PB97-963117
                                 EPA/541/R-97/041
                                 November 1997
EPA   Superfund
       Explanation of Significant Difference
       for the Record of Decision:
        Selma Treating Co.,
        Selma, CA
        4/18/1997

-------

-------
                                                                    SFUNO RECORDS CTR
                                                                      1047-01124
                 EXPLANATION OF SIGNIFICANT DIFFERENCES        AROQ01
                                DECLARATION
SITE NAME AND LOCATION

Selma Pressure Treating Superfund Site
Selma, California
STATEMENT OF BASIS AND PURPOSE

On September 24,1988, the United States Environmental Protection Agency ("EPA")
signed the Record of Decision ("1988 ROD") for the Selma Pressure Treating
Superfund Site in Selma, California ("Site"). This Explanation of Significant Differences
#2 ("ESD2") explains the significant differences between the remedial action selected in
the 1988 ROD, as changed by the Explanation of Significant Differences issued in 1993
(1993 ESD), and the remedial action which will be implemented at the Site. (The 1988
ROD and the 1993 ESD are collectively referred to herein as the "ROD".) It was
developed in accordance with Section 117 of the Comprehensive Environmental
Response, Compensation, and Liability Act ("CERCLA"), as amended, and 40 C.F.R.
300.435 © (2) (I) (55 Fed. Reg. 8666, 8852 March 8,1990) of the National Contingency
Plan ("NCP"). This decision is based on the administrative record for this Site.
SUMMARY

This ESD2 explains changes in certain remedial action details pertaining to the return of
the treated water to the aquifer as described in the ROD. The 1988 ROD selected a
groundwater remedy which would employ a conventional precipitation, coagulation, and
flocculation extraction and treatment process, with either reinjection or off-site disposal
of the treated effluent. Based on reconsideration of certain technical information during
the design phase and additional data gathered pursuant to the ROD, EPA proposes to
modify the remedy by using percolation ponds to return the treated water to the aquifer.
All other aspects of the selected groundwater remedy are as described in the ROD,
including the scope and the cleanup standards.
DECLARATION

This remedy remains protective of human health and the environment, and continues to
comply with applicable or relevant and appropriate federal and state requirements that
were identified in the 1988 ROD, the 1993 ESD, and this ESD2. The selected remedy
also remains cost-effective and continues to use permanent solutions and alternative
treatment technologies to the maximum extent practicable for this Site.  Finally, the

-------
selected remedy continues to employ treatment that permanently and significantly
reduces the volume, toxicity, or mobility of hazardous wastes.
                                            4-
Keith Takata, Director                             Date
Superfund Division

-------
               SELMA PRESSURE TREATING SUPERFUND SITE

                      Explanation of Significant Differences

                                April 18, 1997
I. Introduction

      On September 24, 1988, the United States Environmental Protection Agency
("EPA") signed the Record of Decision ("1988 ROD") for the Selma Pressure Treating
Superfund Site in Selma, California ("Site"). This Explanation of Significant Differences
#2 ("ESD2") explains the significant differences between the remedial action selected
in the 1988 ROD, as changed by the Explanation of Significant Differences issued in
1993 (1993 ESD), and the remedial action which will be implemented at the Site. (The
1988 ROD and the 1993 ESD are collectively referred to herein as the "ROD".)  See
Attachments 1 and 2.

      Pursuant to Section 117 of the Comprehensive Environmental Response,
Compensation, and Liability Act  ("CERCLA"), as amended, and pursuant to 40 C.F.R.
300.435 © (2) (I) (55 Fed. Reg. 8666, 8852 March 8, 1990) of the National Contingency
Plan ("NCP"), EPA is required to publish an Explanation of Significant Differences
("ESD") when differences in the  selected remedy "significantly change, but do not
fundamentally alter the remedy selected in the ROD with respect to scope,
performance, or cost."  This ESD2 briefly describes the Site's location and history,
summarizes the remedy selected in the ROD, describes the differences between the
proposed changes and the ROD, and explains the basis for the changes.

      This ESD2 explains changes in certain remedial action details pertaining to the
return of the treated water to the aquifer as described in the ROD. The groundwater
remedy selected in the ROD consists of a conventional pump-and-treat system which
would return the treated water to the  aquifer via reinjection wells. EPA proposes to
modify the remedy by using percolation ponds to return the treated water to the aquifer.
All other aspects of the selected groundwater remedy are  as described in the ROD,
including the scope and the cleanup  standards.

      This ESD2 and the supporting documentation will become part of the Selma
Pressure Treating Administrative Record.  A copy of the Administrative Record has
been placed at the following locations:

                  Fresno County Library
                  Selma Branch
                  2200 Selma Ave.

-------
                  Selma, CA 93662
                  (209) 896-3393

                  U.S. EPA Region IX
                  Superfund Records Center
                  75 Hawthorne Street
                  San Francisco, CA 94105
                  (415) 536-2000
II. Site Description and History

       Located in Fresno County, California, the Site is approximately 15 miles south of
the City of Fresno and adjacent to the southern city limits of Selma. The Site is
comprised of approximately 18 acres which include a 4-acre wood treatment facility and
14 acres of vineyards that were used for site drainage. The Site is located in a
transition zone between agricultural, residential, and industrial areas.  Twelve (12)
residences and/or businesses are located within 1/4 mile of the site.  As of November
1996, a small transmission repair business leases an open air garage within 200 feet of
the abandoned wood treatment facility.  See Figure 1.

      The wood preserving process originally employed at the site involved dipping
wood into a mixture of pentachlorophenol ("PCP") and oil, then drying the wood in open
racks to let the excess liquid drip off. In 1965, the wood treating operator converted to
a pressure treating process which consisted of conditioning the wood and impregnating
it with chemical preservatives. Chemical preservatives known to have been used at
the Site include fluor-chromium-arsenate-phenol, chromated copper arsenate, PCP,
copper-8-quinolinolate, LST concentrate, and Woodtox 140 RTU and Heavy Oil Penta
5% Solution.  Prior to 1982, discharge practices for wastes generated from spent retort
fluids and sludges included: 1) runoff into drainage and percolation ditches; 2) drainage
into dry wells; 3) spillage onto open ground; 4) placement into an unlined pond and a
sludge pit; and 5) discharges to the adjacent vineyards. Wood treating operations
ceased in February 1994.

      From 1971 to 1981, the Regional Water Quality Control Board ("RWQCB")
regulated the discharges from the facility pursuant to a Waste Discharge Requirements
Order. In January 1981, EPA, the RWQCB, and the predecessor to the California
Department of Toxic Substance Control ("DTSC"), the Department of Health Services
("DHS"), conducted an investigation in accordance with Section 3007 of the Resource
Conservation and Recovery Act which raised concerns regarding potential groundwater
contamination at the Site.  In September 1983, the Site was placed on the National
Priorities List.

      From 1981 to 1984, the RWQCB and DHS employed various enforcement tools
in an attempt to force the owners and/or operators to conduct response actions at the

-------
Site.  In April 1984, DHS referred the Site to EPA for further action.  EPA issued
Unilateral Administrative Orders ("UAOs") to the owners and/or operators of the Site to
conduct the work. The potentially responsible parties declined to comply with the UAOs
based upon an inability to fund the work.

      In 1988, EPA issued a final Remedial Investigation and Feasibility Study which
characterized the soil and groundwater contamination at, and developed cleanup
standards for, the Site.  In September 1988, EPA signed the 1988 ROD which, in
relevant part, identified chromium as the only significant contaminant in the
groundwater. Sampling results during the remedial investigation indicated  that a plume
of chromium contamination extends downgradient from the Site to the southwest, with
the southern boundary of the plume approximately 1700 feet southwest of the facility.

      Groundwater investigations conducted by EPA after the issuance of the 1988
ROD provided a more complete picture of the extent of contamination and  the pumping
characteristics of the aquifer. Among other things, EPA's additional investigations
revealed that the groundwater table had dropped to elevations below the point where
EPA's original investigation had found the highest concentrations of chromium.
Sampling and analysis of the groundwater before the 1988 ROD had suggested that
PCP might be present in concentrations exceeding the then-newly promulgated, more
stringent drinking water maximum contaminant level ("MCL") of 1 part per billion ("ppb").
Based upon its recent groundwater monitoring studies,  EPA has determined that any
concentrations of PCP in groundwater are below the current MCL of 1 ppb, and that
chromium is the only groundwater contaminant present in concentrations which exceed
the MCL of 50 ppb.

      The 1988 ROD selected a groundwater remedy which would employ a
conventional precipitation, coagulation, and flocculation extraction and treatment
process, with either reinjection or off-site disposal of the treated effluent. The 1988
ROD established the cleanup standard for chromium to be 50 ppb.

      In 1993, EPA issued the 1993 ESD which, among other things clarified language
in the 1988 ROD and explained certain changes to the selected groundwater remedy.
In relevant part, the 1993 ESD: 1) changed the term "cleanup goal" to "cleanup
standard" wherever it was used in the 1988 ROD; 2) set the cleanup standard for PCP
in groundwater at 1 ppb to comply with a new more stringent drinking water MCL
(initially  the 1988 ROD did not establish a cleanup standard for PCP because the
California State action level of 30 ppm, which was considered a guideline, substantially
exceeded the concentrations detected in the groundwater); and 3) modified the
implementation of the groundwater extraction and reinjection system to reflect a more
phased, observational approach for the siting and design of the wells.
III. Description of Significant Differences and the Basis for Those Differences

-------
       Based on reconsideration of certain technical information during the design
phase and additional data gathered pursuant to the ROD, this ESD2 changes the
manner in which treated water will be returned to the aquifer.

       During the design phase, DTSC contended that there was insufficient data to
sufficiently predict the impact to the aquifer from reinjection of treated water.
Subsequently, EPA re-evaluated the groundwater treatment system and relevant data
and was concerned that the treated water, if recharged to the aquifer via reinjection,
might cause the plume of chromium concentration to spread laterally and/or vertically.
An added concern was that the change in hydrology attributed to reinjection of water
around the boundary of the plume could cause a loss of capture and reduce plume
containment, thereby allowing the plume to spread into new areas. Based on the
foregoing, EPA considered percolation as an alternative to reinjection because
percolation more closely mimics natural aquifer recharge, and thereby reduces the risk
of creating unwanted subterranean water movement or displacement of the
contaminated plume.  Off-site disposal of the effluent to the irrigation district was also
considered, but this method was rejected because the irrigation district did not want the
water during the rainy season.

      Additional data and review of the design for the groundwater remedy indicated
that percolation would be a preferable method for returning treated groundwater to the
aquifer. Pursuant to the ROD, EPA gathered additional field data using observation
wells and conducted a series of pilot percolation tests. The pilot percolation tests
primarily tested the hydraulic conductivity and measures the infiltration rates in the
subsurface soil. The results indicate that the infiltration rates are high enough to allow
for successful recharge of the treated  groundwater to occur by percolation.  The results
also indicate that returning the treated water to the aquifer via percolation would
minimize the effect on the underlying aquifer and plume of contamination. Based on
the foregoing, EPA determined that the Site conditions favor using a percolation pond
to recharge the aquifer. See Attachment 3.

      Additional benefits are associated with opting for percolation versus reinjection.
First, the costs for construction and operation and maintenance of the percolation
ponds would be less than such costs associated with reinjection. The higher cost to
construct the reinjection system  is attributable to the need to drill and develop eight
wells and a network of piping to connect these wells to the groundwater treatment plant.
The greater operation and maintenance costs for the reinjection system arise from the
cost of energy to pump water into the wells, the cost of increased maintenance
associated with the more extensive piping network, and the closure or removal of the
wells.  In contrast, percolation ponds employ a simpler technology which would not
require additional wells or a pumping system, and would use a less extensive piping
system, resulting in lower costs.  See Attachment 4.

      Second, employing percolation ponds would confine the recharge system to the
Site, while the reinjection system requires that two wells and the associated piping be

-------
placed off-Site on neighboring properties. The reinjection system would require
individual access agreements for each of the neighboring parcels affected and added
security to oversee the off-Site system, in addition to coordination to minimize the
disturbances to the neighboring agricultural operations. Construction of the reinjection
system with eight new wells, six on-Site and two off-Site, would have a larger, more
lasting impact than the percolation system.

       In light of the factors discussed above, EPA has determined that a percolation
pond recharge system is the preferred method for returning treated effluent to the
aquifer at this Site. DTSC has also accepted the concept of percolation over reinjection
for this Site. Such change will be implemented by a percolation system which will
discharge treated effluent into two percolation ponds.  The dimensions of each pond
are two hundred feet by two hundred sixty feet (200'x260'). The ponds will be located
approximately four hundred feet east of the western site border, and two hundred to
four hundred south of the northern site border. See Figure 2.

      The changes proposed in this ESD2 herein do not fundamentally alter the basic
features of the groundwater remedy with respect to scope, cost, or performance (40
CFR 300.435(c)(2)(ii)). The overall remedial approach to groundwater remains
extraction and treatment using conventional precipitation to remove  the contaminant of
concern, chromium.
IV. Support Agency Comments

      California DTSC has reviewed, and concurred on, the draft of this ESD2 before it
was sent out for public review.
V. Affirmation of the Statutory Determinations

      This selected remedy remains protective of human health and the environment,
and continues to comply with applicable or relevant and appropriate federal and state
requirements that were identified in the 1988 ROD, the 1993 ESD, and this ESD2. The
selected remedy also remains cost-effective and continues to use permanent solutions
and alternative treatment technologies to the maximum extent practicable for this Site.
Finally, the selected remedy continues to employ treatment that permanently and
significantly reduces the volume, toxicity, or mobility of hazardous wastes.
VI. Public Participation

      While neither CERCLA nor the NCP requires EPA to provide a period for public
comment in connection with this Explanation of Significant Differences, in light of
community interest in future land use, EPA intends to provide a period to allow for the

-------
public to comment on the changes discussed herein.

      A public notice fact sheet describing this Explanation of Significant Differences
was distributed to people listed as interested community members for the Selma Site as
of April 23, 1997. The fact sheet summarized the changes proposed in the draft ESD2,
identified the repository in Selma where the entire text of the draft ESD2 could be
reviewed and provided a period for public comments from April 24 to May 23, 1997.

-------
FIGURES

-------

-------
CALIFORNIA
                                     ^ r i  •
 a* '''^~~^~' \ •
                                                          Selma
                                                          Project Site
                                                          ,. M J:l_....A^..-J

                                                                S -  A
                                                          ".!>  ^     \
                                         Se//na  Pressure
                                         Treating  Site
     north

01   Z  3  4  3
        P
THOUSANDS OF
         Selma Pressure Treating Site
         Camp Dresser & McKee Inc.

-------
     Bechtel Environmental, Inc
SELMA PRESSURE TREATING SUPERFUND SITE
               RECHARGE BASIN
             CONCEPTUAL DESIGN

-------
                  ATTACHMENT  1                  SFUNO RECORDS CTR
                                                 1M7-00167
              RECORD OF DECISION

                 •  FOR THE
      SELMA PRESSURE TREATING COMPANY

               SUPERFUND SITE
               PREPARED BY

THE U.S. ENVIRONMENTAL PROTECTION  AGENCY
                REGION IX

        SAN  FRANCISCO, CALIFORNIA
             SEPTEMBER, 1988

-------

-------
                         TABLE OF CONTENTS
                       SELMA RECORD OF DECISION                 Pagt

       Declaration for the Record of  Decision	1
       Decision Summary	3

    I.  Site Name, Description/ and Location	3

   II.  Site History and Enforcement Activities	5

  III.  Community Relations	 . 8

   IV.  Site Characteristics	9
       A.  Surface and Subsurface Soil Results	...9
       B.  Soil Clean-up Goals and Areas
             Requiring Remediation	15
       C.  Groundwater Results	16
       D.  Groundwater Clean-up Goals	19

   V.  Summary of Site Risks	20
       A.  Chemicals of Concern	20
       B.  Exposure Pathways.....	21
       C.  Toxicity of Chemicals of Concern	21
       D.  Risk Characterization	22
       E.  Analytical Methods Used	24

  VI.  Documentation of Significant Changes/
         Section 117(b)S(c)	24

 VII.  Description of Alternatives.	24
       A.  Alternative 1	24
       B.  Alternative 2	24
       C.  Alternative 3	...26
       D.  Alternative 4	30

VIII.  Summary of Comparative Analysis of Alternatives...	32
       A.  Overall Protection of Human Health and the
             Environment	32
       B.  Compliance with ARARS	33
       C.  Long-term Effectiveness and Permanence	33
       D.  Reduction in Toxicity, Mobility, and Volume	33
       E.  Short-term Effectiveness	34
       F.  Implement ability	 .34
       G.  Estimated Capital, O&M, and Present Worth Cost	35
       H.  State and Community Acceptance	35

  XI.  The Selected Remedy	35

   X.  The Statutory Determinations	36
       A.  Protection of Human Health and the Environment	36
       B.  Attainment of ARARS	36
       C.  Cost-effectiveness.	.37
       D.  Utilization of Permanent Solutions Employing
             Alternative Technologies to the Maximum Extent
             Practicable	38

-------

-------
                             -1-
              DECLARATION FOR THE RECORD OF DECISION
SITE NAME AND LOCATION

The Selma Pressure Treating Company (SPT)  site is located in
Selma/ California, 15 miles south of the City of Fresno, in
California's Central Valley.

STATEMENT OF BASIS AND PURPOSE

This decision document represents the selected remedial action
for the Selma Pressure Treating site, developed in accordance
with the Comprehensive Environmental Response, Compensation and
Liability Act of 1980, as amended, and the National Contingency
Plan.  This decision is based on the administrative record for
this site.  (The attached index identifies the items which
comprise the administrative record upon which the selection of
the remedial action is based).  The State of California has
concurred on the selected remedy.

DESCRIPTION OF THE SELECTED REMEDY

This Record of Decision (ROD) for the Selraa Pressure Treating
site includes the following actions to address contaminated
soil and groundwater for the entire site (there are no operable
units):

0  Conventional water treatment to remove chromium from the
   groundwater, including:

   -  Extraction of contaminated groundwater

      Treatment of contaminated groundwater using precipitation,
      coagulation, and flocculation processes to remove chromium
      to meet the applicable drinking water standard
                               •
   -  Disposal of treated and tested groundwater by reinjection
      into the aquifer or off-site disposal, as appropriate

      Groundwater monitoring to verify contaminant clean-up

0  Soil fixation with a Resource Conservation and Recovery
   Act (RCRA) Cap to treat contaminated soil, including:

      Excavation of contaminated soils exceeding cleanup goals

      Mixing soils with a fixative agent to solidify and stabilize
      contaminated soil

      Replacement of fixed soil into excavated areas and covering
      the fixed areas with a RCRA Cap

-------
                               -2-
   -  Long term monitoring of fixed soils for a period of
      approximately 30 years

      Long-term access and land use restrictions for fixed
      areas and short-term institutional controls to prevent
      use of contaminated groundwater until remediation is complete

DECLARATION

The selected remedy is protective of human health and the envi-
ronment f attains federal and state requirements that are
applicable or relevant and appropriate to this remedial action
and is cost-effective.  The groundwater remedy satisfies the
statutory preference for remedies that employ treatment that
reduces toxicity, mobility, or volume as a principal element and
utilizes permanent solutions to the maximum extent practicable.
The soil fixation/RCRA Cap element of this remedy is not considered
fully permanent/ due to the need for long-term monitoring.  It
does employ treatment that significantly reduces mobility as a
principal element.  However, toxicity is not reduced and volume
is increased due to addition of the fixative agent.

Because this remedy will result in hazardous substances remain-
ing on the site, a review will be conducted within five years after
commencement of the remedial action to ensure that the remedy con-
tinues to provide adequate protection of human health and the
environment.  The State's letter of concurrence is attached.
        Daniel W. McGovern                            Date
        Regional Administrator

-------
                               -3-
                         DECISION SUMMARY

I.   SITE NAME, DESCRIPTION,  AND LOCATION

    The SPT site is located  about 15 miles  south  of  Fresno and
    adjacent to the southern city limits of Selma (Figure  1).
    Dockery Avenue and Golden State  Boulevard  (old Highway 99)
    mark the entrance to the site.   The SPT site  comprises
    approximately 18 acres,  including a 3-4 acre  wood treatment
    facility and 14 acres  of adjacent vineyards that were  used
    for site drainage.

    Zoned for heavy industrial use,  SPT is  located in a transition
    zone between agricultural, residential,  and industrial areas.
    Situated in the center of the San Joaquin Valley, the  area
    contains many vineyards, and Selma is labeled the "Raisin
    Capital of the World."  Urban residential areas  lie to the
    north,  and scattered suburban dwellings surround the site.
    Approximately 12 residences and/or businesses are located
    within  1/4 mile of  the SPT site.   Currently,  a wood treating
    facility,  Selma Treating Company (STC),  is operating at the
    SPT site.   STC is owned  by Saw Mill Properties,  Inc.   STC
    operations are regulated by state Waste  Discharge Requirements
    Order No.  78-171, which  precludes discharges  to  areas
    having  hydraulic continuity with groundwater.  At the  time
    STC began operating, the Regional Water  Quality Control
    Board (RWQCB) required installation of  drip pads, berms
    around  the site, and runoff containment to prevent ongoing
    contamination.

    The Consolidated Irrigation District provides the majority of
    the irrigation supply  in the area.   The  surface water  irriga-
    tion supply is supplemented by groundwater resources in the
    vicinity of the site.  The groundwater  resources also  supply
    the necessary domestic water for the surrounding communities
    and the scattered county residences.  The regional groundwater
    gradient in the vicinity of the  site is  to the southwest.
    The groundwater resources in the area of the  SPT site  have
    been classified as  a Sole-Source Aquifer by the U.S.   Environ-
    mental  Protection Agency,  under  the Safe Drinking Water
    Act, 42 U.S.C.  §1424(e).   Under  EPA's Groundwater Protection
    Strategy (1984),  the aquifer in  the SPT area  has been  classi-
    fied as a Class II  A current drinking water source with other
    beneficial uses.

    No  other significant natural resources were found at SPT,
    such as federal or  state rare, threatened, or endangered
    species,  or wetlands.  The site  is  not  included on the
    National  Register of Historic Places under the Historic
    Preservation Act of 1966,  16 U.S.C.  §470 et. seq.

    The climate for the site consists  of hot summers and mild
    winters.   The maximum  temperatures  are generally around 100°F
    in  July, with a minimum  temperature of  35° in January.

-------
                                                                               1
                                               CALIFORNIA

                                               San
                                               Francisco
                                       Se/ma  Pressure
                                       Treating Site
                         ,
                              ......
                     r-/  i
     norfh

01  2343.-
         Selma Pressure  Treating Site
                                        REGIONAL LOCATION MAP
         Camp Dresser  & McKee Inc.

-------
                               -5-
     Average annual precipitation in the area is less than 10
     inches.  The monthly evaporation losses range from two inches
     per month during the winter to 18 inches per month during the
     summer.

II.  SITE HISTORY AND ENFORCEMENT ACTIVITIES

     Treatment of lumber products has been ongoing at the SPT
     site since 1942.  The original wood treatment facility
     covered approximately 3-1/2 acres.  In 1961, the treatment
     operation was taken over by Gerald Petery,  the son of the
     original owner, and his wife, Mary Ann Petery (now Schuessler).
     A summary of the operating history of the Potential Responsible
     Parties (PRP's) is as follows:
     Dates

     1961-1/1970


     1/1970-12/1977




     1971-Present
     12/1977-late/1981
     4/1981
     2/1982
     2/1982-Present
Owners

Gerald Petery and Mary Ann Petery operated
the facility as individuals.

Gerald Petery and Mary Ann Petery incor-
porated as Selma Pressure Treating
Company, which was responsible for
operating the facility.

Selma Leasing Company (SLC) was organ-
ized and owned by Gerald Petery.  SLC
became the owner of the land  upon
which SPT, and later Saw Mill Properties,
Inc., operated.

Gerald Petery sold his interest in SPT
to Mary Ann Schuessler (formerly Petery).
Mary Ann Schuessler became the sole
owner, president, and operator of SPT.

SPT filed for bankruptcy and  First Inter-
state Bank or a trustee took  over the
operation.

SPT's trustee sold wood treating assets
to Saw Mill Properties, Inc.

Saw Mill Properties, Inc. has operated
the facility, as Selma Treating Company.
     The wood-preserving process originally employed at the site
     involved dipping wood into a mixture of pentachlorophenol
     and oil, and then drying the wood in open racks to let the
     excess liquid drip off.   A new facility was constructed
     in 1965, and SPT converted to a pressure treating process
     which consisted of conditioning the wood and then impregna-
     ting it with chemical preservatives.

-------
                         -6-
Prior to 1982, discharge practices included:  (1)  runoff
into drainage and percolation ditches,  (2)  drainage into
dry wells, (3) spillage onto open ground,  (4)  placement into
an unlined pond and sludge pit,  and (5)  discharges to the
adjacent vineyards.  These wastes were  generated  from spent
retort fluids and sludges.  Figure 2 depicts  these disposal
sites.

Between 1971 and 1981,  the Regional Water  Quality Control
Board (RWQCB) regulated the discharges  from SPT,  under a
Waste Discharge Requirements Order.  An  Uncontrolled
Hazardous Site Investigation was conducted on January 31, 1981
in accordance with §3007 of the  Resource Conservation and
Recovery Act  (RCRA), by the EPA's Field Investigation Team
(FIT), the California Department of Health Services (DBS),
and the RWQCB.  This inspection  raised  concerns about the
potential for groundwater contamination from  the  site.  As
a result, SPT was required to modify its operation to minimize
the potential for contamination.  Initial  site investigation
activities were then conducted by the state and EPA to
assess contamination problems.

Between 1981 and 1984,  RWQCB, EPA, and  DBS pursued efforts
to have SPT and, later, SLC investigate the site to determine
the extent of contamination.  In September of 1981, the
RWQCB issued a Cleanup and Abatement Order to SPT, requiring
a geotechnical investigation and establishing a timetable for
cleanup.  The timetable for cleanup was not submitted to the
RWQCB and in September of 1984,  the RWQCB  referred the
Order to the California Attorney General's office, for
enforcement.  The Attorney General's office is pursuing a
case against SLC, SPT,  Gerald Petery, and Mary Ann Schuessler,
on behalf of  itself and the RWQCB.  Gerald Petery has
filed a cross-claim against a number of parties,  including
Mary Ann Schuessler, various  chemical manufacturers of  PCP,
EPA's consultant, COM, First  Interstate Bank, Koppers,  and
Osmose.

In September  of 1983, DHS informed SPT of violations  and
transmitted an Order, Settlement Agreement, and Schedule
of Compliance, including  civil penalties of $75,000.   In
December of 1983,  DHS found SLC's  counter proposal  to this
Order to be unsatisfactory.   DHS referred the site  to EPA
for further action  in April of  1984.

In August of  1983,  EPA ranked the  site using the Hazardous
Ranking System  (HRS) 40 C.F.R.  Part  300, Appendix A,  as
authorized under 42 U.S.C. §105(a)(8), to determine whether
to include the site on the Superfund National Priorities
List  of hazardous waste sites.  The HRS ranking for the
site  indicated that releases  of hazardous substances  from
the site may  present a danger to human health and the environ-
ment.  Based  on this information the site was placed  on the
Superfund National Priorities List of hazardous waste sites
in September  1983.  The HRS ranking was 43.83, and  the  site
was listed as number 195.

-------
DATAMMMT  •   N077B

-------
                               -8-
      In September 1984, EPA requested Camp Dresser & McKee Inc.
      (COM), under their REM II contract,  to prepare a Work Plan
      outlining the tasks required to prepare a Remedial Investi-
      gation and Feasibility Study (RI/FS)  for the  site.  COM
      submitted the Work Plan outlining the RI/FS activities to
      be conducted/ on June 7, 1985.   The  various project plans
      required to support the field investigation activities
      were submitted in 1985 and 1986.  Field activities were
      initiated in April 1986, and were conducted in various
      phases through August 1987.   The final RI report (COM, 1988)
      provides the .results of those field  activities.  An Endanger-
      ment Assessment (EA) was prepared to assess risks to human
      health and the environment associated with the No Action
      Alternative (ICF, 1988).  The FS report (COM, 1988) analyzes
      alternatives based on data collected and analyzed during the
      RI investigation and based on the results of  the EA.

      Potentially Responsible Parties (PRPs)  have not been involved
      in development of the RI/FS.  EPA is  currently in discussion
      with PRPs regarding the potential for their involvement in
      the Remedial Design/Remedial Action  (RD/RA) phases of this
      project and for recovery of  past costs.  Special notice
      letters will be issued in the near future under $122(e) of
      CERCLA.  PRPs identified include Gerald Petery, Mary Ann
      Schuessler, and First Interstate Bank.

      At present/ technical discussions with PRPs have been limited
      to formal comments on the FS/Proposed Plan and related meet-
      ings.   This information is included  in the responsiveness
      summary and is part of the administrative record.

III.   COMMUNITY RELATIONS

   ••  The following is a summary of community relations  activities
      conducted by EPA for the SPT site, in order to meet the
      requirements under Sections  113(k)(2)(i-v)  and 117 of CERCLA.

      Dates                Activities

      March/April         EPA community relations (CR)  represent-
      1985                atives conducted  community assessment
                          interviews  with  interested community
                          members  in  the Selma area.

      July 1985           EPA distributed a fact  sheet announc-
                          ing the  commencement of RI/FS  work,
                          and describing the  RI/FS  activities
                          to the community.

      July 1985           EPA held a  community meeting in Selma
                          to explain  RI/FS  activities that  EPA
                          was undertaking and to  respond to the
                          community's questions and concerns.

-------
                             -9-
     January 1986
     March 1986
     May 1986




     July 1987


     April 1988


     June 1988




     June 22, 1988
     September 1988
EPA finalized the Community Relations
Plan detailing the community concerns
as expressed in the July 1985 community
assessment interviews and communitty
meeting.

EPA distributed a fact sheet describ-
ing the purpose and nature of the
monitoring wells placed in the
Selma area.  EPA also distributed a
Spanish translation of this fact
sheet.

EPA Community Relations Coordinator
met informally with community members
to listen to their concerns and to
explain current site activities.

EPA distributed well sampling results
to interested community members.

EPA distributed a fact sheet detailing
the results of the Rl.

EPA distributed a fact sheet explain-
ing the contents of the FS Report and
announcing the upcoming public comment
period and community meeting.

EPA held a community meeting to explain
the FS Report and to receive public
comment on EPA's Proposed Plan for
addressing the soil and groundwater
contamination at the SPT site.

Notice of this ROD, or Final Plan,
will be published and made available
to the public before commencement of
the remedial action.
IV.  SITE CHARACTERISTICS

     The following discussions address contamination problems
     for the entire SPT site; there are no operable units
     (i.e./ sub-investigations) for this site.   All data were
     validated by Region 9, EPA, using standard review protocols
     and data quality was considered in analysis of the data
     and in reaching the decision.

     A.  Surface And Subsurface Soil Results

         A total of 48 surface soil samples were collected during
         two rounds of sampling.  The samples were collected
         from locations where waste was suspected to have been
         discharged, from known waste disposal areas, and from

-------
                      -10-
background locations.   The samples were analyzed for a
variety of constituents,  including:   An initial screening
for Hazardous Substance List (HSL) volatiles,  semi-vol-
atiles and metals; hexavalent chromium? individual
phenols; and dibenzodioxin/dibenzofuran (dioxin/furan)
chlorinated tetra through octa homologs.   A subsequent
phase to confirm earlier  results  was  performed and
included analysis for  isomer specific chlorinated
dioxin/furans and metals.   The site-related contaminants
of concern found in surface soils included chromium,
arsenic, copper, dioxin/furan, pentachlorophenol
(PCP), and trichlorophenols (TCP).

A round of subsurface  soil samples was collected at 21
boring locations during the RI field  program (Figure
3).  Samples were generally collected at  the following
depths; 1 to 2.5 feet  (ft.), 2.5  to 4.0 ft., 4 to 5.5.
ft., 10 to 11.5 ft., 15 to 16.5 ft.,  and 20 to 21.5
ft.  (e.g. to the water table).  The  samples were
analyzed for individual phenols,  chromium, arsenic,
and copper.  Selected  samples were also analyzed for
the tetra through octa chlorinated dioxin/furan homologs,
without identification of isomers.  Chemicals of
concern for the subsurface soils  were the same as for
the surface soils.

The soil sampling results identified  seven areas where
past practices resulted in levels of  contamination
above background concentrations that  they warranted
further evaluation.  The  seven soil contamination
areas are the Waste Sludge Pit, North Unlined Percolation
Ditch (Ditch A), South Unlined Percolation Ditch
(Ditch B), Unlined Waste  Disposal Pond, Drainage Area,
Southeast Disposal Area,  and Southwest Disposal Area.
Table 1 provides the highest level for each of the
contaminants of concern detected  in each area of
concern.  Figure 4 identifies the location of each of
the areas.  The boundary  of each  area was based on the
available sampling data and geographical  features
associated with each site.

These locations represent areas of concern due to the
elevated levels of site-related contaminants detected
at each of these; sites.   For example, high levels of
arsenic, up to 4120 ppm,  were detected at the Waste
Sludge Pit.  High levels  of arsenic were  also detected
at the Unlined Waste Disposal Pond and Southeast
Disposal Area.   Elevated  levels of dioxin/furan contam-
ination, in tetra chlorinated dibenzodioxin (TCDD)
equivalents, were detected at the former Unlined Waste
Disposal Pond and the  Southeast Disposal Area.

TCDD equivalents are a means of comparing the levels of
dioxin/furan contamination in various locations.  The
toxi'city of a particular  dioxin/furan compound is

-------
                                       -11-
Btaine Ave.
      200   400   800
P1  •   WELL BORING LOCATION
        SOIL BORING LOCATION
Project No.

123-FS1
Selma Pressure Treating Site
                                   SUBSURFACE SOIL
                                 SAMPLING LOCATIONS
            Camp Dresser & McKee

-------
                                                                                      -12-
                                                      TABLE
                                                                  MAXIMUM CONTAMINANT CONCENTRATIONS FOUND IN SOILS
Location
Waste Sludge
Pil (Sample Sites
W04. S34-S38)
- Surface
Unlined Percolation
Ditch A (Sample Sites
SI. 52. S3)
- Surface
• 1 to 2.5 ft.
• 2.3 to 4 ft.
-4 to 3.5ft.
- 10(0 11.5ft.
- 15 to 16.3 ft.
- 20 to 21 .5 ft.
Unlined Percolation
Diich B (Sample Sites
S4. S5)
- Surface
• 1 to 2.5 ft.
- 2.5 to 4 ft.
- 4 to 5.3 ft.
• 10 to 11. 5 ft.
• IS to 16.5 ft.
- :o to 21.5 ft.
Unlined Wane
Disposal Pond (Sample
siies W03. S29 - S33)
- Surface
Southwest
Disposal Area
(Sample site S7)
- Surface
- 1 to 2.5 ft.
- 2.S to 4 ft.
- 4 to 5.J ft.
- 10 to 11.5 ft.
- IS to 16.3 ft.
• 20 to 21. 5 ft.
Arsenic
mg/kg



4120


55
ND
22
23
3.2
3.5
ND



ND
3.7
12
63
5.3
ND
ND



8SO



21
31
25
28
9.9
17
8 It
Chromium
mg/kg



3910


196
13
9.7
9
8
11
12



12
15
23
19
11
13
12



879



24
31
15
11
S.9
6.7
7
Copper
mg/kg



1870


121
14
9.6
10
7.3
12
18



17
11
10
12
18
8.3
12



553



9
5.6
ND
ND
6.3
3.1
ND
PCP
Ig/kg



11000


1100
32
34.9
363
21.1
ND
43



ND
ND
231
340
11.4
26
ND



460.000



ND
ND
ND
ND
ND
ND
234
Total1
TCP
*g/kg



R


R
277
4.9
14
80
ND
38



ND
10
ND
ND
13
ND
41



R



ND
3
ND
ND
ND
ND
8.0
Total1
Dioxins
ng/g



283.8


130.2
63.2
32.9
40.3
2.5
NS
1.0



7
0.9
0.8
12.5
0.2
NS
ND



1228.7



1233.7
621.3
21.1
2.64
1.7
NS
0.1
Total1 TCDD2
Furans EQUV
ng/g ng/g



36.6 .29


40.1 .31
11.5
2.7
10.1
0.48
NS
0.18



2.5 .01
ND
Q.I
2.5
ND
NS
ND



634 5.65



361.9 .29
119.7
0.7
ND
ND
NS
ND
Total
TCDD
ng/g



ND


ND
ND
ND
ND
ND
NS
ND



ND
ND
ND
ND
ND
NS
ND



ND



ND
ND
ND
ND
ND
NS
ND
Total
TCDF
ng/g



ND


ND
ND
ND
ND
ND
NS
ND



ND
ND
ND
ND
ND
NS
ND



ND



0.12
0.19
ND
ND
ND
NS
ND
Total
PeCDD
"g/g



ND


ND
ND
ND
ND
ND
NS
ND



ND
ND
ND
ND
ND
NS
ND



ND



ND
ND
ND
ND
ND
NS
ND
Total
PeCDF
ng/g



ND


0.7
0.05
ND
ND
ND
NS
ND



ND
ND
ND
ND
ND
NS
ND



11.9



2.8
1.0
ND
ND
ND
NS
ND
Total
HxCDD
ng/g



3.4


3.4
0.71
0.21
0.85
NA
NS
ND



ND
ND
ND
ND
ND
NS
ND



117



12.7
7.3
ND
ND
ND
NS
ND
Total
IUCDF
ng/g



6.8


5.4
1.7
1.1
1.3
0.061
NS
ND



ND
ND
0.21
t.:x
NA
NS
ND



232



64 7
246
0.11
ND
ND
NS
ND
N/A   Not Available          R: Data Rejected during data validation     TCDD:  Tetrachlorodibenzo-n-dioxini
ND   Not Detected                                                  TCDD EQUV:  TCDD equivalents
NS    Not Sampled                                                  TCDF:  Telrachlorodibenzorurans
2 Total diotin/Curan analysis includes Tetra through Octa homologs. of which the Octa nomolog Is considered innocuous.
  TCDD Equiv. are based on both the isomer specific and homolog data.
PeCDF:   Pemachlorodlhenzolurins
HxCDD:  Hexachlorodibenzo-p-dloilns
HxCDF:  Hexachlorodibenzofuran
PeCDD: Pentachlorodibenzo-p-Oioiins

-------
                                                                                            -13-
                                                  TABLE 1   MAXIMUM CONTAMINANT CONCENTRATIONS FOUND IN SOILS (continued)
Location
Drainage
Arei (Sample site S9)
• Surface
- 1 to 2.5 ft.
- 2,5 to 4 ft.
- 4 to 5.5 ft.
- 10 to 11.5ft.
- 15 to 16.5 ft.
- 20 to 21. 5 ft.
Arsenic
rag/kg
12.2
5.0
14.0
13.0
2.7
R
1.4
Chromium
mg/kg
25
21
14
10
ND
ND
7.1
Copper
at/kg
15
7.7
17
12
9.2
7.4
13
PCP
*g/kg
ND
ND
ND
ND
ND
ND
ND
Total1
TCP
PE/kg
ND
ND
ND
ND
ND
ND
ND
TotaJ1
Dioxins
ng/g
2S.3
0.5
13.2
11.4
0.6
NS
0.3
Total1
Furans
ng/g
6.8
O.I
2.0
.77
ND
NS
ND
TCDD2
EQUV
ng/g
.03
Total
TCDD
ng/g
ND
ND
ND
ND
ND
NS
ND
Total
TCDF
ng/g
ND
ND
ND
ND
ND
NS
ND
Total
PeCDD
"R/g
ND
ND
ND
ND
ND
NS
ND
Total
PeCDF
ng/g
ND
ND
ND
ND
ND
NS
ND
Total
HxCDD
ng/g
0.38
ND
0.052
ND
ND
NS
ND
Total
IUCDF
"8/g
0.64
ND
0.16
ND
ND
NS
ND
Southeast
Disposal Area (Sample
sites W05. S39 - S44)
  •  Surface
                       467
                                      390
                                                   422
200.000
                                                                            92
                         2316.5
                                      2214.2
                                                  1.62
                                                                                                                        ND
                                                                                                                                   ND
                                                                                                                                             ND
                                                                                                                                                            S.2
                                                                                                                                                                    45
                                                                                                                                                                                   R6.2
N/A   Not Available           R:  Data Rejected during data validation      TCDD:   Teiracnlorodibcnio-n-dionins
ND   Not Delected                                                   TCDD EQUV:  TCDD equivalents
fS    Not Sampled                                                    TCDF:  Tetrachlorodihen/ofurans
2 Total dionin/luran  analysis includes Tetra through Octa homologs, of which the Ocla hornolog is considered innocuous
  TCDD  Equiv. are hasixi on hoth the isomer specific and homolog data.
                                                    PeCDF:   Penlachlorodibenzol'urans
                                                    HxCDD:  Hcxachlorodihcnro-n-dioxins
                                                    HxCDF:  HenachlorcxJiben/oturan
                                                    PeCDD:  Pcmachlorodibcruop Jionns

-------
Selma  Pressure Treating S
     EXTENT OF
SOIL CONTAMINATION

-------
                         -15-
    dependent upon the degree of chlorination at the 2,3,7,8,
    position.  The exception to this is the" octa chlorinated
    dioxin/furan homologs, which are considered innocuous.
    The remaining tetra through hepta isomers have various
    degrees of toxicity.  In order to assess the potential
    toxicity associated with the dioxin data, each sample
    was evaluated with respect to 2,3,7,8 TCDD equivalents.
    This involves converting each dioxin/furan homolog
    into TCDD equivalents based on the EPA approved method-
    ology using Toxicity Equivalent Factors (TEF).

    Due to the lack of vertical extent data in source areas,
    an estimate of vertical extent of contamination was
    made to calculate volumes of soil requiring cleanup.
    The metal contamination in the soil was assumed to
    extend to a depth of 20 feet, which corresponds to the
    approximate depth of the water table.  This assumption
    is based on the results of the groundwater sampling,
    which show elevated levels of chromium in the shallow
    portions of the aquifer.  Dioxin/furan contamination
    is assumed to extend to 10 feet in depth based on
    available subsurface sampling results from various
    boring locations, which indicate that dioxin/furan
    contamination reaches permissible levels within the
    first 10 feet.  This is evident from Table 1 which
    indicates that dioxin was detected in trace levels in
    only one soil sample taken from below 10 feet.  Additional
    soil borings will be collected during RD/RA to refine
    this information on vertical extent of contamination.

    The site-related surface and subsurface soil contaminants
    have variable mobilities in the environment.  For
    example, dioxin/furan compounds have very low solubilities
    and are extremely immobile in the soil.  Copper is
    also not very mobile in the environment due to its
    strong affinity for clays, hydrous metal oxides,  and
    soil organic matter.  Trivalent chromium has similar
    sorption characteristics to copper, and as such,  tends
    not to be very mobile.  Hexavalent chromium is very
    soluble and highly mobile in the environment.  Furthermore,
    hexavalent chromium is not easily sorbed on the soil.
    However, hexavalent chromium is only stable under
    oxidizing conditions and will form trivalent chromium
    in a reducing environment.  In regard to PCP and
    arsenic, these compounds can be relatively mobile
    under high pH environments.  However, these compounds
    appear to be relatively immobile at the SPT site due
    to the general lack of observed levels in the groundwater.

B.  Soil Clean-up Goals and Areas Requiring Remediation

    Of the organic contaminants at SPT, the site-specific
    risk assessment indicated that dioxin/furan would drive
    the clean-up goals.  The clean-up goal selected for
    dioxin/furan contaminated soil is 1.0 ng/g (ppb), in

-------
                          -16-
    TCDD equivalents.   This  clean-up goal  is-based  on a
    TCDD risk study performed  by Kimbrough, et  al.  (1984)
    of the Centers For Disease Control  (CDC).   This study
    is the basis for EPA policy and clean-up  goals  at
    Superfund sites where there is dioxin  contamination.
    The 1 ppb goal is for areas where potential residential
    or agricultural uses could occur.  While  the SPT site
    is currently used for industrial purposes,  the  1 ppb
    goal was selected due to the proximity of residences
    and agricultural activities to the  site.

    The heavy metals of concern at SPT  are arsenic/ chromium/
    and copper.   Based on the  health risk  assessment, the
    metals clean-up goals were driven by arsenic.   However,
    the primary  basis for the  metals clean-up goals will
    be the protection of groundwater.  The selected 50 ppm
    arsenic goal assumes solubility and attenuation factors
    which are being verified by "collecting more data.
    During remedial design (RD), data to evaluate the solu-
    bility of the soil contaminants and establish a site-
    specific attentation factor may indicate  that both the
    arsenic and  chromium clean-up goals need  to be  modified
    in order to  provide adequate protection of  the  groundwater,
    A modification in the clean-up goals could  result in a
    change in the volume of  soil requiring remediation.

    The 50 ppm arsenic goal  is protective  of  all direct
    contact scenarios except new, on-site  residential
    development.  Institutional controls are  required to
    prevent on-site residential development.

    As stated previously, seven areas of contaminated soil
    were identified at SPT (see Figure  4).  The clean-up
    goals indicate that four of these areas require re-
    mediation.  The four areas proposed for clean-up
    are the Waste Sludge Pit,  the Unlined  Percolation Ditch
    A, the Unlined Waste Disposal Pond, and the Southeast
    Disposal Area.

    Sampling results for three other areas indicate that
    contamination levels are below clean-up goals.   These
    three areas  are the Unlined Percolation Ditch B, the
    Drainage Area, and the Southwest Disposal Area.

C.  Groundwater  Results

    The hydrogeologic setting  for the area consists of
    valley-fill  sequence due to the deposition  of sediments
    from the adjacent Sierra-Nevada highlands.   The deposi-
    tional environment results in discontinuous geologic
    units.  The  exception to the discontinuous  nature of the
    units is a five to ten foot clay layer located  at a
    depth *of approximately 55  to 60 feet below  ground surface,
    which appears to be continuous or semicontinuous
    across the site.   Additional data will be collected

-------
                      -17-
during remedial design to verify the continuity of the
clay layer.  The groundwater directly underlying the
site is an unconfined aquifer.

Three rounds of groundwater samples were conducted in
the vicinity of the SPT site.  The first round of sampling
occurred in April-May 1986 and included several regional
domestic and irrigation wells, as well as five existing
EPA monitoring wells installed by the EPA Environmental
Response Team (ERT).  The second round of sampling was
performed in February-March 1987.  This round included
the sampling of the five existing EPA monitoring wells
and the ten newly installed plume tracking monitoring
wells.  A third round of sampling occurred in July-August
1987 and included all of the monitoring wells and selected
regional wells.   The analyses performed for each round
were as follows:

1.  First Round, April-May 1986:

    Individual phenols (Method 604)
    Routine Analytical Services (RAS) Metals
    General water quality parameters

2.  Second Round, February-March 1987:

    Individual phenols (Method 604)
    RAS Metals
    General water quality parameters

3.  Third Round, July-August 1987:

    Individual phenols (Method 604) - all wells
    Dissolved chromium, arsenic, copper - all wells
    Target Compound List (TCL) Volatiles - existing EPA
      and plume tracking monitoring wells
    TCL Semivolatiles - existing EPA and plume tracking
      wells
    Dioxin/furan homologs - five existing EPA monitoring
      wells

While there are several contaminants at elevated levels
in the soil, chromium was the only contaminant of signi-
ficance detected in the groundwater, due to the relative
immobility of dioxin/furan, arsenic, and copper.
Organics (dioxin/furan and PCP) are being resampled as
part of remedial design related activities, but previously
detected levels are believed to be due to sampling errors.

Sampling results indicate that a chromium contaminated
plume extends downgradient from the site to the southwest
(Figure 5).  The southern boundary of this plume appears
to range approximately 1,200 feet south-southwest of
the existing wood treatment facility boundary.  The
groundwater contamination is apparently confined to

-------
                                        -18-
 Approximate
                                        R-22
                                     (ND.13.0.2.0J)
Boundary of 50 ugll
/soconcentrat/on
Contour for
Chromium
                           R-24 —
                      <4.0,326,,7.0J)
                         •\
                                                       2.0.80.5.0J)
                                                                   P-4S —
                                                                (ND.NDJ.O)
       Approximate Boundary of
       Chromium Contaminated Plume
                                     — P-6S
                                     ND,7.0,6.0J>
            EPA MONITORING WELL LOCATION

            EPA PLUME TRACKING WELL LOCATION
(ND NO 4 0) VALUES FOR ARSENIC. CHROMIUM * COPPER
      ' '   CONCENTRATIONS IN ug/l- July/Augutt. 1967
                                                              P-3S •
                                                            (ND.2.0.5.0)
                                   DATA ESTIMATED
          NOT DETECTED
         Setma Treating Company Site
                                               GROUNOWATER PLUME
                                                   BOUNDARY MAP
          Camp Dresser & McKee Inc.

-------
                         -19-
    the  shallower portion  of  the aquifer  (to 40'), and
    does not currently  affect any municipal, private, irri-
    gation/  or  industrial  wells in  the vicinity, based
    on the sampling  results.  Contamination was not detected
    in the deep monitoring wells at depths of  87-100'.
    However, contamination levels  in the  intermediate portions
    (40-60*) of the  aquifer have not yet  been  defined.

    The  extent  of the chromium contaminated plume  needs
    additional  definition  to  the west and southwest of  well
    R24.  As part of remedial design, two well nests
    west and south of R-24 are planned.   A well nest will con-
    sist of  one shallow well  (40')  and one intermediate
    well (601).

    Additional  definition  of  the vertical extent of  contam-
    ination  within the groundwater plume  is also planned
    as part  of  remedial design.  Three intermediate  level
    wells completed at depths of 60 feet  will  be paired
    with the existing shallow wells in this area.

    Additional  data will also be collected on  the continuity
    of the clay layer present at a depth  of 55 to 60  feet.
    This data will be collected during the monitoring well
    installation program described above.

    Other monitoring well  installation plans include  a
    shallow  monitoring well  (40*)  downgradient of the South-
    east Disposal Area, and an  intermediate level monitoring
    well and two observation  wells  in the upgradient
    background  area.  Other groundwater characterization
    activities  to be conducted as  part of remedial
    design include:

    1.  Monthly water level measurements  for one year
    2.  Quarterly water quality sampling  for one year
    3.  Long-term aquifer  testing
    4.  Efforts to locate  and sample the  original Brown
        and  Caldwell monitoring wells

    Based on evaluation of the data collected  from the
    above described activities, a  decision will be made
    regarding the need for any additional characterization.

D.  Groundwater Cleanup Goals

    The  groundwater cleanup goal is the Maximum Contaminant
    Level (MCL) established under  both the federal and  state
    Safe Drinking Water Acts. Due  to the fact that  chromium
    was  the  only contaminant  of significance detected  in the
    groundwater, additive  effects were not of  concern.   There-
    fore, it was possible  to  select an ARAR as a clean-up
    goal, rather than a risk  assessment driven goal.

-------
                              -20-
        Currently the MCL pertinent to SPT is the  50  ppb level
        set for chromium.  The federal MCL is proposed  for
        revision to 100 ppb, however, the state  50 ppb  standard
        will probably be in effect at the time of  remedial
        action.  The most stringent of the state or federal MCL
        in effect at the time of RD/RA will be used.  For
        analyses in the Feasibility Study and Record  of Decision,
        the 50 ppb MCL was assumed.  The arsenic MCL  of 50 ppb,
        is also an applicable ARAR for the SPT site.  However,
        arsenic was detected only at levels well below  the
        existing or proposed MCL.

        The boundary of the groundwater plume exceeding the
        chromium clean-up goal is delineated in  Figure  5.   This
        boundary was based on the elevated chromium values
        observed in the shallow monitoring and plume  tracking
        wells.  The western extent of contamination was estimated,
        based on the observed trend of the plume in other
        areas.  The extent of contamination in this area will
        be further defined during the RD phase,  through the
        installation of additional monitoring wells,  as discussed
        in the proceeding section.

        The data collected from the deep plume tracking wells
        in the site vicinity indicate that the chromium con-
        tamination at a depth of 90-120 feet does  not exceed
        the chromium clean-up goal of 50 ppb. The exact
        vertical extent of contamination that exceeds the
        clean-up goal in the intermediate portions of the
        aquifer will be further defined as part  of the  RD, as
        described in the proceeding section.

V.  SUMMARY OF SITE RISKS
  ••
    A.  Chemicals Of Concern

        Data collected during the RI were reviewed to select a
        subset of chemicals (chemicals of concern) for  detailed
        evaluation in the risk assessment.  Separate  subsets were
        selected for surface soils, subsurface soils  (soil bor-
        ings), and groundwater, in order to reflect the different
        exposure pathways associated with these  different
        media.

        A comparison of on-site and background levels of metals
        in surface soils, reveals that only arsenic,  chromium,
        and copper appeared at elevated levels above  background.
        Therefore these site-related chemicals were selected as
        chemicals of concern in surface soil, from among the
        metals.  The organics of concern in the  surface soil,
        identified in the risk assessment, were  phenols, dioxins,
        furans, bis(2-ethylhexyl) phthalate, and di-n-butylphth-
        alate.  An analysis of subsurface soils  produces the same
        subset of chemicals of concern, except that the phthalates

-------
                          -21-
    were not included.   The levels of arsenic and dioxin/furan
    contamination in the soil were the only constituents
    exceeding the health based clean-up goals.

    Groundwater samples were collected from domestic,  indus-
    trial, municipal,  and irrigation wells, and from fifteen
    monitoring wells.   Site-related chemicals detected were
    arsenic, chromium,  copper, pentachlorophenol, and two
    dioxin congeners.   Based on considerations of toxicity,
    concentration, and relations to site activities, arsenic,
    chromium, copper,  and the dioxins were selected as chem-
    icals of concern.   However, only chromium exceeded the
    clean-up goals in groundwater.

B.  Exposure Pathways

    Potential human exposure pathways at the SPT site include
    exposure to contaminated groundwater, exposure via direct
    contact with contaminated soil (including incidental
    ingestion), and inhalation of contaminated dust.  Based
    on data from existing private and municipal wells, risks
    associated with current use of groundwater in the vicinity
    of the site were evaluated.  Using estimates based on
    data from monitoring wells and groundwater modeling,
    potential future risks associated with use of local
    groundwater as a potable supply were also evaluated.  For
    soil, the EA evaluated exposure of individuals working at
    the site or in the vicinity of the site, local residents,
    and trespassers.  Direct contact (dermal absorption or
    inadvertent ingestion) and inhalation were the exposure
    routes used.  A number of scenarios involving these types
    of exposure were examined.  Finally, a number of scenarios
    examining the potential exposure of off-site receptors to
    contaminants present in windborne dust also were evaluated
    using an air dispersion model.

C.  Toxicity Of Chemicals Of Concern

    Both the carcinogenic and noncarcinogenic effects of
    chemicals of concern used in the EA analysis are presented
    below.  Exposure to arsenic has been associated with an
    increased incidence of cancer in humans.  Chromium has
    been associated with an increased incidence of lung
    cancer in humans exposed via inhalation, but has not been
    associated with an increased incidence of cancer when
    exposure occurs via ingestion.  Bis(2-ethylehexyl)phthalate
    and 2,4,6 trichlorophenol are classified as probable
    human carcinogens  based on evidence from animal carcino-
    genicity bioassays.   Certain dioxins and furans are
    considered to be carcinogenic by EPA and are also  toxic to
    the reproductive system and the immune system.

    Exposure to chromium via ingestion is associated with
    non-carcinogenic toxcicity,  including decreased water
    consumption,  and at  higher levels,  gastrointestinal

-------
                      -22-
disturbances, liver damage, kidney damage-,  internal
hemorrage, dermatitis,  and respiratory problems.   Many of
these effects are thought to be due to chromium VI, not
to chromium III.  Exposure to copper, chlorophenol,
cresols, di-n-butylphthalate, 2,4-dichlorophenol,
2,4-dinitrophenol, 2- and 4-nitrophenol, pentachloro-
phenol, and phenol have been associated with a variety
of systemic, noncarcinogenic effects in humans or
experimental animals.

Risk Characterization

A quantitative assessment of potential risks posed by
contaminants in the vicinity of the SPT site was performed.
The potential for endangerment of human health under a
number of current-use and future-use exposure scenarios
was evaluated.  For each exposure scenario evaluated,
two exposure cases, an average and a plausible maximum
case, were considered.   For the average exposure case,
mean concentrations are used together with what are
considered to be the most likely (though conservative)
exposure conditions.  For the plausible maximum case,
the highest measured concentrations are used, together
with high estimates of the range of potential exposure
parameters relating to frequency and duration of exposure
and quantity of contaminated media contact.

To summarize the risk assessment, carcinogenic risks at
SPT may be associated with exposure to surface soil con-
taminants and airborne particulates under current use
scenarios.  Under future use scenarios, exposure to
groundwater contamination may pose both a carcinogenic and
noncarcinogenic risk.  Risk results for both the current-
use and future-use scenarios are discussed below.  The
risk numbers are presented for carcinogenic risks
greater than 1 x 10~*> or where the Chronic Daily Intake
(GDI) exceeded the Reference Dose (RfD) for noncarcino-
genic risks.  Generally, at SPT these risks are associated
with the plausible maximum scenario, rather than the
average case.

1.  Current-use scenarios: Under current-use scenarios,
    exposure of workers and residents to surface soil
    contaminants in the adjacent vineyard,  through
    dermal adsorption and incidental ingestion, and
    inhalation were considered a carcinogenic risk.
    The plausible maximum risk associated primarily
    with exposure to arsenic and dioxin/furans was 3 x
    10~4, or the risk of three excess cancer cases dur-
    ing a lifetime exposure of 10,000 individuals.

    The plausible maximum cancer risk from exposure of
    trespassers to surface soil contaminants at the
    wood treating facility was 2 x 10~5.  For workers,
    the average risk was 6 x 10~6 and the plausible

-------
                  -23-
maxiraura risk was risk was 4 x 10~3.  Again this
risk is associated primarily with exposure to
arsenic and dioxin/furans.

The plausible maximum risks due to inhalation of
contaminated dust are associated primarily with
exposure to arsenic and chromium.  The risk ranges
from 1 x 10~5 to 5 x 10~6 for locations 250 meters
north and south of the site and 500 meters southeast
of the site.

Under current-use conditions/ groundwater as a
potable supply is not expected to be a potential
health concern, since the GDI is less than the RfD.
This is based on exposure to chromium, which is a
noncarcinogen by ingestion.  The reason the current-
use scenario has no risk is that no drinking water
wells are currently within the groundwater plume
boundaries.  Institutional controls are needed to
ensure that no wells are drilled into the contaminated
area for drinking water purposes, until remediation
is completed.

Future-use Scenarios;  Under future use conditions,
use of the shallow groundwater as a potable supply
may be a potential health concern under the plausible
maximum scenario, where the GDI levels for chromium
could be 49 times greater than the RfD.

For the deep groundwater, risk assessment based on
a mass balance model indicated that the GDIs for
several of the noncarcinogenic contaminants of
concern could exceed their corresponding RfDs under both
the average and plausible maximum scenarios.  This
is due to the potential for future leaching of
contaminants, such as chromium, out of the soil
into the groundwater.

Under the mass balance model, excess cancer risks
associated with exposure to carcinogenic contaminants
(primarily background arsenic) was estimated to be 3 x
10~2.  However, arsenic is not expected to be highly
mobile at SPT, based on observed levels in groundwater.
The mixing model used to derive the risk number did
not account for attenuation of contaminants in the
environment and represents a very conservative estimate
of the potential future risk associated with groundwater
use.   Because of this, arsenic was not retained as a
chemical of concern in the formulation of groundwater
remediation alternatives in the FS.

Under future use scenarios, direct contact with soil
contaminants or inhalation of contaminated particulates

-------
                                 -24-
              over relatively short periods  of  time  by  on-site
              construction workers, are not  expected to be  a
              potential health concern.  This  is  the case for
              exposed individuals under either  average  or plausible
              maximum cases.

      E.   Analytical Methods  Used

          The Endangerment Assessment  for the SPT site  generally
          followed the guidelines established by  EPA for risk
          assessments under CERCLA (EPA 1985a,  1986a) and for
          health risk assessments in general (EPA 1986b,c,d).
          The purpose of the  assessment was  to  evaluate the No
          Action Alternative.  The assessment was based on  data
          generated under the EPA contract laboratory program
          (CLP).

 VI.   DOCUMENTATION OF SIGNIFICANT CHANGES,  Section  117(b)&(c)
      of  CERCLA

      The preferred alternative in the Proposed Plan is the same
      as  the remedy selected  in this ROD: Soil fixation with a
      RCRA cap and conventional groundwater  treatment.   No  signif-
      icant changes are proposed at this time.  Additional  data
      collection activities that will  occur  as  part  of  remedial
      design could impact information  contained in the  ROD.

VII.   DESCRIPTION OF ALTERNATIVES

      A.   Alternative 1 - No  Action

          This alternative involves taking no action to treat,
          contain, or remove  the contaminated groundwater and soil.
          Multi-media monitoring would be performed  every five
          years to support a  reassessment of the  No  Action  Alterna-
          tive.  The costs for this alternative are  as  follows:

          Capital cost                                  $18,000
          Operation and maintenance (OSM) cost  (annual) $22,000
          Present worth (life of project at  8%  dis-
            count and 4% inflation rates)               $90,000

      B.   Alternative 2 - RCRA Cap with Slurry  Wall

          Alternative 2 is a  containment alternative.   The  function
          of the multi-layer  RCRA Cap  is to  prevent  direct  contact
          with soil by humans and wildlife,  and to minimize the
          potential for airborne contamination.   In  addition,  the
          low permeability Cap reduces infiltration  and leaching
          of contaminants from the soil into the  groundwater.   The
          Cap would be constructed over the  areas of contam-
          inated soil that exceed the  cleanup goals. Approximately
          33,300 square feet  of Cap would be required to cover
          these areas, based  on the current  clean-up goals.
          The Cap would meet  the RCRA  closure requirements  under

-------
                      -25-
40 C.F.R. §264, Subparts F, G and N.  An ^example of Cap
construction according to EPA closure guidance would
be:

1.  A 2 foot clay layer with hydraulic conductivity
    no greater than 1 x 10"^ cm/sec.

2.  A minimum 20 mil High Density Polyethylene (HOPE)
    geomembrane.

3.  A one-foot sand layer with a hydraulic conductivity
    of 1 x 10~3 cm/sec and filter fabric.

4.  A two foot top soil layer.

Capping does not eliminate the leaching of contaminants
from the untreated waste left on-site.  Fluctuating
groundwater levels may cause groundwater contact with
contaminated soils.  This may result in additional
contamination at levels above the MCL, particularly for
chromium.

The groundwater component of this alternative is to
install a slurry wall to isolate the contaminated
groundwater from the uncontaminated portion of the
aquifer.  A 1,375 foot long wall would be  keyed into a
clay layer at a depth of 55 feet.  Approximately 75
million gallons of contaminaated groundwater is estimated
to need containment.  Extraction wells would be placed
inside the slurry wall to maintain the hydraulic gradient
toward the contaminated groundwater being  contained.
Monitoring wells would be located downgradient and
outside the slurry wall in order to evaluate the
effectiveness of the wall over time.  The  risks of
leaving contaminated groundwater in the aquifer would
be potential exposure of users to water that does not
meet the drinking water standards.  Therefore, institu-
tional controls to prevent such use are required.

The major limitation associated with the slurry wall
is that the clay layer proposed for its base may not
be thick or continuous enough to support the wall.
Additional investigation of this, clay layer would be
needed to support this alternative.

The aquifer in the Selma area is currently classified
under EPA's Groundwater Protection Strategy, as a Class
II A aquifer, which is currently used for  drinking
water and other beneficial uses.  Also, the Fresno area
has a designated Sole Source Aquifer under the Safe
Drinking Water Act, 42 U.S.C. S1424(e).  Alternative 2
would not be consistent with protection of this groundwater
resource, due to the continued exceedences of the MCL
for chromium and the potential for continued leaching
of chromium or other constituents from the soil.

-------
                           -26-
    Under Alternative 2,  implementation requirements include
    obtaining permission  for use of private property during
    Cap and slurry wall construction.   The slurry wall
    would require permanent easements  or private property
    acquisition along its alignment.  Off-site treatment and
    disposal options for  the extracted groundwater would need
    to be evaluated.

    Long-term institutional controls would be implemented
    to prevent access by  unathorized persons to the capped
    areas, including fencing,  signs and other land use
    restrictions.  Long-term access to capped areas, extraction
    wells, and monitoring wells  would  be needed by government
    officials or representatives to ensure O&M activities
    could occur.  Finally,  long-term institutional controls
    would be needed to prevent the use of the contaminated
    portions of the aquifer as a drinking water supply.

    The implementation timeframe for Alternative 2 would be
    approximately two months for RCRA  Cap construction
    and seven months for  slurry  wall construction, after
    property access agreements have been obtained.

    Costs for Alternative 2 are  as follows:

    Capital:         $2,180,000
    O&M:               $40,000
    Present worth:   $2,390,000

C.  Alternative 3 - Soil  Fixation with a RCRA Cap and
    Conventional Groundwater Treatment

    For soils, Alternative  3 has both  treatment and contain-
    ment components.  The function of  soil fixation, as
    treatment, is to create a  monolithic soil matrix which
    inhibits leaching,  using a stabilization and solidifi-
    cation process.   The  RCRA Cap,  placed on top of the
    fixed soils would provide  additional protection from
    surface disturbance and surface water infiltration.   The
    waste to be treated is  contained in the areas where  the
    soil constituents exceed cleanup goals.  Also, under
    this alternative/ six dry  wells will be evaluated and
    abandoned, as appropriate.

    The arsenic and chromium contamination is considered a
    RCRA characteristic waste  under 40 C.F.R. §261.24.  The
    dioxin and PCP waste  is considered a RCRA K001 listed
    waste under 40 C.F.R. §261.32.   Once excavated, substantive
    RCRA standards for treatment,  storage and disposal of
    these wastes under 40 C.F.R. §264  apply.  In addition,
    disposal of K001 waste  is  regulated under 40 C.F.R.
    §268, Land Disposal Restrictions,  since placement has
    occurred.   The volume of contaminated soils requiring
    treatment  total  approximately 16,100 cubic yards of

-------
                      -27-
raaterial.  Volume estimates will be further refined
during remedial design/ and should be considered
estimates here.

The typical on-site fixation operation includes a batch
plant for mixing the fixative agent (cement/ silicate
materials, and additives)/ and conventional construction
equipment for excavating and backfilling the soil.  The
batch plant and staging area for temporary storage of
contaminated soils is proposed for a 1.5 acre area in
the northwest corner of the SPT site.   The staging area
will comply with RCRA regulations under 40 C.F.R. §264,
Subpart L - Waste Piles/ calling for temporary double
synthetic liners and a double leachate collection
system.  The temporary waste and storage facilities
will also need to comply with the construction standards
for Class I waste piles in Title 23, Subchapter 15,
California Code of Regulations (CCR).   Cap construction
will be as outlined for Alternative 2, and will meet
the same RCRA applicable or relevant and appropriate
requirements (ARARS).

The fixed soil will meet the leachablity requirements
for the appropriate site-specific constituents under
RCRA.  The maximum concentration of arsenic and chromium
characteristic wastes, using EP toxicity, is 5 mg/1
under 40 C.F.R. §261.24.  It is predicted that fixation
will meet land disposal restriction level under 40
C.F.R. §268, of 37 ppm for PCP, using a total waste
analysis test.

Also, as discussed previously, soils will be tested
during remedial design to determine the soluble fraction
of the contaminants and the attenuation factor.  Based
on this testing, treatment goals needed to protect ground-
water will be evaluated by EPA and the RWQCB.  The
RWQCB recommends site-specific cleanup goals under the
authority of the Porter Cologne Water Quality Control
Act California Water Code §§13000 et seq.

Under Alternative 3, residual levels of arsenic, dioxin/
furan, chromium, copper, and phenols below the health
risk-based cleanup goals would remain onsite, untreated.
Based on the Endangerment Assessment for SPT it was
determined that these residuals will not pose an unacceptable
risk to public health or the environment.  The solubility
testing will ensure  that residual levels do not pose  a
risk to groundwater.

There  is a potential for the future breakdown of  the
monolithic soil matrix.  To reduce  this potential  the
fixed soils will be  covered with a Cap that meets  the
RCRA requirements as described under Alternative  2.
Long-term monitoring will also be performed to meet  the
substantive RCRA requirements for closure under 40
C.F.R. §264, Subpart F, G and N.

-------
                      -28-
For the groundwater component of Alternative 3,  a
conventional precipitation, coagulation, and floccu-
lation process is proposed to remove chromium to the
MCL level.  Based on the assumption of a 50 ug/1 MCL
and a two dimensional model, the volume of extracted
groundwater requiring treatment is estimated at  2.7
billion gallons.  This estimate will be further  defined
during the remedial design phase of the project, based
on additional aquifer testing and monitoring well
installation.

Based on the estimate discussed above and the distribu-
tion of the plume, approximately 25, 6-inch diameter
extraction wells, 50 feet deep will be pumped at a
cumulative total of 1,040 gallons per minute for five
years.  This assumes a treatment plant operating 24
hours a day, seven days a week, with an online availablity
of approximately 95%.  The five year timeframe is based
on several assumptions regarding estimates of extent of
contamination, the number of extraction and injection
wells, and the .volume of groundwater requiring treatment.
Specific timeframes will be further defined as part of
RD.  A range of  5-10 years may be more realistic,
depending on the results of data collected during RD.

The treatment facility will consist of an influent
storage tank/ a  rapid mix unit, a slow mix unit, a sedi-
mentation tank,  a filter, a treated effluent storage
area, and associated piping, valves, and pumps.   This
facility proposed for location in the vineyard south of
the wood treating facility, will occupy approximately
1/2 acre.

Based on satisfactory treatment and testing of the ground-
water, either reinjection or off-site disposal will occur.
If reinjection is appropriate, approximately 35, 4-inch
diameter recharge wells will also be distributed throughout
the aquifer.

The treatment level to be achieved is the more stringent
of the federal or state Safe Drinking Water Act Maximum
Contaminant Levels.  Currently this level is 50 ppb,
under both federal and state law.  Residual untreated
groundwater would not exceed the MCL.  Residual treated
groundwater would either be reinjected or disposed of
off-site.  For reinjection, substantive requirements of
the Safe Drinking Water Act 42 U.S.C. §§1421-1422,
40 C.F.R. §5144-147, would be met.  For off-site disposal,
the RWQCB would establish discharge limits consistent
with requirements under the National Pollutant Discharge
Elimination System (NPDES) program.  The reinjection
of treated groundwater will also be regulated by substantive
RWQCB waste discharge requirements to provide protection
of the beneficial uses of the underlying groundwater.

-------
                      -29-
The sludge generated from the treatment facility will
be dried in lagoons on two acres adjacent to the treatment
facility.  The sludge will be disposed of at an approved
off-site RCRA facility or municipal landfill, depending
on sampling results.  The sludge lagoons will be con-
structed to RCRA standards as set forth in 40 C.F.R. §264 -
Subpart K - Surface Impoundments, which require two or
more liners and a leachate collection system.  Synthetic
liners are proposed for use at SPT.  The sludge lagoons
will also need to meet the construction criteria in
Title .23, Subchapter 15 of the CCR, regulated by the
RWQCB.  Other options, for sludge drying, such as
mechanical methods, will be considered during the
design phase.

Regarding implementation requirements for soil remediation
activities under Alternative 3, equipment and materials
for Cap construction are readily available.  Treatability
testing is required for soil fixation, and is currently
being performed.  There are numerous commercial enterprises
involved in developing and marketing fixation technology.
Sixteen companies were identified in a vendor survey as
capable of providing expertise in treating metals and
organics with solidification and stabilization processes.
Access to private property will be needed for the batch
plant and staging areas.

Short-term worker protection during soil excavation
will be required, consistent with federal and California
Occupational Safety and Health Act (OSHA and Cal OSHA)
standards.  EPA currently has federal-lead jurisdication
for worker protection at wood treating facilities.
However, EPA has adopted OSHA standards for use at
these sites.  Excavation, storage, and fixation of soil
are also subject to Fresno Air Pollution Control District
(APCD) Rules 210.1, 404, 405, and 418.  Discharges
during remediation could include:  (1) fugitive dust con-
taining toxic metals and toxic organics, and (2) volatile
toxic organics.  Requirements of the Clean Air Act, 42
U.S.C. S7401 et seq, are incorporated into APCD Rules,
per Section 110 of the Clean Air Act.

For the groundwater component, implementation requirements
include disposal of treatment residuals, utility require-
ments, access to private property for the treatment
plant and sludge lagoons, treatability studies for waste
stream characteristics, and disposal of treated water.
Significant implementation obstacles are not foreseen.

The main uncertainty regarding Alternative 3 is the
implementability of soil fixation based on treatability
testing.  If this test is not successful, it will be
necessary to select a different alternative to remediate
SPT site soils.

-------
                          -30-
    The groundwater classification is Class II A,  and
    implementation of Alternative 3 would be consistent
    with maintaining the use of the aquifer for drinking
    water and other purposes.

    Short-term institutional controls include limiting
    access to the staging area, treatment areas,  and sludge
    drying beds,' through use of fencing,  signs and security.
    Until remediation of groundwater is achieved,  institu-
    tional controls over the use of the contaminated portions
    of the aquifer will be required.  Long-term institutional
    controls include access restrictions  to capped and
    fixed areas, and long-term access for monitoring and
    maintenance activities.

    The implementation timeframe for Alternative  3 is
    approximately 12-18 months for the soil component and
    5-10 years for groundwater treatment.

    Costs associated with Alternative 3 are estimated as
    follows:

    Capital:         $ 6,500,000
    O&M:             $ 1,300,000
    Present Worth:   $11,280,000

D.  Alternative 4 - On-site Rotary Kiln with Off-site
    DjLsjposal and Conventional Groundwater Treatment

    This alternative has both treatment and containment
    (disposal) components.  The groundwater components are
    the same as described in Alternative  3 and will not be
    discussed further here.  The soil treatment component
    applies to the organic constituents in the soil.  An
    on-site rotary kiln would be used to  incinerate dioxin/
    furan and pentachlorophenol wastes totalling  7800 cubic
    yards.  Included with the organic wastes are  metal
    constituents that would not be destroyed during inciner-
    ation.  In addition, there is another 8300 cubic yards
    of metals contaminated soil with no organic contamination.
    All of the soils, treated and untreated (a total of
    16,100 cubic yards), would be disposed of at  an off-site
    RCRA facility.  The SPT wastes containing pentachlorophenol
    would require treatment (e.g., incineration)  prior to
    disposal to meet the present RCRA Best Demonstrated
    Available Technology (BDAT) requirements of 37 ppm,
    under 40 C.F.R. §268.  The untreated  arsenic  and chromium
    contaminated wastes are RCRA characteristic wastes and
    therefore require disposal at an approved RCRA Class I
    facility.

    The mobile unit assumed for SPT is rated at 15 million
    BTU/hour and treats 4.50 tons/hour of dry solids.
    The primary (i.e., rotary kiln) and secondary (i.e.,
    afterburner) combustion chambers are generally mounted

-------
                      -31-
on concrete slabs.  Approximately .5 acres is expected
to be required for stockpiling excavated soil, locating
feed handling and preparation equipment, and temporary
storage of decontaminated soil.  Sufficient area for
processing exists on the storage yard being used by
the present wood treating operation.

For organics, treatment levels achieved would be the
BDAT treatment level requirements for PCP of 37 ppm
and the 1 ppb clean-up goal for dioxin/furan contamination.
For the incinerator, 99.99% destruction and removal
efficiency (DRB) is required under 40 C.F.R. S264,
Subpart 0, for the principal organic hazardous constituents
(POHCs).  The metals would remain untreated, and would
either be captured in the air pollution control equipment
or remain in the incinerated soil residuals.

If BDAT for metals under 40 C.F.R. §268 is in effect at
the time of project implementation, then these levels
would need to be met as well.  For this ROD it is
assumed that the incinerator soil residuals would
require disposal at a RCRA Class I facility due to the
metals content of the residue.

Under the California Air Resources Act, California
Health and Safety Code §39650 et seq, the Air Pollution
Control District (APCD) will set emission limits for
discharges associated with use of the incinerator under
APCD Rule 210.1, New Source Review.  Rules 404, 405, 418
and 417 also apply to excavation and incinerator activ-
ities.  Discharges associated with soil excavation may
consist of:  (1) fugitive dust containing toxic metals
and/or toxic organics, and (2) volatile toxic organics.
Compliance with APCD Rules includes Clean Air Act
requirements.

Implementation requirements include access to a mobile
rotary kiln, of which there may be a limited supply.
Acceptance of SPT wastes at an off-site RCRA facility
would be determined based on waste characteristics and
BDAT requirements in effect at the time of waste disposal.
Access to private property is required for the inciner-
ator, groundwater treatment systems, and monitoring
well installation activities.  Pilot work would be
necessary to aid in addressing materials handling
requirements and to assess air .emissions.

Alternative 4 would be consistent with the area's Class
II A aquifer classification.  The contaminated groundwater
would be treated and contaminated soils would be removed.
The removal of the contaminated soil would prevent the
possibility of continuing migration of the contaminants
to the groundwater.  As stated previously, soil clean-up
goals will be evaluated after solubility testing to
ensure protection of groundwater quality.

-------
                                  -32-
           Institutional controls include short-term access restric-
           tions to the soil and groundwater treatment areas/ and
           restrictions over the use of the contaminated portions
           of the aquifer for drinking water purposes.  Long-term
           institutional controls are not needed for this alternative.

           The soils remediation implementation timeframe for
           Alternative 4 would be 7-10 months at an incinerator
           unit operating 24 hours a day, seven days a week,  with
           online availability of 80%.  An additional 1-2 months
           would be required to demobilize equipment.  Groundwater
           treatment is estimated to take 5-10 years.

           Costs estimated for Alternative 4 include:

           Capital:         $15,630,000
           O&M:              $1,290,000
           Present worth:   $20,360,000

VIII.  SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

       A.  Overall Protection of Human Health and the Environment

           1.  No Action;  No protection is provided, although
               monitoring would provide a warning indicator of
               contaminant transport.

           2.  RCRA Cap with Slurry Wall;  Partial protection is
               provided, with ongoing maintenance.  The migration
               of contaminated groundwater is restricted from
               reaching uncontaminated portions of the aquifer.
               Direct contact with soils and generation of contam-
               inated airborne dust is prevented.  The Cap also
               limits infiltration of surface water and contaminant
               mobility.  Institutional controls are necessary to
               prevent the use of contaminated groundwater exceeding
               primary drinking water standards.  Continued leaching
               of capped soils due to groundwater fluctuations
               could exacerbate the chromium contamination problem.

           3.  Soil Fixation with RCRA Cap and Conventional Ground-
               water Treatment;  For soil, protection is provided
               with ongoing -maintenance.  Cap protection features
               are the same as for Alternative 2.  Addition of the
               fixative agent greatly reduces continued leaching
               of contaminants to groundwater, protecting potable
               water supplies from a continuing source of contamina-
               tion.  Groundwater treatment provides complete
               protection to the MCL cleanup level.

           4.  On-site Rotary Kiln and Off-site Disposal with
               Conventional Groundwater Treatment;  For soil,
               complete protection is provided on-site.  No contam-
               inants exceeding the cleanup goals remain at SPT.
               Careful short-term incinerator operation would be

-------
                          -33-
        required to assure that significant adverse air
        quality impacts do not occur.  For groundwater, the
        same complete level of protection is provided as
        for Alternative 3.

B.  Compliance with ARARS

    1.  Alternative 1:  Does not comply with MCLs for ground-
        water.  No action would be taken to meet ARARS.

    2.  Alternative 2;  Does not comply with MCL for chromium
        or Porter Cologne Water Quality Act cleanup goals
        for soils (a requirement "to be considered," rather
        than an ARAR).  Would comply with RCRA requirements
        under 40 C.F.R. §264, Subparts F, G, and N.

    3.  Alternative 3;  Will comply with all ARARS, including
        MCLs, RCRA BDAT for K001 listed waste, and RCRA
        closure requirements.

    4.  Alternative 4;  Would comply with all ARARS identified
        at this stage, including MCLs, RCRA BDAT for K001
        listed waste,  and RCRA requirements for off-site dis-
        posal of waste.   .

C.  Long-term Effectiveness and Permanence

    1.  Alternative 1;  Not a permanent solution.

    2.  Alternative 2;  Not a permanent solution.  Long-term
        monitoring and maintenance activities are associated
        with the Cap.   Groundwater is not treated.  Long-
        term institutional controls would be required to
        ensure that drinking water wells are not located in
        the contaminated portions of the aquifer.

    3.  Alternative 3;  For soil, full permanence cannot be
        assured due to limited experience with the fixation
        technology.  Long-term maintenance and monitoring
        is required.  Depending on the monitoring results,
        additional work could be required in the future if
        the monolithic soil matrix breaks down.  For ground-
        water, a permanent solution.

    4.  Alternative 4;  For soil, a permanent solution for
        organics (dioxin/furans and PCP); but not permanent
        for metals.  Off-site disposal requires long-term
        O&M at the RCRA facility.  For groundwater, a
        permanent solution.

D.  Reduction in Toxicity, Mobility and Volume (TMV)

    1.  Alternative 1;  Does not reduce TMV.

    2.  Alternative 2:  Reduces mobility but not toxicity or
        volume.

-------
                         -34-
    3.   Alternative  3;   For  soil,  mobility  significantly
        reduced,  toxicity  is not  reduced, and  volume  is in-
        creased due  to  the addition  of  the  fixative agent.
        For groundwater, TMV reduced.

    4.   Alternative  4;   For  soil,  near  complete  reduction of
        toxicity and mobility for  organics.  For metals,
        reduces mobility only by  removing contaminants from
        the site and containing them in a Class  I  RCRA facil-
        ity.  For groundwater,  TMV reduced.

E.  Short-term Effectiveness

    1.   Alternative  It   There would  be  no short-term  impacts.

    2.   Alternative  2t   Short-term impacts  to  workers
        associated with slurry wall  and Cap construction
        would be minimal.

    3.   Alternative  3t   Short-term exposure to workers during
        soil excavation and  treatment,  and  groundwater well
        installation could occur.  Worker safety precau-
        tions and dust  suppression needed to protect  workers
        and others onsite.and in  site vicinity.

    4.   Alternative  4;   Short-term impacts  would be comparable
        to Alternative  3.  Differences  include short-term
        potential for accidental  spillage during off-site
        transport of wastes  and exposure to incinerator
        emissions.  Air pollution  control equipment and
        careful transport  required in addition to  measures
        outlined in  item 3,  above.

F.  Implementability

    1.   Alternative  It   No implementability factors are
        relevant.

    2.   Alternative  2t   The  technology  for  both  the RCRA Cap
        and slurry wall are  readily  available.  The technical
        feasibility  of  the slurry  wall  is questionable due
        to potential problems with inadequate  thickness and
        continuity of the  clay layer.   Access  problems assoc-
        iated with the  slurry wall alignment may also arise.

    3.   Alternative  3;   The  RCRA  Cap and conventional ground-
        water treatment technologies are readily available
        and proven.   Property access/acquisition problems
        may arise for the  well installation and  treatment
        areas.  Fixation technology  requires site-specific
        treatability testing to verify  effectiveness  prior
        to use.

-------
                               -35-
             Alternative 4;  Conventional groundwater treatment
             issues are the same as under Alternative 3, above.
             Use of incinerator requires prior on-site treat-
             ability testing in coordination with the local
             APCD.  Off-site disposal of wastes requires acceptance
             by the receiving facility depending on actual waste
             characteristics analysis.  Regulatory status governing
             off-site disposal of land ban wastes may influence
             disposal options at time of remedial action.
         Estimated Capital, O&M, and Present Worth Cost
                                CAPITAL
O&M
PRESENT WORTH
Alt 1 No Action
Alt 2 Slurry Wall/
RCRA Cap
Alt 3 GW Treatment/
Fixation
Alt 4 GW Treatment/
Rotary-Kiln/
Off-Site Disposal
$18,000
2,180,000
6,500,000
15,630,000
22,000
40,000
1,300,000
1,290,000
90,000
2,390,000
11,280,000
20,360,000
     H.  State and Community Acceptance

         1.  Alternative 1;   Not acceptable to the state; no
             input was received from the community.

         2.  Alternative 2;   Not acceptable to the state due to
             potential insufficiency of clay layer to key slurry
             wall into and because chromium remaining in soils
             under the Cap could leach to groundwater.   No
             community input received.

         3.  Alternative 3;   Acceptable to the state.  Additional
             remedial design-related groundwater and soil sampling
             and treatability testing will be reviewed by the state
             for continued acceptance of remedy.  No community
             comments received.

         4.  Alternative 4;   State concerned about potential
             incinerator emissions-related public perception and
             regulatory approval problems.   Incinerator pilot
             testing and remedial design-related sampling results
             would be reviewed by the state.  No community
             issues raised at this time.

IX.   THE SELECTED REMEDY

     Alternative 3 - Conventional Water Treatment and Soil Fixation
     with a RCRA Cap, has been selected as the remedy for the
     SPT site.   Remediation  of the chromium contaminated groundwater
     under this alternative  consists of pumping the groundwater
     from the aquifer, treating it in an on-site facility utilizing

-------
                               -36-
    a conventional water treatment method,  and disposing of the
    treated effluent through reinjection into the aquifer, or
    off-site, as appropriate.

    The soil remediation component of this  alternative consists of
    excavating the contaminated soil, transporting it to a pro-
    cessing plant onsite;  "fixing" the soil with cement, silicate
    and other bonding agents;  and then backfilling and compacting
    the fixed material on-site.  Fixed areas of soil will then be
    covered with a RCRA Cap.

X.  THE STATUTORY DETERMINATIONS

    A.  Protection of Human Health and the  Environment

        The selected remedy will eliminate  risk of exposure to
        groundwater contaminated with chromium above MCL levels.
        The remedy will eliminate exposure  to contaminated soil
        that exceeds groundwater and health based cleanup
        goals.  In the case of soils, the contaminants will not
        be removed or destroyed.  Long term O&M is required to
        ensure that the soil remedy is effective.

        Adequate safety precautions will be used during construc-
        tion and treatment activities.  Therefore, unacceptable
        short-term impacts are not expected.  Cross media
        impacts are also not foreseen associated with this
        remedy.  Careful attention to drilling techniques will
        be paid to ensure that drilling will not contaminate
        the deeper, unaffected portions of  the aquifer.  Cleanup
        goals will take into account the potential leaching of
        soil contaminants into the groundwater.  Careful dust
        suppression methods during all remedial activities will
        ensure that contaminants are not transmitted into the
        air at unacceptable levels during construction.  The
        RCRA Cap will provide  long-term protection agaist trans-
        mission of contaminated particulates into the air.

    B.  Attainment of ARARS

        The selected remedy will attain the applicable or relevant
        and appropriate requirements determined to date; no
        ARARS waiver is necessary.  The following are the main
        ARARS that have been determined to  apply to the remedy:
            Statute

        Safe Drinking Water Act
        42 U.S.C.  §300A ejt seq;
        40 C.F.R Part 141.

        Safe Drinking Water Act
        42 U.S.C.  §300A e_t seq;
        40 C.F.R.  Parts 144-147.
   Standard

Maximum contaminant levels
for chromium and arsenic
in groundwater.

Underground injection
control requirements for
Class V Wells, including
dry wells.

-------
                       -37-
 Safe Drinking Water Act
 42 U.S.C. §1424(e).
 Resource Conservation
 and Recovery Act
 42 U.S.C. §6901 et seq;
 40 C.F.R. Parts 257, 261,
 262, 263, 264, 265, 268.
 California Safe Drinking
 Water and Toxic Enforcement
 Act.  California Health and
 Safety Code §252.5 et seq.

 California Air Resources
 Act.  California Health and
 Safety Code §39650 et seq.
 Porter Cologne Water
 Quality Control Act.
 California Water Code
 §13000 et seq.
 California "Superfund"
 Law - Hazardous
 Substances Account Act/
 Hazardous Substances
 Cleanup Bond Act.
 California Health and Safety
 Code §25300 et seq.

California Occupational
Safety and Health Act.
California Laboratory
Code §6300 et seq.

Occupational Safety and
Health Act.  29 U.S.C.
§651 et seq.

Cost-Effectiveness
Prohibits any project with
federal financial assistance
from contaminating a Sole
Source Aquifer.

Practices to be followed by
generators, transporters,
owners and operators of
hazardous waste.  Standards
for land disposal of certain
restricted hazardous wastes.

The state MCL for
chromium.
Discharge limits for
activities conducted
during the remedial
action.  Includes Clean
Air Act requirements.

Waste discharge requirements,
NPDES discharges, specific
cleanup standards estab-
lished on a site specific
basis.

Substantive requirements
of a Remedial Action Plan
(RAP).
Standards for worker
protection during remed-
iation.
Under 40 C.F.R. §300.38,
OHSA requirements apply to
all activities conducted
under the NCP.
The selected remedy estimated at $11,280,000 is the
least expensive of the remedies that meet the statutory
criteria of protection of public health and the environ-
ment, and attainment of ARARS.  For example, alternative
4, Conventional Water Treatment/Incineration and Off-site
Disposal is estimated at $20,360,000; almost double the
selected remedy.  Alternative 2, slurry wall/RCRA Cap,

-------
                            -38-
    is much less costly than the selected remedy at an esti-
    mated $2,390,000; but would not be protective of public
    health or meet ARARs.

D.  Utilization of Permanent Solutions Employing Alternative
    Technologies to the Maximum Extent Practicable (MEP)

    The selected remedy is an appropriate solution for the
    site.  It will effectively treat groundwater contaminants,
    prevent contact with soil contaminants,  and prevent leach-
    ing of contaminants to the groundwater at levels above
    the MCL.   The remedy provides protection of public
    health, achieves ARARS compliance and is cost-effective.

    In comparison, on-site and off-site RCRA disposal options
    are more  problematic for soils at SPT than the chosen
    method of fixation.  An on-site RCRA landfill would not
    meet RCRA or CCR siting criteria due to  the site geology
    and presence of a Sole Source Aquifer.  Since BDAT was
    not established for the dioxin K001 waste, it could con-
    ceivably  be disposed of off-site, along  with the metal
    contamination, without treatment.  The PCP wastes would
    require treatment to the 37 ppm BDAT standard.  However,
    straight off-site disposal of wastes does not comply
    with the intent of CERCLA for remedies that use permanent
    solutions and treatment to the maximum extent practicable.
    Finally,  the regulatory status governing land disposal
    of SPT waste  is in a state of development.  It is not
    certain whether RCRA disposal facilities would accept
    SPT wastes  at the  time of remediation; and  if so, what
    Best Demonstrated Available Technology  (BDAT) would  be
    required  (BDAT may be promulgated  for arsenic).

    In regard to  soil  treatment methods,  fixation and  inciner-
    ation were  the only  two that were  deemed  technically
    feasible in the FS screening process.  Incineration,
    however, treats only the organic contents of the SPT
    waste, resulting in untreated metals  requiring disposal.
    Fixation has  been  identified as a  feasible  technology
    for  the low organic/high metals ratio in  the SPT wastes.
    (Treatability testing will be performed to ensure that
    this method will effectively treat SPT wastes).  The
    sandy-silty soil composition at SPT  is also amenable to
    fixation.

    Several nonthermal treatment process  for  removing  soil
    contaminants  at  SPT  were examined,  including physical,
    chemical, and biological.  Of the  physical  methods,  (fix-
    ation  and soil washing), soil washing was found not  to
    be effective  for removing the relatively  low  arsenic and
    chromium concentrations  in  the waste, and is  not  an
    effective remedy for organic wastes.  For chemical methods,
    nucleophilic  substitution, or KPEG,  only  applies  to  the
    organics and  has not been demonstrated effective  in  removing
    the  dioxin/furan concentrations  to the  1  ppb  level.

-------
                       -39-
Biological treatment processes,  both on-site and in-situ.-
were examined for soil treatment.   Biological treatment
applies only to the organic contaminants in the waste, and
does not treat the metals.   However, laboratory tests did
not show reduction of dioxins to the 1 ppb level and no
large scale pilot studies have been conducted on use of
biodegradation for dioxin wastes.

For groundwater treatment,  the metals-precipitation
chromium removal technology selected for groundwater
cleanup is a conventional and effective method commonly
used in industrial processes.  The other groundwater
treatment method evaluated in detail was ion exchange.
However, ion exchange processes would not be effective
in treating site groundwater due to the potential for
clogging of the resins.  Clogging occurs as the trivalent
chromium in the water will readily precipitate out of
solution as chromium hydroxide.   In addition, large
quantities of brine are generated, increasing costs over
conventional treatment without greater protection.

Therefore, in comparison to other possible technologies,
soil fixation with a RCRA Cap and conventional groundwater
treatment have been determined to be the most appropriate
technologies for the SPT site.

For groundwater, the remedy selected is considered the
maximum extent to which a permanent solution and treatment
can be practicably utilized.  For soil, full permanence
cannot be assured due to limited experience with the
fixation technology.  Therefore, long-term monitoring is
required.  In terms of treatment, the contaminants are
rendered immobile by application of the fixative agent.
However, this form of treatment does not reduce contaminant
volume or significantly reduce toxicity.

A fully permanent treatment solution for the combination
of wastes present in the SPT soil was not determined to
be feasible at this time.  Therefore, the selected remedy
represents the maximum extent to which permanent solutions
and treatment can be practicably utilized.

-------

-------
2

-------

-------
                                                           SFUNO RECORDS CTR

                                                             1047-00465
                          ATTACHMENT 2
          SELMA PRESSURE TREATING COMPANY SUPERFUND SITE

                              Final
              EXPLANATION OF SIGNIFICANT DIFFERENCES
                 From the 1988 Record of Decision

I.   Introduction

     On  September  24,  1988,  the  United  States  Environmental
Protection Agency  (EPA) signed a Record of Decision (ROD) for the
final  remedial actions  at the  Selma Pressure  Treating Company
Superfund site, located in Selma, California.  The EPA is the lead
agency for the investigation and clean up of the  site; the primary
state  agency  is the  California  Environmental  Protection Agency,
Department of Toxic Substances Control.

     Since 1988, the EPA has been conducting treatability studies,
collecting additional field data,  and preparing  design plans and
specifications for construction  of the remedy.   In the course of
conducting these additional studies and preparing  detailed designs,
the EPA in consultation with other regulatory agencies has modified
certain aspects of the remedial actions and clean up levels.  The
purpose of this document is to explain the significant differences
that have come about since the  ROD  was written in 1988.   These
differences, though significant, are not a fundamental alteration
of the remedy described in  the ROD.

     Under Section 117 of the Comprehensive Environmental Response,
Compensation, and  Liability Act  of 1980,  as amended (CERCLA),  42
U.S.C. §9617, and  pursuant to 40 C.F.R. Section 300.435(c)(2)(i)
(55  Fed.Reg.  8666,  8852   (March  8,  1990)), EPA is required  to
publish an Explanation of Significant Differences (ESD) whenever a
significant  (but  not fundamental)  change  is  made  to a  final
remedial action plan  as described  in a ROD.

     This document provides a brief background of the Selma site,
a summary of the remedy selected in the ROD, a description of the
changes to  the  ROD  that. EPA is  now  making  (including how  the
changes affect  the remedy originally selected by the  EPA  in the
1988 ROD),  and  an explanation  of why the EPA  is making these
changes to the ROD.

     The EPA is issuing this ESD to clarify certain aspects of the
clean  up  standards for the site,  to explain changes  in certain
remedial  action details  described in the  ROD,  and to document
compliance  with Land Disposal  Restrictions  under the Resource
Conservation and Recovery Act through a Treatability Variance.

-------
     This BSD:

     (A)  changes the term "clean up goal" to "clean up standard"
wherever it is used in the ROD;
     (B)   revises the clean  up standard for arsenic  in surface
soils from 50 mg/kg to 25 mg/kg, a more stringent standard;
     (C)  sets a clean up standard  for pentachlorophenpl in ground
water at 1 ppb to comply with  a new, more stringent drinking water
Maximum Contaminant Level  (MCL)  and sets  a  clean up standard for
pentachlorophenol in soil at 17 ppm;
     (D)  identifies additional areas  of  soil contamination that
require excavation and treatment, and revises the total volume and
on site disposal location;
     (E)  modifies the implementation of the ground water extrac-
tion and reinjection system to reflect a more phased, .observational
approach for the siting  and design of  the wells,  with  an initial
phase consisting of 4 extraction and 6 reinjection wells; and
     (F) documents compliance with RCRA Land Disposal Restrictions
through a Treatability Variance for the contaminated soil.

     As required by 40 C.F.R.  Section 300.825(a)(2), the BSD will
become part of the Administrative Record file for the Selma site.
This file is  available for public review during  normal business
hours in the  EPA Region 9 Super fund Record Center,  75 Hawthorne
Street, San Francisco, California,  94105.


     Remedy

     Site History

     The Selma site is located in Fresno County, California, about
15 miles south of Fresno and adjacent to the southern city limits
of Selma.  The site comprises approximately 18 acres, including a
4 acre wood treatment facility and 14 acres of adjacent vineyards
that were used for site drainage.   Zoned for heavy industrial use,
the site  is located in  a transition zone between  agricultural,
residential, and  industrial areas.  There are 12 residences and
businesses within 1/4 mile of the site.

     The  company that  originally  operated  at  the site,  Selma
Pressure  Treating  Company,   ceased   operation   and  filed  for
bankruptcy in 1981.   There is  another wood treating company, Selma
Treating Company, currently leasing the land and operating on the
site.

     The wood preserving process originally employed at the site
involved dipping wood into a mixture of pentachlorophenol and oil,
and then drying  the wood in open racks to let the  excess liquid
drip off.  A new facility was  constructed in 1965, and the company
converted  to  a  pressure  treating process  which  consisted  of
conditioning   the   wood  and   impregnating   it  with  chemical

-------
preservatives.   Known  chemical preservatives used  at the  site
include Fluor-chromium-arsenate-phenol, chromated copper arsenate,
pentachlorophenol,  copper-8-guinolinolate,  LST  concentrate,  and
Woodtox 140 RTU.

     Prior to 1982, discharge practices included: (1)  runoff into
drainage and percolation ditches, (2)  drainage into dry wells, (3)
spillage onto open ground, (4) placement into an unlined pond and
a sludge pit, and (5) discharges to the adjacent vineyards.

     Contamination Problems

     Efforts by regulatory agencies to get  the  company to comply
with  clean up  orders  were   unsuccessful  and  the  company  went
bankrupt in 1981.  EPA placed the site on the National Priorities
List of hazardous waste sites in 1983.

     A Remedial Investigation/Feasibility Study  was  conducted by
the EPA  to characterize  the  areas of contamination  and  develop
clean up alternatives for the site.   The investigations revealed
several areas of  soil contamination and a  plume of  contaminated
ground water eminating from the site.  Elevated levels of the heavy
metals arsenic,  chromium and  copper were  found in both surface and
subsurface soils.  Soil analyses also showed  elevated levels of the
organic compounds pentachlorophenol (PCP) and dioxin/furan.  While
there were  several  contaminants at elevated levels in  the soil,
chromium  was the only  contaminant  found  to  be  significantly
elevated in the ground water.

     Additional soil and groundwater studies were conducted after
the ROD was signed to provide more detailed characterization for
the design of the remedial actions.  The supplemental investigation
of the soils provided a more accurate delineation of  the areas of
contamination and identified  additional areas needing remediation.
The  supplemental ground  water  investigations   provided  a  more
accurate picture  of  the extent of contamination and  the  pumping
characteristics of the aquifer,  and revealed that the ground water
table had dropped to below the elevations where the highest levels
of  chromium had  been  found  during  the original  investigation.
Sampling and analysis of the ground water utilizing more sensitive
protocols also revealed that PCP may be present in levels exceeding
a new, more stringent drinking  water MCL  of l  ppb,  promulgated
after the ROD was prepared (the previously proposed MCL for PCP had
been 37 ppb).

     Remedy Selected in the 1988 ROD

     The remedy  selected in  the original Record of  Decision is
composed of two  components, one  for contaminated soils and one for
contaminated ground water.  The soil remediation component consists
of excavating the  contaminated  soil,  treating it on  site  with a
fixative  agent,  and then backfilling and  compacting the  fixed

-------
material on site,  fixed areas of soil were then to-be covered with
a RCRA cap.  For remediation of the contaminated ground water, the
ROD calls for extraction and treatment of it in an on site facility
utilizing  a conventional  precipitation,  coagulation, and  floc-
culation process, with either reinjection or off site disposal of
the treated  effluent,  and disposal of sludge  at an  approved off
site  landfill.    Institutional  controls  were  also  required  to
prevent future  activities  or developments on  the  site that could
impact the integrity and maintenance  of capped materials or create
opportunities for  increased exposures such as those  that  would
occur in a residential area.

     The ROD defined clean up goals for the soil and ground water
components in terms of organic and heavy metal contaminants that,
according  to   the  risk   assessment,  would   act   as  indicator
contaminants and drive the clean up.  For  soils the  two driving
organic and heavy metal contaminants were found to be dioxin/furan,
with a clean up  goal of 1 ppb by TCDD  equivalents, and arsenic with
a clean up goal  of 50 ppm.  For ground water the ROD set a single
clean up goal of 50 ppb for total  chromium, which  was the MCL at
the time.

     Criteria were also established for treatment of the excavated
soil prior to redisposal.   Treated soil was required to meet RCRA
requirements. The maximum concentration of arsenic and chromium in
treated soil, using EP  toxicity testing, was 5 mg/1 under 40 C.F.R.
Part 261.24, and 37 ppm for PCP using a total waste analysis under
40 C.F.R. Part 268.

III. Description of the significant Differences and the Basis for
     ThoseDifferences

     This ESD clarifies and modifies several portions of EPA's 1988
ROD for the Selma site.  To the extent that this ESD differs from
the ROD, the ESD supersedes the ROD.

     The fundamental nature of the remedial actions for the Selma
site  have  not  changed;   contaminated  soils  are  still  to  be
excavated, treated with a  fixative  agent,  disposed of on site, and
capped in accordance with RCRA standards.   Ground water is still to
be extracted, treated  using conventional  precipitation to remove
chromium contamination, and reinjected into the aquifer.

     Certain aspects of the remedy have been modified as a result
of 1)  additional data gathered subsequent to the ROD; 2) changes in
Federal and State promulgated standards for contaminants found at
the site;  3)  reconsideration during the  design phase  of certain
aspects of technical and material handling; and 4) clarification of
the applicability of RCRA Land Disposal Restrictions for soil and
debris.  The significant changes from the ROD,  and the rationale
for those changes,  are as follows.

-------
     A.   Clean up Standards

     This ESD uses the term "clean up standard" rather than "clean
up goal".  This ESD changes the term "clean up goal" to "clean up
standard" wherever it occurs in the 1988 ROD.

     B.   Clean up standard for Arsenic in Surface Soils

     The clean up standard for  arsenic in surface soils identified
in the ROD,  50 ppm,  was selected to be protective  of  all direct
contact exposure scenarios except on site residential development.
The ROD further required implementation of institutional controls
to prevent future on site residential development.

     Upon subsequent consultation with the California Environmental
Protection Agency and review of other RODs from throughout the U.S.
that have subsequently  set  arsenic clean up standards  for direct
contact exposure scenarios/ EPA has determined that a lower clean
up standard  for arsenic  is appropriate,  and  would not  rely on
institutional  controls  to assure  adequate  health  protection.
Therefore, a new clean up standard of 25 ppm has been established
for arsenic in surface soils at the Selma site.  All surface soils
(down to a depth of five feet)  containing arsenic in excess of 25
ppm shall be excavated, treated, and disposed of beneath a RCRA
cap.

     c.   Clean up Standard for Pentachlorophenol in Ground Water

     The 1988 ROD did not identify a specific clean up standard for
PCP in ground water, since it had not been detected in ground water
at levels any where near the MCL proposed at the time the ROD was
signed, 200 ppb.  Subsequent revisions  to the drinking water HCLs
have resulted  in the  PCP level being lowered to l ppb.   PCP has
been  detected in  ground water  on or  near the  site  in  levels
elevated above 1 ppb.   Therefore, this  ESD establishes  a clean up
standard of  i ppb for PCP  in ground water at the Selma site, and
requires that the treated effluent from the ground water treatment
plant meet the same standard before it  is  reinjected or otherwise
discharged.

     The new, stricter MCL for PCP came about due to new evidence
on the potential carcinogenicity  of the compound.   Based on this
information,  EPA and California DTSC re-evaluated the  need for a
soil clean up standard for PCP; based on our risk analyses, a new
soil clean up standard of 17 ppm has  been selected to assure that
direct human exposures to  soil  at the  site do not  exceed the
acceptable risk range prescribed iri  the NCP, and to assure that
residual levels remaining at the site do not have the potential to
cause ground water contamination.

     It  should  be noted  that  the federal  MCL for chromium was
changed in July 1992, from 50 ppb to 100 ppb.  Since the California

-------
State MCL has not been relaxed,  we have retained the sane clean up
standard for chromium in ground water that was selected in the ROD,
50 ppb.  Should the State MCL be revised to match the federal MCL,
the clean  up standard for chromium in ground water  at  the Selma
site will also be adjusted to 100 ppb.

     O.   Additional Areas of Soil Contamination to be Excavated

     The 1988  ROD identified four areas  where  contaminated soil
exceeded clean up standards and required clean up.  At the time of
the ROD,  the  total volume  of soils  requiring remediation  was
estimated at 16,100 cubic yards, and the treated soils were to be
backfilled into the areas from which they were  excavated.

     Subsequent soil  investigations provided more  precise volume
estimates and identified additional areas where contaminated soil
exceeds clean up standards and requires excavation and treatment.
The revised  list  of  areas requiring excavation  are identified in
Table A.   The new estimate for the total volume  of contaminated
soil to be excavated is now 11,500 cy.  Also, rather than returning
treated soils to the areas where they were excavated, all treated
soils will  now be consolidated into  a  single  unit  on  the site,
under a single RCRA cap.

     E.   Changes in  the  Design of the Ground  Water Extraction,
          Treatment, and Disposal System

     The ROD described the ground water remediation both in concept
(i.e.  extraction  of ground water exceeding  MCLs,  treatment,  and
disposal either  by reinjection or  off site discharge),   and in
detail (construction of 25 extraction wells,  50 feet deep, pumped
at a cumulative total of 1,040 gallons per minute).  Although the
concept remains the same  (with the addition of  the 1 ppb clean up
standard for PCP  identified  in  paragraph  C above),  the  design of
the extraction and treatment system has been modified.  Rather than
installing 25  wells,  the ground water extraction  system  will be
developed in phases, with the first phase consisting of 4 wells,
screened at  a depth  of 70  feet.   The treatment  plant  will be
constructed to an effective design capacity of 250 gpm, and will be
expandable.   Treated effluent  will be  discharged back into  the
aquifer through 8 injection wells.   Based on information gathered
from  the  operation  of  this  initial   phase   of  ground  water
extraction, treatment, and reinjection, additional wells  will be
installed  and/or additional  treatment plant  capacity  will  be
constructed, as appropriate.

     F.   Documentation   of  Compliance   with   Land   Disposal
          Restrictions  through  a   Treatability  Variance  for
          Contaminated Soil

     As described in  the  original  Record of Decision,  RCRA Land
Disposal Restrictions  (40 C.F.R. Part 268) are  applicable to the

-------
                                 TABLE A


                               CONTAMINATED
                            SOILS EXCAVATION***
Area
A
B
C
D
E
T'
G
E
TOTAL
Location
West half of South Percolation
East half .of South Percolation
Unlined Waste Disposal Pond
West half of North Percolation
Ditch
East half of North Percolation
Ditch
Wood Treatment Area
Cal Trans Ditch
Southeast Disposal Area HI
H2
H3
Length
(feet)
335 ft
135 ft
122 ft
235 ft
185 ft
N/A
141 ft
N/A
N/A
N/A
Width
(feet)
14 ft
14 ft
70 ft
14 ft
14 ft
"M25 ft)!
14 ft
"r(25 ft)'
"r.(2S ft)'
"j:(25 ft)'
Depth
(feet)
10 ft
10 ft
*10 ft
25 ft
10 ft
5 ft
1 ft
5 ft
5 ft
10 ft
Soils Volume
(cubic yards)
1740 cy
700 cy
3160 cy
3050 cy
960 cy
360 cy
75 cy
1455 cy
I
f***ll,500 cy
**
»**
Average Depth
Circular Surface Area
Does not include "Possible Contaminated Soils", which, as shown in the Plans,
must also be excavated.

-------
remedial actions for contaminated soil at the Selma.site.  However,
the  ROD did  not  appropriately  identify  the means by  which the
remedial actions will comply with the LDRs.  The ROD inaccurately
stated that the contaminated soil is considered to be a K001 listed
waste under 40 C.F.R.  Part 261.32.   K001  is a  class  of listed
wastes  under RCRA  consisting  of sludges and tank bottoms  from
treatment processes for wood preservative wastes.  The soil at the
Selma site  became contaminated  from dripping, spillage,  and the
direct  discharge  of  spent wood  treating solutions  onto  the
property.   The levels of contamination  exceed the  threshold for
RCRA  characteristic wastes.    Therefore,  the  Selma  soil  is  a
characteristic, rather than a listed RCRA waste.

     Because  the  contaminated  soil  at the  Selma  site  is  a
characteristic RCRA waste, treatment must comply with Land Disposal
Restrictions.   Often,  Superfund wastes differ significantly from
the waste used to set the  LDR  treatment standard (LDR treatment
standards are generally based on treating less complex matrices of
industrial  process  wastes,  rather  than contaminated soil  and
debris).  Since treatment standards have not yet been promulgated
for soil and debris,  there is a presumption that Superfund response
actions involving the placement  of soil and debris will utilize a
Treatability Variance to comply with the LDRs.

     The selected remedy for contaminated soils at the Selma site
will comply with the LDRs through a Treatability Variance under 40
C.F.R.  Part  268.44.   This  Variance  will result  in the use  of a
fixation/solidification technology to attain the Agency's interim
treatment level range for the contaminated soil at the site.   The
treatment level range established through a Treatability Variance
for each constituent as determined by the indicated analyses are:

Pentachlorophenol        90 - 99% reduction (TWA)
Chromium                 95 - 99.9% reduction (TCLP)
Arsenic                  90 - 99.9% reduction (TCLP)

     Based on  treatability  studies conducted on  the contaminated
soil  from the  Selma  site,  it  is  anticipated  that  full  scale
operation  of  the selected  technology  will comply  with  these
standards.

IV.  support Agency comments

     The California Environmental Protection Agency, Department of
Toxic Substances Control was provided an opportunity to comment on
this draft ESD before it was sent out for public review.  Based on
comments  received  from DTSC,  EPA  added  language in .the  ESD
pertaining  to  the  soil   clean up   standard   of  17   ppm  for
pentachlorophenol.

-------
V.   Affirmation of the statutory Determinations  .

     Considering the  new  information  that  has  been developed and
the changes that have been made to  the selected remedy,  the  EPA
believes that the remedy remains protective of human health and the
environment, complies with federal and state requirements that were
identified in the ROD and  in this ESD as applicable or relevant and
appropriate  to this  remedial  action  at  the  time  this ESD  was
signed, and  is cost-effective.   In addition,  the revised  remedy
utilizes permanent  solutions and alternative treatment technologies
to the maximum extent practicable for this site.

VI.  Public Participation

     A public notice fact  sheet describing  this  Explanation  of
Significant Differences was distributed to people on EPA's mailing
list of  interested community members  for  the  Selma site  in  May
1992.  A public notice was also  placed  in the Fresno Bee newspaper
on May 8,  1992.  The fact  sheet  summarized the changes proposed in
the draft ESD, identified  the repository in Selma where the  entire
text of the draft ESD could be reviewed, and provided a period for
public comments  from May  8 to  June 8, 1992.   (A public comment
period was included  for   this  ESD because  EPA  invoked a  RCRA
treatability  variance.)   EPA received no public  comments  on  the
draft  ESD.    Therefore, the changes identified  in this ESD  are
identical to the changes identified in the version made available
to the public in May 1992.
    r^-^**-
John C. Wise                                      Date
Deputy Regional Administrator

-------

-------
                                        034 00282
            ATTACHMENT 3



TECHNICAL MEMORANDUM ON THE RESULTS

                 OF

  REMEDIAL DESIGN PERCOLATION TESTS

               AT THE

SELMA PRESSURE TREATING SUPERFUND SITE
            PREPARED FOR
U. S. ENVIRONMENTAL PROTECTION AGENCY
        75 HAWTHORNE STREET
       SAN FRANCISCO, CA 94105
                BY
        BECHTEL NATIONAL, INC.
           50 BEALE STREET
        SAN FRANCISCO, CA 94119

-------

-------
                           TABLE OF CONTENTS
1.0   SCOPE OF WORK PERFORMED

     1.1    Subcontractor Responsibility
     1.2    Borehole Permeability Tests
     1.3    Monitoring Wells
     1.4    Percolation Pit Construction and Testing

 2.0  SUMMARY OF TEST RESULTS

     2.1    Borehole Permeability Test Results
     2.2    Percolation Test Pit Results
     2.3    Recommendations for Recharge Pond
                                 FIGURES

Figures

      1      Site Plan: Location of Percolation Test Pit
      2      Percolation Test Pit As-Built


                              ATTACHMENTS

Attachments

      1      Results of Geologic Logging, Well Installation and Permeability Testing
      2      Percolation Pond Infiltration Test Data
      3      Recharge Test Infiltration Rate and Treatment Plant Pond Size
Selma\Submittal No. 8                            j                             9/16/96

-------

-------
1.0    SCOPE OF WORK PERFORMED

Bechtel prepared, issued, and negotiated an invitation for bid for subcontract services at
the Selma Pressure  Treating  site to provide  all necessary  labor, tools,  supplies,
equipment, personnel, transportation, supervision, suppliers, and materials to: drill test
boreholes; perform borehole  permeability tests;  construct monitoring wells; construct,
test, and backfill a percolation test pit; and construct, perform  infiltration test on, and
abandon (if required) stone  columns, if necessary.  Based on results of the  initial
borehole permeability tests, construction  of stone columns (Option 2) was not required
and construction of a percolation test pit (Option 1) was conducted.

By investigating local suppliers and conditions, Bechtel arranged the required water
supply for the percolation test under an agreement with the California Water Services
Company and the Upright Platform Company, adjacent to the Selma site, to supply a
metered-hydrant water supply at commercial rates.  Bechtel provided expert oversight
and procured subcontracted plumbing services for meter hookup, piping, and valves
required to deliver a constant, reliable water supply.

The work was performed in the following sequence, under Bechtel supervision, by the
subcontractor:

    •     Drilled boreholes and performed permeability tests;
    •     Constructed monitoring wells;
    •     Constructed .a percolation test pit;
    •     Performed percolation testing;
    •     Backfilled pit; and
    •     Breakdown of equipment, cleaned and restored work site.

1.1    Subcontractor Responsibility

BSK & Associates, Inc., performed all field work at the Selma site and constructed a
temporary working pad adjacent  to the test pit location, surrounded  by a gated,
lockable 6-foot chain  link fence to prevent entry by unauthorized persons or animals.
The working pad included a decontamination area divided into an  exclusion zone,
contamination reduction zone and support zone.  Responsibilities of the subcontractor
during the execution of the test period were the following:

    •     Obtain any necessary permits for performing the work;
    •     Check drilling and excavation locations for underground utility interference,
         per the Existing Site Utilities Plan provided;
    •     Locate and survey boreholes and the boundaries, top, and bottom of the test
         pit;
    •     Deliver to the site required construction equipment, materials, tools and
         supplies, supervision and labor to:

-------
              Drill and sample two test boreholes,
              Perform borehole permeability tests,
              Install monitoring wells in the two boreholes,
              Construct a percolation test pit,
              Perform percolation testing,
              Backfill percolation test pit, and
              Breakdown and remove equipment and supplies from site; and
    •    Clean and restore work areas.

All drill cuttings were stockpiled on plastic sheeting in an area adjacent to the test pit.
Pit excavation materials were used to construct the berm around the test pit. The drill
cuttings and excavated soil were backfilled into the test pit at the end of the testing
period.  Dust control was provided during drilling and excavation activities by use of
water spraying to minimize visible air emissions. After completion of testing, fencing
was removed and work  areas were cleaned and restored to as near their  original
condition as feasible. Locks were provided for the two monitoring wells to allow their
future use in monitoring recharge pond performance.

1.2    Borehole Permeability Tests

Two boreholes were drilled adjacent to the location of the outer boundary of the test
pit to: facilitate the performance of permeability tests at 5 and 10 feet below ground
surface (bgs); and facilitate the installation of two monitoring wells.  The two test
boreholes  were drilled with nominal six-inch diameter hollow stem auger to depths of
18 and 55 feet bgs. Eight subsurface soil samples were collected from the boreholes
using a Standard  Penetration Test sampler, in accordance with ASTM  D1586-84.
Permeability tests were conducted at depths of 5 and 10 feet bgs in each borehole. The
tests were performed by  measuring the rate of water needed to maintain a constant
head inside the hollow stem augers. Coarse sand was utilized in the bottom of the hole
to reduce caving. The borehole permeability tests were conducted for periods  of 23 to
60 minutes, until a steady-state flow rate was approximately achieved.

1.3    Monitoring Wells

Subsequent  to the drilling  and  testing of the boreholes  described above, two
monitoring  wells  were completed  in each of the  two tested boreholes.    Work
associated with these wells was performed in accordance with Technical Specification
TS-034-003.   The monitoring wells were installed within the vadose and saturated
zones to bottom depths of  18 and 55  feet bgs,  respectively.  Wells were completed
inside 6-inch hollow stem augers  and  constructed with two-inch diameter, Schedule-
40, polyvinylchloride (PVC) casing. The bottom 10 feet of the wells were transversely
slotted with 0.01-inch width slots and terminated with a threaded cap. The top of the
PVC casing was extended approximately three feet above ground.

-------
The annulus was  filled with approximately 12.5 feet of filter pack, consisting of
Monterey #3 silica sand, from the bottom of the well to approximately two feet above
the well screen.  Prior to the addition of a bentonite seal, the well was surged to settle
the surrounding sand filter pack. A 2.5-foot plug of hydrated bentonite pellets was
placed on top of the filter pack, prior to the grout seal. The remaining annulus was
filled to ground surface with a neat cement.  Protective surface casing of steel was
installed to a depth of three feet and threaded with a locking cap.

1.4    Percolation Pit Construction and Testing

A  test basin was constructed with bottom dimensions of 25- by 25-foot  square,
surrounded by slopes cut to a 2.5 horizontal to 1 vertical grade.  The bottom depth was
5 feet bgs, as directed by Bechtel. A 2- to 3-foot high protective benn was constructed
around the test pit with the excavated soil.  Compaction  of the test pit bottom was
minimized during  excavation. Compaction  of the slopes  was performed as deemed
necessary to prevent slumping. The test pit location and as-built drawings are shown
in  Figures 1 and 2, respectively.  A drop basin was constructed at the water  inlet to
minimize  erosion during pond filling and testing.   A staff gauge was installed in the
basin near the edge for measurement of water depth. In addition, an evaporation pan,
rain gage, and thermometer, were also provided for the duration of the testing.

The percolation pit test consisted of the following work:

   •    Filled the test basin to approximately 2.75 feet height of water, and
        monitored and controlled the flow of water into the test pit continuously for
        48 hours; and

   •    Subsequently  performed periodic work, initially on a daily basis:
              Measured water level in test pit at the staff gauge,
              Measured water temperature in test pit,
              Adjusted the inflow of water to maintain a relatively constant water
              depth of 2.5 to 3 feet,
              Measured evaporation rate and refill evaporation pan,
              Measured rain gauge, if any precipitation occurred, and
              Measured water levels, if any,  in the two test monitoring wells.
2.0    SUMMARY OF TEST RESULTS

Geologic logging of the boreholes, borehole permeability testing, and well installation
are described in Attachment 1.  The percolation test data recorded by the subcontractor
are provided in Attachment 2.  The calculation of the recharge rate and estimate of
pond size  required  for the treatment plant are  provided in  Attachment 3.  The

-------
.net,     mtt.

-------
Calculation Sheet
Originator	
Project -5g/*d.
Subject	&
                                       Date
                              TsrA-h*a Job No
                                                                                     Bochtel
                                                                  Calc. No..
                                                                  Checked.
Rev. No.
Date	
                                                                                                 fZ^_2
 2

 3

 4

 5

 6

 7

 8

 9

10

11

12

13



15

16

17

18

19

20

21.

22

23

24

25

X

27

28'

29

30



32

33

34

35

36

                                             is.



                                           A
                                                 A
                                                                                              Tee. ef

                                                                                             Toe  c~f
                                                                 ,*,«,'-tvf,'«a  «*<£//  (ssf ty}
                                                                           I         *       */

-------
following sections briefly summarize the results of the borehole  permeability and
percolation pit testing.

2.1    Borehole Permeability Test Results

The borehole permeability test results indicated that the soils in the shallow vadose
zone, at 5 feet and 10 feet below ground surface, would be suitable for the percolation
pit test  (Option 1).   The vertical hydraulic conductivity  was  estimated  to be
approximately 2  feet per day, based  on the average of four tests.  An area of
approximately 170 feet by 170 feet was estimated to be required for recharge of the
treatment plant design capacity of 300 gallons per minute, assuming  a recharge rate
approximately equal  to the estimated vertical hydraulic conductivity.  Sufficient area
of unused land  remains at  the Selma site  to accommodate much more than this
preliminary pond size.

2.2    Percolation Test Pit Results

Subsequent to pond filling, the test period duration was approximately 45 days (12:11
on July 9 through 13:32 on August 23, 1996).  Based  on hydrant meter readings, the
total water volume placed in the pond was 391,000 gallons, with an  average flow rate
of 6.02 gallons per minute.  The total pan evaporation measured during the test was
20.9 inches.   The measured pan evaporation, assuming a pan coefficient of 0.7,
represents an evaporation rate of 0.03 feet per day.  The net infiltration rate, with
negligible adjustment for evaporation, was estimated to be 1.1  feet per day, assuming
an effective infiltration area of 32 feet by 32 feet for the percolation test.

Significant decreases in the flow rate or infiltration rate during the test did not occur,
and in fact, the final rate was slightly higher than during the initial portion of the test.
A relatively steady rate of increase in the water table level was indicated  to begin
about 4 days after starting the test, but the change (about 1 ft in 45  days) may reflect
slight seasonal variation in the local water table in combination with slight water table
mounding.  The shallow monitoring well (screened  8 to 18 ft bgs) remained dry
throughout the test, suggesting absence of perched water mounding.

2.3    Recommendations for Recharge Pond

By direct extrapolation of the percolation pit test results, the required pond bottom area
for the treatment plant discharge of 300 gallons per minute is 228  feet by 228 feet.
However, pond bottom dimensions of 200 feet by 260 feet are recommended for the
recharge pond, to more conveniently fit within the unused land at the Selma site. A
duplicate or standby pond  is recommended to allow continuous  operation of the
treatment plant when maintenance activities are required in the recharge pond.

The  infiltration capacity of the constructed  ponds must be verified  during startup.
Activities during pond  construction, such  as  unintended  excessive  reworking and

-------
compaction of the pond bottom during excavation, could result in infiltration rates
different than those estimated from the recharge test.  Such activities which would tend
to reduce the infiltration rate are to be avoided.

-------

-------
                 ATTACHMENT 1
RESULTS OF GEOLOGIC LOGGING, WELL INSTALLATION, AND
          BOREHOLE PERMEABILITY TESTING

-------

-------
                                                            C3-1  OC266
Bechtel National, Inc.
50 Beale Street (94105)
P.O. Box 193965 (94t19)
San Francisco, CA
                  ARCSWEST - Selma Pressure Treating Site
To:
Company:
From:
Phone:
Location:
M. Sholley and W. Sweet-Dodge
Bechtel National
M. Janowiak
8-8224
San Francisco, CA
Date: July 1
cc: Prem
M. L
, 1996
Attanayake
Introduction

The Selma Pressure Treating Superfund Site is located in Selma, California. The site
was placed in the Superfund program because of groundwater and soil contamination.
There is a groundwater pump-and-treat system proposed to control migration of a
chromium plume. The system will pump up to a maximum of 250 gallons per minute.
Treated groundwater will be recharged to the aquifer in an on-site recharge system.

On June 27,1996, BSK Engineers drilled and logged two boreholes and conducted
borehole permeability tests (Figure 1). Monitor wells were installed in the boreholes.
The borings were drilled near the area where a recharge pilot test will be conducted.
The purpose of these borings was to test the permeability of the shallow soils and to
install monitor wells for the recharge pilot test.

Permeability test results were used to decide if recharge is best attained by recharge
basins'or by stone columns. Initial results indicate that the vertical hydraulic
conductivity in the shallow vadose zone is approximately 2.0 ft/day (average of four
tests, Kh/Kv = 10 from Table 1).

Methods, Results, and Discussion
The following presents the field methods and results of the geologic logging, well
installation, and permeability testing.

Geologic Logging
Split-spoon sampling was conducted from 3.5 feet bgs to 45 feet bgs in boring #1. The
upper 8 feet of soil was a damp silty sand to sandy silt. These soils were not cohesive.
At 8.5 feet bgs, there was a distinct contact where the deeper material was a fine sand.
Only a trace of silt was present. The fine sand extended to a depth of approximately 18
feet bgs. From 18 to 25 feet bgs, the lithology was a silty sand to sandy silt From 25
feet to approximately 40 feet bgs, a fine sand was encountered. At approximately 40

-------
feet, there was a caliche or weakly-cemented silty sand. At this depth there was a color
change from olive brown to a reddish brown.  Groundwater was encountered at 49 feet
bgs.

At site #2, the lithology was similar to site #1.  There were very thin coarse sand beds (2
to 3 inches) encountered in this zone in the 17  to 18 feet bgs interval. This indicates that
the silt encountered from 18 to 25 feet bgs at site #1 may not be vertically continuous.

Well Installation
A monitor well was installed in Test #1 with the screened interval extending from 54.5
feet to 44.5 feet bgs in this borehole. In Test #2, the monitor well screened interval
extended from 17.5 to 7.5 feet bgs.

The wells were constructed with 2-inch diameter, schedule 40 PVC, 0.010-inch machine
slot screen and blank casing to the surface. Monterey #3 sand was used for the filter
pack, which extended 2 feet above the top of the screen. Bentonite chips were placed on
top of the filter pack and hydrated.  Neat cement grout was placed over the bentonite
plug to ground surface and the wells were completed with a 6-inch diameter surface
casing.

Test #1 was installed as a water table well to monitor mounding associated with
recharge water from the pilot test. Test #2 was installed at the top of the silt unit
encountered at a depth of 18 feet to monitor potential perching on that unit as the
recharge test progresses.

Permeability Testing
Permeability testing was done as follows:
1. a soil sample was collected from 3.5 to 5.0 feet bgs,
2. the borehole was reamed to 5.0 feet,
3. augers were lifted one foot,
4. sand was placed into the hole to a point several inches into the auger stem,
5. a water-level sounder was placed at a preset depth 10 inches above the sand,
6. the hole was filled with water up to the depth monitored by the sounder using one-
   liter containers,
7. elapsed time was measured and recorded as time since first water was placed in the
   borehole,
8. one liter of water was added when the sounder indicated water levels dropped to
   just below the sounder level,
9. when water take had stablized (usually after about 10 minutes), the test was
   continued to measure the average rate of take in the borehole.

By adding water in one-liter increments the head was maintained at a +/- 2.5 inch
interval about the sounder level.

-------
The first test at site #1 was conducted with a much higher head (several feet) rather than
10 inches.

Table 1 is summary of test parameters and the resulting vertical hydraulic
conductivities calculated for each of the four tests. The vertical hydraulic conductivities
ranged from 0.35 ft/day to 3.01 ft/day. The shallow lithologies had lower Kv
compared to the deeper lithologies, but only marginally at site #2.

Summary
The vertical hydraulic conductivities, as measured at the two boreholes, are high
enough that a recharge pond should be tested instead of a stone column.  There appears
to be sufficient area at the Selma Pressure Treating site to accommodate ponds of the
dimensions needed for recharge of 250 gpm (Table 2). This will be further tested during
the pilot study. Monitor wells installed in the test basin area can be used to evaluate
perching of the recharge water and mounding effects on the water table.

References
(see tables 1 and 2)

Attachments
1.  Geologic logs (final logs due from BSK)
2.  Well construction diagrams
3.   Permeability Test  Data

-------
                                                                                                            Table 1
                                                                                              Selma Near-Surface Infiltration Tests


Test
location

,

i

2

2


Test
depth
(inches)

60

120

60

120


Material tested

Silly Sand
(20 to 40% sill)
Fine Sand with Silt
(< 10% silt)
Silly Sand
(20 to 40% sill)
Fine Sand with Sill
«10% silt)

Hole
diameter
jnches)

6

6

6

6


Effective
area of
lest hole
(ft2>

0.20

0.20

0.20

0.20


Approximate
head
(inches)

30

10

10

10


Test
duration
(mm)

60

30

30

23


Water
volume
added
(mL)

43000

21000

23000

22000


Time
required
10
infiltrate
(min)

55

19.25

29

23.3


Flow
rale
(L/hr)

46.91

65.45

47.6

56.7


Row
rale
(ft'/day)

39.76

55.48

40.3

48.0

Vertical
hydraulic
conductivity,
K,"'
(assume
(ft/day)
2.34

16.32

11.9

14.1

Vertical
hydraulic
conductivity,
(assume
(ft/day)
0.35

3.01

2.19

2.60


Notes

Higher head than other tests



Cleaner sand in sampler shoe, may
be reason for higher K than at ff 1


               Notes:
                '" Horizontal hydraulic conductivity, K» = Q In I mL/D + ( 1 + (mL/D)! )")/(2itLHt) (Lambe & Whitman, p. 284-285, for open borehole, uniform soil, constant head),
                   where "transformation ratio", m = ( K|/K,) °5, and D = hole diameter, L = saturated length, H< = constant head, and Q = water flow. Try in = 01, 1, and 10.
•\\IHHI IK* XI.1
                                                                                                          I'agt 1 oj I
                                                                                                                                                                                                                       AfO'J  7/2/Vrt 7 29AM

-------
                                                Table 2
                   Green & Ampt Infiltration Equation
                                                             Pond Sizing Estimate
Assume Kt from Lambe & Whitman analysis corresponds to K^..^t:
     0.35
     3.01
     2.19
     2.60
-2.0
-2.0
-2.0
-2.0
2
2
2
2
10
10
10
10
Assume Kt from Lambe & Whitman analysis corresponds of v t;
0.49
4.20
3.06
3.63
1.28
11.04
7.96
9.53
0.82
7.02
5.08
6.03
0.66
5.65
4.11
4.88
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
-2.0
0.67
0.67
0.67
0.67
0.67
0.67
0.67
0.67
0.67
0.67
0.67
0.67
1
1
1
1
2
2
2
2
3
3
3
3
0.35
3.01
2.19
2.60
0.35
3.01
2.19
2.60
0.35
3.01
2.19
2.60
Notes:
  (l) Infiltration rate, v, = K (Hw + Lf - /»„ ) / Lf (Bouwer. 1978, p. 253).
 •m Required pond dimension, W = Q / !£
Required
flow.
Q
(gal/min)
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
250
Required pond
dimension.
W«
(ft)
371
126
148
136
194
66
78
71
243
83
97
89
270
92
108
99

-------

Elapsed
Time
min
1
2
3
5
7
9
13
16
19
23







Elapsed
Time
mm
1
2
4
6
8
10
13
16
19






sec
33
13
20
9
40
56
10
24
41
20








-
sec
55
46
30
13
35
55
30
20
15







1.550
2.217
3.333
5.150
7.667
9.933
13.167
16.400
19.683
23.333










1.917
2.767
4.500
6.217
8.583
10.917
13.500
16.333
19.250





Vol. Added
(liters)
13
1
1
1
1
1
1
1
1
1




._



Vol. Added
(liters)
13
1
1
1
1
1
1
1
1

,



Total Volume
(liters)
13
14
15
16
17
18
19
20
21
22








Total Volume
(liters)
13
14
15
16
17
18
19
20
21




Water
Depth
(ft bgs)
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5







Water
Depth
{ft bgs)
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5
-8.5





















Infiltration Rates (Site #2, 10 feet
bgs)
25 -i 	 1
t A *
B 20 . • *
< + * *
fp-v*
i =. 10
5
i 5
0
0.000 5.000 10.000 15.000 20.000 25.
Elapsed Time (mln)
000



































Infiltration Rates (Site #1,10 feet
bgs)
^ 25 -i 	 	
i20 '«••**
$«•• .«»*
| 10
i s-
0.000 5.000 10.000 15.000 20.
Elapsed Time (mln)
DOO

















-------


Elapsed
Time
min
10
17
17
17
26
35
40
45
50





Elapsed
Time
mm
1
2
4
6
8
11
13
16
19
22
25
29

•





sec
0
15
45
58
50
0
0
0
0







sec
21
25
26
18
43
0
32
30
30
25
50
5








10.000
17.250
17.750
17.967
26.833
35.000
40.000
45.000
50.000








1.350
2.417
4.433
6.300
8.717
11.000
13.533
16.500
19.500
22.417
25.833
29.083






Vol. Added
(liters)
27
2
1
1
4
2
2
2
2






Vol. Added
(liters)
12
1
1
1
1
1
1
1
1
1
1
1






Total Volume
(liters)
27
29
30
31
35
37
39
41
43






Total Volume
(liters)
12
13
14
15
16
17
18
19
20
21
22
23





Water
Depth
(ft bgs)
-1
-1
-1
-1
-1
-1
-1
-1
-1





Water
Depth
(ft bgs)
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5
-3.5























Infiltration Rates (Site #1 , 5 feet bgs)

§40
j» 30
| 20
3 10 •
1 „



0.000 10.000 20.000 30.000 40.000 50.
Elapsed Time (min)


























>

uoo





Infiltration Rates (Site #2, 5 feet bgs)
Cumulative VoL (liters)
o 01 o in o N
O.C







XX) 10.000 20.000 30.<
Elapsed Time (min)















-



XX)






-------
 GEOLOGIC  DRILL  LOG
                                                             1SI
                                                                fo
                                                                  ')•».»

                                                                3" 5"
         /3>o -,
            -?
AV. J/j

                WATIft
                PMCMUHC
                   i
                                                  AM ckA ••***«* me*
                                      jflf^ l/ft ^
^
/7
                                       B «««/»<•
                                2-
                                                    - s
                                             •'' *'> '-•* ' -"V -' -^<-
                           2.5-'
                                      rt,. •
                                •r.
                                                   7K
                                            . <=« J£.,

-------
         ?/^  ,55
               <7r*vy>(J7
                        r-:-
                           -zc
                                                1   I
                                      t •

                                      M
         -i
                                     M.HJL
                                     NnMXI^
                                     HIXVM
                   :
- T
901  11IHQ 31901039

-------
GEOLOGIC  DRILL  LOG
                                                           ^r
T&k

                                                              ••«« JrrJ   |r«T*ia«»Ti
                          /#
.,,,. ,,_- /_
               WATIM

              PltCMUItl
              '

       r
                          r
                          f.r

                          /
-------
MONITORIN6 WELL
JO. NO.
•MOW
Wl
COUPLITto
Wl /•» i

// fa..*
S-fl ll A f) l_ a <•, , — 'i^^ , . „ -J


1
l.J ' '• £
• GENE RALIZED GEOLOGIC LOG


If
1 "*
V*
V*
\
j
T
A
i
*
i
t
c
K
•
*
1
•
f
4
1
j
i
i

—
^



J,.-
EUEV
l
4
J '
•J
r

ATI ON TOP Of RISER CASINO ___

" ^ GROUND SURFACE

SURFACE CASING
TYPE: .. "f^ f^ { t*j r £ **t-*t-£w»/^ £A^}^-
f



BACKFILL MATERIAL



RISER CASING
DIA: 2 "

J

1



ANNULAR SEAL
0 Iti C 1 *-^ »•- 1 »*t—


FILTER PACK
TYPE:



L
r


SCREEN:
DIA: 2" TYPE: <>:4.1<> f"J^
OPENINGS" WIDTH: 0.019"
TYPE: A,!,. ,(. .- » .;.*







"TcfT^1 1


DEPTH


s-
^.r
'4ft
^?^
r^
r
— •
__


ELEV.









-------

-------
1

*
" " * ' \
v'
_ f
1'
2
a
a
FIELD PERMEABILITY TEST REPORT BECHTEL INCORPORATED
PROJECT:. 5 £t-Mfr P^wr^Tmed,'-*
LOCATION:. tfL /U A C fir •
CLIENT: /rPA
CONTRACTOR:
DRILLER:

&{Y~ INSPECTOR:
INSTALLATION DATE : (, 111 lit' TEST DATE : C 1 * T~ If (,
TJPE INSTAL
IATTOM BOREHOLE

1 _^^* ft 1 ^} 1" ' J
TYPE TEST Cpv^ 7 O~vA r S&A \^il
RELATIVE TO GROUND SURFACE
> Ground Surface
i Ground Surface
STATIC h
NG BOTTOM C

(FEET):
fATFR A)rv£^
E CASING
• -XO'' BOTTOM OF TEST- 5". fl '

5-0"
JOB NO. 2o3 ^^ -c>3V
TEST
NO. *^L
BORING NO. 7/-J7-- 1
LOCATION


SHEET / OF
REMARKS ? SKETCH
^4?'
•w^ «r-^
PERMEABILITY TEST DATA
TIME
(HOURS-MINS!




&-5~ ^.^
0-2? _,^



•? ^;<^


» ^*^ p' •*•

f '
r*;^




ELAPSED
TIME
(MIN..SCC.)
l^.'OO.'fiO
/^'.p
_2 ^*: 5-^
3O :«?r
J?-? ,TJ
35"; ot3 •
3$',£~O
unioo
f/r"; *0 /"7
_T<5: «o
rr :o6


MCTER
READINO

•

(+ 2. li-Kdj
f-( 1 l:lw«.)
f-dfi+lr*.



f-f-t] l;fo,e$\
'

/"•fA l,K*i}

/4- 3. )^c^
iT/2 /./^j
r+s, AVv#$)



WATER
QUANTITY
• (GALLONS)
•^-Sf. J^e^


<2. °l ///twr

3^ :^t



35- ///^


5-9. /;A,tfJ.

19 /iVv^S
^J /;^e >;-^^s


DEPTH TO WATER
FROM TOP OF CASING
(FEET1 -• :
- 1..4
--2.3
-2 , C,
-2.3
.

- 3. 2_
-2. i
- 2. ?-
- 2 . O
- a. 2. •
- 2* • 3
-a. /
— ^ • V
- .2 /
-^.. ^9
''1,1
- 2.. 2-


REMARKS
^/ $, 7 iQ, H
12. 13 '^ /f / £.
lit /A 14


-------


•X
\
.i
!
t
1
I
1
1
«
FIELD PERMEABILITY TEST REPORT BECHTEL INCORPORATED
PROJECT:. StsLMA : JOB NO. 2.03 -j. f
LOCATIONr, '• TEST NO. .2-
CLIENT- __pP~K 	 " - 	 '" BORING NO. -TZ  Ground Surface
^ Ground Surface
STATIC M
NG BOTTOM C
BOTTOM 0
(FEET):
ATPJI —
F CASING?^
F TEST '3,0 '

REMAW
.•i^i«
• ^
3 7 SKETCH
i i
r
— \W
3't.
r1
PERMEABILITY TEST DATA
' TIME
(HOURS-WINS!
io-~lo
0. '' »,.•-
h '- C" i_ ' -v
. •}. C u- . .«-
2.. 3
3-'.'~3~*-<~
'^.L'-'.^.
2 .^ u..--
^ . £) •v—'-u 	







V '



ELAPSED
TIME
(MIN.-SEC.)
/: r <
?:i6
t'l • $o •
i'. 13
? ' ^ e"
IO:'.±0
1 4 \3.(J
11 '-if.











METER
READ IN 0-
•
** -1 I.-H.
-h I' 1 / l**e—
4-1 i,+v*-
4- . /'hrt.
-4 ' l."tfc^
fl Jl-^vr
+/ l.'-n-t—
J. 1 /.•**• fi~











WATER
. QUANTITY
• ' /•? j-4- c-
' Of // ' i- «5
/V .'.'TV-S
/ r /.-^w-j
/ t. ^.A-€_
/'7- /,-n-e.
i O i ^
'? A4wej
J?^ llf.tf '
2\ J.+V2.J











DEPTH TO WATER
FROM TOP OF CASINO
(FEET) ••=•••>
~~ & O
- i^O
- f. o
' — o O
-Y-^
--?. o ' -
-f.o
-r. o
~ ' .






'




REMARKS








-------
                        FIELD PERMEABILITY TEST REPORT
BORING NO.
                              .TEST NO..
                                                        SHEET
                                                                     OF
LOCATION.
DRILLING CONTRACTOR.

DRILLING Fimn    A A
                      ftr
                                             .TEST DATE.

                                             .DRILLER _
                                             .SUPERVISOR.
TYPE OF TEST.
TYPE OF CASING	

LENGTH OF CASING

TEST SECTION LENGTH
                                J.D..
I.D..
                 .SOIL DESCRIPTION.
DEPTH OF TEST (FT.).
                   r.
ELEVATIONS (FT.AMSL):

SURFACE ELEVATION	i
                     .BOTTOM OF CASING—^.
          "^ f
TOP OF TEST V 5      RftTTOM OF TEST.

STATIC WATER 1 FVFL  "J. 5"  4 c. J
                                                       REMARKS /SKETCH
                            PERMEABILITY TEST DATA
   CLOCK TIME
  (HOUR&MINS.)
               ELAPSED TIME
                  (MIN.)
  METER
 READING
 WATER
QUANTITY
 DEPTH TO
WATER (FEET)
REMARKS
                                        /2
 2.0
 / •  (f
                  :•//
-il.
           -3.
                    30
                            +1
                                                    - ?.
                                                     j.
                                                    -3.

-------
'  I
         r
            -A
           5
i  i
                     VA)
^H^S^XJ^- :A
                         o
                         P
                                        u
                                     0
                                          O!
                                              \A i
                                             $ fi
                                             \  tA
                                             Jf
               i)t

               (°


-------
            ATTACHMENT 2
PERCOLATION POND INFILTRATION TEST DATA

-------

-------
POND INFILTRATION TEST DATA
SELMA PRESSURE TREATING Page 1 of 5
Date
(1996)
07/09















Time
(hr.)
0605
0705
0810
0902
0955
1104
1211
1310
1408
1505
1602
1659
1808
1900
2003
2100
A Time
(hr.)

1.00
1.08
0.87
0.88
1.15
1.12
0.98
0.97
0.95
0.95
0.95
1.15
0.95
1.05
0.95
Water Level
(in. from hue)

0.0
14.3
21.0
28.0
31.9
33.1
33.0
33.0
33.0
32.9
32.9
32.9
32.8
32.5
32.4
Meter
(ft1)
792580
793345
794000
794580
795240
795875
796048
796082
796117
796150
796184
796217
796278
796303
796339
796370
&VoL
(ft1)

765
655
580
660
635
173
34
35
33
34
33
61
25
36
31
Ave,Flow
(*P»»)

95.4
75.6
83.1
93.5
68.8
19.3
4.3
4.5
4.3
4.5
4.3
6.6
3.3
4.3
4.1
Depth to
Groundwater
(in. from ToC)
TH.1
(South)


45.85


45.86



45.83


45.82
,
45.85

Pan Evaporation
Water HL (in.)
intt.













6.5


end
















Water
Temp
CF)
















Evap.
(inches)
















- /»•»_'.'1
BSK

-------
POND INFILTRATION TEST DATA
SELMA PRESSURE TREATING Page 2 of 5
(continued)
Date
(199«)
07/10
















Time
0>r.)
21S9
2258
2400
0058
0158
0300
0400
0500
0600
0700
0804
0858
1000
1103
1210
1306
140-1
A Time
(kr.)
0.98
0.98
1.03
0.97
1.00
1.03
0.97
1.00
1.00
1.00
1.07
1.10
1.03
1.05
1.12
0.93
0«J7
Water Level
(In. from bate)
32.5
32.6
32.8
32.8
32.9
33.0
33.0
33.1
33.3
33.3
33.3
33.0
33.0
32.9
32.9
32.9
125
Meter
(ft*)
796418
796466
796521
796571
796623
796678
796731
796786
796841
796870
796892
796912
796935
796959
796985
797008
7')7»)
6.1
6.1
6.7
6.4
6.5
6.7
6.8
6.9
6.9
3.6
2.6
2.3
2.8
2.8
2.9
3.1
30
Depth to
Groundwater
(ukfromToC)
mi
(South)
45.88

45.89

45.89

45.89

45.91

45.93

45.92

45.89

45 88
Pan Evaporation
Water Ht (in.)
init








6.4




6.3


62
end



.




6.4




6.3


62
Water
Temp
CF)









-



86


88
Evap.
(inches)

















BSK

-------
POND INFILTRATION TEST DATA
SELMA PRESSURE TREATING Page 3 of 5
(continued)
Date
(1996)
07/10









07/11






Time
(hr.)
1504
1605
1703
1756
1900
2000
2100
2159
2259
2400
0101
0200
0300
0359
0500
0600
1300
A Time
(hr.)
1.00
1.02
0.97
0.88
1.07
1.00
1.00
0.98
1.00
1.03
1.00
0.98
1.00
0.98
1.02
1.00
700
Water Level
(In. from bate)
32.4
32.5
32.5
32.4
32.4
32.4
32.4
32.4
32.3
32.4
32.4
32.4
32.4
32.4
32.4
32.4
325
Meter
(ft1)
797058
797096
797133
797168
797213
797250
797290
797327
797367
797410
797451
797493
797534
797576
797613
797651
797940
AVoL
(If)
27
38
37
35
45
37
40
37
40 ,
43
41
42
41
42
37
38
289
Ave.Flow
(gpm)
3.4
4.6
4.8
4.9
5.2
4.6
5.0
4.7
5.0
5.2
5.1
5.3
5.1
5.3
4.5
4.7
51
Depth to
Groundwater
(In. from ToQ
TH.1
(South)

45.85

45.84

45.%
45.99

45.99
45.99

45.99

45.99

45.99
45.95
Pan Evaporation
Water Ht. (in.)
init.



6.1











5.8

end



6.1











5.8

Water
Temp
CF)



97











74
-
Evap.
(inches)



0.4











0.3

Job 01 -40-022H

-------
POND INFILTRATION TEST DATA
SELMA PRESSURE TREATING Page 4 of 5
(continued)
Date
(1996)
07/11










07/12


07/13

07/14
Time
(hr.)
1410
1500
1600
1700
1800
1900
2000
2100
2202
2305
2359
0830
1100
1430
1432
1630
1436
A Time
(hr.)
2.17
0.83
1.00
1.00
1.00
1.00
1.00
1.00
1.03
0.95
0.98
8.52
1.50
3.50
24.03
1.97
22 10
Water Level
(In. from bate)
32.5
32.5
32.5
32.5
32.3
32.4
328
32.4
32.3
32.4
32.4
32.4
32.4
32.5
33.1
33.1
325
Meter
(If)
797990
798020
798070
798120
798150
798190
798230
798270
798320
798350
798386
798755
798824
799002
800255
800350
801408
AVoL
(ft1)
50
30
50
50
30
40
40
40
50
30
36
369
69
178
1253
95
1058
Ave.Fkm
(SP*»)
2.9
4.5
6.2
6.2
3.7
5.0
5.0
5.0
6.1
3.9
4.6
5.4
5.7
6.3
6.5
6.0
60
Depth to
Groundwater
(in. from ToQ
TH.1
(South)
45.92
45.92
45.92
45.92
45.92
45.92
45.93
45.95
45.98
45.97
45.99
45.99
45.99
45.98
45.89
45.89
4588
Pan Evaporation
Water Ht. (In.)
Intt




5.6






5.4
6.6

5.9

6.2
end




5.6






5.4


5.9

6.2
Water
Temp
fF>




88






77


99

" 98
Evap.
(inches)




0.2






0.2


0.7

0.5
BSK

-------
POND INFILTRATION TEST DATA
SELMA PRESSURE TREATING Page 5 of 5
(continued)
Date
(1996)
07/15
07/16
07/17
07/19
07/22
07/24
07/28
07/31
08/02
08/05
08/08
08/09
08/13
08/18
08/23
Time
(hr.)
1010
1040
1030
0830
1830
1831
0630
1400
1702
1803
1558
1430
1820
(128
1332
A Time
(hr.)
19.57
24.33
24.13
48.13
82.00
48.00
84.00
79.50
51.00
71.00
48.01
22.51
99.83
113.17
122.01
Water Level
(In. from bate)
38.8
35.8
33.8
32.3
30.2
32.5
35.3
39.8
33.5
30.0
30.0
29.0
33.3
35.0
38.3
Meter
(If)
802581
803902
804842
806771
809690
811966

820612



828230


848297
*VoL
(If)
1173
1321
940
1929
2919
2276

8,646



7,618


20.067
Ave. Flow
(ipm)
7.5
6.8
4.9
5.0
4.4
5.9

7.5



4.4


7.5
Depth to •
Groundwater
(In. from ToC)
TH.1
(South)
45.86
45.85
45.83
45.80
45.73
4569
45.63
45.55
45.50 .
45.44
45.33

45.20
44.91
44.79
Pan Evaporation
Water Ht (in.)
Init
5.9
5.7
5.6
5.5
4.7
6.1
4.8
5.1
5.5
6.0
5.6

3.4
6.1
5.5
end
6.2
6.1
6.6
6.4
7.0
6.6
6.8
6.6
7.4
7.1
5.6

8.5
7.7
5.5
Water
Temp
CF)
78
78
80
79
92
90
72
86
88
88
87

90
80
82
Evap.
(Inchet)
0.3
0.5
0.5
1.1
1.4
0.9
1.8
1.7
1.1
1.4
1.5

1.8
2.4
2.2
Job oi-io-u::fi
BSK

-------

-------
                 ATTACHMENT 3
CALCULATION OF RECHARGE TEST INFILTRATION RATE AND
           TREATMENT PLANT POND SIZE

-------

-------
CALCULATION COVER SHEET
PROJECT
AKCSWEST - Selma Pressure Treating
JOB NO.
20376434
SUBJECT
Recharge Test Infiltration Kale A Treatment Plant Pond Size
CALCNO.
C-003
SHEET
/
DISCIPLINE
Ceotech. & Environ. Technologies

CALCULATION PRELIMINARY
STATUS | Xj
DESIGNATION
CONFIRMED
. cn
SUPERSEDED
cu
' VOIDED
COMPUTER SCP
PROGRAM/TYPE [T] YES \ | NO
MAINFRAME PC
i i m
PROGRAM NO.
EXCEL
VERSION/RELEASE NO.
5.0




No.



Initial calculation
Ftotson tor Revision



9
Tool Nad
Stab



9
US She*
No.



^7*^ffuOut
&Tr




OMCked




AppraMd




Data
Record of Revisions

-------

-------
SUBJECT
CALCULATION SHEET
Kediargt Tea Infiltration Rate & Treatment Plant Pond Sat
BY Michael Sholley DATE 9/11/96
PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV
AKCSWEST-Selma
20376-034-023
C-O03
2 of 9
0

Table of Contents
1. Purpose	~	3
2. Methodology	3
3. Results	4
4. Conclusions	4
5. References	5
Table 1       Recharge Test Data and Results

Figure 1      Average Pond Water Depth, Flow Rate, and Infiltration Rate
Figure 2      Depth to Ground-Water Table

-------

-------
0 CALCULATION SHEET
SUBJECT Recharge Tta Infiltration Rale A Treatment Plant Pond Size
BY Michael StoUey DATE 9/11/96
PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV
ARCSWEST-Selma
20376-034-023
C-003
3 of 9
0

1.     Purpose
The purpose of this calculation is to determine the infiltration rate during the pond recharge test
conducted July 10 through August 23,1996, at Selma Pressure Treating site, and to estimate the
required pond dimensions for the groundwater treatment system design capacity of 300 gal/min.
This work is conducted as part of Subtask 023, "Percolation Tests", based on the Activity Work
Plan (Bechtel, 1995b).  Additional work completed for Subtask 023, installation of test
monitoring wells and borehole permeability tests, are reported in Bechtel memorandum from
Matt Janowiak, dated July 1,1996. The design capacity requirement of 300 gal/min includes a
contingency of 50% above the expected full-scale extraction system rate of 200 gal/min, based on
an expected maximum of ten extraction wells at 20 gal/min per well (Bechtel,  1995a, pg. 6-1).


2.     Methodology	

Field measurements of cumulative flow at various times were used to determine average flow
rate and to estimate the infiltration rate for the 45-day recharge pond test.  Data was also
collected on pah evaporation, ground-water table response, and potential perched mounding in
the vadose zone. The recharge test was conducted within a test pit with dimensions of 5-ft depth
and 25-ft by 25-ft bottom area, and side slopes of 2.5H:1 V. The water depth in the test pond was
maintained between 29 to 40 inches, but was typically 30 to 36 inches.

The data measurements (BSK, 1996) are summarized in Table 1.  From the time that the pond
was filled (to a water depth of 33 inches), the  following parameters were calculated using ah
EXCEL spreadsheet (Table  1):

       •  elapsed time (days),
       •  average pond depth (in.),
       •  average flow rate (gal/min),
       •  average evaporation rate (ft/day), and
       •  average infiltration rate (ft/day).

The infiltration rate was determined by dividing the average flow rate by the bottom area of the
test pond plus one-half of the side slope area under water.  Because of side slope compaction
during excavation, the contribution of this portion of the pond area to infiltration is uncertain.
The infiltration rate was adjusted for evaporation by multiplying the pan evaporation rate by a
pan coefficient of 0.7 (Hjelmfelt and Cassidy, 1975).

This method of estimating the  infiltration rate does not evaluate the effects of horizontal
infiltration through pond sides or alternate pond water depths.  As a result, this method of
analysis may slightly overestimate the actual infiltration rate for a larger pond with shallower

-------
SUBJECT
CALCULATION SHEET
Recharge Tat Infiltration Kate & Treatment Float Fond Size
BY Michael Shollty DATE 9/11/96
PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV
ARCSWEST-Selma
20376-034-023
C-O03
4 of 9
0

water depth. Recharge through the pond sides compared to through the pond bottom would be
proportionally less for a larger pond than the test pond size (assuming vertical hydraulic
conductivity is significantly lower than the horizontal conductivity, and neglecting side slope
compaction effects). The infiltration rate for a pond water depth less than the test pond depth of
2.5 to 3 feet would be slightly less, but the reduction  is much less than the proportional difference
in head because of unsaturated flow conditions beneath the pond (i.e., mounded water table does
not intercept the recharge pond).

Using this approach, the pond size required for discharge of the treatment plant rate of 300
gal/min was estimated from the approximate steady-state flow rate indicated by the recharge test:

       •  required discharge pond size  = 300 gal/min treatment plant discharge rate / (test
          pond flow rate / test pond area - evaporation rate), and
          test pond area  = (25 ft + 33.5 in712 x 2.5)  = (32 ft)  , where the pond area includes
          one-half of the side slopes under water during testing; average pond depth is 33.5
          inches, and side slopes are 2.5H:1V.
3.     Results
The 45-day recharge test indicated an average flow rate of 6.02 gal/min into the test pond (Table
1). The average evaporation rate was estimated to be 0.03 ft/day. The infiltration rate, adjusted
for evaporation, was estimated to be 1.11 ft/day, based on an infiltration area of 32 ft by 32 ft.
By direct extrapolation of the test results, the required pond bottom dimensions for the treatment
plant discharge of 300 gal/min are 228 ft by 228 ft.

Significant decreases in the flow rate/infiltration rate during the test did not occur, and in fact, the
final rate was slightly higher than during the earlier testing period (Figure 1). A relatively steady
rate of increase in the water table level was indicated to begin about 4 days after starting the test
(Figure 2), but the change (about 1 ft in 45 days) may reflect seasonal variation in the local water
table in combination with water table mounding. The shallow monitoring well (screened 8 to 18
ft bgs) remained dry throughout the test, indicating absence of perched water mounding.


4.     Conclusions	

Pond bottom dimensions of 200 ft by 260 ft are recommended for recharge of the groundwater
treatment plant discharge. A duplicate pond is recommended to allow continuous operation of
the treatment plant during maintenance activities in one recharge pond. Maintenance activities
are expected because of eventual partial clogging resulting from anticipated progressive
accumulation of fines in the pond bottom. Because the required treatment discharge capacity of

-------
^ CALCULATION SHEET
SUBJECT Recharge Ten Infiltration Kate A Treatment Plant Pond Size
BY.
Michael Sholley DATE 9/11/96

PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV

ARCSWEST - Selma
20376-034-023
C-003
5cf9
0

300 gal/min already includes a 50% contingency beyond the expected full-scale extraction rate of
200 gal/min, additional conservatism in pond dimensions was not warranted.

The infiltration capacity of the constructed ponds must be verified during startup. Activities
during pond construction, such as unintended excessive compaction of the pond bottom during
excavation, could result in infiltration rates different than those estimated from the recharge test.
Such activities which would tend to reduce the infiltration rate are to be avoided.
5.    References
Bechtel, 1996, Description of borehole permeability tests and monitor wells for recharge test,
July 1, 1996 (interoffice memorandum from M. Janowiak to M. Sholley and W. Sweet-Dodge).

Bechtel, I995a, Submittal #1 - Evaluation of Full-Scale and Pilot-Scale Groundwater Treatment
Plant and Extraction/Reinjection System Designs, June 16,1995 (letter transmittal to Michelle
Lau from Wileen Sweet-Dodge).

Bechtel, 1995b, Selma Pressure Treating Activity Work Plan, December 1995.

-BSK  & Associates, 1996, "Results of Pond Infiltration Test," August 26, 1996 (fax to Bechtel).

Hjelmfelt, A.T., Jr., and J.J. Cassidy, 1975, Hydrology for Engineers and Planners, Iowa State
University Press.

-------
^ CALCULATION SHEET
SUBJECT Kecha^ Tta Infiltration Ratt A Trtatment Plant Poiui Size
BY MichatlSMIfr DATE 9/11/96
PROJECT
JOB NUMBER
CALCNO.
SHEET MO.
SHEET REV
ARCSWEST-Stlma
20376-O34-O23
C-OOJ
6 of 9
0

Table 1 - Recharge Test Data and Results
Field Measurements
Date
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
9-Jul
10-tal
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
10-Jul
11-Jul
11-Jul
Time
6:05
7:05
8:10
932
935
11:04
12:11
13:10
14:08
15:05
16:02
1639
18:08
1930
2033
21:00
2139
2238
24:00
038
138
3.-00
4:00
5:00
6:00
730
834
838
10:00
11:03
12:10
1336
1434
1534
16:05
1733
1736
19:00
20:00
2130
2139
2239
24:00
1:01
2:00
Depth
(in.)
.
0.0
14.3
21.0
28.0
31.9
33.1
33.0
33.0
33.0
3X9
3X9
3X9
3X8
323
32.4
323
3X6
32.8
3X8
3X9
33.0
33.0
33.1
333
33.3
333
33.0
33.0
-$2.9--
3X9
3X9
323
3X4
323
323
32.4
32.4
32.4
3X4
3X4
32.3
32.4
32.4
32.4
Flow
(en. ft)
79X580
793.345
794.000
794380
795040
795375
796.048
796.082
796.117
796.150
796.184
796J17
796378
796303
796339
796370
796.418
796.466
796321
796371
796.623
796.678
796.731
796,786
79*841
79*870
79*892
79*912
79*935
79*959
79*985
797.008
797X131
797.058
797.096
797.133
797.168
797313
797350
797390
797327
797367
797,410
797.451
797.493
Depth
to
: Grand- Pan
water EraporadoB
(ft) (in.)
.
-
45.85
-
-
45.86
-
-
-
45.83
-
-
45.82
0
45.85
-
45.88
.
45.89
-
45.89
-
45.89
-
45.91 0.1
-
45.93
-
45.92
O.I
45.89
'
45.88 0.1
.
45.85
-
45.84 O.I
.
45.96
45.99
-
45.99
45.99
-
45.99
Elapsed
Time
(days)
.
-
-
-
-
-
0
0.04
0.08
0.12
0.16
0.20
0.25
038
0.33
0.37
0.41
0.45
0.49
033
037
0.62
0.66
0.70
0.74
0.78
0.83
0.87
0.91
0.95
1.0
1.0
1.1
l.t
1.2
1.2
1.2
1.3
1.3
1.4
1.4
13
1.5
1.5
1.6
Infiltration Eftii
Average
POod
Depth
(In.)
.
-
-
-
-
-
33.1
33.0
33.0
33.0
33.0
33.0
33.0
33.0
3X9
3X9
3X8
32.8
3X8
3X8
32.8
3X8
3X8
3X8
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X9
3X8
3X8
3X8
32.8
3X8
3X8
3X8
3X8
3X7
Average
Flow
Batf
(galtain.)
Begin flow
Pond filling
Pond filling
Pond filling
Pond filling
Pond filling
.
43
4.4
4.4
4.4
4.4
4.8
4.7
4.6
4.6
4.7
4.8
5.0
5.1
5.2
53
5.4
53
53
5.4
53
S3
5.1
5.0
4.9
4.8
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.7
4.8
•ate

Average Avenge
Evaporation Infntntfoa
Rate* Rat*'
(ft/day) (ft/day)
.
-
-
-
-
-
-
0.8
0.8
0.8
0.8
0.8
0.9
0.9
0.9
0.8
0.9
0.9
0.9
. 1.0
1.0
1.0
1.0
1.0
0.01 1.0
1.0
1.0
1.0
0.9
0.01 0.9
0.9
0.9
0.02 0.9
0.9
0.9
0.9
0.02 0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9














































-------
SUBJECT
CALCULATION SHEET
Recharge Ttn hftitmtio* Knit A Treatment Plant Pond Size
BY Michatl SMolUy DATE 9/11/96
PROJECT
JOB NUMBER
CALC NO.
SHEET NO.
SHEET REV
AKCSWEST-Selma
20376434-023
C-003
7of9
0

                                           Table 1 - Recharge Test Data and Results

Date
I l-Jul
Il-Jul
1 l-Jul
tl-Jul
1 l-Jul
1 l-Jul
Il-Jul
1 l-Jul
1 l-Jul
1 l-Jul
1 l-Jul
Il-Jul
1 l-Jul
1 l-Jul
U-Jul
1 l-Jul
12-Jul
12-Jul
12-Jul
* 13-Jul
13-Jul
14-Jul
15-Jul
16-Jul
17-Jul
19-Jul
22-Jul
24-Jul
28-Jul
3 l-Jul
2-Aug
5-Aug
8-Aug
9-Aug
13-Aug
18-Aug
23-Aug
S-Sep

Time
3:00
349
5:00
6:00
13:00
14:10
15:00
16:00
17:00
18:00
19.-00
20:00
21:00
22.-02
23:05
2349
8:30
11:00
14:30
14:32
16:30
14:36
10:10
10:40
10:30
8:30
18:30
18:31
6:30
14:00
17:02
18:03
1548
14:30
18:20
11:28
13:32
11:00
Field
Pood (
Depth
(In.)
32.4
32.4
32.4
32.4
324
324
324
32J
3X5
324
32.4
32.8
32.4
3X3
32.4
32.4
32.4
32.4
32.5
33.1
33.1
324
38.8
35.8
33.8
324
307
3X5
35 Jr
39.8 -
33S
304)
30.0
29.0
33.3
35.0
384
0.0
MevureiD
^unaUttre
Flow
(Ctt.fl)
797434
797476
797.613
797.651
797.946
797.990
798.020
798.070
798.120
798.150
798.190
798,230
798.270
798.320
798450
798,386
798.755
798.824
799.002
800755
800350
801.408
802481
803,902
804,842
806.771
809,690
811,966
-
82Q£12
.
.
-
828730
-
-
848797
-
eott
Depth
to
Ground-
water 1
(ft)

45.99

45.99
45.95
45.92
45.92
45.92
45.92
45.92
45.92
45.93
45.95
45.98
45.97
45.99
45.99
45.99
45.98
45.89
45.89
45.88
45.86
45.85
45.83
45.80
45.73
45.69
45.63
45.55
4540
45.44
45.33

4570
44.91
44.79
44.45

Pan
EvBpontkm
(In.)

-
-
04
-
-
-
.
-
07
-
.
-
-
-
.
0.2
-
.
0.7
.
04
04
04
04
.1
.4
0.9
.8
.7
.1
.4
14
-
1.8
2.4
27
•

Ebpted
Time
(dm)
1.6
1.7
1.7
1.7
2,0
2.1
2.1
27
27
27
24-
2.3
2.4
2.4
24
24
2.8
3.0
3.1
4.1
4.2
5.1
5.9
6.9
7.9
9.8
13.3
15.3
18.8
22.1
247
277
307
31.1
35.3
40.0
45.1
.58.0
Infil
Avenge
Pood
Depth
(in.)
3i7
3X7
32.7
32.7
32.7
32.7
32.7
32.7
32.7
32.7
32.7
32.7
32.1
32.6
32.6
32.6
32.6
3X6
3X6
3X6
3X7
3X7
33.1
33.7
33.8
33.7
33.1
3X8
33.0
33.7
34.0
33.7
33.4
337
33.0
33.1
334

tradon Estta
Avenge
Flow
Rate
(raVmin.)
4.8
4.8
4.8
4.8
4.8
4.8
4.8
4.9
4.9
4.9
4.9
4.9
4.9
4.9
4.9
4.9
4.9
4.9
5.0
5.3
54
54
5.7
5.9
5.8
5.7
54
5.4

5.8



5.4


6.02

aate
Avonge
ctaycMiioii
Rate*
(ft/day)



0.02





0.02






0.02


0.03

0.03
0.03
0.03
0.03
0.03
0.03
0.03
0.03
0.03
0.03
0.03
0.03

0.03
0.03
•M


Avenge
InBhntkM
Rale*
(ft/day)
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
.0
• .0
.0
.1
.1
.1
.0
.0
.0

1.1



1.0


1.11

Notes:
   *  Evaporation rate estimate assumes paa coefficient of 0.7.
     Infiltration nte estimate assumes effective area of infiltration during testing of 32 ft x 32 ft

-------
^ CALCULATION SHEET
SUBJECT Recharp Tea Infiltration Kate A Treatment Plant Pond Size
BY Michael SholUy DATE 9/11/96
PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV
AACSWEST • Selma
20376434-02J
C-C03
8 of 9
0

            Figure 1 - Average Pond Water Depth, Flow Rate, and Infiltration Rate
0
  0
10
20           '   30
Elapsed time, in days
40
                                                                   0
50
         • Flow rate (gpm)
            • Infiltration rate (ft/day) • • A • • Pond water depth (inches)

-------
^ CALCULATION SHEET
fl ip.lFPT *tctuuit Tea Infiltration Kali A Treatment Plant Pond Sue
BY Michael SHoUey DATE Ml/96

PROJECT
JOB NUMBER
CALCNO.
SHEET NO.
SHEET REV

ARCSWEST-S*lma
20376434-O23
C-003
9 of 9
0

                          Figure 2 - Depth to Ground-water Table
44.0
47.0
     0
10
20
30
40
50
60
                                    Elapsed time, in days

-------

-------
                   ATTACHMENT A
 USEPA/Selma Pressure Treating Superfund Site
Groundwater Extraction-Recharge Basin/Treatment
          Construction Cost Estimate
                    BEI
              November 6, 1996

-------

-------
                                         Job 20376
                              USEPA/Sclma Pressure Treating Site
                                            Protect Data
        Client:       USEPA Region IX
                     San Francisco, California

        Work
        Assignment:  Selma Pressure Treating Superfund She

        Location:     Selma, California

        Estimate     The estimate scope includes construction of groundwater extraction system,
        Scope:       groundwater treatment plant and treated groundwater recharge basin.

                     A brief description of these three construction hems are;

                     (A-U Groundwater Extraction System
                      - Four (4) groundwater extraction wells and pumps
                      - 2,400 feet of HOPE piping delivering groundwater to treatment plant
                      - Leak detection system
                      - Bore/jack steel carrier pipe
                      • Electrical and control

                     (A-2) Recharge Basin
                      - Two (2) basins, 200' x 260' each
                      - 600 feet of PVC piping connecting between treatment plant and basins
                      - Basin inlet valves & flowmeters in two (2) manholes
                      - 1,800 feet of cyclone fence and a gate around the basins

                     (B) Groundwater Treatment Plant
                      - Sized to treat 300 gpm of extracted groundwater by chemical precipitation,
                             clarification and filtration.
                      - Chromium is the contaminant of concern

        Type of      Order of magnitude construction cost estimate. The Bechtel estimate updates
        Estimate:     an estimate previously prepared by Weston to reflect the latest design.

        Pricing       Fourth Quarter 1 996 Price and Wage Level.
        Level:        The estimate has been escalated to 2Q 1997 at 3% per year.

        Purpose of    To provide the client with the updated total construction cost for
        Estimate:     the project.  The original estimate was prepared by Weston, Inc. in 1 992.
       Construction Project schedule has not been
       Schedule:
                                                                                   11/7/96
SELMA.DOC

-------
                                       Job 20376
                            USEPA/Selma Pressure Treating Site
        1.0  General

              Selma Pressure Treating Co. is a former wood preserving site, located 15
              miles south of Fresno, California. Beginning in 1981, EPA performed
              investigations at the site identifying both soil and groundwater contamination.
              Chromium is the contaminant of concern.  A full scale groundwater
              extraction, treatment and reinjection scheme was proposed.

              Roy F. Weston, Inc. (Weston) prepared a Remedial Action Design package
              based on this scheme and prepared a construction cost estimate in 1992.
              Subsequently, the decision was made by EPA to use a recharge basin concept
              for the treated-water disposal, instead of reinjection wells.

              This estimate package was prepared based on the design modifications made
              by Bechtel Environmental, Inc (BEI) which includes use of a recharge basin
              instead of reinjection wells, and use of a pressure piping system instead of a
              gravity piping system (resulting in the elimination of 2 lift stations).

       2.0 Estimate Methodology

              This estimate has been prepared by escalating Weston's estimate from 1992 to
              1996 and revising it to reflect the current modified scope.

              The major cost revisions made on Weston's estimate are:

Groundwater
Extraction

Recharge Basin


Major
Modifications
-Piping
- Lift station
- Reinjection well
- Piping
- Recharging Basin
Weston's
Estimate
4,250 ft
2ea
8 each
6,900 feet
None
This Estima

2,400ft
deleted
Deleted
600 feet
Included
SELMA.DOC
                                                                              11/7/96

-------
                                     Job 20376
                           USEPA/Selma Pressure Treating Site
                                    Major         Weston's      This Estimate
                                 Modification      Estimate

              Groundwater    -Row Rate         500 gpm    300 gpm
              Treatment       -Storage Tank           -       No modification
              Plant            -Piping                 -       Minor modification
                              -Process            Remove     Remove total
                                                 hexavalant   chromium
                                                 chromium
                              - Plot Arrangement       -       Minor modification
                The cost of the Groundwater Treatment Plant has not been adjusted for
                this estimate based on the assumption that the cost decrease due to the
                lower flow rate may be offset by more sophisticated process equipment
                required to meet a more stringent process (removal of total chromium
                instead of hexavalant chromium). This assumption may require further
                verification by the contractor.

       3.0 Estimate Basis

           - Estimate pricing is based on 4th quarter 1996 price and wage level.

           - Future escalation is included in the estimate at 3% per year.

           - The composite direct labor wage included in the estimate is $ 35/hr.

           - Material pricing and unit man-hour rates for civil work (recharge basin) are
             based on recent Means Construction Cost Data.

           - The man-hours required for hazardous waste operator training is included in
             the estimate.

           - Indirect field cost is included in the estimate at 100% of direct labor.

           - Engineering, Procurement and Construction Management cost (EPCM) is
             excluded from the estimate per the original Weston estimate.

           - Contingency is included in the estimate at 25% per the original Weston
             estimate.
                                                                            11/7/96
SELMA.DOC

-------
                                      Job 20376
                            USEPA/Selma Pressure Treating Site
      4.0  Qualifications and exclusions

            - It is assumed that the demolished asphalt and excavated soil for the recharge
              basin is not contaminated i.e. no hazardous waste disposal fee.

            - It is assumed that the excavated soil can be disposed within 20 miles from the
              job site with no fee.

            - It is assumed that there will be no dewatering during the excavation of
              recharge basins (water table at approximately 34 feet below the excavated
              basin).

            - Cost of relocation of any underground and above ground utilities is not
              expected and therefore excluded.

            - Agency oversight cost is excluded.
     5.0 Estimate Results
           Table 1
           Table 2
Construction Cost Estimate for Groundwater
Extraction/Recharge Basin

Construction Cost Estimate for Groundwater Treatment Plant
           Attachment A   Construction Cost Estimate detail for Recharge Basin
SELMA.DOC
                                                                              11/7/96

-------
                                                    Table 1
                                         USEPA/Sekna Pressure Treating Site

                                       Oroundwatar Extraction/Recharge Basin




const
rucDon MMI csonaie
I Weston Estimate*
Item
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19


Scope
Clearing & grubbing
Reflection wel
12" PVC reJnjectton piping
Including deanoute and sumps
4- PVC reinfection piping
Pressurized water system
Wei head piping
Wei vault
Bore/jack steel carrier pipe
Extraction well
4V2" extraction piping
10V6" extraction piping
12"/8" extraction piping
Leak detection system for
extraction system
Uft station 1
Security fencing and gates
Lift station 2
Electrical & control (50 HP)
Not used
Subtotal Construction Cost
round
Total Construction Cost. 4Q 96
Only
1
1
8
4.454
2.419
1
12
12
200
4
2,170
280
1.800
4.250
1
152
1
1



UnK
Is
Is
es
If
If
Is
ea
ea
If
ea
If
If
If
If
Is
If
Is
Is



UnK
Cost
281.475
5,629
23.644
39
11
135.108
6.868
Z815
563
22,518
68
126
169
12
128,353
23
188.025
394,065



* Original Weston's estimate of 1992 escalated to 4Q 96
Total
Cost
281.475
5.629
189.152
173.706
26,609
135.108
82,416
33,780
112,600
90.072
147,560
35.280
304,200
51.000
128,353
3.496
188,025
394,065

2,382,526
595.632
21.842
3.000.0QQ


Estimate for Extraction/Recharge Basin Concept |
UnK
Scope Only UnK Cost
Mobization 1 Is 281,475
Clearing & grubbing 1 Is 5.629
Dett.
8" PVC dass 150 piping 600 If 39
Delete
Delete
Wei head piping 4 ea 6.868
WelvauK 4 ea 2.815
Bore/tock steel carrier pipe 200 If 563
Extraction wen 4 ea 22,518
fOT extraction piping 100 If 68
10"/6T extraction piping 2,300 If 126
Delete
.ask detection system for 2,400 If 12
extraction system
Delete
Delete
Delete
Electrical & control (20 HP) 1 Is 160,000
Recharge basin (see Attach A) 1 I* 800,000
Subtotal Construction Cost
l^riiBttnnamr*! atf ^Wfaf
• wU mM lyM IV y •( &ym
round
Total Construction Cost, 4Q 96
- Escalate to 2Q 97 at 3«/yr
Total Construction Cost, 2Q 97
Total
Cost
281,475
5,629

23,400

27,472
11.260
112.600
90.072
6.800
289,800
28,800


160.000
600,000
1.637.308
408,327
53.365
2,100.000
31,500
2.1 31 .500
11/7/96
                                                                                               SELMA-IOLSTabtel

-------
                                         Table 2
                            USEPA/Selma Pressure Treating Site

                               Groundwater Treatment Plant
                                Construction Cost Estimate
Item
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15



Description
Mobilization
Equalization Tank
Chemical Storage Tank
Dirty Water Tank
Reactor Modules
Plate Separator/Thickener
Sand Filters
Effluent Storage Tanks
Rlter Press
Foundation and Sitework
Pumps and Equipment
Piping and Valves
Electrical and Controls
O & M Trailer
Monitoring/Analysis System
Subtotal Construction Costs
Contingency at 25%
round
Total Construction Cost, 4Q 96*
Total Cost
$
225,180
55,169
81,065
30,399
340,022
263,461
283,727
247,698
90,072
285,979
213,921
90,072
281,475
11,259
45,036
2,544,534
636,133
19,333
3.200.000
                     * Original Weston's estimate of 1992 escalated to 4Q 96
11/7/96
SELMA-1.XLSTable2

-------
FILE   :
DATE:

QTYBY:
EST BY:
J:\COMMON\YJYIM\ARCS\(SELMA-1 JCLSJTtbte 1
                                04-NOV-96
          Attachment A
USEPA/Selma Preaawe TrMting Site
         Recharge Baahi

    Construction Co«t Estimate
                                                                                                                          Locaton     Sekne. CA
                                                                                                                          ProducUvty      1.00
                                                                                                                          Labor Wage     36.00
                                                                                                                                     PAGE
ITEM


10






































DESCRIPTION


Rectum Basin. 2 ea. 200* x 2W eidl

DemoHah ndsUna aephal eurteoe, SOff x 25a

RMTWM exMkig bean, ISwxJhx 430" tang

Excavate lor basin No. 1& 2. 20ffx260'x8>l 2 ea

BedcM wth Mod lor beeln No. 1 A 2, Hoot thick

Construct 2 ramp*, ItTw x SOT long each

Construct epMway. 18Vrx401ong
- FMw fabric. lO-xSff
- 6" Reno rrwttreM. KTxSff
. Gabon, yvvWedTntehxiecriono
• Mtfto MM wonc, wow

Provkto manhole*. S db x T deep

Construct naw Mrth d»».15V» x J Moh x 1 .000* tono

Provto* • new cyclone fence, ff high. 6 ge

Haul A dhpoee demotahed nprwlt end excavated
eol (Olepoee wthki 20 mtee wXh no fee)
Alow for cM work required for level control and
otncr mtoc unw

HazardouewaHe operator traWna. alow
at 8 people, 50 hour* each


Total Direct FMd Cost

Indirect FMd Coat at 100% of Direct Labor Coat

Roundoff
TOTAL THIS PAGE. 4Q 96
QTY




14.000

750

22.222

3.700

500


600
60
20
100

2

1.700

1,800

25.000

1


1










UNIT




ay

cy

cy

cy

cy


af
ay
cy
cy

ea

cy

It

cy

R


R









UNIT COST
EQUIPT






1.40

1.40

0.60

1.20





1.40



1.20



5.30














MATLS










12.00




0.50
10.00
20.00


1,200







2.500












SIC




2.2C



















18.0C
















MANHOURS
UNIT MH






0.06

0.06

0.02

0.05


0.10
0.05
2.00
0.06

16

0.05



0.06

50


400









TOTAL






45

1.333

74

25


SO
3
40
8

32

85



2,075

50


400



4.218





WAGE
RATES









































COSTS IN $
EbUiPT






1.050

31.111

2.220

600





140



2.040



132.500








169,661





MATLS










44.400




250
800
400


2,400







2.500






50,550





LABOR






1,575

46,666

2.590

875


1,750
105
1.400
210

1.120

2.975



72,625

1.750


14,000



147,641





S/C




30.800



















32.400










63.20C





TOTAL




$30.800

$2.625

$77.777

$49,210

$1.475


$2.000
$705
$1.800
$35|

$3.520

$5.015

$32.400

$206.125

$4.25C


$14,OOC



$431,052

$147,641

$21.307
$600,000
      11/7/96
                                                                                                                                              SELMA-1 XLSAtt-A

-------

-------

-------

-------