United States     November
      Environmental Protection 1984
      Agency
SEPA An
      Emerging
      Technology
      Vacuum-
      Assisted
      Sludge
      Dewatering
      Beds
      An Alternative
      Approach

-------
Vacuum-Assisted  Sli
Introduction
Nearly all wastewater treatment facilities require a
means of handling and disposing of sludges
generated by the treatment processes. Often, the
sludge handling process involves the dewatering of
the liquid sludge to reduce the sludge volume and
produce a relatively dry sludge cake for additional
treatment or less costly treatment and disposal.
Due to the relative simplicity of operation, sand
drying beds have been widely utilized for sludge
dewatering at many small and medium  sized
treatment plants. Larger treatment plants often
utilize mechanical sludge dewatering systems
because the land area required for sand beds is
excessive.
Vacuum-assisted sludge dewatering beds (VASDB)
combine several features of both sand drying beds
and mechanical dewatering systems. Potential
advantages of VASDB in comparison to sand
drying beds include:
• Reduced area needs
• Greater operational control

Advantages over mechanical dewatering systems
include:
• Lower costs
• Ease  of operation

Due to their potential advantages, vacuum-assisted
sludge dewatering beds should  be considered by
communities and their consultants when sludge
dewatering is proposed.

 Description and Operation
Vacuum-assisted sludge dewatering beds closely
 resemble sand drying beds in .appearance. A cross
 section of a typical VASDB is shown in Figure 1.
          Polymer
          System
                             Rigid Porous
                             Media Plates.
                            -Intermediate
                             Support/Drainage Layer
                             (Gravel)       .;•-:•
                    • To Treatment PJant        :
 Figure 1. Typical Section of Vacuum-Assisted
         Sludge Dewatering  Bed

-------
  .CO
                3 _  4' .5
                Time (hours)
                                 58 -"24
 Figure 2.Dewatering Curve (Aerobically Digested
         Sludge)
 A list of typical facilities using vacuum-assisted
 sludge drying beds is presented in Table 2.
Location *
Sunrise City, -FL •• *
Portage, IN
Clarksvffle, IN " ,
. Casey, IL" • ' • '
Lumberton, NC
Sheridan, WY
Grand Junction, CQ
Geneva, IL • •
Woodbridge, IL
, Taylors, SC' - • •
Hilton Mead, SC
Union' City, IN
Pjttsffsld, Ik ' '
Sullivan, "IL ,
Plant Size'
4.5 mgd ' '"
3.5 mgd
0.9 mgd >
* * 1:0 mgd
- 10,0 mgd
4"A mgd
12.5 mgd - -
, 4,0 mgd
4.0 mgd
" 7.5 mgd
' .'i,:2mgd
1.5 'mgd;
', t.efngd ,
0,5 mgd
Number
'of Beds
2,"
. 6
2
2' "
2
• • 8
16

• 4
. 2 "
', 1"
2"
4 ,
3 -
Table 2.Typical Vacuum-Assisted Sludge prying
        Bed Installations

Design Considerations
Evaluation of the use of vacuum-assisted
dewatering beds must consider potential limitations
as well as benefits. The following conditions may
limit the applicability of the VASDB process:

• Treatment of highly viscous sludges
• Treatment of sludges which have a high
  concentration of fine solids and/or grease

-------
• Large treatment facilities where a continuous
  sludge flow system may be more appropriate

• Facilities requiring a consistently very dry sludge
  cake (dry solids above 20 percent)

Experience with raw sludge applications to VASDB
is limited and the use of VASDB with raw sludges
should be carefully evaluated. In most cases,
digestion of the sludges prior to application to the
drying beds is practiced. Also, providing a  means of
periodically cleaning the beds to prevent possible
problems due to the presence of greases in the
sludge should be considered. Beds are cleaned
after every use and at most VASDB installations,
chemical agents are used to wash the surface on a
regular  basis.

Costs
The construction costs for vacuum-assisted sludge
dewatering beds indicate that this system offers the
potential for significant cost savings compared to
other dewatering systems. In Table 3, the  actual
construction costs for VASDB systems are
compared  to estimated costs for conventional open
sand  drying beds, a rotary vacuum filter, and a belt
filter press system for wastewater flows of 1  and 5
million gallons per day. The comparison assumes
approximately 2,000 pounds of  aerobically digested
primary and secondary dry solids per million gallons
of wastewater flow and return of the filtrate to the
plant influent. The actual cost of a VASDB system
is dependent  upon site-specific  treatment
conditions. The major factors which influence the
cost are sludge volume, dewatering time required,
and the sludge loading rate.
                                 Design Flow
   System                      1 MGD      5 MGD
   Vacuum Assisted Dewatering Beds   $158,0001  $1,068,0001
  Open Sand Beds                $330,8002  $2,632,SQ&
  Rotary Vacuum Filters      .      $382tSXf  $4,252,5002
  Belt Filter Press                 STO.SOO2  $2,463,8002 .
   'Derived from actual 1984 construction cost data.             .
  tlerived from EPA Dewaterfng Municipal Waslewater S/urfges • Design    :
     Manual 1S82 (EPA 625/1-82-014). Adjusted to 1934 dollars
 Table 3. Construction Cost Comparison
         (1984 Dollars)

-------
^n  Alternative  Approach
    <~j -\:  Objective

   f     Loading Hates


          "  Bed Size

       Number of Beds


    Chemical Conditioning


       Total Cycle Time


    Percent Solids in Cake


         Cake Removal

      Major Components
              Extract e>tcess*afef from waste sludge   '   :.

              Vanes -075 to. 15 pounds of dry solids per
              squats foot per day typical,  ,

              20 x 40 foot units standard

              Minimum of 2 recommended. Total number
              based upon .daily sludge volumes and loading
              rales

              Polymer adiMm to improve dewatenng normally
              practiced

              Varies from $ to 48 hours 24 to 48 hours typical
              for digested sludges

              Vanes with type at sludge, cycle iirns, and
              loading rate Normal range is 10 to 20 percent

              Manual, rubber tiVed. loader or vacuum trucK

              « ftigfd poroXiS media plates
              • Grave' support drainage medta
              » Concrete containment basiii,
              * Vacutiro pumps      '  *
              »Filtrate pumps    *            - ,
              » Potyrrser system,
              # Concrete or steel sump

Climatic ProieetlQR Covered beds reromnierded' for northern and or
              wei climates        ,  "
              Filtrate

         ScUds Capture
              Returned to irealment facility.

              > 99 percent
  Table 1. Design Features of Vacuum-Assisted
          Sludge Dewatering Beds


  open sand drying beds with chemical addition. This
  indicates the area required for drying beds could be
  reduced by as much as 90 percent when  utilizing
  VASDB in place of open sand drying beds.

  The'performance of vacuum-assisted sludge drying
  beds is influenced by the following factors:

  • Solid and liquid loading rates
  • Chemical pre-conditioning of solids
  « Cycle time
  • Vacuum application characteristics

  Data from several different treatment plants  indicate
  dry solids concentrations in the dewatered sludge
  cake ranging from 8 percent to as high as 23
  percent with cycle times of 8 to 48 hours.  Typically,
  the process produces an acceptable sludge cake
  within 24 hours with  a reduction of 80 to 90 percent
  in the initial sludge volume. A typical dewatering
  curve for an aerobically digested sludge js shown in
  Figure 2. Analysis of the drying bed filtrate indicates
  a solids capture rate of greater than 98 percent.

-------
Annual operation and maintenance costs for
vacuum-assisted dewatering beds also exhibit a
potential for cost savings over some of the other
dewatering systems, particularly for smaller plants.
Table 4 compares the estimated annual O&M costs
for VASDB, open sand drying  bed, rotary vacuum
filter, and belt filter press systems. As Table 4
illustrates, the annual O&M costs for mechanical
dewatering systems, as represented by the rotary
vacuum filter and belt filter press system, may
become less than the comparable costs for a
VASDB system at 5 MGD and higher flow rates
and sludge volumes. This is primarily due to a
significant reduction in the labor requirements per
unit volume of sludge dewatered for mechanical
systems as total sludge volume increases.
   System
   Vacuum Assisted Dewatering Beds
   Open Sand Beds
   Rotary Vacuum Filters
   Belt Filter Press
                                Design Flow
1 MGD
$25,700' :
$1 2,500s
                             $43,7002
 5 MGD
$173,300*
$131,100*
$182,40CF:
  'Estimated tor actual 1984 projects
  "Derived from EPA Dewatering Municipal WastswaSer Sludges - Design •
     Manual 
-------
Ige Dewatering   Beds  -
  Sludge from the treatment processes is uniformly
  applied to the bed to a depth of approximately 12
  to 18 inches. During the sludge application, a
  polymer is normally added to improve the sludge
  dewatering characteristics. A gravity dewatering
  phase, during which much of the free water may be
  removed from the sludge, continues until the sludge
  forms a relatively dense mat over the media plates.
  At this point, the vacuum pump is started to create
  a vacuum in the sump and under the media plates.
  The vacuum draws additional water out of the
  thickened sludge mat and continues until the sludge
  mat begins to crack. Normally, the mat begins to
  crack after 80 percent or more of the free water is
  removed. After the sludge mat cracks, air drying of
  the sludge continues until the dewatered sludge
  cake achieves the desired dryness. The sludge
  cake is then removed from the bed for further
  treatment or disposal. Filtrate from the dewatering
  process is normally returned to the treatment facility
  by a float-actuated submersible pump located in the
  filtrate sump.

  The rigid porous media plates form  an abrasion
  resistant, load bearing surface which permits the
  sludge cake to be easily removed manually or by a
  rubber'tired loader. The plates also  eliminate the
  need for periodic replacement of the filtering media
  common with sand drying beds.

  The total cycle time for dewatering of the sludge
  depends upon many factors, including the sludge
  dewatering characteristics, degree of sludge cake
  dryness desired, and climatic conditions. Normal
  total cycle times vary from 8 to 48 hours, with 24 to
  48 hours representing typical total cycle times for
  digested sludges. In comparison, drying times for
  sand drying beds normally range from 1 to 2
  weeks. Due to the reduced drying time and the
  assistance provided by the vacuum system,
  VASDB are generally less affected by inclement
 weather than are sand drying beds.

 Design and Performance
 As noted in Table 1, vacuum-assisted sludge
 dewatering beds are typically designed for a dry
 solids loading rate of 0.75 to 1.5 pounds  per square
 foot per day, which is equivalent to an annual
 loading of about 275 to 550 pounds  per square
 foot. This compares with typical annual design
 loading rates of 40 to 60 pounds per square foot fw

-------
Mention of trade names or commercial products
does not constitute endorsement.

Prepared by Environmental Resources Management, Inc.
For additional Information contact:
EPA-OWPO(WH-595)
401 M Street, SW
Washington, DC 20460
(202)382-7370/7369

EPA Region 1
John F. Kennedy Federal Building
Boston, MA 02203

EPA Region 2
26 Federal Plaza
New York, NY 10278

EPA Region 3
6th & Walnut Streets
Philadelphia, PA 19106

EPA Region 4
345 Courtland Street, NE
Atlanta, GA 30365

EPA Region 5
230 South Dearborn Street
Chicago, IL 60604
EPA-MERL (489)
26 West St. Clair Street
Cincinnati, OH 45268
(513)684-7611

EPA Region 6
1201 Elm Street
Dallas, TX 75270

EPA Region 7
324 East 11th Street
Kansas City, MO 64106

EPA Region 8
1860 Lincoln Street
Denver, CO 80295

EPA Region 9
215 Fremont Street
San Francisco, CA 94105

EPA Region 10
1200 6th Avenue
Seattle, WA 98101

-------