EPA-8 VI -F-8 9-100
                     United States
                     Environmental Protection
                     Agency
                        Office of Water           Publication U-1
                        Nonpoint Source Branch    August 1989
                        (WH 585)
&EPA
Retrofitting Storimwater
Management Basins for
Phosphorus Control
    The Problem
            n the early 1970s, nuisance blue-green
            algae blooms and low dissolved oxygen
            problems began to plague the Loch
            Raven Reservoir, a 21 billion gallon
            impoundment near Baltimore, Maryland.
            The cause was an overload of
            phosphorus generated by
            agricultural activities and
            urbanization.
      Baltimore County had several
    phosphorus control programs, but of limited
    effectiveness. In urban areas, the programs
    focused mainly on retaining stormwater,
    primarily through some 36 "dry" ponds that
    become inundated only during very large
    storms. Because the hydraulic controls were
    designed to accommodate only large flows,
    most storm flows and the sediments they
    carried passed through the basin unimpeded
    by a low-flow pipe. Thus, the basins did little
    to enhance water quality — and,
    consequently, the reservoir suffered.
      To combat this problem, the Water
    Quality Management Office of the Baltimore
    City Department of Public Works started a
    program, funded in part by a Clean Lakes
                       Program grant, to modify these stormwater
                       structures. The goal: change the structures so that
                       they could d etain flows from small storms without
                       compromising their ability to control larger storm
                       flows.
                Baltimore County
                                              Prettyboy Reservoir
                                                     Loch
                                                     Raven
                                                     Reservoir

-------
 Project Design and Construction
            efore modification, the 36 structures
            were able to control the flows from
            storms that occurred every two years,
            10 years, and 100 years. But since
            most storm events were less intense
            than even the two-year variety,
            engineers and planners needed to
 adjust the structures to accommodate the smaller
 storms.
    To modify the structures, engineers took a
 two-pronged design approach. First, they needed to
 needed to know how small the basins could be
 without restricting their capacity to control the
 runoff from larger storms. Through computer
 modelling, it was determined that the basins could
 be modified to accommodate one-year storms, and
 that even smaller storms would not be
 short-circuited.
   Second, the engineers needed to design the
actual retrofits, which would vary the size of the low
flow release structure to handle smaller storms. This
was accomplished by designing a special
attachment and installing a trash debris guard.
   So far, five retrofits have been built. The first,
Dulaney Gate, was installed during the summer of
1984; the most recent, Huntridge, was completed in
March 1988.
   Each retrofit was tailored to individual outlet and
site conditions. Three of the retrofits were dry ponds
and installation took less than three days.
Retrofitting the wet pond was more complicated and
expensive because the pond had to  be pumped and
the bottom dredged because the low flow release
was covered by sediment.
   A schematic of a detention basin that has been
retrofitted appears on the last page.
Retrofit Diagram

-------
Costs
           he cost of the retrofits ranged from
           $2,000 to $13,000 per basin. The dry
           ponds cost approximately $2,000 and
           the wet pond $13,000. The added cost
           of dredging bottom sediment and
pumping the standing water accounts for the higher
cost associated with the wet basin. In addition to the
costs, it took an average of one day to install the dry
basin and one week for the wet basin.
                                                 Maintenance and Liability
           ny modification made to an existing
           pond could increase liability and
           maintenance. The county government
           agreed to work with private basin
           owners and, if necessary, relieve them
           of these responsibilities. Because of
legal and political issues, the county could guarantee
maintenance for the retrofit only on ponds already
owned by the county, thus limiting the available
coverage of this effort.
Water Quality Monitoring and Results
           reliminary results indicate the retrofits
           remove over 90 percent of all
           paniculate material and between 30
           and 40 percent of the total phosphorus.
           These high removal efficiencies were
           fairly consistent for all storms. All of the
storms successfully monitored had less than a
one-year recurrence interval and detention times
ranged from 3 to 5 hours.
   Not one of the retrofits has clogged,
demonstrating the effectiveness of the trash-debris
guards. Sediment in-filling of the basins does not
appear to be appreciable despite their estimated
high trap efficiency. This is most I ikely due to the fact
that all of the retrofits drain stabilized urban areas
that characteristically have low sediment export
rates. Sediment in-filling is expected to be a concern
in areas with construction activity.
                                        Retrofit Design Criteria

                                               Retrofit
            Detention Times (hours)
            112 year         1 year
Drainage Area
   (acre)
             DulaneyGate
             Oakhampton
             Mays Chapel
             Loveton
             Huntridge

-------
                               ..^sSSOS^^   L°""sta<">
                                                            Extended
                                                            Detention
                                                            Control
                                                            Device
                                  10 Year Water Surface Elevation

                                  2 Year
          Illustration from Controlling Urban Runoff: a Practical Manual for Planning and Designing Urban BMPs,
                   by Thomas R. Schueler, Department of Environmental Programs, Washington
                           Metropolitan Council of Governments; published July 1987.
If you have any questions concerning this project, please contact Randall G. Waite, Clean
Water Coordinator, Region HI, Philadelphia, PA, (215/597-3425) or William P. Stack, Tech-
nical Manager, Baltimore City Water Office, Baltimore, MD (301/396-0732).
                                          Printed on Recycled Paper

-------