United States
        Environmental Protection     Office of Water       EPA 830-B-94-001
        Agency              (4201)           April! 994


&EPA  COMBINED SEWER OVERFLOW

        (CSO) CONTROL POLICY

-------

-------
ENVIRONMENTAL PROTECTION AGENCY



40 £FR Part 122



[FRL -             ]



Combined Sewer Overflow (CSO) Control Policy



AGENCY;  Environmental Protection Agency  (EPA)  ;



ACTION;   Final Policy



SUMMARY;  EPA has issued a national policy statement entitled



"Combined Sewer *bverflow (CSO) Control Policy."  This policy



establishes a consistent national approach for controlling



discharges from CSOs to the Nation's waters through the National



Pollutant Discharge Elimination System (NPDES) permit program.



FOR FURTHER INFORMATION CONTACT;  Jeffrey Lape, Office of



Wastewater Enforcement and Compliance, MC-4201, U.S.



Environmental Protection Agency, 401 M Street S.W., Washington,



D.Cl 20460, (202) 260-7361.



SUPPLEMENTARY INFORMATION;   The main purposes of the CSO Control



Policy are to elaborate on the Environmental Protection Agency's



(EPA's) National (CSO) Control Strategy published on September 8,.



1989, at 54 FR 37370, and to expedite compliance with the



requirements of the Clean Water Act (CWA).  While implementation



of the 1989 Strategy has resulted in progress toward controlling



CSOs, significant public health and water quality risks remain.



     This Policy provides guidance to permittees with CSOs, NPDES



authorities and State water quality standards authorities on



coordinating the planning,  selection,  and implementation of CSO



controls that meet the requirements of the CWA and allow for



public involvement during the decision-making process.

-------
     Contained in the Policy are provisions for developing
appropriate, site-specific NPDES permit requirements for all
combined sewer systems (CSS) that overflow as a result of wet
weather events.  For example, the Policy lays out two alternative
approaches ~ the "demonstration" and the "presumption"
approaches — that provide communities with targets for CSO
controls that achieve compliance with the Act, particularly
protection of water quality and designated uses.  The Policy also
includes enforcement initiatives to require the immediate
elimination of overflows that occur during dry weather and to
ensure that the remaining CWA requirements are complied with as
soon  as practicable.
      The permitting provisions of the Policy were developed as a
result of  extensive input received from key stakeholders during a
negotiated policy dialogue.  The CSO stakeholders included
representatives  from  States, environmental groups,  municipal
organizations  and others.   The negotiated dialogue  was conducted
during the Summer of  1992 by the Office of Water and  the Office
of Water's Management Advisory Group.  The enforcement
 initiatives,  including one  which is  underway  to address CSOs
 during dry weather,  were developed by  EPA's Office  of Water and
 Office of Enforcement.
      EPA issued a Notice of Availability on  the draft CSO  Control
 Policy on January 19, 1993, (58 FR 4994)  and requested comments
 on the draft Policy by March 22, 1993.  Approximately forty-one
 sets of written comments were submitted by a variety of interest

-------
groups including cities and municipal groups, environmental
groups, States, professional organizations and others.  All
comments were considered as EPA prepared the Fineil Policy.  The
public comments were largely supportive of the draft Policy.  EPA
received broad endorsement of and support for the key principles
and provisions from most commenters.- Thus, this final Policy
does not include significant changes to the major- provisions of
the draft Policy, but rather, it includes clarification and
better explanation of the elements of the Policy to address
several of the questions that were raised in the comments.
Persons wishing to obtain copies of the public comments or EPA's
summary analysis of the comments may write or call the EPA
contact person.
     The CSO Policy represents a comprehensive national strategy
to ensure that municipalities, permitting authorities, water
quality standards authorities and the public engage in a
comprehensive and coordinated planning effort to achieve cost
effective CSO controls that ultimately meet appropriate health'
and environmental objectives.  The Policy recognizes the site-
specific nature of CSOs and their impacts and provides the
necessary flexibility to tailor controls to local situations.
Major elements of the Policy ensure that CSO controls are cost
effective and meet the objectives and requirements of the CWA.
     The major provisions of the Policy are as follows.
     CSO permittees should immediately undertake a process to
accurately characterize their CSS and CSO discharges, demonstrate

-------
implementation of minimum technology-based controls identified in
the Policy, and develop long-term CSO control plans which
evaluate alternatives for attaining compliance with the CWA,
including compliance with water quality standards and protection
of designated uses.  Once the long-term CSO control plans are
completed, permittees will be responsible to implement the plans'
recommendations as soon as practicable.
     State water* quality standards authorities  will be involved ^
in the  long-term CSO control planning effort as well.  The water
quality standards authorities will help ensure that development
of the  CSO permittees' long-term CSO control plans are
coordinated with the review and possible revision of water
quality standards on CSO-impacted waters.
     NPDES authorities will issue/reissue or modify permits, as
appropriate,  to  require  compliance with the technology-based and
water  quality-based  requirements of the CWA.  After completion of
the  long-term CSO  control  plan,  NPDES permits will be reissued
or modified  to incorporate the  additional requirements specified
 in the Policy, such  as performance  standards  for  the  selected
 controls  based on average design conditions,  a post-construction
 water quality assessment program, monitoring  for  compliance with
 water quality standards, and a reopener clause  authorizing the
 NPDES authority to reopen and modify the permit if it is
 determined that the CSO controls fail to meet water quality
 standards or protect designated uses.
      NPDES authorities should commence enforcement actions

-------
against permittees that have CWA violations due to CSO discharges

during dry weather.  In addition, NPDES authorities should ensure

the implementation of the minimum technology-based controls and

incorporate a schedule into an appropriate enforceable mechanism,

with appropriate milestone dates, to implement the required long-

term CSO control plan.  Schedules for implementation of the long-

term CSO control plan may be phased based on the relative

importance of adverse impacts upon water quality standards and

designated uses, and on a permittee's financial capability.
 i
     EPA is developing extensive guidance to support the Policy

and will announce the availability of the guidances and other

outreach efforts through various means, as they become available.

Fpr example, EPA is preparing guidance on the nine minimum

cbntrols, characterization and monitoring of CSOs, development of

long-term CSO control plans, and financial capability.

     Permittees will be expected to comply with any existing CSO-

related requirements in NPDES permits, consent decrees or court

orders unless revised to be consistent with this Policy.

     The policy is organized as follows:

     I. INTRODUCTION

          A.   Purpose and Principles

          B.   Application of Policy

          C.   Effect on Current CSO Control Efforts

          D.   Small System Considerations

          E.   implementation Responsibilities

          F.   Policy Development

-------
II.  EPA OBJECTIVES FOR PERMITTEES
     A.   Overview
     B.   implementation of the Nine-Minimum Controls
     C.   Long-Term CSO Control Plan/Controls
          1. characterization, Monitoring and Modeling of
          Combined Sewer Systems
          2. Public Participation
          3. consideration of  Sensitive  Areas
          4. Evaluation of Alternatives
          5. cost/Performance  Consideration
           6. Operational Plan
           7. Maximizing Treatment at the POTW Treatment
           Plant
           8.  Implementation Schedule
           9.  Post-Construction Compliance Monitoring Program
 HI. COORDINATION WITH STATE WATER QUALITY STANDARDS
      A.   overview
      B.   Water  Quality Standards Reviews
 IV.   EXPECTATIONS FOR PERMITTING AUTHORITIES
       A.   overview
       B.   NPDES  Permit Requirements
            1.Phase I  Permits - Requirements for Demonstration
            of  Nine Minimum Controls and Development of
            the Long-Term CSO Control Plan
            2.  Phase II Permits - Requirements for
            implementation of a Long-Term CSO Control Plan

-------
   1             3. Phasing Considerations


   !  V.   ENFORCEMENT AND COMPLIANCE

                                                I
          A. Overview


          B. Enforcement of CSO Dry Weather Discharge Prohibition


          C. Enforcement of Wet Weather CSO Requirements


                1. Enforcement for Compliance with Phase I Permits


                2. Enforcement for Compliance with


                Phase II Permits


          D. Penalties





List of Subjects in 40 CFR Part 122:  Water Pollution Control


Authority:  Clean Water Act, 33 U.S.C. 1251 et seq.
   f


       .w

Carol M. Browner


Administrator

-------
           COMBINED  SEWER  OVERFLOW (CSO)  CONTROL  POLICY

I.INTRODUCTION

A.Purpose and Principles

     The main purposes of this Policy are to elaborate on EPA's
National Combined Sewer Overflow  (CSO) Control Strategy published
on September 8, 1989 at 54 FR 37370  (1989 Strategy) and to
expedite compliance with the requirements of the Clean Water Act
(CWA).  While implementation of the  1989 Strategy has resulted in
progress toward controlling CSOs, significant water quality risks
remain.

     A combined sewer system  (CSS) is a wastewater collection
system owned by a State or municipality  (as defined by Section
502(4) of the CWA) which conveys  sanitary wastewaters  (domestic,
commercial and industrial wastewaters) and storm water through a
single-pipe system to a Publicly  Owned Treatment Works (POTW)
Treatment Plant  (as defined in 40 CFR 403.3(p)).  A CSO is the
discharge from a CSS at a point prior to the POTW Treatment
Plant.  CSOs are point sources subject to NPDES permit
requirements including.both technology-based and water quality-
based requirements  of the CWA.  CSOs are not subject to secondary
treatment requirements applicable to POTWs.

     CSOs  consist of mixtures of  domestic sewage,  industrial and
commercial wastewaters, and storm water  runoff.  CSOs  often
contain high levels of suspended  solids, pathogenic
microorganisms,  toxic pollutants, floatables, nutrients, oxygen-
demanding  organic compounds,  oil  and grease, and other-
pollutants.  CSOs can cause exceedances  of water quality
standards  (WQS).  Such exceedances may pose risks  to. human
health, threaten aquatic  life and its habitat, and impair the use
and enjoyment  of the Nation's waterways.

      This  Policy is intended  to  provide  guidance to  permittees
with CSOs, National Pollutant Discharge  Elimination  System
 (NPDES) permitting  authorities,  State water quality  standards
authorities  and enforcement  authorities.  The purpose  of the
Policy is  to coordinate  the  planning, selection, design and
 implementation of  CSO  management practices and controls to meet
the requirements of the  CWA  and  to  involve the public  fully
during the decision making process.

      This  Policy reiterates  the  objectives  of  the  1989 Strategy:

      1.   To ensure that if CSOs  occur,  they  are  only as  a  result
      of wet weather;

      2   To bring all wet weather CSO discharge points into
      compliance with the technology-based and water quality-based
                                 8

-------
     requirements of the CWA; and

     3.  To minimize water quality, aquatic biota, and human
     health impacts from CSOs.

   :  This CSO Control Policy represents a comprehensive national
strategy to ensure that municipalities, permitting authorities,
water quality standards authorities and the public engage in a
comprehensive and coordinated planning effort to achieve cost-
effective CSO controls that ultimately meet appropriate health
and environmental objectives and requirements.  The Policy
recpgnizes the site-specific nature of CSOs and their impacts and
prqvides the necessary flexibility to tailor controls to local
situations.  Four key principles of the Policy ensure that CSO
controls are cost-effective and meet the objectives of the CWA.
The key principles are:

     1) "  providing clear levels of control that would be
   [       presumed to meet appropriate health and environmental
   ;       objectives;

     2)   providing sufficient flexibility to municipalities,
          especially financially disadvantaged communities,  to
          consider the site-specific nature of CSOs and to
   ;       determine the most cost-effective means of reducing
          pollutants and meeting CWA objectives and requirements;

     3)   allowing a phased approach to implementation of CSO
          controls considering a community's financial
   i       capability; and

     4)   review and revision, as appropriate, of water quality
          standards and their implementation procedures when
          developing CSO control plans to reflect the site-
          specific wet weather impacts of CSOs.

   ,  This Policy is being issued in support of EPA's regulations
and policy initiatives.  This Policy is Agency guidance only and
does not establish or affect legal rights or obligations.   It
does not establish a binding norm and is not finally
determinative of the issues addressed.   Agency decisions in  any
particular case will be made by applying the law and regulations
on the basis of specific facts when permits are issued.   The
Administration has recommended that the 1994 amendments to the
CWA endorse this final Policy.

     B.   Application of Policy

     The permitting provisions of this Policy apply to all CSSs
that overflow as a result of storm water flow, including snow
melt runoff (40 CFR Section 122.26(b)(13)).   Discharges from CSSs
during dry weather are prohibited by the CWA.   Accordingly,  the

-------
permitting provisions of this Policy do not apply to CSOs during
dry weather.  Dry weather flow is the flow in a combined sewer
that results from domestic sewage, groundwater infiltration,
commercial and industrial wastewaters, and any other non-
precipitation related flows  (e.g., tidal infiltration).  In
addition to the permitting provisions, the Enforcement and
Compliance section of this Policy describes an enforcement
initiative being developed for overflows that occur during dry
weather.

     Consistent with the 1989 Strategy, 30 States that submitted
CSO permitting strategies have received EPA approval or, in the
case of one State, conditional approval of its strategy.  States
and EPA Regional Offices should review these strategies and
negotiate appropriate revisions to them to implement this Policy.
Permitting authorities are encouraged to evaluate water pollution
control needs on a watershed management basis and coordinate CSO
control efforts with other point  and nonpoint source control
activities.

     C.   Effect on Current  CSO Control Efforts

     EPA recognizes that extensive work has been done by many
Regions, States, and municipalities to abate CSOs.  As such,
portions of this Policy may  already have been addressed by
permittees' previous efforts to control CSOs.  Therefore,
portions of this Policy may  not apply, as determined by the
permitting  authority on a  case-by-case basis, under the following
circumstances:

      1.  Any permittee that, on the date of publication of  this
      final  Policy,  has completed  or substantially completed
      construction  of  CSO  control  facilities that are designed  to
      meet WQS  and  protect  designated  uses, and where  it has been
      determined that  WQS  are being  or will be attained,  is  not
      covered  by the initial  planning  and construction  provisions
      in this  Policy;  however,  the operational plan  and post-
      construction  monitoring provisions  continue to apply.   If,
      after  monitoring,  it is determined  that  WQS are not  being
      attained,  the permittee should be required  to  submit a
      revised CSO control plan  that,  once implemented,  will  attain
      WQS.

      2.  Any permittee that, on the date of publication of this
      final Policy, has substantially developed or  is implementing
      a CSO control program pursuant to an existing permit or
      enforcement order,  and such program is considered by the
      NPDES permitting authority to be adequate to meet WQS and
      protect designated uses and is reasonably equivalent to the
      treatment objectives of this Policy,  should complete those
      facilities without further planning activities otherwise
      expected by this Policy.   Such programs, however, should be
                                 10

-------
     reviewed and modified to  be  consistent with  the  sensitive
     area, financial capability,  and post-construction  monitoring
     provisions of this Policy.

     3.  Any permittee that has previously constructed  CSO
     control facilities in an  effort to comply with WQS but has
     failed to meet such applicable standards or  to protect
     designated uses due to remaining CSOs may receive
     consideration for such efforts in future permits or
     enforceable orders for long-term CSO control planning,
     design and implementation.

     In the case of any ongoing or substantially  completed CSO
control effort, the NPDES permit  or other enforceable mechanism,
as ;appropriate, should be revised to include all  appropriate
permit requirements consistent with Section IV.B. of this Policy.

     D.   Small System Considerations

     The scope of the long-term CSO control plan, including the
characterization, monitoring and  modeling, and evaluation of
alternatives portions of this Policy may be difficult for some
small CSSs.  At the discretion of the NPDES Authority,
jurisdictions with populations under 75,000 may not need to
complete each of the formal steps outlined in Section II.c. of  •
thdjs Policy, but should be required through their permits or
other enforceable mechanisms to comply with the nine minimum
controls (II.B),  public participation (II.C.2),   and sensitive
areas (II.c.3)  portions of this Policy.   In addition,  the
permittee may propose, to implement any of t'he criteria contained
in jthis Policy for evaluation of  alternatives described in
II.;C.4.  Following approval of the proposed plan, such
jurisdictions should construct the control projects and propose a
monitoring program sufficient to determine whether WQS are
attained and designated uses are protected.

   ,  In developing long-term CSO control plans based on the
sma!ll system considerations discussed in the preceding paragraph,
permittees are encouraged to discuss the scope of their long-term
CSC- control plan with the WQS authority and the NPDES authority.
These discussions will ensure that the plan includes sufficient
information to enable the permitting authority to identify the
appropriate CSO controls.

     E.   Implementation Responsibilities

     NPDES authorities (authorized States or EPA Regional
Offices, as appropriate)  are responsible for implementing this
Policy.  It is their responsibility to assure that CSO permittees
develop long-term CSO control plans and that NPDES permits meet
the requirements of the CWA.   Further,  they are responsible for
coordinating the review of the long-term CSO control plan and  the

                               11              '.

-------
development of the permit with the WQS authority to determine if
revisions to the WQS are appropriate.  In addition, they should
determine the appropriate vehicle (i.e., permit reissuance,
information request under CWA Section 308 or State equivalent or
enforcement action) to ensure that compliance with the CWA is
achieved as soon as practicable.

     Permittees are responsible for documenting the
implementation of the nine minimum controls and developing and
implementing a long-term CSO control plan, as described in this
Policy.  EPA recognizes that financial considerations are a major
factor affecting the implementation of CSO controls.  For that
reason, this Policy allows consideration of a permittee's
financial capability in connection with the long-term CSO control
planning effort, WQS review, and negotiation of enforceable
schedules.  However, each permittee is ultimately responsible for
aggressively pursuing financial arrangements for the
implementation of its long-term CSO control plan.  As part of
this effort, communities should apply to their State Revolving
Fund program, or other assistance programs as appropriate, for
financial assistance.

     EPA and the States will undertake action to assure that all
permittees with CSSs are subject to a consistent review in the
permit development process, have permit requirements that achieve
compliance with the CWA, and are subject to enforceable schedules
that require the earliest practicable compliance date considering
physical and financial feasibility.

     F.   Policy Development

     This Policy devotes a separate section to each step
involved in developing and implementing CSO controls.  This is
not to  imply that  each function occurs separately.  Rather, the
entire  process surrounding CSO controls, community planning, WQS
and permit development/revision, enforcement/compliance actions
and public participation must be coordinated to control CSOs
effectively.  Permittees and permitting authorities are
encouraged to consider  innovative and alternative approaches and
technologies that  achieve the objectives of this Policy and the
CWA.

      In developing this  Policy,  EPA  has  included information on
what  responsible parties are  expected to accomplish.  Subsequent
documents  will  provide  additional guidance on how  the objectives
of this Policy  should be met.   These documents will provide
 further guidance on:   CSO  permit writing,  the nine minimum
 controls,  long-term CSO control plans,  financial capability,
 sewer system characterization and receiving water  monitoring and
modeling,  and application  of  WQS to  CSO-impacted waters.   For
most CSO control efforts however,  sufficient  detail has  been
 included in this Policy to begin immediate implementation of  its
                                 12

-------
provisions.


II.  EPA OBJECTIVES FOR PERMITTEES

     A.  Overview

     Permittees with CSSs that have CSOs should immediately
undertake a process to accurately characterize their sewer
systems, to demonstrate implementation of the nine minimum
controls, and to develop a long-term CSO control plan.

     B.  Implementation of the Nine Minimum Controls

     Permittees with CSOs should submit appropriate documentation
demonstrating implementation of the nine minimum controls,
including any proposed schedules for completing minor
construction activities.  The nine minimum controls are:

 ;    1.  proper operation and"regular maintenance programs for
 •^   the sewer system and the CSOs;

     2.  maximum use of the collection system for storage;

     3.  review and modification of pretreatment requirements to
     assure CSO impacts are minimized;

     4.  maximization of flow to the POTW for treatment;

     5.  prohibition of CSOs during dry weather;

     6.  control of solid and floatable materials in CSOs;

     7.  pollution prevention;

     8.  public notification to ensure that the public receives
     adequate notification of CSO occurrences and CSO impacts;
     and

     9.  monitoring to effectively characterize CSO impacts and
     the efficacy of CSO controls.            '*

     Selection and implementation of actual control measures
should be based on site-specific considerations including the
specific CSS's characteristics discussed under the sewer system
characterization and monitoring portions of this Policy.
Documentation of the nine minimum controls may include operation
and maintenance plans, revised sewer use ordinances for
industrial users, sewer system inspection reports;,
infiltration/inflow studies,  pollution prevention programs,
public notification plans, and facility plans for maximizing the
capacities of the existing collection, storage and treatment

                                13

-------

Policy.

 enforceable mechanism.
     C.  Long-Term cso control Plan







 designated uses.
     This policy identifies «£. -.Jar ^^^^.S^'Su
 ^rm ^rmCSsorcon?rol'plan as soon aS practicable, but generally
 long-term CSO control Pf*"        the NPDES permit provision,



 iSI^E-lS" a.-ss'is.-s essa  „ -
 appropriate  enforceable mechanism.
                           14

-------
     EPA expects each long-term CSO control plan to utilize
appropriate information to address the following minimum
elements.  The Plan should also include both fixed-date project
implementation schedules  (which may be phased) and a financing
plan to design and construct the project as soon as practicable.
The minimum elements of the long-term CSO control plan are
described below.

     1.  Characterization, Monitoring, and Modeling of the
     Combined Sewer System
   !                                             '
          In order to design a CSO control plan adequate to meet
   ,  the requirements of the CWA, a permittee should have a
     thorough understanding of its  sewer system, the response of
     the system to various precipitation events, the
   :  characteristics of the overflows, and the water quality
     impacts that result from CSOs.  The permittee should
     adequately characterize through monitoring, modeling, and
   '  other means as appropriate,  for a range of storm events, the
     response of its sewer system to wet weather events including
     the number, location and frequency of CSOs, volume,
     concentration and mass of pollutants discharged and the
     impacts of the CSOs on the receiving waters and their
     designated uses.   The permittee may need to consider
     information on the contribution and importance of other
     pollution sources in order to develop a final plan designed
     to meet water quality standards.   The purpose of the system
   !  characterization, monitoring and modeling program initially
     is to assist the permittee in developing appropriate
     measures to implement the nine minimum controls and,  if
   I  necessary, to support development of the long-term CSO
   ;  control plan.  The monitoring and modeling data also will be
     used to evaluate the expected effectiveness of both the nine
   ;  minimum controls and, if necessary,  the long-term CSO
   1  controls, to meet WQS.

   ;       The major elements of a sewer system characterization
     are described below.

          a.   Rainfall Records -  The permittee should examine
          the complete rainfall record for the geographic area of
          its existing CSS using sound statistical procedures and
          best available data.  The permittee should evaluate
          flow variations in the receiving water body to
          correlate between CSOs and receiving water conditions.

          b.   Combined Sewer System Characterization -  The
          permittee should evaluate the nature and extent of its
          sewer system through evaluation of available sewer
   ',       system records,  field inspections and other activities
          necessary to understand the number,  location and
          frequency of overflows and their location relative to

                               15

-------
sensitive areas and to pollution sources in the
collection system, such as indirect significant
industrial users.

c    CSO Monitoring -  The permittee should develop a
comprehensive, representative monitoring program that
the impact of the CSOs on the receiving waters   The
monitoring program should include necessary CSO
effluent and ambient in-stream monitoring and, where
appropriate, other monitoring protocols such as
biological assessment, toxicity testing - and sediment
saitmllnci.  Monitoring parameters should include, for^
exampS? oxygen demanding pollutants  nutrients, toxic
pollutants, sediment contaminants, pathogens,
bacteriological indicators  (e.g., Enterococcus
E. Coli), and toxicity.  A  representative sample of
overflow points can be selected that  is sufficient to
allow characterization of CSO discharges and their
water quality impacts and to facilitate evaluation of
control plan alternatives.

d    Modeling -   Modeling of a  sewer  system is
recognized  as a valuable tool  for predicting sewer
system response to various  wet  weather  events  and
assessing water quality  impacts when  evaluating
different  control strategies and  alternatives.   EPA
supports  the  proper and  effective use of models, where
Appropriate,  in the evaluation of the nine  minimum
 controls  and  the  development  of ^e long-term  CSO
 control plan.   It is also  recognized  that  there are
many models which may be used  to do this.   These models
 range from simple to complex.   Having decided to use a
 model, the permittee should base its  choice of a model
 on the characteristics of its , sewer  system the number
 and  location of overflow points,  and the sensitivity of
 ?he  receiving water body to the CSO discharges   Use of
 models should include appropriate calibration and
 verification with field measurements.  The
 sophistication of the model should relate to the
 complexity of the system to be modeled and to the
 information needs associated with evaluation of CSO
 control options  and water  quality impacts.  EPA
 believes that continuous simulation models, using
 historical rainfall data,  may be the best way to model
  sewer systems, CSOs, and their impacts   Because of the
  iterative  nature of modeling sewer systems  CSOs  and
  their impacts, monitoring  and modeling efforts are
  complementary and should be coordinated.
                       16

-------
2.   Public Participation

     In developing its long-term CSO control plan, the
permittee will employ a public participation process that
actively involves the affected public in the decision-making
to select the long-term CSO controls.  The affected public
includes rate payers, industrial users of the sewer system,
persons who reside downstream from the CSOs, persons who use
and enjoy these downstream waters, and any other interested
persons.

3.  Consideration of. Sensitive Areas       ]

     EPA expects a permittee's long-term CSO control plan to
give the highest priority to controlling overflows to
sensitive areas. Sensitive areas, as determined by the NPDES
authority in coordination with State and Federal agencies,
as appropriate, include designated Outstanding National
Resource Waters, National Marine Sanctuaries, waters with
threatened or endangered species and their habitat, waters
with primary contact recreation, public drinking water
intakes or their designated protection areas, and shellfish
beds.  For such areas, the long-term CSO control plan
should:

     a.  prohibit new or significantly increased overflows;

     b.   i.  eliminate or relocate overflows that discharge
          to sensitive areas wherever physically possible
          and economically achievable,  except where
          elimination or relocation would provide less
          environmental protection than additional
          treatment;  or

          ii.   where elimination or relocation is not
          physically possible and economically achievable,
          or would provide less environmental protection
          than additional treatment,  provide the level of
          treatment for remaining overflows deemed necessary
          to meet WQS for full protection of existing and
          designated uses.  In any event, the level of
          control should not be less than those described in
          Evaluation of Alternatives below; and

     c.   Where elimination or relocation has been proven
     not to be physically possible and economically
     achievable, permitting authorities should require,  for
     each subsequent permit term, a reassessment based on
     new or improved techniques to eliminate or relocate,  or
     on changed circumstances that influence economic
     achievability.
                           17

-------
4.  Evaluation of Alternatives

     EPA expects the long-term CSO control plan to consider
a reasonable range of alternatives.  The plan should, for
example, evaluate controls that would be necessary to
achieve zero overflow events per year, an average of one to
three,-four to seven, and eight to twelve overflow events
per year.  Alternatively, the long-term plan could evaluate
controls that achieve 100% capture, 90% capture, 85%
capture, 80% capture, and 75% capture for treatment.  The
long-term control plan should also consider expansion of
POTW secondary and primary capacity in the CSO abatement
alternative analysis.  The analysis of alternatives should
be sufficient to make a reasonable assessment of cost and
performance as described in Section II.C.5.  Because the
final long-term CSO  control plan will become the basis for -
NPDES permit limits  and requirements, the selected controls
should  be sufficient to meet CWA requirements.

     In addition to  considering sensitive areas, the long-
term CSO control plan should adopt one of the following
approaches:

     a.  "Presumption" Approach

          A program  that meets any of the criteria  listed
     below would be  presumed to provide  an adequate  level of
     control to meet the water quality-based requirements of
     the CWA,  provided  the  permitting authority determines
     that such presumption  is reasonable in light of the
      data and  analysis  conducted  in the  characterization,
     monitoring, and modeling of  the  system and the
      consideration of  sensitive areas described above. These
      criteria  are  provided  because data  and modeling of wet
      weather  events  often do  not  give a  clear picture  of the
      level  of  CSO  controls  necessary  to  protect WQS.

           i.   no more  than  an average of four overflow
           events per year,  provided  that the permitting
           authority may allow up  to  two  additional  overflow
           events per year.   For the  purpose  of  this
           criterion, an overflow event is one  or  more
           overflows from a CSS as the result of a
           precipitation event that does  not  receive the
           minimum treatment specified below;  or

           ii.  the  elimination or the capture for treatment
           of no less than 85% by volume of the combined
           sewage collected in the CSS during precipitation
           events on a system-wide annual average basis;  or
                            18

-------
      iii.   the elimination or removal  of no less than
      the mass  of  the  pollutants,  identified as causing
      water  quality  impairment through  the sewer system
      characterization,  monitoring,  and modeling effort,
      for the volumes  that  would be  eliminated  or
      captured  for treatment under paragraph ii.  above.

Combined sewer flows  remaining after implementation  of
the nine minimum  controls  and within the criteria
specified at II.C.4.a.i or ii, should  receive  a  minimum
of:

      o    Primary clarification (Removal of floatables
          and  settleable solids may be. achieved  by any
          combination of treatment technologies  or
          methods that are shown  to be equivalent to
          primary clarification.)/

      o    Solids  and floatables disposal; and

      o    Disinfection of  effluent, if  necessary, to
          meet WQS, protect designated  uses  and protect
          human .health, including removal of harmful
          disinfection chemical residuals, where
          necessary.

b.    "Demonstration" Approach

     A permittee  may demonstrate that a  selected
control program,  though not meeting the  criteria
specified in II.C.4.a. above is adequate to meet the
water quality-based requirements of the  CWA.  To be a
successful demonstration,  the permittee  should
demonstrate each  of the following:

     i.  the planned control program is adequate to
     meet WQS and protect designated uses, unless WQS
     or uses cannot be met as a result of natural
     background conditions or pollution sources other
     than CSOs;

     ii.  the CSO discharges remaining after
     implementation of the planned control program will
     not preclude the attainment of WQS or the
     receiving waters' designated uses or contribute to
     their impairment.  Where WQS  and designated uses
     are not met  in part because of natural background
     conditions or pollution sources other than CSOs,
     a total maximum daily load,  including a wasteload
     allocation and a load allocation,  or other means
     should be used to apportion pollutant loads;
                      19

-------
          iii.   the planned control program will provide the
          maximum pollution reduction benefits reasonably
          attainable;  and

          iv.    the planned control program is designed to
          allow cost effective expansion or cost effective
          retrofitting if additional controls are
          subsequently determined to be necessary to meet
          WQS or designated uses.

5.  cost/Performance Considerations

     The permittee should develop appropriate
cost/performance curves to demonstrate the relationships
among a comprehensive set of reasonable control alternatives
that correspond to the different  ranges specified in
Section II.C.4.  This should include an analysis to
determine where the increment of pollution reduction
achieved in the receiving water diminishes compared to tne
increased costs.  This analysis, often known as knee of the
curve, should be among the considerations used to help guide
selection of controls.

6.   Operational Plan

     After agreement between the permittee and NPDES
authority on the necessary CSO controls to be implemented
under the long-term CSO control plan, the permittee should
revise the operation and maintenance program developed as
part of the nine minimum controls to include the agreed-upon
long-term CSO controls.  The revised operation and
maintenance program should maximize the removal of
pollutants during  and after each precipitation event using
all available facilities within  the collection and treatment
system.   For any  flows  in  excess of the criteria specified
at II.C.4.a.i.,  ii. or  iii and not receiving the treatment
specified in II.C.4.a,  the operational plan should ensure
that  such flows receive treatment  to the greatest extent
practicable.

7.  Maximizing  Treatment at the  Existing POTW Treatment
    Plant

      In some communities,  POTW- treatment plants  may have
primary treatment capacity in excess of their secondary
treatment capacity.   One effective strategy to  abate
pollution resulting from CSOs is to maximize the delivery  of
 flows during wet weather to the POTW treatment  plant  for
 treatment.  Delivering these flows can have two significant
 water quality benefits: first,  increased  flows  during wet
 weather to the POTW treatment plant may enable the permittee
 to eliminate or minimize overflows to sensitive areas;
                            20

-------
second, this would maximize the use of available POTW
facilities for wet weather flows and would ensure that
combined sewer flows receive at least primary treatment
prior to discharge.
     Under EPA regulations, the intentional diversion of
waste streams from any portion of a treatment facility,
including secondary treatment, is a bypass..  EPA bypass
regulations at 40 CFR Section 122.41(m) allow for a facility
to bypass some or all the flow from its treatment process
under specified limited circumstances.  Under the
regulation, the permittee must show that the bypass was
unavoidable to prevent loss of life, personal injury or
severe property damage, that there was no feasible
alternative to the bypass and that the permittee submitted
the required notices.  In addition, the regulation provides
that a bypass may be approved only after consideration of
adverse effects.

     Normally, it is the responsibility of the permittee to
document, on a case-by-base basis, compliance with 40 CFR
Section 122.41(m)  in order to bypass flows legally.  For
some CSO-related permits, the study of feasible alternatives
in the control plan may provide sufficient support for the
permit record and for approval of a CSO-related bypass in
the permit itself, and to define the specific parameters
under which a bypass can legally occur.  For approval of a
CSO-related bypass, the long-term CSO control plan, at a
minimum, should provide justification for the cut-off point
at which the -flow will be diverted from the secondary
treatment portion of the treatment plant, sind provide  a
benefit-cost analysis demonstrating that conveyance of wet
weather flow to the POTW for primary treatment is more
beneficial than other CSO abatement alternatives such as
storage and pump back for secondary treatment, sewer
separation, or satellite treatment.  Such a permit must
define under what specific wet weather conditions a CSO-
related bypass is allowed and also specify what treatment or
what monitoring, and effluent limitations aind requirements
apply to the bypass flow.  The permit should also provide
that approval for the CSO-related bypass will be reviewed
and may be modified or terminated if there is a substantial
increase in the volume or character of pollutants being
introduced to the POTW.  The CSO-related bypass provision in
the permit should also make it clear that all wet weather
flows passing the headworks of the POTW treatment plant will
receive at least primary clarification and solids and
floatables removal and disposal, and disinfection, where
necessary, and any other treatment that can reasonably be
provided.

     Under this approach, EPA would allow ci permit to
authorize a CSO-related bypass of the secondary treatment

                           21

-------
portion of the POTW treatment plant for combined sewer flows
in certain identified circumstances.  This provision would
aSplv only to those situations where the POTW would
ordinarily meet the requirements of 40 CFR 122.41(m) as
evaSKedon a case-by-case basis.  Therefore  there must be
Sufficient data in the administrative record (reflected in
the permit fact sheet or statement of basis) supporting all
th! requirements in 40 CFR Section 122.41(m)(4) for approval
of an anticipated bypass.

     For the purposes of applying this regulation to CSO
permittees, "severe property damage" could i™^6
Situations where flows above a certain level wash out the
POTW's secondary treatment system.  EPA further believes
S£t !he feasible alternatives requirement of  the regulation
can be met if the record shows that the secondary treatment
svstem is properly operated and  maintained, that the system
hal Ken designedtomeet secondary limits  for flows greater
than the peak dry weather flow,  plus an appropriate quantity
of wet weather  flow,  and that  it is either  technically  or
financially  infeasible to provide secondary treatment at the
JSSSng facilities  for greater  amounts of  wet weather  flow.
The  feasible alternative analysis should  include, for
example, consideration of enhanced primary  treatment  (e.g.,
chemical addition)  and non-biological  secondary treatment.
SSS  Sases  supporting a  finding of no feasible alternative
may  also  be  available on  a  case-by-case basis. AB  part of
 its  consideration of possible adverse  effects  resulting from
the!  byplss?  the permitting  authority  should also  ensure that
the  bvpass will not cause exceedances  of  WQS.
      This  Policy does not address the appropriateness  of
 approving anticipated bypasses through NPDES permits  in
 advance outside the CSO context.

 8.   Implementation Schedule

      The permittee should include all pertinent information
 in the long term control plan necessary to develop the
 construction and financing schedule *?' implementation of
 CSO controls. ' Schedules for implementation of the CSO
 controls may be phased based on the relative  importance of
 adverse impacts Spon WQS and designated uses  priority
 projects identified  in the long-term plan, and on a
 permittee's financial capability.

      Construction phasing should  consider:

      a.  Eliminating overflows  that discharge to sensitive
      areas  as  the highest priority;
       b.   Use impairment;


                            22

-------
          c.  The permittee's financial capability  including
          consideration of such factors as:

   :            i.  Median household income;

               ii.  Total annual wastewater and CSO contrpl costs
               per household as a percent of median household
               income;

               iii.   Overall net debt as a percent of full
               market property value;

   ;            iv.  Property tax revenues as a percent of full
               market property value;

               v.   Property tax collection rate;

               vi.   Unemployment; and

               vii.  Bond rating;

          d.  Grant and loan availability;

          e.  Previous and current residential, bornmercial and
   ;       industrial sewer user fees and rate structures; and

          f.  Other viable funding mechanisms and sources of
          financing.

   ;  9.  Post-Construction Compliance Monitoring Program

          The selected CSO controls should include a post-
     construction water quality monitoring program adequate to
     verify compliance with water quality standards and
     protection of designated uses as well as to ascertain the
     effectiveness of CSO controls.  This water quality
     compliance monitoring program should include a plan to be
     approved by the NPDES authority that details the monitoring
     protocols to be followed,  including the necessary effluent
     and ambient monitoring and,  where appropriate,  other
     monitoring protocols such as biological assessments, whole
     effluent toxicity testing,  and sediment sampling.

III. COORDINATION WITH STATE WATER QUALITY STANDARDS

     A.   Overview

     WQS are State adopted,  or Federally promulgated rules which
serve as the goals for the water body and the legal basis for the
water quality-based NPDES permit requirements under the CWA.   WQS
consist of uses which States designate for their water bodies,
criteria to protect the uses,  an anti-degradation policy to

                               23

-------
protect the water quality improvements gained and other policies
affecting the implementation of the standards.  A primary
objective of the long-term CSO control plan is to meet WQS,
including the designated uses through reducing risks to human
health and the environment by eliminating, relocating or
controlling CSOs to the affected waters.
     State WQS authorities, NPDES authorities, EPA regional
offices, permittees, and the public should meet early and
frequently throughout the long-term CSO control planning process.
Development of the long-term plan should be coordinated with the
review and appropriate revision of WQS and implementation
procedures on CSO-impacted waters to ensure that the long-term
controls  will be sufficient to meet water quality standards.  As
part of these meetings, participants should agree on the data,
information and analyses needed to support the development of the
long-term CSO control plan and the review of  applicable WQS, and
implementation procedures, if appropriate.  Agreements should be
reached on the monitoring protocols and models that will be used
to evaluate the water quality impacts of the  overflows, to
analyze the attainability of the WQS and to determine the water
quality-based requirements for the permit.  Many opportunities
exist  for permittees and States to share  information as control
programs are developed and as WQS are reviewed.  Such information
should assist States in determining the need  for revisions to WQS
and  implementation procedures to better reflect the site-specific
wet  weather impacts of CSOs.  Coordinating the development of the
long-term CSO control plan and the review of  the WQS and
implementation procedures provides greater assurance that the
long-term control plan selected and the limits and requirements
included  in the NPDES permit will be sufficient to meet WQS and
to comply with Sections  30l(b)(l)(C) and  402(a)(2) of the CWA.

      EPA  encourages  States and permittees  jointly to sponsor
workshops  for the  affected public  in the  development of the  long-
term CSO  control plan  and  during the development of appropriate
revisions  to WQS  for  CSO-impacted waters.  Workshops provide  a
forum for including the  public  in discussions of the  implications
of  the proposed  long-term CSO  control  plan on the water quality
and uses  for  the  receiving water.

      B-.    Water Quality Standards  Reviews

      The CWA requires States to periodically, but  at  least once
 every three years,  hold public hearings for the purpose  of
 reviewing applicable water quality standards and,  as ,aPP^°P^^e;
 modifying and adopting standards.   States must provide the public
 an opportunity to comment on any proposed revision to water
 quality standards and all revisions must be submitted to EPA for
 review and approval.

      EPA regulations and guidance provide States with the
 flexibility to adapt their WQS, and implementation procedures to
 reflect site-specific conditions including those related to CSOs.
 For example, a State may adopt site-specific criteria for a
                                 24

-------
particular pollutant if the State determines thcit the site-
specific criteria fully protects the designated-use  (40 CFR
Section 131.11).  In addition, the regulations at 40 CFR Section
131.10(g), (h), and (j) specify when and how a designated use may
be 'modified.  A State may remove a designated use from its water
quality standards only if the designated use is not an existing
use.  An existing use is a use actually attained in the water
body on or after November 28, 1975.  Furthermore, a State may not
remove a designated use that will be attained by implementing the
technology-based effluent limits required under Sections 301(b)
and 306 of the CWA and by implementing cost-effective and
reasonable best management practices for nonpoimt source
controls.  Thus, if a State has a reasonable basis to determine
that the current designated use could be attained after
implementation of the technology-based controls of the CWA, then
the use could nost be removed.

     In determining whether a use is attainable and prior to
removing a designated use, States must conduct and submit to EPA
a use attainability analysis.  A use attainability analysis is a
structured scientific assessment of the factors affecting the
use, including the physical, chemical, biological, and economic
factors described in 40 CFR Section 131.10(g).   As part of the
analysis, States should evaluate whether the designated use could
be attained if CSO controls were implemented.  For example,
States should examine if sediment loadings from CSOs could be
reduced so as not to bury spawning beds, or if biochemical oxygen
demanding material in the effluent or the toxicity of the
effluent could be corrected so as to reduce the acute or chronic
physiological stress on or bioaccumulation potential of aquatic
organisms.

     In reviewing the attainability of their WQS and the
applicability of their implementation procedures to CSO-impacted
waters, States are encouraged to define more explicitly their
recreational and aquatic life uses and then, if appropriate,
modify the criteria accordingly to protect the designated uses.

     Another option is for States to adopt partial uses by
defining when primary contact recreation such as swimming does
not exist, such as during certain seasons of the year in northern
climates or during a particular type of storm event.  In making
such adjustments to their uses,  States must ensure that
downstream uses are protected, and that during other seasons or
after the storm event has passed, the use is fully protected.

     In addition to defining recreational uses with greater
specificity, States are also encouraged to define the aquatic
uses more precisely.  Rather than "aquatic life use protection,"
States should consider defining the type of fishery to be
protected such as a cold water fishery (e.g., trout or salmon)  or
a warm weather fishery (e.g., bluegill or large mouth bass).
Explicitly defining the type of fishery to be protected may
assist the permittee in enlisting the support of citizens for a

   !                             25

-------
CSO control plan.

     A water quality standard variance may be appropriate, in
limited circumstances on CSO-impacted waters  where the State is
uncertain as to whether a standard can be attained and time is
needed for the State to conduct additional analyses on the
attainability of the standard.  Variances are short-term  .
modifications in water quality standards.  Subject to EPA
approval SStiS, with their own statutory authority ^y grant a
variance to a specific discharger for a  specific pollutant.  The
Justification Sor a variance is similar  to that required for a
                             d  althouh the showings needed
 ustifcaton  or a va
ne^manent change in the  standard,  although the showings needed
Sre leS rigorous.  Variances are also  subject to public



                                               coned ana
 re le   rigorous.  Variances are aso suec
as progress is made to improve water quality

     Tustifications for variances are the same as those
             ?faP -S?        tppe                io   .
      S Standards and reviews the variance every three years.
 IV.   EXPECTATIONS FOR PERMITTING AUTHORITIES
      A.  overview
      CSOs are point sources subject to NPDES permit requirements


 g^V" {Son+gninerv Env.i i-nninental Position VS. Costle, 646 F.2d
 568 (D.C. Cir. 1980) ) .
      All oermits for CSOs  should require the nine minimum

 = L^^
 Sil Vssrs&rss, i^sus-s-a^srs"^
 ?eqS?riments are to be established based on applicable  water
 quality standards.
                               26

-------
authority should generally require joint preparation and
implementation of the elements of this Policy and should
specifically define the responsibilities and duties of each
authority.  Permittees should be required to coordinate system-
wide implementation of the nine minimum controls arid the
development and implementation of the long-term CSO control plan.
The,individual authorities are responsible for their own
discharges and should cooperate with the permittee for the POTW
receiving the flows from the CSS.  When a CSO is permitted
separately from the POTW, both permits should be cross-referenced
foriinformational purposes.

    , EPA Regions and States should review the CSO permitting
priorities established in the State CSO Permitting Strategies
developed in response to the 1989 Strategy.  Regions and States
may;elect to revise these previous priorities.  In setting
permitting priorities, Regions and States should not just focus  "
on those permittees that have initiated monitoring programs.
When setting priorities, Regions and States should consider, for
example, the known or potential impact of CSOs on sensitive
areas, and the extent of upstream industrial user discharges to
the CSS.

    I During the permittee's development of the long-term CSO
control plan, the permit writer should promote coordination
between the permittee and State WQS authority in connection with
possible WQS revisions.  Once the permittee has completed
development of the long-term CSO control plan and has coordinated
with the permitting authority the selection of the controls
necessary to meet the requirements of the CWA, the permitting
authority should include in an appropriate enforceable mechanism,
requirements for implementation of the long-term CSO control
plan, including conditions for water quality monitoring and
operation and maintenance.

     B.  NPDES Permit Requirements

    ; Following are the major elements of NPDES permits to
implement this Policy and ensure protection of water quality.

     1,  Phase I Permits -  Requirements for Demonstration of
     Implementation of the Nine Minimum Controls,and Development
     of the Long-Term CSO Control Plan.

          In the Phase I permit issued/modified to reflect this
     Policy, the NPDES authority should at least require
     permittees to:

    !      a.  immediately implement BAT/BCT, which at a minimum
          includes the nine, minimum controls, as determined on a
          BPJ basis by the permitting authority;
                                27

-------
     b.   develop and submit a report documenting the _
     implementation of  the nine minimum controls withzn two
     years of permit issuance/modification;

     c.   comply with applicable WQS, no later than the date
     allowed under the  State's WQS,  expressed in the form of
     a narrative limitation; and

     d.   develop and submit, consistent with this Policy and
     based on a schedule in an appropriate enforceable
     mechanism, a long-term CSO control plan as soon as
     practicable, but generally within two years after the
     effective date of  the permit issuance/ modification.
     However, permitting authorities may establish a longer
     timetable for completion of the long-term CSO control
     plan on a case-by-case basis to account for site-
     specific factors that may influence the complexity of
     the planning process.

     The NPDES authority should include, compliance dates on
the fastest practicable schedule for each of the nine
minimum controls in an appropriate enforceable mechanism
issued in conjunction with the Phase I permit.  The use of
enforceable orders is necessary unless Congress amends the
CWA.  All orders should require compliance with the nine
minimum controls no later than January 1, 1997.

2.  Phase II Permits -  Requirements for Implementation of a
Long-Term CSO  Control Plan

     Once the  permittee has  completed development of the
long-term CSO  control plan  and the  selection of the controls
necessary to meet  CWA requirements  has been coordinated with
the permitting and WQS authorities,  the permitting authority
should include,  in an appropriate enforceable mechanism,
requirements  for implementation of  the  long-term CSO control
plan  as  soon  as practicable.   Where the permittee has  ,
selected controls  based on the "presumption" approach
described in Section II.C.4,  the permitting  authority  must
have  determined that the  presumption that  such  level .of
treatment will achieve water quality standards  is reasonable
in light of the data and  analysis conducted  under this
Policy.   The Phase II  permit should contain:

      a   Requirements  to  implement  the technology-based
      controls including the nine minimum controls determined
      on  a BPJ basis;

      b   Narrative requirements which  insure that the
      selected CSO controls are implemented,  operated and
      maintained as described in the long-term CSO control
      plan;
                            28

-------
c.  Water quality-based effluent limits under 40 CFR
Sections 122.44(d)(1) and 122.44(k), requiring, at a
minimum, compliance with, no later tham the date
allowed under the State's WQS, the numeric performance
standards for the selected CSO controls, based on
average design conditions specifying ait least one of
the following:

     i.  A maximum number of overflow events per year
     for specified design conditions consistent with
     II.C.4.a.i; or

     ii.  A minimum percentage capture of combined
     sewage by volume for treatment under specified
     design conditions consistent with II.C.4.a.ii; or

     iii.  A minimum removal of the mass of pollutants
     discharged for specified design conditions
     consistent with II.C.4.a.iii; or

     iv.  performance standards and requirements that
     are consistent with II.C.4.b. of the Policy.

d.  A requirement to implement, with an established
schedule, the approved post-construction water quality
assessment program including requirements to monitor
and collect sufficient information to demonstrate
compliance with WQS and protection of designated uses
as well as to determine the effectiveness of CSO
controls.

e.  A requirement to reassess overflows to sensitive
areas in those cases where elimination or relocation of
the overflows is not physically possible and
economically achievable.  The reassessment should be
based on consideration of new or improved techniques to
eliminate or relocate overflows or changed
circumstances that influence economic achievability;

f. Conditions establishing requirements for maximizing
the treatment of wet weather flows at the POTW
treatment plant, as appropriate,  consistent with
Section II.C.7. of this Policy;

g.  A reopener clause authorizing the NPDES authority
to reopen and modify the permit upon determination that
the CSO controls fail to meet WQS or protect designated
uses.  Upon such determination, the NPDES authority
should promptly notify the permittee and proceed to
modify or reissue the permit.  The permittee should be
required to develop, submit and implement, as soon as
practicable, a revised CSO control plan which contains
additional controls to meet WQS and designated uses.
If the initial CSO control plan was approved under the

                      29

-------
          demonstration  provision  of  Section  II.C.4.b.,  the
          revised  plan,  at  a  minimum,  should  provide  for controls
          that  satisfy one  of the  criteria  in Section II.C.4.a.
          unless the  permittee demonstrates that  the  revised plan
          is  clearly  adequate to meet WQS at  a lower  cost and it
          is  shown that  the additional controls resulting from
          the criteria in Section  II.C.4.a  will not result in a
          greater  overall improvement in water quality.

          Unless the  permittee can comply with all  of the
     requirements  of  the Phase II  permit, the NPDES authority
     should include,  in  an  enforceable mechanism, compliance
     dates on the  fastest practicable schedule for  those
     activities directly related to meeting the requirements of
     the CWA.  For major permittees,  the compliance schedule
     should be  placed in a  judicial order.  Proper  compliance
     with the schedule for  implementing the controls  recommended
     in the long-term CSO control  plan constitutes  compliance
     with the elements of this Policy concerning  planning and
     implementation of a long term CSO remedy.

     3.  Phasing  Considerations

          Implementation of CSO controls may  be phased based on
     the relative importance of and adverse impacts upon WQS and
     designated uses, as well as  the  permittee's  financial
     capability and its  previous  efforts to control CSOs.  The
     NPDES authority should evaluate  the proposed implementation
     schedule and construction phasing discussed  in Section
     II.C.8.  of this Policy.   The permit should require
     compliance with the controls proposed  in the long-term CSO
     control plan no later  than the applicable deadline(s) under
     the CWA or State law.   If compliance with the  Phase II
     permit is  not possible,  an enforceable schedule, consistent
     with the Enforcement and Compliance Section  of this Policy,
     should be issued in conjunction with  the Phase II permit
     which specifies the schedule and milestones  for
     implementation of the long-term CSO control  plan.

V.   ENFORCEMENT AND COMPLIANCE

     A.   Overview

     It  is important that permittees act immediately to take the
necessary steps to comply with the CWA.  The  CSO enforcement
effort will  commence with an  initiative to address CSOs that
discharge during  dry weather,  followed by an  enforcement effort
in conjunction with permitting CSOs discussed earlier in this
Policy.   Success  of the  enforcement effort will depend in large
part upon  expeditious action  by NPDES authorities  in  issuing
enforceable  permits that include  requirements both for the nine
minimum controls  and for compliance with all  other requirements
of the CWA.  Priority for  enforcement actions should  be  set based
on environmental  impacts or  sensitive areas  affected  by  CSOs.
                                30

-------
     As a further inducement for permittees to cooperate with
this process, EPA is prepared to exercise its enforcement
discretion in determining whether or not to seek civil penalties
for past CSO violations if permittees meet the objectives and
schedules of this Policy and do not have CSOs during dry weather.

     B.   Enforcement of CSO Dry Weather Discharge Prohibition

  '   EPA intends to commence immediately an enforcement
initiative against CSO permittees which have CWA violations due
toiCSOs during dry weather.  Discharges during dry weather have
always been prohibited by the NPDES program.  Such discharges can
create serious public health and water quality problems.  EPA
will use its CWA Section 308 monitoring, reporting, and
inspection authorities, together with NPDES State authorities, to
locate these violations, and to determine their causes.
Appropriate remedies and penalties will be sought for CSOs during
dry weather.  EPA will provide NPDES authorities more specific
guidance on this enforcement initiative separately.

     C.   Enforcement of Wet Weather CSO Requirements

     Under the CWA, EPA can use several enforcement options to
address permittees with CSOs.  Those options directly applicable
to this Policy are Section 308 Information Requests, Section 309
(a) Administrative Orders, Section 309(g) Administrative Penalty
Orders*, Section 309(b) and (d) Civil Judicial Actions, and
Section 504  Emergency Powers.  NPDES States should use comparable
me;ans.

     NPDES authorities should set priorities for enforcement
based  on environmental impacts or sensitive areas affected by
CSOs.  Permittees that have voluntarily initiated monitoring and
are progressing expeditiously toward appropriate CSO controls
should be given due consideration for  their efforts.

      1.   Enforcement  for  Compliance with Phase I Permits

          Enforcement  for  compliance with Phase-. I permits will
  '•    focus on  requirements to  implement at  least the nine minimum
      cpntrols, and  develop the  long-term CSO control plan leading
      to  compliance  with the requirements of the CWA.  Where
      immediate compliance  with  the Phase I  permit  is  infeasible,
      the NPDES authority should  issue  an enforceable  schedule,  in
      concert with the  Phase I  permit,  requiring compliance with
      the CWA and  imposing  compliance schedules with dates for
      each of the  nine  minimum  controls as soon as  practicable.
      All enforcement  authorities should require compliance with
      the nine  minimum controls no later than January  1,  1997.
      Where the NPDES  authority is issuing an order with a
      compliance  schedule  for  the nine  minimum  controls,  this
      order should also include a schedule  for  development of  the
      long-term CSO control plan.
                                 31

-------
         If a CSO permittee fails to meet the final compliance
    date of the schedule, the NPDES authority should initiate
    appropriate judicial action.

    2.   Enforcement  for Compliance with Phase II Permits

         The main focus for enforcing compliance with Phase II
    permits will be to incorporate the  long-term CSO control
    plan through a civil judicial action, an adl^nis^^Y®
    order, or other enforceable  mechanism requiring compliance
    with the CWA and  imposing a  comPliancevsch^UiLnt  the olan
    appropriate milestone dates  necessary to implement  the plan.

         in general,  a judicial  order  is the appropriate
    mechanism  for  incorporating  the  above Pr°;:is^!j£F *£*?*,.
    II.  Administrative  orders,  however, may ^appropriate  for
    permittees whose  long-term  control  P1^5."^  *akeless  than
    five years to  complete,  and for  minors  that  have  complied
    with the  final  date  of  the  enforceable,  order for  Compliance
    with their Phase  I  permit.   If  necessary,  any of  the nine
    minimum controls  that have  not  been implemented by this  time
     should be  included in the terms  of the  judicial order.

     D. Penalties

     EPA is prepared not to seek civil penalties for past CSO
violations', !f permittees have no di-^H *£g* <** wath*r
and meet the objectives and schedules of this Policy.
No?wi?hstaSdingDthis,  where a permittee has °^erud^a^c£o£
violations for which EPA or the State is taking judicial action,
penalties may be considered as part of that action for the
following:

     1. CSOs during dry weather;

     2  violations of CSO-related requirements in NPDES  permits;
     consent decrees  or court orders which predate this  policy;
     or

     3.  other  CWA violations,
      EPA will not seek penalties for  past  CSO  violations  from
 remittees that fully comply with the Phase  I  permit  or
 SnfSceableorder requiring compliance with  the Phase I permit.
 ?Sr permittees that fail to comply,  EPA will exercise its
 en1o?cement discretion in determining whether  to seek Penalties
 for the time period for which the compliance schedule was
 vTolated    If the milestone dates of the  enforceable schedule
 Ire no? thieved and penalties are sought  P-alties  should be
 calculated from the last milestone date that was met.

      At the time of the judicial settlement  imposing  a compliance
                                 32

-------
the Phase I permit and if the terms of the judicial order are
expeditiously agreed to on consent.  However, stipulated
penalties for violation of the judicial order generally should be
included in the order, consistent with existing Agency policies.
Additional guidance on stipulated penalties concerning long-term
CSO controls and attainment of WQS will be issued.

(Approved by the Office of Management and Budget, under Control
Number 2040-0170)
                               33

-------

-------