain a sufficient
supply  of  water  for the quench tower and scrubber, a
minimum water flowrate of 40 gallons per minute (gpm)
is needed.  The  baghouse will require approximately 85
standard cubic feet per minute (scfm) of compressed air
at 60 to 100 pounds per square inch gauge pressure (psig).
Natural gas must be provided to serve as a supplemental
fuel in the cyclone furnace, which consumes approximately
100,000 standard cubic feet (scf) of natural gas per hour of
operation. Oil and coal may also be used as supplemental
fuels.
                                                       10

-------
 3.4.8    Size of Operation

 The feed rate for the pilot-scale cyclone furnace soil vitri-
 fication system utilized during the SITE demonstration was
 approximately 170 Ib/hr of contaminated soil. The pilot-
 scale system occupied an area measuring approximately 30
 feet long by 30 feet wide.

 The  projected soil  feed rate  for the  commercial-scale
 cyclone furnace soil vitrification system is 80 tons per day
 (tpd), or approximately 3.3  tons  per hour  (tph).  The
 layout of the commercial-scale system may  be adjusted
 somewhat to conform to an optimum facility  design plan.
 The area required for onsite construction of the system
 will vary with the configuration, but it will require at least
 2400 square feet.
3.5     Applicable Media

The B&W  cyclone furnace  can be used to treat  soils,
sludges, liquids, and slurries contaminated with hazardous
inorganic and organic constituents, low level radioactive
solid wastes, or a combination of the two. The pollutant
concentrations which may be treated by this technology are
constrained by the characteristics (i.e., volatility, mobility,
etc.) of the individual pollutants and the ability of the
furnace to destroy or immobilize the different pollutants.

The Demonstration Test indicated that the furnace was
capable of destroying 99.99 percent of the SVOCs spiked
within the SSM (as demonstrated by DREs) and immobil-
izing approximately 12 percent of the cadmium, over 75
percent of the chromium, and approximately 29 percent of
the lead present within the feed. Since TCLP analyses of
the slag demonstrate acceptable teachability characteristics,
these metals  are  most  likely  trapped within the  slag.
Metals analyses of the baghouse solids indicate that the
remainder of the metals are volatilized and collected with
the particulate by the baghouse.

Simulated   radionuclides  (bismuth,   strontium,   and
zirconium) from the feed were also immobilized in the
slag during  the Demonstration Test.  Approximately 27
percent of the bismuth, 88 percent of the strontium, and
97 percent of the zirconium were immobilized in the slag.
Simulated radionuclides  not  contained in the slag were
primarily recovered in the baghouse solids. Because actual
radionuclides  are expected  to  behave similarly,   this
technology can be used to treat radioactive soils to prevent
the migration of radionuclides from a site.   Following
treatment, the slag and the baghouse solids will still be
radioactive,  but it  is  projected that  the  slag will be
nonleachable.
 3.6     Regulatory Requirements

 Operation of the  B&W Cyclone  Vitrification Furnace
 Technology for treatment of contaminated soil requires
 compliance with certain Federal, state, and local regulatory
 standards   and  guidelines.     Section   121  of  the
 Comprehensive Environmental Response, Compensation,
 and Liability Act (CERCLA) requires that, subject to
 specified exceptions, remedial actions must be undertaken
 in compliance with Applicable or Relevant  and Appro-
 priate Requirements (ARARs), Federal laws, and more
 stringent promulgated state laws (in response to release or
 threats of releases of hazardous substances, pollutants, or
 contaminants) as necessary to protect human health and
 the environment.

 The ARARs which must be followed in treating contamin-
 ated media onsite are outlined in the Interim Guidance on
 Compliance with ARAR, Federal Register, Vol. 52, pp.
 32496 et seq.  These are:

 •        Performance, Design, or Action-Specific Require-
         ments.  Examples include  RCRA incineration
         standards and Clean Water Act (CWA) pretreat-
         ment standards for discharge to POTWs.  These
         requirements are  triggered  by  the particular
        - remedial activity selected to clean a site.

 •        Ambient/Chemical-Specific    Requirements.
         These set health-risk-based concentration limits
         based on  pollutants and  contaminants, e.g.,
         emission limits and ambient ear quality standards.
         The most stringent ARAR  must be complied
         with.

 •        Locational Requirements. These set restrictions
         on activities because  of  site  locations and
         environs.

Deployment of the B&W cyclone furnace will be affected
by three main levels of regulation:

•        Federal EPA air and water pollution regulations

•        State air and water pollution regulations

•        Local  regulations,   particularly  Air  Quality
         Management District requirements

These regulations govern the operation of all technologies.
Other Federal, state, and local regulations are discussed in
detail in the following paragraphs as  they apply to  the
performance,  emissions,   and residues evaluated  from
measurements taken during the Demonstration Test.
                                                      11

-------
3.6.1    Federal Regulations

3.6.1.1 Clean Air Act (CAA)

The CAA establishes primary and secondary ambient air
quality standards for the protection of public health and
emission limitations for certain hazardous air pollutants.
Because the cyclone furnace has the potential to emit
pollutants which are presently regulated under the CAA,
notably CO and NOX, operators of this system must pay
particular attention to the control of these emissions and
compliance with the ambient air quality standards.  Other
regulated emissions may also be produced, depending on
the waste  feed.   During  the Demonstration  Test,
particulate matter, CO, and THC from the stack gas were
monitored relative to their effect on the emission limits
stipulated under 40 CFR 264.  NOX emissions were also
evaluated.
3.6.1.2  CERCLA

CERCLA  of  1980  as  amended  by  the  Superfund
Amendments and Reauthorization Act (SARA) of 1986
provides for Federal funding to respond to releases of
hazardous substances to air, water, and land. Section 121
of SARA,  Cleanup  Standards, states a strong statutory
preference for remedies that are  highly reliable  and
provide long-term protection.  It strongly recommends that
remedial action use  onsite treatment that "...permanently
and significantly reduces the volume, toxicity, or mobility
of hazardous substances." In addition,  general factors
which must be addressed by  CERCLA remedial actions
include:

•        Overall  protection  of human health and  the
         environment

•        Compliance with ARARs

•        Long-term  effectiveness and permanence

•        Reduction of toxicity, mobility, or volume

•        Short-term effectiveness

•        Implementability

•        Cost

•        State acceptance

•        Community acceptance
 The ability of the B&W cyclone furnace to destroy the
 majority of the organic contaminants originally present in
 the feed, as demonstrated  by DREs of 99.99 percent or
greater, indicates the cyclone furnace is capable of "perma-
nently and significantly" reducing the threat posed by the
organic compounds.  TCLP analyses of the vitrified slag
demonstrated  that the  cyclone furnace  is  capable  of
immobilizing heavy metal contaminants within the slag in
the short-term. However, the long-term effectiveness and
permanence of these results were not evaluated as part of
this project.  It is anticipated,  however, that the  heavy
metals will be  immobilized within the treated soil.

The short-term effectiveness of the B&W process may be
evaluated by examining analytical data obtained from the
stack gas and stack gas solids.  Since the stack emissions
are well below the emission  limits stipulated by 40 CFR
for particulates, CO, and THC, the data indicate that the
cyclone furnace is highly reliable in respect to the regulat-
ed emissions of concern.

Except for soil-bearing capacity requirements, very few site
characteristics  can restrict the implementation of this
system. Unfortunately, the system is not easily or quickly
assembled or disassembled.  Thus the cyclone furnace  is
better  suited  for facilities where ongoing treatment  is
required rather than  for facilities where short-term or
small-scale treatment is required.

This technology may be used to treat media contaminated
with metals, radionuclides, and organics which are not
amenable to treatment using traditional techniques. If the
cyclone furnace were applied to such media, the organics
would  be  destroyed.   A  portion  of the  metals  and
radionuclides  would be immobilized  in the  slag; the
remainder  would be  contained in the baghouse  solids.
Both the slag and the baghouse solids would be radioactive
and the baghouse solids would likely be hazardous. It is
projected that the metals and  radionuclides in the slag
would be nonleachable since the slag generated during the
SITE demonstration was nonleachable. The slag would be
considered  nonhazardous   according  to   CERCLA
requirements.
3.6.1.3  RCRA

RCRA  is the  primary Federal  legislation  governing
hazardous waste  activities.    Under RCRA,  various
incineration  performance  standards  are  established.
Although a RCRA permit is not  required, the cyclone
furnace  must meet all of  its substantive requirements.
However,  administrative RCRA requirements such as
reporting and recordkeeping are not applicable for onsite
action.

Subtitle C of RCRA contains requirements for generation,
transport, treatment, storage, and  disposal of hazardous
waste. Compliance with these requirements is mandatory
for CERCLA sites producing hazardous waste  onsite.
                                                      12

-------
Two potentially hazardous waste streams, the baghouse
solids  and the treated slag, are produced by the B&W
cyclone furnace.  Since a limited potential exists for the
heavy  metals to leach from the slag, as demonstrated by
TCLP data, the flyash from the baghouse constitutes the
primary hazardous waste stream produced by this process.
This material is contaminated with metals which volatilized
or oxidized to form fumes or fine participates during the
treatment process. These metal fumes and particles were
removed from the gas stream by the baghouse.

In  order  to  maintain  compliance with  RCRA,  sites
employing the  cyclone  furnace  must  obtain  ah EPA
generator  identification number  and  observe  storage
requirements stipulated under 40 CFR 262. Alternatively,
a Part B Treatment, Storage, and Disposal (TSD) permit
of interim status maybe obtained. Invariably, a hazardous
waste manifest must accompany offsite shipment of waste
and transport must comply with Federal Department of
Transportation hazardous waste transportation regulations.
Without exception, the  receiving TSD facility must  be
permitted and in compliance with RCRA standards.

The technology or treatment standards  applicable to the
media produced by the B&W furnace (vitrified slag and
baghouse solids) will be determined by the characteristics
of the material  treated  and the waste  generated.  The
RCRA land disposal restrictions (40 CFR 268) preclude
the land disposal of hazardous wastes which fail  to meet
the stipulated treatment standards.  Wastes which do not
meet these standards must receive additional treatment to
bring the wastes into compliance with the standards prior
to land disposal, unless a variance is granted. The amount
of baghouse solids requiring treatment or disposal may be
eliminated if they are recycled  through the furnace. This
modification has been proposed by B&W although it has
not been tested.
3.6.1.4  CWA

The CWA regulates direct  discharges to surface water
through  the  National  Pollutant Discharge  Elimination
System (NPDES) regulations.  These regulations require
point-source discharges of wastewater to meet established
water quality standards.  The discharge of wastewater to
the sanitary sewer requires a discharge permit or, at least,
concurrence from  state and local  regulatory authorities
that the wastewater is in compliance with regulatory limits.

During the SITE demonstration, the water used to quench
the molten slag produced by the cyclone furnace  was
disposed of in accordance with the terms of B&W's waste-
water discharge agreement with its local POTW.   The
wash water from decontamination  and rinse water from
demonstration equipment cleanups was collected, stored
separate  from other  wastes,  and  disposed  of as  a
hazardous waste. The nature of the wash and rinse water
 will be site-specific; it may be a hazardous waste at some
 sites.  In the commercial-scale system, the slag quench
 water, wash water, and rinse  water will create  only
 occasional discharges.  The water from the quench tower
 will be  discharged  continuously during  operation and
 should be suitable for discharge to a sanitary sewer.
 3.6.1.5  Safe Drinking Water Act (SDWA)

 The SDWA establishes primary and secondary national
 drinking water  standards.   CERCLA refers to  these
 standards and Section 121(d)(2) explicitly mentions two of
 these  standards  for  surface water  or groundwater  -
 Maximum Contaminant Levels (MCLs) and Federal Water
 Quality Criteria.  Alternate Concentration Limits may be
 used when  conditions of Section 121 (d)(2)(B) are met
 and cleanup to  MCLs or other protective levels is  not
 practicable. Included in these sections is guidance on how
 these requirements may be applied to Superfund remedial
 actions.   The guidance, which is based  on Federal
 requirements and policies, may be superseded by more
 stringent promulgated state requirements, resulting in the
 application of even stricter standards than those specified
 in Federal regulations.
3.6.1.6 Atomic Energy Act (AEA)

Radioactive material treatment, storage, and disposal are
regulated under the AEA.   For commercial  and most
federal facilities, the Nuclear Regulatory  Commission
(NRC) maintains the regulatory framework under which
use  of radioactive  material is  controlled.   For DOE
facilities, standards for the control of radioactive material
are established under a series of DOE Orders.  Most
NRC regulations are not directly applied to DOE facilities,
since both agencies were founded  under the auspices of
the AEA.  However, some NRC regulations, particularly
in disposal of certain wastes, are  directly applicable to
DOE operations.

Operation of  the   B&W  furnace  for  treatment of
radioactive materials at a  non-DOE  facility must be
specifically authorized under a license issued by the NRC,
mandating compliance with the safety and health standards
contained hi 10 CFR 20.  The license application will
define  the conditions under  which  the furnace would be
operated to ensure health and safety protection of the
workers, the public, and the environment.  At a DOE
facility, the comparable requirements for general radiation
protection will apply, although no license document would
be required.

Disposal of the treatment  residuals from the furnace
would  be regulated  under 10 CFR 61  or DOE Order
5820.2A, depending of whether it  is at a DOE facility.
Under either set  of  requirements,  a  defined  upper
                                                     13

-------
concentration level has been established for near surface
disposal of certain radionuclides.

Certain regulations of the EPA also apply to some forms
of radioactive  waste disposal.   In general,  the  EPA
radioactivity standards would  not  apply to the B&W
furnace,  unless it is used to treat high-level waste  or
wastes from a uranium or thorium mill tailing site.

If treatment residues contain both  RCRA  regulated
constituents and radioactive  material, they would be
classified as mixed waste.  Since there are no currently
operating mixed waste disposal facilities, any mixed waste
resulting from  operation of the furnace would  have  to
meet the RCRA land disposal regulations standards such
that it could be stored for the time required to develop an
acceptable disposal facility.
3.6.2    State and Local Regulations

Compliance  with  ARARs  may  require  meeting state
standards that are more stringent than Federal standards
or that are the controlling standards in the case of non-
CERCLA treatment activities. Several types of state and
local regulations which may affect operation of the B&W
cyclone furnace are cited below:

•       Permitting requirements for
        construction/operation

*       Limitations on emission levels

•       Nuisance rules
3.7     Personnel Issues

3.7.1    Training

Since all personnel involved with sampling  or working
dose to the furnace will be required to wear respiratory
protection, 40 hours of Occupational Safety  and Health
Act  (OSHA)   training   covering  Personal  Protective
Equipment Application,  Safety and Health,  Emergency
Response  Procedures, and  Quality Assurance/Quality
Control are required.  Additional training addressing the
site activities,  procedures,  monitoring,  and  equipment
associated with the technology is  also  recommended.
Personnel should also be briefed when new operations are
planned, work practices change, or if the site or environ-
mental conditions change.
 3.72    Health and Safety

 Personnel should be instructed on the potential hazards
associated with  the  operation  of the cyclone furnace,
recommended  safe  work  practices,   and  standard
emergency plans and procedures.   Health and  Safety
Training covering the potential hazards and provisions for
exposure,  monitoring, and the use and care of personal
protective  equipment   should  be  required.    When
appropriate, workers should have medical exams. Medical
exams are particularly appropriate if the cyclone furnace
is being used for the remediation of radioactive media.
All workers should be routinely monitored for exposure to
radiation.   Health and safety  monitoring  and incident
reports  should  be  routinely  filed and  records of
occupational illnesses and injuries   (OSHA Forms 102
and 200)  should  be  maintained.   Audits ensuring
compliance with the health and  safety plan should be
carried out.

Proper personal protective equipment should be available
and properly utilized by all onsite personnel.  Different
levels of personal protection will be required based on the
potential hazard associated with  the site and the work
activities.

Site monitoring should be conducted to identify the extent
of hazards and to document exposures at the site.  The
monitoring results should be maintained and posted.
3.73     Emergency Response

In the event of an accident, illness, explosion, hazardous
situation at the site, or intentional acts of harm, assistance
should be immediately sought from the local emergency
response teams and first aid or decontamination should be
employed where appropriate. To ensure a timely response
in the case of an emergency, workers should review the
evacuation plan, firefighting procedures, cardiopulmonary
resuscitation (CPR) techniques, and emergency decon-
tamination procedures before operating the system.  Fire
extinguishers,  spill cleanup  kits,  alarms,  evacuation
vehicles, and an extensive first aid kit should be onsite at
all times.

For sites with radioactive media, bioassay urine samples
should be collected whenever an intake above allowable
limits may have  occurred.
 3.8     References

 1.       Procedures Manual for Preparation of Synthetic
         Soils Matrix (SSM 019) Samples for B&W SITE
         Program.  Prepared by Foster Wheeler Envire-
         sponse,   Inc.  for  the  U.S.  Environmental
         Protection Agency, September 1991.
                                                      14

-------
                                                 Section 4
                                           Economic Analysis
4.1     Introduction

The primary purpose of this economic analysis  is  to
estimate costs (not  including profits) for a commercial
treatment  system utilizing the B&W cyclone  furnace
vitrification process.  This analysis is based on the results
of  a SITE  demonstration which  utilized  a pilot-scale
cyclone furnace vitrification system. The pilot-scale unit
operated at a feed rate of 170 Ibs/hr of contaminated soil
and utilized  energy  at a rate of 5  million Btu/hr.   It is
projected the commercial unit will be capable of beating
approximately 3.3 tons per hour (tph) of contaminated soil
and will require an  energy input of 100 million Btu/hr.
The daily feed rate for  the pilot-scale  system  was
approximately 2 tons per day (tpd), while it is projected
the commercial system will be capable of treating 80 tpd.
4.2     Conclusions

The commercial-scale cyclone furnace vitrification system
proposed by  B&W appears to be applicable  to the
remediation of soils and other solid wastes contaminated
with organics, metals, and radionuclides. Treatment costs
appear to be competitive with other available technologies.
The cost to remediate  20,000 tons  of contaminated soil
using a 3.3 tph  cyclone furnace vitrification system  is
estimated at  $465 per ton  if  the  system is online 80
percent of the tune or $529 per ton if the system is online
60 percent of the time.  Projected unit costs for a smaller
site (less than 20,000 tons of contaminated soil) are slightly
higher; projected unit costs for a larger site are slightly
lower.
4.3     Issues and Assumptions

Because the  B&W cyclone furnace vitrification process
appears  to  be  capable  of  effectively  treating  soils
contaminated with organics, metals, and radionuclides, it
is considered potentially applicable to the remediation of
DOE and DOD sites as well as typical Superfund sites. In
the following economic analysis, the costs associated with
this  technology are calculated based on the treatment of
20,000 tons of contaminated soil.  This basis was chosen
because a small to medium DOE or DOD site may have
approximately 20,000 tons of contaminated soil suitable for
treatment by cyclone furnace vitrification. Approximately
3 tons of contaminated soil were treated  during the SITE
demonstration.

Costs  which are assumed to be  the obligation of  the
responsible party or site owner have been omitted from
this  cost estimate and are  indicated by a line (—)  in all
tables.

Important assumptions regarding operating conditions and
task responsibilities that could significantly affect the cost
estimate results are presented in the following paragraphs.
43.1     Costs Excluded from Estimate

The cost estimates presented are representative of the
charges typically assessed to the client by the vendor but
do not include profit.

Many other actual or potential costs were not included as
part of this estimate. These costs were omitted because
site-specific engineering designs beyond the scope of this
SITE project would be required to determine those costs.
As  a result, certain functions were assumed to be the
obligation of the responsible party or site owner and were
not included in this estimate.

Costs  such as  preliminary  site  preparation,  permits,
regulatory requirements, initiation of monitoring programs,
waste disposal, sampling and analyses, and post-treatment
site cleanup and restoration are considered to be the re-
sponsible party's (or site owner's) obligation and are not
included. These costs tend to be site-specific and it is left
to the reader to perform calculations relevant to each
specific case. Whenever possible, applicable information
                                                      15

-------
is provided on these topics so the reader may perform
calculations to obtain relevant economic data.
based on the treatment of a total of 20,000 tons of waste
using a 3.3 tph system.
        Maximizing Treatment Rate
Factors limiting the treatment rate include the feed rate
and  the  online  percentage.   Increasing the feed  rate
and/or the online percentage can reduce the unit treat-
ment cost. Increasing the feed rate of the commercial unit
beyond 33  tph,  however, may result hi less  effective
reduction of contaminants.
433    Utilities

To support the operation of the cyclone furnace vitrifica-
tion system, a site must have clean water available at a
flow rate of at least 40 gpm. The majority of this water
(34 gpm) will be used in the water quench tower to cool
the flue gas.  The remainder of the water will be used in
the scrubber and in other miscellaneous onsite applications
such as cleaning and rinsing.

A natural gas source and  the required piping must be
available and  accessible to  accommodate a natural gas
usage of approximately 100,000 cubic feet per hour at
standard conditions (60°F and 30 inches of mercury). The
natural gas will serve as  a supplemental fuel  for the
cyclone furnace.  Alternatively, provisions may be  made
for the use of oil or coal as a supplemental fuel.

Electrical power is required for the  operation of the fan,
the baghousc, the scrubber, and many smaller pieces of
equipment.  The baghouse also requires compressed air,
which must be supplied at a pressure of 60 to 100 pounds
per square inch gauge (psig) and a flow rate of at least 85
standard cubic feet per minute (scfm).

For these cost calculations, it  is assumed the site will
support all of these requirements. The cost of preparing
a site to meet these requirements can be high and  is not
included in this analysis.
43A    Operating Times

It is assumed the treatment operations will be conducted
24 hours a day, 5 days a week.  It is further assumed site
preparation,  assembly,  shakedown  and  testing,   and
disassembly operations will be conducted 12 hours a day,
5 days a week.  Excavation activities for site preparation
will be concurrent with treatment (and may be concurrent
with  assembly  and  shakedown and  testing as well).
Assembly, shakedown and  testing,  and disassembly are
assumed  to  require  6 weeks,  6 weeks,  and 3 weeks,
respectively.  Except where noted, these calculations are
43.5    Labor Requirements

Treatment operations for a typical shift are assumed to
require ten workers:  four feed operators, two mainten-
ance operators, and four system operators.  Each shift is
assumed to be 8 hours long.
43.6    Capital Costs

Capital costs for equipment consist of the cost of the
furnace  and  additional  equipment  such  as a  heat
exchanger, a  water quench tower, a  feed system,  a
baghouse, and a scrubber.
43.7    Equipment and Fixed Costs

Annualized equipment cost and costs that are estimated as
percentages of equipment costs on an annual basis have
been prorated for the duration of time that the equipment
is onsite. The costs for equipment, contingency, insurance,
and taxes accrue during assembly, shakedown and testing,
treatment, and disassembly; scheduled maintenance costs
accrue during treatment only.
4.4    Basis of Economic Analysis

The cost  analysis  was prepared by breaking down the
overall cost into 12 categories.  The categories, some of
which do not have costs  associated  with them for this
particular technology, are:

•       Site preparation costs
•       Permitting and regulatory costs
•       Equipment costs
•       Startup and fixed costs
•       Labor costs
•       Supplies costs
•       Consumables costs
•       Effluent treatment and disposal costs
•       Residuals  and waste  shipping,  handling, and
        transport costs
•       Analytical costs
•       Facility modification,  repair,  and replacement
        costs
•       Site demobilization costs

The 12 cost factors examined as they apply to the B&W
cyclone furnace vitrification process, along with the as-
sumptions employed, are  described  in  the following
paragraphs.
                                                      16

-------
 4.4.1    Site Preparation Costs

 It is assumed  that preliminary site preparation will be
 performed by the responsible party (or site owner).  The
 amount of preliminary site preparation will depend on the
 site.  Site preparation responsibilities include site design
 and layout, surveys and site logistics, legal searches, access
 rights and roads, preparations for support and decontamin-
 ation facilities, utility connections, and auxiliary buildings.
 Since these costs are site-specific, they are not included as
 part of the site preparation costs in this cost  estimate.

 Certain site preparation activities,  such  as excavating
 hazardous waste from the  contaminated site,  will be
 required at all sites and are therefore included in this
 estimate. Cost estimates for site preparation are based on
 rental costs for operated heavy equipment, labor charges,
 and equipment fuel costs.

 An excavation  rate of 9.1 tph is assumed for all cleanup
 scenarios using the 3.3 tph cyclone furnace. It is assumed
 the  minimum rental equipment required  to achieve an
 excavation rate of approximately 9.1 tph includes three
 excavators, one box dump truck, and one backhoe.  The
 operation of this equipment will consume approximately 14
 gallons  of diesel fuel per hour.   It is  also assumed
 excavation activities will be conducted 12 hours  a day, 5
 days a week.  An excavation rate of 45.5 tph is assumed
 for the  cost estimate based on the use of a larger cyclone
 furnace (capable of treating 20 tph). It is further assumed
 that an excavation rate of 45.5  tph will require five times
 as much equipment, labor, and diesel fuel as an excavation
 rate of  9.1 tph. Excavation costs are itemized in  Table 7.
Table 7. Excavation Costs
Item
Excavator
Box dump truck
Backhoe
Supervisor
Excavator operator
Dump truck operator
Backhoe operator
Diesel fuel
Cost
$l,260/week
$525/week
$585/week
$40/hour
$30/hour
$30/hour
$30/hour
Si/gallon
4.4.2    Permitting and Regulatory Costs

Permitting  and  regulatory  costs  are generally  the
obligation of the responsible party (or site owner), not of
the vendor.  These costs may include actual permit costs,
system monitoring requirements, and/or the development
 of monitoring and analytical protocols.  Permitting and
 regulatory costs can vary greatly because they are site- and
 waste-specific.  No permitting or regulatory costs are
 included in this analysis. Depending on the treatment site
 however, this may be a significant factor since permitting
 activities can be both expensive and time consuming.
 4.43    Equipment Costs

 Major pieces of equipment include the:
    Cyclone furnace
    Heat exchanger
    Feed system
    Baghouse
    Quench tower
    Scrubber
The cyclone furnace cost supplied by B&W was used.  It
was comparable to  an independent cost estimate.  All
other  equipment costs were estimated  from various
references.  The primary references used were the third
edition of Plant Design and Economics  for  Chemical
Engineers by M.S. Peters and K.D. Timmerhaus [1] and
the fourth edition of the Office of Air Quality Planning and
Standards Cost Control Manual [2]. Total equipment costs
for the 3.3 tph cyclone furnace  vitrification system are
estimated to be approximately $3,500,000;  equipment
costs  for  the  20  tph system  are  estimated  to  be
approximately $11,600,000.  For each system, a useful life
of 15 years and an interest rate of 10 percent are assumed.

It is assumed no rental equipment or purchased support
equipment will be  required for  operation.   Support
equipment refers to  pieces of purchased  equipment
necessary for operation but not integral to the system.

The commercial-scale cyclone furnace will  be capable of
treating 3.3 tph of  contaminated soil  and will require
approximately 100 million Btu/hr. System accessories will
include a feed  system  (holding  tank,  mixer, and feed
nozzle) and an air pollution control system. The effluent
flue gas flows through an air-to-air heat exchanger where
it  is cooled  from 2000°F to BOOT while heating the
influent combustion  air from ambient temperature to
800°F.   Following the  heat  exchanger, the flue gas is
cooled to 200°F in a water quench tower. The cooled gas
flows to a lime spray dryer for acid gas removal and then
to a pulse-jet baghouse for particulate removal.

The total equipment cost is calculated and is annualized
using the following formula:

       A =     C *  i * fl +  iV
                (1 + i)n - 1
                                                      17

-------
where:          A = annualized cost, $
                C = capitalized cost, $
                i =  interest rate, %
                n = useful life, years

The annualized cost  (rather than depreciation) is used to
calculate  equipment costs incurred by  a  site.   The
annualized equipment cost is prorated to the actual time
the reactor is commissioned to treat a hazardous waste
(including assembly,  shakedown and testing, treatment,
and disassembly).  The prorated cost is then normalized
relative to tons of soil treated.
4.4.4    Startup and Fixed Costs

Mobilization includes both transportation and assembly.
The cyclone furnace vitrification system will be difficult to
transport and its relocation will require a great deal of
time  and planning.   For the purpose  of  this  estimate,
transportation costs are included with mobilization rather
than  demobilization.   Transportation  activities include
moving the system and the workers to the site.  As a
rough estimate, it is assumed that ten tractor-trailers will
be required  to transport the  commercial-scale cyclone
furnace soil  vitrification system.  A 1,000 mile basis is
assumed  at  a rate of  $1.65  per  mile per legal load
(including drivers).  Transportation costs  for  the  30
workers are based on a $300 one-way airfare per person.
The accuracy of this airfare estimate was confirmed by an
examination  of one-way airfares for flights from Akron,
Ohio (near Alliance) to Dallas-Fort Worth and to Fort
Laudcrdale, both of which are approximately 1000 miles
from Akron.

Assembly consists of unloading the system from the trucks
and trailers and reassembling the furnace.  It is assumed
that unloading the equipment will require the use of an
operated 50-ton crane for 6 weeks at a cost of $6,360 per
week. Assembly is assumed to require 30 people working
12 hours per day, 5 days per week, for 6 weeks. Labor
charges during assembly consist of wages ($40 per hour)
and living expenses (refer to subsection 4.4.5).

This cost estimate assumes that 6 weeks of shakedown and
testing will be required after assembly and prior to  the
commencement of treatment. During this tune, the system
components are tested individually.  It is estimated that 15
workers will be required for 12 hours per day, 5 days  per
week during shakedown and testing. Labor costs consist
of wages ($40 per  hour)  and living expenses (refer to
subsection 4.4.5).

Working capital consists of the amount of money currently
invested  in  supplies, energy,  and spare parts kept on
hand [1]. The working  capital for this system is based on
maintaining a 1-month inventory of these items. For the
calculation of working capital, 1 month is defined as one-
twelfth of a year, or approximately 21.7 working days.

Insurance  is  approximately  1  percent  of  the total
equipment capital  costs, while taxes are 2 to  4 percent.
The cost of insurance for a hazardous waste process can
be  several times more than this.  Insurance  and taxes
together are assumed, for the purposes of this estimate, to
be  10 percent of the equipment capital  costs [1].  These
costs have been prorated to the actual  time the cyclone
furnace is commissioned to treat  contaminated waste on
a  site  (including  assembly,  shakedown  and  testing,
treatment, and disassembly).

The cost for the  initiation of monitoring programs has not
been included in this estimate.  Depending on the site,
local authorities  may  impose  specific guidelines  for
monitoring programs.  The stringency and frequency of
monitoring required may have a significant impact on the
project  costs.

An annual contingency cost of 10 percent of the annual-
ized equipment capital costs is allowed to cover additional
costs caused by  unforeseen or unpredictable events, such
as strikes, storms, floods, and, price variations [1].  The
annual  contingency cost has been prorated to  the actual
time the reactor is  commissioned to treat hazardous waste
(including assembly,  shakedown  and testing,  treatment,
and disassembly).
 4.4.5   Labor Costs

 Labor  costs  consist  of wages  and  living  expenses.
 Personnel requirements per shift during treatment are
 estimated at:   four feed operators at $25 per hour, two
 maintenance operators  at $30 per hour, and four system
 operators at $40 per hour.  Rates include overhead and
 administrative  costs.  It is  assumed that personnel will
 work an average of 40 hours per week at three shifts for
 a 24-hour, 5-day-per-week operation.

 Living expenses depend on  several factors:  the duration
 of the project, the number of local workers hired, and the
 geographical location of the project. Living expenses for
 all personnel who are not local hires consist of per diem
 and rental cars, both charged at 7 days per week for the
 duration  of the treatment.  Per diem varies by location,
 but for the purposes of this report is assumed to be $60
 per day per person.  Six rental cars are required for a 24-
 hour operation and are available for $30 per day per car.
 Depending on the length of the project, B&W may elect
 to hire  local personnel and train them hi the operation of
 the furnace, thus eliminating living expenses.
                                                       18

-------
 4.4.6   Supplies Costs

 For this estimate, supplies consists of chemicals and spare
 parts.  Lime requirements  for  scrubber  operation  are
 estimated  to cost approximately  $28,500 per year  of
 operation (a year of operation is defined as a year of time
 spent actually processing waste).  Spare parts consist of
 baghouse bags, which cost approximately $12,800 per set
 and are assumed  to  require annual replacement  during
 periods of treatment.
 4.4.7   Consumables Costs

 The cyclone furnace consumes natural gas at a rate of
 approximately 100 million Btu/hr. The cost of natural gas
 is estimated as $5.10 per million Btu with no monthly fee,
 yielding a fuel cost of approximately $510 per hour of
 operation.

 The projected air usage for the baghouse is approximately
 85 scfm of 60 to 100 psig air; air costs are estimated at
 $0.20 per 1000 standard cubic feet (scf).

 The electricity  requirement  for  the  baghouse  fans is
 approximately 414,600 kilowatt-hours (kWh) per year of
 operation. It is estimated that the electrical requirements
 for  the  scrubber will  have  an  associated  cost  of
 approximately $5 per hour of operation. The cost estimate
 assumes that electricity can be obtained for a flat rate of
 $0.06 per  kWh with no monthly charge.

 The quench tower requires 34 gpm of water.  Smaller
 quantities  of  water are  used in the scrubber  and  in
 miscellaneous other applications  yielding an estimated
 total water usage rate of 40 gpm.  Water costs are
 estimated at $1.10 per 1000 gallons.
4.4.8    Effluent Treatment and Disposal Costs

B&W is currently investigating the feasibility of mixing the
baghouse solids into the feed and recycling them through
the system.  If this process change is found to be feasible,
it will be implemented in the commercial-scale system and
it will not be necessary to dispose of the baghouse solids.
The  baghouse   solids  generated  during  the  SITE
demonstration were found to be hazardous  and  will
therefore require disposal as a hazardous waste and/or
additional treatment.

The water from  the quench tower should be  suitable for
discharge to a municipal sewer system.  The  responsible
party or site owner should obtain a discharge permit from
the local municipality if possible.  If no sewer service is
available, the site owner or responsible party must obtain
a direct discharge permit or arrange for disposal by other
 means. It should not be necessary to treat the water prior
 to discharge, but this must be determined on a site-specific
 basis.

 Onsite treatment and disposal costs are restricted to onsite
 storage (if necessary) of the water from the quench tower
 and are assumed to be the obligation of the site owner or
 responsible party.   Offsite treatment  and disposal costs
 consist of wastewater disposal fees and are assumed to be
 the  obligation of the responsible party (or  site  owner).
 These costs may significantly add to the total cleanup cost.


 4.4.9   Residuals  and Waste Shipping, Handling, and
        Transport Costs

 It is assumed that  the only residual  generated by this
 process will be the  slag.  The  slag generated during the
 SITE demonstration passed the TCLP test; as a result, it
 is anticipated that the slag will be disposed of in a sanitary
 landfill.  The teachability of the slag from actual wastes
 must be determined on a site-specific basis.  Potential
 waste disposal costs include storage, transportation, and
 treatment costs and are assumed to be the obligation of
 the responsible party (or site owner).  These costs could
 significantly add to the total cleanup cost.
4.4.10  Analytical Costs

No analytical costs  are included in this cost estimate.
Standard  operating procedures for B&W do not require
sampling  or analytical activities.  The client may elect or
may be required by local authorities to initiate a sampling
and analytical program  at then- own expense. If specific
sampling  and monitoring criteria are imposed  by local
authorities, these analytical requirements could contribute
significantly to the cost of the project.
4.4.11   Facility Modification, Repair, and
        Replacement Costs

Maintenance labor and material costs vary with the nature
of the waste and the performance of the equipment.  For
estimating purposes, total annual maintenance costs (labor
and materials) are assumed to be 10 percent of annualized
equipment costs. Maintenance labor typically accounts for
two  thirds  of the  total  maintenance  costs  and  has
previously been accounted for under in subsection 4.4.5.
Maintenance material costs are estimated at one third of
the total maintenance cost and are prorated to the entire
period of treatment.  Costs for design adjustments, facility
modifications, and equipment  replacements are included
in the maintenance costs.
                                                      19

-------
4.4.12  Site Demobilization Costs

Demobilization costs are  limited to disassembly costs;
transportation costs are accounted for under mobilization.
Disassembly consists of taking the cyclone furnace apart
and loading it  onto ten trailers  for transportation.  It
requires the use of an operated 50-ton crane, available at
$6,360 per week,  for 3 weeks.  Additionally,  disassembly
requires a 30-person crew working 12-hour days, 5 days a
week, for 3 weeks.  Labor costs consist of wages ($40 per
hour  per   person)  and   living  expenses  (refer  to
subsection 4.4.5).

Site cleanup and restoration are limited to the removal of
all equipment  from the  site.  These  costs have been
previously  incorporated   into  the   disassembly  costs.
Requirements   regarding   the   filling,  grading,   or
rccompaction of the soil will vary depending on the future
use of the site and are assumed to be the obligation of the
responsible party (or site owner).
4.5     Results of Economic Analysis

The costs associated with the  operation of the cyclone
furnace, as presented in this economic analysis, are defined
by 12 cost categories that reflect typical cleanup activities
encountered  on Superfund sites. Each of these cleanup
activities is defined and  discussed, forming the bases for
the cost analysis presented in Table 8.
  TableS. Treatment Costs for  3.3 tph Cyclone furnace
          Vitrification  System  Treating  20,000  Tons   of
          Contaminated Soil
   Item
                            60%
                            online
      Cost (S/ton)
          70%
         online
         80%
         online
   Site Preparation
   Permitting and
   Regulatory Costs
   Equipment Cost Incurred
   Startup and Fixed Costs
   Labor
   Supplies
   Consumables
   Effluent Treatment
   and Disposal
   Residuals Handling
   and Transport
   Analytical Costs
   Facility Modification,
   Repair and Replacement
   Site Demobilization
   Total Operating Costs
                             31.37
 43.83
 58.67
219.95
  2.02
157.96
          31.37
                                              31.37
 38.52    34.53
 58.94    59.48
188.53   164.96
  1.87     1.76
157.96   157.96
  1.24      1.06     0.93
 13.83     13.83    13.83
528.88    492.09   464.84
                                The percentage of the total cost contributed by each of the
                                12 cost categories is shown in Table 9.

                                   Table 9. Treatment Costs as Percentages of Total Costs
                                           for 3.3 tph Cyclone Furnace Treating 20,000
                                           Tons of Contaminated Soil

                                                            Cost (as % of total cost)
Item
Site Preparation
Permitting and
Regulatory Costs
Equipment Cost
Incurred
Startup and Fixed Costs
Labor
Supplies
Consumables
60%
online
5.9
—
8.3
11.1
41.6
0.4
29.9
70%
online
6.4
—
7.8
12.0
38.3
0.4
32.1
80%
online
6.7
—
7.4
12.8,
35.5
0.4
34.0
                                   Effluent Treatment and
                                   Disposal

                                   Residuals Handling and
                                   Transport

                                   Analytical Costs

                                   Facility Modification,
                                   Repair and Replacement

                                   Site Demobilization

                                   Total Operating Costs
                                                   0.2

                                                   2.6

                                                  100.0
                                    0.2

                                    2.8

                                   100.0
 0.2

 3.0

100.0
B&W states that coal-fired cyclone furnaces  frequently
operate with online factors of over 90 percent. The online
factor for a cyclone furnace being used to vitrify soil is
unknown, so online  factors of 60 percent, 70 percent, and
80  percent  were used to  estimate the cost of  cyclone
furnace vitrification. The online factor is used to adjust
the unit treatment cost to compensate for the fact that the
system is not online constantly because of  maintenance
requirements,  breakdowns, and  unforeseeable  delays.
Through the use of the online factor, costs incurred while
the system is not operating are incorporated into the unit
cost.

The B&W cyclone furnace vitrification system is expected
to be capable of a week of continuous operation; only one
startup should  be required each week  unless problems
arise.  In fact,  the  system is  believed to be capable  of
operating continuously (24 hours per day, 7 days per week)
for extended periods of time  and B&W will most likely
choose to  conduct site remediations in this manner.  If
B&W chooses to operate  continuously, adjustments must
be made to the  cost estimates for fuel, labor, and all other
                                                         20

-------
 items which are affected by the length of time that the
 system is onsite.

 The feed rate during the SITE Demonstration Test was
 approximately  170  Ib/hr and the  furnace  consumed
 approximately 5 million Btu/hr. The results of this pilot-
 scale demonstration were used to estimate the results of
 commercial-scale operation. The "six-tenths" rule was used
 to estimate the cost of equipment for the commercial-scale
 system from  available cost data for equipment  of  a
 different capacity [1].  The Marshall & Swift  cost index
 was used to estimate current costs (fourth quarter of 1991)
 from earlier cost data [1]. It is assumed the commercial-
 scale unit will have a feed rate of 3.3 tph and will require
 approximately 100  million Btu/hr. For this feed rate, the
 results of the analysis show a unit cost ranging  from $465
 per ton to $529 per ton for 80 and 60 percent online
 conditions, respectively.

 These costs are considered order-of-magnitude estimates
 as defined by the American Association of Cost Engineers.
 The actual cost is expected to fall between 70 percent and
 150 percent of these estimates. Since costs were estimated
 from a pilot unit, the range may actually be wider.

 Table 10 compares estimated unit treatment costs for sites
 containing 10,000,  20,000, and 100,000 tons of  contamin-
 ated  soil,  while Table 11 shows the  percentage of the
 treatment  costs contributed  by  each  of the  12  cost
 categories.    All  variables  except   total  amount  of
 contaminated soil  are  held constant.   In  particular, all
 three estimates utilize a 3.3 tph cyclone furnace and a 60
 percent online factor.  If the 3.3 tph  cyclone  furnace is
 used to remediate  a site containing less than 20,000 tons
 of contaminated   soil   (all  other variables   remaining
 constant), the startup and fixed costs will become more of
 a factor. Unit costs derived from startup and from fixed
 expenses  will  be  higher, but  unit  costs  derived  from
 operating expenses will remain approximately  the same.
 Variations hi the impacts of the 12 cost categories can be
 seen in Tables  10 and 11.

 For example, if this system is applied to a site containing
 10,000 tons of contaminated soil, the unit treatment costs
 (using a 60 percent online factor) are estimated at $601
per ton of soil. If the 3.3 tph cyclone furnace is used at a
 site containing  over 20,000 tons of contaminated soil (all
 other variables remaining constant), the startup and fixed
costs will become less of a factor. Unit costs derived from
startup and from fixed expenses will be lower, but unit
costs   derived  from operating expenses  will  remain
approximately the same.  For example, if  this  system is
applied to the  remediation of a site containing 100,000
tons of contaminated soil,  the unit treatment costs (using
a 60 percent online factor) are estimated at $472 per ton
of soil.
  Table 10. Treatment Costs  for 3.3 tph Cyclone  Furnace
           Vitrification System Operating with a 60% Online
           Factor
   Item
 10,000
  tons
Cost (S/tonl

  20,000
   tons
 100,000
  tons
   Site Preparation            31.37

   Permitting and
   Regulatory Costs             —

   Equipment Cost Incurred     50.46

   Startup and
   Fixed Costs               109.90

   Labor                   219.95

   Supplies                    2.02

   Consumables              157.96

   Effluent Treatment
   and Disposal                —

   Residuals Shipping,
   Handling and Transport       —

   Analytical Costs             —

   Facility Modification, Repair
   and Replacement
          31.37    31.37
          43.83    38.53


          58.67    17.69

         219.95   219.95

           2.02     2.02

         157.96   157.96
   Site Demobilization

   Total Operating Costs
  1.24

 27.67

600.57
    1.24

   13.83

  528.88
  1.24

  2.77

471.53
It will take over 8 years to remediate a site containing
100,000 tons of contaminated soil with the 3.3 tph system.
For this volume of  soil, a larger  unit  would be  more
appropriate. Although B&W does not currently have any
plans to construct a larger  system,  a preliminary cost
estimate was prepared for a system capable of treating 20
tph of contaminated soil.

Table 12 compares estimated unit treatment costs for the
use of 3.3 tph and 20 tph systems at a site containing
100,000 tons of contaminated soil, while Table 13 shows
the percentage of the treatment costs contributed by each
of the 12 cost  categories.  All variables except feed rate
are held constant. In particular, both estimates utilize a 60
percent online  factor.  This preliminary analysis indicates
that it will cost  $505 per ton to remediate a site containing
100,000 tons of contaminated soil using the 20 tph system
(assuming a 60 percent online factor). When the larger
system  is  used,  the  treatment tune is approximately
1.3 years and the equipment is onsite for approximately
1.6 years.   Transportation  and  onsite assembly of the
larger unit, however, could present difficulties.
                                                       21

-------
   Table 11. Treatment Costs as % of Total Costs for 3.3
           tph Cyclone Furnace Vitrification System
           Operating with a 60% Online factor
                              Cost (as % of total cost)
Item
Site Preparation
Permitting and
Regulatory Costs
Equipment Cost Incurred
Startup and Fixed Costs
Labor
Supplies
Consumables
Effluent Treatment
and Disposal
Residuals Handling and
Transport
Analytical Costs
Facility Modification,
Repair and Replacement
Site Demobilization
Total Operating Costs
10,000
tons
5.2
—
8.4
18.3
36.6
0.3
26.3

—
—
—
0.2
4.6
100.0
20,000
tons
5.9
—
8.3
11.1
41.6
0.4
29.9

—
—
—
0.2
2.6
100.0
100,000
tons
6.7
—
8.2
3.8
46.6
0.4
335

—
—
—
0.3
0.6
100.0
Table 12. Treatment  Costs for the  Remediation of 100,000
         Tons of Contaminated Soil Using Cyclone Furnace
         Vitrification System Operating with a 60% Online
         Factor
                                                                                                   Cost (S/ton)
                                                                  Item
                             3.3 tph
                             System
20 tph
System
                                                                  Site Preparation                31.37          31.37
                                                                  Permitting and
                                                                  Regulatory Costs                —           —
                                                                  Equipment Cost Incurred         38.53          24.62
                                                                  Startup and Fixed Costs          17.69          46.06
                                                                  Labor                        219.95          90.73
                                                                  Supplies                        2.02           2.02
                                                                  Consumables                  157.96         303.19
                                                                  Effluent Treatment
                                                                  and Disposal                   —           —
                                                                  Residuals Shipping,
                                                                  Handling and                   —           —
                                                                  Transport
                                                                  Analytical Costs                —           —
                                                                  Facility Modification,
                                                                  Repair and  Replacement          1-.24           0.68
                                                                  Site Demobilization              2.77           6.57
                                                                  Total Operating Costs          471.53         505.24
The costs excluded from this cost analysis are described in
subsections 4.3 and  4.4.  This analysis does not include
values for 4 of the 12 cost categories, so the actual cleanup
costs incurred by the site owner or responsible party may
be significantly higher than the costs shown hi this analysis.
4.6     References

1.  Peters, M.S. and Timmerhaus, K.D. Plant Design and
    Economics for Chemical Engineers; Third Edition;
    McGraw-Hill, Inc: New York, 1980.

2.  U.S. Environmental Protection Agency Office of Air
    Quality  Planning  and Standards.    Cost  Control
    Manual. PB90-169954.  January,  1990.
 Table 13. Treatment Costs as Percentages of Total Costs for
         Cyclone  Furnaces  Treating  100,000  Tons  of
         Contaminated Soil
                              Cost (as % of total cost)
                                3.3 tph       20 tph
                                                                   Item
                                                                                                system
                                            system
  Site Preparation                 6.7          6.2
  Permitting and Regulatory
  Costs                          —          —
  Equipment Cost Incurred          8.2          4.9
  Startup and Fixed Costs           3.8          9.1
  Labor                          46.6          18.0
  Supplies                        0.4          0.4
  Consumables                    33.5          60.0
  Effluent Treatment and           —          —
  Disposal
  Residuals Handling and           —          —
  Transport
  Analytical Costs                 —          —
  Facility Modification, Repair       0.3          0.1
  and Replacement
  Site Demobilization              0.6          1.3
  Total Operating Costs            100.0         100.0
                                                             22

-------
                                            Appendix A
                                      Process Description
 A.1    Introduction
 The  B&W  cyclone  furnace  technology is  a well-
 established design for coal combustion.   Previous
 applications  of this  technology to municipal solid
 waste (MSW) ash containing heavy metals led to its
 use on metals-contaminated soils  that also contain
 organic constituents.  B&W's cyclone furnace is an
 innovative  thermal  technology which may  offer
 advantages in treating soils containing organics, heavy
 metals, and/or radionuclide contaminants.  The pilot
 scale  unit  used  during the  SITE  demonstration
 simulates typical full-scale commercial cyclone boilers
 being used for steam generation in power plants.

 The  demonstration  was conducted to  evaluate the
 ability  of the  B&W cyclone  furnace to  vitrify
 contaminated soil and waste (liquids and solids). The
 process was demonstrated using an SSM provided by
 the EPA's Risk Reduction Engineering Laboratory in
 Edison, New Jersey.  SSMs are well-characterized,
 clean   soils  which   are   spiked  with   known
 concentrations of specified contaminants.
A.2     The Cyclone Furnace

The pilot unit, shown in Figure A-l, is a scaled-down
version  of  a B&W commercial coal  combustion
cyclone  furnace.   The furnace  is watercooled  and
similar  to  B&W's single  cyclone, front-wall fired
cyclone burners. It has a 6-million Btu/hr heat input.

For the demonstration, natural  gas was introduced
into the cyclone furnace.  Preheated combustion air
(nominal 800°F) entered tangentially into the cyclone.

The feed SSM was  introduced  via a soil disperser
(atomizer)  at the center of the cyclone.  The  gas
exiting  the  cyclone  barrel  had  a temperature of
approximately 3000°F while the gas exiting the upper
furnace had  a temperature over 2000°F with a 2-
second residence time.
 The energy requirements for vitrification of the SSM
 were 15,000 Btu/lb. Given the much larger surface
 area-to-volume ratio of the pilot unit, one may expect
 a full-scale unit to achieve lower energy requirements.
           STACK PARTICULATE
           SAMPLING LOCATION
     SSM FEED
     SYSTEM
       CONTINUOUS EMISSIONS
       MONITOR (CEM)
       SAMPLING LOCATION
SSM
SAMPLING
LOCATION
 SLAG AND
 QUENCH
 WATER
 SAMPLING
 LOCATION
                      ID FAN
BAGHOUSE

 HEAT
 EXCHANGER
                                                    FURNACE
                                                    STACK
                                         NATURAL
                                         GAS
                                        SOIL
                                        INJECTOR
                       1  \SLAG  ^CYCLONE
                          SPOUT   BARREL
                     -SLAG
                      QUENCHING
                      TANK
Figure A-l. Cyclone Test Facility.
                                                 23

-------
The cyclone is designed to achieve very high  heat
release   rates,   temperatures,   and   turbulence.
Participate matter from the soil stream is retained
along the walls of the furnace by the swirling action of
the  combustion air and  is  incorporated into  the
molten  slag layer.  Organic  material in the soil is
vaporized or combusted in the molten slag. The slag,
which has a temperature of 2400°F,  exits the cyclone
furnace from a tap at the  cyclone throat and drops
into a  water-filled tank  where  the  material is
quenched. A small portion of the soil exits as flyash
in the flue gas and is collected hi a baghouse.  A heat
exchanger cools stack  gases to approximately 200°F
before they enter the baghouse. The cyclone facility is
also equipped with a  scrubber  to control any acid
gases that maybe generated.  For this demonstration,
the  scrubber  was not required since  chlorinated
compounds were not spiked into the SSM.
The SSM was delivered onsite in 55-gallon drums and
fed to the system by connecting the SSM transport
drum to the feed cone. A system of dust-free valves
was opened to allow a screw feeder to transfer the soil
to the cyclone feed hopper. A screen above the feed
hopper removed oversized materials and a mixer kept
the SSM from settling in  the feed hopper.   After
passing the screw feeder,  the soil was  fed  to the
furnace pneumatically, utilizing a small fraction of the
combustion air.

A variety of sampling ports and instrument monitors
were fitted  to the pilot unit. A system of stairways
and walkways provided  access to  all required gas
stream sampling points.
                                                   24

-------
                                                 Appendix B
                                              Vendor's  Claims
B.I   Site Demonstration Vendor's Claims

The  effectiveness  of   the   B&W   Cyclone  Furnace
Vitrification  Technology at  destroying  organics and
immobilizing heavy metals and simulated radionuclides in
a  non-leachable slag was evaluated  during  the SITE
Demonstration. To perform this evaluation, the following
critical and non-critical Vendor's Claims were  developed
by Babcock & Wilcox, based on discussions with the U.S.
EPA, for evaluation in the Demonstration.  These claims
are presented in Table B-l.
B.2   Comparison of Performance Results from
       the  Two  SITE  Emerging  Technologies
       Projects with the Vendors Claims

B.2.1  Synthetic Soil Matrix and Feed Conditions

Two Superfund Innovative Technology Evaluation (SITE)
Emerging Technology projects were conducted prior to the
SITE Demonstration.  These  two projects, Phase  I and
Phase II, were conducted to establish the feasibility of the
cyclone vitrification process for dry soil (Phase I) and wet
soil (Phase II) treatment.  In each project, measurements
were made  to  evaluate  TCLP  leachabilities,  volume
reduction, and materials and heavy metals mass balances.

A synthetic soil matrix formulated by EPA was used for all
cyclone testing. Both clean and spiked SSM were obtained
from the EPA Risk Reduction  Engineering Laboratory
(RREL) Releases Control Branch in Edison, NJ.  SSM,
used by EPA  for treatment technology evaluations, has
been well-characterized in previous studies [1]. Clean soil
was used for furnace conditions optimization. The spiked
SSM   used  in  the  Emerging  Technologies  projects
contained 7,000 ppm (0.7 percent) lead, 1,000 ppm (0.1
percent)  cadmium,  and  1,500  ppm  (0.15  percent)
chromium.
  Table B-l.   B&W Claims for Cyclone Vitrification Technology
  Parameter                          Claim
  Critical
    TCLP               Produce a vitrified slag that does not
                        exceed Toxicity Characteristic
                        Leaching Procedure (TCLP) regula-
                        tory levels for cadmium (i.e., < 1
                        mg/L), lead (<5 mg/L), and
                        chromium (<5 mg/L).
                        Achieve at least a 10 to 1 ratio (dry
                        weight basis) of slag to flyash.
                        Capture at least 60% (by weight) of
                        the non-volatile metal chromium
                        from the dry, untreated SSM in the
                        vitrified slag.
                        Achieve at least a 25 percent volume
                        reduction in solids when comparing
                        product solid to untreated SSM.
                        Achieve a 99.99% destruction and
                        removal efficiencies DREs for each
                        organic contaminant spike
                        (anthracene and dimethylphthalate).
                        Comply with emission limits for CO,
                        total hydrocarbons (THC), and
                        particulates from the stack as
                        stipulated by 40 CFR 264 (i.e., CO
                        of <100 ppm, THC of <20 ppm,
                        and particulates of <0.08 gr/dscf at
                        7% oxygen).


                        Produce a slag that immobilizes
                        (passes leaching standards)
                        radionuclides as measured by the
                        American Nuclear Society test
                        (ANS) 16.1 (i.e., ANS 16.1 calculated
                        teachability index (LI) >6).
                        Capture at least 60% (by weight) of
                        the non-volatile metals strontium
                        and zirconium in the vitrified slag.
  Slag to Flyash Ratio

  Non-Volatile Metals
  Capture (Cr) in the
  Slag

  Volume Reduction
  DREs
  CO, THC, Particulates
Non-Critical
  ANS 16.1 Simulated
  Radionuclide
  Leachability
  Non-Volatile
  Radionuclide Capture
  in the Slag
In Phase I, dry SSM was processed at feed rates of 50 to
150 Ib/hr.  In Phase II, wet SSM was processed at
feed rates of 100 to 300 Ib/hr (dry basis).
                                                        25

-------
Approximately 11 tons of spiked and unspiked SSM were
processed during each of the two project Phases.
B.2.2  Performance Results

A comparison of Phase I and  II  results against  the
Vendor's  Claims developed for  the Demonstration is
presented in Table B-2.  Not ah1 of the Demonstration
claims were tested during these projects (e.g., DRE, ANS
16.1 were omitted).   All  claims tested were  met  or
exceeded during these Emerging Technology projects (the
Claims were finalized on the basis of these results).

Table B-2.    Phase I & Phase II Performance vs. Vendor Claims


Parameter
TCLP-Cadmium
TCLP-Lcad
TCLP-Chromlum
Slag to Flyash
Ratio
Non-Volatile
Metal (Or)
Capture in the
Slag
Volume Reduction
Performance Performance
Criterion in Measured in
Vendor's Claim Phase 1°
< 1.0 mg/L 0.13 mg/L
< 5.0 mg/L 0.20 mg/L
< 5.0 mg/L 0.11 mg/L
> 10:1 14.6:1
> 60% 80-95%

>25% 35%
Performance
Measured in
Phase II"
0.07 mg/L
0.20 mg/L
0.04 mg/L
34:1
78-95%

25%
a Average results where several measurements were made.
B.3 Compar
ison of Performance Rt
ssultsfrom
       the SITE Demonstration with the Vendors
       Claims

B3.1  Synthetic Soil Matrix and Feed Conditions

On the basis of the Phase I and II Emerging Technology
projects, Babcock & Wilcox was asked to perform a SITE
Demonstration.  For the Demonstration, a wet SSM was
used.  Demonstration goals included the vendor's claims
given above.

The SSM used in the SITE Demonstration contained 7,000
ppm lead, 1,000 ppm cadmium, and 4,500 ppm chromium;
6,500 ppm anthracene; 8,000 ppm dimethylphthalate; and
the three simulated radionuclides:  4,500 ppm bismuth,
4,500 ppm  strontium, and 4,500 ppm  zirconium.  The
rationale for B&Ws choice of radionuclide surrogates is
as follows:  Bismuth was used as a surrogate for volatile
radionuclides important at DOE/DOD  sites  such  as
cesium (cold cesium was originally proposed but found to
be excessively expensive).  Cold strontium was used as a
surrogate for radioactive strontium (the cold version of the
radionuclide is the best possible  surrogate).   Zirconium
was  considered an excellent surrogate for radioactive
thorium and uranium from the standpoint of both volatility
and chemical behavior (all are oxophillic and tend to be in
the +4 oxidation state).

A total of 3 tons of  SSM were processed during the
Demonstration at a feed rate of 170 Ib/hr.
B3.2  Performance Results

A comparison of the Demonstration results against the
Vendor's  Claims developed  for  the  Demonstration  is
presented in Table B-3. AH claims tested were exceeded
during the Demonstration.

Table B-3.   SITE Demonstration Performance vs. Vendor Claims
                                                          Parameter
                      Performance      Performance
                       Criterion in      • Measured
                     Vendor's Claim   in Demonstration"
TCLP-Cadmium
TCLP-Lead
TCLP-Chromium
Slag to Flyash Ratio
Non-Volatile Metal
(Cr) Capture in the
Slag
Non-Volatile Metal
(Sr) Capture in the
Slag?3
Non-Volatile Metal
(Zr) Capture in the
Slag>
Volume Reduction
DRE-Anthracene
DRE-
Dimethylphthalate
CO
THC
Participates
< 1.0 mg/L
< 5.0 mg/L
< 5.0 mg/L
> 10:1

>60%

> 60%

> 60%
>25%
> 99.99%
> 99.99%

<100 ppm
<20 ppm
< 0.08 gr/dscf3
0.12 mg/L
0.29 mg/L
0.30 mg/L
15.6:1

76%

88%

96%
28.1%
> 99.996%
> 99.998%

4.8-54.1 ppm
<5.9-18.2 ppm
0.001 gr/dscf
 ANS 16.1 Leachability-
 Bismuthb

 ANS 16.1 Leachability-
 Strontiumb

 ANS 16.1 Leachability-
 Zirconiumb
LI > 6
LI > 6
LI > 6
LI = 13.4
LI = 13.1
LI = 8.7
  a        Average results where several measurements were
          made.
  b        Non-critical parameter.
  c        Corrected to 7 percent oxygen.
                                                      26

-------
B.4   Summary

The Babcock & Wilcox  6-million  Btu/hr pilot cyclone
furnace met or exceeded all  critical and  non-critical
Vendor's Claims. Because these performance results were
measured on a pilot cyclone furnace configured as a utility
boiler, and by no means optimized for soil vitrification, a
unit designed for dedicated soil vitrification may improve
process performance and  throughput.
B.5  Reference

1.     P. Esposito, J. Hessling, B. Locke, M. Taylor, M.
      Szabo, R. Thurnau, C. Rogers, R. Traver, and E.
      Barth, "Results  of Treatment  Evaluations of a
      Contaminated Synthetic  Soil,"  JAPCA.  39: 294
      (1989).
                                                    27

-------
                                              Appendix C
                                   SITE Demonstration Results
C.1    Introduction

This  appendix summarizes  the  results  of  the SITE
Demonstration Test  of the B&W  Cyclone  Furnace
Vitrification Technology.  These results are also discussed
in Section 3 of this report. A more detailed account of the
demonstration may be found in the TER.

During the demonstration, the effectiveness of the process
was evaluated by conducting three identical runs using a
B&W pilot-scale  unit (Runs 1,  2, and 3).  In addition, a
background run  was conducted  to  determine baseline
conditions  (Run 0). Sampling of the feed SSM and waste
streams was performed in accordance with the procedures
outlined in the Demonstration Plan.

The  emphasis of  a SITE  demonstration is  for the
technology to meet ARARs. The ability  of the cyclone
furnace to destroy semivolatile organics and immobilize
heavy metals and simulated radionuclides into a non-
leachable  slag   was  evaluated.    Results  from  this
demonstration include  TCLPs  of  the  slag, metals
partitioning, DREs, and emissions from the technology.
The concentration of contaminants hi the quench water
and baghouse solids, as well as the slag-to-flyash ratio,
volume reduction, radionuclide  teachability from the slag,
and SSM characteristics are also addressed.

Data  regarding  simulated  radionuclides are suspect
because the method has not  been validated  for these
metals. Since the method's accuracy and precision are not
well quantified, the data are used for information purposes
only.
 C.2    Slag Characteristics

 During  the demonstration,  94 percent  of the  non-
 combustible portion  of the feed was  transformed  from
 loosely  packed soil  to a brittle, glass-like  slag.  The
 remaining 6 percent of the non-combustible feed was re-
leased hi the flue gas as particulate matter. By comparing
the particulate emission rate from the furnace
outlet with the amount of slag produced per hour by the
cyclone furnace, a  relative measure of slag and  flyash
production can be calculated.  This "slag-to-flyash ratio" is
a comparative measure of solids generation and is  calcu-
lated by dividing the mass of the slag (dry weight) by the
mass of the flyash  (dry weight).   Average slag-to-flyash
ratios of 14.5, 13.7, and 12.9 were obtained for Runs 1, 2,
and 3, respectively.  These results are consistent with
Demonstration Test objectives and support B&W's claim
that a greater than 10:1 ratio of slag-to-flyash ratio can be
achieved using the cyclone furnace.
C.2.1   Leachability

TCLPs were  performed  on both  the feed SSM  and
vitrified  slag.   The  teachabilities  obtained for these
materials are summarized  hi  Table  C-l.   Significant
reductions were experienced for all the metals, particularly
cadmium and lead, which were brought into compliance
with regulatory limits as a result of cyclone vitrification
treatment. The data demonstrate the cyclone furnace can
immobilize  cadmium,  chromium,   and lead  so  that
regulatory compliance is achieved.

To verify that decreases in teachability are due to changes
in the leaching behavior of the soil, and not due to lower
concentrations  of metals  hi  the  slag,  the  percent
teachability of metals in the SSM and slag was determined
by dividing the amount of each heavy metal which leached
during the TCLP test from the SSM  and slag by the  total
amount  of each heavy metal which could be leached.
These percent leachable metals are listed in Table C-2 and
are based on  average results for the  demonstration.  The
results indicate the vitrification process  decreases the
leachability hi the slag by changing the physical/chemical
behavior of the soil.

ANS  Method   16.1   (American   National   Standard
Measurement of the Leachability of Solidified Low-Level
Radioactive Wastes by a Short-Term Test Procedure) was
                                                      28

-------
 Table C-l.
Average TCLF Results from B&W SITE Demonstration
Runs1' (mg/L)
                    Cadmium   Chromium
                                          Lead
SSM
Runl
Run 2
Run3
Slag
Runl
Run 2
RunS

52.0
63.6
34.2

<0.11»
0.19
0.07

2.29
1.77
3.87

0.15
0.37
0.15

90.8
75.6
125

<0.25
<0.39b
<0.29b
 a       Average values were calculated from nine individual samples
        collected over course of each run.

 b       If result was  undetected, the detection limit was used in
        calculations for averages. This represents worst case scenario.


 Table C-2.        Percentage of Leachable  Metals from B&W
                Cyclone Furnace
                            Metal Leached
                  Total       from lOOg
Heavy Metals
SSM
Cadmium
Chromium
Lead
Slag
Cadmium
Chromium
Lead
Metal in lOOg
sample
(nig)

126
435
641

10.6
161
176
sample in TCLP
Test
(mg)

99.8
5.28
195

0.24
0.44
0.62
% of Metal
Present That
Leached

79
1.2
30

2.3
0.27
0.35
used to determine the  leachability  of the simulated
radionuclides strontium, zirconium, and bismuth from the
slag generated  during  the SITE demonstration.   The
method was modified to account for the irregular shape of
the slag.

Although  all  other  equations  and  data  reduction
procedures remain the  same, the method accuracy and
precision are not well quantified because the method has
not been verified for the slag and the  data are therefore
suspect. Results from the ANS  method are reported as a
leachability index and presented in Table C-3.
C22   Volume Reduction

Combustion  of any carbonates, sulfates,  and  organics
present hi the SSM contributed to the volume reduction
experienced during the Demonstration Test. The percent
Table C-3.
Slag
Runl
Range
Mean
Run 2
Range
Mean
Run3
Range
Mean
Leacha
Bismuth
12.9-13.7
13.2
13.5-14.2
13.8
123-14.0
13.3
ibilify Index of Sim
Strontium
12.1-13.6
12.9
12.8-13.7
13.3
11.6-14.0
13.0
ulated Radionuclii
Zirconium
8.2-8.8
8.6
8.2-9.4
8.7
8.3-9.0
8.7
                                              volume reduction of dry SSM after treatment (as deter-
                                              mined by the volume of slag produced) was computed
                                              according to the following equation:
                                              Percent Volume Reduction =    Vf - Vs
                                                                                    X100%
                                              Where:
                                              Vf      =      Volume of the SSM feed on a dry weight
                                                             basis

                                                             Mass of the feed (dry basis) used for the
                                                             run  divided by the bulk density of the
                                                             feed

                                              Vs      =      Volume of the slag on a dry weight basis

                                                      =      Mass of the slag produced for  the run
                                                             divided by the bulk density of the slag

                                              The bulk density of the slag was initially analyzed using
                                              the American Society for Testing and Materials (ASTM)
                                              method for specific gravity (ASTM D854 Test Method for
                                              Specific Gravity of Soil). This method defines the specific
                                              gravity as the ratio of the mass of a unit volume of soil to
                                              the mass of the same volume of water.  The result  from
                                              this analysis could not be effectively employed in  calcula-
                                              tions using the bulk density values obtained for the feed.

                                              The feed was re-analyzed using a method B&W developed
                                              for determining bulk density.  This method determines
                                              bulk density by weighing  the soil in a box  of known
                                              volume.  Bulk density is calculated as follows:

                                              Bulk density in lb/ft3 = Wt - W0

                                             Where:
                                                                                     V
                                                     V =    Volume of the box in ft3

                                                     Wj =   Weight of the box with sample in pounds

                                                     W0 =   Original weight of the box in pounds
                                                      29

-------
This method was also used to determine bulk density of
the slag. Although the accuracy of the data obtained using
this non-standardized method is questionable, comparisons
between the SSM and slag data provide reliable results.

Table C-4 lists the percent volume reductions achieved
using the slag bulk  density values  from the ASTM and
B&W methods. The negative values for volume reduction
calculated using the ASTM generated values for the slag
specific  density  are inconsistent with  both  testing
expectations and field observations. The results obtained
using  the B&W  data,   however, agreed with  field
observations  and Demonstration Test  objectives.  These
results confirm B&Ws claim that an average of 25 percent
reduction in the volume is experienced during treatment.
Table C-4.
Method of
Bulk Density
ASTM
B&W
Volume Reduction (%)
Run 1
-43.8
31.2
Run 2
-32.7
32.0
Run3
-49.7
23.5
Avg
-42.0
28.9
 C.3    Metals Partitioning

 The fate of a metal spiked within the SSM was dependent
 on the relative volatility of the metal.  The majority of the
 metals spiked within the SSM were either captured within
 the slag or the flyash; however, a small portion did escape
 to the ambient air. Metal emission data are presented in
 Table C-5.
  Table C-5.
    Run
    No.
      Summary of Metals Emissions
                             Emission rate (Ib/h)
Location
Cd
Cr
                                 Pb
           Furnace
           Outlet

           Stack

           Furnace
           Outlet

           Stack

           Furnace
           Outlet

           Stack
           7.4xlO'2    4.3xlO'2     3.6x10-'


           3.8xlO-s    5.8xlO'5     1.2X10-4

           7.9xlO'2    4.4xlO'2     4.2x10-'
                     1.9X10"
                                ZlxlO"4
           7.8xlO'2    6.4xlO'2.     4.7x10''


           9.4x10-*    2.1xlO'5     4.8xlO'5
 Percent retentions in the slag of the metals initially present
 within the SSM were evaluated by comparing the total
                                             mass of metals hi the SSM to the total mass of metals in
                                             the slag.

                                             These  values were  determined  using  the following
                                             equation:
                                             Percent Metal Retention =

                                             Where:

                                             pP
                                                                   MSi
                                                                 MPi + MSi
                                                                    xlOO%
                                            =   Percentage of non-combustible SSM that
                                                becomes furnace outlet participate

                                            =   Furnace outlet particulate emission rate
                                                divided by the non-combustible portion
                                                of the feed
                                             pS         =   Percentage of non-combustible SSM that
                                                             becomes slag

                                                         =   100% - pP

                                             MPi        =   Percentage of metal  of  interest  in the
                                                             furnace outlet particulate

                                                         =   pP x concentration of metal of interest in
                                                             furnace outlet particulate

                                             MSi        =   Percentage of metal  of  interest  in the
                                                             slag material

                                                         =   pS x concentration of metal of interest in
                                                             slag

                                             MPi + MSi =   Percentage of metal of interest in SSM
Table 5 in Section 3 lists the percent metal retention of
the six metals spiked in the SSM. On the average, over 75
percent of the chromium was incorporated in the vitrified
slag.  This supports B&W's claim that greater than 60
percent of the chromium (by weight) would be trapped
within the vitrified slag.  Approximately 88 and 97 percent
of  the  strontium  and  zirconium,  respectively,  were
captured within the slag. These results are consistent with
the non-volatile nature of these metals.  The more volatile
bismuth, cadmium,  and lead experienced lower captures.
The bulk  of these metals partitioned to the flue gas and
were eventually captured by the baghouse.

Comparisons between the emissions entering the baghouse
from the  furnace outlet  and exiting the stack yield an
average particulate removal efficiency of 99.89 percent.
The majority of the metals exiting the furnace in the flue
gas  are captured within the baghouse, although  small
amounts were detected in the stack gas.
                                                       30

-------
 C.4    Air Emissions
                                 Where:
 C.4.1    Particulate

 Participate emissions were measured at the furnace outlet
 prior to the air pollution control devices and at the stack
 for  all  runs.   Particulate  emissions  out of the stack
 averaged 0.0008 gr/dscf (corrected by 7 percent O2), or
 0.01 Ib/hr, which is well under the RCRA regulatory limit
 of 0.08 gr/dscf.  Average particulate emissions from the
 furnace outlet were 0.806 gr/dscf (corrected to 7 percent
 O2),  or 6.07 Ib/hr.   Before  furnace outlet emissions
 reached the stack, they were controlled by a baghouse,
 which had an average removal efficiency of 99.89 percent
 efficiency.  Table 6 in Section 3 summarizes particulate
 testing during the demonstration.

 CA2    ORE

 In addition to producing a slag capable of retaining a high
 percentage  of  the heavy metals, the  cyclone   furnace
 achieved the organic destruction efficiency required  of
 RCRA hazardous waste incinerators (99.99 percent).  By
 comparing  the  concentrations  of  the spiked   organic
 contaminants, anthracene and dimethylphthalate,  present
 in the SSM to their concentrations in the stack gas, DREs
for these compounds were calculated as follows:
                                   W.
                                   in
                                 W.
                                   out
Mass feed rate of the POHC of interest
in the waste stream feed to the furnace

Mass emission rate of the same POHC
present in  exhaust emissions  prior to
release to the atmosphere
                                 As listed in Table C-6, the cyclone furnace was capable of
                                 removing greater than 99.99 percent of both anthracene
                                 and  dimethylphthalate.    Because these  organics  are
                                 relatively difficult to  destroy,  it is projected  that  the
                                 commercial-scale  cyclone furnace  will  be  capable  of
                                 achieving DREs of at least 99.99 percent for all or nearly
                                 all organics.
Table C-6.
Compound
Anthracene
Dimethyl
phthalate
DREs
Run 1
> 99.996
> 99.998
(%)
Run 2
> 99.997
> 99.998

Run3
> 99.996
> 99.998

Average
> 99.997
> 99.998
DRE(%)  =
                            xlOO%
                     'in
                                C.43    PICs

                                VOC  concentrations were  measured by the  Volatile
                                Organic Sampling Train (VOST) analysis.  Average VOC
                                concentrations are presented in Table C-7. Run 0 data
            Table C-7. Summary of Volatile Organic Concentrations in Stack Gas from B&W SITE Demonstration (pg/m3)8
                            TriPu                                      Field Blank
     Compound
Blankb
             RunO
                                                        Run 1
                                                                       (Run 1)

Chloroethane
Methylene chloride
Acetone
Carbon Disulfide
Chloroform
1,1,1-Trichloroethane
Carbon tetrachloride
Trichloroethene

Benzene
Tetrachloroethene
Toluene
Ethylbenzene
Total xylenesh

c
0.40
c
1.45
d
d
d
d

d
d
d
d
0.85

c
<0.25-1.15f
<050-2.50f
d
0.48-0.70
0.48-0.73
d
d

1.06-3.47
1.41-2.23
1.22-8.32
0.67-554 !
3.04-20.4

c
2.95-3.69
<0.50-5.896
<0.25-10.2f
<0.25-0.45e
29.8-31.4
<0.25-3.81e
d

2.02-2.78
1.01-1.12
1.79-4.85
<0.25-0.91f
0.63-1.92

c
2.20
0
2.20
d
d
d
d

d
d
0.25
d
0.70
<0.50-1.51e
< 0.50-0.96°
0.81-5.26
c
<0.25-1.28e
<0.25-0.37f
14.4-18.7
< 0.25-1.60°

0.25-0.27
1.26-2.34
0.84-1.01
1.32-1.76
< 0.25-0.26°
0.64-1.26
<0.50-1.85a>S
c
1.01-20.8
<050-41.1f
<0.25-1.61f
<0.25-0.42e
<0.25-20.2f
<0.25-2.52°
d

1.44-7.29
<0.25-0.94f
0.72-2.71
0.25-051
1.41-2.06
       No field blank was taken for Run 0.  No compounds were detected in the lab blanks and field blanks for Run 2/3.
       Concentrations are based on a sample volume of 20L.
       Not detected. Detection limit 050 fig/m3.
       Not detected. Detection limit 0.25/tg/m3.
       Emissions were detected in 1 out of 3 samples.
       Emissions were detected in 2 out of 3 samples.
       An estimated 15 mg was detected in the lab blank during this analyses; however, it was less than the specified detection limit
       The laboratory indicated that painting activities during the VOST analysis time period may have contributed to xylene contamination
       in the samples at levels similar to those detected in the trip and field blank. All other xylene levels may be biased slightly high
                                                       31

-------
represent VOC concentrations when natural gas only was
fired. Although no chlorinated compounds were spiked in
the SSM, several chlorinated  VOC  compounds  were
detected in the stack gas.  In order to account for these
chlorinated compounds, the feed SSM was analyzed for
trace levels of chlorine.  The chlorine levels ranged from
<0.01 percent to 0.03 percent.  These trace amounts may
have resulted in the formation of chlorinated VOCs.
C.4.4   CEMs

CEMs were used to measure NO,, CO, THC, CO* and
O2 emissions during the Demonstration Test.  CEM data
are summarized in Tables C-8 and C-9.  CEM data for
CO2 and O2 compare favorably with values obtained from
Orsat analysis. These data reflect typical excess air values
for a natural gas-fired furnace.
C.5    Quench Water

The quench water was tested to determine if any of the
metals or semivolatile organics present in the slag or
infusible matter leached into the quench water.

Concentrations of cadmium, chromium, and lead were
detected and are listed in Table C-10.  It appears these
concentrations increased after Runs 1 and 2. Since many
of the readings are close to or below analytical detection
limits and method quantitation limits, the significance of
these increases is minimal, however. Concentrations of
semivolatiles,  bismuth,  and  zirconium  are considered
insignificant, since they were at  or  below the  analytical
detection limits and method quantitation limits.
  Table C-10.       Quench  Water  from  B&W  SITE
                 Demonstration
Table C-8. Summary of NOX, CO, and THC CEM Data
Concentration (ppm •
Run No. Value
1 Average
Low
High
2 Average
Low
High
3 Average
Low
High
NOX
357
328
373
338
310
423
383
311
435
- dry basis)
CO THC as CjHg
>6.1
4.8
>54.1
6.9
6.3
7.4
5.0
4.9
5.2
<7.4
<6.9
8.4
11.3
8.9
18.2
<6.4
<5.9
8.1
Cadmium Chromium Lead
Oig/L) Og/L) Og/L)
Before Run 0 <3.0
After Run 0 <3.0
Before Run 1 6
After Run 1 11
Before Run 2 <3.0
After Run 2 (4)
Before Run 3 (4)
After Run 3 (4)
Notes:
1. Values given as less than (<) a
the instrument detection limit;
<7.0 <25
<7.0 <25
18 <25
26 31
<7.0 <25
16 41
16 41
10 <25

certain quantity were below
the quantity given is the
detection limit.
1 x/nl.mp in *-»o*ja«tV\*»cAc r/»T»i-pcpnt MptitifipH jmalvtcs with
estimated values that are above instrument detection limits




but below method quantitation
limits.
Table C-9. Summary of CO2 and O2 CEM Data
Concentration (%)
Run No. Value CO2 O2
1


2


3


Average
Low
High
Average
Low
High
Average
Low
High
9.2
8.8
9.5
8.9
8.2
11.8
9.6
9.6
9.7
4.9
4.6
6.5
4.9
4.4
5.2
4.9
4.8
5.1
                                                      32

-------
                                           Appendix D
                                          Case  Studies
D.I    Municipal  Solid  Waste (MSW) Ash
        Testing

The cyclone furnace was  used in a research and
development project to vitrify MSW ash containing
heavy  metals.   The cyclone furnace  produced  a
vitrified MSW ash which was below EPA leachability
limits  for  all  eight  of  the RCRA metals.   The
successful treatment of MSW ash suggested that the
cyclone furnace could  treat high-inorganic-content
hazardous  wastes  and contaminated soils that also
contain  organic  constituents.    These  types  of
wastes/soils exist at many Superfund sites, as well as
at sites where petrochemical and chemical sludges
have been disposed.

The suitability of the  cyclone vitrification technology
relies on the premise that for acceptable performance
in  treating hazardous  waste  mixtures containing
organic and heavy metals  constituents,  the cyclone
furnace must melt the SSM while producing a non-
leachable  slag.   It  must  also  achieve the DREs
(currently 99.99%) for organic contaminants normally
required for RCRA  hazardous waste incinerators.
The high temperature (over 3000°F), turbulence, and
residence time  in the cyclone and main furnace are
expected to achieve high organics DREs.
D.2    Emerging Technologies
        Testing

D.2.1   Introduction

The B&W Cyclone Vitrification Furnace was initially
evaluated for the treatment of heavy- metal-contami-
nated soil under the EPA's SITE Emerging Technolo-
gies Program. The sampling and analysis program for
this test was conducted  by B&W.  The  favorable
results  of  that  two-part   study  led to B&W's
participation in the present Technology Demonstration
Program.
 The Emerging Technology tests took place during the
 fall of 1990 and summer of 1991.  These tests were
 designed to evaluate whether the 4 to 6-million Btu/hr
 B&W cyclone furnace located at the B&W Alliance
 Research Center in Alliance, Ohio was capable of
 treating  soils contaminated with heavy metals  The
 same  pilot-scale unit  was  employed  during this
 Technology   Demonstration  Test,  with   minor
 modifications to the feed system.
 D22   Phase I

 The specific objectives of the first phase of Emerging
 Technology tests included the establishment of cyclone
 operability,  determination  of slag  leachability and
 volume reduction, and determination of preliminary
 mass balance for the cyclone treatment process.

 Testing utilized SSMs spiked with high levels of lead,
 cadmium, and chromium.  These soils were  fed at
 nominal rates of 50 and 150 Ib/hr tangentially into the
 cyclone furnace.  The soil was melted and the  result-
 ing slag was released into  a water-filled  slag tank
 where it was solidified.

 In order to determine whether a vitrified material was
 produced, samples of the feed SSM and  slag were
 taken and analyzed for total  metals  content and
 metals leachability using the Toxicity Characteristic
 Leachability Procedure (TCLP).  The properties  of
 the SSMs, the volume reductions experienced, and
 preliminary  metals mass balances to determine the
 fate  of the heavy metals during soil treatment were
 also  determined.

 The  results  of this  study  are  summarized in the
 following:

Metals Leachabilitv after Cyclone Treatment:  The
 results indicate the vitrification process changed the
physical and chemical composition of the soil in such
 a manner as to render the heavy metals less teachable.
The  percent leachability  for  lead, cadmium,  and
 chromium in the untreated SSM were 29, 84, and 3.8
                                                 33

-------
percent, respectively. Percent leachability of the slag
for lead, cadmium, and chromium was 0.18, 2, and
0.07 percent, respectively.  All slag samples were well
below TCLP limits for the three heavy metals.

Total Metals  in  Soil  and Slag:   The total metals
results on  the soil and slag samples,  averaged and
reported on a dry basis, are given in Table D-l. As
compared to the level of total metals in the SSM, the
slag was relatively enriched hi chromium and depleted
in lead and cadmium.

Volume Reduction; The vitrification process achieved
a volume reduction of approximately 35 percent over
the dry SSM.
Table D-l.
Sample
Composite Soil
(DiySSM)
11/15
11/16
Reagent Blank
Composite Slag
11/15
11/16
Reagent Blank
Multiple Metals
Train Particulatcs
11/15
11/16
Filter Blank
Total Metals in Soil, Slag, and Multiple
Metals Train Particulates (mg/kg)
Cadmium Chromium Lead

1316.+40
1223+34
<0.05

101
134.+3.2
<0.05

15146
14816
15

1391+86
1339+.93
<0.05

1907
2169_+_147
<0.05

12493
9893
108

8007.+248
7390jf214
<0.05

1624
2432.+.221
<0.05

80414
99880
149
 Fate  of Heavy Metals:   Heavy metals could  be
 trapped within the vitrified slag or be volatilized and
 leave the furnace with the flue gas.  Metal volatility
 controls the distribution of heavy metals between the
 fiyash and the slag. To determine the mass balance,
 a total heavy metals analysis was performed on the
 SSM, vitrified slag, and captured fiyash.  Chromium
 was determined to be the least volatile with between
 80  and  95 percent  retention in  the slag.  Cadmium
 was the most  volatile metal,  with  a range  of 7
 to 8 percent retention in the slag.  Lead fell between
 chromium and cadmium, in terms of slag retention, at
 24 to 35 percent.
DJ53   Phase II

The second phase of the Emerging Technology tests
was designed to build upon the knowledge gained in
the first phase of  tests.   Phase I established  the
suitability of the cyclone furnace for the vitrification of
contaminated  soils.   Phase II provided additional
operating data and allowed further optimization of
process parameters.

Like Phase I, Phase II utilized SSMs spiked with lead,
cadmium, and chromium.   Feed rates in  Phase II
ranged from 100 to 300 pounds  of SSM per hour.
When the feed rate was increased to 400 pounds per
hour,  the  furnace  temperature  dropped  and  slag
tapping stopped or was blocked. The effects of feed
rate on various parameters were studied.  Results
indicated  that NOX  levels  and   heavy  metals
concentrations in the slag were proportional to feed
rate,  while   slag   temperatures  were   inversely
proportional to feed rate.

Phase II testing included an evaluation of Borax  as a
fluxing agent.  Fluxing agents are intended to cause
the soil to  melt  and tap at lower  temperatures,
thereby decreasing metals volatilization and increasing
metals capture in the slag. In a fluxing test, a mixture
containing 10 percent Borax and 90 percent SSM was
fed to the cyclone  furnace at a nominal rate of 200
pounds per hour.  The results of this  Borax addition
are as follows:

•       Natural gas load was reduced from 5 million
         Btu per hour to 4.1 million Btu per hour.

 •       The  slag  temperature was  reduced  from
         2430°F to 2320°F.

 •       NOX levels  in  the stack decreased  from
         between 318 and 337 ppm to 260 ppm.

 •       Fiyash production increased.

 •       Metals emissions rates decreased slightly.

 •       TCLP results indicate that the leachability of
         lead from the SSM decreased slightly; further
         testing would be required  to   determine
         whether   this   change  was   statistically
         significant.

 •       Volume  reduction,   though  not  directly
         measured, appeared to decrease.

 •       Cadmium  retention in  the  slag increased
         sh'ghtly, but further testing would be required
         to confirm the significance of this change.
                                                   34

-------
After these results were evaluated,  the  developer
determined that the  addition  of Borax did  not
significantly improve  the operation  of the cyclone
furnace.

The remainder  of the Phase II testing primarily
reinforced the results of the Phase I testing, although
Phase II testing used wet feed and Phase I testing
used dry feed. Additional data from Phase II testing
are summarized  hi the following:

•       All slag  samples were below TCLP limits for
        the three metals.

•       The percent teachabilities for lead, cadmium,
        and chromium in the untreated SSM were 20,
        57,  and 0.55  percent,  respectively.    The
        percent teachabilities for lead, cadmium, and
        chromium in  the slag were  0.09, 0.70, and
        0.02 percent, respectively.
As compared to the feed SSM, the slag was
relatively enriched in chromium and depleted
in lead and cadmium.

The  vitrification process achieved a volume
reduction  of  approximately  25  percent
between the SSM  and the  slag.   This is
somewhat lower than the 35 percent volume
reduction achieved  in Phase I,  but  the
difference may simply reflect the difficulty of
obtaining representative samples of the slag.

As in Phase I, heavy metals were retained in
the slag or were volatilized into the flue gas.
In Phase II testing, the following percentages
of heavy metals were retained in the slag:

        Chromium: 78 to 95 percent
        Lead:      38 to 54 percent
        Cadmium:  12 to 23 percent
                                                35

-------

-------

-------

-------

-------
United States
Environmental Protection Agency
Center for Environmental Research Information
Cincinnati, OH 45268

Official Business
Penalty for Private Use
$300
Please make all necessary changes on the below label,
detach or copy, and return to the address In the upper
left-hand comer.

If you do not wish to receive these reports CHECK HERE D;
detach, or copy this cover, and return to the address In the
upper left-hand comer.
      BULK RATE
POSTAGE & FEES PAID
          EPA
   PERMIT No. G-35
EPA/540/AR-92/017

-------