v>EPA
                      United States
                      Environmental Protection
                      Agency
                      Off ice of Water
                      Washington, D.C.
EPA 832-F-99-048
September 1999
Storm Water
Technology  Fact Sheet
Wet Detention  Ponds
DESCRIPTION

Wet detention  ponds  are storm  water control
structures providing both retention and treatment of
contaminated storm water runoff.  A typical wet
detention pond design is shown in  Figure 1.  The
pond consists of a permanent pool of water into
which storm water runoff is directed. Runoff from
each rain event is detained and treated in the pond
until it is displaced by runoff from the next storm.
                    By capturing and retaining runoff during storm
                    events, wet detention ponds control both storm
                    water quantity and quality.  The pond's natural
                    physical, biological, and chemical processes then
                    work  to  remove pollutants.    Sedimentation
                    processes remove particulates, organic matter, and
                    metals, while dissolved metals and nutrients are
                    removed through biological uptake. In general, a
                    higher level of nutrient removal and better storm
                    water quantity  control can be  achieved in wet
                           Principal Release Pipe
                           Set on Negative Slope
                           to Prevent Clogging
     Riser with Trash Rack
     Emergency
     Spillway
                                     Deep Water Zone for
                                     Gravity Settling
   Riprap
                                      Riprap for Shoreline
                                      Protection
                                                   Inlet
                                                             Sediment Forebay
         Cutoff Trench
                         Concrete
                         Base
                                  Low Flow Drain for Pond Maintenance
                                  (should be designed to provide easy access and to
                                  avoid clogging by trapped sediments.)
  Source: Maryland Department of the Environment, 1986.

                FIGURE 1 TYPICAL LAYOUT OF A WET DETENTION POND

-------
detention ponds than can be achieved with other
Best Management Practices (BMPs), such as dry
ponds, infiltration trenches, or sand filters.

There are several common modifications that can
be made to the ponds to increase their pollutant
removal effectiveness. The first is to increase the
settling area for sediments through the addition of
a sediment forebay, as shown in Figure 1. Heavier
sediments will drop out of suspension as runoff
passes through the sediment forebay, while lighter
sediments will settle out as the runoff is retained in
the  permanent  pool.    A  second  common
modification is the construction of shallow ledges
along the  edge of the permanent pool.   These
shallow peripheral ledges can be used to establish
aquatic plants that can  impede  flow and  trap
pollutants as they enter the pond. The plants also
increase biological uptake of nutrients. In addition
to their function as aquatic plant habitat, the ledges
also have several other functions, which can include
including acting as a safety precaution to  prevent
accidental drowning and providing easy access to
the permanent pool to aid in maintenance. Finally,
perimeter wetland areas can also be created around
the pond to aid in pollutant removal.

APPLICABILITY

Wet detention ponds  have  been  widely used
throughout the U. S. for many years. Many  of these
ponds  have been monitored to  determine their
performance.    EPA Region  V  is  currently
performing a study on the effectiveness of 50 to 60
wet detention ponds.  Other organizations, such as
the Washington, D.C., Council of Governments
(WMCOG) and the Maryland Department of the
Environment,  have  also  conducted  extensive
evaluations of wet detention pond performance.

ADVANTAGES AND DISADVANTAGES

Wet detention ponds  provide both  storm water
quantity  and  quality  benefits,   and   provide
significant   retrofit  coverage  for  existing
development. Benefits include decreased potential
for downstream flooding and stream  bank erosion
and improved water quality due to the removal of
suspended solids, metals, and dissolved nutrients.
While the positive impacts from a wet detention
ponds will generally exceed any negative impacts,
wet detention ponds that are improperly designed,
sited, or maintained, may have potential  adverse
affects on water quality, groundwater, cold water
fisheries, or wetlands.  Improperly  designed  or
maintained ponds may result  in stratification and
anoxic conditions that can promote the resuspension
of solids and the release of nutrients and metals
from  the  trapped  sediments.    In addition,
precautions should be taken to prevent damage to
wetland areas during pond construction. Finally, the
potential for groundwater contamination should be
carefully evaluated.   However, studies  to  date
indicate  that   wet  detention  ponds  do   not
significantly   contribute   to   groundwater
contamination (Schueler, 1992).

The following limitation should also be considered
when determining the feasibility of installing a wet
detention pond:

1.      Wet  detention  ponds  must  be  able  to
       maintain  a  permanent pool of  water.
       Therefore, ponds cannot be constructed in
       areas  where   there  is   insufficient
       precipitation to maintain the pool or in soils
       that are highly permeable. In wetter regions,
       a small drainage area may be  sufficient to
       ensure  that there  is  enough water  to
       maintain a permanent pool; whereas in more
       arid regions, a larger drainage  area may be
       required. In some cases, soils that are highly
       permeable may be compacted or overlaid
       with  clay blankets to make the bottom less
       permeable.

2.      Land constraints, such as  small  sites  or
       highly developed areas, may preclude the
       installation of a pond.

3.      Discharges from ponds usually consist of
       warm water,  and thus pond  use may  be
       limited  in  areas   where  warm  water
       discharges from the pond  will adversely
       impact a cold water fishery.

4.      The local climate (i.e., temperature)  may
       affect the biological uptake in the pond.

-------
5.      Without   proper   maintenance,   the
       performance of the  pond will drop  off
       sharply. Regular cleaning of the forebays is
       particularly important.   Maintaining the
       permanent  pool  is  also  important  in
       preventing  the  resuspension of trapped
       sediments. The accumulation of sediments
       in the pond will reduce the pond's storage
       capacity  and  cause  a  decline  in  its
       performance.    Therefore,  the  bottom
       sediments in the permanent pool should be
       removed about every 2 to 5 years. In most
       cases, no  specific limitations  have been
       placed on disposal of sediments removed
       from wet detention ponds.  Studies to date
       indicate that pond sediments are likely to
       meet  toxicity limits  and  can be  safely
       landfilled (NVPDC,  1992).  Some states
       have allowed sediment disposal on-site, as
       long as the sediments are deposited away
       from the shoreline to prevent their re-entry
       into the pond.

DESIGN CRITERIA

In general,  pond designs are unique for each site
and application. Criteria for  selecting the site  for
installation of the pond should  include the site's
ability to support the pond environment, as well as
the cost effectiveness of locating a pond at that
specific site.  In addition, the pond should  be
located where the topography of the site allows for
maximum storage at minimum construction costs
(NVPDC, 1992). Site-specific constraints for pond
construction  may  include   wetlands  impacts,
existing utilities (e.g., electric or gas) that would be
costly to relocate, and underlying bedrock that
would require expensive  blasting operations to
excavate.

The site must have adequate base-flow from the
groundwater or from the drainage area to maintain
the permanent pool.  Typically, underlying soils
with permeabilities of between 10"5 and 10"6 cm/sec
will be adequate to maintain a permanent pool.

All local,  state and federal  permit requirements
should be  established prior to initiating the pond
design.  Depending on the location of the pond,
required permits and certifications  may include
wetland permits, water quality certifications, dam
safety permits, sediment and erosion control plans,
waterway permits, local grading permits, land use
approvals, etc.(Schueler, 1992).  Since many states
and  municipalities  are still  in the process  of
developing  or modifying  storm  water permit
requirements, the applicable requirements should be
confirmed   with  the  appropriate  regulatory
authorities.

Wet detention ponds should be designed to meet
both storm  water quality  and quantity control
requirements.  Storm water quantity requirements
are typically met by designing the pond to control
post-development  peak   discharge   rates   to
pre-development  levels.    Usually  the pond  is
designed to control multiple design storms (e.g. 2-
and/or 10-year storms) and safely pass the 100-year
storm event. However, the design storm may vary
depending on local conditions and requirements.

Storm water quality  control is achieved through
pollutant removal in the permanent pool.  Removal
efficiency is primarily dependent on the length of
time that runoff remains in  the  pond,  which is
known as the pond's Hydraulic Residence  Time
(HRT).  As discussed above, wet detention ponds
remove pollutants through both sedimentation and
biological uptake processes,  both of which increase
with the length of time runoff remains in the pond.
These processes can be modeled to determine a
design HRT using either the solids settling method
or  the  eutrophication  method,  respectively
(Hartigan, 1988).

The  calculated HRT will  be dependent on  the
method   selected.     HRTs  calculated by  the
eutrophication method can  be up to three  times
greater than HRTs calculated by the solids settling
method.  The longer HRTs  associated with  the
eutrophication method appear to be due  to  the
slower reaction rates associated with the biological
removal of dissolved  nutrients (Hartigan, 1988).

Once the design HRT has  been determined,  the
actual dimensions of the pond must be calculated to
achieve  the design  HRT.   The  primary factor
contributing to  a  pond's  HRT  is its volume.
Because many wet detention ponds are restricted in
area, pond depth can  be an important factor in the

-------
pond's overall volume. However, the depth of the
pool also affects many  of the  pond's removal
processes, and so it must be carefully controlled. It
is important to maintain a sufficient permanent pool
depth in  order to prevent  the  resuspension  of
trapped sediments (NVPDC, 1992).  Conversely,
thermal stratification and anoxic conditions in the
bottom  layer might  develop if  permanent pool
depths are too  great.  Stratification and  anoxic
conditions may  decrease  biological  activity.
Anoxic conditions may also increase the potential
for the  release  of phosphorus and heavy  metals
from the pond sediments  (NVPDC, 1992).  These
factors dictate that the permanent pool depth should
not exceed 6 meters (20 feet).  The optimal depth
ranges between 1 and 3 meters (3 and 9 feet) for
most  regions, given a 2 week  HRT (Hartigan,
1988).

Other key factors to be  considered in the pond
design are the volume and area ratios.  The volume
ratio,  VB/VR, is the ratio of the permanent pool
storage  (VB) to the mean storm runoff (VR).
Larger VBs and smaller VRs provide for increased
retention and treatment between storm events. Low
VB/VR ratios result in  poor  pollutant removal
efficiencies.

The area ratio, A/As, is the ratio of the contributing
drainage area (A) to the  permanent pool surface
area (As).  The area ratio is also an indicator  of
pollutant removal efficiency. Data from previous
studies indicates that area ratios  of less than 100
typically have better pollutant removal efficiencies
(MDDEQ, 1986).

The contours of the pond are also important.  The
pond should be constructed with adequate slopes
and lengths.   While a  length-to-width ratio  is
usually  not used in the design of wet detention
ponds for storm water quantity management, a 2:1
length-to-width ratio is commonly used when water
quality  is  of  concern.    In  general,  high
length-to-width  ratios (greater  than  2:1)  will
decrease the possibility of short-circuiting and will
enhance sedimentation within the permanent pool.
Baffles  or islands can also be added within the
permanent pool to increase the flow path (Hartigan,
1988). Shoreline slopes between 5:1 and 10:1 are
common and allow easy  access for maintenance,
such as mowing and sediment removal (Hartigan,
1988). In addition, wetland vegetation is difficultto
establish and maintain on slopes steeper than 10:1.
Ponds should be wedge-shaped so that flow enters
the pond and gradually spreads out. This minimizes
the potential for zones  with little  or no flow
(Urbonas, 1993).

The design of the wet pond embankment is another
key factor to be  considered.  Proper  design  and
construction of the embankments will prolong the
integrity of the pond structure.   Subsidence  and
settling will likely occur after an embankment is
constructed.  Therefore during construction,  the
embankment should be overfilled by  at least  5
percent (SEWRPC, 1991).  Seepage through the
embankment can also affect  the  stability of the
structure.  Seepage can generally be minimized by
adding  drains,  anti-seepage  collars,  and  core
trenches.  The embankment  side slopes can be
protected  from erosion by using minimum side
slopes of 2:1 and by covering the embankment with
vegetation or rip-rap. The embankment should also
have a minimum top width of 2 meters (6 feet) to
aid in maintenance.

Finally, the internal flow control of the pond must
be  considered.   Discharge  from  the pond is
controlled by a riser and an inverted release pipe.
Normal flows will be discharged through the  wet
pond  outlet,  which consists  of a  concrete  or
corrugated metal  riser and  barrel.  The riser  is a
vertical pipe or inlet structure that is attached to the
base with a  watertight connection.   Risers  are
typically placed in or adjacent to the embankment
rather than in the middle of the pond. This provides
easy access for maintenance and prevents the use of
the riser as a recreation spot (e.g.  diving platform
for kids)  (Schueler,  1988).    The  barrel is  a
horizontal pipe attached to the riser that conveys
flow under the embankment.

Typically, flow passes through an inverted  pipe
attached to the riser, as shown in Figure 1, while
higher flows will pass through  a trash rack installed
on the riser.  The inverted pipe should discharge
water from below the pond water surface to prevent
floatables  from  clogging the pipe and to avoid
discharging the warmer surface water. Clogging of
the pipe  could  result in overtopping  of  the

-------
embankment and  damage to the  embankment
(NVPDC, 1992).  Flow is conveyed through the
near horizontal barrel  and is  discharged to the
receiving stream.  Rip-rap, plunge pools, or other
energy dissipators, should be placed at the outlet to
prevent scouring and to minimize erosion. Rip-rap
also provides a secondary benefit of re-aeration of
the pond discharges.

Planners should consider both the design storm and
potential construction materials when designing and
constructing the riser  and  barrel.  Generally, the
riser and barrel are sized to meet the storm water
management design criteria (e.g. to pass a 2-year or
a 10-year storm event). In many installations, the
riser and barrel are designed  to convey  multiple
design storms (Urbonas, 1993).  To increase the life
of the outlet,  the riser  and barrel  should  be
constructed  of reinforced concrete rather than
corrugated metal pipe (Schueler, 1992). The riser,
barrel, and base should also provide have sufficient
weight to prevent flotation  (NVPDC, 1992).

In most  cases, emergency spillways  should  be
included in the pond design. Emergency spillways
should be sized to safely pass flows that exceed the
design storm flows. The spillway prevents pond
water levels from  overtopping the embankment,
which could  cause  structural damage  to the
embankment. The emergency spillway should be
located so that downstream buildings and structures
will not be negatively  impacted  by  spillway
discharges. The pond design should include a low
flow drain, as shown in Figure 1.  The drain pipe
should be designed for gravity discharge and should
be equipped  with an adjustable gate valve.

PERFORMANCE

The primary  pollutant removal mechanism in a wet
detention pond is sedimentation. Significant loads
of suspended pollutants, such as metals, nutrients,
sediments,  and organics,  can  be  removed  by
sedimentation.     Other  pollutant  removal
mechanisms include algal  uptake, wetland  plant
uptake, and  bacterial  decomposition  (Schueler,
1992). Dissolved pollutant removal also occurs as
a  result  of  biological  and  chemical processes
(NVPDC, 1992).
The removal rates of conventional wet detention
ponds  (i.e.,  without the sediment  forebay  or
peripheral ledges) are well documented and are
shown in Table 1.  The wide range in the removal
rates is a result of varying hydraulic residence times
(HRTs), which  is further discussed in the Design
Criteria  section.  Increased pollutant removal by
biological uptake and sedimentation is correlated
with  increased  HRTs.    Proper  design  and
maintenance also effect pond performance.

Studies have shown that more than 90 percent of the
pollutant  removal occurs during  the  quiescent
period (the period between the rainfall events) (MD
DEQ, 1986).   However, some removal  occurs
during the dynamic period (when the runoff enters
the pond).  Modeling results  have indicated that
two-thirds of the sediment, nutrients and trace metal
loads  are removed by sedimentation within 24
     TABLE 1 REMOVAL EFFICIENCIES
       FROM WET DETENTION PONDS
    Parameter
Percent Removal

Total
Suspended
Solid
Total
Phosphorus
Soluble
Nutrients
Lead
Zinc
Biochemical
Oxygen
Demand or
Chemical
Oxygen
Demand
Schueler,
1992
50-90

30-90

40-80

70-80
40-50
20-40



Hartigan,
1988
80-90



50-70







   1 hydraulic residence time varies
   2 hydraulic residence time of 2 weeks
   Source: Schueler, 1992 & MD DEQ, 1986.

-------
hours.   These projections are supported by the
results of the EPA's 1993 National Urban Runoff
Program (NURP) studies. However, other studies
indicate that an HRT of two weeks is required to
achieve significant phosphorus removal (MD DEQ,
1986).

The pond's treatment efficiency can be enhanced by
extending the detention time in the permanent pool
to up to 40 hours. This allows for a more gradual
release  of collected  runoff,  resulting  in  both
increased pollutant removal and control of peak
flows (Hartigan, 1988).

OPERATION AND MAINTENANCE

Wet detention  ponds function  more effectively
when they are regularly inspected and maintained.
Routine maintenance of the pond includes mowing
of the embankment and buffer areas and inspection
for erosion and nuisance problems (e.g. burrowing
animals,  weeds,  odors) (SEWRPC,  1991).  Trash
and debris should be removed routinely to maintain
an attractive appearance and to prevent the outlet
from becoming clogged. In general, wet detention
ponds should be inspected after every storm event.
The embankment and emergency spillway should
also be routinely inspected for structural integrity,
especially after major storm events.  Embankment
failure could result in severe downstream flooding.
When any problems are observed during routine
inspections,  necessary repairs  should be made
immediately. Failure to correct minor problems
may lead to  larger and more expensive repairs or
even to  pond failure.  Typically,  maintenance
includes  repairs to the embankment, emergency
spillway, inlet, and outlet; removal of sediment; and
control   of  algal  growth, insects,  and  odors
(SEWRPC, 1991).  Large vegetation or trees that
may weaken the embankment  should be removed.
Periodic  maintenance may  also   include  the
stabilization of the outfall area  (e.g. adding rip-rap)
to prevent erosive damage to the embankment and
the stream bank.  In most cases, sediments removed
from wet detention ponds are  suitable for landfill
disposal. However, where available, on-site use of
removed sediments for soil amendment will reduce
maintenance costs.
COSTS

Typical costs for wet detention ponds range from
$17.50-$35.00 per cubic meter ($0.50-$1.00 per
cubic foot) of storage area (CWP, 1998). The total
cost for a pond includes permitting, design and
construction,  and maintenance costs.  Permitting
costs may vary  depending on  state and  local
regulations. Typically, wet detention ponds are less
costly to construct in  undeveloped areas  than to
retrofit into developed areas. This is due to the cost
of land and the difficulty in finding suitable sites in
developed areas. The cost of relocating pre-existing
utilities or structures is also a major  concern in
developed areas.  Several studies have shown the
construction cost of retrofitting  a wet detention
pond into a developed area may be 5 to 10 times the
cost of constructing the same  size pond in an
undeveloped area.  Annual maintenance costs can
generally be  estimated at 3 to  5 percent of the
construction costs (Schueler, 1992).  Maintenance
costs include the costs for regular inspections of the
pond  embankments,  grass  mowing, nuisance
control, debris and liter removal, inlet and outlet
maintenance and inspection, and sediment removal
and  disposal.   Sediment removal  cost  can be
decreased by as much as 50 percent if an on-site
disposal areas are available (SEWRPC, 1991).

REFERENCES

1.      Center for Watershed Protection,  1998.
       Cost and Benefits of Storm Water BMPs.

2.      Hartigan, J.P.,  1988  "Basis for Design of
       Wet Detention  Basin BMPs," in Design of
       Urban Runoff Quality Control. American
       Society of Engineers. 1988.

3.      Maryland Department of the Environment,
       1986. Feasibility and Design of Wet Ponds
       to  Achieve   Water  Quality  Control.
       Sediment and Storm Water Administration.

4.      Northern   Virginia   Planning  District
       Commission,   Engineers  and  Surveyors
       Institute, 1992.  Northern  Virginia BMP
       Handbook.

-------
5.      Schueler, T.R., 1992. A Current Assessment
       of Urban  Best Management Practices.
       Metropolitan  Washington  Council  of
       Governments.

6.      Southeastern Wisconsin Regional Planning
       Commission,  1991.    Costs for  Urban
       Nonpoint Source Water Pollution Control
       Measures.  Technical Report No. 31.

7.      Urbonas, Ben  and Peter  Stahre,  1993.
       Storm Water Best Management Practices
       and Detention for Water Quality, Drainage
       and CSOManagement. PTR Prentice Hall,
       Englewood Cliffs, New Jersey.

ADDITIONAL INFORMATION

City of Charlotte, North Carolina
Steve Sands
Storm Water Services, Engineering and Property
Management
600 East 4th Street
Charlotte, NC 28202

Illinois EPA
Charles Fellman
Auxiliary Point Source Program, Permit Section,
Division of Water Pollution Control
1021 N. Grand Avenue East, P.O. Box 19276
Springfield, IL 62794

Minnehaha Creek Watershed District
Pete Cangialosi
Gray Freshwater Center, Navarre
2500 Shadywood Road, Suite 37
Excelsior, MN 55331
Southwest Florida Water Management District
Betty Rushton
2379 Broad Street
Brooksville, FL 34609

The mention of trade names or commercial products
does not constitute endorsement or recommendation
for the use by the U.S. Environmental Protection
Agency.
Polk County, Florida
Bob Kollinger
Natural Resources and Drainage Division
4177 Ben Durrance Road
Bartow, FL 33830

City of Reynoldsburg, Ohio
Larry Ward
Storm Water Utility
7806 East Main Street
Reynoldsburg, OH 43068
           For more information contact:

           Municipal Technology Branch
           U.S. EPA
           Mail Code 4204
           401 M St., S.W.
           Washington, D.C., 20460


           I
           Excellence in compliance through optimal technical solutions
           MUNICIPAL TECHNOLOGY BR/TfTfff
MTB

-------