&EPA
           United States
           Environmental Protection
           Agency
           Office Of Water
           (4204)
EPA 832-B-96-002
September 1996
Interim Report-Evaluation
Of The Advanced Ecologically
Engineered System (AEES)
"Living Machine"Wastewater
Treatment Technology-
Frederick, MD.

-------

-------
EVALUATION OF ALTERNATIVE WASTEWATER TREATMENT TECHNOLOGIES
    AN INTERIM PROCESS EVALUATION OF THE
              AEES "LIVING MACHINE"
    i  • ,   •   ',    .  ,,.-..   ,••'.-.   .     ''  ....

              FREDERICK COUNTY, MD
                      PREPARED FOR:


           U.S. ENVIRONMENTAL PROTECTION AGENCY
            OFFICE OF WASTEWATER MANAGEMENT.
             . MUNICIPAL TECHNOLOGY BRANCH
                 WASHINGTON, DC 20460
                  Report No. 832-B-96-002
                  Contract No. 68-C2-0102
                 Work Assignment No. 3-18
                     September 1996

-------

-------
        EPA1 s Environmental Technology Verification Program
        / ,-       .       ;   - •  -        \         •        • .      >
 Throughout Its history,  the U.S. Environmental Protection Agency
 (EPA)  has evaluated technologies to determine their effectiveness
 in preventing, controlling,, and cleaning iip pollution.   As a part
 of the Environmental Technology Initiative, EPA is now expanding
 these- efforts by instituting a new program, the Environmental
 Technology Verification 'Program "-- or ETV -- to verify the
 performance of a larger universe of innovative technical
 solutions to problems that threaten human health or the
 environment.  ETV was created to substantially accelerate the -
 entrance  of new environmental technologies into the domestic and
 international marketplace.  It supplies technology buyers and
 developers,  consulting engineers,  states,  and the U.S.  EPA
 Regions with high quality data on the performance of new '  .  •
 technologies to encourage more rapid protection of the ;
 environment with better and less expensive approaches^   EPA will
 utilize the expertise of both public and private partner       .
 "verification organizations," including federal laboratories,
 states/ universities, and private sector facilities,  to design
 efficient processes fpr conducting performance tests of         '
 innovative technologies.v Verification organizations will oversee
 and report verification activities based on testing and quality
 assurance protocols developed with input from all major  ,
-stakeholder/customer groups associated with the technology area.
                          i         ' '    ""     ','-••'
 This interim process evaluation report on the Applied Ecological
 Engineered Systems (AEES)  "Living Machine," prepared, in     ;
 cooperation with EPA's .contractor -- Parsons Engineering Science,
 Inc.  --serves as an' example o~f the type-of independent testing.
 envisioned under the GPA's new ETV Program.  Currently'ETV pilot
.projects  are underway involving the testing; of small- package
 drinking'water systems (EPA has partnered with NSF Int'!.}',
•pollution prevention< and waste treatment systems v(EPA has
 partnered with the State of California),  site characterization
 technologies (EPA has partnered with Sandia and Oak Ridge
 National.Labs.),  and indoor air products (EPA has partnered' with '
 the Research Triangle Institute).   For'further information
 regarding the ETV Program,  contact the Penelope Hansen,  Program
 Coordinator,, at 202/260-2600.         • •           ...

-------
                                   Disclaimer
       The information in this document has been funded wholly, or in part, by the United
States Environmental Protection Agency under Contract 68-C2-0102, Work Assignment
No. 3-18.   Mention  of  trade  names or commercial  products does not constitute an
endorsement or a recommendation for use.

-------
                                Acknowledgments
       Mr. Sherwood Reed, P.E. of Environmental  Engineering Consultants, Norwich, VT
and  Mr. James Salisbury  of  Parsons Engineering  Science,  Iric., Fairfax, VA were the
principal authors of this report.  This work was performed under the direction of Mr. Robert
E.  Lee,  Chief of  the  Municipal  Technology Branch,  and  Mr. Robert  Bastian,  Work
Assignment  Manager,  USEPA  Office  of  Wastewater Enforcement  and  Compliance.
Ms. Lauren Fillmore and Ms. Lisa Allard of  Parsons  Engineering Science, Inc., Fairfax, VA
provided project management  and direction during the study and the preparation of this
report.   Additional project support was provided  by  Mr. Brian Stone,  P.E., Mr. Keith
Kornegay, Mr. Robert Cain, and Mr. Glenn  Pearson  of Parsons  Engineering Science,  Inc.,
Fairfax, VA.
     ^                          .  -                          ^
       The authors wish to thank  Dr. John Todd and Ms. Beth Josephson of Ocean  Arks
International, Falmouth, MA,  and Mr.  Michael  Shaw  and Ms.  Lynne Stuart of Living
Technologies,  Inc., .Burlington, VT for their cooperation  and assistance during this study.
The authors especially wish to thank Mr. Stanley Serfling, Ms. April  Smith,  Ms.  Janette
Emming and Ms. Kerrie Kyde, the Ocean Arks staff  at the Frederick, MD facility, for  their
assistance and patience during the data collection phase of this project.      .
                                            Ill

-------
IV

-------
                                       Foreword
        Providing effective and reliable wastewater treatment in a cost-effective manner is a
 problem facing urbanizing areas across the country.  The Clean Water Act (PL92-500 and
 its more recent amendments) led to the construction of .many new wastewater treatment
 facilities to help control water pollution  from both industrial and municipal sources.  In the
 future^ add-on processes will be needed to upgrade many of these treatment  facilities.  In
 addition,  more facilities  will  be needed to  help deal  with small  volume municipal  point
 sources as well as non-point sources of water pollution  if the water quality objectives of the
 Clean Water Act are ever to be fully realized.

        Many treatment technologies are currently available for use in meeting essentially
 any level of wastewater treatment found to be necessary to meet regulatory requirements—
 including technologies that can effectively and reliably treat  wastewater to meet  drinking
 water quality.  However, many of these currently available technologies are expensive to
 build and operate, require extensive energy resources, and produce large volumes of sludges
 that are also expensive to properly manage.

        In  an  effort to offer, a new  approach to meeting a variety of advanced treatment
 requirements,  "ecological  engineering"  concepts are  being  used to design  wastewater
 treatment systems that incorporate naturally-occurring, complex ecological systems within a
 highly controlled environment.  After working with a number of small pilot-scale facilities
 employing  his early proprietary designs,  generally referred to as  "Solar Aquatics"  {which
 evolved from work with self-contained  aquaculture production systems), Dr.  John Todd,
 President of the non-profit Ocean Arks Ltd., has developed a series of second generation,
 design (non-proprietary) demonstration-scale projects he refers to as "Advanced Ecologically
 Engineered Systems" (AEES)  or "Living  Machines."  To date a  total of $5.75  million  in
 federal funding to support these demonstration-scale "Living  Machine" projects  has been
 provided by Congress'in the form of special add-on appropriations to EPA's budget (in FYs
 '92-'95).   Most of these funds were awarded  through a cooperative agreement  to the
 Massachusetts  Foundation  for  Excellence in  Marine  and  Polymer Sciences, a financial
 supporter of  Dr. Todd's earlier efforts to  develop the original  "Solar Aquatics"  technology,
 toj assist in the design,-construction, operation  and  documentation of results associated
 with the demonstration-scale "Living Machine" projects.

        Dr. Todd promotes his "Advanced. Ecologically Engineered Systems" (AEES)  or
 "Living Machines"  as  a new,  low  cost,  solar powered,  no chemical  use alternative
 wastevyater treatment technology capable of being constructed  in modules as additional
 capacity is needed.  These systems incorporate  many  of the same basic processes (e.g.,
 sedimentation, filtration, clarification, adsorption, nitrification, denitrification, volatilization,
 anaerobic  and aerobic decomposition) utilized in more conventional  advanced biological
treatment systems. Dr. Todd is trying to  simulate these processes as they occur in natural
 biological ecosystems (such as lakes, rivers and wetlands).  He is attempting to encourage
them to operate  at  optimal  rates  under controlled  conditions.    Still, his  ecologically
engineered systems incorporate  variations of well established  treatment technologies such
as anaerobic  bioreactors,  complete > mix aerated tanks, aerobic  fluidized  bed  reactors,
clarifiers, high rarte constructed  Wetlands, and plant-covered  ponds.   However, Dr. Todd
approaches'the design and operation of  his facilities from  an  ecological systems point-of-
view  and  attempts to  incorporate objectives  well  beyond  just  achieving  the  desired
                                              ¥ ,

-------
wastewater treatment  goals into his  projects.    For  example,  Todd  emphasizes  the
importance of snails, freshwater clams and other invertebrates in his "ecological fluid beds,"
as well as utilizing a variety of aquatic and wetland plants throughout his systems.  He also
stresses the value  of his systems as a potential opportunity to produce fish  as well  as
aquatic and wetland horticultural plants to be marketed locally, and for educating the public
about the importance of natural biological systems in  purifying and recycling wastewater.

       Robert Bastian, 24 December 1995

-------
                                            Contents
•   '     .      .'       '    •.-'"           •.-••'.-    •   '    ..''•'        -'   .. •   Page
 Disclaimer.........	..;....	jj
 Acknowledgments	j|j
.Foreword	.......v;........	jv
 Contents	.;....................	.........;	 vi
 List of Figures	:, ...........	'.	.......viii
 List of Tables	.....:x
 List of Abbreviations	xii

    1.      Introduction	1-1
            1.1    Background	....1-1
            1.2   Objectives of the Study	1-2
            1.3   Organization of the Report	.;	1-3

    2,.    ' Description of the AEES Facility in Frederick, MD	2-1
  ;          2.1    Introduction	'.			2-1
            2.2    Anaerobic Bio-reactor..	'.	...2-3
            2.3    Aerated Tanks	'.	:..	,	.....2-3
            2.4    Ecological Fluidized Beds....	....2-4
            2.5    Duckweed Clarifier '.-.	1	....;.	 ..2-5
            2.6    High-rate Marsh	„	2-5
    3.      Flow Monitoring......	3-1
            3.1    Introduction	.............	3-1
           .3.2    Influent Flow Monitoring	<	.3-1
            3.3    Effluent  Flow Monitoring	......3-1
   4.      Wastewater.arid Residuals Sampling	;......	4-1
            4.1    Introduction......	:.....	,	...	..4-1
            4.2    Sampling Locations.....	4-1
            4.3    Sampling Methods.........	4-2
   5.       Tracer Study ...'................	5-1
         -   5.1'   Introduction	5-1
            5.2    Test Locations	:..;	.„	......5-1
            5.3    Tracer Study Methods.....	...	,...,5-2
   6.       Analytical Procedures	6-1
            6.1     Introduction	6-1
            6.2    Field Analyses	..............6-1
            6.3    Laboratory Analyses	6-1
   7.       Quality Assurance and Quality Control	..7-1
            7.1     Introduction..	,...,....	 ........7-1
            7,2   QA/QC Program Implementation and Procedures	....7-1
           -7.3   QA/QC Program Results	...........7-2
            7.4   Conclusion			..7-5

-------
                                                                              Page
    8.      Flow Data
           8.1   Introduction	.-	8-1
           8.2  Influent Flows	8-1
           8.3  Effluent Flows	8-1
    9.      System Performance	9-1
           9.1   Introduction	9-1
           9.2  Wastewater Characteristics	....:'.	9-1
           9.3  Treatment Efficiencies..	9-8
           9.4  Residuals Characteristics	9-11
           9.5   Operations and  Maintenance During the Process Evaluation	9-20
    10.     Hydraulic Detention Times	10-1
           10.1  Introduction	.:.......	*.... 10-1
           10.2  Tracer Study Results	;	10-1
           10.3  Calculation of Hydraulic Detention Times	10-2
    11.     Comparison of Study Data with Ocean Arks' Data...	,	11-1
           11.1  Introduction	11-1
           11.2  Comparison of Data Sets	11-2
    12.     Investigation of the System Without Plants	12-1
           12.1  introduction	12-1
           12.2  Wastewater  Sampling	;..'.	;	...12-1
           12.3  Analytical Procedures and QA/QC	.12-1
        -   12.4  Process Performance Without Plants...	12-1
           12.5  Comparison to Process  Performance With Plants.	12-2

    13.     Evaluation of the AEES Facility in Frederick, MD	....	.13-1
           13.1  Introduction	,	,	.,,	...13-1
           13.2  Process Performance	13-1
           13.3  Process Residuals,	'.	;	...13-8
           13.4  Cost Comparisons	13-9
           13.5  USEPA- Ocean Arks Data Comparison..	...-.	13-14
           13.6  Role of Plants in the AEES Process	13-17
   14.    Conclusions and Recommendations	14-1
           14.1  Conclusions	...			....14-1
           14.2  Recommendations ...<.	..<	14-4
   15.    References	'.	15-1

APPENDICES
   A.     Quality Assurance Project Plan
   B.     Raw Data: Flow Monitoring
   C.     Raw Data: Water Quality and  Residuals
   D.     Raw Data: Tracer Study
   E.     Raw Data: Water Quality (System Without Plants)
   F.     Cost Estimates for Conventional Treatment Systems
   G.     Cost Estimates for the AEES
                                             VU1

-------
                                 LIST OF FIGURES
 Figure 2-1     Process Flow Diagram for the Frederick, MD AEES Living Machine ...2-2

 Figure 4-1     Wastewater and Residuals Sampling Locations ...... . ..... ....... ______ ......4-2
 Figure 5-1     Tracer Study Sampling Locations ............ . ...... ........ . ...... ........ ....... 5-2

 Figure 9-1     Eleven Week Performance Evaluation - Chemical Oxygen Demand ....9-4

 Figure 9-2     Eleven Week Performance Evaluation - Biochemical
              .Oxygen Demand.. ........... ....... ............... ........... ... ..... ........ ...:.... ..9-5

 Figure 9-3     Eleven Week Performance Evaluation - Suspended Solids ...... . ......... 9-6

 Figure 9-4     Eleven Week Performance Evaluation - TKN, Ammonia and Nitrate ...9-7

 Figure 9-5     Eleven Week Performance Evaluation - Total Phosphorus...... ...... .....9-9

 Figure 9-6  -  Eleven Week Performance Evaluation - Dissolved Oxygen and pH...9-10
 Figure 9-7     Contributions of Process Components -  Total COD Removal ..... ..... 9-14

 Figure 9-8     Contributions of Process Components -  Total Biochemical
              Oxygen Demand Removal .... ....... .. ______ .'; ...... ... ......... ... ....... . ........ 9-14

 Figure 9-9     Contributions of Process Components -  Total Suspended Solids
              Removal ........... . ..... ..... ....... ........ ........ . ..... .. ...... . ................. ....9-15

 Figure 9-10   Contributions of Process Components -  Total Kjeldahl Nitrogen
              Removal.... ...... ..... ............. ..... ...... ...... ......... .-.' ....................... ..9-15

 Figure 9-1 1    Contributions of Process Components -  Ammonia Removal. ........... 9-16
 Figure 9-12   Contributions of Process Components -  Total Phosphorus
              Removal ............... ...... ............ . ......... . ..... ...:................ ...... . ..... 9-16 '

 Figure 10-1   Tracer Study to Determine HDTs ..... . ..... . ..... .... ....... .... ...... .......... 10-1
 Figure 12-1   Comparison of System Treatment With and Without Plants
             Parameter: Total Chemical Oxygen Demand. ........ ....... ...... . ....... ..12-5
 Figure 12-2  Comparison of System Treatment With and Without Plants
             Parameter. Soluble Chemical Oxygen Demand ......... ........... ........12-6
 Figure 1 2-3  Cpmparison of System Treatment With and Without Plants
             Parameter. Total Biochemical Oxygen Demand... ........ .. ........ . ...... 12-7
 Figure 12-4  Comparison of System Treatment With and Without Plants
             Parameter: Soluble Biochemical Oxygen  Demand. ... ............... . _______ 1 2-8
 Figure 12-5   Comparison of System Treatment With and Without Plants
             Parameter: Total Suspended So/ids.............. ......... ....... ...... ......... 12-9
 Figure 12-6   Comparison of System Treatment With and Without Plants
             Parameter: Volatile Suspended Solids ......... , ................ ............ 12-10
Figure 12-7   Comparison of System Treatment With and Without Plants
             Parameter: Total Kjeldahl Nitrogen (TKN) ........ ,. ............. ..." ....... .. 1 2-1 1
                                          IX

-------
                           LIST OF FIGURES (continued)
                                                                        Page

Figure 12-8   Comparison of System Treatment With and Without Plants
             Parameter: Ammonia	.„...	12-12
Figure 12-9   Comparison of System Treatment With and Without Plants
             Parameter: Nitrate	:	 12-13
Figure 12-10  Comparison of System Treatment With and Without Plants
             Parameter: Phosphorus	12-14
Figure 12-11  Comparison of System Treatment With and Without Plants
             Parameter: pH	.	 12-15
Figure 12-12  Comparison of System Treatment With and Without Plants
             Parameter: Dissolved Oxygen	12-16

-------
                                     LIST OF TABLES

      • •      . ~~ .  ,        -'"'••.   •    •    .     .'•-'•   • • '    ''   '          Pa9e
  Table 2.1     ; Water Quality Goals for the AEES Facility	...............	2-1
  Table 4.1     Wastewater Sampling Locations	,	'.	..-	..4-1
  Table 5.1     Tracer Study Sampling Locations.....	5-1
 , Table 5.2     Calculated HOT and Sample Times for Tracer Study	5-3
  Table 6.1     Summary of Laboratory Analyses.	6-2
  Table 7.1     RPDs and PRRs for Analyzed Samples........	'..'.	I..................7-3
  Table 7*.2     Study Completeness..	...7-4
  Table 8.1     Mean Daily Wastewater Flows into TrainB.....	.8-2
  Table 9.1     Water Quality Summary for AEES Facility	.....9-3
  Table 9.2     Pollutant Treatment Efficiencies for AEES Facility..,.:.....	........9-12
  Table 9.3     Pollutant Removal Contributions for AEES Facility	....9-13
  Table 9.4     Sludge Data Summary......	..i	9-18
       ' •   •      * .                      .       ''•••-         ,.'•           ' '%  -  '
  Table 9.5     Plant Data Summary,	...9-19
  Table 9.6     Weekly Chemical/Bacteria Additions to Train B	 9-20
  Table 9.7     Weekly Sludge Removals	.9-21
  Table 9.8     Weekly Plant Removals from Train B	9-22
  Table 9.9     Abnormal Operations and Modifications that Occurred During
               the Study	 9-24
  Table 10.1    Actual and theoretical HDTs for the AEES	\10-3
  Table 1O.2    Percentage Lithium Recoveries for the Tracer Study	10-4
  Table 11.1    T-test Results for Total Chemical Oxygen Demand	 11-2
  Table 11.2    T-test Results for Total Suspended Solids.	,..	...... 11-2
  Table 11.3    T-test Results for Volatile Suspended Solids	........11-2
  Table 11.4    T-test Results for Total Kjeldahl Nitrogen	...11-3
  Table 11.5    T-test Results for Ammonia.........	,	 11-3
  Table 11.6    T-test Results for Nitrate.......!	11-3
, Table 11.7    T-test Results for Total Phosphorus..	....11-4
  Table 11.8    Descriptive  Statistics for Total Chemical Oxygen Demand	;..... 11-5
  Table 11.9    Descriptive Statistics for Total'Suspended Solids	 1.1-5
               ^     - ' "    r   .  ', - L '      '          .                      '    .    -   .
 Table 11.10  Descriptive  Statistics for Volatile Suspended Solids	11-6

-------
                            LIST OF TABLES (continued)

                                                                          Page
 Table 11.11   Descriptive Statistics for Total Kjeldahl Nitrogen	11-6
 Table 11.12   Descriptive Statistics for Ammonia	 11-7
 Table 11.13   Descriptive Statistics for Nitrate	11-7
 Table 11.14   Descriptive Statistics for Total Phosphorus	11-8
 Table 12.1    Water Quality Summary for AEES Facility...	12-3
 Table 12.2    Pollutant Treatment Efficiencies for AEES Facility	12-4
 Table 13.1    Performance of the Frederick AEES During the Study Period	13-2
 Table 13.2   AEES Process, Capital Costs	,	13-11
 Table 13.3   Annual O&M Costs for the AEES System	13-12
 Table 13.4   AEES System, Present Worth and total Annual Costs	13-13
 Table 13.5   Capital and O&M Costs for the 40,000 and 80,000 gpd
             Alternatives	.-	 13-15
Table 13.6   Capital and O&M Costs for the 1,000,000 gpd Alternatives	13-16
Table 13.7   Present Worth Comparison, AEES and Conventional Systems	13-17
                                         31

-------
                             LIST OF ABBREVIATIONS
AGES      Advanced Ecologically Engineered System           ,
BOD,      Biochemical Oxygen Demand
COD      Chemical Oxygen Demand                            '
DO        Dissolved Oxygen
EEC       Environmental Engineering Consultants
EQ        Exceptional Quality
gpd       gallons per day
HDTs      Hydraulic Detention Times
kg         kilograms
LD         Laboratory Director                  ,
mgd       million gallons per day
MFEMPS   Massachusetts. Foundation for Excellence in Marine and Polymer Sciences
mg/kg     milligrams per kilogram
.mg/L      milligrams per liter
MLSS      Mixed Liquor  Suspended Solids
NH4       Ammonia
NIST    .  National Institute of Standards in Technology
NO?       Nitrate '
NPDES     National Pollutant Discharge Elimination System
OAI -      Ocean Arks International
O&M      Operation and Maintenance     "'/•    ;
Parsons ES Parsons Engineering Science, Inc.
PRR       Percent Recovery Range      ".'  '••;•".'•
QAC       Quality Assurance Cpordinator
QAM      Quality Assurance Manager
QAPjP     Quality Assurance Project Plan
QA/QC     Quality Assurance/Quality Control
RPD       Relative Percent Difference
SF   ,     Subsurface Flow
SM        Standards Methods
TKN       Total Kjeldahl  Nitrogen
TN      ,   Total Nitrogen                                        •  •  ,.       ,
TP         Total Phosphorus            ,
TSS       Total Suspended Solids
USEPA     United States  Environmental Protection Agency
VSS       Volatile Suspended Solids
WWTP     Wastewater Treatment Plant
                                         \m

-------

-------
                                      Section 1
                                    Introduction
 1.1  Background

        The Advanced Ecologically Engineered System ,(AEES) in Frederick County, MD is
 one of several  related, projects in the United States intended to provide Water  quality
 improvements for a variety of water sources. The AEES technology is also called a  "Living
 Machine" because of the ecologically-based components in  the treatment process.  The
 system was conceived by Dr John Todd, the President of Ocean Arks International {OAI}, a
 non-profit institution based in Falmouth, MA.

        The other AEES demonstration facilities  are located in  South Burlington, VT, San
 Francisco,  CA,  and  near Harwich, MA.  The'Frederick facility is intended  to provide
 advanced levels of  treatment  for  untreated raw  sewage.   The  Burlington pr.oje.ct  uses
 essentially the same technology, and has.the same purpose as Frederick, but is designed to
 operate at a higher flow rate and in a colder climate.  The project in Harwich,  MA  uses a
 floating raft incorporating a portion of the AEES technology to provide in-situ water  quality
 improvements in lakes and ponds.  The project in San  Francisco  also uses part of the AEES
 technology to provide final high fiow rate polishing for treated  secondary effluent; the intent
 is to produce a water quality which would allow unrestricted  irrigation reuse of the treated
 water in California. This report describes the evaluation of performance of the AEES  facility
 in Frederick County, MD during the period between the end of February 1995 and late June
 1995.   The original  proposal to the US  Environmental Protection Agency (USEPA)  stated
 that the purpose  of the demonstration facilities was to: "(Dtest the efficacy  of using
 Advanced Ecologically Engineered Systems under the particular climate conditions prevailing
 in the specific areas;  (2) test the ability of the'systems, and  individual components  within
 the system,  to "improve water quality in  accordance with  established  parameters;  and
 (3) determine the costs of operating the system under given conditions and during specified'
 time periods". The proposal further stated that the purpose of the demonstration facilities
 was to  enable operators, water resources officials and community users to understand the
 dynamics of natural systems, and to become involved in  revitalizing the. water supply  in a
 sustainable way.

       These AEES demonstration projects were funded in part  with special appropriations
from the US Congress, by a grant to the Massachusetts Foundation for Excellence in Marine
 and Polymer Sciences  (MFEMPS) which has  subcontracted out much of the .effort to OAI.
The  demonstration facilities  are staffed  by  OAI personnel and, performance data  are
 routinely collected.  However,  it was agreed that an independent evaluation  by USEPA
 would  be desirable, and funds from the special  appropriations were set-aside  for  that
 purpose. All of the AEES facilities were included in the study but the focus for independent
data collection  was  the system in Frederick County, MD, since it was  expected  to be
operating at "steady state" conditions when the study period commenced.

       The  facility in  Frederick County, MD was constructed  in  1993 and has been  in
operation since that time.  Following  a "ramp-up"  period from January to July 1994, the
facility continued to  move toward "steady state" operations during the latter part of  that
year.  It incorporates the experience gained at previous OAI pilot  systems in Massachusetts,
                                            1-1

-------
                                                                            Section 1
 Vermont and Rhode Island, and represents  a "second generation" design,   this  "Living
 Machine"  technology  is intended to clean wastewater to advanced treatment standards
 using "natural, solar-powered, greenhouse-based technology without the use of chemicals".
 A related but technically distinct concept called "Solar Aquatics" was developed by OAI and
 also  utilizes  a greenhouse  and contained treatment elements also claimed to  be based  on
 solar energy. Although the "Solar Aquatics" technology  is sometimes confused with the
 "Living Machine", the former is now marketed by another firm which holds the exclusive
 rights to this technology. The "Living Machine" system in  Frederick County,  MD, is located
 adjacent to the Ballenger Creek wastewater treatment plant (WWTP) and draws wastewater
 from Ballenger Creek after screening and  degritting for treatment by the AEES process.
                                             !           '
        Parsons  Engineering  Science,  Inc. (Parsons ES) was  selected  by USEPA,  under
 Contract Number  68-C2-0102, to perform this independent evaluation.  Under the same
 contract, Mr. Sherwood Reed of Environmental  Engineering  Consultants  (EEC), Norwich,
 VT, was retained as the technical director of this effort.

 1.2 Objectives of the Study

        The basic  objective of this effort is  to provide an independent evaluation  of the
 AEES "Living Machine" technologies which have.been built and are operated  with federal
 funding  in  Maryland,  California, Vermont,  and Massachusetts.    "Natural" treatment
 processes  based on solar energy inputs and  with a minimal of mechanical  equipment and
 conventional  energy sources may  offer  considerable advantages  for highly effective
 treatment  at relatively  low costs.    Positive  results from  this  independent evaluation
 sponsored  and  published  by  the   USEPA  may then serve to  help provide  a  better
 understanding of these technologies and their  potential use  in the United States.
                                                                                   i
       The major objectives of this study were to:

 •      Evaluate the performance of the  individual treatment components'-and the overall
       AEES process  through monitoring  of flow, characterization  of wastewater and
       residuals,  and determination of hydraulic detention times via tracer studies.  All  of
       this work was  to be performed at the  AEES facility in.Frederick County, MD. by.
       Parsons ES.

 •      Compare the capital costs and operation and maintenance (O&M) costs of the AEES
       process with equivalent conventional wastewater treatment  tephnologies.    This
       comparison would be performed  for flow  rates of  40,000,80,000 and 1,000^000
       gallons per day (gpd).  AEES  costs  would be provided by the designers of the
       "Living  Machine" whereas   conventional  WWTP  costs  would be prepared  by
       Parsons ES;

•      Carry out a statistical comparison  of the water quality data generated by this study
       to that produced by OAI, both from their on-site laboratory and their certified testing
       laboratory (at Ballenger Creek WWTP).  The purpose of this exercise was to validate
       the OAI procedures and results, thereby reducing the  requirement for independent
       testing in future evaluations of this type.               •

•      Evaluate the performance of the  "Living Machine" with and without plants  in the
       treatment units in order to quantify and document the contribution  of  the floating
       macrophyte plant species to the AEES  wastewater treatment process.

       The original intent was to collect independent  water quality data over an 8 week
period while the Frederick AEES was operated at steady state conditions. This part of the
study was then extended, resulting in an  assessment of 11 weeks' duration.  The study to
                                            1-2

-------
                                                                             Section 1
 evaluate the roje of the .plants in treatment was then  added, which meant that the total
.duration of  the sampling  effort  was  14 weeks.  The  sampling  started  the week  of
 February 28, 1995 but was not continuous thereafter and the study period actually,ended
 on June 23, 1995.

        The Frederick facility  contains  three sets of  parallel  units  (trains)  inside the
 protective greenhouse.  Flow to two of these trains (A & B) was maintained as closely  as
 possible to steady state during the study period. The sampling effort inside the greenhouse
 focused on just one of the trains'(Train B), considering it to be representative of the  overall
 system performance.

 1.3  Organization of the Report       .

        This report contains 1.4 sections,  a list of references, and  appendices.   The
 appendices contain all of the data collected at the Frederick AEES facility during the study
 period, the quality assurance project plan and the detailed cost estimates prepared for the
 AEES  process  and for the conventional alternatives.   Section 2 describes the  physical
 components at the Frederick facility while Sections  3 to 7 describe the data collection and
 monitoring procedures, and the quality assurance/quality control procedures used.    .

        Section 8 details the flow data  collected during the study.  Sections 9, 10, 11, and
 12 discuss water quality performance, hydraulic detention times in system components,
comparison  of independent data  to  OAI  data,  and  the evaluation  of the  treatment
contribution from the plants.

       Section 13" provide  the  cost  data for the  AEES  process  and  the conventional
alternatives, and evaluates the capabilities of the AEES process based on the data collected
during  the  period  of the  USEPA  study.    Section 14 presents  the  conclusions and
recommendations drawn from this study.
                                            1-3

-------

-------
                                      Section 2
                 Description of the AEES Facility in Frederick, MD
 2.1  Introduction

        The AEES facility in Frederick Co., MD is designed to treat 40,000 gpd of screened
 and degritted sewage.   A schematic of the  process, prepared by the system designer, is
 shown  on Figure 2-1 {the detention times given  on Figure  2-1  are preliminary estimates).
 All of the components, except the anaerobic bio-reactor are housed in a greenhouse with
 plastic  glazing (Nexus  design  steel frame,  Serac glazing).   The  anaerobic  bio-reactor is
 outside the greenhouse and is partially buried with an exposed  cover.  The  original water
 quality goafs for this system, when operated-at 40,000 gpd,  are summarized in Table 2.1.

                   Table 2.1  Water Quality Goals for the AEES Facility
           Water Quality Parameter
Goal for AEES Facility
           5-day Biochemical Oxygen Demand (BOD5)

           Total Suspended Solids (TSS)

           Ammonia (NH3/NH4)

           Nitrate (NO3)

           Total Nitrogen (TN)

           Total Phosphorus (TP)
      < 10 mg/l

    ,  < 10 mg/l

      <  1 mg/l

      <  5 mg/l

      < 10 mg/l

      <  3 mg/l
       The system is located adjacent to the Ballenger Creek Sewage Treatment Facility;
the influent for the AEES is taken after the screening and degritting units at the  Ballenger
plant.  Since the AEES system is a demonstration project all effluent and wasted sludges
are returned to the Ballenger facility.  The greenhouse, structure encloses three sets of the
components shown on Figure 2-1. Two of these process "trains" are used to demonstrate
the capability to treat the design flow rate under steady state conditions. The third train is
used for testing  and experimentation but typically receives one  third of the 40,000 gpd
design flow..  The nomenclature  used to identify the treatment  units in this process,  as
shown on Figure 2-1, was developed by the system designers.      ,

      /The conceptual design and  structural  details  of  the  anaerobic bio-reactor were
developed  by Sunwater Systems, Inc. located in Solario Beach, CA.  The "Living Machine"
concept, and the conceptual design  of the AEES facilities were developed by Ocean  Arks
International, a non-profit institute located in Falmouth, MA.  The engineering and structural
details for the greenhouse and "enclosed components were provided by Living Technologies,
Inc., located in Burlington, VT.   The computer controls for  the greenhouse units were
provided by Q Com Environmental Control in Irvine, CA.
                                            2-1

-------
                                                                                                Section 2
         A demaratiuoa
             monflj-uioo project 
-------
                                                                             Section 2
 2.2 Anaerobic Bio-Reactor

        The first treatment unit at the  Frederick facility is  the partially buried anaerobic
 reactor. It has a concrete floor and concrete block side walls and is lined with 30 mm high
 density polyethylene.  The floating plastic membrane liner contains a layer of insulation for
 thermal protection.  The reactor is 15 ft wide and 28 ft long and maintains a 9 ft water
 depth.  As shown on Figure  2.1, an internal dam about 6ft tall contains a permanent
 sludge blanket.  The untreated  wastewater enters this zone via diffuser pipes on the bottom
 of the tank and then  flows upward through the sludge blanket and then into the second
 compartment.  A unique  aspect of the second compartment are strips, of polypropylene
 mesh netting  suspended  from  the reactor cover and spanning the full width of the tank.
 This mesh assists in trapping and settling solids and provides significant surface area for
 colonization by attached  growth microorganisms.   The  settled sludge in this compartment
 undergoes^some anaerobic digestion.   Sludge  is  removed  from this  compartment on a
 weekly schedule via perforated pipes on the bottom of the reactor.  At  a flow rate of
 37,000 gpd, the theoretical fluid detention time  is 18% hours  in this  reactor.  ^Untreated
 wastewater is pumped, at a constant rate, from  the Ballenger WWTP screening and grit
 removal unit to the bio-reactor.  A depth of about two feet of settled sludge from the
 Ballenger  facility was added to the first compartment at start-up to  serve as the initial
 sludge blanket.

       In order to control odors in the greenhouse and on the site, the effluent from this
 reactor is piped to small covered aerated tanks with a detention time of about 20 minutes
 at design  flow.  The effluent leaving this unit  is aerobic  and odor free  and ready for
 treatment in the greenhouse.  The exhaust gasses  from this  aeration unit are routed to an
 underground earth filter for odor control.

      .The basic  purpose  of this  anaerobic  reactor  is  to  signifipantly reduce  the
 concentrations of BOD5  and  solids  (TSS) in the  wastewater  prior to treatment in the
 greenhouse.  Supplemental heat is not added to this reactor so a relatively warm climate is
 required for successful sludge digestion. The designers have replaced this anaerobic reactor
 with an aerated  aerobic  unit in the  "Living Machine"  now  under construction in  South
 Burlington, VT.

 2.3 Aerated Tanks

       As  shown on Figure 2.1, the aerated effluent from  the anaerobic bio-reactor flows
to the first of two aerated tanks in series.  Each tank is 10 ft  in diameter and  9 ft deep, the
top 4 ft of the tank is above the concrete greenhouse floor the remainder is below ground.
The  cylindrical tank walls are corrugated  steel, of the type commonly used for culvert pipe.
The  interior of the  tank is  lined with  a  20 mm  plastic  membrane container to insure
complete fluid retention.  Both  aeratjon  tanks arejoperated  in the complete-mix  aeration
mode to keep all solids in suspension and to insure rapid circulation and contact with the
submerged roots of the plants floating on.the water surface of these tanks.   Wifley Weber
circular diffusers are used as the aeration source in these tanks, and other process units.
Air  is supplied for the entire-system with three Roots blowers (1-1 hp, 1-1.5 hp, 1-2 hp)
which operate continuously.          '

       The plants used on these tanks are floating macrophytes; the first tank usually is
covered  with water  hyacinth  (Eictihornia  crassipes  ).,  the  second  with  pennywort
(Hydrdcotyle umbef/ata).  About 1 hour per week of operator time is required for the care of
these plants.  Any plant material removed from these tanks is composted.  The theoretical
detention time in each tank  is 8.5 hr at design  flow (13,300  gpd/train).  Table 10.1 in
Section 10 compares theoretical to actual detention times in all of the process units.
                                            2-3

-------
                                                                             Section 2
        A variety of biological, bacterial, and mineral additives are applied to the wastewater
 prior to the aeration tanks to enhance treatment  responses and maintain health of the
 plants.   Bacterial additions  include Bactapure N  for  nitrification,  and  XL to  assist in
 breakdown of grease and sludges; mineral  additions consist of Mar/ah powder intended to
 improve mineral  content  and health of plants;  the  biological  additive is  Kelp meal to
 supplement the potassium content in the wastewater.  Typical dosages of these materials
 can be found in Table 9.6 in Section 9 of this report.

        It is the basic purpose of these  aeration tanks to reduce the  dissolved wastewater
 BOD5 to low levels and to commence the nitrification of ammonia. The roots of the floating
 plants are intended to serve as  a substrate for the support  of attached growth nitrifying
 organisms.

        In the original design and layout of units in the Frederick  greenhouse the  flow from
 the  second aeration tank passed directly to the  next treatment component which is  the
 "ecological fluidized beds".  Sludge accumulation  in these  beds required  very frequent
 cleaning so a small  clarifier was added  to the process train after the  second  aeration tank,
 this is shown on Figure 2.1.  Most of the sludge removed from this clarifier is wasted to the
 anaerobic bio-reactor; a small percentage is  recycled to the first  aeration tank. The mixed
 liquor suspended solids in these tanks was typically  less than 150 mg/L, in a complete mix
 activated sludge  process the  mixed liquor  solids might  range from 1500 to 4000 mg/L
 depending on the  purpose of the reactor.

 2.4 Ecological Ruidized Beds    ,            ,

        As shown on Figure 2.1, there are  three of these units in the process train.  The
 outer container of these tanks is the same size and constructed of the same materials used
 for the aeration tanks. These units also include an  inner tank which contains the pumice
 gravel which is the  media used in these  beds.  Flow enters in the annular space between .
 the inner and outer tanks  and is lifted by air lift pipes to the top of the inner ring containing
 the pumice media.  The bottom of the inner tank  is  not sealed so 'the down flowing liquid
 returns to the outer annular space and is again circulated onto  the top of the pumice gravel.
 The  air lifts  not only move the  liquid  but  the  air bubbles provide the  oxygen source to
 maintain aerobic conditions in the circulating  liquid.

        The depth of  pumice in  the  inner tank is about 8ft.  The  pumice gravel has a
 median size of about 0.5  inch. This  size media was selected to  provide a high surface to
volume ratio for the attachment of the microbial organisms for effective  nitrification in the
bed.  Pumice was selected as the material  because of it's low density which renders it
nearly buoyant. This feature is critically important to successful operation of the unit.  As
sludge is separated from the fluid stream in the bed the hydraulic capacity in the forward
flow  direction  is  impeded,  if accumulation were  allowed to continue  the  bed would
eventually  become  completely clogged.   To  correct this potential  problem  the unit  is
designed with additional aeration diffusers beneath the  pumice bed.   When these aerators
are on the whole inner tank acts as  an upflow airlift so the flow direction is reversed; the
aeration also "fluidizes" the pumice bed  and suspends the buoyant  pumice gravel in the
liquid. This also releases  the trapped sludge which is washed over into,  and settles at the
bottom of, the outer annular space.  Most  of this sludge is  removed manually  from  this
space and is also returned to the anaerobic reactor.

       The choice of "ecological fluidized  bed" as the name for this  unit is somewhat
misleading.  It is normal practice to define the function of a treatment unit while  operating
in the forward flow direction.  In this case, when the bed is in the treatment mode the
                                             2-4

-------
                                                                              Section 2
 pumice is not fluidized and the bed acts as a dqwnflow, coarse media, filter unit.  It is only
 during the backwash cleaning operations that'the pumice is fluidized.                  ,

         The three  Ecological  Fluidized Beds were originally designed and operated as three
 aerobic units in  series.   Operational  experience soon  indicated  that  nitrification  was
 essentially complete after the second unit.  The third tank was therefore converted to an
 anoxic  unit  to  provide  additional capacity  for denitrification.   This  was accomplished
 without major physical changes in the unit.  The airlift delivery pipes were turned off and a
 1.5 hp  recirculating  pump located at the top of the central tank.  This induces an upflow
 direction in the pumice bed and the pump delivered the fluid to the bottom of the annular
 space.  The lack of aeration and the resulting low oxygen levels created anoxic conditions in
 the pumice  creating  an environment suitable  for denitrif ication.  This modified unit is still
 backwashed  in the same manner described previously.

:         Denitrification requires a carbon source for the reaction to function and the available
 carbon  (BOD5) in the wastewater is very low at this point and,insufficient.  As a result it is
 necessary to add a carbon .source to the water prior to the denitrification process.  A variety
 of carbon sources were fried including sugar and  acetate but methanol  has become the
 standard.  Table 9.6 in Section 9 summarizes the carbon source additions during the  EPA
 study period.                ;

         The  theoretical detention time  in  each of these-units is about 7 hours  at design
 flow.   Table 10.1  in Section 1  compares theoretical  detention times.to actual times as
 measured  during the EPA study period.   It is the basic purpose of the first two units to
 essentially complete removal of BOD5 and nitrification of the ammonia contained  in the
 wastewater.  The'third unit is now used for denitrification of that ammonia.

        The  water surface of the annular space  in these tanks  is used  to support the
 hydroponic growth  of tree  seedlings  and  other plants  suspended in  pots  around  the
 perimeter  of the tank.  The plants do remove some nutrients  and micronutrients from the
 water but their  contribution  to the treatment function of the  system is  believed  to be
 minimal. However, these plants can provide a beneficial return since they can be sold.  It is
 estimated  that an  annual  revenue of about $1,200 could be  achieved from sale of these
 plants during the spring/summer gardening season in Maryland.   _

 2.5 Duckweed Clarifier                       ,

        The three Ecological Fluidized Beds are followed by a hopper bottomed clarifier for
 final separation pf  most of the remaining sludge prior to the final marsh component  in the
 system.  The tank for this  clarifier and  the  materials used  are the same as  previously
 described for the aeration tanks.  The settled sludge is periodically removed  from this tank
 and discharged to  the Ballenger Creek WWTP.  The water 'surface on this tank is covered
 with duckweed (Lemna spf)  and other small floating plants.   It is not believed that these
 plants contribute significantly to treatment due to the  very  small root  structure.   The
 theoretical detention  time in this final clarifier is calculated as 8.5  hours, at design flow.

 2.6 High-rate Marsh

        The High-rate Marsh  is the final component in the  process  train.   It is  similar in
 concept to the subsurface flow (SF) constructed wetland concept used for treatment of
 municipal and domestic wastewaters. This High-rate Marsh consists of a lined excavation
 in the floor of. the greenhouse filled with clean,selected gravel, and planted at the top with a
 variety of, plant  species.   The rectangular bed  is  about  13 ft  wide and 30 ft  long  and
 contains a 3% ft depth of gravel. The top foot of gravel is small 3/8" stone, the remaining
                                             2-5

-------
                                                                             Section 2
 depth is composed of 13&" stone. The theoretical detention time, at design flow in this unit
 is about 9 hours.

      „  This  high rate marsh is operated  and maintained differently than the conventional
 subsurface flow wetland. In the latter case, the depth of the SF wetland bed typically does
 not exceed 2 ft to allow the roots of the vegetation to interact with all of the wastewater
 flowing through the bed. Deeply rooted  emergent vegetation such  as bulrush (Scirpus) or
 common reeds (Phragmites) are typically used.  This is necessary in the SF system since the
 plant  roots  supply  the oxygen which is necessary  for  nitrification  of the  wastewater
 ammonia.    The  plant  litter   is allowed  to accumulate on  top  of  the  bed and  the
 decomposition  of  this material provides  some  of  the  carbon source   needed  for
 denitrification. The SF wetland bed  is sized to accomplish the  limiting treatment response,
 typically either nitrification or denitrification.  One of these SF wetland units, depending on
 only the plant litter as a carbon source for denitrification would have to be much larger than
 the "Living Machine" High-rate  Marsh.

       The  "Living  Machine"  high  rate  marsh  does  not have  to provide significant
 nitrification since  the ecological fluidized beds are intended  for  that  purpose.    Since
 methanol is used as a carbon source the plant litter is not allowed to accumulate on top of
 the bed. Since deeply rooted plants  are not really needed a variety of plants can be grown
 for aesthetic and commercial horticultural  purposes.  These plant roots are in contact with-
 the flowing wastewater and certainly provide some uptake of nutrients and micro nutrients,
 but they are not  one of the  major components responsible for treatment  as in  the  SF
 concept.   In essence this final high rate  marsh  acts as a polishing filter with the upper
 surface maintained as  a commercial horticultural operation.   Seedlings  are  planted and
 raised to marketable size and then replaced with new plant material. It is estimated that a
 revenue of about $3,600 per year could be achieved from sale of these plants during the
 summer gardening  season in Maryland.

       Based on the  performance data documented in Section 9 this high rate marsh unit,
 as operated in Frederick County, provides a relatively small improvement in wastewater and
therefore, may not be an essential treatment component in the  "Living Machine" process.
A marsh with a larger area might contribute more significantly to treatment but would result
in a very high cost for the enclosing greenhouse structure.  In most climates it should be
possible to locate  a larger marsh outside  the greenhouse  but then  it could not serve for
commercial   horticultural  purposes.    The  80,000 gpd   "Living  Machine"  now   under
construction in South Burlington, VT does not include a marsh component.
                                            2-6

-------
                                      Section 3


                                  Flow Monitoring
 3.1  Introduction
        Influent and effluent flow monitoring was carried out over the duration of the study.
.This monitoring was necessary to  provide data concerning the quantities of wastewater
treated during the study period, and  to  assist with the calculation of system  hydraulic;
detention times (Sections).  The  following section  describes where and how this  flow
monitoring was performed.

3.2  Influent Flow Monitoring
               '               . -.,         • •   .    •''-'.  \      .           '  •-.
        Influent flow monitoring was achieved using a flow meter installed by the field study
team.   This meter was a doppler  flow meter, manufactured  by  Controllotron,  and  was
installed on the influent pipe to the first Train B Aerated Tank. The flow meter measured
flow rates and totalized flows, and downloaded its data to a  local computer.  This meter
monitored  the average daily  influent  flows  into Train B which was the  treatment train
investigated in this study.
        "             -                ' '                ,  '                   f
3.3  Effluent Flow Monitoring

        Effluent flow  monitoring was performed using the existing OAI  flow  meter at  the
discharge pipe of the Train B High-rate Marsh.  This flow meter was a tee-mount, impellor
flow sensor manufactured by Great Lakes Flow Meters.  The .flow meter measured mean
flow rates and downloaded its data to a local computer.   Using this meter,  it would be
possible to calculate the average daily effluent flows from Train B of the AEES Facility:
                                            3-1

-------

-------
                                       Section 4
                        Wastewater and Residuals Sampling
4.1  Introduction                                                  :             ,
             /•     r      '     • ,       •            " ••"-'""             •          .  f

        This section describes the water quality and residuals sampling protocol that was
followed  during  the evaluation  of the AEES Facility.   Composite and  grab wastewater
samples were collected for the system  performance assessment.  Samples of the process
residuals  (sludge  and plants) were also collected  during the study.   Information  on the
sampling locations and methods is provided below.

4.2  Sampling Locations
                                  •x     ' •               i '    . >

4.2.1   Wastewater "Sampling Locations

        During the study, wastewater samples were taken from six locations throughout the
AEES Facility. The study examined Train B of the treatment system.  These sampling points
are listed in Table 4.1  and displayed graphically in Figure 4-1.

                         Table 4.1     Wastewater Sampling Locations
              Sample Point
Description of Location
                   W1
Raw influent into the Anaerobic Bio-reactor,
after primary screening
W2
W3
W4
, W5(1) '
W6
Anaerobic Bio-reactor effluent -
Effluent from the 2nd Aerated Tank
Effluent from the 3rd Ecological Fluidized Bed
Effluent from the 1 st Ecological Fluidized Bed
Effluent from the High-rate, Marsh
             (1)  The position of sampling location ,W5 was changed after the first
                 week of the study.  Originally, sample point W5 was located at the
              .  outlet of the Duckweed Clarifier.  However, as noted in the Quality
                 Assurance Project Plan (see Appendix A), little difference existed in
                 water quality between effluent from the 3rd Ecological Fluidized Bed
                 and effluent from the Duckweed Clarifier.  In the second week of the
                 study, this sampling location was moved to sample effluent from the
                 1st Ecological Fluidized Bed, where it remained until the end of the
                 study.    :          .
                                             4-1

-------
                                                                            Section 4
 4,2,2—Residuals Sampling Locations

        Samples of both sludge and plants were collected during the study.  Sludge samples
 were  removed  from the Anaerobic  Bio-reactor  (Sample Location S1) and the clarifier
 following the 2nd Aerated Tank (Sample Location S2).   Plant  samples  were  taken as
 follows: water hyacinth from the 1st Aerated Tank, pennywort from the 2nd Aerated Tank,
 and both duckweed  and azolla from the 2nd  Ecological  Fluidized Bed.   Figure 4-1  also
 summarizes these sampling locations.
          Figure 4-1   Waste water and Residuals Sampling Locations
                                         	^ to Trains A and C

                                          Train B (Sampled Train)
      Raw
     Influent
                  Anaerobic Bio-reactor
         Aerated Tanks
                Clarifier
    Treated
    Effluent
                  High-rate Marsh
Duckweed
 Clarifier
Ecological Fluidized Beds
4.3 Sampling Methods            '

4.3.1   Composite Wastewater Samples

       Time-proportioned,  composite  24-hour  wastewater  samples  were  collected
throughout the study using ISCO  automatic  samplers located at the sampling locations
described in Section 4.2.  The six samplers used for the study were inspected, cleaned, and
calibrated  at the beginning  of the study and,  subsequently, on a  routine basis throughout
the remainder  of the study period.  One  sample was collected from each location every
week for the eleven week duration of the study.

       Before each sampling event, the sampler tubing and  collection container were rinsed
with the wastewater being tested,  and  the  samplers  were filled  with ice for  sample
                                           4-2

-------
                                                                            Section 4
 preservation, the automated samplers were then programmed to take the required number
 of samples and locked to maintain sample security.

        Each  automated sampler was  programmed to composite 48  %-hourly samples
 during the 24-hour sampling period.  In addition, the sampler was programmed to flush its
 sample tubjng with fresh wastewater before  and after taking each %-hourly sample.   The
r automated  samplers also recorded any abnormalities  detected  during the sampling period
 {e.g., inability to take a full sample) which enabled the field team to-detect sampling errors
 that might have occurred.                 '                         ,

        When the 24-hour composite samples were removed from the'automated samplers,
 the sample  temperatures  were  taken and  the collection  containers  were agitated  to
 distribute any settled solids throughout the sample. The sample was then transferred into
 sample bottles and preserved in ice before shipment to the laboratory for chemical analysis.
 Information on the analytical procedures is presented in Section 6.              '

 4.3.2  Grab Wastewater Samples

        Grab  wastewater   samples  were also  collected  for  dissolved  oxygen,   pH,
 temperature and feCal coliform analysis.  These samples were obtained  using the same
 automated samplers used for the composite sampling.

        Before collection of a grab sample, the sample collection container  was rinsed with
fresh wastewater and any  remaining ice was emptied from trie sampler.  The wastewater
sample was then taken and transferred to a clean container in preparation for field analysis.
 Samples that had to be analyzed for fecal coliform were segregated at  this  stage,  and
preserved in ice before shipment  to the laboratory.  Field  analyses to determine dissolved
oxygen (DO), pH, and temperature were then  performed on the  grab samples.  Information
on analytical procedures is presented in Section 6.

.4.3.3  Sludge Samples

       Sludge samples  were collected ~from  the  system  using a  sampling  pole  and
transferred into a clean  container prior to field analysis.  At  this point,, samples  to be
analyzed for Part 503 metals, TKN, total phosphorus,  % solids and  fecal coliform were
segregated and preserved in ice before shipment to the laboratory- Field analyses for  DO,
pH, and temperature were  then  carried  out  on the samples.   Information on  analytical
procedures is presented in Section 6.

4.3.4  Plant Samples

       Plant tissue samples were  collected by hand from the sampling locations. Samples
of water hyacinth and pennywort were dissected into  a stem section and a root section
using a  clean plastic knife, and. then placed  inside  sample containers.   These sample
containers were preserved in ice before shipment to the laboratory for analysis.  Information
on analytical procedures is presented,in Section 6.
                                            4-3

-------

-------
                                      Section 5
                                     Tracer Study
 5.1 Introduction
        This section  describes the methodology used to perform the tracer study at the
 AEES Facility.  The objective of the tracer study was to examine the individual stages of the
 treatment system in  order to determine the actual hydraulic detention times (HDTs) of the
 process components.  Information on the tracer study protocol is provided below.

 5.2 Test Locations

        The tracer study was performed at several locations throughout the AEES system.
 Each sampling  location had an injection point for the tracer compound and a water sampling
 point for  sample collection.   The  stages of the process  examined  are  summarized in
 Table 5.1 and displayed graphically in Figure 5-1.

                     Table 5.1      Tracer Study Sampling Locations
              Sample Point
 Description of Location
                   T1

                   T2

                   T3

                   T4

                   T5

                   T6

                   T7
. Across High-rate Marsh •

Across Duckweed Clarifier   '  •   '

Across the three Ecological Fluidized Beds

Across the 1st Ecological Fluidized Bed

Across the two Aerated Tanks

Across the 1 st Aerated Tank
                           i
Across the Anaerobic Bio-reactor
       The tracer study was carried out "in reverse order"; from the end of the process,
towards  the head of the process.   The reason for this was to prevent the anomalous
detection of previously injected tracer compound in the later stages of the study.
                                            5-1

-------
                                                                             Section 5
                  Figure 5-1   Tracer Study Sampling Locations
                                   Train B
      Raw
     Influent
                                              to Trains A and C
                  Anaerobic Bio-reactor
                  High-rate Marsh
         Aerated Tanks
Clarifier
Duckweed
 Clarifier
                                                     Ecological Fluidized Beds
    Treated
    Effluent
5.3 Tracer Study Methods

5.3.1  Tracer Compound and Injection                                   •'.,'•

       The  tracer compound  used in  this study was lithium  chloride.   Dyes  are  more
typically used 'for tracer studies but, in  this case, the plants in the AEES might have taken
the dye up through their roots. For this reason, it was necessary to use a compound that
would not be absorbed by  the plants and, consequently, lithium chloride was selected.

       The  required quantities of lithium  chloride for each sample location  were calculated
and weighed out using calibrated laboratory scales (accurate to oil g).  Before each part of
the study, the tracer compound was dissolved in deionized water and injected in a single
batch solution at the  head of  the system component  being tested.  The time of injection
was noted so that sampling would be started at the correct time.

5.3.2  Sample Collection

       Discrete wastewater samples were collected with an ISCO automatic  sampler that
was moved to a position downstream of the relevant sampling location at each stage of the
                                            5-2

-------
                                                                            Section 5
tracer study (T1 through T7J.  This sampler was inspected, cleaned,  and calibrated at the
beginning of each stage of the study.

       Before each sampling event,  the collection  containers were  cleaned and sample
tubing was  rinsed with the wastew^ter being tested,  the sampler was then filled with ice
for sample  preservation.  The  automated sampler was programmed  to  take  the required
number of samples  and locked to maintain sample security.

       The  automated sampler .was programmed to take discrete hourly samples during the
24-hour  sampling period.   In addition, the sampler  was programmed to flush  its sample
tubing with  fresh wastewater before and after taking each hourly sample.  The automated
sampler also recorded any abnormalities detected during the sampling  period (e.g., inability
to take a full sample).           '                .                        •'•.-•

       The  first discrete sample for a sample  location was always taken one  hour "after
injection of the tracer compound. The last sample was taken at'three  times the theoretical
HOT. These times are summarized in Table 5.2            .      , .,               _-'••.

        1     Table 5.2  Calculated HOT and Sample Times for Tracer Study
  Sample Point    Description of Location
Theoretical HOT
                                                           ID
Sampling End <2>
.: ' . . • . T1
T2 •
T3 •:
T4
' T5 '
T6
f 7
High-rate Marsh
Duckweed Clarifier
Three Ecological Fluidized Beds
1st Ecological Fluidized Bed
Two Aerated Tanks
'1st Aerated Tank
Anaerobic Bio-reactor
9 hours
7% hours
19% hours
6% hours
18 hours
9 hours
1 9 hours
27 hours
23 hours
59 hours
20 hours
54 hours
27 hours
57 hours
(1)     Calculated by Parsons ES.                        .              '
(2)     Time measured after injection of lithium chloride.           •

       When  the discrete, samples  were,  removed  from the  automated sampler, the
collection containers, were agitated to distribute any settled  compounds throughout the
sample.  Each sample was then transferred into a sample bottle, preserved with nitric acid,
and stored in ice before shipment to the laboratory for chemical analysis.  Information on
the analytical procedures  used is presented in Section 6.                             .

5.3.3  Calculation of Hydraulic Detention Times

       On receipt of the analytical data,  graphs of lithium concentration versus time were
plotted.,  The centroid of  each graph was calculated and used to derive the actual HDTs of
each system component.  As a check on the accuracy of the tracer study, calculations were
also performed to confirm the percentage  recovery of lithium chloride  for each sample
location.  More information on these calculations is presented in Section 9.
                                            5-3

-------

-------
                                      Section 6
                               Analytical Procedures
 6.1 introduction
        The analytical procedures used during this investigation may be separated into two
 general categories: field analyses and laboratory analyses.  The following sections describe
 the methods used during the study to perform both types of test.                       -

 6.2  Field Analyses

        Field analyses were carried  out on the wastewater and sludge  grab samples
 collected during the study. These analyses were as follows:

      •-•   '  ,PH;'      '   . •    •-'       '    .•'•','      .             '      :

        •      dissolved oxygen; and
        •      temperature.

                 '           .            '                 •   *          .             /  .
        Sample pH  was measured using a portable pH meter and probe;  dissolved  oxygen
 was  measured  using  a  portable  DO meter  and probe;  and sample  temperature was
 measured using a thermometer.  Both the pH and DO meters were calibrated before use and
 then  as required during  sampling.    Duplicate  samples  were  analyzed  according  to the.
 Quality Assurance Project  Plan (Section 7 and Appendix A).

        No field analyses were performed on the plant samples collected.
                               '          •                    '         ,
 6.3 Laboratory Analyses                  .                                       -

       A variety of chemical analyses were performed on the wastewater and residuals
 samples collected during  the study.   These analyses,  and  the USEPA approved methods
 followed, are summarized  in Table 6.1.                                    ,

 6.3.1   Wastewater

       The composite wastewater samples obtained for the process evaluation of the AEES
 were  analyzed for a range of  water quality parameters (Table 6.1). These parameters Were
 selected as they were/considered to be indicative of general water quality.  The methods
that were used for  analyses of these  conventional pollutants are the type most commonly
 specified in National Pollutant Discharge Elimination System (NPDES) permits for municipal
 wastewater  treatment  plants. The results of these  analyses  were used to evaluate the
 removal, efficiencies of the Anaerobic  Bio-reactor and the different'process components in
Train  B of the  treatment  system.   Factors such as  solids  removal,  and nitrification and
denitrification efficiencies could be estimated using this data. Discrete wastewater samples
collected during the tracer study were analyzed to determine  lithium concentration.  The
results of these analyses were used in the calculation  of HDTs for the system components.
 Duplicate analyses and  spike  samples  were  analyzed  for  these  wastewater samples
according to the Quality Assurance Project Plan (Section 7 and Appendix A).               '
                                            6-1

-------
                                                                                Section 6
                      Table 6.1     Summary of Laboratory Analyses
Measurement
Chemical Oxygen Demand (COD), total
Chemical Oxygen Demand (COD), soluble
Biochemical Oxygen Demand (BOD), total
Biochemical Oxygen Demand (BOD), soluble
Total Suspended Solids (TSS)
Volatile Suspended Solids (VSS)
Total Kjeldahl Nitrogen (TKN)
Total Kjeldahl Nitrogen (TKN)
Ammonia 
-------
                                      Section 7
                      Quality Assurance and Quality Control
 7.1  Introduction
             '            '"•'-< '   .    •        •      - \ .    .    .=  "<'.        -
        A quality assurance/quality control; (QA/QC) program was established for this study
 with  the  objective of gathering sufficiently precise and  accurate data for evaluating the
 AEES facijity.   A Quality  Assurance Project Plan (QAPjP)  was prepared  prior to  data
 collection to identify and/or  establish procedures fpr the following:         .
        QA/QC program organization and responsibilities;                      ,     -     -

        QA/QC objectives for precision, accuracy, completeness, representativeness, and
        comparability;                  -           !|
        Sampling and analytical procedures;

        Quality control checks and system audits;               -
       '. Data validation and calculation of data quality indicators; and
        Corrective action.
       In addition to the Project Manager and Technical Directors identified in the Work
Plan, the QAPjP identified QA/QC program staff to assume the roles  of Quality Assurance
Manager (QAM),  Quality Assurance Coordinator  (QAC), and  Laboratory Director  (LD).
QACs and  LDs  were  identified for both  field  and  analytical  activities.   The  QA/QC
responsibilities and lines of authority for each of the QA/QC program  staff are summarized
in the QAPjP.                ,

       A copy of,the QAPjP is presented in Appendix A.                         .

7.2  QA/QC Program Implementation and Procedures

7.2.1  Field Activities    ,   ,         '   , .

       Prior to initiating sample collection, the field QAC and LD reviewed and practiced
sample  collection  and handling techniques and  instrument  calibration procedures.  The
meters and equipment were calibrated prior to the start of field activities to ensure all were
in good working condition and  again during field activities, as required in  the  QAPJP-  The
field  LD,  or  a  designated  member  of  the  field  team,  completed  all  field   QA/QC
documentation  including chain-of  custody forms,  sample labels, field data  sheets, and
logbook notes.  Quality control  checks for field activities consisted of duplicate analyses on
field pH, DO, and temperature measurements.

       A field audit was conducted on the second day of sample collection activities. The
audit was conducted .by the, field QAC  to evaluate the performance of the. field LD, who
was the principal sample collector during  the study.  The audit  covered sample collection
and handling, as well as calibration and use of field instruments.
                                            7-1

-------
                                                                            Section 7
 7.2.2  Analytical Activities
        In  addition to following the project  specific  QA/QC guidelines in  the  QAPjP, the
 Parsons ES laboratory in Atlanta, Georgia, adheres to it's own QA/QC protocols described in
 their Quality Assurance and Quality Control  manual  (Parsons ES,  1992).   Technicians are
 well  qualified and undergo a formal training and certification program fbr each analytical
 parameter they perform.  The quality of work  performed  by the laboratory is indicated
 through successful participation in the  USEPA performance check sample program.

        The laboratory analyzed a variety of QC samples during the conduct of this study to
 assess accuracy and precision of the data including:  calibration standards, system blanks,
 laboratory control  samples, duplicate samples,  and  matrix spike samples.   Calibration
 standards, system blanks, and laboratory control  samples were performed with each set of
 samples to ensure  that  analytical procedures and  measurement systems were working
 properly.  Duplicate samples  were performed  on a minimum of 10%  of the samples
 collected for a specific parameter to assess the data quality objectives for precision,  Matrix
 spike samples were also  performed on 10% of the  samples collected for TKN, ammonia,
 nitrate, and total phosphorus to assess the data quality objectives for accuracy.

        A laboratory audit was conducted three weeks after initiation of analytical activities.
 The audit was  conducted by the laboratory QAC  to evaluate  the  performance of  the
 laboratory technicians receiving and analyzing samples for the study.  The audit covered
 sample receipt  and  handling, facilities  and general equipment,  QA/QC  documentation,
 chemical analysis, and data reduction, validation, and reporting.

        The laboratory QAC was responsible for reviewing, validating, and reporting all data
 generated.  The QAC evaluated compliance  with method  detection limits  and calculated
 precision, accuracy,  and completeness  values from the data.

 7.2.3   Program  Activities

        Monthly  reports were  prepared  by  the  QA/QC program staff.   The  field  and
 analytical LDs reported QA/QC activities using the  LD Field Form 1 and LD Lab Form 1,
 respectively, from the QAPjP. The field and analytical QACs reviewed the monthly reports
 from the LDs and reported QA/QC activities using the QAC  Form 1 from *the QAPjP.  All of
 the reports were submitted to the QAM, who reviewed the reports arid reported QA/QC
 activities to the Program Manager using the QAM Form 1 from the.QAPjP.

        Guidelines for implementation of corrective action procedures  are identified  in the
 QAPjP. Documentation of problem conditions was reported  on the  QAC and QAM Forms 1
 and on the cover letters from the laboratory (if applicable).

 7.3 QA/QC Program Results

 7.3.1   Field Activities

        Documentation of  field instrument calibrations are provided in the field logbook.  No
significant  problems  with  equipment calibration were  identified.  All required field QA/QC
documentation,  including  chain-of  custody forms, sample  labels, field data sheets,  and
logbook notes, was recorded and/or prepared daily during field activities.  Duplicate analysis
on  field pH,  DO,  and temperature measurements were evaluated from  April 12,1995,
through the end  of the sampling period.  All duplicate analyses were within 20  percent of
the original value as shown in Table 7.1. Duplicates were not performed for the first  six
                                            7-2

-------
                                                                            Section 7
 weeks of the study; however, results of duplicates performed later in the study indicated no
 technique or equipment problems.

                    Table 7.1  RPDs and PRRs for Analyzed Samples
Parameter
COD (total and soluble)
BOD (total and soluble)
TSS
vss
TKN '
TKN
Ammonia
Nitrate
Total phosphorus
Tptal phosphorus
Field pH
Field DO
Field temperature .
Fecal coliform
Part 503 metals
Matrix
water
water
water
water ,
water
sludge/plants
water
water
water
sludge/plants
water/sludge
water/sludge
water/sludge
water/sludge/plants
sludge/plants
RPD
{maximum)
3.9%
8.6%
i.
46%"'
27% .
12%
9%
4.2%
5.1%
12%
. 9.1%
0.4% -'•-.
20%
11.1%
,46%(2> '•
•15%
RPD PRR ':' PRR
Limit Limit
20% 97-105% 80-120%
20% . 90-115% 80-120%
30% ' -
30% -''.,-• - -
20% 87-120% 80-120%
30% 111-128% 70-130%
20% ' 97-1 27%131 , 80-120%
20% 79-109% 70-130%
20% 85-108% 80-120%
30% 80-116% 70-130%
- . . • - .•-.-/'
- -. ' - * ~ '
•'• -
•_'••-'•
30% ' ,80-118% . 70-130%
RPD Relative Percent Difference
PRR Percent Recovery
Range


(1) One duplicate analysis exceeded the control limit for this parameter. ,
(2) Only one duplicate analysis exceeded 30%,
(3) One matrix spike
exceeded the- control limit
although there was
for this parameter.
no control limit for this parameter.

       Results  of the field audit were satisfactory with two minor nonconformities.  The,
stock buffer solutions used for calibrating the  pH meter were past the recommended one
year expiration  date and the thermometer used for field activities had not been calibrated
with an NIST (National Institute of Standards in Technology) traceable thermometer.
                                            7-3

-------
                                                                             Section 7
 7.3.2  Analytical Activities

        Results of duplicate and matrix spike samples in terms of relative percent difference
 (RPD) and percent recovery range (PRR), respectively, are presented in Table 7.1.  Data
 quality objectives were met with the exception of one duplicate for TSS and one spike for
 ammonia. Percent completeness for each sampling location is provided  in Table 7.21  The
 percent completeness is the percent of the total data set that is valid (i.e., that meet  the
 RPD and PRR control  limits and  are analyzed  within  the  allowable holding  time).   The
 objective for this study is 90%  completeness. Three sampling points for TSS analyses were
 slightly below this objective; however, the overall percent completeness for each parameter
 was J>.93.

        Results of the  laboratory audit were satisfactory:with  one minor  nonconformity.
 The laboratory does not have a standard operating procedure for data reduction, validation,
 and reporting.  However, the laboratory*does address this topic in their QA/QC .manual.

                            Table 7.2  Study Completeness
Parameter
Total COD
Soluble COO
Total BOD-
Soluble BOD
TSS
VSS
TKN
Ammonia
Nitrate
Total phosphorus
Field pH
Reid DO
Field temperature
Fecal Coliform
Part 503 metals
Percent solids
W1
100%
100%
93%
93%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%


W2
100%
100%
- 93%
93%
86%
93%
100%
93%
100%
100%
100%
100%
100%



% Completeness by Sample Location
W3 W4 W5 W6 S1
100%
100%
93%
93%
86%
93%
100%
93%
100%
100%
100%
100%
100%



100%
100%
93%
93%
100%
93%
100%
100%
100% ,
100%
100%
100%
100%



100%
100%
93%
93%
86%
1 00%
100%
93%
100%
1 00%
100%
100%
100%



100%
1 00%
93%
93%
100%
1 00%
100% ' 100%
100%'
100%
100% 100%
100% '100%
100% 100%
100% 100%
100% 100%
100%
1 00%
% Comp
S2 Plants Overall
100%
100%
93%
93%
93%
96%
100% 100% 1OO% ,
96%
1OO%
100% 100% TOO%
100% 100%
100% , , 1OO%
100% 1OO%
100% 100% 700%
100% 100% 700%
100% WO%
7.3.3  Program Activities

       QA reports were prepared for the months of March, April, May, and June 1995. No
major problem conditions were reported that required extensive corrective action.  Several
minor problems were identified and quickly resolved  during the conduct of this study and
include the following:

•      As  discussed in  Section 7.3.2,  variances to the  data quality objectives  Were
       observed with two sets of data. The variance observed with the TSS duplicate data
                                            7-4

-------
                                                                           Section 7
       for  the March 15 samples was attributed to a  non-homogenous sample.   The
       variance observed with the ammonia matrix spike data for the April 12 samples was
       attributed  to  matrix  interference,  since the  laboratory  control  sample   run
       concurrently was well within the control limit.

•      A problem  condition 'with BOD analyses was identified and resolved quickly by the
       QAC when it was discovered that the wrong seed innoculum had been shipped to
       the laboratory from the supplier.                      ,

•      During the  beginning  of the study, some TKN values  were determined to be less
       than the  ammonia values for the corresponding samples.  The reason for this was
       judged to be a consequence of the analytical method  for TKN  when  the analyzed
       sample contained a high percentage  of nitrogen  as ammonia.   The TKN analysis
       (USEPA Method 351.3) involves refluxing the sample for a period of time which can
       drive  volatile ammonia from  the  sample  before the analysis  is complete.   This
       problem was rectified by modifying the analytical  method slightly to  decrease  the
       reflux period and, consequently, minimize the loss of ammonia from the sample.
       Where this,had occurred, the value for TKN was  assumed to equal the value for
       NH3.                -    -           :
•      It was suggested that analytical variability was the  reason that some VSS values
       were determined to be greater than TSS values. This only occurred when both TSS
       and VSS  were  of low magnitude.  Where this occurred, the VSS  value was assumed
       to equal the TSS value.         .
•      A review of the  field  QA report for March revealed  that field duplicates were  not
       being performed  for pH, DO;  and temperature.   This  field activity was initiated
       immediately thereafter by the field LD.

7.4 Conclusion

       In general,  the QA/QC requirements identified in the QAPjP  were met during  the
conduct of this study and all of the required  QA/QC documentation is  on file.  The data
quality objectives for accuracy and precision were not achieved in two cases; however,  the
reason was not  attributed to analytical performance.  In  both cases, the variances  were
attributed  to sample characteristics.   For this reason and  the fact that the  number of
samples collected  for this study is relatively small, the sample data  impacted by these
variances are used  in the data analysis.                           ,                ,
                                            7-5

-------

-------
                                      Section 8
                                     Flow Data
 8.1  Introduction
        The flows of' waste water treated by the AEES  Facility were  measured  for the
 duration of the  eleven week study using influent and effluent flow meters.  This section
 summarizes the  results and findings of the flow measurements.  The raw data from which
 this summary \s  drawn is presented in Appendix B.

 8.2 Influent Flows

        The recorded Train B influent data demonstrated that mean daily flow rates between
 10,000 and 15,OOQ gpd were being achieved for the duration of the  study (not including
 periods when the plant was shut down).  The average of mean daily flows over the course
 of the study was calculated to  be  13,451 gpd which is comparable with the anticipated
 flow rate into  Train B of approximately 13,300 gpd.  The weekly mean influent flow rates
 are summarized in Table 8.1.      '.''

       -There were  some instances during  the study when accidental power  outages  and
 problems with the flow  meter and associated computer resulted  in "gaps" in the recorded
 flow data.   Where this  occurred, the missing flow data were either calculated from daily
 totalized flow  data  recorded  by  hand in the field, or the data were interpolated from  the
 recorded flows.  In addition, as noted in the table, on three  occasions the AEES Facility was
 shut down and,  consequently, was not receiving influent flow for a period of days. The
 influent flows for these  days have not been included in the calculations of the daily mean
 flows.

 8.3 Effluent Flows

       The  effluent  flow data recorded by the existing OAI flow meter showed a large
 variability in comparison  with the influent flow data.  The cause of this could have been  the
 effluent flow meter.  For this reason the effluent flow data was deemed to be unreliable and
 not used in the evaluation.  The influent flow totals were considered to be sufficient data
for the process evaluation.                      '"!'.'•."
                                            8-1

-------
                                                                             Section 8

Study Week
Weekl
Week 2
WeekS

n/a

Week 4
WeekS
. Week6
Week?
WeekS
WeekS
Week 10
Week 1 1
n/a

n/a



Week 12

Week 13
Week 14



Table 8.1 Mean
Dates
2/28/95 to 3/3/95
3/4/95 to 3/1 0/95
3/1 1/95 to 3/1 7/95

3/1 8/95 to 3/24/95

3/25/95 to 3/31/95
4/1/95 to 4/7/95
4/8/95 to 4/14/95
4/1 5/95 to 4/21/95
4/22/95 to 4/28/95
4/29/95 to 5/5/95
5/6/95 to 5/1 2/95
5/1 3/95 to 5/1 9/95
5/20/95 to 5/26/95

5/27/95 to 6/2/95



6/3/95 to 6/9/95

6/1 0/95 to 6/16/95
6/1 7/95 to 6/23/95



Daily Wastewater
Mean Daily Flow
1 1 ,622 gpd
1 3,303 gpd
13,870 gpd

13,804 gpd

13,463 gpd
13,238 gpd
14,775 gpd
13,542 gpd
13,456 gpd
12,639 gpd
13,743 gpd
14,239 gpd
no data

no data



no data

13,009 gpd
13,6 14 gpd



Flows into Train B
Comments


The plant was shut down on 3/1 7/9$
owing to a power outage (this day is not
included in the daily mean) >
The plant was shut down from 3/1 8/95 to
3/20/95 owing to a power outage (these
days are not included in the daily mean)


'





Flow meter malfunction resulted in the
inaccurate reading of influent flows
Flow meter malfunction resulted in the
inaccurate reading of influent flows.
Influent flow was shut down between
5/24/95 and 6/1/95
Flow meter malfunction resulted in the
inaccurate reading of influent flows :

.Low influent flows on 6/1 7/95 and 6/1 8/95
owing to clogging of influent pump at
Ballanger WWTP (these days are not
included in the daily mean)
Mean of Mean Daily Flows
13,451 gpd
                                            8-2

-------
                                     Section 9
                               System Performance
 9.1 Introduction
        The data generated during  the eleven  week  wastewater  and residuals sampling
 study {Section 4) was used to evaluate the performance of the AEES Facility.  This section
 summarizes these data  and details  some observations concerning the AEES process. The
 raw data on which this section is based is presented in Appendix C.

 9.2 Wastewater Characteristics

       ,By the end. of the eleven week study, individual water quality samples had  been
 taken from each sample location.(W1 to W6J throughout the process.  Analysis of these
 samples yielded the data that was  used to assess the process performance of the AEES
 Facility.   However,  before these data were used, they were examined and adjusted to
 remove any spurious points and statistical outliers that might influence the evaluation.

 SL2J—Data Manipulation and Statistical Assessment

       The first step of the  data  manipulation was to review the  field  notebook  and
 laboratory reports to remove any data points that were known to be invalid.  Some values
 were removed because of a process upset and a sampling mishap that  occurred during the
 study.  Additionally/the first week's data for point W5 could not be used since the initial-
 location for sample point W5 was moved after Week 1  of the study  (see Section 4). There
 were also a few  cases where, owing to analytical variability, some values for VSS exceeded
 those for TSS.  In these cases, the value for VSS was  assumed to equal the TSS value.
 Similarly, the analyses for ammonia yielded some values that exceeded the TKN values.
 This was determined to be a consequence of the analytical method for  TKN when the TKN
 comprises mainly ammonia.  Consequently, the analytical method was  modified slightly to
 account forjhis  but, where this had already occurred,  the TKN was assumed to equal the
 ammonia value.      >

       After the initial review, the data  were examined statistically.  This involved testing
to identify how the study data, were statistically distributed, followed by discordancy testing
to remove any "outliers" (points that are outside a data set's normal  distribution).  Outliers
 were removed in order that they would not influence the  process evaluation,  by influencing
the mean data either upwards  or downwards.  Once these statistics had been performed,
the data were used  to derive means from which the  process could be assessed.  These
means are presented  in Section 9.2.2.

       Full, details of the data manipulation and statistical assessment  are  presented in
Appendix C.                                                                   '
                                           9-1

-------
                                                                             Section 9
  9.2.2   Mean Water Quality Data

         The mean  water  quality data from the  eleven  week study  are  presented in
  Table 9.1.  The raw  data,  indicating  the  values  removed after data  manipulation  and
  statistical assessment, are presented in Appendix C.

         The mean values for chemical oxygen demand  (total and soluble), along with the
  associated standard deviations, are  depicted graphically m  Figure 9-1.  Most of the  COD
  (total)  reduction occurs in  the Anaerobic Bio-reactor, even though further treatment takes
  place downstream. The very slight increase in total  COD in the Aerated Tank effluent could.
  be  a result of the sludge recycle to the Aerated  Tanks from  upstream.   However, the
  standard deviations of the  data from sample points W2 and W3 overlap to a large  degree
  which indicates the insignificance of this small peak.                               .

         Soluble COD appears to increase slightly in the effluent from the Anaerobic Bio-
  reactor which suggests that some of the total COD reduction is caused by breakdown of
  compounds into a more soluble form.  The  major decline in soluble  COD appears to  take
  place in the Aerated Tanks, after which the levels fall only  slightly throughout the  rest of
 the system.

        The mean values for total and  soluble  BOD, along with the associated  standard
  deviations, are depicted graphically in  Figure 9-2.   As in'the  case of COD, the. major
  reduction  in total five-day BOD occurs in the  Anaerobic Bio-reactor,  although  additional
 decreases occur in the subsequent process components.  The soluble BOD increases slightly
 after the Anaerobic Bio-reactor which could  be  a  result  of the breakdown of BOD-causing
 compounds into a more soluble form. -The Aerated  Tanks appear to remove the  remaining
 BOD from the wastewater before it passes out of the system.

        In  this case, "soluble" BOD may be  a slight misnomer  since the fraction of BOD
 analyzed by the USEPA method (Method 405.1)  is  actually that  which passes through a
 0.45//m cellulose-nitrate membrane.   Therefore, this  BOD fraction  is  not necessarily
 "soluble".   However,  since the Method 405.1  definition of soluble  BOD is  used by the
 USEPA, it is a valid one with respect to this process evaluation.
•
        The mean values for suspended solids (total and volatile), along with the associated
 standard deviations, are  displayed graphically in  Figure 9-3.  Again, the Anaerobic  Bio-
 reactor appears to be responsible for the majority of  TSS and VSS reduction taking place in
 the  treatment  system.   The peak that occurs following the Anaerobic Bio-reactor  could
 possibly be a consequence of the sludge recycle  to the Aerated Tanks from upstream  (a
 similar, less-defined peak occurs for total COD). Alternatively, root matter from the  plants
 in the Aerated Tanks may be  sloughed off into  the system, resulting in an increase  in
 suspended solids;  or it could be a combination of these two factors.

        Most of the ensuing solids reduction appears  to be carried out by the 1st Ecological
 Fluidized Bed.  With respect to suspended solids, there  is very  little  noticeable difference
 between the effluent from the 3rd Ecological Fluidized Bed and the High-rate Marsh.

       The mean values for the nitrogenous components  (TKN, ammonia and nitrate), along
 with the associated standard deviations, are displayed graphically in Figure 9-4. this  graph
 provides an indication of what is occurring with respect to  nitrification and denitrification
throughout the system. Both TKN and ammonia decrease steadily as they pass through the
 process. There is a slight peak of TKN that occurs after the Aerated Tanks but this may be
 a result of the aforementioned sludge recycle  from upstream  (the overlapping  standard
deviations  between W2 and W3 may  mean that this  peak is not even significant).   There is
                                             9-2

-------
     >.

     Ij
     o
     (O <
     UJ 3
     CC LU
     O LU
     u. u
0)
i?
         -
     >•
     a.fc
     CC
     ^










1
•—
CO
3
O

5
CO
CD
S

•







. 8 i s
-< is «
LU r-
j:
vrata ME
Effluent
oa
x
§
O TJ
li
T2 S
m 2
t£
Ecological
id Bed Effluent
• .5
•"" -o
3
U.
•£

ted Tank E
«
oblo Bio-raaotor
Effluent
a
c

c
D '
I"
i
£

I



I


•s






i

i





i

' -• '• " x
• - 3-





1
E.
o

' -
t

c<
to



r*


00
ai






ai
m,
CO

S
|





q
CO





•


Q
O
O
"3
K

1

ct
CO



»


-d
IO






CO
CO*
CO
,
CM
CO*





to
o


cb






a
3
ID
E
3
O

O

10



OC


2






CO
10*
O
^-

0
d
CO





00
0


D)






in
Q
3
"to
o

1

C

'

CO


CO*






o>

b






g


D)






in
D
o
5
o
CO

6

10
CO



05
O3


CO






q
03*

0
»





^
0


Ob


»
•a
"o
CO
•a
a>
3
D
1
W
3
a
o

1

o
C1



cc


CO
«






q
CM'

q
CO





0
•<*
CO
CO


0)

'*>
"2
CO
•a
3
0
3.
0
CO
03
O

w

Q



O
C


O3
0)
CM






O
CO*

CO
CO*





to*
10


a



5
a
0

0
7
03
O

-

to
IT



10


03
CN
CN






q
CO
CM

03
CO
CO





CO
10
CM


s=
t





5
3
£.
£

in

c



o>
o
^^

CN






03
CO
d

IO
d





CO
d


D)






ID
IO
?
Composite Samples

0»

CO



q


q
03*






to
00

CM
00*





CO
CO

Q.
OJ






3
i
v>
3
to
3

I

O


1
||

1
1
iH§^
^^«s
^^^N!
^S;

1
1
1
I

§§s§s»



03
05*
O
CO
&
o
"o





Coliform
ta
o

1

f



to


'ij






CO

CM





03
O5

|
H





3.
T3
y

|

a
p



to
w


1C
10*






o>

o>





O5
CM

3



O
CD
X
O
d Dissolved
3

|

to
CO*



M
00


^






5

to
•a





m

O



0) :
3
g .
0)
1
D

-------
                                                        C
                                                        'o
                                                        Q.
                                                        J>
                                                        Q.
                                                        £
                                                        to
                                                        03
{|/6iu) pueiuea ueBAxo
                       9-4

-------
ua.6XxQ
     9-5

-------
    CO ,W
    .2 ^

    i£ co

    g|
f)  C ^

05  E §
2  5 §"
u.
 0)

ai
       s
       03

       2
       CO
                                                                       J3

                                                                        S ro  «
                                                                        Q> O  ^
                                                                        
-------
(l/6ui) puetuaq uaBAxQ
                9-7

-------
                                                                              Section 9
 also a slight increase in ammonia in the Anaerobic Bio-reactor effluent which could indicate
 that a fraction  of the TKN is broken down to ammonia in this component of the process.
 Alternatively, this  could be a result of the  sludge recycle into the Anaerobic Bio-reactor.
 There is very little reduction of TKN or ammonia observed passing through the Duckweed
 Clarifier and High-rate Marsh.

        Nitrate  levels  begin to  increase visibly  within  the  Ecological  Fluidized  Beds,
 indicating that most nitrification is occurring  in these units. The effluent from the High-rate
 Marsh demonstrates a reduction in nitrate concentrations,  suggesting that dentrification has
 begun to occur in the last two stages of the process (the  Duckweed Clarifier and High-rate
 Marsh).                           '  .\       •                                '
                                                                               »i
       The  mean values  for total  phosphorus,  along   with the  associated  standard
 deviations,  are  displayed  graphically  in  Figure 9-5.   As  with  total  COD, total _BOD  and,
 suspended solids, most of the phosphorus removal occurring in the system appears to take
 place in the Anaerobic Bio-reactor.  Once again, there, may be  a slight increase  occurring
 within the Aerated Tanks which could be attributed to the sludge recycle.  However, the
 overlapping standard deviations of the data -at points W2, W3 and W5 suggest that the
 increase is not a significant one.   There is also a slight decrease in total phosphorus within
 the Ecological Fluidized Beds.                                                    :

       The mean  values for field pH and  dissolved oxygen,  along  with the associated
 standard deviations, are displayed graphically in Figure 9-6.  The pH  remains consistently
 between pH 7 and pH 8 throughout the process, 'and the  small standard deviations of this
 data suggest that  with respect to pH the system is very stable.   The level  of  dissolved
 oxygen Is at approximately the same level in both the influent and the treated effluent.  This
 level increases within the process system in the Aerated Tank and  Ecological Fluidized Bed
 effluents, since these units are both aerated.  The increase  of DO observedlin the Anaerobic
 Bio-reactor effluent is likely to be  the result of the  aeration that the wastewater undergoes
 in the three odor-control tanks following this system component.                  . '..

       Graphs were not plotted for fecal coliform or temperature. The mean fecal coliform
 count in the raw influent decreases by  over 99.9%  by the time it has left the treatment
 system.  From the data, it is not possible to tell where in the process most  of. this reduction
 is taking place.  The field  sample temperatures taken at  each  sample location increased
throughout  the  duration of  the study,  as the  weather got  warmer and,  therefore, .it is
doubtful that this data would be useful in the process evaluation. This data was  collected
purely for QA/QC purposes.

9.3 Treatment Efficiencies

       Using the water quality data described in Section  9.2, treatment efficiencies were
calculated for the overall process  as well as for  the individual process  components of the
AEES Facility.  The individual component treatment efficiencies  were calculated using the
following equation:

              Component Treatment Efficiency  =  [(Pa - Pb)/Pa] x 100

       Where:       Pa =  pollutant concentration in component influent

                     Pb =  pollutant concentration in component effluent
                                             9-8

-------
    C
    O
    ®  S
    o  o
in  c s:
-L  a-
-------
                                  Sample pH
                 q
                 CO
q
oi
q
d

11
 §  ?
5  I
 O

 C  QJ

 >  I
^  2
HI  03
   Q_
c
05
03
>•
X
O
73
03
>
O
to
to
a
2
0)
u_
f











IT
Q.
2
CD
LE
i
*
q
06
q
CO
                                                          IXA
                                                      VXi
                                                    -XH
                                                                         * ~  r
                                                                         CO -C  C
                                                                             LU
                                                O  0)
                                                '5 03 ^

                                                "5  ® 3
                                                o .H 5:
                                                CO "O
                                                O 03
                                                '3 °°
                                                                                 £
                                                                                 Q.

                                                                                 CO
                                                                                 CO
                                                                     gjltf
                                                                        w « .
                                                                          CO
                                                                        a
                                                                        CO
                                                                       QC
         oo      r»      CD     in     ^     co     CM


                         (l/Biu) ueBAxo paAjossja
                                       ,9-10

-------
                                                                             Section 9
        The  calculation  of  the  system's overall treatment efficiency >was  based on  the
 following equation:    /                                 .

                  Process Treatment Efficiency  =  [(P, - Pe)/P,] x 100

        Where:        Ps =  pollutant concentration in raw influent to AEES

                      Pe = pollutant concentration in treated effluent from AEES

        An exception to  this formula  was used in the  case  of nitrate treatment efficiency.
 This  pollutant is generated in the process during  nitrification and, therefore, the overall
•treatment efficiency was calculated  by looking at the performance  of the denitrifying
 components of the process (the  Duckweed Clarifier and High-rate Marsh).

        The  overall  and individual  component treatment  efficiencies  for  the  selected
 pollutants are shown in Table 9.2. ,                                            .

        In addition to this, the percentage contributions to pollutant removal of each system
 component was calculated for the major water quality  parameters (excluding  nitrate).  This
 was calculated using the following equation:

            Contribution to Ppllutant Removal  =  t(Pa - Pb)/(Pi - Pe)l x 100

        Where:        Pa =  pollutant concentration in component influent

   .     .             Pb •=  pollutant concentration in component effluent

                      PI  = pollutant concentration in  raw influent to AEES

                  -  Pe = . pollutant concentration in treated effluent from AEES

        In some situations,  an  increase of a  given pollutant .occurred within a system
component.  For example, an increase of suspended solids takes  place  after the Aerated
Tanks which, it is suspected, is  caused by the sludge recycle.  In these instances, system
components had to be combined in order to calculate thejr correct percentage contributions
to pollutant removal.                                                        ...

        The percentage contributions  to pollutant removal for the selected pollutants are
shown in Table 9.3 and are also displayed as pie charts  in Figures 9-7 through  9-12.

        These figures confirm  the  previous observations  that the Anaerobic  Bio-reactor is
removing the vast  majority  (65% to  85%)  of total  COD,  total  BOD, TSS, and  total
phosphorus from the wastewater  passing through the system.  In the case of  TKN and
ammonia, it is evident from the pie charts that most nitrification is taking  place in the 2nd
and  3rd  Ecological  Fluidized  Beds,   with  some  occurring  further  upstream  in  the  1st
Ecological Fluidized Bed and the Aerated Tanks.

9.4 Residuals Characteristics

        During the  eleven week study, various samples tif the process residuals (sludge and
plants)  were collected from sample locations  throughout the  process.  Analysis of these
samples yielded data that were used to assess the quality of the residuals generated by the
process. This assessment would examine how suitable the sludge and plants  were for land
disposal and(or composting.
                                            9-11

-------
Csj



UJ  LU
T:  LU

Z  °
W- <

^  i

fc  2
UJ  cc
t_  ui
2  °-
O
      UJ  ai
      CC  >
      H  3
      I-  tu



      1




      2
                                                                                 E
                                                                                 co
                                                                                5
                                                                                S
                                                                                °-
                                                                                E

                                                                                8
                                                                          8
                                                                          S

                                                                          U

                                                                          .£

                                                                          c
                                                                          CO

                                                                          CO
                                                                                        o
                                                                                        c:
                                                                                        o


                                                                                        to
                                                                                        
 o  -2

 (U  (U
                                                                          o

                                                                          T3
                                                                                a


                                                                                co
                                                                          8

                                                                          CO
                                                                          Q.
                                                                          0)

                                                                          I

                                                                          a
                                                                          O)
 CO  C

J  -2

 £  i

 c  I
 5  w

j*  §
 M  §
J2  E
 5  £
                                                                                    O

                                                                                    •-

                                                                                    CO
                                                                                   ,£
    co
    +*
    D
                                                                                       O

                                                                                       Q.
                                                                               «-  CM   CO
                                               9-12

-------
CO
 (0
        O
        2
        s
       '
            '8
            '
        £9
        CC   cc
        O   u

        0 -S
        _l   LU
            IU
       2












CO
o
CC
m
S
2
J.
.0
o
0
 m
||
CO J
"O 1=
a UL

reactor
6
m
u
In
2
CD
CO
C '

'-
- . ' •



1
2
CO
D.




'•
CN





#
CO




O
CM







•

^



0
CO

o ^ JC co •o -Si 75 H ^9 0 S3 J^ ^o n *^ • CO "c o E E -CO c •55 c •2 c CO c •2 c V 13 •t z. CN « v§ CM O i o CO o Q. to O Q- 75 1— I '£ o u 0) J3 § CO t> cu OQ cu • c 15 . I . u -£ O H- •o o o w o *3 § CO •o Z CO C m o _, u .0) N co = o ^ -i _3 "> LL. =6 "5 ^ O CU P. -B o s 75 t> ^ CO CO i= •o Cl> a> €'• •o CO CO u OJ J S 2 E ' £T 2 "i o c CO ~ a> a o u - o -£•'•1: 1 I c _o *4-» _co 3 O CO u "8 CO cu CO o a. 3 Q. CU -C o LL. trt" >«~" •o CO n *w O U cu 4-« o 4= co ' 3 U CO 0 H* o to cu (0 o a. 3 a. cu JZ o , LL c a> "c .0 ra .y "c V 4^- "o a> 3 1 0) - 4-* 2 a O i o S. 4-» CO "E o *^ CO c cu o a. 0 p 9-13


-------
                       Figure 9-7
         Contributions of Process Components
       Total Chemical Oxygen Demand Removal
                      Duckweed Clarifier and
                        High-rate Marsh
      2nd and 3rd Ecological      2%
         Fluidized Beds
             6%
 1st Ecological
 Fluidized Bed
    20%
 Aerated Tanks
     4%
                                            Anaerobic Bio-reactor
                                                  68%
                      Figure 9-8
        Contributions of Process Components
     Total Biochemical Oxygen Demand Removal
    2nd and 3rd Ecological
        Fluidized Beds
            7%
   1st Ecological
   Fluidized Bed
      12%
Aerated Tanks
    12%
Duckweed Clarifier and
   High-rate Marsh
        1%
                                          Anaerobic Bio-reactor
                                                 68%
                           9-14

-------
                                Figure 9-9
                  Contributions of Process Components
                    Total Suspended Solids Removal
            2nd and 3rd Ecological
               Fluidized Beds
                   7%
         Aerated Tanks
        and 1 st Ecological
          Fluidized Bed
              8%
Duckweed Clarifier and
   High-rate Marsh
        1 %
                                                        Anaerobic Bio-reactor
                                                              84%
                               Figure 9-10
                 Contributions of Process Components
                    Total Kjeldahl Nitrogen Removal
                          Duckweed Clarifier and
                             High-rate Marsh
                                  3%
2nd and 3rd Ecological
    Fluidized Beds
       42%
                                                    Anaerobic Bio-reactor
                                                           27%
                                                     Aerated Tanks  •
                                                    and 1 st Ecological
                                                      Fluidized Bed
                                                         28% .'
                                   9-15

-------
                             Figure 9-11
               Contributions of Process Components
                         Ammonia Removal
                  Duckweed Clarifier and
                     High-rate Marsh
Anaerobic Bio-reactor,
 Aerated Tanks and
    1 st Ecological
    Fluidized Bed
       13%
                                                       2nd and 3rd Ecological
                                                          Fluidized Beds
                                                              77%
                            Figure 9-12
              Contributions of Process Components
                    Total Phosphorus Removal
       2nd and 3rd Ecological
           Fluidized Beds
              16%
                         Duckweed Clarifier and
                            High-rate Marsh
                                2%
 Aerated Tanks
and 1st Ecological
  Fluidized Bed
      2%
                                                  Anaerobic Bio-reactor
                                                        80%
                                 9-16

-------
                                                                                Section 9
           The raw results from the analysis of the sludge are presented in Appendix C.  Before
    these data  can  be  compared  with the  503  Regulations  for sludge  disposal,  the
    concentrations of metal (in mg/l) must be converted to a dry weight basis. The converted
>•    data are  shown  in Table 9.4.  Note  that this  conversion  assumes all  of the  metals are
    concentrated iri the solid fraction of the sludge.

           For the  sludge samples taken  from  both  sampling  locations, there  are no
    concentrations of metals  that  exceed the  limits  as described in the 503 Regulations.
    Therefore, with respect to  the current metals regulations, there would be no restrictions on
    the land application of the sludge generated by the AEES.

           However,  the  fecal coliform  count in the  sludge  from the Anaerobic  Bio-reactor
    would appear to be well in  excess of the Land Applicable Minimum Criteria permitted by,the
    503 Regulations for pathogens.  This would preclude the land application  of the sludge from
    this  unit unless it had first been treated to reduce the fecal coliform count.  The sludge from
    the clarifier (sample location S2)  contains  less fecal cofiform,  although  it is still over the
    limit  for,  exceptional  quality  (EQ) sludges, meaning  that it  could only be  applied to
    agricultural land, forests, public contact sites and/or reclamation sites in limited situations
    by using additional restrictions (e.g., limited site access and crop uses).  Its application to'
    sites other than these would be permitted without restriction.                . ,

          The data from the plant analyses are shown in Table 9.5.  These data are compared
    with the 503 Regulations (for land application of sewage sludge) owing  to the absence of
    other suitable standards for the land application of compostable, material. This comparison
    is made assuming  that no metals are lost during  composting (e.g., from leaching), and  that
    any compost bulking agents used do not affect the metals content of the  product. •

          The data  indicate that the plants contain very low concentrations of the metals
    controlled  by the  503 Regulations and that these concentrations are well below the EQ
    limit. The general trend appears to be that the plant roots hold more metals than the plant
    stems which is  probably a result of sludge that covers the root systems (i.e., it is  the sludge
   ,that  is the location of most of these  metals, not the plants).    However,  it could also be
   .caused  by preferential storage of metals  in the  roots so further examination of  this
    phenomenon would be required before a definite conclusion could be drawn. Fecal coliform
    counts on the plants are also less than the pathogen Pollutant Limit and exhibit the trend of
    being higher for the  plants' roots, although the coliform on the composted product  would
    likely be different to that on the plants prior to composting.  Therefore, on the basis  of the
  .  above information, the composted product  from  these plants could be allowably land
    applied.

          There do not appear to be any major differences between plant type with  respect to
    metals concentration but there was ten times more fecal coliform on the hyacinth root than
   on the pennywort  root. This could be a result of the process since the  pennywort sample
    was  taken from the  2nd Aerated Tank whereas the hyacinth was taken from the  1st
   Aerated Tank.   Fepal  coliform could, therefore, be  reduced .between   these two tanks.
    However,  once  again the difference is more likely, to be attributable to sludge accumulation
   or root storage: the  hyacinth  roots are significantly larger than those on  the pennywort;
   Consequently,  fecal  coliform   counts  would   be   higher   on   the   hyacinth  root.
                                               9-17

-------

O)


I
             (O
             o
             a.

             ui

             a.

             S
             <
             (O
3

|
<
•J3
C
«
1
u



£
H
S
CO
o
1
i
<




«


•5
K
eo
3
10

g
0
II 1
•o
*^
e.
T5
ill
g.
2
^
*••
«3
e • £

S
t

5
•B .
i|I
I
e-
33.
Sei
I S -5 1
S S g:§
£ S'i<3

o S
U i2
= J! 5
o "S 5
a >s -2 T:
1 HE
cS — s
5
c

o
i


co
CO




ID
CO




CO*





CO




5




D

O
^

[Arsenic


CD
c




f.
co




5





£




en
co




8

o
a

iCadmlum


CO
c




S




rt





i?




8
CM




CO

I
"3

3
U


CO
u




f.
cc




CO
to
CO





§




8
ID




If

I
^

D


a




R




5





§




I




I

t
o

•s
2


en
0




«




CD
6





CO




t




D

I
E

3
J
i


a




8




o
CO





s




1
1
•)



o

5
a
E
3
i
3
|


<0
C




CO
eo




CO
eo





en
CO




O
C4




S

I
5

i


to
CO




to
CO




CO
eo'





eo
ri




CO
CO




I

I
"a

1 Selenium


i
c




rv
oE



N
s
*~




s
.*"



8
CO




1

s
1

R
§.
ts
S
si 1
i 5 s
I
^>
•*•*
e_
i
•gs |
».
s
£__
*M
" — £
a
S

s_
f
|||
1>f
t
s
S
^ . 3
55 if
5s 15

0
X
UJ
s '•
•S 's
:£st§
jf*§
5 il
— ii
|


C
c! :

s
5
c



g
1



I
8"
r«



s
|
d



1




|

S
u
£
I
U
                                                                                              5  '
                                                                                                       J  CJ  «


                                                                                                       ill
                                                                                                        a.  g  5.

                                                                                                       5-  £  5-
                                                                                                       D
                                                                                                             .u
                                                                                              I     I
                                                                                              i  11
                                                                                              I  t  !
                                                                                              i  &  i
xceed
                                                                                                 0  o

                                                                                                 m  O.
             SS  g  E


             £  1  &


             I  -  "


             ! 1  -
             t *-  c
             o  c  o

             &  S  e
             O  C  o
             O.  S  Q.
       §  1
                                                                                                    *•*
    S  I1  *
    1  1  D
    I'-  *
    g  S  -g

    11  s
    s  E  e
                n
                   I  s
                                                                                                       ja  >•

                                                                                                       r*  „ eo
                                                                                                        .  CO .£
e re
    S  JS


    25
    e  I
                                                                                                       ^  I
                                                                                                       S  «

                                                                                                       i  I
                                                                                                       J.  8
          -E  Si
S  te
                                                                                             I 1
                                                                                             -  e
                                                                                             .2 I
                                                                                                          •«  s
    g  1  f

   |  J  I
    >  2  c»


   fll
lform fo
   I i



   III
                                                                                                       =  £
                                                                                                             S',-r
J
   1  I
         JB


         •O
                118
E  E
3=3-3
££<}<>
                                                                                                *-  o  u  u  'o

                                                                                                 °  ^  J2  £  £


                                                                                                I  |  §  J  J

                                                                                                 •9  e  d  «  «]





                                                                                                       II  I
   I  ^
   •  3
   CO  <
                                                          9-18

-------
     o
     $
     Q
     O

     2.
in
. o>
CD
   Q 2
   II
I
o
<
     i


?
s

z





09
§
J?
s.



PS-0330-1200/
P5-O419-121S
P4-0330-11S5/
P4-0418-1130



P3-O330-1150/
P3-O419-1125

P2-0330-1140/
P2-O419-1115


P1-O33O-1 13S/
P1-O419-111O
S =
1 1°

5 J! ?
fill
° 1 ' J
cf -3 ~
P, - S
, J,


1
' 1
IOuckwaad 1
& Aiolla
Pannywort
(root!


t E
'annywo
taf & att
~ =
JI


1. Hyacinth
(laaf & ttam
1
^^
^^
B



i


i
i
12nd Ecological 1
FluldliadBad
2nd Aaratad
Tank


y
!'
CN
Aaratad Tank
S
•g
]
1
%H
^t!
B



i
-
sj
|
1
o
10
CO
o
09



5

0
CO


CO
r*
O)
c


£



0.
61
1
5
J2
i
O
O
s
co"



o
o

i


o
8
"c


c



2



Z
CN
V
CO
V



IO
V

CO
CN
V


V
*


in



2
f


o
V
m
10
CN
6
V
o"
V



6
V

CN
0*
V


IO
CN
O
V
s


IO
03



t


|,
"8
V
S
V

,.

CN
V

CO
V


CO
CN
O
O


1
CO


f


1
f,
CO
CO
CN
to
in



CO
r>
0

co'


CN
O
s-


8
cn
'i-


f.
f


._
Q.
f,
S
y
V



CN
V

CO
V


«
V
o
8


o
00


2
i



1-
o
o"
V
o
6
V



o
6
V

o
o
V


o
5
V
e


IO



1


fr
p
CN
V
CN
V



CN
V

V


CN
V
f


in



t


*
1
V
IO
y



V

CO
V


V
o


o
CN
*


3
1



u
CO
CN
V
CO
oi
V



IO
CN
V

' CO
CN
V


CN
V
CO


o
o
^ •


2
I


1
•I
CO
IO
o



CO
CO

2


CO
IO
8
09
CN


§
r»


2
1.
-



PS-O330-1200/
P5-0419-1215
P4-O330-11S5/
P4-O419-1130



P3-0330-11SO/
P3-O419-112S

P2-O330-114O/
P2-O419-1115

'. . f
P1-O33O-1 13S/
P1-0419-1110
•< \ 1 3
If 11
3 3 S."
a
* • ^
OJ = J €
" in * 1
J *
-S
1


.1
1
CN
CN



CN

8


*
O
O


§
o
C3
%
CN

"5

E
3
i
f
                                                             I
                                                             I
                                9-19

-------
                                                                             Section 9
9.5    Operations and Maintenance During the Process Evaluation

9.t511—Chemical/Bacteria Additions                                                    .

       Various bacteria  and chemical  additions are  made to  the  AEES process stream
during the course of normal operations.  The purpose  of these additions is to maintain the
bacterial  populations for nitrification and denitrification, and to provide a carbon source and
nutrients to the organisms within the system.  The quantities of  chemicals added to Train B
during the eleven week evaluation are shown in Table 9.6.

                Table 9.6  Weekly Chemical/Bacteria Additions  to Train B
Addition:
Study Week Dates
Weekl
Week 2
Weeks
n/a
Week 4
WeekS
Week 6
Week?
WeekS
WeekS
Week 10
Week 1 1
(1)
(2)
(3)
2/28/95 to 3/3/95
3/4/95 to 3/1 0/95
3/1 1/95 to 3/1 7/95
3/1 8/95 to 3/24/95
3/25/95 to 3/31/95
4/1/95 to 4/7/95
4/8/95 to 4/1 4/95
4/1 5/95 to 4/21/95
4/22/95 to 4/28/95
4/29/95 to 5/5/95
5/6/95 to 5/1 2/95
5/1 3/95 to 5/1 9/95
Bactapur N and XL were dosed
N-2000, XL and Pond KLEAR on
Bacteria "'
150ml
4,250 ml
2,050 ml
300 ml
300 ml
350 ml
2,050 ml
1,650ml
4,250 ml
2,150ml
4,050 ml
5,950 ml
into the system until
May 1 (during Week 9
Carbon
Source (2)
5 Ibs
6lbs
33 Ibs
13 Ibs
15 Ibs
17 Ibs
21 Ibs
13.31
14.1 I
11.21
8.81
10.91
April 30; the
of the study).
Mariah Kelp Meal
Powder
J 00 Ibs131
5 Ibs
22 Ibs
16 Ibs
6 Ibs
7 Ibs
5 Ibs
5 Ibs
5 Ibs
5 Ibs
5 Ibs
5 Ibs
bacteria additions were
Until April 1 4, the carbon source used was sodium acetate; the carbon source was changed
on April 17 (during Week 7 of the study).
The Week 1 addition of Mariah powder was added into
none
3 Ibs
none
2 Ibs
4 Ibs
7 Ibs
5 Ibs ,
5 Ibs
5 Ibs
none
^ 1 Ib
5 Ibs
changed to
to methanol
the Anaerobic Bio-reactor.
                                           9-20

-------
                                                                           Section 9
9.5.2  Sludge and Plant Disposal            !  ,

       As part of normal operation of the AEES, quantities of sludge and plant material are
removed from the system.  Sludge removed is pumped  directly back to Ballanger .Creek
WWTP whereas  plant material is composted on site,  A  log is kept of these activities to
record the residuals quantities being produced as a result of the system operation.

       Sludge is pumped out of the Anaerobic Bio-reactor, the Ecological Fluidized Beds
and the Duckweed Clarifiers.  The sludge volumes removed from Train B during the eleven
week study are shown in  Table 9.7.               ,

                         Table 9.7  Weekly Sludge Removals
Sludge Removed from:
Study Week
Week 1
Week 2
WeekS , ,
n/a
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
Week 10
Week 11
Dates
2/28/95 to 3/3/95
3/4/95 to 3/1 0/95
3/1 1/95 to 3/1 7/95
3/18/95 to 3/24/95
3/25/95 to 3/31/95
4/1/95 to 4/7/95
4/8/95 to 4/14/95
4/1 5/95 to 4/21/95
4/22/95 to 4/28/95
4/29/95 to 5/5/95
5/6/95 to 5/12/95
5/1 3/95 to 5/1 9/95
Total Sludge Removed
(1) 1st, 2nd
and 3rd Ecological Fluidized
Anaerobic
Bio-reactor
3,600 gallons
3,600 gallons
3,600 gallons
4,200 gallons
6,000 gallons
4,800 gallons
10,200 gallons
- 7,200 gallons
3,600 gallons
5,200 gallons
2,400 gallons
2,400 gallons
56,800 gallons
Beds in Train B only.
Ecological
Fluidized Beds111
none
1 ,400 gallons
700 gallons
1 ,000 gallons
1 ,500 gallons
800 gallons
600 gallons
800 gallons
500 gallons
1 ,000 gallons
700 gallons
240 gallons
9,240 gallons

.Duckweed
Clarifier'21
none
• none
none
100 gallons
1 00 gallons
200 gallons
1 00 gallons
100 gallons
100 gallons' "
1 00 gallons
none
75 gallons
875 gallons

(2) Duckweed Clarifier in Train B only. ,- , •'.
                                          9-21

-------
                                                                                  Section 9
         Plant  material is also  removed from various parts of the process.  This  is done in
 order to stimulate growth among the remaining  plants  (consequently increasing pollutant
 uptake), to  reduce  overcrowding of  the tanks', to  remove plants  that  are infected  or
 infested.  Plant material is also removed  because various plants  in the system are grown to
 be sold to outside customers. The quantities of plant matter removed from  Train B during
 the eleven week study are shown in Table 9.8.

                       Table 9.8  Weekly Plant Removals from Train B
 Study Week    Dates
                     Total Mass of
                   Plants Removed'11
                     Locations from which
                      Plants were Taken
Weekl
Week 2
2/28/95 to 3/3/95
3/4/95 to 3/1 0/95
none
93lbs
n/a
1 st, 2nd & 3rd Ecological Fluidized Beds,
 Week3

 n/a


 Week 4


 WeekS
3/11/95 to 3/17/95

3/18/95 to 3/24/95


3/25/95 to 3/31/95


4/1/95 to 4/7/95
 none

19 Ibs


87 Ibs


12 Ibs
 Duckweed Clarifier and High-rate Marsh

                n/a

3rd Ecological Fluidized Bed and D'uckweed
           •  Clarifier             .

  2nd & 3rd Ecological Fluidized Beds,
 Duckweed Clarifier and High-rate Marsh

 3rd Ecological Fluidized Bed, Duckweed
     Clarifier and High-rate Marsh '
Weeks
Week 7
WeekS
Week 9
Week 10
Week 1 1
Total Plants
4/8/95 to 4/1 4/95
4/1 5/95 to 4/2 1/95
4/22/95 to 4/28/95
4/29/95 to 5/5/95
5/6/95 to 5/1 2/95
5/1 3/95 to 5/1 9/95
Removed from Train B
none
50 Ibs
7 Ibs
none
. 199 Ibs
797 Ibs121 -
1,264 Ibs121
n/a ' ,
1st, 2nd & 3rd Ecological Fluidized Beds
High-rate Marsh
n/a
1 st and 2nd Aerated Tanks, 3rd Ecological
Fluidized Bed, Duckweed Clarifier and High-
rate Marsh
1 st and 2nd Aerated Tanks and High-rate
Marsh

(1)      Wet weight.                  .  •                                 ,   .

(2)      795 Ibs of this weight was the plants removed from the Aerated Tanks in preparation for the second
        stage of the study.                                                            •
                                               9-22

-------
                                                                            Section 9
9.5.3  Abnormal Operations and Modifications

       During the course  of  the  study, events  occurred  that might have affected the
"normal" operating conditions of the AEES.   Ail of these events were recorded by the
Parsons ES field team and are presented in Table 9.9.

       In situations  where these operating  abnormalities might have affected the study
data,  this fact was  recognized and spurious data points were noted and  removed.  For
example, on March 7 an  operating  mishap resulted in 600 gallons of sludge being pumped
into the system  before sample location  W2.   This  event adversely affected the  data for
points W2 and W3 during this week of the study  (Week 2), so these points were removed
during data manipulation (Section 9.2.1).
                                           9-23

-------
                                                                                              Section 9
       Table 9.9  Abnormal Operations and Modifications that Occurred During the Study
 Date
Event
 March 1              Influent flow to the Anaerobic Bio-reactor was off between 0930 and 1030.
 March 7              A mishap occurred during sludge removal from the Anaerobic Bio-reactor, resulting in
                      approximately 600 gallons of sludge being pumped into the system after the Anaerobic Bio-
                      reactor (before sample point W2).
 March 10            One of the three Air Blowers was repaired (this blower had been inoperative since the start
                      of the study). The repair meant that system aeration would now be increased.
 March 10            Approximately 600 gallons of mixed liquor from Ballanger Creek WWTP was added to the
                      1st Aeration Tank of each train to seed the system.
 March 10            Approximately 300 gallons of solids were recycled from the 3rd Ecological Fluidized Bed to
                      the 1st Ecological Fluidized Bed.
 March 17            Influent flow to the Anaerobic Bio-reactor was shut off owing to contractors at Ballanger
                      Creek WWTP damaging the inlet line.
 March 20            Inlet line was repaired, allowing flows into the AEES to resume (this shutdown resulted in
                      scheduled sampling being suspended for one week).
 April 7               A quantity of iron filings were added into the Anaerobic Bio-reactor to induce phosphate
                      precipitation.     .
 April 10              Influent flow to the Anaerobic Bio-reactor was off between 0700 and 1000.
 April 11  .            Influent flow to the Anaerobic Bio-reactor was off between 0400 and 0700.
 April 17              Methanol was substituted for sodium acetate as the carbon source for the process.
 April 17             A flushing valve to the Anaerobic Bio-reactor was discovered to be malfunctioning. This
                     situation was thought to have existed for up to one month and it had resulted in blockage of
                     one third of the inlets pipes to the Bio-reactor.  The valve was subsequently repaired.
 April 17             Plants in the Aerated Tanks were cut back.
 April 24             Half of the shade cloth was placed on the roof of the greenhouse.
 April 26             Influent flow to the Anaerobic Bio-reactor was off between 0830 and 0940.
 May 1                The second half of the shade cloth was placed on the roof of the greenhouse.
 May 10              At 0800, the 1st Aerated Tank (Train B) overflowed owing to plant matter blocking the
                     outlet pipe.  The blockage was later cleared.                              ,
 May 18              All of the plants (hyacinth and pennywort) were removed from the Train B Aerated Tanks in
                     preparation for the second part of the study.
June 14             Influent flow to the Anaerobic Bio-reactor was off between 1030 and 1200.
June 15             3rd Ecological Fluidized Bed (Train B) was changed to aerobic operation. This filter had been
                     operating anaerobically since the start of the study.
June 17 to 18        Influent flow to the Anaerobic Bio-reactor was off for approximately 24 to 36 hours, owing
                     to clogging of the  influent pump at Ballanger STP.
June 17 and 18       Each of the Ecological Fluidized Beds were backflushed for 24 hours each.
June 20             At Parsons ES' request, 3rd Ecological Fluidized Bed (Train B) was changed back to
                     anaerobic operation to maintain process continuity for the study.
                                                     9-24

-------
                                      Section  10
                              Hydraulic Detention Times
  10.1   Introduction
       , The actual hydraulic detention times of the AEES components were calculated using
 the data obtained during the tracer study (Section 5). This section summarizes the results
 of this study and explains how the HDTs were calculated.  All of the raw data from the
 tracer study is presented in Appendix D.           ,

 10.2  , Tracer Study Results                                                       /

        In most  simple flow systems, where there, are few branches  and no recycling, the
 concentration of the tracer  compound measured at a given point will begin to rise sharply
 after injection.   The "compound  will then attain a peak concentration  that will begin to
s decrease  sharply at  first,   gradually  becoming  less  severe over  time.    Plotting  the
 concentration of the tracer compound detected  over time will, yield a  plot such  as that
 shown in Figure 10-1.
                                       Figure 10-1,
                              Tracer Study to Determine HDTs,
                             . Location: Across High-rate Marsh
     0.00
       9:00   11:00  13:00   15:00  17:00
                                        21:00   23:00

                                            Time
                                                    1:00
                                                              5:OO
                                                                    7:00
                                                                         9:00
                                                                               11:00 '
                                             10-1

-------
                                                                            Section 10
        The above graph shows the data from the tracer study of the High-rate Marsh at the
 AEES.   Following  the  completion  of  the  tracer study, data  had  been obtained  that
 characterized the flows throught the various system components of the "Living Machine".

        Using this graphical data, calculations were carried out to  establish the actual HOT
 of each system  component.  The method used to determine this information is desbribed
 below.

 10.3   Calculation of Hydraulic Detention Times

        The  actual  HOT  of the  lithium  chloride  through each  system  component was
 calculated in the following manner:

 1.     The time at which the tracer material was first injected  was  identified.   This
        established the zero-time benchmark for that sample location.

 2.     The HOT is defined as the x-axis ("time" axis) coordinate of the centroid of the area
        under the curve.  The  "centroid" of the area under the curve is the area's geometric
        center.

 3.     The first  step of determining this x-axis coordinate is to find the partial area  under
        the curve between two data points and applying the concept of discrete integration.

 4.     The area  beneath the curve between two points is estimated by assuming a straight
        line between the two  points  and finding the partial area of the region as though  it
        were a true trapezoid.  A small  amount of  error is introduced here since the actual
        function defining the concentration over time is, more than  likely, not a straight line;
        between  any two consecutive  points.  However, the  closer the data points are
        together, the less error is introduced.              .

 5.      After the entire curve is separated into discrete  "smaller"  areas, the moment arm
        about the y-axis for  each smaller area is computed by finding the distance from the
        y-axis to the  midpoint of the smaller area.

 6.      The problem  is then solved, borrowing from statics, using the following equation;

                                 Cy = Z[M.xd(A)]/S[d(A)]

        Where:       Cy    =   Centroid of time {x-axis centroid coordinate)

                     M    = •  Moment arm distance of each d(A) from the y-axis

                     d{A)  =   Partial area under the curve  between each two
                                consecutive data points

       The difference  in  hours between the time of lithium  chloride injection  ancl the
calculated  x-axis  centroid  coordinate  is,  therefore, the actual  HOT of that  system
component.
                                            10-2

-------
                                                                              •Section 7O
                  Table 10.1  Actual and Theoretical HDTs for the AEES
System
Component
Anaerobic Bio-reactor
1 st Aerated Tank
2 Aerated Tanks
1st Ecological Fluidized
Bed
Time of Injection
(date/time)
5/9/95 @ 10:30
5/2/95 @ 9:30
4/25/95 @ 10:00
4/24/95 @ 10:00
Calculated Centroid
(date/time)
5/1 0/95 @ 4:58
5/2/95 @ 1 8:57
4/26/95 @ 6:57
,4/24/95 @ 15:04
Actual HDT
(hours:mins)
•, 18:28
10:52
,20:57
6:15 ,
Theoretical HDT
(hours:mins)
18:30
8:30
17:00
7:00
3 Ecological Fluidized
Beds
6/20/95 @>10:00   6/21/95 @ 10:55
24:55
21:00
Duckweed Clarifier
High-rate Marsh
4/1 2/95 @ 9:50
4/4/95 @ 9:00
4/12/95 @ 22:02
4/4/95 @ 1 9:24,
12:12
10:24
8:30
9:00
TOTAL HOT
           121
                                                             86:56
                74:00
(1)      Theoretical HDTs were calculated by OAI and are based on a flow of 37,000 gpd into the Anaerobic Bio-
        reactor, and 13,300 gpd into train B.                    X ,-'..-.
(2)      The total HOT is calculated by adding the HDTs of the Anaerobic Bio-reactor, both Aerated tanks,  all
       .three Ecological Fluidized Beds, the Duckweed Clarifier and the High-rate Marsh.

        The calculated HDTs  for the various individual process components of the AEES are
shown  in Table 10.1.   It is apparent from  this data that  most  of  the detention times
determined  by the tracer study are within 1 to 3  hours of the  theoretical  times.   The
exception to this, among the individual units measured, is the Duckweed Clarifier which has
an actualHDT of 12 hours and 12 minutes; 3 hours and 42  minutes above the theoretical
HOT. With respect to the totalsystem detention time, the estimated HOT of the system  is
approximately 3Yz days whereas the theoretical. HDT is closer  to 3 days.

        Calculations  were also performed to estimate the percentage  recoveries of lithium
chloride in each part of the  tracer study.  These were done  as a test of the  tracer study
accuracy since,  a suitably substantial recovery (approximately 9Q%) of lithium is typically
required to make the test valid.  A summary of the lithium percentage recoveries is provided
in Table 10.2.

        AH  but two of the calculated recovery percentages was in excess of  100%.   The
excess  was attributed to  analytical variability  and so  it was still considered that the lithium
recovery was satisfactory to validate the tracer study results.   The study  ort the three
Ecological Fluidized Beds  and the,single Ecolqgical Fluidized  Bed yielded .lithium  recoveries
of 90% and 88%, respectively. .These percentages are considered sufficient to validate the
calculated HDTs, however, the less-than-tptal recoveries might suggest that the  calculated
HDTs should be  of slightly longer duration than the tracer study showed.
                                             10-3

-------
                                                                                     Section 10
               Table 10.2   Percentage Lithium Recoveries for the Tracer Study
             System Component
Percentage Recovery of Lithium
             Anaerobic Bio-reactor

             1st Aerated Tank

             2 Aerated Tanks

             1st Ecological Fluidized Bed

             3 Ecological Fluidized Beds <2>

             Duckweed Clarifier

             High-rate Marsh
              > 100%

              >100%

              >100%

               88%

               90%

              >100%

              >100%
(1)      Occurrences where the lithium recovery is in excess of 100% is attributed to analytical variability.

(2)      The first time this sampling location was tested, the lithium recovery was only 65%.  This was attributed
        to an instance when sludge was pumped out of the Ecological Fluidized Beds during that part of the tracer
        study.  The  tracer study of the three  Ecological  Fluidized Beds was subsequently repeated  and a
        sufficiently high recovery was attained.
                                                 10-4

-------
                                     Section 11
                Comparison of Study Data with Ocean Arks' Data
 11.1   Introduction   .                                              -;  •

        In addition to the water quality sampling carried out by Parsons ES during the study
 period, sampling was also  performed, by OAI staff at the AEES.  The samples collected by
 OAI were analyzed  both at the OAI  on-site  laboratory and, at a local  certified laboratory.
 Potentially, this additional  data could be used to increase the size of the data set for the
 process performance evaluation if it was found to be statistically similar to the Parsons ES
 study data.                  -     ,  .
                /               -          -                  -         ••!
        Consequently, parametric statistical testing was performed on all three sets of data
 to assess their statistical similarity.   In addition, a simple visual comparison  of the data's
 summary statistics  was also performed.  The details of these comparisons are described in
 this section.

 11.2   Comparison of Data Sets                  ••   ~

 11.2.1' Statistical Comparison  of Data

        After  data  manipulation  and statistical assessment  (Section 9,2.1),  parametric
 testing  was carried  out on the study data. The data from OAI were not altered in any way
 before this "testing  since it was assumed that any necessary data manipulation  {such as".
 removal of  spurious data or statistical, outliers) would  have  been  performed by OAI
 themselves.                .                                               *
               '   '    '    ••'..-'/         .    •            • .         • f    •     ~
        Two-tailed T-tests (which assumed equal variances between the study data) were
 the  parametric  tests  performed  on  the data.   These  tests  generated a  factor  that
 represented the probability  that the twp data sets tested had come from populations having
the same mean, therefore  indicating the statistical similarity of the  data.  Since not all of
the Parsons ES and OAI data were collected on the same date and time, this  T-testing
 assumed that there  were  no significant variations between  these data owing to  different
sample  dates  and times.  To  verify this assumption, as well as  T-testing all  of the study
data, tests were also carried.out that  only examined the data that were taken on the same
days. The results of these T-tests are shown in Tables 11.1 through  11.7.

       The two-tailed T-tests performed on  the data showed similarities and differences
 between the  various Parsons ES study data,  and the  data generated at OAl's on-site and
certified labs.  Assuming that a T factor of 0.5 (50% probability that the data are similar) is
reasonable, 11 out of the 30 data sets compared between Parsons ES and the OAI on-site
lab were statistically similar. Comparisons-between Parsons ES' and the OAI certified lab's
data showed  that 7  but of 12  of the sets  were similar (using the 0.5  T factor).   The
parameters that display the best similarities  between laboratories, are TSS,  TKN, ammonia
and total phosphorus.      ,          -  '
                                            11-1

-------
                                                       Section 11
Table 11.1  T-test Results for Total Chemical Oxygen Demand

Laboratory
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ESVs OAI Certified Lab
Parsons ES vs OAI Certified Lab
Table 11. 2

Sample Location
Wt
W2
W3
W4
W6
W1
. W6
T-test Results for Total
T-test
All Data
0.211
0.034
- 0.000
0.256
0.334
n/a
n/a
Suspended Solids
Result
Same Day Data
0.339
n/a
0.012
n/a
0.443
n/a
n/a
•' ' .
T-test Result
Laboratory
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
Table 11.3
Sample Location •
W1
' W2
W3
W4
W6
W1
W6
T-test Results for Volatile
All Data
0.502
0.512
0.459
0.645
0.134
0.192
0.059
Suspended Solids
Same Day Data
0.132
n/a
0.857
n/a
0.470
n/a
n/a

T-test Result
Laboratory
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
Sample Location
W1
W2
'W3
W4
we
.W1
W6
All Data
0.265
0.543
0.338
0.559
0.251
0.140
0.000
Same Day Data
0.090
n/a
0.494
n/a
0.871 ',
n/a
n/a
                           11-2

-------
                         Section 7 7
Table 1 1 .4
T-test Results for Total
Kjeldahl Nitrogen

T-test Result
Laboratory
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAlSite Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
'.-':"• table

Laboratory
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
Sample Location
W1
W2 , ' •
, W3
W4
W6
W1
W6
11.5 T-test Results for

Sample Location
W1 -
W2
W3
W4
W6
W1
W6
All Data
ji/a ,
n/a
n/a
n/a
n/a
0.615
0.857
Ammonia
• ' _-' T-test
All Data
0.627
0.506
0.159
0.482
0.126
0.708
0.857
Same Day Data
n/a
n/a
n/a
n/a1
n/a
n/a
n/a

Result
Same Day Data
: 0.567
n/a
0.131
n/a
0.906
.n/a
n/a
Table 11. 6 T-test Results for Nitrate
Laboratory '
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
Sample Location
wi
W2
W3
W4 • .
W6
. ' WI
W6
T-test
All Data
0.042
' 0.000
O.O64
0.144
0.277
0.016
0.916
Result
• Same Day Data
0.038
n/a
0.189
n/a
. 0.820
n/a
n/a
11-3

-------
                                                                         Section 11
                      Table 11.7  T-test Results for Total Phosphorus
 Laboratory
Sample Location
       T-test Result
All Data       Same Day Data
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Site Lab
Parsons ES vs OAI Certified Lab
Parsons ES vs OAI Certified Lab
W1
W2
W3
W4
W6
W-1
. W6
0.429
0.699
0.726
0.840
0.735
0.831
0.617
0.165
n/a
0.589
n/a
0.596
n/a
n/a
        For the data taken on the same days, the probability of similarity increased in 10 out
 of 18 cases (and decreased in the remaining 8 cases).  Only in 4 of the 10 cases where
 there was an increase in the probability did the T factor change to suggest that the  data
 were similar.  The parameters  showing the best similarities in this case were ammonia and
 total phosphorus.

        Therefore, although the testing indicated some similarity between the data, it was
 Inconclusive with respect to showing total statistical similarity or dissimilarity between the
 laboratories and sampling methods used in this study.

 11.2.2  Simple Comparison of Data                                                    ,

        Following the inconclusive results of the statistical  comparison of the data, a less
 complex  method was  chosen to  perform  a  general  comparison  of  the  study data.
 Descriptive statistics (mean, median, standard deviation, and  variance)  were generated for
 the individual data sets and a "visual" comparison of these parameters was performed.  This
 method involved looking at the descriptive statistics and making an informed judgment on
 their similarity based upon knowledge of reasonable laboratory error and sample variability.
 Although  subjective, this comparison was thought to be appropriate for identifying whether
 the  data  sets were  really as dissimilar as the T-testing had  suggested.  The descriptive
 statistics for the Parsons ES and the OAI data are shown in Tables 11.8 through 11.14.

       This comparison of the study data revealed that, despite the results of the T-tests,
 the Parsons ES data and the OAI data were actually quite similar. For example, T-tests of
the total COD data for sample location W1  did not indicate similarity between the data  sets
 (T factor of 0.211) but the descriptive statistics did show some similarity (10% difference
 between means, 2%  difference between standard deviations).  Comparable  cases can  also
 be observed for a number of other parameters at various sample locations.

       Based on these comparisons, it is considered that the Parsons ES data and the  OAI
data are not as different as the T-testing implied.  This is not surprising since analytical and
sample  variability will inevitably lead to  discrepancies  between  data which may be
interpreted by the T-tests to be a result of greater differences than they actually are.
                                            11-4

-------
                            Section 7 7
Table 1 1 .8 Descriptive Statistics for Total Chemical Oxygen Demand
Laboratory
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Table
Laboratory.
Parsons ES f
OA Site Lab
OA Certified Lab
Parsons ES
OA Site Lab \
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES •
O A Site Lab
OA Certified Lab
Sample
Location
W1
W1
W2
W2
W3
W4
W4-
W6
Vi/6
Mean
1,307
1,193
445
377
399
292
73.4
59.8
53.2
42.3
Descriptive Statistics
Median Standard Variance
Deviation
1 ,290
1,109
429 ,
368
415
275
60.8
53.0
58.4
35.0
1 1 .9 Descriptive Statistics for Total
, Sample
Location
W1
W1
W1
W2
W2
W3
W3
W4
. W4
W6
W6
W6
Mean
470
536
564
78.0
84.0
148
143
9.9
11.4
3.5
2.2
1.8
243
240
76.1
80.9
81.4
58.5
39.1
25.9
33.0
26.8
Suspended
59,147
57,337
5,796
6,552
6,632
3,424
1,530
673
1,089
721
Solids
Descriptive Statistics
Median Standard Variance
. Deviation
' 493
530
.535
82.1
85.0 ,
152
142
.9.6
10.0
2.0
1.7
1.5
136
1 50
175
22.6
25.1
36.2
33.9
6.3
7.0
2.4
- 1.4
1.2
18,602
22,490
30,475
513
.628
1,313
1,150
40 .
50
.6
2
2
Count
11 •
21
10
21
10
18
10
21
11
19

Count
10
, 21
11
10
20
10
18
10
21
9
18
11
11-5

-------
                           Section 11
Table 11.10 Descriptive Statistics for Volatile Suspended Solids
Laboratory
Parsons ES
OA Site Lab
OA Certified Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
OA Certified Lab
Table
Laboratory
Parsons ES
OA Certified Lab
Parsons ES
OA Certified Lab
Sample
Location
W1
W1
W1 .
W2
W2
W3
W3
W4
W4
W6
W6
W6
Descriptive Statistics
Mean Median Standard Variance
Deviation
364
410
442
64.0
69.0
122
112
6.3
7.3
2.3
1.8
• 1.2
11.11 Descriptive
Sample
Location
W1
W1
W6
W6
Mean
55.9
54.2
8.4
7.9
362
410
425
60.7
71.5
121
106
• 5.0
7.2
2.0
1.3
1.0
Statistics for
96.4
108
131
20.7
20.9
,. 30.8
25.6
5.5
4.0
0.5
1.3
0.5
Total Kjeldahl
9,284
11,555
17,041
426
436
948
657
30
16
0
2
0
Nitrogen
Descriptive Statistics
Median , Standard Variance
Deviation
58.4
54.2
5.0
5.4
7.1
8.8
7.0
6.7
50.3
77.9
48.6
44i4
Count
10
21
11
10
20
10
19
10
23
9
17
11

Count
11
11
11
10
11-6

-------
                           Section 77

Laboratory
Parsons ES •
OA Site Lab
OA Certified Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
OA Certified Lab
• * '~ • • i
Laboratory
Parsons ES
OA Site Lab
'OA Certified Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES '
OA Site Lab
Parsons ES
OA Site Lab
OA Certified Lab
Table 11.12
Sample
Location
W1
« ' "
W1 ;
W1
• W2 • .
W2
W3
W3
W4
W4
W6
W6
W6
Table 11.13
Sample
Location
W1
W1
W1
W2
W2
' W3
W3
W4
W4 ;
W6
W6
W6
/Descriptive Statistics for Ammonia
Descriptive Statistics
Mean Median Standard Variance
Deviation
25.6
26.3
26.2
33.8
35.1
28.0
30.2
7.5
5.9
5.5 .
2.5
6.0
Descriptive
25.1
25.9
24.9
33.8
35.0
28.1
30.3
4.4
4.1
2.6
0.4
3.3
Statistics
4.2
3.1
' 2-8
5.9
4.8
4.6
3.8
6.6
5.9
6.3
4.0
6.1
for Nitrate
17
10
8
35
23
21
14
44
34
39
16
37

Descriptive Statistics
Mean Median Standard Variance
Deviation ,
0.2
1.3
0.1
0.1
1.3
0.4
0,7
10.5
14.1 .
5.4
, 8.0
5.2
0.1
0.8
0.1
0.1
1.1
0.3
0,7
9.0
12.0
5.7
7.3
5.3
0.1
1.8
0.1
0.1
0.5
0.2
0.4
^6.9
6.5
5.2
6.4
5.1
0
3
O
0
0
0
0
47
42 ,-
27
41
26
Count
11
2O .
11
10
21
10
20
11
21
11
18
10

Count
11
21
11
10
21
9
20
11
23
10
20
11
11-7

-------
                                                       Section 11
Table 11.14  Descriptive Statistics for Total Phosphorus
Descriptive Statistics
Laboratory
Parsons ES
OA Site Lab
OA Certified Lab
Parsons ES
OA Site Lab
Parsons ES
OA Site Lab
Parsons ES ,
OA Site Lab
Parsons ES
OA Site Lab '
OA Certified Lab
Sample
Location
W1
W1
W1
W2
W2
W3
W3
W4
W4
W6
W6
W6
Mean
13.6
12.9
13.8
8,2
8.0
8.5
. 8.4
7.0
6.9
6.8
6.7
7.0
Median
13.4
12.4
13.8
8.4
8.0
8.2
8.2
7.1
6.8
6.9
. 6,6
6.6
Standard
Deviation
2.2
2.2
2.7
1.5
0.9
' . 1.2
1:.0
0.8
0.8
0.8
0.8
1.0
Variance
,. 5
5
7
2
1
1
1
1
1
1
1
1
Count
10
21
11
10
21
9
20
10
23
11 ,-, .
20
11
                          11-8

-------
                                     Section 12
                    Investigation of the System Without Plants
 12.1   Introduction                            .

        At the request of USEPA, an additional investigation was performed on the AEES to
 determine the extent to which  the plants  in the  Aerated  Tanks affected the process
 performance of the system.  This study was carried out over a three week period before
 which all of the plants (water hyacinths and pennywort) were removed from the Train B
 Aerated Tanks.   As  with the  main process performance  study,  composite and  grab
 wastewater samples were  collected from the system during the study period.  Information
 concerning the methods and results of this investigation is presented below.  The raw data
1 for this section is presented in Appendix E.

 1,2.2   Wastewater Sampling

 12.2.1  Sampling Locations             :

        The wastewater sampling  locations used for this part of the study were the same as
 those used in the eleven week study.  The locations of these sample points may be found in
 Table 4.1 and Figure 4-1.

 12.2.2  Sampling Methods

        As in  the  previous stage  of the study, time-proportioned,  composite  24-hour
 wastewater samples were collected for the study duration using ISCO automatic samplers.
 The samplers were located  at the  sampling  locations identical  to  those described  in
 Section 4.2.1.   One sample was collected from  each  location every  week  for the three
 week duration of the study. The same sampling, cleaning, and maintenance protocols were ,
'followed as was used for the eleven week process performance evaluation (Section 4.3.1).

       The wastewater grab samples collected  for field analysis were  also collected in an
 identical manner to those gathered for the process performance study (Section 4.3.2).

 12.3  Analytical Procedures and QA/QC  '"••'-                    '

       Identical field and laboratory  analyses were  performed on the saroples collected
 during this part of the study as were carried out during the process performance evaluation
 (Section 6).   The  QA/QC procedures and  requirements were also  identical to those
 previously used (Section 7).

 12.4  Process Performance Without Plants

       This part of the study yielded three  weeks  of  water  quality  data  by which the
 performance  of the AEES without  plants could be assessed.   Sample collection  and
 laboratory  analysis   went ahead  without incident for  this  part  of the study  so data
                                           12-1

-------
                                                                           Section 12
 manipulation was not required.  Additionally, detailed statistical analyses of these data were
 not performed owing to the small sample size; it was considered inappropriate to identify
 outliers from a sample size of three samples.  Simple summary statistics were calculated,
 however.   The  mean  water quality data for the three  week evaluation of the process'
 without plants are presented in Table 12^1.                                         .

        As before, treatment efficiencies were calculated for the overall process as well as
 for the individual process components of the  AEES Facility.   This  was done using the
 equations  detailed   in  Section 9.3.   The  calculated  efficiencies  are  summarized in
 Table 12.2.

 12.5   Comparison to Process Performance With Plants

        The data generated during the three week process evaluation (without plants)  were
 then  compared with that from the eleven week evaluation (with plants). Owing to  the  small
 sample size  from the three week study,  statistical comparison of the two data  sets was
 considered to  be inappropriate  as  it would  not yield conclusive  results.  Therefore, the
 comparison was limited to using graphs to visually contrast the data.,

        Figures 12-1  through  12-12 show how the various water quality parameters are
 reduced throughout the AEES, with and without plants in the Aerated Tanks.  The standard
 deviations  of the data are  also displayed on the graphs to show the variability of the data
 sets  and to  provide an indication  of the true  extent to which the the data points are
 "different".                                     .     •     .

        For the parameters COD (total and soluble), BOD (total  and soluble), TSS, VSS, and
 phosphorus (Figures 12-1 to 12-6,  and  12-10), there does  not appear to be a significant
 difference between the process with and without plants in the Aerated Tanks.  Neither is a
 significant  difference apparent between the parameters for pH  and  DO (Figures 12-11  and
 12-12).

        However,  there do seem to  be  some differences  between the  graphs for  TKN,
 ammonia, and nitrate (Figures 12-7  through 12-9).  Both TKN  and ammonia in the system
 effluent are lower, and nitrate is higher, when the system is operating with  plants in the
 Aerated Tanks.  This suggests that  nitrification may be more effective when the plants are
 present in the system.   The lower  nitrate levels in the effluent from the system without
 plants would seem to be a result of the reduced nitrification upstream, rath'er than improved
 denitrification in the latter part of the process system.

        However, these differences could be regarded as  slight  when the closeness and/or
 overlap of the standard deviations are taken into account. Additionally, the differences for
these parameters are  most marked downstream of the 1st Ecological Fluidized  Bed  whereas
the plants were removed upstream of that process component.

        None of  this  is to say that there is no difference at all between the performance of
the AEES with and without plants. Additional water quality data would be required in  order
to observe  more subtle differences between the two modes of operation.  What this part of
the study appears to have demonstrated is that no major differences are apparent when the
 process is operating without plants in the Aerated Tanks.                    ,
                                            12-2

-------
      Ij

      o
      to z
      m <
      S-
CM
(0
      CO

      >
     a:
     ui
         o
         <











co
CO
Q
j^
75
O
2
CO
c .
cc
0)












j:
u
s !
o S
S c
I23
cs
™
*
=5
1,1
•5 £
jO **-

U QQ
I
8 •
s „
1 1
± ••§
a c
J ffl
A .
S
.2
d tank Ef
V
£
V> '
%
S
bic Bio-r
Effluent
.0
i :
c
o
r
—

1 o
' O
CO
i
CO
^




1





ITS




i



S-





i


M
• ' . -''S




•*••
' ' S'
CO
Q.

CD
co
CM




CN
CO
in





cri




CO
CO
CO



co
d




co
CO
o
CM
*~


£




Q
J
5
3
CO
IS.
CM




CO
cn
CO





CO
in




CM
'CM
co



O
d
cn





en



O)
E




£)
J
5,
"5
CO
a
'"*




a





CO




O
co"
en



CO
in





CD
co



£




to
D
CQ
3
O
*




CO
en





'£




CM
cn



O
cri
CO





q
en



E




10
a
5
D
o
CO
en
CM




CO
CO





CO




q
CM



in
o





q
cn
in



E
CO
•5
~o
CO
•a
•§
c
Q.
co
a
5 .
0

X
O
-o
CO
"o
CO
CO
O
13
CO
r>
CN
CN




tn
CN
CN





m
CM




CO
CM



CO
CM





q
CM



o
o

3
CO

-------
o


0)

25
ca
O

£

CO
1U
UJ  CO

<  £
CC  <

S  -

CO  5
LU  o

O  I


ii
o  >
ii  t
u.  -i
     b  s
     <  b
     LU  <
     CC  Uj
     O
     Q.
                                                               
0
E
£
. .
c
2

0
Q.
—
CO
1
O
                                                              r-  CM  n
                                     12-4

-------
    w
    4-»

   _ro

   o.


    5
    o
    c;
 .
3
i    .
 0)  -g

 E  |
 -M  QJ
 <0  JC
 w
   >/ * •
    1_

W £

II
 C  (o
 o  >-
 CO  CB
-c: Q.
 (0
 Q.



I  '
                 CO
                 +-I


                 _to

                 Q.
              3

              O
              J=    JC
                      c
                      eg
                      Q.
O
O
O
"CD
+-*

£



.f
Q
O
O


2
o


I
•fl
I
                                                               H3?
                                                                        m -C  C
                                                                     CO  i- W   o a 3
                  > o .N q=
                    LU 5 -ft
                                                                            .  q=

                                                                            2 JS
                                                                            3
                                                                   •»«
                                                                  . _c

                                                                   'o
                                                                   Q.


                                                                  -JS'
                                                                   Q.

                                                                   E
                                                                   CO
                                                                       -a  3

                                                                         •
                                                                       0)
                                                                         •
                                                                         III
                                                                         Q) tO -^'
                                                                         I °S
                                                                         < CQ
                                                                       a>
                                                                       1 s
                                                                      '
       o
       o
       CO
                               o
                              .0
                               o
                       o
                       o
                       00
                        o
                        o
                        CD
O
o
o
o
CM
                   (l/Bai) pueiuaa uaBAxo
                                            12-5

-------
a,
    CO
    4->


    JS
    D_
        <
    1  I
    CO  O)

       s
       S
    E  ^
    CD  Q
   CO  JI

   *o  o

    c  E
    O  (0

   •8  SB
    CO  O_
    Q.


    O
   O
c
co
Q.
+-•
ZJ
o
I
Q
O
O
03
£1
=3
O
CO
i

C/3
•£
_CO

_£.
|
o
o
o
_0>
o
3
0
CO
I
u
1
                                                                                    <5 -c- c
                                                                                 CO  >••  «0  (1)
                                                                                 ^^  1  k*  "^
                                 £0 T3
                                 O 0)
                                 '5 o°  £
                                 .2 -a  »
                                 o w  3
                                 o .H  5=
                                 in is  g:

                                 -gl^

                                 CO "•
                                 re  "D
                                 _o  a)


                                 .2  "a  S
                                 o  w  3
                                                                                   2c
                                                                                   |2

                                                                                   T3
                                                                                   0)
                                           «£
                                           Q.


                                           CO
                             £  S
                    «  5 ^
                   ^  t> i

                    w  w ^
                    re  V a-
                    = .o uj
                   < 03
                                                                                   a>
                                                                                   O)
                                                                                   re  4->

                                                                                   re
                                                                                  tr
o
o

                                      §
                                      CO
§
CM
8
                         (l/Btu)  pueiuaa uaBAxo
                                                   12-6

-------
   .5
    o
    *  I
   •.C  X
      o
c?
£ J= ;|'
3 to'  O
Q» P .P
    O
w

co
s-
o
       Q)
      -g
   *C (0
   co a.
   a.

   o -
   O
                    (I/Bui) puBuiaa ueBAxo
                                        12-7

-------
     O
     4-»
     JO
     Q. 13
     +-  s
     3  2
     o  R

        1
         3
o>
2.
3
    (0
.
U.  I-

    E
    Q)
    CO
    H-
    o
   11
    co  co
    Q. Q-

    O
   O
                      OT



                     I    I
                     •>->    co

                      g    *
                     .c    j=
                    in
                    Q
                    O
                    00
in
Q
O
03
                     O    O
                    5    3
                    .5    .2
                     o  '  o
                    1
                           1
              o
              o
              CO
                        o
                        in
                        CN
        o
        o
        CN
o
in
                        (1/OlU) PUBUI9Q
                                                     |BOILU9llOOig
                                               12-8

-------
IT)

CNI
   'I
    _eo
    a.

    .•i-i

    o
    •a
    c
c  ^ •

c ^O

to 1§
    o  a?
    c
    o
    (0
    a.


    o
   O
£

J2
a.

£
03
CO
                            (I/Bui) spijos pspuedsns
                                         12-9

-------
   I
   JO
   0.
   4-»
   o


   i*
     ,0
   •a C/D


  ±i  c:
fl3  C

5  S
  <* E
  t CD
   ca
   a.


   o
  O
                      (I/6iu) spijos papuedsng
                                 12-10

-------
 I
  O
 o  ^
 -  §
 (0

K  S §:



-If
Q)  C _Qj

3  to 5^
o>  2 ^
il  h- S
 o

 to  il
 >•  0)
 c
 o
.J2

 CO
 Q.


 O
O
    to
                                                                                   I

                                                                                   _a>
                                                                                   a.

                                                                                   |
                                        12-11

-------
     V)
     •*->


    J2
    Q_

     4-*


     O
    •o
       -
CO
 2  !  -
 3  CO  o

.2> 2 -S
u.  I-  E

    E  2
    0)  CO

    to °-
    >.
    CO
    H—
    O

    c
    O
    CO
    *c
    CO
    Q.


    O
    O
                                                                                     £
Q.

E
CO
                                (M-l/Bai) eiuouiLuv
                                          12-12

-------

















0
1
CM
t—
0)
1_
.i
LL

























CO
£
(0
Q_
3
o
.1± .
•a
c
CO

5 5»
J|

o __ • -

II:
E-£
OJ Q_

CO
CO
0
C
0
co
*C
CO
a.
o
O






~ ' ' — '•' - • . - "' '
CO -• .•'.'"•
C 1 .-i *.
TO CO ' /"
Q- c .-./•/
• +•• CO- i • / /
i ^ •/. /
•C ^ / /

5 ^ / /
• ~^ . — • , . • ., " 1
•2 '*••''" ' •'.-'- /

4-» -M - , . ' \ 1
* Z, \
1 ' \ \
i --T, •-•-.. \ \
'' - \ \
\
' \ \
• - I-^BC
.'••••''' , \
'.' - ' -.''••: " . \
• '- ' - '
- - . -'",;. 1
.-...'•'-.' ' " . '
•
', ,
•"'••'•• " ' ':''
"- - •

' ' t

• ' •




•.''"•'' '

' | " ' .•_''•;•'_... • . <


 '


»

15 -o
.U 0)
'5 °° ^
5 "5 w §
> 0 .£J 5=
UJ -n «^
••of"1
«=.
To "o
, ** ^2
O) na ^
"5 — "S ®
>• O 0> 3
UJ ^ **•
^w E


c •
n -o § - •-
^i£

• • <.
.

o *~
CNlll
> Q3 03 3
> re "r 5:
< s m

.
03
O)
CO +J
CO .
cc
0 0 0 0 0 0
m 5f co CM «-


















'o
0.
0)
Q.
E
CO


















(N-I/6UJ)
        12-13

-------
CM
    t=
    CO
    CL
    •*->

    o
    Jd
    ra jo
    *  8-
                         CO

                     §   ^
1   1
Q.   Q.

]S   ]§

£   £
                    I
o  -S
»_  ••»  • •
J=  tD  i—
3  Q  Q)
u.
    E
    ^  (0
    CD  £
    c
    o
    CO
    Q.



    O

   O
                                                                             52 S>
                                                                          to TO
                                                                          o o>
                                                                          BCQ, £
                                                                          J2 -a g


                                                                          !«§!
                                                                          •
                                                                         rTo T)
                                                                         _O OJ
                                                                         ---0 S
                                                                         s «i
                                                                         21S
                                                                         (0
                                                                                   .2
                                                                                   Q.

                                                                                   E
                                                                                   (0
                                                                                   w
                 00    
-------
     1
      «
     a.
     •4->

      O
     c
     (0
T- -      Q.
r-      -
»=   co
5:2
   :
     CO

    CO
     c
     o
    .J2
     CD
     a.

     o
    O
          O
          c,
         -
                        CO


                        _co    *eo

                        Q.  '  "c
                        <4->    CO

                       •§•   *
                        -C    .C
                       X    X
                       Q.    a.
                       cu
                       LL

                       f
                             iZ
                                                                                              CO  »-  O}' Q>

                                                                                              ^ "01  J  "^
                                                                                                 ^     iS
                                                                                                 -C
                                                                                                  to
                                                                                                  o
                                                                                                 '
                                                                >  O    O'.N 5:
                                                                   m 2 £
                                                                   •S 5.
                                                                   co u.
                                                                                                 co -a
                                                                                                 u  a>
                                                                                                 •5 03  ^
                                                            «
                                                            ,<0 *->
                                                            h- c
                                                            -o §
                                                                               i;
                                                                               (Q
                                                                                                 O  o
                                                                                                s  § s
                                                                                             CN  S  CO »
                                                                                             >  Q>  
-------
    I
    JO
    a.
    •M

    O
    "i
       o
CM i  -C5
r-     CD
o
     .  s
   OD  co
   ^_ CL
    C
    O
   jtn
   *C
    ra
    a.


    o
   O
                                                                                  Q.

                                                                                  E
                                                                                  CO
                           (l/Biu)  ua6Axo paAjossiQ
                                       12-16

-------
                                     Section 13
            Interim Evaluation Of The AEES Facility In Frederick, MD
 13.1   Introduction

        Previous sections of this report have described, and presented the results of,  the
 independent monitoring program performed at the AEES in Frederick, MD.  This section  will
 present an evaluation of these data, which were the major objectives of this study.  These
 objectives were to:

 •       Evaluate the performance of the individual treatment components and the overall
        AEES  process,  through  monitoring  of  flow, characterization  of wastewater and
        residuals, and determination of HDTs.

 •       Compare the capital costs and operation and maintenance (O&M) costs of the AEES
        process with equivalent conventional Wastewater treatment technologies.
 •       Carry out a statistical comparison of the water quality data generated by this study
        to that produced by OAI, both from their on-site laboratory and their certified testing
        laboratory (at Ballenger Creek WWTP).  The purpose of this exercise was to validate
        the OAI procedures and  results, thereby reducing the requirement for independent
       testing in future evaluations  of this type.

 •       Evaluate the performance of the "Living Machine" with and without plants in the
      "treatment units  in order to quantify  and document the contribution of the floating
        macrophyte plant species to the AEES wastewater treatment process.           .


       This report is based on the  evaluation of the data collected during the February to
 June 1995 EPA study period,  Conclusions based on this short study period are considered
 to be interim.  The  AEES continued in  operation through 1995 and  into 1996 with data
x?pllection by  the OAI .staff.   It is intended,, if funding  is available,  to  conduct a final,
 complete  evaluation in  1996 based upon  all 1995/96  performance data.   A cursory
 examination of data collected since June 1995 indicates that the AEES process has not yet
 solved all problems with respect to nitrogen and phosphorus removal which are discussed
 later in this section.                    ,

 13.2  Process Performance                                    ,

       The  performance  goals  established  by Ocean  Arks  for  the  Frederick "Living
 Machine" are  compared below  to the mean  water quality  values  observed during this
 11 week EPA study period.  These  observed  values were measured at the end of the
 process. A summary of all of the water quality observations can be found in Table ,9.1, in
 Section 9, and in Appendix C.         ,
                                           13-1

-------
                                                                            Section 13
          Table 13.1  Performance of the Frederick AEES During the Study Period
     Parameter
Unit
Performance Goal
                                                          Actual Mean Performance
BODS
TSS
Ammonia
N03
TN(1>
TP
mg/l
mg/l
mg/l-N
mg/l-N
mg/l
mg/l-P
10
10
1
5
<10
3 .;
12.5
3.5
5.5
5.4
13.8
6.8
    (1)  The value for TN (total nitrogen) is derived by taking the sum of TKN and NO3 from the system effluent in
        Section 9, Table 9.1.                           -     ,   .

        It is apparent from this comparison that the "Living Machine" did not meet any of its
 established performance goals during the study period, with the exception of the goal for
 TSS.  Consequently, it could be concluded that the process has not aphieved its intended
 objectives and/or that more modest performance goals  should be defined.  However, this is
 not a completely valid  conclusion if both the influent  wastewater characteristics and the
 status of the Frederick AEES during the study period are taken into account.

        It  was  the premise of  Ocean Arks when  establishing  these goals  that  the
 wastewater at Frederick would have  "typical" moderate strength characteristics, i.e.: BOD5
 **  220 mg/L,  TSS * 220 mg/L,  TN *  40  mg/L,   TP * 8 mg/L.  The actual wastewater
 characteristics at Frederick could instead, be considered a  "strong" wastewater, i.e.: BODS
 * 469 mg/L, TSS * 470 mg/L,  TN  * 56 mg/L, TP ' * 14 mg/L. Consideration was given,
 prior  to  the  EPA study period, to reducing the flow  rate into the AEES  facility so that
 loadings on the system  would more closely match the original Ocean Arks expectations.  It
 was finally decided,  with  EPA concurrence, that  the  system  should  be operated  at  the
 design flow  rate of 40,000 gpd  so the system  did  have to  contend  with higher than
 expected wastewater strength.

       It was the premise of EPA, in  planning this study, that the Frederick facility was
truly in "steady state" operation with all of the "bugs" eliminated and all of the components
and procedures operating at their optimum potential.  This  expectation proved  not to be
valid.  The "Living Machine" technology  is still evolving so that procedural and operational
changes continued  to be made  during the EPA study period.  Typical examples of these
changes included variations in the backflushing frequency and duration for the pumice filter
beds,  and the type and dose of carbon source used for denitrification. As shown on Table
9.6 sodium acetate was the carbon source in use  at the beginning  of the study, and this
continued until the 7th week. The change to methanol  had a very significant impact on the
characteristics of the final  effluent. The average effluent  during the first six weeks was:
BOD5  7.4 mg/L,  and NO3  6.9 mg/L; after these modifications  the effluent concentrations
in the last four weeks of the study averaged: BOD 23  mg/L, and NO3  2 mg/L. It is clear
that denitrification improved due to the change to  methanol as  the carbon  source but the
                                            13-2

-------
                                                                            Section 13
  effluent BOD increased due the presence of the residual methanol. In this case, it is believed
  that as operational experience with methanol improves  the procedure will be optimized to
  yield both a low effluent nitrate and a low BOD5 .

         It is believed that when the AEES "Living Machine" process is fully optimized and
  truly operating  at  steady state conditions  it  should be  capable  of satisfying all of the
  specified  treatment goals except phosphorus.  Effective phosphorus removal may require
  the  addition of suitable chemicals and/or filtration  through suitable media. This opinion
  regarding  the potential capability of the "Living Machine" still needs to be  demonstrated.
  Unfortunately,  the process demonstration at  Frederick,  MD is not well suited  for  this
  ultimate purpose,  since wastewater is pumped into the AEES facility at a uniform rate so
  the system is not exposed to the normal diurnal flow variations or the peak flows which
  occur  in  response to  storm events,   In addition, sludges are returned to the  adjacent
  municipal treatment plant without processing.  Dewatering on reed beds is proposed for
  future  applications of  the  "Living Machine".   In this case, the leachate from  these  reed
  beds would  have  to  return to  the AEES facility for treatment.    The need  to include
  treatment of this very strong leachate with the normal wastewater stream might reduce the
  claimed capacity of the system by about 5 percent (i.e.: a 40,000 gpd unit could only treat
  38,000 gpd of  wastewater and  .600 gpd of very strong sludge leachate).  The AEES
'  facilities in Frederick and South Burlington are well  suited to demonstrate the  capabilities of
  the process under "ideal" operating conditions.,                  :

  13.2.1 Anaerobic Bio-reactor

        It is clear from examination of Figures   9-7 to 9-12  that the anaerobic  bio-reactor
 was a critical component in the successful performance of the AEES system at Frederick. It
  removed more BOD5, COD, TSS, and phosphorus than all of the other system components
 combined. The effective removal of BOD5, COD, and TSS was essential for the operation of
 the system since  the  greenhouse components could  not contend  with  the untreated
 wastewater if applied  directly. This reactor was also very  effective for solids removal as
 evidenced  by  the  84  percent removal of TSS.  It is also apparent that at least some
 anaerobic digestion is  occurring in the reactor  since the volatile TSS was reduced while
 ammonia and soluble COD and soluble BOD5 increased significantly. It is believed the major
 mechanism responsible for removal of phosphorus, BOD, and COD  in this unit is effective
 removal of the solids in the incoming wastewater and in the recycled sludges.  The BOD and
 COD can undergo  further reduction  due to  digestion of the solids but  most  of  the
 phosphorus will remain with the sludge removed from the unit.  It has been estimated that a
 solids reduction of at least 20 percent is accomplished by the anaerobic digestion in  this
 reactor. As shown in Table 10.1  the  theoretical and measured detention time in this  unit
 are the  same at about  18.5 hours at design flow. Table  9.1  shows  a positive dissolved
 oxygen  concentration in the effluent from this reactor; that is due to the small  aeration
 tanks prior to the greenhouse which were discussed in Section 2 of this report.

        The observed advantages of this anaerobic  unit would seem to. favor its  continued
 use  with  future  applications  of  the AEES technology.  Anaerobic reactors  can deal
 effectively  with  high  organic  loads and organic compounds which  might not be easily
 treated by the units inside the greenhouse. Using such a reactor as the initial treatment step
 protects the greenhouse processes from upsets  and disruptions even with low to moderate
 strength wastewaters.  Its use  would be  essential for high  strength wastewaters.  It does
 require  odor control for any exhaust  gasses and  the   digestion  process is temperature
 dependent and would be less efficient in cold climates. These constraints seem a small price,
                                            13,3

-------
                                                                            Section 13
 to pay for the advantages of the anaerobic technology. Even if the digestion process was
 negligible during the cold winter month the solids wasting requirements might not increase
 more than 20 percent based on the experience at Frederick. It might be possible to sustain
 a significant level of digestion by adding extra layers of insulation around the perimeter of
 the tank in  cold  climates,  and possibly heating the sludge  wasted from  the greenhouse
 before it is returned to the reactor.  It has, however, been decided to replace this anaerobic
 reactor by increasing the aerated tanks in the greenhouse from two to five, per train, in the
 system under construction in Vermont.

        Sludge is routinely wasted from this unit to the Ballenger Creek WWTP, and sludge
 is routinely added with sludge from the pumice filter beds  (sludge from the final clarifier is
 also  wasted to the  Ballenger Creek, WWTP). Similar arrangements are planned for the
 80,000 gpd system now under construction in South Burlington, VT. In future applications
 of the AEES technology where it cannot depend on an adjacent treatment  plant  it will be
 necessary to add suitable headworks for screening and  grit removal to protect the anaerobic
 bio-reactor. It might  also be necessary to  increase the volumetric  capacity of the unit to
 accommodate all of the sludge from all of the greenhouse clarifiers and to achieve further
 stabilization and solids reduction via anaerobic digestion.

 13.2.2 Aerated Tanks

       The measured detention time in the two.  aerated tanks is  about 21 hours (Table
 10.1).  This  is comparable to the detention time commonly used in the extended  aeration
 activated sludge process. There are however, two major differences with the AEES  tanks: a
 layer of vegetation  floats  on  the  water surface  of the tank, and  the  suspended solids.
 concentration maintained in these  tanks is quite low. The uptake of  nutrients and other
 pollutants, by the plants, is minimal but the plant roots are  expected to provide a substrate
 for support of the  microorganisms providing treatment of BOD and for  nitrification of
 ammonia  nitrogen.                                                      •

       As might be expected with a long detention time, these tanks provide a 91  percent
 removal of soluble BOD5 and a 70 percent  removal of soluble COD.  Much  of this  removal
 occurs via generation of new microbial solids and the volatile solids increase by 91  percent
 in the tank effluent, and the TSS  also increases by 90 percent. There is a small reduction in
 ammonia  (17  %)  in these tanks but the Kjeldahl  nitrogen (TKN)  increases by about seven
 percent.  The  small  ammonia  removal is  probably due to a.  lack  of  sufficient nitrifying
 organisms in the tank environment. The  small increase  in TKN is  probably due the increase
 of microfaial solids mentioned previously and the associated uptake of ammonia nitrogen.

       The average effluent TSS from the second tank was 140  mg/L.  Since the tank was
 completely mixed  that would  also be the  concentration of solids  contained  in the  tank
 (mixed liquor suspended solids  (MLSS)).  That is a much lower  concentration than  typically
 maintained in conventional  activated sludge processes and may be one reason for the low
 ammonia  removal efficiency. In the general case, the nitrifying organisms cannot compete
 with the heterotrophic organisms which consume  the BOD, that is why many conventional
treatment processes are two  stage systems.  However,  in long detention  time activated
sludge systems the soluble BOD reaches low levels and the nitrifiers can compete if they
are present in high enough concentrations.   In order to keep the population  of nitrifiers at
 high levels it is necessary to recirculate some of the sludge removed by clarification to the .
aeration tank  and to maintain a  MLSS  concentration  of  about 2000 mg/L. The AEES
aeration units at Frederick  provide neither significant  sludge return  or maintenance of
                                           13-4

-------
                                                                            Section 13
 sufficient MLSS to achieve significant nitrification which could be expected in the complete
 mix mode of operation.     .                      .   -  •                               .

        The roots of the floating macrophytes on these tanks are also intended  to serve as
 the substrate for the nitrifying organisms which allows their retention in an otherwise mixed
 tank. In this case the mixing action brings the wastewater into contact with the organisms
 attached to the plant  roots. This activity is apparently not very effective at the Frederick
 facility, and there may be two contributing reasons. It is possible that the roots are covered
 with accumulated TSS so that oxygen and the wastewater ammonia cannot get to the root
 surfaces and the accumulated organic matter would discourage occupation by the nitrifiers.
 The major reason is that there are just not enough plants in the Frederick AEES facility. The
 amount of root matter available is a  function of the  number of plants present and  that in
 turn is a function of the surface area of the container. The  volume, or depth of water in the
 container then influences the number of opportunities for wastewater ammonia tp come
 into contact with the plant roots. At the Frederick AEES facility the ratio of depth to surface
 area is  about 1  ft:20 ft2. Treatment basins using floating  macrophytes are typicaljy about
 three feet deep  and have  a depth to surface area ratio of at least 1ft: 140 ft2. It is obvious
 that the latter  system can  have many  more plants and therefore  many more contact
 opportunities between  roots and ..circulating  wastewater., These macrophyte  basins  are
 typically used jn subtropical and tropical climates, without greenhouse protection. The AEES
 system  at Frederick is  constrained by the costs required to  provide the greenhouse and it is
 not  possible to provide  enough  water  surface and  plants  to depend on the use  of
 microorganisms attached to the plant roots for significant nitrification.
                         ' .                *      '                         '         '
       The aeration tank technology as used at Frederick, MD is therefore a hybrid concept
 with minimal capability for nitrification by either complete mix or attached growth microbial
 processes. The nitrification potential  of this system  component can only be improved  if
 one  or  both of these mechanisms  are  optimized. The complete mix pathway  could be
 improved by maintaining a higher concentration of MLSS in  these tanks. That would require
 improved clarification after the aeration tanks and routine return of a portion of that  sludge
 to the first  tank in series. These high MLSS concentrations would probably result  in the
 plant roots becoming completely ineffective for  nitrification because of sludges trapped in
 the  roots.  The  plants  would still  survive  and grow  but their function would  largely be
 aesthetic. Substrate for attached growth nitrification could be provided with the use of
 commercially available  submerged plastic media.  It is also  possible to continue the present
 mode of operation and design- these tanks for  only BOD5 removal  and depend on the
 "ecological  fluidized beds"  for nitrification. This approach would still require improved
 clarification  after the aeration tanks to reduce the  solids load on the filter beds.

 13.2.3 Ecological Fluidized Beds      . >    '  "

       These beds  are a unique and  imaginative attempt to solve  several treatment issues:
 1. the need to  provide a media that can  effectively trap solids and also serve as the
 substrate for microbial  nitrification and denitrification,  and 2. a media which can  be cleaned
easily without excessive use of energy or large  volumes  of water for backwashing.  The
 pumice gravel used  in these units would seem to be an ideal choice for these purposes. The
first  piimice bed achieves a 71  percent removal of TSS, 53 percent removal of BOD5, and a
 31 percent removal of TN. The three pumice beds in series produce a 93 percent  removal of
TSS, 83 percent removal of BOD5, and a 56 percent removal of TN.
                                            13-5

-------
                                                                            Section 13
        As described in Section 2, the final bed in the set is operated as an anoxic upflow
 reactor to accomplish devitrification of the nitrates produced in the earlier process units. As
 shown on Table 9.1  the average  effluent nitrate from this, third bed was 10.5 mg/L during
 the study period. This, however is somewhat misleading since the carbon source addition
 was changed to methanol at about the 2/3 point in the study period, and in the final sample
 the nitrate  concentration  was down to  4.2 mg/L.   This suggests that  very  effective
 denitrification is possible once the use of the methanol addition is optimized.

        The removal of accumulated TSS from the pumice bed is accomplished by aeration
 which reverses the flow in the inner ring and  "fluidizes" or suspends the  pumice gravel in
 the upflowing water. This  flushes the retained TSS out of the bed and  into the annular
 space outside the pumice container. A perforated pipe  was added at the bottorn of that
 annular space for sludge wasting but that has not proven to be very effective and  a manual
 vacuum operation is  routinely used to remove this sludge.  A hopper bottom on  the entire
 tank  with a suitable airlift  might be a more effective  method for sludge management in
 these units.

        It is believed  that effective management of TSS is the key to successful operation
 of these pumice bed  filters. Rapidly accumulating  sludges in the beds require very frequent
 cleaning and  the  oxygen demand from the sludge tends to reduce the  effectiveness of
 nitrification.   It is suggested that a full sized, and more  effective clarifier between  the
 aeration tanks and these filters would significantly improve the performance of the entire
 AEES process.  The  small  clarifier installed  at this point in the Frederick facility was  an
 "after-thought."   The  80,000  gpd  "Living  Machine"  now under construction   in South
 Burlington, VT has a specifically designed clarifier at this point.

        The  pumice gravel seems, at first glance, to be an ideal choice for .this service. The
 gravel provides a high surface  area for microbial  growth  and  its  low  density  allows
 suspension  with minimal airlift  energy input. However,  the softness of pumice  creates a
 problem for operation of  the  units. The   inter-particle  abrasion occurring during  the
 backflushing operation causes significant degradation of the gravel particles.and loss of  the
 abraded fines. The loss has  been equivalent to almost a one foot depth of gravel in some of
 these tanks during the first year of operation. As  a result of these losses, a higher density,
 harder  volcanic  stone has been selected  for  use  in  the  80,000 gpd  facility under
 construction in Burlington, VT. At the Frederick facility it might be possible to reduce  the
 rate of loss if more  effective clarification ahead of the pumice beds  would reduce  the
frequency of backflushihg required.                          •

 13.2.4  Duckweed Clarifier

       The  Frederick, MD facility has a "Duckweed" clarifier after the final pumice  bed. The
 "Duckweed" portion of the unit name is due to the presence of a mat of  floating duckweed
 (Lemna  sp.) on the water surface of this  tank. In its present location in the flow path at
Frederick this  clarifier is  not a very effective component in  the process and  does  not
contribute significantly to treatment. This is primarily due  to  the  the very  effective TSS
removal in the pumice filter beds. A sampling point was originally planned for the EPA study
after  this clarifier. Data collected  by the  Ocean  Arks  staff indicated that  there  was an
insignificant change  in water quality  between the effluent from the third pumice bed and
the effluent from  this clarifier so  the sampling point was moved to the third pumice bed
outlet as shown on Figure 4-1. This clarifier is not needed in this position at .Frederick since
the high rate marsh  is there for  final effluent polishing, but  as noted  below the marsh
                                             13-6

-------
                                                                            Section 13
  provides a  marginal  level of further water quality improvement.  As a  result,  both this
  clarifier and the final,marsh unit have been eliminated from the 80,000 gpd unit now under
  construction in South Burlington, VT.

        A significant improvement in performance at the Frederick facility should be possible
  using this clarifier, but significant piping changes would be necessary.  The effluent from
  the final pumice bed could bypass this clarifier and flow directly to the  high  rate marsh.
  Effluent from the second aeration tank could bypass the pumice beds and-flow directly to
  this clarifier. A small 10 gpm pump would then be required to return the clarified effluent to
  the inlet of  the first pumice filter bed. This arrangement would then replicate to flow path
  intended for South Burlington and would keep the existing high rate marsh in service.

,  13.2.5 High-Rate Marsh

        This unit was intended for final effluent polishing via physical filtration by the1 gravel
  media, by microbial action of the contained organisms, and by contact with the roots of the
  plants growing in the  marsh.  The measured detention time in this unit  was  about  10.5
  hours, and is the reason for the term "high-rate"  since the detention time in marshes of this
  type  is usually measured in term .of days; Space and cost limitations for the enclosing
  greenhouse  would preclude the use of a larger marsh. The marsh produced an additional 65
  percent removal of TSS but TSS was already at the project goal in the effluent  from the
  pumice bed  filters. A 32 percent further removal of BOD,was achieved but the final marsh
  effluent still exceeded  the 10 mg/L goal, on average. A 27 percent ammonia removal was
  achieved, and nitrate removal averaged 48 percent confirming that  an anoxic environment
  exists in the graver marsh bed.  Removal of total nitrogen (TN) averaged, 33 percent but the
  final effluent (14 mg/L) still exceeded the 10 mg/L Ocean Arks goal. The nitrogen removal
  in the bed is beljeved due to the combination of  solids  removal  and denitrificatibn; uptake
  by the plants growing on the bed is a negligible contribution.

        To provide a  major contribution to wastewater treatment this marsh would have to
  have a significantly larger area  and/or improved  control ovej denitrifiction  carbon sources.
 as a rule-of-thumb  at  least five pounds  of BOD5 are  required to denitrify one pound  of
 wastewater  nitrate. At 18 mg/L it is clear that the marsh influent contains insufficient BOD5
 to support complete denitrification and the short detention time may not  be sufficient. In
 most  marsh systems the  plant  litter is allowed to accumulate and  becomes an additional
 carbon source for denitrification. At the Frederick facility, the marsh surface is managed as
 a horticultural nursery so the plants are removed before they can develop deep root systems
 and litter is not allowed on the bed surface.                                '        ,'

        It is believed that performance at the Frederick facility can meet treatment goals for
 BOD5, TSS,  and nitrogen forms with improved clarification  and methanol  management in
 the upstream units. This would reduce the  function'of the present marsh to a  horticultural
 role. A,gravel bed marsh may still be a useful final polishing unit for the AEES concept, and
 a larger bed  could be located outside the greenhouse, even in cold climates. However, such
 a marsh would be intended for treatment and have minimal horticultural use.
                                              1  -           - s

 13:2.7 Phosphorus Removal

        The performance goal for phosphorus was set by Ocean Arks at 3 mg/L. During the
 EPA study period the final effluent phosphorus averaged 7 mg/L, or 50 percent removal for
 the overall process. The untreated wastewater had an unusually high organic strength but
                                             13-7

-------
                                                                           Section 13
 the phosphorus concentration at 14 mg/L was typical of most municipal waste waters. Most
 of the phosphorus removed in the. system  was taken but in the anaerobic bio-reactor, the
 next  largest contribution was from the pumice filter beds. Neither of these processes have
 an inherent affinity for phosphorus, the likely removal pathway is  with the  sludge which
 was separated from the liquid in these units and then wasted.

        None  of  the  biological pathways  available in the current  AEES  process can  be
 expected to remove large  quantities  of phosphorus.  Biological  phosphorus  removal is
 possible in specially designed and  operated  treatment  plants. The  patented  Bardenpho
 process is one example; these processes tend  to induce biological uptake of phosphorus by
 the microorganisms and result in  the production of large quantities of sludge. The other
 commonly used phosphorus removal pathway in wastewater treatment is chemical  additions
 to precipitate the phosphorus; these also produce large quantities of  sludge. It is possible to
 remove significant amounts of  phosphorus via plant uptake and  harvest  but the plant
 density and harvesting program at the  AEES facilities are  not sufficient to account for
 significant amounts of phosphorus. Based on the,data  presented in Tables 9.1, 9.5 and  9.8
 it can be calculated that about 751 kg/yr of phosphorus enters the AEES with the  incoming
 wastewater, at a flow rate of 40,000 gpd.  Approximately 0.44 kg/yr of phosphorus would
 leave the facility with the routinely harvested and composted  plant material. Additional
 phosphorus is  removed during the horticultural operations but it is unlikely that  the total
 annual phosphorus for all plants leaving the greenhouse exceeds 1 kg/yr. The plants in  the
 Frederick  AEES system can therefore, account  for about 0.1 percent of  the phosphorus
 entering the system.  Either significant phosphorus removal should be dropped as  an AEES
 performance claim or more positive methods for removal incorporated in the system.

 13.2.8 Fecal Coliforms

       Fecal coliforms were  only measured  in  the untreated wastewater  and  the final
 effluent. QA/QC  procedures  require  a  grab sample so the data only  represent a specific
 point  in time during the sampling day.  The  apparent  removal by the over all system was
 quite  good. The untreated wastewater  had  a typical concentration of 8 x  106 cfu/100  mi,
 and the final effluent 170 cfu/100 ml for  a  four  log reduction. Final disinfection of this
 effluent would not be required for most  discharge or  reuse purposes.  The San Francisco
 AEES is intended to  produce 2.2  cfu/100   ml  which is the  "Title  22"  water quality
 requirement by the State of California for unrestricted irrigation use.

 13.3   Process Residuals

       The residuals  leaving the AEES process include  sludges from  the anaerobic  bio-
 reactor and sludges from the final duckweed clarifier and the plants removed from the
 water surfaces on the various tanks. The plants removed during the horticultural  operations
 are not included in the "residuals"  estimate since they are intended  for replanting and not ,
 disposal. The  sludge  removed from  the pumice filter beds  is returned to the anaerobic
 reactor and are accounted for in the  sludge wasted from  that unit.  The volume of sludge
 and the weight of plants removed during the EPA study period are given in Tables 9.7 and ,
 9.8 respectively.

       Samples of sludge and plant material were collected on several occasions  and tested
for nitrogen, phosphorus and the  metals of concern  for land application  of sludge (503
 regulations). The plant material showed no  unusual concentrations of any material and the
final compost could be used for any agricultural or horticultural purposes. .The sludges from
                                            13-8

-------
                                                                           Section 13
the system met all of the  503 limits except for fecal conforms, • and 'these  limits could be
met with additional stabilization and treatment of the sludges.

        the total amount of residual materials removed  from the AEES facility in Frederick
can  be estimated from the data in Tables 9.7 and 9.8.  Based on the data in Table 9.7 an
average of 4434 gallons of sludge per week were wasted from the anaerobic bio-reactor; at
2.8 percent solids; that is about 472 kg/wk of dry solids, the final clarifier would contribute
about 2 kg/wk,  and the plant residuals about  1 kg/wk of dry material. On an annual basis,
the  residuals  production would  be  about 12 dry  tons (metric) per year.  A comparable
40,000 gpd extended aeration package plant,  with a final denitrification filter,  would waste
about 1000 gallons of sludge per day with about 2 percent solids, this would equal 76 kg/d
of dry solids or  14 dry tons (metric) of sludge  per year., The AEES system produces slightly
less   sludge than a conventional  extended  aeration  treatment process, which also includes
final filtration, and the effluent  characteristics of the two systems  are comparable.  This
should not be surprising since the process functions in  each system are also  similar.  The
difference  in:  residuals production between  the, two  systems  is  probably  due  to  the
estimated 20 percent  solids reduction achieved in the AEES anaerobic bio-reactor.

13.4  Cost Comparisons                          ,

       Previous discussion in this section evaluates the performance of the AESS process
and  compares that performance and residuals  production-to conventional  wastewater
treatment technology. It is the  intent of this section to compare costs for construction,
operation,  and maintenance  of the AEES  process  to  conventional1 treatment processes
capable of delivering the same effluent quality. Cost comparisons at three flow rates were
developed: 40,000 gpd (Frederick, MD flow rate), 80,000 gpd (S. Burlington, VT flow rate)
and  1,000,000  gpd.  T,he cost estimates for  the AEES process were prepared by  Living
Technologies,  Inc., in Burlington, VT; the costs for comparable conventional  technologies
were developed  by process specialists and staff at Parsons Engineering Science, Fairfax,
VA.  All of the individuals contributing to this effort  are listed in the Acknowledgements for
this report.                   ,                     .                     -

       Great care has been taken in the development of these comparisons to  be sure that
"apples are compared  to apples" with respect to process capabilities,  residuals management
requirements and the inclusion or exclusion of particular items in the cost estimates. An,
example is the level  of phosphorus removal.  The  original specification given to Parsons
Engineering Science required the conventional processes  to achieve all'of the original Ocean
Arks performance goals. However, the AEES facility at Frederick, MD does not satisfy  this
goal  so it was dropped from the second iteration of cost estimates for the conventional
systems.

       All of the costs cited  are essentially for the process  components, ancillary facilities
such  as headworks,  administration  and laboratory buildings,  roads  and fences, power
transmission, telephone service, etc  will  vary  with the size of  the treatment  plant.  All of
these features would probably be included in a 1 mgd capacity treatment plant but none of
these elements, or land costs  are included in .either set of cost estimates at any of the three
flow rates. All costs are given in 1995 dollars,  the calculations of present worth value  and
total annual cost are based  on 7 percent interest and a 20 year recovery period.
                                            13-9

-------
                                                                           Section 13
 13.4.1 AEES Process Costs

        The  costs for construction, operation, and  maintenance of the AEES system  at
 40,000,  80,000 and 1,000,000 gpd  are  given  in Table  13.2.  The original data were
 provided  by Living Technologies, Inc. at Burlington, VT. The cost estimates at the 80,000
 and 1,000,000 gpd  flows are for a location in Maryland with a similar climate to Frederick,
 not the low temperature environment expected in Burlington, VT. As a result, the propbsed
 process train for 80,000 gpd has four aeration tanks instead of the five under construction
 at South  Burlington, VT. The costs for the 40,000 gpd. system are based on  actual costs for
 the Frederick,  MD  system  with some deductions for a  special railroad crossing and
 landscaping; it does include the cost of the anaerobic bio-reactor. The AEES projections for
 80,000 gpd and  1  mgd do  not utilize an   anaerobic reactor, extra aeration tanks are
 provided  instead. It  was necessary for the senior  author  of this report  to  make  some
 adjustments and modifications to these costs based on the actual operational experience  at
 Frederick, MD with  respect to labor and utilities, residuals production and management,
 and horticultural revenues.  Adjustments were also made so that  the unit  costs for labor
 rates, and power, etc, were compatible between the Parsons and AEES cost estimates. The
 costs  are presented for an  AEES  system, with and  without a  greenhouse'since the
 greenhouse should not be required in warm, frost-free, southern climates. The original cost
 estimates prepared by Living Technologies can be found in Appendix G.

       The reed bed included in Table 13.2 is, in essence, a sand bed planted with  reeds
 (Phragmites}.   The bed provides for sludge  dewatering and long  term stabilization  since
 cleaning, and sludge  removal are  only required every 5 to 7 years.  The  leachate draining
 from  this sludge is returned to  the  basis  treatment  process  for treatment.   This
 consideration has not been included in the  proposed AEES design capacity flows.  For
 example,  a 40,000 gpd  AEES system might only have the  capacity to treat  38,000 gpd of
 municipal  wastewater plus this leachate.  An O&M cost will occur every 5 to 7 years for
 removal and disposal of sludge  from these  beds.  This  estimated  cost  is  included  in
 Table 13.3 as a pro-rated annual cost.           .

       Table  13.3  presents  operation  and maintenance costs for the AEES system at
 40,000 gpd, 80,000  gpd and 1 mgd. The original, and a revised second  set of estimates
 were provided by Living Technologies, Burlington, VT.  Some line items have been modified
 by the senior  author of this  report to reflect actual costs for energy  and horticultural
 revenue at Frederick,  MD and  also adjusted so the labor rates, etc would be the same for
 both the AEES and Parsons ES estimates.  For example, the  potential horticultural revenue
 claimed in the first AEES  cost estimate was  $5,411  (at the 40,000 gpd system), this
 increased  to $17,472 in their revised estimate even though the revised system would  be in
 a smaller  greenhouse and without a  marsh component.  The actual horticultural  revenues
during  1995 at the Frederick, MD facility was about  $2,400 and 75 percent of that came
from the plants grown on the marsh component, the remainder ($600) came from potted
plants suspended in the annular space on the pumice filter beds.  It was  assumed (by the
senior author of this report) that the $600 revenue from potted plants could be increased by
a factor of four so $2,400 was entered in Table 13.3.  The revenue for  80,000_gpd and
 1 mgd  was then calculated based  on the ratio of greenhouse  areas  available.   Similar
procedures were used to scale  up other 40,000 gpd costs to the other two flow rates. The
unmodified revised cost estimate prepared by Living Technologies; Inc. is given in Appendix
G.
                                           13-10

-------
                                                                                       Section 13
                            Table 13.2 AEES Process, Capital Costs
40,000 gpd 80,000 gpd . 1 mgd
' w/g-house w/o grouse w/g-house • w/o g-house w/g-house w/o g-house
Facility Description'
Size of Anaerobic . . '
Bio-reactor (ft2) , 635 635 none
Size of "Living '
Machine" (ft2) 2,184 2,184 '< 3,000
Power (kwh/d) 409 409 . 624
Operator (hr/wk) 20 20 30
Residuals (dt/yf) ,' 12 12 ' 24
Reed Bed Area (ft2) . 5,280 ,5,280 1.0,560

none none • ••• none
3,000 31,584 31,584
624 5,728 5,728
30 126 . 126
24 300 300
10,560 132,000 132,000
Facility Costs
AEES Facility '
Reed Beds
          (2)
TOTAL COST
              (3) ,
$402,475      $348,414     $560,457     $485,289    $4,043,026   $3,554,987


 $26,400      $26,400       $52,800      $52,800      $660,000     $660,000


$428,875      $374,814     $613,257     $538,089    $4,703,026   $4,214,987
(1)  Assumed to include bonds, insurance, mobilization, overhead & profit, and contingencies.

(2)  Sized at 0.22 ft2/kg/yr dry solids, cost $5/ft2 w/all overhead, etc, sizing ratio and unit cost provided by Living
    Technology, Inc.    -        ,   .         ,                             -

(3)  Totar cost does noi include disinfection since fecai coliform < 200cfu/100 ml at Frederick.
                                                  13-11

-------
                                                                                             Section 13
Table 13.3 Annual O&M Costs for the AEES System
Item
40,000
gpd
w/g-house w/o g-house
Energy "'
Materials & Supplies
Bioaugmentation
Methanol
Contingencies la
Gas
Labor'31
Sludge Disposal (4)
Maintainance IS>
Hort. Revenue (SI
TOTAL O&M COSTS
$9,000

$4,300
$2,901
$1,080
$3,231
$26,000
!$2,000
$4,288
($2,400)
$50,400
$9,000

$4,300
$2,901
$1,080
$0
$26,000
$2,000
$3,748
($2,400)
$46,629
80,
w/g-house
$13,666

- $5,450
$5,802
$1,688
$4,438
$78,000
$4,000
$6,132
($3,300)
$115,876
000 gpd
w/o g-house
$13,666 .
'
$5,450
$5,802
$1,688
$0
$78,000
$4,000
$5,380
($3,300)
$110.686
*
1
w/g-house
$125,443

$31,500
$10,800
$15,604
$70,088
$327,600
$50,000
$47,030
($35,000)
$643,065

mgd
w/o g-house
$125,443

$31,500
$10,800
$15,604
$0
$327,600
$50,000
$42,150 '
($35,000)
$568,097
(1)   Electrical power at $0.06/KWH
(2)   Contingencies = 15% of Materials and supplies
(3)   Labor at $25/hr including benefits
(4)   Sludge disposal, at $500/dt every 7 years, assume 2/3 reduction of mass on bed during 7 years. This is the
     cost every seventh year/7.                 '                                  '      •        -  .       '
(5)   Maintenance at 1 % of capital cost
(6)   Horticultural revenue, based on 4 times the 1995 actual return at Frederick, MD
                                                     13-12

-------
                                                                            Section' 13
Table  13.4 summarizes capital and O&M costs for the AEES process and presents .the
present worth and total annual costs.

            Table 13.4 AEES System, Present Worth and Total Annual Costs


Item                 40,000 gpd               80,000 gpd                 1 mgd
                w/g-house   ,w/o g-house  ,  w/g-house    w/o g-house    w/g-house   w/o g-house
Capital Costs
O&M Costs ,
Present Worth
• total Annual
$428,875
$50,400
$960,500
$90,900
$374,814
$46,629
$866,700
$82,000
$613;257
$115,876 .
$1,835;,600
$173,800
$538,089
$110,686
r
$1,705,700
$161,500
34,703,026
$643,065
$11,486,700
$1.087,000
$4,214,987
$568,097
$10,207,800
$966,000
13.4.2 Costs of Conventional Treatment Technologies

These cost estimates were prepared by process specialists at Parsons Engineering Science.
They have provided capital and O&M cost estimates for conventional wastewater treatment
processes recieving the same influent characteristics as the present AEES system in
Frederick* MD, with the capability to  produce the same quality effluent (i.e.: BOD5 < 10
mg/L, TSS < 10 mg/L, Ammonia  < 1 mg/L,/and TN <10 mg/L. Since low levels of
phosphorus are not achieved by the AEES facility at Frederick this requirement was also
dropped from the Parsons alternatives.  However, all of the Parsons alternatives can remove
phosphorus to comparable levels (« 50%). As indicated previously, these estimates only
include the direct process costs and related O&M, the ancillary facilities and activities
typically found at larger treatment plants are not included. These omissions are to insure
compatibility with the AEES estimates.,       *

This section presents a  brief  discussion and summary tables. The detailed Parsons  cost
estimates and  related discussion can be found  in Appendix F. The  comparisons are at the
40,000  gpd,  80,000 gpd, and 1 mgd  flow rates  to  again be compatible with the"AEES
estimates. The process specialist  developed costs for  the most cost effective conventional
process at each  of these flow  rates.  As a result, the process selected varies with the flow
rate. The systems are:

1.     40,000 gpd: . A prefabricated packaged extended aeration plant with a final anoxic
       filter for  denitrification  and filtration^ followed  by ultraviolet (UV) disinfection.   The
       only chemical addition is methanol as a carbon  source for denitrifieation.

2.     80,000 gpd: A  sequencing batch reactor (SBR) followed by a filter with backwash
       and UV  disinfection.   Methanol is  not, needed in  this case since the wastewater
       BQD5  provides sufficient carbon in  an anoxic period which  is developed during the
       SBR operational sequence. Two options were developed: a prefabricated package
r       plant, and on-site constructed concrete tanks.       -

3.,  .  1,000,000 gpd:  Two  optioris  were developed for this flow rate:  A prefabricated
      ^extended aeration package plant with a  cylindrical steel tank erected on a concrete
       pad, the system  includes an anoxic filter for denitrifieation, and UV disinfection;
       methanol is  used as  a  carbon source.   The second alternative is a Carrousel
                                           13-13

-------
                                                                           Section 13
        oxidation  ditch  process  with typical  concrete  aeration/anoxic  zone tanks,  final
        clarifiers and sludge return pumping, a polishing filter and UV disinfection. Methanol
        is not needed in this case because the wastewater BOD5 provides sufficient carbon
        for denitrifiaction in the anoxic zone of the oxidation ditch.


        The costs for residuals management and final disposal are included in the estimates.
 At the 40,000  and 80,OOO gpd  flow rates sludge, disposal is via a contract septic/sludge
 tank truck hauler which convey the sludge  to an off-site facility for final  treatment and
 disposal. Such  a  procedure is commonly used  at these lower flow  rates.  The  1  mgd
 systems include on-site sludge  management  and  stabilization  procedures.   The  1  mgd
 package plant includes digestion and contract land application for final  disposal. Digestion is
 not required for the  1  mgd  oxidation ditch  since there  is no primary sludge. The sludge
 management  costs for  this alternative are derived from  actual process  costs  for the
 Downington WWTP in Pennsylvania.
                              * .                              •" '
        The  O&M  costs  are  based  on  manufacturers  data  on power  requirements,
 manpower,  and chemicals. The  unit O&M cost for sludge processing,  stabilization,  and
 disposal at  the  1  mgd flow rate is  based on historical data from ALCOSAN Diversified
 Residuals Management Program  (1994) and Sludge Management Alternatives Evaluation
 Report (1994). This unit cost at $500 per dry ton includes belt press filter dewatering,  lime
 stabilization and contract land application;  The costs for  the smaller flow rates is based on
 a $95/hr rate for the sludge hauler. This cost, converted to  $/dry ton (metric) is $1,000 per
 dry ton produced by the WWTP at the 40,000  and 80,000 gpd flow rates. A $500/dt  cost
 was  also added for  the .final sludge  disposal operations  in the AEES cost estimates.
 Tables 13.5 and 13.6 present summary data for the three  flow rates.             ,

        Table 13.7 compares the  total present worth costs of the AEES process and the
 Parsons ES alternatives  for the three  flow  rates.  The cost differences at the 40,000 gpd
 and 80,000 gpd are within  15 percent and  therefore not significant.  The cost difference' at
 1,000,000 gpd  is very  significant  and favors either of  the two conventional treatment
 alternatives.  It can be tenatively concluded that the AEES process will  cost about the same
 as conventional  technology at  flow rates less  than about  100,000 gpd; at  flow rates of
 100,000 gpd  or higher  conventional wastewater  technology  is apparently more cost
 effective. This is probably  due to economy of scale issues. An oxidation  ditch at 100,000
 or 1,000,000 gpd can usually be a single process unit whereas the AEES system must have
 several replications of greenhouses and process  tanks.

       Neither the conventional or the AEES costs represent a complete treatment system.
 Some  items  not included  are: headworks, roads,  fences,  administrative and laboratory
facilities, chemical storage,  and redundant treatment units.  As a result, these costs cannot
 be compared to treatment system costs published elsewhere.  Addition of these costs
 would increase the costs of both the AEES and conventional processes.
                 /                                                             .  ' •
 13.5   USEPA-Ocean Arks  Data Comparison

 It was the intent of this part of the study to compare the data  produced by the EPA study
team during the 11 week study period to that produced by Ocean Arks staff in their on-site
laboratory at Frederick and by their   QA/QC  certified laboratory at the Ballenger Creek
WWTP.  The purpose  of  the comparison was to validate,, if possible, the  Ocean Arks data
                                           13-14

-------
                                Section 13
Table 13.5 Capital
Item
Capital Costs
Construction
Bonds, Insurance, 3%
Mobilizaton, @ 4%
Misc. Costs, @ 1 0%
Subtotal
OH&P1, 15% '
Contingency! 1.5%
Total Capital Costs
Annual O&M Costs
Energy2 , $0.06/KWH
• Methanol3, $0,23/lb' '
Contingencies4, 15%
Labor5, $25/hr
Sludge Management6
Maintenance, 1 % of Capital
Costs '
Total O&M Costs
Total Present Worth
Total Annual Cost
and O&M Costs
40,000 gpd

, $266,289
$7,989
.$10,652 ,
$26,629
; $311,559
$46,734
$46,734
$405,025

$7,931
$2,902 :
$435
$36,500
$13,140
$4,050
$64,958
$1,093,200
$103,192
for the 40,000 and 80,000
80,000 gpd. Steel
- . '
$450,149 :
$13,504
$1;8,006
$45,014
$526,674
$79,000
$79,000
$684.676
' •'- , .
$7,493
$0
$0
$54,750
$26,280
$6,847
$95,370
$1,695,000
$160,000
gpd Alternatives
80,000 gpd. Concrete
•'. •' ; • ' --.
$416,802,
$12,504
$16,672
$41,680
$487,659
$73,149
$73,149
$633,956
'
$7,493
$0
$-0
. $54,750
$26,280
$6,340
$88,119
$1,567,500
$148,000
(1) Construction contractor's overhead and profit. '
(2) Electrical power for process
(3) Methanol at .35 Ib/d. ,
and UV. disinfection.
.
' ' ' . •
- ' • " ' •


(4) A percentage of chemicals and supplies. . <
(5) Includes" fringe benefits.
. • '
- '' '•
..• :; -'. -. , -
13-15

-------
                              Section 13
. Table 13.6 Capital and O&M
Item
Capital Costs
Construction
Bonds, Insurance, 3%
Mobilizaton, @ 4%
Misc. Costs, -@ 10%
Subtotal
OH&P1, 15%
Contingency, 15%
Total Capital Costs
Annual O&M Costs
Energy2, $0.06/KWH
Methanol3, $0.23/lb
Contingencies4, 15 %
Labor5, $25/hr
Sludge Management6
Maintenance, 1 % of Capital Costs
Total O&M Costs
Total Present Worth
Total Annual Cost
(1) Construction contractor's overhead and profit.
Costs for the 1 ,000,000
1 mgd. Packaged

,$2,111,460
$63,344
$.84,458
$211,146
$2,470,408
$370,561
$370,561
$3,211,530

$88,053
$10,786
$1,618
$146,000
$164,250
' $32,115
$442,822
$7,902,800
$746,000

gpd Alternatives
1 mgd. Carrousel

$2,100,227
$63,007
$84,009
$210,023
$2,457,266,
$368,590
$368,590
$3,194,446
' ' - • "•
$42,304
• $0
$0
$146,000
$196,188
$31,944
$416,436
$7,606,169
$718,000

(2) Electrical power for process and UV disinfection. . '
(3) Methanol at 1 30 Ib/d.
(4) A percentage of chemicals and supplies.
(5) Includes fringe benefits.


-



13-16

-------
                                                                            Section 13
          Table 13.7   Present Worth Comparison, AEES and Conventional Systems
 System Size
40,000 gpd
80,000 gpd
1,000,000 gpd
AEES
w/ Greenhouse
w/o Greenhouse

$960,000
$866,700

$1,835,600
$1,705,700

$11,486,700
$10,207,800
 Conventional System

  Package Plant

  SBR

     w/ steel tanks

     w/-concrete tanks

  Carrousel
 $1,093,200
                      $7,902,800
                      $1,695,000

                      $1,567,500
                                           $7,606,200
 sources so that in continued or future evaluations of the AEES process the EPA study team
 would  not have  to continue to  produce  an independent  water quality  data  set  for
 performance evaluation.

        Although some  of the data sets were considered.to show statistical similarities, the
 T-test results did not suggest that these similarities existed throughout the data.  The best
 similarities were found  between the USEPA data sets and those produced by the certified
 laboratory at  the Ballenger Creek WWTP.  Similarities'between analytical parameters were
 best between the  results for TSS, TKN, ammonia  and  total phosphorus.   The  lack of
 statistical similarity between the different data sets are almost certainly a result of sampling
 and analytical variations between the USEPA and OAI data.  A simple visual inspection of
 the data sets  indicated that the data were more similar than the T-tests had implied.

        Therefore, although statistical dissimilarities exist, an objective examination of any
 one of  the three  data sets will .lead  to the same conclusions  regarding  performance
 capabilities of  the  AEES  process.   Consequently,  it can  be  concluded that  the data
 generated  by  OAI are reliable and could be used in the future for an objective assessment of
 system performance.

 13.6   Role of Plants in the AEES Process

        As shown on Figure 2-1, prepared by Ocean Arks, plants supported by solar energy
 are included on almost every unit  in the AEES system and their contribution is  believed
 essential to the performance of the  process, hjaving committed to plants and solar energy
 the design logic then  requires the  use of a greenhouse when  colder  seasonal  climates
'prevail, for protection and continued year-round growth of the plants.  A commitment to a
 greenhouse then creates a design dilemma since the high cost of the space enclosed,by a
                                            13-17

-------
                                                                            Section 13*
 greenhouse then  requires deep  high  rate treatment units for cost effective use of that
 space. Such high rate units then  minimize the surface areas available for utilization of plants
 so the  role of the plants is diminished as is the original highly desirable intent to  utilize
 plants and solar energy as major components in the system. A treatment system based on
 the use of  plants and solar energy as major components  must provide sufficient surface
 area so the  plants are in fact a major physical presence in the system.

        Plants were  utilized on all of the treatment units at the AEES facility in Frederick,
 MD and are  intended for similar  use at the 80,000 gpd facility under construction in  South
 Burlington, VT. The  plants are considered essential for treatment on some  units and for
 horticultural purposes on  others,  depending on the plant species used.   Regardless of their
 purpose, the  presence  of these  plants in the AEES greenhouse creates an aesthetically
 pleasing and  often  beautiful environment  unlike any other  conventional  wastewater
 treatment system.

       As discussed in a previous section, at the plant density and harvesting schedule
 used in the Frederick AEES facility the plant uptake of pollutants and then removal via
 harvesting accounts for a negligible fraction of pollutant removal in  the  system.  The major
 removal  mechanisms are believed  to be  microbial  activity  and physical  separation  of
 particles via settling  and  filtration. It is believed that the floating plants can  contribute to
 this microbial  activity  through  colonization of  their  root  systems  by  the  organisms
 responsible for treatment  and this was the intent  of the floating macrophytes used on the
 two aeration tanks at Frederick, MD.                                               '  ,

       the  plants were present,  and completely covered the water surfaces in the aeration
 tanks during the first 7 weeks.of  the EPA study period, so their contribution to treatment is
 included, but cannot be separately defined,  in the performance data collected during* that
 period. At the suggestion  of the  EPA study team and with the concurrence of Ocean Arks
 all of the plants were removed from these tanks for the second phase of .the study (the
 disposal  of these  plants is not included in the residuals balance discussed in  a previous
 section). The system was'allowed to come to equilibrium and then sampling and testing of
 system  performance without these  plant continued for  the remainder of  the period.
 Although wastewater characteristics might vary during the two study periods  it was hoped
 that a comparison of the "plants" versus " no plants" operational periods might help define
 the  treatment contribution of the plants. A detailed discussion and data comparisons can
 be found in Section 12 of  this report.

       There is no significant difference,  without the plants,  for removal of COD, BOD5,
TSS, VSS and phosphorus when the  data in Table 12.2 (without plants) is  compared to
Table 9.2 (with plants), for either the final  system effluent or just the effluent from the
 aerated  tanks. There  are slight, but significant differences for the nitrogen forms. The TKN
 and  ammonia  are  lower and  the  nitrate levels are higher when the  aerated tanks contain
 plants. The nitrate concentrations leaving the aerated tanks  is somewhat higher with plants
 on the tanks, suggesting  that the microbial activity on the plant roots does contribute to
 nitrification.  However,  this   diminished  nitrification  capacity without the  plants can
 apparently  be  compensated  by  nitrification in  the pumice filters  so  there  is  no  major
 difference in performance of  the overall system  with  or without plants on  the aeration
tanks. This observation has been confirmed by continued operation without the plants after
the end  of  the EPA study period.   As a result, it  can be  concluded that the  floating
macrophytes used on the  aeration tanks do not contribute significantly to treatment.  The
                                            13-18

-------
                                                                           Section 13
potential is there, but the limited surface area available on .these deep tanks does not permit
a sufficient number of plants to make a significant difference in performance.

       The duckwesd and azolla floating on the surface of the final clarifier may  make a
contribution to treatment by their physical presence on the water s'urface. Their presence on
the water surface adsorbs most of the solar radiation and prevents development of,algae in
this tank. Such algae would be removed in the final high rate marsh at Frederick, but at the
South Burlington AEES facility without a marsh this algae could have an adverse impact on
final effluent quality.
                                            13-19

-------

-------
                                    Section 14
                       Conclusions and Recommendations
14..1   Conclusions

       These conclusions are  based on the evaluation of data  collected during the EPA
study period  extending from February through late June 1995.  Operation of the AEES
process at Frederick, MD is expected to continue into :at least  mid 1996,  If funding  is
available, a final evaluation will be conducted at that point and will consider all data.  Some
of the conclusions given below with respect to system  performance may be modified
somewhat in this final evaluation.,                              .

1.     During the  11 week USEPA study period, the AEES.at Frederick, MD did not, on an
       average basis, meetiits performance goals for BOD5,  ammonia, NO3,  TN or TP.
       However, the removal of TSS was significantly better than the 10 mg/l performance
       goal.

2.     Based on the .data collected during this study, it is believed that the AEES has the
       potential to produce,an effluent with: BOD5 <  10mg/(, TSS  < 10 mg/l. Ammonia
       < 1 mg/l,   NO3  < 5 mg/l> TN < 10 mg/l, and fecal coliform <  200 cfu/100ml.
   .    Optimization of methanol feed, and  of the aerobic and anoxic Ecological Fluidized
       Beds will be required to realize this potential.
3.     During the  EPA study  period, the concentrations of BOD5, COD, TSS, and VSS
       entering the AEES process were higher than expected and this  may have had some
       impact on system  performance.  On a mass basis, the system removed about twice
       the amount of organic pollutants it was designed for.  Most of this removal occurred
       in the preliminary Anaerobic Bio-reactor.
4.     The AEES, as presently configured and operated, cannot remove phosphorus to the
       desired level (£.3  mg/l).  Some additional process modification  will  be necessary to
       achieve low phosphorus levels in the  system effluent; or phosphorus removal claims
       for the process should be abandoned.

5.     The AEES was not at true "steady state" operation during the entire study period
      -and procedural  changes by OAI staff took place  during the study which were
       intended to  improve the performance  of the facility; For example, the carbon source
       for denitrification was changed to methanol about two thirds of the way through the
       study  which  had  a significant impact on the effluent  BOD5 and nitrate levels.
       Functional changes at the Ballenger Creek vyWTP, beyond the  control of OAI, also
       impacted  significantly on  the influent wastewater characteristics at  the  AEES
       facility.         ,        '            ••',/'.-.-'              ,         ,

6.    ' The Anaerobic Bio-reactor, designed by Sunwater Systems, Inc.  was essential to the
       successful performance of  the Frederick "Living Machine".  It removed  more COD,
       BOD5, TSS  and phosphorus than all'of the other system components, combined and
       also contributed significantly to solids reduction.           •
                                           14-1

-------
                                                                             Section 14
 7.     The floating macrophytes in the Aerated Tanks were shown to contribute in a minor
        way to nitrification,  probably through  microbial' activity  in the  plant  root  zone.
        However, the AEES could achieve suitable levels  of nitrification  in the Ecological
        Fluidized Beds without any plants in the Aerated Tanks.  The emergent plants on the
        High-rate Marsh do not appear to contribute  significantly to treatment in  this unit
        either.                                                                   .

 8.     The  issue  is  not the basic  capability  of plants  in  providing a contribution  to
        treatment,  but rather  that there are insufficient  numbers  of  plants in the  AEES
        greenhouse  to  contribute significantly.  In the current  AEES  design  there is  not
        enough available water, surf ace on  the tanks to support the number of  floating
        plants  required.  Shallow tanks with a  much larger water surface area would be
        required, and  the cost of a  greenhouse to  cover this increased area would be
        prohibitive.  The main  value of the plants presently used in the AEES is aesthetic,
        although they also have  economic value as a horticultural nursery if plant species
        with some market value are used.

 9.      The High-rate Marsh  at  the Frederick  AEES  facility is  also not  large enough to
        contribute significantly to treatment.  It might be possible to .construct a marsh with
        a larger area, outside  the greenhouse,  and  depend on the plant residues in the
        marsh as the carbon source for denitrification  whereas,  in the current process, it is
        necessary to   add  methanol  as a  carbon   source  to  achieve  denitrification.
        Denitrification cari be achieved in the  final, anoxic Ecological Fluidized Bed which
        means  that  the High-rate  Marsh is not really  necessary  except for  horticultural
    ,  •  purposes.

 10.     The pumice  gravel used  in the Ecological  Fluidized Beds is too soft to withstand
        inter-particle abrasion  and particle loss during  the  backflushing operations  that are
        used to clean the beds. These losses have reduced the depth of pumice by almost
        a foot, in some tanks, during the first year of system  operation.  More effective
        clarification  ahead of  these beds  would  reduce the filtration and backflushing
        requirements and, additionally, the use of a iow density,  abrasion-resistant  material
        should be considered as the media in these beds.

 11.     The Duckweed  Clarifier located after the final Ecological  Fluidized  Bed does not
        contribute significantly to treatment at the Frederick AEES.  However, in future
        systems, a final clarifier may be necessary if the marsh is not used.  The clarification
        provided after the Aerated  Tanks at  Frederick is  inadequate  and results in too
        frequent backflushing of the first Ecological Fluidized Bed.  The Duckweed  Clarifier
        could be  put to use for  this purpose  at Frederick, if  some piping changes  were
        made.                                                                          •

12.     The sludge and  other residuals produced by the AEES at Frederick, MD are slightly
        less than that from a conventional extended aeration process, designed for the same
        performance goals and flow rates.  The digestion occurring in  the Anaerobic Bio-
        reactor at the  Frederick  facility is  believed  responsible for this  difference since
        digestion in this unit results in a 15 to 20 percent solids reduction.  If this Anaerobic
        Bio-reactor is not used  in  future "Living Machines" then  residuals production would
        be at least comparable to conventional technology.
13.    The present worth and total annual costs of the AEES process are approximately the
       same as conventional wastewater treatment technology at flow rates of 80,000 gpd
       or less.  At higher  flow  rates the  conventional processes  are  likely to be more
       economical  to  build  and operate..   At  1,000,000 gpd, for example, the  AEES
                                            14-2

-------
                                                                           Section 14
        process with greenhouses would have a present worth value of $11,500,000, while
        a conventional  oxidation  ditch process  would have  a present worth  value of
        $7,600,000,  Both of these costs represent only the key treatment components and
        not a complete treatment facility.  Common items such as roads, administration and
        laboratory facilities are excluded from both estimates. The higher AEES costs at the
        higher flow rates  are probably a result of the need to utilize several replicates of
        tankage  and  greenhouse  structures,   as compared  to a  few  large  tanks for
        conventional systems.                                 ,    .

 14.     The detention times in the AEES unit  processes  as measured during the  USEPA
        study were comparable to  the theoretical detention times calculated, by OAI.  The
        total detention time for the process (including the Anaerobic  Bio-reactor) was 3.6
        days at a flow rate of 37,000 gpd. The total detention time  for the components
        inside the greenhouse was  2.8 days. The detention time in the Aerated Tanks was
        21  hours  which is comparable to  conventional extended aeration activated sludge
        processes.

 15.     Statistical analysis of the USEPA study  data and the OAI performance data  for the
        Frederick  facility  did not  suggest that,  in  the main,  the, two  data  sets were
        statistically similar.  However, when the data's summary statistics were  compared
   ;     visually, general  similarities  were  noted  between  the  data  sets.   It  was  also
        considered that an objective assessment of either data set would reach the same
        conclusions regarding system performance.

 16.     Sludges wasted from  the  AEES  facility  in Frederick,  MD  are returned  to the
       Ballenger  Creek  WWTP and have no further impact on operations of the AEES
        system. Future "stand-alone" applications of the AEES technology propose the use
        of reed beds for  sludge  dewatering and stabilization.   No such  system  has been
       constructed so the impacts cannot be evaluated.  It is believed that operator time
       will have to increase, and the necessary return of the leachate from the reed beds to
       the AEES  process  for treatment may reduce the claimed treatment capacity of the
       system.    ','„'.,

 17.    The corrugated metal and  plastic  lined  tanks used  at Frederick  are not  the best
       choice for this service  and  are likely to, require  high  costs  for repair  and liner
       replacement during a 20-year design life.  A different type of tank will be used at
       the new facility in Vermont.  This  tankage, based  on farm silo concepts,  is  bolted
       steel with an integral inner waterproof  coating  of plastic or glass.   The cost
      ..effectiveness of the AEES process will be improved  as the number of separate tanks
       required is reduced.

18.    A variety  of bacterial supplements and mineral and organic additives are  routinely
       used in the AEES facility  at Frederick  in addition to  the methanol  used as a
       denitrification carbon source.  The value of these  other  additives is not clear  arid;
       was  not evaluated during  this study.   Based  on  experience with conventional
       wastewater  technology,  effective  nitrification  in  the AEES  process should  not
       require the continuous addition of bacterial supplements.   ,
19.    The OAI "Living Machine" claims to be an ecologically-based process supported by
   ,    solar  energy which is  minimally  dependent  upon mechanical  equipment  and
       chemicals.. In fact, the AEES process utilizes the same mechanical energy sources
       and chemicals as  conventional  wastewater  treatment technologies designed to
       achieve the same performance goals.  In effect, the AEES process is an  extended
       aeration process followed by aerobic/anoxic filtration.  The  plants growing  in the
                                           14-3

-------
                                                                           .Section 14
       system, and utilizing the solar energy,  provide largely aesthetic and horticultural
       benefits.

20.    A predecessor concept known as "Solar Aquatics" was also developed by OAI and
       the lessons learned from this earlier technology  were the basis for many of the
       improvements  utilized  at  the Frederick,  MD facility.    The  "Solar  Aquatics"
       technology is now marketed by others.  It is believed that many of the technical and
       cost limitations of the "Living Machine" discussed in this report would apply to the
       "Solar Aquatics" process also.

14.2  Recommendations

1.     A follow-up study of the Frederick, MD facility  is  recommended to validate the
       potential. performance  expectations  described  above.   It is  assumed  that the
       Frederick system  will be in true  steady state  operation  by  late fall 1995.  An
       independent evaluation of the  1996 performance data generated by ' OAI'. would
       complete this effort.
2.     Operational modifications to the Frederick facility should be considered by OAI. The
       Duckweed Clarifier is now ineffectual but,  with some piping  changes, it could  be
       used as a clarifier after the Aerated Tanks. This would also require a pump to move
       the clarifier effluent back tb the first Ecological Fluidized Bed.

3.     Nitrification  in the first two  Aerated Tanks  at Frederick  could be improved  by
       maintaining a  higher sludge concentration in these tanks  with sludge  recycle  from
       the modified clarifier. Nitrification could also be improved by addition of appropriate
       media  in these  tanks to provide the substrate for the nitrifier organisms.

4.     The Anaerobic Bio-reactor used at Frederick is an excellent primary component  in
       the AEES process  and its continued use is recommended in future  applications.
       Perhaps  the  second  compartment could include  a  deeper,  hopper-bottomed  pit
       instead of the present configuration.  This would allow more time for digestion and
       sludge storage, and reduce the frequency of  sludge wasting.

5.     The 80,000 gpd AEES in  South Burlington,  VT should be  operational  In late 1995.
       This facility incorporates  modifications and "lessons learned" from  the  Frederick
       facility, and it also must operate in a colder climate.   An'independent evaluation of
       the OAI performance data from  this facility  in  late  1996  would  establish the
       capabilities of this  modified system.
                                            14-4

-------
                                    Section 15
                                    References
Grubbs arid Beck (1972). Extension of sample sizes and percentage points for significance
              tests of outlying observations. Technometrics, 14, pp.  847-854.

Parsons Engineering Science, Inc. (1994).  ALCOSAN Diversified Residuals Management
              Program. Parsons ES, Fairfax.                             ,

Parsons Engineering Science, Inc. (1992).  Quality Assurance and Quality Control Manual.
              Atlanta Laboratory.

Parsons Engineering  Science, Inc.  (1994).   Sludge Management Alternatives Evaluation
              Report.  Parsons ES, Fairfax.
                                           15-1

-------

-------
                                   Appendix A
                         Quality Assurance Project Plan
       This Appendix contains the Quality Assurance Project Plan (QAPjP) for the process
evaluation of the Ocean  Arks  AEES in Frederick, MD.   The QAPjP  describes the  Quality
Assurance Plan organization and responsibilities) the objectives of the  plan and the sampling
and analytical procedures used on the project.
                                           A-l

-------

-------
               .         -FINAL, .. , ,    •'••

          QUALITY ASSURANCE PROJECT PLAN
     EVALUATION OF ALTERNATIVE WASTEWATER
              TREATMENT TECHNOLOGIES
                  CONTRACT NO. 68-C2-0102
                WORK ASSIGNMENT NO. 3-18
                       SUBMITTED BY:
            PARSONS ENGINEERING SCIENCE,  INC.
                  REVIEWED AND APPROVED  BY:
EPA WORK ASSIGNMENT MANAGER:
EEC TECHNICAL DIRECTOR:
                                  ROBERT BASTIAN
                                  SHERWOOD REED
PARSONS ES TECHNICAL DIRECTOR:   \/M-*W/J
      ' i              °~ •        J    To / TT
                           y^-^B^H.



PARSONS ES PROJECT MANAGER:
                                 x^/^t-*>
                                  LAUREN EILLMORE
 PARSONS ES QUALITY
 ASSURANCE MANAGER:
                                   ELAINE WILSON
                                                           DATE
                                                           DATE


                                                         2/2.
                                                         / D4
-------

-------
                             TABLE OF CONTENTS
SECTION
PAGE
      ABBREVIATIONS LIST

  1   PROJECT DESCRIPTION

      1.1  General Overview                                                  1-1
          1.1.1    Description of the Advanced Ecologically Engineered System     1-1
          1.1.2    Laboratory Selection Criteria                                1-5
          1.1.3    Statement of Project Goals                                  1-6
      1.2  Experimental Design                                                1-6
      1.3  Critical Versus Non-Critical Measures                                 1-8
      1.4  Schedule                                  "   ••  "   -v •'•'••          1-8
   •   1.5  Quality Assurance Program Organization and Responsibilities            1-11
          1.5.1    Responsibilities                                           1-13
  2   QUALITY ASSURANCE OBJECTIVES

      2.1  Quality Assurance Objectives  ,
      2.2  Quantitative Objects
          2.2.1    Precision
          2.2.2    Accuracy
          2.2.3    Method Detection Limits
          2.2.4    Completeness
      2.3  Qualitative Objectives
          2.3.1    Representativeness
          2.3.2    Comparability
      2.4  Impact of Not Meeting Quality Objectives
2-1
2-1
2-3
2-3
2-3
2-3
2-3
2-3
2-4
2-4
  3   SAMPLING AND  ANALYTICAL  PROCEDURES

      3.1  Sampling Objectives
      3.2  Sampling Locations
          3.2.1     Flow Monitoring
          3.2.2     Tracer Study
          3.2.3     Performance Evaluation
          3.2.4   ^  Residuals Testing
      3.3  Sampling Schedule                   ,
      3.4  Sampling Protocol
          3.4.1     Sampling Equipment     ".
          3.4.2     Sampling Procedure   ...  •
        ,3.4.3     Sample Transfer  ;
      3.5  Sample Handling ,
          3.5.1     Sample Preparation
3-1
3-1
3-1
3-3
3-3
3-4
3-4
3-4
3-4
3-7
3-8
3-8-
3-8

-------
                              TABLE OF  CONTENTS
                                     (Continued)
SECTION
                                                           PAGE
      3.6 Sample Custody
          3.6.1
          3.6.2
          3.6.3
          3.6.4
          3.6.5
      3.7 Analytical Procedure
      3.8 Calibration
Chain of Custody
Sample Labeling
Field Data Sheet
Sample Receipt and Documentation
Sample Storage and Security
  4   APPROACH TO QA/QC

      4.1 Calculation of Results      '
          4.1.1    Data Utilization
          4.1.2    Data Validation
      4.2 Internal Quality Control Checks
          4.2.1    Calibration Standards
         .4.2.2    Spiked Sample Analysis
         "4.2.3    System Blanks
         •4.2.4    Duplicate Analysis
          4.2.5    Additional Internal Quality Control Checks
      4.3 System Audits
      4.4 Calculation of Data Quality Indicators
          4.4.1    Precision
          4.4.2    Accuracy
          4.4.3    Completeness
          4.4.4    Method Detection Limit
      4.5 Corrective Action
      4.6 Quality Assurance Reports to Management
          4.6.1    QA Forms and Reporting
          4.6.2    Quality-Related Training
          4.6.3    QA Results In The Project Final Report

 :     References
 3-9
 3-9
3-11
3-11
3-11
3-15
3-15
3-15
                                                          4-1
                                                          4-1
                                                          4-2
                                                          4-2
                                                          4-6
                                                          4-6
                                                          4-6
                                                          4-6
                                                          4-6
                                                          4-7
                                                          4-7
                                                         4-13
                                                         4-13
                                                         4-14
                                                         4-14
                                                         4-14
                                                         4-17
                                                         4-17
                                                         4-18
                                                         4-25

                                                          5-1
                                         u

-------
                             TABLE OF CONTENTS
                                    (Continued)
SECTION
                                                                            PAGE
                                LIST OF TABLES
1.1       Critical and Non-Critical Measurements
1.2       Project Schedule   '
2.1       Quantitative Objectives
3.1    '   Sample Volumes, Containers, Preservation Techniques
          and Holding Tunes     •
3.2       Field Data Sheet for the Tracer Study
3.3       Field Data Sheet for Water Quality Study
3.4       Field Data Sheet for the Residuals Study
 1-9
1-10
 2-2

 3-5
3-12
3-13
.3-14
                                LIST OF FIGURES
 1-1       Process Flow Diagram for the Ballenger Creek Living Machine
 1-2       Quality Assurance Program Organization                    :
 3-1       Sampling Locations at the AEES Facility in Frederick
 3-2       Chain of Custody Record
 4-1       Operation and Maintenace Log Sheet
 4-2       QA Report Form:  LD Lab. Form 1
 4-3       Quality Assurance Field Adit Checklist
 4-4       Quality Assurance Laboratory Audit Checklist  .
 4-5       QA Report Form:  LD Field Form 1   '
 4-6       QA Report Form:  QAC Form
 4-7       A Report Form
  1-3
 1-12
  3-2
 3-10
  4-3
  4-4
  4-8
 4-10
 4-19
 4-21
 4-23
                                         m

-------
                          ABBREVIATIONS LIST
QAPjP
EPA
OWEC
O&M
AEES
OA
COD
BOD
TSS
VSS
TKN
NH4
NO3    -
TP
DO
Parsons ES
LD
QAC
QAM
PM
TD
MDL
PJPD
PRR
L
HRT
WWTP
COC
NPDES
Quality Assurance Project Plan
Environmental Protection Agency
Office of Wastewater Enforcement and Compliance
Operation and Maintenance
Advanced Ecologically Engineered System
Ocean Arks International
Quality Assurance
Chemical oxygen demand
Biochemical oxygen demand
Total suspended solids
Volatile suspended solids
Total kjeldahl nitrogen
Ammonia
Nitrate                              -
Total phosphorus
Dissolved oxygen
Parsons Engineering Science, Inc.
Laboratory Director
Quality Assurance Director
Quality Assurance Manager
Project Manager
Technical Director
Method detection limit
Relative percent difference
Percent recovery range
Liter
Hydraulic retention time
Wastewater treatment plant
Chain of custody
National Pollutant Discharge Elimination System

-------
                                  SECTION 1
                           PROJECT DESCRIPTION
1.1    GENERAL OVERVIEW
                      i        '              . S         '     '         '       "'"•
       The evaluation of new technologies for wastewater treatment is supported by the
United States Environmental Protection1 Agency (EPA) as required by Section 201 of the
Clean  Water  Act.   Technology transfer programs in  the  Office  of  Wastewater
Enforcement and  Compliance  (OWEC) are. designed  to allow new  and emerging
technology development.  OWEC often, evaluates new wastewater treatment processes or
applications to verify performance, since information provided by the developer of the
technology  is sometimes  incomplete.   These  evaluations are  beneficial in answering
design-related questions, identifying  specific weaknesses  or limitations,  providing cost
dat^ and resolving operation and maintenance (O&M) problems. .In addition, the results
of the evaluation may identify a specific range of conditions under which the process or
technology  demonstrates  maximum or  minimum  performance  efficiency.    These
technology evaluations are an essential first step in, disseminating actual field data-on the
operation of selected processes or techniques.

        The wastewater control technology evaluated  in this  study is  the Advanced
. Ecologically Engineered System (AEES) developed by Ocean Arks International (OA), a
 non-profit educational and research institution.  -The purpose of  this study is to gather
 reliable data and information on the effectiveness of the AEES technology for wastewater
 treatment.                                       s  '
 1.1.1   Description of the Advanced Ecologically Engineered  System
.In May 1992, the  House Subcommittee, on  Fisheries and Wildlife Conservation
 hearings featured the potential benefits of using advanced ecological engineering of living
 systems to clean wastewater.  Since this time, federal funding totaling, $3. 75 million has
                                        1-1

-------
been  provided by  congress for the  development and  evaluation  of OA's  AEES
demonstration facilities in Maryland, California, Vermont, and Massachusetts.

       The Maryland AEES facility, which is  located on  a one quarter  acre lot in
Frederick, was constructed in 1993. and is currently operational. This facility incorporates
the experience gained from previous OA systems in Massachusetts, Vermont, and Rhode
Island, and represents a second generation design of what OA terms a 'Living Machine".
The system is designed to clean wastewater to advanced wastewater treatment standards
using a natural, solar-powered greenhouse instead of chemicals.  The Frederick facility is
the focus of the independent testing program to -be conducted under this work assignment,
since the  facilities in California and  Vermont are  either under construction  or in the
planning stages.

       The Frederick facility, which is called Ballanger Creek AEES, takes sewage from
the neighboring Ballanger Creek Sewage Treatment Plant.  The screening and  degritting
operations at the treatment plant are not very effective,  therefore, AEES often receives
influent that contains scum and grit. The AEES system was originally designed for 40,000
gallons per day (gpd) maximum steady state flow, but the recorded flows have been closer
to an average of 33,000 gpd. The lower flow rates are due to a higher'strength sewage
than anticipated and also the design capacity of the anaerobic bio-reactor (approximately
30,000 gpd).  During the proposed study period, it is anticipated that the three treatment
trains will run at approximate flow rates of 13,300 gpd, 10,000 gpd and 13,300 gpd.

       The process begins-when raw wastewater is pumped from the treatment plant to
the AEES. Once at the AEES, primary treatment of the wastewater occurs in an outdoor
anaerobic bio-reactor, as shown in Figure lrl.  Wastewater is retained within this stage of
treatment for approximately 24  hours,  during  which time the organic  wastewater
constituents are partially broken down by bacteria in the absence of oxygen. Flow from
the bio-reactor is then pumped into one of three treatment trains; the AEES has three
                                                                    i
parallel secondary and tertiary treatment trains.
                                       1-2

-------
                                              FIGURE  1-1
                                PROCESS FLOW DIAGRAM FOR THE
                              BALLENGER CREEK LIVING MACHINE

        A demonstration project of an innovative ecological wastcwatcr treatment technology in.Frederick. Maryland.
            The system is designed, and managed by Ocean  Arks International. The project is funded U.S. EPA.
           WASTl-WATER )
ANAEROBIC
HO-REACTOR
J-stage system for
lombincd BOD reduction,
rSS removal and solids
digestion.            "
.retention lime =
1 day for water.
1 year for solids)
VERATEDTANKS
or biological
reatment using
suspended
microorganisms
retention time  '
= 1.0 day)
iCOLOGICAL
"LUIDIZED BEDS
or tertiary biological
rcalmcnt,
retention time
= 1.5 days)
DUCKWEED
CLARIFIER
final sedimentation.
(retention time
 = 0.5 days)
                                                                                            Methane Gas
floating insulated cover
                                           biosolids recycled to ABRand fed to fish
                                                                                                    -Fish    .
                                                                                                     (or lake stocking.
                                                                                                    bait, or animal feed
                                                     Secondary
                                                    Quality Water
                                                          . Tertiary
                                                       Quality Water


                                                                           Pumice Biofiller
        SWS San Diego, CA.
                                                  HIGH-RATE MARSH for polishing
                                                  effluent to advanced tertiary quality/
                                                  (retention time = 0.5 days)
                                                                                                  Advanced Tertiary  j
                                                                                                    Quality Water    I
                                                           1-3

-------
       Secondary treatment takes place in two aerated tanks in series,  followed  by a
secondary  clarifier.   Wastewater is  retained in the aerated  tanks for  approximately
24 hours (12 hours in each tank) before flowing through the secondary clarifier. Floating
plants such as duckweed, water hyacinths, and pennywort are contained in the aerated
tanks.  Flow from the secondary clarifier is then pumped into one  of the three tertiary
treatment units.   Tertiary treatment is achieved in three pumice stone  filters  located in
series, followed by a tertiary clarifier.   Wastewater is retained in the pumice stone filters
for approximately 36 hours, the buoyant pumice stones in these tanks providing additional
surface area for microbial growth.  The pumice stone filters also contain plants such as
duckweed, oregano, cedar, foxtail, and elephant ears. Wastewater flow from the pumice
stone filters is then pumped into one of three high-rate marshes, which contain various
plant species; any accumulated sludges are settled out and removed at the tertiary clarifier
tanks prior to the marshes.  Each marsh has a capacity of 4,000 gallons and a retention
time of 10 hours.  The gravel media and plant roots in the marshes perform the final
treatment of the effluent to meet advanced wastewater treatment standards.              . >

       Other demonstration facilities  in California, Vermont, and Massachusetts will be
evaluated  as part of this work assignment.   The  facility under  construction in San
Francisco,  California,  is a skid-mounted demonstration polishing facility designed to treat
approximately 30,000 gpd  of secondary effluent  to  meet  California Title 22   reuse
standards  (oxidized,  filtered  to a  very low turbidity standard,  and  disinfected to
2.2 coliforms per 100 ml). This facility is planned to be operated for a minimum of six
months.                                                               .

       The Chittenden County, Vermont facility is currently in the planning and design
stage.  It is. intended to treat, approximately 80,000 gpd.  The design is based on the same
principles used in Frederick and San Francisco but adapted to Vermont climatic conditions
and wastewater influent temperatures.

       The Harwich, Massachusetts,  demonstration project involves the  evaluation, of a
'Lake Restorer" bioremediation system located in Flax Pond in this community.   Flax
                                         1-4

-------
Pond is polluted due to long-term seepage from adjacent septage  pits over the years.
Ammonia nitrogen is believed to be the pollutant of major concern.  The, Lake Restorer
device is; essentially an airlift unit suspended from a floating raft.  The airlift raises pond
water through a media and. over the vegetated surface of the raft.  -

1.1.2  Laboratory Selection Criteria                            ,

       The laboratory or laboratories selected for this study will conform to the following
criteria:           -   .   ,                   /       ,                         " . ,
' .        ,'            '     '                 --".I.-      f      - ^     ^         _        -
       •   Have an active quality assurance (QA) program that is based on a written QA
           protocol;         '                                  ,         .
       •   Have a designated QA staff member with the authority to implement corrective
           actions: and                                          i   .
       •   Have demonstrated good analytical performance based  on  a federal  or state
           performance sample program, or a sample splitting program.

        Specific QA components that will be evaluated for the laboratory will include the
 following:
        •  Documentation of routine quality control analyses including  spikes, duplicates,
           blanks,  unknowns,  calibration standards,  detection  level  standards,  and
   ,         performance standards;                                            •
        •   Assignment of sample accession numbers to all samples to ensure proper cross-
            reference, of analytical results;
        •   Proper sample storage procedures to ensure sample integrity;
       "•   Documentation of routine maintenance of analytical instruments;
        •   Documentation of routine calibration of analytical instruments;
        •   Certification or training of laboratory staff in general laboratory procedures
            and specialized instrumentation; and
        •   Documentation  of  the  successful use of corrective actions -and follow-up
            evaluations to identify, resolve, and prevent problem conditions.
                                          1-5

-------
1.1.3  Statement of Project Goals

      The goals of this study are to:
      •   Evaluate the  performance capabilities  and cost effectiveness of the AEES
          technology under demonstration in Maryland;
      •   Compare the influent, effluent and sludge data gathered by Parsons ES to
          influent, effluent, and sludge data gathered by OA and analyzed by a certified
          laboratory to determine the possibility of using OA influent, effluent, and
          sludge data in the evaluation.  The degree of water quality sampling will be
          kept flexible to consider the  use of the OA data analyzed by the certified
          laboratory;
      •   Comparison of the  capital  and operation and  maintenance  costs of the
          demonstration facilities to more conventional wastewater treatment approaches
          for meeting the same water quality objectives;
     - •   Prepare one  draft report that includes  process  descriptions of the Living
       '   Machine technologies (i.e., direct observation and  literature  comparisons),
          findings on the Ballanger Creek  AEES process performance evaluation, and
          comparisons  to  conventional wastewater treatment  systems  (e.g.,   land
          treatment, sand filters, BNR);
      •   Prepare a second draft report that provides an assessment of the status and
          potential  for future application of the  Living Machine technology  for
          wastewater treatment; and       -
      •   Prepare two final reports based on revisions made to the two draft reports.

1.2   EXPERIMENTAL DESIGN

       The Ballanger Creek AEES performance study will consist of the following tasks:
       •  Flow monitoring;
       •  Tracer study;
       •  Performance evaluation;                      .'                  .   '
                                        1-6

-------
 -      •   Residuals testing; and                                    •
       •   Collection of available,  existing  data at  OA AEES  facilities in California,
          Vermont, and Massachusetts.          .        .

       A brief description of these tasks is presented in the following paragraphs.

       Flow Monitoring: Influent and effluent flows will be monitored and recorded to
determine the average daily influent and effluent flow rates through the Ballanger Creek
AEES.   •    ''.'••     -              .'.:._   ;. ._'  •" ;    ....   -"••  , '   '
       Tracer Study:  A tracer study will be conducted to determine the detention time
            ;                     "•.-,'•,•'        .     -           >' •
within each major system component of the selected treatment train. Lithium chloride will
be the tracer compound that is used due to its conservative properties.  The detention time
for seven components of the system will be determined. Discrete  wastewater samples will
be collected hourly up to three times the theoretical detention time and will be  analyzed
for lithium concentration.
       , Performance Evaluation;  A performance evaluation will include  water quality
testing to determine the treatment achieved in the selected, treatment train. Water quality
parameters that will be tested for include total and soluble chemical oxygen  demand
 (COD), total  and soluble biochemical oxygen  demand (BOD)'  total suspended solids
 (TSS), volatile suspended solids (VSS), total kjeldahl nitrogen (TKN), ammonia (NHU),
 nitrate (NO3), total phosphorus (TP), pH, dissolved oxygen (DO), temperature, and fecal
 coliform.  <3rab samples will be collected for measurement of pH, DO, temperature, and
 fecal coliform; the remainder of the samples will be 24-hour composite samples.

       Residuals Testing: Analytical testing will be conducted  on the process' residuals
 (i.e.,, sludge and plants), to determine the characteristics of the residuals resulting from the
 wastewater treatment process in. the selected treatment train. Residual  samples will be
 tested for pH, percent solids  (sludge only), ;TKN,  TP, fecal coliform, and the  Part  503
 metals.
                                        1-7.

-------
       Data Collection at Other OA Facilities:  All available data from OA systems in
California, Vermont; and Massachusetts will be obtained through site visits. Key areas of
information to be obtained will include design, operation and maintenance requirements,
performance data, and applicability.   Design and cost data are  the  only  information
available for the Vermont system, since this facility is still in the planning and design stage.
                                                                        ;    !
1.3    CRITICAL VERSUS NON-CRITICAL MEASUREMENTS

       Critical measurements are defined as 'measurements that are necessary to achieve
the project objectives" (EPA, 1989).  Procedures for critical measurements will follow
EPA-approved methods as described in Section 3.  A list of critical -measurements to be
performed is provided hi Table 1.1. Table 1.1 also lists non-critical measurements, which
will be analyzed to better define process operations, document process control data, or
provide general background information.  The system conditions (i.e.,  test  operating
parameters and process controls) for each measurement are noted in Table 1.1.  System
conditions  are  defined  as parameters that  are routinely  monitored to  ensure proper
operating conditions for critical measurements.

1.4    SCHEDULE                              .
       The time sequence of the study components is presented in Table 1.2. The  study
will be conducted over an approximate seven month period.  Assuming approval of the
site-specific Quality Assurance Project Plan (QAPjP), the field activities will tentatively
begin in mid-March, 1995. Prior to beginning field activities, an initial background review
of the Ballanger Creek AEES wastewater, flow, and sludge data will be conducted.  The
facility has been operational for nearly  one year and during this  time wastewater and
sludge samples have been taken to determine the effectiveness of the treatment, system.
Effluent flow rates from three treatment trains have also been monitored.  This historical
 OA data will be collected and reviewed.  Since changes have been made to  the three
 treatment  trains  to make the system more effective, some of the historical  OA data
 obtained may not be appropriate for comparison to the current treatment system.  The
                                        1-8

-------
I
a.
 a
 I
  so

S o
 1
tmtmts
2 2 2 2 22 222 ~
J 2, 3, 2, &.&•&•&-&
jsaaa'aa aaa
a a a a a -a a a a
                      a a a a a
        llllljljlit Jill
                             H

                             1
                             S

                             *
•1 1


II


13
            1     1  f
            6: •    ^  5»

            |>S S Sl'-S-S
            3 5 «^ as . J « a
                               I
                                 5 I «

                                 III
       I
I I

i S.
 §
 CQ



 I
   .

 ,  8  8
     1
   ,    .

   Q D Q O ^5 to
      O O w J«
      « « H >
 O O
 U U
§
                   ii
S

                          •a
                                  •§
                                         I
                                         g
                                   •8-
"
       V 3*
         Q &.H
                    1-9

-------
                       TABLE 1.2   PROJECT SCHEDULE
  Task Description
         Date
  Start of Data Collection and Review of O A Data from
  Frederick facility                              •

  Submission of Quality Assurance Project Plan and Health
  and Safety Plan

  Start of Technical Direction

  Start of Field Testing

  Start of Additional Field Testing


  Start of Data Collection from OA facilities in MA, VT, and
  CA

  Submission of draft "Future Potential of Living Machine
  Technology" report

  Submission of draft "Frederick AEES Living Machine
*  System" report

  Receipt of comments on draft reports

  Submission of final reports
    February 1, 1995


    February 15, 1995


    February 1, 1995
- {
    February 27, 1995

9 weeks after start of field
         testing

      June 1, 1995


    August 15, 1995


    August 15, 1995


    September  1, 1995

   September "30, 1995
                                        1-10

-------
changes that have taken place and the reasons for the alternations will be obtained during
the background review.                                                       .   '

Field data collection will' begin in late February and is anticipated to continue for 9 weeks.
The  data collection will  be extended 4 weeks  if OA data analyzed by  the  certified
laboratory does not statistically compare to the gathered Parsons ES data.  The extended
sampling period will provide additional data for the database and a broader view of the
treatment achieved by the system. .Following  data collection and evaluation, two draft
reports will be submitted to the EPA.  Based on EPA revisions, revised draft reports will
be submitted for EPA's peer review process. Two final reports will be submitted to the
EPA following incorporation of peer review comments and EPA approval.

1.5    QUALITY ASSURANCE PROGRAM ORGANIZATION AND
RESPONSIBILITIES
       Quality assurance program organization for this study is shown in Figure 1-2 and
includes individuals' from/each party participating in the study.  Due  to  the  need  for
specialized  expertise  in  natural  systems for the treatment  of wastewater,  Parsons
Engineering Science, Inc.'(Parsons ES) will use the services of Environmental Engineering
Consultants  (EEC)  to  complete the assignment.   Parsons  ES  will  have  overall
responsibility for QA  Parsons ES Atlanta Laboratory will have QA responsibility for their
portion of the work.
        To  implement an  effective  QA  program,  the QAPjP  includes the following,
 assignments:                    :                   ,         .                     ,
        •  Laboratory Director (LD) -The. laboratory and field monitoring .organizations'
      ,    will each assign a LD who will be responsible for maintaining daily quality
           control of all sampling and analysis  activities;             •   ...
        •  Quality Assurance Coordinator (QAC) - The laboratory and field monitoring
           organizations will each assign a QAC who will be responsible for confirming
                                        1-11

-------
                                  FIGURE 12
              QUALITY ASSURANCE PROGRAM ORGANIZATION
  TECHNICAL DIRECTORS
  Sherwood Reed (EEC)
Billy Komegay (Parsons ES)
 ^^^^^^fy"j^^^^s^f^^^^o^^s^y^
    LABORATORY
 QUALITY ASSURANCE
    COORDINATOR
     Greg Jones
                                     USEPA
                            WORK ASSIGNMENT MANAGER
                                  Robert Bastian
        PROJECT .MANAGER
         Lauren Fillmore
ANALYTICAL
LABORATORY
 DIRECTOR
   TBD
                QUALTTY ASSURANCE
                    MANAGER
                   Elaine Wilson
    HELD
 LABORATORY
  DIRECTOR
James Salisbury
      HELD
QUALITY ASSURANCE
   COORDINATOR
    Lisa Allan!
                                       1-12

-------
          quality control  of all laboratory  or  field activities by conducting  monthly
  _      internal QA reviews;                 .
      :•   Quality Assurance Manager (QAM);- A QAM will be assigned to the project
    ".     who will be responsible for overall project  QA and for coordinating QA
          activities of the laboratory and field monitoring organizations;
       •   Project Manager (PM) - The PM will interact with the QAM to ensure that the
          QA objectives for the project are achieved; and                 .

technical Director(TD) - The project TD will ensure that quality assurance is addressed
in all technical management aspects of the study.

1.5.1   Responsibilities                                                    :
       As  shown in Figure 1-2, the LDs from each organization will provide quality
control (QC)  data to the organization's QAC.  QACs will report to the QAM and the
QAM will report to the PM   The QA  organization  can function independently of the
technical management  organization, Responsibilities of each of the QA staff are outlined
as follows:           •
 by:
Laboratory Director: The LD maintains daily QC of all laboratory/field activities

•   Ensuring that QC documentation. including chain of custody (COC) forms,
"    laboratory notebooks, calculations, analytical data, and QC data is compiled;
•   Maintaining  QC  procedures including  calibration  and internal  standards,
    duplicate analyses, and spike sample analyses;
•   Maintaining acceptable analytical and reporting schedules to ensure that sample
    analyses or field measurements are performed in a timely manner;
•   Preparmg;monthly reports using LD Form 1  (Section 4), which summarizes
    laboratory and/or-< field analytical results, QC analytical  results,  and any  ,
   , corrective action(s) required and performed.
                                         1-13

-------
       Quality Assurance Coordinator;   The QAC monitors the performance  and
adequacy of the QC checks for all laboratory and/or field activities by:
       •  Verifying documentation by reviewing COC forms, laboratory notebooks (or
          other appropriate data reporting systems), calculations and analytical data, QC
          data, and the LD Form 1;                            ,
       •  Verifying the'performance of QC procedures including calibration and internal
          standards, duplicate analyses, and spike sample analyses;
       •,  Preparing monthly reports using QAC Form 1  (Section 4), which consists of
          the QAC's comments on the review of analytical or field QC data including
          identification of possible QC discrepancies;
       •  Preparing  special reports to notify the QAM and/or PM (within 24 hours) of
          any discrepancies or required corrective actions;
       •  Maintaining and updating the organization's QA file, which will include LD
          Form 1, QAC Form 1, and any special reports to the QAM and/or PM.

       Quality Assurance Manager: The QAM maintains and coordinates QA of all
                e
laboratory and field activities by:       '           ;
       •  Verifying results from LD Form 1;
       •  Verifying QA activities noted in QAC Form 1;
       •  Verifying that reports are reviewed by the Technical Directors and that  they
          have signed  a project review  sign-off sheet, as  required by .the Project
          Management Plan (ES,  1992);                 .    • ,  '             ••;.',
       •  Verifying that the analytical schedule is being met;
       •  Preparing monthly reports using QAM Form, 1  (Section 4), which summarizes
          analytical  results and field data, QC analytical results, QC discrepancies, and
          corrective actions taken to address QC discrepancies; and                ,
       •  Maintaining and updating the project QA files, which include LD Form 1, QAC
          Form 1, QAM Form 1,  and any additional QA reports.
                                       1-14

-------
       Project Manager: The PM ensures that overall QA objectives for the project are
met by:         '      "        '                     '     ,
     ' ;•  Reviewing and verifying monthly QAM Form 1 reports; and
       •  Initiating corrective actions identified by the QAM..

       Technical Director: The project TD ensures that QA program requirements are
being met and that the technical objectives of the project are achieved by:
                                                             i          .  • •
    "*  *  Renewing and verifying monthly QAM Form 1 reports.

       Preparation and submittal of QA report forms is described in detail in  Section 4.
 Table  1.1  delineates  each  organization's responsibility  in  performing  the  critical
 measurements for this  study.. In addition, the laboratory will be responsible for providing
 sample containers,  receiving samples, and ensuring the sample handling procedures are
 followed as described in Section 3.
                                         1-15

-------

-------
              -•         .           SECTION 2        •..'-.-• ....
                        QUALITY ASSURANCE OBJECTIVES

 2.1    QUALITY ASSURANCE OB JECTTVES
"  "       \      '"••'-/'•'•      "• '         - ,
     ,   The QA objective of this project is to gather sufficiently precise and accurate data
 to permit the evaluation of the AEES Living Machine in Frederick, Maryland.  Chemical
 analyses of wastewater and residual samples vail be  conducted using EPA-approved
 methods. The collected data includes the following:
    ,   •  Concentrations of lithium in each discrete sample collected for the tracer study;
        .  Concentrations of COD,  BOD, TSS, VSS,. TKN, NH4, NO3,  TP in each
           wastewater composite sample;            ,
        •" pH, dissolved oxygen, temperature, and fecal cdliform in each wastewater grab
            sample;           ,         •;                       .-•.".'
        •   Concentrations  of TKN,; TP,  fecal coliform,  and Part  503 metals in each
            residual sample; and
        •   pH and percent solids (sludge only) in each residual sample.

        The collected data should be suitable for determining the following:  ,
1        -         '            - •     .,•<--     *..-•'".."   7
        •   Conventional pollutant  concentrations,  wastewater  flow  rates, and tracer
            concentrations in the wastewater;
         •   Removal of conventional pollutants by the AEES;,and       •   '
         •   Detention time of each-major system component.
  2.2    QUANTrrATTVE OBJEC1TVES
         A summary of the quantitative objectives for this study  are shown in Table  2.1.
  Descriptions of each of the QA objectives are provided in the paragraphs below.
                                        •'2-1

-------








*



1
H
ci §
S i
£Q £H^
^ S
^^ r^t
c
E~*
1



















n
8
g ^
5C?
Cr*
p, »-•
SB
|* g §
3 5 fe.
^ ^
s^

1 1
£
S
Q

|





1
•s
S











1




Measurement

* -


°$?°$?005?£S?
O\ ON CA w\ OS O\ ,CA O\- O\
Q
cs es c5 S S P ts
•H -H -H -H ' ' -H S -H
•H

^». ^-. • Q
^> T^ CQ
eoooS-S-oSo
CSCStSCSootSgW
en en O
SSTt'^'Tt'^'riH"^
eg
"a
Bh CtO W> BO "5b "5b *M E *5b
EEEEEEE--E
"So .




a K
n o o — • «•« o
*>^ <•-* o o v v m V) m






t>
3
.a
**
•£
CO
&
S'SSS5SS^S
5 5 5 5 5 5 • 5 - 1 5
???????55?




0 0
3 1 a I
2 S 2 S
Q Q* Q" Q" w co Z Z *
OOOOcocoSSS
OOffl«H>HPZ
^



So o o o o o o
C7k Ok Ok Ok Ok Ok Ok

» s E s
-H -H | ' ' ' -H '
-H
' ' 1 ' '

s s s • • ' •. a •

Q 0
o d S ' ' 0-
BO
^b ^5i) , E 3 O "5i> "^b "Bb
E E _,- K • E E E ,
00 0.
• E




' .S .S .2
>, Sx S,
I 1 ' 1 2 2
c*l v* in "5 "C *5 ^s ^s
in VD vD --5 *s .M «c «£
co en en ti. U- U. co CO






§
m
en
"-S 00
** Ofl CtO
^ "a 13
Gj Eo co
s -5s a ss "E. "B ss s
^. *5 *O i ** «5 *S «S JS
•? k? -3 »? *? *? «^ k?^
>^S3^>^^>


g
S? <»
. £• ' S
li.J
ex ^ .5 —
**> C CO ?• ^
o a. o. s ' g .a ^ g
Z HH o,H Q Jt
2-2



g




'

i

i
60
{



•o
o
s
M
1
Ok
CO






o


1
££
55



M
Fecal coliform




o o
_ Ok Ov

o
en
•H



o
en

1 S
•5 •
> 0
BO
1
*."





* <*">
£ 1






o
3
.a
"•S s
CB
&
O O
W) bo
"O "O
3 3
CO CO



en .
Part 503 Metal
Percent solids










.


i
1

'„' i
i i
° I
•^ s
ok .3
" 8 - e
- Q |
<^« CO g
g a. £g
|||l

.Slip
. ct< c L.
~ 1 S =
,in g " a
J5 'e ^ M
-r 1 1 ^
(Jl "O .Q °
CS 09 JS ^j
'»* Jo '*' S
^ *j S
• i 1 1 1
• ."i >.
a
• *- 5 ° 1

O w " *n
i 1 = 1
I i "s 1
ti Z3 to w
Sw w rt 
-------
2.2.1   Precision                        ,
       Precision objectives for all of the chemical' analyses, except those for pH, are  •
presented as relative percent  difference (RPD) of duplicate  analyses.   The precision
objectives for pH are listed in pH units,and are expressed !as limits for duplicate analyses.
The duplicate or matrix spike duplicate analyses will be performed on at least 10 percent.
of the samples collected for analysis. In cases where more than two replicate observations
are made, a relative standard deviation will be utilized as an estimator of precision.
Equations used to estimate precision are presented in Section 4.

2.2.2  Accuracy
       Accuracy objectives are expressed as the percent recovery range (PRR) for spiked
samples.  Accuracy objectives for T'S.S, VSS, fecal coliform, DO (field measurement) and
pH (field measurement) are  not available for this study.  Ten percent  of the samples
collected for chemical analysis will be spiked. Laboratory control samples will be used to
determine accuracy for BOD and COD analyses.      '

2.2.3  Method Detection Limits

       Method detection limits are presented in Table 2.1.

 2.2.4  Completeness
       Completeness objectives for chemical analyses are to obtain 90 percent of all data
 within allowable limits for precision and accuracy.

 2.3    QUALITATIVE OB JECTTVES

 2.3.1   Representativeness
        The objectives of the  sampling  program are  to  collect samples  that will be
 representative  of the' sample  type.  , For example,  24-hour  composite  samples of
 wastewater will be collected from the research site once per week over a period of several
                                         2-3

-------
weeks to account for daily variation in pollutant parameters. This data and potentially the
existing OA data will be analyzed for possible trends in daily variation.  If such trends
become apparent, the sampling schedule will be modified accordingly to maintain the QA
objectives.  The field activities will continue for a minimum of 9 weeks, and will  not
address seasonal variation.

2.3.2   Comparability

       Standard measurement units "for all critical measurements are listed in Table 2.1.

2.4    IMPACT OF NOT MEETING QUALITY ASSURANCE OBJECTIVES
                    4
       The overall impact  of not meeting one or more of the QA objectives will be to
reduce the validity of the database.   Therefore, whenever possible, samples will  be
reanalyzed if the data are outside the allowable Q A objectives.           ,
                                       2-4

-------
                                  SECTIONS
                   SAMPLING AND ANALYTICAL PROCEDURES

3.1    SAMPLING OBJECTIVES

       The main objective of the sampling program is to (1) collect representative samples
of wastewater from the selected treatment train in the  AEES,  (2) measure wastewater
flows, and (3) define the detention time in major system  components.  The assumption of
representativeness for the conventional pollutant analytical samples will be satisfied by
collecting samples using sampling techniques that are appropriate to the particular waste
stream. The variability of the constituents in the wastewater will be assessed by collecting
sufficient samples over a period of time.
          " •         •                                 f      '            r .'
3.2    SAMPLING LOCATIONS

3.2.1  Flow  Monitoring
       The AEES currently has flow monitoring devices on the three discharge pipes from
the  marsh  unit.  These devices have provided OA with accurate effluent flow data.
Effluent flow data recorded from the monitoring device will be used to determine the
average daily flow through the selected treatment train.  Influent flow monitoring devices
are  not currently installed at the facility.  As a result, a flow monitoring device will be
installed on the influent pipe to the first aeration tank of the selected treatment train for
this evaluation.  Data from the influent monitoring device will be used to determine the
 average daily flow into the  selected treatment train.  The OA effluent flow meter and the
 influent flow meter will be calibrated prior to the start of the field studies.
                                        3-1

-------
                                AEES FACILITY IN FREDERICK
         A demonstration project of an innovative ecological waste-water treatment technology in Frederick. Maryland.
             The system is designed, and managed by Ocean Arks International. The project is funded U.S. EPA.
            WASrUWATHK
               INPUT

 ANAEROBIC
 BIO-REACTOR
 3-stagc system for
 combined BOD reduction.
 TSS removal and solids
 digestion.
 (retention time =
 1 day for water.
 1 year for solids)
AERATED TANKS
for biological
treatment using
suspended
microorganisms
(retention time
 a 1.0 day)
floating insulated cover
                                                                                      Methape Gas
                                     recycled solids
                    digested solids

               Solar Energy
                                                                       ~~"7F	*  (    Compost  j
ECOLOGICAL  '
FLUIDIZED BEDS
for tertiary biological
treatment.
(retention time
 3 l.Sda>.s)
                                           biosolids recycled to ABR and fed lo fish
                                                    Secondary     |
                                                   Quality Water   I
                                                                                                     Fish
                                                                                                  for lake stocking.
                                                                                              I   bait, or animal feed
                                                                                              Tertiary
                                                                                           Quality Water
DUCKWEED
CLARIF1ER
final sedimentation.
(retention time
 s 0.5 days)
© SWS San Diego. CA.

     udge Sampling Location
   Water Quality Sampling Location
   Tracer Study Sampling Location
                                                 HIGH-RATE MARSH for polishing
                                                 effluent to advanced tertiary quality.
                                                 (retention time = 0.5 days)
                                                              3-2
                                                                                             j  Advanced Tertian
                                                                                             I    Quality Water [
        (1) may be moved to after first pumice stone filter.

-------
3.2.2  Tracer Study
       The tracer study will be performed at several locations throughout the system, as
shown in Figure3-1, to determine the detention time and performance of the major system
components. Wastewater samples will be collected at the following seven locations:
       •  Marsh;            •   ,                                        -    ./
       •  Final clarifier;                                              -
               >   -                   .   -             }    • •             '
       •  Three pumice stone filters in series;
       •  First pumice stone filter;
       •  Two aerated tanks in series;
       •  First aerated tank; and    '     ,                                :
        •  Anaerobic bio-reactor.                    •

. the tracer study will conducted at the end of the process  train  and work forward to
 prevent any influence from previous tests.
                         •             '           -•''•',     i •   *       •
 3.2.3  Performance Evaluation
        The performance  evaluation will' include  water quality  testing.   Wastewater
 samples will  be collected  from the following six  sampling  locations,  as shown in
 Figure 3-1:                  ^                                  ,
        ••"  Raw sewage to anaerobic bio-reactor;               • ;  . •      -
         •   Anaerobic bio-reactor to first aeration tank;                           .
         •   Clarifier following second aeration tank to first pumice stone filter;         !
      "   •   Third pumice stone filter to final clarifier;                 .•   _  •  .•   :      -
         •   Final clarifier to marsh; and          ;               ,
         •   Marsh effluent.     .               '      .               •               '

         There has been some discussion about.,the usefulness of the sampling location from
  the final clarifier to the marsh.  -OA indicates that there is little difference in the  water
                                          3-3

-------
quality from the third pumice stone effluent to the final clarifier effluent.   There does
appear, however, to be a significant difference in water quality from the first pumice stone
filter to the second pumice stone filter. If after review of OA data this is indeed trie case,
then the sampling location will be switched to the area between the first pumice stone filter
and the second pumice stone filter.

3.2.4  Residuals Testing

      Wastewater sludge samples will he collected from three locations in the treatment
       "*•                            ,
process  including the anaerobic bio-reactor, the clarifier after the aerated tank, and the
final clarifier after  the pumice stone filter.  Five plant  samples  will be collected in the
treatment process (locations to be determined).

3.3   SAMPLING SCHEDULE

      The field activities are anticipated to begin in late February 1995, and will continue
for approximately 9 weeks (13 weeks, if necessary).  Flow  rate measurements and the
tracer study will be performed in conjunction with the water quality sampling.

3.4   SAMPLING PROTOCOL

3.4.1  Sampling Equipment                              •   > .

      The sampling equipment used in this study will consist of automatic Isco samplers
     ^                                ,
and manual aids such as sampling poles. All sampling equipment that is placed in direct
contact with the sample will be made  of, or lined with, inert non-toxic plastic materials,
Teflon, stainless steel, or glass, and will be equipped with lids made of similar material.
The required container type is shown in Table 3.1.  All sampling equipment, including
automatic samplers will be cleaned and inspected on-a routine basis.

      Prior to the start of the first sampling round,. reusable automatic sampler tubing
will be scrubbed with hot  water .and detergent then rinsed several times with tap water,
followed by distilled or deionized water and finally rinsed three times with the wastewater
                                        3-4

-------
                             TABLES.!

SAMPLE VOLUMES, CONTAINERS, PRESERVATION TECHNIQUES AND HOLDING
'  .••     '                 .   •  -TIMES      '•'   ."• •    ' ' ' •    :     ' •'-  •
(
Analysis
COD, total and soluble
BOD, total and soluble
TSS
vss
TKN '. • ,
NH4
N03
TP
Lithium '
Fecal coliforms
Fecal coliforms
Part 503 metals
TP
TKN
Percent solids
Matrix ;
Water
Water
Water
Water
Water
Water
Water
Water
Water
Water
Sludge/Plant
Sludge/Plant
Sludge/Plant
Sludge/Plant
- Sludge
Minimum
Quantity
Required
0.25 L x
l.OL
1.0 L
- '
1.0 L
. - ' •
• . .' •- ' '

0.25 L
0.12 L
0.12L/10g
1.0 L / 10 g
1.0 L / 10 g.
-710g
: -
Container
Type
Plastic
< Plastic
Plastic
Plastic
Plastic
Plastic
Plastic
Plastic '
Plastic
Sterile plastic
Sterile plastic
Plastic
Plastic
Plastic
Plastic
Sample
Preservation
2mlH2S04/l 
-------
to be sampled.  After the sampling event, the tubing and collection container will be rinsed
with tap water.  Prior to subsequent sampling events, the tubing and collection container
will be flushed three times with the wastewater being tested.   A dedicated automatic
sampler will be located at each sampling  location.  Each automatic sampler will  be
calibrated according to manufacturer specifications! A notebook will be maintained by the
person performing the sampling and will note the cleaning, inspection,  and calibration of
all samplers used in this study.  Manual  sampling aids such as sampling poles will  be
designated for sampling only one type of sample (i.e., pumice stone filter effluent).  This
equipment will be rinsed with the wastewater being sampled and wiped clean prior to each
sample collection.                                           •

       All sampling containers and labels  will be supplied by the laboratory.  Whenever
possible, new sample containers supplied and cleaned by the laboratory will  be used and
will not require pre-cleaning by the field team. Prior to initial sample collection, sampling
containers (Isco- automatic  sampling containers, grab samplers) will be  cleaned according
to the following standard EPA procedures:                            '_
       •   Wash with synthetic, biodegradable, non-phosphate detergent;
       •   Rinse with hot tap water;                .                             .
       •   Rinse with 20 percent hydrochloric acid;
       •   Rinse with tap water;
       •   Rinse with 20 percent nitric acid;
       •   Rinse with tap water;        ••••-,
       •   Rinse with distilled or deionized water; and
       •   Allow to dry.

       All cleaning using  the  above procedure will be conducted in  areas of adequate
ventilation and away  from areas that  could subject the freshly cleaned equipment to
airborne contamination.  Further, personnel engaged in cleaning will wear appropriate
dress including laboratory coats and safety glasses.
                                         3-6

-------
3.4.2   Sampling Procedure

       Wastewater samples will be collected from six locations once per week for at least
nine weeks  by Parsons ES personnel and will consist of 24-hour, time-proportioned
composite samples collected with portable automatic samplers and grab samples.  Samples
will be chilled to 4°C during composite sample collection.   Composite samples will be
used  for conventional  pollutant  characterizations;  grab  samples will be used  for
.measurement of fecal coliform, pH, temperature, and dissolved oxygen.  After collection,
the wastewater samples will be stored On ice.  ,    ,  ,

       Samples of residual sludge and plant tissue will also be collected by Parsons ES
personnel.   There will be three sludge grab samples taken on different days from three
locations and five plant samples taken from locations within the treatment  train.  The
samples  will be  stored on ice until shipped to the laboratory.  EPA procedures will be
         '  ~"   " .    ' .     -       '' •                     '           .      ',"..'*-,..
followed for all sampling.                 .

       The tracer study will be conducted by adding a solution of lithium chloride, in a
single batch; to the influent of the major system component being tested.  The testing will
start from the end of the treatment train and proceed backwards until all components are,
tested.  The lithium chloride solution will be  prepared by dissolving seven pounds of dry-
lithium chloride in  each ten gallons of water required.  Approximately one gallon of the
 solution will be needed for every 10,000 gallons per day of actual flow into the treatment
train. As  a significant amount of heat is released during the dissolution of the lithium
 chloride, care must be exercised during preparation of the solution.

        Sampling of the' effluent from the  system component being tested will begin after
 one-quarter of a theoretical hydraulic retention time (HRT) has passed and will continue
 up to three times the theoretical HRT. Discrete samples will be  collected on an hourly
 basis using an automatic discrete sampler.  Samples will be collected in plastic containers. .

  •      Influent and effluent flow rates will be  measured for one of the treatment trains.
  The effluent flow meter has been installed by OA staff.  The instantaneous effluent flow
                                         3-7

-------
rate is  currently recorded,  however, the software for totalizing the flow is not yet
functional. At this time OA staffperform calculations to' obtain the totalized effluent flow.
Flow data will be obtained in this manner if the software is not available at the time of the
sampling. The OA calculations will be reviewed to verify the results of the Calculations.
An influent flow meter will be installed to the selected treatment train.  The flow meters
will be calibrated prior to  the start of the sampling  session.  Documentation of the
calibration will be retained in the project file.

3.4.3  Sample Transfer

       Samples for this study will be analyzed by the Parsons ES laboratory,  with the
exception of fecal coliform.  Fecal coliform. will be analyzed by a certified laboratory,
different to that already used by OA for coliform analyses.  The fecal coliform samples will
be hand delivered to this laboratory.  Other -samples will be delivered via ah  overnight
courier service to the Parsons ES laboratory in compliance with hazardous waste transport
regulations.  All samples will be delivered in iced containers within 24 hours of sample
collection. Samples which are not immediately delivered to the laboratory will be stored
at 4°C in a secured refrigerator. Upon receipt of the sample by the laboratory, the sample
will be immediately refrigerated or analyzed. .The laboratory will receive chain of custody
forms and field sheets for each sample.

3.5    SAMPLE HANDLING

3.5.1  Sample Preparation               -

       A sufficient volume of wastewater will be collected to conduct the  chemical
analyses. The minimum sample volume required for each chemical analysis is presented in
Table 3.1. Composite samples will be stored hi an iced or refrigerated container during
collection. Immediately following collection,' the samples will be preserved according io
the techniques listed in Table 3.1. The lids of the sample containers should be taped shut
and samples will be shipped to the laboratory in iced coolers to maintain a temperature of
4°C or less.   A description of the  type  of container,  container  preparation, and
                                        3-8

-------
preservation techniques for  each critical measurement is presented in Table 3.1.  The
following information will be collected for each sampling event:
            1  ' -  * •   ' • • .    .    -    -•        '      - •         •  *      "   '*••".
     ,  ,•  Date and time that each sample is collected;
       •  Weather conditions;             r    ,        -      *              '    . '
       •  Field pH,  temperature, and dissolved oxygen for each wastewater and sludge
       .   sample; and
       •  Narrative  description of the sample during sample collection (color, plant type,
'          etc.).                                     ^

3.6    SAMPLE CUSTODY

       Sample custody will consist of the following procedures:
       •  Chain of custody (COC);                   •
       •  Sample labeling;
       •  Sample receipt and documentation; and
       •  Sample storage and security.

3.6.1  Chain  of Custody

       The COC is a documentation mechanism for tracking a sample from the time of its
collection through its delivery to the analytical laboratory (Figure 3-2).  The chain begins
with the sampling person who will initiate a COC form for each sample. As the samples
are passed from individual to individual, the transfers will be noted on these forms.  This
process will continue until the samples are delivered to the laboratory, where the receipt of
each sample listed on the COC form will  be verified  and the form will be signed as
received and entered  into .the project file,

 ,"-,.•  The COC form will document the material sampled,  location sampled, and the
number and type of containers collected and shipped to the laboratory.  The form must be
completed  in  accordance with  the  designations stated in  this  QAPjP  to  minimize
                                       3-9

-------
cs

en
    O
LU

O


LU  cc

08
CO  ^

CfJ  >•
55"  Q
s  s£

ff  5°
    2  |
    LU  g



    O
    CO
    cc

£
=
tn



Q
S
3
J
J

j
ft
u



PROJECT NAME/LOCATION:
0
z
m
o
S


gineering Science, Inc.
aoratory
ifiltu Hr M P
Parsons En
Atlanta Lai
9RflR P.har





.










I
1
> 0
r n £3
; o "?
: . m
> CO CM
> S £2
3 <0 **
) ~ O
1 < 
• Js
t •
Received for Laborato
1
1
3
C
03
•o
f • "
T)
cc



•n
CC

•
S3
1
o


I
I
J3
t. .
o
o
1
u
£
e
Q
3
13
e
07
en
CD
•n
f
cc


-------
ambiguity or confusion.   To  ensure quality  control for sample documentation, each
laboratory will be required to maintain copies of all COC forms that are initiated.

3.6.2  Sample Labeling
       Information  on  the  sample  label should be identical  to the  corresponding
information entered on COG forms. This information should be  verified before samples
are released for transport. The following information, at a minimum, will be required on
each sample label:
                                           Date Collected
Client
Project Number
Location
Analysis Required
                                           Time Collected
                                           Collected by
                                           Preservative(s)
             Parsons ES Sample Number     Sample Type (i.e., grab)
 3.6.3  Field Data Sheet
                                 '--.-.   ''   •  /     • '    /
       The appropriate field data sheet (Table 3.2, 3.3, and 3.4) will be completed by the
 sample collector for each day of sample  collection.  The field data sheet will document
 study location,  sample type (i.e., grab  versus composite), sample code, preservation
 technique, date and time sampled, and weather conditions during sampling.

 3.6.4  Sample Receipt and Documentation
        After samples have been Collected, labeled, and, the appropriate information on the
 COC forms recorded, the forms and field data sheets will be transported with the samples
 to the laboratory.  Upon receipt of the  samples, the laboratory's sample custodian will
                                        '                          "*•
 inspect   each  sample  for  integrity,  and  check  the  samples  against  the  COC
                                        3-11

-------
                    Table 3.2   .   Field Data Sheet for the Tracer Study
                            LITHIUM CHLORIDE TRACER STUDY
                            Tracer Dosage and Sample.Collection
DATA SHEET NUMBER:
                                PAGE
OF
Section of process being investigated:
Dosage of Lithium Chloride Tracer
Date and time of dosage:
                Dosing performed by:
Location of lithium chloride injection point:
Dosage of lithium chloride: '
a)   quantity of lithium chloride used:
b)   volume of water used to make solution:
Weather conditions at time of dosing:
Other comments (e.g. problems, notable details, etc.):
Sampling of Wastewater to Detect Tracer
Date and time of sampling:1
                Sampling performed by:
Location of sample point:
Sampler ID Number (if available):
Sample Type (e.g. composite, grab, etc.):
Sample ID Number(s):
Sample Preservation Method Used (See Table 3.1 in QAPjP):
Weather conditions at time of sampling:
Description of Sample and Other comments (e.g. problems, notable details, etc.):
                                             3-12

-------
                   Table 3.3      Field Data Sheet for Water Quality Study
                                   WATER QUALITY STUDY
                             Sample Collection and Field Analysis
DATA SHEET NUMBER:
                                                                 PAGE
                                                                              OF
Wastewater Sampling
Date and time of sampling:
                Sampling performed by:
Location of sample point:
Sampler ID Number (if available):
Sample Type {e.g. composite, discrete, grab, etc.
Sample ID Number(s):
Sample Preservation Method Used (See Table 3.1 in QAPjP):
Weather conditions at time of sampling:
Description of Samples and Other commenits (e.g. problems, notable details, etc.):
Wastewater Grab Sampling and Field Analysis
Date and time of sampling:
                Sampling performed by:
Location of sample point:
Sample Type (e.g. composite, discrete, grab, etc.):
Sample ID Number(s): '
Sample Preservation Method Used (See Table 3.1 in QAPjP}:
Weather conditions at time of sampling:
pH meter calibrated?
                DO meter calibrated?
Field pH:
Field DO (%):
                                                                Sample Temp (°C):
Sample sent to laboratory-for fecal coliform analysis?
Description of Sample and Other comments (e.g. problems, notable details, etc.):
                                              3-13

-------
                   Table 3.4      Field Data Sheet for the Residuals Study
                                      RESIDUALS STUDY
                             Sample Collection and Field Analysis
DATA SHEET NUMBER:
                                                                 PAGE
                                              OF
Sludge Sampling and Field Analysis (NB. sample needed for fecal coliform analysis}
Date and time of sampling:
                Sampling performed by:
.ocation of sample point:
Sample Type (e.g. composite, discrete, grab, etc.):
Sample ID Number(s): •
Sample Preservation Method, Used (See Table 3.1 in QAPjPJ:
Weather conditions at time of sampling:
pH meter calibrated?
                DO meter calibrated?
Reid pH:
Reid DO {%):
Sample Temp (°C):
Sample sent to laboratory for fecal coliform analysis?
Description of Samples and Other comments (e.g. problems, notable details, etc.):
3lant Sampling (NB. sample needed for fecal coliform analysis)
Date and time of sampling:
                Sampling performed by:
.ocation of sample point:
Sample Type (e.g. composite, discrete, grab, etc.):
Sample ID Number(s):
Sample Preservation Method Used (See Table 3.1 in QAPjP):
Weather conditions at time of sampling:
Sample sent to laboratory for fecal coliform analysis?
Description of Sample (including plant type) and Other comments (e.g. problems, notable details, etc.
                                               3-14

-------
 form. When the samples received and the COC forms are in agreement, the custodian will
 sign the COC form> enter the sample information intp the laboratory log, and assign a
 laboratory accession number to each sample.  Any discrepancies between, the COC form
 and a sample label will be documented and the sampling organization will be notified. If
 the1 discrepancies  cannot be corrected, then the  sample will be discarded.  Corrective
 actions, as described In Section 4, will be initiated to ensure that the problem does not
 recur.

 3.6.5   Sample Storage and Security              ,

        During storage, samples will be maintained in a refrigerator at 4°C ± 2°C, unless
 otherwise specified.   Maximum holding time allowed for each  analysis is indicated in
 Table 3.1.  If analyses are not initiated within the maximum allowable holding  time, the
 samples will be discarded  and new  samples will be collected.  Corrective actions,  as
 described in Section 4, will be initiated to, ensure that the problem does not recur.
 Samples will be retained for 30 days  after analyses have been  completed so  that any
 unforeseen analytical problems may be addressed. At the end of 30 days, the samples will
 be discarded.                  ,                         •  \  '  •'        •

 3.7    ANALYTICAL PROCEDURE

       The standard.methods for conventional pollutant  analyses were chosen because
 they are the type most commonly specified in National Pollutant Discharge Elimination
 System (NPDES) permits  for municipal  wastewater  treatment/plants.   Analytical
procedures and references to be used in this study are presented in Table 2.1.  This table
 also'presents the minimum analytical detection limits.  All standard procedures are taken
 from EPA support documents or EPA approved manuals.

3.8    CALIBRATION

 , .     Calibration standards will be performed as required by EPA (EPA,  1983) for the
conventional pollutant analyses listed in  Table 2.1.  Calibration procedures for the critical
                                       3-15

-------

-------
                                 SECTION 4
                           APPROACH TO QA/QC
4.1    CALCULATION OF RESULTS

4.1.1   Data Utilization

       Evaluation of OA's AEES will be based on data collected during the monitoring
phase of the project.  Effluent purity as well as technology effectiveness will be based on
the degree, to which  wastewater constituents; are removed from the waste stream as it
passes through the individual treatment trains of the Living System.  Pollutant removal
effectiveness will be .calculated  using  percent.removal -of selected  pollutants, from
individual components of the system as well as .the final  product delivered from the
system. Percent removal of pollutants from individual components of the system will be
calculated using the following equation:
                    Percent Removal  = (Pb-P»)/Pb * 1.00

       Where:       Pb = Pollutant initial concentration
           •    •   -  Pa = Pollutant concentration after treatment train ,  ' •

       The percent  removal of pollutants in the  final  product will  be based on the
 following equation:.                                                        •

       ,             Percent Removal  =(Pi-Pe)/Pi* 100
 ;              •            "          "       , »  •                           .
       Where:      P; = Pollutant concentration in influent
                    Pe = pollutant concentration in effluent

        Those pollutants being monitored for. overall system removal as well as component
 reduction from the waste stream include COD, BOD, TSS, VSS, TKN,'NEfc, NO3,.and
 TP.     '  •        ' •       '.'••'     ''•-'.-    ' '  -     -'       ''  -••'•'••'
                                       4-1

-------
       The evaluation of the OA's AEES will  incorporate operation and maintenance
costs performed during  the study.  Collected data will include material  or equipment
replacement costs, maintenance, and any problems encountered at the project site.  Figure
4-1 is an example of the log sheet that will be used to collect O&M information.  •

4.1.2 Data Validation

       The laboratory directors selected for assuring quality of samples collected at the
study site will be responsible for reviewing and validating all data generated. Data will be
validated by  spot  checking field notebooks,  hand-written notes as well as computer
generated data and calculations.  All data conforming to QC limits will be acceptable for
use in this project.  Data found to be acceptable will  be compiled and reported  to the
QAC's and PM along  with accompanying QC verification datal   Data entered into
spreadsheets will be periodically checked against raw data.

       Data  that does not  conform to  allowable, QC limits will be reanalyzed when
possible.  Reanalysis of samples may not be possible in some situations, and in such
circumstances, the unacceptable data,either will  not be used or, if used, will be noted in
the Project Final Report with an explanation of why those analyses were not repeated.
                                                                     /

       The integrity of data produced will be  verified by QACs and the QAM.  The LD
will report data which are outside the allowable QC  limits  to the QAC, who  will be
responsible to  ensure that corrective actions  are  taken.   QA  forms  and  reporting
requirements are described in Subsection 4.6. Data found to be unacceptable for precision
purposes will be recorded on Figure 4-2.

4.2  INTERNAL QUALITY CONTROL CHECKS

       The internal quality control checks for all critical measurements are presented in
this section.   Samples will be collected in sufficient  volume to allow for appropriate
internal quality control analysis.
                                        4-2

-------
g

-------
              FIGURE 4.2 QA REPORT FORM:  LD LAB FORM 1 (pg 1 of 2)
REPORT PERIOD
                                 SAMPLE CUSTODY
Chain of custody forms attached:
QC sample preservation techniques maintained:
                                                 Yes( )No(
                                                 Yes( )No(
                                      RESULTS
    Test
  Initiation
    Date
  Sample
Description
Accession
 Number
 Critical
Measure-
  ment
Precision
  RPD
Accuracy
% recovery
System, conditions monitored during tests:
Percent Completeness:
It is estimated that
         of
                                Yes()No.()

   submitted samples were analyzed during this report period.
     samples will be analyzed during the report period ending
                                  DOCUMENTATION
 Analytical data and QC data entered onto computer:
 Laboratory notebooks and records maintained:
                                                 Yes( )No( )
                                                 Yes ( )No ( )
                                   QA/QC ANALYSES
                      REPORT PERIOD:
                                          4-4

-------
             FIGURE 4.2, QA REPORT FORM: LD LAB FORM 1 (pg 2 of 2)
                                          Not
                                       Applicable
Calibration Standard
Internal Standards •
Split Samples
Spiked Samples
Replicate Analyses
Other
 Analyses
Performed

Yes   No
()
•C)
( )
( )
( )
( )
( )
0
( )
( )
( )
()
            Within QC
              Limits
                                                                            Yes   No
COMMENTSi
                               CORRECTIVE ACTION
REPORTPERIOD:
Problem conditions) identified during report
period which required corrective action:
QAC notified of problem condition:
Cause of problem condition identified:
  Yes( )
  Yes( )
 - Yes( )
                   No()
                   No ( )
                   No( )
 PROBLEM CONDITIONS REQUIRING CORRECTIVE ACTION
 ANTICIPATED OA EFFORTS FOR THE NEXT REPORT PERIOD
                                         Approved By:
                                                             Date
                                          Laboratory Director
                                         4-5

-------
4.2.1   Calibration Standards

       Calibration standards will be used daily for TKN, NELt, NO3,  and TP analysis.
Internal quality control checks will be employed to ensure that the analytical equipment is
functioning  properly and  the method is  being performed correctly  by the  analyst.
Calibration  standards will be utilized to  establish  standard  curves which  will allow
calculation of sample concentrations based upon instrument response.

4.2.2 Spiked Sample Analysis

       Spiking samples with  a known standard will be used to monitor data accuracy.
Ten percent of the  samples collected for analysis of TKN, NH,, NO3, and  TP will  be
spiked. For proper spike determination, the standard addition of the spiking compound
will be at a level approximately mid range in,the calibration range.  Allowable spiked
sample recovery ranges for each analysis are presented in Table 2.1.

4,2.3 System Blanks

       System blanks will be analyzed to ensure that system conditions are not biasing the
data. These will include filters, laboratory pure water, and reagents.

4.2.4 Duplicate Analysis

       Duplicate or matrix spike duplicate analysis will be performed on  all critical
measurements listed in Table 2.1.  At a minimum, ten percent of all samples collected  for
analysis will be subjected to duplicate analysis.                       .         t

4.2.5  Additional Internal Quality Control Checks

        In  addition to the  internal  quality control checks  listed above,  analysis  of
performance samples will be used in  this study to ensure and maintain quality control.
Performance samples are currently analyzed by the Parsons ES Laboratory two times  per
 year to maintain quality control and such samples are provided by the EPA.
                                         4-6

-------
4.3     SYSTEM AUDITS

       Technical system audits will be conducted by each QAG to qualitatively evaluate
the components of the field and laboratory procedures.  These audits will be performed
shortly  after initiation of the  study (one  to  two weeks) to allow  early detection 'of
problems and identify needed corrective actions as soon as possible. During such audits,
all components of each field and laboratory procedure will be evaluated and will include
the following:

        •   Sample collection, delivery, storage and chain of custody;   _
        •   Field and laboratory analysis techniques including equipment calibration;.
           technician performance and data calculation methods; and
        •   QC procedures including calculation of data quality indicators.

        Following receipt of the data generated during this period, the systems audit will
 continue with an evaluation of the following components:                      .

        •  Data reduction, validation and reporting procedures; and
        •  Quality control ,reports.         .

        Field and laboratory checklists, as shown in Figure 4-3 and 4-4, will be used during
 the;system audit. Results of the findings of the systems audits will be forwarded to the
 QAM  who  will summarize the information in a letter  report to the PM.   If necessary,
 corrective action will be initiated using procedures described in Subsection 4.5.


 4.4    CALCULATION OF DATA QUALITY INDICATORS

        Data  quality  indicators . from  this  study  will  include precision,  accuracy,
 completeness and method detection limit. These indicators will be used to determine if the
 QA objectives for this study are being met.
                                          4-7  •

-------
££
j
i*"
Si^
1

1
;V;;
"/""•
•>
DC

L,
D
O

"*
- -1







-
;:s
"S


0
u
D
O
O
^

CO
u
**"
111
J
11
cc
11
i.
LU
CC





rntiPSTioNS
1 —
c

TJ
03
re
O)
o
2
a.
o
5
03
z
CN














a?
a


•a
03
CO '
il
;S
Automatic samplers routinely cleaned, inspected, and cal
and documented in a notebook.
CO














oT
O







CD
in
.0
Q.
C
re
03
u
•o
03
Q.
"5
•c
re
•o
03
03
O
Q.
,CD
"5.
re
CO
*














Q?
O







Collection container/sampler is chilled (4° i 2°C) during
rnllprtinn handlina. and transDort to lab.
LO














oT
O







Sampler is set to obtain a 24-h composite sample.
CO



-










5T
0



^
O
Q
^ -
Grab samples are collected for field measurements of pH
and tfimnerature. and for fecal coliform. ,
^














-



T3
03
03 U
-g » 03
— 0 "n
Sample containers for fecal coliform are kept closed until
moment the sample is collected, the stopper or cap is pn
from contamination, and replaced immediately after sam|
rnllp.rtion.
00













n
CJT
o





.
O3
Required sample volumes are collected for each paramet
«













fi
a?
O







Sample label is complete and legible and corresponds to
information on COC.
o








,




n
ST
a







15
'a
•o
re
Q)
03
a.
o
u
.52
E
o
H-
O
o
CJ
£













n
"tx"
O







tf
o
a.
CO
I
h.
3
CO
•o
03
a.
re
03
, re
CO
V-
03
"re
4-*
0
u
03
a.
re
CO
2
CN

>












cT
O







j
"E
•o
<
i
1
~i
E
c
u
_(
^
i
i
, i
i
i
r
T—

-;
\
i
'}
-

<>
f"~



^
;-"i
V

• V
/





CO
+•
c
i
(
I
C
{
"^
1
1
J
1
O
i
cc
1












<
.111


03
.CO

T3
C
SOPs for instrument and automatic sampler calibration a
are available.


 LU
 O

 UJ


 CO

 C3  c
 ^ -2
 CC  ro
 III  3

 II
 a.  Q.
                                                                  4-8

-------
  r
   o
  u
o
LU

O
UJ
u.
LU
O

<
cc

w
en
 CO

 4
 LU
 tr
   LU
   O

   LU

   O


   O c
   Z .2

   E IS
   LU' 5
   LU -"
   Z

   S

   gLU
    0. O.
                                                                                                       in
                                                                                                       gj
                                                                                                       in
                                                                                                       CM
s.
•. s
'-\'
C/3
CC
U.
•z.
o
o
•J\
V
ffi
f
fs
^
>*>
v" S1
ff
LU
5
o
o
z

(/)
111
*"
LU
o
LU
cc
LU
LL
LU
CC.












<
UJ


I
"5
CO
2
.S
.»*-
CO
CD
"5.
E
CO
U)
.c .•'
"D «
.11
.CD IT
...









Q.
cTT'
O -.



w meter calibration.










<
D_
LU



1
Q. •
O
g
*-•
CD
'w qj
3 3
CD It
fj
-: '









<
Q.
LU
^

2
jroughly between samples and af
r distilled water.










• <
LU


CO
|'
3
0
to
"3
Q.
CO
CB
%CZ
' as
o Q"
•2 CD
« R
jp 0
"5 ._
IE'
££ (D
CD i_
0. 0 ,
I!
:
V
''
-a

r QUESTIONS
Q
<
-TO m
fc c
Field technician has been
procedures prior to field a
CM

O
Verify documentation of f
CO

— ID
> JZ
pH meter is calibrated dail
standards which bracket t
•*

J 5
pH electrodes are rinsed t
calibration with deionized
in

w
o
Calibration is checked per
recorded in a logbook.
CO

s'
TJ,
£
CO
co
_O
3
O
to
u.
CD
• 3
Q.
^.'

i.^
o
Stock buffer standards an
more than one year.
00

2r
DO meter is calibrated dai
05
• ' •
w
. w
DO calibration checks are
o

$1
DO membrane is checked
^

-o
DO membrane is rinsed ai
CM

CO
DO probe is immersed in
durina calibration.
CO
	
o
Thermometer is checked
2
— _
=" °
Thermometer is periodica
traceable calibrated therrr
LO

" ~
A duplicate is conducted
field parameter (DO, pH,
to
	 ; —
  O'
  CD
  Q.
  to



  D>
                                                                                              C O
                                                                                              jo .ti

                                                                                              Q- 5
p  o
   CO

It
15
                                                                                              to
                                                                                              as
                                                                                                en
                                                  4-9

-------
  CO
§
O
UJ

5
h
Q
cc
I
cc
g
s
CO
CO
 UJ
 cc
 UJ
 o

 UJ

 o
 (O
 DC
 UJ
 Z MJ
 UJ uJ
 CO <

 II
 II
• .,:

i/i:
'•jii H-
if 5
.:••;' O
,;;;i,: J
CC Z
u_
•z. co
0 "f
U >
UJ
• uj
UJ
It
,„ Uj

fit
V
I
L
c
I-
' C




-




-

"?•


.J.
UJ


Sample Receipt and Handling
Sample temperature is recorded upon receipt at the lab and
' comnia ic ohprkerl fnr adeauate observation.
3 .
C <












„.
UJ


Personnel releasing and receiving custody of sample sign the
*• mr fnrm














<
UJ


03
CT
1 «
w o
.1 ^
o •£
•o c
. c
V QJ
o ^
^ '>
0 5
5 w
"e '•=
3 C
51
« o:
11
II
.2 '^
i 03 .-
ill
) co S
CO














.((
LLJ


Sample custodian notes condition of custody seal, physical
4 condition of sample, and number of samples received.














<
UJ


5 Sample procedures and responsibilities are documented.


•\'
,-5
''
n
;
;

f

,
-

£ '
D-
111 S'
,

Sample is refrigerated until utilized for testing (wastewater
samples).






'
f






H\
^'
fff

Facilities and General Equipment
Laboratory has separate designated areas for sample
1 submission, sample storage, extractions, organic analysis, wei
ohnmictrv anH wastfl riisnosal.
.
m
















Source of laboratory pure water available, checked daily for
^ ASTM Type II quality, and corrective action taken as necessar





,











-o
CO
T3
03
L3
03
U
.52
0
t
•o
CO
CO
03
U
*-* •
Q.
03 .
13
03
O
Q.
CO
TJ
O
O
«- "5
.-S'i
JS c
•5 t
UJ S
CO













'




Temperature of cold storage units recorded daily in logbooks,
r^nokla rtf maintaininn 4.° 4- 2 C. •


















Drying oven temperature recorded daily in logbooks, capable c
,v,n;r.toimr>n im-inR°r.



!













03
Muffle furnace temperature recorded daily in logbooks, capabi
c
„* mointalninn RRO 4- /- ROT.


,?,
'"!
•'-
>,
:'*
•;*
Mill
^
V
A^

/;
•
0
-
03
BOD incubator temperature recorded daily in logbooks, capab
of maintainina 20 +/- 1°C.
nnnimpntatinn/Oualitv Assurance/Quality Control


-












-------


•o
w
o
3
o
o
6
1
LL
I
o
c
<
ff"
u.
c

<
oc
f*
i
<
u
c.
2
<
S

c7
(/
<
J
C
^
^
u
c
C
u
u
1
^X
C
4
i
!
i
1
i
.

- •


O
















j
>
w

5
3
C
:
3
;
j
^
3
I
Ll
J
y
J
0
2.
= •
c
JJ .
JJ
5' i
ii
Si
o
/>
3C '
<
0.
?:
tt
,%
;•
%sj
^j
• VJ *

^ UJ
?? o
05 o

u.
Z CO
8>
-•
LLJ
...'^ O
^ S rf rf
* CC Q- O.
•• LU LU LU
,"' LL.
>-' ty
^^ QC
^ w
5.
v -f :
-. £ fi .2 <5 = <=
j in 'tn to to -c t:
. 0. Q- 0. 0_ .> .£
> C> O O O •£ «
3 CO CO CO CO J= £
} «* in CD r>- oo









t














^
03
O
03
UJ
C
igbooks are legible and pages numbered co
: .2
i -o
1 0
: m


.





















03

j£
c •
'S3
s maintained in accordance with GLP (e.g.,
s. riates. initials, etc.)
o r
a'S
o



















<
Q-
LU





to
.O
V
O ,
charts are maintained and current for each i
Rr •
*-
' *= n
) r- CT
111

























03 ;
<0
O
'•5
conditions are reported to QA Coordinator
ir verbal' reoorts)
; E c
: OB 5
i.3 t
i S '1
J.Q.S
CM













*






V




o
a
03
1
rds sHow corrective action implemented to
• 8 a
> v ~
!oJ
: 0 t
CO
















•










M
CO
£
TJ
to
to
%
•o
i
i
"55- >
c
o
2
. 03
a.
,0

. "5 '
! c
; 03
, Q.
' °?
























S
c
erforma
inely produces acceptable results on EPA p
in sarrmles •
3 '•£
_! 3



•.'•li
-.
•• :
x ;


T
3
sf.
~"'"'fs

*

'il
%•
'"'f
V
\i
^
^ ;.
rt-*




.52

-------
>- CD
•° T3
•O Q
Q
cc
§
LU
o

I
en
(O
a
••a-
ui

S
£2
u.
LU
O

LU
O
CO

i
 CC
 LU
 LU  CC
 1
 LU
 to <
 •z.
 o *•*
 S M

 II




CO
r
o
u.
H
o
u
y?







|;=


;'v.


n
z
LU
S
D
U
0
Z

CO
JJ
^
JJ
2
JJ
3C
JJ
J.
r





IT QUESTIONS
c
<











0.
oT

q

k.
•*-
CO
CD
Q.
re
CO
"o
CD ^
CD "C
A duplicate or spike is conducted on ten p
each parameter, or a minimum of one per
CO

-
"•
-.«•












•*rt,





ata Reduction, Validation, and Reporting
Q
u
















£
13
erforme
Q.
CD
to
CO
c
o
Data reduction is computerized or calculat
oermanentlv bound notebooks
'-

















CO
re
•s
CO
co
03
1
0>
u»
u_
O
T>
Individual analysts verify completeness an
CM

.










Q.
ST

O

.2
"C
2
'&
8
•o
CD
j=
_co
3
2
+•*
co
CD
CD
"I
CD
O
.2
"5.
ffe
£ <
-D 0
* CD
•> c
CD —
«- JE
.CO t
co i;
O co
en


















**"•
0
CD
CO
CO
^
CO
5
o
Q.
Q.
Laboratory project manager reviews and a
data to be complete, legible, and accurate
•«*

•










Q.
"o?

O



•o
i
^
CO
T3
to
CD
15.
0
o
£
CD
CO
•8 co
CJ LU
< CO
° §
"O CO
11
in




f












^0
to O
O co"
s. —
CO CO
CO T3
CD »-
kl CO
o "°
^^
Sample report includes analytical method,
precision, and completeness), blank and s
form, and copies of all raw data
CO

                                                     4-12

-------
4.4.1  Precision

       Duplicate  analysis will be performed to assess method precision.  A sufficient
volume of sample will be collected to allow for duplicate analyses.  At a minimum, ten
percent of the samples collected will be subjected to duplicate analysis.  Precision will be
determined for all parameters listed in Table 2.1.  Precision will be the relative percent
difference (RPD)  between'duplicate analysis. RPD will be calculated using the following
equation:

              RPD=  fRepl-Reo2>>   x 100
                     (Rep l+Rep2)/2               ,

       Where: Rep 1, Rep 2= Observed values for duplicate analysis.

4.4.2 Accuracy

        Spiked sample analysis will be performed to assess method accuracy.  A sufficient
volume of sample will be collected to allow for spiked sample analysis. Ten percent of the
samples collected, for NEU, NO3, TKN, and TP will be assessed for method accuracy. For
proper spike determination, the standard addition will be at a level approximately mid-
range in the calibration range.  Laboratory control/samples will be used to determine
accuracy for BOD and COD analyses.
      . i    '   :    •      -      '         '            •        •           ••"...•
                                :  :          \        .   ' .             -
        Accuracy will be determined by calculating the .percent recovery range (PRR) of
the sample spike  for NO3, NHL,, TKN, and TP analysis. PRR will be calculated using the
following equation:
              PRR = Cs-Cu  x  100 %
                        Ca
        Where
.Cs = Measured concentration in spiked sample.
Cu = Measured concentration in unspiked sample.
Ca = Actual concentration of spike added.
                                        4-13

-------
4.4.3 Completeness
                                                                 \
       Completeness objectives for this project are listed in Table 2.1. It will be assessed
as the percentage of all analyses performed whose results are within the QA objectives for
precision and' accuracy. Completeness will be calculated using the following equation:

              %C = Jrfv x  100%
                      Mt

       Where :       %  C = Percent completeness.
                     Mv = Number  of valid measurements.       ,           ;
                     Mt   =  Total number of measurements.           .'.-'-

4.4,4 Method Detection Limit

       For the critical measurements listed in Table 2.4, method detection limits will be
based on values that are established in the referenced standard procedure for each analysis.
Referenced MDL's may not be attainable in the presence of matrix interferences.

4.5    CORRECTIVE ACTION

       Each corrective action will involve nine steps as specified in the EPA Preparation
Aid  for Category II  Quality Assurance  Project Plans (EPA,  1989).   These steps are
described as follows:

1.     Initial Recognition of a Problem Condition.
                                      **           i                         •'
       Corrective action will be initiated when one or more of the following  problem
       situations or conditions occur:

       •      Procedures for sample collection,, handling and storage do not adhere to
              quality control standards described in Section 3.
       •      Predetermined limits for  data quality indicators are exceeded.
       •      Equipment or instrumentation is found to be faulty.       .            ,
       •      Procedures or data are not suitable,for their intended use.
       •      The schedule for either the analytical data reporting and/or submittal of QA
              reports/forms is not being met.
                                        4-14

-------
       •     Data reduction,  validation and reporting procedures,  as described in
    -         Subsection 4.1, are not being followed.
       •     Performance and system audits indicate QC deficiencies. .

2.     Identification of a Problem Condition.
       Upon recognition of a problem condition, the person making the observation will
report the problem to the laboratory's QAC. The QAC will then judge whether it is severe
enough to warrant  immediate notification  of the QAM.   Problems not  warranting
immediate notification of the QAM will be reported in the monthly QA report (Subsection
4.6) and corrected under the direction of the QAC. If such problems are not successfully
rectified, they will be referred to the QAM for further corrective action.

3. -     Assignment of Responsibility for Investigating the Problem.
        The QAM will notify the PM of all problem conditions reported: by the QACs.
These conditions will be reviewed by the QAM and the PM to determine the magnitude of
the problem, possible corrective action and who will be responsible for investigating the
situation. In general, the QAM will direct the QAC of the affected laboratory to conduct
the investigation. However, in critical  situations, the QAM will work directly with the
QAC to evaluate and resolve the problem.
        , /        t. .         '         /     .-'.'.            .    •    .  ,   ,' '
4.     Investigation to Determine the Cause of the Problem.
        Investigation of a problem will  involve a review of the procedures that  may be
^ntributing to the unacceptable situation. Each procedure, including system conditions
 for critical measurements, will be reviewed with respect to deficiencies  in QC.  This may
 include a review of sampling procedures, instrument calibration, system conditions and/or
, and data handling and reporting.

  5.     -Determination of an Appropriate Corrective Action.,
        Following investigation of the problem, the QAC and/or QAM, in  consultation
  with the PM,  will determine appropriate action to correct the situation.  The corrective
  action will indicate steps to take to preclude repetition of the problem.
                                         4-15

-------
6.     Assignment of Responsibility for Implementing the Corrective Action.
       In most  cases,  the  QAM will assign the QAC  of the affected organization to
implement the corrective action. The QAC will work closely with the LD to -ensure that it
is properly  implemented.   Problem  resolution  may require the issuance, of standard
operating procedure (SOP)  memoranda to assist the process.   Where  unusual or
significant corrective actions must be implemented, the PM, with  assistance from the
QAM, will be responsible for implementation.

7.     Establishment of the Effectiveness of the Corrective Action.
       Effectiveness of the corrective action will be assessed by reviewing ensuing results
over an  appropriate period of time.   The  QAC. and/or QAM will be responsible for
evaluation of effectiveness.
8.
Verification that the Corrective Action Has Eliminated the Problem.
       Based on the review of the ensuing results, the QAC and/or QAM will prepare a
report describing the actions taken and their effectiveness.  This report will identify any
additional actions, if necessary, that will be required.  The report will be submitted to the
PM.                                                           ;  -

9.     Documentation of the Problem Condition, Corrective Action Taken, Effectiveness
of the Corrective Action and QA Activities to Prevent Further Problem Occurrence.
       Documentation of minor problem conditions and their resolution will use the
standard QA report forms described in Subsection 4.6. This documentation will include:

       •     Report (LD Form 1) from the LD to the QAC regarding  the occurrence of
             a problem condition.
       •     Report (QAC Form 1) from the QAC to the QAM describing the problem
             and corrective actions taken.
       •     Report (QAM Form 1) from the QAM to the Project Manager discussing
             the problem condition and its solution.
       •     Unusual problem  conditions will require  special documentation.  This
             documentation will consist of one or more of the following reports:
       •     Telephone memoranda from the QAC to the QAM regarding the problem.
                                      4-16

-------
      •      A special report from the QAC to the QAM regarding the nature of the
            . problem and steps that could be taken to correct the problem.
      •      A special report, if necessary, from the .QAM to the PM describing the
             problem and possible steps for its solution.
      •      Telephone memoranda or letters from the QAM assigning responsibility for
            , investigating the problem.
      •      A report from the QAC to the  QAM regarding the effectiveness of the
             corrective action and any needed additional steps.
      •      Copies of all documentation prepared as the result of a corrective action
             will be maintained by the QAM in the QA file.

4.6   QUALITY ASSURANCE REPORTS  TO MANAGEMENT

      The main  goal of the QA program is  to ensure precision  and accuracy of the
analytical data.  It will be achieved by ongoing monitoring  of the field operations and by
proper management and  monitoring of  laboratory analytical  procedures.   This QA
program has been designed so that QC problems can be identified and corrected quickly.
All data generated or collected during this study will be maintained in a manner which
provides for a permanent and traceable path for an external review or audit.
           i      _,.      ,     -    >,    .          _         ..'...-...   ,  . ,
4.6.1  OA Forms And Reporting

       The roles  of the QA staff in preparing and submitting QA reports are described in
Section 1.  To  ensure timely reporting, the following QA report forms will be utilized in
this study.   . •  ,      -                        -              ,    .             ••

LD Form 1: This form will be completed by the LD  for each-month of field work or
analytical testing  and will be submitted to the organization's QAC.  When completed, LD
Form 1 (Figure 4-2) will include:              ,

       •      A  surnmary of samples collected/received and ensuing analytical' results;
       •      Completed QC analytical results;-  ,   '               ,
       •   .   Problems requiring corrective action(s); and
    •.•-•',  A confirmation that previously noted corrective actions have been taken.
                                       4-17

-------
       It should be noted that LD Form 1 is intended to provide a summary of results.
The checklist format will be utilized to minimize the time and effort required by the LD to
report the QC results.

       A modified LD Field Form 1  is  presented in Figure 4-5 for use by  the field
laboratory director. This form relates to sample collection.

OAC Form 1:  This form (Figure 4-6) will be completed monthly by each QAC and will be
submitted to the QAM. The QAC monthly report will include:

       •      A summary of samples collected/received and their status;
       •      Field and/or laboratory sample analytical results;
       •      QA results;
       •      A description of quality control discrepancies; and
       •     'Copies of LD Form 1 which were completed during the reporting period.  ,

      "It should be noted that the QAC monthly report  will include both QC results  and
sample analysis results. Copies of original QC and analytical  data must be included with
the monthly QAC report.  QAC Form 1 is  intended  as a  checklist for reporting  the
necessary information.  The QAC may have to prepare special  reports  which identify
significant problems that require the immediate attention of the QAM or the PM.

O AM Form 1:  This form will be completed monthly by the QAM and will be submitted to
the PM.  When completed, QAM Form  1 (Figure 4-7) will include:

       •      A summary of the samples collected and/or analyzed;                  :
       •      QA results; and           ,
       •      QC discrepancies and actions taken.

4.6.2  Quality-Related Training

       It is anticipated that properly trained and qualified personnel will be assigned to
this project. As a result, quality-related training will not be required for this study.
                                        4-18

-------
             FIGURE 4-5 QA REPORT FORM: LD FIELD FORM 1 (pg 1 of 2)
REPORT PERIOD
SAMPLE COLLECTION
Sampling procedure followed correctly:
Equipment maintain*** in good condition:
Equipment cleaned properly:
Yes(
Yes(
Yes<
No(
No(
No(
REPORT PERIOD
SAMPLE CUSTODY
Chain of custody forms attached
QC sample preservation techniques
  maintained
Samples are correctly labeled
Information on sample labels
  correspond with COG forms
Yes(  )

Yes(  )
Yes(,)

Yes(  )
No(

No(
No(

No(
DOCUMENTATION
Field data sheets completed daily
Rainfall records maintained
Operation and maintenance costs
  recorded daily       '
 Yes()
 Yes( )

 Yes( )
 No ( )
 No ( )

 No( )
                                         4-19

-------
            FIGURE 4-5 QA REPORT FORM: LD FIELD FORM 1 (pg 2 of 2)
CORRECTIVE ACTION
REPORT PERIOD  	
Problem conditions) identified during
 report period which required
 corrective action:
QAC notified of problem condition:
Cause of problem condition identified:
Yes(
Yes(
Yes(
No( )
No()
No ( )
PROBLEM CONDITIONS REQUIRING CORRECTIVE ACTION
ANTICIPATED OA EFFORTS FOR THE NEXT REPORT PERIOD
                                        Approved By:
                                                            Date
                                        Laboratory Director
                                        4-20

-------
                FIGURE 4-6 QA REPORT FORM: QAC FORM 1 (pg 1 of 2)
REPORT PERIOD
The following information is included in this report:
Conventional pollutant
 analysis results:
Field measurement results:
Quality assurance results:
Copies of QA Form 1:
                                                        Not
                                                     Applicable
     Yes

     ( )
     ( )
     ( )
     ( )
No

 (  )
 (  )
 (  )
 (  )
                                      QA REPORT
 OA PROGRESS TO DATE
 Problem condition(s) identified during report
 period which required corrective action:
 Cause of problem conditon identified:
 Corrective action initiated:
 Corrective action resolved problem condition:
 QAPO notified of corrective action:
 PM notified of corrective action:
Yes(
Yes(
Yes(
Yes(
Yes(
Yes(
         No(
         No(
         No(
         No(
         No(
         No(  )
 PROBLEM CONDITIONS REQUIRING CORRECTIVE ACTION
                                           4-21

-------
              FIGURE 4-6  QA BEPORT FORM: QAC FORM 1 (pg 2 of 2)
^ANTICIPATED OA EFFORTS FOR THE NEXT REPORT PERIOD
                                      Approved By:
                                                         Date
                                      Quality Assurance Coordinator
                                     4-22

-------
               FIGURE 4-7 QA REPORT FORM: QAM FORM 1 (pg 1 of 2)
REPORT PERIOD
The following information is included in this report:
                                            •'  '  Not applicable  Yes    No
CONVENTIONAL POLLUTANT ANALSIS RESLULTS
FIELD MEASUREMENT RESULTS
QUALITY ASSURANCE RESLUTS
COPIES OF LD FORM 1
COPIES OF QA FORM 1
                                  QA\QC REPORT
OA PROGRESS TO DATE
.     Problem condition(s) identified during report
     period which required corrective action:
   ,  Cause of problem conditon identified:
     Corrective action initiated by QAC:
     Corrective action resolved problem condition:
     QAM notified of corrective action:
     PM notified of corrective action:
                                                                             Yes ( ) No (-. )
                                                                             Yes ( ) No ( )
                                                                             Yes( ) No( )
                                                                             Yes()No()
                                                                             Yes()No()
                                                                             Yes()No()
                                        4-23

-------
              FIGURE 4-7 QA REPORT FORM: QAM FORM 1 (pg 2 of 2)
PROBLEM CONDITIONS REQUIRING CORRECTIVE ACTION
ANTICIPATED OA EFFORTS FOR THE NEXT REPORT PERIOD
                                      Approved By:
                                                         Date
                                       Quality Assurance Coordinator
                                     4-24

-------
4.6.3   OA Results In The Project Final Report

       The Final Report for this project will include a separate section that addresses how
the QA program was implemented during the project.  This section will include:

       •      A description of QA activities;
       •      Results of QC analyses;
       •      A description of corrective actions that were taken; and
       •      ,Copies of relevant QA documentation (e.g., QAM monthly reports).
                                         4-25 .  ;

-------

-------
                                 SECTIONS
                               REFERENCES
Engineering-Science, Inc.  1992.  Project  Management Plan for the Evaluation  of
       Municipal Wastewater Technologies and Sludge Management Systems.

U.S. Environmental Protection Agency. 1983. Methods for the Chemical Analysis of
       Water and  Wastes, EPA-600/4-79-020, Environmental Monitoring and Support
       Laboratory, Cincinnati, Ohio.                                     '

U.S.; Environmental Protection Agency. 1989. Preparation Aid for HWERL's Category
       IV Quality Assurance Project Plans,  Office of Research and  Development,
       Hazardous  Waste and Engineering Laboratory, Cincinnati, Ohio.

U.S. Environmental Protection Agency, 1990.  NPDES Compliance Monitoring Inspector
       Training: Sampling, Office of Water Enforcement and Permits, Washington, DC.
                                      5-1

-------

-------
                                    Appendix B
                            Raw Data: Flow Monitoring
       This appendix  contains  abbreviated raw flow data for Train B of the process,
recorded by both the influent (Parsons ES) and effluent (OAD flowmeters during the process
evaluation pf the AEES Facility.  The actual flow data from the influent flowmeter is'in the
form of minute-by-minute flow totals and is considered too much data to include here.  For
simplicity and brevity, only daily flow totals are shown, these are provided in Table B.1

       The periods when the plant was shut down (Section 9.5.3) are indicated in the table
by  grey shading.   Influent daily  flow totals annotated with  "est". were not  recorded
electronically by the flowmeter but were interpolated from flow total data  recorded in the
field notebook.   This had to be done when  problems were encountered with the computer
which prevented it from recording the flow data.
                                           B-.1

-------
             Table B.1
       AEES Facility Flow Data
Influent and Effluent Flows for Train B
Date
2/28/95
3/1/95
3/2/95
3/3/95
' 3/4/95
3/5/95
3/6/95
3/7/95
3/8/95
3/9/95
3/10/95
3/11/95
3/12/95
3/13/95
3/14/95
3/15/95 -
3/16/95
3/t7/95 ' v'
3/18/95
3/19/95
3/20/95 '
3/21/95
3/22/95
3/23/95
3/24/95
3/25/95
3/26/95
3/27/95
3/28/95
3/29/95
3/30/95
3/31/95
4/1/95
4/2/95
4/3/95
4/4/95
4/5/95
4/6/95
4/7/95
4/8/95
4/9/95
Day
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday-
*' SafaBtfay
•. Sunday' ,
•. ' Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday -
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
, Sunday
Influent Flow
gallons
70,704 est
10,704 est
11,928 est
13,162 est
13,162 est
13,152 est
13,152 est
12,392
13,856
13.892
13,528
13,977
13,997
13,877
13,770
13,791
13,808
6,483
23S
301 "
5,221
13,900
13,605
13,970
13,740
13,741
.1 3,551
13.004
13,451
13,360
13.507
13.630
13,486
13,314
13,318
13.269
13,183
12,951
13,144
13,815
15,838 est
Effluent Flow
gallons
8,194
6,538
12,211
8.813
11.612
10,095
6,470
10,113
12,587
7,140
13,802
9,780
12,443
11,753
11,205
11,807
11,829
, 4,694
0
0
3*248
11,201
12,230
11,753
10,896
10,787
10.665
10.199
9,540
7,580
9,809
11.030
9,284
10,398
10,500
10,674
9,672
7,007
6,992 ,
9,348
4,389
                  B-2

-------
        Table B.1 (continued)
       AEES Facility Flow Data
Influent and Effluent Flows for Train B
Date
4/10/95
4/11/95^
4/12/95
4/13/95
4/14/95
4/15/95
\4/16/95
4/17/95
4/18/95
4/19/95
4/20/95
4/21/95 '
4/22/95
4/23/95
4/24/95
4/25/95
4/26/95
. 4/27/95
' 4/28/95
4/29/95
4/30/95 ,
5/1/95
5/2/95
5/3/95
5/4/95
5/5/95
5/6/95
5/7/95
5/8/95
5/9/95
5/10/95
5/11/95
5/12/95
5/13/95
5/14/95
5/15/95
5/16/95
5/17/95
5/18/95
5/19/95
5/20/95
Day
Monday '
' Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday ,
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday ,
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday1
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Influent
gallons
15,838 est
16,838 est
14,264 est
14,271 est
13,660 est
13,660 est
13,660 est
13,660 est
13,229 est
13,131 est
13,696 est
14,061 est
14,061 est
14,061 est
14,061 est
13,147 est
13,300 est
12,736 ;
; 12.826
10.380
11.804
12.025
13,436
13.183
14,043
13,600
13,534
13,477
13,303
12,999
14,329
14,318
14,240
14,879
15,104
13,890 ;
13.085
no data
no data
no data
no data
Effluent
gallons '
6,051
11,642
6,660
10.559
9.920
9,342
9,366
8,201
7.889
8,561
9,894
10,280
10,341
10,017
8.975
8,567
10,203
9,872
6,935
5,367
6,604
7,059
9,026
6,644
18.842
10,656
12.098
11.960
12,246
11,918
7.604
11.103
14,402
16,311
16,647
1 5,783
15,315
13,512
12,984
12,773
13,866
                 B-3

-------
        Table B.1 (continued)
       AEES Facility Flow Data
Influent and Effluent Flows for Train B
Date
5/21/95
5/22/95
5/23/95
-_ 5724/95 -
5/25/95 f"
5/28/95
," 5/27/95
; S/28/95 , '"
S/28/9S^s;
5730/95;;'
S/31/95
eyiyas' _,^
6/2/95
6/3/95
6/4/95
6/5/95
6/6/95
6/7/95
6/8/95
6/9/95
6/10/95
6/11/95
6/12/95
6/13/95
6/14/95
6/15/95
6/16/95
'e/tr/95
em/95
6/19/95
6/20/95
6/21/95
6/22/95
6/23/95
Day
Sunday
Monday
Tuesday
\ Wednesday
Thursday
*, Friday
.''.. Saturday •
Sunday
Monday
Tuesday %
- Wedljesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday •
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Influent
gallons
no data
no data
no data
no data
no data ' ,
no data
s no- data
no data
•• , no- data
no data
nftdata
no data
no data
no data
no data
no data
no data
no data
no data
13.240
13.840
14.340
12,340
12,710
13,180
14,050
10,600
1,040
7,400
13,090
13,320
13,910
13,870
13,880
Effluent
gallons
14,546
14,639
12,960
531 "
' 812:
' 0
*T" "
0
98
o >t
4,676
8.550
7,082
7.197
11.012
13,514
13.572
14.621
16.497
no data
no data
no data
no data
no data
no data
no data
no data
no data
no data
no data
no data
no data
no data
                 B-4

-------
                                     Appendix C
                      Raw Data: Water Quality and Residuals
        This  appendix contains  the  raw wastewater quality and  residuals  data recorded
 during the eleven-week process performance study.  As well as listing all of the data, the
 appendix also describes the data manipulation and statistical analyses performed  to identify
 statistical outliers and spurious data points.                     :

        All of the raw water quality data for the eleven-week performance evaluation, along
 with their summary statistics, are shown in Tables C.1 to C.6.

        The raw residuals  data  were not subjected  to the  statistical analyses  that were
 performed upon the  wastewater data.  This was owing to the  small  sample size  (3-5
 samples)  which, it was  considered, made  distribution  testing  and  lack-of-fit  .testing
 meaningless. Summary statistics, however, were generated  for the residuals data.  All of
 the raw sludge data, along with their summary statistics, are shown in Tables C.7 and C.8.
 The raw data for the plant samples are provided in Table 9.5 (Section 9:4).

 Data Manipulation

       As described in Section 9.2.1, .the first step of the data manipulation was to review
 the field notebook and laboratory reports to remove or modify data points that were known
 to be invalid for any reason. The data removed or modified were:

 1.     Samples W2-0308-0955' (Table C.2) and W3-0308-.1023 (Table C.3): all of the data
   .,   for these two samples  were disregarded as the samples were contaminated  by raw
       sludge following a process mishap (Section 9.5.3).

 2.     Sample W5-03Q1-1210 (Table C.4): the data for this  sample could not be  used
       since  the location for sample  point W5 was moved after Week 1  of the study (see
       Section 4).

 3.     Sample W6-0316-1045 (Table C.6): the TSS and VSS data for  this sample were
       uncharacteristically high.  These data were determined to'be caused by of pieces of
       algae  that had been scraped off the piping following the replacement of the sample
       tubing in effluent pipe.  Therefore, the solids  data for this sample were considered
       to be  unrepresentative  of the normal effluent  and they were discarded.  The other
       parameters for this sample appeared to be unaffected, so they were retained.

4.     Samples W2-0412-1150 & W2-0426-0935 (Table C.2), W3-0426-1000 (Table C.3),
       W5-0426-1040 (Table  C.4), and  W6-0330-1030 & W6-0413-1050  (Table C.6):
       analysis of these samples yielded VSS values that slightly exceeded the TSS values.
       This was determined totbe  the result of analytical variability when the two values
       were,  in fact, very close  (i.e., the total solids'comprised  mostly volatile solids).  In
       these  cases, the value for VSS was assumed to equal the TSS value. •
                                           C-1

-------
   H 5 •
   
to
}
o


•
1
1
•
(
t
i
c
«
o
Q

£
to
O
^

*
CO
o
^
i
o
CM

5
0
^-
5
g
O
>
3
S
)

o


i
i
;
1
1
t
S
C
r*
CO
ID

£
1

10
g
C9
i
OS
n

n
*£
CM
CM
*
to
2
o
8
S
in
CM
CJ
*r
^
>
i-
o


•

1
1
o
i
o
CM
to
£
«

S
S
03

i
c
w
8
n
CO

in
CO
D
2
01
q
4
o
3
to
>
ra
q
)
o


1
1
t
c
(
o
tn
i
e
8
to
C
1O

e
r*
c
to

g
*
cc
to
ph
to
V
M
5"

^
^
M
<£

CM
O
J
6
o
O
^


I
I
2
c
4
p
a
•
c
r
c
r*.
r^

CO
u
e

*
cc
CO
o

CD
09
CM
CM
5
C:
^t
>
CD
2
o


I
1
1
L
1
1
                                ta
                                
2.400.000
S
&
CM
t
I
M
3
to
2.400,000
24,000,000
>
>
o
o"
>
o
in*
i
o
o?
>
oS
£
|
:
•<
r*.
pt
r*
€
0
g
o
a
r»
p*
a
I**
.CM
C
a
s
pC
p*
p»
.pi
EN
CO
O
CM
CD
S
O
•4
0
?
i
a
CD
O>
-
1
L
I
C
p*
p
c
r
0
c>
^
-er
O)
c
cr

o
1
in
i
c
(
q
0
o
o
q
r
c
f
o
a
0
p*
q
r*
ii
1
0)
-
0
s
q
4
q
2
-
}
L
                                                        01 —

                                                        O) t
                                                        o o>
                                                        S e
                                                        o e
                                                        .2 (O
                                                     O)
                                                     c
                                                     g  _ .£ • _»


                                                     IgMii
                                                     S '™ .*S o o rv
                                                           I S S
                                                           a § s
                                                           Sue

                                                             g
                                                             •a
                                                           jo
                                                          1
                                                          e
                                                     I

                                                      s'-f 5
                                                           ** CD
                                                      I s' 's i
                                                          5 2- s
                                                        f i
                                                        1 I
                                                        II
                                                        § I
                                                        s I
                                                        I §
                                                           •o •= i
                                                           1 i -
                                                           s: g
                                                           o 2
                                                           •• c


                                                           I!
                                                           E |

                                                           I ^ = I E
                                                           o -*^
                                                        S 5
                                                        i i
                                                        o £
                                                        5 5
                                                        5 S
ll



II


ll
,1
                                                                 1*
                                                                 CO CO
                                                           2 °
                                                         S  £
                                                        3 2 -a Z
                                                        S 5 = '-
                                                        > > a o
                                                         w
                                                     11
                                                              o o • t> o
                                                              E E g E
                                                              ~ o o o
                                                                
                                                        
-------


• ' "" /

!
-.'.''•
I.
If
i:
*P
Q S i 3
«N >; i a 1 ]
0 5|J S
05 < £C 2 UJ
| 31J I
oe £ S fe
Ul °- CM S ' -
i- « > g
|||
B'2 '
> - i
UJ Q.
ti 1
CO
«
1
I
•5
t(
- •" • 1






W2-OS1 7-1005 § § •§ -8 g
. • s
W2-0510-09SO I g § i S
W2-OS03-1020 g « | g „
W2-O428-O935 § « S S "
f"s CO O O f**
« W2-0419-1005 £ g 8 2 0-
£ ™ *^ "^ *~ tO
?
5* - '
1 W2-0412-11SO S 8' 1 § 5
6 	 	
S *• SO O rs,
W2-O405-10O5 g « n g P
W2-0329-1010 | § S g Jj
- ' S
O «• o o *
W2-O315-1015 « 0 
W2-030S-0955 § J I '§' |
W2-0301-1130 | | § g ,o
S^O llxcor-M
1 1 * S 8 S. 5 S
: 5=»
"E c
•5 | -:••*»»
C •? O tO N N C*
• s **•,»-«««
* § S § °- "2
- - 2 i 1 § s i?
J=  P
U) C4 CM «-. «-
J «? 9 . e
1 I 5 1 '!' s
= g g o -o 'S-

S •>=<=•;<;<;
1 I I I 1 I
5 § § § 1 : ''
S 0 j a «
. 1 5 = s 2 » <
i- Ifi- 5lfi ,S 2 5
J B> '9 t £ g
• * 5 * 5 J3
§ . • " ,
.. _ a o co r*.
I i (ri oi « «.
•V CO O K>
cj q 01 f g
!cft w W ^ x
P* ^ CO O 2
"to to * * co , ,,
»- ^ o> . *7
01 » CM O »
CO CD CO 0 —
r* CD w *T ^
n n .n o co
= ' 2
CO •- *- CD CM
^ oi m ' 1 t -
o> in v o f^
» " S 2 S
IA CO O . .
ID * O 01
CM 2 " 2 £!
10 S 8 d CO
10 0) CM O *
SID Cft *t 1
c9 CM o rv
Mil!: 1.
• 	 ;; E
<
CO (•» CM O CO **
•^ ui » *: 9 "»
0 CO CJ O 01 <
5 S ». g 5
CO •- °> 'O CM
a 2 S§2
» p^ *: o £ •
w to ej *t *J J
m n N o 10 j
"I
1 <
W 03 *- (D 0 c
5 3 9 2 g ;|
«
i^ m co M to
O ^ « *T *? '
v <• n o flo
q w co to pv
S*- m n T~ *7 ;
'*• a o 00
o o o o o

5 s-5 ? 4
E 6 || |
1 . 1 •
n z | a «
S S 1 i 2
G2-0517-1020 ^
G2-O51O-1OO5 ^
G2-OS03-1030 ^
G2-0426-0950 %
„ G2-O419-101S ^ |
& 	 ||-
*" ' ^^
=| G2-O412-12OO ^ |
»_ • ^!
* — ' 	 	 ^ ~
1 1 C
G2-0405-1020 M J
G2-0329-1025 ^ c
G2-0315-1O3O ^ *
G2-0308-1010 ^ *
G2-O301-1135 ^ r
§*= •
i - 0 ^ r-
£ S* ^ 2
"» I
ij j|g
ft
1 ^ ^
1"
1 |:-
; ' s if ^
\ \*.
S M i-
^ -
^ *"
i ii
S i _
E "I
S S S
S. Z iS
5 «? 5
i^ " £
2 10 "!
r! ri S
5 » 2
N n t
g n 0
5 2 g
? •?- S
; » t
; ~ s
; « 5
'. 0 «8
: » 2
is 1-
: 1
Bl 9
^ £
a 9
•»" S
-«— ffc
oi w
w q

n 2
10 9
•»' 2
3. 5 - '
5: ? .

.— .—
1?
IRold 00
Simplo Temp.
                                                    1 —
                                                    A  -

                                                    IS-


                                                    f ? Jc
                                                    J w  e
                                                    «* Q ,O
                                                    S .2 S
                                                    -
                                                   -

                                             ,
                                             IS
                                              c 1  a

                                             111
                                             ^  o  o
                                              • • B  g-
                                             t  S'E
                                            '  • JS  8
                                             4  ? j
                                             lie
 o "S  f
S «  S
 s «  s
£ ^g ,0.-

£ « ^
•O T3  O

 ! Ii
 S E  S
 E £ f
   §co  c
   cct  a
 S S  a=
                                                    §  s  i  s
         •I  e  S
         *  §  -3
         f  s  I
         I  11
          i.  o  °

          If  I
          O  3  fc.
          O  O  O
         £  S  »

          I'll
                                                      —  >!.•£
                                                          Ja  t>
                                                          c  §
                                                      O     ^j

                                                      •o  |  c
                                                      §  5 S
                                                      •£
                                                      «
                                             >
                                             c


                                             I  I
      >
      
-------
m
d
          S
<
CO
Ul

g
o
OL

O
U







|
*
&
a
1







g
s
ititlitioil /








W3-0510-1020
W3-O5O3-1O45

W3-042B-1000

W3-O419-1O30
W3-O412-1215
W3-O4O5-1 03O

W3-O32S-1035
W3-O315-1O45
W3 -04303-1 023
W3-O3O1-1150
§5 =
1 •? °
5 i *
c • £
cj £ ra
•g g
11
55
I
I
1
1
|
C

1
"m
e
I
^

C
Q

r*.
in

e
B»
C
«r
?

0
K
c;
S
(0
•t
3
'T
2
o
^
a
q

Q
>
ID
*
f
«*•
CO
Cl
ca
>

1
i
^
c
n
o
01

u

.>
.>
*-

«
if
in
s
i
«i
a
"
q
_
^
ID
Ol
O
S
CO
s
01

1
o
o
u
i
1
.

CD
GO
O

IS.

•i
o
R

S
O
i
D
O
n
oi
o
g
q
o.
CD
tn
>
CO

1
1
.
c
p»
o
^

T-

e
tn


cr
ec
r«*
CD
i
3
ID
03

(D
q
a
0
0
Ol


?
(0
a
N
*~
S
ID
OJ
G

~8

S
00
*J
*

CD
^
|
!
^
M
i
CO
8
0
•*
q
D
q
4
O
a
>

•
n
i
CM

t
O
f*

to

u
e
CO
10
CO

o
O!
^r
to
ID
*
I
r»*
in
n
01
at
s
^
to
CO
s
CO
CD*
V
O
CD
V
>

>
.
C
C4
CD
C
C9
ID
Ol

ID
d

CD
C4
"5
e
n
ID
CO
*
3
ce
n
CJ
i
o
s
12
CD
"f
•*
8
CD
CO
CO
CO
«
o
CO
c*
>
_
\
| Ammo nit
r*.
c
10
r
<
CO
e

O
C

CM
S
O
03
C
O
1
$
tn
a
c
r»
d
0
I
g
O
1
CM
n
O*

d
1
CO
1
m
CO
d
01
2
i
i
•
'
CD
P
a
CO
d

c

Ol
CD
CO
a
rC
r»
tn
CJ
cc
N
O>
a
ts
4tt
1
s
»
0
o
I
s
CO
*
in
Ol

f
i
!
L
i
                                                                               .


                                                                              <
                                                                              CO
Wlter Quality Rnulta |



1
c
lUtistfcal /



G3-O517-1055
G3-O51O-1O30
G3-O503-105S
G3-0426-1010
G3-0419-104O
G3-O412-1230
G3-O40S-1O4O
G3-O329-10S5
G3-O315-111S
G3-O308-1035
G3-0301-12OO
g S 3
in
JJS
II
1
s
c
1
£
z
c
•
T!
3
S
1
tl
1
1
1
|
1
|
i
i
i
ii
i
i
i
i
jj;
1
|
1
1
i
1
1
i
i
1
1
i
!
!
O
tr
r*
i*.
u
r*
CO
u
r*
p-
u
tv
C4
r*K
r*
a
r*
CD
If
r-
s
rZ
N
CC
rC
»
rC
»
S
d
M
d
0
s
ft
>
-
1
i.
i
CO
c
r«
o>
c
r
u
c
u
c
e
tr
ir
tr
ui
r*
CD
q
n

o
0
o
0
o
0
q
r*
q
r*
q
r»
q
CO
o
a
CD
2
o
n
»
0
q
£
-
j
L
1
L
t
                                                                                                                         *  c  i
                                                                                                                                        S
                                                                                                                               S S
                                                                                                                         2  e  t f
                                                                                                                                     U9 (O


                                                                                                                                     P g
                                                                           C-4

-------
''







• • ?.--•••
«
•J!.'
$& ••
<. < t
H > N
^ Ul *O CO
* £si i
5 =11 s"
•§ g 2 f |
§- S » °
5s5
If
S £
JO
•? I • :
CO
CO
»
. • " i
*
' '- -j
1 1
''-"...




s, " 5 1 -
WS-0517*1110 § to 5 -S <
; * • g g -3
s
i WS-0510-10SO 258*5
W5-O503-1110 § ai 8 J .5


, WS-O419-110O J ^ J « 0
=5 W5-0412-1250 = S g- g S
3 *• ID o
• , W5-O4O5-105O 5 2 g S ^
- *~ n °* at
WS-O329-1105 S o> 5 ID 2
, W C5
- • . s
W5-0315-1120 | 5 £>• 2 '3
W5-O3O8-1O45 g 5 ? § ^
, I
: _ " X *«. ~ «» «,
W5-0301-1210' S J f . 3j 3
§5 =
S-o •» q 10 ,0 ~
I'ljg •" S S « S
82" , .,
"Eg
i •§ ~ ® '"v q CM 01
U O • •
i. .- i •: ! I 3 s
1
•= °- *• O O 10
£ 5 S 8 2 g
. J imi
! "3 5 '•* * *
x 1 S 5 "' 3
c oi ^ oo at o>
1 f 1 I I !
"'- a - 
, S  °J 1
CM T- T- (D
»-iiS3 |
• • <
S cu S 5 $ !?
>ili! |
i 1 s g s ;
2 -3 3 "5 2 ; ;
O r*  J
• ~*
to o> m »- •* *«
« o a! ^. o -S
,
O en a CM o
8o> oi -T 1^
CM . CM CM °°
=> 2 S 0, 0
-; •= ? ? o.
o a «: ^ ^ "
E E 1 I 1
I :
O
^S o .
c ^
a 5 i I i
^i.i ^- £
65-0517-1125 ^ "
G5-051O-11O5 ^ .J
G5-O503-1120 ^ J
l|
. "G5-0426-10SS ^ 5
„ G5-O419-1115 ^ ?
=1 GS-0412-1310 ^ [H
G5-O4O5-11OO ^ ™.
G5-0329-112S ^p g
GS-O315-1125 Sl| J
05:0308-1055 ^ ?
GS-O301-1220 ^ ^
^^ (D
g ^ 0 ^ CM
i I * l| 5
1 s | 1| §
s ° If
^W;
'•••'"* 'is
X §|| rC
1 1s
I |s
= ^ 2

I 1 T ,
1 2 f i
.1 S2:
£ £ E L
S -3 ,
2 §
r» q •
ri 2
• - ^"
5 g,
CM q
 «* "05
m § — o
	 _0 — 0 CO
0 * » g
2 t " ' | * =
. o cr — o .
i--i'?. § S 51
	 	 « — S w ~ ri
0 CM _ " •O .
.— v O • ^ • o ® 1^
1 S 1 °> i S £ "c
° . HlHf
^ "f.Jiin
2 o 5 5 •= S
Sra^JDff^'
' • J r o s s -g
»: * - -ol-'^a.c
- - . • i i § s i s
•^ ° = «,• o S
	 § S > 1 .f s
jj „ OT Q >* qj
n o. 5' S S > -g S
^ - l| liH
M M ;£
s§ iJllll
™ jo o £ o £
In M!
oj g • £ I c £ g--t
« 2 o -^ £• * -S §
*^ *" t^ *0 C ^
cog Jl£gS!°
*~ ^5 S o o To S
•S » ji .0 eg
1 1 11 £ I
S 9 ' i I I 1 i 1
, S 2 f t S 1
— s i g i g. g
22 S5£«|>-
•S«»oSc
-— J S 5 S co i
o o " tt > ™
1? JJ=J-oi.
§55555
« » CO Z CO CO
» w CO ,i^ CO OJ
£ o > 1— I- 1—
a. o o o o ID eo •
1 § § S E S S
)2 -S -S 0 0 0 0
io u;°7cocococo
_ a. a) fe •
S 1 o c £ . . • •
C-5

-------
  cr
    I

">   £

S   <
5   =>
12   £C
    111

    I
l
11
ui ^
o G:

II
   co
   UI
I?
S*i £2.
ii
G  8






^
s
r Quility R
i







i
Statlitloil /









W4-05 18-0950
W4-0511-1010

W4-O504-OS55
W4-O427-1000
W4-0420-1050
W4-O413-1O15


W4-0330-1000
W4-O31S-1O3O
W4-O309-104O
W4-0302-10SO
si 5
s £*
c • to
35*
if
55
1
f
5c
|
1
§
s
c

e

1
7>
£
i i
< i

*- f^
* '
^ e
w c
o in
ID T
«r a
i S
T w
$ «
B *
^ «
^ n
D «N
> «a
B cr
3 S
i> a
j oj
I 5
: o.
! 2
CN
; 2
^
jr
«.
«r
CN
CO
o



g
•
1

G9
•
t
t
O
«N
§


CM
0
O
«*
»
0


*r
^~
^
^
«
o
2
o
V
o
3

*
n
^



a
|
-
0,

C
«
a
0
c
r*
u
C|


i
0
o
^
(D
^
t
2
pj
q
d
tn
04
O
03

01
Q


E

«
CO

*r
CD
II
a
c


i
•*
to
n
oi
oJ
2
q
N
5f
4
o
in

0
o


£

2


t
to
(
(t
c
c
N
TO
g
IX
r^
O
O
01
-
OJ
CD
•*
es
TO
CD
Ol

>
^


E
.
?
i

c
01
c
o
p*
c
n
c

r
^
(

0
en
u
a
o
c
c
c
d
"~
Q
e
c
CM
8
f.

,_

_„
i
;
i
i
ri

e
o>
c
r^
•
L
C
S
r-C
^
CD
CO
a
rC
CM
c
CD
r*
CD
q
™
°.
o
o
0)

^

^
o


i
L
i
                                            CO

                                            CO
                                          g
Water Quality Results


•a
o
s.
•
Statistical /



G4-O518-10O5
G4-O511-102O
G4-0504-1005
•
G4-0427-1010
G4-O42O-T10O
G4-O413-1030
G4-O4O6-1025
G4-033O-101S
G4-O316-1035 ,
1
G4-O309-1050
~
G4-O3O2-1100
m
JJS
•E =
ij
si
i;.
i
c
€
s
•
1
=
-
•
I
v «
•
I
r
l!
I
i^
P
|;
h
h
1s
1*
h
1s
h
h
h
h
h
1=
1
i
S
0
.J
a
<<
IN.
c
a
c
01
0
4O>
"C
.01
»t
r%
^r
a
e>
Ol
CN
in
Ol
o
ei
Ol
^
Ol
CN
in
C9
-
B

2
2
c
I
o
O
1C
0
o
a
-o
o
o
o
o
a
0
I
c
CN
CN
O
CD
in
F>
o
)
CN
0
-
o
[
                                                                      —   o

                                                                      «   To
                                                                      d>   a
                                                                          ft _;
                                                                          oi T
                                                                          e 


                                                                          I | rf,
                                                                              CO
                                                                                      e


                                                                                    § I
                                                                                    CQ g
                                                                                    O W

                                                                                    2 S
1 _t
19 *-

IS

a §

ll
2 V

I" -2


1.1


If
Jd °
§ i

I S
 tr -—  o
 " S  S ?J
 s ?  ^ «:


:l!il
 ' g  8 .3
                                                                              I I
                                                                        3 i f
11
§  s
1  §
CO  "o
10  >
»I
                                                                       If
                                                                            II
                                                                       H
                                                                          S  g

                                                                          I  §

                                                                          g  I
                                                                          £  c
  « ?
  g £
  i I
- 1 2
I f s
~ « 1
  •o >

  M
  CD rr
  • g

  I'*

  I S
  I *
  2. -2
                                                                        I  I
                                                                        2  2
                                                                       1
                                                                       1 1

                                                                       to u
                                                                       s s
                                                                       g g
                                                                          s  s
                                                                          •o  -a


                                                                          To  To
                                                                          c  c

                                                                          £  2

                                                                          II
                                                                         •s — "°
                                                                         W (0 C
                                                                                      S 1
                                                                                      o o
                                                                                      •a 31
                                                                                      o o
                                                                                      Is

                                                                                      i s

                                                                                      2 1
                                                                                      o c.
                                                                                      •S s
                                                                             CO CO
                                                                             CO CO
                                                                            E  E  E  E
                                                                            o  o  o  o
                                                                            W  CO  CO  CO
                                                                     i
                                                                           »^ CN W
                                          C-6

-------
     2*
     H o

     il
"•   !S.'3I

   •S.I -i

 •3•-'ESi I
    -J Si"
 •g •  S S o £
 «  a 2 I 5
 I-. "T* tt   O
 1   f^ in ' s s
W6-O51B-1O35 o 
•S f 9 -: « o *
g| g ?3 2 J2 «
wo
; , ! 11 33 s
• 1 J3'JI a
• .
1 5 S "• "• °-
| . 'g § ». •• «
| « ". » « u>
I S S 2 ° ri
= ^ 2 0) 01 0)
'.-..- 1 till!
o  U> f^ (D
CO ID *- f^
t S S R ?
$ » -' ^ ,o
=« 5 - °. S
•- ° *: 10
S S S S S
* co « >: <°
S
••?. ? i 1 S
s
w « oi r-.
« i-: rC •» 9
*- .^- CD  :1?
E ' 1 1 1 1 = ?•
> > > > a o
« "• W. Z M 03
1 S > ^ " "
i£ i§ -2 o o o o
3 0 B t t w <" <" O3
                                    C-7

-------
  z
  o
  §
fc 2
5 










S1-O51O-1140
S1-O427-1200
S1-0413-1145


S1-O330-1235
IAS
ijg
ci _
•C g
I I
|


JS

S
1

i
B

3

S
£
S
IO
J5
IO
n
IO

|

5


CO
CO
CM
CO
IO


D


10

I
CO
o.
i
3
2
L
i
3
I
O
o
c
i


1

0
o


to
o
CD
0
*-

1
"
%


0
o
CO
_,
1

E
R
»
as
?
a
o

1
i

a


CM
d
CO
r«
CM

£
CO
*
CM

39
09
CM
CO

*

3
&
^
o
CO
e
o
S
C4
O

1

o
d


o
o
1
o

CO
CM
o
B
d

CM
99
d
CO

a

_o
i
B
O
e
0
CD
O9
O
o

1

s
0


CM
o
d
as
as
o
e

§
o
t
CM
o*

N
d
CO

"a

3
5
O
O
c
0
o
o
CO
p
e
c


I

m
d


0*
O9
CM
09
O

o
CO
CO
"
o
CM

S
CO

I

5
5
u
0
0
c
c
o
CM
CM

1
i

0
09


IO
10
CM
CM


CM
CM*

O
CO

10
CO
CM
CO

1

1
1
to
T
s
CD
CQ
*•

1

CO
CO
6


0
CO
CO
'"'

R.

10
-

CO
10
CO

a

]
a>
o
o
c
0
CO
c
s
o
e
o

1
en
CM
§
O


g
o
d
CO
d

8
S
d
to
CO
o
d

F*
1
d
CO

"5

5
D
e
e
o
c
CM
O

1

d


CO
CM
d
CM


8

A
d

§
d
CO

1

%
a
10
i—
tv
CM
•"

I

S
d


n
o
o
CM
*~

J

10
-

10
CO

?

I
o
o
fm


1

"c


o
o






d

d
CO

E

|
E
D
%
c
CO
V,

e*j

i

as
CO


CO
CM"
09


S"

to
g

3
CO

D

3
1
1
e
§
l£
g
d
S
d
g
IO
•—
O)
S
"
o
§
g

to
1
e>
§
o
o
o
•V
r^
|
C
CM

"o
E
0
I
I
                                   to

                                   I

<0
I
18
CO





CO
_>•
atlstteal A
fn




SI -O5 10-1 140

S1-O427-1200
S1-0413-1145

SI -0330-1 235
H?

•B e
m o
si
1
. 1

i
*
1
B
5 ,
1
a
£
C
CO
CO
n
CO
CN
CO*

s
to
s
o
CM'
O
«"
o
co'
5

CD
CO
CO*
*
1
X
•a
i
CO
o

o
CM
d

CM
d

o
CM
O
d
CO
d

CM
o
CO
d
*
n
3
•a
D
u
*
e
o

o
CO

0
la
CO

CO
CM
O
10*
9
CM

^

0)
*
p
a.
3
                        C-8

-------
         g J
         UI  C
    U,
00

6

CD
(/)




I
UI
a
a
            CM

            1
£  c3   >

£ |   o


S ~   §.

U CO   <
        •Bl"£

s
i
j
R
CO





.fa
1
C
Statistical fi










S2-O5 10-1 155


S2-O413-1200
S2-O330-1215
8 « —

1 g
; • «•
i

V:i
? . e
e ,

l
c •
5* •


I
i
£
0»
C
0
ej
69
C
^1
1

CO
a

E
5

a>
m
CO
CM
O
CO

3
CO

>
i
1
L
i
£
*


S
1

1

i
a

e
0

CO
9
CO
z
i



£
i
*
r
j
c
i

C"
a
o

00
B
5

{
i

>
ID
CO

*


.

o
c

o
as
t
o
§

c
o

c
6
O

3
6
6

9
o'
CO

>


1
:
1
C
CO
o
e
o
i

g
c
o

c
o
a

D
O
p
0
3
p"

1
o
C9

f


\
\
t
1
If
c
o
o
o
c
c
o
1

n
a
e

1C
6
c

s
o
6
o
0
CM
0

i
6
CO

>

_
>
•^
u
c

CO
1C
Q
a
1

o
a

5
if

s
eo°
O)
CO
CO

10
o
00
m

>


I
a.

1
co
o
11
c*
o
1

1C
c
o

CO
6
£
T.
O

s
a>
o
0
9
O

5
6
CO

*



^
1
«
c
o
o
I
.<
o
i

§
e
o
m
e
o
d

9
6
M'
O
a'

1C
9
?
«

>


i
a
!
»

O
p
e
C
1

r
o

S
6
S

CO
CO
o
«
6.

o
CO
o
«

»

i
i
i
4
10
(
{
c
r.
O
i
o
I

|
o

6
i
6

1C
g
6
^
6

o
)
CO

"


J
=?
c


o
I

J
c

'O
6
o"

6
o

6
CO

»


l

5


u
r
1

e>
e
CO

o
CD

to
o>

o
9
CO-

>




I
1
1
Q
O
e
c
c
«i
o
o
c
e
c

c1
a
r-

S
s
$

1
9
0
S
o
3
-

I

!
1
1

<
J
^
0

Istlcal Analyses
0

S2-05 10-11 55
S2-0427-1145
S2-O413-1200
S2-0330-1215
lil
II
; I I
J
1

i
; i
*
" ... B
"•' • 5
- •. 3
' £
1
I
CO
C
CO
00
u
a
e>
c
o
^
o
00
l£
ce
S
CO

CO*
J
co
CO
(

1
c
e
V-
o
c
o
1C
o
n
p
p*
X
6

CM
d
m
o
m
~?
3
O
i
(
(
ID
C
O
0
o
5
1C
•""
o
s.
ta
s

CO
o'
1C

CO
«
L
i
L
i
1
                                                          C-9

-------
                                                                           Appendix C
 5.     Samples  W5-0308-1045   &   W5-05TO-105   (Table C.4),  W4-0302-1050  &
        W4-0309-1040  (Table C.5),  and  W6-0302-1110 & W6-0309-1100  (Table C.6):
        these samples gave  values for ammonia that exceeded the samples' TKN values.
        This was determined to be a consequence of the analytical  method for TKN when
        the TKN comprises mainly  ammonia (the sample must be refluxed for a period  of
        time which can drive some of the volatile  ammonia  from the sample).  When this
        was first observed, the analytical method was modified slightly to account for  this.
        However, where this occurred, the TKN value was assumed to equal the ammonia
        value.

 Statistical Analysis

        After the initial review described above, the data were analyzed statistically.  The
 analyses performed on the data were as follows:

 •       Kolgomorov-Smirnov  (K-S) distribution testing  to determine whether the data was  in
        a  normal or  lognormal  distribution.  T.hese  analyses were performed  as many
        statistical tests (e.g. = T-tests) assume a normal distribution.   Consequently, if the
        data is lognormal, it  is necessary to  "transform"  it before  further tests  are
        performed.
                                /      ' -      *
 •       K-S lack-of-fit testing to identify  any statistically  outlying data that  should be
        discarded. These outliers were removed in  order that they would not influence the
        process evaluation, by influencing the mean data either upwards or downwards.  It
        was intended that, by removing  outliers,  the  data would better reflect the normal
        operating conditions of the process rather than being influenced by a "spike" result.

        The K-S distribution  tests were performed on  the  water quality data using  the
 program Statgraphics Plus, Version 7.0 (distributed by  Marmgistics).

        The K-S lack-of-fit tests^were carried out using the following equation:
                                   TNI  =
                                           X(n) - X
       Where        TN1 is the factor generated by the discordancy test; ,
                     X(n) is value being tested for discordancy;

                     x is the mean of the data set; and
                     s is standard deviation of the data set.

       This lack-of-fit test assumes a normal distribution and identifies a single outlier only.
This was considered suitable for the sample sizes  in this study (in most cases, the n was
between 9  and 11).   In each  case,  the value furthest from the mean  was tested  by
comparing the factor generated  with a critical value, for a 5% significance level, found in
statistical tables (see Table C.9). If the generated factor was greater than the critical value,
then the point tested was determined to be an outlier and was removed from the data set.
                                            C-10

-------
                                                                             Appendix C
         In the main,  the. K-S distribution testing of the data was inconclusive as to its
 nature. This is not surprising owing to the relatively low number of values in the data sets.
 Because of this situation, an assumption had to be made concerning the distribution of the
 data.

        Typically, most environmental data occurs in a lognormal distribution which is a
 reasonable assumption considering that much environmental data comprises data gathered
 about the mean value with some spike values - these spikes skew the data into a lognormal
 distribution pattern.  If this assumption was made, the data would have to be "transformed"
 (by taking the natural log of each data value) before further statistical  tests  were carried
 out.

             Table C.9  Critical Values for a Single Outlier in a Normal Sample
.'.«''
3
•\
i .4
5
. ' -6,.;
7
. • 8
' 9
10
-12
14
15 • '
16
18
20
30 ;
40
Significance Level
•:"&%'•-.
1-15

1.46 , .
1.67 :
i.82
- 1 .94
2.03
2.11 .
2.18
2.29
2.37
2.41
2.44
2.50
2.56
2.74
2.87
1%
1.15

1 .49
1.75
1.94
2.10
2.22
2.32
2.41
2.55
2.66
2.71
2.75
2.82
2.88
3.10
3.24
                        This table is abridged from Grubbs and Beck (1972).

       However, in this situation, it was considered that a spike value might, influence the
data adversely (by increasing or decreasing the mean),' with respect to the evaluation of the
system's "normal" operating conditions.  This is because one spike, in a sample population
of 9-11 values  could  have a  large influence on  the mean,  therefore, for this process
evaluation, the assumption was made that the data was in a  normal distribution  pattern
and, consequently, the data was nol transformed before further statistical testing.

       The lack-of-fit  testing identified a total of 26 outliers  throughout the data sets.
Additional K-S distribution tests were subsequently performed on the modified data.
                                            C-11

-------
                                                                                    Appendix C
The  results  of both the  K-S  distribution  tests and the lack-of-fit tests  are provided in
Tables C. 10 through C.20.

        Table C.10   Distribution Test Results for Total Chemical Oxygen Demand
                                                    K-S Distribution Test Factor
Laboratory
 Sample
Location
                                                Whole Data Set
Normal(2)
Lognormal
                                                                      (3)
ID
Outlier Removed <4)
      Normal
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
W1
W2
W3 .
W4
W5
W6
0.966
0.914
0.781
0.816
0.486
0.799
0.943
0.928
0.588 '
0.998
0.767
0.741
n/a
n/a
n/a
0.890
0.957
n/a
(1)      These factors are basicall probabilities that the data is arranged,in either a normal or a lognormal
(2)      This column shows the factors for the K-S test of the hypothesis that the distribution is "normal".
(3)      This column shows the factors for the K-S test of the hypothesis that the distribution is "lognormal".
(4)      This column shows the factors for the K-S test of the hypothesis that the distribution is "normal", once a
        single outlier has been removed from the data set. "n/a" in this column indicates that there were no
        outliers removed from this data set.
        Table C.11   Distribution Test Results for Soluble Chemical Oxygen Demand
Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Sample
Location
W1
W2
W3
W4
W5
W6
K-S Distribution Test Factor
Whole Data Set Outlier Removed
Normal Lognormal Normal
0.881
0.642
0.357
0.720
0.979
0.676
0.958
0.618
0.569
0.997
0.989
0.9998
0.986
n/a
0.921
n/a
n/a •
0.894
                                                 C-12

-------
                             Appendix C
Table C. 12 Distribution


Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES,
Parsons ES
Parsons ES
Table C.13


Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES • .
Parsons ES
Table


Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
'Parsons ES '

Sample
Location
W1
W2
W3
W4
W5
W6
Test Results


Normal
Oi849
0.940
0.517
0.886
0.892
0.371
for Total Biochemical Oxygen
K-S Distribution Test Factor
Whole Data Set
Lognormal
0-947
, 0.955
0.533
0.9998
0.309
0.554 ":•
Distribution Test Results for Soluble Biochemical Oxygen

Sample
Location
W1
W2
W3
W4
W5
W6

K-S Distribution Test Factor
Demand

Outlier Removed
Normal
n/a
n/a
0.427
0.858
0.720
0.262
Demand

Whole Data Set Outlier Removed ,
Normal
0.947
0.692
0.953
0.521
0.912
O.TQ8
, Lognormal
0.983
0.849
0.917
0,534
0.969
0.158
, Normal
n/a
n/a
n/a
0;419
n/a
O.075
N "'""'"', i
C.14 Distribution Test Results for Total Suspended Solids

Sample
Location •
W1
W2
W3
. W4
W5
W6

K-S Distribution Test Factor

Whole Data Set Outlier Removed
Normal
0.575
0.941
0.710
0.047
: 0.340
0.233
Lognormal
0.920
0.879
0.485.
0.357
0.519
0.492
• Normal
,0.987
n/a
n/a
0.304
0.722 . -
0.347
C-13

-------
                            Appendix C
Table C.15 Distribution Test Results for Volatile Suspended Solids
Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES

Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Sample
Location
W1
W2
W3
W4
W5
W6
Table C. 16 Distribution
Sample
Location
W1
W2
W3
W4
W5
W6
K-S Distribution Test
Whole Data Set
Normal Lognormal
0.924 0.9996
0.945 0.923
0.922 0.996
0.042 0.305
0.097 0.228
0.149 . 0.295
Test Results for Total Kjeldhal
K-S Distribution Test
Whole Data Set
Normal Lognormal
0.865 0.797
0.906 0.972
0.914 0.811
0.826 0.986
0.772 0.894
0.590 0.978
Factor
, Outlier Removed
Normal
0.999
n/a
n/a
0.103
0.242
0.109
Nitrogen
Factor
Outlier Removed
Normal
n/a
n/a
n/a
n/a
n/a
n/a , ,
Table C.17 Distribution Test Results for Ammonia
Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Sample
Location
W1
W2
W3
W4
W5
W6
K-S Distribution Test
Whole Data Set
Normal Lognormal
0.999 0.999
0.961 0.993
0.999 0.991
0.315 ~ '• 0.891
0.994 0.9995
0.271 0.975
Factor
Outlier Removed
Normal
n/a
n/a
n/a
n/a
n/a
n/a >
C-14

-------
                                                                     Appendix C
Table C.18 Distribution

• ,
Laboratory
Parsons ES
Parsons ES
Parsons ES
Parsons ES
Parsons ES •*
Parsons ES



Laboratory
Parsons ES
Parsons ES
Parsons ES ,
Parsons ES
Parsons ES
Parsons ES


: , >-•
Laboratory
Parsons ES
Parsons ES

Sample
Location
W1
W2
W3
; W4
W5
W6
Table C. 19
.
Sample
. Location
' W1
W2
W3
W4
W5
W6
, Table. C.20

Sample
Location'
W1
W6

Test Results for Nitrate
K-S Distribution Test Factor
. . Whole Data Set
Normal
0.262
0.448
0.309
0.886
' 0.739
0.074
Lognormal
0.540
0.358
0.773
0.504
0.944
0.762
Distribution Test Results for Total Phosphorus
•-p
K-S Distribution Test Factor
Whole Data Set
Normal
0.247
, 0.995
0.505
0.011
0.985
0.993
Distribution Test

, .Lognormal
0.405
0.990
0.135
0.038
0.994
0.994
Results for Fecal Coliform
K-S Distribution Test Factor


Outlier Removed
Normal
n/a
n/a
0.529
.. n/a
0.853
0.696
' • *
•
Outlier Removed
Normal
0.895
n/a
0.783
0.627
n/a
n/a


Whole Data Set Outlier Removed
Normal
0.586
0.008
Lognormal
0.858
0.663
Normal
n/a
0.325
A simple description of the study data is provided in Table C.21.
                                    C-15

-------
                              Appendix C

Table C.21. Simple
Statistical
Description for Water Quality Data
Statistics
Sample
Location
W1











•
W2











Water Quality
Parameter
COD (total)
COD (soluble)
BOD5 (total)
BOD5 (soluble)
TSS
VSS
TKN
Ammonia
Nitrate
Total Phosphorus
Fecal Coliform 8,
Reid pH
Reid DO
COD (total)
COD (soluble)
BOD5 (total)
BOD5 (soluble)
TSS
VSS
TKN
Ammonia
Nitrate
Total Phosphorus
Field pH
Field DO
Mean
1,307.0
157.5
468.8
70.1
470.4
364.0 ,
55.9
25.6
0.16
13.6
109,091
7.98
2.9
444.7
216.2
160.0
107.7
78.0
64.0
43.3
33.8
0.15
8.17
7.26
4.9
Standard
Deviation
243.2
13.6
116.4
- 14.3
136.4
96.4
7.1
4.2
0.07
2.2
6,872,184
0.27
1.0
76.1
15.6
32.4
22.9
22.5
20.7
6.7
5.9
0.06
1.47
0.17
1.3 ,
Analysis

One outlier (21 2) was removed from these
data statistically.


Two values (229 & 71 5) increased the
standard deviation of the data. One outlier
(1,040) was removed from these data
, statistically. •
One value (520) increased the standard
deviation of the data. One outlier (765) was
, removed from these data statistically.


Three values (0.24, 0.28 & 0.29) increased
the standard deviation of the data.
One outlier (37.6) was removed from these
data statistically.
The range of values (2,400,000 to
24,000,000) was responsible for the high
standard deviation.''

The range of values (1 .2 to 4.7) was
responsible for the high standard deviation.




One value (1 1 7) increased the standard
deviation of the data.
The range of values (33.5 to 91.3) was'
responsible for the high standard deviation.
i

Two values (0.24 & 0.26) increased the
standard deviation of the data.


-
C-16

-------
                              Appendix C
Table C.21 Simple Statistical Description for Water Quality Data (continued)
, Statistics
Sample Water Quality
Location Parameter
W3 COD (total)
COD (soluble)

BOD5 (total) :
• "* ' . •''--,

. BODS (soluble)

...;'• , '* TSS • • '
vss

TKN
Ammonia
Nitrate


'
' Total Phosphorus

Field pH
Field.DO
W5 COD (total)

COD (soluble)
BOD5 (total)
i " •
BOD5 (soluble)
•' • '"
TSS

VSS
4 . '

TKN
Ammonia
Nitrate



Total Phosphorus
. Field pH
Field Dp
Mean
399.4
63.8

105.6
.
9.7

148.0
122.0

46.0
28.0
0.38
•• • •


8.54

7.61
4.9
149.8 ,

50.7
49.4

6,4,

42.6

33.6


29.9
22.9
2.12



8.0
7.47
5.5
Standard
Deviation
81.4
7.0

9.1

3.1

36.2
30.8

6.0
4.6
. 0.22



1.19

,0.12
1.1
27.6

11.5
10.0 /

2.2

9.2

1 1 .6


6.1
4.1
1.41



1.2
0.07
1.3
Analysis

One outlier (105) was removed from these
data statistically. "
One outlier (71) was removed from these
data statistically.
The range of values (6.3 to 1 5) was
responsible for the high standard deviation.
. ' • . . ' , • •. •
One value (182) increased the standard
deviation of the data.


Two values (0.62 & 0.85) increased the
'Standard deviation of the data. One outlier
(1.58) was removed from these data
.statistically.
One outlier (1 .69) was removed from these
data statistically. : -
" ' ' : - ' • ' - .','•'

One outlier (279) was removed from these
data statistically.

One outlier (7.2) was removed from these
data statistically.
The range of values (4.0 to 1 0.0) was
responsible for the high standard deviation.
One outlier (1 22) was removed from these
data statistically. , •
One value (62.5) increased the standard
deviation of the data. One outlier (101) was
removed from these data statistically.


The range of values (0.22 to 4.71) was
responsible for the high standard deviation.
One outlier (7.44) was removed from these
data statistically.

**" '

• r~ ' '. ; ' \ : ' r ~~~~ ~~~ ^~~~' — ! 	 ' 	
C-17

-------
                                                                                       Appendix C
     Table C.21   Simple Statistical Description for Water Quality Data (continued)
 Sample
Location
Water Quality
Parameter
     Statistics  .

Mean       Standard
            Deviation
Analysis
   W4        COD (total)            73.4          39.1       The range of values (25.6 to 141) was
                                                            responsible for the high standard deviation.
                                                       ,     One outlier (256) was removed from these
                                               -             data statistically.

              COD (soluble)          43.2          19.0       The range of values (14.2 to 74.1) was
                                                            responsible for the high standard deviation.
        •»•                 '                                  One outlier (130) was removed from these
                                                            data statistically.

              BODS (total)           18.4          11.6       The range of values (4.0 to 39.0) was
                                                            responsible for the high standard deviation.
                                                            One outlier (73) was removed from these
                                                            data statistically.                  • '

              BODS (soluble)         11.3          11.2       The range of values (4.0 to 37.0) was
                                                            responsible for the high standard deviation.
                                                            One outlier (59) was removed from these
                                                            data statistically.

              TSS                  9.9           6.3       One value (25.7) increased the standard
                                                            deviation of the data.  One outlier (98.3)
                                                            was removed from these data statistically.

              VSS                  6.3           5.5       One value (21.4) increased the standard
                                                            deviation of the data.  One outlier (43.3)
                                                            was removed from these data statistically.
TKN
Ammonia
Nitrate
Total Phosphorus
Field pH
Field DO
10.0
7.5
10.49
7.0
7.15
3.5
4.8
6.6
6.89
0.8
0.14
0.9
The range of values (3.1 to 17.9) was
responsible for the high standard deviation.
The range of values (0.32 to 1 7.9) was
responsible for the high standard deviation.
The range of values (1 .32 to 24.1 ) was
responsible for the high standard deviation.
One outlier (34.5) was removed from these
data statistically.
' '. • •

  W6         COD (total)        '  53.2          33.0      The range of values (10.0 to 128) was
                                                           responsible for the high standard deviation.

              COD (soluble)         38.3          23'.1      The range of values (10.0 to 78.6) was
                                                           responsible for the high standard deviation.
                                                   ,        One outlier (128) was removed from these
                                                           data statistically.                       '

              BODS (total)           12.5          13.2      The range of values (4.0 to 42.0J was
                                                           responsible for the high standard deviation.
                                                           One outlier (88)  was removed from these
                                                           data statistically.

              BODS (soluble)         10.2          12.8      The range of values (4.0 to 41.0) was
                                                           responsible for the high standard deviation.
                                                           One outlier (80)  was removed from these
                                                           data statistically.
                                                 C-18

-------
                                                                     Appendix C
Table C.21  Simple Statistical Description for Water Quality Data (continued)
Sample Water Quality
Location Parameter >
W6(contd.) TSS
vss
TKN
Ammonia
Nitrate
Total Phosphorus
Fecal Coliform
i . - •
Field pH
Field DO
Statistics
Mean Standard Analysis
Deviation

3.5 2.4 The range of values (2.0 to 8;2) was
responsible for the high standard deviation.
One outlier (1 9.8) was removed from these
data statistically.
2.2 0.4' One outlier (10.4) was
data statistically.
8.4 7-0 ' The range of values (1.
responsible for the high
5.5 . 6.3 The range of values (0.
responsible for the high
removed from these
5 to 23.5) was
standard deviation.
1 to 17.3) was
standard deviation.
5.40 5.20 The range of values (0.39 to 1 7.3) was
responsible for the high standard deviation.
One outlier (69.7) was removed from these
data statistically.
6.8 ,0.8

170 236 , The range of values (4 to 800) was
responsible for the high standard deviation.
One outlier (30,000) was removed from
these data statistically. ' v


                                    C-19

-------

-------
                                    Appendix D
                             Raw Data: Tracer Study


       This appendix contains the raw data recorded during the tracer study performed at
the AEES, to determine hydraulic detention times of the various process equipment.  The
data  are in  the form of  sampling  times  and ;the  corresponding lithium  chloride
concentrations, and are provided in Tables D.1 through 6.7. The graphs of the tracer stqdy
data are presented in Figures D-1 through D-7.

       The  detection limit  for the  lithium  analyses  was 0.02 mg/l lithium.  Where the
concentration of lithium was determined to be < 0.02 mg/l, a concentration of 0.02 mg/l is
quoted for the purposes of plotting the graphs and calculating HDTs.
                                           D-1

-------
          Table D.I
 Tracer Study Data Summary
Sample Point T1 (High-rate Marsh)
Sample
Starting Point (9:00)
T1 -0404-1 000
T1 -0404-1 100
T1 -0404-1 200
T1 -0404-1 300
T1 -0404-1 400
T1 -0404-1 500
T1 -0404-1 600
T1 -0404-1 700
T1 -0404-1 800
T1 -0404-1 900
T1 -0404-2000
T1 -0404-21 00
T1 -0404-2200
T1 -0404-2300
T1 -0404-2400
T1 -0405-01 00
T1 -0405-0200
T1 -0405-0300
T1 -0405-0400
T1 -0405-0500
T1 -0405-0600
T1 -0405-0700 .
T1 -0405-0800
T1 -0405-0900
T1 -0405-1 000
T1 -0405-1 100
T1 -0405-1 200
Time
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00-
12:00
Lithium Chloride
Concentration (mg/l)
0.020
0.020
0.020
0.020
0.020
0.052
0.381
0.766
0.971
0.920
0.820
0.663
0.501
0.348
0.236
0.165
0.117
0.097
0.075
0.061
0.049
0.040
0.036
0.035
0.032
0.029
0.028
0.023
              D-2

-------
           Table D.2
  Tracer Study Data Summary
Sample Point.T2 (Duckweed Clarifier)
Sample
Starting Point (9:50)
T2-0412-1050
T2-0412-1150
T2-0412-1250
T2-0412-1350
72^0412-1450
72-0412-1550
T2-0412-1650
T2-0412-1750
72-0412-1850
72-0412-1950
72-0412-2050
T2-0412-2150
T2-04 12-2250
T2-041 2-2350
T2-0412.-0050
72-0413-0150
72-0413-0250
T2-041 3-0350
T2-041 3-0450
T2-041 3-0550
T2O41 3-0650
T2-04 13-0750
|T2-041 3-0850
Time
9:50
10:50
11:50
12:50
13:50
14:50
15:50
16:50
17:50
18:50
19:50
,20:50
21:50
22:50
23:50
0:50
1:50
2:50
3:50
4:50
5:50
6:50
7:50
8:50
Lithium Chloride
Concentration (mg/l)
0.020
0.020
0.042
0.024
0.079
0.182
0.395
. 0.464
0.437
0.415
0.408
0.382
0.344
0.313
0.264
0.230
0.186
0.164
0.146
0.121
0.108
0.095
0.088
0.075
              D-3

-------
             Table D.3a
     Tracer Study Data Summary
Sample Point T3 (Ecological Fluidized Beds)
            Second Attempt
Sample
Starting Point (10:00)
T3-0620-1100
T3-0620-1200
T3-0620-1300
T3-0620-1400
T3-0620-1500
T3-0620-1600
T3-0620-1700
T3-0620-1800
T3-0620-1900
T3-0620-2000
T3-0620-2100
T3-0620-2200
T3-0620-2300
T3-0620-2400
T3-0621-0100
T3-0621-0200
T3-0621-0300
T3-062 1-0400
T3-0621-0500
T3-0621-0600
T3-062 1-0700
T3-0621-0800
T3-062 1-0900
T3-0621-1000
T3-0621-1100
T3-0621-1200
T3-0621-1300
T3-0621-1400
T3-0621-1500
Time
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
Lithium Chloride
Concentration (mg/l)
0.020
0.023
0.076
0.134
0.183.
0.221
0.262
0.277
0.288
0.297
0.304
0.298
0.297
0.293
0.287
0.275
0.271
0.264
0.260
0.249
0.241
0.234 .
0.224
0.218
0.209
0.202
0.195
0.190
,0.183
0.178
                  D-4

-------
       Table D.3a (continued)
    Tracer Study Data Summary
Sample Point T3 (Ecological Fluidized Beds)
            Second Attempt
Sample
T3-0621-1600
T3-0621-1700,
T3-0621-1800
T3-0621-1900
T3-062 1-2000
T3-0621-2100
T3-062 1-2200
T3-0621-2300 >
T3-062 1-2400
T3-Q622-0100
T3-0622-0200
T3-0622-0300
T3-0622-0400
T3-0622-0500
T3-0622-0600
T3-0622-0700
T3-0622-0800
T3-0622-0900
T3-0622-1000
T3-0622-1100
T3-0622-1200
T3-0622-1300
|T3-0622-1400
T3-0622-1500
T3-0622-1600
T3-0622-1700
T3-0622-1800
T3-0622-1900
T3-0622-2000
T3-0622-2100
Time
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1 :00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
1 0:00
1 T:00
12:00
13:00
14:00
15:00
16:00
1 7:00
18:OQ
19:00
20:00
21:00
Lithium Chloride
Concentration (mg/l)
0.170
0.166
0.160
0.154
0.150
0.145
0.141
0.136
0.131
0.126
0.122
0.117
0.114
0.108
0.106
0.101
0.098
0.095
0.092
0.088
0.086
0.084
0.081
0.077
0.076
. 0.073
0.069
0.067
0.068
0.065
                 D-5

-------
             Table D.3b
    Tracer Study Data Summary
Sample Point T3 (Ecological Fluidized Beds)
             First Attempt
Sample
Starting Point (10:00)
T3-0417-1100
T3-0417-1200
T3-0417-1300
T3-0417-1400
T3-0417-1500
T3-0417-1600
T3-0417-1700
T3-0417-1800
T3-0417-1900
T3-041 7-2000
T3-0417-2100
T3-041 7-2200
T3-041 7-2300
T3-041 7-2400
T3-0418-0100
T3-041 8-0200
T3-041 8-0300
T3-041 8-0400
T3-041 8-0500
T3-041 8-0600
T3-041 8-0700
T3-041 8-0800
T3-041 8-0900
T3-0418-1000
T3-0418-1100
T3-04 18-1 200
T3-0418-1300
T3-0418-1400
T3-041 8-1 500
Time
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
Lithium Chloride
Concentration (mg/i)
0.020
0.020
0.020
0.040
0.060
0.087
0.123
0.162
0.200
0.216
0.229
0.233
0.249
0.203
0.193
0.197
0.200
0.202-
0.211
0.220
0.214
0.207
0.202
0.193
0.185
0.200
0.197
0.185
0.181
0.173
                  D-6

-------
       Table D.3b (continued)
     Tracer Study Data Summary
Sample Point T3 {Ecological Fluidized Beds)
             First Attempt
Sample
T3-0418-1600
13-041,8-1700
T3-0418-1800
13-0418-1900
T3-041 8-2000
T3-0418-2100
T3-04 18-2200
T3-04 18-2300
T3-041 8-2400
T3-0419-0100
T3-041 9-0200
T3-04 19-0300
T3-04 19-0400
T3-04 19-0500
T3-041 9-0600
T3-04 19-0700
T3-04 19-0800
T3-041 9-0900
T3-0419-1000
T3-0419-T100
T3-0419-1200
T3-0419-1300.
T3-0419-1400
T3-0419-1500
T3-0419-1600
T3-0419-1700
T3-0419-1800 .
T3-041 9-1 900
T3-041 9-2000
T3-0419-2100
Time
16:00
17:00
18:00
1 9:00
20:00
21:00
22:00
23:00
0:00
1 :OQ
2:00
3:00
4:00 ...
5:00
6:00
7:00
8:00
9:00
10:00
11:0.0.
1 2:00
13:00
14:OO
15:00 .
16:00
17:00
18:00
19:00
20:00
21:00
Lithium Chloride
Concentration (mg/l)
0.165
0.158
0.149
0.143
0.137
0.132
0.126
0.122
0.118
0.1 13
0.109
0.103
0,099
0.095
0.092
0.090
0.084 ,
0.084
0.077
0.081
0.084 .
0.085
0.081
0.078
0.074
0.074
0.065
0.063
0.063
0.063
                 D-7

-------
               Table D.4
      Tracer Study Data Summary
Sample Point T4 (1st Ecological Fluidized Bed)
Sample
Starting Point (1 0:00)
T4-0424-1100
T4-0424-1200
T4-0424-1300
T4-0424-1400
T4-0424-1 500
T4-0424-1600
T4-0424-2400
T4-0424-2500
T4-0424-1 900
T4-0424-2000
T4-0424-2100
T4-0424-2200
T4-0424-2300
T4-0424-2400
T4-0425-0100
T4-0425-0200
T4-0425-0300
T4-0425-0400
T4-0425-0500
T4-0425-0600
Time
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1 :00
2:00
3:00
4:00
5:00
6:00
Lithium Chloride
Concentration (mg/l)
0.020
0.574
0.450
0.359
0.289
0.243
0.207
0.176
0.154
0.133
0.118
0.106
0.092
0.090
0.081
0.076
0.068
0.066
0.058
0.053
0.047
                   D-8

-------
         Table D.5
Tracer Study Data Summary
Sample Point T5 (Aerated Tanks)
Sample
Starting Point (10:00)
T5-0425-1100
% T5-0425-1200
T5-0425-1300
T5-0425-T400
T5-0425-1500
T5-0425-1600
T5-0425-2500
T5-0425-2600
T5-0425-2700
T5-0425-2000
T5-0425-2100
T5-0425-2200
T5-0425-2300
T5-0425-2400
T5-0426-0100
T5-0426-0200
T5-0426-0300
T5-0426-0400
T5-0426-0500
T5-0426-0600
T5-0426-0700
T5-0426-0800
T5-0426-0900 ,
T5-0426-1000
T5-0426-1100
T5-0426-1200
T5-0426-1300
T5-0426-1400
T5-0426-1500
T5-0426-1600
T5-0426-2500
T5-0426-2600
T5-0426-2700
Time
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00 •
16:00
17:00
18:00
19:00 ,
Lithium Chloride
Concentration (mg/I)
0.020
0.135
0.238
0.313
0.370
0.406
0.434
0.447
0.456
0.458
. 0.446
' 0.435
i 0.427
0.421
0.400
0.392
0.372
0.360
0.338 ;
0.327
0.315 ,
0.300
0.279
0.268
0.268 , •
0.262
0.253
0.239
0.233
0.226
0.215
0.178
0.163
0.150
            D-9

-------
   Table D.5 (continued)
Tracer Study Data Summary
Sample Point T5 (Aerated Tanks)
Sample
T5-0426-2000
T5-0426-2100
T5-0426-2200
T5-0426-2300
T5-0426-2400
T5-0427-0100
T5-0427-0200
T5-0427-0300
T5-0427-0400
T5-0427-0500
T5-0427-0600
T5-0427-0700
T5-0427-0800
T5-0427-0900
T5-0427-1000
T5-0427-1100
T5-0427-1200
T5-0427-1300
T5-0427-1400
T5-0427-1 500
T5-0427-1600
Time
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
• 8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
Lithium Chloride
Concentration (mg/l)
0.140
0.135
0.130
0.122
.,- ' 0.116
0.137
0.123
0.119
0.117
0.114
0.111
0.103
0.100 '
0.095
0.092
0.081
0.077
0.075
0.073
0.070
0.067
           D-10

-------
          Table D.6
 Tracer Study Data Summary
Sample Point T6 (1st Aerated Tank)
Sample
Starting Point (9:30)
T6-0502-1030
T6-0502-1130
T6-0502-1230
T6-0502-1330
T6-0502-1430
T6-0502-1530
T6-Q502-1 630
T6-0502-1730
T6-05Q2-1830
T6-0502-1930
T6-0502-2030
T6-0502-2130
T6-0502-2230
T6-0502-2330
T6-0502-0030 ,
T6-0503-013Q
T6-0503-0230
T6-0503-033Q
T6-0503-0430
T6-0503-0530
T6-0503-0630
T6-0503-0730
T6-0503-0830
T6-0503-0930
T6-0503-1030
T6-0503-1130
T6-0503-1230
Time
9:30
10:30
1 1 :30
12:30
13:30
14:30
15:30
1 6:30
17:30
18:30
19:30
20:30
- 21:30
22:30
23:30
0:30
1:30
2:30
3:30
4:30
5:30
6:30
7:30
8:30
9:30
10:30
11:30
12:30
Lithium Chloride
Concentration (mg/l)
0.020
0.504
0.445
0.390
0.344
. 0.304
0.278
0.252
0.233
0.212
0.198
0.186
0.171
0.161
0.151
0.142
0.137
0.132 ,
0.129
0.125
0.119
0.116
0.112
0.107
6.102
0:094
0.089
0.084
             D-11

-------
            Table D.7
   Tracer Study Data Summary
Sample Point T7 (Anaerobic 3io-reactor)
Sample
Starting Point (10:30)
T7-0509-1130
T7-0509-1230
T7-0509-1330
T7-0509-1430
T7-0509-1530
T7-0509-1630
T7-0509-1730
T7-0509-1830
T7-0509-1930
T7-0509-2030
T7-0509-2130
T7-0509-2230
T7-0509-2330
T7-05 10-0030
T7-05 10-01 30
T7-05 10-0230
T7-05 10-0330
T7-05 10-0430
T7-05 10-0530
T7-05 10-0630
T7-05 10-0730
T7-05 10-0830
T7-05 10-0930
T7-0510-1030
T7-05 10-1 130
T7-0510-1230
T7-0510-1330
T7-05 10-1 430
T7-05 10-1530
Time
10:30
1 1 :30
12:30
13:30
14:30
15:30
1 6:30
17:30
18:30
19:30
20:30
21:30
22:30
23:30
0:30
1:30
2:30
3:30
4:30
5:30
6:30
7:30
8:30
9:30
10:30
11:30
12:30
13:30
14:30
15:30
Lithium Chloride
Concentration (mg/l)
0.020 .
0.025
0.040
0.076
0.188
0.344
0.503
0.575
0.636
0.682
0.670
0.680
v 0.674
0.667
0.654
0.621
0.585
0.539
0.506
0.476
0.461
0.452
0.427
0.395
0.330
0.279
0.257
0.237
0.225
0. 1 96
                 D-12

-------
      Table D.7 (continued)
   Tracer Study Data Summary
Sample Point T7 (Anaerobic Bio-reactor)
Sample
T7-0510-1630
T7-05 10-1 730
T7-05 10-1 830
T7-0510-1930
T7-051 0-2030
T7-05 10-2 130
T7-05 10-2230
T7-05 10-2330
T7-051 1-0030
T7-0511-0130
T7-051 1-0230
T7-051 1-0330
T7-051 1-0430
77^0511-0530
77-0511-0630
77-0511-0730
77-0511-0830
T7-05 11-0930
77-0511-1030
T7-0511-1130
T7-0511-1230
77-0511-1330
T7-051 1-1430
77-0511-1530
T7-0511-1630
T7-0511-1730
T7-0511-1830
I
T7-05 11-1 930 ...
Time
16:30
17:30
18:30
19:30
20:30
2.1:30
22:30
23:30
0:30
1:30
2:30
3:30
4:30
5:30
6:30
7:30
8:30
9:30
10:30
11:30
12:30
13:30
14:30
15:30
16:30
17:30
18:30
.19:30
Lithium Chloride
Concentration (mg/l)
0.177
0.159
0.140
0.128
0.130
0.125
0.108
0.103
0.094
0.087
0.088
0.082
0.074
0.068
O.Q63
0.061
0.059
0.058
0.052
0.048
0.042
0.040
0.039
0.038
0.037
0.038
0.040
0.034
I










                D-13

-------
       l
T  o  ?
Q  S -5
 0  Q S*
    o -^
    3
    8  o
    £ to
        o
        o
                                  (I/BUI) UOJJBJIU90UOO IQJ1



                                               D-14

-------
                                                  0)
                                                  S
(I/Bui) uojiBJjuaouoo ion

           D-15

-------
       ,8?
    to 03
co     -—
 «   0> (0
 o>

131
    O
       CO
       O
       O
                              O        O        O        O


                                (|/6ui) uoiiejjuaouOo ion
                                            D-16,

-------
    Q  q>

    -

r\
   CO  CO
       eo
       o
       O
(I/6iu)
                                                     ion
                                            D-17

-------
LO

Q
     is
11
0)  J?
SI"
5  $
D) ^
   03 '.1
   O 5
   2 .2
   X. 4^
   H CD
     o
     o
                       (I/Bui) uoijBjjuaouoo ion



                                D-18

-------
                                                0)
                                                E
(l/Biu) uojjenuaouoo ion

          /D-19

-------
Q
   fc

 Si
•= OQ
 E .o
& <$.
 03 P
Q QJ
-o
3
    Co
    c
o

S  c
h-  o
   '•M
    (0
    o
                            (l/Biu) uoijBJiuaouoo ion
                                       D-2O

-------
                                    Appendix E
               Raw Data: Water Quality (System Without Plants)
       This appendix contains the raw data from the three-week  study that investigated
the performance of the Advanced Ecologically Engineered System once the plants had been
removed from the Aerated Tanks.

       These water quality data were not subjected to the same statistical  analyses that
were performed upon the wastewater data from the eleven-week process evaluation.  This
was owing to the small sample size (3 samples per location) which, it was considered,
made distribution testing and lack-of-fit testing meaningless. Summary statistics, however,
were generated for this data.                               '

       All of the  raw water quality data for this three-week evaluation, along  with their
summary statistics, are shown in Tables  E.1 to E.6.
                                          E-1

-------
<  z
E521

3
&
I
a
I





|
|

'





W1-OR22-0935


W1-OB1S-1010


W1-OS08-0945

III!
||
si
j
1
i
i
c
i


|
O
e


Ci


S3
*"
f.
ia
o


o
o
V3
q
q
1
C9
!


Totll COD
S


M
a


o

r*
n
3

O
ID
1
o
S
cs
«,
1

n
Solubit CO
c


8


n

ID
n
'
I
C9
I
§
M
OJ
0
n
i


[Totll BQDt
R


o


p»

a
M
^
'
q
ID
r*
§
o
S
q
o
n
1

g
I
1


£


S

CT
ID
«,

q
S
ID
O
i
i
o
i
co
a


(A
12
g


i


m

o
B
^

q

-------
         2
         g
u
o
S
    O z
    a §i
    a: S S
    in UU
    •a?- i i
co
^
e
£•
i
o
«
1



t>
•»
•1
Statistical A








W2-OC21-OS30
W2-OB14-09SS

W2-O807-103S

Iff I
li
!
:• t
' 1 .
'. i



|

1
; :
e ^
< 09



m
o

c
^
0
K
D
O
a
r*.
I
o
CD
2
IA
>



p


S
*

e
n

ti
^
a
O
a
»
*
a>
t
i



»


i
r*«

e
fin

&
OS
P
4-
s
Cj
n
9
jj
9



p


;


C
N

B>
C
C
/Q)
A
«.
n
n
"t
7
«
9





I
i
s
1

<

5
c
O
o
o
o
o
o



^

1
1
r*
o
<

8
*"
C
fC
«|
«r
CD
ID
5
5
>





I
f
L
i
                                                               G2-OB21-O935
                                                               G2-O814-1O15
                                                              G2-OBO7-1O45
                                                                    s-
                                                                  lt
                                                                  o
                                                                  s
 I
.€
 •<5
 E

 3
 S

                                                                                     1
                                                                                   I
                                               E-3

-------
        f? »
          §
«
              S

       5-i
       UI o.

       S I
•i
1
&
2-
S
•3
5




*
-1





W3-0821-09SO


W3-O014-1O30



W3-OSO7-1110
IfH
in*
II
s&
I

1
s
X
i
e
1



1
|


CN
«r



s
9
S
CO

1

o
I
q
9
GO
n
CO
i

n
n
u
|
«
C
10


s



»
s
CN
fl)
id

m
o
to

J
o
o
8
N
O
.
1

O
o

a
1
n
o


o



5
2
o

o

e
e
9
S
0>
o
D

.

|
«
^


n
09



"
5
3

CO

o.
m
CD
CD
0
"C
Ol

o

|
i
r*
1C


5



a
s
1C

0
CO

1
o
s
s
CO
D



A
5


c



«
S
«>
M
CO
10
O)

i

e
S
q
o
1
CO
f



to
s
5


M
•3
GO



0
S
•o
o
,

CO
CO

I
N
CO
CD
CO
•s



z
s


a
^
d



ID
S
a
6
e
o

i

I
,,,
to
ID
IO
CM
CO
z
I



i
'M
5


n
o



IO
«
6
5
o

o"

S

o
N
O
n
z
I



|
z
e>
pC


IT
co



s
m
*
S

S

s

p.

-------
     <

     Q
111   =
    LU
    H

    S
o S
2 J5
I J2


iy
> 0>
f- o
u.

1-
       < .£
       ui  o

       E Q-
       I- _£

          Q.


          ea
         (O
s

I
i
1C
j
C
•g
s


r




S
J.
1
•I
03









WS-0621-101O § CM §
WS-OB14-1O55 S1'^ § i*


WSV0607-1145 2 S R S


^1°S 2 oo " !
|j85
•B J
•8 | t "» ^ ^ t
• If a s <»• - s
(00
* S « q « «
•S ^ " a » s

•g §•?«."««
• * S •• S 5 S 5

•' f. iilss
I 2: 5 2'r -2
I S S n ^ c?
= m ra co ra co
1 •-••lf|'|s

! 8 ! §i 1
E — 2 3
E S = | 5 J>
5 IS- § ? s
co ci ex V «j
. •? «- a -a
CT ^ cj d PC

eo co 
. _
M CM CM O' "°
C, C, C, C, C,
I | i t i

i

1 I I 1 IJ





SAMPLES
m
O
•- •




J
er Quality Re
1


I
Statistical A




•-
G5-O621-1O15 H| ,
• G5-O614-11O5 i|
G5-0607-1155 Si| i
1 1 g ^ 1 °
y. '.HI'S
J I*
jc SsS; «x
J §§§§ ,«
1 - 111 ^
1 • 1 =.
• * 1| "*
e 5§§§S ._
" ^ *
<= § -
;
s =
•* o ?
E - "•
e- s %
in 0
«' S
2 §
eo 9
u> ^
-: q I
« eg ^Q
2
cs
CO CO §
1
.
S 2 i
" • s
«. • *>
CD P Q)
- • ^ co
• a s
o
o
• £
52-5
3
i
3
u
o <». "5
<°' « °
£
«J
- • ? I
Jc
o
c
o- -
i s
5 »'5=
t f
                                                 E-5

-------
U)

111
        i
      J2 "s

      i2
    £ o 1
    «i H ^
    Q x 1
    >-
u.

•S"
       CO

       i

ifcf I

ii! I
£ 2-2 I

5&? s
i II
  5 =
  Ui o
  eft |\,
,
«r Quality Ri
1



M
e
•1
SUti>tic*IA







W4-OB22-1010
W4-0615-1O4S
W4-O603-1015
. lili
II
II
3
i
i
s




!
o
c
c
K
0
c
in
in
Ci
f-.

O
CD
CO
K
o
d
to
CM
CO
in



5
jTotil COD
c
c
o
CO
o
e
S

*"
i
CD
CO
i
CD
cn
CO



I
[Soluble COD
c
fx
O
to
c
CM
CD
|x
OS
O
CM
q
ID
CD
n



1
(Total BOD6
&
rx
> a
CO
tn
o
CM
to
IX
q
m
m
CD.
at



D
(Soluble BODB
J
c
0
c
IX
O
O
CM
*r
CM
CO
IX
CD
CD



"5
f)
0
a
e
a
0
e
tc
cs
CD
~
CD
CO
If
CD*
CD
CO
5



E

t
u
c
CM
oa
0
01
in
CD
CO
ui
to
3)
CO




»
1
c
c
0
p
IX
tc

CO
o>
CN
at
CD
CO
rx
D



i
[Ammonia
c
g
p
in
o
S
CO
*•
in
en
q
O)
CM
n
CM



a
9
03
e
Q
IX
C
fx
q
CD
O
2
00
2
CD




i
3
3
                                        CO

                                        S
                                              G4-Q622-1025
                                                              1
                                              G4-O61S-110B
                                              G4-O60S-1035
                                                o E
                                                   1


                                                        1
                                                                  J
                                                                  §
                                                                  CO
                                                                  £
                                                                  &
                                                                  •o
                               E-6

-------
      --I


<

a
cc
Ul

I
     if
— o
S «'



si

i5
5 5

£ c
ui 6
S •£
£ -2
^ a.
1U £

.^I
S
         S

<
 0
5 * *
. CO 0


ra o ^ K.
o o" «' ri ,
°- °- 2 § ' s
"* N ~ ° <

? 3 2 & s

> o °! -•! r-
> " 2 2 e

« S 2 o


-
o o «= =i






0 ,

(D
^
O 1**
» ^
0 c


6 °
s -•


9 ®


>r*»





^
£
.











09
1U
.J

4
09
ffi
1.
















i
4
C
5









o
"S
1
1
in






•«.„;.
GS0615-113S

66:0608-1105 ;

8 5 3 -
| I o I S
o JE ra ~
•p c
ll 1
»a


J O
3 Z


z ' a



J g
• * 
-------

-------
                                    Appendix F
              Cost Estimates for Conventional Treatment Systems
 Introduction
       This  task  involved  obtaining  or developing capital  and  O&M  cost  data  for
conventional treatment  systems  for comparison   against the  Advanced  Ecologically
Engineered  System that is presently  being  pilot-tested in Frederick, MD.   All  of  the
conventional treatment systems that were costed are packaged treatment systems;   the
only costs that were estimated were for concrete tankage, electrical supply and connection,
and  instrumentation.  Specifically, the costs for yard piping,  buildings, site  preparation,
land, and equipment redundancy are  not included in these cost  estimates.  These cost
estimates were developed to be comparable with cost data provided by OAI  for similarly
sized AEES.                                                   .

Influent Wastewater Characteristics and Effluent Discharge Criteria

       For the purpose of this report, the  influent wastewater characteristics (strength) and
effluent-criteria for the conventional, treatment systems are the .same as for the  AEES.
These values are provided in Tables F.1 and F.2 below.

                      Table F.1  Influent Waste Characteristics
Parameter
Total COD
Soluble COD
Total BODS
Soluble BOD5
TSS
VSS
TKN
Ammonia
Nitrate
Total Phosphorus
Unit
mg/l
mg/l
mg/l
rrig/I
mg/l
mg/l
mg/l
• • '- i
mg/l-N
mg/l-N
mg/l-P '
Concentration in Influent
. . . i
t 1,043
174.5
325
. 81 .5
• 357 .
273
45
25.9
0.1
11.2
                                           F-1

-------
                                                                           Appendix F
        Table F.2  Effluent Criteria used for Conventional Treatment Cost Evaluation
             Parameter
Unit
Effluent Critieria
Total BOD5
TSS
Ammonia
Nitrate -
Total Phosphorus
mg/l
mg/l
mg/l-N
mg/l-N
mg/l-P
< 10
< 10
< 1
< 5.
< 6
        The flowrates included in this evaluation are 40,000 gpd (the same flowrate as the
AEES in Frederick, Maryland), 80,000 gpd, and  1 mgd.

        Biological nitrogen removal  has been included in the selection of the conveptional
treatment systems for comparison.  Nitrification, the  oxidation of ammonia to nitrate, and
denitrification,  the reduction of nitrate to nitrogen gas, can be accomplished biologically
without" the addition of an external  carbon source  by two of the conventional systems
evaluated - the oxidation ditch and the sequencing batch reactor. The packaged extended
aeration plants require an  external  carbon source  (methanol) for denitrification.   The
carrousel oxidation ditch requires alum for phosphorous removal.             1  '

Conventional treatment systems

        The costs of the following treatment  technologies were evaluated  in this estimate:

•       For the 40,000 gpd conventional system, we have costed out a small conventional
        (extended aeration) packaged wastewater treatment plant.

•       For the 80,000 gpd system,  we have  costed out  sequencing batch reactor with
        prefabricated tankage and With concrete tankage option.

•       For the 1  mgd system, we have costed  out a packaged BNR wastewater treatment
        plant and a carrousel oxidation ditch.

Ultraviolet disinfection was included for microbial inactivation prior to discharge.  This cost
was based on a manufacturer's quotation, for the  complete UV disinfection  lamps with a
steel channel and the appropriate instrumentation.

Method of Cost Estimating

       The  cost  of  the equipment  and size of the  tankage  has been  provided  by the
manufacturer of the  technology based on historical information  assembled as a result of
supplying these systems to  clients  in the requested size range.  In the  cases where the
manufacturer recommends  that  the tankage be constructed of reinforced  concrete, the
                                            F-2

-------
                                                                            Appendix F
 quantity of concrete has been estimated and priced;  If not included in the manufacturer's
 quote,  materials and  labor pricing for  installing  the equipment  was  estimated  as  a
 percentage {25%} of the equipment cost.  The cost for instrumentation was included in the
 manufacturer's quotation;  the  equipment recommended by  the  manufacturer allows for
 automatic operation of the system.  Mobilization, bonds and  insurance, and miscellaneous
 direct cost are assumed  to be a, percentage of the direct cost of construction.  Overhead
 and profit is assumed 'at 15%, and a contingency of 1 5% was included to cover other items
 that could not accurately estimated.

       1 The AEES is primarily a treatment process for the liquid stream and  not the solids
 stream; therefore, this  evaluation focuses on the treatment cost of the  liquid stream.
 However, capital and O&M 'costs for sludge handling and  disposal are estimated*,  where
 applicable. The method of disposal assumed for the smaller facilities (40,000  and 80,000
 gpd) is  via a septic hauler to an off-site treatment facility, eliminating any  capital  costs.
 This method of sludge disposal  is typical for treatment facilities of this size. The larger 1
 mgd facilities are costed for a sludge handling facility, which includes a polymer system,
 belt filter presses, and lime stabilization equipment:  A sludge digestion tank is included in
 the package plant and the corresponding capital costs.  Sludge digestion is not  required for
 the sludge produced  by the oxidation ditch  since primary sludge  is not produced by  this
 system. The cost is based on information received from the  Downingtown WWTP, PA.

        The cost estimate for O&M is based on information from the manufacturer on power
 requirements,  number of operators  required, and  the additional cost of  chemicals, if
 required,, A unit O&M cost for sludge processing, stabilization, and disposal  at the 1 mgd
 facilities is based on historical  data  from ALCOSAN Diversified Resuidua/s Management
 Program, 1994 and Sludge Management Alternatives Evaluation Report, 1994.  This value,
 $500.00 per dry ton, includes belt filter press dewatering,  lime  stabilization, and contract
 land application.  Costs for sludge handling and disposal at the  40,000 gpd and 80,000  gpd
 facilities is estimated  based  on quotes  for  septic haulers to  remove and dispose  the
 residuals from a proposed 15,000 gpd SBR facility in the Village of Aldie> VA,

        In developing a conceptual estimate of this type, the focus is on the tankage  and
 the equipment.  Other ancillary items, such as exterior lighting and paving, while required
 for construction, have not been included.  It is assumed that the  costs of these ancillary
 items have not been included in the cost estimate prpvided by OAI.

 Cost Estimates for 40,000 gpd Conventional Treatment System

 Extended Aeration S
       The estimated capital cost for a packaged treatment system that is rated for 40,000
gpd  is $405,000.  This cost is for a complete steel packaged extended  aeration system
constructed  on an  at-grade concrete pad.  A denitrifying filter  and UV disinfection  are
included  at. the  end of the process  for  denitrification  and final  polishing  as well as
disinfection.  The packaged treatment system  is 12 feet wide by 12 feet high by 80 feet
long and the filter is 8 feet wide by 1 2 feet high by 16 feet long.

    •„  The estimated cost for  annual  operation and  maintenance,  which includes sludge
processing and disposal, is  approximately $65,900. Based on a twenty year plant life and
assuming an annual inflation rate of 7%, the present value for  operation and maintenance is
                                            F-3

-------
                                                                          Appendix F
 $697,000.  The total present value,  $1,102,000, is the sum of the capital cost and the
 present value of operation and maintenance.

 Cost Estimates for 80,000 gpd Conventional Treatment System

 Sequencing Batch Reactor - Package Treatment System

       For this flow regime,  two sequencing batch reactor systems were costed out; one
 with concrete tankage and one with prefabricated tanks. These costs are the average cost
 of these two SBR Systems.. The estimated capital cost  for an SBR that is rated for 80,000
 gpd is $659,800. This cost is complete for two  24' x 24' tanks with mixing equipment, a
 filter with automatic backwash, and UV disinfection.                          -

       The average annual cost for operation and maintenance of the two SBR systems is
 estimated at $78,000 per year.  Assuming a 7% interest rate and a life  cycle of 20 years
 bring the present worth of operation and maintenance to $827,6QO.   The total present
 value for capital cost and O&M is estimated at $1,486,900.

 Cost Estimates for 1 mgd Conventional Treatment Systems

 Packaged BNR Treatment Plant

       The estimated capital  cost for a 1 mgd packaged BNR treatment plant $3,324,700.
 This cost is complete  for a circular packaged system, complete with a denitrification filter,
 UV disinfection, and a s'ludge handling facility.  This cost is based on a steel structure that.
 is field-supported on a concrete pad.

       The annual cost for operation and maintenance is estimated at $371,400 per year.
 Assuming a 7%  inflation rate  and  a  life  cycle  of 20  years bring the  present worth  of
 operation and  maintenance to approximately $3,934,900.  The  total  present value  for
 capital cost and O&M  estimated at $7,259,600.

 Carrousel Oxidation Ditch

       The  estimated capital cost for a carrousel  oxidation  ditch  is  $3,307,700 and
 includes  a concrete carrousel "racetrack" style tank complete with mixers and  a return
 sludge pumping station, aeration  equipment,  two final clarifiers, polishing filter, and UV
 disinfection and a sludge handling facility!

       The  annual cost for O&M of  the  carrousel system is $320,900 and the  present
 worth cost at  7% interest over 20 years is $3,399,700.  The total present  worth cost  of
this system is $6,707,400.
                                            F-4

-------
Pack. Plant (40,000 gpd)
EPA ABES Evaluation
Task 3D: Conventional Treatment Systems Estimate
Treatment System

Mean's Ref. No.
Division 1 - Genei

Evaluated and Avg Daily Flow:

Item
al - • • ,

Division 2 - Sitework


Division 3 - Concrete
1.1-140-6300
i.i-soa-ono

Division 7 - Them

Footer excavation and construction
Base slab construction

lal and Moisture Protection •

Division 8 - Doors and Windows


Division 9 - Finishes .


Division 10 - Specialties (none)


Division 11 - Equipment




Package Plant (12* w x 12' h x 80' 1)
inc. filtration equipment
UV disinfection

Division 12 - Furnishings (none)


Division 13 - Special Construction


Division 14 - Conveying Systems (none) •


Division 15 - Mechanical


Division 16 - Electrical




-'.



^


Subtotal
Bonds, Insurance @
Mobilization @
Miscellaneous Direct Costs @

Total
Contractor's OH & P @
Contingency @




Package Plant @ 40,000 gpd

Qty.





184
36










1

1








;












Unit





If
cy






-



Is

Is












3%
4%
10%


15%
15%

. Unit
Price





$ 50.00
$ 250.00










$ 238,750.00

$ 9,450.00






















Total
Price





$ 9,200.00
$ 8,888.89










$ 238,750.00

$ 9,450.00











> 266,288 89
J 7,988 67
! 10,651.56
; ' 26 628 89

1 311,558.00
! 46,733.70
i 46,733.70
! 405,025.40
       F-5

-------
Pack. Plant (40,000 gpd)
EPA ALTERNATIVES EVALUATION

OPERATIONS AND MAINTENANCE ESTIMATE
SYSTEM: PACKAGE PLANT
FLOWRATE: 40,000 GPD

PREPARED BY:
CHECKED BY:

ENERGY CONSUMPTION

ITEM
EST. ENERGY CONSUMPTION
EST. ENERGY CONSUMPTION - UV

CHEMICAL CONSUMPTION

METHANOL

MANPOWER REQUIREMENTS


OPERATOR @ $25/HR INC. FRINGE

SLUDGE PROCESSING AND DISPOSAL


SLUDGE PROCESSING & DISPOSAL (1)

TOTAL DAILY OPERATING COST
YEARLY OPERATING COST



ANNUAL MAINTENANCE ESTIMATED
AT 1% OF CONSTRUCTION COST





BFS
KJK



•









QTY
4



QTY
40000




















KW-HRS/DAY
358
4.1


LBS/DAY
35



UNIT/DAY
HRS/DAY



UNIT/DAY
GALLONS








(

ANNUAL OPERATING AND MAINTENANCE COST


PRESENT VALUE BASED ON 20 YEARS AT 7%














UNIT
PRICE
$ 0.07
$ 0.07


U.P.
$ 0.23


UNIT
PRICE
$ 25.00


UNIT
PRICE
0.0009












10.594










TOTAL
PRICE
$ 25.07
$ 0.30


TOTAL
$ 7.95
t

TOTAL
PRICE
$ 100.00


TOTAL
PRICE
$ 36.00

$ 169.32
$ 61,801.06


-

$ 4,050.25


$ 65,851.32

$ 697,628.87































' X










Note: (1) Sludge collected by septage hauler and disposed by the hauler at a cost of $95/hr. The cost to
remove sludge from a 15,000 gpd SBR plant is $5,000 per year. Cost per gallon treated at this rate is
S0.0009/gal. treated






        F-6

-------
,SBR (80,000 gpd)
••••-• EPA AEES Evaluation
Task 3D: Conventional Treatment Systems Estimate
Treatment System

Mean's Ref. No.
Division 1 - Gene

Division 2 - Skew

, Division 3 - Conci
1.1-140-6300
1.1-500-0170


Division 4 - Maso

Division 5 - Misce

Evaluated and Avg Daily Flow:

Item
ral

ork

rete". -. • . • . . -
Footer construction.
Base slab construction
Tank wall construction

nry
>
llaneous Metals

Division 6 - Woods and Plastics

Division 7 - Them

Division 8 - Doors

-• - • •
lal and Moisture Protection

and Windows
i , .
Division 9 - Finishes

Division 10 - Speci

, Division 1 1 - Equii




Division 12 - Fund

Division 13 - Speci

Division 14 - Conv<

Division 15 - Mech

Division 16 - Electr


•
• •• ]
]


<
<
1 	 _ 	 __I

aides

nnent
SBR Equipment and installation
Filtration equipment
UV disinfection

shings (none)

al Construction

tying Systems

anical '•

ical • ... •

Subtotal
Bonds, Insurance @ -
Mobilization®
Miscellaneous Direct Costs @

Fotal
Contractor's OH & P @
Contingency®



SBR @ 80,000 gpd

Qty.





250
140 .-.
250
















1
1
1





















Unit





>-.lf
cy
cy
















Is
rls
Is












3%
4%
10%


15%
15%



Unit
Price





$ 50.00
$ 250.00
$ 350.00
















$ 230,742.40
$ 40,000.00
$ 11,060.00






















Total
Price





$ 12,500.00
$ 35,000.00
$ 87,500.00
















$ 230,742.40
$ 40,000.00
$ 11,060.00











$ 416,802.40
$ 12,504.07
$ 16,672.10
$ 41,680.24

$ 487,658.81
$ 73,148.82
$ 73,148.82
$ 633,956.45
     F-7

-------
SBR (80,000 gpd)
EPA ALTERNATIVES EVALUATION

OPERATIONS AND MAINTENANCE ESTIMATE
SYSTEM: SEQUENCING BATCH REACTOR
FLOWRATE: 80,000 GPD

PREPARED BY:
CHECKED BY:

ENERGY CONSUMPTION

ITEM
EST. OPERATING BRAKE HP - SBR
EST. ENERGY CONSUMPTION - UV

CHEMICAL CONSUMPTION - NONE

MANPOWER REQUIREMENTS


OPERATOR @ $25/HR INC. FRINGE

SLUDGE PROCESSING AND DISPOSAL


SLUDGE PROCESSING & DISPOSAL (1)

TOTAL DAILY OPERATING COST
YEARLY OPERATING COST



ANNUAL MAINTENANCE ESTIMATED
AT 1% OF CONSTRUCTION COST





BFS
KJK







,



QTY
4



QTY
80000


. -





*
s
ANNUAL OPERATING AND MAINTENANCE COST

PRESENT VALUE BASED ON 20 YEARS AT 7 %






1 -





KW-HRS/DAY
334
8.16





UNIT/DAY
HRS



UNIT/DAY
GALLONS














/








UNIT
PRICE
$ 0.07
$ 0.07




UNIT
PRICE
$ 25.00


UNIT
PRICE
0.0009












10.594

•








TOTAL
PRICE
$ 23.38
$ 0.60




TOTAL
PRICE
$ 100.00


TOTAL -
PRICE
$ 72.00.

$ 195.98
$ 71,531.12




$ 6,339.56


$ 77,870.69

$ 824,962.07

Note: (1) Sludge collected by septage hauler and disposed by the hauler at a cost of $95/hr. The cost to
remove sludge from a 15,000 gpd SBR plant is $5,000 per year. Cost per gallon treated at this rate is
$0.0009/gal. treated




     F-8

-------
Pack. SBR (80,000 gpd)
EPA AEES Evaluation
Task 3D: Conventional Treatment Systems Estimate
Treatment System Evaluated and Avg Daily Flow:

Mean's Ref. Nc

> Item >,
Division 1 - General


Division 2 - Sitework

Divisions - Coi
1.1-140-6300
1.1-500-0170


ncrete '••"._•
Footer construction
Base slab construction

Division 7 - Thermal and Moisture Protection


Division 8 - Doors and Windows »


Division 9 - Finishes


Division 10 - Specialties (none)

Division 11 -Eq





uipment
Package Plant (12' w x 12' h x 80' 1)
inc. filtration equipment
UV disinfection

Division 12 - Furnishings (none)


Division 13 - Special, Construction


Division 14 - Conveying Systems (none) . ,


Division 15 - Mechanical ,


Division 16 - Electrical




•


.
•


Subtotal
Bonds, Insurance @ ^
Mobilization®
Miscellaneous Direct Costs @

Total
Contractor's OH & P @
Contingency @




Package Plant @ 80,000 svd

Qty





,244
36










1

1





















Unit





If
i cy










Is ,-

Is












3%
4%
10%


15%
15%

Unit
' Price .





$ 50.00
$ 250.00










$ 418,000.00 |
^
$ 11,060.00

















i




Total
Price





$ 12,200.00
$ 8,888.89


,







$ 418,000.00

$ 11,060.00











$ 450,148.89
$ 13,504.47
$ 18,005.96
$ 45,014.89

$ 526,674.20
$ 79,001.13
$ 79,001.13
$ 684,676.46
       F-9

-------
Pack. SBR (80,000 gpd)
EPA ALTERNATIVES EVALUATION

OPERATIONS AND MAINTENANCE ESTIMATE
SYSTEM: SEQUENCING BATCH REACTOR
FLOWRATE: 80,000 GPD

PREPARED BY:
CHECKED BY:

ENERGY CONSUMPTION

ITEM
EST. OPERATING BRAKE HP - SBR
EST. ENERGY CONSUMPTION - UV
•
CHEMICAL CONSUMPTION - NONE

MANPOWER REQUIREMENTS


OPERATOR @ $25/HR INC. FRINGE

SLUDGE PROCESSING AND DISPOSAL


SLUDGE PROCESSING & DISPOSAL

TOTAL DAILY OPERATING COST
YEARLY OPERATING COST






BFS
KJK













KW-HRS/DA







QTY
4



QTY
80000







334
8.16





UNIT/DAY
HRS



UNIT/DAY
GALLONS







TENANCE ESTIMATED AT 1 % OF CONSTRUCTION COST






ANNUAL OPERATING AND MAINTENANCE COST


PRESENT VALUE BASED ON 20 YEARS AT 7%














UNIT
PRICE
$ 0.07
$ 0.07




UNIT
PRICE
$ 25.00


UNIT
PRICE
0.0009












10.594










TOTAL
PRICE
$ 23.38
$ 0.60




TOTAL
PRICE
$ 100.00


TOTAL
PRICE
$ 72.00

$ 195.98
$ 71,531.12




$ 6,846.76


$ 78,377.89

$ 830,335.34











•


>

















• .







Note: (1) Sludge collected by septage hauler and disposed by the hauler at a cost of $95/hr. The cost to
remove sludge from a 15,000 gpd SBR plant is $5,000 per year. Cost per gallon treated at this rate is
S0.0009/gal. treated
1 1



     F-10

-------
Pack. Plant (1 mgd)
• .• EPA AEES Evaluation
Task 3D: Conventional Treatment Systems Estimate
Treatment System Evaluated and Avg Daily Flow:

Mean's Ref. Nc

> Item
Division 1 - General


Division 2 - Sitework


Division 3 - Concrete
1.1-140-6300
-. •
1.1-500-0170


Footer construction (121' dia. tank)
Footer construction (12* x 105' filter)
Base slab construction (tank)
Base slab construction (filter)

Division 7 - Thermal and Moisture Protection


Division 8 - Doors and Windows


Division 9 - Finishes


Division 10 - Specialties (none)

Division 1 1 - EC





uipment
Package Plant (121 w x 12' h x!20' 1) '
1 inc. filtration equipment
UV disinfection

Division 12 - Furnishings (none) -


Division 13 - Special Construction "


Division 14 -Conveying Systems (none)


Division 15 - Mechanical


Division 16 - Electrical







••
,
,

.
1


Subtotal
Bonds, Insurance @
Mobilization @
Miscellaneous Direct -Costs @

Total
Contractor's OH & P @
Contingency @
Subtotal
• ••
Solids Handling Facility (1)
Contractor's OH & P @
Contingency®


Package Plant @ 1 mgd

Qty.





379.S
234
425.7
46.67










1

1




• -




















Unit





If
If
cy
cy










Is'

Is


'









3%
4%
10%


15%
15%



15%
15%
Unit
Price ;

,

••- •

$; 50.00
$ 51.00
$ 250.00
$ 251.00








" '! ' '

$ 1,165,000.00

$ 44,800.00





-




















Total
Price





$ 18,997.00
$ 11,934.00
$ 106,418.38
$ 11,713.33










$ 1,165,000.00

$ 44,800.00








• .
•

5 1,358,862.71
5 40,765.88
! 54,354.51
> 135,886.27

I 1,589,869.37
! 238,480.41
1 238,480.41
i 2,066,830.19

880,539
132,081
_ 132,081
     F-1'1

-------
                              Pack. Plant (1 mgd)
Subtotal
      1,144,700
Total
$   3,211,531
NOTE: (1) Capital costs were scaled using the six-tenths rule.
             Log-log plot of capacity versus equipment cost for a given type of equipment
             should be a straight line with a slope of 0.6. Solids handling capital cost were
             scaled from a 7 mgd (5.5 DTPD) design capacity plant - Downingtown WWTP.
             Aerobic digester cost was included in the original cost estimate.  This cost estimate
             represents additional solids handling equipment downstream of the digester -
            polymer system, belt filter presses, and lime stabilization equipment.
                                     F-12

-------
Pack! Plant (1 mgd)
EPA ALTERNATIVES EVALUATION
OPERATIONS AND MAINTENANCE ESTIMATE
SYSTEM: PACKAGE PLANT ,
FLOWRATE: 1 MGD

PREPARED BY
CHECKED BY.

ENERGY CONSUMPTION

ITEM
EST. DAILY POWER REQUIREMENTS
EST. DAILY POWER REQUIREMENTS- UV


CHEMICAL CONSUMPTION - NONE

METHANOL


MANPOWER REQUIREMENTS


OPERATOR @ $25/HR INC. FRINGE

SLUDGE PROCESSING AND DISPOSAL

. •. • • ..
SLUDGE PROCESSING & DISPOSAL

A .
TOTAL DAILY OPERATING COST
YEARLY OPERATING COST



ANNUAL MAINTENANCE ESTIMATED
AT 1 % OF CONSTRUCTION COST
• ' . - - ,- ' v






BKS
KJK















OIY
1



UIY
0.9











ANNUAL OPERATING AND MAINTENANCE COST

PRESENT VALUE BASED ON 20 YEARS AT 7%












KW-HRS/DAY
3939
81.6



LBS/DAY
130




UNIT/DAY
EA



UNIT/DAY
DTPD
I











%










UNIT
PRICE
$ 0.07
$ 0.07



U.P.
$ 0.23



UNIT
PRICE
$200.00


UNIT
PRICE
$500.00













10.594









TOTAL
PRICE
$ 275.72
$ 5.71



TOTAL
$ 29.55



TOTAL
PRICE
$ 200.00


TOTAL
PRICE
$ 450.00


$ 960.98
$ 350,757.35




$ 20,668.30


$ 371,425.66

$ 3,934,883.41











































    F-13

-------
CARROUSEL (1 mgd)
EPA AEES Evaluation
Task 3D: Conventional Treatment Systems Estimate
Treatment System Evaluated and Avg Daily Flow:

Mean's Ref. No.

Item
Division 1 - General


Division 2 - Sitework



Pump station wet well
Pump station drywell

Division 3 - Concrete
1.1-140-6300
1.1-500-0170





Footer construction (caroussel)
Base slab construction (caroussel)
Tank wall construction (caroussel)
Footer construction (clarifiers)
Base slab construction (clarifiers)
Tank wall construction (clarifiers)
•
Division 4 - Masonry (none)


Division 5 - Miscellaneous Metals

•
Division 6 - Woods and Plastics


FRP tanks for alum addition

Division 7 - Thermal and Moisture Protection


Division 8 - Doors and Windows


Division 9 - Finishes


Division 10 - Specialties

Division 11 -Equi







pment
Aeration Equipment
RAS Pump Station
Filtration equipment
UV disinfection
Clarifier Mechanisms

Division 12 - Furnishings (none)


Division 13 - Special Construction


Division 14 - Conveying Systems (none)

,
Division 15 - Mechanical


Division 16 - Electrical





Carrousel Oxidation Ditch @ 1 mgd

Qty.



1
1


634
1044
599
283
94
124






2






-



1
1
1
1
2







v




Unit



mh
mh


If
cy
cy
If
cy
cy






ea



•






Is
Is
Is
. Is
ea






•




Unit
Price i



$ 4,000.00
$ 4,000.00


$ 50.00
$ 250.00
$ 350.00
$ 50.00
$ 250.00
$ 350.00






$ 9,000.00










$ 206,250.00
$ 50,000.00
$ 312,000.00
$ 50,000.00
$ 60,000.00






, ' -•
*





Total
Price



$ 4,000.00
$ 4,000.00


$ 31,700.00
$ 261,000.00
$ 209,650.00
$ 14,130.00
$ 23,500.00
$ 43,400.00






$ 18,000.00










$ 206,250.00
$ 50,000.00
$ 312,000.00
$ 50,000.00
$ 120,000.00


'








      F-14

-------
CARROUSEL (1 mgd)






















I

Subtotal •
Bonds, Insurance @
Mobilization @
Miscellaneous Direct Costs @

Total
Contractor's OH & P @
Contingency®
Subtotal

Solids Handling Facility (1)
Contractor's OH & P @
Contingency®
Subtotal
•'• • - . •
Total Estimate
-- : - -





i












3%
4% .
10%

•>
15%
15%



15%
15%



-
NO it: (1) Capital costs were scaled using the six-tenths rule.








•




.




$ 1,347,630.00
$ 40,428.90
$ 53,905.20
$ 134,763.00

$ 1,576,727.10
$ 236,509.07
$ 236,509.07
$ 2,049,745.23

$ 880,538.75
$ 132,081
$ 132,081
$ ,1,144,700

$ 3,194,446
• ,

Log-log plot of capacity versus equipment cost for a given type of equipment
should be a straight line with a slope of 0.6. Solids handling capital cost were
scaled from a 7 mgd (5.5 DTPD) design capacity plant - Downingtown WWTP.
The digester is not required for the Carrousel oxidation ditch. This cost estimate
represents solids handling equipment (polymer system, belt filter presses.
and lime stabilization equipment).



      F-15

-------
CARROUSEL (1 mgd)
EPA ALTERNATIVES EVALUATION

OPERATIONS AND MAINTENANCE ESTIMATE
SYSTEM: CARROUSEL OXIDATION DITCH
FLOWRATE: 1MGD

PREPARED BY:
CHECKED BY:

ENERGY CONSUMPTION

ITEM
EST. DAILY POWER REQUIREMENTS


BFS
KJK





EST. DAILY POWER REQUIREMENTS- UV


CHEMICAL CONSUMPTION - NONE


MANPOWER REQUIREMENTS


OPERATOR @ $25/HR INC. FRINGE

SLUDGE PROCESSING AND DISPOSAL


SLUDGE PROCESSING & DISPOSAL


TOTAL DAILY OPERATING COST
YEARLY OPERATING COST



ANNUAL MAINTENANCE ESTIMATED
AT 1% OF CONSTRUCTION COST









OTY
8



OTY
1.08





















KW^HRS/DAY
1850.0
81.6


GAL/DAY




'UNIT/DAY
bis



UNIT/DAY
DTPD











ANNUAL OPERATING AND MAINTENANCE COST,


PRESENT VALUE BASED ON 20 YEARS AT 7%











UNIT
PRICE
$ 0.07
$ 0.07


U.P.



UNIT
PRICE
$ 25.00


UNIT
PRICE
$500.00













10.594









TOTAL
PRICE
$ 129.50
$ 5.71


TOTAL



TOTAL
PRICE
$ 200.00


TOTAL
PRICE
$ 537.50


$ 872.71
$ 318,539.88




$ 2,365.09


> 320,904.97

J 3,399,667.26









































     F-16

-------
                                     Appendix G
                            Cost Estimates for the AEES
        The AEES cost estimates presented in Tables G.1 and G.2 were provided in August
 1995 by Living Technologies, Inc., Burlington,  VT.  They include  significant revisions of
 original estimates that were provided in May  1995. As noted  in Section 13 of this report
 some modifications to the estimates below were made by the senior author of this report to
 reflect the actual costs for power  and gas,  the actual sludge production, and the actual
 horticultural revenue at the AEES facility in Frederick, MD.  Additional minor changes were
 made to ensure compatibility  between the AEES and Parsons ES estimates for labor rates,
 power rates, maintenance needs, etc.         ,

 Notes by the Senior Author of this Report

       Table G..1 estimates sludge  production at 40,000 gpd at about 2 dry ton per year.
; Based on the actual data from the Frederick system, the sludge production would be 12 dry
 ton per year.   This then requires an increase in size and costs for  the reed  beds.  These
 increases were then, extrapolated for the 80,000 gpd and 1 mgd flows for the cost tables in
 Section-13 of this report.                          .                  -

       Table G.1  estimates horticultural revenue at 40,000 gpd at $17,472.   The  May
 1995  cost estimate produced by Living Technologies assumed  a horticultural revenue of
 $5,411.   The  actual horticultural revenue at the  Frederick, MD facility during the 1995
 market season  was about $2,400 with 75  percent of that for the plants grown on the High-
 rate Marsh. The sale of potted plants grown on the other tanks returned about $600.  The
 cost estimates  for the systems in this appendix do  not include a marsh component so  the
 only horticultural revenue is from the potted  plants.  An estimate  of  4 times  the actual
 potted plant  revenue was  used  for the  40,000  gpd AEES  costs.tabulated  in Section  13.
 This value was then extrapolated to  the higher flow rates.

       Table G,2 gives gas costs at 40,000 gpd. at $1,800 per year.  Based on the records
 at Frederick, MD the gas costs are  $3>231 per year. This value was then extrapolated to
 the 80,000 gpd and 1 mgd  rates in Section 13 of the report.

       Table G.2 also gives electricity costs at $5,000 for 40,000 gpd. Based/on records
 at Frederick,  MD the  electricity costs were about $9,000 per year.  This value was then
 extrapolated to the higher flow rates in the cost tables in Section 13.

       The cost of reed beds increases because of the higher sludge  production which then
 increases the capital costs of the system,  and" also the maintenance  costs which are taken
 as  a percentage of the capital  costs.  Parsons ES used 1%  in their  estimates whereas
 Tables G.1  and G.2 used  2.5%.  For continuity, a value of 1% was used for all of the cost
 tables in Section 13.
                                        G-1

-------
                                Appendix G
Table
Item
Greenhouse Area
Number of operators
Costs w/ greenhouse
Construction
Annual O&M
Costs w/o greenhouse
Construction
Annual O&M
G.I Total
Units
ft2


«
*

$
$
Estimated System
40,000 gpd ' .
2,184
0.6

$402,475
$47,697

$348,414
$44,545
Costs for the AEES
80,000 gpd
3,000
0.8

$560,457
$66,689

$485,289
$62,410
-
1,000,000 gpd
31,584
3.6

$4,043,026
$373,471

$3,554,987
$339,270
Total Cost w/ greenhouse & reed bed „
Horticultural revenue
Plant residuals
Sludge residuals
Reed bed area
Reed bed cost
Construction
Annual O&M
Total Present Worth
Total Annual Cost
$
kg/yr
kg/yr
ft2
$
$
$
$
$
$17,472
430
4,148
1,383
. $13,826
$416,301
$49,128
$562,063
$88,427
$24,000
86 j
8,295 .
2,765
$24,886
$585,343
$68,690
$1,313,045
$123,946
$221,088
10,785
103,693
34,564
$207,386
$4,250,412
$384,675
$8,325,659
$785,913
G-2

-------
                                                                         Appendix 
-------

-------