-------
Introduction
Coal preparation is the process of upgrading raw coal by physical
means. In general, preparation techniques improve the heating value
and physical characteristics of the coal by removing impurities such
as pyrite and ash material (e.g., shales, clays, shaley coals, etc.).
By removing potential pollutants such as sulfur-bearing minerals prior
to combustions, coal cleaning can be an important control strategy for
complying with air quality standards. The physical upgrading of
metallurgical coal has long been a necessity because the steel
'industry has had the toughest quality requirements of all major coal-
consuming industries. On the other hand, utility (steam) coal has
been subjected to less extensive preparation. Although utility coal
is required to be relatively uniform in size, the economic benefits
accrued from deep cleaning in the past has not been sufficient to
.justify the additional preparation costs. However, with the
'establishment of new sulfur dioxide emission standards for power
generating plants, there is a growing demand for more complete
cleaning of utility coal. Electric utility companies can meet these
^standards by installing scrubbers or other technologies that reduce
the sulfur content of stack gases, or by burning cleaner, lower sulfur
;coal .
Coal Preparation Processes
The physical coal cleaning processes used today are oriented toward
product standardization and reduction of ash, with increasing
attention being placed on sulfur reduction. In a modern coal-cleaning
plant, the coal is typically subjected to size reduction and
screening, gravity separation of coal from its impurities, and
dewatering and drying. The commercial practice of coal cleaning is
primarily based on separation of the impurities due to differences in
the specific gravity of coal constituents (i.e., gravity separation
processes), and on the differences in surface properties of the coal
and its mineral matter (i.e., froth flotation).
Although it is not possible to describe a universal coal preparation
process, certain processing methods common to most preparation
operations can be identified. Figure IV-27 illustrates a coal-
cleaning facility that uses common process methods, without detailing
specific unit operations.
Initial Coal Preparation
Prior to the actual cleaning process, run-of-mine coal must undergo
initial preparation. This involves preliminary crushing of the coal
to remove large rock fractions and to liberate entrained impurities
such as clay, rock, and other inorganic materials, including pyrite.
The first crushing step is followed by a screening operation and
A second screening step produces two product
process area: one containing a fine fraction
secondary crushing.
streams from this
(usually less than 6.5 mm) and the other containing coarse particles
(normally 76.0 x 6.5 mm). These two coal streams are then routed to
80
-------
I
R-O-M Coal |
STORAGE
1/2 HOUR
OF
RATED
PLANT
CAPACITY
Recirculating Plant Water
CO
COARSE COAL
CLEANING
Initial Coal Preparation
Fine Coal Processing
Coarse Coal Processing
Water Management and
Final Coal Preparation
PROCESS AREAS
Clean Products
Reject Streams
Coal Slurry
Water Flows
Coal Flows
Recycle
and /or .
Discharge
1
Refuse i
1
1
WATER
TREATMENT
AND
RECOVERY
1
i
1
Source: "The Energy Requirements for Control SO. Emissions from Coal Fired Steam/
Electric Generators," Radian Corporation, TJCN-77-200-T87-08-06, EPA Contract
No. 68-02-2608, U.S. EPA-IERL, 1977.
Figure 1V-27. Simplified Flow Scheme—Physical Coal Cleaning Process
-------
their respective process
takes place (7).
areas where the actual cleaning operation
Fine Coal Processing
Fine coal processing can involve either wet or dry cleaning methods.
In plants utilizing a dry coal cleaning process, fine coal from the
initial preparation step flows to a feed hopper and then to an air
cleaning operation. This cleaning operation can employ one of several
devices which rely on an upward current of air traveling through a
fluidized bed of crushed coal. Separation is effected by particle
size and density. Product streams from a dry cleaning process are
sent directly to the final coal preparation step, while reject streams
are usually processed further in wet cleaning operations (19).
operations utilizing wet methods to effect fine coal cleaning, the
'ream containing less than 6.5 mm coal is slurried
In operations utilizing wet methods to effect fine coal cleaning,
process feed stream containing less than 6.5 mm coal is slurried w
water as it enters the fine coal processing area of the plant. T
slurry is then subjected to a desliming operation which removes
o.ior^nci^r, containing approximately 50 percent of minus 200 m
usually in the range
hJJJ.LJl-1-Y .*- U ^ 1 J \^ 1 1 •hJt*li»'J^'\«'b.*wt*i W V-* M U^-l*J^XJIl^ai^ V £S\^ ^ U Ip* ^ IX A I TTltXV'il LW1IIWV
suspension containing approximately 50 percent of minus 200
material. The cutoff size for this separation is usually in the
of 28 to 48 mesh. This desliming operation is necessary because
presence of slimes adversely affects the capacity and efficien
with
This
a
200 mesh
of 28 to 48 mesh
presence of slimes
fine cleaning units
the
ciency of
Subsequent to desliming, the oversize coal fraction (greater than 28
mesh) is pumped to the fine coal cleaning process. Here, fine coal
particles undergo gravity separation in one of several wet cleaning
devices. This removes a percentage of ash and pyritic sulfur to
produce a clean coal product. The product stream from this operation
is fed to the drying area of the plant; refuse material is further
processed in the water treatment section.
The slimes removed from the fine coal stream are fed to a froth
flotation process. Other material, such as reject from dry cleaning
operations, may also be treated in the flotation process. This
process consists of "rougher" and "cleaner" sections which are
comprised of cells of flotation machines. Upon entering the flotation
process area, the slime suspension is treated with a frothing agent.
This agent selectively floats coal particles in the flotation machines
while allowing pyrite and ash impurities to settle. Processing slime
in the "rougher" cells produces a reject stream and a low-grade
product. The low-grade product is further processed in the "cleaner"
cells to produce a clean coal product. This final float product is
then sent to the dewatering area for further handling, while reject
material from both rougher and cleaner sections is processed in the
water treatment and recovery area.
Coarse Coal Processing
Feed to the coarse coal processing area of the plant consists of
oversize material {76 x 6.5 mm particles) from the initial preparation
area. This feed stream is slurried with water prior to cleaning,
82
-------
since coarse coal cleaning operations employ wet processing equipment
to remove impurities from the coal. The coarse coal slurry is fed to
one of the many types of process equipment currently employed in
coarse coal cleaning. Here, impurities are separated from the coal
due to differences in product and reject density. It is common
practice to remove a middling fraction from the separation operation
and process it further by means of recycle or by feed to another
cleaning process. These cleaning operations result in removal of two
streams from the coarse coal processing area: a product and a reject
stream. Subsequent to the coarse cleaning operation, the product
stream is pumped to the dewatering and drying area of the plant, while
the reject stream is processed in the water treatment recovery area.
Water Management/Refuse Disposal
Dewatering and drying equipment handle the product flows from both the
fine and coarse coal preparation areas. Typically, cleaning plants
employ mechanical dewatering operations to separate coal slurries into
a low-moisture solid and clarified supernatant. The solid coal sludge
produced in the dewatering step can be mechanically or thermally dried
to further reduce the moisture. The supernatant from the dewatering
process is returned to the plant water circulation system.
The water treatment and recovery section of a cleaning plant processes
refuse slurries containing both coarse material and reject slimes.
Here, the refuse slurry is dewatered, typically in thickeners and
settling ponds. The supernatant from this operation is most often
returned for reuse in the plant, while the refuse can be buried and
revegetated to prevent burning, or piled prior to reclamation. The
coal product from the dewatering and drying area of the plant often
undergoes additional processing. This may involve crushing and
screening operations to separate the product into various product
sizes. The cleaned and sized product is then conveyed to storage
silos or bins prior to shipping.
Plant Statistics
There was a total of 458 preparation plants processing anthracite,
bituminous, and lignite coal in the United States in 1975 (18).
(Current estimates (1979) indicate there are now approximately 670
preparation plants.) Based on 1976 data, 95 percent of the plants
employed wet processing methods (see Figure IV-28). Only 21 plants
used dry methods. Two-thirds of the wet processing plants utilized
heavy media separation, froth flotation, or both. Table IV- 10 shows
bituminous and lignite tonnage processed in 1975 by type of cleaning
method. Two hundred and forty-two million metric tons (267 million
short tons) (41 percent) of 1 975 production received mechanical
cleaning using wet processing methods, whereas 288 million metric tons
tons) (49 percent) were subjected to crushing
only and 58 million metric tons (64 million short
received no processing prior to consumption. Table
mechanical cleaning of bituminous and lignite coal
(317 million short
and/or screening
tons) (10 percent)
IV-11 breaks down
by type of equipment.
83
-------
-------
Table IV-11
MECHANICAL CLEANING OF BITUMINOUS AND LIGNITE COAL
IN 1975, BY TYPE OF EQUIPMENT
Type of
Equipment
Washing Only Processes
Jigs
Concentrating Tables
Classifiers
Launder ers
Subtotal
Dense Media
Processes
Magnetite
Sand
Calcium Chloride
Subtotal
Flotation
Total Wet Methods
Pneumatic Methods
kkg * 1.06
113.0
26.0
5.6
2.4
147.0
65.7
12.2
0.9
78.8
10.4
236.2
6.1
Short Tons * 106
124.3
28.7
6.2
2.7
161 .9
72.4
13.5
1 .0
86.9
11 .5
260.3
6.7
Percent
46.6
10.7
2.3
1 .0
60.6
27.1
5.1
0.4
32.6
4.3
36.9
2.5
Grand Total
242.3
267.0
100.0
Source
-------
PREPARATION PLANTS IN U,S
458
WET PROCESS
437
I
DRY PROCESS
21
FROTH FLOTATION AND
DENSE MEDIA SEPARATION
292
WASHING
ONLY
145
Figure IV-28
TYPES OF COAL PREPARATION PLANTS IN THE
UNITED STATES
Source: (20)
86
-------
Associated Areas
Associated areas include refuse piles, raw and clean coal stockpiles,
applicable haulroads or access roads, and disturbed areas from
preparation plant facilities; that is, areas associated with the
preparation of and waste generated by a refined coal product. Refuse
piles and coal stockpiles, plus other associated areas, can be prone
to generation of acid waters, especially if high pyritic coals are
involved. Proper management and treatment techniques are required to
be used to minimize water pollution from these areas.
-------
-------
SECTION V
WASTEWATER CHARACTERIZATION AND INDUSTRY SUBCATEGORIZATION
INTRODUCTION
The development of effluent limitations guidelines is based upon the
determination of the effluent characteristics of the industrial
category and the identification of suitable treatment technologies for
reduction of pollutants within the category. All industrial
categories have inherent processing, site, or raw material differences
which influence their effluent characteristics and methods of
wastewater treatment. The purpose of this section is to recognize any
of these major inherent differences that exist within the category,
and more importantly, to determine their impact on treatability and
effluent characteristics. The subcategorization scheme developed from
this evaluation provides the basis for the selection of treatment
technologies and the determination of effluent standards.
SUBCATEGORIZATION
The development of the BAT subcategorization scheme includes an
examination of many factors which might affect effluent quality and
treatability. The factors examined include mine type (surface or
underground), coal type (anthracite, bituminous, lignite), size,
location, and effluent source (preparation plant, active mine, or
reclamation area). These factors were previously examined during the
.development of BPT effluent limitations, and a BPT subcategorization
scheme was established. That subcategorization has been reexamined in
light of additional data collected during the BAT program.
Statistical and engineering analyses of these data indicate that
several modifications are appropriate.
Revised BPT, BAT and NSPS Subcateqorization Scheme
The following categorization provides the basis for the remainder of
this study:
-------
1, Preparation Plants and Associated Areas (for NSPS, different
standards apply to preparation plants and associated areas).
2. Acid Mine Drainage
Alkaline Mine Drainage
Post Mining Discharges
a. Reclamation areas and
b. Underground mine discharges
SAMPLING AND ANALYSIS PROGRAM
To develop the regulations, data characterizing wastewaters generated
during the extraction and preparation of coal were obtained and
evaluated. The initial data collection effort was instituted during
1974 and 1975 for the development of BPT effluent limitations. These
data included results from a sampling and analysis program and
assimilation of a large amount of historical data supplied by the
industry, the U.S. Bureau of Mines and other sources. This
information characterized wastewaters from coal mining operations
according to a number of key control parameters—acidity, alkalinity,
total suspended solids, pH, iron, and others. However, little
information on other pollutants such as toxic metals and organics were
available from industry or government sources. To establish the
levels of these pollutants, a second sampling and analysis program was
instituted to specifically address these toxic compounds, including
the 65 pollutants and pollutant classes for which regulation was
mandated by the Clean Water Act Amendments of 1977. These pollutants
are listed on Table VI-1. This sampling effort also served to extend
the coal wastewater data base of conventional and nonconventional
pollutants.
Data Base Developed During This Rulemaking
The Agency instituted a screening sampling program and a verification
sampling program directed primarily at determining levels of the toxic
pollutants in raw and BPT-treated effluents in the coal mining
industry. Additional analytical data were obtained during engineering
site visits to seventeen mine sites. Two EPA regional offices
supplied supporting data from facilities within their geographical
areas. Data generated from a self-monitoring program for areas during
precipitation events and areas under reclamation are also part of the
data base, A precision and accuracy study of settleable solids
90
-------
Table V-l
DATA SOURCES DEVELOPED DURING BAT REVIEW FOR
WASTEWATER CHARACTERIZATION
Number of Facilities by Proposed Subcategory
Preparation Preparation Plant Reclamation
Data Source
Screening
Verification
Engineering Site
Visits
EPA Regional Studies
Self -Monitoring
Survey
Prep. Plant
Questionnaire
Prep. Plant Sampling
NPDES DMR
Site Specific Areas
Under Reclamation
Acid
9
7
3
0
0
0
0
56
0
Alkaline
14
5
11
3
0
0
0
32
0
Plants
15
5
5
1
0
152
3
12
0
Associated Areas
6
2
4
0
0
152
3
1
0
Areas
0
0
1
0
24
0
0
0
8
TOTALS
75
65
193
168
33
-------
studies are
studies are
and Control
sedimentation
concentrations less than 1.0 ml/1 was also performed. Finally, data
from a preparation plant industry questionnaire and NPDES Discharge
Monitoring Reports from four EPA regions have been compiled for
addition to the active data base. These data sources are presented,
by proposed subcategory, in Table V-l and discussed in more detail
below. Table V-2 summarizes statistics for the data base upon which
coal industry wastewaters are characterized. A number of treatability
studies were also conducted to evaluate the capacity of candidate
technologies to treat coal mine drainage. These
summarized in Table V-3. Results from the treatability
discussed in detail in Section VII, Treatment
Technologies. Special reports for anthracite mining,
pond sludge samples and coal preparation plants were also prepared.
(See Ref 21.22, and 23 respectively).
Data Sources
Screening and Verification Sampling
The screening and verification sampling program began in 1977.
Several criteria were considered in the selection of sampling sites.
It was determined that facilities to be sampled should: 1. Be
representative of the industry to account for all major factors (i.e.,
location, topography, seam characteristics, etc.) which could
influence effluent quality and treatability; and 2. Include treatment
processes considered exemplary within the industry to establish a
baseline for best available technologies. Applying these criteria, a
candidate list of sites was prepared and submitted to the Water
Quality Committee of the National Coal Association for comment. A
final list of sites to be visited for the screening phase was then
compiled. The mine companies were contacted and sampling arrangements
made. Screening sampling visits were conducted during 1977 to sites
within the various subcategories as listed in Table V-l. All sampling
and analysis during this phase were done according to EPA sampling
protocols. (8). After review of screen sampling analytical results,
several additional sites were selected for verification sampling.
Three coal mines and preparation plants were revisited to verify data
collected during screening. Three additional bituminous and lignite
mines, as well as four anthracite facilities, were also sampled to
enhance the representativeness of the data base. Sampling and
analytical protocols for this phase were all in accordance with EPA
procedures (8). More detail on these protocols can be found in
Appendix C, of the Proposed Coal Mining Development Document. (EPA
440/1-81/057/b).
Engineering Site Visits
The engineering site visits were carried out primarily to collect cost
data for verifying and supplementing costs previously developed for
the coal mining industry. Fourteen separate mines, some with an
associated preparation plant, were contacted and visited in the fall
of 1979. A sample data checklist used on the visits may be found in
Appendix D of the Proposed Coal Mining Development Document. Samples
92
-------
Table V-2
DATA BASE SOURCES
BPT Study
BCRI Surveys
*BAT Screening
and Veriftcatton
*Self-Monitoring
Survey
*EPA Region IV, VIII
*Engineering Site
Visits
*Preparation Plant
Site Visits
*Preparation Plant
Industry Survey
Total No. in Data Base
Total No. of Independent
Facilities in Computerized
Data Base
Percent of 1978 Total
Production Represented
tn Total Data Base
Type of
Facility
Anthracite,
Bituminous Coal
and Lignite Mines
89
162
29
17
3
14
0
0
314
Preparation Plants
and Associated
Areas
34
118
19
0
1
8
3
152
335
58
39
167
43
*Data from this source has been computerized.
93
-------
Table V-3
TREATABILITY STUDIES CONDUCTED ON COAL MINE DRAINAGE
VD
4="
Technology
Examined
Site(s) of
Study or Mine(s)
Lime/Limestone Crown, WV
Lime/Limestone Norton, WV
Reverse Osmosis
Flocculant
Addition
Granular Media
Filtration
Neutralization
Aeration
Ozonation
Sand Filtration
Carbon Adsorption
Reverse Osmosis Crown, WV
Ion Exchange
Lime Neutralization
Norton, WV
Morgantown, WV
Ebensburg, PA
Mocanaqua, PA
Norton, WV
Hollywood, PA
Crown, WV
Stonefort, IL
Ebensburg, PA
Greensboro, PA
Crown, WV
Type of
Drainage Treated
Acid Mine Drainage
(Ferrous Iron)
Acid Mine Drainage
(Ferric Iron)
Acid Mine Drainage
Acid Mine Drainage
Acid Mine Drainage
Acid Mine Drainage
Dates
of Effort
1974-1976
1974
1972
1979
1980
Acid, Alkaline Mine 1978-1979
Drainage for Organ-
ics and Toxic
Metals
Acid Mine Drainage
1978
Reference
(2)
(3)
(4)
(5)
(6)
(7)
-------
of raw and treated effluents were collected and shipped for analysis
of "classical" parameters (TSS, Fe, Mn, pH, turbidity,
alkalinity/acidity, settleable solids, and total dissolved solids) and
the thirteen toxic metals. The analytical protocol used was
established by EPA. The metals were analyzed by inductively-coupled
argon- plasma emission spectrometry and atomic adsorption (9).
EPA Regional Support Studies
EPA Region 8 (Denver, Colorado) instituted a sampling effort to assess
the water treatment configurations and effluent qualities
characteristic of the western coal producing region. Several mines
were visited during the spring of 1979; however, due to an unusually
mild winter and an abnormally dry spring, only two of those contacted
were found to have a discharge that could be sampled. Grab samples
were collected and analyzed for the currently regulated parameters,
priority metals, and a number of nonconventional pollutants. EPA
Region 4 (Atlanta, Georgia) conducted a similar effort at one mine in
its region. These data were forwarded to the Effluent Guidelines
Division and incorporated into the data base. This information was
incorporated into a report comparing effluents from eastern and
western mines.(10) The data was also used to further characterize mine
drainage and wastewater treatability, particularly for priority metals
removal.
Preparation Plant Industry Survey
This study was conducted with the cooperation of the National Coal
Association (NCA) to assess water usage and treatment in coal
preparation plants. NCA producer companies were mailed a
questionnaire requesting the following information: facility profile,
water balance around the preparation facility, makeup water sources,
discharge points and quantities, water treatment practices employed,
water management procedures and acreage of preparation plant
associated areas, and effluent quality data. A sample questionnaire
is in Appendix D of the Proposed Coal Mining Development Document (EPA
440/1-8/057-b) for the proposed rulemaking. One hundred and fifty-two
plants (approximately 50 percent of the NCA producer company
preparation plants) responded to the survey, representing roughly 30
percent of all the plants in the industry. This information was
incorporated into the computer data base developed in support of the
overall program, and may be found in Appendix E of the Proposed Coal
Mining Development Document (EPA 440/1-81/057-b). The uses of the
industry responses include the following:
1. Determination of the number
recycle system;
of plants operating a total
2. Determination of requirements for modifying
treatment configurations to a total recycle system; and
current
3. Determination of the runoff
ancillary to the preparation plant.
treatment strategy for areas
95
-------
Questionnaire results are discussed in Section VII, Treatment and
Control Technology.
Self-Monitoring Survey
A one year survey conducted under authority of Section 308
Clean Water Act was performed in order to characterize
discharges from sedimentation pond effluents during and after
and also for reclamation areas. (See Appendix A of this document).
Seventeen mining facilities involving 24 ponds reported data.
Sampling of one pond ended shortly after the study because the
facility discontinued discharging into it. Four other ponds did not
report a discharge during the study. Therefore,
from a total of 19 ponds.
of the
surface
storms
data was collected
Samples were taken of the influent to and effluent from the ponds.
One sample per week was collected to establish base flow conditions,
with additional samples taken during any significant rainfall event
and the day after the rainfall event. The results of these sample
analyses, coupled with design specifications submitted by the
participating companies for each pond, permitted identification of the
treatment effectiveness of the ponds during dry weather and storm
conditions, as well as concentrations of pollutants which characterize
runoff from mining areas. The parameters analyzed include total
suspended solids, settleable solids, total iron, dissolved iron, and
pH, Certain samples were also analyzed for the priority metals.
(After the first six months' of the toxic metals analyses, results
were so low that sampling for these parameters was discontinued).
Settleable Solids Precision and Accuracy Study
A second major sampling and analysis effort was performed to develop a
precision and accuracy determination for measurement below 1.0 ml/1 of
settleable solids for active mining and reclamation area discharges
from eastern and western coal mines. (See Appendix B of this
document). Under this program, eight treatment ponds were sampled and
analyzed for settleable solids using the Standard Methods protocol
(14th Ed., American and Public Health Association, Washington, D.C.,
1975). Based on the results of this study, EPA has concluded that it
is possible to measure settleable solids below 1.0 ml/1 and that an
effluent limitation below 1.0 ml/1 is indeed reasonable. In fact, EPA
concluded that the maximum method detection limit for settleable
solids in the coal mining industry is 0.4 ml/1.
Preparation Plant Sampling Program
This sampling and analysis effort was instituted to characterize
preparation plant effluents and to compare wastewater generated within
total recycle systems with wastewater discharged from partial recycle
and once-through systems. Grab samples were collected at three
preparation plants and associated areas and analyzed according to
Agency protocol (8). Cost and wastewater engineering data were
collected simultaneously to augment existing data and to permit an
96
-------
evaluation of the feasibility of
preparation plant water circuits.
Regional Discharge Monitoring Reports
Program
no discharge of pollutants from
(DMR) Filed Under the NPDES
A program was conducted to collect DMRs from EPA regional offices
located in the major coal producing areas in the United States. These
data identify the levels of variation in flow and pollutant
characteristics associated with mine drainage. Of particular interest
is the daily maximum value of each regulated pollutant (TSS, Fe, Mn,
and pH) during the 30-day monitoring period. Eighty-eight sets of
data were obtained from EPA Regions 3, 4, 5, and 8.
WASTEWATER SOURCES AND CHARACTERISTICS
Water enters surface or deep mines by groundwater infiltration,
precipitation, and surface runoff. Surface runoff can become
contaminated with suspended solids from sediment. If pyritic material
is exposed on the mine bottom, highwall, or spoil piles, oxidation and
acid formation can occur and leach toxic metals. Groundwater entering
a surface or deep mine is also subject to acid formation.
The wastewater situation at coal mines is notably different from that
found in most other industries. No process water is used in coal
extraction, except for minor use in dust suppression, equipment
cooling, and firefighting needs. Water is an operational hindrance to
a coal mine, and requires careful management to minimize water
entering the active mining area. Water can cause occupational health
hazards, such as spoil bank or highwall instability or an electrical
short circuit in the case of operations using electric trunk lines to
power mining equipment. As indicated in the industry profile section,
the quantities of water generated at a mine site do not correlate with
the coal production rate. This again differs from most other
industries, where flow, and thus pollutant loadings, can be linked
with the rate of production.
A final major difference with water management in the coal industry is
the possibility of continuing discharges of polluted wastewater after
the facility has ceased production, especially from underground
operations. Control practices, which are discussed in Section VII,
can be implemented to minimizei or treat these discharges during and
after the active mining phase.
97
-------
This subsection will summarize raw wastewater data first for all
subcategories and then for each individual proposed subcategory. The
data sources in the summary tables include the following:
1. Screening sampling data,
2. Verification sampling data,
3. Self-monitoring survey data,
4. EPA regional data,
5. Engineering site visits,
6. Preparation plant site visits.
A number of explanatory points should be made to correctly interpret
the tables presented in this section and the next section. First, all
concentrations are presented in micrograms per liter, listed as UG/L
on the tables.
Second, the tables represent an effort to illustrate the quantity and
•distribution of the data. Thus, the total number of samples analyzed
for each pollutant parameter is listed in the first numerical_ column.
The second column presents the total number of times the pollutant was
detected during analysis. Because the Agency considers 10 ug/1 as a
realistic lower limit for detection of organic compounds (5 ug/1 for
pesticides), the third column depicts the total number of samples
where a detected value of greater than 10 ug/1 was found. These are
termed "quantifiable levels." The final six columns are an attempt to
illustrate the data distribution of only the detected values. The
statistics listed include the minimum, the 10 percent value (i.e., 90
percent of the detected values are above this concentration), the
median of detected values, the mean of detected values, the 90 percent
value (90 percent of the detected values are below this value), and
the maximum reported concentration. Nearly all the organic priority
pollutants and a number of the toxic metal pollutants are most
frequently found as "not detected," i.e., below the detection limit.
To record these values on the final five columns would render these
columns essentially meaningless. For instance, cyanide was detected
in onl.y three samples out of 50 for raw wastewater (see Table V-4).
If the not detected values were recorded in the final five columns,
the minimum, the 10 percent value, the median, and the 90 percent
value would all be listed as not detected. This may be appropriate
for some types of evaluation, but, for the purpose of developing
treatment technologies and supporting a subcategorization scheme,
illustrating the data distribution for detected values is more
informative.
Third, in situations where fewer than 10 detected values occur, no
meaningful number could be selected to represent the 10 percent and 90
percent values. This is denoted by an asterisk. Dots in the minimum,
mean, median, and maximum columns indicate no values were detected for
that parameter.
Fourth, concentrations were sometimes reported by the analytical
laboratory as "detected less than X" where X equals some detection
limit. This apparently contradictory information can be explained by
98
-------
Table V-4
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORXDE
CHLOROBENZENE
1.2. 3 -TR I CHLOROBENZENE
HEXACHLOROBENZENE
,2-DICHLOROETHANE
, 1 , 1-TRICHLOROETHANE
HEXACHLOROETHANE
, 1-DICHLOROETHANE
. 1 . 2-TRICHLOROETHANE
.1.2. 2-TETRACHLOROETHANE
CHLOROETHANE
BXS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHi.OROETHYL VINYL ETHER (MIXED)
2 -CHLQRONAPHTHALENE
2 . 4 . 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 . 2-DICHLOROBENZENE
1 . 3-DICHLOR08ENZENE
1 ,4-DICHLOROBENZENE
3,3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
49
47
47
47
48
47
48
49
49
47
47
49
47
47
47
47
47
49
47
49
46
46
47
46
49
49
49
48
TOTAL
NUMBER
DETECT
3
0
O
13
0
0
1
0
0
O
4
O
0
0
O
O
0
O
0
«
0
O
25
1
2
0
1
O
NUMBER
SAMPLES
>10UG/L
O
0
O
8
O
0
1
0
0
O
1
0
0
O
O
0
0
O
O
0
0
O
22
1
1
0
O
O
DETECTED CONCENTRATIONS
IN UG/L
MZN 10X MEDIAN MEAN 90% MAX
3 3
.
2
.-
.
12
t
t
,
3
.
.
.
.
.
p
.
.
3
.
.
3
86
3
.
3
.
.
m
16
f
t
12
f
+
m
3
.
.
.
.
.
..
.
,
3
.
.
32
86
3
.
3
.
3 3
,
ft
24 4
p
,
12
f
m
m
8
.
.
.
.
.
,
,
.
3
.'
,
93 3Of
86
11
.
3
.
.
,
73
,
.
12
.
.
23
.
.
t
.
f
.
.
g
3
,
f
476
86
18
9
3
.
-------
Table V-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
ALL SUBCATEGORIES
TOXIC POLLUTANTS
o
o
COMPOUND
1. 1-DICHLOROETHYLENE
1 ,2-TRANS-DICHLOROETHYLENE
2,4-DICHLOROPHENOL
1 , 2-DICHLOROPROPANE
1 , 3-DICHLOROPROPENE
2 , 4-DIMETHYLPHENOL
2 . 4-DXNITROTOLUENE
2 . 6-DINITROTOLUENE
1 , 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMDPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BIS(2-CHLQROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUDRONETHANE
OICHLORODIFLUOROMETHANE
CHLORODIBROMOMETHANE
HEXACHLOROBUTADIEME
HEXACHLOROCYCLOPENT ADI ENE
ISOPHDRONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
47
47
46
47
47
46
49
49
49
48
49
49
49
49
49
47
47
47
47
47
47
47
47
49
49
49
49
49
TOTAL
NUMBER
DETECT
3
1
O
O
0
3
1
t
1
4
5
1
O
0
O
43
O
O
O
O
0
0
0
0
O
1
1O
1
NUMBER
SAMPLES
>10UG/L
O
O
O
o
o
3
1
1
O
1
2
O
O
O
o
34
O
O
O
O
O
0
O
0
O
1
6
1
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN
3
1O
.
,
.
18
18
3O
3
2
3
3
,
.
.
V
.
,
,
.
.
.
.
,
.
307
3
10
.
,
.
20
18
30
3
3
3
3
,
.
.
501
.
307
2 2 1O
21 * 21
MEAN 90% MAX
3 3
10
.
.
.
21
18
30
3
s
B)
3
.
.
.
1188 22O
.
.
.
*
.
.
,
.
.
307
10
,
9
9
24
18
SO
3
11
11
3
,
.
.
11190
,
.
,
.
307
75 22O 4 1O
21 * 21
-------
Table V-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW VASTEVATER
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
2-NITROPHENOL
4-NXTROPHENOL
2.4-DINXTROPHENOL
4,6-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSOOI -N-PROPYLAMXNE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
OJ-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
OIETHYt PHTHALATE
DIMETHYL PHTHALATE
BENZQf A)ANTHRACEKE
BENZO(A)PYRENE
BENZO ( B ) FLUORANTHENE
BENZO( K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO (G,H. I )PERYLENE
FLUORENE
PHENANTHRENE
DIBENZO( A , H ) ANTHRACENE
INDENOC 1,2. 3-C . 0)PYRENE
PYRENE
TOTAL
UIUDCD
MM0EN
SAMPLES
46
46
48
46
49
49
48
46
46
49
49
49
49
40
49
46
49
49
49
46
49
46
49
49
46
49
49
49
TOTAL
M IMP CD
NLM0CK
DETECT
1
O
0
1
O
1
O
O
6
21
4
19
1
11
1
0
7
O
3
0
1
0
7
5
1
5
4
6
NUMBER
CAUBI EC
SAMPLES
>10UG/L
1
0
O
1
0
1
O
O
1
12
O
3
O
1
O
O
2
0
2
O
1
O
1
2
1
O
O
2
DETECT
MXN
17
,
.
194
.
45
1 .
.
3
3
3
2
3
1
3
.
1
.
1
.
9
.
1
1
12
3
3
1
ED CONC
10%
*
*
*
*
*
*
*
*
*
3
*
3
*
1
*
*
*
*
*
*
*
*
*
*
*
*
*
*
;ENTRATIO
MEDIAN
17
,
.
194
.
48
,
,
3
9
3
3
3
3
3
t
3
,
4
,
9
,
3
3
12
3
3
3
MS IN t
MEAN
17
a
m
194
f
45
,
.
5
16
3
4
3
B
3
.
24
t
B
.
9
.
5
14
12
5
6
9
KJ/L
90%
*
*
*
*
*
*
*
*
*
44
*
8
*
3
*
*
*
*
*
*
*
*
*
*
*
*
*
*
MAX
17
.
.
194
.
45
f
t
16
62
3
11
3
23
3
,
141
.
11
m
9
B
10
44
12
10
1O
25
-------
Table V-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
ALL SUBCATEGORIES
TOXIC POLLUTANTS
o
ro
COMPOUND
TETRACHLOROETHYLEME
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLOROANE
4.4-DDT
4, 4 -DDE
4. 4 -ODD
ENDOSULF AN- ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR EPOXIDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-OELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCS -1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-124B (AROCHLOR 124ft)
PCB-1260 (AROCHLOR 1260)
PCB-1O16 (AROCHLOR 1O1B)
TOTAL
NUMBER
SAMPLES
47
47
47
47
45
45
46
45
45
45
45
45
46
48
45
45
45
45
45
45
45
46
46
46
46
46
46
46
TOTAL
NUMBER
DETECT
O
16
1
O
1
3
0
O
1
1
3
2
0
O
2
2
3
5
6
5
5
0
0
O
0
o
o
0
NUMBER
SAMPLES
>10UG/L
O
10
0
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
0
o
0
o
o
o
o
DETECTED CONCENTRATIONS IN UG/L
MIN 10X MEDIAN
*
2211
3 * 3
*
6.40
2.24
,
,
2.24
2,24
0.10
2.24
»
,
2.24
2.24
0.2O
1.10
O.33
O.43
O.1O
.
.
.
.
.
.
6.40
2.24
.
.
2.24
2.24
1.17
2.24
.
.
2.24
2.24
1.22
2.24
1.40
2.24
1.23
.
.
MEAN 90% MAX
*
IB 4O 45
3
.
8.4O
2.26
,
.
2.24
2.24
1.52
2.24
.
,
2.24
2.24
1.S6
2.O8
1.47
1.87
t.41
,
,
.
.
.
.
.
3
.
6.40
2.3O
.
.
2.24
2.24
2.24
2.24
.
2-24
2.24
2.24
2. BO
2.24
2.24
2.24
.
.
.
. .
.
.
.
-------
Table V-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
ALL SUBCATEGORIES
TOXIC POLLUTANTS
o
U)
COMPOUND
TOXAPHENE
2,3.7 . 8-TETRACHLORODIBENZO-P-DIOXIN
ANTHRACENE/PHENANTHRENE
BENZOI A ) ANTHR ACENE/CHRYSENE
BENZO( 3 , 4/K )FLUORANTHEN£
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
46
49
45
19
16
1O3
104
1O4
1O4
104
104
57
104
104
1O4
1O4
1O4
1O4
1O4
TOTAL
NUMBER
DETECT
O
O
10
6
a
45
49
32
24
64
75
3
41
44
51
39
32
27
91
NUMBER
SAMPLES
MOUG/L
0
0
5
2
1
22
28
17
22
58
58
0
32
6
51
23
20
12
88
DETECTED CONCENTRATIONS IN
MIN
.
2
1
3
1
2
0
6
6
4
2
2
0.20
23
1
4
$
7
10%
*
*
2
*
*
2
2
1
10
10
a
*
3
O.33
40
3
5
1
IS
MEDIAN
.
3
3
3
7
38
10
17
50
20
4
67
1.10
153
22
13
9
99
MEAN
.
24
IS
4
40
345
39
42
288
429
B
491
4.99
729
66
18
26
1408
UG/L
90%
*
*
48
*
*
117
863
92
92
508
1145
*
1000
14.20
12 1O
213
31
66
2897
MAX
,
1O4
49
7
235
650O
450
290
7500
6500
8
BSOO
43.00
1OOOO
450
64
184
3OOOO
-------
Table V-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
ALL SUBCATEGORIES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS* TOTAL-FIBERS/LITER)
COO
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CACO3)
HO ALKALINITY (CACO3)
PHENOLICS(4AAP)
SULFATE
TOTAL ACIDITY (CAC03)
TOTAL SOLIDS
TOTAL
NUMBER
SAMPLES
98
100
1O5
103
1O
57
38
42
28
65
B6
6
33
58
8
1
35
TOTAL
NUMBER
DETECTS
97
100
1O4
94
9
52
38
41
22
S3
49
' B
33
11
a
i
35
DETECTED CONCENTRATIONS IN UQ/L
NIN
SCO
2.4
11
3
3500E3
4O
71000
10000
10OO
o.o
280
19OOO
1O
2
13OOOO
10500
18000O
10%
1S7O
3.6
2O9
25
*
818O
145000
43400
1080
O.O
1258
*
7967
2
*
*
31485O
MEDIAN
57BOO
7.5
2230
1075
1090E6
34000
73OOOO
222167
4800
0.7
14150
41000
190000
20
503333
10500
1326E3
MEAN
1016E4
6.9
257578
5190
9372E6
1009E4
1130E3
6968E3
1418E3
126. B
1322E3
181500
392425
33
659583
10500
9B89E3
90%
146OE4
8.2
687997
12600
*
3O94E4
2S80E3
2494E4
751992
378.7
3O22E3
*
587000
SO
*
*
1180E4
MAX
2400EB
9.4
9OOOE3
8OOOO
4100E7
222OE5
32OOE3
8O51E4
28OOE4
18OO.O
2847E4
740OOO
B400E3
155
1530E3
1050O
19OOE5
-------
evaluating common laboratory procedures. The analytical machines used
for these samples frequently have a significant degree of background
noise, often due to 60 Hz electrical frequencies and internal
electrical phenomena which on the readout can partially or totally
mask the signature of a compound. This level of noise is one factor
which is accounted for in the determination of the detection limit.
In most laboratory.analyses, the signatures of the desired compounds
that are partially masked can be identified by a skilled lab
technician. The concentration is thus reported as being detected, but
at less than the detection limit. For computational purposes, a
method for quantifying these detected values is needed. Thus, in the
accompanying tables, for values reported as "detected less than X,"
where X equals some detection limit, the value was calculated and
recorded on the table as 1/2 of X when X was less than 4 ug/1 and as
the square root of X when X was greater than 4 ug/1.
Fifth, some values were too large to put in a column in decimal
notation; these are recorded in exponential notation with an "E" prior
to an integer number of zeros. For example, on the sixth page of
Table V-4 for the total suspended solids mean value, a level of 1016E4
is recorded. This should be interpreted as 10,160,000 ug/1.
Sixth, to accurately analyze the data, factors which could bias the
data should be minimized or eliminated. Two particular instances
should be noted. First, each piece of data is coded according to a
number of identifying parameters, one of which is its sample type
(e.g., raw wasteload, partially treated stream, final discharge). To
include multiple analyses of the same raw effluent source would be
redundant and introduce bias. Thus, for four facilities (00013,
00014, 00009, 00010), multiple raw effluent points were averaged for
each facility to yield one raw effluent data point per facility. A
second similar situation occurred when multiple samples were taken of
the same sample point over a period of days. For instance, three days
of verification sampling of the same point were averaged to yield one
distinct data point before statistical calculations were performed.
This also avoids unnecessary bias.
Finally, three pairs of priority organic compounds cannot be
distinguished using GC/MS equipment. They are anthracene/
phenanthrene, benzo(a)anthracene/chrysene, and benzo(3,4)
fluoranthene/benzo(k)fluoranthene (abbreviated on the table as
benzo(3,4/k)fluoranthene). The dual compounds are reported prior to
the priority metals data as one concentration value for each pair.
The data for raw wastewater from coal mines for all proposed
subcategories are summarized in Table V-4. This table permits an
overview of the characterization of mine drainage. The following
subsections present sources and data on raw effluent for each proposed
subcategory.
Acid Mine Drainage
Formation of Acid Mine Drainage
105
-------
Iron sulfide, or pyrite, is a common substance formed from mineral
sulfur. It is this sulfur-containing compound that is a precursor to
acid mine drainage. As water drains across or percolates through
pyritic material, in the presence of oxygen, the formation of acid
drainage occurs in two steps (13, 12). The products of the first step
are ferrous iron and sulfuric acid as shown in equation 1.
2FeS
70
2FeS04 + 2H2S04
1)
The ferrous iron (Fe+2) then undergoes oxidation to the ferric state
(Fe+3) as shown in equation 2.
4FeS04 + 2H2S04
2Fez(S04)3 + 2H20
The reaction may proceed to form ferric hydroxide or basic ferric
sulfate as shown in equations 3 and 4 respectively.
Fez(S04)3 +
Fe2(S04)3 + 2H20
2Fe(OH)3 + 3H3=2S04
2Fe(OH(S04)) + H2S0
The ferric iron can also directly oxidize pyrite to produce more
ferrous iron and sulfuric acid as shown in equation 5.
FeS, + 14 Fe+3 + 8H,0
15 Fe+2 + 2S04-z
16H+
Thus, the oxidation of one mole of iron pyrite yields two moles of
sulfuric acid. As the pH of the pyritic systems decreases below five,
certain acidophilic, chemoautotrophic bacteria become active. These
bacteria, Thiobacillus ferroxidans, Ferrobacillus ferroxidans,
Metalloqenium, and species are active at pH 2.0 to 4.5 and use COZ as
their source (20). These bacteria are responsible for the oxidation
of ferrous iron to the ferric state, the rate limiting step in the
oxidation of pyrite. Their presence is generally an indication of
rapid pyrite oxidation and is accompanied by waters low in pH and high
in iron, manganese, and total dissolved solids. The acid formed from
these reactions is an effective extraction agent, causing trace
elements to be leached and dissolved into solution. The solubilities
of these substances, mostly heavy metals, are very sensitive to
changes in pH. This is illustrated in Figure V-l. The data on this
figure are derived from an experimental study of acid .mine drainage
(7), Acid drainage can be readily formed by rainfall upon either a
coal storage or a refuse pile. These wastewaters can be high in
certain metals concentration, especially after a substantial rainfall
event (12). Also, acid waters can be formed in underground mines and
aquifers if sufficient air is present to permit oxidation of pyritic
materials in either the coal seam or adjacent strata. The leaching
process is promoted by a long contact time for water and the sulfur-
containing material.
Characteristics of Acid Mine Drainage
106
-------
0.01
12
Figure V-l
CONCENTRATIONS OF CERTAIN ELEMENTS AS A FUNCTION OF pH
Source: (?)
107
-------
The principal pollutants in surface water from mines exhibiting acid
mine drainage include suspended and dissolved solids, pH, and certain
metal species. Causes for the formation of low pH and high metals
concentrations have just been discussed. In general, the problem of
acid mine drainage is confined to western Maryland, northern West
Virginia, Pennsylvania, Ohio, western Kentucky, and along the Illinois
- Indiana border. Acid drainage is not serious in the West because
the coals and overburden contain little pyrite and because the amount
of infiltration into spoils is low due to low rainfall (16, 15).
Suspended solids result from erosion of scarified areas, where
vegetation has been removed. The level of sediment concentration in
runoff is a function of the following:
1. Slope of the area
2. Residual vegetation
3. Soil type
4. Surface texture
5. Drainage area
6. Precipitation intensity and duration
7. Existing soil moisture
8. Particle or aggregate size.
The number and interaction of these variables render wide variations
in raw wastewater from day to day in any one mine, and from mine to
mine in a given region.
Dissolved solids can result from infiltration of precipitation that
leaches through spoil and coal piles. Acid leaching of soil and coal,
and ion exchange reactions of runoff and soil also cause the formation
of this pollutant. Calcium, magnesium, and sodium are the principal
dissolved materials in surface runoff. The factors affecting the
quantity of wastewater generated by a surface mine include:
1. Frequency, intensity, and duration of precipitation and snowmelt
events
2. The number, porosity and water content of any aquifers above or
including the coal seam that are mined through or breached
3. Drainage area
4. Soil porosity
5. Pump capacity and rate
6. Evaporation rate
7. Watershed slope and flow length.
Groundwater is the primary source of drainage from underground mining
sites. Underground operations in or below aquifers can cause
localized decline of the water table, changes in flow direction and
possible changes in flow rate (16). Lowering of water levels may
cause wells or springs in the vicinity to dry up. Fracturing as a
result of subsidence may similarly alter groundwater flow. In
addition, the presence of subsidence fractures and depressions at the
surface may increase groundwater recharge in the vicinity of the mine
(17). Underground mining may also cause degradation of groundwater
quality. Flow of groundwater through a mine with acid forming
108
-------
potential may result in leaching of soluble materials including trace
metals and other ions that will cause an increase in dissolved solids
content and may contaminate groundwater supplies.
During the screening phase, facilities 00005, 00012, 00017, 00018, and
00021 through 00024 were sampled. For facility 00012, drainage from
inactive mine areas was the source of acid drainage. Verification
sampling was conducted at mines 00198, 00021, 00023, 00188 through
00190, and 00197. Descriptions of the above facilities and treatment
process schematics, including sampling points, can be found in
Appendix F of the Proposed Coal Mining Development Document (EPA
440/1-81/057-b). Engineering site visits were conducted at mines
00035, 00038, and 00195. Data for toxic pollutants, and conventional
and nonconventional pollutants in untreated acid mine drainage appear
in Table V-5. As can be seen from the table, organics concentrations
are very low from these mining operations. In contrast, conventional
and toxic metals concentrations are often quite substantial. All raw
data are contained in Appendix B of the Proposed Coal Mining
Development Document (EPA 440/1-81/057-b).
Alkaline Mine Drainage
The discussion on sediment concentrations and wastewater quantity in
the acid mine drainage subsection is also applicable to alkaline mine
drainage and will not be repeated here. Facilities 00001, 00002,
00003, 00004, 00006, 00007, 00011, 00013, 00014, 00015, 00016, 00019,
00020, and 00025 were sampled during the screening phase. During
verification sampling, mines 00011, 00018, and 00025 were revisited
and mines 00009 and 00010 were sampled for the first time. Mine 00018
is also listed under acid mines during the screening phase because it
possesses both acid raw effluents and alkaline raw effluents. These
samples were appropriately divided and recorded on the proper table.
Descr ipt ions of the above fac i1i t i es and treatment schemat i cs,
including sampling points, can be found in Appendix F of the Proposed
Coal Mining Development Document (EPA 440/1-81/057-b). Mines 00009,
00032, 00033, 00034, 00036, 00037, 00103, 00107, 00193, 00194, and
00196 were sampled during the engineering site visits. EPA Region 8
sampled mines 00029 and 00030. EPA Region 4 sampled facility 00031.
Data for toxic pollutants and conventional and nonconventional
pollutants from all these sources are summarized in Table V-6. As
shown on the table, organics concentrations and metals concentrations
are both very low. Further, conventional pollutants with the
exception of TSS are very low. The raw data are contained in Appendix
B of the Proposed Coal Mining Development Document.
Preparation Plants
Wastewater is generated in a coal preparation plant from the coal
cleaning process. Flow rates vary widely depending upon certain
factors such as the degree of cleaning, the equipment or processes
used, and the characteristics of the run-of-mine coal. Each of these
factors was discussed in detail in Section IV. Physical coal cleaning
removes impurities from coal via a mechanical separation process. In
109
-------
Table V-5
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1.2. 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
. 2-DICHLOROETHANE
. 1 , 1-TRICHLOROETHANE
HEXACHLOROETHANE
. 1-DICHLOROETHANE
, 1 . 2-TRICHLOROETHANE
,1,2 . 2-TETRACHLOROETHANE
CHLOROETHANE
BIS (CHLOROMETHYL) ETHER
BIS< 2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2 -CHLORONAPHTHALENE
2,4, 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 ,2-DICHLOROBENZENE
1 , 3-DICHLOROBENZENE
1 , 4-DICHLOROBENZENE
3 . 3-DICHLOROBENZIOINE
TOTAL
NUMBER
SAMPLES
17
16
16
16
17
16
16
17
17
16
16
17
IB
16
16
16
16
17
16
17
14
14
16
14
17
17
17
16
TOTAL
NUMBER
DETECT
0
0
O
6
O
O
O
O
O
O
O
O
O
0
0
0
O
O
0
0
O
O
9
0
0
0
O
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
MOUG/L MIN 10% MEDIAN MEAN 9O% MAX
o
O
o .
4 2
0
O
o
0
o
o
o
o
o
o
o
o
o
o
0
o
0
0
9 16
0
0
o
o
o
16 20
m B
. .
. u
, .
, .
. ,
. .
. .
. .
, .
. .
. .
. .
. .
. .
34 1O1
. .
.
.
,
.
40
.
.
.
.
,
.
.
.
.
.
.
.
442
.
.
.
-------
Table V-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
1. 1-DICHLOROETHYLENE
1 , 2-TRANS-DICHLOROETHYLENC
2 , 4-DICHLOROPHENOL
1 , 2-DICHLOROPROPANE
1 , 3-DICHLOROPROPENE
2 . 4-DIMETHYLPHENOL
2, 4-DINITROTOLUENE
2,8-DINITROTOLUENE
1 , 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BIS(2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE ( DICHLOROMETHANE )
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUQROMETHANE
DICHLORODIFLUOROMETHANE
CHLORODI BROMOMETHANE
HE XACHLOROBUTAO I ENE
HEXACHLOROCYCLOPENTAOIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
18
16
14
18
18
14
17
17
17
17
17
17
17
17
17
18
16
16
18
16
16
16
18
17
17
17
17
17
TOTAL
NUMBER
DETECT
O
1
O
O
O
0
0
0
0
2
0
0
O
O
O
16
O
0
0
0
O
O
0
O
0
0
3
O
NUMBER DETECTED CONCENTRATIONS IN UG/L
SAMPLES
MOUG/L MIN 10% MEDIAN MEAN 90% MAX
0
0 1O
0
0
o
O
0
o
0
0 2
0
0
0
o
o
15 7 1
0
O
0
O
0
0
0
o
0
o
1 2
0
10 10
. .
2 3
487 1B98 380<
. .
. .
. .
4 8
. .
10
.
.
,
,
,
.
.
. 4
.
.
.
.
,
11190
.
.
.
.
.
.
.
.
,
.
1O
.
-------
Table V-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
2-NITROPHENOL
4-NITROPHENOL
2,4-DINITROPHENOt
4.B-DINITRO-0-CRESOL
N-NITROSODIMETHYLAMXNE
N-NITROSODIPHENYLAMINE
N-NITROSOOI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL> PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
DXETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO( A) ANTHRACENE
BENZO(A)PYRENE
BENZO(B)FLUORANTHENE
BENZO(K)FLUORANTHEN£
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO(G.H. I >PERYLEN£
FLUORENE
PHENANTHRENE
DIBENZO(A.H)ANTHRACEHE
INDENO(1.2,3-C.D)PYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
14
14
14
14
17
17
17
14
14
17
17
17
17
17
17
14
17
17
17
14
17
14
17
17
14
17
17
17
TOTAL
NUMBER
DETECT
0
O
O
O
0
O
O
O
0
10
0
a
0
5
O
O
3
0
3
O
O
O
3
1
1
2
2
1
NUMBER
SAMPLES
MOUG/L
O
O
0
0
O
O
O
0
0
8
O
3
0
1
0
O
O
0
2
O
O
O
O
O
1
O
O
0
DETECTED CONCENTRATIONS IN UQ/L
M1N 10% MEDIAN
.
*
.
,
,
.
.
B
3
,
2
.
1
p
f
1
,
1
,
,
.
1
1
12
6
7
1
.
.
10
.
3
m
2
.
m
1
.
4
.
4
1
12
8
7
1
MEAN 90% MAX
^
.
,
,
^
m
,
.
21 4
,
B
f
B
,
m
1
.
B
,
.
9
6
1
12
8
8
1
^
,
m
.
.
f
t
62
f
11
B
23
,
.
2
.
11
,
.
,
10
1
12
10
10
1
-------
Table V-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
oo
COMPOUND
TETRACHtOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4,4-DDT
4,4-DDE
4,4-DDD
ENDOSULFAN-ALPHA
ENDOSULFAN-BETA
ENOOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE
BHC- ALPHA
BHC- BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-126O (AROCHLOR 1260)
PCB-1O16 (AROCHLOR 1016)
TOTAL
NUMBER
SAMPLES
16
IS
16
16
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
TOTAL
NUMBER
DETECT
0
7
0
0
O
0
0
o
0
0
0
o
0
o
o
1
o
1
1
o
1
0
o
0
0
o
0
0
NUMBER DETECTED CONCENTRATIONS IN UG/L
SAMPLES
>10UG/L MIN 10X MEDIAN MEAN 90X MAX
0
4 2
0
0
0
o
0
0
0
0
O
0
o
0
0
0 2.24
0
0 2.24
0 2.24
0
O 2.24
0
O
O
0
0
0
0
1O 15
9 9
.
t t
. ,
„ ,
f m
t m
. .
4 .
t 9
t
.
m 9
2.24 2.24
f m
2.24 2.24
2.24 2.24
, .
2.24 2.24
. .
. .
.
. .
. .
, .
.
45
w
,
f
,
,
,
m
,
.
.
.
,
.
2.24
.
2.24
2.24
.
2.24
.
.
.
,
.
-------
Table V-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
TOXAPHENE
2.3,7,8 -TETRACHLOROOI BENZO-P-DIOXIN
ANTHRACENE/PHENANTHRENE
BENZO( A ) ANTHRACENE/CHRYSENE
BENZOC 3 . 4/K ) FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL.)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER. (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
14
17
14
5
2
22
23
23
23
23
23
18
23
23
23
23
23
23
23
TOTAL
NUMBER
DETECT
0
O
3
1
0
9
13
7
3
11
17
O
6
12
13
12
10
7
21
NUMBER
SAMPLES
>10UG/L
0
O
2
O
O
1
8
4
2
11
IS
O
5
O
13
7
7
2
21
DET
MIN
.
2
1
.
1
2
7
10
14
5
.
8
O.4O
23
2
4
1
11
ECTED C
10%
*
*
*
*
*
*
2
*
*
14
7
*
*
O.46
28
2
4
*
29
ONCENTW
MEDIAN
,
8
1
,
2
23
12
11
47
29
,
27
1.30
125
17
11
1
420
kTIONS
MEAN
,
15
1
,
5
89
18
40
128
133
^
147
1.73
489
25
14
4
932
IN UQ/L
90X
*
*
*
*
*
*
189
*
*
177
174
*
*
3.14
1000
55
29
*
2209
MAX
.
28
1
,
26
51O
34
98
780
1290
4
405
4.10
2O20
59
31
14
662O
-------
Table V-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ACID DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
MIN
DETECTED CONCENTRATIONS IN UQ/L
10X MEDIAN MEAN 90% MAX
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS(TOTAL-FIBERS/LITER)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CAC03)
MO ALKALINITY (CACO3)
PHENOLICSMAAP)
SULFATE
TOTAL SOLIDS
23
25
23
23
2
18
14
11
7
13
18
B
9
18
7
11
22
2B
23
22
1
IB
14
11
8
9
17
5
B
1
7
11
98OO
2.S
77
22
3SOOE3
5100
71OOO
30OOO
1400
O.O
26O
19OOO
10
8
130OOO
37OOOO
11040
3.2
588
283
*
9050
71800
312OO
3O
378000
65OOO
S.9
12387
4300
35OOE3
43150
450000
320250
4000
1.O
9150
345OO
39OOO
8
678333
3600E3
1O33E4 2964E3 218OES
5.8 7.9 8.8
198222 217500 2790E3
8323 124OO 63OOO
3500E3 * 3SOOE3
8O27E3 919999 88OOE4
85S762 1537E3 2130E3
812818 12S2E3 14OOE3
153100
7O.8
289821 189
69800
54890
8
709524
890000
600.0
00 441OE3
180000
120000
a
1B30E3
3739E3 874OE3 82OOE3
-------
Table V-6
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1.2. 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
, 2-DICHLOROETHANE
. 1 . 1-TRICHLOROETHANE
HEXACHLOROETHANE
, 1 -DICHLOROETHANE
. 1 . 2-TRICHLOROETHANE
.1,2. 2-TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL> ETHER
2-CHLOROETHVL VINYL ETHER (MIXED)
2 -CHLORONAPHTHALENE
2.4, 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 ,2-DICHLORQBENZENE
1 . 3-DICHLOROBENZENE
1 . 4-DICHLOROBENZENE
3 , 3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
21
2O
20
20
21
20
19
21
21
2O
2O
21
20
20
20
2O
20
21
20
21
21
21
2O
21
21
21
21
21
TOTAL
NUMBER
DETECT
O
0
O
3
O
O
O
O
O
O
2
O
O
o
o
o
0
o
0
o
o
o
12
O
2
O
1
o
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UG/L MIN 10% MEDIAN MEAN 00X MAX
O .
o
O
1 3
O
0
0
o
o
o
O 3
0
0
o
o
o
a
o
0
o
o
o
10 3
o
1 3
o
0 3
0
3 2fl
. ,
3 3
32 78 12
. .
3 11
. .
3 3
. .
.
73
.
.
.
.
9
3
f
f
.
^
f
m
,
m
,
,
,
488
.
18
.
3
.
-------
Table V-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
1 , 1-DICHLOROETHYLENE
1 ,2-TRANS-DZCHLOROETHYLENE
2 , 4-DICHLOROPHENOL
1 , 2-DXCHLOROPROPANE
1 , 3-DICHLOROPROPENE
2 . 4-DXMETHYLPHENOL
2,4-DINITROTOLUENE
2.B-DXNITROTOLUENE
1 . 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BIS(2-CHLOROETHOXY) METHANE
HETHYLENE CHLORIDE (DXCHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DXCHLOROBROMOMETHANE
TRXCHLOROFLUOROMETHANE
DXCHLORODIFLUOROMETHANE
CHCORODI BROMOMETHANE
HEXACHLOROBUTAOIENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
20
20
21
20
20
21
21
21
21
20
21
21
21
21
21
20
20
20
20
20
20
20
20
21
21
21
21
21
TOTAL
NUMBER
DETECT
3
0
O
0
0
0
O
O
O
1
0
O
0
0
O
19
O
O
0
0
O
O
0
0
0
0
1
O
NUMBER DETECTED CONCENTRATIONS IN UO/L
SAMPLES
>100Q/L MIN 1OX MEDIAN MEAN 90% MAX
0 3
o
O
o
0
o
0
o
o .
t 11
0
o
0
0
o
13 3
O
0
o
0
o
0
o
0
0
0
1 11
o
33 3
, .
. .
. ,
. ,
. .
. .
B u
f t
11 11
m i
.
^ B
. ,
. ,
533 1 1S2 245
. ,
a 9
m m
m u
, .
, .
t .
m m
t f
, .
11 11
. .
,
,
.
.
.
.
m
.
11
B
.
,
u
.
89B4
.
,
^
.
11
.
-------
Table V-6 (Continued)
VASTEUATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
CO
COMPOUND
TETRACHLOROETHVLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4.4-DDT
4.4-DDE
4,4-ODO
ENDOSULFAN- ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR EPOXIDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-12S4 (AROCHLOR 12S4)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCS- 1260 (AROCHLOR 12BO)
PCB-1016 (AROCHLOR 1O16)
TOTAL
NUMBER
SAMPLES
2O
20
20
2O
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
TOTAL
NUMBER
DETECT
0
3
O
O
O
O
O
O
0
O
O
O
O
O
0
O
O
1
1
2
O
O
O
0
O
O
O
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>100Q/t MIN 1O% MEDIAN MEAN »OX MAX
O .
3 11
O
O
O
O
O
o
O
o
o
0
o
o
o
o
o
O 1.1O
O O.40
O 2.24
O
O
O
O
O
O
O
0
26 3O
t
t
t
m
9
m
t
.
,
,
t
9
1.10 1
O.40 O
2.24 2
10
40
24
40
m
,
.
m
f
m
t
,
.
m
,
t
m
f
,
1.10
0.4O
2.24
,
m
,
.
.
.
.
.
-------
Table V-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
2-NITROPHENOL
4-NXTROPHENQL
2,4-DINITROPHENOL
4 . 6-DIN1TRO-0-CRESQL
N-NITROSOOIMETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BXS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
D I ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZOt A) ANTHRACENE
BENZO(A)PYRENE
BENZOt B) FLUOR ANTHENE
BENZO( K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZOt G,H, I )PERYLENE
FLUORENE
PHENANTHRENE*
OIBENZO(A.H)ANTHRACENE
JNOENO(1,2,3-C.D)PYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
TOTAL
NUMBER
DETECT
0
0
0
0
O
O
O
O
2
4
1
6
0
2
O
0
0
O
0
0
0
0
1
O
0
1
1
O
NUMBER
SAMPLES
MOUG/L
O
0
O
0
O
0
O
O
0
1
0
0
0
0
0
0
O
0
0
0
0
O
0
O
O
0
0
O
DETECTED CONCENTRATIONS IN UO/L
MIN 1OX MEDIAN
.
.
.
,
.
.
,
3
3
3
3
»
3
.
.
.
,
.
.
.
,
3
.
.
3
3
.
B
t
.
.
3
3
3
3
.
3
.
.
.
.
.
.
3
.
.
3
3
.
MEAN 90% MAX
t
m
.
,
f
m
f
3
e
3
3
m
3
,
,
.
,
.
.
.
,
3
.
m
3
3
.
.
.
r
9
9
m
f
3
14
3
3
,
3
f
,
,
,
.
.
,
,
3
.
.
3
3
.
-------
Table V-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
ro
o
COMPOUND
TOXAPHENE
2.3.7. 8-TETRACHLORODIBENZO-P-DIOXIM
ANTHRACENE/PHEMANTHRENE
BENZO( A ) ANTHRACENE/CHRYSENE
DENZO ( 3 , 4/K ) FUJORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
21
21
20
7
7
44
44
44
44
44
44
28
44
44
44
44
44
44
44
TOTAL
NUMBER
DETECT
0
O
1
0
O
14
10
4
0
23
24
3
15
20
13
11
8
7
39
NUMBER
SAMPLES
>10UG/L
O
0
o
0
o
4
2
0
5
21
12
O
a
i
13
2
S
2
32
DETECTED CONCENTRATIONS
MIN
,
3
.
.
1
2
O
8
a
4
2
2
0.27
30
2
10
1
7
10%
*
*
*
*
*
1
2
*
*
8
S
*
2
O.30
3O
2
*
*
11
MEDIAN
.
3
.
.
3
4
1
15
39
1O
4.
15
O.S5
02
3
13
2
50
MEAN
,
3
.
.
7
11
1
14
43
13
0
33
1.47
88
2O
14
8
81
IN UQ/L
80%
*
*
*
*
*
IB
21
*
*
85
28
*
80
1.87
17O
23
*
*
133
MAX
.
3
.
.
27
72
2
21
109
42
8
94
13.00
305
10O
22
23
1100
-------
Table V-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS MIN
DETECTED CONCENTRATIONS IN UQ/L
10% MEDIAN MEAN 90% MAX
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS(TOTAL-FIBERS/LITER)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
MO ALKALINITY (CACO3)
PHENOLICS(4AAP)
TOTAL ACIDITY (CACO3)
TOTAL SOLIDS
4O
4O
44
43
7
28
10
20
IS
24
27
17
27
1
18
40
4O
43
35
7
26
16
19
10
2O
22
17
6
1
18
BOO 16OO
6.3 7.O
11 113
3 8
33OOE4 *
40 7000
8SOOO 203200
10000 51700
1OOO 1000
O.O 0.0
5533 6800
4OOOO 820OO
2 *
10500 *
260000 288000
16400
7.8
384
142
109OE6
17200
880OOO
136500
2800
0.1
1OB33
295OOO
16
10500
920000
80078 2O9999 8710OO
7,8 8.3 9.4
1842 27 1O 3904O
520 923 7000
1132E7 * 41OOE7
15662O 898B7 3260E3
1315E3 294OE3 3200E3
3785E3 681586 6700E4
24280 12000 2OOOOO
99. 0 1O. O 1800.0
32770 S7407 1330OO
331353 S83OOO 6OOOOO
18 * 40
105OO * 10500
1188E4 3292E3 19OOE5
-------
most cleaning operations, this separation of impurities is based on a
specific gravity difference between less dense coal and heavier
contaminants such as sulfur, ash, and rock. Sulfur occurs in a coal
seam in three forms: as pyrites, in organic compounds, and as
sulfate. In coal, the sulfur contribution from sulfate is almost
always negligible. The total sulfur content may vary from less than
one percent to over eight percent; most bituminous coals are in the
two to five percent range.
The total sulfur content distribution between the organic and pyritic
forms ranges from 5 to 60 percent and 40 to 95 percent, respectively.
Organic sulfur in coal is chemically bound and requires a chemical
extraction process for removal; physical coal cleaning is restricted
to removal of ash, refuse, and the pyritic sulfur (FeS2) from coal.
In the physical cleaning processes, water is most often used to assist
in the removal of unwanted components. The water consumption and
usage in a preparation plant was discussed in the previous section.
Effluents are most often laden with suspended coal and refuse fines.
This slurry is generally dewatered by mechanical or thermal drying
equipment internal to the preparation plant, with the water recycled
and the partially dewatered, solids-laden slurry discharged to a
dewatering and slurry treatment system. Clarified water from this
section can often be recycled to the preparation plant to reduce
makeup water needs as well as lessen the quantity of final discharge
to a receiving stream.
Facilities 00003 through 00005, 00007, 00008, 00011 through 00014,
00017, 00019 through 00022, 00024, and 00025 were sampled during the
screening phase of sampling. During verification, preparation plants
00011, 00021 and 00025 were revisited and sampled and facilities 00018
and 00023 were sampled for the first time. Engineering site visits
were conducted at preparation plants 00032 through 00035. Analytical
results of the untreated wastewater for each of these facilities are
summarized on Table V-7, with the raw data in Appendix B of the
Proposed Co"al Mining Development Document (EPA 440/1-81/057-b). The
flow charts and a description for each facility may be found in
Appendix F in the Proposed Coal Mining Development. The high metals
concentrations are the result of coal and refuse fines found in a
preparation process slurry effluent. The suspended solids levels in
some of these slurries can be quite high if no fines recovery or
removal is practiced.
Preparation Plant Associated Areas
The principal source of drainage in preparation plant associated areas
is precipitation-induced runoff. Three areas generating drainage can
be delineated as follows: 1. Coal storage piles 2. Refuse piles 3.
Other disturbed areas.
Coal Storage Piles
The quantity and quality of wastewater generated by drainage through a
coal storage pile are highly variable, depending upon rainfall
122
-------
Table V-7
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
ru
U)
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1 . 2 . 3-TRICHLOROBENZENC
HEXACHLOROBENZENE
1 . 2-DICHLOROETHANE
t , 1 , 1 -TRICHLOROETHANE
HEXACHLOROETHANE
1,1-DICHLOROETHANE
1 . 1 , 2-TRICHLOROETHANE
1.1.2.2 -TETR ACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHLOROETHVL VINYL ETHER (MIXED)
2-CHLORONAPHTHALENE
2 . 4 , 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 . 2-DICHLOROBENZENE
1 . 3-DICHLOROBENZENE
1 . 4-DICHLOROBENZENE
3 . 3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
7
-7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
3
O
O
2
O
0
o
0
o
o
2
0
o
o
0
o
o
o
0
1
o
o
2
1
0
o
o
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UG/L MIN 10% MEDIAN MEAN 80% MAX
03 33 3
0
0 .
1 3
0 t
o
o .
0 f
o
o
1 3
0
o
O
o
o
o
o
o
0 3
O
0
1 S
1 86
0
0
O
O
3 8
, B
^ t
3 13
9 ,
a 9
. ,
, .
, .
, B
. .
. .
3 3
. .
. .
S 17
88 88
. ,
. ,
, ,
.
.
^
IS
^
,
f
t
f
m
23
m
m
.
.
,
u
.
.
3
29
88
*
.
-------
Table V-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
ro
COMPOUND
1 . 1-DtCHLOROETHYLENE
1 . 2-TRANS-DICHLOROETHYLENE
2.4-DICHLOROPHENOL
1 .2-DICHLOROPROPANE
1 . 3-DICHLOROPROPENE
2 . 4-DIMETHYLPHENOL
2 . 4-OINITROTOUIENE
2.6-DINITROTOLUENE
1 , 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS<2-CHLOROISOPRQPYL) ETHER
BISC2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHAME
DICHLORODIFLUOROMETHANE
CHLOROOIBROMOMETHANE
HEXACHLOROBUTADI ENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
O
0
0
0
O
3
1
1
1
1
5
1
O
O
O
4
O
0
O
O
0
O
O
O
0
1
6
1
NUMBER
SAMPLES
>100Q/L
O
O
O
O
O
3
1
1
O
O
2
O
O
O
O
2
O
0
O
O
O
O
0
O
O
1
4
1
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
,
.
,
,
IS
18
30
3
3
3
3
.
.
.
3
.
,
,
.
m
m
fc
.
,
3O7
3
21
.
.
.
^
2O
IB
30
3
3
3
3
f
,
.
7
,
,
m
9
307
43
21
MEAN 9O% MAX
*
*
.
.
m
21
18
30
3
3
6
3
,
,
,
125
m
m
r
f
f
,
.
,
307
121
21
,
,
.
24
18
3O
3
3
11
3
f
t
f
292
.
.
.
.
.
a
.
.
307
410
21
-------
Table V-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
ro
ui
COMPOUND
2-NITROPHENOL
4-NITROPHENOt
2,4-DINITROPHENOL
4 , 6-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS<2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
OI-N-OCTYL PHTHALATE
PI ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO(A)ANTHRACENE
BENZO(A)PYRENE
BENZO { B )FLUORANTHENE
BENZO(K)FLUORANTHENE
CHftYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO ( G , H , 1 )PERYLENE
FLUORENE
PHENANTHRENE
DI BENZO ( A, H) ANTHRACENE
INDENO( 1.2,3-C,D)PYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
1
0
O
1
O
1
0
0
4
5
3
5
1
4
1
O
4
0
O
0
1
0
3
4
0
2
1
B
NUMBER
SAMPLES
>10UG/L
1
0
O
1
O
1
0
0
i
3
O
0
O
O
0
0
2
0
0
0
1
0
t
2
O
0
0
2
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
17 17
f
.
194
t
45
.
.
3
3
3
3
3
3
3
.
3
f
t
.
9
^
3
3
f
3
3
3
.
194
.
45
3
6
3
a
3
3
3
t
3
.
.
.
9
.
3
3
.
3
3
3
MEAN 90X MAX
17 17
194
f
45
B
19
3
3
3
3
3
.
40
.
.
9
.
4
17
f
3
3
1O
.
194
.
45
18
48
3
3
3
3
3
.
141
.
.
9
.
7
44
m
3
3
25
-------
Table V-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
ru
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELORIN
CHLOROANE
4.4-ODT
4.4-DDE
4.4-DDD
ENDOSULFAN-ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR EPOXIDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PC8-12S4 (AROCHLOR 12S4)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCS- 1248 (AROCHLOR 1248)
PCB-12BO (AROCHLOR 1260)
PCS -10 16 (AROCHLOR 1016)
TOTAL
NUMBER
SAMPLES
7
7
7
7
6
6
7
6
6
8
6
6
7
7
a
6
8
8
6
8
8
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
O
3
1
O
1
3
O
O
1
1
3
2
O
O
2
1
3
3
3
3
3
O
O
O
O
O
O
0
NUMBER
SAMPLES
>10UG/L
O
1
O
O
O
O
O
0
O
O
O
O
O
O
O
0
O
O
O
O
O
0
O
0
O
0
0
O
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
3
3
.
6.4O
2.24
.
,
2.24
2.24
O.1O
2.24
.
B
2.24
2.24
O.2O
2.24
1.40
0.43
O.23
.
.
.
.
.
.
.
3
3
.
6.40
2.24
f
9
2.24
2.24
1.17
2.24
f
2.24
2.24
1.22
2.24
1.82
1.33
1.23
MEAN 80% MAX
* *
S
3
T
6.40
2.26
.
»
2.24
2.24
1.52
2.24
.
^
2.24
2.24
1.S6
2.36
1.86
1.63
1.S7
,
,
.
.
B
.
.
9
3
.
6.40
2.30
.
.
2.24
2.24
2.24
2.24
.
m
2.24
2.24
2.24
2.80
2.24
2.24
2.24
a
.
,
.
,
.
,
-------
Table V-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
COMPOUND
TOXAPHENE
2.3,7.8 -TETRACHLOROOIBENZO-P-DIOXIN
AKTHRACENE/PHENANTHRENE
BENZOC A ) ANTHRACENE/CHRYSENE
BENZOC 3 , 4/K )FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
•SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
7
•7
7
6
- 8
13
13
13
13
13
13
7
13
13
13
13
13
13
13
TOTAL
NUMBER
DETECT
O
O
6
5
3
6
12
a
e
11
13
0
12
7
10
10
8
9
12
NUMBER
SAMPLES
>10UG/L
O
O
3
-2
1
3
12
8
•6
11
13
O
12
4
10
9
6
4
12
DETECTED CONCENTRATIONS
MIN
.
3
3
3
2
37
3
13
29
100
.
24
1.00
300
3
6
7
480
10%
*
*
*
*
*
*
40
*
*
36
138
*
33
*
300
3
*
*
846
MEDIAN
.
3
4
3
2
240
36
34
418
1180
.
76O
11.25
933
40
22
9
2867
MEAN
.
32
18
4
18
1072
93
102
126O
2106
.
1453
17.85
1537
137
29
18
4464
IN UQ/L
90%
*
*
*
*
*
*
2408
*
*
2582
6280
*
4287
*
2800
350
*
*
9860
MAX
.
104
49
7
50
6500
450
290
750O
65OO
.
5500
43.00
5500
410
84
31
13500
-------
Table V-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY PREP PLANTS
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
ro
oo
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS ( TOTAL-FIBERS/LITER )
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
MO ALKALINITY (CAC03)
PHENOLICSMAAP)
TOTAL SOLIDS
TOTAL .
NUMBER
SAMPLES
12
12
13
13
1
7
5
7
2
11
7
S
7
2
NUMBER
TOTAL
DETECTS
12
12
13
13
1
7
B
7
2
11
7
5
4
2
DETECTED CONCENTRATIONS
MIN
9131E3
4.2
7000O
1O75
B1OOE6
1470E4
8SOOOO
7S67E3
20OOE3
56.3
11OOE3
160000
20
9BOOE3
10%
9776E3
4.7
77200
1262
B
.7
MEDIAN
3440E4
7.3
676250
6067
S100E6
3430E4
1O55E3
2191E4
2OOOE3
224.3
4137E3
26OOOO
2B
9600E3
MEAN
6244E4
7.2
825372
8337
B1OOE8
6123E4
1372E3
2893C4
15OOE4
367.4
S446E3
1356E3
63
2380E4
IN UQ/L
90%
187SEB
8.0
18SOE3
17900
83
.0
MAX
2400ES
8.1
23OOE3
250OO
51OOE6
2220ES
25OOE3
8O91E4
28OOE4
880.0
2847E4
S400E3
IBS
3800E4
-------
conditions, pile configuration, and coal quality and size. The
phenomena responsible for the formation of acid mine drainage in the
active mining area can also operate within the coal storage pile. The
outer layer of a coal pile (to a depth of approximately one foot) is
subject to slacking. Slacking refers to rapid changes in moisture
content brought about by alternating sun and rain. This often opens
up fresh surfaces and accelerates oxidation. Although organic
leaching rates are very low, specific inorganic coal components, such
as calcium, magnesium, and toxic metals may be contained in the
wastewater. Erosion of waste coal fragments can result in high
suspended solids levels (19). Pollutants can be leached into any
water contacting the coal storage pile. The composition of pile
drainage- is influenced by the residence time of the water within the
pile. Precipitation will wash this leachate from the pile, so that
contaminant concentrations will decrease with increasing water flow
rate, until the time that this flushing is complete.
Refuse Piles
Mining, crushing, and washing processes concentrate the coal
impurities in the refuse. Extraneous metals and other minerals are
separated from the coal and may appear in refuse pile runoff. As most
coal-cleaning methods employ gravity separation, dense materials such
as clays, shales, and pyrite will be removed as refuse (13). These
will contribute to suspended solids levels in the wastewater, while
oxidation of the pyrite will produce acid drainage. Organic sulfur
and fine pyrite cannot easily be extracted from coal (12), so that
these forms do not contribute as significantly to sulfate formation.
The relative acidity and pollutant levels of refuse pile drainage are
dependent upon the following:
1. Mineral characteristics of the coal and surrounding strata
2. Extent of refuse compaction
3. Configuration of the refuse pile
4. Type of soil cover
5. Climatology
6. Surface water control practices
Other Disturbed Areas
Other disturbed areas ancillary to the preparation plant are analogous
to those associated with mines, e.g., adjacent haul roads. As is the
case for mines, suspended solids is the primary pollutant of concern
in runoff. Screening samples were collected from associated areas at
facilities 00016, 00017, 00018, and 00024. Facility 00018 was
resampled during the verification phase. Preparation plant associated
areas at facilities 00034, 00038, and 00036 were sampled during the
engineering site visits. Descriptions of treatment processes,
including sampling points, can be found in Appendix F of the Proposed
Coal Mining Development Document (EPA 440/1-81/057-b). A summary of
the organic, metal and classical pollutants found during the screening
and verification sampling programs appears in Table V-8.
129
-------
Table V-8
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
u>
o
TOTAL TOTAL
NUMBER NUMBER
COMPOUND SAMPLES DETECT
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIOE
CHLOROBENZENE
1,2. 3-TRICHLOROBENZENE
KEXACHLOROBENZENE
. 2-DICHLOROETHANE
, 1 . 1-TRICHLOROETHANE
HEXACHLOROETHANE
. 1 -DICHLOROETHANE
. 1 ,2-TRICHLOROETHANE
.1.2.2 -TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2-CHLORONAPHTHALENE
2,4. 6-TRICKLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 . 2-DICHLOROBENZENE
1 . 3-DICHLOROBENZENE
1 . 4-DICHLOROBENZEME
3 . 3-DICHLOROBENZIDINE
O
O
O
2
O
O
1
0
0
o
0
o
o
o
o
0
0
0
0
o
o
o
2
0
0
o
0
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UG/L MIN 10% MEDIAN MEAN BOX MAX
O .
O
O
2 44
O
O
1 12
0
O
O
O
o
o
o
o
o
o
o
o
0
o
o
2 45
O
O
O
o
o
a 9
* a
44 46
12 12
45 261
.
.
48
.
12
,
t
,
m
t
t
,
,
,
.
.
,
,
m
f
476
^
.
.
.
.
-------
Table V-8 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
U)
COMPOUND
1, 1-DICHLOROETHYLENC
1 ; 2-TRANS-DICHLOROETHYLENE
2 . 4-DICHLOROPHENOL
1 ,2-DICHLOROPROPANE
1 .3-DICHLOROPROPENE
2 . 4-DIMETHYLPHENQL
2,4-DIHITROTOLUENE
2.Q-DINITROTOLUENE
1 , 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS12-CHLOROISOPROPYL) ETHER
biS<2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE ( DICHLOROMETHANE )
METHYL CHLORIDE
METHYL BROMIDE
BROHOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHANE
DICHLORODIFLUOROMETHANE
CHLORODIBROMOMETHANE
HEXACHLOROBUT ADI ENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
TOTAL
NUMBER
DETECT
O
O
0
O
O
0
0
0
0
O
0
O
O
O
0
4
0
0
O
0
0
O
0
0
O
0
O
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
MOUG/L MIN tOX MEDIAN MEAN 9OX MAX
0 .*..*.
O .*..*.
O
O
O
0
O
0
O
0
0
0
0
O
O
4 1B2
O
O
0
0
0
0
0
O
0
0
O
0
34B 783
. .
. .
. .
. .
,
, .
.
.
.
.
.
.
.
,
.
,
.
144O
.
» .
.
.
.
,
-------
Table V-8 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORV ASSOCIATED AREAS
TOXIC POLLUTANTS
UJ
f\>
TOTAL TOTAL
NUMBER NUMBER
COMPOUND SAMPLES DETECT
2-NITROPHENOL
4-N1TROPHENOL
2 , 4-DINITROPHENOL
4.B-DINITRO-O-CRCSOL
N-NITROSODIMETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
DXETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO( A) ANTHRACENE
B£NZO(A)PYRENE
BENZO( B >FLUORANTHENE
BENZO ( K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO(G.H. I )PERYLENE
FLUORENE
PHENANTHRENE
DIBENZO( A . H ) ANTHRACENE
INDENOC 1.2. 3-C. D)PYRENE
PYRENE
0
O
O
O
O
O
0
0
O
2
0
O
0
O
O
0
O
O
0
0
0
O
O
0
O
0
O
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UG/L MIN 10% MEDIAN MEAN SOX MAX
0 .
O
0 m
o
0
o .
o .
0
o .
O 3
O
0
o
o
o
o
0
o
0
o
o
o
o
0
o
0
o
o
3 7
,
.
.
't [
.
.
.
.
.
10
.
.
.
-------
Table V-8 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
CO
U)
TOTAL TOTAL
NUMBER NUMBER
COMPOUND SAMPLES DETECT
TETRACHLOROETHYLENE O
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4,4-OOT
4.4-DOE
4.4-DOD
ENDOSULFAN-ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRXN
ENORIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE
BHC-ALPHA
8HC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCS- 1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
3
O
0
0
0
O
0
0
0
O
O
0
O
0
O
0
0
1
O
1
0
0
0
O
0
PCB-1280 (AROCHLOR 12BO) 4 0
PCB-IOta (AROCHLOR 1018) 4 O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UQ/L MIN 10% MEDIAN MEAN ftOX MAX
O .
2 1O
O
O
0
o
O
o
o
0
o
o
0
o
0
0
0
o
O O.33
0
O O.1O
0
o
0
0
o .
0
o
12 17
. .
• •
,
.
.
.
,
.
.
.
.
,
,
.
.
.
O.33 0
.
O.1O O
33
10
.
, .
. .
.
27
^
.
o
O
33
10
»
.
•
.
.
.
.
-------
Table V-8 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
COMPOUND
TOXAPHENE
2.3.7. 8-TETRACHLORODIBENZO-P-DIQXIN
ANTHRACENE/PHENANTHRENE
BENZO ( A ) ANTHRACENE/CHRYSENE
BENZO(3.4/K)FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
4
4
4
1
1
B
B
B
B
B
B
4
B
8
B
8
8
B
8
TOTAL
NUMBER
DETECT
O
0
O
0
O
3
4
4
3
7
7
O
4
4
7
4
2
1
8
NUMBER
SAMPLES
>10UG/L
O
O
O
0
O
1
2
2
3
6
S
O
3
O
7
3
2
1
a
DETECTED CONCENTRATIONS IN UO/L
MIN 10% MEDIAN
.
.
.
.
2
2
2
13
1O
6
,
3
0.20
38
1
27
14
18
S
3
4
18
61
44
.
30
0.70
232
21
27
14
24O
MEAN BO% MAX
13
350
60
23
235
232
.
271
1.10
1771
137
31
14
4287
28
1340
220
38
B8O
1OOO
.
1OOO
2.40
1OOOO
450
36
14
3OOOO
-------
Table V-8 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ASSOCIATED AREAS
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
oo
Ul
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CAC03)
MO ALKALINITY (CAC03)
PHENOLICS(4AAP)
SULFATE
TOTAL SOLIDS
TOTAL
NUMBER
SAMPLES
7
7
9
9
4
3
4
4
3
4
1
2
4
1
4
NUMBER
TOTAL
DETECTS
7
7
9
9
4
3
4
4
2
3
1
2
O
1
4
DETECTED CONCENTRATIONS IN UQ/L
._.._ __., --*
MIN 10% MEDIAN
3300 2O200
2.4
27S
27
12675
580000
260OO
220O
O.O
4125
740000
1000
.
310000
180000
5.8
3700
2237
15500
1390E3
84250
4800
0.0
7612
7400OO
1000
,
310000
410000
MEAN BOX MAX
67084 240000
5.4
1246E3
17436
362O44
1960E3
1398E3
1O250
0.0
11508
740OOO
21500
.
310000
9147E3
7.2
9OOOE3
80OOO
1160E3
3100E3
2900E3
280OO
0.0
19300
740000
42000
.
310000
2200E4 .
-------
from this
substantial
established.
Agency are
Post, Mining Discharges
Reclamation Areas
Reclamation areas are tracts of surface acreage which have been
recontoured and seeded to establish ground cover after mining has
ceased. Regrading has already been completed by removal of the spoil
peaks and reestablishment of natural drainageways. Replanting of
indigenous grasses, legumes, and other annual or perrenial flora
occurs as soon as possible to stabilize the regraded area. Runoff
area directly following active mining can exhibit
suspended solids loadings until vegetation is well
Data from a self-monitoring survey initiated by the
presented in Table V-9. These data are from facilities
00015, 00033, 00037, 00085, 00101, and 00181 through 00187. Also
included in Table V-9 are data from facility 00033 sampled during the
engineering site visits. As shown on the table, suspended solids
loadings are substantial. This is particularly true for rainfall
conditions.
Underground Mines
Discharges from underground mines will continue after the temporary or
permanent cessation of mining until appropriate mine closure
procedures are implemented. This is because the principal source of
water is from aquifers that were intercepted during mine development.
These waste-bearing strata will continue to drain water into the mine
during and after the production of coal. A study was conducted to
characterize these discharges from active and abandoned anthracite
underground mines (21). The results of the study indicate that these
discharges will be similar to the wastewaters encountered during
active mining. For instance, an active discharge and an adjacent
abandoned discharge from one mining operation exhibited similar
characteristics. The reader is referenced to the active mine drainage
tables (Tables V-5 and V-6) for more detailed characterization of post
mining discharges from underground mines.
SUPPORT FOR THE SUBCATEGORIZATION SCHEME
In light of the data characterizing raw wastewater, this subsection
will discuss the evolution of the final BPT, BAT, and NSPS
subcategorization schemes already presented at the beginning of this
section. Preliminary analysis of the results of the BAT screening and
verification program (conducted from 1977 to 1979) suggested a number
of changes to the BPT categorization. Some of these changes were
retained, while others were eliminated based on additional data.
136
-------
Table V-9
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY AREAS UNDER RECLAMATION
TOXIC POLLUTANTS
COMPOUND
ANTIMONY (TOTAL)
'ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
15
15
15
15
15
15
15
15
15
15
15
15
15
TOTAL
NUMBER
DETECT
13
4
8
6
12
14
4
1
&
2
4
3
15
NUMBER
SAMPLES
>10UQ/L
13
4
3
8
9
13
4
1
8
2
O
3
15
DETECTED CONCENTRATIONS
MIN
66
66
1
11
8
6
30
40,00
45
70
5
147
7
10%
68
*
*
*
6
8
*
*
*
*
*
*
10
MEDIAN MEAN
101
79
4
16
17
19
37
4O.OO
85
7O
5
149
71
117
328
6
19
37
44
59
40. OO
258
74
5
161
1160
IN UG/L
90%
186
*
*
*
101
114
*
*
*
*
*
*
1828
MAX
235
890
12
40
116
131
103
4O.OO
996
77
6
184
12644
-------
Table V-9 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY AREAS UNDER RECLAMATION
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
MIN
DETECTED CONCENTRATIONS IN UG/L
10% MEDIAN MEAN BOX MAX
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
SETTLEABLE SOLIDS
IB
18
16
IS
14
16 12733 128S9 72139 3381O1 9B74BO 194SE3
IB 5.1 5.9 7.S 7.3 7.9 8.O
16 241 SOS 2365 12655 35S5O 65683
15 94 94 390 14O7 177O 11BOS
11 O.O O.O O.3 4.8 6.0 39.0
U)
CO
-------
First, surface and underground mines were categorized separately for
both acid and alkaline mines. In addition to differences in raw
wastewater characteristics, this separation resulted from differences
in the type of treatment technology that would be applied at surface
and deep mines. For instance, mobile or skid mounted treatment
processes might often be required at surface mines where current
treatment facilities (i.e., sedimentation ponds and possibly
neutralization equipment) frequently require relocation. At
underground facilities, permanent treatment facilities can usually be
installed for the life of the mine.
Second, although separate subcategories for preparation plants and
preparation plant associated areas were not established, separate
subsets of this category were formed only for NSPS because of the
different types of wastewater handling techniques available to the two
areas.
Third, post mining discharges were established as a subcategory to
provide regulatory coverage for two subsets of this subcategory:
surface reclamation areas and underground mine discharges.
Fourth, Pennsylvania anthracite mines were identified as a candidate
subcategory based on potential differences in toxic pollutant
discharges by different ranks of coal.
Fifth, western mines were separately categorized because of the
potential effects of different climatology and coal seams on mine
discharges. These modifications resulted in the following preliminary
subcategorization scheme:
1 . Acid drainage surface mines
2. Acid drainage underground mines
3. Alkaline drainage surface mines
4. Alkaline drainage underground mines
5. Preparation plants and associated areas
a. Preparation Plants
b. Preparation associated areas
6. Post mining discharges
a. Surface reclamation areas
b. Underground mines
7. Pennsylvania anthracite
8. Western mines
These subcategories were then reviewed by consideration of (1) the
engineering principles involved, and (2) the data collected from BAT
sampling programs conducted after the screening and verification
effort. The following discussion presents the results of this review
for each subcategory.
Surface and Underground Mines
Two factors were utilized to establish the surface/underground
distinction: (1) differences in raw wastewater characteristics and
139
-------
(2) differences in the mobility of applicable treatment options. Both
of these are rendered academic, however, because of the reduction
achieved by application of existing (BPT) technology. When the
untreated discharges from deep and surface are subjected to BPT
treatment, the resulting effluent are very similar in "classical"
pollutants (TSS, iron, manganese). Tables V-10 and V-ll illustrate
these data for alkaline and acid mines. Although there are
substantial differences in the acid and alkaline raw wastewaters from
deep and surface mines, these tables indicate the similarity of BPT-
treated discharges with respect to these three key pollutants. The
similarity of treated effluent also extends to the toxic metals, as
can be seen in Table V-12. Because of these factors, separate
subcategories for surface and underground mines were not established.
Preparation Plants and Preparation Plant Associated Areas
These two segments of the coal mining category are classified
differently for new sources than for existing sources. For new
sources, preparation plants and associated areas are subject to
different standards based upon differences in the following:
1. TSS and metals concentrations
2. Treatment strategies
3. Water usage requirements
4. Regulatory strategies
A comparison of raw wastewater metals and TSS concentrations in these
two subcategories is presented in Table V-13. The preparation plant
raw wastewater is much higher in suspended solids, while toxic metals
occur more consistently and in higher concentrations than in
associated areas runoff. It is not merely the differences in water
quality as apparent from the data, but the differences in treatment
strategy implied by these data, that support this division. The major
contributor to total metals in the preparation plant slurry is
suspended metals, due to the nature of the cleaning process. This is
evidenced by the data in Table V-14. This indicates that settling of
preparation plant slurry will provide substantial removal of toxic
metals. Conversely, metals from associated areas are mostly due to
the low pH, and thus a different treatment strategy would be selected,
i.e., pH adjustment via neutralization. Figure V-2 shows two typical
preparation plant water circuits. Although many factors suggest
different treatment systems for preparation plants and associated
•areas, most facilities currently commingle these drainages, as
illustrated in the top configuration of Figure V-2.
For new sources, segregated treatment can be designed into the overall
wastewater system. The incentives for separate treatment are
discussed below. Water management considerations and economics will
most o,ften dictate maximizing water recycle. Preparation plants
utilize water to assist in cleaning the coal, and thus the water is
process water subject to one class of treatment options. Runoff from
associated areas is usually not used in coal cleaning, and hence
140
-------
Table V-10
COMPARISON OF CLASSICAL POLLUTANTS IN
ALKALINE SURFACE AND UNDERGROUND MINES
Mean Values (mg/1)
Raw
Treated
Pollutant
TSS
Iron
Manganese
Surface
141
1.52
0.82
Deep
40
0.41
0.076
Surface
36
1.26
0.39
Deep
39
0.68
0.29
141
-------
Table V-ll
COMPARISON OF CLASSICAL POLLUTANTS IN
ACID SURFACE AND UNDERGROUND MINES
Mean Values (mg/1)
Raw
Pollutant
TSS
Iron
Manganese
Surface
732
45-7
17.7
Dee]
158
135
4.9
Treated
Surface Deep
32 21.1
1.21 1.72
2.45 1-27
142
-------
Table V-12
COMPARISON OF MEDIAN TOXIC METAL CONCENTRATIONS IN ACID AND
ALKALINE SURFACE AND UNDERGROUND MINES
(in ug/1)
Raw
Treated
-Cr
UO
Acid
Pollutant
Antimony
Arsenic
Beryllium
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Selenium
Silver
Thallium
Zinc
Surface
—
210
23
98
187
150
323
1.3
2020
17
ND
ND
6620
Deep
2.5
23
12
6
30
82
51
0.9
400
34
5
1
510
Alkaline
Surface
6
3
2
ND
32
10
23
0.4
30
3.5
10
2
80
Deep
2
5
ND
ND
49
6
72
0.6
57
3
ND
2
56
Acid
Surface
8
11
ND
ND
126
14
ND
0.3
95
13
ND
2
29
Deep
2.5
18
ND
ND
24
13
102
1.0
5
14
5
1
49
Alkaline
Surface
6
4
2
ND
33
10
23
0.5
30
3
10
1.5
70
peep
2
4.4
ND
ND
49
6
72
0.6
57
3
ND
1.7
56
Source: Screening and Verification Data
-------
Table V-13
PREPARATION PLANTS VERSUS ASSOCIATED AREAS
UNTREATED WATER
Preparation Plants
Associated Areas
Parameter
Anti»ony
Arsenic
Berylliu*
Cadniu*
ChronLun
Copper
Lead
Mercury
Nickel
Selcniun
Silver
Tha 1 1 iun
Zinc
tron
Manganese
TSS
pll (units)
Total
Samples
11
11
11
11
11
11
11
11
11
11
11
11
11
U
11
10
10
Total
Detects
6
10
7
4
9
11
10
6
8
8
6
7
10
11
11
10
10
Detects
>10 ppb
3
10
7
4
9
11
10
4
8
7
4
4
10
11
11
Median*
(•B/i)
.002
.200
.036
.034
.502
.860
.760
.015
.933
.050
.019
.010
2.9
841**
8.5**
69.330**
7.1
Tot at
Samples
8
8
8
8
8
8
8
8
a
8
8
8
8
8
8
6
6
Total
Detects
3
4
4
3
7
7
4
4
6
4
2
1
7
8
8
6
6
Deflects
>10 ppb
1
2
2
3
6
5
3
0
6
3
2
1
7
8
8
Median*
(«B/D
.005
.003
.004
.018
.061
.044
.030
.330
.021
.027
.014
.266
1402**
19**
77**
5.1
* This Is the Median of all values >10 ppb.
** Mean
Sources: Screening and Verification Da"ta;
Engineering Site Visit Data
-------
Table V-14
PREPARATION PLANT PROCESS EFFLUENT TOTAL
VERSUS DISSOLVED METALS
Preparation Plant A
Prepa ra t too ._Pl_ant__B_
Preparation Plant_C_
Total Dissolved
Ketals (ng/1) Metals
Antimony
Arsenic
Beryl Hum
Ca datum .
Chromium
Copper
• *
5 iron
Lead
Mercury
Manganese
Nickel
Selenium
Silver
Thallium
Zinc
<0.005
0.037
0.016
0.034
0.098
0.33
94
0.071
<0.001
1.7
0.33
<0-005
0.019
<0.002
0-98
<0,005
<0.002
<0.001
<0,005
0.009
0.006
0.097
0.003
<0.001
0.047
0.026
<0.005
0.009
<0-002
<0.002
Total Dissolved
Metals (MR/ I) Metals
<0.005
2.7
0.012
0.29
0.92
6.4
2,300
1.0
<0-001
13
2.8
0.21
0.064
0.026
8.3
<0.005
<0.002
<0.001
0.016
0-032
0.037
2.4
<0-002
<0.001
0.71
<0.020
<0.005
0.026
<0.002
0.015
Total Dissolved
Metals (me/1) Metals
<0.005
6.5
0.016
0.17
0.47
6.0
1,000
0.024
<0-001
12
2.1
0.35
0.057
0.008
6.0
<0.005
<0.002
<0.001
<0.005
0.013
0.020
1.0
<0.002
<0.001
0.12
<0.020
<0-005
0.019
<0.002
0.007
Source: Engineering Site Visit Data
-------
Recycle
PREPARATION
PLANT
Makeup
As Required
Slurry
Recycle
ADDITIONAL
DEWATERING
(OPTIONAL)
^
(TREATMENT \
(IF REQUIRED) )
Dewatered Sludge
to Kefuse Pile
Recycle
t
PREPARATION
PLANT
Slurry ^ f SLUR
Precipitation
Emergency
Discharge
Sludge
Periodic Dredging
May Be Required
To Refuse Pile
Precipitation
(In some cases,
can be diverted)
Makeup
As Required
Figure V-2. Typical Preparation Plant Water Circuits
-------
different wastewater treatment strategies are suggested. For
instance, the intermittent runoff generated in associated areas is
suited to a sedimentation pond system with possible neutralization
required if this runoff is acidic. On the other hand, a preparation
plant continually discharges process wastewater from the coal cleaning
equipment while the plant is operating. This continuous effluent is
usually alkaline and solids laden and is thus suited for a settling
and decant recycle system. Slurry impoundments could also be used;
the flow to these would not increase during a rainfall unless surface
runoff is also received. This is not the case for associated areas
which most often only discharge significant quantities during rainfall
events.
Increased regulatory flexibility is provided by separating these
segments. This is particularly in reference to the potential for a
"zero discharge" or total recycle regulation for preparation plant
slurry waters. If the associated area runoff can be segregated from
slurry effluent, the water balance can be achieved through diversion
ditching and otjier techniques, thus allowing total water recycle
systems for preparation plants. This is more extensively discussed in
Sections VII and VIII.
For existing sources, however, these reasons are overridden by
consideration of engineering and cost factors. Current practice in
the industry is commonly to commingle wastewater from refuse and
storage piles (associated areas) with preparation plant process
wastewater for treatment. To set differing limitations for the two
segments would cause most operators to segregate the two types of
drainage, which would require massive expenditures and gross
inefficiency for a facility. Installation of extensive retrofit
equipment and construction of new ponds would severely impact the
capital and human resources of many coal mining operations, without
significantly reducing the discharge of toxic pollutants. A further
discussion of these factors is presented in Section VII.
Pennsylvania Anthracite Mines
The Agency examined anthracite mining and preparation to assess any
statistical or technical differences in wastewater from bituminous and
lignite operations. Results shown in Table V-15 indicate that no
significant differences exist; thus anthracite facilities will be
categorized identically with bituminous and lignite operations.
Post Mining Discharges
Surface and underground mines can continue to discharge polluted
wastewater after production from the mine has ceased. For surface
mines, this discharge consists of runoff from a previously mined area
that has been backfilled, regraded, and revegetated. This process,
called reclamation, is an ongoing operation at one area of a mine that
occurs simultaneously with active mining of another area. For
underground mines, the post-mining discharge results from groundwater
147
-------
Table V-15
COMPARISON OF ANTHRACITE AND ACID RAW WASTEWATER
Anthracite Mines
Acid Mines
Pollutant
TSS
Iron
Manganese
pH (units)
Sb
As
Be
Cd
Cr
Cu
Pb
Hg
Ni
Se
Ag
Tl
Zn
Total
Number
Samples
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
Total
Detects
5
5
5
5
0
1
3
0
4
5
3
0
5
0
2
0
5
Median
Value
(mg/1)
56*
34*
6.7*
4.3
(ug/1)
.-
26
7
—
40
20
9
—
50
—
11
—
520
Total
Number
Samples
22
22
22
24
21
22
22
22
22
22
22
22
22
22
22
22
22
Total
Detects
21
22
^
24
8
14
7
3
11
16
6
11
11
11
7
5
20
Median
Value
(mg/1)
440*
88*
8.2*
5.3
(ug/1)
2
31
10
11
41
48
18
1.1
140
28
13
1
460
*Mean value
148
-------
infiltration into the mined out areas. This groi ndwater can originate
from breached aquifers or from adjacent abandoned mines.
During active mining, water is usually pumped to the surface for
treatment and discharge. After mine closure, this water will continue
to drain into the mine workings. Over a period of time, several
outcomes are possible. First, a state of equilibrium could occur when
the gravity head of the water balances the infiltration pressure.
Second, the water could erode and break through mine seals to adjacent
active or abandoned mine tunnels. Third, the mine pool could continue
to rise until the level reaches ground level, and, should no mine seal
be in place, a surface discharge occurs. Fourth, if the mine is
sealed, the water can erode and break through the seal, again
resulting in a surface discharge.
The post-mining discharges from either a reclamation area at a surface
mine or from an abandoned underground mine can contain significant
amounts of pollutants. These problems are addressed by SMCRA. The
performance based required by SMCRA is not to be released until the
SMCRA regulatory authority determines that post-mining pollution
problems are abated and can be reasonably expected not to occur.
Sufficient data does not exist to support the promulgation of
regulations for discharges after release of the SMCRA bond.
Post-mining discharges were not previously regulated by EPA, and so
were postulated as a candidate subcategory for BAT and NSPS effluent
limitations. To verify this for the final subcategorization, data
were gathered from four independent studies. A self monitoring
industry survey was initiated at 24 surface mine sites to characterize
raw and treated streams from both active mining and reclamation areas.
These data are presented in Table V-9. A second study was conducted
at eight surface mine sites which classified pond effluents as well as
determined the precision and accuracy of measuring settleable solids
below 1.0 ml/1. A third study sampled four anthracite mines to
collect data on postmining discharges from underground mines. (Among
the wastewaters samples, were discharges from underground abandoned
mines). The data are contained in a supplement to this report (21)
and are also presented in Table V-15.
EPA determined that settleable solids and pH should be regulated for
surface mines in the reclamation phase and for active mines during
precipitation events. On the other hand, post-mining discharges from
underground mines are very similar to wastewater generated during
active mining. This is because the mechanism for wastewater
generation is identical.
Western Mines
An evaluation of the nature of discharges from western mines has been
performed to determine the appropriateness of separately
subcategorizing mines in this region (10). Coal mines west of the
100th meridian in the United States were designated as western mines
(42 FR 46937, 19 September 1977). Mines in Colorado, Montana, North
149
-------
Dakota, South Dakota, Utah, and Wyoming (42 FR 21380, 26 April 1977}
are included in the western subcategory. These coal regions are
depicted in Figure V-3. This subcategory was established because of
potential differences in achievable effluent quality between eastern
and western mines for a number of reasons.
The West receives substantially less rainfall than the eastern region.
Further, evaporation rates are higher primarily because of the lower
humidity in the West^ These two conditions result in a smaller amount
of runoff and high evaporation from settling ponds. Figure V-4
illustrates the location of these areas. Additionally, site-specific
conditions such as topography and hydrogeology are potential
incentives for separate regulations.
Tables V-16 through V-19 present data from the BAT sampling program
for eastern and western raw wastewaters (10). Treated effluent data
for the two regions appear in Tables V-20 through V-23. Additional
data from discharge monitoring reports (DMRs) are summarized in Table
V-24. Information collected from the DMRs indicates that western mines
(16 facilities were included) exhibit no discharge 41 percent of the
time samples were taken, compared to 19 percent from eastern mines (56
facilities were included). However, as Tables V-20 through V-23
indicate, the final discharge compositions are very similar for
eastern and western mines when a discharge did occur.
This similarity in discharges was further verified by a statistical
analysis. The purpose of this analysis was to determine, with respect
to TSS, whether effluent discharges at Western alkaline mines were
statistically different from effluent discharges at Eastern alkaline
mines. The data available for the analysis consisted of 68 samples
from Eastern mines (22 influent and 46 effluent) and 26 samples from
Western mines (11 influent and 15 effluent). The statistical approach
used was a "goodness of fit" test, adopted because of the limited
number of samples available from Western mines. Under this approach,
the more plentiful Eastern mine data is used to define a sample
distribution for TSS. A statistical test is then performed to
determine how well the Western mine data "fit" into the Eastern mine
distribution. The test results show that the distribution of TSS at
Western mines is statistically similar to that at Eastern mines.
Figure V-5 provides observed and expected frequencies for influent and
effluent samples at Western mines.
The expected frequencies are those which one would expect to see if
the Western mine data followed the same distribution as the Eastern
mine data. The observed frequencies are those which were actually
found in the data. These frequencies were calculated by classifiying
each value of TSS observed at a Western mine into one of the four
quadrants of the TSS distribution established for Eastern mines. The
quadrants of a distribution are those areas which divide the data into
four equally dense portions. That is, the first quadrant will contain
25 percent of the data, the second quadrant will contain 25 percent of
the data and so on. It should be noted that quadrants were
established independently for influent and effluent samples. The
150
-------
Table V-17
EASTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
*-> COPPER (TOTAL)
w LEAD (TOTAL 1
MERCURY (TOTAL)
NICKEL (TOTALI
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
17
17
17
17
17
17
17
17
17
17
17
17
17
TOTAL
NUMBER
DETECT
3
4
2
3
10
4
8
7
7
H
6
1
13
NUMBER
SAMPLES
MOUG/L
0
1
0
2
9
3
4
0
7
0
3
0
10
DETECTED CONCENTRATIONS
MIN IPX
2 *
2 *
2 *
6 *
o a
10
2
0,30
30
4
10 *
2 *
7 7
IN UG/L
MEDIAN MEAN 90ft
2
2
2
10
33
13
a
0,44
67
6
10
2
31
3
12
2
14
42
20
29
1.06
115
6
13
2
52
^
*
*
*
65
*
*
*
*
*
*
*
13fl
MAX
6
40
2
21
109
H2
9<*
2,20
365
7
22
2
156
-------
Table V-16
EASTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
DETECTED CONCENTRATIONS IN UG/L
M1N 10* MEDIAN MEAN 9QX MAX
TOTAL SUSPENDED SOLIDS
PH (UNITSJ
TOTAL IRON
MANGANESE (TOTAL)
1**
17
17
14 2600 3160 17000 67364 1702HO 330000
14 6.6 6.8 7.6 7.6 6.1 6.7
17 11 96 537 1094 2590 3500
17 3 25 475 935 1430 7000
-------
Table V-19
WESTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBtR
SAMPLES
11
11
11
11
11
11
11
11
11
11
11
11
11
TOTAL
NUMBER
DETECT
3
3
2
2
5
11
1
3
1
3
0
0
10
NUMBER
SAMPLES
>10UG/L
2
0
0
2
4
6
0
0
1
0
0
0
10
DETECTED CONCENTRATIONS
HIN
6
4
0
11
a
4
4
0.27
174
2
•
.
13
10X
*
*
*
*
*
4
*
13
MEDIAN
a
4
0
11
44
10
4
0.35
174
2
.
*
BO
MEAN
14
6
1
14
42
14
4
0.70
174
3
«
.
184
IN U6/L
90S
2
*
166
MAX
27
a
i
17
57
36
4
1.40
174
3
.
•
1100
-------
Ul
LO
Table V-18
WESTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
RAW WASTEWATER
SUBCATEGORY ALKALINE DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
DETECTED CONCENTRATIONS IN U&/L
MIN 10K MEDIAN MEAN 90* MAX
TOTAL SUSPENDED SOLIDS
PH (UNITS)
TOTAL IKON
MANGANESE (TOTAL)
11
11
11
11
11
11
11
11
500
6.9
6*4
H
510
7.0
66
H
65250
7.7
1317
90
153361 292000 871000
7.7 8,1 a.2
4996 5250 39040
172 222 9H7
-------
Table V-20
EASTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ALKALINE DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL NUMBER DETECTED CONCENTRATIONS IN U&/L
SAMPLES DETECTS HIM 10X MEDIAN MEAN 90ft MAX
TOTAL SUSPENDED SOLIDS
PH CUNITSJ
TOTAL IKON
MANGANESE
-------
Table V-21
EASTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
ui
COMPOUND
ANT I MONT (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
30
30
30
30
30
30
30
30
30
30
30
29
30
TOTAL
NUMBER
DETECT
7
13
0
5
20
6
5
13
4
7
7
2
19
NUMBER
SAMPLES
>10U6/L
1
3
0
4
17
4
3
0
3
1
7
0
15
DETECTED CONCENTRATIONS
MIN
1
2
.
5
9
6
5
0.10
10
1
14
1
7
10%
*
2
*
*
10
*
*
0.16
*
*
*
*
9
MEDIAN
2
5
.
14
33
10
12
0.50
52
2
20
1
19
MEAN
5
6
.
14
77
19
24
1.34
66
5
20
1
47
IN U6/L
90X
*
13
*
*
63
*
*
1.67
*
*
*
*
103
MAX
15
22
.
23
660
40
66
7.90
146
20
25
2
166
-------
Table V-22
WESTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ALKALINE DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
TOTAL IKON
MANGANESE (TOTAL)
TOTAL
NUMbt-K
SAMPLES
11
11
11
11
NUMBCK
TUTAL
OETECTS
11
11
10
11
DETECTED CONCENTRATIONS
MIN
2400
7.5
mo
17
10*
2720
7.5
mo
18
MEDIAN
9650
7.9
3H9
<***
MEAN
2172H
8.0
<»7«t
103
IN UG/L
90X
26893
8.H
1030
2H2
MAX
97000
8.5
1200
285.
Ul
-------
Table V-23
WESTERN MINES
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ALKALINE DRAINAGE MINES
TOXIC POLLUTANTS
ui
Co
COMPOUND
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
11
11
11
11
11
11
11
11
11
11
11
11
10
TOTAL
NUMBER
DETECT
3
3
1
1
H
7
3
2
0
1
0
1
6
NUMBER
SAMPLE!
>10U6/l
2
0
0
0
3
2
1
0
0
0
0
0
6
DETECTED CONCENTRATIONS IN UG/L
! __-—_«____ _„_ ——.,,. „-- .—«.—
MIN 10X MEDIAN MEAN
3 * 7
3 * i*
0
9
6
3
2
0.63
•
0
9
11
9
5
0*83
•
2 * 2
• *
1 * 1
IH * H5
10
5
0
9
30
9
40
1.72
•
2
•
1
63
90X
*
*
*
*
*
*
*
*
*
*
*
*
*
MAX
15
6
0
9
SO
IS
109
2.60
•
2
•
1
127
-------
., Table V-24 ^
COAL MINE DMR DATA
1979 AVERAGE TSS & Fe VALUES*:
ALKALINE EASTERN VS. ALKALINE WESTERN FACILITIES
Jan
Feb
Mar Apr May June July Aug Sept
Oct
Nov
Dec
Overall Ave.
Values 1979
WESTERN **
TSS
Ave
Ave
Ave
Fe
Ave
Ave
Ave
(nig/1 )
. Maximum
. Minimum
. Average
(no/1)
. Maximum
. Minimum
. Average
Value
Value
Value
Value
Value
Value
23.9
4.2
16.3
1.02
0.36
0.69
24
4
15
1
0
0
.2
.5
.3
.03
.36
.67
37.2 34.9 27.1 19.1 26.3 21.4 23.0
7.3 7.3 5.2 7.2 6.4 5.2 4.6
19.8 18.3 14.3 13.4 14.4 11.4 12.2
1.00 0.88 0.86 0.54 0.75 1.08 0.81
0.25 0.10 0.10 0.17 0.28 0.28 0.31
1.27 0.40 0.45 0.34 0.47 0.60 0.45
9.8
3.3
6.5
0.58
0.19
0.50
13.3
5.4
8.6
0.84
0.18
0.65
15.8
6.6
10.7
0.35
0.13
0.24
23.
5.
13.
0.
0.
0.
0
6
4
81
23
56
EASTERN**
TSS
Ave
Ave
Ave
Fe
Ave
Ave
Ave
(nfl/1)
. Maximum
. Minimum
. Average
(mg/1)
. Maximum
. Minimum
. Average
Value
Value
Value
Value
Value
Value
27.3
5.5
16.3
1.09
0.44
0.65
4
3
12
1
0
0
.4
.8
.4':
.0
.22
.41
19.9 20.4 92.5 9.4 18.0 31.1 25.6
9.2 22.2 63.2 5.9 17.0 9.2 6.7
11.3 16.0 48.9 11.6 13.5 17.2 11.2
0.82 0.45 1.79 0.52 1.16 0.80 0.78
0.39.0.35 1.5 0.48 1.03 0.56 0.70
0.42 0.35 1.3 0.39 1.0 0.49 0.5
81.0
3.0
21.8
0.45
0.02
0.73
17.9
4.1
7.8
1.00
0.30
0.44
46.0
36.3
27.8
1.0]
0.53
0.93
32.
15.
18.
0.
0.
0.
8
5
0
91
54
63
**
Values do not Include Instances of "No Discharge/ "No Reported Values," or violations due to
precipitation events.
Includes data from 10 Western facilities and 10 Eastern facilities.
-------
to
§
H
«?
a> 25
1-. M
EL K
So H
*
0)
u
i
160
-------
«fc 1 F^ . k • .^ . _fcT ^^ » - + * 'f W — jT*^ "» ^ •
100th
Meridian
Figure V-4
RELATION OF AREAS OF POSITIVE EVAPOTRANSPIRATION
TO THE 100th MERIDIAN
161
-------
Figure V-5
OBSERVED AND EXPECTED FREQUENCIES
OF TSS CONCENTRATIONS
AT WESTERN ALKALINE MINES
QUADRANTS
Influent
Effluent
3
(3)
4
(4)
0
(2)
5
(4)
3
(3)
3
(4)
5
(3)
3
(3)
11
15
26
Expected frequencies are given in parentheses.
162
-------
expected frequencies are found by taking 25 percent of the available
samples. Since there were 11 influent samples, one would expect
approximately three to fall into each quadrant if the distribution of
TSS at Western mines was similar to that at Eastern mines. Figure V-5
shows that in most cases the observed frequencies are similar to the
expected frequencies. The largest differences are found in the second
and fourth quadrants of the influent distribution. Calculation of a
chi square statistic indicates that these differences are not
statistically significant. Based on these facts, a separate
subcategory for western mines is not warranted.
163
-------
-------
SECTION VI
SELECTION OF POLLUTANT PARAMETERS
INTRODUCTION
The Agency has studied coal mining wastewaters to determine the
presence or absence of toxic, conventional, and non-conventional
pollutants. This section will address the selection of pollutant
parameters for post mining discharges and effluents that have
undergone BPT treatment. The quantities and treatability of
pollutants in these treated wastewaters will form the basis for
selection of pollutant parameters for regulation. The CWA requires
that effluent limitations be established for toxic pollutants referred
to in Section 307(a)(l). These pollutants, and the conventional and
selected nonconventional pollutants are summarized in Table VI-l. The
Settlement Agreement in Natural Resources Defense Council,
Incorporated vs. Train, 8 ERC 2120 (D.D.C. 1976), modified, 12 ERC
1833 (D.D.C. 1979), provides for the exclusion of particular
pollutants, categories and subcategories (Paragraph 8), according to
the criteria summarized below:
1. Equal or more stringent protection is already
guidelines and standards under the Act.
provided by EPA's
2. The pollutant is present in the effluent discharge solely as a
result of its presence in the intake water taken from the same body of
water into which it is discharged.
3. The pollutant is not detectable in the effluent within the
category by approved analytical methods or methods representing the
state-of-the-art capabilities. (Note: this includes cases in which
the pollutant is present solely as a result of contamination during
sampling and analysis by sources other than the wastewater.)
4. The pollutant is detected in only a small number of sources within
the category and is uniquely related to only those sources.
5. The pollutant is present only in trace
causing nor likely to cause toxic effects.
amounts and is neither
6. The pollutant is present in amounts too small to be effectively
reduced by known technologies.
165
-------
Table VT-1
LIST OF 129 PRIORITY POLLUTANTS, CONVSNTIONALS
AND NON-CONVENTIONALS (1)
Priority Pollutants
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27,
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
*acenaphthene
*acroletn
*acrylonitrile
*benzene
*benzidene
(B)
(V)***
(V)
(V)
(B)
*carbon tetrachloride (tetrachloromethane) (V)
chlorobenzene (V)
1,2,4-trichlorobenzene (B)
hexachlorobenzene (B)
1,2-dichloroethane (V)
1,1,1-trichlorethane (V)
hexachlorethane (B)
1,1-dichloroethane (V)
1,1,2-trichloroechane (V)
1,1,2,2-tetrachloroethane (v)
chloroethane (V)
bis (chloromethyl) ether (V)
bis (2-chloroethyl) ether (B)
2-chloroethyl vinyl ether (mixed) (V)
2-chloronaphthalene (B)
2,4,6-trichlorophenol (A)***
parachlorometa cresol (A)
*chlorofora (trichloromethane) (V)
*2-chlorophenol (A)
1,2-dichlorobenzene (B)
1,3-dichlorobenzene (B)
1,4-dichlorobenzene (B)
3,3!-dichlorobenzidine (B)
1,1-dichloroechylene (V)
1,2-trans-dischloroethylene (V)
*2,4-dichlorophenol (A)
1,2-dichloropropane (V)
1,2-dichloropropylene (1,3-dichloropropene) (V)
*2,4-dimenthylphenol (A)
2,4-dinitrotoluene (B)
2,6,-dinitrotoluene (B)
*l,2-diphenylhydrazine (B)
*ethylbenzene (V)
*fluoranthen* (B)
4-chlorophenyl phenyl ether (B)
4-broaophnyl phenyl ether (B)
bis(2-chloroisopropyl) ether (B)
166
-------
Table VI-1 (Continued)
LIST OF 129 PRIORITY POLLUTANTS, CONVENTIONALS
AND NON-CONV1OTIONALS (1)
43. bis(2-chloroethoxy) methane (B)
44. methylene chloride (dichloromethane) (V)
45. methyl chloride (chloromethane) (V)
46. methyl bromide (bromontethane) (V)
47. bromoform (tribrononethane) (V)
48. dichlorobromomethan* (V)
49. trichlorofluoromethane (V)
50. dichlorodifluoromethane (V)
51. chlorodibromomethane (V)
52. *hexachlorobutadiene (B)
53- *hexachlorocyclopentadiene (B)
54. *isophorone (B;
55. *naphthalene (B)
56. *nitrobenzene (B)
57. 2-nitrophenol (A)
58. 4-nitrophenol (A)
59. *2,4-dinitrophenol (A)
60. 4,6-dinitro-o-cresol (A)
61. N-nitrosodimethylamine (B)
62. N-nitrosodiphenylamine (B)
63- N-nitrosodi-n-propylamine (B)
64. *pentachloroohenol (A)
65. *phenol (A)
66. bis(2-ethylhexyl) phthalate (B)
67. butyl benzyl phthalate (B) \
68. di-n-butyl.. phthalate (B)
69. di-n-octyl phthalate (B)
70. diethyl phthalate (B)
71. diaethyl phthalate (B)
72. benzo (a)anthracene (1,2-benzanthracene) (B)
73. benzo (a)pyrene (3,4-benzopyrene) (B)
74, 3,4-benzofluoranthene (B)
75. benzo(k)fluoranthane (11,12-benzofluoranthene) (B)
76. chrysene (B)
77. acenaphthylene (B)
78. anthracene (B)
79. benzo(ghi)perylene (1,12-benzoperylene) (B)
80. fluorene (B)
81. phenathrene (B)
82. dibenzo (a,h)anthracene (1,2,5,6-dibenzanthracene)
83. indeno (1»2,3-cd)(2,3,-o-phenylenepyrene) (B)
84. pyrene (B)
85. *tetrachloroethylene (V)
86. *toluene (V)
(B)
167
-------
Table VI-1 (Continued)
LIST OF 129 PRIORITY POLLUTANTS, CONVENTIONALS
AND NON-CONVENTIONALS (1)
87. *trichloroethyl«ne (V)
88. *vinyl chloride (chloroethylene) (V)
89. *aldrin (P)
90. *dieldrin (P)
91. *chlordane (technical mixture and metabolites) (P)
92. 4,4'-DDT (P)
93. 4,4'-DDE(p,p'DDX) (P)
94. 4,4'-DDD(plp'TDE) (P)
95. a-endosulfan-Alpha (P)
96. b-end03ulfan-Beta (P)
97. endosulfan sulfate (P)
98. endrin (P)
99. endrtn aldehyde (P)
100. heptachlor (P)
101. heptachlor epoxide (P)
102. a-AHOalpha (P) (B)
103. b-BHC-beta (P) (V)
104. r-BHC (lindane)-gamma (P)
105. g-BHC-delta (P)
106. PCB-1242 (Arochlor 1242) (P)
107. PCB-1254 (Arochlor 1254) (P)
108. PCB-1221 (Arochlor 1221) (P)
109. PCB-1232 (Arochlor 1232) (P)
110. PCB-1248 (Arochlor 1248) (P)
111. PCB-1260 (Arochlor 1260) (P)
112. PCB-1016 (Arochlor 1016) (P)
113. *Toxaphene (P)
114'. **2,3,7,8-tetrachlorodibenzo-p-dioxin (TCDD) (P)
115. *Antimony (Total)
116. *Arsenic (Total)
117. *Asbestos (Fibrous)
118. *Beryllium (Total)
119. *Cadmium (Total)
120, *Chromium (Total)
121. *Copper (Total)
122. *Cyanide (Total)
123. *Lead (Total)
124. *Mercury (ToCal)
125, *Nickel (Total)
126. *Seienium (Total)
127. *Silver (Total)
128. *Thalltum (Total)
129. *Zinc (Total)
168
-------
Table VI-1 (Continued)
LIST OF 129 PRIORITY POLLUTANTS, CQNVENTIONALS
AND NON-CONVENTIONALS (1)
Conventionals
PH
Total Suspended Solids
Non-Conventionals
Iron
Manganese
Chemical Oxygen Demand (COD)
Total Organic Carbon (TOC)
Settleable Solids (SS)
*Specific compounds and chemical classes as listed in the
consent degree.
**This compound was specifically listed in the consent degree.
***3 * analyzed in the base-neutral extraction fraction
V * analyzed in the volatile organic fraction
A » analyzed in the acid extraction fraction
P * pesticide/polychlorinated diphenyl
169
-------
7. The pollutant is effectively controlled by the technologies upon
which other effluent limitations and guidelines are based. All
pollutants detected in treated effluents of the coal mining industry
are summarized in Table VI-2. These results are also summarized by
subcategory in Tables VI-3 through VI-7.
POLLUTANTS SELECTED FOR REGULATION IN THE COAL MINING POINT SOURCE
CATEGORY
Specific effluent limitations are being established for total
suspended solids, pH, iron and manganese for each subcategory except
post mining discharges from reclamation areas. (See the Coal Mining
Development Document for the BPT Regulations, for an explanation of
the selection of these pollutants and development of their
limitations.) Settleable solids and pH have been selected to control
effluents from reclamation areas and discharges from all subcategories
during rainfall events.
PRIORITY ORGANICS EXCLUDED FROM REGULATION
All of the priority organic pollutants are excluded from regulation.
The reasons for their exclusion are presented in Table VI-8 and are
discussed below.
Priority Orpanics Not Detected un Treated Effluents
The Settlement Agreement provides for the exclusion from regulation of
toxic pollutants not detectable by approved methods or methods
representing state-of-the-art capabilities. The sixty-seven organic
priority pollutants not detected during sampling and thus excluded
from regulation are listed in Table VI-9.
Priority OrganIcs Detected Due to Laboratory Analysis and Field
Sampling Contamination
Ten of the priority organics were detected in one or more of the
treated effluent samples; however, their presence is believed to be
the sole result of contamination by sources in the field or laboratory
independent of the composition of the actual wastewater. Table VI-10
tabulates the pollutants in this category. Field controls and blanks
were used during each phase of the sampling program (Screening,
170
-------
Table VI-2A
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIOENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1.2, 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
,2-DICHLOROETHANE
. 1 . 1-TRICHLOROETHANE
HEXACHLOROETHANE
, 1-DICHLOROETHANE
, 1 , 2-TRXCHLOROETHANE
,1.2 , 2-TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2 -CHLORONAPHTHALENE
2 . 4 . 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 ,2-DICHLOROBENZENE
1 , 3-DICHLOROBENZENE
1 , 4-DICHLOROBENZENE
3, 3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
53
51
51
51
53
51
50
53
53
51
51
53
51
51
51
51
51
53
51
53
51
51
51
51
S3
S3
S3
52
TOTAL
NUMBER
DETECT
O
O
O
21
O
O
O
0
0
2
11
1
O
O
1
O
0
O
0
O
0
O
40
O
2
O
1
1
NUMBER
SAMPLES
MOUG/L
O
0
O
2
O
0
O
O
O
O
O
O
O
O
O
O
0
0
O
O
O
O
22
0
1
0
0
O
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN
*
*
*
O O 2
*
.
,
.
f
1
1
3
,
,
3
t
,
.
B
.
.
|
f
3
,
.
.
.
1
2
3
.
m
3
.
.
ft
m
.
,
13
.
3
3 * 3
3 * 3
MEAN 90X MAX
*
.
,
.
1
2
3
.
^
3
.
.
.
t
60 12
.
11
9
3
3
16
.
i
3
3
3
.
.
t
476
m
18
3
3
-------
Table VI-2A (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
1 . 1 -DICHLOROETHYLENE
9 , 2-TRANS-DICHLOROETHYLENE
2 ; 4-DICHLOROPHENOL
1 , 2-DXCHLOROPROPANE
1 . 3-DICHLOROPROPENE
2 . 4-DIMETHYLPHENOL
2 , 4-DINITROTOLUENE
2.6-DINITROTOLUENE
1 , 2-OIPHENYLHVORAZINE
ETHYLBENZENE
FLUOR ANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENTL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BXS(2-CHLOROETHQXY) METHANE
METHYLENE CHLORIDE (DtCHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMONETHANE
TRICHLOROFLUOROMETHANE
DICHLORODXFLUOROMETHANE
CHLORO01BROMOHE THANE
HEXACHLOROBUTADXENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
51
51
51
51
51
51
53
52
53
52
S3
53
53
S3
53
51
51
51
51
51
51
51
51
S3
S3
S3
53
S3
TOTAL
NUMBER
DETECT
3
11
0
O
O
O
O
0
0
8
1
O
O
O
1
47
O
O
0
O
7
0
O
0
O
0
4
O
NUMBER
SAMPLES
>10UG/L
O
O
O
O
O
0
0
O
O
1
0
O
0
O
0
41
O
O
O
0
7
0
O
0
O
O
3
O
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
3 * 3
00 2
.
.
.
.
.
.
.
1
3
.
.
.
3
3
.
M
,
,
14
.
.
,
.
.
3
.
.
.
.
.
.
.
.
3
3
m
.
,
3
895
,
.
17
,
If
.
MEAN 90X MAX
3 * 3
2 3 10
.
.
.
.
.
,
.
3
3
,
,
^
3
5743 969
* .
f
f
t
21
,
w
,
.
,
10
.
.
.
,
.
.
.
.
11
3
.
.
m
3
71000
.
9
,
t
37
r
p
14
.
-------
Table VI-2A(Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
AIX SUBCATEGORIES
TOXIC POLLUTANTS
—3
U)
COMPOUND
2-NITROPHENOL
4-NITROPHENQL
2,4-DINITROPHENOL
4,B-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMINE
N-NITROSODZPHENYLAMINE
N-NITROSODX -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS<2-ETHYUIEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-H-BUTYL PHTHALATE
DI-N-OCTVL PHTHACATE
DIETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO ( A ) ANTHRACENE
BENZO(A)PYRENE
BENZO ( B ) FLUORANTHENE
BENZO ( K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO(G,H,X)PERYLENE
FLUORENE
PHENANTHRENE
DIBENZ0(A.H)ANTHRACENE
XNDENO(1.2.3-C.D)PYRENe
PYRENE
TOTAL
NUMBER
SAMPLES
SI
51
51
51
S3
S3
S3
61
51
52
S3
51
53
62
S3
51
53
53
53
51
53
31
53
53
51
S3
53
S3
TOTAL
NUMBER
DETECT
O
O
1
1
0
0
0
1
B
38
8
25
1
12
O
O
2
O
2
O
O
O
4
1
1
3
3
1
NUMBER
SAMPLES
>1OUG/L
O
O
O
O
0
O
0
O
O
27
O
15
0
3
0
O
O
O
2
O
O
O
2
O
O
2
3
O
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN
.
3
3
.
.
t
3
3
4%
3
4*
3
4
,
,
3
,
13
.
.
f
3
1
3
1O
1O
2
B
3
3
.
m
t
3
3
170
3
63
3
3
.
t
3
m
13
f
t
,
3
1
3
11
10
2
MEAN
f
3
3
.
t
t
3
3
935
3
244
3
101
t
,
5
,
13
(
f
f
8
1
3
11
11
2
90%
*
*
*
*
*
*
*
*
*
1848
*
6O5
*
315
*
*
*
*
*
*
*
*
*
*
*
*
*
*
MAX
,
3
3
.
t
9
3
3
11000
3
98O
3
780
a
t
8
,
13
,
.
.
13
1
3
12
11
2
-------
Table VI-2A(Contintaed)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELORIN
CHLORDANE
4.4-ODT
4, 4 -DOE
4.4-DOD
ENDOSULFAN-ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE
BHC-ALPHA
BHC-BETA
BHC ( LINO ANE) -GAMMA
BHC-OELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCS -1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-12BO (AROCHLOR 12BO)
PCB-1O18 (AROCHLOR 1O16)
TOTAL
NUMBER
SAMPLES
SI
51
51
51
47
47
49
47
47
47
47
47
49
49
47
47
47
47
47
47
47
49
49
49
49
49
49
49
TOTAL
NUMBER
DETECT
17
22
3
0
2
O
O
1
O
1
0
O
O
O
O
2
1
3
3
2
a
o
0
o
o
o
o
o
NUMBER
SAMPLES
>10UG/L
6
5
O
0
o
o
0
o
o
o
o
0
o
o
o
0
0
o
o
o
0
o
0
0
o
o
o
o
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN
1 1 4
0 O 2
1 * 2
.
2.24
.
f
2.24
.
2.24
.
.
.
.
.
2.24
2.24
O.10
0.28
2.24
O.10
.
.
.
.
.
.
.
,
2.24
.
.
2.24
.
2.24
,
.
.
.
.
2.24
2.24
1.17
1.25
2.24
1.17
.
.
.
.
MEAN 90% MAX
12 23 81
7 20 40
2 * 3
.
2.24
t
t
2.24
,
2.24
.
.
.
.
.
2.24
2.24
1.52
1.58
2.24
1.52
.
,
.
.
.
.
.
.
2.24
.
.
2.24
.
2.24
.
.
.
.
.
2.24
2.24
2.24
2.24
2.24
2.24
.
.
.
.
.
.
.
-------
Table VI-2A (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL
NUMBER
DETECT
NUMBER
SAMPLES
>10U6/L
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN MEAN 9O%
MAX
TOXAPHENE 49 O O
2.3.7.8-TETRACHLQRODIBENZO-P-DIOXIN 53 0 .O
ANTHRACENE/PHENANTHRENE 46 6 2 3
BENZO(A)ANTHRACENE/CHRYSENE 14 1 0 3
BENZO(3,4/K)FLUORANTHENE 12 O O
ANTIMONY (TOTAL) 114 44 17 1
ARSENIC (TOTAL) 114 44 14 2
BERYLLIUM (TOTAL)* 114 70 O
CADMIUM (TOTAL) 114 16 9 3
CHROMIUM (TOTAL) 114 63 55 6
COPPER (TOTAL) 114 61 33 3
CYANIDE (TOTAL) 62 5 O 3
LEAD (TOTAL) 114 22 13 2
MERCURY (TOTAL) 114 39 1 0.10
NICKEL (TOTAL) 112 25 23 5
SELENIUM (TOTAL) 114 32 15 1
SILVER (TOTAL) 114 29 21 2
THALLIUM (TOTAL) 113 19 5 1
ZINC (TOTAL) 113 85 79 6
*
*
*
*
*
1
2
*
4
9
6
*
3
0.30
IS
1
5
1
10
.
.
3
3
f
4
e
i
12
3O
11
4
21
0.70
60
6
15
2
4O
.
.
13
3
f
29
12
2
12
46
15
5
66
1.47
75
22
IB
13
59
92
29
*
17
63
27
*
1O4
2.51
138
64
26
24
131
f
.
35
3
,
255
72
3
23
880
46
7
B2O
13.00
182
160
31
137
382
-------
Table VI-2B
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
ALL SUBCATEGORIES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTQS(TOTAL-FIBERS/LITER)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CACO3)
MO ALKALINITY (CAC03)
PHENOLICS(4AAP)
SULFATE
TOTAL ACIDITY (CACQ3)
TOTAL SOLIDS
TOTAL
NUMBER
SAMPLES
110
113
115
110
24
62
45
46
35
66
56
2
47
61
6
4
43
TOTAL
NUMBER
DETECTS
1O9
113
111
98
24
55
45
46
27
47
51
2
47
1O
6
4
43
DETECTED CONCENTRATIONS IN UQ/L
MIN
32
3.2
21
11
5BOOOO
4O
3SOOO
260OO
1000
O.O
26O
50
1OO
2
13OOOO
3OOO
70OO
10%
25OO
6.8
128
25
1379E4
116OO
11SOOO
S12OO
1000
0.0
1051
*
164OO
2
*
*
263OOO
MEDIAN
15925
7.8
528
3O3
8800E5
2435O
8050OO
135OOO
47OO
0.0
9000
50
13OOOO
13
246667
40OO
B35OOO
MEAN
28507
7.8
1239
922
6766E6
89569
1232E3
1689E3
13304
4.9
15366
14025
17O428
15
S52778
55OO
5895E3
90X
622OO
8.4
312O
2020
1800E7
48000
285OE3
467599
151 2O
0.2
3B940
*
383OOO
2O
*
*
4O43E3
MAX
45OOOO
10.8
11205
7167
5200E7
326OE3
6600E3
67OOE4
2OOOOO
2OO.O
6500O
280OO
62OOOO
40
1373E3
1O500
1900E5
-------
Table VI-3
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
ACEHAPHTHENE
ACROLETN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1 , 2 , 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
1,2-DICHLOROETHANE
1.1.1 -TRXCHLOROETHANE
HEXACHLOROETHANE
1 , 1-OICHLOROETHANE
1,1, 2-TRICHLOROETHANE
1,1,2 . 2-TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS( 2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2-CHLORONAPHTHALENE
2,4. 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLQROPHENOL
1 , 2-DICHLOROBENZENE
1 ,3-DICHLOROBENZENE
1 . 4-DICHLOROBENZENE
3,3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
11
11
13
11
13
13
13
12
TOTAL
NUMBER
DETECT
0
O
O
9
0
0
O
O
0
O
3
O
O
O
O
0
0
O
O
O
O
O
10
0
0
O
0
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UG/L MIN 10% MEDIAN MEAN 9O% MAX
0 .
0
O
0 1
O
0
O
O
O
O
0 1
O
0
0
0
O
0
0
0
O
0
O
2 3
.
, .
( .
1 2
f m
t t
t m
m t
8 1 1 14 72 17
0 *
0 *
0 *
0 *
O *
7
f
f
2
.
f
,
.
.
.
.
B
.
.
442
.
9
t
-------
Table VI-3 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
1 . 1-DICHLOROETHYLENE
1 . 2-TRANS-DICHLOROETHYLENE
2.4-DICHLOROPHENOL
1 .2-DICHLOROPROPANE
1 . 3-DICHLOROPROPENE
2 . 4-DIMETHYLPHENOL
2 , 4-DINITROTOLUENE
2 , 6-D1NITROTOU1ENE
1 ,2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FUUORAMTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROtSOPRQPYU) ETHER
BIS(2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLORONETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMQFORM
DICHLOROBROMDMETHANE
TRiCHLOftOFLUOROMETHANE
DICHLOROOI FLUOROMETHANE
CHLORODIBRONOMETHANE
KEXACHLOROBUTADI ENE
HEXACHLOROCrCLOPENTAOlENE
ISOPHORQNE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
13
13
11
13
13
11
13
13
13
14
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
TOTAL
NUMBER
DETECT
O
4
O
0
O
O
O
O
O
3
O
O
O
O
O
13
O
0
O
O
2
O
O
O
0
O
2
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>100Q/L MIN 10X MEDIAN MEAN SOX MAX
0 .
0 1
O
0
O
0
0
O
O .
0 1
O
O
O
O
O
12 7
0
0
O
O
2 14
O
0
O
O
O
2 12
O
1 2
1 2
• *
2250 3968 SB4
. .
14 26
. .
. .
12 13
.
2
,
.
.
.
.
,
.
3
.
.
.
.
.
13OOO
.
.
37
.
.
14
.
-------
Table VI-3 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
COMPOUND
2-NITROPHENOL
4-NITROPHENOL
2,4-DINITROPHENOL
4 , B-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMZNE
N-NITROSODIPHENYLAMIME
N-NITROSODI-N-PROPYLANINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHTLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DX-N-BUTYL PHTHALAft
DI-N-OCTYL PHTHALATE
DI ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO< A) ANTHRACENE
BENZO(A)PYRENE
BENZO( B ) FLUORANTHENE
BENZO
-------
-Table VI-3 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXICE POLLUTANTS
CO
o
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4.4-DDT
4.4-DDE
4.4-DDD
ENOOSULFAN-ALPHA
ENOOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRXN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCS- 1242 (AROCHLOR 1242)
PCB-12S4 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-12BO (AROCHLOR 1260)
PCB-1018 (AROCHLOR 1O18)
TOTAL
NUMBER
SAMPLES
13
13
13
13
9
9
9
9
9
9.
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
TOTAL
NUMBER
DETECT
B
7
0
O
0
0
0
o
o
o
o
o
o
o
o
o
o
1
1
1
1
0
0
o
0
o
o
o
NUMBER DETECTED CONCENTRATIONS IN UG/L
SAMPLES
>10UG/L MIN 10X MEDIAN MEAN 90% MAX
32 0 13 31
O 0
O
o
o
o
o
o
o
0
o
o
o
o
0
o
0
0 2.24
0 2.24
O 2.24
O 2.24
O
O
o
o
0
0
0
2 3
a ,
. .
. .
2.24 2.24
2.24 2.24
2.24 2.24
2.24 2.24
S
m
f
9
m
f
f
+
f
m
t
,
w
+
i
,
2.24
2.24
2.24
2.24
.
,
,
-------
Table VI-3 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
CO
COMPOUND
TOXAPHENE
2.3,7. 8-TETRACHLORGDIBENZO-P-DIOXIN
ANTHRACENE/PHENANTHRENE
BENZO(A)ANTHRACENE/CHRYSENE
BENZO(3,4/K)FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
9
13
11
4
2
23
23
23
23
23
23
15
23
23
23
23
23
23
23
TOTAL
NUMBER
DETECT
O
0
2
O
O
10
10
1
2
13
15
1
8
10
8
11
11
3
19
NUMBER
SAMPLES
>10UQ/L
O
0
2
0
0
1
7
O
2
12
9
O
3
0
7
7
9
O
18
DETECTED CONCENTRATIONS
MIN
,
28
.
.
2
2
3
12
9
a
e
3
0.30
S
1
2
2
a
10%
*
*
*
*
*
2
2
*
*
10
8'
*
*
0.30
*
1
2
*
18
MEDIAN
m
28
,
.
3
13
3
12
27
12
0
40
0.90
69
12
11
2
38
MEAN
.
32
.
.
S
16
3
IB
39
14
6
167
1.09
82
25
16
2
63
IN UQ/L
90%
*
*
*
*
*
9
28
*
*
67
21
*
*
1.60
*
65
26
*
142
MAX
9
35
.
.
13
37
3
18
126
27
6
620
2.50
180
77
3O
3
1B7
-------
Table VI-3 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
oo
ro
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOSCTOTAL-FIBERS/LITER)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CAC03)
MO ALKALINITY (CACO3)
PHENOLICS(4AAP)
SULFATE
TOTAL SOLIDS
TOTAL
NUMBER
SAMPLES
22
24
23
23
a
15
14
10
6
14
15
1
13
15
S
10
NUMBER
TOTAL
DETECTS
21
24
22
22
8
1O
14
10
4
9
14
1
13
2
S
10
DETECTED CONCENTRATIONS
MIN
2700
3.5
63
22
B60000
1O2OO
35OOO
3OOOO
14OO
O.O
260
280OO
100
14
13OOOO
43OOOO
10%
3865
6.1
71
82
*
1O200
41400
30OOO
*
*
365
*
3670
*
*
430000
MEDIAN
14OOO
7.3
859
1300
130OE5
23667
330OOO
1350OO
1400
O.O
69OO
28OOO
29OOO
14
441667
29OOE3
MEAN
34184
7.5
1575
2O86
B456E5
43637
1223E3
21B625
35OO
0.1
7457
28000
47238
17
629333
3O9OE3
IN UQ/L
90X
6230O
8.6
4400
5672
*
49400
262OE3
43OOOO
*
*
15640
*
1134OO
*
*
BOOOE3
MAX
19785O
10.8
65OO
7167
21OOE8
19OOOO
66OOE3
53OOOO
6600
0.1
17200
28OOO
13OOOO
2O
1373E3
81OOE3
-------
Table VI-4
WASTHMATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
00
U)
COMPOUND
ACENAPHTHENE
ACROLEXN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1,2, 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
1 ,2-DICHLOROETHANE
1,1. 1-TRICHLOROETHANE
HEXACHLOROETHANE
1.1-DICHLOROETHANE
1,1, 2-TRICHLOROETHANE
1,1,2 , 2-TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BtS(2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2 -CHLORONAPHTHALENE
2,4, B-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 , 2-DICHLOROBENZENE
1 , 3-DICHLOROBENZENE
1 . 4-DICHLOROBENZENE
3 , 3-DICHtOROBENZIDINE
TOTAL
NUMBER
SAMPLES
3O
28
28
28
30
28
27
30
30
28
28
30
28
28
28
28
28
30
28
30
3O
3O
28
3O
30
30
30
3O
TOTAL
NUMBER
DETECT
O
O
O
9
O
0
O
0
O
2
4
1
O
0
O
0
O
O
O
O
0
0
21
O
2
O
1
1
NUMBER
SAMPLES
>10UQ/L
O
0
O
1
0
O
0
O
O
0
0
0
0
0
0
0
O
O
0
O
O
O
11
O
1
O
0
0
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
,
.
0
.
.
.
.
.
1
1
3
. .
,
,
.
,
,
.
.
.
.
M
.
3
.
3
1
m
.
1
1
3
•
11
t
3
.
3
3 * 3
MEAN 90X MAX
.
.
3
f
.
t
u
,
1
2
3
,
,
.
m
t
f
.
.
,
.
50 12
,
11
9
3
3
IB
.
i
3
3
.
.
.
.
t
m
488
.
18
3
3
-------
Table VI-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
CO
J=-
COMPOUND
1 , 1-DICHLOROETHYLENE
1,2-TRANS-DICHLOROETHYLENE
2 , 4-DICHLOROPHENQL
1 . 2 -DICHLOROPROPANE
1 , 3-DICHLOROPROPENE
2.4-DIMETHYLPHENOL
2.4-DINITROTOLUENE
2.6-DINITROTOLUENE
1 ,2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BIS(2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORN
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHANE
DICHLORODIFLUORQMETHANE
CHLORODXBRONOMETHANE
HEXACHLOROBUTAOIENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
28
28
3O
28
28
30
30
3O
30
28
3O
30
3O
30
3O
28
28
28
28
28
28
28
28
SO
30
SO
30
30
TOTAL
NUMBER
DETECT
2
3
O
O
O
O
0
O
O
4
1
O
0
O
0
25
O
O
O
O
4
O
O
O
O
O
1
0
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UQ/L MIN 10% MEDIAN MEAN 0O% MAX
0 3
O 0
o
o ,
o
o .
o
o
o
1 1
O 3
o .
o
o
0
22 3
o
O
o
0
4 18
O
o
0
o
0
3 3
1 1
. ,
» ,
m t
t m
3 5
3 3
. ,
. ,
792 S090 848
. .
. .
, .
".
17 19
. ,
. .
. .
. .
. .
1 11 * 11 11
o *
3
2
11
3
,
,
,
,
71000
.
,
,
,
28
,
.
.
11
.
-------
Table VI-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
CO
COMPOUND
2-NITROPHENOL
4-NITROPHENOL
2.4-DINITROPHENOL
4 . B-DINITRO-0-CRESOL
N-NtTROSOOZNETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSODX-N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
OI-N-BUTYL PHTHALATE^
Dl-N-OCTYL PHTHALATE
DI ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO(A)ANTHRACENE
BENZO(A)PYRENE
BENZO10UQ/L
O
0
O
0
0
0
O
0
0
12
0
8
O
1
0
0
0
O
O
0
0
0
0
0
0
1
1
O
DETECTED CONCENTRATIONS IN UO/L
MIN 10% MEDIAN
.
3
3
a
f
.
3
3
«
3
M
3
3
,
^
t
t
m
m
. •
#
3
1
t
12
10
2
.
3
3
.
,
3
3
170
3
3
3
3
.
t
f
.
a
^
.
.
3
1
t
12
10
2
MEAN 00% MAX
3
3
3
3
B72 77
3
28O 67
3
81
t
f
.
,
.
.
.
3
1
.
12
1O
2
3
3
3
3
4400
3
96O
3
39O
3
1
12
1O
2
-------
Table VI-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
oo
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4 . 4-DDT
4.4-DDE
4.4-DDO
ENDOSULFAN- ALPHA
ENDOSULFAN-BETA
ENOOSULFAN SULFATE
EHDRIM
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACKLOR E POX IDE
BHC-ALPHA
BHC-BETA
BUG (LINDANE)-QAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242}
PC8-12S4 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-1280 (AROCHLOR 12 BO)
PCB-1O16 (AROCHLOR 1O16)
TOTAL
NUMBER
SAMPLES
28
28
28
28
28
28
30
28
28
28
28
28
30
30
28
28
28
28
28
28
28
30
30
30
30
30
30
30
TOTAL
NUMBER
DETECT
8
10
2
0
1
0
o
0
o
o
o
0
o
o
0
1
1
1
1
1
1
o
o
0
0
o
0
o
NUMBER
SAMPLES
MOUQ/L
2
4
0
O
O
0
0
0
o
o
o
0
o
o
0
0
o
o
o
o
o
o
o
0
0
0
0
0
DETECTED CONCENTRATIONS IN UQ/L
MIN 10X MEDIAN
1 » 4
0 O 2
1 V 1
,
2.24
,
,
,
,
B
.
.
.
,
t
2.24
2.24
0.10
0.2B
2.24
O.1O
.
.
.
.
.
.
.
^
2.24
.
,
9
,
,
,
.
.
.
t
2.24
2.24
O.10
O.2B
2.24
O.1O
a
,
B
MEAN 90% MAX
14 * 81
12 40 40
2
4
2.24
.
.
.
.
.
.
„
.
.
w
2.24
2.24
0.10
0.2B
2.24
O.10
u
9
.
,
.
.
.
3
2.24
.
,
,
.
m
,
.
,
,
t
2.24
2.24
0. 1O
O.28
2.24
0.1O
.
.
*
.
-------
Table VI-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
TOXIC POLLUTANTS
oo
—3
COMPOUND
TOXAPHENE
2.3,7,8 -TETRACHLORODIBEN20-P-DIOXIN
ANTHRACENE/PHENANTHRENE
BENZO(A)ANTHRACENE/CHRYSENE
BENZOO . 4/K ) FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
30
30
29
8
8
57
57
57
57
57
67
37
57
57
57
57
57
66
56
TOTAL
NUMBER
DETECT
0
0
3
1
0
18
25
1
7
32
24
4
14
25
9
12
9
9
37
NUMBER
SAMPLES
>10UQ/L
0
0
0
0
0
5
4
0
5
28
9
0
8
1
8
3
9
2
33
DETECTED CONCENTRATIONS
MIN
,
3
3
.
1
2
0
5
8
3
3
2
O.1O
10
1
13
1
7
10X
*
*
*
*
*
1
2
*
*
10
5
*
2
O.3O
*
1
*
*
10
MEDIAN
.
3
3
.
3
6
0
14
34
9
3
20
O.65
55
3
17
2
43
MEAN
.
3
3
.
6
9
0
14
63
13
4
36
1.63
62
19
19
6
52
IN UG/L
BOX
*
*
*
*
*
IB
12
*
*
64
27
*
81
2. 2O
*
24
*
*
101
MAX
•
,
3
3
,
IB
72
0
23
eeo
4O
7
109
13.00
146
160
25
23
188
-------
Table VI-4 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ACID DRAINAGE MINES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
MIN
DETECTED CONCENTRATIONS IN UQ/L
10X MEDIAN MEAN BOX MAX
oo
CO
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS*TOTAL-FIBERS/LITER)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
FREE ACIDITY (CAC03)
MO ALKALINITY (CAC03)
PHENOLICS(4AAP)
TOTAL ACIDITY (CAC03)
TOTAL SOLIDS
SB
sa
57
56
1S
37
23
29
24
32
34
1
23
30
1
27
B6
56
B4
47
15
35
23
29
IS
26
31
1
23
5
1
27
32 2OOO
3.2 7.1
21 132
11 18
33OOE4 33OOE4
4O 9700
86000 205000
440OO 6S2OO
1OOO 1OOO
O.O 0.0
100O 3O87
50 *
23000 84900
2 *
105OO *
148OOO 312OOO
125OO
7.8
39O
170
2050E8
22413
86OOOO
135OOO
4000
0.0
9383
50
245OOO
9
10500
82000O
29542 7OB27 45OOOO
7.7 8.4 9.4
892 2589 51OO
381 110O 28OO
1053E7 2B5OE7 5200E7
117475 45SOO 326OE3
1198E3 278OE3 36OOE3
2571E3 608426 67OOE4
16133 1288O 2OOOOO
8.2 O.4 2OO.O
19595 4762O 65OOO
SO * 50
28O783 494000 620OOO
16 * 40
10500 * 10500
8O31E3 248OE3 19OOE5
-------
Table VI-5
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
oo
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1,2, 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
1 . 2-DICHLOROETHANE
1,1.1 -TRICHLOROETHANE
HEXACHLOROETHANE
1 , 1-DICHLOROETHANE
1,1, 2 -TRICHLOROETHANE
1,1,2. 2-TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2 -CHLORONAPHTHALENE
2 , 4 ,8-TRlCHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 , 2-DI CHLOROBENZENE
1 ,3-DICHLOROBENZENE
1 , 4-OICHLOROBENZENE
3,3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
O
O
O
2
O
O
0
0
0
0
3
O
0
O
1
O
O
0
0
O
0
O
a
O
0
O
0
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10UQ/L MZN 10X MEDIAN MEAN 9OX MAX
0 . . .
o
O
1 1
o
O
O •
0
0 .
o
0 2
O
0 .
o
O 3
O
0 •
0
0
0
0
o
3 3
O
o
0
o
0
f
i 7
.
.
,
,
2 2
.
.
.
3 3
.
,
.
.
3 21
, t
t
.
.
12
3
3
78
*
-------
Table VI-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
COMPOUND
1 , I-OICHLOROETHYLENE
1 . 2-TRANS-DICHLOROETHYLENC
2 . 4-DICHLOROPHENOL
1 ,2-DICHLOROPROPANE
1 . 3-DICHLOROPROPENE
2 . 4-DXMETHYLPHENOL
2 . 4-DINITROTOLUENE
2.B-DINITROTOLUENE
1 . 2-DIPHENYLHYDRAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL> ETHER
BIS(2-CHLOROETHOXY) METHANE
HETHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHANE
OICHLORQOIFLUOROMETHANE
CHLORODIBROMOMETHANE
HEXACHLOROBUTADIENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
6
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
1
3
O
O
O
o
o
o
o
1
o
o
o
o
1
B
o
o
o
o
o
o
o
o
0
o
1
o
NUMBER DETECTED CONCENTRATIONS IN UGYL
SAMPLES
> 10UQ/L MIN 10% MEDIAN MEAN 9O% MAX
O 3 33 3
0 1
O
O
0
o
O •
0
o
0 3
O
o
o
o
0 3
4 3
O
0
o
o
o
o
o
o
o
o
0 3
O
2 B
. .
3 3
t f
, 9
3 3
4B3 3998
. .
, m
•
m ft
. .
, ,
. .
, .
3 3
. .
10
.
.
.
.
.
.
.
3
,
.
.
»
3
20000
3
.
-------
Table VI-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL NUMBER
NUMBER SAMPLES
DETECT >100Q/L
DETECTED CONCENTRATIONS IN UQ/L
NIN
10% MEDIAN MEAN BOX
MAX
2-NITROPHENOL
4-NITROPHENOL
2,4-DINITROPHEMOt
4,6-DXNITRO-O-CRESOL
N-NITRpSODIMETHYLAMINE
N-NITROSODIPHENYLAMINE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BISU-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
01ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO(A)ANTHRACENE
BENZO(A)PYRENE
BENZO(B)FLUORANTHENE
8ENZO(K)FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO(Q,H,I)PERYLENE
FLUORENE
PHENANTHRENE
DIBENZO(A,H)ANTHRACENE
INDENO(1,2,3-C.D)PYRENE
PYRENE
o
o
o
0
0
o
o
o
3
8
O
3
0
3
0
O
O
0
0
o
o
0
0
0
o
0
0
o
0
0
o
0
o
0
o
o
0
3
o
1
0
1
o
o
0
0
o
o
o
o
0
o
o
0
o
0
3
180
•2
285
3
BIO
27O
79O
-------
Table VI-5 (Continued)
WASTEWAfER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
vo
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4. 4 -DDT
4, 4 -DDE
4.4-DDD
ENDOSULFAN- ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENORXN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE
BHC-ALPHA
BHC-BETA
BHC (LINOANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-126O (AROCHLOR 128O)
PCB-1O16 (AROCHLOR 1O16)
TOTAL
NUMBER
SAMPLES
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
TOTAL
NUMBER
DETECT
a
3
1
0
0
o
0
o
o
o
o
o
o
0
0
o
0
o
o
o
o
0
0
0
o
0
o
o
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>1OUQ/L MIN 1OX MEDIAN MEAN 8O% MAX
13 4 * 20
1 0
O 3
O
O
O
0
o
o
0
o
o
0 •
o .
.0
o
o
o
o
o
o
o
o
o
o
o
o
o
3 4
3 3
. .
, ,
. .
. t
, ,
, ,
, ,
. ,
, ,
. ,
. ,
. .
. ,
. .
. .
. .
.
. .
.
. .
. .
.
.
7
3
.
,
.
.
.
.
.
.
.
.
.
,
.
.
.
.
.
.
.
.
,
.
.
*
*
-------
Table VI-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
TOXIC POLLUTANTS
vo
UJ
COMPOUND
TOXAPHENE
2,3,7. 8-TETRACHLORODIBEHZO-P-DIOXIN
ANTHRACENE/PHENANTHRENE
BENZO ( A ) ANTHRACENE/CHRYSENE
BENZO ( 3 , 4/K ) FLUORANTHENE
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
CYANIDE (TOTAL)
LEAD (TOTAL)
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
7
7
3
1
1
9
9
9
9
9
9
7
9
9
TOTAL
NUMBER
DETECT
0
0
1
O
0
3
4
0
1
4
6
O
2
1
2
4
2
4
8
NUMBER
SAMPLES
>10U6/L
0
O
O
O
0
0
1
0
O
4
4
0
2
O
2
3
1
O
.8
DETECTED CONCENTRATIONS IN UQ/L
MIN 10% MEDIAN
* •
.
3
.
.
1
2
.
3
24
B
.
87
O.30
20
B
8
1
39
,
3
.
.
1
3
.
3
24
13
.
87
0.30
20
7
8
2
40
MEAN 80% MAX
.
3
.
*
2
1O
*
3
31
2O
.
82
O.30
35
20
1b
3
70
.
3
*
„
3
30
,
3
41
48
,
87
O.3O
BO
BO
24
7
2OO
-------
Table VI-5 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY PREP PLANTS
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
\o
Jr
COMPOUND
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
ASBESTOS< TOTAL-FIBERS/LITER )
COO
DISSOLVED SOLIDS
TOTAL VOLATILE SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
MO ALKALINITY (CACO3)
PHENOLICS(4AAP)
TOTAL ACIDITY (CAC03)
TOTAL SOLIDS
TOTAL
NUMBER
SAMPLES
8
9
9
8
1
7
2
4
3
2
4
B
7
3
4
NUMBER
TOTAL
DETECTS
B
9
9
S
1
7
2
4
3
2
4
5
3
3
4
DETECTED CONCENTRATIONS IN UO/L
MIN 1OX MEDIAN
2500
6.2
98
25
1400E5
2035O
58OOOO
94000
3BOO
O.O
B87S
19000
10
3000
7OOO
118OO
7.1
388
86
1400E5
35200
56OOOO
140OOO
4200
0.0
11600
4O750
1O
35OO
53OOOO
MEAN 90X MAX
14O44 28500
7.4
868
247
1400ES
44984
1O20E3
210438
10133
0.1
14669
61900
12
3833
1334E3
9.1
4400
700
MOOES
113000
1480E3
42OOOO
22OOO
0.1
25000
1185OO
IS
4500
37OOE3
-------
Table VI-6
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1,2, 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
,2-OICHLOROETHANE
. 1 , 1-TRICHLOROETHANE
HEXACHLOROETHANE
, 1-DICHLOROETHANE
. 1 ,2-TRICHLOROETHANE
,1,2,2 -TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS(2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2-CHLORONAPHTHALENE
2 , 4 , 6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 . 2-DICHLOROBENZENE
1 . 3-DICHLOROBENZENE
1 , 4-DICHLOROBENZENE
3 , 3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
TOTAL
NUMBER
DETECT
O
O
O
1
O
0
O
0
O
O
1
0
O
O
0
0
0
0
O
O
O
O
3
0
0
O
0
O
NUMBER DETECTED CONCENTRATIONS IN Ufl/L
SAMPLES
MOUQ/L MIN 10X MEDIAN MEAN 9OX MAX
0 .
O
0
0 6
O
O
0
0
O
O
0 2
O
0
O
O
o
o
0 .
0
0
o
o
2 3
O
o
0
0
o
6 6
f *
.
2 2
11 166
. ,
. .
. m
.
,
6
,
.
.
.
f
t
2
.
,
.
,
t
t
m
t
€
,
,
476
#
t
t
,
.
-------
Table VI-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL
NUMBER
DETECT
NUMBER
SAMPLES
>10UQ/L
DETECTED CONCENTRATIONS IN UG/L
MXN10% MEDIAN MEAN 555 MAX
1.1 -DICHLOROETHYLENE 3
1.2-TRANS-DICHLOROETHYLENE 3
2.4-DICHLOROPHENOL 3
1,2-DICHLOROPROPANE 3
1.3-DICHLOROPROPENE 3
2,4-DIMETHYLPHENOL 3
2,4-OINITROTOLUENE 3
2.6-DINITROTOLUENE 3
1.2-DIPHENYLHYDRAZINE 3
ETHYLBEKZENE 3
FLUORANTHENE 3
4-CHLOROPHENYL PHENVL ETHER 3
4-BROMOPHENYL PHENVL ETHER 3
BISiX-CHLORQISOPROPYL) ETHER 3
BISC2-CHLOROETHOXY) METHANE 3
METHYLENE CHLORIDE (DICHLOROMETHANE) 3
METHYL CHLORIDE 3
METHYL BROMIDE 3
BRONDFORM 3
DXCHLOROBROMONETHANC 3
TRICHLOROFLUOROMETHANE 3
DICHLORODIFLUOROMETHANE 3
CHLOROOIBRONOMETHANE 3
HEXACHLOROBUTADXENE 3
HEXACHLOROCYCLOPENTADIENE 3
XSOPHORONE 3
NAPHTHALENE 3
NITROBENZENE 3
O
1
O
O
O
O
O
O
O
O
O
O
O
O
0
3
0
O
O
O
1
O
O
0
0
0
O
O
O
O
O
O
O
O
0
O
O
O
O
O
O
O
O
3
O
O
O
O
1
O
O
0
O
O
O
O
22
SB3 22369
22 22
B6000
22
-------
Table VI-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
COMPOUND
2-NXTROPHENOL
4-NITRQPHENOL
2,4-DINITROPHENOL
4 . 6-DINITRO-O-CRESOL
N-NXTROSOPIMETHYLAMINE
N-NITROSOOIPKENYLAMJNE
N-NITROSODI -N-PROPYLAMINC
PENTACHLOROPHENDL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
DI ETHYL PHTHALATE
DIMETHYL PHTHALATE-
BENZO < A ) ANTHRACENE
BENZO(A)PYRENE
BENZO ( B ) F LUORANTHENE
BENZCK K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO(G,H,I.)PCRYLENE
FLUORENE
PHENANTHRENE
DXBENZO(A,H)ANTHRACENE
XNDENO(1.2,3-C.D)PYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
TOTAL
NUMBER
DETECT
O
0
0
0
O
0
O
O
O
3
0
2
O
0
0
O
O
O
0
0
O
O
O
O
0
O
0
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
SAMPLES
>10OQ/L MIN 10% MEDIAN MEAN tO% MAX
O .
O
O
o
o
0
o .
0
0
1 3
o .
1 3
o
0
0
0
0
o
o
o
0
o
o
0
0
o
0
o
, ^
7 2038
, .
3 107
. f
9 9
9 t
* •
. .
. p
. .
. .
,
^
*
s
,
%
*
%
6100
.
210
B
,
,
.
t
.
.
B
.
.
f
t
m
-------
Table VI-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
.£>
OO
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DIELDRIN
CHLORDANE
4,4-DDT
4.4-DDE
4,4-DDD
ENDOSULFAN- ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR E POX IDE .
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-12S4 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-1260 (AROCHLOR 12BO)
PCB-1O18 (AROCHLOR 1O16)
TOTAL
NUMBER
SAMPLES
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
TOTAL
NUMBER
DETECT
1
2
0
0
1
0
o
1
o
I
o
o
o
0
o
1
o
1
1
o
1
o
0
0
0
0
o
0
NUMBER
SAMPLES
MOUG/L
0
0
0
0
0
O
0
o
0
o
o
o
0
0
0
0
o
o
o
0
0
o
0
0
0
0
o
o
DETECTED CONCENTRATIONS IN UO/L
MIN 10% MEDIAN
1 1
2
.
^
2.24
.
,
2.24
f
2.24
f
^
m
f
.
2.24
,
2.24
2.24
,
2.24
^
,
,
.
,
.
.
2
.
2.24
.
^
2.24
.
2.24
.
.
.
.
2^24
f
2.24
2.24
B
2.24
.
t
MEAN 00% MAX
1 t
3
.
ft
2.24
.
.
2.24
. •
2.24
.
.
.
2^24
.
2.24
2.24
fc
2.24
,
,
B
m
t
.
»
3
,
2.24
.
.
2.24
.
2.24
.
.
.
2^24
t
2.24
2.24
t
2.24
,
r
t
f
.
-------
Table VI-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL NUMBER
NUMBER SAMPLES
DETECT >10UG/L
DETECTED CONCENTRATIONS IN UQ/L
MIN
10X MEDIAN MEAN 90%
MAX
TOXAPHENE 3
2.3,7,8-TETRACHtORODIBENZO-P-DIOXIN 3
ANTHRACENE/PHENANTHRENE 3
BENZOCA)ANTHRACENE/CHRYSENE 1
BENZO(3.4/K)FLUORANTHENE 1
ANTIMONY (TOTAL) 8
ARSENIC (TOTAL) 8
BERYLLIUM (TOTAL) a
CADMIUM (TOTAL) 8
CHROMIUM (TOTAL) 8
COPPER (TOTAL) 8
CYANIDE (TOTAL) 3
LEAD (TOTAL) 8
MERCURY (TOTAL) 8
NICKEL (TOTAL) 8
SELENIUM (TOTAL) 8
SILVER (TOTAL) 8
THALLIUM (TOTAL) 8
ZINC (TOTAL) 8
0
0
0
O
0
O
O
O
2
5
3
0
O
O
3
O
2
O
B
2
2
IB
14
B
3
0.40
50
1
8
19
2
3
IS
27
11
3
0.55
59
2
17
38
3
3
18
30
18
3
1.80
83
B
22
Be
4
4
17
48
32
3
4.3O
130
9
31
ISO
-------
Table VI-6 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY ASSOCIATED AREAS
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
MIN
DETECTED CONCENTRATIONS IN UQ/L
1OX MEDIAN MEAN 90X MAX
ro
o
o
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
COD
DISSOLVED SOLIDS
TOTAL VOLATILE.SOLIDS
VOLATILE SUSPENDED SOLIDS
SETTLEABLE SOLIDS
TOTAL ORGANIC CARBON
NO ALKALINITY (CACO3)
PHENOLICS(4AAP)
SULFATE
TOTAL SOLIDS
6000
7.2
2O5
27
15SOO
1550E3
2GOOO
48OO
o.o
ssoo
250OO
170OOO
180000
18400
7.6
62O
348
17217
162SE3
3100O
480O
0.0
5500
34500
24897
a.o
1760
1775
21178
1717E3
40111
122OO
0.1
6567
64167
170000
180OOO
170000
220000
62000
9.7
9500
63OO
291OO
19OOE3
58333
1960O
0.1
7633
123500
170000
2OOOOO
-------
Table VI-7
WASTEWATER CHARACTERIZATION SUMMAP.Y
FINAL EFFLUENT
SUBCATEGORY AREAS UNDER RECLAMATION
TOXIC POLLUTANTS
COMPOUND
ANTIMONY (TOTAL)
ARSENIC (TOTAL)
BERYLLIUM (TOTAL)
CADMIUM (TOTAL)
CHROMIUM (TOTAL)
COPPER (TOTAL)
LEAD (TOTAL) •
MERCURY (TOTAL)
NICKEL (TOTAL)
SELENIUM (TOTAL)
SILVER (TOTAL)
THALLIUM (TOTAL)
ZINC (TOTAL)
TOTAL
NUMBER
SAMPLES
14
14
14
14
14
14
14
14
14
14
14
14
14
TOTAL
NUMBER.
DETECT
11
2
5
3
8
11
0
O
3
2
4
3
14
NUMBER
SAMPLES
>1OUG/L
11
2
0
O
5
8
O
O
3
2
O
3
14
DETECTED CONCENTRATIONS
MIN
52
42
1
6
6
5
.
71
42
B
12
8
10%
53
*
*
*
*
5
*
*
*
*
*
*
9
MEDIAN
78
42
1
7
9
15
.
.
82
42
B
23
C2
MEAN
100
49
2
7
12
17
.
'.
115
80
6
81
71
IN UQ/L
90%
116
*
*
*
*
26
*
*
*
«
*
*
187
MAX
255
55
3
8
24
41
.
.
182
77
7
137
382
-------
Table VI-7 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
FINAL EFFLUENT
SUBCATEGORY AREAS UNDER RECLAMATION
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
NUMBER
TOTAL
DETECTS
MIN
DETECTED CONCENTRATIONS IN UQ/L
10% MEDIAN MEAN 90% MAX
ro
o
ro
TOTAL SUSPENDED SOLIDS
PH (UNITS)
IRON (TOTAL)
MANGANESE (TOTAL)
SETTLEABLE SOLIDS
15
15
15
14
12
15 1O400 11OO4 21675 2984S 46125 81969
15 5.5 6.0 7.5 7.4 7.9 B.O
15 302 315 B14 21O1 6457 112OS
14 77 84 235 828 911 B94O
5 O.O * O.1 3.1 * 14.8
-------
Table VI-8
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
o
LO
Pollutant
acenaphthene
aerolein
acrylonitrlle
benzene
benzldine
carbon tetrachloride
(tetrachloromethane)
chlorobenzene
1,2,4-trtchlorobenzene
hexachlorobenzene
1,2-dichloroethane
1,1,1-trtchloroethane
hexachloroethane
1,1-dichloroethane
1,1,2-trlchloroethane
1,1,2,2-tetrachloro-
ethane
chloroethane
bis(chloromethyl)ether
bis(2-chloroethyl)ether
Not
Detected
x
x
X
Believed to be Detected
from But Always
Contamination Below 10 ug/1
Detected in Amounts
too Small to Be
Effectively Reduced
x
X
X
X
X
X
X
X
X
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
tu
o
-Cr
Pollutant
2-chloroethyl vinyl
ether (mixed)
2-chloronaphthalene
2,4,6-trichlorophenol
parachlorometa cresol
chloroform (trichloro-
methane)
2-chlorophenol
1,2-dichlorobenzene
1,3-dichlorobenzene
1,4-dichlorobenzene
3,3'-dichlorobenzidine
1,1-dichloroethylene
1,2-trans-dichloro-
ethylene
2,4-dichlorophenol
1,2-dichloropropatie
1,2-dichloropropylene
(1,3-dichloropropene)
2,4-dimethylphenol
Not
Detected
x
x
X
X
X
Detected in Amounts
too Small to Be
Effectively Reduced
x
x
X
X
X
X
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
ro
o
Pollutant
2,4-dinitrotoluene
2,6-dinitrotoluene
1,2-diphenylhydrazine
ethylbenzene
fluoranthene
4-chlorophenyl phenyl
ether
4-bromophenyl phenyl
ether
bts(2-chloroisopropyl)
ether
bis(2-chloroethoxy)
methane
methylene chloride
(dichloromethane)
methyl chloride
(chloromethane)
methyl bromide
(bromoraethane)
bromoform
Not
Detected
x
x
X
Believed to be Detected
from But Always
ContaminatJon Below 10 ug/1
Detected in Amounts
too Small to Be
Effectively Reduced
x
x
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
ru
o
Pollutant
d ichlorobromomethane
trichlorofluoromethane
d ichlorod i fluoromethane
chlorod ibromome thane
hexachlorobutadiene
hexachlorocyclopen-
tadiene
isophorone
naphthalene
nitrobenzene
2-nitrophenol
4-nitrophenol
2,4-dinitrophenol
4,6-dinitro-o-cresol
N-nitrosodimethylamine
N-nttrosodlphenylamine
N-nitrosodi-n-
propylamine
pentachlorophenol
phenol
Not
Detected
Believed to be
from
Contamination
Detected
But Always
Below 10 ug/1
Detected in Amounts
too Small to Be
Effectively Reduced
x
x
X
X
X
X
X
X
X
X
X
X
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
Pollutant
bis(2-ethylhexyl)
phthalate
butyl benzyl phthalate
di-n-butyl phthalate
di-n-octyl phthalate
diethyl phthalate
dimethyl phthalate
benzo(a)anthracene
(1,2-benzanthracene)
benzo(a)pyrene(3,4-
benzopyrene)
3,4-benzofluoranthene
benzo(k)fluoranthene
(11,12-benzofluoran-
thene)
chrysene
acenaphthylene
anthracene
benzo(g,h,i)perylene
(1,12-benzoperylene)
Not
Detected
Believed to be Detected
from But Always
Contaminat ion Below 10 ug/1
Detected in Amounts
too Small to Be
Effectively Reduced
x
X
X
X
X
X
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
o
CO
Pollutant
fluorene
phenanthrene
dibenzo(a,h)anthracene
(1,2,5,6-dibenzan-
thracene)
indeno(l,2,3-c,d)pyrene
(phenylenepyrene)
pyrene
tetrachloroethylene
toluene
vinyl chloride
(chloroethylene)
trichloroethylene
aldrin
dieldrin
chlordane (technical
(mixture and* metabo-
lites)
4,4'-DDT
4,4'-DDE (p,p'-DDX)
4,4'-DDD (p,p'-TDE)
-endosulfan-Alpha
Not
Detected
Believed to be
from
Contamination
Detected
But Always
Below 10 ug/1
Detected in Amounts
too Small to Be
Effectively Reduced
x
x
X
X
-------
Table VI-8 (Continued)
COAL MINING POINT SOURCE CATEGORY ORGANIC PRIORITY POLLUTANTS
DETERMINED TO BE EXCLUDED
TO
O
Pollutant
-endosulfan-Beta
endosulfan sulfate
endrin
endrin aldehyde
heptachlor
heptachlor epoxtde
-BHC-Alpha
-BHC-Beta
-BHC-(lindane)-Gamma
-BHC-Delta
PCB 1242 (Arochlor 1242)
PCB-1254 (Arochlor 1254)
PCB-1221 (Arochlor 1221)
PCB-1232 (Arochlor 1232)
PCB-1248 (Arochlor 1248)
PCB-1260 (Arochlor 1260)
PCB-1016 (Arochlor 1016)
toxaphene
2,3,7,8-tetrachlorodi-
benzo-p-dioxin (TCDD)
Not
Detected
x
x
X
X
Believed to be
from
Contamination
Detected Detected in Amounts
But Always too Small to Be
Below 10 ug/1 Effectively Reduced
x
x
X
X
X
X
X
X
X
X
X
X
X
X
-------
Table VI-9
PRIORITY ORGANICS NOT DETECTED IN TREATED EFFLUENTS
OF SCREENING AND VERIFICATION SAMPLES
1 . acenaphthene
2. acroletn
3. acrylonitrtle
4. benzidine
5. carbon tetrachloride (cetrachloromethane)
6. chlorobenzene
7. 1,2,4-trichlorobenzene
8. hexachlorobenzene
9. 1,1-dichloroethane
10. 1,1,2-trichloroethane
11. chloroethane
12. bis(chloromethyl) ether
13. bis(2-chloroethyl) ether
14. 2-chloroethyl vinyl ether (mixed)
15. 2-chloronaphthalene
16. 2,4,6-trichlorophenol
17. parachlorometa cresol
18. 2-chlorophenol
19. 1,3-dichlorobenzene
20. 2,4-dichlorophenol
21. 1,2-dichloropropane
22* 1,2-dichloropropylene (1,3-dichloropropene)
23. 2,4-dimethylphenol
24. 2,4-dtni trotoluene
25. 2,6-dinitrotoluene
26. 1,2-diphenylhydrazine
27. bis(2-chloroisopropyl) ether
28. 4-chlorophenyl phenyl ether
210
-------
Table VI-9 (Continued)
PRIORITY ORGANICS NOT DETECTED IN TREATED EFFLUENTS
OF SCREENING AND VERIFICATION SAMPLES
29. 4-bromophenyl phenyl ether
30. methyl chloride (chloromethane)
31. methyl bromide (bromomethane)
32. bromoform (tribromomethane)
33. dichlorobromomethane
34. dichlorodifluoromethane
35. chlorodibromomethane
36. h exachlorobutadi ene
37. hexachlorocyclopentadiene
38. isophorone
39. nitrobenzene
40. 2-nitrophenol
41. 4-nitrophenol
42. N-nitrosodimethylamine
43* N-nitrosodiphenylamine
44. N-nitrosodi-n-propylamine
45. dimethyl phthalate
46. benzo(a)pyrene
47. 3,4-benzofluoranthene
48. benzo(k)fluoranthane(l1,12-benzofluoranthene)
49. acenaphthylene
50. vinyl chloride (chloroethylene)
51. dieldrin
211
-------
Table VI-9 (Continued)
PRIORITY ORGANICS NOT DETECTED IN TREATED EFFLUENTS
OF SCREENING AND VERIFICATION SAMPLES
52. chlordane (technical mixture and metabolites)
53. 4,4'-DDE (p,p'-DDX)
54. a-endosulfan-Alpha
55. B-endosulfan-Beta
56. endosulfan sulfate
57. endrin
58. endrin aldehyde
59. PCB 1242 (Arochlor 1242)
60. PCB 1254 (Arochlor 1254)
61. PCB 1221 (Arochlor 1221)
62. PCB 1232 (Arochlor 1232)
63. PCB 1248 (Arochlor 1248)
64. PCB 1260 (Arochlor 1260)
65. PCB 1016 (Arochlor 1016)
66. toxaphene
67. 2,3,7,8-tetrachlorodibenzo-p-dioxin (TCDD)
212
-------
Table VI-10
PRIORITY ORGANICS DETECTED BUT PRESENT DUE TO
CONTAMINATION OF SOURCES OTHER THAN THOSE SAMPLES
SCREENING AND VERIFICATION SAMPLES
1. benzene
2. chloroform
3. methylene chloride
4. phenol
5. bis(2-ethylhexyl)phthalate
6. butyl benzyl phthalate
7. di-n-butyl phthalate
8. diethyl phthalate
9. tetrachloroethylene
10. toluene
213
-------
Verification, and EPA Regional Sampling and Analysis). The field
controls consisted of water that was run through the automatic sampler
for each composite sample site prior to the actual sampling. The
water used as control water was deionized and as such, any
contaminants appearing in the collected control water could be
attributed to the sampling apparatus or to the laboratory analysis.
The results for field control samples are found for all subcategories
in Table VI-11. Field blanks were also collected to assess
contamination in transport and in laboratory analysis. For the
volatile organics, deionized water was periodically placed in 45 ml to
125 ml vials and shipped to the laboratory for analysis. For the
remainder of the priority pollutants, a facility blank, prepared in
the laboratory, was hand-carried by sampling personnel during field
sampling. Table VI-12 summarizes the blanks for the screening and
verification sampling and analysis program. Table VI-2 indicates that
members of the phthalate class were observed in many of the samples
representing treated wastewater.
Only two of the phthalates (bis-phthalate and di-n-butyl phthalate)
were detected in the raw water (refer to Table V-4); however, five of
the phthalates (bis-phthalate, di-n-butyl phthalate, butyl benzyl
phthalate, di-n-octyl phthalate, and diethyl phthalate) were detected
in treated water. This suggests that these compounds were introduced
into the water during sample collection or analysis. It is known that
during sample collection, automatic composite samplers were equipped
with polyvinyl chloride (Tygon) tubing or manufacturer supplied
tubing. Phthalates are widely used as plasticizers to ensure that
tubing remains soft and flexible (2). These compounds, added during
manufacturing, have a tendency to migrate to the surface of tubing and
leach out into water passing through the sample tubing. In addition,
laboratory experiments were performed to determine if phthalates and
other priority pollutants could be leached from tubing used on
automatic samplers (3). The types of tubing used in these experiments
were: (1) Clear tubing originally supplied with the sampler at time
of purchase; and (2) Tygon S-50-HL, Class VI. Results of analysis of
the extracts representing the original and replacement Tygon tubings
are summarized in Table VI-13. The data indicate that both types
contain bis(2-ethylhexyl)phthalate and the original tubing leaches
high concentrations of phenol. Although bis(2-ethylhexyl)phthalate
was the only phthalate detected in the tubing in these experiments, a
similar experiment conducted as part of a study pursuant to the
development of BAT Effluent Limitations Guidelines for the Textiles
Point Source Category found dimethyl phthalate, diethyl phthalate, di-
n-butyl phthalate, and bis(2-ethylhexyl)phthalate, in tubing
"controls" (4). Thus, four of the phthalates bis(2-
ethylhexyl)phthalate, butylbenzyl phthalate, di-n-butyl phthalate,
diethyl phthalate and phenol can be attributed to contamination during
sample collection and cannot be conclusively identified with the
wastewater.
A number of the volatile organic compounds were detected during the
sampling program (benzene, chloroform, methylene chloride,
tetrachloroethylene, toluene). The volatile nature of these compounds
-------
Table VI-11
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
ui
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1 , 2, 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
,2-DICHLOROETHANE
, 1 , 1-TRICHLOROETHANE
HEXACHLOROETHANE
,1-DXCHLOROETHANE
. 1 ,2-TRICHLOROETHANE
, 1,2, 2 -TETRACHLOROETHANE
CHLOROETHANE
BIS(CHLOROMETHYL) ETHER
BIS( 2-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER {MIXED)
2 -CHLORON APHTHALENE
2,4,6-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 ,2-DICHLOROBENZENE
1 , 3-DICHLOROBENZENE
1 . 4-DICHLOROBENZENE
3,3-DICHLOROBENZIDINE
TOTAL
NUMBER
SAMPLES
44
1O
10
1O
44
1O
1O
44
44
10
1O
44
1O
1O
10
1O
28
44
1O
44
44
44
10
44
44
43
43
44
TOTAL
NUMBER
DETECT
O
0
O
B
0
0
O
O
0
O
1
O
O
0
O
0
0
O
O
O
O
O
2
O
2
0
3
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
MOUG/L MIN 10X MEDIAN MEAN §0% MAX
O .
O
O
5 21
o
O
o
o
o
0
0 3
O
O
O
o
o
o
o
o
0
o
o
1 3
O
0 3
O
O 1
O
9
• . *
27 52
9 m
.
.
3 3
.
f
.
. p
^
B
.
9
,
3 2S
.
3 3
.
2 2
.
IBS
,
3
.
^
,
.
47
3
.
3
.
-------
Table VI-11 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
ro
COMPOUND
1 . 1-DICHLOROETHYLENE
1 , 2-TRANS-DICHLOROETHYLENE
2 . 4-DICHLOHOPHENOL
1 . 2-DICHLOROPROPANE
1 . 3-DICHLOROPROPENE
2 , 4-DIMETKYLPHENOL
2 . 4-DINITROTOLUENE
2 . 6-DINITROTOLUENE
1 . 2-QIPHENVUHYORAZINE
ETHYLBENZENE
FLUORANTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPROPYL) ETHER
BIS(2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHANE
DICHLORODX FLUOROMETHANE
CHLORODIBROMOMETHANE
HEXACHLOROBUTAOI ENE
HEXACHLOROCYCLOPENTADIENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
10
1O
44
1O
1O
44
44
44
44
1O
44
44
44
44
44
1O
10
10
10
10
10
10
10
44
44
44
44
44
TOTAL
NUMBER
DETECT
O
O
O
O
0
O
O
0
O
O
1
O
O
O
O
9
O
O
O
O
O
O
O
O
0
O
1
O
NUMBER DETECTED CONCENTRATIONS IN UO/L
>10U8/L MIN 1OX MEDIAN MEAN 9O% MAX
D .
0
O
0
O
O
O
o
o
o
0 3
0
o
o
0
7 3
O
O
O
0
0
O
o
o
o
o
O 3
O
. .
» .
3 3
9
m .
282 3R9
. .
, .
. .
. .
. ,
, .
. .
3 3
.
9
,
,
^
.
.
.
,
.
3
m
m
m
»
88O
.
.
.
m
.
.
3
.
-------
Table VI-11 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
2-NXTROPHENOL
4-NITROPHENOL
2.4-OINITROPHENOL
4 . 6-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMXNE
N-NITROSODIPHENYLAMINE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-8UTYL PHTHALATE
DI-N-OCTYL PHTHALATE
DIETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO ( A ) ANTHRACENE
BENZO(A)PYRENE
BENZO( B )FLUORANTHEN£
BENZO( K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO (Q.H, I )PERYLENE
FLUORENE
PHENANTHRENE
DXBENZO(A,H)ANTHRACENE
INDENO(1,2.3-C,D)PYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
28
44
44
29
44
44
44
TOTAL
NUMBER
DETECT
0
O
1
1
0
O
O
O
2
19
2
13
O
5
O
O
O
0
0
0
O
NUMBER
SAMPLES
MOUG/L
0
0
O
O
0
O
O
O
O
14
O
7
O
O
O
O
O
O
O
0
0
0
0
0
0
O
O
O
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN
,
4
6
*
.
,
,
3
3
3
1
p
1
t
.
.
.
.
.
.
3
3
.
3
3
3
3
9
4
6
,
.
.
,
3
215
3
9
.
2
B
»
.
.
.
3
3
.
3
3
3
3
MEAN 90% MAX
9
4
a
,
t
4
.
3
453 121
3
275 88
.
2
.
.
.
.
.
.
.
3
3
.
3
3
3
3
9
4
0
9
,
9
f
3
1600
3
1100
9
. 3
,
t
,
,
.
„
.
3
3
.
3
3
3
3
-------
Table VI-11 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
ro
t-1
oo
COMPOUND
TETRACHLOROETHVLENE
TOLUENE
TRZCHLOROETHVLENE
VINYL CHLORIDE
ALDRIN
OIELDRIN
CHLORDANE
4.4-DDT
4.4-DDE
4.4-DDD
ENDOSULFAN-ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIN ALDEHYDE
HEPTACHLOR
HEPTACHLOR EPOXIDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-124B (AROCHLOR 1248)
PCB-126O (AROCHLOR 126O)
PCB-1O1B (AROCHLOR 1016)
TOTAL
NUMBER
SAMPLES
1O
1O
10
1O
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
TOTAL
NUMBER
DETECT
O
6
1
O
2
1
O
O
1
1
O
O
O
1
O
1
2
2
O
1
2
O
O
O
O
O
O
O
NUMBER
SAMPLES
>10UG/L
O
s
0
O
O
0
0
O
0
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
0
DETECTED CONCENTRATIONS IN UG/L
MIN 10X MEDIAN
3
3
.
3.16
3.18
.
9
3.16
3.16
.
.
.
3.16
.
3.18
3.18
3.16
„
3.16
3.16
.
.
.
.
.
.
.
23
3
t
3.16
3.16
3.16
3.16
m
,
*.
3.16
f
3.16
3.16
3.16
.
3.18
3.16
.
.
.
.
.
.
.
MEAN 80% MAX
41
3
,
3.16
3.16
9
m
3.16
3.16
,
9
,
3.16
.
3.16
3.16
3. .16
,
3.16
3.16
.
.
.
.
.
.
.
146
3
.
3.16
3.16
m
m
3.16
3.16
,
.
.
3.16
,
3.16
3.16
3.16
.
3.18
3.16
.
.
.
.
.
.
.
-------
Table VI-11 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL NUMBER
NUMBER SAMPLES
DETECT >10UQ/L
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN MEAN 9OX
MAX
TOXAPHENE 37 O O
2.3.7.8-TETRACHLORODIBENZO-P-DIOXIN 27 0 O
ANTHRACENE/PHENANTHRENE 2O O O
ANTIMONY (TOTAL) 19 2 O 1
ARSENIC (TOTAL) 19 1O 0 1
BERYLLIUM (TOTAL) 20 0 O
CADMIUM (TOTAL) 20 1 1 20
CHROMIUM (TOTAL) 2O 1 1 3O
COPPER (TOTAL) 2O 9 4 5
LEAD (TOTAL) 2O S 5 86
MERCURY (TOTAL) 2O 17 O 0.1O
NICKEL (TOTAL) 2O 2 2 SO
SELENIUM (TOTAL) 2O 6 O O
SILVER (TOTAL) 20 0 O
THALLIUM (TOTAL) 20 3 0 1
ZINC (TOTAL) 20 1O 10 27
*
*
*
*
1
*
*
*
*
*
O.1O
*
*
*
*
.
.
a
1
2
t
20
30
8
100
0.35
SO
2
.
1
.
,
.
1
2
.
20
30
17
102
0.99
SO
2
,
1
18
27
38
*
*
1O8 30O
1
5
20
3O
58
115
3.9O
50
2
38O
-------
Table VI-11 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
CONTROLS
ALL SUBCATEGORIES
CONVENTIONAL AND NONCONVENTIONAL POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL
NUMBER
DETECTS
DETECTED CONCENTRATIONS IN UG/L
MIN 10% MEDIAN MEAN BOX
MAX
TO
ro
o
IRON (TOTAL)
MANGANESE (TOTAL)
PHENOLICS(4AAP)
2O
20
1
18
6
O
43 I
10 *
*
116
15
4O36
46
4422
50000
19O
-------
Table VI-12
WASTEWATER CHARACTERIZATION SUMMARY
PLANT BLANKS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
FO
to
COMPOUND
ACENAPHTHENE
ACROLEIN
ACRYLONITRILE
BENZENE
BENZIDENE
CARBON TETRACHLORIDE
CHLOROBENZENE
1,2. 3-TRICHLOROBENZENE
HEXACHLOROBENZENE
1 . 2-DICHLOROETHANE
1,1, 1-TRICHLOROETHANE
HEXACHtOROETHANE
1,1-DICHLOROETHANE
1 , 1 , 2-TRICHLOROETHANE
1,1.2 .2-TETRACHLOROETHANE
CHLOROETHANE
BXS(CHLOROMETHYL) ETHER
BISU-CHLOROETHYL) ETHER
2-CHLOROETHYL VINYL ETHER (MIXED)
2-CHLORONAPHTHALENE
2 , 4 . 8-TRICHLOROPHENOL
PARACHLOROMETA CRESOL
CHLOROFORM
2-CHLOROPHENOL
1 , 2-DICHLOROBENZENE
1 . 3-DICHLOROBENZENE
1 . 4-DICHtOROBENZENE
3, 3-DICHLOROBENZIOINE
TOTAL
NUMBER
SAMPLES
21
If
11
11
2f
11
11
21
21
11
11
21
11
11
11
11
10
21
11
21
21
21
11
21
21
21
21
21
TOTAL
NUMBER
DETECT
O
O
O
9
O
O
2
O
0
2
2
O
O
f
1
O
O
O
0
O
0
O
ff
O
O
0
O
O
NUMBER DETECTED CONCENTRATIONS
IN UQ/L
>10UQ/L MIN 10% MEDIAN MEAN 90% MAX
O
O
O
3 1
O
O
O 3
O
O
0 1
0 1
O
O
O 3
0 3
O
O
o
o
0
o
o
6 3
0
O
o .
o
0
¥
9
3
B
m
3
,
.
1
f
9
,
3
3
9
,
*
.
.
.
.
ff
.
9
,
,
.
f
t
18
.
m
3
.
,
2
1
,
f
3
3
,
.
.
.
.
.
.
25 5
,
,
.
.
.
110
.
.
3
f
,
3
2
.
3
3
t
.
.
m
f
.
.
13O
,
m
9
,
,
-------
Table VI-12 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
PLANT BLANKS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
rvj
rv>
ro
COMPOUND
1 . 1-DICHLOROETHYLENE
1 ,2-TRANS-DICHLOROETHYLENE
2 , 4-DICHLOROPHENpL
1 , 2-DICHLOROPROPANE
1 ,3-OICHLOROPROPENE
2 . 4-DIMETHYLPHENOL
2 , 4-OINITROTOLUENE
2 ,6-DINITROTOLUENE
1 , 2 -DI PHENYLHYDRAZINE
ETHYLBENZENE
FLUORAHTHENE
4-CHLOROPHENYL PHENYL ETHER
4-BROMOPHENYL PHENYL ETHER
BIS(2-CHLOROISOPRQPYL) ETHER
BXS(2-CHLOROETHOXY) METHANE
METHYLENE CHLORIDE (DICHLOROMETHANE)
METHYL CHLORIDE
METHYL BROMIDE
BROMOFORM
DICHLOROBROMOMETHANE
TRICHLOROFLUOROMETHANE
OICHLORODIFLUOROMETHAKE
CHLOROOIBROMQMETHANE
HEXACHLOROBUTADI ENE
HEXACHLOROCYCLOPENTADXENE
ISOPHORONE
NAPHTHALENE
NITROBENZENE
TOTAL
NUMBER
SAMPLES
11
11
21
11
11
21
21
21
21
11
21
21
21
21
21
11
11
11
11
11
11
11
11
21
21
21
21
21
TOTAL
NUMBER
DETECT
0
2
O
O
O
O
O
0
O
4
O
0
O
O
O
10
O
O
1
0
6
0
O
0
0
O
O
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
a AMPLE 9 — — — «._——— — ».- — _—...-_ _—»_•________
>10UG/L MXN 10X MEDIAN MEAN 90X MAX
O .
0 1
O
O
o
O
o
o
o
1 1
o
0
o
1 2
.
.
.
. .
.
2 6
. .
o *
o *
9 33 2BOO 5321 11OOC
O *
O *
O 3*33
O .
6 13 25 29
O .
O .
0 .
0 .
O -
O .
O .
2
.
.
,
,
.
,
,
2O
.
.
.
,
.
23000
_ .
.
3
SO
.
.
.
.
.
.
-------
Table VI-12 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
PLANT BLANKS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
ro
U)
COMPOUND
2-NITROPHENOL
4-NITROPHENOL
2 . 4-DINITROPHENOL
4 . 6-DINITRO-O-CRESOL
N-NITROSODIMETHYLAMINE
N-NITROSODIPHENYLAMZNE
N-NITROSODI -N-PROPYLAMINE
PENTACHLOROPHENOL
PHENOL
BIS(2-ETHYLHEXYL) PHTHALATE
BUTYL BENZYL PHTHALATE
DI-N-BUTYL PHTHALATE
DI-N-OCTYL PHTHALATE
D I ETHYL PHTHALATE
DIMETHYL PHTHALATE
BENZO ( A ) ANTHRACENE
BENZO(A)PYRENE
BENZO(B)FLUORANTHENE
BENZO (K ) FLUORANTHENE
CHRYSENE
ACENAPHTHYLENE
ANTHRACENE
BENZO (G.H, I )PERYLENE
FLUORENE
PHENANTHRENE
01 BENZO ( A. H) ANTHRACENE
INDENO( 1 , 2 ,3-C. DIPYRENE
PYRENE
TOTAL
NUMBER
SAMPLES
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
TOTAL
NUMBER
DETECT
0
O
O
O
0
0
O
0
0
4
O
1
O
O
0
0
0
0
0
0
0
O
O
O
0
0
0
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
>10UG/L MIN 10% MEDIAN MEAN 9OX MAX
O .
O
O
0
0
O
0
O
O
4 16
0
1 22O
O
O
0
O
O
O
O
O
O
o
0
o
o
o
o
o
. .
. .
840 989
. .
220 22O
. .
. ,
.
.
.
,
m
t
,
,
,
,
9
16OO
,
22O
.
.
.
.
.
.
.
.
,
,
.
.
.
,
.
.
-------
Table VI-12 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
PLANT BLANKS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
ro
ro
COMPOUND
TETRACHLOROETHYLENE
TOLUENE
TRICHLOROETHYLENE
VINYL CHLORIDE
ALDRIN
DZELDRIN
CHLOROANE
4,4-DDT
4,4-DDE
4.4-DOD
ENDOSULFAN- ALPHA
ENDOSULFAN-BETA
ENDOSULFAN SULFATE
ENDRIN
ENDRIH ALDEHYDE
HEPTACHLOR
HEPTACHLOR EPOXXDE
BHC-ALPHA
BHC-BETA
BHC (LINDANE) -GAMMA
BHC-DELTA
PCB-1242 (AROCHLOR 1242)
PCB-1254 (AROCHLOR 1254)
PCB-1221 (AROCHLOR 1221)
PCB-1232 (AROCHLOR 1232)
PCB-1248 (AROCHLOR 1248)
PCB-126O (AROCHLOR 12BO)
PCB-1016 (AROCHLOR 1018)
TOTAL
NUMBER
SAMPLES
11
11
11
11
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
2(
21
21
21
TOTAL
NUMBER
DETECT
8
1O
1
O
O
O
O
O
O
O
O
O
0
O
O
0
O
O
O
0
O
O
O
O
O
0
O
O
NUMBER DETECTED CONCENTRATIONS IN UQ/L
>10UQ/L MIN 1O% MEDIAN MEAN *O% MAX
3 1 * 8 IB * 4O
2 33 5 20 7O 92
0 3
O
O
0
0
O
O
O
O
O
O
O
O
0
O
O
O
O
O
O
O
O
O
O
O
O
3 3
, .
3
.
^
.
,
.
,
,
.
.
,
,
.
.
.
.
.
.
.
.
.
.
.
.
-------
Table VI-12 (Continued)
WASTEWATER CHARACTERIZATION SUMMARY
PLANT BLANKS
ALL SUBCATEGORIES
TOXIC POLLUTANTS
COMPOUND
TOTAL
NUMBER
SAMPLES
TOTAL NUMBER
NUMBER SAMPLES
DETECT >10UG/L
DETECTED CONCENTRATIONS IN UO/L
MIN 10% MEDIAN MEAN SOX
MAX
TOXAPHENE 21
2.3,7.8-TETRACHLORODXBENZO-P-DIOXIN 21
ANTHRACENE/PHENANTHRENE 21
po
to
Ul
-------
Table VI-13 (3)
TUBING LEACHING ANALYSIS RESULTS
Mlcrograms/Liter
Component
Bis (2-ethylhexyl) Phthalate
Acid Extract
Base-Neutral Extract
Phenol
Acid Extract
Base-Neutral Extract
Original ISCO
915
2,070
19,650
N.D.
Tygon
N.D.
885
N.D.
N.D.
N.D. - Not Detected
226
-------
suggests contamination as a possible source, especially considering
the relatively low concentrations detected in the samples. More
importantly, all of these compounds may be found in the laboratory as
solvents, extraction agents or aerosol propellants. Thus, the
presence and/or use of the compounds in the laboratory may be
responsible for sample contamination. This type of contamination has
been previously addressed in another study (5). In a review of a set
of volatile organic blank analytical data from this study, inadvertent
contamination was shown to have occurred for each of the above
compounds (see Table VI-12).
Another contaminant is methylene chloride. This compound is separated
and quantified with other volatile compounds. The organics analytical
procedure involves the use of methylene chloride as a solvent (1),
(5). Thus, the relatively high concentrations and the detection of
this compound in 47 of .51 of the treated water samples (Table VI-2)
may be explained by its use in analytical procedures.
Priority Orqanics Detected in Treated Effluents at One
and Uniquely Related to Those Sources
or Two Mines
The 23 pollutants in Table VI-14 were detected at two or fewer
facilities and always at concentrations below 10 ug/1. One of these
compounds is a member of the phthalate family, two are volatile
organics, three are acid-extractable, twelve are base neutrals and
five are pesticides. These organics are excluded from regulation
since they are present at less than the nominal detection limit (10
ug/1) in two or less facilities within the category. This level was
established by the Agency to indicate where background signals in the
machines used for analysis begin to mask actual detection signals
(i.e., the signal to noise ratio reaches approximately 2:1).
Examination of Tables VI-11 and VI-12 shows that 14 of these compounds
were also detected in at least one field blank or control sample.
Priority Orqanics Detected but
Effectively Reduced
Present in Amounts too Small to be
The 14 compounds in Table VI-15 were detected in treated effluents in
this industry. The concentrations of these pollutants are so small
that they cannot be substantially reduced. In some cases this is
because no technologies are known to further reduce them beyond those
of BPT; in other cases, the pollutant reduction cannot be accurately
quantified because the analytical error at these low levels can be
larger than the value itself. These 14 p9llutants are thus excluded
from regulation. Therefore, all pollutants listed in Table VI-8 were
determined to be excluded from regulation at this time.
227
-------
Table VI-14
COMPOUNDS DETECTED IN TREATED WATER
AT ONE OR TWO MINES
BUT ALWAYS BELOW 10 ug/1
1. *1,2-dtchloroethane
2. hexachloroethane
3. *1,1,2,2-tetrachloroethane
4. *1,4-dichlorobenzene
5. 3,3'-dichlorobenzidine
6. *fluoranthene
7. bis(2-chloroethoxy) methane
8. *2,4-dinitrophenol
9. *4,6-dinitro-o-cresol
10. pentachlorophenol
11. di-n-octyl phthalate
12. benzo(a)anthracene
13. chrysene
14. ^anthracene
15. fluorene
I
16. *phenanthrene
17. *pyrene
18. *benzo(g,h,i)perylene
19. *aldrtn
20. 4,4!-DDT
21. *4,4f-DDD
22. *heptachlor
23. *heptachlor epoxlde
*This compound was detected in one or more field blanks and/or
controls.
228
-------
Table VI-15
PRIORITY ORGANICS DETECTED BUT PRESENT IN ^
AMOUNTS TOO SMALL TO BE EFFECTIVELY REDUCED
1. 1,1,1,-trtchloroethane
2. 1,1-dtchloroethylene
3. 1,2-trans-dtchloroethylene
4. ethyIbenzene
5. trtchlorofluoromethane
6. trichloroethylene
7. 1,2-d ichlorobenzene
8. naphthalene
9. dtbenzo (a,h) anthracene
10. tndeno (l,2,3-c,d) pyrene
11. BHC-Alpha
12. BHC-Beta
13. BHC-Gamma
14. BHC-Delta
229
-------
PRIORITY METALS EXCLUDED FROM REGULATION
All of the priority metals have been excluded from regulation.
Examination of Table VI-2 shows that five priority metals (antimony,
beryllium, cadmium, silver and thallium) and cyanide were detected in
effluents at more than two facilities. However, in all cases the
detected concentrations were at levels only slightly above the
detection limit for each respective species. This precludes any
meaningful determination of the effectiveness of treatment beyond BPT
technologies . Thus, antimony, beryl 1 ium, cadmium, cyanide, si Iver and
thallium can be excluded from BAT regulation since they cannot be
effectively reduced by known technologies.
The remaining eight (arsenic, chromium, copper, lead, mercury, nickel,
selenium, and zinc) were sometimes found at concentrations above the
detection limit in BPT-treated discharges as also shown in Table VI-2.
Paragraph 8 (a) ( iii ) provides for • exclusion of pollutants if these
pollutants are already effectively controlled by technologies upon
which other effluent limitations and guidelines are based. It is the
Agency's opinion that these eight metals are in generally low enough
•concentrations such that they are effectively controlled by BPT
technology and thus were not selected for national regulation under
BAT or NSPS. However, some of these metals appear in significant
amounts for individual mines. This results from a number of factors,
including: (1)
plant life that
geologies of
variations. In
imposition of
in question.
Differing trace element compositions in the precursor
was later transformed into coal, (2) Differing
strata surrounding the coal , and ( 3 ) Geographic
these cases, the permit authority should consider the
a limitation for the pollutant of concern for the mine
230
-------
SECTION VII
TREATMENT AND CONTROL TECHNOLOGY
INTRODUCTION
Previous sections have presented the characteristics of raw and
treated effluents in the coal mining industry, including the priority,
conventional, and nonconventional pollutants present in these
wastewaters. This section presents the existing treatment practices
of the coal mining industry (which should reflect, at a minimum, BPT
or equivalent technology), the candidate BAT treatment and control
technologies, and the associated levels of conventional, noncon-
ventional and toxic pollutant reduction. These control practices will
be evaluated only from a technical standpoint; cost considerations
will be presented in Section VIII.
APPROACH
A summary of in-use treatment technology (BPT or its equivalent) is
presented in this section for each subcategory. Next, the candidate
treatment technologies applicable to BPT-treated effluents in each
subcategory are reviewed. To determine the best available technology,
all potentially available treatment techniques were assessed according
to a number of initial criteria. These initial screening criteria
are:
1. The candidate technology must produce or be capable of
producing .an effluent of better quality than that required under BPT
guidelines.
2. The candidate technology must be in use or available to the
coal mining industry or transferable from other industrial or
municipal wastewater treatment applications.
3. Preliminary cost studies or cost data must be available;
this information should indicate baseline cost feasibility of the
candidate technology.
231
-------
Applying these initial criteria, the following candidate
were selected:
1 . Flocculant Addition,
2. Granular Media Filtration,
3. Carbon Adsorption,
4. Ion Exchange,
5. Reverse Osmosis,
6. Electrodialysis,
7. Ozonation, and
8. Sulfide Precipitation.
technologies
Next, the technical feasibility of
based on the following criteria:
these technologies was assessed
1. Process fundamentals,
2. Control effectiveness,
3. Non-water quality impacts,
4. Reliability,
5. Secondary waste streams, and
6. Preliminary cost/economic considerations.
The process fundamentals description is a short summary highlighting
the major operating parameters, equipment required, and the mechanism
for pollutant reduction or removal. The degree of this reduction is
presented as the control effectiveness for each technology, in tabular
form where sufficient data exist.
The non-water quality impacts resulting from applications of a
treatment technique are also discussed. These include sludge
generation, air pollution, and energy requirements.
Another factor considered—reliability—is principally a function of
the maturity of the technology; i.e., the degree to which the process
has been commercialized and initial problems resolved. The generation
of secondary waste streams, such as brines, are also important
parameters in determining the merit of each technology. Finally,
preliminary cost estimates were prepared to analyze the cost
effectiveness of each candidate technology.
After reviewing the above aspects of each technology and, in
particular, the preliminary cost and control effectiveness,
appropriate candidate treatment technologies in each subcategory were
selected.
The final screening step for the BATEA determination is application of
cost and economic criteria. Cost estimates are first prepared for
each technology not previously eliminated (these cost curves and
supporting material are presented in Section VIII). The cost curves
for each treatment system are then used as input to a computer
economic model. This computer model will predict the nationwide
economic impact by geographic region including total cost to the
industry; changes in selling price of the commodity, productivity,
232
-------
employment, and number of operating facilities; and import/ export
fluctuations. The results of this economic assessment are contained
in a separate document entitled, "Economic Impact Analysis for Final
Effluent Limitations and Standards for the Coal Mining Industries."
ACID MINE DRAINAGE
Current Treatment Technology
Raw wastewaters from mines exhibiting acid drainage are characterized
by low pH and high levels of dissolved iron and other metals. Raw
wastewaters from surface operations may carry substantial sediment
loads. The effluent limitations currently in force can be achieved by
application of the best practicable technology to these wastewaters.
For this subcategory, this level of technology includes chemical
precipitation/pH adjustment, aeration, and settling. A flow chart for
a typical BPT treatment system is illustrated in Figure Vll-l. Each
of the principal process units is discussed below. The raw water
holding pond, although not always installed, is employed by many
facilities as an equalization basin. Variation in flow and
pollutants, particularly pH, can be minimized by this pond. Overflow
from this facility is then commonly routed to a mixing tank where pH
adjustment is initiated.
pH Adjustment/Chemical Precipitation
This technology consists of the addition of an alkaline reagent to
acid mine drainage.to raise the pH to between six and nine. This pH
change also causes the solubilities of positively charged metal ions
to decrease and thus precipitate (settle as an insoluble compound) out
of solution. These metal ions are replaced in solution by more
acceptable calcium, magnesium and sodium ions. In general, three
types of reactions occur as a result of pH adjustment:
1. Neutralization, an ion exchange reaction that, in the case
of acid mine drainage, combines basic hydroxyl ions with acidic
hydronium ions;
2. Oxidation, which converts ferrous iron (iron in the +2
valence state) to ferric iron (iron in the +3 valence state); and
3. Precipitation, which results from
toxic and other metal ions.
solubility decreases of
233
-------
Raw
Waatewater
RAW Water
Holding Pond
Neutralization
Chemical
Feed
Mixer or
Aeration
Tank
Settling
Facility
treated
Discharge
LO
Figure VII-1
TYPICAL BPT TREATMENT CONFIGURATION FOR ACID MINE DRAINAGE
-------
The precipitates are, in most cases, metal hydroxides such as ferric
hydroxide (Fe(OH)3) which can be removed to a great extent by
settling. One of four reagents are commonly used to effect the above
reactions: hydrated lime (Ca(OH)2), calcined or quick lime (CaO),
caustic soda (NaOH), or soda ash (NazC03). Selection of one of these
alkaline compounds depends upon the acidity and ferrous/ferric iron
ratio of the raw mine water, and the availability and cost of the
reagents.
Hydrated Lime is the most commonly used reagent for pH adjustment. It
can be introduced as an aqueous slurry or as a dry powder. The slurry
can be prepared using the acid drainage, good quality water or treated
effluent. Dry lime or lime slurry is then, in most cases, added to
the acid mine drainage (AMD) in a mixing tank. Addition rates can be
controlled automatically or manually.
Calcined Lime (also termed "unslaked" or "quicklime") can also be used
as a reagent. A potential problem with the use of either calcined
lime or hydrated lime is the formation of gypsum (CaS04 2H20). This
compound forms when calcium ions from the lime reagent combine with
the typically high concentrations of sulfate ions present in AMD.
Gypsum will deposit on tanks, impellers, piping, control equipment
including pH probes, and other surfaces that contact the treated AMD.
High concentrations of gypsum, if allowed to accumulate, may result in
plugged lines and damaged equipment. This problem can be lessened
with proper chemical dosages, and correctly sized pipes and tanks.
The selection of the type of lime used is a matter of economics which
usually favor hydrated lime except in very large installations, where
use of unslaked lime becomes advantageous.
Caustic Soda or Sodium Hydroxide (NaOH) is used as the neutralization
reagent in a number of acid mines; most of these have drainage with
lesser acidity and iron concentrations, or low flows. Caustic soda is
a strong base, but it is also the most expensive per unit of alkaline
equivalence. As an aqueous solution, it mixes readily with AMD, and
reacts rapidly.
The use of an aqueous solution of caustic soda may eliminate the need
for expensive dispensing and mixing equipment. Savings in capital and
operating costs of such a system may more than offset the additional
expense of the reagent when only small amounts of alkali are needed.
Where calcium is the limiting reactant, caustic soda does not
precipitate calcium sulfate. This substantially decreases gypsum
deposits.
Caustic soda use also has several disadvantages. The reagent is
dangerous to handle, requiring the use of protective clothing.
Although it is available in 50 percent solution, this solution freezes
at 54° F and thus often requires heating to remove it from the
transport containers. Thus, a 20 percent solution is favored where
winter temperatures are below freezing. Nevertheless, even the 20
percent solution can continue to be difficult to pump at winter
temperatures. Also, because sodium hydroxide is such a strong base,
235
-------
closer flow-proportioned control is required to prevent overtreatment
(1).
Soda Ash or Sodium Carbonate (Na^CO,) is used as an alkaline reagent
by a small perdentage of mining operations. Although some degree of
caution must be exercised in the use of soda ash, the hazards
associated with its handling are less than with caustic soda. Similar
to lime, soda ash can be added dry (ground or in briquettes), or as a
slurry. The sludge formed with soda ash settles to greater densities
than sludge resulting from lime addition or caustic soda, but reagent
consumption is also relatively high.
Limestone has the lowest cost of any of the neutralizing reagents. It
is used minimally, however, because of several factors. Two
predominant disadvantages are that limestone has very low reactivity
at high pH and its use results in the formation of gypsum. This
substance coats the unreacted limestone and further reduces its
reactivity. The achievable pH ceiling for limestone treatment is
approximately 7.5, which is insufficient to precipitate many metals
(particularly manganese) (1).
The control effectiveness of neutralization and settling on metals is
dependent upon the reagent used, influent and effluent pH,
temperature, flow, and the presence of any side reactions including
metal chelation and mixed-metal hydroxide complexing. Complete mixing
of the alkaline agent and AMD is also important to control effluent pH
and metals removal. Table VII-1 presents metals removal data for lime
neutralization generated in a pilot plant treatment study at EPA's
Crown Field site (2). Referring again to Figure VII-1, oxidation of
iron from its ferrous to ferric state can be achieved using aeration.
Aeration
Often, aeration is accomplished by allowing the water to simply flow
or cascade down a staircaselike trough or sluiceway. This causes
turbulence that increases the oxygen transfer rate and therefore the
oxidation reaction rate. In other cases, the air or oxygen may be
supplied by one or more of the following types of aerators:
1. Diffused air systems,
2. Submerged turbine aerators
3. Surface aerators.
The oxidation system consists of a tank or pond fitted with one of the
above aeration systems. The presence of dissolved oxygen supplied by
the aerating technique oxidizes ferrous ions enhancing the formation
of essentially insoluble ferric hydroxide. The resulting sludge is
more easily settled. Temperature, pH, flow, dissolved oxygen content,
and initial concentration are all important design parameters (3).
The control performance of aeration will cause a nearly complete
conversion of influent ferrous ion to the oxidized or ferric state.
Further, many volatile organics present are often stripped or oxidized
236
-------
Table VII-1
TRACE ELEMENT REMOVAL BY LIME NEUTRALIZATION
- CROWN MINE PILOT PLANT STUDY -
Parameters
Ar s enic
Boron
Cadmium
Chromium
Copper
Mercury
Nickel
Phosphorous
Selenium
Zinc
Spiked
Influent
1 .90 mg/1
2.36
-90
.54
5.30
.50
.66
9.83
.94
5.65
pH-7
mg/1
.10
2.25
.18
.04
.30
.02
.34
3.81
.05
1 .01
pH-9
mg/1
.04
-
.08
.07
.11
.01
.08
2.30
.16
.11
pH-11
mg/1
.03
1 .90
.01
.05
.06.
.02
.06
3.56
.39
.11
Source: (2)
237
-------
by this process to nondetectable levels (4). Referring again to
Figure VI I-1, the neutralized wastewater, laden with insoluble
precipitates, is routed to a settling facility prior to final
discharge.
Settling
The process of sedimentation removes the suspended solids, which
includes the insoluble precipitates. Sedimentation can be
accomplished in a settling pond or clarifier (a settling tank). The
extent of solids removal depends upon surface area, retention time,
flow patterns, settling characteristics of influent suspended solids,
and other operating parameters of a particular installation.
Clarifiers are mechanical settling devices which can be used where
insufficient land exists for construction of a pond. Clarifiers
operate on essentially the same principles as a sedimentation pond.
The most significant advantage of a clarifier is that closer control
of operating parameters such as retention time and sludge removal can
be maintained, while problems such as runoff from precipitation and
short-circuiting can be avoided.
Center feed (the most common), rectangular, and peripheral feed basins
are a few of the several clarifier designs. Center feed Clarifiers
have four distinct sections: the inlet zone, the quiescent settling
zone, the outlet zone, and the sludge zone. The inlet zone allows a
smooth transition from the high velocities of the inlet pipe to the
low uniform velocity needed in the settling zone. Careful control of
the velocity change is necessary to avoid turbulence, short-
circuiting, and carryover. The quiescent settling zone must be large
enough to reduce the net upward water velocity to below the settling
rate of the solids. The outlet zone provides a transition from the
low-velocity settling zone to the relatively high overflow velocities.
The sludge zone must effectively settle, compact, and collect the
solids and remove this sludge without disturbing the settling zone
above. The bottom of the circular clarifier is usually sloped five to
eight degrees to the center of the unit where sludge is collected in a
hopper for removal. Mechanically driven sludge rakes rotate
continuously and scrape the sludge down the sloped bottom to the
sludge hopper (see Figure VII-2).
The rectangular basin or clarifier is similar to a section of a center
feed clarifier with the inlet at one end and the outlet at the other.
Usually a flight system removes sludge in the rectangular basin. The
flights travel along the basin bottom to convey the sludge to a
discharge hopper. To avoid turbulence, which would hinder settling,
the flight system moves slowly. This type of clarifier has the
advantage that common walls can be used between multiple units to
reduce construction costs (see Figure VII-3).
The peripheral feed or rim feed Clarifiers shown in Figure VII-4, are
designed to utilize the entire volume of the circular clarifier basin
for sedimentation. In both types of Clarifiers, water enters the
lower section at the periphery at very low velocities to provide
238
-------
*^
>)
TV
' \ ^
10
^
'T
/
c^l^NJxJ'^J-^
EFFLUENT
Source: (5)
Figure
CIRCULAR CENTER FEED CLARIFIER WITH
A SCRAPER SLUDGE REMOVAL SYSTEM
239
-------
DRIVE SPROCKET
ADJUSTABLE WEIRS
INFLUENT
FLIGHT-
SLUDGE HOPPER
Source: (5)
Figure VII-3
RECTANGU7-AR SEDIMENTATION CLARIFIER
WITH CHAIN AND FLIGHT COLLECTOR
210
-------
INFLUENT
EFFLUENT
SLUDGE
(a) CIRCULAR RIM-FEED, CENTER. TAKE-OFF CLARIFIER WITH A
HYDRAULIC SUCTION SLUDGE REMOVAL SYSTEM
INFLUENT
i » EFFLUENT
SLUDGE
(b) CIRCULAR RIM-FEED, RIM TAKE-OFF CLARIFIER
Figure VII-4
PERIPHERAL FEED CLARIFIERS
Source: (5)
241
-------
immediate settling of large particles. In a peripheral take-off
configuration, the flow then accelerates toward the center and
subsequently drops as the flow reverses and redirects to a peripheral
overflow weir. In the center take-off system, effluent is discharged
through weirs located centrally. Peripheral feed clarifiers are
sensitive to temperature changes and load fluctuations. Sludge
recirculation is difficult with these types of clarifiers.
Clarification of acid mine drainage produces two secondary streams:
the clear overflow or decant and the sludge underflow. The overflow
is often discharged in current treatment systems. The dilute solids
underflow stream, usually of only 5 to 10 percent solids content is
often dewatered further before final disposal. Evaporation,
centrifugation, and vacuum filtration are several techniques that may
be used to further dewater sludges from clarifiers prior to ultimate
disposal.
Installation of clarifiers to provide sedimentation is principally in
hilly or mountainous areas where suitable land for a sedimentation
pond is difficult to obtain. Ponds can also be installed to provide
sedimentation capability. The settling pond can be created by
excavating a depression or damming a natural runoff water course. For
example, an abandoned strip mine pit at surface facilities may be
used.
The purpose of a sediment basin is to remove sediment from runoff and
thus protect drainageways, properties, and rights-of-way below the
sediment basin from sedimentation (6). Construction of these basins
is regulated primarily by the Office of Surface Mining Reclamation and
Enforcement (OSM) in the Department of Interior. A settling pond
operates on the principle that as the sediment laden water passes
through the pond, the particles will settle to the bottom and be
trapped. Some of the factors affecting the settling velocity of a
particle include water viscosity (which is a sensitive function of
temperature), and the density, size, and shape of the particle. For
instance, as the temperature increases, the water viscosity decreases,
and thus a particle will have a greater settling velocity in warm
water (7, 8, 9, 10, 11, 12).
The use of sedimentation facilities has been commonplace in the
industry for some time. Some mines, particularly in mountainous
areas, may opt for several small ponds. These ponds are usually
constructed in series, with the decant of one flowing into another.
Other acid mine drainage treatment plants use two ponds in a parallel
configuration. When the sludge content in one pond has reached
capacity, flow is diverted to the second pond and the sludge in the
first is either removed by dredging or allowed to undergo drying and
compaction which greatly reduces the sludge volume. When the second
pond is full of sludge, flow is returned to the first and the cycle is
repeated. Application of the above treatment technologies to acid
mine drainage will result in achievement of the BPT limitations dis-
cussed in Reference 13.
242
-------
Candidate Treatment Technologies
Source control options are discussed under the best management
practices subsection (Section X). The candidate end-of-pipe
technologies examined for treatment of acid mine drainage were
previously listed and include:
1. Flocculant Addition,
2. Granular Media Filtration,
3. Activated Carbon,
4. Ion Exchange,
5. Reverse Osmosis,
6. Electrodialysis,
7. Ozonation, and
8. Sulfide Precipitation.
The first two technologies were selected for further study. The
remaining technologies and the reasons for their rejection are
discussed below.
Activated Carbon
Activated carbon technology is predicated upon the considerable
sorptive properties of granular or powdered carbon. The activated
carbon process is often associated with organics removal, although
some reduction of heavy metals can also be accomplished (14, 15).
A typical system is depicted in Figure VI1-5. Contaminated water is
introduced across a fixed or moving bed of granular or powdered
activated carbon. Residence time in the bed is the major control
parameter for pollutant removal. When a bed becomes fully loaded or
exhausted, the adsorbent must be regenerated or disposed of.
Regeneration (for granulated carbon only) is usually effected by
heating to volatilize any organics and/or heavy metals. The
adsorptive capacity of carbon depends on the pore size, typical size
of the sorbed molecules, pH of the solution, temperature, and the
initial pollutant concentration. Adsorption capacity generally
increases as pH decreases and, normally, adsorption efficiency
increases as the concentration increases (14).
A large amount of data is available on organic pollutant removal by
this technology, whereas less data exist in the literature for metals
removal. For cases where metals are present in the untreated
wastewater at the parts per million level, significant reductions of
Sb, As, hexavalent Cr, Sn, Ag, Hg, Pb, and Ni are documented in the
literature (16). Cu, Cd, and Zn removals vary widely, while
concentrations of Ba, Se, Mo, Mn, and W are not significantly reduced.
BPT-treated effluents in the coal mining industry contain toxic metals
at the parts per billion level, and data quantifying reductions beyond
these levels are not available.
Table VII-2 presents an estimate of general effluent water quality
parameters. Suspended solids will quickly foul an activated carbon
-------
Table VII-2
ESTIMATED EFFLUENT CONTAMINANT LEVELS - ACTIVATED CARBON
pH
Tocal iron
Dissolved iron
Manganses, total
Total suspended
solids
Acid Mines
Alkaline Mines
30-Day
Average*
6-9.00
2.00
0.30
2.00
Daily
Maximum*
6-9.00
3.00
0.60
4.00
30- Day
Average*
6-9.00
2.00
—
__
Daily
Maximum*
6-9.00
3.00
—
_..
15.00
30.00
15.00
30.00
*All values in mg/1 except pH,
Source: (15)
244
-------
MonnntTQ +
UMOGtMINQ
uruxn
went
CA«SOH
KD
K7*
CAMON
uo
OkMOM
ICO
mMm
nwoucr
UATtt
me.
win
Figure VII-5
ACTIVATED CARBON SYSTEM
245
-------
column, hence, filtration, which will itself reduce metals
concentrations, is a required pretreatment step in an activated carbon
system. Activated carbon columns would be very difficult to operate
at remote sites. Some provision for regeneration (typically including
multiple hearth , furnaces) is required to make such a system cost
effective. Beyond this, the substantial capital cost for equipment
and the high operating costs for carbon purchase and regeneration
cannot be justified for any potential additional reductions of metals
beyond BPT. Based on these factors, activated carbon is not selected
as a BAT option for further analysis.
Ion Exchange. The property of reversible interchange of ions between
solids and liquids is the fundamental principle of ion exchange. Ion-
rich water is introduced into an exchanger or column in which a solid
resin bed resides. This resin, most commonly a type of
styrenedivinylbenzene copolymer, has the ability to sorb (capture) and
contain ions before release during regeneration. Of the many ion
exchange configurations available, a typical arrangement/ shown in
Figure VII-6, is a cation column using an acidic solution for
regeneration, followed by an anion column using an alkaline
regeneration solution to elute (de-absorb with a solvent) sorbed
anions.
Individual ion exchange systems do not generally exhibit equal
affinity or capacity for each ionic species, and hence may not be
suited for broad-spectrum removal schemes in wastewater treatment.
Their behavior and performance are usually dependent upon pH,
temperature, exchange resins, and concentration. The highest removal
efficiencies are generally observed for polyvalent ions. In waste-
water treatment, some pretreatment or preconditioning of wastes to
adjust suspended solid concentrations and other parameters is likely
to be necessary.
High concentrations of ions other than those to be recovered may
interfere with practical removal. Calcium ions, for example, are
generally* collected along with the divalent heavy metal cations of
copper, zinc, lead, etc. High calcium ion concentrations, therefore,
may make ion exchange removal of divalent heavy metal ions impractical
by causing rapid loading of resins.
Ion exchange can effectively produce low levels of metals. However,
although ion exchange is a commercially available technology, it
becomes uneconomical on streams high in dissolved solids due to resin
replacement costs. Even at less than 500 ppm dissolved solids, ion
exchange is expensive and requires relatively sophisticated equipment
and control (2, 3, 17). Table VII-3 presents data from an EPA mine
drainage study snowing metals removal (2).
A number of operational disadvantages are associated with this
technology. For instance, secondary pollution stream is generated and
must be treated. Iron fouling is a common problem in the cation
sorption column, necessitating an acidification step prior to the
first resin bed. Also, 'a final effluent neutralization step is
246
-------
Table VII-3
ION EXCHANGE EFFLUENT WATER QUALITY (in mg/1)
Faramecer
Spiked Feed
(mean)
Cation Effluent
(mean)
Anion Effluenc
(mean)
pH
Ars enic
Cadmium
Chromium
Copper
Iron, cotal
M angaries e
Mercury
Nickel
Selenium
Zinc
4.8
2.47
0.95
0.63
7.27
160
3.9
0.72
0.86
1.34
7.44
1.9
1.68
0.04
0.05
0.11
2.1
0.09
0.07
0.02
T.19
0.14
9.9
0.52
0.001
0.01
0.03
0.05
0.05
0.001
0.02
0.09
0.03
Source: Adapted from (2)
247
-------
Sulfuric acid
Trace element injection i
y Acid mine drainage f
fU
oo
1 *
To Waste
[Backwash]
,
Backwash
1 -1
CATION
EXCHANGER
•— — * — •
^rn
11
Sodium
hydroxide
T
o,..
^i^ivi
r
ANION
EXCHANGE!
-Ml
1
To waste
(Backwash)
:
h~
To waste
(Regeneration and rinses)
Product
To waste
(Regeneration and rinses)
'To
filiation, and
chlorination)
Source: (2)
Figure VII-6
CONCEPUTAL DESIGN OF AN ION EXCHANGE SYSTEM
-------
required if the pH remains too high downstream of the anion exchanger.
Acidic and basic regenerant solutions are required. Operation of this
relatively sophisticated system at remote sites, especially in the
mountainous terrain of Appalachia, would be very difficult. For these
reasons, this technology was not selected as a BAT option for further
analysis.
Reverse Osmosis
Reverse osmosis is the process of concentrating ions on one side of a
semipermeable membrane by the application of external pressure. This
pressure must be sufficient to overcome the osmotic gradient which
acts in the opposite direction—hence, the name reverse osmosis. This
is schematically illustrated in Figure VII-7. Water is separated from
the ions by forcing it across a membrane, which is impervious to ion
transfer. Treated water is then decanted and discharged, while the
brine requires further treatment prior to disposal.
Since 1966, the EPA has been sponsoring and conducting research to
determine the potential of using reverse osmosis to treat acid mine
drainage. This EPA work includes pilot plant studies that have been
undertaken at the Crown Mine Drainage Control Field Site (2). Results
from these and other research efforts (19) have shown that in treating
mine drainage, reverse osmosis can remove nearly all dissolved solids
and up to 95 percent of the aluminum, iron, calcium, magnesium,
manganese, sodium, and sulfate ions.
The basic reverse osmosis system consists of a number of potential
pretreatment steps (e.g./ filtration, pH adjustment); a high pressure
pump (400 to 800 psig); a reverse osmosis membrane package; and post-
treatment, if necessary (Figure VII-8). One of the problems
encountered in applying reverse osmosis to acid mine drainage
treatment is fouling of the membranes. Fouling of a semipermeable
membrane is defined as any reduction in permeability or efficiency due
to blinding of the membrane by suspended solids, age of the membrane,
or deterioration of the membrane. Membrane fouling progressively
lowers water recovery (until recovery rates are no longer practical).
The two major causes of fouling in the treatment of acid mine drainage
are chemical and bacterial. Two solutions for the bacterial fouling
are to disinfect the water before it enters the reverse osmosis unit
or to adjust the mine water to below pH 2.5 which greatly retards
bacterial growth. The two chief chemical compounds that can foul the
membrane are the sulfates of iron and calcium. Under normal
conditions ferric iron fouling can be controlled either by the
addition of an acid to maintain a pH below 3.0 or by the addition of
reducing chemicals such as sodium sulfite, to reduce ferric iron to
ferrous. The stream can also be filtered prior to polishing in a
reverse osmosis unit to remove suspended material such as ferric or
calcium sulfate.
Table VII-4 presents effluent pollutant reductions of acid mine
drainage achievable by reverse osmosis. Although reverse osmosis is
249
-------
Table VII-4
EFFLUENT WATER QUALITY ACHIEVED BY REVERSE OSMOSIS
(in mg/1)
Parameter
pH
Arsenic
Cadmium
Chromium
Copper
Iron, cotal
Manganese
Mercury
Nickel
Selenium
Zinc
Spiked Feed
(mean)
2.2
2-29
0.83
0.54
6.18
170
110
0.23
0.74
1.17
6,25
Produce
(mean)
2.0
0.01
0.006
0.01
0.01
0.30
0.20
0.06
0.01
0.11
0.06
Brine
(mean)
3.6
3.58
1.22
0.82
9.12
270
130
0.17
1.10
1.83
9.63
Source: Adapted from (2)
250
-------
Pressure
S emipermeab 1 e
membrane
Concentrated
Solution
Dilute
Solution
Figure VII-7
TRANSFER AGAINST OSMOTIC GRADIENT IN
REVERSE OSMOSIS SYSTEM
Source: Adapted from (18)
251
-------
Influent
Monitor
ro
m
ro
Ft
pH
Pump
Iter (400-800 psi)
/ c
t Vlx
PresHtirp Vessel
^^^^temb ran e
I
I
1 .
1 *.
i »
1 Concentrated
Adjustment Brine
Treated
Figure VII-8
SCHEMATIC OF REVERSE OSMOSIS SYSTEM
Source: Adapted from (18)
-------
slightly more effective than lime neutralization and settling for
metals removals, this technology is very expensive and appropriate
only for low volume, high dissolved solids feed streams. Further,
concentrated brine requiring further treatment is generated from the
separation chambers.
Based on the above considerations, reverse osmosis was not selected as
a BAT option for further analysis.
Electrodialysis
Electrodialysis can be used for the control of dissolved inorganics in
coal mine wastewaters. The technology is based upon differentially
permeable membranes operating in an electric field. Contaminated
water is introduced into a cell or "stack" of alternating anion- and
cation-permeable membranes. With an electric field applied across the
stack providing the driving force, ions are forced into alternating
cells, while deionized water is withdrawn from the remaining cells
(Figure VII-9). A small bench-scale electrodialysis unit was tested
by the Federal Water Pollution Control Administration at its Mine
Drainage Treatment Laboratory, Norton, West Virginia, in cooperation
with the Office of Saline Water (17). When used on drainage without
pretreatment, the cathode cell quickly became fouled with iron. In
those cases where the mine drainage was pretreated by lime
neutralization for iron removal, the unit operated satisfactorily.
Electrodialysis is a costly technology suitable chiefly for low flow,
high dissolved solids streams, with pretreatment frequently necessary.
Energy requirements to maintain the electrical field add significantly
to the operating costs. The process also produces a secondary stream
of concentrated brine that requires further treatment. Based on the
above considerations, electrodialysis was not selected as a BAT option
for further analysis.
Ozonation
Ozone, 03, is an unstable molecule that is a powerful oxidant. Its
primary application to the coal mining industry is oxidation of metal
compounds that render them less soluble and thus increases the
settling rates. It has also been shown to be effective in the
oxidation of soluble manganese to an insoluble state which can be
removed prior to discharge into streams. Because of the instability
of ozone, facilities for on-site generation are required. The gas is
generated by passing air across a high voltage field (5 to 30
kilovolts). The gas is then injected into a stream where oxidation
occurs (3). Preliminary cost estimates show ozonation to be a
relatively costly technology. Further, no data are available to
quantify toxic metals removal by ozonation systems on coal mine
drainage.
Finally, suspended solids in substantial concentrations impede
ozonation performance (16). Because of these factors, ozonation was
not selected as a BAT option.
253
-------
^ ,. FEED TO SAUNE FEED
CONCENTRATES CELLS WATER
^G*5
^
{'CATHODE
>—
8
s
1
<
-D
^ft-
1
CATH
] c
'
Sk
Jf*
1
1
A ! C
»
Sk
2
e»
ODE
WASTED
s^ J
A
ce ~
i
8
*
\
h
«
*•
a
1
1
1
1
1
i
t
A ! C
Ek
[
1
i
v. >
1*
% 5 **
ut
u
CLpOR
i
i
A ! C
-®
6k
i
3
o
1
1
1
|
- T~
1
t
TJ
I
X *
**
^ a^'
£
UJ
I
I
A F fDi
A :
&
^
i
\
1
1
t
1
1
^^
a
K
&
ANODE
WASTE
r
CONCENTRATE PRODUCT
ELECTRODIALYSIS STACK
Figure VII-9
CONFIGURATION OF ELECTRODIALYSIS CELLS
Source: (17)
-------
Sulfide Precipitation
Sulfide precipitation is analogous to lime precipitation in that
heavy metal cations (positively charged) are combined with anions
(negatively charged) to form an insoluble compound that settles out of
solution. In this process, sulfide is the anion used. Sulfide
precipitates vary in solubility which will determine the removal
efficiency. Heavy metal sulfides are in general very insoluble and
have excellent settling properties. Table VII-5 gives the theoretical
solubilities of hydroxides and sulfides of various metals in pure
water. In addition to having lower solubilities than hydroxides in
the alkaline pH ranges, sulfides also tend to have low solubilities in
the pH 7 range or below (14). Several steps enter into the process of
sulfide precipitation (16): 1. Preparation of sodium sulfide.
Although this product is often in oversupply from byproduct sources,
it can also be made by reduction of sodium sulfate. The process
involves an energy loss in the partial oxidation of carbon (such as
that contained in coal) as follows:
Na2S04
4C —
Na2S + 4CO (gas)
2. Precipitation of the pollutant metal (M) in the waste stream by an
excess of sodium sulfide:
Na2S + MS04 -> MS (precipitate) + Na2S04
3. Physical separation of the metal sulfide in thickeners or
clarifiers, with reducing conditions maintained by excess sulfide ion.
4. Oxidation of excess sulfide by aeration:
Na2S + 202 > Na2S04
In practice, sulfide precipitation can be best applied when the pH is
sufficiently high (greater than eight) to assure generation of
sulfide, rather than bisulfide ion or hydrogen sulfide gas. A process
utilizing ferrous sulfide as the principal source of sulfide ion has
been developed and appears to overcome the problem from the FeS only
when other heavy metals with lower equilibrium constants for their
sulfide form are present in solution. If the pH can be maintained at
8.5 to 9, the liberated iron will form a hydroxide and precipitate out
as well.
Although very effective in pollutant removal, sludge produced from
sulfide precipitation is easily degraded to soluble salts that will
leach toxic materials. Sludge produced from lime addition is much
more stable (15). The most probable application of sulfide technology
is as a polishing unit downstream of a lime precipitation unit.
However, to be implemented in the coal industry, the problem of
potential leaching of soluble salts from sulfide precipitation sludge
must be mitigated or circumvented. Also, the cost of operation with
sulfides is much higher than lime neutralization, with only slight
improvement in effluent quality. These factors preclude sulfide
255
-------
Table VII-5
THEORETICAL SOLUBILITIES OF HYDROXIDES AND
SULPIDES OF HEAVY METALS IN PURE WATER
Metal
Cadmium (Cd++)
Chromium (Cr+++)
Cobalt (Co++)
Copper (Cu++)
Iron (Fe++)
Lead (Pb++)
Manganese (Mn++)
Mercury (Hg++)
Nickel (N1++)
Silver (Ag+)
Tin (Sn++)
Zinc (Zn++)
Solubility of Metal Ion (mg/1)
As Hydroxide As Sulflde
2.3 x 10-5
8.4 x 10-4
2,2 x 10-1
2.2 x lO-2
8.9 x 10-1
2.1
1.2
3.9 x 10-4
6.9 x 10-3
13-3
1.1 x 10-4
1.1
6.7 x 10-10
No precipitate
1.0 x 10-8
5.8 x 10-18
3.4 x 10-5
3.8 x 10-9
2.1 x 10-3
9.0 x 10-20
6.9 x 10-8
7.4 x 10-12
3.8 x 10-8
2.3 x 10-7
Sources: (20, 21, 22)
256
-------
precipitation from being considered as a candidate best available
technology.
The two technologies recommended for further evaluation and economic
impact assessments are flocculant addition and granular media
filtration. These are discussed in the following paragraphs.
Flocculant Addition
Flocculant addition is a term often used interchangeably with chemical
coagulation. The process involves the aggregation and settling of
suspended particles by the addition of a coagulant aid. Technically,
coagulation involves the reduction of electrostatic surface charges
and the initial formation of aggregated material. Coagulation is
essentially instantaneous in that the only time required is that time
necessary for dispersing the chemicals in solution. Flocculation is
the time dependent physical process of the aggregation of wastewater
solids into particles large enough to be separated by sedimentation,
flotation, or filtration.
For particles in the colloidal and fine supracolloidal size ranges
(less than one to two micrometers), natural stabilizing forces
(electrostatic repulsion, physical repulsion by absorbed surface water
layers) predominate over the natural aggregating forces (van der
Waals) and the natural mechanism which tends to cause particle contact
(Brownian motion). The function of chemical coagulation of wastewater
may be the removal of suspended solids by destabilization of colloids
to increase settling velocity, or the removal of soluble metals by
chemical precipitation or adsorption on a chemical floe (16).
There are three different types of flocculants: inorganic
electrolytes, natural organic polymers and synthetic organic
Polyelectrolytes. Inorganic electrolytes are salts or multivalent
ions such as alum (aluminum sulfate) that act by neutralizing the
charged double layer of colloidal particles. Natural organic polymers
are derived from starch, vegetable materials, or monogalactose, and
act to agglomerate colloidal particles through hydrogen bonding and
electrostatic forces. Synthetic polyelectrolytes are polymers that
incorporate ionic or other functional groups along the carbon chain in
the molecule. The functional groups can be either anionic (attract
positively charged species), neutral or cationic (attract negatively
charged species). Polyelectrolytes function by electrostatic bonding
and the formation of physical bridges between particles, thereby
causing them to agglomerate.
The colloidal particles in AMD sludge usually carry a negative charge.
Consequently a cationic flocculant must be used. Synthetic
polyelectrolytes are most frequently employed since they function best
in the high ionic strength solutions encountered in AMD.
Chemical coagulants are most commonly added upstream of sedimentation
ponds, clarifiers,. or filter units to increase the efficiency of
solids separation. The settling solids are more effective in
257
-------
/ adsorbing fine metal hydroxide precipitates. As these fine
are agglomerated and settled, equilibrium relationships
particles
will cause
insoluble
of certain
of large
additional dissolved metals to react and form additional
precipitates. The major disadvantage of the addition
coagulants to a raw wastewater stream is the production
quantities of sludge, which must subsequantly be disposed of.
Therefore, raw wastewaters may be treated by removal of easily settled
particles in a primary sedimentation pond. Coagulants are then added
to this effluent prior to secondary settling or filtration. In most
cases, chemical coagulation can be used with minor modifications and
additions to existing treatment systems. In mines with acid drainage,
this would be accomplished by polymer addition downstream of
neutralization and primary settling facilities.
To assist in determination of performance characteristics of this
technology at acid mines, a treatability study (23), was performed at
four coal mine sites exhibiting acid mine drainage. Raw acid mine
drainage samples (from the Crown, Norton, Hollywood, and Will Scarlet
sites) were treated via lime neutralization and precipitation,
f locculation, aeration and settling.
Chemical dosage rates and polymer selection were determined by jar
tests. Settling tests were then conducted in an eight-inch inner
diameter by eight foot high settling tube to establish performance
data. Spiking solutions containing priority metals were added to the
acid mine drainage to raise influent concentrations to levels
significant for measurement of test parameters. The chief objective
of the study was to establish priority metals and suspended solids
concentrations achievable by application of chemically aided
precipitation.
Settling tests performed with dosages of each chemical are summarized
in Table VII-6. Influent suspended solids concentrations are recorded
after addition of lime. As can be seen from Table VII-6, flocculant
addition consistently reduces effluent suspended solids to 20 mg/1 or
less. In fact, reductions below 10 mg/1 are frequent. Also, in other
industries, such as ore mining, reductions via flocculant addition of
total suspended solids to 15 mg/1 and less are typical.
The removal of priority metals was also evaluated for each of the 28
settling tests. Because spiking solutions were not readily obtainable
and background levels were less than the detection limits, no data
could be recorded for removals of arsenic, antimony, selenium, and
thallium. Referring to Table VII-7, consistently high removals were
achieved for beryllium, cadmium, chromium, copper, iron, mercury,
nickel, lead, and zinc. Less consistent reduction is achieved for
silver and manganese. These effluent levels are summarized in Table
VII-7.
A number of points concerning this table should be made. First, raw
mine drainage from these facilities does not exhibit high (>1.0
mg/1) concentrations of priority metals. Copper, lead, zinc, chromium
(hexavalent ) , mercury, nickel, cadmium, and manganese were thus added
258
-------
Table VII-6
SUMMARY OF SETTLING TESTS PERFORMED
WITH FLOCCULANT ADDITION
HIM
Crown
Morton*1
Hollywood*
PO
Ul
Hill Scarlet4
Test Ho.
C-l
C-2
C-3
C-4
C-5
C-6
H-l
H-2
H-3
H-4
H-5
N-6
H-l
H-2
H-3
H-4
H-5
H-6
H-7
H-8
H-9
H-10
S-I
S-2
S-3
S-4
S-5
S-6
Splksd
X
X
X
X
X
X
X
X
X
X
X
X
X
LlM <•*/!>
0
0
350
350
420
425
0
300
290
275
270
300
250
265
225
250
260
34O
275
360
300
445
10.400
17,325
7.660
20,000
15.220
11,870
Chestlcsls Added Initial Ptnal
Sodlua Suit Ida
-------
Table VII-7
SUMMARY OF TEST RESULTS FOR METALS REMOVAL (me/1)
BY BPT AND FLOCCULANT ADDITION
TO
CT\
O
Effluent
Nine Teat No.
Crown C-l (Raw)
Influent
Effluent
C-2 (spiked)
Influent
Effluent
C-3
Influent
Effluent
C-4 (spiked)
Influent
Effluent
C-5
Influent
Effluent
C-6 (spiked)
Influent
Effluent
Pll
4.9
5.0
4.9
4.7
7.0
7.2
7.0
7.0
7.7
7.7
7.8
7.8
TOS
3140
3360
3510
3440
3520
3490
3500
3370
3460
3410
3610
3400
Afi
DL
PL
.on
.007
DL
.019
.006
.016
.015
.015
.012
.008
As
DL
Dl,
PL
DL
DL
DL
DL
DL
DL
DL
DL
DL
Be
.008
.007
.007
.007
.008
DL
.007
DL
.007
DL
.006
DL
Cd
.038
.033
.150
.141
.040
.021
.130
.060
.038
.020
.142
.024
Cr
.047
.042
.086
-085
.038
.041
.OB9
-047
.058
.047
.090
.046
Cu
.019
.019
.111
.105
.006
.008
.088
.009
.016
DL
.094
.010
Fe
155
161
155
142
154
13
122
23
138
1.5
138
.82
"&
DL
DL
.80
.126
DL
DL
.003
.032
DL
DL
.170
.024
Mn
4.6
4.7
4.7
4.3
4.5
2.9
3,9
3.4
4.2
1-9
4.2
1.9
Ni
.26
.25
.31
.29
.30
.12
.31
.18
.28
-13
.32
.11
Pb
.002
.008
.280
.294
DL
DL
.340
DL
.002
DL
.200
DL
Sb
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
Se
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
Tl
DL
DL
DL
DL
DL
DL -
DL
DL
DL
DL
DL
DL
Zn
.400
.400
.470
.430
.390
.008
.390
.031
.378
.442
.410
DL
Detection Limits
.005 .005 .001 .001 -002
.005
.005 -001 .005 .005 -001 .005 .010 -002 .002
-------
Table VII-7 (Continued)
SUMMARY OF TEST RESULTS FOR METALS REMOVAL (mg/1)
BY BFT AND FLOCCULANT ADDITION
ON
Effluent
Mine Test Mo. pH
Norton N-l (Raw)
Influent
Effluent
N-2
Influent
Effluent
N-3 (spiked)
Influent
Effluent
N-4 (spiked)
Influent
Effluent
N-5
Influent
Effluent
N-6 (spiked)
Influent
Effluent
2.8
2,8
9.4
9.4
6.3
6.3
8.3
8.1
8.2
8.0
8.1
8.0
TDS
997
951
979
993
1100
1100
983
1000
1020
989
1140
1090
.013
DL
.005
DL
.023
DL
.013
DL
.009
.006
.015
.010
As
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
Be
Cd
Cr
Cu Fe Hg
.007 .237 -227 .411
.007 .006 .017 .876
.008 .007 .020 .142
DL .056 -062 .066
.009 2.50 2.54 3.20
DL .686 .077 .084
.009 .015 .023 .146
DL DL .008 DL
.011 .009 .023 .242
DL .020 .013 .005
.009 2.93 2-99 3.74
DL .210 .091 .093
Mn
Nl Pb Sb Se
Tl
Zn
40.3 .072 2.43 4.86 .004 DL DL DL .888
41.8 .080 2.19 .275 DL DL DL DL .610
37.8
.756
40.4
1.03
36.4
1.38
54.4
1 .94
37.4
.821
DL
DL
.790
.410
.655
DL
.615
.110
.750
.625
2.31
.006
4.73
3.47
2.33
.500
2.82
.439
5.23
2.12
.294
.058
2.78
.960
.317
.066
.358
.080
3.18
.312
DL
DL
7.0
.029
.002
DL
DL
DL
8.5
.037
DL
DL
DL
DL
DL
DL
DL
DL
SL
DL
DL
DL
DL
DL
DL
DL
PL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
.617
.065
3.43
.167
.641
.012
.780
.025
3.99
.095
Detection Limits
.005 .005 -001 .005 -005 .005 .005 .001 .005 .005 .001 .005 .010 .002 .002
-------
Table VII-7 (Continued)
SUMMARY OF TEST RESULTS FOR METALS REMOVAL (me/1)
BY BPT AND FLOCCULANT ADDITION
ro
Effluent
Mine
Holly-
wood
Test No.
Raw
H-l
Influent
Effluent
H-2 (aplked)
Influent
Effluent
11-3
Influent
Effluent
11-4 (spiked)
Influent
Effluent
H-5
Influent
Effluent
11-6 (aplked)
Influent
Effluent
H-7
Influent
Effluent
II-B (spiked)
Influent
Effluent
11-9
Influent
Effluent
11-10 (spiked)
Influent
Effluent
PH
3.5
7.0
7.4
8.7
8.8
A. 4
8.5
7.5
7.6
9.5
9.5
9.6
9.6
9.2
9.2
9.6
9.7
9.7
9.4
10.2
10.0
TDS
775
861
839
719
733
637
636
829
891
799
822
1060
1000
A46
864
980
1000
879
831
1090
103O
Afi
.022
-009
.008
.011
.020
.008
DL
.010
.013
.Oil
.014
.024
DL
DL
DL
.006
DL
.017
.013
.022
.014
As
PL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
PL
DL
DL
DL
DL
DL
DL
De
.006
.008
DL
.006
DL
.004
DL
.008
DL
.008
DL
.009
DL
.009
DL
.009
UL
.004
DL
.005
DL
Cd
.020
.022
.006
3.01
.084
.014
DL
3.16
.220
.018
DL
3.15
.029
.019
DL
3.11
.024
.015
DL
2.93
.024
Cr
.040
.057
.017
2.66
.089
.033
.019
2.82
.118
.039
.021
2.81
.048
.043
.017
2.83
.047
.042
.019
2.72
.043
Cu
.019
.033
.017
2.79
.082
.023
DL
2.93
.105
.016
.006
2.90
.023
.015
DL
2.90
.022
.015
DL
2.79
.026
Fe
46.9
58. Q
1.13
33.3
-803
38.2
1.29
39.4
1.29
57.2
.785
47-0
.351
50.1
.534
51.1
.395
48-9
.477
45-5
.306
«fi
DL
DL
DL
1.20
.234
DL
DL
DL
.005
DL
DL
1.07
.151
DL
OL
.715
DL
DL
DL
2.82
.819
Hn
1.33
1.60
.161
34
.179
1.15
.120
3.59
1.35
1.59
.040
3.84
.060
1.42
.026
3.95
.041
1.40
.027
3-74
.032
Nl
.376
.481
.072
3.38
.14
.305
.074
3.60
.414
.437
.079
3.65
.118
.409
.075
3.67
.109
.401
.085
3-56
.104
Pb Sb
.010 DL
DL DL
DL DL
4.8 DL
.040 DL
DL DL
DL DL
4.70 DL
.046 DL
DL DL
DL PL
4.2 PL
.015 DL
DL PL
DL PL
4.50 DL
.011 DL
DL DL
DL DL
5-5 DL
.008 DL
Se
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
PL
DL
DL
DL
DL
DL
DL
DL
PL
DL
Tl
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
DL
PL
DL
DL
DL
DL
DL
DL
DL
DL
DL
Zn
.521
.668
.027
2.78
.076
.430
.018
2.99
.106
.625
.020
3.04
.017
.565
.017
3.07
.023
.558
.008
2.92
.017
Detection Limits
.005 -001 .001 .002 .005 -001 .005 .005 .005 .005 .001 .005 .010 .002 .002
-------
Table VII-7 (Continued)
SUMMARY OF TEST RESULTS FOR METALS REMOVAL (mg/1)
BY BPT AND FLOGCULANT ADDITION
Effluent
Mine
Will
Test No.
Raw
PH
2.03
TDS
19100
A£
.241
As
PL
§£
.175
Cd
.603
Cr
.461
Cu
.246
Fe
10.50
Hfi
.628
M"
183
Nl
7.27
Pb
.012
Sb
DL
Se
DL
Tl
DL
Zn
31.6
Scarlet
S-l
Influent
Effluent
S-2 (spiked)
Influent
Effluent
Detection Limits
9.6
9.75
10.5
9.8
...
2650
2920
3250
2610
.168
.085
.258
.158
.005
DL
DL
.017
m.
.005
.137
.045
.272
DL
.001
.523
.196
4.31
.051
.001
.431
.178
3.73
.097
.002
.208
.081
3.49
.082
.005
1220
311
1980
.809
.005
DL
DL
.121
.013
.001
221
61.8
U.9
,283
.005
6.08
2.36
4.15
DL
.005
DL
DL
DL
DL
.001
DL
DL
DL
DL
.005
Dt.
DL
DL
DL
.010
DL
DL
DL
DL
.002
22.6
8.66
39.3
.059
.002
U)
-------
to the raw drainage in about half of the tests to yield a
concentration of 3 mg/1 for each of the metals prior to neutralization
and flocculant addition. Due to an inadvertent error, the spiked
solutions used at the Crown site produced an initial concentration of
only 0.3 mg/1 for each spiked priority metal. At Norton, these
compounds were added as nitrates and at Hollywood, chloride metal
salts were utilized.
Second, the quantity of lime required to neutralize the acidity in the
drainage from Will Scarlet was so voluminous for tests S-3 through S-6
that the settled sludge kept the lower sampling tap (where metal
samples were obtained) covered throughout the test. Thus, analytical
results are available on the metals contained in AMD sludge, but are
of no value and, as such, are not included on Table VII-7.
Thirdly, raw water characteristics from the Crown site are presented
as settling tests C-l and C-2. This is also true of the Norton site
where test N-l summarizes raw mine water settling characteristics.
These tests were run without chemical addition to establish baseline
performance data. Tests on raw water at Hollywood and Will Scarlett
would be redundant and hence were not conducted.
Excluding the datd from tests S-3 through S-6, means are presented in
Table VII-8 for each of the final effluent metals concentrations
(quantifying non-detected values as 1/2 the detection limit). These
values represent achievable effluent limitations for acid mine
drainage from deep and surface facilities through the application of
BPT and flocculant addition technology.
Additional treatability analyses have been conducted by the Agency at
the Crown, West Virginia site for polymer addition; results indicate
that certain priority metals (Ni, Cu, Cr, and Se) are effectively
reduced (2). Other studies have also confirmed the suspended solids
and metals reductions documented above (16, 24, 25, 26, 27, 28).
In cases where settling ponds are at remote locations, construction of
access roads and power lines will be necessary to install and maintain
polymer feed equipment. The installation of chemical handling
equipment, tanks, access roads, land, and power lines in remote areas
could exacerbate coal mining production problems, particularly for
small mines. Costs for those items are presented in the next section
of this report. In some cases where ponds are difficult to access or
lack electricity, gravity feed systems (used in one Western coal mine
visited) or diesel generators can be employed.
Filtration
Filtration is used as a suspended solids and metals removal
technology. Filter systems are usually located downstream of primary
gravity settlers, lime precipitation units, or polymer addition
equipment. Filtration is accomplished by the passage of water through
a physically restrictive medium with resulting entrapment of suspended
264
-------
Table VII-8
MEAN FINAL EFFLUENT CONCENTRATIONS (mg/1) FOR
UNSPIKED AND SPIKED SAMPLES
Unspiked
Metal
Ag
As
Be
Cd
Cr
Cu
Fe
Hg
Mn
Ni
Pb
Sb
Se
Tl
Zn
Mean
.009
.0025
.0005
.0252
.0581
.0114
2.28
0.0114
.612
.084
.0005
.0025
.005
.001
.0642
Standard
Deviation
.006
0
0
.060
.0622
.0197
3.79
0.0327
.986
.023
0
0
0
0
.134
Spiked
Mean
.023
.0025
.001
.150
.072
.0636
2.96
.183
1.55
.273
.019
.0025
.001
.001
.059
Standard
Deviation
.045
0
.002
.203
.0263
.043
7.04
.280
1.60
,263
.018
0
0
0
.0521
265
-------
particulate matter. Filtration is a versatile method in that
be used to remove a wide range of suspended particle sizes.
it can
Filtration processes can be placed in two general categories: (1)
surface filtration devices, including microscreens and diatomaceous-
earth filters; and (2) granular-media filtration, such as rapid sand
filters, slow sand filters, and multimedia filters. For application
to coal mine wastewaters, granular media filtration systems are most
suitable.
Granular media filtration utilizes a variety of mechanisms including
straining, interception, impact ion, and adsorption for suspended
solids removal. Filters are most often classified by flow direction
and type of filter bed. Downflow, multimedia filters would probably
find the widest application to both acid and alkaline coal mine
wastewaters. In such a system, influent is piped to the top of the
filter and by gravity or external pressure percolates through the bed
before discharge or further treatment.
Maximum loading of the filter is determined either by a prescribed
permissible head loss (the pressure drop across the filter) or a
ceiling level of suspended solids in the filtered effluent. When
these conditions occur, the filter is backwashed and air-scrubbed to
clean the bed, and the wash water disposed of in an acceptable manner,
usually by settling and return to the head of the treatment plant.
Various combinations of media, including sand, gravel, garnet,
activated carbon, anthracite coal, and ilmenite, can be used in a
filtration system. These materials represent a wide distribution of
specific gravities and grain sizes. Total media depths typically
range from 50 cm to 250 cm, with feedwater flux rates of 2 to 30
gallons per minute per square foot of cross-sectional area, with 10
gpm per square foot typical,
Whenever possible, designs should be based on pilot filtration studies
of the actual wastewater. Such studies are the best way to assure:
(1) representative cost comparisons between different filter designs
capable of equivalent performance {i.e., quantity filtered and
filtrate quality); (2) selection of optimal operating parameters, such
as filter rate, terminal head loss, and run length for a given medium
application; (3) definite effluent quality performance for a given
medium application; and (4) determination of the effects of
pretreatment variations. Ultimate clarification of filtered water
will be a function of particle size, filter medium porosity,
filtration rate, and other variables.
The technology is proven in both industrial and municipal applications
and is less expensive than other technologies when reductions to 10
mg/1 TSS and less and very low levels of suspended metals are to be
achieved. A major question in application to coal mine wastewater is
the potential for gypsum fouling/blinding if lime is used for
neutralization when calcium ions liberated by the dissolution of lime
(CaO) combine at alkaline pH with sulfate ions. This substance will
266
-------
deposit on surfaces throughout the treatment system. When this
material deposits on the granular media pores, water is impeded from
passing across or through the filtration apparatus. This phenomena is
called fouling or blinding. The problem can be abated by proper
dosage of lime, recycle of sludge or use of a different neutralizing
chemical. To examine the levels of suspended solids and toxic removal
potential achieved by filtration technology, a treatability study was
instituted by the Agency at two mines, both exhibiting normally acid
mine drainage (24, 25).
The first testing program, conducted on BPT-treated acid mine drainage
from a deep mine in Pennsylvania, consisted of bench scale jar tests,
dual media filtration tests and backwash settling tests at the coal
mine site. In addition to determination of achievable removal of
suspended matter, an evaluation of possible effects of fouling caused
by gypsum or excess lime was carried out. Further, a number of
filtration tests were run with addition of different polyelectrolytes
to ascertain their effect on filter performance. Composite samplers
were used to track filter progress.
Initial flux rates for each test were established at 20 gpm per square
foot of filter area. The influent to the test unit was clarifier
effluent from the acid mine drainage treatment plant. The final
effluent from a final settling pond was not used because the
concentrations of TSS and iron were too low to provide large enough
pollutant loadings to satisfactorily evaluate pollutant removal
capability. Test parameters for each test run are summarized in Table
VII-9. No filter test runs exhibited a significant flow reduction,
including a test of 43 hours duration {test no. 9). Effluent
suspended solids averages were always below 15 mg/1 and, in many
cases, less than 10 mg/1. This level was independent of the duration
of the test run. At the end of each filter test run, the filter
media were cleaned by a combination of air and water backwash. A
backwash period of 10 minutes was found to be sufficient in each case
to regenerate the filter.
Analytical data for the priority metals are summarized in Table VII-
10. Priority metals in the clarifier effluent used as influent to the
filtration apparatus were very low. In addition, no spiking of
effluent for treatment was conducted. As a result, quantitative
prediction of priority metals, removal is not possible. Metal levels
in many influents were not detectable and in no case did a priority
metal have a filter effluent concentration of greater than .012 mg/1.
Reductions of iron to .75 mg/1 average effluent concentration from 2.8
mg/1 average influent, and reduction of manganese to .063 mg/1 from
.17 mg/1 average were achieved.
ALKALINE MINE DRAINAGE
267
-------
Test
No.
1
2
3
4
5
6
7
8
9
10
ro 11
oo 12
13
14
15
16
17
Polymer Added
(none)
-
-
-
-
-
la
1*
-
1 b
1 o
-
-
lc
lc
-
Table VII-9
SUMMARY OF FILTRATION TESTS PERFORMED
Suspended Solids (mg/1)
Min.
10.2
--
9.9
--
16.2
16.4
14.4
--
--
13.6
19.0
17.6
--
17.8
—
16.2
--
Influent
Max.
27.4
--
17.8
--
38.8
40.6
34.8
--
--
29.4
48.2
39.2
--
43.0
--
99.4
--
Ave.
12.8
13.6
13.3
17.4
27.8
28.6
23.6
21.2
20.2
22.2
33.6
24.9
20.0
27.8
11.4
24.0
15.4
Min.
1.2
--
1.6
--
2.8
6.1
1.0
_-
--
<1.0
9.9
3.4
--
<1.0
--
7.0
.-
Effluent
Max.
9.2
--
7,0
--
11.4
16.1
8.6
--
..
13.6
17.3
10.2
..
10.6
--
16.4
--
Ave.
2.6
1.4
3.0
3.8
7.8
11.0
5.5
5.2
7.0
7.3
14.1
6.6
10.4
6.5
10.2
9.8
2.8
Initial
PH
9.2
9.4
9.4
9.5
9.3
9.2
9.5
9.4
9.0
9.4
9.2
9.5
9.7
9.4
9.2
9.8
9.9
Final
PH
9.2
9.2
9.1
9.1
9.1
9.2
9.2
9.1
8.8
9.1
9.2
9.3
8.7
9.3
9.0
9.5
9.7
Notes: aDowell 144
"^agnifloc 1820A
cCalgon L670E
-------
Table VII-10
ANALYTICAL RESULTS FROM FILTRATION TREATABILITY STUDY
(in ug/1 unless noted)
Test Ho. pH (units) TPS («g/l> *&**leCdCtCu?b¥e Kg tfa Hi Sb Se Tl Zn
1
Influent
Effluent
2
Influent
Effluent
3
Influent
Effluent
4
Influent
Effluent
5
Influent
Effluent
6
Influent
Effluent
7
Influent
Effluent
Influent
effluent
9
Influent
Effluent
10
Influent
Effluent
9.*3
9.4
9.4
9.2
8.5
9.5
9.4
9.3
9.1
9.5
9.4
9.7
9.4
9.6
9.7
8.9
8.9
9.3
8.8
1400
1400
1400
1400
1350
1400
1400
1400
1400
1400
1400
1400
1400
1360
1400
1400
1420
1430
1440
1430
10
3
8
7
14
15
11
11
16
16
23
21
28
36
34
33
4
<2
<2
<2
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<1 <8
<1
-------
Table VII-10 (Continued)
ANALYTICAL RESULTS FROM FILTRATION TREATABILITY STUDY
(in ug/1 unless noted)
Teat Ho. pH (unlta) TDS (•g/1)
Hn
Hi
Sb
Se
Tl
Zn
11
Influent
Effluent
12
Influent
Effluent
13
Influent
Effluent
14
Influent
Effluent
15
Influent
Effluent
16
Influent
Effluent
17
Influent
Effluent
Average
Influent
Effluent
9.3
9.2
9.5
9.4
9.7
8.6
9.7
9.5
9.8
9.6
9.7
9.4
9.6
9.6
1440
U4D
1350
1340
1360
1360
1410
1390
1400
1400
1380
1370
1390
1380
1400
1400
<2
<2
<2
<2
<2
<2
<2
<2
<2
7
8
9
5
10
i.5
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
<3
1.5
1.5
8
7
8
7
8
7
8
7
8
7
8
7
8
7
4.8
4.7
<8
<8
<8
<8
<8
<8
<8
<8
<8
<8
<8
<8
<8
<8
4.3
4.4
<3
<3
<3
<3
<3
<3
4
2
2
1
9
9
10
7
10.9
9.8
<1 <2
<1 <2
<1 <2
<1 <2
<1 <2
-------
Current Treatment Technology
Mines exhibiting alkaline drainage supply a majority of U.S. coal
production. Raw wastewaters from these mines are generally
characterized by very low metals levels and are pH neutral or slightly
alkaline. Alkaline surface mines can contain high sediment loading
caused by precipitation and runoff, whereas alkaline underground mines
are most often low in suspended solids. Many mines with alkaline
drainage can discharge the raw water without any treatment. However,
most mines will have a pond or pond system installed to contain or
treat runoff resulting from rainfall. Aside from precipitation and
the ensuing sediment laden runoff, the major exception to mines that
can normally discharge without treatment is for those mines located in
geological strata containing fine clays. These colloidal clays are
difficult to settle without coagulant aids. If fine clays are
prevalent, chemical flocculant addition may be required to comply with
BPT limitations. This, however, is an infrequent situation in the
industry. Figure VII-10 depicts a typical BPT treatment system for
alkaline drainage. The settling facility is identical to the sediment
pond or mechanical clarifier discussed under the previous acid mine
drainage subsection. Ponds installed to comply with rainfall
provisions are discussed later in this section.
Candidate Treatment Technologies
Technologies applicable to alkaline mines are similar to treatment
options discussed under acid mine drainage for BPT treated
wastewaters. The reader is directed to the Acid Mine Drainage
Candidate Treatment Technology subsection for a detailed discussion of
the technologies.
PREPARATION PLANTS
Current Treatment Technologies
Wastewater from coal preparation plants, as discussed in Section V,
originates from preparation plant coal separation and cleaning
equipment, such as jigs, washers, froth flotation units, and wet
cyclones. The water is high in coal fines which are removed prior to
discharge or reuse. Economic and environmental incentives often
dictate that some portion of this effluent water be recycled for plant
use. Some plants operate under total recycle while others recycle
only a fraction or none at all. The remainder is discharged after
appropriate treatment, usually consisting of some type of
sedimentation technology. This will remove the coal fines which are
present as suspended solids. Figure VII-11 illustrates a typical
treatment scenario for preparation plant wastewaters.
271
-------
Raw
Wastewater
Settling
Facility
Discharge
ro
—j
ro
Figure VII-10
TYPICAL BPT TREATMENT CONFIGURATION FOR ALKALINE MINE DRAINAGE
-------
U)
Preparation
Plant
Raw
Slurry
A
. Optional
' Recycle
r
Recycle
Settling
Facility
Underflow
Dewatering
Optional Make-Up and Recycle
Overflow
Fresh Water
Lake
To Disposal
Figure V1I-11
TYPICAL BPT TREATMENT CONFIGURATION FOR PREPARATION PLANT WASTEWATER
-------
The slurry stream generated by the preparation plant usually contains
fine coal refuse as a waste product from the coal cleaning process.
The refuse contained in the slurry is usually 0.10 in (approximately
2.50 mm) and finer in size and frequently contains less than 10
percent by weight solids. In many cases, fine coal, clay and other
mineral particles with size below 0.004 in (0.10 mm) are present. In
some cases, very fine colloidal-sized material is present. These
solids are removed to allow reuse or discharge of the clarified water.
The settling facilities most often used are sedimentation or slurry
ponds, or, where adequate land is not available, clarifiers/thickeners
are frequently employed. Where the latter option is selected,
dewatering by vacuum or pressure filtration is occasionally
implemented within the industry to recover additional water and permit
easier handling of the dewatered refuse. The water from this process
is recycled to the clarifier influent and the refuse is hauled to a
disposal site, a borehole, or an abandoned or active pit.
In Appalachian facilities, dewatering of the thickener underflow is
commonly accomplished in a sedimentation pond for settling of the
solids and recycle or discharge of the basin decant. Overflow from
the clarifier/thickener is either directly recycled to the preparation
plant or routed to a pond system (termed a "fresh water lake" in
Figure VII-11) for eventual recycle or discharge. In many existing
facilities, this latter alternative of drawing makeup from a fresh
water basin is often preferred to provide a dependable water source of
consistent quality for preparation plant use.
Many midwestern and western facilities employ sedimentation basins in
lieu of clarifiers to provide solids removal for the refuse slurry.
Basins are sometimes designed for the life of the preparation plant,
but more frequently, a number of ponds are required over the operating
life of the cleaning facility. As one slurry pond is silted out,
slurry is diverted to a new basin. The old pond can be dredged and/or
reclaimed. These sedimentation basins will often receive drainage
from areas associated with the preparation plant, such as disturbed
areas ancillary to the site, coal storage piles, and refuse piles.
The characteristics and treatment of effluents from these three
sources are discussed in the next subsection. The pond system will
also frequently receive storm runoff drainage from undisturbed areas,
which, in some cases, can consist of vast tracts of land.
This storm runoff is also analyzed later in this section. Decant
routed from the primary slurry settling pond is commonly commingled
with this undisturbed area drainage and raw or treated effluents from
the associated areas in a fresh water lake. Lakes provide secondary
settling prior to recycle of water required by the preparation plant.
The suspended solids removal technology selected by mine operators is
very dependent on the region in which the mine is located. In
Appalachia and other regions where steep terrain is prevalent,
thickeners and clarifiers are usually installed rather than settling
basins to handle preparation plant slurries.
274
-------
Those plants using a clarifier often use a coagulant aid to assist in
agglomerating fine solids, resulting in greater settling rates of
solids. Preparation plants that employ settling ponds for suspended
solids removal do not usually inject chemical aids but instead rely on
the longer retention times available to provide sufficent settling.
Candidate Treatment and Control Technologies - Existing Sources
Control technologies are particularly applicable to preparation plant
wastewaters in the abatement of pollution from these sources. This
includes consideration of a no discharge of pollutants requirement
that would require recirculation of all water from a system treating
wastewater from a preparation plant water circuit.
Total Recycle Option
To properly evaluate this option for existing sources, an examination
of the definition of preparation plant wastewater is essential. For
the remainder of this report, "preparation plant wastewater" is
defined as any wastewater which results from processing a stream of
coal to remove ash forming constituents. This wastewater consists of
the following:
1. Water purposely brought into contact with
to clean the coal,
run-of-mine coal
2. Water collected in the waste sump resulting from
cleanup within the preparation plant boundaries, and
spills or
3. Runoff resulting from precipitation
preparation plant wastewater treatment system.
which enters
the
Thus, the zero discharge requirement would effectively disallow the
discharge of any pollutant-bearing water that stems from or contacts
process water from the preparation plant.
To assist in the analysis of this issue, Figure VII-12 depicts the
various flows into and out of the preparation plant. The types of
flow streams entering the water circuit are shown on the left side of
the block diagram and flows exiting the system are shown on the right
side. The various sources and losses of water in the system will be
discussed below in an effort to evaluate the requirements for
attainment of total recycle for the preparation plant water circuit.
Water sources include:
1. Makeup Water. Water from sources external to the preparation
plant and slurry water systems are almost always needed to meet the
feed water requirements of the plant after using the water recycled
from slurry treatment. Typical sources might be surface
impoundments, mine drainage, well water, or drainage from preparation
275
-------
Make-Up Water
Water on Feed Coal
Ox
Preparation
Plant
Water on Coarse Refuse
Water on Coal Product
Miscellaneous Water Losses
iA
Recycle
Precipitation and Runoff
Slurry Water
Treatment
Evaporation and Seepage
Water on Fine Refuse
Figure V1I-12
WATER SOURCES AND LOSSES IN A PREPARATION PLANT WATER CIRCUIT
-------
plant associated areas. This water should be neutral or basic to
minimize corrosion problems and be relatively low in suspended solids
content to avoid nozzle fouling in the plant. The volume of makeup
water from sources external to the preparation plant water circuit may
be zero if the slurry treatment system has sufficient capacity to
store large volumes of water. In general, however, implementation of
a zero discharge requirement would necessitate a makeup water source
that can be throttled to balance the system.
2. Water on the Surface of Feed Coal. The coal entering the
preparation plant usually has some water on the surface of the coal.
This water results from dust suppression sprays in underground mined
coal or from ground water in wet surface or underground mines. The
raw coal also receives water as a result of precipitation falling on
storage piles or on the coal as it is transported to the plant.
3. Precipitation and Runoff. The quantity of water entering the
system from precipitation and runoff is governed by design and
climatological factors which are both site specific. A slurry
treatment system consisting of a thickener and filtration of the
underflow receives precipitation only on the surface of the thickener.
The amount of precipitation entering a pond system is related directly
to the drainage area of the pond or ponds. The amount of runoff
entering from areas adjacent to the pond system can be controlled at
the design phase or as a retrofit procedure by using diversion
ditching and diking as required to control inflow.
Water losses include:
1 * Moisture on the coal product. This moisture leaves a preparation
plant as residual water after having undergone some form of mechanical
and/or thermal coal drying. The degree to which the coal material is
dried is usually determined by what is necessary to achieve purchaser
specifications and/or the avoidance of excessive transportation costs.
The amount of water leaving with the coal will most often be greater
than that entering with it since the cleaning process involves a size
reduction with the attendant increase in surface area. This increase
in porosity due to smaller grain sizes enhances water retention.
2. Water on Coarse Refuse.
remove
The cleaning process is designed to
material that either does not contribute to the end use of the
coal or has some deleterious effect on the use of the coal. These
materials are removed as refuse by processes in the preparation plant.
The bulk of this refuse leaves the plant as a surface-saturated solid
after mechanical dewatering. It is dry enough to allow handling by
truck or conveyor to a disposal site. The large size of this refuse
makes use of wet disposal impractical. The volume of this coarse
refuse will be a function of the amount of non-coal components in the
plant feed and the efficiency of the separation. The total amount of
water leaving the system by this route will be dependent on the amount
of refuse as well as the relative size of the refuse.
277
-------
3. Miscellaneous Water Lost (Drying and Evaporation). In some cases,
thermal drying of the coal is required to meet product specifications.
Usually, thermal drying is primarily used for the fine coal fraction.
In this process, the surface moisture in the coal is reduced by
evaporative losses. Water is also lost by evaporation in the plant,
particularly at locations where water sprays are used in processing.
Usually the water removed from the system as a result of drying and
evaporation is not large compared to the total plant water
requirement.
4. Evaporation and Seepage from Slurry Water Treatment. The volume
and importance of these losses from the system will be a function of
the design of the system as well as site specific hydrologic
conditions. For example, if the slurry water treatment consists of a
thickener and underflow dewatering, then seepage is nonexistent.
Evaporation, although still dependent on local climatic factors, is
limited to the surface area of the thickener. On the other hand,
slurry water treatment by sedimentation in a pond system can result in
major losses by evaporation and seepage depending upon design and
maintenance of the system (e.g., surface area, lining, etc.).
5. Fine
designed to
Refuse Moisture. Generally, a preparation process is
minimize the production of fines while achieving the
•desired coal quality improvement. Therefore, the fine solids which
can be removed from the slurry by some combination of sedimentation
(usually in mechanical thickeners or settling impoundments) and
filtration usually represent a relatively small proportion of the feed
material. After the fine solids have been removed in the settling
facility from the bulk slurry, they will retain considerable water.
Fine soli'ds can be dewatered by filtration of the thickener underflow,
and will often contain about 25 percent water by weight. The fine
solids removed by sedimentation in ponds will, of course, retain
greater amounts of water.
As indicated above, losses from water on the coal product and coarse
refuse, as well as internal evaporative losses are insignificant in
comparison to the total water flow in the plant. Closing the water
circuit will primarily involve recycling of preparation plant
effluents as makeup to the facility. However, the wastewater leaving
the preparation plant as slurry is not suited for direct reuse in the
preparation plant because of its fine solids content.
The slurry treatment process must prepare water for recycle that is
relatively free of suspended solids so that its solids carrying
capacity is restored for removal of similar material in the
preparation plant. Solids even in fine sizes and low concentrations,
can cause long term maintenance problems as a result of excessive pump
and piping wear. Nozzle plugging is an additional maintenance problem
for washing operations within the plant. The reuse for screen spray
and wash water of thickener overflow with suspended solids less than
100 ppm has been reported. Slurry treatment must also provide recycle
water which is neutral or alkaline to minimize corrosion of the
process equipment.
278
-------
Two primary issues can be delineated regarding a no discharge
requirement. First, a total recycle system must provide sufficient
water to meet process requirements while taking into account the water
losses previously discussed. Second, the feasibility of segregating
preparation plant wastewater from other wastewater must be assessed.
Both of these factors are primarily design considerations.
A survey was conducted in cooperation with the National Coal
Association in 1980 of its member companies to collect data and
information specifying the design of their preparation plant slurry
treatment systems. Eighty-eight member producer companies of the NCA
were canvassed for profile information and water management data.
These companies operate approximately 292 preparation plants. One
hundred and fifty-two of these (52 percent), representing about 24
entire preparation plant industry, responded to the
from the responding facilities indicate that
percent are currently achieving zero discharge of
wastewater. This suggests that certain facilities
addressed the two issues outlined above. Other
system design that provides for a sufficiently large
continually supply preparation plant makeup water
percent of the
survey. Results
approximately 34
preparation plant
have adequately
facilities have a
drainage area to
needs. Such systems resolve the first issue but are susceptible to
voluminous amounts of discharge during rainfall. Plants that obtain
water from this type of system would have to provide adequate
freeboard in their slurry basins to accomodate the storm flows. A
second way to comply would be to install a clarifier/thickener with
underflow dewatering, thus obviating the need for the pond system. A
third alternative is to install diking and diversion ditching around
the pond system and drawing makeup water from a new source. This
third alternative may also require installation of new facilities to
treat the diverted runoff, particularly if acidic refuse and coal pile
drainage is involved.
These alternatives are shown schematically in Figures VIII-18 and
VIII-19 in Section VIII. If a facility already has a clarifier
installed, changes would be confined to recycling all decant to the
preparation plant and dewatering the underflow solids. This option is
depicted schematically in Figure VIII-20 of Section VIII. Redesign of
the clarifier or additon of equipment for chemically aided solids
settling may be required to provide water of suitable quality as
makeup water. Many facilities already have this flocculant addition
equipment in place with their clarifiers.
However, there are certain interferences involved with coal
preparation processes that may occur as a result of a total recycle
system that could make an occasional discharge or purge necessary.
Such interferences are:
1. Build-up of froth flotation chemical reagents, used
froth flotation process, making the process less effective,
in the
279
-------
2. Build-up of gypsum used in pretreating the recycled water
for pH adjustment interfering with both the froth flotation and
gravity separation processes,
3. Build-up of slimes that interfere with gravity
processes particularly when using heavy media vessels,
separation
4. Build-up of TSS and tds causing scaling of pipes
plugging of nozzles,
and
5. Build-up of TSS and TDS that impair the use of filters used
to dewater sludge from the water recycle treatment system causing a
higher filter cake moisture content.
This leads to problems in refuse disposal.
Thus while total recycle with no discharge is a technically achievable
control technology for some facilities, certain processes may require
occasional purges from the water recycle circuit. This occassional
purge allowance has been incorporated into the zero discharge option.
Facilities using this purge allowance will be subject to alternate
limitations (equal to BPT) while purging. The costs associated with
the implementation of this alternative are presented and discussed in
Section VIII.
Flocculant Addition
Flocculant addition is also a candidate BAT option for preparation
plant wastewaters. Important factors characterizing this technology
were previously discussed for mine drainage and will not be repeated
here.
Filtration
Preparation plant wastewaters are readily amenable to this type of
treatment. Gypsum is rarely evident in the normally alkaline
effluents. Further, metals, if present, are in the suspended state
and are thus removed by filtration. Application of this technology is
feasible for both clarifier and sediment basin effluents. Achievable
levels are documented in the mine drainage section.
Other Technologies
Reverse osmosis, ion exchange, electrodialysis, and sulfide
precipitation are technologies applicable for dissolved solids
removals. Alkaline effluents are characteristically low in unde-
sirable and toxic dissolved metals, and thus these technologies are
not considered for preparation plant wastewaters. Activated carbon
and ozonation are fouled by high suspended solids, rendering them
ineffective for these types of effluents. Moreover, their principal
280
-------
application is for a dissolved compound at a low pH
which are expected in preparation plant discharges.
Candidate Treatment Technologies - New Sources-
value, none of
Two major options are considered for new source preparation plant
discharges—a no discharge of pollutants requirement (with an
occasional purge allowance) and a discharge with effluent standards
achievable through application of the best available demonstrated
treatment technology. These approaches are identical to that
discussed for existing sources however, additional considerations are
relevant for the no discharge requirement. Total recycle, even
without a purge, for new sources is more easily achievable than for
existing sources because water handling strategies to achieve zero
discharge can be incorporated into the initial design phases such that
occasional purges, if necessary, are kept to a minimum. For example
segregation of other drainage from the preparation plant wastewater
can be a design parameter of the system. Ponds can be located in
topographical areas that do not receive large amounts of natural
drainage. This will lessen the volume of storm runoff requiring
diversion around the slurry treatment system. Also, if
clarifier/thickeners are selected for settling, small emergency ponds
can be provided to contain temporary imbalances in the water circuit
arising from operational problems or exceedingly heavy precipitation
on the clarifier surface. Certain flocculants to remove slime can be
added, use of other pH adjustment metal remover chemicals besides lime
can be used and improved sludge handling techniques can be employed.
Costs for implementation of this option and of discharges employing
filtration technology to polish the final effluent are presented in
the next section.
PREPARATION PLANT ASSOCIATED AREAS
Current Treatment Technology
Drainage from these areas is a result of runoff from coal storage and
refuse piles and other disturbed areas. This runoff has similar
characteristics to untreated drainage from adjacent mines. The
rulemaking published on 26 April 1977 (42 FR 21380) established
limitations similar to those for active mine drainage; i.e., standards
for pH, TSS, and iron (and manganese for drainage that is normally
acidic prior to treatment). As a result, current treatment technology
for this subcategory typically includes neutralization, aeration, and
settling for acidic runoff and settling for alkaline runoff. In cases
where site logistics permit, runoff is often commingled with mine
drainage due to the cost advantages in joint treatment. Each of the
281
-------
technologies was discussed in detail in the mine drainage subsection
and is not reiterated here.
Candidate Treatment Technologies
Drainage from preparation plant associated areas is often commingled
for treatment with the preparation plant wastewaters. Establishment
of a no discharge regulation for associated area runoff is infeasible
due to the extremely wide variations in storm runoff. If such a
requirement is proposed for preparation plant wastewaters in existing
sources, associated area drainage would in most cases have to be
segregated and treated separately. Because this wastewater is similar
to mine drainage, the reader is referred to the discussion found in
the Candidate Treatment Technologies portion of that subsection.
POST MINING DISCHARGES
Reclamation Areas
Current Treatment Technology
Areas under reclamation are defined as areas of land resulting from
the surface mining of coal which has been returned to final contour
and revegetation begun. Drainage from land that has been regraded
after active mining is not currently subject to EPA regulations unless
commingled with wastewater from the active mining area, OSM, under
authority of SMCRA, has required that drainage from reclamation areas
must be routed through a sedimentation pond. OSM has, however,
proposed to delete this requirement. 46 FR 34784 (July 2, 1981).
Operators have installed sedimentation ponds to treat this drainage
until revegetation requirements are met and untreated drainage
{influent to the ponds) meets the applicable state and federal water
quality standards for the receiving stream (see 44 FR, 3 March 1979).
Candidate Treatment Technology
The Agency has conducted a sampling and analysis program under
authority of Section 308 of the Clean Water Act to have 12 companies
monitor influents and effluents at 24 ponds for one year. (See
Appendix A). This study is summarized in more detail in the following
section under "Precipitation Events." These ponds primarily receive
drainage resulting from precipitation from areas undergoing
revegetation, although some ponds also receive active mine drainage.
Data from the program are presented in Appendix A. Total suspended
solids were found at widely varying levels, due partly to differences
in particle size distribution delivered to the pond from the
reclamation area. These differences were large enough such that
282
-------
nationally applicable TSS regulations could not be developed.
Settleable solids (i.e., suspended particles that will settle within
one hour) and pH, however, are effectively controlled by these
sediment ponds. The data also demonstrate that concentrations of the
toxic metals and iron and manganese in drainage from these areas are
at or very near limits of analytical detection.
The Office of Surface Mining initiated a regulatory program under the
Surface Mining Control and Reclamation Act (SMRCA) to control both
surface coal mining and the surface effects of underground coal mining
(30 CFR Parts 700 et seq.), Section 509 of SMCRA requires coal mines
to post bond securing their performance with the requirements of the
Act. Liability under the bond remains for at least five years after
the last year of augmented seeding, fertilizing, irrigation and other
reclamation work (for at least 10 years after that time in those
regions of the country where the average annual precipitation is 26
inches or less)
Liability under performance can continue for as long as necessary to
achieve compliance with all requirements of SMCRA. Runoff from the
disturbed areas of a surface mine must be passed through a
sedimentation pond or treatment facility until the disturbed area has
been restored, revegetation requirements have been met, and the
quality of the drainage without treatment "meets the applicable State
and Federal water quality standard requirements for the receiving
stream."
EPA's regulations for post-mining discharges are consistent with the
requirements of SMCRA in that effluent limitations guidelines apply
only until full release of the SMCRA performance bond. The release of
the bond by the appropriate SMCRA authority signifies the OSM's
determination that the coal mine operator has carried out his
responsibilities under SMCRA, and that post-mining pollution problems
are accounted for and can be reasonably expected not to occur.
However, EPA investigated the potential need for effluent limitations
guidelines after the SMCRA bond release (see Appendix C). This
investigation, completed in August 1982, consisted of a telephone
survey, and a literature search of information regarding effluent
discharges at "post-bond" release mines. Federal, State, and public
information sources were examined. As a result of this investigation,
the Agency was able to develop estimates of the number of active,
closed, and abandoned coal mines, but was not able to determine the
number of coal mines sealed or reclaimed under SMRCA. Based on the
results of this data collection effort, there is insufficient data
available to support the development of regulations for post-bond
release reclamation areas.
Underground Mine Discharges
Current Treatment Technology
283
-------
Underground mines will often continue to discharge after cessation of
coal removal from the mine. This drainage is similar in composition
to the drainage that occurred during the active life of the mine,
since the mechanism for generation is identical (see "Inventory of
Anthracite Coal Mining Operations, Wastewater Treatment and Discharge
Practices," by Frontier Technical Associates, Buffalo, N.Y., June
1980). No EPA limitations are currently established for these
discharges. However, OSM standards require that this drainage be
treated until either the discharge continuously meets the applicable
Federal and State requirements or the discharge has permanently
ceased.
Technology to control these discharges is identical to that
implemented for active mine drainage. For acid discharges, this
includes neutralization, aeration, and settling. Alkaline discharges
require only settling. Each of these has been extensively discussed
and will not be repeated here.
Candidate Treatment Technology
Each treatment technology presented in the active
sections is also considered for this subcategory.
mine drainage
ALTERNATE LIMITATIONS DURING PRECIPITATION EVENTS
Precipitation events can make it
limitations on TSS, iron and manganese
Capability of Surface Mine Sediment
Engineers-Consultants, Harrisburg,
infeasible to meet effluent
(see "Evaluation of Performance
Basins" by Skelly and Loy,
Pennsylvania, July 1 979) .
Precipitation events are beyond the control of the coal operator;
thus, some mechanism should exist to temporarily exempt the facility
from compliance during wet weather conditions until "dry weather"
conditions return. For the coal mining industry, precipitation is the
prime cause of an excursion beyond the effluent standards,
particularly for total suspended solids. This is because the vast
tracts of land occupied by many surface coal mines receive substantial
rainfall, particularly in the Appalachian coal region.
The original exemption for storm (or snowmelt) was published in the
BPT regulatory promulgation of 26 April 1977 (42 FR 21380). The
exemption was provided for overflows from sedimentation ponds that
were "designed, constructed, and maintained to contain or treat the
discharges . . . which would result from a 10-year, 24-hour
precipitation event . . . . " Thus, the exemption was available
regardless of the size of the hydrologic event.
284
-------
On 12 January 1979, the Agency promulgated new source performance
standards for the coal mining category that contained a modified storm
exemption. The modification included that: (1) the burden of proof
was placed on the operator to demonstrate that the appropriate
prerequisites to obtaining the exemption had been met, and (2) an
exemption could only be granted if a 10-year, 24-hour or larger event
(or snowmelt of equivalent volume) had actually occurred. On 2 April
1979, the exemption provided for existing sources was amended to be
identical to the NSPS exemption.
These actions met with substantial criticism and legal opposition by
various industry trade groups, such that EPA withdrew its modified
exemption provision and instituted the Skelly and Loy Study cited
above to more clearly define sedimentation pond performance,
particularly for those storms less than the 10-year, 24-hour event.
This study concluded that sediment-pond efficiency during storm events
is, to a large extent, dependent on site-specific factors. The inflow
hydrograph (i.e., the volume of water delivered to a pond at any given
moment during or immediately after a storm) of a given storm event,
and the volume and concentration of sediment delivered, will depend in
each case on, among other things, the soil erodibility, length and
steepness of the terrain, and cover and management practices employed
at a given watershed. Moreover, the specific total suspended solids
concentration in the effluent of a given sediment pond will depend on
the particle size distribution of the solids delivered to the pond.
As the Skelly and Loy study demonstrates, theoretical detention times
on the order of 24 hours may not be sufficient to permit settling of
fine, colloidal solids. Thus, even if all of the larger solids
settle, TSS effluent concentrations can vary widely depending upon the
amounts of fine material present in the influent. The particle size
distribution of the sediment delivered at a particular site is thus a
critical factor affecting effluent quality, and is largely beyond the
control of the operator. This distribution will vary not only from
site to site for a given storm event, but at the same site during the
course of the storm (7).
These conclusions were verified by other available literature,
including an EPA study entitled, "Effectiveness of Surface Mine
Sedimentation Ponds" published in 1976. This study's central
conclusion was that the sediment ponds which were properly designed
and maintained were measured to have high efficiencies of removal of
suspended solids during the baseline sampling period. However, the
efficiency of removal of suspended solids was measured to be much
lower during the storm event (12).
As a result of these investigations, on 28 December 1979 (44 FR
76788), the Agency rescinded its BPT and NSPS storm exemptions and
promulgated what was .essentially the original BPT exemption, with the
burden of proof placed upon an operator and a requirement that the
overflow had been caused by an actual hydrological event.
285
-------
During the course of this rulemaking, the Agency instituted two
studies to investigate the appropriateness of alternate limitations
during the storm exemption period. One study established the data
base supporting the pH and settleable solids limitations, of 6-9 and
0.5 ml/1 respectively, for reclamation areas and active mining areas
during precipitation events (see Appendix A of this document). The
other study determined that settleable solids can be measured below
1,0 ml/1 with a reasonable degree of precision and accuracy, and that,
for the coal mining industry, 0.4 ml/1 is the method detection limit
for this parameter (see Appendix B of this document). (This study was
performed because, since proposal of this regulation, considerable
public comment was submitted to EPA stating the discrepancy between
the proposed 0.5 ml/1 standard and the Standard Methods statement that
"the practical lower limit is about 1 ml/l/hr.) These two studies are
briefly discussed below in order to present the rationale behind the
selection of settleable solids for regulation.
Settleable Solids
The 308 self-monitoring survey, as discussed in Appendix A, requested
industry submit weekly data on their sedimentation pond performance
for a one year period. Data was submitted on TSS, suspended solids,
total and dissolved iron, and pH by EPA approved analytical methods.
These data, with pertinent rainfall information, were to be submitted
to EPA on a monthly basis.
Twenty-four ponds submitted data. Seventeen of the 24 ponds satisfy
the necessary design criteria as specified in the May 26, 1982
proposal to the coal mining regulations. This specification required
that in order for a facility to become eligible for a "storm
exemption" the treatment facility must be able to contain the runoff
resulting from a 10-year, 24-hour storm. The volume of runoff had to
include the drainage from inactive (reclaimed) areas in addition to
the active mining areas (undisturbed, or virgin areas were excluded
from consideration). Four of the 17 ponds had no discharge. Two
additional ponds were excluded from analysis because of design and
operational defects.2 Thus a total of 11 of the 10-year, 24-hour ponds
submitted discharge data and satisfied the design criteria.
The facilities submitted data during both wet and dry conditions.
However, analysis were only performed on the wet weather data because
1) the settleable solids limitation for active mines will only apply
during precipitation events, and 2) although the settleable solids
limitation will apply during all weather conditions for reclamation
2The two ponds excluded from analysis either had effluent points
located very near the influent point, resulting in poor settling
performance or had drainage from surrounding spoil areas at
unspecified influent points to the pond. This was not the case for
the other ponds.
286
-------
areas, effluent discharges at these areas are primarily a result of
runoff during precipitation.
These eleven ponds submitted a total of 262 measurements taken during
wet weather conditions of which 4 exceeded settleable solids value of
0.5 ml/1. Thus, 98.47% of the measurements were less than or equal to
this value.
A stastical analyses was performed on these results and is presented
in Appendix A. On the basis of this analysis, the Agency concluded
that the 0.5 ml/1 value is consistent with the 99% compliance
criterion used for establishing effluent limitations.
Furthermore, similar analyses were performed on data from 18 ponds
regardless of size, (excluding from the original 24, the 4 ponds
without discharge, and the two that were improperly designed). There
were a total of 414 observations from these ponds of which 7 exceeded
the effluent limit of 0.5 ml/1 for settleable solids. Thus, 98.31% of
the measurements were less than or equal to this value. Again,
analyses of these data showed the 0.5 ml/1 limitation to be
consistent with the 99% compliance criterion.
Thus, analysis of the available settleable solids data from coal
mining sedimentation ponds demonstrates that the proposed limit of 0.5
ml/1 is consistent with Agency policy for effluent guidelines of 99%
compliance. Statistical analysis shows that the observed exceedance
rate is not significantly different from 1%. This conslusion holds
regardless of whether or not the size criterion for ponds specified in
the proposed regulation is considered.
Even though the technology basis behind the 0.5 ml/1 limitation is a
10-year, 24-hour pond, the analysis shows that even smaller ponds can
achieve this limitation. Therefore, any type of treatment facility
such as smaller ponds, diversion ditching, or diking can qualify for
alternate limitations during precipitation events as long as the
limitations are met.
The deletion of the pond design criteria is also consistent with the
OSM proposed regulations which have deleted this requirement as well.
Comments were submitted regarding their concern over a 0.5 ml/1
settleable solids limitation because Standard Methods suggest that the
"practical lower limit is about 1.0 ml/1." Therefore, EPA conducted a
study to determine the precision and accuracy of measuring settleable
solids below 1.0 ml/1 (see Appendix B). This study concluded that not
only can settleable solids be measured below 1.0 ml/1 but that the
maximum method detection limit for this parameter is 0,4 ml/1. The
method detection limit is defined as the minimum concentration of a
substance that can be measured and reported with 99 percent confidence
that the analyte concentration is greater than zero and determined
from analyses of a sample in a given matrix containing sample. A
description of the procedure to calculate the method detection limit
is presented in Appendix B or can be found in Environmental Science
287
-------
and Technology, "Trace Analyses for Wastewaters," Vol. 15, No. 12,
December 1981, Page 1426.
This study involved field and laboratory determinations of the method
detection limit using samples collected at 8 different sedimentation
ponds. Samples were analyzed using the Imhoff cone method as
specified in Standard Methods for the Examination o|_ Water and
Wastewater and 304(h) of the "EPA's methods for Analysis of Water and
Wastewater".
Settleable solids analyses were first conducted in the field. Seven
aliquots were prepared for each sample and placed in Imhoff cones.
Each aliquot was read by three independent observers. The seven
aliquots were then recombined into one sample and shipped to EPA's
laboratories whereby the same procedure was repeated only under more
controlled conditions. A method detection limit was then determined
from the results of these samples.
There were a total of eight samples (one from each pond) measured on
site. The method detection limits determined from these samples
ranged from 0.04 ml/1 to 0.40 ml/1 with an arithmetic average of 0.22
ml/1. Out of the 10 samples sent to and measured in the laboratory (2
were duplicates), the method detection limit ranged from 0.05 ml/1 to
0.20 ml/1 with an arthmetic average of 0.12 ml/1. {Laboratory results
are typically lower because of the more controlled conditions under
which samples are analyzed). In an effort to derive a practical
method detection limit representative of industrial conditions, a
method detection limit based on the field determinations is deemed
most appropriate. In addition, rather than establish the method
detection limit based on the average value a more conservative
approach is to base the method detection limit on the maximum value.
Thus, this study concluded that 1) settleable solids can be read below
1.0 ml/1 and 2) a method detection limit of 0.4 ml/1 should be
established for the coal mining industry.
The results from both studies concluded that the 0.5 ml/1 settleable
solids limitation is achievable and measurable and therefore is an
appropriate and effective means of sediment control both for active
mines during precipitation events and for reclamation areas.
288
-------
SECTION VIII
COST, ENERGY AND NON-WATER QUALITY ISSUES
INTRODUCTION
The principal purpose of this chapter is to present results of a cost
analysis for treatment technologies within each subcategory. Energy
requirements and nonwater quality • impacts such as solid waste
generation and air pollution are also discussed for each treatment
system. To conduct this analysis, a model plant approach was
utilized. The first step in this procedure is to estimate average and
maximum flow volumes and other design parameters. This was
accomplished by review of pertinent literature and site visits to
operating coal mines. From this information, capital and operating
cost curves are prepared to reflect each component of the treatment
system. These component costs are then assembled into overall costs
for an entire treatment system or level. Energy usage for each
technology is also computed.
A detailed breakdown of this section's summarized costs is presented
in a cost manual developed as a part of this project (1),' which is
included as a supplement to this document. Additional assumptions and
backup cost data are found in Appendix A of the Proposed Coal Mining
Development Document (EPA 440/1-81/057-b), and in reference (2).
The final step in the cost analysis was to verify the accuracy of
model plant costs with actual costs at an active coal mine. This was
achieved by first visiting various mines and collecting design and
cost information and then computing system costs for that mine. The
results, which are presented in Appendix A in the Proposed Coal Mining
Development Document, were then compared with the model plant costs,
using the actual flow at that mine. Treatment methods such as reverse
osmosis, electrodialysis, carbon adsorption, ion exchange, sulfide
precipitation, and ozonation were initially considered as possible
treatment processes for attaining BAT or NSPS compliance. These
treatment systems are not included in this section because these
systems are not feasible for reasons previously discussed. Table
VIII-1 summarizes capital c.nd operating costs for these systems based
on a flow of 1.0 mgd.
Note: Costs presented are based on estimates prepared in 1978 and
1979. These costs can be converted to 1982 dollars (or appropriate
year) by using the Engineering News Record (ENR) Construction Cost
289
-------
Table VIII-1
CAPITAL AND OPERATING COSTS OF ALTERNATE
TREATMENT TECHNOLOGIES
NOT RECOMMENDED FOR BAT
ro
vo
o
Carbon
Adsorption
Ion Exchange
Reverse Osmosis
Electrodialysls
Ozonation
Sulfide Precipi-
tation
Pollutants Treated
Organics and heavy
metals
Dissolved solids
and heavy metals
Dissolved solids
and heavy metals
Dissolved solids
and heavy metals
Cyanide Reduction
Heavy metals
Capital Cost
($1.OOP's)
2,000
500 to 1,000
500 to 1,000
500
240
No applicable
data available
Operating Cost
(1/1.000 gal)
1.37 - 1.64
1.00 - 1.90
0.95 - 1.90
0.80 - 1.00
0.20 - 0,25
No applicable
data available
Source
(6)
(6)
(6)
(1), (7)
Basis: 1.0 mgd facility; 1979 dollars.
-------
Index. For example the index for 1978 is 2,776 and 1982 is 3,730.
{See "Engineering News Report," March 18, 1982, for index listings).
Dividing the 1982 index by the 1978 index yields a factor of 1.34.
Compliance costs in 1978 dollars can be multiplied by this factor to
derive costs in 1982 dollars.
MINE DRAINAGE
Existing Sources
Treatment Levels
Four treatment systems (designated levels 1, 2, 3, and
identified as the basis for the cost analysis. These
incorporate the technically feasible technologies discussed in
VII, as outlined below,
4) were
systems
Section
Level One. This system is typical of a BPT treatment configuration.
As shown schematically in Figure VIII-1, this scheme consists of
optional raw water holding for equalization, neutralization if
required for acid drainage, optional aeration, settling, and optional
sludge dewatering.
required.
Some type of pH monitoring and control is
Level Two. This level consists of installing "add-on" equipment to
the present BPT facilities to permit the addition of a flocculant aid.
The flocculant aid is normally an organic polyelectrolyte added to
promote agglomeration and subsequent settling of finer suspended
solids. This level is depicted schematically in Figure VIII-2.
Level Three. This level, shown schematically in Figure VI11-3,
consists of mixers and flocculator-clarifiers in lieu of sedimentation
basins, and also additional chemical feed, mixing and aeration
facilities. More sophisticated chemical and pH monitoring and control
facilities are also included. This level of treatment would be
applicable to a major upgrade of existing BPT facilities or where a
mine was meeting BPT requirements without treatment facilities and
would chose this treatment system to comply with BAT limitations.
Level Four
filtration
This technology
This level consists of the addition of granular media
to one or more of the first three levels of treatment.
is depicted in Figure VIII-4.
Capital Costs
Capital cost estimates were prepared for each level of treatment, in
most cases for ranges between 0.02 and 9 million gallons per day
291
-------
(IF INSTALLED)
RAW
WATER
RAW WATER!
HOLDING
POND
LIME
FEED
(IF REQUIRED)
MIXER 8k/OR
AERATION
TANK
SETTLING
FACILITY
>EFFLUENT
SLUDGE
DEWATERING
OPTIONAL
SLUDGE/SEDIMENT
TO DISPOSAL
NOTE:
AERATION STEP NOT USED FOR WATERS
CONTAINING NON-FERROUS IRON.
Figure VIII-1
SCHEMATIC OF LEVEL 1 (BPT) FACILITIES
-------
NEW
POLY FEED
FACILITIES
RAW
WATER
ro
^D
UO
EXISTING
LIME
FEED
(IF REQUIRED)
(IF INSTALLED)
RAW WATER
HOLDING
POND
MIXER a/OR
AERATION
TANK
SETTLING
FACILITY
SLUDGE
DEWATERING
OPTIONAL
EFFLUENT
SLUDGE SEDIMENT
TO DISPOSAL
NOTE;
AERATION STEP NOT NORMALLY USED
FOR WASTE WATERS CONTAINING NON
FERROUS IRON.
Figure VIII-2
SCHEMATIC OF LEVEL 2 SYSTEM TO TREAT ACID DRAINAGE
-------
COAGULANT
EXISTING
CHEMICAL
FEED
FACILITIES
RAW WATER
POLY
FLOCCULATOR
CLARIFIER
PO
_^ILTRATE_
~TO LEVEL I
EQUALIZATION
(OPTIONAL)
DISCHARGE
SLUDGE
DEWATERING
OPTIONAL
Y
i
SLUDGE
TO DISPOSAL
I
I
I
i
SLUDGE
TO DISPOSAL
Figure VIII - 3
SCHEMATIC OF LEVEL 3 MINE WATER TREATMENT SYSTEM
-------
VJ)
RAW ^
WATE
R
E:
L
TRI
VMB
:
^
KISTIfy
EVEL
EATME
mmmm
4
i
r
SLUDG
DEWATER
OPTION
IG 1
piiLJ PUMPS
^-FILTRATE
Nu |^
AL 1
FILTER
1
t
r
** •
^ i
< 0 B;
' Q s
SMB
EFFLUENT
^CKWASH I
TORAGE 1
mmaBamfumm
BACKWASH 1
TREATMENT 1
1
1
_kj
i
SLUDGE
TO DISPOSAL
Figure VIII-4
SCHEMATIC OF LEVEL 4 - FILTRATION OF LEVEL 1 EFFLUENT ACID MINE WATER
-------
(mgd). These flows cover the range of more than 99 percent of active
discharging mines. The capital costs for each level of treatment
include the purchase and installation of all necessary equipment but,
in most cases, do not include land, power lines, access roads or
sludge disposal costs. These costs are presented separately. Level 1
has not been costed since it is assumed to be installed to meet the
BPT requirements. A 25 percent factor is included in the capital cost
curves to account for engineering, administration, and contingencies.
System Capital Cost for Level ^ Treatment
system provides for polymer addition
suspended solids in mine drainage (acid or
the mixing, storage and feeding of polymer
range of flow rates. Only two different
to cover the entire flow range of 0.02 to
capital costs for the treatment level 2
rates up to 0.75 mgd and $40,000 for flow
including an enclosure.
The level 2 treatment
as an aid in the removal of
alkaline). Equipment for
can be operated over a wide
polymer systems are required
4.5 mgd level (1). The
systems are $30,000 for flow
rates greater than 0.75 mgd
System Capital Costs for Level 3. Treatment. Figure VIII-3 presented a
schematic of the equipment included in the level 3 treatment system.
This system includes a pump station, mixing tanks, clarifiers, and a
control building. The capital costs are presented as a function of
flow rate in Figure VIII-5.
System Capital Costs for Level 4. Treatment. The equipment and
facilities comprising this treatment system are pump station, gravity
filters, backwash water storage tank, and control building. A
schematic diagram of this system was presented in Figure VIII-4. The
capital cost curve is shown in Figure VIII-6.
Land Requirements
The land requirements computed for treatment levels 3 and 4 are
presented in Figure VIII-7, The land required for level 2 should be
minimal and is included with the capital cost. Once the land area
that is needed from a particular treatment level is known, then this
value can be multiplied by the cost per acre at the site in question.
For the purposes of this report the cost per acre is assumed to be
$4,000.
Annual Costs
Level 2_. Table VIII-2 provides a breakdown of annual costs associated
with level 2 treatment system. By incorporating the appropriate
amortized capital cost and polymer cost, Figure VIII-8 was generated.
Level 3_. The annualized costs and energy requirements for level 3
treatment are computed in the same manner as those for level 2.
Polymer addition is also included in this treatment level and the
annualized cost and energy curves are presented in Figure VII1-9 with
a two mg/1 polymer dosage. In this treatment system, two operators
296
-------
Table VIII-2
BREAKDOWN OF ANNUALIZED COST FOR LEVEL 2 TREATMENT SYSTEM
1. Capital Recovery
Construction:
0.10608 x Cc
Mechanical:
0.16725 x Cc
TOTAL
2. Operating Personnel
3. Maintenance
(Materials & Supplies)
(S 3% of Capital Cost)
4. Chemicals
(€ $2/lb & 365 days/year)
(function of flow rate
and dosage)
5. Energy
(€ $0.03/kW-hr, 24 hr/d,
365 d/yr)
0.015-1.0 mgd
$ 500
3,200
$3,700
$9,000
$ 900
$91-46,000
$ 400
1.0-4.5 mgd
$ 900
5.100
$6,000
$9,000
$1,200
$6,000-274,000
$ 700
297
-------
Coat in Mllliona of Dollars
ro
VD
CO
n
o
en
H
o
*i
rt
r1
oo
MO
M
ID
I
cn
O
A O
to •
•9
5*
p
a
Ml
i i i 11 MM
1 l~l I 1111
I I I Milt I I i I • • ili
t I t I i l-ri
-------
Cost in Millions of Dollars
.
\D
r*
**J M
r M
H t-*
o
z
i_j y H*
HH-9
8
> M
WO £
»"~i r^ t 1
E™1 H
ZZJ •_. O^
i»3
en Z
CM
w
M
CO
r<
tr
A
CO
31
•
O
O
I I I I I I ll| . I I I I I I III
r i rniir
i i inii
i i i i 11 in
I I I I M I i
-------
UJ
o:
o
0.01
DESIGN FLOW IN M.G.D.
Figure VIII-7
MINE WATER TREATMENT SYSTEM
DESIGN FLOW VERSUS LAND AREA
REQUIREMENTS
300
-------
COST IN THOUSANDS OF DOLLARS
U)
o
3
3)
-n
5
^
V/A
3
P
o
ft
1
01
1
-------
10
I I II 111 (I I I I 1 I 11 II I I I I I I I
100
Cfl
i^
S
1
3
£
X
W
H
i.o
o.i
10
z
o
-J
M
£
5
K
z
u
1.0
Energy
.01
.01
I_ I 111 t I II l' I I I I M II ! I 1 I I! I L 0.1
0.1 1.0
DESIGN FLOW IK H.G.D.
10
Figure VII1-9
TREATMENT LEVEL 3 ANNUALIZED COSTS AND ENERGY
REQUIREMENTS VERSUS MINE DRAINAGE FLOWRATES
302
-------
per shift are assumed for flow rates up to 0.75 mgd; above
three shift operators are required.
0.75 mgd,
Level £. Annualized costs and energy requirements for level 4
treatment were estimated by the same process used for level 2 and are
presented in Figure VIII-10. Only one operator per shift is required
for this system.
New Sources
Four treatment levels were also established for new sources in the
mine drainage subcategory. These levels correspond closely to the
treatment levels under existing sources, with only minor modifications
in levels 3 and 4. As shown in Figure VIII-ll, level 3 for new
sources would include recycle of filtrate from sludge dewatering
equipment to the head of the treatment plant. Level 4 for new sources
is modified to include levels 1, 2, or 3, as shown in Figure VIII-12.
Capital Costs
The capital cost assumptions for new sources are identical to those
made for existing sources, with one major exception. New sources by
definition do not have any existing treatment installed, while
existing sources were assumed to have BPT or equivalent in place.
Therefore, new source capital (and annual) cost estimates must include
the cost of BPT facilities as well.
System Capital Costs for Level ±_ Treatment. The level 1 treatment
system provides for the construction of a sedimentation basin or
clarifier to remove suspended matter from mine drainage (acid and
alkaline). The capital costs for sedimentation ponds are presented in
Figure VIII-13, If lime feed equipment is required and the dosage
known, Figure VIII~14 can be used to determine the cost of installed
equipment.
System Capital Costs for Level 2_ Treatment. The level 2 treatment
system provides for the construction of a sedimentation basin for
polymer addition as an aid in the removal of suspended matter in mine
drainage (acid or alkaline). The capital costs for sedimentation
ponds are presented in Figure VII1-13. Since the sedimentation pond
sizing is based on the area storm runoff while the polymer addition
equipment is based on the dry weather flow, it is infeasible to
prepare cost curves of combined sedimentation basins and polymer
addition equipment costs. Therefore separate curves are presented.
The capital costs for the polymer addition systems are $30,000 for
flow rates up to 0.75 mgd and $40,000 for flow rates greater than 0.75
mgd including an enclosure.
System Capital Costs for Level 3_ Treatment. This system includes a
pump station, mixing tanks, clarifiers, and a control building. The
capital costs were presented as a function of flow rate in Figure
VIII-5.
303
-------
COST IN THOUSANDS OF DOLLARS
o
I
H
m
2
£
f 52
* ?
5 "
w >
M £
« £
s 5
H w
P3 O)
pa *fl
H* Z
H OQ O
gj C -t
> re z
•^ o
z < r-
m fc-4 C
z "-1 2
H M g
j> "-*
Z 0 M
£ 1-
^ §
^ 0
n ^
w <=>
fi H
c m
S "
w o
o
^)
£
***
tl
H
A
o
z 2
o
H
m
en
O
1
en
m
s
m
7
"n
5
$
—
2 °
O
»
s
I
\
I
\
^
I
\
\
\
v
\
\
^
\
v
\
s
s
v
\
V
\
\
\
\
\
\
-------
COAGULANT
UJ
O
Ul
CHEMICAL
FEED
FACILITIES
POLY
FLOCCULATOR-
CLARIFIER
RAW WATER
L« rlLI_nA.'.t.
SLUDGE
DEWATERING
OPTIONAL
SLUDGE
TO DISPOSAL
SLUDGE
TO DISPOSAL
DISCHARGE
Figure VIII-11
SCHEMATIC OF LEVEL 3 NSPS FACILITIES
-------
RAW
WATER
SEDIMENTATION
BASIN OR LEVEL
2 OR 3 TREATMENT
EFFLUENT
SLUDGE
TO DISPOSAL
F LTERS
BACKWASH
WATER
STORAGE
•^FILTRATE
SLUDGE
DEWATERING
OPTIONAL
BACKWASH
TREATMENT
Figure VIII-12
SCHEMATIC OF LEVEL 4 NSPS FACILITIES
-------
THOUSAND OF DOLLARS
o
o
ro
O
o
I
"n
m
m
H
O
-n
fc.
\
O
O
m
\
ro
ro
ro
-------
COST IN THOUSAND OF DOLLARS
R
<
PJ
Z
PI
H W
t-3C
r H
PI
cs ?o
o
WH
n§
CH
5C 2k
PI Z
WH
2
c
03
c
n>
i
H*
*^
-------
System Capital Costs for Level 4 Treatment. The equipment and
facilities comprising this treatment system are pump station, gravity
filters, backwash water storage tank, and control building. A
schematic diagram of this system was presented in Figure VII1-4. The
capital cost curve was shown in Figure VII1-6. This level of
treatment must be applied after either a sedimentation basin alone, or
after level 3 treatment. If the total cost for this system is
required the costs from Figure VIII-6 should be combined with costs
for the appropriate sedimentation basin or the level 3 costs.
Land Requirements
The land requirements for levels 3 and 4 were presented in Figure
VIII-7. An insignificant amount of land is required for level 2.
Annual Costs
Level 1_. The annual costs for level 1 are composed of sedimentation
basin annual costs from Figure VIII-15, lime feeding for pH adjustment
from Figure VIII-16 if required and sludge dewatering from Figure
VIII-17 if this is installed.
Level 2_. The annual costs
presented in Figure VIII-8.
for level 2, polymer addition, were
Level ,3. The annual costs for level 3 were presented in Figure VIII-
9.
Level £. The annual costs for level 4 were presented in Figure VIII-
10.
PREPARATION PLANTS AND ASSOCIATED AREAS
Existing Sources
Water discharged from coal preparation plants and their immediate
areas originates from two sources: (1) preparation plant process
wastewater (PP) and (2) wastewater generated in the vicinity of the
plant facilities, from coal storage areas, and from refuse disposal
areas (Associated Area Runoff (AA)).
These discharges are disposed of in various methods depending on the
specific site under consideration. For instance, the flows could be
segregated or commingled. The preparation plant water circuit could
be once-through or with partial or total recycle of process
wastewaters. Various systems have been costed in an attempt to cover
309
-------
THOUSAND OF DOLLARS
U)
M
O
ro
O
O
30
m
<0
3*
m
H
O _
> OD
m
10
ro
Ni
-------
10000
LO
a:
giooo
a
z
<
to
D
o
H
2 100
10
O
O
10
OOI
I 10
WASTEWATER FLOW-MOD
IOO
IOOO
Figure VIII-16
LEVEL 1 MINE WASTEWATER TREATMENT pH ADJUSTMENT
ANNUAL COST CURVES
-------
LO
CO
CC
•*
o
o
u.
o
en
a
O)
O
t-
z
CO
O
o
1.000
100
IO.O
100
SOLIDS (DRV) IN 1.000 POUNDS/HR
Figure VIII-17
WASTEWATER TREATMENT VACUUM FILTRATION
SLUDGE DEWATERING FACILITIES CAPITAL COST CURVET
-------
each of the water handling options (3).
discussed below.
These options and systems ;are
Zero Discharge of Preparation Plant Water Circuit
Three systems were identified for existing sources to achieve total
recycle of preparation plant process wastewater (also termed "zero
discharge").
System ]_. This system, shown in Figure VIII-18, assumes that a pond
system is installed, the preparation plant presently has from 0 to TOO
percent recycle, and the associated area storm runoff enters the
preparation plant water circuit. In this case, the existing
sedimentation basin would require dikes to divert the associated area
runoff to a new sedimentation pond designed to contain the volume of
runoff from a 10-year, 24-hour storm and also diversion of the
undisturbed area runoff around the associated area.
System 2_. This system assumes that preparation plant wastewater and
associated area runoff are segregated for treatment. A clarifier is
installed to treat the preparation plant wastewater. Recycle from the
clarifier overflow to the preparation plant can vary from 0 to 100
percent. A sedimentation pond is assumed to be in place which
receives only associated area runoff and possibly some undisturbed
area runoff. Figure VIII-19 is a schematic of this system.
System 3_. This system, shown in Figure VIII-20, assumes a clarifier
is installed to treat preparation plant wastewater. The clarifier
discharge and associated area runoff presently are combined and routed
to an existing pond for treatment. Recycle from the pond can vary
from 0 to 100 percent. Modifications would include the elimination of
the pond from the preparation plant water circuit by installing a new
pump station to route 100 percent of the clarifier overflow to the
preparation plant. The pond would, however, continue to provide
treatment for the associated area runoff.
Allowable Discharge from the Preparation Plant Water Circuit
Since this configuration is currently the option selected by
plants, only one system was identified for costing purposes.
most
System 4_. This scenario assumes an allowable discharge from the
preparation plant water circuit. Preparation plant waters may or may
not be recycled. Figure VIII-21 is a schematic of this system showing
the preparation plant discharge treated first in either a
sedimentation basin or a clarifier and then by filtration. Associated
area runoff is shown as being treated separately, however, it may be
commingled.
Capital Costs
Cost estimates were prepared for the components for each of the
preparation plant flow configurations. These costs were then plotted
313
-------
U)
t->
4=-
NEW DIKES TO DIVERT
ASSOCIATED AREA
RUNOFF TO NEW
SEDIMENTATION
POND
EXISTING
ASSOCIATED
AREA
RUNOFF
EXISTING
PREP
PLANT
NEW
SEDIMENTATION
POND
T0
EXISTING StJURRY
POND®
DISCHARG
DIVERSION DITCHES TO SEGREGATE
UNDISTURBED AREA RUNOFF
"0" DISCHARGE
NEW OR
EXPANDED
PUMP
STATION
MAKEUP
LEGEND
EXISTING FACILITIES
PROPOSED
II
+++++ ABANDONED »
Figure VIII-1&
EXISTING PREPARATION PLANT - SYSTEM 1 WATER CIRCUITS - ZERO DISCHARGE
-------
U)
H1
U1
EXISTING
PREP.
PLANT
EXISTING
CLARIFIER
SLUDGE CAKE
TO LAND FILL
r
MAKEUP
NEW OR
EXPANDED
PUMP
STATION
O" fclSCHARGE
ASSOCIATED
AREA —
RUNOFF
SEDIMENTATION /
BASIN
LEGEND
TO
DISCHARGE
EXISTING FACILITIES
PROPOSED »
ABANDONED «
Figure VIII-19
SYSTEM 2 - EXISTING PREPARATION fLANT WATER CIRCUITS
-------
LO
EXISTING
PREP
PLANT
WATER SOURCE
SLUDGE CAKE
TO LAND FILL
NEW
PUMP
STATION
* f A
ASSOCIATED
AREA
TO
DISCHARGE
EXISTING \
SEDIMENTATION \
POND >
LEGEND
EXISTING FACILITIES
PROPOSED »
w,w ABANDONED *
r+*
Figure VIII-20
SYSTEM 3 - EXISTING PREPARATION PLANT WATER CIRCUITS
-------
uo
t-1
-a
POLYMER
FEED
POLYMER
FEED
1
ASSOCIATED
AREA ~
RUNOFF
UNDISTURBED _
AREA
SLUDGE CAKE
TO LAND FILL
EXISTING
PREP.
PLANT
EXISTING
SLURRY
POND
PROPOSED DIKE
| FILTRATION} > TO.DISCHARGE
| FILTRATION] > TO DISCHARGE
EXISTING CLARIFIER
LEGEND
EXISTING FACILITIES
PROPOSED »
w* ABANDONED «
i> TO DISCHARGE
EXISTING
SEDIMENTATION >
POND /
Figure VIII-21
SYSTEM 4 - EXISTING PREPARATION PLANT - ALLOWABLE DISCHARGE
-------
with flow rate or, in the case of storm runoff, with runoff volume.
The expected cost for each component includes the purchase and
installation of all necessary equipment but does not include
installation of power lines or access roads assumed to be in place at
existing preparation plants, but needed for new sources. Since the
total capital cost is very site-specific, the component costs are
presented so that if the parameters of a specific site are known the
total system can be costed using the appropriate component costs.
System K The items that may require costing for this system,
depending on the particular site in question, include:
Sedimentation basin-diking,
Associated area drainage ditch construction,
Recycle pump station,
Polymer feed system,
Sedimentation basins.
Knowing the size and configuration of the sedimentation basin will
allow the determination of the length of diking required. With this
known, Figure VHI-22 can be used to determine the cost. The
associated area dimensions would then be used to determine the length
of drainage ditches required to segregate the undisturbed area runoff
from the associated area. Figure VIII-23 is used to determine the
cost of the ditches required. Figure VIII-13 is used to determine the
cost of the sedimentation basin required to serve the associated area
and Figure VIII-24 is used to determine the cost of a new recycle pump
station. If there is a flow from the associated area during dry
weather, a polymer addition system may be required so that the
effluent will meet guidelines. A cost of $30,000 is estimated for
flows less than 750,000 gpd and $40,000 for flow rates greater than
750,000 gpd, including an enclosure.
System 2.. The items that may require costing for this system,
depending on the particular site in question, include:
Clarifier underflow dewatering
Recycle pump station
It is assumed that the existing associated area sedimentation basin
will not require augmentation. Figure VIII-24 is again used to
determine the cost of pumping facilities. The sludge dewatering
capital cost can be determined from Figure V1II-17. The vacuum filter
loading rate (based on vendor design criteria) is 50 pounds/hr/ft2.
Assuming the flow rate and slurry concentration at a particular
preparation plant is known, the proper size filter can then be
determined. As an example, for a vacuum filter influent suspended
solids concentration of 100,000 mg/1 (10 percent), and a flow of 250
gpm, the solids level in pounds per hour would be calculated using the
following formula:
S <= C x F X D X T
10*
318
-------
or
o
o
ti.
o
CO
o
(O
O
X.
I-
co
o
o
I/W
\\J\J
W.
1.
r
0.1-
ii
NOT
!'
/
/
f
f
s
f
V
/
/
x
'
(
^
/
t
/
/
/
4
•X
-^
— V
S
/
/
/
^
/
J
y^
y
Jr
y
/
/^
y
jr
/
/
/
|
i .
;
/
^
i
DO 1,000 IQPOO 100,000
LINEAR FEET
E:
CAN BE USED TO SEGREGATE UNDISTURBED
AREA FROM ASSOCIATED AREA OR ASSOCIA-
TED AREA FROM PREPARATION PLANT FLOW.
Figure VIII-22
COAL MINE PREPARATION PLANT WASTEWATER TREATMENT
EARTH DIKE FOR RUNOFF CONTROL CAPITAL COST CURVE
319
-------
ru
o
a>
H
CAN BE USED TO SEGREGATE UNDISTURBED
AREA FROM ASSOCIATED AREA OR ASSOCIATED
AREA FROM PREPARATION PLANT FLOW.
z UUDI IN IHUUSMNUS UF UUUUAKO
0 _ ?
m _8 - 5 8 S
•• 8
r
"Z.
m
m
o
"n
o
H
og
o
Q
\
\
k
\
\
x
s_
x
X
x
x
V
~
^
S_
x
x
x
>
\
SK
^
^
^
s
s
*
s
^
x
x
, .. X
-------
CO
cr
o
o
u.
o
CO
o
n
-J
i
o
0.01
0.1 1.0
WASTEWATER FLOW - M G
10.0
Figure VIII-24
COAL MINE PREPARATION PLANT WASTEWATER TREATMENT
RECYCLE/MAKE-UP WATER PUMPING FACILITY CAPITAL COST CURVE
321
-------
where C * concentration of suspended solids in mg/1
F = flow in gpm
D = 8.34 Ibs/gallon
T - time * 60 minutes.
For the example stated:
S - 12,510 Ibs per hour.
Using Figure VIII-17, the cost would be approximately $250,000.
System 3_, The items that may be required for this system, depending
on the particular site in question, include:
Sludge dewatering
Recycle pump station
It is assumed that the associated area sedimentation basin design will
not require augmentation. Figure VII1-17 can be used to determine the
cost of dewatering clarifier sludge. Figure VIII-24 can be used to
determine the cost of a recycle pump station.
System 4. The items that may be required for the system, depending on
the particular site in question, include:
Sedimentation basin-diking
Sludge dewatering
Polymer feed and granular media filtration.
This system assumes an allowable discharge from the preparation plant
without recycle using either existing sedimentation basins or
clarifiers. The sludge dewatering cost, if required, can be obtained
from Figure VIII-17. In order to meet effluent limitations, a polymer
feed may be required before the preparation plant slurry pond or the
clarifier. The capital cost for polymer feed equipment is $30,000 for
flows up to 750,000 gpd and $40,000 for flows over 750,000 gpd. If
filtration is required to meet effluent limitations its cost can be
found in Figure VIII-6.
Annual Costs
Since the components for the various systems described above and the
annual costs to operate and amortize these components are the same,
the annual costs are presented only once. Once the need for a
component in a particular system is determined, the annual cost is
derived from the following Figures: VIII-25; Annual Costs of Dikes and
Ditches, VIII-26; Annual Costs of Recycle Pump Station, VIII-27 Annual
Costs of Sludge Dewatering Facilities, VI11-15; Annual Costs of
Sedimentation Ponds, VIII-28; Annual Costs of Clarifier and Pump
322
-------
COST IN THOUSANDS OF DOLLARS
ua
ro
uo
ft
t-3
M
m
OR H-
2 2 OQ
OPl fl»
CjO I
hP K
w
00
M
025
O
M
H
O
w-
r
2
m
•n
m
m
H
o
o
o
o
o
o
"o
o
p
b
o
o
O
O
b
8
-------
1.0
UJ
to
-t=-
CO
or
_
o
o
u_
o
5
(O
O
o
O.I
o.ot
O.OI
O.I 1.0
WASTEWATER FLOW -MOD
IO.O
Figure VIII-26
WASTEWATER TREATMENT RECYCLE/MAKE-UP WATER
PUMPING FACILITIES ANNUAL COST CURVE
-------
uo
to
(n
0:
_
o
o
U-
O
o
CA
^
O
X
cn
o
o
100
ANNUAL COST—v
100
SOLIDS (DRY) IN 1,000 POUNDS/HOUR
Figure VIII-27
WASTEWATER TREATMENT SLUDGE DEWATERING FACILITIES
ANNUAL COST CURVE
-------
ANNUAL COST IN THOUSANDS OF DOLLARS
W
8
OH
cm
D
*0
I
M
m
i
m
o
I
G>
O
ANNUAL ENERGY COST IN
THOUSANDS OF DOLLARS
-------
Station. All the component annual costs are additive for a given
system.
New Sources
Zero Discharge from Preparation Plant Water Circuit
System ]_. This system assumes a new source using a pond to treat the
preparation plant discharge prior to 100 percent recycle. A separate
pond designed to contain the runoff from a 10-year, 24-hour storm
would be used for associated area runoff. The associated area and
pond would be ditched to divert an undisturbed area runoff from
associated area runoff. Figure VIII-29 is a schematic of this system.
System £. This system assumes a new source using a clarifier to treat
the preparation plant discharge prior to 100 percent recycle. A
separate pond designed to contain the runoff from a 10-year, 24-hour
storm would be used for associated area runoff. The associated area
and pond would be ditched to divert undisturbed area runoff from
associated area runoff. Figure VIII-30 is a schematic of this system.
Capital Costs
System 1_. This system, as shown in Figure VIII-29, is applied to new
sites where all treatment facilities are constructed when the
preparation plant is constructed. A slurry pond for the preparation
plant wastewater would be installed and a pump station for TOO percent
recycle of the treated water required. Associated area runoff would
be segregated from the undisturbed area. The items required for this
system include Figures: VII1-13 & VII1-22; Preparation Plant Slurry
Pond with Dikes, VIII-24; Recycle pump Station, VIII-23; Associated
Area Segregation by Ditch and VIII-13; Pond for Associated Area
Runoff. The figure numbers next to the items can be used to determine
the capital costs.
System 2_. This system, as shown in Figure VIII-30, is applied to new
sites when a clarifier is used to treat the preparation plant
discharge. The items required for this system include Figures:
VIII-31; Clarifier, VIII-17; Sludge Dewatering, VIII-24; Recycle Pump
Station, VIII-23; Associated Area Segregation from Undisturbed Area by
Ditch, and VIII-13 and VIII-22; Pond Associated Area Runoff. The
figure numbers next to the items can be used to determine the capital
costs.
Annual Costs
For both new source systems, the annual costs can be derived from the
same annual cost curves presented for existing sources.
327
-------
NEW
PREP.
PLANT
POLYMER
IF
ro
CD
SLUDGE DISPOSAL
SLURRY
POND
WATER SOURCE
MAKEUP WATER
REQUI
ASSOCIATED
AREA
RUNOFF
i
RED SLUI
DISPC
A
* ^.
DGE
)SAL
k
/
PUMP STA
*
TO
DISCHARGE
DITCHES TO DIVERT
UNDISTURBED AREA
RUNOFF
Figure VIII-29
SYSTEM I - NEW SOURCE WATER CIRCUITS
-------
u>
ro
— DIVERSION DITCHES
TO SEGREGATE
UNDISTURBED AREA RUNOFF
POLYMER
IF
REQUIRED
ASSOCIATED
AREA
RUNOFF
NEW
PREP.
PLANT
,,1
UJ
5
OH
5
u.
SLUDGE CAKE
TO LAND FILL
NEW PUMP
STATION
NEW CLARIFIER
SLUDGE TO
DISPOSAL
POND
s
WATER SOURCE
MAKEUP WATER
PUMP STATION
TO DISCHARGE
Figure VIII - 30
SYSTEM 2 - NEW SOURCE WATER CIRCUITS
-------
0££
COST IN THOUSANDS OF DOLLARS
>
2
O
c*
S>
*S3
Si
«5
3>S
£*
11
TO 3
W A
$3
S"
^?c
?s
" M
Q2
SS
o
c
73
<
P5
»«1
H.
00
C
*
ft
<
M
M
tH
to
h^
-------
POST MtHIRfi DISCHARGES
Operation and maintenance costs to treat post mining discharges
through bond release are presented in this section. (Note: this
treatment is already required by OSM. )
on-s' Use'd
In determining the treatment costs, five assumptions were made:
1. No capital charges are included. It is assumed facilities
are fully depreciated by the time of mine closure.
2. No "typical" pond size could be assumed. Ponds range from
"no pond" to 21 acre-feet in storage.
3. A "typical" lime dosage is 300 mg/1.
4. Operation and maintenance and energy costs for lime feeding
•are not sensitive to lime dosage rates are assumed constant.
5, Sludge pumping energy costs are less than five percent of
the total operation and maintenance costs.
Therefore, energy costs for varying sludge rates are masked by the
total operation and maintenance costs.
Re'cTaniati'o'rt Areas'
These costs apply only to surface mines. The costs include
sedimentation structures for treating the runoff from areas under
reclamation through release from the applicable reclamation bond. For
this subcategory, treatment is for the control of settleable solids
and pH.
Assumpti ons
In determining the treatment costs, two assumptions were necessary:
1.. Since limitations for active mining are based on treatment
pond technology and facilities can leave the pond in-place, no capital
costs result from these requirements.
2. Lime for pH control should not be required for discharge
systems covered in the reel am at ion phase si nee no acid wastewater
should be formed at these facilities.
Again, this has been verified by an Agency study of reclamation areas.
Operation and Maintenance Costs
331
-------
The costs associated with areas under reclamation include operation
and maintenance costs for sedimentation ponds and maintenance costs
for runoff control with earth dikes or drainage ditches. The cost
curves for these areas are identical to figures previously presented,
but are repeated here for convenience. Figure VI11-32 presents
operation and maintenance costs for sedimentation ponds. The capital
cost of the pond was found in Figure VIII-13. The maintenance costs
for runoff control with earth dikes or drainage ditches are given in
Figure VI11-33. Supporting information and assumptions for developing
these figures may be obtained in Appendix A to the Proposed Coal
Mining Development Document (EPA 440/1-81/057-b).
Alkaline Underground Mines
Only settling ponds are considered for costing. No clarifiers have
been included because few alkaline deep mines employ clarifiers for
wastewater treatment. The annual operation and maintenance cost curve
for wastewater treatment with settling ponds was presented in Figure
VIII-32. The annual maintenance cost curve for earth dike or drainage
ditch runoff control was illustrated in Figure VIII-33. Supporting
information and assumptions for developing these figures may be found
in Appendix A to the Proposed Coal Mining Development Document.
Acid Underground Mines
Two treatment systems are considered for costing. The first system
includes settling ponds, lime addition equipment, and aeration
equipment. The second system includes clarifiers, lime addition
equipment, and aeration equipment.
Costs Associated with Both Settling Pond and Clarifier.
The annual costs associated with both systems may be obtained from
Figures VIII-34, VIII-35, and VIII-36. Included in the cost curves of
Figure VIII-36 is the cost of hydrated lime at $65 per ton.
Supporting information and assumptions for developing these figures
may be found in Appendix A.
Costs Associated Only with the Settling Pond System.
Operation and maintenance costs were illustrated in Figures VIII-32
and VIII-33. The total operation and maintenance costs for the
sedimentation pond system (including sedimentation ponds, 1ime
addition and aeration) are determined by adding the costs from Figures
VIII-32 and VIII-33 to the costs obtained from Figures VIII-34, VIII-
35, and VIII-36.
Cost Associated Only with the Clarifier System.
The clarifier and sludge pumping operation and maintenance costs are
presented in Figure VII1-37. To obtain the total operation and
maintenance costs for the clarifier system (including clarifiers, lime
332
-------
COST IN DOLLARS
U)
U)
U)
OH
0>
3 *,
rt 55 H-
O 00
OP
cn
H
10
O *
Z OJ
10
M
CO
O
(A
3)
g
m
"
o u>
m
o
31
m
m
N
8
o
8
Ol
8
o
fit
8
o
-------
COST IN THOUSANDS OF DOLLARS
z
z
SO *"•
ez
o w
O W
o
at —
M W
0 =
nw
era
c
(0
-------
COST IN THOUSAND DOLLARS/YEAR
to
LO
Ul
oo
TO GO
o
cz a
33: "— «
en O oo
-a •SL •—•
o m 3
=2: m
O 30
oo o >
•— • o
o o o
o > — <
f— Co o
m m cz
oo i—
-H
m o
—i —i
rn r>
z cz
s: rn
•—• oo
a>
oo
o
m
o
P
b
-------
en 10,000
cc
<
_i
o
a
z
u>
O
o 1000
tnn
_^
-X"^
X
^
.^
^
08tM
it
/
/
i*
«
COST-
_rf
X1
"\
\
X
\_
s
X]
EN
/
EF
X
(G
/
Y
j
/
C
•*
;c
y
I?
s
s
)ST
/
jA
/
/
l^
x
F
k*
./
O.I
I.O IO.O
DESIGN FLOW IN M.G.D.
100.0
Figure VIII-35
POST MINING DISCHARGE LIME FEED FACILITIES OPERATION AND
MAINTENANCE ANNUAL COST CURVES FOR UNDERGROUND COAL MINE
ACID WASTEWATER TREATMENT WITH
SEDIMENTATION PONDS OR CLARIFIERS
336
-------
100,0
DOLLARS
P
o
THOUSANDS
COST
r-
o
0.1
X /
M/A
?
IXT. I i
1.0 10.0
DESIGN FLOW IN MGD
too.o
Figure VIII-36
POST MINING DISCHARGE AERATION OPERATION
AND MAINTENANCE ANNUAL COST CURVE FOR UNDERGROUND COAL
MINE ACID WASTEWATER TREATMENT WITH SEDIMENTATION PONDS
OR CLARIFIERS
337
-------
100,000
CO
or
o
D
en
O
o
z
Z
10,000
1,000
O.I
1.0
10.0
100.0
DESIGN FLOW IN MOD
Figure VIII-37
AFTER MINE CLOSURE CLARIFIER MECHANISM AND
SLUDGE PUMPING OPERATION AND MAINTENANCE
ANNUAL COST CURVE FOR UNDERGROUND .COAL MINE
ACID WASTEWATER TREATMENT WITH CLARIFIERS
338
-------
COST IN THOUSANDS DOLLARS
U)
B
O
MM»TJ
0=50
M055
iws
^
n OQ
o jad (ft
wo
HJHO>
i-i eH
WC?ci?0
WH<>
WHMH
PC H
rqO
W O2J
W?«
o o
MC; »tj
g2m
Ho j*j
M0!2
o S
a
»d
oo
ap
O
rn
-n
2
o
o
-------
100,000
o
o
tn
O
u
D
Z
Z
<
10,000
1,000
0.1
1.0
10.0
100.0
DESIGN FLOW IN MGO
Figure VIII-37
AFTER MINE CLOSURE CLARIFIER MECHANISM AND
SLUDGE PUMPING OPERATION AND MAINTENANCE
ANNUAL COST CURVE FOR UNDERGROUND .COAL MINE
ACID WASTEWATER TREATMENT WITH CLARIFIERS
338
-------
addition, and aeration), add the costs from Figure VIII-37
costs obtained from Figures VIII-34, VIII-35, and VIII-36.
to the
GENERAL ASSUMPTIONS UNDERLYING CAPITAL COSTS FOR ALL SUBCATEGORIES
Building Costs
Buildings will be required to house chemical and polymer feed
equipment, as well as the controls for the treatment systems. The
cost estimates were prepared by including various subcategories, i.e.,
costs for concrete, superstructure, plumbing, sanitation, and
lighting. The electrical and control panel costs as well as
laboratory facilities and office equipment are included in the
building costs. These costs are included in the capital
for each of the treatment levels.
Piping
cost curves
The type of piping costed for each treatment system is carbon steel.
Pipe diameters were sized based on six to seven feet per second flow
velocity. The costs for piping were based on up-to-date pipe cost
quotations and a factor of 100 percent was added to this cost to
account for fittings, flanges, hangers, excavation, and backfilling as
required.
Electrical and Instrumentation
The electrical and instrumentation costs for the treatment levels were
estimated at 30 percent of the cost of the applicable equipment.
Power Supply for Mine Water Treatment
Operation of the equipment associated with the three candidate levels
of BAT treatment may require additional electric power at the site.
This power can be supplied by either running a power line from an
accessible trunk line or power source, or by using diesel powered
generator units. tThe worst case would probably be to run a high
voltage trunk line from a generating facility long distances to the
wastewater treatment facility. In addition to the capital cost for
power line construction, associated costs for metering, transformers
and secondary lines would be required.
In order to provide information on the costs for running power lines,
two supply voltage levels were assumed: 480 volts and 4.16 kilovolts.
It was then assumed that the practical breakpoint on transmission
distance would be between 500 to 1,000 feet for 480 volts. Distances
approaching 1,000 feet and longer would require a feeder of 4.16 kV.
339
-------
Table VII1-3 has been prepared to present approximate cost for power
lines. If the distance from the source and user and the load in
kilowatts (kW) is known, the table can be used to obtain the power
line costs. These prices include installation, poles, wire,
insulators and crossarms for 480 volts and also includes a power
center at the user containing a high voltage incoming section with
necessary protection disconnecting devices, transformer (4.16 KV/480V)
and secondary side circuit breaker.
In cases where trunk or secondary lines are not readily available, it
may be advantageous to operate diesel engine generator units. The
range of approximate power requirements for the three candidate levels
of BAT is from 5 kw at the lowest flow rate, level 2, to 150 kw for
the highest flow rate, level 4. An economic tradeoff exists between
the relatively low capital cost for a diesel unit and the relatively
low maintenance and operating costs of a long distance trunk line
system. Table VIII-4 provides cost estimates for diesel generator
units for a range of power requirements. The costs presented in Table
VIII-4 include an ICC approved weather-housed trailer with controls,
cables, battery muffler system, alternator, control panel, silencer,
diesel engine, and generator. Capital costs for electric power supply
do not include land requirements and are not included in the capital
cost curves presented for the various treatment levels, due to the
highly site-specific nature of these costs, No extensive power
requirements are necessary at the preparation plants since power is
already available for production equipment.
Land
Additional land may have to be purchased in order to comply with
BAT/NSPS. This cost is difficult to estimate on a general basis since
the information received during the mine visits indicated that the
cost can vary from a few hundred dollars to $40,000 per acre. If
additional land is required, land costs must be added to the capital
cost obtained from the treatment level system curves. The amount of
land needed for proposed BAT alternatives is presented on an
individual equipment basis for each level of treatment suggested (1).
A value of $4,000 per acre is assumed to be a reasonable cost because
it is a representative cost of land in a rural location in the
midwest.
Equipment
The equipment costs included in this subsection are for polymer
addition equipment, pump stations, mixing tanks, clarifiers, gravity
filters, and water storage tanks. This encompasses equipment required
for all three treatment levels. Cost estimates for installation,
engineering, administration, and contingencies are also included.
Polymer Addition Equipment. Capital costs of polymer addition
equipment are relatively insensitive to mine drainage flow rates
according to vendor price quotations. Below 750,000 gpd the installed
capital cost was estimated at $30,000 and above 750,000 gpd the cost
340
-------
Table VIII-3
COST OF OVERHEAD ELECTRICAL DISTRIBUTION SYSTEMS
480V System
Distance
ft
250
500
Distance
ft
1000
1500
2000
2500
3000
3500
4000
4500
5000
100
$1500
$3200
100
$19,000
$20,400
$22,000
$23,500
$25,000
$26,600
$28,000
$29,800
$31,300
L 0
200
$1900
$4900
L
200
$19,000
$20,400
$22,000
$23,500
$25,000
$27,700
$29,400
$31,200
$32,900
A D - K
300
$2100
$5500
4.16 KV
0 A D -
300
$20,000
$21,400
$23,000
$25,300
$26,000
$28,700
$32,400
$34,400
$36,400
w
400
$2500
$6700
System
K W
400
$23,000
$25,000
$26,600
$29,600
$31,500
$36,300
$38,600
$41,000
$49,700
500
$3100
*
500
$23,000
$25,000
$25,600
$29,600
$31,500
$36,300
$38,600
$41,000
$49,700
Notes
*Voltage drop
excessive
Notes
Power center
costs included
it 11
it n
it n
n it
ii ii
M u
ti u
n n
Reference (2)
-------
Table VIII-4
CAPITAL COSTS FOR DIESEL GENERATOR SETS
Generator Type
Air-Cooled
Air-Cooled
Power Requirement (Kw)
10
30
Cost (1000$)
11
16
Radiator-Cooled
Radiator-Cooled
Radiator-Cooled
55
100
150
20
24
30
Reference (4)
342
-------
estimate was $40,000. These costs include a mixing tank, feed pump,
transfer pump, storage tank, an enclosure, and an electric heater.
Costs for the enclosure and heater were additional to those given by
the vendors of the polymer equipment. The costs for these two items
were estimated at $10,000 for the enclosure and $6,000 for the heater.
Pump Stations. Installed capital costs for pump stations include a
3/8 inch steel structure, pumps and motors, piping, valves, fittings,
structural steel (stairwells, ladders, ancillary equipment),
electrical equipment and instrumentation. Two pumps were assumed for
all flow rates up to 3,0 mgd; above this flow rate three pumps were
used.
Mixing Tanks. The cost for the mixing tanks used in level 3 includes
three steel tanks and skids, three mixers, nine slide gates,
structural steel, aeration systems (blowers and piping), electrical
equipment, and instrumentation.
Flocculator-Clarifiers. A flocculator-clarifier composed of a steel
tank (1/4 inch thick) in concrete base, the internal flocculation and
sludge scraping mechanisms, structural steel, slide gates, sludge
pumps and motors, electrical equipment and instrumentation.
Gravity Granular Media Filters. The equipment included with gravity
filters is composed of a concrete pad, a backwash water storage tank,
piping connections, filter cells, media, underdrain system, electrical
equipment and instrumentation. The filters were sized based on a flux
rate of 10 gpm/ft*.
Installation. Installation is defined here to include all services,
activities, and materials required to implement the described
wastewater treatment systems. Many factors affect the magnitude of
this cost including wage rates, in-house or contracted construction
work and site dependent conditions. The installation costs are
included in capital cost estimates presented in this section.
Engineering, Administration and Contingencies. The costs associated
with taxes, insurance, engineering, administration, and contingencies
are computed as 25 percent of the installed cost of facilities and
equipment.
GENERAL ASSUMPTIONS UNDERLYING ANNUAL COSTS FOR ALL SUBCATEGORIES
The annual costs computed for each of the treatment systems
for BAT are categorized as follows:
Amortization
suggested
343
-------
Operation and Maintenance
Labor
Materials and Supplies
Chemical s
Energy
The annual depreciation and capital costs are computed based on using
the capital recovery factor:
AC = (II){CRF)
where
AC = annual cost
II - initial investment
CRF = capital recovery factor = (r) "{ 1 +r)/( (1 +r)n -1)
r = annual interest rate
n s useful life in years.
An interest rate of 10 percent was used in all cases. The expected
life differs for civil construction work and mechanical and electrical
equipment items and their installation, i.e., the expected life for
civil construction work is 30 years and 10 years for installed
mechanical and electrical equipment. No residual or salvage value is
assumed. Based on these assumptions, the general multipliers (AC/II)
compute as f ol lows :
CRF (civil)3fj * 0.10608
* * 1^ v
CRF (mech. & elec.JlO = 0-16275
Qpiertftfdri a'rftf Ma'i'nte'riaric^
=?h'e'r'a'T. Operating time of the systems costed is assumed to be for 24
hours per day, 365 days per year.
OpeYtfti n^ a'h'd Ma'f nt'enah'ce1 Pers'o'nne'T. Personnel costs are based on an
a n n u a~l F?te of $28,000.
Mai'rite'nan'c'e* flat'e'ri tfl'S. The materials necessary for performing yearly
maintenance acti vltles are estimated at three percent of the capital
cost of the facilities including the contingency item.
Cftgfrtfc'a'Ts. The chemicals costed for use in any of the levels of
treatment are polymer and lime. The polymer cost is estimated at
$2.00 per pound, lime estimated at $65/ton. Yearly costs will vary
according to the dosage level used in the treatment system. A polymer
-------
dosage rate of two mg/1 was selected for computing annual polymer
costs in each applicable system.
Power Costs. Electricity costs are based on auxiliary power
requirements in terms of kilowatts and 8,760 hours per year of
operation. The cost per kilowatt hour is estimated at $0.03 (2).
SLUDGE HANDLING AND ASSOCIATED COSTS
The sludge produced in the treatment of mine drainage, preparation
plant effluent and pond sedimentation can be handled by various
methods. Three methods which may be used and are considered in this
report are: sludge lagoons, trucking of dewatered sludge to disposal
site and trucking of undewatered sludge to disposal site.
Sludge Lagoons
The sludge lagoon would require construction of a lagoon and pumping
the sludge from the treatment facility to the lagoon. Available data
for lime neutralization indicates that sludge production is about 10
percent by volume of the incoming flow (solids concentration of two
percent) (1). This sludge would compact in a lagoon to 10 percent
solids which equates to three percent by volume of the incoming flow
treated. To arrive at a cost it is assumed that the sludge storage
requirements would be for an estimated 10 year life of the mine. The
cost curves for capital and yearly cost for the sludge lagooning
approach are shown in Figure VIII-38.
Haulage of. Dewatered Sludge
The method of dewatering sludge considered here consists of pumping
the sludge to a thickener. The thickened sludge is then dewatered by
vacuum filters before hauling to disposal. It is assumed that this
system will increase the solids loading in the sludge to about 25
percent. The cost curves for capital and yearly costs, as well as
energy requirements for this dewatering, are shown in Figure VIII-39.
The. estimated cost for hauling dewatered sludge to disposal sites,
based on a one round trip mile, is presented in Figure VIII-40. To
maintain a uniform cost basis, this curve is a plot of design flow in
mgd versus cost in thousands of dollars.
Haulage of. Undewatered Sludge
The final sludge handling approach is to haul the sludge to disposal
sites without dewatering. This involved pumping the sludge at about
two percent solids to a tank truck and then hauling to a disposal site
where it is lagooned or pumped into a bore hole. The trucking cost
-------
COST IN MILLIONS OF DOLLARS
Ui
-fc-
O\
(A
rr
8»»J
a **•
§32?
tt
U>
Co
O
§
I » HIM I I I * Mill I I I * »lll| * I I I Illl
^ I l I I I 1+
-------
COST IN MILLIONS OF DOLLARS
LO
in
a
a
o
w
otn
w si
00
mo s n>
2 >
O jxJ M
•-< t/1 H M
G M i
o cn w v>
C3 3> vO
C/lM
o9
O
P
b
ENERGY IN MILLION Kw-hr./yr
-------
COST IN THOUSAND DOLLARS/YEAR
uo
-Cr
Co
HIM n
53 O
CO
H-
O OQ
MES
O fl>
W <
H
1
HCO O
> O O
HO
S3 Hi Hi
HgnJ
OM
s;
-------
for hauling this sludge, based on a round trip mile, is also presented
in Figure VIII-40. Assumptions and cost criteria for sludge handling
are based on information provided in reference (2). To calculate the
cost of land, Figure VIII-41 presents the sludge lagoon area required
versus mine drainage flow rates.
REGIONAL SPECIFICITY FOR COSTS
Variations in capital and annualized costs are dependent on the region
in which the treatment facility is located. These differences are due
to such factors as soil type, precipitation, topography, and
vegetation. Cost multipliers have been prepared to reflect these cost
differences and are presented in Table VIII-5 in the column entitled
"Basic Capital Cost Multiplier." The development of these multipliers
is presented in reference (5).
Before using these multipliers for a particular region, the extent to
which certain costs have already been absorbed in establishing BPT
facilities should be determined; this may require a certain degree of
downward multiplier adjustment in the cost. Items which affect the
accuracy of these basic multipliers are previously built-in access
roads, clearing and grubbing, etc.
The development of the Capital Cost Multiplier Adjusted to Civil Works
was based on the premise that the multiplier is only applicable to
that portion of the capital cost which is associated with excavation,
backfilling, and concrete placement. The assumed contribution which
these items provided in the overall construction investment is 40
percent. Thus, the basic multipliers are adjusted to 40 percent of
their original value (5). Table VIII-5 also presents the formula
which demonstrates the application of the adjusted capital cost
multiplier to yearly costs. Regional cost multipliers for yearly cost
would apply only to that portion of the yearly cost associated with
the civil works part of the facilities, such as the civil works
portion of the amortization and associated charges.
Examples of regionally specific
provided in the cost manual (1).
cost determination procedures are
NON-WATER QUALITY ASPECTS
349
-------
Table VIII-5
COST MULTIPLIERS FOR COAL MINING REGIONS IN THE UNITED STATES
Region
Northern Appalachia
Central Appalachia
South Appalachia
Midwest
Central W*st
Gulf
Northern Great Plains
Rockies
Southwest
Basic Capital
Cost Multiplier
Capital Cost Multi-
plier Adjusted to
Civil Works
1.8
1.8
1.7
1.3
1.2
1.0
1.0
1.9
1.65
1.32
1.32
1.28
1.12
1.08
1.0
1.0
1.36
1.26
NOTES:
To obtain the adjusted yearly cost for a region where the capital
cost multiplier is greater than one use the following formula:
Adjusted
Yearly
Cost
Yearly
Cost from -
Curve
Capital
Recovery
Factor
Reference (5)
Yearly
x Cost from
Curve
Capital
x 1 - Cost
Multiplier
350
-------
DESIGN FLOW IN M.G.D.
Figure VIII-41
SLUDGE LAGOON - AREA REQUIRED VERSUS DESIGN FLOW
MINE DRAINAGE TREATMENT
351
-------
The effects of the candidate technologies on air pollution, solid
waste generation, and energy requirements have been considered. The
latter aspect has been addressed in earlier subsections, and will not
be repeated.
Air Pollution
Imposition of regulations based on any of the candidate technologies
in any subcategory will not create any additional air pollution.
Solid Waste Generation
The neutralization and aeration of acid mine drainage results in .a
suspension of ferric hydroxide, other metal hydroxides, and unreacted
reagents (lime) in an aqueous solution of salts composed largely of
sulfates. This suspended matter must be removed before the water is
discharged. Also, alkaline drainage contains sediment which requires
removal. Many preparation plants in the United States use water to
assist in the sizing, separation, and cleaning of run-of-mine coal.
The waste slurry discharged from the plant is often high in suspended
coal fines that require reduction or removal prior to recycle or
discharge. Also, coal preparation facilities generate a solid or
semisolid refuse of material rejected from the cleaned coal. Ash,
clays, and other materials make up this refuse, which is conveyed as a
slurry to a refuse pile, or disposed of in some other manner. The
creation of these sludges result from application of the BPT
requirement. Additional sludge generation resulting from the
candidate technologies are discussed in the following paragraphs.
Flocculant Addition and Granular Media Filtration
For mine drainage or preparation plant wastewaters, the application of
these technologies would result in additional sludge production of a
composition similar to sludge generated by BPT requirements. However,
the amount of this extra solid waste would be minimal in comparison
with quantities produced by compliance with BPT. For instance, in the
acid drainage subcategory, the average TSS removal (which makes up a
substantial portion of the solid waste) at a typical mine by
application of BPT is 1,310 pounds per day. Installation of
flocculant addition equipment would result in an additional estimated
removal of 40 pounds per day, or a little over three percent of the
BPT sludge production. For application of filtration technology,
additional sludge production would be approximately 80 pounds per day,
or less than 6.5 percent of the sludge produced under the BPT
requirement.
Total Recycle Option-Preparation Plants
The total recycle option was considered only for preparation plant
wastewaters {distinct from preparation plant associated area
wastewater). As in the previous case, the additional sludge resulting
from selection of the zero discharge option would be minimal. Again,
using a typical facility, 370,000 pounds per day are removed from the
352
-------
wastewater by application of settling (BPT) technology (this figure
does not include the small amounts of any gypsum or other "spectator"
solids that might settle). Installation of facilities to achieve
total recycle would remove an additional 140 pounds per day from
waters discharged to the environment.
Settling - Reclamation Areas
The Agency is promulgating effluent limitations for areas under
reclamation and for sites where mining has ceased. Because these
limitations are based on a technology (a sedimentation pond) whose
installation is already required by active mining regulations there
will be no incremental non-water quality impacts resulting from the
EPA rule for post-mining regulations. Because the composition of the
settled material does not include toxic metals, the environmental
impacts of solid waste disposal in this subcategory are projected to
be minimal.
353
-------
-------
SECTION IX
AMENDMENTS TO BPT
The following are amendments to the previously promulgated BPT
regulations (42 FR 21380 (April 26, 1977)). These changes also apply
to BAT and NSPS presented in the following sections.
WESTERN MINES
As discussed in Section V, western mines will no longer be a separate
subcategory.
POST MINING DISCHARGES
This subcategory was established (as "areas under reclamation") during
the NSPS rulemaking, but the Agency deferred promulgation of any
limitations until further data could be gathered and analyzed. As
discussed in Sections V and VII, additional data have been collected
that support the establishment of effluent limitations for this
subcategory.
Reclamation Areas
Pollutants to be regulated for reclamation areas include settleable
solids and pH. The technology basis on which these limitations are
based is a sedimentation pond capable of containing the runoff from
the reclaimed area resulting from a 10-year, 24-hour storm. The
Agency has concluded that the following limitations shall apply to the
reclamation areas for mining of coal of all ranks including, but not
limited to, lignite, bituminous, and anthracite:
355
-------
Effluent Limitations
Effluent Characteristic
Settleable Solids
pH
Maximum for
Any One Day
0.5 ml/1
within the range
6.0 to 9.0
at all times
30 Day
Average
These regulations shall apply until full release of the
performance bond.
Underground Mine Discharges
SMCRA
Effluent limitations for underground mines shall be the same as those
for active mines because the wastewater characteristics are not
significantly different as discussed in Sections V and VII.
ALTERNATE LIMITATIONS DURING PRECIPITATION EVENTS
EPA is amending the exemption available for discharges caused by
precipitation events. EPA's studies have shown that well-operated
treatment facilities can achieve settleable solids and pH limitations
during rainfall events of varying intensity as discussed in Section V
and VIII. The "storm exemption" published on December 28, 1979 (44 FR
76788) is being modified as follows:
(1) Settleable solids and pH limitations will apply to
discharges, overflows, or increases in discharges caused by
precipitation events less than or equal to a 10-year,
24-hour storm event.
(2) Only pH limitations will apply to discharges, overflows, or
increases in discharges caused by precipitation events
greater than a 10-year, 24-hour storm event.
(3) The alternate limitations apply to coal mining operations
regardless of the treatment installed; there is no
requirement to install a "10-year, 24-hour pond", or indeed
any pond at all. This requirement has been deleted in
conformity with the July 2, 1981 proposal by OSM, to allow
mining operations flexibility in designing their treatment
systems. The limitations on settleable solids of 0.5 ml/1
and pH (range of 6-9) are based on the treatment capability
356
-------
of a pond designed, constructed and maintained to contain
the volume of water which would drain into the pond from
active mining areas and reclaimed areas during the 10-year,
24-hour precipitation event. (See Section VII).
(4) Discharges from underground mines are not eligible for the
alternate limitations unless they are commingled with
surface discharges. Precipitation does not significantly
affect the mechanism of underground mining discharges, and
thus relief from effluent limitations is not necessary.
Techniques for preventing or minimizing infiltration in
underground mines is presented later in this section.
Costs to comply with the storm exemption are less than those
originally required in the BPT regulations because a
10-year, 24-hour pond is not required. Smaller ponds or
other treatment options may be used and the facility may
still qualify for the alternate limitations.
Any overflow, increase in volume of a discharge or discharge from a
bypass system caused by precipitation within any 24-hour period less
than or equal to the 10-year, 24-hour precipitation event (or snowmelt
resulting in equivalent volume) shall be subject to the following
alternate limitations:
Effluent Limitations
Effluent characteristic
Settleable Solids
PH
Maximum for
Any One Day
0.5 ml/1
within the range
6.0 to 9.0
at all times
30 Day
Average
Any overflow, increase in volume of a discharge or discharge from a
by-pass system caused by precipitation within any 24-hour period
greater than the 10-year, 24-hour precipitation event (or snowmelt
resulting in equivalent volume) shall be subject to the following
alternate limitations:
Effluent Limitations
Effluent Characteristic
PH
Maximum for
Any One Day
within the range
6.0 to 9.0
at all times
30 Day
Average
357
-------
The Agency has decided to delete the design
flexibility in treatment systems, consistent
regulations.
criteria to allow
with OSM's proposed
358
-------
SECTION X
BEST AVAILABLE TECHNOLOGY ECONOMICALLY ACHIEVABLE (BAT
The factors considered in assessing best available technology
economically achievable (BAT) include the age of equipment and
facilities involved, the process employed, process changes, nonwater
quality environmental impacts (including energy requirements) and the
costs of application of such technology (Section 304(b)(2)(B)). In
general, the BAT technology level represents, at a minimum, the best
economically achievable performance of plants of various ages, sizes,
processes, or other shared characteristics. Where existing
performance is uniformly inadequate BAT may be transferred from a
different subcategory or category. BAT may include process changes or
internal controls, even when not common industry practice.
Under the Clean Water Act amendments of 1977, the primary emphasis of
BAT is the control of toxic pollutants. Tie statutory assessment of
BAT "considers" costs, but does not require a balancing of costs
against effluent reduction benefits. In developing the final BAT,
however, EPA has given substantial weight to the reasonableness of
costs. The Agency has considered the volume and nature of discharges,
the volume and nature of discharges expected after application of BAT,
the general environmental effects of the pollutants, and the costs and
economic impacts of the required pollution control levels. Despite
this expanded consideration of costs, the primary determinant of BAT
remains effluent reduction capability.
Effluent limitations in this industry are expressed as concentrations
(i.e., mass per unit volume, most often milligrams per liter— mg/1).
Mass limitations cannot be written because wastewater flow cannot be
correlated with coal production. This stems from the fact that,
although little process water is employed in coal extraction, large
volumes of water still require treatment because of infiltration from
precipitation and runoff through the active mining area as well as
groundwater seepage from breached aquifers. Thus a particular mine
may have large volumes of water to treat that are essentially
independent of the coal production capacity of the mine. This
situation is also found in the coal preparation segment. Although
process water used for coal cleaning can be correlated with
production, wastewater flows are impossible to predict due to varying
amounts of surface runoff from preparation plant associated areas such
as coal stockpiles.
The Agency considered a number of options for regulation of existing
sources subject to the BAT requirement a^nd new sources subject to the
359
-------
NSPS requirement.
New source options
The BAT limitations options
are discussed in Section XII.
are detailed below
BAT OPTIONS CONSIDERED
General Applicability
Under all options considered
discharge for coal preparation
allowed for discharges caused
regulations apply to all
regulations and alternate storm
and described below (except zero
plants) alternate limitations would be
by precipitation. The post-mining
options also (both the post-mining
limitations are the same as those
presented in Section IX "Amendment to BPT" ) .
Option One - BAT ^ BPT
For acid drainage mines and coal preparation plants and associated
areas the limitations are based on the application of neutralization,
aeration, and settling technology. For alkaline mines limitations are
based on application of settling technology.
Option Two - BAT 2. BPT +_ Flocculant Addition Technology
A treatability study commissioned by the Agency has shown that when
toxic metals were spiked into the untreated wastewater, substantial
reduction of these pollutants was also achieved along with suspended
solids. Additional toxic metal removals for BPT-treated water without
spiking were highly variable due to the low influent levels of these
metals. Costs for installation and operation of this technology would
range from $30,000 to $40,000 per outfall for capital costs and from
$.042/1,000 gallons treated to $.41/1,000 gallons treated for annual
costs.* The cost of implementating this option at preparation plants
and associated areas for the entire U.S. is 50.0 million dollars
(capital) and 25.1 million dollars (annual) for this subcategory.
*Note: The lower cost was calculated assuming a two mg/1 dosage rate
and a 4,5 mgd facility; the higher cost was calculated assuming a two
mg/1 dosage rate and a 0.1 mgd facility.
Option Three - BAT = BPT + Granular Media Filtration Technology
Two acid drainage treatment plants were studied for evaluation of this
technology. They consisted of BPT treatment (neutralization,
aeration, and settling) of acid mine drainage followed by a dual-media
filter. Toxic metal reductions are not quantified because influent
concentrations of toxic metals to the filter were very low, i.e., the
neutralization and settling processes effectively removed the priority
360
-------
metals contained in the raw wastewater. Capital costs for this
technology range from $150,000 for a design flow of 100,000 gpd to
$900,000 for a design flow of 8,000,000 gpd. Annual costs for
filtration range from $.51/1,000 gallons treated for the 100,000 gpd
facility to $.055/1,000 gallons treated for the 8 mgd facility. No
capital and annual costs were estimated for implementation of this
option specifically for preparation plants and associated areas.
Option Four - BAT f. %ero Discharge for Coal Preparation Plants
Associated area drainage would be segregated from preparation plant
wastewaters for separate treatment. Total recycle of preparation
plant water would be necessary, with ditching or diking installed
around the slurry pond to divert storm and other surface runoff.
Makeup water would be provided from an independent source. An
occasional purge, subject to BPT, would be allowed when necessary to
reduce the concentration of solids or process chemicals in the water
circuit to a level which will not .interfere with the preparation
process or process equipment. Associated area drainage would, if
required, be neutralized and settled in a separately constructed
facility. Option 1 thru 3 would be considered for the mine drainage
subcategories. The alternate limitations for precipitation events
will not apply to new source preparation plants. Total industry
capital costs for implementation of this option are estimated to total
291.2 million dollars. Annual costs are estimated at 52.6 million
dollars.
BAT SELECTION AND DECISION CRITERIA
EPA has selected Option One (BAT = BPT) as the basis for final BAT
effluent limitations. Additional removal of toxic compounds by
Options Two and Three is insignificant. There was some additional
removal of iron and manganese, however the costs associated with
installation and operation of these technologies are too high to
warrant such removal. These options provided only small incremental
toxic metal removals and in some cases exhibited virtually no
additional removal at all. Thus, lower BAT limitations based on these
technologies could not be justified. Suspended solids removals were
quantifiable; however, TSS is subject to BCT, not BAT limitations.
These technologies will be subject to the BCT "cost reasonableness"
test when it is promulgated; until then, BCT limitations are reserved
for the coal mining industry. Option four for existing preparation
plants was not selected based upon the high retrofit expenditures. In
the Agency's judgment, the costs of retrofitting for zero discharge
are not justified by the effluent reductions that would result from
that option. As noted in Section XII, "New Source Performance
Standards (NSPS)," the zero discharge option was selected for new
36l
-------
source preparation plants because no retrofit costs were involved.
The BAT effluent limitations guidelines for the coal mining category
are summarized in Table X-l.
BEST MANAGEMENT PRACTICES (WATER MANAGEMENT
Section 304(e) of the Clean Water Act (33 U.S.C. 1251) authorizes the
Administrator of EPA to promulgate Best Management Practices (BMPs)
for each class or subcategory of both point and nonpoint sources of
pollution. Under the Surface Mining Control and Reclamation Act of
1977 (SMCRA) (Public Law 95-87), OSM was assigned responsibility for
the development of a comprehensive program to ensure environmental
protection and land reclamation of surface coal mining operations.
Water handling practices can include the application of various
mining, aquifer and erosion control techniques to prevent or minimize
adverse environmental effects. The purpose of these techniques is to
effect a reduction in effluent water volumes and/or an improvement in
effluent quality, thereby reducing wastewater treatment and its
associated costs. The following paragraphs discuss water management
practices available to operators and permit authorities to reduce
wastewater quantity. For both surface mining and the surface effects
of underground mining, OSM has promulgated specific regulations
governing water management associated with mining and reclamation
operations (44 FR 15143-15178). A number of these standards have been
remanded as a result of litigation; therefore, OSM is now in the
process of a new rulemaking.
Underground Mines
Surface or groundwater may enter underground mines from above, below,
or laterally through adjacent rock strata. Faults, joints, and roof
fractures are common sites of water entrance into abandoned
underground mines. Water may also enter mines through exploration
drill holes or through boreholes that supply power and air to
underground equipment. Surface water can drain into underground mines
from surface mines or as a result of inadequate stream diversion
practices. Flooding or seepage from adjacent abandoned or inactive
underground mines is often a significant source of water infiltration.
Factors that can affect the quantity of water entering a deep mine
are: the depth of the mine, the source of the drainage, the location
of water bearing strata, and groundwater flow patterns.
Investigations of the quantity of water entering underground coal
mines have found the average rate of infiltration to vary between
6,260 and 10,280 liters per hectare per day {670 to 1,100
gal/acre/day). These rates may be exceeded if catastrophic flooding
of a mine occurs from adjacent or overlying abandoned drifts (1),
Various infiltration control practices are required in order to comply
362
-------
Table X-l
EFFLUENT LIMITATIONS BASED ON BEST AVAILABLE
TECHNOLOOY ECONOMICALLY ACHIEVABLE (BAT)
Effluent Limitations (mg/1)
Subcategory and
Effluent
Characteristics
Acid Mine Drainage:
Fe (total)
Mn (total)
Maximum for
any one day
7.0
4.0
Average of daily
values for 30
consecutive days
shall not exceed
3.5
2.0
Alkaline Mine Drainage:
Fe (total)
7.0
3.5
Preparation Plants and
Associated Areas:
Fe (total)
Mn (total)
Post Mining Discharges:
Areas Under Reclamation
Settleable Solids
PH
Underground Mine
Discharges
7.0
4.0
3.5
2.0
0.5 ml/1
within the range
6.0 to 9-0
at all times
Effluent limitations that apply
from appropriate active mine
drainage subcategory
363
-------
with OSM regulations restricting the discharge of
underground mines (44 FR 15269 sec. 817.55). OSM
endorsed by EPA include:
1. Borehole sealing and casing
2. Mine sealing
3. Regrading and revegetation of surface facilities,
4. Surface water diversion
water into
requirements
and
Borehole Sealing
Underground mines are commonly intercepted by boreholes extending from
the ground surface. These holes are sometimes drilled during mineral
exploration, but may also be utilized for supplying power or air to
underground equipment or for discharge water pumped from active
sections. Upon abandonment of an underground mine, these boreholes
may collect and transport surface and groundwater into the mine.
These vertical, or nearly vertical, boreholes can be successfully
sealed from below in an active underground mine. The sealing can also
be achieved by placing packers and injecting a cement grout. Often
abandoned holes will be blocked with debris and will require cleaning
prior to sealing. The packers should be placed below aquifers
overlying the mine to prevent entry of sub-surface waters, but should
be well above the roof to prevent damage to the seal from roof
collapse. A borehole may also be sealed by filling the hole with rock
until the mine void directly below the hole is filled to the roof.
Successive layers of increasingly smaller stone should be placed above
the rock, A clay and/or concrete plug Is then placed in the borehole.
The remainder of the borehole may be filled with rock or capped.
Mine Sealing
Several techniques contained in the OSM program prevent postmining
formation of acid mine drainage. One of these techniques is mine
sealing. ' Mine sealing is defined as the closure of mine entries,
drifts, slopes, shafts, subsidence holes, fractures, and other
openings in underground mines with clay, earth, rock, timber,
concrete, fly ash, grout, and other materials. The purpose of mine
sealing is to control or abate the discharge of mine drainage from
active and abandoned mines. Mine seals have been classified into
three types based on method of construction and function. The three
seal types are:
1. Dry Seal—The dry seal is constructed by placing suitable material
in mine openings to prevent the entrance of air and water into the
mine. This seal can be applied to openings where there is little or
no water flow from within the mine and little danger of a hydrostatic
head developing.
2. Air Seal—An air seal prevents the entrance of air into a mine
while allowing the normal mine discharge to flow through the seal.
This seal is constructed with a water trap similar to the traps in
sinks and drains.
364
-------
3. Hydraulic Seal—Construction of a hydraulic seal involves placing
a plug in a mine opening that is discharging water. The plug prevents
discharge after the mine is flooded. Flooding excludes air from the
mine and retards the oxidation of sulfide minerals. However, the
possibility of the failure of mine seals or outcrop barriers increases
with time as the sealed mine workings gradually become inundated by
groundwater and the hydraulic head increases. Depending upon the rate
of groundwater influx and size of the mine area, complete inundation
of a sealed mine may take several decades. Consequently, the maximum
anticipated hydraulic head on the mine seals may not occur for a long
time. In addition, seepage through, or failure of, the coal outcrop
barrier or mine seal could occur at any time.
Surface Area Regrading
Water discharging from underground mines often originates as surface
water from ungraded, unvegetated strip mine spoils. This commonly
occurs in the eastern United States where coal outcrops are often
mined by contour stripping techniques. These strip mines can
intercept underground workings or have underground mine entries and
auger holes located along the highwall. When these openings occur on
the updip side of an underground mine, large volumes of surface water
may be conveyed to underground workings. Surface mines may collect
water and allow it to enter a permeable coal seam. This water can
flow along the seam to adjacent underground mines.
The purpose of regrading is to return the disturbed area back to its
approximate original contour, with natural drainageways and
watersheds. Various methods of surface regrading have been practiced
in the eastern coal fields. The selection of a regrading method will
depend upon such factors as: the amount of backfill material
available, the degree of pollution control desired, future land use,
funds available and topography of the area. Prior to backfilling,
impervious materials may be compacted against the highwall and coal
seam, to prevent the flow of water to adjacent underground mines.
Where contour terrace regrading methods are applied, surface runoff is
diverted away from the highwall.
Surface Water Diversion
Surface cracks, subsidence areas, ungraded surface mines, and shaft,
drift and slope openings often are the source of surface water
infiltration, into underground mines. Water diversion entails the
interception and conveyance of water around these underground mine
openings. This procedure controls water infiltration and decreases
the volume of mine water discharge.
Ditches, trench drains, flumes, pipes, and dikes are commonly used for
surface water diversion. Ditches are often used to divert water
around surface mines. Flumes and pipes can be used to carry water
across surface cracks and subsidence areas. To ensure effective
diversion, the conveyance system must be capable of handling maximum
365
-------
expected flows. Riprap may be required to reduce water velocities
ditch type conveyance systems.
in
In addition to the above practices required by OSM, permit writers may
make use of the following water management practices to assure the
control of 'infiltration into underground mines:
1. Surface or subsurface sealing
2. Channel reconstruction
3. Aquifer interception
4. Subsidence sealing and grading
Surface Sealing
Surface mines that overlie deep mines can collect water in a pit and
this water could percolate into the underground facility. To control
this, the surface permeability should be reduced. That can be
accomplished by placement of impervious materials, such as concrete,
asphalt, rubber, plastic, latex, or clay on the ground surface.
Surface permeability may also be decreased by compaction; however, the
degree of success will depend upon soil properties and the compaction
equipment utilized.
A seal below the surface would have several advantages over surface
seals: it would be less affected by mechanical and chemical actions;
land use would not be restricted; and the seal would most likely be
located in an area of lower natural permeability. The seal would be
formed by injecting an impermeable material into the substrata.
Asphalt, cement and gel materials have been used to control water
movement below the surface. The effectiveness of various latexes,
water soluble polymers, and water soluble inorganics, which hydrate
with existing ground materials to form cement like substances, has
been demonstrated in laboratory and field tests. However, large scale
applications of subsurface sealants to control acid mine drainage have
not been demonstrated.
Channel Reconstruction
Vertical fracturing and subsidence of strata overlying underground
mines often create openings on the ground surface. Streams flowing
across these openings may have a complete or partial loss of flow to
the underground workings. During active operations, pumping of this
infiltrating water is required. In both active and abandoned
underground mines the problem of infiltrating stream flow can be
effectively controlled by reconstructing and/or lining the stream
channel. The reconstructed channel bottom may be lined with an
impervious material to prevent seepage or flow to the underground
mine. To ensure complete and effective diversion, the reconstructed
channel must be capable of handling peak stream flows. In instances
when stream flow cannot be diverted to a new channel, flow into
underground mines can be controlled by plugging the mine openings with
clay or other impervious material.
366
-------
Aquifer Interception
This mine water handling technique utilizes hydrogeologic features of
an underground mine in order to help prevent the inflow and
contamination of groundwater. Wells are drilled from the land surface
through the aquifer to the underground mine. The groundwater may then
be drained through the mine zone for discharge into underlying
aquifers, or conveyed from the mine through a pipe system.
Subsidence Sealing and Grading
Before or after abandonment of underground mines, fracturing or
general subsidence of overlying strata can occur. This fracturing
increases the permeability of the strata, and can result in the flow
of large volumes of water into a mine. The volume of water that is
diverted into an underground mine via fracturing or subsidence depends
upon the structure of the overlying rock, and the surface topography
and hydrology of the area. Vertical permeability may be decreased by
placing impermeable materials around the subsided area. These
materials may be compacted on the surface and graded, or placed in a
suitable sealing strata below ground level. Materials which have been
successfully utilized for subsidence sealing are rubber, clay,
concrete, and cement.
Prevention of Acid Formation
Because sufficient water is almost always present in deep mines to
allow acid formation, methods for reducing oxygen availability and
contact time are important in preventing this reaction. Reduction of
contact time can be accomplished during active operations by pumping
water from the mine and maintaining the mine pool at a sufficiently
low level. Pumping costs can be quite high, particularly if the water
sources are diffuse; therefore, it is also good practice to try and
reduce the amount of water flowing into the mine. For inactive or
abandoned mines, mine sealing is a viable alternative. This method
can eliminate oxygen from entering an underground mine.
Surface Mining
Water handling techniques for surface mines include practices
associated with two categories: (1) mining technology, and (2)
reclamation technology. Pre-mine planning to institute these
practices is very important, as is borne out by the permit procedures
required by OSM. The mining and reclamation techniques discussed in
this subsection represent source control methods that can contain or
prevent pollution formation during active mining.
Mining Methods
Certain mining techniques can help reduce the environmental impacts of
coal strip mining. One such technique currently employed by industry
and favored by OSM is termed "Modified Block Cut" mining. This method
is basically applicable to moderate slopes (20% or less), low
367
-------
highwalls (60 feet average) and thin seams. It has been applied to
mines located in the east. This technique is expected to be feasible
in even steeper terrain. The modified block cut method is a variation
of conventional contour strip mining (2). Material from the first cut
is often stored in a valley or head of hollow fill. This initial cut
is usually three times wider than each succeeding cut in order to
accommodate excess spoil as the mining plan progresses. After
completion of each cut, a void is created near the highwall to store
pollutant-forming materials encountered during mining. Overburden
from the next cut is backfilled into the previous cut simultaneously
exposing coal and initiating reclamation. This method offers several
advantages:
eliminated
1. Overburden is handled only once.
2. Most of the spoil is confined to a mined area,
3. Spoil on the downslope is almost completely
thereby reducing the amount of disturbed area,
4. Reclamation is concurrent, and
5. Grading and revegetation areas are reduced.
Figure X-l illustrates the "Modified Block Cut" method.
Excess Spoil Disposal
According to OSM regulations, spoil not used in returning the land to
approximate original contour must be hauled and placed in a designated
disposal area. The operator must ensure that leachate and surface
runoff from the fill will not harm the surface waters or groundwater
and the fill area must be suitable for reclamation. The regulations
allow three types of fill design: valley, head-of-hollow, and durable
rock.
A valley fill can be described as follows: a structure located in a
hollow where the fill material has been hauled and compacted into
place with diversion of upstream drainage around the fill. In
addition, according to OSM regulations, valley fills must meet rules
for subdrainage and filter systems.
Head-of-hollow fills are constructed in a manner similar to valley
fills. However, instead of diverting upstream drainage around the
fill, a rock-core chimney, constructed from the toe to the head of the
fill, passes drainage through a fill core. In addition, head-of-
hollow fills must completely fill the disposal site to the approximate
elevations of the ridge line (3). Figure X-2 illustrates a head-of-
hollow fill.
Durable rock fills represent a third type of valley fill but can be
utilized only if the amount of durable rock (i.e., rocks which do not
slake in water) is 80 percent of the total fill volume. Spoil
material is dumped over a berm located at the head of the fill. The
rock material forms a natural blanket drainway across the bottom of
the fill. A drainage system is required but the regulations leave
design open to the operator (3).
368
-------
Cut
Highwall--
Hill
Diagram A
Valley
Spoil Bank
Spoil Backfill
Outcrop Sorrier
Cut
Cut I
Highwall—*
Hill
Diagram 8
Valley
Cut
Hill
Diagram C
Highwall—
Valley
Hil
Diagram D
Valley
Cut
Valley
Hill
Diagram
Valley
Figure X-1
MODIFIED BLOCK CUT
Source: (1)
369
-------
Strip Mine Bench
Crowned
Terraces
PLAN
Original
Ground Surface
Highwal!
Fill
Lateral Drain
Crowned.
Terraces
Rock Filled
Natural Drainway
Figure X-2
CROSS SECTION OF TYPICAL HEAD-OF-HOLLOW FILL
Source: (1)
370
-------
Reclamation
Proper reclamation techniques play a vital role in overall
environmental quality control for any mining operation. Reclamation
is considered an integral part of the overall mining plan. According
to SMCRA, as contemporaneously as practicable with operations, all
disturbed land shall be reclaimed to a condition equal to or exceeding
any previous use which such lands were capable of supporting
immediately prior to any exploration or mining function. Reclamation
techniques center basically on regrading and revegetation.
Regrading
The purposes of regrading include the following:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
( j }
Aesthetic improvement of the land surface
Returning the land to usefulness
Providing a suitable base for revegetation
Burial of pollution-forming materials
Reducing erosion
Eliminating landsliding
natural drainage
ponding
hazards, such as high cliffs, deep pits and deep
Encouraging
Eliminating
Eliminating
ponds
Controlling
water pollution.
Regrading, as applied to surface mining, is currently defined as that
of reconstructing the approximate original contour. Regrading is
often more difficult in older surface mines where mining was conducted
with less regard to environmental concern. For example, spoil was
often placed without consideration of future regrading requirements.
Contour strip mines in steep terrain create special problems where the
spoil was deposited over the outslope. The terrain becomes difficult
to cover with topsoil prior to regrading. Achieving a suitable
surface for revegetation on abandoned mines becomes complicated
because spoil segregation was rarely practiced. Topsoil usually was
not segregated or stockpiled and pollution-producing materials are
often well mixed throughout the spoil. This emphasizes the importance
of regrading methods such as soil spreading and burying of pollution-
forming materials. Revegetation techniques such as soil
supplementation and spoil segregation are also important. Practices
such as water diversion and sealing both underground mine openings and
auger holes in highwalls can eliminate many erosional and/or pollution
problems otherwise encountered during regrading and revegetation.
A major characteristic of most open pit mines or quarries is the large
area required for disposal of overburden and processing wastes.
Usually the required disposal acreage exceeds the actual pit area,
Careful management of topsoil and overburden must be maintained for
later use in land reclamation. Proper disposal of wastes avoids
leaching of toxic materials from waste sites. Revegetation and
regrading techniques help avoid water infiltration and severe erosion
371
-------
losses which could eventually result in landslides and severe
pollutant loadings in nearby waters. Each of these practices is
specified under OSM regulations.
Revegetation
Proper revegetation is one of the most effective pollution and
erosional control methods for surface mined lands. Revegetation
results in aesthetic improvement, and returns land to agricultural,
recreational, or silvicultural usefulness.
A dense ground cover stabilizes the surface with its root system,
reduces velocity of surface runoff, and functions as a filter to
remove sediment from water flowing over and through it. This
vegetative cover will annually contribute organic matter to the
surface and can greatly reduce erosion. Eventually the soil profile
develops into a complete soil ecosystem. The soil bacteria act as an
oxygen barrier by consuming oxygen as it enters the soil from the
atmosphere. The amount of pollution formed due to oxidation .of
materials lying below the soil horizon is thus greatly reduced.
A soil profile also tends to act as a sponge by retaining water near
the surface. The retained water acts as a surface coolant as it
evaporates from the surface. The resulting decrease in surface
temperature enhances vegetative growth. Additionally, water retained
at the surface or evaporated from the surface does not pass through
underlying spoil material, thereby averting potential pollution
problems.
Loss of the topsoil is a major hindrance to revegetation and,
therefore, topsoil stockpiling is required by OSM. To protect the
stockpile from erosion, OSM regulations require that quickgrowing
annual and perennial plants be seeded on the pile.
Revegetation can be an entire pollution control plan in some
instances, but generally it must be an integral part of more com-
prehensive plans that incorporate water diversion, overburden
segregation, and regrading.
Past revegetation efforts were primarily concerned with planting
trees. However, to establish vegetative cover adequately, tree
planting must be accompanied by establishment of dense ground covers
of grasses and legumes that are compatible with the local plants and
local environment. Again, OSM regulations specify many facets of
revegetation and reclamation.
Erosion and Sediment Control
The most widely practiced method of erosion control is diversion of
water. Diverting streams and surface runoff to avoid contamination
from mined or disturbed areas is required by OSM. Diversion involves
collection of water before it enters a mine area and conveyance of
that water around or through the mine site to a suitable disposal
372
-------
area. Structures used for these purposes include diversion dikes,
diversion ditches or swales, diversion pipes, and flumes (4, 5).
Flumes and pipes are used mainly in areas of steep terrain or to carry
water across regraded areas. A dike, a ridge of compacted soil, is
used to simply divert the flow of water, whereas a ditch or diversion
system collects the water and transfers it to a suitable disposal
area. Erosion can also be controlled by reducing the velocity of the
water. This can be done by spreading rip rap over the area, by using
check dams, or by using sandbag or straw bale barriers (see Figure X-
3). The establishment of vegetation will also decrease erosion damage.
Diversion techniques are directed toward preventing water from
entering a mined area. Runoff control employs various methods to
handle water after it has reached the mine site. Erosional damage due
to runoff can be effectively and inexpensively controlled by the
establishment of vegetation. In areas where vegetation cannot be
established, rip rap can be used to reduce erosion. Slope reduction
and terracing of embankments are also effective in achieving runoff
control.
In general, diversion and runoff control methods alone are
insufficient to prevent erosion and therefore sedimentation. Methods
of sediment control during active mining are needed to remove
sediments from the runoff before it is discharged.
The most common method of sediment control is the use of sedimentation
ponds. In some cases, certain techniques may be employed to enhance
sedimentation pond performance. One such method is the use of straw
bale dikes (see Figure X-3). This is a replaceable barrier
constructed out of straw bales. The dike intercepts the runoff,
reduces the water's velocity, and detains small amounts of sediment
(4). Another technique is the use of in-pond baffles to reduce short
circuiting and thereby increase retention time.
Water Infiltration Control
Control of surface infiltration involves either isolating waste
material from the water supply or decreasing the surface permeability.
Generally, it is not feasible to isolate the large amounts of waste
material generated by mining operations. Also, the waste material may
be needed as backfill during regrading operations. Under these
conditions, if infiltrating water is causing formation of pollutants,
abatement will require on-site control of infiltration such . as
contained disposal of toxic wastes or decreasing the surface
permeability.
Controlling water infiltration from rainfall and subsurface sources
can be accomplished by placing impervious barriers on or around the
waste material, establishing a vegetative cover, or constructing
underdrains. Impervious barriers, constructed of clay, concrete,
asphalt, latex, plastic, or formed by special processes such as
carbonate bonding, can prevent water from reaching the waste material.
373
-------
A. SANDBAG BARRIERS
B. LOG CHECK DAM
Source: USEPA, Erosion and Sediment Control-Surface Mining
in the Eastern U.S., 1976.
Figure X-3
SEDIMENT TRAPS
374
-------
FLOW
10.2 cm
<4") VERTICAL FACE
EMBEDDING DETAIL
ANGLE FIRST STAKE
TOWARD PREVIOUSLY
LAID BAIL
FLOW
WIRE OR NYLON BOUND
BALES PLACE ON THE
CONTOUR
2 RE-BARS, STEEL PICKETS, OR
5.1 cm x 5.1 cm (2" x 2") STAKES
0.46 m to 0.61 m (!%' to 2') IN GROUND
ANCHORING DETAIL
C. STRAW BALE BARRIER
Figure X-3 (Continued)
SEDIMENT TRAPS
375
-------
A dense vegetative cover has varying effects on infiltration. For
instance, vegetation tends to reduce the velocity of water, thereby
inducing infiltration. Conversely, a vegetative cover will build up a
soil profile, which tends to increase the surface retention of water.
This water is available for evaporation and can result in a net
decrease in the amount of water entering underlying materials.
Vegetation also utilizes large quantities of water in its life
processes (again decreasing the amount of water that will reach the
underlying material). When infiltration is caused by interception of
surface flow, it is usually beneficial to divert the flow. One or
more of the techniques illustrated in the erosion and sediment control
subsection may be employed for this purpose.
Underdrains are often used to control water infiltration after it has
entered the waste material. By offering a quick escape route, contact
time between water and any pollutant-forming
waste is reduced. Also, water flow paths
materials are shortened. The possibility of
is eliminated. Underdrain discharges should
the nature of pollutants contained therein.
material contained in the
through pollution-forming
a fluctuating water table
be monitored to determine
Underdrains also serve as
making
collection points to concentrate diffuse groundwater drainage
any required treatment of this wastewater more manageable.
Infiltration can also occur via exploration drillholes or via other
holes drilled during mining operations although as previously
mentioned, OSM regulations require that these drillholes be cased,
sealed or otherwise managed in a manner that avoids drainage into
groundwater.
376
-------
SECTION XI
AMENDMENTS TO NEW SOURCE PERFORMANCE STANDARDS (NSPS
New source performance standards (NSPS) under Section 306 of the Act
are based on the best available demonstrated technology. New mining
facilities have the opportunity to implement the best and most
efficient coal mining processes and wastewater technologies.
Congress, therefore, directed EPA to consider the best demonstrated
process changes and end-of-pipe treatment technologies capable of
reducing pollution to the maximum extent feasible. New source
performance standards were proposed on 13 May 1976 (41 FR 19841) and
19 September 1977 (42 FR 46932) and promulgated on 12 January 1979 (44
FR 2586). The Agency has reviewed these standards and established a
number of new options.
NSPS OPTIONS CONSIDERED
General Applicability
The alternate limitations during precipitation events and post-mining
discharge limitations apply to all options considered below (the
alternate limitations, though do not apply to the zero discharge
option for coal preparation plants).
Option One
Require achievement of performance standards in each subcategory based
on the same technology proposed for BAT, including neutralization and
settling for acidic wastewaters. This option is predicated on
application of the same technology proposed for BPT for the acid
drainage and preparation plant and associated areas subcategories.
The alkaline drainage and areas under reclamation subcategories would
be required to meet performance standards based on settling
technology. No additional expenditures would be required from
selection of this option.
Option Two
Require achievement of performance standards based on flocculant
addition. As discussed in Section X, this technology would provide
377
-------
some additional reduction of total suspended solids, but would not
provide a cost-effective decrease in toxic pollutant levels, which
were found to be extremely low.
Option Three
Require achievement of performance standards based on granular media
filtration. As in the case of Option Two, granular media filtration
would provide some additional reduction of solids, but would not
provide a cost-effective decrease in toxic pollutant levels.
Option Four
Require achievement of no discharge of process wastewater pollutants
in the coal preparation plant subcategory with one of the other
options selected for the mine drainage subcategories. An occasional
purge, subject to BPT limitations, would be allowed when necessary to
reduce the concentration of solids or process chemicals in the water
circuit to a level which will not
process or process equipment.
considerations have already provided
in existing preparation plants which
process water. The zero discharge requirement
discharge of any pollution-bearing streams from the
water circuit, including the treatment system.
would be available.
interfere with the preparation
Economic and environmental
the incentive to design processes
partially or
completely reuse
would prohibit the
preparation plant
No storm exemption
NSPS SELECTION AND DECISION CRITERIA
EPA has selected Options One and Four as the basis for final new
source performance standards. The rationale for selecting Option One
was discussed in Section X. In Option Four, the preparation plant
subcategory is separated from the associated areas subcategory for new
sources. Many existing facilities are practicing total recycle of
preparation plant wastewaters, thus zero discharge is a demonstrated
technology for these facilities. Further, this option is feasible for
new sources because treatment system and water management planning can
be implemented from the design phase, eliminating the economic and
technical inefficiency associated with retrofitting. Finally, zero
discharge removes an average of 35 mg/1 (monthly average) of TSS, a
parameter regulated under NSPS but not under BAT. Option One will
apply to coal mines and coal preparation plant associated areas.
378
-------
SECTION XII
PRETREATMENT STANDARDS
Section 307(b) of the Act requires EPA to promulgate pretreatment
standards for both existing sources (PSES) and new sources (PSNS) of
pollution which discharge their wastes into publicly owned treatment
works (POTWs). These pretreatment standards are designed to prevent
the discharge of pollutants which pass through, interfere with, or are
otherwise incompatible with the operation of POTWs. In addition, the
Clean Water Act of 1977 adds a new dimension to these standards by
requiring pretreatment of pollutants, such as heavy metals, that limit
POTW sludge management alternatives. The legislative history of the
Act indicates that pretreatment standards are to be technology based
and, with respect to toxic pollutants, analogous to BAT. The Agency
has promulgated general pretreatment regulations which establish a
framework for the implementation of these statutory requirements (see
43 FR 27736, 16 June 1978). EPA is not establishing pretreatment
standards for existing sources (PSES) in the coal mining point source
category at this time nor does it intend to promulgate such standards
in the future (PSNS) since there are no known or anticipated
dischargers to publicly owned treatment works (POTWs). Coal mines are
located in rural areas, often far from population centers and publicly
owned treatment plants. No rational mine operator would choose to
route the high volume mine discharge to a POTW for treatment. This is
true for existing sources and will continue to be true for new
sources, and thus pretreatment standards would be irrelevant and
unnecessary.
379
-------
-------
SECTION XIII
ACKNOWLEDGEMENTS
This document was prepared by Radian Corporation, McLean, Virginia
with direction from Mr. Dennis Ruddy and Ms. Allison M. Phillips of
the Energy and Mining Branch of the Effluent Guidelines Division of
EPA. Direction and assistance were also provided by Mr. William A.
Telliard, Chief of the Energy and Mining Branch and Technical Project
Officer for this study, and Mr. Matthew Jarrett and Mr. Ron Kirby,
Effluent Guidelines Technical Project Monitors. Much of the input for
this document was provided by Radian's subcontractors Frontier
Technical Associates, Buffalo, New York and Hydrotechnic Corporation,
New York, New York. An earlier version of this document was developed
and written by Versar Incorporated, Springfield, Virginia. Much of
the information developed by Versar was incorporated in this draft.
The following agencies and divisions of agencies contributed to the
development of this document:
Environmental Protection Agency
1. ,A11 regional offices
2. Industrial Environmental Research Laboratory, Cincinnati,
Ohio
3. Office of Research and Development
4. Office of General Counsel
5. Office of Analysis and Evaluation
6. Monitoring and Data Support
7. Criteria and Standards division
Pennsylvania Department of Environmental Resources
Bituminous Coal Research
National Coal Association
Many coal companies were very cooperative in providing access to coal
mines and coal preparation plants for various sampling and engineering
studies. Of particular assistance were:
AMAX Coal Company
Beltrami Enterprises, Incorporated
Beth-Elkhorn Corporation
Bethlehem Mines Corporation
Bill's Coal Company
Buffalo Mining Company
381
-------
Central Ohio coal Company
Clemens Coal Company
Consolidation Coal Company
Drummond Coal Company
Duquesne Light Company
Eastern Associated Coal Company
Falcon Coal Company
Harmar Coal Company
Industrial Generating company
Inland Steel Coal Company
Island Creek Coal Company
Jewell Ridge Coal Company
Jones & Laughlin Steel Corporation
Kaiser Steel
Kentland Coal Corporation
King Knob coal Company
Knife River Coal Company
Monterey Coal Company
National Mines Corporation
North American Coal Company
Old Ben coal Company
Peabody Coal Company
Peter Kiewit & Sons, Incorporated
Pittston Coal Company
Southwestern Illinois Coal Company
U.S. Steel
V. & J, Carlson
Washington Irrigation & Development Company
Western Energy Company
382
-------
SECTION XIV
REFERENCES
Section III
1. Nielsen, George F,, ed., 1981 Keystone Coal Industry Manualf
McGraw Hill, New York, New York, 1981.
2. The President's Commission on Coal, Coal Data Book, U.S.
Government Printing Office, Washington, D.C., February 1980.
3. "U.S. Coal Unlikely to Meet Carter's Production Goal," Oil and
Gas Journal, Volume 77, No. 46, pages 205-210, November 12, 1979.
4. "Facts About Coal," National Coal Association, Washington, D.C.,
1982.
5. Wilmoth, R. C., et al., "Removal of Trace Elements from Acid Mine
Drainage," EPA-Industrial Environmental Research Laboratory and
Hydroscience, Inc., for U.S. EPA, Contract No. 68-03-2568, EPA 600/7-
79-101, April 1979.
Section IV
1. Cassidy, Samuel M., ed., Elements of. Practical Coal Mining,
American Institute of Mining, Metallurgical, and Petroleum Engineers,
Inc., New York, New York, 1973.
2. Berkowitz, N., An Introduction to Coal Technology, Academic Press,
New York, 1979.
3. Wachter, R. A. . and T. R. Blackwood, "Source Assessment: Water
Pollutants from Coal Storage Areas," IERL, EPA, Cincinnati, May 1978.
4. Jackson, Dan, "Western Coal is the Big Challenge to Reclamation
Experts Today," Coal Age, Volume 82, No. 7, pages 90-108, July 1977.
5. "Technical Assistance in the Implementation of the BAT Review of
the Coal Mining Industry Point Source Category," U.S. Environmental
Protection Agency, prepared by Versar, Inc., Contract Nos. 68-01-3273,
4762, 5149, and 68-02-2618, Draft, July 1979.
383
-------
6. Leonard, J. W. and D. P. Mitchell, editors. Coal Preparation,
Seeley W. Mudd Series, The American Institute of Mining,
Metallurgical, and Petroleum Engineers, Inc., New York, 1968.
7. Argonne National Laboratory, "Environmental Control Implications
of Generating Electric Power from Coal," Technology Status Report,
Appendix A, Part 1, "Preparation and Cleaning Assessment Study,"
Argonne, Illinois, 1977.
8. Energy Information Administration:
Vols. II & III, 1977.
Annual Report to Congress,
9, U.S. Department of the Interior, Bureau of Mines, Minerals
Yearbook. Volume I: Metals, Minerals and Fuels, 1976 edition,
Washington, D.C.
10. Pennsylvania Department of Environmental Resources, "Annual
Report on Mining, Oil and Gas, and Land Reclamation and Conservation
Activities," Harrisburg, Pennsylvania, 1977 and 1978 Reports.
11. Terlecky, P. Michael, and David M. Harty, "Inventory of
Anthracite Coal Mining Operations, Wastewater Treatment and Discharge
Practices," by Frontier Technical Associates, Inc., for U.S.
Environmental Protection Agency, Contract No. 68-01-5163, October
1979.
12. Jackson, Dan, "Outlook Shines for Coal Slurry Lines," Coal Age,
Volume 83, No. 6, pages 88-93, June 1978.
13. "Facts About Coal," National Coal Association, Washington, D.C.,
19.82.
14. Bureau of Mines: Minerals Yearbooks, 1968-1976, Congressional
Research Service: National Energy Transportation, Volume Ill-Issues
and Problems, March 1978.
15. Nielson, George F., ed.,
McGraw-Hill, New York, 1981.
1981 Keystone Coal Industry Manual,
16. Department of the Interior: Energy Perspectives 2, June 1976.
17. U.S. Department of the Interior, Bureau of Mines, "Coal -
Bituminous and Lignite in 1975," Washington, D.C., 1976.
18. Nielson, George F., ed., 1976 Keystone Coal Industry Manual,
McGraw-Hill, Inc., New York, 1976.
19. "Water Pollution Impact of Controlling Sulfur Dioxide Emissions
from Coal-Fired Steam Electric Generators," Radian Corporation, EPA
Contract No. 68-02-2608, U.S. EPA-IERL, Research Triangle Park, North
Carolina, 1977.
384
-------
Section V
1. Wilmoth, R. C., "Limestone and Lime Neutralization of Acid Mine
Drainage," U.S. EPA, IERL, Cincinnati, Ohio, EPA-600/2-77-101, May
1977.
2. Wilmoth, R. C., "Limestone and Limestone-Lime Neutralization of
Acid Mine Drainage," U.S. EPA, Office of Research and Development,
Cincinnati, Ohio, EPA-670/2-74-051, June 1974.
3. Wilmoth, R. C., "Application of Reverse Osmosis to Acid Mine
Drainage Treatment," U.S. EPA, Office of Research and Development
Cincinnati, Ohio, EPA-670/2-73-100, December 1973.
4. "Testing of Neutralization and Precipitation of Coal Mine Acid
Mine Drainage," Hydrotechnic Corporation, EPA Contract No. 68-01-5163,
U.S. EPA, Washington, D.C., September 1979, draft report.
5. "Testing of Dual Granular Media Filtration of Treated Acid Mine
Drainage," Hydrotechnic Corporation, EPA Contract No. 68-01-5163,
U.S. EPA, Washington, D.C., March 1980, preliminary draft.
6. "Treatability of Coal Mine Drainage for Removal of Priority
Pollutants," Radian Corporation, McLean, Virginia, EPA Contract No.
68-01-5163, U.S. EPA, Washington, D.C., January 1980, preliminary
draft.
7. Wilmoth, R. C., "Removal of Trace Elements from Acid Mine
Drainage,11 U.S. EPA, lERL-Cincinnati and Hydroscience, Inc., EPA
Contract No. 68-03-2568, EPA 600/7-79-101, April 1979.
8. U.S. EPA, "Sampling and Analysis Procedures for Screening of
Industrial Effluents for Priority Pollutants," Environmental
Monitoring and Support Laboratory, Cincinnati, Ohio, March 1977,
revised April 1977.
9. "Inductively-Coupled Plasma-Atomic Emission Spectrometric Method
for Trace Element Analysis of Water and Wastes," U.S. EPA-EMSL,
Cincinnati, Ohio, June 1979.
10. "Comparison of Coal Mine Wastewaters 'from Eastern and Western
Regions," Environmental Protection Agency, Effluent Guidelines
Division, Washington, D.C., Jan. 1981.
11. "Mine Drainage Treatment and Costing Study: Coal Mining
Industry," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, Contract Nos. 68-02-2608 and 68-01-5163,
December 1979.
12. Martin, J. F., "Quality of Effluent from Coal Refuse Piles," U.S.
EPA, Cincinnati, Ohio, 1974.
385
-------
13. Yancey, H. F., M. R. Greer, et al,, "Properties of Coal and
Impurities in Relation to Preparation," pages 1.3 to 1.53 in Leonard
and Mitchell, eds., Coal Preparation, American Institute of Mining,
Metallurgical, and Petroleum Engineers, Inc., New York, 1968.
14. "Development Document for Effluent Limitations Guidelines and New
Source Performance Standards for the Steam Electric Power Generating
Point Source Category," U.S. EPA 4401/1-74-029-a, October 1974.
15. U.S. Bureau of Land Management, Northwest Colorado Coal, final
environmental statement, 4 Volumes, undated.
16. U.S. Geological Survey, Development of Coal Resources in Central
Utah, draft environmental statement, Part 1-Regional analysis; Part 2-
Site specific analysis, 1978.
17. U.S. Department of the Interior, Office of Surface Mining
Reclamation and Enforcement, Permanent Regulatory Program Implementing
Section 501(b) of the Surface Mining Control and Reclamation Act of_
1977, draft environmental statement, September 1978.
18. U.S. Bureau of Land Management, Northwest Colorado Coal Regional
Environmental Statement, supplemental report, undated.
19. Wachter, R. A. and T. R. Blackwood, "Source Assessment: Water
Pollutants from Coal Storage Areas," IERL, EPA, Cincinnati, Ohio, May
1978.
20. Anderson, W. C. and M. C. Youngstrom, "Coal Pile Leachate Quality
and quantity Characteristics," ASCE, Journal of the Environmental
Engineering Division, Volume 102, No. EE6, pages 1239 to 1253, 1976.
21. Terlecky, P. Michael and D. M. Harty, "Inventory of Anthracite
Coal Mining Operations, Wastewater Treatment and Discharge Practices,"
by Frontier Technical Associates, Inc. for U.S. Environmental
Protection Agency, Contract No. 68-01-5163, Final Report, June 10,
1980.
22. "Sludge Sampling Report," Radian Corporation,
1981 .
McLean, VA, Jan.
23. "Coal Preparation Plant Study in Support of Proposed Effluent
Limitations Guidelines for the Coal Mining Point Source Category,"
L.C. Ehrenreich, Jan. 1981.
Section VI_
1. "Sampling and Analysis Procedures for Screening of Industrial
Effluents for Priority Pollutants," U.S. Environmental Protection
Agency, Environmental Monitoring and Support Laboratory, Cincinnati,
Ohio, March 1977, Revised April 1977.
386
-------
2. "Condensed Chemical Dictionary," P. Hawley, Van Norstrand,
Reinhold, New York, New York, 1971.
3. "Development Document for BAT Effluent Limitations Guidelines and
New Source Performance Standards for the Ore Mining and Dressing
Industry," Calspan Report No. 6332-M-l, September 5, 1979.
4. Rawlings, G. D., and M. Samfield, Environmental Science and
Technology, Vol. 13, No. 2, February 1974.
5. "Seminar for Analytical Methods for Priority Pollutants," U.S.
Environmental Protection Agency, Office of Water Programs, Savannah,
Georgia, May 23-24, 1978.
Section VII
1. Lovell, Harold L., "An Appraisal of Neutralization Processes to
Treat Coal Mine Drainage," Pennsylvania State University, University
Park, Pennsylvania, November 1973.
2. Wilmoth, Roger C., et al., "Removal of Trace Elements from Acid
Mine Drainage," EPA Industrial Environmental Research Laboratory and
Hydroscience, Inc., for U.S. Environmental Protection Agency Contract
No. 68-03-2568, EPA 660/7-79-101, April 1979.
3. "Environmental Control Selection Methodology for a Coal Conversion
Demonstration Facility," U.S. Department of Energy, prepared by Radian
Corporation, Contract No. EX-760-C-01-2314, October 1978.
4. "Treatability of Coal Mine Drainage for Removal of Priority
Pollutants: Effluent Limitations Guidelines for the Coal Mining Point
Source Category," U.S. Environmental Protection Agency, prepared by
Versar, Inc., Contract No. 68-01-4762, Draft, September 1979.
5. "Process Design Manual for Suspended Solids Removal," U.S.
Environmental Protection Agency Technology Transfer, EPA 625/1-75-
0039, January 1975.
6. "Erosion and Sediment Control: Surface Mining in the Eastern
U.S.," U.S. Environmental Protection Agency, EPA 625/3-76-006, October
1976.
7. Ettinger, Charles E. and J. E. Lichty, Evaluation of Performance
Capability of. Surface Mine Sediment Basins, Harrisburg, Pennsylvania,
Skelly and Loy, August 1979.
8. Environmental Protection Agency, Resource Extraction & Handling
Division, Sedimentation Ponds - A Critical Review, report, Cincinnati,
Ohio, undated.
9. Hill, Ronald D., Water Pollution from Coal Mines/ EPA, August
1973.
387
-------
10. Hill, Ronald D., "Sediment Control and Surface Mining," Presented
at the Polish-U,S. Symposium Environmental Protection in Openpit Coal
Mining/ Denver, Colorado, May 1975.
11. Grim, Elmore C. and Ronald D. Hill, Environmental Protection in
Surface Mining of Coal, final report, Cincinnati, Ohio, U.S. EPA,
National Environmental Research Center, Office of Research and
Development, October 1974.
12. Kathuria, D. Vir, M. A. Nawrocki and B. C. Becker, Effectiveness
°I Surface Mine Sedimentation Ponds, Columbia, Maryland, Hittman
Associates, Inc., August 1976.
13. Environmental Protection Agency, Development Document for Interim
Final Effluent Limitations Guidelines and New Source Performance
Standards for the Coal Mining Point Source Category, Washington, D.C.,
May 1976.
14. Lanouette, Kenneth H., "Heavy Metals Removal,"
Engineering, Vol. 84, No. 22, pp. 73-80, October 1977.
Chemical
15. "Mine Drainage Treatment and Costing Study: Coal Mining
Industry," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, Contract Nos. 68-02-2608 and 68-01-5163,
November 1979.
16. "Development Document for BAT Effluent Limitations Guidelines and
New Source Performance Standards for the Ore Mining and Dressing
Industry," U.S. Environmental Protection Agency, prepared by Calspan
Corporation, Contract No. 68-01-4845, Draft, September 1979.
17. "Processes, Procedures, and Methods to Control Pollution from
Mining Activities," U.S. Environmental Protection Agency, prepared by
Skelly and Loy and Penn Environmental Consultants, Inc., Contract No.
68-01-1830, EPA 430/9-73-011, October 1973.
18. "Technical Assistance in the Implementation of the BAT Review of
the Coal Mining Industry Point Source Category," U.S. Environmental
Protection Agency, prepared by Versar, Inc., Contract Nos. 68-01-3273,
4762, 5149, 68-02-2618, Draft, July 1979.
19. Wilmoth, Roger C., Applications of_ Reverse Osmosis to Acid Mine
Drainage Treatment, 2 copies, EPA, Crown Mine Drainage Control Field
Site, December 1973.
20. "Handbook of Chemistry and Physics," 50th edition, Weast, R. C,,
editor, Chemical Rubber Company, Cleveland, Ohio, p. B252.
21. "Handbook of Analytical Chemistry," Meites, L., editor, McGraw-
Hill, New York, pp. 1-15 to 1-19, 1963.
388
-------
22. "Ionic Equilibrium as Applied to Qualitative Analyses," Hogness
and Johnson, Holt Rinehart & Winston Company, New York, pp. 360-362,
1954.
23. "Testing of the Neutralization and Precipitation of Coal Mine
Acid Mine Drainage," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, Contract No. 68-01-5163, final report,
November 1979.
24. "Testing of Dual Granular Media Filtration of Treated Acid Coal
Mine Drainage," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, Contract No. 68-01-5163, final report,
August 1980.
25. "Testing of Dual Granular Media Filtration of Treated Acid Coal
Mine Drainage at a Second Site,11 U.S. Environmental Protection Agency,
prepared by Hydrotechnic Corporation, Contract No. 68-01-5163, final
report, December 1980.
26. Janiak, Henryk, "Purification of Waters Discharged from Polish
Lignite Mines," Central Research and Design Institute for Open-pit
Mining, Wroclaw, Poland, for U.S. Environmental Protection Agency, EPA
600/7-79-099, April 1979.
27. Mann, Charles E., "Optimizing Sediment Control Systems," in
Surface Coal Mining and Reclamation Symposium: Coal Conference & Expo
V, October 23-25, Louisville, Kentucky, McGraw-Hill, Inc., New York,
1979.
28. Huck, P. M., K. L. Murphy, C. Reed, (McMaster Univ. Hamilton,
Ontario, Canada) and B. P. LeClair, (Environmental Protection Service,
Ottawa, Ontario, Canada) "Optimization of Polymer Flocculation of
Heavy Metal Hydroxides," Journal WPCF, pp. 2411-2418, December 1977.
29, Reese, R. D. and R. E. Neff, (American Cyanimid Company)
"Flocculation-Filtration Studies on Acid Coal Mine Drainage," BCR-
MD70-86, June 15-19, 1970.
30. Brodeur, T. and D. A. Bauer, "Picking the Best Coagulant for the
Job," Water and Wastes Engineering, Vol. 11, No. 5, p. 52-57, 1974.
Section VIII
1, "Mine Drainage Treatment and Costing Study: Coal Mining
Industry," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, Contract Nos. 68-02-2608 and 68-01-5613,
December 1979.
2. "Coal Mine Industry Mine Drainage Treatment and Costing Study:
Backup Data," U.S. Environmental Protection Agency, prepared by
Hydrotechnic Corporation, March 20, 1980.
389
-------
3. Ruddy, Dennis, U.S. Environmental Protection Agency, communication
to Leo Ehrenreich and Harold Kohlmann, outline of preparation plant
scenarios, March 18, 1980.
4. Curtis, Robert, "Mine Drainage Treatment Costing File: A Set of
Notes and Phone Call Memos on the Cost of Treating Mine Drainage,"
Radian Corporation, McLean, Virginia, January 1980.
5. Randolph, K. B., Versar, Inc., memorandum to Dennis Ruddy, U.S.
Environmental Protection Agency, regarding cost multipliers for coal
mining regions of the United States, January 25, 1979.
6. "Environmental Control Selection Methodology for a Coal Conversion
Demonstration Facility," U.S. Department of Energy, prepared by Radian
Corporation, October 1978.
7. Gumerman, R. C., et al., "Estimating Water Treatment Costs: Volume
2. Cost Curves Applicable to 1 to 200 MGD Treatment Plants," U.S.
Environmental Protection Agency, prepared by Culp/Wesner/Culp
Consulting Engineers, Contract No. 68-03-2516, EPA-600/2-79-162b,
August 1979.
Section X
1. "Processes, Procedures, and Methods to Control Pollution from
Mining Activities," U.S. Environmental Protection Agency, prepared by
Skelly and Loy and Penn Environmental Consultants, Inc., Contract No.
68-01-1830, EPA 430/9-73-011, October 1973.
2. Grim, Elmore C. and R. D. Hill, Environmental Protection iji the
Surface Mining of Coal, Final Report, Cincinnati, Ohio; USEPA,
National Environmental Research Center, Office of Research and
Development, October 1974.
3. Joyce, Christopher R., Final Federal Surface Mining Regulations,
Washington, D.C., McGraw-Hill, 1980.
4. "Erosion and Sediment Control: Surface Mining in the Eastern
U.S.," U.S. Environmental Protection Agency, EPA 625/3-76-006, October
1976.
5. . "Technical Assistance in the Implementation of the BAT Review of
the Coal Mining Industry Point Source Category," U.S. Environmental
Protection Agency, prepared by Versar, Inc., Contract Nos. 68-01-3273,
4762, 5149, 68-02-2618, Draft, July 1979.
390
-------
SECTION XVI
GLOSSARY
absorption: The process by which a liquid is drawn into and tends to
fill permeable pores in a porous solid body; also the increase in
weight of a porous solid body resulting from the penetration of liquid
into its permeable pores.
acid: A substance which dissolves in water with the formation of
hydronium ion. A substance containing hydrogen which may be displaced
by metals to form salts.
acid mine drainage (AMD): Synonomous with "ferruginous mine
drainage." That drainage which before any treatment has a pH of less
than 6.0 or a total iron concentration of more than 10.0 mg/1.
acidity: The quantitative capacity of aqueous solutions to react with
hydroxyl ions (OH~). The condition of a water solution having a pH of
less than 7.
acre-foot: A term used in measuring the volume of water that is equal
to the quantity of water required to cover 1 acre, 1 foot deep, or
43560 ft3.
Act: The Federal Water Pollution Control Act, as amended (33 U.S.C.
1251, 1311 and 1314(b) and (c), P.L. 92-500). Also called the Clean
Water Act and amendments through 1977.
activated carbon: Carbon which is treated by high-temperature heating
with steam or carbon dioxide producing an internal porous particle
structure. Activated carbon is often used to adsorb organic
pollutants and/or remove metal ions.
active mining area: An area where work or other activity relating to
the extraction, removal or recovery of any coal is being conducted.
This includes areas where secondary recovery of coal is being
conducted, but specifically does not include for surface mines any
area of land on or in which grading to return the land to the desired
contour has been completed and reclamation work has begun.
Administrator: Administrator of the U.S. Environmental Protection
Agency, whose duties are to administer the Act.
adsorption: The adhesion of an extremely thin layer of molecules (of
gas, liquid) to the surfaces of solids (granular activated carbons for
instance) or liquids with which they are in contact.
391
-------
alkaline mine drainage: That mine drainage which before any treatment
has a pH of more than 6.0 and a total iron concentration of less than
10.0 mg/1.
advanced waste treatment: Any treatment method or process employed
following biological treatment (1) to increase the removal of
pollution load, (2) to remove substances which may be deleterious to
receiving waters or the environment, (3) to produce a high-quality
effluent suitable for reuse in any specific manner or for discharge
under critical conditions. The term tertiary treatment is commonly
used to denote advanced waste treatment methods.
aerated pond: A natural or artificial wastewater treatment pond in
which mechanical or diffused air aeration is used to supplement the
oxygen supply.
aeration: The bringing about of intimate contact between air and
liquid by one of the following methods: spraying the liquid in the
air, bubbling air through the liquid (diffused aeration), agitation of
the liquid to promote surface absorption of air (mechanical aeration),
agglomeration: The coalesence of dispersed suspended matter into
larger floes or particles which settle more rapidly.
alkalinity: The capacity of water to neutralize acids, a property
imparted by the water's content of carbonates, bicarbonates,
hydroxides, and occasionally borates, silicates, and phosphates. It
is expressed in milligrams per liter of equivalent calcium carbonate.
anion: The charged particle in a solution of an electrolyte which
carries a negative charge.
anion exchange process: The reversible exchange of negative ions
between functional groups of the ion exchange medium and the solution
in which the solid is immersed. Used as a wastewater treatment
process for removal of anions, e.g., carbonate.
anthracite: A hard natural coal of high luster which contains little
volatile matter, and greater than 92% fixed carbon.
anticline: A fold that is convex upward. The oldest strata are
closest to the axial plane of the fold.
aquifer: A subsurface rock formation that is capable of producing
water.
areas under reclamation: A previously surface mined area where
regrading has been completed and revegetation has commenced.
asbestos minerals: Certain minerals which have a fibrous structure,
are heat resistant, chemically inert and possessing high electrical
insulating qualities. The two main groups are serpentine and
amphiboles. Chrysotile principal commercial variety. Other
392
-------
commercial varieties are armosite,
anthophyllite, and tremolite.
crocidolite, actinolite,
auger: Any drilling device in which the cuttings are mechanically and
continuously removed from the borehole without the use of fluids;
usually used for shallow drilling or sampling.
auger mining: Spiral boring for additional recovery of a coal seam
exposed in a highwall.
backfilling: The transfer of previously moved material back into an
excavation such as a mine or ditch, or against a constructed object.
backwashing: The process of cleaning a rapid sand or mechanical
filter by reversing the flow of water.
base: A compound which dissolves in water to yield hydroxyl ions
bench: The surface of an excavated area at some point between the
material being mined and the original surface of the ground on which
equipment can be set, move or operate. A working road or base below a
highwall as in contour stripping for coal.
best available technology economically achievable (BATEA or BAT): The
level of technology applicable to effluent limitations to be achieved
by July 1, 1984, for industrial discharges to surface waters as
defined by Section 301(b) (2) (A) of the Act.
best practicable control technology currently available (BPCTCA or
BPT): Treatment required by July 1, 1977 for industrial discharge to
surface waters as defined by Section 301 (b) (1) (A) of the Act.
best available demonstrated technology (BADT): Treatment rquired for
new sources as defined by Section 306 of the Act.
biochemical oxygen demand (BOD): A measure of water contamination
expressed as the amount of dissolved .oxygen (mg/1) required by
microorganisms, during stabilization of organic matter by aerobic
chemical action.
bituminous: A coal of intermediate hardness containing between 50 and
92 percent fixed carbon.
blowdown: A portion of water in a closed system which is removed or
discharged in order to prevent a buildup of dissolved solids.
carbon absorption: A process utilizing the efficient absorption
characteristics of activated carbon to remove both dissolved and
suspended substances.
cation: The positively charged particles in solution
electrolyte.
of
an
393
-------
cationic flocculant: In flocculation, surface active substances which
have the active constituent in the positive ion. Used to flocculate
and neutralize the negative charge residing on colloidal particles.
chemical analysis: The use of a standard chemical analytical
procedure to determine the concentration of a specific pollutant in a
wastewater sample.
chemical coagulation: The destabilization and initial aggregation of
colloidal and finely divided suspended matter by the addition of a
floe-forming chemical.
chemical oxygen demand (COD): A specific test to measure the amount
of oxygen required for the complete oxidation of all organic and
inorganic matter in a water sample which is susceptible to oxidation
by a strong chemical oxidant.
chemical precipitation: (1) Precipitation induced by addition of
chemicals. This includes the reaction of dissolved substances such
that they pass out of solution into the solids phase. (2) The
process of softening water by the addition of lime and soda ash as the
precipitants.
clarification: A physical-chemical wastewater treatment process
involving the various steps necessary to form a stable, rapid settling
floe and to separate it by sedimentation. Clarification may involve
pH adjustment, precipitation, coagulation, flocculation, and
sedimentation.
clarifier:
low velocity
A basin usually made of steel in which water flows at
allow settling of suspended matter.
to
coagulation: The treatment process by which a chemical added to
wastewater acts to neutralize the repulsive forces that hold waste
particles in suspension.
coagulants: Materials that induce coagulation and are used to
precipitate solids or semi-solids. They are usually compounds which
dissociate into strongly charged ions.
coal mine: An area of land with all property placed upon, under or
above the surface of such land, used in or resulting from the work of
extracting coal from its natural deposits by any means or method
including secondary recovery of coal from refuse or other storage
piles derived from mining, cleaning, or preparation of coal.
coal mine drainage:
mine.
Any water drained, pumped or siphoned from a coal
coal pile drainage: Drainage from
percolation or runoff from rainfall.
coal pile as a result of
394
-------
colloids: Suspensions of particles, usually between a nanometer and a
micrometer in diameter, in any physical state. In this size range the
surface area is so great compared to the volume that unusual
phenomenon occur, i.e., particles do not settle out by gravity and are
small enough to pass through normal filter membranes (i.e., not
ultrafilters).
composite wastewater sample: A combination of individual samples of
water or wastewater taken at selected intervals, generally hourly for
some specified period, to minimize the effect of the variability of
the individual sample. Individual samples may have equal volume or
may be roughly proportioned to the flow at time of sampling.
concentration, hydrogen ion: The weight of hydrogen ions in grams per
liter of solution. Commonly expressed as the pH value that represents
the logarithm of the reciprocal of the hydrogen ion concentration.
conventional pollutants:
TSS.
pH, BOD, fecal coliform, oil and grease, and
crusher, jaw: A primary crusher designed to reduce the size of
materials by impact or crushing between a fixed plate and an
oscillating plate or between two oscillating plates, forming a tapered
jaw.
crusher, roll: A reduction crusher consisting of a heavy frame on
which two rolls are mounted; the rolls are driven so that they rotate
toward one another. Coal is fed in from above and nipped between the
moving rolls, crushed, and discharged below.
cyclone: (a) The conical-shaped apparatus used in dust collecting
operations and fine grinding applications; (b) A classifying (or
concentrating) separator into which pulp is fed, so as to take a
circular path. Coarser and heavier fractions of solids report as the
apex of long cone while finer particles overflow from central vortex.
data correlation: The process of the conversion of reduced data into
a functional relationship and the development of the significance of
both the data and the relationship for the purpose of process
evaluation.
dect.nt structure: Apparatus for removing clarified water from the
surface layers of tailings or settling ponds.
deep mine: An underground mine.
dense-media separation: (a) Heavy media separation, or sink float.
Separation of heavy sinking from light floating mineral particles in a
fluid of intermediate density; (b) Separation of relatively light
(floats) and heavy particles (sinks), by immersion in a bath of
intermediate density.
395
-------
denver cell: A flotation cell of the subaeration type, in wide use.
Design modifications include receded disk, conical-disk, and
multibladed impellers, low-pressure air attachments, and special froth
withdrawal arrangements.
denver jig: Pulsion-suction diaphragm jig for fine material, in which
makeup (hydraulic) water is admitted through a rotary valve adjustable
as to portion of jigging cycle over which controlled addition is made.
dependent variable: A variable whose value is a function of one or
more independent variables.
deposit: Mineral, coal or ore deposit is used to designate a natural
occurrence of a useful mineral, coal, or an ore, in sufficient extent
and degree of concentration to permit exploitation,
depressing agent; depressor; depressant: In the froth flotation
process, a substance which reacts with the particle surface to render
it less prone to stay in the froth, thus causing it to wet down as a
tailing product (contrary to activator).
detention time: The time allowed for solids to collect in a settling
tank. Theoretically , detention time is equal to the volume of the
tank divided by the flow rate. The actual detention time is
determined by operating parameters of the tank.
dewater: To remove a portion of the water from a sludge or a slurry.
differential flotation: Separating a raw coal into two or more coals
and pyrites by flotation; also called selective flotation. This type
of flotation is made possible by the use of suitable depressors and
activators.
discharge: Outflow from a pump, drill hole, piping system, channel,
weir or other discernible, confined or discrete conveyance (see also
point source).
discharge pipe: A section of pipe or conduit from the condenser
discharge to the point of discharge into receiving waters or cooling
device.
dispersing agent: Reagent added to flotation circuits to prevent
flocculation, especially of objectionable colloidal slimes. Sodium
silicate is frequently added for this purpose.
dissolved solids: Theoretically, the anhydrous residues of the
dissolved constituents in water. Actually, the term is defined by the
method used in determination. In water and wastewater treatment, the
Standard Methods tests are used.
disturbed area: An area which has had its natural condition altered
in the process of mining coal, preparing coal, or other mine related
396
-------
activities. This includes but is not limited to all areas affected by
grubbing and topsoil removal; road construction; construction of mine
facilities; coal mining, reclamation and preparation activities;
deposition of topsoil, overburden, coal or waste materials, etc.
These areas are classified as "disturbed" until said areas have been
returned to approximate original contour (or post-mining land use) and
topsoil (where appropriate) has been replaced.
dragline: A piece of excavating equipment which employs a cable-hung
bucket to remove overburden.
drift: A deep mine entry driven directly into a horizontal or near
horizontal mineral seam or vein when it outcrops or is exposed at the
ground surface.
effluent: Liquid, such as wastewater, treated or untreated which
flows out of a unit operation, reservoir or treatment plant. The
influent is the incoming stream.
eluate: Solutions resulting from regeneration (elution)
exchange resins.
of ion
eluent: A solution used to extract collected ions from an ion
exchange resin or solvent and return the resin to its active state.
embankment (or impoundment): Storage basin made to contain wastes
from mines or preparation plants.
erosion: Processes whereby solids are removed from their original
location on the land surface by hydraulic or wind action.
filter, granular: A device for removing suspended solids from water,
consisting of granular material placed in a layer(s) and capable of
being cleaned by reversing the direction of the flow.
filter, (rapid sand: A filter for the purification of water which has
been previously treated, usually by coagulation and sedimentation.
The water passes downward through a filtering medium consisting of a
layer of sand, prepared anthracite coal or other suitable material,
usually from 24 to 30 inches thick and resting on a supporting bed of
gravel or other porous medium. The filtrate is removed by an
underdrain system. The filter is cleaned periodically by reversing
the flow of the water upward through the filtering medium; sometimes
supplemented by mechanical or air agitation during backwashing to
remove mud and other impurities that are lodged in the sand.
filter, vacuum: A filter consisting of a cylindrical drum mounted on
a horizontal axis, covered with a filter cloth revolving with a
partial submergence in liquid. A vacuum is maintained under the cloth
for the larger part of a revolution to extract moisture and the cake
is scraped off continuously.
397
-------
filtration: The process of passing a liquid through a filtering
medium for the removal of suspended or colloidal matter.
final contour: The surface shape or contour of a surface mine (or
section thereof) after all mining and earth moving (regrading)
operations have been completed.
fine: Fines is a term that refers to the size of a particle. They
are approximately between -100 and -200 mesh.
floe: A very fine, fluffy mass formed
suspended particles.
by the aggregation of fine
flocculants: Any substance which will cause flocculation. They are
specifically useful in wastewater treatment. Lime, alum, and ferric
chloride are examples of inorganic flocculants and polyelectrolytes
are organic flocculants.
flocculate: To cause to aggregate or to coalesce into small lumps
loose clusters, e.g., the calcium ion tends to flocculate clays.
or
flocculation: In water and wastewater treatment, the agglomeration of
colloidal and finely divided suspended matter after coagulation by
gently stirring by either mechanical or hydraulic means.
flotation: The method of coal or mineral separation in which a froth
created in water by a variety of reagents floats some finely crushed
coal or minerals, whereas pyrites and other minerals sink.
flotation agent: A substance or chemical which alters the surface
tension of water or which makes it froth easily. The reagents used in
the flotation process include pH regulators, slime dispersants,
resurfacing agents, wetting agents, conditioning agents, collectors,
and frothers.
flume: An open channel or conduit on a prepared grade.
froth, foam: In the flotation process, a collection of bubbles
resulting from agitation, the bubbles being the agenct for raising
(floating) the particles of coal or ore to the surface of the cell.
frother(s): Substances used in flotation processes to make air
bubbles sufficiently permanent principally by reducing surface
tension. Common frothers are pine oil, creyslic acid, and amyl
alcohol.
flow model: A mathematical model of the effluent wastewater flow,
developed through the use of multiple linear regression techniques.
flow rate: Usually expressed as liters/minute (gallons/minute) or
liters/day (million gallons/day). Design flow rate is that used to
size the wastewater treatment process. Peak flow rate is 1.5 to 2.5
times design and relates to the hydraulic flow limit and is specified
398
-------
for each plant. Flow rates can be mixed as batch and continuous where
these two treatment modes are used in the same plant.
frequency distribution: An arrangement or distribution of quantities
pertaining to a single element in order of their magnitude.
grab sample: A single sample of wastewater taken at neither
time nor flow.
set
gravity separation: Treatment of coal or mineral particles which
exploits differences between their specific gravities. Their sizes
and shapes also play a minor part in separation. Performed by means
of jigs, classifiers, hydrocyclones, dense media, shaking tables,
Humphreys spirals, sluices, vanners and briddles.
grinding: (a) Size reduction into relatively fine particles. (b)
Arbitrarily divided into dry grinding performed on coal or mineral
containing only moisture as mined, and wet grinding, usually done in
rod, ball or pebble mills with added water.
groundwater table (or level
of saturation.
Upper surface of the underground zone
grout: A fluid mixture of cement, sand (or other additives) and water
that can be poured or pumped easily.
hardness: A characteristic of water, imparted by salts of calcium,
magnesium, and iron, such as bicarbonates, carbonates, sulfates,
chlorides, and nitrates, that causes curdling of soap, deposition of
scale in boilers, damage in some industrial process, and sometimes
objectionable taste. It may be determined by a standard laboratory
procedure or computed from the amounts of calcium and magnesium as
well as iron, aluminum, manganese, barium, strontium, and zinc, and is
expressed as equivalent calcium carbonate.
heavy-media separation: See dense-media separation.
highwall: The unexcavated face of exposed overburden and coal in a
surface mine or the face or bank on the uphill side of a contour strip
mine excavation,
hydrocyclone: A cyclone separator in which a spray of water is used.
hydroclassifier: A machine which uses an upward current of water to
remove fine particles from coarser material.
hydrology:
earth.
The science that relates to the water systems of the
independent variable: A variable whose value is not dependent on the
value of any other variable.
399
-------
influent:
wastewater,
plant. The
The liquid, such as untreated or partially treated
which flows into a reservoir, process unit, or treatment
effluent is the outgoing stream.
in-plant control: Those treatment techniques that are used to reduce,
reuse, recycle, or treat wastewater prior to end-of pipe treatment.
ion: A charged atom, molecule or radical, the migration of which
affects the transport of electricity through an electrolyte.
ion exchange: A chemical process involving reversible interchange of
ions between a liquid and solid but no radical change in the structure
of the solid.
jig: A machine in which the feed is stratified in water by means of a
pulsating motion and from which the stratified products are separately
removed, the pulsating motion being usually obtained by alternate
upward and downward currents of the water. jigging: A process used
to separate coarse materials in the coal or ore by means of
differences in specific gravity in a water medium.
lagoon: Man-made ponds or lakes usually 4 feet deep (or up to 18 feet
if aerated) which are used for storage, treatment, or disposal of
wastes. They can be used to hold wastewater for removal of suspended
solids, to store sludge, cool water, or for stabilization of organic
matter by biological oxidation. Lagoons can also be used as holding
ponds, after chemical clarification and to polish the effluent.
lignite: A carbonaceous fuel ranked between peat and bituminous coal.
lime: Any of a family of chemicals consisting essentially of calcium
hydroxide made from limestone (calcite) which is composed almost
wholly of calcium carbonate or a mixture of calcium and magnesium
carbonates.
lime slurry: A form of calcium hydroxide in aqueous suspension that
contains free water.
linear regression: A method to fit a line through a set of points
such that the sum of squared vertical deviations of the point values
from the fitted line is a minimum, i.e., no other line, no matter hpw
it is computed, will have a smaller sum of squared distances between
the actual and predicted values of the dependent variable.
magnetic separator: A device used
magnetic or nonmagnetic materials.
to separate magnetic from less
mathematical model: A quantitative equation or system of equations
formulated in such a way as to reasonably depict the structure of a
situation and the relationships among the relevant variables.
mean value: The statistical expected or average figure.
400
-------
median value:
the midrange.
A data observation located at the 50th percentile or
mesh size (activated carbon): The particle size of granular activated
carbon as determined by the U.S. Sieve series. Particle size
distribution within a mesh series is given in the specification of the
particular carbon.
milligrams per liter (mg/1): This is a mass per volume designation
used in water and wastewater analysis.
minable: (a) Capable of being mined. (b) Material that can be mined
under present day mining technology and economics.
mine; (a) An opening or excavation in the earth for the purpose of
excavating minerals, coals, metal ores or other substances by digging.
(b) A word for the excavation of minerals by means of pits, shafts,
levels, tunnels, etc., as opposed to a quarry, where the whole
excavation is open. In general the existence of a mine is determined
by the mode in which the mineral is obtained, and not by its chemical
or geologic character. (c) An excavation beneath the surface of the
ground from which mineral matter of value is extracted.
mine drainage: Mine drainage usually implies gravity flow of
wastewater from coal mining to a point away from the mining operation.
However, this term encompasses any wastewater emanating from a coal
mining or preparation operation.
mixed-media filtration: A filter which uses two or more filter
materials of differing specific gravities selected so as to produce a
filter uniformly graded coarse to fine.
mulching: The addition of materials (usually organic
surface to curtail erosion or retain soil moisture.
to the land
multiple linear regression: A method to fit a plane through a set of
points such that the sum of squared distances between the individual
observations and the estimated plane is a minimum. This statistical
technique is an extension of linear regression in that more than one
independent variable is used in the least squares equation.
neutralization: Adjustment of pH by the addition of acid or alkali
until a pH of about 7.0 is achieved. See pH adjustment.
new source: Any point source, the construction of which is begun
after the publication of proposed Section 306 regulations.
new source performance standard (NSPS): Performance standards for the
industry and applicable new sources as defined by Section 306 of the
Act.
401
-------
NPDES permits: National Pollutant Discharge Elimination System
Permits are issued by the EPA or an approved state program in order to
regulate point-source discharge to public waters.
nonconventional pollutants: Chemical or thermal pollutants,
principally defined by not being a conventional or toxic pollutant.
normalized coefficients: Regression constants whose magnitudes are
referenced to some value.
open-pit mining, open cut mining: A form of operation designed to
extract coal or minerals that lie near the surface. Waste, or
overburden, is first removed, and the coal or mineral is broken and
loaded.
osmosis: The process of diffusion of a solvent through a
semipermeable membrane from a solution of lower to one of higher
solute concentration.
osmotic pressure: The equilibrium pressure differential across a
semipermeable membrane which separates a solution of lower from one of
higher concentration.
outcrop: The exposing of bedrock or strata projecting through the
overlying cover of detritus and soil.
outfall: The point or location where sewage or drainage discharges
from a sewer, drain or conduit.
overburden: Material of any nature, consolidated or unconsolidated,
that overlies a deposit of useful materials (i.e., coal, ores, etc.).
overflow: Excess water discharged from the treatment system.
oxidation: The addition of oxygen to a chemical compound, or any
reaction which involves the loss of electrons from an atom.
oxidized zone: In coal mining, that portion of a refuse pile near the
surface, which has been leached by percolating water carrying oxygen,
carbon dioxide or other gases.
permeability: Capacity for transmitting a fluid.
pH: A measure of the acidity or alkalinity of an aqueous solution,
generally expressed in terms of the hydrogen ion considered an acidic
solution; and above 7 it is considered an alkaline solution.
pH adjustment: Treatment of wastewater by the addition of an acid or
alkali to effect a change in the pH or hydrogen ion concentration.
Alkalis such as lime (CaO), limestone (CaC03), caustic soda (NaOH), or
soda ash (Na2C03), which supply hydroxyl ions are used to adjust
acidic streams while an acid, usually sulfuric (H2S04) or hydrochloric
(HC1) reacts with alkaline streams by supplying hydrogen ions. The pH
402
-------
of an effluent
for discharge.
is adjusted to a range of 6 to 9 to make it suitable
pH modifiers: Proper functioning of a cationic or anionic flotation
reagent is dependent on the close control of pH. Modifying agents
used are soda ash, sodium hydroxide, sodium silicate, sodium
phosphates, lime, sulfuric acid, and hydrofluoric acid.
pH value: A scale for expressing the acidity or alkalinity of a
solution. Mathematically, it is the logarithm of the reciprocal of
the gram ionic hydrogen equivalents per liter. Neutral water has a pH
of 7.0 and hydrogen ion concentration of 10~7 moles per liter.
physical-chemical treatment: In this study, it is taken to mean a
method of treating wastewater by the addition of chemicals to
physically separate the pollutant from a stream, usually by
precipitation, followed by settling or flotation of the
accomplish this, several processes may be utilized
adjustment, reduction of hexavalent chromium,
precipitation,
settling.
wastes. To
such as pH
heavy-metal
coagulation, flocculation, and clarificaiton by
point source: Any discernible, confined and discrete conveyance,
including but not limited to any pipe, ditch, channel, tunnel,
conduit, well, discrete fissure, container, rolling stock,
concentrated animal feeding operation, or vessel or other floating
craft, from which pollutants are or may be discharged.
preparation plant: A facility that cleans, sizes and upgrades run-of-
mine coal thereby creating a final coal product prior to shipping or
consumption, and facilities (i.e., slurry pond, fresh water pond,
conveyances) directly associated with the recycling or discharge of
waters used during the "preparation" of coal.
preparation plant ancillary or associated areas: Areas that are
interrelated with coal preparation or coal load out activities but do
not include the preparation plant building and the preparation plant
water recycle/discharge system. Said areas include but are not
limited to ancillary buildings associated with coal preparation;
disturbed areas in proximity to the preparation plant or related
preparation activities; coal stockpiles; coal refuse storage areas/
coal haulroads and refuse haulroads in proximity to the preparation
plant or coal refuse storage site; treatment systems designed to
handle runoff or seepage from preparation plant "disturbed" areas, or
coal refuse piles etc.
priority pollutants: Those pollutants included in Table 1 of
Committee Print Numbered 95-30 of the "Committee on Public Works and
Transportation of the House of Representatives," subject to the Clean
Water Act of 1977, and included in Table VI-l of this document.
pyrites: Mineral group composed of iron and sulfur found in coal
403
-------
rank of coal: A classification of coal based upon the fixed carbon on
a dry weight basis and the heat value.
raw mine drainage: Untreated or unprocessed water drained, pumped or
siphoned from a mine.
reagent: A chemical or solution used to produce a desired chemical
reaction; a substance used in flotation.
reclamation: The procedures by which a disturbed area can be reworked
to make it productive, useful, or aesthetically pleasing, consisting
primarily of regrading and revegetation.
reduction: A chemical
electrons to a species.
reaction which involves the addition of
refuse pile: Waste material from a preparation plant. The material
includes pyrites, ash, and water or chemicals used in cleaning the
coal.
regression model: A mathematical model, usually a single equation,
developed through the use' of a least squares linear regression
analysis.
reserve: That part of an identified resource from which a usable
mineral and energy commodity can be economically and legally extracted
at the time of determination.
residuals: The differences between the expected and actual values in
a regression analysis.
reverse osmosis: The process of diffusion of a solvent through a
semipermeable membrane from a solution of higher to one of lower
solute concentration, effected by raising the pressure of the more
concentrated solution to above the osmotic pressure.
riprap: Rough stone of various sizes placed compactly or irregularly
to prevent erosion.
room and pillar mining: A system of mining in which the
distinguishing feature is the mining of 50 percent or more of the coal
in the first working. The coal is mined in rooms separated by narrow
ribs (pillars); the coal in the pillars can be extracted by subsequent
working in which the roof is caved in successive blocks.
runoff: That part of precipitation that flows over the
from the area upon which it falls.
land surface
sampler: A device used with or without flow measurement to obtain any
adequate portion of water or waste for analytical purposes. May be
designed for taking a single sample (grab),composite sample,
continuous sample, or periodic sample.
404
-------
sampling stations: Locations where several flow samples are tapped
for analysis.
scarification: The process of breaking up the topsoil prior to
mining.
sediment: Solid material settled from suspension in a liquid medium.
sedimentation: The gravity separation of settleable, suspended solids
in a settling basin or lagoon.
settleable solids: (1) That matter in wastewater which will not stay
in suspension during a preselected settling period, such as 1 hour but
either settles to the bottom or floats to the top. (2) In the Imhoff
cone test, the volume of matter that settles to the bottom of a i-
liter cone in 1 hour.
Settlement Agreement of June 1, 1976: Agreement between the U.S.
Environmental Protection Agency (EPA) and various environmental
groups, as instituted by the United States District Court for the
District of Columbia, directing the EPA to study and promulgate
regulations for a list of chemical substances, referred to as Appendix
A Pollutants.
settling pond: A pond, natural or artificial, for recovering solids
from an effluent.
significance: A statistical measure of the validity, confidence, and
reliability of a figure.
sludge: Accumulated solids separated from a liquid during processing.
sluice; To cause water to flow at high velocities for wastage, for
purposes of excavation, ejecting debris, etc.
slurry: Solid material conveyed in a liquid medium.
spoil material: Overburden that is removed from above the coal seam;
usually deposited in previously mined areas.
statistical variance: The sum of the squared deviations about the
mean value in proportion to the likelihood of occurrence. A measure
used to identify the dispersion of a set of data.
subsidence: Surface depression created by caving of the roof material
in an underground mine-
sump: Any excavation in a mine for the collection of water for
pumping.
suspended solids: (1) Solids which either float on the surface of or
are in suspension in water, wastewater, or other liquids, and which
are removable by a .45 micron filter. (2) The quantity of material
405
-------
removed from wastewater in a laboratory test, as prescribed in
"Standard Methods for the Examination of Water and Wastewater" and
referred to as nonfilterable residue, measured in mass per unit volume
(e.g., mg/1),
surface active agent: One which modified physical, electrical, or
chemical characteristics of the surface of solids and also surface
tensions of solids or liquid. Used in froth flotation (see also
depressing agent, flotation agent).
syncline: A fold that is concave upward. The younger strata are
closest to the axial plane of the fold.
table, air: a vibrating, porous table using air currents to effect
gravity concentration of sands or other waste material from coal.
terracing: The act of creating horizontal or near horizontal benches.
thickener: A vessel or apparatus for .reducing the amount of water (or
conversely, increasing the concentration of settled material)in a
wastewater stream.
tolerance limits: Numerical values identifying the acceptable range
of some variable.
turbidity: Is a measure of the amount of light passing through a
volume of water, which is directly related to the suspended solids
content.
weir: An obstruction placed across a stream for the purpose of
diverting the water so as to make it flow through a desired channel,
which may be an opening or notch in the weir itself.
yellowboy: Salt of iron and sulfate formed by treating acid mine
drainage (AMD) with lime; FeS04.
406
-------
ABBREVIATIONS
Ag
Al
As
BADT
BATEA (BAT)
BCPCT (BCT)
Demonstrated
Be
BMP
BOD
BPCTCA
Ca
Cd
CN
COD
Cr
Cu
CWA
DM
EPA
Fe
FWPCA
Hg
Mg
Mn
Na
Ni
NPDES
NSPS
OSM
Pb
POTW
PSES
PSNS
RCRA
Sb
Se
SMCRA
(BPT)
Silver
Aluminum
Arsenic
Best Available
Technology
Best Available Technology
Economically Achievable
Best Conventional Pollutant
Control Technology
Beryllium
Best Management Practices
Biochemical Oxidation Demand
Best Practicable Control
Technology Currently Available
Calcium
Cadmium
Cyanide
Chemical Oxygen Demand
Chromium
Copper
Clean Water Act of 1977
Dissolved Metals
Environmental Protection
Agency
Iron
Federal Water Pollution
Control Act of 1972
Mercury
Magnesium
Manganese
Sodium
Nickel
National Pollution Discharge
Elimination System
New Source Performance
Standards
Office of Surface Mining
(Reclamation and Enforcement)
Lead
Publicly Owned Treatment Works
Pretreatment Standards for
Existing Sources
Pretreatment Standards for New
Sources
Resource Conservation and
Recovery Act of 1976
Antimony
Selenium
Surface Mining Control and
Reclamation Act of 1977
407
-------
ss
TDS
Tl
TM
TS
TSS
Zn
Units
FTU
JTU
kkg
mgd
mg/1
ml/1
ug/1
mty
ppb
ppm
t
NTU
Settleable Solids
Total Dissolved Solids
Thallium
Total Metals
Total Solids
Total Suspended Solids
Zinc
Franklin Turbidity Unit
Jackson Turbidity Unit
thousand kilograms
million gallons per day
milligram(s) per liter
mililiter(s)/liter
microgram(s)/liter
million tons per year
part(s) per billion
part(s) per million
ton
Nephelometric Turbidity Unit
408
-------
APPENDIX A
COAL MINING INDUSTRY SELF MONITORING PROGRAM
A-i
-------
-------
INTRODUCTION
This appendix consists of the following three reports all concerning
the results of the 308 industry self-monitoring survey:
1) "Coal Mining Industry Self-Monitoring Program" by Radian Corporation,
1981.
2) "Reassessment of the Self-Monitoring Data Base According to
the Amended 10-Year, 24-Hour Pond Design Volume for Coal Mines",
by EPA, 1982.
3) "Statistical Support for the Proposed Effluent Limitation of
0.5 ml/1 for Settleable Solids in the Coal Mining Industrial
Category", by EPA, 1982.
The first report summarizes and evaluates the data obtained from an
industry self-monitoring survey. This evaluation determined that 0.5
ml/1 settleable solids was an appropriate effluent limitation for reclamation
areas and for active mines during storms equal to or less than the 10-
year, 24-hour precipitation event. The technology on which this effluent
limitation was based was a 10-year, 24-hour pond as defined in the January
13, 1981 proposal to the coal mining industry. The language in this
proposal required that the treatment facility's design, construction,
operation, and maintenance be based upon water draining into it, including
waters from the undisturbed (virgin) area and inactive (reclaimed) area,
in addition to the active mining area. Twenty-four ponds submitted data
in this survey, 7 of which were determined to be 10-year, 24-hour ponds.
The analysis upon which the 0.5 ml/1 limitation was established was
based, though, on 6 of these 7 ponds because one was considered to be
improperly operated and designed.
The January 13, 1981 proposal was amended on May 26, 1981. This
amendment modified the design volume of a pond by excluding from consideration
waters from undisturbed areas which drain into the treatment facility.
The data base submitted by the 24 ponds was therefore reevaluated and it
was determined that eleven father than six ponds were 10-year, 24-hour
ponds according to the new definition. The second report presents the
calculations and results of this revaluation.
The third report presents the statistical evaluation performed on
the data submitted by these eleven 10-year, 24-hour ponds which determined
that 0.5 ml/1 is within EPA's 99th percentile criterion for establishing
effluent limitations.
A-l
-------
-------
REPORT 1
COAL MINING INDUSTRY
SELF-MONITORING PROGRAM
May 1981
Prepared by:
Radian Corporation
Suite 600, Lancaster Building
7927 Jones Branch Drive
Mclean, Virginia 22102
Prepared fpr:
Effluent Guidelines Division
Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
A-3
-------
-------
TABLE OF CONTENTS
Section
1.0
2.0
3.0
4.0
INTRODUCTION
SUMMARY AND CONCLUSIONS
SAMPLING AND ANALYSIS PROGRAM,
3.1 Self-Monitoring Study
3.2 Facilities Samples .
3-3 Analysis Program. . »
3.4 Pond Design Data. . .
RESULTS
4.1 Pond Design Data
4.2 Wastewater Characterization . .
4.2.1 Toxic and Nonconventional
4.2.2 Settleable Solids. , . .
4.2.3 Total Suspended Solids .
A-ll
A-13
A-19
A-19
A-21
A-21
A-23
A-27
A-27
A-35
A-35
A-45
A-56
APPENDICES
A-5
-------
-------
LIST OF TABLES
Table
2-1
3-1
4-1
4-2
4-3
4-4
4-5
4-6
4-7
4-8
4-9
4-10
4-11
4-12
4-13
4-14
SUMMARY OF INDUSTRY RESPONSES AND DATA
SUBMITTALS
FACILITIES SAMPLED
SEDIMENTATION POND DESIGN CRITERIA SUPPLIED BY
FACILITIES
SUMMARY OF INPUTS REQUIRED TO CALCULATE OSM
POND VOLUME
SCS RUNOFF CURVE NUMBERS .
RUNOFF DEPTH IN INCHES FOR SELECTED CURVE
NUMBERS AND RAINFALL AMOUNTS
COMPARISON OF OSM "REQUIRED" VOLUMES AND ACTUAL
POND VOLUMES
METALS RESULTS FOR RAW WASTEWATER DURING DRY
CONDITIONS
METALS RESULTS FOR POND EFFLUENT DURING DRY
CONDITIONS
METALS RESULTS FOR RAW WASTEWATER DURING WET
CONDITIONS
METALS RESULTS FOR POND EFFLUENT DURING WET
CONDITIONS
METALS RESULTS FOR RAW WASTEWATER WITH RAINFALL
CONDITION UNIDENTIFIED
METALS RESULTS FOR POND EFfLUENT WITH RAINFALL
CONDITION UNIDENTIFIED ...
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER DRY CONDITIONS
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
EFFLUENT DRY CONDITIONS
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER WET CONDITIONS
a -
A-14
A-22
A-28
-jQ
A-33
A-34
A-36
A-38
A-39
A-40
A-41
A-42
A-43
A-46
A-47
A-it8
A-7
-------
LIST OF TABLES
Table
4-15
4-16
4-17
4-18
4-19
4-20
4-21
4-22
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
EFFLUENT WET CONDITIONS
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER DRY CONDITIONS
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
EFFLUENT DRY CONDITIONS
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER WET CONDITIONS
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
EFFLUENT WET CONDITIONS
Page
A-49
A-57
A-59
A-60
PERCENT REDUCTION OF SEDIMENTATION PONDS DURING
WET AND DRY CONDITIONS ............. A-62
RANKED EFFLUENT TSS MEANS FOR DRY CONDITIONS
RANKED EFFLUENT TSS MEANS FOR WET CONDITIONS
A-64
A-65
A-8
-------
LIST OF FIGURES
Figure
4-1
4-2
4-3
4-4
Page
HISTOGRAM OF "NOT-DETECTED" EFFLUENT SETTLEABLE
SOLIDS VALUES DURING DRY CONDITIONS
HISTOGRAM OF "NOT-DETECTED" EFFLUENT SETTLEABLE
SOLIDS VALUES DURING WET CONDITIONS ....... A-52
HISTOGRAM OF DETECTED EFFLUENT SETTLEABLE SOLIDS
VALUES FOR DRY CONDITIONS ............ A-53
HISTOGRAM OF DETECTED EFFLUENT SETTLEABLE SOLIDS
VALUES DURING WET CONDITIONS. . ......... A-54
A-9
-------
-------
1.0
INTRODUCTION
On 12 January 1979, EPA (the Agency) proposed areas
under reclamation as a separate subcategory for establishment of
effluent limitations. Also, the Agency published, during the
spring and summer of 1979, a number of notices in the Federal
Register regarding a storm relief provision for sedimentation
ponds at coal mines. Both areas were reserved pending further
data base development. To augment the data bases for these two
areas, the Agency instituted two studies.
The first is a currently ongoing study jointly spon-
sored with the Office of Surface Mining, Reclamation and Enforce-
ment (OSM). Approximately 39 mine sites have been identified for
a survey of reclamation and sediment control techniques, includ-
ing sediment pond performance. Eight sites have been designated
for more intensive study and sample collection. As data from
this study become available, the results will be evaluated.
The second study is the subject of this report. EPA is
granted authority under Section 308 of the Clean Vater Act Amend-
ments of 1977 to "require the owner or operator of any point
source to ... install, use, and maintain monitoring equipment
or methods . . . and sample effluents (in accordance with such
methods, at such locations, at such intervals, and in such manner
as the Administrator shall prescribe)" for the purpose of devel-
oping effluent limitations under the Act. The Agency utilized
this authority in establishing an industry self-monitoring survey
at 23 mine reclamation ponds around the country.
The results of both these studies will be used to
establish actual pond performance data and, ultimately, to form
part of the basis for development of effluent limitations for
areas under reclamation and for storm events. A summary and the
A-ll
-------
conclusions art presented in Section 2*0. Background information
for the study is presented in Section 3.0, and the analytical
data and a discussion of the results are presented in Section
4.0.
A-12
-------
2*0
SUMMARY AND CONCLUSIONS
The data collection portion of this study commenced in
September 1979 and concluded in September of 1980. The set of
instructions for each industry participant appears in Appendix A.
Industry participants were requested to submit design criteria, a
topographic map, and a photograph or slide for each pond. In
addition, samples collected during each month were to be analyzed
by the participants for total suspended solids, settleable
solids, total and dissolved iron, and pH by EPA-approved analyti-
cal methods. These data with pertinent rainfall information were
to be submitted to EPA on a monthly basis. Also, certain samples
were to be split and one of the splits transported to EPA analyt-
ical laboratories in Denver, Colorado. In Denver, the samples
were analyzed for iron, manganese,- and the 13 toxic metals.
After the first six months' results from these split samples were
received, continuation of this part of the program was deemed
unnecessary and was terminated in April 1980.
As shown in Table 2-1, industry compliance was scat-
tered, with some facilities providing all requested information
and others providing little. The gaps in the data rendered con-
sistent analyses more difficult. Moreover, data submitted on
monthly reporting sheets by certain facilities were sometimes
incomplete or incorrectly reported. Certain facilities (182 and
192) could not provide samples because no discharge occurred.
These facilities are located in the Vest where more arid con-
ditions prevail or where extended periods of freezing tem-
peratures are common.
Nineteen ponds provided data for analysis of toxic
metals and settleable and suspended solids. Reviewing the design
information, seven of these 19 were adequately sized to handle
the runoff from a 10-year, 24-hour storm. Subsequent analysis
A-13
-------
TABLE 2-1
SUMMARY OF INDUSTRY RESPONSES AND DATA SUBMITTALS
Monthly Data Submittals
Design
Information
Facility
15
15
25
25
25
33
35
37
38
85
101
123
181
182
182
Pond
1
2
3*
4
7
1
2
6
19
1
2
3
99
1
2
Submitted?
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Discharged?
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
1979
OCT NOV
X X
0 0
X X
0 0
X
0
X X
0
X X
0
X
0
DEC
X
0
X
0
X
0
X
0
X
0
X
0
X
0
X
0
JAN
X
X
0
X
0
X
X
0
X
0
X
o
X
0
X
0
X
0
X
0
FEE
0
X
0
X
X
0
X
0
X
0
X
0
X
0
X
0
X
0
X
0
MAR
0
0
X
0
X
X
X
0
X
0
X
o
X
X
0
X
0
X
0
X
APR
X
X
X
0
X
X
0
X
X
X
X
0
X
0
X
0
MAY
X
X
X
X
X
X
X
X
X
X
X
JUN
X
X
X
X
X
X
X
X
X
X
X
JUL AUG SEP OCT NOV
XXX
XXX
XXX
XXX
XXX
XXX
XXX
X
X
X
•*
X
X XX
-------
TABLE 2-1 - Continued
SUMMARY OF INDUSTRY RESPONSES AND DATA SUBMITTALS
Monthly Data Submittals
Facility
183
184
185
> 186
l
S 187
191
191
192
192
Pond
1
7
4
2
1
55
18
4
6
Design
Information
Submitted? Discharged?
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
1979
OCT NOV
X X
0
X X
0
X X
0
X X
0
X X
0
DEC
X
0
X
0
X
0
X
0
X
O
X
0
X
0
JAN
X
0
X
0
X
0
X
0
X
0
X
0
FEB
X
0
X
0
X
0
X
0
X
0
X
0
MAR
X
0
X
0
X
0
X
0
X
0
X
0
APR MAY
X X
0
X
X X
X
X
X X
X X
JUN
X
X
X
X
X
X
X
JUL
X
X
X
X
X
X
X
AUG SEP OCT NOV
X X
X X
X
X X
X X
X
X
X - Data supplied by industry.
0 - Data supplied by EPA laboratories.
* - Pond 3 was replaced by pond 4 at facility 25 in March 1980,
-------
shoved one of these, pond 1 at facility 101, to be poorly
designed In other aspect*. These screening procedures thus
yielded six ponds that were properly designed to contain the
10-year, 24-hour event, and 13 that were not*
sions:
Results from the study support the following conclu-
Toxlc metals were not found in concentrations In
pond effluents significantly above their limit of
detection;
Variations in total suspended solids in influent
streams appear to depend on differences in weather
conditions* drainage area size, soil type, ground
cover, degree of reseeding, and other site-specific
factors;
Pond performance is closely linked with design
and operation;
The data indicated that, on a dally basis, total
suspended solids of 70 mg/1 in reclamation area
discharges cannot be consistently achieved, espe-
cially during rainfall events;
Settleable solids effluent values were reported at
zero or not detectable levels in 92 percent and 81
percent of the reported cases for dry and wet condi-
tions, respectively;
Settleable solids detection limit was reported as
0.1 ml/1 in over 93 percent of the cases where
a "not detected11 value was recorded, i.e., <0.1
ml/1;
A daily maximum limitation of 0.5 ml/1 represents
an achievable settleable solids limitation; pond
volume was found to be a relevant factor in achiev-
ing this limitation. All ponds in this study with
proper design and volume large enough to contain
the 10-year, 24-hour storm always achieved the
0.5.ml/1 settleable solids limitation regardless
of any other factors, including weather; and
A-16
-------
Although only four to six of the facilities treated
active area drainage (e.g., pit pximpage) in the
ponds, in every case during rainfall these ponds
achieved the 0.5 ml/1 settieable solids limitation.
Based on the data received to date, active area
sedimentation facilities could also consistently
achieve the 0.5 ml/1 settleable solids limitation
during periods of rainfall less than the 10-year,
24-hour storm.
A-17
-------
-------
3.0
SAMPLING AND ANALYSIS PROGRAM
3.1
Self-Monitoring Study
The purposes of this study include:
(1) Establish data for regulation development within
the reclamation subcategory
(2) Augment current data on sedimentation pond
performance
(3) Link pond performance to pond design
(4) Establish data on pond performance during and
immediately after precipitation events.
To assemble a representative data base, the coal mining
industry was reviewed for the number of facilities where reclama-
tion is occurring* There are some 2,600 surface mines currently
in operation, so this represents the target population. Most of
these mines are very small, with no full time environmental or
water management staff. It Is doubtful that sufficient personnel
and laboratory resources would be available at these small mines
for participation in this program. Therefore, the focus of the
study was on surface mines operated by large, well established
mining companies.
To select the facilities, the mines were screened
according to the following criteria:
• Location
• Topography
• Existence of ponds serving reclamation
areas
• Sufficient resources to conduct program
• Cost to industry participant!
• Participation and cooperation of facility and/or
mining company in previous EPA studies.
A-19
-------
These criteria were applied in conjunction vith EPA and its con-
tractor's knowledge of the candidate facilities, and In consulta-
tion with the industry trade association, the National Coal
Association* One additional constraint was the available time
for collection, analysis, and reporting of the data, since the
Agency is subject to schedules for regulatory proposals estab-
lished by the Clean Water Act and the 1976 Consent Decree.
This process resulted in the selection of 23 ponds at
17 separate facilities. Although this is a small percentage of
the total population, the results and conclusions can be reliably
applied to the other mining facilities. This is because the
variation of sediment load to any one pond over the period of a
year is much greater than the variation from pond to pond. Thus
the large majority of potential conditions that could be expected
at a surface mine will have been encountered during the course of
this study.
Twelve coal mining companies owning the 17 facilities
were contacted in September 1979. Two of the facilities were
reported to have little or no discharge during the study, and
thus were excluded frpm further participation. Facility person-
nel sampled on a weekly basis the Influent and effluent to each
pond. Additional samples were collected the day of a rainfall
event and the day after the event. Flow rate of the discharge
was measured or estimated at the time of sampling. To correlate
the data with the pond design, the Agency also requested that
each company submit design data for each pond being monitored.
An example of the data request form sent to each company may be
found in Appendix A.
A-20
-------
3.2
Facilities Sampled
A total of 19 ponds were sampled at 15 facilities.
These ponds primarily receive runoff from virgin areas (acreage
where no disturbance by the mining company has occurred) and
areas under reclamation (areas that have been regraded and
revegetated). The mine locations, number of ponds sampled, and
facility codes are listed in Table 3-1.
3.3
Analysis Program
The samples collected by each participant were analyzed
by the participant for the following parameters:
• Total suspended solids
• Settleable solids
• pH
• Total iron
* Dissolved iron.
Some samples were split, with one of the splits sent to EPA
Denver laboratories. These split samples were given a code
number by the company to permit matching of the samples after
analyses were completed.
The EPA laboratory analyzed each sample for the follow-
ing parameters:
• Total suspended solids
• Total iron
• Total manganese
• Dissolved iron
A-21
-------
Location
Pennsylvania
Pennsylvania
Vest Virginia
Vest Virginia
Vest Virginia
Vest Virginia
Kentucky
Kentucky
Ohio
Ohio
Indiana
Illinois
Illinois
Illinois
Alabama
Montana^
Vyoming2
Table 3-1
FACILITIES SAMPLED
Number of
Ponds
1
1
2
1
1
1
1
1
2-3l
1
2
1
1
1
2
2
2
23
Mine
Code Number
186
187
15
183
184
185
38
181
25
101
33
37
85
123
191
182
192
1 Facility 25 substituted one of the ponds sampled midway
through the study*
facilities apparently had little or no discharge of
water during the study.
A-22
-------
• Dissolved manganese
• Total and dissolved toxic metals, including
*-antimony
•-arsenic
--beryllium
--cadmium
--chromium
—copper
--lead
--mercury
--nickel
--selenium
--silver
—thallium
--zinc.
The metals were analyzed by inductively-coupled argon plasma
spectroscopy (ICAP).
Monthly reports were submitted to the Effluent Guide-
lines Division on forms provided by the Agency* An example of
this form is provided in Appendix A.
3.4
Pond Design Data
The Agency requested the companies to provide design
data, a topographic map, and photographs for each pond included
as a part of this study. These design parameters can be linked
to performance of the pond, both in the long-term and for shock
loads resulting from, for example, storm runoff. The form used
to request this information may also be found in Appendix A.
Major design parameters requested include:
• Drainage area acreage
--virgin
•-disturbed
• Average slope of drainage area
• Type of soil and cover
A-23
-------
• Surface area, average depth, and volume of sedimen-
tation pond*
• Design and occupied sediment storage volume
• Design detention time
• Devatering device
• Embankment height and width.
The last five of these design factors had corresponding
criteria promulgated on 13 March 1979 by the Department of the
Interior's Office of Surface Mining, Reclamation, and Enforcement
(OSM) tinder authority of the Surface Mining Control and Reclama-
tion Act of 1977 (SMCRA). On 31 December 1979, OSM suspended
certain of these design criteria pending further study. In part,
these were the specific standards for minimum sediment .storage
volume and minimum hydraulic detention time. However, the basic
requirement that the pond be adequately sized to hold the undi-
verted water resulting from a 10-year, 24-hour precipitation
event remained intact. For the purposes of this study, the
suspended OSM criteria were examined to allow a first assessment
of pond design. The consistent use of this uniform set of
criteria for all ponds also permitted comparisons between ponds
in terms of achievable effluent quality. The OSM criteria and
requirements are discussed below.
Surface Area, Average Depth, and Volume of the Pond
Only the volume of the pond is regulated. It must be
sized to hold the runoff resulting from a 10-year, 24-hour pre-
cipitation event*
-------
Sediment Storage
Minimum sediment storage allowable in a pond is either
three years of sediment computed by using accepted methods, or
0.1 acre-feet of sediment per acre of disturbed land. If on-site
control methods such as check dams and grass filters can be shown
to limit sediment delivery from the disturbed land, sediment
storage as low as 0.035 acre-feet of sediment per acre of dis-
turbed land can be used if approved by the regulatory authority.
Further, sediment must be removed from the pond when 60 percent
of the design storage volume has been occupied.
Design Detention Time
Minimum theoretical detention time to be provided by
sedimentation ponds is 24 hours for a 10-year, 24-hour event. A
detention time as low as 10 hours may be approved if any or all
of the following techniques or conditions are used and are shown
not to reduce pond efficiency:
(a) Improved pond design
(b) Special sediment characteristics occur
(c) Chemical treatment is used.
Dewatering Device
A dewatering device must be used to remove the detained
water in the designed time period and must always remain above
the sediment storage level.
Embankment Height and Width
The embankment top must be at least 1..0 foot above the
maximum water level during a 25-year, 24-hour precipitation
A-25
-------
event. The top width of the embankment must be at least (H +
35)/5i where H Is the height In feet from the upstream toe to the
top.
The design data submitted by the companies are pre-
sented in detail in the next section.
A-26
-------
4.0
RESULTS
In this section the pond design data submitted by each
company are presented and discussed. The analytical results from
the industry sampling program are also tabulated and linked to
pond design.
4.1
Fond Design Data
Incomplete information was often submitted by the
industry participants regarding pond design factors. The avail-
able data are summarized in Table 4-1. In general, the results
show that the ponds are in compliance with most of the OSM stan-
dards. Fourteen ponds, however, did not provide the OSM design
storage volume for the runoff area, while an additional three
were between the lower and upper bounds for adequate storage
volume. Thus, only six ponds were designed properly.
The most significant pond design variable is the deten-
tion time, which is, among other factors, a function of the pond
volume. In cognizance of this, both OSM and EPA have linked the
storm exemption provisions to design, construction, and mainte-
nance of ponds of a certain volume. As indicated above, this
volume had been specified as that required to contain all the
runoff from a 10-year, 24-hour storm that drains into the pond.
Because of its relative importance in treatment efficiency, the
pond volume was explored more thoroughly in this study.
To determine whether or not each pond was sized to the
OSM criterion, the data provided by the companies were used in
conjunction with precipitation data from the literature to calcu-
late the "OSM pond volume." This value could be compared with
the actual pond volume provided by the facility. Table 4-2
summarizes the inputs required to calculate the pond volume.
A-27
-------
Table 4-1
SEDIMENTATION POND DESIGN CRITERIA SUPPLIED BY FACILITIES
ro
CD
Facility ID State Pond
Design Sediment Storage
(acre-ft/acre disturbed)
Occupied
Sediment
Storage (%}
Design Theoretical Detention
Time Hours
OSM Criterion
15
15
25
25
33
33
37
38
85
101
123
181
182
182
183
184
185
186
187
191
191
192
192
WV
WV
OH
OH
IN
IN
IL
KY
IL
OH
IL
KY
MT
MT
VA
WV
WV
PA
PA
AL
AL
WY
WY
1
2
4
7
1
2
6
19
1
2
3
99
1
2
1
7
4
2
1
18
55
4
6
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
.100*
.125
.125
-0561
.136
**
.100
.069
.179
.020
-125
.100
.100
.113
.113
xx
.076
.073
.200
.114
.075
.352
.200
.375
60
31.3
27.8
xx
*x
8.76
<0.10
Negligible
*£
XX
None
XX
20
Negligible
Negligible
XX
3.82
5
XX
XX
10
5
XX
XX
24
1
0
XX
XX
46
64
12
173
10
24
173
10
24
24
XX
XX
XX
XX
XX
2
2
24
24
.13
.90
.7
(base flow)
(base flow)
.15
.74
*Sediment storage volume may be exempted down to 0.035 acre-feet disturbed.
**No information available.
IA large pond (#3) is located directly below pond 4.
-------
Table 4-1 (Continued)
SEDIMENTATION POND DESIGN CRITERIA SUPPLIED BY FACILITIES
Embankment
Width of Top of
Facility ID
OSM Criterion
15
15
25
25
33
33
37
38
85
101
123
181
182
182
183
184
185
186
187
191
191
192
192
State
„
WV
WV
OH
OH
IN
IN
IL
KY
IL
OH
IL
KY
MT
MT
VA
WV
WV
PA
PA
AL
AL
WY
WY
Pond
.
1
2
4
7
1
2
6
19
1
2
3
99
1
2
1
7
4
2
1
18
55
4
6
Height (feet)
H
9.2
10
XX
XX
XX
XX
XX
XX
XX
XX
XX
10
8 1/2
16
XX
XX
10
14
>19
XX
XX
XX
XX
Embankment
(H + 35
OSM
Required
9
9
XX
XX
XX
XX
XX
XX
XX
XX
XX
9
8.65
10.2
XX
XX
9
9.8
XX
XX
XX
XX
XX
(feet)
)/5
Actual
14
14
XX
XX
XX
XX
XX
XX
XX
XX
XX
15
15
15
XX
XX
14
10
20
XX
XX
XX
XX
Dewatering Device
Any Device
Type of Devices
Spillway
Spillway
36" perforated stand pipe
24" perforated stand pipe
Open channel*
Open channel*
Open channel*
Earth cut channel*
60" corrugated pipe
Horizontal 18" pipe
XX
Combination Riser*
Decant spillway*
Decant spillway*
Riser pipe**
Channel
Spillway
Perforated riser only
Riser with syphon only
18" pipe
5 ft. pipe
Earthen spillway*
Earthen spillway*
**No information available
-------
>
Table 4-2
SIMMARY OF INPUTS REQUIRED TO CALCULATE OSM FOND VOLUME
10-Year, 24-Hour
Drainage Area (Acres)
Facility
Code State
15
15
25
25
25
33
33
37
38
85
101
123
181
182
182
WV
WV
OH
OH
OH
IN
IN
IL
KY
IL
OH
IL
KY
MT
MT
Precipitation
Pond Event Boil Actively
Number (Total Inches)* 'type** Mined
1
2
3
4
7
1
2
6
19
1
2
3
99
1
1
3.5
3.5
3.5
3.5
3.5
4.0
4.0
4.0
4.0
4.0
3.5
4.0
4.0
2.5
2.5
- 4.0
- 4.0
- 4.0
- 4.0
- 4.0
- 5-0
- 5.0
- 5.0
- 5.0
- 5.0
- 4.0
- 5.0
- 5.0
- 3.0
- 3.0
B-C
B-C
NSt
NS
Disturbed Virgin
Area Area
18.5
10.0
488.0
195-8
Slope Composite Pond
of Runoff Curve Area
Area Numbers (Acres)
47
57
No additional
B-Cit
Dt*
B-Ctt
Dt*
C
C
C
B
B-C
A-B
C
C
B
B
NS
27-5
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
36
27.5
90.7
27.1
280.0
67
110
190
820.4
38.9
70.5
46.2
99-5
33.8
43.5
18.8
1120.0
223.2
0
115
3737.6
0
0
0
28
28
3
4
3
2
15
7
0.
84
25
5
65.9
67.0
0.44
0.43
Calculated Pond
to Meet "OSM" D
(Acre-Feet)
35-6 -
15.0 -
48.3
19.7
data submitted
80.6
85.4
88.0
81.0
81.1
63.2
76.7
67.4
7 77-7
80.5
73.3
63.3
0.33
0.25
2.17
3.22
2.79
1.91
1.80
5.03
33
2.00
1.80
1.34
19.1 -
10.6 -
30.6 -
8.1 -
248.8 -
22.6 -
16.5 -
22.7 -
710.2 -
6.8 -
3.4-
2.2 -
23.7
12.8
41.1
11.4
349.5
36.9
23-8
28.6
1020.8
9-5
5.2
3.4
*Data from "A Compliance Manual—Methods for Meeting OSM Requirements," Skelly and Loy Engineers, McGraw-Hill, Inc.
New York, New York, 1979, p. 6-34.
**See text for explanation of soil types.
1NS - Not supplied by the facility.
ttDisturbed.
t*Vlrgin.
-------
Ve would appreciate. If you hive not already done so, the submt£tal of
transparencies (slides) of your ponds used In this program. Tl8s 1s
directed to those several participants who submitted prints wltn the first
subnlttal of pond data.
50 sample labels and 50 mailing labels are enclosed for shipment of
samples to EPA's Denver laboratory for the period covered by this extension
A-75
-------
STATEMENT CONCERNING CONFIDENTIALITY AND ERA'S STATUTORY AUTHORITY
This request for information is made under authority provided by Section
308 of the Federal Water Pollution Control Act, 33 U.S.C. §1318. Section
308 provides that: "Whenever required to carry out the objective of this
Act, including but not limited to ... developing or assisting in the
development of any effluent limitation ... pretreatment standard, or
standard of performance under.this Act" the Administrator may require
the owner or operator of any point source to establish and maintain records,
make reports, install, use and maintain monitoring equipment, sample
effluents and provide "such other information as he may reasonably require."
In addition, the Administrator or his authorized representative, upon
presentation of credentials, has right of entry to any premises where an
efffluent source is located or where records which must be maintained
are located and may at reasonable times have access to and copy such
records, inspect monitoring equipment, and sample effluents.
Information may not be withheld from the Administrator or his authorized
representative because it is confidential. However, when requested to do
so, the Administrator is required to consider information to be confidential
and to treat it accordingly if disclosure would divulge methods or processes
entitled to protection as trade secrets. EPA regulations concerning
confidentiality of business information are contained in 40 CFR Part 2,
Subpart B, 41 Federal Register 36902-36924 (September 1, 1976). These
regulations provide that a business may, if it desires, assert a business
confidentiality claim covering part or all of the information furnished
to EPA. The manner of asserting such claims is specified in 40 CFR §2.203(b).
Information covered by such a claim will be treated fay the Agency in
accordance with the procedures set forth in the Subpart B regulations.
In the event that a request is made for release of information covered by a
claim of confidentiality or the Agency otherwise decides to make a determination
whether or not such information is entitled to confidential treatment,
notice will be provided to the business which furnished the information.
No information will be disclosed by EPA as to when a claim of confidentiality
has been made except to the extent and in accordance with 40 CFR Part 2,
Subpart B. However, if no claim of confidentiality is made when information
is furnished to EPA, the information may be made available to the public
without notice to the business.
Lffluent data (as defined in 40 CFR §2.302(a)(2)) may not be considered
by EPA as confidential. In addition, any information may be disclosed to
other officers, employees or authorized representatives of the United
States concerned with carrying out the Federal Water Pollution Control
Act or when relevant in any proceeding under this Act.
A-76
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON. D.C 20460
AUG 1980
TO PARTICIPANTS IN THE COAL MINING INDUSTRY MONITORING PROGRAM
To fully evaluate the performance of each of the sedimentation
ponds being sampled in this program, the origin of wastewater to
be treated by the pond is an important factor. Accordingly, we
are requesting that each participant provide the following infor-
mation for each sedimentation pond'sampled:
• Area draining to the pond from reclaimed areas,
acres;
• Area draining to the pond from virgin areas,
acres;
• Area draining to the pond from actively mined
areas, acres; and
• Estimate of the percentage of the total wastewater
volume from each of the above three areas.
Also, please ensure that all requested data items on the monthly
submittal forms are completed, e.g., rainfall data is often
missing on the submitted forms*
Thank you for your continued cooperation with this program.
Please call me if you have any questions concerning this request
or on the program in general.
William A. Telliard, Chief
Energy and Mining Branch
Effluent Guidelines Division (WH-552)
(202) 426-4617
A-77
-------
-------
APPENDIX B
OF REPORT 1
POND VOLUME CALCULATIONS
A-79
-------
-------
CHANGES IN ORIGINAL SELF-SAMPLING AND ANALYTICAL PROGRAM
t This extension applies to the same ponds for w&ich data 1s currently
6*1 ng submitted.
•' pils extension expires September 30, 1980.
• Please submit, by Hay 1, 1980, an update of the pond design parameters
Indicated 1n the Initial request (Included in attached Tab 2). Please
also submit the following statistic for each pond:
The volume attributable to runoff from a 10 year/24 hour storm event for
the pond being used 1n this program. Please show your calculations 1n
the submlttal. For purposes of this calculation, a model such as the
Water Shed Storm Hydrograph, Penn State Urban Run-Off Model, or similar
model may be used. Alternatively, the following may be used:
P
TT x
, )
where
§ C
V 1s volume 1n cubic feet
P 1s the 10 year/24 hour precipitation event, 1n Inches
A| Is the area of the active area drained to the pond,
1n acres
1s the run-off coefficient for the active area drained
to the pond
1s the area of the drainage area which coming!es with
drainage from the active'area, 1n acres. This
Includes runoff from virgin areas and areas under
reclamation which drain to the pond.
1s the runoff coefficient for areas corresponding to
The following may be used to determine Cj and Cj
Active Mining Area
Virgin land and land
under reclamation
Sandy
Loam
0.3
0.1
Clay &
Loam
0.5
0.3
Clay
0.6
0.4
The above values are Increased by 0.1 for slopes ranging from 5S to 105,
and Increased by 0.2 for slopes ranging from 10* to 30*.
For each sample taken during a rainfall event, Indicate when sampling was
performed. Example; 1 hr. & 15 m1n. after start of 20-hour rainfall which
totalled 2.1 Inches.
-------
-2-
o Age of pond
* o Volume of sediment 1n pond during sampling
* o Last time pond was cleaned
o General condition of pond and other Information, e.g.. Inlet
baffle, trees 1n pond, check dam, etc.
o Topographical map of mine area and drainage area (attach)
o 35 mm slide or glossy photo of each pond (attach).
Note: Submit pond design criteria with the first month's data subir.lsslor
Submit asterisked Items each month If they change appreciably*
You may respond directly on this form.
A-73
-------
Form Approved
O.M.B. No. 153-R01SO
Date
Company
Mine Name
Pond Name
Pond Design Criteria: For each pond sampled during this program, provide;
Pond name or other Identification.
o Drainage area • acres
o Drainage area which is disturbed - as acres or % of drainage area
o Average slope of the drainage area
o Cover type on undisturbed portion of the drainage area
o Type of soil/spoil on drainage area, e.g., sandy, silt, loam
o Size of pond • surface area
o Size of pond • volume
o Sketch of pond showing: Inflow points, effluent points, shape (attach)
o Depth of pond * average and maximum design
o Type of discharge device
o Design Sediment Storage Volume
o Design detention time
A-72
-------
Sample Shipment to EPA for Analysis
In addition to the previously Identified parameters to be anajyzed for
by each recipient of this package, a split of the following t£pes of
samples will be labeled* packaged and shipped t^ EPA's Denver Surveillance
and Analysis laboratory for analysis by EPA:
o One sample each of Influent and effluent for each pond every 30 days which
was taken during "base flow" conditions (no rainfall).
o One sample each of Influent and effluent for each pond every 30 days which
was taken during a rainfall event. If, for a given 30 day period, no
rainfall occurs by the time the last "base flow** samples are scheduled to
be taken, then submit a second set of "base flow" samples.
o Container Type:
o Container Size:
o Sample Preservation:
o Frequency of Shipment:
o Method of Sample Shipment:
o Sample Label Information:
0 EPA Laboratory Address
Poly/Plastic
500 ml. minimum
None.
Within 46 hours of sample collection.
United Parcel Service or equivalent,
prepaid.
Preprinted sample labels will soon be
sent directly to you. Should you begin
sampling for this program prior to
receipt of the preprinted labels, please
provide your own labels with the
following Information on them:
o Company Name
o Mine Name
o Pond Identification
o I • Influent sample; E • effluent
sample
o Oate Sample Taken
o R « during rainfall; A • day after
rainfall; 0 « no rainfall
U.S. EPA
Region 8 Laboratory
Building 53 Entrance W-1 Upstairs
Denver Federal Center
Denver, Colorado 60225
A-71
-------
Data Submission; Submit analytical results on a monthly basjs (each 30
days) for the duration of the sampling program to:
W.A. TelUard (UH-552)
U.S. EPA
401 M Street. S.U.
Washington, O.C. 20460
Unless you are using these analytical results to also comply with minimum
NPDES permit monitoring requirements, you need forward them only to the
above Individual.
The attached table Is to be used to report data. Please be sure to
reproduce enough copies of the blank table for use throughout the sampling
program.
A-70
-------
ORIGINAL INSTRUCTIONS
COAL MINING INDUSTRY MONITORING PROGRAM
Purpose; To supplement the data base upon which effluent standards
wf11 be based for sedimentation structures (I.e., ponds) which handle
surface runoff from mining areas and those areas under regradlng and
revegetatlon*
Sampling Locations and Pond Selection; Sampling locations will be the
influent and effluent of two ponds at surface coal mines owned by your
company. The two ponds may be either at the same facility or at different
facilities. The ponds selected should be those which handle mostly runoff
waters from areas under regradlng and revegetatlon. Each pond selected
should not be one that Is fed by another pond. Additionally, the ponds
should 'Ee~those that discharge nost frequently, even during dry w6ather
conditions,
Duration of Sampling: Sampling Is to begin within 30 calendar days from
receipt of this package and last through March 31, 1980.
Sampling Frequency: A minimum of one sample per week of both Influent
and effluent of each pond representing "base flow" conditions, I.e., no
rainfall, but while the pond Is discharging; PLUS, for each rainfall
event during the sampling program, two samples each of Influent and
effluent on the first day of rainfall and two samples each of Influent
and effluent on the day after the rainfall event ends.
Sample Type; All samples taken for this program will be grab samples.
Parameters for Analysis; All samples taken for this program will be
analyzed for the following parameters: Total Suspended Solids, Settleable
Solids* Total Iron, Dissolved Iron, and pH. These analyses are to be
performed by or arranged (e.g., contracted) for your company. EPA-approved
methods are to be used for all analyses. The approved methods are sped fie
In 40 CFR 136, which are the same methods presently In use by Industry for
NPDES monitoring.
Flow: Record flow (as gpm) when each sample Is taken. Bse weir, etc.
measurements If Installed and Indicate what type of measurement device
1s Installed. If flow Is estimated, Include a description of the*flow
estimation technique.
Rainfall Events: Provide the duration (hours) and quantity (Inches) of
each rainfall event which occurs during the sampling program. Indicate
the method used to determine the quantity of rainfall.
A-69
-------
-------
APPENDIX A
OF REPORT 1
INSTRUCTIONS FOR COAL MINING INDUSTRY
MONITORING PROGRAM AND
DATA REQUEST FORMS
A-67
-------
The results of this study support conclusions of previ-
ous studies: first, performance of a pond is closely tied to its
design and operation; second, total suspended solids of 70 mg/1
cannot be consistently achieved during rainfall events; third,
TSS variation is quite substantial in treated effluents from
areas under reclamation, and cannot-be effectively or uniformly
regulated in treated runoff from these areas.
A-66
-------
Table 4-22
RANKED EFFLUENT TSS MEANS FOR WET CONDITIONS
Facility Pond Effluent Mean "OSM"?
33
33
123
184
38
181
187
191
185
37
15
25
85
191
183
25
101
186
1
2
3
7
19
99
1
55
4
6
1
7
1
18
1
4
2
2
12
18
24
24
25
28
29
34
58
59
63
74
77
85
103
123
162
202
Yes
Yes
No
No
Yes
No
Yes
No
No
No
No
No
No
Yes
No
No
Yes
Yes
A-65
-------
Table 4-21
RANKED EFFLUENT TSS MEANS FOR DRY CONDITIONS
Facility Pond Effluent Mean "OSM"?
184
38
181
191
33
33
187
25
123
101
85
37
7
19
99
18
1
2
1
7
3
2
1
6
7
9
10
11
11
14
20
20
23
29
34
41
No
Yes
No
Yes
Yes
Yes
Yes
No
No
Yes
No
No
A-64
-------
Che discrete effluent stream. A final mechanism that has been
previously alluded to Is also possible. Each pond has a theoret-
ical and an actual retention time associated with it, ranging
from a few hours to many days. The theoretical retention time is
calculated by knowing the pond volume and the average volume of
flow Into the. pond. This theoretical detention often bears
little relation to the actual detention time. The actual
detention time is defined as the average length of time that a
discrete volume (say, one liter) of water enters the pond until
that same volume of water exits the pond. It is a complex func-
tion of the pond geometry, water temperature, fluid mechanics,and
other factors. It will also vary with the volume of inflow to
the pond. Obviously, a sampler who collects an effluent aliquot
is not accounting for retention time in the pond, which ranged in
this study from a few hours to many days. This problem, which is
inherent in this type of sampling program, is especially acute
during periods of low flow and low TSS concentrations because so
little TSS enters the pond. Only small amounts of natural
scouring caused by wind and wave action on the surface need to
occur to cause the effluent TSS value to be above the influent
value.
In recognition of these factors, the ponds exhibiting
negative efficiencies were disregarded in further analyses. The
remaining ponds were ranked according to effluent mean to assess
the Importance of the 10-year, 24-hour storm design criterion.
Those appear in Table 4-21 and 4-22. For dry conditions, five of
the seven best performing ponds were sized to OSM criteria. For
wet conditions, four of the seven best performing ponds were "OSM
ponds.11 However, as shown In Table 4-22, certain ponds sized to
OSM criteria had very high effluent means, suggesting that.varia-
bles other than size are also extremely important on pond perfor-
mance. Therefore, it cannot be concluded that "OSM ponds"
consistently 'deliver superior performance*
A-63
-------
Table 4*20
PERCENT REDUCTION OF SEDIMENTATION PONDS DURING
WET AND DRY CONDITIONS
Percent Reduction
Sized to
Facility Pond OSM- Criterion
15 1 No
15 2 No
25 4 No
25 7 No
33 1 Yes
33 2 Yes
37 6 No
38 19 Yes/No
85 1 No
101 2 Yes/No
123 3 No
181 99 No
183 1 No
184 7 No
185 4 No
186 2 Yes
187 1 Yes
191 18 Yes/No
191 55 No
Average for "OSM" Ponds
Average for "Non-OSM" Ponds
negative values indicates that the effluent was higher than
the influent.
SIX1
0
•233
- 16
78
11.5
30
32
92
56
88
89
95
- 67
12
-179
•180
27
38
- 1
11.4
- 11.6
Wet1
27
-147
68
90
68
38
91
92
69
92
99
88
10
33
74
34
99.6
76
77
71
45.6
A-62
-------
the revegetation process (five to ten years), and the significant
erosion rates associated with the Initial stages of the reclama-
tion process. Each of these parameters not only causes reclama-
tion wastewaters to be different from active area drainage, but
also leads to wide variation from mine to mine within reclamation
areas. Tables 4-16 and 4-18 clearly demonstrate this variation.
Results reported by some of the facilities were
surprising. Table 4-20 illustrates this by presenting the
efficiencies or percent reductions for each pond for wet and dry
conditions. These reductions were calculated based on the log-
normal mean influent and effluent values.* Negative reductions
indicate that the effluent mean is higher than the influent mean.
While this type of variation is possible on specific sample sets
(due to retention time of the pond), this behavior in the aggre-
gated data from each facility is subject to question. In some
cases, this anomaly can most likely be attributed to errors in
the data reporting procedure. In other cases, the problem is
probably attributable to sampling procedures. For instance, some
ponds possess multiple inflow points* In many instances, only
one influent was sampled. However, these multiple influents will
contain varying concentrations of TSS. It is easy to envision
how an apparent negative efficiency can result. Another mecha-
nism that could cause this is the selection of the sampling
location within the influent or effluent stream. The influent
stream is more frequently diffuse and shallow. Thus it is more
difficult to select a representative location to sample than in
*"Lognormal" indicates that the data were distributed approxi-
mately lognormally, i.e., a near normal distribution occurred
when the logarithm of each point was calculated and plotted.
The lognormal mean is calculated from a lognormal model of the
data rather than the actual data, because this procedure is not
as sensitive to extreme values.
A-6l
-------
Table 4-19
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
EFFLUENT
WET CONDITIONS
Facility
15
15
25
25
33
33
37
38
85
101
123
181
183
184
185
186
187
191
191
Overall
Pood
*w«^^»
1
2
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
Hunter of
Sample*
13
12
12
15
65
64
17
5
30
41
6
32
17
30
21
12
12
16
16
404
Concentrations
Hlnifflun
1
4
16
17
1
1
16
14
1
4
15
4
2
2
10
45
13
2
_1
1
M«ao
63
42
123
74
12
18
59
25
77
162
24
28
103
24
58
202
29
85
34
52
Median
16
29
104
40
10
13
42
23
35
54
23
18
41
14
43
104
30
14
8
NC
(«8/D
put
424
126
236
193
23
34
178
40
134
350
38
63
281
64
147
486
51
887
341
NC
haxlaun
504
150
288
214
53
55
294
40
654
966
38
402
321
77
182
504
55
2,628
712
966
NC - Not calculated.
A-60
-------
Table 4-18
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER
WET CONDITIONS
Facility
15
15
25
25
33
33
37
38
85
101
123
181
183
184
185
186
187
191
191
Overell
Pond
^V^^MV
1
2
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
Muaber of
Sample*
13
13
12
16
66
64
17
5
30
42
6
34
25
30
21
12
12
17
17
452
Concentrations (u/l)
Minimum
2
3
10
X2
2
2
14
3
17
5
33
4
2
2
3
3
13
11
_4
2
Mean
86
17
379
771
34
29
636
315
247
1,949
3,736
233
114
36
227
306
7,473
1,075
882
276
Median
^^•^•^••••A
11
5
100
74
16
16
131
71
71
325
528
67
16
8
21
55
103
82
38
HC
£01
907
100
1,648
2,889
95
59
2,050
504
794
4,578
5,978
448
768
160
779
1,413
22,875
6,447
6.609
NC
Maxima
1,305
101
1,880
3,097
342
229
3,504
504
9,148
23.260
5,978
10,507
2,110
453
5.460
1,725
30,090
9,998
7.053
30.090
NC - Not calculated.
A-59
-------
Table 4-17
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
EFFLUENT
DRY CONDITIONS
Facility
15
15
25
25
33
33
37
38
85
ioi
123
181
183
184
185
186
187
191
191
Overall
Pond
1
2
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
Number of
Saaplea
30
23
19
22
26
26
28
10
20
28
9
18
29
25
17
33
33
7
5
408
Minimua
2
0.5
5
2
1
1
7
3
4
1
5
1
1
3
3
9
8
4
2
0.5
Concentrations
Mean
11
20
22
20
11
14
41
9
34
29
23
10
10
7
39
94
20
11
_5
25
Median
9
15
16
14
8
11
36
10
22
14
15
6
5
6
29
60
17
11
-i
NC
(»B/1)
9U1
20
36
39
44
22
27
70
16
50
66
68
28
25
15
81
243
32
18
7
NC
Maxima
30
73
91
109
27
27
90
17
318
128
69
69
93
23
105
464
35
18
7
464
NC • Not calculated.
A-58
-------
Table 4-16
TOTAL SUSPENDED SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER
DRY CONDITIONS
Facility
15
15
25
25
33
33
37
38
85
101
123
181
183
184
IMS
186
187
191
191
Overall
fond
1
2
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
IS
55
ttuober of
Sanple*
24
18
19
22
25
26
27
10
20
27
9
8
29
24
17
31
33
4
3
369
Concentration* (mg/1)
HiniBum
0.5
0.5
6
2
1
2
50
2
4
15
23
1
1
1
1
I
3
37
U
0.5
Mean
11
6
19
90
13
20
60
102
77
235
213
200
6
8
14
33
25
a42
188
48
Median
6
4
15
17
9
14
36
96
40
69
47
111
6
4
7
6
19
189
107
HC
901
22
16
36
290
31
45
188
231
199
818
3,060
738
11
22
35
132
59
341
191
NC
Maximum
23
30
52
4.260
64
75
490
243
414
870
3,060
738
13
79
46
282
121
341
191
4,260
HC • Not calculated.
A-57
-------
The remaining settleable solids values above 0.5 ml/1
vere reported by facilities 15, 183, and 185. A review of the
pond designs at these facilities revealed no particular anomalies
except that each was severely undersized with respect to the OSM
volume criterion. Of those ponds that vere sized to the 10-year,
24-hour criterion and also vere properly operated, none vere
found to discharge settleable solids greater than 0*5 ml/1.
Based on these considerations, 0.5 ml/1 represents an
achievable daily maximum limitation for areas under reclamation
and for ponds subject to the storm events that occurred during
the course of this study.
4.2.3
Total Suspended Solids
The capabilities of sedimentation ponds to remove total
suspended solids (TSS) have been extensively investigated by
several researchers. Fev have had access to the amount of data
collected during this study; moreover, none have had adequate
field data to drav conclusions on sedimentation pond performance
during and immediately after rainfall events* This subsection
vill present and discuss the TSS data reported by the participat-
ing facilities.
Tables 4-16 through 4-19 contain summary statistics for
each facility and pond. As can be seen, TSS variation is much
more substantial than that shown by the settleable solids data.
Additionally, great variation in effluent TSS is found from pond
to pond, indicating the importance of the type and ground cover
of areas draining into the pond, as veil as the soil type and
terrain. These differences are much greater than those observed
for pit pumpage or active area drainage. This is an expected
result, given the vast amounts of acreage often associated vith
the reclamation process and treatment facilities, the length of
A-56
-------
reclaimed areas, this sedimentation pond serves 190 acres of
disturbed area. From poncf design data and a topographic map
submitted by the company, these 190 acres appear to be largely
unreclaimed spoil areas. This differs markedly from other ponds
In the study. Runoff from the spoil areas will be heavily loaded
with sediment and evidently enters the pond at diffuse locations
as veil as the specified inflow point. This situation causes
only a small portion of the pond to be used and thus may result
In a substantial reduction in sediment removal efficiency, espe-
cially during intense rainfall events. If this spoil area was
properly reclaimed, erosion would be substantially reduced and
the achievable effluent quality would Improve. Also at this
facility, a second inflow point located less than 200 feet from
the outflow further exacerbates the problem. This situation
exists even though the pond has a surface area of over five acres
and measures almost 1,000 feet in available length. Having an
inflow point so close to the outflow fails to utilize the full
sediment removal capacity of the pond, which again has a delete-
rious effect on effluent quality. Therefore, though this pond is
adequately sized according to storm exemption criteria, it does
not represent an adequate or exemplary design. This discounts
the validity of the effluent data from this facility.
A similar situation exists for pond 55 at facility 191.
Although not sized according to storm exemption criteria, it also
has similar features to pond 2 at facility 101 with respect to
multiple points adjacent to a spoil area. Thus, data from this
facility is also of doubtful validity.
Two values of 0.6 ml/1 were reported during wet condi-
tions from a sedimentation pond in Alabama. The pond Is sized
between the upper and lower ranges of ''the OSM design storage vol-
ume criterion. Because the pond is not clearly within the "OSM
pond" category, these data are not considered to be from an
exemplary facility.
A-55
-------
>
I
HIUPOINI
VALUE
0.0
0.1
0.2
0,4
0,6
0,6
1.0
2,0
3.0
4.0
9,0
6,0
r
*
***********************************
********
*
*****
**
*
***
*
*
**
*
*
*
*
*
FREQ
172
34
22
7
9
1
5
0
1
0
0
1
cun.
FREW
172
206
226
235
244
245
250
250
251
251
251
252
PERCENT
66,29
13,49
6,73
2,76
3,57
0,40
1,98
0,00
0,40
0,00
0,00
0.40
CUN.
PERCENT
66.25
61,79
90,46
93,29
96.63
97.22
99.21
99.21
99.60
99.60
99,60
100.00
20 40 60 60 100 120 140 160
FREQUENCY
Figure A-4
HISTOGRAM OF DETECTED EFFLUENT SETTLEABLE SOLIDS
VALUES DURING WET CONDITIONS
-------
HIDPOINT
VALUE
0.0
0,1
0,2
0,4
0,6
0.8
1,0
2.0
3.0
4,0
5.0
6.0
**********************************************************
*
£*********
t
********
**
*
*
*
*
*
*
*
*
*
*
*
FREQ
113
17
13
1
0
0
0
0
0
0
0
0
cun*
FREQ
113
130
143
144
144
144
144
144
144
144
144
144
PERCENT
78.47
11.81
9.03
0.69
0.00
0,00
0,00
0,00
0,00
0,00
0,00
0.00
CUM.
PERCENT
78.47
90.28
99*31
100.00
100.00
100.00
100,00
100,00
100,00
100.00
100,00
100,00
10 2o 30 40 SO 60 70 80 90 100 HO
FREQUENCY
Figure 4-3
HISTOGRAM OF DETECTED EFFLUENT SETTLEABLE SOLIDS
VALUES FOR DRY CONDITIONS
-------
nxoPoiNi
VALUE
0.01
0,10
0*20
0.30
0.40
O.SO
0.60
0.70
0.60
0.90
1.00
*
f
*
^
f
*****************************************************************
*
*
*
*
*
*
*
^
*
*
*
*
*
±
T-
*
*
*****
*
— »+—»-*—-»*«._-4— —+—*—+— * — + --»*—*-*-*—*-*— + — **- — *
:REQ
1
159
1
0
0
0
0
0
0
0
9
CUM.
FREQ
1
160
161
161
161
161
161
161
161
161
170
PERCENT
0.59
93.53
0.59
0,00
o.oo
0.00
o.oo
0.00
o.oo
0.00
5.29
CUM.
pERCEN
0.5
94.1
94,7
94.7
94.7
94.7
94,7:
94.7:
94.7
94.7:
100.01
10 2« 30 40 50 60 70 BO 90 100 110 120 130 140 ISO 160
FREQUENCY
Figure 4-2
HISTOGRAM OF "NOT-DETECTED" EFFLUENT SETTLEABLE SOLIDS
VALUES DURING WET CONDITIONS
-------
hlOPOiNI
VALUt
0,01
0,10
0,20
0,30
0,40
0,50
0,60
0,70
0.60
0.90
1.00
r
i
^
#
*
*
******************************************
*
*
^A
#
*
^&
iF
#
*
*
*
*
*
*
*
*
*
#
*
****
*
_.„_ + „_- + — + — + — - + — + --- + — - + —- + —- + -
-REO
1
207
0
0
1
0
0
0
0
0
1*
cun.
FREQ
1
208
206
206
209
209
209
209
209
209
223
PERCENT
0.45
92.63
0.00
0,00
0,45
0,00
0.00
0.00
0.00
0,00
6.26
cun.
PERCENT
0.45
93.27
93,27
93.27
93.72
93.72
93.72
93,72
93,72
93.72
100.00
20 40 60 60 100 120 140 160 160 200
FREQUENCY
Figure 4-1
HISTOGRAM OF "NOT-DETECTED" EFFLUENT SETTLEABLE SOLIDS
VALUES DURING DRY CONDITIONS
-------
in all cases, regardless of the rainfall condition, were less
than 0.5 ml/1. Moreover, the overall effluent mean for all ponds
in both cases was equal to or less than 0.1 ml/1.
Histograms (frequency distributions) were prepared to
illustrate the distribution of the data. Figure 4-1 presents a
histogram for "not detected11 values for effluents during dry con-
ditions. These "not detected" values actually represent the dif-
fering detection limits reported by each company. The vertical
axis represents the midpoint value of the range examined for the
frequency calculation. For instance, on Figure 4-1, the hori-
zontal row of asterisks at 0.1 ml/1 indicate that a certain num-
ber of values (in this case, 207) were found in the data base at
a range of concentrations between 0.05 ml/1 and 0.15 ml/1. A
similar plot for "not detected" values during wet conditions
appears in Figure 4-2* No apparent difference was found between
wet and dry conditions. These plots clearly demonstrate that the
detection limit recorded by most companies is 0.1 ml/1; however,
this number did fluctuate in a small number of cases. The signi-
ficant number of values at 1.0 ml/1 were recorded by a facility
that also recorded a detection limit of 0.1 ml/1 for a substan-
tial number of samples. To summarize, the detection limit was
recorded as 6.1 ml/1 or less, approximately 94 percent of the
time "not detected", values were reported for effluent samples.
Histograms for detected values in pond effluents are
depicted in Figures 4-3 (dry) and 4-4 (wet). Over 71 percent of
the values were reported as 0.0 ml/1. For dry conditions, 100
percent of the values were less than or equal to 0.4 ml/1. Dur-
ing wet conditions, 95 percent were less than or equal to 0.5
ml/1. Thirteen values above 0.5 ml/1 were recorded by six of the
22 sites (13 samples in a total of 789 effluent samples). In
fact, four of the 13 highest values were reported by facility 101
in eastern Ohio. In addition to 115 acres of virgin and
A-50
-------
Table 4-15
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
EFFLUENT
VET CONDITIONS
Facility
13
15
25
25
25
33
33
37
38
85
101
123
181
183
184
185
186
187
191
191
Ova rail
Pond
1
2
3
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
Numbar of
13
12
3
12
14
64
61
17
3
30
26
6
32
16
39
24
12
12
11
11
413
Nuobar of
Da tact a
3
6
1
3
5
64
61
4
0
22
26
0
2
2
4
2
8
10
11
-II
245
Concancraciona (•!/!)
Hiniatun
<0.1
<0, \
0.0
<0.1
<0.1
0.0
0.0
<0.1
--_
0.0
0.0
..
<0»l
40*1
-------
Table 4-14
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER
WET CONDITIONS
Facility
15
IS
25
25
25
33
33
37
38
85
101
123
181
163
184
185
186
187
191
191
Overall
Food
1
2
3
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
Nu»b«r of
S*apl«*
13
13
2
12
15
62
61
17
5
30
39
6
34
24
30
24
12
12
11
12
436
Nunbor of
D*e*cti
2
1
1
11
10
62
61
9
4
27
39
4
14
4
9
8
6
10
11
12
307
Conccnera clone (•!/!)
Minima
<0.1
<0»1
<0. \
6.15
0.0
0.0
0.0
<0.1
<0.1
0.0
0.02
<0.1
<0*1
<0.l
-------
Table 4-13
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
EFFLUENT
DRY CONDITIONS
raclllty
15
15
25
25
25
33
33
37
38
85
.101
123
181
183
184
185
186
187
191
191
Overall
Pood
1
2
3
4
7
1
2
6
19
1
2
3
99
1
7
4
2
I
18
55
Nuubar of
Saupla*
25
18
3
18
22
26
22
28
10
20
7
9
18
26
25
20
33
33
3
1
367
Nuabar of
Datacti
2
4
0
6
3
26
22
8
0
15
7
0
0
0
1
1
20
25
3
1
144
ConcanCraCiona (•!/!)
Hiniaua
< .1
< .1
«
< .02
< a
0.00
0.00
< .1
•»•
0.00
0.00
• •
—
--
< .1
< .1
0.00
0.00
0.0
0.0
b.o
Ma an
^•M^MriH
0.06
0.09
••
0.08
0.06
0.00
0.00
0.31
«
0.02
0.08
••
«
••
0.06
0.05
0.02
0.01
0.0
0.0
0.06
Madlan
^^•P^^A^PW
< .1
< .1
• •>
< .1
< .1
0.00
0.00
0.40
..
0.00
0.05
«
«
••
< .1
< .1
0.00
0.00
0.0
0.0
HC
901
0.07
0.22
...
0.20
0.10
0.00
0.00
<1.0
—
0.05
0.30
«
«
«
< .1
< .1
< .1
< .1
0.0
0.0
MC
Maxima
0.20
0.40
< .1
0.20
0.20
0.00
0.00
<1.0
< .1
0.20
0.30
< .1
< .1
< .1
0.20
0.10
< .1
< .1
0.0
0.0
0.4
NC - Hoc calculated.
A-47
-------
Table 4-12
SETTLEABLE SOLIDS DATA BY FACILITY AND POND
RAW WASTEWATER
DRY CONDITIONS
Facility
15
15
25
25
25
33
33
37
38
85
101
123
161
183
184
185
186
187
191
191
192
192
Overall
Pond
1
2
3
4
7
1
2
6
19
1
2
3
99
1
7
4
2
1
18
55
4
6
Number of Number of
Saaple* Detects
24
16
3
19
21
25
20
28
10
20
20
9
8
27
24
20
32
33
2
2
4
3
372
3
3
2
2
7
25
20
7
8
16
20
1
5
0
1
0
20
25
2
2
3
3
175
Concent rat iona _£•!/!)
Mtninua
«0.1
<0.1
<0.1
<0»1
<0.1
0.00
0.00
-------
not recorded (Table 4-10) show elevated levels, which corresponds
to the increased flow of sediment to the pond. The effluent
values (Tables 4*9 and 4-11), however, are quite similar to the
effluent values for dry conditions, with one exception, Nickel
appears in a large number of effluent samples in Table 4-11. The
vast majority of the detected values for nickel, however,
occurred at one facility. Again, this is not unusual given the
specific soil characteristics at that facility and other factors
unique to each site.
As a result of the infrequent occurrence of the toxic
metals and the low concentrations encountered when detections did
occur, sampling and analysis for the toxic metals and manganese
beyond the first six months of the program were deemed unneces-
sary and thus terminated.
4.2.2
Settleable Solids
Data summaries for settleable solids are found by
facility and pond in Tables 4-12 through 4-15. These data are
presented by facility and pond to illustrate variation in influ-
ent characteristics and to examine any variation in performance
from pond to pond. Settleable solids were detected in 47 per-
cent of influent samples during dry conditions and in approxi-
mately 70 percent of the influent samples during wet conditions.
Detected values occurred in 39 percent and 59 percent of the
effluent samples for dry and wet conditions, respectively.
Examining the mean values for influent waters during
dry conditions, it can be seen that only five of the 22 ponds had
concentrations of settleable solids above 1.0 ml/1. For wet con-
ditions, eleven of the 20 ponds have mean influent values above
1.0 ml/1. This indicates that, for the remaining facilities,
reductions were difficult to quantify. The mean effluent values
A-45
-------
condition was not recorded or specified for roughly one third of
the analytical results* This stemmed primarily from incomplete
documentation of samples by industry personnel*
Examining the mean values for untreated wastewater
listed on Table 4-6, it can be readily seen that the toxic metals
all averaged well below 0*1 mg/1. In fact, the 90th percentile
was, in each case, less than or equal to 0*1 mg/1. As expected,
iron and manganese are somewhat higher, but still substantially
lower than the BPT limitations. The maximum values for all the
metals indicate some variation from site to site.
The sedimentation ponds provide reduction of the
metallic species, as shown on Table 4-7. Four of the toxic
metals were never detected, and an additional five appeared in
less than 10 percent of the samples taken, and then at very low
values. Copper and chromium were detected in a significant
number of samples, but always below 0.05 mg/1. Antimony was
detected in 17 of 79 samples taken (22 percent), and at values
higher than would be expected from the type of areas being
investigated. To determine if this unexpected result stemmed
from the analytical procedure, the concentrates were reanalyzed
by a different protocol. Results Indicate that when atomic
absorption was used in place of inductively coupled argon plasma
emission spectroscopy, antimony was not detected above 0.1 mg/1.
Zinc appears frequently in effluent samples from the majority of
facilities, however, the median concentration is very low at .013
mg/1, indicating that the high values occurred infrequently.
Indeed, further research showed that zinc occurred above 0.1 mg/1
only in a few isolated cases. This is to be expected given the
natural variation and common occurrence of zinc compounds In all
soils.
The results for the untreated wastewater during wet or
storm conditions (Table 4*8) and where the rainfall status was
-------
Table 4-11
METALS RESULTS FOR FOND EFFLUENT WITH RAINFALL CONDITION UNIDENTIFIED
>
U)
COMPOUND
ANTINONV ITOTALI
ARSENIC ITOTALI
BERYLLIUM iToTALl
CADMIUM ITOTALI
CHROMIUM
-------
Table 4-10
METALS RESULTS FOR RAW WASTEWATER WITH RAINFALL CONDITION UNIDENTIFIED
i
4=-
ro
COMPOUND
ANTinOKV < TOTAL*
AII5LN1C (TOTAL!
BERTLLIU* (TOTAL!
CA(u«iun ITOT*LI
CHRoniutf {Tor AH
COI'PEH UulAL*
LEAO (TUlAL)
ntncuitY ITOMU
NICKEL «Tl»TAl 1
scLCNiun HOTALI
S1LVCR IfOlALl
IIULtlUn |1(I1AU
^INC IIOI*L|
MftHGAHtSl UllMD
nton doun
TOTAL
Ntimitn
SAran.cs
65
63
ts
63
63
63
63
63
63
63
63
63
69
63
63
wunecft
TOTAL
OCTECTS
21
21
25
23
1*
2b
0
0
SH
0
0
9
5«
63
63
CONCCH1KAHONS 1M U6/L
tlCAN
84
61
3.2
10. a
19
*\
•>
»
591
-
•
6%. 3
793
7526
32067
hCUIAN
SO
20
0.5
2.5
5
3
•
-
51
-
-
bO.O
aa
1660
1*00
vos
211
1*6
».»
ZZ.fc
10
120
-
-
1*1«
-
*
127.2
2«nit
26900
9l9i|0
MAX
&69
%9|
15.0
02*0
173
233
< 30. t
< 40*0
1660
< 50. fl
< 5-0
199.0
Stftt
3^230
27aooo
-------
Table 4-9
METALS RESULTS FOR POND EFFLUENT DURING WET CONDITIONS
conpotiNO
AMTIffONV I'OTALI
AHStNtC (TOTAL!
OCHUt-JWl 1 TOTAL'
CAoftTun ITOTALI
CHRoniun norM.1
COPTER i TOTAL*
LlAD f TOTAL I
ntllCUflf (TOTAL!
NICKEL (TOTAL I
SttfWIU* ITOMLI
StLVCH IIOTALl
TMALLlUn (TQIALI
/INC (TOTAL*
nANCAMtSe (TQTALt
I«OH ITOIALI
TOTAL
MUHBLK
SAflTLtS
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
Mtinacft
IOIAL
UCTCClE
13
0
4
1
11
19
0
0
0
1
5
•
«*
TO
71
CONCCMTNATfONS IM U6/L
• fCAN
56
-
• *5
2.*
5
7
-
-
-
25
2.7
-
*3
442
17«
KUIAN
bt
-
• .5
2.9
3
3
-
-
-
25
2.5
-
1*
265
!•••
9tX
97
•
• .9
2.5
17
25
«.
•
-
25
2.5
-
54
984
*972
MAX
27«
< ••••
1*4
7.*
27
«4
< 3t-0
< 40. •
< 9»-«
42
7.2
-------
Table 4-8
METALS RESULTS FOR RAW WASTEWATER DURING WET CONDITIOHS
i
-t-
o
conrotttio
ANTinoMY I TOTAL!
AN SI NIC MOTALI
UCNVLLIWI < TO TALI
CAMUIJ* (10T*LI
CMRortiun HOTALI
COPI'CH (TOTAL)
LEAD I1OTALI
fltRcunv noTAti
NICKEL HOIAI I
SCLCNIim HOTALI
SILVCN 1 TOTAL 1
THALLIUM (TOTAL!
ZINC |fOt All
RAMGAMLSL IffllALl
IftON ItOlALl
TOTAL
MllMItt •
nUHIKR
SAHPLCS
73
73
T3
75
73
73
73
73
73
73
73
73
73
73
73
NifnOCN
vn**t
IWiflt
OLTCCT8
21
»
16
19
36
36
3
•
1*
3
4
•
t7
73
72
1
HtAN
66
50
1.7
6.a
29
34
17
•
62
26
2.7
-
937
l«7*
27894
:OMCtMTHATIO
HCDIAN
SO
20
• •9
2.9
3
3
19
-
29
29
2.9
-
39
662
3210
US IN UC/l
98*
153
82
3«7
1^.6
70
107
19
•
140
29
2.8
-
991
2792
89828
NAK
239
890
28*0
106.0
92*
791
92
< 40*8
H»»
70
6*9
-------
Table 4-7
METALS RESULTS FOR POND EFFLUENT DURING DRY CONDITIONS
COMPOUND
IOTAL
MunotN
SAMPLES
NurtHtn
TOTAL
UtTCClS
CONCENTRATIONS IN Ut/L
» ••*••••**•»"• V»** W W«^V *»«*•«•
ftCAN HEDIAN 9»«
V V • » • •* W ^» • * * • » ^^ * * V«* • ^ • V « •* » •
61 S« 112
ANfinoNT (TOTAL!
ARSENIC (TOTALI
OEftVLLiun (TOTAL)
CAOfltUft (TOTAL!
ciMtoniun iTOTAL!
COPtEfl ITOTAf I
LCAO ITOTALI
HERCUHY CTOTAL!
NICKCL IT01ALI
SELLNIUH IIOTAL!
SILVER IIOlALl
THALLIUR |TulAL!
2 INC |T01*L|
HAHCANCSL
IRON ITOlALI
79
79
79
79
79
79
79
79
79
79
79
79
79
79
17
D
5
3
19
0
0
3
2
3
61
79
77
• •6
2.7
S
&
32
25
2.6
29
396
A54
• •9
2*5
3
3
29
25
2.5
13
232
• *5
2,5
11
13
25
2.5
7ft
98«
22«t
3.2
37
9i
»•*•
97
87
7.1
113
-------
Table 4-6
METALS RESULTS FOR RAW WASTEWATER DURING DRY CONDITIONS
i
CO
GO
COMPOUND
ANTINOMY (10TALI
ANSCNIC IT01ALI
UCRVLLlUfl HOT AM
CAonum ITOTALI
CHiiomun doiALi
COPPCN (101 At I
LT.AO 1 TOTAL)
flLRCUNV ITOTALI
NICKEL (TOTAL)
SCLf-NlUn | TOTAL)
SILVCK (TOTAL*
THALLIUM IIOIAL)
2 IMC | TOTAL }
flANCAMCSL UOTALI
IHOW (TOTAL)
TOTAL
Human
SAKPLCS
as
fti
•3
Bi
Aif
as
A3
A3
A3
A3
A3
A3
A]
A3
A3
NunucH
TOTAL
UtTCCfS
17
3
fc
3
11
20
4
1
b
3
3
0
69
A2
AO
CONCENTRATIONS IN UWL
HCAN
67
26
0.6
2.7
6
5
17
20.2
31
26
2.6
-
63
43A
!Ab7
MEDIAN
50
20
«.s
2.6
3
3
IS
20.0
25
25
2.5
-
16
20*
310
90S
too
*>0
0,6
2.5
7
1*
16
20.0
«&
25
2.5
-
«5
1036
4A10
flAX
250
15
5.3
16.0
111*
2A
103
40.0
110
96
6*2
<100*0
10&0
9690
^73»«
-------
Table 4-5 (Continued)
Facility
COMPARISON OF OSM "REQUIRED" VOLUMES AND ACTUAL FOND VOLUMES
State
Pond
OSM
"Required11 Volume
Acre-Feet
Actual Pond
Volume
Acre-Feet
191
191
192
192
AL
AL
WY
WY
18
55
4
6
18.4 -
127.4 -
6.1 -
4.8 -
23.1
161.8
8.5
6.3
20
125
13.6
16.8
Does the Pond
Comply With
OSM Criterion?
Yes/No
No
Yes
Yes
I
L*J
-------
Table 4-5
COMPARISON OF OSM "REQUIRED" VOLUMES AND ACTUAL FOND VOLUMES
>
Facility
State
Pond
OSM
"Required" Volume
Acre-Feet
Actual Pond
Volume
Acre-Feet
Does the Pond
Comply With
OSM Criterion?
15
15
25
25
33
33
37
38
85
101
123
181
182
182
183
184
185
186
187
WV
WV
OH
OH
IN
IN
IL
KY
IL
OH
IL
KY
MT
MT
WV
WV
WV
PA
PA
1
2
4
7
1
2
6
19
1
2
3
99
1
2
1
7
4
2
1
35.6 -
15.0 -
19.1 -
10.6 -
30.6 -
8.1 -
248.8 -
22.6 -
16.5 -
22.7 -
710.2 -
6.7 -
3.4 -
2.2 -
11.8 -
4.6 -
20.8 -
1.3 -
12.0 -
48.3
19.7
23.7
12.8
41.1
11.4
349.5
36.9
23.8
28.6
1020.8
9.5
5,2
3.4
15.0
6.1
26.4
1.7
15.1
2.6
1*6
1.3
1.5
48.5
19.4
32.2
28.6
16.2
28.2
215
3.9
13.5
10.0
3.1
1.9
6.6
3.3
20
No
No
No
No
Yes
Yes
No
Yes/No
No
Yes/No
No
No
No
No
No
No
No
Yea
Yea
-------
where: • V is volume, in acre-feet.
• A is the total area drained to the pond, in acres.
• R is the runoff depth, in inches of water.
A sample calculation of this method is found in
Appendix B.
Table 4-5 presents the results for all ponds and indi-
cates which facilities meet the OSM pond volume criterion and
which do not* Those marked "Yes/No" fall between the upper and
lower boundaries of the necessary volume, indicating that the
pond may or may not be adequately sized according to the OSM
standard.
4.2
Vastewater Characterization
During the course of this program, two basic periods
were characterized: (1) base flow or "dry11 conditions (no rain),
and (2) rainfall or "wet11 conditions (day of rainfall or day
after rainfall). The wastewater characteristics from the dry
period represent the data base for reclamation areas, while the
results from samples taken during wet conditions were used to
augment available data on effluent qualities during various storm
events.
4.2.1
Toxic and Nonconventional Metals
Summaries of toxic and nonconventional metals analyzed
for during the program are presented in Tables 4-6 through 4-11.
These tables present, data for influent and effluent during wet or
rain conditions and during dry or baseflow conditions. It should
be noted, as shown on Tables 4-10 and 4-11, that the rainfall
A-35
-------
Table 4-4
RUNOFF DEPTH IN INCHES FOR SELECTED
CURVE NUMBERS AND RAINFALL AMOUNTS
i
OJ
-fcr
Rainfall
(Inchea)
1.0
1.2
1.4
1.6
1.8
2.0
2.5
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
Runoff Curve Number
60
0
0
0
0.01
0.03
0.06
0.17
0.33
0.76
1.30
1.92
2.60
3.33
4.10
4.90
5.72
6.56
65
0
0
0.02
0.05
0.09
0.14
0.30
0.51
1.03
1.65
2.35
3.10
3.90
4.72
5.57
6.44
7.32
70
0
0.03
0.06
0.11
0.17
0.24
0.46
0.72
1.33
2.04
2.80
3.62
4.47
5.34
6.23
7.13
8.05
75
0.03
0.07
0.13
0.20
0.29
0.38
0.65
0.96
1.67
2.45
3.28
4.15
5.04
5.95
6.88
7.82
8.76
80
0.08
0.15
0.24
0.34
0.44
0.56
0.89
1.25
2.04
2.89
3.78
4.69
5.62
6.57
7.52
8.48
9.45
85
0.17
0.28
0.39
0.52
0.65
0.80
1.18
1.59
2.46
3.37
4.31
5.26
6.22
7.19
8.16
9.14
10.12
90
0.32
0.46
0.61
0.76
0.93
1.09
1.53
1.98
2.92
3.88
4.85
5.82
6.81
7.79
8.78
9.77
10.76
95
0.56
0.74
0.92
1.11
1.29
1.48
1.96
2.45
3.43
4.42
5.41
6.41
7.40
8.40
9.40
10.39
11.39
98
0.79
0.99
1.18
1.38
1.58
1.77
2.27
2.78
3.77
4.76
5.76
6.76
7.76
8.76
9.76
10.76
11.76
NOTE: To obtain runoff depths for other curve numbers and rainfall amounts not
shown in this table, use an arithmetic interpolation.
Source: Skelly and Loy Engineers, A Compliance Manual—Methods for Meeting OSM
Requirements» McGraw-Hill, Inc., New York, New York, 1979, p. 6-f
-------
Land Cover
Table 4*3
SCS RUNOFF CURVE NUMBERS
Condition A
Soil Group
B C
Virgin Lands
Forests
Farmsteads
Meadow
Pasture/Range
Regraded - Revegetated
Close Seeded Legumes
(Contoured & Terraced)
Small Grains
(Contoured & Terraced)
Row Crops
(Contoured & Terraced)
Fallow
Cleared Unvegetated
Dirt Roads
Hard Surface Roads (or
Paved Surfaces
Source: Skelly and Loy E
for Meeting OSM
Poor
Fair
Good
—
Good
Fair
Poor
Good
Poor
Good
Poor
Good
•*•
— —
Pit) —
--
Ingineers , A
Requirements
45
36
25
59
30
49
63
51
61
59
66
62
77
72
74
98
Compliance
66
60
55
74
58
69
73
67
72
70
74
71
86
82
84
98
77
73
70
82
71
79
80
76
79
78
80
78
91
87
90
98
83
79
77
86
78
84
83
80
82
81
82
81
94
89
92
98
Manual- -Methods
( McGraw-Hill,
Inc.,
New
York, New York, 1979, p. 6-32.
A-33
-------
Many methods are available to arrive at the "necessary"
pond volume, but only the method used is detailed below. An
alternate method is presented in Appendix B.
The selected method uses a Soil Conservation Service
(SCS) runoff curve number. The runoff curve number is based on
establishing a relationship between rainfall and runoff volumes.
This depends upon the soil and land cover types.
Four hydrologic soil groups are identified which define
the potential infiltration and water transmission rates:
A (Low Runoff Potential). High infiltration rate
and water transmission rate. Example: sands,
gravel.
B Moderate infiltration rate and water transmission
rate. Example: sandy loam.
C Slow infiltration rate and water transmission
rate. Example: clay and silty loam.
D (High Runoff Potential). Very slow infiltration
rate and water transmission rate. Example: tight
clay or clay pan (soil with permanent high water
table).
Using the land cover type supplied by industry and soil
type, Table 4-3 can be used to determine the runoff curve number
for each type of drainage area. A composite runoff curve number
for an entire drainage area can be determined by calculating a
weighted average of the runoff curve numbers from the individual
drainage areas. Using this composite curve number and the amount
of rainfall associated with a given storm event, runoff depth for
the drainage area is obtained (in inches of water) as shown on
Table 4-4. The runoff volume is then calculated as follows:
V - A x R/12
A-32
-------
I
U)
Table 4-2 - Continued
SIMMAKY OF INPUTS REQUIRED TO CALCULATE QSM PCM) VOLUME
10-Year, 24-4Iour
Precipitation
Event Boil
Drainage Area (Acres)
Facility Pond
Code State Number (Total Inches)* Type** Mined
183
184
185
186
187
191
191
192
192
wv
wv
w
PA
PA
AL
AL
WY
WY
1
7
4
2
1
55
18
4
6
3-5 - 4.0
3.5 - 4.0
3-5 - 4.0
3.5 - 4.0
3.5 - 4.0
6.0 - 7.0
6.0 - 7-0
2.5 - 3-0
2.5 - 3.0
C
Ctt
Bt*
C
C-D
C
B-C
B-C
C
D
Actively
Mined
0
0
NS
NS
NS
NS
NS
NS
NS
Disturbed
Area
31
15
53.8
12
70
350
61.5
41
12
Virgin
Area
76
60
50
0
26
130
3.5
41
33
Slope
of
Area
39
50
50
150
14
14
4
3
2
Composite Pond
Runoff Curve Area
Numbers (Acres)
75.1
64.0
75.0
75.2
77.9
74.0
76.1
80.0
86.3
0.74
. 0.15
0.84
0.50
3.10
8.30
0.94
2.22
6.86
Calculated Pond
to Meet "OSM" D
(Acre-Feet)
11.8
4.6
20.8
1-3
12.1
127.4
18.4
6.1
4.8
- 15.0
- 6.1
- 26.4
- 1.7
- 15-1
- 161.8
- 23.1
- 8.5
- 6.3
•Data from "A Compliance Manual—Methods for Meeting OSM Requirements," Skelly and Loy Engineers, McGraw-Hill, Inc.,
New York, New York, 1979, p. 6-34.
**See text for explanation of soil types.
TtDIsturbed.
t*Virgin.
-------
Sample Calculation - Method 1
Facility 192
Campbell County, 'Wyoming
Sedimentation Trap #4 (Soil Type estimated as C)
Using curve numbers from Table 4-3, the composite curve
number is obtained as follows:
Type of
Land Cover
Pond
Range
Revegetated -
Seeded
Total
Area
(Acres)
2.22
41
38.78
82.00
Individual
CN
100
79
80
Fractional
Area
0.027
0.500
0.473
1.000
Composite
CN
2.7
39.5
37.8
80.00
Thus, the composite curve number is 80.0 for this
drainage area. A 10-year, 24-hour storm for facility 192 is 2.5
to 3.0 inches of precipitation. For 2.5 inches, Table 4.4 shows
that 0.89 inches of runoff reach the sedimentation basin.
The runoff volume is then calculated as follows:
V - A x R/12
• (82 acres) x (0.89 in./12 inches/ft.)
- 6.08 acre-feet
The above runoff volume corresponds to the pond volume
required to contain a 2.5 inch precipitation event at facility
192. Therefore, the required pond volume for a 10-year, 24-hour
storm event (i.e., 2.5 to 3.0 inches) -for pond 4 at facility 192
is 6.08 to 8.54 acre-feet.
A-81
-------
Runoff volume may also be determined using the follow-
ing equation:
V - P/12 x [(AI x GI) + the runoff coefficient for the active area.
o A2 is the drainage area which commingles with
drainage from the active area, in acres. This
includes runoff from virgin areas and areas under
reclamation which drain to the pond.
o C2 is the runoff coefficient for areas which
commingle drainage from the active area.
The following may be used to determine GI and C2:
Sandy Loam Clay and Loam
Active Mining Area 0.3 0.5
Virgin Land and Land 0.1
Under Reclamation
0.3
0.6
0.4
The above values are increased by 0.1 for slopes rang-
ing from 5 to 10 percent, and increased 0.2 for slopes ranging
from 10 to 30 percent.
Since seven of the ponds involved have drainage areas
with slopes much steeper than 30 percent, the first method is
applied in order to keep the calculations on a uniform basis.
A-82
-------
REPORT 2
REASSESSMENT OF THE SELF-MONITORING DATA BASE ACCORDING TO THE AMENDED
10-YEAR, 24-HOUR POND DESIGN VOLUME FOR COAL MINES
September 1982
Prepared by:
Allison Phillips
Effluent Guidelines Division
Office of Water Regulations & Standards
U.S. EPA
Washington, D.C. 20460
A-83
-------
-------
PURPOSE
The treatment facility design volume necessary to qualify for alternate
effluent limitations during precipitation events was amended on May 29,
1981 to that proposed on January 13, 1981 for the coal mining regulations.
This amendment modified the design volume of a pond by excluding from
consideration waters from undisturbed areas which drain into the treatment
facility.
The self-monitoring survey established the data base in support of
the 0.5 ml/1 settleable solids effluent limitation for coal mines during
precipitation events and for reclamation areas. Analyses of the results
of this survey were completed before the amended definition for a pond
size was proposed. Thus, the technology basis in support of the 0.5
ml/1 limitation was a 10-year, 24-hour porid according to the January 13,
1981 proposal. Therefore, the data had to be reevaluated after the
amendment to reflect the new pond size definition. The analysis to
assess the number of 10-year, 24-hour ponds (according to the new definition)
is presented below:
ANALYSIS:
Pond design data and factors used to determine the required pond size are
taken from Report 1 of this Appendix.
Assumptions - 1} The curve (CN)* numbers are averaged for each type of
land cover according to soil group (See Table 1).
2) All "disturbed areas" are equal to "regraded or
revegetated" land as presented in the CN land cover
groups.
3) All "actively mined areas" are equal to "cleared
unvegetated" land as presented in the CN land cover
groups.
Data from Table 4-2 in Report 1 was used to calculate the "new" 10-year,
24-hour ponds. The calculations were performed according to the example
in Appendix B of Report 1 except that the virgin land areas were deleted from
consideration.
*Upper or lower limits were calculated wherever it was unnecessary according
to comparison with the actual volume. (For example, for pond 25-7 where
the actual volume is 1.5 and the lower limit for the required volume is
10.13, the upper limit does not have to be calculated in order to determine
whether or not the pond is a 10-year, 24-hour pond .)
A-85
-------
An example calculation is given below:
Facility 15-1
Soil type estimated as B-C.
Using averaged curve numbers from Table 1, the composite curve
number is obtained as follows:
Type of Land
Cover
Area
(Acres)
Individual
CN
Fractional
Area
Composite
CN
Pond
Disturbed
.44
18.06
100
77
2.4
75.2
Thus, the composite curve number is 77.6 or 78 for this drainage area. A
10-year, 24-hour storm for facility 15-1 is 3.5-4 inches of precipitation
as shown in Table 4-2 of Report 1. For 3.5 inches, Table 4-4 of Report 1
shows that 1.52 inches of runoff reach the sedimentation basin.
The runoff volume is then calculated as follows:
V = A x R/12
= (18.5 acres) x (1.52 in/12in/ft)
=2.34 acre feet
The above runoff volume corresponds to the pond volume required to
contain a 3.5 inch precipitation event at facility 15-1. Therefore, the
required pond volume for a 10-year, 24-hour storm event (i.e., 3.5-4.0
inches) for this pond is 2.34 to 2.91 acre feet.
Table 4-5 of Report 1 shows that the actual pond volume for facility
15-1 is 2.5 acre feet. This is within the required pond volume of 2.34
to 2.91 acre-feet and thus, this pond is considered to be a 10-year, 24-
hour pond.
RESULTS:
All the ponds were evaluated according to the above calculations which
resulted in the 11 ponds determined to be 10-year, 24-hour ponds as shown
in Table 2.
A-86
-------
Land Cover
Regraded - Revegetated
Close Seeded Legumes
{Contoured & Terraced)
Small Grains
(Contoured & Terraced)
Row Crops
(Contoured & Terraced)
Fallow
TABLE 1
RUNOFF CURVE NUMBERS
Condition
Poor
Good
Poor
Good
Poor
Good
Soil Group
A A-B* B B-C C C-D D
Ave.**
63
51
61
59
66
62
77
63
72
74
98
68
55
67
65
" 70
66
80
6/
73
67
72
70
74
71
86
/3
82
84
98
78
72
76
74
77
75
90
//
87
80
76
79
78
80
78
91
80
87
90
98
82
79
81
80
81
80
93
82
83
80
82
81
82
81
94
83
89
92
98
Cleared Unvegetated
Dirt Roads
Hard Surface Roads (or Pit)
Paved Surfaces
*Where "A-B" soil type was submitted, the median curve number between soil
types was calculated and used in the averaging.
**These average curve numbers were used in the calculations.
Source: Skelly and Loy Engineers, A Compliance Manual—Methods for Meeting
OSM Requirements, McGraw-Hill, Inc., New York, New York, 1979, p. 6-
"ST.
A-87
-------
TABLE 2
10-Year, 24-Hour Ponds
Pond
15-1
15-2
25-3
25-4
25-7
33-1
33-2
37
38
85
101
123
181
182-1
182-2
183
184
185
186
187
191-55
191-18
192-4
192-6
Actual Volume Required Volume 10-Year, 24-Hour Pond?
2.6
1.6
No data
1.3
5
2.34 - 2.91
1.26 - 1.58
submitted on design
1.
48,
19,
32,
28,
16,
28,
215
3.9
33.5
10.0
3.1
1.9
6.6
3.3
20
125
20
13.6
16.8
4.74
10.13
47.6 -
17.34 -
6.89 -
,14
,05
,40
104.46
15.83
4.51
1.79
5.91
*
3.08
7.18
67,4
13.18
24.02
19.16
197.58
8.27
35
50
48
55
- 9.15
- 2
29
12.37
129.5
20.19
- 2.26
yes
yes
no
no
no
yes
yes
no
yes
yes**
yes
yes
no
yes
yes
no
yes**
no
yes
yes
yes
yes
yes
yes
*Upper or lower limits were calculated wherever it was unnecessary according
to comparison with the actual volume. (For example, for pond 25-7 where
the actual volume is 1.5 and the lower limit for the required volume is
10.13, the upper limit does not have to be calculated in order to determine
whether or not the pond is a 10-year, 24-hour pond.)
**An error of at least 10% is assumed in these calculations because of
the 1} vast amount of land involved, 2) difficulty in determining pond
depth and therefore pond volume, 3) difficulty in determining precise
amount of runoff, 4} error in precipitation estimates for 10-year, 24-
hour storms.
A-88
-------
REPORT 3
STATISTICAL SUPPORT FOR THE PROPOSED
EFFLUENT LIMITATION OF 0.5 ml/1
FOR SETTLEABLE SOLIDS IN THE
COAL MINING INDUSTRY
September 1982
Prepared by:
Office of Analysis and Evaluation
Office of Water Regulations and Standards
U.S. EPA
Washington, D.C. 20460
A-89
-------
-------
DATE:
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
2 8 1982
SUBJECT: Statistical Support for the Proposed Effluent Limitation of
0.5 ml/1 for Settleable Solids in the Coal Mining Industry
FROM: RB Clifton Bailey, Statistician
Program Integration and Evaluation Staff"fVfl-586)
T0: Allison Phillips, Project Officer
Energy and Minerals Branch (WH-552)
Analysis of the data for settleable solids from the coal mining industry
confirms the proposed limitation of 0.5 ml/1 is consistent with Agency policy
for effluent guidelines. The limitation is supported by data from sedimentation
ponds which serve active mine areas and/or reclamation areas and met the size
criterion as specified in the May 26, 1981 amendment to the coal mining effluent
guidelines regulations proposed on Oaunary 13, 1981. The settleable solids
limitation applies at active mine sites to effluent affected by precipitation
events and at reclamation sites to effluent regardless of weather conditions.
Reclamation area discharges are minimal during dry weather conditions so that
effluent discharge occurs almost exclusively as the result of run off from
precipiation. The data and analysis that support the limitations are
described in this memorandum.
Data
The data used here were obtained in a one year self monitoring study of the
coal mining industry. The study was conducted to obtain data that would support
an evaluation of the effluent limitation proposed for settleable solids. A
total of 24 sedimentation ponds were included in the self monitoring study. These
ponds were selected to span the range of geographical and operational conditions
in the indsutry. A comprehensive summary of the design and operation of the 24
ponds is contained in Coal Mining Industry Self-Monitoring Program, Radian
Corporation, May, 1981. Data were collected at these ponds from September, 1979
to September, 1980 and classified as either "wet conditions" or "dry conditions."
"Wet conditions" refers to data collected on the day of and day immediately
following a precipitation event while "dry" refers to data collected at other
times. The evaluation of the proposed limitation of 0.5 ml/1 for settleable
solids is based on the observations taken only during wet conditions because
the limitation applies at active mine effluents affected by precipitation
events and, although reclamation areas are subject to the limitation under all
weather conditions, only during wet conditions are they likely to have an
effluent discharge.
The Imhoff cone method was used to measure settleable solids in the self-
monitoring study. The method is described in Standard Methods for the Examina-
tion of Water and Wastewater and 304(h) of the EPA's "Methods for Analysis of
Water and Wastewater" as having a "practicable lower limit of measurement" of
"about 1 ml/1." The proposed limitation of 0.5 ml/1 is below this value. In
fact, all facilities with effluent discharge in the self monitoring study
reported values well below 1.0 ml/1. Consequently, a study was conducted to
examine the detection limit for settleable solids using the Imhoff cone method
EPA Form 1320-6 (R«v. 3-76)
A-91
-------
-2-
on coal mining effluent. The study is described in Coal Mine - Drainage
Precision and Accuracy Determination for Settleable Solids at Less Than 1.0
the method of detection
an arithmetic average of
were made (at least one
ml/1 with an arithmetic
prepared for EPA by Hydrotechnic Corporation, August, 1982. The study
involved field and laboratory determinations of the method detection limit
using samples collected at 8 different sedimentation ponds. The study followed
the procedure described in "Definition and Procedure for the Determination of
the Method Detection Limit" [1/21/81 Revision 1.11, by EMSL-CI, EPA]. There
were 8 field determinations (one from each pond) of
limit which ranged from 0.04 ml/1 to 0.40 ml/1 with
0.22 ml/1. A total of 10 laboratory determinations
from each pond) which ranged from 0.05 ml/1 to 0.20
average of 0.12 ml/1. The results of this study support the conclusion that
it is possible to measure settleable solids values below 1.0 ml/1. As a result
of this study the method detection limit for settleable solids in coal mining
was set conservatively to be 0.4 ml/1, the maximum of the field determinations.
The self-monitoring data are summarized by pond in Table 1. The ponds
are identified by a facility number F and a pond number P as P.P. Thus, for
example, pond 2 at facility 15 is designated by 15.2. These data were evaluated
and several adjustments were made for the purpose of analyzing the proposed
limit. Ponds 101.2 and 191.55 were excluded from the evaluation of the limita-
tion because of design and operational defects as described in the Radian
Report and further documented in the Record (Memo to the Effluent Guidelines
Division from Radian: Marc Papai to Allison Wledeinan, September 21, 1982).
Four ponds that were included in the study, 182.1, 182.2, 192.4 and 192.6 had
no discharge and thus yielded no effluent data. One of the twenty-three ponds
originally selected for study, pond 25.3 was taken out of operation in March
1980 and replaced by pond 25.4. In some cases, duplicate observations on the
same day were reported at ponds 25.3, 25.4, 25.7, 37.6, 184.7 and 185.4.
These values were below the proposed limitation of 0.5 ml/1 or reported as
nondetect (ND) or trace (TR). In Table 1 these duplicates have been counted
as a single determination for that day. This approach is conservative and
consistent with the study protocol. Counting the duplicates as separate obser-
vations would give the misleading appearance of higher rates of compliance
since these values were below the proposed limit. Values reported as trace
(TR) were not counted as exceeding the limit. For pond 37.6, several measurements
of "ND 1" were reported during wet conditions. This is a convention for
identifying measurements below 1 ml/1. No additional values were reported in
this manner after June 12, 1980. Values of ND 0.1, 0.15, and 0.3 ml/1 were
also reported for this pond. The observations reported as ND 1 have been
counted as not exceeding the proposed limitations of 0.5 ml/1.
Analysis
The objective of this analysis is to establish whether the proposed limitation
is consistent with the usual Agency policy of 99% compliance for effluent limita-
tions guidelines. That is, if the data demonstrate that 0.5 ml/1 is met roughly
99% of the time by sedimentation ponds that satisfy design criteria, then the
proposed limit is a reasonable regulatory value.
A-92
-------
-3-
TABLE 1
FREQUENCY OF EFFLUENT SETTEABLE SOLIDS VALUES (ml/1) EXCEEDING THE
0.5 ml/1 LIMITATION AS REPORTED BY
COAL MINING FACILITIES DURING WET CONDITIONS
Pond
*15.1
*15.2
25.3
25.4
25.7
*33.1
*33.2
37.6
*38.19
*85.1
°*101.2
*123.3
181.99
t*182.1
t*182.2
183.1
*184.7
185.4
*186.2
*187.1
*191.18
°*191.55
t*192.4
t*192.6
TOTAL
# of Observations
> 0.5
2
0
0
0
0
0
0
0
0
0
5
0
0
0
0
1
0
2
0
0
2
1
0
0
13 (7) ((4))
Total
of Observations
13
12
3
13
16
66
65
17
5
30
42
6
63
0
0
16
30
24
12
12
11
11
0
0
467 (414) ((262))
* Satisfies size criterion.
t No discharge.
0 Deleted from analysis (see text).
() Values in parentheses are totals with ponds 101.2 and 191.55 deleted.
(()) Values in double parentheses are totals for ponds which exceed size
criterion with ponds 101.2 and 191.55 deleted.
A-93
-------
-4-
The data shown in Table 1 provide the basis for the analysis of the proposed
limitation. The number of measurements from each pond is variable because the
precipitation events for each pond vary. Data such as this are referred to as
clustered, i.e., the sampling days are clustered by pond. If the proportion of
sampling days with values exceeding 0.5 ml/1 is roughly 1% or less, then the
proposed limit would be consistent with the 99% compliance criterion. The
estimation of proportions for clusters is discussed in Cochran, W.G., Sampling
Techniques, 2nd Edition, Wiley and Sons, 1963, pp. 64-70, The analysis employed
here follows Cochran's recommendations.
The overall proportion, p, exceeding the limit is estimated by
P « X/N,
where X is the total number of observations exceeding the limit and N is the
total number of observations over all ponds. The variance of p is approximated
by
-------
-5-
proportion p exceeding 0.5 ml/1 and the standard error of p. The estimates
are
p = 4/262 = 0.0153
and
S.E. (0.0153) = 0.0121.
The value of the test statistic is
Z0 = (0.0153 - 001)70.0121 = 0.44.
The probability of exceeding this value for Z0 is approximated by
Probability { Z > 0.44 } = 0.330
where Z is a standardized normal variate (Tabled values for standardized normal
variates are given in most statistics texts. See, for example, Walpole, R.E.
and R.H. Myers, Probability and Statistics for Engineers, 2nd Edition,
MacMillian, 1978, Table IV, p. 513).Since the probability associated with the
observed value of Z0 for the ponds meeting the size criterion is not small, the
data do not demonstrate an exceedance rate for the proposed limit that is signi-
ficantly different from 0.01. Therefore, the data support the conclusion that
the 0.5 ml/1 value is consistent with the 99% compliance criterion.
Analysis of Ponds Without Regard to Size Criterion
When pond size is disregarded, the data still show a high rate of compliance
with the proposed limit of 0.5 ml/1. This result is based on the analysis of
the data for a total of seventeen ponds, without regard to size, (see Table 1;
NB, data for 25.3 and 25.4 were combined because one was a replacement for the
other). From the 17 ponds there are a total of 414 observations of which 7
exceeded the limit. That is, 98.31% of the observations satisfy the proposed
limitations. Now the estimate of the exceedance rate fl is
with
Thus,
and
p * 7/414 = 0.0169
S.E. (0.0169) * 0.00939,
Z0 = (0.0169 - 0.01J/0.00939 * 0.73
Probability { Z > 0.73 } * 0.233.
Therefore, when data from all ponds without regard to size are considered,
the observed exceedance rate is not significantly different from 0.01 and the
proposed limit is judged to be consistent with the 99% compliance criterion.
A-95
-------
-6-
Conclusions
Analysis of the available settleable solids data from coal mining
sedimentation ponds demonstrates that the proposed limit of 0.5 ml/1 is cons-
istent with Agency policy for effluent guidelines of 99% compliance. Statistical
analysis shows that the observed exceedance rate is not significantly different
from 1%. This conclusion holds regardless of whether or not the size criterion
for ponds specified in the proposed regulation is considered. Therefore, the
0.5 ml/1 settleable solids value is a reasonable and practicable limitation.
A-96
-------
APPENDIX B
COAL MINE DRAINAGE -
PRECISION AND ACCURACY DETERMINATION
FOR
SETTLEABLE SOLIDS AT LESS THAN 1.0 ml/1
B-i
-------
-------
COAL MINE - DRAINAGE
PRECISION AND ACCURACY DETERMINATION
FOR
SETTLEABLE SOLIDS AT LESS THAN 1.0 ML/L
Prepared for:
U.S. Environmental Protection Agency
Effluent Guidelines' Division
Energy and Mining Branch
M Street, S.W. (WH-552)
Washington, D.C. 20460
August 1982
Prepared by:
Hydrotechnic Corporation
1250 Broadway
New York, New York
B-iii
-------
-------
Contents
Page
I. Background B-l
II. Purpose B-l
III. Procedure B-2
IV. Mine Ponds B-3
V. Results B-4
VI. Conclusions B-5
Reference 1 - Settleable Matter Procedure B-9
Reference 2 - Picture of an Imhoff Cone . B-13
Reference 3 - Method Detection Limits SP-SP
Reference Articles B-17
Reference 4 - Field Results - Data Sheets B-39
Reference 5 - Laboratory Results ..... . . B-51
B-v
-------
-------
I. Background
In the proposed Coal Mining Point Source Category Effluent
Limitations Guidelines (40 CPR Part 434, May 29, 1981), Sections
434, 52, 53, 55 and 63, prepared by the U.S. Environmental Protec-
tion Agency, a limit of 0.5 ml/1 for settleable solids was speci-
fied for discharges from reclamation areas for BPT, BAT, NSPS and
during precipitation events for active area surface drainage.
This limit of 0.5 ml/1 was established based on the results of
self-monitoring programs in which various, mines sent settleable
solids effluent data to the U.S. EPA. Settleable solids readings
ranged from "0" to 1.0 ml/1.
The method employed to measure settleable solids is the
volumetric method outlined in Standard Methods and 304 (h) of the
Agency's "Methods for Analysis of Water and Wastewater." However,
the method for settleable matter determination, specified in these
publications, states that "the practical lower limit of measurement
is about 1 ml/1."
The purpose of this study was to further investigate the
precision and accuracy of measuring settleable solids below 1.0
ml/1. The results determined the method detection limit for
settleable solids to be 0.4 ml/1.
Purpose
In order to determine the variability and repeatability of
settleable solids measurements around 0.5 ml/1, a test program was
planned to develop a precision and accuracy determination for the
measurement of less than 1 ml/1 of settleable solids for active
area and reclamation area discharges from coal mines.
Eight pond influents and effluents were sampled and settleable
solids tests were run for each pond. Since overflows during rainfall
B-l
-------
periods could not be practically obtained, pond influents were used
to spike pond effluents in order to obtain settleable solids of
less than one ml/1 for the purpose of this determination. Concurrent
measurements and statistical analyses were also conducted on the
samples by the Agency's Environmental Monitoring and Support Labora-
tory in Cincinnati, Ohio.
III. Procedures
To determine the variability at levels around 0.5 ml/1 settle-
able solids, a certain analytical and statistical methodology was
employed. This program involved taking eight samples from various
mine drainage and mining activities (varying in geographical and
soil characteristics, etc.) which were collected for study and
measurement. Seven replicates of each sample were measured simulta-
neously in the field. The samples were also measured for pH. In
cases where the effluent levels from either settling ponds or mine
drainage treatment facilities were significantly less tha 0.5
ml/1, the Influent was used to spike the effluent to provide a
level of effluent within the desired range for determining variabil-
ity, precision, and accuracy. The replicates of each sample were
then recombined into one container and shipped to the Cincinnati
Laboratory in 7 to 8 liter volumes. The laboratory then also ran
seven replicates on each sample by the volumetric method.
The Industry was contacted prior to this study and, in most
cases, made concurrent measurements in the field. This provided
three independent measurements, in the field, for most samples.
The analytical method was as specified in the EPA adopted
Standards Methods procedure for settleable matter (See Reference 1).
This method employs an Imhoff cone (illustrated in Reference 2)
for analysis. All the field data was forwarded to the Environmental
Monitoring and Support Laboratory in Cincinnati (EMSL) where standard
B-2
-------
calculations were performed to determine the lower levels of detec-
tion and variability. The same statistics were performed on the
laboratory results. The calculation procedures are described in
Reference 3.
IV. Mine Ponds
Three mine ponds in the East and five in the West were tested.
Mine Pond No. 1 - The pond is a preparation plant slurry pond
associated with a surface mine and is located
in Central West Virginia.
Mine Pond No. 2 - The pond is a silt control structure downstream
of a slurry dam located at a deep mine site
in West-Central Ohio.
Mine Pond No. 3 - The pond is used to settle treated AMD and
is located in West-Central Pennsylvania.
Western Miners
All ponds tested were located in North Western Colorado.
Mine Pond No.
- The pond collects water mainly from a
reclamation area. Some water also enters
from a disturbed area,
Mine Pond No. 5 - This pond collects runoff from an active
mining area and from surrounding disturbed
areas.
Mine Pond No. 6 - Two ponds receive water discharging from a
coal crusher building and the area around the
building.
B-3
-------
Mine Pond No. 7 - This pond receives runoff from a partially
revegetated reclamation area. The flow en-
ters the pond from various drainage ditches.
Mine Pond No. 8
Water from an active area is pumped to this
pond and runoff from a reclaimed area is
also collected in the pond. The water from
this pond discharges to a secondary pond
before final discharge to the receiving wa-
ters.
V. Results
A summary of the results obtained in the field and in the
laboratory are presented in Table I. The complete data is presented
in References 4 and 5» It can be seen that the values obtained in
the field were higher than the laboratory results in all but one
case. This difference, in the case of the higher field values, was
probably due to the physical set-up for obtaining the results in
the field. The field set-up was rather crude and the Imhoff cone
holder may not have been perfectly level when the tests were run.
In addition, a magnetic stirrer was not available for mixing
the sample and, in accordance with Standard Methods, the cones were
only stirred once after forty-five minutes to loosen solids which
had deposited on the sides of the cone. No attempt at "leveling"
wes made in the field. The leveling procedure, described in Appendix
B, could have had the effect of reducing the effects of hindered
settling, thus reducing the apparent amount of settleable solids
present.
For Mine Pond No. 3, the field measurements of settleable
solids were significantly lower than the laboratory readings. This
pond was used to settle neutralized acid mine drainage in contrast
to the other ponds which removed solids carried by storm runoff arid
dry weather drainage. The neutralized AMD effluent contains iron
-------
hydroxides which, under certain conditions, form a voluminous
floe. During the field tests only a "pin-point" floe was observed
in the Imhoff cones for Mine Pond No. 3 in contrast to the heavy
floe reported for the laboratory results. The heavy floe formed
in the laboratory could have been caused by the use of the magnetic
stirrers which may have produced a flocculating action. In the
field the 2.5 gallon containers were vigorously shaken which
probably broke up the floe into pin-point "size".
The "large" floe particles could have caused the hindered
settling because of entralnment of water due to the clustering of
the large floe particles. In contrast, the pin-point floe may have
allowed the water to separate from the settleable solids thus
resulting in lower field values.
The difference between the readings of the seven cones for
each Mine Pond are apparently greater in the field data then in the
laboratory. This is probably due to two reasons, namely; the method
of mixing and decanting of the samples to the seven cones was not
as precise in the field and the readings taken in the field were,
in most cases, to only one significant figure. This "problem" in
the field readings is probably more representative of what will
happen when actual field samples are taken and measured.
Therefore, we have opted to use only the field results to base
our conclusions on. As noted in Table No. 1, the maximum method
detection level is 0.40 ml/l/hr. The mean of the standard deviation
values is 0.08 ml/l/hr. To obtain a 99% confidence level for both
the MDL and the standard deviation, the standard deviation would
have to be multiplied by three to obtain a value of 0.24 ml/l/hr.
This then affirms a method detection limit of 0.40 ml/l/hr.
Conclusions
Based on field samples and analysis of settleable solids both
in the field and in the laboratory, it was determined that values of
B-5
-------
settleable solids can be read with a reasonable degree of accuracy
below 1.0 ml/l/hr using the volumetric method outlined in Standard
Methods and 304(h) of the Agency's "Methods for Analysis of Water
and Wastewater". This method has been used for years to determine
the amount of settleable solids in wastewater. The method states
that "the practical lower limit of measurement is about a ml/1"
(increments between 0 and 1,0 ml/1) and upon observing the cones it
is obvious that readings can be made below the level of 1.0 ml/1.
In fact, the method detection limit for settleable solids measure-
ments has been statistically determined by this study to be 0.4
ml/1 for the coal mining industry.
B-6
-------
TABLE NO. I
SUMMARY OF COAL MINE POND
SETTLEABLE SOLIDS TESTING
IMHOFF CONE NO.
Mine
Pond
No. Obser,
E
C
M
L*
1
0.7
0.65
0.8
0.40/
0.50
0.30
0.40
0.45
0.38
0.1
0.1
0.13
0.50
0.6
0.5
'0.5
0.58
0.7
0.7
0.50/
0.45
0.7
0.7
0.50
0.2
0.3
0.15
0.3
0.3
0.3
0.12
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
1
0
0
0
0
0
0
0
0
2-
.8
.85
.7
.40/
.55
.30
.40
.40
.35
.09
.09
.11
.55
.4
.4
.4
.60
.7
.7
,507
.40
.0
.0
.45
.3
.3
.12
.4
.4
.3
.15
3
0.8
0.8
0.9
0.40/
0.40
0.35
0.35
0.40
0.35
0.09
0.09
0.1
0.60
0.6
0.5
0.5
0.55
0.7
0.7
0.457
0.40.
0'. 9
0.9
0.48
0.4
0.4
0.10
0.3
0.3
0.3
0.15
4
0.7
0.9
0.7
0.38/
0.50
0.35
0.35
0.35
0.30
0.09
0.09
0.1
0.60
0.5
0.4
0.4
0.65
0.6
0.5
0.45/
0.40.
0.9
0.9
0.40
0.2
0.3
0.10
0.4
0.5
0.4
0.15
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
5
.7
.9
.9
.307
.40
.35
.30
.40
.30
.08
.09
.13
.50
.6
.6
.6
.60
.5
.5
.407
.42 '
.8
.7
.40
.2
.2
.12
.3
.3
.3
.12
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
•0
0
0
0
0
0
0
6
.7
.75
.8
.35/
.50
.30
.35
.35
.25
.08
.09
.1
.55
.7
.7
.7
.50
.7
.8
.457
.42
,7
.7
.40
.3
.4
.12
.3
.3
.3
.15
0
0
0
n
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
7
• 7 1
•7 !>
.6 J
.138/
.40
.30 ~'
.35 >
.4 _J
.28
.07 "I
.07 >
.09 J
.55
.9 "~j
.8 >
.9 _j
.55
-7 ~i
.7 >
.407
.40
.8 -1
•8 J
.40
.2 ~|
.2 f>
.10
-5 1
.5 >
.5 J
.12
Mean.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
76
37/
46
36
32
094
55
56
58
65
45/
42
82
43
28
12
36
14
Std.
Dev.
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
. 09
.038/
.063
.043
.046
.015
. 041
.16
.048
.09
.041/
.092
.11
.043
.08
.018
.081
.016
MD
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
.23
+•*•/,
.20
.11
.14
.04
.13
.40
.15
.25
.137
.070
.30
.14
.21
.057
.20
.050
DUPLICATE TESTS RUN IN LABORATORY
E - EPA, EGD REPRESENTATIVE
C - EPA CONTRACTOR
M - MINE REPRESENTATIVE
L - EPA LABORATORY
B-7
-------
-------
REFERENCE 1
SETTLEABLE MATTER PROCEDURE
B-9
-------
-------
Prom: "Standard Methods for the Examination of Water and Wastewater",
Ulth edition, 1976, APHA-AWWA-WPLF
208 F.
1. General Discussion
Settleabie Matter
2. Apparatus
Settleabie matter in surface and saline
waters as well as domestic and industrial
wastes may be determined and reported
on either a volume (milliliters per liter)
or a weight (milligrams per liter) basis.
The apparatus listed under Sections
208 A.2 and 208 B.2, and an Imhoff
cone, are required for a gravimetric test.
The volumetric test requires only an
Imhoffeone.
3. Procedure,
a. By volume: Fill an Imhoff cone to
the liter mark with a thoroughly mixed
sample. Settle for 45 min, gently stir the
sides of the cone with a rod or by spin-
ning, settle 15 min longer, and record
the volume of settleable matter in the
cone as milliliters per liter. The practical
lower limits is about I ml/I/hr. Where
a separation-of settleable and floating
materials occurs, do not estimate the
floating material. •
b. By weight:
I) Determine the suspended matter
(in milligrams per liter) in fhe sample as
in Method D, preceding.
2) Pour a well-mixed sample into a
glass vessel not less than 9 cm in diame-
ter. Use a sample of not less than I I and
sufficient to give a depth of 20 cm. A
glass vessel of greater diameter and a
larger volume of sample also may be
used. Let stand quiescent for 1 hr and,
without disturbing the settled or floating
material that which may be floating,
siphon 250 ml from the center of the
container at a point halfway between
the surface of the settled sludge and the
liquid surface. Determine the suspended
matter (in milligrams per liter) in all or
in a portion of this supernatant liquor as
directed under Method D. This is the
n on sen ling matter.
4. Calculation
mg/l settleable matter
-mg/1 suspended matter
-mg/1 nonscntcable matter
B-ll
-------
-------
REFERENCE 2
PICTURE OF AN IMHOFP CONE
B-13
-------
-------
HYDROTECHNIC CORPORATION
NCW VOW. N. Y.
1000
ACRYLONtTRJUE.
CONE
250
POLVETHYLeSJE
ELEVATION
"
« I")
.5
CONE
USEIT? IN COAL
(FULU SCALE.)
L-tN
-------
-------
REFERENCE 3
METHOD DETECTION
LIMIT - REFERENCE ARTICLES
B-17
-------
-------
Trace analyses
for wastewaters
Method detection limit, a new performance criterion for
chemical analysis, is defined as that concentration of the
analyte that can be detected at a specific confidence level.
Both theory and applications are discussed for reliable
wastewater analyses of priority pollutants
John A. Glaser
Denis L. Foerst
Gerald D. McKee
Stephan A. Quave
William L. Budde
U.S. Environmental Protection
Agency
Environmental Monitoring and
Support Laboratory
Cincinnati, Ohio 45268
The development of trace analysis
methodology brought with it a series of
questions about method performance
at low concentration levels of analyte
(t. 2,3). Under Section 304(h) of the
Clean Water Act, as amended in 1977,
(4) the Environmental Monitoring and
Support Laboratory (EM&L) in Cin-
cinnati is responsible for providing test
procedures for the measurement of
specified pollutants at trace concen-
trations in municipal and industrial
wastewaters.
A series of procedures was pub-
lished in the Federal Register for the
analysis of the 129 priority pollutants
(5). These procedures are designed to
monitor direct discharges from in-
dustrial and publicly owned treatment
works (POTW), sources under the
National Pollutant Discharge Elimi-
nation System (NPDES), and dis-
charges into a POTW system under
pretreatment regulations. The 304(h)
monitoring methods for organic anal-
yses are of two types:
• 12 methods designed around
gas-liquid and high performance liq-
uid chromatography with standard
detectors and modest operational skill
requirements for the permit holder
• three methods that employ a mass
spectrometer as a detector for multiple
measurements with minimal interfer-
ence.
To meet the needs associated with
these methods for analysis of the pri-
ority pollutants, it was incumbent on
EMSL to develop method perfor-
mance characteristics for these meth-
ods. As advocated by Wilson (6),
method performance characteristics
are specified criteria that detail the
ability of a method to analyze for an-
alyte.
Clearly, analyte detection is a fun-
damental criterion of performance for
an analytical system. Any analytical
system is constrained by an inability to
discern the signal due to noise from the
signal due to the presence of analyte at
low concentrations. The limit of de-
tection for a given analyte can be de-
fined as that concentration of the an-
alyte which can be detected at a spe-
cific confidence level.
The concept of detection limit has
been the focus of debate (7). The
controversy generally centers on defi-
nitions that vary with the analyst (8).
Confusion arises when instrumental
and method detection limits are com-
pared and sometimes used inter-
changeably (9). Moreover, detection
and determination have also been
conceptually intertwined by some in-
vestigators (10). Although definitions
of the detection limit for a given ana-
lyte vary, investigators concur that the
detection limit should be related to the
standard deviation of the measured
values at or near zero concentration of
the analyte (;/).
There is no doubt that the detection
limit is one of the most important
performance characteristics of an an-
alytical procedure. In most cases, a
detection limit must be viewed as a
temporary limit to current method-
ology.
Complete analytical system
Ostensibly, analysts do not directly
observe concentrations of analyte. The
measurements of the transducer signal,
which are related to the analyte con-
centration, are actually observed. In
any analytical system, information
concerning the identity and quantity of
an analyte is contained in the analyti-
cal signal, which depends on a large
number of experimental variables.
Since these variables contain a random
component, the analytical signal will
also have a random component char-
acterized by a probable uncertainty.
Some part of an averaged signal must
be a function of the true analytc con-
centration. Analysis of the signal pre-
cludes the ability of the analyst to
discern the fluctuations of the back-
ground from the average value of the
analytical signal for a given concen-
tration of analyte.
The relationship between back-
ground noise and analytical signal has
been studied by many authors; their
work has helped to develop the defini-
tion and evaluation of the detection
limit. A point of reference is necessary
to specify the sources of background
noise contributing to the overall ana-
lytical signal. Kaiser (12) has been a
major "figure in this development. He
has centered his thoughts on the de-
tection limit of a "complete analytical
procedure." Such a procedure or
method is specified in every detail by
1426 Environmental Science & Technology
This article not subiect to U.S. Copyright. Published 1961 American Chemical Society
B-19
-------
fixtJ working directions (order of
analysis) and is directed for use it a
particular analytical task. The specif-
ics of • "complete analytical proce-
dure" include a predetermination of
everything associated with the ana-
lytical task: the apparatus, the external
conditions, the experimental proce-
dure, the evaluation of results, and
calibration of the analytical system.
Thompson and Howarth (13) have
expanded this concept to develop an
analytical system that comprises:
• a set of samples of the analyte in
a specific matrix
• an exactly defined analytical
procedure
• the particular instrumentation
used.
The purpose for developing a pro-
cedure to evaluate detection limits was
lo design a methodology not limited by
instrumentation or analytical meth-
odology. For pragmatic reasons, we
focused on an operational definition of
detection limit. The analytical meth-
odology for priority pollutants served
as a basis for the concepts concerning
the method detection limit (MDL).
Each of the methods comprising this
methodology is designed to constitute
a "complete analytical procedure" or
"complete analytical system." Integral
to these concerns was an attempt to
specify a parameter for performance
measurement of each method of anal-
ysis.
The method detection limit refers to
samples processed through all the steps
comprising an established analytical
procedure. The fundamental differ-
ence between our approach to detec-
tion limit and former efforts is the
emphasis on 4he operational charac-
teristics of the definition. MDL is
considered operationally meaningful
only when the method is truly in the
detection mode, i.e., analyte must be
present. The method detection limit is
defined as the minimum concentration
defi
of a
o a substance that can be identified,
The MDL can be presented M an
«ror distribution. The definition of MDU
Implies that, on an average. 89% of
the trials measuring the analyte con-
e*ntration at the MDL must be signifi-
cantly different from zero anal/la
concentration. A one-sided test to
performed to evaluate this hypoth-
esis.
This graphical description of MDL to
based on the assumptions that the
«MTor distribution associated with th*
analytical measurement. In • suffi-
ciently large neighborhood proximal*
to the MDL. has a relatively homoge-
neous variance and Is normally dis-
tributed. A sufficiently large neigh-
borhood Is specified to accommodate
our recommendations (or the Initial
estimate of the MDU
Basic to these concepts ft the as-
sumption that the variability of an an-
alytical measurement, as measured by
the standard deviation an error distribution
Theory
can be approximated by a polynomial
of degree M
ffc " *o **• fciC
(1)
Since economic considerations
demand that the MDL be determined
with a limited number of analyses, the
standard deviation Sc employed In
these calculations Is an estimate of the
population standard deviation a* V the
mass of the standard addition (spike)
to measured accurately, the coeffi-
cients and Intercept for the polynomial
model may be estimated by linear re-
gression. This model can be truncated
to a first order equation:
S. -
(2)
The form of the error distribution
associated with these considerations
Is Irrelevant, but we assumed that the)
number of Independent error compo-
nents, associated with most analytical
systems, will be large enough to In-
voke the central limit theorem.
Therefore, the normal distribution will
be a good approximation of the error
distribution associated with any ana-
lytical determination (16. 17}.
To help avoid a negative estimate of
Jfe, the regression equation can be
transformed by dividing through by
C.
£+*<
0)
Measure? analyta concentration
A regression on S«/C vs. 1/C will yield
the estimated slope fco and the Inter-
cept *|. The estimate of the'slope
should be less sensitive to nonrandom
errors than the Intercept estimate.
Hence. • negative estimate of ft* often
may be avoided.
Since a limited number of samples
wttl be taken at each concentration.
ttte error distribution of this sampling
to expected to be approximated by a
student's t distribution. By defining ^
V(N)
1/1
then
«, c <«>
and the regression equation be-
comes:
IMWi *.
(6)
The regression equation Is now In a
form compatible to find MDL, such
that
df, 1-tt-
or
MDL
rf. l-o-.M) ftp
(7)
H must be emphasized that *« Is
conceptually no longer the sample
standard deviation at zero concentra-
tion, a concept which necessitates the
possibility of negative analytical re-
sponses at zero concentration of ana-
lyte. Now kg Is the linear trend In the
regression of (N)1"/fc vs. 1/C. which
In practical terms means that analyti-
cal responses at zero concentration
a/a not necessary or Implied In the
determination 01 MDL For obvious
economic reasons, the equation tor
MDL can be reduced to:
MX - f<*-i«.1-,-jijS. (8)
by setting the Intercept ft, to be equal
to zero and setting V(M1/7 equal to
Se, where Sc refers to the standard
deviation of replicate determination*
at a fUed concentration.
B-20
yok*na 15. NunberlJ. December 19(1 WIT
-------
measured, and reported with
confidence that the analyte concen-
tration is greater than zero and is de-
termined from replicate analyses of a
sample of a given matrix containing
anaiyte (14).
Single step procedure
The procedure for determining
MDL is based on the analysis of seven
samples of the matrix containing an-
alyte. If the MDL is to be determined
.in reagent (blank) water, a laboratory
standard of the analyte in reagent
water is prepared at a concentration at
least equal to or in the same concen-
tration range as the estimated MDL.
We recommend that the analyte be
added to the water to give a final con-
centration between one and five times
the estimated MDL. When the MDL
is to be determined in a sample matrix
other than reagent water, analysis of
the sample background ii reqnired..
If the measured level of analyte is
less than the estimated MDL, the an-
alyte is spiked into the matrix to bring
the level of analyte to a concentration
between one and five times the esti-
mated MDL. Should the .measured
level of analyte be greater than five
times the estimated MDL, two options
exist:
• the analyst is required to obtain
another sample of the same matrix
with a lower level of analyte present
• the sample may be used as is for
the MDL determination if the analyte
level does not exceed 10 times the
MDL of the analyte in reagent
water.
The error variance of the analytical
method changes as the analyte con-
centration increases above MDL.
Hence, MDL values determined in a
matrix containing a high analyte con-
centration may not truly reflect
method error variance at lower analyte
concentrations.
A minimum of seven aliquots of
matrix are processed thro.ugh the en-
tire analytical method and the MDL is
calculated. All concentration calcu-
lations are made according to the de-
fined method, with final results ex-
pressed in the method reporting units.
If a blank measurement is required to
calculate the measured level of ana-
lyte, the analyst must obtain a separate
blank measurement for each sample
aliquot analyzed. The average blank
measurement is subtracted from the
respective sample measurements.
It may be economically and techni-
cally desirable to evaluate the esti-
mated MDL before proceeding with
the analysis of the seven atiquots. This
will prevent repeating the entire pro-
cedure and ensure that the MDL de-
termination is being conducted at the
correct concentration. It is quite pos-
sible that an incorrect MDL could be
calculated from data obtained at many
times the actual MDL even though the
level of analyte would be less than five
times the calculated method detection
limit.
To ensure that the estimate of the
method detection limit is a good esti-
mate, the analyst must determine that
a lower concentration of analyte will
not result in a significantly lower cal-
culated MDL. We recommend initial
analysis of two aliquots of the sample
for this purpose. Should these mea-
surements indicate that the sample is
in the desirable range for the MDL
determination, five additional aliquots
are processed through the MDL pro-
cedure. If the sample is not in the cor-
rect range, the MDL must be reesti-
mated and seven new aliquots of the
sample matrix processed as de-
scribed.
The standard deviation of the seven
replicate measurements is calculated
and the MDL is commuted as
MDL «
where:
c (9)
t(N-\,l-a~.99)
This theory Is tested by collecting
data from a limited number of samples
at a single concentration estimated to
be In a sufficiently large neighborhood
proximate to the MDL. The directions
given to guide the analyst In estimating
the MDL are the following:
• the concentration value that
corresponds to an Instrument signal/
noise In the range of 2.5-5. If the cri-
teria for qualitative Identification of the
analyte is based upon pattern recoft-
nltlon techniques, the least abundant
signal necessary to achieve identifi-
cation must be considered
* the concentration value that
corresponds to three times the stan-
dard deviation of replicate Instrumental
measurements for the anatyte In-re-
agent water
* the concentration value that
corresponds to the region of the stan-
dard curve where there Is a significant
change In sensitivity at low analyte
concentrations. I.e.. a break In the
slope of the standard curve
• the concentration value that
corresponds to known Instrumental
limitations.
Testing the theory
The analyst's experience Is not In-
tended to supersede any of the other
considerations, but tt does provide for
crucial input of any relevant back-
ground with which a decision can be
reached If the other directions for es-
timation are either Inoperative or do
not give a clear choice for estimating
the MDL.
Invoking these criteria for estimation
of the MDL Involves a risk such that If
the initial estimates of the MDL are not
proximate to the (true) MDL, the cal-
culated MDL will be much In error. The
assumptions involved in the estimation
of the MDL can be tested In one of two
ways:
1. The estimated MDL Is aqua! to
the calculated MDL. If the 95% confi-
dence Interval of the calculated MDL
contains the estimated MDL value.
2. If the condition set forth In Item
1 Is not satisfied, then an Iterative
procedure, where the most recent
calculated MDL value Is used as the
next estimated MDL, must be used until
the variances of successive Iterations
do not differ using the F test.
Clearly, the MDL Is prescribed by
any attending Instrumental detection
limits. The procedure to determine the
MDL was designed to apply to a wide
variety of sample matrices ranging
from reagent (blank) water containing
analyte to wastewater containing an-
alyte. Thus, the MDL for an analytical
procedure may vary as a function of
the sample type (matrix). The devel-
oped procedure requires a complete,
specific, and well-defined analytical
method. All sample processing steps
of the analytical method must be In-
cluded In the determination of the
method detection limit.
A crucial point Is that the MDL for a
given analyte In a given matrix does
not preclude quar.tttatlon below the
MDL. However, when quantltatlon
below MDL ts pursued, the confidence
interval estimate of an analyte con-
centration below MDL will be greater
than at MDL for a given confidence
level and a given analytical effort. In
other words, It would require a greater
number of samples to analyze for an
analyte concentration below MDL to
achieve the same confidence limits
attached to the MDL,
1428 Environmental Selene* & Technology
-------
is the student's / value for u one-tailed
test at the 99% confidence level with
yV — 1 degrees of freedom. Sc is the
standard deviation of the seven repli-
cate analyses. Confidence-interval
estimates for the MDL are computed
using pcrcentiles of the chi square over
degrees of freedom distribution
(X /#)• The 95% confidence limits for
the MDL are computed in Equations
lOand II:
UCLwDL
> MDL
'.025
LCL
MDL
P.97S
(10)
where the perccniilc values are ob-
tained from the xV^/distribution for
the associated degrees of freedom
LCLMDL = 0.64 MDL
= 2.20 MDL
l }
The confidence limit expressions
reduce to Equation 1 1 where LCLMot
and UCLwoL are the lower and upper
95% confidence limits of the MDL
based upon the analysis of seven ali-
quots.
Iterative procedure
An additional procedure is pre-
sented to test the reasonableness of the
MDL estimate and subsequent MDL
determinations on the same matrix.
The initial calculated MDL is tested
by spiking the matrix at the calculated
MDL and processing the seven sam-
ples through the entire MDL proce-
dure. At each iteration of the MDL
calculation, the variance from the
current MDL calculation and the
variance of the proceeding MDL cal-
culation are compared by computing
the F-ratio, which is compared with
the tabulated F-ratio, F0.9S(6,6> ~ 3.05.
If the computed F-ratio is less than
3.05, then the pooled standard devia-
tion is calculated using the standard
deviation of the current MDL deter-
mination and the proceeding iteration.
The MDL is then calculated in Equa-
tion 12:
MDL « 2.68 1 XSpoo,ed (12)
where:
2.681 is equal tot(i2. i-a-.99)
and
The confidence levels for the M DL of
the iterative procedure are computed
from the percent iles of the chi squared
over degrees of freedom distribution
with degrees of freedom (N « 12)
based on 14 aliquots. Two degrees of
freedom are lost in the calculating of
the averages of the two ^eta. of seven
aliquots.
The confidence limit expression for
the MDL based on the iterative pro-
cedure reduces to
LCLMDL = 0.72 MDL
UCLMDL« 1.65 MDL
(13)
where LCLMDL and UCLMDL (13)
are the lower and upper 95% confi-
dence limits of the MDL based on the
analysis of 14 aliquots.
When'the analyte is present in the
matrix at a relatively "high" concen-
tration, measurement of the MDL is
not meaningful. If the analyte is found
at a relatively "low" level in the sample
matrix, the sample at that analyte
concentration may be used as* the inn
tial estimate of the MDL, and the
sample aliquots processed through the
MDL procedure. However, if the cal-
culated MDL is lower than the back-
ground level of analyle present in that
matrix, the iterative procedure cannot
be used. Convergence of the iterative
procedure will depend on the closeness
of the estimated MDL, or the back-
ground level of analyte present in the
matrix, to the calculated MDL.
Reporting information
The analytical method used must be
specifically identified by number or
title and the MDL for each analyte
expressed in the appropriate method
reporting units. If the analytical
method permits options affecting the
method detection limit, such options
must be specified with the MDL value.
The analyst must also report the mean
analyte level and specify the matrix
used with the MDL. If a laboratory
standard or a sample that contained a
known amount of analyte was used for
this determination, the mean recovery
must also be reported. If the level of
analyte in the sample is below the de-
termined MDL or does not exceed 10
times the MDL of the analyte in re-
agent water, no MDL value is re-
ported.
Applications
Method detection data were col-
lected for the organic priority pollutant
methods and are displayed in Tables
1-5. Data for Method 603-acrolcin
and aery Itm it rife are currently un-
available. The earlier estimates of de-
lection limits cited in Reference 5 were
based solely on signal-to-noise cri-
teria.
Some of the reported MDL values
in the tables are at concentrations
higher than had been anticipated. Low
values for MDL are closely tied to the
learning curve of each method. Expe-
.rience has demonstrated that the an*
alyst who has extensive experience
with a,given method is more likely i,
generate lower MDL values than an
analyst with only cursory experience
with the method.
The optional iterative scheme was
developed as a response to high MDL
values in these tables. These larger
values are attributed to a mistaken
estimate of the MDL. The closeness of
the initial estimate to the final calcu-
lated MDL is a critical concern in
using this procedure. The tables are
organized according to each method
and its particular set of analytes.
Background, spike level, percent re-
covery, and matrix types are included
as specified in the reporting require-
ments for the MDL.
Some analytes in Tables 2 and 3
gave wastewater background levels
that range from 18 to 90000 times
larger than the Tespective reagent
water MDL value; therefore, no
wastewater MDL value should be re-
ported. However, the wastewater
MDL values are included to illustrate
that the MDL procedure can give
meaningless values when the analyte
or analyte plus interference is present
at levels much larger than 10 times the
MDL value in reagent water.
For these analytes, the calculated
wastewater MDL values averaged 240
times larger (range 6 to 1150) than the
respective reagent water MDL value.
There are analytes in Table 2 that
exhibited wastewater background
levels that range from 0.8 to 8 times
the respective MDL value in reagent
water. The MDL procedure gave
meaningful values for these analytes
since the wastewater MDL values
avenged 2 lime<> larger (range 0.4 to
9) than the respective reagent water
MDL values.
Method 602—purgeablc aromatics
This is not a purge-and-trap method
using packed column gas chromatog-
raphy and a photoionization detector.
The M DL values listed in 1 able 1 for
the purgcable aromatics are quite
reasonable for reagent water although,
except for toluene, the recoveries are
consistently over 100%. The MDL
values calculated for the two waste-
waters are derived from background
analyte levels when the analyte was
present in the wastewater and from
spike levels when absent. Recoveries
and MDL values for analytes spiked
into wastewater No. 1 are reasonable
but the MDL value based on the
background concentration of 1,2-di-
chlorobcnzene is not. the MDL value
for 1,2-dichlorobcnzene reflects a large
variation in the analyte background
level. However, 'he MDL vali,^ loses
i' - r"nce ihe analyte is present
B-22
Volume 15, Number 12. December 1981 1429
-------
TABU 1
Method detection limit for purgeable aromattcs as analyzed by Method 602 (S2)
Naagont valar
Compound
Benzene
Toluene
Ethyl Benzene
CMorobenzerw
1,2-OJchtorobenzene
l.&CHchtorobenzene
1.4-Oichlorobenzene
•pit*
0.5
0.6
6.5
0.5
0.5
0.5
0.5
Avorag*
131
•0
120
120
120
.120
140
HDL
(W/U
0.2
0.2
0.2
0.2
0.4
0.4
0.3
.Background
-. 0.4
s.e«
0.0
0.0
34"
0.0
0-0
Waatowalar No. 1 • Wortoi
hwal
0.0
0.0
O.fi
0.5
0.0
•0.6
0.5
Aworaga
• •_•
-.__
100
60
• —
80
;*°
MOL
(WA)
1.74
1.55
0.2
0.2
20°
0.3
0.4
Background
41.
938
TO
'09
1.8
i.e
7
•pMa
lavol
(MflA)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
MtarKo. I*
taoovory- (paA)
— 30.0«
— 230"'
— 34«
— 197°
— 0.4*
— 1.0
— 1.7*
• Effluent Irwn chamlcal Mtmedato manufacturer.
* Effluent from rubber, plutlclzers and specialty chemicals manufacturing faculty
•Background greetar than 10 times calculated MX In reagent water.
in determinable quantities. The M Di-
va lues in wastewater No. 2 are simi-
larly inflated.
Method 605—benzidines
This is a HPLC method using re-
verse-phase chromatography and an
electrochemical detector. The MDL
value for benzidine in reagent water
was determined using an electro-
chemical detector pole.jtial of +0.8 V
vs. S.C.E., while in the two wastewa-
ters, the MDL was determined using
a potential of 0.6 V due to the presence
of interfering peaks at 0.8 V. Reducing
the potential gives more specificity for
benzidine but also lowers the instru-
mental sensitivity. Dichlorobenzidine
was determined at +0.8 V in all ma-
trices. The estimated MDLs published
with the earlier version of this method
(5) have nearly been achieved. In the
reagent water and wastewater No. 1,
the MDLs are within a factor of two of
those originally estimated, while for
wastewater No. 2 they are approxi-
mately a factor of 4 higher for ben-
zidine and a factor of 2 higher for
dichlorobcnzidinc. Recoveries of
60-70% for benzidine and 50-70% for
dichlorobenzidine were achieved,
similar to those obtained in the original
method development. To achieve these
MDLs, it was important to eliminate
all oxidizing agents from the sample
matrix. Residual chlorine, which is
recognized as a notorious oxidant, was
decomposed by adding 35 mg/L so-
dium thiosulfate to each wastewater
and reagent water. The reagent water
was adjusted to a neutral pH prior to
spiking the sample matrix with ana-
lyte.
The low recoveries at low spiking
levels are probably due to oxidation
during sample processing. Since such
oxidation reactions are overall second
order processes (first order in both
oxidant and amine), low recovery of
the amine can occur at low concen-
trations of analyte and relatively large
concentration of oxidants.
Organochlorine pesticides and PCBs
Method 608 is a GC method using
packed column chromatography and
an electron capture detector (ECD).
The MDL valued of the pesticide and
PCB analytes in reagent water listed
are generally equal to or lower than
those reported as estimates with the
earlier version of this method (5).
Heptachlor cpoxide analysis exhibited
anomalous behavior in reagent water.
This resulted from the presence of an
interfering chromatographic peak that
clearly coeluted with the compound,
thus requiring blank measurements. In
many instances, the level of this in-
terference did not remain constant but
was variable for the aliquots of a given
matrix. In this case, the blank did not
necessarily represent the background
concentration of the interfering species
in the sample. By averaging the back-
ground, we assume that a more reliable
measure of the background is ob-
tained.
The basic approach to determining
MDLs in wastewater was the same as
for reagent water. However, in the
presence of coeluting or interfering
substances, the analyst chose to modify
the MDL procedure. In s.ome cases,
when the water contained pesticide or
PCB analytes, direct calculation of the
standard deviation was prevented by
coeluting, interfering materials. Large
fluctuations in the background were
observed, which attenuated the utility
of the blank measurements.
Since the response of an interfering
species and anaiyte was being mea-
sured, the variability of the response
represented the total variability due to
both compounds. In this case the cor-
rected variance of the sample, calcu-
lated by subtracting the variance of the
background from the variance due to
the analyte plus background was
used to calculate the MDL. Two ana-
lytes in wastewater No. 1, endosulfan
sulfate and -y-BHC, required this
treatment. In wastewater No. 2, this
alternate scheme of variance calcula-
tion was used for 0-BHC, 5-BHC,
•y-BHC, endosulfan sulfate, aidrin,
and endosulfan II. The MDLs in
wastewater No. 1 are fairly consistent
but considerably higher than the re-
agent water MDL values. The MDL
values for wastewater No. 2 compare
more favorably to the reagent water
than do those from wastewater No. 1,
TABl£ 2
Method detection limit for benzidines as analyzed by
Method 605 (24)
Compound
Beruldlne
Dichtorobenzkflne
W0.1*
MOi. r*oo**ry MDL i*cov*qr
0.60
0.60
62
60
0.08
0.13
74
72
0.06 •
0.09
74
69
0.19
0.22
* Pigment manufacturing waauwatar.
* Aniline manufacturing wattowwtw.
* Background we* 0.06 jig/L,
1430 Environmental Science & Technology
B-23
-------
TABLE !»
Method detection limits for pesticides and polychlorlnated blphenyls as analyzed by method
f r0
%#• level Amr*0»
MDL •Mkflreund
•pike level Average %
Average % MDL
« Effluent from a pesticide manufacturing plant.
* Effluent from an organic* and pla*tlcs manufacturing plant
•Background greater than 10 times MDL In reagent water.
ff-BHC
0-8HC
J-BHC
7-BHC
DOD
ODE
DDT
Endosutfanl
EndosutfanH
Endoeulfan sulfate
HeptteNor
Heptaehlor epoxkto
AJdrln
DWdrin
Endrin
Chtordana
Toxaphene
PC81242
9.6
24.0
19.6
17.2
62.0
24.0
70.0
25.2
48.0
272.0
11.6
18.4
14.4
30.4
43.2
162.0
166.0
188.0
99
97
91
103
100
96
99
72
97
81
91.
153
84
100
101
99
99
90
.003 260"
.006 —
.009 —
.004 —
.011 —
.004. —
.012 —
.014 —
.004 —
.066 —
JOGS —
.083 —
.004 —
.002 —
.006 31C
.014
.235
.065
0.0
30.0
43.0
20,0
62.0
20.0
60.0
46,0
12.0
160,0
6,0
A5.0
20,0
6,0
0,0
164
84
320
77
129
76
76
37
105
715
155
140
276
—
0.184«
0.059
0.062
0.283
0.031
0.038
0.049
0.061
0.009
0.30
0.055
0.148
0.055
0.017
0.079°
14.0
30.0-
43.0
20.0
62.0
20.0
69.0
73.0
21.0
329.0
18.0
65.0
20.0
13.0
32.0
72
94
94
101
79
71
71
99
60
94
89
80
'80
107
70
0.013
0.011
0.023
0.007
0.029
0.008
0.030
0.056
0.013
0.262
0.009
0.021
0.0054
0.010
0.031
and reflect the tower background of
electron capture-sensitive materials
present in wastewater No. 2.
Polycyclic aromatic hydrocarbons
Method 610 is a reverse-phase
HPLC method using UV and fluores-
cence detectors. From the data in
Table 4, it is obvious that both recovery
and precision for most of the PAHs
were good, generally ±10% precision
and 90-100% recovery, in all matrices.
Fluoranthene was the only analyte that
was significantly different. In one ali-
quot of reagent water, the result for
fluoranthene was nearly twice the
spike level. There is a possibility that
this aliquot was doubly spiked; this
would explain the unexpected accre-
tion of analyte. Hence, the MDL for
fluoranthene in reagent water is
skewed toward a higher concentration
because of the higher value of the
standard deviation. Precision and re-
covery data for fluoranthene in the two
waslewaters, one of which had a de--
tectable background level of fluoran-
thene, were considerably better than in
reagent water.
The fluoranthene MDL data for the
wastewaters is probably a better indi-
cation of the precision of the method,
providing that blank contamination is
not a problem. The single reagent
water aliquot giving a high result for
fluoranthene was probably contami-
nated in some way. On occasion,
fluoranthene has been observed at low
concentration levels in reagent water;
this points to fluoranthene as being the
PAH analyte most likely to present
contamination problems. This obser-
vation is more credible since fluoran-
thene is a highly fluorescent compound
under Method 610 assay conditions,
and is one of the most commonly found
PAHs in environmental samples.
The MDL values obtained for the
PAH analytes in these three water
matrices are all equal to or lower than
those estimated in the earlier version
of the method (except for fluoranthene
in reagent water).
2,3,7,8-Tetrachlorodihenzo-p-
dioxin30
Method 613 is a gas chromatogra-
phy/mass spectrometry (GC/MS)
method that requires use of a capillary
column, which uniquely separates
2,3,7,8-TCDD from the other 21
TCDD isomers and specifies operating
the MS detector in the selected ion
monitoring mode (SIM) of data
acquisition. The MDL value
for 2,3,7,8-tetrachlorodibenzo-p-di-
oxin (2,3,7,8-TCDD) in reagent water
is 0.002 Mg/L and is slightly lower
than the detection limit given in the
earlier version of this method (5). The
spiking level in reagent water was 5.0
ng/L, which gave an average recovery
of 95%.
This method has extremely high
selectivity and sensitivity for 2,3,7,8-
TCDD. Qualitative identification is
based on pattern recognition using the
ratio of the response for the ions at m/z
320,322, and 257. The seven aliquots
of reagent water at 5 ng/L gave an
average ratio of 0.79 ± 0.04 for the
ions at m/z 320 and 322.
The response for the ion at m/z 257
is approximately 30% of the response
for the ion at m/z 322. Refinement of
the MDL value through reiteration of
the MDL procedure using a spiking
level of 2 ng/L will demonstrate that
the MDL is not significantly lower
than 2 ng/L and will also demonstrate
that qualitative identifications can be
made if the 2,3,7,8-TCDD concen-
tration is 2 ng/L.
Base/neutrals, acids & pesticides
This GC/MS method employs
packed columns and requires operating
the MS detector in a repetitive scan
mode for data acquisition. The reagent
water MDL values for 62 of the 72
analytes in Method 625 are given in
Table 5. All MDL values are lower
than the detection limits specified in
the earlier version of this method (5).
The table includes values for PCB-
B-24
Volume 15. Number 12, December 1961 1431
-------
TABLE 4
Method detection limit for polycycllc
aromatic hydrocarbons as analyzed by Method 610 (27)
•tttMo.1* WMUw.tw Mo.2*
»«-.
Napthalene
Aoenaphthytene
Acenaphthene
Fluorene
Phenarrthrene
Anthracene
Fkioranthene
Pyrene
Benzo(a)-anthracene
Chrysene
Benzo(6)-fluorarrthene
Ben2o(fc}-fluoranthene
&enzo(A>pyrene
Dibenzo(a,n}-anthracene
Benzotff, h, 0-perylene
lndeno{ 1 ,2,3-cd)pyrene
• Refinery effluent.
* Coke oven «tt kient.
"SUr
4.1
8.0
4.9
0.80
2.0
2.4
0.084
0.86
0.061
0.81
0.84
0.084
0.81
0.098
0.40
0.15
*=tr
104
05
100
85
95
96
130
98
93
95
97
95
81
88
83
93
MM.
Own.)
1.8
2.3
1.8
0.21
0.64
0.66
0.21
0.27
0.01
0.15
0.02
0.02
0.02
0.03
0.08
0.04
*3ty
83
90
08
93
95
96
107
103
93
95
98
93
96
102
98
93
MDL
O«/l>
1.2
2.4
1.5
0.22
0.61
0.52
0.02
0.13
0.01
0..10
6.01
0.01
0.01
0.02
0.08
0.03
Avwap* %
80
86
90
95
90
92
114
98
94
96
98
95
95
$12
98
93
MDL
OWL)
2.9
4.0
1.4
0.25
0.79
0.99
0.08
0.26
0.02
0.18
0.02
0.02
0.01
0.02
0.13
0.04
1221 and PCB-1254 that were not
specified before.
During the MDL study for Method
625, concentration was done using the
optional nitrogen blow-down instead
of the second micro Kuderna-Danish
concentration. Recoveries ranged from
28-94% for the 62 analytes studied;
however, only eight analytes gave an
average recovery larger than the re-
covery for thai analyte in Methods 604
through 612. There were two instances
where the calculated MDL was larger
than the spike level. Nineteen values
are based on the analysis of eight or 10
aliquots.
Overall, it is best to view the MDL
values in Table 5 as initial values
subject to refinement through iteration
of the MDL procedure. Since the
qualitative identification scheme for
this mass spectrometer method relies
on lower abundance ions with variance
not reflected in the calculation of the
MDL value, it is possible that quali-
tative verification might not be made
when the analyle is present at a con-
centration in the neighborhood of
MDL. This is another reason to pursue
an iteration of the MDL procedure for
Method 625.
Comparing the reagent water MDL
values for the phenolic analytes com-
mon to both Methods 604 and 625
shows that only 4-nilrophcnol and
pentachlorophenol gave lower MDL
values in Method 625.
4-Nitrophenol was spiked at 10
in the MDL study for Method
625 and at 15.4 jig/L for the Method
604 study. The corresponding spike
levels for pentachlorophenol were 10
Mg/L and 21 ng/L. Thus, the inter-
action between instrumental sensitivity
and spiking level can be seen to have an
effect on the calculated MDL. The
remaining phenolic analytes gave
MDL values for Method 625 that were
between 1.5 and 11 times larger than
the corresponding values in Method
604.
The reagent water MDL value for
3,3'-dichlorobenzidine in Method 625
is 250 times larger than that value in
Method 605. Since the average re-
coveries for this analyte are approxi-
mately equal in both methods, this
large difference reflects instrumental
differences in both sensitivity and
chromatography. As a rule, amines
chromatograph much better under
reverse-phase HPLC conditions than
gas chromatography conditions. No
MDL value for benzidine is reported
with Method 625 because of losses
experienced in the drying and con-
centration steps.
In those cases in which the phlha-
lates were spiked at higher concen-
trations in the Method 625 MDL
study compared to the Method 606
study, the MDL values were approxi-
mately four to seven times higher than
the Method 606 MDL values. Bis(2-
ethylhexyl)phthalate was spiked at
nearly identical concentrations in both
MDL studies and gave nearly identical
MDL values. Di-n-octy! phthalate was
spiked at a lower concentration in the
Method 625 MDL study and gave a
slightly lower MDL value compared to
Method 606.
Method 625 and Method 606 show
opposite trends in the average recovery
of the phthalates. In Method 625 re-
covery increases with increasing re-
tention time, but decreases with in-
creasing retention time in Method 606.
All Method 625 M DL values are close
to the spiking values; therefore, itera-
tion of the MDL procedure for the
phthalates may not result in much
different MDL values.
The nilroso analyte in the Method
625 MDL study exhibits an MDL
value consistent with the differences in
instrumental sensitivity between
Method 625 and Method 607. In
Method 625, the spiking level was 12
times higher than in Method 607 and
the calculated MDL value was 17
limes higher.
The pesticide analytes that survive
the basic extraction step of Method
625 show MDL values between 27 and
1400 times higher than the corre-
sponding values in Method 608. Hep-
tachlor epoxide displayed the least
difference and 4,4'-DDE displayed the
greatest difference. The average re-
covery in the Method 625 MDL study
is generally lower than that in Method
608; however, no recovery was greater
than 100%, as was the case in Method
608. The pesticides a-BHC, -y-BHC,
endosulfan 1, endosulfan II, and cndrin
were lost durinp. the basic extnclion
1432 Environmental Science & Technology
B-25
-------
step. Large differences in deleclor
sensitivity are responsible for the large
differences in MDL between Method
625 and 608.
The MDL values for nitrobenzene
and isophorone again show the inter-
play between the original estimate of
MDL and the subsequent value of the
calculated MDL. In Method 625, both
analytes were spiked into reagent
water at concentrations lower than
that used in Method 609 and each gave
a lower MDL value. Since there is not
a great deal of difference between in-
strumental-sensitivity in this case, it is
not surprising that the lower estimate
for MDL resulted in a lower calculated
MDL. In contrast, the dinitrotoluene
analytes gave MDL values that were
220 and 320 times larger in Method
625 compared to Method 609. This
difference is attributed to the large
differences between instrumental
sensitivity in these two methods.
Method 625 MDL values for the
first three eluting PAH analytes
(naphthalene, acenaphthalenc, and
acenaphthylenc) are very similar to the
values obtained for Method 6 i 0. These
three analylcs are detected with a UV
detector similar in instrumental sen-
sitivity to the mass spectrometer used
in Method 625. Naphthalene was the
only PAH analyte that gave a lower
MDL value in Method 625, but it was
also the only analyte spiked at a lower
concentration in Method 625 com-
pared to 610. The 13 remaining PAH
analytes gave MDL values in Method
625 that were between 3 and 780 times
higher than the corresponding values
in Method 610. This reflects the dif-
ferences between the fluorometer and
mass spectrometer in detector sensi-
tivity. Benzo(g, h, Operylene gave an
MDL larger than the spike level in the
Method 625 study and it was the only
PAH in Method 625 that gave an av-
erage recovery higher than the corre-
sponding recovery in Method 610.
The haloether analyles in Method
625 gave MDL values consistent with
detector sensitivity and spiking, level.
The calculated MDL for 4-bromo-
phenyl phenyl ether was lower than the
value in Method 611, but it was also
spiked at a lower level. The remaining
haloether analytes gave MDL values
ranging from 1.1 to 19 times larger
than the corresponding values in
Method 611. Clearly, there is no great
difference in MDL results between
these two methods. The Method 625
haloether recoveries were about half
those reported in Method 611.
1,3-Dichlorobenzene gave an
anomalous MDL value when com-
pared to the other analytes in Method
625. Highly variable losses were at-
tributed to the volatility of the analyte.
The spike level was lower than thai in
Method 612, but in Method 625 the
TABLE 5
Method detection limits for compounds as analyzed by Method 625 In reagent water (31)
Bpft* tevol Av«r*o« % MOL Bpft* tovof Avcrae* % HDL
Compound
Compound
Acenaphthene
Acenaphthylene
Anthracene
AWrln
Benzo{A)anthraoene
Beruo(*)fluoranthene
8en20(a)pyrene
Benzoff ,/». Operylana
Benzyl butyl phthalate
Bls(2-chloroethyl) ether
BIM2-chhxoethoxy) methane
8l»(2-ethylnexyl) phthalate
Bl*(2-chlorolsopropyt) ether
4-Bromophenyl phenyl ether
2-Chloronaphthatene
Ctvysene
4-4'-OOO
4.4'-DOT
D)benzoU.r>)anthraoene
(N-fttutyl phthalate
1,3-Dlchlc/obenzane
1t4-Dlchloroben2ene
DfeUrln
Dfethylphthalate
Dimethyl pnthalate
2,*OWtroto)uer>e
DJ-rwctyf phtnalate
Ruoranthene
Ffcjorene
Heptachlor
3.6
3.8
3.8
10
25
3.8
3.8
3.6
3.8
13.3
13.3
3.6
25
3.8
9.8
3.8
10
10
3.8
3.8
3.6
13.3
10
3.6
3.8
3.8
3.8
3.8
3.8
10
63
47
70
72
68
80
73
02
74
43
45
04
61
68
66
66
60
63
. 82
05
60
40
63
64
48
64
64
80
64
69
1.9
3.5
1.9
1.9
7.6
2.6
2.5
4.1
2.5
6.7
6.3
2.5
6.3
1.9
1.9
2,5
2.6
4.7
2.5
2.5
4.4
6.0
2.6
1.9
1.6
1.9
2.5
2.2
1.9
1.9
Heptachtor epoxtte
Hexachlorobenzene
Hexachlorobutadlene
Hexachloroethane.
todeno< 1 ,2,3-cd)pyrene
Itophorone
Naphthalene
Nitrobenzene
WJItroso-dl-/>-propylamIne
Pyrene
1.2,4-Trlchlorobenzene
Benxo(b)fluoranthene*
4-Chlorophenyl phenyl ether"
3,3'-Dic*ilorotxHizktone*
2,4,-Dlnltrotoluene'
PC8 1221*
PCS 1254*
Phenanthrene*
4^hloro-3-methylphenol*
2.4-Dlchlorophenof*
2.44>imethylphenol*
2,44>lnltropnenol'
2-MethyW,6-dlnltrophenol"
4-NHrophenol"
Pentachlorophenol* .
Phenol'
2.4.6-Trlchlorophenol*
0BHC*
«BHC*
4,4'.ooe»
EndoMJtfan eulfata*
10
3.8
3.6
3.6
3.8
3.8
3.8
3.8
25
3.6
3.6
13.3
13.3
33
13.3
91
61
13.3
1°
10
10
40
40
10
10
10
10
6
6
10
7
62
67
66
.60
65
69
70
66
86
79
66
45
45
62
44
77
80
6i :
71
60
67
94
77
62
67
26
•64
69
M
69
79
2.2
1.9
0.9
1.6
3.7
2.2
1.6
1.9
6
1.9
1.9
4.6
43
16.6
6.7
30
36
6.4
3.0
2,7
2.7
42
24
2.4
3.6
1.6
2.7
4.2
3.1
5.6
6.6
" MX faetetf on 8 aliquot* of rugent water.
• MDL based onlO •tiquett of re»0wi water.
B-26
Volume 15, Number 12, December 1981 1433
-------
calculated MDL value was larger than
the spike level. Hence the results for
this chlorinated hydrocarbon analyte
should be regarded with caution.
Conclusions
The purpose of this procedure is to
provide a "MDL that is used to judge
the significance of a single measure-
ment of a future sample. The MDL
procedure was formulated to accom-
modate application to a broad variety
of physical and chemical methods. It
was necessary to make the procedure
device—or instrument—independent
to accomplish the wide application
desi/ed.
The measurement of the MDL
value, in a given matrix, is meaningless
if it can be shown by analyte-specific
methods that a high background is due
to interference rather than the analyte
in question. Standard additions in a
large neighborhood proximate to the
MDL on an interfering background for
the purpose of determining the MDL
can have value in providing an accu-
racy and precision statement for the
analytical method at analyte levels
comparable to the interference con-
centration in that specific matrix.
The iterative procedure is presented
only as a means to overcome mistaken
estimates for the MDL. When the
analyte is present in the matrix due
solely to standard additions and the
estimated MDL was found to be out-
side the 95% confidence interval of the
calculated MDL, only one or two it-
erations should be necessary to identify
the MDL with sufficient accuracy.
However, only a full regression treat-
ment would provide a more complete
description. When economically fea-
sible, the full regression treatment
should be used.
If the relative standard deviation of
the seven replicates is in the range of
20.5-70.1%, then the estimated MDL
will be within the 95% confidence in-
terval of the calculated MDL, This is
sufficient statistical evidence to stop
the iterative MDL procedure. Should
the relative standard deviation fall
outside this range, the results are sus-
pect. Experience has shown that when
the relative standard deviation is at or
near 10%, the calculated MDL values
can be below instrumental detection
limits.
We can look forward to continued
lowering of such performance char-
acteristics as established analytical
procedures are adjusted to accommo-
date future advances in analytical
technology. This will serve to push the
MDL to lower values than those pre-
viously assigned.
I4M Environmental Science A Technology
B-27
-------
Acknowledgments
We wish to recognize the analysts of Bat-
tellc Columbus Laboratories, IT Enviros-
cience, Monsanto Research Corporation-
Dayton Laboratory, and Southwest Re-
search Institute, who generated the MDL
data Tor Methods 601 through 613. An
EMSL team of analysts are recognized as
the source of (he MDL data for Methods
524 and 625. A number of our EMSL co-
workers have personally contributed to the
roncept of MDL in this regard. We wish to
ick now ledge the constructive input of
Thomas Bellar, Paul Brilton, Seymour
Told, James Lichtenberg, and James
.ong bottom.
iefore publication this article was com-
,ented on for technical accuracy by Dr.
eorge W. Barton, Jr., Lawrence Liver-
lore Laboratory, University of California,
.O. Box 808, Livermore, Calif. 94550,
nd Dr. Ervin J. Fenyvcs, the University of
'exas at Dallas, P.O. Box 688, Richardson,
ex. 75080
teferences
1) Liteanu, C.; Rica, 1. "Standard Theory and
Methodology of Trace Analysis"; John Wiley
& Sons: New York, 1980; Chapter 7, pp.
255-125.
.2) Massart, D. L.; Dijkstra, A.; Kaufman, L.
"Evaluation and Optimization of Laboratory
Methods and Analytical Procedures"; Else-
vier: Amsterdam, 1978; Chapter 6, pp.
143-156.
(3) "Guidelines Tor Data Acquisition and Data
Quality Evaluation in Environmental
Chemistry", Anal. Chem. 1980, 52, 2249.
(4) "The Clean Water Act Showing Changes
Made by the 1977 Amendments", CFR 95-
12, Dec. 1977.
(5) "Guidelines Establishing Test Procedures
for the Analysis of Pollutants", 44 FR 69464,
Dec. 3, 1979.
(6) Wilson, A. L. Talanta 1970, /7(2I), 31;
1973,20,725; 1974,21,1109; "The Chemical
Analysis of Water"; Society for Analytical
Chemistry: London, 1975.
(7) Wilson, A. L, Analyst 1961,50,72; Roos,
J. B. Analyst 1962, 87. 883; DeGaleu, L.
Spectrosc. Left. 1970, 3, 123; Altshuler. B.;
Pasternack, B. Health Phys. 1963, 9, 293;
Skogcrboe, R. K.; Grant, C. L. Sptcirosc.
Lett. 1970, .J. 215; Liteanu, C.; Rica, 1. Pure
Appl. Chem. 1975,44, 535; Habaux, A.; Vos.
G. Anal. Chem. 1970,42,849; Currie, L. A.
Anal. Chem. 1968, 40, 586.
(8) Ingle,J.D.,Jr.J.Chem.Ed. 1974.5/.100;
Boumans, P. W. J. M. Sptctrochim. Acia
1978, 33B, 625.
(9) Ramirez-Munoz. J. Talanta 1966, 13,
87.
(10) Sutherland, C.L. Residue Reo. IMS, 10,
85.
(II) Parsons, M. L. J. Chem. Ed. 1969, 46,
290.
(12) Kaiser, H. Anal. Chem. 1970,42(2), 24 A;
42(4), 26 A; Kaiser, H.; Menzies. A. C. "The
Limit of Detection of a Complete Analytical
Procedure"; Adam Hilger: London, 1968;
Kaiser, H. In "Methodicum Chimicum";
Korte, F.. Ed.; Academic: New York, 1974;
Vol. 1, "Analytical Methods"; Part A; Kiiser,
H. Spectrochim. Acta 1978,33B, 551.
(13) Thompson, M.; Howarth, R. J. Analyst
1976.101,690.
(14) "Definition and Procedure for the Deter-
mination of the Method Detection Limit
Revision 1.12"; U.S. Environmental Protec-
tion Agency, Environmental Monitoring and
Support Laboratory: Cincinnati. January
(IS) Gabrieli, R. Anal Chem. 1970, 42,
1439.
(16) EckJChliger. K. "Errors Measurement ind
Results in Chemical Analysis"; Chalmers, R.
A., Transl,, Van Nosirand Rcinhold; London,
1969; p. 103.
(17) Thompson, M.; Howarth, R. J. Analyst
1980,105, 1188.
(18) Winefordner, J. D.; Ward, J. L. Anal. Leil.
1980. I3(A14). 1293.
(19) Dison, W. J.; Masscy, F. J., Jr. "Intro-
duction to Statistical Analysts", 3rd ed.;
McGraw-Hill: New York, 1969; Chapter 7,
pp. 101-105.
(20) "The Analysis of Aromatic Chemical In-
dicators of Industrial Contamination in
Water by the Purge and Trap Methods"; U.S.
Environmental Protection Agency, Environ-
mental Monitoring and Support Laboratory:
Cincinnati, May 1980.
(21) McMillin, C. R.; Warner, B. J.; Mitrosky,
S. "EPA Method Validation Study 23,
Method 601 (Purgeable Halocarbons)",
Report for EPA Comract 687-03-2856, in
preparation.
(22) McMilUn, C. R.; Warner, B. J.; Strobel,
J. "EPA Method Validation Study 24,
Method 602 (Purgeable Aromatics)", Report
for EPA Contract 68-03-2856, in prepara-
tion.
(23) Hall, J. R.; Florence, J. R.; Strother, D. L;
Maggio. S. M. "Development of Detection
Limits, EPA Method 604, Phenols", Special
letter report for EPA Contract 68-03-2625,
Environmental Monitoring and Support
Laboratory: Cincinnati.
(24) Riggin, R. M.; Bins, M. A. "Determina-
tion of Method Detection Limit and Analyt-
ical Curve and EPA Method 60S—Benzid-
ines". Special letter report for EPA Contract
68-03-2624, Environmental Monitoring and
Support Laboratory: Cincinnati.
(25) Thomas. R. £.; Millar, J. D.; Harding, H.
J.;Schattenberg, H. J. III. "Method Detec-
tion Limit and Analytical Curve Studies.
EPA Methods 606, 607, and 608". Special
letter report for EPA Contract 68-03-2606,
Environmental Monitoring and Support
Laboratory: Cincinnati.
(26) Riggin, R. M.; Cole, T. F. "Determination
of Method Detection Limit and Analytical
Curve for EPA Method 609, Nitroaromalics
and Isophorone", Special letter report for
EPA Contract 68-03-2624, Environmental
Monitoring and Support Laboratory: Cin-
cinnati.
(27) Cole, T.; Riggin, R.; G laser, J. "Evaluation
of Method Detection Limits and Ana,ytLai
Curve for EPA Method 610, PNAs", Proc.
$th Int. Symp. Polynuclear Aromatic Hy-
drocarbons (Battelle Columbus Laboratory.
Columbus, Ohio, 1980).
(28) McMillin. C. R.; Gable, R. C; Kyne, J.
M.;Quill, R. P.;Thomas, J.S. "Development
of Detection Limits, EPA Method 61U
Haloethers", Special letter report for EPA
Contract 68-03-2625, Environmental Moni-
toring and Support Laboratory: Cincinnati.
(29) Hall. J. R.; Florence, J. R.; Strother, D. L.;
Maggio, S. M. "Development of Detection
Limits, EPA Method 612, Chlorinated Hy-
drocarbons", Special letter report for EPA
Contract 68-03-2625, Environmental Moni-
toring and Support Laboratory: Cincinnati.
(30) McMillin, C. R.; Hileman. F. D. "Deter-
mination of Method Detection Limits for
EPA Method 613", Special letter report for
EPA Contract 68-03-2863, Environmental
Monitoring and Support Laboratory: Cin-
cinnati.
(31) Olynyk, P.; Budde, W. L.; Eichelberger,
J. W. "Method Detection Limits of Method
624 and 625 Analytes", unpublished EPA
report. May 1980.
Supplementary Material Available Tables 6~I4
contain additional Method Detection Limits
(MDLs)for the analyses of trace organics in
wastewater. Table 6—volatile compounds by
Method 601. Table 7—phenols by Method
604 using flame ioniiation detection. Table
&—ptniafluorobenzyl derivatives of phenols
by Method 604 using electron capture de-
tection. Table 9—phtnalates by Method 606.
Table 10—niirosamines by Method 607.
Table U—nitroarometics and isophorone by
Method 609. Table 12—halotthers by
Method6ll. Table 13—chlorinated hydro-
carbons by Met hod 612. Table 14—volatile
compounds by Method 624 using GCfMS.
photocopies of the supplementary material
from this paper or Microfiche (105 X 148
mm, 24 X reduction, negatives) may be ob-
tained front Business Operations, Books and
Journals Division, American Chemical So-
ciety, 1155 16thS{.,N.W., Washington,D.C.
20036. Full bibliographic citation (journal,
title of article, author) and prepayment,
check or money order for S13 for photocopy
($14.50 foreign) or $4 for microfiche (}5
foreign), are required.
*USOPOt 1982- 550-092/3394
B-28
Volume 15. Number 12, December 1981 1435
-------
1/21/81
Definition and Procedure for the Determination
of the Method Detection Limit
Revision 1.11
EMSL - CI
Environmental Protection Agency
Office of Research and Development
Environmental Monitoring and Support Laboratory
Cincinnati, Ohio 45268
B-29
-------
Definition
The method detection limit (MDL) is defined as the minimum con-
centration of a substance that can be measured and reported with
99& confidence that the analyte concentration is greater than zero
and determined from analysis of a sample in a given matrix containing
analyte.
Scope and Application
This procedure is designed for applicability to a wide variety of
sample types ranging from reagent (blank) water containing analyte
to wastewater containing analyte. The MDL for an analytical
procedure may vary as a function of sample type. The procedure
requires a complete, specific and well .defined analytical method.
It is essential that all sample processing steps of the analytical
method be Included in the determination of the method detection limit.
The MDL obtained by this procedure Is used to Judge the significance
of a single measurement of a future sample.
The MDL procedure was designed for applicability to a broad variety
of physical and chemical methods. To accomplish this, the procedure
was made devise- or instrument-independent.
Procedure
1 . Make an estimate of the detection limit using one of the
following:
(a) The concentration value that corresponds to an in-
strument signal/noise In the range of 2.5 to 5v
(b) Three times the standard deviation of replicate
Instrumental measurements of the reagent water.
B-30
-------
(c) The area of the standard curve where there is a
significant change in sensitivity, i.e., a break in
the slope of the standard curve.
(d) Instrumental limitations.
It is recognized that the experience of the analyst is
important to this process. However, the analyst must
include the above considerations in the estimate of the
detection limit.
2. Prepare reagent (blank) water that is as free of analyte
as possible. Reagent or Interference free water is defined
as a water sample in which analyte and interferent con-
centrations are not detected at the method detection
limit of each analyte of interest. Interferences are
defined as systematic errors in the measured analytical
signal of an established procedure caused by the presence
of interfering species (interferent). The interferent
concentration is presupposed to be normally distributed in
representative samples of a given matrix.
3. (a) If the MDL is to be determined in reagent (blank)
water, prepare a laboratory standard (analyte in
reagent water) as a concentration which is at least
equal to or in the same concentration range as the
estimated method detection limit. (Recommend between
1 and 5 times the estimated method detection limit.)
Proceed to Step 4.
(b) If the MDL is to be determined in another sample
matrix, analyze the sample. If the measured level of
the analyte is in the recommended range of one to
five times the estimated detection limit, proceed to
Step 4.
B-31
-------
If the measured level of analyte is less than the
estimated detection limit, add a known amount of
analyte to bring the level of analyte between one and
five times the estimated detection limit.
If the measured level of analyte is greater than five
times the estimated detection limit, there are two op-
tions.
(1) Obtain another sample of lower level of analyte
in same matrix if possible.
(2) The sample may be used as is for determining the
method detection limit if the analyte level does
not exceed 10 times the MDL of the analyte in
reagent water. The variance of the analytical
method changes as the analyte concentration in-
creases from the MDL, hence the MDL determined
under these circumstances may not truly reflect
method variance at lower analyte concentrations.
(a) Take a minimum of seven aliquots of the sample to be
used to calculate the method detection limit and
process each through the entire analytical method.
Make all computations according to the defined method
with final results in the method reporting units. If
a blank measurement is required to calculate the
measured level of analyte, obtain a separate blank
measurement for each sample aliquot analyzed. The
average blank measurement is subtracted from the
respective sample measurements.
(b) It may be economically and technically desirable to
evaluate the estimated method detection limit before
proceeding with 4a. This will: (1) prevent repeating
B-32
-------
this entire procedure when the costs of analyses are
high and (2) insure that the procedure is being
conducted at the correct concentration. It is quite
possible that an incorrect MDL could be calculated
from data obtained at many times the real MDL and the
level of analyte would be less than five times the
calculated method detection limit. To insure that
the estimate of the method detection limit is a good
estimate, it is necessary to determine that a lower
concentration of analyte will not result in a sig-
nificantly lower method detection limit. Take two
aliquots of the sample to be used to calculate the
method detection limit and process each through the
entire method, including blank measurements as de-
scribed above in 4a. Evaluate these data:
(1) If these measurements indicate the sample is in
desirable range for determination of the MDL,
take five additional aliquots and proceed. Use
all seven measurements for calculation of the MDL.
(2) If these measurements indicate the sample is not
in correct range, reestimate the MDL, obtain new
sample as in 3 and repeat either 4a or 4b.
Calculate the variance (S2) and standard deviation (S)
of the replicate measurements, as follows:
Xi
S =
n - 1
($2)1/2
where the Xj_, i=l to n are the analytical results in the
B-33
-------
final method reporting units obtained from the n sample
allquots and refers to the sum of the X
values from 1=1 to n.
6. a.) Compute the MDL as follows:
MDL - t(n_1).99) (S)
where:
MDL
= the method detection limit
t(n-l,.99)
= the students' t value appropriate for a
99% confidence level and a standard de-
viation estimate with n-1 degrees of free-
dom. See Table.
S
= Standard deviation of the replicate analyses
b.) The 95% confidence interval estimates for the MDL
derived in 6a are computed according to the following
equations derived from per cent lies of the chl square
over degrees of freedom distribution (X2/df),
LCL =0.69 MDL
UCL =1.92 MDL
where LCL and UCL are the lower and upper 95% confidence
limits respectively based on seven aliquots.
7. Optional iterative procedure to verify the reasonableness
of the estimate of the MDL and subsequent MDL determina-
tions.
a, ) If this Is the initial attempt to compute MDL based
on the estimate of MDL formulated in Step 1, take the MDL
-------
as calculated in Step 6, spike in the matrix at the
calculated MDL and proceed through the procedure starting
with Step M.
b,) If this is the second or later iteration of the MDL
calculation, use S2 from the current MDL calculation and
S2 from the previous MDL calculation to compute the P-
ration. The P-ratio is formed by substituting the
largest S2of the two into the numerator S and the other
into the denominator S. The computed P-ratio is then
compared with the P-ratio found in the table which is
3.05 as follows:
if
S2
A
S2
B
< 3.05,
then compute the pooled standard deviaiton by the fol
lowing equation:
1/2
Spooled
6S2 + 6S2
A
B
12
if
> 3-05,
B
respike at the last calculated MDL and process the
samples through the procedure starting with Step M,
B-35
-------
c.) Use the SpOOxed as calculated in 7b to compute the
final MDL according to the following equation:
MDL - 2.681 (Spooled)
where 2.681 is equal to
= .99)*
d.) The 95% confidence limits for MDL derived in ?c are
computed according to the following equations derived
from per cent lies of the chi squared over degrees of
freedom distribution.
LCL =0.72 MDL
OCL =1.65 MDL
where LCL and UCL are the lower and upper 95% confidence
limits respectively based on 14 allquots.
Table of Students ' t Values at the 99 Percent Confidence Level
Number of
Degrees of Freedom
fc(n-l,.99)
7
8
9
10
11
16
21
26
31
61
00
6
7
. 8
9
10
15
20
25
30
60
00
3.143
2.998
2.896
2.821
2.764
2.602
2.528
2.485
2.457
2.390
2,326
B-36
-------
Reporting
The analytical method used must be specifically identified by number
of title and the MDL for each analyte expressed in the appropriate
method reporting units. If the analytical method permits options
which affect the method detection limit, these conditions must be
specified with the MDL value* The sample matrix used to determine
the MDL must also be identified with the MDL value. Report the mean
analyte level with the MDL. If a laboratory standard or a sample
that contained a known amount analyte was used for this determination,
also report the mean recovery.
If the level of analyte in the sample was below the determined MDL
or does not exceed 10 times the MDL of the analyte in reagent water,
do not report a value for the MDL.
B-37
-------
-------
REFERENCE 4
FIELD RESULTS - DATA SHEETS
B-39
-------
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF RESEARCH AND DEVELOPMENT
ENVIRONMENTAL MONITORING AND SUPPORT LABORATORY
CINCINNATI, OHIO 45268
DATE: July 21, 1982
SUBJECT: Settleable Solids
FROM: Gerald D. McKee, Chief ,1Ly
Inorganic Analyses Secpon
Physical and Chemical Methods Branch
TO: William Telliard, Chief
Energy and Mining Branch
Effluent Guidelines Division
U.S. Environmental Protection Agency (WH-552)
Washington, D.C. 20460
Enclosed are the Method Detection Limits (MDL) calculated from the
settleable solids field data.
All of the observers' data were included in the calculations for each sample
because there was only one aliquoting into each Imhoff cone. The calculated
data are in Table 1.
Two general observations were made in regard to differences between the
field data and the laboratory data:
1) Higher data values were obtained in the field than in the laboratory
with exception of one sample (108).
2) The MDLs are higher for the field data, probably due to two reasons, the
mean values are higher and the field data were reported to only one
significant figure (one exception).
Enclosure (1):
As stated
B-41
-------
TABLE 1
FIELD DATA
Sample No.
82-101
82-102
82-103
82-104
82-105
82-106
82-107
82-108
Source
Mine Pond No. 4
Mine Pond No. 8
Mine Pond No. 7
Mine Pond No. 6
Mine Pond No. 5
Mine Pond No. 2
Mine Pond No. 1
Mine Pond No. 3
ml/l/hr
Mean
0.58
0.36
0.28
0.82
0.65
0.36
0.76
0.094
Standard
Deviation
0.15
0.081
0.08
0.11
0.09
0.043
0.09
0.015
MDL
0.40
0.20
0.21
0.30
0.25
0.11
0.23
0.04
B-42
-------
Date: 5-18-82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-107
Mine Pond No. 1
Sampling Crew: W. Telliard - EPA-EGD
H. Kohlmann - Hydrotechnic
da
i
-Cr
UJ
Pond Influent - Settleable Solids (ml/1) 15.0
Pond Effluent - Settleable Solids (ml/1) 0.0
PH
PH
8.2
8.0
Determination of Dilution, if required.
Based on 8-liter batch, and 0,5 ml/1 range required,
x = vol. of infl. req'd;
y = vol. of effl. req'd;
GI = ml/1 settleable solids in influent
C2 = ml/1 settleable solids in effluent
C,x + C9y = 4,000ml x + y = 8,000 ml
J- b
x = 1,068 ml y = 6,932 ml
Settleable Solids Test Results (ml/1) - pH 8.0
" • — Imjioff Cone #
Observer" • — ^_
Mine Rep.
EPA Rep.
EPA Contractor
1
0.8
0.7
0.65
2
0.7
0.8
0.85
3
0.9
0.8
0.80
4
0.7
0.7
0.90
5
0.9
0.7
0.90
6
0.8
0.7
0.75
7
0.6
0.7
0.7
-------
Date:
5-19-82
tu
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-106
Mine Pond No. 2
Pond Influent - Settleable Solids (ml/1)
Pond Effluent - Settleable Solids (ml/1)
Sampling Crew: W. Telliard - EPA-EGD
H. Kohlmann - Hvdrotechnic
24
0
PH
PH
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required,
x = vol. of infl. req'd;
y = vol. of effl. req'd;
GI = ml/1 settleable solids in influent
C2 = ml/1 settleable solids in effluent
+ C2y = 4,000ml x + y = 8,000 ml
x = 667 ml y = 7333 ml
Settleable Solids Test Results (ml/1) - pH
"" --imhpff Cone #
Observer"""-— -^_
Mine Rep.
EPA Rep.
EPA Contractor
1
0.45
0.30
0.40
2
0.40
0B30
0.40
3
0.40
0.35
0.35
4
0.35
0.35
0.35
5
0.40
0.35
Q.30
6
0.35
0.30
0.35
7
0.4
0.30
0.35
-------
Date:
5-20-82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-108
Mine Pond No. 3
Sampling Crew: W. Telliard - EPA-EGD
H. Kohlmann - Hydrotechnic
td
i
-tr
U1
Pond Influent - Settleable Solids (ml/1)
Pond Effluent - Settleable Solids (ml/1)
pH 8
0
PH 7
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required,
x = vol. of infl. reg'd; C;L = ml/1 Settleable solids in influent
y = vol. of effl. req'd; €2 = ml/1 Settleable solids in effluent
C^x + C2y = 4,000ml x + y = 8,QQO ml
x = 3,200 ml y = 4,800 ml
Settleable Solids Test Results (ml/1) - pH 7
" - — Imhoff Cone #
Observer • — ^_
Mine Rep.
EPA Rep.
EPA Contractor
1
0.13
Q.I
0.1
2
0.11
0,09
0.09
3
0.1
0.09.
0.09
4
0.1
0.09.
0.09
5
0.13
0,08
0.09
6
0,1
0,08
0.09
7
0.09
O.Q7
0.07
-------
Date
5-11-82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-101
Mine Pond No. 4
Sampling Crew: D. Ruddy - EPA-EGD
D. Ruggiero - Hydrotechnic
to
i
-tr
O\
Pond Influent - Settleable Solids (ml/1) Non-Det.
Pond Effluent - Settleable Solids (ml/1) Non-Pet.
Upper Wadge Pond - Influent SS (ml/1) 1.2 ml/1
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required.
PH
PH
7.0
7.0
7.0
x - vol. of infl. req'd;
y = . vol. of effl. req'd;
C]_ - ml/1 settleable solids in influent
C2 = ml/1 settleable solids in effluent
Clx "*" C2y = 4,000ml x + y - 8,OQO ml
x = 4,6.66 ml y = 3,334 ml
Settleable Solids Test Results (ml/1) - pH 7.7
•"— -^JCighpf £ Cone #
Observer "~--— __^
Mine Repfc
EPA Rep.
EPA Contractor
1
0.5
0.6
0.5
2
0,4
0.4
0.4
3
0.5
0.6
0,5
4
0.4
0.5
0.4
5
0.6
0.6
0.6
6
0.7
0.7
0.7
7
0.9
0.9
0.8
-------
Date:
5-18*82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-106
Mine Pond No. 5
Sampling Crew: D. Ruddy - EPA'-EGD
D. Ruggiero - Hydrotechnic
Pond Influent - Settleable Solids (ml/1) 2'°
Pond Effluent - Settleable Solids (ml/1) Non-Det,
pH
PH
6.4
6.4
do
l
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required,
x = vol. of infl. req'd;
y = vol. of effl. req'd;
C^ = ml/1 Settleable solids in influent
C-2 = ml/1 settleable solids in effluent
+ C2y = 4,000ml x t y ~ 8,000 ml
x = 2,gOO ml y = 6,000 ml
Settleable Solids Test Results (ml/1) - pH 6.4
^~" — -Jjnhoff Cone #
Observer "^^— ^_
Mine Rep .
EPA Rep.
EPA Contractor
1
-
0.7
0.7
2
-
0.7
Oe7
3
-
0.7
0.7
4
-
o.e:
0.5
5
-
0,5
0.5
6
-
0,7
0,8
7
-
0,7
0,7
-------
Date: 5-18-82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-104
Mine Pond No. .6
Sampling Crew: D. Ruddy EPA-EGD
D. Ruggiero - Hydrotechnic
i
-Cr
CO
Pond Influent - Settleable Solids (ml/1) 2.0
Pond Effluent - Settleable Solids (ml/1) Non-Pet.
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required.
PH
PH
7.0
7.0
x - vol. of infl. req'd;
y = vol. of effl. req'd;
GI = ml/1 settleable solids in influent
C2 = ml/1 settleable solids in effluent
+ C2y = 4,000ml x + y = 8,000 ml
x = 2,000 ml y = 6,000 ml
Settleable Solids Test Results (ml/1) - pH
7.0
"— — Imhpff Cone #
Observer"""" -— ^_
Mine Rep.
EPA Rep.
EPA Contractor
1
-
0.7
0.7
2
-
1.0
1.0
3
-
0.9
0.9
4
-
0.9.
0.9
5
-
0.8
0.7
6
-
0.7
Q.,7
7
-
0.8
0,8
-------
Date: 5-18-82
to
i
J=r
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-103
Mine Pond No. 7
Pond Influent - Settleable Solids (ml/1)
Sampling Crew: D. Ruddy - EPA-EGD
P. Ruggiero - Hydrotechnic
pH 6.6
Pond Effluent - Settleable Solids (ml/1) Non-Pet.
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required.
pH 6.6
x = vol. of infl. reqfd; C
y = vol. of effl. req'd; (_
Cxx + C2y = 4,000ml x + y = 8,OQO ml
x = 1,000 ml
= ml/1 settleable solids in influent
= ml/1 settleable solids in effluent
Y =
7,000 ml
Settleable Solids Test Results (ml/1) - pH 6.6
~--— Imjioff Cone #
Ob s e r ver^~"^-^^^
Mine Rep .
EPA Rep.
EPA Contractor
1
-
0.2
0.3
2
-
0.3
0,3
3
-
0.4
0.4
4
-
0.2
Q.3
5
-
0.2
Q.2
6
-
Q.3
0.4
7
-
0.2
0.2
-------
Date:
5-20-82
SETTLEABLE SOLIDS TESTING
DATA SHEET
82-102
Mine Pond No. 8
Sampling Crew: D. Ruddy - EPA-EGD
D. Ruggiero - Hydrotechnic
tc
ui
o
Pond Influent - Settleable Solids (ml/1)
0.3
Pond Effluent - Settleable Solids (ml/1) Non-Pet .
Determination of Dilution, if required
Based on 8-liter batch, and 0,5 ml/1 range required,
pH 8.1-8.2
pH 7.6-7.7
x = vol. of infl. req'd;
y = vol. of effl. req'd;
Clx + C2y = 4'000ml x
C^ = ml/1 Settleable solids in influent
C2 = ml/1 Settleable solids in effluent
= 8,QQO ml
x = 7,000 ml y = 1,000 ml
Settleable Solids Test Results (ml/1) - pH 8.1-8.2
~~-- Jjnhpff Cone #
Observer ^_
Mine Rep.
EPA Rep.
EPA Contractor
1
0.3
0.3
0.3
2
0.3
0.4
0.4
3
0.3
0.3
0.3
4
0.4
0.4
0.5
5
0.3
0.3
0.3
6
0.3
0.3
0.3
7
0.5
0.5
0.5
-------
REFERENCE 5
LABORATORY RESULTS
B-51
-------
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF RESEARCH AND DEVELOPMENT
ENVIRONMENTAL MONITORING AND SUPPORT LABORATORY
CINCINNATI, OHIO 45266
DATE: June 15, 1982
SUBJECT: Settleable Solids
FROM: Gerald D. McKee, Chief
Inorganic Analyses Sec1
Physical and Chemical Methods Branch
TO: William Telliard, Chief
Energy and Mining Branch
Effluent Guidelines Division
U.S. Environmental Protection Agency (WH 552)
Washington, DC 20460
Enclosed are the Settleable Solids data for the eight samples we received
from various mining operations. As decided in our discussion of April 22,
1982, we determined the Method Detection Limit (MDL) on each of the samples
and the variability (standard deviation) of data on samples with a concen-
tration of about 0.5 ml/l/hr Settleable Solids.
The "Method Detection Limit" is defined as the minimum concentration of a
substance that can be measured and reported with 99% confidence that the
analyte concentration is greater than zero and determined from analysis of a
sample in a given matrix containing analyte. Two papers describing this
method are attached. The variability of each sample is reported as the
standard deviation of seven replicate measurements.
A total of 8 samples were received for analysis, 5 on 5/21/82 and 3 on
5/24/82. Samples were approximately 8 liters in volume and were contained
in 2.5 gallon cubitainers. Cubitainers were placed on a large (2 ft.
square) magnetic stirrer and mixed at high speed using a 4 inch Teflon
coated stirbar for at least 10 minutes before aliquoting. Seven aliquots
were obtained using a glass delivery tube (inserted about mid level into the
sample) and compressed air to transfer the 1 liter sample directly into the
plastic Imhoff cones.
The procedure used for this analysis (EPA Method 160.5) is found in
"Standard Methods for the Examination of Water and Wastewater," 14th
Edition, Page 95, Method 208F, Procedure 3A (1975).
To level the settled material as much as possible, the individual Imhoff
cones were tapped with a wooden rod and/or the liquid was gently swirled
with a glass stirring rod before reading. This leveling seemed to have no
adverse effect on the solids reading.
B-53
-------
- 2 -
Data from one sample (82-104) were discarded because they were obviously not
random. The first aliquot taken was the highest in concentration and each
subsequent sample was lower with a range of 0.80 ml/l/hr (first) to 0.40
ml/l/hr (last). Analysis of this sample was repeated and these data are
Included.
The calculated data are In Table 1. Our conclusions are:
1) The calculated MDL for Settleable Solids of sample's used for this
investigation was 0.12 ml/l/hr. Since-the Imhoff cone has
divisions of only 0.1 ml, practically this MDL is O.H ml/l/nr.
2) The standard deviation of the six samples near 0.5 ml/l/hr (x •
0.45 ml/l/hr), excluding samples 82-102 and 82-103, is 0.043
ml/l/hr.
Enclosures:
As stated
B-54
-------
Table 1
ml/l/hr
Sample No.
82-101
82-102
82-103
82-104
82-105
82-106
82-107
82-108
Source
Mine
Mine
Mine
Mine
Mine
Mine
Mine
Mine
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
No.
No.
No.
No.
No.
No.
NO.
No.
4
8
7
6
5
2
1
3
Mean
0.58
0
0
0
0
0
0
0
.14
.12
.43
.45
.32
.37
.55
Standard
Deviation
0
0
0
0
0
0
0
0
.048
.016
.018
.043
.041
.046
.038
.041
MDL
0.15
0.
0.
0.
0.
0.
0.
0.
050
057
14
13
14
12
13
B-55
-------
82-101 Mind Pond No. 4
Date 5-17-82, Received 5-21-982, Analyzed 5-26-82
Lt. Brown Color, Some Silt and Sticks, pH 8.3
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.58
0.60
0.55
0.65
0.60
0.50
0.55
0.58
0.048
0.15
(0.45 in 820 ml)
82-102 Mine Pond No. 8
Date 5-20-82. Received 5-21-82, Analyzed 5-26-82
Light Brown Color, Some Pines, pH 7.9
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.12
0.15
0.15
0.15
0.12
0.15
0.12
0.14
0.016
0.050
B-56
-------
82-103 Mine Pond No. 7
Date 5-18-82, Received 5-12-83, Analyzed 5-27-82
Light Brown Color, Pew Pines, pH 7-9
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.15
0,12
0.10
0.10
0.12
0,12
0.10
0.12
0.018
0.057
82-104 Mine Pond No. 6
Date 5-18-82, Received 5-21-82, Analyzed 6-4-82
Light Brown Color, Some Pines, pH 8.2
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.50
0.45
0.48
0.40
0.40
0.40
0.40
0.43
0.043
0.14
B-57
-------
82-105 Mine Pond No. 5
Date 5-18-82, Received 5-21-82, Analyzed 5-27-82
Light Brown Color, Some Fines, pH 8.0
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev,
MDL
ml/l/hr
0.50
0.50
0.45
0.45
0.40
0.45
0.40
0.45
0.041
0.13
82-105 Mine Pond No. 5 Duplicate
Analyzed 6-4-82
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.45
0.40
0.40
0.40
0.42
0.42
0.45
0.42
0.022
0.070
B-58
-------
82-106 Mind Pond No. 2
Date 5-19-82, Received 5-24-82, Analyzed 5-28-82
Light Brown Color, Some Fines, pH 7.9
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.38
0.35
0.35
0.30
0.30
0.25
0.28
0.32
0.046
0.14
82-107 Mine Pond No. 1
Date 5-18-82, Received 5-24-82, Analyzed 5-28-82
Light Brown Color, Some Pines, pH 8.2
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev,
MDL
ml/l/hr
0.40
0.40
0.40
0.38
0.30
0.35
0.38
0.37
0.038
0.12
B-59
-------
82-107D Mind Pond No, 1
Duplicate, Analyzed 6-4-82
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.50
0.55
0.40
0.50
0.40
0.50
0.40
0.46
0.063
0.20
82-108 Mine Pond No. 3
Date 5-20-82, Received 5-24-82, Analyzed 6-2-82
Yellow Color, Heavy Flock, pH 7.9
Aliquot
1
2
3
4
5
6
7
Mean
Std. Dev.
MDL
ml/l/hr
0.50
0.55
0.60
0.60
0.50
0.55
0.55
0.55
0.041
0.13
B-60
-------
APPENDIX C
INVESTIGATION OP POST-MINING
DISCHARGES AFTER
SMCRA BOND -RELEASE
C-i
-------
-------
INVESTIGATION OF POST-MINING
DISCHARGES AFTER
SMCRA BOND RELEASE
SEPTEMBER 1982
Prepared by:
OFFICE OF ANALYSIS AND EVALUATION
OFFICE OF WATER REGULATIONS AND STANDARDS
U.S. ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON, D.C. 20460
C-iii
-------
-------
As stated in the Preamble of the proposed Coal Mining Point Source
Regulations (46 FR 3146 January 13, 1981), a data collection effort was
initiated to provide the Agency with a basis for assessing the
appropriateness and feasiblity of establishing national regulations
applicable after SMCPA Bond Release. The objective of this effort was to
assess the possibility and severity of pollution discharges at coal mines
after SMCRA Bond Release, and to address the cost-effectiveness and economic
impacts of setting effluent limitations after release of bond.
The Agency recognized that the minimum liability period for reclamation
at underground mines that closed under OSM Regulations ( 44 FR 15336 March
13, 1979) had not expired and at most was only three years old. However,
the Agency hoped that the information collected in the survey, combined with
records and documents submitted by interested parties during the public
comment period, would provide a suitable data base to project the
possibility and extent of post-bond release pollution and the
cost-effectiveness of extending the period of liability0 after a reclamation
bond was released by OSM.
. A preliminary telephone survey was conducted during October and
November 1980 to establish the best sources of data in the regulatory
community. The responses yielded very limited information from eight states
(Table 1) and little encouragement of data being available in the next few
years. A literature search was also conducted at that time, which produced
six reports relevant to the survey. Only one of the six reports proved to
be of direct interest. The report is a study of the long-term environmental
effectiveness of close down procedures at eastern underground coal mines and
was prepared in August 1977 for EPA's IERL, Cincinnati. The study found
that from the 200 locations identified as closed or abandoned coal mines,
only 86 provided sufficient data for inclusion in the study. The study1 s
conclusions are specified as being general and of a preliminary nature due
to the extreme variability of the available data, both historical and
analytical. The two conclusions of interest are: 1) that the sealing
efforts with longer monitoring records covering both the pre and post
closure periods were sponsored by State or Federal agencies; and 2) that
based on these records the overall effect of the studied closures on water
quality is beneficial. However, the effectiveness is determined
predominately by the physical characteristics of the landscape and the type
of mining operation instead of the sealing technology.
The questionaire portion of the survey was deferred until a sufficient
number of coal mines could be identified as being relevant to the survey.
Although both pro and con comments were received on post-bond release
regulations during the proposed regulation's comment period, no records or
documents were submitted to substantiate either position and no mines were
identified for additional evaluation. Therefore, a final survey review was
initiated to examine all the previous data collected and attempt to augment
C-l
-------
it with any information currently available from Federal, States, and public
sources. Discussions with OSM have revealed that the Abandoned Mine Lands
Program had completed one underground mine reclamation project to date,
while the Federal Reclamation Program has about 200 underground mine
projects (number of mines unknown) completed or under contract since FY79.
Although none of these mines are known to have developed a failure ( i.e., a
new discharge point or an unacceptable discharge quality), none have been
closed longer than the normal bonding period o£ five years (10 years west
of the 100th meridan). The Pennsylvania Department of Environmental
Resources attempted to compile a similar list of closed mines from permits
issued between 1965 and 1975 to estimate the number of closed and abandoned-
mine inspections needed. An estimate of 1,000 closed mines was made with no
estimate available on the number closed under SMCRA or state reclamation
regulations, or the number causing water quality problems. The use of
comprehensive field inspection to determine the status of closed or
abandoned mines has not been attempted cy any state or federal agencies due
to the high cost, lack of trained personnel, and the uncertainty of the
results. The failure of a mine seal could produce new discharge points at
rock fractures, mine vents, air ducts/ or even ground seeps anywhere in the
vicinity of the mine site. Adverse changes in water quality could occur in
normal runoff waters, new discharge points, or underground streams. The
ability of a field inspection to determine the occurrence, cause, and source
of any of the above events is directly related to the physical
characteristics of the mine and its location. The State of Pennsylvania has
required that a water-tight seal be used when closing a coal mine since
1965. In the period from 1975 to 1980, 30 small coal mines were closed by
the State (20 of these are included in the report discussed previously) and
15 were closed by the mine operators. The available background,
correspondence, and water quality data on six Pennsylvania closed mines
currently causing water quality problems were reviewed for use as a
representative sampling. This approach was rejected due to the large
variability in both the mine and sealing, technology parameters (when
sufficient data was available to make such determinations).
Finally, another literature search was conducted in July 1982 for case
studies or technology demonstrations of closed mines. Oily three additional
references were found potentially useful from the 397 references reviewed.
The first reference is a case study on sealing an underground deep mine in
Pennsylvania in compliance with the states sealing regulations. The second
reference is a case study on methods used to seal a closed mine with a
continuous discharge in Japan. The final reference is an evaluation of
water pollution prevention and control from inactive and abandoned
underground mines. It surveys mining, sealing, and treatment methods
developed largely in eastern U.S. coal fields. Although usefulr these three
reports did not contribute significant r*ew data.
In summary, tne Agency has been able to develop estimates of the number
of active, closed, and abandoned coal mines but has not been able to
determine the number of closed coal mines sealed or reclaimed under SMCRA.
C-2
-------
Also, the Agency has not been able to determine the number of closed coal
mines that are the source of water quality problems after being sealed or
reclaimed in compliance with SMCRA or equivalent state regulations. Based
on the results of this data collection effort, it is felt that there is
insufficient data available to support the development of national
regulations on post-bond release. Therefore, the basis for a nationally
applicable regulation for discharges after bond release does not currently
exist, and any point source discharge after bond release that might occur
can be addressed through the NPDES permit system.
References
(1) Telephone Survey Report
(2) Hydrotechnic Trip Report
(3) Results of 1980 Literature Search
(4) Final Survey Review Telephone Memos
(5) File Histories of six closed PA coal mines
(6) 1982 Literature Search Report
C-3
-------
Table 1
Identification of Data From State Agencies
Pennsylvania - Limited data on 45 mines most of which is already summarized
in EPA Report "Long-Term Environmental Effectiveness of Close Down
Procedures - Eastern Underground Coal Mines."
Tennessee - Limited data on a few mines sealed with impervious clay or
backfilled spoils.
Illinois - Data on only a few mines.
Maryland - Water Quality data on streams, not on specific mines.
Virginia - No data available.
Alabama - Three mines backfilled with spoil material.
Kentucky - Little useful data on sealing effectiveness.
West Virginia - Some data available from a demonstration project.
-------
REFERENCE 1
TELEPHONE'SURVEY REPORT
C-5
-------
-------
Verssir
inc.
MEMORANDUM
TO:
FROM:
DATE:
SUBJECT:
Bill Kaschak
/, /
Greg Schweer j$/Qr
October 24, 1980
Type and Availability of Data
Effectiveness of Underground
cc: B. Maestri
P. Abell
Concerning the Long-Term
Coal Mine Sealing Procedures 569TM-60
A telephone survey was conducted on October 21, 22, and 23, 1980, by
Versar personnel to determine the type and availability of monitoring data and
any other relevant data that will enable MDSD to assess the long-term effective-
ness of underground coal mine sealing procedures. The scope of this survey
was limited due to OMB restraints on the number of non-federal contacts
allowed for survey purposes. State mining and/or environmental officials
in five coal producing states (Pennsylvania, Tennessee, Maryland, Alabama,
and Virginia) as well as EPA personnel in three regions (3,4, and 5) and one
consulting firm (Hydrotechnics Corp) were contacted during the course of this
survey. The results of the limited number of interviews conducted indicate
that, with the exception of the State of Pennsylvania and the data gathered for
the HRB-Singer Study, little pertinent data are available. The available
data are summarized below.
• Pennsylvania - Limited seal effectiveness data available on approximately
thirty abandoned mines sealed by the state and approximately fifteen
mines sealed by coal companies in the past fifteen years. Water quality
data available for some mines particularly in Maraine State Park.
* Tennessee - Limited seal effectiveness data available on several mines
sealed with impervious clay or backfilled spoils.
» Illinois - Some mines have been reported to have been sealed but
more in depth contacts are required.
• Maryland - Good water quality data available on a recently sealed
mine. Locations of some old sealed mines can also be identified.
* Alabama - Limited data available on three mines backfilled with spoil
material.
• Virginia - No data available.
C-7
-------
Vcrsar,
October 24, 1980
Memorandum 569TM-60
Page 2
• West Virginia - Information available on abandoned mines sealed
in the Roaring Creek - Grassy Run watersheds as part of the Federal-
State Elkins Mine Drainage Pollution Control Demonstration Project.
No useful contacts were established in this state.
• Kentucky - Little useful data on sealing effectiveness seem to be
available.
Attached to this memorandum are photocopies of the file memos for each
telephone interview conducted. Also attached are file memos from another
Versar project concerning State regulations pertatrving to coal mining. The
latter set of memos present some general information on the extent: of under-
ground coal mining and pertinent regulations for individual states.
It is recommended that a more intensive telephone survey be conducted to
further determine the type and availability of pertinent data. All the coal
producing states in the Eastern United States (i.e., Illinois, Indiana, Iowa,
Kentucky, Maryland, Ohio, Pennsylvania, Tennessee, Virginia, and West Virginia)
should be investigated. At a minimum, the following officials/groups should
be contacted.
State environmental officials
State mining officials
State geological surveys
U.S. Geological Survey Districts
U.S. Bureau of Mines Districts
University Officials
Coal companies
Coal industry trade associations (e.g., National Coal Association
and Bituminous Coal Research)
C-8
-------
Pennsylvania
FILE MEMO
Name
Time
Gre
Date 10/23/80
11:00 a.m.
File No.
569.1.1
Subject Coal Mine - Post Mine Drainage Control
- in State of Pennsylvania
Persons Contacted:
Name D. Richard Thompson, Chief
Name
Mine Drainage Control & Reclamation
Company Deot. Environmental Resouff^ag Company
Phone
717-783-8845
Phone
Comments: Referred me to:
Richard Hoffman or Evan Schuster
Bureau of Water Quality Mgmt.
Non-Point Industrial Sources
Dept. of Environmental Resources
and
Bud Frederick
Mine Area Restoration
Dept. of Environmental Resources
Action Required
717-787-8184
717-787-7668
C-9
-------
Pennsylvania
FILE MEMO
Name
Time
Greg Schweer
Date 10/23/80
11:10 a.m.
File No.
569.1.1
Subject
Coal Mines - Post Mine Drainage Control
- in State of Pennsylvania
Persons Contacted:
Name
Schuster
Name
Company Bureau of Water Quality Mgmt.Company
Phone Non-Point Industrial Sources B]phone
Dept. of Environmental Resources
Comments:
This branch is the permit issuing section including permits for
mines. "Water-tight" coal mine seals have been required since
1965 by the State of Pennsylvania. Mr. Schuster is not certain
how many mines have been sealed since 1965 but a review of the
files would reveal this info (15 mines have been sealed since
1976). Also, the files may contain some water quality monitoring
data and any inspection reports on mine seal conditions. Due to
lack of manpower and funds, the state has done little monitoring
and inspection of sealed mines. Mr. Schuster was receptive to the
idea of EPA extracting data from his files and for conducting a
survey of ^e sealed mines. Mr. Schuster will assist
in any way possible.
C-10
-------
Pennsylvania
FILE MEMO
Name
Time
Greg Schweer
Date 10/23/80
1:30
File No. 569.1.1
Subject
Coal Mines - Post Mine Drainage Control
- in State of Pennsylvania
Persons Contacted:
Name Bud Frederick
Company Abandoned Mine Area Resto-
Name Dave Hbgeman
Company same
ration Division/ Dept. Environmental Resources
Phone 717-787-7668 . Phone
Comments:
Mr. Frederick was in a day-long meeting so I spoke with his
assistant, Dave Hbgemaru This division is concerned with abandoned
mine reclamation. Approximately 30 mines have been sealed by the
state in the past 15 years. Twenty of these mines are small mines
located in Moraine State Park for which there is water quality data
and relatively routine inspection by the state ^personnel and U.S.
Bureau of Mines personnel. Most of these mines were covered in the
HRB-Singer study according to Ifogeman. Any data in the state files
can be made available to the EPA but it may require some "digging."
Any request for data should be made to Bud Frederick. Hogeman's
A tion R a ired suggested that Max MacsiirDvic, U.S. Bureau of Mines,
" Pittsburgh, PA (412-675-6549) be contacted for
additional information.
C-ll
-------
Tennessee
FILE MEMO
Name
Time
Greg Schweer
Date 10/23/80
3:30
File No.
569.1.1
Subject Coal Mines - Post Mine Drainage Control
- in State of Tennessee
Persons Contacted;
Name Bob McKay, Permit Office
Company Tenn. State Water Quality
•' uontroi Hcancn
Phone 615-741-2275
Name ___
Company
Phone
Comments:
Bob McKay referred me to Gary Mabry, WQCB, Surface
Mining Office, 615-741-7883
and to Billy Tucker, Tennessee Dept. of Conservation
Surfaces Mining Office
615-741-1046
Action Required
C-12
-------
Tennessee
FILE MEMO
Name
Time
Grecr Schweer
Date
10/22/80
3:40
File No.
569.1.1
Subject Coal Mines - Post Mine Drainage Control
- in State of Tennessee
Persons Contacted:
Name Gary Mabry, Surface Mining Off. Name
Company Tenn. State Water Quality
Control Board
Phone 615-741-7883 L
Company
Phone
Comments: - not in office (3:40 pm 10/22)
- will call again on 10/23
- not in office (9:30 10/23)
- called at 10:30 10/23. Mabry referred me to his assistant,
Cliff Bole (geologist). Mr. Bole was very helpful and
interested in the survey. He said that Tennessee has liioited
data on the effectiveness of mine seals. In recent years,
several mines have been sealed with impervious clay material
or bulldozed spoils. A more elaborate seal is being required
on an abandoned mine in a surface mine tract being operated
by Calcan Mining Co. Mines were not required to be sealed
until recently.
Action Required He informed me of a case study of a mine near
his birthplace in Western Pennsylvania. Near the town
of Kettaning in Armstrong County, a mine seal broke in
the summer of 1980 that had been successful for 13 years.
A three-foot high flood of water gushed out of the
mine and caused quite extensive damage to a trailer park
downstream. He strongly recommends that I contact D. R.
Thompson, Chief
Mine Drainage Control & Reclamation Division (Dept. of Env. Resource*
P. 0. Box 2063
Fulton Bldg., 7th Floor 717-783-8845
Harrisburq, PA 171.00
C-13
-------
Illinois
FILE MEMO
Name Gre9 Schweer
Time
Date 10/22/80
3:20
File No.
569.1.1
Subject Coal Mines - Post Mine Drainage Control
- in State of Illinois
Persons Contacted:
Kame
Grosbold, Director
Name
Company Mining Land Reclamation
Phone 217-782-0588
Phone
Comments:
Called 10/22 and spoke to Mr. Grosbold's assistant and
explained the nature of our request. Mr. Grosbold will return
the call on 10/22 or 10/23.
Action Required
-------
Maryland
FILE MEMO
Name
Phil
Date W2V80
Time 3:00
File No. 569.1.1
Subject Data on mine sealing in Stafrfl gf Maryland
Persons Contacted:
Name Pat Gallagher
Company EM - Maryland
Phone 301-689-4136
Name ___
Company
Phone
Comments:
See attached sheet.
Action Required
C-15
-------
Name: Pat Gallagher
State: Maryland (301)689-4136
1. Mine sealing techniques used - yes. 1 known case.
Double - blkhead (gravel) with center concrete plug.
2. Success in preventing post-mine drainage. This seal was
finished in March 80.
3. Maintenance required - No - none anticipated. Obs. well is
in place to allow monitoring.
4. Failures - W.Q. data available for:
a) post-failure Being closely monitored.
b) pre-sealing - yes and flow
5. Failures - has re-sealing or treatment been feasible? Treatment
would be feasible. Could be pumped out if needed since
it is a relatively small mine.
6. Failures - any environmental damage reported? N/A
7. Is list available of all mines sealed within the past five years?
This is the only recent one. Some very old WPA seals.
N/A
This is a
10-acre mine.
C-16
-------
Kentucky
FILE MEMO
Name Phil flbell
Time 3:20
Date
10-22-80
File No.
569.1.1
Subject Mine sealing techniques and effectiveness
Persons Contacted:
Name
Name
Company Kentucky Geological Survey Company
Phone
(606) 258-5863
Phone
Comments:
Had no information. Referred me to:
Kentucky Department of Mines and Minerals
(606) 254-0367
Action Required
C-17
-------
Alabama
FILE MEMO
Name
Time
Phil Abell
Date 10-22-80
2:20
File No.
569.1.1
Subject Mine sealing techniques and effectiveness
Persons Contacted:
Name
Joe Meyers
Company Alabama ?
Phone
(205) 277-3630
Name
Company
Phone
Comments:
Had no information.
Referred me to Bob teller in charge of lands reclamation
(205) 832-6753
Action Required
C-18
-------
Alabama
FILE MEMO
Name
Time
Phil Abell
Date
10-22-80
2:35
File No.
569.1.1
Subject Mine sealing techniques and effectiveness.
Persons Contacted:
Name Bob Vfeller
Company Alabama Land Reclamation
Phone (205) 832-6753
Name __
Company
Phone
Comments:
Have only "sealed" 3 mines. These were not really seals.
Simply filled the mines with spoil material. No plug or cap,
Action Required
C-19
-------
Virginia
FILE MEMO
Name Phil Abell
Date
22 October
Time 10:3°
File No.
569.1.1
Subject Mine sealing techniques and effectiveness
Persons Contacted:
Bob Dott (reached)
Name Fred Kaurich (out sick)
Company Va. Mater Control Bd.
Phone (703) 628-5183
Name ___
Company
Phone
Comments:
Va. W2B does not ironitor mines specifically. May have w.q,
stations near mine, but that is incidental. Suggested I call:
Dept. of Labor and Industry
Division of Mines and Quarries
Big Stone Gap, Va.
(703) 523-0335
Mr. Wheatley will call 10-23-80.
Action Required
C-20
-------
Virgnia
FILE MEMO
Name Phil Abell
Date
10-22-80
Time 2:00
File No.
569.1.1
Subject Mine sealing techniques, and effectiveness.
Persons Contacted:
Name Mr. Wheatley
Name
Va. Dept. of Labor & Industry
Company Division oZ Mines & Quarries Company
Phone
(703) 523 0335
Phone
Comments:
Mr. Wheatley was not in his office. Will return the call
tomorrow (10-23-80).
1:10 p.m. 10-23-80
Mr. Wheatley called me back. He is not aware of any
.program in the state of Virginia. Mines must be closed to
prevent entry of people. No record is kept of closures or
water quality. At least not during the past 7 years since
Wheatley has been with the office. - •
Action Required
C-21
-------
Hydrotechnics
FILE MEMO
Name
Time
Date 10-22-80
3:00
File No. 569.1.1
Subject Mine sealing techniques and effectiveness
Persons Contacted:
Name
Company
Phone
,Dansberger
Name
Hydro-technics Corp.
212-695-6800
Company
Phone
Comments:
Discussed the report prepared by Victoria Lickers. Alex said
they really have very little information (as far as he knows) on the
engineering aspects (type of seal, etc.). They're mainly concerned
with water quality. He is going to try and come up with some good
contacts in Perm, and will call me back.
10-23-80 Returned call. Recommended Giovannitti.
Action Required
C-22
-------
EPA - Atlanta
FILE MEMO
Name Phil Abell
Date 10-22-80
Time
2:00
File No.
569.1.1
Subject
Mine sealing techniques and effectiveness
Persons Contacted:
Name
Mike Taimi
Company EPA - Atlanta
Phone 404-881-4727
Name
Company
Phone
Comments:
Mr. Taimi will return the call later today,
Action Required
C-23
-------
Wfest Virginia
FILE MEMO
Name PhilAbell
Time 1:45
Date 10-22-80
File No. 569.1.1
Subject Mine sealing and effectiveness,
Persons Contacted:
Name Bob Scott
Company
W. Va. DNR
Phone O04) 636-1767
Name
Company
Phone
Comments:
Bob Scott was out, but is expected to return on Thursday 10-23-80.
Called again 10-23-80. Still not in. Secretary expects him in tomorrow,
Action Required
C-24
-------
EPA - Atlanta
FILE MEMO
Name
Time
phil
Date 10-23-80
3:15
File No.
569.1.1
Subject Mine sealing techniques and effectiveness.
Persons Contacted;
Name
Mike Taimi
Name
EPA- Atlanta
Company
Phone <404> 881-4727
Company
Phone
Comments:
In charge of NPDES permitting for mine.
Mike said most of the sealed mines he knows of also
have large disturbed areas and spoil piles* The runoff
from these is collected and discharged together with the drainage
from the mine itself. This obviously biases the data and would
mask the effectiveness of the sealing technique. He is not
really aware of any data base on this subject for the Kentucky
Region (his area).
Action Required
C-25
-------
Illinois
FILE MEMO
Name Gre9 Schweer
Date
10/22/80
Time 3:15
File Ho. 569.1.1
Subject Coal Mines - Post Mine Drainage Control
- in State of Illinois
Persons Contacted:
Name
_Bob
EPA, Field Inspector
Company
Phone 618-997-4371
Name ___
Company
Phone
Comments:
Does not have any pertinent data but can identify mines
that have been sealed in recent years.
-• Suggested that Al Grosbold, Director
Mining Land Reclamation Council
618-782-0588
be contacted.
Action Reguired
C-26
-------
Name
Time
Greg Schweer
3:45
EPA - Region III
FILE MEMO
Date
10/23
File No. 569.1.1
Subject
Coal Mines - Post Mine Drainage Control
- in EPA Region III
Persons Contacted!
Name Kathy Ifodgekiss
Company EPA Region 3 - Enforcement
Phone 215-597-2945
Name _____
Company
Phone
Comments:
Hodgekiss knew of no available data hut would check around and
call B. Kaschak if any relevant data are found.
Action Required
C-27
-------
IOC
MEMORANDUM
TO: Fiie Date: August 16, 1977
475.15-106
FRCM: Linda Kay
SUBJECT: State Regulations Pertaining to Coal Mining - TTTTMTITS
ILLINOIS
Division of Water Pollution Control, Permit Section
217-782-0610
Mark Bryant
Illinois has established its own regulations for the mining of coal in
this state. Permits must be obtained from both the Division of Water
Pollution Control and the Department of Mines and Minerals in order to mine.
The state has established its own effluent standards which, for some parameters,
are more stringent than EPA's BP T standards. Only BPT standards are enforced
at present. Mark Bryant is sending Versar a copy of the state's permit conditions,
Sludge disposal does not appear to be much of a problem for Illinois.
A sludge build-up has not yet occurred in most treatment facilities. In
those cases where a build-up has occurred, mine sediments and sludge are
lagooned and evaporated. In sane instances, the dried solids are buried.
No regulations specifically address sludge disposal, however, state officials
consider it a solid mine waste and regulate its disposal under Chapter 4
of the Pollution Control Board Regulations for Mine Related Pollution.
Department of Mines & Minerals
Ernest Ashby 217-782-4970
Bob Robson 217-782-6792
Illinois regulates strip mining and strip mine reclamation. Ernest
Ashby is sending Versar a copy of these regulations.
According to both Ernest Ashby and Bob Robson, Illinois has no problem
with acid producing coal mines. Apparently all surface mines are required
to be designed so as to prevent water from comirig in contact with the coal
seam. Also, reclamation techniques prevent any problems with run-off.
Bob Robson insisted that deep mines have no drainage problems. Ke cited
two reasons: 1) diminished precipitation ill the mid-west as ccr^ared to the
east and 2) the structure of deep mines in Illinois. Deep coal mines in
this state are shaft mines runnincr straight down for 250' to 1000'.
C-28
-------
MEMO
August 16, 1977
475.15-106
This information contradicts Versar's observations of mining in this
state. The Will Scarlet Mine (Peabody Coal) had sore of the most acid
discharges encountered in the BAT Coal screening sampling.
Environmental Protection Agency
Bob Gates, Field Inspector
618-997-4371
Bob Gates was sorrewhat more realistic about mine drainage problems
in Illinois. He did provide a "partial" list of counties where a potential
for acid drainage exists. They include: St. Clair, Monroe, Randolph,
Jackson, Johnson, Williamson, Christian, Vermillion, Jfessac, Pope, Hardin,
Saline, Gallatin, Franklin, Madison, Douglas, Bond, Jefferson, Knox, Peoria,
Fulton, and Macoupin.
C-29
-------
MEMORANDUM
August 9, 1977
TO: 475.15 File
FKM: Lirda Kay
SUBJECT: State Regulations Pertaining to Goal Mining
ICWA
Soil Conservation Department
Division of Mines and Minerals
515-281-5851
Marvin Ross
Iowa dees very little to regulate coal mining principally because this
industry is so small in this state. Presently there are only 2 underground
mines and 7 surface mines in operation. Large deposits of coal, however,
underlie this area and officials expect the industry to increase in size in
the future with the current ernphasis on coal as an energy source*
Iowa does have a surface mine reclamation act that went into effect
February 1, 1977. Versar will receive a copy of the act and the accompanying
regulations.
Acid mine drainage is not much of a problem in Iowa. Only a couple of
mines have acid discharges and, due to relatively lew precipitation rates in
this area of the country, their discharge volume is minimal. Abandoned
strip pits are the largest concern in this respect. During particularly
heavy storms, the pits sometimes overflew and discharge acid water into local
drainage systens.
Department of Environmental Quality
Division of. Water Quality
Joe Cber
515-265-8134
The Division of Water Quality dees not make any attempt to monitor
drainage frcrn coal mine operations. It dees not administer a permit program
and it has not established any effluent standards.
All regulation of the coal industry has been delegated to the federal
ccvenrrsnt. The U.S. EFA (P^gicn V) administers the NFDES permit program ar^f
enforces EFT effluent standards in this stats.
C-30
-------
Vcrsai
inc.
MEMORANDUM
TO:
475.15 File
Data: August 30, 1977
475.15-114
FFCM: Linda Kay
SUBJECT: INDIANA - State Regulations Pertaining to Coal Mining
INDIANA
Indiana Stream Pollution Control Board
Water Pollution Control Division
317-633-0751
Jim Ray
Indiana has been approved by EPA to administer the federal NPDES permit
program. Ihe state is therefore enforcing BPT effluent standards for the
coal mining industry.
According to state water pollution authorities, acid mine drainage is
not much of a problem in Indiana, A few abandoned mines are sources of acid
water and there are some potentially acid areas along Indiana's southwest
border in Vigo, Sullivan, Knox, Gibson, and Posey counties. However, the
employment of new mining methods required by the surface mine reclamation
act prevents the formation of acid drainage.
The Water Pollution Control Division is not aware of any problems in
the industry with sludge disposal and it has not developed regulations which
address the topic.
Department of Natural Resources
Division of Reclamation
317-633-6217
Richard McNabb
Indiana has a surface mine reclarration act in effect. Richard McNabb
is sending Versar a copy of the act and accompanying regulations.
Surface ironing comprises the bulk of the mining industry in this state.
There are presently only two active deep mines.
C-31
-------
•
inc.
MEMORANDUM
TO; 475.15 File j
Linda Kay "3-
Data: August 8, 1977
475.15-99
SUBJECT: Ohio - Survey of Coal Mining States Regarding State Regulations
Pertaining to Coal Mining.
Chio
Department of Natural Resources
Division of Reclamation
614-466-4850
Barbara Merrill
Ohio regulates strip mining and strip mining reclamation. Division
of Reclamation will send Versar a copy of state regulations,
Division of Mines (Ohio)
614-466-4240
This division regulates mine safety only.
Office of Wastewater Pollution Control
614-466-2390
Dave Danford
Ohio administers EPA's NPDES program and currently has approved
677 permits. Ohio is just beginning to actively monitor mining
activities and is currently enforcing BPT standards as they
appeared in the Federal Register. In the past, coal mining has
been a low priority industry in Ohio. State resources were
allocated primarily to the regulation of larger, more dominant
industries such as steel and the utilities.
There appears to be little or no state regulation of the disposal
of sludge from treatment facilities. Ohio's permit system
requires the optimum operation of treatment facilities, and this
requirement permits state officials to demand sludge removal if
the sludge build-up becomes a problem in the operation of these
plants. Basically, the state's regulation of sludge is handled
on a case by case basis. Ohio does have solid waste regulations
in force; however they do not address the disposal of sludge from
coal operations in particular. Revisions of these regulations
to include acid mine drainage sludge are expected in the future.
Ohio has an appeal system that permits the establishment of more
stringent effluent standards for certain pristine waters. Kov^ver,
action to establish new standards can only be instigated by citizen
G-32
-------
TO:
FRCM:
SUBJECT:
Division of Water Resources
1200 Greenbrier Street
Charleston, WV 25311
K. Randolph
August 6, 1977
475.15-96
State Regulations on Coal Mining: West Virginia
Talked with:
Mr. Paul Ware
Water Resources
(304) 348-3614
Date Called: August 4, 1977
10:10 a.m.
West Virginia has a state permit system for regulating coal mine drainage.
By and large, this boils down to EPA BPT guidelines. Each permit is handled
individually as far as effluent limitations are concerned, but in the majority
of cases, the limitations are HPT. There are some exceptions in what were
referred to as "sensitive waters". In those cases, the receiving water quality
controls the limitations imposed by West Virginia and these are always more
stringent than BPT.
West Virginia formulated some "new" water quality standards three years
ago, and these are being published this week. Mr. Ware will send us a
copy as soon as they are available.
Strip mines are regulated by the Reclamation Division under the Strip
Mine Reclamation Act. This act provides seme water quality standards that
are less stringent than BPT, CpH > 5.5, Fe - 10 ppm). However, Water
Resources Division passes on all NPDES permits and they must rule on
water quality from strip mines before the mine can get a mining permit.
Water Resources, once again, generally imposes BPT standards. Mr. Ware
will send us a copy of the Act when he sends the water quality standards.
As for regulation of sludge disposal, this corres under the mining
permit, and it is handled on a case by case basis. The mining conpany must
show in their application for a mining permit how any sludge will be disposed
of and the Reclarrati.cn Act has something to say on this too. West Virginia
does not have any formal regulation for sludge disposal. Lagocning, returning
to mine, drying and filling may all be acceptable depending on conditions.
I asked if their data on flew and quality of water from coal mines was
on a ccrrputer or was in a form where the amount of acid drainage in West
Virginia could be determined readily. The response was that their manage-
irent didn't seem to know that computers had been invented. One clerk
handles the data and she is two years behind. However, Mr. Ware cemented
that the AMD prcblen wz-s s-'^rlous only in the? Monor.gahela River valley
C-33
-------
- 2 -
Memo to 475.15 File
August 5, 1977
475.15-96
and drainage area. But he had no idea how much water was being treated
Mr. V&re was very cordial and quite helpful. He said that we were
welcome to call anytime.
-------
Versat
•
inc.
MEMORANDUM
August 3, 1977
10: 475.15 File j
FRCM: Linda Kay i$
SUBJECT: State Regulations Pertaining to Coal Mining
MARYIAND
larry Ramsey
Industrial and Hazardous Wastes, Water Resources ^ministration
Maryland Department of Natural Resources
The State of Maryland regulates drainage fron coal mines. In fact, the
Department of Natural Resources maintains a very active program. They have
established effluent guidelines, based on in-house studies of the state's
particular mining conditions, which are actually more stringent than EPA!s
BPT guidelines, ^feryland monitors turbidity (and therefore 1SS), iron, and
alkalinity. According to Larry Ramsey, Maryland mines have no problems
achieving these standards. Versar will be sent a copy of Maryland's permit
conditions.
Maryland has a very effective, centralized enforcement program. While
the Bureau of Mines approves mining permits for both deep and surface mines,
routine inspection is carried out by the Vfeter Resources Mministration.
This division is also responsible for the enforcement of the conditions
required by other permits necessary for coal mining (Soil Conservation Service
permits and water discharge permits). Violations of the conditions of one
permit result in the revocation of all permits required for mining. Tnis
centralized system is unique among the coal mining states and it appears, .to
encourage a fair and comprehensive regulation of the industry in this state.
Maryland, like other states, dees not specifically regulate the handling
of acid mine drainage sludge. Solid waste regulations are in effect, however,
and disposal of sludge from coal raining - should it occur - must concur with
these regulations.
C-35
-------
Versm
irxx
MARYLAND, Con't.
Tony Abar
Bureau of Mines
301-269-3382
Robert Creter
Water Resources Admin., Cumberland Office
301-777-2134
Maryland has a strip-mining reclamation act, in effect since July 1,
1976. Accompanying regulations have been established and are in the process
of revision. Tony Abar is sending Versar a copy of the act and current regu-
lations. Versar will also receive similar regulations pertaining to deep
mines.
Sludge disposal does not appear to be a problem in Maryland. The new
strip mine reclamation regulations provide for the burial of sludge in strip
pits. In most cases/ sludge is allowed to remain in the sedimentation ponds
and, after the mining operations cease, the liquid portion eventually
evaporates. This is especially the case in surface mining operations where
sludge build-up is rarely a problem since ns* ponds are continually being
constructed as mining proceeds. Officials expect difficulties with sludge
disposal to increase with the opening of more large deep mines within the
state.
According to Robert Creter-of the Water Resources Administration all
coal seams in Maryland are acid producing.
Maryland Effluent Standards for Coal Mines
pH 6.0 - 9.0
Alkalinity must exceed acidity
*Turbidity> 100 Jackson Campbell units
TSS 35 mg/1 (average) 45 mg/1 (maximum)
Total iron 4.0 mg/1 (maximum)
*Turbidity has been correlated with total suspended solids for ease of measure-
ment in the field.
C-36
-------
Kentucky
FILE MEMO
Name Gre9 Schweer
Date Nov. 12, 1980
Time 2:15 p.m.
File No. 569.1.1
Sub j ect
- Post Mine Drainage Control
- State of Kentucky
Persons Contacted:
Name Joey Roberts
Name
Kentucky Dept. of Natural Resources
Company & EnvironmentalJ&gptection Company
Div. of Standards and Specifications
Phone 502-564-2377 . Phoue
Comments:
Since 1978, water quality monitoring of discharge from active
mines has been required under the NPDES program. However, compliance
in reporting has not been good and data has not been compiled into
any readily accessible form.
The State of Kentucky has discouraged the practice of
underground mine sealing based on expected failure of seals.
Action Required
C-37
-------
Kentucky
FILE MEMO
Name
Time
Greg Schweer
Date 11/13/80
2:00 p.m.
File No.
569.1.1
Subject
Coal Mines - Post Mine Drainage Control
- State of Kentucky
Persons Contacted:
Name David Rosenbaum
Name
Kentucky Dept. of Natural Resources
Company and Environmental Protection Company
Division of Abandoned Lands
Phone 502-564-2141 . Phone
Comments:
Mr. Rosenbaum heads this newly formed Division of Abandoned
Lands. TMs division will be addressing acid mine drainage problems
and developing abatement plans. lb his knowledge, there has been
very little sealing of abandoned mines in Kentucky in toe past and
there is little if any monitoring data on mine drainage. His division
will be undertaking an inventory of abandoned mines in the state within
three weeks.
At present, 034 is constructing an emergency seal on a mine
in Knott county. The state is designing cover seals for three
Action Required mines in western Kentucky.
C-38
-------
Maryland
FILE MEMO
Name
Time 2:15
Greg Schweer
Date 11/13/80
File No.
569.1.1
Subject
Mines - Post : .Mints
"*
- State of Maryland
Persons Contacted:
Name Anthony Abar
Name
Maryland Dept. of Natural Resources
Company Rnwaan ^f M-ir^g Company
Phone
301-689-4136
Phone
Comments:
The only potentially relevant data Maryland has is:
1. Preliminary monitoring data for the Lost land Run daylighting project.
- data will be presented in a draft report soon by
Ackenaeil and Associates
Pittsburgh, PA
(Peter Campion 412-531-2470)
- pre-, during, and post-data are available. Post data, at
present, is being collected. Three months worth of data are
available and data will be collected for another 9 months.
Action Required
2. Maryland conducted a one-year monitoring study of acid
mine drainage in the early 1970s. Data was collected in the Castleman,
Cherry Creek, and Georges Creek watersheds. The data is quite extensive
and identifies individual mines and associated water quality. Some
of the identified mines had been sealed in the past.
The State of Maryland has not conducted any mine sealing programs;
considers treatment of AMD to be more feasible and reliable.
C-39
-------
Vfest Virginia
FIIZ MEMO
Name
Time
Greg Schweer
Date
11/12/80
Subject
3:15
File No.
569.1.1
Coal Mines - Post Mine Drainage Control
- State of Vfest Virginia
Persons Contacted:
Name
Paul Ware
Name
W.Va. Dept. of Natural Resources
Company Division of Vfeter Jtesouraes Company
Phone
304-348-3614
Phone
Comments:
No program is underway in W. Va. to seal abandoned mines.
ffowever, Mr. Ware stated that he is aware of several dozen mines
which have been sealed and for which pre-sealing water quality
data probably could be compiled and made accessible to EPA. Little
if any post-sealing water quality data is expected to be available.
Action Required
C-40
-------
Vfest Virginia
FILE MEMO
Name
Time
Greg Schweer
Date
11/12/80
3:30
File No.
569.1.1
Subject Coal Mines - Post Mine Drainage Control
State of Sfest Virginia
Persons Contacted:
Name Dave Kessler
Name
Company W.Va. Dept. of Mines
Uioqtrs.j
Phone 304-348-2061
Company
Phone
Comments;
Mr. Kessler can provide a computerized list of abandoned mines
for which mine maps are available. In regards to sealed mines and
sealing techniques, he suggested that the five regional divisions be
contacted:
Northern Division
Oak Hill Division
Vivian Division
Logan Division
Kanawha Division
Action Required
Grant King - 292-5642
Frank Legg - 469-2222
Ed Jarvis - 585-7013
Mr. Cook - 239-2326
Jim Gillespie - 442-2823
-------
-------
REFERENCE 2
HYDROTECHNIC TRIP REPORT
C-43
-------
-------
Trip Report - Pennsylvania Department of
Environmental Resources
Pennsylvania D. E. R.
Fulton Building
3rd and Locust Street
Harrisburg, PA
Prepared by: Victoria Lickers - Hydrotechnic Corp.
Date of Trip: October 9, 1980
Purpose of Trip: Obtain data on inactive coal mines and
post-mining discharges
Contacts: Kathy Seiber (717) 787-9646
Dix Hoffman (717) 787-8184
Ernest Giovannitti
Results:
Seven facilities, representing cases of successfully sealed
mines with no discharge problems, and sealed mines where post-mining
discharges have occurred, were selected for review by DER. These files
had been pulled:
1. Barnes & Tucker Co.
567M035 and 567M028 (same mine - two permits)
2. Margaret #7 Mine
366M006
3. Wildwood Mine
466M011
4. OVN Mine
367M034
5. Carrolltown No. 2 Mine
566M006
6. North Camp No. 1 Mine
266M032
C-45
-------
Barnes & Tucker, Margaret #7 Mine/ and Wildwood Mine have
all had problems with post-mining discharges. The remaining three
facilities fall into the "sealed, no discharge" category.
Data was Xeroxed and is now on file in Hydrotechnic' s office
for all facilities except the JVM Mine and the Barnes & Tucker facility.
The remaining data is to be copied by DER personnel and forwarded to
Hydrotechnic.
It was learned (from D. Hoffman) that the number of inactive
mines in Pennsylvania, for which the operators are responsible, probably
falls within the range of 300-500. Those facilities in the "sealed,
no discharge" category are inspected about tari.ce a year (after the first
5-year period) by DER personnel. Due to limited manpower, only the
portals are checked for discharge. There is no groundwater monitoring
or engineering analysis performed.
Mines with discharge problems would be monitoring more
closely, depending upon the circumstances.
Based upon his understanding of the information that EPA was
after, Hoffman did not seem to think that obtaining data for more than
the selected 7 facilities was necessary. He also stated that for
someone to piece together the background of a particular facility
from the files could be difficult and time-consuming.
C-46
-------
Since there was a great deal of data (much of it legal
correspondence) concerning the Barnes & Tucker facility, the need
to Xerox and/or use all of it was questioned. E. Giovannitti was
consulted as to the possibility of someone familiar with the
case preparing a short "history" of the problem, actions taken,
etc. He responded that it would be difficult, and that he didn't
know who would be qualified to do it. He suggested that if EPA
were to get in touch with him regarding a specific aspect of the
problem, he may be able to help.
Giovannitti also noted that he thought the EPA was
stressing the wrong aspect of the post-mining discharge problem.
He felt that more attention should be paid to those mines which
have been successfully sealed and to the sealing techniques employed,
rather than to treating the post-mining discharges that occur at
some of the inactive mines. As he pointed out, treating the discharge
from an active or an inactive mine is essentially the same.
C-47
-------
-------
REFERENCE 3
RESULTS OF 1980 LITERATURE SEARCH
C-49
-------
-------
US.
XOM«aCE
Ibtioesl Tccfeoetil hftatttiw Sento
PK272.373
LONG-TERM EWIPDNMENTAL EFFECTIVENESS
OF CTOSE DCfWN PROCEDURES
EASTERN UNDERGROUND COAL MINES
HRB-Singer, Inc., State College, Pa.
Prepared for
INDUSTRIAL ENVIRONMENTAL RESEARCH LAB - CINCINNA.TI, OHIO
Aug 77
C-51
-------
Report No.: EPA-600/7-77-083
Title and Subtitle: long-Term Environmental Effectiveness of
Close Down Procedures - Eastern Underground Coal Mines
Authors: M. F. Bucek and J. L. Emal
Performing Organization Name and Address:
HRB-Singer, Inc.
P. 0. Box 60
Science Park, State College, PA 16801
Sponsoring Agency Name and Address:
Industrial Environmental Research Lab. - Cin., OH
Office of Research and Development
U.S. Environmental Protection Agency
Cincinnati, Ohio 45268
Abstact:
The objective of the research project was to prepare an up-to-date
document on deep mine closures that have been or are planned to be
implemented in the eastern coal mining regions. The project was also
to provide an initial overview of the effectiveness of the closure
methods and the factors to which their effectiveness can be attributed.
The effectiveness was evaluated in terms of a closure effect on
mine drainage quality and quantity.
The trend analyses of the pollutant concentrations and outputs for
the pre- and post-closure periods show that the closures for more than
half of the sites reversed or reduced increasing pollutant trends, augmented
the already decreasing trends, and reduced variability in fluctuations of
the water quality. The effectiveness of the mine closures with respect
to the mine effluent quality by comparison with the preliminary mine
effluent guidelines was observed to be usually less than 50 percent
effective. The degree of closure effectiveness with respect to the
mine water quality improvement was found to be predominantly determined
by the physical and mining framework to the sites and less by the closure
technology.
C-52
-------
EPA-600/7-77-090
August 1977
ELKINS MINE DRAINAGE
POLLUTION CONTROL
DEMONSTRATION PROJECT
by
Resource Extraction and Handling Division
Industrial Environmental Research Laboratory
Cincinnati, Ohio 45268
Edited by
PEDCo Environmental, Inc.
Cincinnati, Ohio 45246
Contract No. 68-02-1321
Project Officer
Ronald D, Hill
INDUSTRIAL ENVIRONMENTAL RESEARCH LABORATORY
OFFICE OF RESEARCH AND DEVELOPMENT
U.S. ENVIRONMENTAL PROTECTION AGENCY
CINCINNATI, OHIO 45268
C-53
-------
ABSTRACT
Underground and surface coal mining operations have re-
sulted in degradation of the environment. Past mining opera-
tion* continue to pollute streams with acid, aedintent, and heavy
metal laden waters. Land disturbed during mining lies deluged,
and useless. In 1964 several Federal agencies in cooperation
with the State of West Virginia initiated a project to demon-
strate methods to control the pollution from abandoned under-
ground and surface mines in the Roaring Creek-Grassy Run water-
sheds near Elkins, West Virginia.
The Roaring Creek-Grassy Run watersheds contained 400
hectares of disturbed land, 1200 hectares of underground mine
workings and discharged over 11 metric tons per day of acidity
to the Tygart Valley River. The reclamation project was to
demonstrate the effectiveness of mine seals, water diversion
from underground workings, burial of acid-producing spoils and
refuse, surface mine reclamation, and surface mine revegetation.
Following a termination order in 1967, major efforts were
directed away from the completion of the mine sealings and
toward surface mining reclamation and revegetation. In July
1968 the reclamation work was completed with the reclamation and
revegetation of 284 hectares of disturbed land and the construc-
tion of 101 mine seals.
Results of an extensive monitoring program revealed that
some reduction in acidity load (as high as 20 percent during
1968 and 1969), and little if any in iron and sulfate loads and
flow have occurred in Grassy Run. Roaring Creek had an insig-
nificant change in flow as a result of water diversion, and a
decrease of 5 to 16 percent in acidity and sulfate load. Bio-
logical recovery in both streams has been nonexistent except in
some smaller subwatersheds. Good vegetative cover has been
established on almost all of the disturbed areas. Legumes
dominate in most areas after eight years. Tree survival and
growth has been good.
Average reclamation costs (at 1967 prices) were as follows:
surface mine reclamation - $4,ISO/hectare, seal construction -
$4,140/seal, and revegetation - $620/hectare.
-------
EPA-600/3-80-070
July 1980
ENVIRONMENTAL EFFECTS OF WESTERN COAL SURFACE MINING
PART VIII - FISH DISTRIBUTION IN TROUT CREEK, COLORADO, 1975-1976
by
John P. Goettl, Jr. and Jerry W. Edde
Colorado Division of Wildlife
Fisheries Research Center
Fort Collins, Colorado 80522
Grant No. R803950
Project Officer
Donald I. Mount
Environmental Research Laboratory-Duluth
Duluth, Minnesota 55804
ENVIRONMENTAL RESEARCH LABORATORY
OFFICE OF RESEARCH AND DEVELOPMENT
U.S. ENVIRONMENTAL PROTECTION AGENCY
DULUTH, MINNESOTA 55804
C-55
-------
ABSTRACT
A study was conducted on Trout Creek 1n northwestern Colorado during
1975-1976 to assess the effects of drainage from an adjacent surface coal
mine on the distribution of f1ah« In the cr*«k, and to r«1dtft th«1r dis-
tribution to physical and chemical variables. A second objective was to
determine the possible toxlclty of surface coal mine drainage water on fish
stocked In ponds receiving surface and groundwater run-off from the mine.
Results did not Indicate any direct effects of mine drainage water on
the distribution of fishes 1n Trout Creek, although possible effects may
have been masked by elevation, stream flow, streambed alterations, and agri-
cultural Irrigation return flows. Brook trout (Salvelinus fontinalie) was
the dominant salmonld species in the upper reaches of the creek; rainbow
trout (Salmo gaivdnevi) and brown trout (S. -toutta) were found only 1n the
region of the mine. Mottled sculpln (Cottue bairdi) and speckled dace
(Rhiniohthya oaoulua) were the most common fishes found throughout and at
all but the uppermost reaches, respectively.
Rainbow trout stocked 1n mine seepage water ponds for a year evi-
denced high survival rates over an eight-month period during the winter,
but fared poorly during the ensuing summer months, this latter most pro*
bably because of extremely high water temperatures. There was no apparent
evidence of toxlcity to the fish from contaminants 1n the mine pond water.
C-56
-------
U.S. DEPARTMENT OF COMMERCE
National Technical Information Service
PB-264 936
Water Pollution Caused by Inactive
Ore and Mineral Mines - A National
Assessment
Toups Corp, Santa Ana, Calif
Prepared for
Industrial Environmental Research Lab -Cincinnati, Ohio Resource Extraction
and Handling Div
Dec 76
C-57
-------
TECHNICAL REPORT DATA
(Ptem md Imuructtom on tht ttvtnt btfon compttttng)
1. REPORT NO.
EPA-600/2-76-298
2.
a. RlCIPlENrs ACCEUION NO.
4, TITLS AND SUaTITUI
HATER POLLUTION CAUSED BY INACTIVE ORE
AND MINERAL MINES - A National Assessment
s, REPORT
D« ci«b«r
_I976 iasuincrdat*-
*. PfRPORMINQ ORGANIZATION COOt
'. AUTHORIS)
Harry H. Martin
William R. Mills,
I. PERFORMING ORGANIZATION REPORT NO
Jr.
i. PERFORMING ORGANIZATION NAM* AND AODREM
Toups Corporation
1010 N. Main Street
Santa Ana, CA 92711
10. PROORAM ILIMlNTNO.
1BB040
nTCONTHACT/OKAN TWO.
68-03-2212
13. SPONSORING AGENCY NAMf AND AOO«i»
Industrial Environmental Research Laboratory - C1n., OH
Office of Research and Development
U.S. Environmental Protection Agency
Cincinnati, Ohio 45268
13. TVPI OP MFOflT AND PIMIOD COVtNIO
Final _^ ___
14. SPONSOHINO AOINCY CODI
EPA/600/12
19. SUPPLEMENTARY NOTES
ttie report Identifies the scope and magnitude of water pollution from Inactive
ore and mineral mines. Data collected from Federal, State, and local agencies
Indicates water pollution from adds, heavy metals, and sedimentation occurs at
over 100 locations and affects over 1200 kilometres of streams and rivers. The
metal mining Industry was shown to be the principal source of this pollution.
Descriptions of the mineral Industry are presented. Including a summary of economic
geology, production methods, and historic mineral production methods, and historic
mineral production. The mechanisms of formation,- transporation, and removals of
pollutants are detailed.
Annual pollutant loading rates for acid and metals from Inactive mines are given anc
a method provided to determine the extent of mine-related sedimentation 1n Western
watersheds. State-by-state summaries of mine related pollution are presented.
An assessment of current water pollution abatement procedures used for Inactive
mines 1s given and research and development programs for necessary Improve-
ments are recommended.
7.
KEY WOftOE AND DOCUMENT ANALYSIS
DESCRIPTORS
tUOENTIPICRE/OPEN ENDED TERMS
c, COSATI Field/Croup
Water Quality
Water Pollution
Metalliferous Minerals
Metalliferous Mineral Deposits
Mining Waste Disposal
Mine Surveys
Assessments
Ore and Klneral Mines
Metal Mining
Acid Mine Drainage
Heavy Metals
Pollution Control Tech.
R and 0 Programs
13/B
08/1
9, OlSTWieUTlON STATEMENT
RELEASE TO PUBLIC
19. SECURITY CLASS
UNCLASSIFIED
21. NO. Q.P PAGES
2O. SECURITY CLASS (TM3poge>
UNCLASSIFIED
32. PRICE
IPA form aalo-t (*•?])
C-58
fUSGPOi 197? — 717-0*6/9491 R^lon 5-11
-------
EPA-430/9-73-011
October 1973
PROCESSES, PROCEDURES, AND METHODS TO
CONTROL POLLUTION FROM
MINING ACTIVITIES
U. S* Environmental Protection Agency
Washington, D. C. 2O460
For Hi* by the Superintendent o( Document!, U.a. Qownunent Printing Office
WMbingtoD, D.C, 30402 - Price ».«
C-59
-------
-------
EPA-440/9-75-007
INACTIVE & ABANDONED
UNDERGROUND MINES
W*t*r Pollution Prevent/on & Control
U.S. ENVIRONMENTAL PROTECTION AGENCY
Washington, D.C. 20460
C-61
-------
ABSTRACT
Underground mining operations across the United States produce a number of
environmental problems. The foremost of these environmental concerns is acid
discharges from inactive and abandoned underground mines that deteriorate streams,
lakes and impoundments. Waters affected by mine drainage an altered both
chemically and physically.
This report discusses in Part I the chemistry and geographic extent of mine
drainage pollution in the United States from inactive and abandoned underground
mines; underground mining methods; and the classification of mine drainage control
techniques. Control technology was developed mainly in the coal fields of the
Eastern United States and may not be always applicable to other regions and other
mineral mining.
Available at-source mine drainage pollution prevention and control techniques
are described and evaluated in Part II of the report and consist of five major
categories; (1) Water Infiltration Control; (2) Mine Sealing; (3) Mining Techniques;
(4) Water Handling; and (S) Discharge Quality Control. This existing technology is
related to appropriate cost data and practical implementation by means of examples.
A summary of the mineral commodities mined in the United States follows
Part!! and relates to type, locale and environmental effects.
A list of minerals, mineral formulas, glossary and extensive bibliography are
included to add to the usefulness of this report.
C-62
-------
REFERENCE 4
FINAL SURVEY REVIEW TELEPHONE MEMO'S
C-63
-------
-------
RECORD OF CONVERSATION
7/7/82 3:30PM
TELGON MEMO
Contacted:
Ted Ifft at 343-7887
Organization: Federal Reclamation Program, O3M
Caller:
James S^atarella, EPA (WH-553)
Subject:
Coal Mining Reclamation
Discussion: TJie program actually started sealing and reclamation projects
in 5Y78. That year the projects were only to prevent
endangering lives at abandoned mines. The majority of our
projects started in BY80 and FY81 (Note - There have been up
to 10 projects at cne mine) with 131 shaft projects and 199
other projects cotpleted or under contract. There have been
no known failures at mines with conpleted sealing projects.
C-65
-------
RECORD OF CONVERSATION
7/7/82 3PM
TEUXJN MEMO
Contacted: Charles Crawford at 343-7921
Organization: Abandoned Mine Lands Program, CSM
Subject: Coal Mining Reclamation
Caller: James Spatarella, EPA (WH-553)
Discussion: The program is just moving into full swing with many states
waiting for our funding. One project in W. VA has been
recently completed (Feb. 82) with 1,100 projects anticipated
likely.
Another source of information might be the Federal
Reclamation Program, OSM.
C-66
-------
RECORD OF OONVERSKTIQN
7/16/82 2:30PM
TELOOW MEMO
Contacted:
Dix Hoffinan at (717) 787-8183
Organizations Pennsylvania Department of Environmental Resources
Caller:
James Spatarella, EPA (WH-553)
Subjects
Coal Mining Reclamation
Discussion: Tliis call was identified as a follow-up to the Hydrotechnic
trip of October 1980 which he remembered. He explained that
little new progress has been made in quantifing the extent of
the problem. Ihe data given to Hydrotechnic was the results
of the last attempt on defining the problem and was based on
permits from 1965-1975 that were found to be inactive in
1980. This method estimated z& 1,000 closed mines in the
state but no data on the number of closed mines causing water
quality problems.
C-67
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON, D.C. 20460
AUG25 1982
MEMORANDUM
SUBJECT: Investigation of Post-Mining Discharges After SMCRA Bond Release
45.
FROM:
TO:
THRU:
James J.-Spatarella, Environmental Engineer
Monitoring and Data Support Division (WH-553)
Bill Telliard, Chief
Energy and Mining Branch
Effluent Guidelines Division (WH-552)
Alec.McBrider Chief
Water Quality Branch
Monitoring and Data Support Division
The attached meno is forwarded for inclusion in reference (4) of the
subject issue paper. The memo documents our last attenpt to update the 1980
telephone survey, and again shows the lack of available data from state
agencies. The results of this survey are consistent with the issue paper.
cc: Rod Frederick (WH-553)
Allison Phillips (WH-552)
Joe Freedman (A-131)
Chip Lester (WH-586)
C-68
-------
Versar.
R A
M
TO:
FROM:
DATE:
SUBJECT:
Jim Spa tar el la
Justine Alchowiak^-
August 25, 1982
Type and Availability of Data Concerning the
Long-Term Effectiveness of Underground Coal Mine
Sealing Procedures
cc:
B. Maestri
M. Neely
569TM-232
A telephone survey was conducted between August 19 and 23, 1982 by
Versar personnel to determine the type and availability of monitoring data
and other relevant data that will enable MDSD to assess the long-term
effectiveness of underground coal mine sealing procedures. The scope of
this survey was limited to obtaining information from the state mining
and/or environmental officials in eight coal producing states
(Pennsylvania, Tennessee, Maryland, Alabama, Illinois, West Virginia,
Kentucky and Virginia). A similar survey was conducted by Versar in
October 1980. The results of the limited number of interviews conducted
indicate that since 1980 little additional data pertinent to this survey
are available. The available data are summarized below.
Pennsylvania - Approximately 40 to 50 mines have been sealed. These data
were previously available to EPA. Any available monitoring data are
available In the HRB-Singer Study (also mentioned in the October 1980
survey) and in the files maintained by the state's Dept. of Environmental
Resources, Abandoned Mine Area Restoration Division.
Maryland - One mine sealed recently (March 1980). Water quality monitoring
has been done in cooperation with the U.S. Bureau of Mines.
Alabama - Three mines have been sealed, however, they have not been sealed
In accordance with SMCRA regulations. Water quality monitoring data are
available for two mines which discharge into the Main Creek Watershed.
Fish kills have occurred in the area. There Is a court suit pending
against the mine owners.
Tennessee - No new data available.
Illinois - Approximately 40 to 50 mines have been sealed since 1977. These
mines have not been sealed in accordance with SMCRA regulation. No water
quality data available at this time. A water quality program Is expected
to start In 1983.
C-69
-------
Memo to Jim Spatarella
August 25, 1982
Page Two
West Virginia - Limited water quality data may be available.
Kentucky - Limited water quality data may be available.
Virginia - Limited water quality data may be available.
Attached to this memorandum are copies of the file memos for each telephone
interview conducted* Please contact me if you have any questions.
IUS 5183
C-70
-------
Pennsylvania
FILE MEMO
Name
Time
Pat Wood
Date 8/19/82
File No.
569.1.1
Subject
Coal Mines - Confirmation of 1980 info for Post Mine
Drainage Control - State of PA
Persons Contacted:
Name Dave Jfogeman
Name
Company Abandoned Mine Area Company
Restoration Div., Dept. of Environ. Res.
Phone 717-787-7668 _^ Phone
Comments:
8/19 will return call.
8/20/82 Preconstruction H20 quality data
Post construction monitoring data for seals and H~0 drainage
Approx. 40-50 mines have been sealed. HRB *- Singer
study covers mine techniques used. Any obtainable data
plus HRB Singer study are contained in the Star files and
should be requested through Bud Fredrick.
Action Required Abandoned Mine Area Restoration Div,
Dept. of Environmental Resources
C-71
-------
Pennsylvania
FILE MEMO
Name
Time
Pat Hood
Date 8/19/82
File No. 569.1.1
Subject Confirmation of 1980 info concerning Post Mine Drainage control
in Pennsylvania
Persons Contacted:
Name Evan Schuster
Name
Company Bureau of Water Quality M9m£ompany
Phone 717-787-8184 . Phone
Comments:
Mr. Schuster win be in- the office on Monday and will return call.
Mr. Schuster says situation in Pa. is the sane, ffowever, approx. 30
mines are sealed now since 1976. All H-O monitoring data and inspection
reports are in the files. The Bureau is now (very recent) working with 024
and frequent monitoring is expected to /follow in the next year. Is not
aware of any sealing, environmental or H^ quality problems. Due to lack
of funds, the Bureau has not kept a very good tracking record.
Action Required
C-72
-------
Maryland.
FILE MEMO
Name
Time
Pat Vtood
Date 8/19/82
File No. 569.1.1
Subject
sealing and Drainage Control. New info and confirmation
of 1980 info.
State of Maryland
Persons Contacted:
Name
Jeff McCombs
Name
Company Bureau of Mines in Maryland company
Phone 301-689-4136 Phone
Comments:
8/20/82 Mr. McConibs is. in the field.
Will return call later.
8/20/82 Bear Creek mine is the only recent mine sealed. Completed
March 1980. Monitoring has been done in cooperation with
the U.S. Bureau of Mines. All data has been handled by
(see below).
Action Required
U.S. Bureau of Mines
Lester Adams @ 412-675-4331
C-73
-------
Alabama
FILE MEMO
Name
Time
Pat Wx>d
Date 8/20/82
File No. 569.1.1
Subject Mine sealing techniques and its effectiveness? confirmation
of 1980 info.
State of Alabama
Persons Contacted;
Name
Bob Waller
Name
Company Alabama Land Reclamations company
Phone 205-832-6753 _ phone
Comments:
8/20/82 Will return call.
8/20/82 Filling with spoils/clay/dirt/ and sealed with concrete cap.
for safety due to growth of housing population in the immediate area.
Sealed
Action Required
-------
Region IV
FILE MEMO
Name
Time
Pat Wood
Date 8/20/82
File No. 569.1.1
Subject
Post Mine Drainage Control in EPA Region IV
Persons Contacted:
Name Mr. Bill Taylor
Name
Ken McDowell
Company
Phone
EPA - Atlanta
404-881-4727
Company Alabama H20 Improvement Commission
Phone 205-277-3630
Comments;
8/23 Referred to Ken McDowell
205-277-3630 Alabama
8/23 Underground - not known. Referred me to Alabama Underground Mine
Authority - 205-221-4130.
Mr. McDowell is currently involved in project concerning discharge
from two abandoned mines. One mine has low Ph and other high Ph
and contain aluminum. Interaction has caused an Al precipitation
Action Required
believed to be A10H, causing flocculation in the creek bed.
This, in turn, is causing fish kill. The mines claim the
same watershed. One empties directly into the main creek
and the other into a tributary of the main creek. Data has
been gathered for 1 1/2 years and is available to EPA. There
is to be a court suit against the mine owners Aug/Sept.
C-75
-------
Tennessee
FILE MEMO
Name
Time
Pat Wood
Date 8/19/82
File No.
569.1.1
Subject Mine Sealing - New info since 10/80 and confirming old info.
State of Tennessee
Persons Contacted:
Name Cliff Bole
Name
Company Tenn. State Vfater Quality Company
Control Board
Phone 615-741-6636 . Phone
Comments:
No new changes that he is aware of but referred me to:
1. 615-546-4783
Director - Arthur Ffape
Div. of Surface & Mines
Dept. of Conservation
2. MESA (Mining Enforcement Safety Assoc.}
Max Condra (615) 942-3389
Action ReguiredFrank Wbin <615> 424-9439
8/23 Frank Durbin - No longer with MESA
Max Condra will return call on Thursday 8/26/82,
C-76
-------
Illinois
FILE MEMO
Name
Time
Pat Wood
Date
8/19/82
Pile No.
569.1.1
Subject Post Mine Drainage Control - Confirmation of Oct. 1980 info,
State of Illinois
Persons Contacted:
Name
Sue JMagfiH ft.'
Company Mining Land Reclamation
Council
Phone 217-782-0588
Name ___
Company
Phone
Steve Jenkusky for Sue Massie
Comments:
8/19 Will return call.
8/23 Will return call.
8/23 Mr. Jenkusky informed me that the state of Illinois has sealed 40-50
mine openings since 1977 Act. The goal was to protect humans rather
than other reasons for sealing. Sealing techniques used are capping
and filling for shaft mines. However, capping has been found to be
ineffective someaAiat due to settling 0f the concrete which causes cracks
Action Required and holes. If surface area is on a drift, the opening is
filled and then covered with a concrete cap. For sloped
surfaces, filling has been found to be effective. To date,
there is one drift opening with drainage. Consequently,
a drain pipe was installed because drainage was not acidic.
Monitoring has not been done but will start next year. For
technical info, call Mr. Jenkusky. He is also interested in
any documents available in our files.
C-77
-------
Name
Time
Subject
West Virginia
FILE MEMO
Pat Wood
Date
8/20/82
File No. 569.1.1
Mine sealing and drainage control
State of West Virginia
Persons Contacted:
Name
Jessie Crater
Name
Phone
Company W.Va. Dept. Natural
Phone 304-636-1767
Comments:
Dry seal - plug up to maintain H-0
Wet seal - pipe to outside to drain H20
Regulated only in last two years.
Abandoned mines are monitored oocassionally by Abandoned Mine Division.
Drain to high quality stream is the only time monitoring is done by DNR,
Action Required
Dept. of Mines in Charleston, W.Va, may have more
info. 348-2051.
C-78
-------
Wast Virginia
FILE MEMO
Name
Time
Pat Wood
Date 8/20/82
File No.
569.1.1
Subject Mine Sealing & Drainage Control
State of W. Va.
Persons Contacted;
Name Mr. Jordan, Dept. of Mines
Company Charleston, W.Va.
Phone 304-348-2051
Name ___
Company
Phone
Comments :
Controls Sealing of Mines
Sealing Types:
1. Cinderblodc with pipe
2. Back seal - 20 ft. long pipe (backfilled) 15 ft.
Shaft mines = cap off or fill completely with dirt or spoil.
No failures to his knowledge.
Action Reuired
. more than 1000 openings sealed
(not mines) may be 12-15 openings/mine.
Reclamation Bond - reclamation on outside.
1. Tear down unused surface structure.
2. Seal mine openings.
All monitoring of ELO quality is done by DNR. Request data availability
from DNR.
C-79
-------
Name
Time
Subject
Kentucky
FILE MEMO
Pat Vtood
Date
8/20/82
File No.
569.1.1
Mine sealina techniaues
of 1980 info.
State of Kentucky
Persona Contacted;
Name Nancy Toombs
Company Kentucky, pept. of Mines
and Minerals
Phone 606-254-0367
Name
Mr. Turner
Company
Phone
437-9616
Comments•
8/20/82 Will return call
8/20/82 MSHA
Suggested I call local MSHA (233-2677 - 437-9616)
8/23 Mr. Clyde Turner
Use tvro techniques:
1. fill openings with seal (earth)
Action Required2' ooncrete stopper at the entrance
For shaft mines, soil filling techniques is normally used.
Slope - soil filling and the concrete slab for applying.
Kentucky is divided into three mining districts for MSHA work. Therefore,
Mr. Turner is not aware of # of mines sealed. Office of Surface Mines do H00
quality data and State H20 Control Board dses QC work. 2
C-80
-------
Virginia
FILE MEMO
Name
Time
Pat Wood
Date 8/20/82
File No.
569.1.1
Subject
Coal Mines - Post Drainage Control
State of Virginia
Persons Contacted:
Name Mr. Louis Wheatley
Name
Va. Dept. of Labor & Industry
Company Division of Mines & Quarries Company
Phone
703 - 523-0335
Phone
Comments:
Mr. Wheatley is not aware of any new changes in the state program.
He thinks that the Division of Mine, Land, Reclamation section monitors
ILC) from mine drainage. Controls mines with area greater than 2 acres.
Refer to 703-523-2925, Div, of Mine, Land, Reclamation.
Action Required
C-81
-------
EPA Region III
FILE MEMO
Name
Time
Pat Wood
Date 8/20/82
File No. 569.1.1
Subject Post Mine Drainage Control in EPA Region III
Persons Contacted:
Name Kathy HDdgekiss
Name
Company EPA Region III - Enforcement Company
Phone 215-597-9023 Phone
Comments;
8/20 - no answer
8/23 - no answer
8/23 - Kathy will return call. Will be on Travel thru Tuesday 8/24/82,
Action Required
C-82
-------
REFERENCE 5
FILE HISTORIES OF SIX CLOSED PENN. COAL MINES
C-83
-------
-------
Detailed files of the following mines are contained in the rulemaking record
for this regulation:
1. Barnes & Tucker Co..
567M035 and 567M028 (same mine - two permits)
2. Margaret 17 Mine
366M006
3. Wildwood Mine
466M011
4. JVN Mine
367M034
5. Carrolltown No. 2 Mine
566M006
6. North Camp No. 1 Mine
266M032
The record is available in EPA's Public Information Reference Unit, Room
2004, 401 M Street, S.W., Washington, D.C. 20460.
C-85
-------
-------
REFERENCE 6
1982 LITERATURE SEARCH REPORT
(PRINTOUT)
C-87
-------
-------
18/5/2
1257440 ID NO. E18205037440
SEALING AN UNDERGROUND DEEP MINE IN PENNSYLVANIA.
Beck, Laurance A.
Pa Mines Corp., Ebensburg, Pa. f
Segg Pgp - AM Min Congr Coal Conv, St. Louis, Mo, Mag 10-13 1981 Publ bg
Am Min Congr, Washington, DC, USA, 1981 17 p
This paper describes the methods used at the Oneida Mine by Pennsylvania
Mines Corporation to meet sealing regulations in Pennsylvania. 7 refs.
DESCRIPTORS: (*CQAL MINES AND MINING, *Pennsylvania),
CARD ALERT: 503
o
\
CD
18/5/55
827159
ID NO. - E1780427159
PREDICTION OF THE DRAINAGE CONTROL BY MINE SEALING $EM DASH$ 2. STUDIES
ON THE TECHNIQUE TO PREVENT THE MINING POLLUTION AT A CLOSED MINE.
Oks, Yukitoshi; Terada, Makoto; Kuroda, Kazuo; KomukaeitDri, Kazuo;
Nakano, Koji; Katasiri, Makio; Hakari, Nobuo
J Min Metall Inst Jpn v 93 n 1075 Sep 1977 p 603-608 CODEN: NIKKA9
AT the Horobetsu Sulphur Mine, a closed mine in Hokkaido, Japan, strongly
acid mine water continues to flow out from the underground at the rate of
4-7 cu m/min. The treatment of acid mine water has been carried out by the
lijne-neutralization method since the closing of the mine. Recently,
however, the lack of room for dumping the sludge produced in waste water
treatment has become an urgent problem. Therefore, the authors have
considered the sealing of the mine to reduce drainage. This article
describes the hydrological curves conducted for this purpose, and the
prediction of the effect of sealing on mine drainage. 4 refs. In Japanese
with English abstract.
DESCRIPTORS: (*MINES AND MINING, *Drainage), (SULFUR DEPOSITS, Japan),
(WATER TREATMENT, INDUSTRIAL, Japan),
IDENTIFIERS: SULFUR MINES AND MINING
CARD ALERT: 502, 505, 452, 445
-------
18/5/15
o
i
^o
o
133354 W79-03247
Inactive and Abandoned Underground Mines. Water Pollution Prevention and Control.
Scott, R. L.; Hays, R. M.
Baker (Michael), Jr., Inc., Beaver, PA.
Available from the National Technical Information Service, Springfield, VA 22161
as PB-258 263, Price Codes: A14 in paper copy, A01 in microfiche. Report No. EPA-440/9-75-007,
June 1975. 293 p, 54 fig, 14 tab, 132 ref. 68-01-2907.
Journal Announcement: SWRA1207
The chemistry and geographic extent of mine drainage pollution in the U.S. from inactive
and abandoned underground mines is discussed; underground mining methods are surveyed. Mine
drainage control technology, largely developed in eastern U.S. coal fields and not always
applicable to other regions and other mineral mining, are classified into two main categories:
(!) at-source and (2) treatment. At-source mine drainage pollution prevention and control
techniques are evaluated and described according to the following classifications: water
infiltration control; mine sealing; mining techniques; water handling; and discharge quality
control. Appropriate cost data is related, examples technique implementation are given. A
summary of the mineral cormodities mined in the U.S. includes location and the environmental
effects associated with mining them. An extensive bibliography is provided. (Davison-IPA).
Descriptors: *Water pollution control; *Mine drainage; Underground structures; *Acid
mine water; water quality control; Pollution abatement; Water pollution sources; Costs; Mineral
industry; Mine wastes; Mine water; Metals; Nonmetals; Coal; Thorium; Uranium.
Section Heading Codes: 50 (Water Quality Management and Protection - Water Quality Control);
50 (Water Quality Management and Protection - Waste Treatment Processes).
-------
-------
-------