United States
Environmental Protection
Agency
                    September
                    1984
oEPA   Value
         Engineering
         For
         Wastewater
         Treatment
         Works

-------
Value Engineering  For Waste
Introduction
Value engineering (VE) is a specialized cost control
technique applied by an independent team of
experienced multidisciplined professionals during the
design of wastewater treatment works. VE provides a
systematic, functional and creative study of a proposed
wastewater treatment facility to identify life cycle cost
savings without sacrificing performance or reliability.

From 1977 to 1983, the EPA's value engineering
program produced a $15 return on each dollar invested
in VE studies and a 5.4% net capital savings on $7.5
billion worth of total construction costs. The VE
program also produced additional benefits of operation
and maintenance cost savings and enhanced reliability.
These benefits were achieved with VE study costs of
less than 0.4  percent of the total  construction costs.

While VE studies are required on all proposed
wastewater treatment works with estimated construction
costs greater than 10 million dollars, EPA encourages
the use of VE on projects of less than $10 million since
they offer similar potentials for cost savings.

Strategy For a Value Engineering  Study
The VE study is divided into four sequential periods of
activity:
  (1) administrative (contracting)  activity,
  (2) pre-workshop activity,
  (3) VE workshop, and
  (4) post-workshop activity.

Figure 1 is a VE study task flow  diagram outlining
these activities. The VE workshop is the major
component of the VE study.

The scope of the VE effort will depend on the size,
cost, and complexity of the facility. Most wastewater
treatment projects with costs  over $10 million require
two studies to obtain maximum VE benefits (See
Figure 2). The first VE workshop occurs when the

-------
water Treatment Works
    project design is 20 to 30% complete and the second
    workshop occurs at 65 to 75% of design completion.
    One VE study is usually sufficient for small
    non-complex facilities. A single VE workshop should be
    performed at 20 to 30 percent of design completion.
Administrative (Contracting) Activity

Dealgner'a Services
Designer/Owner Contract to
Support VE Study
VE Included in Design
Schedule


Pre-Workshop Preparation
Coordination Meeting
Schedule
Outline Format tor Cost Data
Develop Format lor Designer
Presentation
Outline Needed Background
Data
Outline Project
Responsibilities
VE Workshop
Orientation
Introduction
Project Description and
Presentation
Outline Project Requirements



Post-Workshop Activity
Final VE Report
Review VE Report
Prepare Final VE Report
Implement Accepted
Recommendations



RFP
Owner Supplies Facility
Owner Defines Schedule,
Scope, Number of VE
Studies, and Evaluation
Criteria

Preparation
Collect Design Data
Confirm Team Composition
Distribute to Team Members
Assemble Cost Data
Familiarization with Data by
Team Members
Select Location for Workshop

Information Phaae
Analyze Project Costs
Analyze Energy Usage
Function Analysis
Identify High Cost Areas
Identify High Energy Areas
Develop Cost/Worth Ratios

List Ideas Generated During
Function Analysis

Final Acceptance
Owner/Agency Interface
Agency Acceptance
of Final VE Report

^^


VE Consultant'! Proposal
Defines Approach, VE
Composition, and Level of
Effort

Construct Co«t Model*
Distribute Costs by Process __
Areas or Major Component,
or Both
Identify High Cost Areas

Develop Energy Model
Distribute Costs by Process
or Both
Identify High Cost Energy
Areas

Speculative/
Creative Phaee

• Quantity of Ideas
• Association of Ideas

Brainstorming
Individual Creative Ideas

1 Use Checklist tor Ideas L

    Figure 1. VE Study Task Flow Diagram

-------
The VE team members should be experienced design,
operation and construction professionals familiar with
the principles of value engineering. The composition of
each VE team should reflect the complexities of the
specific project. At least two members of each VE team

-------
should be experienced in the major high cost areas OT
the project. The VE Team Coordinator (VETC) plays a
key role in the success of the VE study. This individual
manages all aspects of the study.

Pre-Workshop Activity
Prior to the workshop the owner, designer, and VETC
meet to confirm the VE study schedule and form a
consensus on the study objectives. During this stage,
the VETC accumulates the technical and cost data on
the project. The technical data consist of feasibility and
engineering reports, pertinent regulations,  discharge
permits, plus all current design drawings and
specifications. The cost data consist of cost estimates
for the equipment, construction, operation  and
maintenance of the wastewater treatment  works. This
information is used to develop cost, energy and life
cycle models which aid the VE team in the rapid
analysis and identification of high cost areas or
components of the facility during the workshop.

The VE Workshop
The VE workshop is accomplished through a Job Plan
with five distinct phases:
(1) Information  Phase: The VE team gains as much
    information as possible on the  project  design,
    background, constraints and projected costs. The
    team performs a function anyalysis of  the project to
    identify high cost areas.
(2) Speculative/Creative  Phase:  The VE team uses a
    group  interaction process to  identify alternative
    ideas for accomplishing the function of a system or
    subsystem.
(3) Evaluation/Analytical  Phase:  Alternative ideas are
    screened and evaluated by the team. The ideas
    showing the greatest potential for cost savings and
    project improvement are selected for further study.
(4) Development/Recommendation Phase: The team
    researches the selected ideas and prepares
    descriptions, sketches, and life cycle cost estimates
    for the VE recommendations.

-------
(5) Report Phase: VE recommendations are orally
    presented to the owner and designer at the
    conclusion of the workshop. A written VE Report is
    prepared within one to three weeks after
    completion of the workshop.

Post-Workshop Activity
The owner and designer thoroughly review and
evaluate each VE recommendation. A Final VE Report
is prepared to summarize the VE study. This report
describes the action taken on each of the VE
recommendations. Total or partial rejection  of any VE
recommendation must be supported by valid reasons
which are specifically detailed in the report. The Final
VE Report and the VE Report serve as complete
documentation of the VE study.
                                  Conclusion
                                  Value engineering provides communities with an
                                  excellent opportunity to reduce the present and future
                                  costs of their wastewater treatment facilities. The
                                  positive application of VE to individual wastewater
                                  treatment projects can typically result in 5% to 10% net
                                  capital cost savings plus additional operation and
                                  maintenance cost savings.
   Administrative (Contracting)
          Activity
           I
    First VE Study at 20-30%
      Design Completion
Pre-Workshop Activity
                             Finalize VE Team
                               Composition
   Second VE Study at 65-75%
      Design Completion
Pre-Workshop Activity
                             Finalize VE Team
                               Composition
                                                                   Final VE Report Second
                                                                        Workshop
                                                                                           Designer Implement Accepted
                                                                                              VE Recommendations
                                                               Designer Implement Accepted
                                                                  VE Recommendations
Figure 2. VE Row Diagram: Normal Sequence (Two VE Studies)

-------
Reference:  U.S.  E.P.A. "Value Engineering For Wastewater
               Treatment  Works" 1984.
For additional information contact:
EPA-OWPO(WH-547)                     EPA-MERL (489)
401 M Street, SW                        26 West St. Clair Street
Washington, DC 20460                    Cincinnati, OH 45268
(202)382-7370/7369                       (513)684-7611

EPA Region 1                           EPA Region 6
John F. Kennedy Federal Building            1201 Elm Street
Boston, MA 02203                        Dallas, TX 75270

EPA Region 2                           EPA Region 7
26 Federal Plaza                         324 East 11th  Street
New York, NY 10278                      Kansas City, MO 64106

EPA Region 3                           EPA Region 8
6th & Walnut Streets                      1860 Lincoln Street
Philadelphia, PA 19106                    Denver, CO 80295

EPA Region 4                           EPA Region 9
345 CourHand Street, NE                   215 Fremont Street
Atlanta, GA 30365                        San Francisco, CA 94105

EPA Region 5                           EPA Region 10
230 Soutti Dearborn Street                  1200 6th Avenue
Chicago, II60604                        Seattle, WA 98101

-------