PB96-964609
                                 EPA/ROD/R10-96/141
                                 August 1996
EPA  Superfund
       Record of Decision:
       Standard Steel and Metal Salvage Yard,
       (USDOT) Superfund Site,
       Anchorage, AK
       7/16//1996

-------

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION 10
1200 6TH AVENUE
SEATTLE, WASHINGTON
RECORD OF DECISION

DECLARATION,
DECISION SUMMARY,
AND
RESPONSIVENESS SUMMARY
FOR
FINAL REMEDIAL ACTION
STANDARD STEEL AND METALS SALVAGE YARD
SUPERFUND SITE
ANCHORAGE ALASKA

-------

-------
                              RECORD OF DECISION
                         STANDARD STEEL AND METALS
                        SALVAGE YARD SUPERFUND SITE
                              ANCHORAGE, ALASKA
DECLARATION
Site Name and Location
Standard Steel and Metals Salvage Yard
Anchorage Alaska

Statement of Basis and Purpose

       This decision document presents the selected remedial action for the Standard Steel
and Metals Salvage Yard, in Anchorage, Alaska, which was chosen in accordance with the
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as
amended by the Superfiind Amendments and Reauthorization Act (SARA), and, to the extent
practicable, the National Oil and Hazardous Substances Pollution Contingency Plan (NCP).
This decision is based on the administrative record for this site.

       The State of Alaska concurs with the selected remedy.

Assessment of the Site

       Actual or threatened releases of hazardous substances from this site, if not addressed
by implementing the response action selected in this Record of Decision (ROD), may present
an imminent and substantial  endangerment to public health, welfare, or the environment.

Description of the Selected Remedy

       This is the final remedial action for the site. The site was not divided into operable
units. EPA conducted a Removal Action to address the principle threats and most imminent
sources of continued releases of hazardous substances, and to stabilize the site prior to
conducting this remedial action. The Removal Action utilized treatment as a principle
element for the principle sources.

       The selected remedy entails the following major components:

             •     Removal of regulated material stockpiled on-site and investigation
                   derived wastes with subsequent disposal in a RCRA Subtitle C or D
                   landfill, or recycling of materials;
             •     Off-site disposal of remaining scrap debris by recycling or disposal in a
                   RCRA Subtitle D landfill or, if the debris is a characteristic hazardous
                   waste or contains greater than 50 mg/kg PCBs or lOug/lOOcm2 by
FROD.7/96

-------
                    standard wipe tests, treatment and disposal in a RCRA Subtitle C or
                    TSCA landfill;
              •      Excavation and consolidation of all soils exceeding cleanup levels;
              •      Treatment of all soils at or greater than 1000 mg/kg lead and 50 mg/kg
                    PCB by stabilization/solidification;
              •      On-site disposal of stabilized/solidified soils and excavated soils between
                    10 mg/kg and 50 mg/kg in a TSCA landfill;
              •      Excavation of soils impacted above 1 mg/kg PCB's and 500 mg/kg lead
                    from the flood plain and consolidation of these soils elsewhere on the
                    site;
              •      Maintenance and Repair of erosion control structure on bank of Ship
                    Creek;
              •      Maintenance of solidified/stabilized soils and the landfill;
              •      Institutional controls to limit land uses of the site and, if appropriate,
                    access;
              •      Monitoring of groundwater at the site to ensure the effectiveness of the
                    remedial action.

Statutory Determinations

       The selected remedy is protective of human health and the environment, complies with
or justifies a waiver of Federal and State requirements that are legally applicable or relevant
and appropriate to the remedial action, and is cost-effective.  This remedy utilizes permanent
solutions and alternative treatment technologies to the maximum extent practicable, and
satisfies the statutory preference for remedies that employ treatment that reduces toxicity,
mobility, or volume as a principal element.

       Because this remedy will result in hazardous substances remaining on-site above health
based levels, a review will be conducted within five years after commencement of remedial
action to ensure that the remedy continues to provide adequate protection of human health and
the environment.
Chuck Clarke             •                                                Date
Regional Administrator
U.S. Environmental Protection Agency
Region 10
FROD.7/96

-------
                           RECORD OF DECISION
               STANDARD STEEL AND METALS SALVAGE YARD
                            DECISION SUMMARY
                                    AND
                        RESPONSIVENESS SUMMARY
                           TABLE OF CONTENTS

SECTION   TITLE                                                    PAGE

1.0   SITE NAME, LOCATION, AND DESCRIPTION                          1
      1.1  Site Name                                                        1
            1.1.1  Site Location and Description                                 1
      1.2  Topography                                                      1
      1.3  Zoning                       .  •     •                             2
      1.4  Natural Resource Uses                                             2
            1.4.1  Terrestrial Resources                                       2
            1.4.2  Aquatic Resources                                         '2
            1.4.3  Endangered Species/Wetlands                                3
      1.5  Location and Distance to Nearby Human Populations                    3
      1.6  General Surface-water, Groundwater Resources and Geology              3
            1.6.1  Ship Creek Stage                                           3
            1.6.2  Surface Water Runoff                                       3
            1.6.3  Geology                                                  4
            1.6.4  Regional Groundwater Conditions                             4
            1.6.5  Unconfined Aquifer                                         5
            1.6.6  Bootlegger Cove Formation Aquitard                           5
            1.6.7  Confined Aquifer                                           5
            1.6.8  Groundwater Occurrence                                    6
            1.6.9  Groundwater Supply                            .             6

2.0   SITE HISTORY AND ENFORCEMENT ACTIONS                        6
      2.1  Scope and Role of Removal Action                                   8

3.0   HIGHLIGHTS OF COMMUNITY PARTICIPATION                       9
      3.1  Summary of Community Relations Activities:                          10

4.0   SUMMARY OF SITE CHARACTERISTICS                             11
      4.1  Nature and  Extent of Contamination          •                       11
      4.2  Media of Concern                                                11
           4.2.1  Surface and Subsurface Soil                                 11
                 4.2.1.1  Lead                                             11
                 4.2.1.2  Other Inorganics                                   12
                 4.2.1.3  PCBs                                             12

-------
                   4.2.1.4 Dioxins and Furans                                   13
                   4.2.1.5 Volatiles and Semivolatiles                            13
                   4.2.1.6 Presence of Light Non-Aqueous Phase Liquid (LNAPL)   13
                         4.2.1.6.1  Concentration of PCBs in LNAPL              14
                         4.2.1.6.2  Concentration of Lead in LNAPL              14
                         4.2.1.6.3  Concentration of Other Contaminants in LNAPL 14
                   4.2.1.7 Shotcrete Covered Soils                               14
      4.3 Groundwater                                                       15
            4.3.1  Lead                                                       15
            4.3.2  PCBs                                                       15
            4.3.3  Volatile Organic Compounds                                  15
            4.3.4  Semivolatile Organic Compounds                              16
            4.3.5  Other Metals                                                16
      4.4 Surface  Water                                                      17
      4.5 Sediment                                                          17
      4.6 Air                                                                18
      4.7 Summary                                                          18

5.0 '  SUMMARY OF SITE RISKS                                            18
      5.1 Human  Health Risks                                                 19
            5.1.1  Contaminants of Potential Concern                             19
            5.1.2  Risks Related to Compounds Other Than Lead                  19
                   5.1.2.1 Toxicity Assessment                                   20
                   5.1.2.2 Exposure Assessment                                 20
                   5.1.2.3 Risk Characterization                                 21
                   5.1.2.4 SoilCOCs                                          22
      5.2 Combined Short- and Long-Term Workers Exposure Pathways            22
            5.2.1  Short-Term Worker           "                               22
            5.2.2  Long-Term Worker                   .                       23
      5.3 Combined Residential Exposure Pathways                              23
      5.4 Risks Related to Lead Only                                          23
      5.5 Ecological Risk Assessment                                           25
      5.6 Uncertainty in the Risk Assessment                                    25
      5.7 Conclusion                                                         26

6.0   REMEDIAL ACTION OBJECTIVES AND CLEANUP  STANDARDS        26
      6.1 Remedial Action Objectives                                          27
      6.2 Cleanup Standards                                                   27
            6.2.1  Soil Cleanup Standards                      "                 27
                   6.2.1.1 PCB Cleanup Standards                               28
                   6.2.1.2 Lead Cleanup Standards                              28
      6.3 Cleanup Standards Conclusions                                       29

7.0   DESCRIPTION OF ALTERNATIVES                                    30
      7.1 Individual Analysis of Alternatives                                     32
            7.1.1  Alternative 1 - No Action/Monitoring                          32

                                      ii

-------
                   7.1.1.1 Cost
             7.1.2 Alternative 2 - Limited Action                                  32
                   7.1.2.1 Cost                                                  33
             7.1.3 Alternative 3 - Capping                                        34
                   7.1.3.1 Cost                                                  35
             7.1.4 Alternative 4 - Containment with Treatment of Principal Threat
                   Soils by Stabilization/Solidification                             35
                   7.1.4.1 Cost                                                  37
             7.1.5 Alternative & Stabilization/Solidification with Treatment of PCB
                   Principal Threat Soils by Thermal Desorption                   37
                   7.1.5.1 Cost                                                  38
             7.1.6 Alternative 6 - Stabilization/Solidification                        38
                   7.1.6.1 Cost                                                  40
             7.1.7 Alternative 7 - Soil Washing                                    41
                   7.1.7.1 Cost                                                  42
             7.1.8 Alternative 8 - Thermal Desorption                             43
                   7.1.8.1 Cost                                                  44
             7.1.9 Alternative 9 - Off-site Disposal                                 45
                   7.1.9.1 Cost                                                  46
             7.1.10 Alternative 10 - Off-site Incineration                           4t>
                   7.1.10.1  Cost                                                 47
      7.2 Groundwater Component                                              47
      7.3 Applicable or Relevant and Appropriate Requirements                   48
             7.3.1 Chemical-Specific ARARs                                      48
             7.3.2  Action-Specific ARARs                                        48

8.0   COMPARATIVE ANALYSIS                                              49
      8.1 Overall Protection of Human Health and the Environment                50
      8.2 Compliance with ARARs                                               50
             8.2.1 Assessment                                                    50
      8.3 Long-Term Effectiveness and Permanence                                51
             8.3.1 Magnitude of Residual Risk                                    51
             8.3.2 Adequacy and Reliability of Controls                            52
             8.3.3 Assessment                                                    52
      8.4 Reduction  of Toxicity, Mobility, or Volume Through Treatment            53
             8.4.1 Discussion                                                    53
             8.4.2 Assessment
      8.5 Short-Term Effectiveness                              .                 55
             8.5.1 Short-Term Protection of the Community, Workers, and the
                  Environment                                                   55
             8.5.2 Time Unit Remedial Response Objectives are Achieved           56
             8.5.3 Assessment                                                    56
      8.6 Implementability                                                       57
             8.6.1 Technical Feasibility                                           57
             8.6.2 Administrative Feasibility                                       58
             8.6.3 Availability of Services and  Materials                            58

                                       iii

-------
 9.0
      8.6.4  Assessment
8.7 Cost
8.8 State Acceptance
8.9 Community Acceptance

THE SELECTED REMEDY
9.1 Remedy Description
 10.0  STATUTORY DETERMINATIONS
      10.1 Protective of Human Health and the Environment
      10.2 Applicable or Relevant and Appropriate Requirements
           Cost Effectiveness
 10.3
 10.4

 10.5
                                                                            58
                                                                            59
                                                                            59
                                                                            59
60

70
70
71
72
           Utilization of Permanent Solutions and Alternative Treatment Technologies
           to the Maximum Extent Practicable                                  72
           Preference for Treatment as a Principle Element                       73
 11.0  DOCUMENTATION OF SIGNIFICANT CHANGES
                                                                      73
         FIGURES AND TABLES (Attached at the End of Record of Decision)

Figure 1-1   Site Location Map
Figure 1-2   Flood Plain and Wetlands Map
Figure 1-3   Locations of Historical Operation and Storage Areas
Figure 1-4   Current Site Status (Post-Scrap Removal)
Table 5-1   Summary of Media and Chemicals of Concern
Figure 5-1   Concentration of PCBs in Surface Soil
Figure 5-2   Concentration of PCBs in Soil within the Water Table Zone
Figure 5-3   Concentration of Lead in Surface Soil
Figure 5-4   Monitoring Well and Ship Creek Sediment Sampling Locations
Table 6-1   Residential Risk Blend Based Concentrations, Background Concentrations,
            and Maximum Concentrations of PCOCs in Soils and Groundwater
Table 6-2   Parameters Used to Calculate Risk-Based Screening Concentrations
Table 6-3   Summaries of RME Hazard Indices
Table 6-4   Summaries of RME Excess Cancer Risks
Table 6-5   Summary of  Estimated Excess Cancer Risks Associated with lOmg/kg PCB
            Cleanup Level
Figure 6-1   Areas of Concern
Figure 8-1   Areas to be Remediated - Alternative 4
Figure 8-2   Areas to be Remediated - Alternative 5
Figure 8-3   Areas to be Remediated - Alternatives 6, 7, 8, 9, and 10
Table 9-1    Soil Cleanup Level Summary
                        RESPONSIVENESS SUMMARY
                                     iiii

-------
                             RECORD OF DECISION

                 STANDARD STEEL AND METALS SALVAGE YARD



 1.0    SITE NAME, LOCATION, AND DESCRIPTION

 1.1    Site Name

 Standard Steel and Metals Salvage Yard

 1.1.1  Site Location and Description

 Standard Steel and Metals Salvage Yard (site) is located on a 6.2 acre parcel of land in
 Anchorage, Alaska, near the intersection of Railroad Avenue and Yakutat Street  The
 site is owned by the Federal Railroad Administration and in the possession and control
 of the Alaska Railroad Corporation.  The site is situated in an industrialized area of
 Anchorage along the north side of lower Ship Creek (Figure 1-1). A warehouse is
 located directly north of the site.  To the east are assorted light industries, warehouses
 and a produce packing facility, and to the west is a steel fabrication operation.
 Approximately 500 feet upstream of the site is the Elmendorf Fish Hatchery and the
 Eagle Glen Golf Course on Elmendorf Air Force Base. Non-adjacent land use is
 comprised of assorted light industry and the Alaska Railroad Corporation's rail yard.

 The site has been cleared of most scrap metal and debris during previous CERCLA
 activities (see Section 2.0).  There is a small stand of cottonwoods and small brush
 adjacent to Ship Creek, otherwise the site is covered with gravel/fill.  The site was
 contaminated during 30 years of salvage operations, primarily by releases from lead acid
 batteries and PCB contaminated transformers. The site consists of all areas
 contaminated by PCBs and lead which resulted from activities at the Standard Steel and
•Metals Salvage Yard. These areas are defined in the remedial investigation and
 generally conform to the property boundaries.

 12    Topography

 The site is situated on a gently sloping outwash plain. The ground surface elevation
 ranges from approximately 70 to 80 feet above mean sea level. The site is built upon the
 reclaimed flood plain of Ship Creek.  Ship Creek defines the southern border of the site.
 The site extends into Ship Creek's 100 year flood plain on the south-western comer of
 the site.  A preservation wetland is also located in the south-western corner of the site
 (Figure 1-2). Review of historical aerial photographs showed that significant areas of the
 site have been excavated and subsequently filled to raise the surface elevation of the site
 to its current height of between 70 and 80 feet above sea level.

 FROD.7/96                                  1

-------
 1.3    Zoning

 The areas from Reeve Boulevard to Knik Arm surrounding Ship Creek and enclosing the
 site are zoned 1-2, denoting a heavy industrial district.  The areas south of this district
 (beginning 1/4 mile from the site) are zoned as business districts, light industrial districts,
 and public lands and institution districts.  The area to the north (1/3 mile .from the site)
 is reserved for the military.

 The Municipality of Anchorage has adopted a land use plan that reflects and continues
 the current zoning of this area. The site, as well as all lands west of Reeve Avenue,
 south of Post Road, east of Wrangell Street and north of Ship Creek, is currently
 managed and controlled by the Alaska Railroad Corporation (ARRC) pursuant to an
 exclusive license issued by the United States under the authority of an act of Congress,
 the Alaska Railroad Transfer Act of 1983.  ARRC assumed control of these properties
 from the United States government on January 5, 1985.  The underlying property owner
 of the  site is the United States, pending eventual transfer to ARRC as  contemplated  by
 that Act. The ARRC is a public corporation owned by the State of Alaska. ARRC has
 publicly taken the position that the zoning of the site and surrounding areas should
 remain industrial.  An  active rail line is located along Post Road, with a spur that
 connects the site to the main line.

 1.4    Natural Resource Uses

 1.4.1   Terrestrial Resources

 The site  has limited terrestrial natural resources. It was used during the  1950's as a
 gravel  mine.  There is very limited vegetation and habitat on the site. Small rodents,
 passerines and gulls have been observed on the site. Moose have been seen adjacent to
 the site along Ship Creek.

 1.4.2   Aquatic Resources

 The quantity and variety of fish in Ship Creek is dependent upon stocking, harvesting
 and environmental factors. Status  of the stock is measured  by fish harvest reports by the
 Alaska Department of  Fish &  Game. The only data collected on native fish of Ship
 Creek  are from the annual harvest reports and visual fish counts, which concentrate on
 the chinook and coho species.  In relation to the total numbers of chinook and coho in
 Ship Creek in any given year, it is important to note the regulated nature of fish
 stocking. Many variables influence the decision regarding the number of chinook and
 coho smelt to stock info Ship Creek each year; this, in turn, affects the  total number of
 returning adults.  Approximately 5 percent of chinook smelt and approximately 5-15.
percent of coho smelt return to Ship Creek as adults. It is  estimated that roughly twenty
percent of both returning coho and chinook are of native stock. Small  numbers of pink
 and chum salmon may  also use Ship Creek.


FROD.7/96                                 2

-------
 1.43  Endangered Species/Wetlands

 No threatened or endangered species have been observed at the site.  The site has been
 heavily disturbed throughout it's history and provides little preferred or suitable habitat.
 A small wetland is located on the south-west boundary of the site.  This area has not
 been contaminated by site activities. Threatened or endangered species which may be in
 the vicinity of the site are highly unlikely to utilize the site for feeding, resting, or
 propagating.

 1.5    Location and Distance to Nearby Human Populations

 The area around the site is dedicated to industrial/commercial use. The nearest
 residential area is located 1/2 mile  south-east of the site on the other side of Ship Creek
 in the Mountainview area. Military housing at Elmendorf Air Force Base is located 1/3
 mile north-east of the site. Population figures for the area in the immediate vicinity are
 not available. However, 1990 Anchorage Census Tracts 5 and 6, which cover the site
 and a large  surrounding area including Mountainview residential area, contained 7,188
 people. An unknown number of homeless  adults are reported to live along Ship Creek
 and the Bluff north of the site during summer months.

 1.6    General Surface-water, Groundwater Resources and Geology

 1.6.1  Ship  Creek Stage

 The lower Ship Creek drainage basin covers roughly 27 square miles.  The creek
 traverses approximately 10 miles from the Chugach Mountains to Cook Inlet. The  site is
 located along the north bank of Ship Creek, approximately 2 miles upstream from the
 mouth. Ship Creek flows south and west adjacent to the site.

 The U.S. Army Corp  of Engineers (Alaska District) personnel made numerous cross
 section measurements (August 1976) in order to project possible flood magnitude in the
 area. Floodway boundaries were computed for  each cross section with the HEC-2
 computer program.  The projected 100-year flood plain area is depicted on Figure 1-2.

 1.6.2   Surface Water Runoff

A site map based on the topographic site survey is presented as Figure 1-2.  The site is
relatively flat, sloping slightly to the south with an average slope of less than 3 percent.
 Surface water drainage from the site appears to be variable, with the majority of
precipitation infiltrating the soil rather than forming discrete runoff patterns. Only a
single potential drainage channel leading from the site has been observed to date, but
surface water has never been observed in the channel, and it is blocked by an earthen
berm before it reaches Ship Creek.  It is located outside of and approximately parallel to
the fence along the south of the site.  The slope in this channel appears to trend

FROD.7/96                                  3

-------
southwesterly and eventually joins the fairly pronounced gully southwest of the site which
is visible on the site map (Figure 1-2).  This gully heads toward Ship Creek downstream
of the site.

Although the snow  melted within a relatively short period of time during the spring of
1993, no surface runoff from the site to the creek or to surrounding properties was
observed, except for a small amount flowing for several days southwest into the adjacent
property.  This surface runoff infiltrated into the soil soon after entering that property;
no runoff to  the creek was observed.

Available municipal and railroad records do not indicate existence of storm sewers that
drain surface runoff from the site.  Field teams did not find any storm sewer grates at
the site or other water conduits down gradient of the site, except for a culvert near
Yakutat Street, which drains a storm sewer on the northeast corner of Yakutat and
Railroad Avenues.

1.6.3   Geology

The site is located in the Anchorage lowland area within the upper Cook Inlet region of
Alaska. The lowland  areas of the Cook Inlet region are surrounded by several heavily -
glaciated mountain  ranges, including the Alaska, Talkeetna, Chugach, and Kenai Ranges.
Unconsolidated glacial deposits, which  are typical of the lowland areas surrounding Cook
Inlet, have been deposited and reworked by three main agents: glacial ice; flowing water
in streams or deltas; and still water in ponds, lakes and marine estuaries.

Several glacial events  in the Cook Inlet area resulted in deposition of thick sequences of
unconsolidated fine-grained  glacial sediments in glacially-dammed lakes. The outwash
from these glaciers  has deposited rock flour and silt in the lowlands, producing large
areas of mud flats along the Cook Inlet shoreline.  These silt-rich deposits
discontinuously overlay glacial and glacial fluvial materials.  The lowland deposits are
bordered by uplands or glacial moraine and drift deposits.  The site is located in an
active seismic area.

1.6.4   Regional Groundwater Conditions

The area commonly referred to as the Anchorage Bowl encompasses approximately 180
square miles  and includes the site and most of the urban area of Anchorage. This area
is bounded on the north, west and south by two estuaries, the Knik and Turnagain Arms
of Cook Inlet, and on the east by the Chugach foothills.  Two aquifers have been
identified in this area  separated by a thick aquitard (the Bootlegger Cove Formation).
These aquifers are distinguished by their  relatively coarse lithologies and capacity to
transmit groundwater horizontally.  An unconfined aquifer is located in the deposits
above the Bootlegger Cove Formation and  a confined aquifer is located in the deposits
FROD.7/96

-------
below the Bootlegger Cove Formation.  The existence of potential water-bearing units
beneath the confined aquifer at the site was not investigated.

The Bootlegger Cove Formation has been identified as an effective aquitard based on its
relatively fine-grained lithology, thickness, and continuous areal extent over the study
area.  This aquitard is an important feature of the hydrogeologic model, because it
impedes vertical groundwater flow and chemical transport.  The three units are described
below.

1.6.5  Unconfined Aquifer

An unconfined aquifer is located in a sheet of outwash plain deposits (chiefly sand and
gravel) that covers much of the northeast, central and western parts of the Anchorage
area.  This aquifer generally extends from the flanks of the Chugach foothills on the east
to Cook Inlet, including the Turnagain and Knik Arms, on the north, west and south.
This aquifer consists of sand and gravel lenses intermixed with silty sand and gravel.  In
the vicinity of the site the aquifer is approximately 25 feet thick. This aquifer is naturally
recharged by rain, snowmelt and leakage from streams.  Groundwater flows to the south
west with some water discharging to Ship Creek and the remainder to Cook Inlet.

1.6.6  Bootlegger Cove Formation Aquitard

The Pleistocene Bootlegger Cove Formation is a low permeability clay unit that
underlies most of the Anchorage area. This unit is up to 270 feet thick and generally
thickens with increasing distance from the mountains.  In the vicinity of the site, the
aquitard is 100 to 150 feet thick.

The aquitard consists of saturated, clayey glacially-derived sediments of very low
permeability. Permeability tests were performed on five samples collected from the
Bootlegger Cove Formation at the site and resulted in hydraulic conductivity values
ranging from 0.0006 to 0.002 ft/day (2.1 x 10'7 to 7.0 x 10'7 cm/sec).  These estimated
hydraulic conductivity values are consistent with the regional value (0.0001 ft/day).

1.6.7   Confined Aquifer

The confined aquifer  is composed of several layers of interbedded sand and gravel, till,
and silty clay deposits. The more permeable sand and gravel layers are hydraulically
connected and are considered to be a single aquifer. The aquifer is continuous below
the entire Anchorage  Bowl.  The thickness generally increases from approximately 100
feet in the Chugach foothills to 1100 feet at a point between the Knik and Turnagain
Arms.  In the vicinity of the site, the  aquifer is approximately 600 feet thick and is
located approximately 100 to  300 feet below the ground surface.
FROD.7/96

-------
 1.6.8  Groundwater Occurrence

 The depth to the top of the unconfined aquifer ranges from about 3 to 10 feet below the
 ground surface and the average saturated thickness is approximately 15 feet. The surface
 of the water table slopes southwest at the site and varies in elevation between
 approximately 65 and 74 feet above mean sea level. The water elevations measured
 during the RI field investigation were used to create water table contour maps. The two
 sets of contours are similarly shaped and show a difference in water table of 1 to 2 feet.
 The horizontal hydraulic gradient ranged from approximately 0.007 to 0.01 ft/ft.

 1.6.9  Groundwater Supply

 A survey of the water supply wells within 1/2 mile radius of the site revealed 9 potable
 water wells and 4 non-potable water wells.  All of these wells draw from the lower
 confined aquifer with the potable wells ranging in depth from 76 feet below ground
 surface (bgs) to 850 feet bgs, and the non-potable wells ranging in depth from 152 feet
 bgs to 257 feet bgs.  Only three of these wells,  the Inlet Co. well, the Steel Fab well, and
 the Alaska Concrete Products well are located  down gradient from the site.  No
 groundwater wells completed in the unconfined aquifer were identified within a half-mile
 radius of the site.                                                                 ~

 2.0    SITE HISTORY AND ENFORCEMENT ACTIONS

 The first documented use of the site occurred in  October of 1950, when much of the site
 was leased by a construction company for maintenance and storage of heavy equipment
 and supplies.  This operation continued on parts  of the site until 1960.

 Aerial photographs of the Ship Creek area are available for most years since 1939.
 Photographs prior to 1939 show little salvage material and debris and no buildings
 onsite.  Aerial photographs show that considerable excavation occurred in the southern
 half of the site between 1950 and 1953.  A haul road is visible up the bluff to the north
 leading to Elmendorf Air Force Base, and it is likely that gravel from the site was mined
 for use in base construction.  Aerial photographs also show that these excavations had
 been backfilled by 1972 to establish the present site grade. Soil borings and test pits
 indicate that the fill material consisted mostly of sandy and silty soil.  No material was
 encountered during subsurface investigations which indicates dumping of hazardous
waste materials during  fill operations.

 Metal recycling and salvage  businesses operated on the site beginning in  1955 and until
 1993. From 1955 to 1986, metal recycling and  salvaging occurred on the entire area
within the present fence lines. Following EPA's initial response action in 1986, the scrap
business was restricted  to the small parcel northeast of the fenced area south of Railroad
Avenue and west of Yakutat Street.  During the period from 1955 to  1986, hundreds of
thousands of tons of ferrous and nonferrous materials were handled at the site. At some
FROD.7/96

-------
time after 1955 batteries were handled at the site to recover their lead and transformers
were handled primarily to recover the copper in the core windings.

Transformer oil was drained by site operators.  The oil was released onto the ground, or
used as hydraulic fluid in onsite equipment. There is no information (such as manifests)
which indicate that transformer oils were shipped off-site for proper disposal or
treatment.  Copper transformer cores were removed from the cases and placed in an
onsite incinerator to remove shellac and paper  insulation.  The copper cores were then
shipped offsite for salvage. Batteries were stockpiled onsite and may have been
processed onsite prior to sale for their lead content. Processing of batteries may have
included draining fluid from cases and breaking the cases to remove the lead plates.
Drums containing wastes and chemicals were also stored onsite  as part of the salvaging
operations.

Aerial photographs from the 1960s through 1986 reveal salvage  materials onsite.  By
1975, the incinerator building, sales office trailer, and warehouse on the north end of the
site had been constructed. The volume of salvage  material and the number of buildings
adjacent to the site continued to increase until  1985.

Although activities known  to have resulted in hazardous substance releases were
discontinued in April 1986, when an EPA Order was issued pursuant to 42 U.S.C.
§ 9606, site operations continued on the  northeast  corner of the site until April 1993.
The site  owners and site operator were requested to perform a removal action but
declined to or were unable to conduct the work. The 1986 Order led to an EPA
removal action and resulted in a portion of the site being fenced off and closed to public
access. The removal action is described  in more detail in Section 2.1 below.  Figure 1-3
shows the location of former operations on the  site and scrap-covered  areas in existence
when the removal action was  begun by the EPA in 1986.

The site was proposed for  listing on the National Priorities List  (NPL) on July 14, 1989.
The site was listed on the  NPL on August 30, 1990. 55 Fed. Reg. 35502.

On December 6, 1991, the United States filed a lawsuit under Section 107  of CERCLA,
42 U.S.C. § 9607, against eight parties for recovery of EPAfs costs incurred in
performing the removal action and a determination of liability for future costs. The
eight parties sued were the Alaska  Railroad Corporation, Ben Lomand Inc., Chugach
Electric Association, Inc., Westinghouse Electric Corporation, Sears, Roebuck and Co.,
Montgomery Ward and Co., Inc., J.C. Penny Company, Inc., and Bridgestone/Firestone,
Inc. Certain other Federal entities arc considered to be within the class of persons who
may be liable under CERCLA.  Those entities  are the Federal Railroad Administration,
Department of Transportation, Defense Reutilization and Marketing Service,
Department of Defense, and the Army/Air Force Exchange Service.
FROD.7/96

-------
On September 23, 1992, Chugach Electric Association entered into an Administrative
Order on Consent to conduct a remedial investigation/feasibility study at the site.  The
RI commenced in October 1992 and ended in August 1994.  The feasibility study was
completed in January 1996.  During the remedial investigation and feasibility study,
treatability tests were performed for solidification and soil washing and a pilot scale soil
washing unit was tested on-site. Supplemental soil sampling occurred during preparation
of the feasibility study. During the EPA removal action, the RI/FS field work, and
scrap/debris removal, wastes were containerized and placed within the fenced portion of
the site.  The current location of existing fence and the various containers and wastes are
shown in Figure 1-4.

EPA issued a Unilateral Administrative Order on September 7, 1993 to the Alaska
Railroad Corporation to remove  armored personnel carriers sitting on a portion of the
site to allow access to the site for completing the remedial investigation and feasibility
study.

2.1    Scope and  Role of Removal Action

During the period 1986 to  1988, the EPA Region X Superfund Removal and
Investigations Section performed a removal action at the site under authority provided in
Section 104  of CERCLA, 42 U.S.C. § 9604. The scope of the removal effort was
directed towards removing the ongoing sources of releases or substantial threat of
releases of hazardous substances  from transformers, lead acid batteries and barrels and
drums stored on the site.  Additionally, soil and groundwater samples were collected. A
rip-rap berm was constructed along the bank of Ship Creek on the southeast corner of
the site to prevent erosion.  Several areas of contaminated soils were excavated and
placed in a mound on-site  and sprayed with shotcrete (Figure 1-4).  A more complete
description of the removal  action can be found in the On Scene Coordinators Report for
the site.

The removal actions removed and treated the  principle threats present at the site.  These
principle  threats included more than one thousand gallons of PCB contaminated oils,
eighty-two 55 gallon drums of RCRA hazardous  waste, 10,450 gallons of waste oils, 185
PCB contaminated transformers and 781,000 pounds  of lead acid batteries. The PCB
oils were incinerated and the waste oil was recovered and the batteries were recycled.

Major Chronological Events of the Removal Action  are as follows:

August 1985       Soil Samples collected by  the Alaska Department of Environmental
                   conservation (ADEC)  identified  PCB contamination in on-site
                   surface soils  as high as 110,000:

October  1985      EPA conducted a two  week assessment documenting wide spread
                   PCB and heavy metal  contamination in soils, the  presence of 175


FROD.7/96                                 8

-------
                   transformers, hundreds of drums and thousands of batteries.
                   Chlorinated Dioxins and Furans were identified in ash associated
                   with an on-site incinerator.

 April 1986         EPA issued a CERCLA  106 Order against potentially responsible
                   parties to begin stabilization and cleanup of the site. No parties
                   came forward to implement the cleanup.

 June-July 31
 1986              Phase 1 of the response action commenced by EPA. Site security
                   was undertaken, removal of 1000 gallons of PCB contaminated oils,
                   removal of eighty-five 55 gallon drums of RCRA hazardous waste,
                   installation of four groundwater monitoring wells, isolation of
                   dioxin/furan wastes, construction of an erosion control wall along
                   Ship Creek, fish bioassay of resident fish in Ship Creek, initial PCB
                   soil sampling.

 May 1987          EPA Emergency Response Team and EPA contractors conducted
                   additional site assessment including installing seven temporary
                   monitoring wells, shallow surface soil borings, off-site sampling
                   along Ship Creek.

 June 1987-
 October 1987      EPA conducted phase II  of removal action. Approximately 781,000
                   pounds of batteries and 10,450 gallons of waste oils were recycled,
                   1600 cubic yards of PCB  contaminated soils were stockpiled and
                   sprayed with a temporary concrete fiber cap.

 June 1988          EPA conducted final phase of removal action. These activities were
                   primarily focused on securing the site until further remedial actions
                   could be undertaken.

3.0   HIGHLIGHTS OF COMMUNITY PARTICIPATION

The Proposed Plan for the site was released to the public  for comment on March 13,
1996.  The plan identified EPA's recommendation for cleaning up lead and
polychlorinated biphenyl contaminated soil at the Standard Steel and Metals Salvage
Yard in Anchorage. The Proposed Plan was made available along with the RI/FS
reports at the Information Repositories.  The  comment period lasted from March 18 to
April  17, 1996. The selected remedy is based on the Administrative Record for this site.
The Administrative Record  is located in the EPA Region  10 office and in the  site
information repository located in the Bureau of Land Management Library in
Anchorage, Alaska.
FROD.7/96

-------
A public meeting was held on April 10 at the Fairview Community Recreation Center in
Anchorage.  On April 2 a reminder of the meeting was mailed.  The meeting was
attended by twenty-two people.  EPA's project manager and Chugach Electric
Association's project manager presented information about the site and the
recommended cleanup alternative.  Questions were answered and formal comment was
taken. Four commentators presented oral comments at the meeting.  Responses to the
comments are included in the Responsiveness Summary to the ROD.

3.1    Summary of Community Relations Activities:

July 14, 1989 - Standard Steel proposed for inclusion on the NPL and 60-day comment
period initiated.

July 22, 1992 - Community Relations Plan issued based on telephone interviews
conducted throughout May of 1992.

October 2, 1992 - A fact sheet issued summarizing previous cleanup activities and
upcoming investigations.

May 26, 1993 - A fact sheet announced an agreement signed by Chugach Electric
Association to conduct investigations, and announced an informational meeting to be
held on June 24.

June 24, 1993 - EPA attended meetings with local community groups to discuss the scope
of the remedial investigation.  EPA was interviewed by two local television stations.

November 24, 1993 - A fact sheet was published to update the public on activities at the
site.

July 12, 1994 - A 30-day public comment  period was announced on a proposed Consent
Decree for past cost recovery between EPA and a number of federal and private parties.

March 16, 1995 - A fact sheet asked for input on cleanup  alternatives being evaluated
based on the completed RI/FS.

April 25,  1995 - EPA and the State of Alaska hosted an informational meeting regarding
the remedial alternatives being evaluated.

June 23, 1995 - A fact sheet explained the need for delaying the Proposed Plan for
cleanup and the need for additional studies to evaluate soil washing as a alternative for
remediating  the site.

April 10,  1996- A public meeting was held in Anchorage Alaska to present the Preferred
Alternative to .the community.


FROD.7/96                                10                -

-------
 4.0    SUMMARY OF SITE CHARACTERISTICS

 4.1    Nature and Extent of Contamination

 The nature and extent of contamination has been evaluated using data presented in the
 OSC and the RI reports and supplemental soil sampling conducted during the feasibility
 study.  These data show that, consistent with past site operations, the primary chemicals
 of concerns (COCs) are lead and polychlorinated biphenyls (PCBs).

 For almost all samples where PCBs were detected, Aroclor 1260 was the only PCB
 congener which was found, so that the total  PCB concentration is represented by Aroclor
 1260.

 42    Media of Concern

 The media of concern utilized to evaluate the site are surface and  subsurface soil,
 groundwater, surface water, sediment, and air. 'Contaminants were screened against Risk
 Screening Tables, Supplemental Guidance for Superfund Risk Assessments in Region 10,
 USEPA, October 30, 1992 (Table 6-1) (these values have been replaced in Region 10 by
 using the Region 3 risk tables), and local background values for inorganics. The tables
 utilize  a residential exposure scenario, using standard default exposure  (ingestion and
 inhalation) assumptions which would not result in a 1 in one  million additional chance of
 developing cancer from exposure to a contaminant through ingestion or pose a non-
 carcinogenic risk as expressed by a Hazard Quotient (HQ) greater than 0.1 for
 contaminants in groundwater and lxE-7 and 0.1 HQ in  soils.  Background values were
 derived from the Elmendorf Air Force Base Basewide Background Sampling Report,
 Volume 1.  Contaminants which exceeded screening values were further evaluated in the
 Baseline Risk Assessment.
4.2.1  Surface and Subsurface Soil

Surface soil is defined as the ground surface to 12 inches depth. Subsurface soil is
defined as below 12 inches depth. The following paragraphs discuss the COCs for
surface and subsurface soil. Figures 5-1 through 5-3 depict surface and subsurface soil
PCB and surface lead concentrations.

4.2.1.1 Lead

Lead was detected in 128 of 132 samples analyzed during the RI. The maximum
concentration measured during the RI sampling was 4,300 mg/kg.  The maximum lead
concentration detected during EPA's removal actions investigations was 44,500 mg/kg.
Supplemental sampling during the FS had detections up to 7,200 mg/kg in surface soil.
The background soil concentration for lead is 13.3 mg/kg, as determined by studies


FROD.7/96                                11

-------
conducted during the Elmendorf Air Force Base remedial investigations.  Lead
concentrations greater than 500 mg/kg do not extend below the first two feet of soil.

During the FS numerous additional samples were collected to conduct treatability tests.
These samples focused on acquiring representative soils representing low, average, and
high lead contamination. Low concentrations were around 500 mg/kg, average
concentrations were around 1700 mg/kg, and high concentrations were around 5200
mg/kg. The highest lead concentration detected 24,000 mg/kg.

42.12 Other Inorganics

Arsenic, beryllium, cadmium, chromium, copper and zinc were detected above screening
values and/or background. Arsenic concentrations were below background values
(13.1mg/kg) in all but two samples, (27 mg/kg and 55 mg/kg). These samples were
located in areas with greater than 1000 mg/kg lead.  Beryllium concentrations exceeded
the screening criteria but were all below background. Cadmium concentrations
(maximum of 11.6 mg/kg) exceeded background values  (3.01 mg/kg) but were below the
screening criteria (lOOmg/kg).  Chromium concentrations were all within background
(48.4 mg/kg surface soils and 76.1 mg/kg in subsurface soils) and below the screening
value of 137 mg/kg in all but three samples. These samples were all located in areas ~
with greater than 1000 mg/kg  lead. The maximum chromium concentration detected
was 151 mg/kg.  Copper was detected above background (20 mg/kg) and  above the
screening value of 2,900 mg/kg in only one sample.  This sample had greater than 1,000
mg/kg lead. Zinc was detected (maximum 2,520 mg/kg) above area background (103
mg/kg) but below the screening value of 80,000,mg/kg.

4.2.13 PCBs

PCBs were detected in 89 of 132 soil samples  analyzed during the RL  The maximum
concentration measured during the RI/FS sampling was 380 mg/kg. Twenty nine of 212
samples had concentrations above 50 mg/kg.  Stockpiled (Section 4.2.1.7)  soils from the
Removal Action  had maximum PCB concentrations of up to 10,600 mg/kg. During
sample collection for treatability testing samples were obtained from the stockpiled soils
which had concentrations up to 3,500 mg/kg.

Subsurface PCB contamination extends to groundwater in three locations on site. These
locations are depicted in Figure 5-2.  Of approximately 120 subsurface soil samples
collected (RI/FS and Removal Actions) 3 had concentrations greater than 50 mg/kg.
Maximum concentrations of up to 519 mg/kg PCBs were detected in subsurface soils
associated with the LNAPL. The LNAPL had PCB concentrations of 4,500 mg/kg.
FROD.7/96                                12

-------
During the FS numerous additional samples were collected to conduct treatability
studies. These samples were focused on acquiring representative samples of low, average
and high soil PCB contaminated soils. Low soils were around 50 mg/kg, average soils
were around 150 mg/kg and high soils were around 700 mg/kg. The maximum high
detected was 2700 mg/kg PCBs.

4.2.1.4  Dioxins and Furans

The concentrations of the dioxins and furans are expressed as 2,3,7,8-tetrachlorodibenzo-
p-dioxin equivalent (2,3,7,8-TCDD equivalent).  Dioxins and furans were detected at 9 of
10 surface sample locations.  The maximum 2,3,7,8-TCDD equivalent concentration was
0.0017 mg/kg. All nine samples exceeded the screening value of .0000004 mg/kg.

42.1.5 Volatiles and Semivolatiles

Several volatile and semivolatile organic compounds were detected in the surface soils.
These  compounds include methylene  chloride, trichlorofluoromethane, tetrachloroethane,
bis(2-ethylhexyl)phthalate, butylbenzylphthalate, di-n-butylphthalate, di-n-octylphthalate,
diethylphthalate, dimethylphthalate, 1,2,4-trichlorobenzene, 2-methylnaphthalene,
acenaphthene, anthracene, fluoranthene, fluorene, naphthalene, phenanthrene, and
pyrene. These compounds were all eliminated as potential COCs in the screening
process after comparison of the maximum concentrations with the chemical specific
RBCs.

One or more carcinogenic Polycyclic Aromatic Hydrocarbons (cPAH) were detected at  8
of 11 surface sample locations, often at estimated concentrations less than the practical
quantification limit. No cPAHs were detected at the 9  subsurface soil sample locations.
The maximum concentration of total cPAHs was 25.4 mg/kg.

42.1.6 Presence of Light Non-Aqueous Phase Liquid (LNAPL)

The LNAPL present iat monitoring wells 17 and 19 locations is not evaluated separately
as a medium of concern. The LNAPL is a very viscous, tarry material that cannot be
effectively separated from the soil.  Consequently, the LNAPL is considered as the same
media  of concern as subsurface soil.

During each groundwater sampling event all wells were monitored for the presence of
both light and dense NAPL phases. DNAPL was not detected in any well. LNAPL was
detected in MW-17A and MW-19A.  Selected wells were examined for the presence of
LNAPL using an oil/water interface probe during four separate measuring events.  A
layer of LNAPL was detected in MW-17A (0.23 to 0.44 feet thick) and MW-19A (0.05 to
0.89 feet thick). An LNAPL sheen was detected in well MW-17 for three events and in
MW-19 for the first event only. Temporary wells MW-25 through MW-29 did not
contain LNAPL during any of the measuring events.  These data indicate that, the


FROD.7/96                                13

-------
 LNAPL plume is confined to the central part of the site in the vicinity of MW-17A and
 MW-19A bounded by the temporary well locations 25, 26, 27, 28 and 29, where a free
 product layer was not detected.  A sample of LNAPL was collected from MW-17A and
 analyzed for volatile and semivolatile organics, PCBs, and metals.  The LNAPL analyte
 concentrations are compared with risk based screening values and  MCLs for
 groundwater in the paragraph below. However, the risk based screening values and
 MCLs for groundwater are not applicable for product layer and are mentioned for
 comparative purposes only.

 42.1.6.1 Concentration of PCBs in LNAPL

 The MW-17A product sample was analyzed for seven congeners of PCBs.  Only PCB
 1260 was detected, at  a concentration of 4500 mg/kg (the laboratory reports product
 results in mg/kg instead of mg/L). ,

 42.1.62 Concentration of Lead in LNAPL

 Lead was detected in the MW-17A product sample at a concentration of 4.3 mg/kg.

 42.1.63 Concentration of Other Contaminants in LNAPL

 Volatile organic  compounds detected in the MW-17A product sample  indicated
 concentrations of methylene  chloride (9300 mg/kg), tetrachloroethane (3600 mg/kg), 1,3-
 dimethyl-cyclohexane (3.0 mg/kg), 1,2-dichlorobenzene (0.62 mg/kg), 1,4-
 dichlorobenzene  (2.8 mg/kg), ethylbenzene (1,7 mg/kg), tetrachloroethane (5.6 mg/kg),
 toluene (0.34 mg/kg),  1,1,1-trichloroethane (0.049 mg/kg), trichlorofluoromethane (0.017
 mg/kg) and total xylenes (7.2 mg/kg), and six unknown hydrocarbon compounds.

 Semivolatile organic compounds detected in the product sample included 1,4-
 dichlorobenzene  (13 mg/kg), 1,2,4-trichlorobenzene (1300 mg/kg),  2-methylnaphthalene
 (33 mg/kg), and  bis(2-ethylhexyl)phthalate (20 mg/kg).

 Other metals detected in the product sample which exceeded screening values for
 groundwater included  aluminum (116 mg/kg), calcium (84.5 mg/kg), chromium (0.72
 mg/kg),'copper (4.8 mg/kg),  iron (148 mg/kg), magnesium (47.3 mg/kg), manganese (3.4
 mg/kg), potassium (15.6 mg/kg) and vanadium (0.69 mg/kg).  Arsenic, beryllium,
 cadmium, mercury, silver and thallium were not detected, but the detection limits were
 above their respective  screening values.

42.1.7  Shotcrete  Covered Soils

Approximately 1,600 cubic  yards of PCB contaminated soils are covered  with Shotcrete
along the eastern boundary of the site. These soils have the highest concentration of
PCBs detected at the site, with a maximum concentration of 10,600 mg/kg. An


FROD.7/96                  '              14

-------
 evaluation of frequency has not been conducted but the purpose of the stockpiling on-
 site was to address off-site hot spot areas which exceeded the OSCfs off-site action level
 of 10 mg/kg. On-site soils which had high concentrations (not defined in OSC report
 but some were above 500 mg/kg PCB) of PCBs were excavated and placed in the are
 which was subsequently covered with shotcfete.

 4.3    Groundwater

 Three sets of groundwater data were obtained from twenty wells over approximately a
 one year period. Sampling was conducted at high and low groundwater events.  Seven
 wells were installed as pairs to monitor for dense and light non-aqueous phase liquids.
 Because of sampling problems associated with high sediment levels in groundwater the
 first round groundwater data was not utilized for PCBs, metals and semivolatile organic
 compounds.  Phase 1 and 2 data were used for evaluating volatile organic compounds.
 Volatile organic compounds were not measured during Phase 3. Phase 2 and 3 data
 were used for evaluating metals and semivolatile compounds, including PCBs.

 4.3.1  Lead

 Lead was detected at 3 of 9 down gradient groundwater monitoring locations in Round 2
 at concentrations of 0.0016 to 0.0031  mg/L. Lead was not detected at any of 8 down
 gradient locations in Round 3.

 Lead concentrations in Rounds 2 and 3 are low relative to the EPA promulgated action
 level of 0.015 mg/L, and relative to background at Elmendorf AFB (0.047 mg/L).
 Considering  the low frequency of detection and the low concentrations detected relative
 to the guideline, lead was not retained as a COC for groundwater.

 4.32   PCBs

 PCBs were detected in none of 12 well locations during Round 2.  During Round 3,
 PCBs were detected at 2 of 9 well locations ranging from 0.000023 mg/L to 0.000032
 mg/L. The concentrations are about 20 times lower than the MCL (0.0005 mg/L).
 Considering  the low frequency of detection and the low concentrations detected relative
 to the MCL> PCBs were not retained as a COC for groundwater.

 4.3.3  Volatile Organic Compounds

 Tetrachloroethane (PCE) was detected at 2 of 12 sample locations during Round 1, and
 2 of 9 sample locations during Round 2. The MCL for PCE is 0.005 mg/L and the RBC
was 0.002 mg/L. PCE was detected at 0.0075 mg/L (MW-21) and 0.0022 mg/L (MW-
 24) during Round 1 (January 1993). During Round 2 (April/May 1993), the
 concentrations at these well locations (non-detect at MW-21 and 0.0016 mg/L at MW-
 24) were below both the  MCL and close to the RBC. The additional Round 2 detection


 FROD.7/96                 '               15

-------
 (0.0002 mg/L at well MW-23), was below both the MCL and the RBC  The 95% upper
 confidence limit concentration of PCE including Round 1 data (0.00176 mg/L) is less
 than the MCL and the RBC  PCE was not identified as a COC in soil in the RA.  The
 maximum level of PCE measured in soil was 0.12 mg/kg.  Based on the  low levels of
 PCE in groundwater and no significant detections in soils, PCE is not retained as a COC
 for groundwater.

 43.4   Semivolatile Organic Compounds

 1,2,4-trichlorobenzene was detected at only two locations (MW-21 and MW-24). The
 measured levels were 0.0003 mg/L (MW-21) and 0.0007 mg/L (MW-24). These
 concentrations are below the state and federal MCLs (0.07 mg/L) and the RBC (0.02
 mg/L). (1,2,4-trichlorobenzene was detected in MW-21 at 0.003 mg/L during Round 2,
 which is above the RBC. This concentration, however, was an estimated concentration
 below the practical quantification limit for that sample.  1,2,4-trichlorobenzene was
 detected at .024 mg/1 at MW-21 during round 1, however this data was not utilized
 because of excessive sediment in the sample.) Consequently, 1,2,4-trichlorobenzene is
 not retained as a COC for groundwater.

 43.5   Other Metals

 Various metals in addition to lead were detected in groundwater samples from all twelve
 monitoring wells. As stated previously, Round 1 data will not be discussed here because
 high levels of sediments  in those samples do not make them representative of
 groundwater conditions.  Metals which exceeded screening values in Round 2 and/or
 Round 3 included arsenic (9 wells), cadmium  (1 well), and manganese (1 well). Arsenic
 was the only metal that exceeded its screening value in up gradient monitoring well #23.
 The maximum reported detection for arsenic was 13.9 //g/L in well MW-18, which is
 below the MCL (50 //g/L). The only metal to exceed its MCL was cadmium, which
 exceeded the MCL of 5 //g/L in MW-13 (29.1 //g/L) and up gradient well MW-23 (16.9
//g/L). Concentration of arsenic in Anchorage groundwater production wells ranged
 from 2 to  10 //g/L.  This indicates that the arsenic levels detected in the  groundwater
 samples only slightly exceed area  background  for the lower aquifer.
                                                     »
 The reported background level for cadmium is 0.1 Mg/L. However, the detection
 frequency  of cadmium was low. Cadmium was detected at 3 of 9 well locations within or
 down gradient of the fenced area. Cadmium was detected in 4 of 32 samples collected
 from these wells. Further, it was  detected only in unfiltered groundwater samples.  The
 levels of cadmium measured in unfiltered samples ranged  from 2.4 to 29 Mg/L.  Finally,
 as noted above, it was also detected at the up gradient MW-23 well location at a
 concentration of 16.9 Mg/L. These data suggest that the few detections of cadmium
likely result from the cadmium associated with sediment in unfiltered samples.  The data
do not suggest elevated cadmium resulting from past site operations.
FROD.7/96                                16

-------
 4.4    Surface Water

 No surface water runoff was observed at the site during the course of the RL The only
 surface water feature in the site vicinity is Ship Creek. The average flow rate in Ship
 Creek is approximately 90 million gallons per day.

 4.5    Sediment

 Ship Creek sediment quality was evaluated in the RI. Samples were analyzed for lead
 and PCBs. Washington State 1991 Marine Sediment Guidelines were utilized for
 screening sediments  because no federal or Alaska criteria were as stringent or available
 at the time.  The PCB screening value was .07 mg/kg dry weight and the lead value was
 31.0 mg/kg.  The RI data revealed no significant impacts to Ship Creek sediment
 immediately  adjacent to the site and as far as 500 feet below the site from ongoing or
 current releases from the site.  The scope of the RI did not include sampling further
 downstream because there were reported, non-site related, PCB spills into Ship Creek
 and sediments are periodically dredged from Ship Creek. These two activities would
 have made evaluating past site releases into Ship Creek impractical.  Only two of 22
 creek sediment samples contained lead (CS-261: 34 mg/kg and CSA6-3: 45 mg/kg)
 above the screening value; however, the CS-261  sediments were; not found to be toxic toT
 aquatic life as a result of using two toxicity tests and downstream benthic macro
 invertebrate samples indicated that the benthic communities appeared to be  similar to
 upstream communities.  Two of 22 creek sediment sampling locations (CS-268 and
 CSA6-3) contained PCBs above the detection limit. The measured concentration were
 0.2 mg/kg and 0.078 mg/kg, which are above the screening value. Creek sampling
 locations are shown on Figure 5-4.

 The detections of lead and  PCBs may have resulted*from transport of soil containing
lead and PCBs from the site into the creek or from transport of sediments containing
 lead and PCBs from locations upstream from the site.  Soil transport from the site could
 occur as surface water runoff (although surface water runoff from the site was not
 observed during the RI field investigations) or during flood events. The estimated area
 of submergence during a 100-year flood event is depicted on Figure 1-2. The soils
 present in the areas that would be submerged generally contain low levels of lead
 (maximum 350 mg/kg) and PCBs (maximum 12  mg/kg). The general lack of lead and
 PCB detections at significant concentrations in Ship Creek sediment samples, the lack of
 observed surface water runoff from the site, and the relatively low levels of lead and
 PCBs in soils that would be submerged during flooding suggest that impacts to the creek
 sediment from lead and PCBs originating from the site would not be significant. These
 soils are not creek sediments and as explained earlier, there is no direct surface water
 runoff pathway to transport them into Ship Creek.

 The location  of a wetland identified in the vicinity of the site is shown on Figure 1-2.
 No samples of the sediment in the wetland were collected during the RI;  however, the

 FROD.7/96                                17

-------
nearest soil samples, located between the fenced area of the site and the wetland, about
50 feet from the edge of the wetland, contained low levels of lead (74 to 110 mg/kg) and
PCBs (<0.03 to  1.4 mg/kg).

4.6    Air

Air dispersion modeling was performed to estimate potential maximum off-site ambient
air concentrations and deposition of PCBs and lead resulting from contaminant emissions
from the site under current site conditions and during salvage operations (pre 1986).
Modeling was conducted using the EPA-approved Industrial Source Complex- Long-term
Dispersion Model (ISCLT2).  Modeling conclusions were that air concentrations and
subsequent deposition were insignificant.

Air is not retained as a medium of,concern.

4.7    Summary

The  highest and  most consistent detections of the principle contaminants, lead and PCBs,
was found in surface and subsurface soils. These levels were not as high as those initially
detected during the Removal Action. However, the RI did not re-sample the soil
stockpile and therefore higher concentrations than were reported in the RI are likely
present in the stockpile.

5.0    SUMMARY OF SITE RISKS

CERCLA response actions at the site as described in this ROD are intended to protect
human health and the environment from current and potential future exposure to
hazardous substances found at the site.

To assess the risks posed by site contamination, a "Baseline Human Health and
Ecological Risk Assessment," (Risk Assessment) was conducted by EPA.  The Risk
Assessment assumes that there is no further site cleanup.

The site was divided into three Areas of Concerns (AOC) (Figure  6-1). The  AOCs
were selected based on current site conditions and historical activities. AOC-1 comprises
the north eastern portion'of the site.  This area was where transformers and other
materials were handled frequently.  AOC-1 is characterized by the highest concentrations
of PCBs and lead.  It is also the area where PCB contaminated soils were stockpiled and
covered during the Removal Action.  AOC-2 comprises the remaining portions of the
site within the EPA erected fence and areas bordering the site along Ship Creek.. This
area was used primarily as a storage area for the salvage operations prior to EPA's
Removal Action. AOC-3 consists of areas outside the fence primarily on  the north-west
side of the site.
FROD.7/96                                18

-------
5.1    Human Health Risks

The site is currently a vacant lot. Past uses of the site and the surrounding property is
industrial/commercial. Activities at the site are anticipated to stay
industrial/commercial.

An assessment of the risks to human health involve a four-step process: identification of
contaminants of potential concern (COPCs), an assessment of contaminant toxicity, an
exposure assessment for the population at risk, and a quantitative characterization of the
risk.

5.1.1  Contaminants of Potential Concern

An initial screening analysis was done to identify the chemicals of potential concern
(COPCs).  This screening involved two steps.  In the first step, COPCs were selected
based upon a very conservative estimate of potential health risk.  Maximum
concentrations of chemicals in media (e.g., soil and groundwater) on the site were
compared to conservative risk based concentrations (EPA Region 3 Risk Based
Concentration Table) and background values for inorganics.  The risk based
concentrations were derived assuming residential exposures; acceptable cancer risk levels
of IxlO'7 for soil and IxlO"6 for water; and acceptable HQs of Q.I (Table 6-2).  For lead,
the risk based criteria selected were 500 mg/kg for soil (After completion of the
Baseline Risk Assessment, EPA lowered the screening level for lead to 400 mg/kg in
soils. This change does not affect the conclusions of the Risk Assessment at this site)
and  15 ug/1 for water.  These values are recommended by Superfund guidance.

The  second step in the selection of COPCs was a more refined screening which
narrowed the list of COPCs by considering factors such as frequency of occurrence of
each COC and detection limits.

The  final list of COCs for soil and groundwater are: Arsenic, cadmium, copper,
chromium, lead, dioxins/furans, PAHfs, PCBfs, tetrachloroethane, and 1,2,4-
trichlorobeiizene.  The potential for these  COCs to impact health was further evaluated
using more realistic and site-specific exposure assumptions.

5.1.2  Risks Related to Compounds Other Than Lead

The  methods used to assess exposure and toxicity and to characterize risk are different
for lead than for other contaminants.  Therefore, lead is discussed separately from the
other contaminants in Section 5.4.
FROD.7/96                        .         19

-------
 5.12.1  Toxicity Assessment

 Toxicity information was provided in the Risk Assessment for the chemicals of potential
 concern (COPCs). Generally cancer risks are calculated using toxicity factors known as
 slope factors (SFs), while noncancer risks are assessed using reference doses (RfDs).

 EPA developed SFs  for estimating excess lifetime cancer risks associated with  exposure
 to potential carcinogens. SFs are expressed in units of (mg/kg-day)"1 and are multiplied
 by the estimated intake of a potential carcinogen, in mg/kg-day, to provide an upper-
 bound estimate of the excess lifetime cancer risk associated with exposure at that intake
 level.  The term "upper-bound" reflects the conservative estimate of the risks calculated
 from the SF. Use of this approach makes underestimates of the actual cancer risk highly
 unlikely. SFs are derived from the results of human epidemiological studies, or chronic
 animal bioassay data, to which mathematical interpolation from high to low doses, and
 from animal to human studies, have been applied.

 EPA developed RfDs to indicate the potential for adverse health effects from exposure
 to chemicals exhibiting noncarcinogenic effects.  RfDs, which are expressed in units of
 mg/kg-day, are estimates of lifetime daily exposure for humans, including sensitive
 subpopulations likely to be without risk of adverse effect.  Estimated intakes of
 contaminants of concern from environmental media (e.g., the amount of a contaminant
 of concern ingested from contaminated drinking water) can be compared to the RfD.
 RfDs are derived from human epidemiological studies or animal studies to which
 uncertainty factors have been applied.

 The Risk Assessment relied on oral and inhalation SFs and RfDs.  For the two
 chemicals for which dermal exposures were able to be estimated (PCBs and chlorinated
 dioxins/furans), SFs were derived from oral SFs by adjusting for oral absorption.
 Toxicity factors were obtained from the Integrated Risk Information System (IRIS) or, if
 no IRIS values were  available, from the Health Effects Assessment Summary Table
 (HEAST).

 5.1.2.2 Exposure Assessment

The exposure assessment characterizes  the exposure scenarios, identifies potentially
 exposed populations  and their exposure pathways and routes of exposure, and quantifies
 exposure in terms of chronic daily dose (mg/kg/day or milligrams of contaminant taken
into the body per kilogram of body weight per day).

For current land use, exposures to long-term workers in AOC 3 were considered, AOC 1
and 2 are fenced off  and are not currently used.  For future land-use, on-site exposures
to workers as well  as potential future residents were added for evaluation.  For
residential exposures, the following pathways were considered: (1) exposure to  soil
contaminants through soil ingestion and dermal contact, and inhalation of soil

FROD.7/96                   '            20

-------
 contaminants that have volatilized or have been resuspended on particles in the air; and
 (2) exposure to groundwater contaminants through ingestion of drinking water and
 inhalation of volatiles during showering.  For industrial exposures, all of the same
 pathways were considered except inhalation during showering.

 EPA Superfund guidance recommends that both reasonable maximum exposures
 (RMEs) and average exposures be calculated in site risk assessment. RME exposures
 are calculated using assumptions that result  in higher than average exposures to ensure
 that the risk assessment results are protective of the reasonably maximally exposed
 individual.  For this risk assessment, RME and average exposures were quantified by
 using EPA default exposure factors (e.g.9 body weight; contact rate, exposure frequency
 and duration) with site-specific exposure point concentrations. Both RME and average
 (more typical) exposures were calculated for residents and workers.

 To estimate exposure point concentrations (EPCs) for soil for ingestion and dermal
 exposures, the 95 percent upper confidence levels (UCLs) on the mean were calculated
 separately for soils in each AOC. Because the EPA removal data representing soils
 below the shotcrete cap were not quantitatively evaluated, the EPCs do not include the
 highest PCB concentrations observed in soils at the site.  For drinking water, the
 maximum values of the COPCs in individual wells were used as the EPCs.

 5.1.23  Risk Characterization

 For carcinogens, risks are estimated as the incremental probability  of an individual
 developing cancer over a lifetime as a result of exposure to the  specific carcinogen.
 Excess lifetime cancer  risk is calculated by multiplying the SF (see toxicity assessment,
 Section 5.1.2.1) by the  quantitative estimate  of exposure, the "chronic daily intake."
 These risks  are probabilities generally expressed in scientific notation (e.g., IxlO"6).  An
 excess lifetime cancer risk of IxlO*6 indicates that an individual has a one in one million
 (1:1,000,000) chance of developing cancer as a result of site-related exposure to a
 carcinogen under the specific exposure conditions assumed.

 The potential for noncarcinogenic effects is evaluated by comparing an exposure level
 over a specified time period (lifetime) with a RfD (see toxicity assessment section above)
 derived for a similar exposure  period. The ratio of exposure to toxicity is called a hazard
 quotient (HQ). Hazard quotients are calculated by dividing the exposure by the specific
 RfD. By  adding the hazard  quotients for all contaminants of concern that affect the
 same target  organ (liver, nervous  system, etc),  the hazard index  (HI) can be calculated.

The  RME provides a conservative but reasonable exposure scenario for considering
 remedial actions at a Superfund site.  Based on the RME, when the excess lifetime
 cancer risk estimates are below 1x10"6, or when the noncancer HI is less than 1, EPA
generally considers the potential human health risks to be below levels of concern.
Remedial action may be warranted when excess lifetime cancer risks exceed IxlO"4  (one

 FRQD.7/96                                 21

-------
in ten thousand) and His exceed 1.0. Between IxlO"6 and IxlO"4, clean up may or may
not be selected, depending on individual site conditions including human health and
ecological concerns.

The following discussion summarizes the cancer and noncancer risk characterization
results for the site.

5.1.2.4  Soil COCfs

Cadmium, chromium, and copper were identified in the Risk Assessment (RA) as
preliminary COCs for surface soils.  None of these metals were identified in the RA as
posing a carcinogenic risk above 10"6 or non-carcinogenic risk greater than a HQ of 1.0 .
The RA determined that metals other than lead do not contribute significantly to risk.
These metals were not retained as COCs for developing Remedial Action Objectives
(RAOs); however, their potential contribution to cumulative systemic toxicity was utilized
in evaluating overall risks for the site.  RAOs are discussed in Section 6.

Polycyclic Aromatic Hydrocarbons;  Each of the polycyclic aromatic hydrocarbons
(PAHs) identified in  the RA as a potential COC is a suspected carcinogen.  The
compounds are generally discussed as a group and referred to as carcinogenic PAHs
(cPAHs).  Neither total or individual cPAH risks exceeded the lower end of EPA's
range (lxE-4) for any scenario  or exposure pathway.  Five of the cPAHs posed a risk
greater than lxE-6 for residential exposure via ingestion, and only two cPAHs posed
greater than lxE-6 risk for long-term worker industrial exposure via ingestioa
(Benzo(a)pyrene 3.2xE-6 risk and Chrysene 1.9xE-6 risk).  The RA concluded that
cPAHs are not a significant risk driver at the site and cPAHs were not retained as
COCs for development of RAOs.

52   Combined Short-  and Long-Term Worker Exposure Pathways

Both short- and long-term workers may be exposed to soil ingestion, dermal contact, and
particulate inhalation pathways.  Short-term workers are characterized as construction, or
utility workers who would be exposed to  the site for a limited amount of time.  Short
term workers have a higher ingestion rate (480 vs. 50 mg/day) but shorter exposure
frequency (<75 days/year vs. 250 days/year) and duration (1 year vs. 25 years) and
averaging time for noncarcinogens (365 days vs. 9,125 days) than long-term workers.

5.2.1  Short-Term Worker

Combined RME short-term worker pathway excess cancer risks are 3E-5 in AOC-1, and
combined AOC-1 hazard indices are 3.1. Risks are primarily contributed by PCBs.
Cancer risks are within the 1E-4  to 1E-6 target risk range, while the hazard index
exceeds the level of exposure unlikely to result in adverse health effects.
FROD.7/96                                22

-------
 522  Long-Term Worker

 Combined RME long-term excess cancer risks are 1E-3 in AOC-1 and combined AOC-1
 hazard indices are 5.3. Combined RME long-term cancer risks are 1E-4 in AOCs 2
 and 3, while combined hazard indices are 1.0 in AOC-3 and less than 1.0 in AOC-2.
 These risks are also primarily contributed by PCBs. PCB cancer risks exceed or are
 equivalent to the  1E-4 target risk range in all the AOCs.  The hazard index in AOC-1
 exceeds the level  of exposure unlikely to result in adverse health effects.

 53    Combined  Residential Exposure Pathways

 Combined RME excess cancer risks are 5E-3 in AOC-1, 6E-4 in AOC-2, and 9E-4 in
 AOC-3.  Combined RME hazard indices exceed unity in all AOCs. PCB and 2,3,7,8-
 TCDD equivalent cancer risks exceed the 1E-4 to  1E-6 target risk range in all AOCs.
 Hazard indices for all AOCs exceed the level of exposure that is unlikely to result in
 adverse health effects.  PCBs contribute the greatest to site risks, estimated at
 approximately 80%.  Lead risks were not quantified but exceed EPA's soil screening
 values in all AOCs.  Groundwater risks  do not contribute significantly to total risks.

 The RA reported that 2,3,7,8-TCDD equivalent presented a residential cancer risk
 exceeding 10"4.  Dioxins and furans are retained as soil COCs for development of RAOs,
 because of their potential to contribute to the  cumulative excess cancer risk.  However,
 residential use of the site is highly unlikely and the risk posed by dioxms/furans to long
 and short term workers is within the acceptable risk range.

 Combined Short-  and Long-term workers, and residential risks are summarized in Tables
 6-3 and 6-4.

 The groundwater  pathways do not contribute significantly to risk if inorganic risks are
 not considered, due to  high background concentrations. The inorganic risks were
 attributed to background  contaminants. Lead  risks are discussed below.

 5.4    Risks Related to Lead Only

 There is substantial scientific literature on the toxicological effects of lead in humans.
 Children appear to be the segment of the population at greatest risk from the toxic
 effects of lead.  Health impacts from lead are primarily assessed by using levels of lead
 in blood.  At blood lead levels of 40 to 100 micrograms per deciliter (ug/dL), children
 have exhibited nerve damage, permanent mental retardation, colic, anemia, brain
 damage, and death.  Blood lead levels as low as lOug/dL (or lower) have been
 associated with neurological and developmental defects in children. Blood lead levels of
 concern for adults are generally higher than for children.  However, studies examining
the relationship between lead exposure and blood pressure suggest that blood lead levels
from as low as 7 ug/dL upward  to approximately 30 or 40 ug/dL may increase blood


FROD.7/96                                23

-------
pressure.  In addition, studies suggest that low levels of exposure for pregnant women
may increase the risk for developmental effects in the unborn child.

For lead in soil, EPA's Office of Solid Waste and Emergency Response (OSWER) has
issued Interim Soil Lead Guidance for CERCLA sites. In this guidance, a 400 mg/kg
screening level for lead in soil under residential land use is recommended. This level
was derived using the Integrated Exposure Uptake/Biokinetic (IEUBK) Model to
estimate a soil concentration that will not result, under default residential exposure
assumptions, in an unacceptable blood lead level in children.  Exceeding this level does
not necessarily indicate that a remedial action is necessary, but does indicate that a
site-specific  study of risks is warranted.  Residential cleanup standards for CERCLA
remedial actions can be developed using the IEUBK Model on a site-specific basis where
site data support modification of model default parameters. EPA considers this model
to be the most appropriate and widely applicable tool available for evaluating residential
risks from lead.

Lead was not included  in the quantitative risk estimates of the Risk Assessment because:
(1) EPA-approved RfDs and Sfs are unavailable, and (2) EPA guidelines specify the use
of the EPA Integrated  Exposure Uptake/Biokinetic (IEUBK) model for estimating
acceptable lead levels in soil for children in residential scenarios but there is no EPA *
accepted model for estimating lead exposure to adults in Industrial scenarios.

The IEUBK model estimates the blood lead concentrations expected to result from
exposure to lead concentrations in soil and other media  (e.g., air, water, diet, dust, and
paint) for children.  EPA recommends a benchmark of either  95 percent of the sensitive
population of children having blood lead levels below lOug/dL or a 95 percent
probability of an individual child having a blood lead level below lOug/dL.  When the
IEUBK model is run using this benchmark and all the model's default parameters, an
acceptable soil screening level of about 400 mg/kg is predicted for lead.  [Note:  When
the Risk Assessment was done for the site the IEUBK model  in use by EPA predicted
an acceptable soil screening level of about 500 mg/kg.  The newer version of the model
predicts a level around  400 mg/kg.]

The IEUBK model does not address lead  exposure to older children or adults.
Therefore, potential risks associated with exposures  of adult residents and workers could
not be quantitatively evaluated using the IEUBK model. However, the exposure
potential and sensitivity of older receptors are generally  lower than those of young
children.

Health impacts for lead were characterized by comparing the exposure point
concentrations calculated for lead in soil at the site, using the  methods summarized  .
above to 500 mg/kg (for residential exposures); and to 1,000 mg/kg (for industrial
exposure). In both cases, risks associated with either residential or industrial exposures
to the elevated  concentrations of lead in site soil were determined to present significant


FROD.7/96                                24

-------
risks to human health.  Therefore, a cleanup action to address the lead-contaminated soil
at the site is warranted.

5.5    Ecological Risk Assessment

The objective of the ecological risk assessment was to evaluate potential harm to
ecological receptors posed by chemicals in environmental media both on- and off-site.
The scope of the assessment was limited to the two primary chemicals-of-concern, PCBs
and lead. The assessment identifies several groups of potential ecological pathways and
receptors:

       •     Vegetation potentially exposed through contact with soils
       •     Soil-dwelling invertebrates potentially exposed through contact with soil
       •     Small mammals potentially exposed through ingestion of soil and
             contaminated food
       •     Aquatic life potentially exposed through contact with sediments, or through
             ingestion of contaminated prey.  ,

The ecological risk assessment  concluded  that the most sensitive ecological habitat in the
site vicinity  is  found in Ship Creek.  It further concluded that the data indicate that
conditions within Ship Creek, within the study area, are not significantly impacted by
contamination from the site.

The ecological risk assessment  observed that the highest  contaminant concentrations
were measured in the area where former site operations  were concentrated and that,
because of the gravelly fill material and shotcrete cap, little ecological habitat is present
in this area.

Based on the information presented in the ecological risk assessment, it appears that risk
to ecological receptors are small, due to the poor habitat of the site.  Concentrations of
PCBs outside the existing fence and adjacent to Ship Creek pose a risk to ecological
receptors.

5.6    Uncertainty in the Risk  Assessment

The accuracy of the risk characterization depends in large part on the accuracy and
representativeness of the sampling,  exposure, and toxicological data.  Most assumptions
are intentionally conservative so the risk assessment will  be more likely to overestimate
the risk than to underestimate it. For instance, the Risk Assessment did not alter the
exposure frequency to account for at least 'five months of frozen, or snow covered soils at
the site.

Uncertainty  in the toxicity evaluation may over-estimate risks by relying on slope factors
that describe the upper  confidence limit on cancer risk from carcinogens. Also, evidence

FROD.7/96                                  25

-------
for carcinogenicity of the contaminants of potential concern are based on animal studies
and limited human data.  Some under-estimation of risk may occur, however, due to lack
of quantitative toxicity information for some contaminants detected at the site, and
because the PCB-contaminated soils below the shotcrete were not quantitatively
evaluated.  The soils stockpiled below the shotcrete had PCB detections up to 10,600
mg/kg.

5.7   Conclusion

The Baseline Risk Assessment supports the conclusion that hazardous substances are
found on the  site and that the actual or threatened release of these substances from this
site, if a response action is not taken, may present an imminent and substantial
endangerment to the public health, welfare, or the environment.

6.0   REMEDIAL ACTION OBJECTIVES AND CLEANUP STANDARDS

The overall objective of the remedial actions for the Standard Steel and Metals Salvage
Yard Site is to provide  an effective mechanism for protecting human health and the
environment from contaminated site soils, while allowing future industrial use of the
property. Remediating the site to industrial cleanup levels is appropriate because the
existing land use is industrial/commercial and future land use plans of the municipality
of Anchorage call for maintaining industrial/commercial zoning at the site and
surrounding area.  The  following  remedial action objectives for each contaminated media
have been developed to describe  what site remedial actions will need to be
accomplished.

Groundwater is not retained as a medium of concern for development of RAOs;
however, prevention of future migration of contaminants into groundwater will be
addressed by the selected remedy.

Sediment is not retained as a contaminated medium for development of RAOs; however,
prevention of future migration of contaminants into creek or wetland sediments will be
addressed by the selected remedy.

Surface and subsurface  soil (which includes the LNAPL soil) are retained as media of
concern for development of RAOs. Table 5-1 shows the COCs for the soil medium.
Groundwater, surface water, and  sediments are not retained as contaminated media for
development of RAOs;  however,  prevention of future migration of contaminants into
groundwater, surface water, and sediments will be addressed by the "selected  remedy.

PCBs are the  dominant quantified risk driver, estimated  to contribute at least 80% of the
risk at the site.  While lead was not quantified, a comparison of the lead concentrations
to other contaminants, besides PCBs, showed that lead represents the next most
significant contaminant  at the site. Based on the majority of risks being contributed by


FROD.7/96    -             '              26

-------
lead and PCBs, and the fact that all other contaminants are co-located with PCBs and
lead, these two compounds were selected as "limiting chemicals* for evaluating the site
and remedial action objectives.

Remedial actions at the site are required for contaminated soils only. Groundwater,
sediments, and surface water do not pose an unacceptable risk and therefore do not
require remedial actions.  These three media, as well as air, are media of concern
because, without taking action on contaminated soils, these media would potentially pose
an unacceptable risk in the future.

6.1    Remedial Action Objectives

The RAO's identified for the site are to:

       •     Prevent exposure by inhalation, ingestion, and dermal contact with
             contaminated soils that would result in an excess lifetime carcinogenic risk
             above 1E-4 for industrial use, and off-site non-industrial use;
       •     Prevent exposure by inhalation, ingestion, and dermal contact with
             contaminated soils that would result in noncarcinogenic health effects as
             indicated by an HI greater than 1.0;
       •     Prevent off-site migration of contaminants caused by mechanical  transport,
             surface water runoff, flood events, and wind erosion;
       •     Prevent leaching or migration of soil contaminants into groundwater that
             would result in groundwater contamination  in excess of regulatory
             standards.

These  RAOfs will protect surface water and sediment media of concern.

6.2    Cleanup Standards

Using the RAOs, cleanup standards were developed for each of the contaminants of
concern. Cleanup technologies can be evaluated against these cleanup standards.

62.1    Soil Cleanup Standards

Based upon future industrial land use on the site, cleanup standards for the soil on-site
are required for 2 contaminants: PCBs and lead. The estimated upper-bound cancer
risks were unacceptable (> IxlO"4) for PCBs.  Lead levels were found on site which
exceed the residential screening level  (400 mg/kg) and which are above typical industrial
cleanup levels.  Two sets of cleanup standards will apply to the site.  One set for the
area of the site which will have engineering and/or institutional controls applied to it. In
general, the controlled area will be inside the existing fence.  Another set of cleanup
standards for lead and PCBs will be for areas on the site  that will have unrestricted
access and which pose more ecological concerns.  In general, those areas will be outside

FROD.7/96                                 27

-------
of the existing fence.  PCBs have been detected at levels which would pose a risk to
ecological receptors beyond the fence line and pose an estimated 1E-4 risk to long-term
workers in AOC 3.

There are no federal or Alaska regulatory cleanup standards for PCBs or lead in soil.
The cleanup standards applied at the site soil are derived from two main sources:

      *     EPA guidance on soil cleanup levels (for PCBs and lead);
      >     Risk-based concentrations when guidance is not available.

62.1.1 PCB Cleanup Standards

For PCBs in soil, EPA established  a nationwide spill cleanup policy under the Toxic
Substance Control Act (TSCA), 15 U.S.C. § 2601 et. seq.  The  requirements specified
under 40 CFR 761, Subpart G, particularly with respect to the clean up of
PCB-contaminated soil, are considered a to-be-considered (TBC) guidance  for purposes
of CERCLA actions.  The TSCA cleanup policy applies to spills containing PCBs at
concentrations greater than 50 mg/kg. The cleanup standard for surface soils in
restricted access areas is 25 mg/kg and for nonrestricted  access areas is 10 mg/kg, with
at least a 10 inch cover of clean (less than 1.0 mg/kg PCB) soil.

Less stringent cleanup standards may be approved by EPA on a site-specific basis, as
defined  in 40 CFR § 761.120(c), if factors associated with the spill "may mitigate
expected exposures and risks or make clean up to these requirements impracticable.1'
Alternatively, more stringent levels may be required by EPA based on site-specific
factors (e.g., depth to groundwater  or presence of drinking water wells) as outlined in 40
CFR  § 761.120(b).

For CERCLA sites, EPA developed guidance which recommends action levels for
contaminated soils in both residential and industrial land use scenarios. The action level
for industrial  sites is between  10-25 mg/kg PCBs in soils.

Based on the above guidances and  site-specific conditions, EPA has selected 10 mg/kg
PCB as the cleanup level for soil within the current fenced area (industrial  use) and 1
mg/kg PCB for soils outside of the fenced area. The soil above these levels will have to
be a part of the response action. Table 6-5 presents residual risks posed by the main
risk drivers, excluding lead.

6.2.12 Lead Cleanup Standards

For Standard Steel and Metal Salvage Yard an industrial land-use scenario  is considered
most appropriate. Unfortunately, the IEUBK Model is applicable only to children, and
no IEUBK model is currently approved by EPA for developing an adult industrial
screening level for lead.

FROD.7/96      '                          28

-------
To mitigate health impacts from lead exposure, a 1000 mg/kg soil cleanup level was
chosen as protective.  This level is consistent with other Siiperfund lead cleanup levels at
industrial sites and past EPA guidance (current EPA guidance suggests a 400 mg/kg
screening level is protective for residential scenarios, no screening level is given for
industrial scenarios).

Soil lead concentrations exceed 1000 mg/kg over much of the site in surface soils. The
RI data show that all soils with greater than 1,000 mg/kg lead in surface soils were
within the 10 mg/kg PCB surface soil contour.

Lead in excavated soil is a RCRA hazardous waste when the  results of the Toxicity
Characteristic Leaching Procedure (TCLP) exceeds 5 mg/kg.  When a soil fails TCLP for
lead it is known as a "characteristic" hazardous waste. Concentrations of  1,000 mg/kg for
lead in site soils have failed TCLP, and therefore, are considered hazardous waste.

Considering the  RCRA characteristic waste criteria, collocation of soils with greater than
10 mg/kg PCBs  with 1000 mg/kg lead contaminated soils, EPA's lead cleanup guidance,
and other lead cleanup levels at Superfund sites, the soil cleanup standard for lead at
1000 mg/kg was selected for the site. Soils exceeding 500 mg/kg outside  the current
fenced area will be consolidated into the remediation area. A 500 mg/kg cleanup level ~
was selected instead of current guidance of 400 mg/kg lead screening level in soils
because the surrounding land use is industrial, and will remain industrial in the future.
These soils are not considered RCRA wastes.  However, these soils could be transported
to Ship Creek in the future by surface activities or surface water runoff and pose an
unacceptable risk to biological receptors.

Therefore, excavating and treating soils with greater than 1000 mg/kg lead would occur
to reduce the risks posed by lead in those soils and those soils would require treatment
to comply with RCRA.  Cleanup levels established for lead at other industrial sites in the
region were considered in establishing the cleanup standard at the site.

6.3   Cleanup Standards Conclusions

Based on the information gathered and evaluated in the RI/FS, EPA concludes that
contaminated soil on the site presents an unacceptable risk to human health, welfare,
and the environment.  All other contaminants of concern detected at the site above risk
based levels were contained within soils with greater than  10 mg/kg PCBs and 1000
mg/kg lead.  Therefore actions taken for PCBs and lead will address all remaining
unacceptable risks at the site.

As stated above, the area within the existing fence line is considered the remediation
area.  This area, depending upon the alternative, will require an element of remediation
(capping, treatment, or excavation) and institutional controls.  The area outside of the
existing fence line will not have engineered controls, thus,  those areas will have a 1

FROD.7/96                   '              29

-------
 mg/kg PCB and a 500 mg/kg lead cleanup level for protection of ecological receptors
 adjacent and within Ship Creek.  All soils removed from outside of the existing fence
 line will be consolidated and disposed of within the existing fence boundary, outside of
 the flood plain.

 Liquid PCBs, if present, are considered a principle threat at the site for PCBs.  Principle
 threat lead soils are those which will always fail TCLP. TCLP tests run during the RI
 found a concentration of 3,000 mg/kg lead always exceeded 5 mg/L lead. The
 determination of principle threat lead soils is not a significant factor for evaluating
 remedial actions at the  site, but all principle threat soils will be treated.  All soils failing
 TCLP are  a continuing  source which could impact groundwater, and soils with greater
 than 500 mg/kg PCBs pose an estimated one to two orders of magnitude greater risk
 than the acceptable low end risk range, lEx-4 and are a potential source for impacting
 groundwater.

 EPA evaluated the impacts of dioxins/furans in the Baseline  Risk Assessment.  The
 assessment determined  that dioxins/furans do pose a risk. These soils are collocated
 with PCB soils having greater than 10 mg/kg PCBs. All  actions taken to address PCBs
 will also address dioxins/furans.

      Soil cleanup standards* for the site are:
Contaminant
PCBs
Lead
Within Fence Line
10 mg/kg
1,000 mg/kg
Bevond Fence Line
1 mg/kg
500 mg/kg
* EPA altered the subsurface cleanup level contained in the FS for PCBs from 50 mg/kg
to 10 mg/kg to consolidate all soils which would pose an unacceptable risk if these soils
were exposed in the future by site activities or erosion. This consolidation will ensure
that all surface soils contain less than 10 mg/kg PCBs even after remedial actions are
complete without monitoring soil concentrations or maintaining a clean soil layer (when
applicable). The cost of this alteration is not considered significant because treatment of
soils between 10 mg/kg and 50 mg/kg is not required and there is a reduction in
monitoring and maintenance costs by consolidating contaminated soils.

7.0   DESCRIPTION OF ALTERNATIVES

General response actions and the process options chosen to represent the various
technology types are combined  to form alternatives for the site as a* whole.  Alternatives
were developed to represent a range of potential remedial actions, including institutional
controls, on-site containment, on-site treatment, and off-site treatment and disposal.

The alternatives include a no-action alternative (Alternative  1); an alternative  using
institutional controls with limited on-site remedial  actions  (Alternative 2); a capping


FROD.7/96                                 30

-------
 alternative (Alternative 3); two alternatives that combine containment of low threat soil
 with treatment of principal threat soil (Alternatives 4 and 5); three alternatives that
 incorporate on-site treatment of both low threat and principal threat soil (Alternatives 6,
 7, and 8); and two alternatives that incorporate off-site treatment and disposal of both
 low threat and principal threat soil (Alternatives 9 and 10).

 All alternatives considered except Alternative 1, include: (1) excavation and disposal
 within the existing fence line of contaminated soils from ecologically sensitive areas
 (flood plains and wetlands); and (2) treatment or disposal of materials stockpiled on-site
 from EPA removal actions, remaining scrap material that are deemed hazardous wastes
 under RCRA or as PCB wastes under TSCA, and investigation derived wastes.

 An important element in considering each alternative is the residual risk to human
 health and the  environment after completion of remedial actions.  The risk equations
 and exposure parameters used in the residual risk calculations were the same as those
 used in the Baseline Risk Assessment except for Exposure Frequency.  The exposure
 frequency was changed to 150 days/year to account for the presence of frozen ground for
 five months of  the year at the site.

 Estimates of volumes of soil to be excavated, treated, and disposed of were obtained in
 the following manner.  In the feasibility study, volumes of soil are divided into two major
 categories: principal threat soils (i.e.,  soils with greater than 3,000 mg/kg lead and soils
 with greater than 500 mg/kg PCBs) and soils exceeding remedial action goals (i.e., soils
 with greater than 1,000 mg/kg lead and/or greater than 10 mg/kg  PCBs, and subsurface
 soils with greater than 1,000 mg/kg lead and/or greater than 50 mg/kg PCBs).

 After the FS was completed EPA decided  that the subsurface soil PCB cleanup level was
 should be 10 mg/kg.  This change will affect the volume estimates for subsurface
 excavation for the  selected remedy.  This alteration was deemed more protective of
 human health and  the environment because it ensures future releases would not occur
 from vehicular  traffic, freeze thaw process  and erosion.  Based on current site
 information this alteration should  not result in a significant volume increase in excavated
 soils.

 For each category  of soil, a, range  of potential volumes was estimated.  The minimum
 estimated volumes of soil are obtained using existing soil data with limited extrapolation
 into areas where sampling was not conducted.  The maximum estimated volumes of soil
 are obtained using the existing soil data with extrapolation that involved estimating a
potential maximum extent of contaminated area based on assessment of existing data.

 Present worth cost of each of the alternatives was estimated using the procedures
 described in the EPA Guidance for Conducting Remedial Investigations and Feasibility
Studies Under CERCLA (EPA 1988).  Consistent with this guidance the cost for each
 alternative (where  appropriate) consisted of an estimation of capital  (based on volume

 FROQ.7/96                                 31

-------
estimates, and contingencies) operation and maintenance, and present worth costs
determined for 30 years at a 10 percent discount rate.  Operation, maintenance and
monitoring costs vary per alternative depending on action (soil cover vs geomembrane
cap, removal of all soils vs removal of principle threat soils) and groundwater monitoring
results after five year reviews) Ranges of costs are presented based on  the sensitivity of
the costs to the volume of soil requiring remediation and the unit costs of transportation,
treatment,  and disposal.

7.1    Individual Analysis of Alternatives

Detailed description of these elements is presented in the discussion of the selected
remedy only. (See chapter 10)

7.1.1  Alternative 1 - No Action/Monitoring

Alternative Description

Alternative 1 includes these key components:

       •      Long-term groundwater and surface water monitoring

The existing fence would provide a margin of protection by restricting access; however,
the fence would not provide long-term protection because it would not be maintained
under this alternative, and a fence is not an engineering control to eliminate migration of
contaminated soil by wind erosion, site activities, or a major flood event.  The hazardous
substances  stockpiled on site would also remain and, over time, present a threat of future
releases into the environment.  Detoxification of the  soil as a result  of the natural
degradation of the COCs  over time is not expected to contribute significantly to long-
term effectiveness as lead does not degrade and degradation of PCBs is slow. The half-
lives of the more  highly-chlorinated PCB congeners in soil environments are estimated to
be 20 to 3LO years, under controlled laboratory conditions.

7.1.1.1 Cost

Capital Cost	$     0.0
30 Years Operations and Maintenance Cost	$ 264,000
Present Worth(1)	,	$264,000

(1) Discount rate  (10%) is the average rate of return on private investment, before taxes
and after inflation.

7.1.2  Alternative 2 - Limited Action
FROD.7/96                                 32

-------
Alternative Description

Alternative 2 includes these key components:

       •      Removal of regulated material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •      Excavation and, consolidation within existing fenceline, of impacted and
             estimated 650 cubic yards (cy) soil from flood plain
       •      Installation and maintenance of a protective cover over upland areas
       •      Off-site disposal of 150 tons of scrap and debris by recycling or in a TSCA
             or RCRA Subtitle C or D  landfill
       •      Maintenance of the existing fence to restrict access to the site
       •      Institutional controls to restrict land uses
       •      Long-term groundwater and surface water monitoring

Institutional controls would limit site use  to industrial/commercial use and would
prohibit use of the site for potentially high-exposure commercial use such as a day care
facility. Land use restrictions combined with the fence would greatly reduce the
potential for future exposure of children to lead in site soils. This alternative would
require long-term maintenance of the existing shotcrete cover over the northern part of
the site and establish health and safety procedures for future workers should soil
excavation be  conducted.

Other long-term management controls would include groundwater and surface water
monitoring and installation and maintenance of a protective cover. The cover would
consist of 12 inches of soil over the existing contaminated surface soils to  prevent direct
exposure to  COCs.  The protective cover would reduce long-term worker  exposure (by
about one order of magnitude based on EPA's PCB guidance) and would prevent
erosion and  migration of contaminated soil to surface water or wetlands.  The alternative
contains no provisions for treatment or containment of the LNAPL soil.

The relatively  small volume of soil containing greater than 500 mg/kg lead or 1 mg/kg
PCBs that is present in the flood plain would be consolidated within the fenced area and
beneath the  protective cover.

7.12.1 Cost

Capital Cost	$ 1,290,000
30 Years Operations and Maintenance  Cost	$   283,000
Present Worth(1)	$ 1,573,000

(1) Discount rate (10%) is the average  rate of return on private investment, before taxes
and after inflation.
FROD.7/96                                 33

-------
 7.13  Alternative 3 - Capping

 Alternative Description

 The key components of Alternative 3 include:

       •     Removal of regulated material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •     Off-site disposal of 150 tons of scrap debris by recycling or disposal in a
             TSCA or RCRA Subtitle C or D landfill
       •     Capping all soils exceeding the cleanup levels
       •     Consolidation, under the  cap, of an estimate  1,800 cy of soil exceeding
             cleanup levels from areas outside the proposed capping area
       •     Installation and maintenance of a protective cover over remaining upland
             areas of the site
       •     Institutional controls  to restrict land use

 The cap would cover an area of about  19,000 square yards. The capped area is entirely
 outside of the limits of the  100-year floodplain.  Soil from areas beyond the proposed
 capping area with lead or PCBs above  cleanup levels would be excavated and
 consolidated  beneath  the cap, however, none of these soils would be a characteristic
 hazardous waste by TCLP-lead or would contain greater than 50 mg/kg PCBs.  Soil
 stockpiled during the EPA removal action would also be capped.

 The consolidation area would be compacted prior to cap placement. The consolidation
 area would be capped with a composite layer consisting of a 6-inch sand base layer, a
 minimum 60  mil thick synthetic liner, a 6-inch sand drainage layer, and a 12-inch  soil top
 layer.  Run-on water would be diverted away from the capped area. Based on
 groundwater  modeling, this cap configuration would limit groundwater  infiltration to less
 than 0.01 feet per year and decrease the potential for groundwater contamination. The
 LNAPL soil would be capped but not treated.

 The cap would be designed to be resistant to freeze-thaw and burrowing animals. Since
 the low permeability layer of the cap consists of a synthetic liner and not clay, freeze-
 thaw resistance could  be achieved by providing a base for the synthetic liner that  is
 composed of  non-frost susceptible material, such as sand. Resistance to burrowing
 animals could be  achieved by incorporating a layer of cobbles or heavy-gauge wire mesh
 above the synthetic liner. The cap would also be designed to  support vehicle traffic.

This alternative would require long-term maintenance and  repair of the cap.
 Maintenance  would include yearly inspections of the cap. The inspections would  assess
 any damage to  the synthetic liner or cover materials caused by surface  water erosion,
freeze-thaw action, or human or animal activities.  The inspections would be conducted
FROD.7/96         '                        34

-------
 after breakup, when any potential effects of erosion and freeze-thaw would be most
 visible.

 A protective cover would be placed over upland areas that are not capped. The cover
 would consist of 12 inches of soil containing less than 1 mg/kg PCBs.

 Protection of Ship Creek and wetland sediment and water quality would be achieved
 through installation of the cap, as the cap would effectively isolate impacted soil from
 surface water.  Soil within the flood plain containing >500 mg/kg lead or  > 1 mg/kg
 PCBs would be excavated and consolidated on-site beneath the cap.

 7.L3.1 Cost
                                                           Low            High
 Capital Cost	$2,839,000        $ 2,862,000
 30 Years Operations and Maintenance Cost	$   283,000        $  283,000
 Present Worth*1*	$3,122,000       $3,145,000

 (1) Discount rate (10%) is the average rate of return on private investment, before taxes
 and after inflation.

 7.1.4  Alternative 4 • Containment with Treatment of Principal Threat Soils by
 Stabilization/Solidification

 Alternative Description

 The key components of Alternative 4 include:

       •    .  Removal of regulated material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill, or recycling
       •      Off-site disposal of 150 tons of scrap debris by recycling or in a TSCA or
             RCRA Subtitle. C or D Landfill
       •      Excavation and treatment by stabilization/solidification of an -estimated
             4,400 cy of soil containing lead and PCBs above principal threat
             concentrations
       •      Capping all remaining soils exceeding the cleanup levels
       •      Containment of the LN?APL soil within a 20,000 square foot slurry wall
       •      Excavation and consolidation  beneath the cap of impacted soil from  the
             flood plain
       •      Installation and maintenance of a protective cover over remaining  upland
             areas of the site
       •      Institutional controls to restrict land use
       *      Groundwater monitoring meeting the requirements of 40 CFR § 271.75
FROD.7/96                                 35

-------
The combination of treatment of principal threat soils and containment of low threat
soils is consistent with the NCP (40 CFR § 300.430(a)(iii)(A) through (C)).

The cap would be constructed in the same manner and would cover the same area for
this alternative as for Alternative 3 (Capping). The area of the cap, the source areas
that would be consolidated beneath the cap, the principal threat soil source areas, and
the location of the slurry wall are depicted on Figure 8-1.  The cap would have the same
beneficial effects in preventing contact with impacted soil and minimizing surface water
infiltration as discussed for Alternative 3.  The area contained by the vertical barrier
(discussed below) would be included within the capped area. Areas outside of the cap
would be  covered with 12 inches of soils containing less than 1 mg/kg PCB.

All principal threat soil (greater than 3000 mg/kg lead and 500 mg/kg PCBs) at the site
would be  treated to significantly reduce mobility of the contaminants using
stabilization/solidification.  The stabilization/solidification treatment is described in
greater  detail under Alternative 6.  The treated soil would be placed on-site beneath the
cap above the zone of groundwater fluctuation and below 1 foot depth. Some principal
threat soil is present in the stockpiled soil from the EPA removal action.  The principal
threat soil would be treated and the remainder of the stockpiled soil would be
consolidated beneath the cap.  The stabilization/solidification treatment would result in"
a soil volume increase (estimated to be 15 to 30%) due to addition of stabilizing agents..

Further groundwater protection would be provided by containing the LNAPL soil area
(the area beneath grids B4 through E5, Figure 8-1) within a low-permeability
soil/bentonite slurry wall that is keyed five feet into the low-permeability Bootlegger
Cove Formation. The LNAPL containment area is included within the capped area.
The perimeter of the wall is approximately 800 feet and the area of wall (assuming the
Bootlegger Cove Formation is an average of 25 feet from the soil surface) is 20,000
square feet.  The wall would be formed by excavating a trench around the area to be
contained. The trench would be filled with a bentonite slurry.  The soil excavated from
the trench, which is not expected to be significantly contaminated, would be mixed with
bentonite, and the slurry mixture backfilled into the trench to form the cutoff wall.

Protection of Ship Creek and wetland sediment and water quality would be achieved
through the treatment for mobility of the principle threat soils and installation of the
cap, as the cap would effectively isolate impacted soil from surface water.  Soil within
the flood plain containing >500 mg/kg lead or > 1 mg/kg PCBs would be excavated and
consolidated on-site beneath the cap.

Institutional controls, including land use  and access restrictions would be used. The deed
and access restrictions would be the same as those described for Alternative 3.
Groundwater monitoring would be conducted meeting the requirements of 40 CFR
271.75(b)(6).
FROD.7/96                   '              36

-------
7.1.4.1  Cost
                                                          Low             High
Capital Cost	a	$4,367,000        $4,505,000
30 Years Operations and Maintenance Cost	$  283,000        $   283,000
Present Worth(1)	,	$4,650,000        $4,788,000

(1) Discount rate (10%) is the average rate of return on private investment, before taxes
and after inflation.

7.1.5  Alternative 5 - Stabilization/Solidification with Treatment of PCB Principal
Threat Soils by Thermal Desorption

Alternative Description

The key components of Alternative  5 include:

       •     Removal of regulated  material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill,  or recycling
       «     Off-site disposal of 150 tons of scrap debris in an appropriate landfill
             (TSCA, RCRA Subtitle C or D)
       •     Treatment of an estimated 3,500 cy of soil exceeding the PGB principal
             threat level using thermal desorption
       •      Excavation and on-site stabilization/solidification of an estimated 12,600 cy
             of soils exceeding cleanup levels
       •      Disposal of treated soil on-site in a TSCA landfill
       •      Off-site disposal of thermal desorption process residuals,  including lead-
             contaminated dusts (RCRA Subtitle C landfill) and desorbed PCBs
             (incineration)
       •      Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •      Installation and maintenance of a protective cover over upland areas of the
             site
       •      Institutional controls to restrict land use
       •      Long-term maintenance  of a fence to restrict access to the containment
             area

Soil above cleanup levels would be excavated and pre-processed. Soil containing greater
than 500 mg/kg PCBs would be segregated  for treatment using thermal desorption. Soil
containing less than 500 mg/kg but greater than 50 mg/kg PCBs and greater than  1,000
mg/kg lead would be stabilized.  Soil containing less than 1,000  mg/kg lead and 50
mg/kg PCBs would be disposed of on-site at a depth of greater than one foot but above
the zone of groundwater fluctuation. The zone of groundwater fluctuation would be
backfilled with clean fill.  The locations and approximate depths of the soil that would be
treated are depicted on Figure 8-2.  After pre-processing, the volume of soil to  be


FROD.7/96                                37

-------
 treated by thermal desorption would be approximately 2,400 to 2,900 cubic yards, and the
 volume treated by stabilization/solidification would be approximately 7,700 to 12,600
 cubic yards.  Detailed descriptions of the stabilization/solidification and thermal
 desorption treatments are presented under Alternatives 6 and 8, respectively.

 The LNAPL soil would be excavated, solidified and disposed of on-site or, if PCB
 concentrations are greater than 500 mg/kg, treated by thermal desorption.

 A protective cover consisting of 12 inches of soil containing less than 1 mg/kg PCBs
 would be placed over upland areas of the site to minimize erosion and potential for
 migration of contaminants to surface water or wetlands. Soil within the flood plain
 containing >500 mg/kg lead or  >1 mg/kg PCBs would be excavated and consolidated
 on-site beneath  the cover.  Long-term groundwater monitoring would be conducted to
 assess the effectiveness of the treatment for protecting groundwater.

 7.1.5.1  Cost
                                                           Low            High
 Capital Cost	$ 7,346,000       $ 8,866,000
 30 Years Operations and Maintenance Cost	$   283,000       $  283,000
 Present Worth(1)	_.$ 7,629,000       $9,149,000

 (1) Discount rate (10%) is the average rate of return on private investment, before taxes
 and after inflation.

 7.1.6  Alternative 6 - Stabilization/Solidification

Alternative Description

The key components of Alternative  6 include:

       •      Removal of regulated material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •      Disposal of 150 tons of scrap debris by recycling or disposal in  a TSCA or
             RCRA subtitle C or D landfill

Excavation of an estimated 12,600 cy of soil with subsequent treatment by
stabilization/solidification of soils

       •      Disposal of an estimated  18,300 cy of stabilized/solidified soil on-site in a
             TSCA landfill
       •      Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •      Installation and maintenance of a  protective cover over upland areas of the
             site


FROD.7/96                                 38

-------
       •     Institutional controls to restrict land use
       •     Long-term Operation, Maintenance, and Monitoring of the
             stabilized/solidified soils and the protective coyer (if no re-use of solidified
             soils)
       •     Groundwater monitoring that meets the requirements  of 40 CFR  §
             761.75(b)(6)

 Soil above cleanup levels would be excavated and pre-processed to remove debris and
 oversized rocks.  Soil containing between 10 mg/kg and 50 mg/kg PCBs would  be
 backfilled on-site at a depth of greater than one foot but above the  zone of groundwater
 fluctuation in the on-site TSCA landfill. The zone of groundwater fluctuation would be
 backfilled with clean fill. The locations and approximate depths of the soil that would be
 treated are depicted on Figure 8-3. The excavated, pre-processed soil would be added  to
 a pug mill where it would be mixed with the stabilizing additives and placed in  the
 landfill.  After pre-processing the total volume of soil to be treated would be
 approximately 7,700 to 12,600 cubic yards.  A mixture of 16% cement and 8% fly ash,
 which was determined to be the most effective combination during the treatability study,
 is the suggested stabilizing agent combination. The LNAPL soil may be included with
 the soil that is stabilized/solidified.

 The exact mixing ratios and long-term durability would be evaluated by further  testing
 during remedial design, including freeze-thaw and wet-dry testing. If inadequate
 durability is obtained, engineering controls (for example, changing the agentrsoil ratio,
 increasing the burial depth, or providing a low-permeability liner above or below the
 treated soil) would be implemented.   Based on treatability study results, a soil volume
 increase of about 15 to 30% is anticipated after stabilization.

 Stabilization/solidification is anticipated to be a very effective treatment for protecting
 groundwater because  of two factors: (1) stabilization/solidification of the lead and PCBs
 results in lower potential leaching of COCs to groundwater from the stabilized mass and
 (2)  the low permeability of the stabilized material results in .very slow rates of infiltration
 to the aquifer.  Leaching tests (TCLP) conducted during treatability studies indicate that
 the concentrations of lead and PCBs in leach water would be less than MCLs.  The
 TCLP test uses an acidic solution to simulate leaching, which generally results in more
 leaching of COCs than would occur under natural conditions at the  site. Permeability
 tests indicate very low hydraulic conductivities of the stabilized soil,  ranging from 7 x 10"7
 to 8 x 10"8 centimeters per second (cm/sec).  By comparison, the average hydraulic
 conductivity of site  soils estimated from grain-size distribution relationships was 5 x 10"3
 cm/sec (Woodward-Clyde 1994a), and the hydraulic conductivity in the site vicinity was
 estimated by the USGS to be about 3 x 10'2 cm/sec (USGS 1988). The TSCA chemical
waste landfill liner hydraulic conductivity requirement is 10"7 cm/sec which indicates that
 the  solidified material itself will meet the requirements of a landfill  liner.
FROD.7/96                   '              39

-------
 A potentially important factor in evaluating stabilization/solidification is the effect of the
 presence of the solidified mass on future land use.  The solidified soil would not be
 placed within the 100-year flood plain and would be placed at least one foot above the
 maximum groundwater table elevation.  Clean soil (less than 1 mg/kg PCBs) from on-
 site sources would be used to replace soil excavated from the groundwater table zone. A
 gravel course would be placed over the treated soils to provide a wearing  surface and
 minimize erosion. The ground surface elevations will increase due to the  volume
 increase from the treatment and the addition of the cover layer. The solidified mass
 would be configured to accommodate future site development.  The solidified mass will
 provide excellent foundation support for structures and excellent stability during seismic
 events. Excavation of the solidified soil, however, could not be conducted by
 conventional methods. Disposal of solidified material would be in accordance with
 TSCA disposal and landfill requirements,  40 CFR §§ 761.60 and 761.75. Justification for
 waiving select technical requirements of 40 CFR § 761.75 have been justified in the
 feasibility study, and are  discussed in more detail in section 9.2.

 A protective cover consisting of 12 inches of soil would be placed over upland areas of
 the site to minimize erosion and migration of contaminants to surface water or wetlands.
 Soil within the  flood plain containing >500 mg/kg lead or > 1 mg/kg PCBs would be
 excavated and consolidated on-site. Groundwater monitoring in compliance with 40
 CFR  § 761.75(b)(6) would be conducted to assess the effectiveness of the  remedy for
 protecting groundwater.

 Institutional controls to limit land uses and restrict access would be used.  At a
 minimum, land use restrictions  must be recorded on the title of the property to keep
 activities limited to commercial/industrial uses and  restrict high exposure uses  of
 children, such as day care facilities. Unless the solidified soils are designed and used as
 a building foundation,  a fence or other access barrier may be required to limit
 unrestricted access onto the landfill.

 Long-term monitoring  and, if needed, maintenance  of the landfill will be required.

 7.1.6.1 Cost

                                                           Low            High
 Capital Cost	.'	$4,434,000       $5,396,000
 30 Years Operations and Maintenance Cost	$   283,000       $   283,000
 Present Worth(1)	$4,717,000       $5,679,000
                                                               %
 (1) Discount rate (10%) is the average rate of return on private investment, before taxes
and after inflation.
FROD.7/96 .                                40

-------
7.1.7 Alternative 7 - Soil Washing

Alternative Description

The key components of this remedial alternative include:

       •     Removal of regulated materials stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •     Off-site disposal of 150 tons of scrap debris by recycling or disposal in a
             TSCA or RCRA Subtitle C or D landfill
       •     Excavation of 17,700 cy of soil and treatment by enhanced soil washing of
             an estimated  12,600 cy (after screening) of soil exceeding cleanup levels
       •     Backfilling of an estimated 16,200 cy of screened and washed soil on-site
       •     Stabilization (if necessary) of soil containing elevated levels of lead prior  to
             on site disposal
       •     Dewatering and stabilization of contaminated fines and disposal in an off-
             site TSCA landfill
       •     On-site treatment of process water and disposal in a POTW
       •     Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •     Installation and maintenance of a protective cover over upland areas of the
             site
       •     Institutional controls to restrict land use
       •     Groundwater monitoring in compliance with 40 CFR § 761.75(b)(6)

Soil above cleanup levels would be excavated.  Surface soils containing less than
1,000 mg/kg lead and 50 mg/kg PCBs but above cleanup levels would be backfilled on-
site at a depth of greater than one foot but  above the zone of groundwater fluctuation.
Soil containing greater than 1,000 mg/kg lead or 50 mg/kg PCBs would be treated by
soil washing.  The LNAPL soil would be excavated and treated.

The excavated soil would be screened to remove oversize material including large gravel
and scrap  material.  The soil aggregates would then be broken down and the soil
separated  into fine (fine sand and smaller particle sizes) and coarse fractions using a
trommel.  The fine fraction, is estimated to be 12% to 20% of the total volume washed,
based on particle-size analyses.  The fine fraction (particles smaller than 0.15 mm
diameter)  would be dewatered, stabilized to pass TCLP-lead criteria, and disposed of in
an off-site TSCA landfill. The fine fraction is estimated to be 25% solids prior to
dewatering and 50%  solids  after dewatering. The fines would be disposed of off-site in a
TSCA landfill.  The coarse fraction would be treated in one or two steps.  Paniculate
lead may be removed using a specific gravity separation technique, such as jigging.  The
soil would then be washed using surfactant-enhanced water. Approximately 7,700 to
12,600 cubic yards of soil would be washed in this manner.
FROD.7/96                                 41

-------
Process water and water removed from the sludge fraction would be treated on-site as
needed and discharged to the POTW.  Five thousand gallons of process water was
generated during the pilot tests. A full scale soil washing system must be more effective
at minimizing process water generation. Lead concentrations in the process water were
as high as 32 mg/L (sample SS-WWH4). The POTW discharge standard for lead is 5.0
mg/L; there is no standard for  PCBs.  Process water would be treated to  reduce
inorganic chemicals, organic chemicals and surfactants, and pH neutralization.  Water
treatment may include one or more of the following processes: oil\water separation,
Electrofloc®, precipitation, ultraviolet oxidation, neutralization, and carbon adsorption.

The treated coarse fraction would be disposed on-site.  Treated soil that contains greater
than greater than 1,000 mg/kg lead or 10 mg/kg PCBs would not be replaced within the
top foot or within the zone of groundwater fluctuation. Disposal of soils with greater
than 50 mg/kg PCBs would invoke TSCA disposal and landfill requirements, 40 CFR §§
761.60 and 761.75.  Waivers of  parts of 40 CFR § 761.75 would be required, however
justification for waiving bottom liners and leachate collection systems can not be
justified.

A protective cover consisting of 12 inches of soil would be placed over upland areas of
the site to minimize erosion and migration of contaminants to surface water or wetlands.
Soil within the flood plain containing >500 mg/kg lead or > 1 mg/kg PCBs would be
excavated and consolidated on-site beneath the cover.

Deed and access restrictions would be used as described under Alternative 6. Periodic
groundwater monitoring would  be conducted after remediation is completed.

7.1.7.1 Cost
                                                           Low             High
Capital Cost	$ 6,563,000       $ 8,881,000
30 Years Operations and Maintenance Cost	$   234,000       $   234,000
Present Worth(1)	$6,797,000       $9,115,000

(1) Discount rate (10%) is the average rate of return on private investment, before taxes
and after inflation.

Because  of the relatively high unit cost of treatment, the estimated cost for this
alternative is sensitive to the volume of soil requiring treatment.  In addition, the volume
of fines generated requiring treatment, transportation, and disposal has significant cost
implications, again due to the relatively high unit disposal cost for this soil fraction.  This
is particularly true if incineration of fines is required.  The cost estimate assumes no soil
or fines will require incineration.  The volume and ultimate treatment requirements for
the process water may have significant impact on the final cost for this alternative. Cost
FROD.7/96                                 42

-------
 estimates assumes local treatment of process water will be employed, and that
 incineration will not be required.  Finally, cost estimates assumed stabilization of treated
 soils to obtain a TCLP-lead level of <5 mg/L will not be required. If this supplemental
 treatment process is necessary, an additional cost of approximately $300,000 - $425,000
 can be expected. The Operation and Maintenance cost reduce groundwater monitoring
 after the first 10 years.

 7.1.8  Alternative 8 - Thermal Desorption

 Alternative Description

 The key components of this remedial alternative include:

       •     Removal of regulated materials stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •     Off-site disposal of 150 tons of scrap debris by recycling or disposal in a
             TSCA or RCRA Subtitle C or D landfill
       •     Excavation of an estimated 17,700 cy of soils exceeding cleanup levels and
             treatment of 12,000 cy of soils by thermal desorption
       •     Backfilling treated soil on-site
       •     Stabilization of 5,000 cy of soil and dusts containing elevated lead prior to
             on-site disposal
       •     Disposal of process residuals, including lead-contaminated dusts (off-site
             landfill) and desorbed PCBs (off-site incineration)
       •     Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •     Installation and maintenance of a protective cover over upland areas of the
             site
       •      Institutional controls to restrict land use

Soil above cleanup levels would be excavated and pre-processed.  Surface soil containing
less than 1,000 mg/kg lead and 50 mg/kg PCBs but above surface soil cleanup levels
would be backfilled on-site at a depth of greater than one foot but above the zone of
groundwater  fluctuation. Soil  containing greater than 50 mg/kg PCBs would be treated
by low-temperature thermal desorption.  Soil containing greater than 1,000 mg/kg lead
would be treated by stabilization.  The estimated volume of soil that would be treated by
thermal desorption following pre-processing is  7,200 to 12,000 cubic yards. The
estimated volume of soil that would be treated by stabilization following pre-processing is
3,300 to 5,000 cubic yards.  The LNAPL soil would be excavated and treated.

The excavated, pre-processed soil would be treated using thermal desorption. The
vacuum-enhanced desorption process is  incorporated in the alternative as a potential
process option.  The soil would be fed into a batch processing unit where the
temperature is raised to volatilize PCBs. A negative pressure (vacuum up to 28 inches


FROD.7/96                                 43

-------
Hg) would be maintained within the processing unit to control air emissions and to allow
PCBs to volatilize at a lower temperature (300 to 400T) than at atmospheric pressure
(1,100 to 1,300T). The, volatilized PCBs would be  condensed and concentrated in an oil
phase.  The captured PCBs would be drummed and transported off-site to a TSCA
incinerator. Lead-contaminated dusts collected in the air emissions system would be
stabilized and land filled off-site. The quantity of dust that would be generated is
estimated to be 750 to 1,000 tons.

The vacuum-enhanced process option is currently undemonstrated and not TSCA-
permitted for PCBs.  The vacuum-enhanced process may be unavailable when remedial
activities begin at the site. The high-temperature process option is demonstrated for
PCBs; however, it would be much more expensive to mobilize to Alaska.

Further studies would be required during remedial  design to demonstrate effectiveness
and to determine the most appropriate treatment operating parameters for site soils. In
addition, further studies should probably be conducted to evaluate materials-handling
aspects, such as rewetting of the soil after treatment.

The treated soil would be disposed of on-site. Treated soils with lead concentrations
exceeding 1,000 mg/kg would be stabilized prior to  disposal on-site. The thermally
desorbed soil would require rewetting before it can be stabilized.  The water volatilized
during the desorption process may be used to rewet the soil if it is free of lead and
PCBs. Treated soil that contains greater than 1,000 mg/kg lead or greater than
10 mg/kg PCBs would  not be replaced within the top foot of soil.

A protective cover consisting of 12  inches of soil would be placed over upland areas of
the site to minimize erosion  and migration of contaminants to surface water or wetlands.
Soil within  the flood  plain containing >500 mg/kg lead or > 1 mg/kg PCBs would be
excavated and consolidated on-site  beneath the cover.

Deed restrictions would be used as described under Alternative 6.  Periodic groundwater
monitoring  in compliance with 40 CFR § 761.75(b)(6) would be conducted after
remediation is completed.

7.1.8.1 Cost
                                                         Low             High
Capital Cost	$9,316,000      $ 12,709,000
30 Years Operations  and Maintenance Cost	$  234,000      $    234,000
Present Worth(1)	$9,550,000      $ 12,313,000

(!)  Discount rate  (10%) is the average rate of return on private investment, before ta,xes
and after inflation.
FROD.7/96        '                        44

-------
 The estimated present worth cost for Alternative 8 ranges from $9,550,000 to
 $12,313,000.  Because of the relatively high unit cost of treatment, the estimated cost for
 this alternative is sensitive to the volume of soil requiring treatment. The unit cost for
 processing and cost for mobilization used in the cost estimate assumed that the vacuum-
 enhanced thermal desorption process option, which is currently unproven, will not be
 available when remediation of the site is conducted. The high-temperature thermal
 desorption process option costs were used in the estimate.

 7.1.9  Alternative 9 • Off-site Disposal

 Alternative Description

 The key components of this remedial alternative include:

       •     Removal of regulated material stockpiled on-site and disposal in  a RCRA
             Subtitle C or D landfill
       •     Disposal of 150 tons of scrap debris by recycling or disposal in a TSCA or
             RCRA Subtitle C or D landfill
       •     Excavation of an estimated 17,700 cy of soils exceeding cleanup levels and'
             disposal of an estimated 12,600 cy of soils in an off-site TSCA/RCRA
             landfill
       •     Backfilling of excavations with imported clean soil
       •     Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •     Installation and maintenance of a protective cover over upland areas of the
             site
       •   .  Institutional controls to restrict land use

 Soil above cleanup levels would be excavated.  Soils containing greater than 1,000 mg/kg
 lead would be disppsed of in a solid waste landfill, except that any soils above 5 mg/L
 TCLP-lead will require stabilization prior to disposal. Surface soil containing less than
 1,000 mg/kg lead and 50 mg/kg PCBs but above cleanup levels would be backfilled on-
 site at a depth greater than one foot but above the zone of groundwater fluctuation. The
 excavations would be backfilled with imported clean fill material.  Soil containing greater
 than 50 mg/kg PCBs would  be disposed of in an off-site TSCA landfill.  The LNAPL soil
would be excavated and disposed of off-site.

 Prior to disposal, all debris and material larger than two inches would be screened out.
 The estimated volume of material  to be disposed is 7,700 to 12,600 cubic yards. The
 remaining material would be loaded  on  rail gondola cars to be transported to a
permitted landfill in the lower 48 states  for disposal. All soils would be  stabilized for
lead prior to landfilling.
FROD.7/96                                 45

-------
 A protective cover consisting of 12 inches of soil, containing less than 1 mg/kg PCBs,
 would be placed over upland areas of the site to minimize erosion and migration of
 contaminants to surface water or wetlands.  Soil within the flood plain containing >500
 mg/kg lead or  > 1 mg/kg PCBs would be excavated and consolidated on-site beneath the
 cover.

 Institution controls would be used to prevent exposure to contaminated soils.

 7.1.9.1  Cost

                                                           Low            High
 Capital Cost	:	$8,246,000       $ 12,168,000
 30 Years Operations and Maintenance Cost	$  139,000       $    139,000
 Present Worth(1)	$8,385,000       $ 12,307,000

 (1) Discount rate (10%)  is the average rate of return on private investment, before  taxes
 and after inflation.

 7.1.10 Alternative 10 - Off-site Incineration

 Alternative Description

 The key components of this remedial alternative include:

       •      Removal of regulated material stockpiled on-site and disposal in a RCRA
             Subtitle C or D landfill
       •      Off-site disposal of 150 tons of scrap debris by recycling or disposal  in a
             TSCA or RCRA Subtitle C or D landfill
       •      Excavation of an estimated 17,700 cy of soils exceeding cleanup levels,
             treatment of an estimated 12,600 cy of soils at an off-site TSCA
             incinerator, and stabilization of incinerator ash for lead
       •      Backfilling  excavations with clean imported soil
       •      Excavation and consolidation within the existing fenceline of impacted soil
             from the flood plain
       •      Installation and maintenance of a protective cover over upland areas of the
             site
       •      Institutional controls to restrict land use

Soil above cleanup levels would be excavated. Surface soil containing less than
 1,000  mg/kg lead and 50 mg/kg PCBs but above cleanup levels would be backfilled on-
site at a depth greater than  one foot but above the zone of groundwater fluctuation. The
excavations would  be backfilled with imported clean fill material.  Soil containing greater
than 1,000 mg/kg lead or 50 mg/kg PCBs would be transported off-site and treated  at a
FROD.7/96                   '              46

-------
TSCA incinerator. The LNAPL soil would be excavated and treated off-site.  Lead-
contaminated incinerator ash would be stabilized.

Prior to disposal, all debris and material larger than two inches would be screened out.
The volume of material to be treated/disposed is estimated to range from 7,700 to
12,600 cubic yards.  The remaining material would be loaded on rail gondola cars to be
transported to a TSCA incinerator in the lower 48 states for disposal.

A protective cover consisting of 12 inches of soil, containing less than 1 mg/kg PCBs,
would be placed over upland areas of the site to  minimize erosion and migration of
contaminants to surface water or wetlands.  Soil within the flood plain containing  >500
mg/kg lead or > 1 mg/kg PCBs would be excavated  and consolidated on-site beneath the
soil cover.

Institutional controls would be used to restrict land use.

The estimated present worth cost for Alternative 10  ranges from $21,880,000 to
$34,318,000.  Because of the very high unit  costs of transportation and disposal, the
estimated cost for this alternative is very sensitive to the volume of soil requiring
treatment.

7.1.10.1 Cost
                                                          Low            High
Capital Cost	$21,741,000       $34,179,000
30 Years Operations and Maintenance Cost	$    139,000      $  139,000
Present Worth(1)	$21,880,000      $34,318,000

(1) Discount rate (10%) is the average rate of return on private investment, before taxes
and after inflation.

12    Groundwater Component

The remedial investigation determined that groundwater is not a media of concern
requiring treatment.  Although there is a LNAPL present in the center of the site, no
dissolved contaminants were identified at the boundary of the site. The physical
properties of the LNAPL are conducive to excavation with contaminated soils.  The
LNAPL will be remediated by the same treatment as the soils, unless it is determined
during remedial design testing that the LNAPL requires off-site disposal because it is
considered a liquid as determined by Method 9095 (Paint Filter Liquids Test)  contained
in 40 CFR  § 268.32(i).
FROD.7/96                                 47

-------
 73   Applicable or Relevant and Appropriate Requirements

 Remedial actions implemented under CERCLA must meet legally applicable or relevant
 and appropriate requirements (ARARs).  ARARs include promulgated environmental
 requirements, criteria, standards, and other limitations. Other factors to be considered
 (TBCs) in remedy selection may include nonpromulgated standards, criteria, advisories,
 and guidance, but are not evaluated pursuant to the formal process required for ARARs.
 ARARs of federal or state governments must be complied with during CERCLA
 response actions. Local ordinances with promulgated criteria or standards are not
 considered ARARs, but may  represent TBCs.  Major chemical-specific, location-specific,
 and action-specific ARARs and TBCs for the remedial alternatives are presented below.

 73.1  Chemical-Specific ARARs

 Clean Water Act, 33 U.S.C. § 1314,  establishes water quality criteria for freshwater
 surface waters for lead and PCBs.

 Clean Water Act, 33 U.S.C. § 1313 and 40 CFR § 131.36(d)(12), establishes and
 implements the National Toxics Rule, and sets water quality standards for Alaska.

 40 CFR § 141, Subpart B and F, the Safe Drinking Water Act Maximum Contaminant
 Levels and Maximum Contaminant Level Goals establishes cleanup standards for metals
 and organic compounds, including PCBs, in ground water.

 7.32  Action-Specific ARARs

 Toxic Substances Control Act, 15 U.S.C. § 2601 et se^, and 40 CFR §§ 761.60, 761.70,
 and 761.75 for the treatment, incineration, and disposal of PCBs.

 Clean Water Act, 33 U.S.C. § 1311,  40 CFR § 122.26, direct discharges must meet
 technology-based standards, and storm water regulations for controlling discharges
 associated with industrial or construction activities.                      .

 Clean Water Act, 33 U.S.C. § 1314(b)(l) and 40 CFR Part 230, substantive requirements
for dredge and fill requirements in waters of the United States.

40 CFR Part 403, pretreatment standards for discharges to Publicly Owned Treatment
Works.

40 CFR §§ 268.45 and 268.48. RCRA Land Disposal Restrictions for Hazardous Debris
treatment and disposal.

40 CFR § 261.24. RCRA Characteristic Hazardous Waste Determination is applicable
for identifying soil that must be managed  as hazardous waste (i.e. lead).


FROD.7/96                                48

-------
40 CFR 264, Subpart C, RCRA Standards for Owners and Operators of Hazardous
Waste Treatment, Storage, and Disposal Facilities; Preparedness and Prevention is
applicable for staging and implementing the remedy.

40 CFR 264.310(a), RCRA Subtitle C Landfill Regulation is relevant and appropriate for
the cover design of a landfill, if appropriate.

40 CFR 268, Subparts C and D, Prohibitions on Land Disposal and Treatment Standards
(i.e. lead and California List Wastes) is applicable for preventing the disposal of
Characteristic and California List Wastes;

Alaska Air Quality Regulations 18 AAC Chapter 50 for dust suppression.

733   Location-Specific ARARs

Executive Order 11988, 40 CFR 6, App. A, action within floodplains, avoid adverse
effects, minimize potential harm, restore and preserve natural and beneficial values.

Executive Order 11990, 40 CFR 6, App. A, action within wetlands, avoid adverse effects,-
minimize potential harm, restore and preserve natural and beneficial values.

73.4   To-Be-Considered (TBC) Guidances and Policies

EPAfs Groundwater Protection Strategy, August 1984.

40 CFR Part 761, Subpart G, TSCA PCB Spill Cleanup Policy.

Guidance on Remedial Actions at Superfund Sites with PCB Contamination, OSWER
Directive 9355.4-01.

8.0     COMPARATIVE ANALYSIS

In this section, the relative performance of each alternative  in relation to each specific
evaluation criterion is assessed.  According to the  RI/FS guidance, "the  purpose of the
comparative analysis is to identify the advantages and disadvantages  of each alternative
relative to one another so that the key tradeoffs the decision maker must balance can be
identified".

The NCP requires that a CERCLA remedy provide overall protection of human health
and the environment and  comply with ARARs. These criteria are referred to as the
"threshold criteria."  The remaining five criteria that are analyzed in  the FS are referred
to as the  "balancing criteria." The balancing criteria are:

       •     Long-Term Effectiveness and Permanence;

FROD.7/96                                49

-------
       •      Reduction in Toxicity, Mobility, or Volume (TMV) through Treatment;
       •      Short-Term Effectiveness;
       •      Implementability; and
       •      Cost.

The final two criteria, state acceptance and community acceptance, are evaluated by
EPA after public comment on the Proposed Plan and are referred to as the "modifying
criteria."

8.1    Overall Protection of Human Health and the Environment

Evaluation of this criterion focused on how exposure pathways (ingestion, inhalation,
dermal contact of soils) are eliminated, reduced, or controlled through engineering or
institutional controls.

Alternatives 1 and 2 would not be protective of human health and the environment
because site conditions would remain fundamentally unchanged except for a ten inch soil
cover in Alternative 2, which would not be protective, nor effective over the long term
because activities on-site and/or weather would easily disturb or remove the ten inches
of soil and expose the contaminated soils below.  Alternative 2 does not comply with
TSCA disposal requirements.   They will not be discussed further.  All other alternatives
would be protective of human health and the environment. Alternatives 9 and 10 would
provide the greatest degree of protection for receptors in Anchorage Alaska because the
contaminants would be treated and/or disposed off-site.  Alternatives 3, 4, 5, 6, 7, 8, 9,
and  10 would be protective of human health and the environment.

The principal tradeoffs are between alternatives that provide permanent reductions in
residual risks to human health and the environment through treatment and/or off-site
disposal (Alternatives 5, 6, 7, 8, 9, and 10)  and alternatives that are less permanent but
involve less short-term risk and are easier to  implement (Alternative 3). Alternative 4
provides a compromise in that it combines slightly lower levels of permanence relative to
Alternatives 5, 6, 7,  8, 9, and 10, but has less short-term risk and easier implementability.

8.2    Compliance with ARARs

This criterion addressed whether each alternative meets the action-specific, chemical-
specific, and location-specific ARARs relevant for each  alternative at the site.

8.2.1  Assessment

It is  anticipated that Alternatives 5, 6, 8, 9, and 10 would comply with all ARARs or
meet the criteria for a waiver.
FROD.7/96                                 50

-------
 Alternatives 2, 3, and 4 would not meet the TSCA treatment and disposal requirements
 because no treatment or disposal in an approved chemical waste landfill would occur
 and, as proposed, these alternatives would not meet the criteria for a waiver under
 TSCA's landfill regulation.

 Alternatives 2, 3, and 4 do not comply with Safe Drinking Water MCLs because they
 would not treat contaminated, on-site groundwater.

 Alternative 7 would not meet RCRA LDR ARARs because the treatment method would
 not be able to remove the toxicity characteristic for lead, nor would it achieve the
 percent reductions required for a treatability variance.

 Alternatives 5, 6, 7, 8, 9, and  10 would meet all TBCs.

 Alternatives 3 and 4 do not meet the response objectives of the PCB Spill Cleanup
 Policy because soil containing greater than 10 mg/kg would not be excavated to a depth
 of 10 inches.

 Alternative 3 does not meet the response objectives of the CERCLA PCB guidance
 because containment of low threat  soils and treatment of principal threat soils would not
 be provided.

 8.3    Long-Term Effectiveness and Permanence

 The evaluation of alternatives under this criterion addresses the results of a remedial
 action in terms of the risk remaining at the site after response objectives have been met.
 The criterion is composed of two components: magnitude of residual risk and adequacy
 and reliability of controls used to manage residuals at the site.

 As part of the Removal Action  all liquid principle threats were removed and treated or
 disposed.

 8.3.1   Magnitude of Residual Risk

 Estimated residual long-term worker cancer risk levels in the range of 10"5 to 10"6 and an
 HI of less than 1.0 are estimated after remediation is  completed for Alternatives 3
 through 10. Protection of the environment, including  groundwater, surface water, and
 sediments in the short term, would  be achieved for each of these alternatives. The
potential for impacts to groundwater from the LNAPL soil would be'slightly higher for
Alternative 3  than for Alternatives  4, 5, 6, 7, -8, 9, and 10, although no impacts' to
groundwater,  outside of a very small on-site area, have been observed to date.
FROD.7/96                                 51

-------
83.2  Adequacy and Reliability of Controls

Alternatives 5 through 10 have reliable controls to ensure their permanence.  Alternative
4 relies on a cap and slurry wall which is not as reliable or permanent as solidification,
thermal desorption or off-site disposal/treatment.

Institutional controls provided for Alternatives 4, 5, 6, 7, 8, 9, and 10 are consistent with
the long-term management controls listed in the PCB guidance and are considered to be
adequate and reliable for the levels of lead and PCB residuals that would be left at the
site.

The institutional controls provided for Alternatives 2 and 3 (Capping) are not anticipated
to be adequate for long-term protection of human health, surface water, and sediments.
Alternative 1 does not include institutional controls.

8.33  Assessment

Long-term effectiveness and permanence at the site would be greatest for Alternatives 9
(Off-site Landfill)  and 10 (Off-site Incineration). The maximum  residual long-term
worker cancer risk is in the range of 10"5 to lO^6 and the HI is less than 1.0. Protection~
of the environment would be achieved for each of these alternatives.  Adequate and
reliable controls would be provided for the concentrations of lead and PCBs left on-site.
Future land use would be unrestricted except for a restriction on residential use.

Alternative 8 (Thermal Desorption) was ranked next highest  for long-term effectiveness
and permanence.  Residual long-term worker cancer risks in  the range of 10"5 to 10"6  are
estimated for this alternative. Long-term protection of  the environment would be
achieved. Future land use,  however, would be restricted by the presence of elevated
concentrations of lead in soil. The alternative includes  reliance on institutional controls
to protect workers from exposure  to lead and to maintain the soil cover.

Alternatives 5 (Stabilization/Solidification with Treatment of PCB Principal Threat by
Thermal Desorption) 6 (Stabilization/Solidification), and 7 (Soil  Washing) were ranked
next highest for long-term effectiveness and permanence.  The maximum residual long-
term worker cancer risk is also in the range of 10"5 to 10"6 and the HI is also less than
1.0.  Protection of the environment would be achieved for each of these alternatives by
either destruction of principle threat COCs or the immobilization of all soils above
cleanup levels.  Although, higher levels of COCs in treated soil would be left on-site
compared to Alternatives 8, 9, and 10, long-term groundwater monitoring would be
required to assess protection of groundwater, and future land use will be restricted to
maintain industrial exposures. Additionally these alternatives would rely on institutional
controls and long-term maintenance of solidified soils and soil cover.
FROD.7/96                                  52

-------
Alternative 4 (Containment with Treatment of Principal Threats by Stabilization) was
ranked significantly lower.  It also achieves a maximum residual long-term worker cancer
risk in the range of 10~5 to  10"6, an HI of less than 1.0, and protection of the
environment.  However, while principle threat COCs are immobilized, destruction of
COCs would not be achieved and the majority of PCB and lead contaminated soil would
be  untreated and  left on-site under a cap. Institutional controls would be required for
maintenance and monitoring of the cap. Permanence of the cap would depend on future
land use, and would rely more on institutional controls to keep it intact.  A cap and
slurry wall are less permanent and reliable in the long term than solidification of soils.
Future catastrophic events, such as flooding and seismic  events would pose a significant
threat to the cap and require greater operation, maintenance and monitoring procedures
than solidification or off-site disposal.

Alternative 3 (Capping) was ranked  lower than Alternative 4, although the residual
long-term worker health risks are 10"5 to 10"6 and the HI is less than 1.0, and impacts to
the environment are not anticipated. All COCs (except  the emergency removal action
and scrap removal action wastes) would remain on-site as untreated residuals. The
LNAPL soil would not be treated or contained, and some potential for long-term
groundwater impacts would exist.  Similar  to Alternative 4, a higher reliance on future
land use restrictions would be required to  maintain the cap.

8.4    Reduction of Toxicity, Mobility, or Volume Through Treatment

This evaluation focuses on  the NCP expectation of reduction of toxicity, mobility, or
volume (TMV) for principal threats. The  components of the criterion  are:

       •      Treatment process used and  materials  treated
       •      Amount of hazardous material destroyed or treated
       •      Degree of expected reductions in toxicity, mobility, or volume
       •      Degree to which treatment is irreversible
       •      Type and quantity of treatment residuals remaining after treatment

8.4,1   Discussion

Alternatives 8 and 10 are expected to achieve significant reductions (anticipated  to be
95% or greater) in TMV through treatment. All soil above cleanup levels would be
remediated. It is estimated that greater than 90% of the mass of lead  would be
immobilized and greater than 90% of the mass of PCBs  would be destroyed.

Alternatives 5, 6, and 7 also treat and/or contain all soil above cleanup levels; however,
these  were downgraded  relative to Alternatives 8 and 10 because of lower TMV
reductions and the volume  increase (estimated to be 15 to 30%) associated with
stabilization/solidification (all soils are stabilized/solidified in Alternative  6; all soil
except principal threat PCBs are stabilized/solidified in Alternative 5; and sludges  and

FROD.7/96                                 53

-------
lead-contaminated soils are stabilized as part of Alternative 7). Average PCB reductions
of 93% are estimated for Alternatives 5 and 6 (based on TCLJP reduction, however
TCLP reductions are difficult to reproduce and leaching of PCBs is not a significant
issue).  PCB reductions of 57% to 94% were observed during pilot testing for Alternative
7. For Alternative 7, lead reductions as low as 7% and as high as 99% were observed
during pilot testing.  Alternative 5 was ranked higher than 6 or 7 because destruction of
principal threat PCBs would be achieved.

Alternatives 4 (Containment with Treatment of Principal Threats by Stabilization) was
downgraded somewhat because low threat soil would not be treated.

Alternative 9 (Off-site Landfill) was rated significantly lower because the only reduction
in TMV that would be achieved is associated with stabilization that is required for lead.

Alternatives 3, 4, 6, and 9 would produce little or no process residuals. Alternative 7
followed by 5, 8, and 10 produce the greatest amount of process residuals that would
require further treatment or off-site disposal. Alternative 5 produces an intermediate
amount of process residuals.

Alternatives 4, 5, 6, 7, 8, and 10 would satisfy the statutory preference for treatment as  a
principal element. Alternatives 3 and 9 would not satisfy the statutory preference.

8.4.2   Assessment

Alternatives 8 (Thermal Desorption) and 10 (Off-site Incineration) are ranked highest.
Lead would be treated using BDAT and greater than 95% of PCBs would be destroyed.
Alternative 5 (Stabilization/Solidification with Treatment of PCB Principal Threats by
Thermal Desorption) is ranked next highest.  Lead in principal threat soil would be
treated using stabilization/solidification and greater than 95%  of PCBs contained in
principal threat soil would be destroyed.

Alternatives 4, 6 and 7 are  comparable. Lead would be treated by
stabilization/solidification and PCBs would be treated using solidification (80 to 99%
reduction  in mobility).  The tradeoffs involved in rating the alternatives are that
Alternative 7 would produce relatively  large quantities of process residuals, whereas,
Alternative 6 would produce a relatively large volume increase, while Alternative 4
presents a compromise in that a somewhat smaller mass of COCs would be treated but
relatively small residual amounts and volume increases would be produced.

Alternative 9 (Off-site Disposal) is ranked significantly lower.  The treatment for toxicity
employed  would be minimal and the wastes would be transferred to another location to
contain.
FROD.7/96                                 54

-------
 8.5    Short-Term Effectiveness

 In this section, two criteria are considered: protection of the community, workers, and
 the environment during remedial actions and the time until remedial response objectives
 are achieved.

 8.5.1   Short-Term Protection of the Community, Workers, and the Environment

 Alternative 3 (Capping) involves no excavation, above ground treatment, or transport of
 wastes; therefore, the associated community, worker, and ecological exposures during the
 remedial actions are lowest.

 Alternatives 4 (Containment with Treatment of Principal Threat Soil by Stabilization), 5
 (Stabilization/Solidification with Treatment of PCB Principal Threats by Thermal
 Desorption) 6 (Stabilization/Solidification), 7 (Soil Washing), 8 (Thermal Desorption), 9
 (Off-site Disposal), and 10 (Off-site Incineration) are generally similar in that the
 potential for human or environmental exposures exists during excavation activities.  The
 potential community and worker exposures include physical injury and inhalation of
 contaminated dusts.  The potential  environmental exposures are releases of
 contaminated dusts and runoff water to surface water or wetlands and mobilization of
 COCs to groundwater. The potential exposures are significantly less for Alternatives 4
 and 5 than Alternatives 6, 7,  8, 9, and iO because of the much smaller volumes of
 excavation involved.

 Alternatives 5, 7, 8, 9, and  10 have  additional potential exposures during transportation
 of contaminated wastes or process residuals to the continental U.S. for
 treatment/disposal.  These potential exposures are associated with overland transport,
 overseas transport, and on- and off-loading. Alternatives 9 and 10 involve the largest
volumes of transported wastes and Alternative 5 the smallest volume. Alternative  10
 also includes potential releases of COCs to air at the incinerator site and exposures
 during treatment and transport of lead-contaminated ash.

Alternatives 4, 5, 6, 7, and 8 involve additional potential exposures resulting from on-site
treatment of soil. The potential exposures include physical hazards and releases of
contaminated residuals. The greatest potential exposure from release of treatment
residuals is estimated to result from dry, lead-contaminated dusts and volatile COCs
associated with the thermal desorption treatment (Alternatives 5 and 8).  The potential
exposures are greater for Alternative 8 than Alternative 5 because of the larger volume
of soil treated.  Alternative 7 is anticipated to result in an intermediate level of
exposures during treatment including process water  management, while the exposures
associated with the stabilization/solidification treatment used in Alternatives 4 and 6 are
expected to be less.
FROD.7/96                                 55

-------
 8.5.2  Time Until Remedial Response Objectives are Achieved

 The time frame for completing Alternatives 3 (Capping) is shortest because no
 excavation is involved. Excavation of smaller volumes of soil at shallower depth is
 included in Alternatives 4 and 5, and delays due to excavation are not anticipated. The
 times for completing excavations under Alternatives 6, 7, 8, 9, and 10 are likely to be
 longer because excavation of relatively large volumes of soil, likely including soil beneath
 the groundwater table, is required.  Excavation times could be lengthened if wet weather,
 which is common in Anchorage in the summer, is encountered. For Alternatives 9 (Off-
 site Disposal) and 10 (Off-site Incineration), the time to obtain all necessary approvals
 for shipment of wastes to the off-site treatment/disposal facility could be significant.

 The time frames for completing the treatment component of Alternatives 5
 (Stabilization/Solidification with Treatment of PCB Principal Threats by Thermal
 Desorption) 7 (Soil Washing), and 8 (Thermal Desorption) would likely be longer
 because of factors including:

       •     Pilot and/or pre-remediation testing of equipment
       •     Uncertainty of equipment availability
       •     Multiple treatment/containment processes

 It is reasonable  to expect that each of Alternatives 3, 4, 6, 9, and 10 can be completed in
 a single construction season.  Despite the relatively small treatment volumes under
 Alternative 5, a significant potential exists that the Alternative would not be completed
 in a single construction season because of the need for two separate treatment processes
 and the uncertainties of equipment availability,  effectiveness, and implementability.
 Alternatives 7 and 8 have the greatest potential for extended remediation times.

 8.5*3  Assessment

 Alternative 3 (Capping) has the highest short-term effectiveness.  No excavation or above
 ground treatment is involved; therefore, the associated community, worker, and
 ecological exposures during the remedial actions are  small. Human exposure  and the
potential for migration of COCs to surface water or groundwater are significantly
reduced in a relatively short (one construction season) time period. The short-term
 effectiveness of Alternative 4 (Containment with Treatment of Principal Threats by
 Stabilization) is  nearly as good as Alternative 3 (Capping). Excavation volumes are
limited, no significant exposures have been identified for the treatment process, and it is
anticipated that  the remediation can be completed within a single construction season
using locally available contractors and materials. Alternative  6
 (Stabilization/Solidification) is similar to Alternative 4 but was downgraded because of
the larger excavation volumes, although the short-term impacts due to excavation could
be prevented by using an in-situ process option  and mitigation methods such as dust
control.


FROD.7/96                         .         56

-------
 Overall short-term effectiveness is similar for Alternatives 5, 9, and 10.  The tradeoffs
 are that smaller volumes of soil are excavated and less waste is transported over long
 distances with Alternative 5, but potential exposures and schedule delays associated with
 the treatment process are greater.

 The poorest short-term effectiveness is associated with Alternatives 7 (Soil Washing) and
 8 (Thermal Desorption). Both involve excavation of large volumes of soil, relatively
 complex treatment processes, and transport of residual wastes over long distances. Each
 involves potential exposures  and schedule delays associated with the treatment process.

 8.6    Implementability

 In this section, three criteria are compared: technical feasibility, administrative feasibility,
 and availability of services and materials.

 8.6.1  Technical Feasibility

 Few technical feasibility considerations have been identified for Alternative 3 (Capping).

 Greater implementability concerns exist for Alternatives 5, 6, 7, 8, 9, and 10 because of
 the potential need to control groundwater during excavation near the groundwater table.
 An additional consideration is availability of space to conduct excavation, soil staging and
 dewatering (if required), and treatment/loading.

 Few concerns exist with  respect to the ability to successfully operate the stabilization/
 solidification technology (Alternatives  4, 5, and 6). Stabilization is  a common remedy
 chosen for CERCLA sites and has been accepted in EPA guidance as a treatment
 technology for PCBs.  Stabilization/Solidification has  also been identified as Best
 Demonstrated Available Technology (BDAT) for treating lead under the land disposal
 restrictions. Treatability studies conducted on soil from the site indicate that leaching of
 lead (measured using the TCLP test) is reduced by greater than 99% and leaching of
 PCBs is reduced by 80 to 99% (not a significant issue) following
 stabilization/solidification treatment. The FS provides a summary of the detailed
 analyses conducted to address potential implementability and permanence issues
 associated with stabilization/solidification.  These analyses confirmed that the technology
 is effective, permanent, and implementable at the site.  A potential  implementability
 concern for Alternatives 4, 5, and 6 is  designing the stabilized monolith to withstand
 freeze thaw conditions at the site.  These concerns would be addressed during remedial
 design.

The greatest technical feasibility considerations are associated with soil washing
 (Alternative 7) and thermal desorption (Alternatives 5 and 8).  These considerations are
related to uncertainties in the ability to successfully operate the technologies and
possible schedule delays resulting from technical problems and equipment unavailability.

 FROD.7/96                                  57

-------
 8.6.2  Administrative Feasibility

 Administrative feasibility considerations are expected to be low for Alternatives 3
 (Capping), 4 (Containment with Treatment of Principal Threat Soil by Stabilization), and
 6 (Stabilization/Solidification).  Some concerns related to the long distance transport of
 contaminated material exist for Alternatives 5 (Stabilization/Solidification with
 Treatment of PCB Principal Threats by Thermal Desorption) 7 (Soil Washing), 8
 (Thermal Desorption), 9 (Off-site Disposal), and 10 (Off-site Incineration). Additional
 implementability considerations for Alternatives 5, 7, and 8 are related to meeting
 process water disposal and air emissions (Alternatives 5 and 8 only) requirements.

 8.63  Availability of Services and Materials

 Availability of services and materials is not anticipated to be a problem for Alternatives
 3, 4, 6, 9, and 10.  Alternatives 3, 4, and 6 can be implemented using local materials and
 contractors.  Treatment/disposal under Alternatives 9 and 10  would require services
 available only in the lower 48 states. Availability of services and materials is a concern
 for Alternatives 5, 7, and 8. Availability of services is particularly a concern for
 Alternatives 5 and 8 since only one contractor can currently supply the process option
 evaluated. It is unlikely that Alternatives 5, 7, and 8 can be completed using local
 contractors.

 8.6.4  Assessment

 The fewest considerations are associated with Alternatives 3 (Capping), 4 (Containment
 with Treatment of Principal Threat Soil by Stabilization), and 6
 (Stabilization/Solidification).  Alternative 6 was downgraded somewhat because of
 technical implementability considerations related to excavation near the groundwater
 table.

 Alternative 5 (Stabilization/Solidification with Treatment of PCB Principal Threats by
 Thermal Desorption) is ranked next highest for implementability, but was downgraded
 significantly relative to Alternative 6 (Stabilization/Solidification) because of
 uncertainties of the ability to successfully operate the thermal desorption equipment, the
 potential for schedule  delays due to equipment problems, the  need to meet air emissions
 and process water disposal requirements, administrative considerations related to long-
 distance  transport of wastes, and the potential for poor availability of services,  and the
 difficulties in operating multiple treatment trains on a site with limited available space.

Alternative 7 (soil washing) is ranked with Alternative 5 due to implementability
 considerations summarized above, including wash water volume and corresponding
 treatment requirements, and potential  operational difficulties due to input  materials
variability. Excavation near the water table, equipment reliability, and transport of
FROD.7/96                      '            58

-------
 residual waste over long distances are additional implementability considerations
 associated with this alternative.

 Alternatives 9 (Off-site Landfill) and 10 (Off-site Incineration) are ranked below
 Alternative 5. The tradeoffs are that excavation near the groundwater table and
 transport of larger volumes of waste would be required under Alternatives 9 and 10, and
 this would more than balance the greater concerns with equipment availability and
 reliability and meeting air emissions and process water  disposal requirements that are
 associated with Alternative 5.

 Alternative 8 (Thermal Desorption) is ranked lowest for implementability. This
 alternative has numerous implementability considerations, including excavation near the
 water table, equipment availability and reliability, process water disposal and air
 emissions (Alternative 8) requirements, and transport of waste over long distances.

 8.7    Cost

 Costs for the ten alternatives range from a low of $0.3 million for Alternative  1 (No
 Action) to a high of $21.9 to $34.3 million for Alternative 10 (Off-site Incineration). The
 remaining eight alternatives rank as follows (from low to high):

       •      Alternative 2 (Limited Action)—$1.6 million
       •      Alternative 3 (Capping)—$3.1 million
       •      Alternative 4 (Containment with Treatment of Principal Threat Soils by
             Stabilization/Solidification)—$4.7 to $4.8 million
       •      Alternative 6 (Stabilization/Solidification)—$4.7 to $5.8 million
       *      Alternative 7 (Soil Washing)—$6.8 to $9.1 million.
       •      Alternative 5 (Stabilization/Solidification  with Treatment of PCB Principal
             Threats by Thermal Desorption)—$7.6  to  $9.1 million
       •      Alternative 9 (Off-site Landfilling)—$8.4 to $12.3 million
       •      Alternative 8 (Thermal Desorption)—$9.6 to $12.3 million

8.8    State Acceptance

The State of Alaska concurs with the selected remedy.

8.9    Community Acceptance

Comments received during the Public Review were both receptive and opposed to the
preferred alternative. Comments opposed were mainly  concerned with future  releases  of
contaminants from the TSCA landfill.  Some of these concerns will be addressed during
remedial design of the landfill. More complete responses to the comments received are
contained in the Responsiveness Summary attached to this Record of Decision.
FROD.7/96                                  59

-------
9.0    THE SELECTED REMEDY

9.1    Remedy Description

Based upon consideration of the requirements of CERCLA, the detailed analysis of the
alternatives using the nine criteria, and public comments, EPA has determined that
Alternative 6 (Solidification/stabilization), with changes from the feasibility study
described below, is the most appropriate remedy for the Standard Steel and Metals
Salvage Yard Site in Anchorage, Alaska.

The key components of the selected remedy include:
(Refer to Table 9-1 for cleanup and treatment level summary)

       •      Removal of regulated, material stockpiled on-site and investigation derived
             wastes with subsequent disposal in a RCRA Subtitle C or D landfill, or
             recycling of materials;
       •      Off-site disposal of remaining scrap .debris by recycling or disposal in a
             RCRA Subtitle D landfill or, if the debris is a characteristic hazardous
             waste  or contains greater than 50 mg/kg PCBs or lOug/100cm2 by standard
             wipe tests, treatment and disposal in a RCRA Subtitle C or TSCA landfill;
       •      Excavation and consolidation of all soils exceeding a 10 mg/kg PCBs or
             lOOOmg/kg lead cleanup level;
       •      Treatment of all soils at  or greater than 1000 mg/kg lead or 50 mg/kg
             PCB, or greater, by stabilization/solidification;
       •    . * On-site disposal of stabilized/solidified soils and excavated soils between
             10 mg/kg and 50 mg/kg  PCBs in a TSCA landfill;
       •      Excavation of soils impacted above Img/kg PCBs and 500 mg/kg lead
            .from the flood plain and consolidation of these soils elsewhere on the site;
       •      Maintenance and repair of erosion control structure on bank of Ship
             Creek;
       •      Maintenance of solidified/stabilized soils and the landfill;
       •      Institutional controls to limit land uses of the  site and, if appropriate,
             access;
       •      Monitoring of groundwater at the site to ensure the effectiveness  of the
             remedial action.

Scrap Debris Disposal

Approximately 150 tons of debris generated during the scrap removal action remain
stockpiled on-site. All scrap and debris, including that generated during soil pre-
screening and located in the channel of Ship Creek, would be transported off-site and
disposed at a permitted Subtitle C, D or TSCA  landfill.  Disposal will comply with all
applicable rules and regulations.  Scrap metal is to be recycled through a legally
permitted scrap metal recycler.  This recycling must include resmelting/melting of all


FROD.7/96                                60

-------
scrap metal.  (Scrap metal may be incorporated into the on-site TSCA landfill if it will
not compromise the integrity of the landfill.)

Regulated Material Removal

Approximately 290 drums are currently stored on-site. The drums contain materials
stored by EPA during the emergency removal actions, oil and fuel salvaged during the
scrap removal actions, and decontamination wastes and personal protective equipment
generated during the RI field work. Also remaining on-site are a shipping container with
the former site incinerator, various batteries, and other wastes. Off-site disposal of some
of these materials is regulated by RCRA, depending on the specific waste.  Disposal
options include off-site landfilling or off-site incineration. Final disposal actions will be
decided during remedial design and will be based on cost, and availability of services.
Disposal will comply with all applicable  rules and regulations.

Excavation

All soils above 10 mg/kg PCBs and all soils above 1000 mg/kg lead will be excavated
and placed in the on-site TSCA landfill. Soils within the flood plain will be excavated
when it exceeds  1  mg/kg PCBs or 500 mg/kg lead and placed elsewhere on-site.

Contaminant levels will be determined prior to excavation by current data or additional
sampling. Soils may not be stockpiled in a manner which would reduce the contaminant
concentrations to below the treatment level of 50 mg/kg PCBs or lOOOmg/kg lead,
unless the stockpiled soils will be treated.

Soil above cleanup levels would be excavated, screened and pre-processed to remove
materials not suitable for stabilization/solidification.  Soil containing less than  1,000
mg/kg lead and less than 50 mg/kg PCBs but greater than 10 mg/kg PCB will be
consolidated on-site in the TSCA landfill at a depth of greater than one foot below the
surface, but above the zone of groundwater fluctuation. The change of the subsurface
cleanup level contained in the feasibility study from 50 mg/kg to 1.0 mg/kg  PGBs is
appropriate to insure future site activities and flood events do not expose greater than 10
mg/kg PCBs contaminated soils.  This change is more cost effective than requiring a
TSCA cap over the entire site and associated monitoring and maintenance of the soils
and cap.  If soils with PCB concentrations between 10 mg/kg and 50 mg/kg are placed
on the top of the landfill  a cover which will prevent erosion, infiltration and contact with
untreated soils will be required above  those soils.

Grading/Backfilling/Cover

The zone of groundwater fluctuation would be backfilled with clean fill (less than 1
mg/kg PCBs). The site will be graded  to prevent surface water runoff to Ship Creek (see
Stormwater Management section). Excavated areas  above the groundwater fluctuation


FROD.7/96                                 61

-------
zone will be backfilled with soils containing less than 10 mg/kg PCBs. The surface of
the site will^be graded with clean soils which will support a vegetative cover or paved to
prevent erosion of surface soils. If no immediate reuse of the  TSCA landfill occurs than
it will be covered with a protective cap to (1) allow the landfill to function with minimal
maintenance and (2) promote drainage, reduce freeze thaw effects and minimize erosion
or abrasion of the treated soils. 40 CFR 264.310(a)  is relevant and appropriate for this
action.

Soil Pretreatment/Prescreening

All soil that needs to be treated (greater than or equal to 50 mg/kg PCBs and 1000
mg/kg lead) would go through a pretreatment step to screen out  material which is
oversized and may interfere with the treatment process. Potential material to be
screened out includes wood, cardboard, wire, cobbles and scrap debris.  As observed
during the  site investigations, the scrap debris include predominantly pieces of metal and
wood.  If remedial design determines that scrap will  not interfere in the performance of
the  monolith than this material may be included in  the monolith. Wood and other
organic debris will be screened out and disposed of off-site pursuant to all rules and
regulations (see above discussion on Scrap Debris Disposal)

Soils and debris will be kept wet during screening to minimize dust.  The cobbles may be
separated from the debris in an additional screening step. The cobbles could be used
along fill material to backfill the excavations or be disposed of in the TSCA landfill.

Stabilization/Solidification Process

The excavated, pre-processed soil would be added to a pug mill where it would be mixed
with the  stabilizing additives.  After pre-processing the 'total volume of soil to be treated
would be approximately 7,700 to 12,600 cubic yards.  A mixture of 16%  cement and 8%
fly ash, which  was determined to be the most effective combination during the
treatability study is anticipated as a likely mix ratio.  However, additional design testing
will be conducted to refine the mix ratio to minimize volume increases, reduce freeze
thaw effects and maximize the solidified massfs long-term durability and potential as a
building  platform.  The addition of pozzolans will  be evaluated to reduce pH changes in
the solidified soils  and temperature increases during  curing.  The  LNAPL will be
included with  the soil that is stabilized/solidified if it is determined that it will not
interfere with  curing and is not considered a liquid.  If the LNAPL is considered a liquid
or will interfere with the curing of the monolith then the LNAPL will be collected and
transported off-site for incineration.  Contaminated soils associated^with the LNAPL will
be stabilized if they do not interfere with the stabilization process.

An expanded treatability study shall be conducted as soon as practicable to further assess
the stability and physical characteristics of the stabilization/solidification process and to
demonstrate the predicted effectiveness of the stabilization/solidification process. The


FROD.7/96                                  62

-------
 recommended tests shall include, but not be limited to: (1) PSA Mod. MCC-1 Static
 Leach Test (U.S. DOE-5820) or comparable test procedure; (2) TCLP analysis on the
 solidified material; (3) additional leaching test(s) on solidified samples subjected to test
 procedures to simulate long term weathering such as freeze-thaw, compression, etc.; and
 (4) evaluation of chemical/physical properties such as temperature and pH on the
 solidification process. A life expectancy of 1000 years will be a design goal. Life
 expectancy is defined as the time before contaminants are released above design criteria
 from the TSCA landfill.

 If inadequate durability is obtained, additional engineering controls (for example,
 changing the agent: soil ratio, increasing the burial depth, or providing a low-
 permeability liner above and/or below the treated soil) would be implemented at the
 discretion of EPA. Based on treatability study results,  a soil volume  increase of about 15
 to 30% is anticipated after stabilization.

 A potentially important factor in evaluating  stabilization/solidification is the effect of the
 presence of the  solidified mass on future land use.  The solidified soil would not be
 placed within the  100-year flood plain and would be placed at least one foot above the
 maximum groundwater table elevation.  Clean soil (less than  Img/kg PCBs) and other
 fill would be used to replace soil excavated from the groundwater table zone.  In the
 event there is no planned future use of the landfill as a building foundation or parking
 area, a cover to protect the landfill will be placed to provide a wearing surface, prevent
 infiltration and minimize erosion.  The  cover will be maintained until reuse of the
 monolith occurs. The ground surface elevations will increase due to  the volume increase
 from the treatment and the addition of the cover layer (see Grading/Backfilling/Cover
 section). The solidified mass will be configured to accommodate future site development
 to the greatest extent practicable.

 There are potential short-term  human health and environmental impacts associated with
 excavation and the solidification/stabilization process.  One potential impact is dust,
which could be inhaled by workers or members of the community or could migrate to
 surface water or adjacent properties.  The steps that would be taken  to minimize these
 impacts include use of dust suppressants and collection and analysis of air samples. A
 second potential impact is migration of COCs to ecological receptors via surface water
runoff.  These impacts would be controlled by covering impacted soils and using berms
and diversion ditches. A final potential impact is physical injury to workers. These
impacts would be controlled by instituting appropriate health  and safety procedures. A
third potential impact is the volatilization of PCBs during the solidification process. This
potential will be evaluated during treatability testing and appropriate measures will be
taken to prevent volatilization of PCBs  or control the release of volatilized PCBs during
treatment.

In order to evaluate the effectiveness of the  stabilization/solidification process, the
following physical  and chemical tests of treated solidified soil shall be established as

FROD.7/96                                 63

-------
minimum performance standards. The minimum performance standards shall be
demonstrated in the laboratory and in field testing during construction.

       1.     The Toxicity Characteristic Leaching Procedure (TCLP) test for PCBs shall
             be .5 ug/L or less.  For lead the values shall be 5 mg/L or less. These
             values reflect the MCL for PCBs and the Maximum Concentration of
             Contaminants for the Toxicity Characteristic test, pursuant to 40 CFR
             261.24, Table 1.

       2.     The 28-d,ay unconfined compressive strength shall be greater than 50 psi
             (ASTM Method D2166 or equivalent).  Depending upon the additive mix
             ratio this test may be inappropriate and another test will be utilized to
             determine unconfined compressive strength, with the approval of EPA.

       3.     The triaxial permeability shall be less than  1 x 10[-7] cm/sec (USAGE
             Method 1110-2-1906 or equivalent).

       4.     PSA Mod. MCC-1 Static Leach Test (U.S. DOE-5820) This  test will
             demonstrate that the treated soils do not  leach lead above 15 ug/L. The
             goal is to not increase the leachability of  lead under neutral water
             conditions.

If during design testing it is determined that the  Performance Standards for unconfined
compressive strength and triaxial permeability will reduce the permanence of the
containment system these standards may be altered with the approval of EPA.
Engineered controls shall be employed to compensate for the reduction of compressive
strength and permeability.

Confirmation Sampling

All soils to be excavated, treated or disposed will include confirmation sampling to
determine the amount of soil to be excavated and treated and to document that soils
above cleanup levels are removed and treated if necessary.  Confirmation testing would
include analysis for both lead and PCBs.  If the excavation testing indicates that the lead
or PCB cleanup level is exceeded, additional material would be excavated vertically and
horizontally until cleanup levels are met.  Samples of the stabilized soil will be collected
for future evaluation and testing.

Treatment Equipment and Staging Areas Preparation             "

A soil staging area would be set up on the site.  The  area, which would be on the order
of 200 by 200 feet, would be lined by plastic sheeting. An area on the order of 100 feet
by 200 feet, depending  on the needs for the project, would be cleared near the soil
FROD.7/96                                64

-------
staging area and compacted prior to construction of a bermed pad for equipment set up.
Utility hook-ups would be established as appropriate for the equipment.

Consolidation of Soil from Hood Plain Within Upland Areas

Soils within the floodplain which contain lead or PCBs at concentrations at or greater
than 500 mg/kg lead or at or greater then 1 mg/kg PCBs would be excavated and
consolidated within the existing fence line outside  of the 100 year floodplain. These
lower action levels (compared to the 1,000 mg/kg  lead and 10 mg/kg PCBs cleanup
levels for non-flood plain soils) would be used to provide an additional margin of
protection in ecologically-sensitive areas.  Figure 2-3 shows the approximate extent of the
100-year flood plain (based on 1988 mapping). A small flood plain area beyond the
southwest corner of the fence contains soil with greater than 1 mg/kg PCBs.  A
comparison of Figure 2-3 with Figures 1-6 and 1-8 indicates that no mapped wetlands
contain soil with greater than 500 mg/kg lead or 1 mg/kg PCBs.  The area disturbed by
excavation would be restored to the original grade and revegetated with native species.
The consolidation action would not include any excavation or disposal of hazardous
waste or TSCA-regulated material.

Disposal of Treated Soils

Treated soil and soils at or above 10 mg/kg PCBs would be disposed into  an on-site
TSCA landfill.  The location and dimensions of the landfill shall be determined during
remedial design and must be outside the 100-year  floodplain. The relevant TSCA
regulations for design are provided in 40 CFR § 761.75(b), except the requirements
waived pursuant to 40 CFR  § 761.75(c)(4) below. Solidified soils with lead or PCB
concentrations at or greater than 1,000 or 50 mg/kg, respectively, would not be replaced
in the top foot or in the zone of groundwater  fluctuation. Surface concentrations of the
treated soils will be less than 10 mg/kg PCBs. Routine maintenance and inspection of
the TSCA landfill shall be conducted during groundwater monitoring events and after
any seismic or flood event. The landfill will be designed and located to maximize future
use of the site, specifically to utilize the solidified soils as a building foundation or
parking area. If use of the landfill as a foundation or parking lot does not occur a cover
consisting of an impermeable liner, drainage layer, and erosion control layer will be
provided.  These layers will consist of a impermeable (less than lxE-6 permeability)
liner, a one foot boundary layer and one foot  of growth media.

The following technical requirements specified in 40 CFR § 761.75(b) are waived:
(1),(2),(3),(7), and (8).  40 CFR § 761.75(b)(9)(i) may be waived if conditions discussed
below occur.  The following evaluation justifies waiving these requirements:

      •      Soils.  This standard specifies  that the landfill be located in a thick,
             relatively impermeable soil or rock formation or a low-permeability in-
             place soil with a minimum thickness  of 4 feet or  on a compacted, low


FROD.7/96                                 65

-------
             permeability liner with a minimum thickness of 3 feet. [40 CFR §
             761.75(b)(l)]. The Selected Remedy includes  encapsulation of the COCs.
             Through proper design, this encapsulation will be equivalent to the
             relatively impermeable soils, low permeability  soils, and low permeability
             liner specified in the standard.  The solidified  mass will have an extremely
             low permeability such that leachate generation out of the disposal unit will
             be minimized.  The treatability study completed for the site supports this
             determination.  The hydraulic conductivities of solidified treatability study
             samples ranged from 8 x 10"8 to 7 x 10"7 cm/sec, similar to the hydraulic
             conductivity requirement provided in 40 CFR § 761.75(b)(l). Additionally,
             research and applicable experience at CERCLA sites provide further
             evidence that a properly designed stabilization/solidification remedy can
             adequately, through groundwater releases, protect against an unreasonable
             risk of injury to health or  the environment by reducing leachate generation
             to extremely  low levels.

       •     Synthetic Membrane Liners.  This standard specifies that a synthetic
             membrane liner with a minimum thickness of 30 mils will be used when, in
             the judgment of the Regional Administrator, the hydrologic or geologic
             conditions at the landfill require such a liner to provide at least a
             permeability  equivalent to the soils described above. [40 CFR §
             761.75(b)(2)]. This requirement addresses a bottom liner under the waste.
             As noted above, the soil treatment design will  be developed such that the
             stabilized/solidified soils provide a level of protection comparable to  a low
             permeability  liner, (e.g.  a 30 mil synthetic bottom liner system as specified
             in the regulations).  In general,  a top liner would be needed at a disposal
             site to minimize infiltration into the waste if hydrologic or geologic
             conditions were such that  precipitation could enter the waste at a rate
             greater than it could leave the waste.  This would not be the case with the
             selected remedy because the treated soils would have an extremely low
             permeability  as compared to the underlying and surrounding native soils.
             Following the path of least resistance, precipitation would instead tend to
             migrate around the solidified mass rather than through it.  Therefore
             waiving this requirement will not present an unreasonable  risk of injury to
             health or the environment.

       •      Hydrologic Conditions.  In part, this standard specifies that the bottom of
             the landfill be at  least 50 feet above the historical high water table.  [40
             CFR § 761.75(b)(3)J.  The very  minimal amount of leachate that could
             result from a properly designed  and implemented
             solidification/stabilization  remedy would not result in excessive risk to
             human health or the environment.  This determination is supported by the
             groundwater sampling results, the treatability study,  and the soil
             stabilization/solidification  durability assessment.  Waiving this requirement


FROD.7/96                           .      66

-------
             will not present an unreasonable risk of injury to health or the environment
             even though not located 50 feet above the high water table.

       •      Leachate Collection. This standard describes methods for collection and
             analysis of leachate produced by the landfill.  [40 CFR § 761.75(b)(7)].
             The amount of leachate produced from a properly designed and
             implemented solidification/stabilization remedy would be minimal because
             precipitation would travel around, rather than through, the treated soils.
             Additionally,  as shown in the treatability study, the concentration of PCBs
             in the leachate is expected to be low (the average concentration of PCBs in
             8 treatability study TCLP samples was 0.26 //g/L, as compared to the PCBs
             MCL of 0.5 /*g/L).  The combination of low volumes of leachate and low
             PCB concentrations within the leachate make it appropriate to waive this
             requirement because such a waiver will not present an unreasonable risk of
             injury to human health or the environment.

       •      Chemical Waste Landfill Operations. Operation requirements contained in
             40 CFR § 761.75(b)(8) are not applicable to the TSCA landfill on this site
             because no liquid or other types of wastes other than the solidified soils
             and low concentration PCB soils will be placed in it before final closure.

       •      Fence. Wall or Similar Device.  The requirement, contained in 40 CFR §
             761.75(b)(9)(i); to place  a fence, wall or similar device around the landfill
             will not be waived unless the solidified soil mass is designed and used as a
             building foundation or it is paved over for a parking lot A waiver of fence
             or other access barrier is appropriate under these two scenarios because
             access to unauthorized persons and animals would be  effectively prohibited
             by the building or pavement.

Based on the evidence presented in the remedial investigation and feasibility study and
other information contained in the administrative record for this Record of Decision, it
has been determined that waiving these requirements will not result in an unreasonable
risk of injury to health or the environment from PCBs.

Waste Shipment

Shipment of wastes would be conducted as part of debris, and potentially LNAPL
disposal.  This debris and wastes will be shipped pursuant to Department of
Transportation rules and regulations regarding transport of hazardous waste, if
applicable.  All off-site facilities will be in compliance with the off-site Disposal Rule (40
CFR 300.440)
FROD.7/96                      '           67

-------
 Repair of Erosion Control Wall Along Ship Creek

 The erosion control wall constructed during the Removal Action along Ship Creek will
 be repaired and, where needed, reconstructed.  Repair and maintenance of this structure
 is needed to meet the goals of the Floodplain and Protection of Wetlands Executive
 Orders, as well as, to ensure protection of the TSCA landfill once constructed.  Repair
 and, where necessary, reconstruction of the erosion control wall must comply with the
 substantive requirements of Section 404(b)(l) of the Clean Water Act and its
 implementing regulations.

 Flood Evaluation

 As part of Remedial Design a study will be conducted to evaluate the 100 year and 500
 year flood potential for Ship Creek ,and potential impacts on the site.  This  study will
 produce an updated flood map depicting the  100 year flood plain and 500 year flood
 plain for the site-  The results of the study will be used to design appropriate controls to
 prevent damage to the landfill from flooding.

 Institutional Controls

 In addition to the remedial actions used to treat COCs, institutional .controls would be
 used to prevent unacceptable exposure to contamination remaining at source areas at
 concentrations above acceptable levels. Institutional controls for soil left on-site that
 contains greater than 1 mg/kg PCBs were selected following EPA guidance for long-term
 management controls of CERCLA PCB sites.  Specific controls will include restrictions
 limiting future land use, preventing groundwater use, and limiting site access.  EPA
 guidance suggests selecting institutional controls for solidified PCBs based on mobility
 (TCLP) testing and exposure potential.

 Deed Notice and Land Use Restrictions

 A deed notice will be recorded on the title records for the site, if possible, and will notify
 any subsequent purchaser and/or successor in interest that the property is subject to a
 CERCLA Record of Decision.  The selected  cleanup levels for the COCs are based on a
 future industrial land use scenario. Consequently, land use restrictions must be
 implemented at the site to assure that no residential land uses, or commercial uses with
 potential chronic exposures of children (i.e., day care center) are allowed. To assure
 long-term protectiveness, the land use restrictions shall run with the land, bind  all
 successors in interest, and be recorded in the  property records. The "objectives of the land
use restrictions are:

       •      Ensure that site use continues to be industrial or commercial and prevent
             use of the site for commercial developments that involve potential chronic
             exposures of children to soil (e.g., use of the site for a day care center);


 FROD.7/96                     '            68

-------
       •     Restrict activities at the site that could potentially impair the integrity of
             the TSCA landfill; and
       •     Prevent movement  of soil containing greater than 1,000 mg/kg lead or
             10 mg/kg PCBs to the surface or within the top foot of soil where chronic
             long-term worker exposures could occur.

 Groundwater Use Restrictions

 Groundwater use restrictions are  necessary to prevent the installation of groundwater
 supply wells at the site. The property interest implemented to assure acceptable future
 land use shall include provisions for restricting use of groundwater underlying the site for
 any purpose.

 In addition, to the recorded restrictions all available regulatory controls shall be
 undertaken by providing written notification of restrictions and site conditions to local,
 regional, and state agencies, departments, and utilities. The property owner(s) will be
 responsible for providing these  restrictions.

 Access Restrictions

 Access to all areas impacted by soil contamination shall be limited during the
 construction of the remedial action.  Access to the landfill should be prohibited to the
 general public and limited to long or short-term workers in compliance with 40 CFR §
 761.75(b)(9)(i), which requires a six foot woven mesh fence, wall, or similar device.
 However, if the solidified soil mass  is designed and used as a building foundation or
 parking lot, this requirement may be waived. Long term public access will be limited to
 those areas of the site where surface contamination of greater  than 1 mg/kg PCBs
 remains after all excavation, treatment, and disposal is complete.  Public access will be
 limited by installing and maintaining a  six foot fence, or similiar structure.

 Groundwater Monitoring

 Ground water monitoring for PCBs and metals shall be conducted twice a year for the
 first two years of operation and may be reduced to annually thereafter with approval of
 EPA in consultation with Alaska  Department of Environmental Conservation for a
 minimum of ten years. After ten years an assessment of the groundwater data will be
 conducted to determine whether groundwater monitoring is still required or whether  the
frequency will be altered.

 Groundwater monitoring would be conducted to assess the effectiveness of the remedy
for protecting groundwater.  The  groundwater standards that are to be achieved are the
MCL and action level for PCBs and lead, 0.5 ug/L and 15 ug/L respectively.
FROD.7/96                                 69

-------
Monitoring of groundwater down gradient of the landfill for PCBs (EPA method 8080),
lead (EPA method 6000/7000), pH, specific conductance, and chlorinated organics (40
CFR § 761.75(b)(6)((iii)), or methods with equivalent detection limits and accuracy will
be conducted to ensure the landfill is not contributing contamination to groundwater, nor
altering groundwater conditions.

Stormwater Management

The site will be graded to prevent surface water discharges to Ship Creek.  Site storm
water structures will be designed to meet the requirements of 40 CFR § 761.75(b)(4)(ii),
and constructed to prevent contaminated discharges of storm water to Ship Creek and
prevent the transport of contaminated sediments off-site, including to Ship Creek.

Operation and Maintenance

The remedy will be operated and maintained for as long as the stabilized soils (landfill)
remains on-site.  Operation and maintenance of the remedy will include:

      •      Maintenance of the landfill to ensure that it  retains its structural integrity^
             and prevents release of PCBs and lead through any of  the following
             mechanisms: erosion (including flood and seismic events), leaching,
             excavation;
      •      Maintenance of the rip rap erosion control wall  along Ship Creek.  The
             erosion control wall will be inspected once a year for the first five years
             and after flood and seismic events and extreme precipitation events defined
             as 24-hour, 25-year storms;
      •      Maintenance of a six foot (minimum) woven mesh fence, wall or similar
             device or other means to prevent unauthorized access to the site, if
             deemed necessary after remedial design.

10.0  STATUTORY  DETERMINATIONS

The selected remedy  satisfies the statutory requirements of Section 121 of CERCLA.
The following sections discuss how the selected remedy meets these requirements.

10.1  Protective of Human Health and the Environment

The selected remedy  is protective of human health and the environment. The existing
exposure pathways will be eliminated by preventing  inhalation, dermal contact, and
ingestion of the COC's through treatment and containment. Site risks will be reduced
to within the  1E-4 to  1E-6 risk range for carcinogens and the Hazard Indices will be  less
than 1.0 for non-carcinogens in an industrial land-use scenario. No unacceptable short-
term risks or cross media impacts will be caused by  implementation of the remedy.  The
FROD.7/96                                70

-------
 selected remedy is the best alternative for the site because it is cost effective, reliable,
 and allows future use of the site.

 10.2   Applicable or Relevant and Appropriate Requirements

 The selected remedy will comply with all ARARs and, based on the administrative
 record, justifies waiving certain TSCA landfill requirements as discussed in Section 9.1
 above. The chemical-specific, action-specific, and location-specific applicable or relevant
 and appropriate requirements (ARARs) that will be attained are:

       Clean Water Act, 33 U.S.C. § 1313 and 40 CFR § 131.36(d)(12) are applicable for
       preventing future releases to Ship Creek, establishes and implements the National
       Toxics Rule, and sets water quality standards for Alaska.

       40 CFR § 141, Subpart B and F,  the Safe  Drinking Water Act Maximum
       Contaminant Levels are  applicable and Maximum Contaminant Level Goals are
       relevant and appropriate, establishes cleanup standards for metals and organic
       compounds, including PCBs, in ground water.

       Toxic  Substances Control Act, 15 U.S.C. § 2601 et se^ and 40 CFR §§ 761.60
       and 761.75(b),  (except the waived requirements as described in section 9.0), is
       applicable for the on-site disposal of PCBs.

       Clean Water Act, 33 U.S.C. § 1311, 40 CFR § 122.26 is applicable, direct
       discharges must meet technology-based standards, and storm water regulations for
       controlling discharges associated with industrial or construction activities.

       Clean Water Act, 33 U.S.C. § 1314(b)(l) and 40 CFR Part 230, substantive
       requirements for dredge  and fill requirements in waters of the United States is
       applicable for repairing the  erosion control wall.

       40 CFR § 261.24. RCRA Characteristic Hazardous Waste Determination is
       applicable for identifying soil and debris that must be managed as hazardous
       waste  (i.e. lead).

       40 CFR 264, Subpart C,  Standards for Owners and Operators of Hazardous Waste
       Treatment, Storage, and  Disposal Facilities; Preparedness and Prevention is
       applicable for staging and conducting the remedial action.

       40 CFR 264.310(a)  RCRA Subtitle C Landfill regulation is relevant and
       appropriate for the  cover design of the landfill, if appropriate.
FROD.7/96                                 71

-------
       40 CFR 268, RCRA Subparts C and D, Prohibitions on Land Disposal and
       Treatment Standards are applicable to the disposal of Characteristic and
       California List wastes, including contaminated debris.

       Alaska Air Quality Regulations 18 AAC Chapter 50 for dust suppression and PCB
       emissions is applicable.

       Executive Order 11988, 40 CFR 6, App. A, is applicable for action within
       floodplains, and to avoid adverse effects, minimize potential harm, restore and
       preserve natural and beneficial values.

       Executive Order 11990 Protection of Wetlands is applicable for activities in
       wetlands or which could impact wetlands.

       Off Site Disposal Rule 40 CFR 300.440 is applicable for disposing of
       contaminated materials  off site.

       To-Be-Considered (TBC) Guidances and Policies:

       40 CFR Part 761, Subpart G, TSCA PCB Spill Cleanup Policy.

       Guidance on Remedial Actions at Superfund Sites with PCB Contamination,
       OSWER Directive 9355.4-01.

10.3   Cost Effectiveness

The selected remedy affords overall effectiveness proportional to their costs.  The
selected remedy provides the best long-term permanence and risk reduction by treating
the mobility of the COCs and preventing exposure via containment.

10.4   Utilization of Permanent Solutions and Alternative Treatment Technologies to the
       Maximum Extent Practicable

EPA has determined, by utilizing the nine criteria of CERCLA, that the selected remedy
represents the maximum extent to which permanent solutions and treatment technologies
can be used cost-effectively at the Standard Steel and  Metals Salvage Yard Site.  Of
those  alternatives that are protective of human health and the environment and comply
with ARARs, EPA has determined  that the selected remedy provides the best balance in
terms of long-term effectiveness and permanence; reduction in toxicity, mobility or
volume achieved through treatment; short-term effectiveness; implementability; cost; and
the statutory preference for treatment as a principle element and considering state and
community acceptance.
FROD.7/96                                72

-------
The selected remedy will provide for permanent containment of the contaminants of
concern. Greater protection could have been achieved by transporting the wastes off-
site. However, because Alaska does not have chemical or hazardous waste treatment or
disposal facilities, this option was deemed less implementable, too costly, and along with
increased short-term risks, would not have reduced the risks substantially more than on-
site treatment and containment.

10.5   Preference for Treatment as a Principle Element

The preference for treatment is satisfied by the selected remedy because EPAfs removal
action treated the principle threats and additional treatment is being implemented. The
treatment will immobilize lead and PCBs in soil as well as eliminate lead contaminated
soils as a Characteristic Waste, pursuant to RCRA.

11.0   DOCUMENTATION OF SIGNIFICANT CHANGES

No significant changes to the proposed remedy, as presented to  the public in the
Proposed Plan have occurred.  EPA altered Alternative 6, as presented in the feasibility
study, in proposing its preferred alternative to the public.  EPA  determined that the
subsurface cleanup standard should be 10 mg/kg for PCBs instead of 50 mg/kg. This
alteration was deemed necessary to ensure future releases of hazardous substances from
the site would not occur.  The change is not anticipated to result in a significant change
in estimated costs for the remedial action.

Additionally, the feasibility  study and the Proposed Plan incorporated the Removal
Action as a common element of the analysis of alternatives. The Removal Action
included the construction of an erosion control wall along Ship Creek.  In describing the
selected remedy, EPA has more specifically included a requirement that the erosion
control wall  be repaired and maintained.
FROD.7/96                                73

-------

-------
                                               ELMENDORF
                                             AIR FORCE BASE
    PORT OF
  ANCHORAGE
                                                STANDARD
                                                  STEEL
 :  —' n i p (^ r c c f     ,
DOWNTOWN
                                    Alaska  •
                                    Anchorage /  Canada
                            SITE LOCATION MAP

                         STANDARD STEEL & METALS SPTE
Figure 1-1
            Woodward-Clyde Consultants

-------
                                         (based on Anchorac.C Bovs
                                         Weliands Map. May 1908)
         Interpolated Water Level Coniours
         From HEC-2 Compuior Model
        FLOOD PLAIN AND WETLANDS MAP

               STANDARD STEEL & METALS SITE
Woodward-Clyde Consultants
Figure 1-2

-------
                                                                                             O-*- Suxm[>»»n
i  I^L^LAJ:J,:J~LJ:J;^^^
                                                                                                       i—f-i-i- t~r
                                                                                                   RAILROAD AVENUE
                                              in
                ICono«,l« Sl*b
                                                        ^^^{il^1^^

                                                                     i
                                                       L; :L; : : ilt: : itjEjijin?      ..•••••..        siong.ArM

                                                       tif. f. : •] 'ifl lirlS-jpr    /' V^»-	»	Po'm.r Sll. O« Hydfiullc
                                                       h. i f: : : Hh : Jpipiy      •*•..•'          Cfinh«f Building
^\
•%*?
*<•' Suind.i/d S ool
ON.GO T.a.W
i::*--i





I
&
1







rin«lerm«r
long* Ar»t
	 B.n.,v
Slorigt X...
"I'TlLu.,
T^tlBn-,
/*.



\-
STREE

\-
<
>-
D
X
<
>-



r~

LI
i_

r

sc
r
/ .

/
1
	 -L 	 LEGEND
FBT-FT]
                                                                                                                                     cvl >u«ly Covered
                                                                                                              LOCATIONS OF HISTORICAL
                                                                                                           OPERATION AND STORAGE AREAS

                                                                                                               STANDARD STEEL & METALS SFT,:
                                                                                                   Woodward-Clyde CorwuHarrt*
Figure  1-3

-------
  - Rock Rip-Rap Wall Constructed
    During Removal Action to
    Control Erosion and to Prevent
    Releases from Site Into Ship
    Crook
             CURRENT SITE STATUS
            (POST-SCRAP REMOVAL)
             STANDARD STEEL & METALS SITE
Woodward-Clyde Consultants
Figure 1-4

-------
                                           iabie 3-1
                    SUMMARY OF MEDIA AND CHEMICALS OF CONCERN
Media of Concern                           Chemicals of Concern
Surface and Subsurface Soil                    PCBs
                                           Lead
                                           Dioxins and Furans (co-located with PCBs)

-------
.d-
                      GATE
                                         r
                     j<0036 •    <0.090t  <0035
                      0 34  *     017 •
THEATER GUILD
BUILDING

                                                                                          - FOF MER
                                                                                              MERATOR
                                                                                              DING   I
|           UA.C ^     |

   .   .   .   -     --• • —1,
                                                                                              © STORM DRAIN

                                                                                             RAILROAD AVENUE
                                                                                                 0.22 •
     APPROXIMATE SCALE IN
                                                                                                                      LEGEND

                                                                                                             •  < 10 mg/kg PCBs
                                                                                                             A  10-25mg/Vg/PCBs
                                                                                                                25 • 50 mg/kg PCBs
                                                                                                                50-150 mg/kg RGBs
                                                                                                             ©  150 • 500 mg/kg PCBs
                                                                                                                > 500 mg/kg PCBs
                                                                                                                Excavated Area with Clean Backfill
                                                                                                             OB Sediment Sampio
                                                                                    CONCENTRATION OF PCBs IN SURFACE SOIL
                                                                                               STANDARD STEEL & METALS SITE
                                                                                   Woodward-Clyde Consultants
                                                                                                                 Figure 5-1

-------
                                                                              Q STOHM DRAIN

                                                                             RAILROAD AVENUE
                                                                                                     LEGEND

                                                                                                     < 10 mg/kg PCBs
                                                                                                     10 - 25 mg/kg/PCBs
                                                                                                     25-50 mg/kg PCBs
                                                                                                 •   50-150 mg/kg PCBs
                                                                                                 ©   150 • 500 mg/kg PCBs
                                                                                                     > 500 mg/kg PCBs
                  200
               I _'" ~. 1
APPHQXIMATF SCALC IN
CONCENTRATION OF PCBs IN SOIL
WITHIN THE WATER TABLE ZONE
    STANDARD STEEL & METALS SITE
                                                                 Woodward-Clyde Consultants
                                  Figure 5-2

-------
    /
                O STORM DRAIN


              RAILROAD AVENUE
                      _GAT£

                          I
.if
            	]        -y
             69 •
                    49    «i3o     I:
                          i  no •  ^r

                        »"  .35     '
                          L-*-15	I -
                              H      G     - F--
         A
                                                                                                                        LEGEND
                           t   < 500 mg/kg Load
                           A   500- 1000 mg/kg Load
                           •   1000 • 3000 mg/kg Lead
                           *   >3000 mg/kg Lead
                              Excavated Area with Clean Backfill

                         Note: Data obtained during EPA's removal
                         action was also used in constructing contour
                         lines. The dala is included in Appendix G.
                   100	 200

           APPROXIMATE SCALE IN FEET
CONCENTRATION OF LEAD IN SURFACE SOIL
            STANDARD STEEL & METALS SITE
                                                                                  Woodward-Clyde Consultants  ^r
                                          Figure 5-3

-------
                 IHT
                                W'V»
                               won 4
^                                      IJLJ.
      _1"1	J" ~r~~     ""—
                                                                       0     	lOOh

                                                                         SCALE
                                                                    = Monitoring Well
                                                                      Wells 1-12 EPA
                                                                      Wells 13-29WCC

                                                                  A  = Sediment Sample Location

                                                                 cs-261 - Sample Number
                                                                      For PCB/Lead Analysis  .

                                                                 es-003 - Sample Number
                                                                      For Microtox Analysis
                                                                     s Runoff Deposition Samples
                                                                      In Drainage

                                                                     =: Outfall Surface Water Sample
                                      MONITORING WELL AND SHIP CREEK
                                        SEDIMENT SAMPLING LOCATIONS
                                            STANDARD STEEL & METALS SITE:.
                                Woodward-Clyde Consultants   w
I Figure 5-4

-------
                                Table 6-1
   RESIDENTIAL RISK BASED CONCENTRATIONS, BACKGROUND
CONCENTRATIONS, AND MAXIMUM CONCENTRATIONS OF PCOC'S
                    IN SOILS AND GROUND WATER
Chemical
SOIL
PCBs
Chrysene
Benzo(b)fluoranthene
Benzo(k)fluoranthene
Benzo(a)pyrene
Indeno( 1 ,2,3-c,d)pyrene
Dibcnzo(a,h)anthracene
2,3,7.S-tetrachlorodibcnzo-p-
d«oxin(2,3,7,S-TCDD)
Cadmium
Chromium
Copper
' Lead
GROUNDWATER
Tetrachloroeihylene
1 ,2,4-Trichlorobenzcne
Arser.ic
Cadr-iuni
PCB>
Lead
Risk Based
Concentration
mg/kg in soil &
mg/L in
groundwater

0.008
0.009
0.009
0.009
0.009
0.009
0.009
0.0000004
10
136.7
1000
500

0.002
0.002
0.00005
0.02
0.00001
NA
Background
Concentration
mg/kg in soil &
mg/L in
groundwater

NA
" NA
NA
NA
NA
NA
NA
NA
1.13
19.80
14.85
6.89

NrX
NA
0.010
0.0001
NA
0.047
Maximum
Concentration*2*
mg/kg in soil &
mg/L in
groundwater

380
7.8
4.9
1.6
3.8
2.5
0.68
0.00172
11.60
151
3,320
7,200

0.0075
0.024
0.0159
0.0291
0.000032
0.0031 J
Maximum
Concentration
(EPA Removal
Action) nig/kg
in soil & nig/L in
groundwater

10,600
NA
NA
NA
NA
NA .
NA
NA
128
1.570
7.700
4^500

0.043 .
0.39
ND
ND
2.025
0.00076
             -• nl from Standard Steel Human Health Rtsk Assessment Report  Background

            .-- ::om iiinicndorf Al:H OU-S Rcpon.

             . ^rtuindxvaicr. I'hciscs 1 :uu! 2 (unfilicrcd ;ujd filtered scuwplcs) data a/e usecJ tor

            : " • ."iiK>r<>)vn/ene  IMiases 2 (unhllcrcd and Jillercd samples) ai:-,l 3 daia arc u-,ed

              . cniraiion\ ol melalb and i'l 'i ^s

            : •'•'-. reuu»\\il action uu'eslu'.ations

-------
                                               Table 6-2
                        PARAMETERS USED TO CALUCULATE RISK-BASED SCREENING
                                             CONCENTRATIONS

                                                           t'nrnniclcr/Rcnsonablc Maximum Exposure Values
Scenario/
» led in
Receptor
Soil Residential/
Adult
Residential/
Child
Exposure
Route
Ingestion

Ingestion

Target
Cancer Risk
Level
I.OOE-07

I.OOE-07

Turret
Hn/nnl.
Index
O.I

O.I

digestion
Rate
100 mg/day

200 mg/day

Exposure
Frequency
((Jays/year)
350

350

Exposure
Duration
(years)
24

6

Body
Weight
(kg)
70

15 ,.

Averaging Time
(days)
25,550 (Carcinogen)
10,950 (Noncarcinogen)
25,550 (Carcinogen)
10,950 (Noncarcinogen)
Groundwaier   Residential/    Ingestion
             Adult
I.OOE-06
O.I
2 L/day
350
30
70      25,550 (Carcinogen)
      10,950 (Noncrrcinogen)

-------
                                                             Table 6-3
                                             SUMMARIES OF RMK HAZARD INDICES

i '. x POM it c. Pathway
Soil Ingcstidn
Soil Dermal Contact
Paniculate Inhalation
( j roundwater Ingestion
CJroundwatcr Dermal
Contact
Inhalation of Volatile
Organic Com pounds.. During
Showering
Total I la/^'ird Indices
. Short-Term Worker
AOC 1
1.8
1.3
2E-5
NA
NA

NA
X

3.1
AOC 2
1
0.8
4E-6
NA
NA

NA


1.8
AOC 3
0.3
0.2
4E-6
NA
NA

NA


OJ5
Long-Term Worker
AOC 1
1.4
3,9
NA
NA
NA

NA


5.3
AOC 2
0.1
0.5
NA
NA
NA

NA


0.6
AOC 3
0.3
0.7
NA ,
NA
NA

NA


1
Resident
AOC I1
10.6
8.5
NA
0.6
0.03

0.01


19.7
AOC2b
1
1.1
NA
1.6
0.1

NA


3.8
AOC 3
2
1.6
NA
NA
NA

NA


3.6
NA   Not applicable




      Includes ha/.ard indices attributed to MW-21 groundwatcr exposure pathways




      Includes ha/ard indices attributed to MW-13 groundwaler exposure pathways

-------
                                                     Table 6-4
                                   SUMMARIES OF RME EXCESS CANCER RISKS
Exposure Pathway
Soil Invest ion
Soil Dermal Contact
Paniculate Inhalation
( irouiul-A.iii t 1 ivrsi i >n
( i round u.u or ( Vr tru!
(.'ontact
Inhalation of Volatile
Organic Compounds During
Showering
Total Excess Cancer Risk
Short-Term Worker
AOC 1
2IZ-5
1E-5
1E-10
NA
NA

NA
3E-5 V
AOC 2
9E-6
6E-6
1E-10
NA
NA

NA
1E-5
AOC 3
3E-6
2E-6
4E-12
NA
NA

NA
5E-4
Long-Term Worker
AOC 1
3E-4
8E-4
9E-8
NA
NA

NA
1E-3
AOC 2
. 4E-5
1E-4
7E-8
NA
NA

NA
1E-4
AOC 3
5E-5
1E-4
NA
NA
NA

NA
1E-4
Resident
Aocr
3E-3
2E-3
1E-7
lE-4b
5E-6

7E-8
5E-3
AOC 2
3E-4
3E-4
1E-7
NA
NA

NA
6E-4
AOC 3
5E^4
4E-4
NA
NA
NA

NA .
9E-4
NA    Not applicable




       Includes risks attributed to MW-21 groundwater exposure pathways




       Preliminary groundwater data for October 1993 reports PCB detections in MW-18 and MW-19 in the 3E-5 cancer risk range

-------
                                    Table 6-5
            SUMMARY OF ESTIMATED EXCESS CANCER RISKS
             ASSOCIATED WITH lOmg/kg PCB CLEANUP LEVEL
Estimated RME risk: Long-term
worker—combined dermal contact
with ingestion00
Notes:
(1) Expressed as 2,3,7,8-TCDD equivalent
(2) The procedure used to calculate risk is described in Appendix A
(3) Risk for cPAHs is ingestion only; EPA has not recommended absorption factors for dermal uptake
   of PAHs and states that further research is required on the bioavailability of PAHs in soil

-------
                    -j STANDARD STEEL
                     OFFICE
       AREAS OF  CONCERN  .
STANDARD  STEEL RISK ASSESSMENT
     ENVIRONMENTAL MANAGEMENT,  INC.

-------
                                                                  1    e STORM DRAIN


                                                                  |   RAILROAD AVENUE
                                                                  *v ;*s•..**£.:. -<<*»:fttt>*'V>J\«»y«y4»)B»-:«MHmiJ
   GATE -x
                                                                            r
                                                                      PRINCIPAL THREAT
                                                                      SOILS IN STOCKPILE
                                                                      TREATED. REMAINING
                                                                    A SOIL IN STOCKPILE
                                                                    ^CONSOLIDATED
                                                                      UNDER CAP
                                                                     8
         H     G
                             • SHIP CREEK
       ";.."...-"	]
: SC.Al.f IN FFFT
                                                                                                           o
                                                                                                             '
                                                                                                       LEGi:ND
                              Capped Area

                         ^^ Areas to be Excavated
                         W& to Moot Depth and
                              Consolidated Under Cap

                         Hgij Principal Threat Soil Area •
                              to be Excavated to 1-foot
                              and Treated

                         Rfffl Principal Threat Soil Area •
                              to be Excavated to Ground-
                              water Table and Treated

                         --• Slurry Wall
                                                                                                    V
AREAS TO BE REMEDIATED - ALTERNATIVE 4
            STANDARD STEEL & METALS SITE
                                                                   Woodward-dyd* Consultant*
                                            I Figure 8-1

-------
                                                                       © STORM DRAIN


                                                                      RAILROAD AVENUE
    t,*lt -,     I
 100  	LOO

ii SCAI I IN rri i
                                                                            r
                                                                       PRINCIPAL THREAT
                                                                       SOILS IN STOCKPILE
                                                                     A TREATED BY
                                                                     4 THERMAL
                                                                       DESORPTION.
                                                                       REMAINING SOIL
                                                                       IN STOCKPILE
          H     G
                                                                                                         LEGEND
                            Area to be Excavated to 1-foot
                            Depth  and Consolidated in   .  .
                            Upland Areas

                            Areas  to be Excavated to
                            Groundwater Table and Treated

                            Areas  to be Excavated to 1 -foot
                            Depth  and Treated or Buried if
                            PCB Concentration < 50mg/kg

                            3-foot  Smear Zone Around
                            Groundwater Table Excavated
                            and Treated

                            Top 1-foot and 3-foot Smear Zone
                            Around Groundwater Table
                            Excavated and Treated

                            All Areas Delineated by Dashed
                            Lines are PCB Principal Threat
                            Soils and are Treated by Thermal
                            Disorption
AREAS TO BE REMEDIATED - ALTERNATIVE 5
            STANDARD STEEL & METALS SITE
                                                                 Woodward-Clyde Consultants
                                         Figure 8-2

-------
     © STORM DRAIN


    RAILROAD AVENUE  '
                                      LEGEND
                              Area to be Excavated to 1-foot
                              Depth and Consolidated in
                              Upland Areas

                              Areas to be Excavated to
                              Groundwater Table and Treated

                              Areas to be Excavated to 1-foot
                              Depth and Treated or Buried if
                              PCB Concentration < 50 mg/kg

                              3-foot Smear Zone Around
                              Groundwater Table Excavated
                              and Treated

                              Top 1-foot and 3-foot Smear Zone
                              Around Groundwater Table
                              Excavated and Treated
            AREAS TO BE REMEDIATED -

          .ALTERNATIVES 6, 7, 8 9, AND 10
             STANDARD STEEL & METALS SITE
Woodward-Clyde Consultants
Figure 8-3

-------
                                       Table 9-1
                               Soil Cleanup Level Summary
PCB (mg/kg)
<1
1-9.9
10-49
50 or greater
Lead (mg/kg)
<500
500-999
NA
1000 or greater
Action*
No Action
Flood plain soils only, .
excavate and consolidate elsewhere on-site
Excavate and consolidate soils in onsite TSCA landfill
below 1 foot of landfill surface
Excavate soils and treat by solidification/stabilization, then
dispose in a on-site TSCA landfill. Treated soils cannot be
placed in top foot of landfill unless concentration is less
than 10 mg/kg PCBs or within the groundwater fluctuation
zohe.
* Groundwater fluctuation zone will be backfilled with soils containing less than 1 mg/kg PCBs.
All other excavated areas will be backfilled with soils containing less than 10 mg/kg PCBs. Soils
may not be stockpiled, and subsequently backfilled, in a manner which reduces the
concentrations below 10 mg/kg, or to avoid treatment.

-------

-------
                           RESPONSIVENESS SUMMARY
                          STANDARD STEEL AND METALS
                                SALVAGE YARD SITE
       The purpose of this responsiveness summary is to summarize and respond to public
comments submitted regarding the Proposed Plan for the remedy at the Standard Steel and
Metals Salvage Yard site located in Anchorage, Alaska.  The public comment period for the
Proposed Plan was held from March 18, 1996 through April 17, 1996.

       This responsiveness summary meets the requirements of Section 117 of the
Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA)
as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA).

       Four verbal comments were received during the April 10,1996 public meeting held in
Anchorage, Alaska. All four comments supported the selection of stabilization/solidification as a
final remedy for the site.

       Six written comments were received postmarked by April 17, 1996. These comments are
listed and responded to in the following text. Similar comments have been combined and the
text is paraphrased due to the length of comments. All comments are included in the
Administrative Record.

       Two comments were received after the end of the public comment period. These
comments are very similar and reflect the same concerns as those submitted by Greenpeace and
the Anchorage Waterways Council. EPA will address these comments in this responsiveness
summary.

Comment 1:  Chugach Electric Association commented on EPA's alteration of the PCB
subsurface soil cleanup level from 50 mg/kg to 10 mg/kg. Chugach commented that there was
insufficient notice about the change because it was not evaluated in the feasibility study.
Chugach also commented that it is concerned that EPA's proposed alteration of Alternative 6
may invalidate the results of the FS. Of particular concern to Chugach is the effect on the cost of
implementing the additional excavation. Chugach also notes that there is little legal basis for
selecting a 10 ppm cleanup level. Chugach mentioned that if EPA limits the extent of this
alteration to the three known areas of subsurface PCB contamination that their above concerns
"will not be triggered". Chugach also stated that they look forward to working with EPA on
implementing the remedy.

Response:     In the Proposed Plan EPA presented the preferred alternative to the public with a
10 mg/kg cleanup level for both surface and subsurface soils, instead of a 10 mg/kg  surface and
50 mg/kg subsurface cleanup level, as presented in the FS. The change from the FS was

                                          1

-------
 identified and explained in the Proposed Plan and during the public meeting. EPA supplied
 sufficient notice to the public and informed them of why the change was proposed. No other
 comments were received objecting to the proposed subsurface cleanup standard.

       Chugach's concern with the alteration of the price is warranted and EPA did consider it in
 proposing the alteration from the FS. In EPA's judgment, the change in volume to be excavated
 will not have a significant impact on actual costs of implementing the remedy.  Since soils
 between lOppm and SOppm are only required to be consolidated in the TSCA landfill, as is
 proposed with surface soils, and not treated with stabilization the only impact will be on costs of
 excavating and backfilling. The cost of excavating soils is estimated (FS estimates) at $25.00/cy
 and backfilling and compaction at $8.00/cy.  The cost of increasing subsurface excavations by
 1000 cy is estimated at $33,000.  Even with an additional 3000 cy of subsurface soils requiring
 excavation the increase in cost will be less than $100,000, which is approximately 2% of the low-
 end estimation of the preferred alternative.  Additionally, the small increase in costs resulting
 from additional excavation and backfilling would be less than the costs of monitoring and
 maintenance of the cap that would have been required over areas of the site that would have had
 50 mg/kg in the subsurface.

       Chugach's comment about the legal basis of selecting a 10 mg/kg cleanup level is noted.
 There is no federal or state ARAR that^sets PCB soil cleanup levels. The cleanup levels at this
 site were based on residual risk, long-term protection, and consideration of cleanup standards
 contained in the TSCA Spill Policy and Superfund PCB Guidance and policies. Although the
 TSCA Spill Policy may not require 10 mg/kg beyond 10 inches, EPA has the discretion to select
 a more stringent cleanup level.  We selected 10 mg/kg as the cleanup level for  PCBs because
 commercial activities on the site and the nature of the climate in Anchorage cast doubt on the
 effectiveness of a one foot soil layer over soils containing 50 mg/kg at depth. EPA decided that
 either a substantial cap (asphalt, geomembrane) would be needed to prevent exposure to soils
 with up to 50 mg/kg PCBs, or an alternative was to excavate soils above the surface soil cleanup
 level and contain with other soils exceeding the cleanup level. Containing moderately
 contaminated soils with the treated soils was determined to be more cost effective and practical
 than capping most of the site and maintaining that cap forever.

       Regarding the extent of subsurface soil excavations above 10 mg/kg PCBs. EPA
 anticipates, based on current data, that these areas are limited to four locations on-site.  EPA's
 alteration is based on the need to prevent future releases from the site. Considering that
 subsurface characterization is limited and additional sampling may determine significant areas of
 subsurface contamination beyond the three areas identified in the RI/FS, EPA can not put a limit
 on the need for addressing these soils. However, EPA will reevaluate the remedy if very
 significant areas of subsurface contamination are discovered that would greatly increase volumes
to be excavated and contained. In that event, EPA will work with the participating parties
conducting the remedial action and the community to address these  soils in a protective manner.

Comment 2: Anchorage Waterways Council (AWC) submitted substantial comments regarding

-------
 the lack of information on current stream bed conditions and hydraulic characteristics of Ship
 Creek in the Administrative Record.  AWC does not support stabilization/solidification as the
 remedy at the site and can "concur only with options 9 or 10.   Main points raised by AWC are
 listed below.

        1)     Degree of aggradation of Ship Creek, a study is needed to quantify and qualify the
       degree of aggradation.

       2)     Ship Creek has been channelized in some locations ypstream of the site and
       significant urbanization may significantly alter the slug flow and flooding characteristics
       of Ship Creek.

       3)    . Dams located upstream may significantly affect the stream bed condition,
       gradient, and elevation. AWC states that" There appears to be a significant chance of
       catastrophic failure of one or both of the fish hatchery dams during a flooding event."
       This could significantly alter the  stream bed.

       4)     The Standard Steel site is located in an area which "will almost certainly be
       inundated by a 100, 500 or 1000 year flood event, just as it was in the flood of August
       1989." AWC raised concerns of changes in global weather patterns and that flooding and
       inundation will be more frequent.

       5)     EPA's evaluation  of remedial  options may contain errors regarding which options
       achieve long-term permanence and  that alternatives 2, 3, 5, and 6 must be included in the
       category  of alternatives which could be effected by catastrophic events.

       6)     EPA's evaluation  fails to  adequately consider the economic and health aspects of
       the release of site contaminants to Ship Creek.

       7)     AWC recommends EPA perform an  analysis of potential economic and health
       effects of a release  of contamination from this site. Also, that leaving these wastes on-
       site is in effect leaving an "environmental timebomb".
Response to points 1) ,2), 3), 4) and 5):     As part of Remedial Design a study of flooding
potential in the Ship Creek basin will be required. This study will evaluate the impacts of a 100
and 500 event on the site. The landfill and solidification mix will be designed to resist at a
minimum a 100-year flood event in accordance with TSCA landfill requirements. It should be
noted that there are common engineering solutions to designing structures in flood plains. The
fact that the structure contains PCBs and lead does not prevent the structure  from being designed
to withstand flooding, erosion or seismic events.

       The stabilized mass will immobilize the waste and not allow PCBs or lead to be released

-------
 from the site.  The solidified wastes and groundwater will be monitored.  If monitoring shows
 releases of hazardous substances above drinking water standards or site cleanup levels, such
 releases will be addressed.  It should be noted that significant transport of contaminated soils did
 not occur after the August 1989 flood event.  This is supported by sampling data from the EPA
 removal actions and comparison to RI/FS sampling.  The landfill will not be placed within the
 100 year flood plain.

       The  erosion control bank along the site's border and Ship Creek will be repaired and, if
 necessary, improved. This erosion control structure will be maintained as long as the landfill
 exists.

 Response to point No. 6:     Concerning Long-term effectiveness and permanence, EPA stated
 in the Proposed Plan (March 18,1996) that

              "Alternative 4 would require maintenance of a cap and containment measures
              forever, and therefore receives a low rating.  Alternatives 5,6,8,9, and 10 would all
              have a high long term reliability because the contaminants would either be
              removed from the site or solidified. Although the containment cell would require
              monitoring, there is sufficient  experience with solidification to predict that it
              would be reliable over time. Alternative 7 would remove most (90%) of PCBs,
              but would not provide as significant on-site controls  (constructed mechanisms) to
              prevent long term releases as Alternative 6. Potential releases from Alternatives 4
              and 7 would be caused by very significant site disturbances, such as earthquakes,
              flooding, or failure of land use controls."

       EPA does not disagree with AWQ's position that "Any" waste left on-site could (EPA
 emphasis added) be affected by catastrophic events or improper application of land use controls.
 However, CERCLA states that EPA is to evaluate risk based on reasonable land use scenarios
 and base remedies on reasonable assumptions. Flood and seismic events can be anticipated and
 the landfill designed to minimize releases associated with such events. All potential effects from
 global warming, acts of God, or war cannot be anticipated.  EPA considers the evaluation
 presented in the Proposed Plan as an accurate evaluation of which alternatives comply with the
 criteria of long-term protection and effectiveness, and that our assumptions and remedy is
 reasonable.

 Response to point No. 7: EPA has evaluated  effects of releases from the site and has determined
that there are no current releases from the  site. We have also determined that by implementing
this remedy  future releases will be highly unlikely. EPA strongly disagrees with the statement
that the wastes at this site are in effect an environmental timebomb.  Neither PCBs or lead are
mobile in water, substantial actions have been undertaken which have eliminated risks posed by
the principle threats at the site (PCB oils), and on-site containment versus offsite containment or
treatment poses fewer risks due to transportation.  Exposure through other pathways, such as
direct contact, inhalation, ingestion will be eliminated by solidification.

-------
Comment 3 and 4: Greenpeace and Bob French submitted the following comments
                 (comments were separate but similar enough to address together):

       1)     EPA stated the life expectancy of the monolith is approximately 30 years.  The
       commenters concern is that the short life expectancy is too short to ensure protection of
       environmental and human health. The commenter also states that this technology is
       untested in subarctic environments and that a GAO report states that EPA officials
       believe that technologies must be used multiple times under a variety of conditions before
       their cost and performance data become reliable and acceptable for cleanup decisions.

       2)     EPA has minimized the severity of pollution problems ensuing from the creek and
       that a DEC Site Summary for Standard Steel stated groundwater was contaminated with
       PCBs, lead, and tetrachloroethylene (not addressed in the Proposed Plan) and that
       sediments in Ship Creek are contaminated with PCBs.  The commenter feels the scope of
       the investigation was too limited to address impacts to offsite drinking water sources and
       bioaccumulation of persistent organochlorine contaminants downstream from the site.

       3)     EPA has not adequately considered the endocrine  disruption potential for the
       organochlorine chemicals in wildlife and humans.  EPA has not fully discussed the fate of
       dioxin/furan contaminated ash, and that the containers with the dioxin/furans are not
       secured.

       4)     Greenpeace feels that with "the serious uncertainties and lack of proven
       technology regarding the proposed remedy, the best solution to the problem is Alternative
       9- Offsite disposal.

Responses:

       1)    EPA stated during the public meeting that the "life expectance is at least thirty
       years.  We say it could go on indefinitely."  Stabilization (cement/concrete) technology
       has been employed for thousands of years and has a long history of data to draw from.
       The design of the containment cell will be for hundreds of years, and Institutional
       Controls will be required to ensure the remedy is maintained and changes in land use do
       not pose an unacceptable risk to human health or the environment.

             Regarding the GAO report, without knowing the report referred to and its context,
       EPA cannot directly respond to that statement. EPA has a national policy to promote the
       use of innovative technologies when they have a reasonable chance of providing a cost
       effective, efficient, and reliable treatment solution. Stabilization/solidification has been
       used at other Superfund cleanups, and  EPA has proposed  stabilization/solidification as an
       alternative remedial alternative for PCBs under the Toxic Substances Control Act,
       Resource Conservation and Recover Act and the Comprehensive Environmental
       Response,  Compensation and Liability Act.

-------
       EPA acknowledges the challenge of implementing this remedy in a subarctic
       environment. However, solidification has been implemented successfully at many
       Superfund Sites in the lower forty eight states which have similar climatic conditions as
       Anchorage, Alaska.

       2)     Both EPA and DEC were involved in the scoping of the RJ/FS and concurred on
       the scope of the RI/FS investigation.  EPA maintains that groundwater is not
       contaminated at levels which require remediation. The tetrachloroethylene contamination
       the commenter  is referring to was located onsite and only in one well. This does not
       constitute a situation requiring remediation of groundwater, nor does it necessitate a
       different remedial alternative. The selected remedy  includes monitoring of groundwater
       to ensure that there is no migration of contaminants  off-site.

              Ship Creek was evaluated by EPA, with the input by DEC and a Biological
       Technical Advisory Committee consisting of the U.S. Fish and Wildlife Service, Alaska
       Department of Fish and Game, Elmendorf AFB Natural Resource Trustee. This group
       concurred with  the conclusion that the Standard Steel site is not currently releasing
       contaminants to Ship Creek. Ship Creek is a heavily impacted waterway by many point
       and non-point sources.  There have been other PCB  spills adjacent to the creek and some
       directly into the creek as well as urban runoff, storm sewers and other unknown sources.
       It was decided during scoping that correlating past releases from the Standard Steel site to
       Ship Creek was impractical.

       3)     EPA did evaluate the impacts of dioxin/furans in the Baseline Risk Assessment.
       The assessment determined that dioxins/furans do pose a risk.  EPA is taking action to
       mitigate these risks by stabilizing/solidifying all soils containing dioxins/furans.  These
       soils are collocated with PCB soils requiring excavation  and treatment.

              The dioxin/furan contaminated equipment is  secured on site in a locked shipping
       container. This container is within the fence boundary and located on private property
       maintained by the Alaska Railroad Corporation.  Ash from the incinerator was placed in
       the shipping container with the incinerator equipment. The equipment and ash will be
       properly disposed off-site as part of the selected remedy.

       4)     EPA feels the uncertainty related to the effectiveness and reliability of
       stabilization/solidification is low and that remedial design will result in a protective long-
       term solution for the site. EPA feels that shipping large volumes of soils from Anchorage
       Alaska to a disposal facility in the lower forty eight states poses greater short-term risks,
       does not alter the long-term risks and would simply transfer the waste to another location
       at a substantial cost.

Comment 5:   The Municipality of Anchorage submitted a comment concerning erosion by Ship
Creek along the bank of the site. The commenter does not oppose the proposed alternative in

-------
 concept.

 Response:     The remedy will require an assessment of Ship Creek erosion potential and
 mitigation requirements. The remedy will include maintenance of the erosion control structure
 along the site bank.

 Comment 6:   Sears Roebuck and Co commented that the proposed plan for remediation of the
 site represents an effective and pragmatic approach to remediating the subject site.  However, the
 commenter has concerns with the selected 1000 mg/kg treatment level for lead.  The commenter
 feels it is "excessively conservative".  The commenter provided an Attachment entitled
 "Calculation of Lead PRO Using Bowers Et. Al. (1994) Model" This calculation results in a
 PRO of 7,850 mg/kg lead in soil.

 Response: EPA appreciates that the commenter supports the proposed remedy. The treatment
 level for lead is not solely driven by risk alone. Pursuant to the Resource Conservation Recovery
 Act, the lead present in soils at the site is considered a characteristic RCRA hazardous waste
 (waste code D008) when generated (excavated). Pursuant to RCRA Land Disposal Restrictions
 characteristic wastes must be treated prior to land disposal or obtain at Treatability Variance.
 Soils at the site failed the characteristic test (SW-846, TCLP) of leaching greater than 5.0mg/kg
 lead when the soil concentrations was ^s low as 780mg/kg (Table 2-10 of FS).  It was shown in
 the soil treatability tests that soils above 1700mg/kg lead would consistently fail the
 characteristic test and would be considered Hazardous Waste.

       Since  soils exceeding 10  mg/kg PCBs will be excavated and placed in the TSCA landfill
 and these soils have greater the than lOOOmg/kg lead, the presence of lead forces treatment of
 these materials prior to land disposal.

       The 1000 mg/kg cleanup level has been utilized at many other Superfund sites with an
 industrial land use. This level is considered protective by EPA in these circumstances. As EPA
 and the commenter noted an acceptable method of quantitatively evaluating the risk posed by
 lead to adults  at industrial sites is unavailable. The Bowers Et. Al. (1994) model is being
 evaluated by EPA for general application in the Superfund program. However, the model has
 not yet been generally  accepted in Superfund guidance and it was not being considered at the
 time the Baseline Risk Assessment was completed for this Site.

       EPA utilizes the Baseline Risk Assessment to determine whether an evaluation of
 remedial alternatives is warranted at a site. EPA does re-evaluate risks when new information
 becomes available. However, unless that new information demonstrates that a significant change
 (either greater or lesser risk) in risk from the previous risk assessment would occur, EPA does
not consider it necessary to delay cleanup and incur additional cost to revise the risk assessment
or reassess alternatives.

       EPA (Mark Maddaloni, EPA Lead Evaluation Workgroup, chair of the sub-committee for

                                           7

-------
 non-residential exposure) did a limited evaluation of the analysis Sears submitted using the
 Bowers Et Al. (1994) model and disagrees with two default assumptions used by Sear's
 consultant. First and foremost, EPA cannot support adjustment of the frequency of contact
 (FOC) to account for EPAfs default industrial exposure duration divided by a lifetime (i.e., 25
 years / 70 years). An elevated blood Pb level will reflect current exposure conditions and has
 nothing to do with the how long people tend to live. Rather than integrate the blood lead level
 over a lifetime, EPA is interested in exposure durations that could be limited to nine months -
 that duration representing the gestational period in which lead would be transferred from  mother
 to fetus.  Second, bioavailability is an issue. The value used by Sears (8%) represents a lower
 bound estimate in that it reflects conditions where bioavailability was measured during a  fed
 rather than fasted state. Absorption is much greater when lead is introduced to an empty stomach.
 A default value employed at the Leadville Superfund Site of 12% would be recommended.

       The Bowers Et. Al. (1994) model may be an appropriate tool for evaluating lead risks at
 non-residential sites. However, EPA does not think it would be in the best interests of the
 community, or the site to delay cleanup and conduct another evaluation of risks at the site, when
 the outcome would not likely be a significant change in cleanup level or cleanup costs. EPA
 considers a 1000 mg/kg cleanup level for lead appropriate at the site based on a qualitative
 evaluation of lead risks, previous remedial action levels at other Superfund sites, and the
 collocation of lead and PCBs at the sit^.

       It would be very expensive and delay cleanup to conduct TCLP tests on all soils prior to
 treatment to determine whether they fail the TCLP test, and it is impractical to separate the lead
 contaminated soils from the PCB soils. Therefore EPA will retain the lOOOmg/kg treatment level
 for lead contaminated soils.

 Late Comments: Two comments were received from the Sierra Club, Alaska Chapter and the
 Downtown (Anchorage) Community Council. There concerns  are that EPA does not have
 enough information for selecting stabilization/solidification as a final remedy  and groundwater
 and Ship Creek Sediments are contaminated and need to be addressed. They submitted similar
 concerns as the above comments regarding flooding and seismic events.

 Response: EPA believes there is sufficient information to assess stabilization/solidification.
 Treatability tests have been conducted on site soils and have determined that s/s is effective at
 binding the wastes in a monolith. Further testing will be conducted to determine how to address
 freeze/thaw process. If these tests determine that the monolith can not be constructed to
withstand freeze/thaw process and maintain its goal of preventing exposure and release of the
contaminants then an alternative remedy will need to be selected.

      EPA does not concur that groundwater and sediments in Ship Creek require remedial
action to  address contamination. The data within the RI and the  Risk Assessment clearly
illustrate  that groundwater does not pose an unacceptable risk to human health or the
environment. The LNAPL is a high risk material, but is considered to be a "source" to potential

                                            8

-------
groundwater contamination and not considered to be groundwater. The LNAPL and LNAPL
contaminated soils will be excavated and treated as part of the selected remedy.  RI data on Ship
Creek sediments show no PCB contamination is not present in sediment adjacent to the site
which pose an unacceptable risk to human health or the environment and therefore does not
require remedial action. Stream sediment samples adjacent to the site and downgradient did not
detect PCB or lead contamination which demonstrated a release from the site. These samples
were obtained in depositional areas and would indicate whether there have been recent releases.
Past releases may have occurred but would be distinguishable, if detected, from non-site releases.

       Flooding and seismic Events will be addressed during design of the monolith. These are
common engineering restraints which any activity within the Ship Creek basin and throughout
most of Anchorage would have to accommodate.

-------

-------

-------

-------