'It's AH Downhill From Here!"
                                                                      ICR Update
                                                                  Jim Walasek, Editor
                                                              Technical Support Center
                                                                      February 1999
 July  '97  Data Finally  Final!


 ICR Update ISSUe Number 16 - This information sheet, the ICR
 Update, is the sixteenth one to be issued by the Technical Support Center (TSC) of the Office of
 Ground Water and Drinking Water (OGWDW).  Future issues will be distributed as needed to
 maintain information flow related to the ICR.

 Editor's Note: I've been wanting to use this headline for some time, but as you know there
 were problems with the validation process that delayed the final validation of the ICR
 monitoring data. You will receive the final validation report(s) for July 1997 in a few weeks. I
 know it took much longer than we expected, but the validation process is quite complicated and
 there were a number of "bugs" that had to be worked through. Final validation reports of the
 first three (and six) months of ICR monitoring data should be available in May of this year (see
 Status of ICR Data Validation).

    The deadline for submitting resubmission diskettes following review of the latest set of
 validation reports is February 5th. The next set of reports you receive will include validation
 reports for the entire second quarter of ICR monitoring (i.e., October, November, and
 December 1997). Even though you will be receiving a larger volume of reports the review
 period will be the same as hi the past, approximately 4 weeks. This should be adequate,
 however, since the monitoring phase of the ICR has been "wrapped up." We hope that
 everything will go much smoother now that we all have the experience of validation (the first
 three months, anyway) behind us. .Thanks for working with us during this difficult time. Now, 1 1
 we can just get through the rest of the winter!
            FlOW Data? - While reviewing each of the ICR data fields in ICRFE-l)
for completeness it was noted that several utilities had failed to provide flow data for influent
flow and some of the plant intakes. In the interest of having as complete a data set as possible
the affected utilities are being contacted to provide the missing information. A printout is be mi-
sent to affected utilities that lists the PWSED number and plant name, sampling period, intake

-------
 name, and water resource for which flow data is missing. Utilities are being asked to take the
 time to review the printout and update their monthly sampling data as necessary. They should
 send in replacement diskettes for the sampling months that were updated based on the printout
 and also, as time permits, review and update the flow data for the remaining sampling months.
 Replacement diskettes for Sampling Periods 01 and 02 (July and August 1997) should be sent to
 Jim Walasek at USEPA/TSC, 26 West M. L. King Drive (MS-140), Cincinnati, OH 45268.
 Diskettes for all subsequent sampling periods (03 - 18) should be sent to the following address:
 namely:
                                  USEPA (ICR4600)
                          ICR Data Center - Attn: Ed Cottrill
                               RoomlllSB East Tower
                                  401 M Street, S.W.
                                Washington, DC 20460

     Questions regarding this request should be directed to Jim Walasek at (513) 569-7919 or
 Fax him at (513) 569-7191.
          ,!„          .    „  .                           '»'        :   '  i
                                                                  i

 Wrong DechlOrinatlng Agent? -  Has your lab informed you that you
 incorrectly entered the wrong dechlorinating agent into the ICR Utility Database System for
 your chloral hydrate or haloacetonitrile samples? If you're having trouble figuring  out how to
 fix that mistake, or others that involve data from your laboratory, there is someone who can
 walk you through the process.  The EPA contractor who assisted EPA with the ICR chemistry
 laboratory approval program, is available to answer your questions. You can contact Science
 Applications International Corporation (SAIC) at 703-917-8496. Please note that they will only
 be able to help you with laboratory data questions - not questions about software problems or
 data entry for process control or design parameters.
                                                                  i

 Continued Protozoan PE  Program? -The ICR performance
 evaluation (PE) programs for protozoa.and virus have now concluded.  The last sets of PE filters
 were shipped in December. At this time there is no longer an EPA approval program for
 protozoa and virus laboratories for drinking water because EPA has no monitoring requirements
 for these analytes. However, due to the high visibility of the Cryptosporidium issues, there are
 many utilities which plan to continue their monitoring programs.  Because of this, laboratories,
 utilities and states have contacted us requesting that we continue to provide some kind of PE
 service for protozoa. Although this differs from the direction we are taking for the chemistry
 PE program (which has been transferred to the private sector), we are willing to try this for the
 short term on the assumption that it could also be transferred to the private sector if it proves
 successful.

    This program would be voluntary for the laboratory.  There would be no set pass/fail
criteria, but rather, laboratories would be furnished with the true values (after the results have
been submitted) and a summary of the data of all the participating laboratories.  We envision
sending two samples per quarter per laboratory (not per analyst). Similar to the ICR program.
we may choose to send a larger number of samples initially to obtain a more statistically
significant database with which to compare ongoing performance. The samples would consist of
live cysts and oocysts in a concentrated matrix. At this time it has not been determined whether
we will ship full volume or concentrated samples. The samples would then be filtered and

-------
  analyzed by whatever method the laboratory is using for client samples. This would be a PE
  program for enumeration only. We will not attempt to measure viability and infectivity.

      Because we have very little funding to apply to this program and are unable to charge
  laboratories for the service, we will have to ask the laboratories to pay for shipping in order to
 . keep our costs down. This cost will vary depending on the sample size.

      We will request some basic information from the laboratory in order to take part in the
  program  similar to the information provided during the IGR. Individual laboratory results will
  be provided only to the laboratory.  Customers may obtain a list of participating laboratories
  and summary data  from EPA but must request individual data from the laboratory itself. In
  order to participate in the program, laboratories will have to agree to provide this information to
  ineir clients on request.

      We will not be in a position to provide on site visits pr audits to the laboratories
 However, we would be willing to work with private industry to design a laboratory evaluation
 program similar to the ICR program which could then be purchased directly by the customer  It
 is up to the utility to be a wise consumer and take full advantage of the evaluation programs  '
 available to determine the capability of the laboratory.
 ni. ^ I0™™*0™1? ** I' !nterested in Participating in this PE program for protozoan analysis
 please Fax Mary Ann Feige at 513/569-7191 for application information.


 StatUS Of ICR Data Validation - December 1998 marked the completio
 of a major milestone for the ICR, the end of the ICR 18-month monitoring program This effort
 involved approximately 300 public water systems which conducted monitoring at 500 water
 treatment plants.  Laboratories will be analyzing ICR samples into early 1999; monitoring
 results for December 1998 from utilities and laboratories are due to EPA by April 1999 The
 validation of all of the data, July 1997 - December 1998, is scheduled for completion in
 November 1999.  The successful completion of the  18-month monitoring and the start-up of the
 data validation system could only have been accomplished because of the commitment by the
 water systems, their contractors, laboratories, EPA and its contractors and stakeholders.

    As of December 31, 1998, the third month of ICR sampling data (September 1997) and
 supporting laboratory QC data had been successfully uploaded into the ICR Federal (ICRFE D >
 database  Resubmission diskettes were also uploaded into the ICRFED, thus, upload of the flr,t

             '
                                                    COmP[eted-  1* <» computer
              were successfully run and internal data processing reviews were completed.
r                  19"' UtilltieS re°eiVed and began review of August and September 1
reports while laboratories reviewed August, September and October 1997 reports  Final
bchi999            a  *0™017 rep0rtS °r IUly and AugUSt 1997-m be <<
by March 1999. The next set of review reports is expected to be distributed by early March
    The overall schedule for data review by utilities is shown in Table 1. Once the review and

                 CPl6ted f°r ? chureP°rting Peri°d' the fmal data wil1 be «**** from :t
                    to auxiliary databases to facilitate data availability and analysis.

-------
                     Table 1. ICR Data Validation Review Schedule
Sample Months
3 through 6
7 through 9
10 through 12
13 through 15
16 through 18
Data Review Periods
March '99
May '99
June/July '99
August '99
October '99
Final Reports Distribution
May '99
July '99
September '99
November '99
December '99
Analysis of GAC Treatment Study Results -The last issue of
ICR Update included an article that provided a general overview of the data management plan
for the ICR treatment study data.  As a continuation of that article, the current article will
describe the analysis plan for the GAC study results.
                                                                   i
                           "        •                 ,.••,.••;!'        '   '  ' ''
     The GAC studies are designed to characterize the breakthrough profiles of DBF
precursors which occurs due to the unsteady-state nature of this process.  In order to maximize
the utility of this information, the breakthrough data will be fit with a logistic model that
describes the "S" shape of a typical breakthrough curve. For each set of breakthrough data, the
logistic model will be applied to the data in order to develop a set of equations that describe the
breakthrough trends. These continuous functions relate single contactor runtime to effluent
concentration for each water quality parameter, thus facilitating the evaluation of runtimes to
rfach any effluent concentration within the range of the data. Additionally, the integrated form
of the logistic equation provides an estimate of the blended effluent concentration as a function
of runtime (assuming ten or more contactors in parallel). The estimation of blended effluent
water quality is critical to the economic analysis of GAC performance since blending is
Commonly used at full-scale to extend the reactivation frequency, thus reducing costs.

     The equations describing the single contactor and blended contactor breakthrough profiles
will be transferred to a database. This will allow the user to evaluate the efficacy of GAC
treatment to achieve a specific treatment objective. Furthermore, the querying capability of this
database will allow the user to conduct this evaluation across all studies or a specified sub-set of
studies. A simplified description of this process follows:
                                                                   !
1.   Select a regulatory target (e.g., THM4 = 40 ug/L; HAAS = 30 ug/L, etc.).
2.   For a specific GAC run, use the single contactor breakthrough curve to determine the
     runtime at which the effluent concentration reaches this regulatory target.
3.   Use this single contactor runtime calculated under Step 2 to determine the effluent
     concentrations of other water quality parameters of interest (e.g., TOC, UV, BDCM, etc.).
4.  Use the integrated form of the logistic function to calculate the runtime at which the
    blended effluent concentration reaches the regulatory target!
5.   Repeat Steps 2 through 4 for additional study runs.
    This will be a very effective tool for evaluating the ability of GAC to meet different
regulatory targets for a variety of source waters.  However, the accuracy of this tool is only as

-------
 good as the data generated during the studies, and we are relying on the hard work and
 dedication of everyone involved in these studies to provide the highest quality data.


 Review Of Treatment Study Data -As the treatment studies near
 completion, individuals involved in conducting these tests will start to focus on the preparation
 of the Final Treatment Study Report. Prior to delving into this task, it is critical that the data
 undergo a thorough review. We are relying on utilities, consultants and laboratories to verify the
 accuracy of the data that are submitted to the final report. EPA will also conduct a review of the
 data in order to identify outliers and erroneous data entries; however, no one will be better able
 to evaluate the validity of your data than you.  So we ask that you spend a sufficient amount of
 time on this important task. Here are a few examples of things to look for during the review:

     Is all of the reported data generated from analytical batches that passed the QA/QC
     requirements in the DBP/ICR Analytical Methods Manual? If not, it may be necessary to
     report "NR" (not reported) for data associated with an analytical batch that failed QA/QC
     criteria.
 •    Were there problems with any of the simulated distribution system (SDS) tests?  If so, it
  •   may be necessary to report "NR" for DBFs associated with these SDS tests. For example,
     DBF data generated from SDS tests in which the free chlorine residual at the end of
     incubation was less than the minimum reporting level is considered invalid.
 •   Do plots of the data reveal outliers?  If so, are these outliers data entry errors that can be
     corrected? Was there a problem with sample collection or analysis for that observation?  If
    an outlier resulted from an identifiable problem that occurred during the study, "NR" should
    be reported for that result.                         i
 •   Is all of the data reported in the correct units?

    By carefully reviewing your data before submitting it to EPA, the amount of time and effort
 associated with external review and resubmission will be greatly reduced. Furthermore, this will
 increase the confidence level of rule negotiators that are relying on this data to make regulatory
 decisions.


 Spiking Program and Supplemental Surveys - Theica  Lab
 Spiking Program ended in December and data are now being validated. The Supplemental
 Surveys are scheduled to begin in March 19.99 for the Large and Medium systems; the projected
 start date for the Small System Survey is April 1999. Read on for  more details.

 Spiking Program - The lab spiking program ended in December 1998.  EPA would like to
thank again all the plants and laboratories who participated in the program.  Presently, we hav e
validated data for the spiking conducted May through October 1998. The current plan for data
release is to provide each utility the data for their two spiking events once the full 8 months of
data are available, thus allowing us to provide a context for the individual results. At that time.
we will make the complete data set available (while providing for anonymity of individual
utilities' results) and relevant summary statistics to all the participants. If any utility needs or
wants their individual data prior to then, please contact Heather Shank-Givens to receive the
summary sheets for your utility.

-------
       ICR Supplemental Surveys - We are now scheduled to begin the Large and Medium
       Supplemental Surveys the first week of March 1999!  EPA would like to thank the 87 utilities
       who are on board to participate for their enthusiasm and patience. We have resolved the
       contractual difficulties which impacted our ability to obtain sufficient laboratory support for the
       surveys.  A letter was sent during the week of January 25th providing all utilities the confirmed
       start date and providing each with a list of their biweekly sample dates (including dates for
       collecting extra water for matrix spikes). Utilities should expect to receive the necessary
       collection materials several days in advance of their first sample date.

           We are also striving to initiate the Small System Survey.  The program has obtained OMB
       approval and the recruitment letters have been sent! Letters were sent to 200 randomly selected
       small systems requesting their participation, from which we will select final 40 plants. During
       the week of February  1st, EPA contractors will begin calling the utilities to confirm their receipt
       of the invitation and to verify the contact information. We are asking for a reply on or before
       February 19,1999.  The projected start date for the Small System Survey is April 1999.

           For further information please contact Heather Shank-Givens at 202-260-0063 or at
       givens.heather@epa.gov.


       Checkitout! -  OGWDW  Home Page  - OGWDW on the internet has
       a hew name and a new face. The old address http://www.epa.gov/ogwdw still works; but an
       address that people will more likely remember, http://www.epa.gov/safewater. has been added.
       You will notice on entering the Home page that there are more graphics and that it has been
       streamlined. The subject areas no longer appear on the main page, but they are easy to find in
       the Topic Index.  For instance, click on Topic Index in the left margin, click on "I," and you MX-
       Information Collection Rule. Click there and you get to the ICR index page.  There are lots ot
       new articles and features on the Safewater Home Page. Let us know what you think.
United States
Environmental Protection Agency
Office of Ground Water and Drinking Water (MS-140)
Cincinnati, OH  45268

Official Business
Penalty for Private Usa
1300

EPA815-N-99-001a
PRESORTED FIRST CLASS
POSTAGE & FEES PAiO
 EPA PERMIT No G 35

-------